ProjectId,Category,Current Status,Department,Div,Estimate Amount (Lakhs),Project Name,Source of Fund,Zone,YearProposed,YearComplete 3/2008-2009,Bridges,Completed,J-Bridges,22,51617841,Spill Over Work Construction of ROB at Kathivakkam High Road,JNNURM,3,2008-09,2016-17 16/D/2009-10,Storm Water Drain,Completed,D-Storm Water Drains,1,676800000,"Spill Over Work Providing Re Sectioning and concrete Lining to Captain Cotton Canal, Link Canal, Kodungaiyur Canal, Vyasapadi Canal and Jawahar Canal including fencing and other imporvement workes in Captain cotton canal wather shed in Chennai city. Zone I, III IV.",JNNURM,1,2009-10,2017-18 17/D/2009-10,Storm Water Drain,Completed,D-Storm Water Drains,1,205930000,"Spill Over Work Construction of Storm water Drain work in North Buckingham Canal Water Shed in Chennai city. Zone I, Zone II Zone III.",JNNURM,1,2009-10,2016-17 26/D/2009-10,Storm Water Drain,Completed,D-Storm Water Drains,3,144900000,Spill Over Work Providing and Re Sectioning and concrete lining to Eggangipuram canal TVS Canal including fencing and other improvement work in Otteri Nullah Water Shed in Chennai City.,JNNURM,1,2009-10,2016-17 24/D/2009-10,Storm Water Drain,Completed,D-Storm Water Drains,4,893300000,Spill Over Work Construction of Storm Water Drain work in Otteri Nullah Water Shed in Chennai City.,JNNURM,1,2009-10,2016-17 31/D/2009-10,Storm Water Drain,Completed,D-Storm Water Drains,9,226300000,"Spill Over Work Providing and Re Sectioning and concrete lining to Chellammal canal, Jafferkhanpet Canal, MGR Canal Guindy Industrial Estate canal including fencing and other improvement work in Adyar Water Shed in Chennai City.",JNNURM,1,2009-10,2016-17 22/D/2009-10,Storm Water Drain,Completed,D-Storm Water Drains,32,823620000,"Spill Over Work Construction of Storm Water Drain work in Coovum River water Shed in Chennai City. Zone III,V,VI VII.",JNNURM,3,2009-10,2018-19 20/J/2009-10,Bridges,Completed,J-Bridges,119,39300001,Spill Over Work Repairs and retrofitting work to Kodambakkam Over bridge,Own Sources,9,2009-10,2018-19 L/2010-11/7257,Electrical,Completed,L-Electrical,30,1981800,REMOVAL OF RUSTED POST AND ERECTION OF NEW POST,Own Sources,3,2010-11,2017-18 L/2011-12/6666,Electrical,Completed,L-Electrical,64,2707500,"Removel of 48 nos of existing post from plotform and 32 nos lamp post from centre medium and provision of 50 nos of 8mtr lamp post with arch bracket with 250w mhl fitting along the inner ring road on the western side from CPWD quarters to school road jn in Division 64,zone V due to the implemention of GRADE SEPARATOR Poject.",Deposit Works,6,2011-12,2016-17 L/2011-12/6670,Electrical,Completed,L-Electrical,99,623000,"Removal of existing lamp post with double stright bracket with 250w s.v fitting at 2nd avenue from 12 th main road juction to 13 main road juction in Div -64,zone-V",Deposit Works,8,2011-12,2017-18 L/2011-12/6669,Electrical,Completed,L-Electrical,100,863700,"Removal of Existing Post and Provision of New 14 Nos. of 8 Mtr Post with Double Straight Bracket at IInd Avenue for Metro Rail Project of Anna Nagar Tower in Div.100,Zone VIII",Deposit Works,8,2011-12,2017-18 L/2011-12/6668,Electrical,Completed,L-Electrical,101,1608000,"Removal of Existing Post and Provision of 23 Nos. of 8Mtr Lamp Post with Double Straight Bracket with 250w SVL and 2 Nos. of 8 Mtr Post with Triple Straight Bracket with 250 w SVL at IInd Avenue(Roundtana to Chinthamani) in Div.67,for Metro Rail Station,Annanagar East,Zone V",Deposit Works,8,2011-12,2016-17 L/2011-12/6664,Electrical,Completed,L-Electrical,102,1094900,"Removal of existing post and provision of 17nos of 8mtr lamp post with single straight arch bracket with 250W SVL fitting at Pulla Avenue in div 68. for metro rail station , Thiru. Vi.Ka Park Zone V",Deposit Works,8,2011-12,2019-20 L/2011-12/6678,Electrical,Completed,L-Electrical,102,470500,removel of existing post and provision of 6nos of 8mtr lamp post with arch bracket and 250W SVL fitting at EVR Salai,Deposit Works,8,2011-12,2019-20 L/2011-12/6681,Electrical,Completed,L-Electrical,103,483200,"Removal of existing lamp post and provision of 7nos of 8mtr lamp post with arch bracket and 250W SVL fitting at EVR Salai Div-70, for Kilpuk Metro Rail Station Project.",Deposit Works,8,2011-12,2019-20 L/2011-12/6680,Electrical,Completed,L-Electrical,104,539800,Removal of existing lamp post and provision of 8nos of 8mtr lamp post with arch bracket and 250W SVL fitting at EVR Salai Div 70& 71 for Nehru Park Metro Rail project.,Deposit Works,8,2011-12,2019-20 L/2011-12/5237,Electrical,Completed,L-Electrical,116,4553400,Provision of new post,Deposit Works,9,2011-12,2018-19 L/2011-12/5243,Electrical,Completed,L-Electrical,116,3634300,Provision of new post,Deposit Works,9,2011-12,2018-19 L/2012-13/10719,Electrical,Completed,L-Electrical,5,1787500,"Provision of 30 Nos. of 8 Mtr G.I Lamp Post with double arch bracket with 250WS.V Fitting at Thiruvottiyur High Road from wimco Market to Ernavoor Bridge in Dn:5, Zone I",Own Sources,1,2012-13,2017-18 NA/2012-13/27185,Roads,Completed,NA-THIRUVOTTIYUR,9,650000,"Forming,Strengthening and Re Laying the BT Road with Paver Finisher at Soma Sundaram Nagar 1st Street in Dn 9,Unit 3,Zone 1.",Own Sources,1,2012-13,2016-17 B/2012-13/27857,Buildings,Completed,B-Buildings,11,40000000,"CONSTRUCTION OF 24X7 ZONAL EOC IN MEDICAL OFFICE BUILDING (AFTER DISMANTLING OLD DISPENSARY AND HOSPITAL FOR WOMAN) AT THIRUVOTRIYUR HIGH ROAD IN DN-11, ZONE-1",Grants,1,2012-13,2020-21 B/2012-13/9503,Buildings,Completed,B-Buildings,41,9250000,"CONSTRUCTION OF COMMUNITY CENTRE AT VOC NAGAR 1 STREET ,PULIANTHOPE IN DN 72 ZONE 6",MLACDS,4,2012-13,2016-17 E/2012-13/15587,Electrical,Completed,E-Education,42,778000,"ELECTRIFICATION WORK AT CHENNAI HIGHER SECONDARY SCHOOL AT NO.540, T.H.ROAD IN DN;42, ZONE IV.",Own Sources,4,2012-13,2016-17 BR/2012-13/12424,Footpath,Completed,BR-Bus Route Roads,61,4443000,"Forming Footpath using Granite kerb and slab at Pantheon road Reach 1 (from Gandhi Irwin bridge road to Aadhithanar salai) in ward 61, Zone 5.",Grants,5,2012-13,2016-17 BR/2012-13/12427,Footpath,Completed,BR-Bus Route Roads,61,8932000,"Forming Granite footpath at Pantheon road reach 2 (From Police commissioner office road to Ethiraj salai ) in ward 61, Zone 5.",Grants,5,2012-13,2016-17 BR/2012-13/12429,Footpath,Completed,BR-Bus Route Roads,61,6233000,"Forming Granite footpath at Ethiraj salai (From Pantheon road to Binny road) in ward 61 , Zone 5.",Grants,5,2012-13,2016-17 BR/2012-13/12431,Footpath,Completed,BR-Bus Route Roads,61,2394000,"Forming Granite footpath at Whannels road (Pantheon road to Gandhi irwin road ) in ward 61, Zone 5.",Grants,5,2012-13,2016-17 BR/2012-13/12798,Footpath,Completed,BR-Bus Route Roads,61,8233000,"Forming Granite Foot path at Gandhi Irwin Road (from Dr.T.M.Nair Bridge to the Gandhi Irwin Bridge Road ) in ward 61,Zone 5.",Grants,5,2012-13,2016-17 BR/2012-13/12806,Footpath,Completed,BR-Bus Route Roads,61,6154000,"Forming Granite Foot path at Halls Road (from Dr.T.M.Nair Bridge to the Casa Major Road ) in ward 61,Zone 5.",Grants,5,2012-13,2016-17 BR/2012-13/12809,Footpath,Completed,BR-Bus Route Roads,61,5064000,"Forming Granite Foot path at Casa Major Road (from East Mayor Ramanathan Salai to the jn.of Pantheon Road ) in ward 61,Zone 5.",Grants,5,2012-13,2016-17 BR/2012-13/12103,Footpath,Completed,BR-Bus Route Roads,63,1801000,"Forming Granite footpath at Blackers road (from jn. of Anna salai to Dams road ) in ward 63, Zone 5.",Grants,5,2012-13,2016-17 NE/2012-13/18047,Parks,Completed,NE-ROYAPURAM,63,457000,"ANNUAL MAINTENANCE OF L.G.ROAD PARK at ATHITHANAR SALAI PARK IN DN 63,U 14,Z 5. FOR TWO YEARS MAINTENANCE QUALIFIED HORTICULTURIST",Own Sources,5,2012-13,2016-17 NE/2012-13/18061,Parks,Completed,NE-ROYAPURAM,63,510000,"ANNUAL MAINTENANCE OF DAMS ROAD PARK at RAHIJA COMPLEX PARK (OSR LAND) PARK IN DN 63,U 14,Z 5. FOR TWO YEARS MAINTENANCE QUALIFIED HORTICULTURIST",Own Sources,5,2012-13,2016-17 NF/2012-13/23970,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2258000,LAYING CEMENT CONCRETE ROAD WITH M40 GRADE RMC AT GURUMOORTHY GARDEN STREET IN DN 70 UNIT 16 Z 6,Own Sources,6,2012-13,2016-17 NF/2012-13/24001,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,828000,LAYING CEMENT CONCRETE ROAD WITH M40 GRADE RMC AT THIRUVENKADAM STREET IN DN. 70 U 16 Z VI,Own Sources,6,2012-13,2016-17 NF/2012-13/24002,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1561000,LAYING CEMENT CONCRETE ROAD WITH M40 GRADE RMC AT ANANTHAVELU 1ST CROSS STREET IN DN. 70 U 16 Z VI,Own Sources,6,2012-13,2016-17 NF/2012-13/24005,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1775000,LAYING CEMENT CONCRETE ROAD WITH M40 GRADE RMC AT PUZAL SIVAGANAM STREET IN DN. 70 U 16 Z VI,Own Sources,6,2012-13,2016-17 NH/2012-13/0967,Footpath,Completed,NH-ANNA NAGAR,96,754000,REPAIRS AND IMPROVMENT TO EXISTING FOOT PATH AT KONNUR HIGH ROAD DN 96 ZONE 8,Own Sources,8,2012-13,2016-17 NH/2012-13/16697,Roads,Completed,NH-ANNA NAGAR,96,2724000,Providing and Layaing white Topping Road With M40 grade Concrete at V. P Colony FIRST CROSS street in dn 96 zone 8,Own Sources,8,2012-13,2016-17 NH/2012-13/16702,Roads,Completed,NH-ANNA NAGAR,96,4975000,Providing and Layaing white Topping Road With M40 grade Concrete at V. P Colony South street in dn 96 zone 8,Own Sources,8,2012-13,2016-17 NH/2012-13/16721,Roads,Completed,NH-ANNA NAGAR,96,3242487,Providing and Layaing white Topping Road With M40 grade Concrete at V. P Colony Third cross street in dn 96 zone 8,Own Sources,8,2012-13,2016-17 L/2012-13/9492,Electrical,Completed,L-Electrical,125,3979000,"PROVISION OF 106 NOS OF SOLAR PHOTO VOLTAIC (SPV) LIGHTING WITH 20W LED AT BYE PASS ROAD FROM NOCHI KUPPAM TO FORESHORE ESTATE, DIVISION 125, ZONE IX.",MLACDS,9,2012-13,2016-17 NK/2012-13/24279,Roads,Completed,NK-KODAMBAKKAM,128,2455000,"Proposed White Topping Concere Interior Road at Abirami Nagar Main Road and 1st and 2nd Cross Street in Dn. 128, Unit 29, Zone 10.",Own Sources,10,2012-13,2018-19 NK/2012-13/24317,Roads,Completed,NK-KODAMBAKKAM,128,1152000,"Proposed White Topping Concrete Interior Road at AVM Avenue 6th Street in Dn. 128, Unit 29, Zone 10.",Own Sources,10,2012-13,2018-19 NM/2012-13/24172,Roads,Completed,NM-ALANDUR,161,2167000,LAYING C C ROAD USING RMC M40 GRADE AT TNGO COLONY 1ST STREET IN DN 161 U 36 Z 12,Own Sources,12,2012-13,2016-17 NM/2012-13/24179,Roads,Completed,NM-ALANDUR,161,1700000,LAYING C C ROAD FOR USING M40 GRADE AT GOODSHED ROAD IN DN 161 U 36 Z 12,Own Sources,12,2012-13,2016-17 NM/2012-13/24219,Roads,Completed,NM-ALANDUR,161,4664000,LAYING C C ROAD FOR USING RMC M40 GRADE AT MASTHAN GOWRI STREET IN DN 161 U 36 Z 12,Own Sources,12,2012-13,2016-17 NM/2012-13/24491,Roads,Completed,NM-ALANDUR,161,976000,LAYING C C ROAD FOR USING RMC M40 GRADE AT THIRUVALLUVAR 2ND STREET IN DN 161 U 36 Z 12,Own Sources,12,2012-13,2016-17 NM/2012-13/24495,Roads,Completed,NM-ALANDUR,161,517000,LAYING C C ROAD FOR USING RMC M40 GRADE AT TNGO COLONY 1ST STREET IN DN 161 U 36 Z 12,Own Sources,12,2012-13,2016-17 NM/2012-13/24504,Roads,Completed,NM-ALANDUR,161,855000,LAYING C C ROAD FOR USING RMC M40 GRADE AT LIOYDS AVENUE 2ND STREET IN DN 161 U 36 Z 12,Own Sources,12,2012-13,2016-17 NM/2012-13/24512,Roads,Completed,NM-ALANDUR,161,772000,"LAYING C C ROAD FOR USING RMC M40 GRADE AT SANJAI GANDHI 1st STREET IN DN 161, U 36, Z 12",Own Sources,12,2012-13,2016-17 NM/2012-13/25118,Roads,Completed,NM-ALANDUR,161,1059000,LAYING C C ROAD USING RMC M40 GRADE AT GOOD SHED ROAD 4TH STREET IN DEN 161 U 36 Z 12,Own Sources,12,2012-13,2016-17 NM/2012-13/24216,Roads,Completed,NM-ALANDUR,162,2336000,LAYING OF CEMENT CONCRETE ROAD RMC M40 AT KANNAN COLONY MAIN ROAD IN DN 162 U 36 Z 12.,Own Sources,12,2012-13,2016-17 NM/2012-13/24231,Roads,Completed,NM-ALANDUR,162,1724000,LAYING OF CEMENT CONCRETE ROAD RMC M40 AT HALFMAN 2ND STREET IN DN 162 U36 Z 12.,Own Sources,12,2012-13,2016-17 NM/2012-13/24490,Roads,Completed,NM-ALANDUR,162,821000,LAYING OF CEMENT CONCRETE ROAD RMC M40 AT NOBLE 3RD STREET IN DN 162 U 36 Z 12.,Own Sources,12,2012-13,2016-17 NM/2012-13/24501,Roads,Completed,NM-ALANDUR,162,821000,LAYING OF CEMENT CONCRETE ROAD RMC M40 AT KANNAN COLONY 3RD STREET IN DN 162 U 36 Z 12.,Own Sources,12,2012-13,2016-17 NM/2012-13/24506,Roads,Completed,NM-ALANDUR,162,1090000,LAYING OF CEMENT CONCRETE ROAD RMC M40 AT KANNAN COLONY 4TH STREET IN DN 162 U 36 Z 12.,Own Sources,12,2012-13,2016-17 NM/2012-13/24511,Roads,Completed,NM-ALANDUR,162,461000,LAYING OF CEMENT CONCRETE ROAD RMC M40 AT ALIGHAN CROSS STREET IN DN 162 U 36 Z 12.,Own Sources,12,2012-13,2016-17 NM/2012-13/25173,Roads,Completed,NM-ALANDUR,164,778000,"Laying Cement Concrete Road Using RMC M40 grade at KULAKKARAI second Street in Dn 164, U 36, Zone XII",Own Sources,12,2012-13,2016-17 NB/2013-14/8609,Parks,Completed,NB-MANALI,15,4850000,"FORMING PARK AT MANLI NEW TOWN BLOCK NO 26 IN S.NO 307pt,333pt,334pt (c.p.s-10) in dn-15,unit-4,zone-2",Own Sources,2,2013-14,2016-17 B/2013-14/20597,Buildings,Completed,B-Buildings,20,49680000,"Proposed Construction of Lorry Operation Depot at Kamarajar Salai,Manali in Dn-20,ZONE-II",Own Sources,2,2013-14,2016-17 B/2013-14/33495,Buildings,Completed,B-Buildings,20,89600000,"CONSTRUCTION OF ZONAL OFFICE FOR ZONE II AT KAMARAJAR SALAI,MANALI IN DN-20,ZONE-II",Own Sources,2,2013-14,2018-19 NC/2013-14/18992,Parks,Completed,NC-MADHAVARAM,22,344000,"MAINTENANCE PARK AT GURUSHANTHI NAGAR IN DIV-22,U-06,ZO-3",Own Sources,3,2013-14,2016-17 ND/2013-14/18303,Storm Water Drain,Completed,ND-TONDIARPET,34,4985000,"CONSTRUCTION OF PROPOSED NEW TANK (FOR RAIN WATER HARVESTING)AT UNION CARPIT COLONY 9TH STREET IN DN-34,U-9,Z-4.",Own Sources,4,2013-14,2017-18 D/2013-14/34384,Storm Water Drain,Completed,D-Storm Water Drains,35,85734000,Name of the work:Construction of RCC open box type retaining wall and bed to Kodungaiyur Canal South Wing (Reach 1) from the junction of Kamaraj salai to Muthamizh nagar 191st street.Length 800 M Ch. 0 to 800M in dn 35 zone IV,JNNURM,4,2013-14,2016-17 D/2013-14/34394,Storm Water Drain,Completed,D-Storm Water Drains,35,92160000,Name of the work:Construction of RCC open box type retaining wall and bed to Kodungaiyur Canal South Wing (Reach 2) from the Muthamizh nagar 191st street Road to Y junction.Length :875M Ch.800 to 1675M in dn 35 zone IV,JNNURM,4,2013-14,2016-17 ND/2013-14/22106,Buildings,Completed,ND-TONDIARPET,41,1575000,"Construction of ICDS Center No-12085 at Sivaji Nagar Main Street in Ward-41,Unit-10, Zone-4",MLACDS,4,2013-14,2016-17 B/2013-14/36624,Buildings,Completed,B-Buildings,42,82259858,"DEMOLISHING OF EXISTING BUILDING & CONSTRUCTION OF ZONAL OFFICE IV (G+3F) AT 266,THIRUVOTTRIYUR HIGH ROAD,OLD WASHERMENPET, FOR IN DN-42,ZONE-IV",Own Sources,4,2013-14,2017-18 L/2013-14/35540,Electrical,Completed,L-Electrical,43,2863100,"Provision of Video System for the Newly Constructed Auditorium in Communicable Diseases Hospital, Division 43, Zone IV",Own Sources,4,2013-14,2016-17 L/2013-14/35557,Electrical,Completed,L-Electrical,43,2859100,"Provision of Audio System for the Newly Constructed Auditorium in Communicable Diseases Hospital, Division 43, Zone IV",Own Sources,4,2013-14,2016-17 ND/2013-14/22095,Buildings,Completed,ND-TONDIARPET,43,1575000,"Construction of ICDS Center No-1072&1073 at Pudumanai Kuppam Main street in Ward-43,Unit-10,Zone-4",MLACDS,4,2013-14,2016-17 ND/2013-14/27019,Roads,Completed,ND-TONDIARPET,46,3613000,"LAYING CEMENT CONCREATE ROAD BY RMC AT B.KALYANAPURAM 1ST STREET,IN DN-46,U-11,ZONE-4",Own Sources,4,2013-14,2016-17 ND/2013-14/26174,Roads,Completed,ND-TONDIARPET,47,1573000,"Relaying Cement concret road by RMC @ meeanambal nagar 6th street , in Division -47, unit-11, zone-4.",Own Sources,4,2013-14,2016-17 L/2013-14/32057,Electrical,Completed,L-Electrical,51,4758300,"Supply & Erection of 66 nos of 9.5 mtr lamppost at Second line beach Road & mannady street in Dvn60 and 46nos of 7mtr lamp post at Kachaleeswarer agraharam Dn60,Malayappan street Dn 56 under Zone V.",Own Sources,5,2013-14,2016-17 NE/2013-14/29524,Roads,Completed,NE-ROYAPURAM,51,396000,"Laying of Cement Concrete road at Kalingarayan 1st street in Ward 51, Unit 12,Zone V",Own Sources,5,2013-14,2016-17 NE/2013-14/32598,Buildings,Completed,NE-ROYAPURAM,53,4078000,"Construction of 16th day modern ceremony centre inside moolakothalam burial ground in ward 53, unit 12, zone 5",MPLADS,5,2013-14,2016-17 NE/2013-14/37115,Roads,Completed,NE-ROYAPURAM,53,994000,"Laying cement concrete road at Peddu street in ward-53, unit-12, zone-5",Own Sources,5,2013-14,2016-17 NE/2013-14/33218,Roads,Completed,NE-ROYAPURAM,54,2620500,"LAYING CEMENT CONCRETE ROAD USING RMC40 AT SUNDERAM 1 TO 6 LANE IN DN-54,U-13,Z-5",Own Sources,5,2013-14,2016-17 NE/2013-14/33233,Roads,Completed,NE-ROYAPURAM,54,1657000,"LAYING CEMENT CONCRETE ROAD USING RMC40 AT VENKATESAN STREET IN DN-54,U-13,Z-5",Own Sources,5,2013-14,2016-17 NE/2013-14/34111,Roads,Completed,NE-ROYAPURAM,57,4978000,"LAYING CEMENT CONCRETE ROAD USING RMC40 AT DAVIDSON STREET IN DN-57,U-13,Z-5",Own Sources,5,2013-14,2016-17 NE/2013-14/34171,Roads,Completed,NE-ROYAPURAM,57,1767000,"LAYING CEMENT CONCRETE ROAD USING RMC40 AT JADKAPURAM LANE IN DN-57,U-13,Z-5",Own Sources,5,2013-14,2017-18 B/2013-14/31748,Buildings,Completed,B-Buildings,58,73500000,"ADDITIONAL OUTER AND INNER WORKS AND SITE DEVELOPMENT FOR THE RENOVATION OF THE RIPON BUILDING IN EVR PERIYAR SALAI IN DN-58, ZONE-V.",Own Sources,5,2013-14,2016-17 L/2013-14/32828,Electrical,Completed,L-Electrical,58,4408000,"Supply and Erection of 32 Nos of 8 Mtr Post with LED Fitting at Sydams Road and Cable Replacement at Vepary High Road ,Jermiah Road and Alli Kulam in Dn 58 Zone V.",Own Sources,5,2013-14,2016-17 NE/2013-14/29533,Roads,Completed,NE-ROYAPURAM,58,363000,"Laying of existing CC Road at Arunachalam Lane in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2016-17 NE/2013-14/29536,Roads,Completed,NE-ROYAPURAM,58,226000,"Laying of existing CC Road at Samynathan Lane in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2016-17 NE/2013-14/29538,Roads,Completed,NE-ROYAPURAM,58,282000,"Laying of existing CC Road at V.V. Koil Lane in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2016-17 NE/2013-14/29539,Roads,Completed,NE-ROYAPURAM,58,340000,"Laying of existing CC Road at Chengalvarayan Lane in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2016-17 NE/2013-14/29548,Roads,Completed,NE-ROYAPURAM,58,808000,"Laying of existing CC Road at Macadoom Sheriff Street in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2016-17 NE/2013-14/29554,Roads,Completed,NE-ROYAPURAM,58,520000,"Laying of existing CC Road at Varadhachari Lane in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2016-17 NE/2013-14/29557,Roads,Completed,NE-ROYAPURAM,58,235000,"Laying of existing CC Road at Kelly Lane in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2016-17 NE/2013-14/32384,Buildings,Completed,NE-ROYAPURAM,58,999000,"Improvements to the existing PC at Kannapper Thidal near Metro water pumping station in Dn-58, Unit-14, Zone-05.",Own Sources,5,2013-14,2018-19 NE/2013-14/10038,Parks,Completed,NE-ROYAPURAM,59,675000,"Annual Maintenance of Park Coovum River Side and Below MRTS at Swamy Sivananda Salai in Dn-59, Unit-14, Zone-05 for One Year",Own Sources,5,2013-14,2016-17 NE/2013-14/33247,Roads,Completed,NE-ROYAPURAM,59,2623000,"LAYING CEMENT CONCRETE ROAD USING RMC40 AT MUKTHURUNNISA 1 TO 7 LANE IN DN-59,U-14,Z-5",Own Sources,5,2013-14,2016-17 NE/2013-14/31432,Roads,Completed,NE-ROYAPURAM,61,3490000,"RE LAYING CEMENT CONCRETE ROAD AT LABBAI STREET IN DN 61 ,UNIT 14, Z05",Own Sources,5,2013-14,2016-17 NE/2013-14/31357,Roads,Completed,NE-ROYAPURAM,62,1539000,"RE LAYING CEMENT CONCRETE ROAD AT KOOVOOR VAITHIYANATHAN STREET IN DN 62 ,UNIT 14, Z05",Own Sources,5,2013-14,2016-17 NE/2013-14/31366,Roads,Completed,NE-ROYAPURAM,62,394000,"RE LAYING CEMENT CONCRETE ROAD AT USMANKHAN STREET IN DN 62 ,UNIT 14, Z05",Own Sources,5,2013-14,2016-17 NE/2013-14/33005,Buildings,Completed,NE-ROYAPURAM,62,2980000,"PROPOSED CONSTRUCTION OF FIRST FLOOR AT GYM BUILDING AT ARUNACHALAM STRRET IN DN-62,U-14,Z-5",Own Sources,5,2013-14,2016-17 B/2013-14/14501,Buildings,Completed,B-Buildings,64,14900000,CONSTRUCTION OF CHEMISTRY LAB IN G.F PHYSICS LAB IN F.F BIOLOGY LAB IN S.F AND COMPUTER LAB IN T.F AND TOILET BLOCK FOR C.H.S.S AT SCHOOL ROAD KOLATHUR IN DN 64 ZONE VI,Own Sources,6,2013-14,2016-17 NF/2013-14/37977,Footpath,Completed,NF-THIRU-VI-KA NAGAR,65,460000,"FORMING THE FOOTPATHS IN 10TH SENTHIL NAGAR IN DIVISION 65,UNIT 15,ZONE 6",Own Sources,6,2013-14,2016-17 NF/2013-14/37978,Footpath,Completed,NF-THIRU-VI-KA NAGAR,65,690000,"FORMING FOOTPATH IN SENTHIL NAGAR 9TH STREET IN DIV 65,UNIT 15,ZONE 6",Own Sources,6,2013-14,2016-17 NF/2013-14/37979,Footpath,Completed,NF-THIRU-VI-KA NAGAR,65,690000,FORMING FOOT PATH IN SENTHIL NAGAR 11TH STREET,Own Sources,6,2013-14,2016-17 NF/2013-14/3229,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2300000,Laying Cement concrete road with M40 Grade RMC at Periyar nagar 19th street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3244,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1960000,Laying Cement concrete road with M40 Grade RMC at Sivalingam street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3249,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,3880000,Laying Cement concrete road with M40 Grade RMC at Periyar nagar 12th street and 4 cross street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3251,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2240000,Laying Cement concrete road with M40 Grade RMC at Ramasamy street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3254,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1390000,Laying Cement Concrete road with M40 Grade RMC at Periyar nagar 20th street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3256,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1320000,Laying Cement concrete road with M40 Grade RMC at Jayaram street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3259,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1880000,Laying Cement concrete road with M40 Grade RMC at Periyar nagar 13th street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3262,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2480000,Laying Cement concrete road with M40 Grade RMC at Ganthimathi street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3267,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2560000,Laying Cement concrete road with M40 Grade RMC at Annal Ganthi street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/3271,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1200000,Laying Cement concrete road with M40 Grade RMC at Periyar nagar 21st street in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/9395,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,200000,Maintainance of park by private agency for the Period of 24 Month at Periyar Nagar 21st street Park in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/9396,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,158000,Maintainance of park by private agency for the Period of 24 Month at Jawahar Nagar 2nd Circular road Park in Dn66 U16 Z06,Own Sources,6,2013-14,2016-17 NF/2013-14/2807,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1527000,LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE AT GURUSAMY STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/2812,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1762000,LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE AT KAMARAJ STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/2857,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,2990000,LAYING OF CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT GOPALAPURAM 1ST STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/2859,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,2630000,LAYING OF CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT GOPALAPURAM 2ND STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/2870,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,2350000,LAYING OF CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT GOPALAPURAM 3RD STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/2886,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,2130000,LAYING OF CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT TEEDS GARDEN 1ST STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/2888,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1940000,LAYING OF CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT GURUMOORTHY NAGAR IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/24654,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,4990000,"RELAYING CEMENT CONCRETE SLUM ROADS AT MADURAI STREET & LANES, VASANTHA GARDEN 1ST STREET & 1ST, 2ND LANES IN DIV-69,UNIT-16, ZONE-6.",Own Sources,6,2013-14,2017-18 NF/2013-14/9467,Parks,Completed,NF-THIRU-VI-KA NAGAR,69,146000,"MAINTENANCE OF PARK BY PRIVATATION ENGAGING OUT SOURCING AT RAGHAVAN STREET PARK IN DIV 69 UNIT 16, ZONE 6",Own Sources,6,2013-14,2017-18 NF/2013-14/9469,Parks,Completed,NF-THIRU-VI-KA NAGAR,69,153000,"MAINTENANCE OF PARK BY PRIVATATION ENGAGING OUT SOURCING AT VENKATESWARA NAGAR 1st STREET PARK IN DIV 69 UNIT 16, ZONE 6",Own Sources,6,2013-14,2017-18 NF/2013-14/3275,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1775000,LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE AT DR.RAM STREET IN DN 70 U 16 Z 6,Own Sources,6,2013-14,2016-17 NF/2013-14/33134,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,693000,"MAINTANANCE OF RAGIV GANDHI PARK AT PH ROAD IN DN 70,UNIT 16, ZONE 6, (2 YEARS)",Own Sources,6,2013-14,2016-17 NF/2013-14/3390,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,999000,LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT CHINNAIAH NEW COLONY 1ST CROSS STREET IN DN 70 U 16 Z 6,Own Sources,6,2013-14,2016-17 NF/2013-14/3396,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2972000,LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT MUTHUMARIAMMAN KOVIL STREET IN DN 70 U 16 Z 6,Own Sources,6,2013-14,2016-17 NF/2013-14/25297,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,440000,"RELAYING WITH DBM50MM AND BC30MM AT PERAMBUR HIGH ROAD 1ST CROSS STREET IN DN 71, U-16, ZONE-6.",Own Sources,6,2013-14,2016-17 B/2013-14/31177,Buildings,Completed,B-Buildings,72,18000000,"ADDITIONAL CONSTRUCTION OF FIRST FLOOR AND PORTICO FOR COMMUNITY CENTRE AND COMPOUND WALL IN VOC NAGAR FIRST STREET AT PULIANTHOPE IN DN-72, ZONE-VI",Own Sources,6,2013-14,2016-17 L/2013-14/31733,Electrical,Completed,L-Electrical,72,631800,Supply and erection of 18 nos of 7mtrs GI lamp post with 40w to 50 watts LED fitting and laying of 4x25 sq.mm Al. cable at decastor road in division 72 in zone 6,Own Sources,6,2013-14,2016-17 L/2013-14/32687,Electrical,Completed,L-Electrical,72,2503400,"REPLACEMEMT OF 73 NOS 6/7 RUST EATEN ED LAMP POST WITH 77 NOS OF GI 7MTRS LAMP POST WITH 40 T0 50 WATTS LED FITTING AND SUPPLY AND LAYING OF 2X25 SQ.MM AL. CABLE AND 4X25 SQ.MM AL. CABLE AT VOC NAGAR , AMBATHKAR NAGAR , DECASTOR ROAD AND SOURROUNDING AREA IN DIVISION 72 IN ZONE 6",Own Sources,6,2013-14,2016-17 L/2013-14/34706,Electrical,Completed,L-Electrical,72,2768600,Supply and erection of 28nos of 9.5mtr GI double st. bracket with 90-120w LED Fitting with laying of 1000mtr of 4x25sqmm UG Cable at Basin bridge Centre mediun portion in div 72 zone VI,Own Sources,6,2013-14,2016-17 Q/2013-14/7008,Buildings,Completed,RN-Regional office - North,72,4670000,Installation of Bio power generation from segregated Municipal solid waste at transfer station in zone V,Own Sources,6,2013-14,2016-17 L/2013-14/32100,Electrical,Completed,L-Electrical,73,2180200,Supply and erection of 69 NOS OF 7MTS GI LAMP POST WITH 40 TO 50 WATTS LED FITTING AND LAYING OF 2X25 SQ.MM AL. CABLE AT NARAYANA SWAMI STREET AND SURROUNDING AREA AND GREY NAGAR IN DIVISION 73 IN ZONE 6,Own Sources,6,2013-14,2016-17 NF/2013-14/24936,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,593000,"RELAYING BC 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT A.K.SAMY NAGAR 6TH STREET IN DN.74, UNIT.17, ZONE.6",Own Sources,6,2013-14,2016-17 NF/2013-14/24937,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1179000,"RELAYING BC 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT A.K.SAMY NAGAR 7TH STREET IN DN.74, UNIT.17, ZONE.6",Own Sources,6,2013-14,2016-17 NF/2013-14/3149,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,3878000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT SECRETARIAT COLONY 2ND STREET IN DN 74, UNIT 17, ZONE 6.",Own Sources,6,2013-14,2016-17 NF/2013-14/3159,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,3592000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT SECRETARIAT COLONY 3RD STREET IN DN 74, UNIT 17, ZONE 6.",Own Sources,6,2013-14,2016-17 NF/2013-14/3175,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,2474000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT SECRETARIAT COLONY 4TH AND 5TH STREET IN DN 74, UNIT 17, ZONE 6.",Own Sources,6,2013-14,2016-17 NF/2013-14/2806,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,4486000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT S.S.PURAM A BLOCK 1ST STREET IN DN.75, UNIT.17, ZONE.6",Own Sources,6,2013-14,2016-17 NF/2013-14/31872,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,7555000,"LAYING CEMENT CONCRETE ROAD WITH RMC 40 GRADE CONCRETE AT VENGADATHRI STREET IN DH.75, UNIT.17, ZONE.6",Own Sources,6,2013-14,2016-17 NF/2013-14/18132,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,780000,"MAINTENANCE OF PARK FOR TWO YEARS AT C.S.NAGAR IN DIV-76, UNIT-17, ZONE-6.",Own Sources,6,2013-14,2016-17 NF/2013-14/25112,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1925000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT GOVINDARAJULU STREET AND GOVINDA (A) STREET, DN-77, UNIT-17, ZONE-6",Own Sources,6,2013-14,2017-18 NF/2013-14/30775,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,3881000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT SUNDARAPURAM 3RD STREET, 1ST LAND AND 2ND LANE, DN 77, UNIT 17, ZONE 6.",Own Sources,6,2013-14,2017-18 NF/2013-14/3136,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1500000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE CONCRETE AT PULIANTHOPU 4TH STREET IN DN.77, UNIT.17, ZONE.6",Own Sources,6,2013-14,2016-17 NG/2013-14/14665,Buildings,Completed,NG-AMBATTUR,79,456000,"IMPROMENT WORKS TO AMMA UNAVAGAM AT KATABOMMAN ST WARD-79, UNIT-18, ZONE-7.",Own Sources,7,2013-14,2016-17 NG/2013-14/27770,Roads,Completed,NG-AMBATTUR,79,9590000,"Forming and strengthening of road at Rajiv ganthi street, Rajiv ganthi cross street, Ellai amman street, Anbazagan street, Kumaran street in Dn.79, Unit-18,Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/27773,Roads,Completed,NG-AMBATTUR,79,7190000,"Forming and strengthening of road at V.O.C.street, Perumal koil street, Ambedkar street, Kalaivanar street in Dn.79, Unit-18,Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/16974,Roads,Completed,NG-AMBATTUR,80,1780000,"PROVIDING AND FIXING OF SIGNAGE STREET NAME BOARDS AT VARIOUSSTREETS IN DIV.80, UNIT18, ZONE 7 (AMBATTUR)",Grants,7,2013-14,2016-17 NG/2013-14/30872,Roads,Completed,NG-AMBATTUR,80,2700000,"Laying of CC road at Thirumalai Priya Nagar 16th,16th cross,15th,10th and 10th 1st cross Streets in Dn-80,Unit-18,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/30875,Roads,Completed,NG-AMBATTUR,80,2780000,"Laying of CC road at Thirumalai Priya Nagar 10th 2nd Cross,7th Street,6th Street and 6th Cross Street in Dn 80,Unit-18,zone-7",Grants,7,2013-14,2016-17 NG/2013-14/30877,Roads,Completed,NG-AMBATTUR,80,2680000,"Laying of CC road at Thirumalai Priya Nagar 3rd Street,3rd Cross,4th Street and 5th Street in Dn 80,Unit-18,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/30879,Roads,Completed,NG-AMBATTUR,80,2990000,"Laying of CC road at Kamaraj Street,Kamaraj 1st Street and Vairam Kulam 2nd Street in Dn80,Unit-18,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/30881,Roads,Completed,NG-AMBATTUR,80,2800000,"Laying of CC road at Nethaji 2nd Cross Street,Abiramipuram 2nd Cross,2nd Street and pudur 2nd Cross Street in Dn-80,Unit-18,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/28272,Roads,Completed,NG-AMBATTUR,81,2800000,"LAYING OF CEMENT CONCRETE ROAD AT INDRA NAGAR 1 - 3RD STREET IN DN 81,UNIT-18,ZONE-7",Grants,7,2013-14,2016-17 NG/2013-14/28274,Roads,Completed,NG-AMBATTUR,81,3330000,"LAYING OF CEMENT CONCRETE ROAD AT SEMAYAPURATHAMMAN KOIL STREET AND ANNA STREET IN DN 81,U-18,ZONE-7.",Grants,7,2013-14,2016-17 NG/2013-14/29334,Roads,Completed,NG-AMBATTUR,81,1740000,"LAYING OF CC ROAD AT INDRA NAGAR 6TH AND 7TH STREET IN DN 81, U 18, ZONE 7",Grants,7,2013-14,2016-17 NG/2013-14/29541,Roads,Completed,NG-AMBATTUR,81,2600000,"LAYING OF CC ROAD AT INDRA NAGAR 4TH AND 5TH STREET IN DN 81,U-18,Z-7.",Grants,7,2013-14,2016-17 NG/2013-14/29545,Roads,Completed,NG-AMBATTUR,81,1900000,"LAYING OF CC ROAD AT KALYANAPURAM 2ND STREET AND MARIYAMMAN KOIL 1ST STREET IN DN 81, U 18, ZONE 7",Grants,7,2013-14,2016-17 NG/2013-14/29547,Roads,Completed,NG-AMBATTUR,81,2060000,"LAYING OF CC ROAD AT KALYANAPURAM BAJANAI KOIL 3RD CROSS AND KALYANAPURAM 1ST STREET IN DN 81, U 18, ZONE 7",Grants,7,2013-14,2016-17 NG/2013-14/30816,Roads,Completed,NG-AMBATTUR,81,3500000,"LAYING OF CC ROAD AT K.K ROAD 4TH,5TH AND 11TH CROSS STREET IN DN 81,U-18,ZONE-7.",Grants,7,2013-14,2016-17 NG/2013-14/21330,Roads,Completed,NG-AMBATTUR,82,4995000,"Forming and strengthening of road at Suburamani street,Prithipakam pillayar koil street, India vangi colony 5th street and Theradi street(1st part) in DN 82, Unit 18, Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/21336,Roads,Completed,NG-AMBATTUR,82,4990000,"Forming and strengthening of road at V.O.C Nagar main road(2ND PART) and V.O.C nagar 1st and 2nd street in DN 82, Unit 18, Zone-7.",Own Sources,7,2013-14,2016-17 NG/2013-14/33951,Roads,Completed,NG-AMBATTUR,82,4995000,"Forming and strengthening of road at Theradi street(2nd part) in DN 82, Unit 18, Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/33997,Roads,Completed,NG-AMBATTUR,82,4995000,"Forming and strengthening of road at North pillayar koil street in DN 82, Unit 18, Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/22271,Parks,Completed,NG-AMBATTUR,83,9950000,CONSTRUCTION OF PARK AT TNHB 61st STREET (O S R LAND) IN DN 83 UNIT 19 ZONE 7,Own Sources,7,2013-14,2016-17 NG/2013-14/27964,Roads,Completed,NG-AMBATTUR,83,27500000,FORMING AND LAYING OF BT COURSE BY PAVER AT VANDIPATTAI ROAD ( FROM SRINIVASAPURAM 3RD MAIN ROAD TO KARUKU MAIN ROAD ALONG RAILWAY TRACK ) IN DIV 83 UNIT 19 ZONE 7,Own Sources,7,2013-14,2016-17 NG/2013-14/9584,Buildings,Completed,NG-AMBATTUR,84,4890000,"PROPOSED CONSTRUCTION OF DIVISION OFFICE AT EAST AVENUE ROAD IN DIVISION-84, UNIT-19, ZONE-7",Own Sources,7,2013-14,2016-17 NG/2013-14/9616,Buildings,Completed,NG-AMBATTUR,84,1600000,"CONSTRUCTION OF ANGANWADI BUILDING IN CMS AT CHAVADI STREET IN DIVISION -84 UNIT-19,ZONE-7",MLACDS,7,2013-14,2016-17 NG/2013-14/27892,Roads,Completed,NG-AMBATTUR,86,2180000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Eastern Side of Ayanambakkam Road)-6th Street, 6th Cross Street, in Dn-86, U-19,Zone-7",Grants,7,2013-14,2016-17 NG/2013-14/27894,Roads,Completed,NG-AMBATTUR,86,2420000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Eastern Side of Ayanambakkam Road)-5th Street and 5th Cross Streets(E&W) in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/27926,Roads,Completed,NG-AMBATTUR,86,2660000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Eastern Side of Ayanambakkam Road)-1st Street and 2nd Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/28242,Roads,Completed,NG-AMBATTUR,86,5650000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Eastern Side of Ayanambakkam Road)-1st Main Road in Dn-86, U-19,Zone-7..",Grants,7,2013-14,2016-17 NG/2013-14/28244,Roads,Completed,NG-AMBATTUR,86,1450000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Western Side of Ayanambakkam Road)-5th Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/28248,Roads,Completed,NG-AMBATTUR,86,2790000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Western Side of Ayanambakkam Road)-3rd Street and 4th Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/28253,Roads,Completed,NG-AMBATTUR,86,1810000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Western Side of Ayanambakkam Road)-1st Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31065,Roads,Completed,NG-AMBATTUR,86,2630000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Eastern Side of Ayanambakkam Road)-7th Street and 7th Cross Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31217,Roads,Completed,NG-AMBATTUR,86,1990000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Eastern Side of Ayanambakkam Road)-9th Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31220,Roads,Completed,NG-AMBATTUR,86,2350000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III,Mahatma Gandhi Nagar-Cauvery,Sindhu,Krishna,Gangai Streets in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31226,Roads,Completed,NG-AMBATTUR,86,2460000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III,Mahatma Gandhi Nagar-3rd Main Road in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31229,Roads,Completed,NG-AMBATTUR,86,2640000,"Laying of Cement Concrete Roads at P.V. City-1st Main Road in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31243,Roads,Completed,NG-AMBATTUR,86,2910000,"Laying of Cement Concrete Roads at P.V. City-1st Cross Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31245,Roads,Completed,NG-AMBATTUR,86,2780000,"Laying of Cement Concrete Roads at P.V. City-2nd Cross Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31277,Roads,Completed,NG-AMBATTUR,86,2910000,"Laying of Cement Concrete Roads at P.V. City-3rd Cross Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/34241,Roads,Completed,NG-AMBATTUR,86,1817000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Western Side of Ayanambakkam Road)-2nd Street in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/34264,Roads,Completed,NG-AMBATTUR,86,2000000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III (Western Side of Ayanambakkam Road)-5th cross Streets in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/34273,Roads,Completed,NG-AMBATTUR,86,1920000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III,Mahatma Gandhi Nagar-Yamunai,Vaigai,Saraswathi and Narmathai Streets in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/34277,Roads,Completed,NG-AMBATTUR,86,1220000,"Laying of Cement Concrete Roads at ICF Colony,THHB Phase-III,Mahatma Gandhi Nagar-4th Main Road in Dn-86, U-19,Zone-7.",Grants,7,2013-14,2016-17 B/2013-14/22385,Buildings,Completed,B-Buildings,87,13250000,"CONSTRUCTION OF FISH MARKET AT MTH ROAD, PADI IN DN-87 ZONE-VII",Own Sources,7,2013-14,2016-17 NG/2013-14/30815,Roads,Completed,NG-AMBATTUR,89,2434000,"Providing and Laying CC Road At Radial House Streets ( Block-A) in Dn-89,Unit-20,Zone-7",Grants,7,2013-14,2016-17 NG/2013-14/31530,Roads,Completed,NG-AMBATTUR,89,2450000,"Providing and Laying CC Road At Radial House Streets ( Block-B) in Dn-89,Unit-20,Zone-7",Grants,7,2013-14,2016-17 NG/2013-14/31532,Roads,Completed,NG-AMBATTUR,89,2450000,"Providing and Laying CC Road At Radial House Streets ( Block-C) in Dn-89,Unit-20,Zone-7",Grants,7,2013-14,2016-17 NG/2013-14/38988,Roads,Completed,NG-AMBATTUR,89,1166000,"Forming and Relaying the BT Road at Olympic Colony Main Road in Dn.89, Unit-19,Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/38989,Roads,Completed,NG-AMBATTUR,89,1702000,"Forming and Relaying the BT Road at Akshaya Colony 3rd Street in Dn.89, Unit-19,Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/38991,Roads,Completed,NG-AMBATTUR,89,1850000,"Forming and Relaying the BT Road at Akshaya Colony 1st Streets in Dn.89, Unit-19,Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/16078,Roads,Completed,NG-AMBATTUR,90,11942000,"Strengthening and laying of BT road at Kalaivanar Colony main pillaiyar koil st, Karumariyamman koil St, Gandhi St, Ambethkar St, Anna Street, Rajaji St, Kalaivanar colony Extn. in Div-90, Unit-20, Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/16088,Roads,Completed,NG-AMBATTUR,90,16270000,"Strengthening and laying the BT road at Gandhi nagar main road, Kamarajar nagar main road, Periyyar nagar, Kovil St and Annai Flats in Div-90, Unit-20, Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/16103,Roads,Completed,NG-AMBATTUR,90,32820000,"Strengthening and laying the road at 5th avenue, 6th avenue, 7th Avenue, 9th,10th,11th and 12th Sreet in Div-90, Unit-20, Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/16129,Footpath,Completed,NG-AMBATTUR,90,790000,"Construction of Service Cable Inspection Chamber at Gandhi Nagar main road, Kamaraj nagar main road, Periyar nagar main road, Koil Street and annai flats in Div-90, Unit-20, Zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31141,Roads,Completed,NG-AMBATTUR,90,5866000,"LayIng of Cement Concrete Roads at Thamarai Kudiyiruppu street in Div-90, Unit-20,Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/39023,Roads,Completed,NG-AMBATTUR,90,3848000,"Forming and Relaying the BT Road at 6th Avenue in Dn.90, Unit-20, Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/39024,Roads,Completed,NG-AMBATTUR,90,3848000,"Forming and Relaying the BT Road at 7th Avenue in Dn-90, Unit-20, Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/39025,Roads,Completed,NG-AMBATTUR,90,3038000,"Forming and Relaying the BT Road at Welcome Colony 1st Street in Dn-90, Unit-20,Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/39027,Buildings,Completed,NG-AMBATTUR,90,12660000,"Construction of storm water drain of size 900 X900 MM along 6th & 7th Avenue In Division 90 , Unit-20, Zone: VII",Grants,7,2013-14,2016-17 NG/2013-14/16909,Buildings,Completed,NG-AMBATTUR,91,2892000,"PROVIDING FOOT PATH WORK BOTH SIDES AT MOGAPPAIR WEST KAMBER ROAD FROM AMBATTUR - THIRUMANGALAM ESTATE ROAD TO MOGAPPAIR WEST 3rd MIAN ROAD IN DIV.91, UNIT20, ZONE-7",Grants,7,2013-14,2016-17 NG/2013-14/17071,Buildings,Completed,NG-AMBATTUR,91,5348000,PROVIDING AND FIXING OF SIGNAGE STREET NAME BOARDS AT VARIOUS STREET IN DIVISION 91 UNIT 20 ZONE 7,Grants,7,2013-14,2016-17 NG/2013-14/20182,Buildings,Completed,NG-AMBATTUR,91,5302000,"PROVIDING FOOT PATH WORK MOGAPPAIR TNHB 7TH BLOCK SCHOOL ROAD IN DIV.91, UNIT 20, ZONE - 7",Grants,7,2013-14,2016-17 NG/2013-14/2590,Parks,Completed,NG-AMBATTUR,91,385000,ANNUAL MAINTENANCE TO MOGAPPAIR WEST BUS STAND PARK IN DIVISION NO.91 U 20 ZONE 7,Own Sources,7,2013-14,2016-17 NG/2013-14/31081,Roads,Completed,NG-AMBATTUR,91,4590000,"Construction of storm water drain of size 900 X900 MM at Jeswanth Nagar 1st Main Road In Division-91, Unit-20, zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/31126,Roads,Completed,NG-AMBATTUR,91,2026000,"LayIng of Cement Concrete Roads at Land bank scheme 4th street, Land bank scheme 5th street and Land bank scheme 6th street in Div-91, Unit-20,Zone VII",Grants,7,2013-14,2016-17 NG/2013-14/35897,Storm Water Drain,Completed,NG-AMBATTUR,91,4590000,"Construction of storm water drain of size 900 X900 MM at Jeswanth Nagar 2nd Main Road In Division-91, Unit-20, zone-7.",Grants,7,2013-14,2016-17 NG/2013-14/7096,Parks,Completed,NG-AMBATTUR,91,331000,"Annual Maintenance to jesvanth nagar phase - 1 park in div - 91, Unit- 20,Zone - 7",Own Sources,7,2013-14,2016-17 NG/2013-14/7395,Parks,Completed,NG-AMBATTUR,91,330000,"Annual Maintenance to Mogappair Eri Scheme 8 th street park in Div-91,Unit-20,Zone-7.",Own Sources,7,2013-14,2016-17 NG/2013-14/7962,Parks,Completed,NG-AMBATTUR,91,340000,"Annual maintenance to mogappair west VGN Avenue Park in Div-91, Unit-20, Zone-7.",Own Sources,7,2013-14,2016-17 NG/2013-14/8083,Electrical,Completed,NG-AMBATTUR,91,456000,Construction of Compound wall and other Improvement works to Mogappair Eri scheme 13th cross street open space in Division no.91 Zone-7,Own Sources,7,2013-14,2016-17 NG/2013-14/8872,Buildings,Completed,NG-AMBATTUR,91,2617000,"Additional Improvements works to Chennai corporation Health Post at TNHB Kalamegham salai in D.No.91 Unit-20, Zone-7",Own Sources,7,2013-14,2016-17 NG/2013-14/24839,Roads,Completed,NG-AMBATTUR,92,4735000,Laying of Cement Concrete Roads at Dr JJ Nagar east VGP Nagar cross street (R2) in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/29215,Roads,Completed,NG-AMBATTUR,92,4747000,Laying of Cement Concrete Roads at Dr JJ Nagar east VGP Nagar cross street (R1) in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/30318,Roads,Completed,NG-AMBATTUR,92,4778000,Laying of Cement Concrete Roads at Dr JJ Nagar east Spartan School 1st street (R1) in Div-92 Zone VII,Own Sources,7,2013-14,2017-18 NG/2013-14/30362,Roads,Completed,NG-AMBATTUR,92,4813000,Laying of Cement Concrete Roads at Dr JJ Nagar east Spartan School 1st street (R2) in Div-92 Zone VII,Own Sources,7,2013-14,2017-18 NG/2013-14/30375,Roads,Completed,NG-AMBATTUR,92,4812000,"Laying of Cement Concrete Roads at Dr JJ Nagar east Spartan School 3rd street (R2) in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/30491,Roads,Completed,NG-AMBATTUR,92,4824000,Laying of Cement Concrete Roads at Dr JJ Nagar east Spartan School 3rd street (R1) in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/30900,Roads,Completed,NG-AMBATTUR,92,2389000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 11th block 1 to 2 ,15streets and 10th block 41th street in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/30906,Roads,Completed,NG-AMBATTUR,92,2103000,Laying of Cement Concrete Roads at Dr JJ Nagar east 11th block3 to 7 streets in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/30910,Roads,Completed,NG-AMBATTUR,92,2751000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 11th block 13,16 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/30912,Roads,Completed,NG-AMBATTUR,92,2094000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 11th block 22 to 24, 12th block 1 to 4 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/30914,Roads,Completed,NG-AMBATTUR,92,2899000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 10th block 9 ,14, 15 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/30915,Roads,Completed,NG-AMBATTUR,92,2635000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 10th block 8, 10 to 12 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/30917,Roads,Completed,NG-AMBATTUR,92,588185,Laying of Cement Concrete Roads at Dr JJ Nagar east 10th block 34 to 40 streets in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/30922,Roads,Completed,NG-AMBATTUR,92,2091000,Laying of Cement Concrete Roads at Dr JJ Nagar east 10th block 31 to 33 streets in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/30945,Roads,Completed,NG-AMBATTUR,92,4220000,Laying of Cement Concrete Roads at Dr JJ Nagar east zion street in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/30948,Roads,Completed,NG-AMBATTUR,92,2759000,Laying of Cement Concrete Roads at Dr JJ Nagar east Zion 1st cross street in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31011,Roads,Completed,NG-AMBATTUR,92,4722000,Laying of Cement Concrete Roads at Dr JJ Nagar east Venugopal street (part)in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31032,Roads,Completed,NG-AMBATTUR,92,4722000,Laying of Cement Concrete Roads at Dr JJ Nagar east Gandhi street in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31039,Roads,Completed,NG-AMBATTUR,92,3878000,Laying of Cement Concrete Roads at sangeetha street (R2) in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31041,Roads,Completed,NG-AMBATTUR,92,4790000,Laying of Cement Concrete Roads at Dr JJ Nagar east Pada salai 2nd street in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31044,Roads,Completed,NG-AMBATTUR,92,4790000,Laying of Cement Concrete Roads at Dr JJ Nagar east Green view colony in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31045,Roads,Completed,NG-AMBATTUR,92,4790000,Laying of Cement Concrete Roads at Dr JJ Nagar east pada salai 1st street in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31053,Roads,Completed,NG-AMBATTUR,92,4790000,Laying of Cement Concrete Roads at Dr JJ Nagar east Pandian street in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31067,Roads,Completed,NG-AMBATTUR,92,3953000,Laying of Cement Concrete Roads at Dr JJ Nagar east Bajana koil 2nd street and Zion 2nd cross street in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/31802,Roads,Completed,NG-AMBATTUR,92,4824000,Laying of Cement Concrete Roads at Dr JJ Nagar east Spartan School 2nd street (R1) in Div-92 Zone VII,Own Sources,7,2013-14,2017-18 NG/2013-14/31804,Roads,Completed,NG-AMBATTUR,92,4812000,Laying of Cement Concrete Roads at Dr JJ Nagar east Spartan School 2nd street (R2) in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/33840,Roads,Completed,NG-AMBATTUR,92,2291000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 11th block 8 to 12,14 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/34008,Roads,Completed,NG-AMBATTUR,92,1842000,Laying of Cement Concrete Roads at Dr JJ Nagar east 11th block 17 to 21 streets in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/34017,Roads,Completed,NG-AMBATTUR,92,2583000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 12th block 5 to 12 ,14,16 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/34019,Roads,Completed,NG-AMBATTUR,92,2195000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 12th block 13 & 15, 17 to 20 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/34046,Roads,Completed,NG-AMBATTUR,92,2536000,"Laying of Cement Concrete Roads at Dr JJ Nagar east 12th block 21 TO 23 and 10 block 2,3 streets in Div-92 Zone VII",Own Sources,7,2013-14,2016-17 NG/2013-14/34052,Roads,Completed,NG-AMBATTUR,92,1767000,Laying of Cement Concrete Roads at Dr JJ Nagar east 10th block 16 to 20 streets in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/35149,Roads,Completed,NG-AMBATTUR,92,1955000,Laying of Cement Concrete Roads at Dr JJ Nagar east 10th block 21st to 24th streets in Div-92 Zone VII,Own Sources,7,2013-14,2016-17 NG/2013-14/39444,Buildings,Completed,NG-AMBATTUR,92,381000,THE IMPROVEMENT WORKS TO NNMP SHED AT PATTINATHAR SALAI,Own Sources,7,2013-14,2016-17 NG/2013-14/15725,Footpath,Completed,NG-AMBATTUR,93,3230000,"Providing footpath work at Dr.JJ Nagar East Gangai amman Nagar main road and Church Road in Div-93, U-20, Zone-7",Grants,7,2013-14,2016-17 NG/2013-14/15980,Roads,Completed,NG-AMBATTUR,93,12310000,"Strengthening and Forming the BT road at Church road and Gangai amman nagar Main road in Div-93, U-20, Zone -7",Grants,7,2013-14,2016-17 NG/2013-14/16748,Roads,Completed,NG-AMBATTUR,93,5297000,"PROVIDING AND FIXING OF SIGNAGE STREET NAME BOARDS AT VARIOUS STREET IN DIV-93, UNIT-20, ZONE-7(AMBATTUR).",Grants,7,2013-14,2016-17 NG/2013-14/23371,Buildings,Completed,NG-AMBATTUR,93,1928000,"Construction of NNMP Shed in chennai primary school-sector I at Dr.JJ Nagar East 2nd Block Agathiyar Salai in Div 93,U 20,Zone 7.",Own Sources,7,2013-14,2016-17 NG/2013-14/39384,Storm Water Drain,Completed,NG-AMBATTUR,93,7944000,"Construction of Storm Water Drain Of Size 900x900 mm along Vandiyamman Kovil Street and Veeramamunivar Street From Nakkeeran Salai to Seethakadhi Salai in Div-93,Unit-20,Zone-VII.",Grants,7,2013-14,2016-17 NG/2013-14/9142,Electrical,Completed,NG-AMBATTUR,93,5303000,"Construction of Division office at Padikuppam main road in Div-93, Unit-20, Zone-7",Own Sources,7,2013-14,2017-18 NH/2013-14/4096,Roads,Completed,NH-ANNA NAGAR,94,4995000,Providing and laying cement concreat roadat thathankuppam main road in dn 94,Own Sources,8,2013-14,2016-17 NH/2013-14/14235,Roads,Completed,NH-ANNA NAGAR,95,46000,"RAISING THE ROAD LEVEL WITH WMM AT I.C.F ANNEX LANE IN DN-95,UNIT-21,ZONE-8.",Own Sources,8,2013-14,2016-17 NH/2013-14/19781,Buildings,Completed,NH-ANNA NAGAR,95,90000,"IMPROVEMENTS TO PUBLIC TOILET AT THIRUVEETHI AMMAN KOIL 2nd STREET IN DN-95, UNIT-21, ZONE-08",Own Sources,8,2013-14,2016-17 NH/2013-14/38735,Roads,Completed,NH-ANNA NAGAR,95,568000,"LAYING C.C. ROAD AT THIRU VA KA NAGAR 2ND STREET IN DN-95,UNIT-21,ZONE-08",Own Sources,8,2013-14,2016-17 B/2013-14/32789,Buildings,Completed,B-Buildings,96,13800000,"CONSTRUCTION OF DISPENSARY IN G.F AND F.FLOOR AFTER DEMOLITION OF EXISTING DILAPIDATED RMO QUARTERS AT UNITED INDIA NAGAR FIRST MAIN ROAD AND DEMOLITION OF DILAPIDATED DISPENSARY AT PALAVOYAL ROAD IN DN-96, ZONE-VIII",Own Sources,8,2013-14,2016-17 NH/2013-14/36196,Roads,Completed,NH-ANNA NAGAR,96,2980000,"PROVIDING AND LAYING WHITE TOPPING ROAD WITH M40 GRADE CONCRETE AT V.P COLONY SOUTH STREET ( JUNCTION OF V.P.COLONY 2ND CROSS STREET TO JUNCTION OF S.S DEVAR 6TH STREET) IN DN-96 , U-21 , Z-08",Own Sources,8,2013-14,2016-17 NH/2013-14/34948,Parks,Completed,NH-ANNA NAGAR,97,127679,"Maintenance of Park for 2 years at Patchaikal Veerasamy Tenement in Dn.97, Unit.21, Zone. 8",Own Sources,8,2013-14,2016-17 NH/2013-14/34952,Parks,Completed,NH-ANNA NAGAR,97,246321,"Annual Maintenance to Park at VELLALA STREET in Dn.97, Unit.21, Zone. 8",Own Sources,8,2013-14,2016-17 NH/2013-14/33614,Roads,Completed,NH-ANNA NAGAR,101,92000,"SUPPLY AND FIXING NAME BOARD AT AMMA ARANGAM IN DN-101,U-22,Z-08",Own Sources,8,2013-14,2017-18 NH/2013-14/8980,Parks,Completed,NH-ANNA NAGAR,101,998000,"ANNUAL MAINTENANCE OF BOUGAINVILLA PARK,C BLOCK PARK,2 nd MAIN ROAD PARK AT DN.101,U-22,Z-8.(For the period of one year)",Own Sources,8,2013-14,2016-17 B/2013-14/15485,Buildings,Completed,RC-Regional office - Central,102,11100000,"CONSTRUCTION OF COMMUNITY CENTER AT T.P.CHATRAM MAIN ROAD IN DN-102,ZONE-8",MLACDS,8,2013-14,2016-17 B/2013-14/21553,Buildings,Completed,B-Buildings,103,13000000,"CONSTRUCTION OF MULTIPURPOSE HALL AT KUMMALAMMAN KOIL ST, KILPAUK IN DN.103,ZONE-8",MPLADS,8,2013-14,2016-17 NJ/2013-14/16205,Roads,Completed,NJ-TEYNAMPET,110,3046200,"Providing Centre Median with Granite Stone at Harrington Road in Division 110, Unit 24,Zone IX",Own Sources,9,2013-14,2016-17 NJ/2013-14/16261,Footpath,Completed,NJ-TEYNAMPET,110,29210000,"PROVIDING NEW GRANITE STONE KERBS AND GRANITE SLAB FOOT PATH AT HARRINGTON ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2013-14,2016-17 NJ/2013-14/16311,Parks,Completed,NJ-TEYNAMPET,110,490000,"SUPPLYING AND PLANTING ORNAMENTAL PLANTS AT HARRINGTON ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2013-14,2016-17 NJ/2013-14/16372,Roads,Completed,NJ-TEYNAMPET,110,32750000,"PROPOSED CEMENT CONCRETE ROAD AT HARRINGTON ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2013-14,2016-17 NJ/2013-14/16618,Storm Water Drain,Completed,NJ-TEYNAMPET,110,20915000,"DEMOLITION OF EXISTING SWD OF SIZE 900 MM X 900 MM AND RE CONSTRUCTION OF RCC BOX TYPE DRAIN OF SIZE 1200 X 1200 MM ALONG HARRINGTON ROAD [ SOUTH SIDE ] HARRINGTON ROAD SUBWAY TO COOUM RIVER NEAR MC. NICHOLS ROAD RBS BUILDING IN DIVISION - 110, UNIT-24, ZONE-IX.",Grants,9,2013-14,2016-17 NJ/2013-14/17711,Roads,Completed,NJ-TEYNAMPET,110,1995000,"PROVIDING ROAD MARKING AND ROAD SIGNS AT HARRINGTON ROAD IN DIVISION-110, UNIT-24, ZONE-IX",Own Sources,9,2013-14,2016-17 D/2013-14/37567,Storm Water Drain,Completed,D-Storm Water Drains,111,4000000,"Providing Waste Water Treatment plant on the banks of Nungambakkam canal near Greams Lane (Adj Appollo Hospital) Dn.111, Zone 9",Own Sources,9,2013-14,2018-19 NJ/2013-14/13679,Roads,Completed,NJ-TEYNAMPET,111,970000,"MAINTENANCE OF PARK BY PRIVATE AGANCES AT BINNY ROAD PARK and GREEMS ROAD ROAD SIDE PARK IN DIVISION-111,UNIT-24,ZONE-9.",Own Sources,9,2013-14,2016-17 NJ/2013-14/37283,Buildings,Completed,NJ-TEYNAMPET,113,999000,"SUPPLY AND FIXING NAMMA TOILET WITH SEWARAGE SA MODEL MEN (1+2) AT G.N.CHETTY ROAD IN DIV 113,U-26,ZONE -9",Own Sources,9,2013-14,2018-19 NJ/2013-14/37284,Buildings,Completed,NJ-TEYNAMPET,113,999000,"SUPPLY AND FIXING NAMMA TOILET WITH SEWARAGE SA MODEL WOMEN (1+2) AT G.N.CHETTY ROAD IN DIV 113,U-26,ZONE -9",Own Sources,9,2013-14,2018-19 BR/2013-14/25590,Footpath,Completed,SP-SPECIAL PROJECTS,114,80200000,"Dismantling of existing compound wall and re construction of compound wall with Heritage pillars, Cast-Iron grills & Cast-Iron gate and paving with granite foot path along with railing of SS pipe and Granite pedestal stones at Western side of Kamarajar Salai, Marina (From Parthasarathi Koil entrance to Presidency College ) in Divisijavascript:openMap();on -114, Zone - 9.",Own Sources,9,2013-14,2019-20 BR/2013-14/25607,Footpath,Completed,SP-SPECIAL PROJECTS,114,87400000,"Dismantling of existing compound wall and re construction of compound wall with Heritage pillars, Cast-Iron grills & Cast-Iron gate and paving with granite foot path along with railing of SS pipe and Granite pedestal stones at Western side of Kamarajar Salai, Marina (From Presidency College to Swami Sivananda Salai ) in Division -114, Zone - 9.",Own Sources,9,2013-14,2019-20 NJ/2013-14/27213,Buildings,Completed,NJ-TEYNAMPET,114,471000,"Supplying and Fixing Stainless Steel Doors at Toilet Rooms in Swimming Pool in dn-114,Unit-27,Zone-9.",Own Sources,9,2013-14,2016-17 NJ/2013-14/31464,Roads,Completed,NJ-TEYNAMPET,114,3015000,"Providing and Laying Cement Concrete Road at Adam Street in Dn-114,Unit-27,Zone-9.",Own Sources,9,2013-14,2016-17 BR/2013-14/25536,Footpath,Completed,SP-SPECIAL PROJECTS,116,71300000,"Dismantling of existing compound wall and re construction of compound wall with Heritage pillars, Cast-Iron grills & Cast-Iron gate and paving with granite foot path along with railing of SS pipe and Granite pedestal stones at Western side of Kamarajar Salai, Marina (From Teachers College entrance gate to Parthasarathi Koil entrance ) in Division -116, Zone - 9.",Own Sources,9,2013-14,2019-20 NJ/2013-14/12551,Roads,Completed,NJ-TEYNAMPET,116,2800000,"PROPOSED LAYING CEMENT CONCRETE ROAD @ NALLATHAMBI STREET IN DN-,116, U-27, Z-9.",Own Sources,9,2013-14,2016-17 NJ/2013-14/22840,Roads,Completed,NJ-TEYNAMPET,118,2150000,RELAYING THE EXISTING B.T ROAD AT SRINIVASAPERUMAL SANNATHY 1ST STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/22843,Roads,Completed,NJ-TEYNAMPET,118,1768000,RELAYING THE EXISTING B.T ROAD AT SRINIVASAPERUMAL SANNATHY 2ND STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/22844,Roads,Completed,NJ-TEYNAMPET,118,781000,RELAYING THE EXISTING B.T ROAD AT SRINIVASAPERUMAL SANNATHY 3RD STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/22846,Roads,Completed,NJ-TEYNAMPET,118,1124000,RELAYING THE EXISTING B.T ROAD AT THANDAVARAYAN STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/22848,Roads,Completed,NJ-TEYNAMPET,118,697000,RELAYING THE EXISTING B.T ROAD AT NORTH GOPALAPURAM 1ST STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/22849,Roads,Completed,NJ-TEYNAMPET,118,804000,RELAYING THE EXISTING B.T ROAD AT NORTH GOPALAPURAM 2ND STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/22895,Roads,Completed,NJ-TEYNAMPET,118,586000,RELAYING THE EXISTING B.T ROAD AT GEORGE AVENUE IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/22900,Roads,Completed,NJ-TEYNAMPET,118,1424000,RELAYING THE EXISTING B.T ROAD AT ELLAIAMMAN COLONY MAIN ROAD IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/30360,Roads,Completed,NJ-TEYNAMPET,118,700000,RELAYING THE EXISTING B.T ROAD AT ELLAIAMMAN COLONY 5TH CROSS STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 NJ/2013-14/30369,Roads,Completed,NJ-TEYNAMPET,118,700000,RELAYING THE EXISTING B.T ROAD AT ELLAIAMMAN COLONY 6TH CROSS STREET IN DN.118 UNIT.24 ZONE.9.,Own Sources,9,2013-14,2016-17 BR/2013-14/19528,Roads,Completed,BR-Bus Route Roads,122,6999000,"Proposed construction of 6Nos Modern Stainless Steel Bus Shelter at K B Dasan Road 1No (Div - 122), R.K.Mutt Road 2Nos (Div - 124), TTK Road 1No (Div - 123), Kamarajar Salai near All India Radio Bus Stop 1No (Div - 125) and Santhome High Road near KFC Restaurant 1No (Div - 126) in Zone - IX.",MLACDS,9,2013-14,2017-18 NJ/2013-14/30355,Roads,Completed,NJ-TEYNAMPET,122,2548000,"RELAYING THE ROAD WITH BCCMP 40 MM THICK WITH CAMBER CORRECTION AT CENETOPH 2ND LANE IN DIV 122,U-26,Z-9",Own Sources,9,2013-14,2016-17 NJ/2013-14/32850,Buildings,Completed,NJ-TEYNAMPET,122,1850000,CONSTRUCTION OF NNMP SHED NO 709 AT CENATOP 1ST STREET (UNDER MLA FUND) IN DIV 122 / U-26 / Z-9,Own Sources,9,2013-14,2016-17 BR/2013-14/25508,Footpath,Completed,SP-SPECIAL PROJECTS,125,92100000,"Dismantling of existing compound wall and re construction of compound wall with Heritage pillars, Cast-Iron grills & Cast-Iron gate and paving with granite foot path along with railing of SS pipe and Granite pedestal stones at Western side of Kamarajar Salai, Marina (From All India Radio to Teachers College entrance gate) in Division -125 & 126, Zone - 9.",Own Sources,9,2013-14,2019-20 BR/2013-14/33058,Roads,Completed,SP-SPECIAL PROJECTS,125,79900000,"PROPOSED IMPROVEMENTS TO THE MARINA LOOP ROAD BY LAYING CEMENT CONCRETE ROAD,FORMING CYCLE TRACK,PAVING WITH GRANITE FOOTPATH WITH RAILING OF STAINLESS STEEL PIPE AND GRANITE PEDESTAL STONE ALONG WITH CONSTRUCTION OF SWD,CONSTRUCTION OF RCC DUCT FOR SERVICE UTILITIES AND CONSTRUCTION OF UNDER GROUND DRAINAGE SYSTEM WITH PROVISIONS FOR LIGHTING ARRNGEMENTS,SOFT LANDSCAPING ETC FROM JUNCTION OF KAMARAJAR SALAI TOWARDS PATTINAPAKKAM,CHAINAGE 0M-450M,IN DIVISION-125,ZONE-IX.",Own Sources,9,2013-14,2018-19 BR/2013-14/33076,Roads,Completed,SP-SPECIAL PROJECTS,125,79200000,"PROPOSED IMPROVEMENTS TO THE MARINA LOOP ROAD BY LAYING CEMENT CONCRETE ROAD,FORMING CYCLE TRACK,PAVING WITH GRANITE FOOTPATH WITH RAILING OF STAINLESS STEEL PIPE AND GRANITE PEDESTAL STONE ALONG WITH CONSTRUCTION OF SWD,CONSTRUCTION OF RCC DUCT FOR SERVICE UTILITIES AND CONSTRUCTION OF UNDER GROUND DRAINAGE SYSTEM WITH PROVISIONS FOR LIGHTING ARRNGEMENTS,SOFT LANDSCAPING ETC FROM JUNCTION OF KAMARAJAR SALAI TOWARDS PATTINAPAKKAM,CHAINAGE 450M-850M,IN DIVISION-125,ZONE-IX.",Own Sources,9,2013-14,2018-19 BR/2013-14/33084,Roads,Completed,SP-SPECIAL PROJECTS,125,78800000,"PROPOSED IMPROVEMENTS TO THE MARINA LOOP ROAD BY LAYING CEMENT CONCRETE ROAD,FORMING CYCLE TRACK,PAVING WITH GRANITE FOOTPATH WITH RAILING OF STAINLESS STEEL PIPE AND GRANITE PEDESTAL STONE ALONG WITH CONSTRUCTION OF SWD,CONSTRUCTION OF RCC DUCT FOR SERVICE UTILITIES AND CONSTRUCTION OF UNDER GROUND DRAINAGE SYSTEM WITH PROVISIONS FOR LIGHTING ARRNGEMENTS,SOFT LANDSCAPING ETC FROM JUNCTION OF KAMARAJAR SALAI TOWARDS PATTINAPAKKAM,CHAINAGE 850M-1300M,IN DIVISION-125,ZONE-IX.",Own Sources,9,2013-14,2017-18 BR/2013-14/33129,Roads,Completed,SP-SPECIAL PROJECTS,126,88000000,"PROPOSED IMPROVEMENTS TO THE MARINA LOOP ROAD BY LAYING CEMENT CONCRETE ROAD,FORMING CYCLE TRACK,PAVING WITH GRANITE FOOTPATH WITH RAILING OF STAINLESS STEEL PIPE AND GRANITE PEDESTAL STONE ALONG WITH CONSTRUCTION OF SWD,CONSTRUCTION OF RCC DUCT FOR SERVICE UTILITIES AND CONSTRUCTION OF UNDER GROUND DRAINAGE SYSTEM WITH PROVISIONS FOR LIGHTING ARRNGEMENTS,SOFT LANDSCAPING ETC FROM JUNCTION OF KAMARAJAR SALAI TOWARDS PATTINAPAKKAM,CHAINAGE 1300M-1800M,IN DIVISION-126,ZONE-IX.",Own Sources,9,2013-14,2018-19 BR/2013-14/35712,Roads,Completed,SP-SPECIAL PROJECTS,126,68300000,"PROPOSED IMPROVEMENTS TO THE MARINA LOOP ROAD BY LAYING CEMENT CONCRETE ROAD,FORMING CYCLE TRACK,PAVING WITH GRANITE FOOTPATH WITH RAILING OF STAINLESS STEEL PIPE AND GRANITE PEDESTAL STONE ALONG WITH CONSTRUCTION OF SWD,CONSTRUCTION OF RCC DUCT FOR SERVICE UTILITIES AND CONSTRUCTION OF UNDER GROUND DRAINAGE SYSTEM WITH PROVISIONS FOR LIGHTING ARRNGEMENTS,SOFT LANDSCAPING ETC FROM JUNCTION OF KAMARAJAR SALAI TOWARDS PATTINAPAKKAM,CHAINAGE 2200M-2550M,IN DIVISION-126,ZONE-IX.",Own Sources,9,2013-14,2017-18 NK/2013-14/38585,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,216000,REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VARIOUS PLACES IN DN-127 U-29 Z-10,Own Sources,10,2013-14,2016-17 NK/2013-14/39360,Parks,Completed,NK-KODAMBAKKAM,127,847000,"Maintenance of Park 1 and 2 at Jai Nagar in DN.127,Unit-29,Zone-10.",Own Sources,10,2013-14,2016-17 L/2013-14/37109,Electrical,Completed,L-Electrical,128,115300,"Design, Supply, erection Testing and commissioning of 1 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Division Office-128, No.77 Kamarajar salai , AVM colony Virugambakkam Zone-X",Own Sources,10,2013-14,2016-17 NK/2013-14/2990,Roads,Completed,NK-KODAMBAKKAM,128,664000,"Proposed Cement Concrete Interior Road at Balammal st in Dn. 128, Unit 29, Zone 10.",Own Sources,10,2013-14,2018-19 NK/2013-14/34546,Buildings,Completed,NK-KODAMBAKKAM,128,397000,"ANNUAL MAINTENANCE OF PARK AT ANNAJI NAGAR ,2ND STREET VIRUGAMBAKKAM IN DIV 128, U 28, Z 10",Own Sources,10,2013-14,2016-17 NK/2013-14/34553,Buildings,Completed,NK-KODAMBAKKAM,128,359000,"ANNUAL MAINTENANCE OF PARK AT LAMBERT NAGAR VIRUGAMBAKKAM IN DIV 128, U 29, Z 10",Own Sources,10,2013-14,2016-17 NK/2013-14/38810,Roads,Completed,NK-KODAMBAKKAM,128,797000,"Proposed Cement Concrete Interior Road at Pallavan Salai in Dn. 128, Unit 29, Zone 10.",Own Sources,10,2013-14,2018-19 NK/2013-14/4000,Roads,Completed,NK-KODAMBAKKAM,128,1296000,"Proposed Cement Concrete Interior Road at Othavadai Street in Dn 128, U 29, Z 10",Own Sources,10,2013-14,2018-19 L/2013-14/37125,Electrical,Completed,L-Electrical,129,115300,"Design, Supply, erection Testing and commissioning of 1 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Division Office-129,No.18 arunachalam Road ,Saligrammam in Zone-X",Own Sources,10,2013-14,2016-17 NK/2013-14/25359,Parks,Completed,NK-KODAMBAKKAM,129,613000,"Maintanance Of Park for One Year at Abusali road,Navalar Main road and Pillaiyar Koil Street in DN-129,Unit-29,Zone-10.",Own Sources,10,2013-14,2018-19 L/2013-14/37127,Electrical,Completed,L-Electrical,130,115300,"Design, Supply, erection Testing and commissioning of 1 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Division office 130 Amman Koil Street chennai- 24 Zone-X",Own Sources,10,2013-14,2016-17 NK/2013-14/10295,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,Demolishing the existing Dilaphilated RCC Slab and Re-Construction of RCC Slab Over the SWD at Palani Andavar koil street in Dn-130 U-29 Z-10,Own Sources,10,2013-14,2016-17 NK/2013-14/8764,Buildings,Completed,NK-KODAMBAKKAM,130,428000,"Providing Gas Connection Arrangements and other improvements in Amma Unavagam at Nerkundram Pathai (East) in Dn. 130, Unit - 29, Zone - 10",Own Sources,10,2013-14,2017-18 L/2013-14/37129,Electrical,Completed,L-Electrical,131,115300,"Design, Supply, erection Testing and commissioning of 1 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Division office .131 No.33, Bobbli Raja Salai , K.K.Nagar ch -78 Zone-X",Own Sources,10,2013-14,2016-17 NK/2013-14/19057,Buildings,Completed,NK-KODAMBAKKAM,131,944000,"PROPOSED CONSTRUCTION OF TOILET BUILDING AND MOTOR ROOM BUILDING AT RANI ANNA NAGAR PARK IN DN 131,UNIT 28,ZONE 10",Own Sources,10,2013-14,2016-17 NK/2013-14/19063,Parks,Completed,NK-KODAMBAKKAM,131,966000,"PROVIDING GREENARY ARRANGEMENTS AND GALVANAISHED IRON SHEET SHED AT RANI ANNA NAGAR PARK IN DN 131,UNIT 28,ZONE 10",Own Sources,10,2013-14,2016-17 L/2013-14/35023,Electrical,Completed,L-Electrical,132,411600,"Replacement of damaged wiring ,Tube light fittings and Ceiling fans at various places in Corporation School and Buildings at Zone-X area",Own Sources,10,2013-14,2016-17 L/2013-14/37148,Electrical,Completed,L-Electrical,133,461400,"Design, Supply, erection Testing and commissioning of 4 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Division office , in Division - 133 Ram Colony , west mambalam Zone-X",Own Sources,10,2013-14,2016-17 L/2013-14/37150,Electrical,Completed,L-Electrical,134,1960000,"Design, Supply, erection Testing and commissioning of 17 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Zonal office , in Division - 134 No.117, NSK Salai , Kodambakkam ch .24 Zone-X",Own Sources,10,2013-14,2016-17 NK/2013-14/20591,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,869000,"DESILTING THE EXISTING S.W.D AT VARIOUS STREETS IN DIV-134,U-31,Z-10",Own Sources,10,2013-14,2016-17 NK/2013-14/26805,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,340000,IMPROVEMENTS TO STORMWATERDRAIN AT VARIOUS STREETS IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2013-14,2016-17 NK/2013-14/31551,Buildings,Completed,NK-KODAMBAKKAM,134,650000,PROVIDING AND RAISING MANHOLEDOORS ( SEWER) AT VARIOUS STREETS IN DN 134 UNIT31 ZONE 10,Own Sources,10,2013-14,2016-17 NK/2013-14/39448,Buildings,Completed,NK-KODAMBAKKAM,134,900000,"IMPROVEMENTS TO TOILET BLOCK AND FLOORING WORK TO SCHOOL BUILDING AT CMS SCHOOL IN CORPORATION COLONY IN DN-134, UNIT-31, ZONE-10",Own Sources,10,2013-14,2017-18 L/2013-14/37135,Electrical,Completed,L-Electrical,135,115300,"Design, Supply, erection Testing and commissioning of 1 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at division office , in Division - 135 ,thambia reddy road jn Bakthavatchalam street, Westmambalam,ch 33. Zone-X",Own Sources,10,2013-14,2016-17 NK/2013-14/36857,Parks,Completed,NK-KODAMBAKKAM,136,590000,"ANNUAL MAINTENANCE TO PANAGAL PARK AT BASHYAM ROAD IN DIV 136,U 30, Z 10(Employed qualified Horticulturist only)",Own Sources,10,2013-14,2016-17 NK/2013-14/37024,Parks,Completed,NK-KODAMBAKKAM,136,231000,"ANNUAL MAINTENANCE TO JEEVA PARK AT G.N CHETTY ROAD IN DIV 136,U 30, Z 10(By qualified horticulturist only)",Own Sources,10,2013-14,2016-17 NK/2013-14/33907,Buildings,Completed,NK-KODAMBAKKAM,139,960000,OPERATION AND MAINTENANCE WORK OF GASIFIRE CREMATORIUM AT SADAPET BURIYAL GROUND IN DN139 UNIT28 ZONE10,Own Sources,10,2013-14,2017-18 NK/2013-14/3342,Roads,Completed,NK-KODAMBAKKAM,140,1735000,"LAYING CEMENT CONCRETE ROAD AT SOUTH KAVARAI STREET IN DIV 140,U 30,Z 10",Own Sources,10,2013-14,2016-17 NK/2013-14/39449,Roads,Completed,NK-KODAMBAKKAM,140,449000,"ATTENDING PATCH WORK BY USING CEMENT CONCRETE AT REDDYKUPPAM SALAI, NEW STREET AND VARIOUS STREETS IN DIV-140, U-30, Z-10.",Own Sources,10,2013-14,2019-20 BR/2013-14/21839,Roads,Completed,BR-Bus Route Roads,141,23650000,"Providing and Laying Cement Concrete Road at Muthu Rangan Salai (From the jn.of New Boag Road to the jn.of Madley Road) in Ward -141, Zone - 10.",Own Sources,10,2013-14,2016-17 L/2013-14/37145,Electrical,Completed,L-Electrical,141,346100,"Design, Supply, erection Testing and commissioning of 3 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Division office , in Division - 141 , 4 th Main Road,jn 4th cross st, CIT Nagar Zone-X",Own Sources,10,2013-14,2016-17 B/2013-14/25014,Buildings,Completed,B-Buildings,142,31000000,"CONSTRUCTION OF WASHING AREA, DRYING SHED, IRONING AND REST ROOMS IN DHOBIKANA (PHASE-I) AT SAIDAPET DN-142, ZONE-X",Own Sources,10,2013-14,2017-18 B/2013-14/30930,Buildings,Completed,B-Buildings,142,35728794,"CONSTRUCTION OF WASHING AREA , DRYING SHED, IRONING AND REST ROOMS IN DHOBIKANA (PHASE-II) AT SAIDAPET DN-142, ZONE-X",Own Sources,10,2013-14,2019-20 B/2013-14/31034,Buildings,Completed,B-Buildings,142,31000000,"CONSTRUCTION OF WASHING AREA , DRYING SHED , IRONING AND REST ROOMS IN DHOBIKANA (PHASE-III) AT SAIDAPET DN-142, ZONE-X",Own Sources,10,2013-14,2019-20 L/2013-14/37133,Electrical,Completed,L-Electrical,142,115300,"Design ,Supply, erection Testing and commissioning of 1 Kwp including Warranty, operation & maintenance for 2 years of roof Top Solar PV System at Division office -142 No.2 / 12, West Jones Road , Saidapet ,chennai-15 Zone-X",Own Sources,10,2013-14,2016-17 NL/2013-14/3954,Parks,Completed,NL-VALASARAVAKKAM,143,2620000,"Forming New Park At Nolambur, Phase1, 12th cross street in Division 143, Unit 32, Zone XI.",Own Sources,11,2013-14,2017-18 NL/2013-14/8095,Buildings,Completed,NL-VALASARAVAKKAM,144,3960000,"CONSTRUCTION OF WARD COUNCILOR /DIVISION OFFICE AT POONAMALLE HIGH ROAD INSIDE VACANT LAND NEAR VILLIVAKKAM PANCHAYAT UNION SCHOOL IN DIV 144, U-32, ZONE-XI.",Own Sources,11,2013-14,2016-17 NL/2013-14/6802,Parks,Completed,NL-VALASARAVAKKAM,149,595000,"GREENARY AND MAINTENANCE OF THIRU.VI.KA PARK AT GANDHI ROAD (CHENNAI CORPORATION PARKS) FOR TWO YEAR IN DN.149, U 33, Z 11. (TO DEPLOY QUALIFIED PERSONNEL WITH DIPLOMA IN HORTICULTURE)",Own Sources,11,2013-14,2016-17 NL/2013-14/33653,Buildings,Completed,NL-VALASARAVAKKAM,150,2995000,CONSTRUCTION OF ADDITIONAL FIRST FLOOR AT CMS CHETTIAR AGARAM SCHOOL STREET IN DN.150 U.34 Z.11( MP FUND).,MPLADS,11,2013-14,2016-17 B/2013-14/15609,Buildings,Completed,B-Buildings,156,13200000,CONSTRUCTION OF GASIFIER CREMATORIUM AT MUGALIVAKKAM BURIAL GROUND IN DN 156 ZONE XII,Own Sources,12,2013-14,2017-18 NM/2013-14/13271,Storm Water Drain,Completed,NM-ALANDUR,157,805000,CONSTRUCTION OF SIDE DRAIN AT METTU COLONY 2ND STREET IN DN 157 U 35 ZONE 12,Own Sources,12,2013-14,2018-19 NM/2013-14/13276,Storm Water Drain,Completed,NM-ALANDUR,157,510000,CONSTRUCTION OF SIDE DRAIN AT METTU COLONY 3RD STREET IN DN 157 U 35 ZONE 12,Own Sources,12,2013-14,2018-19 NM/2013-14/19304,Storm Water Drain,Completed,NM-ALANDUR,157,510000,CONSTRUCTION OF SIDE DRAIN AT PILLAYAR KOIL STREET 1ST CROSS STREET IN DN 157 U 35 ZONE 12,Own Sources,12,2013-14,2016-17 NM/2013-14/19307,Storm Water Drain,Completed,NM-ALANDUR,157,322000,CONSTRUCTION OF SIDE DRAIN AT PILLAYAR KOIL STREET 4TH CROSS STREET IN DN 157 U 35 ZONE 12,Own Sources,12,2013-14,2016-17 NM/2013-14/34472,Buildings,Completed,NM-ALANDUR,157,998000,"Proposed Construction of 3+3 Seated Public Toilet Block For Councillor Fund at Periya Colony in Dn-157,U-35, Zone-12.",Own Sources,12,2013-14,2016-17 L/2013-14/11813,Electrical,Completed,L-Electrical,158,1941500,"Erection of 6 Nos of 9.5 mtr lamp post with Double straight bracket and One No 9.5 mtr pole with single straight bracket and Laying of 2483 Mtr 4x25 Sqmm cable in the place of Deteriorated cable at Mount poonamalli Road, from Kathipara Junction To Trade center,in Dn 158, Zone XII.",Own Sources,12,2013-14,2017-18 NM/2013-14/39104,Roads,Completed,NM-ALANDUR,165,1695000,"Forming,strengthening and Laying of interior road by paver finisher (Grid:3) at Surendar nagar 6th street, 4th cross street in Dn:165 Unit:37 Zone:12",Grants,12,2013-14,2016-17 NM/2013-14/39110,Roads,Completed,NM-ALANDUR,165,1118000,"FORMING ,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT Avvaiyaar Street ( Grid 3- Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39111,Roads,Completed,NM-ALANDUR,165,635000,"FORMING ,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT Vanjinathan Street (Grid 3 - Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39112,Roads,Completed,NM-ALANDUR,165,966000,"FORMING ,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT Mudhiyal Reddy Nagar 3rd Street (Grid 3 Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39113,Roads,Completed,NM-ALANDUR,165,236000,"FORMING ,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT BHARATHIDASAN NAGAR 1ST STREET( Grid 3 Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39114,Roads,Completed,NM-ALANDUR,165,1803000,"FORMING,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT BHARATHIDHASAN NAGAR MAIN ROAD (Grid 3 Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39115,Roads,Completed,NM-ALANDUR,165,683000,"FORMING ,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT Bhuvaneshwari nagar 1St Street (Grid 3 - Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39116,Roads,Completed,NM-ALANDUR,165,2756000,"FORMING ,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT Bhuvaneshwari nagar 6th Street & Gas Goodown Street (Grid 3- Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39117,Roads,Completed,NM-ALANDUR,165,417000,"FORMING ,STRENGTHENING AND LAYING THE ROAD USING PAVER FINISHER AT BHUVANESHWARI NAGAR 5TH STREET (Grid-3- Savings) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39120,Footpath,Completed,NM-ALANDUR,165,339000,"FORMING FOOTPATH (GRID-3 Savings) AT Kesari Nagar 1st main Road, IN DN 165, UNIT 37, ZONE 12.",Grants,12,2013-14,2016-17 NM/2013-14/39121,Footpath,Completed,NM-ALANDUR,165,283000,"FORMING FOOTPATH (GRID-3 Savings) AT Lakshmi Nagar 2nd Street, IN DN 165, UNIT 37, ZONE 12.",Grants,12,2013-14,2016-17 NM/2013-14/39122,Footpath,Completed,NM-ALANDUR,165,350000,"FORMING FOOTPATH (GRID- 3 Savings) AT Lakshmi Nagar 1st Street, IN DN 165, UNIT 37, ZONE 12.",Grants,12,2013-14,2016-17 NM/2013-14/39124,Footpath,Completed,NM-ALANDUR,165,283000,"FORMING FOOTPATH (GRID- 3 Savings) AT Vanjinathan Street, IN DN 165, UNIT 37, ZONE 12.",Grants,12,2013-14,2016-17 NM/2013-14/39129,Footpath,Completed,NM-ALANDUR,165,480000,"FORMING FOOTPATH (GRID-3 Savings) AT Income Tax Colony Main Road, IN DN 165, UNIT 37, ZONE 12.",Grants,12,2013-14,2016-17 NM/2013-14/39130,Footpath,Completed,NM-ALANDUR,165,180000,"FORMING FOOTPATH (GRID-3 Savings) AT Kesari Nagar 4th street , IN DN 165, UNIT 37, ZONE 12.",Grants,12,2013-14,2016-17 NM/2013-14/39131,Footpath,Completed,NM-ALANDUR,165,52000,"FORMING FOOTPATH (GRID-3 Savings) AT Lakshmi Nagar 3rd Street, IN DN 165, UNIT 37, ZONE 12.",Grants,12,2013-14,2016-17 NM/2013-14/39151,Storm Water Drain,Completed,NM-ALANDUR,165,1936000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VANCHINATHAN STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39152,Storm Water Drain,Completed,NM-ALANDUR,165,674000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT AVVAIYAR STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39153,Storm Water Drain,Completed,NM-ALANDUR,165,1760000,"DISMANTLING AND RECONSTRUCTION OF EXISTING STORM WATER DRAIN AT LAKSHMI NAGAR 1st STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39154,Storm Water Drain,Completed,NM-ALANDUR,165,1005000,"DISMANTLING AND RECONSTRUCTION OF EXISTING STORM WATER DRAIN AT LAKSHMI NAGAR 3rd STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39155,Storm Water Drain,Completed,NM-ALANDUR,165,1108000,"DISMANTLING AND RECONSTRUCTION OF EXISTING STORM WATER DRAIN AT LAKSHMI NAGAR 2nd STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39156,Storm Water Drain,Completed,NM-ALANDUR,165,1776000,"DISMANTLING AND RECONSTRUCTION OF EXISTING STORM WATER DRAIN AT KESARI NAGAR 1st MAIN ROAD IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39157,Storm Water Drain,Completed,NM-ALANDUR,165,1465000,"DISMANTLING AND RECONSTRUCTION OF EXISTING STORM WATER DRAIN AT KESARI NAGAR 4th STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39158,Storm Water Drain,Completed,NM-ALANDUR,165,1093000,"DISMANTLING AND RECONSTRUCTION OF EXISTING STORM WATER DRAIN AT MANI VASAGAM STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/39159,Storm Water Drain,Completed,NM-ALANDUR,165,826000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT RAJAJI STREET IN DIV - 165,UNIT - 37,ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/15308,Buildings,Completed,NM-ALANDUR,166,2990000,"CONSTRUCTION OF GYM BUILDING WITH GYM EQUIPMENTS (UNDER WARD COUNCILLOR FUND) AT BURMA THAMIZHAR COLONY, IN DN 166, UNIT 37, ZONE 12.",Own Sources,12,2013-14,2016-17 NM/2013-14/29720,Roads,Completed,NM-ALANDUR,167,1599000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT STATE BANK COLONY 1ST STREET ( NEAR RANGA COLONY ) IN DN 167 U 37 Z 12,Grants,12,2013-14,2016-17 NM/2013-14/29753,Roads,Completed,NM-ALANDUR,167,1128000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT STATE BANK COLONY 1ST LANE IN DN 167 U 37 Z 12,Grants,12,2013-14,2016-17 NM/2013-14/29771,Roads,Completed,NM-ALANDUR,167,1731000,"FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT STATE BANK COLONY 2ND STREET ( NEAR NEHRU NEDUN SALAI ) IN DN 167 U 37 Z 12",Grants,12,2013-14,2016-17 NM/2013-14/29795,Roads,Completed,NM-ALANDUR,167,1643000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT ESWARAN COLONY 1ST STREET IN DN 167 U 37 Z 12,Grants,12,2013-14,2016-17 NM/2013-14/29803,Roads,Completed,NM-ALANDUR,167,4226000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT ESWARAN COLONY 2ND STREET IN DN 167 U 37 Z 12,Grants,12,2013-14,2016-17 NM/2013-14/29809,Roads,Completed,NM-ALANDUR,167,1139000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER PERIYAR NAGAR ROAD ( MMTC ) IN DN 167 U 37 Z 12,Grants,12,2013-14,2016-17 NM/2013-14/30234,Roads,Completed,NM-ALANDUR,167,1966000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT LAKSHMI NAGAR 7TH STREET (4TH STAGE) IN DN-167 UNIT-37 ZONE-12,Grants,12,2013-14,2016-17 NM/2013-14/30247,Roads,Completed,NM-ALANDUR,167,3912000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT VOLTAS COLONY MAIN ROAD IN DN-167 UNIT-37 ZONE-12,Grants,12,2013-14,2016-17 NM/2013-14/30252,Roads,Completed,NM-ALANDUR,167,1912000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT AYYAPPA NAGAR 1ST STREET IN DN-167 UNIT-37 ZONE-12,Grants,12,2013-14,2016-17 NM/2013-14/30262,Roads,Completed,NM-ALANDUR,167,3483000,FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT UNION CARBIDE STREET IN DN-167 UNIT-37 ZONE-12,Grants,12,2013-14,2016-17 NM/2013-14/30518,Roads,Completed,NM-ALANDUR,167,1224000,"FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT VOLTAS COLONY 50 FEET ROAD 1ST CROSS LANE AND SECOND CROSS LANE IN DN167 , UNIT 37 , ZONE12",Grants,12,2013-14,2016-17 NM/2013-14/30520,Roads,Completed,NM-ALANDUR,167,842000,"FORMING AND LAYING OF INTERIOR ROAD BY USING PAVER FINISHER AT NANGANALLUR 6TH MAIN 1ST CROSS LANE IN DN167 , UNIT 37 , ZONE12",Grants,12,2013-14,2016-17 NM/2013-14/39219,Roads,Completed,NM-ALANDUR,167,888000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT AGS COLONY 5TH STREET IN DN 167, U 37,Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39220,Roads,Completed,NM-ALANDUR,167,1051000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT AGS COLONY 4TH STREET IN DN 167, U 37,Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39221,Roads,Completed,NM-ALANDUR,167,1130000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT AGS COLONY 3RD STREET IN DN 167, U 37,Z 12..",Grants,12,2013-14,2016-17 NM/2013-14/39222,Roads,Completed,NM-ALANDUR,167,888000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT AGS COLONY 2ND STREET IN DN 167, U 37,Z 12..",Grants,12,2013-14,2016-17 NM/2013-14/39223,Roads,Completed,NM-ALANDUR,167,2013000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT AGS COLONY 1ST STREET IN DN 167, U 37,Z 12..",Grants,12,2013-14,2016-17 NM/2013-14/39224,Roads,Completed,NM-ALANDUR,167,612000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 6th STREET IN DN 167, U 37,Z 12..",Grants,12,2013-14,2016-17 NM/2013-14/39225,Roads,Completed,NM-ALANDUR,167,751000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 5th STREET IN DN 167, U 37,Z 12..",Grants,12,2013-14,2016-17 NM/2013-14/39226,Roads,Completed,NM-ALANDUR,167,912000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 4th STREET IN DN 167, U 37,Z 12..",Grants,12,2013-14,2016-17 NM/2013-14/39227,Roads,Completed,NM-ALANDUR,167,738000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 3rd STREET IN DN 167, U 37,Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39228,Roads,Completed,NM-ALANDUR,167,1602000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 2ND STREET IN DN 167, U 37,Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39229,Roads,Completed,NM-ALANDUR,167,2101000,"WIDENING STRENGTHING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 1ST STREET IN DN 167, U 37,Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39230,Roads,Completed,NM-ALANDUR,167,2391000,FORMING AND LAYING OF INTERIOR ROAD BY PAVER FINISHER AT NANGANALLUR 100 FEET ROAD (NANGANALLUR 46TH STREET TO LAKSHMI NAGAR 10TH STREET) IN DN-167 UNIT-37 ZONE -12.,Grants,12,2013-14,2016-17 NM/2013-14/39231,Storm Water Drain,Completed,NM-ALANDUR,167,2859000,"DISMANTLING AND RECONSTRUCTION OF RCC STORM WATER DRAIN OF SIZE 600X750MM(GRID 3 SAVINGS) AT EAST MAIN ROAD IN DN 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39232,Storm Water Drain,Completed,NM-ALANDUR,167,2877000,"Construction of RCC Storm Water Drain of size 600x750mm(Grid 3 savings) at Kannan Nagar 1st Main Road in Dn 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39233,Storm Water Drain,Completed,NM-ALANDUR,167,1070000,"Construction of RCC Storm Water Drain of size 600x750mm(Grid 3 savings) at Kannan Nagar 4th Main Road in Dn 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39234,Storm Water Drain,Completed,NM-ALANDUR,167,2106000,"Construction of RCC Storm Water Drain of size 600x750mm(Grid 3 savings) at Kannan Nagar 3rd Main Road in Dn 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39235,Storm Water Drain,Completed,NM-ALANDUR,167,2475000,"Construction of RCC Storm Water Drain of size 600x750mm(Grid 3 savings) at Lakshmi Nagar 4th strage 3rd cross street in Dn 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39236,Storm Water Drain,Completed,NM-ALANDUR,167,2067000,"Construction of RCC Storm Water Drain of size 600x750mm(Grid 3 savings) at Kannan Nagar 4th street in Dn 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39241,Footpath,Completed,NM-ALANDUR,167,202000,"FORMING FOOTPATH AT KANNAN NAGAR 1ST MAIN ROAD IN DN 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39242,Footpath,Completed,NM-ALANDUR,167,202000,"FORMING FOOTPATH AT KANNAN NAGAR 4TH STREET IN DN 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NM/2013-14/39243,Footpath,Completed,NM-ALANDUR,167,238000,"FORMING FOOTPATH AT LAKSHMI NAGAR 4TH STAGE 3RD CROSS STREET IN DN 167, U 37, Z 12.",Grants,12,2013-14,2016-17 NP/2013-14/32378,Buildings,Completed,NP-PERUNGUDI,168,4700000,"CONSTRUCTION OF DIVISION OFFICE 168 AT MG NAGAR STREET ULLAGARAM IN DN-168,UNIT-42,ZONE-14",Own Sources,14,2013-14,2016-17 B/2013-14/15626,Buildings,Completed,B-Buildings,169,10300000,CONSTRUCTION OF GASIFIER CREMATORIUM AT PUZUTHIVAKKAM BURIAL GROUND IN DN 169 ZONE XIV,Own Sources,14,2013-14,2016-17 NN/2013-14/27270,Roads,Completed,NN-ADYAR,170,963000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT KALAIMAGAL NAGAR 4TH CROSS STREET IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2013-14,2016-17 NN/2013-14/27284,Roads,Completed,NN-ADYAR,170,857000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT PALAYALKARAN LANE IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2013-14,2016-17 NN/2013-14/28486,Roads,Completed,NN-ADYAR,170,1600000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT BALAJI NAGAR 2ND MAIN ROAD IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2013-14,2016-17 NN/2013-14/28489,Roads,Completed,NN-ADYAR,170,1107000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT BALAJI NAGAR 4TH CROSS STREET IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2013-14,2016-17 NN/2013-14/28492,Roads,Completed,NN-ADYAR,170,1522000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT SWAMY NATHAN STREET IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2013-14,2016-17 NN/2013-14/10338,Buildings,Completed,NN-ADYAR,174,995000,"PROPOSED CONSTRUCTION OF GENTS TOILET& URINAL BLOCK IN FIRST FLOOR AT FIFE FURLONG ROAD CORPORATION HIGH SCHOOL CAMPUS IN DN-174, UNIT-40(A). ZONE - 13.",Own Sources,13,2013-14,2017-18 NN/2013-14/2088,Roads,Completed,NN-ADYAR,174,2242000,"RAISING & RELAYING THE ROAD WITH 25mm THICK SDBC BY PAVER FINESHER AT MADHAVAN STREET IN DN 174, UNIT 40A, ZONE 13",Own Sources,13,2013-14,2016-17 NN/2013-14/28541,Roads,Completed,NN-ADYAR,174,1244000,"RAISING AND RELAYING OF ROAD WITH B.T. COURSE 30MM TK. BY USING PAVER FINISHER AT SOMASUNDARAM STREET (SANKARAN AVENUE 1st STREET) IN DN - 174, U.-40A, ZONE - 13.",Own Sources,13,2013-14,2016-17 NN/2013-14/19505,Parks,Completed,NN-ADYAR,176,373000,"AVENUE TREES ARE PLANTING WORK AT VERIER PLACES IN DIVISION-176,181 AND 182, UNIT-38,ZONE-13.",Own Sources,13,2013-14,2016-17 NN/2013-14/34574,Parks,Completed,NN-ADYAR,176,887000,"Forming Road side Park at 1st Cross street and Improvements and Water Supply to Road side park at Besant Nagar 4th Avenue in Dn-176, Unit-38, Zone-13.",Own Sources,13,2013-14,2021-22 NN/2013-14/37621,Buildings,Completed,NN-ADYAR,176,2121000,"Proposed improvements and Additional construction of Health Post at 1st Avenue, Besant Nagar in Div-176, Unit-38, Zone-13.",Own Sources,13,2013-14,2016-17 NP/2013-14/18359,Roads,Completed,NP-PERUNGUDI,183,743000,"FORMING STRENGTHENING AND LAYING BT ROAD AT VENKATESHWARA NAGAR 10TH STREET IN DIVISION-183,UNIT-41,ZONE14",Grants,14,2013-14,2016-17 NP/2013-14/18956,Roads,Completed,NP-PERUNGUDI,183,843581,"Forming strengthening and laying BT Road at venkateshvara nagar 13th street in division-183,unit-41,zone14",Grants,14,2013-14,2016-17 NP/2013-14/18960,Roads,Completed,NP-PERUNGUDI,183,3246000,"Forming strengthening and laying BT Road at venkateshvara nagar 19th street in division-183,unit-41,zone14",Grants,14,2013-14,2016-17 NP/2013-14/28008,Roads,Completed,NP-PERUNGUDI,183,996000,"FORMING STRENGTHENING AND LAYING BITUMINOUS ROAD AT KALYANI NAGAR NIMALAN STREET IN DIVISION-183,UNIT41,ZONE14",Grants,14,2013-14,2016-17 NP/2013-14/28011,Roads,Completed,NP-PERUNGUDI,183,2117000,"FORMING STRENGTHENING AND LAYING BITUMINOUS ROAD AT LAKSHMANA PERUMAL NAGAR KRISHNA STREET IN DIVISION-183,UNIT41,ZONE14",Grants,14,2013-14,2016-17 NP/2013-14/28021,Roads,Completed,NP-PERUNGUDI,183,877000,"FORMING STRENGTHENING AND LAYING BITUMINOUS ROAD AT SRI RAM AVENUE 2ND STREET IN DIVISION-183,UNIT41,ZONE14.",Grants,14,2013-14,2016-17 NP/2013-14/28027,Roads,Completed,NP-PERUNGUDI,183,946000,"FORMING STRENGTHENING AND LAYING BITUMINOUS ROAD AT SRI RAM AVENUE 5TH STREET IN DIVISION-183,UNIT41,ZONE14.",Grants,14,2013-14,2016-17 NP/2013-14/28028,Roads,Completed,NP-PERUNGUDI,183,1475000,"FORMING STRENGTHENING AND LAYING BITUMINOUS ROAD AT NATESAN COLONY IN DIVISION-183,UNIT41,ZONE14.",Grants,14,2013-14,2016-17 NP/2013-14/28030,Roads,Completed,NP-PERUNGUDI,183,1741000,"FORMING STRENGTHENING AND LAYING BITUMINOUS ROAD AT SANGAM COLONY 2ND STREET IN DIVISION-183,UNIT41,ZONE14",Grants,14,2013-14,2016-17 NP/2013-14/28681,Roads,Completed,NP-PERUNGUDI,183,2235000,"FORMING AND STRENGTHENING AND LAYING B.T. ROAD AT KAMARAJ STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2013-14,2016-17 NP/2013-14/28693,Roads,Completed,NP-PERUNGUDI,183,3229000,"FORMING AND STRENGTHENING AND LAYING B.T. ROAD AT CORNET GARDEN IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2013-14,2016-17 NP/2013-14/28694,Roads,Completed,NP-PERUNGUDI,183,1122000,"FORMING AND STRENGTHENING AND LAYING B.T. ROAD AT SRINIVASA NAGAR (EAST) IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2013-14,2016-17 NP/2013-14/18273,Roads,Completed,NP-PERUNGUDI,184,2277000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT PILLAYAR KOIL STREET IN DN 184 UT .41 .ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/18305,Roads,Completed,NP-PERUNGUDI,184,1587000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT PILLAYAR KOIL 1 ST STREET IN DN 184 UT .41 .ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/18311,Roads,Completed,NP-PERUNGUDI,184,6939000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT MAYANASALAI IN DN .184 UT.41 ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/18400,Roads,Completed,NP-PERUNGUDI,184,4637000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT ERIKKARAI SALAI IN DN 184 UT .41 .ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/18404,Roads,Completed,NP-PERUNGUDI,184,9950000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER A T TELEPHONENAGAR MAIN ROAD IN DN .184 .UT .41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18406,Roads,Completed,NP-PERUNGUDI,184,5304000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 11 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18791,Roads,Completed,NP-PERUNGUDI,184,1918000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONENAGAR 12 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18805,Roads,Completed,NP-PERUNGUDI,184,1097000,FORMING AND LAYING BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 13 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18809,Roads,Completed,NP-PERUNGUDI,184,980000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 14 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18942,Roads,Completed,NP-PERUNGUDI,184,714000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 15 TH CROSS STREET IN DN .184 UT .41 .ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18944,Roads,Completed,NP-PERUNGUDI,184,2253000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 16 TH CROSS STREET IN DN 184 UT .41 Z0NE 14,Grants,14,2013-14,2016-17 NP/2013-14/18947,Roads,Completed,NP-PERUNGUDI,184,2348000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONENAGAR 17 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18949,Roads,Completed,NP-PERUNGUDI,184,1628000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONENAGAR 18 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18980,Roads,Completed,NP-PERUNGUDI,184,631000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONENAGAR 19 TH CROSS STREET IN DN 184 UT ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18981,Roads,Completed,NP-PERUNGUDI,184,933000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 9 TH CROSS STREET IN DN 184 UT 41 .ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/18984,Roads,Completed,NP-PERUNGUDI,184,1229000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONENAGAR 10 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/18989,Roads,Completed,NP-PERUNGUDI,184,933000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 8 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/19038,Roads,Completed,NP-PERUNGUDI,184,787000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 7 TH STREET IN DN 184 .UT 41 .ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/19041,Roads,Completed,NP-PERUNGUDI,184,714000,PROVING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 6 TH CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/19043,Roads,Completed,NP-PERUNGUDI,184,535000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 5 TH CROSS STREET IN DN 184 UT 41 ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/19076,Roads,Completed,NP-PERUNGUDI,184,559000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONENAGAR 4 TH CROSS STREET IN DN 184 UT .41 ZONE .14,Grants,14,2013-14,2016-17 NP/2013-14/19083,Roads,Completed,NP-PERUNGUDI,184,981000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONE NAGAR 2 ND CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/19240,Roads,Completed,NP-PERUNGUDI,184,933000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT TELEPHONENAGAR 1 ST CROSS STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/19244,Roads,Completed,NP-PERUNGUDI,184,5525000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT NETHAJI NAGAR MAIN ROAD IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/19438,Roads,Completed,NP-PERUNGUDI,184,2990000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT THIRUVALLUVAR STREET IN DN 184 UT 41 ZONE 14,Grants,14,2013-14,2016-17 NP/2013-14/22854,Roads,Completed,NP-PERUNGUDI,186,3410000,"FORMING AND LAYING OF INTERIOR ROAD AT PILLAYAR KOIL 4TH STREET IN DN -186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/23631,Roads,Completed,NP-PERUNGUDI,186,2974000,"FORMING AND LAYING OF INTERIOR ROAD AT THIRUMALAI NAGAR MAIN ROAD (NORTH) IN DN -186, U-41, Z-14",Own Sources,14,2013-14,2016-17 NP/2013-14/23635,Roads,Completed,NP-PERUNGUDI,186,2974000,"FORMING AND LAYING OF INTERIOR ROAD AT THIRUMALAI NAGAR MAIN ROAD (SOUTH) IN DN -186, U-41, Z-14",Own Sources,14,2013-14,2016-17 NP/2013-14/28243,Roads,Completed,NP-PERUNGUDI,186,494000,"FORMING AND LAYING BT ROAD AT THIRUMALAI NAGAR ANNEX 5TH CROSS STREET IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28246,Roads,Completed,NP-PERUNGUDI,186,1861000,FORMING AND LAYING BT ROAD AT MANIKODISRINIVASAN NAGAR 4TH CROSS STREET IN DIV-186 U-41 Z-14,Own Sources,14,2013-14,2016-17 NP/2013-14/28247,Roads,Completed,NP-PERUNGUDI,186,2020000,FORMING AND LAYING BT ROAD AT THIRUMALAI NAGAR ANNEXE BHARATHI STREET DIV-186 U-41 Z-14,Own Sources,14,2013-14,2016-17 NP/2013-14/28285,Roads,Completed,NP-PERUNGUDI,186,2269000,"FORMING AND LAYING BT ROAD AT SENTHIL NAGAR 1ST CROSS STREET IN DIVISION - 186, UNIT -41,ZONE - 14",Own Sources,14,2013-14,2016-17 NP/2013-14/28286,Roads,Completed,NP-PERUNGUDI,186,1722000,"FORMING AND LAYING AT BT ROAD SENTHIL NAGAR 2ND CROSS STREET IN DIVISION - 186, UNIT - 41, ZONE - 14",Own Sources,14,2013-14,2016-17 NP/2013-14/28287,Roads,Completed,NP-PERUNGUDI,186,2019000,"FORMING AND LAYING AT BT ROAD IN SENTHIL NAGAR 8TH CROSS STREET IN DIVISION - 186, UNIT -41,ZONE -14",Own Sources,14,2013-14,2016-17 NP/2013-14/28308,Roads,Completed,NP-PERUNGUDI,186,1011000,"FORMING AND LAYING BT ROAD AT SCHOOL STREET IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28343,Roads,Completed,NP-PERUNGUDI,186,3921000,"FORMING AND LAYING AT BT ROAD VENKATESHWARA NAGAR MAIN ROAD IN DIVISION - 186, UNIT -41, ZONE - 14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28346,Roads,Completed,NP-PERUNGUDI,186,1094000,"FORMING AND LAYING AT BT ROAD THAMARAI NAGAR IN DIVISION - 186,UNIT-41,ZONE-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28349,Roads,Completed,NP-PERUNGUDI,186,2061000,"FORMING AND LAYING AT BT ROAD VARGHEES STREET IN DIVISION - 186, UNIT - 41, ZONE -14",Own Sources,14,2013-14,2016-17 NP/2013-14/28537,Roads,Completed,NP-PERUNGUDI,186,958000,"FORMING AND LAYING BT ROAD AT VEERAVANJINATHAN 2ND CROSS STREET IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28539,Roads,Completed,NP-PERUNGUDI,186,4000000,"FORMING AND LAYING BT ROAD AT KARUNANITHI STREET IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28542,Roads,Completed,NP-PERUNGUDI,186,733000,"FORMING AND LAYING BT ROAD AT NEW INDIA COLONY MAIN ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28546,Roads,Completed,NP-PERUNGUDI,186,517000,"FORMING AND LAYING BT ROAD AT NEW INDIA COLONY 3RD CROSS STREET IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28550,Roads,Completed,NP-PERUNGUDI,186,690000,"FORMING AND LAYING BT ROAD AT VEERAPANDIYAKATTABOMMAN 1ST CROSS STREET IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28566,Roads,Completed,NP-PERUNGUDI,186,298000,"FORMING AND LAYING BT ROAD AT KAMARAJAR NAGAR 14TH CROSS STREET IN DN-186, U-41, Z-14.",Own Sources,14,2013-14,2016-17 NP/2013-14/28642,Roads,Completed,NP-PERUNGUDI,186,410000,"FORMING AND LAYING AT BT ROAD RATHINAMANI NAGAR 2ND CROSS STREET IN DIVISION - 186, UNIT -41,ZONE -14",Own Sources,14,2013-14,2016-17 NP/2013-14/28651,Roads,Completed,NP-PERUNGUDI,186,410000,"FORMING AND LAYING AT BT ROAD RATHINAMANI NAGAR 3RD CROSS STREET IN DIVISION - 186, UNIT-41,ZONE -14",Own Sources,14,2013-14,2016-17 NP/2013-14/28660,Roads,Completed,NP-PERUNGUDI,186,661000,"FORMING AND LAYING AT BT ROAD THIRUMALAI NAGAR ANNEXE 6TH CROSS STREET IN DIVISION - 186, UNIT - 41, ZONE -14",Own Sources,14,2013-14,2016-17 NP/2013-14/28668,Roads,Completed,NP-PERUNGUDI,186,315000,"FORMING AND LAYING AT BT ROAD IN OOMAITHURAI 1ST CROSS STREET IN DIVISION - 186, UNIT-41,ZONE -14",Own Sources,14,2013-14,2016-17 NP/2013-14/28683,Roads,Completed,NP-PERUNGUDI,186,1077000,"FORMING AND LAYING AT BT ROAD ADIYAMAN STREET IN DIVISION - 186,UNIT-41,ZONE-14",Own Sources,14,2013-14,2016-17 NP/2013-14/28695,Roads,Completed,NP-PERUNGUDI,186,1011000,"FORMING AND LAYING AT BT ROAD IN PANCHAYAT MAIN ROAD 3RD CROSS STREET IN DIVISION - 186, UNIT-41,ZONE -14",Own Sources,14,2013-14,2016-17 NP/2013-14/31198,Roads,Completed,NP-PERUNGUDI,186,2153000,"FORMING AND LAYING OF INTERIOR ROAD AT RAJALAKSHMI AVENUE 5TH CROSS STREET IN DN-186,U-41,Z-14",Own Sources,14,2013-14,2016-17 NP/2013-14/28669,Roads,Completed,NP-PERUNGUDI,189,1645000,"Forming,strengthing and laying the road at Kavimani St to VGP Shanthi Nagar (Church Avenue) REACH-1 in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28679,Roads,Completed,NP-PERUNGUDI,189,1193000,"Forming,strengthing and laying the road at Labour Colony 2nd Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28680,Roads,Completed,NP-PERUNGUDI,189,1251000,"Forming,strengthing and laying the road at Labour Colony 1st Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28682,Roads,Completed,NP-PERUNGUDI,189,1193000,"Forming,strengthing and laying the road at Labour Colony 3rd Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28684,Roads,Completed,NP-PERUNGUDI,189,2677000,"Forming,strengthing and laying the road at Labour Colony 4th Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28685,Roads,Completed,NP-PERUNGUDI,189,703000,"Forming,strengthing and laying the road at Labour Colony 5th St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28686,Roads,Completed,NP-PERUNGUDI,189,1163000,"Forming,strengthing and laying the road at Labour Colony 6th St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28688,Roads,Completed,NP-PERUNGUDI,189,2368000,"Forming,strengthing and laying the road at Ma.Po.Si Nagar 1st St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/28689,Roads,Completed,NP-PERUNGUDI,189,1543000,"Forming,strengthing and laying the road at Ma.Po.Si Nagar 2nd St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29918,Roads,Completed,NP-PERUNGUDI,190,1193000,"Forming,strengthing and laying the road at Bharathidasan 1st Street Extn., in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29920,Roads,Completed,NP-PERUNGUDI,190,1987000,"Forming,strengthing and laying the road at Bharathidasan 2nd Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29922,Roads,Completed,NP-PERUNGUDI,190,622000,"Forming,strengthing and laying the road at Bharathidasan 2nd Street Extn., in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29924,Roads,Completed,NP-PERUNGUDI,190,1767000,"Forming,strengthing and laying the road at Bharathidasan 1st Street ? 1st Cross Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29926,Roads,Completed,NP-PERUNGUDI,190,1379000,"Forming,strengthing and laying the road at Bharathidasan 1st Street ? 2nd Cross Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29928,Roads,Completed,NP-PERUNGUDI,190,1067000,"Forming,strengthing and laying the road at Bharathidasan 1st Street ? 3rd Cross Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29929,Roads,Completed,NP-PERUNGUDI,190,428000,"Forming,strengthing and laying the road at Bharathidasan 1st Street ? 4th Cross Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29931,Roads,Completed,NP-PERUNGUDI,190,294000,"Forming,strengthing and laying the road at Bharathidasan 1st Street ? 5th Cross Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29932,Roads,Completed,NP-PERUNGUDI,190,169000,"Forming,strengthing and laying the road at Bharathidasan 1st Street ? 6th Cross Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29937,Roads,Completed,NP-PERUNGUDI,190,395000,"Forming,strengthing and laying the road at Bharathidasan 1st Street ? 7th Cross Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29938,Roads,Completed,NP-PERUNGUDI,190,1205000,"Forming,strengthing and laying the road at Bharathidasan Well Approach Road in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/29941,Roads,Completed,NP-PERUNGUDI,190,1197000,"Forming,strengthing and laying the road at Bharathiyar Street in Dn -190,Unit- 43, Zone- XIV",Grants,14,2013-14,2016-17 NP/2013-14/4851,Buildings,Completed,NP-PERUNGUDI,190,24000,"Providing street furnitures at Varadharajapuram 4 th street in Division 190 ,Unit-43, Zone: XIV",Loans And Grants,14,2013-14,2016-17 D/2013-14/22670,Storm Water Drain,Completed,D-Storm Water Drains,192,5808000,"Construction of storm water drain of size 900x900mm along Rajenda Nagar main road (R1) from Rajendra Nagar 1st main road to Rajendra Nagar 9th street in Dn.192, Zone XV",JNNURM,15,2013-14,2016-17 D/2013-14/19281,Storm Water Drain,Completed,D-Storm Water Drains,193,25220000,"Construction of Storm water drain of size 1200 x 1200mm along Anandh nagar and Vinayagar nagar main road from Vinayar nagar 1st cross street to Pallikaranai marsh land in Dn-193,zone-15",JNNURM,15,2013-14,2016-17 NQ/2013-14/31550,Roads,Completed,NQ-SHOZHINGANALLUR,195,2304000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR 2ND MAIN ROAD (260m TO 520m) IN DN195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31561,Roads,Completed,NQ-SHOZHINGANALLUR,195,2304000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR 2ND MAIN ROAD (0 TO 260m) IN DN195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31592,Roads,Completed,NQ-SHOZHINGANALLUR,195,2119000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR 4TH 5TH 6TH CROSS STREET IN DN195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31594,Roads,Completed,NQ-SHOZHINGANALLUR,195,2119000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR 7 TH HCROSS STREET IN DN195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31595,Roads,Completed,NQ-SHOZHINGANALLUR,195,2119000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR 8TH 9TH CROSS STREET IN DN195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31597,Roads,Completed,NQ-SHOZHINGANALLUR,195,2304000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR 10TH 11TH CROSS STREET IN DN195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31637,Roads,Completed,NQ-SHOZHINGANALLUR,195,2396000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR MAIN ROAD AND 14TH CROSS STREET IN DN 195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31944,Roads,Completed,NQ-SHOZHINGANALLUR,195,2304000,FORMING AND LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR 12TH 13TH CROSS STREET IN DN 195,Own Sources,15,2013-14,2016-17 NQ/2013-14/31894,Roads,Completed,NQ-SHOZHINGANALLUR,197,4910000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 4th Cross Street Reach-1 (ch-0 to 200m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 NQ/2013-14/31896,Roads,Completed,NQ-SHOZHINGANALLUR,197,4910000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 4th Cross Street Reach-2 (ch-200 to 400m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 NQ/2013-14/31897,Roads,Completed,NQ-SHOZHINGANALLUR,197,3430000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 5th Cross Street Reach-1 (ch-0 to 140m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 NQ/2013-14/31899,Roads,Completed,NQ-SHOZHINGANALLUR,197,3430000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 5th Cross Street Reach-2 (ch-140 to 280m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 NQ/2013-14/31900,Roads,Completed,NQ-SHOZHINGANALLUR,197,3330000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 5th Cross Street Reach-3 (ch-280 to 415m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 NQ/2013-14/31901,Roads,Completed,NQ-SHOZHINGANALLUR,197,3880000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 6th Cross Street Reach-1 (ch-0 to 160m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 NQ/2013-14/31903,Roads,Completed,NQ-SHOZHINGANALLUR,197,3880000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 6th Cross Street Reach-2 (ch-160 to 320m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 NQ/2013-14/31905,Roads,Completed,NQ-SHOZHINGANALLUR,197,3880000,"Stabilization of Soil and Forming and Laying B.T. Road with Paver Finisher at Classic farm 6th Cross Street Reach-3 (ch-320 to 480m) Sholinganallur in Dn-197, U- 45, Zone -XV.",Own Sources,15,2013-14,2016-17 J/2013-14/17898,ROB,Completed,J-Bridges,,42062000,Repairs and Improvements to Kodambakkam Over bridge in Divisions 110 134 Zone IX X,Own Sources,Greater Chennai Corporation,2013-14,2016-17 J/2013-14/33658,Bridges,Completed,J-Bridges,,10840000,"Relaying of Wearing Coat and Epoxy Painting to the Existing Kodambakkam Over bridge in Divisions 110 & 134, Zone ? IX & X",Own Sources,Greater Chennai Corporation,2013-14,2017-18 NA/2014-15/15839,Buildings,Completed,NA-THIRUVOTTIYUR,1,2935000,"DISMANTLING AND RECONSTRUCTION OF EXISTING DAMAGED COMPOUND WALL AT S.V.M. NAGAR BURIAL GROUND IN DN - 01, UNIT - 02, ZONE - 01.",Own Sources,1,2014-15,2016-17 NA/2014-15/16410,Buildings,Completed,NA-THIRUVOTTIYUR,1,850000,"REPLACING EXISTING DILAPIDATED BUS SHELTER BY CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER OF SIZE 6.00 X 2.50 M AT THALANKUPPAM, K.H. ROAD IN DN - 01, UNIT - 01, ZONE - 01.( COUNCILLOR FUND 2014 - 15 )",Own Sources,1,2014-15,2017-18 NA/2014-15/27114,Roads,Completed,NA-THIRUVOTTIYUR,1,1072000,"LAYING CEMENT CONCRETE ROAD TO NETTUKUPPAM MAIN ROAD (NETTUKUPPAM 1 STREET TO 5 STREET) IN DN - 01, U - 01, ZONE- 01.",Own Sources,1,2014-15,2016-17 NA/2014-15/27116,Roads,Completed,NA-THIRUVOTTIYUR,1,704000,"LAYING CEMENT CONCRETE ROAD TO NETTUKUPPAM BEACH ROAD IN DN - 01, U - 01, ZONE- 01.",Own Sources,1,2014-15,2016-17 NA/2014-15/27120,Roads,Completed,NA-THIRUVOTTIYUR,1,684000,"LAYING CEMENT CONCRETE ROAD TO NETTUKUPPAM CHINNAMMAN KOIL 2 ND STREET IN DN - 01, UNIT -01,ZONE - 01.",Own Sources,1,2014-15,2016-17 NA/2014-15/27125,Roads,Completed,NA-THIRUVOTTIYUR,1,691000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM CHINNAMMAN KOIL 3rd STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27133,Roads,Completed,NA-THIRUVOTTIYUR,1,569000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM CHINNAMMAN KoIL 4Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27134,Roads,Completed,NA-THIRUVOTTIYUR,1,651000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM CHINNAMMAN KOIL 5Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27135,Roads,Completed,NA-THIRUVOTTIYUR,1,451000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM COLONY ROAD STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27137,Roads,Completed,NA-THIRUVOTTIYUR,1,1042000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM BAJANAI KOIL STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27139,Roads,Completed,NA-THIRUVOTTIYUR,1,398000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM AMMAN KOIL MAIN St TO BAJANAI KOIL STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27142,Roads,Completed,NA-THIRUVOTTIYUR,1,336000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM BEACH ROAD CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27143,Roads,Completed,NA-THIRUVOTTIYUR,1,216000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM BEACH ROAD 2ND CROSS St STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27146,Roads,Completed,NA-THIRUVOTTIYUR,1,378000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM COLONY ROAD TO BEACH ROAD IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27148,Roads,Completed,NA-THIRUVOTTIYUR,1,1651000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM BEACH ROAD IN DIVISION-1,UNIT-1,ZONE-1 .",Own Sources,1,2014-15,2016-17 NA/2014-15/27149,Roads,Completed,NA-THIRUVOTTIYUR,1,343000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 1st CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27150,Roads,Completed,NA-THIRUVOTTIYUR,1,224000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 2nd CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27153,Roads,Completed,NA-THIRUVOTTIYUR,1,300000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 3rd CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27198,Roads,Completed,NA-THIRUVOTTIYUR,1,234000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM 1st CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27201,Roads,Completed,NA-THIRUVOTTIYUR,1,214000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM 2nd CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27203,Roads,Completed,NA-THIRUVOTTIYUR,1,205000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM 3rd CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27205,Roads,Completed,NA-THIRUVOTTIYUR,1,267000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM 4th CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27217,Roads,Completed,NA-THIRUVOTTIYUR,1,1088000,"LAYING CEMENT CONCRETE ROAD AT SATHYAVANIMUTHU NAGAR 7 th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27218,Roads,Completed,NA-THIRUVOTTIYUR,1,1065000,"LAYING CEMENT CONCRETE ROAD AT THIRUVALLUVAR NAGAR 2 nd STREET IN DIVISION-01, UNIT-1, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/27222,Roads,Completed,NA-THIRUVOTTIYUR,1,1226000,"LAYING CEMENT CONCRETE ROAD AT SATHYAVANIMUTHU NAGAR 14 th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27227,Roads,Completed,NA-THIRUVOTTIYUR,1,546000,"LAYING CEMENT CONCRETE ROAD AT SATHYAVANIMUTHU NAGAR 15 th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27232,Roads,Completed,NA-THIRUVOTTIYUR,1,536000,"LAYING CEMENT CONCRETE ROAD AT SATHYAVANIMUTHU NAGAR 15 th STREET 1st CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27233,Roads,Completed,NA-THIRUVOTTIYUR,1,491000,"LAYING CEMENT CONCRETE ROAD AT SATHAYAVANIMUTHU NAGAR 15 th STREET 2 nd CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27236,Roads,Completed,NA-THIRUVOTTIYUR,1,521000,"LAYING CEMENT CONCRETE ROAD AT SATHYAVANIMUTHU NAGAR 16 th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27239,Roads,Completed,NA-THIRUVOTTIYUR,1,913000,"LAYING CEMENT CONCRETE ROAD AT SATHYAVANIMUTHU NAGAR 17St STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27244,Roads,Completed,NA-THIRUVOTTIYUR,1,568000,"LAYING CEMENT CONCRETE ROAD AT ULAGANATHAPURAM 3rd STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27259,Roads,Completed,NA-THIRUVOTTIYUR,1,817000,"LAYING CEMENT CONCRETE ROAD AT ULAGANATHAPURAM 4Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27261,Roads,Completed,NA-THIRUVOTTIYUR,1,790000,"LAYING CEMENT CONCRETE ROAD AT ULAGANATHAPURAM 5Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27265,Roads,Completed,NA-THIRUVOTTIYUR,1,881000,"LAYING CEMENT CONCRETE ROAD AT ULAGANATHAPURAM 8Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27268,Roads,Completed,NA-THIRUVOTTIYUR,1,279000,"LAYING CEMENT CONCRETE ROAD AT ULAGANATHAPURAM 5Th CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1 .",Own Sources,1,2014-15,2016-17 NA/2014-15/27271,Roads,Completed,NA-THIRUVOTTIYUR,1,267000,"LAYING CEMENT CONCRETE ROAD AT ULAGANATHAPURAM 6Th CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27277,Roads,Completed,NA-THIRUVOTTIYUR,1,216000,"LAYING CEMENT CONCRETE ROAD AT ULAGANATHAPURAM 7th CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27281,Roads,Completed,NA-THIRUVOTTIYUR,1,469000,"LAYING CEMENT CONCRETE ROAD AT MUGATHUVARAKUPPAM 4Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27287,Roads,Completed,NA-THIRUVOTTIYUR,1,533000,"LAYING CEMENT CONCRETE ROAD AT MUGATHUVARAKUPPAM 5Th STREET IN DIVISION-1,UNIT-1,ZONE-1 .",Own Sources,1,2014-15,2016-17 NA/2014-15/27289,Roads,Completed,NA-THIRUVOTTIYUR,1,242000,"LAYING CEMENT CONCRETE ROAD AT MUGATHUVARAKUPPAM 5Th CROSS STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27294,Roads,Completed,NA-THIRUVOTTIYUR,1,872000,"LAYING CEMENT CONCRETE ROAD AT ENNOREKUPPAM 4th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27296,Roads,Completed,NA-THIRUVOTTIYUR,1,473000,"LAYING CEMENT CONCRETE ROAD AT ENNOREKUPPAM 5Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27298,Roads,Completed,NA-THIRUVOTTIYUR,1,927000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 1st STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27299,Roads,Completed,NA-THIRUVOTTIYUR,1,908000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 2nd STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27302,Roads,Completed,NA-THIRUVOTTIYUR,1,1129000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 3rd STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27304,Roads,Completed,NA-THIRUVOTTIYUR,1,1066000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 4Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27305,Roads,Completed,NA-THIRUVOTTIYUR,1,667000,"LAYING CEMENT CONCRETE ROAD AT NETTTUKUPPAM 5Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27307,Roads,Completed,NA-THIRUVOTTIYUR,1,812000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM 6Th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27418,Roads,Completed,NA-THIRUVOTTIYUR,1,560000,"LAYING CEMENT CONCRETE ROAD AT THALANGKUPPAM 4 th STREET IN DIVISION - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27426,Roads,Completed,NA-THIRUVOTTIYUR,1,526000,"LAYING CEMENT CONCRETE AT THALANGKUPPAM 3 rd STREET IN DIVISION - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27435,Roads,Completed,NA-THIRUVOTTIYUR,1,1377000,"LAYING CEMENT CONCRETE ROAD AT ENNOREKUPPAM 2nd ST IN DIVISION - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27438,Roads,Completed,NA-THIRUVOTTIYUR,1,1147000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT ULAGANATHAPURAM 7 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27440,Roads,Completed,NA-THIRUVOTTIYUR,1,1300000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT ULAGANATHAPURAM 6 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27442,Roads,Completed,NA-THIRUVOTTIYUR,1,1212000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT ULAGANATHAPURAM 2 nd CROSS STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27445,Roads,Completed,NA-THIRUVOTTIYUR,1,791000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT ULAGANATHAPURAM 2 nd STREET IN DN - 1, UNIT -1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27448,Roads,Completed,NA-THIRUVOTTIYUR,1,1229000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 18 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27450,Roads,Completed,NA-THIRUVOTTIYUR,1,2232000,"STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 13 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27452,Roads,Completed,NA-THIRUVOTTIYUR,1,2100000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 12 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27455,Roads,Completed,NA-THIRUVOTTIYUR,1,2100000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 11 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27458,Roads,Completed,NA-THIRUVOTTIYUR,1,2080000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 10 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27459,Roads,Completed,NA-THIRUVOTTIYUR,1,1407000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 8 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27461,Roads,Completed,NA-THIRUVOTTIYUR,1,1407000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 6 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27462,Roads,Completed,NA-THIRUVOTTIYUR,1,1407000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 5 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27463,Roads,Completed,NA-THIRUVOTTIYUR,1,1405000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 4 th STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27464,Roads,Completed,NA-THIRUVOTTIYUR,1,1405000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 3 rd STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27465,Roads,Completed,NA-THIRUVOTTIYUR,1,1970000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER SATHYAVANIMUTHU NAGAR 2nd STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27466,Roads,Completed,NA-THIRUVOTTIYUR,1,1410000,"STRENGTHENING AND RELAYING BT ROAD BY PAVER FINISHER AT SATHYAVANIMUTHU NAGAR 1st STREET IN DN - 1, UNIT - 1, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27474,Roads,Completed,NA-THIRUVOTTIYUR,1,817000,"LAYING CEMENT CONCRETE ROAD AT ENNOREKUPPAM 3rd STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/30893,Buildings,Completed,NA-THIRUVOTTIYUR,1,875000,"CONSTRUCTION OF PUBLIC CONVEINANCE AT THALANKUPPAM BEACH ROAD IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26261,Roads,Completed,NA-THIRUVOTTIYUR,2,347000,"Concrete Road laying in Chinnakuppam 1st street in Dn-2, Unit-1 and Zone-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27316,Roads,Completed,NA-THIRUVOTTIYUR,2,492000,"Concrete Road laying in Chinnakuppam 1st cross in Dn-2, Unit-1 and Zone-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27317,Roads,Completed,NA-THIRUVOTTIYUR,2,221000,"Concrete Road laying in Chinnakuppam 2nd street in Dn-2, Unit-1 and Zone-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27318,Roads,Completed,NA-THIRUVOTTIYUR,2,387000,"Concrete Road laying in Chinnakuppam 2nd cross street in Dn-2, Unit-1 and Zone-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27319,Roads,Completed,NA-THIRUVOTTIYUR,2,551000,"Concrete Road laying in Chinnakuppam 3rd cross street in Dn-2, Unit-1 and Zone-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27320,Roads,Completed,NA-THIRUVOTTIYUR,2,294000,"Concrete Road laying in Chinnakuppam 3rd street in Dn-2, Unit-1 and Zone-1",Own Sources,1,2014-15,2016-17 NA/2014-15/31107,Buildings,Completed,NA-THIRUVOTTIYUR,3,999000,"Improvements To Anganwadi Building(NNMP Shed) Centre No.20 at Sakthipuram 2nd Street in Div-5, Unit-02, Zone-01.(Councillar Fund 2015-16)",Own Sources,1,2014-15,2016-17 NA/2014-15/25869,Roads,Completed,NA-THIRUVOTTIYUR,4,1087000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT VP NAGAR 1ST STREET N/S IN DN-.4 , UNIT-1, ZONE-1.L=205 W=3..40",Own Sources,1,2014-15,2016-17 NA/2014-15/26056,Roads,Completed,NA-THIRUVOTTIYUR,4,3603000,"Forming, strengthening and Laying Paver finisher Bituminous road @ Thiruveethiamman koil (A.D.Colony) 8th street,Eranavoor in Div -4, unit- 1, zone - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27004,Roads,Completed,NA-THIRUVOTTIYUR,4,900000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT VP NAGAR 5TH STREET N/S IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27005,Roads,Completed,NA-THIRUVOTTIYUR,4,113000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT 1st GANDGHI NAGAR 2nd STREET,DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27008,Roads,Completed,NA-THIRUVOTTIYUR,4,357000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT BAJANAI KOIL 2nd CROSS STREET IN DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27010,Roads,Completed,NA-THIRUVOTTIYUR,4,313000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT Mullai Nagar 2nd cross st IN DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27011,Roads,Completed,NA-THIRUVOTTIYUR,4,702000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT BHAJANAI KOIL 1ST CROSS STREET N/S IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27012,Roads,Completed,NA-THIRUVOTTIYUR,4,115000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT Mangalliamman koil school 2nd Cross St ,Eranavoor, IN DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27013,Roads,Completed,NA-THIRUVOTTIYUR,4,392000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT METTU 1ST STREET IN DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27014,Roads,Completed,NA-THIRUVOTTIYUR,4,330000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT RAMANATHAPURAM 8 th STREET IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27018,Roads,Completed,NA-THIRUVOTTIYUR,4,716000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT RAMANATHAPURAM 9th STREET N/S IN DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27019,Roads,Completed,NA-THIRUVOTTIYUR,4,377000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT MULLAI NAGAR 4th CROSS STREET N/S IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27020,Roads,Completed,NA-THIRUVOTTIYUR,4,1181000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT Ist GANDHI NAGAR 1 st STREET,ERANAVOOR IN DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27078,Roads,Completed,NA-THIRUVOTTIYUR,4,1156000,"Forming, strengthening and Laying Bituminous road @ Thiruveethiamman koil (A.D.Colony)15th street,Eranavoor in Div -4, unit- 1, zone - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27255,Roads,Completed,NA-THIRUVOTTIYUR,4,238000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT BRINDAVAN NAGAR EXTN 3rd STREET ,ERANAVOOR IN DN-.4 , UNIT-1, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27256,Roads,Completed,NA-THIRUVOTTIYUR,4,567000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT 2nd GANDHI NAGAR 3rd STREET ,ERANAVOOR IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27258,Roads,Completed,NA-THIRUVOTTIYUR,4,163000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT 1ST GANDHI NAGAR 3rd STREET,ERANVOOR IN DN-.4 , UNIT-1, ZONE-1,",Own Sources,1,2014-15,2016-17 NA/2014-15/27262,Roads,Completed,NA-THIRUVOTTIYUR,4,223000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT BRINDHAVAN NAGAR EXTN. 2ND 2ND C/ST IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27263,Roads,Completed,NA-THIRUVOTTIYUR,4,162000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT 2ND GANDHI NAGAR 1ST STREET IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27264,Roads,Completed,NA-THIRUVOTTIYUR,4,284000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT VASANTHAM NAGAR IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27266,Roads,Completed,NA-THIRUVOTTIYUR,4,162000,"FORMING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT 2ND GANDHI NAGAR 2ND STREET N/S IN DN-.4 , UNIT-1, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/28124,Roads,Completed,NA-THIRUVOTTIYUR,4,368000,"strengthening and Laying the BT road paver finisher @ Ramanathapuram 7th street in Div -4, unit- 1, zone - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/12345,Roads,Completed,NA-THIRUVOTTIYUR,5,422000,"Relaying the BT Road by Paver finisher at Manikkam nagar 1st street IN DN.5, UNIT-2, ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/15240,Parks,Completed,NA-THIRUVOTTIYUR,5,339000,"ANNUAL MAINTENANCE OF PARK AT HANSA GARDEN OSR LAND IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/15244,Parks,Completed,NA-THIRUVOTTIYUR,5,420000,"ANNUAL MAINTENANCE OF PARK AT SAKTHIPURAM (SRI RANGAM NEW TOWN) IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/15266,Parks,Completed,NA-THIRUVOTTIYUR,5,323000,"ANNUAL MAINTENANCE OF PARK AT ALL CARGO LOGISTIC COMPANY OSR LAND IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/16679,Roads,Completed,NA-THIRUVOTTIYUR,5,6840000,"FORMING AND STRENGTHENING BT ROAD AT NAITHAL NAGAR MAIN STREET IN DN - 05, UNIT - 02, ZONE - 01.",Grants,1,2014-15,2016-17 NA/2014-15/19112,Roads,Completed,NA-THIRUVOTTIYUR,5,949000,"Strengthening and Relaying the BT Road by Paver Finisher at Palagai Thotti Kuppam 1st Street in Dn 5, Unit 2, Zone 1 L = 90 M, W = 5.00 M, A = 450 SQM",Own Sources,1,2014-15,2016-17 NA/2014-15/19115,Roads,Completed,NA-THIRUVOTTIYUR,5,1394000,"Strengthening and Relaying the BT Road by Paver Finisher at Palagai Thotti Kuppam 2nd Street in Dn 5, Unit 2, Zone 1 L = 170 M, W = 4.00 M, A = 680 SQM",Own Sources,1,2014-15,2016-17 NA/2014-15/19118,Roads,Completed,NA-THIRUVOTTIYUR,5,493000,"Strengthening and Relaying the BT Road by Paver Finisher at Palagai Thotti Kuppam cross Street in Dn 5, Unit 2, Zone 1 L=60M W= 4.00, A = 240",Own Sources,1,2014-15,2016-17 NA/2014-15/26297,Roads,Completed,NA-THIRUVOTTIYUR,5,156000,"LAYING CEMENT CONCRETE ROAD AT MANIKKAM NAGAR EXTENSION IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26650,Roads,Completed,NA-THIRUVOTTIYUR,5,610000,"LAYING CEMENT CONCRETE ROAD AT VIVEGANADHAN STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26930,Roads,Completed,NA-THIRUVOTTIYUR,5,238000,"LAYING CEMENT CONCRETE ROAD AT Subway service road South side IN DN-5,UNIT-2,Z",Own Sources,1,2014-15,2016-17 NA/2014-15/26932,Roads,Completed,NA-THIRUVOTTIYUR,5,486000,"LAYING CEMENT CONCRETE ROAD AT North Bharathiyar Nagar 4th street IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26933,Roads,Completed,NA-THIRUVOTTIYUR,5,408000,"LAYING CEMENT CONCRETE ROAD AT North Bharathiyar Nagar 3rd street IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26934,Roads,Completed,NA-THIRUVOTTIYUR,5,435000,"LAYING CEMENT CONCRETE ROAD AT North Bharathiyar Nagar 2nd street IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26935,Roads,Completed,NA-THIRUVOTTIYUR,5,554000,"LAYING CEMENT CONCRETE ROAD AT GANDHI NAGAR EXTN IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26936,Roads,Completed,NA-THIRUVOTTIYUR,5,423000,"LAYING CEMENT CONCRETE ROAD AT SRI NAGAR IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26937,Roads,Completed,NA-THIRUVOTTIYUR,5,466000,"LAYING CEMENT CONCRETE ROAD AT THIRUMALAI NAGAR IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26938,Roads,Completed,NA-THIRUVOTTIYUR,5,139000,"LAYING CEMENT CONCRETE ROAD AT THIRU NAGAR MARVAADI QUARTRES 2ND STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26939,Roads,Completed,NA-THIRUVOTTIYUR,5,244000,"LAYING CEMENT CONCRETE ROAD AT THIRU NAGAR MARVAADI QUARTRES 1ST STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26940,Roads,Completed,NA-THIRUVOTTIYUR,5,729000,"LAYING CEMENT CONCRETE ROAD AT THIRU NAGAR EXTN 2ND STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26941,Roads,Completed,NA-THIRUVOTTIYUR,5,600000,"LAYING CEMENT CONCRETE ROAD AT THIRU NAGAR 1ST STREET EXTN IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26942,Roads,Completed,NA-THIRUVOTTIYUR,5,355000,"LAYING CEMENT CONCRETE ROAD AT PHALAGAI THOTTI KUPPAM 5TH STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26943,Roads,Completed,NA-THIRUVOTTIYUR,5,723000,"LAYING CEMENT CONCRETE ROAD AT PHALAGAI THOTTI KUPPAM 4TH STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26944,Roads,Completed,NA-THIRUVOTTIYUR,5,723000,"LAYING CEMENT CONCRETE ROAD AT PALAGAI THOTTI KUPPAM 3RD STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26945,Roads,Completed,NA-THIRUVOTTIYUR,5,564000,"LAYING CEMENT CONCRETE ROAD AT PHOOMPUGAR NAGAR 3RD STREET IN DN-5,UNIT-2,ZONE-1 L=130M W=3.50M A=455 SQM CPITAL 2015-16",Own Sources,1,2014-15,2016-17 NA/2014-15/26946,Roads,Completed,NA-THIRUVOTTIYUR,5,564000,"LAYING CEMENT CONCRETE ROAD AT PHOOMPUGAR NAGAR 2ND STREET STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26947,Roads,Completed,NA-THIRUVOTTIYUR,5,564000,"LAYING CEMENT CONCRETE ROAD AT POOMPUGAR NAGAR 1ST STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26948,Roads,Completed,NA-THIRUVOTTIYUR,5,430000,"LAYING CEMENT CONCRETE ROAD AT KALAINGAR NAGAR 2ND STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26949,Roads,Completed,NA-THIRUVOTTIYUR,5,673000,"LAYING CEMENT CONCRETE ROAD AT KALAINGAR NAGAR 1ST STREEET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26962,Roads,Completed,NA-THIRUVOTTIYUR,5,2200000,"Strengthening and Relaying the BT Road by Paver Finisher at Pattinathar kovil street in Dn 9, Unit 2, Zone 1",Own Sources,1,2014-15,2016-17 NA/2014-15/27032,Roads,Completed,NA-THIRUVOTTIYUR,5,28500,"LAYING CEMENT CONCRETE ROAD AT MALLIGA PURAM 1ST LANE IN DN-14,UNIT-3,ZONE-1. (L=10.00,W=2.00M,Area=20.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/28056,Roads,Completed,NA-THIRUVOTTIYUR,5,134000,"Strengthening and Relaying the BT Road by Paver Finisher at Manikkam Nagar 3rd cross Street in Dn 5, Unit 2, Zone 1 L=74M W= 4.00, A =296 sqm",Own Sources,1,2014-15,2016-17 NA/2014-15/28057,Roads,Completed,NA-THIRUVOTTIYUR,5,172000,"Relaying the BT Road by Paver Finisher at Manikkam Nagar 1st cross Street in Dn 5, Unit 2, Zone 1 L=95.00M W= 4.00, A = 380 sqm",Own Sources,1,2014-15,2016-17 NA/2014-15/28060,Roads,Completed,NA-THIRUVOTTIYUR,5,375000,"Relaying the BT Road by Paver Finisher at Wimco Nagar Station Road in Dn 5, Unit 2, Zone 1 L=165M W= 5.00, A = 825 sqm",Own Sources,1,2014-15,2016-17 NA/2014-15/28070,Roads,Completed,NA-THIRUVOTTIYUR,5,153000,"Relaying the BT Road by Paver Finisher at Manikkam Nagar 2nd cross Street in Dn 5, Unit 2, Zone 1 L=90M W= 3.50, A = 315 sqm",Own Sources,1,2014-15,2016-17 NA/2014-15/28071,Roads,Completed,NA-THIRUVOTTIYUR,5,171000,"Relaying the BT Road by Paver Finisher at Manikkam Nagar 4th cross Street in Dn 5, Unit 2, Zone 1 L=84M W= 4.50, A =378 sqm",Own Sources,1,2014-15,2016-17 NA/2014-15/28416,Roads,Completed,NA-THIRUVOTTIYUR,5,409000,"Strengthening and Relaying the BT Road by Paver Finisher at Sowndhrapandiyanar Nagar in Dn 5, Unit 2, Zone 1 L=150M W= 6.00, A = 900 sqm",Own Sources,1,2014-15,2016-17 NA/2014-15/28417,Roads,Completed,NA-THIRUVOTTIYUR,5,250000,"Relaying the BT Road by Paver Finisher at KVK Kuppam Padavettamman Koil Street in Dn 5, Unit 2, Zone 1 L=110M W= 5.00, A = 550",Own Sources,1,2014-15,2016-17 L/2014-15/27951,Electrical,Completed,L-Electrical,6,26539000,"Provision of 525 nos. of 6 Mtr G.I Octogonal lamp post with Single Bracket with 40w LED fittings in Rajashanmugam nagar, Sakathi ganapathy Nagar, Kalaingar Nagar, Subramaniyam Nagar, Madura Nagar, T.S. Gopal Nagar, Jothi Nagar, Murugappa Nagar, Jai-Hind Nagar, Kalaivanar Nagar, Ponniamman Nagar, Ambedkar Nagar, 55 nos. of 6 Mtr G.I Octogonal lamp post with Single Bracket with 90w LED fittings in Rajashanmugam nagar, 8 nos. of 8 mtr G.I Octogonal lamp post with Single Bracket with 150w LED fitting at Manali Express Road and 19 nos. of 8 mtr G.I Octogonal lamp post with Double Bracket with 150W LED fitting at Manali Express Road near Jothi Nagar etc., in Division-6, Zone-I.","Loans, Grants And Own Sources",1,2014-15,2016-17 NA/2014-15/13576,Roads,Completed,NA-THIRUVOTTIYUR,6,2010000,"STRENGTHENING AND RELAYING EXISTING ROAD BY PAVER FINISHER @ JOTHI NAGAR MAIN CROSS STREET IN DN-6, UNIT-2, ZONE-1.",Grants,1,2014-15,2016-17 NA/2014-15/22213,Buildings,Completed,NA-THIRUVOTTIYUR,6,630000,"IMPROVEMENTS OF COMMUNITY HALL @ SARASWATHI NAGAR 13th STREET IN DIVISION-6, UNIT-2, ZONE-1.",Own Sources,1,2014-15,2017-18 NA/2014-15/23324,Roads,Completed,NA-THIRUVOTTIYUR,6,84000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 1st CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/23329,Roads,Completed,NA-THIRUVOTTIYUR,6,166000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 2nd CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23343,Roads,Completed,NA-THIRUVOTTIYUR,6,210000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 3rd CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2017-18 NA/2014-15/23345,Roads,Completed,NA-THIRUVOTTIYUR,6,125000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 4th CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23346,Roads,Completed,NA-THIRUVOTTIYUR,6,126000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 5th CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23347,Roads,Completed,NA-THIRUVOTTIYUR,6,502000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 6th CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23349,Roads,Completed,NA-THIRUVOTTIYUR,6,251000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 8th CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23351,Roads,Completed,NA-THIRUVOTTIYUR,6,172000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR PILLAYAR KOIL 1st CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2017-18 NA/2014-15/23357,Roads,Completed,NA-THIRUVOTTIYUR,6,196000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR PILLAYAR KOIL 2nd CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23359,Roads,Completed,NA-THIRUVOTTIYUR,6,249000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR PILLAYAR KOIL 3rd CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23362,Roads,Completed,NA-THIRUVOTTIYUR,6,249000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR PILLAYAR KOIL 4th CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23528,Roads,Completed,NA-THIRUVOTTIYUR,6,345000,"FORMING CEMENT CONCRETE ROAD @ JAIHIND NAGAR AMBEDKAR STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23530,Roads,Completed,NA-THIRUVOTTIYUR,6,476000,"FORMING CEMENT CONCRETE ROAD @ SIVASAKTHI NAGAR 1st STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23531,Roads,Completed,NA-THIRUVOTTIYUR,6,501000,"FORMING CEMENT CONCRETE ROAD @ SIVASAKTHI NAGAR 2nd STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23532,Roads,Completed,NA-THIRUVOTTIYUR,6,501000,"FORMING CEMENT CONCRETE ROAD @ SIVASAKTHI NAGAR 3rd STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23533,Roads,Completed,NA-THIRUVOTTIYUR,6,530000,"FORMING CEMENT CONCRETE ROAD @ SIVASAKTHI NAGAR 4th STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23534,Roads,Completed,NA-THIRUVOTTIYUR,6,828000,"FORMING CEMENT CONCRETE ROAD @ SIVASAKTHI NAGAR 6th STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 NA/2014-15/23551,Roads,Completed,NA-THIRUVOTTIYUR,6,1405000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ SARASWATHI NAGAR 8th STREET IN DIVISION-6, UNIT-2, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/23561,Roads,Completed,NA-THIRUVOTTIYUR,6,539000,"FORMING STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHINIG @ RAJASHANMUGAM NAGAR 9th 3rd CROSS STREET IN DIVISION-6, UNIT-2, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/24125,Roads,Completed,NA-THIRUVOTTIYUR,6,483000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ RAJASHANMUGAM NAGAR 9th 5th CROSS STREET IN DIVISION-6, UNIT-2, ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/24278,Roads,Completed,NA-THIRUVOTTIYUR,6,480000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ RAJASHANMUGAM NAGAR 9th 1st CROSS STREET IN DIVISION-6, UNIT-2,ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/24360,Roads,Completed,NA-THIRUVOTTIYUR,6,1032000,"FORMING CEMENT CONCRETE ROAD @ DR.AMBEDKAR NAGAR 2nd STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26813,Roads,Completed,NA-THIRUVOTTIYUR,6,1957000,"STRENGTHENING AND RELAYING THE EXISTING BT ROAD BY PAVER FINISHING @ SATHYAMOORTHY NAGAR 2nd STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26816,Roads,Completed,NA-THIRUVOTTIYUR,6,81000,"STRENGTHENING AND RELAYING THE EXISTING BT ROAD BY PAVER FINISHING @ SATHYAMOORTHY NAGAR 2nd CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26817,Roads,Completed,NA-THIRUVOTTIYUR,6,182000,"STRENGTHENING AND RELAYING THE EXISTING BT ROAD BY PAVER FINISHING @ SATHYAMOORTHY NAGAR 3rd CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26818,Roads,Completed,NA-THIRUVOTTIYUR,6,272000,"STRENGTHENING AND RELAYING THE EXISTING BT ROAD BY PAVER FINISHING @ SATHYAMOORTHY NAGAR 4th CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26820,Roads,Completed,NA-THIRUVOTTIYUR,6,706000,"STRENGTHENING AND RELAYING THE EXISTING BT ROAD BY PAVER FINISHING @ SATHYAMOORTHY NAGAR 7th STREET IN DIVISION-06, UNIT-02, ZONE-01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26821,Roads,Completed,NA-THIRUVOTTIYUR,6,374000,"STRENGTHENING AND RELAYING THE EXISTING BT ROAD BY PAVER FINISHING @ SATHYAMOORTHY NAGAR 7th CROSS STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2014-15,2016-17 BR/2014-15/19495,Roads,Completed,BR-Bus Route Roads,7,27351000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Kargil Nagar Main road (from the Junction of Nehru I street to the Junction of Kargil Nagar I Street ) Division - 7 , Zone - I",Grants,1,2014-15,2017-18 NA/2014-15/17543,Roads,Completed,NA-THIRUVOTTIYUR,7,6990000,"STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT GANGAIAMMAN NAGAR IN DN - 07, UNIT - 02, ZONE - 01.",Grants,1,2014-15,2016-17 NA/2014-15/17545,Roads,Completed,NA-THIRUVOTTIYUR,7,2860000,"STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT RADHAKRISHNAN NAGAR MAIN ROAD IN DN - 07, UNIT - 02, ZONE - 01.",Grants,1,2014-15,2016-17 NA/2014-15/27054,Roads,Completed,NA-THIRUVOTTIYUR,7,445000,"LAYING CEMENT CONCRETE ROAD AT CHARLES NAGAR 4TH STREET 4TH CROSS STREET IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2017-18 NA/2014-15/27055,Roads,Completed,NA-THIRUVOTTIYUR,7,252000,"LAYING CEMENT CONCRETE ROAD AT RMV Nagar 2nd STREET IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27056,Roads,Completed,NA-THIRUVOTTIYUR,7,252000,"LAYING CEMENT CONCRETE ROAD AT RMV NAGAR 3RD STREET IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27057,Roads,Completed,NA-THIRUVOTTIYUR,7,324000,"LAYING CEMENT CONCRETE ROAD AT RAMASAMY NAGAR 9TH STREET IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27058,Roads,Completed,NA-THIRUVOTTIYUR,7,800000,"LAYING CEMENT CONCRETE ROAD AT RAMASAMY NAGAR CROSS STREET IN DIVISION-7,UNIT-2,ZONE-1. .",Own Sources,1,2014-15,2017-18 NA/2014-15/27059,Roads,Completed,NA-THIRUVOTTIYUR,7,1871000,"LAYING CEMENT CONCRETE ROAD AT NEHRU NAGAR (OTHAVADAI STREET) IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2017-18 NA/2014-15/27060,Roads,Completed,NA-THIRUVOTTIYUR,7,1140000,"LAYING CEMENT CONCRETE ROAD AT KCP ROAD (KAMARAJ STREET ) IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2017-18 NA/2014-15/27061,Roads,Completed,NA-THIRUVOTTIYUR,7,339000,"LAYING CEMENT CONCRETE ROAD AT ANNAMALAI NAGAR 3RD CROSS STREET IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2017-18 NA/2014-15/27062,Roads,Completed,NA-THIRUVOTTIYUR,7,386000,"LAYING CEMENT CONCRETE ROAD AT CHARLES NAGAR 1 ST CROSS STREET IN DIVISION-7,UNIT-2,ZONE-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27064,Roads,Completed,NA-THIRUVOTTIYUR,7,402000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT CHARLES NAGAR 3 rd STREET 1 st CROSS STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27065,Roads,Completed,NA-THIRUVOTTIYUR,7,754000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT CHARLES NAGAR 3 rd STREET 2 nd CROSS STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27066,Roads,Completed,NA-THIRUVOTTIYUR,7,1545000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT RAJAJI NAGAR ANNA STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27067,Roads,Completed,NA-THIRUVOTTIYUR,7,1379000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT CHARLES NAGAR 4 th STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27068,Roads,Completed,NA-THIRUVOTTIYUR,7,575000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT CHARLES NAGAR 4 th STREET 1 st CROSS STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27069,Roads,Completed,NA-THIRUVOTTIYUR,7,520000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT GANGAIAMMAN NAGAR 1 st STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27070,Roads,Completed,NA-THIRUVOTTIYUR,7,520000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT GANGAIAMMAN NAGAR 2 nd STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27071,Roads,Completed,NA-THIRUVOTTIYUR,7,1028000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT GANGAIAMMAN NAGAR 3 rd STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27072,Roads,Completed,NA-THIRUVOTTIYUR,7,4980000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT GANDHI NAGAR ( OTHAVADAI STREET ) IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27073,Roads,Completed,NA-THIRUVOTTIYUR,7,12080000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KCP ROAD IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27074,Roads,Completed,NA-THIRUVOTTIYUR,7,2060000,"FORMING,STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KAMARAJ STREET ( RAMASAMY NAGAR) IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2016-17 NA/2014-15/27075,Roads,Completed,NA-THIRUVOTTIYUR,7,176000,"LAYING CEMENT CONCRETE ROAD AT CHARLES NAGAR 4TH STREET 3rd CROSS STREET IN DN - 7, UNIT - 2, ZONE - 1.",Own Sources,1,2014-15,2017-18 NA/2014-15/27096,Roads,Completed,NA-THIRUVOTTIYUR,7,1350000,"FORMING, STRENTHENING AND LAYING BT ROAD BY PAVER FINISHER AT CHARGLES NAGAR 3rd STREET IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2014-15,2016-17 NA/2014-15/26990,Roads,Completed,NA-THIRUVOTTIYUR,8,241000,"LAYING CEMENT CONCRETE ROAD AT EGAVALLI AMMAN NAGAR 3RD CROSS STREET IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26991,Roads,Completed,NA-THIRUVOTTIYUR,8,211000,"LAYING CEMENT CONCRETE ROAD AT EGAVALLI AMMAN NAGAR 2ND CROSS STREET IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26992,Roads,Completed,NA-THIRUVOTTIYUR,8,190000,"LAYING CEMENT CONCRETE ROAD AT EGAVALLI AMMAN NAGAR 1ST CROSS STREET IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26993,Roads,Completed,NA-THIRUVOTTIYUR,8,272000,"LAYING CEMENT CONCRETE ROAD AT VADUGAR PALAYAM 1ST STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26994,Roads,Completed,NA-THIRUVOTTIYUR,8,262000,"LAYING CEMENT CONCRETE ROAD AT VADUGAR PALAYAM 2ND STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26999,Roads,Completed,NA-THIRUVOTTIYUR,8,271000,"LAYING CEMENT CONCRETE ROAD AT THULASI GARDEN 1ST STREET IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/27000,Roads,Completed,NA-THIRUVOTTIYUR,8,271000,"LAYING CEMENT CONCRETE ROAD AT THULASI GARDEN 2ND STREET IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/27001,Roads,Completed,NA-THIRUVOTTIYUR,8,161000,"LAYING CEMENT CONCRETE ROAD AT RETTAI MALAI SRINI VASAN NAGAR 1ST LANE IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27003,Roads,Completed,NA-THIRUVOTTIYUR,8,216000,"LAYING CEMENT CONCRETE ROAD AT RETTAI MALAI SRINI VASAN NAGAR 3RD LANE IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27023,Roads,Completed,NA-THIRUVOTTIYUR,8,216000,"LAYING CEMENT CONCRETE ROAD AT RETTAI MALAI SRINI VASAN NAGAR 4TH LANE IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27024,Roads,Completed,NA-THIRUVOTTIYUR,8,217000,"LAYING CEMENT CONCRETE ROAD AT RETTAI MALAI SRINI VASAN NAGAR 5TH LANE IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27025,Roads,Completed,NA-THIRUVOTTIYUR,8,220000,"LAYING CEMENT CONCRETE ROAD AT RETTAI MALAI SRINI VASAN NAGAR 6TH LANE IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/27026,Roads,Completed,NA-THIRUVOTTIYUR,8,151700,"LAYING CEMENT CONCRETE ROAD AT KAVERI NAGAR 1ST STREET IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/27027,Roads,Completed,NA-THIRUVOTTIYUR,8,181000,"LAYING CEMENT CONCRETE ROAD AT KAVERI NAGAR 2ND STREET IN DN-8,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/30454,Roads,Completed,NA-THIRUVOTTIYUR,8,1877000,"Strengthening and Relaying the BT Road by Paver Finisher at RETTAI MALAI SRINIVASAN NAGAR ,DIV-8 Unit 2, Zone 1",Own Sources,1,2014-15,2016-17 NA/2014-15/16261,Roads,Completed,NA-THIRUVOTTIYUR,9,995000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (M30) AT PATTINATHAR KOIL 1ST LANE, 3RD STREET, 4TH LANE,VILLAGE CROSS LANE,VILLAGE 1ST LANE AND CROSS LANES IN DN.9, U-2, ZONE1(COUNCILLOR FUND 2014-15) L=185M W=3.00M, A=555SQM",Own Sources,1,2014-15,2016-17 NA/2014-15/16273,Roads,Completed,NA-THIRUVOTTIYUR,9,982000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (M30) AT VILLAGE STREET CROSS LANE, APPARSAMY KOIL 1ST CROSS LANES, 2nd CROSS LANES AND CROSS LANES IN DN.9, U-2, ZONE1(COUNCILLOR FUND 2014-15) L=190M W=3.00M, A=570SQM",Own Sources,1,2014-15,2016-17 NA/2014-15/26963,Roads,Completed,NA-THIRUVOTTIYUR,9,512900,"Laying Cement Concrete Road at Pattinathar kovil 6th cross lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26964,Roads,Completed,NA-THIRUVOTTIYUR,9,630000,"Laying Cement Concrete Road at Pattinathar kovil 7th cross lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26965,Roads,Completed,NA-THIRUVOTTIYUR,9,629000,"Laying Cement Concrete Road at Appar samy kovil 2nd cross street IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26966,Roads,Completed,NA-THIRUVOTTIYUR,9,180000,"Laying Cement Concrete Road at appar nagar 1st street IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26968,Roads,Completed,NA-THIRUVOTTIYUR,9,580000,"Laying Cement Concrete Road at Pattinathar kovil 2nd cross lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26970,Roads,Completed,NA-THIRUVOTTIYUR,9,347000,"Laying Cement Concrete Road at Appar samy kovil 2nd lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26972,Roads,Completed,NA-THIRUVOTTIYUR,9,236000,"Laying Cement Concrete Road at Thulukanath amman kovil 2nd cross lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26973,Roads,Completed,NA-THIRUVOTTIYUR,9,82000,"Laying Cement Concrete Road at Thulukanath amman kovil 3rd cross street IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26974,Roads,Completed,NA-THIRUVOTTIYUR,9,236000,"Laying Cement Concrete Road at Burial Ground Back side 1st lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26975,Roads,Completed,NA-THIRUVOTTIYUR,9,190000,"Laying Cement Concrete Road at Burial Ground Back side 2nd lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26976,Roads,Completed,NA-THIRUVOTTIYUR,9,238000,"Laying Cement Concrete Road at Burial ground back side 3rd lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26977,Roads,Completed,NA-THIRUVOTTIYUR,9,103000,"Laying Cement Concrete Road at Burial ground back side 4th lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26978,Roads,Completed,NA-THIRUVOTTIYUR,9,84000,"Laying Cement Concrete Road at Burial ground back side 5th lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26979,Roads,Completed,NA-THIRUVOTTIYUR,9,51000,"Laying Cement Concrete Road at Burial ground back side 6th lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26980,Roads,Completed,NA-THIRUVOTTIYUR,9,352000,"Laying Cement Concrete Road at Burial ground back side 7th lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26981,Roads,Completed,NA-THIRUVOTTIYUR,9,692000,"Laying Cement Concrete Road at Pattinathar kovil 5th cross lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 NA/2014-15/26982,Roads,Completed,NA-THIRUVOTTIYUR,9,139000,"Laying Cement Concrete Road at Pattinathar kovil 8th cross lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2017-18 NA/2014-15/26983,Roads,Completed,NA-THIRUVOTTIYUR,9,187000,"Laying Cement Concrete Road at Apparsamy kovil 1st lane IN DN-9,UNIT-2,ZONE-1",Own Sources,1,2014-15,2016-17 BR/2014-15/30023,Roads,Completed,BR-Bus Route Roads,10,14880000,"Strengthening and Relaying the Road With DBM and CBC by Paver Finisher by Using plastic Waste at BALAKRISNA STREET BALA KRISNA ST EXTN, STATION ROAD, LAKE VIEW ROAD IN DN - 133 & 135 ZONE - 10",Grants,1,2014-15,2016-17 NA/2014-15/21576,Buildings,Completed,NA-THIRUVOTTIYUR,10,998000,"IMPROVEMENTS TO ANGANWADI BUILDING (NNMP SHED NO.52) AT WEST MADA STREET IN DN.10, U-3, Z-1. COUNCILLOR FUND",Own Sources,1,2014-15,2016-17 NA/2014-15/24164,Roads,Completed,NA-THIRUVOTTIYUR,10,516000,"STRENGTHENING AND RELAYING THE ROAD USING PAVER FINISHER AT TVK NAGAR 2ND STREET IN DIV-10,UNIT-3,ZONE-1 (LENGTH-80M ,WIDTH-4.50M ,AREA-360 SQ.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/24166,Roads,Completed,NA-THIRUVOTTIYUR,10,730000,"STRENGTHENING AND RELAYING THE ROAD USING PAVER FINISHER AT NETHAJI NAGAR 3rd STREET IN DIV-10,UNIT-3,ZONE-1. (LENGTH-100M ,WIDTH-5.00M ,AREA-500 SQ.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/24170,Roads,Completed,NA-THIRUVOTTIYUR,10,352000,"STRENGTHENING AND RELAYING THE ROAD USING PAVER FINISHER AT RAILWAY STATION ROAD CROSS STREET IN DIV-10,UNIT-3,ZONE-1(LENTH-60M ,WIDTH-4.00M ,AREA-240 SQ.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/24176,Roads,Completed,NA-THIRUVOTTIYUR,10,658000,"STRENGTHENING AND RELAYING THE ROAD USING PAVER FINISHER AT NETHAJI NAGAR 2ND STREET IN DIV-10,UNIT-3,ZONE-1(LENGTH-95M ,WIDTH-4.70M ,AREA-450 SQ.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/24179,Roads,Completed,NA-THIRUVOTTIYUR,10,731000,"STRENGTHENING AND RELAYING THE ROAD USING PAVER FINISHER AT NETHAJI NAGAR 1st STREET IN DIV-10,UNIT-3,ZONE-1. (L-100M , W-5.00M ,A=500SQ.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/25757,Roads,Completed,NA-THIRUVOTTIYUR,10,692000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT ANNA COLONY IN DN.10, U-3, Z-1. (L=120.00M,W=3.60M,Area=432 sq.m)",Own Sources,1,2014-15,2017-18 NA/2014-15/25760,Roads,Completed,NA-THIRUVOTTIYUR,10,897000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT SOUTH PRAGARAM 1ST CROSS STREET IN DN.10, U-3, Z-1. (L=135.00M,W=3.80M,Area=513 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25761,Roads,Completed,NA-THIRUVOTTIYUR,10,558000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT BASIN ROAD LANE IN DN.10, U-3, Z-1. (L=90.00M ,W=3.50M , Area=315.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25762,Roads,Completed,NA-THIRUVOTTIYUR,10,415000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT GOMATHA NAGAR IV STREET (1ST & 2NDCROSS STREET) IN DN.10, U-3, Z-1.(L= 60.00M ,W= 4.00M ,Area= 240.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25765,Roads,Completed,NA-THIRUVOTTIYUR,10,581000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT SOUTH PRAGARAM 2ND CROSS STREET IN DN.10, U-3, Z-1. (L=125.00 M,W=2.60 M,Area=325.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25766,Roads,Completed,NA-THIRUVOTTIYUR,10,348000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT WEST MADA CROSS STREET IN DN.10, U-3, Z-1. (L=60.00 M, W=3.20 M,Area=192.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25768,Roads,Completed,NA-THIRUVOTTIYUR,10,823000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT MEENAKSHI NAGAR IN DN.10, U-3, Z-1. (L=130.00 M , W=3.60 M, Area=468.00 sq.m)",Own Sources,1,2014-15,2017-18 NA/2014-15/25770,Roads,Completed,NA-THIRUVOTTIYUR,10,493000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT RAJIV NAGAR 3RD STREET IN DN.10, U-3, Z-1. (L=70.00 M, W=4.00 M, Area=280.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25772,Roads,Completed,NA-THIRUVOTTIYUR,10,197000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT VIVEKANANDAN NAGAR CROSS STREET IN DN.10, U-3, Z-1. (L=45.00 M, W=3.00 M, Area=135.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25774,Roads,Completed,NA-THIRUVOTTIYUR,10,487000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT SIVA SHAKTHI NAGAR IN DN.10, U-3, Z-1. (L=85.00M , W=3.20 M, Area=272.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25776,Roads,Completed,NA-THIRUVOTTIYUR,10,138000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT SADYAKUPPAM PATTAI CROSS STREET IN DN.10, U-3, Z-1. (L=25.00M,W=3.00M,Area=75.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25779,Roads,Completed,NA-THIRUVOTTIYUR,10,336000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT NELLIKARAN CROSS STREET IN DN.10, U-3, Z-1.(L=45M, W=4M, AREA=180Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25780,Roads,Completed,NA-THIRUVOTTIYUR,10,1189000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONTHOTTAM 2ND CROSS STREET IN DN.10, U-3, Z-1.(L=180M, W=3.80M, AREA=684Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25782,Roads,Completed,NA-THIRUVOTTIYUR,10,616000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT TVK NAGAR 1ST STREET IN DN.10, U-3, Z-1.(L=100M, W=3.40M, AREA=340Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25784,Roads,Completed,NA-THIRUVOTTIYUR,10,630000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT NORTH MADA CROSS STREET IN DN.10, U-3, Z-1.(L=120M, W=2.80M, AREA=336.00Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25787,Roads,Completed,NA-THIRUVOTTIYUR,10,330000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT GOMATHA NAGR LANE IN DN.10, U-3, Z-1.(L=65M, W=2.50M, AREA=182Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25791,Roads,Completed,NA-THIRUVOTTIYUR,10,219000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT KUMARA PILLAI NAGAR MAIN STREET IN DN.10, U-3, Z-1.(L=60M, W=2.10M, AREA=126Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25792,Roads,Completed,NA-THIRUVOTTIYUR,10,231000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT SOUTH MADA STREET (NEAR KGL LODGE) IN DN.10, U-3, Z-1.(L=40M, W=1.80M, AREA=72Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27622,Roads,Completed,NA-THIRUVOTTIYUR,10,94000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE MIX AT KUMARA PILLAI NAGAR 1ST STREET IN DN.10, U-3, Z-1.(L=25, W=1.90, AREA=48Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27629,Roads,Completed,NA-THIRUVOTTIYUR,10,94000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE MIX AT KUMARA PILLAI NAGAR 2ND STREET IN DN.10, U-3, Z-1.(L=25, W=1.90, AREA=48Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27630,Roads,Completed,NA-THIRUVOTTIYUR,10,71000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE MIX AT KUMARA PILLAI NAGAR 3RD STREET IN DN.10, U-3, Z-1.(L=20, W=1.70, AREA=34Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27649,Roads,Completed,NA-THIRUVOTTIYUR,10,59000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE MIX AT KUMARA PILLAI NAGAR 4TH STREET IN DN.10, U-3, Z-1.(L=18, W=1.50, AREA=27Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27653,Roads,Completed,NA-THIRUVOTTIYUR,10,139000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE MIX AT KUMARA PILLAI NAGAR 5TH STREET IN DN.10, U-3, Z-1.(L=30, W=2.50, AREA=75Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/16665,Roads,Completed,NA-THIRUVOTTIYUR,11,993000,"STRENGHENING AND RELAYING THE ROAD WITH PAVER FINISHER AT POONGA NAGAR MAIN ROAD DN.11, U-3, Z-1. (LENGTH - 214M, WIDTH - 4.20M, AREA - 900Sq.M)",Grants,1,2014-15,2016-17 NA/2014-15/17675,Buildings,Completed,NA-THIRUVOTTIYUR,11,405000,"Construction of Sump with water supply arrangements for Chennai Primary School at Market lane in Dn.11, U-3, Z-1.(COUNCILLOR FUND)",Own Sources,1,2014-15,2016-17 NA/2014-15/24151,Roads,Completed,NA-THIRUVOTTIYUR,11,525000,"STRENGTHENING AND RELAYING THE EXISTING BT ROAD USING PAVER IN VIVEKANANDA 2ND STREET(ELLAI AMMAN KOIL STREET) AT DIV-11,UNIT-3,ZONE-1.(L=90M,W=4.00M,AREA=360Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24152,Roads,Completed,NA-THIRUVOTTIYUR,11,488000,"STRENGTHENING AND RELAYING THE ROAD USING PAVER FINISHER AT VIVEKANANDA 1ST STREET(ELLAI AMMAN KOIL STREET) IN DIV-11,UNIT-3,ZONE-1(LENGTH-67M,WIDTH-5.00M,AREA-335 SQ.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/24155,Roads,Completed,NA-THIRUVOTTIYUR,11,1207000,"STRENGTHENING AND RELAYING THE ROAD USING PAVER FINISHER AT ABC AVENUE IN DIV-11,UNIT-3,ZONE-1.(LENGTH - 245M, WIDTH - 5.70M (Ave.), AREA - 1400SQ.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/24733,Roads,Completed,NA-THIRUVOTTIYUR,11,297000,"Laying cement concrete road with M30 Design Mix at Market Lane 1st street in Dn.11, U-3, Z-1.(L=90M, W=1.80M, AREA=162Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24735,Roads,Completed,NA-THIRUVOTTIYUR,11,239000,"LAYING CEMENT COCRETE ROAD WITH M30 DESIGN MIX AT MARKET LANE 2ND STREET IN DN.11, U-3, Z-1.(LENGTH-49M, WIDTH-2.80M, AREA=138Sq.M.)",Own Sources,1,2014-15,2016-17 NA/2014-15/24736,Roads,Completed,NA-THIRUVOTTIYUR,11,482000,"LAYING CEMENT CONCRETE ROAD WITH M30 DESINGN MIX AT MARKET LANE 3RD STREET IN DN.11, U-3, Z-1.(L=100M, W=2.00M, AREA=200Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24737,Roads,Completed,NA-THIRUVOTTIYUR,11,426000,"LAYING CEMENT CONCRETE ROAD WITH M30 DISIGN MIX AT MARKET LANE 4TH STREET IN DN.11, U-3, Z-1.(L=95M, W=2.60M, AREA=247Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24739,Roads,Completed,NA-THIRUVOTTIYUR,11,533000,"LAYING CEMENT CONCRETE ROAD WITH M30 DESIGN MIX AT MARKET LANE 5TH STREET IN DN.11, U-3, Z-1.(L=120M, W=3.30M, AREA=396Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24741,Roads,Completed,NA-THIRUVOTTIYUR,11,475000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT MARKET LANE 6TH STREET IN DN.11, U-3, Z-1.(L=90M, W=2.90M, AREA=261Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24742,Roads,Completed,NA-THIRUVOTTIYUR,11,627000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT MARKET LANE 7TH STREET IN DN.11, U-3, Z-1.(L=130M, W=2.60M, AREA=338Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24743,Roads,Completed,NA-THIRUVOTTIYUR,11,178000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT MARKET LANE 9TH STREET IN DN.11, U-3, Z-1.(L=50M, W=2.00M, AREA=100Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24745,Roads,Completed,NA-THIRUVOTTIYUR,11,449000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT MARKET LANE 10TH STREET IN DN.11, U-3, Z-1. (L=70.00M, W=3.60M, AREA=252.00 Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24746,Roads,Completed,NA-THIRUVOTTIYUR,11,223000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT MARKET LANE 11TH STREET IN DN.11, U-3, Z-1. (L=75.00M, W=1.60M ,Area=120.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24747,Roads,Completed,NA-THIRUVOTTIYUR,11,363000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT MARKET LANE 13TH STREET IN DN.11, U-3, Z-1. (L=110.00M,W=1.80M,Area=198.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24748,Roads,Completed,NA-THIRUVOTTIYUR,11,644000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT POONGA NAGAR 1ST STREET IN DN.11, U-3, Z-1. (L=110.00M,W=3.20M,Area=352.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24749,Roads,Completed,NA-THIRUVOTTIYUR,11,367000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT POONGA NAGAR 2ND STREET IN DN.11, U-3, Z-1. (L=60.00M, W=3.20M, Area=192.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/24750,Roads,Completed,NA-THIRUVOTTIYUR,11,370000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT POONGA NAGAR 3RD STREET IN DN.11, U-3, Z-1. (L=63.00M, W=3.20M ,Area=203 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25724,Roads,Completed,NA-THIRUVOTTIYUR,11,207000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM IST STREET IN DN.11, U-3, Z-1.(L=75M, W=1.60M, AREA=120Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25726,Roads,Completed,NA-THIRUVOTTIYUR,11,216000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 2ND STREET IN DN.11, U-3, Z-1.(L=75M, W=1.60M, AREA=120Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25727,Roads,Completed,NA-THIRUVOTTIYUR,11,160000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 3RD STREET IN DN.11, U-3, Z-1.(L=55M, W=1.80M, AREA=99Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25728,Roads,Completed,NA-THIRUVOTTIYUR,11,270000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 4TH STREET IN DN.11, U-3, Z-1.(L=60M, W=2.50M, AREA=150q.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25734,Roads,Completed,NA-THIRUVOTTIYUR,11,157000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 5TH STREET IN DN.11, U-3, Z-1.(L=45M, W=2.20M, AREA=99Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25738,Roads,Completed,NA-THIRUVOTTIYUR,11,435000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 6TH STREET IN DN.11, U-3, Z-1.(L=120M, W=1.80M, AREA=216Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25740,Roads,Completed,NA-THIRUVOTTIYUR,11,197000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 7TH STREET IN DN.11, U-3, Z-1.(L=70M, W=1.60M, AREA=112Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25741,Roads,Completed,NA-THIRUVOTTIYUR,11,199000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 8TH STREET IN DN.11, U-3, Z-1.(L=43M, W=3.00M, AREA=129Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25742,Roads,Completed,NA-THIRUVOTTIYUR,11,203000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 9TH STREET IN DN.11, U-3, Z-1.(L=50M, W=2.3M, AREA=115Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25743,Roads,Completed,NA-THIRUVOTTIYUR,11,184000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 10TH STREET IN DN.11, U-3, Z-1.(L=48M, W=2.000M, AREA=96Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25744,Roads,Completed,NA-THIRUVOTTIYUR,11,158000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 11TH STREET IN DN.11, U-3, Z-1.(L=50M, W=1.80M, AREA=90Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25746,Roads,Completed,NA-THIRUVOTTIYUR,11,165000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 12TH STREET IN DN.11, U-3, Z-1.(L=45M, W=2.10M, AREA=95Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25747,Roads,Completed,NA-THIRUVOTTIYUR,11,235000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 13TH STREET IN DN.11, U-3, Z-1.(L=50M, W=2.60M, AREA=130Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/25748,Roads,Completed,NA-THIRUVOTTIYUR,11,291000,"LAYING CEMENT CONCRET ROAD WITH M30 GRADE DESIGN MIX AT POONGAVANAPURAM 14TH STREET IN DN.11, U-3, Z-1. (L=55.00M ,W=3.00M ,Area=165.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27022,Roads,Completed,NA-THIRUVOTTIYUR,11,3938000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE DESIGN MIX AT JANAKI AMMAL ESTATE CROSS STREETS (FROM SANNATHI STREET) IN DN.11, U-3, Z-1.(L=565M, W=3.90M, AREA=2205Sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/29934,Buildings,Completed,NA-THIRUVOTTIYUR,11,82000,"REPAIRS AND RENEWING PUBLIC TOILET AT SATHYAMOORTHY NAGAR AND MARKET LANE IN DN.11, U-3, Z-1.",Own Sources,1,2014-15,2016-17 NA/2014-15/30309,Buildings,Completed,NA-THIRUVOTTIYUR,11,175000,"PROVIDING WIRELESS ROOM WITH ALUMINIUM PARTITION AND PAINTING FOR ELECTRICAL ROOM IN ZONAL OFFICE INSIDE AT T.H. ROAD, DN,11, U-3, Z-1..",Own Sources,1,2014-15,2016-17 NA/2014-15/20228,Roads,Completed,NA-THIRUVOTTIYUR,12,535000,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING RMC30) AT JAN RAVER LINK ROAD IN DIV-12 UNIT-3 ZONE-1 (COUNCILLAR FUND 2014-15) (L-84.00 B-3.20 AREA-269.00sqm),Own Sources,1,2014-15,2016-17 NA/2014-15/20229,Roads,Completed,NA-THIRUVOTTIYUR,12,558000,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING RMC30) AT JAN RAVER 1ST CROSS STREET IN DIV-12 UNIT-3 ZONE-1 (COUNCILLAR FUND 2014-15) (L-97.00 B-3.00 AREA-291.00sqm),Own Sources,1,2014-15,2016-17 NA/2014-15/26912,Roads,Completed,NA-THIRUVOTTIYUR,12,271400,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT KUMARAN NAGAR 1ST CROSS STREET IN DIVISION-12 UNIT-3 ZONE-1 (L-60.00 B- 3.00 AREA- 138.00 SQM),Own Sources,1,2014-15,2016-17 NA/2014-15/27325,Roads,Completed,NA-THIRUVOTTIYUR,12,1588400,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT SOUTH PRAGARAM STREET(KALADIPET) IN DIVISION-12 UNIT-3 ZONE-1 (L- 241.00 B-5.5,Own Sources,1,2014-15,2016-17 NA/2014-15/27326,Roads,Completed,NA-THIRUVOTTIYUR,12,594600,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT V.O.C 2ND STREET(KALADIPET) IN DIVISION-12 UNIT-3 ZONE-1 (L- 139.00 B-3.00,Own Sources,1,2014-15,2016-17 NA/2014-15/27327,Roads,Completed,NA-THIRUVOTTIYUR,12,264800,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT KUMARAN NAGAR 4TH C/St IN DIVISION-12 UNIT-3 ZONE-1 (L- 62.00 B-3.00,Own Sources,1,2014-15,2016-17 NA/2014-15/27328,Roads,Completed,NA-THIRUVOTTIYUR,12,301200,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT KUMARAN NAGAR 5TH C/St IN DIVISION-12 UNIT-3 ZONE-1 (L- 65.00 B-3.5 ),Own Sources,1,2014-15,2016-17 NA/2014-15/27331,Roads,Completed,NA-THIRUVOTTIYUR,12,346000,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT WEST MADA 2ND CROSS LANE IN DIVISION-12 UNIT-3 ZONE-1(L- 78.00 B-3.00,Own Sources,1,2014-15,2016-17 NA/2014-15/27332,Roads,Completed,NA-THIRUVOTTIYUR,12,280100,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT SOUTH MADA STREET LANE IN DIVISION-12 UNIT-3 ZONE-1 (L- 65.00 B-3.00,Own Sources,1,2014-15,2016-17 NA/2014-15/27475,Roads,Completed,NA-THIRUVOTTIYUR,12,224000,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT BRINDHAVAN NAGAR EXTN 2ND 1ST C/StT IN DIVISION-04 UNIT-1 ZONE-1,Own Sources,1,2014-15,2016-17 NA/2014-15/14670,Roads,Completed,NA-THIRUVOTTIYUR,13,1137100,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX ) AT GANDHI NAGAR 4TH STREET IN DIVISION-13 UNIT-3 ZONE-1(L-145.00 B-5.9.,Own Sources,1,2014-15,2016-17 NA/2014-15/15845,Roads,Completed,NA-THIRUVOTTIYUR,13,598000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX ) AT GANDHI NAGAR 3RD STREET in Dn :13, Unit : 3, Zone :1. L = 75.00 M, W = 5.9 M ,",Own Sources,1,2014-15,2016-17 NA/2014-15/16913,Roads,Completed,NA-THIRUVOTTIYUR,13,1235400,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX ) AT GANDHI NAGAR 1st STREET IN DN-13 UNIT-3 ZONE-1( L=165.00 B=5.6,Own Sources,1,2014-15,2016-17 NA/2014-15/16914,Roads,Completed,NA-THIRUVOTTIYUR,13,594800,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX ) AT GANDHI NAGAR 2ND STREET IN DN-13 UNIT-3 ZONE-1( L=75.00 B=5.9,Own Sources,1,2014-15,2016-17 NA/2014-15/16915,Roads,Completed,NA-THIRUVOTTIYUR,13,661300,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX ) AT GANDHI NAGAR 5TH STREET IN DN-13 UNIT-3 ZONE-1( L=75.00 B=6.7),Own Sources,1,2014-15,2016-17 NA/2014-15/27368,Roads,Completed,NA-THIRUVOTTIYUR,13,284000,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT VILLAGE 9TH STREET IN DIVISION-13 UNIT-3 ZONE-1 (L- 60.00 B-3.00),Own Sources,1,2014-15,2016-17 NA/2014-15/27369,Roads,Completed,NA-THIRUVOTTIYUR,13,275000,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT SATHANKADU NORTH LANE DIVISION-13 UNIT-3 ZONE-1 (L- 70.00 B-2.25,Own Sources,1,2014-15,2016-17 NA/2014-15/27370,Roads,Completed,NA-THIRUVOTTIYUR,13,151600,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT KANNIYAPPA GRAMMANI 2ND CROSS LANE IN DIVISION-13 UNIT-3 ZONE-1 (L- 30.00 B-3.50,Own Sources,1,2014-15,2016-17 NA/2014-15/27371,Roads,Completed,NA-THIRUVOTTIYUR,13,133200,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT SESHACHALA GRAMANI CROSS IN DIVISION-13 UNIT-3 ZONE-1 (L- 30.00 B-3.00,Own Sources,1,2014-15,2016-17 NA/2014-15/27372,Roads,Completed,NA-THIRUVOTTIYUR,13,339700,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT PERUMAL KOIL LANE STREET IN DIVISION-13 UNIT-3 ZONE-1 (L-75.00 B-2.75,Own Sources,1,2014-15,2016-17 NA/2014-15/27374,Roads,Completed,NA-THIRUVOTTIYUR,13,319500,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30 GRADE DESIGN MIX) AT VILAGE 10TH STREET IN DIVISION-13 UNIT-3 ZONE-1 (L- 56.00 B-4.00,Own Sources,1,2014-15,2016-17 NA/2014-15/24146,Roads,Completed,NA-THIRUVOTTIYUR,14,528000,STRENTHENNING AND RELAYING OF BT SURFACE TO KATA THOTTI STREET (T.H.ROAD) IN DN-14 UNIT-3 ZONE-1( L=90.00 B=4.00 AREA=360 M2),Own Sources,1,2014-15,2016-17 NA/2014-15/25953,Buildings,Completed,NA-THIRUVOTTIYUR,14,512000,"SUPPLYING AND FIXING GYM EQUIPMENTS IN GYM BUILDING AT THYAGARAYAPURAM 1st CROSS STREET IN DIVISION-14, UNIT-03, ZONE-01.",Own Sources,1,2014-15,2018-19 NA/2014-15/25960,Buildings,Completed,NA-THIRUVOTTIYUR,14,137000,"REPAIRS AND IMPROVEMENTS TO VARIOUS BUILDINGS OF GREATER CHENNAI CORPORATION IN DIVISION-14, UNIT-3, ZONE-01.",Own Sources,1,2014-15,2018-19 NA/2014-15/27029,Roads,Completed,NA-THIRUVOTTIYUR,14,458000,"LAYING CEMENT CONCRETE ROAD AT DOPIKANA lane IN DN-14,UNIT-3,ZONE-1(L=120.00M,W=4.00M,Area=480.00 sq.m)",Own Sources,1,2014-15,2017-18 NA/2014-15/27030,Roads,Completed,NA-THIRUVOTTIYUR,14,275000,"LAYING CEMENT CONCRETE ROAD AT MALLIGA PURAM 1ST STREET IN DN-14,UNIT-3,ZONE-1.(L=52.00M,W=4.00M,Area=208.00 sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27031,Roads,Completed,NA-THIRUVOTTIYUR,14,199000,"LAYING CEMENT CONCRETE ROAD AT MALLIGA PURAM 2ND STREET IN DN-14,UNIT-3,ZONE-1. (L=50.00M,W=3.00M,Area=150.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27033,Roads,Completed,NA-THIRUVOTTIYUR,14,90000,"LAYING CEMENT CONCRETE ROAD AT BH.SADHANANDHAPURAM NEAR ENNORE EXPRESS ROAD IN DN-14,UNIT-3,ZONE-1. (L=32.00,W=2.00M,Area=64.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27037,Roads,Completed,NA-THIRUVOTTIYUR,14,189000,"LAYING CEMENT CONCRETE ROAD AT PPD 2ND Cross street IN DN-14,UNIT-3,ZONE-1. (L=56.00M,W=2.50M,Area=140.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27040,Roads,Completed,NA-THIRUVOTTIYUR,14,477900,"LAYING CEMENT CONCRETE ROAD AT PPD 5TH STREET IN DN-14,UNIT-3,ZONE-1. (L=115.00M,W=3.00M,Area=345.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27042,Roads,Completed,NA-THIRUVOTTIYUR,14,350000,"LAYING CEMENT CONCRETE ROAD AT THYAGARAYAPURAM 10TH CROSS STREET IN DN-14,UNIT-3,ZONE-1. (L=85.00M,W=3.00M,Area=255.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27043,Roads,Completed,NA-THIRUVOTTIYUR,14,243900,"LAYING CEMENT CONCRETE ROAD AT THYAGARAYAPURAM 11TH CROSS STREET IN DN-14,UNIT-3,ZONE-1. (L=87.00M,W=2.00M,Area=174.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27045,Roads,Completed,NA-THIRUVOTTIYUR,14,636000,"LAYING CEMENT CONCRETE ROAD AT THYAGARAYAPURAM 7TH STREET IN DN-14,UNIT-3,ZONE-1. (L=160.00M,W=3.00M,Area=480.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27046,Roads,Completed,NA-THIRUVOTTIYUR,14,636000,"LAYING CEMENT CONCRETE ROAD AT THYAGARAYAPURAM 8TH STREET IN DN-14,UNIT-3,ZONE-1. (L=160.00M,W=3.00M,Area=480.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27047,Roads,Completed,NA-THIRUVOTTIYUR,14,206000,"LAYING CEMENT CONCRETE ROAD AT THYAGARAYAPURAM 8TH CROSS STREET IN DN-14,UNIT-3,ZONE-1. (L=52.00M,W=3.00M,Area=156.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27048,Roads,Completed,NA-THIRUVOTTIYUR,14,174000,"LAYING CEMENT CONCRETE ROAD AT THYAGARAYAPURAM 9TH STREET IN DN-14,UNIT-3,ZONE-1. (L=62.00M,W=2.00,Area=124.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27049,Roads,Completed,NA-THIRUVOTTIYUR,14,216000,"LAYING CEMENT CONCRETE ROAD AT THYAGARAYAPURAM 9TH CROSS STREET IN DN-14,UNIT-3,ZONE-1. (L=78.00M,W=2.00M,Area=156.00sq.m)",Own Sources,1,2014-15,2016-17 NA/2014-15/27052,Roads,Completed,NA-THIRUVOTTIYUR,14,185000,"Laying Cement Concrete Road at A. Sadhanandha puram IN DN-14 ,UNIT-3,ZONE-1. (L=45.00M,W=3.00M,Area=135.00sq.m)",Own Sources,1,2014-15,2016-17 B/2014-15/21387,Buildings,Completed,B-Buildings,15,5663981,"CONSTRUCTION OF DIVISION OFFICE AT MANALI IN DN-15,ZONE-II.",Own Sources,2,2014-15,2017-18 NB/2014-15/16747,Roads,Completed,NB-MANALI,15,2047000,"Forming and Laying of BT Road at Manali New Town 30 feet Road 13th Main Road(part) in Dn-15, Unit-4, Zone-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/16749,Roads,Completed,NB-MANALI,15,781000,"Forming and Laying of BT Road at Manali New Town 40 feet Road adjacent to Community hall building in Dn-15, Unit-4, Zone-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/17994,Buildings,Completed,NB-MANALI,15,625000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT NORTH SIDE OF OSR LAND (PHASE 1 BLOCK NO 20) CPS -11 IN MANALI NEW TOWN IN DN-15,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/17995,Buildings,Completed,NB-MANALI,15,700000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT EAST SIDE OF OSR LAND (PHASE 1 BLOCK NO 20)CPS - 11IN MANALI NEW TOWN IN DN-15,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/17997,Buildings,Completed,NB-MANALI,15,750000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT SOUTH SIDE OF OSR LAND (PHASE 1 BLOCK NO 20) CPS-11 IN MANALI NEW TOWN IN DN-15,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/17998,Buildings,Completed,NB-MANALI,15,890000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT WEST SIDE OF OSR LAND (PHASE 1 BLOCK NO 20) CPS - 11 IN MANALI NEW TOWN IN DN-15,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/20118,Roads,Completed,NB-MANALI,15,486000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 58TH BLOCK 20FEET ROAD 36TH STREET IN DN15, UN4 ZN2",Own Sources,2,2014-15,2016-17 NB/2014-15/20128,Roads,Completed,NB-MANALI,15,395000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 59TH BLOCK 20FEET ROAD 37TH STREET IN DN -15, UN -4 ZN -2",Own Sources,2,2014-15,2016-17 NB/2014-15/20131,Roads,Completed,NB-MANALI,15,486000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 60TH BLOCK 20FEET ROAD 38TH STREET IN DN15, UN4 ZN2",Own Sources,2,2014-15,2016-17 NB/2014-15/20133,Roads,Completed,NB-MANALI,15,303000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 54TH BLOCK 24FEET ROAD 44TH STREET IN DN15, UN4 ZN2",Own Sources,2,2014-15,2016-17 NB/2014-15/20134,Roads,Completed,NB-MANALI,15,486000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 31ST BLOCK 20FEET ROAD 31ST STREET IN DN15, UN-4 ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/20136,Roads,Completed,NB-MANALI,15,486000,"FORMING AND LAYING THE PAVER FINISHER AT MANALI NEW TOWN 32ND BLOCK 30FEET ROAD 12TH STREET IN DN15, UN4 ZN2",Own Sources,2,2014-15,2016-17 NB/2014-15/20140,Roads,Completed,NB-MANALI,15,395000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 30TH BLOCK 20FEET ROAD 30TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20145,Roads,Completed,NB-MANALI,15,486000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 29TH BLOCK 20FEET ROAD 29TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20189,Roads,Completed,NB-MANALI,15,590000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 86TH BLOCK 20FEET ROAD 53RD STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20190,Roads,Completed,NB-MANALI,15,744000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 62ND BLOCK 24FEET ROAD 47TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20192,Roads,Completed,NB-MANALI,15,760000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 67TH BLOCK 24FEET ROAD 48TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20193,Roads,Completed,NB-MANALI,15,760000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 68TH BLOCK 24FEET ROAD 49TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20194,Roads,Completed,NB-MANALI,15,730000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 70TH BLOCK 20FEET 51ST STREET IN ROAD DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20196,Roads,Completed,NB-MANALI,15,577000,"LAYING ROAD BY PAVER FINISHER AT VINAYAGAR KOIL STREET (WITH CONNECTING 8TH MAIN ROAD AND 10TH MAIN ROAD) MANALI NEW TOWN DN-15, UN-4 ZN-2.",Grants,2,2014-15,2016-17 NB/2014-15/20198,Roads,Completed,NB-MANALI,15,3105000,"WIDENING AND LAYING ROAD PAVER FINISHER AT MANALI NEW TOWN 39TH BLOCK 40FEET ROAD 1ST MAIN ROAD IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20201,Roads,Completed,NB-MANALI,15,500000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 35TH BLOCK 20FEET ROAD 5TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20203,Roads,Completed,NB-MANALI,15,395000,"LAYING THE PAVER FINISHER AT MANALI NEW TOWN 35TH BLOCK 16FEET ROAD 6TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20207,Roads,Completed,NB-MANALI,15,500000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 33RD BLOCK 24FEET ROAD 7TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20208,Roads,Completed,NB-MANALI,15,380000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 37TH BLOCK 30FEET ROAD 4TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20209,Roads,Completed,NB-MANALI,15,150000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 39TH BLOCK 30FEET ROAD 3RD STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20210,Roads,Completed,NB-MANALI,15,500000,"LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 49TH BLOCK 16FEET ROAD 34TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20211,Roads,Completed,NB-MANALI,15,1555000,"FORMING AND LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN 44TH BLOCK 30FEET ROAD 24TH STREET IN DN-15, UN-4 ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/20488,Buildings,Completed,NB-MANALI,15,710000,"Proposed Construction of Compound Wall West & North side for OSR land (Vacand land) at Ponniamman Nagar in DN -15, unit-4, zone-2",Own Sources,2,2014-15,2016-17 NB/2014-15/20489,Buildings,Completed,NB-MANALI,15,699000,"Proposed Construction of Compound Wall East & South side for OSR land (Vacant land) at Ponniamman Nagar in DN -15, unit-4, zone-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21741,Buildings,Completed,NB-MANALI,15,830000,"CONSTRUCTION OF PUBLIC CONVENIENCES AT EDAIYANCHAVADI MAIN ROAD IN EDAIYANCHAVADI IN DN-15,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/27541,Buildings,Completed,NB-MANALI,15,990000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT WEST SIDE OF COMMUNITY CENTRE IN MANALI NEW TOWN IN DN-15,U-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/27543,Buildings,Completed,NB-MANALI,15,995000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT NEW NAPPALAYAM IN DN-15,U-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/27782,Roads,Completed,NB-MANALI,15,129000,"PROVIDING HOT APPLIED THERMO PLASTIC COMPOUND AND FIXING UDIRECTIONAL REFLECTIVE PAVEMENT MARKER (RPM) OR ROAD STUDS BONED TO SPEED BREAKERS AT 10TH MAIN ROAD,NEAR POLICE STATION AND 80 FEET ROAD IN MANALI NEW TOWN IN DN-15 UN-4 ZN-2",Own Sources,2,2014-15,2016-17 L/2014-15/19517,Electrical,Completed,L-Electrical,16,188700,Shifting of lamp post,Deposit Works,2,2014-15,2016-17 NB/2014-15/16102,Buildings,Completed,NB-MANALI,16,860000,"IMPROVEMENTS TO CRIMINATION SHED AT INSIDE OF BURIAL GROUND AT BURMA NAGAR IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/16743,Buildings,Completed,NB-MANALI,16,790000,"PROPOSED CONSTRUCTION OF GAZEBO AT PARK IN CPS-2 IN MANALI NEW TOWN IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/16751,Roads,Completed,NB-MANALI,16,1217000,"Forming and Laying of BT Road at Andarkuppam Vinayagar Koil Street in Dn-16, Unit-4, Zone-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/16753,Roads,Completed,NB-MANALI,16,968000,"Forming and Laying of BT Road at Sadayakuppam Amman Koil Street in Dn-16, Unit-4, Zone-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/16801,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSRUCTION OF COMPOUND WALL FOR OPEN LAND AT GANGAI AMMAN KOIL STREET IN KANNIAMMAN PET 2 IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/16817,Buildings,Completed,NB-MANALI,16,998000,"CONSTRUCTION 0F YOGA AND MEDITATION HALL AT MANALI NEW TOWN CPS 4 IN DN; 16 , U;4, Z;2.",Own Sources,2,2014-15,2016-17 NB/2014-15/21120,Buildings,Completed,NB-MANALI,16,970000,"CONSTRUCTION OF TOILET AND COMPOUND WALL TO THE EAST SIDE OF GYM BUILDING ADJECENT TO KANNIAMMANPET BURIAL GROUND IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21121,Buildings,Completed,NB-MANALI,16,500000,"PROVIDING FLOORING ,ELECTRICAL ARRANGEMENTS AND WATER SUPPLY FACILITIES TO MULTIPURPOSE HALL (ANGANVADI) AT BURMA NAGAR IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21122,Buildings,Completed,NB-MANALI,16,690000,"CONSTRUCTION OF COMPOUND WALL TO GYM BUILDING AT ADJECENT TO KANNIAMMANPET BURIAL GROUND IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21745,Buildings,Completed,NB-MANALI,16,770000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT EAST SIDE OF BURIAL GROUND IN BURMA NAGAR IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21748,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT WEST SIDE OF VACAND LAND IN SADAYANKUPPAM IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21750,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT EAST SIDE OF VACAND LAND IN SADAYANKUPPAM IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21751,Buildings,Completed,NB-MANALI,16,760000,"PROPOSED CONSTRUCTION OF COMPOUND WALL,GATE AND GATE PILLAR AT SOUTH SIDE OF (CHAINAGE 0-70M) VACAND LAND IN SADAYANKUPPAM IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2017-18 NB/2014-15/21752,Buildings,Completed,NB-MANALI,16,760000,"PROPOSED CONSTRUCTION OF COMPOUND WALL,GATE AND GATE PILLAR AT NORTH SIDE OF (CHAINAGE 0-70M) VACAND LAND IN SADAYANKUPPAM IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21754,Buildings,Completed,NB-MANALI,16,690000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT SOUTH SIDE OF (CHAINAGE 70-140M) VACAND LAND IN SADAYANKUPPAM IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21823,Buildings,Completed,NB-MANALI,16,610000,"PROPOSED CONSTRUCTION OF COMPOUND WALL TO NORTH SIDE OF PLAY GROUND AT TNHB ,PHASE-1 IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21825,Buildings,Completed,NB-MANALI,16,710000,"PROPOSED CONSTRUCTION OF COMPOUND WALL TO EAST SIDE OF (CHAINAGE0-70M) PLAY GROUND AT TNHB ,PHASE-1 IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2017-18 NB/2014-15/21826,Buildings,Completed,NB-MANALI,16,710000,"PROPOSED CONSTRUCTION OF COMPOUND WALL TO EAST SIDE OF (CHAINAGE70-140M) PLAY GROUND AT TNHB ,PHASE-1 IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2017-18 NB/2014-15/21827,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL, GATE AND GATE PILLAR TO WEST SIDE OF PLAY GROUND AT TNHB ,PHASE-1 IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21832,Buildings,Completed,NB-MANALI,16,998000,"PROVIDING PATHWAY TO PLAY GROUND AT BURMA NAGAR IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/21833,Roads,Completed,NB-MANALI,16,1465000,"FORMING AND LAYING ROAD BY PAVER FINISHER AT BURMA NAGAR IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/22161,Roads,Completed,NB-MANALI,16,1613000,"FORMING AND LAYING ROAD BY PAVER FINISHER AT MANALI NEW TOWN RL NAGAR IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/22170,Buildings,Completed,NB-MANALI,16,940000,"CONSTRUCTION OF RR MASONRY WALL TO ANDARKUPPAM PERUMAL KOIL STREET TANK (CH 0-50M) IN DN-16,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 L/2014-15/19654,Electrical,Completed,L-Electrical,17,112900,Provision of new lamp post and shifting of existing lamp post,Deposit Works,2,2014-15,2016-17 NB/2014-15/13414,Buildings,Completed,NB-MANALI,17,418000,"IMPROVEMENT TO CRIMINATION SHED AND PROPOSED CONSTRUCTION OF WAITING HALL AT INSIDE BURIAL GROUND AT SAMUVEL NAGAR IN DN-17, UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/13418,Buildings,Completed,NB-MANALI,17,910000,"PROPOSED CONSTRUCTION OF CARE TAKER ROOM ,STORE ROOM AND TOILET FACILITIES FOR BURIAL GROUND AT SAMUVEL NAGAR IN DN-17,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/17042,Buildings,Completed,NB-MANALI,17,740000,"CONSTRUCTION OF COMPOUND WALL AT EAST SIDE OF POND IN KOSAPPUR CHELLIAMMAN KOIL STREET IN KOSAPPUR IN DN-17,U-4,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/17043,Buildings,Completed,NB-MANALI,17,740000,"CONSTRUCTION OF COMPOUND WALL AT NORTH SIDE OF POND IN KOSAPPUR CHELLIAMMAN KOIL STREET IN KOSAPPUR IN DN-17,U-4,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/17134,Parks,Completed,NB-MANALI,17,740000,"CONSTRUCTION OF COMPOUND WALL AT SOUTH SIDE OF POND IN CHELLIAMMAN KOIL STREET IN KOSAPPUR IN DN-17,U-4,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/28143,Buildings,Completed,NB-MANALI,17,840000,"PROPOSED CONSTRUCTION OF COMPOUND WALL EAST SIDE AND GATE AND GATE PILLAR AT SOUTH SIDE OF OSR LAND ALLOTTED FOR SCHOOL PLAY GROUND IN THIYAGI VISWANATHA DASS NAGAR IN DN-17,U-4,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/28144,Buildings,Completed,NB-MANALI,17,830000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR NORTH AND WEST SIDE AT OSR LAND ALLOTTED FOR SCHOOL PLAY GROUND IN THIYAGI VISWANATHA DASS NAGAR IN DN-17,U-4,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/28145,Buildings,Completed,NB-MANALI,17,680000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR NORTH AND EAST SIDE AT OSR LAND ALLOTTED FOR PARK IN THIYAGI VISWANATHA DASS NAGAR IN DN-17,U-4,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/16220,Storm Water Drain,Completed,NB-MANALI,18,826000,"Raising and Improvement works of SWD at Zaher Hussain 2nd Street (FROM Zaher Hussain 1ST STREET TO Jalagandamariamman koil street )(Reach 1) Dn-18, Ut-5, Zn-2",Own Sources,2,2014-15,2016-17 NB/2014-15/16529,Storm Water Drain,Completed,NB-MANALI,18,840000,"Raising and Improvement works of SWD at Zaher Hussain 2nd Street (FROM SALAIMA NAGAR TO Zaher Hussain 2ND 1st Lane) (Reach 2) Dn-18, Ut-5, Zn-2",Own Sources,2,2014-15,2016-17 NB/2014-15/16661,Roads,Completed,NB-MANALI,18,2306000,"FORMING AND LAYING THE ROAD BY PAVER FINISHER AT CPCL 1ST MAIN ROAD ( FROM NEDUNCHEZIYAN TO CHANDRAN STREET )IN DN-18, UT-5,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/16943,Buildings,Completed,NB-MANALI,18,920000,"CONSTRUCTION OF CARE TAKER ROOM ,STORE ROOM AND TOILET FACILITIES OF BURIAL GROUND AT HARIKRISHNAPURAM BHARATHIYAR STREET IN DN-18 U-5 ZN-II",Own Sources,2,2014-15,2016-17 NB/2014-15/17168,Storm Water Drain,Completed,NB-MANALI,18,998000,RISING AND IMPROVEMENT OF SWD AT LABBAIMEDU SHAKE ANSARI STREET IN DN-18 U-5 ZN-II,Own Sources,2,2014-15,2016-17 NB/2014-15/27280,Storm Water Drain,Completed,NB-MANALI,18,720000,IMPROVEMENT OF SWD AT CPCL 9TH STREET IN DN-18 U-5 ZN-II,Own Sources,2,2014-15,2016-17 NB/2014-15/15808,Parks,Completed,NB-MANALI,19,750000,"Proposed Construction of Compound Wall for OSR Land at MMDA 74th Street in Dn-19, Unit-5, Zone-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/15809,Parks,Completed,NB-MANALI,19,750000,"Proposed Construction of Compound Wall for OSR Land at MMDA 71st Street in Dn-19, Unit-5, Zone-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/20813,Buildings,Completed,NB-MANALI,19,900000,"CONSTRUCTION OF footpath IN SIDE OF PARK AT M.M.D.A 2nd main road in dn-19, u-5 , z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/22169,Buildings,Completed,NB-MANALI,19,2270000,"FORMING AND LAYING ROAD BY PAVER FINISHER AT CPCL 2ND MAIN ROAD IN DN-19,UN-4,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23274,Roads,Completed,NB-MANALI,19,2300000,"Forming and Laying the Interior road by paver finisher@ CPCL 3RD MAIN ROAD, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23276,Roads,Completed,NB-MANALI,19,738000,"Forming and Laying the Interior road by paver finisher @ CPCL 1ST STREET IN DN-19 , UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23277,Roads,Completed,NB-MANALI,19,848000,"Forming and Laying the Interior road by paver finisher@ CPCL 2nd STREET IN DN-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23278,Roads,Completed,NB-MANALI,19,1014000,"Forming and Laying the Interior road by paver finisher@ CPCL 3RD STREET IN DN-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23280,Roads,Completed,NB-MANALI,19,906000,"Forming and Laying the Interior road by paver finisher@ CPCL 4TH STREET in Dn-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23281,Roads,Completed,NB-MANALI,19,332000,"Forming and Laying the Interior road by paver finisher @ CPCL 5TH STREET IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23282,Roads,Completed,NB-MANALI,19,332000,"Forming and Laying the Interior road by paver finisher@ CPCL 6TH STREET IN DN-19 , UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23283,Roads,Completed,NB-MANALI,19,332000,"Forming and Laying the Interior road by paver finisher At CPCL 7TH STREET IN DN-19 , UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23284,Roads,Completed,NB-MANALI,19,896000,"Forming and Laying the Interior road by paver finisher@ CPCL 8TH STREET IN DN-19 , UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23285,Roads,Completed,NB-MANALI,19,503000,"Forming and Laying the Interior road by paver finisher@ CPCL 9TH STREET IN DN-19 , UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23286,Roads,Completed,NB-MANALI,19,1299000,"Forming and Laying the Interior road by paver finisher@ CPCL 10 TH STREET IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23287,Roads,Completed,NB-MANALI,19,1299000,"Forming and Laying the Interior road by paver finisher@ CPCL 11TH STREET IN DN-19 , UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23288,Roads,Completed,NB-MANALI,19,1278000,"Forming and Laying the Interior road by paver finisher@ CPCL 12TH STREET IN DN-19 , UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23289,Roads,Completed,NB-MANALI,19,541000,"Forming and Laying the Interior road by paver finisher@ CPCL 13TH STREET IN DN-19 UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23290,Roads,Completed,NB-MANALI,19,786000,"Forming and Laying the Interior road by paver finisher@ MMDA 43rd street IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23291,Roads,Completed,NB-MANALI,19,533000,"Forming and Laying the Interior road by paver finisher@ MMDA 79th Street 2nd Cross Street IN DN-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23292,Roads,Completed,NB-MANALI,19,615000,"Forming and Laying the Interior road by paver finisher@ MMDA 118th Street 1st Cross Street IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23293,Roads,Completed,NB-MANALI,19,323000,"Forming and Laying the Interior road by paver finisher @ MGR Salai 3rd Street in DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23294,Roads,Completed,NB-MANALI,19,982000,"Forming and Laying the Interior road by paver finisher@ APPOLO ARMSTRONG NAGAR in Dn-19 , Unit -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23295,Roads,Completed,NB-MANALI,19,738000,"Forming and Laying the Interior road by paver finisher@ MUTHU NAGAR CROSS STREET IN DN-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23296,Roads,Completed,NB-MANALI,19,118000,"Laying C.C Road At MMDA 121st STREET 2nd CROSS STREET In Dn-19, UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23299,Roads,Completed,NB-MANALI,19,1170000,"Forming and Laying the Interior road by paver finisher@ CHINNA SAMY NAGAR 5TH STREET in DN-19, UNIT -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23300,Roads,Completed,NB-MANALI,19,1065000,"Forming and Laying the Interior road by paver finisher@ CHINNA SAMY NAGAR 6TH STREET IN DN-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23301,Roads,Completed,NB-MANALI,19,1475000,"Forming and Laying the Interior road by paver finisher@ CHINNA SAMY NAGAR 3RD STREET (PART) IN DN-19 UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23302,Roads,Completed,NB-MANALI,19,1278000,"Forming and Laying the Interior road by paver finisher@ BABUJI NAGAR 1STS TREET IN DN-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23303,Roads,Completed,NB-MANALI,19,1703000,"Forming and Laying the Interior road by paver finisher@ BABUJI NAGAR 2ND STREET IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23304,Roads,Completed,NB-MANALI,19,851000,"Forming and Laying the Interior road by paver finisher@ BABUJI NAGAR 3RD STREET IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23305,Roads,Completed,NB-MANALI,19,1598000,"Forming and Laying the Interior road by paver finisher@ BABUJI NAGAR 4TH STREET IN DN-19 UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23306,Roads,Completed,NB-MANALI,19,393000,"Forming and Laying the Interior road by paver finisher@ Arunlantha Nagar 1st Cross Street (PART) IN DN-19 UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23307,Roads,Completed,NB-MANALI,19,410700,"Forming and Laying the Interior road by paver finisher@ Arunlanthanagar 4th lane cross street IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23310,Roads,Completed,NB-MANALI,19,1228000,"Forming and Laying the Interior road by paver finisher@ Kamaraj salai lane IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23311,Roads,Completed,NB-MANALI,19,720000,"Forming and Laying the Interior road by paver finisher@ Kamaraj salai 12th lane in DN-19,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23312,Roads,Completed,NB-MANALI,19,819000,"Forming and Laying the Interior road by paver finisher@ Kamaraj salai 11th lane In DN-19, UNIT -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23313,Roads,Completed,NB-MANALI,19,934000,"Forming and Laying the Interior road by paver finisher@ Bakthavatchalu 3rd Street IN DN-19, UNIT -5 & Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23314,Roads,Completed,NB-MANALI,19,345000,"Forming and Laying the Interior road by paver finisher@ Karumariamman Koil 9th Street IN DN-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23315,Roads,Completed,NB-MANALI,19,573000,"Forming and Laying the Interior road by paver finisher@ kamaraj salai 10th lane IN DN-19, UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23375,Roads,Completed,NB-MANALI,19,2980000,"Forming and Laying the Interior road by paver finisher At CPCL 1ST MAIN ROAD div-19, UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23395,Roads,Completed,NB-MANALI,19,702500,"Forming and Laying C.C. Road at Ponniamman Koil 4th Lane In Div -19 ,UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23396,Roads,Completed,NB-MANALI,19,355000,"Laying of C.C. Road At KARUMARI AMMAN KOVIL 6TH STREET In Dn-19, UNIT -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23398,Roads,Completed,NB-MANALI,19,280500,"Laying C.C. Road at MGR Salai 5th Street . div -19 , UNIT -5, Z-02",Own Sources,2,2014-15,2016-17 NB/2014-15/23399,Roads,Completed,NB-MANALI,19,752000,"Laying C.C. Road At PONNI AMMAN KOVIL 1ST LANE In Div -19 ,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23400,Roads,Completed,NB-MANALI,19,295000,"Laying C.C. Road At PONNI AMMAN KOVIL 2nd LANE IN DN-19,UN-5,ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23401,Roads,Completed,NB-MANALI,19,1207002,"Laying C.C. Road At PONNI AMMAN KOVIL 3rd LANE IN DN-19,UN-5,ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23402,Roads,Completed,NB-MANALI,19,876300,"Laying C.C. Road At Perumal Koil Kizhandai mada veethi street In Div -19 ,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23404,Roads,Completed,NB-MANALI,19,488000,"Laying C.C. Road at Perumal Koil Kizhandai mada veethi cross street in Div -19 , UNIT -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23405,Roads,Completed,NB-MANALI,19,653500,"Laying C.C. Road At Kamaraj salai 9th lane in Div -19 ,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23406,Roads,Completed,NB-MANALI,19,416200,"Laying C.C. Road At Arunlantha Nagar 2nd lane cross street In Div -19, UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23408,Roads,Completed,NB-MANALI,19,248900,"Laying of C.C. Road at MMDA 13th street In Div -19, UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23409,Roads,Completed,NB-MANALI,19,79700,"Laying C.C. Road At MMDA 18th Street 1st Cross Street In Div -19,UNIT -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23410,Roads,Completed,NB-MANALI,19,79750,"Laying C.C. Road At MMDA 22nd Street 1st Cross Street In Div -19 ,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23411,Roads,Completed,NB-MANALI,19,63900,"Laying C.C. Road At MMDA 25th Street 1st Cross Street. div -19 , UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23412,Roads,Completed,NB-MANALI,19,79750,"Laying C.C. Road At MMDA 30th Street 1st Cross Street.in Div -19, UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23418,Roads,Completed,NB-MANALI,19,56200,"Laying C.C. Road At MMDA 33rd Street 1st Cross Street. div -19 , UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23419,Roads,Completed,NB-MANALI,19,64750,"Laying C.C. Road At MMDA 34th Street 1st Cross Street. div -19 , UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23421,Roads,Completed,NB-MANALI,19,133900,"Laying C.C. Road At MMDA 35th Street 1st Cross Street. div -19 , UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23423,Roads,Completed,NB-MANALI,19,63700,"Laying C.C. Road At MMDA 41stStreet 1st Cross Street. div -19 , UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23425,Roads,Completed,NB-MANALI,19,159750,"Laying C.C. Road At MMDA 42th Street 1st Cross Street. div -19 , UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23426,Roads,Completed,NB-MANALI,19,80100,"Laying C.C. Road At MMDA 49th Street 1st Cross Street In Div -19 , UNIT -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23427,Roads,Completed,NB-MANALI,19,144900,"Laying C.C. Road At MMDA 61st Street 1st Cross Street IN Div -19 ,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23428,Roads,Completed,NB-MANALI,19,64750,"Laying C.C. Road At MMDA 65th Street 1st Cross Street in Div -19 ,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23429,Roads,Completed,NB-MANALI,19,72100,"Laying C.C. Road At MMDA 66th Street 1st Cross Street IN Div -19,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23430,Roads,Completed,NB-MANALI,19,79700,"Laying C.C. Road At MMDA 70th Street 1st Cross Street In Div -19,UNIT -5,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23431,Roads,Completed,NB-MANALI,19,137550,"Laying C.C. Road At MMDA 73rd Street 1st Cross Street In Div -19 ,UNIT -5,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23433,Roads,Completed,NB-MANALI,19,63750,"Laying C.C. Road At MMDA 39th Street 1st Cross Street In Dn-19,Zn-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23434,Roads,Completed,NB-MANALI,19,79000,"Laying C.C. Road at MMDA 74th Street 1st Cross Street.In Div -19 ,UNIT -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/23435,Roads,Completed,NB-MANALI,19,79000,"Laying C.C. Road At MMDA 71st Street 1st Cross Street.In div -19 ,UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23436,Roads,Completed,NB-MANALI,19,110000,"Laying C.C. Road At MMDA 97th Street 1st Cross Street.In Div -19 ,UNIT -5,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23437,Roads,Completed,NB-MANALI,19,64000,"Laying C.C. Road At MMDA 90th Street 1st Cross Street.In Div -19 ,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23440,Roads,Completed,NB-MANALI,19,364000,"Laying C.C. Road At MMDA 106th Street 1st Cross Street.In Div -19,UNIT -5,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23441,Roads,Completed,NB-MANALI,19,1055000,"Laying C.C. Road At MMDA 86th Street 1st Cross Street.In Div -19,UNIT -5, Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23442,Roads,Completed,NB-MANALI,19,80000,"Laying C.C. Road At MMDA 110th Street 1st Cross Street. div -19 , UNIT -5, Z-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/23443,Roads,Completed,NB-MANALI,19,80000,"Laying C.C. Road At MMDA 114th Street 1st Cross Street.In Dn-19,Un-5,Zn-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23444,Roads,Completed,NB-MANALI,19,157000,"Laying C.C. Road At MMDA 121st Street 1st Cross Street In Dn-19,Un-5,Zn-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/23445,Roads,Completed,NB-MANALI,19,785000,"Laying C.C. Road At Namachivayam street .In Div -19,UNIT -5,Z-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/24896,Roads,Completed,NB-MANALI,19,355500,"Laying Of CC Interior Road at Srinivasa Perumal Koil sreet. Div -19 ,UN -5, Z-2",Own Sources,2,2014-15,2016-17 NB/2014-15/25611,Roads,Completed,NB-MANALI,19,495000,"LAYING OF C.C ROAD AT JEEVA NAGAR IN DN-19,UN-4,ZN-2.",Own Sources,2,2014-15,2016-17 NB/2014-15/28073,Buildings,Completed,NB-MANALI,19,900000,"CONSTRUCTION OF WARM UP AREA AND FENCING AT INSIDE OF THE PARK AT MMDA 2ND MAIN ROAD IN DN-19,UN-5,ZN-2",Own Sources,2,2014-15,2016-17 NB/2014-15/30317,Roads,Completed,NB-MANALI,19,954000,"PROVIDING SPEED BREAKERS AT MANJAMBAKKAM LINK ROAD, M.M.D.A 1st, 97th STREET, M.M.D.A 2, 3 & 5 CROSS STREET (11 NOS) IN DN-19 UNIT-5, ZONE-02.",Own Sources,2,2014-15,2016-17 NB/2014-15/16742,Footpath,Completed,NB-MANALI,20,912000,"HARD EARTH FILLING AND LAYING OF FOOT PATH WAY IN SIDE OF BURIAL GROUND AT KAMARAJAR SALAI IN DN; 20, U; 05, Z; 02.",Own Sources,2,2014-15,2016-17 NB/2014-15/17219,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF LAKE BOUNDARY FLOOD RETAINING WALL AT KAMARAJAR SALAI (NEW M G R NAGAR 1ST STREET ) (REACH-1) IN DN 20 , UNIT 5, ZONE 02.",Own Sources,2,2014-15,2016-17 NB/2014-15/21710,Storm Water Drain,Completed,NB-MANALI,20,938000,"IMPROVEMENT WORK OF S W D AT CHINNA MATHUR ROAD ( FROM SRINIVASA PERUMAL KOIL STREET TO BALARAMAN KOIL STREET END) IN DN; 20, UNIT; 05, ZONE; 02",Own Sources,2,2014-15,2016-17 L/2014-15/27885,Electrical,Completed,L-Electrical,21,4182700,Provision of 45 Nos 6Mtr Octogonal Lamp Post with Single straight bracket with 40W to 50Watts LED Fittings at Dr.Varadharajan street Police Quarters and others street and 32 Nos of 8mtr Octogonal Lamp Post with Single Arch Bracket with 150wto 165 watts LED Fitting at PadasalaiStreet and Nedunchhezian street in Ward -21/Zone-II.,"Loans, Grants And Own Sources",2,2014-15,2016-17 NB/2014-15/21951,Buildings,Completed,NB-MANALI,21,998000,"CONSTRUCTION OF COMPOUND WALL EAST SIDE AT SANNATHY STREET (POND) DN;21, U;5, Z;2.",Own Sources,2,2014-15,2017-18 NC/2014-15/12929,Buildings,Completed,NC-MADHAVARAM,23,345000,"Ambathur Redhills Road Park in Div-23,Unit-6,Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/10097,Buildings,Completed,NC-MADHAVARAM,25,400000,"Providing of rental modular toilet on contract basis and Maintenance for one year at Nagappa Industrial Estate in Dn- 25, Unit-6, Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/23916,Roads,Completed,NC-MADHAVARAM,25,1390000,"FORMING AND LAYING BT ROAD @ RAGAVENDRA NAGAR 1ST STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2014-15,2016-17 NC/2014-15/23940,Roads,Completed,NC-MADHAVARAM,25,1712000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT DEVADOSS AVENUE IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2014-15,2016-17 NC/2014-15/29110,Buildings,Completed,NC-MADHAVARAM,25,771000,"ADDITIONAL IMPROVEMENTS TO DIVISION 25 EXITING BUILDING AT EMS STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2014-15,2016-17 NC/2014-15/10100,Parks,Completed,NC-MADHAVARAM,26,400000,"Providing of rental modular toilet on contract basis and Maintenance for one year at Majastic Colony in Dn- 26, Unit-7, Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/21959,Storm Water Drain,Completed,NC-MADHAVARAM,26,412000,"IMPROVEMENTS TO THE SIDE DRAIN AT VASANTHA NAGAR IN DIV-26, UNIT-7, ZONE-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/23835,Roads,Completed,NC-MADHAVARAM,26,323000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY PAVER FINISHER AT THANIGACHALAM NAGAR F BLOCK 2ND MAIN ROAD PART IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 NC/2014-15/23838,Roads,Completed,NC-MADHAVARAM,26,1043000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY PAVER FINISHER AT NATRAJ NAGAR 4TH CROSS STREET IN DIVISION 26 UNIT7 ZONE 3,Own Sources,3,2014-15,2016-17 NC/2014-15/23846,Roads,Completed,NC-MADHAVARAM,26,1056000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY PAVER FINISHER AT NATRAJ NAGAR 3RD CROSS STREET IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 NC/2014-15/23849,Roads,Completed,NC-MADHAVARAM,26,406000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY PAVER FINISHER AT THANIGACHALAM NAGAR F BLOCK 3RD MAIN ROAD PART IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 NC/2014-15/23851,Roads,Completed,NC-MADHAVARAM,26,2643000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY PAVER FINISHER AT NATRAJ NAGAR MAIN ROAD PART IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 B/2014-15/30340,Buildings,Completed,B-Buildings,27,4990000,"PROPOSED CONSTRUCTION OF DIVISION OFFICE AT PERUMAL KOVIL STREET BEHIND AMMA UNAVAKAM IN DN - 27, ZONE - III (MADHAVARAM)",Own Sources,3,2014-15,2016-17 NC/2014-15/10102,Buildings,Completed,NC-MADHAVARAM,27,400000,"Providing of rental modular toilet on contract basis and Maintenance for one year at Assisi Nagar in Dn- 27, Unit-7, Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/24083,Roads,Completed,NC-MADHAVARAM,27,1899000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY PAVER FINISHER AT CHELLIAMMAN KOIL 3RD CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 NC/2014-15/24086,Roads,Completed,NC-MADHAVARAM,27,599000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY PAVER FINISHER AT DHARMALINGAM NAGAR IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 NC/2014-15/18885,Roads,Completed,NC-MADHAVARAM,28,1208000,"Forming and Laying Bituminous Course by Paver Finisher at Bakthavatchalam nagar Street in Ward-28,Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18925,Roads,Completed,NC-MADHAVARAM,28,1449000,"Forming and Laying Bituminous Course by Paver finisher at Siva Padam 3rd Street inWard-28, Unit-7,Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/18926,Roads,Completed,NC-MADHAVARAM,28,644000,"Forming and Laying Bituminous Course by Paver Finisher at Padavattamman koil 2nd street 2nd lane in Ward-28, unit-7,Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/18942,Roads,Completed,NC-MADHAVARAM,28,173000,"Forming and Laying Bituminus Course by Paver finisher at Padavattamman Koilm 2nd street 3rd street in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18950,Roads,Completed,NC-MADHAVARAM,28,414000,"Forming and Laying Bituminous Course by paver finisher at Subham Nagar 2nd street in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18952,Roads,Completed,NC-MADHAVARAM,28,460000,"Forming and Laying Bituminous Course by Paver Finbisher at Subham Nagar 3rd Street in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18953,Roads,Completed,NC-MADHAVARAM,28,460000,"Forming and Laying Bituminous Course by Paver Finisher at Subham Nagar 4th Street in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18956,Roads,Completed,NC-MADHAVARAM,28,1208000,"Forming and Laying Bituminous Course by paver Finisher at Subham Nagar 5th Street in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18957,Roads,Completed,NC-MADHAVARAM,28,276000,"Forming and laying Bituminous Course by paver finisher at Padavattamman Koil 1st Lane in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18958,Roads,Completed,NC-MADHAVARAM,28,207000,"Forming and Laying Bituminous Course by Paver Finisher at Padavattamman Koil 2nd Lane in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18959,Roads,Completed,NC-MADHAVARAM,28,759000,"Forming and Laying Bituminous Course by Paver Finisher at Padavattamman Koil Kannika Street in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18960,Roads,Completed,NC-MADHAVARAM,28,552000,"Forming and Laying Bituminous Course by Paver Finisher at Padavattamman Koil 2ndStreet Danapal Street in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18961,Roads,Completed,NC-MADHAVARAM,28,1207000,"Forming and Laying Bituminous Course by Paver Finisher at Padavattamman Koil 2nd Street in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18962,Roads,Completed,NC-MADHAVARAM,28,552000,"Forming and Laying Bituminous Course by Paver Finisher at Padavattamman Koil 2nd Street 1st Lane in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18963,Roads,Completed,NC-MADHAVARAM,28,207000,"Forming and Laying Bituminous Course by Paver Finbnisher at Padavattamman Koil 2nd stret 4th Lane street in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18964,Roads,Completed,NC-MADHAVARAM,28,316000,"Forming and Laying Bituminous Course by Paver Finisher at Padavattamman koil 3rd Street in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18965,Roads,Completed,NC-MADHAVARAM,28,736000,"Forming and Laying Bituminous Course By Paver Finisher at Padavattamman Koil 4th street in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18966,Roads,Completed,NC-MADHAVARAM,28,1127000,"Forming and laying Bituminous /Course by paver Finisher at Varadappa Street K.K. Thazhai in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18967,Roads,Completed,NC-MADHAVARAM,28,443000,"Forming and Laying Bituminous Course by Paver Finisher at Kethsamane Nagar Street in Ward-28, Unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18968,Roads,Completed,NC-MADHAVARAM,28,759000,"Forming and laying Bituminous Course by Paver Finisher at Kannika Garden Street in Ward-28, unit-7,Zone-4.",Own Sources,3,2014-15,2016-17 NC/2014-15/18969,Roads,Completed,NC-MADHAVARAM,28,2576000,"Forming and Laying Bituminous Course By Paver Finisher at Vasugi nagar main Road (Pattammal Main road) in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18970,Roads,Completed,NC-MADHAVARAM,28,805000,"Forming and laying Bituminous Course by Paver Finisher at Vasugi Nagar 1st Street (Pattammal 1st Street) in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18971,Roads,Completed,NC-MADHAVARAM,28,805000,"Forming and Laying Bituminous /course by paver Finisher at Vasugi Nagar 2nd Street (Pattammal 2nd Street) in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18972,Roads,Completed,NC-MADHAVARAM,28,863000,"Forming and Laying Bituminous Course by Paver Finisher at Vasugi nagar 3rd Street 9 Pattammal 3rd Street) in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18973,Roads,Completed,NC-MADHAVARAM,28,1932000,"Forming and Laying Bituminous Course by Paver Finisher at Siva Padam 1st Street K.K. Thahai in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/18974,Roads,Completed,NC-MADHAVARAM,28,1397000,"Forming and Laying Bituminous Course by paver Finisher at Siva padam 2nd street K.K.Thazhai in Ward-28, unit-7,Zone-3.",Own Sources,3,2014-15,2016-17 NC/2014-15/23860,Roads,Completed,NC-MADHAVARAM,28,711000,"LAYING CEMENT CONCRETE ROAD BY RMC30 AT NAGAPPAN STREET, PERIYASEKKADU IN DIVISION 28 UNIT 7 ZONE 3",Own Sources,3,2014-15,2016-17 NC/2014-15/23868,Roads,Completed,NC-MADHAVARAM,28,355000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT KASI STREET PERIYASEKKADU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 NC/2014-15/23892,Roads,Completed,NC-MADHAVARAM,28,535000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT LOGU STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2014-15,2016-17 RN/2014-15/12992,Buildings,Completed,B-Buildings,28,4990000,"PROPOSED CONSTRUCTION OF DIVISION OFFICE AT ARUL NAGAR NEAR AMMA UNAVAKAM IN DN - 28, ZONE - III (MADHAVARAM",Own Sources,3,2014-15,2016-17 NC/2014-15/12416,Parks,Completed,NC-MADHAVARAM,30,565000,"Annual MAINTENANCE of Park at V R D Nagar DN-30,Unit-08,Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/9489,Parks,Completed,NC-MADHAVARAM,31,570000,Annual Maintenance of Park at K K R GARDEN PARK DN-31 Unite-08 Zone-3 (Qualified Horticulturist only),Own Sources,3,2014-15,2016-17 NC/2014-15/9491,Parks,Completed,NC-MADHAVARAM,31,530000,ANNUAL MAINTENANCE OF PARK AT K K R NAGAR DN-31 UNITE-08 ZONE--3 (Qualified horticulturist only),Own Sources,3,2014-15,2016-17 NC/2014-15/11476,Parks,Completed,NC-MADHAVARAM,32,400000,"Annual Maintenance to the Park at Lakshmipuram Teachers Colony 6th Main Road in Division 32,Unit-8,Zone 3(Qualified horticulturist for Maintenance work)",Own Sources,3,2014-15,2016-17 NC/2014-15/11478,Parks,Completed,NC-MADHAVARAM,32,410000,"Maintenance to the Park at Lakshmipuram Teachers Colony 4TH cross street in Division 32,Unit-8,Zone 3(Qualified horticulturist for Maintenance work)",Own Sources,3,2014-15,2016-17 NC/2014-15/21016,Buildings,Completed,NC-MADHAVARAM,32,995000,"Construction of Compound Wall to OSR Land at Teachers Colony 5th Main Road (North and Eastern sides) in Ward-32, Unit-8,Zone-3.",Own Sources,3,2014-15,2017-18 NC/2014-15/0268,Parks,Completed,NC-MADHAVARAM,33,347000,"Annual Maintenance of V G P Santhosh Nagar Park in Dn-33, Unit-8, Zone-3",Own Sources,3,2014-15,2016-17 NC/2014-15/10105,Parks,Completed,NC-MADHAVARAM,33,400000,Providing of rental modular toilet on contract basis and Maintenance for one year at Vasu Nagar 80 Feet Road in Division 33 Unit 8 Zone 3,Own Sources,3,2014-15,2016-17 NC/2014-15/11475,Parks,Completed,NC-MADHAVARAM,33,372000,"Annual Maintenance to the Park at Thanigachalam Nagar,B'Block 5th Main Road in Division 33,Unit 8, Zone 3(Qualified Horticulturist For Maintenance work)",Own Sources,3,2014-15,2016-17 NC/2014-15/12489,Parks,Completed,NC-MADHAVARAM,33,355000,"Annual Maintenance to the Park at Selvam Nagar Park in Division 33,Unit 8, Zone 3 (Qualified Horticulturist For Maintenance work)",Own Sources,3,2014-15,2016-17 L/2014-15/29008,Electrical,Completed,L-Electrical,34,1737300,"Provision of 38 Nos of 6Mtrs Lamp Post With Hot Dip Zinc Galvanising with Single Arch Bracket with 90W LED Fitting at Vedhanda Murgappan main Road in Division -34, Zone -4",Own Sources,4,2014-15,2016-17 L/2014-15/29046,Electrical,Completed,L-Electrical,34,1243000,"Provision of 27 Nos of 6Mtrs Street Lamp Post with SIngle Arch Bracket with 90W LED Fitting at RIswan Road in Division - 34, ZOne - 4",Own Sources,4,2014-15,2016-17 ND/2014-15/14104,Parks,Completed,ND-TONDIARPET,34,955000,"ANNUAL MAINTENANCE TO PARKS AT VENKATESWARA COLONY 5THSTREET, UNION CARPIT COLONY 14TH STREET, BINNYNAGAR MAIN ROAD, KAVARI NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27587,Roads,Completed,ND-TONDIARPET,34,943000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARASIMMA REDDIYAR NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27589,Roads,Completed,ND-TONDIARPET,34,881000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARASIMMA REDDIYAR NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27593,Roads,Completed,ND-TONDIARPET,34,825000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARASIMMA REDDIYAR NAGAR 4th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27594,Roads,Completed,ND-TONDIARPET,34,380000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARASIMMA REDDIYAR NAGAR 4th CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27597,Roads,Completed,ND-TONDIARPET,34,2472000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 1st MAINROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27598,Roads,Completed,ND-TONDIARPET,34,154000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27599,Roads,Completed,ND-TONDIARPET,34,2744000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 2nd MAINROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27600,Roads,Completed,ND-TONDIARPET,34,760000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27601,Roads,Completed,ND-TONDIARPET,34,2130000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 3rd MAINROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27602,Roads,Completed,ND-TONDIARPET,34,529000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27603,Roads,Completed,ND-TONDIARPET,34,628000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 4th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27604,Roads,Completed,ND-TONDIARPET,34,1337000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 5th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27605,Roads,Completed,ND-TONDIARPET,34,522000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 6th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27608,Roads,Completed,ND-TONDIARPET,34,371000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARAYANASWAMMY GARDEN 8th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27610,Roads,Completed,ND-TONDIARPET,34,1132000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT PARVATHY NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27611,Roads,Completed,ND-TONDIARPET,34,603000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT PARVATHY NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27612,Roads,Completed,ND-TONDIARPET,34,794000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT PARVATHY NAGAR 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27613,Roads,Completed,ND-TONDIARPET,34,2406000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27614,Roads,Completed,ND-TONDIARPET,34,4177000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27615,Roads,Completed,ND-TONDIARPET,34,3264000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27617,Roads,Completed,ND-TONDIARPET,34,596000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 4th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27618,Roads,Completed,ND-TONDIARPET,34,1190000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 5th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27619,Roads,Completed,ND-TONDIARPET,34,2513000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 6th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27620,Roads,Completed,ND-TONDIARPET,34,655000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 7th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27623,Roads,Completed,ND-TONDIARPET,34,587000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 8th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27624,Roads,Completed,ND-TONDIARPET,34,3116000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 9th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27627,Roads,Completed,ND-TONDIARPET,34,455000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 11th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27628,Roads,Completed,ND-TONDIARPET,34,546000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 12th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27631,Roads,Completed,ND-TONDIARPET,34,556000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 13th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27632,Roads,Completed,ND-TONDIARPET,34,4511000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 14th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27633,Roads,Completed,ND-TONDIARPET,34,347000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 15th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27634,Roads,Completed,ND-TONDIARPET,34,440000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 16th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27635,Roads,Completed,ND-TONDIARPET,34,1006000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 17th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27636,Roads,Completed,ND-TONDIARPET,34,3892000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 18th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27637,Roads,Completed,ND-TONDIARPET,34,547000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 19th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27639,Roads,Completed,ND-TONDIARPET,34,1547000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 21th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27640,Roads,Completed,ND-TONDIARPET,34,467000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT UNION CARBIDE COLONY 22th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27641,Roads,Completed,ND-TONDIARPET,34,6856000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SCHOOL ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27642,Roads,Completed,ND-TONDIARPET,34,692000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27643,Roads,Completed,ND-TONDIARPET,34,1038000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY 4th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27644,Roads,Completed,ND-TONDIARPET,34,1232000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY 5th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27645,Roads,Completed,ND-TONDIARPET,34,1475000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY 6th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27646,Roads,Completed,ND-TONDIARPET,34,470000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY 9th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27647,Roads,Completed,ND-TONDIARPET,34,463000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY 8th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27648,Roads,Completed,ND-TONDIARPET,34,3917000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27650,Roads,Completed,ND-TONDIARPET,34,717000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27651,Roads,Completed,ND-TONDIARPET,34,3208000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27652,Roads,Completed,ND-TONDIARPET,34,3196000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27654,Roads,Completed,ND-TONDIARPET,34,1488000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 4th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27655,Roads,Completed,ND-TONDIARPET,34,1624000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 1st CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27656,Roads,Completed,ND-TONDIARPET,34,938000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 2nd CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27657,Roads,Completed,ND-TONDIARPET,34,914000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 3rd CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27659,Roads,Completed,ND-TONDIARPET,34,960000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-1) 4th CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27660,Roads,Completed,ND-TONDIARPET,34,2881000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-2) 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27662,Roads,Completed,ND-TONDIARPET,34,2636000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-2) 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27663,Roads,Completed,ND-TONDIARPET,34,2040000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-2) 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27664,Roads,Completed,ND-TONDIARPET,34,1156000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA NAGAR (PART-2) 1st CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27673,Roads,Completed,ND-TONDIARPET,34,3964000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SOLAIAMMAN KOIL MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27675,Roads,Completed,ND-TONDIARPET,34,1393000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT LAKSHMI AMMAN KOIL STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27676,Roads,Completed,ND-TONDIARPET,34,4220000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT BINNY NAGAR MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27677,Roads,Completed,ND-TONDIARPET,34,577000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT M.R.L COLONY 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27678,Roads,Completed,ND-TONDIARPET,34,937000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SAGAYA NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27679,Roads,Completed,ND-TONDIARPET,34,4763000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT MILK COLONY ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27680,Roads,Completed,ND-TONDIARPET,34,2087000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT RISWAN SALAI IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27681,Roads,Completed,ND-TONDIARPET,34,534000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KATTABOMMAN 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27682,Roads,Completed,ND-TONDIARPET,34,678000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KATTABOMMAN 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27683,Roads,Completed,ND-TONDIARPET,34,1209000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KATTABOMMAN 6th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27684,Roads,Completed,ND-TONDIARPET,34,1451000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KATTABOMMAN 7th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27685,Roads,Completed,ND-TONDIARPET,34,1130000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KATTABOMMAN 9th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27687,Roads,Completed,ND-TONDIARPET,34,1899000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT JAI BALAJI NAGAR 1st MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27689,Roads,Completed,ND-TONDIARPET,34,548000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT JAI BALAJI NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27690,Roads,Completed,ND-TONDIARPET,34,516000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT JAI BALAJI NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27691,Roads,Completed,ND-TONDIARPET,34,706000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT JAI BALAJI NAGAR 1st CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27692,Roads,Completed,ND-TONDIARPET,34,780000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SENTHIL NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27693,Roads,Completed,ND-TONDIARPET,34,904000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SENTHIL NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27694,Roads,Completed,ND-TONDIARPET,34,1251000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SENTHIL NAGAR MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27695,Roads,Completed,ND-TONDIARPET,34,263000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KUMARAN NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27696,Roads,Completed,ND-TONDIARPET,34,429000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KUMARAN NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27697,Roads,Completed,ND-TONDIARPET,34,352000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KUMARAN NAGAR 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27698,Roads,Completed,ND-TONDIARPET,34,299000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KUMARAN NAGAR MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27699,Roads,Completed,ND-TONDIARPET,34,318000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARASIMMA REDDIYAR NAGAR 5th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27700,Roads,Completed,ND-TONDIARPET,34,1454000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VENKATESWARA COLONY 7th STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27701,Roads,Completed,ND-TONDIARPET,34,1136000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT CHINNA PAPPAMMAL STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27702,Roads,Completed,ND-TONDIARPET,34,1077000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT ANNAI AVENUE 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27704,Roads,Completed,ND-TONDIARPET,34,1030000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT ANNAI AVENUE 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27705,Roads,Completed,ND-TONDIARPET,34,1283000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT ANNAI AVENUE 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27706,Roads,Completed,ND-TONDIARPET,34,1134000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT RAGAVENDHRA NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/27707,Roads,Completed,ND-TONDIARPET,34,1312000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT RAGAVENDHRA NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 ND/2014-15/29084,Roads,Completed,ND-TONDIARPET,34,383000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NARASIMMA REDDIYAR NAGAR 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2014-15,2016-17 BR/2014-15/30040,Roads,Completed,BR-Bus Route Roads,35,15633000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Muthamil Nagar North Avenue(from the junction of Tondiarpet High Road to the junction of West Avenue ), Division 35 , Zone - IV",Grants,4,2014-15,2016-17 BR/2014-15/30041,Roads,Completed,BR-Bus Route Roads,35,69028000,Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Tondiarpet High Road(from the Junction of Kodungaiyur Dumping Ground to the Junction of M.R.Nagar Market) IN DN 35 & 37 Zone IV,Grants,4,2014-15,2016-17 L/2014-15/29019,Electrical,Completed,L-Electrical,35,2582500,"Provision of 38 Nos. of 8Mtr G.I Octagonal Lamp Post with Single Arch Bracket with 165W LED Fitting at Tondiarpet High Road in Dn:35, Zone IV",Own Sources,4,2014-15,2016-17 L/2014-15/29030,Electrical,Completed,L-Electrical,35,1022200,"Provision of 23 Nos.of 6 Mtr Lamp Post with Single Arch Bracket with 90W LED Fitting at North Avenue Road in Dn:35, Zone IV.",Own Sources,4,2014-15,2016-17 L/2014-15/29040,Electrical,Completed,L-Electrical,35,1068300,Provision of 24 Nos of 6Mtr lamp Post with Single Arch Bracket with 90W LED Fitting at South Avenue Road in Division -35 Zone -4,Own Sources,4,2014-15,2016-17 ND/2014-15/18976,Parks,Completed,ND-TONDIARPET,35,970000,"ANNUAL MAINTENANCE WORK PARK AT 9TH STREET MUTHAMIZH NAGAR AND KRISHNAN PARK IN DN-35, UNIT-09, ZONE-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26823,Roads,Completed,ND-TONDIARPET,35,212000,"Relaying of Cement Concrete Road by RMC M30 Grade at A.P.Arasu 1st lane, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26824,Roads,Completed,ND-TONDIARPET,35,212000,"Relaying of Cement Concrete Road by RMC M30 Grade at A.P.Arasu 2nd lane, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26825,Roads,Completed,ND-TONDIARPET,35,283000,"Relaying of Cement Concrete Road by RMC M30 Grade at A.P.Arasu 3rd Lane, in Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26826,Roads,Completed,ND-TONDIARPET,35,297000,"Relaying of Cement Concrete Road by RMC M30 Grade at A.P.Arasu 5th Lane, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26827,Roads,Completed,ND-TONDIARPET,35,1555000,"Relaying of Cement Concrete Road by RMC M30 Grade at A.P.Arasu Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26828,Roads,Completed,ND-TONDIARPET,35,283000,"Relaying of Cement Concrete Road by RMC M30 Grade at ,Ambedkar 1st lane in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26829,Roads,Completed,ND-TONDIARPET,35,562000,"Relaying of Cement Concrete Road by RMC M30 Grade at Ambedkar street (Erukkencherry) in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26830,Roads,Completed,ND-TONDIARPET,35,219000,"Relaying of Cement Concrete Road by RMC M30 Grade at Indra nagar (West) lane , Division- 35,Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26831,Roads,Completed,ND-TONDIARPET,35,837000,"Relaying of Cement Concrete Road by RMC M30 Grade at Ambedkar 2nd lane (Chinnady madam) , Division-35 ,Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26836,Roads,Completed,ND-TONDIARPET,35,1285000,"Relaying of Cement Concrete Road by RMC M30 Grade at Anna Salai 2nd Cross Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26843,Roads,Completed,ND-TONDIARPET,35,438981,"Relaying of Cement Concrete Road by RMC M30 Grade at Bharathi dasan street (Kodungaiyur) Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26844,Roads,Completed,ND-TONDIARPET,35,1406000,"Relaying of Cement Concrete Road by RMC M30 Grade at Nayanar Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26845,Roads,Completed,ND-TONDIARPET,35,5207000,"Relaying of Cement Concrete Road by RMC M30 Grade at Anna Main Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26846,Roads,Completed,ND-TONDIARPET,35,532000,"Relaying of Cement Concrete Road by RMC M30 Grade at Chinna thambiran street in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26847,Roads,Completed,ND-TONDIARPET,35,340000,"Relaying of Cement Concrete Road by RMC M30 Grade at Dr. Anna Salai 1st Street,(Kodungaiur), Division -35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26848,Roads,Completed,ND-TONDIARPET,35,944000,"Relaying of Cement Concrete Road by RMC M30 Grade at Kailasan Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26849,Roads,Completed,ND-TONDIARPET,35,1825000,"Relaying of Cement Concrete Road by RMC M30 Grade at Indra Nagar West, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26851,Roads,Completed,ND-TONDIARPET,35,2649000,"Relaying of Cement Concrete Road by RMC M30 Grade at Jayapranjothi Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26852,Roads,Completed,ND-TONDIARPET,35,887000,"Relaying of Cement Concrete Road by RMC M30 Grade at Rettamalai Srinivasan Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26858,Roads,Completed,ND-TONDIARPET,35,2045000,"Relaying of Cement Concrete Road by RMC M30 Grade at Meenambal Sivaraj Street (party), in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26859,Roads,Completed,ND-TONDIARPET,35,1263000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 171th Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26860,Roads,Completed,ND-TONDIARPET,35,1832000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 172nd street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26861,Roads,Completed,ND-TONDIARPET,35,546000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 173th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26862,Roads,Completed,ND-TONDIARPET,35,553000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 174th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26863,Roads,Completed,ND-TONDIARPET,35,461000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 178th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26864,Roads,Completed,ND-TONDIARPET,35,461000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 180th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26865,Roads,Completed,ND-TONDIARPET,35,603000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 197th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26866,Roads,Completed,ND-TONDIARPET,35,802000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 198th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26868,Roads,Completed,ND-TONDIARPET,35,212000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 200th Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26869,Roads,Completed,ND-TONDIARPET,35,212000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 201th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26870,Roads,Completed,ND-TONDIARPET,35,1256000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 202 th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26871,Roads,Completed,ND-TONDIARPET,35,1477000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 203th Street in Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26872,Roads,Completed,ND-TONDIARPET,35,340000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 204th street in Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26873,Roads,Completed,ND-TONDIARPET,35,532000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil Nagar 205th street, in Division -35 , Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26874,Roads,Completed,ND-TONDIARPET,35,269000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil Nagar 206th street, in Division -35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26875,Roads,Completed,ND-TONDIARPET,35,269000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil Nagar 207th street, in Division -35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26877,Roads,Completed,ND-TONDIARPET,35,269000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil Nagar 209th street, in Division -35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26878,Roads,Completed,ND-TONDIARPET,35,1832000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil Nagar 210th street, in Division -35 Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26879,Roads,Completed,ND-TONDIARPET,35,2542000,"Relaying of Cement Concrete Road by RMC M30 Grade at N.V.N Street Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26880,Roads,Completed,ND-TONDIARPET,35,1079000,"Relaying of Cement Concrete Road by RMC M30 Grade at C.S.I. School Street, Kodungaiyur ,Division -35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26881,Roads,Completed,ND-TONDIARPET,35,716000,"Relaying of Cement Concrete Road by RMC M30 Grade at Sathiyavani muthu street (Chinnandi madam), Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26882,Roads,Completed,ND-TONDIARPET,35,2045000,"Relaying of Cement Concrete Road by RMC M30 Grade at Selva Perumal koil street (Chinnandi madam) Division -35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26885,Roads,Completed,ND-TONDIARPET,35,1398000,"Relaying of Cement Concrete Road by RMC M30 Grade at Manavalzhar street ,Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26886,Roads,Completed,ND-TONDIARPET,35,2066000,"Relaying of Cement Concrete Road by RMC M30 Grade at Kumaran street ,Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26887,Roads,Completed,ND-TONDIARPET,35,525000,"Relaying of Cement Concrete Road by RMC M30 Grade at Rajavelu street (Erukkanchery) ,Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/28270,Roads,Completed,ND-TONDIARPET,35,3503000,"Relaying of Road with BC by Paver Finish in South Avenue (From TH Road to Mask) in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28577,Roads,Completed,ND-TONDIARPET,35,3507000,"Relaying of Road with BC by Paver Finish in West Avenue Road in Muthamil Nagar (From South Avenue to Ambedkar street) in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28578,Roads,Completed,ND-TONDIARPET,35,3096000,"Relaying of Road with BC by Paver Finish in South Avenue (From West Avenue to Mask) in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28580,Roads,Completed,ND-TONDIARPET,35,2419000,"Relaying of Road with BC by Paver Finish in Cauvery Salai Main road in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28581,Roads,Completed,ND-TONDIARPET,35,1037000,"Relaying of Road with BC by Paver Finish in E.V.R. Periyar Street (Kodungaiyur) in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28582,Roads,Completed,ND-TONDIARPET,35,670000,"Relaying of Road with BC by Paver Finish in Muthamil nagar 5th Block 111st street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28583,Roads,Completed,ND-TONDIARPET,35,670000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 112th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28584,Roads,Completed,ND-TONDIARPET,35,622000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 113th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28585,Roads,Completed,ND-TONDIARPET,35,245000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 114th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28586,Roads,Completed,ND-TONDIARPET,35,177000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 115th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28587,Roads,Completed,ND-TONDIARPET,35,301000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 116th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28588,Roads,Completed,ND-TONDIARPET,35,231000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 117th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28589,Roads,Completed,ND-TONDIARPET,35,202000,"Relaying of Road with BC by Paver Finish in West Avenue Muthamil Nagar Vth Block 118th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28590,Roads,Completed,ND-TONDIARPET,35,208000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 119th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28591,Roads,Completed,ND-TONDIARPET,35,83000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 120th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28592,Roads,Completed,ND-TONDIARPET,35,201000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 121th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28593,Roads,Completed,ND-TONDIARPET,35,258000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 122nd Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28594,Roads,Completed,ND-TONDIARPET,35,213000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 123th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28597,Roads,Completed,ND-TONDIARPET,35,1002000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 126th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28599,Roads,Completed,ND-TONDIARPET,35,203000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 128th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28600,Roads,Completed,ND-TONDIARPET,35,209000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 129th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28601,Roads,Completed,ND-TONDIARPET,35,238000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar Vth Block 130th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28607,Roads,Completed,ND-TONDIARPET,35,934000,"Relaying of Road with BC by Paver Finish at Muthamil Nagar VIIth Block 176th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28608,Roads,Completed,ND-TONDIARPET,35,506000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIIth Block179th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28612,Roads,Completed,ND-TONDIARPET,35,388000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VI th Block 143th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28623,Roads,Completed,ND-TONDIARPET,35,426000,"Relaying of Road with BC by Paver Finish in Muthamil nagar VIth Block156th street in in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28627,Roads,Completed,ND-TONDIARPET,35,213000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar 6th Block 160th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28629,Roads,Completed,ND-TONDIARPET,35,222000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIth Block 162nd Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28630,Roads,Completed,ND-TONDIARPET,35,200000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIth Block 163rd Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28631,Roads,Completed,ND-TONDIARPET,35,532000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VI th Block 164th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28632,Roads,Completed,ND-TONDIARPET,35,1374000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIIIth Block 192nd Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28633,Roads,Completed,ND-TONDIARPET,35,1361000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIIIth Block 191st Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28634,Roads,Completed,ND-TONDIARPET,35,381000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIIIth Block 196th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28635,Roads,Completed,ND-TONDIARPET,35,3512000,"Relaying of Road with BC by Paver Finish in West Avenue (From South Avenue to 61st Street) in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28637,Roads,Completed,ND-TONDIARPET,35,582000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIth Block 155th Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28639,Roads,Completed,ND-TONDIARPET,35,136000,"Relaying of Road with BC by Paver Finish in Muthamil Nagar VIth Block 153rd Street in DN-35, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 BR/2014-15/29877,Roads,Completed,BR-Bus Route Roads,36,22442000,"Name of Work : Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Tratfic improvement works at MKB Nagar West Avenue road ( from the junction of Erukkencheri High Road to the middle of the Meenambal Bridge )in Division 36 , Zone - IV.",Grants,4,2014-15,2016-17 BR/2014-15/29878,Roads,Completed,BR-Bus Route Roads,36,23380000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Ethiraj Samy Salai ( from the Junction of Erukkancheri High road to the Junction of M.R. Nagar) Division 36 , Zone - IV",Grants,4,2014-15,2016-17 L/2014-15/29078,Electrical,Completed,L-Electrical,36,2047700,"Provision of 30 Nos. of 8 Mtr G.I Octagonal Lamp Post with Single bracket with 165W LED Fitting at Ethirajsami Salai in Dn:36, Zone IV",Own Sources,4,2014-15,2016-17 ND/2014-15/19025,Parks,Completed,ND-TONDIARPET,36,500000,"ANNUAL MAINTENANCE OF PARK WORK AT VASUKI NAGAR PARK IN DN-36, UNIT-09, ZONE-04",Own Sources,4,2014-15,2016-17 ND/2014-15/19026,Parks,Completed,ND-TONDIARPET,36,508000,"ANNUAL MAINTENANCE OF PARK WORK AT INDIRA GANDHI NAGAR ERUKENCHERY MAIN ROAD IN DN-36, UNIT-09, ZONE-04",Own Sources,4,2014-15,2016-17 ND/2014-15/19068,Parks,Completed,ND-TONDIARPET,36,442000,"ANNUAL MAINTENANCE OF PARK WORK AT BHARATHY PARK AT IN DN-36, UNIT-09, ZONE-04",Own Sources,4,2014-15,2016-17 ND/2014-15/19349,Parks,Completed,ND-TONDIARPET,36,522000,"ANNUAL MAINTENANCE OF PARK WORK AT M.R NAGAR IST MAIN ROAD IN DN-36, UNIT-09, ZONE-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26246,Roads,Completed,ND-TONDIARPET,36,2168000,"Laying Cement Concrete Road By RMC At S.A Colony 2nd Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26286,Roads,Completed,ND-TONDIARPET,36,2181000,"Laying Cement Concrete Road By RMC At S.A Colony 4th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26326,Roads,Completed,ND-TONDIARPET,36,1605000,"Laying Cement Concrete Road By RMC At S.A Colony 6th street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26356,Roads,Completed,ND-TONDIARPET,36,1772000,"Laying Cement Concrete Road By RMC At S.A colony 7th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26362,Roads,Completed,ND-TONDIARPET,36,1224000,"Laying Cement Concrete Road At S.A Colony 8th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26420,Roads,Completed,ND-TONDIARPET,36,830000,"Laying Cement Concrete Road By RMC At S.A Colony 9th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26433,Roads,Completed,ND-TONDIARPET,36,830000,"Laying Cement Concrete Road By RMC At S.A Colony 10th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26775,Roads,Completed,ND-TONDIARPET,36,727000,"Laying Cement Concrete Road By RMC At Gandhi Nagar 1st Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26780,Roads,Completed,ND-TONDIARPET,36,727000,"Laying Cement Concrete Road By RMC At Gandhi Nagar 2nd Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26784,Roads,Completed,ND-TONDIARPET,36,727000,"Laying Cement Concrete Road By RMC At Gandhi Nagar 3rd Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26786,Roads,Completed,ND-TONDIARPET,36,439000,"Laying cement Concrete Road By RMC At Gandhi Nagar 4th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26796,Roads,Completed,ND-TONDIARPET,36,727000,"Laying Cement Concrete By RMC At Gandhi Nagar 5th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26800,Roads,Completed,ND-TONDIARPET,36,673000,"Laying Cement Concrete Road By RMC At Gandhi Nagar 6th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26922,Roads,Completed,ND-TONDIARPET,36,585000,"Laying Cement Concrete Road By RMC At Gandhi nagar 7th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26924,Roads,Completed,ND-TONDIARPET,36,2211000,"Laying Cement Concrete Road By RMC At Gandhi Nagar 8th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26925,Roads,Completed,ND-TONDIARPET,36,277000,"Laying Cement Concrete Road By RMC At Pudhu Nagar 1 Cross Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26926,Roads,Completed,ND-TONDIARPET,36,212000,"Laying Cement Concrete Road By RMC At Pudhu Nagar 1st Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26927,Roads,Completed,ND-TONDIARPET,36,452000,"Laying Cement Concrete Road By RMC At Pudhu Nagar 2nd Cross Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26928,Roads,Completed,ND-TONDIARPET,36,138000,"Laying Cement Concrete Road By RMC At Pudhu Nagar 2nd Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26950,Roads,Completed,ND-TONDIARPET,36,138000,"Laying Cement Concrete Road By RMC At Pudhu Nagar 3rd Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26952,Roads,Completed,ND-TONDIARPET,36,138000,"Laying Cement Concrete Road By RMC At Pudhu Nagar 4th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/26957,Roads,Completed,ND-TONDIARPET,36,138000,"Laying Cement Concrete Road By RMC At Pudhu Nagar 5th Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28477,Roads,Completed,ND-TONDIARPET,36,3006000,"Relaying of B.T course By Paver At Dr.Radhakrishnan Salai in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28515,Roads,Completed,ND-TONDIARPET,36,3268000,"Relaying of B.T course By Paver At T.V.K 1st Link Road in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28518,Roads,Completed,ND-TONDIARPET,36,2081000,"Relaying of B.T course By Paver At T.V.K 1st Link Road (T.V Nagar) in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28542,Roads,Completed,ND-TONDIARPET,36,597000,"Relaying of B.T course By Paver At T.V.K 1st Link extension Road in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28569,Roads,Completed,ND-TONDIARPET,36,2379000,"Relaying of B.T course By Paver At Vadiudaiamman Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28573,Roads,Completed,ND-TONDIARPET,36,597000,"Relaying of B.T course By Paver At Valmeegi Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28658,Roads,Completed,ND-TONDIARPET,36,632000,"Relaying of BT Course By Paver At 10th West Cross Street in DN-36, U-09, Z-04",Own Sources,4,2014-15,2016-17 BR/2014-15/29884,Roads,Completed,BR-Bus Route Roads,37,29638000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Meenambal Salai (from the junction of Tondiarpet High Road to the middle of Meenambal Bridge)in Division 37 , Zone - IV",Grants,4,2014-15,2016-17 BR/2014-15/30146,Roads,Completed,BR-Bus Route Roads,37,10448000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at TVK Link Road(East) (from the junction of Tondiarpet High Road to Sathyamurthy Nagar ) Division37, Zone - IV",Grants,4,2014-15,2016-17 ND/2014-15/26364,Roads,Completed,ND-TONDIARPET,37,726000,"Relaying of Cement Concrete Road by RMC M30 Grade at 3rd Street m.g.r. Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26365,Roads,Completed,ND-TONDIARPET,37,472000,"Relaying of Cement Concrete Road by RMC M30 Grade at 3rd Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26366,Roads,Completed,ND-TONDIARPET,37,1420000,"Relaying of Cement Concrete Road by RMC M30 Grade at 4th Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26367,Roads,Completed,ND-TONDIARPET,37,843000,"Relaying of Cement Concrete Road by RMC M30 Grade at 4th Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26368,Roads,Completed,ND-TONDIARPET,37,1300000,"Relaying of Cement Concrete Road by RMC M30 Grade at 4th Street jagajeevan ram Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26369,Roads,Completed,ND-TONDIARPET,37,558814,"Relaying of Cement Concrete Road by RMC M30 Grade at 4th Street m.g.r. Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26370,Roads,Completed,ND-TONDIARPET,37,250000,"Relaying of Cement Concrete Road by RMC M30 Grade at 4th Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26371,Roads,Completed,ND-TONDIARPET,37,254000,"Relaying of Cement Concrete Road by RMC M30 Grade at 5th Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26372,Roads,Completed,ND-TONDIARPET,37,1100000,"Relaying of Cement Concrete Road by RMC M30 Grade at 5th Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26373,Roads,Completed,ND-TONDIARPET,37,1386000,"Relaying of Cement Concrete Road by RMC M30 Grade at 5th Street jagajeevan ram Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26374,Roads,Completed,ND-TONDIARPET,37,959000,"Relaying of Cement Concrete Road by RMC M30 Grade at 5th Street m.g.r. Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26375,Roads,Completed,ND-TONDIARPET,37,433000,"Relaying of Cement Concrete Road by RMC M30 Grade at 5th Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26376,Roads,Completed,ND-TONDIARPET,37,388000,"Relaying of Cement Concrete Road by RMC M30 Grade at 6th cross Street m.g.r. Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26377,Roads,Completed,ND-TONDIARPET,37,250000,"Relaying of Cement Concrete Road by RMC M30 Grade at 6th Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26378,Roads,Completed,ND-TONDIARPET,37,827000,"Relaying of Cement Concrete Road by RMC M30 Grade at 6th Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26379,Roads,Completed,ND-TONDIARPET,37,1398000,"Relaying of Cement Concrete Road by RMC M30 Grade at 6th Street jagajeevan ram Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26380,Roads,Completed,ND-TONDIARPET,37,388000,"Relaying of Cement Concrete Road by RMC M30 Grade at 6th Street m.g.r. Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26381,Roads,Completed,ND-TONDIARPET,37,387000,"Relaying of Cement Concrete Road by RMC M30 Grade at 6th Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26382,Roads,Completed,ND-TONDIARPET,37,259000,"Relaying of Cement Concrete Road by RMC M30 Grade 7th Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26383,Roads,Completed,ND-TONDIARPET,37,920000,"Relaying of Cement Concrete Road by RMC M30 Grade at 7th Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26384,Roads,Completed,ND-TONDIARPET,37,966000,"Relaying of Cement Concrete Road by RMC M30 Grade at 7th Street jagajeevan ram Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26385,Roads,Completed,ND-TONDIARPET,37,388000,"Relaying of Cement Concrete Road by RMC M30 Grade at 7th Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26386,Roads,Completed,ND-TONDIARPET,37,1042000,"Relaying of Cement Concrete Road by RMC M30 Grade at 8th Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26387,Roads,Completed,ND-TONDIARPET,37,875000,"Relaying of Cement Concrete Road by RMC M30 Grade at 8th Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26388,Roads,Completed,ND-TONDIARPET,37,963000,"Relaying of Cement Concrete Road by RMC M30 Grade at 8th Street jagajeevan ram Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26389,Roads,Completed,ND-TONDIARPET,37,385000,"Relaying of Cement Concrete Road by RMC M30 Grade at 8th Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26390,Roads,Completed,ND-TONDIARPET,37,1037000,"Relaying of Cement Concrete Road by RMC M30 Grade at 9th Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26392,Roads,Completed,ND-TONDIARPET,37,435000,"Relaying of Cement Concrete Road by RMC M30 Grade at 9th Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26393,Roads,Completed,ND-TONDIARPET,37,924000,"Relaying of Cement Concrete Road by RMC M30 Grade at Link Road dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26394,Roads,Completed,ND-TONDIARPET,37,1300000,"Relaying of Cement Concrete Road by RMC M30 Grade at Link Road dhamodar nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26397,Roads,Completed,ND-TONDIARPET,37,1042000,"Relaying of Cement Concrete Road by RMC M30 Grade at 10th debar nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26398,Roads,Completed,ND-TONDIARPET,37,1042000,"Relaying of Cement Concrete Road by RMC M30 Grade at 11th street debar nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26401,Roads,Completed,ND-TONDIARPET,37,1200000,"Relaying of Cement Concrete Road by RMC M30 Grade at 1st cross Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26402,Roads,Completed,ND-TONDIARPET,37,990000,"Relaying of Cement Concrete Road by RMC M30 Grade at 1st Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26403,Roads,Completed,ND-TONDIARPET,37,1010000,"Relaying of Cement Concrete Road by RMC M30 Grade at 1st Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26404,Roads,Completed,ND-TONDIARPET,37,1030000,"Relaying of Cement Concrete Road by RMC M30 Grade at 1st Street m.g.r. Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26405,Roads,Completed,ND-TONDIARPET,37,420000,"Relaying of Cement Concrete Road by RMC M30 Grade at 1st Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26408,Roads,Completed,ND-TONDIARPET,37,251000,"Relaying of Cement Concrete Road by RMC M30 Grade at 2nd Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26409,Roads,Completed,ND-TONDIARPET,37,887000,"Relaying of Cement Concrete Road by RMC M30 Grade at 2nd Street Dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26410,Roads,Completed,ND-TONDIARPET,37,1378000,"Relaying of Cement Concrete Road by RMC M30 Grade at 2nd Street jagajeevan ram Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26411,Roads,Completed,ND-TONDIARPET,37,737000,"Relaying of Cement Concrete Road by RMC M30 Grade at 2nd Street m.g.r. Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26412,Roads,Completed,ND-TONDIARPET,37,419000,"Relaying of Cement Concrete Road by RMC M30 Grade at 2nd Street udayasuriyan Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26413,Roads,Completed,ND-TONDIARPET,37,250000,"Relaying of Cement Concrete Road by RMC M30 Grade at 3rd Street debar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26414,Roads,Completed,ND-TONDIARPET,37,1152000,"Relaying of Cement Concrete Road by RMC M30 Grade at 3rd Street dhamodar Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26415,Roads,Completed,ND-TONDIARPET,37,1375000,"Relaying of Cement Concrete Road by RMC M30 Grade at 3rd Street jagajeevan ram Nagar, in Division - 37, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26840,Roads,Completed,ND-TONDIARPET,37,802000,"Relaying of Cement Concrete Road by RMC M30 Grade at Dr.Karunanidhi Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26841,Roads,Completed,ND-TONDIARPET,37,1413000,"Relaying of Cement Concrete Road by RMC M30 Grade at Tirupur kumaran street (Nehru Nagar), in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26842,Roads,Completed,ND-TONDIARPET,37,1739000,"Relaying of Cement Concrete Road by RMC M30 Grade at Barathi dasan Street,(Erukkencherry) in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26867,Roads,Completed,ND-TONDIARPET,37,318000,"Relaying of Cement Concrete Road by RMC M30 Grade at Muthamil nagar 199th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/26876,Roads,Completed,ND-TONDIARPET,37,269000,"Relaying of Cement Concrete Road by RMC at Muthamil Nagar 208 th street , in Division-35, Unit - 9, Zone - IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/28254,Roads,Completed,ND-TONDIARPET,37,768000,"Relaying of Road with BC by Paver Finisher in Eswaran Street in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28255,Roads,Completed,ND-TONDIARPET,37,1750000,"Relaying of Road with BC by Paver Finisher in Ganapathy Street in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28257,Roads,Completed,ND-TONDIARPET,37,5598000,"Relaying of Road with BC by Paver Finisher in Gandhi Street in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28258,Roads,Completed,ND-TONDIARPET,37,296000,"Relaying of Road with BC by Paver Finisher in Jawahar 1st lane in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28259,Roads,Completed,ND-TONDIARPET,37,296000,"Relaying of Road with BC by Paver Finisher in jawahar 2nd lane in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28260,Roads,Completed,ND-TONDIARPET,37,1361000,"Relaying of Road with BC by Paver Finisher in Jawahar 1st street in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28261,Roads,Completed,ND-TONDIARPET,37,2529000,"Relaying of Road with BC by Paver Finisher in Sannadhi Street(public well street) in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28263,Roads,Completed,ND-TONDIARPET,37,341000,"Relaying of Road with BC by Paver Finisher in Navoroji Street in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28265,Roads,Completed,ND-TONDIARPET,37,632000,"Relaying of Road with BC by Paver Finisher in Srinivasan 2nd lane in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28266,Roads,Completed,ND-TONDIARPET,37,985000,"Relaying of Road with BC by Paver Finisher in Palani Street in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28267,Roads,Completed,ND-TONDIARPET,37,1010000,"Relaying of Road with BC by Paver Finisher in Pathmavathy Street in DN-37, Unit-09, Zone-04",Own Sources,4,2014-15,2016-17 BR/2014-15/18055,Roads,Completed,BR-Bus Route Roads,38,15080000,"Relaying the road with CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Vaidhyanathan Bridge Road (from the junction of Ennore High Road to the junction of Elaya Street) in Division 38 , Zone - IV",Grants,4,2014-15,2016-17 L/2014-15/28387,Electrical,Completed,L-Electrical,38,1487800,"Provision of 22 Nos. of 8 Mtr G.I Octagonal Lamp post with Single Arch Bracket with 150W to 165W LED Fitting at Ennore High Road ( From Parameswari Nagar to IOC Bus Stand) in Dn:38,Zone IV.",Own Sources,4,2014-15,2016-17 L/2014-15/28944,Electrical,Completed,L-Electrical,38,3504300,"Provision of 97 Nos. of 6 Mtr GI Lamp Post with Single Straight bracket with 40W LED Fitting at Sundaram Pillai Nagar in Dn:38, Zone IV",Own Sources,4,2014-15,2016-17 ND/2014-15/26049,Roads,Completed,ND-TONDIARPET,38,432000,"Relaying of Cement Concrete Road by RMC M30 Grade Concrete at Annai Sandhya Nagar 1st Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26318,Roads,Completed,ND-TONDIARPET,38,480000,"Relaying of Cement Concrete Road by RMC M30 Grade Concrete at Annai Sandhya Nagar 2nd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26320,Roads,Completed,ND-TONDIARPET,38,506000,"Relaying of Cement Concrete Road by RMC M30 Concrete at Annai Sandhya Nagar 3rd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26321,Roads,Completed,ND-TONDIARPET,38,458000,"Relaying of Cement Concrete Road by RMC M30 Grade Concrete at Annai Sandhya Nagar 4th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26322,Roads,Completed,ND-TONDIARPET,38,339000,"Relaying of Cement Concrete Road by RMC M30 Grade Concrete at Annai Sandhya Nagar 5th. 6th, 7th & 8th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26624,Roads,Completed,ND-TONDIARPET,38,279000,"Relaying of Cement Concrete Road by RMC M30 Concrete at Durga Devi Nagar 1st Cross Street in Dn38, Unit-9, Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26656,Roads,Completed,ND-TONDIARPET,38,1141000,"Relaying of Cement Concrete Road by RMC M30 Grade Concrete at Karunanidhi Nagar 2nd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26659,Roads,Completed,ND-TONDIARPET,38,352000,"Relaying of Cement Concrete Road using by RMC M30 concrete at Navalar nagar B street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26660,Roads,Completed,ND-TONDIARPET,38,443000,"Relaying of Cement concrete Road by RMC M30 concrete at Navalar Nagar C street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26661,Roads,Completed,ND-TONDIARPET,38,231000,"Relaying of Cement concrete Road by RMC M30 concrete at Navalar nagar D street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26662,Roads,Completed,ND-TONDIARPET,38,619000,"Relaying of Cement concrete Road by RMC M30 concrete at Navalar nagar E street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26666,Roads,Completed,ND-TONDIARPET,38,337000,"Relaying of Cement concrete by RMC M30 concrete at Nehru nagar 1st street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26667,Roads,Completed,ND-TONDIARPET,38,348000,"Relaying of Cement concrete Road by RMC M30 concrete at Nehru nagar 2nd street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26668,Roads,Completed,ND-TONDIARPET,38,777000,"Relaying of Cement concrete Road by RMC M30 concrete at Nehru nagar 3rd street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26669,Roads,Completed,ND-TONDIARPET,38,414000,"Relaying of Cement concrete Road by RMC M30 concrete at Nehru nagar 4th street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26670,Roads,Completed,ND-TONDIARPET,38,682000,"Relaying of Cement concrete Road by RMC M30 concrete at Nehru nagar 10th street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26673,Roads,Completed,ND-TONDIARPET,38,822000,"Relaying of Cement concrete Road by RMC M30 concrete at Patel Nagar Main Road in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26674,Roads,Completed,ND-TONDIARPET,38,873000,"Relaying of Cement comcrete Road by RMC M30 concrete Patel Nagar 1st Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26675,Roads,Completed,ND-TONDIARPET,38,682000,"Relaying of Cement concrete Road by RMC M30 concrete at Patel Nagar 2nd Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26676,Roads,Completed,ND-TONDIARPET,38,1331000,"Relaying of Cement concrete Road by RMC M30 concrete at Patel Nagar 3rd Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26677,Roads,Completed,ND-TONDIARPET,38,291000,"Relaying of Cement concrete Road by RMC M30 concrete at Patel Nagar 4th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26678,Roads,Completed,ND-TONDIARPET,38,350000,"Relaying of Cement concrete Road by RMC M30 concrete at Sanjay Gandhi Nagar 1st Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26679,Roads,Completed,ND-TONDIARPET,38,331000,"Relaying of Cement concrete Road by RMC M30 conctere at Sanjay Gandhi Nagar 2nd Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26680,Roads,Completed,ND-TONDIARPET,38,391000,"Relaying of Cement concrete Road by RMC M30 concrete at Sanjay Gandhi Nagar 3rd Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26681,Roads,Completed,ND-TONDIARPET,38,364000,"Relaying of Cement concrete Road by RMC M30 concrete at Sanjay Gandhi Nagar 4th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26683,Roads,Completed,ND-TONDIARPET,38,348000,"Relaying of Cement concrete Road by RMC M30 concrete at Sanjay Gandhi Nagar 6th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26684,Roads,Completed,ND-TONDIARPET,38,678000,"Relaying of Cement concrete Road by RMC M30 concrete at Sastri Nagar 1st Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26685,Roads,Completed,ND-TONDIARPET,38,582000,"Relaying of Cement concrete Road by RMC M30 concrete at Sastri Nagar 2nd Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26686,Roads,Completed,ND-TONDIARPET,38,582000,"Relaying of Cement concrete by RMC M30 concrete at Sastri Nagar 3rd Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26687,Roads,Completed,ND-TONDIARPET,38,2227000,"Relaying of Cement concrete Road by RMC M30 concrete at Vinobha Nagar Main Road in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26688,Roads,Completed,ND-TONDIARPET,38,678000,"Relaying of Cement concrete Road by RMC M30 concrete at Vinobha Nagar 7th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26689,Roads,Completed,ND-TONDIARPET,38,655000,"Relaying of Cement concrete Road by RMC M30 concrete at Vinobha Nagar 8th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26690,Roads,Completed,ND-TONDIARPET,38,605000,"Relaying of Cement concrete Road by RMC M30 concrete at Vinobha Nagar 9th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26691,Roads,Completed,ND-TONDIARPET,38,554000,"Relaying of Cement Concrete Road by RMC M30 concrete at Vinobha Nagar 10th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26692,Roads,Completed,ND-TONDIARPET,38,532000,"Relaying of Cement concrete Road by RMC M30 concrete at Vinobha Nagar 11th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26693,Roads,Completed,ND-TONDIARPET,38,483000,"Relaying of Cement concrete Road by RMC M30 concrete at Vinobha Nagar 12th Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26696,Roads,Completed,ND-TONDIARPET,38,371000,"Relaying of Road using Paver Finisher at Vaidyanathan 1st Lane in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26699,Roads,Completed,ND-TONDIARPET,38,508000,"Relaying of Cement Concrete Road by RMC M30 concrete at Chinnaswamy Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26700,Roads,Completed,ND-TONDIARPET,38,483000,"Relaying of Cement concrete Road by RMC M30 concrete at M.G.R Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26701,Roads,Completed,ND-TONDIARPET,38,410000,"Relaying of Cement Concrete Road by RMC M30 concrete at Periyar Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/26702,Roads,Completed,ND-TONDIARPET,38,461000,"Relaying of Cement concrete Road by RMC M30 concrete at Govindaswamy Street in Dn-38, Unit-9, Zone-4 .",Own Sources,4,2014-15,2016-17 ND/2014-15/30785,Buildings,Completed,ND-TONDIARPET,38,670000,"Construction of Disable Friendly Toilet at Singaravelan Nagar in Div - 43, Unit -10, Zone -4",Own Sources,4,2014-15,2016-17 BR/2014-15/30038,Roads,Completed,BR-Bus Route Roads,39,66610000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Thiruvottriyur High Raod (from the junction of Sir Thyagaraya College to the junction of A.E Koil street) in Division 39, 40, 42, 48 Zone - IV.",Grants,4,2014-15,2016-17 BR/2014-15/30039,Roads,Completed,BR-Bus Route Roads,39,52570000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Suryanarayanan Chetty street (from the Kasima Nagar 1st street to the junction of Poondi Thangammal Street) Division 39&43, Zone - IV",Grants,4,2014-15,2016-17 L/2014-15/28386,Electrical,Completed,L-Electrical,39,2114500,"Provision of 21 Nos.of 8 Mtr G.I Octagonal Lamp Post with Double bracket with 150W to 165 LED Fitting at T.H Road ( From Cross Road junction to A.E Koil Street junction in Dn:39, Zone IV",Own Sources,4,2014-15,2016-17 ND/2014-15/22496,Buildings,Completed,ND-TONDIARPET,39,997000,"Improvements to dhobikana at irusappa street in div-39,zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/28937,Roads,Completed,ND-TONDIARPET,39,363000,"Relaying of Road with BC by Market form 4th lane in DN-39, Unit-10, Zone-04(L-75.00m,W-4.50m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28938,Roads,Completed,ND-TONDIARPET,39,192000,"Relaying of Road with BC by Market lane 5th lane in DN-39, Unit-10, Zone-04( L-71.00m,W-5.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28942,Roads,Completed,ND-TONDIARPET,39,194000,"Relaying of Road with BC by Market form 1st lane in DN-39, Unit-10, Zone-04(L-88.00m,W-4.00m)",Own Sources,4,2014-15,2016-17 L/2014-15/28384,Electrical,Completed,L-Electrical,40,2807400,"Provision of 27 Nos. of 8 Mtr Octagonal Lamp Post with double bracket with 150W to 165W LED Fitting at T.H Road (From Cross Road Junction to Tolgate Junction) in Dn:39, Zone IV",Own Sources,4,2014-15,2016-17 L/2014-15/28385,Electrical,Completed,L-Electrical,40,3468200,"Provision of 35 Nos. of 8 Mtr G.I Octagonal Lamp Post with double bracket with 150W to 165 W LED Fitting at T.H Road (From Old Vaidyanathan Street to A.E Koil Street) in Dn;40, Zone IV",Own Sources,4,2014-15,2016-17 L/2014-15/28943,Electrical,Completed,L-Electrical,40,1263800,"Provision of 28 Nos. of 6 Mtr GI Lamp Post with Single Arch Bracket with 90W LED Fitting at Cross Road in Dn:40, Zone IV",Own Sources,4,2014-15,2016-17 ND/2014-15/27401,Roads,Completed,ND-TONDIARPET,40,1257000,"Relaying cc Road at Jeevanagar 2ND Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27402,Roads,Completed,ND-TONDIARPET,40,665000,"Relaying cc Road at Jeevanagar 3RD Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27403,Roads,Completed,ND-TONDIARPET,40,1102000,"Relaying cc Road at Jeevanagar 4TH Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27408,Roads,Completed,ND-TONDIARPET,40,209000,"Relaying cc Road at Kmarajar Nagar (V.O.C Meenavar Quarters) in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27409,Roads,Completed,ND-TONDIARPET,40,506000,"Relaying cc Road at Mangammal Thottam 1st Cross to press colony in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27410,Roads,Completed,ND-TONDIARPET,40,225000,"Relaying cc Road at Mangammal Thottam 1st lane in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27411,Roads,Completed,ND-TONDIARPET,40,287000,"Relaying cc Road at Mangammal Thottam 2ND lane in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27412,Roads,Completed,ND-TONDIARPET,40,167000,"Relaying cc Road at Mangammal Thottam 2nd Cross to press colony in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27413,Roads,Completed,ND-TONDIARPET,40,300000,"Relaying cc Road at Mangammal Thottam 3rd lane in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27414,Roads,Completed,ND-TONDIARPET,40,300000,"Relaying cc Road at Mangammal Thottam 4th lane in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27415,Roads,Completed,ND-TONDIARPET,40,300000,"Relaying cc Road at Mangammal Thottam 5th lane in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27416,Roads,Completed,ND-TONDIARPET,40,300000,"Relaying cc Road at Mangammal Thottam 6th lane in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27428,Roads,Completed,ND-TONDIARPET,40,902000,"Relaying cc Road at Seniamman Koil Street 3rd street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27436,Roads,Completed,ND-TONDIARPET,40,293000,"Relaying cc Road at Thiruvalluvar Ngar I Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27437,Roads,Completed,ND-TONDIARPET,40,293000,"Relaying cc Road at Thiruvalluvar Nagar N Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27439,Roads,Completed,ND-TONDIARPET,40,261000,"Relaying cc Road at Thiruvalluvar Ngar P Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27444,Roads,Completed,ND-TONDIARPET,40,135000,"Relaying cc Road at Tsunami Quarters 2nd Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27449,Roads,Completed,ND-TONDIARPET,40,479000,"Relaying CC Road at Tsunami Quarters 4TH Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27451,Roads,Completed,ND-TONDIARPET,40,1552000,"Relaying CC Road at Tsunami Quarters 5th Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27453,Roads,Completed,ND-TONDIARPET,40,118000,"Relaying cc Road at Tsunami Quarters 6th Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27454,Roads,Completed,ND-TONDIARPET,40,545000,"Relaying CC Road at Tsunami Quarters 7th Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27456,Roads,Completed,ND-TONDIARPET,40,1086000,"Relaying CC Road at Tsunami Quarters 8th Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27457,Roads,Completed,ND-TONDIARPET,40,345000,"Relaying CC Road at Tsunami Quarters 9th Street in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28904,Roads,Completed,ND-TONDIARPET,40,617000,Relaying for BT Road by Paver Finisher at LIG Colony 2nd Street in Dn-40 Unit-10 Zone-4.,Own Sources,4,2014-15,2016-17 ND/2014-15/28917,Roads,Completed,ND-TONDIARPET,40,531000,"Relaying for BT Road by Paver Finisher at L.I.G Colony 3rd Street in DN-40,Unit-10,Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/28918,Roads,Completed,ND-TONDIARPET,40,2130000,"Relaying for BT Road by Paver Finisher at Kamaraj Salai in DN-40,U-10,Z-04",Own Sources,4,2014-15,2016-17 S/2014-15/12453,Footpath,Completed,BR-Bus Route Roads,40,4500000,"Forming Foot path at New Vaidyanathan Street from the jn of Thiruvottiyur High Road to the jn of Seniamman Koil Street in Div - 40, Zone - 4.",Grants,4,2014-15,2016-17 L/2014-15/29288,Electrical,Completed,L-Electrical,41,2485000,"Provision of 70nos of 6mtr GI Hot Dip Zinc Galvanising Lamp Post with 40watss LED Fitting at Sivaji Nagar in Dision 41,Zone IV.",Own Sources,4,2014-15,2016-17 L/2014-15/29299,Electrical,Completed,L-Electrical,41,1854000,"Provision of 53 Nos of 6Mtr GI Hot Dip Galvanising lamp post with 40W LED Fitting at thiruvalluvar Nagar in Division - 41, Zone - 4",Own Sources,4,2014-15,2016-17 ND/2014-15/27199,Roads,Completed,ND-TONDIARPET,41,781000,"Relaying of cc Road by RMC M30 at Kumaran Nagar 3rd Street in DN-41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27202,Roads,Completed,ND-TONDIARPET,41,767000,"Relaying of cc Road by RMC M30 at Kumaran Nagar 4TH Street in DN-41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27321,Roads,Completed,ND-TONDIARPET,41,1272000,"Relaying of cc Road at Amman koil Street in DN-41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27333,Roads,Completed,ND-TONDIARPET,41,831000,"Relaying of cc Road at Azeess Nagar 2nd Street in DN-41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27336,Roads,Completed,ND-TONDIARPET,41,1262000,"Relaying of CC Road at M.G.R Nagar 1st Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27341,Roads,Completed,ND-TONDIARPET,41,1433000,"Relaying of cc Road at M.G.R Nagar 3rd Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27345,Roads,Completed,ND-TONDIARPET,41,1433000,"Relaying of cc Road at M.G.R Nagar 4th Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27349,Roads,Completed,ND-TONDIARPET,41,831000,"Relaying of CC Road at Azeez Nagar 3rd Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27354,Roads,Completed,ND-TONDIARPET,41,1261000,"Relaying of cc Road at M.G.R Nagar 6th Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27358,Roads,Completed,ND-TONDIARPET,41,1638000,"Relaying of cc Road at M.G.R Nagar 7th Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27364,Roads,Completed,ND-TONDIARPET,41,1536000,"Relaying of cc Road at M.G.R Nagar 8th Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27141,Roads,Completed,ND-TONDIARPET,42,289000,"Relaying cc Road at Seniamman Nagar 1st lane in DN-42,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27145,Roads,Completed,ND-TONDIARPET,42,341000,"Relaying cc Road at Seniamman Nagar 2ndt lane in DN-42,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27147,Roads,Completed,ND-TONDIARPET,42,481000,"Relaying cc Road at Seniamman Nagar 3rd lane in DN-42,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27151,Roads,Completed,ND-TONDIARPET,42,205000,"Relaying cc Road at Seniamman Nagar 4TH lane in DN-42,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27155,Roads,Completed,ND-TONDIARPET,42,232000,"Relaying cc Road at Seniamman Nagar 6TH lane in DN-42,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27159,Roads,Completed,ND-TONDIARPET,42,203000,"Relaying cc Road at Seniamman Nagar 7TH lane in DN-42,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27165,Roads,Completed,ND-TONDIARPET,42,1275000,"Relaying cc Road at Seniamman Nagar Main Street in DN-42,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/27195,Roads,Completed,ND-TONDIARPET,42,873000,"Relaying of cc Road by RMC M30 at Kumaran Nagar 2nd Street in DN-41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28924,Roads,Completed,ND-TONDIARPET,42,3992000,"Relaying of Road with BC by Senniamman Koil Street in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28926,Roads,Completed,ND-TONDIARPET,42,225286,"Relaying of Road with BC by Perumal koil garden 3rd street in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28927,Roads,Completed,ND-TONDIARPET,42,118000,"Relaying of Road with BC by Perumal Koil 2nd Street in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28928,Roads,Completed,ND-TONDIARPET,42,238000,"Relaying of Road with BC by Perumal koil 1st street in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28929,Roads,Completed,ND-TONDIARPET,42,406219,"Relaying of Road with BC by M.C.M Garden 3rd Street in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28930,Roads,Completed,ND-TONDIARPET,42,253000,"Relaying of Road with BC by M.C.M Garden 2nd street in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28931,Roads,Completed,ND-TONDIARPET,42,377000,"Relaying of Road with BC by M.C.M Garden 1st street in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28932,Roads,Completed,ND-TONDIARPET,42,417000,"Relaying of Road with BC by T.H Road Service Road in DN-42, Unit-10, Zone-04",Own Sources,4,2014-15,2016-17 ND/2014-15/8709,Buildings,Completed,ND-TONDIARPET,42,920000,"Providing of Rental modular Toilet on contract basis and maintenance for one year at Thiruvotriyur High Road, Tondiarpet in Dn-42,Unit-10,Zone-4",Own Sources,4,2014-15,2017-18 BR/2014-15/18060,Roads,Completed,BR-Bus Route Roads,43,11787000,"Relaying the road with CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Kummalamman Koil Street ( from the junction of PAN Rajarathinam Salai to the Junction of Thiruvottriyur high road )in Division 43, Zone - IV",Grants,4,2014-15,2016-17 L/2014-15/28934,Electrical,Completed,L-Electrical,43,1503400,"Provision of 41 Nos.of 6 Mtr GI Octagonal Lamp Post with Single bracket with single bracket with 40W LED Fitting at Pudumanai Kuppam in Dn:43, Zone IV",Own Sources,4,2014-15,2016-17 ND/2014-15/19935,Roads,Completed,ND-TONDIARPET,43,890000,"Laying BT Road at Pudumanaikuppam main street in DN-43,U-10,Z-04 (L-115 B-6.3)",Own Sources,4,2014-15,2016-17 ND/2014-15/27085,Roads,Completed,ND-TONDIARPET,43,371000,"Laying of Cement Concrete road by RMC M30 at Varadharajaperumal koil lane in Ward-43,Unit-10,Zone-4",Own Sources,4,2014-15,2017-18 ND/2014-15/27098,Roads,Completed,ND-TONDIARPET,43,264000,"Laying of cement concrete Road by RMC M30at Suriyanarayanan 1st lane in DN-43,U-10,Z-04(l-110,w-2m)",Own Sources,4,2014-15,2017-18 ND/2014-15/27105,Roads,Completed,ND-TONDIARPET,43,408000,"Laying of cement concrete Road by RMC M30at Suriyanarayanan 2nd lane in DN-43,U-10,Z-04(l-175,w-2m)",Own Sources,4,2014-15,2017-18 ND/2014-15/27117,Roads,Completed,ND-TONDIARPET,43,271000,"Laying of cement concrete Road by RMC M30at Suriyanarayanan 5th lane in DN-43,U-10,Z-04(l-110,w-2m)",Own Sources,4,2014-15,2017-18 ND/2014-15/27121,Roads,Completed,ND-TONDIARPET,43,358000,"Laying of cement concrete Road by RMC M30at Suriyanarayanan 6th lane in DN-43,U-10,Z-04(l-130,w-2.3m)",Own Sources,4,2014-15,2017-18 ND/2014-15/27126,Roads,Completed,ND-TONDIARPET,43,511000,"Laying cement concrete Road by RMC M30at Suriyanarayanan 7th lane in DN-43,U-10,Z-04(l-210,w-2m)",Own Sources,4,2014-15,2017-18 ND/2014-15/27339,Roads,Completed,ND-TONDIARPET,43,1433000,"Relaying of cc Road at M.G.R Nagar 2nd Street in DN41,U-10,Z-04",Own Sources,4,2014-15,2016-17 ND/2014-15/28204,Roads,Completed,ND-TONDIARPET,43,445000,"Relaying of Bituminous concrete road at Tondiar nagar Main street (L-220.00m,W-4.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28208,Roads,Completed,ND-TONDIARPET,43,308000,"Relaying of Bituminous concrete road at Tondiar nagar 1st street (120.00m,W-5.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28213,Roads,Completed,ND-TONDIARPET,43,328000,"Relaying of Bituminous concrete road at Tondiar nagar 2nd street (L-129.00m,W-5.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28214,Roads,Completed,ND-TONDIARPET,43,328000,"Relaying of Bituminous concrete road at Tondiar nagar 3rd street (L-129.00m,W-5.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28215,Roads,Completed,ND-TONDIARPET,43,110000,"Relaying of Bituminous concrete road at Tondiar nagar 4th street (L-41m,W-5.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28218,Roads,Completed,ND-TONDIARPET,43,90000,"Relaying of Bituminous concrete road at Tondiar nagar 5th street (L-35m,W-5.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28219,Roads,Completed,ND-TONDIARPET,43,121000,"Relaying of Bituminous concrete road at Tondiar nagar 6th street ( L-45,W-5.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/28221,Roads,Completed,ND-TONDIARPET,43,379000,"Relaying of Bituminous concrete road at Tondiar nagar 7th street ( L-153m, W-5.00m )",Own Sources,4,2014-15,2016-17 ND/2014-15/28222,Roads,Completed,ND-TONDIARPET,43,1646000,"Relaying of Bituminous concrete road at Thandavarayan street( L-435m,W-6.00m)",Own Sources,4,2014-15,2016-17 ND/2014-15/31997,Storm Water Drain,Completed,ND-TONDIARPET,43,995000,"De silting,Repairs and Maintenance to SWD at Jeevarathinam salai (From Tondiar nagar main street to Vinayagapuram main street) in Ward-43,Unit-10,Zone-4",Own Sources,4,2014-15,2017-18 ND/2014-15/5544,Footpath,Completed,ND-TONDIARPET,43,623000,"Improvements and Face Lift Work to Chockalingam Colony Main street in Ward-43,Unit-10,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/5769,Footpath,Completed,ND-TONDIARPET,43,315000,"Improvements and Face Lift Work to Murugesan colony in Ward-43,Unit-10,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26152,Roads,Completed,ND-TONDIARPET,44,62000,"Relaying CC Road at Alagirisamy 1st Lane in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26153,Roads,Completed,ND-TONDIARPET,44,1028000,"Relaying BT Road at Veera Pandian Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26154,Roads,Completed,ND-TONDIARPET,44,553000,"Relaying BT Road at Nagammaiyar Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26155,Roads,Completed,ND-TONDIARPET,44,293000,"Name of the work : Relaying BT Road at Munivel Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26156,Roads,Completed,ND-TONDIARPET,44,519000,"Relaying BT Road at Kakkanji Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26157,Roads,Completed,ND-TONDIARPET,44,731000,"Relaying BT Road at KVK Sami Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26159,Roads,Completed,ND-TONDIARPET,44,293000,"Relaying BT Road at Gangadharan Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26160,Roads,Completed,ND-TONDIARPET,44,1028000,"Relaying BT Road at Thiruppur Kumaran Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26161,Roads,Completed,ND-TONDIARPET,44,1081000,"Relaying BT Road at Rajaji Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26163,Roads,Completed,ND-TONDIARPET,44,375000,"Relaying BT Road at Kamaraj Nagar 8th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26165,Roads,Completed,ND-TONDIARPET,44,297000,"Relaying BT Road at Kamaraj Nagar 7th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26166,Roads,Completed,ND-TONDIARPET,44,209000,"Relaying BT Road at Kamaraj Nagar 6th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26168,Roads,Completed,ND-TONDIARPET,44,254000,"Relaying BT Road at Kamaraj Nagar 5th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26169,Roads,Completed,ND-TONDIARPET,44,240000,"Relaying BT Road at Kamaraj Nagar 4th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26171,Roads,Completed,ND-TONDIARPET,44,480000,"Relaying BT Road at Kamaraj Nagar 3rd Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26172,Roads,Completed,ND-TONDIARPET,44,512000,"Relaying BT Road at Kamaraj Nagar 2nd Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26174,Roads,Completed,ND-TONDIARPET,44,1028000,"Relaying BT Road at Jawahar Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26176,Roads,Completed,ND-TONDIARPET,44,718000,"Relaying BT Road at Asiriyar Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26178,Roads,Completed,ND-TONDIARPET,44,294000,"Relaying BT Road at Kamalammal Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26188,Roads,Completed,ND-TONDIARPET,44,500000,"Relaying CC Road at Subramaniyam Street (Kakkanji Colony) in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26191,Roads,Completed,ND-TONDIARPET,44,1400000,"Relaying CC Road at Kamarajar Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26193,Roads,Completed,ND-TONDIARPET,44,660000,"Relaying CC Road at Gandhiji Main Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26194,Roads,Completed,ND-TONDIARPET,44,110000,"Relaying CC Road at Gandhiji 6th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26197,Roads,Completed,ND-TONDIARPET,44,350000,"Relaying CC Road at Gandhiji 5th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26198,Roads,Completed,ND-TONDIARPET,44,350000,"Relaying CC Road at Gandhiji 4th Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26200,Roads,Completed,ND-TONDIARPET,44,340000,"Relaying CC Road at Gandhiji 3rd Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26202,Roads,Completed,ND-TONDIARPET,44,340000,"Relaying CC Road at Gandhiji 2nd Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26203,Roads,Completed,ND-TONDIARPET,44,1142000,"Relaying CC Road at Gandhiji 1st Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26802,Roads,Completed,ND-TONDIARPET,44,62000,"Relaying CC Road at Alagirisamy 2nd Lane in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26803,Roads,Completed,ND-TONDIARPET,44,62000,"Relaying CC Road at Alagirisamy 4th Lane in Dn-44, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 BR/2014-15/29888,Roads,Completed,BR-Bus Route Roads,45,21007000,"Strengthening and Relaying the road with DBM 60mm and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Moorthingar Road ( from the junction of Melpatti ponnappan street to the junction of Erukkencheri High Road) in Ward 45 &46,Zone -IV",Grants,4,2014-15,2016-17 BR/2014-15/29980,Roads,Completed,BR-Bus Route Roads,45,13610000,Strengthening and Relaying the road with DBM and CBC after Cold Milling by paver finisher using shredded plastic waste along with Traffic improvement works at B.B Road from the junction of Melpatti ponnappan street to the Junction of AA road) Division 45 Zone -IV,Grants,4,2014-15,2016-17 ND/2014-15/24256,Roads,Completed,ND-TONDIARPET,45,990000,"RELAYING THE BT ROAD AT KRISHNA KOIL STREET IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/24257,Roads,Completed,ND-TONDIARPET,45,458000,"RELAYING THE BT ROAD AT CHINNATHAMBI STREET IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/24258,Roads,Completed,ND-TONDIARPET,45,898000,"RELAYING THE BT ROAD AT BALAKRISHNAN STREET IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/24259,Roads,Completed,ND-TONDIARPET,45,1100000,"RELAYING THE BT ROAD AT BHAKTHAVATCHALAM COLONY 2ND STREET DIVIVISION-45, UNIT-11, ZONE-4,",Own Sources,4,2014-15,2016-17 ND/2014-15/24260,Roads,Completed,ND-TONDIARPET,45,1104000,"RELAYING THE BT ROAD AT BHAKTHAVATCHALAM COLONY 3RD STREET DIVIVISION-45, UNIT-11, ZONE-4,",Own Sources,4,2014-15,2016-17 ND/2014-15/26747,Roads,Completed,ND-TONDIARPET,45,1949946,"Relaying CC Road at Grammiyar Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26750,Roads,Completed,ND-TONDIARPET,45,1985456,"Relaying CC Road at Mayor Krishnamurthy main road in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26760,Roads,Completed,ND-TONDIARPET,45,280000,"Relaying CC Road at Mayor krishna Murthy 1st Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26761,Roads,Completed,ND-TONDIARPET,45,300000,"Relaying CC Road at Mayor Krishna Murthy 2nd Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26762,Roads,Completed,ND-TONDIARPET,45,490061,"Relaying CC Road at Mayor krishna Murthy 3rd Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26764,Roads,Completed,ND-TONDIARPET,45,378584,"Relaying CC Road at Mayor krishna Murthy 4th Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26765,Roads,Completed,ND-TONDIARPET,45,339722,"Relaying CC Road at Mayor krishna Murthy 5th Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26766,Roads,Completed,ND-TONDIARPET,45,308048,"Relaying CC Road at Sundaram 1st Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26770,Roads,Completed,ND-TONDIARPET,45,689103,"Relaying CC Road at Sundaram 2nd Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26771,Roads,Completed,ND-TONDIARPET,45,2062040,"Relaying CC Road at Sundaram 3rd Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26773,Roads,Completed,ND-TONDIARPET,45,1240500,"Relaying CC Road at Sundaram 6th Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26778,Roads,Completed,ND-TONDIARPET,45,1690000,"Relaying CC Road at kakknaji colony 1st Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26782,Roads,Completed,ND-TONDIARPET,45,934731,"Relaying CC Road at kakknaji colony 3rd Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26785,Roads,Completed,ND-TONDIARPET,45,800000,"Relaying CC Road at kakknaji colony 2nd Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26787,Roads,Completed,ND-TONDIARPET,45,931000,"Relaying CC Road at kakknaji colony 4th Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26789,Roads,Completed,ND-TONDIARPET,45,1200000,"Relaying CC Road at kakknaji colony 5th Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 ND/2014-15/26790,Roads,Completed,ND-TONDIARPET,45,500000,"Relaying CC Road at kakknaji colony puthu Street in Dn-45, Unit-11, Zone-04.",Own Sources,4,2014-15,2016-17 S/2014-15/12459,Footpath,Completed,BR-Bus Route Roads,45,14300000,"Forming Foot path at Dr.Ambedkar College Road from the jn of Moorthingar Street to the jn of Sundaram Street in Div - 45, Zone - 4.",Grants,4,2014-15,2016-17 BR/2014-15/29995,Roads,Completed,BR-Bus Route Roads,46,4814000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Muthu Mudali Street (from the junction of Moorthingar street to the Junction of Erukkancherri High Road ) , Division 46, Zone - IV",Grants,4,2014-15,2016-17 ND/2014-15/17174,Roads,Completed,ND-TONDIARPET,46,2311000,"Dismantling and Relaying of Cement Concrete Road at New Magazenpuram in DN-46, Unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/21569,Parks,Completed,ND-TONDIARPET,46,731000,Annual Maintenance of Sathyamoorthy Nagar Park in Div-46 Unit-11 Zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/26181,Roads,Completed,ND-TONDIARPET,46,1595000,"Relaying the cc road at 24th block in Dn-46,Unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26195,Roads,Completed,ND-TONDIARPET,46,1717000,"Relaying the cc road at Arumugam street in Dn-46,Unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26205,Roads,Completed,ND-TONDIARPET,46,2525000,"relaying the cc road at Old megazinepuram in Dn-46,Unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26207,Roads,Completed,ND-TONDIARPET,46,665000,"Relaying the cc road at Samanthipoo colony 1st street in dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26215,Roads,Completed,ND-TONDIARPET,46,1023000,"Relaying the cc road at Samanthipoo colony 2nd street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26225,Roads,Completed,ND-TONDIARPET,46,711000,"Relaying the cc road at Samanthipoo colony 3rd street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26229,Roads,Completed,ND-TONDIARPET,46,1119000,"Relaying the cc road at Samanthipoo colony 4th street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26231,Roads,Completed,ND-TONDIARPET,46,2141000,"Relaying the cc road at Nehru nagar main road in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26234,Roads,Completed,ND-TONDIARPET,46,1975000,"Relaying the cc road at Nehru nagar 1st street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26237,Roads,Completed,ND-TONDIARPET,46,1422000,"Relaying the cc road at Nehru nagar 2nd st in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26239,Roads,Completed,ND-TONDIARPET,46,2411000,"Relaying the cc road at Nehu nagar 3rd street in Dn-46,Unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26247,Roads,Completed,ND-TONDIARPET,46,1444000,"Relaying the cc road at Nehru nagar 4th street Dn-46,unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26251,Roads,Completed,ND-TONDIARPET,46,1168000,"Relaying the cc road at Nehru nagar 5th st in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26258,Roads,Completed,ND-TONDIARPET,46,1191000,"Relaying the cc road at Nehru nagar 6th street in Dn-46,Unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26259,Roads,Completed,ND-TONDIARPET,46,702000,"Relaying the cc road at Mallipoo colony 1st street in DN-46,Unit-11,Zone-4",Own Sources,4,2014-15,2016-17 ND/2014-15/26262,Roads,Completed,ND-TONDIARPET,46,702000,"Relaying the cc road at Mallipoo colony 2nd street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26265,Roads,Completed,ND-TONDIARPET,46,702000,"Relaying the cc road at Mallipoo colony 3rd street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26268,Roads,Completed,ND-TONDIARPET,46,702000,"Relaying the cc road at Mallipoo colony 4th street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26269,Roads,Completed,ND-TONDIARPET,46,913000,"Relaying the cc road at Mallipoo colony 5th street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26270,Roads,Completed,ND-TONDIARPET,46,1781000,"Relaying the cc road at Mallipoo colony main street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26294,Roads,Completed,ND-TONDIARPET,46,2986000,"Relaying the cc road at Mousque street in Dn-46,Unit-11,Zone-4.",Own Sources,4,2014-15,2016-17 BR/2014-15/30003,Roads,Completed,BR-Bus Route Roads,47,15181000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Tratfic improvement works at Kathivakkam High Road (from the junction of manali salai to the juction of Korukkupet level crossing) Division47, Zone - IV",Grants,4,2014-15,2016-17 L/2014-15/0723,Electrical,Completed,E-Education,47,83700,"ELECTRIFICATION WORK AT CHENNAI HIGHER SECONDARY SCHOOL AT HARINARAYANAPURAM IN DN:47, ZONE IV.",Own Sources,4,2014-15,2016-17 L/2014-15/29312,Electrical,Completed,L-Electrical,47,1019000,"Provision of 23 Nos of 6 Mtrs Street Lamp post with Hot Dip Zinc Galvanising with Single Arch Bracket with 90W LED Fitting at undiveeran Street, Pitty Munusamy Street in Division - 47, Zone - 4.",Own Sources,4,2014-15,2016-17 L/2014-15/29319,Electrical,Completed,L-Electrical,47,2167000,"Provision of 47 Nos of 6Mtr Sreet Lamp Post qith Hot Dip Zinc Galvanising with Single Arch Bracket with 90W LED Fitting at Theyagappa Street, Ekkabairam Street, in Dn:47, Zone - 4",Own Sources,4,2014-15,2016-17 L/2014-15/29321,Electrical,Completed,L-Electrical,47,1479000,"Provision of 32Nos of 6Mtr Street Lamp Post with Hot dip Zinc Galvanising with Single Arch Bracket with 90W LED Fitting at Jawanmal Sowcar Street, Egappan Street, and Muniyappan street in Dn 74, Zone 4",Own Sources,4,2014-15,2016-17 L/2014-15/7577,Electrical,Completed,J-Bridges,47,976300,"Provision of 22nos of 7mtr GI Lamp post with Single Arch Bracket with 90watts LED Fitting at CB Road Bridge (Eastern side) in Division 47,Zone IV.",Own Sources,4,2014-15,2016-17 L/2014-15/7599,Electrical,Completed,J-Bridges,47,974600,"Provision of 22nos of 7mtr GI Lamp post with Single Arch Bracket with 90watts LED Fitting at CB Road Bridge (Western side) in Division 47,Zone IV.",Own Sources,4,2014-15,2016-17 ND/2014-15/15549,Buildings,Completed,ND-TONDIARPET,47,2246000,"Construction of New Amma Unavagam (Phase -2) at Sigirinthapalayam 5th Street Korukkupet in DN-47,Unit -11, Zone -04.",Own Sources,4,2014-15,2016-17 ND/2014-15/17361,Roads,Completed,ND-TONDIARPET,47,420000,"Improvements of SWD at Kamarajar Nagar 12th Street to 'B' Canel in DN -47, Unit -11, Zone -04.",Own Sources,4,2014-15,2016-17 ND/2014-15/27089,Roads,Completed,ND-TONDIARPET,47,838000,Relaying cement concrete road by RMC at Bharathi Nagar 2nd Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27090,Roads,Completed,ND-TONDIARPET,47,861000,Relaying cement concrete road by RMC at Bharathi Nagar 3rd Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27091,Roads,Completed,ND-TONDIARPET,47,860000,Relaying cement concrete road by RMC at Bharathi Nagar 4th Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27092,Roads,Completed,ND-TONDIARPET,47,860000,Relaying cement concrete road by RMC at Bharathi Nagar 5th Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27093,Roads,Completed,ND-TONDIARPET,47,850000,Relaying cement concrete road by RMC at Bharathi Nagar 6th Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27095,Roads,Completed,ND-TONDIARPET,47,768000,Relaying cement concrete road by RMC at Bharathi Nagar 8th Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27097,Roads,Completed,ND-TONDIARPET,47,503000,Relaying cement concrete road by RMC at Bharathi Nagar 9th Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27100,Roads,Completed,ND-TONDIARPET,47,386000,Relaying cement concrete road by RMC at Bharathi Nagar Cross Street (East) in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27104,Roads,Completed,ND-TONDIARPET,47,361000,Relaying cement concrete road by RMC at Sastri Nagar main Road in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27192,Roads,Completed,ND-TONDIARPET,47,846000,Relaying cement concrete road by RMC at Motchapuram 1st street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27194,Roads,Completed,ND-TONDIARPET,47,863000,Relaying cement concrete road by RMC at Motchapuram 2nd street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27224,Roads,Completed,ND-TONDIARPET,47,838000,Relaying cement concrete road by RMC at Ambedhkar Nagar 3rd Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27231,Roads,Completed,ND-TONDIARPET,47,838000,Relaying cement concrete road by RMC at Ambedhkar Nagar 1st Cross Street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27527,Roads,Completed,ND-TONDIARPET,47,872000,Relaying cement concrete road by RMC at Kamaraja Nagar 9th street in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 ND/2014-15/27530,Roads,Completed,ND-TONDIARPET,47,634000,Relaying cement concrete road by RMC at Meenabamal Nagar Cross st in Division-47 unit-11 zone-4,Own Sources,4,2014-15,2016-17 L/2014-15/29331,Electrical,Completed,L-Electrical,48,675000,"Provision of 15Nos of 6Mtr Street Lamp Post with Hot Dip Zinc Galvanising with Single Arch Bracket 90W LED Fitting at Ramujyam Iyer Street, Dn 48, zone 4",Own Sources,4,2014-15,2016-17 L/2014-15/29333,Electrical,Completed,L-Electrical,48,925000,"Provision of 21 Nos of 6 Mtr Street Lamp Post with Hot dip Zinc Galvanising on Single Arch Bracket with 9+0W LED Fitting Muthaiah Mudali Street, Dn-48, Zone 4",Own Sources,4,2014-15,2016-17 L/2014-15/29337,Electrical,Completed,L-Electrical,48,874000,"Provision of 19 Nos of 6 Mtr Street Lamp Post with Hot dip Zinc Galvanising on single Arch Bracket with 90W LED Fitting at Parthasarathy Main Street in Dn - 48, Zone -4",Own Sources,4,2014-15,2016-17 ND/2014-15/26432,Roads,Completed,ND-TONDIARPET,48,250000,"Relaying for BT Road by Paver finisher at Natarajan Street in Dn.48, Unit.11, Zone.4.",Own Sources,4,2014-15,2016-17 ND/2014-15/26435,Roads,Completed,ND-TONDIARPET,48,847000,"Relaying for BT Road by Paver finisher at D.B.K. Street in Dn.48, Unit.11, Zone.4",Own Sources,4,2014-15,2016-17 ND/2014-15/26442,Roads,Completed,ND-TONDIARPET,48,1113000,"Relaying for BT Road by Paver finisher at Nallappavathiyar Street in Dn.48, Unit.11, Zone.4",Own Sources,4,2014-15,2016-17 ND/2014-15/26444,Roads,Completed,ND-TONDIARPET,48,1369000,"Relaying for BT Road by Paver finisher at Solaiyappan Street in Dn.48, Unit.11, Zone.4",Own Sources,4,2014-15,2016-17 ND/2014-15/26466,Roads,Completed,ND-TONDIARPET,48,567000,"Relaying for BT Road by Paver finisher at Jamal Sowcar Street in Dn.48, Unit.11, Zone.4",Own Sources,4,2014-15,2016-17 ND/2014-15/26472,Roads,Completed,ND-TONDIARPET,48,214000,"Relaying for BT Road by Paver finisher at Jamal Sowcar Lane in Dn.48, Unit.11, Zone.4",Own Sources,4,2014-15,2016-17 ND/2014-15/5050,Buildings,Completed,ND-TONDIARPET,48,990000,"ANNUAL REPAIRS AND MAINTENANCE FOR DAY TO DAY IN TPF @ BASIN BRIDGE ROAD IN DN-48, U-11, Z-4.",Own Sources,4,2014-15,2016-17 BR/2014-15/18068,Roads,Completed,BR-Bus Route Roads,49,5980000,"Relaying the Road With CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at West Kalmandapam Road(from the Junction of M.S Koil street to the Junction of PAN Rajarathnam Salai) in Division 49 ,Zone-V",Grants,5,2014-15,2016-17 NE/2014-15/18328,Buildings,Completed,NE-ROYAPURAM,49,530000,"Improvement to CHS Appasamy school in ward-49, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/18330,Buildings,Completed,NE-ROYAPURAM,49,372000,"Improvements to NNMP Shed and Tax Collection Center at Division Office in Ward-49, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/27735,Buildings,Completed,NE-ROYAPURAM,49,900000,"Improvement and Repairs to Tax Collector Centre in Division office at DR.V.Road in Ward-53, unit-12, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29283,Roads,Completed,NE-ROYAPURAM,49,291000,"Relaying of road with BCCMP 40mm thick by paver finisher at Thanikachalam Street in Ward-49, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29285,Roads,Completed,NE-ROYAPURAM,49,1221000,"Relaying of road with BCCMP 40mm thick by paver finisher at Adam Street in Ward-49, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29287,Roads,Completed,NE-ROYAPURAM,49,142000,"Relaying of road with BCCMP 40mm thick by paver finisher at Alavandar Street in Ward-49, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29289,Roads,Completed,NE-ROYAPURAM,49,308000,"Relaying of road with BCCMP 40mm thick by paver finisher at Kumarasamy Lane in Ward-49, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29290,Roads,Completed,NE-ROYAPURAM,49,393000,"Relaying of road with BCCMP 40mm thick by paver finisher at Somu 4th Lane in Ward-49, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29291,Roads,Completed,NE-ROYAPURAM,49,144000,"Relaying of road with BCCMP 40mm thick by paver finisher at Venkatapathy Street in Ward-49, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29292,Roads,Completed,NE-ROYAPURAM,49,144000,"Relaying of road with BCCMP 40mm thick by paver finisher at Venkatramanujam Street in Ward-49, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 BR/2014-15/30005,Roads,Completed,BR-Bus Route Roads,50,20335000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at West Mada Koil Street(from the Junction of NRT road to the Junction of East Kalmandapam Road) in Division 50,Zone-V",Grants,5,2014-15,2017-18 BR/2014-15/30022,Roads,Completed,BR-Bus Route Roads,50,20759000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Surya Narayanan (Chetty) Street ( from the Junction of Mannarsamy koil Street to the Junction of Kasima Nagar Ist Street in Division 50 ,Zone-V",Grants,5,2014-15,2016-17 BR/2014-15/30024,Roads,Completed,BR-Bus Route Roads,50,12790000,"Strengthening and Relaying the Road With DBM and CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at East Kalmandapam Road (from the Junction of M.S Koil Street to the Junction of West Mada Church Street) in Division 50,Zone -V",Grants,5,2014-15,2016-17 BR/2014-15/30026,Roads,Completed,BR-Bus Route Roads,50,34918000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Mannarsamy Koil Street (From Junction Of Ibrahimji Street the Junction of Sooryanarayanan Chetty Street) in Division 50&52 , Zone - V",Grants,5,2014-15,2016-17 NE/2014-15/13721,Roads,Completed,NE-ROYAPURAM,50,500000,"Providing breathing space around trees and painting at various streets in Ward-50, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/13725,Footpath,Completed,NE-ROYAPURAM,50,53000,"Improvements and repairs to compound wall around the Electrical transformer at Lotus Ramasamy Street in Ward-50, Unit-12, Zone-V",Own Sources,5,2014-15,2016-17 NE/2014-15/16611,Roads,Completed,NE-ROYAPURAM,50,860000,"Proposed Construction of Modern Stainless steel Bus shelters at Suryanarayana street (Near kumarn hospital) in ward-50, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/16612,Roads,Completed,NE-ROYAPURAM,50,860000,"Proposed Construction of Modern Stainless steel Bus shelters at Suryanarayana street (Near N1 police station) in ward-50, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28504,Roads,Completed,NE-ROYAPURAM,50,4039000,"Laying of C.C. Road with M30 Grade of Cement concrete at G.M. Pettah (TNSCB) in Ward-50, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28886,Roads,Completed,NE-ROYAPURAM,50,1829000,"Relaying of road with BCCMP 40mm thick by paver finisher at Arthoon road in Ward-50, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28899,Roads,Completed,NE-ROYAPURAM,50,881000,"Relaying of road with BCCMP 40mm thick by paver finisher at Bazaar street in Ward-50, Unit-12, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/30066,Roads,Completed,NE-ROYAPURAM,50,578000,"Laying of C.C. Road with M30 Grade of Cement concrete at Durai Street (Pallam) in Ward-50, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/4487,Buildings,Completed,B-Buildings,50,3060000,"Construction of Additional building for UPHC at S.N (c) street (Grace garden) in ward-50, unit-12, zone-5",Own Sources,5,2014-15,2017-18 NE/2014-15/12499,Buildings,Completed,NE-ROYAPURAM,51,990000,"Construction of compound wall around amma unvagam at manikandan 6th street in ward-51, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/20717,Buildings,Completed,NE-ROYAPURAM,51,429000,"Improvement work to toilet block in chennai primary school at cemetry road in Dn-51,Unit-12,Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/20927,Buildings,Completed,NE-ROYAPURAM,51,998267,"Deslting and Repairs to Storm water Drain at Thulackalam street,West Cemetry road, Cemetry Road and Other Streets in Ward-51, Unit-12, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28512,Roads,Completed,NE-ROYAPURAM,51,663000,"Laying of C.C. Road with M30 Grade Cement Concrete at Company Chathiram Street in Ward-51, Unit-12, Zone-V",Own Sources,5,2014-15,2016-17 NE/2014-15/16613,Roads,Completed,NE-ROYAPURAM,52,860000,"Proposed Construction of Modern Stainless steel Bus shelters at Cemetry road (Near RSRM hospital) in ward-52, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/16614,Roads,Completed,NE-ROYAPURAM,52,860000,"Proposed Construction of Modern Stainless steel Bus shelters at N.R.T road in ward-52, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/18550,Bridges,Completed,NE-ROYAPURAM,52,990000,"Construction of Pedestal steps and strengthening revetment at Royapuram old bridge in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/21152,Buildings,Completed,NE-ROYAPURAM,52,558000,"IMPROVEMENTS AND REPAIRS TO P.C AT OLD SLAUGHTER HOUSE ROAD 5TH LANE IN DN - 52 , UNIT-12, ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/21154,Buildings,Completed,NE-ROYAPURAM,52,411592,"IMPROVEMENTS AND REPAIRS TO P.C AT OLD SLAUGHTER HOUSE ROAD IN DN-52 ,UNIT-12 , ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/28517,Roads,Completed,NE-ROYAPURAM,52,461000,"Laying of C.C. Road with M30 Grade Cement Concrete road at Chidambaranathan Street in ward-52, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28519,Roads,Completed,NE-ROYAPURAM,52,923000,"Laying of C.C. Road with M30 Grade Cement Concrete road at Karimedu Colony in ward-52, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29330,Roads,Completed,NE-ROYAPURAM,52,2200000,"Relaying of road with BCCMP 40mm thick by paver finisher at M.C. Road in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/29332,Roads,Completed,NE-ROYAPURAM,52,190000,"Relaying of road with BCCMP 40mm thick by paver finisher at Ranga Garden street in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/29334,Roads,Completed,NE-ROYAPURAM,52,237000,"Relaying of road with BCCMP 40mm thick by paver finisher at Appier lane in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/29336,Roads,Completed,NE-ROYAPURAM,52,190000,"Relaying of road with BCCMP 40mm thick by paver finisher at Barber lane in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/29338,Roads,Completed,NE-ROYAPURAM,52,380000,"Relaying of road with BCCMP 40mm thick by paver finisher at M.S.Koil Lane in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/29340,Roads,Completed,NE-ROYAPURAM,52,108000,"Relaying of road with DBM 50MM and BCCMP 30mm thick by paver finisher at B.C. Press road 2nd lane in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/29343,Roads,Completed,NE-ROYAPURAM,52,208000,"Relaying of road with BCCMP 40mm thick by paver finisher at Periannan street in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/29344,Roads,Completed,NE-ROYAPURAM,52,570000,"Relaying of road with BCCMP 40mm thick by paver finisher at Vaigundam street in Ward-52, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 BR/2014-15/30000,Roads,Completed,BR-Bus Route Roads,53,4118000,"Strengthening and Relaying the Road With DBM and CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at Peddu (N) Street (From the junction of Padavattamman Koil street to the Junction of Walltax road) ) in Ward -53 ,Zone -V",Grants,5,2014-15,2017-18 BR/2014-15/30030,Roads,Completed,BR-Bus Route Roads,53,15398000,"Strengthening and Relaying the road with DBM and CBC after Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Parthasarathy Over Bridge Road( From the Junction of North Wall road to the Junction of Dr.Vijayaraghavalu road ) Division 53 , Zone - V",Grants,5,2014-15,2016-17 NE/2014-15/12880,Buildings,Completed,NE-ROYAPURAM,53,812000,"Improvement to Urdu school at Jayaram street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2017-18 NE/2014-15/12885,Buildings,Completed,NE-ROYAPURAM,53,313000,"Improvement to Urdu school and NNMP shed at Kathapada road 3rd sheet in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2017-18 NE/2014-15/21292,Buildings,Completed,NE-ROYAPURAM,53,998000,"Construction of Segrigation shed at Burial ground at Kathpada road in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/23689,Buildings,Completed,NE-ROYAPURAM,53,589000,"Construction of Toilet in Segrigation room Shed at Burial ground at Kathpada road in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2017-18 NE/2014-15/26426,Buildings,Completed,NE-ROYAPURAM,53,999000,"Unused Toilet Converted to Fish Market at Kathpada Market at Kathpada Road in Ward-53, Unit-12, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/27868,Roads,Completed,NE-ROYAPURAM,53,156000,Improvement and Repairs to Centre median at Parthasarathy Fly over in Ward-53,Own Sources,5,2014-15,2016-17 NE/2014-15/28763,Roads,Completed,NE-ROYAPURAM,53,578000,"Laying of C.C. Road with M30 Grade Cement Concrete at Chidambaram Nagar 1st Street in Ward-53, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28767,Roads,Completed,NE-ROYAPURAM,53,578000,"Laying of C.C. Road with M30 Grade Cement Concrete at Chidambaram Nagar 2nd Street in Ward-53, Unit-12, Zone-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28769,Roads,Completed,NE-ROYAPURAM,53,491000,"Laying of C.C. Road with M30 Grade Cement Concrete at Chidambaram Nagar 3rd Street in Ward-53, Unit-12, Zone-V",Own Sources,5,2014-15,2016-17 NE/2014-15/28863,Roads,Completed,NE-ROYAPURAM,53,1736000,"Laying Cement Concrete road at M30 Grade at Chidambaram Nagar 5th Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28864,Roads,Completed,NE-ROYAPURAM,53,350000,"Laying Cement Concrete road at M30 Grade at Chidambaram Nagar 6th Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28865,Roads,Completed,NE-ROYAPURAM,53,486000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 6th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28866,Roads,Completed,NE-ROYAPURAM,53,602000,"Laying Cement Concrete road at M30 Grade at Stanly Nagar 1st Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28868,Roads,Completed,NE-ROYAPURAM,53,947000,"Laying Cement Concrete road at M30 Grade at Stanly Nagar 2nd Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28869,Roads,Completed,NE-ROYAPURAM,53,946000,"Laying Cement Concrete road at M30 Grade at Stanly Nagar 3rd Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28870,Roads,Completed,NE-ROYAPURAM,53,1830000,"Laying Cement Concrete road at M30 Grade at Stanly Nagar 4th Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28871,Roads,Completed,NE-ROYAPURAM,53,2099000,"Laying Cement Concrete road at M30 Grade at Stanly Nagar 5th Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28872,Roads,Completed,NE-ROYAPURAM,53,2996000,"Laying Cement Concrete road at M30 Grade at Stanly Nagar 6th Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28873,Roads,Completed,NE-ROYAPURAM,53,209000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 1st Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28875,Roads,Completed,NE-ROYAPURAM,53,406000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 2nd Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28876,Roads,Completed,NE-ROYAPURAM,53,517000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 3rd Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28879,Roads,Completed,NE-ROYAPURAM,53,338000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 4th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28881,Roads,Completed,NE-ROYAPURAM,53,259000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 5th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28882,Roads,Completed,NE-ROYAPURAM,53,183000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 7th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28884,Roads,Completed,NE-ROYAPURAM,53,337000,"Laying Cement Concrete road at M30 Grade at Sajja Munusamy 8th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28885,Roads,Completed,NE-ROYAPURAM,53,214000,"Laying Cement Concrete road at M30 Grade at Parasuram 1st Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28888,Roads,Completed,NE-ROYAPURAM,53,239000,"Laying Cement Concrete road at M30 Grade at Parasuram 2nd Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28889,Roads,Completed,NE-ROYAPURAM,53,209000,"Laying Cement Concrete road at M30 Grade at Parasuram 3rd Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28891,Roads,Completed,NE-ROYAPURAM,53,414000,"Laying Cement Concrete road at M30 Grade at Parasuram 4th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28894,Roads,Completed,NE-ROYAPURAM,53,184000,"Laying Cement Concrete road at M30 Grade at Parasuram 5th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28895,Roads,Completed,NE-ROYAPURAM,53,184000,"Laying Cement Concrete road at M30 Grade at Parasuram 6th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28896,Roads,Completed,NE-ROYAPURAM,53,161000,"Laying Cement Concrete road at M30 Grade at Parasuram 7th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28898,Roads,Completed,NE-ROYAPURAM,53,121000,"Laying Cement Concrete road at M30 Grade at Parasuram 8th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28900,Roads,Completed,NE-ROYAPURAM,53,254000,"Laying Cement Concrete road at M30 Grade at Sundaram Naidu Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28902,Roads,Completed,NE-ROYAPURAM,53,212000,"Laying Cement Concrete road at M30 Grade at Kollpurai Nagar 3rd Cross Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28905,Roads,Completed,NE-ROYAPURAM,53,426000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 2nd lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28908,Roads,Completed,NE-ROYAPURAM,53,2297000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 2nd street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28910,Roads,Completed,NE-ROYAPURAM,53,426000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 3rd lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29649,Roads,Completed,NE-ROYAPURAM,53,426000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 4th lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29650,Roads,Completed,NE-ROYAPURAM,53,426000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 5th lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29651,Roads,Completed,NE-ROYAPURAM,53,426000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 6th lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29652,Roads,Completed,NE-ROYAPURAM,53,451000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 7th lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29653,Roads,Completed,NE-ROYAPURAM,53,588000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar 8th lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29654,Roads,Completed,NE-ROYAPURAM,53,2562000,"Laying Cement Concrete road at M30 Grade at Bojaraja nagar Main road in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29655,Roads,Completed,NE-ROYAPURAM,53,2474000,"Laying Cement Concrete road at M30 Grade at Srinivasapuram 1st lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29656,Roads,Completed,NE-ROYAPURAM,53,213000,"Laying Cement Concrete road at M30 Grade at Srinivasapuram 2nd lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29657,Roads,Completed,NE-ROYAPURAM,53,213000,"Laying Cement Concrete road at M30 Grade at Srinivasapuram 3rd lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29658,Roads,Completed,NE-ROYAPURAM,53,214000,"Laying Cement Concrete road at M30 Grade at Srinivasapuram 4th lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29659,Roads,Completed,NE-ROYAPURAM,53,652000,"Laying Cement Concrete road at M30 Grade at M.S Nagar Main Road in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29660,Roads,Completed,NE-ROYAPURAM,53,642000,"Laying Cement Concrete road at M30 Grade at M.S Nagar 1st Cross street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29661,Roads,Completed,NE-ROYAPURAM,53,574000,"Laying Cement Concrete road at M30 Grade at M.S Nagar 2nd Cross street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29663,Roads,Completed,NE-ROYAPURAM,53,2171000,"Laying Cement Concrete road at M30 Grade at Nehru Ninaivu Nagar in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29665,Roads,Completed,NE-ROYAPURAM,53,451000,"Laying Cement Concrete road at M30 Grade at Nagappa Nagar 1st Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29666,Roads,Completed,NE-ROYAPURAM,53,346000,"Laying Cement Concrete road at M30 Grade at Nagappa Nagar 2nd Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29667,Roads,Completed,NE-ROYAPURAM,53,346000,"Laying Cement Concrete road at M30 Grade at Nagappa Nagar 3rd Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29668,Roads,Completed,NE-ROYAPURAM,53,345000,"Laying Cement Concrete road at M30 Grade at Nagappa Nagar 4th Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29669,Roads,Completed,NE-ROYAPURAM,53,1300000,"Laying Cement Concrete road at M30 Grade at Kollapuri Nagar Main road in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29670,Roads,Completed,NE-ROYAPURAM,53,250000,"Laying Cement Concrete road at M30 Grade at Kollapuri Nagar 1st Cross Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29671,Roads,Completed,NE-ROYAPURAM,53,403000,"Laying Cement Concrete road at M30 Grade at Kollapuri Nagar 2nd Cross Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30210,Roads,Completed,NE-ROYAPURAM,53,204000,"Relaying of road with BCCMP 40mm thick by paver finisher Muthiah Chetty 1st Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30213,Roads,Completed,NE-ROYAPURAM,53,199000,"Relaying of road with BCCMP 40mm thick by paver finisher Kathbada 2nd Cross Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30214,Roads,Completed,NE-ROYAPURAM,53,157000,"Relaying of road with BCCMP 40mm thick by paver finisher Kathbada 1st Cross Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30474,Roads,Completed,NE-ROYAPURAM,53,975000,"Providing temporary Bus Shelter for temporary mint new bus depo in Ward-53, Unit-12, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30475,Roads,Completed,NE-ROYAPURAM,53,309000,"Relaying of road with BCCMP 40mm thick by paver finisher Kathbada 1st Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/7479,Parks,Completed,NE-ROYAPURAM,53,268000,"Improvement to park at Stanly Nagar 5th street in ward-53, unit-12, Zone-5",Own Sources,5,2014-15,2017-18 NE/2014-15/23798,Parks,Completed,NE-ROYAPURAM,54,982000,Greenary arrangement in Sivagananam park at Peddu Street in Div-54 Unit-13 Zone-05,Own Sources,5,2014-15,2016-17 NE/2014-15/27787,Buildings,Completed,NE-ROYAPURAM,54,998000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS TO VARIOUS ROAD IN DN-54, UNIT-13, ZONE-05",Own Sources,5,2014-15,2017-18 NE/2014-15/27788,Buildings,Completed,NE-ROYAPURAM,54,996000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS TO VARIOUS STREETS IN DN-54, UNIT-13, ZONE-05",Own Sources,5,2014-15,2016-17 NE/2014-15/28520,Roads,Completed,NE-ROYAPURAM,54,1839000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KANNAIAH STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28521,Roads,Completed,NE-ROYAPURAM,54,1499000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT MUNIAPPAN STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28522,Roads,Completed,NE-ROYAPURAM,54,1513000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT PERUMAL STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28523,Roads,Completed,NE-ROYAPURAM,54,1048000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KONDAL STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28524,Roads,Completed,NE-ROYAPURAM,54,1083000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VENGU STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28525,Roads,Completed,NE-ROYAPURAM,54,1202000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT ARUNACHALA STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28526,Roads,Completed,NE-ROYAPURAM,54,1848000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT PERUMAL KOIL GARDEN MAIN STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28527,Roads,Completed,NE-ROYAPURAM,54,952000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VINAYAGAM STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28528,Roads,Completed,NE-ROYAPURAM,54,619000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT NALLANAN STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/4103,Buildings,Completed,NE-ROYAPURAM,54,998000,"IMPROVEMENT WORK FOR HEALTH POST AT V.O.C SALAI IN DIV-54, UNIT-13, ZONE-5",Own Sources,5,2014-15,2016-17 NE/2014-15/18687,Buildings,Completed,NE-ROYAPURAM,55,984000,"MPROVEMENTS TO HEALTH POST AT APPU MASTRY STREET IN DIV-55,UN-13,Z-05",Own Sources,5,2014-15,2016-17 NE/2014-15/28529,Roads,Completed,NE-ROYAPURAM,55,815000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT MANGAMMAL STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28530,Roads,Completed,NE-ROYAPURAM,55,1132000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VEERANGAVEDU STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28531,Roads,Completed,NE-ROYAPURAM,55,279000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT DHARAMARAJA KOIL 2ND LANE IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28532,Roads,Completed,NE-ROYAPURAM,55,587000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KUTTY STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28533,Roads,Completed,NE-ROYAPURAM,55,2166000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT PERIYANNA STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28534,Roads,Completed,NE-ROYAPURAM,55,2673000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT GOVINDTHAPPA STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28535,Roads,Completed,NE-ROYAPURAM,55,881000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT THIYAGARAJAN STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28536,Roads,Completed,NE-ROYAPURAM,55,1353000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VEERASAMY STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28537,Roads,Completed,NE-ROYAPURAM,55,689000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT HAWKER JAISON STREET IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 BR/2014-15/30103,Roads,Completed,BR-Bus Route Roads,56,11345000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Ibrahimji Salai (From the Junction of Clive Battery To the Junction of Thambu Chetty Street) in Division 56, Zone - V",Grants,5,2014-15,2016-17 NE/2014-15/12598,Parks,Completed,NE-ROYAPURAM,56,995000,"Construction of ELECTRONIC TOILET' at BUNDER GARDEN (GEORGE TOWN) DN--56. ,Unit ? 13 ,Zone ? V.",Own Sources,5,2014-15,2017-18 NE/2014-15/12599,Buildings,Completed,NE-ROYAPURAM,56,995000,"Construction of ?ELECTRONIC TOILET? at KATCHALEESWARAR GARDEN (GEORGE TOWN) in DN--56 ,Unit ? 13 ,Zone ? V.",Own Sources,5,2014-15,2017-18 NE/2014-15/12600,Buildings,Completed,NE-ROYAPURAM,56,995000,"Construction of ?ELECTRONIC TOILET? at AMMAN KOIL STREET (AMMAN KOIL SOUTH) in DN--56. ,Unit ? 13 ,Zone ? V.",Own Sources,5,2014-15,2017-18 NE/2014-15/17697,Buildings,Completed,NE-ROYAPURAM,56,995000,"IMPROVEMENTS TO NIGHT SHELTER AT BRN GARDEN IN DN-56,U-13,Z-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/20289,Buildings,Completed,NE-ROYAPURAM,56,395000,"improvements to storeroom,staffroom,siroom at ff in UPHS AT brn garden in dn-56,u-13,z-5.",Own Sources,5,2014-15,2018-19 NE/2014-15/28538,Roads,Completed,NE-ROYAPURAM,56,891000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT PONNIAMMAN KOIL STREET IN DN-56, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28539,Roads,Completed,NE-ROYAPURAM,56,888000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT SRINIVASAN STREET IN DN-56, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28540,Roads,Completed,NE-ROYAPURAM,56,461000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VENKATA LANE STREET IN DN-56, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/8111,Parks,Completed,NE-ROYAPURAM,56,981000,Annual Maintenance of Terrace Garden Park in Div-56 Unit-13 Zone-05,Own Sources,5,2014-15,2016-17 S/2014-15/12528,Footpath,Completed,BR-Bus Route Roads,56,24500000,"FORMING FOOTPATH AT IBRAHIMJI SAHIB ROAD FROM THE JUNCTION OF RAJAJI SALAI TO THE JUNCTION OF PRAKASAM SALAI IN DIVISION 56,60 ZONE V.",Grants,5,2014-15,2017-18 BR/2014-15/18076,Roads,Completed,BR-Bus Route Roads,57,5360000,"Relaying the road with CBC after Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Elephant Gate Bridge Road( From the Junction of Walltax road to the Middle of the Elephant Gate Bridge )Division 57 , Zone - V",Grants,5,2014-15,2016-17 NE/2014-15/12615,Buildings,Completed,NE-ROYAPURAM,57,996000,"Construction of ?ELECTRONIC TOILET? at BROADWAY (GEORGE TOWN) in DN-57,Unit ? 13 ,Zone ? V.",Own Sources,5,2014-15,2017-18 NE/2014-15/28549,Roads,Completed,NE-ROYAPURAM,57,2640000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VARADHA (M) STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28550,Roads,Completed,NE-ROYAPURAM,57,1089000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT NATTU PILLAIYAR KOIL STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28551,Roads,Completed,NE-ROYAPURAM,57,892000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT PERIYANEIKKARAN STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28552,Roads,Completed,NE-ROYAPURAM,57,889000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT CHINNA NEIKKARAN STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28553,Roads,Completed,NE-ROYAPURAM,57,1192000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT ELA KANDHAPPAN STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28554,Roads,Completed,NE-ROYAPURAM,57,2409000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT IRULAPPAN STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28555,Roads,Completed,NE-ROYAPURAM,57,2115000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KALATHI STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28556,Roads,Completed,NE-ROYAPURAM,57,1465000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KANDTHAPPA STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28557,Roads,Completed,NE-ROYAPURAM,57,1473000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT MANAGAPPAN STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28558,Roads,Completed,NE-ROYAPURAM,57,1491000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT MURUGAPPAN STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28559,Roads,Completed,NE-ROYAPURAM,57,1849000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT PALLIAPPAN STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28560,Roads,Completed,NE-ROYAPURAM,57,1074000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT PALLIAPPAN LANE IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28561,Roads,Completed,NE-ROYAPURAM,57,617000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT RAMANUJA STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28562,Roads,Completed,NE-ROYAPURAM,57,2124000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT THULASINGAM STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28563,Roads,Completed,NE-ROYAPURAM,57,785000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT THULASINGAM 1 ST LANE IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28564,Roads,Completed,NE-ROYAPURAM,57,326000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT THULASINGAM 2ND LANE IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28565,Roads,Completed,NE-ROYAPURAM,57,530000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VINAYAGA STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28566,Roads,Completed,NE-ROYAPURAM,57,1176000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KRISHNAPPA STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28567,Roads,Completed,NE-ROYAPURAM,57,3357000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT MALAYA PERUMAL STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28568,Roads,Completed,NE-ROYAPURAM,57,524000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KUMARAPPA STREET IN DN-57, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/7445,Buildings,Completed,NE-ROYAPURAM,57,990000,"Additional work in Amma unavagam in Davision street in ward-57, unit-13, zone-5",Own Sources,5,2014-15,2017-18 B/2014-15/9006,Buildings,Completed,B-Buildings,58,4769000,"SUPPLYING AND LAYING GRANITE SLAB FOR FLOOR AND WALL IN TOILETS AT RIPON BUILDING ANEX IN DN-58,ZONE-5",Own Sources,5,2014-15,2016-17 BR/2014-15/29946,Roads,Completed,BR-Bus Route Roads,58,27100000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at E.V.K.Sampath Salai(From the Junction of EVR Periyar Salai to the Junction of Narayanaguru Salai) in Division 58 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/29952,Roads,Completed,BR-Bus Route Roads,58,11400000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Tratfic improvement works at Jemaiah Road (from the junction of EVK Sampath Salai to the juction of Perambur Barracks Road) Division58, Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/29962,Roads,Completed,BR-Bus Route Roads,58,9996000,"Strengthening and Relaying the Road With DBM and CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at Purasaiwakkam High Road(from the Junction of Thana Street to the Junction of Perambur Barracks Road) in Division 58,Zone-V.",Grants,5,2014-15,2016-17 BR/2014-15/30017,Roads,Completed,BR-Bus Route Roads,58,25683000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Tratfic improvement works at Thiru Narayana Guru Salai ( from the junction of Perambur Barracks Road to the junction of Choolai High road , Division 58 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/30032,Roads,Completed,BR-Bus Route Roads,58,20984000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Vepery High Road,( From the Junction of Rajamuthiah Salai to the Junction of EVK Sampath Salai ) Division 58 , Zone - v",Grants,5,2014-15,2016-17 BR/2014-15/30048,Roads,Completed,BR-Bus Route Roads,58,34912000,"Strengthening and Relaying with DBM and CBC after cold miiling by Paver finisher using shredded plastic waste along with traffic improvement at RajaMuthaiah Salai(from the Junction of EVR Periyar Salai to the Junction of Choolai High Road) in Division-50 ,Zone-V",Grants,5,2014-15,2016-17 L/2014-15/7958,Electrical,Completed,L-Electrical,58,2496900,"Wiring with 3runs of 2.5Sqmm PVC insulated FRLS multistranded Copper conductor wire for Lighting Circuits in Auditorium ( Ground floor) and wiring of UPS power and raw power sockets in Modular workstation , cabin areas located in the 1st floor to 3rd floor of Ripon Annex building in Dn.58, Zone V.",Own Sources,5,2014-15,2016-17 NE/2014-15/10148,Parks,Completed,NE-ROYAPURAM,58,117000,"IMPROVEMENTS TO THE EXISTING DAMAGED STEPS AT ALLIKULAM PARK IN DIV-58,UNIT-14,ZONE-5",Own Sources,5,2014-15,2016-17 NE/2014-15/10154,Buildings,Completed,NE-ROYAPURAM,58,197000,"IMPROVEMENTS TO EXISTING AMMA UNAVAGAM AT WHANNELS ROAD IN DIV-58,UNIT-14,ZONE-5",Own Sources,5,2014-15,2016-17 NE/2014-15/10181,Buildings,Completed,NE-ROYAPURAM,58,326000,"REPAIRS AND IMPROVEMENTS TO VARIOUS CORPORATION BUILDINGS AND SWIMMING POOL IN ALLIKULAM IN DIV-58,UNIT-14,ZONE-5",Own Sources,5,2014-15,2016-17 NE/2014-15/11967,Buildings,Completed,NE-ROYAPURAM,58,50500,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CGHSS IN ROTTLER STREET AND DIVISION OFFICE IN DN-58,UNIT-14,ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/12400,Parks,Completed,NE-ROYAPURAM,58,786000,"Annual Maintenance Park AT Jermiah Park,Thirumalai Park,Dowton Tower Clock Park .Dn-58,Unit-14,Zone-5 Maintenance Period 6Month Only",Own Sources,5,2014-15,2016-17 NE/2014-15/12613,Buildings,Completed,NE-ROYAPURAM,58,995000,"Construction of ?ELECTRONIC TOILET? at WHANNELS ROAD (EGMORE) in DN-58 ,Unit ? 14 ,Zone ? V.",Own Sources,5,2014-15,2017-18 NE/2014-15/12678,Parks,Completed,NE-ROYAPURAM,58,46100,"PROVIDING STAINLESS STEEL PIPES FOR RAGHAVENDRA PARK AND SUPPLYING AND FIXING NAME BOARDS AT ROTTLER STREET HEALTH POST IN DN-58,UNIT-14,ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/13031,Buildings,Completed,NE-ROYAPURAM,58,157000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS CORPORATION BUILDINGS IN DIV-58.UNIT-14,ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/15638,Buildings,Completed,NE-ROYAPURAM,58,199000,"IMPROVEMENTS AND REPAIRS TO WATER LINE FACILITIES DIVISION OFFICE,COMMUNITY HALL AT KANNAPPAR THIDAL AND SUPPLYNG OF BILLING MACHINE TO ALLIKULAM SWIMMING POOL IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/15643,Buildings,Completed,NE-ROYAPURAM,58,224000,"PROVIDING BARRICADING TO FOOTBALL GROUND BY CHAIN LINK FENCING AT NAVAL HOSPITAL ROAD FOOTBALL GROUND IN DN-58,UNIT-14,ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/1610,Buildings,Completed,NE-ROYAPURAM,58,333000,"IMPROVEMENTS TO THE WORKERS ROOM IN TPF AT BASIN ELEPHANT ROAD IN DIV-58,UNIT-14,ZONE5.",Own Sources,5,2014-15,2016-17 NE/2014-15/19723,Buildings,Completed,NE-ROYAPURAM,58,242000,"IMPROVEMENTS TO THE DOVETON TOWER CLOCK IN DN-58,UNIT-14,ZONE-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/28731,Roads,Completed,NE-ROYAPURAM,58,108100,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT EDAPPALAYAM 1ST LANE IN DN-59, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28736,Roads,Completed,NE-ROYAPURAM,58,2513000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT E.K. GURU STREET IN DN-58,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28739,Roads,Completed,NE-ROYAPURAM,58,1319000,"LAYING OF C.C. ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NATESA NAGAR IN DN-58, U-14, Z-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/28740,Roads,Completed,NE-ROYAPURAM,58,1388100,"LAYING OF C.C. ROAD WITH M30 GRADE OF CEMENT CONCRETE AT PATNOOL SANDUJA STREET IN DN-58, U-14, Z-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/28741,Roads,Completed,NE-ROYAPURAM,58,520400,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT LALA KUTTY LANE IN DN-58,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28742,Roads,Completed,NE-ROYAPURAM,58,353100,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT HOSPITAL LANE N DN-58,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28748,Roads,Completed,NE-ROYAPURAM,58,832700,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KALATHIYAPPA LANE IN DN-58,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28795,Roads,Completed,NE-ROYAPURAM,58,715500,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT RAMASAMY STREET IN DN-58,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28805,Roads,Completed,NE-ROYAPURAM,58,186900,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT ASTABUJA LANE IN DN-59,U-14,Z-5",Own Sources,5,2014-15,2016-17 S/2014-15/12408,Footpath,Completed,BR-Bus Route Roads,58,16000000,"Forming Footpath at Purasaiwalkam High Road from the junction of Thana street to the junction of Perambur Barracks road in Dn 58,Zone 5",Grants,5,2014-15,2017-18 BR/2014-15/17936,Roads,Completed,BR-Bus Route Roads,59,29950000,"Relaying the Road With CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at N.S.C Bose Road (From Prakasam Salai jn to Rattan Bazaar jn)in Ward -59 ,Zone -V",Grants,5,2014-15,2017-18 BR/2014-15/30100,Roads,Completed,BR-Bus Route Roads,59,35248000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Swamy Sivanandha Salai(From the Junction of Anna Salai to the Junction of Adam Street)in Division 59 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/30633,Roads,Completed,BR-Bus Route Roads,59,11642000,"Strengthening and Relaying the Road With DBM and CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at Pallavan Salai (Stanley Via Duct Road) from the Junction of Body guard muneeswaran Koil to the Junction of E.V.R Periyar Salai in Ward -59 ,Zone -V",Grants,5,2014-15,2016-17 NE/2014-15/13074,Buildings,Completed,NE-ROYAPURAM,59,996000,"Repairs and Improvements to Public Convence at S.M.Nagar Main Road Near CSP and Anna Salai Junction (Ward Member Development Fund 2013-2014) in Dn-59,U-14,z-v.",Own Sources,5,2014-15,2016-17 NE/2014-15/13346,Buildings,Completed,NE-ROYAPURAM,59,950000,"Repair and Improvements to NNMP SHED Center no 03010 &03084 (Scheme 003) at Ellis Road in Dn-59,U-14,Z-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/18935,Storm Water Drain,Completed,NE-ROYAPURAM,59,994005,"Providing Elevation work for Amma Unavagam at Frazer bridge road in ward-59, unit-14, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/19859,Buildings,Completed,NE-ROYAPURAM,59,966000,"Providing and Fixing Name board, Aluminum Signage letters,Digital Name board, Price board, Introduction Board, Information board for Amma unvagam in Ward-59, unit-14, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/20389,Buildings,Completed,NE-ROYAPURAM,59,920000,"REPAIR AND IMPROVEMENTS OF CPS AT S.M NAGAR NEW ROAD IN DIVISION-59, UNIT-14, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/22675,Storm Water Drain,Completed,NE-ROYAPURAM,59,965000,"Improvements of Storm Water Drain (Evening Bazaar Road to CH150) at Frazer Bridge Road in Dn-59,U-14,Z-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/23222,Storm Water Drain,Completed,NE-ROYAPURAM,59,984000,"Improvements and Construction of Storm Water Drain (CH150 to Kellys Drain) at Frazer Bridge Road in Dn-59,U-14,Z-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/23309,Roads,Completed,NE-ROYAPURAM,59,588000,"Improvement to Group Bin at Various Location in Unit-14, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28726,Roads,Completed,NE-ROYAPURAM,59,1020700,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NAINIAPPA (N) STREET IN DN-59 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28727,Roads,Completed,NE-ROYAPURAM,59,195000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT VALLAL LANE IN DN-59, U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28728,Roads,Completed,NE-ROYAPURAM,59,278500,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT EDAPPALAYAM 4TH LANE IN DN-59, U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28729,Roads,Completed,NE-ROYAPURAM,59,288800,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT EDAPPALAYAM 3RD LANE IN DN-59, U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28730,Roads,Completed,NE-ROYAPURAM,59,108100,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT EDAPPALAYAM 2ND LANE IN DN-59,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28732,Roads,Completed,NE-ROYAPURAM,59,2038700,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT BANKARU AMMAN STREET AND THAYAR SAHIB 1ST LANE IN DN-59 U -14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29400,Buildings,Completed,NE-ROYAPURAM,59,450000,Repairs and Improvements to PC at VOC Salai in Div-59 Unit-14 Zone-5,Own Sources,5,2014-15,2016-17 NE/2014-15/29514,Roads,Completed,NE-ROYAPURAM,59,754000,"Relaying of road with BCCMP 40mm thick by paver finisher at Edapalyam Street in Dn-59, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29515,Roads,Completed,NE-ROYAPURAM,59,317000,"Relaying of road with BCCMP 40mm thick by paver finisher at Stringers Street in Dn-59, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29517,Roads,Completed,NE-ROYAPURAM,59,2480000,"Relaying of road with BCCMP 40mm thick by paver finisher at Ellis Street in Dn-59, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29518,Roads,Completed,NE-ROYAPURAM,59,923000,"Relaying of road with BCCMP 30mm thick by paver finisher at Bangaru Naicken Street in Dn-59, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29519,Roads,Completed,NE-ROYAPURAM,59,107500,"Relaying of road with BCCMP 30mm thick by paver finisher at Narayanan Lane in Dn-59, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29520,Roads,Completed,NE-ROYAPURAM,59,847000,"Relaying of road with BCCMP 30mm thick by paver finisher at Ponnappa chetty Street in Dn-59, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29521,Roads,Completed,NE-ROYAPURAM,59,1611000,"Relaying of road with BCCMP 40mm thick by paver finisher at Narayanappa Road in Dn-59, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/30154,Roads,Completed,NE-ROYAPURAM,59,317400,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT MOORTHY LANE IN DN-59 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30211,Roads,Completed,NE-ROYAPURAM,59,104000,"Relaying of road with BCCMP 40mm thick by paver finisher Kuppammal Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30212,Roads,Completed,NE-ROYAPURAM,59,794000,"Relaying of road with BCCMP 40mm thick by paver finisher Kathbada 3rd Cross Street in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 BR/2014-15/24634,Roads,Completed,BR-Bus Route Roads,60,47770000,"Relaying the road with CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Rajaji Salai (from Reserve Bank Subway To Junction of War memorial ) in Division - 60,Zone-5",Grants,5,2014-15,2017-18 BR/2014-15/30013,Roads,Completed,BR-Bus Route Roads,60,23762000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Kamaraj Salai (from Samy Sivanandha Salai To Junction of War memorial ) in Division 60,Zone-5",Grants,5,2014-15,2017-18 BR/2014-15/30034,Roads,Completed,BR-Bus Route Roads,60,91244000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Rajaji Salai (From the Junction of Clive Batteryto the Junction of Reserve Bank Subway) in Division 60 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/30090,Buildings,Completed,BR-Bus Route Roads,60,34021000,"Strengthening and Relaying thr road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at N.S.C Bose road (From the Junction of Rajaji Salai to the Jn. of prakasam salai)in Division 59&60,Zone-5",Grants,5,2014-15,2016-17 BR/2014-15/30096,Roads,Completed,BR-Bus Route Roads,60,27294000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Wallajah Salai (From the Junction of Anna Salai to the Junction of Arunachalam Street) in Division 60 , Zone-V",Grants,5,2014-15,2016-17 NE/2014-15/2657,Parks,Completed,NE-ROYAPURAM,60,982000,Maintenance & Improvement at Secretariat Park in Ward-60 / Unit-13 /Zone-5 (Maintenance Period 3months),Own Sources,5,2014-15,2017-18 NE/2014-15/28543,Roads,Completed,NE-ROYAPURAM,60,1706000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT MANNADY STREET IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28545,Roads,Completed,NE-ROYAPURAM,60,1009000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT GRENARY STREET IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28546,Roads,Completed,NE-ROYAPURAM,60,2574000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT JEHANGIR STREET REACH-1 IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 NE/2014-15/28547,Roads,Completed,NE-ROYAPURAM,60,4385000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT JEHANGIR STREET REACH-2 IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2014-15,2016-17 Q/2014-15/20868,Storm Water Drain,Completed,Q-Solid Waste Management,60,14950000,REMOVAL OF GARBAGE AND CONSTRUCTION DEBRIS ALONG THE COOVUM RIVER BANKS FROM THE BAY OF BENGAL MOUTH OF THE COOVUM RIVER TO THE MADURAVAYAL BYEPASS WITHIN THE CHENNAI CORP LIMIT - CRRT,Grants,5,2014-15,2016-17 Q/2014-15/31771,Storm Water Drain,Completed,Q-Solid Waste Management,60,7440000,REMOVAL OF GARBAGE AND CONSTRUCTION DEBRIS ALONG THE COOVUM RIVER BANKS FROM THE BAY OF BENGAL MOUTH OF THE COOVUM RIVER TO THE MADURAVAYAL BYEPASS WITHIN THE CHENNAI CORP LIMIT - CRRT,Grants,5,2014-15,2019-20 BR/2014-15/24628,Roads,Completed,BR-Bus Route Roads,61,6390000,"Relaying the Road With DBM and CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at Whannels Road (From the Junction of Pantheon Road To the Junction of Ganthi Irwin Road ) in Ward - 61 ,Zone -V",Grants,5,2014-15,2017-18 BR/2014-15/29947,Roads,Completed,BR-Bus Route Roads,61,7300000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at East Ramanathan Salai ( From the Junction of Gangi reddy Subway to the Junction of Mayor Ramanathan Salai )in Division 61 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/29949,Roads,Completed,BR-Bus Route Roads,61,12300000,"Strengthening and Relaying thr road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Casa major road(from the Junction of Pantheon Road to the Junction of East Ramanathan Salai ) in Division 61,Zone-V",Grants,5,2014-15,2016-17 BR/2014-15/29950,Roads,Completed,BR-Bus Route Roads,61,18100000,"Strengthening and Relaying the Road With DBM and CBC after cold milling by Paver finish using plastic Waste along with traffic improvement work at Adhithanar Salai (from the Junction of Pantheon road to the Junction of Market ) in Ward -61 ,Zone -V",Grants,5,2014-15,2016-17 BR/2014-15/29954,Roads,Completed,BR-Bus Route Roads,61,10731000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Police Commissioner office Road ( From the Junction of Pantheon road to the Junction of Gandhi irwin road )Division 61 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/29955,Roads,Completed,BR-Bus Route Roads,61,47864000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Pantheon Road ( From the junction of Langs Garden Road to the junction of Ethiraj Salai ) Division 61 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/29956,Roads,Completed,BR-Bus Route Roads,61,19464000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Ethiraj Salai(from the Junction of Binny road to the Junction of Pantheon Road) in Division 61,Zone-V",Grants,5,2014-15,2016-17 BR/2014-15/29957,Roads,Completed,BR-Bus Route Roads,61,18314000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Egmore High Road(from the Junction of Halls road to the Junction of East Ramanathan Salai) in Division , Zone-V",Grants,5,2014-15,2016-17 BR/2014-15/29958,Roads,Completed,BR-Bus Route Roads,61,23018000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Rukmani Lakshmipathy Salai(From the Junction of Adhithanar Salai to the Junction of Binny Road) in Division 61 ,Zone-V",Grants,5,2014-15,2016-17 BR/2014-15/29959,Roads,Completed,BR-Bus Route Roads,61,14645000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Tratfic improvement works at Gandhi Irwin Bridge Road(from the Junction of EVR Periyar Salai to the Junction of Pantheon Road) in Division 61 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/29960,Roads,Completed,BR-Bus Route Roads,61,29822000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Gandhi Irwin Road( From the Junction of Police Commissioner office road to the Junction of Gandhi Irwin Bridge Road )in Division 61 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/30018,Roads,Completed,BR-Bus Route Roads,61,13673000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Halls Road(From the Junction of Police Commissioner office road to the Junction of Casamajor road )in Division 61 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/30020,Roads,Completed,BR-Bus Route Roads,61,3185000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Ponniamman Koil Street(from the Junction of Whannels Road to the Junction of Gandhi irwin Bridge Road) in Division 61,Zone-V",Grants,5,2014-15,2016-17 NE/2014-15/12842,Buildings,Completed,NE-ROYAPURAM,61,559000,"CONSTRUCTION OF RAINWATER HARVESTING AT PANTHEON ROAD ,HALLS ROAD,ETHIRAJ SALAI,GANDHI IRWIN ROAD, MONTIETH ROAD,ADITHANAR SALAI,CASA MAJOR ROAD IN DN -61,U-14, Z-5",Own Sources,5,2014-15,2017-18 NE/2014-15/18404,Buildings,Completed,NE-ROYAPURAM,61,950000,"CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENT TO GREENARY ARRANGEMENTS AT ROADSIDE PARK AT PCO ROAD IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/19663,Storm Water Drain,Completed,NE-ROYAPURAM,61,946000,"Improvement to SWD at GopalSamy Nagar and East Ramanathan Salai in ward-61, unit-14, Zone-5",Own Sources,5,2014-15,2017-18 NE/2014-15/20626,Footpath,Completed,NE-ROYAPURAM,61,752000,"PROVIDING RAMP IN EXISTING FOOTPATH AT VARIOUS PLACES IN DN-61 AND DN-63 IN UNIT-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/21083,Storm Water Drain,Completed,NE-ROYAPURAM,61,388000,"Improvements to SWD at Ethiraj Lane in Div-61, Unit-14, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28809,Roads,Completed,NE-ROYAPURAM,61,2535000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT RANGACHARI STREET IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28810,Roads,Completed,NE-ROYAPURAM,61,1492000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NARAYANADASARI STREET IN DN- 61 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28811,Roads,Completed,NE-ROYAPURAM,61,418000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NAINIAPPAN STREET IN DN- 61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28812,Roads,Completed,NE-ROYAPURAM,61,2128600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT PERUMAL(R)STREET (OPP TO AMBEDKAR MANDRAM) IN DN- 61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28813,Roads,Completed,NE-ROYAPURAM,61,360000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT GENGU (R) 1ST LANE IN DN- 61 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28814,Roads,Completed,NE-ROYAPURAM,61,346000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT GENGU (R) 2ND LANE IN DN- 61 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28815,Roads,Completed,NE-ROYAPURAM,61,389000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT EGMORE HIGH ROAD 1ST LANE (SANTHOSH HOSPITAL BACK) IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28816,Roads,Completed,NE-ROYAPURAM,61,339800,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT EGMORE HIGH ROAD 2ND LANE IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28817,Roads,Completed,NE-ROYAPURAM,61,331000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NARAYANADASARI LANE IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28818,Roads,Completed,NE-ROYAPURAM,61,331000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT BASHA SAHIB 1ST LANE IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28819,Roads,Completed,NE-ROYAPURAM,61,531000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT JAMAL MOHIDEEN STREET IN DN- 61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28820,Roads,Completed,NE-ROYAPURAM,61,563000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KAJA MOHIDEEN STREET IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28821,Roads,Completed,NE-ROYAPURAM,61,442000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT ABDUL HUSSAIN STREET IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28822,Roads,Completed,NE-ROYAPURAM,61,442000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT ABDUL SUKKUR STREET IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28823,Roads,Completed,NE-ROYAPURAM,61,455000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT DR. SUKKUR STREET IN DN- 61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28824,Roads,Completed,NE-ROYAPURAM,61,840000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT AYYASAMY LANE IN DN- 61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28825,Roads,Completed,NE-ROYAPURAM,61,402000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NARAYANAN LANE IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28826,Roads,Completed,NE-ROYAPURAM,61,327000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SESHAGIRI LANE IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28827,Roads,Completed,NE-ROYAPURAM,61,547000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SESHAGIRI STREET IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28828,Roads,Completed,NE-ROYAPURAM,61,527000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT THULUKANAM STREET IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28829,Roads,Completed,NE-ROYAPURAM,61,647900,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT THIYAGARAJAN STREET IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28830,Roads,Completed,NE-ROYAPURAM,61,381600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KETTIEPONNAN STREET IN DN-61, U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28831,Roads,Completed,NE-ROYAPURAM,61,339600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT POOSARAN LANE IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28832,Roads,Completed,NE-ROYAPURAM,61,1150000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SRINIVASAN STREET IN DN-61, U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29434,Parks,Completed,NE-ROYAPURAM,61,403000,ANNUAL MAINTENANCE PARK AT INSIDE AVANAKAPPAKAM (Madras record office)in DIV-61 UNIT-14 ZONE-05,Deposit Works,5,2014-15,2017-18 NE/2014-15/29529,Roads,Completed,NE-ROYAPURAM,61,1725000,"Relaying of road with BCCMP 40mm thick by paver finisher at Sulaiman Zackaria Avenue in Dn-61,Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29531,Roads,Completed,NE-ROYAPURAM,61,406000,"Relaying of road with BCCMP 40mm thick by paver finisher at Manohar Avenue in Dn-61, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29532,Roads,Completed,NE-ROYAPURAM,61,1051000,"Relaying of road with BCCMP 40mm thick by paver finisher at Varadarajulu Street in Dn-61, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29533,Roads,Completed,NE-ROYAPURAM,61,750000,"Relaying of road with BCCMP 40mm thick by paver finisher at Gengu Reddy Subway service Road in Dn-61, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29535,Roads,Completed,NE-ROYAPURAM,61,207000,"Relaying of road with BCCMP 30mm thick by paver finisher at Syful Mulk Street in Dn-61, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29538,Roads,Completed,NE-ROYAPURAM,61,418000,"Relaying of road with BCCMP 40mm thick by paver finisher at P.C.O Lane in Dn-61, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29541,Roads,Completed,NE-ROYAPURAM,61,169000,"Relaying of road with BCCMP 30mm thick by paver finisher at Thiruvengadam Lane in Dn-61, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29543,Roads,Completed,NE-ROYAPURAM,61,290000,"Relaying of road with BCCMP 40mm thick by paver finisher at Boopathy Nagar in Dn-61, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/8532,Buildings,Completed,NE-ROYAPURAM,61,2990000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM INSIDE GOVT EYE HOSPITAL AT RUKMANILAKSHIPATHY SALAI IN DN-61,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/14385,Storm Water Drain,Completed,NE-ROYAPURAM,62,998000,"REPAIRS TO STORM WATER DRAIN AND FORMATION OF FOOTPATH AT WALLERS ROAD IN DN -62,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28660,Roads,Completed,NE-ROYAPURAM,62,763000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT MOHAMMED HUSSAIN LANE IN DN-62,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28661,Roads,Completed,NE-ROYAPURAM,62,1636600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT MUKKIYAMMAN KOIL STREET IN DN-62,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28664,Roads,Completed,NE-ROYAPURAM,62,1871300,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT REX STREET IN DN-62,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28667,Roads,Completed,NE-ROYAPURAM,62,1300000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT WEST PADAVATAMMAN KOIL STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28669,Roads,Completed,NE-ROYAPURAM,62,304000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SOUTH KOILOORAMMAN KOIL STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28671,Roads,Completed,NE-ROYAPURAM,62,419000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KRISHNAPPA (C) LANE IN DN -62 , U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28672,Roads,Completed,NE-ROYAPURAM,62,419200,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT DAWOOD (S) STREET IN DN -62 , U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28673,Roads,Completed,NE-ROYAPURAM,62,980000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT ADHIAPPA STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28674,Roads,Completed,NE-ROYAPURAM,62,444100,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NORTH PADAVATTAMAN STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28675,Roads,Completed,NE-ROYAPURAM,62,1100400,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NEW BALAKRISHNAN STREETIN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28676,Roads,Completed,NE-ROYAPURAM,62,478600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NAVALAR NEDUNCHELIYAN NAGAR FIRE PROOF HOUSE LANE (56)LANE (T.N.S.B) IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28677,Roads,Completed,NE-ROYAPURAM,62,478600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NAVALAR NEDUNCHELIYAN NAGAR SLUM IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28678,Roads,Completed,NE-ROYAPURAM,62,382500,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT MUKIAMMAN KOIL 1ST LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28679,Roads,Completed,NE-ROYAPURAM,62,404600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT MUKIAMMAN KOIL 2ND LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28680,Roads,Completed,NE-ROYAPURAM,62,360400,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KOILORAMMAN KOIL 1ST LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28681,Roads,Completed,NE-ROYAPURAM,62,954500,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT JOTHIAMMAL NAGAR (T.N.S.B) IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28682,Roads,Completed,NE-ROYAPURAM,62,648000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SOUTH PADAVATTAMMAN KOIL STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28683,Roads,Completed,NE-ROYAPURAM,62,287500,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT BALAKRISHNAN LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28684,Roads,Completed,NE-ROYAPURAM,62,1755600,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT WASHERMAN STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28713,Roads,Completed,NE-ROYAPURAM,62,748300,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT WALLERS LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28714,Roads,Completed,NE-ROYAPURAM,62,581000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SINGANAN (C) LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28715,Roads,Completed,NE-ROYAPURAM,62,382500,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SIVAPRAKASAM LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28716,Roads,Completed,NE-ROYAPURAM,62,898500,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SADASIVA (P) LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28717,Roads,Completed,NE-ROYAPURAM,62,3174900,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT RITCHIE STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28718,Roads,Completed,NE-ROYAPURAM,62,2204400,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT RAJAGOBAL (N) LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28720,Roads,Completed,NE-ROYAPURAM,62,981700,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NEW BUNGLOW STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28721,Roads,Completed,NE-ROYAPURAM,62,1639300,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KUTTY (N) STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28722,Roads,Completed,NE-ROYAPURAM,62,1319000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KRISHNAPPA (C) STRRET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28723,Roads,Completed,NE-ROYAPURAM,62,1465400,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT DR.GOVINDAN STREET IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28906,Roads,Completed,NE-ROYAPURAM,62,648000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT SINGANNA (C) 1ST , 2ND AND 3RD LANE IN DN -62 ,U-14, Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29489,Roads,Completed,NE-ROYAPURAM,62,342000,"Relaying of road with BCCMP 30mm thick by paver finisher at Mohammed Hussain street in Dn-62, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29496,Roads,Completed,NE-ROYAPURAM,62,574000,"Relaying of road with BCCMP 40mm thick by paver finisher at Bazzar Street in Dn-62, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/30171,Roads,Completed,NE-ROYAPURAM,62,528000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT WALLERS 3RD LANE IN DN-62,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30173,Roads,Completed,NE-ROYAPURAM,62,982000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT ARUNACHALAM (N) LANE IN DN-62,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30216,Roads,Completed,NE-ROYAPURAM,62,218000,"Relaying of road with BCCMP 40mm thick by paver finisher Kathbada 2nd Lane in ward-53, unit-12, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/30228,Roads,Completed,NE-ROYAPURAM,62,481000,"Relaying of road with BCCMP 30mm thick by paver finisher at Palani Andawar Koil Street in Dn-62, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/30233,Roads,Completed,NE-ROYAPURAM,62,65000,"Relaying of road with BCCMP 30mm thick by paver finisher at Iyya lane in Dn-62, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 BR/2014-15/29951,Roads,Completed,BR-Bus Route Roads,63,6500000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Dams Road ( From the Junction of Annasalai to the junction of Blackers Road ) Division 63 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/29953,Roads,Completed,BR-Bus Route Roads,63,9181000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Deputy Mayor Kabalamurthy Salai(from the Junction of Anna Salai to the Junction of Arunachalam Street) in Division 62 , Zone-V",Grants,5,2014-15,2016-17 BR/2014-15/29961,Roads,Completed,BR-Bus Route Roads,63,22681000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Langs Garden Road(from the Jun. of Pantheon road to the Jun. of Adithanar Salai), Division 61 & 63 , Zone - V",Grants,5,2014-15,2016-17 BR/2014-15/30016,Roads,Completed,BR-Bus Route Roads,63,18621000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Link road (from the Junction of Boothaperumal Koil street to the Junction of Binny Road) in Division 63,Zone-5",Grants,5,2014-15,2017-18 BR/2014-15/30019,Roads,Completed,BR-Bus Route Roads,63,9913000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Boothaperumal Koil Street (from the Junction of Link road to the Junction of Dams Road) in Division 63,Zone-5",Grants,5,2014-15,2017-18 BR/2014-15/30021,Roads,Completed,BR-Bus Route Roads,63,18672000,"Strengthening and Relaying thr road with DBM and CBC after cold milling by Paver finish using plastic waste along with traffic improvement work at Thiru - Vi - Ka High Road Part II( G.P.Road)(From the Junction of Anna Salai to the Junction of Woods Road) in Division 63 , Zone-V.",Grants,5,2014-15,2016-17 NE/2014-15/19358,Footpath,Completed,NE-ROYAPURAM,63,665000,"PROVIDING RAMP IN EXISTING FOOTPATH AT VARIOUS PLACES in ward-63, unit-14, zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28689,Roads,Completed,NE-ROYAPURAM,63,406000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT KARIM MOHIDEEN 2ND TO 8TH LANE IN DN-63 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28691,Roads,Completed,NE-ROYAPURAM,63,3418000,"LAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NARAYANAN (N) 1st to 12th LANE IN DN-63 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/28693,Roads,Completed,NE-ROYAPURAM,63,606000,"LLAYING C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT MOHAN DOSS LANE IN DN-63 ,U-14,Z-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29551,Roads,Completed,NE-ROYAPURAM,63,275000,"Relaying of road with BCCMP 30mm thick by paver finisher at Sadu (c)Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29552,Roads,Completed,NE-ROYAPURAM,63,585000,"Relaying of road with BCCMP 40mm thick by paver finisher at Meeran Sahib Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29553,Roads,Completed,NE-ROYAPURAM,63,470000,"Relaying of road with BCCMP 40mm thick by paver finisher at Boobegam Street in Dn-63, Unit-14, Zone-5",Own Sources,5,2014-15,2016-17 NE/2014-15/29555,Roads,Completed,NE-ROYAPURAM,63,287000,"Relaying of road with BCCMP 40mm thick by paver finisher at Swamy Achari Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29556,Roads,Completed,NE-ROYAPURAM,63,406000,"Relaying of road with BCCMP 40mm thick by paver finisher at Byram Jung Bahadur Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29558,Roads,Completed,NE-ROYAPURAM,63,411000,"Relaying of road with BCCMP 40mm thick by paver finisher at Oil Monger Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29559,Roads,Completed,NE-ROYAPURAM,63,1290000,"Relaying of road with BCCMP 40mm thick by paver finisher atChella Pillayar Koil Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29564,Roads,Completed,NE-ROYAPURAM,63,777000,"Relaying of road with BCCMP 40mm thick by paver finisher at Velayudha Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/29565,Roads,Completed,NE-ROYAPURAM,63,686000,"Relaying of road with BCCMP 40mm thick by paver finisher at Nagappa (M) Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/30243,Roads,Completed,NE-ROYAPURAM,63,60700,"Relaying of road with BCCMP 30mm thick by paver finisher at Oil Monger Lane in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/30244,Roads,Completed,NE-ROYAPURAM,63,653000,"Relaying of road with BCCMP 40mm thick by paver finisher at Burrah (S) Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 NE/2014-15/30245,Roads,Completed,NE-ROYAPURAM,63,207800,"Relaying of road with BCCMP 30mm thick by paver finisher at Neelikara veerasamy street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2014-15,2016-17 BR/2014-15/29967,Roads,Completed,BR-Bus Route Roads,64,8900000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Senthil Nagar I Main Road from Thillai nagar I Cross Street to Srinivasa Nagar I Main Road in Dn.64, Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29970,Roads,Completed,BR-Bus Route Roads,64,4644000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Burial Ground Road from the jn of Srinivasa nagar I main Road to Periyar Street, Then Palalani Nagar in Dn.64, Zone-Vi",Grants,6,2014-15,2016-17 BR/2014-15/29971,Roads,Completed,BR-Bus Route Roads,64,4013000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Balaji Nagar Main Road from thr jn of paper Mills Road to 80 Feet Road in Dn.64, Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29972,Roads,Completed,BR-Bus Route Roads,64,5698000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Jawhar Nagar Main Road from SRP Koil Street to 70 Feet Road in Dn.64, Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29973,Roads,Completed,BR-Bus Route Roads,64,12137000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Sembium Redhills Road from Balaji nagar I Main Road to Inner Ring Road Signal in Dn.64 & 65, Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29976,Roads,Completed,BR-Bus Route Roads,64,13990000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Poombuhar Nagar Main Road from Kolathur main Road to Poombuhar Nagar 2nd Main Road in Dn.64, Zone-VI",Grants,6,2014-15,2016-17 NF/2014-15/16581,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,975000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT THENPALANI NAGAR PERIYAR STREET IN DN 64 U 15 ,Z 6",Own Sources,6,2014-15,2016-17 NF/2014-15/19625,Electrical,Completed,NF-THIRU-VI-KA NAGAR,64,442300,Provision of additional electrification work and electrical fittings at least prize canteen centers in div 64 to 78 at various places in zone VI,Own Sources,6,2014-15,2016-17 NF/2014-15/24169,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1130000,"Relaying of BT Coures with paver finisher at selliyaman nagar main road in Dn-64,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/27276,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,2240000,Laying Cement Concrete road at Kannagi nagar Kambar street in Dn64 U15 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/27282,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,695000,Laying Cement Concrete road at Kannagi nagar Anna cross street in Dn64 U15 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/27285,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1190000,Laying Cement Concrete road at Kannagi nagar Subramaniyam street in Dn64 U15 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/28491,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,965000,"Relaying of BT Road at Venkateshwara nagar Vinayagar kovil street in Div-64,Unit-15,Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28492,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,940000,"Relaying of BT Road at Venkateshwara nagar Veeramaamunivar street in Div-64,Unit-15,Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28494,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,990000,"Relaying of BT Road at Thenpalani nagar Thiruvalluvar street in Div-64,Unit-15,Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28495,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,980000,"Relaying of BT Road at Thenpalani nagar Muthumariamman kovil street in Div-64,Unit-15,Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28497,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,900000,"Relaying of BT Road at Uma maheshwari nagar 7th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29026,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,92000,"Providing flooring arrangement and Special repairs to Kamaraj nagar PC in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29209,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1050000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 3rd street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29210,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,840000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 4th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29211,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1470000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 5th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29212,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,530000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 6th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29213,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1080000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 10th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29214,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1160000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 12th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29216,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1150000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 14th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29217,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1150000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 15th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29218,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1150000,"Relayig existing BT Road with BC 30mm thick at Poompugar nagar 16th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29220,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,999000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 18th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29221,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,995000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 19th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29224,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1430000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 20th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29225,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,995000,"Relaying existing BT Road BC 30mm thick at Poompugar nagar 21th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29227,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1430000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 22nd street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29230,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1650000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 27th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29231,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,2100000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 28th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29233,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,670000,"Providing BT Road at Poompugar nagar 30th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29235,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1520000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 3rd cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29236,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,730000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 4th cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29237,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1070000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 5th cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29239,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,950000,"Relaying existing BT Road with BC 30mm thick at Poompugar nagar 6th cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29248,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,460000,"Relaying existing BT Road with BC 30mm thick at Jeyaram nagar 1st cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29249,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1230000,"Relaying existing BT Road with BC 30mm thick at Jeyaram nagar 2nd cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29250,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,375000,"Relaying existing BT Road with BC 30mm thick at Jeyaram nagar 3rd cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29251,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,430000,"Relaying existing BT Road with BC 30mm thick at Jeyaram nagar 4th cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29252,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,850000,"Relaying existing BT Road with 30mm thick BC at Thanigai nagar Valmigi street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29253,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,490000,"Relaying existing BT Road with 30mm thick at Thanigai nagar Kalamegam street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29254,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,430000,"Relaying existing BT Road with BC 30mm thick at Thanigai nagar Veeramamuni street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29255,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,680000,"Relayimng existing BT Road with 30mm thick at Thanigai nagar Sanakiya street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29257,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,860000,"Relaying existing BT Road with BC 30mm thick at Venkateshwara nagar Indira street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29258,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1250000,"Relaying existing BT Road with BC 30mm thick at Venkateshwara nagar Anna street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29260,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,630000,"Relaying existing BT Road with BC 30mm thick at Venkateshwara nagar Nehru street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29270,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,325000,"Providing BT Road with BC 30mm thick at Thenpalani nagar V.O.C street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29271,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1680000,"Providing BT Road with BC 30mm thick at Nehru street Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29272,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1270000,"Providing BT Road with BC 30mm thick at Anna street Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29403,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,910000,"Providing Street furniture at Haridos colony, Santhi nagar & Kolathur colony in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29422,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,103300,RELAYING OF BT COURES WITH PAVER FINISHER AT LAKSHMI NAGAR MAIN ROAD IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29424,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,322000,RELAYING OF BT COURES WITH PAVER FINISHER AT LAKSHMI NAGAR 2ND STREET DN64 UNIT15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29428,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,154000,RELAYING OF BT COURES WITH PAVER FINISHER AT LAKSHMI NAGAR 3RD STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29429,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,281000,RELAYING OF BT COURES WITH PAVER FINISHER AT LAKSHMI NAGAR 4TH STREET IN DN64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29433,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,497000,RELAYING OF BT COURES WITH PAVER FINISHER AT LAKSHMI NAGAR 5TH STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29437,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,311000,RELAYING OF BT COURES WITH PAVER FINISHER AT LAKSHMI NAGAR 7TH STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29443,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,412000,RELAYING OF BT COURES WITH PAVER FINISHER AT ARJUN NAGAR 1ST STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29444,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,280000,RELAYING OF BT COURES WITH PAVER FINISHER AT ARJUN NAGAR 2ND STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29445,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,267800,RELAYING OF BT COURES WITH PAVER FINISHER AT ARJUN NAGAR 3RD STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29446,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,576900,RELAYING OF BT COURES WITH PAVER FINISHER AT RAMDASS NAGAR 1ST STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29447,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,423300,RELAYING OF BT COURES WITH PAVER FINISHER AT RAMDASS NAGAR 2ND STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29452,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,618000,RELAYING OF BT COURES WITH PAVER FINISHER AT GANGA DEVI NAGAR MAIN ROAD IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29456,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,267800,RELAYING OF BT COURES WITH PAVER FINISHER AT GANGA DAVI NAGAR CROSS STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29459,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,675000,RELAYING OF BT COURES WITH PAVER FINISHER AT VETRIVEL NAGAR 1ST CROSS STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29464,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,239000,RELAYING OF BT COURES WITH PAVER FINISHER AT VETRIVEL NAGAR 3RD CROSS STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29466,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,679000,RELAYING OF BT COURES WITH PAVER FINISHER AT SUNDRAM NAGAR1ST STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29468,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,488000,RELAYING OF BT COURES WITH PAVER FINISHER AT SUNDRAM NAGAR 2ND STREET IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29841,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,730000,"RELAYING BT ROAD AT POOMPUGAR NAGAR EAST STREET IN DIV-64, UNIT-15, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/29866,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,998000,"Proposed construction of modern stainless steel bus shelter at 200' feet road , Kannagi nagar in Div-64,Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30703,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,970000,"Providing and fixing of street name board at Kannagi nagar,Uma maheshwari nagar,Poompugar nagar,Thenpalani nagar and various streets in Dn-64,unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/30704,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,970000,"Providing and fixing of street name board at Balaji nagar,Velavan nagar,Nermai nagar,Tiruppathi nagar,Valarmathi nagar,Srinagar colony and various streets in Dn-64,unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/30706,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,740000,"Relaying the BT Road at Ashoka avenue 5th cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30707,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,730000,"Relaying the BT Road at Ashoka avenue 4th cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30708,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,380000,"Relaying the BT Road at Ashoka avenue 3rd cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30709,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,255000,"Relaying the BT Road at Ashoka avenue 2nd cross street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30710,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,670000,"Relaying the BT Road at Ashoka avenue 2nd main road in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30714,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,390700,"Relaying the BT Road at Tiruppathi nagar extn Annai Indira street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30715,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,320800,"Relaying the BT Road at Nedaji street in Div-64, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30764,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,998000,"PROPOSED CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER AT POOMPUGAR NAGAR 1ST MAIN ROAD IN DIV-64,UNIT-15,ZONE-6 (WARD COUNCILOR FUND )",Own Sources,6,2014-15,2016-17 NF/2014-15/30765,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,998000,PROPOSED CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER AT SEMBIUM REDHILLS ROAD NEAR ANNA STATUE IN DN64 U-15 Z- 6 (WARD COUNCILLOR FUND ),Own Sources,6,2014-15,2016-17 NF/2014-15/30766,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,998000,PROPOSED CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER AT RETARY JUNCTION DN64 U 15 Z 06 (WARD COUNCILLOR FUND),Own Sources,6,2014-15,2016-17 NF/2014-15/9412,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at 1st Main Road Thanigai Nagar(kolathur) in Dn-64, Unit -15 , Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/9413,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at 1st Main Road Durga Colony(kolathur) in Dn-64, Unit -15 , Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/9892,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,654000,Improvements to Footpath at VELMURUGAN nagar 2nd main road in Dn64 U15 Z06,Own Sources,6,2014-15,2016-17 BR/2014-15/29966,Roads,Completed,BR-Bus Route Roads,65,34007000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Paper Mills Road from the jn of Perambur High Road South to balaji Nagar Main Road in Dn.65, 66 & 69 ,Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29974,Roads,Completed,BR-Bus Route Roads,65,1953000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Thillai Nagar I main Road from Thillai nagar I Cross Street to Inner Ring Road in dn.65, Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29977,Roads,Completed,BR-Bus Route Roads,65,3787000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Srinivasa Nagar I Main Road jn of Burial Ground Road ( Makkaram Thottam) to Baba Nagar I Main Road in Dn.65, Zone-VI",Grants,6,2014-15,2016-17 NF/2014-15/20825,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1180000,"RELAYING OF CEMENT CONCRETE ROAD AT KOLATHUR INDIRA NAGAR 3RD STREET,DN-65,UNIT-15,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20872,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,759000,"RELAYING OF C.C ROAD AT MAKKARAM THOTTAM THIRUVALLUVAR STREET,DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20888,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,604000,RELAYING CEMENT CONCRETE ROAD AT MAKKARAM THOTTAM V.O.C STREET IN DN-65 U-15 Z-6.,Own Sources,6,2014-15,2016-17 NF/2014-15/21029,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1792000,"LAYING OF C.C ROAD AT MAKKARAM THOTTAM ANNA STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21043,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,533000,"RELAYING OF C.C ROAD AT MAKKARAM THOTTAM KARUMARIAMMAN STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21048,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,949000,"LAYING OF C.C ROAD AT MAKKARAM THOTTAM BHARATHI STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21056,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1189000,"LAYING OF C.C ROAD AT MAKKARAM THOTTAM KAMARAJAR STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21532,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1677000,"RELAYING OF C.C ROAD AT G.K.M COLONY 43RD STREET THILLAIYADI VALLIAMMAI STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21537,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,3817000,"LAYING OF C.C ROAD AT G.K.M COLONY 42ND STREET JEGAJEEVAN STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21540,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,944000,"RELAYING C.C ROAD AT RAJAJI NAGAR RATHINAM AVENUE IN DN-65,U-15,Zn-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21550,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,7183000,"LAYING OF C.C ROAD AT G.K.M COLONY 34TH STREET VINOBAAJI STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21581,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,336000,"LAYING OF C.C ROAD AT MUTHAMIL NAGAR 1ST STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21582,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,569000,"LAYING OF C.C ROAD AT MUTHAMIL NAGAR 2ND STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21708,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,148000,"RELAYING EXISTING BT ROAD WITH BC40MM THICK AT LAKSHMI THILAGAM STREET IN DN-65,U-15,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/27718,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,472000,"LAYING OF C.C ROAD AT MAKKARAM THOTTAM PERIYAR STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/27719,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,2597000,"LAYING OF C.C ROAD AT MAKKARAM THOTTAM PERUMAL KOIL STREET IN DN-65,U-15,Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/2884,Footpath,Completed,NF-THIRU-VI-KA NAGAR,65,370000,"LAYING OF FOOT PATH AT SENTHIL NAGAR 4TH CROSS STREET IN DN 65,U15 Z6",Own Sources,6,2014-15,2017-18 NF/2014-15/2885,Footpath,Completed,NF-THIRU-VI-KA NAGAR,65,370000,"LAYING OF FOOT PATH AT SENTHIL NAGAR 5TH CROSS STREET IN DN-65,U-15,Z-6",Own Sources,6,2014-15,2017-18 NF/2014-15/29710,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,256000,"Relaying existing BT road WITH BC 40mm thick Selvi Nagar 1st Street in Div-65 Unit-15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/29713,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,126000,"Relaying BT road with BC40MM Thick at 1st and 2nd Street link road-Rajaji Nagar-Div-65,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/29790,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,2967000,"Relaying existing BT road WITH BC 30mm thick at Rajaji Nagar 4th Street in Div-65, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29916,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,399000,"Relaying existing BT road WITH BC 40mm thick at Ganga Street in Div-65, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29919,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,271000,"Relaying existing BT road WITH BC 40mm thick at Selvi Nagar 5th Street in Div-65, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29924,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,790000,"Relaying existing BT road WITH BC 40mm thick at Annai terasa street in Div-65, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29928,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,371000,"Relaying existing BT road WITH BC 40mm thick at Selvi Nagar 4th Street in Div-65, Unit-15, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/31517,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,867000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT GKM COLONY 35TH STREET AZAD STREET(REACH 1) IN DIV-65, U-15, Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/31522,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,880000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT GKM COLONY 35RD STREET AZAD STREET(REACH 3) IN DIV-65, U-15, Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/31523,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,257000,"IMPROVEMENT TO E-SEVAI, AT DIVISION OFFICE IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/31524,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,300000,"IMPROVEMENT TO FENCING AT GKM COLONY 1ST MAIN ROAD GORUND AND FIXING FRC DOORS IN VARIES STREETS IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/31525,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,140000,"IMPROVEMENT TO STORE ROOM AT DIVISION OFFICE IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/31526,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,266000,"IMPROVEMENT TO REST ROOM & TOILET AT DIVISION OFFICE IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/31527,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,317000,"IMPROVEMENT TO BORE IN SCHOOL AT SRINIVASAN STREET IN DIV-65, U-15, Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/31528,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,169000,"IMPROVEMENT TO DIVISION OFFICE IN DIV-65, U-15, Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/31529,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,270000,"PROVIDING AND FIXING OF STREET NAME BOARD STICKERING AT VARIES STREETS IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/31668,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,139000,"Providing screw gearing shutter arrangements in the Storm water drain to avoid the overflow of water @ 200'ft road jn of Vivekandanda Salai in Dn-65,Unit-15,Zone-06",Own Sources,6,2014-15,2016-17 NF/2014-15/31669,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,189000,"Providing screw gearing shutter arrangements in the Storm water drain to avoid the overflow of water @ 200'ft road jn of thirumalai Nagar in Dn-65,Unit-15,Zone-06",Own Sources,6,2014-15,2016-17 NF/2014-15/31670,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,181000,"Providing screw gearing shutter arrangements in the Storm water drain to avoid the overflow of water @ 200'ft road jn of SivanadhaSalai in Dn-65,Unit-15,Zone-06",Own Sources,6,2014-15,2016-17 NF/2014-15/31671,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,722000,"Desilting the canal from Retteri disposal to Metro water filling station along Thiruvallur Street,Kanagi Nagar in Dn-65,Unit-15,Zone-06",Own Sources,6,2014-15,2018-19 NF/2014-15/9415,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at Thiruvalluvar Nagar Lakshmipuram in Dn-65, Unit -15 , Zone-6.",Own Sources,6,2014-15,2016-17 BR/2014-15/29975,Roads,Completed,BR-Bus Route Roads,66,3505000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Kandasamy Salai from the jn of Jaganathan Salai to the jn of Venkateshan salai in Dn -66,Zone -6",Grants,6,2014-15,2016-17 NF/2014-15/10189,Playfields,Completed,NF-THIRU-VI-KA NAGAR,66,880000,Improvements to play ground 2nd Circular road at in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/14845,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,998000,Providing Street Furniture at Various Street at Vetri Nagar in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/14851,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,996000,Providing and Fixing Street Furniture Various Street at Kumaran Nagar and Vetri nagar Extn in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/14852,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,996000,"Providing and Fixing Street Furniture Various Street at Ramamurthy Colony, Ram Nagar,Lakshman Nagar in Dn66 U16 Z06",Own Sources,6,2014-15,2016-17 NF/2014-15/17664,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,274000,Maintenance of Park by Private Agency for Two Years at Sakthivel Nagar Park in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/17666,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,317000,Maintenance of Park by Private Agency for Two years at Jawaharl Nagar 5th main road Park in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/17669,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,950000,Attending Special Repair works for park at Periyar nagar 20th st Park in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/17991,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,810000,Providing and Laying Interlocking Paver Block at Annal Ganthi Cross Street in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/22604,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,69000,Repairs works to Collapsed Swd at Siva Elango Salai and Govindha samy street in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/24514,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1580000,"Relaying the BT road at Sakthivel nagar 1st street in DIV-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25324,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1150000,"Relaying the BT Road at Selliyamman kovil 2nd street in Div-66,Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25367,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1400000,"Relaying the BT Road at Sakthivel nagar 2nd street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25378,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1650000,"Relaying the BT Road at Sakthivel nagar 3rd street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25413,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2850000,"Relaying the BT Road at Periyar nagar 1st street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25417,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2290000,"Relaying the BT Road at Periyar nagar 2nd street in Div -66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25425,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2290000,"Relaying the BT Road at Periyar nagar 3rd street & Periyar nagar 5th street (East portion) in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25483,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2500000,"Relaying the BT Road at Periyar nagar 4th street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25484,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2500000,"Relaying the BT Road at Periyar nagar 6th street & Periyar nagar 5th cross street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25494,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2670000,"Relaying the BT Road at Periyar nagar 7th street & Periyar nagar 7th cross street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25498,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1900000,"Relaying the BT Road at Periyar nagar 8th street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25501,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1900000,"Relaying the BT Road at Periyar nagar 9th street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25508,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1900000,"Relaying the BT Road at Periyar nagar 10th street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25511,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1800000,"Relaying the BT Road at Periyar nagar 11th street in Div -66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25758,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,3350000,"Relaying the BT Road at Venkatraman salai in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25771,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,4300000,"Relaying the BT with BC 40mm thick at Jeganathan salai in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25799,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2620000,"Relaying the BT Road at Devakiammal cross street & Devakiammal main street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25821,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1040000,"Relaying the BT Road at Venugopal street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/27242,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,4000000,"RELAYING THE CC Road at Rangasamy street in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29028,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,99000,"Providing Drainage Arrangement and Repair works to PC at Kamaraj nagar in Div-66, Unit-16, Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30044,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,998000,"Proposed construction of modern stainless steel bus shelter at Paper mills road (Near don bosco school) in Div-66, Unit -16,Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30045,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,998000,"Proposed construction of modern stainless steel bus shelter at 80' road (Near Ramani bai colony in Div-66, Unit -16,Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30056,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,940000,"FORMING OF SPEED BREAKER AS PER IRC STANDARDS at BALASUBRAMANIAN SALAI ,KANDASAMY SALAI & JEGANNATHAN SALAI IN DIVISION -66, UNIT -16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/30093,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,925000,"FORMING OF SPEED BREAKER AS PER IRC STANDARDS at KARTHIKEYAN SALAI, PAPER MILLS ROAD IN DIVISION -66, UNIT -16, ZONE-6",Own Sources,6,2014-15,2018-19 NF/2014-15/6018,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,400000,Improvements to Footpath at Manavalan Street in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/6021,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,320000,Improvements to Footpath at Karthikl Street and Viswanathan street in Dn66 U16 Z06,Own Sources,6,2014-15,2016-17 NF/2014-15/14276,Footpath,Completed,NF-THIRU-VI-KA NAGAR,67,997000,"Improvements to Footh path using Granite Kerb stones at LOCO SCHEME 2nd Street (part) in Dn - 67, Unit -15 , Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/15892,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,974000,"Construction and Erection of Shed at Market street CGHSS Shool in Dn-67, Unit -15 , Zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/15893,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,114000,"CONSTRUCTION OF COMPOSITE BIN AT ANANDAN PARK IN DN-67, UNIT-15, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/15963,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,540000,"Relaying of BT course with paver finisher at Loco scheme 2nd street (part) in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2018-19 NF/2014-15/15964,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,880000,"Relaying of BT course with paver finisher at Palavayal road in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2018-19 NF/2014-15/15965,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,589000,"Relaying of BT course with paver finisher at Govindajulu street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/15966,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,690000,"Relaying of BT course with paver finisher at Bisset Road in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/15967,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,997000,"reet Relaying of BT course with paver finisher at Thanthondriamman koil street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/15968,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,400000,"Relaying of BT course with paver finisher at Rajput street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2018-19 NF/2014-15/15971,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,987000,"Providing and fixing Street Name Board Various street Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/15975,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,990000,"attending patch work at various street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/16736,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,915000,"Providing and fixing of Roof truss and Roofing sheet at Market street CGHSS Shool in Dn-67, Unit -15 , Zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/19757,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,223000,"Relaying the Cement Concrete Road at Loco work 3rd lane in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19758,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,325000,"Relaying the Cement Concrete Road at Loco works 2nd lane in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19759,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,340000,"Relaying the Cement Concrete Road at loco work 1st lane in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19760,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,745000,"Relaying the Cement Concrete Road at Loco works 1st Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19762,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,965000,"Relaying the Cement Concrete Road at Somaramasamy Main Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19763,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,995000,"Relaying the Cement Concrete Road at Ballard street (from thulukanathamman koil to chengalvaryan stret junction) in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19764,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,545000,"Relaying the Cement Concrete Road at Malligaipoo Garden in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20836,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,2279000,"Relaying the Cement Concrete Road at Annai Anjugam Nagar Thalamuthu street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20845,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,2504000,"Relaying the Cement Concrete Road at G.K.M Colony 24th A Amman koil street Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20846,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,357000,"Relaying the Cement Concrete Road at Radakrishnan Nagar Thilayadi Valliamai Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20847,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,712000,"Relaying the Cement Concrete Road at Radakrishnan Nagar Elango Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20848,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,2438000,"Relaying the Cement Concrete Road at Parthasarthy Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20849,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,893000,"Relaying the Cement Concrete Road at Somaramasamy 3rd Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20850,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1515000,"Relaying the Cement Concrete Road at Annai Anjugam Nagar Periyar Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20851,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,4482000,"Relaying the Cement Concrete Road at Market Street in Dn-67, Unit- 15, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20874,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,428000,"Relaying of BT course with paver finisher at Thullukathaman lane in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20876,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1485000,"Relaying of BT course with paver finisher at GKM Colony 23rd Street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20877,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1922000,"Relaying of BT course with paver finisher at Kumaran Nagar Cross Street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20878,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1922000,"Relaying of BT course with paver finisher at Sai Nagar Cross Street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20879,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1354000,"Relaying of BT course with paver finisher at GKM 21st Nethaji Street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20880,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1516000,"Relaying of BT course with paver finisher at G.K.M Cololy 24th street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20883,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,2952000,"Relaying the Cement Concrete Road at Ballard street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/22611,Playfields,Completed,NF-THIRU-VI-KA NAGAR,67,873000,"IMPROVEMENTS TO PLAY FILED AT AMIRTHAMMAL COLONY, GOPAL COLONY 3RD STREET, LOCO WORKS ROAD, THULUKANATHAMMAN KOIL STREET, SOMARAMA SAMY 3RD STREET,LOCO WORK 2ND STREET, WATER WORKS ROAD IN DN 67 UNIT 15 ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/24186,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,690000,"RELAYING C.C ROAD AT G.K.M COLONY 10TH KAMARAJAR STREET IN DIVISION-67,UNIT-15,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/25721,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1014000,RELAYING THE CEMENT CONCRETE ROAD AT JOGI HUTS IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/28751,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,850000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT JAMBULINGAM MANI ROAD IN DN-67, UNIT-15, ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/30196,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,999000,"PROVIDING SPEED BREAKERS AT VARIOUS LOCATIONS IN DN -67,UNIT -15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/30662,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,525000,"Relaying of BT course with paver finisher at G.K.M Colony 9th street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/30663,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,995000,"Relaying of BT course with paver finisher at Anni Anjugam Nagar Karunanithi street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/30664,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,995000,"Relaying of BT course with paver finisher at G.K.M Cololy 5th street in Dn-67,Unit-15,Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/31547,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,210000,"IMPROVEMENT TO GROUP BIN AT VARIES STREETS IN DN-67, UNIT-15, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/31549,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,385000,"IMPROVEMENT TO SOMIYA SCHOOL, MARKET SCHOOL, KUMARAMANGALAM COLONY SCHOOL IN DN-67, UNIT-15, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/9405,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at Gandhi Nagar in Dn-67, Unit -15 , Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/9409,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at Gandhi Naga(Agaram) in Dn-67, Unit -15 , Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/17708,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,990000,LAYING CEMENT CONCRETE ROAD JAMALIYA LANE (MADURAI SAMY MADAM LANE) IN DN 68 UNIT 16 ZONE6,Own Sources,6,2014-15,2016-17 NF/2014-15/18261,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,560000,"improvements to existing gym and play ground at madurai samy madam in Ward 68, Unit 16, Zone 6",Own Sources,6,2014-15,2016-17 NF/2014-15/18316,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,990000,"LAYING CEMENT CONCERATE ROAD AT MADURAI SAMY MADAM LANE IN DN 68,UNIT 16, ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/18840,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,990000,REPAIRS & ANNUAL MAINTANENCE WORK TO 68 WARD OFFICE IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19013,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,999000,"LAYING CEMENT CONCRETE ROAD AT MALLIPOO NAGAR IN DN 68 ,UNIT 16, ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/19015,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,990000,ROAD WIDENING AT PRAKASAM STREET IN DN68 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19046,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,999000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT PAPER MILLS ROAD ( NEAR KAMRAJ STATUE) IN DN-68, UNIT-16, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/19047,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,470000,IMPROVEMENT TO FLOORING IN FRONT OF DIVISION OFFICE AT PAPER MILLS ROAD IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19071,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,750000,"LAYING CEMENT CONCRETE ROAD AT MALLIPOO LANE IN DN 68 ,UNIT 16, ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/19216,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,999000,REPAIRS AND IMPROVEMENT TO THE FOOTPATH AT PALLAVAN SALAI IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/21732,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,990000,PROVIDING NEW SPEED BREAKER AT VARIOUS STREETS IN DIV-68 UNIT-16 ZONE-6,Own Sources,6,2014-15,2016-17 NF/2014-15/23736,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,318600,REPAIRS AND IMOROVEMENTS TO PUBLIC TOILET MADURAISAMY MADAM ST AND SRP KOIL STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/9416,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at Thiru.Vi.Ka.Nagar Perambur in Dn-68, Unit -16 , Zone-6.",Own Sources,6,2014-15,2017-18 NF/2014-15/13508,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,990000,"LAYING CEMENT CONCRETE ROAD AT BAJANAI KOIL STREET IN DN 69, UNIT - 16, ZONE - VI",Own Sources,6,2014-15,2016-17 NF/2014-15/13510,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,994000,"LAYING CEMENT CONCRETE ROAD AT DAMOTHARAN STREET IN DN 69, UNIT - 16, ZONE - VI",Own Sources,6,2014-15,2016-17 NF/2014-15/13511,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,970000,"LAYING CEMENT CONCRETE ROAD AT THANIKACHALAM LANE IN DN 69, UNIT - 16, ZONE - VI",Own Sources,6,2014-15,2016-17 NF/2014-15/13976,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,792000,"LAYING CEMENT CONCRETE ROAD AT RAJA STREET 1,2 & 3 LANES IN DIV-69, UNIT-16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/13991,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,840000,"PROVIDING STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREETS IN DN 69, UNIT -15, ZONE - 06",Own Sources,6,2014-15,2016-17 NF/2014-15/13998,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,792000,"LAYING CEMENT CONCRETE ROAD AT FOXEN STREET AND LANES IN DIV-69, UNIT-16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/14569,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,807000,"LAYING CEMENT CONCRETE ROAD AT SRINIVASA RAGHAVA LANE AND SIRUVALLUR LANE IN DN 69, UNIT - 16, ZONE - VI",Own Sources,6,2014-15,2016-17 NF/2014-15/14570,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,829000,"LAYING CEMENT CONCRETE ROAD AT M.H ROAD 1ST LANE IN DN - 69, UNIT - 16, ZONE - VI",Own Sources,6,2014-15,2016-17 NF/2014-15/14846,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,543000,"LAYING CEMENT CONCRETE ROAD AT PAPER MILLS LANE IN 69, UNIT- 16, ZONE - VI",Own Sources,6,2014-15,2016-17 NF/2014-15/16432,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,997000,"PROVIDING STREET FURNITURES AT SSV KOIL STREETS, MADUMANAGER STREETS ,GOUTHAM PURAM HOUSIEING BOARD STREETS, IN DN 69 UNIT 16 ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/16433,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,997000,"PROVIDING STREET FURNITURES AT KOLLAM TOTTAM STREETS, MHS ROADS ,JAMUNABAI NAGAR STREETS ,ELANGOVAN STREETS IN DN 69 UNIT 16 ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/17307,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,997000,"IMPROVEMENTS TO CHS BLOCK -4 BUNDER GARDEN IN DN-69, UNIT-16, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/18094,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,975000,"IMPROVEMENTS TO CHS BLOCK 1 AT BUNDER GARDEN IN DIVISION-69, UNIT-16, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/18323,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,990000,"LAYING CEMENT CONCRETE ROAD AT VENKATESHWARA 2 ND STREET IN DN 69, UNIT16, ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/18325,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,990000,"LAYING CEMENT CONCRETE ROAD AT VENKATESHWARA 1 ST STREET IN DN 69, UNIT16, ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/18566,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,990000,LAYING CEMENT CONCRETE ROAD AT VENKATESHWARA 3 RD STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/18567,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,990000,"LAYING CEMENT CONCRETE ROAD AT RAJAVEL LANE, AMBEDKAR LANE ,AND MYLAPPA LANE IN DN 69 , UNIT 16 ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/18568,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,990000,"laying concrate road around ragavan park in Dn.69,U 16, Z 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/18730,Electrical,Completed,NF-THIRU-VI-KA NAGAR,69,314600,Additional electrification of newly constructed room at second floor in zonal office building div 69 and provision of additional lighting at road side park in Barracca road in div 74 and provision of junction lights at Kolathur East railway gate road and Jambu lingam main road in div 65 and provision of headvy duty exhaust fan at gassifier burrial ground in pallavan salai in div 68 zone VI,Own Sources,6,2014-15,2017-18 NF/2014-15/18833,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,999000,"IMPROVEMENTS TO PLAY GROUND AND CLASS ROOM FLOORING WORK IN CMS AT MADURAI STREET IN DIV-69,UN-16,Z-06",Own Sources,6,2014-15,2016-17 NF/2014-15/18836,Playfields,Completed,NF-THIRU-VI-KA NAGAR,69,998000,"ADDITIONAL IMPROVEMENT TO GYM BUILDING AT MADURAI STREET IN DIV-69,UN-16,Z-06",Own Sources,6,2014-15,2016-17 NF/2014-15/19538,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,930000,"LAYING OF BT ROAD AT BUNDER GARDEN 2 ND STREET IN DIV 69,U16 ,ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/19541,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,977000,LAYING OF BT ROAD AT CARPENTERR STREET & MASILAMANI LANE IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19546,Grade Separator,Completed,NF-THIRU-VI-KA NAGAR,69,960000,LAYING OF BT ROAD AT BANGARU STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19547,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING OF BT ROAD AT BANDER GARDEN MAIN STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19548,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING OF BT ROAD AT JAWAHAR ROAD IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19550,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,810000,LAYING OF BT ROAD AT RAMANA NAGAR ASHOKAR STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19552,Footpath,Completed,NF-THIRU-VI-KA NAGAR,69,820000,LAYING OF BT ROAD AT RAMANA NAGAR ELANGO STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19554,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,930000,LAYING OF BT ROAD AT GNANAMBAL GARDEN 1 ST STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19569,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,790000,LAYING OF BT ROAD AT PRAKASH STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19570,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,960000,LAYING OF CC ROAD AT JANAKI NAGAR 5 TH LANE IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19697,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,790000,LAYING CEMENT CONCRETE ROAD AT SANTHI NAGAR 2 ND STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19698,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING CEMENT CONCRETE ROAD AT SANTHI NAGAR 1 ST AND 2 ND LANE IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19699,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,980000,LAYING CEMENT CONCRETE ROAD AT SRINIVASALU LANE IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/19706,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING CEMENT CONCRETE ROAD AT SRINIVASALU STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20082,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,999000,ROAD WIDENING AT RAGAVAN STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20418,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,690000,LAYING BT ROAD AT M H ROAD 2 ND LANE IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20419,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,980000,LAYING BT ROAD AT SSV KOIL 1 ST STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20423,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,990000,LAYING BT ROAD AT SRINIVASA RAGAVA STREET IN DN 69 UNIT16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20435,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING BT ROAD AT PILKINGTON ROAD IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20536,ROB,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING BT ROAD AT MYLAPPA STREET IN DN 69 UNIT16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20538,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,990000,LAYING BT ROAD AT VENUGOPALSAMY KOIL STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/20963,Grade Separator,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING BT ROAD AT JAMUNA BAI STREET IN DN 69 UNIT 16 ZINE6,Own Sources,6,2014-15,2016-17 NF/2014-15/20988,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,999000,"LAYING INTERLOCK BLOCK AT CHINNA KULANDHAI 1ST TO 4 TH LANE,KOLLAM TOTTAM, LAXMI AMMAN LANE ,RAJAVEL STREET, VAJRAVEL, PUZHAL MUNUSAMY STREET ,SSV KOIL 2 ND STREET , MADURAI STREET LANE, VASANTHA GARDEN 1 ST STREET, IN DN 69 UNIT 16 ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/21085,Footpath,Completed,NF-THIRU-VI-KA NAGAR,69,999000,"LAYING INTERLOCK BLOCK AT VASANTHA GARDEN 2RD ,3 RD AND 4 TH STREET , PONNUVELPURAM 1 ST TO 5 TH STREET , THIKKAKULAM 1 ST AND 2 ND STREET , ST MARYS LANE ,ST MARYS ROAD IN 69 UNIT 16 ZONE 6",Own Sources,6,2014-15,2016-17 NF/2014-15/21112,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,990000,IMPROVEMENT TO FOOT PATH AT MH ROAD (FROM PALLVAN SALAI JUNCTION TO SIMPSON GATE JUNCTION) IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2018-19 NF/2014-15/22235,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,999000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT MH ROAD ( SIMPSON STOP ) IN DN-69 , UNIT-16, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/22241,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,999000,PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT MH ROAD ( LAKSHMI AMMAN KOIL STOP ) IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/22278,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,570000,REPAIRS AND IMPROVEMENTS TO OLD DN 53 OFFICE FOR ADE IN THE PREMISES OF ZONE -6 AT ANDERSON ROAD IN DN -69 UNIT -16 ZONE-6,Own Sources,6,2014-15,2016-17 NF/2014-15/22512,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,999000,SPECIAL IMPROVEMENTS TO APPROACH TO THE AYANAVARAM BUS DEPO FROM ANDERSON ROAD IN DN 69 UNIT16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/24156,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,3239000,RELAYING BT ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT SIRUVALLUR ROAD IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/27550,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,999000,PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT PAPER MILLS ROAD ( NEAR EB OFFICE STOP ) IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/27665,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,520000,LAYING CC ROAD AT JAMUNABAI NAGAR 2 ND STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29024,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,990000,LAYING CEMENT CONCRETE ROAD AT VENKATESHWARA MAIN STREET (FROM MH ROAD JUNCTION TO VENKATEHWARA 1 ST STREET JUNCTION ) IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/29038,Footpath,Completed,NF-THIRU-VI-KA NAGAR,69,999000,LAYING CEMENT CONCRETE ROAD AT M E S ROAD (FROM JAMUNABAI NAGAR JUNCTION TO MH ROAD JUNCTION ) IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/30065,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,990000,PROVIDING NEW SPEED BREAKER AT VARIOUS STREETS IN DIV-69 UNIT-16 ZONE-6,Own Sources,6,2014-15,2016-17 NF/2014-15/5380,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,245000,"PROVIDING ENTRANCE FOOTPATH AND OTHER IMPROVEMENTS TO THE CORPORATION HIGHER SECONDARY SCHOOL AT BUNDER GARDEN MAIN ROAD IN DIV-69,UNIT-16 , ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/6509,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,2400000,PROPOSED OF AMMA UNAVAGAM PHASE II AT ANDERSION ROAD IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/9417,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at Chinna Chembarambakkam (Ayanavaram) in Dn-69, Unit -16 , Zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/9419,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,430000,"Providing of Rental modular Toilet on contract basis and maintenance for one Year at Chinna Chembarambakkam Ayanavaram in Dn-69, Unit -16 , Zone-6.",Own Sources,6,2014-15,2016-17 BR/2014-15/17595,Roads,Completed,BR-Bus Route Roads,70,28890000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Dr.Ambedkar College Road From Pulianthope High Road from the jn of Ganesapuram Subway in Dn.70 & 73, Zone-VI",Grants,6,2014-15,2016-17 NF/2014-15/12173,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,943000,IMPROVEMENTS TO THE EB SUB STATION AT PADDY FIELD ROAD IN DN 70 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/14211,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,906000,": Annual Maintenance of Park at Murasolimaran Park in Dn.70,Unit-16,Zone-6(By QualifiedHorticulturist For one year)",Own Sources,6,2014-15,2016-17 NF/2014-15/14281,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,317000,Maintenance of Vadivel(M)2nd cross street park and Kannabiran kovil street Park at Perambur in division 70 unit 16 zone 6 (By QualifiedHorticulturist For one year) .,Own Sources,6,2014-15,2016-17 NF/2014-15/16324,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,143000,PROVIDING MANHOLE COVERS AT VARIOUS STREETS IN DN 70 U 16 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/16436,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,774000,RELAYING BY PAVER FINISER WITH AT SRINIVASA (M) ST IN DN-70 UNIT-16 ZONE-6,Own Sources,6,2014-15,2016-17 NF/2014-15/16592,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,526000,LAYING CEMENT CONCRETE ROAD AT PALANI STREET FROM PATEL ROAD TO VASAN STREET IN DN 70 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/16598,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,694000,LAYING CEMENT CONCRETE ROAD AT PATEL ROAD 2ND CROSS STREET FROM PATEL ROAD TO VASAN STREET IN DN 70 UNIT 16 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/16619,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,619000,"Repairs to the Gandhi park at M.H. Road, Parambur. Division -70 Unit-16 Zone-VI",Own Sources,6,2014-15,2016-17 NF/2014-15/16621,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,70000,"Repairs to the Rajiv Gandhi Park, jamalia, perambur in Division -70, Unit-16, Zone-VI",Own Sources,6,2014-15,2016-17 NF/2014-15/17673,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,969000,"RELAYING BY PAVER FINISER WITH DBM50MM AND BC30MM AT P.H ROAD 2ND STREET IN DN:70,UNIT-16,ZONE-6.",Own Sources,6,2014-15,2017-18 NF/2014-15/18473,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,990000,"Supplying and fixing Street furniture at various street in Dn-70 Unit-16, Zone-06.",Own Sources,6,2014-15,2016-17 NF/2014-15/18486,Footpath,Completed,NF-THIRU-VI-KA NAGAR,70,998000,"IMPROVEMENTS TO FOOT PATH AT PERAMBUR HIGH ROAD FROM PERAMBUR PAPERMILLS ROAD IN DIV- 70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19653,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,930000,"STRENGTHENING AND RELAYING OF BITUMEN CONCRETE WITH PAVER FINISHER AT MADURAI STREET FROM VADIVEL STREET TO VADIVEL 1st CROSS STREET IN DN-70,UNIT-16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/19661,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,994000,"STRENGTHENING AND RELAYING OF BITUMEN CONCRETE WITH PAVER FINISHER AT VENKATRAMAN CANAL ROAD FROM P.H.ROAD TO VASAN STREET IN DIV-70 UNIT-16, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20406,Electrical,Completed,NF-THIRU-VI-KA NAGAR,70,135000,"Provision of additional electrification work and electrical fittings at corporation girls higher secondary school science lab building at Madhavaram high road school road Perambur in Dn-70, Unit-16, zone VI",Own Sources,6,2014-15,2016-17 NF/2014-15/20622,Footpath,Completed,NF-THIRU-VI-KA NAGAR,70,300000,"Improvement work towards Group bin at various locations in Dn -70, Unit 16, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21003,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,659000,"LAYING CEMENT CONCRETE ROAD WITH RMC M20 CONCRETE AT THIRUVENGADAM 2ND CROSS STREET IN DN-70,UNIT-16,ZONE-6.",Own Sources,6,2014-15,2017-18 NF/2014-15/21007,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,601000,"LAYIG CEMENT CONCRETE ROAD WITH RMC M20 CONCRETE AT THIRUVENGADAM 3 RD CROSS STREET IN DN-70,UNINT-16,ZONE-6.",Own Sources,6,2014-15,2017-18 NF/2014-15/21025,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,432000,"LAYING CEMENT CONCRETE ROAD WITH RMC M20 CONCRETE AT THIRUVENGADAM 4 TH CROSS STREET IN DN-70,UNIT-16,ZONE-6.",Own Sources,6,2014-15,2017-18 NF/2014-15/21028,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,705000,"LAYING CEMENT CONCRETE ROAD WITH RMC M20 CONCRETE AT PATEL ROAD LANE IN DN-70,UNIT-16,ZONE-6.",Own Sources,6,2014-15,2017-18 NF/2014-15/21032,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,359000,"LAYING CEMENT CONCRETE ROAD WITH RMC M20 CONCRETE AT NELVAYAL SALAI 2ND CROSS STREET IN DN-70,UNIT-16,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21033,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,438000,"LAYING CEMENT CONCRETE ROAD WITH RMC M20 CONCRETE AT NELVAYAL SALAI 3RD & 4TH CROSS STREET IN DN-70,UNIT-16,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21035,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,993000,"LAYING CEMENT CONCRETE ROAD WITH RMC M20 CONCRETE AT NELVAYAL SALAI 1ST LANE IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2017-18 NF/2014-15/21317,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1814099,"RELAYING OF BT ROAD WITH PAVER FINISHER OF PERAMBUR HIGH ROAD NORTH LANE IN DIV-70, UNIT-16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21320,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2664308,"RELAYING OF BT ROAD WITH PAVER FINISHER OF CHINNAIAH NEW COLONY 2ND MAIN ROAD IN DIV-70, UNIT-16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21321,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,3590225,"RELAYING OF BT ROAD WITH PAVER FINISHER OF BHARATHY ROAD 2ND STREET IN DIV-70, UNIT-16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21323,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2620152,"RELAYING OF BT ROAD WITH PAVER FINISHER OF BHARATHY ROAD 1ST STREET IN DIV-70, UNIT-16, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21327,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2475188,"RELAYING OF B.T ROAD WITH PAVER FINISHER OF PADDY FIELD ROAD LANE IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21338,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,4057929,"RELAYING OF B.T ROAD WITH PAVER FINISHER OF JAMALIYA NAGAR MAIN ROAD IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21341,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2550000,"RELAYING B.T ROAD WITH PAVER FINISHER OF STATE BANK COLONY 1ST STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21342,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,3550000,"RELAYING B.T ROAD WITH PAVER FINISHER OF EDEN GARDEN STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21343,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1299042,"RELAYING B.T ROAD WITH PAVER FINISHER OF HYDER GARDEN MAIN ROAD IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21345,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2661945,"RELAYING B.T ROAD WITH PAVER FINISHER OF SRINIVASA ACHARI STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21347,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,693482,"RELAYING OF B.T ROAD WITH PAVER FINISHER OF RAMACHANDRAN STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21349,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,842000,"RELAYING OF CEMENT CONCRETE ROAD BY RMC 30 AT GOVINDHAPURAM SLUM IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21350,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1066000,"RELAYING OF CEMENT CONCRETE ROAD BY RMC 30 AT VEERA RAGHAVAN STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21351,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,829000,"RELAYING OF CEMENT CONCRETE ROAD BY RMC 30 AT UPPANDI BABU LANE IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21352,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,933000,"RELAYING OF CEMENT CONCRETE ROAD BY RMC 30 AT VARADHAN STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21353,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1421000,"RELAYING OF CEMENT CONCRETE ROAD BY RMC 30 AT DASARI STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21354,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,939000,"RELAYING OF CEMENT CONCRETE ROAD BY RMC 30 AT BANGARU STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21355,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1006000,"RELAYING OF CEMENT CONCRETE ROAD BY RMC 30 AT RANGAPPAN STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21955,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,559000,"IMPROVEMENTS TO NNMP SHED NO : 33603070332 AT SCHOOL ROAD IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2014-15,2016-17 NF/2014-15/21958,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,812000,"PROVIDING ROOFING SHEET ARRANGEMENTS AND OTHER IMPROVEMENTS TO CMS(TELUGU) AT MADHAVARAM HIGH ROAD IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2014-15,2016-17 NF/2014-15/21960,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,998000,"IMPROVEMENTS TO THE SCIENCE LAB AT CGHSS -2 AT MADHAVARAM HIGH ROAD(SCHOOL ROAD) IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2014-15,2016-17 NF/2014-15/22039,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,819000,"REPAIRS AND IMPROVEMENTS TO TOILET BLOCK AND AUDITORIUM BUILDING AND CGHSS BUILDING (SOUTH SIDE) AT M.H.ROAD 9SCHOOL ROAD ) IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2014-15,2017-18 NF/2014-15/22041,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,985000,"PROVIDING SAHABAD STONE FLOORING WORK IN SECOND FLOOR IN CGHSS BUILDING (NORTH SIDE) AT M.H.ROAD(SCHOOL ROAD) IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2014-15,2016-17 NF/2014-15/23270,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,583000,"RELAYING BT ROAD WITH PAVER FINISHER AT GOVINDHASAMY LANE IN DN-70, UNIT-16, ZONE-6",Own Sources,6,2014-15,2017-18 NF/2014-15/23554,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,377000,"Improvements to the public convenence near perambur Bus stand in Division-70, Unit-16, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23557,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,900000,"Improvements to work CI,SI,Tax collector office in division-70 Unit-16, Zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/26627,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,110000,"Arrangement work for e - seva center at Bharathy Road in DN-70, Unit-16, Zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/9426,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,984000,"LAYING CEMENT CONCRETE WITH M GRADE RMC M40 AT EDEN GARDEN CROSS STREETS IN DN 70 ,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 S/2014-15/12532,Footpath,Completed,BR-Bus Route Roads,70,27100000,"FORMING FOOT PATH AT PERAMBUR HIGH ROAD FROM THE JN OF COOKS ROAD TO CHANDRAYAGO SAMBDHI STREET IN DN 70, ZONE VI",Grants,6,2014-15,2017-18 BR/2014-15/29964,Roads,Completed,BR-Bus Route Roads,71,24246000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Perambur High Road (South) From Jn of Cooks Road to Perambur High Road Bridge toe in Dn.70 & 71, Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29965,Roads,Completed,BR-Bus Route Roads,71,16902000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Perambur High Road (North) from the jn of Paper Mills Road to B.B.Road Jn. in Dn.70 & 71, Zone-VI",Grants,6,2014-15,2016-17 NF/2014-15/11340,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1700000,LAYING CEMENT CONCRETE WITH RMC M30 GRADE CONCRETE AT EGANKIPURAM 1ST STREET IN DN 71 UN 16 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/11343,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,845000,LAYING CEMENT CONCRETE WITH RMC M30 GRADE CONCRET AT EGANKIPURAM 2ND STREET IN DN 71 UN 16 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/11487,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2130000,LAYING OF CEMENT CONCRETE WITH RMC M30 GRADE CONCRETE AT EGANKIPURAM 4TH STREET IN DN-71 UN-16 Z-6,Own Sources,6,2014-15,2016-17 NF/2014-15/11513,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,956000,LAYING CEMENT CONCRETE WITH RMC M30 GRADE CONCRETE AT EGANKIPURAM 3RD STREET IN DN-71 UNIT-16 Z-6,Own Sources,6,2014-15,2016-17 NF/2014-15/12139,Electrical,Completed,NF-THIRU-VI-KA NAGAR,71,826400,Provision of 1 no of 20mtrs High-mast lamp post with 12nos of 2x400w MH Fitting at Chandrayoghi samathi Road Lorry Station in division 71 of ZVI.,Own Sources,6,2014-15,2017-18 NF/2014-15/16295,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,757000,MAINTENANCE OF MURASOLI MARAN PARK IN DN 71 U 16 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/17115,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,543000,"PROVIDING SANITARY AND ELECTRICAL ARRENGEMENTS TO THE NNMP SHED AT NEW VAZHAMA NAGAR IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/18326,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,93000,REPAIR AND IMPROVEMENT WORKS TO THE EXISTING BUS SHELTER AT PERAMBUR HIGH ROAD JAMALIA (NORTH SIDE) IN DN 71 UNIT-16 Z-6,Own Sources,6,2014-15,2016-17 NF/2014-15/18329,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,188000,"REPAIR AND IMPROVEMENT WORKS TO THE EXISTING BUS SHELTER AT KH ROAD IN DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20572,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1620000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT ADISESHA NAGAR MAIN ROAD DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20582,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1070000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT ADISESHA NAGAR 5th STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20583,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1100000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT ADISESHA NAGAR 6th STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20584,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,640000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT BRISLY NAGAR 1st STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20585,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,700000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT BRISLY NAGAR 2nd STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20586,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,750000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT BRISLY NAGAR 3rd STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20587,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,780000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT BRISLY NAGAR 4th STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/20588,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,820000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT BRISLY NAGAR 5th STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/22016,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,926000,PROVIDING ROAD SIDE PARK AT BRISLY NAGAR MAIN STREET IN DN 71 UN 16 Z 6,Own Sources,6,2014-15,2017-18 NF/2014-15/27710,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1992000,"RELAY ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT CHANDRAYOGI SAMATHI SAMIAR MADAM STREET IN DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/27712,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1960000,"RELAY ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT HYDER GARDEN 4TH STREET IN DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/27905,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,3040000,LAYING CEMENT CONCRETE WITH RMC M30 GRADE CONCRETE AT BASHYAM 3RD STREET IN DN 71 UN 16 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/27908,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,890000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT BRISLY NAGAR MAIN STREET DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/27909,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,369000,"LAYING OF CEMENT CONCRETE WITH RMC M30 AT BRISLY NAGAR LANE DN-71,U-16,Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/9820,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,731000,IMPROVEMENTS TO N N M P SHED AT EGANKIPURAM 1ST STREET IN DN 71 UN 16 Z 6,Own Sources,6,2014-15,2016-17 L/2014-15/27859,Electrical,Completed,L-Electrical,72,3493800,Provision of 118nos of 6mtr Octagonal lamp post with single straight bracket with laying of 2x16sqmm cable at Kannigapuram area (Phase 2) in div 72 zone VI,Own Sources,6,2014-15,2016-17 NF/2014-15/12905,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,396062,"REPAIRS AND IMPROVEMENTS TO GROUP BINS AND PROVIDING ADDITIONAL TEMPORARY SHED IN SLAUGHTER HOUSE DN-72,UNIT-17,ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/16895,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,999000,"CONSTRUCTION OF PUBLIC CONVIENIENCE (GENTS TOILET) AT KASTURI BAI COLONY,KANNIGAPURAM IN DN-72,UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/18616,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,996000,"ADDITIONAL IMPROVEMENTS TO SLAUGHTER HOUSE IN DIV-72,UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20960,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,999000,"CONSTRUCTION OF COMPOUND WALL AT SLAUGHTER HOUSE IN DIV-72,UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21057,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1196259,"Relaying of cement concrete road with RMC M30 in Doss nagar first street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21063,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1196259,"Relaying of cement concrete road with RMC M30 in Doss nagar second street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21065,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1196259,"Relaying of cement concrete road with RMC M30 in Doss nagar third street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21073,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1196259,"Relaying of cement concrete road with RMC M30 in Doss nagar fourth street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21081,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1196259,"Relaying of cement concrete road with RMC M30 in Doss nagar fifth street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21086,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1196315,"Relaying of cement concrete road with RMC M30 in Doss nagar sixth street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21088,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1196259,"Relaying of cement concrete road with RMC M30 in Doss nagar seventh street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21090,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,882713,"Relaying of cement concrete road with RMC M30 in Doss nagar eighth street at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21107,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,2231966,"Relaying of cement concrete road with RMC M20 in Doss nagar main road at kaiinkapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21110,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,731377,"Relaying of cement concrete road with RMC M30 in Doss nagar first cross street at kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21178,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,630000,"Laying of cement concrete road M15 in shatri nagar first and second street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21181,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,630000,"Laying of cement concrete road M15 in shatri nagar third and fourth street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21182,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,630000,"Laying of cement concrete road M15 in shatri nagar fifth and sixth street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21186,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,630000,"Laying of cement concrete road M15 in shatri nagar seventh and eigth street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21188,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,630000,"Laying of cement concrete road M15 in shatri nagar nineth and tenth street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21192,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,618000,"Laying of cement concrete road M15 in shatri nagar 11th and 12th street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21194,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,618000,"Laying of cement concrete road M15 in shatri nagar 13th and 14th street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21197,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,567000,"Laying of cement concrete road M15 in shatri nagar 15th and 16th street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21201,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,567000,"Laying of cement concrete road M15 in shatri nagar 17th and 18th street in pulianthope dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/22350,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,992000,"ADDITIONAL IMPROVEMENTS TO THE COMPOUND WALL AT OLD SLAUGHTER HOUSE IN DIV-72,UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/23077,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,999000,"ADDITIONAL IMPROVEMENTS TO SLAUGHTER HOUSE IN DIV-72,UNIT17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/23079,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1114000,"Relaying of road with camber correction BCCMP40mm thick using paver finisher veera street in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23091,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,869000,"Relaying of road with camber correction BCCMP40mm thick using paver finisher POWDER MILLS ROAD in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23092,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,934788,"Relaying of cement concrete RMC M30 at old venkatesapuram 1 st street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23096,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,934788,"Relaying of cement concrete RMC M30 at old venkatesapuram 2nd street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23100,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,934788,"Relaying of cement concrete RMC M30 at old venkatesapuram 3rd street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23103,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,934788,"Relaying of cement concrete RMC M30 at old venkatesapuram 4th street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23107,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,934788,"Relaying of cement concrete RMC M30 at old venkatesapuram 5th street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23111,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,934788,"Relaying of cement concrete RMC M30 at old venkatesapuram 6th street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23130,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,934788,"Relaying of cement concrete RMC M30 at old venkatesapuram 7th street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23133,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,1103775,"Relaying of cement concrete RMC M30 at old venkatesapuram 1 st cross street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23137,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1847286,"Relaying of cement concrete RMC M30 at old venkatesapuram 2nd cross street in kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23157,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1627882,"Relaying of cement concrete RMC M30 at new venkatesapuram 4th street at kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/23159,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1627882,"Relaying of cement concrete RMC M30 at new venkatesapuram 5th street at kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23234,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1627882,"Relaying of cement concrete RMC M30 at new venkatesapuram 1st cross street at kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/23236,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1235420,"Relaying of cement concrete RMC M30 at new venkatesapuram 2nd cross street at kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/23240,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1366844,"Relaying of cement concrete RMC M30 at new venkatesapuram 3rd cross street at kannikapuram in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/23264,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,639891,"Relaying of cement concrete road with RMC M30 at V.O.C nagar 7th street at pulianthope in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/23265,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,639891,"Relaying of cement concrete road with RMC M30 at V.O.C nagar 8th street at pulianthope in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 NF/2014-15/30058,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,520000,"Constructing new auditorium at chennai middle school in harness saddle factory road in dn-72,unit-17,zone-6",Own Sources,6,2014-15,2016-17 RC/2014-15/22087,Playfields,Completed,P-Parks and Playfields,72,25000000,"IMPROVEMENTS TO THE KANNIGAPURAM PLAYGROUND AT BRIGHTON ROAD ,DN-72,UNIT-17,ZONE-VI.",Own Sources,6,2014-15,2019-20 NF/2014-15/13373,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,998000,"Construction of Modern bio-methanation plant at New Ferrance Road in Dn-73, Unit-17, Zone-06.",Own Sources,6,2014-15,2016-17 NF/2014-15/16573,Parks,Completed,NF-THIRU-VI-KA NAGAR,73,139000,"Maintenance of Vadia park at New Ferrance road, Dn 73, Unit 17, Zone 6",Own Sources,6,2014-15,2016-17 NF/2014-15/17667,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,993000,"Repairing and improvements to ICDS and (Center no. 05 & 08) along with Kitchen Shed at Thiruvendam st. Dn-73, Unit-17 ,Zone-VI.",Own Sources,6,2014-15,2016-17 NF/2014-15/17670,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,996000,"Repairs and Improvements to CHS Building, Auditorium and Cycle Stand at Thiruvengadam st. Dn-73, Unit-17 ,Zone-VI.",Own Sources,6,2014-15,2016-17 NF/2014-15/19482,Bridges,Completed,NF-THIRU-VI-KA NAGAR,73,865000,Construction of toilet block and improvements to the existing CWC @ Thiruvengadam street. Dn 73. Unit 17. Zone 6.,Own Sources,6,2014-15,2016-17 NF/2014-15/19486,Bridges,Completed,NF-THIRU-VI-KA NAGAR,73,832000,Providing parking shed and screen partition arrangement for CWC at Thiruvengadam street.Dn 73. Unit 17. Zone 6.,Own Sources,6,2014-15,2016-17 NF/2014-15/23446,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,247000,"REPAIRS TO IMPROVEMENTS AND PUBLIC CONVINIYANCE AT RAMASAMY STREET IN DN-73, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/23450,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,221000,"REPAIRS TO FOOTPATH AT COOKS ROAD IN DN-73, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/23458,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,186000,"REPAIRS TO FOOT PATH AT DR. AMBEDKAR COLLAGE ROAD IN DN-73, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26243,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1540203,Laying of cement concrete road at Thiruvenkadam street in Jn. of pulianthope high road to decasster road,Own Sources,6,2014-15,2016-17 NF/2014-15/26244,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,625900,"laying of cement concrete road at ponnappan street & lane in Dn.73, unit-17, zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26249,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1052132,"Laying of cement concrete road at Alexander street in Dn.73, unit-17, zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26250,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,854836,"Relaying of road at Darga street from Jn.of Strahans road to New ferrance road in Dn.73, unit-17, zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26252,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,270680,"Laying of cement concrete road at strahans 1st street in Dn.73, unit-17, zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26255,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1009295,"Laying of cement concrete road at Pensioners main lane in Dn.73, unit-17, zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26257,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,166090,"Laying of cement concrete road at New ferrance lanes (1 to 4 lanes, north side) in Dn.73, unit-17, zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26360,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,2345677,"Strengthening & Relaying of road at Mannarswamy street from Jn.of pulianthope high road to Decaster road inDn.73, unit-17, zone-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28472,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1424440,"Laying of cement concrete road at pensioners 1 to 4 lane in Dn.73, unit-17,zone-6.",Own Sources,6,2014-15,2016-17 RC/2014-15/13525,Buildings,Completed,B-Buildings,73,92000000,"CONSTRUCTION OF ZONAL OFFICE-VI BUILDING AT STRAHANS ROAD IN DN 73,ZONE-6.",Own Sources,6,2014-15,2019-20 NF/2014-15/14306,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,195000,Annual maintenance to park at secretariat colony 2nd street in dn 74 unit 17 zone 6.(two years),Own Sources,6,2014-15,2016-17 NF/2014-15/15858,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,960000,"RELAYING BITUMINOUS ROAD 40MM THICK WITH CAMBER CORRECTION WITH PAVER FINISHER AT SANTHIYAPAN 1 ST STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/15860,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,962000,"RELAYING BITUMINOUS ROAD 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT SANTHIYAPPAN 2ND STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/15912,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,2680000,"RELAYING BITUMEN CONCRETE 30MM WITH CAMBER CORRECTION BY PAVER FINISHER AT CHINNA BABU STREET IN DN-74, UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/16304,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,397000,"PROVIDING ROAD SIDE PARK AT BARAKKA ROAD IN JUN OF SEC.COLONY 3RD STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/16473,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,937000,"ADDITIONAL IMPROVEMENTS TO HERBAL PARK IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/17260,Footpath,Completed,NF-THIRU-VI-KA NAGAR,74,997000,"REPAIRS TO FOOT PATH AT BARRAKKA ROAD IN DIVISION-74,UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/19105,Electrical,Completed,NF-THIRU-VI-KA NAGAR,74,444000,"PROVIDING WATER SUPPLY ARENGEMENTS AND IMPROVEMENTS TO NNMP SHED AT S.V.M NAGAR IN DN-74, UNIT-17, Z-6",Own Sources,6,2014-15,2018-19 NF/2014-15/19145,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,609000,"PROVIDING ROAD SIDE PARK AT BARRAKKA ROAD JUN.OF DIVISION OFFICE OPPOSITE IN DN-74, UNIT-17, ZONE-6",Own Sources,6,2014-15,2017-18 NF/2014-15/20911,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,997000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT SUBARAYAN 5TH STREET IN DN-74, UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20956,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1187000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT SUBRAYAN 2ND STREET IN DN-74, UNIT-17,ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20997,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,820000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT SUBARAYAN 3RD STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21002,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,893000,"RELAYING BITUMINOUS ROAD30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT SUBARAYAN 4TH STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21006,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,996000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT NEW SECRETARIAT COLONY STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21157,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,295000,"RELAYING BITUMINOUS ROAD 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT NEW SECRETARIAT COLONY 1ST LANE IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21163,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,294000,"RELAYING BITUMINOUS ROAD 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT NEW SECRETARIAT COLONY 2ND LANE IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21165,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,950000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT VARADHAMMAL GARDEN ROAD IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21166,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,390000,"RELAYING BITUMINOUS ROAD 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT VARADHAMMAL GARDEN 1ST STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21168,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,989000,"RELAYING BITUMINOUS ROAD30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT VARADHAMMAL GARDEN 3RD STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21174,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,810000,"RELAYING BITUMINOUS ROAD 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT VARADHAMMAL GARDEN 2ND STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21301,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,702319,"LAYING OF CEMENT CONCRETE ROAD M15 IN SUBARAYAN 4TH STREET 1ST LANE IN DN 74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21357,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,702319,"LAYING OF CEMENT CONCRETE ROAD M15 IN SUBARAYAN 4TH STREET 2ND LANE IN DN-74,UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21370,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,445917,"LAYING OF CEMENT CONCRETE ROAD M15 IN SUBARAYAN 4TH STREET 3RD LANE IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21375,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,656000,"LAYING OF CEMENT CONCRETE ROAD M15 IN KASAVAN STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2018-19 NF/2014-15/21378,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,383756,"LAYING OF CEMENT CONCRETE ROAD M15 IN OTHAVADAI STREET LANE IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21381,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,533188,"LAYING OF CEMENT CONCRETE ROAD M15 IN THANDUMARIYAMMAN KOIL STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21385,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,728000,"LAYING OF CEMENT CONCRETE ROAD M15 AT PANDURANGAN KOIL STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21885,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,549000,"PROVIDING GATE PILLAR AND COMPOUND WALL RAISING IN CHS CHINNABABU STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21902,Footpath,Completed,NF-THIRU-VI-KA NAGAR,74,970000,"REPAIRS AND IMPROVEMENTS TO FOOTPATH AT A.K.SAMY NAGAR I TO 7 STREETS IN DIVISION-74,UNIT-17,ZONE-06.",Own Sources,6,2014-15,2016-17 B/2014-15/18913,Buildings,Completed,B-Buildings,75,16317000,"PROPOSED CONSTRUCTION OF 3 CLASSROOMS WITH 1 LAB IN EACH FLOOR ( G.F + F.F + S.F) IN CMS AT VENKATTAMMAL SAMATHI STREET IN D-75, ZONE - 6",Own Sources,6,2014-15,2017-18 NF/2014-15/15109,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,690000,"RELAYING CEMENT CONCRETE ROAD RMC40 GREDE AT S.S.PURAM A BLOCK I4TH & 15TH STREET IN DN75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/15116,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,810000,"RELAYING CEMENT CONCRETE ROAD RMC40 GRADE AT S.S.PURAM A BLOCK 12TH & 13TH STREET IN DN 75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/15269,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,988000,"RELAYING CEMENT CONCRETE ROAD RMC40 GRADE AT S.S.PURAM A BLOCK 10TH & 11TH STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2018-19 NF/2014-15/16946,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,998000,"LAYING CEMENT CONCRETE ROAD RMC40 GRADE CONCRETE ROAD AT S.S.PURAM A BLOCK 3RD STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/16947,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,997000,"LAYING CEMENT CONCRETE ROAD RMC40 GRADE CONCRETE AT S.S.PURAM A BLOCK 2ND STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2018-19 NF/2014-15/16969,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,475000,"LAYING CEMENT CONCRETE ROAD RMC40 GRADE CONCRETE AT S.S.PURAM B BLOCK 2ND STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/18751,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,979000,"STRENGTHENING AND RELAYING SDBC40MM THICK MINI HOT MIX PLANT FOR S.S. PURAM BRICK LIN ROAD NEAR POLICE BOOTH TO OTTERI DUMPING GROUND IN DN-75,UNIT-17,ZONE-6",Own Sources,6,2014-15,2017-18 NF/2014-15/19080,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,274000,"ANNUAL MAINTENANCE TO PATEL PARK AT CHELLAPPA STREET IN DIVISION-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/19100,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,997000,"RELAYING BITUMINOUS ROAD 40MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT NARAYANA MESTHERI STREET IN DIVISION-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21408,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,2933503,"LAYING CEMENT CONCRETE ROAD M30 AT VENGATTAMMAL SAMATHI STREET IN DN-75 UNIT-17, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/21417,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,2825000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT PADAVATTAMMAN KOIL STREET IN DN-75,UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21419,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,960000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT PUDU STREET IN DN75, UNIT17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21421,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,606000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT EDWARD PARK STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21423,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,348000,"RELAYING BITUMINOUS ROAD 30MM THICK WITH CAMBER CORRECTION BY PAVER FINISHER AT PADAVATTAMMAN KOIL STREET LANE IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/21970,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,997000,RELAYING BT 40MM THICK WITH BY PAVER FINISHER AT KANNAPPA STREET IN DN-75 UNIT-17 ZONE-6,Own Sources,6,2014-15,2016-17 NF/2014-15/14741,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,425000,"ANNUAL MAINTENANCE OF PARK (OUT SOURCING FOR THE PERIOD OF 24 MONTH (TWO YEARS) BHAKAVATCHALAM PARK @ ANGALAMMAN KOIL STREET IN DIV 76, UNIT 17, ZONE6.",Own Sources,6,2014-15,2017-18 NF/2014-15/14991,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,978000,"IMPROVEMENTS TO NNMP SHED AT EDWARD PARK STREET IN DN-76, UNIT-17, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/15005,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,973000,"IMPROVEMENTS TO NNMP SHED AT C.S.NAGAR IN DN-76, UNIT-17, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/15009,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,993000,"IMPROVEMENTS TO NNMP SHED AT SATHIDHANNANDHAM STREET DN-76, UNIT-17, ZONE-6",Own Sources,6,2014-15,2016-17 NF/2014-15/16286,Electrical,Completed,NF-THIRU-VI-KA NAGAR,76,997000,"IMPROVEMENTS TO C.S.NAGAR PARK AT RAMANUJAM GARDEN IN DN-76, U-17, Z-6",Own Sources,6,2014-15,2016-17 NF/2014-15/17983,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,983000,"IMPROVEMENTS TO NNMP SHED AT PERAMBUR BARRACKS ROAD IN DN-76,U-17, Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20758,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,640000,"Maintance of park out sourcing for the period of 24 month (Two Years) 1 Kalaigner Karunanidhi Park 2 Selvapathi park in Dn 76, Unit-17, Zone-6",Own Sources,6,2014-15,2017-18 NF/2014-15/26007,Electrical,Completed,NF-THIRU-VI-KA NAGAR,76,82000,"IMPROVEMENTS TO EXISTING P.C. AND SCHOOL AT VARIOUS STREET IN DN-76, U-17, Z-6.",Own Sources,6,2014-15,2018-19 NF/2014-15/26033,Electrical,Completed,NF-THIRU-VI-KA NAGAR,76,494000,"IMPROVEMENTS TO EXISTING P.C. AT PERAMBUR BARRACKS ROAD IN DN-76, U-17, Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/26593,Electrical,Completed,NF-THIRU-VI-KA NAGAR,76,492000,"IMPROVEMENTS TO EXISTING P.C. AT RAMANUJAM STREET IN DN-76, U-17, Z-6.",Own Sources,6,2014-15,2017-18 NF/2014-15/28068,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,527249,"RELAYING THE ROAD WITH BCCMP 40MM THICK INCLUDING CAMBER CORRECTION BY PAVER FINISHER AT ETHIRAJ STREET IN DN-76,U-17, Z-6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28109,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,1267163,"RELAYING THE ROAD WITH BCCMP 40MM THICK INCLUDING CAMBER CORRECTOIN USING BY PAVER FINISHER AT RAMANUJAM GARDEN STREET IN DN-76, U-17, Z 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/29204,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,170000,"Construction of Compound Wall around the Transformer at Angalamman Koil Street IN WARD 76, UNIT 17, ZONE 6.",Own Sources,6,2014-15,2016-17 BR/2014-15/17597,Roads,Completed,BR-Bus Route Roads,77,16244000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Demollows Road From Raja Muthiah salai to the Jn of Strahans Road in Dn-77, Zone-VI",Grants,6,2014-15,2016-17 BR/2014-15/29968,Roads,Completed,BR-Bus Route Roads,77,5564000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Basin Elephant Gate Road from the JN of Demellows Road to Pulianthope High Road in Dn.77 Zone-VI,Grants,6,2014-15,2016-17 BR/2014-15/29969,Roads,Completed,BR-Bus Route Roads,77,13889000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Pulianthope High Road from the jn Dr.Ambedkar College Road to Basin Bridge Road in Dn-77,Zone-6",Grants,6,2014-15,2016-17 NF/2014-15/13926,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,667000,"DISMANTLING AND RECONSTRUCTION OF STORMWATER DRAIN FROM DR.ANSARI STREET TO HINDU UNION COMMITTE SCHOOL IN DN-77, UNIT-17, ZONE-6.",Own Sources,6,2014-15,2018-19 NF/2014-15/16147,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,889000,"Maintenance of Puliyanthope New Park(Two Years) at Basin Elephant Gate Road, Dn - 77, Unit -17, Zone - VI",Own Sources,6,2014-15,2017-18 NF/2014-15/20897,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,847763,"Laying Cement concrete road with RMC M30 Grade concrete at Aasirvaadhapuram 1st street, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20909,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,702165,"Laying M30 Grade Cement Concrete road at Aasirvaadhapuram 2nd street, Dn 77, unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20910,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,650760,"Laying RMC M30 Grade cement concrete road at Aasirvaadhapuram 3rd street, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20912,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,768797,"Laying RMC M30 Grade cement concrete road at Aasirvaadapuram 4th street, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/20913,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,679439,"Laying RMC M30 Grade Cement Concrete road at Aasirvaadapuram 5th street, Dn77, Unit 17, Zone 6",Own Sources,6,2014-15,2016-17 NF/2014-15/20915,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,666241,"Laying RMC M30 Grade Cement concrete road at Aasirvaadapuram 6th street, Dn 77, Unit 17, Zone 6",Own Sources,6,2014-15,2016-17 NF/2014-15/21400,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,696466,"Laying RMC M30 Grade Cement Concrete Road at KP Park 1st Block, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/24104,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,151000,"REPAIR AND IMPROVEMENT PUBLIC CONVENIENCE AT VARIOUS STREET IN DN 77, U 17, Z 6",Own Sources,6,2014-15,2018-19 NF/2014-15/24201,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,313000,"IMPROVEMENTS TO T.B HOSPITAL AT PULIANTHOPE HIGH ROAD IN DN - 77, UNIT - 17, ZONE - 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/24286,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,88000,"Improvements to Amma park at Basin elephant gate road in, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28499,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,589887,"Laying RMC M30 Grade Cement Concrete road in between KP Park 2nd & 3rd Block, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28502,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,883749,"Laying RMC M30 Grade cement concrete road at KP Park 4th Block, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/28507,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,828120,"Lsying RMC M30 Grade Cement Concrete Road at KP park 5th Block, Dn 77, Unit 17, Zone 6",Own Sources,6,2014-15,2016-17 NF/2014-15/28510,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1132378,"Laying RMC M30 Grade Cement Concrete Road in between 6th & 7th bllock in K.P.block, Dn 77, Unit 17, Zone 6.",Own Sources,6,2014-15,2016-17 NF/2014-15/30114,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,913659,"Relaying BC 40MM thick with Camber Correction at Market street, Dn 77, Unit 17, Zone 6",Own Sources,6,2014-15,2016-17 L/2014-15/27797,Electrical,Completed,L-Electrical,78,2007500,"Provision of 51nos of 6mtr octagnol lamp post with laying of cables at Kuravankulam, Subba naidu Street, Govindhan Street and surrounding areas div 78 zone VI",Own Sources,6,2014-15,2016-17 NF/2014-15/17012,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,850000,RELAYING THE BT ROAD BYUSING PAVER FINISHER AT AP ROAD 1ST LANE IN WARD 78 UNIT 17 ZONE 6,Own Sources,6,2014-15,2016-17 NF/2014-15/21583,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,145000,"PAINTING TO FOOTPATH AT SYDENHAMS ROAD AND PERRAMBUR BARRACKS ROAD IN DIV-78,UN-17,Z-06",Own Sources,6,2014-15,2016-17 NF/2014-15/22359,Electrical,Completed,NF-THIRU-VI-KA NAGAR,78,241000,"IMPROVEMENTS TO PUBLIC CONVENIENCE (P.C) AND PROVIDING RAMP AT SYDENHAMS ROAD IN DIV-78,UN-17,Z-06",Own Sources,6,2014-15,2016-17 NF/2014-15/24232,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,969231,RELAYING OF B.T ROAD BY USING MECHANICAL PAVER AT ERRAN STREET IN DN 78 U 17 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/27190,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,552485,RELAYING CEMENT CONCRETE ROAD AT CHOOLAI BAZAAR LANE IN DN 78 U-17 Z-6,Own Sources,6,2014-15,2016-17 NF/2014-15/27590,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,552485,RELAYING OF C.C ROAD BY USING RMC30 AT DHARMA RAJA KOVIL STREET IN DVN 78 U 17 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/27592,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1132784,RELAYING OF C.C ROAD BY USING RMC 30 AT ASTABUJAM 1ST LANE IN DN 78 U 17 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/27595,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1132784,RELAYING OF C.C ROAD BY USING RMC 30 AT SIDDALU STREET IN DVN 78 U 17 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/27596,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1132795,RELAYING OF C.C ROAD BY USING RMC 30 AT MADURAI STREET IN DVN 78 U 17 Z 6,Own Sources,6,2014-15,2016-17 NF/2014-15/30077,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,999000,PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT CHOOLAI HIGH ROAD (NEAR KUNNATHAMMAN KOVIL) IN DN -78 U- 17 Z-6(WARD COUNCILOR FUND),Own Sources,6,2014-15,2016-17 NF/2014-15/4964,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,952000,RELAYING OF B.T ROAD BY USING MECHANICAL PAVER AT PRASANNA VINAYAGAR KOIL STREET IN DN 78 U 17 Z 6,Own Sources,6,2014-15,2016-17 S/2014-15/12541,Footpath,Completed,BR-Bus Route Roads,78,12900000,FORMING FOOTPATH AT CHOOLAI HIGH ROAD FROM THE JN OF RAJA MUTHAIAH SALAI TO JN OF NARAYANA GURU SALAI IN DN78 ZONE VI,Own Sources,6,2014-15,2017-18 NG/2014-15/15552,Parks,Completed,NG-AMBATTUR,79,1400000,"IMPROVEMENT WORKS FOR RAM NAGAR PARK IN DIV-79,UNIT-18, ZONE-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/15558,Parks,Completed,NG-AMBATTUR,79,1168000,"IMPROVEMENT WORKS FOR LENIN NAGAR PARK IN DIV-79,UNIT-18, ZONE-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/15936,Parks,Completed,NG-AMBATTUR,79,1777000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT LENIN NAGAR PARK, LAKSHMI AMMAN NAGAR PARK, RAM NAGAR PARK AND GANDHI NAGAR PARK IN DN-79, UNIT- 18, ZONE-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/16042,Parks,Completed,NG-AMBATTUR,79,237000,"IMPROVEMENT WORKS FOR GANDHI NAGAR PARK IN DIV-79,UNIT-18, ZONE-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/16045,Parks,Completed,NG-AMBATTUR,79,1900000,"IMPROVEMENT WORK FOR LAKSHMI AMMAN PARK IN DIV-79,UNIT-18, ZONE-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/22160,Electrical,Completed,NG-AMBATTUR,79,2033800,"Providing Electrical Wiring And Generator forUrban primary Health centre at Kattabomman St, Gandhi Nedunchalai in Div-79 UNIT-18 ZONE-7(Ambattur)",Own Sources,7,2014-15,2016-17 NG/2014-15/22517,Buildings,Completed,NG-AMBATTUR,79,312000,"Proposed Construction of composed pit in Div-79,Unit-18, Zone-7.",Own Sources,7,2014-15,2017-18 NG/2014-15/24703,Roads,Completed,NG-AMBATTUR,79,4271570,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GOPAL STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25266,Roads,Completed,NG-AMBATTUR,79,4389181,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GOVINDHARAJU STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25276,Roads,Completed,NG-AMBATTUR,79,4128939,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT T P ELUMALAI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25288,Roads,Completed,NG-AMBATTUR,79,1840896,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT AMBETHKAR STREET & CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25294,Roads,Completed,NG-AMBATTUR,79,3543939,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MEENAMBAL SIVARAJ STREER & PERUMAL KOIL 1ST CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25299,Roads,Completed,NG-AMBATTUR,79,1357674,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ABIRAMI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25300,Roads,Completed,NG-AMBATTUR,79,1480448,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ABIRAMI 1ST CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25372,Roads,Completed,NG-AMBATTUR,79,2634775,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GANDHI AND NETHAJI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25373,Roads,Completed,NG-AMBATTUR,79,2221031,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT VEDHACHALAM STREET AND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25397,Roads,Completed,NG-AMBATTUR,79,2578822,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PASUMPONSALAI 1ST STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25398,Roads,Completed,NG-AMBATTUR,79,2578822,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PASUMPONSALAI CROSS STREET AND IYYAPAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25399,Roads,Completed,NG-AMBATTUR,79,2928765,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NEHRU STREET & CROSS, ANTHONIYAR STREET AND KAMARAJAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25442,Roads,Completed,NG-AMBATTUR,79,2389953,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GANDHI NAGAR KOIL CROSS 1ST AND 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25443,Roads,Completed,NG-AMBATTUR,79,2429725,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT AZHUMUTHU YADAVAR STREET AND DHESAPILLAI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25444,Roads,Completed,NG-AMBATTUR,79,4336050,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PERIYANDAVAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25445,Roads,Completed,NG-AMBATTUR,79,1480838,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PERIYANDAVAR 1ST AND 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25446,Roads,Completed,NG-AMBATTUR,79,1179391,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT JEEVANANDHAM CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25468,Roads,Completed,NG-AMBATTUR,79,4059760,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT A P ARASU STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25469,Roads,Completed,NG-AMBATTUR,79,2023823,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT A P ARASU 1ST AND 2ND CROSS AND RANGANATHAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25470,Roads,Completed,NG-AMBATTUR,79,2283821,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ARUNAGIRINATHAR STREET AND APPAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25471,Roads,Completed,NG-AMBATTUR,79,2023823,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MUTHUVALLI STREET AND GANAPATHI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25472,Roads,Completed,NG-AMBATTUR,79,2429725,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GOPALSAMY STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25473,Roads,Completed,NG-AMBATTUR,79,3508603,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KAVERI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25474,Roads,Completed,NG-AMBATTUR,79,4127460,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NIRMAL STREET AND LAL BAGATHOOR STREET AND KAVERI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25475,Roads,Completed,NG-AMBATTUR,79,3808898,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT V V GIRI STREET AND KUMARAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25476,Roads,Completed,NG-AMBATTUR,79,3454177,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KAMALAPURAM COLONY AND BHARATHIYAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25489,Roads,Completed,NG-AMBATTUR,79,4440089,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT E V R STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25490,Roads,Completed,NG-AMBATTUR,79,1580654,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT E V R CROSS AND REDHILLS MAIN ROAD CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25491,Roads,Completed,NG-AMBATTUR,79,4059760,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT T V K STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25492,Roads,Completed,NG-AMBATTUR,79,4059760,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT RAMKRISHNA STREET AND MAPOCI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25493,Roads,Completed,NG-AMBATTUR,79,2216439,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MASILAMANI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25500,Roads,Completed,NG-AMBATTUR,79,2033128,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT METTU STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25502,Roads,Completed,NG-AMBATTUR,79,1358394,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT METTU 1ST CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25504,Roads,Completed,NG-AMBATTUR,79,3942944,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ANNA STREET AND 1ST CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25505,Roads,Completed,NG-AMBATTUR,79,1242855,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ANNA 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25506,Roads,Completed,NG-AMBATTUR,79,1900821,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PARK STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25507,Roads,Completed,NG-AMBATTUR,79,1631709,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KANNAKI CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25522,Roads,Completed,NG-AMBATTUR,79,1886350,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KALAIVANAR 1ST AND 3RD CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25523,Roads,Completed,NG-AMBATTUR,79,1563686,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KALAIVANAR 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25524,Roads,Completed,NG-AMBATTUR,79,2431775,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KALAIGAR KARUNANITHI STREET, INDRAGANDHI CROSS AND BHAVANI AMMAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25525,Roads,Completed,NG-AMBATTUR,79,1755236,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MARIYAMMAN KOIL STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25526,Roads,Completed,NG-AMBATTUR,79,1883095,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT INDRA GANDHI STREET (AKA NAGAR) IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25793,Roads,Completed,NG-AMBATTUR,79,4334136,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NAGATHAMMAN KOIL 1ST CROSS AND ST. THOMAS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25802,Roads,Completed,NG-AMBATTUR,79,2519704,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KRISHNA 1ST STREET AND VOC CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25804,Roads,Completed,NG-AMBATTUR,79,1948034,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KRISHNA 2ND STREET AND KAMARAJ STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25805,Roads,Completed,NG-AMBATTUR,79,4849619,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NADHAMUNI STREET AND AYIRAMKATHAMMAN KOVIL 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25806,Roads,Completed,NG-AMBATTUR,79,2220443,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NADHAMUNI 1ST AND 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25807,Roads,Completed,NG-AMBATTUR,79,2509467,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NSC BOSE STREET, AYIRAKATHAMMAN KOVIL 4TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25808,Roads,Completed,NG-AMBATTUR,79,4481309,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT VOC AND DR AMBETHKAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25809,Roads,Completed,NG-AMBATTUR,79,2078953,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MGR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25810,Roads,Completed,NG-AMBATTUR,79,2900880,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PERIYAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25811,Roads,Completed,NG-AMBATTUR,79,2456887,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT AYRIMKATHAMMAN KOIL 1ST & 3RD CROSS AND THILAGAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25824,Roads,Completed,NG-AMBATTUR,79,4062708,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ANNA STREET AND 3RD CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25825,Roads,Completed,NG-AMBATTUR,79,2094554,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT IN ANNA 1ST AND 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25838,Roads,Completed,NG-AMBATTUR,79,2518119,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GANAPATHI NAGAR 1ST AND 8TH STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25840,Roads,Completed,NG-AMBATTUR,79,2092082,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GANAPATHI NAGAR 2ND STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25841,Roads,Completed,NG-AMBATTUR,79,2518119,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GANAPATHI NAGAR 3RD AND 6TH STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25842,Roads,Completed,NG-AMBATTUR,79,1680897,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GANAPATHI NAGAR 4TH AND 5TH STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25843,Roads,Completed,NG-AMBATTUR,79,1794191,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GANAPATHI NAGAR 7TH STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25872,Roads,Completed,NG-AMBATTUR,79,2074597,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 2ND & 5TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25873,Roads,Completed,NG-AMBATTUR,79,2321909,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 7TH & 9TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25874,Roads,Completed,NG-AMBATTUR,79,2201332,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 9TH-A AND 9TH-B CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25875,Roads,Completed,NG-AMBATTUR,79,1811831,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 14TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25876,Roads,Completed,NG-AMBATTUR,79,1811831,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 15TH-B CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25877,Roads,Completed,NG-AMBATTUR,79,2201332,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 15TH AND 19TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25878,Roads,Completed,NG-AMBATTUR,79,2321909,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 16TH AND 18TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25879,Roads,Completed,NG-AMBATTUR,79,1672761,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 20TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25880,Roads,Completed,NG-AMBATTUR,79,1869216,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 21TH AND 22ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25881,Roads,Completed,NG-AMBATTUR,79,2346629,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 23RD AND 24TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25882,Roads,Completed,NG-AMBATTUR,79,2201332,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 25TH AND 26TH CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25883,Roads,Completed,NG-AMBATTUR,79,2074597,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 27TH AND VIKNESWARA STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25884,Roads,Completed,NG-AMBATTUR,79,2346629,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LENIN NAGAR 28TH AND 28TH -A CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25926,Roads,Completed,NG-AMBATTUR,79,5975721,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT SRV RAMAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25927,Roads,Completed,NG-AMBATTUR,79,3365770,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BHAVANI AMMAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25928,Roads,Completed,NG-AMBATTUR,79,2173447,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT INDRA GANDHI STREET(VENKATESWARA NAGAR) IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25929,Roads,Completed,NG-AMBATTUR,79,1838149,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PANDIYAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25930,Roads,Completed,NG-AMBATTUR,79,6083082,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BHARATHIDASAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25931,Roads,Completed,NG-AMBATTUR,79,6658162,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PACHAMMAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25933,Roads,Completed,NG-AMBATTUR,79,1776582,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KAMBER STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25934,Roads,Completed,NG-AMBATTUR,79,2342212,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT SRINIVASA AND KALAIVANAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25935,Roads,Completed,NG-AMBATTUR,79,1788942,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT THIRUVALLUVAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25936,Roads,Completed,NG-AMBATTUR,79,1583085,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PINTO AND MAGESH STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25937,Roads,Completed,NG-AMBATTUR,79,3530762,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT DR. AZHAPPA STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25938,Roads,Completed,NG-AMBATTUR,79,6291448,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT RAJARAJAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25940,Roads,Completed,NG-AMBATTUR,79,1811856,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT SAMICHETTY 1ST CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25941,Roads,Completed,NG-AMBATTUR,79,1811856,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PADMANABAN STREET AND SAMICHETTY 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25942,Roads,Completed,NG-AMBATTUR,79,2137977,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KAMARAJ STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25943,Roads,Completed,NG-AMBATTUR,79,1957677,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT VALLALAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25944,Roads,Completed,NG-AMBATTUR,79,1576905,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT OM SAKTHI 1ST AND 2ND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25945,Roads,Completed,NG-AMBATTUR,79,2543272,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT SANMUGAM AND SELVAGANAPATHI STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25946,Roads,Completed,NG-AMBATTUR,79,1672924,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PARISAMDAM STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25947,Roads,Completed,NG-AMBATTUR,79,1947841,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PAZANIANDAVAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26023,Roads,Completed,NG-AMBATTUR,79,1899553,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MANIGANDAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26024,Roads,Completed,NG-AMBATTUR,79,1558263,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NARASIMMAN STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26025,Roads,Completed,NG-AMBATTUR,79,2007102,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT VINAYAGAR STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26028,Roads,Completed,NG-AMBATTUR,79,1669058,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PADAMAVATHI SRINIVASA NAGAR MAIN ROAD IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/2636,Buildings,Completed,NG-AMBATTUR,79,1920000,"CONSTRUCTION OF NNMP SHED AT ORAGADAM IN DIV-79,UNIT- 18, ZONE -7",Own Sources,7,2014-15,2016-17 NG/2014-15/26430,Roads,Completed,NG-AMBATTUR,79,1592433,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT SATIYAVANI MUTHU STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/30791,Roads,Completed,NG-AMBATTUR,79,335000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 1ST CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30792,Roads,Completed,NG-AMBATTUR,79,320000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 2ND CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30793,Roads,Completed,NG-AMBATTUR,79,350000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 3RD CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30794,Roads,Completed,NG-AMBATTUR,79,497000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 4TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30795,Roads,Completed,NG-AMBATTUR,79,470000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 5TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30796,Roads,Completed,NG-AMBATTUR,79,510000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 6TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30797,Roads,Completed,NG-AMBATTUR,79,240000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 7TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30798,Roads,Completed,NG-AMBATTUR,79,180000,"LAYING OF CEMENT CONCRETE ROAD AT GANDHI MAIN ROAD 8TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30799,Roads,Completed,NG-AMBATTUR,79,285000,"LAYING OF CEMENT CONCRETE ROAD AT M G R CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30800,Roads,Completed,NG-AMBATTUR,79,485000,"LAYING OF CEMENT CONCRETE ROAD AT GARDEN STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30801,Roads,Completed,NG-AMBATTUR,79,605000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI THERESA 1ST CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30802,Roads,Completed,NG-AMBATTUR,79,740000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI THERASA 2ND CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30803,Roads,Completed,NG-AMBATTUR,79,630000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI THERASA 3RD CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30804,Roads,Completed,NG-AMBATTUR,79,240000,"LAYING OF CEMENT CONCRETE ROAD AT ST THOMAS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30805,Roads,Completed,NG-AMBATTUR,79,836000,"LAYING OF CEMENT CONCRETE ROAD AT ABIRAMI CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30806,Roads,Completed,NG-AMBATTUR,79,260000,"LAYING OF CEMENT CONCRETE ROAD AT PERIYAR STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30807,Roads,Completed,NG-AMBATTUR,79,410000,"LAYING OF CEMENT CONCRETE ROAD AT M G R 2ND CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30808,Roads,Completed,NG-AMBATTUR,79,836000,"LAYING OF CEMENT CONCRETE ROAD AT ANBAZAGAN 1ST CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30809,Roads,Completed,NG-AMBATTUR,79,425000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA 1ST CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30810,Roads,Completed,NG-AMBATTUR,79,594000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA 2ND CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30811,Roads,Completed,NG-AMBATTUR,79,1224000,"LAYING OF CEMENT CONCRETE ROAD AT LENIN NAGAR 19TH A CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30812,Roads,Completed,NG-AMBATTUR,79,1039000,"LAYING OF CEMENT CONCRETE ROAD AT LENIN NAGAR 19TH B CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30813,Roads,Completed,NG-AMBATTUR,79,557000,"LAYING OF CEMENT CONCRETE ROAD AT LENIN NAGAR 13TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30814,Roads,Completed,NG-AMBATTUR,79,464000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA MAIN ROAD 1ST CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30815,Roads,Completed,NG-AMBATTUR,79,410000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA MAIN ROAD 2ND CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30816,Roads,Completed,NG-AMBATTUR,79,506000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA MAIN ROAD 3RD CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30817,Roads,Completed,NG-AMBATTUR,79,476000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA MAIN ROAD 4TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30818,Roads,Completed,NG-AMBATTUR,79,504000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA MAIN ROAD 5TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30819,Roads,Completed,NG-AMBATTUR,79,339000,"LAYING OF CEMENT CONCRETE ROAD AT METTU 1ST CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30820,Roads,Completed,NG-AMBATTUR,79,205000,"LAYING OF CEMENT CONCRETE ROAD AT AYIRAMKATTHAMMAN KOIL 5TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30821,Roads,Completed,NG-AMBATTUR,79,205000,"LAYING OF CEMENT CONCRETE ROAD AT AYIRAMKATTHAMMAN KOIL 6TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30822,Roads,Completed,NG-AMBATTUR,79,477000,"LAYING OF CEMENT CONCRETE ROAD AT PERUMAL KOIL STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30823,Roads,Completed,NG-AMBATTUR,79,574000,"LAYING OF CEMENT CONCRETE ROAD AT PERUMAL KOIL CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30824,Roads,Completed,NG-AMBATTUR,79,504000,"LAYING OF CEMENT CONCRETE ROAD AT AMBETHKAR 1ST CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30825,Roads,Completed,NG-AMBATTUR,79,574000,"LAYING OF CEMENT CONCRETE ROAD AT AMBEDKAR 2ND CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30826,Roads,Completed,NG-AMBATTUR,79,504000,"LAYING OF CEMENT CONCRETE ROAD AT AMBEDKAR 3RD CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30827,Roads,Completed,NG-AMBATTUR,79,574000,"LAYING OF CEMENT CONCRETE ROAD ATAMBEDKAR 4TH CROSS STREET IN DN-79,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/3258,Buildings,Completed,NG-AMBATTUR,79,6650000,"Construction of Urban Primary Health Center (UPHC) at Gandhi nagar main road at oragadam in Div-79,Unit-18,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/12092,Roads,Completed,NG-AMBATTUR,80,2500000,"Forming and strengthening of bt road at ANNA street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/13776,Roads,Completed,NG-AMBATTUR,80,1025000,"Name of the work:- Pre Manson work of to providing GSB, Stone dust, Hiring charges for JCB and Dewatering work, to flood affected area in Dn-80, Unit-18, Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/2204,Roads,Completed,NG-AMBATTUR,80,700000,"Forming and Strengthening of road at banu nagar 30th avenue cross in dn 80, unit 18, zone 7",Own Sources,7,2014-15,2016-17 NG/2014-15/2205,Roads,Completed,NG-AMBATTUR,80,1500000,"Forming and Strengthening of road at rajivgandhi street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/2207,Roads,Completed,NG-AMBATTUR,80,700000,"Forming and Strengthening of road at GOVINDAN street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22243,Roads,Completed,NG-AMBATTUR,80,2500000,"Forming and Strengthening of road at neduncheziyan street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22244,Roads,Completed,NG-AMBATTUR,80,2300000,"Forming and Strengthening of road at munsamy pillai street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22246,Roads,Completed,NG-AMBATTUR,80,4900000,"Forming and Strengthening of road at bharat ratna rajiv gandhi nagar 1st main road in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22247,Roads,Completed,NG-AMBATTUR,80,3500000,"Forming and strengthening of road at vijayalaksmipuram vageeswari amman street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22248,Roads,Completed,NG-AMBATTUR,80,1800000,"Forming and Strengthening of road at subash chandra bose street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22249,Roads,Completed,NG-AMBATTUR,80,1000000,"Forming and Strengthening of road at indragandhi street in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22250,Roads,Completed,NG-AMBATTUR,80,2000000,"Forming and Strengthening of road at evr street and in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/22259,Roads,Completed,NG-AMBATTUR,80,2500000,FORMING AND STRENGTHENING OF BT ROAD AT PRAKASAMGARU STREET IN DIVISION 80 ZONE 7,Own Sources,7,2014-15,2016-17 NG/2014-15/22302,Roads,Completed,NG-AMBATTUR,80,600000,"Forming and Strengthening of road at RAJAGOPAL STREET in Dn.80, Unit-18,Zone -7",Own Sources,7,2014-15,2016-17 NG/2014-15/2393,Roads,Completed,NG-AMBATTUR,80,900000,FORMING AND STRENGTHENING OF BT ROAD AT VIVEKANDAR STREET IN DIVISION 80 ZONE 7,Own Sources,7,2014-15,2016-17 NG/2014-15/25615,Roads,Completed,NG-AMBATTUR,80,2167501,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MURUGESAN STREET AND PERIYAR STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25618,Roads,Completed,NG-AMBATTUR,80,2133927,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT NAGAMMAI STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25621,Roads,Completed,NG-AMBATTUR,80,2167501,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KUMARAN AND CROSS STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25623,Roads,Completed,NG-AMBATTUR,80,2096847,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT AMBEDKAR STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25626,Roads,Completed,NG-AMBATTUR,80,3189004,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT JAGATHAMBAL STREET IN DIVISION:8/0,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25628,Roads,Completed,NG-AMBATTUR,80,1962871,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT VARADHARAJAN STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25629,Roads,Completed,NG-AMBATTUR,80,2967900,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT INDRAGANDHI STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25630,Roads,Completed,NG-AMBATTUR,80,1903990,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MORAJI STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25632,Roads,Completed,NG-AMBATTUR,80,4410510,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ANNIE BESANT STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25635,Roads,Completed,NG-AMBATTUR,80,2061890,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ANNIEBESANT 1ST CROSS, 2ND CROSS, CHERAN CROSS, PALLAVAN ST AND CROSS STREET IN DIVISION:79,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25638,Roads,Completed,NG-AMBATTUR,80,2537179,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT CHOLAN STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25647,Roads,Completed,NG-AMBATTUR,80,4935608,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BHARATHI NAGAR 1ST CROSS STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25650,Roads,Completed,NG-AMBATTUR,80,3820084,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BHARATHI NAGAR 2ND CROSS STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25652,Roads,Completed,NG-AMBATTUR,80,2455889,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BHARATHI NAGAR 3RD CROSS STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25655,Roads,Completed,NG-AMBATTUR,80,1903990,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT PATEL CROSS STREET, AYYAPPA STREET, AND JAYAPRAKASH STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25657,Roads,Completed,NG-AMBATTUR,80,1903990,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT LAKSHANASAMY STREET, ARAVINDAR SATREET AND TAGORE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25730,Roads,Completed,NG-AMBATTUR,80,2232097,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT ANNAI THERASA 5TH CROSS AND THIRUMALAI PRIYA NAGAR 12TH STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25732,Roads,Completed,NG-AMBATTUR,80,4220551,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT TMP 1ST STREET & TMP 2ND STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25735,Roads,Completed,NG-AMBATTUR,80,3688881,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT THIRUTHANIGAI NAGAR IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26087,Roads,Completed,NG-AMBATTUR,80,2216642,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT DHANALAKSHMI STREET AND INDRA GANDHI STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26089,Roads,Completed,NG-AMBATTUR,80,2714777,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT RAJIV GANDHI STREET AND KAMARAJAR STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26105,Roads,Completed,NG-AMBATTUR,80,2137977,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 25TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26106,Roads,Completed,NG-AMBATTUR,80,2338029,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 26TH AND 26TH CROSS STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26107,Roads,Completed,NG-AMBATTUR,80,3929852,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 5TH AND 22TH CROSS STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26108,Roads,Completed,NG-AMBATTUR,80,4298516,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 18TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26109,Roads,Completed,NG-AMBATTUR,80,4298516,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 19TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26111,Roads,Completed,NG-AMBATTUR,80,4827643,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 20TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26112,Roads,Completed,NG-AMBATTUR,80,2073878,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 21ST AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26113,Roads,Completed,NG-AMBATTUR,80,4452036,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 9TH AND 11TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26114,Roads,Completed,NG-AMBATTUR,80,3388924,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 7TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26115,Roads,Completed,NG-AMBATTUR,80,2201332,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 27TH CROSS STREET AND 28TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26116,Roads,Completed,NG-AMBATTUR,80,2201332,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 8TH AVENUE 1ST CROSS STREET IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/26117,Roads,Completed,NG-AMBATTUR,80,2736130,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT BANU NAGAR 10TH AVENUE IN DIVISION:80,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/30828,Roads,Completed,NG-AMBATTUR,80,477000,"LAYING OF CEMENT CONCRETE ROAD AT K V K SAMY 2ND STREET IN DN-80,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30829,Roads,Completed,NG-AMBATTUR,80,477000,"LAYING OF CEMENT CONCRETE ROAD AT K V K SAMY 3RD CROSS STREETIN DN-80,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30830,Roads,Completed,NG-AMBATTUR,80,477000,"LAYING OF CEMENT CONCRETE ROAD AT BANU NAGAR 26TH CROSS STREET IN DN-80,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30831,Roads,Completed,NG-AMBATTUR,80,630000,"LAYING OF CEMENT CONCRETE ROAD AT C P C 3RD CROSS STREET IN DN-80,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30832,Roads,Completed,NG-AMBATTUR,80,630000,"LAYING OF CEMENT CONCRETE ROAD AT C P C 4TH CROSS STREET IN DN-80,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30833,Roads,Completed,NG-AMBATTUR,80,630000,"LAYING OF CEMENT CONCRETE ROAD AT C P C 1ST CROSS STREET IN DN-80,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30834,Roads,Completed,NG-AMBATTUR,80,630000,"LAYING OF CEMENT CONCRETE ROAD AT C P C 5TH CROSS STREET IN DN-80,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/31061,Buildings,Completed,NG-AMBATTUR,80,2000000,"CONSTRUCTION OF NNMP SHED AT PUDUR IN REDHILLS MAIN ROAD IN DIV-80,UNIT- 18, ZONE -7",MLACDS,7,2014-15,2017-18 BR/2014-15/30472,Roads,Completed,BR-Bus Route Roads,81,20100000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Cholapuram Main Road from CTH Road to Nehru Nagar 2nd Street in Ward-81, Zone-7",Grants,7,2014-15,2016-17 NG/2014-15/14113,Buildings,Completed,NG-AMBATTUR,81,976000,"Providing New speed breakers at Vasuki Street, Hospital Road, T.V 1st main Road, Wersten Road, South Park Street, Old Baroda Bank Street, Kannaiya chitty Street ,Oragadam Road at Div-81, Unit-18, Zone-07",Own Sources,7,2014-15,2016-17 NG/2014-15/16059,Parks,Completed,NG-AMBATTUR,81,1004000,"ANNUAL MAINTENENCE OF CORPORATION PARK AT THIRUVENGADAM PARK & KRISHNAPURAM PARK IN DN 81, UNIT 18, ZONE 7",Own Sources,7,2014-15,2016-17 NG/2014-15/16585,Buildings,Completed,NG-AMBATTUR,81,1059000,"Providing New speed breakers Murugappan Reddy Street, South End Road, West End Road, T.V 2nd main Road, T.I School Road Old MTH Road, North Park Street Div-81, Unit-18, Zone-07",Own Sources,7,2014-15,2016-17 NG/2014-15/16586,Buildings,Completed,NG-AMBATTUR,81,1326000,"Providing New speed breakers at K.K Road, School Road, ,Oragadam Road, Mouna Swamy Road, Old Township Road, Nainiammal Street, Rukmaniammal Street Div-81, Unit-18, Zone-07",Own Sources,7,2014-15,2016-17 NG/2014-15/22083,Electrical,Completed,NG-AMBATTUR,81,2058900,"PROVIDING ELECTRICAL WIRING AND GENERATOR FOR URBAN PRIMARY HEALTH CENTER AT SOUTH PARK STREET VENKATAPURAM IN DN -81,UNIT - 18 ZONE-7(AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/22607,Buildings,Completed,NG-AMBATTUR,81,2000000,"CONSTRUCTION OF NNMP SHED AT K K ROAD (Near menambedu Alamaram) IN DIVISION - 81,UNIT- 18, ZONE -7",Own Sources,7,2014-15,2017-18 NG/2014-15/22626,Parks,Completed,NG-AMBATTUR,81,1012000,"ADDITIONAL IMPROVEMENT AT THIRUVENGADAM PARK IN DIV-81,UNIT-18, ZONE-7.",Own Sources,7,2014-15,2017-18 NG/2014-15/3385,Buildings,Completed,NG-AMBATTUR,81,6650000,"Construction of Urban Primary Health Center (UPHC) at sSouth Park Street in Div-81,Unit-18,Zone-7.",Own Sources,7,2014-15,2016-17 BR/2014-15/30009,Roads,Completed,BR-Bus Route Roads,82,19685000,"Strengthening and Relaying with DBM 50mm thick and CBC 40mm thick by Paver finishe using Plastic Waste along with Traffic Improvement work at Karukku Main Road From pattravakkam Bridge to Bypass Bridge in Dn.82, Zone-7",Grants,7,2014-15,2016-17 NG/2014-15/25542,Roads,Completed,NG-AMBATTUR,82,1275688,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GOVINDHA SAMY STREET, GANGAI NAGAR IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25545,Roads,Completed,NG-AMBATTUR,82,1577273,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT JEEVA RATHINAM STREET,GANGAI NAGAR IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25549,Roads,Completed,NG-AMBATTUR,82,2144809,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KABILAR AND NARMATHA STREET IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25550,Roads,Completed,NG-AMBATTUR,82,1930928,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT KAVIYARSU KANNADASAN STREET IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25551,Roads,Completed,NG-AMBATTUR,82,1354460,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT GAYATHRI STREET,OM SAKTHI NAGAR IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25554,Roads,Completed,NG-AMBATTUR,82,5379848,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT THIRUNAVUKARASU STREET IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25556,Roads,Completed,NG-AMBATTUR,82,1446328,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT SENTHIL MURUGAN NAGAR 2ND AND 3RD STREET IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25559,Roads,Completed,NG-AMBATTUR,82,1145767,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT THIRUVALLUAR STREET IN DIVISION:82,UNIT-18,ZONE-VII",Grants,7,2014-15,2016-17 NG/2014-15/25561,Roads,Completed,NG-AMBATTUR,82,4787593,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT D.A.B.C LAYOUT - 1ST ,2ND STREET AND 1ST ,2ND & 3RD STREET IN DIVISION - 82,UNIT- 18,ZONE -7",Grants,7,2014-15,2016-17 NG/2014-15/30835,Roads,Completed,NG-AMBATTUR,82,811000,"LAYING OF CEMENT CONCRETE ROAD AT THILAGAVATHI NAGAR 1ST STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30836,Roads,Completed,NG-AMBATTUR,82,574000,"LAYING OF CEMENT CONCRETE ROAD AT THILAGAVATHI NAGAR 2ND STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30837,Roads,Completed,NG-AMBATTUR,82,339000,"LAYING OF CEMENT CONCRETE ROAD AT LALITHAMBIGAI STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30838,Roads,Completed,NG-AMBATTUR,82,550000,"LAYING OF CEMENT CONCRETE ROAD AT THILAGAVATHI CROSS STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30839,Roads,Completed,NG-AMBATTUR,82,991000,"LAYING OF CEMENT CONCRETE ROAD AT PALLAVAN STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30840,Roads,Completed,NG-AMBATTUR,82,969000,"LAYING OF CEMENT CONCRETE ROAD AT SHOBANA STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30841,Roads,Completed,NG-AMBATTUR,82,425000,"LAYING OF CEMENT CONCRETE ROAD AT NORTH PILLAYAR KOIL STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30842,Roads,Completed,NG-AMBATTUR,82,504000,"LAYING OF CEMENT CONCRETE ROAD AT NORTH PILLAYAR KOIL CROSS STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30843,Roads,Completed,NG-AMBATTUR,82,410000,"LAYING OF CEMENT CONCRETE ROAD AT PILLAYAR KOIL 3RD CROSS STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30844,Roads,Completed,NG-AMBATTUR,82,241000,"LAYING OF CEMENT CONCRETE ROAD AT 1ST LANE PILLAYAR KOILM (ARCH ROAD) IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30845,Roads,Completed,NG-AMBATTUR,82,410000,"LAYING OF CEMENT CONCRETE ROAD AT PATTAMMAL STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/30846,Roads,Completed,NG-AMBATTUR,82,991000,"LAYING OF CEMENT CONCRETE ROAD AT KUMARAN STREET IN DN-82,UNIT-18,ZONE-VII.",Grants,7,2014-15,2016-17 NG/2014-15/3507,Buildings,Completed,NG-AMBATTUR,82,1660000,"CONSTRUCTION OF NNMP SHED AT CHENNAI MIDDLE SCHOOL AT KALLIKUPPAM IN DIV-82,UNIT- 18, ZONE -7",MLACDS,7,2014-15,2016-17 D/2014-15/26753,Storm Water Drain,Completed,D-Storm Water Drains,83,325279000,Construction of Integrated Storm water drains in Padi kuppam Watershed of Cooum Basin in expanded area of Chennai Corporation -Package-12,"Loans, Grants And Own Sources",7,2014-15,2019-20 D/2014-15/26756,Storm Water Drain,Completed,D-Storm Water Drains,83,208405000,Construction of Integrated Storm water drains in Padikuppam Watershed of Cooum Basin in expanded area of Chennai Corporation -Package-13,"Loans, Grants And Own Sources",7,2014-15,2018-19 D/2014-15/27324,Storm Water Drain,Completed,D-Storm Water Drains,83,160933000,"Cooum Water Basin, Padikuppam Water shed, Korattur TNHB Colony Canal,Package-20.",Loans And Grants,7,2014-15,2019-20 NG/2014-15/10235,Buildings,Completed,NG-AMBATTUR,83,1660000,"CONSTRUCTION OF NNMP SHED AT NORTH RAILWAY STATION ROAD IN DIV-83,UNIT- 19, ZONE -7",MLACDS,7,2014-15,2016-17 NG/2014-15/21185,Parks,Completed,NG-AMBATTUR,83,788500,"IMPROVEMENT WORKS AND PROVIDING GREENERIES WITH PLAY APPARATUS AT RANGA GARDEN PARK IN DIV.83, ZONE-7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/22028,Buildings,Completed,NG-AMBATTUR,83,1400000,"Construction of Compound wall with M.S gate at kandigai burial ground at agraharam in Div.83, Zone- 7(ambattur)",Own Sources,7,2014-15,2016-17 NG/2014-15/22104,Buildings,Completed,NG-AMBATTUR,83,2120000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE BUILDING WITH WATER SUPPLY ARRANGEMENT FOR BURIAL GROUND AT SRB 5TH STREET THATHANKUPPAM IN DIV.83, ZONE-7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/3491,Buildings,Completed,NG-AMBATTUR,83,6966000,"Construction of Urban Primary Health Center (UPHC) atTNHB 32nd Street in Division:-83, Unit : 19, ,Zone-7.",Own Sources,7,2014-15,2016-17 D/2014-15/25820,Storm Water Drain,Completed,D-Storm Water Drains,84,384118000,Construction of Integrated Storm water drains in Pdikuppam Watershed of Cooum Basin in expanded area of Chennai Corporation -Package-16,"Loans, Grants And Own Sources",7,2014-15,2018-19 NG/2014-15/13473,Roads,Completed,NG-AMBATTUR,84,760000,"SUPPLYING OF FRONT END LOADER AND LAYING GSB, AT VARIOUS STREETS FOR FLOOD WORK IN DIVISION :84 UNIT 19,ZONE 7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/14186,Buildings,Completed,NG-AMBATTUR,84,1585000,"Proposed construction of Care Taker room with Toilet block for Burial Ground at Kannagi Nagar in Dn - 84, Unit - 20, Zone - 7.",Own Sources,7,2014-15,2017-18 NG/2014-15/14335,Buildings,Completed,NG-AMBATTUR,84,1580000,"Proposed construction of Care Taker room with Toilet block for Burial Ground at Kakkapalayam in Dn - 84, Unit - 20, Zone - 7.",Own Sources,7,2014-15,2016-17 NG/2014-15/14357,Buildings,Completed,NG-AMBATTUR,84,1690000,"Proposed construction of Care Taker room with Toilet block for Burial Ground at Pattaravakkam ( EB Road) in Dn - 84, Unit - 20, Zone - 7.",Own Sources,7,2014-15,2016-17 NG/2014-15/15553,Electrical,Completed,NG-AMBATTUR,84,285000,"Repair and Water Supply arrangement to CI Room TNHB 4TH Street in Division 84, Unit - 20, Zone - 7.",Own Sources,7,2014-15,2016-17 BR/2014-15/29981,Roads,Completed,BR-Bus Route Roads,85,63600000,"Strengthening and Relaying the Road With DBM and CBC by Paver Finish Using plastic Waste along with Traffic improvement works at Padikuppam Main Road from Thirumangalam Amabattur Idustrial Estate Road to Rail Nagar Road in Ward-93, zone-7",Grants,7,2014-15,2016-17 NG/2014-15/25537,Roads,Completed,NG-AMBATTUR,85,4300000,"Strenthening and Re-laying BT roads At Mangala puram Various Street In Kullan Street, Mangalapuram main road Extension in Dn.85, Unit-19, Zone -7.",Own Sources,7,2014-15,2016-17 NG/2014-15/25540,Buildings,Completed,NG-AMBATTUR,85,4327000,"Strengthening and Re-laying BT roads at Ramapuram Various Street In Thiruvalluvar 1st street, Thiruvalluvar 2nd Street in Dn.85, Unit-19, Zone -7.",Own Sources,7,2014-15,2016-17 NG/2014-15/25565,Roads,Completed,NG-AMBATTUR,85,4313000,"Strengthening and Re-laying BT roads At Mangalapuram Various Street In Mangalapuram main road in Dn.85, Unit-19, Zone -7.",Own Sources,7,2014-15,2016-17 NG/2014-15/25568,Roads,Completed,NG-AMBATTUR,85,4241000,"Strengthening and Re-laying roads at Ramapuram Various Street In Damodaran street, Nethaji Street And Samthariya Cross Street in Dn.85, Unit-19, Zone -7.",Own Sources,7,2014-15,2016-17 NG/2014-15/26266,Roads,Completed,NG-AMBATTUR,85,4330000,"Strengthening and Re-laying roads at Ramapuram Various Street In Ayyappan Street, Ayyappan 1st, 2nd, 3rd Cross Strteet in Dn.85, Unit-19, Zone -7.",Own Sources,7,2014-15,2016-17 NG/2014-15/26267,Roads,Completed,NG-AMBATTUR,85,4220000,"Strengthening and Re-laying roads at Ramapuram Various Street In Jayalalitha street,Balaji Street, Ambedkar Street in Dn.85, Unit-19, Zone -7.",Own Sources,7,2014-15,2016-17 NG/2014-15/30886,Buildings,Completed,NG-AMBATTUR,85,730000,"Proposed Common Service Centre in Zonal Office-7 Campus In Division-85,Unit-19,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/30891,Buildings,Completed,NG-AMBATTUR,85,400000,"Proposed Improvements Works to Existing Compound Wall, Watchman Room and Entrance of Zonal Office Building in Division-85,Unit-19,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/4984,Storm Water Drain,Completed,NG-AMBATTUR,85,2910000,"Repairs And Improvement Of SWD At kamarajapuram In Division 85, Unit 19, Zone 7.",Own Sources,7,2014-15,2016-17 NG/2014-15/9725,Parks,Completed,NG-AMBATTUR,85,3770000,"Construction of Compound wall, Footpath and Play approach With in OSR land At CTH Road in Dn-85, unit-19, zone-07.",Own Sources,7,2014-15,2016-17 BR/2014-15/29983,Roads,Completed,BR-Bus Route Roads,86,53600000,"Strengthening and Relaying the Road With DBM and CBC by Paver Finish Using plastic Waste along with Traffic improvement works at Thirupathikudai Road from ICF colony Main Road to Thiruverkadu koladi Road in Ward-86, zone-7",Grants,7,2014-15,2016-17 BR/2014-15/29984,Roads,Completed,BR-Bus Route Roads,86,39200000,"Strengthening and Relaying the Road With DBM and CBC by Paver Finish Using plastic Waste along with Traffic improvement works at ICF Colony Road from Thiruverkadu Koladi High Road to New Century School Road in Ward-86, zone-7",Grants,7,2014-15,2016-17 BR/2014-15/29985,Roads,Completed,BR-Bus Route Roads,86,14400000,"Strengthening and Relaying with DBM and CBC by Paver finisher at Kalaivannar Main Road from Vanagaram Main Road to ICF colony Ayanampakkam in Ward.86, Zone-7",Grants,7,2014-15,2016-17 D/2014-15/24369,Storm Water Drain,Completed,D-Storm Water Drains,86,551446000,Construction of integrated storm water drains in Padikuppam watershed of Cooum basin in expanded area of Chennai Corporation-Package-17.,Loans And Grants,7,2014-15,2018-19 D/2014-15/25384,Storm Water Drain,Completed,D-Storm Water Drains,86,240134000,Construction of Integrated Storm water drain in Cooum watershed of Cooum Basin in expanded area of Chennai Corporation- Package -8.,Loans And Grants,7,2014-15,2019-20 D/2014-15/26015,Storm Water Drain,Completed,D-Storm Water Drains,86,332234000,Construction of integrated storm water drains in Cooum watershed of Cooum basin in expanded area of Chennai Corporation-Package-9.,Loans And Grants,7,2014-15,2017-18 D/2014-15/26060,Storm Water Drain,Completed,D-Storm Water Drains,86,398291000,Construction of integrated storm water drains in Cooum watershed of Cooum basin in expanded area of Chennai Corporation-Package-10.,Loans And Grants,7,2014-15,2019-20 NG/2014-15/10620,Electrical,Completed,NG-AMBATTUR,86,1809000,Providing Electrical Wiring And Generator forUrban primary Health centre at atti pattu chinna colony in Div-86 UNIT-19 ZONE-7(ambattur),Own Sources,7,2014-15,2016-17 NG/2014-15/22935,Roads,Completed,NG-AMBATTUR,86,1740000,"PROVIDING AND FIXING OF SIGNAGE STREET NAME BOARDS AT VARIOUS STREETS AT VGN SHANTHI NAGAR, KSR NAGAR AND MAHAVEER GARDEN IN DIV-86,UNIT-19,ZONE-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/31060,Roads,Completed,NG-AMBATTUR,86,2240000,"Temporary Restoration To The Rain Damaged Roads At Ganesh Street, Alamaram (Burial Ground ) Road In Div 86, Unit 19, Zone 7.",Own Sources,7,2014-15,2016-17 NG/2014-15/3170,Buildings,Completed,NG-AMBATTUR,86,6650000,"Construction of Urban Primary Health Center (UPHC) at Anna Street, Chinna Colony, Athipattu In Division : 86, Unit : 19, ,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/8149,Buildings,Completed,NG-AMBATTUR,86,4550000,"Proposed Construction Of Compound Wall At Western And Southern Sides Of Dumping Yard,Athipattu in Dn-86, U-19,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/8163,Buildings,Completed,NG-AMBATTUR,86,3560000,"Proposed Construction Of Compound Wall At Northern And North-West Sides Of Dumping Yard,Athipattu in Dn-86, U-19,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/9637,Buildings,Completed,NG-AMBATTUR,86,1750000,"Proposed Construction Of Weigh Bridge with Weigh Room at Athipattu Dumping Yard in Dn-86.U-19,Zone-7.",Own Sources,7,2014-15,2016-17 D/2014-15/24306,Storm Water Drain,Completed,D-Storm Water Drains,87,325759000,Construction of integrated storm water drains in Padikuppam watershed of Cooum basin in expanded area of Chennai Corporation-Package-14.,Loans And Grants,7,2014-15,2019-20 D/2014-15/24342,Storm Water Drain,Completed,D-Storm Water Drains,87,139237000,Construction of integrated storm water drains in Padikuppam watershed of Cooum basin in expanded area of Chennai Corporation-Package-18.,Loans And Grants,7,2014-15,2019-20 NG/2014-15/30892,Buildings,Completed,NG-AMBATTUR,87,233400,"Proposed Common Service Centre (Arasu Cable Centre) Church Road at Division Office in Division 87,Unit-19,zone-VII.",MLACDS,7,2014-15,2016-17 NG/2014-15/1333,Parks,Completed,NG-AMBATTUR,88,1060000,"Improvement Works on Painting, Greeneries and Providing Children Play Apparatus At B-Sector Park In Dn-88,Unit-19, Z-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/15565,Roads,Completed,NG-AMBATTUR,88,579000,"Providing New Speed Breaker (As Per IRC Standard) In School Road,East Main Road,Soundariya Colony,Vellammal School Road,Valayapathi Salai at Zone-07(Ph-1).",Own Sources,7,2014-15,2016-17 NG/2014-15/18979,Parks,Completed,NG-AMBATTUR,88,282000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT B-SECTOR PARK IN DIV-88, UNIT-19,ZONE-07.",Own Sources,7,2014-15,2016-17 NG/2014-15/18980,Parks,Completed,NG-AMBATTUR,88,297000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT C -SECTOR PARK IN DIV-88, UNIT-19,ZONE-07.",Own Sources,7,2014-15,2016-17 NG/2014-15/18981,Parks,Completed,NG-AMBATTUR,88,250000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT AP PLOTS PARK IN DIV-88, UNIT-19,ZONE-07.",Own Sources,7,2014-15,2016-17 NG/2014-15/19012,Parks,Completed,NG-AMBATTUR,88,960000,"ANNUAL MAINTENANCE OF MILLINIUM PARK IN DIV-88, UNIT-19,ZONE-07.",Own Sources,7,2014-15,2016-17 NG/2014-15/19792,Parks,Completed,P-Parks and Playfields,88,4993000,"Improvements By Providing Greeneries, Pebble Path, Shuttle Court, Children Play Apparatus and Compound Wall at Millennium Park in Division-88,Unit-19 , Zone-7.",Own Sources,7,2014-15,2017-18 NG/2014-15/24089,Road Cut,Completed,NG-AMBATTUR,88,821000,"Road Cut Restoration Work At Patel road, Mahathma Gandhi road, Rajaji street, in Div-88, Unit-19, Zone-7.",Deposit Works,7,2014-15,2016-17 NG/2014-15/24092,Road Cut,Completed,NG-AMBATTUR,88,239000,"Road Cut Restoration Work At kalaivanar Nagar in Div-88, Unit-19, Zone-7.",Deposit Works,7,2014-15,2016-17 NG/2014-15/24097,Road Cut,Completed,NG-AMBATTUR,88,800000,"Road Cut Restoration Work At Patel Strret, Lokamanya Thilakar Street, Rajaji Street, in Div-88, Unit-19, Zone-7.",Deposit Works,7,2014-15,2016-17 NG/2014-15/3198,Buildings,Completed,NG-AMBATTUR,88,3676000,"Proposed Construction of Amma Unavagam at Pandurangapuram in Div-88,Unit-19,Zone-7",Own Sources,7,2014-15,2016-17 NG/2014-15/4121,Roads,Completed,NG-AMBATTUR,88,3595000,"Construction of Center Median at Park Road From North Main Road to 4th Avenue in Divi-88,Unit -19,Zone -7.",Own Sources,7,2014-15,2016-17 NG/2014-15/6346,Buildings,Completed,NG-AMBATTUR,88,570000,"Repair and Maintenance work for Buildings at CPS kalivanar nagar main road, Millineum park, B-sector park and amma unavagam in division -88, unit - 19, Zone -7.",Own Sources,7,2014-15,2016-17 D/2014-15/25818,Storm Water Drain,Completed,D-Storm Water Drains,89,356382000,Construction of Integrated Storm water drains in PADIKUPPAM Watershed of Cooum Basin in expanded area of Chennai Corporation -Package-15,"Loans, Grants And Own Sources",7,2014-15,2018-19 NG/2014-15/15415,Electrical,Completed,NG-AMBATTUR,89,274400,Providing electrical wiring for exiting building for 1 st floor in health centre in tvs colony ward-89 zone-VII-ambattur,Own Sources,7,2014-15,2016-17 NG/2014-15/17077,Parks,Completed,NG-AMBATTUR,89,472000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT TVS COLONY PARK IN DIV 89 UNIT-19,ZONE-07.",Own Sources,7,2014-15,2016-17 NG/2014-15/17078,Parks,Completed,NG-AMBATTUR,89,677000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT GOLDEN COLONY PARK IN DIV 89, UNIT-19,ZONE-07.",Own Sources,7,2014-15,2016-17 NG/2014-15/22015,Roads,Completed,NG-AMBATTUR,89,586000,"Road Cut Restoration Work At Golden Colony 1st Main road in Div-89, Unit-19,Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/22111,Roads,Completed,NG-AMBATTUR,89,586000,"Road Cut Restoration Work At Sathya Nagar 2nd Main Road in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/2371,Buildings,Completed,NG-AMBATTUR,89,2240000,"IMPROVEMENTS TO EXISTING CHILDREN PARK AT OFFICERS COLONY MAIN ROAD IN DN-89,UNIT-19,ZONE-7",Own Sources,7,2014-15,2017-18 NG/2014-15/23918,Roads,Completed,NG-AMBATTUR,89,195000,"Road Cut Restoration Work At Vallal Pari Nagar in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/23960,Roads,Completed,NG-AMBATTUR,89,130000,"Road Cut Restoration Work At Akshaya Colony 4th Avenue in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/23969,Roads,Completed,NG-AMBATTUR,89,66000,"Road Cut Restoration Work At Bhakkiathammal Nagar in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/26005,Roads,Completed,NG-AMBATTUR,89,287000,"Road Cut Restoration Work At Officers Colony 1st Street in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/26605,Roads,Completed,NG-AMBATTUR,89,195000,"Road Cut Restoration Work At Officers Colony 1st Street in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/26613,Roads,Completed,NG-AMBATTUR,89,390000,"Road Cut Restoration Work At Akshaya Colony 1st Main Road in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/26736,Roads,Completed,NG-AMBATTUR,89,196000,"Road Cut Restoration Work At Golden Colony Main Road in Div-89, Unit-19, Zone-7.",Deposit Works,7,2014-15,2017-18 NG/2014-15/17189,Parks,Completed,NG-AMBATTUR,90,597000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT GOLDEN JUBILEE PARK IN DIV-90, UNIT-20,ZONE-07.",Own Sources,7,2014-15,2016-17 NG/2014-15/28853,Parks,Completed,NG-AMBATTUR,90,1158000,"Improvement of Welcome Colony Block No.48, 49 Park in Dn-90,Unit-20, Zone-7",Own Sources,7,2014-15,2016-17 NG/2014-15/29106,Parks,Completed,NG-AMBATTUR,90,785000,"Improvement of Santham Colony Near Block No.2,3,10 Pancharathinam Park in Dn-90, Unit-20, Zone-7",Own Sources,7,2014-15,2016-17 NG/2014-15/29108,Parks,Completed,NG-AMBATTUR,90,1526000,"Improvement of Collector Nagar Park in Dn-90,Unit-20, Zone-7",Own Sources,7,2014-15,2016-17 BR/2014-15/29982,Roads,Completed,BR-Bus Route Roads,91,15700000,"Strengthening and Relaying with DBM and CBC after Cold milling by Paver finish USing Plastic Waste along wqith Traffic improvement works by Paver finisher at Kambar Salai From Mogappair West 3rd Main Road to Ambattur Industrial Estate in Ward.91, Zone-7",Grants,7,2014-15,2016-17 BR/2014-15/29992,Roads,Completed,BR-Bus Route Roads,91,19400000,"Strengthening and Relaying with DBM and CBC after Cold milling by Paver finish USing Plastic Waste along wqith Traffic improvement works by Paver finisher at Mogappair West 3rd Main Road from Kavimani salai to Petrol Bunk in Ward.91, Zone-7",Grants,7,2014-15,2016-17 NG/2014-15/1637,Buildings,Completed,NG-AMBATTUR,91,1955000,"CONSTRUCTION OF NNMP SHED NO.10 AT Dr.JJ NAGAR WEST 1st BLOCK IN DIV-91, U-20, ZONE-7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/1644,Buildings,Completed,NG-AMBATTUR,91,1955000,"CONSTRUCTION OF NNMP SHED NO.13 AT Dr.JJ NAGAR WEST 2nd BLOCK IN DIV-91, U-20, ZONE-7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/1656,Buildings,Completed,NG-AMBATTUR,91,1955000,"CONSTRUCTION OF NNMP SHED NO.4 AT Dr.JJ NAGAR WEST 7th BLOCK IN DIV-91, U-20, ZONE-7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/17146,Roads,Completed,NG-AMBATTUR,91,910000,"PROVIDING NEW SPEED BREAKER(AS PER IRC STANDARD) AT REDDIPALAYAM MAIN ROAD, KAVIMANI SALAI,MOGAPPAIR WEST 3RD MAIN ROAD, IN DIVISION-91,UNIT-20,ZONE-7.(AMBATTUR).",Own Sources,7,2014-15,2016-17 NG/2014-15/21995,Buildings,Completed,NG-AMBATTUR,91,1600000,"Construction of Compound wall with M.S gate at NNMP shed centre No: 03, 1st Block in Div.91, Unit20, Zone- 7(ambattur)",Own Sources,7,2014-15,2016-17 NG/2014-15/22000,Buildings,Completed,NG-AMBATTUR,91,1450000,"Construction of Compound wall with M.S gate at NNMP shed centre No: 9, 7th Block in Div.91, Unit20, Zone- 7(ambattur)",Own Sources,7,2014-15,2016-17 NG/2014-15/22009,Buildings,Completed,NG-AMBATTUR,91,1450000,"Construction of Compound wall with M.S gate at NNMP shed centre No: 06, 3rd Block in Div.91, Unit20, Zone- 7(ambattur)",Own Sources,7,2014-15,2016-17 NG/2014-15/22010,Buildings,Completed,NG-AMBATTUR,91,1490000,"Construction of Compound wall with M.S gate at NNMP shed centre No: 5,Mogappair west 1st Block in Div.91,Unit20, Zone- 7(ambattur)",Own Sources,7,2014-15,2016-17 NG/2014-15/22011,Buildings,Completed,NG-AMBATTUR,91,1625000,"Construction of Compound wall with M.S gate at NNMP shed centre No: 02, 3rd Block in Div.91, Unit20, Zone- 7(ambattur)",Own Sources,7,2014-15,2016-17 NG/2014-15/28968,Buildings,Completed,NG-AMBATTUR,91,1320000,"Construction of Toilet for Chennai Middle School at Sector-9, 7th Block,Mogappair West in Div-91,Unit-20,Zone-VII",Own Sources,7,2014-15,2016-17 NG/2014-15/29003,Buildings,Completed,NG-AMBATTUR,91,1320000,"Construction of Toilet for Chennai Primary School at Sector-5, 1st Block,Mogappair West in Div-91,Unit-20,Zone-VII",Own Sources,7,2014-15,2016-17 NG/2014-15/29409,Parks,Completed,NG-AMBATTUR,91,779000,"IMPROVEMENT OF GREENERIES FOR CORPORATION PARKS AT JESWANTH NAGAR PHASE I & II PARK IN DIV-91,UNIT-20,ZONE-07(AMBATTUR)",Own Sources,7,2014-15,2016-17 RC/2014-15/7695,Roads,Completed,BR-Bus Route Roads,91,1421000,"Proposed Construction of Center Median work at Mugapair West in ward 91, Zone 7",Own Sources,7,2014-15,2016-17 BR/2014-15/30008,Roads,Completed,BR-Bus Route Roads,92,17564000,"Strengthening and Relaying with DBM and CBC after Cold milling by Paver finish USing Plastic Waste along wqith Traffic improvement works by Paver finisher at Vallalar street from Thirumangalam Ambattur Industrial Estate to Mogappair West 3rd Main Road and Venugopal street junction in Ward.92, Zone-7",Grants,7,2014-15,2016-17 BR/2014-15/30010,Roads,Completed,BR-Bus Route Roads,92,17077000,"Strengthening and Relaying the Road With DBM and CBC by Paver Finish Using plastic Waste along with Traffic improvement works at Church Road from Mogappair Eri Scheme 6th Main Road to Golden George Ratnam Road in Ward-93&91, zone-7",Grants,7,2014-15,2016-17 NG/2014-15/22525,Roads,Completed,NG-AMBATTUR,92,6423000,"Strengthening and Forming the BT Road at Kongu Nagar Main Road and 1 to 3 cross streets in DN-92,Unit-20,Zone-7",Own Sources,7,2014-15,2016-17 NG/2014-15/3058,Buildings,Completed,NG-AMBATTUR,92,3676000,"Proposed Construction of Amma Unavagam at Kamarajapuram In Division 85, Unit 19 ,Zone-7",Own Sources,7,2014-15,2016-17 NG/2014-15/15671,Buildings,Completed,NG-AMBATTUR,93,1560000,"Construction of Compound Wall to ICDS Center at 3rd Block Pugazhendhi Salai 20th Street Mogappair East in Div-93,Unit-20,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/15675,Buildings,Completed,NG-AMBATTUR,93,1990000,"Construction of Compound Wall to NNMP Shed at 4th Block Nakkeeran Street Mogappair East in Div-93,Unit-20,Zone-7.",Own Sources,7,2014-15,2017-18 NG/2014-15/15684,Buildings,Completed,NG-AMBATTUR,93,1590000,"Construction of Compound Wall to ICDS Center at 5th Block Burner Salai Mogappair East in Div-93,Unit-20,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/2109,Buildings,Completed,NG-AMBATTUR,93,6650000,"Construction of Urban Primary Health Center (UPHC) at Veeramunivar Salai Mogappair East in Div-93,Unit-20,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/21443,Buildings,Completed,NG-AMBATTUR,93,1900000,"Maintenance and Improvement works for PC at Padikuppam Main Road in Div-93,Unit-20,Zone-VII",Own Sources,7,2014-15,2016-17 NG/2014-15/21735,Buildings,Completed,NG-AMBATTUR,93,640000,"Maintenance and Improvement works for Chennai Primary School Sector I,Agathiyar Salai,Mogappair East,in Div-93,Unit-20,Zone-VII.",Own Sources,7,2014-15,2016-17 NG/2014-15/21757,Buildings,Completed,NG-AMBATTUR,93,1360000,"Maintenance and Improvement works for Chennai Primary School Sector III at Pari Salai 1st Cross Street in Div-93,Unit-20,Zone-VII.",Own Sources,7,2014-15,2016-17 NG/2014-15/21773,Buildings,Completed,NG-AMBATTUR,93,640000,"Maintenance and Improvement works for Chennai Middle School Sector IV at Nakkeeran Salai in Div-93,Unit-20,Zone-VII.",Own Sources,7,2014-15,2016-17 NG/2014-15/21939,Buildings,Completed,NG-AMBATTUR,93,800000,"Providing Foot path,Sump and Maintenance Works to ICDS Centers at 5th Block Agathiyar Salai,3rd Block Pugazhenthi Salai,3rd Block Nakeeran Salai,5th Block Burnar Salai,2nd Block Pugazhenthi Salai,in Div-93,Unit-20,Zone-VII.",Own Sources,7,2014-15,2016-17 NG/2014-15/22003,Buildings,Completed,NG-AMBATTUR,93,1310000,"Construction of Toilet for Chennai Primary School at Sector III Parish Salai 1st Cross Street,Mogappair East in Div-93,Unit-20,Zone-VII",Own Sources,7,2014-15,2016-17 NG/2014-15/22004,Buildings,Completed,NG-AMBATTUR,93,1310000,"Construction of Toilet for Chennai Middle School at Sector II Pugazhenthi Salai,Mogappair East in Div-93,Unit-20,Zone-VII",Own Sources,7,2014-15,2016-17 NG/2014-15/22005,Buildings,Completed,NG-AMBATTUR,93,1310000,"Construction of Toilet for Chennai Primary School at 1st Sector,Agathiyar Salai Mogappair East in Div-93,Unit-20,Zone-VII",Own Sources,7,2014-15,2016-17 NG/2014-15/28173,Roads,Completed,NG-AMBATTUR,93,12250000,"Providing and Laying of BT Road at 5Th Block Burner Salai 1st Cross Street,2nd Cross Street,3rd Cross Street,4th Cross Street,5th Cross Street, 6th Cross Street,Pari Salai 1st Cross Street,Gangai Amman Kovil Street, vandiamman kovil street, indhra gandhi street, ori salai and Church Road at Mogappair East in Div-93,Unit-20 ,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/28186,Roads,Completed,NG-AMBATTUR,93,3823000,"Providing and Laying of BT Road at 5Th Block Burner Salai 18th Cross Street,19th Cross Street,20th Cross Street,21st Cross Street,22nd Cross Street, 23rd Cross Street, Anna Street,MGR Street,Rajiv Gandhi Street,Indhira Gandhi Street Mogappair East in Div-93,Unit-20 ,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/3656,Buildings,Completed,NG-AMBATTUR,93,1046000,"REPAIRS, MAINTANANCE AND IMPROVEMENT WORKS FOR ALL COC BUILDINGS IN DIV.93, U20, ZONE7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 NG/2014-15/5564,Buildings,Completed,NG-AMBATTUR,93,2310000,"Construction of Compound Wall to Chennai Middle School at 4th Sector Nakkeeran Salai Mogappair East in Div-93,Unit-20,Zone-7.",Own Sources,7,2014-15,2016-17 NG/2014-15/8427,Electrical,Completed,NG-AMBATTUR,93,1809000,"PROVIDING ELECTRICAL WIRING AND GENERATOR FOR URBAN PRIMARY HEALTH CENTER AT Dr.JJ NAGAR EAST VEERAMA MUNIVAR STREET IN DIV.93, UNIT20, ZONE-7 (AMBATTUR)",Own Sources,7,2014-15,2016-17 BR/2014-15/29979,Roads,Completed,BR-Bus Route Roads,94,8562000,Strengthening and Relaying the Bus Route Road with DBM and CBC after cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Villivakkam Redhills Road (S) ( From the JN of Balliamman Kovil Street to the JN of Villivakkam Railway Subway(LC2) Ward-94 Zone-8,Grants,8,2014-15,2016-17 BR/2014-15/29991,Roads,Completed,BR-Bus Route Roads,94,3700000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Balliamman Kovil Street From the Junction of Reddy Street to the Junction of Villivakkam Redhills Road (South) in Ward-94 Zone 8,Grants,8,2014-15,2016-17 BR/2014-15/30067,Roads,Completed,BR-Bus Route Roads,94,38356000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at MTH Road From the Junction of Konnur High Road to the Junction of Reddy Street and From the JN of New Avadi Road to the Jn of Padi Flyover in Ward-94,95 Zone 8",Grants,8,2014-15,2016-17 BR/2014-15/30069,Roads,Completed,BR-Bus Route Roads,94,9496000,Strengthening and Relaying the Bus Route Road with DBM and CBC after cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Sidco Nagar 4th Main Road ( From the JN of MTH Road to the JN of Villivakkam Redhills Road Ward-94 Zone-8,Grants,8,2014-15,2016-17 BR/2014-15/30070,Roads,Completed,BR-Bus Route Roads,94,8134000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Sidco Nagar 1st Main Road From the Junction of MTH Road to the Junction of Sidco Nagar 4th Main Road in Ward-94 Zone 8,Grants,8,2014-15,2016-17 BR/2014-15/30072,Roads,Completed,BR-Bus Route Roads,94,5944000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Reddy Street From the Junction of MTH Road to the Junction of Balliamman Kovil Street in Ward-94 Zone 8,Grants,8,2014-15,2016-17 L/2014-15/28467,Electrical,Completed,L-Electrical,94,1152200,"Provision of 26 nos of 6 mtr G.I Lamp post with Single arch bracket with Hot dip Zinc galvanising with 90W-120W LED fitting at redhills main road in villivakkam in div94, Z-VIII",Own Sources,8,2014-15,2016-17 NH/2014-15/12976,Buildings,Completed,NH-ANNA NAGAR,94,503000,"PROVIDING MANHOLE RASING AND LOWERING (CMWSSB MANHOLE) VARIOUS STREET IN DN 94,ZONE 8",Own Sources,8,2014-15,2016-17 NH/2014-15/18864,Subway,Completed,NH-ANNA NAGAR,94,794000,ANNUAL MAINTANANCE OF VILLIVAKKAM SUB WAY ENGAGING FOR MOTOR MECHANICAND WATCH MAN FOR ONE YEAR IN DN 94 ZONE 8,Own Sources,8,2014-15,2016-17 NH/2014-15/24262,Roads,Completed,NH-ANNA NAGAR,94,841000,"RELAYING CC ROAD RMC 30 AT ARIGNAR ANNA STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/27900,Roads,Completed,NH-ANNA NAGAR,94,844000,"RELAYING CC ROAD RMC 30 AT ANNAI SATHYA NAGAR 1 TO 2 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/27920,Roads,Completed,NH-ANNA NAGAR,94,853500,"RELAYING CC ROAD RMC 30 AT SIDCO 74 TO 81 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27921,Roads,Completed,NH-ANNA NAGAR,94,853000,"RELAYING CC ROAD RMC 30 AT SIDCO NAGAR 15 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27922,Roads,Completed,NH-ANNA NAGAR,94,860000,"RELAYING CC ROAD RMC 30 AT sidco 13 &14 st DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27927,Roads,Completed,NH-ANNA NAGAR,94,710000,"RELAYING CC ROAD RMC 30 AT SIDCO 16 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27928,Roads,Completed,NH-ANNA NAGAR,94,853700,"RELAYING CC ROAD RMC 30 AT SIDCO 82 TO 89 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27938,Roads,Completed,NH-ANNA NAGAR,94,853700,"RELAYING CC ROAD RMC 30 AT SIDCO 39 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27943,Roads,Completed,NH-ANNA NAGAR,94,2100000,"RELAYING CC ROAD RMC 30 AT SIDCO 53 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/27944,Roads,Completed,NH-ANNA NAGAR,94,875000,"RELAYING CC ROAD RMC 30 AT SIDCO 28, 47 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/27945,Roads,Completed,NH-ANNA NAGAR,94,853700,"RELAYING CC ROAD RMC 30 AT SIDCO 61 & 62 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27947,Roads,Completed,NH-ANNA NAGAR,94,853700,"RELAYING CC ROAD RMC 30 AT SIDCO 66 TO 73 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27955,Roads,Completed,NH-ANNA NAGAR,94,854000,"RELAYING CC ROAD RMC 30 AT SIDCO 37 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/27956,Roads,Completed,NH-ANNA NAGAR,94,860000,"RELAYING CC ROAD RMC 30 AT SIDCO 46 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/28077,Roads,Completed,NH-ANNA NAGAR,94,854000,"RELAYING CC ROAD RMC 30 AT SIDCO 64 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/28079,Roads,Completed,NH-ANNA NAGAR,94,853700,"RELAYING CC ROAD RMC 30 AT SIDCO 65 STREET DIVISION-94, ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/30955,Buildings,Completed,NH-ANNA NAGAR,94,662000,Improvements To NNMP Shed ( Creche)and construction of baby toillet At Sidco nagar 60th street in Dn-94 Unit-21 Zone - 8,Own Sources,8,2014-15,2017-18 L/2014-15/28473,Electrical,Completed,L-Electrical,95,2033000,"Provision of 47 nos of 6 mtr G.I Lamp post with Single arch bracket with Hot dip Zinc galvanising with 90W-120W LED fitting at East madha street,south madha street and Ramandiram street in villivakkam in div95, Z-VIII",Own Sources,8,2014-15,2016-17 L/2014-15/28479,Electrical,Completed,L-Electrical,95,1663900,"PROVISION OF 49 NOS OF 6 MTR G.I LAMP POST WITH SINGLE STRIHT BRACKET WITH 40 W-50 W LED FITTING AT PONNANGIKINARI ,MURUTHY NAGAR AND MURUGESAN STREET IN DIV-95,Z-VIII",Own Sources,8,2014-15,2016-17 L/2014-15/28489,Electrical,Completed,L-Electrical,95,2150800,PROVISION OF 46 NOS OF 6 MTR G.I OCTAGONAL LAMP POST WITH SINGLE STRIHT BRACKET WITH 90 W-120 W LED FITTING AT THIRUMANGALAM MAIN ROAD JN OF I BLOCK IN ANNA NAGAR WEST IN DIV-95VIII,Own Sources,8,2014-15,2016-17 NH/2014-15/21808,Buildings,Completed,NH-ANNA NAGAR,95,900000,"IMPROVEMENT TO PLAY GROUND AT KAMBAR COLONY IN DN-95 , U-21 , Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/21813,Roads,Completed,NH-ANNA NAGAR,95,399000,"RELAYING OF ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT VALLALAR KUDI IRUPPU 7TH STREET IN DN-95 , U-21 ,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/21815,Roads,Completed,NH-ANNA NAGAR,95,209000,"RELAYING OF ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT VALLALAR KUDI IRUPPU 9TH STREET IN DN-95 , U-21 ,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/2386,Buildings,Completed,NH-ANNA NAGAR,95,3436000,"ADDITIONAL CONSTRUCTION IN FIRST FLOOR FOR HEATH POST AT VENNUGOPAL STREET IN DN-95,Z.8.",Own Sources,8,2014-15,2016-17 NH/2014-15/27800,Roads,Completed,NH-ANNA NAGAR,95,560000,"LAYING OF CEMENT CONCRETE ROAD AT THIRU-VI-KA 2ND STREET IN DN-95,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27803,Roads,Completed,NH-ANNA NAGAR,95,560000,"LAYING OF CEMENT CONCRETE ROAD AT THIRU-VI-KA 3RD STREET IN DN-95,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27804,Roads,Completed,NH-ANNA NAGAR,95,520000,"LAYING OF CEMENT CONCRETE ROAD AT MOSQUE 1ST STREET IN DN-95,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27806,Roads,Completed,NH-ANNA NAGAR,95,439000,"LAYING OF CEMENT CONCRETE ROAD AT SEEYALAM 4TH LANE IN DN-95,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27808,Roads,Completed,NH-ANNA NAGAR,95,381670,"LAYING OF CEMENT CONCRETE ROAD AT THIRUVEETHI AMMAN KOIL 2ND CROSS STREET IN DN-95,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27973,Roads,Completed,NH-ANNA NAGAR,95,203000,"RELAYING OF ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT AGATHIYAR NAGAR 35TH STREET IN DN-95,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27975,Roads,Completed,NH-ANNA NAGAR,95,418000,"RELAYING OF ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT THIRUVALLUVAR KUDI IRUPPU 25TH STREET IN DN-95 , U-21 ,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/12332,Parks,Completed,NH-ANNA NAGAR,96,530000,"MAINTENANCE OF JEEVA PARK FOR 2 YEARS IN DN-96 , U-21 , Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27738,Roads,Completed,NH-ANNA NAGAR,96,1690000,"RELAYING OF CEMENT CONCRETE ROAD AT GANDHI NAGAR TENEMENTS ROAD IN DN-96,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27740,Roads,Completed,NH-ANNA NAGAR,96,1476000,"RELAYING OF CEMENT CONCRETE ROAD AT K.K NAGAR 5TH STREET IN DN-96,U-21,Z-08",Own Sources,8,2014-15,2017-18 NH/2014-15/27741,Roads,Completed,NH-ANNA NAGAR,96,1495000,"RELAYING OF CEMENT CONCRETE ROAD AT K.K NAGAR 10TH STREET IN DN-96,U-21,Z-08",Own Sources,8,2014-15,2017-18 NH/2014-15/27744,Roads,Completed,NH-ANNA NAGAR,96,1862000,"RELAYING OF CEMENT CONCRETE ROAD AT TAGORE NAGAR 1ST STREET IN DN-96,U-21,Z-08",Own Sources,8,2014-15,2017-18 NH/2014-15/12333,Parks,Completed,NH-ANNA NAGAR,97,370000,"MAINTENANCE OF OSR LAND PARK NEAR SUNNYVEL APPARTMENT AT K.H ROAD FOR 2 YEARS IN DN-96 , U-21 , Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/18281,Storm Water Drain,Completed,NH-ANNA NAGAR,97,980000,".Providing Silt Catch pit with FRP Gratings with frame at variours in Ward 97, Unit 21, Zone 8",Own Sources,8,2014-15,2016-17 NH/2014-15/20468,Buildings,Completed,NH-ANNA NAGAR,97,999000,"PROPOSED CONSTRUCTION OF ADDITIONAL GYM BUILDING AT VEELALA STREET IN DN-97,U-21,Z-08",Own Sources,8,2014-15,2017-18 NH/2014-15/23072,Parks,Completed,NH-ANNA NAGAR,97,980000,"PROVIDING GREENARY, OUTDOOR GYM AND PLAY APPARATUS AT VELLALA STREET PARK IN DN-97 , U-21 , Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/24195,Storm Water Drain,Completed,NH-ANNA NAGAR,97,998000,"DESILTING AND RECONSTRUCTION OF STORM WATER DRAIN AT PERIYAR SALAI IN DN-97 , U-21 , Z-08",Own Sources,8,2014-15,2017-18 NH/2014-15/25310,Parks,Completed,NH-ANNA NAGAR,97,600000,"IMPROVEMENT TO PLAY GROUND AND PROVIDING GYM EQUIPMENTS AT PACHAIKKAL VEERASAMY STREET IN DN-97, U-21, Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/25516,Storm Water Drain,Completed,NH-ANNA NAGAR,97,531000,"DESILTING AND IMPROVEMENT TO RAIN WATER HARVESTING WELL AT VARIOUS STREET IN DN-97,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27182,Roads,Completed,NH-ANNA NAGAR,97,1472000,"LAYING OF CC ROAD AT KAMARAJ STREET IN DN-97,U-21,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27185,Roads,Completed,NH-ANNA NAGAR,97,1718000,"LAYING OF CC ROAD AT SOLAI AMMAN KOIL STREET IN DN-97,U-21,Z-08",Own Sources,8,2014-15,2017-18 NH/2014-15/27193,Roads,Completed,NH-ANNA NAGAR,97,715000,"LAYING OF CC ROAD AT VELLALA STREET 1ST LANE IN DN-97,U-21,Z-08",Own Sources,8,2014-15,2017-18 NH/2014-15/5441,Buildings,Completed,NH-ANNA NAGAR,97,997000,"IMPROVEMENT OF ICDS CENTRE NO:05034 ,05035 ,05036, 05037 IN DN-97 , U-21 , Z-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/2497,Buildings,Completed,NH-ANNA NAGAR,98,3145000,ADDITIONAL CONSTRUCTION AND IMPROVEMENTS TO EXISTING HEALTH POST AT ASPIRAN GARDEN 1ST STREET KILPAUK IN DN -98 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/27208,Roads,Completed,NH-ANNA NAGAR,98,1270000,"LAYING OF CEMENT CONCRETE ROAD AT POLICE MANIKAM STREET IN DN-98,U-23,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27813,Roads,Completed,NH-ANNA NAGAR,98,890000,"LAYING OF CEMENT CONCRETE ROAD AT LOGANATHAN STREET IN DN-98,U-23,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27815,Buildings,Completed,NH-ANNA NAGAR,98,87600,"PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT SWAMY DOSS PURAM IN DN-98,U-23,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/27847,Roads,Completed,NH-ANNA NAGAR,98,890000,"LAYING OF CEMENT CONCRETE ROAD AT KALAINGAR NAGAR IN DN-98,U-23,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/5278,Roads,Completed,NH-ANNA NAGAR,98,986000,"PROVIDING AND LAYING SPEED BREAKERS AT AYANAVARAM ROAD , RAJU STREET AND PATCH WORKS AT VARIOUS STREETS IN DN-98 U-23 Z-8",Own Sources,8,2014-15,2016-17 NH/2014-15/19491,Footpath,Completed,NH-ANNA NAGAR,99,153000,WATER SUPPLY ARRANGEMENT TO SCHOOL BUILDING AT C.P.S T.V. NAGAR THIRUMANGALAM IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2014-15,2016-17 NH/2014-15/21691,Buildings,Completed,NH-ANNA NAGAR,99,999000,CONSTRUCTION OF CHENNAI CORPORATION ELEMENTRY SCHOOL EASTERN BLOCK AT THILLAYADI VALLIYAMMAI NAGAR (PILLAYAR KOVIL STREET)IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2014-15,2016-17 NH/2014-15/23201,Roads,Completed,NH-ANNA NAGAR,99,936000,Restoration of road cut mede by cmwssb @ Anna street majestic colony bharathidhasan street thandai periyar street thillai vinayagar street thiru.v.ka street Dr.ambethkar street v.o.c.street nehru street dn 99,Deposit Works,8,2014-15,2016-17 NH/2014-15/23219,Buildings,Completed,NH-ANNA NAGAR,99,999000,CONSTRUCTION OF CHENNAI CORPORATION ELEMENTRY SCHOOL WESTERN BLOCK AT THILLAYADI VALLIYAMMAI NAGAR (PILLAYAR KOVIL STREET)IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2014-15,2016-17 NH/2014-15/2407,Parks,Completed,NH-ANNA NAGAR,99,830000,ANNUAL MAINTENANCE OF PARK AT ( O.S.R LAND ) R.B.I QRS PARK JN OF 15TH MAIN ROAD IN DN 99 UNIT 21 ZONE 8(BY QUALIFIED HORTICULTURIST FOR TWO YEARS),Own Sources,8,2014-15,2018-19 NH/2014-15/9699,Playfields,Completed,NH-ANNA NAGAR,99,999000,"IMPROVEMENTS TO CHILDREN PLAYGROUND AT H-BLOCK 16TH STREET ( BRINLAY GARDEN ) ANNA NAGAR IN DN-99 , U-21 , Z-8",Own Sources,8,2014-15,2016-17 BR/2014-15/29989,Roads,Completed,BR-Bus Route Roads,100,12480000,Strengthening and Relaying the Bus Route Road with DBM and CBC after cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Anna Nagar 5th Avenue( From the JN of 6th Avenue to the JN of Anna Nagar 4th Main Road in Ward-100 Zone-8,Grants,8,2014-15,2016-17 L/2014-15/28211,Electrical,Completed,L-Electrical,100,4347400,Provision of lamp post,Own Sources,8,2014-15,2016-17 L/2014-15/28242,Electrical,Completed,L-Electrical,100,4999100,PROVISION OF LAMP POST,Own Sources,8,2014-15,2016-17 L/2014-15/28251,Electrical,Completed,L-Electrical,100,3660700,PROVISION OF LAMP POST,Own Sources,8,2014-15,2016-17 L/2014-15/28277,Electrical,Completed,L-Electrical,100,3387000,PROVISION OF LAMP POST,Own Sources,8,2014-15,2016-17 NH/2014-15/16486,Parks,Completed,NH-ANNA NAGAR,100,500000,"ANNUAL MAINTENANCE OF DR. VISWESWARAYA TOWER PARK TOILET CLEANING MAINTENANCE FOR ONE YEAR IN WARD 100, UNIT 22, ZONE VIII.",Own Sources,8,2014-15,2017-18 NH/2014-15/16487,Buildings,Completed,NH-ANNA NAGAR,100,225000,"ADDTIONAL IMPROVEMENTS TO NNMB SHED AT MGR COLONY,AMBEDKAR NAGR IN DN-100,U-22,Z-8",Own Sources,8,2014-15,2016-17 NH/2014-15/16675,Buildings,Completed,NH-ANNA NAGAR,100,108000,"PAINTING FOOTPATH AT VARIOUS ROAD IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/16676,Buildings,Completed,NH-ANNA NAGAR,100,130000,"IMPROVEMENT TO TOWER PARK VISWESWARIAYA TOWER PARK IN DIVISION-100,UNIT-22,ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/17347,Roads,Completed,NH-ANNA NAGAR,100,990000,"IMPROVEMENTS TO THE CEMENT CONCRETE ROAD AT NSK NAGAR 3RD STREET IN DN-100,UNIT-22,ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/17348,Roads,Completed,NH-ANNA NAGAR,100,990000,"IMPROVEMENTS TO THE CEMENT CONCRETE ROAD AT NSK NAGAR 2ND STREET IN DN-100,UNIT-22,ZONE-8",Own Sources,8,2014-15,2017-18 NH/2014-15/17349,Roads,Completed,NH-ANNA NAGAR,100,990000,"IMPROVEMENTS TO THE CEMENT CONCRETE ROAD AT NSK NAGAR 1ST STREET IN DN-100,UNIT-22,ZONE-8",Own Sources,8,2014-15,2018-19 NH/2014-15/18294,Buildings,Completed,NH-ANNA NAGAR,100,990000,"IMPROVEMENTS WORK AT AL BLCOK PLAY GROUND IN DN-100,UNIT-22,ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/2384,Road Cut,Completed,NH-ANNA NAGAR,100,517000,"ATTENDING ROAD CUT PATCH WORK WITH WET MIX MACADAM AT VARIOUS STREET IN DIVISION-100,UNIT-22,ZONE-VIII.",Own Sources,8,2014-15,2017-18 NH/2014-15/29059,Buildings,Completed,NH-ANNA NAGAR,100,999000,"Providing S S handrail for bridge at naduvankarai (west side) in division-100,unit-22, zone-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/29060,Buildings,Completed,NH-ANNA NAGAR,100,999000,"Providing S S handrail for bridge at naduvankarai (east side) in division-100,unit-22, zone-08.",Own Sources,8,2014-15,2016-17 BR/2014-15/29988,Roads,Completed,BR-Bus Route Roads,101,26200000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Anna Nagar 2nd Avenue From the Junction of Anna Nagar 1st Avenue to the Junction of F Block 5th Street in Ward-101 Zone 8,Grants,8,2014-15,2016-17 L/2014-15/28227,Electrical,Completed,L-Electrical,101,2623900,PROVISION OF LAMP POST,Own Sources,8,2014-15,2016-17 L/2014-15/28237,Electrical,Completed,L-Electrical,101,3366400,PROVISION OF LAMP POST AT H and J BLOGS AND ROYAL ENCLAVE,Own Sources,8,2014-15,2016-17 NH/2014-15/11381,Roads,Completed,NH-ANNA NAGAR,101,51000,"PROVIDING MOTOR ARRANGEMENTS AT BOGANVILLA PARK IN DN-101,U-22,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/12017,Parks,Completed,NH-ANNA NAGAR,101,845000,"ANNUAL MAINTENANCE OF BOUGAINVILLA PARK,C BLOCK PARK,2 nd MAIN ROAD PARK AT DN.101,U-22,Z-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/15998,Buildings,Completed,NH-ANNA NAGAR,101,630000,CONSTRUCTION OF DE COMPOSING YARD AT VELAGADU PURIAL GROUND DN- 101 UNIT- 22 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/17157,Buildings,Completed,NH-ANNA NAGAR,101,999000,CONSTRUCTION OF R C C ROOF BUILDING-AT AMMA AUTITORIUM IN DIVISION101 UNIT-22 ZONE-08,Own Sources,8,2014-15,2017-18 NH/2014-15/17471,Parks,Completed,NH-ANNA NAGAR,101,547000,"Providing Stainless Steel Play Apparatus to C Block Park Inn Div :- 101 Unit :-22, Zone:- VIII",Own Sources,8,2014-15,2016-17 NH/2014-15/17738,Parks,Completed,NH-ANNA NAGAR,101,767000,"Improvement to Park At C Block In Division 101, Unit 22, Zone 08",Own Sources,8,2014-15,2016-17 NH/2014-15/28041,Roads,Completed,NH-ANNA NAGAR,101,990000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER WITH CAMBER CORRECTION AT M BLOCK 8TH STREET IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/28042,Roads,Completed,NH-ANNA NAGAR,101,995000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER WITH CAMBER CORRECTION AT M BLOCK 9TH STREET IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/28043,Roads,Completed,NH-ANNA NAGAR,101,992000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER WITH CAMBER CORRECTION ATM BLOCK 10TH STREET IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/28044,Roads,Completed,NH-ANNA NAGAR,101,500000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER WITH CAMBER CORRECTION AT GANDHIJI STREET IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/31428,Buildings,Completed,NH-ANNA NAGAR,101,88500,"PROVIDING FENCING FOR TENNIS PLAY GROUND IN DN-101,U-22,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/31495,Buildings,Completed,NH-ANNA NAGAR,101,127000,"PROVIDING 3 PHASE IP565.5 HP AIR COMPRESSOR MOTOR AND FIXING PIPE LINE AT LORRY STATION IN DN-101,U-22,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/31496,Buildings,Completed,NH-ANNA NAGAR,101,52500,"PROVIDING BORING ARRANGEMENT AT VELANKADU BURIAL GROUND IN DN-101,U-22,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/9361,Buildings,Completed,NH-ANNA NAGAR,101,145000,"REPAIRING AND IMPROVEMENT WORK AT AMMA ARANGAM IN DN-101,U-22,Z-08",Own Sources,8,2014-15,2016-17 NH/2014-15/9919,Storm Water Drain,Completed,NH-ANNA NAGAR,101,70000,"DESILTING OF SWD AT B-BLOCK 6TH STREET IN DN-101 , U-22 , Z-08",Own Sources,8,2014-15,2016-17 BR/2014-15/29978,Roads,Completed,BR-Bus Route Roads,102,33252000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Pulla Avenue From the Junction of Periyar EVR Salai to the Junction of Anna Nagar 1st Avenue in Ward-102 Zone 8,Grants,8,2014-15,2016-17 BR/2014-15/30074,Roads,Completed,BR-Bus Route Roads,102,39442000,"Strengthening and Relaying the Bus Route Road with DBM and CBC after cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at New Avadi Road from the junction of Periyar EVR salai to the junction of Kipauk Garden Road and from the junction of Anna Nagar 3rd Avenue to the junction of Chakaravarathi Nagar, Division 101 &103, Zone - VIII",Grants,8,2014-15,2016-17 L/2014-15/28165,Electrical,Completed,L-Electrical,102,1089200,"Erection of 29nos of 6mtr GI Lamp post (Hot dip zinc galvanising) with 40w to 50w LED Fittings Removal of 25 nos Rusted short post Laying of 2x16 sqmm Alu UG Cable 1134mtr at Guji main road and Kumaran Nagar in Divison-102,Zone-VIII Area.",Own Sources,8,2014-15,2016-17 L/2014-15/28170,Electrical,Completed,L-Electrical,102,1629600,"Erection of 44 nos of 6mtr G I Lamp post (Hot dip zinc Galvanising) with 40w to 50w LED Fittings, Removal of 44nos Rusted and short post and Laying of 2x16 Sqmm UG Cable 1673 mtr at Outer circle road ,Inner circle road,N street & I Street in Division-102,Zone-VIII Area.",Own Sources,8,2014-15,2016-17 L/2014-15/28190,Electrical,Completed,L-Electrical,102,827400,"Erection of 6 nos G I Lamp post (Hot dip zinc Galvanising ) and Removal of 4nos of short post Relaying of 1829mtr 2x25 sqmm alu UG Cable in Kathiravan colony and Gajalakshmi Colony 1st street to 3rd street in Division-102,Zone -VIII Area.",Own Sources,8,2014-15,2016-17 L/2014-15/28457,Electrical,Completed,L-Electrical,102,1205400,"Erection of 29 nos of 6mtr G.I Lamp post (Hot dip zinc Galvanising) with 40w to 50w LED Fittings Removal of 22nos rusted short post and laying of 2x16 Sqmm alu U.G Cable 1065 mtr at G-Block 9th street,10th street and 12th street & 2nd Avenue extn.Dn-102 Zone-VIII area.",Own Sources,8,2014-15,2016-17 L/2014-15/28465,Electrical,Completed,L-Electrical,102,657900,"Erection of 7nos of G.I Lamp post (Hot dip zinc Galvanising) with Relaying of 1325 mtr 2x25 sqmm alu.U.G Cable in Manjakollai street and Thiruveethiamman koil 1st to 3rd street Removal of 7nos rusted and short post in Division-102,Zone-VIII area",Own Sources,8,2014-15,2016-17 NH/2014-15/20337,Buildings,Completed,NH-ANNA NAGAR,102,999000,"Proposed construction of sump, stage for CPS manjakollai in Dn-102,Unit-23,Zone-08.",Own Sources,8,2014-15,2017-18 NH/2014-15/22307,Buildings,Completed,NH-ANNA NAGAR,102,999000,"Painting work to out side Of J.J Indoor Stadium At Play Ground Street In Division 102, Unit 23, Zone 08.",Own Sources,8,2014-15,2016-17 NH/2014-15/25752,Roads,Completed,NH-ANNA NAGAR,102,142000,"Providing missing manhole doors at various street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/27538,Buildings,Completed,NH-ANNA NAGAR,102,999000,"Painting and Water Supply Works to CGHSS Pulla avenue DN-102,UNIT-23,ZONE-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/27858,Roads,Completed,NH-ANNA NAGAR,102,1875000,"Laying of CC Road with RMC M30 grade at Gajalakshmi Colony 1st Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/27960,Roads,Completed,NH-ANNA NAGAR,102,1595000,"Laying of CC Road with RMC 30 grade at Gajalakshmi Colony 2nd street in Dn-102, Unit-23, Zone-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/27969,Roads,Completed,NH-ANNA NAGAR,102,1680000,"Laying of CC Road with RMC M30 grade at Gajalakshmi Colony 3rd Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/29472,Parks,Completed,NH-ANNA NAGAR,102,925000,"Improvements to the existing park at G'Block in Dn-102, Unit-23, Zone-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/30203,Buildings,Completed,NH-ANNA NAGAR,102,840000,"Construction of Baby Toilet and Improvements to NNMP Shed No.106 at TP Chathiram 23rd Cross Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/30588,Buildings,Completed,NH-ANNA NAGAR,102,510000,"Providing Electrical arrangements to Amma Unavagam phase 2 at V.S.Puram in Dn-102, Unit-23, Zone-08.",Own Sources,8,2014-15,2016-17 NH/2014-15/3626,Buildings,Completed,NH-ANNA NAGAR,102,3600000,"ADDITIONAL CONSTRUCTION OF FIRST FLOOR FOR UPGRADIATION OF THE EXISTING HEALTH POST INTO URBAN PRIMARY HEALTH CENTER AT PULLA AVENUE IN DN-102,U-23,Z-VIII.",Own Sources,8,2014-15,2016-17 NH/2014-15/7471,Buildings,Completed,NH-ANNA NAGAR,102,225000,"Providing of Rental modular Toilet on contract basis and maintenance for one year at inside of G Block park, Shenoy Nagar in Dn-102, Unit-23, Zone-08.",Own Sources,8,2014-15,2017-18 RC/2014-15/3939,Roads,Completed,RC-Regional office - Central,102,3450000,"Proposed Construction 3 Nos of Modern Stainless Steel Bus Shelters at (Kamaraj Bhavan) Aminjikarai,New Avadi Road (TNHB Complex), Periyar EVR Salai,( opp to Ega theatre) in Dn.102 & 103,Zone-8",MLACDS,8,2014-15,2016-17 RC/2014-15/6466,Roads,Completed,BR-Bus Route Roads,102,1740000,"Proposed construction of Granite Kerb Centre Median at Pulla Avenue (from the JN of E.V.R Salai to the JN of T.V.K park) in Ward-102,Zone-8",Own Sources,8,2014-15,2016-17 BR/2014-15/30562,Roads,Completed,BR-Bus Route Roads,103,4162000,Relaying the Road With CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Flowers Road From the Junction of Periyar EVR Salai to the Junction of Dr.Alagappa Road Ward 103 Zone 8,Grants,8,2014-15,2016-17 NH/2014-15/11555,Roads,Completed,NH-ANNA NAGAR,103,990000,PROVIDING AND LAYING SPEED BREAKERS AT VARIOUS STREET IN DN-103 UNIT-23 ZONE-08.,Own Sources,8,2014-15,2016-17 NH/2014-15/22704,Roads,Completed,NH-ANNA NAGAR,103,950000,"LAYING CEMENT CONCRETE ROAD AT POLICE QUARTERS ROAD IN DN -103,UNIT-23,ZONE-8.",Own Sources,8,2014-15,2016-17 S/2014-15/12328,Footpath,Completed,BR-Bus Route Roads,103,17800000,"FORMING FOOTPATH AT MILLERS ROAD FROM THE JUNCTION OF ORMES ROAD TO THE JUNCTION OF PURASAWAKKAM HIGH ROAD IN DN 103, ZONE VIII.",Grants,8,2014-15,2017-18 S/2014-15/12665,Footpath,Completed,BR-Bus Route Roads,103,22000000,"FORMING FOOTPATH AT BARNABY ROAD FROM JN. OF PERIYAR SALAI TO JN. OF ORMES ROAD IN DN103, ZONE 8.",Grants,8,2014-15,2017-18 BR/2014-15/29963,Roads,Completed,BR-Bus Route Roads,104,14054000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Purasawakkam High Road From the Junction of Bricklin Road to the Junction of Gangadeeswarar Kovil Street in Ward-104 Zone 8,Grants,8,2014-15,2016-17 BR/2014-15/29987,Roads,Completed,BR-Bus Route Roads,104,6500000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Raja Annamalai Road From Junction of Periyar EVR Salai to the Junction of Dr.Alagappa Road Ward 104 Zone 8,Grants,8,2014-15,2016-17 BR/2014-15/30012,Roads,Completed,BR-Bus Route Roads,104,9823000,Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Dr Alagappa Road From the Junction of Raja Anna Malai Road To the Junction of Fiowers Road in Ward 104 Zone 8,Grants,8,2014-15,2016-17 NH/2014-15/19036,Roads,Completed,NH-ANNA NAGAR,104,740000,PROVIDING AND LAYING SPEED BREAKERS AT VARIOUS STREET IN DN-104 UNIT-23 ZONE-08.,Own Sources,8,2014-15,2016-17 NH/2014-15/21434,Parks,Completed,NH-ANNA NAGAR,104,740000,"CONSTRUCTION OF NEW ROADSIDE PARK AT SUNDARAM LANE AND MUTHIAL STREET IN DN 104, UNIT 23,ZONE VIII",Own Sources,8,2014-15,2016-17 NH/2014-15/27935,Roads,Completed,NH-ANNA NAGAR,104,586000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT GRAMA STREET IN DN-104,UNIT-23,ZONE-VIII",Own Sources,8,2014-15,2016-17 NH/2014-15/31123,Parks,Completed,NH-ANNA NAGAR,104,762000,"CONSTRUCTION OF NEW ROADSIDE PARK AT SARAVANA PERUMAL STREET AND PULLPAURAM MAIN ROAD IN DN 104,UNIT 23,ZONE VIII",Own Sources,8,2014-15,2016-17 S/2014-15/12324,Footpath,Completed,BR-Bus Route Roads,104,20800000,FORMING FOOTPATH AT GANGADEESWARAR KOIL STREET (FROM THE JUNCTION OF PURASAWAKKAM HIGH ROAD TO THE JUNCTION OF Dr ALAGAPPA ROAD) IN DN 104 ZONE VIII,Grants,8,2014-15,2017-18 BR/2014-15/30052,Roads,Completed,BR-Bus Route Roads,105,15211000,Strengthening and Relaying the Bus Route Road with DBM and CBC after cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Razak Garden Main Road ( From the JN of Periyar EVR Salai to the JN of Water Tank Mani Road Ward-105 Zone-8,Grants,8,2014-15,2016-17 NH/2014-15/16960,Roads,Completed,NH-ANNA NAGAR,105,969000,"LAYING CEMENT CONCERT ROAD AT KALKI NAGAR 1ST STREET IN DIVISION 105, UNIT 22, ZONE 8.",Own Sources,8,2014-15,2016-17 NH/2014-15/19576,Roads,Completed,NH-ANNA NAGAR,105,119000,"LAYING CEMENT CONCRETE ROAD AT PANCHALIAMMAN KOIL LANE IN DIVISION 105, UNIT 22, ZONE 8.",Own Sources,8,2014-15,2016-17 NH/2014-15/20627,Buildings,Completed,NH-ANNA NAGAR,105,710000,"SUPPLYING AND FIXING OF NAMMA TOILET WITH OUT SEWERAGE RGE.WOMEN -1, REG.MEN-1, URINAL 1 AT LOCATION 1, VINAYAGAPURAM MAIN ROAD IN DN-105,UNIT-22,ZONE-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/23675,Buildings,Completed,NH-ANNA NAGAR,105,1929000,"Construction of ICDS center new no:33603040109 at Pandayan street D-Block mmda colony in division-105, unit-22, zone-8 under MLA Fund",MLACDS,8,2014-15,2016-17 NH/2014-15/24331,Buildings,Completed,NH-ANNA NAGAR,105,993000,"PROVIDING BARRICADING WORKS AROUND THE TRANSFORMER AT ARUMBAKKAM VARIOUS STREET IN DN.105, UNIT.22, ZONE.8",Own Sources,8,2014-15,2016-17 NH/2014-15/25199,Buildings,Completed,NH-ANNA NAGAR,105,1912000,"Construction of ICDS center new no:33603040110 at E-BLOCK 5th cross street, MMDA colony in division-105, unit-22, zone-8 (MLA Fund 2015-16)",MLACDS,8,2014-15,2017-18 NH/2014-15/25242,Buildings,Completed,NH-ANNA NAGAR,105,951000,"PROVIDING PLAY APPARTUS AND OUTER FITTINGS AT CORPORATION PARK IN DN - 105, UNIT - 22, ZONE - 8.",Own Sources,8,2014-15,2016-17 NH/2014-15/27924,Roads,Completed,NH-ANNA NAGAR,105,916000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT POLICE STATION STREET AT M.M.D.A COLONY IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2017-18 NH/2014-15/27959,Roads,Completed,NH-ANNA NAGAR,105,428000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT POLICE STATION CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2017-18 NH/2014-15/27965,Roads,Completed,NH-ANNA NAGAR,105,2156000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT AMBEDKAR NAGAR IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2017-18 NH/2014-15/28501,Buildings,Completed,NH-ANNA NAGAR,105,990000,"IMPROVEMENTS TO FRIENDLY TOILET FOR DISABLED AT PERUMAL KOIL STREET AND IMPROVEMENTS IN KALKI NAGAR MAIN ROAD PARK IN DIVISION-105, UNIT-22, ZONE-08",Own Sources,8,2014-15,2016-17 NH/2014-15/29205,Roads,Completed,NH-ANNA NAGAR,105,800000,"ATTENDING ROAD CUT PATCH WORK AT VINAYAGAPURAM 3RD STREET AND KAMALA NEHRU NAGAR 1ST STREET IN DIV-105,UNIT-22,ZONE-8.",Deposit Works,8,2014-15,2016-17 NH/2014-15/9192,Buildings,Completed,NH-ANNA NAGAR,105,229000,"Providing of Rental modular Toilet on contract basis and maintenance for one year at MMDA Colony main road in division-105, unit-22, zone-8.",Own Sources,8,2014-15,2017-18 RC/2014-15/13722,Buildings,Completed,B-Buildings,105,36448277,"CONSTRUCTION OF COMMUNITY CENTRE AT MMDA COLONY MAIN ROAD,ARUMBAKKAM IN DN-105,UNIT-22,ZONE-.8",Own Sources,8,2014-15,2016-17 L/2014-15/27588,Electrical,Completed,L-Electrical,106,475300,"PROVISION OF 14 NOS OF 6MTR G.I.LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W TO 50W LED FITTINGS C.SET AT SOUTH KASAR THOTTAM , WEST KASASR THOTTAM, NALLA MUTHUMARIAMMAN KIOL STREET IN VARIOUS STREETS PLACES IN DIV-106,ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/12772,Buildings,Completed,NH-ANNA NAGAR,106,992000,PROVIDING RAIN WATER HARVESTING NELSANMANIKAM ROAD @ VARIOUS PLEASES IN DN 106 U 22 Z 8,Own Sources,8,2014-15,2017-18 NH/2014-15/12774,Storm Water Drain,Completed,NH-ANNA NAGAR,106,992000,PROVIDING RAIN WATER HARVESTING AMINJIKARAI @ VARIOUS STREETS IN DN 106 U 22 Z 8,Own Sources,8,2014-15,2016-17 NH/2014-15/13743,Storm Water Drain,Completed,NH-ANNA NAGAR,106,378000,"SUPPLYING AND FIXING OF FRC DOORS AT VARIOUS STREETS IN DN-106,U-22,Z-8",Own Sources,8,2014-15,2017-18 NH/2014-15/13751,Footpath,Completed,NH-ANNA NAGAR,106,995000,"REPAIRS AND IMPROVEMENTS TO FOOT PATH AT RAILWAY COLONY 2nd STREET AND EXTN IN DN-106,U-22,Z-8",Own Sources,8,2014-15,2016-17 NH/2014-15/13972,Storm Water Drain,Completed,NH-ANNA NAGAR,106,996000,REPAIRS AND IMPROVMENTS EXSTING STROWM WATER DRAIN AND FOOTPATH @ M.H COLONY 1ST CROSS 2ND 3RD 2ND MAIN ROAD INDHRAGANTHI STREET 1ST 2ND 3RD 4TH ST 5TH ST IN DN 106 UNIT 22 ZONE 8,Own Sources,8,2014-15,2016-17 BR/2014-15/30014,Roads,Completed,BR-Bus Route Roads,107,26050000,Strengthening and Relaying the Bus Route Road with DBM and CBC after cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Mayor Ramanathan Salai From the JN of Mc Nichols Road to the JN of East Ramanathan Salai Division 107 & Zone - VIII,Grants,8,2014-15,2016-17 L/2014-15/28139,Electrical,Completed,L-Electrical,107,2311100,"Erection of 68nos of 6mtr GI Lamp post (Hot dip Galvanising ) with 40w to 50w LED Fittings Removal of 68 nos Rusted short post and laying of 2314mtr 2x16 sqmm Alu.UG Cable at Nowroji road and Gurusamy Road in Division -107,Zone-VIII Area.",Own Sources,8,2014-15,2016-17 L/2014-15/28153,Electrical,Completed,L-Electrical,107,995000,Erection of 21nos 6mtr GI Octagonal Lamp post with 90w to 120 LED Fittings Removal of 21nos Rusted short post and laying of 679mtr 4x16 sqmm alu UG Cable at Mec-Nicholes road Old Zonal Office side in Division-107 Zone-VIII area.,Own Sources,8,2014-15,2016-17 L/2014-15/28248,Electrical,Completed,L-Electrical,107,704000,"Erection of 20nos 6mtr G.I.Lamp post with single straight bracket with 40w to 50w LED Fittings Laying 2x16 Sqmm Alu.UG Cable 637mtr Removal of 12 nos rusted short lamp post at Dobby Gana and Pillaiyar koil street in Division-107,Zone-VIII Area.",Own Sources,8,2014-15,2016-17 NH/2014-15/16000,Buildings,Completed,NH-ANNA NAGAR,107,850000,"PROVIDING MODERNIZED ICDS CENTERS AT SUBARAYAN STREET FOR (4 CENTERES), IN WARD 107 UNIT23 ZONE 8",Own Sources,8,2014-15,2016-17 NH/2014-15/16079,Buildings,Completed,NH-ANNA NAGAR,107,850000,"PROVIDING MODERNIZED ICDS CENTERS AT 14,SCHOOL ROAD 27,SCHOOL ROAD MC NICHOLS ROAD FOR DIV-107 UNIT-23 ZONE-8",Own Sources,8,2014-15,2016-17 NH/2014-15/1647,Buildings,Completed,NH-ANNA NAGAR,107,900000,Proposed Construction Of Modern Public Convenience at rear side of Pillalayar Koil Street inside dobhikhanaa in Division 107 Unit 23 Zone 8.,Own Sources,8,2014-15,2016-17 NH/2014-15/18011,Buildings,Completed,NH-ANNA NAGAR,107,915000,IMPROVEMENT TO C.H.S.SCHOOL REST ROOM AT SUBBARAYAN IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/26603,Buildings,Completed,NH-ANNA NAGAR,107,998000,CONSTRUCTION OF ADDITIONAL ROOM FOR GYM AT PLAY GROUND IN MAYOR RAMANATHAN SALAI IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/26616,Roads,Completed,NH-ANNA NAGAR,107,965000,LAYING INTER LOCKING BLOCKS AT HARRINGTON ROAD 15th AVENUE IN DIVISION 107 UNIT 23 ZONE 8,Own Sources,8,2014-15,2016-17 NH/2014-15/27481,Roads,Completed,NH-ANNA NAGAR,107,999000,LAYING CC ROAD WITH USING M40 GRADE AT HARRINGTON ROAD 15th AVENUE FROM 0 TO 80M IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/27506,Roads,Completed,NH-ANNA NAGAR,107,999000,LAYING CC ROAD WITH USING M40 GRADE FROM 160M TO 240M AT HARRINGTON ROAD 15TH AVENUE IN DIVISION 107 UNIT 23 ZONE 8,Own Sources,8,2014-15,2016-17 NH/2014-15/27915,Roads,Completed,NH-ANNA NAGAR,107,640000,RELAYING THE CEMENT CONCRETE ROAD WITH M30 GRADE AT BRINDAVANAM 2nd STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/27919,Roads,Completed,NH-ANNA NAGAR,107,760000,IMPROVEMENT TO INTERIOR ROAD APPA RAO GARDEN 1st CROSS STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/27977,Roads,Completed,NH-ANNA NAGAR,107,904000,RELAYING THE CEMENT CONCRETE ROAD WITH M30 GRADE AT BRINDAVANAM 3rd STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28012,Roads,Completed,NH-ANNA NAGAR,107,910000,RELAYING OF C.C. ROAD WITH M 30 GRADE CEMENT CONCRETE AT BRINDAVANAM 4th STREET IN-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28013,Roads,Completed,NH-ANNA NAGAR,107,615000,RELAYING OF C.C ROAD.WITH M 30 CEMENT CONCRETE AT BRINDAVANAM 5th STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28016,Roads,Completed,NH-ANNA NAGAR,107,697000,RELAYING OF C.C. ROAD WITH M30 GRADE CEMENT CONCRETE AT BRINDAVANAM CROSS STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28018,Roads,Completed,NH-ANNA NAGAR,107,504000,IMPROVEMENT TO INTERIOR ROAD AT APPO RAO GARDEN 2nd CROSS STREET AND 3rd STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28026,Roads,Completed,NH-ANNA NAGAR,107,666500,IMPROVEMENT TO INTERIOR ROAD AT APPO RAO GARDEN 4th STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28028,Roads,Completed,NH-ANNA NAGAR,107,666500,IMPROVEMENT TO INTERIOR ROAD AT APPO RAO GARDEN 5th STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28047,Roads,Completed,NH-ANNA NAGAR,107,550000,IMPROVEMENT TO INTERIOR ROAD AT APPO RAO GARDEN 6th STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28058,Roads,Completed,NH-ANNA NAGAR,107,820000,IMPROVEMENT TO INTERIOR ROAD AT APPO RAO GARDEN MAIN ROAD IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/28988,Buildings,Completed,NH-ANNA NAGAR,107,639000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND ELECTRICAL ARRANGEMENTS TO VARIOUS IRON SHEDS INSIDE DHOBHIKANA AT PILLAIYAR KOIL STREET IN DN-107, UNIT-23,ZONE-VIII",Own Sources,8,2014-15,2016-17 NH/2014-15/5163,Buildings,Completed,NH-ANNA NAGAR,107,2950000,CONSTRUCTION OF MULTIPURPOSE HALL AT SCHOOL ROAD IN WARD 107 UNIT 23 ZON E 8,Own Sources,8,2014-15,2016-17 L/2014-15/11124,Electrical,Completed,E-Education,108,401700,"WORK:Electrification of Dameged wiring,Tube Light Fittings and Celling Fans at Corporation High School, N Block,and corporation primary school , O, Block, corporation middle school,C.BLOCK, Division-105, 108, Zone Vlll.",Own Sources,8,2014-15,2016-17 NH/2014-15/12955,Buildings,Completed,NH-ANNA NAGAR,108,997000,PROVIDING RAIN WATER HARCESTING WELL FOR CORPORATION BULDINGS AND WATER STAGNATION LOCATIONS AT VARIOUS STREET IN DN 108 U 22 Z 8,Own Sources,8,2014-15,2016-17 NH/2014-15/18546,Storm Water Drain,Completed,NH-ANNA NAGAR,108,987000,"PROVIDING SILT CATCH PIT AT VARIOUS STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2014-15,2016-17 NH/2014-15/19032,Roads,Completed,NH-ANNA NAGAR,108,775000,"RELAYING THE ROAD WITH BCCMP 40mm THICK BY PAVER FINISHER AT SAMAYAPURATHUAMMAN STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/19141,Electrical,Completed,NH-ANNA NAGAR,108,581000,"IMPROVEMENTS TO DIVISION OFFICE AND PROVIDING SHED FOR STORE ROOM ON SECOND FLOOR DIVISION OFFICE BUILDING AT M.G.R. 3RD STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2014-15,2017-18 NH/2014-15/20098,Buildings,Completed,NH-ANNA NAGAR,108,998000,"DESIlTING STROM WATER DRAIN AT H BLOCKS,E BLOCK 1ST,2ND,3RD STREET IN DN-101,U-22,Z-8.",Own Sources,8,2014-15,2016-17 NH/2014-15/21597,Buildings,Completed,NH-ANNA NAGAR,108,984000,"PROVIDING BARRICADING WORKS AROUND THE TRANSFORMER AT VARIOUS STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2014-15,2016-17 NH/2014-15/21598,Parks,Completed,NH-ANNA NAGAR,108,927000,"IMPROVEMENTS TO ROAD SIDE PARK AT SIDCO NAGAR 1ST STREET AND WATER TANK ROAD IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2014-15,2016-17 NH/2014-15/24496,Roads,Completed,NH-ANNA NAGAR,108,636000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT RAJAGOPALAN STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2017-18 NH/2014-15/24498,Roads,Completed,NH-ANNA NAGAR,108,2660000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT VINAYAGAR KOIL STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2017-18 NH/2014-15/24722,Buildings,Completed,NH-ANNA NAGAR,108,676000,"PROPOSED CONSTRUCTION OF SI ROOM ON SECOND FLOOR AT DIVISION OFFICE IN MGR STREET IN DN-108,U-22,Z-8",Own Sources,8,2014-15,2016-17 NH/2014-15/27483,Roads,Completed,NH-ANNA NAGAR,108,999500,LAYING CC ROAD WITH USING M40 GRADE AT HARRINGTON ROAD 15th AVENUE FROM 80M TO 160M IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2014-15,2016-17 NH/2014-15/27874,Roads,Completed,NH-ANNA NAGAR,108,680000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT RATHINAMMAL 2ND STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2017-18 NH/2014-15/27883,Roads,Completed,NH-ANNA NAGAR,108,923000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT RATHINAMMAL COLONY 1ST STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2014-15,2017-18 NH/2014-15/9349,Buildings,Completed,NH-ANNA NAGAR,108,229000,"Providing of Rental modular Toilet on contract basis and maintenance for one year at O-Block main road in Division-108, Unit-22, Zone-8..",Own Sources,8,2014-15,2017-18 NJ/2014-15/20099,Buildings,Completed,NJ-TEYNAMPET,109,657000,"DEMOLITION AND RECONSTRUCTION OF COMPOUNT WALL CPS AT EAST NAMASIVAYAPURAM in DN-109,U-24,Z-9",Own Sources,9,2014-15,2018-19 NJ/2014-15/25202,Parks,Completed,NJ-TEYNAMPET,109,460000,"ANNUAL MAINTENANCE OF GILL NAGAR PARK(TWO YEARS) AT GILL NAGAR CENTRAL SCHOOL ROAD ( TWO YEARS ) IN DIVISION -109, UNIT-24, ZONE-IX.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28247,Roads,Completed,NJ-TEYNAMPET,109,383000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 1ST STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28249,Roads,Completed,NJ-TEYNAMPET,109,1217000,IMPROVEMENT TO C.C.ROAD AT WEST NAMACHIVAYA PURAM 1ST STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28252,Roads,Completed,NJ-TEYNAMPET,109,1060000,IMPROVEMENT TO C.C.ROAD AT INBARAJAPURAM 2ND STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28269,Roads,Completed,NJ-TEYNAMPET,109,835000,IMPROVEMENT TO C.C.ROAD AT VADA AGARAM 1 ST STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28355,Roads,Completed,NJ-TEYNAMPET,109,426000,IMPROVEMENT TO C.C.ROAD AT WEST NAMACHIVAYA PURAM 1ST LINK STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28356,Roads,Completed,NJ-TEYNAMPET,109,134000,IMPROVEMENT TO C.C.ROAD AT WEST NAMACHIVAYA PURAM 2ND CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28357,Roads,Completed,NJ-TEYNAMPET,109,164000,IMPROVEMENT TO C.C.ROAD AT WEST NAMACHIVAYA PURAM 4TH CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28359,Roads,Completed,NJ-TEYNAMPET,109,178000,IMPROVEMENT TO C.C.ROAD AT WEST NAMACHIVAYA PURAM 6TH CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28360,Roads,Completed,NJ-TEYNAMPET,109,141000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 1ST CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28362,Roads,Completed,NJ-TEYNAMPET,109,141000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 2ND CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28363,Roads,Completed,NJ-TEYNAMPET,109,141000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 3RD CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28364,Roads,Completed,NJ-TEYNAMPET,109,106000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 4TH CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28366,Roads,Completed,NJ-TEYNAMPET,109,138000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 5TH CROSS STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28367,Roads,Completed,NJ-TEYNAMPET,109,396000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 2ND STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28369,Roads,Completed,NJ-TEYNAMPET,109,402000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM 3RD STREET IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28371,Roads,Completed,NJ-TEYNAMPET,109,397000,IMPROVEMENT TO C.C.ROAD AT EAST NAMACHIVAYA PURAM LINK ROAD IN DIV.109 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/29035,Roads,Completed,NJ-TEYNAMPET,109,1643000,"Relaying of road with BCCMP 40mm thick at Kamdhar Nagar 1ST street in div.110,Unit-24, zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29036,Roads,Completed,NJ-TEYNAMPET,109,1249000,"Relaying of road with BCCMP 40mm thick at Kamdhar Nagar 2nd street in div.110,Unit-24, zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29053,Roads,Completed,NJ-TEYNAMPET,109,232000,"IMPROVEMENT OF CEMENT CONCRETE ROAD AT WEST NAMACHIVAYA PURAM 1ST CROSS STREET IN DIVISION-109, UNIT-24,ZONE-09",Own Sources,9,2014-15,2017-18 NJ/2014-15/29066,Roads,Completed,NJ-TEYNAMPET,109,119000,"IMPROVEMENT TO CC ROAD AT EAST NAMA CHIVAYA PURAM 5TH CROSS STREET IN DIV-109 , U-24 ,Z-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/29067,Roads,Completed,NJ-TEYNAMPET,109,456000,"IMPROVEMENT TO CC ROAD AT WEST NAMACHIVAYA PURAM 3RD LINK ROAD IN DIV-109 , U-24 . Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29073,Roads,Completed,NJ-TEYNAMPET,109,972000,"IMPROVEMENT TO CC ROAD AT EAST NAMACHIUVAYA PURAM 4TH STREET IN DIV-109 , U-24 ,Z-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/29091,Roads,Completed,NJ-TEYNAMPET,109,1854000,"RELAYING OF ROAD WITH BC 40 MM THICK AT AMEER JOHN STREET IN DIVISION -109,UNIT -24,ZONE -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29093,Roads,Completed,NJ-TEYNAMPET,109,1321000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT ARTHIREYA PURAM MARKET ROAD IN DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29096,Roads,Completed,NJ-TEYNAMPET,109,1050000,"RELAYING OF ROAD WITH BC 40 MM THICK AT THIRUVENGADA PURAM 2 ND STREET IN DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29097,Roads,Completed,NJ-TEYNAMPET,109,951000,"RELAYING OF ROAD WITH BC 40 MM THICK AT RADHAKRISHNAN NAGAR IN DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29098,Roads,Completed,NJ-TEYNAMPET,109,1413000,"RELAYING OF ROAD WITH BC 40 MM THICK AT SOUTH GANGAIAMMAN KOIL 1 ST STREET IN DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29104,Roads,Completed,NJ-TEYNAMPET,109,555000,"RELAYING OF ROAD WITH BC 40 MM THICK AT ARUNACHALAM NAGAR 1 ST AND 2ND STREET IN DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/30525,Footpath,Completed,NJ-TEYNAMPET,109,1134000,"RELAYING OF ROAD WITH BC 40 MM THICK AT SANKARAPURAM 2nd STREET IN DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/30538,Roads,Completed,NJ-TEYNAMPET,109,1936000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT KODAMBAKKAM HIGH ROAD (NORTH SERVICE ROAD) IN DIVISION-110, UNIT-24, ZONE-09.",Own Sources,9,2014-15,2017-18 NJ/2014-15/30787,Roads,Completed,NJ-TEYNAMPET,109,471000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NARAYANAPURAM 2nd STREET IN DIVISION-109,UNIT-24,ZONE-9.",Own Sources,9,2014-15,2017-18 BR/2014-15/17651,Roads,Completed,BR-Bus Route Roads,110,26239000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Sterling Road(from junction of Valluvar kottam High Road to junction of Tank Bund Road) in Dn-110, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17657,Roads,Completed,BR-Bus Route Roads,110,19310000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Valluvar Kottam High Road(from junction of Uthamar Gandhi Salai to junction of Harrington Road) in Dn-110&113, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17663,Roads,Completed,BR-Bus Route Roads,110,6702000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Sterling Avenue (from junction of Sterling Road to junction ofTank Bunt Road) in Dn-110, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17806,Roads,Completed,BR-Bus Route Roads,110,16220000,"Relaying the road with CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Mahalingapuram Main Road(from junction of 70Feet Scheme Road to junction of Tank Bund Road) in Dn-110, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/13741,Storm Water Drain,Completed,NJ-TEYNAMPET,110,997000,"IMPROVEMENTS TO STORM WATER DRAIN AT SCHOOL ROAD 1ST STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/13746,Storm Water Drain,Completed,NJ-TEYNAMPET,110,998000,"IMPROVEMENTS TO STORM WATER DRAIN AT TANK BUND ROAD FROM VALLUVAR KOTTAM HIGH ROAD TO CHAINAGE 400M SOUTHERN SIDE IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/13750,Storm Water Drain,Completed,NJ-TEYNAMPET,110,335000,"IMPROVEMENTS TO STORM WATER DRAIN AT SCHOOL ROAD FROM SCHOOL ROAD 1ST STREET TO INDEPENDENCE DAY PARK IN DIVISION 110,UNIT 24,ZONE 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/14146,Buildings,Completed,NJ-TEYNAMPET,110,997000,"PROVIDING PATHWAY AND PLATFORM AROUND THE P.C.AT VALLUVARKOTTAM HIGH ROAD NEAR INDEPENDENCE DAY PARK IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/16492,Buildings,Completed,NJ-TEYNAMPET,110,998000,CONSTRUCTION OF ADDITIONAL ROOM IN FIRST FLOOR TO DIVISION OFFICE 110 AT KUTTY STREET IN DIVISION 110 UNIT 24 ZONE 09,Own Sources,9,2014-15,2016-17 NJ/2014-15/21778,Buildings,Completed,NJ-TEYNAMPET,110,989000,"Annual Maintainance of Electrical crematorium at Nungambakkam Burial Ground in Division-110, Unit-24, Zone-IX.",Own Sources,9,2014-15,2016-17 NJ/2014-15/22029,Buildings,Completed,NJ-TEYNAMPET,110,510000,"ATTENDING REPAIR AND MAINTENANCE FOR GROUP BIN AT VARIOUS STREET IN DIVISION-110, UNIT-24, ZONE-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28372,Roads,Completed,NJ-TEYNAMPET,110,1010000,IMPROVEMENT TO C.C.ROAD AT VAIKUNDAPURAM II STREET IN DIV.110 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28373,Roads,Completed,NJ-TEYNAMPET,110,999000,IMPROVEMENT TO C.C.ROAD AT VAIKUNDAPURAM 1ST STREET IN DIV.110 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28374,Roads,Completed,NJ-TEYNAMPET,110,800000,IMPROVEMENT TO C.C.ROAD AT PUSHPANAGAR TENEMENT ROAD (INBETWEEEN T.N.S.C.B V&VIII BLOCKS) IN DIV.110 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28376,Roads,Completed,NJ-TEYNAMPET,110,227000,IMPROVEMENT TO C.C.ROAD AT PUSHPANAGAR TENEMENT ROAD (IN FRONT OF G BLOCKS) IN DIV.110 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28379,Roads,Completed,NJ-TEYNAMPET,110,1120000,IMPROVEMENT TO C.C.ROAD AT KUTTY STREET IN DIV.110 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/29034,Roads,Completed,NJ-TEYNAMPET,110,1553000,"Relaying of road with BCCMP 40mm thick at Jayalakshmipuram 4th Street in Div.110, Unit-24, Zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29041,Roads,Completed,NJ-TEYNAMPET,110,2959000,"Relaying of road with BCCMP 40mm thick at Kothari Road in Div.110, Unit-24, Zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29043,Roads,Completed,NJ-TEYNAMPET,110,706000,"Relaying of road with BCCMP 40mm thick at Ponnagi puram 1st street in Div.110, Unit-24, Zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29048,Roads,Completed,NJ-TEYNAMPET,110,579000,"Relaying of road with BCCMP 40mm thick at Ponnagi puram 2nd street in Div.110, Unit-24, Zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29069,Roads,Completed,NJ-TEYNAMPET,110,1028000,"Relaying of road with BCCMP 40mm thick at Susaipuram Main road in div.110, Unit-24, zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29103,Roads,Completed,NJ-TEYNAMPET,110,849180,"Relaying of road with BCCMP 40mm thick at Sivaganga Road (PART) in div.110,Unit-24, zone -9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29853,Roads,Completed,NJ-TEYNAMPET,110,842000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT VALLUVAR KOTTAM HIGH ROAD IN DIV-110, UNIT-24, ZONE-09",Own Sources,9,2014-15,2017-18 NJ/2014-15/7893,Buildings,Completed,NJ-TEYNAMPET,110,998000,"CONSTRUCTION OF SUMP , WATER SUPPLY, ELECTRICAL WORKS AND OTHER IMPROVEMENT WORKS TO AMMA UNAVAGAM IN DIVISION 110 OFFICE CAMPUS AT KUTTY STREET IN DIVISION-110, UNIT-24, ZONE-IX.",Own Sources,9,2014-15,2016-17 NJ/2014-15/7895,Buildings,Completed,NJ-TEYNAMPET,110,998000,"CONSTRUCTION OF AMMA UNAVAGAM IN DIVISION-110 OFFICE CAMPUS AT KUTTY STREET IN DIVISION-110, UNIT-24, ZONE-IX.",Own Sources,9,2014-15,2016-17 NJ/2014-15/7896,Buildings,Completed,NJ-TEYNAMPET,110,998000,"PROVIDING ADDITIONAL WORKS TO AMMA UNAVAGAM IN 110 DIVISION OFFICE CAMPUS AT KUTTY STREET IN DIVISION-110, UNIT-24, ZONE-IX.",Own Sources,9,2014-15,2016-17 NJ/2014-15/9070,Buildings,Completed,NJ-TEYNAMPET,110,800000,"IMPROVMENT WORKS TO AMMA UNAVAGAM IN 110 DIVISION OFFICE CAMPUS AT KUTTY STREET IN DIVISION-110, UNIT-24, ZONE-IX",Own Sources,9,2014-15,2016-17 RC/2014-15/14173,Buildings,Completed,B-Buildings,110,29500000,"CONSTRUCTION OF ADDITIONAL BLOCK(G+2) AT CGHSS,NUNGAMBAKKAM IN DN-110,ZONE IX",Own Sources,9,2014-15,2017-18 RC/2014-15/4642,Footpath,Completed,RC-Regional office - Central,110,3480000,"Proposed Construction of 3 nos of Modern Stainless Steel Bus Shelters at Dr.MGR Salai (Infront Corp.Park) and Tank Bund Road (Loyola college bus stop) in Div - 110 and G N Chetty Road (Opp.to Hotel Accord) in Div - 117, Zone - 9",MLACDS,9,2014-15,2016-17 BR/2014-15/17652,Roads,Completed,BR-Bus Route Roads,111,37648000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at College Road(from junction of Valluvar kottam High Road to junction of Greams Road) in Dn-111, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17653,Roads,Completed,BR-Bus Route Roads,111,12670000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Binny Road(from junction of Anna Salai to junction of Ethiraj Road) in Dn-111, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17654,Roads,Completed,BR-Bus Route Roads,111,29800000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Whites Road from the junction of Anna Salai to the junction of West Cott Road in Ward-111, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17655,Roads,Completed,BR-Bus Route Roads,111,28527000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Greams Road(from junction of Anna Salai to junction of College Road) in Dn-111, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/29999,Roads,Completed,BR-Bus Route Roads,111,10446000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Woods Road from the junction of Anna Salai to the junction of Thiru-Vi-Ka Road in Ward-110,Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30106,Roads,Completed,BR-Bus Route Roads,111,20877000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Haddows Road (from junction of College Road to junction of Uthamar Gandhi Road) in Dn-111, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30358,Road Cut,Completed,BR-Bus Route Roads,111,968000,"Restoration of Roadcut made by TANGEDCO at Greams Road in Dn-111, Zone-9 Reach 3.",Deposit Works,9,2014-15,2016-17 BR/2014-15/30359,Road Cut,Completed,BR-Bus Route Roads,111,968000,"Restoration of Roadcut made by TANGEDCO at Woods Road in Dn-111, Zone-9",Deposit Works,9,2014-15,2016-17 BR/2014-15/30850,Roads,Completed,BR-Bus Route Roads,111,2162000,"Proposed Construction of 2 Nos of Modern Stainless Steel Bus Shelter at Anna Salai (Near Church Park School) in Dn.111, Zone-9",MLACDS,9,2014-15,2016-17 BR/2014-15/30851,Roads,Completed,BR-Bus Route Roads,111,2162000,"Proposed Construction of 2 Nos of Modern Stainless Steel Bus Shelter at Greams Road (Towards Egmore and Parrys) in Dn.111, Zone-9",MLACDS,9,2014-15,2016-17 NJ/2014-15/22569,Roads,Completed,NJ-TEYNAMPET,111,1730000,"RELAYING OF ROAD WITH BC 40 MM THICK AT CLUB HOUSE ROAD IN DIV -111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/22970,Roads,Completed,NJ-TEYNAMPET,111,3030000,"RELAYING OF ROAD WITH BC 40 MM THICK AT PYCROFTS GARDEN ROAD IN DIVISION-111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/25249,Roads,Completed,NJ-TEYNAMPET,111,660000,"RELAYING OF ROAD WITH BC 40 MM THICK AT RUTLAND GATE 5TH STREET IN DIVISION-111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26597,Storm Water Drain,Completed,NJ-TEYNAMPET,111,237000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT GULAM ABBAS ALIGHAN 1 ST LANE IN DIV-111.UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26739,Storm Water Drain,Completed,NJ-TEYNAMPET,111,205000,"IMPROVEMENTS OF CEMENT CONCRETE ROAD AT BEGUM SAHIB 2 ND STREET IN DIV-111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26819,Buildings,Completed,NJ-TEYNAMPET,111,500000,"IMPROVEMENTS WORK OF CORPORATION PRIMARY SCHOOL IN COCHIN HOUSE AT ANDERSON ROAD IN DIV -111,UNIT-24,ZONE-09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27528,Parks,Completed,NJ-TEYNAMPET,111,190000,"SUPPLY AND FIXING OF DISPLAY BOARD FOR MAINTENANCE DETAILS ABOUT THE VARIOUS PARKS IN DIVISIONS 109,110,111,118 AND 119 UNIT-24, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28081,Roads,Completed,NJ-TEYNAMPET,111,3130000,"RELAYING OF ROAD WITH BCCMP AT 40 MM THICK AT MOORS ROAD IN DIV-111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28192,Roads,Completed,NJ-TEYNAMPET,111,900000,"IMPROVEMENT TO C.C. ROAD AT GULAM ABBAS ALIKHAN VIII IN DIV.111, UNIT.24, ZONE.9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28194,Roads,Completed,NJ-TEYNAMPET,111,255000,IMPROVEMENT TO C.C.ROAD AT GULAM ABBAS ALIKHAN VII LANE IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28195,Roads,Completed,NJ-TEYNAMPET,111,255000,"IMPROVEMENT TO C.C.ROAD AT AZIZ MULK LANE IN DIV.111, UNIT24 ZONE.9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28199,Roads,Completed,NJ-TEYNAMPET,111,490000,IMPROVEMENT TO C.C.ROAD AT GULAM ABBAS ALIKHAN II STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28201,Roads,Completed,NJ-TEYNAMPET,111,326000,IMPROVEMENT TO C.C.ROAD AT GULAM ABBAS ALIGHAN 4 TH STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28202,Roads,Completed,NJ-TEYNAMPET,111,193000,IMPROVEMENT TO C.C.ROAD AT GULAM ABBAS ALIKHAN V STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28206,Roads,Completed,NJ-TEYNAMPET,111,218000,IMPROVEMENT TO C.C.ROAD. AT GULAM ABBAS ALIKHAN VI STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28210,Roads,Completed,NJ-TEYNAMPET,111,466000,IMPROVEMENT TO C.C.ROAD AT GULAM MOHAMED MOHIDEEN STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28220,Roads,Completed,NJ-TEYNAMPET,111,405000,IMPROVEMENT TO C.C.ROAD AT KAMMALAR STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28226,Roads,Completed,NJ-TEYNAMPET,111,245000,RELAYING OF ROAD WITH BCCMP AT NEW STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/28228,Roads,Completed,NJ-TEYNAMPET,111,140000,IMPROVEMENT TO C.C.ROAD AT BEGUM SAHIB 1 ST STREET IN DIV.111 UNIT.24 ZONE.9,Own Sources,9,2014-15,2017-18 NJ/2014-15/29068,Roads,Completed,NJ-TEYNAMPET,111,2370000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SAFEE MOHAMED ROAD IN DIVISION 111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29071,Roads,Completed,NJ-TEYNAMPET,111,2290000,"RELAYING OF ROAD WITH BC 40 MM THICK AT WALLACE GARDEN 3 RD STREET IN DIVISION 111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29162,Roads,Completed,NJ-TEYNAMPET,111,340000,"RELAYING OF ROAD WITH BC 40 MM THICK AT MODEL SCHOOL LANE IN DIVISION -111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29163,Roads,Completed,NJ-TEYNAMPET,111,1110000,"RELAYING OF ROAD WITH BC 40 MM THICK AT SUNDARAM AVENUE IN DIVISION-111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29165,Roads,Completed,NJ-TEYNAMPET,111,800000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT VASAN AVENUE IN DIVISION-111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29799,Parks,Completed,NJ-TEYNAMPET,111,998000,"Provision 10 nos of 6 mtr GI lamp post with 40w LED type fitting at nungambakkam 4th lane park in division -111, unit-24, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/31745,Roads,Completed,NJ-TEYNAMPET,111,5300000,"RELAYING OF ROAD WITH BC 40 MM THICK AT AVVAI SHANMUGAM SALAI IN DIVISION-111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31746,Roads,Completed,NJ-TEYNAMPET,111,4470000,"RELAYING OF ROAD WITHBC 40 MM THICK AT KHADER NAWAS KHAN ROAD IN DIVISION 111,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/6262,Buildings,Completed,NJ-TEYNAMPET,111,520000,"MAINTENACE OF PRE FABRICATED URINAL UNITS IN DIVISION-123,124,125 & 126, UNIT-25, ZONE-9.",Own Sources,9,2014-15,2019-20 NJ/2014-15/9153,Storm Water Drain,Completed,NJ-TEYNAMPET,111,599000,"Providing Rain Water Drain and Chute Pipe Arrangements at Whites Road in Div-111, Unit-24, Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/9788,Buildings,Completed,NJ-TEYNAMPET,111,878000,"PROVIDING RENTAL MODULOR TOILET ON CONTRACT BASIS INCLUDING MAINTENANCE FOR ONE YEAR AT MODEL SCHOOL ROAD AND THOUSAND LIGHTS IN DIVISION -111,UNIT- 24,ZONE-IX.",Own Sources,9,2014-15,2017-18 NJ/2014-15/9790,Buildings,Completed,NJ-TEYNAMPET,111,878000,"PROVIDING RENTAL MODULOR TOILET ON CONTRACT BASIS INCLUDING MAINTENANCE FOR ONE YEAR AT THOUSAND LIGHTS WEST AND AND THOUSAND LIGHTS WEST DIVISION -111,UNIT- 24,ZONE-IX.",Own Sources,9,2014-15,2017-18 NJ/2014-15/9793,Buildings,Completed,NJ-TEYNAMPET,111,878000,"PROVIDING RENTAL MODULOR TOILET ON CONTRACT BASIS INCLUDING MAINTENANCE FOR ONE YEAR AT ANDERSON ROAD AND MOUNT ROAD IN DIVISION - 111,UNIT- 24,ZONE-IX.",Own Sources,9,2014-15,2017-18 S/2014-15/12292,Footpath,Completed,BR-Bus Route Roads,111,9600000,"Forming Footpath at Pattulous Road From the jn of Anna Salai to the jn of Whites Road in Div - 111, Zone 9.",Grants,9,2014-15,2017-18 S/2014-15/12429,Footpath,Completed,BR-Bus Route Roads,111,13900000,"Forming Foot path at Binny Road from the jn.of Anna Salai to the jn.of Ehiraj Salai in Div - 111, Zone -9.",Grants,9,2014-15,2017-18 NJ/2014-15/10727,Storm Water Drain,Completed,NJ-TEYNAMPET,112,1690000,"CONSTRUCTION OF SWD OF SIZE 600X750MM RCC BOX TYPE DRAIN ALONGSOWRESTRANAGAR IST STREET ( FM.CHOOLAIMEDU HIGH ROAD TO CH.149M) (UNDER MLA FUND SCHEME)IN DN-112,UNIT-26,ZONE-09",Own Sources,9,2014-15,2016-17 NJ/2014-15/15290,Road Cut,Completed,NJ-TEYNAMPET,112,324000,"Restoration of road cut made by TNEB TANGEDCO at sivan koil street.in dn112 unit.26,zone 9",Deposit Works,9,2014-15,2018-19 NJ/2014-15/15291,Road Cut,Completed,NJ-TEYNAMPET,112,315000,"Restoration of roadcut madebyTNEB TANGEDCO at sivan koil cross street in dn112,unit.26,zone.9",Deposit Works,9,2014-15,2018-19 NJ/2014-15/15292,Road Cut,Completed,NJ-TEYNAMPET,112,191000,"Restoration of roadcut made by TNEB TANGEDCO at vellala street. in dn112,unit.26,zone9",Deposit Works,9,2014-15,2018-19 NJ/2014-15/23567,Buildings,Completed,NJ-TEYNAMPET,112,456000,"Construction of baby friendly toilet and improvements to ICDC center (center no.33603040203 at varatharajan pet (CPS) in dn-112, unit-26, zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/23575,Buildings,Completed,NJ-TEYNAMPET,112,463000,"Construction of Baby Friendly Toilet and Improvements to ICDC center (center no.33603040123) at Choolaimedu High Road in dn-112,unit-26,z-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/23576,Buildings,Completed,NJ-TEYNAMPET,112,360000,"Construction of baby friendly toilet and improvements to ICDC center (center no.33603040206 and 33603040207) at Dosspuram in dn-112, unit-26, zone-9",Own Sources,9,2014-15,2018-19 NJ/2014-15/23577,Buildings,Completed,NJ-TEYNAMPET,112,450000,"Construction of baby friendly toilet and improvements to ICDC center (center no.33603040208 & 33603040209) at Chennai Middle School, Trustpuram in dn-112, unit-26, zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/23578,Buildings,Completed,NJ-TEYNAMPET,112,427000,"Construction of baby friendly toilet and improvements to ICDC center (center no.33603040210) at vellala street in dn-112, unit-26, zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/23583,Roads,Completed,NJ-TEYNAMPET,112,1317000,"Relaying of road with Bc 40mm thick at Sivan Kovil Street (part) in Division - 112, Unit - 26, Zone - 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/23584,Roads,Completed,NJ-TEYNAMPET,112,648000,"Relaying of road with Bc 40mm thick at Sivan Kovil South Street (part) in Division - 112, Unit - 26, Zone - 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/23606,Roads,Completed,NJ-TEYNAMPET,112,949000,"Relaying of road with Bc 40mm thick at Sivan Kovil Cross Street (part) in Division - 112, Unit - 26, Zone - 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/23615,Roads,Completed,NJ-TEYNAMPET,112,950000,"Relaying of road with Bc 40mm thick atDhayallu Nagar Main Road in Division - 112, Unit - 26, Zone - 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/23617,Roads,Completed,NJ-TEYNAMPET,112,353000,"Relaying of road with Bc 40mm thick at bharadeeswarer Colony 2nd Street (part) in Division - 112, Unit - 26, Zone - 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26085,Roads,Completed,NJ-TEYNAMPET,112,430000,"Improvements to Cement Concrete Road at Vellala street, 1st lane in dn - 112, unit - 26, zone - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/26088,Roads,Completed,NJ-TEYNAMPET,112,375000,"Improvements to Cement Concrete Road at Vellala street, 2nd lane in dn - 112, unit - 26, zone - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/26090,Roads,Completed,NJ-TEYNAMPET,112,600000,"Improvements to Cement Concrete Road at Gandhi street , in dn - 112, unit - 26, zone - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/26092,Roads,Completed,NJ-TEYNAMPET,112,430000,"Improvements to Cement Concrete Road at Dhayallu Nagar,1st street in dn - 112, unit - 26, zone - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/26094,Roads,Completed,NJ-TEYNAMPET,112,670000,"Improvements to Cement Concrete Road at Dhayallu Nagar, 2nd street in dn - 112, unit - 26, zone - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/26095,Roads,Completed,NJ-TEYNAMPET,112,560000,"Improvements to Cement Concrete Road at Dhayallu Nagar, 3rd street in dn - 112, unit - 26, zone - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/26100,Buildings,Completed,NJ-TEYNAMPET,112,535000,"Construction of baby friendly toilet and improvements to ICDC center (center no.33603040124) at choolaimedu high road, in dn-112, unit-26, zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/26102,Buildings,Completed,NJ-TEYNAMPET,112,380000,"Construction of baby friendly toilet and improvements to ICDC center (center no.33603040204 and 33603040205) at CPS varatharajanpet in dn-112, unit-26, zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/29820,Buildings,Completed,NJ-TEYNAMPET,112,999000,"IMPROVEMENTS TO CHEMISTRY LAB IN CHSS AT CHOOLAIMEDU HIGH ROAD IN DN-112, UNIT-26, ZONE-09",Own Sources,9,2014-15,2016-17 BR/2014-15/17656,Roads,Completed,BR-Bus Route Roads,113,52130000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Uthamar Gandhi Road(from junction of Anna Salaia to junction of Valluvar kottam High Road) in Dn-113, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/11310,Parks,Completed,NJ-TEYNAMPET,113,580000,"OUT SOURCING OF SHARMA PARK AT HABIBULLA ROAD FOR 2 YEARS IN DIV 113,U 26,Z 9 (Employed by qualified horticulturist for two years only)",Own Sources,9,2014-15,2017-18 NJ/2014-15/12884,Buildings,Completed,NJ-TEYNAMPET,113,1500000,"PROPOSED CONSTRUCTION OF DINING HALL AT CMS RAMA STREET (UNDER MLA FUND) IN DIV-113, UNIT-26, Z0NE-9",MLACDS,9,2014-15,2017-18 NJ/2014-15/13376,Footpath,Completed,NJ-TEYNAMPET,113,520000,"OUT SOURCING OF KODAMBAKKAM PARK (Near Dharmapuram) FOR 2 YEARS IN DIV 113,U 26,Z 9.(BY qualified Horticulturist only)",Own Sources,9,2014-15,2017-18 NJ/2014-15/18343,Roads,Completed,NJ-TEYNAMPET,113,861000,"RELAYING B.T ROAD AT JOSIER STREET IN DIV 113,UNIT26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/18345,Roads,Completed,NJ-TEYNAMPET,113,582000,"RELAYING B.T.ROAD AT NEW TANK STREET IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/18347,Roads,Completed,NJ-TEYNAMPET,113,898000,"RELAYING B.T.ROAD AT MELAPADI MUTHU STREET IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/18352,Roads,Completed,NJ-TEYNAMPET,113,5240000,"RELAYING B.T.ROAD AT CATHEDRAL GARDEN ROAD IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/18357,Roads,Completed,NJ-TEYNAMPET,113,1408000,"RELAYING B.T.ROAD AT DHARMAPURAM MAIN ROAD IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/18359,Roads,Completed,NJ-TEYNAMPET,113,370000,"RELAYING B.T.ROAD AT NEW COLONY GOPALA NAGAR IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19038,Roads,Completed,NJ-TEYNAMPET,113,636000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT KUMARAPPA LANE IN DIV 113, UNIT-26,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19344,Roads,Completed,NJ-TEYNAMPET,113,333000,"RELAYING OF B.T. ROAD AT NEW COLONY 2ND STREET IN DIV 113, UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19346,Roads,Completed,NJ-TEYNAMPET,113,858000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT GRAMMA 1ST STREET IN DIV 113, UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19352,Roads,Completed,NJ-TEYNAMPET,113,2810000,"RELAYING OF B.T. ROAD AT JAMBULINGAM STREET IN DIV 113, UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19353,Roads,Completed,NJ-TEYNAMPET,113,999000,"RELAYING OF B.T. ROAD AT KRISHNA STREET IN DIV 113, UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19356,Roads,Completed,NJ-TEYNAMPET,113,2527000,"RELAYING OF B.T. ROAD AT THIRUMOORTHY NAGAR MAIN ROAD IN DIV 113, UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/25495,Roads,Completed,NJ-TEYNAMPET,113,998000,"Providing Speed Breakers as per IRC design [Clause 5, 6 of IRC: 99-1988] with Bituminous Concrete (as per clause 509 of MORT&H specification) to the required grade level andalignment and rolled with vibratory roller etc., complete and as directed by Engineers and as per the plan enclosed.at various Road in div 113,unit-26,zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26209,Roads,Completed,NJ-TEYNAMPET,113,920000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT DHARMAPURAM 7TH ST IN DIV 113, U 26, Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26211,Roads,Completed,NJ-TEYNAMPET,113,2070000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT THIRUMOORTHY NAGAR 3rd ST IN DN-113,U-26,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26212,Roads,Completed,NJ-TEYNAMPET,113,1350000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT SEERANIPURAM IN DN-113,U-26,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26214/C,Roads,Completed,NJ-TEYNAMPET,113,2440000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT THIRUMOORTHY NAGAR 5TH ST IN DIV 113, U 26, Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26220,Roads,Completed,NJ-TEYNAMPET,113,1650000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT THIRUMOORTHY NAGAR 6TH ST IN DN-113,U-26,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26223,Roads,Completed,NJ-TEYNAMPET,113,540000,"LAYING CEMENT CONCRETE ROAD AT HABIBULLAH 1ST LANE IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26226,Roads,Completed,NJ-TEYNAMPET,113,1513000,"LAYING CEMENT CONCRETE ROAD AT HABIBULLAH 2ND LANE IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26227,Roads,Completed,NJ-TEYNAMPET,113,1220000,"LAYING CEMENT CONCRETE ROAD AT HABIBULLAH 3RD LANE IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26726,Roads,Completed,NJ-TEYNAMPET,113,3490000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT THIRUMOORTHY NAGAR 1ST IN DN-113,U-26,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26751,Roads,Completed,NJ-TEYNAMPET,113,4200000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT DR.THOMAS ROAD (FROM THOMAS 1ST STREET TO SOUTH BOAG ROAD AND INBETWEEN BLOCKS 1 TO 34 ) IN DIV 117, UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27144,Roads,Completed,NJ-TEYNAMPET,113,1540000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT THIRUMOORTHY NAGAR 4TH ST IN DIV 113, U 26, Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27152,Roads,Completed,NJ-TEYNAMPET,113,3525000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT THIRUMOORTHY NAGAR 2ND ST IN DIV 113, U 26, Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27177,Roads,Completed,NJ-TEYNAMPET,113,258000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT DHARMAPURAM 10TH ST IN DIV 113, U 26, Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28052,Roads,Completed,NJ-TEYNAMPET,113,2590000,"RELAYING B.T. ROAD AT KRISHNAMA ROAD IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/6744,Buildings,Completed,NJ-TEYNAMPET,113,714000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (SHE TOILET) AT HABIBULLAHA ROAD IN DIV -113,UNIT -26,ZONE -9",Own Sources,9,2014-15,2018-19 NJ/2014-15/8962,Buildings,Completed,NJ-TEYNAMPET,113,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT HABIBULLAHA ROAD IN DIV -113,UNIT -26,ZONE -9",Own Sources,9,2014-15,2018-19 NJ/2014-15/9057,Buildings,Completed,NJ-TEYNAMPET,113,878000,"Providing Rental Modulor Toilet on Contract basis including Maintanance for one year at G.N.Chetty Road and Ramakamath puram in Dn-113,U-26, Zone 9",Own Sources,9,2014-15,2017-18 NJ/2014-15/9058,Buildings,Completed,NJ-TEYNAMPET,113,878000,"Providing Rental Modulor Toilet on Contract basis including Maintanance for one year at Cathedral Garden Road and lakshmi colony in Dn-113,U-26, Zone 9",Own Sources,9,2014-15,2018-19 RC/2014-15/4649,Footpath,Completed,RC-Regional office - Central,113,3010000,"Proposed Construction of 6 nos of Modern Stainless Steel Bus Shelters at Nelson Manickam Salai (6X2.50M) in Div - 109, Dr.MGR Salai (Infront of Hotel Palmgrove) and Thirumalai(Pillai)Salai in Div -113 Zone - 9.",MLACDS,9,2014-15,2016-17 S/2014-15/12634,Footpath,Completed,BR-Bus Route Roads,113,18600000,"Forming Footpath at Thirumalai Road from the Junction of Dr.MGR Salai to the Junction of Gopathi Narayanan Salai in Dn-113,Zone-9",Grants,9,2014-15,2017-18 BR/2014-15/17665,Roads,Completed,BR-Bus Route Roads,114,44349000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Bharathi Salai (from junction of Kamarajar Salai to junction of Woods Road) in Dn-63, Zone-V & Dn-114 & 116,Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30104,Roads,Completed,BR-Bus Route Roads,114,37780000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Triplicane High Road (Quaid - e - Millath Road)(from junction of Wallajah Road to junction of Dr.Natesan Road) in Dn-114 & 116, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30105,Roads,Completed,BR-Bus Route Roads,114,18363000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Babu Jagajeevan Ram Road (from junction of Wallajah Road to junction of Bharathi Road) in Dn-114, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/14780,Roads,Completed,NJ-TEYNAMPET,114,1125000,"Re-laying the Road with Bituminious Coarse 40mm thick by paver finishing at Appavoo street in Dn-114,Unit-27, Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/14782,Roads,Completed,NJ-TEYNAMPET,114,1050000,"Re-Laying the Road with Bituminious coarse 40mm thick at Pachaiyappan Street and Pachaiyappan 1st, 2nd lane in Dn-114, Unit-27, Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/16063,Roads,Completed,NJ-TEYNAMPET,114,990000,"Re-Laying the Road with Bituminous coarse 40mm thick by Paver finishing at Lal Mohammed cross street in dn-114,Unit-27, Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/16188,Roads,Completed,NJ-TEYNAMPET,114,334000,"Re-Laying the Road with Bituminous Coarse 40mm thick at Mohammed abdulla 1st Street in Dn-114,Unit-27, Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/16189,Roads,Completed,NJ-TEYNAMPET,114,455000,"Re-Laying the Road with Bituminous Coarse 40mm thick by Paver Finishing at Mohammed abdulla 2nd Street in Dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/16191,Roads,Completed,NJ-TEYNAMPET,114,1195000,"Re-Laying the Road with Bituminous Coarse 40mm thick by Paver Finishing at OVM Street in Dn-114,Unit-27, Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/16347,Buildings,Completed,NJ-TEYNAMPET,114,795000,"Construction of new morden technology of Bio Methanisation Plant for K.G.Hospital Amma Unavagam at Victoria Hostel Road in dn-114,Unit-27, Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/17139,Roads,Completed,NJ-TEYNAMPET,114,522000,"Re-Laying the Road with Bituminous Coarse 40mm thick at Habibulla 4th Lane and Arumugappa Street in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/17982,Buildings,Completed,NJ-TEYNAMPET,114,2499000,"Out sourcing Men and Material for Cleaning of public convenience at Marina service road and Marina Swimming pool in dns.114,116 and 125,Unit-27 and Unit-25,Zone-9. (7 Location -Period 1 Year)",Own Sources,9,2014-15,2016-17 NJ/2014-15/18855,Roads,Completed,NJ-TEYNAMPET,114,1060000,"Re-Laying the Existing Cement concrete road at Mufti Amirulla (S) Street in dn-114 Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19181,Roads,Completed,NJ-TEYNAMPET,114,590000,"Improvements to the Existing Cement Concrete Road at Rice Mandy Street in dn-114, Unit-27, Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19201,Roads,Completed,NJ-TEYNAMPET,114,140000,"Improvements to the Existing Cement Concrete Road at Bharathi Lane in dn-114,Unit-27, Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19387,Roads,Completed,NJ-TEYNAMPET,114,810000,"Improvements to the Existing Cement Concrete Road at Habibulla 1,2,3rd lane in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19391,Roads,Completed,NJ-TEYNAMPET,114,430000,"Improvements to the Existing Cement Concrete Road at Khanabagh Street 1,2,3 and 4th Lanes in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19402,Roads,Completed,NJ-TEYNAMPET,114,262000,"Improvements to the Existing Cement Concrete Road at Mosque Lane in dn-114, Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19403,Roads,Completed,NJ-TEYNAMPET,114,690000,"Improvements to the Existing Cement Concrete Road at Yusuf st and Yusuf Lane in dn-114, Unit-27, Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19406,Roads,Completed,NJ-TEYNAMPET,114,1210000,"Improvements to the Existing Cement Concrete Road at Dowlathkhan Street in dn-114, Unit-27, Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19423,Roads,Completed,NJ-TEYNAMPET,114,359000,"Improvements to the Existing Cement Concrete Road at Kumarasamy Street in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19439,Roads,Completed,NJ-TEYNAMPET,114,570000,"Improvements to the Existing Cement Concrete Road at Big Mosque street and Jony basha Lane in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19442,Roads,Completed,NJ-TEYNAMPET,114,1520000,"Improvements to the Existing Cement Concrete Road at Kithabathkhan Street in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19645,Roads,Completed,NJ-TEYNAMPET,114,510000,"Improvements to the Existing Cement Concrete Road at Gurusamy Street in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19647,Roads,Completed,NJ-TEYNAMPET,114,620000,"Improvements to the Existing Cement Concrete Road at Abdul karem street in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19648,Roads,Completed,NJ-TEYNAMPET,114,880000,"Improvements to the Existing Cement Concrete Road at Abdul karem cross st and Lane in dn-114,Unit-27, Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/19876,Roads,Completed,NJ-TEYNAMPET,114,551000,"Re-Laying of Road with Bituminous Coarse 40mm thick by Paver finishing at Habbibulla cross street in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/21585,Storm Water Drain,Completed,NJ-TEYNAMPET,114,703000,"Construction of Storm water drain 90cmx90cm in Sydoji Street in Dn-114, Unit-27, Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/21587,Storm Water Drain,Completed,NJ-TEYNAMPET,114,620000,"Re-Construction of Storm water drain 0.90mx0.90m in at Babu jegageevanram Road jn.of Parthasarathi (N) Street in Dn-114, Unit-27, Zone-9(Bells Road)",Own Sources,9,2014-15,2016-17 NJ/2014-15/21749,Roads,Completed,NJ-TEYNAMPET,114,997000,"Providing and Attending Rectification(LOWERING/RAISING) of CMWSSB Manhole doors to Road level at Various places in dn-114,115,116,120 and 121,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/23228,Roads,Completed,NJ-TEYNAMPET,114,672000,"Re-Laying of road with Bituminous Coarse 40mm thick by Paver finishing at Krishnappa Street in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/25453,Buildings,Completed,NJ-TEYNAMPET,114,991000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT TYPHOON ALI KHAN STREET IN DN-114,UNIT27,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/25781,Buildings,Completed,NJ-TEYNAMPET,114,659000,"REPAIRS AND IMPROVEMENTS TO PC AT NEAR ANNA SWIMING POOL AND REAR SIDE OF M.G..R MEMORIAL IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26812,Buildings,Completed,NJ-TEYNAMPET,114,962000,"PROPOSED CONSTRUCTION OF COMPOUND WALL, GATE AND GATE PILLAR IN CMS CAMPUS AT BABU JAGAJEEVAN RAM ROAD(BELLS ROAD) IN DIV-114, U- 27, Z-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/29320,Buildings,Completed,NJ-TEYNAMPET,114,592000,"special improvements to dispensary at khana bagh street in dn-114,unit-27,zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/31715,Roads,Completed,NJ-TEYNAMPET,114,930000,"Improvements to the Existing Cement Concrete at Pulipone Bazar 1st,2nd and 3rd Lane in dn-114,Unit-27,Zone-9.",Own Sources,9,2014-15,2016-17 RC/2014-15/22668,Electrical,Completed,P-Parks and Playfields,114,2360000,"PROVIDING ELECTRIFICATION WORKS TO THE FORMATION OF NEW PARK AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DIVISION 114, ZONE - IX",Grants,9,2014-15,2018-19 BR/2014-15/17661,Roads,Completed,BR-Bus Route Roads,115,26047000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Peters Road (from junction of Conronsmith Road to junction of Dr.Besant Road) in Dn-115, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/14666,Roads,Completed,NJ-TEYNAMPET,115,244000,"RELAYING THE EXISTING BT ROAD BY PAVER WITH BCCMP AT SUBBURAYAN STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/14688,Roads,Completed,NJ-TEYNAMPET,115,690000,"RELAYING THE EXISTING BT ROAD BY PAVER WITH BCCMP AT AMEER MAHAL ROAD IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/14690,Roads,Completed,NJ-TEYNAMPET,115,1226000,"RELAYING THE EXISTING BT ROAD BY PAVER WITH BCCMP AT DEVARAJAN STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/14691,Roads,Completed,NJ-TEYNAMPET,115,1228000,"RELAYING THE EXISTING BT ROAD AT BY PAVER WITH BCCMP SOORAPPAN STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/14820,Roads,Completed,NJ-TEYNAMPET,115,1150000,"LAYING C.C ROAD AT WEAVER STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/14821,Roads,Completed,NJ-TEYNAMPET,115,1260000,"LAYING C.C ROAD AT SATHAR ZUNG GARDEN STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/14825,Roads,Completed,NJ-TEYNAMPET,115,1380000,"LAYING C.C ROAD AT HUSSAIN ALI KHAN 2nd STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/14826,Roads,Completed,NJ-TEYNAMPET,115,856000,"LAYING C.C ROAD AT ROB 7th STREET,SRTHAR ZUNG GARDEN TANK STREET AND DEVARAJ LANE IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/14828,Roads,Completed,NJ-TEYNAMPET,115,1550000,"LAYING C.C ROAD AT WHITES LANE,MOHAMMED HUSSAIN LANE IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/14914,Roads,Completed,NJ-TEYNAMPET,115,789000,"RELAYING THE EXISTING BT ROAD AT BY PAVER WITH BCCMP IYYA PILLAI STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/14915,Roads,Completed,NJ-TEYNAMPET,115,900000,"RELAYING THE EXISTING BT ROAD BY PAVER WITH BCCMP PERUMAL ROAD IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/14916,Roads,Completed,NJ-TEYNAMPET,115,521000,"RELAYING THE EXISTING BT ROAD AT BY PAVER WITH BCCMP IYYA SAMY STREET AND PONNAPPAN STREET IN DN-115,U-27,Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/16428,Roads,Completed,NJ-TEYNAMPET,115,646000,"RELAYING THE EXISTING BT ROAD BY PAVER WITH BCCMP AT FEROZ SHAHIB STREET AND SOMU STREET IN DN- 115, U- 27, Z-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/17227,Roads,Completed,NJ-TEYNAMPET,115,1317000,"RELAYING THE EXISTING BT ROAD BY PAVER AT R.O.B MAIN STREET IN Dn-115, Unit-27, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/17229,Roads,Completed,NJ-TEYNAMPET,115,489000,"RELAYING THE EXISTING BT ROAD BY PAVER AT R.O.B 6TH STREET IN Dn-115, Unit-27, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/17231,Roads,Completed,NJ-TEYNAMPET,115,814000,"RELAYING THE EXISTING BT ROAD BY PAVER AT SUBRAMANIYA GARDEN AND ARUMUGA ACHARI STREET IN Dn-115, Unit-27, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/17262,Roads,Completed,NJ-TEYNAMPET,115,335000,"RELAYING THE EXISTING BT ROAD BY PAVER AT ARUMUGA VAITHIYAR IN Dn-115, Unit-27, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/17263,Roads,Completed,NJ-TEYNAMPET,115,730000,"RELAYING THE EXISTING BT ROAD BY PAVER AT VARADHAPILLAI STREET IN Dn-115, Unit-27, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/17264,Roads,Completed,NJ-TEYNAMPET,115,960000,"RELAYING THE EXISTING BT ROAD AT R.O.B 5th STREET IN Dn-115,Unit-27,Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19992,Roads,Completed,NJ-TEYNAMPET,115,1028000,"RELAYING THE EXISTING BT ROAD BY PAVER AT PETERS COLONY 1 TO 10 STREETS IN Dn- 115,Unit- 27, Zone- 9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19994,Roads,Completed,NJ-TEYNAMPET,115,1090000,"RELAYING THE EXISTING BT ROAD BY PAVER AT PETERS COLONY PART-2 (BLOCK NUMBER 8,14&15,17,19) IN Dn- 115,Unit- 27, Zone- 9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28800,Roads,Completed,NJ-TEYNAMPET,115,1250000,"RELAYING THE EXISTING BT ROAD BY PAVER AT MALLAN PONNAPPAN STREET IN Dn-115, Unit-27, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28919,Buildings,Completed,NJ-TEYNAMPET,115,410000,"CONVERTING THE C.I OFFICE ROOM INTO E SEVA ROOM AT WEST COTT ROAD IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/29617,Roads,Completed,NJ-TEYNAMPET,115,2302000,"LAYING CEMENT CONCRETE ROAD AT MUZAFAR JUNG BAHADUR STREET IN DN 115, U 27, Z 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/29618,Roads,Completed,NJ-TEYNAMPET,115,4107000,"Proposed Laying Cement Concrete Road at Jani John Khan Road (part) in Division 115, Unit 27,Zone 9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/20524,Roads,Completed,NJ-TEYNAMPET,116,877000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 AT ARIMUTHU(A) STREET IN DN-116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/20526,Roads,Completed,NJ-TEYNAMPET,116,1255000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 AT SIVARAMAN STREET IN DN-116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/20933,Roads,Completed,NJ-TEYNAMPET,116,507000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 AT ARUMUGAM SRTEET & LANE IN DN-116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27978,Roads,Completed,NJ-TEYNAMPET,116,343000,"LAYING CEMENT CONCRETE ROAD AT VENKATRANGAM 1ST LANE IN DN.116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27979,Roads,Completed,NJ-TEYNAMPET,116,695000,"LAYING CEMENT CONCRETE ROAD AT NEW FIREWOOD TANK IN DN.116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27980,Roads,Completed,NJ-TEYNAMPET,116,603000,"LAYING CEMENT CONCRETE ROAD AT VENKTACHALA (N) STREET IN DN.116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27981,Roads,Completed,NJ-TEYNAMPET,116,680000,"LAYING CEMENT CONCRETE ROAD AT ARIMUTHU(M) STREET IN DN.116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27982,Roads,Completed,NJ-TEYNAMPET,116,999000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NAGOJI STREET IN DN.116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27983,Roads,Completed,NJ-TEYNAMPET,116,778000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT VENKATACHALA (N) 1ST,2ND,3RD LANE IN DN.116,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 BR/2014-15/17821,Roads,Completed,BR-Bus Route Roads,117,35590000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Venkatanarayana Road(from junction of Anna Salai to junction of Bashyam Road) in Dn-122, Zone-IX & Dn - 136, Zone-X",Grants,9,2014-15,2016-17 NJ/2014-15/10836,Buildings,Completed,NJ-TEYNAMPET,117,714000,"SUPPLY AND INSTALLATION FOR E-TOILET (SHE TOILET) AT ANNA ROAD IN DIV 117,UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/10847,Buildings,Completed,NJ-TEYNAMPET,117,714000,"SUPPLY AND INSTALLATION FOR E-TOILET (SHE TOILET) AT MAMBALAM HIGH ROAD IN DIV 117, UNIT-26, ZONE-9",Own Sources,9,2014-15,2018-19 NJ/2014-15/2067,Buildings,Completed,NJ-TEYNAMPET,117,695000,"IMPROVEMENTS TO OUT SIDE OF THE COMMUNITY CENTER AT RAMAKAMATHPURAM IN DIV 117,U-26,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/22328,Roads,Completed,NJ-TEYNAMPET,117,998000,"Providing Speed Breakers as per IRC design [Clause 5, 6 of IRC: 99-1988] with Bituminous Concrete (as per clause 509 of MORT&H specification) to the required grade level andalignment and rolled with vibratory roller etc., complete and as directed by Engineers and as per the plan enclosed.at Melony Road and 8 Roads in div 117,unit-26,zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/25518,Buildings,Completed,NJ-TEYNAMPET,117,790000,"OUT SOURCING FOR ANNUAL MAINTENANCE OF DIAGNOSTIC LAB IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26164,Roads,Completed,NJ-TEYNAMPET,117,6600000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT DR.THOMAS ROAD (FROM THOMAS 1ST STREET TO SOUTH BOAG ROAD AND INBETWEEN BLOCKS ' A' TO 'O' BLOCKS AND 1 TO 10 ) IN DIV 117, UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26167,Roads,Completed,NJ-TEYNAMPET,117,1051000,"RELAYING B.T ROAD AT BHARATHI NAGAR 2ND STREET IN DIV117, UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27101,Roads,Completed,NJ-TEYNAMPET,117,896000,"RELAYING B.T ROAD AT BHARATHI NAGAR 3RD STREET IN DIV 117,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27108,Roads,Completed,NJ-TEYNAMPET,117,3460000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT THIRUVIKA KUDIYERRUPU (FROM THEYAGARAYA ROAD TO VIJAYA RAGHAVA ROAD ) IN DIV 117,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27109,Roads,Completed,NJ-TEYNAMPET,117,3290000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT THIRUVIKA KUDIYERRUPU (INBETWEEN BLOCKS A TO W) IN DIV 117,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27113,Roads,Completed,NJ-TEYNAMPET,117,3950000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT DR GIRIAPPA ROAD (FROM VIJAYA RAGHAVA ROAD TO DR GIRIAPPA ROAD PC IN DIV 117,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27115,Roads,Completed,NJ-TEYNAMPET,117,1280000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT DR GIRIAPPA ROAD NORTH (FROM PC TO NARASIMAN 2ND STREET JUCTION) IN DIV 117,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/8964,Buildings,Completed,NJ-TEYNAMPET,117,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT ANNA COLONY IN DIV -117,UNIT -26,ZONE -9",Own Sources,9,2014-15,2018-19 NJ/2014-15/9086,Buildings,Completed,NJ-TEYNAMPET,117,878000,"Providing Rental Modulor Toilet on Contract basis including Maintanance for one year at Ramakamathpuram and Chari Street in Dn-117,U-26, Zone 9",Own Sources,9,2014-15,2018-19 BR/2014-15/30053,Roads,Completed,BR-Bus Route Roads,118,24029000,Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Swamy sivananda Road (from junction of Kamarajar Road to junction of Adams Street in Dn-114 Zone-IX,Grants,9,2014-15,2016-17 BR/2014-15/30064,Roads,Completed,BR-Bus Route Roads,118,74259000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at TTK Road(from junction of Pasumpon Muthuramalingam Road to junction of Gowdia Mutt Road) in Dn-118,119&123, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/15841,Roads,Completed,NJ-TEYNAMPET,118,870000,"ATTENDING PATCH WORK AT VARIOUS INTERIOR ROADS / STREETS (VARIOUS LOCATION) IN DIV 118,UNIT-24, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/17730,Buildings,Completed,NJ-TEYNAMPET,118,1983000,"CONSTRUCTION OF MULTIPURPOSE HALL IN GALILIAPURAM IN DIVISION-118, UNIT-24, ZONE-9 ( UNDER M.L.A SCHEMES)",MPLADS,9,2014-15,2017-18 NJ/2014-15/18563,Roads,Completed,NJ-TEYNAMPET,118,130000,"ATTENDING FLOOD PATCH WORK WITH BCCMP 40 MM THICK AT SUNDARESHWARAR KOIL STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/18569,Roads,Completed,NJ-TEYNAMPET,118,130000,"ATTENDING FLOOD PATCH WORK WITH BCCMP 40 MM THICK AT MUTHAIAH STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/18572,Roads,Completed,NJ-TEYNAMPET,118,130000,"ATTENDING FLOOD PATCH WORK WITH BCCMP 40 MM THICK AT RAGAVEERA AVENEU IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/18573,Roads,Completed,NJ-TEYNAMPET,118,130000,"ATTENDING FLOOD PATCH WORK WITH BCCMP 40 MM THICK AT SIVASANKARAN STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/18575,Roads,Completed,NJ-TEYNAMPET,118,130000,"ATTENDING FLOOD PATCH WORK WITH BCCMP 40 MM THICK AT POES GARDEN IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19737,Footpath,Completed,NJ-TEYNAMPET,118,378000,"IMPROVEMENTS TO FOOTPATH AT RAMASAMY STREET STREET IN DIV-118,U-24,Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/20798,Buildings,Completed,NJ-TEYNAMPET,118,995000,"IMPROVEMENTS TO FISH MARKET AT PRASANNA VINAYAGAR KOVIL STREET IN DIV - 118 , UNIT - 24, ZONE - IX",Own Sources,9,2014-15,2016-17 NJ/2014-15/21008,Buildings,Completed,NJ-TEYNAMPET,118,999000,"CONSTRUCTION OF MULTIPURPOSE HALL IN MARIAPPAN STREET IN DIVISION-118, UNIT-24, ZONE-9 ( UNDER M.L.A SCHEME)",MLACDS,9,2014-15,2016-17 NJ/2014-15/27251,Footpath,Completed,NJ-TEYNAMPET,118,797000,IMPROVEMENT TO FOOT PATH AT AMMAIAPPAN LANE IN DIV.118 UNIT.24 ZONE.9,Own Sources,9,2014-15,2016-17 NJ/2014-15/27312,Footpath,Completed,NJ-TEYNAMPET,118,998000,IMPROVEMENT TO FOOT PATH AT VEENUS COLONY 1ST STREET IN DIV.118 UNIT.24 ZONE.9,Own Sources,9,2014-15,2016-17 NJ/2014-15/27323,Footpath,Completed,NJ-TEYNAMPET,118,997000,IMPROVEMENT TO FOOT PATH AT VEENUS COLONY 2ND STREET IN.DIV.118 UNIT.24 ZONE.9,Own Sources,9,2014-15,2016-17 NJ/2014-15/27342,Footpath,Completed,NJ-TEYNAMPET,118,776000,IMPROVEMENT TO FOOT PATH AT MAHARANI CHENNAMMAL SALAI IN DIV.118 UNIT.24 ZONE.9,Own Sources,9,2014-15,2016-17 NJ/2014-15/27373,Footpath,Completed,NJ-TEYNAMPET,118,583000,IMPROVEMENT TO FOOT PATH AT SIVASANKARAN SALAI IN DIV.118 UNIT.24 ZONE.9,Own Sources,9,2014-15,2016-17 NJ/2014-15/28388,Roads,Completed,NJ-TEYNAMPET,118,575000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT THOMAYAPPAN STREET IN DIV-118,UNIT-24,ZONE-09",Own Sources,9,2014-15,2017-18 NJ/2014-15/28390,Roads,Completed,NJ-TEYNAMPET,118,675000,"IMPROVEMENTS TO CEMENT ROAD AT PUDUPET GARDEN LANE IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28395,Roads,Completed,NJ-TEYNAMPET,118,165000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT YAHYALI 1 ST STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28397,Roads,Completed,NJ-TEYNAMPET,118,546000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT YAHYALI 2ND STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28400,Roads,Completed,NJ-TEYNAMPET,118,438000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT YAHYALI 3RD STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28402,Roads,Completed,NJ-TEYNAMPET,118,565000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT VARATHA RAJA PURAM CROSS STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28405,Roads,Completed,NJ-TEYNAMPET,118,136000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT PACHAIAMMAL STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28409,Roads,Completed,NJ-TEYNAMPET,118,398000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT NALLAN STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28411,Roads,Completed,NJ-TEYNAMPET,118,379000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT T.T.K LANE IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28413,Roads,Completed,NJ-TEYNAMPET,118,610000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT P.V KOIL 3RD STREET IN DIV-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29086,Roads,Completed,NJ-TEYNAMPET,118,1240000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT BESANT ROAD IN DIVISION-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29087,Roads,Completed,NJ-TEYNAMPET,118,1130000,"RELAYING OF ROAD WITH BC 40MM THICK AT RATHINAM STREET IN DIVISION-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29144,Roads,Completed,NJ-TEYNAMPET,118,2398000,"RRELAYING OF ROAD WITH BCMP 40 MM THICK AT KASTHURI ESTATE 3RD STREET IN DIVISION -118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29151,Roads,Completed,NJ-TEYNAMPET,118,511000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT BABU STREET LANE IN DIVISION -118,UNIT -24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29153,Roads,Completed,NJ-TEYNAMPET,118,540000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT MARIAPPAN LANE IN DIVISION -118,UNIT-24,ZONE-119",Own Sources,9,2014-15,2017-18 NJ/2014-15/29154,Roads,Completed,NJ-TEYNAMPET,118,415000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT POES ROAD 4 TH STREET IN DIVISION -118,UNIT-24,ZONE-119",Own Sources,9,2014-15,2017-18 NJ/2014-15/29155,Roads,Completed,NJ-TEYNAMPET,118,862000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT VENKATA RATHINAM SALAI IN DIVISION -118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29159,Roads,Completed,NJ-TEYNAMPET,118,770000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT CHOKKALINGAM COLONY 1 ST CROSS STREET IN DIVISION -118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29160,Roads,Completed,NJ-TEYNAMPET,118,770000,"RELAYING OF ROAD WITH BCMP 40 MM THICK AT CHOKKALINGAM COLONY 2 nd CROSS STREET IN DIVISION -118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29161,Roads,Completed,NJ-TEYNAMPET,118,777000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT KANAGA SREENAGAR IN DIVISION -118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29637,Buildings,Completed,NJ-TEYNAMPET,118,560000,"IMROVEMENTS TO DISPENSARY (GROUND FLOOR) AT AMMAIYAPPAN STREET IN DIVISION-118,UNIT-24,ZONE-IX.",Own Sources,9,2014-15,2016-17 NJ/2014-15/31314,Roads,Completed,NJ-TEYNAMPET,118,580000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT SUNDARESHWARAR KOIL STREET IN DIVISION-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31315,Roads,Completed,NJ-TEYNAMPET,118,510000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT GOVARTHAN STREET IN DIVISION-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31739,Roads,Completed,NJ-TEYNAMPET,118,1100000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT VEENUS COLONY IN DIVISION -118,UNIT -24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31740,Roads,Completed,NJ-TEYNAMPET,118,1596000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT MAHARAJA SURYA ROAD IN DIVISION -118,UNIT -24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31741,Roads,Completed,NJ-TEYNAMPET,118,1790000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT KASTHURI ESTATE 1 ST STREET IN DIVISION-118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31742,Roads,Completed,NJ-TEYNAMPET,118,1040000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT RAJA KRISHNA RAO ROAD IN DIVISION -118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31743,Roads,Completed,NJ-TEYNAMPET,118,1870000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT VARATHA RAJAPURAM MAIN ROAD IN DIVISION -118,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31744,Roads,Completed,NJ-TEYNAMPET,118,1000000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT RAGAVA VEERA AVENUE IN DIVISION -118,UNIT -24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/9723,Buildings,Completed,NJ-TEYNAMPET,118,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT ROSTERVAR GARDEN IN DIV 118,UNIT24,ZONE 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/9734,Buildings,Completed,NJ-TEYNAMPET,118,714000,"SUPPLAY AND INSTALLATION FOR ELECTRONIC TOILET (SHE) AT ROSTERVAR GARDEN DIVISION-118, UNIT-24,ZONE-IX.",Own Sources,9,2014-15,2016-17 NJ/2014-15/9760,Buildings,Completed,NJ-TEYNAMPET,118,878000,"PROVIDING RENTAL MODULOR TOILET ON CONTRACT BASIS INCLUDING MAINTENANCE FOR ONE YEAR AT CHOKLI STREET AND CHOKKALINGAM NAGAR IN DIVISION-118,UNIT-24,ZONE-IX.",Own Sources,9,2014-15,2017-18 NJ/2014-15/19837,Parks,Completed,NJ-TEYNAMPET,119,535000,"ANNUVAL MAINTENANCE OF C.I.T.COLONY PARK (TWO YEAR ) AT C.I.T.COLONY 5TH CROSS STREET IN DN-119 UNIT-24 ,ZONE-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28415,Roads,Completed,NJ-TEYNAMPET,119,215000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT KOLAKARAN PETTAI 1 ST STREET IN DIV-119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28419,Roads,Completed,NJ-TEYNAMPET,119,80000,"IMPROVEMENTS CEMENT CONCRETE ROAD AT KOLAKARAN PET 2 ND STREET IN DIV-119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29039,Roads,Completed,NJ-TEYNAMPET,119,847000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT SEETHA NAGAR 2ND STREET IN DIV-110, UNIT-24, ZONE-09",Own Sources,9,2014-15,2017-18 NJ/2014-15/31324,Roads,Completed,NJ-TEYNAMPET,119,638000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT BEGUM 3RD STREET IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31327,Roads,Completed,NJ-TEYNAMPET,119,603000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT KASIM STREET IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31328,Roads,Completed,NJ-TEYNAMPET,119,864000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT PERIA MALAIAPPAN STREET IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31329,Roads,Completed,NJ-TEYNAMPET,119,342000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT PERTHO STREET IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31330,Roads,Completed,NJ-TEYNAMPET,119,443000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT THIRU .VI. KA LANE IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31331,Roads,Completed,NJ-TEYNAMPET,119,123000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT AVVAI SHANMUGAM LANE ON DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31332,Roads,Completed,NJ-TEYNAMPET,119,844000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT THIPPU STREET IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31333,Roads,Completed,NJ-TEYNAMPET,119,634000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT BEGUM 5 TH STREET IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/31334,Roads,Completed,NJ-TEYNAMPET,119,312000,"RELAYING OF ROAD WITH B119 BCCMP 40 MM THICK AT SRIPURAM LANE IN DIVISION -119,UNIT-24,ZONE-9",Own Sources,9,2014-15,2017-18 S/2014-15/12664,Footpath,Completed,BR-Bus Route Roads,119,33400000,"Forming Foot path at Thiru Vi Ka High Road from the jn of Peters Road to the jn of Dr.Radhakrishnan Salai in Div - 119, Zone - 9.",Grants,9,2014-15,2017-18 BR/2014-15/29997,Roads,Completed,BR-Bus Route Roads,120,5880000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Dr.Natesan Road (from junction of Radakrishnan to junction of Dr.Ambedkar Bridge) in Dn-125, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/18067,Roads,Completed,NJ-TEYNAMPET,120,1786000,"RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT GAJAPATHY STREET IN DIV 120,UNIT 27,ZONE9",Own Sources,9,2014-15,2016-17 NJ/2014-15/18091,Roads,Completed,NJ-TEYNAMPET,120,966000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT VENKATARANGAM STREET IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19411,Roads,Completed,NJ-TEYNAMPET,120,760000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT NAMMALAVAR STREET AT DIV 120,UNIT27,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19419,Roads,Completed,NJ-TEYNAMPET,120,500000,"IMPROVEMENT TO THE EXISTING CEMENT CONCRETE ROAD AT MUTHAIYA 1ST STREET IN DIV 120,UNIT27,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19429,Roads,Completed,NJ-TEYNAMPET,120,1500000,"IMPROVEMENT TO THE EXISTING CEMENT CONCRETE ROAD AT MUTHIAYA 2ND STREET AT DIV 120,UNIT -27,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/19432,Roads,Completed,NJ-TEYNAMPET,120,217000,"RELAYING THE ROAD WITH BITUMINOUS COARSE 40MM THICK AT JAWAHAR HUSSAIN KHAN CROSS STREET AT DIV 120,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19581,Roads,Completed,NJ-TEYNAMPET,120,426000,"RELAYING THE ROAD WITH BITUMINOUS COARSE 40MM THICK AT JAWAHAR HUSSAINKHAN 1ST STREET IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19586,Roads,Completed,NJ-TEYNAMPET,120,249000,"RELAYING THE ROAD WITH BITUMINOUS COARSE 40MM THICK AT JAWAHAR HUSSAINKHAN 2ND STREET IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19589,Roads,Completed,NJ-TEYNAMPET,120,500000,"RELAYING THE ROAD WITH BITUMINOUS COARSE 40MM THICK AT JAWAHAR HUSSAINKHAN 3RD,4TH ,5TH,& 6TH STREET IN DIV 120,UNIT27,ZONE9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19596,Roads,Completed,NJ-TEYNAMPET,120,216000,"RELAYING THE ROAD WITH BITUMINOUS COARSE 40MM THICK AT MOHAMMED HUSSAIN STREET IN DIV 120,UNIT-27,ZONE9",Own Sources,9,2014-15,2016-17 NJ/2014-15/20821,Roads,Completed,NJ-TEYNAMPET,120,1800000,"RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT MUTHIYA STREET IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/24682,Buildings,Completed,NJ-TEYNAMPET,120,995000,"IMPROVEMENTS TO THE GYM BUILDING AT GAJAPATHY STREET IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27734,Roads,Completed,NJ-TEYNAMPET,120,529000,"RELAYING THE ROAD WITH BITUMINOUS COARSE 40MM THICK AT E- DEPOT STREET & LANE IN DIV 120,UNIT-27,ZONE9",Own Sources,9,2014-15,2016-17 BR/2014-15/17856,Roads,Completed,BR-Bus Route Roads,121,3700000,"Relaying the road with CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at V.M Street (from junction of Dr.Radakrishnan Road to junction of Thiru.V.Ka High Road) in Dn-121, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30050,Roads,Completed,BR-Bus Route Roads,121,33282000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Wallajah Road(from junction of Kamarajar Road to junction of Arunachalam Street) in Dn-114, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/19679,Roads,Completed,NJ-TEYNAMPET,121,345000,"MAN HOLE DOOR RAISING OR LOWERING WORK AT VARIOUS STREET IIN DN 121, U - 27, ZONE -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27363,Roads,Completed,NJ-TEYNAMPET,121,490000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT PALUR KANNIAPPAN STREET IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27379,Roads,Completed,NJ-TEYNAMPET,121,1230000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT APPARSWAMI KOIL STREET (NORTH) IN DN - 121, U - 27, Z-9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27382,Roads,Completed,NJ-TEYNAMPET,121,1368000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT APPARSWAMI KOIL STREET (WEST) STREET IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27383,Roads,Completed,NJ-TEYNAMPET,121,1060000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT NAGARATHINAM COLONY IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27386,Roads,Completed,NJ-TEYNAMPET,121,1328000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT THIRU-VI-KA THIRD STREET IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27388,Roads,Completed,NJ-TEYNAMPET,121,1440000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT THIRU-VI-KA SECOND STREET IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27390,Roads,Completed,NJ-TEYNAMPET,121,2890000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT AVVAI SHANMUGAM SALAI (FROM AMMA UNAVAGAM TO DR. NATESAN ROAD JUNCTION) IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27391,Roads,Completed,NJ-TEYNAMPET,121,3779000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT AVVAI SHANMUGAM SALAI (FROM DR. NATESAN ROAD JUNCTION TO KAMARAJAR SALAI JUNCTION) IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27392,Roads,Completed,NJ-TEYNAMPET,121,310000,"RELAYING THE EXISTING B.T.ROAD WITH BCC MP BY PAVER AT MECCAPURAM MAIN ROAD IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27396,Roads,Completed,NJ-TEYNAMPET,121,445000,"RELAYING THE EXISTING B.T.ROAD WITH NON PAVER AT B.B. ROAD SECOND STREET IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27397,Roads,Completed,NJ-TEYNAMPET,121,389000,"RELAYING THE EXISTING B.T.ROAD WITH NON PAVER AT B.B. ROAD FOURTH STREET IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27400,Roads,Completed,NJ-TEYNAMPET,121,864000,"RELAYING THE EXISTING B.T.ROAD WITH NON PAVER AT ISMAIL GROUND IN DN - 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27404,Roads,Completed,NJ-TEYNAMPET,121,110000,"RELAYING THE EXISTING B.T.ROAD WITH NON PAVER AT MECCAPURAM FOURTH CROSS STREET IN DN- 121, U-27, Z -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27492,Roads,Completed,NJ-TEYNAMPET,121,700000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT B.B. ROAD 3RD STREET IN DN - 121, U - 27, Z - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28238,Roads,Completed,NJ-TEYNAMPET,121,690000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT THIRUVEETHI AMMAN KOIL STREET IN DN - 121, U - 27, Z - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28264,Roads,Completed,NJ-TEYNAMPET,121,1750000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT ROTARY NAGAR MAIN ROAD IN DN - 121, U - 27, Z - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28285,Roads,Completed,NJ-TEYNAMPET,121,290000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT ROTARY NAGAR 7TH CROSS STREET IN DN - 121, U - 27, Z - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28323,Roads,Completed,NJ-TEYNAMPET,121,235000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT SURESH MACCAN 1ST AND 2ND LANE IN DN - 121, U - 27, Z - 9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28346,Roads,Completed,NJ-TEYNAMPET,121,1740000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT GANESAPURAM NOTRH IN DN - 121, U - 27, Z - 9.",Own Sources,9,2014-15,2017-18 BR/2014-15/17658,Roads,Completed,BR-Bus Route Roads,122,9262000,"Strengthening and Relaying the road with CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Cenotaph Road(from junction of Pasumpon Muthuramalingam Road to junction of Anna Salai) in Dn-122, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17884,Roads,Completed,BR-Bus Route Roads,122,12641000,"Relaying the road with CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Turnbulls Road(from junction of Pasumpon Muthuramalingam Salai to junction of Kotturpuram Bridge) in Dn-122, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30002,Roads,Completed,BR-Bus Route Roads,122,72307000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Pon Muthuramalingam Road(from junction ofAnna Salaia to junction of R.A.Puram 2nd Main Road) in Dn-122, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/11102,Buildings,Completed,NJ-TEYNAMPET,122,714000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (SHE) IN NANDANAM EXTENSION IN DIV 122,UNIT26,ZONE 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/22322,Roads,Completed,NJ-TEYNAMPET,122,998000,"Providing Speed Breakers as per IRC design [Clause 5, 6 of IRC: 99-1988] with Bituminous Concrete (as per clause 509 of MORT&H specification) to the required grade level andalignment and rolled with vibratory roller etc., complete and as directed by Engineers and as per the plan enclosed.at TTK 1st cross street and 6 Roads in div 122,unit-26,zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/23487,Roads,Completed,NJ-TEYNAMPET,122,1766000,"LAYING CEMENT CONCRETE ROAD AT GANESHAPURAM 3RD STREET IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26124,Roads,Completed,NJ-TEYNAMPET,122,948000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT GANDHI STREET IN DIV 122, UNIT 26, ZONE 9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26170,Roads,Completed,NJ-TEYNAMPET,122,950000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT ANNA STREET IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26173,Roads,Completed,NJ-TEYNAMPET,122,640000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT CHERAN STREET IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26175,Roads,Completed,NJ-TEYNAMPET,122,366000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT CHOZHAN STREET IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26177,Roads,Completed,NJ-TEYNAMPET,122,900000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT PANDIAN STREET IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26179,Roads,Completed,NJ-TEYNAMPET,122,1363000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT RANGOON STREET IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26180,Roads,Completed,NJ-TEYNAMPET,122,382000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT T.T.K LANE IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26182,Roads,Completed,NJ-TEYNAMPET,122,1258000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT ANBU COLONY 1ST AND 2ND STREET IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26189,Roads,Completed,NJ-TEYNAMPET,122,1640000,"LAYING CEMENT CONCRETE ROAD AT TANK BUND ROAD IN DIV 122,UNIT-26, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26196,Roads,Completed,NJ-TEYNAMPET,122,1777000,"RELAYING B.T. ROAD AT THIRUVALLUVAR SALAI IN DIVISION - 122,UNIT - 26,ZONE - 9",Own Sources,9,2014-15,2016-17 NJ/2014-15/26199,Roads,Completed,NJ-TEYNAMPET,122,2800000,"RELAYING B.T. ROAD AT RATHNA NAGAR AND RATHNA NAGAR ROAD STREET IN DIVISION - 122,UNIT - 26,ZONE - 9",Own Sources,9,2014-15,2017-18 NJ/2014-15/26204,Roads,Completed,NJ-TEYNAMPET,122,385000,"RELAYING B.T ROAD AT TURN BULLS 4TH CROSS STREET IN DIV 122,UNIT-26, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/2689,Buildings,Completed,NJ-TEYNAMPET,122,718000,"PROVIDING GALVANISED IRON SHEET SHELTER FOR PATIENT WAITING HALL AND PARKING AREA AT HEALTH POST K.B.DASAN SALAI IN DIV 122,UNIT-26,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27752,Roads,Completed,NJ-TEYNAMPET,122,884000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT PUGHS ROAD EXTN IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27753,Roads,Completed,NJ-TEYNAMPET,122,1700000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT PUGHS ROAD (PART) IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27757,Roads,Completed,NJ-TEYNAMPET,122,1822000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT M.T.B.BLOCK IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27758,Roads,Completed,NJ-TEYNAMPET,122,727000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT CHAMIERS 1ST LANE IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27759,Roads,Completed,NJ-TEYNAMPET,122,4343000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT SATHYAMOORTHY NAGAR PHASE I,II AND III IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27761,Roads,Completed,NJ-TEYNAMPET,122,904000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT JOGI THOTTAM IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27762,Roads,Completed,NJ-TEYNAMPET,122,463000,"RELAYING B.T ROAD AT T.T.K ROAD 2ND CROSS STREETSTREET IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28915,Roads,Completed,NJ-TEYNAMPET,122,580000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT BARUVA NAGAR IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/29045,Roads,Completed,NJ-TEYNAMPET,122,529000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT RATHNA NAGAR 2ND STREET IN DIV 122 , UNIT-26, ZONE-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/9045,Buildings,Completed,NJ-TEYNAMPET,122,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) IN CENETOPH 1ST STREET IN DIV 122, UNIT-26,ZONE-9",Own Sources,9,2014-15,2018-19 NJ/2014-15/9048,Buildings,Completed,NJ-TEYNAMPET,122,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT BOAT CLUB ROAD IN DIV 122,UNIT-26 ,ZONE-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/9097,Buildings,Completed,NJ-TEYNAMPET,122,878000,"Providing Rental Modulor Toilet on Contract basis including Maintanance for one year at Nandanam Extension and Lotus Colony in Dn-122,U-26, Zone 9",Own Sources,9,2014-15,2017-18 NJ/2014-15/9099,Buildings,Completed,NJ-TEYNAMPET,122,878000,"Providing Rental Modulor Toilet on Contract basis including Maintanance for one year at Nandanam Extension and Boat Club Road in Dn-122,U-26, Zone 9",Own Sources,9,2014-15,2017-18 BR/2014-15/17659,Roads,Completed,BR-Bus Route Roads,123,29900000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at C P Ramasamy Road (from junction of TTK Road to junction of St.Marrys Road) in Dn-123, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17660,Roads,Completed,BR-Bus Route Roads,123,14360000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at R A Puram 2nd Main Road(from junction of Venkatakrishna Road to junction of Pasumpon Muthuramalingam Road) in Dn-123, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/17866,Roads,Completed,BR-Bus Route Roads,123,3336000,"Relaying the road with CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Desilva Road (from junction of East Abiramapuram 2nd street to junction of Luz Church Road) in Dn-123, Zone-IX",Grants,9,2014-15,2017-18 BR/2014-15/24635,Roads,Completed,BR-Bus Route Roads,123,7162000,"Relaying the road with CBC after cold milling by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Warren Road (from junction of Dr.Ranga Road to junction of St.Marrys Road) in Dn-123, Zone-IX",Grants,9,2014-15,2017-18 BR/2014-15/29702,Roads,Completed,BR-Bus Route Roads,123,5274000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at CV Raman Road (from junction of CP Ramaswamy Road to junction of TTK Road) in Dn-123, Zone-IX",Grants,9,2014-15,2017-18 BR/2014-15/30097,Roads,Completed,BR-Bus Route Roads,123,38403000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works a Luz ChurchRoad(from junction of TTK Road to junction of R K Mutt Road) in Dn-123, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30099,Roads,Completed,BR-Bus Route Roads,123,23434000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at P.S.Sivaswamy Road (from junction of Musri Subramaninam Road to junction of Thiru.V.Ka High Road) in Dn-121, Zone-IX",Grants,9,2014-15,2017-18 BR/2014-15/30101,Roads,Completed,BR-Bus Route Roads,123,22309000,"Strengthening and Relaying the road with DBM and CBC after cold milling camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Dr.Radha Krishana Salai from the junction of Kamarajar Road to the junction of Dr.Natesan Salai in Ward-125,Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/30102,Roads,Completed,BR-Bus Route Roads,123,8762000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works atR.A.puram 3rd Cross Street (from junction of St.Marrys Road to junction of V-canal) in Dn-123, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/10669,Buildings,Completed,NJ-TEYNAMPET,123,878000,"PROVIDING RENTAL MODULAR TOILET ON CONTRACT BASIS INCLUDING MAINTENANCE FOR ONE YEAR AT R.A.PURAM 4TH MAIN ROAD AND BASKARAPURAM IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2016-17 NJ/2014-15/10670,Buildings,Completed,NJ-TEYNAMPET,123,878000,"PROVIDING RENTAL MODULOR TOILET ON CONTRACT BASIS INCLUDING MAINTENANCE FOR ONE YEAR AT LUBDHI COLONY AND SAINT MARYS ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2016-17 NJ/2014-15/10832,Buildings,Completed,NJ-TEYNAMPET,123,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT ST.MARYS ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2016-17 NJ/2014-15/10833,Buildings,Completed,NJ-TEYNAMPET,123,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT CANAL BANK ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2016-17 NJ/2014-15/10940,Roads,Completed,NJ-TEYNAMPET,123,990000,"PROVIDING AND LAYING THERMO PLASTIC PAINT FOR ZEBRA CROSSING IN VARIOUS ROADS IN DIV-123, U-25, Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/12827,Buildings,Completed,NJ-TEYNAMPET,123,714000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (SHE) AT ST.MARYS ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2016-17 NJ/2014-15/12959,Buildings,Completed,NJ-TEYNAMPET,123,714000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (SHE) AT CANAL BANK ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2016-17 NJ/2014-15/14758,Parks,Completed,NJ-TEYNAMPET,123,830000,"MAINTENANCE OF PARK AT R.A.PURAM 7TH MAIN ROAD BY PRIVATE AGENCIES OR 2 YEARS OLY IN DN.123,UNIT.25,ZONE.09 (By qualified horticulturist only)",Own Sources,9,2014-15,2017-18 NJ/2014-15/14759,Parks,Completed,NJ-TEYNAMPET,123,850000,"MAINTENANCE OF PARK AT DMONDY COLONY BY PRIVATE AGENCIES FOR 2YEARS IN DN.123,UNIT.25,ZONE.09( By qualified horticulturist only)",Own Sources,9,2014-15,2017-18 NJ/2014-15/27571,Roads,Completed,NJ-TEYNAMPET,123,2350000,"RELAYING OF THE ROAD WITH CBC40MM THICK BY USING PAVAR FINISH AT C.V.RAMAN SALAI (C.P.RAMASAMY SALAI TO WARRAN ROAD)IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27763,Roads,Completed,NJ-TEYNAMPET,123,1040000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT SIR DESIKA ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27770,Roads,Completed,NJ-TEYNAMPET,123,1080000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT DESILVA LANE (BRR) IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27773,Roads,Completed,NJ-TEYNAMPET,123,400000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT STONE LINK AVENUE IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27785,Roads,Completed,NJ-TEYNAMPET,123,1748000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT ASHOKA STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27819,Roads,Completed,NJ-TEYNAMPET,123,1072000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT NARASIMAPURAM IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27826,Roads,Completed,NJ-TEYNAMPET,123,1665000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT R.A.PURAM 3RD MAIN ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27835,Roads,Completed,NJ-TEYNAMPET,123,995000,"ATTENDING PATCH WORK AT BEEMANNA MUDALI STREET, LUZ CHURCH ROAD, KENNADY 1ST STREET, LUZ AVENUE 1ST STREET IN DN-123, UNIT-25, ZNE-09.",Own Sources,9,2014-15,2016-17 NJ/2014-15/27838,Roads,Completed,NJ-TEYNAMPET,123,900000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT R.A.PURAM 4TH CROSS STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27848,Roads,Completed,NJ-TEYNAMPET,123,600000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT ANANDHA ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 NJ/2014-15/27857,Roads,Completed,NJ-TEYNAMPET,123,760000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT LUZ CHURCH 1ST STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2014-15,2017-18 S/2014-15/12457,Footpath,Completed,BR-Bus Route Roads,123,54800000,"FORMING FOOTPATH AT LUZ CHRUCH ROAD FROM JN OF KUTCHERY ROAD TO TTK ROAD IN DIV-123, ZONE-9.",Grants,9,2014-15,2016-17 L/2014-15/22930,Electrical,Completed,L-Electrical,124,3705000,"Proposal for Erection of 49Nos of 8 mtr Long Octagonal Lamp post with Single Straight bracket with Hot dip Zinc galvanising with 150W-165W LED fitting at R.K. Mutt Road in div124 & Div126, Z-IX",Own Sources,9,2014-15,2016-17 NJ/2014-15/19447,Roads,Completed,NJ-TEYNAMPET,124,954000,"Providing Speed Breakers as per IRC design [Clause 5, 6 of IRC: 99-1988] with Bituminous Concrete (as per clause 509 of MORT & H specification) to the required grade level and alignment and rolled with vibratory roller etc., complete and as directed by Engineers and as per the plan enclosed at Slaterpuram Street in Div 124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27172,Roads,Completed,NJ-TEYNAMPET,124,1600000,"Improvement to Cement Concrete Road at Sathyavanimuthu Nagar in division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27869,Roads,Completed,NJ-TEYNAMPET,124,155000,"Relaying of road with BC 30mm thick at Andar Nyniappan Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27873,Roads,Completed,NJ-TEYNAMPET,124,279000,"Relaying of road with BC 40mm thick at Bazaar Lane in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27877,Roads,Completed,NJ-TEYNAMPET,124,2291000,"Relaying of road with BC 40mm thick at Kalvivaru Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27880,Roads,Completed,NJ-TEYNAMPET,124,500000,"Relaying of road with BC 30mm thick at Kesavaperumal South Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27882,Roads,Completed,NJ-TEYNAMPET,124,1081000,"Relaying of road with BC 40mm thick at Madava Perumal Koil Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27887,Roads,Completed,NJ-TEYNAMPET,124,625000,"Relaying of road with BC 30mm thick at Mosque Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27888,Roads,Completed,NJ-TEYNAMPET,124,415000,"Relaying of road with BC 30mm thick at Mundagakanni Amman Koil 2nd Lane in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27889,Roads,Completed,NJ-TEYNAMPET,124,515000,"Relaying of road with BC 30mm thick at Nallapan Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27894,Roads,Completed,NJ-TEYNAMPET,124,220000,"Relaying of road with BC 30mm thick at Singari Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27897,Roads,Completed,NJ-TEYNAMPET,124,325000,"Relaying of road with BC 30mm thick at St.Mary's Lane in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27901,Roads,Completed,NJ-TEYNAMPET,124,1490000,"Relaying of road with BC 40mm thick at Thengur Selva Vinayakar Koil Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27910,Roads,Completed,NJ-TEYNAMPET,124,310000,"Relaying of road with BC 30mm thick at Vadugu Idayar Street in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28050,Roads,Completed,NJ-TEYNAMPET,124,999000,"Improvements to Cement Concrete Road at Lala Thottam in Division-124, Unit-25, Zone-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/28061,Roads,Completed,NJ-TEYNAMPET,124,920000,"Improvements to Cement Concrete Road at Saradhapuram Canal Bank Road in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28076,Roads,Completed,NJ-TEYNAMPET,124,1210000,"Improvements to Cement Concrete Road at Sundara Gramini Thottam in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28120,Roads,Completed,NJ-TEYNAMPET,124,880000,"Improvements to Cement Concrete Road at Nattan Thotam in Division-124, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 BR/2014-15/17747,Roads,Completed,BR-Bus Route Roads,125,42960000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Santhome High Road (from junction of South Canal Bank Road to junction of Karaneeswarar Pagoda Street ) in Dn-125 & 126, Zone-IX",Grants,9,2014-15,2016-17 BR/2014-15/29998,Roads,Completed,BR-Bus Route Roads,125,21800000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Karaneeswarar Pogoda Street(from junction of Santhome High Road to junction of Dr.Ambedkar Bridge) in Dn-125, Zone-IX",Grants,9,2014-15,2016-17 L/2014-15/10899,Electrical,Completed,L-Electrical,125,559500,"Proposal and laying of 16 mtr High Mast at Karni pagoda and Dr. Ambedkar Bridge Junction, Division - 125, Zone-IX.",MPLADS,9,2014-15,2016-17 NJ/2014-15/10246,Buildings,Completed,NJ-TEYNAMPET,125,878000,"Providing Rental Modular Toilet on contract basis including maintenance for one year at Karneeswarapuram and Nochikuppam in Div 125,U-25,Zone -9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/10862,Buildings,Completed,NJ-TEYNAMPET,125,628000,"Supply and installation for Electronic Toilet (General) at Dr.Radhakrishnan Salai in Div 125, Unit 25,Zone -9",Own Sources,9,2014-15,2016-17 NJ/2014-15/10939,Roads,Completed,NJ-TEYNAMPET,125,990000,"PROVIDING AND LAYING THERMO PLASTIC PAINT FOR ZEBRA CROSSING IN VARIOUS ROADS IN DIV-125, U-25, Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/13012,Buildings,Completed,NJ-TEYNAMPET,125,714000,"Supply and installation for Electronic Toilet (She) in Dr.Radhakrishana salai in Div 125, Unit 25,Zone -9",Own Sources,9,2014-15,2016-17 NJ/2014-15/19839,Parks,Completed,NJ-TEYNAMPET,125,745000,"ANNUAL MAINTENANCE OF PARK AT NAINAR STREET(O.S.R LAND BEHIND CITY CENTER) IN DN.125,U-25,Z-IX.(By qualified Horticulturist for Two years)",Own Sources,9,2014-15,2018-19 NJ/2014-15/21277,Buildings,Completed,NJ-TEYNAMPET,125,820000,"Providing of Ramp in various COC building in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27985,Roads,Completed,NJ-TEYNAMPET,125,620000,"Relaying of road with BC 30mm thick by using Paver Finish at Muthupandian Avenue in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28002,Roads,Completed,NJ-TEYNAMPET,125,1230000,"Relaying of road with BC 30mm thick at Rosary Church Street by using Paver Finish in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28003,Roads,Completed,NJ-TEYNAMPET,125,1045000,"Relaying of road with BC 30mm thick at Sullivan Street by using Paver Finish in Div-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28004,Roads,Completed,NJ-TEYNAMPET,125,1170000,"Relaying of road with BC 30mm thick at Muthu Street by using Paver Finish in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28005,Roads,Completed,NJ-TEYNAMPET,125,635000,"Relaying of road with BC 30mm thick at Appu 1st Street by using Paver Finish in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28007,Roads,Completed,NJ-TEYNAMPET,125,1060000,"Relaying of road with BC 30mm thick at Appu 2nd Street by using Paver Finish in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28009,Roads,Completed,NJ-TEYNAMPET,125,1090000,"Relaying of road with BC 30mm thick at Demonte Street by using Paver Finish in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28010,Roads,Completed,NJ-TEYNAMPET,125,900000,"Relaying of road with BC 30mm thick at Santhome Church Lane by using Paver Finish in Division-125, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/28154,Storm Water Drain,Completed,NJ-TEYNAMPET,125,850000,"Proposed Cement Concrete Road at Anthu Street in division - 125, unit - 25, zone - 9.",Own Sources,9,2014-15,2016-17 NJ/2014-15/6945,Buildings,Completed,NJ-TEYNAMPET,125,837000,"IMPROVEMENTS TO DIVISIONAL OFFICE AT KUTCHERY ROAD IN DIV-125, U-25, Z-9",Own Sources,9,2014-15,2016-17 BR/2014-15/29708,Roads,Completed,BR-Bus Route Roads,126,16273000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Venkatakrishna Road (from junction of R K Mutt Road to junction of R A puram 2nd Main Road) in Dn-126, Zone-IX",Grants,9,2014-15,2017-18 BR/2014-15/30081,Roads,Completed,BR-Bus Route Roads,126,9153000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Madha Church Road (from junction of Santhome High Road to junction of Mandeiveli Street) in Dn-126, Zone-IX",Grants,9,2014-15,2017-18 BR/2014-15/30082,Roads,Completed,BR-Bus Route Roads,126,24907000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at South Canal Bank Road (from junction of Santhome High Road to junction of R K Mutt Road) in Dn-126, Zone-IX",Grants,9,2014-15,2017-18 BR/2014-15/30098,Roads,Completed,BR-Bus Route Roads,126,5751000,"Strengthening and Relaying the road with DBM and CBC after cold milling with camber correction by Paver Finisher using Shredded Plastic Waste along with Traffic improvement works at Devanathan Road (from junction of St.Marrys Road to junction of Venkatakrishna Road) in Dn-126, Zone-IX",Grants,9,2014-15,2016-17 NJ/2014-15/10272,Buildings,Completed,NJ-TEYNAMPET,126,878000,"Providing Rental Moudular Toilet on Contract basis including Mainenance for one year at Sringeri mutt road and Sringeri mutt Road in division-126, Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/10274,Buildings,Completed,NJ-TEYNAMPET,126,628000,"Supply and installation for electronic toilet (General) at Karpagam Avenue in division-126, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/10943,Roads,Completed,NJ-TEYNAMPET,126,990000,"PROVIDING AND LAYING THERMO PLASTIC PAINT FOR ZEBRA CROSSING IN VARIOUS ROADS IN DIV-126, U-25, Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/13013,Buildings,Completed,NJ-TEYNAMPET,126,714000,"Supply and installation for electronic toilet (She) at Karpagam Avenue in division-126, Unit-25, Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27077,Buildings,Completed,NJ-TEYNAMPET,126,940000,"Outsourcing for removal of hoardings and banners including gascutter and other materials etc for a period of 1 year in division-123, 124, 125, 126 in Unit-25, Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/27783,Roads,Completed,NJ-TEYNAMPET,126,560000,"Relaying of road with BC 40mm thick by using paver finish at 1st Trust Cross Street in Division-126,Unit-25,Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27829,Roads,Completed,NJ-TEYNAMPET,126,925000,"Relaying of road with BC 40mm thick by using paver finish at R.K.Nagar2nd main road Street in Division-126,Unit-25,Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/27831,Roads,Completed,NJ-TEYNAMPET,126,715000,"Relaying of road with BC 40mm thick at Nainiyappan Street by using paver finish in Division-126,Unit-25,Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28100,Roads,Completed,NJ-TEYNAMPET,126,1000000,"Relaying of road with BC 40mm thick at Vinayagam Street by using paver finish in Division-126,Unit-25,Zone-9",Own Sources,9,2014-15,2017-18 NJ/2014-15/28957,Footpath,Completed,NJ-TEYNAMPET,126,821000,"Providing sand tree guard fence for 125nos of as per green tribunal act trees in santhom high road , south canal bank road 2rd trust main road in DN-126,UNIT-25,ZONE-9.",Own Sources,9,2014-15,2017-18 NJ/2014-15/29613,Buildings,Completed,NJ-TEYNAMPET,126,405000,Proving Ramp For all COC building in divison 126 u 25 z 9,Own Sources,9,2014-15,2017-18 NJ/2014-15/29621,Buildings,Completed,NJ-TEYNAMPET,126,58000,"REPAIRS AND IMPROVEMENT TO THE AMMA UNNAVAGAM AT SANTHOME HIGH ROAD IN DIV-126, U-25, Z-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/31594,Roads,Completed,NJ-TEYNAMPET,126,950000,"Relaying of road with BC 40mm thick by using paver finish at Jeth Nagar Main Road in Division-126,Unit-25,Zone-9",Own Sources,9,2014-15,2016-17 NJ/2014-15/31597,Roads,Completed,NJ-TEYNAMPET,126,4500000,"Relaying of road with BC 40mm thick by using paver finish at 2nd Trust Cross Street, 6th Trust Cross Street and Thiruvenkadam Street in Division-126,Unit-25,Zone-9",Own Sources,9,2014-15,2017-18 L/2014-15/22548,Electrical,Completed,L-Electrical,127,2804200,"Erection of 75 nos of 6mtr Octogonal post with 40-50W LED Fitting at Postal Audit colony ,Bharthiyar street ,Kamber street and Sai nagar anexe under the Division-127 Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/27917,Electrical,Completed,L-Electrical,127,1998200,"Provision of 59 nos of 6 Mtr GI Lamp Post with Single Straight Bracket with 40w-50w LED Fitting at Veda Salai ,Manavalan Street and Kulasekrapuram in Division-127, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/4498,Electrical,Completed,L-Electrical,127,1462500,REMOVAL AND REFIXING OF 11 NOS 9.5 MTR M.S LAMP POST AND NEWELY ERRECTION OF 12 NOS 8 MTR DOUBLE ARCH BRACKET G.I.LAMP POST WITH 150W TO 165 W LED FITTING AT KALIAMMAN KOIL MAIN ROAD TO JN OF 100 FEET ROAD IN DIV-127 ZONE-10,Deposit Works,10,2014-15,2016-17 NK/2014-15/11598,Roads,Completed,NK-KODAMBAKKAM,127,933000,"ENGAGING PRIVATE LORRY (TATA ACE) WITH 6 LABORS FOR CLING WORK IN ALL I.R AND BRR ROADS IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/11599,Roads,Completed,NK-KODAMBAKKAM,127,930000,"ENGAGING PRIVATE LORRY (TATA ACE) WITH 6 LABORS FOR CLING WORK IN ALL I.R AND BRR ROADS IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/13076,Parks,Completed,NK-KODAMBAKKAM,127,610000,"ANNUAL MAINTENANCE OF PARK AT JAI NAGAR PARK-1 IN DN 127,UNIT 29 AND ZONE 10(Employed qualified horticulturist for one year only)",Own Sources,10,2014-15,2016-17 NK/2014-15/16629,Parks,Completed,NK-KODAMBAKKAM,127,961000,"ANNUAL MAINTENENCE OF PARK AT OSR 1 TO 6 OSR SAF GAMES VILLAGE KOYAMBEDU IN DIV - 127, U - 29, Zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/16633,Parks,Completed,NK-KODAMBAKKAM,127,828000,"ANNUAL MAINTENENCE OF PARK AT OSR 7 to 12 OSR SAF GAMES VILLAGE KOYAMBEDU IN DIV - 127, U - 29, Zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/20562,Roads,Completed,NK-KODAMBAKKAM,127,876000,"IMPROVEMENT WORKS TO THE BURIAL GROUND AT NEW COLONY IN DIVISION -127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2019-20 NK/2014-15/24841,Electrical,Completed,NK-KODAMBAKKAM,127,1871000,"PROVISION OF 52 NOS OF LIGHTING WITH EL LAMP POST AVILABLE IN THE DEPARTMENT WITH 90 W LED FITTING AT SAF GAMES VILLAGE 2ND Main Road IN DIVISION -127, ZONE-X",Own Sources,10,2014-15,2016-17 NK/2014-15/26505,Roads,Completed,NK-KODAMBAKKAM,127,895000,"LAYING OF CEMENT CONCRETE ROAD USING M40 GRADE AT BURIAL GROUND ROAD IN DIVISION -127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2019-20 NK/2014-15/29914,Roads,Completed,NK-KODAMBAKKAM,127,710000,"Maintenance to Park Area inside Health Post Building(Western Side) in DN-127,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30911,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,659000,"CONSTRUCTION OF STORM WATER DRAIN AT NEW COLONY FROM JUNCTION OF BURRIAL GROUND ROAD TO EXISTING CANAL IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30912,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,987000,"CONSTRUCTION OF STORM WATER DRAIN AT NEW COLONY (FROM CHAINAGE OF 77M NEAR HAND PUMP TO JUNCTION OF BURRIAL GROUND ROAD) IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30913,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,988000,"CONSTRUCTION OF STORM WATER DRAIN AT NEW COLONY (FROM EXISTING STORM WATER DRAIN TO CHAINAGE OF 77M NEAR HAND PUMP) IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30928,Parks,Completed,NK-KODAMBAKKAM,127,992000,"PROVIDING ROOFING WITH GALVANAISHED IRON SHEET SHED AND PAINTING WORK FOR COC PARK AT JAINAGAR 1st MAIN ROAD IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30964,Buildings,Completed,NK-KODAMBAKKAM,127,999000,"Improvement to Park at Iyyappa Nagar 2nd Main Road in Dn-127, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30965,Buildings,Completed,NK-KODAMBAKKAM,127,848000,"Providing Water Supply and S.S.Handrail Around the Ayyappa Nagar Park in Dn-127, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30966,Buildings,Completed,NK-KODAMBAKKAM,127,960000,"Plantation Work to Ayyappa Nagar Park at Ayyappa Nagar 2nd Main Road in Dn-127, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31081,Parks,Completed,NK-KODAMBAKKAM,127,860000,"Providing Granite Gladding Work at Entrance Wall to Ayyappa Nagar Park at Ayyappa Nagar 2nd Main Road in Div-127, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31082,Parks,Completed,NK-KODAMBAKKAM,127,994000,"Granite Cladding Work to Ayyappa Nagar Park at Ayyappa Nagar 2nd Main Road in Div-127, Unie-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31083,Roads,Completed,NK-KODAMBAKKAM,127,818000,Granite Caldding work to Ayyappa Nagar park East Site at Ayyappa Nagar 2nd Main Road in Div-127 Unit-29 Zone-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31137,Parks,Completed,NK-KODAMBAKKAM,127,993000,"RAISING OF COMPOUND WALL AND SUPPLYING OF PLAY APPARATUS AT RAGAVENDRA COLONY PARKIN DN-127, UNIT-29, ZONE10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31138,Parks,Completed,NK-KODAMBAKKAM,127,961000,"RAISING OF COMPOUND WALL AND SUPPLYING OF PLAY APPARATUS AT AVVAITHIRUNAGAR 3rd STREET PARKIN DN-127, UNIT-29, ZONE10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31139,Parks,Completed,NK-KODAMBAKKAM,127,994000,"PROVIDING AND LAYING OF FOOTPATH INSIDE THE PARK AT RAGAVENDRA COLONY IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31140,Parks,Completed,NK-KODAMBAKKAM,127,995000,"PROVIDING AND LAYING OF FOOTPATH INSIDE THE PARK AT AVVAITHIRUNAGAR 3rd STREET PARK IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31194,Roads,Completed,NK-KODAMBAKKAM,127,999000,Attending patch work at school street and kamarajar street in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31195,Roads,Completed,NK-KODAMBAKKAM,127,980000,Attending patch work at sivan koil street in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31281,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,980000,"PROVIDING FOUNTAIN AT THE EXSISTING STRUCTURE IN JAI NAGAR PARK 1 IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31282,Parks,Completed,NK-KODAMBAKKAM,127,960000,"PROVIDING AND FIXING OF KIDS PLAYSTATION AT JAI NAGAR PARK 1 AND 2 IN DIV 127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31381,Parks,Completed,NK-KODAMBAKKAM,127,993000,"PROVIDING STAINLESS STEEL HAND RAIL FOR JAINAGAR PARK IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31444,Roads,Completed,NK-KODAMBAKKAM,127,2390000,"Proposed Laying of road by using BC 40mm thick at Chinmaya Nagar Stage -I, V.V.Koil street, in div 127, unit-29, zone 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31538,Roads,Completed,NK-KODAMBAKKAM,127,845500,"Strengthening and Laying of Bituminous Road by paver finisher at Srinivasa Nagar Main Road - Reach I (0 - 85M) in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31540,Roads,Completed,NK-KODAMBAKKAM,127,840000,"Strengthening and Laying of Bituminous Road by paver finisher at Srinivasa Nagar Main Road - Reach II (85 - 170M) in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31541,Roads,Completed,NK-KODAMBAKKAM,127,843000,"Strengthening and Laying of Bituminous Road by paver finisher at Srinivasa Nagar Main Road - Reach III (170 - 260M) in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31544,Roads,Completed,NK-KODAMBAKKAM,127,695000,"Strengthening and Laying of Bituminous Road by paver finisher at Srinivasa Nagar 1st Street and 3rd Street in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31546,Roads,Completed,NK-KODAMBAKKAM,127,997000,"Strengthening and Laying of Bituminous Road by paver finisher at Sastri Nagar and Sastri Street in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31548,Roads,Completed,NK-KODAMBAKKAM,127,810000,"Strengthening and Laying of Bituminous Road by paver finisher at Mangamma Nagar North (Reach from Srinivasa Nagar 2nd Street) in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31550,Roads,Completed,NK-KODAMBAKKAM,127,815000,"Strengthening and Laying of Bituminous Road by paver finisher at Mangamma Nagar South (Reach from Srinivasa Nagar 2nd Street) in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31552,Roads,Completed,NK-KODAMBAKKAM,127,610000,"Strengthening and Laying of Bituminous Road by paver finisher at Srinivasa Nagar 2nd Street East in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31553,Roads,Completed,NK-KODAMBAKKAM,127,614500,"Strengthening and Laying of Bituminous Road by paver finisher at Srinivasa Nagar 2nd Street West in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31611,Roads,Completed,NK-KODAMBAKKAM,127,991000,"LAYING OF CEMENT CONCRETE ROAD USING M40 GRADE AT SEMBARUTHI STREET, SOUTH AND WEST MAADA STREET LANES IN DN-127, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31612,Roads,Completed,NK-KODAMBAKKAM,127,989000,"ATTENDING BATCH WORK AT V.V KOVIL STREET AND VARIOUS STREETS IN DN-127,U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31614,Roads,Completed,NK-KODAMBAKKAM,127,990000,"LAYING OF CEMENT CONCRETE ROAD USING M40 GRADE AT SCHOOL STREET AND EAST MAADA STREET LANES IN DN-127, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31615,Roads,Completed,NK-KODAMBAKKAM,127,987000,"ATTENDING BATCH WORK AT NATESANAGAR AND VARIOUS STREETS IN DN-127,U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31638,Roads,Completed,NK-KODAMBAKKAM,127,528000,"Attending Patch work at Jai Nagar 1st Main Road in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31659,Parks,Completed,NK-KODAMBAKKAM,127,472000,"plantation work at saf games village park no-3 in division-127,unit-29,zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31660,Roads,Completed,NK-KODAMBAKKAM,127,996000,Proposed construction of retaining wall for Burial Ground cement concrete road ( north side ) at Koyambedu burial ground raod in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31661,Roads,Completed,NK-KODAMBAKKAM,127,995000,Proposed construction of retaining wall for Burial Ground cement concrete road ( south side ) at Koyambedu burial ground raod in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31662,Buildings,Completed,NK-KODAMBAKKAM,127,970000,"IMPROVEMENT TO PARK NEAR RESERVE BANK QUARTERS AT SAFGV IN DN 127,ZONE 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31663,Roads,Completed,NK-KODAMBAKKAM,127,290000,Attending patch work using RMC 40 at Jai nagar and sayee nagar in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31665,Roads,Completed,NK-KODAMBAKKAM,127,640000,Improvement to park and the SAFGV in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31667,Buildings,Completed,NK-KODAMBAKKAM,127,840000,Construction of meditation Building and Transform Dwart wall at SAFGV in Dn 127 u-29 z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31672,Roads,Completed,NK-KODAMBAKKAM,127,410000,"IMPROVEMENT TO PARK AT BLOCK B14,B15,B16,B7,B8,C13 AT SAFGV IN DN 127,ZONE 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31817,Roads,Completed,NK-KODAMBAKKAM,127,960000,Attending patch work using RMC 40 at mettukulam kamarajar street ch 75 - 140 m in Dn:127 Unit:29 Zone:10,Own Sources,10,2014-15,2016-17 NK/2014-15/31819,Roads,Completed,NK-KODAMBAKKAM,127,460000,Widdening of the road at SAFGV (X Block opp side ) in Dn- 127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31820,Roads,Completed,NK-KODAMBAKKAM,127,700000,Attending patch work using RMC 40 at mettukulam kamarajar street ch 140 - 190 m in Dn:127 Unit:29 Zone:10,Own Sources,10,2014-15,2016-17 NK/2014-15/31821,Roads,Completed,NK-KODAMBAKKAM,127,990000,Attending patch work using RMC 40 at mettukulam kamarajar street ch 0 - 75 m in Dn:127 Unit:29 Zone:10,Own Sources,10,2014-15,2016-17 NK/2014-15/31823,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Attending patch work using RMC 40 at mettukulam 1 to 8 lane in div-127, unit-29, zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31824,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Attending patch work using RMC 40 at mettukulam thiruvalluvar street 1 to 5 lane in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31825,Roads,Completed,NK-KODAMBAKKAM,127,450000,"Attending patch work using RMC 40 at sivan koil street 1st,2nd,3rd,4th,5th lane in Dn-127, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31847,Roads,Completed,NK-KODAMBAKKAM,127,939000,"RELAYING OF ROAD USING CEMENT CONCRETE M40 GHRADE AT NATESANAGAR 4TH AND 3RD MAIN ROAD LINK IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31848,Roads,Completed,NK-KODAMBAKKAM,127,882000,"RELAYING OF ROAD USING CEMENT CONCRETE M40 GRADE AT WEST NATESANAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31849,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,961000,"IMPROVEMENTS TO STORM WATER DRAIN AT KUMARAN NAGAR 2ND CROSS STREET REACH-1 IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31850,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,964000,"IMPROVEMENTS TO STORM WATER DRAIN AT KUMARAN NAGAR 2ND CROSS STREET REACH-2 IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2017-18 NK/2014-15/31851,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,989000,"IMPROVEMENTS TO STORM WATER DRAIN AT KUMARAN NAGAR 2ND CROSS STREET REACH-3 IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2017-18 NK/2014-15/31852,Roads,Completed,NK-KODAMBAKKAM,127,980000,"ATTENDING PATCH WORK USING RMC 40 AT SEMATHAMMAN NAGAR 2 SECTOR 1ST STREET IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31853,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,969000,"LAYING OF PIPE FOR FLOW OF RAIN WATER AT JAI NAGAR, RAGAVENDRA COLONY AND NATESANAGAR 1ST CROSS STREET IN DN-127, UNIT-29 ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31854,Roads,Completed,NK-KODAMBAKKAM,127,980000,"ATTENDING PATCH WORK USING RMC 40 AT SEMATHAMMAN NAGAR 2 SECTOR 2nd STREET IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31858,Roads,Completed,NK-KODAMBAKKAM,127,990000,"ATTENDING PATCH WORK USING RMC 40 AT METTUKULAM BHARATHI STREET LANE IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31859,Roads,Completed,NK-KODAMBAKKAM,127,990000,"ATTENDING PATCH WORK USING RMC 40 AT METTUKULAM KAMARAJAR STREET LANE IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31860,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,410000,IMPROVEMENT TO SWD AT 100 FEET ROAD IN DN 127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31863,Roads,Completed,NK-KODAMBAKKAM,127,989000,"CONSTRUCTION OF INSPECTION CHAMPERS AND PROVIDING WET MIX MACADAM AT METTUKULAM LANES IN DIV-127, UNIT-29, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31892,Roads,Completed,NK-KODAMBAKKAM,127,820000,"Laying of the road using RMC 40 at semathamman nagar 1 sector kurunji street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31893,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Maligai street, Thamarai street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31894,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Samanthi nagar cross street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31895,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Samanthi street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31902,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Sembaruthi street ch 0-60m in div-127, unit-29, zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31904,Roads,Completed,NK-KODAMBAKKAM,127,980000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector MGR street CH 0-60m in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31905,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector MGR street CH 60 - 120 M in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31906,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Sembaruthi street CH 60-120m in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31907,Roads,Completed,NK-KODAMBAKKAM,127,970000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Mullai street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31908,Roads,Completed,NK-KODAMBAKKAM,127,992000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Roja street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31909,Roads,Completed,NK-KODAMBAKKAM,127,991000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Kaliamman koil street side road in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31912,Roads,Completed,NK-KODAMBAKKAM,127,980000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector koyambedu Market side road in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31913,Roads,Completed,NK-KODAMBAKKAM,127,992000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Thalampoo street ch 0-60m in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31914,Roads,Completed,NK-KODAMBAKKAM,127,991000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Thalampoo street ch 60-120m in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31920,Roads,Completed,NK-KODAMBAKKAM,127,980000,"Laying of the road using RMC 40 at Anna street ch120-160m in div-129, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31922,Roads,Completed,NK-KODAMBAKKAM,127,980000,"Laying of the road using RMC 40 at Jeeva street ch 0-60m in div-129, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31924,Roads,Completed,NK-KODAMBAKKAM,127,990000,"LAYING OF THE ROAD USING RMC 40 AT SEMATHAMMAN NAGAR 2SECTOR 5TH CROSS STREET IN DN 127 UNIT-29,ZONE 10",Own Sources,10,2014-15,2017-18 NK/2014-15/31930,Roads,Completed,NK-KODAMBAKKAM,127,960000,"ATTTENDING PATCH WORK USING RMC 40 AT METTUKULAM CROSS STREET IN DN 127,ZONE 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31940,Roads,Completed,NK-KODAMBAKKAM,127,950000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Thalampoo cross street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31941,Roads,Completed,NK-KODAMBAKKAM,127,995000,"Laying of the road using RMC 40 at Semathamman nagar 1 sector Thalampoo street ch 120 -170m in div-127, unit-29, zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31942,Roads,Completed,NK-KODAMBAKKAM,127,260000,PROVIDING PIPE LINE AND CHAMBER AT NATESAN NAGAR 1st STREET AND RAMALINGAM STREET IN DN-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31952,Roads,Completed,NK-KODAMBAKKAM,127,825000,Renovation to the damaged kerb wall around the park in SAF Games Village in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31953,Roads,Completed,NK-KODAMBAKKAM,127,350000,De-silting of road side drain at SAFGV in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/31956,Footpath,Completed,NK-KODAMBAKKAM,127,600000,"Providing and laying gravel mix at SAFGV Walking rack in div-127, unit-29, zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31957,Roads,Completed,NK-KODAMBAKKAM,127,100000,WALL PAINTING WORK TO TENNIS COURT SWIMMING POOL DRESSING ROOM AND ROAD SIDE TREES AT SAFGV IN DN -127 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31958,Road Cut,Completed,NK-KODAMBAKKAM,127,310000,PROPOSED COMPOSITE YARD TO SAFGV IN DN-127 U-29 -10,Own Sources,10,2014-15,2016-17 NK/2014-15/31960,Footpath,Completed,NK-KODAMBAKKAM,127,950000,"Attending patch work at various street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31961,Roads,Completed,NK-KODAMBAKKAM,127,960000,"Improvement to footpath and providing pipe line connection with chamber at Kaliamman koil street reach -1 IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31962,Buildings,Completed,NK-KODAMBAKKAM,127,460000,"Improvement to foot path at Kaliamman koil street in Dn-127,U-29,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31963,Roads,Completed,NK-KODAMBAKKAM,127,960000,"Improvement to footpath and providing pipe line connection with chamber at Kaliamman koil street reach -2 IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31964,Roads,Completed,NK-KODAMBAKKAM,127,960000,"Improvement to footpath and providing pipe line connection with chamber at Kaliamman koil street reach -3 IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31967,Roads,Completed,NK-KODAMBAKKAM,127,990000,Attending patch work using RMC 40 at Semathannagar 1st sector in Dn -127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/31983,Roads,Completed,NK-KODAMBAKKAM,127,995000,"Attending patch work using RMC 40 at Various street in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31985,Footpath,Completed,NK-KODAMBAKKAM,127,980000,Attending patch work using RMC 40 at Various street in Dn -127 U -29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/31986,Roads,Completed,NK-KODAMBAKKAM,127,980000,Repair to Storm water drain at Various street in Dn -127 u-29 z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32001,Roads,Completed,NK-KODAMBAKKAM,127,987000,Attending patch work using RMC40 at Various street in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32002,Footpath,Completed,NK-KODAMBAKKAM,127,995000,"Improvement to footpath at sayee nagar 1st main road (west side ch- 210-280m) in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32003,Footpath,Completed,NK-KODAMBAKKAM,127,990000,"Improvement to footpath at sayee nagar 1st main road (west side ch-0-70m) in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32004,Footpath,Completed,NK-KODAMBAKKAM,127,996000,"Improvement to footpath at sayee nagar 1st main road (west side ch- 70-140m) in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32005,Footpath,Completed,NK-KODAMBAKKAM,127,992000,"Improvement to footpath at sayee nagar 1st main road (west side ch- 140-210m) in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32006,Footpath,Completed,NK-KODAMBAKKAM,127,990000,"Improvement to footpath at sayee nagar 1st main road (west side ch- 0-60m) in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32007,Roads,Completed,NK-KODAMBAKKAM,127,997000,Attending patch work using RMC40 at Various street in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32008,Roads,Completed,NK-KODAMBAKKAM,127,995000,Providing and laying wet mix macadam at Koyambedu Burial ground road CH 0-210 m in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32009,Roads,Completed,NK-KODAMBAKKAM,127,995000,Providing and laying wet mix macadam at Koyambedu Burial ground road CH 210-420 m in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32010,Roads,Completed,NK-KODAMBAKKAM,127,997000,Attending patch work using RMC40 at Various street in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32011,Roads,Completed,NK-KODAMBAKKAM,127,990000,Attending patch work using RMC40 at Various street in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32012,Roads,Completed,NK-KODAMBAKKAM,127,990000,Improvement to foot path at Velayutham colony park in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32013,Roads,Completed,NK-KODAMBAKKAM,127,910000,Improvement to foot path at Velayutham colony park in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32015,Roads,Completed,NK-KODAMBAKKAM,127,980000,Providing and fixing SS hand rail at Velayutham colony park in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32017,Roads,Completed,NK-KODAMBAKKAM,127,980000,Repair to storm water Drain at Various street in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32019,Footpath,Completed,NK-KODAMBAKKAM,127,997000,"De-Silting and Repair to road side drain North side ( CH 1000 m to 2000 m ) at SAFGV in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32020,Footpath,Completed,NK-KODAMBAKKAM,127,990000,"De-Silting and Repair to road side drain South side at SAFGV in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32021,Footpath,Completed,NK-KODAMBAKKAM,127,999000,"De-Silting and Repair to road side drain North side ( CH 0 m to 1000 m )at SAFGV in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32022,Footpath,Completed,NK-KODAMBAKKAM,127,960000,"De-Silting and Repair to road side drain at SAFGV in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32023,Buildings,Completed,NK-KODAMBAKKAM,127,960000,"Providing protected Grill and other repair work to CHSS Building at Koyambedu in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32026,Roads,Completed,NK-KODAMBAKKAM,127,730000,Road widening of road at 1st main road SAFGV in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32027,Roads,Completed,NK-KODAMBAKKAM,127,730000,Road widening of road at 2nd main road SAFGV in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32030,Footpath,Completed,NK-KODAMBAKKAM,127,999000,"De-Silting and Repair to road side drain 2nd main road at SAFGV in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32031,Footpath,Completed,NK-KODAMBAKKAM,127,450000,"Supplying and fixing playing apparatus at SAFGV Parks in div-127, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32051,Roads,Completed,NK-KODAMBAKKAM,127,497000,"Providing Wet Mix Macadam at at A.K.R Road in Dn-127, Unit-29, Zone - X",Own Sources,10,2014-15,2018-19 NK/2014-15/32052,Roads,Completed,NK-KODAMBAKKAM,127,776000,"Providing Wet Mix Macadam at Pillayar koil street,North Mada Street & South Mada Street in Dn-127, Unit-29, Zone - X",Own Sources,10,2014-15,2018-19 NK/2014-15/32106,Roads,Completed,NK-KODAMBAKKAM,127,970000,"ATTENDING PATCH WORK USING RMC 40 AT SEMATHAMMAN NAGAR 2 SECTOR 3rd STREET CH 70-140 m IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32107,Roads,Completed,NK-KODAMBAKKAM,127,990000,"ATTENDING PATCH WORK USING RMC 40 AT SEMATHAMMAN NAGAR 2 SECTOR 3rd STREET CH 0-70 m IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32110,Footpath,Completed,NK-KODAMBAKKAM,127,330000,Providing interlocking paver block In front yoga building and custom quarters in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2018-19 NK/2014-15/32112,Roads,Completed,NK-KODAMBAKKAM,127,980000,Repair to storm water Drain at Various street in Dn-127 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32114,Footpath,Completed,NK-KODAMBAKKAM,127,450000,"Improvement to Dn officediv-127, unit-29, zone-10",Own Sources,10,2014-15,2018-19 NK/2014-15/5239,Buildings,Completed,NK-KODAMBAKKAM,127,573000,"Providing and fixing of mobile urinals at five different location in Div-127, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/7203,Roads,Completed,NK-KODAMBAKKAM,127,1719200,"RELAYING OF ROAD USING CEMENT CONCRETE AT AKR ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2014-15,2017-18 BR/2014-15/17505,Roads,Completed,BR-Bus Route Roads,128,4286000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement works at REDDY STREET from the junction of kamarajar salai to kaliamman koil street in ward 128 Zone - 10.,Grants,10,2014-15,2017-18 NK/2014-15/10748,Roads,Completed,NK-KODAMBAKKAM,128,995000,Relaying the road using with BC 40mm thick by mechanical paver at Ganpathraj Nagar main road in Dn:128 Unit:29 Zone:10,Own Sources,10,2014-15,2016-17 NK/2014-15/13009,Parks,Completed,NK-KODAMBAKKAM,128,740000,"MAINTENANCE OF PARK AT ANNAJI NAGAR 2nd STREET VIRUGAMBAKKAM (2 YEARS) IN DIVISION 128,UNIT-29,ZONE-10.(Qualified horticulturist only)",Own Sources,10,2014-15,2016-17 NK/2014-15/13010,Parks,Completed,NK-KODAMBAKKAM,128,700000,"ANNUAL MAINTENANCE OF PARK AT LAMBERT NAGAR AT VIRUGAMBAKKAM (2 YEARS) IN DIVISION 128,UNIT-29,ZONE-10.(Qualified horticulturist only)",Own Sources,10,2014-15,2017-18 NK/2014-15/20126,Buildings,Completed,B-Buildings,128,998000,"PROVIDING GRANITE FLOORING (OUTSIDE) TO THE (UPHC) HOSPITAL IN DN-128, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20267,Buildings,Completed,B-Buildings,128,995000,"SUPPLYING AND FIXING ALUMINIUM DOORS AND WINDOWS TO THE (UPHC) HOSPITAL IN DN-128, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20421,Buildings,Completed,B-Buildings,128,993000,"CONSTRUCTION OF COMPOUND WALL AND GATE AND GATE PILLAR TO THE (UPHC) HOSPITAL IN DN-128, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20550,Roads,Completed,NK-KODAMBAKKAM,128,994000,Relaying the road using with BC 40mm thick by mechanical paver at Patchaiamman koil 2nd Street in Dn:128 Unit:29 Zone:10,Own Sources,10,2014-15,2016-17 NK/2014-15/21334,Buildings,Completed,B-Buildings,128,999000,"PROVIDING DRAINAGE AND ELECTRICAL ARRANGEMENTS (UPHC) HOSPITAL IN DN-128, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30897,Buildings,Completed,NK-KODAMBAKKAM,128,940000,"PROPOSED CONSTRUCTION OF E-SEVA ROOM IN DIV 128,UNIT-29,ZONE-10",Own Sources,10,2014-15,2018-19 NK/2014-15/30898,Buildings,Completed,NK-KODAMBAKKAM,128,960000,"CONSTRUCTION OF PLASTIC CUTTING MACHINE ,ROOM,TOILET AND OTHER IMPROVEMENT WORK AT DN-128,U-29,ZONE-10",Own Sources,10,2014-15,2018-19 NK/2014-15/30899,Buildings,Completed,NK-KODAMBAKKAM,128,910000,"IMPROVEMENTS TO EXISTING AMMA UNAVAGAM AT DN-128,U-29,Z-10",Own Sources,10,2014-15,2018-19 NK/2014-15/30900,Buildings,Completed,NK-KODAMBAKKAM,128,998000,"IMPROVEMENTS TO NNMP SHED AT VARIOUS PLACES IN DN-128,U-29,Z-10",Own Sources,10,2014-15,2018-19 NK/2014-15/31023,Roads,Completed,NK-KODAMBAKKAM,128,996000,"Providing and Laying Cement Concrete Road by using RMC 40 Concrete at Karumariamman Koil Street ( Chainage 0 -75 m ) in Div - 128, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31109,Buildings,Completed,NK-KODAMBAKKAM,128,860000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT CHS SCHOOL VIRUGAKMBAKKAM IN DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31110,Buildings,Completed,NK-KODAMBAKKAM,128,950000,"CONSTRUCTION OF CYCLE SHED AND OTHER IMPROVEMENTS TO VIRUGAMBAKKAM CHS SCHOOL IN DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31130,Roads,Completed,NK-KODAMBAKKAM,128,999000,"Providing Hand Rail to the Park at Annaji Nagar in Div-128, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31131,Buildings,Completed,NK-KODAMBAKKAM,128,999000,"Improvements to the Park at Annaji Nagar in Div-128, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31132,Parks,Completed,NK-KODAMBAKKAM,128,427000,"Improvements to the Park at CR Ramakrishna puram - Phase I L & T Colony in Div-128, Unit-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31215,Parks,Completed,NK-KODAMBAKKAM,128,225000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO ANNAJI RAO PARK AT NESAPAKKAM IN DN-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31223,Buildings,Completed,NK-KODAMBAKKAM,128,350000,"LAYING OF INTER LOCKING PAVER BLOCKS AND OTHER IMPROVEMENTS TO VIRUGAMBAKKAM CHS SCHOOL IN DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31224,Roads,Completed,NK-KODAMBAKKAM,128,990000,"ATTENDING PATCH WORK BY USING WETMIX MACADEM AT SRINIVASA STREET AND OTHER VARIOUS PLACES IN DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31225,Roads,Completed,NK-KODAMBAKKAM,128,980000,"ATTENDING PATCH WORK BY USING WETMIX MACADEM AT ARCOT ROAD AND OTHER VARIOUS PLACES IN DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31240,Roads,Completed,NK-KODAMBAKKAM,128,954000,"Attending Patch Work using RMC 40 at Ottapillaiyar Koil Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2014-15,2018-19 NK/2014-15/31241,Buildings,Completed,NK-KODAMBAKKAM,128,809000,"Attending Patch Work using RMC 40 at Thiruvengadam Street (Ch 100-140M) in Dn. 128, Unit-29, Zone - X",Own Sources,10,2014-15,2017-18 NK/2014-15/31242,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,834000,Raising or lowering Manhole doors at Various streets in Dn 128 Unit 29 Zone X,Own Sources,10,2014-15,2019-20 NK/2014-15/31243,Roads,Completed,NK-KODAMBAKKAM,128,990000,"Attending Patch Work using RMC 40 at Anna Colony in Dn. 128, Unit-29, Zone - X",Own Sources,10,2014-15,2017-18 NK/2014-15/31244,Roads,Completed,NK-KODAMBAKKAM,128,990000,"Attending Patch Work using RMC 40 at Elango Nagar 4th Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31245,Roads,Completed,NK-KODAMBAKKAM,128,900000,"Attending Patch Work using RMC 40 at Thangal Erikkarai cross street in Dn. 128, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31251,Roads,Completed,NK-KODAMBAKKAM,128,2226000,"Proposed and Laying of Cement Concrete Road by using M30 at Gandhi Nagar Main Road in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31252,Roads,Completed,NK-KODAMBAKKAM,128,1017000,"Proposed and Laying of Cement Concrete Road by using M30 at Katabomman Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31253,Roads,Completed,NK-KODAMBAKKAM,128,1681000,"Proposed and Laying of Cement Concrete Road by using M30 at Shaik Abdulla Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31254,Roads,Completed,NK-KODAMBAKKAM,128,2192000,"Proposed and Laying of Cement Concrete Road by using M30 at Mosque Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31256,Roads,Completed,NK-KODAMBAKKAM,128,2070000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 1st Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31257,Roads,Completed,NK-KODAMBAKKAM,128,2154000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 2nd Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31258,Roads,Completed,NK-KODAMBAKKAM,128,2163000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 3rd Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31259,Roads,Completed,NK-KODAMBAKKAM,128,2166000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 5th Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31260,Roads,Completed,NK-KODAMBAKKAM,128,2166000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 6th Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31261,Roads,Completed,NK-KODAMBAKKAM,128,1317000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 7th & 9th Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31262,Roads,Completed,NK-KODAMBAKKAM,128,1686000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 8th Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31263,Roads,Completed,NK-KODAMBAKKAM,128,2009000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 11th Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31264,Roads,Completed,NK-KODAMBAKKAM,128,1290000,"Proposed and Laying of Cement Concrete Road by using M30 at Annai Sathiya Nagar 12th Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31265,Roads,Completed,NK-KODAMBAKKAM,128,1154000,"Proposed and Laying of Cement Concrete Road by using M30 at Thangal Ulvali Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31267,Roads,Completed,NK-KODAMBAKKAM,128,1137000,"Proposed and Laying of Cement Concrete Road by using M30 at Rajiv Gandhi Street in Dn. 128, Unit - 29, Zone -10",Own Sources,10,2014-15,2016-17 NK/2014-15/31278,Roads,Completed,NK-KODAMBAKKAM,128,999000,"Attending Patch Work using RMC 40 at Thiruvengadam Street ( Ch 0 -100M) in Dn. 128, Unit-29, Zone - X",Own Sources,10,2014-15,2017-18 NK/2014-15/31430,Roads,Completed,NK-KODAMBAKKAM,128,476000,"Raising the road level by using wet mix macadam at annai sathya nagar 3rd street(chainage105-210m) in div-128,unit-29, zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31455,Roads,Completed,NK-KODAMBAKKAM,128,730000,"Relaying of Road by using Paver Finisher at CR Puram Annexe Phase IV in Dn - 128, Unit - 29, Zone - 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31456,Roads,Completed,NK-KODAMBAKKAM,128,733000,"Relaying of Road by using Paver Finisher at Elango Nagar Annexe 4th Phase in Dn - 128, Unit - 29, Zone - 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31457,Roads,Completed,NK-KODAMBAKKAM,128,750000,"Relaying of Road by using Paver Finisher at CR Puram Phase I in Dn - 128, Unit - 29, Zone - 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31458,Roads,Completed,NK-KODAMBAKKAM,128,990000,"Relaying of Road by using Paver Finisher at CR Puram Phase II and Jayalakshmi Street in Dn - 128, Unit - 29, Zone - 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31459,Roads,Completed,NK-KODAMBAKKAM,128,991000,"Relaying of Road by using Paver Finisher at Elango Nagar Main Road from Thangal Street to 2nd Main Road in Dn - 128, Unit - 29, Zone - 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31460,Roads,Completed,NK-KODAMBAKKAM,128,989000,"Relaying of Road by using Paver Finisher (from Elango Nagar 2nd Main Road to Kaliamman Koil Road) along Elango Nagar Main Road in Dn - 128, Unit - 29, Zone - 10",Own Sources,10,2014-15,2016-17 NK/2014-15/31574,Roads,Completed,NK-KODAMBAKKAM,128,996000,"Laying of Cement Concrete Road by Using RMC40 Grade at Aanni Sathya Nagar 4th Street (Chainage 0-60M) in DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31575,Roads,Completed,NK-KODAMBAKKAM,128,630000,"Laying of Cement Concrete Road by Using RMC40 Grade at Aanni Sathya Nagar 10th Street (Chainage 45-77M) in DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31576,Roads,Completed,NK-KODAMBAKKAM,128,756000,"Laying of Cement Concrete Road by Using RMC40 Grade at Aanni Sathya Nagar 10th Street (Chainage 0-45M) in DIV-128, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31581,Roads,Completed,NK-KODAMBAKKAM,128,999000,"Laying of Cement Concrete Road by Using RMC 40 Grade at Annai Sathya Nagar 4th Street (Chainage 60 - 121M) in Div - 128, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31585,Roads,Completed,NK-KODAMBAKKAM,128,991000,"Attending Patch Work by Using BC 40mm thick at Various Street in Dn - 128, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31589,Roads,Completed,NK-KODAMBAKKAM,128,500000,"Enganging private Auto with 5 private labours to Dn-128, U-29, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/32042,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,696000,"Improvements to Strom Water Drain at Various street in Dn-128,Unit-29,Zone-x.",Own Sources,10,2014-15,2018-19 NK/2014-15/32043,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,914000,"Dismantling of Top Slab and Raising of Strom Water Drain to the Road level at Virugambakkam Burial ground in Dn-128,Unit-29,Zone-X.",Own Sources,10,2014-15,2017-18 NK/2014-15/32044,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,835000,"Construction of Storm Water Drain Road crossing by using Pre-cast R.C.C Box Type at Virugambakkam Burial ground road in Dn-128,Unit-29,Zone-X.",Own Sources,10,2014-15,2017-18 NK/2014-15/32045,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,988000,"Construction of Storm Water Drain Road crossing by using Pre-cast R.C.C Box Type at Erikkarai Street in Dn-128,Unit-29,Zone-X.",Own Sources,10,2014-15,2018-19 NK/2014-15/32046,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,959000,"Demolition of Existing Strom Water Drain and Construction of SWD by using Pre-cast Slab at Vanniyer Street from Arcot road to Vanniyer Street in Dn-128,Unit-29,Zone-X.",Own Sources,10,2014-15,2017-18 BR/2014-15/30095,Roads,Completed,BR-Bus Route Roads,129,60045000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at KALIAMMAN KOIL STREET From the junction of 100 feet road to Reddy street in ward 127 & 128 in Zone -10.,Grants,10,2014-15,2016-17 D/2014-15/18649,Storm Water Drain,Completed,D-Storm Water Drains,129,7247000,"Construction of storm water Drain of size 1200x1200mm RCC Box type drain along Sathiyamoorthy st part,Rajaji st,Jayaprakash Narayana st and Devakar Nagar from Agathiyar St to Virugambakkam Canal in Dn 129 Zone 10.",JNNURM,10,2014-15,2016-17 D/2014-15/18652,Storm Water Drain,Completed,D-Storm Water Drains,129,7310000,Dismantlingthe existing dilapidated 1200X1200mm brick work Storm water drain and Re-Construction of storm water Drain of size 1200x1200mm RCC Box type drain along Agathiyar st and Sathiyamoorthy st part from Kamaraj St to V.O.C st in Dn 129 Zone 10.,JNNURM,10,2014-15,2016-17 D/2014-15/18907,Storm Water Drain,Completed,D-Storm Water Drains,129,7310000,Dismantling existing dilapidated 1200X1200mm brick work storm water drain and Re construction of storm water drain of size 1200X1200mm RCC Box type drain along Kamaraj st from Arunachalam Road to Agthiyar st in Dn 129 Zone 10,JNNURM,10,2014-15,2016-17 D/2014-15/18912,Storm Water Drain,Completed,D-Storm Water Drains,129,5800000,Dismantling existing dilapidated 600X750mm brick work Storm water drain and Re-Construction of storm water Drain of size 1200x1200mm RCC Box type drain along Sathiya moorthy st Part and Vivekanandar st from V.O.C St to Virugambakkam Canal in Dn 129 Zone 10.,JNNURM,10,2014-15,2016-17 L/2014-15/4165,Electrical,Completed,L-Electrical,129,2833700,"Provision of 87 Nos of 6 mt GI lamp post with LED Fitting at Navalar Main Road,Devaraj Nagar Main Road,Ramar St,Indira St, Azagappan St,Duraiarasan St ,Sethu St,Thiruvalluvar st,Venkatewara 1st,2nd st,Patchayat colony ,Muthamil Nagar in Division-129,Zone-X",Own Sources,10,2014-15,2016-17 NK/2014-15/12648,Parks,Completed,NK-KODAMBAKKAM,129,792000,"PROVIDING GREENARY, BORE WELL AND SS HAND RAIL ARRANGEMENTS AROUND THE PATHWAY AT ANNAMALAI COLONY PLAY GROUND IN DN-129,UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/12656,Parks,Completed,NK-KODAMBAKKAM,129,720000,"Annual Maintenance of Park at Arcot Road O.S.R. Park in Saligramam Dn.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for 2 years )",Own Sources,10,2014-15,2017-18 NK/2014-15/13005,Parks,Completed,NK-KODAMBAKKAM,129,760000,"Annual Maintenance of Park at Bhaskar Colony Park in Dn.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for 2 years )",Own Sources,10,2014-15,2017-18 NK/2014-15/17686,Parks,Completed,NK-KODAMBAKKAM,129,760000,"IMPROVEMENTS TO THE CHILDRENS PLAY AND PARK AT ARCOT ROAD IN DN-129,UNIT-29,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/19562,Parks,Completed,NK-KODAMBAKKAM,129,800000,"Annual Maintenance of Park at Arcot road (Jain apartments) and Arcot road (Parameswaran vihar) in Saligramam DN.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for 2 years)",Own Sources,10,2014-15,2017-18 NK/2014-15/19563,Parks,Completed,NK-KODAMBAKKAM,129,680000,"Annual Maintenance of Park at Pillayar koil street Park and Navallar main road Park in Dn.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for Two year )",Own Sources,10,2014-15,2017-18 NK/2014-15/19564,Parks,Completed,NK-KODAMBAKKAM,129,750000,"Annual Maintenance of Park at Abusali road Park in Dn.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for Two year )",Own Sources,10,2014-15,2017-18 NK/2014-15/19804,Roads,Completed,NK-KODAMBAKKAM,129,967000,"LAYING OF BITUMINOUS MACADAM AT RAJAJI COLONY, MUTHURAMALUINGAM STREET IN DIV - 129, UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/20269,Parks,Completed,NK-KODAMBAKKAM,129,998000,"IMPROVEMENTS TO THE PATH WAY IN SIDE THE PARK AT ABUSALI ROAD ( AROUND PLAY AREA ) IN DN.129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20270,Parks,Completed,NK-KODAMBAKKAM,129,995000,"IMPROVEMENTS TO THE PARK AT ABUSALI STREET (SOUTH SIDE) IN DN.129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20272,Parks,Completed,NK-KODAMBAKKAM,129,820000,"PROVIDING GREENARY ARRANGEMENTS AND PLAY APPARATUS TO THE CHILDREN'S PLAY AND PARK AT KAVERI RANGAN NAGAR IN DN 129,UNIT-29,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20274,Parks,Completed,NK-KODAMBAKKAM,129,587000,"IMPROVEMENTS TO THE CHILDREN'S PLAY AND PARK AT KAVERI RANGAN NAGAR IN DN 129,UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/23128,Roads,Completed,NK-KODAMBAKKAM,129,560000,"LAYING OF WET MIX MACADAM AT RAJAJI COLONY, MUTHURAMALUINGAM STREET IN DIV - 129, UNIT-29,ZONE-10.",Own Sources,10,2014-15,2019-20 NK/2014-15/23869,Roads,Completed,NK-KODAMBAKKAM,129,267000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE WITH PAVER FINISHER ANNA STREET 2ND CROSS (L=60, A=360M2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/23931,Roads,Completed,NK-KODAMBAKKAM,129,262000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT DURAIRAJ STREET DEVARAJ NAGAR ( L=70 m, A=350 m2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/23939,Roads,Completed,NK-KODAMBAKKAM,129,562000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT INDIRA STREET DEVARAJ NAGAR ( L=150 m, A=750 m2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/23959,Roads,Completed,NK-KODAMBAKKAM,129,579000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT VOC STREET, DEVARAJ NAGAR ( L=130 m, A=780 m2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/23962,Parks,Completed,NK-KODAMBAKKAM,129,556000,"IMPROVEMENTS TO THE PATHWAY AT BASKAR COLONY PARK (ENTRANCE OUT SIDE) IN DIV-129, U-29, Z-10 (UNDER WARD COUNCILLOR FOUND 2015-2016)",Own Sources,10,2014-15,2016-17 NK/2014-15/23967,Parks,Completed,NK-KODAMBAKKAM,129,996000,"IIMPROVEMENTS TO THE PATH WAY IN SIDE THE PARK AT ABUSALI ROAD ( OUTER CIRCLE) IN DN.129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/23997,Roads,Completed,NK-KODAMBAKKAM,129,300000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT BASKAR STREET, NEHRU NAGAR (L=80, AREA= 400 M2)IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/24003,Roads,Completed,NK-KODAMBAKKAM,129,375000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT SETHU STREET, NEHRU NAGAR (L=100 M, A=500 M2 )IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/24010,Roads,Completed,NK-KODAMBAKKAM,129,647000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT RATHINAMMAL COLONY EXTN., GANDHI NAGAR (L=150 M, A=870 M2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/24018,Roads,Completed,NK-KODAMBAKKAM,129,837000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT V.O.C STREET, GANDHI NAGAR (L=300 M, A=1350 M2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/24027,Roads,Completed,NK-KODAMBAKKAM,129,554000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT RAJENDRA COLONY IN (L=115 M,A=750 M2) DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/24058,Roads,Completed,NK-KODAMBAKKAM,129,750000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT VENKATESA NAGAR 2ND STREET(L=200 M,A=1000 M2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/24059,Parks,Completed,NK-KODAMBAKKAM,129,240000,"SUPPLYING AND FIXING GYM EQUIPMENT AND CHAIRS TO CHILDREN PLAY SPACE AT SHANTHI COLONY, THILLAIADI VALLIAMMAI STREET IN DN-129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/24061,Roads,Completed,NK-KODAMBAKKAM,129,574000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT THIRUVALLUVAR STREET, NEHRU NAGAR (L=140 M,A=770 M2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/24065,Parks,Completed,NK-KODAMBAKKAM,129,988000,"IMPROVEMENTS TO THE PATH WAY IN SIDE THE PARK AT ABUSALI ROAD ( INNER CIRCLE) IN DN.129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/24071,Parks,Completed,NK-KODAMBAKKAM,129,680000,"CONSTRUCTION OF PUMP ROOM TO THE PARK AT ABUSALI STREET IN DN-129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/24074,Roads,Completed,NK-KODAMBAKKAM,129,329000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT DASARATHAPURAM 4TH STREET(L=90 M, A=450 M2)IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/28571,Electrical,Completed,NK-KODAMBAKKAM,129,659600,"WORK: Provision of 11 nos 6 mtr stright bracket and 12nos of 6mtr Arch Hot Dip Zinc galvanising Lamp Post at Ambedkar street,Gangadharan street and K.K.Salai in Division-129, Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/28574,Electrical,Completed,NK-KODAMBAKKAM,129,933000,"WORK: Provision of 35 nos 6 mtr stright bracket Hot Dip Zinc galvanising Lamp Post with 70W SVL fitting at Kumaran Colony 1street to 5th street in Division-129, Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/28575,Electrical,Completed,NK-KODAMBAKKAM,129,961300,"WORK: Provision of 25 nos 6 mtr stright bracket and9nos of 6mtr Arch Hot Dip Zinc galvanising Lamp Post at Dhanalakshmi colony,Senthil Andavar street and KG street in Division-129, Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/29886,Parks,Completed,NK-KODAMBAKKAM,129,995000,"IMPROVEMENTS TO CHILDRENS PLAY SPACE AT SHANTHI COLONY, THILLAIADE VALLIAMMAI STREET IN DN-129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31147,Parks,Completed,NK-KODAMBAKKAM,129,785000,"IMPROVEMENTS TO THE PARK AT ABUSALI STREET (FRONT SIDE) IN DN-129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31416,Roads,Completed,NK-KODAMBAKKAM,129,980000,"RELAYING OF BT ROAD BY MECHANICAL PAVER AT ABUSALI STREET (REACH 1) IN DIV-129, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31422,Roads,Completed,NK-KODAMBAKKAM,129,980000,"RELAYING OF BT ROAD BY MECHANICAL PAVER AT ABUSALI STREET (REACH 2) IN DIV-129, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31423,Roads,Completed,NK-KODAMBAKKAM,129,980000,"RELAYING OF BT ROAD BY MECHANICAL PAVER AT ABUSALI STREET (REACH 3) IN DIV-129, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31424,Roads,Completed,NK-KODAMBAKKAM,129,614252,"PROPOSED RELAYING OF BT ROAD BY MECHANICAL PAVER AT ILANGO STREET IN DIV -129, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31587,Roads,Completed,NK-KODAMBAKKAM,129,880000,"Relaying of Road by using BC 40mm Thick by Paver Finisher at Anna Street in Dn. 129, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31588,Roads,Completed,NK-KODAMBAKKAM,129,990000,"Relaying of Road by using BC 40mm Thick by Paver Finisher at Canara Bank Street in Dn. 129, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31822,Roads,Completed,NK-KODAMBAKKAM,129,868000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER AT PERIYAR STREET, GANDHI NAGAR (L=280 M, A=1400 M2) IN DN-129, UNIT-29 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31865,Roads,Completed,NK-KODAMBAKKAM,129,980000,"ATTENDING PATCH WORK USING RMC 40 AT THIVAGAR NAGAR CANAL ROAD IN DN 129,UNIT 29,ZONE 10",Own Sources,10,2014-15,2017-18 NK/2014-15/31866,Roads,Completed,NK-KODAMBAKKAM,129,980000,Attending patch work using RMC 40 at canara bank colony ch 0-75 in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/31871,Roads,Completed,NK-KODAMBAKKAM,129,520000,"Providing and laying wet mix macadam at Thivagar nagar 3rd street in div 129,u-29,zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31915,Roads,Completed,NK-KODAMBAKKAM,129,960000,Laying of the road using RMC 40 at Thivakar nagar canal road in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31916,Roads,Completed,NK-KODAMBAKKAM,129,980000,"ATTENDING PATCH WORK USING RMC 40 AT NEHRU NAGAR MAIN ROAD IN DN-129,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2017-18 NK/2014-15/31918,Roads,Completed,NK-KODAMBAKKAM,129,980000,"Laying of the road using RMC 40 at Anna street ch 0-60m in div-129, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31919,Roads,Completed,NK-KODAMBAKKAM,129,989000,"Laying of the road using RMC 40 at Anna street ch 60-120 m in div-129, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31923,Roads,Completed,NK-KODAMBAKKAM,129,990000,"Laying of the road using RMC 40 at jeeva street ch 60-120m in div-129, unit-29, zone-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31965,Roads,Completed,NK-KODAMBAKKAM,129,910000,Attending patch work at various street in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/31976,Roads,Completed,NK-KODAMBAKKAM,129,980000,"RELAYING OF BT ROAD BY MECHANICAL PAVER AT ABUSALI STREET(REACH 4) IN DIV-129, U-29, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31987,Roads,Completed,NK-KODAMBAKKAM,129,990000,Repair to Storm water drain at Various street in Dn -129 u-29 z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/31988,Roads,Completed,NK-KODAMBAKKAM,129,990000,Repair to foot path at Arcot road (south side) in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/31989,Roads,Completed,NK-KODAMBAKKAM,129,980000,Repair to foot path at Arcot road (North side) in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32016,Roads,Completed,NK-KODAMBAKKAM,129,980000,Providing and fixing SS hand rail at Velayutham colony park (North and South side) in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32103,Roads,Completed,NK-KODAMBAKKAM,129,980000,"Improvement to division office at Arunachalam road in Div 129,U-29,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32108,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,980000,Attending patch work using RMC 40 at Various street in Dn-129 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/7194,Electrical,Completed,NK-KODAMBAKKAM,129,946400,"Provision of Addl Electrification of Newly Proposed Meditation center and erection of 5 Nos of 3 mt lamp post and 4 Nos of 6 mt lamp post with Fitting at Basker Colony Park and Provision of 45 Nos of 3 mt lamp post with Fitting at Abusali Park in Division-129,Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/0073,Roads,Completed,NK-KODAMBAKKAM,130,940000,"Attending pacth work at various street in Dn. 130, Unit - 29, Zone- 10",Own Sources,10,2014-15,2016-17 NK/2014-15/22136,Roads,Completed,NK-KODAMBAKKAM,130,980000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Amman Koil Street(East) in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22137,Roads,Completed,NK-KODAMBAKKAM,130,840000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Palani Andavar koil Street (Arcot Road JN to Amman Koil Street JN ) in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22138,Roads,Completed,NK-KODAMBAKKAM,130,400000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Dharansingh colony 3rd Street in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22139,Roads,Completed,NK-KODAMBAKKAM,130,480000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Dharansingh colony 2nd Street in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22140,Roads,Completed,NK-KODAMBAKKAM,130,540000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Venkateshwara Street in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22141,Roads,Completed,NK-KODAMBAKKAM,130,550000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Thiru nagar 6th Street in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22142,Roads,Completed,NK-KODAMBAKKAM,130,515000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Thiru nagar 3rd Street in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22143,Roads,Completed,NK-KODAMBAKKAM,130,860000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Thiru nagar 2nd Street in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/22442,Roads,Completed,NK-KODAMBAKKAM,130,350000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Gangaiamman koil Street(saligramam) in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/29282,Buildings,Completed,NK-KODAMBAKKAM,130,749000,"Construction of Ration shop at Rajanga Mathiya Veethi in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30431,Buildings,Completed,NK-KODAMBAKKAM,130,940000,"Improvement of SWD at Gangai amman koil street (From Andavar nagar 3rd street to Andavar nagar 5th street)(Chainage from 0-45m) in DN-130,UNIT-29,ZONE-10.A",Own Sources,10,2014-15,2016-17 NK/2014-15/30432,Buildings,Completed,NK-KODAMBAKKAM,130,680000,"Improvement of SWD at Gangai amman koil street (From Ragavan Colony Police booth to Andavar nagar 3rd street)(Chainage from 35-67.50m) in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30434,Buildings,Completed,NK-KODAMBAKKAM,130,940000,"Improvement of SWD at Gangai amman koil street (From Andavar nagar 3rd street to Andavar nagar 5th street)(Chainage from 45-90m) in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30435,Buildings,Completed,NK-KODAMBAKKAM,130,750000,"Improvement of SWD at Gangai amman koil street (From Ragavan Colony Police booth to Andavar nagar 3rd street)(Chainage from 0-35m) in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30438,Roads,Completed,NK-KODAMBAKKAM,130,430000,"Providing Cover Slab and FRCC Door Arrangements at SWD (From Andavar nagar 5th Street to Andavar nagar 6th Street) in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30439,Buildings,Completed,NK-KODAMBAKKAM,130,960000,"Improvement of SWD at Gangai amman koil street (From Andavar nagar 3rd street to Andavar nagar 5th street)(Chainage from 90-136m) in DN-130,UNIT-29,ZONE-10.A",Own Sources,10,2014-15,2016-17 NK/2014-15/30592,Buildings,Completed,NK-KODAMBAKKAM,130,490000,"Letter writing work for CMS Building and L.K.G , U.K.G and school building in Dn-130 U-29 Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/30599,Buildings,Completed,NK-KODAMBAKKAM,130,740000,Improvement to SWD at Gangai amman koil street ( from Andavar nagar 6th street to periya pathai (60m - 102.50) in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/30600,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,990000,Improvement to SWD at Gangai amman koil street ( from Andavar nagar 6th street to periya pathai (0-60m ) in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/30601,Buildings,Completed,NK-KODAMBAKKAM,130,750000,"Art painting work at CMS and LKG, UKG Building in Dn-130 U-29 Z-10",Own Sources,10,2014-15,2018-19 NK/2014-15/30608,Buildings,Completed,NK-KODAMBAKKAM,130,780000,"Providing and Fixing GI Roof Sheet and others improvements at Chennai Middle School in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30613,Roads,Completed,NK-KODAMBAKKAM,130,993000,"TREE PLANTATION ALONG WITH TREE GUARD AT VARIOUS LOCATIONS IN DN-130,132 & 133 U-29 & 30, Z-10",Own Sources,10,2014-15,2019-20 NK/2014-15/30621,Roads,Completed,NK-KODAMBAKKAM,130,410000,"Providing Aluminium partition and MS Door in LKG,UKG Building in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30622,Buildings,Completed,NK-KODAMBAKKAM,130,960000,"Improvement to CMS Building and LKG and UKG Room in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30624,Buildings,Completed,NK-KODAMBAKKAM,130,750000,"Improvement to second floor of Dispensary at Rajanga mathiya veethi in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2017-18 NK/2014-15/30627,Buildings,Completed,NK-KODAMBAKKAM,130,640000,"Providing Staircase head room and Terrace flooring at dispensary in Rajanga mathiya veethi in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30651,Buildings,Completed,NK-KODAMBAKKAM,130,677000,"Providing wall tiles at staircase room in Dispensary at Rajanga Mathiya Veethi in DN-130,UNIT-29,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31012,Roads,Completed,NK-KODAMBAKKAM,130,710000,"Road Crossing at Gangai Amman Koil Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31063,Playfields,Completed,NK-KODAMBAKKAM,130,830000,Improvement to children park at Doshi Garden in Arcot Road in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31064,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,900000,Improvement to SWD at Amman koil street (from 100ft road to ponnammal street)in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31065,Parks,Completed,NK-KODAMBAKKAM,130,710000,Supplying and fixing with S.S Hand raIl at Doshi Garden park In Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31079,Roads,Completed,NK-KODAMBAKKAM,130,620000,"Providing High Mast Dwart Wall at Alagar Perumal Koil Street, Palani Andavar Koil Street, South Mada Street and North Mada Street in Dn - 130 Unit - 29, Zone - 10",Own Sources,10,2014-15,2017-18 NK/2014-15/31095,Roads,Completed,NK-KODAMBAKKAM,130,850000,Improvement to corporation Dispensary G.F at Rajanga mathiya veethi in Dn -130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31097,Buildings,Completed,NK-KODAMBAKKAM,130,810000,"Providing floor tiles and wall tiles at corporation Dispensary 1st.Floor Rajanga mathiya veethi in Dn - 130 U-29 Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31098,Buildings,Completed,NK-KODAMBAKKAM,130,750000,Providing Aluminium partition work at GF of Chennai Dispensary at Rajanga mathiya veethi in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31099,Buildings,Completed,NK-KODAMBAKKAM,130,740000,Providing sump well at Corporation Dispensary at Rajanga mathiya veethi in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31101,Buildings,Completed,NK-KODAMBAKKAM,130,600000,Improvement to PC at west sivan koil street in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31133,Roads,Completed,NK-KODAMBAKKAM,130,840000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Palani Andavar koil Street ( Amman Koil Street JN to Vadapalani Murugan Koil ) in Dn- 130, Unit- 29, Zone- 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31135,Roads,Completed,NK-KODAMBAKKAM,130,870000,"Relaying of the road by using SDBC 40mm thick by Mechanical Paver Finisher at Thiru nagar 5th Street in Dn- 130, Unit- 29, Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31150,Roads,Completed,NK-KODAMBAKKAM,130,224000,Widening of Road at Dharansingh colony 2nd street (vengateshwara street to nerkundram road ) in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31156,Roads,Completed,NK-KODAMBAKKAM,130,410000,Providing and Laying wetmix Macadam at various street in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31163,Roads,Completed,NK-KODAMBAKKAM,130,950000,Proposed Laying cement concrete road at South mada veethi CH 60-120 in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31164,Roads,Completed,NK-KODAMBAKKAM,130,980000,Proposed Laying cement concrete road using RMC 40 at South mada veethi CH 0 - 90 in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31165,Roads,Completed,NK-KODAMBAKKAM,130,520000,Proposed Laying cement concrete road using RMC 40 at South mada veethi CH 90 - 120 in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31178,Roads,Completed,NK-KODAMBAKKAM,130,860000,Proposed laying cement concrete using RMC 40 at West mada street CH 0-75 in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31571,Roads,Completed,NK-KODAMBAKKAM,130,828023,Laying of Wet Mix Macadam at Nerkundram Pathai Cross Street in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2016-17 NK/2014-15/31653,Roads,Completed,NK-KODAMBAKKAM,130,895000,"Laying of Cement Concrete Road at Natheem Garden in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31654,Roads,Completed,NK-KODAMBAKKAM,130,641000,"Laying of Wet Mix Macadam at Venkateswara Street, Dharan singh Colony II & III Street in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31655,Roads,Completed,NK-KODAMBAKKAM,130,149000,"Strengthening of Road by Using Wet Mix Macadam at Ponnammal Street in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31677,Roads,Completed,NK-KODAMBAKKAM,130,890000,"Attending Patch Work by using BC 40 mm thick by Mechanical Paver Finisher at Various Streets in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31678,Roads,Completed,NK-KODAMBAKKAM,130,910000,"Attending Patch Work by using BC 40 mm thick by Mechanical Paver Finisher at Various Streets in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31679,Roads,Completed,NK-KODAMBAKKAM,130,997000,"Providing and Fixing of Thermoplastic Paint Marking and Reflective Pavement Marker (RPM) at various street in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31680,Roads,Completed,NK-KODAMBAKKAM,130,997000,"Providing and Fixing of Thermoplastic Paint Marking and Reflective Pavement Marker (RPM) at various street in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31682,Roads,Completed,NK-KODAMBAKKAM,130,590000,"Engaging Private Auto Vehicle with 6 Private Labours for 6 months (01.01.2015 to 30.06.2015) in Dn - 130, Unit-29, Zone-X",Own Sources,10,2014-15,2016-17 NK/2014-15/31683,Roads,Completed,NK-KODAMBAKKAM,130,208000,"Engaging Private Auto Vehicle with 6 Private Labours for 2 months (01.04.2015 to 31.05.2015) in Dn - 130, Unit-29, Zone-X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31686,Roads,Completed,NK-KODAMBAKKAM,130,624000,"Providing and fixing of Display Board of Amma Schemes at Various Street in Dn - 130 Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31687,Roads,Completed,NK-KODAMBAKKAM,130,624000,"Providing and fixing of Display Board of Amma Schemes at Various Street in Dn - 130 Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31691,Roads,Completed,NK-KODAMBAKKAM,130,467000,"Strengthening and Relaying of Road by using DBMC 50mm thick at Rajangam Mathiya Veethi in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31692,Roads,Completed,NK-KODAMBAKKAM,130,435000,"Strengthening and Relaying of Road by using DBMC 50mm thick at Gangaiamman Koil Street (Saligrammam) in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31693,Roads,Completed,NK-KODAMBAKKAM,130,800000,"Strengthening and Relaying of Road by using DBMC 50mm thick at Amman Koil Street (West) in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31694,Roads,Completed,NK-KODAMBAKKAM,130,672000,"Strengthening and Relaying of Road by using DBMC 50mm thick at Ponnammal Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31695,Roads,Completed,NK-KODAMBAKKAM,130,545000,"Strengthening and Relaying of Road by using DBMC 50mm thick at Bajanai Koil 1st Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31696,Roads,Completed,NK-KODAMBAKKAM,130,250000,"Strengthening and Relaying of Road by using DBMC 50mm thick at Bajanai Koil Cross Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31697,Roads,Completed,NK-KODAMBAKKAM,130,693000,"Strengthening and Relaying of Road by using DBMC 50mm thick at Bajanai Koil 2nd Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31698,Footpath,Completed,NK-KODAMBAKKAM,130,353000,"Removing and Refixing of CC Footpath at Kumaran Colony 7th and 8th Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31699,Footpath,Completed,NK-KODAMBAKKAM,130,645000,"Removing and Refixing of CC Footpath at Karumariamman Koil Street and Alagiri Nagar 1 st Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31700,Footpath,Completed,NK-KODAMBAKKAM,130,279000,"Removing and Refixing of CC Footpath at Alagar Perumal Koil Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31701,Footpath,Completed,NK-KODAMBAKKAM,130,252000,"Removing and Refixing of CC Footpath at Dharan Singh Colony 1st Street in Dn.- 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31705,Buildings,Completed,NK-KODAMBAKKAM,130,756000,"Providing Water Supply and Electrical Arrangements in Amma Unavagam Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31706,Buildings,Completed,NK-KODAMBAKKAM,130,789000,"Improvements to Amma Unavagam at Nerkundrum Pathai in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31707,Buildings,Completed,NK-KODAMBAKKAM,130,944000,"Providing Outer Walker Path to Amma Unavagam at Nerkundrum Pathai in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31708,Buildings,Completed,NK-KODAMBAKKAM,130,433000,"Providing and Fixing of one course Pressed Tiles in Amma Unavagam Building at Nerkundrum Pathai in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31709,Buildings,Completed,NK-KODAMBAKKAM,130,984000,"Proposed Construction of Multi - Purpose Hall at Alagiri Nagar 1st street in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2017-18 NK/2014-15/31711,Buildings,Completed,NK-KODAMBAKKAM,130,989000,"Proposed Construction of Amma Unavagam (Basement Level) at Nerkundram Pathai in Dn - 130, Unit - 29 , Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31713,Buildings,Completed,NK-KODAMBAKKAM,130,609000,"Additional Improvements to Amma Unavagam Building at Nerkundram Pathai in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31716,Buildings,Completed,NK-KODAMBAKKAM,130,360000,"Providing and Fixing of one course Pressed Tiles in Multi - Purpose Hall (TUCS Building Roof) at Alagiri Nagar 1st street in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31723,Roads,Completed,NK-KODAMBAKKAM,130,760000,"Supplying and fixing with S.S Hand rail at Doshi Graden park in Dn. 130, Unit 29, Zone X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31780,Buildings,Completed,NK-KODAMBAKKAM,130,470000,"Providing Water Supply and Electrical arrangements to Amma Unavagam at Nerkundrum Pathai in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31781,Buildings,Completed,NK-KODAMBAKKAM,130,990000,"Providing Compound Wall and Cement Concrete Road in Amma Unavagam at Nerkundrum Pathai in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31788,Roads,Completed,NK-KODAMBAKKAM,130,760000,"Raising and Widening of Road at Alagiri Nagar Main Road in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31791,Roads,Completed,NK-KODAMBAKKAM,130,611000,"Raising and Widening of Road at Alagiri Nagar East Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31796,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,317000,"RAISING OF STROM WATER DRAIN MAN HOLE DOOR AT VARIOUS STREET IN DIV-130,UNIT-29,ZONE-X",Own Sources,10,2014-15,2017-18 NK/2014-15/31801,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,804000,"DEMOLITION AND RECONSTRUCTION OF STORM WATER DRAIN AT THIRU NAGAR MAIN ROAD FROM THIRU NAGAR 6TH STREET TO CANAL IN DIV-130,UNIT-29,ZONE-X",Own Sources,10,2014-15,2016-17 NK/2014-15/31802,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,804000,"DEMOLITION AND RECONSTRUCTION OF STORM WATER DRAIN AT THIRU NAGAR MAIN ROAD FROM THIRU NAGAR 4TH STREET TO THIRU NAGAR 6TH STREET IN DIV-130,UNIT-29,ZONE-X",Own Sources,10,2014-15,2016-17 NK/2014-15/31803,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,804000,"DEMOLITION AND RECONSTRUCTION OF STORM WATER DRAIN AT THIRU NAGAR MAIN ROAD FROM VELLALR STREET TO THIRU NAGAR 4TH STREET IN DIV-130,UNIT-29,ZONE-X",Own Sources,10,2014-15,2017-18 NK/2014-15/31826,Roads,Completed,NK-KODAMBAKKAM,130,794000,"Improvements to Footpath at Arcot Road in Front of Vijaya Hospital in Dn-130, Unit-29, Zone-X",Own Sources,10,2014-15,2016-17 NK/2014-15/31827,Roads,Completed,NK-KODAMBAKKAM,130,999000,"Providing and Fixing of Stainless Steel Handrail to Footpath at Arcot Road in Front of Vijaya Hospital in Dn-130, Unit-29, Zone-X",Own Sources,10,2014-15,2016-17 NK/2014-15/31828,Roads,Completed,NK-KODAMBAKKAM,130,403000,"Raising of Road by Using Wet Mix Macadam at Thiru Nagar 3rd Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31829,Roads,Completed,NK-KODAMBAKKAM,130,579000,"Raising of Road by Using Wet Mix Macadam at Thiru Nagar 5th Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31830,Roads,Completed,NK-KODAMBAKKAM,130,590000,"Raising of Road by Using Wet Mix Macadam at Dharansingh Colony 2nd Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31831,Roads,Completed,NK-KODAMBAKKAM,130,600000,"Raising of Road by Using Wet Mix Macadam at Dharansingh Colony 3rd Street & Venkateswara Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31833,Footpath,Completed,NK-KODAMBAKKAM,130,641000,"Improvements to the existing Footpath at Alagiri Nagar Main Road in Dn - 130, Unit - 29, Zone - X",Own Sources,10,2014-15,2016-17 NK/2014-15/31840,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,511000,"De-Silting of Storm Water Drain at Alagiri Nagar 6th Street,Alagiri Nagar Main road,Arcot Road,Othavada Street in Div-130,U-29,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31841,Roads,Completed,NK-KODAMBAKKAM,130,955000,"Widening of Road by using WMM, P.C.C 1:4:8 and RMC 40 at Kumaran Colony Main Road (Ch 0 - 170m) in Dn-130, Unit-29, Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/31842,Roads,Completed,NK-KODAMBAKKAM,130,955000,"Widening of Road by using WMM, P.C.C 1:4:8 and RMC 40 at Kumaran Colony Main Road (Ch 170 - 340m) in Dn-130, Unit-29, Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/31843,Roads,Completed,NK-KODAMBAKKAM,130,955000,"Widening of Road by using WMM, P.C.C 1:4:8 and RMC 40 at Kumaran Colony Main Road (Ch 340 - 510m) in Dn-130, Unit-29, Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/31844,Roads,Completed,NK-KODAMBAKKAM,130,753000,"Widening of Road by using WMM, P.C.C 1:4:8 and RMC 40 at Kumaran Colony Main Road (Ch 510 - 633m) in Dn-130, Unit-29, Zone-X",Own Sources,10,2014-15,2016-17 NK/2014-15/32032,Roads,Completed,NK-KODAMBAKKAM,130,770000,"Raising and Stregnthening of Road by using Wet Mix Macadam at North Mada Street in Dn-130, Unit-29, Zone - X",Own Sources,10,2014-15,2018-19 NK/2014-15/32033,Roads,Completed,NK-KODAMBAKKAM,130,654000,"Raising and Strengthening of Road by using Wet Mix Macadam at South Sivan Koil Street in Dn-130, Unit-29, Zone - X",Own Sources,10,2014-15,2018-19 NK/2014-15/32037,Roads,Completed,NK-KODAMBAKKAM,130,942000,"Raising and Strengthening of Road by using Wet Mix Macadam at Sannidhi Street in Dn-130, Unit-29, Zone - X",Own Sources,10,2014-15,2018-19 NK/2014-15/32040,Roads,Completed,NK-KODAMBAKKAM,130,586000,"Raising and Strengthening of Road by using Wet Mix Macadam at Pillaiayar Koil Street in Dn-130, Unit-29, Zone - X",Own Sources,10,2014-15,2017-18 NK/2014-15/32066,Roads,Completed,NK-KODAMBAKKAM,130,990000,"Providing Rain Water Harvesting Structure using precast well ring size 1200 (outer dia) x 4500mm (Height) (300mm x 15 nos) x40mm (thk) using 1:1.5:3 concrete necessary earthwork excavation, filling with 20mm HBG metal out side peripheral of the well, providing of RCC frame and covered with RCC cover slab , cleaning the site and finishing etc., complete at Various Locations in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2017-18 NK/2014-15/32067,Buildings,Completed,NK-KODAMBAKKAM,130,690000,"PROVIDING E TOILET AT PALANI ANDAVAR KOIL STREET AND NERKUNDRAM PATHAI IN DIV-130, UNIT-29, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/32102,Roads,Completed,NK-KODAMBAKKAM,130,960000,Improvement to 16th ceremony hall at south mada street in Dn-130 U-29 Z-10,Own Sources,10,2014-15,2017-18 NK/2014-15/32109,Roads,Completed,NK-KODAMBAKKAM,130,996000,"Providing and laying wetmix macadam at Alagiri nagar 1st street in Dn:130, Unit 29, Zone 10",Own Sources,10,2014-15,2017-18 NK/2014-15/32113,Roads,Completed,NK-KODAMBAKKAM,130,990000,"Providing Rain Water Harvesting Structure using precast well ring size 1200 (outer dia) x 4500mm (Height) (300mm x 15 nos) x40mm (thk) using 1:1.5:3 concrete necessary earthwork excavation, filling with 20mm HBG metal out side peripheral of the well, providing of RCC frame and covered with RCC cover slab , cleaning the site and finishing etc., complete at Various Locations in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2014-15,2018-19 NK/2014-15/7811,Buildings,Completed,NK-KODAMBAKKAM,130,3190000,"Proposed Construction of M. S. Sheet Roofing Shed at Vadapalani Andavar Koil Street (Under MLA Scheme) in Dn-130, Unit-29, Zone - 10",MLACDS,10,2014-15,2016-17 NK/2014-15/21629,Buildings,Completed,NK-KODAMBAKKAM,131,810000,"IMPROVEMENTS TO PLAYFIELD AT RANI ANNA NAGAR OPPOSITE TO 10th BLOCK IN DN-131, U-28, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/22263,Buildings,Completed,NK-KODAMBAKKAM,131,795000,"PROVIDING SAFETY COMPOUND WALL FOR TNEB TRANSFORMERS AT P.T RAJAN SALAI AND VARIOUS ROADS IN DN-131, U-28, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/22434,Buildings,Completed,NK-KODAMBAKKAM,131,1415000,"SUPPLYING AND FIXING OF MILD STEEL GRILLS AT SIVANPARK COMPOUND WALL IN DN-131, U-28, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/2420,Roads,Completed,NK-KODAMBAKKAM,131,991000,"PROPOSED CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER AT WEST SIDE P.T.RAJAN SALAI (OFF SIVAN PARK) IN DIVISION-131,UNIT-28, ZONE-10 (UNDER WARD COUNCILLOR FUND)",Own Sources,10,2014-15,2016-17 NK/2014-15/25889,Roads,Completed,NK-KODAMBAKKAM,131,1131000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINISHER AT13th SECTOR 83rd STREET DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/25898,Roads,Completed,NK-KODAMBAKKAM,131,1081000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINISHER AT 13 SECTAR 86 STREET DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/25905,Roads,Completed,NK-KODAMBAKKAM,131,1022000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINISHER AT13 SECTAR 87 STREET DN-131,Z-10,U-28",Own Sources,10,2014-15,2016-17 NK/2014-15/25913,Roads,Completed,NK-KODAMBAKKAM,131,230000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINISHER AT13 SECTAR 88 STREET DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/25918,Roads,Completed,NK-KODAMBAKKAM,131,474000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINISHER AT 13 SECTOR 89 STREET DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26014,Roads,Completed,NK-KODAMBAKKAM,131,421000,"RELAYING THE ROAD BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINICER AT 13th SECTOR 90th STREET IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26031,Roads,Completed,NK-KODAMBAKKAM,131,472000,"RELAYING THE ROAD BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINICER AT 13th SECTOR 91st STREET IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26036,Roads,Completed,NK-KODAMBAKKAM,131,250000,"RELAYING THE ROAD BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINICER AT 13th SECTOR 92nd STREET IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26042,Roads,Completed,NK-KODAMBAKKAM,131,3780000,"RELAYING THE ROAD BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINICER AT BOBBILI RAJA SALAI IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26053,Roads,Completed,NK-KODAMBAKKAM,131,1343000,"RELAYING THE ROAD BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINICER AT PANNEER SELVAM SALAI IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26078,Roads,Completed,NK-KODAMBAKKAM,131,491000,"RELAYING THE ROAD BITUMINOUS CONCRETE AND CAMBER CORRECTION AT T.S.LAKHSMANAN SALAI IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26086,Roads,Completed,NK-KODAMBAKKAM,131,421000,"RELAYING THE ROAD BITUMINOUS CONCRETE AND CAMBER CORRECTION BY PAVER FINICER AT KODIKATTHA KUMARAN STREET IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26518,Buildings,Completed,NK-KODAMBAKKAM,131,846000,"PROVIDING AND LAYING C.C ROAD M-20 GRADE CONCRETE WITH RMC CONCRETE AT MGR NAGAR,ALAGIRI STREET IN DN-131,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/29711,Buildings,Completed,NK-KODAMBAKKAM,131,755000,"DEMOLICTION AND RECONSTRUCTION OF COMPOUND WALL AT RANI ANNA NAGAR (BLOCK- 23 & AVM BURIAL GROUND) IN DN-131,U-28, Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/7826,Buildings,Completed,NK-KODAMBAKKAM,131,992000,"PROVIDING ALUMINIUM COMPOSITE BOARD AMMA UNAVAGAM (PART-1) AT P.V.RAJAMANNAR SALAI K.K.NAGAR IN DN-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8197,Parks,Completed,NK-KODAMBAKKAM,131,940000,"PROVIDING ALUMINIUM COMPOSITE BOARD AMMA UNAVAGAM (PART-2) AT P.V.RAJAMANNAR SALAI K.K.NAGAR IN DN-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8332,Roads,Completed,NK-KODAMBAKKAM,131,2929000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT SATHIYA GARDEN, CHAKKARAPANI STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8370,Roads,Completed,NK-KODAMBAKKAM,131,667000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT SATHIYA GARDEN, KAMARAJAR 2nd STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8371,Roads,Completed,NK-KODAMBAKKAM,131,628000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT SATHIYA GARDEN, KAMARAJAR 3rd STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8372,Roads,Completed,NK-KODAMBAKKAM,131,250000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT SATHIYA GARDEN, KAMARAJAR 4th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8374,Roads,Completed,NK-KODAMBAKKAM,131,224000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT SATHIYA GARDEN, KAMARAJAR 5th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8376,Roads,Completed,NK-KODAMBAKKAM,131,1057000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT MODEL HOUSE, MAIN STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8377,Roads,Completed,NK-KODAMBAKKAM,131,355000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT MODEL HOUSE, 1st STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8378,Roads,Completed,NK-KODAMBAKKAM,131,289000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT MODEL HOUSE, 2nd STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8380,Roads,Completed,NK-KODAMBAKKAM,131,202000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT MODEL HOUSE, 2nd CROSS STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8381,Roads,Completed,NK-KODAMBAKKAM,131,250000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT MODEL HOUSE, 3rd STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8382,Roads,Completed,NK-KODAMBAKKAM,131,1290000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT II SECTOR, 8th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8385,Roads,Completed,NK-KODAMBAKKAM,131,1258000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT II SECTOR, 9th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8386,Roads,Completed,NK-KODAMBAKKAM,131,680000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT II SECTOR, 10th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8387,Roads,Completed,NK-KODAMBAKKAM,131,680000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT II SECTOR, 11th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8390,Roads,Completed,NK-KODAMBAKKAM,131,1560000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT II SECTOR, 12th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8391,Roads,Completed,NK-KODAMBAKKAM,131,1258000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT II SECTOR, 13th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/8392,Roads,Completed,NK-KODAMBAKKAM,131,1286000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT 6th SECTOR, 27th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8394,Roads,Completed,NK-KODAMBAKKAM,131,1180000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT 6th SECTOR, 28th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8401,Roads,Completed,NK-KODAMBAKKAM,131,606000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT 6th SECTOR, 29th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8404,Roads,Completed,NK-KODAMBAKKAM,131,1139000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT 6th SECTOR, 30th STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8405,Roads,Completed,NK-KODAMBAKKAM,131,2150000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT 6th SECTOR, 31st STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/8406,Roads,Completed,NK-KODAMBAKKAM,131,1057000,"RELAYING THE ROADS WITH BITUMINOUS CONCRETE ROAD AT 6th SECTOR, 32nd STREET IN DIVISION-131, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 BR/2014-15/17520,Roads,Completed,BR-Bus Route Roads,132,15816000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at KAMARAJAR SALAI (KK nagar) from the junction of PT Rajan salai to Ashok pillar road in ward 132 Zone-10.,Grants,10,2014-15,2016-17 NK/2014-15/12529,Roads,Completed,NK-KODAMBAKKAM,132,998000,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET IN VARIOUS STREET IN DN-132, U-31, Z-10 PART II",Own Sources,10,2014-15,2016-17 NK/2014-15/18771,Parks,Completed,NK-KODAMBAKKAM,132,784000,"ANNUAL MAINTENANCE OF PARK AT 14TH SECTOR (FOR 2 YEAR) IN DV 132,UNIT-31,ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/28482,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,990000,"IMPROVEMENTS TO STORM WATER DRAIN AT 86TH STREET(FROM 100' ROAD TO 18TH AVENUE SOUTH SIDE) IN DIVISION -132, UNIT-31, ZONE -10.",Own Sources,10,2014-15,2017-18 NK/2014-15/30758,Buildings,Completed,NK-KODAMBAKKAM,132,653000,"CONSTRUCTION OF COMPOSING YARD AND OTHER IMPROVEMENTS AT INDIRA COLONY PLAYGROUND AND WATER SUPPLY ARRANGEMENTS AT 12TH AVENUE PARK IN ASHOKNAGAR IN DN-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30895,Parks,Completed,NK-KODAMBAKKAM,132,990000,"PROVIDING WOODEN HANDRAILS AND GREENARY ARRANGEMENTS IN 1ST AVENUE PARK DIV-132,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30896,Parks,Completed,NK-KODAMBAKKAM,132,990000,"PROPOSED GREENARY ARRANGEMENTS AND PLAY APPARATUS IN 1ST AVENUE PARK DIV-132,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30905,Footpath,Completed,NK-KODAMBAKKAM,132,790000,"FORMING FOOTPATH AT 1ST AVENUE(WEST SIDE) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30910,Buildings,Completed,NK-KODAMBAKKAM,132,775000,"IMPROVEMENTS TO CLASSROOMS CPS AT KANNIYAPPA NAGAR SCHOOL IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30914,Roads,Completed,NK-KODAMBAKKAM,132,4258000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 9TH AVENUE,ASHOKNAGAR, IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30915,Roads,Completed,NK-KODAMBAKKAM,132,1855000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 35TH STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30916,Roads,Completed,NK-KODAMBAKKAM,132,1993000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 53RD STREET(PART),ASHOKNAGAR, IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30917,Roads,Completed,NK-KODAMBAKKAM,132,706000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 66TH STREET,ASHOKNAGAR, IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30918,Roads,Completed,NK-KODAMBAKKAM,132,1819000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 8TH STREET,ASHOKNAGAR, IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30919,Roads,Completed,NK-KODAMBAKKAM,132,606000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT MASTHAN ALI GARDEN, IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30920,Roads,Completed,NK-KODAMBAKKAM,132,1749000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 87TH STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30921,Roads,Completed,NK-KODAMBAKKAM,132,1154000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 88TH STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30922,Roads,Completed,NK-KODAMBAKKAM,132,1419000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 91ST STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30923,Roads,Completed,NK-KODAMBAKKAM,132,977000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 6TH STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30924,Roads,Completed,NK-KODAMBAKKAM,132,1104000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 11TH STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30925,Roads,Completed,NK-KODAMBAKKAM,132,1013000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 12TH STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30926,Roads,Completed,NK-KODAMBAKKAM,132,1367000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 13TH STREET, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30927,Roads,Completed,NK-KODAMBAKKAM,132,551000,"LAYING OF CEMENT CONCRETE ROAD USING RMC M30 GRADE AT 1ST & 3RD LANE, ASHOKNAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31069,Footpath,Completed,NK-KODAMBAKKAM,132,980000,"FORMING FOOTPATH AT 53RD STREET CHILDRENS PARK IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31070,Parks,Completed,NK-KODAMBAKKAM,132,995000,"IMPROVEMENTS AND SUPPLYING PLAY APPARATUS AT 53RD STREET CHILDRENS PARK IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31071,Buildings,Completed,NK-KODAMBAKKAM,132,975000,IMPROVEMENT WORK ON COMPOUND WALL ON 53RD CHILDREN PARK IN DIV 132 U 31 Z 10,Own Sources,10,2014-15,2016-17 NK/2014-15/31072,Buildings,Completed,NK-KODAMBAKKAM,132,991000,PROVIDING GRANITE ON COMPOUND WALL AT 53 RD STREET CHILDREN PARK IN DIV 132 U 31 Z 10,Own Sources,10,2014-15,2016-17 NK/2014-15/31091,Roads,Completed,NK-KODAMBAKKAM,132,999000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 79TH STREET(NORTH SIDE) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31092,Roads,Completed,NK-KODAMBAKKAM,132,950000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 80TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31093,Roads,Completed,NK-KODAMBAKKAM,132,999000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 79TH STREET(SOUTH SIDE) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31219,Roads,Completed,NK-KODAMBAKKAM,132,990000,"ATTENDING PATCH WORK BY MECHANICAL PAVER AT VARIOUS STREETS IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31220,Roads,Completed,NK-KODAMBAKKAM,132,985000,"ATTENDING PATCH WORK BY MECHANICAL PAVER AT VARIOUS STREETS IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31221,Roads,Completed,NK-KODAMBAKKAM,132,750000,"ATTENDING CONCRETE PATCH WORK AT VARIOUS PLACES IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31407,Roads,Completed,NK-KODAMBAKKAM,132,650000,"PROVIDING AND LAYING GSB AT 79TH STREET AND 80TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31562,Roads,Completed,NK-KODAMBAKKAM,132,920000,"ATTENDING BITUMEN PATCH WORK BY PAVER FINISHER AT 3RD AVENUE AND VARIOUS STREET IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31563,Roads,Completed,NK-KODAMBAKKAM,132,570000,"LAYING OF BT ROAD USING MECHANICAL PAVER AT MASTHAN ALI GARDEN (PART) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31616,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT S.V.LINGAM SALAI (REACH 1) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31617,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT S.V.LINGAM SALAI (REACH 2) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31618,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT S.V.LINGAM SALAI (REACH 3) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31622,Roads,Completed,NK-KODAMBAKKAM,132,985000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 65TH STREET IN DIV-132, U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31623,Roads,Completed,NK-KODAMBAKKAM,132,990000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 44TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31624,Roads,Completed,NK-KODAMBAKKAM,132,985000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 45TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31625,Roads,Completed,NK-KODAMBAKKAM,132,740000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 33RD STREET IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31626,Roads,Completed,NK-KODAMBAKKAM,132,990000,"ATTENDING BITUMEN PATCH WORK AT 16TH AVENUE AND VARIOUS STREETS IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31628,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 53RD STREET WEST SIDE (REACH 1) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31629,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 53RD STREET WEST SIDE (REACH 2) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31630,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 53RD STREET WEST SIDE (REACH 3) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31636,Roads,Completed,NK-KODAMBAKKAM,132,780000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT VAIGAI COLONY 1ST STREET IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31640,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 12TH AVENUE (REACH 1) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31646,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 12TH AVENUE (REACH 2) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31647,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 12TH AVENUE (REACH 3) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31648,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 12TH AVENUE (REACH 4) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31649,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 12TH AVENUE (REACH 5) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31650,Roads,Completed,NK-KODAMBAKKAM,132,980000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 12TH AVENUE (REACH 6) IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31704,Roads,Completed,NK-KODAMBAKKAM,132,980000,"PROVIDING SPEED BREAKERS AT 12TH AVENUE AND OTHER VARIOUS STREETS IN DIV-132, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/5513,Buildings,Completed,NK-KODAMBAKKAM,132,4280000,"PROPOSED ADDITIONAL CONSTRUCTION OF UPHC AT 35TH STREET ASHOK NAGAR BY MODIFIYING THE EXISTING HEALTHPOST IN DN-132,U-31,Z-10 .",Own Sources,10,2014-15,2016-17 NK/2014-15/6097,Parks,Completed,NK-KODAMBAKKAM,132,745000,"ANNUAL MAINTENANCE OF PARK AT 12TH AVENUE, ASHOK NAGAR IN DIVISION-132, UNIT-31, ZONE -10.. (Employed qualified Horticulturist for two years only)",Own Sources,10,2014-15,2018-19 NK/2014-15/7860,Buildings,Completed,B-Buildings,132,13930000,"CONSTRUCTION OF GASIFIER CREMATORIUM AT AVM BURIAL GROUND IN DN 132, UNIT 31, ZONE X.",Own Sources,10,2014-15,2018-19 NK/2014-15/8278,Roads,Completed,NK-KODAMBAKKAM,132,516000,"RELAYING THE ROAD WITH BC 40MM THICK BY MECHANICAL PAVER AT 43RD STREET, ASHOK NAGAR IN DIVISION-132, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/8280,Roads,Completed,NK-KODAMBAKKAM,132,571000,"RELAYING THE ROAD WITH BC 40MM THICK BY MECHANICAL PAVER AT 77TH STREET, ASHOK NAGAR IN DIVISION-132, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/9925,Electrical,Completed,NK-KODAMBAKKAM,132,92500,"Provision of Addl Electrification of Newly Proposed 15 Nos of 1 mt bracket with Fitting at 53rd street Park,Ashok Nagar in Division-132,Zone-X",Own Sources,10,2014-15,2017-18 S/2014-15/12537,Footpath,Completed,BR-Bus Route Roads,132,47200000,"Forming Footpath at P.T.Rajan Salai from the Junction of Inner Ring Road to Junction of Anna Main Road in Dn-132,Zone-10",Grants,10,2014-15,2017-18 BR/2014-15/17513,Roads,Completed,BR-Bus Route Roads,133,2410000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at ASHOK NAGAR 12 TH AVENUE from the junction of ashoknagar 11th main road to RR colony 1st street in ward 133 Zone- 10.,Grants,10,2014-15,2017-18 L/2014-15/27721,Electrical,Completed,L-Electrical,133,2422000,"Provision of 46 Nos of 6 mtr GI lamp post with LED Fitting on straight bracket at Ragavan Colony, Vengeeswaran Nagar, Muthuvel Street and Samburnam Aveue in Division-133, Zone-X.",Own Sources,10,2014-15,2017-18 NK/2014-15/20648,Footpath,Completed,NK-KODAMBAKKAM,133,850000,"IMPROVEMENTS TO THE EXISTING SWD AT VARIOUS STREET IN DN-133,U-31,U-31",Own Sources,10,2014-15,2016-17 NK/2014-15/24197,Roads,Completed,NK-KODAMBAKKAM,133,997000,ANNUAL MAINTENANCE OF ROADS WITH ATTENDING PATCH WORKS AT VARIOUS STREETS / ROADS IN DN 133 UNIT 31 ZONE 10,Own Sources,10,2014-15,2016-17 NK/2014-15/25796,Roads,Completed,NK-KODAMBAKKAM,133,855000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT VATHIYAR THOTTAM MAIN ROAD IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26622,Roads,Completed,NK-KODAMBAKKAM,133,555000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT VATHIYAR THOTTAM 1ST STREET IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26628,Roads,Completed,NK-KODAMBAKKAM,133,555000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT VATHIYAR THOTTAM 2ND STREET IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26630,Roads,Completed,NK-KODAMBAKKAM,133,295000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT UMAPATHY STREET EXTN., IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26632,Roads,Completed,NK-KODAMBAKKAM,133,480000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT NAKKEERAN STREET , IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26642,Roads,Completed,NK-KODAMBAKKAM,133,330000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT SWAMINATHAN STREET , IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26647,Roads,Completed,NK-KODAMBAKKAM,133,370000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT THULUKKANAM STREET , IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26652,Roads,Completed,NK-KODAMBAKKAM,133,445000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT VARADHAPPAN STREET , IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26715,Roads,Completed,NK-KODAMBAKKAM,133,1935000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT V TH AVENUE IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27343,Roads,Completed,NK-KODAMBAKKAM,133,2015000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 15TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27347,Roads,Completed,NK-KODAMBAKKAM,133,450000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 17TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27350,Roads,Completed,NK-KODAMBAKKAM,133,360000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 18TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27351,Roads,Completed,NK-KODAMBAKKAM,133,999000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 19TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27353,Roads,Completed,NK-KODAMBAKKAM,133,550000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 20TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27355,Roads,Completed,NK-KODAMBAKKAM,133,495000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 21TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27357,Roads,Completed,NK-KODAMBAKKAM,133,660000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 22TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27359,Roads,Completed,NK-KODAMBAKKAM,133,515000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 25TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27361,Roads,Completed,NK-KODAMBAKKAM,133,1135000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 58TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27362,Roads,Completed,NK-KODAMBAKKAM,133,770000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 59TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27366,Roads,Completed,NK-KODAMBAKKAM,133,550000,"LAYING THE ROAD WITH M30 GRADE CONCRETE AT 60TH STREET ASHOKNAGAR IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/5490,Buildings,Completed,NK-KODAMBAKKAM,133,447000,PROVIDING GUARDWALL WITH GRILL TO TRANSFORMERS AT VARIOUS STREETS IN DN 133 UNIT31 ZONE 10,Own Sources,10,2014-15,2016-17 NK/2014-15/6349,Buildings,Completed,NK-KODAMBAKKAM,133,554000,PROVIDING RAMP FOR N.N.M.P SHEDS AT VARIOUS STREETS IN DN 133 UNIT 31 ZONE 10,Own Sources,10,2014-15,2016-17 BR/2014-15/17508,Roads,Completed,BR-Bus Route Roads,134,7815000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement worS at RANGARAJAPURAM Main road (part from corporation colony road to rathanammal streeet ) in Ward 134 Zone-10.,Grants,10,2014-15,2017-18 NK/2014-15/17957,Parks,Completed,NK-KODAMBAKKAM,134,993000,"IMPROVEMENTS TO GYM BUILDING, POLICE GIRLS AND BOYS CLUB, KITCHEN ROOM,FOOT BALL STORE ROOM AND COMPOUND WALL AT CORPORATION COLONY MAIN ROAD IN DN-134, UNIT-31, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/18796,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,803000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN LINK AT CORPORATION COLONY ROAD JUNCTION OF CHAKRAPANI STREET IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/18807,Roads,Completed,NK-KODAMBAKKAM,134,878000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN LINK AT PARANGUSAPURAM JUNCTION OF AZIZ NAGAR MAIN ROAD AND VISWANATHAPURAM 2ND STREET JUNCTION OF VISWANATHAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/18879,Roads,Completed,NK-KODAMBAKKAM,134,999000,"ATTENDING PATCH WORK USING BC 40MM THICK BY PAVER FINISHER AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/19184,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,998000,"PROVIDING MISSING LINK FOR STORM WATER DRAIN AT VISWANATHAPURAM MAIN ROAD AND JUNCTION OF AZIZ NAGAR 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21068,Electrical,Completed,NK-KODAMBAKKAM,134,981000,"Supply, installation and commissioning of 2Nos of Panel Board arrangement and electrification in Zonal office 10 and EOC Vadapalani in Division 134 ,Zone-X",Own Sources,10,2014-15,2016-17 NK/2014-15/21591,Footpath,Completed,NK-KODAMBAKKAM,134,990000,"IMPROVEMENTS TO THE EXISTING DIVISION OFFICE AT CHAKRAPANI STREET EXTN., IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/21721,Roads,Completed,NK-KODAMBAKKAM,134,998000,"TREE PLANTATION ALONG WITH TREE GUARD AT VARIOUS LOCATIONS IN DN-134 &135, U-31, Z-10",Own Sources,10,2014-15,2019-20 NK/2014-15/22516,Roads,Completed,NK-KODAMBAKKAM,134,990000,"TREE PLANTATION ALONG WITH TREE GUARD AT VARIOUS LOCATIONS IN DN-136 &141, U-30, Z-10",Own Sources,10,2014-15,2019-20 NK/2014-15/27476,Roads,Completed,NK-KODAMBAKKAM,134,906000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KAMARAJAR COLONY 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/27477,Roads,Completed,NK-KODAMBAKKAM,134,1355000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/27478,Roads,Completed,NK-KODAMBAKKAM,134,1410000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT ASHOKA AVENUE IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/27479,Roads,Completed,NK-KODAMBAKKAM,134,2290000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT U.I.COLONY OUTER CIRCULAR ROAD IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/29640,Buildings,Completed,NK-KODAMBAKKAM,134,143000,"Providing Govt E Service Centre at inside of 134th Division Office complex at Chackrapani Sreet in Div-134, U-31 ,Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/29641,Buildings,Completed,NK-KODAMBAKKAM,134,999000,"WATERING AND MAINTENANCE OF TREE SAPLINGS AT VARIOUS STREETS IN DN-130,132,133,134,135,136 & 141 U-29,30 & 31, Z-10",Own Sources,10,2014-15,2019-20 NK/2014-15/30589,Buildings,Completed,NK-KODAMBAKKAM,134,980000,"Improvements to Kalaingar Park West Side and Center Arch Area in Division 134, Unit 31, Zone 10",Own Sources,10,2014-15,2016-17 NK/2014-15/30666,Parks,Completed,NK-KODAMBAKKAM,134,679000,"Plantation of Kalaignar Park in Div-134, Unit-31, Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30907,Parks,Completed,NK-KODAMBAKKAM,134,505000,"SUPPLYING AND FIXING OF R.O PLANT AND OTHER IMPROVEMENTS AT ANNA PARK IN DIV-134, U-31, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30960,Buildings,Completed,NK-KODAMBAKKAM,134,999000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT CORPORATION COLONY MAIN ROAD IN DN-134, UNIT-31, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/30962,Buildings,Completed,NK-KODAMBAKKAM,134,999000,"ADDITIONAL CONSTRUCTION OF DINING HALL AND STAFF TOILET IN CHENNAI MIDDLE SCHOOL AT CORPORATION COLONY MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/30963,Parks,Completed,NK-KODAMBAKKAM,134,999000,"DESILTING AND IMPROVEMENTS TO THE EXISTING SWD AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/30982,Parks,Completed,NK-KODAMBAKKAM,134,549000,"Improvements to Corporation Colony park in Division 134, Unit 31, zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30983,Parks,Completed,NK-KODAMBAKKAM,134,999000,"Improvements to Kalaingar Park in Division 134, Unit 31, Zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30987,Roads,Completed,NK-KODAMBAKKAM,134,756000,"Providing Water supply and electrical Arrangements to Corporation Colony Park in Division 134, Unit 31, Zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30989,Parks,Completed,NK-KODAMBAKKAM,134,955000,"Providing GYM Apparatus Arrangements to Corporation Colony in Division 134, Unit 31, Zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30992,Buildings,Completed,NK-KODAMBAKKAM,134,998000,"Improvements to Corporation Colony park South side in Division 134, Unit 31, zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/30993,Parks,Completed,NK-KODAMBAKKAM,134,977000,"Improvements to Corporation Colony Park West side in Division 134, Unit 31, zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31089,Parks,Completed,NK-KODAMBAKKAM,134,977000,"Providing Basement Arrangement Work to water Fountain at Kalaingnar Park in Dn 134, U 31,Zone 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/31564,Roads,Completed,NK-KODAMBAKKAM,134,996000,"Attending Patch Work by Using RMC 40Grade at Various Street in Dn - 134, Unit - 31, Zone -X.",Own Sources,10,2014-15,2016-17 NK/2014-15/31566,Roads,Completed,NK-KODAMBAKKAM,134,995000,"Attending Patch Work by Using RMC 40 Grade at Various Street in Dn - 134, Unit - 31, Zone - X.",Own Sources,10,2014-15,2017-18 NK/2014-15/31864,Buildings,Completed,NK-KODAMBAKKAM,134,984000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN LINK AT RANGARAJAPURAM MAIN ROAD AND JUNCTION OF AZIZ NAGAR MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/31872,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,991000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT BAJANAI KOIL STREET (FROM GUGAN STREET CH 100-200.00m) IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/31873,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,989000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT BAJANAI KOIL STREET (FROM GUGAN STREET CH 0-100.00m) IN DN-134,U-31,Z-10",Own Sources,10,2014-15,2017-18 NK/2014-15/4069,Parks,Completed,NK-KODAMBAKKAM,134,870000,"Annual Maintenance of Kalainger Park IN Dn.134,UNIT-31,Zone-10.(Employed qualified Horticulturist for two years only)",Own Sources,10,2014-15,2018-19 NK/2014-15/4071,Parks,Completed,NK-KODAMBAKKAM,134,949000,"Improvements and Maintenance of Anna Park in Dn.134,Unit-31,Zone-10.(Employed qualified Horticulturist for two years only)",Own Sources,10,2014-15,2019-20 NK/2014-15/5046,Buildings,Completed,NK-KODAMBAKKAM,134,2894000,"PROPOSED ADDITIONAL CONSTRUCTIONS AND ALTERATIONS FOR UPHC, KODAMBAKKAM IN DN-134, UNIT-31,ZONE-X",Own Sources,10,2014-15,2017-18 NK/2014-15/7208,Electrical,Completed,NK-KODAMBAKKAM,134,604500,"Provision of 34 Nos of 3 mt lamp post with Fitting and 3 Nos of 6 mt lamp post with Fitting at Anna Park in Division-134,Zone-X",Own Sources,10,2014-15,2017-18 NK/2014-15/9170,Footpath,Completed,NK-KODAMBAKKAM,134,948000,"PROVIDING MAN POWER FOR HOUSE KEEPING WORK AT CPS 15TH STREET ASHOK NAGAR (MULLAI NAGAR-133),CHSS N.S.K.SALAI(PULIYUR-133),CPS RANGARAJAPURAM MAIN ROAD(RANGARAJAPURAM-134),CHS RANGARAJAPURAM MAIN ROAD(RANGARAJAPURAM-134) IN DIV-133,134,U-31,Z-10",Own Sources,10,2014-15,2019-20 BR/2014-15/17516,Roads,Completed,BR-Bus Route Roads,135,6890000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at BRINDAVAN STREET from the junction of Duraisamy salai to Aryagowdaroad in ward 135 in Zone-10.,Grants,10,2014-15,2017-18 L/2014-15/27717,Electrical,Completed,L-Electrical,135,1014000,"Provision of 21 Nos of 6 mte GI lamp post with LED Fitting on straight bracket at Thiruvengadam St, Jaisankar St and Ramakrishnapuram 3rd Street in Division-135, Zone-X.",Own Sources,10,2014-15,2017-18 NK/2014-15/18655,Buildings,Completed,NK-KODAMBAKKAM,135,997000,"ATTENDING PATCH WORK USING BC 40MM BY PAVER FINISHER AND PROVIDING SPEED BREAKER AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/19931,Roads,Completed,NK-KODAMBAKKAM,135,1475000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KUPPIAH STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/19940,Roads,Completed,NK-KODAMBAKKAM,135,1170000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT SRINIVASA(I) STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20073,Roads,Completed,NK-KODAMBAKKAM,135,1675000,"RELAYING THE ROAD WITH BC40MM THICK BY PAVER FINISHER AT VEERASAMY STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20075,Roads,Completed,NK-KODAMBAKKAM,135,1570000,"RELAYING THE ROAD WITH BC40MM THICK BY PAVER FINISHER AT SUBBAH STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20076,Roads,Completed,NK-KODAMBAKKAM,135,1575000,"RELAYING THE ROAD WITH BC40MM THICK BY PAVER FINISHER AT ELLAI AMMAN KOIL STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26224,Roads,Completed,NK-KODAMBAKKAM,135,1710000,"RELAYING THE ROAD WITH BC 40 MM THICK BY PAVER FINISHER AT BABU RAJENDRAN PRASAD1ST STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26230,Roads,Completed,NK-KODAMBAKKAM,135,1310000,"RELAYING THE ROAD WITH BC 40 MM THICK BY PAVER FINISHER AT GANDHI STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26232,Roads,Completed,NK-KODAMBAKKAM,135,630000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER ATLAKSHMI STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26233,Roads,Completed,NK-KODAMBAKKAM,135,2085000,"RELAYING THE ROAD WITH BC 40 MM THICK BY PAVER FINISHER AT LAKE VIEW ROAD IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26235,Roads,Completed,NK-KODAMBAKKAM,135,1170000,"RELAYING THE ROAD WITH BC 40 MM THICK BY PAVER FINISHER AT THIRUVENGADAM STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26238,Roads,Completed,NK-KODAMBAKKAM,135,1020000,"RELAYING THE ROAD WITH BC 40 MM THICK BY PAVER FINISHER AT ADIKESAVAN STREET OR VIVEKANANDAPURAM 1ST STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26245,Roads,Completed,NK-KODAMBAKKAM,135,1060000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT POSTAL COLONY 1ST STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26248,Roads,Completed,NK-KODAMBAKKAM,135,1040000,"RELAYING THE ROAD WITH BC 40 MM THICK BY PAVER FINISHER AT POSTAL COLONY 2ND STREET IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/27087,Roads,Completed,NK-KODAMBAKKAM,135,1560000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT THAMBIAH ROAD(part-I) IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/27123,Roads,Completed,NK-KODAMBAKKAM,135,1560000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT THAMBIAH ROAD(part-II) IN DN-135,U-31,Z-10",Own Sources,10,2014-15,2016-17 BR/2014-15/17518,Roads,Completed,BR-Bus Route Roads,136,3498000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at DURAISAMY ROAD from the junction of Usman road to Brindavan road in ward 136 Zone-10.,Grants,10,2014-15,2016-17 BR/2014-15/17524,Roads,Completed,BR-Bus Route Roads,136,13354000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at USMAN ROAD from the junction of North Usman road to south Usman road in Ward 136 Zone-10.,Grants,10,2014-15,2016-17 BR/2014-15/18080,Roads,Completed,BR-Bus Route Roads,136,21650000,"Strengthening and Relaying the Bus Route Road with DBM and CBC after cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Gopathy Narayana (C) Road ( From the JN of Bashyam Road to the JN of Thirumalai (P) Road, Ward-136, Zone-10",Grants,10,2014-15,2016-17 L/2014-15/27720,Electrical,Completed,L-Electrical,136,3204000,"Provision of 61 Nos of 6 mt GI lamp post with LED Fitting on straight bracket at Srinivasa Rd, Rajamannar St, Kamalabai St, Jagathambal St, Muthu Krishan St, Gopala Krishnan St, Raja Bhadur St & Ramachandra Street in Division-136, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/27722,Electrical,Completed,L-Electrical,136,2822000,"Provision of 61 Nos of 6 mt GI lamp post with LED Fitting on straight bracket at Thanjaore Rd, Santhanam Salai, Vasan St, Jawaharlal Neru St, Cart Track Rd, Gandhi St, Ramachadra Rd, Anandan St, Krishasamy St, Krishan St and Govindu St in Division-136, Zone-X.",Own Sources,10,2014-15,2017-18 NK/2014-15/12018,Parks,Completed,NK-KODAMBAKKAM,136,930000,"ANNUAL MAINTENANCE TO NATESAN PARK AT VENKATNARAYANA ROAD IN DIV 136,U 30,Z 10(Employed qualified horticulturist only)",Own Sources,10,2014-15,2016-17 NK/2014-15/12025,Parks,Completed,NK-KODAMBAKKAM,136,700000,"ANNUAL MAINTENANCE TO JEEVA PARK AT G.N.CHEETY ROAD IN DIV 136, U 30, Z 10(Employed qualified horticulturist only)",Own Sources,10,2014-15,2017-18 NK/2014-15/12027,Parks,Completed,NK-KODAMBAKKAM,136,960000,"ANNUAL MAINTENANCE TO PANAGAL PARK AT BASHYAM ROAD IN DIV 136, U 30, Z 10(Employed qualified horticulturist only)",Own Sources,10,2014-15,2017-18 NK/2014-15/13035,Buildings,Completed,NK-KODAMBAKKAM,136,285000,"PROPOSED CONSTRUCTION OF LINK DRAIN ACROSS THE NORTH USMAN ROAD (CONNECTING RAJACHAR STREET) IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2014-15,2017-18 NK/2014-15/13305,Buildings,Completed,NK-KODAMBAKKAM,136,722000,"IMPROVEMENTS TO EXISTING FOOTPATH AT THIYAGARAYA ROAD ( SOUTH SIDE) IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2014-15,2016-17 NK/2014-15/13757,Parks,Completed,NK-KODAMBAKKAM,136,738000,"IMPROVEMENTS TO EXISTING FOOTPATH AT THIYAGARAYA ROAD ( NORTH SIDE) IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14416,Roads,Completed,NK-KODAMBAKKAM,136,2152000,"LAYING WITH CEMENT COCRETE AT KANNADASAN STREET ADJECENT TO NATESAN PARK ( EAST SIDE) IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/14417,Roads,Completed,NK-KODAMBAKKAM,136,2166000,"LAYING WITH CEMENT COCRETE AT KANNADASAN STREET ADJECENT TO NATESAN PARK ( WEST SIDE) IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/16731,Footpath,Completed,NK-KODAMBAKKAM,136,462000,"ATTENDING THE PATCH WORK USING M20 GRADE CONCRETE AT NORTH USMAN ROAD ( SERVICE ROAD ) AND VARIOUS STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2014-15,2019-20 NK/2014-15/18127,Roads,Completed,NK-KODAMBAKKAM,136,993000,"ATTENDING THE PATCH WORK AT KAMALABAI STREET AND VARIOUS STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2014-15,2018-19 NK/2014-15/24338,Footpath,Completed,NK-KODAMBAKKAM,136,998000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT THIYAGARAYA ROAD ( FROM PANAGAL PARK TO Dr.NAIR ROAD) IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26271,Roads,Completed,NK-KODAMBAKKAM,136,2859000,"RELAYING WITH CEMENT COCRETE AT GOVINDHU STREET IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/26278,Roads,Completed,NK-KODAMBAKKAM,136,1696000,"RELAYING WITH CEMENT COCRETE AT RAMESWARAM ROAD REACH 2 (RANGANATHAN STREET to CANARA BANK ATM ) IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/26281,Roads,Completed,NK-KODAMBAKKAM,136,2822000,"RELAYING WITH CEMENT COCRETE AT SAROJINI STREET IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/26285,Roads,Completed,NK-KODAMBAKKAM,136,2251000,"RELAYING WITH CEMENT COCRETE AT RAILWAY BORDER STREET IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/26288,Roads,Completed,NK-KODAMBAKKAM,136,2933000,"RELAYING WITH CEMENT COCRETE AT NATESAN STREET IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/26296,Roads,Completed,NK-KODAMBAKKAM,136,2709000,"RELAYING WITH CEMENT COCRETE AT RAMANATHAN STREET IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/26734,Roads,Completed,NK-KODAMBAKKAM,136,2455000,"RELAYING WITH CEMENT COCRETE AT RAMESWARAM ROAD REACH 1 (CANARA BANK ATM TO DURAISAMY ROAD) IN DIVISION - 136 , UNIT - 30 , ZONE - X",Own Sources,10,2014-15,2017-18 NK/2014-15/28474,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,660500,"MAINTENANCE OF STORM WATER DRAIN AT USMAN ROAD, RAGAVAIYAH ROAD AND VARIOUS STREET IN DIVISION - 136,UNIT - 30, ZONE - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/5688,Buildings,Completed,NK-KODAMBAKKAM,136,644000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT MAKALAKSHMI STREET IN DIV -136,UNIT -30,ZONE -10.(UNIT-2)",Own Sources,10,2014-15,2016-17 NK/2014-15/5844,Buildings,Completed,NK-KODAMBAKKAM,136,644000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT MAKALAKSHMI STREET IN DIV -136,UNIT -30,ZONE -10.(UNIT-1)",Own Sources,10,2014-15,2016-17 NK/2014-15/5847,Buildings,Completed,NK-KODAMBAKKAM,136,644000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT SRI THYAGARAYA ROAD IN DIV -136,UNIT -30,ZONE -10.(UNIT-2)",Own Sources,10,2014-15,2016-17 NK/2014-15/5849,Buildings,Completed,NK-KODAMBAKKAM,136,644000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT SRI THYAGARAYA ROAD IN DIV -136,UNIT -30,ZONE -10.(UNIT-1)",Own Sources,10,2014-15,2016-17 BR/2014-15/29796,Roads,Completed,BR-Bus Route Roads,137,46870000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by Paver finisher using Shredded Plastic waste along with Traffic Improvement Works at ANNA MAIN ROAD from the JN of Ashok Pillar Road to JN of Munusamy Salai in Ward 137,Zone-10.",Grants,10,2014-15,2016-17 BR/2014-15/30091,Roads,Completed,BR-Bus Route Roads,137,21132000,"Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at THIRUVALLUVAR 1ST STREET, PILLAIYAR KOIL STREET, ERIKARAI SALAI, RAMAPURAM MAIN ROAD. From the junction of MUNUSAMY SALAI to KAMARAJAR SALAI in ward 128,137 in Zone - 10.",Grants,10,2014-15,2016-17 L/2014-15/4157,Electrical,Completed,L-Electrical,137,2177900,"Provision of 58 Nos of 6 mt GI lamp post with LED Fitting at Errikarai salai,Khan Nagar Main Road in Division-137, Zone-X",Own Sources,10,2014-15,2016-17 L/2014-15/4168,Electrical,Completed,L-Electrical,137,1255400,"Provision of 40 Nos of 6 mt GI lamp post with LED Fitting at Krishnan St, Rajivgandhi St , Annai Indira St,Kamaraj St in Division-137,Zone-X",Own Sources,10,2014-15,2016-17 NK/2014-15/12019,Parks,Completed,NK-KODAMBAKKAM,137,780000,"MAINTENANCE OF PARK AT 11TH SECTOR, K.K.NAGAR IN DIV 137,UNIT 28,ZONE 10",Own Sources,10,2014-15,2018-19 NK/2014-15/12020,Parks,Completed,NK-KODAMBAKKAM,137,790000,"MAINTENANCE OF PARK AT 4TH SECTOR, K.K.NAGAR IN DIV 137,UNIT 28,ZONE 10",Own Sources,10,2014-15,2018-19 NK/2014-15/12956,Parks,Completed,NK-KODAMBAKKAM,137,970000,"ANNUAL MAINTENANCE OF PARK AT ERIKARAI STREET,NESAPAKKAM IN DIVISION 137,UNIT-28,ZONE-X.( By qualified horticulturist only)",Own Sources,10,2014-15,2017-18 NK/2014-15/12958,Parks,Completed,NK-KODAMBAKKAM,137,940000,"Improvements and Greenery arrangements to 4th Sector Park and 11th Sector Park, K.K.Nagar in Dn.137,Unit-28,Zone-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/13045,Parks,Completed,NK-KODAMBAKKAM,137,715000,"ANNUAL MAINTENANCE OF PARK AT 12TH SECTOR TWO YEARS, K.K.NAGAR IN DN 137,UNIT-28,ZONE-10.(By Empolyed qualified horticulturist for two years only)",Own Sources,10,2014-15,2016-17 NK/2014-15/15151,Roads,Completed,NK-KODAMBAKKAM,137,1104000,LAYING CEMENT CONCRETE ROAD AT KABILAR STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/19535,Roads,Completed,NK-KODAMBAKKAM,137,739000,RELAYING OF ROAD WITH BCCMP FAVER FINISHER AT 10TH SECTOR 54TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20103,Roads,Completed,NK-KODAMBAKKAM,137,504000,LAYING CEMENT CONCRETE ROAD AT THAMARAI VINAYAGAR KOIL STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20176,Roads,Completed,NK-KODAMBAKKAM,137,1035000,RELAYING OF ROAD WITH FAVER FINISHER BCCMP AT 8TH SECTOR 42ND STREET IN DN.137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20177,Roads,Completed,NK-KODAMBAKKAM,137,739000,RELAYING OF ROAD WITH FAVER FINISHER BCCMP 40MM TK. AT 9TH SECTOR 49TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20179,Roads,Completed,NK-KODAMBAKKAM,137,1725000,RELAYING OF ROAD WITH FAVER FINISHER BCCMP AT 10TH SECTOR 59TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20180,Roads,Completed,NK-KODAMBAKKAM,137,1010000,RELAYING THE ROAD WITH FAVER FINISHER BCCMP AT 10TH SECTOR 64 TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20181,Roads,Completed,NK-KODAMBAKKAM,137,1010000,RELAYING THE ROAD WITH FAVER FINISHER BCCMP AT 10TH SECTOR 65TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20182,Roads,Completed,NK-KODAMBAKKAM,137,591000,RELAYING THE ROAD WITH FAVER FINISHER BCCMP AT 11TH SECTOR 67TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20283,Buildings,Completed,NK-KODAMBAKKAM,137,513000,RELAYING THE ROAD WITH FAVER FINISHER WITH BCCMP1 AT T.K.BHANI 1ST STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/20770,Roads,Completed,NK-KODAMBAKKAM,137,373000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT THAMARAI KOIL STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20771,Roads,Completed,NK-KODAMBAKKAM,137,316000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT ANNA STREET (SOOLAI PALLAM) IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20772,Roads,Completed,NK-KODAMBAKKAM,137,345000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT MISHA ABRAHAM STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20774,Roads,Completed,NK-KODAMBAKKAM,137,131000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT SARASWATHY STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20775,Roads,Completed,NK-KODAMBAKKAM,137,499000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KENNADY STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20776,Roads,Completed,NK-KODAMBAKKAM,137,137000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT STALIN STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/20778,Roads,Completed,NK-KODAMBAKKAM,137,903000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT ANJUGAM STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21499,Roads,Completed,NK-KODAMBAKKAM,137,326000,"RELAYING THE ROAD WITH BC40MM THICK BY PAVER FINISHER AT RAGHUL GANDHI STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21500,Roads,Completed,NK-KODAMBAKKAM,137,336000,"RELAYING THE ROAD WITH BC40MM THICK BY PAVER FINISHER AT SONIA GANDHI STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21571,Roads,Completed,NK-KODAMBAKKAM,137,380000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT BHARATHIYAR 1ST STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21572,Roads,Completed,NK-KODAMBAKKAM,137,860000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT NEHRU STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21573,Roads,Completed,NK-KODAMBAKKAM,137,184000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT PERIYAR STREET IN DN-137,U-28,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21836,Roads,Completed,NK-KODAMBAKKAM,137,924000,RELAYING THE ROAD WITH BCCMP 40MM TK BY MECHANICAL PAVER FINISH AT 4TH SECTOR 14TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/21846,Roads,Completed,NK-KODAMBAKKAM,137,714000,RELAYING THE ROAD WITHBCCMP 40MM TK BY MECHANICAL PAVER FINISHER AT 4TH SECTOR 19TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/21848,Roads,Completed,NK-KODAMBAKKAM,137,985000,RELAYING THE ROAD WITH PAVER FINISH BCCMP AT 4TH SECTOR 20TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/22357,Roads,Completed,NK-KODAMBAKKAM,137,624000,RELAYING OF ROAD BCCMP WITH FAVER FINISHER AT 11TH SECTOR 68TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/26216,Roads,Completed,NK-KODAMBAKKAM,137,1207000,LAYING CEMENT CONCRETE ROAD AT SANKARALINGANOR STREETIN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/26218,Roads,Completed,NK-KODAMBAKKAM,137,813000,LAYING CEMENT CONCRETE ROAD AT ANNAVEETHI 2ND STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/26219,Roads,Completed,NK-KODAMBAKKAM,137,425000,LAYING CEMENT CONCRETE ROAD AT ANNA VEETHI 4TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/26221,Roads,Completed,NK-KODAMBAKKAM,137,1104000,LAYING CEMENT CONCRETE ROAD AT ANNAVEETHI 5TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/26295,Roads,Completed,NK-KODAMBAKKAM,137,1026000,RELAYING THE ROAD WITH BCCMP WITH FAVER FINISHER AT 7TH SECTOR 33RD STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/26723,Roads,Completed,NK-KODAMBAKKAM,137,554000,RELAYING THE ROAD WITH FAVER FINISHER AT ANNAI SATHIYA NAGAR 11TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/28161,Footpath,Completed,NK-KODAMBAKKAM,137,500000,"IMPROVEMENTS TO ROAD SIDE BERMS AT RAJIV GANDHI NAGAR ARUNACHALAM STREET, ARJUNAN STREET, ARJUNAN CROSS STREET, NAGAPPAN STREET ,MAHENDRAVARMAR STREET AND KAMARAJAR SALAI IN DN 137 UNIT 28 ZONE 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/29623,Buildings,Completed,NK-KODAMBAKKAM,137,4738000,DESIGN MANUFACTURE SUPPLY BURIAL GROUND OF FIXING ERECTION GASIFIER AND ALTERNATIVE FUEL LPG FIRED FURNAC AT ERRIKARAI STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2014-15,2016-17 NK/2014-15/31599,Buildings,Completed,NK-KODAMBAKKAM,137,838000,"Providing additional Toilet block with all arrangements Compound wall and Auditorium painting of C.H.S. School of Main and Annexure buildings at Erikarai Street and C.M.S. at Kamarajar Street in Dn137,Unit-28,Zone-10",Own Sources,10,2014-15,2016-17 NK/2014-15/5367,Electrical,Completed,NK-KODAMBAKKAM,137,999800,"Provision of 20 Nos of 6 mt lamp post and 32 Nos of 3 mt lamp post with Fitting at Errikarai salai,Nesapakkam BG, park &Play Ground and 4th sector,8th sector and 12th sector in Division-137,Zone-X",Own Sources,10,2014-15,2016-17 S/2014-15/12396,Footpath,Completed,BR-Bus Route Roads,137,46200000,Forming footpath at Lakshmana Samy Salai from junction Munusamy Salai to junction P T Rajan Salai in Dn 137 at Zone 10.,Grants,10,2014-15,2017-18 S/2014-15/12539,Footpath,Completed,BR-Bus Route Roads,137,35600000,"FORMING FOOTPATH AT RAMASAMY SALAI FROM THE JUNCTION OF MUNUSAMY SALAI TO JUNCTION OF P.T.RAJAN SALAI IN DIVISION137, ZONE -X.",Grants,10,2014-15,2017-18 L/2014-15/22552,Electrical,Completed,L-Electrical,138,1123500,"Provision of 21 Nos 8 Mtr GI Lamp Post Single Straight bracket with 90W - 120 W LED Fitting at kk main Road in Division-138, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/22553,Electrical,Completed,L-Electrical,138,756900,"Provision of 14 Nos 8 mtr Mtr GI Lamp Post Single straight bracket with 90W - 120 W LED Fitting at 60 ft Road in Division-138, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/22556,Electrical,Completed,L-Electrical,138,1796700,"Provision of 44 Nos 6 MTR LONG G.I OCTAGONAL STREET LAMP POST WITH 1MTR SINGLE BRACKET with 40W - 50 W LED Fitting at Pachaiyapan 1, 2nd Street & Thangavelu 1, 2nd street and Jambulingam Street in Division-138, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/22558,Electrical,Completed,L-Electrical,138,1529000,"Provision of 29 Nos 8 MTR LONG G.I OCTAGONAL STREET LAMP POLE G,I SINGLE BRACKET with 90W - 120 W LED Fitting at Pillayar Koil street in Division-138, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/27157,Electrical,Completed,L-Electrical,138,2491200,"Provision of 64 Nos 6 MTR LONG G.I OCTAGONAL STREET LAMP POST 1 MTR SINGLE BRACKET with 40W - 50 W LED Fitting at Bharathidasan colony , Nethaji nagar and Nehru avenue in Division-138, ZoneX.",Own Sources,10,2014-15,2017-18 NK/2014-15/16858,Roads,Completed,NK-KODAMBAKKAM,138,621000,"PROPOSED CONSTRUCTION OF MANHOLE DOORS RAISING WORK AT GOVINDASAMY STREET AND VARIOUS STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/21101,Buildings,Completed,NK-KODAMBAKKAM,138,415000,"IMPROVEMENT OF PLAY GROUND AT THIRU NAGAR V.O.C STREET IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21103,Buildings,Completed,NK-KODAMBAKKAM,138,340000,"IMPROVEMENT OF PLAY GROUND AT THIRU NAGAR AVVAI STREET IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/21639,Buildings,Completed,NK-KODAMBAKKAM,138,900000,"ATTENDING PTCH WORK USING PAVER FINISHER AT THIRU NAGAR,VASUDEVAN NAGAR AND VARIOUS STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2014-15,2019-20 NK/2014-15/22551,Buildings,Completed,NK-KODAMBAKKAM,138,460000,"HIRING CHARGES FOR SUPPLYING ,FIXING AND MAINTAING OF PORTABLE TOILET AT AMBEDKAR COLONY, JAWAHARLAL NEHRU SALAI(100' FEET ROAD) IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/23187,Roads,Completed,NK-KODAMBAKKAM,138,980000,"ATTENDING PATCH WORK AT THIRU NAGAR AND VARIOUS STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/25691,Roads,Completed,NK-KODAMBAKKAM,138,3700000,"LAYING OF CEMENT CONCRETE ROAD M40 GRADE AT THANGAVEL NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2014-15,2016-17 BR/2014-15/17511,Roads,Completed,BR-Bus Route Roads,139,4108000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at RR COLONY WEST STREET from the junction of RR colony 1st street to jafferkhanpet main road in ward 139 Zone -10.,Grants,10,2014-15,2017-18 BR/2014-15/17512,Roads,Completed,BR-Bus Route Roads,139,5529000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at RR COLONY 1 ST STREET from the junction of ashok nagar 12th main road to RR colony west street in ward 139 Zone - 10.,Grants,10,2014-15,2017-18 BR/2014-15/17514,Roads,Completed,BR-Bus Route Roads,139,11066000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at JAFFERKHAN PET MAIN ROAD from the junction of 100 feet road to RR colony west side in ward 139 in Zone -10.,Grants,10,2014-15,2017-18 NK/2014-15/0094,Buildings,Completed,NK-KODAMBAKKAM,139,900000,"DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN AT KRISHNAN STREET, MAHADEVAN STREET,ARUMUGAM STREET AND RAJA BADAR STREET IN DN-139, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/14592,Buildings,Completed,NK-KODAMBAKKAM,139,986000,"CONSTRUCTION OF TRANSPORT OFFICER ROOM AND E TOILET IMPROVEMENT WORK IN NEAR SAIDAPET BUS STAND AT WEST JONES ROAD DIV 139 U 28 Z 10",Own Sources,10,2014-15,2016-17 NK/2014-15/14636,Roads,Completed,NK-KODAMBAKKAM,139,1283000,"PROPOSED LAYING OF ROAD USING CEMENT CONCRETE AT ARUMUGAM STREET IN DIV -139, U-28, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/14646,Roads,Completed,NK-KODAMBAKKAM,139,1664000,"PROPOSED LAYING OF ROAD USING CEMENT CONCRETE AT LAKSHMI STREET IN DIV -139, U-28, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/19747,Buildings,Completed,NK-KODAMBAKKAM,139,1005000,CONSTRUCTION OF MULTI PURPOSE HALL AT MUTHURANGAN BLOCK IN DIVISION-139 UNIT-28 ZONE-10 (UNDER MLA FUND),MLACDS,10,2014-15,2016-17 NK/2014-15/22064,Roads,Completed,NK-KODAMBAKKAM,139,222000,"PROPOSED RELAYING OF ROAD WORK USING BITUMINOUS CONCRETE AT NEW COLONY 4TH STREET IN DIV 139,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/22073,Roads,Completed,NK-KODAMBAKKAM,139,490000,"PROPOSED RELAYING OF ROAD WORK USING BITUMINOUS CONCRETE AT SIVANANDAN STREET IN DIV 139,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/22586,Roads,Completed,NK-KODAMBAKKAM,139,983000,"ENGAGING PRIVATE AUTO VEHICLE WITH 6 PRIVATE LABOURS FOR 10 MONTHS TO DN-139, UNIT-28,ZONE-X.",Own Sources,10,2014-15,2016-17 NK/2014-15/26289,Roads,Completed,NK-KODAMBAKKAM,139,820000,"PROPOSED RELAYING OF ROAD USING BITUMINOUS CONCRETE AT ANNAMALAI NAGAR 1ST STREET DIV-139,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26291,Roads,Completed,NK-KODAMBAKKAM,139,627000,"PROPOSED RELAYING OF ROAD USING BITUMINOUS CONCRETE AT ANNAMALAI NAGAR 2ND STREET DIV-139,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26293,Roads,Completed,NK-KODAMBAKKAM,139,796000,"PROPOSED RELAYING OF ROAD USING BITUMINOUS CONCRETE AT ANNAMALAI NAGAR 3RD STREET DIV-139,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/26298,Roads,Completed,NK-KODAMBAKKAM,139,262000,"PROPOSED RELAYING OF ROAD USING BITUMINOUS CONCRETE AT PILLAYAR KOIL STREET DIV-139,UNIT-28,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/2797,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,900000,"IMPROVEMENTS TO STORM WATER DRAIN AT DEVARAJAN STREET AND SUPPLYING AND FIXING FRC DOORS AT PERUMAL KOIL MADA STREET , SUBRAMANIAN STREET AND DEVA NAIDU STREET IN DN-139, UNIT-28, ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/4272,Buildings,Completed,NK-KODAMBAKKAM,139,900000,"IMPROVEMENTS TO NNMP SHED NO: 10036,10037 AND 10038 AT RAGHAVA COLONY 3RD CROSS STREET IN DIV -139 , UNIT - 28 , ZONE - 10.",Own Sources,10,2014-15,2017-18 L/2014-15/28423,Electrical,Completed,L-Electrical,140,858800,"Provision of 26 nos of 6 Mtr GI Lamp Post Straight bracket with 40w-50w LED Fitting at K.R Koil Street in Division-140, Zone-X.",Own Sources,10,2014-15,2017-18 NK/2014-15/14090,Roads,Completed,NK-KODAMBAKKAM,140,1031000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT SADAYAPPA (M) STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14092,Roads,Completed,NK-KODAMBAKKAM,140,1518000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT REDDY KUPPAM SALAI (FROM ARANGANATHAN SUB-WAY TO SERVICE ROAD IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14094,Roads,Completed,NK-KODAMBAKKAM,140,2394000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT OLD MAMBALAM ROAD IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14095,Roads,Completed,NK-KODAMBAKKAM,140,1604000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT K.R.KOIL STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14128,Roads,Completed,NK-KODAMBAKKAM,140,137000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT KALAIGNAR KARUNANIDHI CROSS STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14130,Roads,Completed,NK-KODAMBAKKAM,140,376000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT PERUMAL KOIL STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14131,Roads,Completed,NK-KODAMBAKKAM,140,647000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT KALIGNAR KARUNANIDHI 1ST STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14132,Roads,Completed,NK-KODAMBAKKAM,140,316000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT KALIGNAR KARUNANIDHI 2ND STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14134,Roads,Completed,NK-KODAMBAKKAM,140,543000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT DHANABAL STREET IN DIV-140, U-30, Z-10.)",Own Sources,10,2014-15,2016-17 NK/2014-15/14135,Roads,Completed,NK-KODAMBAKKAM,140,98000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT ANGALAMMAN KOIL STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14137,Roads,Completed,NK-KODAMBAKKAM,140,135000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT JOTHI RAMALINGAM 2ND STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14140,Roads,Completed,NK-KODAMBAKKAM,140,310000,"RELAYING OF CEMENT CONCRETE ROAD (M30) GRADE AT JOTHI RAMALINGAM 1ST STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14141,Roads,Completed,NK-KODAMBAKKAM,140,793000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT ADHIKESAVA PERUMAL KOIL STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14144,Roads,Completed,NK-KODAMBAKKAM,140,655000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT SAMBANGI STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/14145,Roads,Completed,NK-KODAMBAKKAM,140,655000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT KANNIAMMAN KOIL STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/16222,Parks,Completed,NK-KODAMBAKKAM,140,502000,"ANNUAL MAINTENANCE OF ROAD SIDE PARK AT ELLAIAMMAN KOIL STREET (KITTU PARK) (1 YEAR) IN DIV-140, U-30, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/17336,Buildings,Completed,NK-KODAMBAKKAM,140,999000,"ADDITIONAL IMPROVEMENTS WORK OF CHANGING ROOF STRUCTURE TO ANGANWADI (10010) AT NEW STREET IN DIV-140, U-30, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/17337,Buildings,Completed,NK-KODAMBAKKAM,140,998000,"ADDITIONAL IMPROVEMENTS WORK OF CHANGING ROOF STRUCTURE TO ANGANWADI (10012) AT NEW STREET IN DIV-140, U-30, Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/17865,Roads,Completed,NK-KODAMBAKKAM,140,1315000,"RELAYING OF CEMENT CONCRETE ROAD (M40) GRADE AT BURMA KANAGAMBAL STREET IN DIV-140, U-30, Z-10. (UNDER SAIDAPET M.L.A FUND)",MLACDS,10,2014-15,2016-17 NK/2014-15/18665,Roads,Completed,NK-KODAMBAKKAM,140,385000,"RELAYING OF CEMENT CONCRETE ROAD (M30) GRADE AT RAMAIAH STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/18738,Parks,Completed,NK-KODAMBAKKAM,140,995000,"PROVIDING THE PLANTS WORK AT PARK IN KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/23254,Buildings,Completed,NK-KODAMBAKKAM,140,828310,"PROPOSED CEMENT CONCRETE FLOORING IN DIVISION OFFICE AND CONSTRUCTION OF COMPOSITE YARD AT REDDY KUPPAM STREET IN DIV -140, U- 30 ,Z -10.",Own Sources,10,2014-15,2016-17 NK/2014-15/24512,Footpath,Completed,NK-KODAMBAKKAM,140,616000,"REPAIRS AND IMPROVEMENTS WORK FOR VARIOUS SCHOOLS AND ATTENDING PATCH WORK FOR CEMENT CONCRETE (M20 GRADE) AT KODAMBAKKAM ROAD AND VARIOUS STREETS IN DIVISION - 140, UNIT - 30, ZONE - 10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26240,Roads,Completed,NK-KODAMBAKKAM,140,465000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT SRINIVASA IYENGAR MAIN STREET IN DIV-140,U-30,Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26253,Roads,Completed,NK-KODAMBAKKAM,140,131000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT SRINIVASA IYENGAR 2ND STREET IN DIV-140,U-30,Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/27746,Buildings,Completed,NK-KODAMBAKKAM,140,990000,"PROVIDING ADDITIONAL ROOM AND IMPROVEMENTS TO THE DIVISION OFFICE AT KODAMBAKKAM SALAI IN DN-140,UT-30,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/6244,Roads,Completed,NK-KODAMBAKKAM,140,954000,"RELAYING THE ROAD WITH CAMBER CORRECTION AND BITUMINOUS CONCRETE 40MM THICK AT RAJAJI STREET IN DN.140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/6245,Roads,Completed,NK-KODAMBAKKAM,140,891000,"RELAYING THE ROAD WITH CAMBER CORRECTION AND BITUMINOUS CONCRETE 40MM THICK AT NETHAJI STREET IN DN.140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/6246,Roads,Completed,NK-KODAMBAKKAM,140,716000,"RELAYING THE ROAD WITH CAMBER CORRECTION AND BITUMINOUS CONCRETE 40MM THICK AT SARADHAMBAL STREET IN DN.140, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/9872,Parks,Completed,NK-KODAMBAKKAM,140,2323000,"PROVIDING SHED ROOF COVER,YOGA STAGE,CURVED GRANITE PLANTER BOX,LADIES ZONE,PAVER BLOCK LAYING WITH CURB WALL,PATHWAY DETAIL WITH CURB WALL IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIV-140,U-30,Z-10",Own Sources,10,2014-15,2016-17 NK/2014-15/9874,Parks,Completed,NK-KODAMBAKKAM,140,2181000,"PROVIDING CHILDREN TREE HOUSE-1,2,&3,WATER SUPPLY ARRANGEMENT ,DRAINAGE ARRANGEMENT,LANDSCAPING WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIV-140,U-30,Z-10",Own Sources,10,2014-15,2016-17 BR/2014-15/17506,Roads,Completed,BR-Bus Route Roads,141,2253000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement works at C I T NAGAR 4 th main road from the junction of CIT nagar 3rd main road to CIT nagar 1st main road ward 141 Zone -10.,Grants,10,2014-15,2016-17 BR/2014-15/17507,Roads,Completed,BR-Bus Route Roads,141,2160000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement workS at C I T NAGAR 3 RD MAIN ROAD from the junction of annasalai to C I T nagar 4th main road ward 141 Zone-10.,Grants,10,2014-15,2016-17 BR/2014-15/17521,Roads,Completed,BR-Bus Route Roads,141,10806000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at CIT NAGAR 1ST MAIN ROAD from the junction of Annasalai to South usman road in ward 141 Zone -10.,Grants,10,2014-15,2016-17 BR/2014-15/17522,Roads,Completed,BR-Bus Route Roads,141,13021000,Strengthening and relaying the road with DBM and CBC after cold milling by Paver finish using Plastic waste along with traffic improvement work at SOUTH USMAN ROAD from the junction of C I T Nagar 1st main road to usman road in ward 141 Zone-10.,Grants,10,2014-15,2016-17 L/2014-15/27723,Electrical,Completed,L-Electrical,141,1909000,"Provision of 25 Nos of 8 mt Octagonal Lamp Post with LED Fitting on straight bracket at Burkit Road From V.N Road To Usman Road in Division-141, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/27724,Electrical,Completed,L-Electrical,141,4957000,"Provision of 72nos 8mtr Octagonal Lamp Post Single bracket with LED Fitting at CIT Nagar 1st Main Road and South Usman Road from Anna salai to Burkit Road in Division-141, Zone-X.",Own Sources,10,2014-15,2017-18 NK/2014-15/11137,Roads,Completed,NK-KODAMBAKKAM,141,4850000,"RELAYING THE ROAD WITH CEMENT CONCRETE AT CANAL BANK ROAD FROM CANAL CROSS STREET(DOOR NO-40/94)TO CIT NAGAR 3RD MAIN ROAD(DOOR NO-74/86) IN DN-141, UNIT-30 ,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/11200,Roads,Completed,NK-KODAMBAKKAM,141,4130000,": RELAYING THE ROAD WITH CEMENT CONCRETE AT CIT NAGAR 5TH MAIN ROAD FROM CIT NAGAR 3RD MAIN ROAD TO CIT NAGAR 4TH MAIN ROAD (AT DOOR NO- 38/45) IN DN-141, UNIT-30 , ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/11226,Roads,Completed,NK-KODAMBAKKAM,141,4850000,"RELAYING THE ROAD WITH CEMENT CONCRETE AT CANAL BANK ROAD FROM MOOPARAPPAN STREET TO CANAL CROSS STREET(DOOR NO-40/94) IN DN-141, UNIT-30 ,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/11228,Roads,Completed,NK-KODAMBAKKAM,141,4850000,"RELAYING THE ROAD WITH CEMENT CONCRETE AT CANAL BANK ROAD FROM CIT NAGAR 3RD MAIN ROAD(DOOR NO-74/86) TO SOUTH USMAN ROAD IN DN-141, UNIT-30 ,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/11229,Roads,Completed,NK-KODAMBAKKAM,141,3190000,"RELAYING THE ROAD WITH CEMENT CONCRETE AT MOOPPARAPPAN STREET FROM BURKIT ROAD TO DOOR N0-32 IN DN-141, UNIT-30 AND ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/20553,Buildings,Completed,NK-KODAMBAKKAM,141,873000,IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT SOUTH WEST BOAG ROAD AND VARIOUS STREET IN DIVISION 141 U 30 Z 10,Own Sources,10,2014-15,2016-17 NK/2014-15/20558,Roads,Completed,NK-KODAMBAKKAM,141,3525000,"RELAYING THE ROAD WITH CEMENT CONCRETE AT SIDDI VINAYAKAR KOIL STREET IN DIV-141, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/20560,Roads,Completed,NK-KODAMBAKKAM,141,3306000,"RELAYING THE ROAD WITH CEMENT CONCRETE [M20 GRADE] AT BAJANAIKOIL STREET IN DIV-141, U-30, Z-10.",Own Sources,10,2014-15,2017-18 NK/2014-15/20561,Roads,Completed,NK-KODAMBAKKAM,141,1637000,"RELAYING THE ROAD WITH CEMENT CONCRETE [M30 GRADE] AT MADLEY 1st STREET IN DIV-141, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/21398,Buildings,Completed,NK-KODAMBAKKAM,141,702000,"IMPROVEMENT AND ADDITIONAL WORK FOR E TOILET AND URINALS AT BURKIT ROAD AND VARIOUS STREET IN DIV 141,UNIT-30, ZONE-10",Own Sources,10,2014-15,2017-18 NK/2014-15/26319,Roads,Completed,NK-KODAMBAKKAM,141,1145000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE 40MM THICK AT SIVAJI STREET IN DIV-141, U-30, Z-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/3063,Roads,Completed,NK-KODAMBAKKAM,141,4130000,"RELAYING THE ROAD WITH CEMENT CONCRETE AT CIT NAGAR 5TH MAIN ROAD FROM CIT NAGAR 5TH MAIN ROAD CROSS STREET AT DOOR NO-57/90 TO CIT NAGAR 4TH MAIN ROAD AT DOOR NO- 2/45 IN DN-141, UNIT-30 , ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/3768,Roads,Completed,NK-KODAMBAKKAM,141,4130000,"RELAYING THE ROAD WITH CEMENT CONCRETE AT CIT NAGAR 5TH MAIN ROAD FROM ROUNDANA TO CIT NAGAR 5TH MAIN ROAD CROSS STREET AT DOOR NO-57/90, IN DN-141, UNIT-30 AND ZONE-10",Own Sources,10,2014-15,2016-17 L/2014-15/22545,Electrical,Completed,L-Electrical,142,2153600,"Provision of 63 nos 6 mtr GI Lamp Post Straight bracket with LED Fitting at Samiyar Thottam and Poilce Lane in Division-142, Zone-X",Own Sources,10,2014-15,2017-18 L/2014-15/28444,Electrical,Completed,L-Electrical,142,400000,"WORK: Provision of 12 nos of 6 mtr GI Lamp Post Straight bracket with 40w-50w LED Fitting at Kavari Lane, Anjaneryar Koil Street in Division-142, Zone-X.",Own Sources,10,2014-15,2017-18 L/2014-15/30135,Electrical,Completed,L-Electrical,142,517000,"Supply,erection and commissioning of 1 no. of 16 mt. High mast lighting with 8 no. of 2 X 400 watt Metal halide fitting in Bazzar Road (JUN) Anna salai , Division 142, Zone X",MPLADS,10,2014-15,2017-18 NK/2014-15/19989,Buildings,Completed,NK-KODAMBAKKAM,142,938000,"PROVIDING FENCING FOR THE OPEN AREA INFRONT OF CPS SCHOOL AT BAZAAR ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/21661,Roads,Completed,NK-KODAMBAKKAM,142,584000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NOS. FOR DIVISION WORK IN DIVISION-142, UNIT-30 AND ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/21770,Buildings,Completed,NK-KODAMBAKKAM,142,980000,"IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT THIDEER NAGAR IN DIVISION-142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/22718,Buildings,Completed,NK-KODAMBAKKAM,142,986000,"IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT JEENIS ROAD IN DIV-142,UNIT-30,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/25753,Buildings,Completed,NK-KODAMBAKKAM,142,980000,"IMPROVEMENTS TO THE WASHING AREA AT DHOBIKANA,,SAIDAPET AND VARIOUS WORKS IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2014-15,2016-17 NK/2014-15/26287,Roads,Completed,NK-KODAMBAKKAM,142,466000,"LAYING OF CEMENT CONCRETE ROAD AT TANK SQUARE EAST STREET IN DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26292,Roads,Completed,NK-KODAMBAKKAM,142,383000,"LAYING OF CEMENT CONCRETE ROAD AT TANK SQUARE WEST STREET IN DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26312,Roads,Completed,NK-KODAMBAKKAM,142,1900000,"LAYING CEMENT CONCRETE ROAD AT SOUNDARESWARAR KOIL STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26317,Roads,Completed,NK-KODAMBAKKAM,142,2621000,"LAYING CEMENT CONCRETE ROAD AT OTHAVADAI STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26329,Roads,Completed,NK-KODAMBAKKAM,142,590000,"LAYING CEMENT CONCRETE ROAD AT BRAHMIN LANE IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26334,Roads,Completed,NK-KODAMBAKKAM,142,1214000,"LAYING CEMENT CONCRETE ROAD AT VARSHIDHI VINAYAGAR KOIL STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26338,Roads,Completed,NK-KODAMBAKKAM,142,1573000,"LAYING CEMENT CONCRETE ROAD AT CHETTY STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26342,Roads,Completed,NK-KODAMBAKKAM,142,1268000,"LAYING CEMENT CONCRETE ROAD AT ANJANEYAR KOIL STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26343,Roads,Completed,NK-KODAMBAKKAM,142,1268000,"LAYING CEMENT CONCRETE ROAD AT RAMANUJAM STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26345,Roads,Completed,NK-KODAMBAKKAM,142,1477000,"LAYING CEMENT CONCRETE ROAD AT BHARATHIYAR STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26347,Roads,Completed,NK-KODAMBAKKAM,142,1152000,"LAYING CEMENT CONCRETE ROAD AT POLICE LANE IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26348,Roads,Completed,NK-KODAMBAKKAM,142,2433000,"LAYING CEMENT CONCRETE ROAD AT DURAISAMY THOTTAM IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26353,Roads,Completed,NK-KODAMBAKKAM,142,1143000,"LAYING CEMENT CONCRETE ROAD AT DHANASEKARAN STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26437,Roads,Completed,NK-KODAMBAKKAM,142,758000,"LAYING OF CEMENT CONCRETE ROAD AT KARUNAKARAN STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26452,Roads,Completed,NK-KODAMBAKKAM,142,1214000,"LAYING OF CEMENT CONCRETE ROAD AT RAJAGOPAL STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26455,Roads,Completed,NK-KODAMBAKKAM,142,456000,"LAYING OF CEMENT CONCRETE ROAD AT CHINNAMMAL STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26457,Roads,Completed,NK-KODAMBAKKAM,142,6278000,"LAYING OF CEMENT CONCRETE ROAD AT JEENIS STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26474,Roads,Completed,NK-KODAMBAKKAM,142,1969000,"LAYING OF CEMENT CONCRETE ROAD AT ABDUL RAZACK STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26477,Roads,Completed,NK-KODAMBAKKAM,142,1143000,"LAYING OF CEMENT CONCRETE ROAD AT ABDUL RAZACK 1ST STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26481,Roads,Completed,NK-KODAMBAKKAM,142,1484000,"LAYING OF CEMENT CONCRETE ROAD AT ABDUL RAZACK 2ND STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26503,Roads,Completed,NK-KODAMBAKKAM,142,2097000,"LAYING OF CEMENT CONCRETE ROAD AT MORTUARY ROAD(ANNA ROAD) AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26506,Roads,Completed,NK-KODAMBAKKAM,142,1387003,"LAYING OF CEMENT CONCRETE ROAD AT SALAVIYAR COLONY 1 ST STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26508,Roads,Completed,NK-KODAMBAKKAM,142,688000,"LAYING OF CEMENT CONCRETE ROAD AT SALAVIYAR COLONY 2 ND STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26510,Roads,Completed,NK-KODAMBAKKAM,142,1613000,"LAYING OF CEMENT CONCRETE ROAD AT BRAHMIN STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26513,Roads,Completed,NK-KODAMBAKKAM,142,3302000,"LAYING OF CEMENT CONCRETE ROAD AT DIWAN BASHIYAM STREET AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26520,Roads,Completed,NK-KODAMBAKKAM,142,1330000,"LAYING OF CEMENT CONCRETE ROAD AT KARNEESWARAR KOIL STREET CONSERVANCY LANE -1 AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26522,Roads,Completed,NK-KODAMBAKKAM,142,1180000,"LAYING OF CEMENT CONCRETE ROAD AT KARNEESWARAR KOIL STREET CONSERVANCY LANE -2 AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2017-18 NK/2014-15/26523,Roads,Completed,NK-KODAMBAKKAM,142,1445000,"LAYING OF CEMENT CONCRETE ROAD AT V V KOIL CONSERVANCY LANE -1 AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26524,Roads,Completed,NK-KODAMBAKKAM,142,1171000,"LAYING OF CEMENT CONCRETE ROAD AT V V KOIL CONSERVANCY LANE -2 AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26532,Roads,Completed,NK-KODAMBAKKAM,142,1211000,"LAYING OF CEMENT CONCRETE ROAD AT KOTHAVALCHAVADI CONSERVANCY LANE AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26533,Roads,Completed,NK-KODAMBAKKAM,142,1952000,"LAYING OF CEMENT CONCRETE ROAD AT PERUMAL KOIL CONSERVANCY LANE AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26534,Roads,Completed,NK-KODAMBAKKAM,142,977000,"LAYING OF CEMENT CONCRETE ROAD AT KAVARAI STREET CONSERVANCY LANE AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26537,Roads,Completed,NK-KODAMBAKKAM,142,586000,"LAYING OF CEMENT CONCRETE ROAD AT PILLAIYAR KOIL LANE AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2017-18 NK/2014-15/26538,Roads,Completed,NK-KODAMBAKKAM,142,879000,"LAYING OF CEMENT CONCRETE ROAD AT BALAJI SINGH LANE AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26542,Roads,Completed,NK-KODAMBAKKAM,142,1559000,"LAYING OF CEMENT CONCRETE ROAD AT THIDEER NAGAR AT DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26637,Roads,Completed,NK-KODAMBAKKAM,142,2341000,"LAYING OF CEMENT CONCRETE ROAD AT SAMIYAR THOTTAM SLUM MAIN ROAD IN DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/26641,Roads,Completed,NK-KODAMBAKKAM,142,1559000,"LAYING OF CEMENT CONCRETE ROAD AT SAMIYAR THOTTAM SLUM LANES IN DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2014-15,2016-17 NK/2014-15/29342,Roads,Completed,NK-KODAMBAKKAM,142,980000,"ATTENDING PATCHES USING BITUMINOUS CONCRETE IN RAMAPURAM RAMASAMY STREET, NARAYANASMY STREET AND VARIOUS STREETS IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2014-15,2017-18 NK/2014-15/29595,Buildings,Completed,NK-KODAMBAKKAM,142,555000,"providing the electrical works saidapet uphc at west jones road in div-142,unit-30,zone-10.",Own Sources,10,2014-15,2018-19 NK/2014-15/30871,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,539500,"PUMP HIRING AND PRIVATE LABOURS FOR FLOOD WORK IN DN-142, UNIT-30,ZONE-10",Own Sources,10,2014-15,2016-17 NK/2014-15/7510,Buildings,Completed,B-Buildings,142,15749000,"NEW CONSTRUCTION OF URBAN PRIMARY HEALTH CENTRE GROUND FLOOR, FIRST FLOOR,HEAD ROOM,LIFT MACHINE ROOM, WATER SUPPLY ARRANGEMENTS AND DRAINAGE ARRANGEMENTS IN WEST JONES ROAD IN DIV -142,UNIT -30,ZONE -10",Own Sources,10,2014-15,2016-17 D/2014-15/26473,Storm Water Drain,Completed,D-Storm Water Drains,143,246660000,Construction of Integrated Storm water drains in Cooum Watershed of Cooum Basin in expanded area of Chennai Corporation -Package-11,"Loans, Grants And Own Sources",11,2014-15,2018-19 D/2014-15/27531,Storm Water Drain,Completed,D-Storm Water Drains,143,284035000,Construction of Integrated Storm water drain in Nolambur watershed of Cooum Basin in expanded area of Chennai Corporation- Package -22,Loans And Grants,11,2014-15,2017-18 NL/2014-15/13559,Parks,Completed,NL-VALASARAVAKKAM,143,5870000,"PROPOSED CONSTRUCTED OF PARK AT PHASE II, 13TH CROSS STREET IN DN-143, UNIT-32, ZONE-11",Own Sources,11,2014-15,2018-19 NL/2014-15/13564,Parks,Completed,NL-VALASARAVAKKAM,143,3440000,"FORMING PARK AT PHASE II 3rd CROSS STREET IN DN--143, UNIT 32, ZONE 11",Own Sources,11,2014-15,2017-18 NL/2014-15/13600,Buildings,Completed,NL-VALASARAVAKKAM,143,478000,"CONSTRUCTION OF COMPOUND WALL (SOUTH AND WEST SIDE ) AT NOLAMBUR PHASE-1 1ST MAIN ROAD PARK IN D-143, UNIT-32 ZONE-11.",Own Sources,11,2014-15,2016-17 NL/2014-15/15868,Parks,Completed,NL-VALASARAVAKKAM,143,392000,"Maintenance of Park at Nolambur Phase-I Third Main Road in Dn.143,Unit-32,Zone-11(By employed qualified horticulturist 0niy)",Own Sources,11,2014-15,2017-18 NL/2014-15/15869,Parks,Completed,NL-VALASARAVAKKAM,143,340000,"Maintenance of Park at Nolambur Phase-I 9th Main Road in Dn.143,Unit-32,Zone-11(By employed qualified horticulturist 0niy)",Own Sources,11,2014-15,2017-18 NL/2014-15/15870,Parks,Completed,NL-VALASARAVAKKAM,143,333000,"Maintenance of Park at Nolambur Phase-I Channel Road Park in Dn.143,Unit-32,Zone-11(By employed qualified horticulturist 0niy)",Own Sources,11,2014-15,2017-18 NL/2014-15/23718,Roads,Completed,NL-VALASARAVAKKAM,143,1800000,"Laying the Cement Concrete Roads at Nolambur 4th Block 14th street and 4th Block 16th street 2nd Cros Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23772,Roads,Completed,NL-VALASARAVAKKAM,143,1712000,"Laying the Cement Concrete Roads at Nolambur Phase-I, 23rd Cross Street and 4th Block 12th street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23775,Roads,Completed,NL-VALASARAVAKKAM,143,1794000,"Laying the Cement Concrete Roads at 4th Block 8th Street and 18th Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23786,Roads,Completed,NL-VALASARAVAKKAM,143,1646000,"Laying the Cement Concrete Roads at 4th Block 15 Street, 1st Cross Street to 4th Cross Sttreet, 4 th Street 5th Cross Street and 6th Cross Street in Division 143, Unit 32, Zone 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23792,Roads,Completed,NL-VALASARAVAKKAM,143,1748000,"Laying the Cement Concrete Roads at 4th Block 1st Street 2nd Cross Street to 6th Cross Street and Thiruvalluvar 2nd Cross Street to 4th Cross Street in Division 143, Unit 32, Zone 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23804,Roads,Completed,NL-VALASARAVAKKAM,143,2055000,"Laying the Cement concrete Roads at 4th Block 2nd Street 1st cross street. 4th Block 5th street and 5th Block Sivan koil street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23806,Roads,Completed,NL-VALASARAVAKKAM,143,2368000,"Laying the Cement Concrete Roads at Goodwin Road (Reach-1) in Division 143, Unit 32, Zone 11",Loans And Grants,11,2014-15,2017-18 NL/2014-15/23807,Roads,Completed,NL-VALASARAVAKKAM,143,2368000,"Laying the Cement Concrete Roads at Goodwin Road (Reach-2) in Division 143, Unit 32, Zone 11",Loans And Grants,11,2014-15,2017-18 NL/2014-15/23833,Roads,Completed,NL-VALASARAVAKKAM,143,900000,"Laying the Cement Concrete Roads at 4th Block 16th Street 1st cross street and 4th Block 17th Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23836,Roads,Completed,NL-VALASARAVAKKAM,143,1798000,"Laying the Cement Concrete Roads at 4th Block 9th Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2017-18 NL/2014-15/23839,Roads,Completed,NL-VALASARAVAKKAM,143,1784000,"Laying Cement Concrete Roads at 4th Block 10th Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23844,Roads,Completed,NL-VALASARAVAKKAM,143,1784000,"Laying the Cement Concrete Roads at 4th Block 11th Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23845,Roads,Completed,NL-VALASARAVAKKAM,143,1784000,"Laying of the Cement Concrete Roads at 4th Block 11th Street 2nd cross street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23850,Roads,Completed,NL-VALASARAVAKKAM,143,1403000,"Laying the Cement Concrete Roads at 4th Block 15th Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23852,Roads,Completed,NL-VALASARAVAKKAM,143,1321000,"Laying the Cement Concrete Roads at 4th Block 11th Street 1st cross street. 4th Block 7th street and Cross street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2017-18 NL/2014-15/24085,Roads,Completed,NL-VALASARAVAKKAM,143,2396000,"Laying the Cement Concrete Roads at 4th Block 13th street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24088,Roads,Completed,NL-VALASARAVAKKAM,143,1496000,"Laying the Cement Concrete Road at 4th Block 16th street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24090,Roads,Completed,NL-VALASARAVAKKAM,143,1636000,"Laying the Cement Concrete Roads at 4th Block 3rd street and Kamarajar 2nd Cross Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2017-18 NL/2014-15/24091,Roads,Completed,NL-VALASARAVAKKAM,143,1419000,"Laying the Cement Concrete Road at Kamarajar 1st Cross Street and Thiruvalluvar 1st Cross Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24093,Roads,Completed,NL-VALASARAVAKKAM,143,2071000,"Laying the Cement Concrete Roads at Kamarajar Street and 3rd Cross Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2017-18 NL/2014-15/24094,Roads,Completed,NL-VALASARAVAKKAM,143,1664000,"Laying the Cement concrete roads at Kannadasan Street, Vivekanandhar Main Road and 3rd Vivekanandhar 1st Cross Street in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24100,Roads,Completed,NL-VALASARAVAKKAM,143,1501000,"Laying the Cement Concrete Road at Vivekanandhar 2nd Street and Thiruvalluvar Main Road in Division -143, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/27519,Footpath,Completed,NL-VALASARAVAKKAM,143,606000,"Construction of Ramp for Foot path at Various Streets in Dn-143, U-32, Z-XI",Own Sources,11,2014-15,2016-17 NL/2014-15/28157,Roads,Completed,NL-VALASARAVAKKAM,143,2490000,"STRENGTHENING AND LAYING THE BT ROAD WITH DBMC3 AND BCCMP1 AT V.O.C MAIN ROAD EXT TO S & P GARDEN (GRID-III SAVINGS) IN DN-143 , U-32, Z-11",Own Sources,11,2014-15,2016-17 NL/2014-15/28163,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,9940000,"CONSTRUCTION OF 900 X 900 SIZE STORM WATER DRAIN GRID PHASE-III AT V.O.C. MAIN ROAD EST TO S & P GARDEN (GRID-III SAVINGS) IN DN-143, U-32, Z-11.",Own Sources,11,2014-15,2016-17 NL/2014-15/3963,Roads,Completed,NL-VALASARAVAKKAM,143,887000,"Laying of Cement Concrete Roads at Vembuli Amman Koil 1st Cross Street to 6th Cross Street in Division 143, Unit-32, Zone-XI (Councilor Fund)",Own Sources,11,2014-15,2016-17 NL/2014-15/3964,Roads,Completed,NL-VALASARAVAKKAM,143,546000,"Laying of Cement Concrete Roads at Vembuli Amman Koil 7th Cross Street to 8th Cross Street in Division 143, Unit-32, Zone-XI (Councilor Fund)",Own Sources,11,2014-15,2016-17 NL/2014-15/3965,Roads,Completed,NL-VALASARAVAKKAM,143,645000,"Laying of Cement Concrete Roads at Vembuli Amman Koil 9th Cross Street to 12th Cross Street in Division 143, Unit-32, Zone-XI (Councilor Fund)",Own Sources,11,2014-15,2016-17 NL/2014-15/3966,Roads,Completed,NL-VALASARAVAKKAM,143,922000,"Laying of Cement Concrete Roads at Vembuli Amman Koil 1st Street in Division 143, Unit-32, Zone-XI (Councilor Fund)",Own Sources,11,2014-15,2016-17 NL/2014-15/8314,Buildings,Completed,NL-VALASARAVAKKAM,143,998000,"Providing Rental Modulor Toilet on Contract basis and Maintenance for one year for the locations at Mogapaier west Street-Dn-143, Karthikeyan Nagar D-144, Ambethkar Nagar D-146, Pallavan Nagar 6th Street D-147 in U-32, Zone XI",Own Sources,11,2014-15,2016-17 NL/2014-15/20714,Buildings,Completed,NL-VALASARAVAKKAM,144,2010000,"CONSTRUCTION OF ANGANWADI BUILDING AT MMDA COLONY 6th BLOCK 33rd STREET IN DIV-144,UNIT 32,ZONE XI.",MLACDS,11,2014-15,2018-19 NL/2014-15/23760,Roads,Completed,NL-VALASARAVAKKAM,144,1900000,"Forming and Laying the BT Road at Venkateswara Nagar 1st,2nd,3rd Street and MMDA 7th Block 5th Street in Dn-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23899,Roads,Completed,NL-VALASARAVAKKAM,144,1963000,"Forming and Laying the BT Road at Ayyavu Nagar 1st & 2nd Cross Streets & Ohm Shakthi Nagar 1st cross street (REACH-2) in D-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23907,Roads,Completed,NL-VALASARAVAKKAM,144,1878000,"Forming and Laying the BT Road at Ohm Shakthi nagar 1st Cross Street(REACH-1)& P.H. Road 1st Cross Street in Dn-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23992,Roads,Completed,NL-VALASARAVAKKAM,144,1636000,"LAYING OF CEMENT CONCRETE ROADS AT MMDA COLONY 4TH BLOCK 1st & 3rd STREET IN DN 144, UNIT-32, ZONE-11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24033,Roads,Completed,NL-VALASARAVAKKAM,144,2530000,"Forming and Laying the BT Road at MMDA Colony 4th Block 8th Street & 5th Block 15th, 16th & 17th Street in Dn-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24068,Roads,Completed,NL-VALASARAVAKKAM,144,2528000,"Forming and Laying the BT Road at MMDA Colony 5th Block 18th, 19th, 21st & 22nd Street in Dn-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24073,Roads,Completed,NL-VALASARAVAKKAM,144,2310000,"Forming and Laying the BT Road at MMDA Colony 6th Block 26th,27th,28th & 29th Streets in Dn-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24111,Roads,Completed,NL-VALASARAVAKKAM,144,1165000,"Forming and Laying the BT Road at MMDA Colony 6th Block 33rd & 7th Block 3rd Street and Kannan Nagar 1st Street Extension in Dn-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24116,Roads,Completed,NL-VALASARAVAKKAM,144,2186000,"LAYING OF CEMENT CONCRETE ROADS AT MADURAI NAICKEN 2nd, 3rd, 4th,5th,6th, 7th,8th,9th ,10th Street & NAGATHAMMAN KOIL STREET IN DN 144, UNIT-32, ZONE-11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24149,Roads,Completed,NL-VALASARAVAKKAM,144,2259000,"Forming and Laying the BT Road at MMDA Colony 6th Block 31st,35th,36th,37th,38th and 7th Block 4th Street in Dn-144,Unit-32,Zone XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24153,Roads,Completed,NL-VALASARAVAKKAM,144,1572000,"LAYING OF CEMENT CONCRETE ROADS AT MMDA COLONY 4TH BLOCK 8th, 9th & 10th STREET(REACH 1) IN DN 144, UNIT-32, ZONE-11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24158,Roads,Completed,NL-VALASARAVAKKAM,144,1206000,"LAYING OF CEMENT CONCRETE ROADS AT MMDA COLONY 4TH BLOCK 10th (REACH 2) & 13th STREET IN DN 144, UNIT-32, ZONE-11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24162,Roads,Completed,NL-VALASARAVAKKAM,144,1206000,"LAYING OF CEMENT CONCRETE ROADS AT MMDA COLONY 4TH BLOCK 2nd, 4th & 5th STREET IN DN 144, UNIT-32, ZONE-11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24193,Roads,Completed,NL-VALASARAVAKKAM,144,1444000,"LAYING OF CEMENT CONCRETE ROADS AT MMDA COLONY 5TH BLOCK 20th,23rd 24th and 6th BLOCK 30th,32nd & 34th STREETS IN DN 144, UNIT-32, ZONE-11.",Loans And Grants,11,2014-15,2016-17 D/2014-15/26774,Storm Water Drain,Completed,D-Storm Water Drains,145,248689000,Construction of Integrated Storm water drain in Virugambakkam ? Arumbakkam watershed of Cooum Basin in expanded area of Chennai Corporation- Package -29,"Loans, Grants And Own Sources",11,2014-15,2018-19 NL/2014-15/23787,Roads,Completed,NL-VALASARAVAKKAM,145,2910000,"Relaying the Cement Concrete Road at Perumal Koil Street (East) 1st to 10th Streets in DN-145, Unit-33, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24063,Roads,Completed,NL-VALASARAVAKKAM,145,1279000,"Relaying the Cement Concrete Road at Perumal Koil Street (West) 1st to 9th Street in DN-145, Unit-33, Zone-XI.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24080,Roads,Completed,NL-VALASARAVAKKAM,145,2100000,"Forming the Cement Concrete Road at Madha Kovil Street, Barathi Street (Nethaji Avenue)&Perumal koil east 11 to 16 cross street in DN-145, Unit-33, Zone-XI.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/8315,Buildings,Completed,NL-VALASARAVAKKAM,145,503000,"Providing Rental Modulor Toilet on Contract basis on Maintanance for one year for the locations at Nerkundram Main Road Dn-145, & Brindhavan Nagar Main Road - D-149, in U-33, Zone XI",Own Sources,11,2014-15,2016-17 D/2014-15/24444,Storm Water Drain,Completed,D-Storm Water Drains,146,239411000,CONSTRUCTION OF INTEGRATED STORM WATER DRAIN IN COOUM WATERSHED OF COOUM BASIN IN EXPANDED AREA OF CHENNAI CORPORATION - PACKAGE-6,Loans And Grants,11,2014-15,2019-20 NL/2014-15/23340,Roads,Completed,NL-VALASARAVAKKAM,146,2448000,"forming and laying the BT road at jeeva street(rajiv ganthi nagar),periyar street,rajiv ganthi nagar 2nd cr street,karunakara perumal koil street &cross street in Dn-146,U-32,Z-11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23363,Roads,Completed,NL-VALASARAVAKKAM,146,2300000,"forming and laying the BT road at n.s.k salai (bharathidasan nagar),n.s.k cross street, bharathidasan nagar 10th street 5th cross street in Dn-146,U-32,Z-11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23366,Roads,Completed,NL-VALASARAVAKKAM,146,2200000,"forming and laying the BT road at bharathidasan nagar 4th cr street (kannadasan street),bharathidasan nagar 10th st 1st crstreet,bharathidasan nagar 10th st 3rd crstreet in Dn-146,U-32,Z-11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23369,Roads,Completed,NL-VALASARAVAKKAM,146,2150000,"Forming and Laying the BT Road at indhira ganthi street(bharathidasan nagar),bharathidasan nagar 1st street 1st lane, bharathidasan nagar 11th street,DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23371,Roads,Completed,NL-VALASARAVAKKAM,146,1780000,"Forming and Laying the BT Road at kamarajar nagar anex 1st street,kamarajar nagar anex 2nd street,kamarajar nagar anex 3rd street,DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23374,Roads,Completed,NL-VALASARAVAKKAM,146,2230000,"Forming and Laying the BT Road at kamarajar nagar road,kamarajar nagar main road DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23377,Roads,Completed,NL-VALASARAVAKKAM,146,1670000,"Forming and Laying the BT Road at sithi vinayagar 1st cr street, sithi vinayagar 2nd cr street,sithi vinayagar 3rd cr street,nethaji street DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23378,Roads,Completed,NL-VALASARAVAKKAM,146,2190000,"Forming and Laying the BT Road at ganapathy nagar 5th street,ganapathy nagar 2nd street extn.DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23379,Roads,Completed,NL-VALASARAVAKKAM,146,1150000,"Forming and Laying the BT Road at ganapathy nagar 1st street,ganapathy nagar 1st 1st cr street,DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23380,Roads,Completed,NL-VALASARAVAKKAM,146,2300000,"Forming and Laying the BT Road at sri lakshmi nagar 3rd street,sri lakshmi nagar 9th street,sri lakshmi nagar 6th street(cross),sri lakshmi nagar main road cross DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23381,Roads,Completed,NL-VALASARAVAKKAM,146,1967000,Forming and Laying the BT Road at S.B.bala supramaniyam street in DN:146 UNIT:32 ZONE:11,Loans And Grants,11,2014-15,2016-17 NL/2014-15/23385,Roads,Completed,NL-VALASARAVAKKAM,146,2480000,"Forming and Laying the BT Road at iyappa nagar 3rd street,new supramani nagar(iyappa nagar 4th street),new supramani 1st cr street,new supramani 2nd cr street,new supramani 3rd cr street DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23386,Roads,Completed,NL-VALASARAVAKKAM,146,2040000,"Forming and Laying the BT Road at sri lakshmi nagar 8th cr street,sri lakshmi nagar 7th cr street,sri lakshmi nagar 8th street cross DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23388,Roads,Completed,NL-VALASARAVAKKAM,146,2043000,"Forming and Laying the BT Road at annai sathya street, muthu mari amman koil street DN:146 UNIT:32 ZONE:11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23392,Roads,Completed,NL-VALASARAVAKKAM,146,1686000,Forming and Laying the BT Road at ganapathy nagar 6th street DN:146 UNIT:32 ZONE:11,Loans And Grants,11,2014-15,2016-17 NL/2014-15/24107,Roads,Completed,NL-VALASARAVAKKAM,146,1516000,"Forming the Cement Concrete Road at bharathiyar street,kanthan 1st&2nd cross street,dhanalakshmi 17th street,perumal koil 4th cross street,selva vinayagar 1st cross street, DN-146, Unit-32, Zone-XI.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24204,Roads,Completed,NL-VALASARAVAKKAM,146,1158000,"Forming the Cement Concrete Road at North mada cross 14o 17th street DN-146, Unit-32, Zone-XI.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/11976,Buildings,Completed,NL-VALASARAVAKKAM,147,999000,Providing Subsidy Tiffen Centre at Gangai ammam Koil Street Manthoop Colony in Division 147 Unit 32 Zone 11,Own Sources,11,2014-15,2017-18 NL/2014-15/11977,Buildings,Completed,NL-VALASARAVAKKAM,147,859000,"Providing Glading Arrangements to New Fair Price Canteen at Gangai amman Koil Street Manthoop Colony in Division-147, Unit-32, Zone-XI.",Own Sources,11,2014-15,2017-18 NL/2014-15/11978,Buildings,Completed,NL-VALASARAVAKKAM,147,998000,Providing water supply and electrical works at Amma Unavagam at Gangai amman Koil Street Manthope Colony in Division 147 Unit 32 Zone 11,Own Sources,11,2014-15,2017-18 NL/2014-15/13154,Parks,Completed,NL-VALASARAVAKKAM,147,280000,ADDITIONAL IMPROVEMENTS TO THE EXISTING PARK AT BHARATHY NAGAR PARK IN DN-147 UNIT-32 ZONE-11.,Own Sources,11,2014-15,2016-17 NL/2014-15/23779,Roads,Completed,NL-VALASARAVAKKAM,147,1030100,"Forming and Laying the BT Road at Pallavan Nagar in Division 147, Unit 32, Zone 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23780,Roads,Completed,NL-VALASARAVAKKAM,147,1277500,"Forming and Laying the BT Road at Krishnamachari 7th Street and 8th Street in Division 147, Unit 32, Zone 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23796,Roads,Completed,NL-VALASARAVAKKAM,147,810000,"Forming and Laying the BT Road at Bharathi Nagar 3rd Cross Street and Bhakiyam Street in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23800,Roads,Completed,NL-VALASARAVAKKAM,147,1289000,"Forming and Laying the BT Road at Bhakiyalaksmi Nagar 1st Cross Street to 3rd Cross Street in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23802,Roads,Completed,NL-VALASARAVAKKAM,147,903600,"Forming and Laying the BT Road at Mahalakshmi Avenue in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23803,Roads,Completed,NL-VALASARAVAKKAM,147,2473300,"Forming and Laying the BT Road at Kalaimani Street in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23805,Roads,Completed,NL-VALASARAVAKKAM,147,1030100,"Forming and Laying the BT Road at Ponniyamman Koil Street in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24113,Roads,Completed,NL-VALASARAVAKKAM,147,2348000,"Forming and Laying the BT Road at Ekambaram Estate 2nd Street to 4th Street in Division 147, Unit 32, Zone 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24115,Roads,Completed,NL-VALASARAVAKKAM,147,2005300,"Forming and Laying the BT Road at Ekambaram Estate 5th Street to 6th Street in Division 147, Unit 32, Zone 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24118,Roads,Completed,NL-VALASARAVAKKAM,147,1804000,"Forming and Laying the BT Road at Ekambaram Estate 1st Street, Annammal Street and Sundar Nagar 6th Street in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24119,Roads,Completed,NL-VALASARAVAKKAM,147,1510000,"Forming and Laying the BT Road at Ekambaram Estate 7th Street in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24120,Roads,Completed,NL-VALASARAVAKKAM,147,1078400,"Forming and Laying the BT Road at Thiruvalluar 1st Street, 1st Cross Street and 2nd Cross Street in Division -147, Unit-32, Zone-XI",Loans And Grants,11,2014-15,2016-17 NL/2014-15/24121,Roads,Completed,NL-VALASARAVAKKAM,147,1476900,"Laying the Cement Concrete Roada at Sri Devi Nagar 8th Street 1st Lane to 3rd Lane, Puthu Koil Street, Chokanathan Nagar 1st cross Street, Sri Devi Nagar 7thcross Street and Gangaiamman Koil Cross Street in Division 147, Unit 32, Zone 11",Loans And Grants,11,2014-15,2017-18 NL/2014-15/24123,Roads,Completed,NL-VALASARAVAKKAM,147,1380100,"Laying the Cement Concrete Road at Govindhappan Nagar 3rd Street in Division 147, Unit 32, Zone 11",Loans And Grants,11,2014-15,2017-18 NL/2014-15/24124,Roads,Completed,NL-VALASARAVAKKAM,147,1348600,"Laying the Cement Concrete Road at Gandhi Street in Division 147, Unit 32, Zone 11",Loans And Grants,11,2014-15,2017-18 NL/2014-15/24309,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,10330000,"CONSTRUCTION OF 900 X 900 SIZE STORM WATER DRAIN GRID-3 SAVING'S AT ALAPAKKAM MAIN ROAD IN DN-147, U-32 , Z-XI",Own Sources,11,2014-15,2016-17 NL/2014-15/24474,Roads,Completed,NL-VALASARAVAKKAM,147,4330000,"FORMING AND LAYING THE BITUMINOUS ROAD AT ASTALALAKSHMI NAGAR 6TH STREET TO 8TH STREET,GRID-3 SAVING'S IN DIVISION 147, UNIT 32, ZONE-XI",Own Sources,11,2014-15,2016-17 NL/2014-15/24476,Roads,Completed,NL-VALASARAVAKKAM,147,3410000,"FORMING AND LAYING THE BITUMINOUS ROAD AT ASTALALAKSHMI NAGAR 5TH MAIN ROAD,GRID-3 SAVING'S IN DIVISION 147, UNIT 32, ZONE-XI",Own Sources,11,2014-15,2016-17 NL/2014-15/24480,Roads,Completed,NL-VALASARAVAKKAM,147,2240000,"FORMING AND LAYING THE BITUMINOUS ROAD AT GOVINDAPPAN NAICKER 1ST STREET AND 2ND STREET, GRID-3 SAVING'S IN DIVISION 147, UNIT 32, ZONE-XI",Own Sources,11,2014-15,2016-17 NL/2014-15/24482,Roads,Completed,NL-VALASARAVAKKAM,147,4770000,"FORMING AND LAYING THE BITUMINOUS ROAD AT PALAVAN NAGAR MAIN ROAD (P.T.C. OFFICER COLONY)GRID-3 SAVING'S IN DIVISION 147, UNIT 32, ZONE-XI",Own Sources,11,2014-15,2016-17 D/2014-15/25529,Storm Water Drain,Completed,D-Storm Water Drains,148,307257000,Construction of Integrated Storm water drain in Cooum watershed of Cooum Basin in expanded area of Chennai Corporation- Package -2,Loans And Grants,11,2014-15,2018-19 D/2014-15/26788,Storm Water Drain,Completed,D-Storm Water Drains,148,216960000,Construction of Integrated Storm water drain in Virugambakkam ? Arumbakkam watershed of Cooum Basin in expanded area of Chennai Corporation- Package -30,Loans And Grants,11,2014-15,2018-19 D/2014-15/27389,Storm Water Drain,Completed,D-Storm Water Drains,148,363660000,Construction of Integrated Storm water drain in Virugambakkam ? Arumbakkam watershed of Cooum Basin in expanded area of Chennai Corporation- Package -28,Loans And Grants,11,2014-15,2018-19 NL/2014-15/1638,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,689000,"Improvement of Side Drain at Rajivi Nagar 1st Street in Division -148, Unit-33, Zone-XI",Own Sources,11,2014-15,2016-17 NL/2014-15/1639,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,642000,"Improvement of Side Drain at Rajivi Nagar 2nd Street and 3rd Street in Division -148, Unit-33, Zone-XI",Own Sources,11,2014-15,2016-17 NL/2014-15/21916,Buildings,Completed,NL-VALASARAVAKKAM,148,930000,"Improvements to Division Office at Meenachiamman nagar Sannathi street in Dn-148, U-33, Z-11",Own Sources,11,2014-15,2019-20 NL/2014-15/31497,Roads,Completed,NL-VALASARAVAKKAM,148,1468000,"Relaying the BT Road at Thangal Karai main road (reach-1} IN DN-148,U-33, Z-11.",Loans And Grants,11,2014-15,2016-17 D/2014-15/25515,Storm Water Drain,Completed,D-Storm Water Drains,149,362127000,Construction of Integrated Storm water drain in Cooum watershed of Cooum Basin in expanded area of Chennai Corporation- Package -1,Loans And Grants,11,2014-15,2018-19 NL/2014-15/17069,Parks,Completed,NL-VALASARAVAKKAM,149,453000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT ARCOT ROAD (ALSA TOWER O.S.R LAND) IN DN-149,UNIT-33,ZONE-XI(By qualified Horticulturist for two year).",Own Sources,11,2014-15,2017-18 NL/2014-15/17070,Parks,Completed,NL-VALASARAVAKKAM,149,490000,"ANNUAL MAINTENANCE TO CORPORATION PARK AT NEITHAL STREET( CEEBROS O.S.R LAND) IN DN-149,UNIT-33,ZONE-XI(By qualified Horticulturist for one year).",Own Sources,11,2014-15,2017-18 BR/2014-15/30997,Roads,Completed,BR-Bus Route Roads,150,2536000,Road Cut Restoration At Chettiyar Agaram main road From Chainage 1540 M - 2310 M Div- 150 in zone 11,Deposit Works,11,2014-15,2016-17 D/2014-15/24269,Storm Water Drain,Completed,D-Storm Water Drains,150,353615000,Construction of integrated storm water drains in Cooum watershed of Cooum basin in expanded area of Chennai Corporation-Package-3.,Loans And Grants,11,2014-15,2018-19 D/2014-15/24280,Storm Water Drain,Completed,D-Storm Water Drains,150,268068000,Construction of integrated storm water drains in Cooum watershed of Cooum basin in expanded area of Chennai Corporation-Package-4.,Loans And Grants,11,2014-15,2018-19 D/2014-15/24436,Storm Water Drain,Completed,D-Storm Water Drains,150,424310000,CONSTRUCTION OF INTEGRATED STORM WATER DRAIN IN COOUM WATERSHED OF COOUM BASIN IN EXPANDED AREA OF CHENNAI CORPORATION - PACKAGE-5,Loans And Grants,11,2014-15,2018-19 D/2014-15/24454,Storm Water Drain,Completed,D-Storm Water Drains,150,308435000,CONSTRUCTION OF INTEGRATED STORM WATER DRAIN IN COOUM WATERSHED OF COOUM BASIN IN EXPANDED AREA OF CHENNAI CORPORATION - PACKAGE-7,Loans And Grants,11,2014-15,2019-20 NL/2014-15/12871,Buildings,Completed,NL-VALASARAVAKKAM,150,299000,"DEMOLITION AND RECONSTRUCTION OF BOYS TOILET AT KARAMBAKKAM PRIMARY SCHOOL IN DN-150, U-34, Z-11",MLACDS,11,2014-15,2016-17 NL/2014-15/16484,Parks,Completed,NL-VALASARAVAKKAM,150,450000,"ANNUAL MAINTENANCE TO MARUTHI NAGAR PARK PHASE-III AND RAJESWARI NAGAR PARK IN DN.150, UNIT.34, ZONE.11(By Employed qualified horticulturist only)",Own Sources,11,2014-15,2017-18 NL/2014-15/16485,Parks,Completed,NL-VALASARAVAKKAM,150,377000,"ANNUAL MAINTENANCE TO MARUTHI NAGAR PARK PHASE-I. IN DN.150, UNIT.34, ZONE.11(By Employed qualified horticulturist only)",Own Sources,11,2014-15,2017-18 NL/2014-15/17076,Parks,Completed,NL-VALASARAVAKKAM,150,390000,"ANNUAL MAINTENANCE OF PARK AT PONNIAMMAN NAGAR PARK IN 150,UNIT-33,ZONE-XI.(By Employed qualified horticulturist only)",Own Sources,11,2014-15,2017-18 NL/2014-15/18883,Buildings,Completed,NL-VALASARAVAKKAM,150,310000,"BUILDING MAINTANCE AT DIV150, U-34.Z-11",Own Sources,11,2014-15,2017-18 NL/2014-15/18946,Buildings,Completed,NL-VALASARAVAKKAM,150,209000,"Providing boring arrangements,weathering course laying andTiles Laying work at Division office Dn-150-XI.Unit-34, Zone-XI",Own Sources,11,2014-15,2017-18 NL/2014-15/19362,Buildings,Completed,NL-VALASARAVAKKAM,150,232000,"Construction of Conservancy Ladies dressing Room, etc in Dn-150, Unit-34, Zone-XI.",Own Sources,11,2014-15,2017-18 NL/2014-15/19363,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,75000,"Construction of pipe culvert at karambakkam school road and karambakkam main road in Dn-150, Unit-34, Zone-XI.",Own Sources,11,2014-15,2017-18 NL/2014-15/23095,Roads,Completed,NL-VALASARAVAKKAM,150,2718000,"FORMING AND LAYING THE BT ROAD AT ANDAL NAGAR MAIN ROAD IN DN - 150, U - 34 ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23097,Roads,Completed,NL-VALASARAVAKKAM,150,3987000,"FORMING AND LAYING THE BT ROAD AT INDHRA NAGAR 1ST TO 4TH STREET IN DN - 150, U - 34 ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23099,Roads,Completed,NL-VALASARAVAKKAM,150,3716000,"FORMING AND LAYING THE BT ROAD AT INDHRA NAGAR MAIN ROAD IN DN - 150, U - 34 ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23160,Roads,Completed,NL-VALASARAVAKKAM,150,2027000,"STRENTHING AND RELAYING THE BT ROAD AT SIVABOOTHAM MEDU PILLIYAR KOIL STREET IN DIV - 150 , U - 34 ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23167,Roads,Completed,NL-VALASARAVAKKAM,150,3110000,STRENGTHING AND RELAYING THE BT ROAD AT CHETTIYAR AGARAM SCHOOL STREET AND GANDHI NAGAR MAIN ROAD IN DIV - 150 U - 34 ZONE - 11,Loans And Grants,11,2014-15,2016-17 NL/2014-15/23210,Bridges,Completed,NL-VALASARAVAKKAM,150,2987000,"STRENGTHNING AND RELAYING OF BT ROAD AT THUNDALAM ERIKARAI STREET (PERUMAL KOIL STREET) STREET IN DIV -150, U - 34 ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23212,Roads,Completed,NL-VALASARAVAKKAM,150,2992000,"STRENGTHING AND RELAYING OF BT ROAD AT ARUNACHALAM NAGAR 1ST STREET AND VISWANATHAN NAGAR MAIN ROAD STREET IN DIV - 150, U - 34 ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23214,Roads,Completed,NL-VALASARAVAKKAM,150,2427000,"STRENGTHING AND RELAYING OF BT ROAD AT KAVERI NAGAR 1ST STREET, ARUNACHALAM NAGAR BHARATHI SALAI AND ARUNACHALAM NAGAR 7TH STREET IN DIV - 150, U - 34, ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23215,Roads,Completed,NL-VALASARAVAKKAM,150,2987000,"STRENGTHING AND RELAYING OF BT AT KAVERI NAGAR MAIN ROAD, PONNI NAGAR BHARATHI SALAI AND CROSS STREET, AND RAJESWARI NAGAR MAIN ROAD IN DIV - 150, U - 34, ZONE - 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23217,Roads,Completed,NL-VALASARAVAKKAM,150,2895000,"STRENGTHING AND RELAYING OF BT ROAD AT APPADURAI PILLAI STREET AND MAHARISHI TEACHERS COLONY IN DIV - 150, U - 34, ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23319,Roads,Completed,NL-VALASARAVAKKAM,150,2395000,"STRENGTHING AND RELAYING BT ROAD AT KARAMBAKKAM SCHOOL STREET, DEVI NAGAR PILLIYAR KOIL STREET, ARUNACHALAM THOTTAM MAIN ROAD AND PONNI NAGAR MAHAVEER AND CROSS STREET IN DIV - 150, U - 34, ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23527,Roads,Completed,NL-VALASARAVAKKAM,150,938000,"LAYING CC ROAD AT PONNI NAGAR SENGUTTUVAN CROSS STREET, MANTHAVELI CROSS STREET AND KARAMBAKKAM 2ND CROSS STREET IN DIV - 150, U - 34, ZONE - 11",Loans And Grants,11,2014-15,2016-17 NL/2014-15/27154,Roads,Completed,NL-VALASARAVAKKAM,150,120000,"MAINTAINCE AND IMPROVEMENT WORK AT GANDHI NAGAR PC IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2014-15,2017-18 NL/2014-15/18268,Roads,Completed,NL-VALASARAVAKKAM,151,460000,"PROVIDING GSB AND WMM PATCH WORK AT CHINNA PORUR HOSPITAL ROAD, POOTHABEDU SCHOOL ROAD AND SENTHIAL NAGAR 5TH CROSS STREET IN DN: 151, U 34 Z 11.",Own Sources,11,2014-15,2018-19 NL/2014-15/22997,Roads,Completed,NL-VALASARAVAKKAM,151,2640000,"LAYING CEMENT CONCREATE ROAD USING M20 CONCREATE AT RAJAGOPAL STREET,BADRACHALAM ST,IRULAR COLONY,NETHAJI NAGAR 1ST,2ND,3RD, STREET IN DN 151 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23667,Roads,Completed,NL-VALASARAVAKKAM,151,2130000,"LAYING CEMENT CONCREATE ROAD USING M20 CONCREATE AT KUYAPETTAI 1ST STREET,RAMAKRISHNA NAGAR 1ST ST,PILLAIYAR KOIL LANE,NETHAJI NAGAR 4TH,5TH, STREET IN DN 151 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23668,Roads,Completed,NL-VALASARAVAKKAM,151,1962000,"LAYING CEMENT CONCREATE ROAD USING M20 CONCREATE AT KUYAPETTAI 2ND STREET,KAMALA NAGAR LANE, LANE,JAWAHAR NAGAR LANE,LAKSHMI NAGAR 40'FEET ROAD LANE,SENTHIL NAGAR 6TH CROSS STREET,VENKATESWARA ANNEXE,LAKSHMI NAGAR 8TH STREET LANE, IN DN 151 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23669,Roads,Completed,NL-VALASARAVAKKAM,151,3939000,STRENGTHENING AND LAYING OF BT ROAD AT POOTHABEDU SCHOOL ROAD IN DN 151 U 34 Z 11.,Loans And Grants,11,2014-15,2016-17 NL/2014-15/23670,Roads,Completed,NL-VALASARAVAKKAM,151,1894000,"STRENGTHENING AND LAYING OF BT ROAD AT HOSPITAL ROAD, SENTHIL NAGAR 5TH CROSS STREET IN DN 151 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23671,Roads,Completed,NL-VALASARAVAKKAM,151,3268000,"STRENGTHENING AND LAYING OF BT ROAD AT SABARI NAGAR 2ND MAIN ROAD, IN DN 151 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23672,Roads,Completed,NL-VALASARAVAKKAM,151,1571000,"STRENGTHENING AND LAYING OF BT ROAD AT SABARI NAGAR 1ST CROSS STREET,THIRUVALLUVAR STREET, IN DN 151 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/1388,Footpath,Completed,NL-VALASARAVAKKAM,152,667000,Providing Electrical arrangments and improvements works at zonal office 1 floor arcot road in div 152 unit 33 zone11,Own Sources,11,2014-15,2016-17 NL/2014-15/21964,Buildings,Completed,NL-VALASARAVAKKAM,152,660000,Construction of Ramp to Disable Person at Foot path in Various Streets in Dn-152 U-33 Z-11,Own Sources,11,2014-15,2016-17 NL/2014-15/25853,Buildings,Completed,NL-VALASARAVAKKAM,152,486000,Additional improvements works to new amma unavagam at thiruvalluvar salai div152 unit33 zone11,Own Sources,11,2014-15,2016-17 NL/2014-15/3863,Parks,Completed,NL-VALASARAVAKKAM,152,999000,"Improvement to Greenery arrangements and Electical Items at Chowdry Nagar playground in Division 152, Unit 33, Zone XI",Own Sources,11,2014-15,2016-17 NL/2014-15/0439,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,2999000,"Improvements to the Exiting SWD By Raising The Side Wall And Covering With Precast Slab at Krishna Nagar Main Road, 1 st Street, 3rd Street, Duraisamy Nagar 3rd & 4th street. DN-153, U-34,ZONE-XI.",Own Sources,11,2014-15,2016-17 NL/2014-15/17811,Parks,Completed,NL-VALASARAVAKKAM,153,220000,"ANNUAL MAINTENANCE OF PARK AT RAMAKRISHNA NAGAR PARK IN DN.153,UNIT-34,ZONE-11.(BY EMPLOYED QUALIFIED HORTICULTURIST FOR ONE YEAR)",Own Sources,11,2014-15,2017-18 NL/2014-15/17814,Parks,Completed,NL-VALASARAVAKKAM,153,220000,"ANNUAL MAINTENANCE OF PARK AT RAMASAMY NAGAR PARK IN DN.153,UNIT-34,ZONE-11.(BY EMPLOYED QUALIFIED HORTICULTURIST FOR ONE YEAR)",Own Sources,11,2014-15,2017-18 NL/2014-15/23415,Roads,Completed,NL-VALASARAVAKKAM,153,2086000,STRENTHEING AND LAYING OF BT ROAD AT VANNIYAR STREET I DN 153 U 34 Z11.,Loans And Grants,11,2014-15,2016-17 NL/2014-15/23438,Roads,Completed,NL-VALASARAVAKKAM,153,2123000,"STRENGTHEING AND LAYING OF BT ROAD AT R.E.NAGAR 1ST,2ND STREET (WEST) IN DN153 U 34 Z11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23454,Roads,Completed,NL-VALASARAVAKKAM,153,2260000,"STRENGTHEING AND LAYING OF BT ROAD AT CHETTY STREET,PERUMAL KOIL ST, R.E.NAGAR 1ST STREET(EAST) IN DN 153 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23710,Roads,Completed,NL-VALASARAVAKKAM,153,2402000,"STRENGTHENING AND LAYING OF BT ROAD AT RAMAMOORTHY AVENQUE 1ST STREET,2ND STREET,RAMAMOORTHY AVENQUE LANE, KRISHNA NAGAR EXTN MAIN ROAD IN DN 153 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23740,Roads,Completed,NL-VALASARAVAKKAM,153,1586000,"STRENGTHENING AND LAYING OF BT ROAD AT CSI CHURCH ROAD (EAST),R.E.NAGAR 3RD STREET (WEST) DN 153 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23748,Roads,Completed,NL-VALASARAVAKKAM,153,2045000,"FORMING,STRENGTHENING AND LAYING OF BT ROAD AT PERUMAL KOIL 1ST ST,2ND STREET AND 2ST LANE,R.E.NAGAR 3RD STREET (EAST) DN 153 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23755,Roads,Completed,NL-VALASARAVAKKAM,153,1937000,"FORMING,STRENGTHENING AND LAYING OF BT ROAD AT SAKTHI NAGAR PLESANT AVENUE EXTN&GANASH AVENUE 10TH STREET PART,MANGALA NAGAR 10TH CROSS STREET 4TH LANE, DN 153 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23757,Roads,Completed,NL-VALASARAVAKKAM,153,2197000,"FORMING,STRENGTHENING AND LAYING OF BT ROAD AT GANESH AVENUE 1ST MAIN ROAD, DN 153 U 34 Z 11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23765,Roads,Completed,NL-VALASARAVAKKAM,153,2466000,"LAYING OF CEMENT CONCREATE ROAD USING M20 CONCREATE AT R.E.NAGAR 4TH STREET WEST .R.E.NAGAR LANE, ESWARAN KOIL BACK SIDE LANE, IN DN 153 U 34 Z11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/23768,Roads,Completed,NL-VALASARAVAKKAM,153,2084000,"LAYING OF CEMENT CONCREATE ROAD USING M20 CONCREATE AT PERUMAL KOIL CROSS STREET,ERRIKKARAI STREET,R.E.NAGAR 2ND STREET(EAST) IN DN 153 U 34 Z11.",Loans And Grants,11,2014-15,2016-17 NL/2014-15/18887,Buildings,Completed,NL-VALASARAVAKKAM,154,310000,"Building maintenance at division 154 in unit -34, zone -11",Own Sources,11,2014-15,2017-18 NL/2014-15/12820,Buildings,Completed,NL-VALASARAVAKKAM,155,400000,"Construction of Rain Water Harvesting in Unit-32, Unit-33 and Unit-34, Zone-XI.",Own Sources,11,2014-15,2017-18 NL/2014-15/12823,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,350000,"Supplying and Fixing Storm Water Drain Man hole Doors and Frames at Unit-32, Unit-33 and Unit 34, Zone-XI.",Own Sources,11,2014-15,2017-18 NL/2014-15/18881,Buildings,Completed,NL-VALASARAVAKKAM,155,310000,"Building maintainance at Division 155 in Unit-34, Zone-11",Own Sources,11,2014-15,2017-18 D/2014-15/27502,Storm Water Drain,Completed,D-Storm Water Drains,156,216758000,Construction of Integrated Storm Water Drains in Manapakkam Water Shed of Adyar Basin in Extended areas of Chennai Corporation - Package 34,Loans And Grants,12,2014-15,2019-20 D/2014-15/27896,Storm Water Drain,Completed,D-Storm Water Drains,156,275862000,Construction of Integrated Storm Water Drains in Nandambakkam Water Shed of Adyar Basin in Extended areas of Chennai Corporation - Package 35,Loans And Grants,12,2014-15,2018-19 D/2014-15/27912,Storm Water Drain,Completed,D-Storm Water Drains,156,307405000,Construction of integrated Storm Water drains in Nandambakkam Water Shed of Adyar Basin in Extended areas in Chennai Corporation - Package 36,Loans And Grants,12,2014-15,2019-20 D/2014-15/27918,Storm Water Drain,Completed,D-Storm Water Drains,156,363834000,Construction of Integrated Storm Water Drain in Nandambakkam Water Shed of Adyar Basin in Extended area of Chennai Corporation - Package 37,Loans And Grants,12,2014-15,2018-19 D/2014-15/27937,Storm Water Drain,Completed,D-Storm Water Drains,156,325630000,Construction of Integrated Storm Water Drain in Adyar Water Shed of Adyar Basin in Extended areas of Chennai Corporation - Package 31,Loans And Grants,12,2014-15,2019-20 NM/2014-15/17037,Road Cut,Completed,NM-ALANDUR,156,422000,"ROAD CUT RESTORATION AT SABRI NAGAR 1st main Road, AGS COLONY MAIN ROAD,SUBHASHREE NAGAR 4TH EXTNSTREET DN-156,U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/18462,Buildings,Completed,NM-ALANDUR,156,900000,"IMPROVEMENT THE COMMUNITY HALL BUILDING AT SELVALAKSHMI GARDEN AT MUGALIVAKKAM IN DN-156,U-35,Z-XII",Own Sources,12,2014-15,2017-18 NM/2014-15/19283,Parks,Completed,NM-ALANDUR,156,270000,"ANNUAL MAINTENANCE OF PARK AT GURUSAMY NAGAR, DEVADOSS STREET ,NETHAJI STREET PARK IN DN.156,UNIT-35,ZONE-12 (qualified horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/19285,Parks,Completed,NM-ALANDUR,156,290000,"ANNUAL MAINTENANCE OF PARK AT VND RAJESWARI AVENUE, SINDHU STREET, PARK IN DN.156,UNIT-35,ZONE-12 (qualified horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/19286,Parks,Completed,NM-ALANDUR,156,275000,"ANNUAL MAINTENANCE OF PARK AT MADHA NAGAR, 2nd STREET PARK IN DN.156,UNIT-35,ZONE-12 (qualified horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/19291,Parks,Completed,NM-ALANDUR,156,345000,"Annual Maintenance of Park for CRR Puram Park at Manapakkam and Muglivakkam Link road in Dn.156,Unit-35,Zone-12(by Employed Qualified Horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/19292,Parks,Completed,NM-ALANDUR,156,344000,"Annual Maintenance of Park at AGS Colony Park Phase-III in Dn.156,Unit-35,Zone-12(by Employed Qualified Horticulturist for one year only)",Own Sources,12,2014-15,2016-17 NM/2014-15/19293,Parks,Completed,NM-ALANDUR,156,310000,"ANNUAL MAINTENANCE OF PARK AT KUMUTHAM NAGAR 2nd STREET PARK IN DN.156,UNIT-35,ZONE-12((by Employed Qualified Horticulturist one year only)",Own Sources,12,2014-15,2016-17 NM/2014-15/20150,Buildings,Completed,NM-ALANDUR,156,176000,"LAYING INTERLOCKING BLOCK AT COMMUNITY HALL BUILDING AT SELVALAKSHMI GARDEN AT MUGALIVAKKAM IN DN-156,U-35,Z-XII",Own Sources,12,2014-15,2017-18 L/2014-15/29748,Electrical,Completed,L-Electrical,157,4895200,"ERECTION OF 5NOS OF 9MRT GI LAMP WITH DOUBLE ARCH BRACKET AND LAYING OF 1470 MTR OF 4X16SQMM CABLE CONVERTION OF 31NOS DOUBLE STRAIGHT BRACKET INTO ARCH DOUBLE BRACKETS WITH 150-165W LED AT MOUNT POONAMALEESALAI FROM I D P L TO TRADECENTRE - 158,ZONE-12. (City Infrastructure and Beautification work for G.I.M 2015)",Own Sources,12,2014-15,2016-17 L/2014-15/29756,Electrical,Completed,L-Electrical,157,3686100,"ERECTION OF 5NOS OF 9MRT GI LAMP WITH DOUBLE ARCH BRACKET AND LAYING OF 980 MTR OF 4X16SQMM CABLE CONVERTION OF 31NOS DOUBLE STRAIGHT BRACKET INTO ARCH DOUBLE BRACKETS WITH 150-165W LED AT MOUNT POONAMALEESALAI FROM DLF TO L&T - 157,ZONE-12. (City Infrastructure and Beautification work for G.I.M 2015)",Own Sources,12,2014-15,2016-17 NM/2014-15/1150,Storm Water Drain,Completed,NM-ALANDUR,157,999000,"Improvement to the Existing SWD of Side Drain at Dr.Ambedkar Nagar River View Enclave 1st MainRoad (East Side) in Division-157, Unit-35, Zone-12",Own Sources,12,2014-15,2016-17 NM/2014-15/12161,Storm Water Drain,Completed,NM-ALANDUR,157,998998,"Construction of Side Drain at Kamaraj salai crosss street In Division -157, Unit-35, Zone-12",Own Sources,12,2014-15,2016-17 NM/2014-15/21307,Parks,Completed,NM-ALANDUR,157,244000,"Annual Maintenance of Park at River view colony Phase-I Park in Dn.157,Unit-35,Zone-12 (by Employed Qualified Horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/21308,Parks,Completed,NM-ALANDUR,157,280000,"Annual Maintenance of Park at River view colony Phase-II Park in Dn.157,Unit-35,Zone-12 (by Employed Qualified Horticulturist for one year only)",Own Sources,12,2014-15,2016-17 NM/2014-15/21309,Parks,Completed,NM-ALANDUR,157,235000,"Annual Maintenance of Park at Kaviya garden Park in Dn.157,Unit-35,Zone-12 (by Employed Qualified Horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/21310,Parks,Completed,NM-ALANDUR,157,240000,"Annual Maintenance of Park at Bell nagar Park in Dn.157,Unit-35,Zone-12 (by Employed Qualified Horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/21311,Parks,Completed,NM-ALANDUR,157,240000,"Annual Maintenance of Park at Macro marval Park in Dn.157,Unit-35,Zone-12 (by Employed Qualified Horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/11481,Parks,Completed,NM-ALANDUR,158,997000,"IMPROVEMENT TO ROAD SIDE PARK WITH STAINLESS STEEL CHILDRENS PLAY APPARATUS AND WATER ARRANGEMENT IN DN 158, U 35, ZONE 12.",Own Sources,12,2014-15,2018-19 NM/2014-15/13724,Parks,Completed,NM-ALANDUR,158,496000,"FORMING FOOTPATH AND PLANTATIONS FOR ROAD SIDE PARK AT WEST MADA STREET IN DN 158, U 35, ZONE 12.",Own Sources,12,2014-15,2017-18 NM/2014-15/13727,Parks,Completed,NM-ALANDUR,158,396000,"FORMING FOOTPATH AND PLANTATIONS FOR ROAD SIDE PARK AT ARCOTPET STREET IN DN 158, U 35, ZONE 12.",Own Sources,12,2014-15,2017-18 NM/2014-15/13729,Buildings,Completed,NM-ALANDUR,158,677000,"CONSTRUCTION OF COMPOUND WALL FOR ROAD SIDE PARK AT ARCOTPET STREET IN DN 158, U 35, ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/14931,Buildings,Completed,NM-ALANDUR,158,148000,"Improvements work to division office at Bajanai Koil street in Dn-158, Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/14933,Buildings,Completed,NM-ALANDUR,158,48000,"Improvements work tocAmma Unavagam at Bajanai Koil street in Dn-158, Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17818,Road Cut,Completed,NM-ALANDUR,158,987000,"Road cut restoration at Bajanai Koil street,West lake view street,Easwaran koil street,North mada street,Swamy colony street,Arcotpet street in Dn-158.U-35,Zn-12",Deposit Works,12,2014-15,2016-17 NM/2014-15/17952,Buildings,Completed,NM-ALANDUR,158,294000,"Additional improvements works to Division buildings in Dn-158,Unit-35,Zn-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/23719,Parks,Completed,NM-ALANDUR,158,210000,"Annual Maintenance of Park at Sunder nagar in Dn.158,Unit-36,Zone-12.(by qualified horticulturist for one year).",Own Sources,12,2014-15,2016-17 NM/2014-15/24378,Roads,Completed,NM-ALANDUR,158,999000,"Relaying and Strengthening BT road by using Paver Finisher at Sundar Nagar 2nd Avenue in Dn-158, U-35, Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24399,Roads,Completed,NM-ALANDUR,158,298000,"Relaying and Strengthening BT road by using Paver Finisher at Subedhar Dhottam Main Road in Dn-158, U-35, Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24414,Roads,Completed,NM-ALANDUR,158,492000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Ambetkar Street in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24417,Roads,Completed,NM-ALANDUR,158,626000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Koothalamman koil 1st lane in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24419,Roads,Completed,NM-ALANDUR,158,215000,"Relaying and Strengthening CC roaad by using RMC 30 grade atsubedhar thottem lane Street in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24428,Roads,Completed,NM-ALANDUR,158,128000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Nandambakkam colony 3rd cross Street in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24429,Roads,Completed,NM-ALANDUR,158,145000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Nandambakkam colony 2nd cross Street in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24430,Roads,Completed,NM-ALANDUR,158,145000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Nandambakkam colony 1st cross Street in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24431,Roads,Completed,NM-ALANDUR,158,487000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Nandambakkam colony Street in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/24433,Roads,Completed,NM-ALANDUR,158,191000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Ganapathypuram colony 8th Street in Dn-158,Unit-35,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/28838,Storm Water Drain,Completed,NM-ALANDUR,158,805000,"Improvements to existing storm water drain at Sundar Nagar 1st Avenue east side in Din-158, Unit-35, Zone-12",Own Sources,12,2014-15,2016-17 NM/2014-15/28839,Storm Water Drain,Completed,NM-ALANDUR,158,805000,"Improvements to existing storm water drain at Sundar Nagar 1st Avenue west side in Din-158, Unit-35, Zone-12",Own Sources,12,2014-15,2016-17 NM/2014-15/28840,Storm Water Drain,Completed,NM-ALANDUR,158,760000,"Improvements to existing storm water drain at Sundar Nagar 4th Avenue east side in Din-158, Unit-35, Zone-12",Own Sources,12,2014-15,2016-17 NM/2014-15/28842,Storm Water Drain,Completed,NM-ALANDUR,158,744000,"Improvements to existing storm water drain at Sundar Nagar 1st cross street in Din-158, Unit-35, Zone-12",Own Sources,12,2014-15,2016-17 NM/2014-15/28843,Storm Water Drain,Completed,NM-ALANDUR,158,989000,"Improvements to existing storm water drain at Sundar Nagar 2nd cross street in Din-158, Unit-35, Zone-12",Own Sources,12,2014-15,2017-18 NM/2014-15/28844,Storm Water Drain,Completed,NM-ALANDUR,158,547000,"Improvements to existing storm water drain at Sundar Nagar 3rd cross street in Din-158, Unit-35, Zone-12",Own Sources,12,2014-15,2016-17 NM/2014-15/28845,Storm Water Drain,Completed,NM-ALANDUR,158,713000,"Improvements to existing storm water drain at Sundar Nagar 4th cross street in Din-158, Unit-35, Zone-12",Own Sources,12,2014-15,2017-18 NM/2014-15/30856,Roads,Completed,NM-ALANDUR,158,1316000,"Relaying and Strengthening BT road by using Paver Finisher at Sundar Nagar 4th Avenue in Dn-158, U-35, Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/30857,Roads,Completed,NM-ALANDUR,158,816000,"Relaying and Strengthening BT road by using Paver Finisher at Sundar Nagar 2nd cross street in Dn-158, U-35, Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/30858,Roads,Completed,NM-ALANDUR,158,698000,"Relaying and Strengthening BT road by using Paver Finisher at Sundar Nagar 3rd cross street in Dn-158, U-35, Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/30859,Roads,Completed,NM-ALANDUR,158,775000,"Relaying and Strengthening BT road by using Paver Finisher at Sundar Nagar 7th cross street in Dn-158, U-35, Zn-12",Own Sources,12,2014-15,2016-17 L/2014-15/29718,Electrical,Completed,L-Electrical,159,1642400,"Laying of 1862 Mtr 4x16 Sqmm cable in the place of deteriorated cable in G.S.T Road from Meenambakkam Airport V.I.P Gate to Tirisulum in Div 159, Zone XII. (City Infrastructure and Beautification work for G.I.M 2015) . Schedule of rates(2014-15)",Own Sources,12,2014-15,2016-17 L/2014-15/29727,Electrical,Completed,L-Electrical,159,74200,"Removal of 37 Nos of 9.5Mtr.Post with Double Arch bracket, GST Road from International Cargo section to Meenambakkam overbridge due to Metro Rail project (Deposit work), Zone XII (City Infrastructure and Beautification work for G.I.M 2015)-Deposit work",Deposit Works,12,2014-15,2016-17 L/2014-15/29782,Electrical,Completed,L-Electrical,159,1757900,Erection of 30 nos of 8mtr Octagonal lamp posts with single straight bracket and 250 watts SV fittings at G.S.T Road from International cargo office to Meenambakkam over bridge North side due to Metro rail project in division 159 in zone XII. (City Infrastructure and Beautification work for G.I.M 2015)-Deposit work,Deposit Works,12,2014-15,2016-17 NM/2014-15/17778,Roads,Completed,NM-ALANDUR,159,1549000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT ANNA STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17779,Roads,Completed,NM-ALANDUR,159,1884000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT BHARATHIYAR STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17780,Roads,Completed,NM-ALANDUR,159,2328000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT THIRUVALLUVAR STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17781,Roads,Completed,NM-ALANDUR,159,820000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT KUMARAN STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17782,Roads,Completed,NM-ALANDUR,159,1200000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT T.V.K STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17783,Roads,Completed,NM-ALANDUR,159,2758000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT KAMARAJ STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17784,Roads,Completed,NM-ALANDUR,159,1533000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT DR.AMBEDHKAR STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17785,Roads,Completed,NM-ALANDUR,159,755000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT DR.AMBEDHKAR 3RD CROSS STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17786,Roads,Completed,NM-ALANDUR,159,534000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT RAJIVGANDHI STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17787,Roads,Completed,NM-ALANDUR,159,2625000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT VOC STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17788,Roads,Completed,NM-ALANDUR,159,1503000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT EVR STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17789,Roads,Completed,NM-ALANDUR,159,183000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT DR.AMBEDHKAR 1ST CROSS STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17790,Roads,Completed,NM-ALANDUR,159,1092000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT PANDIAN STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17791,Roads,Completed,NM-ALANDUR,159,1225000,"LAYING CC ROAD BY USING RMC GRADE M-30 CONCRETE AT AVVAIYAR STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/17792,Roads,Completed,NM-ALANDUR,159,450000,"LAYING CC ROAD BY USING RMC GRADE M-40 CONCRETE AT DR.AMBEDHKAR 2ND CROSS STREET IN DN-159, U-35,ZONE-12",Own Sources,12,2014-15,2016-17 L/2014-15/29728,Electrical,Completed,L-Electrical,160,1987500,"Erection of 8 Nos of 8m Octagonal lamp post, Laying of 1342 Mtr 4x16 Sqmm cable in the place of deteriorated cable in Porur Vadapalani service road and Vadapalani-Guindy Service Road in Kathipara Bridge, painting of lamp posts in Kathipara Bridge and G.S.T Road, in Div 160, Zone XII. (City Infrastructure and Beautification work for G.I.M 2015)",Own Sources,12,2014-15,2016-17 NM/2014-15/10643,Buildings,Completed,NM-ALANDUR,160,948000,Construction of Amma Unavagam at M.K.N Road in Dn:160 Unit:36 Zone:12,Own Sources,12,2014-15,2017-18 NM/2014-15/10648,Buildings,Completed,NM-ALANDUR,160,958000,Additional Improvements work to Amma Unavagam at M.K.N Road in Dn:160 Unit:36 Zone:12,Own Sources,12,2014-15,2017-18 NM/2014-15/11078,Buildings,Completed,NM-ALANDUR,160,955000,"Improvement to the Zonel Office buliding (ground floor) at New street in Dn-160, U-35, Zone-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11152,Buildings,Completed,NM-ALANDUR,160,814001,"Improvement to the Zonel Office buliding (ground floor& 1st floor toilet) at New street in Dn-160, U-35, Zone-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11663,Roads,Completed,NM-ALANDUR,160,679000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT VEMBULISUBEDHAR STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2017-18 NM/2014-15/11664,Roads,Completed,NM-ALANDUR,160,386000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT LAWYER JEGANATHAN STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11665,Roads,Completed,NM-ALANDUR,160,176000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT U.V.SAMYNATHAN STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11666,Roads,Completed,NM-ALANDUR,160,153000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT DHADIKARASAMY KOIL STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11668,Roads,Completed,NM-ALANDUR,160,290000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT JALL STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2017-18 NM/2014-15/11671,Roads,Completed,NM-ALANDUR,160,525000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT ASHAR KHANA STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11672,Roads,Completed,NM-ALANDUR,160,237000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT GURUBOX STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11674,Roads,Completed,NM-ALANDUR,160,197000,"SUPPLYING AND PAVING THE INTERLOCKING IN PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT IBRAHIM STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/11675,Roads,Completed,NM-ALANDUR,160,119000,"SUPPLYING AND PAVING THE INTERLOCKING PAVER BLOCK AT EXISTING PAVEMENT SHOULDERS (BOTH SIDES) AT PANDU BEEMAN STREET DN-160.U-35,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/16263,Storm Water Drain,Completed,NM-ALANDUR,160,249000,"IMPROVEMENT TO SWD AT DHADIKARASAMY CROOS STREET DN-160,U-35,ZONE-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/16267,Storm Water Drain,Completed,NM-ALANDUR,160,379000,"IMPROVEMENT TO SWD AT PERIYAPALAYATHAMAN STREET DN-160,U-35,ZONE-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/16269,Storm Water Drain,Completed,NM-ALANDUR,160,334000,"IMPROVEMENT TO SWD PACHAIAMMAN KOIL STREET DN-160,U-35,ZONE-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/16276,Road Cut,Completed,NM-ALANDUR,160,187000,"IMPROVEMENT TO SWD AT LUSKER STREET DN-160,U-35,ZONE-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/18149,Buildings,Completed,NM-ALANDUR,160,680000,"Providing Rental Modular Toilets (2 Units) on Contract basis and Maintenance for one year Near West mada street in dn 158.G.S.T Road in front of Buriyal grount in dn 159.MKN Road Near EB office in DN 160,UNIT 35,ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/23627,Parks,Completed,NM-ALANDUR,160,237000,"Annual Maintenance of Park at New street Park in Dn.160,Unit-35,Zone-12 (by Employed Qualified Horticulturist only)",Own Sources,12,2014-15,2016-17 NM/2014-15/25692,Roads,Completed,NM-ALANDUR,160,1406000,Relaying and Strengthening of CC Road by using RMC M-30 At luskar cross street in Div-160 Unit -35 Zone -12,Own Sources,12,2014-15,2016-17 NM/2014-15/31994,Roads,Completed,NM-ALANDUR,160,702000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DIV 160,UNIT 35,ZONE 12.",Own Sources,12,2014-15,2017-18 NM/2014-15/11980,Roads,Completed,NM-ALANDUR,161,98000,PROVIDAING LAYING OF PAVER BLOCK AT THIRUVALLUVAR STREET 2nd LANE DN161 UN36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/11982,Roads,Completed,NM-ALANDUR,161,167547,PROVIDING AND LAYING OF PAVER BLOCK AT TNGO COLONY1s street DN161 UN36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/11989,Roads,Completed,NM-ALANDUR,161,155000,PROVIDAING LAYING OF PAVER BLOCK AT GDDDSHED ROAD 4th STREET DN161 UN36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/11992,Roads,Completed,NM-ALANDUR,161,51000,PROVIDAING LAYING OF PAVER BLOCK AT TNGO COLONI 1st CROSS STREET DN161 UN36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/11993,Roads,Completed,NM-ALANDUR,161,51000,PROVIDAING LAYING OF PAVER BLOCK AT LAYAS AVANUE 2nd STREET DN161 UN36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/11995,Roads,Completed,NM-ALANDUR,161,124604,PROVIDING LAYING OF PAVER BLOCK AT SANJAY GANDHI NAGAR 1ST STREET DN161 UN36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/12194,Roads,Completed,NM-ALANDUR,161,332000,PROVIDING AND LAYING PAVER BLOCKS AT JEEVAN NAGAR 4TH STREET IN DN 161 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/12200,Roads,Completed,NM-ALANDUR,161,411000,PROVEDING LAYING PAVER BLOCK AT MUTHAIAL STREET IN DN 161 U 36 Z 12,Own Sources,12,2014-15,2016-17 NM/2014-15/12201,Roads,Completed,NM-ALANDUR,161,411000,PROVEDING LAYER PAVER BLOCK AT MUTHIAL STREET 2 ND LANE IN D161 U36 Z12,Thanniraivu Thittam,12,2014-15,2016-17 NM/2014-15/12270,Roads,Completed,NM-ALANDUR,161,67000,PROVEDING LAYING PAVER BLACK AT M K N ROAD 2ND LANE IN DN 161 U36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/12273,Roads,Completed,NM-ALANDUR,161,243000,PROVEDING LAYING PAVER BLACK AT MANDI STREET IN DN161 U36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/12276,Footpath,Completed,NM-ALANDUR,161,336000,PROVIDING AND LAYING OF PAVER BLOCKS AT DANIYAL STREET IN DN 161 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/12277,Footpath,Completed,NM-ALANDUR,161,336000,PROVIDING AND LAYING OF PAVER BLOCKS AT ABHAGRAM STREET IN DN 161 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/12379,Storm Water Drain,Completed,NM-ALANDUR,161,660000,"constrcetion of side drain at good shed road in dn 161 u36, z12",Own Sources,12,2014-15,2016-17 NM/2014-15/12433,Parks,Completed,NM-ALANDUR,161,315000,ANNUAL MAINTENANCE PARK AT OFFICERS COLONY 1ST STREET PARK IN DN 161 UN 36 Z 12,Own Sources,12,2014-15,2017-18 NM/2014-15/12436,Parks,Completed,NM-ALANDUR,161,293000,ANNUAL MAINTENANCE PARK AT TN-GO COLONY 1ST STREET PARK IN DN 161 UN 36 Z 12,Own Sources,12,2014-15,2018-19 NM/2014-15/13737,Buildings,Completed,NM-ALANDUR,161,1361000,"PROPOSED CONSTRUCTION OF PUBLIC CONVENIENCE (4+4) seated AT V.O.C NAGAR IN DN-161,U-36,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/13857,Parks,Completed,NM-ALANDUR,161,215000,"Maintenance of Park at Jeevan nagar Park in Dn.161,Unit-36,Zone-12 (by Employed Qualified Horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/14808,Roads,Completed,NM-ALANDUR,161,264000,Laying M40 Concrete at Raja street in Dn:161 Unit:36 Zone:12,Own Sources,12,2014-15,2016-17 NM/2014-15/16461,Storm Water Drain,Completed,NM-ALANDUR,161,485000,"Improvement of storm water drain at Jeevan nagar 3rd Street south side in Dn-161,U-36,Zn-12",Own Sources,12,2014-15,2016-17 NM/2014-15/19053,Parks,Completed,NM-ALANDUR,161,227000,ANNUAL MAINTENANCE PARK AT OFFICERS COLONY 1ST STREET PARK IN DN 161 U 36 Z 12(by Employed Qualified Horticulturist for one year),Own Sources,12,2014-15,2016-17 NM/2014-15/21130,Parks,Completed,NM-ALANDUR,161,196000,ANNUAL MAINTENANCE PARK AT MURUGAN NAGAR PARK IN DN 161 U 36 Z 12(by Employed Qualified Horticulturist for one year),Own Sources,12,2014-15,2016-17 NM/2014-15/22305,Roads,Completed,NM-ALANDUR,161,647000,LAYING CC ROAD RMC M30 AT JEEVAN NAGAR 1 ST CROSS STREET IN DN 161 U 36 Z12,Own Sources,12,2014-15,2016-17 NM/2014-15/22312,Roads,Completed,NM-ALANDUR,161,660000,"LAYING CC ROAD RMC M30 AT JEEVAN NAGAR 1ST STREET LANES IN DN 161, U36, Z 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/24245,Electrical,Completed,NM-ALANDUR,161,2148000,"CONSTRUCTION OF GYM BUILDING WITH GYM EQUIPMENTS ( UNDER WARD COUNCILLOR FUND ) AT SOUTH RAJA STREET IN DIVISION-161, UNIT-36, ZONE-12",Own Sources,12,2014-15,2016-17 L/2014-15/29714,Electrical,Completed,L-Electrical,162,4320400,Supply and Laying of 5158 mtrs of 4 x 16 sqmm Alu cable and replacement of 9 no of 9 mtrs MS Lamp post with new GI Lamp posts at Inner Ring Road in Div - 165 and Div - 162 in zone XII. ( City Infrastructure and Beautification work for G.I.M 2015)Schedule of rates (2014-15),Own Sources,12,2014-15,2016-17 NM/2014-15/14359,Roads,Completed,NM-ALANDUR,162,925000,"RESTORATION OF ROAD CUT MADE BY TANTRANSCO (TNEB) FOR LAYING OF 110 KV,1X1000SQMM UG CABLE AT NOBLE STREET ( FROM PAZHAVANTHANGAL SUBWAY TO NOBLE 3RD STREET ) IN DIV-162,U-36,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/14461,Roads,Completed,NM-ALANDUR,162,925000,"RESTORATION OF ROAD CUT MADE BY TANTRANSCO (TNEB) FOR LAYING OF 110 KV,1X1000SQMM UG CABLE AT NOBLE STREET ( FROM NOBLE 3RD STREET TO G.S.T ROAD ) IN DIV-162,U-36,Z-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/16274,Playfields,Completed,NM-ALANDUR,162,440000,"Improvement of Gym Building at Pitchen street in Dvision162, Unit-36, Zone-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/19055,Parks,Completed,NM-ALANDUR,162,210000,"ANNUAL MAINTENANCE PARK AT THILLAI GANGA NAGAR 33th PARK ALANDUR IN DN 162,U-36 Z-12(by Employed Qualified Horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/19056,Roads,Completed,NM-ALANDUR,162,971000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/31106,Buildings,Completed,NM-ALANDUR,162,450000,"Providing Rental Modular Toilets (2 Units) on Contract basis and Maintenance for one year at Thillai Ganga Nagar 1st main road and Noble street in Dn.162, Unit-36, Zone XII.",Own Sources,12,2014-15,2016-17 NM/2014-15/6781,Buildings,Completed,NM-ALANDUR,162,258000,"Improvement works to Public convenience at Kannan colony main road in Division-162, Unit-36, Zone-12.(COUNCILAR FUND 2014-2015)",Own Sources,12,2014-15,2016-17 NM/2014-15/13464,Storm Water Drain,Completed,NM-ALANDUR,163,558000,CONSTRUCTION OF SIDE DRAIN AT BALAKRISHNAPURAM 6TH STREET IN DN 163 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/15043,Parks,Completed,NM-ALANDUR,163,988000,CONSTRUCTION OF COMPOUND WALL AND BADMINTON COURT AT SHANTHI NAGAR 4TH STREET 2PLAY FIELDS IN DN 163 Z.1,Own Sources,12,2014-15,2016-17 NM/2014-15/15044,Buildings,Completed,NM-ALANDUR,163,194000,WRITING NAME BOARD FOR CONSERVANCY WORKS IN VARIOUS STREET IN DN 163 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/15046,Storm Water Drain,Completed,NM-ALANDUR,163,970000,IMPROVEMENTS WORKS TO SIDE DRAIN AT BALAGANGATHERAN STREET IN DN 163 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/18148,Buildings,Completed,NM-ALANDUR,163,675000,"PROVIDING RENTAL MODULAR TOILETS ( 2 UNITS ) ON CONTRACT BASIS AND MAINTENANCE FOR ONE YEAR AT M.K.N.ROAD,MADAVAKKAM MAIN ROAD IN DN 161 AND BALAKRISHNAPURAM GASIFIER CEREMATORIAM IN DN 163 .Z.12",Own Sources,12,2014-15,2016-17 NM/2014-15/28858,Storm Water Drain,Completed,NM-ALANDUR,163,984000,IMPROVEMENTS WORKS TO SIDE DRAIN AT PALANDIAMMAN KOIL STREET IN DN 163 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/28920,Buildings,Completed,NM-ALANDUR,163,184000,PROVIDING RAMP FOR CORPORATION BUILDINGS AND PROVIDING BIN PLATFORM AT VARIOUS STREET IN DN 163 Z.12,Own Sources,12,2014-15,2016-17 NM/2014-15/14587,Buildings,Completed,NM-ALANDUR,164,340000,"WRITING OF NAME BOARD FOR CONSERVANCY WORK DETAILS IN VARIOUS STREETS IN DIV-164,UNIT-37,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/15759,Buildings,Completed,NM-ALANDUR,164,735000,"Improvement Works To Division Office Building at Krishnaswamy Steet in DN-164, UNIT-37, ZONE-12,",Own Sources,12,2014-15,2016-17 NM/2014-15/19057,Parks,Completed,NM-ALANDUR,164,219000,"ANNUAL MAINTENANCE PARK AT NEHRU STREET PARK IN DN 164,U-36 Z-12(by Employed Qualified Horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/19058,Parks,Completed,NM-ALANDUR,164,205000,"ANNUAL MAINTENANCE PARK AT NANGANALLUR 29th PARK IN DN 164,U-36 Z-12(by Employed Qualified Horticulturist for one year)",Own Sources,12,2014-15,2016-17 D/2014-15/27308,Storm Water Drain,Completed,D-Storm Water Drains,165,423797000,"Construction of Storm Water Drain in Extended areas of Chennai Corporation at Nandambakkam Water Shed, Adyar Basin _ Package 38",Loans And Grants,12,2014-15,2018-19 D/2014-15/27346,Storm Water Drain,Completed,D-Storm Water Drains,165,319911000,Construction of Integrated Storm Water Drains in Manapakkam Water Shed of Adyar Basin in Extended areas of Chennai Corporation - Package 33,Loans And Grants,12,2014-15,2018-19 NM/2014-15/18093,Buildings,Completed,NM-ALANDUR,165,680000,"Providing Rental Modular Toilets (2 Units) on Contract basis and Maintenance for one year Near Pazavanthangal Subway and Nanganallur 4th main road in Dn.164 and Vanuvampet Bus stop in Dn-165, Unit-37, Zone XII.",Own Sources,12,2014-15,2016-17 NM/2014-15/18494,Parks,Completed,NM-ALANDUR,165,210000,"ANNUAL MAINTENANCE OF PARK AT SURENDERA NAGAR PARK IN DN.165,UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/18495,Parks,Completed,NM-ALANDUR,165,307000,"ANNUAL MAINTENANCE OF PARK AT KUNDRAKUDI NAGAR PARK IN DN.165,UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/18496,Parks,Completed,NM-ALANDUR,165,205000,"ANNUAL MAINTENANCE OF PARK AT ADAMBAKKAM LAKSHMI NAGAR I street PARK IN DN.165,UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/18497,Parks,Completed,NM-ALANDUR,165,215000,"ANNUAL MAINTENANCE OF PARK AT BALAJI NAGAR PARK IN DN.165,UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2014-15,2016-17 NM/2014-15/25496,Roads,Completed,NM-ALANDUR,165,952000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/30783,Storm Water Drain,Completed,NM-ALANDUR,165,999000,"IMPROVEMENTS WORK TO SIDE DRAIN AT IN COME TAX COLONY MAIN ROAD WEST SIDE IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/30784,Storm Water Drain,Completed,NM-ALANDUR,165,995000,"IMPROVEMENTS WORK TO SIDE DRAIN AT IN COME TAX COLONY MAIN ROAD EAST SIDE IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/31466,Parks,Completed,NM-ALANDUR,165,638000,"ADDITIONAL IMPROVEMENT OF BHARATH NAGAR PARK WITH COMPOUND WALL, ENTRY GATE AND GREENARY IN DN 165, U-37, ZONE 12",Own Sources,12,2014-15,2016-17 NM/2014-15/4186,Storm Water Drain,Completed,NM-ALANDUR,165,282000,"IMPROVEMENTS WORK TO SIDE DRAIN AT VEL NAGAR 2ND STREET IN DN-165, U-37, ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/4187,Storm Water Drain,Completed,NM-ALANDUR,165,315000,"IMPROVEMENTS WORK TO SIDE DRAIN AT NILAMANGAI NAGAR - THILAKAR STREET IN DN-165, U-37, ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/4306,Storm Water Drain,Completed,NM-ALANDUR,165,379000,"IMPROVEMENTS WORK TO SIDE DRAIN AT BALAJI NAGAR 1ST STREET IN DN-165, U-37, ZONE-12.",Own Sources,12,2014-15,2016-17 NM/2014-15/13462,Storm Water Drain,Completed,NM-ALANDUR,166,601000,"IMPROVEMENT TO THE EXISTING SWD AT B.V.NAGAR 2ND CROSS STREET (SOUTH SIDE) IN DN-166,UNIT-37,ZONE-12",Own Sources,12,2014-15,2016-17 NM/2014-15/14580,Buildings,Completed,NM-ALANDUR,166,995000,Improvement works to GYM Building and Library Building at nehru nedunchalai in Dn:166 Unit:37 Zone:12,Own Sources,12,2014-15,2016-17 NM/2014-15/17728,Roads,Completed,NM-ALANDUR,166,989000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD USING M40 GRADE CONCRETE AT RAGHUPATHI NAGAR 1ST CROSS LANE,RAGHUPATHI NAGAR 2ND ST CROSS LANE AND RAGHUPATHI NAGAR 3RD STREET CROSS LANE IN DN:166 UNIT:37 ZONE:12",Own Sources,12,2014-15,2016-17 NM/2014-15/17832,Footpath,Completed,NM-ALANDUR,166,337000,LAYING INTERLOCKING PAVER BLOCK AT BV NAGAR 14TH STREET IN DN:166 UNIT:37 ZONE:12,Own Sources,12,2014-15,2017-18 NM/2014-15/17833,Footpath,Completed,NM-ALANDUR,166,92600,LAYING INTERLOCKING PAVER BLOCK AT BV NAGAR 15TH STREET IN DN:166 UNIT:37 ZONE:12,Own Sources,12,2014-15,2017-18 NM/2014-15/17837,Footpath,Completed,NM-ALANDUR,166,269000,LAYING INTERLOCKING PAVER BLOCK AT BV NAGAR 16TH STREET IN DN:166 UNIT:37 ZONE:12,Own Sources,12,2014-15,2017-18 NM/2014-15/18873,Parks,Completed,NM-ALANDUR,166,229000,"MAINTENANCE OF PARK AT GANDHI NAGAR ANNA PARK IN DN.166, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/21682,Buildings,Completed,NM-ALANDUR,166,2107000,"CONSTRUCTION OF NNMP SHED FOR CENTER NO 38 & 42 AT GOVINDASAMY STREET, DN 166, U 37, Z 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/7489,Footpath,Completed,NM-ALANDUR,166,547000,"PROVIDING FOOTPATH AT JAIN COLLEGE ROAD EXTENSION ( EAST SIDE ), IN DN 166, UNIT 37, ZONE 12",Own Sources,12,2014-15,2016-17 NM/2014-15/8181,Parks,Completed,NM-ALANDUR,166,990000,"IMPROVEMENTS TO THE PARK, AT ANNA STREET, IN DN 166, UNIT 37, ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/9518,Buildings,Completed,NM-ALANDUR,166,760000,"CONSTRUCTION OF VETERINARY CLINIC AT NEHRU NEDUNCHALAI, IN DN 166, UNIT 37, ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/15406,Parks,Completed,NM-ALANDUR,167,600000,"IMPROVEMENT TO THE EXISTING PARK AT HINDHU COLONY 26TH STREET IN DN -167,U - 37,ZONE 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/17422,Parks,Completed,NM-ALANDUR,167,215000,"MAINTENANCE OF PARK AT VOLTAS COLONY PARK I street IN DN.167, U -37, Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17424,Parks,Completed,NM-ALANDUR,167,213000,"MAINTENANCE OF PARK AT KANNIGA COLONY II street IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17426,Parks,Completed,NM-ALANDUR,167,210000,"MAINTENANCE OF PARK AT LAKSHMI NAGAR 4th Stage IN DN.167, U -37 , Z-12.(By qualified Horticulture only)period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17428,Parks,Completed,NM-ALANDUR,167,206000,"MAINTENANCE OF PARK AT KANNAN NAGAR I MAIN ROAD IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17429,Parks,Completed,NM-ALANDUR,167,210000,"MAINTENANCE OF PARK AT VIJAY AVENUE IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17430,Parks,Completed,NM-ALANDUR,167,210000,"MAINTENANCE OF PARK AT CIVILIATION SRI RAM COLONY IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17431,Parks,Completed,NM-ALANDUR,167,210000,"MAINTENANCE OF PARK AT HINDU COLONY 26th STREET IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17432,Parks,Completed,NM-ALANDUR,167,397000,"MAINTENANCE OF PARK AT INDEPENDENTS DAY PARK IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/17433,Parks,Completed,NM-ALANDUR,167,206000,"MAINTENANCE OF PARK AT LAKSHMI NAGAR 7th STREET PARK IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/18139,Buildings,Completed,NM-ALANDUR,167,675000,"Providing Rental Modular Toilets (2 Units) on Contract basis and Maintenance for one year at Indipendanceday park, Nanganallur Bus Depot and Lakshmi nagar 4th stage park in Dn.167, Unit-37, Zone XII.",Own Sources,12,2014-15,2016-17 NM/2014-15/18845,Parks,Completed,NM-ALANDUR,167,210000,"MAINTENANCE OF PARK AT MMTC Colony Eswaran st Park IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2014-15,2016-17 NM/2014-15/28421,Storm Water Drain,Completed,NM-ALANDUR,167,8867000,"CONSTRUCTION OF RCC STORM WATER DRAIN OF SIZE 600X750mm AT GRID III SAVINGS AT VOLTAS COLONY 50 FEET ROAD IN DN 167, U 37,Z 12.",Own Sources,12,2014-15,2016-17 NM/2014-15/8027,Buildings,Completed,NM-ALANDUR,167,900000,"CONSTRUCTION OF ROAD SIDE PARK AT 100 FEET ROAD NANGANALLUR (FROM LAKSHMI STREET TO NANGANALLUR 46TH STREET) IN DN 167,UNIT37,ZONE12",Own Sources,12,2014-15,2016-17 NM/2014-15/9572,Culvert,Completed,NM-ALANDUR,167,295000,"CONSTRUCTION OF CULVERT AT LAKSHMI NAGAR MAIN ROAD IN DN-167,UNIT-37,ZONE-12",Own Sources,12,2014-15,2016-17 L/2014-15/25562,Electrical,Completed,L-Electrical,168,177300,"NUMBERING OF 7045Nos OF EL,GI and MS POST IN DIVISION 168,169,183 TO 191",Own Sources,14,2014-15,2016-17 L/2014-15/4524,Electrical,Completed,L-Electrical,169,1830400,Conversion of 59 Nos. of 250W SVL fittings into 150w - 165w LED fittings (in place of 250w SVL) in Inner Ring Road in Div.169/ Zone-14.,Own Sources,14,2014-15,2016-17 NP/2014-15/22261,Roads,Completed,NP-PERUNGUDI,169,1207000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT AG's COLONY 1st STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22290,Roads,Completed,NP-PERUNGUDI,169,1207000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT AG's COLONY 2nd STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22296,Roads,Completed,NP-PERUNGUDI,169,1372000,"STRENGTHENING AN DLAYING OF BT ROAD WITH PAVER AT AG's COLONY 3rd STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22299,Roads,Completed,NP-PERUNGUDI,169,330000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT AG's COLONY 1ST Cr. STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22309,Roads,Completed,NP-PERUNGUDI,169,330000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT AG's COLONY 2nd Cr.STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22316,Roads,Completed,NP-PERUNGUDI,169,2158000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMASAMY STREET IN DN-169, UNIT-42,ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22319,Roads,Completed,NP-PERUNGUDI,169,3182000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER ATRAMNAGR 4tH STREET IN DN-169,UNIT-42,ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22321,Roads,Completed,NP-PERUNGUDI,169,3182000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMNAGR 5tH STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22323,Roads,Completed,NP-PERUNGUDI,169,3182000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMNAGAR 6th STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22324,Roads,Completed,NP-PERUNGUDI,169,4115000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMANAGR 7th STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22325,Roads,Completed,NP-PERUNGUDI,169,4115000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMNAGRA 8tH STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22327,Roads,Completed,NP-PERUNGUDI,169,4367000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMNAGAR 9th STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22329,Roads,Completed,NP-PERUNGUDI,169,3950000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMNAGAR 10th STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22331,Roads,Completed,NP-PERUNGUDI,169,4038000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMNAGAR 11th STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22332,Roads,Completed,NP-PERUNGUDI,169,2359000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT RAMNAGAR 12th STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22334,Roads,Completed,NP-PERUNGUDI,169,3621000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT VALLAL ADHIYAMAN STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22335,Roads,Completed,NP-PERUNGUDI,169,3676000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT VALLAL KUMANAN STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22336,Roads,Completed,NP-PERUNGUDI,169,2634000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT VALLAL KARI STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22338,Roads,Completed,NP-PERUNGUDI,169,2798000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT PADMAVATHY STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22339,Roads,Completed,NP-PERUNGUDI,169,2579000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT NAKEERAN STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22340,Roads,Completed,NP-PERUNGUDI,169,2579000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT BALAJI STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22341,Roads,Completed,NP-PERUNGUDI,169,659000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT THIRUMULA STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22343,Roads,Completed,NP-PERUNGUDI,169,2030000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT THIRUGANASAMBANDAR STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22345,Roads,Completed,NP-PERUNGUDI,169,3182000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT KAVIMANI STREET DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/27460,Storm Water Drain,Completed,NP-PERUNGUDI,169,993000,"IMPROVEMENTS TO SIDE DRAIN ALONG MURUGAPPAN STREET, FROM MURUGAPPAN STREET JUNCTION TO THILAK STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2014-15,2017-18 NP/2014-15/27467,Storm Water Drain,Completed,NP-PERUNGUDI,169,976000,"REPAIR AND IMPROVEMENTS SIDE DRAIN ALONG MURUGAPPAN STREET, FROM THILAK STREET TO RADHA NAGAR MAIN ROAD DN-169,UNIT-42,ZONE-14",Own Sources,14,2014-15,2017-18 NP/2014-15/27468,Storm Water Drain,Completed,NP-PERUNGUDI,169,970000,"REPAIR AND IMPROVEMENTS SIDE DRAIN ALONG MURUGAPPAN STREET FROM RADHA NAGAR MAIN ROAD TO BALAJI NAGAR MAIN ROAD DN-169,UNIT-42,ZONE-14",Own Sources,14,2014-15,2017-18 NN/2014-15/13139,Buildings,Completed,NN-ADYAR,170,980000,"IMPROVEMENT TO THE EXISTING BURIAL GROUND IN JOTHI NAGAR IN DIV - 170 , UNIT - 40 A, ZONE XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/18391,Buildings,Completed,NN-ADYAR,170,300000,"PROVIDING OPEN WELL TYPE RAIN WATER HARVESTING AT VARIOUS BUILDINGS IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/18603,Roads,Completed,NN-ADYAR,170,785000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT ARUL PRAKASAM STREET IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2014-15,2016-17 NN/2014-15/18624,Roads,Completed,NN-ADYAR,170,516000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT RAJAJI STREET IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2014-15,2016-17 NN/2014-15/18718,Roads,Completed,NN-ADYAR,170,1984000,"RAISING AND RELAYING THE B.T COURSE 50MM TK.BY USING PAVER FINISHER AT BALAJI NAGAR 1ST MAIN ROAD IN DN-170,U-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/20370,Roads,Completed,NN-ADYAR,170,910000,"RAISING AND RELAYING THE B.T COURSE TK BY USING PAVER FINISHER AT 33' FEET ROAD FROM CH(0 - 110) IN DN-170,U-40A,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/20371,Roads,Completed,NN-ADYAR,170,910000,"RAISING AND RELAYING THE B.T COURSE 50MM TK BY USING PAVER FINISHER AT 33 FEET ROAD FROM CH(110 - 220) IN DN-170,U-40A,Z-13",Own Sources,13,2014-15,2016-17 NN/2014-15/20434,Roads,Completed,NN-ADYAR,170,929000,"RAISING AND RELAYING THE B.T COURSE 50MM TK.BY USING PAVER FINISHER AT BARATHIYAR STREET IN DN-170,U-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/20544,Roads,Completed,NN-ADYAR,170,3275000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING PAVER FINISHER AT PUMPING STATION ROAD IN DIV-170,U-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21227,Roads,Completed,NN-ADYAR,170,381000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING PAVER FINISHER AT BALAJI NAGAR 5TH CROSS STREET IN DIV-170,U-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21280,Roads,Completed,NN-ADYAR,170,973000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING PAVER FINISHER AT ACHUDHAN NAGAR IV STREET -I CROSS STREET IN DIV-170,U-40A,ZONE13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21282,Roads,Completed,NN-ADYAR,170,578000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING PAVER FINISHER AT ACHUDHAN NAGAR II STREET-II CROSS STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21820,Roads,Completed,NN-ADYAR,170,681000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING PAVER FINISHER AT BALAJI NAGAR III CROSS STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21821,Roads,Completed,NN-ADYAR,170,319000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K. BY USING PAVER FINISHER AT BALAJI NAGAR VI CROSS STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21835,Roads,Completed,NN-ADYAR,170,2214000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING PAVER FINISHER AT KALAIMAGAL 2ND MAIN ROAD IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21837,Roads,Completed,NN-ADYAR,170,930000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING THE PAVER FINISHER AT ACHUTHAN NAGAR 1 STREET-II CROSS STREET IN DIV-170,UNIT-40A,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/21840,Roads,Completed,NN-ADYAR,170,534000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING THE PAVER FINISHER AT GANAPATHY NAGAR I STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21842,Roads,Completed,NN-ADYAR,170,528000,"RAISING AND RELAYING THE B.T COURSE 50MM T.K BY USING THE PAVER FINISHER AT GANDHI NAGAR EXTENSIONS IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/21847,Roads,Completed,NN-ADYAR,170,390000,"RAISING AND RELAYING THE B,T COURSE 50MM T.K BY USING THE PAVER FINISHER AT V.V KOIL STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24674,Roads,Completed,NN-ADYAR,170,1150000,"RAISING AND RELAYING THE B.T COURSES 50MM T.K BY USING THE PAVER FINISHER AT KABILAR STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24724,Roads,Completed,NN-ADYAR,170,1741000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE BY CHETTY THOTTAM SLUM WEST STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24726,Roads,Completed,NN-ADYAR,170,1741000,"RELAYING THE CONNCRETE ROAD WITH M30 GRADE ATJOTHI THOTTAM SLUM MAIN ROAD IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24728,Roads,Completed,NN-ADYAR,170,1369000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT JOTHI AMMAL NAGAR SLUM LANES IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24732,Roads,Completed,NN-ADYAR,170,344000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT CHETTY THOTTAM SLUM LANES IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24734,Roads,Completed,NN-ADYAR,170,725000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT NERUPPU MEDU SLUM LANES IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24738,Roads,Completed,NN-ADYAR,170,1337000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT NERUPPU MEDU SLUM MAIN ROAD IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24744,Roads,Completed,NN-ADYAR,170,1179000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT HOSPITAL ROAD 2ND LANES IN DIV-170,UNIT-40A,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24751,Roads,Completed,NN-ADYAR,170,1863000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT CHETTY THOTTAM MAIN ROAD IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24759,Roads,Completed,NN-ADYAR,170,959000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT JOTHY THOTTAM SLUM LANES IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25206,Roads,Completed,NN-ADYAR,170,434000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE AT THANDAVARAYAN STREET IN DIV-170,UNIT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/31972,Roads,Completed,NN-ADYAR,170,976000,"RAISING AND RELAYING THE B.T. COURSE 50MM TK. BY USING PAVER FINISHER AT V.V. KOIL STREET IN DN.- 170, U.-40(A), ZONE - 13",Own Sources,13,2014-15,2016-17 NN/2014-15/8324,Buildings,Completed,NN-ADYAR,170,990000,"PROVINDING ADDITIONAL TOILET AND EXTENSION OF MEDICAL STORAGE ROOM IN EXISTING HEALTH POST IN REDDY STREET IN DIVISION - 170 , UNIT 40 ( A ) , ZONE 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/9513,Buildings,Completed,NN-ADYAR,170,990000,"PROVIDING G.I DIRECTION NAME BOARD AND RETRO REFLECTIVE STREET NAME BOARD AT VARIOUS STREETS IN DN-170, UNIT-40(A), ZONE-13,",Own Sources,13,2014-15,2017-18 BR/2014-15/17410,Roads,Completed,BR-Bus Route Roads,171,26674000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Taluk Office Road from the junction of Anna Salai to Sardar Patel Road Dn-171, Zone - 13",Grants,13,2014-15,2016-17 BR/2014-15/29699,Roads,Completed,BR-Bus Route Roads,171,69649000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Gandhi Mandapam Road from the junction of sardar patel road to the junction of River View Road in Dn-171 & 172, Zone-XIII",Grants,13,2014-15,2016-17 BR/2014-15/29922,Roads,Completed,BR-Bus Route Roads,171,755000,"Attending Patch Work Gandhi Mandapam Fly Over at Sardar Patel Road in Dn 171 & 172, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/26486,Roads,Completed,NN-ADYAR,171,499000,"Name of Work: RELAYING THE ROAD WITH BT SURFACE WITH CAMBER CORRECTION USING PAVER FINISHER AT MODEL HUTMENT ROAD EXTN.",Own Sources,13,2014-15,2016-17 NN/2014-15/26500,Roads,Completed,NN-ADYAR,171,402000,"Name of Work: RELAYING THE ROAD WITH BT SURFACE WITH CAMBER CORRECTION USING PAVER FINISHER AT RANGARAJAPURAM CROSS STREET",Own Sources,13,2014-15,2016-17 NN/2014-15/26548,Roads,Completed,NN-ADYAR,171,1799000,"RELAYING THE ROAD WITH B.T. SURFACE WITH CAMBER CORRECTION USING PAVER FINISH AT SRINAGAR COLONY NORTH MADA IN DN 171 UNIT 40, ZONE13.",Own Sources,13,2014-15,2016-17 NN/2014-15/26560,Roads,Completed,NN-ADYAR,171,2041000,"RELAYING THE ROAD WITH B.T. SURFACE WITH CAMBER CORRECTION USING PAVER FINISH AT SRINAGAR COLONY SOUTH AVENUE IN DN 171 UNIT 40, ZONE13",Own Sources,13,2014-15,2016-17 NN/2014-15/26561,Roads,Completed,NN-ADYAR,171,2010000,"RELAYING THE ROAD WITH B.T. SURFACE WITH CAMBER CORRECTION USING PAVER FINISH AT SRINAGAR COLONY WEST MADA STREET IN DN 171 UNIT 40, ZONE13",Own Sources,13,2014-15,2016-17 NN/2014-15/26569,Roads,Completed,NN-ADYAR,171,837000,"RELAYING THE ROAD WITH B.T. SURFACE WITH CAMBER CORRECTION USING PAVER FINISH AT BHARATHI DASAN STREET IN DN 171 UNIT 40, ZONE13",Own Sources,13,2014-15,2016-17 NN/2014-15/27932,Roads,Completed,NN-ADYAR,171,1537000,"RELAYING THE CONCRETE ROAD WITH M40 GRADE CONCRETE AT SASTHRI I CROSS STREET IN DIVISION 171, UNIT 40, ZONE 13",Own Sources,13,2014-15,2016-17 NN/2014-15/27936,Roads,Completed,NN-ADYAR,171,2312000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE CONCRETE AT ARANGANATHAN SUBWAY NORTH LANE IN DIVISION 171, UNIT 40, ZONE 13",Own Sources,13,2014-15,2016-17 NN/2014-15/27948,Roads,Completed,NN-ADYAR,171,2312000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE CONCRETE AT ARANGANATHAN SUBWAY SOUTH LANE IN DIVISION 171, UNIT 40, ZONE 13",Own Sources,13,2014-15,2016-17 NN/2014-15/27950,Roads,Completed,NN-ADYAR,171,1483000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE CONCRETE AT BHARATHIDASAN 1ST AND 2ND CROSS STREET IN DIVISION 171, UNIT 40, ZONE 13",Own Sources,13,2014-15,2016-17 NN/2014-15/27958,Roads,Completed,NN-ADYAR,171,1768000,"RELAYING THE CONCRETE ROAD WITH M40 GRADE CONCRETE AT MOSQUE GARDEN EAST & NORTH LANES IN DN 171, UNIT 40, ZONE 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/27962,Roads,Completed,NN-ADYAR,171,1768000,"RELAYING THE CONCRETE ROAD WITH M40 GRADE CONCRETE AT MOSQUE GARDEN WEST & SOUTH LANES IN DN 171, UNIT 40, ZONE 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/27964,Roads,Completed,NN-ADYAR,171,1600000,"RELAYING THE CONCRETE ROAD WITH M40 GRADE CONCRETE AT SASTRI 2ND CROSS STREET IN DN 171, UNIT 40, ZONE 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/27966,Roads,Completed,NN-ADYAR,171,1600000,"RELAYING THE CONCRETE ROAD WITH M40 GRADE CONCRETE AT SASTRI 3RD CROSS STREET IN DN 171, UNIT 40, ZONE 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/28203,Roads,Completed,NN-ADYAR,171,2121000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE CONCRETE AT JOTHIAMMAL NAGAR 1ST STREET IN DN - 171, UNIT 40, ZONE 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/28205,Roads,Completed,NN-ADYAR,171,2186000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE CONCRETE AT JOTHIAMMAL NAGAR 2ND STREET IN DN - 171, UNIT 40, ZONE 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/28207,Roads,Completed,NN-ADYAR,171,1693000,"RELAYING THE CONCRETE ROAD WITH M30 GRADE CONCRETE AT JOTHIAMMAL NAGAR 3 TO 10 STREETS IN DN - 171, UNIT 40, ZONE 13.",Own Sources,13,2014-15,2017-18 BR/2014-15/17408,Roads,Completed,BR-Bus Route Roads,172,28664000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at West Canal Bank Road from the junction Sardar Patel Road to the Junction of Ponniamman Koil Street Dn-172, Zone - 13",Grants,13,2014-15,2017-18 NN/2014-15/18930,Buildings,Completed,B-Buildings,172,1879000,"IMPROVEMENTS & ADDITIONAL CONSTRUCTION OF UPSC( DISPENSARY) IN DHANDAYUTHAPANI NAGAR 2nd STREET AT KOTTURPURAM IN DIV-172,UNIT-40,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/23225,Buildings,Completed,NN-ADYAR,172,2000000,"Construction of Multi Purpose Hall at Pondichery road ( GF and FF) in Dn 172,Unit 40, Zone XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/23837,Roads,Completed,NN-ADYAR,172,388000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Avvai Colony in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24345,Roads,Completed,NN-ADYAR,172,647000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Thiruvalluvar Nagar 4th Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24353,Roads,Completed,NN-ADYAR,172,547000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Thiruvalluvar Nagar 2nd Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24356,Roads,Completed,NN-ADYAR,172,424000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Guruvappan Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24362,Roads,Completed,NN-ADYAR,172,431000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Pillaiyar Koil Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24366,Roads,Completed,NN-ADYAR,172,610000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sriram Nagar Colony in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24519,Roads,Completed,NN-ADYAR,172,311000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Chellapa Garden in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24520,Roads,Completed,NN-ADYAR,172,519000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sowbhakya Avenue in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24526,Roads,Completed,NN-ADYAR,172,832000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at New Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24528,Roads,Completed,NN-ADYAR,172,675000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Yadaval Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24529,Roads,Completed,NN-ADYAR,172,366000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sakthi Avenue in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24677,Roads,Completed,NN-ADYAR,172,1173000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Murugappa Roads in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24680,Roads,Completed,NN-ADYAR,172,727000,"Relaying the Concrete road with M30 Grade at Angalamman Koil Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24686,Roads,Completed,NN-ADYAR,172,744000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Valliammai Achi Road in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24687,Roads,Completed,NN-ADYAR,172,1260000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Pallipattu Main Road in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25014,Roads,Completed,NN-ADYAR,172,852000,"Relaying the Concrete road with M30 Grade at Chitra Nagar 1st Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25015,Roads,Completed,NN-ADYAR,172,1296000,"Relaying the Concrete road with M30 Grade at Chitra Nagar 1st to 4th Cross Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25017,Roads,Completed,NN-ADYAR,172,1066000,"Relaying the Concrete road with M30 Grade at Chitra Nagar 2nd Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25019,Roads,Completed,NN-ADYAR,172,672000,"Relaying the Concrete road with M30 Grade at Duraisamy Nagar in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25023,Roads,Completed,NN-ADYAR,172,920000,"Relaying the Concrete road with M30 Grade at E.W.S. Quarters Lane in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25032,Roads,Completed,NN-ADYAR,172,668000,"Relaying the Concrete road with M30 Grade at Pillayar Koil Slum 1st Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25034,Roads,Completed,NN-ADYAR,172,768000,"Relaying the Concrete road with M30 Grade at Pillayar Koil Slum 2nd Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25038,Roads,Completed,NN-ADYAR,172,665000,"Relaying the Concrete road with M30 Grade at Rajiv Gandhi Avenue in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25040,Roads,Completed,NN-ADYAR,172,2262000,"Relaying the Concrete road with M30 Grade at Shriram Nagar 1st to 5th Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25043,Roads,Completed,NN-ADYAR,172,1074000,"Relaying the Concrete road with M30 Grade at Kotturpuram 1st Cross Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25044,Roads,Completed,NN-ADYAR,172,507000,"Relaying the Concrete road with M30 Grade at Kotturpuram 2nd Cross Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25418,Roads,Completed,NN-ADYAR,172,869000,"Relaying the Concrete road with M30 Grade at Kotturpuram 3rd Cross Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25420,Roads,Completed,NN-ADYAR,172,926000,"Relaying the Concrete road with M30 Grade at Kotturpuram 4th Main Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25423,Roads,Completed,NN-ADYAR,172,931000,"Relaying the Concrete road with M30 Grade at Kotturpuram River Bank Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25427,Roads,Completed,NN-ADYAR,172,503000,"Relaying the Concrete road with M30 Grade at Police Station Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25429,Roads,Completed,NN-ADYAR,172,1076000,"Relaying the Concrete road with M30 Grade at Naidu III Lane in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25431,Roads,Completed,NN-ADYAR,172,924000,"Relaying the Concrete road with M30 Grade at Ganapathy Avenue in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25436,Roads,Completed,NN-ADYAR,172,1781000,"Relaying the Concrete road with M30 Grade at Varadhapuram I, II, Lane, I,II Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25801,Roads,Completed,NN-ADYAR,172,4699000,"Relaying the Concrete road with M30 Grade at Kotturpuram Chitra Nagar Slum Clerance Board (Block 55 -88) in DN-172, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 BR/2014-15/17413,Roads,Completed,BR-Bus Route Roads,173,14637000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Kamarajar Salai (RA Puram) from the junction of PS Kumararaj Salai to the Junction of Srinivas Avenue road Dn-173 Zone - 13,Grants,13,2014-15,2016-17 BR/2014-15/17414,Roads,Completed,BR-Bus Route Roads,173,20547000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at P.S Kumaraswamy Raja Salai from the junction of R K Mutt road to the junction of Thideer Nagar Dn-173 Zone - 13,Grants,13,2014-15,2017-18 D/2014-15/27335,Storm Water Drain,Completed,D-Storm Water Drains,173,309742000,Construction of Integrated Storm Water Drains in Adyar Water Shed of Adyar Basin in Extended Areas of Chennai Corporation - Package -32,Loans And Grants,13,2014-15,2019-20 NN/2014-15/10892,Roads,Completed,NN-ADYAR,173,998000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF THANDAVARAYAN STREET TO JN OF M.R.C.NAGAR MAIN ROAD AT Dr. D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/10894,Roads,Completed,NN-ADYAR,173,990000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN AT INFROAT OF Dr.AMBEDKAR LAW UNIVERSITY AT Dr. D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/10895,Roads,Completed,NN-ADYAR,173,980000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN AT DURGA BAI DESMUKH ROAD IN DN-173, U- 40, ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/11176,Buildings,Completed,NN-ADYAR,173,990000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF POTHIGAI VALAGAM TO DR.AMBEDKAR MANI MANDABAM AT Dr. D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/11178,Buildings,Completed,NN-ADYAR,173,990000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN AT JN OF Dr.AMBEDKAR MANI MANDABAM TO KARPAGAM AVENUEAT AT Dr. D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/11179,Buildings,Completed,NN-ADYAR,173,990000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF M.R.C.NAGAR MAIN ROAD TO ROHINI GARDEN ST AT Dr. D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24723,Roads,Completed,NN-ADYAR,173,1379000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT KARPAGAM AVENUE MAIN ROAD IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24731,Roads,Completed,NN-ADYAR,173,1394000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT KESAVA PERUMAL PURAM CRESENT AVENUE IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24740,Roads,Completed,NN-ADYAR,173,1979000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT KRISHNAPURI MAIN ROAD & 1st ,2nd LANE IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24762,Roads,Completed,NN-ADYAR,173,412000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NARAYANA LANE IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24767,Roads,Completed,NN-ADYAR,173,270000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT R.K NAGAR I CROSS STREET IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24769,Roads,Completed,NN-ADYAR,173,221000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT R.K NAGAR III CROSS STREET IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24775,Roads,Completed,NN-ADYAR,173,579000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT SALAIYAR STREET IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24778,Roads,Completed,NN-ADYAR,173,868000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT SOUTH BEACH AVENUE 1ST&2ND STREET IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2017-18 NN/2014-15/24780,Roads,Completed,NN-ADYAR,173,379000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT SOUTH APAVOO 1ST,2ND &3RD STREET IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24783,Roads,Completed,NN-ADYAR,173,2742000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT BISHOP GARDEN IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24786,Roads,Completed,NN-ADYAR,173,1112000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT GREENWAYS ROAD EXTN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24792,Roads,Completed,NN-ADYAR,173,611000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT THIRUVENGADAM STREET EXTN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2017-18 NN/2014-15/24793,Roads,Completed,NN-ADYAR,173,1757000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT R.K NAGAR 2ND MAIN ROAD DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2017-18 NN/2014-15/24795,Roads,Completed,NN-ADYAR,173,1798000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT R.K NAGAR 2ND CROSS STREET DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2017-18 NN/2014-15/24803,Roads,Completed,NN-ADYAR,173,1177000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT MAY FLOWER GARDEN IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24827,Roads,Completed,NN-ADYAR,173,307000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT VELAYUDA RAJA STREET IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2014-15,2017-18 NN/2014-15/25336,Roads,Completed,NN-ADYAR,173,455000,"RELAYING CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR I STREET IN DIVISION - 173, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25344,Roads,Completed,NN-ADYAR,173,448000,RELAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR II STREET DN- 173 ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/25355,Roads,Completed,NN-ADYAR,173,396000,"RELAYING CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR III STREET IN DIVISION - 173, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25365,Roads,Completed,NN-ADYAR,173,779000,"RELAYING CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR IV STREET IN DIVISION - 173, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25368,Roads,Completed,NN-ADYAR,173,957000,"RELAYING CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR Vth STREET IN DIVISION - 173, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25371,Roads,Completed,NN-ADYAR,173,585000,"RELAYING CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR CROSS STREET IN DIVISION - 173, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25499,Roads,Completed,NN-ADYAR,173,779000,"RELAYING CEMENT CONCRETE ROAD AT MADAVAN NAGAR I & II STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25520,Roads,Completed,NN-ADYAR,173,747000,"RELAYING CEMENT CONCRETE ROAD AT NARAYANASAMY THOTTAM 2ND STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25530,Roads,Completed,NN-ADYAR,173,598000,"RELAYING CEMENT CONCRETE ROAD AT NARAYANASAMY THOTTAM 3RD STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25538,Roads,Completed,NN-ADYAR,173,784000,"RELAYING CEMENT CONCRETE ROAD AT S.K.PURAM 1ST CROSS STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25543,Roads,Completed,NN-ADYAR,173,265000,"RELAYING CEMENT CONCRETE ROAD AT S.K.PURAM 1ST STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25544,Roads,Completed,NN-ADYAR,173,925000,"RELAYING CEMENT CONCRETE ROAD AT S.K.PURAM 2ND CROSS STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25546,Roads,Completed,NN-ADYAR,173,338000,"RELAYING CEMENT CONCRETE ROAD AT S.K.PURAM 2ND STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25547,Roads,Completed,NN-ADYAR,173,732000,"RELAYING CEMENT CONCRETE ROAD AT S.K.PURAM 3RD CROSS STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25548,Roads,Completed,NN-ADYAR,173,338000,"RELAYING CEMENT CONCRETE ROAD AT S.K.PURAM 3RD STREET IN DIVISION - 173, UNIT-40, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25754,Roads,Completed,NN-ADYAR,173,2100000,"RELAYING CEMENT CONCRETE ROAD AT SCHOOL ROAD IN DIVISION - 173, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/26315,Roads,Completed,NN-ADYAR,173,1768000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Karpagam Avenue 1st Street and Lane in DN-173, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/28743,Buildings,Completed,NN-ADYAR,173,920000,CONSTRUCTION OF CONSERVANCY DUST BIN PLAT FORMS AT VARIOUS STREET IN IN DN-173 UNIT-40 ZONE-XIII,Own Sources,13,2014-15,2016-17 NN/2014-15/28745,Buildings,Completed,NN-ADYAR,173,284000,"Providing eSeva Centre at Kamarajar Salai in Dn-173, Unit-40, Zone-XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/29394,Buildings,Completed,NN-ADYAR,173,512000,"Repairs and Improvements to public conveyance at Kamarajar Salai, P.S. Kumarasamy Raja Salai, R.K. Mutt Road, Govindasamy East Road and Govindasamy West Road in Dn-173, Unit- 40, Zone-XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/6631,Roads,Completed,NN-ADYAR,173,979000,"PROPOSED CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER AT R.K.MUTT ROAD (OPPOSITE OF RANI MEYYAMMAI GIRLS HIGHER SECONDARY SCHOOL) UNDER WARD COUNCILLOR FUND IN DN-173, U- 40, ZONE-13",Own Sources,13,2014-15,2016-17 BR/2014-15/17409,Roads,Completed,BR-Bus Route Roads,174,97146000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Velachery Main Road from the junction of Anna Salai to Sardar Patel Road from the junction of Swiming pool Kanigapuram to Vijaynagaram bus stop Dn-171, 174 & 179, Zone - 13",Grants,13,2014-15,2016-17 BR/2014-15/28437,Roads,Completed,BR-Bus Route Roads,174,20870000,"Widening and forming of Road,Bus bay, Center median and Construction of SWD, Footpath at Madras Race Course Road in Div - 174, Z one - 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/22521,Parks,Completed,NN-ADYAR,174,999000,"PROVIDING STAINLESS STEEL HAND RAIL TO THE PATHWAY IN BETWEEN THE PARK AT SECEREATIAT COLONY IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/22523,Parks,Completed,NN-ADYAR,174,656000,"PROVIDING PEBBLES WALKING TRACK AT THE PARK AT SECEREATIAT COLONY IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/22530,Buildings,Completed,NN-ADYAR,174,885000,"IMPROVEMENTS TO THE SECOND FLOOR OF THE NINTH STD BLOCK AT THE CHENNAI HIGHER SECONDARY SCHOOL AT FIVE FURLONG ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/22532,Buildings,Completed,NN-ADYAR,174,980000,"IMPROVEMENTS TO THE SCIENCE LAB AND OUTER PAINTING OF THE NINTH AND TENTH STD BLOCK AT CHENNAI HIGHER SECONDARY SCHOOL IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/22536,Buildings,Completed,NN-ADYAR,174,950000,"IMPROVEMENTS TO THE FIRST FLOOR OF THE NINTH & TENTH STD BLOCK AT CHENNAI HIGHER SECONDARY SCHOOL AT FIVE FUR LONG ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/22893,Buildings,Completed,NN-ADYAR,174,484000,"Construction and repairs of toilets,drinking water taps,hand wash taps and urinals at Corporation of Chennai Primary School at Five furlong road in Dn-174,Unit-40(A),Zone-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/23027,Buildings,Completed,NN-ADYAR,174,999000,"Construction and repairs of toilets,drinking water taps,hand wash taps and urinals at Corporation of Chennai High School at Five furlong road in Dn-174,Unit-40(A),Zone-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24715,Roads,Completed,NN-ADYAR,174,550000,"RAISING AND RELAYING OF ROAD USING PAVER FINISHER AT ANNA GARDEN LANE AND CART TRACK LANE IN DN-174, UNIT-40(A),ZONE-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24860,Roads,Completed,NN-ADYAR,174,705000,"RAISING AND RELAYING OF ROAD WITH B.T COURSE USING PAVER FINISHER AT SATHANIPET LANE IN DN 174, UNIT-40(A), ZONE-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24869,Roads,Completed,NN-ADYAR,174,1707000,"RAISING AND RELAYING THE ROAD WITH CAMBER CORRECTION WITH PAVER FINISHER AT RACE VIEW COLONY MAIN ROAD IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24886,Roads,Completed,NN-ADYAR,174,878000,"RELAYING THE ROAD WITH CAMBER CORRECTION USING PAVER FINISHER AT THIRUMURUGAN STREET IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24892,Roads,Completed,NN-ADYAR,174,874000,"RAISING AND RELAYING OF ROAD WITH B.T COURSE USING PAVER FINISHER AT RAJ BHAVAN COLONY DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25307,Roads,Completed,NN-ADYAR,174,2472000,"RELAYING THE ROAD WITH CAMBER CORRECTION USING PAVER FINISHER AT RACE COURSE INTERIOR ROAD IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25329,Roads,Completed,NN-ADYAR,174,879000,"LAYING CEMENT CONCRETE ROAD AT KANNIGAPURAM 1ST STREET,KANNIGAPURAM 29TH STREET,KANNIGAPURAM 30TH STREET IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25386,Roads,Completed,NN-ADYAR,174,585000,"LAYING CEMENT CONCRETE ROAD AT MOSQUE COLONY 11TH STREET IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/9512,Buildings,Completed,NN-ADYAR,174,990000,"PROVIDING G.I DIRECTION NAME BOARD AND RETRO REFLECTIVE STREET NAME BOARD AT VARIOUS STREETS IN DN-174, UNIT-40(A), ZONE-13",Own Sources,13,2014-15,2017-18 BR/2014-15/17411,Roads,Completed,BR-Bus Route Roads,175,20531000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Indira Nagar 1st Avenue from the junction of Dr. Muthu lakshmi Salai to the junction of Indira Nagar 2nd Avenue Dn-175 Zone - 13,Grants,13,2014-15,2017-18 BR/2014-15/17415,Roads,Completed,BR-Bus Route Roads,175,27344000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Dr.Muthulakshmi Salai from the junction of Durgabai Desmuk Road to the junction of Kalkikrishna moorthy Salai Dn-175 Zone - 13,Grants,13,2014-15,2017-18 BR/2014-15/17419,Roads,Completed,BR-Bus Route Roads,175,27242000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Kalki Krishna murthy Salai from the Junction of Mahatma Gandhi Road to the Junction of West Canal Bank Road Dn 175, Zone - 13",Grants,13,2014-15,2017-18 BR/2014-15/17420,Roads,Completed,BR-Bus Route Roads,175,16187000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Indira Nagar 3rd avenue from the junction of Indira Nagar 2nd Avenue to the Junction of Kalkikrishna Moorthy Salai Road in Dn 175 Zone - 13,Grants,13,2014-15,2017-18 BR/2014-15/17421,Roads,Completed,BR-Bus Route Roads,175,22424000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Indira Nagar 2nd avenue from the junction of Mahatma Gandhi Road to the Junction of Rajiv Gandhi Salai service road in Dn 175 Zone - 13,Grants,13,2014-15,2017-18 BR/2014-15/30029,Roads,Completed,BR-Bus Route Roads,175,38320000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Gandhi Nagar 4th Main Road & Canal Bank Road from the junction of west canal bank road to the junction of Durgabai desmuk road Dn 172 & 175, Zone - 13.",Grants,13,2014-15,2016-17 BR/2014-15/30089,Roads,Completed,BR-Bus Route Roads,175,77355000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Sardar Patel Road from the junction of Durgabai Deshmuk Road to Gandhi Mandapam Signal Dn 172 & 175, Z-13.",Grants,13,2014-15,2016-17 NN/2014-15/19089,Buildings,Completed,NN-ADYAR,175,317000,"Repairs and Improvement to Regional Joint Commissioner Office (south) Annex Building at Thiruvengadam street in Dn-175, Unit-40, Zone-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24598,Roads,Completed,NN-ADYAR,175,2276000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Gandhi Nagar 1st Cresent Park Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24599,Roads,Completed,NN-ADYAR,175,1050000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Gandhi Nagar 1st Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24600,Roads,Completed,NN-ADYAR,175,1277000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Gandhi Nagar 2nd Cresent Park Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24601,Roads,Completed,NN-ADYAR,175,2153000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Gandhi Nagar 3rd Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24602,Roads,Completed,NN-ADYAR,175,853000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Gandhi Nagar 4th Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24603,Roads,Completed,NN-ADYAR,175,716000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 1st Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24604,Roads,Completed,NN-ADYAR,175,1973000,"Relaying the Concrete road with M30 Grade at Indira Nagar I, II, III Lane in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24605,Roads,Completed,NN-ADYAR,175,801000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 2nd Avenue Extn-2 in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24607,Roads,Completed,NN-ADYAR,175,413000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 2nd Avenue Extn-1 in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24608,Roads,Completed,NN-ADYAR,175,1718000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 2nd Main Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24689,Roads,Completed,NN-ADYAR,175,889000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 3rd Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24690,Roads,Completed,NN-ADYAR,175,2083000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 3rd Main Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24691,Roads,Completed,NN-ADYAR,175,2070000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 4th Avenue in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24692,Roads,Completed,NN-ADYAR,175,504000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 4th Avenue 1st Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24693,Roads,Completed,NN-ADYAR,175,369000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 4th Avenue Lane in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24694,Roads,Completed,NN-ADYAR,175,1301000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 4th Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24695,Roads,Completed,NN-ADYAR,175,317000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 4th Lane in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24696,Roads,Completed,NN-ADYAR,175,1182000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 4th Main Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24697,Roads,Completed,NN-ADYAR,175,306000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 9th Lane in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24698,Roads,Completed,NN-ADYAR,175,4378000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 20th Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24796,Roads,Completed,NN-ADYAR,175,2347000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 13th Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24798,Roads,Completed,NN-ADYAR,175,800000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Venkatarathinam Nagar - Extn - II in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24801,Roads,Completed,NN-ADYAR,175,716000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Venkatarathinam Nagar - Extn - I in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24802,Roads,Completed,NN-ADYAR,175,5068000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Venkatarathinam Nagar in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24804,Roads,Completed,NN-ADYAR,175,1761000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Teachers colony in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24807,Roads,Completed,NN-ADYAR,175,1088000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Srinivasamurthy avenue in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24811,Roads,Completed,NN-ADYAR,175,512000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at School Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24817,Roads,Completed,NN-ADYAR,175,1470000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at LB Road II street (Anand Apartments) in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24820,Roads,Completed,NN-ADYAR,175,887000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Krishnamachari avenue in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24821,Roads,Completed,NN-ADYAR,175,734000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 5th Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24824,Roads,Completed,NN-ADYAR,175,2037000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Kasthuribai Nagar V Main road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24825,Roads,Completed,NN-ADYAR,175,2243000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Kasthuribai Nagar IV Main road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24826,Roads,Completed,NN-ADYAR,175,3291000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Kasthuribai Nagar III Main road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24829,Roads,Completed,NN-ADYAR,175,592000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 5th Lane in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24830,Roads,Completed,NN-ADYAR,175,2678000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Kasthuribai Nagar II Main road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24831,Roads,Completed,NN-ADYAR,175,980000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 6th Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24832,Roads,Completed,NN-ADYAR,175,1003000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Kasthuri bai nagar VIII main road in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24840,Roads,Completed,NN-ADYAR,175,742000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 8th Lane in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24849,Roads,Completed,NN-ADYAR,175,654000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 11th Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24853,Roads,Completed,NN-ADYAR,175,4286000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Kamaraj avenue II street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24859,Roads,Completed,NN-ADYAR,175,3932000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Kamaraj avenue I street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24861,Roads,Completed,NN-ADYAR,175,656000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Iswarya colony in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24862,Roads,Completed,NN-ADYAR,175,3380000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar XXVIII Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24945,Roads,Completed,NN-ADYAR,175,1162000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar XXVI Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24964,Roads,Completed,NN-ADYAR,175,1807000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar XXIX Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24972,Roads,Completed,NN-ADYAR,175,522000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar XXIV Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24978,Roads,Completed,NN-ADYAR,175,466000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar XXIII Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24988,Roads,Completed,NN-ADYAR,175,754000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar XVIII Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24997,Roads,Completed,NN-ADYAR,175,863000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar XVI Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25764,Roads,Completed,NN-ADYAR,175,938000,"Relaying the Concrete road with M30 Grade at Loganathan Garden in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25767,Roads,Completed,NN-ADYAR,175,872000,"Relaying the Concrete road with M30 Grade at Kanniammal Kadai Lane in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25775,Roads,Completed,NN-ADYAR,175,4170000,"Relaying the Concrete road with M30 Grade at Malligai Poo Nagar in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25837,Roads,Completed,NN-ADYAR,175,511000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar VI Lane in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25848,Roads,Completed,NN-ADYAR,175,1118000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 11th Lane in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25850,Roads,Completed,NN-ADYAR,175,879000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Indira Nagar 12th Cross street in DN-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25855,Roads,Completed,NN-ADYAR,175,1139000,"Relaying the Concrete road with M30 Grade at Indira Nagar XII Lane in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25856,Roads,Completed,NN-ADYAR,175,1042000,"Relaying the Concrete road with M30 Grade at Indira Nagar XIII Lane in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25858,Roads,Completed,NN-ADYAR,175,2263000,"Relaying the Concrete road with M30 Grade at Indira Nagar 14th Cross Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25860,Roads,Completed,NN-ADYAR,175,783000,"Relaying the Concrete road with M30 Grade at Indira Nagar 14th Lane in Dn-175, Unit-40, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/29458,Buildings,Completed,NN-ADYAR,175,636000,Construction of Conservancy Dust Bin platforms at Indira Nagar Entire Streets in Dn-175 Unit-40 Zone-13,Own Sources,13,2014-15,2016-17 NN/2014-15/29474,Buildings,Completed,NN-ADYAR,175,150000,"Repairs and Improvements to public conveyance at Balaraman Street in Dn-175, Unit- 40, Zone-XIII.",Own Sources,13,2014-15,2016-17 BR/2014-15/30080,Roads,Completed,BR-Bus Route Roads,176,33295000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Besant Avenue Road from the junction of Besant Nagar 3rd Avenue to Ellai Amman Kovil in Dn-176, Zone-XIII",Grants,13,2014-15,2017-18 BR/2014-15/30083,Roads,Completed,BR-Bus Route Roads,176,14602000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Besant nagar 3rd avenue from the junction of Besant Avenue to junction of Besant Nagar 2nd Avenue in Dn-176,Zone - 13",Grants,13,2014-15,2017-18 NN/2014-15/0033,Buildings,Completed,NN-ADYAR,176,995000,"Repairs and Improvements to Amma Canteen and Construction of Amma canteen store room at Besant Nagar 1st Avenue (Near Fish market) in Dn-176, Unit 38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/13285,Buildings,Completed,NN-ADYAR,176,705000,LAYING GARBAGE BIN PLATFORM AT VARIOUS LOCATION IN DIVISION-176 UNIT-38 ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/14129,Roads,Completed,NN-ADYAR,176,2667000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 16th Cross Street in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/15134,Roads,Completed,NN-ADYAR,176,568000,"Relaying of Road with BCCMP 40mm thick including camber correction using by paver finisher at venkateswara nagar 2nd street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/22480,Roads,Completed,NN-ADYAR,176,967000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREETS IN DN-176,UNIT- 38 ,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/23597,Roads,Completed,NN-ADYAR,176,1591000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 6th Avenue (Partly), in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/23599,Roads,Completed,NN-ADYAR,176,1336000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 24th Cross Street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/23601,Roads,Completed,NN-ADYAR,176,1132000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 34th Cross Street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/23603,Roads,Completed,NN-ADYAR,176,1299000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 35th Cross Street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/23613,Roads,Completed,NN-ADYAR,176,580000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Customs colony, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/23660,Buildings,Completed,NN-ADYAR,176,728000,"IMPROVEMENTS OF SCHOOL, CARE AND PROTECTION CENTER OF CHILDREN AND SHED AT CPS DHAMODHARAPURAM. DN-176, UNIT- 38, ZONE- 13",Own Sources,13,2014-15,2017-18 NN/2014-15/23686,Roads,Completed,NN-ADYAR,176,732000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Customs colony 1st cross street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/23690,Roads,Completed,NN-ADYAR,176,1621000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Dhamodharapuram Main Road (partly) in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/23691,Roads,Completed,NN-ADYAR,176,1485000,"Relaying the Road with BCCMP 40mm thick Including Camber correction by Paver Finisher at Karpagam Garden 1st Main Road (Partly) in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/23692,Roads,Completed,NN-ADYAR,176,483000,"Relaying the Road with BCCMP 40mm thick Including Camber Correction by Paver Finisher at Karpagam Garden 1st Cross Street (Partly) in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/23694,Roads,Completed,NN-ADYAR,176,822000,"Relaying the Road with BCCMP 40mm thick Including camber correction using by Paver Finisher at Karpagam Garden 2nd Cross Street in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/23700,Roads,Completed,NN-ADYAR,176,822000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Padmanabha Nagar 3rd Street in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/23910,Roads,Completed,NN-ADYAR,176,1034000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Thiruvalluvar Nagar 2nd Main Road in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/23913,Roads,Completed,NN-ADYAR,176,877000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Thiruvalluvar Nagar 2nd Cross Street in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/24246,Roads,Completed,NN-ADYAR,176,782000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Thiruvalluvar Nagar 1st Cross Street in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/24558,Roads,Completed,NN-ADYAR,176,1976000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 1st Avenue Service Road, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/24566,Roads,Completed,NN-ADYAR,176,568000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Cart Track Road, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/25215,Roads,Completed,NN-ADYAR,176,3771000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sastri Nagar I Avenue(Part 1) in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25222,Roads,Completed,NN-ADYAR,176,1560000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sastri Nagar I Cross Street in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25228,Roads,Completed,NN-ADYAR,176,3088000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sastri Nagar I Main Road in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25240,Roads,Completed,NN-ADYAR,176,758000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sastri Nagar XV Cross Street in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25244,Roads,Completed,NN-ADYAR,176,556090,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Vasantha Press South Lane in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25269,Roads,Completed,NN-ADYAR,176,2994000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Padmanabha Nagar 1 to XXIV Lanes in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/25292,Roads,Completed,NN-ADYAR,176,625000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Jayaram Avenue in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/25326,Roads,Completed,NN-ADYAR,176,518000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 19th Cross Street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/25330,Roads,Completed,NN-ADYAR,176,2713000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 2nd Cross Street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/25334,Roads,Completed,NN-ADYAR,176,3097000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 1st main road, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/25338,Roads,Completed,NN-ADYAR,176,2207000,"Relaying the Road with BCCMP 40mm thick including camber correction using by Paver Finisher at Besant Nagar 1st Cross street, in Div - 176, U - 38, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/25347,Roads,Completed,NN-ADYAR,176,3982000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Sastri Nagar I Avenue(Part 2) in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25773,Roads,Completed,NN-ADYAR,176,1085000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Padmanabha Nagar 5th Street (Partly) in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25786,Roads,Completed,NN-ADYAR,176,1451000,"Relaying the Concrete road with M30 Grade at Kakkan Colony in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25788,Roads,Completed,NN-ADYAR,176,488000,"Relaying the Concrete road with M30 Grade at Adhi Dravidar Colony in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25789,Roads,Completed,NN-ADYAR,176,1071000,"Relaying the Concrete road with M30 Grade at Ellaiamman Koil 1st Lane in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25790,Roads,Completed,NN-ADYAR,176,1157000,"Relaying the Concrete road with M30 Grade at Ellaiamman Koil 2nd Lane in Dn-176, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/29352,Buildings,Completed,NN-ADYAR,176,178000,"OUT SOURCING OF PRIVATE CONERVANCY INC.M.S AT 4 TH STREET IN DN-176,UNIT-38,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/29355,Buildings,Completed,NN-ADYAR,176,178000,"OUT SOURCING OF PRIVATE CONSERVANCY IN C.P.S AT SASTRI NAGAR 11 TH STREET IN DN-176,UNIT-38,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/5716,Buildings,Completed,NN-ADYAR,176,995000,"Proposed Repairs and Improvements Works to the Gasifier Crematorium at Besant Nagar( Burial Ground Unit 1 ) in Div - 176, U - 38, Zone - XIII",Own Sources,13,2014-15,2018-19 NN/2014-15/5856,Footpath,Completed,NN-ADYAR,176,495000,"Forming Footpath at Sastri Nagar 11th Cross Street , in Div - 176, U - 38, Zone - 13.",Own Sources,13,2014-15,2016-17 BR/2014-15/17416,Roads,Completed,BR-Bus Route Roads,177,5813000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Brindhavan nagar Main Road from the junction Lake View Road to the junction of Mahalakshmi Nagar 1st Main Road Dn-177 Zone - 13,Grants,13,2014-15,2016-17 BR/2014-15/17417,Roads,Completed,BR-Bus Route Roads,177,4211000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Mahalakshmi nagar 1st Main Road from the junction of Mahalakshmi Nagar 2nd Main Road to the Junction of Brindavan Nagar Main Road Dn 177 Zone - 13,Grants,13,2014-15,2016-17 BR/2014-15/30084,Roads,Completed,BR-Bus Route Roads,177,6587000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at AGS Colony 4th main road from the junction of AGS Colony School Road to the junction of MGR Nagar in Dn-177, Z-13",Grants,13,2014-15,2017-18 BR/2014-15/30085,Roads,Completed,BR-Bus Route Roads,177,1567000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at AGS Colony school road from the junction of Andal nagar 6th Cross Street to the Junction of AGS Colony 4th main road in Dn-177, Z-13",Grants,13,2014-15,2017-18 BR/2014-15/30086,Roads,Completed,BR-Bus Route Roads,177,7666000,"Relaying the Road with CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Andal Nagar 6th Cross Street, Andal Nagar 1th Cross Street, Andal Nagar 3th Cross Street, Andal Nagar 1th Main Road and Andal Nagar 2th Main Road from the junction of Mahalakshmi Nagar 3rd Main road to the Junction of ASG Colony School road in Dn-177, Z-13",Grants,13,2014-15,2017-18 D/2014-15/17985,Storm Water Drain,Completed,D-Storm Water Drains,177,7137000,"Construction of RCC Box type storm water Drain of size 900x900mm along EB Colony 2nd street from EB Colony Main Road to Radha Nagar Extension Main Road in Divn-177, Zone-XIII.",JNNURM,13,2014-15,2016-17 D/2014-15/18121,Storm Water Drain,Completed,D-Storm Water Drains,177,8921000,"Construction of RCC Box type storm water Drain of size 900x900mm along Lakshmi Nagar 2nd Street From Lakhmi Nagar Main Road to Rajiv Gandhi Nagar Main Road in Divn-177, Zone-XIII.",JNNURM,13,2014-15,2016-17 L/2014-15/6745,Electrical,Completed,L-Electrical,177,4338000,"Conversion of 473nos 40w to 50w LED Fitting ( in place of 70w SV Fitting) in Velachery, Div 177, Zone - XIII.",Own Sources,13,2014-15,2016-17 L/2014-15/6748,Electrical,Completed,L-Electrical,177,4434500,"Conversion of 95nos 150/165w LED Fitting ( in place of 250w S.V Fittings) and 82nos 90w/120w LED fitting (in place of 150w SV Fitting) in Velachery, Div 177, Zone - XIII.",Own Sources,13,2014-15,2016-17 L/2014-15/6759,Electrical,Completed,L-Electrical,177,2513000,"Conversion of 274nos 40w to 50w LED Fitting ( in place of 70w SV Fitting) in Velachery, Div 177, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/16119,Buildings,Completed,NN-ADYAR,177,2600000,PROPOSED CONSTRUCTION OF AMMA CANTEEN AT LAKEVIEW ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/19636,Roads,Completed,NN-ADYAR,177,184000,IMPROVEMENTS TO GROUP BIN AT 100 FEET BYE PASS ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/22258,Roads,Completed,NN-ADYAR,177,484000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT MAHALAKSHMI NAGAR EAST EXTN 1st STREET IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2017-18 NN/2014-15/22262,Roads,Completed,NN-ADYAR,177,484000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT MAHALAKSHMI NAGAR EAST EXTN 2nd STREET IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2017-18 NN/2014-15/22270,Roads,Completed,NN-ADYAR,177,570000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT ANDAL NAGAR 3rd CROSS STREET IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2017-18 NN/2014-15/24486,Roads,Completed,NN-ADYAR,177,1936000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT A.G.S COLONY 1st MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24487,Roads,Completed,NN-ADYAR,177,1680000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT A.G.S COLONY 2nd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24488,Roads,Completed,NN-ADYAR,177,1628000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT A.G.S COLONY 3rd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24489,Roads,Completed,NN-ADYAR,177,400000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT A.G.G COLONY 6th CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24490,Roads,Completed,NN-ADYAR,177,1011000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT ANDAL NAGAR EXTN 1st STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24492,Roads,Completed,NN-ADYAR,177,1330000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT ANDAL NAGAR EXTN 2nd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24493,Roads,Completed,NN-ADYAR,177,330000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT GANGAI NAGAR 3rd CROSS STREET IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2017-18 NN/2014-15/24494,Roads,Completed,NN-ADYAR,177,1246000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT ANDAL NAGAR 4th CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24497,Roads,Completed,NN-ADYAR,177,894000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT BRINDHAVAN NAGAR EXTN 2nd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24500,Roads,Completed,NN-ADYAR,177,517000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT BRINDHAVAN NAGAR EXTN 3rd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24501,Roads,Completed,NN-ADYAR,177,517000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT BRINDHAVAN NAGAR EXTN 5th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24502,Roads,Completed,NN-ADYAR,177,252000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT BRINDHAVAN NAGAR EXTN 6th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24503,Roads,Completed,NN-ADYAR,177,1345000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT E.B COLONY 3rd STREET -2nd CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24504,Roads,Completed,NN-ADYAR,177,337000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT E.B COLONY EXTN STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24552,Roads,Completed,NN-ADYAR,177,799000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT E.B COLONY 2nd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24555,Roads,Completed,NN-ADYAR,177,546000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT E.B COLONY 3rd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24597,Roads,Completed,NN-ADYAR,177,521000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT E.B COLONY 4th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24610,Roads,Completed,NN-ADYAR,177,1121000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT E.B COLONY MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24612,Roads,Completed,NN-ADYAR,177,456000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT E.B COLONY 6th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24614,Roads,Completed,NN-ADYAR,177,585000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT GANGAI NAGAR 2nd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24616,Roads,Completed,NN-ADYAR,177,259000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT GANGAI NAGAR 5th MAIN ROAD - 1st CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24624,Roads,Completed,NN-ADYAR,177,721000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT L.H NAGAR 1st STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24633,Roads,Completed,NN-ADYAR,177,953000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT L.H NAGAR 4th CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24639,Roads,Completed,NN-ADYAR,177,1015000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT M.G.R NAGAR 1st MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24661,Roads,Completed,NN-ADYAR,177,502000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT MAHALAKSHMI NAGAR 9th CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24664,Roads,Completed,NN-ADYAR,177,929000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT MOHANAPURI 4th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24666,Roads,Completed,NN-ADYAR,177,650000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT N.N.G.O COLONY 2nd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24668,Roads,Completed,NN-ADYAR,177,517000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT N.N.G.O COLONY 4th MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24670,Roads,Completed,NN-ADYAR,177,1237000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT N.N.G.O COLONY 4th CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24704,Roads,Completed,NN-ADYAR,177,278000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NETHAJI COLONY CHURCH STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24706,Roads,Completed,NN-ADYAR,177,490000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEW SECRETARIAT COLONY 1st STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24707,Roads,Completed,NN-ADYAR,177,445000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEW SECRETARIAT COLONY 2nd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24708,Roads,Completed,NN-ADYAR,177,442000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEW SECRETARIAT COLONY 3rd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24710,Roads,Completed,NN-ADYAR,177,727000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RADHA NAGAR EXTN MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24711,Roads,Completed,NN-ADYAR,177,970000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAJIV NAGAR -AMMAN KOIL STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24753,Roads,Completed,NN-ADYAR,177,491000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAJIV NAGAR- RADHA 1st STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24755,Roads,Completed,NN-ADYAR,177,1001000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAJIV NAGAR MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24757,Roads,Completed,NN-ADYAR,177,1129000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAJIV NAGAR - VIGNESH SALAI IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24760,Roads,Completed,NN-ADYAR,177,862000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAMAKRISHNA NAGAR 2nd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24761,Roads,Completed,NN-ADYAR,177,928000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAMAKRISHNA NAGAR 2nd CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24763,Roads,Completed,NN-ADYAR,177,573000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAMAKRISHNA NAGAR MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24764,Roads,Completed,NN-ADYAR,177,1389000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT V.V COLONY 1st STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24765,Roads,Completed,NN-ADYAR,177,824000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT VEL NAGAR 1st STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24766,Roads,Completed,NN-ADYAR,177,182000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT VEL NAGAR 1st STREET LANE IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24768,Roads,Completed,NN-ADYAR,177,550000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT VEL NAGAR MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24770,Roads,Completed,NN-ADYAR,177,2145000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT M.G.R NAGAR 2nd CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24771,Roads,Completed,NN-ADYAR,177,1389000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR- THIRUVALLUVAR STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24772,Roads,Completed,NN-ADYAR,177,1257000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR- KAMARAJAR STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24774,Roads,Completed,NN-ADYAR,177,868000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NETHAJI COLONY 1st MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24776,Roads,Completed,NN-ADYAR,177,914000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEW SECRETARIAT COLONY 6th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24779,Roads,Completed,NN-ADYAR,177,786000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEW SECRETARIAT COLONY 5th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24781,Roads,Completed,NN-ADYAR,177,967000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAMAKRISHNA NAGAR 1st MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24782,Roads,Completed,NN-ADYAR,177,854000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAJIV NAGAR - RADHA MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24784,Roads,Completed,NN-ADYAR,177,217000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT BRINDHAVAN NAGAR EXTN 4th STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24785,Roads,Completed,NN-ADYAR,177,1186000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT RAJIV NAGAR - NEHRU STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24787,Roads,Completed,NN-ADYAR,177,288000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT ANDAL NAGAR 7th CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24797,Roads,Completed,NN-ADYAR,177,848000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT M.G.R NAGAR 2nd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24822,Roads,Completed,NN-ADYAR,177,1886000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR - KARUNANITHI STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/24823,Roads,Completed,NN-ADYAR,177,716000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR - LAKE VIEW ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24834,Roads,Completed,NN-ADYAR,177,824000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR - BHARATHIYAR STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24835,Roads,Completed,NN-ADYAR,177,926000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR - N.S.K 1st STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24838,Roads,Completed,NN-ADYAR,177,788000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR - N.S.K 2nd STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24867,Roads,Completed,NN-ADYAR,177,654000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR -SATHIYAVANI MUTHU STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24868,Roads,Completed,NN-ADYAR,177,1011000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR -THIRU.V.KA STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24888,Roads,Completed,NN-ADYAR,177,1001000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NETHAJI COLONY 3rd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/24890,Roads,Completed,NN-ADYAR,177,1620000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT ANDAL NAGAR 3rd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/25099,Roads,Completed,NN-ADYAR,177,352000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT TNHB COLONY 99 LANE IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2017-18 NN/2014-15/25107,Roads,Completed,NN-ADYAR,177,401000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEW SECRETARIAT COLONY 4th STREET IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2017-18 NN/2014-15/25112,Roads,Completed,NN-ADYAR,177,850000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT VENKATESWARA NAGAR 4th MAIN ROAD IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2017-18 NN/2014-15/25120,Roads,Completed,NN-ADYAR,177,1335000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT NEHRU NAGAR - KANNAGI STREET IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2016-17 NN/2014-15/25128,Roads,Completed,NN-ADYAR,177,1496000,"RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT VENKATESWARA NAGAR 3rd MAIN ROAD IN DN-177 UNIT-40A ZONE-13,",Own Sources,13,2014-15,2016-17 NN/2014-15/25138,Roads,Completed,NN-ADYAR,177,331000,RELAYING THE ROAD WITH M 30 GRADE AT KANNAGI STREET - 1st LANE IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/25144,Roads,Completed,NN-ADYAR,177,303000,RELAYING THE ROAD WITH M 30 GRADE AT KANNAGI STREET - 2nd LANE IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/25148,Roads,Completed,NN-ADYAR,177,288000,RELAYING THE ROAD WITH M 30 GRADE AT KANNAGI STREET - 3rd LANE IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/25152,Roads,Completed,NN-ADYAR,177,85400,RELAYING THE ROAD WITH M 30 GRADE AT KANNAGI STREET - 4th LANE IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/25155,Roads,Completed,NN-ADYAR,177,85400,RELAYING THE ROAD WITH M 30 GRADE AT KANNAGI STREET - 5th LANE IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/3190,Roads,Completed,NN-ADYAR,177,530000,PROPOSED CONSTRUCTION OF COMPOUND WALL AND PARK AT KAKKAN NAGAR 3rd CROSS STREET IN DN-177 UNIT-40A ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/7837,Buildings,Completed,NN-ADYAR,177,940000,"IMPROVEMENT TO EXISTING HEALTH POST IN TNHB COLONY 3rd AVENUE IN DIVISION 177, UNIT 40 A, ZONE XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/9515,Roads,Completed,NN-ADYAR,177,998000,"PROVIDING G.I DIRECTION NAME BOARD AND RETRO REFLECTIVE STREET NAME BOARD AT VARIOUS STREETS IN DN-177, UNIT-40 (A) , ZONE-13,",Own Sources,13,2014-15,2017-18 L/2014-15/6763,Electrical,Completed,L-Electrical,178,4548500,"Conversion of 7ow SV Fitting 496nos in to 40/50w LED Fitting in Velachery, Div 178, Zone - XIII.",Own Sources,13,2014-15,2016-17 L/2014-15/6766,Electrical,Completed,L-Electrical,178,4117400,"Conversion of 120nos 150/165w LED Fitting ( in place of 250w S.V Fittings) and 20nos 90w/120w LED fitting (in place of 150w SV Fitting) in Velachery, Div 178, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/20057,Buildings,Completed,NN-ADYAR,178,354000,"Providing Garbage Bin Platform at Various locations in Dn 178, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/20070,Buildings,Completed,NN-ADYAR,178,998000,"Proposed Fixing of Street Name Boards using Stainless Steel Pipe and Retro Reflective Sheet at Various Streets in Dn 178, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25204,Roads,Completed,NN-ADYAR,178,456000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Devikarumari Amman Nagar 5th Street in Dn 178, Unit 39,Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25210,Roads,Completed,NN-ADYAR,178,344000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Vijaya Nagar North Extn 3rd Street in Dn 178, Unit 39,Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25254,Roads,Completed,NN-ADYAR,178,291000,"RELAYING OF ROAD USING PAVER AT GOLDEN AVENUE I STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25261,Roads,Completed,NN-ADYAR,178,960000,"RELAYING OF ROAD BY PAVER AT PADMAVATHI NAGAR EXTN MAIN ROAD IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25265,Roads,Completed,NN-ADYAR,178,290000,"RELAYING OF ROAD BY PAVER AT PADMAVATHY NAGAR EXTN IV STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25270,Roads,Completed,NN-ADYAR,178,229000,"Relaying of road with bitumen concrete 40mm thick by using paver finisher at Vijaya Nagar North Extn 4th street in Dn 178, unit 39, zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25272,Roads,Completed,NN-ADYAR,178,221000,"RELAYING OF ROAD BY PAVER AT PADMAVATHY NAGAR EXTN III STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25278,Roads,Completed,NN-ADYAR,178,310000,"RELAYING OF ROAD BY PAVER AT PADMAVATHY NAGAR EXTN II STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25282,Roads,Completed,NN-ADYAR,178,209000,"RELAYING OF ROAD BY PAVER AT PADMAVATHY NAGAR EXTN I STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25284,Roads,Completed,NN-ADYAR,178,1039000,"RELAYING OF ROAD BY PAVER AT JAGANATHAPURAM III MAIN ROAD IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25289,Roads,Completed,NN-ADYAR,178,236000,"RELAYING OF ROAD BY PAVER AT RAJALAKSHMI NAGAR III MAIN ROAD AVENUE IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25293,Roads,Completed,NN-ADYAR,178,1093000,"RELAYING OF ROAD BY PAVER AT RAJALAKSHMI NAGAR III MAIN ROAD IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25296,Roads,Completed,NN-ADYAR,178,290000,"RELAYING OF ROAD BY PAVER AT BRAHMIN STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25298,Roads,Completed,NN-ADYAR,178,245000,"Relaying of road with bitumen concrete 40mm thick by using paver finisher at Padmavathi Nagar 5th street in Dn 178, unit 39, zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25301,Roads,Completed,NN-ADYAR,178,252000,"RELAYING OF ROAD BY PAVER AT GOLDEN AVENUE II STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25303,Roads,Completed,NN-ADYAR,178,2942000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT RAM NAGAR NORTH EXTN VI MAIN ROAD IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25305,Roads,Completed,NN-ADYAR,178,1969000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT RAM NAGAR NORTH EXTN VII MAIN ROAD IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25306,Roads,Completed,NN-ADYAR,178,606000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT OFFICER'S COLONY MAIN ROAD IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25309,Roads,Completed,NN-ADYAR,178,271000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT VIJAYA NAGAR NORTH EXTN 2ND CROSS STREET IN DIVISION - 178, ZONE - XIII.",Own Sources,13,2014-15,2017-18 NN/2014-15/25312,Roads,Completed,NN-ADYAR,178,1452000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT VIJAYA NAGAR I CROSS STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25313,Roads,Completed,NN-ADYAR,178,773000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT AGS COLONY II CROSS STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25314,Roads,Completed,NN-ADYAR,178,2551000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT VIJAYA NAGAR III MAIN ROAD IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25316,Roads,Completed,NN-ADYAR,178,559000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT JAGANATHAPURAM I MAIN ROAD (PART) IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25319,Roads,Completed,NN-ADYAR,178,938000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT PILLAIYAR KOIL STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25320,Roads,Completed,NN-ADYAR,178,587000,"Strengthening of road with Bitumen Course by using paver Finisher at Srinivasa Nagar 2nd Cross Street at Dn178, unit 39, zone 13",Own Sources,13,2014-15,2017-18 NN/2014-15/25321,Roads,Completed,NN-ADYAR,178,440000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT VIJAYA NAGAR NORTH HOME LANE IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25323,Roads,Completed,NN-ADYAR,178,968000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT DEVI KARUMARIAMMAN NAGAR I STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25331,Roads,Completed,NN-ADYAR,178,440000,"STRENGTHENING AND RELAYING OF ROAD BY PAVER AT DEVI KARUMARIAMMAN NAGAR IV STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25342,Roads,Completed,NN-ADYAR,178,594000,"STRENGTHENING AND RELAYING OF ROAD AT DEVI KARUMARIAMMAN NAGAR IX CROSS STREET IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25346,Roads,Completed,NN-ADYAR,178,1523000,"STRENGTHENING AND RELAYING OF ROAD AT SABARI NAGAR IN DIVISION - 178, ZONE - XIII",Own Sources,13,2014-15,2016-17 BR/2014-15/17418,Roads,Completed,BR-Bus Route Roads,179,16450000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Mahatma Gandhi Road from the Junction of Indira Nagar 2nd Avenue to the Junction of Besant Nagar 7th Avenue Dn 179, Zone - 13",Grants,13,2014-15,2017-18 BR/2014-15/30028,Roads,Completed,BR-Bus Route Roads,179,1828000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at LIC Colony main road from the junction of LIC colony 1st Cros street to the junction of Velachery Main Road, in Dn-179, in Z-13",Grants,13,2014-15,2017-18 L/2014-15/6767,Electrical,Completed,L-Electrical,179,4362500,"Conversion of 317nos 40w to 50w LED Fitting ( in place of 70w SV Fitting) and 59nos 90w to 120w LED fitting (in place of 150w LED fitting) and 13nos 150w to 165w LED fitting (in place of 250w LED fitting) in Velachery, Div 179, Zone - XIII.",Own Sources,13,2014-15,2016-17 L/2014-15/6769,Electrical,Completed,L-Electrical,179,3449000,"Conversion of 110nos 150w to 165w LED fitting (in place of 250w LED fitting) in Velachery, Div 179, Zone - XIII.",Own Sources,13,2014-15,2016-17 NN/2014-15/13450,Buildings,Completed,NN-ADYAR,179,183000,"Proposed Construction of Compound Wall for Corporation land at Andal Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/14653,Roads,Completed,NN-ADYAR,179,3820000,"Strengthening of road with B.T. Course by using Paver finisher at Seshadripuram 1st Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/15060,Roads,Completed,NN-ADYAR,179,1761000,"Strengthening of road with B.T. Course by using Paver finisher at Park Avenue 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/15070,Roads,Completed,NN-ADYAR,179,2044000,"Strengthening of road with B.T. Course by using Paver Finisher at Park Avenue 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/15115,Buildings,Completed,NN-ADYAR,179,128000,"Proposed Construction of Gate and Gate Pillar and Raising Compound Wall in Chennai Primary School at Udhayam Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/20079,Buildings,Completed,NN-ADYAR,179,313000,"Improvements to Public Convenience at Thiruveethiamman Koil Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/20545,Parks,Completed,NN-ADYAR,179,39000,"OUTSOURCING MAINTENANCE OF PARK AT VELACHERY MAIN ROAD BHARATHIYAR PARK) IN DIVISION-179,UNIT-39,ZONE-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25212,Roads,Completed,NN-ADYAR,179,474000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Tansi Nagar 3rd Street in Dn 179, Unit 39,Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25216,Roads,Completed,NN-ADYAR,179,2239000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar 7th Main Road in Dn 179, Unit 39,Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25227,Roads,Completed,NN-ADYAR,179,419000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher atKarnam Street in Dn 179, Unit 39,Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25251,Roads,Completed,NN-ADYAR,179,169000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Sarathy Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25252,Roads,Completed,NN-ADYAR,179,109000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Sarathy Nagar 4th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25255,Roads,Completed,NN-ADYAR,179,549000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Seetharam Nagar 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25259,Roads,Completed,NN-ADYAR,179,503000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Seetharam Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25260,Roads,Completed,NN-ADYAR,179,987000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher atMurphydoss Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25263,Roads,Completed,NN-ADYAR,179,282000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Prabhu Lane in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25267,Roads,Completed,NN-ADYAR,179,237000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Prasad Lane in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25273,Roads,Completed,NN-ADYAR,179,313000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar 4th Avenue West 2nd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25277,Roads,Completed,NN-ADYAR,179,483000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Hudson Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25280,Roads,Completed,NN-ADYAR,179,419000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Kambar Street (Dhandeeswaram Nagar) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25283,Roads,Completed,NN-ADYAR,179,552000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Bharathi Street (Dhandeeswaram Nagar) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25285,Roads,Completed,NN-ADYAR,179,746000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25287,Roads,Completed,NN-ADYAR,179,338000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar 6th Main Road Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25290,Roads,Completed,NN-ADYAR,179,846000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar 4th Avenue West in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25295,Roads,Completed,NN-ADYAR,179,834000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Seethapathy Nagar Extn., in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25297,Roads,Completed,NN-ADYAR,179,286000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar 5th Avenue West in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25302,Roads,Completed,NN-ADYAR,179,552000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Ayodhya Colony Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25340,Roads,Completed,NN-ADYAR,179,703000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Latha Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25343,Roads,Completed,NN-ADYAR,179,217000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar 4th Avenue West 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25348,Roads,Completed,NN-ADYAR,179,493000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Arumuga Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25349,Roads,Completed,NN-ADYAR,179,1194000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Ambika Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25356,Roads,Completed,NN-ADYAR,179,885000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Tansi Nagar 17th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25359,Roads,Completed,NN-ADYAR,179,683000,"Relaying of road with Bitumen Concrete 40mm thick by using Paver finisher at Dhandeeswaram Nagar Main Road (Partly) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25366,Roads,Completed,NN-ADYAR,179,557000,"Strengthening of road with Bitumen Course by using Paver finisher at Kamaraj Street (Annai Indira Nagar) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25370,Roads,Completed,NN-ADYAR,179,1175000,"Raising and Strengthening of road with Bitumen Course by using Paver finisher at Kathiravan Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25374,Roads,Completed,NN-ADYAR,179,1438000,"Strengthening of road with Bitumen Course by using Paver finisher at V.G.P. Selva Nagar Extn 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25379,Roads,Completed,NN-ADYAR,179,329000,"Strengthening of road with Bitumen Course by using Paver finisher at Balamurugan Nagar 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25390,Roads,Completed,NN-ADYAR,179,1678000,"Strengthening of road with Bitumen Course by using Paver finisher at V.G.P. Selva Nagar Extn., 5th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25391,Roads,Completed,NN-ADYAR,179,1547000,"Strengthening of road with Bitumen Course by using Paver finisher at Bhuvaneswari Nagar 1st Main Road (Part) (From Plot No.111 to Plot No.122) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25393,Roads,Completed,NN-ADYAR,179,1429000,"Strengthening of road with Bitumen Course by using Paver finisher at Baby Nagar 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25401,Roads,Completed,NN-ADYAR,179,303000,"Strengthening of road with Bitumen Course by using Paver finisher at Bethel Avenue 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25405,Roads,Completed,NN-ADYAR,179,317000,"Strengthening of road with Bitumen Course by using Paver finisher at Bethel Avenue 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25410,Roads,Completed,NN-ADYAR,179,1376000,"Strengthening of road with Bitumen Course by using Paver finisher at Tansi nagar 2ND Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25416,Roads,Completed,NN-ADYAR,179,904000,"Strengthening of road with Bitumen Course by using Paver finisher at Tansi nagar18th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25419,Roads,Completed,NN-ADYAR,179,317000,"Strengthening of road with Bitumen Course by using Paver finisher at Bethel Avenue 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25421,Roads,Completed,NN-ADYAR,179,1006000,"Strengthening of road with Bitumen Course by using Paver finisher at Balamurugan Nagar 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25428,Roads,Completed,NN-ADYAR,179,852000,"Strengthening of road with Bitumen Course by using Paver finisher at Pillaiyar Koil Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25430,Roads,Completed,NN-ADYAR,179,1389000,"Strengthening of road with Bitumen Course by using Paver finisher at V.G.P. Selva Nagar 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25432,Roads,Completed,NN-ADYAR,179,596000,"Strengthening of road with Bitumen Course by using Paver finisher at Bhuvaneswari Nagar 3rd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25435,Roads,Completed,NN-ADYAR,179,1743000,"Strengthening of road with Bitumen Course by using Paver finisher at Bethel Avenue Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25437,Roads,Completed,NN-ADYAR,179,272000,"Strengthening of road with Bitumen Course by using Paver finisher at Anna Nagar Extn 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25439,Roads,Completed,NN-ADYAR,179,404000,"Strengthening of road with Bitumen Course by using Paver finisher at Anna Nagar Extn 3rd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25441,Roads,Completed,NN-ADYAR,179,655000,"Strengthening of road with Bitumen Course by using Paver finisher at Amirtham Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25447,Roads,Completed,NN-ADYAR,179,280000,"Strengthening of road with Bitumen Course by using Paver finisher at Anna Nagar Extn 2nd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25451,Roads,Completed,NN-ADYAR,179,706000,"Strengthening of road with Bitumen Course by using Paver finisher at Mahaveer Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25477,Roads,Completed,NN-ADYAR,179,1435000,"Strengthening of road with bitumen concrete by using Paber finisher at V.G.P. Selva Nagar Extn 4th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25480,Roads,Completed,NN-ADYAR,179,1289000,"Strengthening of road with bitumen concrete by using Paver finisher at V.G.P. Selva Nagar Extn 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25481,Roads,Completed,NN-ADYAR,179,1413000,"Strengthening of road with bitumen concrete by using Paber finisher at V.G.P. Selva Nagar Extn 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25485,Roads,Completed,NN-ADYAR,179,1771000,"Strengthening of road with Bitumen Course by using Paver finisher at V.G.P. Selva Nagar 1st Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25564,Roads,Completed,NN-ADYAR,179,923000,"Strengthening of road with bitumen course by using paver finisher at V.G.P. Selva Nagar Extension in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25567,Roads,Completed,NN-ADYAR,179,295000,"Strengthening of road with bitumen course by using paver finisher at Anaga Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25569,Roads,Completed,NN-ADYAR,179,148000,"Strengthening of road with bitumen course by using paver finisher at Tansi Nagar 6th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25570,Roads,Completed,NN-ADYAR,179,243000,"Strengthening of road with bitumen course by using paver finisher at Thiruvalluvar Street (Dhandeeswaram Nagar) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25571,Roads,Completed,NN-ADYAR,179,403000,"Strengthening of road with bitumen course by using paver finisher at Dhandeeswaram Nagar 7th Avenue West in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25572,Roads,Completed,NN-ADYAR,179,2269000,"Strengthening of road with bitumen course by using paver finisher at V.G.P. Selva Nagar Extn 3rd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2014-15,2016-17 BR/2014-15/30076,Roads,Completed,BR-Bus Route Roads,180,50325000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at CSIR Road from the junction of Rajiv Gandhi Salai to the Junction of Mahatma Gandhi Nagar road -in Dn-180 Zone - 13,Grants,13,2014-15,2016-17 L/2014-15/6730,Electrical,Completed,L-Electrical,180,3210000,"CONVERSION OF 350 NOS OF 70W S.V.L FITTING TO 40-50W L.E.D FITTING AT M.G NAGAR, THANTAHI PERIYAR NAGAR, BHARATHI NAGAR, M.G.R NAGAR, KANAGAM AT THARAMANI IN DIV-180, ZONE-XIII",Own Sources,13,2014-15,2016-17 L/2014-15/6738,Electrical,Completed,L-Electrical,180,4264000,"CONVERSION OF 136 NOS OF 250W S.V.L FITTING TO 150-165W L.E.D FITTING AT L.B ROAD, WEST AVENUE, PAMMAL NALLA THAMBI STREET, THARAMANI BUS STAND AT THARAMANI IN DIV-180, ZONE-XIII",Own Sources,13,2014-15,2016-17 L/2014-15/6741,Electrical,Completed,L-Electrical,180,4860000,"CONVERSION OF 155 NOS OF 250W S.V.L FITTING TO 150-165W L.E.D FITTING AT THARAMANI 100FT ROAD IN DIV-180, ZONE-XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/1368,Buildings,Completed,NN-ADYAR,180,255000,"Providing water supply arrangement and Drainage arrangement to P.C. at Tharamani Bus Stand in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/15114,Buildings,Completed,NN-ADYAR,180,371000,"Repairs to Group Bins at Various street in Dn-180, Unit-39, Zone-13",Own Sources,13,2014-15,2017-18 NN/2014-15/24850,Roads,Completed,NN-ADYAR,180,3605000,"LAYING CEMENT CONCRETE ROAD AT KANAGAM - PERIYAR NAGAR IN DIVISION - 180, UNIT - 39, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/24855,Roads,Completed,NN-ADYAR,180,1743000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Pillaiyar Koil Street kanagam in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24866,Roads,Completed,NN-ADYAR,180,1005000,"LAYING CEMENT CONCRETE ROAD AT THANTHAI PERIYAR NAGAR - KARUNANIDHI II STREET IN DIVISION - 180, UNIT - 39, ZONE - XIIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24871,Roads,Completed,NN-ADYAR,180,2258000,"Relaying the road with DBMC1(N) & BCCMP 30mm thick using by Paver finisher at Karunanidhi 1st street T.P Nagar in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24872,Roads,Completed,NN-ADYAR,180,1998000,"LAYING CEMENT CONCRETE ROAD AT CHOLAMANNAN STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24874,Roads,Completed,NN-ADYAR,180,1211000,"LAYING CEMENT CONCRETE ROAD AT M.G NAGAR - T.K.KABALI STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24877,Roads,Completed,NN-ADYAR,180,1091000,"Laying cement concrete road at Pillaiyar Koil Street M.G. Nagar (From T.K. Kabali Street To Anna Street) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24881,Roads,Completed,NN-ADYAR,180,719000,"Laying cement concrete road at Mariamman Koil Street M.G. Nagar in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24887,Roads,Completed,NN-ADYAR,180,424000,"Relaying of road at Kamaraj nagar west I street IN DIVISION - 180, UNIT - 39, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24891,Roads,Completed,NN-ADYAR,180,1563000,"Relaying the road with DBMC1(N) & BCCMP1 30mm thick using by Paver finisher at Anna Street kanagam in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24898,Roads,Completed,NN-ADYAR,180,1325000,"LAYING CEMENT CONCRETE ROAD AT ERIKARAI STREET & LANE IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24901,Roads,Completed,NN-ADYAR,180,908000,"LAYING CEMENT CONCRETE ROAD AT TARAMANI - ARANAGANNAL STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24904,Roads,Completed,NN-ADYAR,180,3360000,"LAYING CEMENT CONCRETE ROAD AT TARAMANI - THIRUVALLUVAR STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/24906,Roads,Completed,NN-ADYAR,180,1478000,"LAYING CEMENT CONCRETE ROAD AT TARAMANI - RADHAKRISHNAN STREET & SANNATHI STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25304,Roads,Completed,NN-ADYAR,180,593000,"LAYING CEMENT CONCRETE ROAD AT M.G NAGAR - KARUNANIDHI STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25456,Roads,Completed,NN-ADYAR,180,884000,"LAYING CEMENT CONCRETE ROAD AT KAMBER STREET & TARAMANI - M.G.R STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25457,Roads,Completed,NN-ADYAR,180,534000,"Relaying the Cement Concrete road with M30 Grade at Perumal koil 1st cross street (45.00 X .4.00) and South Tharamani road (80.00 X 3.50) Tharamani in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25459,Roads,Completed,NN-ADYAR,180,954000,"LAYING CEMENT CONCRETE ROAD AT M.G.NAGAR - ANTHONIAR KOIL STREET & KIRUPALANI STREET IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25460,Roads,Completed,NN-ADYAR,180,416000,"Relaying the Cement Concrete road with M30 Grade at Mosque cross street (45.00 X3.00) and Ramar Koil 1st street (70.00 X 3.00) M.G. Nagar in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25461,Roads,Completed,NN-ADYAR,180,593000,"Relaying the Cement Concrete road with M30 Grade at M.G.R Street M.G Nagar in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25462,Roads,Completed,NN-ADYAR,180,1137000,"Relaying the Cement Concrete road with M30 Grade at Kattabomman 2nd to 5th Lane Tharamani in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25463,Roads,Completed,NN-ADYAR,180,1137000,"Relaying the Cement Concrete road with M30 Grade at Batwari 1st and 2nd street M.G. Nagar in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25464,Roads,Completed,NN-ADYAR,180,1568000,"Relaying the Cement Concrete road with M30 Grade at Kattabomman cross street Kanagam in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25465,Roads,Completed,NN-ADYAR,180,824000,"LAYING CEMENT CONCRETE ROAD AT JAYANTHI PERIYAR NAGAR - AMBEDKAR STREET & THIRUVANMIYUR CANAL LANE IN DIVISION - 180, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25466,Roads,Completed,NN-ADYAR,180,1092000,"Relaying the Cement Concrete road with M30 Grade at Nehru Street Kanagam ( From Pillaiyar koil street to Bajanai koil street -Portion) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25478,Roads,Completed,NN-ADYAR,180,901000,"Relaying the Cement Concrete road with M30 Grade at Kattabomman 1st lane and Main road Tharamani in Dn-180, Unit-39, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/8881,Roads,Completed,NN-ADYAR,180,316000,"Supply, Installation of Smart Toilet (Disabled) with free maintenance for three Years at Thiruvanmiyur Bus Stand premises in Dn-182, Unit-38, Zone-13",Own Sources,13,2014-15,2016-17 NN/2014-15/8885,Roads,Completed,NN-ADYAR,180,316000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at Thiruvanmiyur Bus Stand premises in Dn-182, Unit-38, Zone-13",Own Sources,13,2014-15,2016-17 NN/2014-15/8889,Roads,Completed,NN-ADYAR,180,316000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at Thiruvanmiyur Bus Stand premises in Dn-182, Unit-38, Zone-13",Own Sources,13,2014-15,2016-17 NN/2014-15/9287,Buildings,Completed,NN-ADYAR,180,549000,"Construction of Kitchen Shed and Prayar Hall CHSS at Bharathiyar Street in Dn-180, Unit-39, Zone-13",Own Sources,13,2014-15,2017-18 S/2014-15/12349,Footpath,Completed,BR-Bus Route Roads,180,17100000,Forming footpath at Kalki Krishnamoorthy Salai from the junction of West Avenue Road to the junction of lattice bridge in Dn 180 at Zone 13,Grants,13,2014-15,2016-17 S/2014-15/12449,Footpath,Completed,BR-Bus Route Roads,180,22900000,"FORMING FOOTPATH AT WEST AVENUE FROM THE JUNCTION OF RAJIV GANDHI SALAI TO KALKI KRISHNAMOORTHY SALAI IN DN-180,ZONE-13.",Grants,13,2014-15,2016-17 L/2014-15/6749,Electrical,Completed,L-Electrical,181,1926000,"CONVERSION OF 210 NOS 70W S.V.L FITTING TO 40-50W LED FITTING AT ODAIKUPPAM, PARI STREET, JAYARAM STREET, VEMBULIAMMANA KOIL STREET, CHELLAPERUAMAL KOIL STREET, SIVAGAMIPURAM, SUBRAMANIM COLONY AND LIC COLONY AT THIRUVANMIYUR IN DIV-181, ZONE-XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/11703,Roads,Completed,NN-ADYAR,181,192000,LAYING OF INTERLOCKING PAVER BLOCKS IN CEMENT CONCRETE ROAD AT C.G.E COLONY 1ST STREET IN DIVISION-181 UNIT-38 ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/11706,Roads,Completed,NN-ADYAR,181,261000,LAYING OF INTERLOCKING PAVER BLOCKS IN CEMENT CONCRETE ROAD AT C.G.E COLONY 2ND STREET IN DIVISION-181 UNIT-38 ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/11709,Roads,Completed,NN-ADYAR,181,437000,LAYING OF INTERLOCKING PAVER BLOCKS IN CEMENT CONCRETE ROAD AT C.G.E COLONY 3RD STREET IN DIVISION-181 UNIT-38 ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/13590,Roads,Completed,NN-ADYAR,181,636000,"PROVIDING & LAYING CEMENT CONCRETE SPEED BREAKERS AT RUKMANI STREET, NEDUNCHEZHILAN STREET AND M.G.R. STREET IN DIVISION-181 UNIT-38 ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/19802,Buildings,Completed,NN-ADYAR,181,810800,PROVIDING WATER SUPPLY AND IMROVEMENT WORKSTO COROPORTION MIDDLE SCHOOL AT THIRUVANMIYUR KUPPAM BEACH ROAD AT THIRUVANMIYUR IN DIVISION 181.,Own Sources,13,2014-15,2016-17 NN/2014-15/19840,Buildings,Completed,NN-ADYAR,181,912000,"IMPROVEMENTS AND REPAIRS TO GANGAI PARK AT GANGAI STREET,THIRUVANMIYUR DIVISION 181",Own Sources,13,2014-15,2016-17 NN/2014-15/24485,Roads,Completed,NN-ADYAR,181,967000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREETS IN DN-181,UNIT- 38 ,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24929,Roads,Completed,NN-ADYAR,181,1739000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Valmiki Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24932,Roads,Completed,NN-ADYAR,181,681000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Subramaniyan Colony 2nd Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24933,Roads,Completed,NN-ADYAR,181,866000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Subramaniyan Colony 1st Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24934,Roads,Completed,NN-ADYAR,181,1099000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Kamaraj Nagar 2nd East Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24935,Roads,Completed,NN-ADYAR,181,972000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Subramaniyan Colony in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24937,Roads,Completed,NN-ADYAR,181,2030000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Pillaiyar Koil Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24953,Roads,Completed,NN-ADYAR,181,590000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Pari Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24955,Roads,Completed,NN-ADYAR,181,1504000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at T.M. Maistry Street and Navarathinam Lane in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24958,Roads,Completed,NN-ADYAR,181,2795000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Mahalakshmi koil street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24959,Roads,Completed,NN-ADYAR,181,1155000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Jayaram Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24960,Roads,Completed,NN-ADYAR,181,1055000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Besant Nagar 30th cross street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24961,Roads,Completed,NN-ADYAR,181,2338000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Besant Nagar 29th cross street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/24962,Roads,Completed,NN-ADYAR,181,553000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Ashtalakshmi Garden 1st street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/24966,Roads,Completed,NN-ADYAR,181,2030000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Anna street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25018,Roads,Completed,NN-ADYAR,181,2403000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Vembuliamman Koil Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25021,Roads,Completed,NN-ADYAR,181,1040000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Vaigai Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25022,Roads,Completed,NN-ADYAR,181,2737000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Kavery Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25026,Roads,Completed,NN-ADYAR,181,1431000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Malavika Avenue in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25028,Roads,Completed,NN-ADYAR,181,972000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Kamaraj Nagar (Marudeeswarar Nagar) in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/25030,Roads,Completed,NN-ADYAR,181,4942000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Coastal road in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25033,Roads,Completed,NN-ADYAR,181,1123000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Beach Road (Gandhigramam School) in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25035,Roads,Completed,NN-ADYAR,181,1403000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Arundale Beach 3rd street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25036,Roads,Completed,NN-ADYAR,181,1255000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Arundale Beach Road in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25037,Roads,Completed,NN-ADYAR,181,3593000,"Relaying the road with DBMC1 & BCCMP 40mm thick using by Paver finisher at Muthulakshmi Salai in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/26040,Roads,Completed,NN-ADYAR,181,1441000,"LAYING PILLAIYAR KOIL STREET LANE IN DIVISION - 181, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26043,Roads,Completed,NN-ADYAR,181,994000,"LAYING CC ROAD AT VALMIGI STREET IN DIVISION - 181, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/28914,Buildings,Completed,NN-ADYAR,181,998000,"Construction of NNMP Shed No: 999 at Valmiki Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/29324,Roads,Completed,NN-ADYAR,181,141000,LAYING OF CEMENT CONCRETE ROAD USING M40 GRADE CONCRETE AT RAJU STREET IN DIVISION-181 UNIT-38 ZONE-13.,Own Sources,13,2014-15,2016-17 NN/2014-15/29325,Buildings,Completed,NN-ADYAR,181,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.M.S AT (GANDHI GRAMAM) LAKSHMI PURAM IN DN-181,UNIT-38,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/29350,Buildings,Completed,NN-ADYAR,181,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.P.S AT THIRUVANMIYUR KUPPAM BEACH ROAD IN DN-181,UNIT-38,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/29351,Buildings,Completed,NN-ADYAR,181,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.P.S AT OODAIKUPPAM IN DN-181,UNIT-38,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/4175,Buildings,Completed,NN-ADYAR,181,891500,"Improvements to GYM at Valmiki Street in Dn-181, Unit-38, Zone-13",Own Sources,13,2014-15,2017-18 NN/2014-15/7687,Buildings,Completed,NN-ADYAR,181,735000,"IMPROVEMENTS TO THE TEACHER'S REST ROOM AT GANDHIGRAMAM CMS SCHOOL IN DN-181,UNIT-38,ZONE-13",Own Sources,13,2014-15,2017-18 BR/2014-15/30035,Roads,Completed,BR-Bus Route Roads,182,3805000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Kamaraj Nagar 22nd East Street from the junction of ECR to the junction of South Avenue road in Dn-182, Zone - 13",Grants,13,2014-15,2017-18 L/2014-15/6754,Electrical,Completed,L-Electrical,182,4233000,"CONVERSION OF 135 NOS OF 250W S.V.L FITTING TO 150-165W LED FITTING AT SOUTH MADA ST, EAST MADA ST, BALAKRISHNA ST, SEA WORLD DRIVE ROAD AND 3RD AVENUE ROAD AT THIRUVANMIYUR IN DIV182, ZONE-XIII",Own Sources,13,2014-15,2016-17 L/2014-15/6757,Electrical,Completed,L-Electrical,182,3485000,"CONVERSION OF 70W S.V.L FITTING TO 40-50W LED FITTING AT KANAPPA NAGAR EXTN, KAMARAJ NAGAR, BARADIDASAN CROSS STREETS, AIBEYA NAGAR AT THIRUVANMIYUR IN DIV-182, ZONE-XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/10740,Buildings,Completed,NN-ADYAR,182,628000,PROVIDING SMART CLASS ROOM IN FIRST FLOOR C BLOCK IN CHSS AT BHARATHIDASAN STREET IN DIVISION-182 UNIT-38 ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/10884,Buildings,Completed,NN-ADYAR,182,760000,"Improvements to Toilet Block at Ground floor in CHSS B Block Bharathidasan Street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/13551,Buildings,Completed,NN-ADYAR,182,987000,"CONSTRUCTION OF COMPOUND WALL AT THIRUVALLUVAR NAGAR 1ST AVENUE DIVISION-182,UNIT,38, ZONE-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/17740,Buildings,Completed,NN-ADYAR,182,804000,CONSTRUCTION OF SUMP AND WATER SUPPLY ARRANGEMENT TO AMMA CANTEEN THIRUVALLUVAR NAGAR 1ST AVENUE THIRUVANMIYUR IN DIVISION-182 UNIT-38 ZONE-13,Own Sources,13,2014-15,2017-18 NN/2014-15/17751,Buildings,Completed,NN-ADYAR,182,998000,CONSTRUCTION OF DINNING HALL AND WASHING AREA AT AMMA CANTEEN THIRUVALLUVAR NAGAR 1ST AVENUE THIRUVANMIYUR IN DIVISION-182 UNIT-38 ZONE-13,Own Sources,13,2014-15,2018-19 NN/2014-15/19034,Buildings,Completed,NN-ADYAR,182,453000,"PROPOSED ROAD CLEANING CONSERVANCY WORKERS NAME BOARD DETAILS AT VARIOUS STREETS IN DN-182, UNIT-38, ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24483,Roads,Completed,NN-ADYAR,182,965000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREETS IN DN-182,UNIT- 38 ,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/24484,Parks,Completed,NN-ADYAR,182,998000,"Improvement to Park at Thiruvalluvar Nagar 1st Avenue in Dn-182, Unit-38, Zone-13.",Own Sources,13,2014-15,2016-17 NN/2014-15/25845,Roads,Completed,NN-ADYAR,182,1664000,"RELAYING OF ROAD AT KAMRAJ NAGAR X TO XIII EAST STREETS IN DIVISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25849,Roads,Completed,NN-ADYAR,182,1640000,"RELAYING OF ROAD AT KAMARAJ NAGAR EAST XIV TO XVII STREETS IN DIVISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25857,Roads,Completed,NN-ADYAR,182,1971000,"RELAYING OF ROAD AT KAMARAJ NAGAR EAST XVIII TO XX STREETS IN DIVISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25859,Roads,Completed,NN-ADYAR,182,2450000,"RELAYING OF ROAD AT KAMARAJ NAGAR EAST XXI TO XXVI STREETS IN DIVISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25921,Roads,Completed,NN-ADYAR,182,1865000,"RELAYING OF ROADS AT II SEAWARD ROAD IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25924,Roads,Completed,NN-ADYAR,182,2845000,"RELAYING OF ROADS AT III & IV SEAWARD ROAD (PART) IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25932,Roads,Completed,NN-ADYAR,182,1881000,"RELAYING OF ROADS AT IV SEAWARD ROAD EXTN, IV SEA WARD ROAD I STREET, IV SEAWARD ROAD LANE IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25948,Roads,Completed,NN-ADYAR,182,1592000,"RELAYING OF ROADS AT V EAST STREET KAMARAJ NAGAR, V EAST STREET KAMARAJ NAGAR I, II & III LANES IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25949,Roads,Completed,NN-ADYAR,182,1099000,"RELAYING OF ROADS AT VII EAST STREET KAMARAJ NAGAR AND LANE AND IX EAST STREET KAMARAJ NAGAR IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25952,Roads,Completed,NN-ADYAR,182,4506000,"RELAYING OF ROADS AT BALAKRISHNAN STREET IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25955,Roads,Completed,NN-ADYAR,182,2131000,"RELAYING OF ROADS AT BHARATHY NAGAR I TO VIII STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25965,Roads,Completed,NN-ADYAR,182,2338000,"RELAYING OF ROADS AT P.T.C COLONY I TO V STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25970,Roads,Completed,NN-ADYAR,182,1702000,"RELAYING OF ROADS AT NEW BEACH ROAD IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25973,Roads,Completed,NN-ADYAR,182,1489000,"RELAYING OF ROADS AT RAJAGOPALAN I STREET, RAJAJI NAGAR I & II STREET, RAJAJI NAGAR LANE IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25981,Roads,Completed,NN-ADYAR,182,1281000,"RELAYING OF ROADS AT BALAKRISHNA NAGAR LANE & GANESH NAGAR IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25986,Roads,Completed,NN-ADYAR,182,2520000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR IX CROSS STREET, XII TO XIV CROSS STREETS, 15, 17, 19TH CROSS STREETS, 30TH CROSS STREET, 54TH CROSS STREET & LANE, 55TH CROSS STREET, 56TH CROSS STREET IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/25990,Roads,Completed,NN-ADYAR,182,2537000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR I AVENUE (PART) IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2016-17 NN/2014-15/25995,Roads,Completed,NN-ADYAR,182,1669000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR XX, XXII, XXIV, XXV, XXVII CROSS STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26000,Roads,Completed,NN-ADYAR,182,1769000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR II MAIN ROAD , II & III CROSS STREET, 34TH, 37TH CROSS STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26004,Roads,Completed,NN-ADYAR,182,1556000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR III MAIN ROAD, 41 TO 44 CROSS STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26006,Roads,Completed,NN-ADYAR,182,1767000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR IV CROSS STREET AND 45 TO 49 CROSS STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26009,Roads,Completed,NN-ADYAR,182,1348000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR IV MAIN ROAD IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26011,Roads,Completed,NN-ADYAR,182,1602000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR 5,6,8, 50,52,53RD CROSS STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26013,Roads,Completed,NN-ADYAR,182,1102000,"RELAYING OF ROADS AT THIRUVALLUVAR NAGAR IX CROSS STREETS IN DIVIISION - 182, ZONE - XIII",Own Sources,13,2014-15,2017-18 NN/2014-15/26047,Roads,Completed,NN-ADYAR,182,583000,"Laying of cement concrete road at Bharathidasan 1st Street in Division-182,Unit-38,Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/26055,Roads,Completed,NN-ADYAR,182,1294000,"Laying of cement concrete road at Sakthi nagar 1st Street in Division-182,Unit-38,Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/26058,Roads,Completed,NN-ADYAR,182,1714000,"Laying of cement concrete road at Sakthi nagar 2nd Street in Division-182,Unit-38,Zone-13.",Own Sources,13,2014-15,2017-18 NN/2014-15/29274,Buildings,Completed,NN-ADYAR,182,1014521,"OUT SOURCING OF PRIVATE CONSERVANCY IN C.H..S.S AT BHARADHIDASAN STREET THIRUVANMIYUR IN DN-182,UNIT-38,ZONE-13",Own Sources,13,2014-15,2017-18 NN/2014-15/3618,Buildings,Completed,NN-ADYAR,182,360000,"Construction of Sump and Toilet Block in Health Post at 8th East Street, Kamaraj Nagar in Dn 182, Unit 40, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/4577,Buildings,Completed,NN-ADYAR,182,1342000,"Improvements to R.J.C. (South) Office at Chennai Higher Secondary School, Bharathidasan Street in Dn 182, Unit 38, Zone 13.",Own Sources,13,2014-15,2016-17 NN/2014-15/5376,Roads,Completed,NN-ADYAR,182,999000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREETS IN DN-182,UNIT- 38 ,ZONE-13",Own Sources,13,2014-15,2016-17 NN/2014-15/9473,Footpath,Completed,NN-ADYAR,182,955000,IMPROVEMENTS TO FOOTPATH AT 1ST SEAWARD ROAD AND THIRUVALLUVAR NAGAR 3RD AVENUE IN DIVISION-182 UNIT-38 ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/9944,Footpath,Completed,NN-ADYAR,182,990000,IMPROVEMENTS TO THE FOOTPATH AT VARIOUS STREET IN DIVISION-182 UNIT-38 ZONE-13,Own Sources,13,2014-15,2016-17 NN/2014-15/9948,Buildings,Completed,NN-ADYAR,182,955000,IMPROVEMENTS TO THE FOOTPATH AT 2ND AVENUE AND JOURNALIST COLONY (CITY LIMIT ROAD) IN DIVISION-182 UNIT-38 ZONE-13,Own Sources,13,2014-15,2016-17 NP/2014-15/15080,Storm Water Drain,Completed,NP-PERUNGUDI,183,899000,"CONSTRUCTION OF SIDE DRAIN AT VENGATESAPURAM 9TH STREET TO 'B' CANAL IN 183,UNIT41,ZONE14",Own Sources,14,2014-15,2016-17 NP/2014-15/19888,Buildings,Completed,NP-PERUNGUDI,183,252000,"providing dust bin platform in various streets and providing ramp in coc buildings at various places in dn 183,unit41,zone14",Own Sources,14,2014-15,2017-18 NP/2014-15/20989,Storm Water Drain,Completed,NP-PERUNGUDI,183,635000,"improvements to side drain at swaminathan nagar 2nd street in division-183 unit41,zone14",Own Sources,14,2014-15,2016-17 NP/2014-15/20995,Storm Water Drain,Completed,NP-PERUNGUDI,183,627000,"CONSTRUCTION OF SIDE DRAIN AT SANGAM COLONY 2ND CROSS STREET IN DIVISION-183,UNIT41,ZONE14",Own Sources,14,2014-15,2016-17 NP/2014-15/20996,Storm Water Drain,Completed,NP-PERUNGUDI,183,684000,"CONSTRUCTION OF SIDE DRAIN AT SANGAM COLONY1ST CROSS STREET IN DIVISION-183,UNIT41,ZONE14",Own Sources,14,2014-15,2017-18 NP/2014-15/20998,Storm Water Drain,Completed,NP-PERUNGUDI,183,955000,"CONSTRUCTION OF SIDE DRAIN AT SANGAM COLONY MAIN ROAD IN DIVISION-183,UNIT41,ZONE14",Own Sources,14,2014-15,2016-17 NP/2014-15/21198,Storm Water Drain,Completed,NP-PERUNGUDI,183,870000,"construction of side drain at elango nagar from gandhi street to amman koil in division-183,unit-41,zone14",Own Sources,14,2014-15,2016-17 NP/2014-15/24319,Roads,Completed,NP-PERUNGUDI,183,1516000,"LAYING CEMENT CONCRETE ROAD AT KUPPAM GANDHI STREET IN DIVISION-183, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24326,Roads,Completed,NP-PERUNGUDI,183,372000,"LAYING CEMENT CONCRETE ROAD AT KUPPAM GANDHI 1ST CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24328,Roads,Completed,NP-PERUNGUDI,183,557000,"LAYING CEMENT CONCRETE ROAD AT KUPPAM GANDHI 2ND CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24330,Roads,Completed,NP-PERUNGUDI,183,354000,"LAYING CEMENT CONCRETE ROAD AT KUPPAM GANDHI 3RD CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/11769,Storm Water Drain,Completed,NP-PERUNGUDI,184,928000,CONSTRUCTION OF SWD OF SIZE 900X900MM AT ANNANEDUNSALAI CROSS STREET (NEAR LAKE VIEW) IN DN 184 UT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/1754,Storm Water Drain,Completed,NP-PERUNGUDI,184,998000,CONSTRUCTION OF CULVERT AND SIDE DRAIN AT CBI COLONY 1ST MAIN ROAD (JN OF LAXMAN SALAI TO CBI COLONY 1ST CROSS STREET),Own Sources,14,2014-15,2017-18 NP/2014-15/20220,Storm Water Drain,Completed,NP-PERUNGUDI,184,986000,IMPROVEMENTS TO SIDE DRAIN AT KOTHANDARAMAN NAGAR 1ST TO 4TH CROSS STREET IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/20221,Storm Water Drain,Completed,NP-PERUNGUDI,184,987000,IMPROVEMENTS TO SIDE DRAIN AT KOTHANDARAMAN NAGAR MAIN ROAD IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/20428,Storm Water Drain,Completed,NP-PERUNGUDI,184,992000,"PROVIDING SPEED BREAKER AT RAMAPPANAGAR MAIN ROAD JN OF 1ST CROSS AND 2ND CROSS ,RAMAPPANAGAR JN OF PILLAYAR KOIL STREET AND JN OF CHURCH ROAD,CHURCH ROAD NEAR NILGRIS,THIRUVALLUVAR STREET JN OF MGR SALAI AND JN OF TELEPHONE NAGAR 11TH CROSS ,TELEPHONE NAGAR 16TH CROSS JUNCTION,ERIKKARAI SALAI JN OF SCHOOL ROAD,PILLAYARKOIL STREET JN OF VEERASAMY SALAI AND ANNANEDUNCHALAI NEAR LAKE VIEW IN DIV 184 UNIT 41 ZONE 14",Own Sources,14,2014-15,2017-18 NP/2014-15/15480,Storm Water Drain,Completed,NP-PERUNGUDI,185,997000,IMPROVEMENTS TO THE SIDE DRAIN AT MAHATHMA GANDHI 3rd STREET IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2014-15,2016-17 NP/2014-15/16970,Storm Water Drain,Completed,NP-PERUNGUDI,185,998000,IMPROVEMENTS TO SIDE DRAIN AT THIRUVALLUVAR STREET AND THIRU-VI-KA STREET(KARUNANIDHI CHOZAN NAGAR) EAST SIDE IN DIV 185 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/16971,Storm Water Drain,Completed,NP-PERUNGUDI,185,994000,IMPROVEMENT TO SIDE DRAIN AT THIRU-VI-KA STREET (KARUNANIDHI CHOZAN NAGAR) WEST SIDE IN DIV 185 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/20952,Buildings,Completed,NP-PERUNGUDI,185,630000,CONSTRUCTION OF EB ROOM AND TOILET AT DIVSION OFFICE IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2014-15,2016-17 NP/2014-15/21697,Buildings,Completed,NP-PERUNGUDI,185,999000,"IMPROVEMENTS TO SIDE DRAIN AT MGR NAGAR 1ST CROSS STREET IN DIVISION-185,UNIT-41,ZONE-14.",Own Sources,14,2014-15,2016-17 NP/2014-15/22724,Roads,Completed,NP-PERUNGUDI,185,651000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER AT PALKALAINAGAR 1st CR. STREET IN DN-185, UNIT-41,ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22727,Roads,Completed,NP-PERUNGUDI,185,612200,STRENGTING OF LAYING B.T ROAD AT PALKALAI NAGAR 2ND C.R STREET IN DIN 185 U 41 ZONE14.,Own Sources,14,2014-15,2016-17 NP/2014-15/22728,Roads,Completed,NP-PERUNGUDI,185,613000,STRENGTING OF LAYING B.T ROAD WITH PAVER FINISH AT PALKALAI NAGAR 3RD C.R STREET IN DIV 185 U 41 Z-14,Own Sources,14,2014-15,2016-17 NP/2014-15/22731,Roads,Completed,NP-PERUNGUDI,185,1073000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 5TH CROSS STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22732,Roads,Completed,NP-PERUNGUDI,185,1150000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH ATPALKALAI NAGAR 6TH C.R STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22733,Roads,Completed,NP-PERUNGUDI,185,474952,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PLKALAI NAGAR 7TH C.R STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22734,Roads,Completed,NP-PERUNGUDI,185,1262053,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 8TH C.R STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22735,Roads,Completed,NP-PERUNGUDI,185,653000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 9TH CROSS STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22738,Roads,Completed,NP-PERUNGUDI,185,968000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 1ST LINK 1ST C.R IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22745,Roads,Completed,NP-PERUNGUDI,185,996000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 4TH C.R STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22746,Roads,Completed,NP-PERUNGUDI,185,1141000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 4TH LINK STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22747,Roads,Completed,NP-PERUNGUDI,185,1141000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 5TH LINK STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22749,Roads,Completed,NP-PERUNGUDI,185,1142000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 6TH LINK STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22750,Roads,Completed,NP-PERUNGUDI,185,1210000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR AVENUE IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22751,Roads,Completed,NP-PERUNGUDI,185,1231000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 1STCROSS AVENUE IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22752,Roads,Completed,NP-PERUNGUDI,185,871000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 2ND CROSS AVENUE IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22753,Roads,Completed,NP-PERUNGUDI,185,889000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 3RD CROSS AVENUE IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22754,Roads,Completed,NP-PERUNGUDI,185,953000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 4TH CROSS AVENUE IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22755,Roads,Completed,NP-PERUNGUDI,185,953000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 5TH CROSS AVENUE IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22756,Roads,Completed,NP-PERUNGUDI,185,885000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 6TH CROSS AVENUE IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22764,Roads,Completed,NP-PERUNGUDI,185,1136000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Palakali nagar 4TH LINK 1ST CROSS STREET ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24341,Roads,Completed,NP-PERUNGUDI,185,2246000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH ATPART 3 VGP 1st MAIN ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24357,Roads,Completed,NP-PERUNGUDI,185,754000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Kambar street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24361,Roads,Completed,NP-PERUNGUDI,185,994000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT M.K.Stalin IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24372,Roads,Completed,NP-PERUNGUDI,185,1300000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT OORATCHI SALALI IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24374,Roads,Completed,NP-PERUNGUDI,185,1353000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT BHARATHIYAR STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24375,Roads,Completed,NP-PERUNGUDI,185,1505000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT THIRUVALLUVAR STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24377,Roads,Completed,NP-PERUNGUDI,185,825000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT POONGA STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24389,Roads,Completed,NP-PERUNGUDI,185,798000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT POONGA 1st CR STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24409,Roads,Completed,NP-PERUNGUDI,185,1016000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT POONGA 2nd CR STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24421,Roads,Completed,NP-PERUNGUDI,185,785000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT POONGA 3rd CR STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24432,Roads,Completed,NP-PERUNGUDI,185,758000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT MUTHUMARIAMMAN KOVIL STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24441,Roads,Completed,NP-PERUNGUDI,185,758000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT MUTHUMARIAMMAN KOVIL 1st STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24443,Roads,Completed,NP-PERUNGUDI,185,799000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT MUTHUMARIAMMAN KOVIL 2nd STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24445,Roads,Completed,NP-PERUNGUDI,185,759000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT MUTHUMARIAMMAN KOVIL 3rd STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24446,Roads,Completed,NP-PERUNGUDI,185,589000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT MUTHUMARIAMMAN KOVIL 4th STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24450,Roads,Completed,NP-PERUNGUDI,185,828000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT MUTHUMARIAMMAN KOVIL 5th STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24451,Roads,Completed,NP-PERUNGUDI,185,624000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT MUTHUMARIAMMAN KOVIL 6th STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24456,Roads,Completed,NP-PERUNGUDI,185,6948000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Ambedhkar Salai IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24457,Roads,Completed,NP-PERUNGUDI,185,761000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Ambedkar street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24459,Roads,Completed,NP-PERUNGUDI,185,829000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Kolavizhiamman Nagar Nagar IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24461,Roads,Completed,NP-PERUNGUDI,185,421000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Kolavizhiamman Nagar 1st street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24462,Roads,Completed,NP-PERUNGUDI,185,762000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Kolavizhiamman Nagar 2ND street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24463,Roads,Completed,NP-PERUNGUDI,185,680000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT Kolavizhiamman Nagar 3rd street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24464,Roads,Completed,NP-PERUNGUDI,185,762000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT JEEVARATHINAM 1st CR. street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24465,Roads,Completed,NP-PERUNGUDI,185,1346000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT JEEVARATHINAM 2nd CR. street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24466,Roads,Completed,NP-PERUNGUDI,185,1137000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT JEEVARATHINAM 3rd CR. street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24467,Roads,Completed,NP-PERUNGUDI,185,1138000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT JEEVANANDHAM STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24468,Roads,Completed,NP-PERUNGUDI,185,1224000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT JEEVANANDHAM 1st Cr. STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24570,Roads,Completed,NP-PERUNGUDI,185,1037000,"Strengthening and Laying of BT Road with Paver at Palkalai Nagar1st link 2nd Cr.st in Dn-185, unit-41, Zone-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24571,Roads,Completed,NP-PERUNGUDI,185,1141000,"Strengthening and Laying of BT Road with Paver at Palkalai Nagar 5TH LINK 1st Cr.st in Dn-185, unit-41, Zone-14",Own Sources,14,2014-15,2016-17 NP/2014-15/24573,Roads,Completed,NP-PERUNGUDI,185,968000,"Strengthening and Laying of BT Road with Paver at Palkalai Nagar 5TH LINK 2nd Cr.st in Dn-185, unit-41, Zone-14",Own Sources,14,2014-15,2016-17 NP/2014-15/27301,Storm Water Drain,Completed,NP-PERUNGUDI,185,957000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT KOLAVILIAMMAN STREET IN DIV 185 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/27311,Storm Water Drain,Completed,NP-PERUNGUDI,185,959000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT KOLAVILLIAMMAN 4TH STREET IN DIV185 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/13020,Buildings,Completed,NP-PERUNGUDI,186,979000,Construction of NNMP shed at Panchayat Office road in Dn 186 unit 41 Zone 14,Own Sources,14,2014-15,2016-17 NP/2014-15/13021,Buildings,Completed,NP-PERUNGUDI,186,769000,Providing water supply and drainage arrangements and Electrical arrangements to NNMP shed and propose construction of multi propose hall at Panchayat Office road in Dn 186 unit 41 Zone 14,Own Sources,14,2014-15,2016-17 NP/2014-15/20432,Roads,Completed,NP-PERUNGUDI,186,993000,"PROVIDING SPEED BREAKER AT THIRUMALAI NAGAR MAIN ROAD,THIRUMALAI NAGAR ANNEX 1ST MAIN ROAD,SCHOOL ROAD,VEERASWAMY SALAI,KAMARAJ 2ND MAIN ROAD,VEERAPANDIYAN KATTABOMBAN STREET,RAJIV NAGAR 1ST MAIN ROAD AND 2ND MAIN ROAD,PANCHAYAT MAIN ROAD AND 3RD LINK ROAD,THIRUMALAINAGAR ANNEX 3RD CROSS AND VARIOUS STREET IN DN 186 UT 41 ZONE 14",Own Sources,14,2014-15,2016-17 NP/2014-15/20446,Buildings,Completed,NP-PERUNGUDI,186,550000,"CONSTUCTION OF BASEMENT AND TOILET FOR CONTAINER WATCHMAN ROOM AT CORPORATION ROAD DUMPING GROUND IN DIVISION-186,UNIT-41,ZONE-14.",Own Sources,14,2014-15,2016-17 NP/2014-15/23026,Storm Water Drain,Completed,NP-PERUNGUDI,186,783000,"IMPROVEMENTS TO THE SIDE DRAIN AT ELIM NAGAR 1ST MAIN ROAD IN DIVISION-186,UNIT-41,ZONE-14.",Own Sources,14,2014-15,2016-17 NP/2014-15/23030,Storm Water Drain,Completed,NP-PERUNGUDI,186,999000,"IMPROVEMENTS TO THE SIDE DRAIN AT THIRUMALAI NAGAR 1ST CROSS STREET IN DIVISION-186,UNIT-41,ZONE-14.",Own Sources,14,2014-15,2016-17 NP/2014-15/25866,Storm Water Drain,Completed,NP-PERUNGUDI,186,999000,IMPROVEMENTS TO SIDE DRAIN AT RAJIV GANDHI 5TH AND 2ND CROSS STREET IN DN-186 UNIT-41 ZONE-14,Own Sources,14,2014-15,2016-17 NP/2014-15/26121,Storm Water Drain,Completed,NP-PERUNGUDI,186,999000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT THIRUMALAI NAGAR 6TH CROSS STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/26126,Storm Water Drain,Completed,NP-PERUNGUDI,186,996000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT KALAIGNAR KARUNANIDHI STREET FROM JN OF MAIN ROAD TO CROSS STREET IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/26134,Storm Water Drain,Completed,NP-PERUNGUDI,186,999000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT RAJIV GANDHI SECOND MAIN ROAD AT NORTH SIDE IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/26138,Storm Water Drain,Completed,NP-PERUNGUDI,186,986000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT GM AVENUE FROM JN OF VEERAPANDI KATTABOMBAN STREET TO END OF THE STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/26139,Storm Water Drain,Completed,NP-PERUNGUDI,186,999000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT THIRUMALAI NAGAR 5TH CROSS STREET AT EAST SIDE FROM PANCHAYAT OFFICE MAIN ROAD TO 4TH STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/26146,Storm Water Drain,Completed,NP-PERUNGUDI,186,999000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT THIRUMALAI NAGAR 4TH CROSS STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/26149,Storm Water Drain,Completed,NP-PERUNGUDI,186,957000,CONSTRUCTION AND IMPROVEMENTS AT THIRUMALAI NAGAR 7 TH CROSS STREET EAST SIDE IN DN 186 UT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/26150,Storm Water Drain,Completed,NP-PERUNGUDI,186,990000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT THIRUMALAI NAGAR 7THCROSS WEST SIDE IN DN 186 UT 41 ZONE 14,Own Sources,14,2014-15,2016-17 NP/2014-15/29572,Storm Water Drain,Completed,NP-PERUNGUDI,186,990000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT KAMARAJAR NAGAR 1ST CROSS STREET IN DIV 186 UNIT 41 ZONE 14.,Own Sources,14,2014-15,2016-17 NP/2014-15/29574,Storm Water Drain,Completed,NP-PERUNGUDI,186,991000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT KAMARAJAR NAGAR 2ND CROSS STREET IN DIV 186 UNIT 41 ZONE 14.,Own Sources,14,2014-15,2016-17 NP/2014-15/29575,Storm Water Drain,Completed,NP-PERUNGUDI,186,992000,CONSTRUCTION AND IMPROVEMENTS TO SIDE DRAIN AT KAMARAJAR NAGAR 3RD CROSS STREET IN DIV 186 UNIT 41 ZONE 14.,Own Sources,14,2014-15,2016-17 NP/2014-15/22906,Roads,Completed,NP-PERUNGUDI,187,435000,"ATTENDING PATCH WORK AT PONNIAMMAN KOIL STREET IN DN - 187, U - 42, Z - 14",Own Sources,14,2014-15,2016-17 NP/2014-15/22909,Roads,Completed,NP-PERUNGUDI,187,532000,"ATTENDING PATCH WORK AT MADIPAKKAM MAIN ROAD IN DN - 187, U - 42, Z - 14",Own Sources,14,2014-15,2016-17 BR/2014-15/29879,Roads,Completed,BR-Bus Route Roads,188,17652000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement work at Senthil Nagar Main Road in Dn.188, Zone - 14",Grants,14,2014-15,2016-17 BR/2014-15/29880,Roads,Completed,BR-Bus Route Roads,188,25253000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement work at Bharathi salai & Ramurthi Nagar Main Road in Dn.188, Zone - 14",Grants,14,2014-15,2016-17 L/2014-15/2964,Electrical,Completed,L-Electrical,188,3692000,"Conversion of 119 nos of 250W SVL fittings into 150W-165W LED fittings in Pallikaranai Fly over bridge, Service Road and Pallavaram Radial Road in div 188, Zone XIV",Own Sources,14,2014-15,2016-17 NP/2014-15/0795,Roads,Completed,NP-PERUNGUDI,188,540000,"FORMATION OF ROAD WITH GSB AT MAHALAKSHMI NAGAR ISWARIYA STREET AND CROSS STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2017-18 NP/2014-15/19188,Electrical,Completed,NP-PERUNGUDI,188,506000,Removal and Refixing of 20mtr high mast lighting at Kaiveli junction ( Removal from Ponniamman Koil Ju in div-187) in Div-188/Z-14,Own Sources,14,2014-15,2016-17 NP/2014-15/21075,Storm Water Drain,Completed,NP-PERUNGUDI,188,970000,"CONSTRUCTION OF SIDE DRAIN AT MYLLAI BALAJI NAGAR 2ND.BLOCK 2ND MAIN ROAD FROM CROSS STREET TO DOOR NO.633 IN DN-188, U - 42, Z-14",Own Sources,14,2014-15,2018-19 NP/2014-15/22202,Roads,Completed,NP-PERUNGUDI,188,2638000,"STRENGTHENING AND LAYING OF BT ROAD AT PERIYAR NAGAR MAIN ROAD IN DN-188, U-42, Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22205,Roads,Completed,NP-PERUNGUDI,188,7220000,"STRENGTHENING AND LAYING OF BT ROAD AT NARAYANAPURAM EARIKARAI SALAI IN DN-188, U-42, Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22206,Roads,Completed,NP-PERUNGUDI,188,1100000,"STRENGTHENING AND LAYING OF BT ROAD AT PERIYAR NAGAR 2ND STREET IN DN-188, U-42, Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22211,Roads,Completed,NP-PERUNGUDI,188,1280000,"STRENGTHENING AND LAYING OF BT ROAD AT PERIYAR NAGAR 1ST STREET IN DN-188, U-42, Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23505,Roads,Completed,NP-PERUNGUDI,188,1580000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR 6TH CROSS STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23506,Roads,Completed,NP-PERUNGUDI,188,1580000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR 4TH CROSS STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23507,Roads,Completed,NP-PERUNGUDI,188,1132000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR 5TH MAIN ROAD 2ND CROSS STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23508,Roads,Completed,NP-PERUNGUDI,188,348000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR 4TH MAIN ROAD CROSS STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23509,Roads,Completed,NP-PERUNGUDI,188,1264000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR 3RD MAIN ROAD CROSS STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23510,Roads,Completed,NP-PERUNGUDI,188,1442000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR 2ND MAIN ROAD CROSS STREET STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23511,Roads,Completed,NP-PERUNGUDI,188,1537000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR 1STMAIN ROAD CROSS STREET IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23512,Roads,Completed,NP-PERUNGUDI,188,1519000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR EXTN 5TH MAIN ROAD IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23513,Roads,Completed,NP-PERUNGUDI,188,1580000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR EXTN 4TH MAIN ROAD IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/23514,Roads,Completed,NP-PERUNGUDI,188,2119000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJESH NAGAR EXTN 2ND MAIN ROAD IN DN-188,U-42,Z-14",Own Sources,14,2014-15,2016-17 NP/2014-15/26633,Roads,Completed,NP-PERUNGUDI,188,920000,"FORMATION OF ROAD WITH GSB AT BALA AMBUGAN NAGAR IN DN - 188, UN - 42, Z - 14",Own Sources,14,2014-15,2017-18 L/2014-15/2968,Electrical,Completed,L-Electrical,189,4033200,"Conversion of 130 nos of 250W SVL fittings into 150W-165W LED fittings in Tambaram Velachery Main Road in div 189, Zone XIV",Own Sources,14,2014-15,2016-17 L/2014-15/2970,Electrical,Completed,L-Electrical,189,2606100,"Conversion of 84 nos of 250W SVL fittings into 150W-165W LED fittings in Thoraipakkam Radial Road in div 189, Zone XIV",Own Sources,14,2014-15,2016-17 NP/2014-15/22682,Roads,Completed,NP-PERUNGUDI,189,123000,"PROVIDING DUSTBIN PLATFORM AT VARIOUS STREET IN DIVISION 189, UNIT 42, ZONE 14.",Own Sources,14,2014-15,2017-18 NP/2014-15/23716,Roads,Completed,NP-PERUNGUDI,189,902000,"Supplying and Fixing Street Furniture at A.G.S Colony 1st Street to 11th Street, V.G.P shanthi nagar main road, V.G.P shanthi nagar V.O.C street, Syndicate Bank Colony main road, I.I.T colony main road in Division 189, Unit 43, Zone 14.",Own Sources,14,2014-15,2016-17 NP/2014-15/32089,Roads,Completed,NP-PERUNGUDI,189,82000,"IMPROVEMENTS TO EXISTING WELL AT VARIOUS STREET IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2014-15,2017-18 NP/2014-15/22954,Buildings,Completed,NP-PERUNGUDI,190,600000,"Repairs and Improvements and Providing Water supply arrangements to the Burrial Ground at Kovalan Nagar and Vivekandha Nagar in Dn 190,Unit 43, Zone XIV",Own Sources,14,2014-15,2016-17 NP/2014-15/23724,Roads,Completed,NP-PERUNGUDI,190,902000,"Supplying and Fixing Street Furniture at Kovalan Nagar Main Road, Meenakshi Nagar Main Road, Kovalan Nagar 1st street to 8th street, Nehru Street, Kakkanji Street, Bharathidasan 2nd Main Road, Gandhi Street, Karmel Street in Division 190, Unit 43, Zone 14.",Own Sources,14,2014-15,2016-17 NP/2014-15/24439,Buildings,Completed,NP-PERUNGUDI,190,998000,Proposed Additional construction of handicapped toilet and other Improvements to Kannapiran koil street Public Convienence in Division -190 Unit-43 Zone-14,Own Sources,14,2014-15,2016-17 NP/2014-15/29406,Buildings,Completed,NP-PERUNGUDI,190,995000,"Proposed Costruction of compound wall with Gate and gate pillar for 16th cermony building at Thandukkari kulam and Desilting and repairs to Thandukarai kulam and Piilaiyarkoil kulam in Division -190, Unit-43, Zone-14",Own Sources,14,2014-15,2016-17 NP/2014-15/22957,Storm Water Drain,Completed,NP-PERUNGUDI,191,957000,"Raising and covering the open side drain at Jayanthi Natarajan street and Rajeev Gandhi street in Dn 191,Unit 43, Zone XIV",Own Sources,14,2014-15,2017-18 NP/2014-15/22958,Storm Water Drain,Completed,NP-PERUNGUDI,191,985000,"Raising and covering the open side drain at Ricemill road and Moopanar street in Dn 191,Unit 43, Zone XIV",Own Sources,14,2014-15,2017-18 NP/2014-15/22961,Storm Water Drain,Completed,NP-PERUNGUDI,191,774000,"Raising and covering the open to Side Drain and partly new construction at Pachaiamman Koil street in Dn 191,Unit 43, Zone XIV",Own Sources,14,2014-15,2017-18 NP/2014-15/22964,Storm Water Drain,Completed,NP-PERUNGUDI,191,988000,"Raising and covering the open side drain at Veerathamman Koil street and Anna Salai-Veerathamman Koil west street in Dn 191,Unit 43, Zone XIV",Own Sources,14,2014-15,2016-17 NP/2014-15/22965,Storm Water Drain,Completed,NP-PERUNGUDI,191,995000,"Raising and covering the open side drain at Anna Salai -Lakshmi nagar in Dn 191,Unit 43, Zone XIV",Own Sources,14,2014-15,2016-17 NP/2014-15/22966,Storm Water Drain,Completed,NP-PERUNGUDI,191,990000,"Raising and covering the open side drain at Anna Salai -Nesawalar nagar in Dn 191,Unit 43, Zone XIV",Own Sources,14,2014-15,2017-18 NP/2014-15/22968,Storm Water Drain,Completed,NP-PERUNGUDI,191,990000,"Raising and covering the open to Side Drain and partly new construction at Anna Salai- Thiruvalluvar nagar in Dn 191,Unit 43, Zone XIV",Own Sources,14,2014-15,2016-17 NP/2014-15/24192,Roads,Completed,NP-PERUNGUDI,191,981000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and Providing Thermo Plastic Compound marking Road pavement markers and signage boards at various Street in Dn 191, Unit-43, Zone-14",Own Sources,14,2014-15,2017-18 RS/2014-15/29811,Parks,Completed,P-Parks and Playfields,191,4709000,"PROVIDING ELECTRICAL ARRANGEMENT AND GREENERIES for OSR land at Jayachandran nagar 1st main road (Southern side) in Dn.191., Unit-43, Zone-14",Own Sources,14,2014-15,2018-19 NQ/2014-15/24873,Roads,Completed,NQ-SHOZHINGANALLUR,192,7740000,FORMING AND LAYING OF BT ROAD AT KAPALEESWARA NAGAR SOUTH 4TH MAIN ROAD IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24899,Roads,Completed,NQ-SHOZHINGANALLUR,192,1720000,"FORMING AND LAYING BT ROAD USING PAVER IN KAPALEESWARAR NAGAR NORTH 3RD MAIN ROAD IN DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24920,Roads,Completed,NQ-SHOZHINGANALLUR,192,4207000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT KAPALEESWARA NAGAR SOUTH 9TH CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24926,Roads,Completed,NQ-SHOZHINGANALLUR,192,1361000,FORMING AND LAYING OF BT ROAD AT RANGA REDDY GARDEN 12TH CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24936,Roads,Completed,NQ-SHOZHINGANALLUR,192,5628000,FORMING AND LAYING OF CC ROAD RMC M30 AT RANGA REDDY GARDEN 1ST PRATHANA SALAI STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24939,Roads,Completed,NQ-SHOZHINGANALLUR,192,663000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT SINGARAVELAR 1ST STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24944,Roads,Completed,NQ-SHOZHINGANALLUR,192,663000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT SINGARA VELAR 2ND STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24946,Roads,Completed,NQ-SHOZHINGANALLUR,192,663000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT SINGARAVELAR 3RD STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24948,Roads,Completed,NQ-SHOZHINGANALLUR,192,3744000,FORMING AND LAYING OF BT ROAD AT SUNRICE AVENUE MAIN ROAD IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24963,Roads,Completed,NQ-SHOZHINGANALLUR,192,2214000,FORMING AND LAYING OF BT ROAD AT SUNRICE AVENUE 7TH CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24982,Roads,Completed,NQ-SHOZHINGANALLUR,192,878000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT C.L.R.I. NAGAR 12TH STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24991,Roads,Completed,NQ-SHOZHINGANALLUR,192,649000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT C.L.R.I. NAGAR 14TH STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25000,Roads,Completed,NQ-SHOZHINGANALLUR,192,521000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT C.L.R.I. NAGAR 13TH STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25006,Roads,Completed,NQ-SHOZHINGANALLUR,192,473000,FORMING AND LAYING OF BT ROAD AT C.L.R.I. NAGAR 15TH STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25010,Roads,Completed,NQ-SHOZHINGANALLUR,192,737000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT C.L.R.I. NAGAR 16TH STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25020,Roads,Completed,NQ-SHOZHINGANALLUR,192,437000,FORMING AND LAYING OF CC ROAD USING M30 CONCRETE AT C.L.R.I. NAGAR 17TH STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25048,Roads,Completed,NQ-SHOZHINGANALLUR,192,1589000,FORMING AND LAYING OF BT ROAD AT PANDIYAN SALAI 2ND CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25052,Roads,Completed,NQ-SHOZHINGANALLUR,192,6253000,FORMING AND LAYING OF BT ROAD AT RAJENDRA NAGAR PIRATHANA SALAI IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25057,Roads,Completed,NQ-SHOZHINGANALLUR,192,305000,FORMING AND LAYING OF BT ROAD AT ELLAI AMMAN KOIL 1ST CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25060,Roads,Completed,NQ-SHOZHINGANALLUR,192,293000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT ELLAI AMMAN KOIL 2ND CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25061,Roads,Completed,NQ-SHOZHINGANALLUR,192,293000,FORMING AND LAYING OF CC ROAD USING RMC M30 AT ELLAI AMMAN KOIL 3RD CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25065,Roads,Completed,NQ-SHOZHINGANALLUR,192,786000,FORMING AND LAYING OF BT ROAD AT ELLAI AMMAN KOIL 4TH CROSS STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25914,Roads,Completed,NQ-SHOZHINGANALLUR,192,618000,FORMING AND LAYING OF BT ROAD AT RUBI COMPLEX MAIN ROAD IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25922,Roads,Completed,NQ-SHOZHINGANALLUR,192,778000,FORMING AND LAYING OFCC ROAD USING RMC M30 AT C.L.R.I 8TH STREET NAGAR IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25925,Roads,Completed,NQ-SHOZHINGANALLUR,192,649000,FORMING AND LAYING OF CC ROAD USING M30 READY MIXED CONCRETE AT C.L.R.I NAGAR 10TH STREET IN DN 192 U-44 Z-15,Own Sources,15,2014-15,2016-17 D/2014-15/15484,Storm Water Drain,Completed,D-Storm Water Drains,193,17962000,"Construction of storm water Drain of size 1200x1200mm along Venkateswara Nagar 7th and 14th Street from Manikodi Srinivasan Nagar3rd Street to South B Canal in Div-193, Zone-15 (Node No: M58002 to N58001)",JNNURM,15,2014-15,2016-17 NQ/2014-15/24922,Roads,Completed,NQ-SHOZHINGANALLUR,193,1234000,"FORMING THE ROAD WITH GSB AND WMM AT MCN NAGAR 1ST STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/24930,Roads,Completed,NQ-SHOZHINGANALLUR,193,927000,"FORMING AND LAYING BITUMINOUS COURSE AT MCN NAGAR 2ND STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25003,Roads,Completed,NQ-SHOZHINGANALLUR,193,886000,"FORMING AND LAYING BITUMINOUS COURSE AT MCN NAGAR 7TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25176,Roads,Completed,NQ-SHOZHINGANALLUR,193,627000,"FORMING AND LAYING BITUMINOUS COURSE AT MCN NAGAR 8TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25177,Roads,Completed,NQ-SHOZHINGANALLUR,193,391000,"FORMING AND LAYING BITUMINOUS COURSE AT MCN NAGAR 9TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25178,Roads,Completed,NQ-SHOZHINGANALLUR,193,264000,"FORMING AND LAYING BITUMINOUS COURSE AT MCN NAGAR 1ST LANE IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25184,Roads,Completed,NQ-SHOZHINGANALLUR,193,1859000,"FORMING AND LAYING BITUMINOUS COURSE AT RE NAGAR 2ND MAIN ROAD IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25185,Roads,Completed,NQ-SHOZHINGANALLUR,193,694000,"FORMING AND LAYING BITUMINOUS COURSE AT SAI BABA NAGARMAIN ROAD IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25197,Roads,Completed,NQ-SHOZHINGANALLUR,193,539000,"Forming and laying the bituminouse course at Karpaga vinayagar nagar 1st cross street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25198,Roads,Completed,NQ-SHOZHINGANALLUR,193,2492000,"FORMING AND LAYING BITUMINOUS COURSE AT VENKATESHWARA NAGAR MAIN ROAD(N) IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25201,Roads,Completed,NQ-SHOZHINGANALLUR,193,639000,"Forming and laying the bituminouse course at Karpaga vinayagar nagar 2nd cross street street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25207,Roads,Completed,NQ-SHOZHINGANALLUR,193,521000,"Forming and laying the bituminouse course at Karpaga vinayagar nagar 26th cross street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25208,Roads,Completed,NQ-SHOZHINGANALLUR,193,550000,"Forming and laying the bituminouse course at Karpaga vinayagar nagar 27th cross street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25211,Roads,Completed,NQ-SHOZHINGANALLUR,193,550000,"Forming and laying the bituminouse course at Karpaga vinayagar nagar 28th cross street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25218,Roads,Completed,NQ-SHOZHINGANALLUR,193,580000,"Forming and laying the bituminouse course at Karpaga vinayagar nagar 30th cross street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25220,Roads,Completed,NQ-SHOZHINGANALLUR,193,539000,"Laying Cement Concrete Road at Karpaga vinayagar nagar 19th cross street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25235,Roads,Completed,NQ-SHOZHINGANALLUR,193,9118000,"Laying Cement Concrete Road at pandian nagar main road in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25241,Roads,Completed,NQ-SHOZHINGANALLUR,193,569000,"Forming and laying the bituminouse course at mahatma gandhi nagar 4th street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25256,Roads,Completed,NQ-SHOZHINGANALLUR,193,1426000,"LAYING CEMENT CONCRETE ROAD AT KULAKARAI 2ND CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25264,Roads,Completed,NQ-SHOZHINGANALLUR,193,1051000,"LAYING CEMENT CONCRETE ROAD AT KULAKKARAI 3RD CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25271,Roads,Completed,NQ-SHOZHINGANALLUR,193,1459000,"LAYING CEMENT CONCRETE ROAD AT PARVATHY AVENUE IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/25281,Roads,Completed,NQ-SHOZHINGANALLUR,193,3729000,"LAYING CEMENT CONCRETE ROAD AT GANGAI AMMAN KOVIL 2ND STREET IN WARD-193, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/5153,Buildings,Completed,NQ-SHOZHINGANALLUR,193,3800000,"CONSTRUCTION OF AMMA UNAVAGAM USING STEEL STRUCTURE AND CORRUGATED SHEET CLADDING RAJIV GHANTHI SALAI (OMR) IN DN-193,U-44,Z-15",Own Sources,15,2014-15,2016-17 D/2014-15/5737,Storm Water Drain,Completed,D-Storm Water Drains,194,29848000,"Construction of storm water Drain of size 2000x2000mm along 1st main road of Ezhil Nagar from Easwaran Koil main road to Existing open drain Ezhil Nagar, Thoraipakkam Dn.194, Zone XV",JNNURM,15,2014-15,2016-17 NQ/2014-15/24845,Roads,Completed,NQ-SHOZHINGANALLUR,194,670000,Forming and Laying the B.T Road With Paver Finisher at Venkateshwara Avenue in Dn-194 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24879,Roads,Completed,NQ-SHOZHINGANALLUR,194,719000,Relaying of Cement concrete road by using M30 grade concrete and interlocking blocksat Anna Street in Dn-194 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24880,Roads,Completed,NQ-SHOZHINGANALLUR,194,572000,Relaying the B.T Road With Paver Finisher at Subramaniyam 1st Lane in Dn-194 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24882,Roads,Completed,NQ-SHOZHINGANALLUR,194,451000,Relaying of CC road by using M30 Grade Concrete and Inter locking blocks at Subramaniyam 2nd Lane in Dn-194 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24941,Roads,Completed,NQ-SHOZHINGANALLUR,194,526000,Relaying of Cement concrete road by using M30 grade concrete and interlocking blocks at J K Avenue in Dn-194 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24927,Roads,Completed,NQ-SHOZHINGANALLUR,195,3551000,FORMING AND LAYING OF C.C ROAD AT VINAYAGA AVENUE IN DN 195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24949,Roads,Completed,NQ-SHOZHINGANALLUR,195,2601000,"Forming and Laying the C,C Road at Kannagi Nagar 2 Aduku 70th Cross Street in Dn-195 U-45 Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24954,Roads,Completed,NQ-SHOZHINGANALLUR,195,679000,Forming and Laying the B.T Road With Paver Finisher at Kannagi Nagar 2 Aduku 71tst Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24965,Roads,Completed,NQ-SHOZHINGANALLUR,195,679000,Forming and Laying the B.T Road With Paver Finisher at Kannagi Nagar 2 Aduku 72nd Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24976,Roads,Completed,NQ-SHOZHINGANALLUR,195,852000,"Forming and laying of BT road at Kannagi nagar 2 aduku 2nd cross street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24979,Roads,Completed,NQ-SHOZHINGANALLUR,195,1689000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 39th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24980,Roads,Completed,NQ-SHOZHINGANALLUR,195,1456000,"Forming and laying of C.C road at Kannagi nagar 2 aduku 48th cross street in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24983,Roads,Completed,NQ-SHOZHINGANALLUR,195,1986000,"Forming and Laying the C,C Road at Kannagi Nagar 2 Aduku 40th Cross Street in Dn-195 U-45 Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24984,Roads,Completed,NQ-SHOZHINGANALLUR,195,1249000,"Forming and laying of C.C road at Kannagi nagar 2 aduku 49th cross streetin Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24986,Roads,Completed,NQ-SHOZHINGANALLUR,195,1689000,"Forming and Laying the C,C Road at Kannagi Nagar 2 Aduku 41st Cross Street in Dn-195 U-45 Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24987,Roads,Completed,NQ-SHOZHINGANALLUR,195,1321000,"Forming and laying of C.C road at Kannagi nagar 2 aduku 50th cross street in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24990,Roads,Completed,NQ-SHOZHINGANALLUR,195,1402000,Forming and Laying the C.C ROAD at Kannagi Nagar 2 Aduku 42nd Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24992,Roads,Completed,NQ-SHOZHINGANALLUR,195,1300000,"Forming and laying of C.C road at Kannagi nagar 2 aduku 51st cross street in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24994,Roads,Completed,NQ-SHOZHINGANALLUR,195,1789000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 43rd Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24998,Roads,Completed,NQ-SHOZHINGANALLUR,195,1233000,"Forming and laying of CC road at Kannagi nagar 2 aduku 52nd cross street in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24999,Roads,Completed,NQ-SHOZHINGANALLUR,195,1308000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 44th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25001,Roads,Completed,NQ-SHOZHINGANALLUR,195,1337000,"Forming and laying of CC road at Kannagi nagar 2 aduku 53rd cross street in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25002,Roads,Completed,NQ-SHOZHINGANALLUR,195,1765000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 45th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25005,Roads,Completed,NQ-SHOZHINGANALLUR,195,1550000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 46th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25007,Roads,Completed,NQ-SHOZHINGANALLUR,195,1115000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 47th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25009,Roads,Completed,NQ-SHOZHINGANALLUR,195,1907000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 54th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25011,Roads,Completed,NQ-SHOZHINGANALLUR,195,439000,"Forming and laying of BT road at Kannagi nagar 2 aduku 58th cross street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25012,Roads,Completed,NQ-SHOZHINGANALLUR,195,1638000,Forming and Laying the C.CRoad at Kannagi Nagar 2 Aduku 55th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25027,Roads,Completed,NQ-SHOZHINGANALLUR,195,1332000,Forming and Laying the C.C Road at Kannagi Nagar 2 Aduku 56th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25039,Roads,Completed,NQ-SHOZHINGANALLUR,195,395000,"Forming and laying of BT road at Kannagi nagar 2 aduku 66th cross street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25045,Roads,Completed,NQ-SHOZHINGANALLUR,195,1641000,Forming and Laying the B.T Road With Paver Finisher at Kannagi Nagar 3 Aduku 24th Cross Street in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25047,Roads,Completed,NQ-SHOZHINGANALLUR,195,412000,"Forming and laying of BT road at Kannagi nagar 2 aduku 67th cross street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25051,Roads,Completed,NQ-SHOZHINGANALLUR,195,1469000,"Forming and laying of BT road at Kannagi nagar 2 aduku 68th cross street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25055,Roads,Completed,NQ-SHOZHINGANALLUR,195,518000,"Forming and laying of BT road at Kannagi nagar 2 aduku 69th cross street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25058,Roads,Completed,NQ-SHOZHINGANALLUR,195,2029000,Forming and Laying the B.T Road With Paver Finisher at Brindavan Garden Road in Dn-195 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25073,Roads,Completed,NQ-SHOZHINGANALLUR,195,1913000,"Forming and laying of BT road at Annamalai Aravind street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25075,Roads,Completed,NQ-SHOZHINGANALLUR,195,2948000,"Forming and laying of BT road at Lakshmi Avenue by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25087,Roads,Completed,NQ-SHOZHINGANALLUR,195,871000,"Forming and laying of BT road at Kannagi ngar link road by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25096,Roads,Completed,NQ-SHOZHINGANALLUR,195,6264000,"Forming and laying of BT road at Kannagi nagar 8th main road by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2014-15,2016-17 D/2014-15/5211,Storm Water Drain,Completed,D-Storm Water Drains,196,20608000,Construction of storm water Drain of size 1500x1500mm along Thiruvalluvar street From Thiruvalluvar 1st street to South B`canal at Bethel nagar Eanchambakkam in division 196 Zone XV,JNNURM,15,2014-15,2016-17 NQ/2014-15/24138,Roads,Completed,NQ-SHOZHINGANALLUR,196,7663000,LAYING OF BT ROAD AT THIRUVALLUVAR SALAI IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25053,Roads,Completed,NQ-SHOZHINGANALLUR,196,2799000,Forming and Laying BT Road with Paver Finisher at Arichandra Salai in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25059,Roads,Completed,NQ-SHOZHINGANALLUR,196,3510000,Forming and Laying BT Road with Paver Finisher at Babul Beach Avenue in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25063,Roads,Completed,NQ-SHOZHINGANALLUR,196,3087000,Forming and Laying BT Road with Paver Finisher at Bajanai Koil Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25066,Roads,Completed,NQ-SHOZHINGANALLUR,196,3403000,FORMING AND LAYING OF CC ROAD AT CHAINNANDI kUPPAM PALLATHERU in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25070,Roads,Completed,NQ-SHOZHINGANALLUR,196,4786000,Forming and Laying BT Road with Paver Finisher at Dr. Nanjundarao Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25072,Roads,Completed,NQ-SHOZHINGANALLUR,196,2483000,Forming and Laying BT Road with Paver Finisher at Gandhi Avenue in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25074,Roads,Completed,NQ-SHOZHINGANALLUR,196,2145000,Forming and Laying BT Road with Paver Finisher at Harichandra Salai in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25076,Roads,Completed,NQ-SHOZHINGANALLUR,196,6678000,FORMING AND LAYING OF BT ROAD AT RAJAN NAGAR IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25077,Roads,Completed,NQ-SHOZHINGANALLUR,196,3301000,Forming and Laying BT Road with Paver Finisher at Jagajeevanram Avenue in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25080,Roads,Completed,NQ-SHOZHINGANALLUR,196,2294000,Forming and Laying BT Road with Paver Finisher at Jagajeevanram Avenue to Shesathri Avenue in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25081,Roads,Completed,NQ-SHOZHINGANALLUR,196,391000,FORMING AND LAYING OF CC ROAD AT SANKAR STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25083,Roads,Completed,NQ-SHOZHINGANALLUR,196,3847000,Forming and Laying BT Road with Paver Finisher at Krishna Koil Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25084,Roads,Completed,NQ-SHOZHINGANALLUR,196,265000,FORMING AND LAYING OF CC ROAD AT SWAMINATHAN SALAI IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25086,Roads,Completed,NQ-SHOZHINGANALLUR,196,3042000,Forming and Laying BT Road with Paver Finisher atP J Thomas Avenue in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25089,Roads,Completed,NQ-SHOZHINGANALLUR,196,2921000,Forming and Laying BT Road with Paver Finisher at Prathana Cross Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25090,Roads,Completed,NQ-SHOZHINGANALLUR,196,727000,FORMING AND LAYING OF BT ROAD AT TEACHERS COLONY 1ST STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25092,Roads,Completed,NQ-SHOZHINGANALLUR,196,5747000,Forming and Laying BT Road with Paver Finisher at Prathana Salai in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25093,Roads,Completed,NQ-SHOZHINGANALLUR,196,727000,FORMING AND LAYING OF BT ROAD AT TEACHERS COLONY 2ND STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25095,Roads,Completed,NQ-SHOZHINGANALLUR,196,1853000,Forming and Laying BT Road with Paver Finisher at Cheran nagar in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25097,Roads,Completed,NQ-SHOZHINGANALLUR,196,727000,FORMING AND LAYING OF BT ROAD AT TEACHERS COLONY 3RD STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25098,Roads,Completed,NQ-SHOZHINGANALLUR,196,1873000,Forming and Laying BT Road with Paver Finisher at Shesathri Avenue in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25100,Roads,Completed,NQ-SHOZHINGANALLUR,196,710000,Forming and Laying CC ROAD at Aavin Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25101,Roads,Completed,NQ-SHOZHINGANALLUR,196,662000,Forming and Laying BT Road with Paver Finisher at Bismillah Nagar 1st Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25103,Roads,Completed,NQ-SHOZHINGANALLUR,196,1719000,Forming and Laying BT Road with Paver Finisher at Bismillah Nagar 2nd Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25104,Roads,Completed,NQ-SHOZHINGANALLUR,196,727000,FORMING AND LAYING OF BT ROAD AT TEACHERS COLONY 4TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25106,Roads,Completed,NQ-SHOZHINGANALLUR,196,1224000,Forming and Laying BT Road with Paver Finisher at Bismillah Nagar 3rd Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25109,Roads,Completed,NQ-SHOZHINGANALLUR,196,1464000,FORMING AND LAYING OF BT ROAD AT 1ST AVENUE IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25111,Roads,Completed,NQ-SHOZHINGANALLUR,196,4090000,Forming and Laying BT Road with Paver Finisher at Chinnandi Kuppam Main Road in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25113,Roads,Completed,NQ-SHOZHINGANALLUR,196,3933000,Forming and Laying BT Road with Paver Finisher at Chinnandi Kuppam Meattu Theru in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25114,Roads,Completed,NQ-SHOZHINGANALLUR,196,1464000,FORMING AND LAYING OF BT ROAD AT 2ND AVENUE IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25116,Roads,Completed,NQ-SHOZHINGANALLUR,196,1284000,Forming and Laying BT Road with Paver Finisher at Dr.Ambetkar Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25117,Roads,Completed,NQ-SHOZHINGANALLUR,196,12244000,FORMING AND LAYING OF BT ROAD AT BAY WATCH FORM IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25118,Roads,Completed,NQ-SHOZHINGANALLUR,196,464000,Forming and Laying of CC Road at Ebrahim Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25121,Roads,Completed,NQ-SHOZHINGANALLUR,196,1925000,FORMING AND LAYING OF BT ROAD AT BRINDAVAN NAGAR IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25122,Roads,Completed,NQ-SHOZHINGANALLUR,196,6102000,Forming and Laying BT Road with Paver Finisher at Injambakkam Kuppam Meenaver in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25123,Roads,Completed,NQ-SHOZHINGANALLUR,196,812000,Forming and Laying BT Road with Paver Finisher at Gandhi Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25124,Roads,Completed,NQ-SHOZHINGANALLUR,196,1804000,FORMING AND LAYING OF CC ROAD AT KARTHICK NAGAR IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25125,Roads,Completed,NQ-SHOZHINGANALLUR,196,1892000,Forming and Laying of CC Road at Gangai amman Koil cross Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25126,Roads,Completed,NQ-SHOZHINGANALLUR,196,3553000,FORMING AND LAYING OF BT ROAD AT KULAKARAI STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25127,Roads,Completed,NQ-SHOZHINGANALLUR,196,4493000,Forming and Laying CC Road at Gangai amman Koil Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25129,Roads,Completed,NQ-SHOZHINGANALLUR,196,6429000,FORMING AND LAYING OF BT ROAD AT SELVA NAGAR MAIN ROAD IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25130,Roads,Completed,NQ-SHOZHINGANALLUR,196,606000,Forming and Laying CC road Finisher at Jansi Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25132,Roads,Completed,NQ-SHOZHINGANALLUR,196,2570000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR MAIN ROAD IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25133,Roads,Completed,NQ-SHOZHINGANALLUR,196,1496000,Forming and Laying CC Road at M A Vaithiyalingam Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25134,Roads,Completed,NQ-SHOZHINGANALLUR,196,2168000,Forming and Laying CC Road at Munishwar Koil Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25135,Roads,Completed,NQ-SHOZHINGANALLUR,196,2570000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 1ST STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25136,Roads,Completed,NQ-SHOZHINGANALLUR,196,681000,Forming and Laying CC Road at Padasalai Street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25137,Roads,Completed,NQ-SHOZHINGANALLUR,196,2384000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 2ND STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25139,Roads,Completed,NQ-SHOZHINGANALLUR,196,2384000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 3RD STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25141,Roads,Completed,NQ-SHOZHINGANALLUR,196,2197000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 4TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25142,Roads,Completed,NQ-SHOZHINGANALLUR,196,1512000,Forming and Laying CC Road at periyar cross street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25143,Roads,Completed,NQ-SHOZHINGANALLUR,196,2570000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 5TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25146,Roads,Completed,NQ-SHOZHINGANALLUR,196,2011000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 6TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25147,Roads,Completed,NQ-SHOZHINGANALLUR,196,3897000,Forming and Laying BT Road with Paver Finisher at periyar street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25149,Roads,Completed,NQ-SHOZHINGANALLUR,196,1824000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 7TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25150,Roads,Completed,NQ-SHOZHINGANALLUR,196,4213000,Forming and Laying BT Road with Paver Finisher at ponniamman koil street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25151,Roads,Completed,NQ-SHOZHINGANALLUR,196,392000,FORMING AND LAYING OF CC ROAD AT BETHAL NAGAR 8TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25153,Roads,Completed,NQ-SHOZHINGANALLUR,196,2570000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 9TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25154,Roads,Completed,NQ-SHOZHINGANALLUR,196,1068000,Forming and Laying BT Road with Paver Finisher at Poompuhar street in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25157,Roads,Completed,NQ-SHOZHINGANALLUR,196,6069000,Forming and Laying BT Road with Paver Finisher at PUMPUHAR STREET TO THURAIPAKKAM in Dn-196 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25158,Roads,Completed,NQ-SHOZHINGANALLUR,196,2197000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 10TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25159,Roads,Completed,NQ-SHOZHINGANALLUR,196,2197000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 11TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25160,Roads,Completed,NQ-SHOZHINGANALLUR,196,2011000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 12TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25161,Roads,Completed,NQ-SHOZHINGANALLUR,196,2384000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 13TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25162,Roads,Completed,NQ-SHOZHINGANALLUR,196,1102000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 14TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25164,Roads,Completed,NQ-SHOZHINGANALLUR,196,1220000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 15TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25165,Roads,Completed,NQ-SHOZHINGANALLUR,196,1220000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 16TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25166,Roads,Completed,NQ-SHOZHINGANALLUR,196,1220000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 17TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25167,Roads,Completed,NQ-SHOZHINGANALLUR,196,948000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 18TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25168,Roads,Completed,NQ-SHOZHINGANALLUR,196,948000,FORMING AND LAYING OF BT ROAD AT BETHAL NAGAR 19TH STREET IN DN 196 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/19091,Buildings,Completed,NQ-SHOZHINGANALLUR,197,951000,Construction of Dress Changing Room and Toilet Room for Conservancy Labour at (Inside Division Office) Gangaiamman koil street karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/20612,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1540000,Construction of Compound Wall For Amma Unavagam at Kaliamman koil Street Karapakkam in Dn-197 U-44 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/24618,Roads,Completed,NQ-SHOZHINGANALLUR,197,6967000,"Forming and Laying of BT Road With Using Paver Finisher at Aringar Anna Street,M.G.R Street and Bharathiyar Street in Dn-197 U-45 Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24637,Roads,Completed,NQ-SHOZHINGANALLUR,197,6930000,Forming and Laying of BT Road With Using Paver Finisher at Nehru Street (Sholinganallur) in Dn-197 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/25214,Roads,Completed,NQ-SHOZHINGANALLUR,197,550000,"Forming and laying the bituminouse course at Karpaga vinayagar nagar 29th cross street in ward-193, zone-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/26625,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1340000,Proposed Construction of Toilet at Periyapalathamman Koil Street Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2014-15,2016-17 NQ/2014-15/5025,Buildings,Completed,NQ-SHOZHINGANALLUR,197,3800000,"CONSTRUCTION OF AMMA UNAVAGAM USING STEEL STRUCTURE AND CORRUGATED SHEET ROOFING AND CLADING AT NEDUNCHEZHIAN SALAI(MANTHOPPU SALAI/SHOPPING COMPLEX) IN DN 197,U45,Z15",Own Sources,15,2014-15,2017-18 NQ/2014-15/24788,Roads,Completed,NQ-SHOZHINGANALLUR,198,4905000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern layout 11th Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24799,Roads,Completed,NQ-SHOZHINGANALLUR,198,3468000,"Forming and Laying CEMENT CONCRETE ROAD at Kudimiyandi Thoppu School 3rd, 6th, 7th, 8th, 9th Street and Padavattamman Koil Street in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24805,Roads,Completed,NQ-SHOZHINGANALLUR,198,3172000,"Forming and Laying CEMENT CONCRETE ROAD at Rajiv Gandhi Nagar 3rd Street, School Road 1st & 2nd Cross Street in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24810,Roads,Completed,NQ-SHOZHINGANALLUR,198,5034000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 3rd Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24812,Roads,Completed,NQ-SHOZHINGANALLUR,198,5196000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 4th Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24813,Roads,Completed,NQ-SHOZHINGANALLUR,198,3861000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 5th Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24814,Roads,Completed,NQ-SHOZHINGANALLUR,198,4761000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 6th Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24815,Roads,Completed,NQ-SHOZHINGANALLUR,198,5082000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 7th Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24816,Roads,Completed,NQ-SHOZHINGANALLUR,198,5019000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 8th Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24818,Roads,Completed,NQ-SHOZHINGANALLUR,198,2243000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern layout 11th Cross (East), 11th Cross (West) Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24911,Roads,Completed,NQ-SHOZHINGANALLUR,198,2034000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Pillayar Koil Main Street in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24913,Roads,Completed,NQ-SHOZHINGANALLUR,198,4194000,"Forming and Laying CEMENT CONCRETE Road at Mayana salai Ambedkar 1st and 2nd Cross Street, Padavattamman Koil Street-Link Road, Vigneshwara Nagar 1st, 2nd Street in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24915,Roads,Completed,NQ-SHOZHINGANALLUR,198,5244000,"Forming and Laying Bituminous Course Road Using Paver Finisher at TVS Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24917,Roads,Completed,NQ-SHOZHINGANALLUR,198,4179000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Drift Wood Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24952,Roads,Completed,NQ-SHOZHINGANALLUR,198,4170000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Shyamala Garden in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24967,Roads,Completed,NQ-SHOZHINGANALLUR,198,4194000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Sparking Sand in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24969,Roads,Completed,NQ-SHOZHINGANALLUR,198,4194000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Sun Rise Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24973,Roads,Completed,NQ-SHOZHINGANALLUR,198,4040000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Spring Garden 1st Street in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24977,Roads,Completed,NQ-SHOZHINGANALLUR,198,4624000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 10th Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24981,Roads,Completed,NQ-SHOZHINGANALLUR,198,5187000,"Forming and Laying Bituminous Course Road Using Paver Finisher at Modern Layout 1st Avenue in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/24989,Roads,Completed,NQ-SHOZHINGANALLUR,198,5561000,"Forming and Laying Bituminous Course Road Using Paver Finisher at VGP 1st and 2nd Cross Street in Div-198, U-44, Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25407,Roads,Completed,NQ-SHOZHINGANALLUR,198,1633000,"Forming and Laying of Cement Concrete Road at Ambedkar 2nd and 3rd Street in Div-198, U-44, Z-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/29645,Parks,Completed,NQ-SHOZHINGANALLUR,198,999000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT TNHB LAYOUT( OMR) AND SEA CLIFF CONCLAVE (ECR) for the period of nine months IN DIV-198, UNIT-44, ZONE-15.",Own Sources,15,2014-15,2016-17 NQ/2014-15/15294,Roads,Completed,NQ-SHOZHINGANALLUR,199,2197000,"FORMING AND LAYING OF BITUMINOUS ROAD USING PAVER MACHINE AT RAJA STREET IN UTHANDI , DN-199,U44,Z-15",Own Sources,15,2014-15,2016-17 NQ/2014-15/15741,Roads,Completed,NQ-SHOZHINGANALLUR,199,594000,"RELAYING OF BITUMINOUS ROAD USING PAVER MACHINE AT KUPPAM MAYANA SALAI IN UTHANDI DN 199, U44, Z15",Own Sources,15,2014-15,2016-17 NQ/2014-15/17274,Roads,Completed,NQ-SHOZHINGANALLUR,199,2264000,"FORMING AND LAYING OF BITUMINOUS ROAD USING PAVER MACHINE AT MGR STREET(Extn) IN DN-199,U44,Z15",Own Sources,15,2014-15,2016-17 NQ/2014-15/25248,Roads,Completed,NQ-SHOZHINGANALLUR,199,3789000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USIING PAVER MACHINE AT VRS SALAI IN DN 199,U44,Z15",Own Sources,15,2014-15,2016-17 J/2014-15/13273,Bridges,Completed,J-Bridges,,12320000,"Providing Stainless steel Handrail at Kodambakkam Over bridge in Divisions 110& 134, Zone ? IX & X",Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/19180,Culvert,Completed,J-Bridges,,3815000,"Demolition of the existing Foot Bridge & Re-Construction of Box Culvert 4 vent (3mX3m) at Railway colony,2nd street in Dn: 106 Zone - 8",Own Sources,Greater Chennai Corporation,2014-15,2018-19 J/2014-15/29801,Bridges,Completed,J-Bridges,,3160000,Improvements to Existing Bridge across Buckingham canal at Dr. Radhakrishnan road in Dn-121 Unit - 27 Zone IX,Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/29807,Bridges,Completed,J-Bridges,,2842000,"Improvements to Existing Bridge across Buckingham canal at Hamilton bridge Near City Centre dumping yard in Dn-125,Unit - 25,Zone -IX",Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/29813,Bridges,Completed,J-Bridges,,1629000,Improvements to Existing Bridge across Buckingham canal at Dr. Besant road in Dn 116 Unit 27 Zone IX,Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/29815,Bridges,Completed,J-Bridges,,1624000,Improvements to Existing Bridge across Buckingham canal at Bharathi street in Dn 116 Unit 27 Zone IX,Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/29818,Bridges,Completed,J-Bridges,,2069000,"Improvement to Existing Bridge across Buckhingam canal at Venkatakrishna iyer road (Mandaveli MRTS) IN Division-126,Zone-IX.",Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/29824,Bridges,Completed,J-Bridges,,3216000,"Improvement to Existing Bridge across Buckhingam canal at Greenways Road in Division -123 & 173, Zone - IX & XIII",Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/29836,Bridges,Completed,J-Bridges,,3112000,"Improvement to Existing Bridge across Buckhinagam canal at Dr.Ranga Bridge west of Saibaba temple in Division -123,Zone -IX",Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/29838,Bridges,Completed,J-Bridges,,1730000,"Improvement to Existing Bridge across Buckhinagam canal at R.K.Mutt Road Mylapore(MRTS) in Division - 124 ,Zone -IX",Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/30062,Bridges,Completed,J-Bridges,,5519000,"Improvement to Existing Munroe Bridge across Cooum River at Mc Nichols Road near the Jn. Of Harrington Road and Valluvar Kottam High Road in Division - 110 ,Zone -IX",Own Sources,Greater Chennai Corporation,2014-15,2017-18 J/2014-15/30137,Bridges,Completed,J-Bridges,,5504000,"Improvements to the Existing Bridge in Anna Arch Road near K3 Aminjikarai Police station in Dn-100,Unit-22,Zone-VIII",Own Sources,Greater Chennai Corporation,2014-15,2016-17 J/2014-15/6212,Bridges,Completed,J-Bridges,,4812000,DEMOLITION THE EXISTING FOOTPATH BRIDGE AND CONSTRUCTION OF BOX CULVERT 5 VENT AT DR.SUBBARAO NAGAR IN DN 108 U 22 ZONE VIII,Own Sources,Greater Chennai Corporation,2014-15,2017-18 J/2014-15/6843,Culvert,Completed,J-Bridges,,3930000,"Demolition the Existing Foot over bridge and Re - Construction of Box Culvert (4 vent) at Vada Agaram in Dn: 109,U-24, Zone ?IX",Own Sources,Greater Chennai Corporation,2014-15,2018-19 RN/2014-15/21982,Parks,Completed,P-Parks and Playfields,,700000,"FORMATION OF PATHWAY,CONSTRUCTION OF GAZEBO, GREENARY WORKS AND OTHER IMPROVEMENTS WORK TO THE EXISTING PARK AT TIRUVALLUVAR STREET IN DN-23, ZONE - III .",Grants,1,2014-15,2017-18 S/2014-15/12311,Footpath,Completed,BR-Bus Route Roads,,17800000,FORMING FOOTPATH AT SIDCO NAGAR MAIN ROAD FROM JUNCTION OF MEENAMBAL SALAI TO JUNCTION OF TONDIARPET HIGH ROAD IN DN 36 ZONE IV,Grants,4,2014-15,2016-17 D/2014-15/27529,Storm Water Drain,Completed,D-Storm Water Drains,,264762000,Construction of Integrated Storm water drain in Nolambur watershed of Cooum Basin in expanded area of Chennai Corporation- Package -21,Loans And Grants,7,2014-15,2018-19 D/2014-15/27533,Storm Water Drain,Completed,D-Storm Water Drains,,411123000,Construction of Integrated Storm water drain in Nolambur watershed of Cooum Basin in expanded area of Chennai Corporation- Package -23,Loans And Grants,7,2014-15,2019-20 D/2014-15/26757,Storm Water Drain,Completed,D-Storm Water Drains,,170940000,Construction of Integrated Storm water drain in Virugambakkam ? Arumbakkam watershed of Cooum Basin in expanded area of Chennai Corporation- Package -26,Loans And Grants,11,2014-15,2018-19 D/2014-15/27384,Storm Water Drain,Completed,D-Storm Water Drains,,333381000,Construction of Integrated Storm water drain in Virugambakkam ? Arumbakkam watershed of Cooum Basin in expanded area of Chennai Corporation- Package -27,Loans And Grants,11,2014-15,2018-19 B/2015-16/0339,Buildings,Completed,B-Buildings,116,36590000,"PROPOSED CONSTRUCTION OF COMMUNITY CENTRE AT VENKATARANGAN PILLAI STREET , TRIPLICANE, CHENNAI.",Own Sources,9,2015-16,2017-18 B/2015-16/10261,Buildings,Completed,B-Buildings,184,96061612,"Proposed construction of Community health centre (100 bed Hospital) in School road, Perungudi, Ward 184 , Zone 14",Own Sources,14,2015-16,2019-20 B/2015-16/10510,Buildings,Completed,B-Buildings,169,3300000,"Supplying , Erecting and Commissioning the Gasifier with necessary Civil Construction in Burial Ground , Puzhuthivakkam , Ward 169, Zone 14",Own Sources,14,2015-16,2017-18 B/2015-16/1069,Buildings,Completed,B-Buildings,7,50700000,"CONSTRUCTION OF LORRY OPERATIONAL DEPOT AT MANALI ROAD ,TIRUVOTTIYUR IN DN-07, UNIT-2, ZONE-I.",Own Sources,1,2015-16,2017-18 B/2015-16/10710,Buildings,Completed,B-Buildings,70,14000000,CONSTRUCTION OF CYCLE SHED IN G.F. AND MODERN AUDITORIUM IN F.F. IN CGHSS AT SCHOOL ROAD (M.H. ROAD) PERAMBUR IN DN-70 ZONE-6,MLACDS,6,2015-16,2019-20 B/2015-16/10812,Buildings,Completed,B-Buildings,151,153681143,"Proposed construction of Community health centre (100 bed Hospital) at hospital road in Valasarwakkam, Ward 151 , Unit- 34, Zone 11",Own Sources,11,2015-16,2019-20 B/2015-16/12529,Buildings,Completed,B-Buildings,53,7000000,"DEMOLITION OF THE EXISTING S.S.A ANNEX BUILDING AND RECONSTRUCTION OF ADDITIONAL CLASS ROOMS FOR CHENNAI URUDU GIRLS MIDDLE SCHOOL IN DIV- 53 , ZONE-V",Own Sources,5,2015-16,2016-17 B/2015-16/15499,Buildings,Completed,B-Buildings,23,69000000,"Proposed Construction of Primary Health Centre at Puzhal,Dn-23,Zone-III",Own Sources,3,2015-16,2020-21 B/2015-16/16889,Buildings,Completed,B-Buildings,39,20400000,CONSTRUCTION OF REST ROOM IN G.F AND F.F(5+5) WITH STAIR CASE AND TOILET BLOCK FOR DHOBHIKAHNA AT BUCHAMMAL STREET IN DN 39 ZONE 4,Own Sources,4,2015-16,2018-19 B/2015-16/1744,Buildings,Completed,B-Buildings,58,2500000,"REPAIRS AND IMPROVEMENT WORKS TO RIPON BUILDINGS CAMPUS IN DN-58, ZONE-V.",Own Sources,5,2015-16,2016-17 B/2015-16/17909,Buildings,Completed,B-Buildings,58,560000,SUPPLY AND FIXING OF WORKSTATION FOR 1913 PGR COMPLAINT CELL IN AMMA MAALIGAI AT RIPON BUILDING CAMPUS IN DN 58 ZONE 5.,Own Sources,5,2015-16,2016-17 B/2015-16/1829,Buildings,Completed,B-Buildings,90,5722042,"CONSTRUCTION OF NNMP SHED AT GROUND FLOOR &DIVISION OFFICE AT FIRST FLOOR IN PADIKUPPAM MAIN ROAD IN DN-90,ZONE-7",Own Sources,7,2015-16,2017-18 B/2015-16/2197,Buildings,Completed,B-Buildings,12,5430000,"Proposed Construction of Division Office-12 at Balakrishna Nagar,3rd Cross St,Dn 12, Zone-I",Own Sources,1,2015-16,2016-17 B/2015-16/22631,Buildings,Completed,B-Buildings,N04,17000000,"PROPOSED CONSTRUCTION OF COMMUNITY CENTRE AT KUMMALAMMAN KOVIL STREET IN DIVISION -43,ZONE - 4",MLACDS,,2015-16,2017-18 B/2015-16/22986,Buildings,Completed,B-Buildings,N02,39413400,"CONSTRUCTION OF COMMUNITY CENTRE IN SECOND AND THIRD FLOOR AT KUMMALAMMAN KOIL STREET IN DIV-43, ZONE-4",Own Sources,,2015-16,2019-20 B/2015-16/24495,Buildings,Completed,B-Buildings,156,3500000,"Supplying , Erecting and Commissioning the Gasifier with necessary Civil Construction in Burial Ground , Mugalivakkam , Ward 156, Zone 12",Own Sources,12,2015-16,2017-18 B/2015-16/24501,Buildings,Completed,B-Buildings,196,3750000,"Supplying , Erecting and Commissioning the Gasifier with necessary Civil Construction in Burial Ground , Injambakkam , Ward 196, Zone 15",Own Sources,15,2015-16,2017-18 B/2015-16/24504,Buildings,Completed,B-Buildings,23,3500000,"Supplying , Erecting and Commissioning the Gasifier with necessary Civil Construction in Burial Ground ,G.N.T.Road , Madhavaram , Ward 23, Zone 3",Own Sources,3,2015-16,2017-18 B/2015-16/24509,Buildings,Completed,B-Buildings,18,3500000,"Supplying , Erecting and Commissioning the Gasifier with necessary Civil Construction in Burial Ground , CBCL Layout, Manali, Ward 18, Zone 2",Own Sources,2,2015-16,2018-19 B/2015-16/24522,Buildings,Completed,B-Buildings,184,3500000,"Supplying , Erecting and Commissioning the Gasifier with necessary Civil Construction in Burial Ground , Perungudi, Ward 184, Zone 14",Own Sources,14,2015-16,2018-19 B/2015-16/26183,Buildings,Completed,B-Buildings,195,56600000,"PROPOSED CONSTRUCTION OF PRIMARY SCHOOL (G+1F , 8+10 CLASSROOMS) IN 3RD MAIN ROAD, EZHIL NAGAR ,WARD 195 , UNIT 44, ZONE 15","Loans, Grants And Own Sources",15,2015-16,2018-19 B/2015-16/2934,Buildings,Completed,B-Buildings,52,4300000,CONSTRUCTION OF NIGHT SHELTER AT STANLEY HOSPITAL IN OLD JAIL ROAD CHENNAI - 600001 DIVISION 52 ZONE 5,Loans,5,2015-16,2016-17 B/2015-16/2935,Buildings,Completed,B-Buildings,52,4300000,CONSTRUCTION OF NIGHT SHELTER AT RSRM HOSPITAL IN CEMETRY ROAD ROYAPURAM CHENNAI-600013 DIVISION 50 ZONE 5,Loans,5,2015-16,2016-17 B/2015-16/30233,Buildings,Completed,B-Buildings,120,7025000,"Construction of New Retail Fish Market with compound wall at Nadukuppam in Dn.120,Zone-9.",Grants,9,2015-16,2019-20 B/2015-16/30497,Electrical,Completed,B-Buildings,20,979900,"Supply and Installation,aiming,testing and commissioning of 20 mtr high mast with 12 nos of 2 x 400w (metal halide-Tubular Lamp) asymmetrical floodlight fittings complete set fitting at newly constructed LORRY DEPOT in Kamarajar salai in Ward-20/Zone-2",Own Sources,2,2015-16,2016-17 B/2015-16/30506,Electrical,Completed,B-Buildings,20,930700,Supply and laying of cables for various machinary erect at newly constructed LORRY DEPOT in kamarajar salai in ward -20/zone-2,Own Sources,2,2015-16,2016-17 B/2015-16/30668,Buildings,Completed,B-Buildings,106,8375000,"CONSTRUCTION OF COMMUNITY CENTRE AT COLLECTORATE COLONY 6th STREET, AMINJIKARAI IN DN-106, Z-8",MLACDS,8,2015-16,2019-20 B/2015-16/30808,Buildings,Completed,B-Buildings,169,5300000,"Construction of Division office 169 at Puzhuthivakkam main road , Ward 169 , Unit 42 , Zone 14",Own Sources,14,2015-16,2019-20 B/2015-16/31527,Buildings,Completed,B-Buildings,74,17067637,"CONSTRUCTION OF NEW RETAIL FISH MARKET AT NAMMALWARPET, AYANAVARAM IN DN-74 Z-6",Own Sources,6,2015-16,2019-20 B/2015-16/3250,Buildings,Completed,B-Buildings,43,10800000,"CONSTRUCTION OF GASIFIER IN BURIAL GROUND AT SASTHRI NAGAR IN WARD 28, ZONE-3",Own Sources,4,2015-16,2017-18 B/2015-16/33958,Buildings,Completed,B-Buildings,58,1890000,"PROPOSED CONSTRUCTION OF SUMP WITH WATER SUPPLY ARRANGEMENTS FOR PROPOSED ANM TRAINING STUDENTS HOSTEL AND VOLLEY BALL AND BASKET BALL COURTS IN CD HOSPITAL CAMPUS AT TONDIARPET IN DN-42, ZONE-IV.",Own Sources,5,2015-16,2016-17 B/2015-16/34332,Buildings,Completed,B-Buildings,199,6474802,"Construction of Division office 199 at Bajana Koil Street , Uthandi , Ward 200 , Zone 15",Own Sources,15,2015-16,2019-20 B/2015-16/3587,Buildings,Completed,B-Buildings,148,13800000,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTER AT NERKUNDRAM IN DN-148-UNIT-33,ZONE-XI",Own Sources,11,2015-16,2017-18 B/2015-16/3594,Buildings,Completed,B-Buildings,170,13800000,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTER AT EKATUTHANGAL ANNA SALAI (NEXT TO AGS CHRUCH) IN DN-170-UNIT- ,ZONE-XIII",Own Sources,13,2015-16,2019-20 B/2015-16/4522,Buildings,Completed,B-Buildings,193,6219737,"Construction of division office 193 at Rajiv Gandhi Salai , OMR , Okkiyam Thoraipakkam, Ward 193 , Zone 15",Own Sources,15,2015-16,2016-17 B/2015-16/4698,Buildings,Completed,B-Buildings,200,5340000,"Construction of division office 200 at Pazhanthota Salai , Chemenchery , Ward 200 , Zone 15",Own Sources,15,2015-16,2016-17 B/2015-16/4776,Buildings,Completed,B-Buildings,188,7940000,"Proposed Construction of Unit office 42 cum Division office 188 at Ambedkar Street , Madipakkam , Ward 188 , Unit 42 , Zone 14.",Own Sources,14,2015-16,2017-18 B/2015-16/4796,Buildings,Completed,B-Buildings,197,3390000,"Construction of a Compound wall and flooring for car parking for community centre , Gajarajan Salai , Karapakkam , Ward 197 , Zone 15.",Own Sources,15,2015-16,2016-17 B/2015-16/4802,Buildings,Completed,B-Buildings,150,5340000,"CONSTRUCTION OF DIVISION OFFICE 150 AT PONNI NAGAR , KARAMBAKKAM , WARD-150 , ZONE-11",Own Sources,11,2015-16,2017-18 B/2015-16/4958,Buildings,Completed,B-Buildings,58,4800000,"PROPOSED LANDSCAPE DEVELOPMENT FOR RIPON BUILDING ANNEXE IN DN-58, ZONE-V.",Own Sources,5,2015-16,2020-21 B/2015-16/5901,Buildings,Completed,B-Buildings,121,10305000,"Proposed Construction of UPHC at Meccapuram in Dn-121, Zone-IX",Own Sources,9,2015-16,2017-18 B/2015-16/6097,Buildings,Completed,B-Buildings,61,4937037,CONSTRUCTION OF NIGHT SHELTER BUILDING INSIDE CHILDRENS HOSPITAL IN HALLS ROAD EGMORE DIVISION-61 ZONE-5,Loans,5,2015-16,2016-17 B/2015-16/6418,Buildings,Completed,B-Buildings,73,22710000,"proposed construction of additional block for E.O.C maternity hospital at Pulianthope in Dn-73, Zone-VI",Own Sources,6,2015-16,2017-18 B/2015-16/6453,Buildings,Completed,B-Buildings,180,12800000,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTER (UPHC) AT GODHAVARI STREET ,THARAMANI IN DN-180, Z-13",Own Sources,13,2015-16,2017-18 B/2015-16/6464,Buildings,Completed,B-Buildings,43,5162000,CONSTRUCTION OF WARD OFFICE IN DIVISION 43 IN ZONE - 4,Own Sources,4,2015-16,2016-17 B/2015-16/6526,Buildings,Completed,B-Buildings,192,12800000,"Construction of UPHC in Kabaleeswarar nagar main road , Neelankarai , Ward 192 , Zone 15",Own Sources,15,2015-16,2017-18 B/2015-16/6630,Buildings,Completed,B-Buildings,102,3000000,"Additional works for community centre at T.P chatram in DN-102, ZN-8",MLACDS,8,2015-16,2016-17 B/2015-16/8162,Buildings,Completed,B-Buildings,58,4300000,"CONSTRUCTION OF NIGHT SHELTER AT RAJIV GANDHI GOVT GENERAL HOSPITAL DIVISION-58 ZONE-5 NO-1 EVR PERIYAR SALAI , PARK TOWN , CHENNAI - 600003",Earmarked Fund,5,2015-16,2016-17 B/2015-16/8166,Buildings,Completed,B-Buildings,58,4300000,"CONSTRUCTION OF NIGHT SHELTER 2 AT RAJIV GANDHI GOVERNMENT GENERAL HOSPITAL AT 1, EVR PERIYAR SALAI , PARK TOWN , CHENNAI-600003, DIVISION- 58, ZONE-5",Earmarked Fund,5,2015-16,2019-20 B/2015-16/8171,Buildings,Completed,B-Buildings,61,4935813,"CONSTRUCTION OF NIGHT SHELTER IN INSTITUTE OF OBSTETRICS AND GYNAECOLOGY AND GOVERNMENT HOSPITAL FOR WOMEN AND CHILDREN WARD-61, EGMORE POLICE COMMISIONER ROAD",Earmarked Fund,5,2015-16,2016-17 B/2015-16/8173,Buildings,Completed,B-Buildings,61,4300000,CONSTRUCTION OF NIGHT SHELTER 2 AT IOG - INSTITUTE OF OBSTETRICS AND GYNAECOLOGY IN POLICE COMMISIONER ROAD EGMORE,Earmarked Fund,5,2015-16,2016-17 B/2015-16/8174,Buildings,Completed,B-Buildings,61,4300000,CONSTRUCTION OF NIGHT SHELTER 2 AT GOVT EGMORE CHILDRENS HOSPITAL HALLS ROAD DIVISION 61 ZONE 5,Earmarked Fund,5,2015-16,2018-19 B/2015-16/8176/C,Buildings,Completed,B-Buildings,55,4300000,CONSTRUCTION OF NIGHT SHELTER 2 AT GOVT.STANLEY HOSPITAL IN OLD JAIL ROAD DIVISION 55 ZONE - 5,Earmarked Fund,5,2015-16,2016-17 B/2015-16/8178/C,Buildings,Completed,B-Buildings,52,4300000,"CONSTRUCTION OF NIGHT SHELTER 2 AT GOVT.RSRM HOSPITAL ROYAPURAM , CEMETRY ROAD DIVISION - 52 ZONE - 5",Earmarked Fund,5,2015-16,2016-17 B/2015-16/8185,Buildings,Completed,B-Buildings,160,12800000,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTER (UPHC) AT APPAVU STREET AT ALANDHUR IN DN-160, zone 12",Own Sources,12,2015-16,2018-19 B/2015-16/8294,Buildings,Completed,B-Buildings,103,4300000,"CONSTRUCTION OF NIGHT SHELTER BUILDING-2 IN KILPAUK MEDICAL COLLEGE IN DN.103, ZONE-8",Own Sources,8,2015-16,2016-17 B/2015-16/8332,Buildings,Completed,B-Buildings,174,15800000,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTER (UPHC) AND DIVISION OFFICE AT FIVE FURLONG ROAD , MADUVANKARAI IN DN-174, Z-13",Own Sources,13,2015-16,2016-17 B/2015-16/8366,Buildings,Completed,B-Buildings,108,4300000,"CONSTRUCTION OF NIGHT SHELTER BUILDING-1 IN KILPAUK MEDICAL COLLEGE IN DN.103, ZONE-8.",Own Sources,8,2015-16,2016-17 B/2015-16/9124,Buildings,Completed,B-Buildings,195,106264029,"CONSTRUCTION OF UPHC (30 BED HOSPITAL) IN 2ND MAIN ROAD, KANNAGI NAGAR, THORAIPAKKAM, WARD 195, UNIT 44, ZONE 15",Own Sources,15,2015-16,2019-20 BR/2015-16/0425,Roads,Completed,BR-Bus Route Roads,62,7675000,"Laying of Cement Concrete road at East Coovam Road from Junction of Laben lane to West Coovam road in DIv 62,Zone-5",Own Sources,5,2015-16,2016-17 BR/2015-16/0753,Footpath,Completed,BR-Bus Route Roads,60,24950000,"Forming Foot path at N S C BOSE ROAD (Northern Side) from rattan bazaar road to rajaji salai in Div - 59 & 60, Zone -5",Grants,5,2015-16,2017-18 BR/2015-16/0760,Footpath,Completed,BR-Bus Route Roads,60,24890000,"Forming Foot path at N S C BOSE ROAD (Southern Side) from rattan bazaar road to rajaji salai in Div - 59 & 60, Zone -5.",Grants,5,2015-16,2017-18 BR/2015-16/10025,Roads,Completed,BR-Bus Route Roads,172,1102000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Ponniamma Koil Street in Div - 172 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/10028,Roads,Completed,BR-Bus Route Roads,170,1102000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Jawaharlal Nehru Road near shall pumps in Div - 170 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/10031,Roads,Completed,BR-Bus Route Roads,170,1102000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Jawaharlal Nehru Road near MRF in Div - 170 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/10301,Roads,Completed,BR-Bus Route Roads,47,4100000,"Improvement to FOOT Path work at KATTIVAKKAM HIGH ROAD in Division 47,Zone-4.",Own Sources,4,2015-16,2016-17 BR/2015-16/10514,Roads,Completed,BR-Bus Route Roads,28,4871000,"Restoration of Road Cut at Madhavaram Milk Colony (From the Junction of Kamarajar Salai to a length of 1500 Meters) by TNEB in Dn-28, Zone-03",Deposit Works,3,2015-16,2016-17 BR/2015-16/10701,Roads,Completed,BR-Bus Route Roads,60,4301000,"Providing Crash Barrier Type Centre Median at Rajaji Salai ( From Jaffarshang Street to Krishna Koil Street) in Dn-60, Zone-5",Own Sources,5,2015-16,2016-17 BR/2015-16/10702,Roads,Completed,BR-Bus Route Roads,N13,920000,Proposed Renovation & Rectification of Electrical Fitting in the existing Modern Bus Shelter in South Region,Own Sources,,2015-16,2016-17 BR/2015-16/10703,Roads,Completed,BR-Bus Route Roads,N13,995000,REMOVING THE EXISTING BANNERS FROM THE MODERN STAINLESS STEEL BUS SHELTERS AND FIXING THE NEW BANNERS WITH GOVERNMENT SCHEMES IN SOUTH REGION,Own Sources,,2015-16,2016-17 BR/2015-16/10704,Roads,Completed,BR-Bus Route Roads,N13,983000,REMOVING THE EXISTING FACIA FROM THE MODERN STAINLESS STEEL BUS SHELTERS AND FIXING THE NEW FACIA WITH GOVERNMENT SCHEMES IN SOUTH REGION,Own Sources,,2015-16,2016-17 BR/2015-16/11082,Roads,Completed,BR-Bus Route Roads,73,1133000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Dr. Ambedkar Colleger Road ( Opp to P1 Police Station)) in Div 73 , Zone 6 under MLA Scheme",MLACDS,6,2015-16,2017-18 BR/2015-16/11083,Roads,Completed,BR-Bus Route Roads,72,1133000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Dr. Ambedkar Colleger Road ( Near Kannigapuram Playground ) in Div 72 , Zone 6 under MLA Scheme",MLACDS,6,2015-16,2017-18 BR/2015-16/11086,Roads,Completed,BR-Bus Route Roads,70,1133000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Perambur High Road (S) Mangalapuram Bus Stop in Div 70 , Zone 6 under MLA Scheme",MLACDS,6,2015-16,2017-18 BR/2015-16/11088,Roads,Completed,BR-Bus Route Roads,70,1133000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Perambur High Road (N) Opp to Perambur Bus Terminous in Div 70 , Zone 6 under MLA Scheme",MLACDS,6,2015-16,2017-18 BR/2015-16/11094,Footpath,Completed,BR-Bus Route Roads,176,691000,"Repair and improvement of footpath with Black and White Painting at Dr. DGS Dinakaran Salai Road in Div 173, Zone - 13.",Own Sources,13,2015-16,2016-17 BR/2015-16/11102,Roads,Completed,BR-Bus Route Roads,60,2413000,"Providing Crash Barrier Type Centre Median at Rajaji Salai ( From Krishna Koil Street to Cive Battery ) in Dn-60, Zone-5",Own Sources,5,2015-16,2016-17 BR/2015-16/11114,Roads,Completed,BR-Bus Route Roads,N08,880000,"Proposed construction of One no. Of Modern Bus Shelter of size 6 x 2.5 m at Anna nagar 4th Avenue (Near Natesan Co operative Bank And College) in Dn-99 , Zone -8 Under MLA Scheme 2014 - 2015",MLACDS,,2015-16,2016-17 BR/2015-16/11406,Roads,Completed,BR-Bus Route Roads,129,978000,"Attending Patch Work at NSK Salai in Dn-129, Zone-10 (Center median South side) From jn of Aiwartirunagar to the jn of Vembuli amman koil street",Own Sources,10,2015-16,2016-17 BR/2015-16/11953,Roads,Completed,BR-Bus Route Roads,145,39000000,"Formation of Cement Concrete road ,crash barrier and footpath in Tamil Nadu Housing Board (Gifted Land )at Natesan Nagar (Nerkundram) div-145, unit-32,zone-11.",Grants,11,2015-16,2018-19 BR/2015-16/12394,Roads,Completed,BR-Bus Route Roads,136,989000,"Attending Footpath repair Works at Thyagaraya Road (South Side) in Dn-136,Zone-10",Own Sources,10,2015-16,2016-17 BR/2015-16/12627,Roads,Completed,BR-Bus Route Roads,113,913000,Attending Patch Work at Kodambakkam High Road in Dn-113 and other various Bus Route Roads in Zone-9,Own Sources,9,2015-16,2016-17 BR/2015-16/12628,Roads,Completed,BR-Bus Route Roads,110,981000,"Repairs and Maintenance of existing Centre Median and Footpath and other various Improvements at Valluvar Kottam High Road in Dn-110, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/12629,Roads,Completed,BR-Bus Route Roads,113,997000,"Repairs and Maintenance of existing Centre Median , Footpath and other various Traffic Improvements at Kodambakkam High Road in Dn-113, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/12762,Footpath,Completed,BR-Bus Route Roads,119,616000,"Attending Emergency patch work with CBC 40mm thick by paver finisher at Dr.Radhakrishnan salai service road (Northern side - reach 2) in Dn - 119, Zone - 9",Own Sources,9,2015-16,2016-17 BR/2015-16/12849,Roads,Completed,BR-Bus Route Roads,110,997000,Attending Patch Work at Valluvar Kottam High Road in Dn-110 and other various Bus Route Roads in Zone-9,Own Sources,9,2015-16,2016-17 BR/2015-16/12850,Roads,Completed,BR-Bus Route Roads,110,571000,Repairs and Maintenance of Traffic Improvement Work at Valluvar Kottam High Road in Dn-110 and various Bus Route Roads in Zone-9,Own Sources,9,2015-16,2016-17 BR/2015-16/12852,Roads,Completed,BR-Bus Route Roads,123,919000,"Proposed Road and Traffic Improvements at St.Marrys Road and Kutchery Road in Dn-123, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/12854,Roads,Completed,BR-Bus Route Roads,115,963000,"Patch Work and Traffic Improvements at West Cott Road, Conronsmith Road, Woods Lane in Dn-115, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/12862,Roads,Completed,BR-Bus Route Roads,136,645000,"Traffic Improvements at Dr.Nair Road and Burkit Road in Dn-136, Zone-10",Own Sources,10,2015-16,2016-17 BR/2015-16/1298,Roads,Completed,BR-Bus Route Roads,70,1097000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Dr. Ambedkar Colleger Road ( Near Slaughter House ) in Div 70 , Zone 6",MLACDS,6,2015-16,2016-17 BR/2015-16/13745,Footpath,Completed,BR-Bus Route Roads,61,12600000,"FORMING FOOT PATH AT EGMORE HIGH ROAD FROM THE JN OF MAYOR RAMANATHAN SALAI TO HALLS ROAD IN DN 61, ZONE V",Own Sources,5,2015-16,2017-18 BR/2015-16/13955,Roads,Completed,BR-Bus Route Roads,102,716000,"Restoration of road cut made by TANGEDCO at Kilpauk Garden Road southern side (from 200 - 340 m to junction of T.P.Chathiram main road ) in div - 102, Zone - 08. (Challan No: BR/2015-16/0000954.)",Deposit Works,8,2015-16,2016-17 BR/2015-16/13997,Roads,Completed,BR-Bus Route Roads,103,198500,Attending patches at Purasaivakkam high road & Anna nagar 6th avenue and Other various bus route roads in Zone - 8,Own Sources,8,2015-16,2016-17 BR/2015-16/14053,Roads,Completed,BR-Bus Route Roads,174,28900000,STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT CITY LINK ROAD IN WARD 174 &177 ZONE 13,"Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14054,Roads,Completed,BR-Bus Route Roads,174,4370000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT CHAKARAPANI STREET IN WARD 174, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14055,Roads,Completed,BR-Bus Route Roads,177,6110000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT KAKAN NAGAR MAIN ROAD IN WARD 177, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14056,Roads,Completed,BR-Bus Route Roads,177,2810000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT SHASTRI NAGAR MAIN ROAD IN WARD 177, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14057,Roads,Completed,BR-Bus Route Roads,170,7280000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT AALANDHUR ROAD IN WARD 170, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14059,Roads,Completed,BR-Bus Route Roads,170,25160000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT KATHIPARA ROAD IN WARD 170, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14061,Roads,Completed,BR-Bus Route Roads,177,1200000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT LAKE VIEW ROAD N WARD 177 ,ZONE 13`","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14062,Roads,Completed,BR-Bus Route Roads,174,12280000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT FIVE FURLONG ROAD N WARD 174, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14063,Roads,Completed,BR-Bus Route Roads,179,17770000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT GANDHI ROAD IN WARD 179, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14085,Roads,Completed,BR-Bus Route Roads,180,22120000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT KALKI KRISHNAMURTHY SALAI (PART) IN WARD180, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14086,Roads,Completed,BR-Bus Route Roads,176,4280000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT SRINIVASA AVENUE IN WARD 176, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14087,Roads,Completed,BR-Bus Route Roads,174,16410000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISH USING PLASTIC WASTE ALONG TRAFFIC IMPROVEMENT WORKS AT RACE COURSE ROAD IN WARD 174, ZONE 13","Loans, Grants And Own Sources",13,2015-16,2016-17 BR/2015-16/14103,Roads,Completed,BR-Bus Route Roads,102,995000,"Restoration of road cut made by TANGEDCO at Kilpauk Garden Road southern side (from junction of pulla avenue 0 - 200 m) in div - 102, Zone - 08. (Challan No: BR/2015-16/0000954.)",Deposit Works,8,2015-16,2016-17 BR/2015-16/14158,Roads,Completed,BR-Bus Route Roads,59,15400000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at EVENING BAZAR ROAD from RATTAN BAZZAR ROAD to EVR SALAI IN DIVISION -59 , ZONE -05.",Grants,5,2015-16,2017-18 BR/2015-16/14159,Roads,Completed,BR-Bus Route Roads,60,17300000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at FLAG STAFF ROAD from RAJAJI SALAI to JN OF MUTHU SAMY OVER BRIDGE and Anna Salai IN DIVISION -60 , ZONE -05.",Grants,5,2015-16,2017-18 BR/2015-16/1416,Roads,Completed,BR-Bus Route Roads,58,1190000,Proposed Construction of Modern Stainless Steel Bus Shelter at CHOOLAI HIGH ROAD (Near Ramalinga vilas) in Div-58 in Zone-5,MPLADS,5,2015-16,2017-18 BR/2015-16/14160,Roads,Completed,BR-Bus Route Roads,60,12400000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Arunachalam street from jn of gandhi irwin bridge road and pantheon road to deputy mayor kabala moorty sal.ai IN DIVISION -60 , ZONE -05.",Grants,5,2015-16,2017-18 BR/2015-16/14161,Roads,Completed,BR-Bus Route Roads,61,4220000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Dr. Nair bridge road from jn of gandhi irwin bridge road and police commisioner office road to EVR salai IN DIVISION -61 , ZONE -05.",Grants,5,2015-16,2017-18 BR/2015-16/14162,Roads,Completed,BR-Bus Route Roads,56,15500000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Old jail road from prakasam salai to jn of vallalar nagar and parthasarathy over bridge IN DIVISION -55 & 56 , ZONE -05.",Grants,5,2015-16,2017-18 BR/2015-16/14163,Roads,Completed,BR-Bus Route Roads,56,19600000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at Muthu samy salai from EVR salai to jn of North fort road and Esplanade road IN DIVISION -55 & 56&57 , ZONE -05.",Grants,5,2015-16,2017-18 BR/2015-16/14164,Roads,Completed,BR-Bus Route Roads,49,11100000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at Pan Rajarathinam salai from Kumbala,mman kovil street to West Kalmandabam road IN DIVISION -49 , ZONE -05.",Grants,5,2015-16,2017-18 BR/2015-16/14185,Roads,Completed,BR-Bus Route Roads,36,5600000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at SIDCO MAIN ROAD from TONDAIRPET HIGH ROAD to TVK 2ND LINK ROAD IN DIVISION -36 , ZONE -04.",Grants,4,2015-16,2017-18 BR/2015-16/14186,Roads,Completed,BR-Bus Route Roads,41,6500000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at MANALI ROAD from TONDAIRPET HIGH ROAD to KORUKPET FIRE STATION IN DIVISION -41 , ZONE -04.",Grants,4,2015-16,2017-18 BR/2015-16/14187,Roads,Completed,BR-Bus Route Roads,45,4900000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at AA ROAD from STEPHENSON ROAD to BSNL Telephone Quartres IN DIVISION -45 , ZONE -04.",Grants,4,2015-16,2017-18 BR/2015-16/14188,Roads,Completed,BR-Bus Route Roads,45,29100000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at MAEL PATTI PONNAPPAN STREET from SUBASH CHANDRABOSH STREET to STEPHENSON LANE IN DIVISION -45 & 44 , ZONE -04.",Grants,4,2015-16,2017-18 BR/2015-16/14189,Roads,Completed,BR-Bus Route Roads,33,10100000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at Madhavaram high road from GNT Road TO EB OFFICE ROAD IN DIVISION -33 , ZONE -03.",Grants,3,2015-16,2017-18 BR/2015-16/14190,Roads,Completed,BR-Bus Route Roads,38,35900000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at ENNORE high road from MANALI SALAI to PARAMAESHWARI NAGAR IN DIVISION -38 , ZONE -04.",Grants,4,2015-16,2017-18 BR/2015-16/14191,Roads,Completed,BR-Bus Route Roads,34,11000000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at Thiruvalluvar salai from Muthamil nagar 5th main road to Kamaraj salai IN DIVISION -34 , ZONE -04.",Grants,4,2015-16,2017-18 BR/2015-16/14207,Roads,Completed,BR-Bus Route Roads,119,620000,"Attending Emergency patch work with BC 40mm thick at DR.Radhakrishnan Salai service road(Northern side) from the jn of TTK road to the jn of P.S Siva samy salai (Reach - 1) in Dn -119 , Zone - 9",Own Sources,9,2015-16,2016-17 BR/2015-16/14208,Roads,Completed,BR-Bus Route Roads,118,993000,"Attending emergency patch work at chevaliar Sivajiganesan salai in Dn - 117, Zone - 9",Own Sources,9,2015-16,2016-17 BR/2015-16/14237,Roads,Completed,BR-Bus Route Roads,142,16752000,"Strengthing and Relaying the Road with DBM and CBC after cold milling by Paver Finisher using Plastic waste along with Traffic Improvement Works at Govindan Road from the Junction Reddy Kuppam Road to the Jn of Ashok Nagar 11th Avenue in Dn-142, Zone-10",Grants,10,2015-16,2016-17 BR/2015-16/14238,Roads,Completed,BR-Bus Route Roads,95,198000,Attending patches at anna nagar 18th main road and Other various bus route roads in Zone - 8,Own Sources,8,2015-16,2016-17 BR/2015-16/14240,Roads,Completed,BR-Bus Route Roads,103,197000,Attending Patch work at Kilpauk garden Road and Ormes road And Other various Bus route roads in Zone - 8,Own Sources,8,2015-16,2016-17 BR/2015-16/14243,Roads,Completed,BR-Bus Route Roads,134,7866000,"Strengthening and Relaying the Road with DBM and CBC after Cold milling by Paver finisher using Plastic Waste along with Traffic Improvement Work at Rangarajapuram Main Road (part) from the Jn of NSK Salai to the Jn of Rathiammal Street in Dn-134, Zone-10",Grants,10,2015-16,2017-18 BR/2015-16/14246,Roads,Completed,BR-Bus Route Roads,118,10130000,"Strengthening and Relaying the Road with DBM and CBC after Cold milling by Paver finisher using Plastic Waste along with Traffic Improvement Work at Avvai Shanumugam Salai from the Jn of conrorn smith road to the Jn of TTk Salai in Dn-118, Zone-9",Grants,9,2015-16,2016-17 BR/2015-16/14248,Roads,Completed,BR-Bus Route Roads,107,15830000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at McNichols Road from the Jn of Valluvar Kottam high Road the Jn of Periyar EVR Salai in Dn-107, Zone-8",Grants,8,2015-16,2016-17 BR/2015-16/14249,Roads,Completed,BR-Bus Route Roads,103,10863000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Burnaby Road from the Jn of Periyar EVR Salai to the Jn of Ormes Road in Dn-103, Zone-8",Grants,8,2015-16,2016-17 BR/2015-16/14253,Roads,Completed,BR-Bus Route Roads,94,6590000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Rajamangalam Main Road from the Jn of Vilivakkam Redhills Road North to the Jn of R.K Link Road in Dn-94, Zone-8",Grants,8,2015-16,2016-17 BR/2015-16/14257,Roads,Completed,BR-Bus Route Roads,94,8807000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Villivakkam redhills road (North) from the Jn of Vilivakkam Redhills Road South to the Jn of Srinivas Nagar 1st Main Road a in Dn-94, Zone-8",Grants,8,2015-16,2016-17 BR/2015-16/14289,Footpath,Completed,BR-Bus Route Roads,107,26000000,"FORMING FOOT PATH AT MAYOR RAMANATHAN SALAI FROM THE JN OF EAST RAMANATHAN SALAI TO VALLUVAR KOTTAM HIGH ROAD IN DN 107, ZONE VIII",Own Sources,8,2015-16,2017-18 BR/2015-16/14291,Footpath,Completed,BR-Bus Route Roads,61,23900000,"FORMING FOOT PATH AT LANGS GARDEN ROAD FROM THE JN OF ADHITHANAR ROAD TO PANTHEON ROAD JUNCTION IN DN 61, ZONE V",Own Sources,5,2015-16,2017-18 BR/2015-16/14295,Footpath,Completed,BR-Bus Route Roads,61,31300000,"FORMING FOOT PATH AT RUKMANI LAKSHMIPATHI SALAI FROM THE JN OF PANTHEON ROAD TO BINNY ROAD IN DN 61, ZONE V",Own Sources,5,2015-16,2017-18 BR/2015-16/14309,Footpath,Completed,BR-Bus Route Roads,61,20300000,"FORMING FOOT PATH AT ADHITHANAR SALAI FROM THE JN OF PANTHEON ROAD TO DAMS ROAD IN DN 61, ZONE V",Own Sources,5,2015-16,2017-18 BR/2015-16/14335,Roads,Completed,BR-Bus Route Roads,180,8322000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at West avenue from the junction of Kalkikrishna Murthy Road to the Junction of Rajiv Gandhi Salai in Dn 180 Zone - 13,Grants,13,2015-16,2016-17 BR/2015-16/14337,Roads,Completed,BR-Bus Route Roads,176,7987000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Besant avenue road from the junction of Ellaiamman Koil to the Junction of Durgabai Deshmuk Road in Dn 176 Zone - 13,Grants,13,2015-16,2017-18 BR/2015-16/14338,Roads,Completed,BR-Bus Route Roads,179,642000,Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at LIC Colony 1st Cross Street from the junction of LIC Colony Main road to the Junction of Velachery Taramani Road in Dn 179 Zone - 13,Grants,13,2015-16,2017-18 BR/2015-16/14339,Roads,Completed,BR-Bus Route Roads,111,6000000,"Strengthening and relaying the road with DBM & CBC after cold milling by paver finisher by using plastic plastic waste with traffic improvement works at Pattulos road from the Jn of Whites road to the jn of Anna Salai in Dn - 111, Zone-9",Grants,9,2015-16,2016-17 BR/2015-16/14341,Roads,Completed,BR-Bus Route Roads,111,9800000,"Strengthening and relaying the road with DBM & CBC after cold milling by paver finisher by using plastic plastic waste with traffic improvement works at Peters road from the Jn of Anna Salai to the jn of Conron smith road in Dn - 111, Zone-9","Loans, Grants And Own Sources",9,2015-16,2016-17 BR/2015-16/14355,Footpath,Completed,BR-Bus Route Roads,123,2494000,Proposed Pedestrain friendly Footpath work at St.Marys road from the Jn of Prithvi Avenue to the JN of CP Ramaswamy road (Southern side) in Dn 123 & 124 Zone IX,Own Sources,9,2015-16,2016-17 BR/2015-16/14382,Roads,Completed,BR-Bus Route Roads,115,3100000,Strengthening & relaying the road width DBM and CBC after cold milling by paver finisher using plastic waste along with traffic improvement works at Peters road Flyover in Dn 115 Zone IX,"Loans, Grants And Own Sources",9,2015-16,2016-17 BR/2015-16/14385,Roads,Completed,BR-Bus Route Roads,115,18040000,Strengthening & relaying the road width DBM and CBC after cold milling by paver finisher using plastic waste along with traffic improvement works at Westcott road from the Jn of whites road to Jn of Peters road in Dn 115 Zone IX,Grants,9,2015-16,2016-17 BR/2015-16/14388,Roads,Completed,BR-Bus Route Roads,91,6872000,"Strengthing and Relayong of Road work using DBM and CBC with Paver finisher using Plastic waste along with Traffic Improvements at Mogappair West 3rd Main Road(Part) from vellalar Street to Kambar Salai in Ward-91, Zone-7",Grants,7,2015-16,2016-17 BR/2015-16/14391,Roads,Completed,BR-Bus Route Roads,92,9586000,"Strengthing and Relayong of Road work using DBM and CBC with Paver finisher using Plastic Waste along with Traffic Improvements at Thiruvalluvar Salai from the Jn of Ambattur Main Road to Venugopal Street in Ward-92, Zone-7",Grants,7,2015-16,2016-17 BR/2015-16/14393,Roads,Completed,BR-Bus Route Roads,64,8006000,"Strengthing and Relayong of Road work using DBM and CBC with Paver finisher using Plastic Waste along with Traffic Improvements at Kumaran Nagar Main Road from the Jn of Senthil Nagar 1st Main Road to Kumaran Nagar Bus Terminous in Ward- 64, Zone-6",Grants,6,2015-16,2016-17 BR/2015-16/14399,Roads,Completed,BR-Bus Route Roads,66,6817000,"Strengthing and Relayong of Road work using DBM and CBC with Paver finisher using Plastic Waste along with Traffic Improvements at Redhills Main Road from the Jn of Thenpalani Nagar to Poompugar nagar 1st Main road in Ward-66, Zone-6",Grants,6,2015-16,2016-17 BR/2015-16/14401,Roads,Completed,BR-Bus Route Roads,117,13426000,"Strengthening and relaying the road with DBM & CBC after cold milling by paver finisher by using plastic plastic waste with traffic improvement works at Dr.Vijayaragavan road from the Jn of Anna salai road to the jn of Dr.Nair road in Dn - 117, Zone-9",Grants,9,2015-16,2016-17 BR/2015-16/14402,Roads,Completed,BR-Bus Route Roads,66,15804000,"Strengthing and Relayong of Road work using DBM and CBC with Paver finisher using Plastic waste along with Traffic Improvements at SRP Kovil North from the Jn of Paper mills road to Pallavan Salai in Ward-66, Zone-6",Grants,6,2015-16,2016-17 BR/2015-16/14445,Roads,Completed,BR-Bus Route Roads,67,7070000,"Stengthening and Relaying the Road with DBM and CBC after Cold milling by paver Finisher using plastic Waste along with traffic Improvement at SRP koil street (South) (from the Jn of Jawagar Nagar Main Road to the Jn of Paper Mills Road in Dn-67, Zone-6",Grants,6,2015-16,2017-18 BR/2015-16/14446,Roads,Completed,BR-Bus Route Roads,39,20300000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at Thiruvotriyur high road (from AE kovil street to North Terminus road ) Division 39 &40,zone IV Zone - IV",Grants,4,2015-16,2016-17 BR/2015-16/14448,Roads,Completed,BR-Bus Route Roads,24,11087000,"Strengthening and Relaying Road with DBM and CBC by Paver Finisher using plastic waste along with Traffic Improvements Work at Kadappa Road from Thiruvalluvar salai to kalaimagal street in Dn-24, Zone-3",Grants,3,2015-16,2016-17 BR/2015-16/14549,Roads,Completed,BR-Bus Route Roads,47,9900000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at KANNAN STREET (from Parthasarathy over bridge to petty munusamy street ) Division 47 & 53 , Zone - IV",Grants,4,2015-16,2016-17 BR/2015-16/1455,Roads,Completed,BR-Bus Route Roads,58,1190000,Proposed Construction of Modern Stainless Steel Bus Shelter at CHOOLAI HIGH ROAD (Opp to Ramalinga vilas) in Div-58 in Zone-5,MPLADS,5,2015-16,2017-18 BR/2015-16/14550,Roads,Completed,BR-Bus Route Roads,39,3790000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at AE KOVIL STREET (from Thiruvotriyur high road to Kamaraj salai ) Division 39 & 40, Zone - IV",Grants,4,2015-16,2016-17 BR/2015-16/14551,Roads,Completed,BR-Bus Route Roads,40,4900000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at SENNI AMMAN KOVIL STREET (from vaidhyanathan street to kailasam street ) Division 40, Zone - IV",Grants,4,2015-16,2016-17 BR/2015-16/14552,Roads,Completed,BR-Bus Route Roads,35,13640000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at tondaiarpet high road (from Ethiraj samy salai to Moolakadai junction ) Division 35, Zone - IV",Grants,4,2015-16,2016-17 BR/2015-16/1456,Roads,Completed,BR-Bus Route Roads,58,1190000,Proposed Construction of Modern Stainless Steel Bus Shelter at E V R Periyar Salai (Near Police Commissioner Office Compound wall) in Div-58 in Zone-5,MPLADS,5,2015-16,2017-18 BR/2015-16/14561,Roads,Completed,BR-Bus Route Roads,114,9680000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at KAMARAJ SALAI PART (from Naeppiar Bridge to Wallajha road ) Division 114, Zone - IX",Grants,9,2015-16,2017-18 BR/2015-16/14566,Roads,Completed,BR-Bus Route Roads,59,8100000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at RATTAN BAZAR ROAD (from NSC Bose road to Evening Bazar road ) Division 59, Zone - V",Grants,5,2015-16,2017-18 BR/2015-16/14567,Roads,Completed,BR-Bus Route Roads,55,20200000,"Strengthening and Relaying the road with DBM and CBC after Cold Milling by Paver finisher using shredded plastic waste along with Traffic improvement works at PRAKASAM SALAI (from N S C bose road to Amman kovil street ) Division 55 & 57, Zone - V",Grants,5,2015-16,2017-18 BR/2015-16/1457,Roads,Completed,BR-Bus Route Roads,58,1190000,Proposed Construction of Modern Stainless Steel Bus Shelter at E V R Periyar Salai (Opp to Member of Parliament Office at Periyamadu ) in Div-58 in Zone-5,MPLADS,5,2015-16,2017-18 BR/2015-16/14671,Roads,Completed,BR-Bus Route Roads,64,2584000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Paper mills road Balaji nagar junction to Eswar hospita IN DIVISION -64 , ZONE -06.","Loans, Grants And Own Sources",6,2015-16,2016-17 BR/2015-16/14672,Roads,Completed,BR-Bus Route Roads,64,4380000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Sembium Redhills road from Balaji nagar jn to Welding shop IN DIVISION -64 , ZONE -06.",Own Sources,6,2015-16,2016-17 BR/2015-16/14673,Roads,Completed,BR-Bus Route Roads,64,4797000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Redhills main road from Burial ground road to poobukar nagar main road IN DIVISION -66 , ZONE -06",Grants,6,2015-16,2016-17 BR/2015-16/14675,Roads,Completed,BR-Bus Route Roads,102,710000,"Restoration of road cut made by TANGEDCO at Kilpauk Garden Road northern side in div - 102, Zone - 08. (Challan No: BR/2015-16/0000954.)",Deposit Works,8,2015-16,2016-17 BR/2015-16/14683,Roads,Completed,BR-Bus Route Roads,61,5840000,"STRENGTHENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at ADTHITHANAR SALAI From MARKET to BLACKERS ROAD IN DIVISION 61 , ZONE -05",Own Sources,5,2015-16,2017-18 BR/2015-16/14685,Roads,Completed,BR-Bus Route Roads,181,5700000,STRENGTHENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at KALASHETHRA ROAD From MUTHU LAKSHMI ROAD TO L.B ROAD IN DIV 181. ZONE-13,Grants,13,2015-16,2016-17 BR/2015-16/14686,Roads,Completed,BR-Bus Route Roads,182,19300000,"STRENGTHENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic Improvements at South Avenue Road IN DIVISION -182 , ZONE -13.",Grants,13,2015-16,2016-17 BR/2015-16/14687,Roads,Completed,BR-Bus Route Roads,119,3950000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at Thiru vi ka road (Royapetah high Road) from Lylods road to Dr. Radhakrishanan road DIVISION 119 , ZONE -09.","Loans, Grants And Own Sources",9,2015-16,2016-17 BR/2015-16/14688,Roads,Completed,BR-Bus Route Roads,121,9190000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Thiru vi ka road (Royapetah high Road) from Dr. Radhakrishanan road to P.S.Sivasamy salai in DIVISION 121&123 , ZONE -09.","Loans, Grants And Own Sources",9,2015-16,2016-17 BR/2015-16/14692,Roads,Completed,BR-Bus Route Roads,64,3486000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Anna nagar8th cross from Annanagar 1st Avenue to Anna nagar 1st main road IN DIVISION , 101 ZONE -08.",Grants,6,2015-16,2016-17 BR/2015-16/14693,Roads,Completed,BR-Bus Route Roads,64,5770000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements atAnna nagar 1st main road from Anna nagar 8th cross st to Anna nagar 3rd cross st in div-101, ZONE -08.",Grants,6,2015-16,2016-17 BR/2015-16/14694,Roads,Completed,BR-Bus Route Roads,64,3578000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic wast5e along with traffic improvements at Anna nagar 3rd cross st from Anna nagar 1st main road to pulla avenue in div-101, ZONE -08.",Grants,6,2015-16,2016-17 BR/2015-16/14760,Roads,Completed,BR-Bus Route Roads,138,13813000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Bharathidasan Colony Main Road in Dn-138, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14761,Roads,Completed,BR-Bus Route Roads,138,25625000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Ashok Pillar Road from the Jn of 100 feet Road to the Jn of Anna Main Road in Dn-138, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14762,Roads,Completed,BR-Bus Route Roads,141,14535000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Burkit Road from the Jn of South Usamn Road to Jn of Venkatinanarayan Road Dn-141, Zone-10",Grants,10,2015-16,2017-18 BR/2015-16/14763,Roads,Completed,BR-Bus Route Roads,132,13156000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Ashok Nagar 2nd Avenue from the Jn of Ashok Nagar 4th Main Road to the Jn of 100feet Road in Dn-132, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14773,Roads,Completed,BR-Bus Route Roads,173,3348000,"Strengthening and Relaying the Road with CBC after cold milling by paver finisher using plastic waste along with Traffic improvement work at Durgabai DeshmukRoad Thiru-Vi-Ka Bridge portion in Dn-173, Zone-XIII",Grants,13,2015-16,2016-17 BR/2015-16/14775,Roads,Completed,BR-Bus Route Roads,136,7950000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Dr.Nayer Road from the Jn of Thyagaraya Road to the Jn of GN Chetty Road in Dn-136, Zone-10",Grants,10,2015-16,2017-18 BR/2015-16/14777,Roads,Completed,BR-Bus Route Roads,133,71190000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at NSK Salai from the jn of Vadaplani Bus terminous to the jn of Alwarthirunagar in Dn-133, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14791,Roads,Completed,BR-Bus Route Roads,129,23544000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Arunachalam Salai from the jn of NSK Salai to the Jn of Dasarathaburam Main road in Dn-129, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14797,Roads,Completed,BR-Bus Route Roads,94,7370000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT M.T.H. ROAD (FROM THE JN. OF REDDY STREET TO NADAMUNI SIGNAL ) DIVISION-94 , ZONE-8.",Grants,8,2015-16,2016-17 BR/2015-16/14803,Roads,Completed,BR-Bus Route Roads,121,5160000,"STRENGTHENING AND RELAYING THE ROAD WITH DBM AND CBC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT ROYAPETTAH HIGH ROAD BRIDGE DIVISION-121 , ZONE-9.","Loans, Grants And Own Sources",9,2015-16,2016-17 BR/2015-16/14807,Roads,Completed,BR-Bus Route Roads,135,21855000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Aryagowda Road from the jn of Postal colony 3rd Street to the Jn of Brindavan Street in Dn-135, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14808,Roads,Completed,BR-Bus Route Roads,129,4624000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at SBI Colony 3rd Street the Jn of Kamarajar Salai to the Jn of Abusali Street in Dn-129, Zone-10",Grants,10,2015-16,2016-17 BR/2015-16/14809,Roads,Completed,BR-Bus Route Roads,129,4644000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at SBI Colony 2rd Street from the jn of Kamarajar Salai to the Jn of Abusalai Street in Dn-129, Zone-10",Grants,10,2015-16,2016-17 BR/2015-16/14981,Roads,Completed,BR-Bus Route Roads,141,9015000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at New Boag Road from the Jn of South usman road to the Jn of 70 Feet Road in Dn- 141, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14982,Roads,Completed,BR-Bus Route Roads,134,2694000,"Strengthening and Relaying the Road with DBM and CBC after Cold Milling by Paver Finisher by Using Plastic waste Along with Traffic improvement work at Corporation Colony from the Jn of Thambiah Road Ext to the Jn of Rangarajaburam Main Road in Dn- 134, Zone-10","Loans, Grants And Own Sources",10,2015-16,2016-17 BR/2015-16/14983,Roads,Completed,BR-Bus Route Roads,68,24163000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Pallavan Salai from the JN of the SRP Colony Main(South) to JN of Madavaram High Road in Dn 68 Zone VI,Grants,6,2015-16,2017-18 BR/2015-16/14984,Roads,Completed,BR-Bus Route Roads,70,12433000,"strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Perambur Flyover from the JN of the Perambur High Road (South) to the Jn of Tank Link Road in Dn 70,71 Zone VI",Grants,6,2015-16,2017-18 BR/2015-16/14985,Roads,Completed,BR-Bus Route Roads,75,15360000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Bricklin Road from the JN of the Venkatammal Samathi Street to the Jn of Strahan's Road in Dn 75 Zone VI,Grants,6,2015-16,2017-18 BR/2015-16/14986,Roads,Completed,BR-Bus Route Roads,78,9532000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Choolai High Road from the JN of the Rajamuthiya Salai to the Jn of Narayanaguru Salai in Dn 78 Zone VI,Grants,6,2015-16,2016-17 BR/2015-16/14987,Roads,Completed,BR-Bus Route Roads,73,17332000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Stephension Road from the JN of the Dr.Ambedkar College Road to the Jn of Cooks road in Dn 73 Zone VI,Grants,6,2015-16,2017-18 BR/2015-16/14988,Roads,Completed,BR-Bus Route Roads,67,3085000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at GKM Colony 17th Street from the JN of the Jambulingam Main Road to the Jn of Venkatesan Salai in Dn 67 Zone VI,Grants,6,2015-16,2017-18 BR/2015-16/14989,Roads,Completed,BR-Bus Route Roads,72,13382000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Basin Power House Road from the JN of the Pulianthope High Road to the Jn of Basin Bridge in Dn 72 Zone VI,Grants,6,2015-16,2016-17 BR/2015-16/14990,Roads,Completed,BR-Bus Route Roads,78,9372000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Elephant Gate Bridge Road from the JN of the Rajamuthiya Salai to the Jn of Elephant Gate Bridge portion in Dn 78 Zone VI,Grants,6,2015-16,2016-17 BR/2015-16/14991,Roads,Completed,BR-Bus Route Roads,65,27848000,strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Kollathur Redhills Road from the JN of the Paper Mills Road to the Jn of Vijayanagar Extent in Dn 65 Zone VI,Grants,6,2015-16,2017-18 BR/2015-16/14992,Roads,Completed,BR-Bus Route Roads,65,25924000,"strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at jambulingam Main Road from the JN of the Kolathur Main Road to the Jn of Jogihurts in Dn 65, 67 Zone VI",Grants,6,2015-16,2017-18 BR/2015-16/14993,Roads,Completed,BR-Bus Route Roads,69,45291000,"strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Madhavaram High road from the JN of the Perambur High road (North) to the Jn of City Limit in Dn 69, 70 Zone VI",Grants,6,2015-16,2017-18 BR/2015-16/14994,Roads,Completed,BR-Bus Route Roads,73,17864000,"strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Strahans Road from the JN of the Bricklin Road to the Jn of Perambur Barraks Road in Dn 73, 76 Zone VI",Grants,6,2015-16,2017-18 BR/2015-16/14995,Roads,Completed,BR-Bus Route Roads,73,15500000,"strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Cooks Road from the JN of the Konnur High Road to the Jn of Stephenson Road Road in Dn 73, Zone VI",Grants,6,2015-16,2017-18 BR/2015-16/14996,Roads,Completed,BR-Bus Route Roads,64,19530000,"strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Kollathur Main Road from the JN of the villivakkam Railway Gate to the Jn of Poombuhar Nagar 1st Main Road in Dn 64, Zone VI",Grants,6,2015-16,2017-18 BR/2015-16/14997,Roads,Completed,BR-Bus Route Roads,70,2673000,"strengthening and relaying the road with DBM and CBC after cold milling by paver finisher by using plasticwaste along with traffic improvement works at Lakshmiamman Koils Street from the Jn of Melpettai Ponapan Street to Jn of State Bank Colony in Div 69, Zone VI",Grants,6,2015-16,2017-18 BR/2015-16/15063,Roads,Completed,BR-Bus Route Roads,174,2490000,"Providing RCC Crash Barirer type Center Median at Velachery Main Road(From Junction of Race Course road to Ch.285 mts. Towards Five Furlong road Junction in Division - 174, Zone -13",Own Sources,13,2015-16,2016-17 BR/2015-16/15133,Footpath,Completed,BR-Bus Route Roads,117,2164000,"Forming Pedestrian Footpath @ GN Chetty road North side from the junction of Habibullah road (Bharathi raja Hospital) chainage 0.00 -310.00 in division 117, zone-9",Own Sources,9,2015-16,2018-19 BR/2015-16/15142,Roads,Completed,BR-Bus Route Roads,91,26388000,"Strengthing and Relayong of Road work using DBM and CBC with Paver finisher using Plastic Waste along with Traffic Improvements at Mogappair Eri Scheme 6th Main Road in Ward-91, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/15144,Roads,Completed,BR-Bus Route Roads,91,10726000,"Strengthing and Relayong of Road work using DBM and CBC with Paver finisher using Plastic Waste along with Traffic Improvements at Kavimani Salai in Ward-91, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/1516,Road Cut,Completed,BR-Bus Route Roads,119,968000,"Restoration of Roadcut made by TANGEDCO at Peters Road in Dn-119, Zone-9 Reach 1",Deposit Works,9,2015-16,2016-17 BR/2015-16/1519,Road Cut,Completed,BR-Bus Route Roads,119,968000,"Restoration of Roadcut made by TANGEDCO at Peters Road in Dn-119, Zone-9 Reach 2",Deposit Works,9,2015-16,2016-17 BR/2015-16/1520,Road Cut,Completed,BR-Bus Route Roads,111,968000,"Restoration of Roadcut made by TANGEDCO at Greams Road in Dn-111, Zone-9 Reach 1.",Deposit Works,9,2015-16,2016-17 BR/2015-16/15219,Roads,Completed,BR-Bus Route Roads,174,1321000,"Proposed Construction of 9.00M X 2.50M size Modern Stainless Steel Bus Shelter at City Link Road in Div - 174, Zone - 13.",Own Sources,13,2015-16,2016-17 BR/2015-16/1522,Road Cut,Completed,BR-Bus Route Roads,111,968000,"Restoration of Roadcut made by TANGEDCO at Greams Road in Dn-111, Zone-9 Reach 2.",Deposit Works,9,2015-16,2016-17 BR/2015-16/15257,Footpath,Completed,BR-Bus Route Roads,125,2489000,Proposed Pedestrain friendly Footpath work at St.Marys road from the Jn of Prithvi Avenue to the JN of CP Ramaswamy road (Northern side) in Dn 123 & 124 Zone IX,Own Sources,9,2015-16,2016-17 BR/2015-16/15332,Footpath,Completed,BR-Bus Route Roads,61,9300000,"FORMING FOOT PATH AT EAST RAMANATHAN SALAI FROM JUNCTION OF MAYOR RAMANATHAN SALAI TO GANGU REDDY BRIDGE IN DN 61, ZONE V",Own Sources,5,2015-16,2017-18 BR/2015-16/15403,Roads,Completed,BR-Bus Route Roads,174,2087000,"Providing RCC Crash Barirer type Center Median at Velachery Main Road(From Junction of Five Furlong Road road to Ch.236 mts. Towards Vijaya nagar bus stop, Jn. of Velachery 100 feet road, Jn. of Gurunanak College and Jn. of Vijayanagar busstop in Division - 174, and 179 Zone -13)",Own Sources,13,2015-16,2016-17 BR/2015-16/15405,Roads,Completed,BR-Bus Route Roads,175,1237000,"Providing RCC Crash Barirer type Center Median at Sardar Patel Road(From Junction of Kasturibai Nagar 2nd Cross street to Ch.140 mts. Towards Adyar signal Division - 175, Zone -13)",Own Sources,13,2015-16,2016-17 BR/2015-16/15409,Roads,Completed,BR-Bus Route Roads,159,8187000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at Gangadeeswarar Koil Street (From the jn of Purasaiwalkam High Road to the jn of Dr.Alagappa road) in Dn - 104, Zone - 8",Grants,12,2015-16,2017-18 BR/2015-16/15410,Roads,Completed,BR-Bus Route Roads,159,17500000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at ORMES ROAD ( From the jn of KG Road to Kellys Road) in Dn-103, Zone-VIII",Grants,12,2015-16,2017-18 BR/2015-16/15411,Roads,Completed,BR-Bus Route Roads,159,10200000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at Harleys Road (From the Jn of KG Road to Balfour Road ) in Dn-103, Zone-VIII",Grants,12,2015-16,2017-18 BR/2015-16/15412,Roads,Completed,BR-Bus Route Roads,159,20600000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at Purasaivakkam High Road ( Jn of Kellys Signal to jn of Millers Road) in Dn-103, Zone-VIII",Grants,12,2015-16,2017-18 BR/2015-16/15413,Roads,Completed,BR-Bus Route Roads,159,8900000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at Vinayagapuram Main Road (from the jn of Jawaharlal Nehru Salai to MMDA Colony) in Dn-105, Zone-VIII",Grants,12,2015-16,2017-18 BR/2015-16/15414,Roads,Completed,BR-Bus Route Roads,159,34300000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at Konnur High Road ( From the jn of ICF Signal to Iyanavaram Market) in Dn-96, Zone-VIII",Grants,12,2015-16,2017-18 BR/2015-16/15415,Roads,Completed,BR-Bus Route Roads,159,52200000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at Anna Nagar 4th Avenue (from the jn of 7th Main Road to Jawaharla Nehru Salai) in Dn-99 & 100, Zone-VIII",Grants,12,2015-16,2016-17 BR/2015-16/15416,Roads,Completed,BR-Bus Route Roads,95,27500000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at New Avadi Road (From the jn of ICF Signal to jn of Nathamuni Signal) in Dn-95, Zone-VIII",Grants,8,2015-16,2016-17 BR/2015-16/15417,Roads,Completed,BR-Bus Route Roads,102,15400000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at New Avadi Road (From the jn of Anna Nagar 1st Avenue to jn of Raju Street) (Southern side) in Dn-102, Zone-VIII",Grants,8,2015-16,2016-17 BR/2015-16/15418,Roads,Completed,BR-Bus Route Roads,106,33500000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver finisher by using plastic waste along with traffic improvement works at Nelson Manickam Road (from Metha nagar bridge to Periyar EVR Salai) in Dn-106, Zone-VIII",Grants,8,2015-16,2016-17 BR/2015-16/15419,Roads,Completed,BR-Bus Route Roads,104,15500000,"Strengthening and relaying the road with DBM & CBC after cold milling by Paver finisher using plastic waste along with traffic improvements at Bricklin Road from the jn of purasaivakkam high road to the jn of venkatammal samathi street in DN -104, Zone - 8",Grants,8,2015-16,2017-18 BR/2015-16/1550,Footpath,Completed,BR-Bus Route Roads,61,876000,CONSTRUCTION OF TRAFFIC ISLAND AT JUNCTION OF E.V.R. SALAI AND GANDHI IRWIN BRIDGE ROAD IN DN 61 ZONE 5,Own Sources,5,2015-16,2016-17 BR/2015-16/15556,Roads,Completed,BR-Bus Route Roads,123,32200000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at St.Marys road (From the jn of RK mutt road to the jn of TTK road) in Dn - 123&124, Zone -9",Grants,9,2015-16,2016-17 BR/2015-16/15561,Roads,Completed,BR-Bus Route Roads,117,83500000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Marina Service Road (From the jn of MGR samathi to Loop Road) in Dn - 114,& 117, Zone -9",Grants,9,2015-16,2016-17 BR/2015-16/15562,Roads,Completed,BR-Bus Route Roads,118,43900000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Cathedral Road(From the jn of TTK Road to Anna Salai) in Dn - 118, Zone -9",Grants,9,2015-16,2016-17 BR/2015-16/15564,Roads,Completed,BR-Bus Route Roads,119,57200000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Dr.Radhakrishnan Salai (From TTK Road to Nadesan Salai) in Dn - 119 & 121, Zone -9",Grants,9,2015-16,2016-17 BR/2015-16/15566,Roads,Completed,BR-Bus Route Roads,114,99100000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Kamaraj Salai (From Walaja Road to Karaneswarar pagoda Street) in Dn - 114 &116, Zone -9",Grants,9,2015-16,2016-17 BR/2015-16/15585,Roads,Completed,BR-Bus Route Roads,124,7200000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Venkatesa Agraharam Street From the Jn of RK Mutt Road to the Jn of St Marys Road in Dn - 124, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15604,Roads,Completed,BR-Bus Route Roads,126,2900000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Singri Mutt Road From the Jn of St Marys Road to the Jn of Venkatakrishna Road in Dn - 126, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15605,Roads,Completed,BR-Bus Route Roads,119,9700000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Gowdia mutt road From the Jn of TTK Road to the Jn of Thiru.vi.ka.road in Dn - 119, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15606,Roads,Completed,BR-Bus Route Roads,120,19200000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Dr.Natesan Road from the Jn of Besant Road to the Jn of Radhakrishnan Salai in Dn - 120 & 121, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15607,Roads,Completed,BR-Bus Route Roads,119,8500000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Musri Subramaniam Salai from the Jn of Luz Church Road to the Jn of PV Sivasami Salai in Dn - 119, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15608,Roads,Completed,BR-Bus Route Roads,113,23700000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Valluvar Kottam High Road (from MGR Salai to Uthamar Gandhi Salai) in Dn - 113, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15609,Roads,Completed,BR-Bus Route Roads,117,16600000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at B.V.Narasiman Road (North Boag Road) from the Jn of GN Chetty Road to the Jn of Thiyagaraya Road in Dn - 117, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15610,Roads,Completed,BR-Bus Route Roads,117,17600000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Thanikachalam Road from the Jn of Thiyagaraya Road to the Jn of Venkatanarayana Road in Dn - 117, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15611,Roads,Completed,BR-Bus Route Roads,123,22100000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Eldams Road from the Jn of TTK Road to the Jn of Anna Salai in Dn - 123, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15612,Roads,Completed,BR-Bus Route Roads,125,4600000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Rosary Church Road from the Jn of Kutchery Road to the Jn of Santhome High Road in Dn - 125, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15614,Roads,Completed,BR-Bus Route Roads,110,1340000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Sivaganga Road from the jn of Wheat Craft Road to the jn of Sterling Road in Dn - 110, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15615,Roads,Completed,BR-Bus Route Roads,124,13900000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Kutchery Road from the jn of Luz Corner to the jn of Rosary Church Road in Dn - 124, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15618,Roads,Completed,BR-Bus Route Roads,110,33000000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Tank bund Road from the jn of valluvar kottam road to the jn ofNungambakkam subway in Dn - 110, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15619,Roads,Completed,BR-Bus Route Roads,110,2300000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Wheat Crafts Road from the jn of valluvar kottam road to the jn of Sivaganga road in Dn - 110, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15620,Roads,Completed,BR-Bus Route Roads,110,10188048,"Strengthening and relaying the road with DBM and CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at 70 Feet Scheme Road from the Jn of Mahalingapuram Main Road to the Jn of MGR Salai in Dn - 110, Zone -9",Grants,9,2015-16,2017-18 BR/2015-16/15621,Roads,Completed,BR-Bus Route Roads,159,4830000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at Dr.Besant Road (from Peters road to Quaid e Milleth Road) in Dn - 116, Zone -9",Grants,12,2015-16,2017-18 BR/2015-16/15622,Roads,Completed,BR-Bus Route Roads,123,10700000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with trffic improvement works at Dr.Ranga road Road (from the jn of CP Ramasamy road to RK mutt road) in Dn- 123, Zone - 9",Grants,9,2015-16,2017-18 BR/2015-16/15623,Roads,Completed,BR-Bus Route Roads,123,9800000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with traffic improvement works at G.N.Chetty road ( from the Jn. of Dr.Nair Road to the jn Dr.Narasiman Road) in Dn-123,Zone - 9",Grants,9,2015-16,2017-18 BR/2015-16/15633,Roads,Completed,BR-Bus Route Roads,109,9600000,"Strengthening and relaying the road with DBM & CBC after cold milling with paver finisher by using plastic waste along with trffic improvement works at Nelson Manickam Road (from the jn of Metha nagar bridge to Nungambakkam subway) in Dn- 109, Zone - 9",Grants,9,2015-16,2016-17 BR/2015-16/15970,Buildings,Completed,BR-Bus Route Roads,110,984000,"Repair and improvements of Traffic Island at Sterling road , college road and the jn of harrington road in Dn - 110, Zone - 9",Own Sources,9,2015-16,2016-17 BR/2015-16/16032,Buildings,Completed,BR-Bus Route Roads,103,984000,"REPAIR AND IMPROVEMENTS WORK TO TRAFFIC ISLAND AT MILLERS ROAD, ORMES ROAD, AND BALFOUR ROAD IN DN-103 ZONE-8",Own Sources,8,2015-16,2016-17 BR/2015-16/16230,Roads,Completed,BR-Bus Route Roads,131,998000,"Attending Emergency Patch Work at P.T.Rajan Salai in Dn-131, Zone-10",Grants,10,2015-16,2016-17 BR/2015-16/1627,Roads,Completed,BR-Bus Route Roads,174,2490000,"Providing RCC Crash Barirer type Center Median at Velachery Main Road(From Junction of Five Furlong road at 570 mts. to Ch.855 mts. Towards Sardar patel road) in Division - 174, Zone -13",Own Sources,13,2015-16,2016-17 BR/2015-16/16317,Roads,Completed,BR-Bus Route Roads,95,42131000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic Improvement works at Anna Nagar 18th Main Road in Ward-95, Zone-8",Grants,8,2015-16,2017-18 BR/2015-16/16320,Roads,Completed,BR-Bus Route Roads,102,36495000,"Strengthening and Relaying the Road with DBM and CBC after cold milling by paver finisher using plastic waste along with Traffic Improvement works at Anna Nagar 1st Avenue Road in Ward-102, Zone-8",Grants,8,2015-16,2016-17 BR/2015-16/16338,Roads,Completed,BR-Bus Route Roads,43,985000,"Providing patch work with DBM mix and removing speed breakers without IRC standards in Zone-4 Dn-43,41and 37",Own Sources,4,2015-16,2016-17 BR/2015-16/1651,Roads,Completed,BR-Bus Route Roads,103,4980000,"Proposed Construction of 6 Nos of Modern Stainless Steel Bus Shelters at (1).New avadi road ( Opp to Sheeba Snacks ) (2).Balfour road(Near Madhar sha house) (3).Medavakkam tank road (Near ABM furniture) (4).EVR salai (NSK Nagar /Govt. Anna siddha hospital compound- Opposite side ) (5).EVR salai (NSK Nagar /Govt. Anna siddha hospital compound side ) (6).EVR SALAI (Toll gate bus stop) in Dn 98,100 , 103 &107, Zone 6 & 8 Under MP scheme 2014 - 2015",MPLADS,8,2015-16,2017-18 BR/2015-16/16669,Roads,Completed,BR-Bus Route Roads,179,2087000,"Providing RCC Crash Barirer type Center Median at Velachery Main Road(From Junction of Five Furlong Road road to Ch.236 mts. Towards Vijaya nagar bus stop, Jn. of Velachery 100 feet road, Jn. of Gurunanak College and Jn. of Vijayanagar busstop in Division - 174, and 179 Zone -13)",Own Sources,13,2015-16,2016-17 BR/2015-16/16684,Buildings,Completed,BR-Bus Route Roads,173,2071000,"Providing Cement Concrete Center Median at Durgabai Deshmuk Road 260 Mtrs(Near Dr. MGR Janaki Ammal College) in Division - 173, Zone - 13.",Own Sources,13,2015-16,2016-17 BR/2015-16/16808,Footpath,Completed,BR-Bus Route Roads,118,46200000,"Proposed junction improvement at the junction of T.T.K road,Cathedral road and Radhakrishnan salai in ward 118&119, Zone-9.",Own Sources,9,2015-16,2017-18 BR/2015-16/1702,Footpath,Completed,BR-Bus Route Roads,61,12700000,"Forming Foot path at GANDHI IRWIN ROAD (Northern side) from Whannels road to Police Commissioner Road in Div - 61, Zone -5.",Own Sources,5,2015-16,2017-18 BR/2015-16/17125,Roads,Completed,BR-Bus Route Roads,102,980000,"Attending patch work at anna nagar 6th avenue, Kilpauk garden road and various Bus route roads in zone - 8",Own Sources,8,2015-16,2016-17 BR/2015-16/17137,Footpath,Completed,BR-Bus Route Roads,110,367000,"PROPOSED IMPROVEMENTS TO EXISTING FOOTPATH, CENTRE MEDIAN AND TREE VENTILATION AT 70 FEET SCHEME ROAD IN DIV-110,ZONE-9",Own Sources,9,2015-16,2016-17 BR/2015-16/17354,Roads,Completed,BR-Bus Route Roads,99,74273000,"Strengthening and Relaying the Road with DBM and CBC after cold miliing by paver Finisher using Plastic Waste along with Traffic improvement works at Anna Nagar 6th Avenue in Division-99, Zone-8",Grants,8,2015-16,2017-18 BR/2015-16/17355,Roads,Completed,BR-Bus Route Roads,141,16359000,"Strengthening and Relaying the Road with DBM and CBC after cold miliing by paver Finisher using Plastic Waste along with Traffic improvement works at South West Boag Road in Division-141, Zone-10",Grants,10,2015-16,2017-18 BR/2015-16/17359,Roads,Completed,BR-Bus Route Roads,99,979000,"Attending patch work at anna nagar 6th avenue, 1st avenue and various streets in zone - 8",Own Sources,8,2015-16,2016-17 BR/2015-16/17361,Roads,Completed,BR-Bus Route Roads,99,978000,"Attending patch work at anna nagar 6th avenue, 13th main road and various Bus route roads in zone - 8",Own Sources,8,2015-16,2016-17 BR/2015-16/17364,Roads,Completed,BR-Bus Route Roads,109,980000,"Attending patch work at mahalingapuram fly over, tank bund road and various Bus route roads in zone - 9",Own Sources,9,2015-16,2016-17 BR/2015-16/17367,Road Cut,Completed,BR-Bus Route Roads,105,600000,"Restoration of road cut made by TANGEDCO at MMDA Colony MAIN ROADin Dn -105, Zone - 8",Deposit Works,8,2015-16,2016-17 BR/2015-16/17709,Roads,Completed,BR-Bus Route Roads,111,969000,"Attendind emergency patch work at Dr.MGR Salai, kamtar nagarin Dn-111 & 113, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/17967,Roads,Completed,BR-Bus Route Roads,111,970000,"Providing Mastic Asphalt at M.G.R.Salai and G.N.Chetty Road in Dn-111 & 113, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/18166,Roads,Completed,BR-Bus Route Roads,161,19600000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Railway station road in Dn-161,162, Zone-XII",Grants,12,2015-16,2017-18 BR/2015-16/18176,Roads,Completed,BR-Bus Route Roads,96,180000,Attending patch work at Konnur High road and Other bus Route Roads in Zone - 8,Own Sources,8,2015-16,2016-17 BR/2015-16/18177,Roads,Completed,BR-Bus Route Roads,95,370000,"Attending Patchwork at Anna Nagar 3rd Avenue, Anna Nagar 18th Main Road and various other Bus Route Roads in Zone-8",Own Sources,8,2015-16,2016-17 BR/2015-16/18216,Roads,Completed,BR-Bus Route Roads,123,2833000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finisher using plastic waste along with traffic improvement works at Karpagambal Nagar Main Road in Dn-123, Zone-IX",Grants,9,2015-16,2017-18 BR/2015-16/18217,Roads,Completed,BR-Bus Route Roads,132,21059000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using plastic waste along with traffic improvement works at Ashok Nagar 7th Avenue in Dn-132, Zone-X",Own Sources,10,2015-16,2016-17 BR/2015-16/18224,Roads,Completed,BR-Bus Route Roads,136,7938000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using plastic waste along with traffic improvement works at Bashyam Road in Dn-136, Zone-X",Grants,10,2015-16,2016-17 BR/2015-16/18225,Roads,Completed,BR-Bus Route Roads,136,5145000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using plastic waste along with traffic improvement works at Prakasam Road in Dn-136, Zone-X",Grants,10,2015-16,2016-17 BR/2015-16/18229,Roads,Completed,BR-Bus Route Roads,138,4947000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using plastic waste along with traffic improvement works at 60 Feet Road in Dn-138, Zone-X",Grants,10,2015-16,2016-17 BR/2015-16/18230,Roads,Completed,BR-Bus Route Roads,136,4351000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using plastic waste along with traffic improvement works at Nageshwara rao Road in Dn-136, Zone-X",Grants,10,2015-16,2016-17 BR/2015-16/18236,Roads,Completed,BR-Bus Route Roads,66,3720000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Venkatraman salai in Dn-66, Zone-VI",Grants,6,2015-16,2016-17 BR/2015-16/18237,Roads,Completed,BR-Bus Route Roads,66,8010000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Jaganathan salai in Dn-66, Zone-VI",Grants,6,2015-16,2016-17 BR/2015-16/18238,Roads,Completed,BR-Bus Route Roads,66,2140000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Balasubramaniam salai in Dn-66, Zone-VI",Grants,6,2015-16,2016-17 BR/2015-16/18239,Roads,Completed,BR-Bus Route Roads,76,26470000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Barracks Gate Road &Konnur High Road in Dn-76, Zone-VI",Grants,6,2015-16,2016-17 BR/2015-16/18240,Roads,Completed,BR-Bus Route Roads,70,6400000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Perambur High Road (Service road ) in Dn-70, Zone-VI",Grants,6,2015-16,2016-17 BR/2015-16/18241,Roads,Completed,BR-Bus Route Roads,70,3520000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Permbur Tank link Road in Dn-70, Zone-VI",Grants,6,2015-16,2016-17 BR/2015-16/18242,Roads,Completed,BR-Bus Route Roads,70,5180000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Permbur Tank street in Dn-70, Zone-VI",Grants,6,2015-16,2016-17 BR/2015-16/18249,Roads,Completed,BR-Bus Route Roads,142,4800000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Perumal koil street in Dn-142, Zone-X",Grants,10,2015-16,2018-19 BR/2015-16/18250,Roads,Completed,BR-Bus Route Roads,142,3180000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Vanniar street in Dn-142, Zone-X",Grants,10,2015-16,2016-17 BR/2015-16/18254,Roads,Completed,BR-Bus Route Roads,39,5200000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at North Terminus Road in Dn-39, Zone-IV",Grants,4,2015-16,2016-17 BR/2015-16/18257,Roads,Completed,BR-Bus Route Roads,95,2220000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Anna Nagar 21st Main road in Dn-95, Zone-VIII",Grants,8,2015-16,2017-18 BR/2015-16/18258,Roads,Completed,BR-Bus Route Roads,103,16920000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Kilpauk Garden Road in Dn-103, Zone-VIII",Grants,8,2015-16,2017-18 BR/2015-16/18259,Roads,Completed,BR-Bus Route Roads,105,11240000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at MMDA COLONY Main Road in Dn-105, Zone-VIII",Grants,8,2015-16,2017-18 BR/2015-16/18266,Roads,Completed,BR-Bus Route Roads,56,13440000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Prakasam salai in Dn-56, Zone-V",Grants,5,2015-16,2016-17 BR/2015-16/18267,Roads,Completed,BR-Bus Route Roads,58,5000000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Allikulamn Link road ( PEOPLES PARK ROAD ) in Dn-58, Zone-V",Grants,5,2015-16,2016-17 BR/2015-16/18272,Roads,Completed,BR-Bus Route Roads,35,15600000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Kamaraj Salai in Dn-35, Zone-IV",Grants,4,2015-16,2016-17 BR/2015-16/18301,Roads,Completed,BR-Bus Route Roads,136,72300000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at NSK Salai in Dn-133, 134, Zone-X",Grants,10,2015-16,2017-18 BR/2015-16/18302,Roads,Completed,BR-Bus Route Roads,113,7130000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish Using plastic Waste along with Traffic improvement works at Kamdar Nagar and 40 Feet Scheme Road in Dn-113, Zone-IX",Grants,9,2015-16,2017-18 BR/2015-16/18382,Roads,Completed,BR-Bus Route Roads,137,610000,"Restoration of road cut made by CMWSSB at Eri Karai Salai in Div. 137, Zone 10",Deposit Works,10,2015-16,2016-17 BR/2015-16/18383,Roads,Completed,BR-Bus Route Roads,137,580000,"Restoration of road cut made by CMWSSB at Erikarai Salai in Div. 137, Zone 10",Deposit Works,10,2015-16,2016-17 BR/2015-16/18384,Roads,Completed,BR-Bus Route Roads,137,890000,"Restoration of road cut made by CMWSSB at Ramapuram Main Road in Div. 137, Zone 10",Deposit Works,10,2015-16,2016-17 BR/2015-16/18398,Roads,Completed,BR-Bus Route Roads,136,40000000,"Strengthening and Relaying the road with DBM and CBC after cold milling by Paver Finisher using plastic waste along with traffic improvement works at Dr.MGR Salai in Dn-113, Zone-IX",Grants,10,2015-16,2017-18 BR/2015-16/18733,Roads,Completed,BR-Bus Route Roads,132,11800000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Ashok Nagar 1st Avenue Road from the junction of Ashok Nagar 10th Avenue Road to Ashok Nagar 11th Avenue Dn 132, Z-10.",Grants,10,2015-16,2017-18 BR/2015-16/18734,Roads,Completed,BR-Bus Route Roads,132,36800000,"Repairing and restoration of road damaged for the flood during NEM 2015 at Ashok Nagar 11th Avenue Road from the junction of GST 100 feet Road toGovindhan road Dn 132 & 133 , Z-10.",Grants,10,2015-16,2016-17 BR/2015-16/18735,Roads,Completed,BR-Bus Route Roads,132,17560000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Dr.Ambedkar Salai From NSK salai to Ashok Nagar 4th Avenue Road Dn 132 & 134, Z-10.",Grants,10,2015-16,2016-17 BR/2015-16/19502,Roads,Completed,BR-Bus Route Roads,66,985000,"Attending Patch work at Karthikeyan Salai and SRP Kovil main Road in Dn-66, Zone-6",Own Sources,6,2015-16,2016-17 BR/2015-16/19809,Roads,Completed,BR-Bus Route Roads,194,1789543,"AtReparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Kumaran Kudil 1st Main Road-1 in Dn-194, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/19822,Roads,Completed,BR-Bus Route Roads,194,760000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at RajiNagar 1st Main Road in Dn-194, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/19823,Roads,Completed,BR-Bus Route Roads,194,1165000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Sakthi Srinivasan Road in Dn-194, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/20128,Roads,Completed,BR-Bus Route Roads,12,5160000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Sathangadu High Road in Div -12 , Zone - 1..",Grants,1,2015-16,2017-18 BR/2015-16/20143,Roads,Completed,BR-Bus Route Roads,12,3740000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at West Mada St in Div -12 , Zone - 1..",Grants,1,2015-16,2017-18 BR/2015-16/20150,Roads,Completed,BR-Bus Route Roads,17,10320000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Kosappur Vadaperumbakkam Salai in Div -17 , Zone - II.",Grants,2,2015-16,2017-18 BR/2015-16/20152,Roads,Completed,BR-Bus Route Roads,26,9010000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Thattankulam Road in Div -26 , Zone - III..",Grants,3,2015-16,2017-18 BR/2015-16/20153,Roads,Completed,BR-Bus Route Roads,34,7580000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Manali salai in Div -34 , Zone - 4..",Grants,4,2015-16,2017-18 BR/2015-16/20154,Roads,Completed,BR-Bus Route Roads,37,11860000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at MKB NAGAR CENTRE AVENUE in Div -37 , Zone - 04.",Grants,4,2015-16,2017-18 BR/2015-16/20156,Roads,Completed,BR-Bus Route Roads,111,6628000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Conron Smith Road in Dn-111, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20161,Roads,Completed,BR-Bus Route Roads,58,13110000,"Strengthening and Relaying road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Basin Bridge road in Div -53 , Zone - 05",Grants,5,2015-16,2017-18 BR/2015-16/20162,Roads,Completed,BR-Bus Route Roads,53,9350000,"Strengthening and Relaying road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at PERAMBUR BARRACS R0AD in Div -58 , Zone - 05.",Grants,5,2015-16,2017-18 BR/2015-16/20163,Roads,Completed,BR-Bus Route Roads,53,5690000,"Strengthening and Relaying road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at North wall roads in Div -53 , Zone - 05.",Grants,5,2015-16,2017-18 BR/2015-16/20169,Roads,Completed,BR-Bus Route Roads,113,9898000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Habibullah Road in Dn-113, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20173,Roads,Completed,BR-Bus Route Roads,66,10520000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Karthikeyan salai in Div -66 , Zone - 06.",Grants,6,2015-16,2017-18 BR/2015-16/20174,Roads,Completed,BR-Bus Route Roads,74,12350000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Medavakkam Tank Rd in Div -74 , Zone - 06.",Grants,6,2015-16,2017-18 BR/2015-16/20177,Roads,Completed,BR-Bus Route Roads,64,5150000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Rajan nagar main road in Div -64&65 , Zone - 06.",Grants,6,2015-16,2017-18 BR/2015-16/20178,Roads,Completed,BR-Bus Route Roads,122,11628000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Kavignar Bharathhidasan salai in Dn-122, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20186,Roads,Completed,BR-Bus Route Roads,113,13851000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at North Usman Road in Dn-113, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20223,Roads,Completed,BR-Bus Route Roads,119,8793000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Thiru-Vi-Ka High Road (Jn of Peters Road to Jn of Avvai Sanmugam Road) in Dn-119&121, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20228,Roads,Completed,BR-Bus Route Roads,113,9346000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Thirumalai Pillai Road in Dn-113, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20229,Roads,Completed,BR-Bus Route Roads,194,1187000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Rajiv Garden 1st Main Road in Dn-194, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/20231,Roads,Completed,BR-Bus Route Roads,117,15175000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Chevaliyar Sivaji Ganesan Road in Dn-117, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20238,Roads,Completed,BR-Bus Route Roads,118,1576000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Poes Garden (Part) in Dn-118, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20240,Roads,Completed,BR-Bus Route Roads,118,2428000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Kasthuri Rangan Road in Dn-118, Zone-IX (From Chaianage 0 to 275m)",Grants,9,2015-16,2016-17 BR/2015-16/20241,Roads,Completed,BR-Bus Route Roads,118,2028000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Shesathri Road in Dn-118, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20244,Roads,Completed,BR-Bus Route Roads,118,1869000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Kasthuri Estate 1st Street in Dn-118, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20245,Roads,Completed,BR-Bus Route Roads,195,4278000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Kannagi Nagar 2nd Main Road in Dn-195, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/20247,Roads,Completed,BR-Bus Route Roads,118,1545000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Binny Road in Dn-118, Zone-IX (From Chainage 0 to 175)",Grants,9,2015-16,2016-17 BR/2015-16/20318,Roads,Completed,BR-Bus Route Roads,157,24170000,"Repairing and restoration of road damaged for the flood during NEM 2015 at Manapakkam main road from Poonamalle high road to Mukkthi Enclave in Div - 157 , Zone - 12.",Grants,12,2015-16,2016-17 BR/2015-16/20322,Roads,Completed,BR-Bus Route Roads,162,1250000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Thillai ganga nagar 1st main road in Div - 162 , Zone - 12.",Grants,12,2015-16,2017-18 BR/2015-16/20323,Roads,Completed,BR-Bus Route Roads,157,530000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Thillai ganga nagar 22nd Street in Div - 162 , Zone - 12.",Grants,12,2015-16,2017-18 BR/2015-16/20325,Roads,Completed,BR-Bus Route Roads,163,1330000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Palandi amman koil street in Div - 163 , Zone - 12.",Grants,12,2015-16,2017-18 BR/2015-16/20326,Roads,Completed,BR-Bus Route Roads,163,1460000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at East Karikalan street in Div - 163 , Zone - 12.",Grants,12,2015-16,2017-18 BR/2015-16/20327,Roads,Completed,BR-Bus Route Roads,163,1380000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Erikarai street in Div - 163 , Zone - 12.",Grants,12,2015-16,2017-18 BR/2015-16/20328,Roads,Completed,BR-Bus Route Roads,157,2340000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Arcot road in Div - 157 , Zone - 12.",Grants,12,2015-16,2017-18 BR/2015-16/20329,Roads,Completed,BR-Bus Route Roads,157,11870000,".. Repairing and restoration of road damaged for the flood during NEM 2015 at Anna main road in Div - 157 , Zone - 12.",Grants,12,2015-16,2017-18 BR/2015-16/20342,Roads,Completed,BR-Bus Route Roads,132,32177000,"Name of Work .. Repairing and restoration of road damaged for the flood during NEM 2015 at Ashok nagar 4th Avenue.from Dr.Ambedkar salai to 100 feet road , in Dn-132.Zone - 10",Grants,10,2015-16,2016-17 BR/2015-16/20437,Roads,Completed,BR-Bus Route Roads,118,1553000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Binny Road in Dn-118, Zone-IX (From Chainage 175 to 350m)",Grants,9,2015-16,2016-17 BR/2015-16/20439,Roads,Completed,BR-Bus Route Roads,118,2427000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Kasthuri Rangan Road in Dn-118, Zone-IX (From Chaianage 275 to 550m)",Grants,9,2015-16,2016-17 BR/2015-16/20440,Roads,Completed,BR-Bus Route Roads,195,2904000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Kannagi Nagar 1st Main Road in Dn-195, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/20441,Roads,Completed,BR-Bus Route Roads,194,3293000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Eswaran Koil Street in Dn-194, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/20453,Roads,Completed,BR-Bus Route Roads,200,9711000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Semmenchery Main Road in Dn-200, Zone-XV",Grants,15,2015-16,2017-18 BR/2015-16/20471,Roads,Completed,BR-Bus Route Roads,177,1817000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Mahalakshmi Nagar 3rd Main Road in Dn-177, Zone-XIII",Grants,13,2015-16,2016-17 BR/2015-16/20472,Roads,Completed,BR-Bus Route Roads,177,1817000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Mahalakshmi Nagar 2nd Main Road in Dn-177, Zone-XIII",Grants,13,2015-16,2016-17 BR/2015-16/20474,Roads,Completed,BR-Bus Route Roads,177,3085000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at TNHB 1st Main Road in Dn-177, Zone-XIII",Grants,13,2015-16,2016-17 BR/2015-16/20475,Roads,Completed,BR-Bus Route Roads,177,3085000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at TNHB 2nd Main Road in Dn-177, Zone-XIII",Grants,13,2015-16,2016-17 BR/2015-16/20477,Roads,Completed,BR-Bus Route Roads,177,9192000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at TNHB Main Road in Dn-177, Zone-XIII",Grants,13,2015-16,2017-18 BR/2015-16/20502,Roads,Completed,BR-Bus Route Roads,58,6550000,"Strengthening and Relaying the Road With DBM and CBC After cold milling by Paver Finish inside the RIPPON BUILDING campus Div- 58, Z - 05.",Grants,5,2015-16,2017-18 BR/2015-16/20592,Roads,Completed,BR-Bus Route Roads,48,2100000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Thiruvotriyur high road From Junction of Thiyagaraya Collage to Old Smith Tank road in Div - 47 , Zone - 04.",Grants,4,2015-16,2016-17 BR/2015-16/20593,Roads,Completed,BR-Bus Route Roads,48,1900000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Thiruvotriyur high road From Junction of Old Smith Tank road to Jayaram street junction in Div - 47 , Zone - 04.",Grants,4,2015-16,2016-17 BR/2015-16/20594,Roads,Completed,BR-Bus Route Roads,48,1700000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Thiruvotriyur high road From Junction of Jayaram street junction to Vijayaragavalu street in Div - 47 , Zone - 04.",Grants,4,2015-16,2016-17 BR/2015-16/20610,Roads,Completed,BR-Bus Route Roads,171,861000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Anna Salai near Chellamala College in Div - 171 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/20612,Roads,Completed,BR-Bus Route Roads,171,1102000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Gandhi Mandapam Road in Div - 171 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/20615,Roads,Completed,BR-Bus Route Roads,174,1102000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Velachery Main Raod near Aquatic Complex in Div - 174 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/20662,Roads,Completed,BR-Bus Route Roads,129,535000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Abusali Road in Div - 129 , Zone - 10.",Grants,10,2015-16,2016-17 BR/2015-16/20664,Roads,Completed,BR-Bus Route Roads,135,892000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Thambiya Ext in Div -135 , Zone - 10..",Grants,10,2015-16,2016-17 BR/2015-16/20665,Roads,Completed,BR-Bus Route Roads,133,644000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Ashok nagar 49 th street From Junction of Ashok nagar 7th Avenue to Postal colony 3rd st in Div - 133 , Zone - 10",Grants,10,2015-16,2017-18 BR/2015-16/20666,Roads,Completed,BR-Bus Route Roads,133,804000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 Postal colony 3rd street in Div - 133 , Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20667,Roads,Completed,BR-Bus Route Roads,135,714000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Thambaiya road in Div - 135 , Zone - 10",Grants,10,2015-16,2017-18 BR/2015-16/20668,Roads,Completed,BR-Bus Route Roads,128,900000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Kamarajar Salai From Junction of N.S.K Salai to Reddy street in Div - 128 , Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20669,Roads,Completed,BR-Bus Route Roads,133,945000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Duraiswamy roadFrom Junction of N.S.K Salai to Ashok nagar 221 st Avenuein Div - 133, Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20670,Roads,Completed,BR-Bus Route Roads,129,1310000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at K.K road From Junction of N.S.K Salai to Reddy street in Div - 129, Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20671,Roads,Completed,BR-Bus Route Roads,142,588000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Jayaram Street in Div - 142 , Zone - 10.",Grants,10,2015-16,2016-17 BR/2015-16/20672,Roads,Completed,BR-Bus Route Roads,128,588000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Mosque street in Div - 128 , Zone - 10.",Grants,10,2015-16,2016-17 BR/2015-16/20673,Roads,Completed,BR-Bus Route Roads,136,1220000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Bazullah roadt in Div - 136 , Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20674,Roads,Completed,BR-Bus Route Roads,140,5591000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at Kodampakkam Road in Div - 133 & 140 , Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20675,Roads,Completed,BR-Bus Route Roads,136,6409000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at North usman road in Div - 136 , Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20676,Roads,Completed,BR-Bus Route Roads,142,2719000,"Repairing and Restoration of Road damaged by the Flood during North East Monsoon 2015 at West jones road in Div - 142 , Zone - 10.",Grants,10,2015-16,2017-18 BR/2015-16/20685,Roads,Completed,BR-Bus Route Roads,134,196000,"ATTENDING PATCHES IN VARIOUS ROADS IN DIV 128,134,135 ZONE-10.",Own Sources,10,2015-16,2016-17 BR/2015-16/20710,Roads,Completed,BR-Bus Route Roads,83,2000000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at TNHB 31st Street in Dn-83, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20714,Roads,Completed,BR-Bus Route Roads,92,6363000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Pari salai in Dn-92 & 93, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20716,Roads,Completed,BR-Bus Route Roads,81,4333000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Old MTH Road in Dn-81, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20722,Roads,Completed,BR-Bus Route Roads,91,5138000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Mogapair Eri Scheme 1st Main Road in Dn-91, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20723,Roads,Completed,BR-Bus Route Roads,103,4165000,"Repair and Restoration of Damaged road due to flood(Northeast Monsoon - 2015) at Halls Road from Jn of New avadi road to the Jn of Kilpauk Garden road in Dn-103, Zone-08.",Grants,8,2015-16,2016-17 BR/2015-16/20725,Roads,Completed,BR-Bus Route Roads,81,10715000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at kaliikuppam Road in Dn-81, Zone-7",Grants,7,2015-16,2016-17 BR/2015-16/20726,Roads,Completed,BR-Bus Route Roads,84,10600000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Central Avenue in Dn-84, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20727,Roads,Completed,BR-Bus Route Roads,93,3869000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Bazzar Road in Dn-93, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20728,Roads,Completed,BR-Bus Route Roads,89,2131000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Officers Colony Main Road in Dn-89, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20734,Roads,Completed,BR-Bus Route Roads,81,6291000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at North Park Street in Dn-81, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20737,Roads,Completed,BR-Bus Route Roads,81,3295000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at South Park Street in Dn-81, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20738,Roads,Completed,BR-Bus Route Roads,92,3442000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Venugopal Street in Dn-92, Zone-7",Grants,7,2015-16,2017-18 BR/2015-16/20753,Roads,Completed,BR-Bus Route Roads,121,10221000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Thiru-Vi-Ka High Road (Jn of PS Sivaswamy Salai to Jn of Luz Church Road) in Dn-119&121, Zone-IX",Grants,9,2015-16,2016-17 BR/2015-16/20755,Roads,Completed,BR-Bus Route Roads,102,19499000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Kilpauk Garden Road in Dn-102, Zone-8",Grants,8,2015-16,2016-17 BR/2015-16/20756,Roads,Completed,BR-Bus Route Roads,101,5089000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Anna Nagar 3rd Avenue eastern Side ( From the jn of 6th Avenue to the jn of 2nd avenue) in Dn-101, Zone-8",Grants,8,2015-16,2016-17 BR/2015-16/20766,Roads,Completed,BR-Bus Route Roads,101,8223000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Anna nagar 3rd avenue (Western side) from Jn of Roundana tothe jn of 6th Avenue in Dn-101, Zone - VIII.",Grants,8,2015-16,2016-17 BR/2015-16/20772,Roads,Completed,BR-Bus Route Roads,100,4773000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Anna nagar 4th main road from Jn of 3rd avenue to Door No:R88 in Dn-100, Zone - VIII.",Grants,8,2015-16,2016-17 BR/2015-16/20774,Roads,Completed,BR-Bus Route Roads,99,35149000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Anna nagar 2nd avenue from Jn of 100 feet road to the Jn of Annanagar roundtana in Dn-99&100,Zone - VIII.",Grants,8,2015-16,2016-17 BR/2015-16/20777,Roads,Completed,BR-Bus Route Roads,99,8880000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at Anna nagar 13th Main road from the Jn of Anna Nagar 4th Avenue to 17th Main road in Dn-99, Zone - VIII.",Grants,8,2015-16,2016-17 BR/2015-16/20781,Roads,Completed,BR-Bus Route Roads,102,4290000,"Repairing and Restoration of Roads damaged by the Flood during North east monsoon 2015 at New avadi road from the Jn of Anna nagar 1st avenue to the Jn of Raju street(Part) in Dn-102, Zone - VIII.",Grants,8,2015-16,2016-17 BR/2015-16/20786,Roads,Completed,BR-Bus Route Roads,167,2220000,"Repairing and restoration of road damaged for the flood during NEM 2015 at M.G.R Road in div 167, Zone- 13",Grants,12,2015-16,2017-18 BR/2015-16/20787,Roads,Completed,BR-Bus Route Roads,167,1330000,"Repairing and restoration of road damaged for the flood during NEM 2015 at nanganallur 5th main Road in div 167, Zone- 13",Grants,12,2015-16,2017-18 BR/2015-16/20801,Roads,Completed,BR-Bus Route Roads,136,196000,ATTENDING PATCHES IN VARIOUS ROADS IN DIV 136 & 142 ZONE -10.,Own Sources,10,2015-16,2016-17 BR/2015-16/20802,Roads,Completed,BR-Bus Route Roads,132,196000,"ATTENDING PATCHES IN VARIOUS ROADS IN DIV - 132, 133, ZONE -10.",Own Sources,10,2015-16,2016-17 BR/2015-16/20803,Roads,Completed,BR-Bus Route Roads,137,199000,"ATTENDING OF PATCHES IN VARIOUS ROADS IN DIV 131 137 & 140, ZONE -10",Own Sources,10,2015-16,2016-17 BR/2015-16/20833,Roads,Completed,BR-Bus Route Roads,149,590000,"Repairing and restoration of road damaged for the flood during NEM 2015 at Radha Avenue from the junction of Sridevi Kuppam to Junction of Amman Koil Dn 149, Z-11.",Grants,11,2015-16,2016-17 BR/2015-16/20835,Roads,Completed,BR-Bus Route Roads,149,590000,"Repairing and restoration of road damaged for the flood during NEM 2015 at Sridevi Kuppam Main Road from the junction of NSK Salai to Radha Avenue Dn 149, Z-11.",Grants,11,2015-16,2016-17 BR/2015-16/20837,Roads,Completed,BR-Bus Route Roads,143,2610000,"Repairing and restoration of road damaged for the flood during NEM 2015 at Mugappair Main Road from the junction of 100 Ft Byepass road to Mogappair West main road Dn 143, Z-11.",Grants,11,2015-16,2016-17 BR/2015-16/20838,Roads,Completed,BR-Bus Route Roads,150,5590000,"Repairing and restoration of road damaged for the flood during NEM 2015 at Chettyar Aragam Main Road from the junction of Mount Poonamalle to Ramachandra Hospital Second Gate Dn 150, Z-11.",Grants,11,2015-16,2016-17 BR/2015-16/22575,Roads,Completed,BR-Bus Route Roads,59,830000,"Restoration of roadcut at North fort road(Muthuswamy Salai )from the junction of Esplande Road to EVR periyar salail to a length of 450 meters by TNEB in Dn-59,Zone-5",Deposit Works,5,2015-16,2016-17 BR/2015-16/22734,Roads,Completed,BR-Bus Route Roads,200,66134000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Nookampalayam main road in Dn-200, Zone-XV.",Grants,15,2015-16,2017-18 BR/2015-16/22849,Roads,Completed,BR-Bus Route Roads,111,14620000,Providing and Laying of Cement Concrete Road using M40 Grade Concrete Road damaged by the Flood during North East Monsoon 2015 at Giriappa Road in Zone-9,Grants,9,2015-16,2016-17 BR/2015-16/22928,Roads,Completed,BR-Bus Route Roads,162,3677000,LAYING CEMENT CONCRETE ROAD AT THILLAI GANGA NAGAR 23 TH MAIN ROAD IN DIV 162 ZONE - 12,Own Sources,12,2015-16,2017-18 BR/2015-16/23053,Roads,Completed,BR-Bus Route Roads,150,2536009,"Road Cut Restoration At Chettiyar Agaram main road From Chainage 770 M - 1540 M Dn 150, Z-11.",Deposit Works,11,2015-16,2016-17 BR/2015-16/23205,Roads,Completed,BR-Bus Route Roads,95,998000,"Proposed construction of Centre median with Stainless steel Grill at Sterling road ( from the jn Valluvar kottam road to the jn of Indian Bank and from the jn of Sterling road to the jn of Sterling avenue) in Dn 110 , zone - 9 & MTH road (from the jn of ICF signal to the jn of Nathan traders) in DN - 95, Zone 8",Own Sources,8,2015-16,2018-19 BR/2015-16/2341,Road Cut,Completed,BR-Bus Route Roads,100,919000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT ANNA NAGAR 3RD AVENUE (From Jn of Anna Nagar Arch to Siddha Hospital) IN DN - 100, ZONE - 8",Deposit Works,8,2015-16,2016-17 BR/2015-16/24771,Roads,Completed,BR-Bus Route Roads,92,980000,Proposed Construction of Crash barrier type centre median @ church road (From the jn of Rathnam street to the jn of ch 250m) in Dn - 92 in Zone-7,Own Sources,7,2015-16,2016-17 BR/2015-16/25053,Roads,Completed,BR-Bus Route Roads,177,864000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Sastri Nagar Main road (Velachery) in Div - 177, Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/25054,Roads,Completed,BR-Bus Route Roads,177,864000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Brindavan Nagar Main road (Velachery) in Div - 177, Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/25055,Roads,Completed,BR-Bus Route Roads,180,1170000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at 100 Feet Road (Taramani) in Div - 180 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/25056,Roads,Completed,BR-Bus Route Roads,180,1170000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at 100 Feet Road (Taramani) in Div - 180 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/25057,Roads,Completed,BR-Bus Route Roads,180,1170000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at L.B. Road (Ration Shop) in Div - 180 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/25058,Roads,Completed,BR-Bus Route Roads,180,1170000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at S.R.P. Tools in Div - 180 , Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/25059,Roads,Completed,BR-Bus Route Roads,176,860000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at MG Road in Div - 176, Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/25060,Roads,Completed,BR-Bus Route Roads,176,864000,"Proposed Construction of 1 no of Modern Stainless Steel Bus Shelters at Besant Nagar in Div - 176, Zone - 13",MLACDS,13,2015-16,2016-17 BR/2015-16/26694,Roads,Completed,BR-Bus Route Roads,132,840000,"TRAFFIC IMPROVEMENT TO ASHOK NAGAR 7TH AVENUE IN DIV 132,ZONE-10",Own Sources,10,2015-16,2017-18 BR/2015-16/26697,Roads,Completed,BR-Bus Route Roads,134,750000,"PROVIDING TRAFFIC IMPROVEMENT WORK N.S.K SALAI FROM VADAPLANI DEPO TO POWER HOUSE DIV 133& 134,ZONE-10",Own Sources,10,2015-16,2017-18 BR/2015-16/26698,Roads,Completed,BR-Bus Route Roads,128,800000,"PROVIDING TRAFFIC IMPROVEMENT TO N.S.K SALAI FROM 80 FEET ROAD TO THIRU NAGAR 1ST STREET. IN DIV 128,129,134 IN ZONE-10",Own Sources,10,2015-16,2016-17 BR/2015-16/26701,Road Cut,Completed,BR-Bus Route Roads,194,310000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT EASWARAN KOIL STREET IN DN 194 , ZONE 15",Deposit Works,15,2015-16,2018-19 BR/2015-16/26703,Road Cut,Completed,BR-Bus Route Roads,194,410000,"Restoration of road cut made by TANGANGO at rajiv nagar Nagar main road in Div - 194, Zone 15.",Grants,15,2015-16,2018-19 BR/2015-16/26953,Roads,Completed,BR-Bus Route Roads,138,250000,"TRAFFIC IMPROVEMENT TO 60 FEET ROAD IN DIV 138,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26958,Roads,Completed,BR-Bus Route Roads,135,780000,TRAFFIC IMPROVEMENT TO CORPORATION COLONY ROAD & BARATHIDASAN COLONY MAIN ROAD IN DIV 135& 138 ZONE-10.,Own Sources,10,2015-16,2017-18 BR/2015-16/26960,Roads,Completed,BR-Bus Route Roads,132,483000,"TRAFFIC IMPROVEMENT TO ASHOK NAGAR 2ND AVENUE IN DIV 138,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26961,Roads,Completed,BR-Bus Route Roads,141,354000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT NEW BOAG ROAD IN DIV 141,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26962,Roads,Completed,BR-Bus Route Roads,131,740000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT 80 FEET ROAD ROAD IN DIV 131,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26963,Roads,Completed,BR-Bus Route Roads,137,746000,"TRAFFIC IMPROVEMENT TO MUNUSWAMY ROAD IN DIV 137,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26964,Roads,Completed,BR-Bus Route Roads,131,955000,"PROVIDING TRAFFIC IMPROVEMENT WORK TO P.T. RAJAN SALAI FROM ASHOK PILLAR ROAD TO KAMARAJAR SALAI IN DIV 131&132,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26965,Roads,Completed,BR-Bus Route Roads,128,800000,"PROVIDING TRAFFIC IMPROVEMENT TO N.S.K SALAI FROM VADAPALANI DEPO TO 80 FEET ROAD. IN DIV 128,129,134 ZONE-10.",Own Sources,10,2015-16,2016-17 BR/2015-16/26966,Roads,Completed,BR-Bus Route Roads,138,582000,"TRAFFIC IMPROVEMENT TO ASHOK PILLAR ROAD IN DIV 138,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26967,Roads,Completed,BR-Bus Route Roads,128,915000,"TRAFFIC IMPROVEMENT TO P.V. RAJAMANAR, VANNIER ST FROM PONAMBALAM ST TO P.T.RAJAN SALAI IN DIV 128&127ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26968,Roads,Completed,BR-Bus Route Roads,137,940000,"PROVIDING TRAFFIC IMPROVEMENTWORKS AT RAMASWAMY SALAI IN DIV 131&137,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26969,Roads,Completed,BR-Bus Route Roads,140,688000,"PROVIDING TRAFFIC IMPROVEMENT WORKS AT REDDY KUPPAM ROAD IN DIV 140,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26970,Roads,Completed,BR-Bus Route Roads,137,955000,"PROVIDING TRAFFIC IMPROVEMENT WORKS AT LAKSHMANSWAMI SALAI IN DIV 131&137,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26972,Roads,Completed,BR-Bus Route Roads,129,630000,"PROVIDING TRAFFIC IMPROVEMENT WORKS AT S.B.I COLONY II ND & S.B.I COLONY III RD STREET IN DIV 129,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26973,Roads,Completed,BR-Bus Route Roads,136,430000,"PROVIDING TRAFFIC IMPROVEMENT WORKS AT DR.NAIR ROADS IN DIV 136,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26974,Roads,Completed,BR-Bus Route Roads,141,660000,"PROVIDING TRAFFIC IMPROVEMENT WORKS AT BURKIT ROAD IN DIV 141,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/26986,Roads,Completed,BR-Bus Route Roads,95,1400000,"Providing Traffic improvements at Anna nagar 18th main road in Dn - 95, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/26989,Roads,Completed,BR-Bus Route Roads,102,1599000,"Providing traffic improvements at Anna nagar 1st avenue in Dn - 102, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/26994,Roads,Completed,BR-Bus Route Roads,100,1600000,"Providing the traffic improvements at Anna nagar 6th avenue in Dn - 99,100 & 101, Zone - 8",Own Sources,8,2015-16,2017-18 BR/2015-16/26998,Roads,Completed,BR-Bus Route Roads,75,985000,"Widening the existing road at strahans Road From Perambur Barracks road to Angalamman koil street to chainage of 150 - 225 m) , in Ward-73 Zone -6",Own Sources,6,2015-16,2016-17 BR/2015-16/26999,Roads,Completed,BR-Bus Route Roads,75,975000,"Widening the existing road at strahans Road From Perambur Barracks road to Angalamman koil street to chainage of 225 - 350 m) , in Ward-73 Zone -6",Own Sources,6,2015-16,2016-17 BR/2015-16/27005,Roads,Completed,BR-Bus Route Roads,95,230000,"Providing traffic improvements at Anna nagar 21 st Main road in Dn - 95, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27011,Roads,Completed,BR-Bus Route Roads,103,570000,"Providing traffic improvements at Kilpauk Garden road in Dn - 103, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27018,Roads,Completed,BR-Bus Route Roads,105,499000,"Providing traffic improvements at MMDA Colony Main road in Dn - 105, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27020,Roads,Completed,BR-Bus Route Roads,74,620000,"Removing Existing Kerbs and Forming Centre Median with Mass RMC and stainless steel grill Concrete at Medavakkam Tank Road From Konnur High road to Trust Square street in Reach 2 Division- 74, Zone - 6",Own Sources,6,2015-16,2016-17 BR/2015-16/27022,Roads,Completed,BR-Bus Route Roads,104,350000,"Providing traffic improvements at Gangadeeswarar koil street in Dn - 104, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27024,Roads,Completed,BR-Bus Route Roads,91,670000,"Providing traffic improvements at Mogapair Eri scheme 6th Main Road in Dn -91, Zone -7",Own Sources,7,2015-16,2017-18 BR/2015-16/27025,Roads,Completed,BR-Bus Route Roads,103,470000,"Providing traffic improvements at Ormes Road in Dn -103, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27026,Roads,Completed,BR-Bus Route Roads,103,370000,"Providing traffic improvements at Harleys Road in Dn -103, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27027,Roads,Completed,BR-Bus Route Roads,129,822000,"PROVIDING TRAFFIC IMPROVEMENT WORKS AT ARUNACHALAM SLAI IN DIV 129,ZONE-10.",Own Sources,10,2015-16,2016-17 BR/2015-16/27028,Roads,Completed,BR-Bus Route Roads,141,820000,"PROVIDING TRAFFIC IMPROVEMENT TO SOUTH WEST BOAG ROAD IN DIV 141,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/27029,Roads,Completed,BR-Bus Route Roads,103,500000,"Providing traffic improvements at Purasaivakkam High Road in Dn -103, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27030,Roads,Completed,BR-Bus Route Roads,135,904000,"PROVIDING TRAFFIC IMPROVEMENT WORKS AT ARYA GOWDA ROAD IN DIV 135,ZONE-10.",Own Sources,10,2015-16,2016-17 BR/2015-16/27031,Roads,Completed,BR-Bus Route Roads,138,510000,"TRAFFIC IMPROVEMENT TO PRAKASAM ROAD,NAGESHWARA RAO ROAD & BASHYAM ROAD IN DIV 136,ZONE-10.",Grants,10,2015-16,2017-18 BR/2015-16/27032,Roads,Completed,BR-Bus Route Roads,134,750000,TRAFFIC IMPROVEMENT TO N.S.K SALAI POWER HOUSE TO BRIDGE IN DIV 133&134ZONE-10.,Own Sources,10,2015-16,2017-18 BR/2015-16/27033,Roads,Completed,BR-Bus Route Roads,105,287000,"Providing traffic improvements at Vinayagapuram Main Road in Dn -103, Zone -8",Own Sources,8,2015-16,2016-17 BR/2015-16/27034,Roads,Completed,BR-Bus Route Roads,96,1033000,"Providing traffic improvements at Konnur high Road in Dn -96, Zone -8",Own Sources,8,2015-16,2016-17 BR/2015-16/27035,Roads,Completed,BR-Bus Route Roads,102,800000,"Providing traffic improvements at New Avadi Road (From the jn of anna nagar 1st avenue to the jn of Raju street) in Dn -102, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27036,Roads,Completed,BR-Bus Route Roads,95,800000,"Providing traffic improvements at New Avadi Road (From the jn of ICF signal to the jn of Nathamuni signal) in Dn -95, Zone -8",Own Sources,8,2015-16,2017-18 BR/2015-16/27038,Roads,Completed,BR-Bus Route Roads,106,777000,"Providing traffic improvements at Nelson Manickam Road (From the jn of Metha nagar bridge to the jn of EVR salai) in Dn - 106, Zone -8",Own Sources,8,2015-16,2016-17 BR/2015-16/27039,Roads,Completed,BR-Bus Route Roads,100,1219000,"Providing traffic improvements at Anna Nagar 4th avenue in Dn - 100, Zone -8",Own Sources,8,2015-16,2016-17 BR/2015-16/27040,Roads,Completed,BR-Bus Route Roads,91,400000,"Providing traffic improvements at Kavimani Street in Dn - 91, Zone -7",Own Sources,7,2015-16,2017-18 BR/2015-16/27041,Roads,Completed,BR-Bus Route Roads,78,366000,"Providing traffic improvements at Choolai High Raod in Dn - 78, Zone -6",Grants,6,2015-16,2017-18 BR/2015-16/27050,Roads,Completed,BR-Bus Route Roads,70,870000,"Providing traffic improvements at Permbur Fly over in Dn - 70, Zone - 6",Own Sources,6,2015-16,2017-18 BR/2015-16/27052,Roads,Completed,BR-Bus Route Roads,123,913000,"Traffic improvement work at St.Marys road (From the jn of RK mutt road to the jn of TTK road) in Dn - 123&124, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27053,Roads,Completed,BR-Bus Route Roads,114,703000,"Traffic improvement work at Marina Service Road (From the jn of MGR samathi to Loop Road) (Reach I) in Dn - 114,& 117, Zone -9",Own Sources,9,2015-16,2017-18 BR/2015-16/27055,Roads,Completed,BR-Bus Route Roads,118,684000,"Traffic improvement work at Cathedral Road(From the jn of TTK Road to Anna Salai) (Reach- I) in Dn - 118, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27056,Roads,Completed,BR-Bus Route Roads,119,769000,"Traffic improvement work at Dr.Radhakrishnan Salai (From TTK Road to Nadesan Salai) (Reach I) in Dn- 119 & 121, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27057,Roads,Completed,BR-Bus Route Roads,114,799000,"Traffic improvement works at Kamaraj Salai (From Walaja Road to Karaneswarar pagoda Street) (Reach I) in Dn - 114 &116, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27058,Roads,Completed,BR-Bus Route Roads,124,366000,"Traffic improvement work at Venkatesa Agraharam Street From the Jn of RK Mutt Road to the Jn of St Marys Road in Dn - 124, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27061,Roads,Completed,BR-Bus Route Roads,126,220000,"Traffic improvement work at Singri Mutt Road From the Jn of St Marys Road to the Jn of Venkatakrishna Road in Dn - 126, Zone -9",Own Sources,9,2015-16,2017-18 BR/2015-16/27066,Roads,Completed,BR-Bus Route Roads,119,497000,"Traffic improvement work at Gowdia mutt road From the Jn of TTK Road to the Jn of Thiru.vi.ka.road in Dn - 119, Zone -9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27073,Roads,Completed,BR-Bus Route Roads,171,757000,"PROVIDING TRAFFIC IMPROVEMENTS WORK AT 70 FEET ROAD IN DIV - 171, ZONE- 13",Own Sources,13,2015-16,2017-18 BR/2015-16/27076,Roads,Completed,BR-Bus Route Roads,120,889000,"Traffic improvement work at Dr.Natesan Road from the Jn of Besant Road to the Jn of Radhakrishnan Salai in Dn - 120 & 121, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27077,Roads,Completed,BR-Bus Route Roads,177,443000,"PROPOSED TRAFFIC IMPROVEMENTS WORK AT KAKKAN NAGAR MAIN ROAD IN DIV 177 , ZONE - 13",Own Sources,13,2015-16,2017-18 BR/2015-16/27078,Roads,Completed,BR-Bus Route Roads,177,230000,PROVIDING TRAFFIC IMPROVEMENT WORK AT SASTRI NAGAR MAIN ROAD IN DIV-177 ZONE-13..,Own Sources,13,2015-16,2017-18 BR/2015-16/27079,Roads,Completed,BR-Bus Route Roads,174,715000,"PROPOSED TRAFFIC IMPROVEMENTS WORK AT FIVE FURLONG ROAD IN DIV 174 , ZONE - 13",Own Sources,13,2015-16,2017-18 BR/2015-16/27080,Roads,Completed,BR-Bus Route Roads,174,288000,"PROPOSED TRAFFIC IMPROVEMENT AT CHAKARAPONI ROAD IN DIV 174,ZONE-13.",Own Sources,13,2015-16,2017-18 BR/2015-16/27081,Roads,Completed,BR-Bus Route Roads,170,375000,"PROPOSED TRAFFIC IMPROVEMENT TO ALANDUR ROAD IN DIV 170,ZONE-13.",Own Sources,13,2015-16,2017-18 BR/2015-16/27082,Roads,Completed,BR-Bus Route Roads,174,682000,PROVIDING TRAFFIC IMPROVEMENT WORK TO RACE COURSE ROAD DIV 174ZONE-13,Own Sources,13,2015-16,2017-18 BR/2015-16/27083,Roads,Completed,BR-Bus Route Roads,138,627000,PROVIDING TRAFFIC IMPROVEMENTS WORK AT KALKI KRISHNAMOORTY SALAI FROM WEST AVENUE TO OMR IN DIV 180 ZONE 13,Own Sources,10,2015-16,2017-18 BR/2015-16/27085,Roads,Completed,BR-Bus Route Roads,119,511000,"Traffic improvement works at Musri Subramaniam Salai from the Jn of Luz Church Road to the Jn of PV Sivasami Salai in Dn - 119, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27116,Roads,Completed,BR-Bus Route Roads,113,980000,"Traffic improvement work at Valluvar Kottam High Road (from MGR Salai to Uthamar Gandhi Salai) in Dn - 113, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27118,Roads,Completed,BR-Bus Route Roads,117,651000,"Traffic improvement work at B.V.Narasiman Road (North Boag Road) from the Jn of GN Chetty Road to the Jn of Thiyagaraya Road in Dn - 117, Zone -9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27120,Roads,Completed,BR-Bus Route Roads,117,572000,"Traffic improvement works at Thanikachalam Road from the Jn of Thiyagaraya Road to the Jn of Venkatanarayana Road in Dn - 117, Zone -9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27124,Roads,Completed,BR-Bus Route Roads,123,544000,"Traffic improvement work at Eldams Road from the Jn of TTK Road to the Jn of Anna Salai in Dn - 123, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27126,Roads,Completed,BR-Bus Route Roads,125,338000,"Traffic improvement work at Rosary Church Road from the Jn of Kutchery Road to the Jn of Santhome High Road in Dn - 125, Zone -9",Own Sources,9,2015-16,2017-18 BR/2015-16/27127,Roads,Completed,BR-Bus Route Roads,113,546000,"Traffic improvement work at North Usman Road Flyover in Dn - 113, Zone -9",Own Sources,9,2015-16,2017-18 BR/2015-16/27129,Roads,Completed,BR-Bus Route Roads,110,95000,"Traffic improvement work at Sivaganga Road from the jn of Wheat Craft Road to the jn of Sterling Road in Dn - 110, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27131,Roads,Completed,BR-Bus Route Roads,124,637000,"Traffic improvement work at Kutchery Road from the jn of Luz Corner to the jn of Rosary Church Road in Dn - 124, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27134,Roads,Completed,BR-Bus Route Roads,110,952000,"Traffic improvement work at Tank bund Road from the jn of valluvar kottam road to the jn of Nungambakkam subway in Dn - 110, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27135,Roads,Completed,BR-Bus Route Roads,110,164000,"Traffic improvement work at Wheat Crafts Road from the jn of valluvar kottam road to the jn of Sivaganga road in Dn - 110, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27136,Roads,Completed,BR-Bus Route Roads,110,406000,"Traffic improvement works at 70 Feet Scheme Road from the Jn of Mahalingapuram Main Road to the Jn of MGR Salai in Dn - 110, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27138,Roads,Completed,BR-Bus Route Roads,138,833000,PROVIDING TRAFFIC IMPROVEMENTS WORK AT CATHEDRALROAD FROM GEMINI FLYOVER TO RADHAKRISNAN ROAD IN DIV 118 ZONE 9 - REACH 1.,Own Sources,10,2015-16,2016-17 BR/2015-16/27141,Roads,Completed,BR-Bus Route Roads,138,833000,PROVIDING TRAFFIC IMPROVEMENTS WORK AT CATHEDRALROAD FROM GEMINI FLYOVER TO RADHAKRISNAN ROAD IN DIV 118 ZONE 9 - REACH 2.,Own Sources,10,2015-16,2016-17 BR/2015-16/27142,Roads,Completed,BR-Bus Route Roads,114,744000,PROVIDING TRAFFIC IMPROVEMENTS WORK AT KAMARAJAR SALAI FROM WALAJA ROAD TO KARANEESWARAR POGODA STREET IN DIV 114 & 116 ZONE 9 - REACH 1,Own Sources,9,2015-16,2016-17 BR/2015-16/27143,Roads,Completed,BR-Bus Route Roads,138,744000,PROVIDING TRAFFIC IMPROVEMENTS WORK AT KAMARAJAR SALAI FROM WALAJA ROAD TO KARANEESWARAR POGODA STREET IN DIV 114 & 116 ZONE 9 - REACH 2,Own Sources,10,2015-16,2016-17 BR/2015-16/27144,Roads,Completed,BR-Bus Route Roads,114,744000,PROVIDING TRAFFIC IMPROVEMENTS WORK AT KAMARAJAR SALAI FROM WALAJA ROAD TO KARANEESWARAR POGODA STREET IN DIV 114 & 116 ZONE 9 - REACH 3,Own Sources,9,2015-16,2016-17 BR/2015-16/27146,Roads,Completed,BR-Bus Route Roads,116,289000,"Traffic improvement work at Dr.Besant Road (from Peters road to Quaid e Milleth Road) in Dn - 116, Zone -9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27148,Roads,Completed,BR-Bus Route Roads,179,760000,PROVIDING TRAFFIC IMPROVEMENT TOR GANDHI ROAD IN DIV 179ZONE-13..,Own Sources,13,2015-16,2017-18 BR/2015-16/27149,Roads,Completed,BR-Bus Route Roads,177,185000,"PROVIDING TRAFFIC IMPROVEMENT TO LAKE VIEW ROAD IN DIV 177 ,ZONE-13.",Own Sources,13,2015-16,2017-18 BR/2015-16/27154,Roads,Completed,BR-Bus Route Roads,123,576000,"Traffic improvement works at Dr.Ranga road Road (from the jn of CP Ramasamy road to RK mutt road) in Dn- 123, Zone - 9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27163,Roads,Completed,BR-Bus Route Roads,123,490000,"Traffic improvement work at G.N.Chetty road ( from the Jn. of Dr.Nair Road to the jn Dr.Narasiman Road) in Dn-123,Zone - 9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27167,Roads,Completed,BR-Bus Route Roads,137,478000,"PROVIDING TRAFFIC IMPROVEMENT WORK TOP.V.RAJAMANNAR, VANNIER ST FROM PONNAMBALAM ST TO N.S.K SALAI IN DIV137,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/27168,Roads,Completed,BR-Bus Route Roads,132,275000,"PROVIDING TRAFFIC IMPROVEMENT WORK P.T RAJAN SALAI FROM 100 FEET ROAD TO KAMARAJAR SALAIIN DIV 132,ZONE-10.",Own Sources,10,2015-16,2017-18 BR/2015-16/27169,Roads,Completed,BR-Bus Route Roads,109,377000,"Traffic improvement work at Nelson Manickam Road (from Metha nagar bridge to Nungambakkam subway) in Dn-106 & 109, Zone-9.",Own Sources,9,2015-16,2017-18 BR/2015-16/27171,Roads,Completed,BR-Bus Route Roads,113,320000,"Traffic improvement work at Kamdar Nagar and 40 Feet Scheme Road in Dn-113, Zone-9.",Own Sources,9,2015-16,2017-18 BR/2015-16/27172,Roads,Completed,BR-Bus Route Roads,123,197000,"Traffic improvement work at Karpagambal Nagar main road in Dn-123, Zone-9.",Own Sources,9,2015-16,2017-18 BR/2015-16/27173,Roads,Completed,BR-Bus Route Roads,113,1181000,"Traffic improvement work at Dr.M G R Salai in Dn-113, Zone-9.",Own Sources,9,2015-16,2017-18 BR/2015-16/27175,Roads,Completed,BR-Bus Route Roads,121,953000,"PROVIDING TRAFFIC IMPROVEMENTS WORK AT RADHAKRISNAN ROAD FROM NATESAN SALAI CATHERAL ROAD IN DIV 121 , ZONE 9 - REACH 1",Own Sources,9,2015-16,2016-17 BR/2015-16/27178,Roads,Completed,BR-Bus Route Roads,121,953000,"PROVIDING TRAFFIC IMPROVEMENTS WORK AT RADHAKRISNAN ROAD FROM NATESAN SALAI CATHERAL ROAD IN DIV 121 , ZONE 9 - REACH 2",Own Sources,9,2015-16,2016-17 BR/2015-16/27183,Roads,Completed,BR-Bus Route Roads,116,770000,"Traffic improvement works at Kamaraj Salai (From Walaja Road to Karaneswarar pagoda Street) (Reach II) in Dn - 114 &116, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27207,Roads,Completed,BR-Bus Route Roads,118,542000,"Traffic improvement work at Cathedral Road(From the jn of TTK Road to Anna Salai) (Reach- II) in Dn - 118, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27261,Roads,Completed,BR-Bus Route Roads,63,980000,"Attending emergency patch work at G P Lane in Dn-63,Zone-5,",Own Sources,5,2015-16,2016-17 BR/2015-16/27422,Roads,Completed,BR-Bus Route Roads,61,998000,"Attending Patch work at East Ramanathan road (Gengu Reddy Subway) from subway to E,V,R Periyar salai in Div -61 Zone - 5",Own Sources,5,2015-16,2016-17 BR/2015-16/27524,Roads,Completed,BR-Bus Route Roads,114,676000,"Traffic improvement work at Marina Service Road (From the jn of MGR samathi to Loop Road) (Reach II) in Dn - 114,& 117, Zone -9",Own Sources,9,2015-16,2017-18 BR/2015-16/27528,Roads,Completed,BR-Bus Route Roads,121,912000,"Traffic improvement work at Dr.Radhakrishnan Salai (From TTK Road to Nadesan Salai) (Reach II) in Dn- 119 & 121, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27537,Roads,Completed,BR-Bus Route Roads,116,823000,"Traffic improvement works at Kamaraj Salai (From Walaja Road to Karaneswarar pagoda Street) (Reach III) in Dn - 114 &116, Zone -9",Own Sources,9,2015-16,2016-17 BR/2015-16/27841,Roads,Completed,BR-Bus Route Roads,117,200000,"Attending Urgent Patchwork in Dr.B.V.Narasiamman Salai and Thanigachalam Road IN Dn:117,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27843,Roads,Completed,BR-Bus Route Roads,122,920000,"Attending Urgent Patchwork in North Usman Road ,K.B.Dasan Road ,Conron smith Road ,Karpagambal Nagar Main Road in Dn:122,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27844,Roads,Completed,BR-Bus Route Roads,117,983000,"Attending Urgent Patchwork in Chevalihar Sivaji Ganesan Road ,Theyagaraya Salai and Thirumalai pillai Road in Dn:117,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27846,Roads,Completed,BR-Bus Route Roads,123,200000,"Attending Urgent Patchwork in Eldams Road in Dn:123,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27847,Roads,Completed,BR-Bus Route Roads,110,989000,"Attending Urgent Patchwork in Dr M G R Salai in Dn:110 & 113,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27849,Roads,Completed,BR-Bus Route Roads,117,620000,"Attending Urgent Patchwork in Gopathyb Narayana Salai and Dr M G R Salai in Dn:117 & 113,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27978,Roads,Completed,BR-Bus Route Roads,119,780000,"Attending Urgent Patchwork in Thiru Vi Ka High Road in Dn:119,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/27993,Roads,Completed,BR-Bus Route Roads,171,198100,"Providing and fixing Stainless steel handrail work at Sardarpatel Road in Dn-171, Zone-XIII.",Own Sources,13,2015-16,2016-17 BR/2015-16/28454,Roads,Completed,BR-Bus Route Roads,58,780000,"Attending patchwork at Raja Muthaiha salai in Ward -58 , Zone -5",Grants,5,2015-16,2016-17 BR/2015-16/28569,Roads,Completed,BR-Bus Route Roads,85,183000,Attending Patches at Madhana Kuppam main road kavi mani salai pari salai bazar road venugopal street and various Bus Route Roads in Zone 7,Grants,7,2015-16,2016-17 BR/2015-16/28570,Roads,Completed,BR-Bus Route Roads,85,199000,Attending Patches at various Bus Route Roads in Zone 7,Grants,7,2015-16,2016-17 BR/2015-16/28571,Roads,Completed,BR-Bus Route Roads,85,199000,Attending Patches at various Bus Route Roads in Zone 7,Grants,7,2015-16,2016-17 BR/2015-16/28675,Roads,Completed,BR-Bus Route Roads,179,947000,Attending Patches due to flood damage with DBM by Paver Finish at Velachery Main Road (Between J7 Police Station to Junction of Jaganathapuram 1st street) in Dn-179 Zone-XIII.,Own Sources,13,2015-16,2016-17 BR/2015-16/28676,Roads,Completed,BR-Bus Route Roads,174,928000,Attending Patches due to flood damage with DBM by Paver Finish at Velachery Main Road (Between Junction of IIT gate to Metrowater pumping station) in Dn-174 Zone-XIII.,Own Sources,13,2015-16,2016-17 BR/2015-16/28707,Roads,Completed,BR-Bus Route Roads,150,2536009,"Road Cut Restoration At Chettiyar Agaram main road From Chainage 0 - 770 M in div - 150 , zone - 11",Deposit Works,11,2015-16,2016-17 BR/2015-16/28715,Roads,Completed,BR-Bus Route Roads,142,820000,"TRAFFIC IMPROVEMENT TO RENGA BASHYAM ST,PERUMAL KOIL ST& VANNIER ST IN DIV 142, ZONE-10",Own Sources,10,2015-16,2017-18 BR/2015-16/29079,Roads,Completed,BR-Bus Route Roads,122,200000,"Attending Urgent Patchwork in St Marys Road and Kutcherry Road in Dn:122,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/29080,Roads,Completed,BR-Bus Route Roads,117,200000,"Attending Urgent Patchwork in Valluvar Kottam High Road IN Dn:117,Zone:9.",Own Sources,9,2015-16,2016-17 BR/2015-16/29214,Roads,Completed,BR-Bus Route Roads,74,610000,"Removing Existing Kerbs and Forming Centre Median with Mass RMC and stainless steel grill Concrete at Medavakkam Tank Road From Konnur High road to Trust Square street in Reach 1 Division- 74, Zone - 6",Own Sources,6,2015-16,2016-17 BR/2015-16/29567,Roads,Completed,BR-Bus Route Roads,137,890000,"Improvement to foot path at THEYAGARJA ROAD ( From DR. Nair road to Panagal park) IN DIV 136, ZONE-10.",Own Sources,10,2015-16,2016-17 BR/2015-16/29775,Roads,Completed,BR-Bus Route Roads,70,378000,"Proposed Construction of Crash Barrier Type Centre Median at Dr.Ambedkar College Road from Chainage 245m to 290m in Division 70, Zone 6",Own Sources,6,2015-16,2016-17 BR/2015-16/29799,Footpath,Completed,BR-Bus Route Roads,142,990209,"WIDENING OF EARTHEN ROAD AT THEYAGARAJA ROAD(NORTH SIDE),IN DIV- 136 , ZONE-10",Own Sources,10,2015-16,2016-17 BR/2015-16/29805,Footpath,Completed,BR-Bus Route Roads,142,993000,"WIDENING OF EARTHEN ROAD AT THEYAGARAJA ROAD(SOUTH SIDE),IN DIV- 136 , ZONE-10",Own Sources,10,2015-16,2017-18 BR/2015-16/30498,Roads,Completed,BR-Bus Route Roads,73,999000,"Forming Foot path at strahans Road From Perambur Barracks road to Angalamman koil street to chainage of 0- 300 m) (South side ) , in Ward-73 Zone -6",Own Sources,6,2015-16,2016-17 BR/2015-16/30795,Roads,Completed,BR-Bus Route Roads,96,956000,"Restoration of Road Cut Made by CMWSSB at Konnur High Road in Division 96, Zone 8",Deposit Works,8,2015-16,2016-17 BR/2015-16/30825,Roads,Completed,BR-Bus Route Roads,104,100000,"Fixing of SS Grills over the Existing Centre median at Purasaivalkam High road from the junction of Tana street to the Junction of of Gangadeeswarar Koil street in Dn - 104-, Zone - 8.",Own Sources,8,2015-16,2016-17 BR/2015-16/31059,Road Cut,Completed,BR-Bus Route Roads,194,300000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT KUMARAN NAGAR MAIN ROAD IN DN 194 , ZONE 15",Deposit-Non Asset,15,2015-16,2018-19 BR/2015-16/31060,Road Cut,Completed,BR-Bus Route Roads,195,940000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KANNAGI NAGAR 2ND MAIN ROAD IN DN 195 , ZONE 15",Own Sources,15,2015-16,2018-19 BR/2015-16/31064,Roads,Completed,BR-Bus Route Roads,200,580000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KUMARANKUDIL MAIN ROAD IN DIV - 194 , ZONE - 15",Deposit Works,15,2015-16,2018-19 BR/2015-16/32151,Roads,Completed,BR-Bus Route Roads,96,4880000,"Attending Emergency patch work at Konnur high road from the jn of Medavakkam tank road to the jn of Portious Street in Dn - 96, zone - 8",Own Sources,8,2015-16,2016-17 BR/2015-16/32336,Roads,Completed,BR-Bus Route Roads,47,990000,"RELAYING THE road with CBC by paver finishing using plastic wastse at Kathivakam High road Bridge Portion IN DIVISION -47 , ZONE -04.",Own Sources,4,2015-16,2017-18 BR/2015-16/32349,Footpath,Completed,BR-Bus Route Roads,N13,655000,"Repairs of footpath and black and white painting in Zone - 13 , div 170-182.",Own Sources,,2015-16,2016-17 BR/2015-16/32350,Roads,Completed,BR-Bus Route Roads,N13,665000,Repairs of footpath and Black and white painting in Zone -13 from Division 170-182.,Own Sources,,2015-16,2016-17 BR/2015-16/32773,Roads,Completed,BR-Bus Route Roads,92,989000,Proposed Construction of Crash barrier type centre median @ church road (from ch 250m - 500 m) in Dn - 92 in Zone-7,Own Sources,7,2015-16,2016-17 BR/2015-16/32804,Roads,Completed,BR-Bus Route Roads,143,960000,Proposed Construction of Crash barrier type centre median @ church road (From the jn of Pari salai to ch of 250m) in Dn - 92 in Zone-7,Own Sources,11,2015-16,2016-17 BR/2015-16/32814,Roads,Completed,BR-Bus Route Roads,40,870000,"ATTENDING Patch work at (T.H Road and North Teriminus road) , (jn of Ennore express road and North Terminus road in div - 39 ), (jn of vaidhynathan street and Ellays stree Jn ), jn of vaidhyanathan street and Senni amman koil street ), in Div -40 , Zone 4",Own Sources,4,2015-16,2016-17 BR/2015-16/32818,Roads,Completed,BR-Bus Route Roads,40,950000,"Strenghtening and Relaying the road with BC by using plastic waste at vaithyanathan bridge over the Deck portion (Southern side )Div -40 , Zone 4",Own Sources,4,2015-16,2016-17 BR/2015-16/32819,Roads,Completed,BR-Bus Route Roads,40,952000,"Strenghtening and Relaying the road with BC by using plastic waste at vaithyanathan bridge over the Deck portion (Northern side )Div -40 , Zone 4",Own Sources,4,2015-16,2016-17 BR/2015-16/32902,Roads,Completed,BR-Bus Route Roads,40,870000,"Repairing and Relaying with BC at Senniamman Koil Street (north) ,Division-40,Zone-4",Own Sources,4,2015-16,2017-18 BR/2015-16/33504,Roads,Completed,BR-Bus Route Roads,28,950000,"Restoration oif road cut @ Madhavaram milk colony in Di -28, Zone - 03.",Own Sources,3,2015-16,2016-17 BR/2015-16/33506,Roads,Completed,BR-Bus Route Roads,28,690000,"Restoration of Road cut at Madhavaram milk colony in Div - 28, zone - 03.",Deposit Works,3,2015-16,2016-17 BR/2015-16/33661,Roads,Completed,BR-Bus Route Roads,92,629952,Proposed Construction of Crash barrier type centre median at church road (From the junction of Rathinam Salai ) in Dn - 92 in Zone-7,Own Sources,7,2015-16,2016-17 BR/2015-16/33675,Roads,Completed,BR-Bus Route Roads,73,989000,"Widening of Existing road at strahans road from perambur barracks Road to Angalamman Koil Street (Chainage of 75 to 150 m) div -73, Zone -6",Own Sources,6,2015-16,2016-17 BR/2015-16/33677,Roads,Completed,BR-Bus Route Roads,73,980000,"Widening of Existing road at strahans road from perambur barracks Road to Angalamman Koil street (Chainage of 0 m to 75 M ) div -73, Zone -6",Own Sources,6,2015-16,2016-17 BR/2015-16/33759,Roads,Completed,BR-Bus Route Roads,91,990000,"Restoration of road cut made by CMWSSB @ Kavimani salaiin Div - 91, Zone - 7.",Deposit Works,7,2015-16,2016-17 BR/2015-16/33871,Roads,Completed,BR-Bus Route Roads,91,952000,"Restoration of road cut made by CMWSSB @ Mugappair eri scheme 6th main road (from jn of kavi mani salai chainage of 0 to 230 M) in div - 91, zone 7",Deposit Works,7,2015-16,2016-17 BR/2015-16/33906,Roads,Completed,BR-Bus Route Roads,91,950000,"Restoration of road cut made by CMWSSB @ Mugappair eri scheme 6th main road (from jn of kavi mani salai chainage of 230 M to 460 M) in div - 91, zone 7",Deposit Works,7,2015-16,2016-17 BR/2015-16/33907,Roads,Completed,BR-Bus Route Roads,91,948000,"Restoration of road cut made by CMWSSB @ Mugappair eri scheme 6th main road (from jn of Church road chainage of 0 to 230 M ) in div - 91, zone 7",Deposit Works,7,2015-16,2016-17 BR/2015-16/33908,Roads,Completed,BR-Bus Route Roads,87,946000,"Restoration of road cut made by CMWSSB @ Mugappair eri scheme 6th main road (from jn of Church road chainage of 230 to 460 M ) in div - 91, zone 7",Deposit Works,7,2015-16,2016-17 BR/2015-16/3391,Roads,Completed,BR-Bus Route Roads,174,3460000,"Construction of Compound wall in front of Madras Race Club at Race Course Road Div - 174, Z one - 13.",Own Sources,13,2015-16,2016-17 BR/2015-16/34079,Roads,Completed,BR-Bus Route Roads,171,629000,"Attending Road cut restoration done by SERVICE DEPARTMENT work at Sardarpatel Road in Dn-171, 173 & 175 Zone-XIII",Deposit Works,13,2015-16,2016-17 BR/2015-16/34501,Roads,Completed,BR-Bus Route Roads,175,970000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Gandhi Nagar 2nd Cross Street from Junction of B Ramachandra Adithanar Road to Junction of Gandhi Nagar 3rd Main Road (Mini Bus Route Road) in Dn-175, Zone-XIII",Own Sources,13,2015-16,2016-17 BR/2015-16/34506,Roads,Completed,BR-Bus Route Roads,175,970000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Gandhi Nagar 2nd Cross Street from Junction of Gandhi Nagar 3rd Main Road to Junction of Gandhi Nagar 2nd Main Road (Mini Bus Route Road) in Dn-175, Zone-XIII",Grants,13,2015-16,2016-17 BR/2015-16/34508,Roads,Completed,BR-Bus Route Roads,175,970000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 at Gandhi Nagar 2nd Cross Street from Junction of Gandhi Nagar 2nd Main Road to Junction of Gandhi Nagar 1st Main Road (Mini Bus Route Road) in Dn-175, Zone-XIII",Grants,13,2015-16,2016-17 BR/2015-16/34513,Roads,Completed,BR-Bus Route Roads,35,310000,"Providing Traffic Improvement work at Manali Salai (from Tondiarpet High Road to Kurukpet Fire Station) DIV 35,ZONE-4.",Own Sources,4,2015-16,2017-18 BR/2015-16/34514,Roads,Completed,BR-Bus Route Roads,36,410000,"Providing Traffic Improvement work at Sidco main road from Jn of Meenambal salai to jn of Tondiarpet high road DIV 36,ZONE-4.",Own Sources,4,2015-16,2017-18 BR/2015-16/34515,Roads,Completed,BR-Bus Route Roads,45,245000,"Providing Traffic Improvement work at AA road (from Stephenson road to BSNL telephone Quarters) in DIV 45,ZONE-4.",Own Sources,4,2015-16,2017-18 BR/2015-16/34516,Roads,Completed,BR-Bus Route Roads,44,995000,"Providing Traffic Improvement work at Melapatti ponnapan street (from Stephenson lane to Subash chandra bose street) in DIV 44 & 45,ZONE-4.",Own Sources,4,2015-16,2017-18 BR/2015-16/34517,Roads,Completed,BR-Bus Route Roads,34,510000,"Providing Traffic Improvement work at Thiruvallavar salai (from jn Muthamizh nagar 5 th main road to Kamaraj salai jn ) in DIV 34,ZONE-4.",Own Sources,4,2015-16,2017-18 BR/2015-16/34518,Roads,Completed,BR-Bus Route Roads,38,800000,"Providing Traffic Improvement work at Ennore high road (from jn of Kathivakkam high road to Jn Vaidhyanathan bridge) in DIV 38,ZONE-4.",Own Sources,4,2015-16,2018-19 BR/2015-16/34521,Roads,Completed,BR-Bus Route Roads,67,240000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT GKM COLONY 17TH STREET (FROM JAMBULINGAM MAIN ROAD TO VENGATESAN STREET ) DIV 67,ZONE- 6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34522,Roads,Completed,BR-Bus Route Roads,65,480000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT KOLATHUR RED HILLS ROAD (FROM POOMBUHAR NAGAR MAIN ROAD TO PAPER MILLS ROAD) DIV 65, ZONE-6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34523,Roads,Completed,BR-Bus Route Roads,78,193000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT LAKSHMI AMMAN KOIL STREET( FROM MADAVARM HIGH ROAD TO MELPATTI PONNAPAN STREET) DIV 78,ZONE- 6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34524,Roads,Completed,BR-Bus Route Roads,78,353000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT ELEPHANT GATE BRIDGE ROAD ( FROM WALTAX ROAD TO DEMOLLOWS ROAD DIV 78,ZONE-6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34525,Roads,Completed,BR-Bus Route Roads,73,625000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT STEPHENSON ROAD (FROM COOKS ROAD TO AMBEDKAR COLLAGE ROAD) DIV 73,ZONE- 6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34526,Roads,Completed,BR-Bus Route Roads,73,596000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT COOKS ROAD ( FROM STEPHENSON ROAD TO K.H ROAD) DIV. 73,ZONE- 6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34527,Roads,Completed,BR-Bus Route Roads,72,613000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT BASIN POWER HOUSE ROAD (FROM E.H ROAD TO PULLIANTHOPE HIGH ROAD) DIV.72, ZONE-6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34528,Roads,Completed,BR-Bus Route Roads,75,574000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT BRICKLIN ROAD (FROM VENKATAMMAL SAMATHI STREET TO STRAHANS ROAD) DIV.75,ZONE- 6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34529,Roads,Completed,BR-Bus Route Roads,64,750000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT KOLATHUR MAIN ROAD ( PUMPUHAR NAGAR MAIN ROAD TO RAILWAY TRACK ) DIV.64,ZONE- 6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34530,Roads,Completed,BR-Bus Route Roads,68,835000,"Providing Traffic Improvement work at Pallavan salai (from Jn of Madhavaram high road to Jn of SRP koil street north) DIV 68,ZONE-6",Own Sources,6,2015-16,2016-17 BR/2015-16/34532,Roads,Completed,BR-Bus Route Roads,70,840000,"Providing Traffic Improvement work at Madhavaram high road (from Jn of Lakshmi amman koil street to Perambur High road North) DIV 70,ZONE-6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34533,Roads,Completed,BR-Bus Route Roads,132,840000,"Providing Traffic Improvement work at Madhavaram high road (from jn of GNT road to Lakshmiamman koil street) DIV 33,ZONE-3.",Own Sources,10,2015-16,2016-17 BR/2015-16/34535,Roads,Completed,BR-Bus Route Roads,60,555000,"Providing Traffic Improvement work at Flag Staff road (from War memorial to Jn of Muthusamy salai) DIV 60,ZONE-5.",Own Sources,5,2015-16,2017-18 BR/2015-16/34536,Roads,Completed,BR-Bus Route Roads,60,725000,"Providing Traffic Improvement work at Arunachalam street (from jn of Pantheon road to Deputy mayor kabalamoorthy salai) DIV 60,ZONE-5",Own Sources,5,2015-16,2017-18 BR/2015-16/34537,Roads,Completed,BR-Bus Route Roads,61,375000,"Providing Traffic Improvement work at Dr Nair Bridge road (from Poonamalee high road to jn of Gandhi irwin road) DIV 61,ZONE-5.",Own Sources,5,2015-16,2017-18 BR/2015-16/34538,Roads,Completed,BR-Bus Route Roads,59,430000,"Providing Traffic Improvement work at Evening bazaar road (from jn Poonamalee high road to jn of Frazer bridge road) DIV 59,ZONE-5",Own Sources,5,2015-16,2017-18 BR/2015-16/34539,Roads,Completed,BR-Bus Route Roads,55,740000,"Providing Traffic Improvement work at old jail road (from Mint bridge to jn of prakasam sali ) DIV 55,ZONE-5.",Own Sources,5,2015-16,2017-18 BR/2015-16/34540,Roads,Completed,BR-Bus Route Roads,56,410000,"Providing Traffic Improvement work at Muthusamy salai (from Jn of Ponnamalee high road to Jn of North fort road) DIV 56,ZONE-5",Own Sources,5,2015-16,2017-18 BR/2015-16/34541,Roads,Completed,BR-Bus Route Roads,49,625000,"Providing Traffic Improvement work at Pan Rajarathinam salai (from Jn of Kummalamman koil street to jn of West kamandabam road) DIV 49,ZONE-5",Own Sources,5,2015-16,2017-18 BR/2015-16/34542,Roads,Completed,BR-Bus Route Roads,132,545000,"Providing Traffic Improvement work at Jambulingam main road From junction of (from Kailaivanar street to Jn of Kolathur main road) DIV 65,ZONE-6",Own Sources,10,2015-16,2017-18 BR/2015-16/34543,Roads,Completed,BR-Bus Route Roads,73,917000,"PROVIDING TRAFFIC IMPROVEMENT WORK AT STRAHANS ROAD ( FROM PERAMBUR BARRACKS ROAD TO K.H ROAD) DIV.73&76,ZONE-6.",Own Sources,6,2015-16,2017-18 BR/2015-16/34545,Roads,Completed,BR-Bus Route Roads,39,220000,"Providing traffic Improvement work at North Terminus road From SN chetty Street to Thiruvottriyur High Road DIV.39,ZONE-4.",Own Sources,4,2015-16,2017-18 BR/2015-16/34546,Roads,Completed,BR-Bus Route Roads,35,950000,"Providing Traffic Improvement at Kamaraj Salai From M.HRoad toThiruvalluvar salai ,Ward -35 ,Zone -4",Own Sources,4,2015-16,2017-18 BR/2015-16/34548,Roads,Completed,BR-Bus Route Roads,56,550000,"Providing traffic improvement at Prakasam Salai From Oldjail Road to Amman Koil Street in Ward -56 ,Zone -5",Own Sources,5,2015-16,2017-18 BR/2015-16/34549,Roads,Completed,BR-Bus Route Roads,58,227000,Providing traffic improvement at Allikulam Link Road (People Park Road ) From Rajamuthiah Salai to Ponnamalle Hig Road),Own Sources,5,2015-16,2017-18 BR/2015-16/34550,Roads,Completed,BR-Bus Route Roads,66,227000,"Providing traffic improvements at Venkatraman salai from Karthigeyan Salai to jaganathan Salai ,ward -66,zone -6",Own Sources,6,2015-16,2017-18 BR/2015-16/34551,Roads,Completed,BR-Bus Route Roads,66,512000,"Providing traffic improvements at Jaganathan Salai from Venkatraman Salai to Kandaswamy Salai ,ward -66,zone -6",Own Sources,6,2015-16,2017-18 BR/2015-16/34552,Roads,Completed,BR-Bus Route Roads,66,174000,"Providing traffic improvements at Balasubramaniam Salai ,ward -66,zone -6",Own Sources,6,2015-16,2017-18 BR/2015-16/34553,Roads,Completed,BR-Bus Route Roads,76,353000,"Providing traffic improvements at Barracks Gate Road and Konnur High Road ,ward -76 &70 ,zone -6",Own Sources,6,2015-16,2017-18 BR/2015-16/34554,Roads,Completed,BR-Bus Route Roads,70,419000,"Providing traffic improvements at Perambur High Road (Service Road ) from Perambur High Road to Subway ,ward -70,zone -6",Own Sources,6,2015-16,2017-18 BR/2015-16/34555,Roads,Completed,BR-Bus Route Roads,70,300000,"Providing traffic improvements at Perambur Tank Link Road from M.H Road to Paper MIlls Road ,ward -70,zone -6",Own Sources,6,2015-16,2016-17 BR/2015-16/34556,Roads,Completed,BR-Bus Route Roads,70,320000,"Providing traffic improvements at Perambur Tank Street from Paper Mills Road To Perambur High Road( North),ward -70 ,zone -6",Own Sources,6,2015-16,2017-18 BR/2015-16/34654,Roads,Completed,BR-Bus Route Roads,177,860000,"PROVIDING TRAFFIC IMPROVEMENT TO KATHIPARA ROAD IN DIV 177 ,ZONE-13.",Own Sources,13,2015-16,2017-18 BR/2015-16/34655,Roads,Completed,BR-Bus Route Roads,177,920000,"PROVIDING TRAFFIC IMPROVEMENT TO CITY LINK ROAD IN DIV 177 ,ZONE-13.",Own Sources,13,2015-16,2017-18 BR/2015-16/34656,Roads,Completed,BR-Bus Route Roads,177,348000,"PROVIDING TRAFFIC IMPROVEMENT TO BESENT NAGAR 2 ND AVENUE IN DIV 177 ,ZONE-13.",Own Sources,13,2015-16,2017-18 BR/2015-16/3715,Footpath,Completed,BR-Bus Route Roads,71,2355000,"Removing existing kerb and forming centre median with Mass RMC Concrete and Stainless steel pipe at Madavakkam Tank Road from Ayanavaram Road to Konnur High Road in Dn-74,Zone-VI",Own Sources,6,2015-16,2016-17 BR/2015-16/3892,Roads,Completed,BR-Bus Route Roads,115,4684000,"Construction of 5 Nos Modern Stainless Steel Bus Shelter at 1.Pasumpon Muthuramalingam Salai towards Mandaiveli, 2 & 3. R.A.Puram 2nd Main Road towards Mandaveli and towards Nandanam, 4. R.A.Puram 3rd Main Road towards Adyar & 5. TTK Road, Adyar Gate Hotel, toeards Luz Church Road in Dn-115, Zone-9",MPLADS,9,2015-16,2016-17 BR/2015-16/3903,Roads,Completed,BR-Bus Route Roads,115,4090000,"Construction of 4 Nos of Modern Stainless Steel Bus Shelter at 1.St.Marys Road towards Mandaveli 2. Rosary Church Road towards Luz 3.TVK Salai @ PS Sivasamy Salai towards Luz 4. Musuri Subramaniam Salai towards Luz in Dn-115, Zone-9",MPLADS,9,2015-16,2016-17 BR/2015-16/4249,Footpath,Completed,BR-Bus Route Roads,110,2326000,"Removing existing kerb and forming centre median with Mass RMC concrete and stainless steel pipe at Sterling Road from Railway Quarters to Village Road in Div-110,Zone-IX",Own Sources,9,2015-16,2016-17 BR/2015-16/4254,Footpath,Completed,BR-Bus Route Roads,110,2326000,"Removing existing kerb and forming centre median with Mass RMC concrete and stainless steel pipe at Sterling Road from Loyola College junction to Railway Quarters in Div - 110,Zone - IX",Own Sources,9,2015-16,2016-17 BR/2015-16/4258,Footpath,Completed,BR-Bus Route Roads,109,2498000,"Removing existing kerb and forming centre median with Mass RMC concrete and stainless steel pipe at Nelson Manikkam Road from Choolaimedu to Metha Nagar in Division-109,Zone-IX",Own Sources,9,2015-16,2016-17 BR/2015-16/4319,Roads,Completed,BR-Bus Route Roads,140,1970000,"Proposed Construction of Modern Stainless Steel Bus Shelters at Reddy Kuppam Road (Near Aranganathan Subway) of size 9 x 2.5 and Mosque Street (Near Mosque) of size 6 x 2.5 in Dn-140 & 142, Zone-10 under MLA Scheme Work",MPLADS,10,2015-16,2016-17 BR/2015-16/4472,Roads,Completed,BR-Bus Route Roads,113,2498000,"Removing existing kerb and forming centre median with Mass RMC concrete and stainless steel pipe at Village Road from Valluvar kottam junction to Tank Bund Road (Independence day park ) in Div- 113, Zone - IX. Length- 465m",Own Sources,9,2015-16,2016-17 BR/2015-16/4473,Roads,Completed,BR-Bus Route Roads,113,2498000,"Removing existing kerb and forming centre median with Mass RMC concrete and stainless steel pipe at Village Road from Tank Bund Road(Independence day park) to New street junction in Div- 113,Zone - IX. Length - 465m",Own Sources,9,2015-16,2016-17 BR/2015-16/4475,Roads,Completed,BR-Bus Route Roads,110,2191000,"Removing existing kerb and forming centre median with Mass RMC concrete and stainless steel pipe at Village Road from New street junction to Wheatcrafts Road in Div -110,Zone - IX.",Own Sources,9,2015-16,2016-17 BR/2015-16/4480,Roads,Completed,BR-Bus Route Roads,107,2498000,"Removing existing kerb and forming centre median with Mass RMC concrete and stainless steel pipe at Village Road from Wheatcraft Road to Spur tank Road in Div -107, Zone - VIII.",Own Sources,8,2015-16,2016-17 BR/2015-16/4556,Roads,Completed,BR-Bus Route Roads,180,71000000,"Widening, Strengthening and relaying of road, Footpath and construction of Storm water drain at Ramanujam I.T city Road (from Rajiv Gandhi Salai to IIT Research center) in Dn-180, Z-13",Grants,13,2015-16,2016-17 BR/2015-16/4759,Roads,Completed,BR-Bus Route Roads,117,1927500,"Proposed Construction of 2 Nos Bus Shelters at Anna Salai DMS (towards Saidapet) in Dn-117, Zone-9 under MLA Scheme",MLACDS,9,2015-16,2016-17 BR/2015-16/5128,Road Cut,Completed,BR-Bus Route Roads,122,1645000,"Restoration of Roadcut made by TANGEDCO at Pasumpon Muthuramalingam Devar Salai in Dn-122, Zone-IX",Deposit Works,9,2015-16,2016-17 BR/2015-16/5140,Road Cut,Completed,BR-Bus Route Roads,111,2500000,"Restoration of Roadcut made by TANGEDCO at Whites Road in Dn-111, Zone-9",Deposit Works,9,2015-16,2016-17 BR/2015-16/5162,Roads,Completed,BR-Bus Route Roads,114,1057000,"Proposed Construction of 1No Bus Shelters at Bells Road in Dn-114, Zone-9 under MP Scheme",MPLADS,9,2015-16,2017-18 BR/2015-16/5527,Footpath,Completed,BR-Bus Route Roads,136,990000,"Attending Footpath repair Works at Thyagaraya Road (North Side) in Dn-136, Zone-10",Own Sources,10,2015-16,2016-17 BR/2015-16/5624,Road Cut,Completed,BR-Bus Route Roads,110,2226000,"Restoration of Roadcut made by TANGEDCO at Mahalingapuram Main Road in Dn-110, Zone-9",Deposit Works,9,2015-16,2016-17 BR/2015-16/5625,Road Cut,Completed,BR-Bus Route Roads,70,2380000,"Restoration of Roadcut made by TANGEDCO at Dr.Ambedkar College Road in Dn-70, Zone-9",Deposit Works,6,2015-16,2016-17 BR/2015-16/5632,Road Cut,Completed,BR-Bus Route Roads,113,2221000,"Restoration of Roadcut made by TANGEDCO at Haddows Road in Dn-113, Zone-9",Deposit Works,9,2015-16,2016-17 BR/2015-16/5740,Roads,Completed,BR-Bus Route Roads,73,2345000,"Proposed Construction of Crash Barrier type Centre Median at Dr.Ambedkar College Road (From the jn of Perambur Barracks Road to the jn of Stephenson Road) in Dn-73, Zone-6",Own Sources,6,2015-16,2016-17 BR/2015-16/5864,Roads,Completed,BR-Bus Route Roads,N08,995000,"REMOVING THE EXISTING BANNERS FROM THE MODERN STAINLESS STEEL BUS SHELTERS AND FIXING THE NEW BANNERS WITH GOVERNMENT SCHEMES IN ZONE - 6,7,8",Own Sources,,2015-16,2016-17 BR/2015-16/5865,Roads,Completed,BR-Bus Route Roads,N09,995000,"REMOVING THE EXISTING BANNERS FROM THE MODERN STAINLESS STEEL BUS SHELTERS AND FIXING THE NEW BANNERS WITH GOVERNMENT SCHEMES IN ZONE - 9",Own Sources,,2015-16,2016-17 BR/2015-16/5866,Roads,Completed,BR-Bus Route Roads,N09,983000,"REMOVING THE EXISTING FACIA FROM THE MODERN STAINLESS STEEL BUS SHELTERS AND FIXING THE NEW FACIA WITH GOVERNMENT SCHEMES IN ZONE - 9",Own Sources,,2015-16,2016-17 BR/2015-16/5933,Roads,Completed,BR-Bus Route Roads,N06,983000,"REMOVING THE EXISTING FACIA FROM THE MODERN STAINLESS STEEL BUS SHELTERS AND FIXING THE NEW FACIA WITH GOVERNMENT SCHEMES IN ZONE - 6 & 7",Own Sources,,2015-16,2016-17 BR/2015-16/5934,Roads,Completed,BR-Bus Route Roads,N08,983000,"REMOVING THE EXISTING FACIA FROM THE MODERN STAINLESS STEEL BUS SHELTERS AND FIXING THE NEW FACIA WITH GOVERNMENT SCHEMES IN ZONE - 8 & 10",Own Sources,,2015-16,2016-17 BR/2015-16/5936,Roads,Completed,BR-Bus Route Roads,N09,920000,Proposed Renovation & Rectification of Electrical Fittings in the existing Modern Bus Shelters in Zone-9,Own Sources,,2015-16,2016-17 BR/2015-16/6279,Roads,Completed,BR-Bus Route Roads,134,1297000,Road cut restoration at Rangarajapuram Main Road,Deposit Works,10,2015-16,2016-17 BR/2015-16/6283,Roads,Completed,BR-Bus Route Roads,137,2836000,Road cut restoration at Ramapuram Main Road,Deposit Works,10,2015-16,2016-17 BR/2015-16/6284,Roads,Completed,BR-Bus Route Roads,137,1774000,Road cut restoration at Erikarai Salai,Deposit Works,10,2015-16,2016-17 BR/2015-16/6478,Road Cut,Completed,BR-Bus Route Roads,127,2619000,"Restoration of Road Cut made by PWD at Kaliamman Koil Street (Chainage 100m) in Dn-127, Zone-10",Deposit Works,10,2015-16,2016-17 BR/2015-16/6536,Roads,Completed,BR-Bus Route Roads,65,4180000,"Proposed construction of 5 nos of Modern stainless steel Bus shelters at Paper mills Road(1)Junction of Siva Elango Road and 70 feet Road (2)80 feet Road junction of Balaji Nagar and Kumaran Nagar(North)(3)Karthikeyan salai(2 nos) (4)Jawaharlal Nehru salai (Senthil Nagar Bus Stop) in Dn-65,66,Zone-6.",Own Sources,6,2015-16,2016-17 BR/2015-16/6537,Roads,Completed,BR-Bus Route Roads,65,4175000,"Proposed construction of 5 nos of Modern stainless steel Bus shelters at Jawaharlal Nehru salai (1) Junction of Retteri signal(2) Jawaharlal Nehru salai (Vivekananda Nagar main Road junction ( 2 nos)(3) Paper mills Road (near K1 police station)(4) Dr.Ambedkar College Road (Near Slaughter house) in Dn-65,69,72,Zone-VI.",Own Sources,6,2015-16,2016-17 BR/2015-16/6575,Roads,Completed,BR-Bus Route Roads,116,920000,"Proposed Renovation & Rectification of Electrical Fitting in existing Modern Bus Shelter in Zone 6,7,8,9 & 10.",Own Sources,9,2015-16,2016-17 BR/2015-16/6620,Roads,Completed,BR-Bus Route Roads,172,2649000,Road cut restoration at West Canal Bank Road,Deposit Works,13,2015-16,2016-17 BR/2015-16/6958,Road Cut,Completed,BR-Bus Route Roads,127,2820000,"Restoration of Roadcut made by PWD at Kaliamman Koil Street from the Jn of 100 Feet Road to CMBT Entrance in Dn-127, Zone-10",Deposit Works,10,2015-16,2017-18 BR/2015-16/6971,Road Cut,Completed,BR-Bus Route Roads,137,28230000,Forming Link Road Connecting from Anna Main Road to Lake View Road at Nesapakkam including Strom Water Drain and Footpath in Ward 137 Zone 10,Grants,10,2015-16,2017-18 BR/2015-16/7569,Roads,Completed,BR-Bus Route Roads,100,3700000,"Proposed Construction of Granite Kerb Centre Median with SS Pipe Grill at Anna Nagar 3rd Avenue from the jn of Anna Nagar 2nd Avenue to Otteri Nallah in Dn-100, Zone-8",Own Sources,8,2015-16,2016-17 BR/2015-16/7572,Roads,Completed,BR-Bus Route Roads,101,960000,"Fixing of SS Grill over the Granite Kerb at Anna Nagar 3rd Avenue from the jn of Anna Nagar 5th Main Road to Anna Nagar 2nd Avenue in Dn-101, Zone-8",Own Sources,8,2015-16,2017-18 BR/2015-16/7574,Roads,Completed,BR-Bus Route Roads,101,1440000,"Supplying and Fixing of SS Grill over the Granite Kerb at Anna Nagar 3rd Avenue from the jn of Anna Nagar 6th Avenue to the Jn of Anna Nagar 5th Main Road in Dn-101, Zone-8",Own Sources,8,2015-16,2017-18 BR/2015-16/7828,Road Cut,Completed,BR-Bus Route Roads,175,791000,"Restoration of Roadcut at Indira Nagar 2nd Avenue Road by CMWSSB in Div 175, Zone - 13",Deposit Works,13,2015-16,2017-18 BR/2015-16/7831,Road Cut,Completed,BR-Bus Route Roads,177,1581000,"Restoration of Roadcut at Andal Nagar 3rd Main Road Colony by TNEB in Div 177, Zone - 13",Deposit Works,13,2015-16,2017-18 BR/2015-16/7897,Roads,Completed,BR-Bus Route Roads,101,2490000,"Proposed Construction of Traffic Island at the junction of 6th Avenue X 3rd Avenue (Near K4 Police Station) in Dn-101, Zone-8",Deposit Works,8,2015-16,2016-17 BR/2015-16/7954,Roads,Completed,BR-Bus Route Roads,145,1940000,"PROVISION OF SIMPLY SUPPORTED OVER HEAD GANTRY SIGN BOARDS AT SARDHAR PATEL ROAD, AIRPORT(18/7) IN VARIOUS ZONE.",Own Sources,11,2015-16,2016-17 BR/2015-16/8044,Roads,Completed,BR-Bus Route Roads,73,565000,"Attending Patch Work at Otteri Bridge Portion in Division-73, Zone 6",Own Sources,6,2015-16,2016-17 BR/2015-16/8047,Roads,Completed,BR-Bus Route Roads,73,748000,"Attending Patch Work at Bricklin Road, Strahans Road and Medavakkam Tank Road in Division 73, 74 and 75 in Zone 6",Own Sources,6,2015-16,2016-17 BR/2015-16/8115,Roads,Completed,BR-Bus Route Roads,63,930000,Repair and Maintenance of Existing Bus Shelters at Various roads in Zone -IV&V,Own Sources,5,2015-16,2016-17 BR/2015-16/8621,Roads,Completed,BR-Bus Route Roads,113,854500,"Proposed Construction of 1No Bus Shelters at North Usman Road in Dn-113, Zone-9 Under MLA Scheme Work",MPLADS,9,2015-16,2016-17 BR/2015-16/8648,Roads,Completed,BR-Bus Route Roads,117,937000,"Attending Emergency Patch Work at Dr.B.V.Narasimman Salai from the jn of Thyagaraya Road to jn of Vijayaragava Road in Dn-117, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/8649,Roads,Completed,BR-Bus Route Roads,117,937000,"Attending Emergency Patch Work at Dr.B.V.Narasimman Salai jn of Vijayaragava Road in Dn-117, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/8651,Roads,Completed,BR-Bus Route Roads,117,945000,"Attending Emergency Patch Work at Dr.B.V.Narasimman Salai from the jn of Vijayaragava Road to jn of G.N.Chetty Road in Dn-117, Zone-9",Own Sources,9,2015-16,2016-17 BR/2015-16/8971,Roads,Completed,BR-Bus Route Roads,116,831000,"Proposed Construction of 1No Bus Shelters at Pycrofts Road in Dn-113, Zone-9 Under MP Scheme Work",MPLADS,9,2015-16,2017-18 BR/2015-16/9071,Roads,Completed,BR-Bus Route Roads,100,820000,"SUPPLYING AND FIXING OF SS PIPE GRILL OVER THE EXISTING CENTRE MEDIAN AT ANNA NAGAR 3RD AVENUE FROM THE JN OF K3 POLICE STATION TO ANNA ARCH IN DN-100,ZONE-8.",Own Sources,8,2015-16,2017-18 BR/2015-16/9180,Storm Water Drain,Completed,BR-Bus Route Roads,129,996000,"Attending Patch Work at NSK Salai in Dn-129, Zone-10 (Centre Median North Side) (From Alwar Thirunagar Jn to Vembuliammam Koil Jn)",Own Sources,10,2015-16,2016-17 BR/2015-16/9306,Roads,Completed,BR-Bus Route Roads,37,4237000,"Providing Crash Barrier Type Centre Median at Tondairpet High Road (From TVK Link Road to Kannadasan Nagar 10th Main Road) in Dn-37, Zone-4",Own Sources,4,2015-16,2017-18 BR/2015-16/9308,Roads,Completed,BR-Bus Route Roads,37,4237000,"Providing Crash Barrier Type Centre Median at Tondairpet High Road (From Kannadasan Nagar 10th Main Road to Meenambal Salai) in Dn-37, Zone-4",Own Sources,4,2015-16,2017-18 BR/2015-16/9572,Road Cut,Completed,BR-Bus Route Roads,127,3929000,"Restoration of Road Cut made by PWD at Kaliamman Koil Street (Chainage 100m to 250m) in Dn-127, Zone-10",Deposit Works,10,2015-16,2016-17 D/2015-16/13159,Storm Water Drain,Completed,D-Storm Water Drains,40,7769000,"Preventive measures to Mosquito menace- Removal of floating materials / Hyacinth etc., along North ?B? Canal from Cooum North Arm to Captain Cotton Canal Jn for a period of 12 months which includes removal of hyacinth and floating materials, using float platform and poclain machineries and carting and disposal of the hyacinth and floating materials to the dumping ground using vehicles",Own Sources,4,2015-16,2018-19 D/2015-16/13164,Storm Water Drain,Completed,D-Storm Water Drains,41,9640000,Proposed desilting work using poclain and float platform in link canal in Dn-41 Zone- IV,Own Sources,4,2015-16,2016-17 D/2015-16/13306,Storm Water Drain,Completed,D-Storm Water Drains,192,18800000,Construction of storm water Drain of size 1200x1200mm alongPandiyan salai From ECR To South B canal Neelakarai in Div- 192 Zone- XV,Own Sources,15,2015-16,2017-18 D/2015-16/13332,Storm Water Drain,Completed,D-Storm Water Drains,192,9143000,Construction of storm water Drain of size 600x750mm Along Kumaraguru Avenue main road and 8th cross street From Kumarakuru avenue main road to Pandiyan salai Neelakarai in Div 192 Zone -XV,Own Sources,15,2015-16,2016-17 D/2015-16/13467,Storm Water Drain,Completed,D-Storm Water Drains,192,10375000,: Construction of storm water Drain of size 900x900mm Along Saraswthi nagar south and Aringnar Anna nagar 4th street From Vaithiyalingam salal to South B CanalDiv 192 Zone-XV,Own Sources,15,2015-16,2018-19 D/2015-16/13513,Storm Water Drain,Completed,D-Storm Water Drains,192,8685000,Construction of storm water Drain of size 600x750mm Along Saraswathi nagar south From Dead end to Aringnar anna nagar 4th street.Neelangarai in DIV 192 Zone XV .,Own Sources,15,2015-16,2016-17 D/2015-16/13515,Storm Water Drain,Completed,D-Storm Water Drains,193,9020000,Construction of storm water Drain of size 900x900mm along 1st and 2nd Main road of karpaka vinayagar sreeet From Poompukar street to South B Canal in Div 193 Zone XV,Own Sources,15,2015-16,2016-17 D/2015-16/13516,Storm Water Drain,Completed,D-Storm Water Drains,196,7285000,Construction of storm water Drain of size 900x900mm along 4th cross street 1st avenue 1st main road and poompukar street From dead end of 4th cross street to karpakavinayaga 1st main road in Div 196 Zone XV,Own Sources,15,2015-16,2016-17 D/2015-16/1405,Storm Water Drain,Completed,D-Storm Water Drains,1,6586000,"Desilting of Thamarai Kulam including removal of obstruction weeds, hyacynth and other floating materials using poclain, special type of float platform in Dn-01, Zone -I",Own Sources,1,2015-16,2016-17 D/2015-16/14137,Storm Water Drain,Completed,D-Storm Water Drains,41,998000,"Preventive measures of mosquito menace- Removal of Hyacinth/floating materials in waterways at North B canal (Reach-2) from Lime kiln road bridge to IOC foot Bridge in Dn-41, Zone IV.h )to prevent mosquito menace at this place.",Own Sources,4,2015-16,2016-17 D/2015-16/14147,Storm Water Drain,Completed,D-Storm Water Drains,41,976000,"Preventive measures of mosquito menace- Removal of Hyacinth/floating materials in waterways at North B canal (Reach-1) from Stanley nagar to Lime kiln road bridge in Dn-41, Zone IV.",Own Sources,4,2015-16,2016-17 D/2015-16/14272,Storm Water Drain,Completed,D-Storm Water Drains,41,44050000,"Providing Resectioning,Concrete lining and Laying Service Road in Link Canal from Ch. 2940.0 to 3360.0 in captain Cotton Canal in Dn.41 Zone IV.",JNNURM,4,2015-16,2017-18 D/2015-16/14274,Storm Water Drain,Completed,D-Storm Water Drains,34,99270000,Construction of RCC Open Box Type Retaining Wall and Bed including chain link Fencing to Kodungaiyur Canal North Wing from Ch 0.0 m to 850.0 M in Dn-34 Zone-IV.,JNNURM,4,2015-16,2017-18 D/2015-16/14276,Storm Water Drain,Completed,D-Storm Water Drains,34,35900000,Construction of RCC Open Box Type Retaining Wall and Bed including chain link Fencing to Kodungaiyur Canal North Wing from Ch 850.0 to Ch.1150 in Dn-34 Zone-IV.,JNNURM,4,2015-16,2018-19 D/2015-16/14279,Storm Water Drain,Completed,D-Storm Water Drains,41,58390000,Providing Resectioning and Concrete lining and Service Road to Link Canal (from Ch 2500.0 to Ch 2940.0) in Division 41 Zone IV,JNNURM,4,2015-16,2017-18 D/2015-16/14387,Storm Water Drain,Completed,D-Storm Water Drains,34,82470000,Construction of RCC Open Box Type Retaining Wall and Bed including chain link Fencing to Kodungayur Main Canal from Ch.1675 to Ch.2191.0 M in Dn-34 Zone-IV.,JNNURM,4,2015-16,2017-18 D/2015-16/17871,Storm Water Drain,Completed,D-Storm Water Drains,177,817000,"Providing Rain water Harvesting structure by using precast well ring at Jenis Street and Ganesh Nagar, 2nd street (DN-142 & 177) in Zone-10 and Zone-13",Own Sources,13,2015-16,2016-17 D/2015-16/17990,Storm Water Drain,Completed,D-Storm Water Drains,130,805000,"Desilting the pallikaranai marsh land area (south side and north side) for free flow of flood water along Pallavaram Radial Road from Kamachi hospital to Perungudi dumping yard in Dn-189, Zone-XIV",Own Sources,10,2015-16,2016-17 D/2015-16/18439,Storm Water Drain,Completed,D-Storm Water Drains,40,16800000,"Dismantling and Re-Construction of RCC Box Type Storm Water Drain of size 1200 x 1200mm along Kamarajar Salai from Elaya Street to A.E. Koil Street in Dn-40, Zone-IV.",JNNURM,4,2015-16,2017-18 D/2015-16/18441,Storm Water Drain,Completed,D-Storm Water Drains,39,26361000,"Dismantling and Re-Construction of RCC Box Type Storm Water Drain of size 1200 x 1200mm along T.H.Road from North Terminal Road to A.E. Koil Street in Dn-39, Zone-IV.",JNNURM,4,2015-16,2016-17 D/2015-16/20990,Storm Water Drain,Completed,D-Storm Water Drains,95,8577000,"Dismantling of the flood damaged Storm water drain and adition improvement in existing storm water drain of size 900 X 900 mm along Anna nagar 18th main road (Northern side) from 100ft road to Ch-425 m (Reach-I)in Dn-95,Zone-VIII.",Own Sources,8,2015-16,2017-18 D/2015-16/21043,Storm Water Drain,Completed,D-Storm Water Drains,95,8577000,"Dismantling of the flood damaged Storm water drain and adition improvement in existing storm water drain of size 900 X 900 mm along Anna nagar 18th main road (Northern side) from Ch-425 m to Vasantham Colony 2nd street (Reach-2) in Dn-95,Zone-VIII..",Own Sources,8,2015-16,2016-17 D/2015-16/21088,Storm Water Drain,Completed,D-Storm Water Drains,95,9032000,"Dismantling of the flood damaged Storm water drain and addition Improvement in existing Storm water drain of size 900 X 900 mm along Anna nagar 18th main road(Southern side) from 100ft road to Ch-500m (Reach-I)in Dn-95, Zone-VIII.",Own Sources,8,2015-16,2016-17 D/2015-16/21095,Storm Water Drain,Completed,D-Storm Water Drains,95,9032000,"Dismantling of the flood damaged Storm water drain and addition Improvement in existing Storm water drain of size 900 X 900 mm along Anna nagar 18th main road(Southern side) from Ch-500m to Otteri Nullah Canal (Reach-2) in Dn-95, Zone-VIII.",Own Sources,8,2015-16,2016-17 D/2015-16/21465,Storm Water Drain,Completed,D-Storm Water Drains,189,905000,"Desilting the pallikaranai marsh land area (South part) for free flow of flood water from pallavaram 200ft radial road (kamachi hospital to perungudi dumping yard) (Culvert- 1 to 10) in dn 189, Zone - XIV.",Own Sources,14,2015-16,2016-17 D/2015-16/23402,Storm Water Drain,Completed,D-Storm Water Drains,99,990000,"NAME OF WORK : Desilting of Ottari Nulah canal including removal of obstruction fallen tree, hyacynth and other floating materials using poclain,special type of float platform in Dn 99, Zone -VIII.",Own Sources,8,2015-16,2016-17 D/2015-16/23796,Storm Water Drain,Completed,D-Storm Water Drains,103,20080000,"Dismantling of existing Storm water drain of size 900x900mm and Re-Construction of RCC Box type SWD of size 1200 X 1200 mm along Purasawalkam High road(Northern side) from Kellys corner to Brick kiln road in Dn-103 & 104, Zone-VIII.",Own Sources,8,2015-16,2017-18 D/2015-16/2434,Storm Water Drain,Completed,D-Storm Water Drains,10,10336000,"Construction of RCC Box type SWD of size 900 x 900mm along Kamarajar Nagar Main Road from Government Higher Secondary School to Road Culvert near Railway Subway in Dn-01, Zone-I.",JNNURM,1,2015-16,2016-17 D/2015-16/2436,Storm Water Drain,Completed,D-Storm Water Drains,N01,10336000,"Construction of RCC Box type SWD of size 900 x 900mm along SVM Nagar 1st Main Road from SVM Nagar 1st Street to Ulaganathapuram Main Road in Dn-01, Zone-I.",JNNURM,,2015-16,2016-17 D/2015-16/2439,Storm Water Drain,Completed,D-Storm Water Drains,N01,16096000,"Construction of RCC Box type SWD of size 900 x 900mm along SVM Nagar 2nd Main Road & Ulaganathapuram Main Road from SVM Nagar 1st Street to Thazankuppam Main Road (near Culvert) in Dn-01, Zone-I.",JNNURM,,2015-16,2016-17 D/2015-16/24562,Storm Water Drain,Completed,D-Storm Water Drains,171,66020000,"Construction of storm water drain of size 1500x1500mm along HRS Campus Anna University Campus from Rajbhavan, Sardar Patel Road to Adyar River in Dn.171, Zone XIII",Own Sources,13,2015-16,2017-18 D/2015-16/24576,Storm Water Drain,Completed,D-Storm Water Drains,171,25840000,"Construction of storm water drain of size 1200x1200mm along Sardel Patel road from Bhakthavachalam memorial mambalam to Existing storm water drain near Rajbhavan main Gate in Dn.171, Zone XIII",Own Sources,13,2015-16,2017-18 D/2015-16/24938,Storm Water Drain,Completed,D-Storm Water Drains,104,5166000,"Dismantling and Re construction of storm water drain of size 900x900mm RCC box type drain along Flowers road from Poonamallee High road to jn of Barnaby road and Ormes road in Dn-103 & 104,Z-VIII.",Own Sources,8,2015-16,2016-17 D/2015-16/25846,Storm Water Drain,Completed,D-Storm Water Drains,111,4620000,"Name of the work:Construction of Side Protection wall and Erection of Iron Channels and Roof covering with Iron Sheets for Nungambakkam Canal From 1121mts to1171 mts near Rutland Gate 2nd street in Div--111,Zone-IX.",Own Sources,9,2015-16,2018-19 D/2015-16/26056,Storm Water Drain,Completed,D-Storm Water Drains,181,974000,"Construction of Precast Storm Water Drain of size 900mmx900mm along ECR and crossing the LB road from Thiruvalluvar Salai to West Avenue, Thiruvanmaiyur in Dn.181, Zone 13",Own Sources,13,2015-16,2016-17 D/2015-16/26394,Storm Water Drain,Completed,D-Storm Water Drains,36,900000,"NAME OF WORK : Desilting of Vyasarpadi Canal Ch 0 M To 750 M including removal of obstruction fallen tree, hyacynth and other floating materials using poclain,special type of float platform in Dn 36, Zone -IV.",Own Sources,4,2015-16,2016-17 D/2015-16/26437,Storm Water Drain,Completed,D-Storm Water Drains,35,840000,"NAME OF WORK : Desilting of Vyasarpadi Canal Ch 750 M To 1440 M including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn 36, Zone -IV.",Own Sources,4,2015-16,2016-17 D/2015-16/26460,Storm Water Drain,Completed,D-Storm Water Drains,197,977000,"Preventive measures of mosquito menace removal of Hyacinth/floating materials in waterways of De-silting of South B Canal near K.K Salai link Bridge Sholinganallur Dn.197, Zone XV",Own Sources,15,2015-16,2016-17 D/2015-16/26813,Storm Water Drain,Completed,D-Storm Water Drains,94,39088000,"Dismantling and Re-Construction of RCC Box Type Canal of size 3000x3500mm along TVS Canal from Annai sathya nagar Railway Culvert to Annai sathya nagar Padi Flyover Bridge Culvert in Div-94,Zone-VIII.",Own Sources,8,2015-16,2017-18 D/2015-16/27629,Storm Water Drain,Completed,D-Storm Water Drains,142,800000,:Construction of storm water Drain of size 600x600mm along Devanbashayam st fromDevanbashayam st to Kavari st Existing Storm water drain in Dn 142 Zone 10.,Own Sources,10,2015-16,2016-17 D/2015-16/29835,Storm Water Drain,Completed,D-Storm Water Drains,130,960000,"Desilting of Virugambakkam Canal Ch 3500 M To 4100 M including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn 130, Zone -X.",Own Sources,10,2015-16,2016-17 D/2015-16/30592,Storm Water Drain,Completed,D-Storm Water Drains,170,988000,"Preventive measures to Mosquito Menace - Removal floating materials/hyacinth etc., along Adyar River Reach II using float platform and poclain machineries and carting and disposal of the hyacinth and floating materials to the dumping ground using vehicles.",Own Sources,13,2015-16,2016-17 D/2015-16/30655,Storm Water Drain,Completed,D-Storm Water Drains,75,996000,"Name of the work: Preventive measures of mosquito menace- Removal of Hyacinth/floating materials in waterways at Otteri Nullah Canal From Ekangipuram canal To Ch-2500 M And Ekangipuram canal From Chaandra Yogi Samadhi Road To Ch-1100 m in Dn-75 & 71 ,Zone VI.",Own Sources,6,2015-16,2016-17 D/2015-16/30669,Storm Water Drain,Completed,D-Storm Water Drains,113,972000,Preventive measures of mosquito menace- Removal of Hyacinth/floating materials in waterways at Mambalam Canal From Valluvar Kottam (Near Metro Water filling station ) to Adayar River & Nandanam Canal FromAnna salai (Rain tree hotel to Adayar River) & Reddykuppam Canal From Division -140 (Metro water Pumping Station to Mambalam Canal & Trustpuram Canal From Arcot road to Coovum River in Zone IX &XIII.,Own Sources,9,2015-16,2016-17 D/2015-16/30817,Storm Water Drain,Completed,D-Storm Water Drains,195,990000,"Preventive measures to Mosquito Menace - Removal floating materials/hyacinth etc., along South B Canal From Elango nagar to okkiyam maduvu and okkiyam madu to pallikaranai Marsh land Reach II using float platform and poclain machineries and carting and disposal of the hyacinth and floating materials to the dumping ground using vehicles",Own Sources,15,2015-16,2016-17 D/2015-16/30933,Storm Water Drain,Completed,D-Storm Water Drains,72,990000,"Preventive measures of mosquito menace- Removal of Hyacinth/floating materials in waterways at Captain Cotton Canal From MKB Nagar Bridge To Link Canal in Dn-37, Zone IV.",Own Sources,6,2015-16,2016-17 D/2015-16/32088,Storm Water Drain,Completed,D-Storm Water Drains,63,981500,Preventive measures of mosquito menace- Removal of Hyacinth/floating materials in waterways at Cooum River (Reach-I) from Nappier Bridge to Ethiraj college road Bridge in Zone-V.,Own Sources,5,2015-16,2016-17 D/2015-16/32094,Storm Water Drain,Completed,D-Storm Water Drains,107,989700,Preventive measures of mosquito menace- Removal of Hyacinth/floating materials in waterways at Cooum River (Reach-II) from Anna nagar 3rd Avenue Bridge to Ethiraj college road Bridge in Zone-VIII.,Own Sources,8,2015-16,2016-17 D/2015-16/33395,Storm Water Drain,Completed,D-Storm Water Drains,174,976000,"Providing and Fixing the ManHole Door at Velachery main Road & Five Furlong Road, DN-174, in Zone-13.",Own Sources,13,2015-16,2016-17 D/2015-16/33397,Storm Water Drain,Completed,D-Storm Water Drains,177,404000,"Preventive measures to Mosquito Menace - Removal floating materials/hyacinth etc., along Velachery lake-Part using float platform and poclain machineries and carting and disposal of the hyacinth and floating materials to the dumping ground using vehicles.",Own Sources,13,2015-16,2016-17 D/2015-16/33400,Storm Water Drain,Completed,D-Storm Water Drains,181,694000,"Providing and Fixing the ManHole Door and silt catchpit at Besant Nagar 7th Avenue & Shastri Nagar 9th Cross Street, DN-176 & DN-181, in Zone-13.",Own Sources,13,2015-16,2016-17 D/2015-16/34560,Storm Water Drain,Completed,D-Storm Water Drains,130,993600,"Preventive measures to Mosquito Menace - Removal floating materials/hyacinth etc., along Virugambakkam&Arumbakkam using float platform and poclain machineries",Own Sources,10,2015-16,2016-17 D/2015-16/3617,Storm Water Drain,Completed,D-Storm Water Drains,12,894000,Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on BRR Roads in Zone I to III.,Own Sources,1,2015-16,2017-18 D/2015-16/3672,Storm Water Drain,Completed,D-Storm Water Drains,136,6493000,Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on BRR Roads in Zone X.,Own Sources,10,2015-16,2016-17 D/2015-16/3698,Storm Water Drain,Completed,D-Storm Water Drains,92,782000,Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on BRR Roads in Zone- VII & VIII.,Own Sources,7,2015-16,2016-17 D/2015-16/3701,Storm Water Drain,Completed,D-Storm Water Drains,100,3171000,Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on BRR Roads in Zone VIII.,Own Sources,8,2015-16,2016-17 D/2015-16/3702,Storm Water Drain,Completed,D-Storm Water Drains,170,4025000,"Providing Silt Catch pits,Vertical gratings and replacing damaged manhole doors in the existing storm water drain at Bus Route Roads in Zone XIII ( Dn.170 to 171).",Own Sources,13,2015-16,2016-17 D/2015-16/3706,Storm Water Drain,Completed,D-Storm Water Drains,113,5688000,Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on BRR Roads in Zone IX.,Own Sources,9,2015-16,2016-17 D/2015-16/3711,Storm Water Drain,Completed,D-Storm Water Drains,195,2313000,"Providing Silt Catch pits,Vertical gratings and replacing damaged manhole doors in the existing storm water drain at Bus Route Roads in Zone XV.",Own Sources,15,2015-16,2016-17 D/2015-16/3757,Storm Water Drain,Completed,D-Storm Water Drains,52,4779000,Providing Silt Catch pit & Vertical grating in the existing storm water drain of BRR Roads in zone-V.,Own Sources,5,2015-16,2017-18 D/2015-16/6216,Storm Water Drain,Completed,D-Storm Water Drains,38,9206000,Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on BRR Roads in Zone-IV.,Own Sources,4,2015-16,2017-18 D/2015-16/6341,Storm Water Drain,Completed,D-Storm Water Drains,127,4660000,Construction of storm water Drain of size 900x900mm RCC Box type drain along Kaliamman koil st Koyambadu from Metrowater office Dn 127 to 100 Feet Road in Dn 127 Zone 10.,Deposit Works,10,2015-16,2016-17 D/2015-16/6500,Storm Water Drain,Completed,D-Storm Water Drains,195,8477000,Construction of storm water Drain of size 600x750mm Along3rd cross street and 4th cross street from ETRB Road to 1st Main Road of Ezhil Nagar Thoraipakkam in Div 195 Zone XV.,JNNURM,15,2015-16,2016-17 D/2015-16/8093,Storm Water Drain,Completed,D-Storm Water Drains,148,22470000,"Construction of storm water Drain of size 1200x1200mm of 500m length and 1500x1500mm of 200mm length from dead end along All India Service officers and other Government servant Quarters Road and Panchaliamman koil street to Virugambakkam Canal in Nerkundrum, Dn.148,Zone-XI.",Own Sources,11,2015-16,2017-18 D/2015-16/9808,Storm Water Drain,Completed,D-Storm Water Drains,158,31334000,"Construction of Storm Water Drain of size 1200mmx1200mm along Ganapathi Colony from Thulasingapuram to Adayar River in Dn.158, Zone 12",Own Sources,12,2015-16,2016-17 J/2015-16/0310,Culvert,Completed,J-Bridges,Greater Chennai Corporation,11599000,Construction of Box Culvert 3 vent(4m x 4m) at Ram Nagar 3rd Extension in Dn 188 Zone 14,Own Sources,,2015-16,2017-18 J/2015-16/10488,Culvert,Completed,J-Bridges,Greater Chennai Corporation,34190000,"Name of the work: Demolishing the existing causeway and construction of 9 vent Box Culvert across Korattur lake surplus water canal at Canal Road near Madhanangkuppam main road in Division: 83, Zone -VII",Own Sources,,2015-16,2017-18 J/2015-16/16124,Bridges,Completed,J-Bridges,Greater Chennai Corporation,1500000,"Proposed Construction of Foot Bridge across Buckingam Canal in between Triplicane MRTS Railway Station & Canal Road at Mattankuppam in Dn.116,Zone-IX.",Own Sources,,2015-16,2016-17 J/2015-16/16425,Bridges,Completed,J-Bridges,Greater Chennai Corporation,4191000,"Refurbishment of flyover at G.K.Moopanar Bridge at Turn Bulls Road and Cenatoph Road in Dn-122 , Zone-IX",Own Sources,,2015-16,2017-18 J/2015-16/16554,Bridges,Completed,J-Bridges,Greater Chennai Corporation,4240000,"Refuribshment of flyover Bridges at North Usman Road and Mahalingapuram in Dn-113& 110, Zone-IX.",Own Sources,,2015-16,2017-18 J/2015-16/19153,Bridges,Completed,J-Bridges,136,1728000,"Proposed Construction of Service Bridge Eastern side of Duraisamy Subway at Duraisamy Road in Dn.136, Zone-X",Own Sources,10,2015-16,2016-17 J/2015-16/26584,Bridges,Completed,J-Bridges,Greater Chennai Corporation,4010000,"Improvements to Aranganadhan subway at Saidapet Dn.140 &171, Zone- 10 & 13.",Own Sources,,2015-16,2016-17 J/2015-16/26814,Bridges,Completed,J-Bridges,Greater Chennai Corporation,3120000,"Improvements to existing bidge at Alandur road across Adyar river in Dn.170, Zone-XIII.",Own Sources,,2015-16,2017-18 J/2015-16/27802,Bridges,Completed,J-Bridges,142,1950000,"Improvements for existing subway at Bazzar road in Dn-142,Zone-X.",Own Sources,10,2015-16,2017-18 J/2015-16/28327,Bridges,Completed,J-Bridges,142,2230000,"Improvements for existing subway at Jones road in Dn.142, Zone-X.",Own Sources,10,2015-16,2017-18 J/2015-16/28613,Bridges,Completed,J-Bridges,Greater Chennai Corporation,3194000,"Improvement to existing Bridge across otteri nullah connecting Strahans Road, Brick kiln road, Konnur high road and Cooks road in Division-71,73 & 75, Zone-VI.",Own Sources,,2015-16,2018-19 J/2015-16/29118,Bridges,Completed,J-Bridges,Greater Chennai Corporation,189000,"Improvements for existing staircase in Kotturpuram bridge at Kotturpuram in Dn-172, Zone-XIII.",Own Sources,,2015-16,2016-17 J/2015-16/29358,Bridges,Completed,J-Bridges,Greater Chennai Corporation,636000,"Improvements for existing flyover at junction of Gandhimandapam road and Sardarpatel road inDn-171 and 172, Zone-XIII.",Own Sources,,2015-16,2016-17 J/2015-16/29933,Bridges,Completed,J-Bridges,Greater Chennai Corporation,4980000,"Removing and relaying wearing coat to Aranganadhan subway in Saidapet in Dn.140 & 171, Zone- 10 & 13.",Own Sources,,2015-16,2017-18 L/2015-16/0349,Electrical,Completed,L-Electrical,169,193300,"Numbering of 2059 nos of GI and MS post in Division-168,169,183 to 191, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/0423,Electrical,Completed,L-Electrical,185,25700,"Painting and Numbering of 73 Nos of 8Mtr Street Lamp post and 4 nos of KIOSK Pillar Boxes at EAST COAST ROAD in Division 183, 185, Zone - XIV.",Own Sources,14,2015-16,2016-17 L/2015-16/0564,Electrical,Completed,L-Electrical,159,150200,"Painting of lamp posts in Kathipara Bridge and G.S.T Road, in Div 159, 160, Zone XII. (City Infrastructure and Beautification work for G.I.M 2015) Painting of lamp posts in Kathipara Bridge and G.S.T Road, in Div 159, 160, Zone XII. (City Infrastructure and Beautification work for G.I.M 2015)",Own Sources,12,2015-16,2016-17 L/2015-16/0565,Electrical,Completed,L-Electrical,158,151500,PAINTING AND NUMBERING OF LAMP POSTS AT MOUNT POONAMALLE ROAD FROM DLF TO BUTTROAD AT DN157&158 IN ZONE XII,Own Sources,12,2015-16,2016-17 L/2015-16/10172,Electrical,Completed,L-Electrical,188,4807200,"Supply & Erection of 90 nos of 6mtr lamp post with single staight bracket with Hot dip zinc galvanising with 90-120w LED fitting at BRR Dr Ramamorrthy salai, Bharathiyar Salai and senthilnagar in Div-188,Zone-14",Own Sources,14,2015-16,2016-17 L/2015-16/10256,Electrical,Completed,L-Electrical,34,709800,"Laying of 510 Mtr of 2x16 sqmm cable and erection of 17 Nos of 6 Mtr GI Street Lamp post Hot Dip Zinc Galvanising with Single Straight Bracket with 17 Nos of 40W LED Fitting at Vedhandamurugappa Street, in Division-34, Kodungaiyur, Zone-IV",Own Sources,4,2015-16,2018-19 L/2015-16/10613,Electrical,Completed,L-Electrical,47,969500,"Replacement of 2146 sqmm cable at Jeeva Nagar Phase I in Division- 47, Zone IV",Own Sources,4,2015-16,2017-18 L/2015-16/10783,Electrical,Completed,L-Electrical,47,462700,"Replacement of 1057Mtrs of 2x16 sqmm cable at Bharathi Nagar HB in Division -47, Zone-4",Own Sources,4,2015-16,2017-18 L/2015-16/10784,Electrical,Completed,L-Electrical,47,668800,"Replacement of 1360 Mtrs of 2x16 sqmm cable at Ambedkar Nagar Phase I in Division -47, Zone-4",Own Sources,4,2015-16,2016-17 L/2015-16/10789,Electrical,Completed,L-Electrical,47,911400,"Replacement of 2146 Mtrs of 2x16 sqmm cable at Jeeva Nagar Phase II in Division-47, Zone-4",Own Sources,4,2015-16,2017-18 L/2015-16/10792,Electrical,Completed,L-Electrical,47,616000,"Replacement of 1327 Mtrs 2x16 sqmm cable at Ambedkar Nagar Phase II Division-47, Zone-4",Own Sources,4,2015-16,2016-17 L/2015-16/10874,Electrical,Completed,L-Electrical,91,128400,"Provision for replacement of 4x16 sq.mm Cable for 295 m for existing 6 mtrs MS Post with 150w S.V fittings at Valliammai salai and I Main road ,Ward 91 zone-7",Own Sources,7,2015-16,2016-17 L/2015-16/10883,Electrical,Completed,L-Electrical,37,190000,Removal of Old 130 nos of 6/7 mtr Lamp Post and 15 nos of 9/11 mtr Lamp Post in Division 37 and 46 in Zone 4,Own Sources,4,2015-16,2018-19 L/2015-16/10893,Electrical,Completed,L-Electrical,37,192000,"Replacement of 3 nos of Damaged Kiosk Pillar Box at Various Location in Division 37,Zone 4",Own Sources,4,2015-16,2018-19 L/2015-16/10894,Electrical,Completed,L-Electrical,44,131000,"Replacement of 2 nos of Damaged Kiosk Pillar Box at Various Location in Division 44,Zone 4",Own Sources,4,2015-16,2018-19 L/2015-16/10899,Electrical,Completed,L-Electrical,45,196000,"Replacement of 4 nos of Damaged Kiosk Pillar Box at Various Location in Division 45,Zone 4",Own Sources,4,2015-16,2018-19 L/2015-16/10900,Electrical,Completed,L-Electrical,104,526100,"Provision of 1 No. of 5KWP Solar Roof Top in Gangatheeswarar koil street Corporation Higher secondary school & 1 No. of 2KWP Solar Roof Top in Vellala street Corporation Middle school in Division -104, Zone VIII.",MLACDS,8,2015-16,2018-19 L/2015-16/10902,Electrical,Completed,L-Electrical,46,174000,"Replacement of 3 nos of Damaged Kiosk Pillar Box at Various Location in Division 46,Zone 4",Own Sources,4,2015-16,2018-19 L/2015-16/11070,Electrical,Completed,L-Electrical,107,349100,"Provision of 2Nos of 2KWP Solar Roof Top System with Solar Photo Voltaic Panels,Power Conditioning unit AC & DC Surge protection device,Electrical wiring for Grid tie system as per the requirement of TEDA / MNRE at Subbarayan street Primary School and Mec-Nicals Road Chennai High School in Division-107,Zone VIII Area.",MLACDS,8,2015-16,2018-19 L/2015-16/11401,Electrical,Completed,L-Electrical,89,392300,"������������������������������������������������������provision for ������������������������������������������������������replacement of cable for 774 m for existing 20 nos. of 6 M MS post with 150w sv fittings at west end colony ,ward 89, zone-7",Own Sources,7,2015-16,2016-17 L/2015-16/11665,Electrical,Completed,L-Electrical,46,3747000,"Provision of 27 nos of 8mtr GI Hot Dip Zinc Galvanising with Single Arch Bracket Street Lamp Post at Service Road Both Sides with 27 nos 165watts LED Fitting and 19 nos of 6mtr GI Hot Zinc Galvanising with Single Arch Bracket with 19 nos of 90watts LED Fitting at Rail Over Bridge (ROB), Vyasarpadi,Phase 4, in Division 46,Zone 4",Deposit Works,4,2015-16,2018-19 L/2015-16/11667,Electrical,Completed,L-Electrical,46,2614000,"Provision of 2 nos of 30mtr High Mast with 16 nos of 2x400watts MH Fitting at Rail Over Bridge (ROB), Vyasarpadi in Division 46,Zone IV",Deposit Works,4,2015-16,2016-17 L/2015-16/11669,Electrical,Completed,L-Electrical,46,896000,"Provision of 1 no of 16mtr High Mast with 8 nos of 2x400watts MH Fitting at Rail Over Bridge (ROB),Junction of EH Road and Muthu Mudali st, Vyasarpadi in Division 46,Zone IV",Deposit Works,4,2015-16,2017-18 L/2015-16/11895,Electrical,Completed,L-Electrical,137,482000,"Supply ,Instalation ,Aiming, Testing and Commissioning of 12mtr High Mast at , Earikarai salai jun of Ramapuram Main Road in div-137,Zone 10 area",MPLADS,10,2015-16,2016-17 L/2015-16/12466,Electrical,Completed,L-Electrical,37,199900,Replacement of 550nos of Old 70watts SV Fitting into New 40watts LED Fitting at Various Location in Division 37 in Zone IV,Own Sources,4,2015-16,2018-19 L/2015-16/12468,Electrical,Completed,L-Electrical,46,196900,Replacement of 373nos of Old 70watts SV Fitting into New 40watts LED Fitting at Various Location in Division 44 and 46 in Zone IV,Own Sources,4,2015-16,2018-19 L/2015-16/12564,Electrical,Completed,L-Electrical,57,501500,"Replacement of 929mtrs of 4C x 16 Sq.mm PVC Alu cable at NSC Bose Road in Division-57, under Zone- V.",Own Sources,5,2015-16,2018-19 L/2015-16/12590,Electrical,Completed,L-Electrical,59,192900,"Supply and Erection of 1 nos of 9M Lamp post with double arch bracket with replacement of 235 mtrs of 4X16sqmm cable at nsc bose road CENTER MEDIUM in Dn-59,Zone-5.",Own Sources,5,2015-16,2016-17 L/2015-16/12917,Electrical,Completed,L-Electrical,36,993300,"Replacement of 1876mtrs of 2x16sqmm cable and 799mtrs of 4x16sqmm cable at Sasthiri Nagar 5th street to 11th street Division 36, Zone,IV.",Own Sources,4,2015-16,2016-17 L/2015-16/12927,Electrical,Completed,L-Electrical,36,998700,"Replacement of 2717mtrs of 2x16sqmm cable at Sasthiri Nagar 1st street to 4th street and 12th street to 19th street in Division 36, Zone,IV.",Own Sources,4,2015-16,2016-17 L/2015-16/13208,Electrical,Completed,L-Electrical,35,568300,"Replacement of 1447mtrs 2x16sqmm cable at Anna Salai, Ambethkar Street and Srinivasaperumal Street in Division 35, Zone.IV.",Own Sources,4,2015-16,2016-17 L/2015-16/13213,Electrical,Completed,L-Electrical,35,684800,"Replacement of 1775 mts of 2x16sqmm cable at Siva Sankaran Street, Periyar Street and Bharathidasan Street in Division 35, Zone IV",Own Sources,4,2015-16,2017-18 L/2015-16/13315,Electrical,Completed,L-Electrical,53,505600,"Providing 8nos of 8mtr lamp post with Double st bracket with 250W FL fitting with MH lamp for Zone-V lorry station in Div-53,Zone-V.",Own Sources,5,2015-16,2016-17 L/2015-16/13457,Electrical,Completed,L-Electrical,59,196900,"Supply and Erection of 1 nos of 9.5 Lamp post with double arch bracket with replacement of 300 mtrs of 4X16sqmm cable at EVR SALAI CENTER MEDIAM in Dn-59,Zone-5.",Own Sources,5,2015-16,2016-17 L/2015-16/14384,Electrical,Completed,L-Electrical,38,195500,"Fixing of 1250 Nos .of 40W LED Fittings in Dn:38,39,40 & 43, Zone IV",Own Sources,4,2015-16,2018-19 L/2015-16/14473,Electrical,Completed,L-Electrical,41,199700,"Replacement of 5 Nos of KIOSK Pillar Box in Division-41, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/14475,Electrical,Completed,L-Electrical,42,199700,"Replacement of 5 Nos of KIOSK BOX Pillar in Division-42, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/14480,Electrical,Completed,L-Electrical,47,199700,"Replacement of 5 Nos of KIOSK Pillar Box in Division - 47, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/14491,Electrical,Completed,L-Electrical,34,652600,"REPLACEMENT OF 1714 MTS OF 2 X 16 Sqmm CABLE AT UNION CORBIDE COLONY 1ST TO 7TH STREET AND 22ND STREET IN DIVISION-34,ZONE IV",Own Sources,4,2015-16,2017-18 L/2015-16/14493,Electrical,Completed,L-Electrical,48,199700,"Replacement of 5 Nos of KIOSK Pillar Box in Division-48, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/14496,Electrical,Completed,L-Electrical,34,863200,"REPLACEMENT OF 2142 MTS OF 2 X 16 Sqmm CABLE AT UNION CORBIDE COLONY 2ND TO 3RD STREET AND 8TH TO 20TH STREET IN DIVISION-34,ZONE IV",Own Sources,4,2015-16,2017-18 L/2015-16/14558,Electrical,Completed,L-Electrical,53,719500,"Providing 12nos of 8mtr lamp post with Double st bracket with 250W FL fitting with MH lamp for Basin bridge road new bus stand in Div-53,Zone-V.",Own Sources,5,2015-16,2016-17 L/2015-16/14559,Electrical,Completed,L-Electrical,53,696500,"Providing 11nos of 8mtrl lamp post with Double st bracket with 250W FL fitting with MH lamp at North chennai lorry station in Div-53,Zone-V.",Own Sources,5,2015-16,2016-17 L/2015-16/14677,Electrical,Completed,L-Electrical,34,656400,"Replacement of 1350 Mtrs of 4x16 sqmm cable at Union Carbide colony 3rd street, 4th street and school road in Division-34, Zone IV",Own Sources,4,2015-16,2017-18 L/2015-16/16003,Electrical,Completed,L-Electrical,50,174600," Provision of 1 No. of 2KWP Solar Roof Top in S.I.Office, 59.M.S.Koil street in Div 50, Zone V. ",MLACDS,5,2015-16,2018-19 L/2015-16/16007,Electrical,Completed,L-Electrical,50,174600," Provision of 1 No. of 2KWP Solar Roof Top in Division Office 50, Eastkalmondapam Road in Div 50, Zone V. ",MLACDS,5,2015-16,2018-19 L/2015-16/16009,Electrical,Completed,L-Electrical,49,174600," Provision of 1 No. of 2KWP Solar Roof Top in Division Office 49, Gothandaraman Street in Div 49, Zone V. ",MLACDS,5,2015-16,2018-19 L/2015-16/16011,Electrical,Completed,L-Electrical,49,174600," Provision of 1 No. of 2KWP Solar Roof Top in Dispensary, PAN Rajarathnam 5th Street in Div 49, Zone V. ",MLACDS,5,2015-16,2018-19 L/2015-16/16016,Electrical,Completed,L-Electrical,52,174600," Provision of 1 No. of 2KWP Solar Roof Top in Royapuram s/s, 5. N,R,T, Road in Div 52, Zone V. ",MLACDS,5,2015-16,2018-19 L/2015-16/16018,Electrical,Completed,L-Electrical,50,351900," Provision of 1 No. of 5KWP Solar Roof Top in Heaith post, Venkatesan 1st Street in Div 50, Zone V. ",MLACDS,5,2015-16,2018-19 L/2015-16/16020,Electrical,Completed,L-Electrical,51,351900," Provision of 1 No. of 5KWP Solar Roof Top in Unit-12 office, Perambalu street in Div 51, Zone -V. ",MLACDS,5,2015-16,2018-19 L/2015-16/16343,Electrical,Completed,L-Electrical,47,1514500,"Conversion of 35 Nos of 6 Mtr Street Lamp post with Hot dip Zinc Galvanising with single bracket with 40W LED fitting at Ranganathapuram housing board, in div 47, Zone IV",Deposit Works,4,2015-16,2016-17 L/2015-16/16360,Electrical,Completed,L-Electrical,54,193000,"Replacement of 594mtrs 2C x 16 Sq.mm PVC Alu cable at Chakara chetty street,ibrahim street, jinda street, at div 54 ,under Zone- V",Own Sources,5,2015-16,2018-19 L/2015-16/16363,Electrical,Completed,L-Electrical,54,192400,"Replacement of 597 mtrs 2C x 16 Sq.mm PVC Alu cable at sundaram 1 to 6 th street, at div 54 ,under Zone- V.",Own Sources,5,2015-16,2018-19 L/2015-16/16364,Electrical,Completed,L-Electrical,54,193000,"Replacement of 594 mtrs 2C x 16 Sq.mm PVC Alu cable at wood warf gate 3, at div 54 ,under Zone- V.",Own Sources,5,2015-16,2018-19 L/2015-16/16365,Electrical,Completed,L-Electrical,54,194700,"Replacement of 595 mtrs 2C x 16 Sq.mm PVC Alu cable at wood warf gate 1, at div 54 ,under Zone- V.",Own Sources,5,2015-16,2018-19 L/2015-16/16368,Electrical,Completed,L-Electrical,54,186800,"Replacement of 490 mtrs of 4C x 16 Sq.mm PVC Alu cable at ANNA PILLAI STREETin Division-57, under Zone- V",Own Sources,5,2015-16,2018-19 L/2015-16/16479,Electrical,Completed,L-Electrical,58,177900,"Supply and Erection of 6 nos of Kiosk pillar box in jermiya road, evk sampath salai,thirupali street,krishnapa tank, teyanapet ramaswami pillar, madox street at various divison, in Zone-5.",Own Sources,5,2015-16,2018-19 L/2015-16/16657,Electrical,Completed,L-Electrical,42,944700,"Replacement of 2145mtrs of 2C x 16 Sq.mm PVC Alu cable at Mayor Basudev Street and Veerakutty Street, in Division-42, under Zone- IV.",Own Sources,4,2015-16,2018-19 L/2015-16/16659,Electrical,Completed,L-Electrical,42,974200,"Replacement of 2166mtrs of 2C x 16 Sq.mm PVC Alu cable at T.K.Gardern 1st to 5th Street, Arani Gangan Lane and Perumal Thottam, in Division-42, under Zone- IV.",Own Sources,4,2015-16,2016-17 L/2015-16/16667,Electrical,Completed,L-Electrical,42,988800,"Replacement of 2421mtrs of 2C x 16 Sq.mm PVC Alu cable at Seniamman Lane, Jeeva Street, Annai Street, Thilagar nagar and Tsunami Housing Board, in Division-42, under Zone- IV.",Own Sources,4,2015-16,2018-19 L/2015-16/16672,Electrical,Completed,L-Electrical,42,919700,"Replacement of 2027 mtrs of 2C x 16 Sq.mm PVC Alu cable at Kothandaraman Street, MCM Gardern and Manikyavathiyar Street, in Division-42, under Zone- IV.",Own Sources,4,2015-16,2016-17 L/2015-16/16679,Electrical,Completed,L-Electrical,42,995700,"Replacement of 2576 mtrs of 2C x 16 Sq.mm PVC Alu cable at Mayor Basudev Street, West KG Gardern and T.H.Road lanes, in Division-42, under Zone- IV.",Own Sources,4,2015-16,2016-17 L/2015-16/16861,Electrical,Completed,L-Electrical,43,1198900,"Provision of 27 Nos. of 6 Mtr Street Lamp Post with Hot dip zinc galvanising with Single Straight bracket with 40W LED Fitting at Power Kuppam, Dn:43, Zone IV. Phase I ( Power Kuppam).",Deposit Works,4,2015-16,2016-17 L/2015-16/16863,Electrical,Completed,L-Electrical,43,573100,"Provision of 14 Nos. of 6 Mtr Street Lamp Post with Hot dip zinc galvanising with Single Straight Bracket with 40W LED Fitting at Power Kuppam, Dn:43, Zone IV. Phase II ( TNSCB Deposit work)",Deposit Works,4,2015-16,2016-17 L/2015-16/17126,Electrical,Completed,L-Electrical,35,473900,"Provision of 4 Nos. of 8 mtr G.I.Hot Dip Zinc Galvanising Lamp post with Double Arch Bracket with 8 Nos of 165W LED Fitting at GNT Road Grade Seperator (Over Bridge), Moolakadai Junction Kodungaiyur in Division: 35, Zone IV.",Deposit Works,4,2015-16,2016-17 L/2015-16/17193,Electrical,Completed,L-Electrical,48,498700,"Provision of 10 Nos of 6Mtr Street lamp post with Hot dip zinc galvanising with single straight bracket on 40W LED Fitting at Parthasarathy Housing Board (SCB) in Div 48, Zone IV",Deposit Works,4,2015-16,2016-17 L/2015-16/17202,Electrical,Completed,L-Electrical,104,1115000,"Provision of 24 Nos of 6mtr Lamp Post with 40 to 50W LED Fittings and laying of 896 Mtr of 2X16 sqmm cable at Annanagar Housing Board EVR Salai in Dn -104, Under Zone-VIII, Area.",Deposit-Asset,8,2015-16,2016-17 L/2015-16/17566,Electrical,Completed,L-Electrical,57,185900,"Replacement of 481 mtrs cable of 2cx16sqmm pvc alu cable at jakapuram slum,in division -57",Own Sources,5,2015-16,2018-19 L/2015-16/17583,Electrical,Completed,L-Electrical,64,4822900,Provision of new 55 Nos of 7mtr GI Single arch lamp post(28nos with 150w to 165w LED Fittings for main track side and 27nos of additional arch bracket for service road side with 2x150w to 165w LED Fitting) with 82nos of LED Fitting at newly constructed Grade separator by department of highways in Jawaharlal Nehru salai junction of perambur redhills road and Erattai eri kadap[pa road in zone vi(by deposit work),Deposit Works,6,2015-16,2016-17 L/2015-16/17625,Electrical,Completed,L-Electrical,83,946700,"Proposed Erection of 6 Nos of 8 Mtr Lamp Post with Double Brackets and Replacement of 4 X 16 sqmm UC Cable at 200 Ft Road from Palanima nagar to Senthil Ngar Signal (Phase II) in Div 83 Zone VII, Ambattur",Own Sources,7,2015-16,2016-17 L/2015-16/17631,Electrical,Completed,L-Electrical,83,961800,"Proposed Erection of 6 nos of 8 Mtr Lamp post with Double Brackets & Replacement of 1110 Mtrs of 4 x 16 Sqmm UG Cable at 200 Feet Ring Road from Padi Bridge toPalanima Nagar ( Phase 1) in Dn 83 Zone VII, Ambattur",Own Sources,7,2015-16,2016-17 L/2015-16/17879,Electrical,Completed,L-Electrical,147,36561000,"Provision of 766 Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 59 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Pallavan Nagar,Rukmani Nagar,Kandha Swamy Nagar,Janaki Nagar, Kandha Swamy Nagar and various Places in Division 147 Zone XI","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/17880,Electrical,Completed,L-Electrical,149,21253000,"Provision of 348 Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 110 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Kamakodi Nagar Kamatchi Amman Nagar Venkata Perumal NagarRamakrishna Nagar, Murali Krishna Nagar & Vijaya Nagar and various Places in Division 149 Zone XI","Loans, Grants And Own Sources",11,2015-16,2017-18 L/2015-16/17881,Electrical,Completed,L-Electrical,152,20335000,"Provision of 336 Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 102 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Indhra Gandhi Nagar, Ambathkar Salai,Rajaji Nagar, Kadambadi Nagar and various Places in Division 152 Zone XI","Loans, Grants And Own Sources",11,2015-16,2017-18 L/2015-16/18005,Electrical,Completed,L-Electrical,59,177900,"Supply and Erection of 6 nos of Kiosk pillar box in issact street, kathursadiyappan,Doveton street,Rajaannamal mandram, Rattan bazar, muthu swami salai at various divison, in Zone-5.",Own Sources,5,2015-16,2018-19 L/2015-16/18019,Electrical,Completed,L-Electrical,180,841500,"PROVISION OF 10 NOS OF 6 MTR LAMP POST WITH ARCH BRACKET AND REMOVAL AND REFIXING OF 20 NOS OF 6 MTR LAMP POST WITH ARCH BRACKET AND LAYING OF 984 MTRS OF 4X16 SQ.MM ALU CABLE AT RAMANUJAM IT CITY ROAD, THRARAMANI IN DIV-180, ZONE-XIII",Own Sources,13,2015-16,2016-17 L/2015-16/18037,Electrical,Completed,L-Electrical,79,179600,"Removal & Reerection of 6 Nos of 8 Mtr Lamp Post and Laying of 266 Mtrs 4 x 16 Sqmm Cable at Redhills Road In Div 79, Zone-VII, Ambattur.",Own Sources,7,2015-16,2016-17 L/2015-16/18317,Electrical,Completed,L-Electrical,95,960200,Replacement of 29 Nos of 6 mtr Reconditioned MS lamp Post with 40 to 50 W LED Fittings at Thiru Nagar 18 th to 25 th Street in Division -95 Under Zone - VIII Area.,Own Sources,8,2015-16,2016-17 L/2015-16/18792,Electrical,Completed,L-Electrical,99,438800,"PROVISION OF ADDL.SINGLE ARCH BRACKET ON EXISTING 7 MTR G.I. LAMP POST AND PROVISION OF 2 NOS G.I LAMP POST AT THIRUMANGALAM OVER BRIDGE IN BOTH SIDES (EAST &WESTERN SIDES) IN DIV-99,ZONE-8",Own Sources,8,2015-16,2016-17 L/2015-16/18804,Electrical,Completed,L-Electrical,58,122800,"Replacement of 289mtrs 2Cx16sq.mm PVC ALU cable at Ritherton Road 3rd lane(Church Lane in Division-58, Zone-5.",Own Sources,5,2015-16,2016-17 L/2015-16/19025,Electrical,Completed,L-Electrical,58,114100,"Replacement of 301 mtrs of 2C x 16 Sq.mm PVC Alu cable at Ritherton Road Avenue in Division-58, Zone-V.",Own Sources,5,2015-16,2016-17 L/2015-16/19038,Electrical,Completed,L-Electrical,61,664200,"Replacement of 1726 mtrs of 2C x 16 Sq.mm PVC Alu cable at Driver Street, Thulasingam Street, Suburayan Street, Basha Shahib Street, Basha Street and Velayutham Street, in Division-61, under Zone- V.",Own Sources,5,2015-16,2016-17 L/2015-16/19298,Electrical,Completed,L-Electrical,34,519600,"Provision of 13 Nos of 6 Mtr GI Lamp post with 40W LED Fitting at R.V. Nagar 5th Street and NSK Salai in Division:34, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/1944,Electrical,Completed,L-Electrical,151,179345,"ERECTION OF 6 NOS OF 8 MTR GI LAMP POST AT MOUNT POONAMALLE ROAD FROM POOTHAPEDU JUNCTION TO PORUR JUNCTION IN DIV 151,ZONE XI (City Infrastructure and Beautification work for G.I.M.2015)",Own Sources,11,2015-16,2017-18 L/2015-16/19587,Electrical,Completed,L-Electrical,150,300000,"REMOVAL AND RE -ERECTION OF 20 MTR HIGHMAST LIGHT AT ARCOT ROAD, PORUR JUNCTION IN DIVISION -150,ZONE-XI",Own Sources,11,2015-16,2016-17 L/2015-16/19813,Electrical,Completed,L-Electrical,81,14879700,"Proposed Erection of 69 nos of 6 Mtr hot dip zinc galvanising Lamp post Straight Brackets with 40 w to 50 watts LED fitting,73 nos of 6 Mtr hot dip zinc galvanising Lamp post arch Brackets with 90 w to 120 watts LED fitting and 98 nos of 8 Mtr 6 Mtr hot dip zinc galvanising Lamp post Straight Brackets with 150 W to 165 W LED fitting at Thullukathamman st,Nathela Sampathu St,Ragavendra st and Various Streets in Dn 81 Zone VII, Ambattur.","Loans, Grants And Own Sources",7,2015-16,2017-18 L/2015-16/19814,Electrical,Completed,L-Electrical,79,20814700,"Proposed Erection of 400 nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 40 w to 50 watts LED fitting and 79 nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post With Arch Bracket with 90 W to 120 W LED fitting at Various Streets in Venkateswara Nagar, Vinayagapuram Lakshmiamman Nagar & Ramnagar in Dn 79 Zone VII.","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19815,Electrical,Completed,L-Electrical,86,23109100,"Proposed Erection of 249 nos of 6 Mtr hot dip zinc galvanising street Lamp post Straight Brackets with 40 w to 50 watts LED fitting,229 nos of 6 Mtr hot dip zinc galvanising st. Lamp post arch Brackets with 90w to 120 watts LED fitting and 12 nos of 8 Mtr hot dip zinc galvanising Lamp post Straight Brackets with 150 W to 165 W LED fitting at PV city,Rampoorn nagar,Padma street,Devadass street and Various Streets in Dn 86 Zone VII, Ambattur.","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19816,Electrical,Completed,L-Electrical,80,17481400,"Proposed Erection of 302 nos of 6 Mtr Hot Zinc Galvanising Lamp post Lamp post with Single Straight Brackets with 40 w to 50 watts LED fitting and 36 nos of 6 Mtr Hot Zinc Galvanising Lamp post With Single Arch Bracket with 90 W to 120 W LED fitting at Various Streets in Thirumalai Priya Nagar,Rajiv Gandhi Nagar , Thiruthanigai Nagar & Pudur & 24 Nos 8 Mtr GI Octogonal Lamp Post with Double Bracket with 150 - 165 W LED Fitting in Redhills Road in Dn 80 Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19817,Electrical,Completed,L-Electrical,87,2764700,"Proposed Erection of 53 nos of 6 Mtr hot dip zinc galvanising post Straight Brackets with 40 w to 50 watts LED fitting,12 nos of 6 Mtr hot dip zinc galvanising Lamp post straight Brackets with 90 w to 120 watts LED fitting at Vanniar st,Raja st,Elango nagar and Various Streets in Dn 87 Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19819,Electrical,Completed,L-Electrical,82,30107800,"Proposed Erection of 330 nos of 6 Mtr Hot Dipped Galvanising Lamp post & 175 Nos of 7 Mtr Hot Zinc Galvanising Lamp post with Single Straight Brackets with 40 w to 50 watts LED fitting , 20 nos of 6 Mtr Hot Dipped Galvanising Lamp post With Single Arch Bracket with 90 W to 120 W LED fitting at Various Streets in Menambedu, Indra Nagar, VOC Nagar ,Muthamizh Nagar , Mookambigai Nagar , West Balaji Nagar & Kabaleeswarar Nagar & 62 Nos 8 Mtr GI Octogonal Lamp Post with Double bracket with 150-165W LED Fitting in Redhills Road in Dn 82, Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19820,Electrical,Completed,L-Electrical,88,4496100,"Proposed Erection of 62 nos of 8 Mtr dip zinc galvanising lamp post double Brackets with 90 w to 120 watts LED fitting at Park road in Dn 88 Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2017-18 L/2015-16/19830,Electrical,Completed,L-Electrical,83,30367000,"Proposed Erection of 449 nos of 7 Mtr Lamp post with Straight Brackets with 40 w to 50 watts LED fitting & 92 Nos 7 Mtr Lamp Post with Arch Bracket with 90 w to 120 watts LED fitting and 80 nos of 8 Mtr G.I Octagonal Lamp post With Double Bracket with 150 W to 165 W LED fitting in TVS Nagar, Seathamman Koil St , Lake View Garden & Other Streets of Dn 83, Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19833,Electrical,Completed,L-Electrical,91,22440900,"Proposed Erection of 529 nos of 6 Mtr long Hot dip Zinc galvanising Lamp Post with Single Straight Bracket with 40 w to 50 watts LED fitting at Various Streets in I,II ,III ,VI, VII ,LIG BLOCK in Dn. 91 Zone VII","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19834,Electrical,Completed,L-Electrical,92,6006900,"Proposed erection of 139 nos. of 6mtr long Hot dip Zinc galvanising Lamp Post with single bracket with 40w-50w LED fittings at Patinathar salai, 10th block, kannadhasan, bharathidasan salai and other streets in Division 92, Zone VII","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19835,Electrical,Completed,L-Electrical,93,21179900,"Proposed erection of 316 nos. of 6 mtr long Hot dip Zinc galvanising Lamp Post with single bracket with 316 nos. of 40w-50w LED Fittings and 85 nos. of 8 mtr long GI Octagonal street lamp pole with single bracket with 85 nos. of 150w-165w LED Fittings at I, II,III,V,VI BLOCKS, padikuppam industrial area and various Streets in Division 93, Zone VII","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19846,Electrical,Completed,L-Electrical,159,843900,"Erection of 19 nos of 6 mtr G.I lamp posts with single straight bracket with 40-50 watts LED fittings at Kumaran street, kumaran lane and other streets in Div 159 in zone XII( sch of rate 2015-16)","Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/19849,Electrical,Completed,L-Electrical,155,30324000,"Provision 569 Nos 6mtr G.I Lamp Post with 476 Nos of 40w LED Fitting and 93 Nos of 90w LED Fitting on Single Bracket at Thirumalai Nagar, Kannadasan Nagar , Giri Nagar, Tamil Nagar, Azhaghapurai and Varoius Places in Division 155 Zone-XI","Loans, Grants And Own Sources",11,2015-16,2017-18 L/2015-16/19850,Electrical,Completed,L-Electrical,160,4405100,"Erection of 48 No's of 6 mtr G.I lamp posts with single straight Bracket with 40 to 50W LED fittings and 20 No's of 8 mtr octagonal G.I lamp posts at Abraham Nagar, Subba reddy colony, Gandhi market, Railway station Road and other streets in Div 160, XII(sch of rate 2015-16)","Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/19851,Electrical,Completed,L-Electrical,154,8157000,"Provision of 177 Nos of 6 mtr Hot Dip Zinc Galvanising Lamp post with 40w LED Fitting on Single bracket at Moon Light,Anandam Nagar,Shanthi Nagar and Varoius Places in Division 154,Zone-XI","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/19852,Electrical,Completed,L-Electrical,85,29129000,"Proposed Erection of 390 nos of 6 Mtr Hot Dipped Zinc galvanasing lamp post with Straight Brackets with 40 w to 50 watts LED fitting and 111 nos of 8 Mtr ocotoganal Lamp post with Double Brackets with 150 w to 165 watts LED fitting at MTH rd (From Ambatuur Railway bridge to Ambattur Estate bus Terminus) Samthariya nagar , kamarajar nagar , OV Alagesan street, Manikkavinayagar koil street and Various Streets in Dn 85 Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19854,Electrical,Completed,L-Electrical,156,42493300,EERECTION OF 1037NOS OF 6MTR GI POST WITH SINGLE BRACKET WITH 40W LED FITTING AT VARIOUS PLACES IN DIV 156 IN ZONE 12,"Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/19868,Electrical,Completed,L-Electrical,156,65221200,Erection 1162 Nos of 6 mtrs GI Lamp posts with single arch bracket with 90-120 watts LED fittings and 40nos of 8mtr octaganalpost with single st bracket with 150w LEDFITTING at various streets in DIV 156 in Zone - 12.,"Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/19884,Electrical,Completed,L-Electrical,64,840000,Provision of new 3nos of 8mtr Height GI Lamp post with 150w to 165w LED Fittings in place of rust eatened lamp post and laying of 1300mtrs of UG Cables at Erattai Eri Salai from Paper mills road to G N T Road Centre mediun in div 64 zone VI due to construction of new divider at centre mediun portion of the road by dept of High ways.,Own Sources,6,2015-16,2016-17 L/2015-16/19903,Electrical,Completed,L-Electrical,158,3920600,`Erection of 65 nos 6 mtrs GI Lamp posts with single straight bracket with 40-50 watts LED fittings and 21 Nos of 7 mtrs GI Lamp posts with single arch bracket with 90-120 watts LED fittings at various streets in DIV 158 in Zone - 12.,"Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/19905,Electrical,Completed,L-Electrical,84,7390700,"Proposed Erection of 192 nos of 6 MtrHot Dipped zinc galvanaised Lamp post with Single Straight Brackets with 40 w to 50 w LED fitting at Pothiamman koil st, sastri squre, Thirumalai nagar ,Sivanandan colony , Chavadi cross streets, 12 to 16 streets and other streets in Dn 84 Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/19908,Electrical,Completed,L-Electrical,157,8483700,Erection of 116 nos 6 mtrs GI Lamp posts with single straight bracket with 40-50 watts LED fittings and 41 Nos of 7 mtrs GI Lamp posts with single arch bracket with 90-120 watts LED fittings and20NOS OF 8mtrpost with 150-165w LED FITTING at various streets in DIV 157 in Zone - 12.,"Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/19909,Electrical,Completed,L-Electrical,61,625100,"Replacement of 1388 mtrs of 2C x 16 Sq.mm PVC Alu cable at Thiruvangadam Street, Seeyali Street, Veelayutham Street, Velayuthum Chetty Street and Basha Street, in Division-61, under Zone- V.",Own Sources,5,2015-16,2016-17 L/2015-16/19910,Electrical,Completed,L-Electrical,64,983400,Provision of new 5nos of 8mtr Height GI Lamp post with 150w to 165w LED Fittings in place of rust eatened lamp post and laying of 1549mtrs of UG Cables at Erattai Eri Salai from Sivanandha nagar junction to Paper mills road Centre mediun in div 65 zone VI due to construction of new divider at centre mediun portion of the road by dept of High ways.,Own Sources,6,2015-16,2016-17 L/2015-16/20018,Electrical,Completed,L-Electrical,188,48863000,"Provision of 888 nos of 6mtr Hot Dip Galvanizing street lamp post with Single Straight Bracket with 40-50w LED fitting and 186 nos of 6 mtr Hot Dip Galvanizing street lamp post with Arch Bracket with 90-120w LED ftittings set at various street in Div-188, Madipakkam Zone-14","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20034,Electrical,Completed,L-Electrical,12,1200000,"Provision of 25 nos. of 6 mtr G.I lamp post with Single Bracket with 40w LED fittings at Sathangadu lanes, Jandravar lane and T.H road lanes etc., in Division-12, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2016-17 L/2015-16/20037,Electrical,Completed,L-Electrical,11,3185000,"Provision of 71 nos. of 6 mtr G.I lamp post with Single Bracket with 40w LED fittings at TKS avenue, Kanappa thottam, ABC avenue, Tiruvottiyur High Road lanes, CMP lanes and Zone-I office area etc., in Division-11, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2016-17 L/2015-16/20053,Electrical,Completed,L-Electrical,110,962400,"Electrification work at Nungambakkam CGHS School Ground floor and First floor in div 110, Zone.IX",Own Sources,9,2015-16,2016-17 L/2015-16/20069,Electrical,Completed,L-Electrical,110,999100,"Electrification work at Nungambakkam CGHS School Second floor and Additional Building Three Floors in div 110, Zone.IX",Own Sources,9,2015-16,2016-17 L/2015-16/20073,Electrical,Completed,L-Electrical,110,996400,"WORK: Electrification work at Nungambakkam CBHS School (A and E Block Buildings) in div 110, Zone.IX",Own Sources,9,2015-16,2017-18 L/2015-16/20089,Electrical,Completed,L-Electrical,185,45540200,"Provision of 561nos of 6 mtr hotdip lamp post with straight bracket with 40-50W LED street light fittings set and 302 nos of 6 mtrhotdip lamp post with straight bracket with 90-120W LED street light and 98Nos of 7mtr Conventional Post with 40-50W LED Fitting set at various street in Div 185,Palavakkam, Zone XIV.","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20123,Electrical,Completed,L-Electrical,194,20816800,Provision of 487Nos of 6Mtr Hot dip Zinc Galvanising street lamp post with Single bracket with 487nos of 40-50watts LED fittings at various location in Dn.194 in Zone-XV,"Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/20125,Electrical,Completed,L-Electrical,143,18492000,"Provision of 366 numbers of 6 mtr Lamp Post with straight bracket of 40w LED Fitting and 48 Nos of 90w LED Fitting on 6 Mtr Lamp Post with Single arch bracket at Nolambur phase 1,Vempuli amman koil st,5th,8th Block,S&P Garden,Gajalakshmi nagar,Mogappair main road and various Places Places in Division 143 Zone XI","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/20127,Electrical,Completed,L-Electrical,195,38548700,Provision of 608Nos of 6Mtr Hot dip Zinc galvanising street lamp post with Single bracket with 608nos of 40-50watts LED fittings and 220Nos of 6Mtr Hot dip Zinc galvanising street lamp post with Arch bracket with 220nos 90-120w LED fitting at Various Location in Dn.195 in Zone-XV,"Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/20133,Electrical,Completed,L-Electrical,196,42877600,Provision of 891Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket 891Nos of 40-50w watts LED fitting and 100Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single Arch bracket with 100nos 90-120w LED fitting at Various Location in Dn.196 in Zone-XV,"Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/20141,Electrical,Completed,L-Electrical,199,1620600,Provision of 11Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket 11Nos of 40-50w watts LED fitting and 19Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single Arch bracket with 19nos 90-120w LED fitting at Various Location in Dn.199 in Zone-XV,"Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/20149,Electrical,Completed,L-Electrical,197,33351600,Provision of 598 Nos of 6Mtr street lamp post with Single straight bracket Hot dip zinc galvanising with 40-50watts LED fittings and 164 nos 6Mtr street lamp post with Single Arch bracket Hot dip zinc galvanising with 90-120w LED fitting at Various Location in Dn.197 in Zone-XV,"Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/20159,Electrical,Completed,L-Electrical,198,76805400,"Provision of 1469 Nos of 6Mtr street lamp post with Single straight bracket Hot dip zinc galvanising with 40-50watts LED fittings, 239 nos 6Mtr street lamp post with Single Arch bracket Hot dip zinc galvanising with 90-120w LED fitting and 35 nos 8Mtr street lamp post with Double Arch bracket Hot dip zinc galvanising with 150-165w LED fittingat Various Location in Dn.198 in Zone-XV","Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/20166,Electrical,Completed,L-Electrical,148,17485000,"Provision of 308 nos of 6 mtr hotdip lamp post with straight bracket with 40-50W LED street light fittings set and 84 nos of 6 mtrhotdip lamp post with straight bracket with 90-120W LED street light set at Mettukupam main road,Kadambadi amman nagar,Periyar nagar and various street in Div 148,Nerkundrum, Zone XI","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/20168,Electrical,Completed,L-Electrical,145,19585000,"Provision of 318 nos of 6 mtr hotdip lamp post with straight bracket with 40-50W LED street light fittings set and 115 nos of 6 mtrhotdip lamp post with straight bracket with 90-120W LED street light set at Muniyappa nagar,New colony,Pallavadi and various street in Div 145,Nerkundrum, Zone XI","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/20189,Electrical,Completed,L-Electrical,33,16910300,"Provision of 391 Nos of 6mtr lamp post, single straight bracket with 40w LED Fitting at Munuswamy Nagar, V.P.C Nagar & various streets in Div-33 of Zone-III (Madhavaram) (Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/20195,Electrical,Completed,L-Electrical,150,18231000,"Erection of 335 nos of 6mtr G.I lamp posts with single straight bracket with 40 to 50 watts LED fittings and 48 Nos of 6mtr G.I lamp posts with single Arch bracket with 90 to 120 watts LED fittings at Samayapuram,Sivapootham Perumal koil Street and Various places in division 150 in zone XI. (Sch of rate 2015-16)","Loans, Grants And Own Sources",11,2015-16,2017-18 L/2015-16/20199,Electrical,Completed,L-Electrical,200,17755900,"Provision of 75Nos of 8Mt GI Octagonal street lamp post with Double Bracket with150Nos of 150-165w LED fitting,80 Nos of 6Mtr street lamp post with Single straight bracket Hot dip zinc galvanising with 40-50watts LED fittingsand 100 nos 6Mtr street lamp post with Single Arch bracket Hot dip zinc galvanising with 90-120w LED fitting at Various Location in Dn.200 in Zone-XV","Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/20205,Electrical,Completed,L-Electrical,153,19356500,"Erection of 391 nos of 6mtr G.I lamp posts with single straight bracket with 40 to 50 watts LED fittings and 32 Nos of 6mtr G.I lamp posts with single Arch bracket with 90 to 120 watts LED fittings at Ambal Nagar,Meenakshi Nagar,Suresh Nagar and Various places in division 153 in zone XI. (Sch of rate 2015-16)","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/20206,Electrical,Completed,L-Electrical,28,16387000,"Provision of 385 Nos of 6mtr lamp post, single straight bracket with 40w LED Fitting at A.A.Nagar, Madhavaram Co.operative Nagar & various streets in Div-28 of Zone-III (Madhavaram) (Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/20222,Electrical,Completed,L-Electrical,151,13720800,"Erection of 304 nos of 6mtr G.I lamp posts with single straight bracket with 40 to 50 watts LED fittings at Lakshmipuram,Kuyappettai Anjeneyar koil street and Various places in division 151 in zone XI. (Sch of rate 2015-16)","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/20283,Electrical,Completed,L-Electrical,58,249100,"Electrification of newly proposed complaint cell (1913 Call center) at First floor in AMMA Maligai, Ripon building premises in Dn.58, Zone V.",Own Sources,5,2015-16,2016-17 L/2015-16/20285,Electrical,Completed,L-Electrical,22,30291400,"Provision of 707 nos of 6mtr lamp post WITH Hot dip zinc galvanising with straight bracket with 40w to 50 w LED Fitting at Mahaveer Garden, Sakthivel Nagar and Various locations in Division-22 of zone-III","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/20292,Electrical,Completed,L-Electrical,24,86869600,"Provision of 216 nos of 8mtr lamp post WITH Hot dip zinc galvanising with straight bracket with 90w to 120 w LED Fitting and 1694 nos of 6mtr lamp post WITH Hot dip zinc galvanising, with straight bracket with 40w to 50 w LED Fitting at Mettur, Murugambedu and Various locations in Division-24 of zone-III (Madhavaram)(Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/20297,Electrical,Completed,L-Electrical,25,27024900,"Provision of 170 nos of 8mtr lamp post WITH Hot dip zinc galvanising with straight bracket with 90w to 120 w LED Fitting and 358 nos of 6mtr lamp post WITH Hot dip zinc galvanising, with straight bracket with 40w to 50 w LED Fitting at Anna Nagar, Moorthy Nagar and Various locations in Division-25 of zone-III (Madhavaram)(Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/20317,Electrical,Completed,L-Electrical,18,34257300,"Provision of 105 Nos of 6Mtr G I Lamp post with Single straight bracket with 40W to 50 watts LED fittings at CPCL Nagar Layout and Other Streets and 228 Nos of 8 Mtr G I Octagonal Sreet Lamp with Double bracket with 150W to 165 watts LED fitting at MFL Jn to Sathankadu Road, Ponneri Express Road CPCL to Tamin Jn,200 Feet Road Tamin Jn to SRF Company Jn of Neduchezian Street in Dn-18/zone-II.","Loans, Grants And Own Sources",2,2015-16,2016-17 L/2015-16/20344,Electrical,Completed,L-Electrical,19,20343000,"Provision of 150 Nos of 6Mtr G I OctagonalLamp Post with Single straight bracket with 40W to 50 watts LED fittings at MMDA Mathur 59 th to 124th Street ,and other street,22 Nos of 8 Mtr G I Octagonal Sreet Lamp with Single Arch bracket with 150W to 165 watts LED fitting at 3rd Main Cross St,90 Nos of 8 Mtr G I Octagonal Sreet Lamp with Double Arch bracket with 150W to 165 watts LED fitting at SRF Company Jn of Kosappur Road Jn, Kosappur Road Jn to Manjambakam road Jn,Manjambakam road Jn to Upto Zone-3 in Dn-19/zone-II. (Sch of rate 2015-16)","Loans, Grants And Own Sources",2,2015-16,2016-17 L/2015-16/20385,Electrical,Completed,L-Electrical,168,5552800,"Provision of 107 nos of 6 Mtr lamp post with Single Straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Rajarathinam Main Road in Division-168, Zone-XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20387,Electrical,Completed,L-Electrical,189,43042800,"Work: Erection of 789nos of 6 Mtr lamp hot dip post with Single st Bracket with 40-50w LED Fitting and 152nos of 6 Mtr lamp not dip galvanising post with Single arch Bracket with 90-120w LED Fitting at various streets in Division-189, Zone-XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20389,Electrical,Completed,L-Electrical,169,45383400,"Provision of 788 nos of 6 Mtr lamp post with Single straight Bracket 40w-50w LED Fitting and 220 nos of 6 Mtr lamp post with Single Straight Bracket 90w-120w LED Fitting with hot dip zinc galvanising at various places in Division-169, Zone-XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20391,Electrical,Completed,L-Electrical,187,8748400,"Provision of 168 nos of 6 Mtr lamp post with Single straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Various Locations in Division-187, Zone-XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20393,Electrical,Completed,L-Electrical,190,47761400,"Provision of 832 nos of 6 Mtr lamp post with Single Straight Bracket 40w-50w LED Fitting and 212 nos of 6 Mtr lamp post with Single Straight Bracket 90w-120w LED Fitting with hot dip zinc galvanising at various places in Division-190, Zone-XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20394,Electrical,Completed,L-Electrical,186,7438600,"Work :Erection of 24nos of 6 Mtr hotdip galavanising lamp post with Single Bracket with 90-120w LED Fitting and 143nos of 6 Mtr lamp post with hotdip galavanising with Single straight Bracket with 40-50w LED Fitting at Eleemnagar manthoppumain road, varkis street and cross street,Seevaram 1-4 ,Thanikachalam St, Kazhaigar St and Ramachandran st in Division-186, Zone-XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/20442,Electrical,Completed,L-Electrical,26,17427800,"Supply & erection of 399 Nos of 6mtr Octaganal lamp post, Single bracket with 40w LED Fitting set at Devaki Nagar and Various location in Div- 26 of Zone-III, Madhavaram .","Loans, Grants And Own Sources",3,2015-16,2017-18 L/2015-16/20457,Electrical,Completed,L-Electrical,27,11617400,"Supply & erection of 161 Nos of 6mtr Octaganal lamp post, Single bracket with 40w LED Fitting set and 87 Nos of 6mtr Octaganal lamp post, Single bracket with 90w LED Fitting set at Edaima Nagar to Assisi Nagar Main Road, Kambar Nagar and Various location in Div- 27 of Zone-III, Madhavaram .","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/20596,Electrical,Completed,L-Electrical,10,2014000,"Provision of 25 nos. of 6 mtr G.I lamp post with Single Bracket with 40w LED fittings fittings at Basin Road lane, Periyamettu palayam lane, Mukunthaman koil West mada and South mada cross lanes, and 10 nos. of 8 mtr G.I Octogonal lamp post with Single Bracket with 165w LED fittings at Sannathy street, etc., in Division-10, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2016-17 L/2015-16/20609,Electrical,Completed,L-Electrical,1,14900000,"Provision of 350 nos. of 6 mtr G.I lamp post with Single Straight Bracket with 40w LED fittings at Thazankuppam, Mugathuvarakuppam beach road, Nettukuppam left out places, S.V.M nagar, Tiruvalluvar nagar, J.J nagar, Donbosco road, TNSCB roads etc., in Division-1, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2016-17 L/2015-16/20616,Electrical,Completed,L-Electrical,2,4852000,"Provision of 110 nos. of 6 Mtr G.I lamp post with Single Straight Bracket with 40w LED fittings at Kamaraj nagar, Sanjai gandhi nagar, MGR nagar, R.S road, Gandhi nagar, Periyakuppam other places & Burial ground road, Foundry road, Shastry nagar etc., in Division-2, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2016-17 L/2015-16/20618,Electrical,Completed,L-Electrical,3,16330000,"Provision of 260 nos. of 6 Mtr G.I lamp post with Single Bracket with 40w LED fittings in West kasi koil Kuppam, KVK kuppam, K.V.puram, Kathivakkam station road, J.J.nagar and Tsunami Quarters, 60 nos. of 8 mtr G.I Octogonal lamp post with Single Bracket with 150w LED fitting at, Ennore Express road near A.S nagar 1st street to 11th street etc., in Division-3, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2016-17 L/2015-16/20619,Electrical,Completed,L-Electrical,123,169300,"Electrification work of Implementation Committee (Hawking Zone) at R.A.Puram 3rd cross street in Division -123, (Unit-25) Zone-IX",Own Sources,9,2015-16,2016-17 L/2015-16/20630,Electrical,Completed,L-Electrical,5,3120000,"Provision of 70 nos. of 6 Mtr G.I lamp post with Single Straight Bracket with 40w LED fittings at Srirangam new town and Soundara pandianar nagar, Wimco nagar railway station road and T.H Road lanes, etc., in Division-5, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2016-17 L/2015-16/20631,Electrical,Completed,L-Electrical,7,25165000,"Provision of 364 nos. of 6 Mtr G.I lamp post with Single straight Bracket with 40w LED fittings and 151 nos. of 6 Mtr G.I lamp post with Single arch Bracket with 90w LED fittings in Raja Annamalai nagar, Ragavendra Colony, Periyar Nagar, M.G.R Nagar, Rajivgandhi Nagar, Gangai amman Nagar, Rajaji Nagar, Kamaraj Nagar Near KCP Road, Balakrishna nagar, Canal Road, etc., in Division-7, Zone-I [SOR-2015-16]","Loans, Grants And Own Sources",1,2015-16,2017-18 L/2015-16/20677,Electrical,Completed,L-Electrical,20,6505400,Provision of 88 Nos of 8 Mtr G I Octagonal Street Lamp post with Single Arch bracket with 90W to 120 watts LED fittings at Kamarajar salai (Jn of Varadharajan st to Padasalai Jn. To CPCL Jn) Ward-20/Zone-II (Sch of rate 2015-16),"Loans, Grants And Own Sources",2,2015-16,2016-17 L/2015-16/20748,Electrical,Completed,L-Electrical,164,1409600,ERECTION OF 33 NOS OF 6 MTRS GI LAMP POSTS WITH 40-50 WATTS LED FITTINGS AT VARIOUS STREETS IN DIV 164 IN ZONE 12.,"Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/20752,Electrical,Completed,L-Electrical,166,4685900,"Erection of 31 nos 6 mtrs GI Lamp posts with single straight bracket with 40-50 watts LED fittings, 30 nos of 7 mtrs GI Lamp posts with Double arch bracket with 90-120 watts LED fittings and 5 nos of GI Lamp posts with single straight bracket with 90-120 watts LED fittings at various streets in DIV 166 in Zone - 12.","Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/21184,Electrical,Completed,L-Electrical,169,4905100,"Replacement of damaged post, cable, fuse box, and 40W LED Fitting in various divisions during flood in Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/21857,Electrical,Completed,L-Electrical,138,2067500,"Erection of 14 nos of 6 mtr Hot Dip Galvanising post with Single arch Bracket with 150w-165w LED Fittings ,and others at Jawaharlal Nehru salai Bridge near Kasi Theater, Jafferkhan pet in Division-138, Zone-X",Own Sources,10,2015-16,2019-20 L/2015-16/22441,Electrical,Completed,L-Electrical,16,31992500,Provision of new lamp post,"Loans, Grants And Own Sources",2,2015-16,2016-17 L/2015-16/22442,Electrical,Completed,L-Electrical,17,16753700,Provision of new lamp post,"Loans, Grants And Own Sources",2,2015-16,2016-17 L/2015-16/22710,Electrical,Completed,L-Electrical,79,1859900,Laying of 1570 Mtrs of 2x16 Sq.mm Alu Cable & 3385 Mtrs of 4x16 Sq.mm Alu Cable at Various Locations in Divisions 79 to 93 in Zone-VII,Own Sources,7,2015-16,2016-17 L/2015-16/22753,Electrical,Completed,L-Electrical,180,4996000,SUPPLY AND LAYING OF 4685 MTRS OF 2X16 SQ.MM ALU CABLE AND 7756 MTRS OF 4X16 SQ.MM ALU CABLE AND SUPPLY AND FIXING OF 5 NOS OF 40-50W LED FITTING AT VARIOUS LOCATIONS IN DIV 170 & 172 TO 177 & 179 TO 182 IN ZONE-XIII,Own Sources,13,2015-16,2017-18 L/2015-16/22792,Electrical,Completed,L-Electrical,49,4940000,Restoration of UG Cable and Piller Box damaged due to Flood at various places in Zone 5 .,Own Sources,5,2015-16,2016-17 L/2015-16/23075,Electrical,Completed,L-Electrical,104,2714900,Restoration of U G cables damaged due to Flood at Zone - VIII area.,Own Sources,8,2015-16,2016-17 L/2015-16/23235,Electrical,Completed,L-Electrical,139,4887000,"Work: Supply and Erection of 170 nos of 6 mtr Department supply lamp post with Single st Bracket at flood affected areas in division on-139, Zone-X.",Own Sources,10,2015-16,2016-17 L/2015-16/23294,Electrical,Completed,L-Electrical,156,4040600,Restoration of underground cables and pillar boxes damaged due to flood at various places in Zone XII.,Own Sources,12,2015-16,2017-18 L/2015-16/23305,Electrical,Completed,L-Electrical,142,4558600,"Work:supply and Erection of 100 nos of 6 mtr Department supply st with Bracket at flood affected areas in division on-140, 142 Zone-X.",Own Sources,10,2015-16,2016-17 L/2015-16/23321,Electrical,Completed,L-Electrical,N03,3447100,Temporary restoration of laying of cable & erection of pillar in the damaged locations caused by the flood in various divisions at Zone-III.,Own Sources,,2015-16,2016-17 L/2015-16/23334,Electrical,Completed,L-Electrical,197,4156500,"Restoration of UG cables,pillar boxes & 40-50W LED fittings damaged due to Flood at Various Places in Dn.192 to 200 in Zone-XV",Own Sources,15,2015-16,2016-17 L/2015-16/23406,Electrical,Completed,L-Electrical,64,1574000,Replacement of damaged 16nos of KIOSK Pillar boxes and damaged cables due to storm water bailing out in various places in div 64 to 78 in zone VI,Own Sources,6,2015-16,2016-17 L/2015-16/23424,Electrical,Completed,L-Electrical,9,1055200,"Provision of 14 nos. of 3phase Analogue Timer, 6 nos. of KIOSK Pillar, 1025 mtrs of 2x16 alu. Cable and 675 mtrs of 4x16 alu cable in flood affected and damaged areas in Zone-I [SOR-2015-16]",Own Sources,1,2015-16,2016-17 L/2015-16/23847,Electrical,Completed,L-Electrical,145,4761100,"REPLACEMENT OF DAMAGED CABLE ,PILLAR AND 40 LED FITTINGS IN VARIOUS DIVISIONS FROM 143 TO 155 DURING FLOODING IN ZONE XI",Own Sources,11,2015-16,2016-17 L/2015-16/24561,Electrical,Completed,L-Electrical,182,198000,"PAINTING OF 866 NOS OF LAMP POST ANDNUMBERING OF 2532 NOS OF LAMP POST AND PAINTING OF 4 NOS OF KIOSK PILLAR BOX AT VARIOUS LOCATIONS AT THIRUVANMIYUR IN DIV-181 & 182, ZONE-XIII",Own Sources,13,2015-16,2017-18 L/2015-16/2458,Electrical,Completed,L-Electrical,163,6947100,"Erection of 30 nos of 6mtr GI lamp posts with straight bracket , 22 nos of 8 mtr octogonal post with double arch bracket, 30 nos of 6m GI octogonal lamp post with 74 nos of 150 to 165 watts LED fittings, 70 nos of 40-50W LED Fittings at various places in div 163 and Removal of 17 nos of 6m MS lamp post with 250W SV fittings at St Thomas Mount Subway in division 163 in zone XII. (Sch of rate 2014-15)","Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/2459,Electrical,Completed,L-Electrical,162,8835400,"Erection of 64 nos of 6mtr GI Octogonal lamp posts with double bracket, 40 nos of 8m GI Octogonal lamp post with straight bracket with 104 Nos of 150 to 165 watts LED fittings, 74 nos of GI single straight bracket with 40-50W LED Fittings at various places in Div 162 and Removal of 11 nos of 6m MS lamp post and 7 nos of 8/9m MS Lamp post with 250W SV fittings in division 162 in zone XII. (Sch of rate 2014-15)","Loans, Grants And Own Sources",12,2015-16,2016-17 L/2015-16/2461,Electrical,Completed,L-Electrical,86,5638000,"Proposed Erection of 111 nos of 6mtr Octagonal Post straight brackets with 40-50W LED fitting and 23nos of 8mtr octagonal post straight brackets with 150-165W LED fitting at Manurpet,Phase-3 Gandhi nagar,Vanagaram road Manthope and various streets in Dn 86","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/2464,Electrical,Completed,L-Electrical,197,8864300,Provision of 40nos of 8Mtr GI Octagonal Lamp post with GI Double bracket with 150-165 watts LED fitting 46Nos of 6Mtr GI Octagonal lamp post with GI Single bracket with 90-120watts LED fittings and 78nos of 6Mtr GI Octagonal lamp post with GI Single bracket with 40-50watts LED fittings at Various Location,"Loans, Grants And Own Sources",15,2015-16,2016-17 L/2015-16/2470,Electrical,Completed,L-Electrical,81,13568900,"Proposed Erection of 70nos of 6mtr GI Octagonal Lamp post straight brackets with 40-50watts LED fitting,26 nos of 8 mtr Octagonal lamp post straight brackets with 90-120 watts LED fitting and 142 nos of 8mtr GI Octagonal lamp post straight brackets with 150-165 watts LED fitting at Cholapuram st,Indira nagar,Pattammal st,Ramdoss st and various streets in Dn 81 Zone VII,Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/2471,Electrical,Completed,L-Electrical,22,4443400,"Provision of 115nos of 6 mtr GI Octoganal lamp post with straight bracket with 40w to 50 w LED Fitting at Ragavendra Nagar, Ramakrishna Nagar and other streets in Division-22 of zone-III (Madhavaram)(Sch of rate 2014-15)","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/2473,Electrical,Completed,L-Electrical,25,4478400,Provision of 115nos of 6 mtr GI Octoganal lamp post with straight bracket with 40w to 50 w LED Fitting at INTUC Nagar and other streets and other streets in Division-25 of zone-III (Madhavaram)(Sch of rate 2014-15),"Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/2479,Electrical,Completed,L-Electrical,33,5889300,"Provision of 121 Nos of 6 mtr GI Octagonal lamp post, single straight bracket with 40w LED fitting and 6 nos of 8 mtr lamp post, arch bracket & 4 nos of 8 mtr lamp post, triple bracket with 150w LED fitting at various locations in Div-33 of Zone-III.","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/2482,Electrical,Completed,L-Electrical,83,19083600,"Proposed erection of 456 nos of 6 Mtr G I Octaganal Lamp Post with Single St Bracket with 40-50 w LED fittings and 40 nos of 8 Mtr G I Octaganal Lamp Post with Sinlgle st Bracket with 90-120 w LED fittings at Sivalinga puram main road , Subulakshmi nagar street,Balaji nagar streets, Rajiv ganthi main road Mahavishnu nagar and other streets in ward 83 Zone VII","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/2484,Electrical,Completed,L-Electrical,80,17289400,"Proposed Erection of 254 nos of 6 Mtr Octagonal G.I Lamp post with Straight Brackets with 40 w to 50 watts LED fitting and 149 nos of 8 Mtr Octagonal G.I Lamp post With Single Bracket with 90 W to 120 W LED fitting at Various Streets in Pudur, Bharathi Nagar, Prakash Nagar & Vijayalakshmipuram in Dn 80 Zone VII, Ambattur","Loans, Grants And Own Sources",7,2015-16,2016-17 L/2015-16/2492,Electrical,Completed,L-Electrical,31,1852900,"Provision of 45Nos of 6mtr G.I Octoganal Lamp post, single straight bracket with 40w LED fitting at Sathiya Raj Nagar and Udhaya Suriyan Nagar in Div.31 of Zone-III","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/25046,Electrical,Completed,L-Electrical,114,188700,"Painting of 603 Nos of 8/9.2 Mtr lamp post at Kamaraj Salai on Both sides from Napier Bridge to Light house and Radhakrishnan Salai, Avvai Shanmugam Salai DR. Besant Road , Santhome high road and Bharathy Salai in Div-114,116,120,121,125 Zone -IX.",Own Sources,9,2015-16,2016-17 L/2015-16/2514,Electrical,Completed,L-Electrical,26,9804000,"Provision of 255 Nos of 6mtr G.I Octagonal Lamp post, single straight bracket with 40w LED fitting at Iyappan Nagar and other streets in Div.26 of Zone-III","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/2516,Electrical,Completed,L-Electrical,30,6657800,"Provision of 174Nos of 6mtr G.I Octagonal Lamp post, single straight bracket with 40w LED fitting at Ring Road Housing sector, Kathirvel Nagar and other streets in Div.30 of Zone-III","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/2531,Electrical,Completed,L-Electrical,183,14747600,"Erection of 354nos of 6 mtr long G.I OCTOGONAL lamp post with straight bracket with 40-50W LED street light fittings set with hot dip zinc galvanising at Various places in Div 183,Kotivakkam, Zone XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/2534,Electrical,Completed,L-Electrical,168,5045600,"Erection of 100Nos of 6Mtr Long GI Octogonal street lamp post with single Straight bracket with 40-50w LED Fitting and 25Nos of 6Mtr Long GI Octogonal street lamp post with single Straight bracket with 90-120w LED Fitting with hot dipping galvanising at Balamal Nagar Main road and cross streets in Division 168,Zone 14","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/2536,Electrical,Completed,L-Electrical,191,15149800,"Erection of 281 nos of 6Mtr long GI Octagonal street lamp post with single straight bracket with 40-50W LED Fitting and 95Nos of 6Mtr long GI Octagonal street lamp post with single straight bracket with 90-120W LED Fitting with hot dip galvanising at various places in Division 191,Zone 14","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/25367,Electrical,Completed,L-Electrical,64,3051200,"Provision of new 2nos of 20mtr High Mast with 200w LED Fitting at newly constructed Grade seperator by department of highways in Jawaharlaal Nehru salai junction of Perambur redhills road and Eratteri Kadappa road in div.64,zone VI(by deposit work)",Deposit Works,6,2015-16,2017-18 L/2015-16/2539,Electrical,Completed,L-Electrical,144,14351400,"Provision of 363 Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket at Mathuranackiyan street,MMDA 7th Block,perumal koil cross streets and various Places in Division 144 Zone XI","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/2540,Electrical,Completed,L-Electrical,146,17988400,"Provision of 461 Nos of 6mtr Lamp Post with 40w LED Fitting on 1 mtr Single straight bracket at Gangaiamman ,Bhakyialakshmi ,Balamurugan,Ganapathy,Iyyapa nagar,south mada street and various Places in Division 146 Zone XI","Loans, Grants And Own Sources",11,2015-16,2016-17 L/2015-16/2553,Electrical,Completed,L-Electrical,186,17023400,"Provision 317 nos of 6 mtr G.I Octagonal lamp post with straight bracket with 40-50W LED street light fittings set and 117 nos of 8 mtr G.I Octagonal lamp post with straight bracket with 90-120W LED street light fittings set at Various places in Div 186,Perungudi, Zone XIV","Loans, Grants And Own Sources",14,2015-16,2016-17 L/2015-16/2566,Electrical,Completed,L-Electrical,29,1476600,"Provision of 33 nos of 6mtr lamp post, single straight bracket with 40w LED fitting at Munuswamy Cross Streets, Perumal Koil Cross Streets and various other streets in Div-29 of Zone-III.","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/2567,Electrical,Completed,L-Electrical,32,1493000,Provision of 39nos of 6mtr GI Lamp post with straight bracket with 40w LED fitting at VOC Street and other streets in DIv-32 of Zone-III.,"Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/2585,Electrical,Completed,L-Electrical,28,7654000,"Provision of 198nos of 6mtr GI Lamp post with single straight bracket with 40w LED fitting at Ganapathy Nagar, Rekha Nagar & various streets in DIv-28 of Zone-III.","Loans, Grants And Own Sources",3,2015-16,2016-17 L/2015-16/26019,Electrical,Completed,L-Electrical,8,991000,"PROVISION OF 18 NOS. OF 8 MTR GI LAMP POST WITH DAB AT TIRUVOTTRIYUR HIGH ROAD FROM VILLAGE STREET TO VIVEKANANDA STREET WITH 250W SVL FITTINGS IN DN-8, ZONE-I",Own Sources,1,2015-16,2016-17 L/2015-16/26089,Electrical,Completed,L-Electrical,42,148000,"Provision of 4 Nos of 6mtr Lamp post with hot dip zinc galvanising with single straight bracket on 40W LED Fitting at Rettaikuzhali Lane in Division 42, Zone IV",Own Sources,4,2015-16,2018-19 L/2015-16/26094,Electrical,Completed,L-Electrical,47,148000,"Provision of 4 Nos of 6mtr Lamp post with hot dip zinc galvanising with single straight bracket on 40W LED Fitting at Kattivakkam High Road in Division 47, Zone IV",Own Sources,4,2015-16,2018-19 L/2015-16/26230,Electrical,Completed,L-Electrical,170,2754000,"Provision of 22nos of 6mtr G.I lamp post with Double Arch Bracket with 150w LED fitting at Nehru Salai (Near Kasi Therater) Kalimagal Nagar Bridge Div-170, Zone-XIII.",Own Sources,13,2015-16,2016-17 L/2015-16/27182,Electrical,Completed,L-Electrical,63,153600,"Replacement of 357mtrs of 2CX16sqmm pvc alu cables at Phycrafts road in div-63,zone5.",Own Sources,5,2015-16,2016-17 L/2015-16/27253,Electrical,Completed,L-Electrical,N02,3148500,Replacement of Damaged cables & pillars during north east monsson natural calamities,Own Sources,,2015-16,2016-17 L/2015-16/27587,Electrical,Completed,L-Electrical,114,867500,"Erection of 7 nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single Arch Bracket with 7 nos 90w-120w LED fitting, 10 nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single straight Bracket with 10 nos 40w-50w LED fitting at Lock Nagar in Division-114,Zone-IX",Deposit-Asset,9,2015-16,2016-17 L/2015-16/27606,Electrical,Completed,L-Electrical,150,469900,"ERECTION & COMMISSIONING OF ONE NUMBER OF 12 MTR OF HIGHMAST LIGHT AT PONNIAMMAN KOIL STREET(PONNIAMMAN KOIL & PARK JUNCTION)-PONNI NAGAR IN DIVISION -150,ZONE-XI",Own Sources,11,2015-16,2016-17 L/2015-16/28058,Electrical,Completed,L-Electrical,177,104300,"Provision of 1 No. of 1KWP Solar Roof Top in CPS school at T.N.H.B Colony, Velachery in Div-177, Zone-XIII",MLACDS,13,2015-16,2018-19 L/2015-16/28059,Electrical,Completed,L-Electrical,178,174600,"Provision of 1 No. of 2KWP Solar Roof Top in CHS School at Rajelakshmi Nagar, Velachery in Div-178, Zone-XIII.",MLACDS,13,2015-16,2018-19 L/2015-16/28061,Electrical,Completed,L-Electrical,180,174600,"Provision of 1 No. of 2KWP Solar Roof Top in CHSS School at Peeliamman Koil Street, Tharamani in Div-180, Zone-XIII.",MLACDS,13,2015-16,2018-19 L/2015-16/2941,Electrical,Completed,L-Electrical,154,191500,"Provision of 3 Nos of 8Mtrs Lamp Post with Double Arch Bkt And 2 Nos of 8Mtrs Lamp Post Post with Triple Arch bkt at Mount Poonamallee Rd From DLF Junction of Hussainy School junction in Div-154,Zone-XI.",Own Sources,11,2015-16,2017-18 L/2015-16/2943,Electrical,Completed,L-Electrical,154,195000,"Provision of 2 Nos of KIOSK Pillar Box with Timer at Mount poonamallee Rd From DLF Junction to Hussainy School Junction in Div-154,Zone-XI",Own Sources,11,2015-16,2017-18 L/2015-16/2966,Electrical,Completed,L-Electrical,7,562300,"Commissioning of 16 mtr high mast with 8 nos. of 2x400w (Metal Halide - Tubular Lamp) asymmetrical flood light fittings complete set at Anna nagar [Railway gate and Junction of Karumariamman Koil], Division-7, Zone-I",MPLADS,1,2015-16,2016-17 L/2015-16/2984,Electrical,Completed,L-Electrical,7,558200,"Commissioning of 16 mtr high mast with 8 nos. of 2x400w (Metal Halide - Tubular Lamp) asymmetrical flood light fittings complete set at Charles nagar [Amman koil junction], Division-7, Zone-I",MPLADS,1,2015-16,2016-17 L/2015-16/3003,Electrical,Completed,L-Electrical,7,562300,"Supply, Installation, aiming, testing and Commissioning of 16 mtr high mast with 8 nos. of 2x400w (Metal Halide - Tubular Lamp) asymmetrical flood light fittings complete set at Football play ground connecting Annamalai nagar and Saravana nagar, Division-7, Zone-I",MPLADS,1,2015-16,2016-17 L/2015-16/3005,Electrical,Completed,L-Electrical,9,554000,"Commissioning of 16 mtr high mast with 8 nos. of 2x400w (Metal Halide - Tubular Lamp) asymmetrical flood light fittings complete set at Thiruvottriyur market area, Division-9, Zone-I",MPLADS,1,2015-16,2016-17 L/2015-16/30183,Electrical,Completed,L-Electrical,176,773500,"Providing 22Nos of EL Lamp posts with 40-50w LED fittings at Orur Kuppam beach road in division-176, Zone-XIII.",Own Sources,13,2015-16,2016-17 L/2015-16/30353,Electrical,Completed,L-Electrical,36,909700,"Replacement of 1996 mtrs of 4X16 sqmm cable at Bharathiyar Street, Radhakrishnan Salai, Thiruvalluvar 3rd Main Road and Thiruvalluvar 1st Main Road in Division 36, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/30370,Electrical,Completed,L-Electrical,36,886600,"Replacement of 1526 mtrs of 2X16 sqmm cable and 568 mtrs of 4X16 sqmm cable at Thiruvalluvar Nagar 1st Link Road and Vivekanandar Nagar 2nd street in Division 36, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/30508,Electrical,Completed,L-Electrical,34,984800,"Replacement of 2185 Mtrs of 4X16 sqmm Cable at Manali Salai and School Road in Division 34, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/31045,Electrical,Completed,L-Electrical,175,175100,"REMOVAL AND RE-FIXING OF 28NOS OF STREET LAMP POSTS AT VARIOUS LOCATIONS IN DIVISIONS-173,175 AND 176 IN ZONE-13",Own Sources,13,2015-16,2016-17 L/2015-16/31284,Electrical,Completed,L-Electrical,173,196000,"Removal and Re-fixing of 31nos of street lamp posts at various locations in divisions 173,175 and 176 in Zone-13",Own Sources,13,2015-16,2016-17 L/2015-16/31371,Electrical,Completed,L-Electrical,172,1325000,"Providing 20Nos of 6mtr Lamp post with single straight bracket with 40w-50w LED fittings and conversion of 16Nos of 70w SV lamp into 40w-50w LED fittings at Kotturpuram Housing Board area in Div-172, Zone-13",Deposit Works,13,2015-16,2016-17 L/2015-16/6207,Electrical,Completed,L-Electrical,107,870100,"Provision of 10KWP Solar Roof Top System with Solar Photo Voltaic Panels,Power Conditioning unit AC & DC Surge protection Devices,Electrical wiring for Grid tie system as per th requirement of TEDA / MNRE at Horington Road Community Hall in division-107",MLACDS,8,2015-16,2018-19 L/2015-16/6638,Electrical,Completed,L-Electrical,92,4406600,"Proposed erection of 36 nos of 8mtr long octagonal lamp post on Double Bracket with 150-165w LED fitting at Mogapair CHURCH STREET in Division 92, Zone VII",Own Sources,7,2015-16,2017-18 L/2015-16/6647,Electrical,Completed,L-Electrical,91,2807300,"Proposed erection of 33nos of 6mtrhot dip zinc galvanisingglamp post with 90-120w LED fittings on DOUBLE ARCH Bracket and 3nos of 6mtr hot dip zinc galvanisingglamp post with 90-120w LED fittings on triple arch bracket at Mogapair 3rd main road in Division 91, Zone VII",Own Sources,7,2015-16,2017-18 L/2015-16/6650,Electrical,Completed,L-Electrical,60,518200,Supply and fixing of 40-50 W LED Fitting and Laying of 320 Mtr of 2Cx10 Sqmm PVC Alu Cable at Napier Bridge in Dn 60 Z 5,Own Sources,5,2015-16,2016-17 L/2015-16/7047,Electrical,Completed,L-Electrical,34,889000,"Provision of 4nos of 8mtr long G.I.Octagonal Street Lamp Post with 16nos of 165w LED Fitting at Manali Road,School Road,Narayanasamy Garden and Gandhi Nagar in Division 34.Kodungaiyur, Zone.IV.",Own Sources,4,2015-16,2017-18 L/2015-16/7060,Electrical,Completed,L-Electrical,34,661700,"Provision of 3nos of 8mtr long G.I.Octagonal Street Lamp Post with 12nos of 165w LED Fitting at Seetharam Nagar, Eveready Colony and Eveready Colony 14th Street in Division 34.Kodungaiyur, Zone.IV.",Own Sources,4,2015-16,2017-18 L/2015-16/7063,Electrical,Completed,L-Electrical,43,3648600,"Provision of 41 Nos. of 8 Mtr G.I Octagonal Lamp Post with Single Bracket with 150W to 165 W LED Fitting at Surya Narayana street, Western Side ( From Jeevarathinam Salai to Balakrishnan Street Junction) in Dn;43, Zone IV. ( R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7065,Electrical,Completed,L-Electrical,34,889000,"Provision of 4nos of 8mtr long GI Octagonal Street Lamp post with 16nos of 165w LED fitting at Kadumpadi Amman Koil Street, Jumbuli Street, Jumbuli New Colony and Solai Amman Koil Street in Division 34 Kodungaiyur,Zone.IV.",Own Sources,4,2015-16,2017-18 L/2015-16/7066,Electrical,Completed,L-Electrical,34,661700,"Provision of 3nos of 8mtr long GI.Octagonal Street lamp post with 12nos of 165w LED fitting at Riswan Road, Kattabomman Street and NSK Salai in Division 34, Kdungaiyur, Zone.IV.",Own Sources,4,2015-16,2017-18 L/2015-16/7082,Electrical,Completed,L-Electrical,41,3573400,"Estimate for provision of 38 nos of 8 mtr GI Octogonal Lamp Post with Single Bracket with 165W LED Fittiing at Manali Salai, Ennore High Road in Division 41, Zone iv. (R.K. NAGAR CONSTITUTENCY) Phase I.",Own Sources,4,2015-16,2016-17 L/2015-16/7090,Electrical,Completed,L-Electrical,41,1688000,"Provision of 36 Nos of 6 Mtr Street Lamp Post with Hot dip zinc galvanising with single straight bracket with 40w led fitting at Lime Kiln Road, Pumping Road, Thoppai Vinyagar Street in div 41 zone IV (RK NAGAR CONSTITUTENCY)",Own Sources,4,2015-16,2016-17 L/2015-16/7092,Electrical,Completed,L-Electrical,37,879400,"Replacement of 2221mtrs 2x16 sqmm Cable at Subramaniyam st,Lourd mada st,Srinivasan st, Jawhar st,Ambedkar st, Valluvar street in Division 37,Zone IV.",Own Sources,4,2015-16,2016-17 L/2015-16/7095,Electrical,Completed,L-Electrical,37,962400,"Replacement of 2354mtrs 2x16 sqmm Cable at Gandhi st, Bose st, Nawaraj st, Anna st, Saravanan st, Lingesan st, Selvaraj st, Linen st, Susila st, Anbazhagan street in Division 37,Zone IV.",Own Sources,4,2015-16,2016-17 L/2015-16/7096,Electrical,Completed,L-Electrical,37,991200,"Replacement of 2382 mtrs 2x16 sqmm Cable at Vivekananda st, Annai sthya nagar, Palani st, Balaji st, Sarvapalli st,Balakrishnan st, Vanjinathan st, Kannan st, Thayagarajan street in Division 37,Zone IV.",Own Sources,4,2015-16,2016-17 L/2015-16/7098,Electrical,Completed,L-Electrical,37,709000,"Replacement of 1738 mtrs 2x16 sqmm Cable at Padmavathi st, Perumal st, Ambedkar st, Balaji st, Sannathi st, Vedamuthu st, Ganapathy street in Division 37,Zone IV.",Own Sources,4,2015-16,2016-17 L/2015-16/7100,Electrical,Completed,L-Electrical,44,945000,"Replacement of 2308 mtrs 2x16 sqmm Cable at Kamarajar nagar, Anna nagar, and Surrounding area in Division 44,Zone IV.",Own Sources,4,2015-16,2016-17 L/2015-16/7105,Electrical,Completed,L-Electrical,42,2845600,Provision of 32 Nos of 8 Mtr GI Octogonal Lamp Post with Single Bracket with 165W LED Fitting at THRoad East Side in div 42. Zone IV (RKNAGAR CONSTITUTENCY),Own Sources,4,2015-16,2016-17 L/2015-16/7135,Electrical,Completed,L-Electrical,45,985000,"Replacement of 2600 mtrs of 2x16sqmm cable at BV Colony 9 to 18 streets in Division 45,Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/7141,Electrical,Completed,L-Electrical,45,992100,"Replacement of 2505 mtrs of 2x16sqmm cable ta BV Colony 19 to 28 streets in Division 45,Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/7157,Electrical,Completed,L-Electrical,76,874800,"Provision of laying of 1834 mtrs of 4x16 sq.mm.pvc alu. cable with additional works in the existing lamp post for replacing the 150 watts LED Fitting at Strahans road div.76,zone-6.",Own Sources,6,2015-16,2016-17 L/2015-16/7170,Electrical,Completed,L-Electrical,24,920000,"Provision of 20 nos of 6 mtr lamp post with straight bracket WITH Hot dip zinc galvanising with 40w to 50 w LED Fitting at Thirumal Nagar 21st,22nd street and 2nd Main Raod in Division-24 of zone-III",Own Sources,3,2015-16,2016-17 L/2015-16/7171,Electrical,Completed,L-Electrical,25,758900,"Provision of 19nos of 6 mtr lamp post with straight bracket WITH Hot dip zinc galvanising with 40w to 50 w LED Fitting at Sathya moorty Nagar 1st, 2nd and 3rd street in Division-25 of zone-III",Own Sources,3,2015-16,2016-17 L/2015-16/7172,Electrical,Completed,L-Electrical,25,821000,"Provision of 18nos of 6 mtr lamp post with straight bracket WITH Hot dip zinc galvanising with 40w to 50 w LED Fitting at Sathyamoorty Nagar 4th,5th and 6th street in Division-25 of zone-III",Own Sources,3,2015-16,2016-17 L/2015-16/7173,Electrical,Completed,L-Electrical,25,874000,Provision of 22nos of 6 mtr of 6 mtr lamp post with straight bracket WITH Hot dip zinc galvanising with 40w to 50 w LED Fitting at Rasi Nagar in Division-25 of zone-III,Own Sources,3,2015-16,2016-17 L/2015-16/7176,Electrical,Completed,L-Electrical,43,2674300,"Provision of 30 Nos. of 8 Mtr G.I Octagonal Lamp Post with Single Bracket with 150W to 165W LED Fitting at Surya Narayana Street, Eastern Side ( From Jeevarathinam Salai to Balakrishanan Street Junction) in Dn:43, Zone IV.( R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7178,Electrical,Completed,L-Electrical,40,2218800,"Provision of 25 Nos. of 8 Mtr G.I Octagonal Lamp Post with Single Bracket with 150W to 165W LED Fitting at Kamaraj Salai in Dn:40, Zone IV. ( R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7186,Electrical,Completed,L-Electrical,38,1622500,"Provision of 36 Nos. of 6 Mtr Street Lamp Post with Hot dip zinc galvanising with Single Bracket with 40W LED Fitting at Nethaji Nagar 4th Street in Dn:38, Zone IV. (R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7222,Electrical,Completed,L-Electrical,42,2742700,"Provision of 31 Nos of 8 Mtr GI Octogonal Lamp Post on Single Straight Bracket with 165W LED Fitting at TH Road Western Side in Division 42, Zone IV (RK NAGAR CONSTITUTENCY)",Own Sources,4,2015-16,2016-17 L/2015-16/7240,Electrical,Completed,L-Electrical,40,3360200,"Provision of 76 Nos. of 6 Mtr Street Lamp Post wtih Hot dip zinc galvanising with Single Straight Bracket with 40W LED Fitting at V.O.C Nagar 18th Street to 28th Street in Dn:40, Zone IV. ( R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7289,Electrical,Completed,L-Electrical,38,3676400,"Provision of 42 Nos of 8 Mtr GI Octagonal Lamp Post with Single Bracket with 150W to 165 W LED Fitting at Ennore High Road ( From Vaidyanathan Bridge to IOC Bus Stand) in Dn:38, ZOne IV. ( R.K Nagar Constitueny).",Own Sources,4,2015-16,2017-18 L/2015-16/7298,Electrical,Completed,L-Electrical,42,1474100,"Provision of 33Nos of 6Mtr Street Lamp Post with Hot Dip Zinc Galvanising with Single Straight Bracket with 40W LED Fitting at Rettairuzhai street and Lane in Div 42, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/7304,Electrical,Completed,L-Electrical,43,2737200,"Provision of 31 Nos.of 8 Mtr G.I Octagonal Lamp Post with Single Bracket with 150W to 165W LED Fitting at Kummallamman Koil St and Jeevarathinam Salai in Dn:43, Zone IV. ( R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7306,Electrical,Completed,L-Electrical,47,2199800,"Provision of 25 Nos of 8Mtr GI Octagonal Lamp Post on single bracket with 165W LED Fitting at Kannan Street in Div 47, Zone Iv ( RK Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7312,Electrical,Completed,L-Electrical,47,1500100,"Provision of 33 Nos of 6Mtr Street Lamp Post with hot dip zinc galvanising on single straight bracket with 40W LED Fitting at Thangavel Pillai Thottam 1 to 3 streets, Karpagavinayagar street, Madurai Muthu Street in Div 47, Zone IV (Rk Nagar Constitucency)",Own Sources,4,2015-16,2016-17 L/2015-16/7315,Electrical,Completed,L-Electrical,47,1623300,"Provision of 36 Nos of 6Mtr Street Lamp Post with Hot dip zinc galvanising on single straight bracket with 40W LED Fitting at RK Nagar 1 to 3 Streets in Div 47, Zone IV(RK Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7367,Electrical,Completed,L-Electrical,58,479922,"Laying of 300Sqmm XLPE Cables from proposed busbar pillar box to Ripon Heritage Building in Ripon Building premises in Div. 58, Zone V.",Own Sources,5,2015-16,2016-17 L/2015-16/7380,Electrical,Completed,L-Electrical,58,652600,"Provision of 300Sqmm XLPE Cables from Ripon Annex building to proposed busbar pillar box near Revenue Department in the Ripon Building premises in Div. 58, Zone V.",Own Sources,5,2015-16,2016-17 L/2015-16/7387,Electrical,Completed,L-Electrical,58,981900,"Provision of 240Sqmm XLPE Cable from Ripon annex building to RD Block and Engg. Block in the Ripon building premises in Div 58, Zone V.",Own Sources,5,2015-16,2018-19 L/2015-16/7418,Electrical,Completed,L-Electrical,39,961800,"Provison of 1 No. of 20 Mtr Highmast with 12 Nos of 2 x 400W Fitting (Metal Halide - Tubular Lamp) at Surya Narayana Street, junction of Poondhithangammal St Dn:39, Zone IV.( R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7421,Electrical,Completed,L-Electrical,39,934700,"Provision of 1 No. of 20 Mtr Highmast with 12 Nos of 2 x 400W Fitting (Metal Halide - Tubular Lamp) at T.H Road, junction of Tolgate Bus Stand in Dn:39, Zone IV. ( R.K Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/7426,Electrical,Completed,L-Electrical,58,970700,"Provision of 36No's of 100mm dia 3Mtr long cast iron earth electrode,50x6mm GI flat,25x6mmGI flat and earth links for Ripon building Heritage,Golden jubilee hall,Revenue dept Building and Engineering block in Ripon building premises in Div-58,Zone-5",Own Sources,5,2015-16,2016-17 L/2015-16/7643,Electrical,Completed,L-Electrical,42,1228500,"Provision of 22 Nos of 6Mtr street Lamp Post with hot dip zinc galvanising with single Arch Bracket with 90W LED Fitting at Rathinasabapathy Street, in Div 42, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/7656,Electrical,Completed,L-Electrical,41,2471800,"Provision of 24Nos of 8 Mtr GI Octagonal Lamp post on single Bracket with 165W LED Fitting at Manali Salai Phase-2, Div 41, Zone IV (RK NAGAR CONSTITUENCY)",Own Sources,4,2015-16,2016-17 L/2015-16/7657,Electrical,Completed,L-Electrical,41,2070200,"Provision of 23 Nos of 8Mtr GI Octagonal Lamp post on single bracket with 165W LED Fitting at Manali Salai Phase III,Din 41,Zone IV (RK NAGAR CONSTITUENCY)",Own Sources,4,2015-16,2016-17 L/2015-16/7853,Electrical,Completed,L-Electrical,58,673400,Replacement of 1260mtrs 4CX16 sq.mm PVC ALU cable at Valiammal Street in Division-58 under the control of Zone-05.,Own Sources,5,2015-16,2016-17 L/2015-16/7863,Electrical,Completed,L-Electrical,43,2265000,"Provision of 52 nos. of 6mtr. G.I Lamp post with 40 watts LED Fitting on straight bracket at Communicable disease hospital in division 43,zone 4",Deposit-Asset,4,2015-16,2016-17 L/2015-16/7970,Electrical,Completed,L-Electrical,60,3245000,"Supply and instalation of 27 nos of 8mtr G.I.Lamp post with 2.7mtr Double Arch bracket at Rajaji salai (From Collecter Office to Clive Battery bridge) in Division-60, Zone-5",Own Sources,5,2015-16,2017-18 L/2015-16/8040,Electrical,Completed,L-Electrical,61,995300,"Replacement of 738mtrs of 2C x 16 Sq.mm PVC Alu cable and 215mtrs 4cX16 sq.mm cable for motor room and 23 nos 40-50w LED fittings with new 6 mtrs lamp post set with hot dip galavanising at lagans Garden park in Division-61, under Zone-V.",Own Sources,5,2015-16,2016-17 L/2015-16/8051,Electrical,Completed,L-Electrical,171,839000,"Replacement of 1565mtrs of 31/2c x 25sqmm cable in place of damaged 4cx25sqmm cables at Sardarpatel road (from the junction of RajBhavan to the junction of Sardarpatel fly Over Bridge near IIT) in Div-171, Zone-13.",Own Sources,13,2015-16,2016-17 L/2015-16/8055,Electrical,Completed,L-Electrical,171,837000,Replacement of 685mtrs of 31/2c x 25sqmm cable in place of damaged 4cx25sqmm cables at Sardarpatel road (from the junction of IIT bridge to the junction of Madhya Kailash temple) in Div-172 Zone-13.,Own Sources,13,2015-16,2016-17 L/2015-16/8063,Electrical,Completed,L-Electrical,171,986000,"Replacement of 1640mtr of 3 1/2cx125sq.mm cable at Anna salai Junction of Chemiers Road to Anna salai Junction of CIT 3RD Main Road in (K.B Nagar Section) Div-171, Zone-XIII.",Own Sources,13,2015-16,2016-17 L/2015-16/8064,Electrical,Completed,L-Electrical,171,997500,"Replacement of 1585mtr of 3 1/2 cx25sq.mm cable at Anna salai JN of CIT 3RD Main Road to Anna salai JN of saidapet Arch in (K.B Nagar Section) Div-171, Zone-XIII.",Own Sources,13,2015-16,2016-17 L/2015-16/8070,Electrical,Completed,L-Electrical,180,671000,"REPLACEMENT OF 1372 MTRS OF 4CX16SQ.MM ALU CABLE AT L.B ROAD, THIRUVANMIYUR IN DIV-180, ZONE-XIII",Own Sources,13,2015-16,2017-18 L/2015-16/8083,Electrical,Completed,L-Electrical,41,776600,"Provision 1 No of 16Mtr High Mast with 8 Nos of 2x400W Fitting (Metal Hallide - tubular Lamp) at Manali Salai, Div-41, Zone IV, (RK NAGAR CONSTITUENCY)",Own Sources,4,2015-16,2016-17 L/2015-16/8084,Electrical,Completed,L-Electrical,47,511200,"Provision of 2 Nos of 8 Mtr GI Octagonal Street Lamp post with 8 No of 165 W LED Fitting at Bharathi Nagar HB, Ambedkar Nagar 3rd Street in Div 47, Zone IV(RK NAGAR CONSITUTENCY)",Own Sources,4,2015-16,2016-17 L/2015-16/8198,Electrical,Completed,L-Electrical,188,835100,"PROVISION OF 20 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT PERIYAR NAGAR 1ST AND 2ND ST IN DIVISION - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 L/2015-16/8205,Electrical,Completed,L-Electrical,188,813800,"PROVISION OF 18 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT PERIYAR NAGAR 9TH AND 10TH STREET IN DIVISION - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 L/2015-16/8207,Electrical,Completed,L-Electrical,188,871600,"PROVISION OF 22 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT PERIYAR NAGAR MAIN ROAD AND 8TH STREET IN DIVISION - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 L/2015-16/8208,Electrical,Completed,L-Electrical,188,888000,"PROVISION OF 21 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT PERIYAR NAGAR EXTN 1ST STREET IN DIVISION - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 L/2015-16/8209,Electrical,Completed,L-Electrical,188,722100,"PROVISION OF 16 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT PERIYAR NAGAR EXTN SIGAMANI NAGAR EXTN IN DIVISION - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 L/2015-16/8210,Electrical,Completed,L-Electrical,188,832600,"PROVISION OF 18 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT PERIYAR NAGAR EXTN KANCHI KAMATCHI NAGAR IN DIVISION - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 L/2015-16/8211,Electrical,Completed,L-Electrical,183,973800,"Provision of 20 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting AND 2 nos of 6 Mtr lamp post with Single straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at JUDGES COLONY in Division-183, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8213,Electrical,Completed,L-Electrical,183,969300,"Provision of 17nos of 6 Mtr lamp post with Single Arch Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Sathya Nagar Main Road in Division-183, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8219,Electrical,Completed,L-Electrical,185,487400,"Provision of 12 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting and with hot dip zinc galvanising at Govindan Nagar 1st, 7th,1st ,cross streets in Division-185, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8225,Electrical,Completed,L-Electrical,188,691600,"PROVISION OF 17 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT PERIYAR NAGAR EXTN 3RD CROSS ST IN DN-188, UN - 42, Z - 14",Own Sources,14,2015-16,2016-17 L/2015-16/8228,Electrical,Completed,L-Electrical,134,610000,"Erection of 12 nos of 6mtr Octagonal Post wit LED Fitting at Station Road,Kodambakkam in Divsion 134,Zone-X",Own Sources,10,2015-16,2016-17 L/2015-16/8231,Electrical,Completed,L-Electrical,130,664000,"Erection of 12 nos of 6mtr Octagonal Post wit LED Fitting at Palani Andavar koil st in Divsion 130,Zone-X",Own Sources,10,2015-16,2016-17 L/2015-16/8282,Electrical,Completed,L-Electrical,97,670089,"SUPPLY , ERRECTION AND COMMISIONING OF 1 NO OF 16 MTR HIGH MAST AT SOLAI AMMAN KOIL PLAY GROUND IN DIVISION -97 , UNDER ZONE - VIII AREA",MPLADS,8,2015-16,2017-18 L/2015-16/8285,Electrical,Completed,L-Electrical,57,989300,"Supply and Erection of 25 nos of 7Mtr Lamp post with straight bracket,, and 25 nos of 40 to 50 W LED fitting and Laying of 807mtr 2x16sqmm kalyanapuram housing board in Dn-57, Zone-5.",Own Sources,5,2015-16,2016-17 L/2015-16/8290,Electrical,Completed,L-Electrical,168,846700,"Provision of 3 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting and 12 nos of 6 Mtr lamp post with Single Straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Balammal Nagar main road phase-1 in Division-168, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8291,Electrical,Completed,L-Electrical,168,736500,"Provision of 1 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting and 14 nos of 6 Mtr lamp post with Single Straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Balammal Nagar main road phase-2 in Division-168, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8293,Electrical,Completed,L-Electrical,168,803800,"Provision of 5 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting and 10 nos of 6 Mtr lamp post with Single Straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Balammal Nagar main road phase-3 in Division-168, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8295,Electrical,Completed,L-Electrical,169,807700,"Provision of 4 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting and 11 nos of 6 Mtr lamp post with Single Straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Senghainiamman Koil Street phase-1 in Division-169, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8315,Electrical,Completed,L-Electrical,104,627770,"Supply, Erection and Commisioning of 1no of 16 mtr High mast at Flowers Road JNn of Dr.Alagappa Road in .Div-104 , Zone -VIII area.",MPLADS,8,2015-16,2017-18 L/2015-16/8383,Electrical,Completed,L-Electrical,169,610300,"Provision of 15 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting with hot dip zinc galvanising at Senghainiamman Koil Street in Division-169, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8384,Electrical,Completed,L-Electrical,169,821500,"Provision of 15 nos of 6 Mtr lamp post with Single straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Senghainiamman Koil Street phase-3 in Division-169, Z-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8385,Electrical,Completed,L-Electrical,169,821300,"Provision of 20 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting with hot dip zinc galvanising at Jayalakshmi Nagar in Division-169, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8389,Electrical,Completed,L-Electrical,190,981300,"Provision of 10 nos of 6 Mtr lamp post with Single straight Bracket with 40w-50w LED Fitting and 10 nos of 6 Mtr lamp post with Single Straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Bhavaniamman Koil Street and Nehru Street in Division-190, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/8510,Electrical,Completed,L-Electrical,107,469811,"Provision for Supply,Erection and Commissioning 1no of 12mtr High mast at Horington Road Junction of Venkatachalapathy street (Near Community Hall) in Division-107,Zone-VIII area.",MPLADS,8,2015-16,2016-17 L/2015-16/8561,Electrical,Completed,L-Electrical,105,627770,"PROVISION OF 16 MTR HIGHMAST LIGHT WITH 8 NOS OF 2X400W MH FITTING C.SET AT EVR SALAI IN JN OF THIRUVEETHIAMMAN KOIL STREET IN DIV-105,ZONE-8",MPLADS,8,2015-16,2017-18 L/2015-16/8588,Electrical,Completed,L-Electrical,38,959900,"Replacement of 1884Mtrs of 4x 16 Sqmm PVC Alu. Cable at Ellayamudali Street ( From Cross Road junction to Vaidynathan Bridge junction) in Dn:38, Zone IV. ( R.K Nagar Constituency).",Own Sources,4,2015-16,2016-17 L/2015-16/8626,Electrical,Completed,L-Electrical,41,843600,"Replacement of 1840mtrs of 2X16sq.mm cable at Kannagi Nagar and MGR Nagar 1 to 4 Street in Division-41, Zone-04.",Own Sources,4,2015-16,2016-17 L/2015-16/8902,Electrical,Completed,L-Electrical,58,230000,"Electrification work at Ripon building Ground floor Financial adviser office,Recorder section third floor and Council hall at Ripon building",Own Sources,5,2015-16,2016-17 L/2015-16/8920,Electrical,Completed,L-Electrical,94,469811,"Supply,Erection and Commisioning of 1no of 12 mtr High mast at Rajamangalam police booth,narth jaganatha nagar indira nagar junction in villivakkam .Div-94 , Zone -VIII",MPLADS,8,2015-16,2016-17 L/2015-16/8972,Electrical,Completed,L-Electrical,167,145000,REPLACEMENT OF TIMERS,Own Sources,12,2015-16,2016-17 L/2015-16/8974,Electrical,Completed,L-Electrical,165,193300,REPLACEMENT OF TIMERS,Own Sources,12,2015-16,2016-17 L/2015-16/9017,Electrical,Completed,L-Electrical,41,650000,"Supply and fixing of 36 Nos of Timer Units in Div 41,42,47,48. Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/9019,Electrical,Completed,L-Electrical,41,943700,"Replacement of 2365 mtrs 2X16sq.mm cable at Karumariamman Nagar, Gopal Reddy Nagar in Division-41, Zone-04.(R.K.Nagar Constituency).",Own Sources,4,2015-16,2016-17 L/2015-16/9064,Electrical,Completed,L-Electrical,66,885700,"Provision and laying of 11 nos of rust eatened lamp post and replacement of damaged 2x16 sqmm U.G Cable at S.R.P Colony Ist to 8 street in div 66 of zone6.",Own Sources,6,2015-16,2017-18 L/2015-16/9088,Electrical,Completed,L-Electrical,41,979900,"Replacement of 2086mtrs of 2X16sq.mm cable at Ezhil Nagar B Block, R.K.Nagar Constitution in Division-41, Zone-04",Own Sources,4,2015-16,2016-17 L/2015-16/9089,Electrical,Completed,L-Electrical,41,965500,"Replacement of 2401mtrs of 2X16sq.mm cable at Chandra Sekar Nagar and Kumaran Nagar, R.K.Nagar Constitution in Division-41, Zone-04",Own Sources,4,2015-16,2016-17 L/2015-16/9095,Electrical,Completed,L-Electrical,38,902800,"Supply and fixing of 50 Nos. of Timer Units in Dn:38,39,40 & 43, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/9143,Electrical,Completed,L-Electrical,74,1181200,Provision of 31 nos of 7 mtr GI Lamp post with single straight bracket with 40-50W led fitting at sathyavanimuthu nagar in div 74 of zone6.,Deposit Works,6,2015-16,2016-17 L/2015-16/9169,Electrical,Completed,L-Electrical,43,199300,"Replacement of 386 Mtrs of 4 x 16 Sqmm PVC Alu.Cable at Surya Narayana Street Center Median in Dn:43, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/9215,Electrical,Completed,L-Electrical,43,604200,"Replacement of 1341 Mtrs of 2 x 16 Sqmm PVC Alu.Cable at Kasima Nagar in Dn:43, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/9283,Electrical,Completed,L-Electrical,189,172100,"Replacement of cable 248 mtrs of 3 1/2 X25 sqmm ALU.UG.Cable at RADIAL ROAD in Div - 189, Zone-XIV, Area.",Own Sources,14,2015-16,2016-17 L/2015-16/9284,Electrical,Completed,L-Electrical,189,163200,"Replacement of cable 302 mtrs of 3 1/2 X25 sqmm ALU.UG.Cable at RADIAL ROAD in Div - 189, Zone-XIV, Area.",Own Sources,14,2015-16,2016-17 L/2015-16/9292,Electrical,Completed,L-Electrical,40,744500,"Replacement of 1098 Mtrs of 2 x 16 Sqmm PVC Alu.Cable at Thiruvalluvar Nagar, Phase I in Dn:40, Zone IV.",Own Sources,4,2015-16,2016-17 L/2015-16/9335,Electrical,Completed,L-Electrical,159,96700,Supply and fixing of 6 Nos of timer units at various locations in divisions 159 and 160 in Zone XII,Own Sources,12,2015-16,2016-17 L/2015-16/9350,Electrical,Completed,L-Electrical,162,145000,Supply and fixing of 9 nos of timer units at various locations in divisions 162 and 163 in Zone XII.,Own Sources,12,2015-16,2016-17 L/2015-16/9380,Electrical,Completed,L-Electrical,39,720300,"Replacement of 1416 Mtrs of 2 x16 Sqmm PVC Alu.Cable at Poondhithangammal St in Dn:39, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/9486,Electrical,Completed,L-Electrical,134,535000,"Replacement of 1240 mtr Cable at N.S.K.Salai from Kodambakkam Bridge to Ambedkar salai jun in Division-134, Zone-X.",Own Sources,10,2015-16,2016-17 L/2015-16/9505,Electrical,Completed,L-Electrical,39,439800,"Replacement of 749 Nos. of 4 x 16 Sqmm PVC Alu.Cable at A.A Scheme Road in Dn :39, Zone IV",Own Sources,4,2015-16,2016-17 L/2015-16/9554,Electrical,Completed,L-Electrical,41,674600,"Replacement of 1453 Mtrs of 2x16 sq mm Cable at MGR Nagar, Rickshaw Colony in division-41, Zone -4 ( RK Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/9557,Electrical,Completed,L-Electrical,41,926800,"Replacement of 2204 Mtrs of 2x16 sqmm Cable at MGR Nagar, Kamaraj salai, Anna salai in Division -41, zone IV",Own Sources,4,2015-16,2018-19 L/2015-16/9563,Electrical,Completed,L-Electrical,41,704900,"Replacement of 1501 Mtrs of 2x16 sqmm Cable at Ezhil Nagar A Block in Division in 41, Zone 4 (RK Nagar Constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/9565,Electrical,Completed,L-Electrical,41,664900,"Replacement of 1501 of 2x16 sqmm cable at Ezhil Nagar A Block in division -41, Zone -4 (RK Nagar constituency)",Own Sources,4,2015-16,2016-17 L/2015-16/9568,Electrical,Completed,L-Electrical,41,711500,"Replacement of 1563 Mtrs of 2x16 sqmm Cable at Mupanar Nagar in Division 41, Zone 4 (RK Nagar Consitutency)",Own Sources,4,2015-16,2016-17 L/2015-16/9648,Electrical,Completed,L-Electrical,188,996000,"PROVISION OF 22NOS OF 6MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40W-50W LED FITTING WITH HOT DIP ZINC GALVANISING AT MATHURAKALI NAGAR IN DIVISION - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 L/2015-16/9773,Electrical,Completed,L-Electrical,187,989900,"Provision of 18 nos of 6 Mtr lamp post with Single straight Bracket with 90w-120w LED Fitting with hot dip zinc galvanising at Anna street and Gopal Street in Division-187, Zone-XIV",Own Sources,14,2015-16,2016-17 L/2015-16/9800,Electrical,Completed,L-Electrical,41,993400,"Replacement of 2215 Mtrs 2x16 sqmm Cable at Azeez Nagar, Govindasamy Nagar in division-41, Zone-4",Own Sources,4,2015-16,2016-17 L/2015-16/9803,Electrical,Completed,L-Electrical,41,870400,"Replacement of 2017 Mtrs of 2x16 sqmm Cable at Annai sathya Nagar, in division 41, Zone - 4",Own Sources,4,2015-16,2016-17 L/2015-16/9805,Electrical,Completed,L-Electrical,41,986300,"Replacement of 2479 Mtrs of 2x16 sqmm cable at Cornation Nagar in Division -41, Zone -4",Own Sources,4,2015-16,2016-17 L/2015-16/9838,Electrical,Completed,L-Electrical,62,351900,Solar Roof Top,MLACDS,5,2015-16,2019-20 L/2015-16/9841,Electrical,Completed,L-Electrical,63,351900,Solar Roof Top,MLACDS,5,2015-16,2019-20 L/2015-16/9842,Electrical,Completed,L-Electrical,63,351900,Solar Roof Top,MLACDS,5,2015-16,2019-20 L/2015-16/9843,Electrical,Completed,L-Electrical,63,351900,Solar Roof Top,MLACDS,5,2015-16,2019-20 L/2015-16/9844,Electrical,Completed,L-Electrical,58,870100,Solar Roof Top,MLACDS,5,2015-16,2018-19 L/2015-16/9845,Electrical,Completed,L-Electrical,58,870100,Solar Roof Top,MLACDS,5,2015-16,2018-19 L/2015-16/9846,Electrical,Completed,L-Electrical,58,104300,Solar Roof Top,MLACDS,5,2015-16,2018-19 L/2015-16/9847,Electrical,Completed,L-Electrical,58,104300,Solar Roof Top,MLACDS,5,2015-16,2018-19 L/2015-16/9848,Electrical,Completed,L-Electrical,61,174600,Solar Roof Top,MLACDS,5,2015-16,2018-19 L/2015-16/9849,Electrical,Completed,L-Electrical,61,1820700,High Mast,MPLADS,5,2015-16,2017-18 L/2015-16/9850,Electrical,Completed,L-Electrical,62,485200,High Mast,MPLADS,5,2015-16,2017-18 NA/2015-16/0261,Buildings,Completed,NA-THIRUVOTTIYUR,3,85000,"Additional Works to Anganwadi at Ernavoor Kuppam in Division-03, Unit-01, Zone-01",Own Sources,1,2015-16,2016-17 NA/2015-16/0549,Buildings,Completed,NA-THIRUVOTTIYUR,11,715000,"CHANGE OF ROOF OF THE EXISTING TOILET BLOCK AND IMPROVEMENTS TO TOILET BLOCK AT MARKET LANE CHENNAI PRIMARY SCHOOL IN DN.11, U-3, Z-1. (COUNCILLOR FUND)",Own Sources,1,2015-16,2016-17 NA/2015-16/0554,Buildings,Completed,NA-THIRUVOTTIYUR,11,320000,"PROVIDING CONSTRUCTION OF ADDITIONAL ROOM INSIDE ZONAL OFFICE CAMPUS (GROUND FLOOR ) AT T.H.ROAD IN DN.11, U-3, Z-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/0732,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,246000,"REPAIR AND IMPROVEMENT TO DAMAGED ROAD CROSSING DRAIN @ KALAINGAR NAGAR 10th STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/0824,Buildings,Completed,NA-THIRUVOTTIYUR,4,637000,"Improvements to Open side drain wall raising ,Demolishing and reconstruction of culvert at Mahalakshmi Nagar 1st & 2nd & 3rd street ,Div-4 ,Unit-1,Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/10527,Roads,Completed,NA-THIRUVOTTIYUR,13,667000,"PROVIDING LAYING CEMENT CONCRETE ROAD (USING M30) MUNUSWAMY GARDEN AND IYYAPILLAI THOTTAM 2nd LANE IN DIVISION -13 U-3 Z-1(COUNCILLAR FUND 2015-2016) L-62.00,52.00 W-3.10,2.50 AREA- 322.20",Own Sources,1,2015-16,2016-17 NA/2015-16/11182,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,475000,"Improvements to open side drain & Providing top cover slab @Brindavanagar main road,Div -4,Unit-1,Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/11189,Buildings,Completed,NA-THIRUVOTTIYUR,3,371000,"Construction of Sump with water supply arrangements for Anganwadi No.4 at Ernavoor kuppam in Dn3, U-1, Z-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/11484,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,998000,"PROPOSED CONSTRUCTION OF OPEN SIDE DRAIN AT SARASWATHI NAGAR, 12TH STREET, DIV-6, UNIT-2, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/11523,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,951000,"Raising of Side drain wall at Kamaraj nagar 5th street in Div-2,Unit-1,Zone-1.",Own Sources,1,2015-16,2017-18 NA/2015-16/11530,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,902000,"Raising of side drain wall at Kamaraj nagar 6th and 7thStreets in Div-2,Unit-1.Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/11596,Buildings,Completed,NA-THIRUVOTTIYUR,4,850000,"PROPOSED CONSTRUCTION OF KITCHEN SHED AT RAMANATHAPURAM 10th Street(MIDDLE SCHOOL )DIV -4 UNIT-1,ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/11601,Buildings,Completed,NA-THIRUVOTTIYUR,12,281000,"REPAIRS IMPROVEMENTS WORKS OF AMMA UNAVAGAM AT WEST MADA STREET in Div-12, Unit-3, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/11607,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,9,767000,"Raising and Improvement of Existing Storm water Drain at Village Street ( From TH Road to Sundar Stores) in Dn.9, Unit -2, Zone - 1.",Own Sources,1,2015-16,2016-17 NA/2015-16/11781,Buildings,Completed,NA-THIRUVOTTIYUR,12,335000,"Repair and Improvement works (Chennai primary school) at North pragaram street in Div-12, Unit-3, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/11949,Roads,Completed,NA-THIRUVOTTIYUR,6,606000,"LAYING CEMENT CONCRETE ROAD AT JOTHI NAGAR MAIN CROSS STREET IN DN-06,U-02,ZONE-1.(COUNCILLOR FUND 2015-16).",Own Sources,1,2015-16,2016-17 NA/2015-16/12000,Buildings,Completed,NA-THIRUVOTTIYUR,2,933000,"Improvement works in Shopping complex at (K.H Road) in Div-2,Unit-1,Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/12055,Buildings,Completed,NA-THIRUVOTTIYUR,8,1978000,"DEMOLISHING AND RE CONSTRUCTION OF ANGANWADI BUILDING IN 2ND STREET SP KOIL STREET, IN DIV-08, UNIT-02, ZONE-14",Own Sources,1,2015-16,2016-17 NA/2015-16/12075,Buildings,Completed,NA-THIRUVOTTIYUR,8,855000,"Improvement works in Anganwadi at Bharthi Nagar in Division-08, Unit-02, Zone-01 (Ward Council fund)",Own Sources,1,2015-16,2016-17 NA/2015-16/12253,Buildings,Completed,NA-THIRUVOTTIYUR,14,999000,"Construction of GYM building at Thiyagarayapuram 1st street in Dn-14,Unit-03,Zone-01.( Ward Council Fund)",Own Sources,1,2015-16,2016-17 NA/2015-16/12342,Buildings,Completed,NA-THIRUVOTTIYUR,2,975000,"Construction of new GYM ( Councillor fund) At K.H.Road In Div-2,Unit-1,Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/12495,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,9,833000,"Raising and Improvement of Existing Storm water Drain at Village Street ( From Railway gate to Sundar stores ) in Dn.9, Unit -2, Zone - 1.",Own Sources,1,2015-16,2016-17 NA/2015-16/12498,Buildings,Completed,NA-THIRUVOTTIYUR,9,2642000,"Construction of Compound wall for Burial Ground at Ennore Express Road in Division-09, Unit-02, Zone-01",Own Sources,1,2015-16,2016-17 NA/2015-16/12531,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,435000,"PROPOSED OPEN SIDE DRAIN AT JOTHI NAGAR MAIN CROSS STREET IN DIVISION-06,UNIT-01,ZONE-1 (COUNCILLOR FUND).",Own Sources,1,2015-16,2016-17 NA/2015-16/12634,Culvert,Completed,NA-THIRUVOTTIYUR,6,233000,"DEMOLITION AND RECONSTRUCTION OF CULVERT AT KALAINGAR NAGAR 7TH AND 8TH STREET IN DN-06,U-02,Z-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/12667,Roads,Completed,NA-THIRUVOTTIYUR,3,425000,"Providing Concrete Platform for Garbage bins in Tsunami Quarters at Division-03, Unit-01, Zone-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/12680,Roads,Completed,NA-THIRUVOTTIYUR,3,956000,"Providing & Fixing Street Name Boards(Stainless Steel) in Various Streets at Tsunami Quarters in Division-03, Unit-01, Zone-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/13057,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,194000,"PROPOSED OPEN SIDE DRAIN AT AMBEDKAR NAGAR 7TH STREET IN DN-06, U-02, Z-01.",Own Sources,1,2015-16,2017-18 NA/2015-16/13060,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,279000,"PROVIDING OPEN DRAIN & TOP COVER SLAB FIXING AT AMBEDKAR NAGAR 8TH STREET IN DN-06, U-02, Z-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/13140,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,401000,"PROPOSED OPEN SIDE DRAIN AT SIVA SHAKTHI NAGAR 6TH STREET IN DN-06, U-02, Z-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/13145,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,300000,"PROPOSED OPEN SIDE DRAIN AT SIVA SHAKTHI NAGAR 4TH STREET IN DN-06, U-02, Z-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/13149,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,283000,"PROPOSED OPEN SIDE DRAIN AT SIVA SHAKTHI NAGAR 3RD STREET IN DN-06, U-02, Z-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/13154,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,287000,"PROPOSED OPEN SIDE DRAIN AT SIVA SHAKTHI NAGAR 2ND STREET IN DN-06, U-02, Z-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/13158,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,287000,"PROPOSED OPEN SIDE DRAIN AT SIVA SHAKTHI NAGAR 1ST STREET IN DN-06, U-02, Z-01",Own Sources,1,2015-16,2016-17 NA/2015-16/13163,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,445000,"PROPOSED OPEN SIDE DRAIN & TOP COVER SLAB AT PONNIAMMAN NAGAR , VALLUVAR 3RD CROSS STREET IN DN-06, U-02, Z-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/13243,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,605000,"CONSTRUCTION OF SIDE DRAIN AND ROAD CROSSING DRAIN AT RMV NAGAR 1 st STREET, 2 nd STREET AND 3 rd STREET IN DN-07,UNIT-02,ZONE-01",Own Sources,1,2015-16,2017-18 NA/2015-16/13245,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,720000,"CONSTRUCTION OF SIDE DRAIN AND ROAD CROSSING DRAIN AT CHARLES NAGAR 3RD STREET 1 st CROSS, 2 st CROSS AND 3 st CROSS STREET IN DN-07, UNIT-02, ZONE - 01.",Own Sources,1,2015-16,2017-18 NA/2015-16/13246,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,365000,"CONSTRUCTION OF SIDE DRAIN AND ROAD CROSSING DRAIN AT RMV NAGAR MAIN ROAD IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2015-16,2017-18 NA/2015-16/13247,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,610000,"CONSTRUCTION OF SIDE DRAIN AND ROAD CROOING DRAIN AT CHARLES NAGAR 4 th STREET 2 nd CROSS , 3 rd CROSS AND 4 th CROSS STREET IN DN-07,UNIT-02, ZONE-01.",Own Sources,1,2015-16,2017-18 NA/2015-16/13298,Roads,Completed,NA-THIRUVOTTIYUR,9,997000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (M30) AT VILLAGE STREET ( Housing Board Block no A and B )IN DN.9, U-2, ZONE1(COUNCILLOR FUND 2015-16)",Own Sources,1,2015-16,2016-17 NA/2015-16/13302,Roads,Completed,NA-THIRUVOTTIYUR,9,997000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (M30) AT VILLAGE STREET ( Housing Board Block no C and D)AND TH ROAD LANE NEAR NELLAI STORES IN DN.9, U-2, ZONE1(COUNCILLOR FUND 2015-16)",Own Sources,1,2015-16,2016-17 NA/2015-16/13313,Buildings,Completed,NA-THIRUVOTTIYUR,2,441000,"Providing necessary Additional works in Anganwadi at Valluvar nagar in Div-2, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/13314,Buildings,Completed,NA-THIRUVOTTIYUR,2,487000,"Providing Necessary Additional works in AMMA UNAVAGAM-2 at village street in Div-2, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/13550,Buildings,Completed,NA-THIRUVOTTIYUR,3,315000,"Improvement Works at AMMA UNAVAGAM in Division-3, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/13614,Buildings,Completed,NA-THIRUVOTTIYUR,3,603000,"Demolition and Reconstruction of Kasi Koil Kuppam Burial Ground Compound wall from Entrance to Caretaker room in Div-3, U-1, Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/13627,Buildings,Completed,NA-THIRUVOTTIYUR,9,995000,"Construction of New Public Convenience with Disabled friendly Toilet at Appar Nagar 3rd Street in Dn-9 Unit-2, Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/13645,Buildings,Completed,NA-THIRUVOTTIYUR,9,995000,"Construction of New Public Convenience with Disabled friendly Toilet at Thiuvottiyur kuppam ( Burrial Ground) in Dn-9 Unit-2, Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/14574,Playfields,Completed,NA-THIRUVOTTIYUR,9,570000,"IMPROVEMENT WORK IN CHILDREN PLAY GROUND WITH PLAY APPRATUS AT VILLAGE STREET IN DIVISION-09,UNIT-02,ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/14581,Buildings,Completed,NA-THIRUVOTTIYUR,3,992000,"Providing Bio-toilet (2+1) at Kasi koil kuppam in Dn-03, Unit-01, Zone-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/15030,Roads,Completed,NA-THIRUVOTTIYUR,8,960000,"PROVIDING STREET FURNITURES AT VARIOUS LOCATION IN DIVISION -08, UNIT-02, ZONE-1(Ward Councilar Fund)",Own Sources,1,2015-16,2016-17 NA/2015-16/15276,Buildings,Completed,NA-THIRUVOTTIYUR,9,990000,"CONSTRUCTION OF BIO GAS PLANT AT BURIAL GROUND IN DIVISION-09,UNIT-02,ZONE-01",Own Sources,1,2015-16,2017-18 NA/2015-16/15938,Roads,Completed,NA-THIRUVOTTIYUR,9,540000,"PROVIDING FENCING ARRANGEMENTS AROUND E.B. TRANSFORMER OF VARIOUS LOCATION IN DIVISION -09, U-2, Z-1.",Own Sources,1,2015-16,2017-18 NA/2015-16/15941,Roads,Completed,NA-THIRUVOTTIYUR,8,445000,"PROVIDING FENCING ARRANGEMENTS AROUND E.B. TRANSFORMER OF VARIOUS LOCATION IN DIVISION -08, U-2, Z-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/15942,Buildings,Completed,NA-THIRUVOTTIYUR,8,995000,"ADDITIONAL CONSTRCTION WORK OF SI ROOM AT PERIYAR NAGAR IN DIVISION -08, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/16282,Buildings,Completed,NA-THIRUVOTTIYUR,2,333000,"Repair and Improvement works in Nehru nagar (Publi conveinece)in DIV-2,U-1,Z-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/16292,Roads,Completed,NA-THIRUVOTTIYUR,6,331000,"CONSTRUCTION OF OPEN SIDE DRAIN AT KALAINGAR NAGAR 12 STREET,3RD CROSS ST IN DN-6,UNIT-2, ZONE-1",Own Sources,1,2015-16,2016-17 NA/2015-16/16482,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,987000,"PROVIDING RCC LOOSE COVER SLAB AT THALANKUPPAM AMMAN KOIL STREET AND MAIN ROAD IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/16483,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,945000,"DISMANTLING AND RECONSTRUCTION OF EXISTING DAMAGED SIDE DRAIN AT ULAGANATHAPURAM 5 STREET IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/17436,Buildings,Completed,NA-THIRUVOTTIYUR,4,138000,"Repair and Maintenance of Ammaunavagam at Bhajanai Koil Street, Eranavoor in Dn-4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/17903,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,114000,"Repair work in open side drain at Sathiyamoorthy nagar 1st St division-6, Unit-2, Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/17916,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,165000,"Providing For top Cover Slab in Open Side Drain at Valluvar street, Ernavoor Div -4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/18318,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,3,460000,"Improvement to Burial Ground at J.J.Nagar in Division-3, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/18404,Buildings,Completed,NA-THIRUVOTTIYUR,3,298000,"Conversion of CPS room in to Arasu Cable room setup (CIVIL WORK) at Annai Sivagami Nagar in Division-3, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/18405,Buildings,Completed,NA-THIRUVOTTIYUR,3,289000,"Conversion of CPS room in to Arasu Cable room setup (Electrical & Finishes Work) at Annai Sivagami Nagar in Division-3, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/18414,Buildings,Completed,NA-THIRUVOTTIYUR,5,490000,"Repairs and Improvements to Anganwadi shed (center No:02) at Bharath Nagar in Division-5, unit-2,Zone-1. (under word councilor development fund 2015-2016)",Own Sources,1,2015-16,2016-17 NA/2015-16/18415,Buildings,Completed,NA-THIRUVOTTIYUR,5,334000,"Improvements works in Community Hall at Bharath Nagar 1st street in Division-5, Unit-2, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/18436,Buildings,Completed,NA-THIRUVOTTIYUR,14,383000,"IMPROVEMENTS TO AMMA CANTEEN AT ENNORE EXPRESS ROAD IN DIVISION-14, UNIT-03, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/1989,Buildings,Completed,NA-THIRUVOTTIYUR,4,300000,"Fencing, Water supply and Electrical arrangements for Bio- Toilet at JJ Nagar in Dn-03, U-1, Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20340,Buildings,Completed,NA-THIRUVOTTIYUR,2,179000,"Repair and improvement works in (Kamalammal nagar) public convenence in Div-2,Unit-1,Zone=1",Own Sources,1,2015-16,2016-17 NA/2015-16/20368,Roads,Completed,NA-THIRUVOTTIYUR,1,447000,"Laying Cement Concrete Road At VARADHARAJAN 2nd CROSS LANE IN DIV-13,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20869,Roads,Completed,NA-THIRUVOTTIYUR,11,156000,"Reparirs and Annual maintanance for Thiruvalluvar Kalai arangam at T.H.Road in Division-11, Unit-3, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/20876,Roads,Completed,NA-THIRUVOTTIYUR,12,68200,"Relaying the Patch work at Vanniar street in Div-12, U-3, Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20877,Roads,Completed,NA-THIRUVOTTIYUR,12,81500,"Relaying the Patch work at Thilagar nagar 3rd street in Div-12,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20879,Roads,Completed,NA-THIRUVOTTIYUR,12,145300,"Relaying the Patch work at New street in Div-12,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20882,Roads,Completed,NA-THIRUVOTTIYUR,12,128600,"Relaying the Patch work at Jandravar street in Div-12,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20883,Roads,Completed,NA-THIRUVOTTIYUR,12,127300,"Relaying the Patch work at Chetty Street in Div-12,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20885,Roads,Completed,NA-THIRUVOTTIYUR,12,75900,"Relaying the Patch work at Kavarai Street in Div-12,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20889,Roads,Completed,NA-THIRUVOTTIYUR,12,114000,"Relaying the Patch work at Kumaran Nagar in Div-12,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20891,Roads,Completed,NA-THIRUVOTTIYUR,12,74100,"Relaying the Patch work at Thilagar Nagar Main Road in Div-12,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20897,Roads,Completed,NA-THIRUVOTTIYUR,13,68200,"Relaying the Patch work at Udhaya Suriyan 1st Street in Div-13,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20903,Roads,Completed,NA-THIRUVOTTIYUR,13,34200,"Relaying the Patch work at Village Street in Div-13,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20907,Roads,Completed,NA-THIRUVOTTIYUR,13,68200,"Relaying the Patch work at M.G.R.Road in Div-13,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/2092,Buildings,Completed,NA-THIRUVOTTIYUR,6,300000,"Fencing, Water supply and Electrical arrangements for Bio- Toilet at Jothi Nagar in Dn-06, U-2, Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20925,Roads,Completed,NA-THIRUVOTTIYUR,6,1495000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD BY PAVER FINISHER AT KALAINGAR NAGAR MAIN ROAD (PART)IN DN-6.U-2,Z-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/20982,Roads,Completed,NA-THIRUVOTTIYUR,6,938000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD BY PAVER FINISHER AT KALAINGAR NAGAR 10TH STREET IN DN-6 U-2,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/20991,Roads,Completed,NA-THIRUVOTTIYUR,11,435000,"RELAYING THE ROAD AT ELLAI AMMAN KOIL STREET BY PAVER FINISHER (PART)(PATCH WORK FOR FLOOD DAMAGED ROAD) IN DIV-11, UNIT-3, ZONE-1.(LENTH-218M ,WIDTH-5.50M ,AREA-1200 SQ.M.)",Own Sources,1,2015-16,2016-17 NA/2015-16/21019,Roads,Completed,NA-THIRUVOTTIYUR,6,1277000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD BY PAVER FINISHER AT KALAINGAR NAGAR 8TH STREET IN DN-6,U-2,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/21071,Roads,Completed,NA-THIRUVOTTIYUR,4,764000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD PAVER FINISHER AT SHANMUGAPURAM 2nd street IN DN-4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/21074,Roads,Completed,NA-THIRUVOTTIYUR,4,565000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD BY PAVER FINISHER AT SHANMUGAPURAM 3RD STREET IN DN-4,U-1,Z-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/21099,Roads,Completed,NA-THIRUVOTTIYUR,4,309000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD BY PAVER FINISHER AT SHANMUGAPURAM 7TH ST IN DN-4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/21100,Roads,Completed,NA-THIRUVOTTIYUR,4,426000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD BY PAVER FINISHER SHANGMUGA PURAM 10 STREET IN DN-4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/21148,Roads,Completed,NA-THIRUVOTTIYUR,10,245000,"RELAYING THE ROAD BY PAVER FINISHER AT WEST MADA STREET PART(FLOOD DAMAGED) IN DN.10, U-3, Z-1.(LENTH-121M ,WIDTH-7.00M ,AREA-850SQ.M.)",Own Sources,1,2015-16,2016-17 NA/2015-16/21616,Roads,Completed,NA-THIRUVOTTIYUR,2,409000,"Laying Cement Concrete road at Kaveri nagar in Div-2, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/21817,Roads,Completed,NA-THIRUVOTTIYUR,2,380000,"Laying Cement concrete Road at Kattu kuppam 2nd cross st in Div-2,Unit-1,Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/2189,Buildings,Completed,NA-THIRUVOTTIYUR,1,985000,"IMPROVEMENTS AND REPAIRS TO CORPORATION SHOPPING COMPLEX AT THIRUVOTIYUR HIGH ROAD IN DN.9, U-2, ZONE-1",Own Sources,1,2015-16,2016-17 NA/2015-16/22036,Roads,Completed,NA-THIRUVOTTIYUR,11,1118000,"FORMING OF ROAD AT THIRIPURA SUNDARI NAGAR (FROM VANNIER STREET USING PAVER FINISHER IN DN.11, U-3, Z-1.(LENTH-219M ,WIDTH-5.50M ,AREA-1205.00 SQ.M.)",Own Sources,1,2015-16,2016-17 NA/2015-16/22110,Roads,Completed,NA-THIRUVOTTIYUR,10,909000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER AT THIRUMALAI AVENUE MAIN STREET, Ist CROSS STREET TO 3rd CROSS STREET IN DN.10, U-3, Z-1.(LENTH-260.00M ,WIDTH-3.80M ,AREA-990 SQ.M.)",Own Sources,1,2015-16,2016-17 NA/2015-16/22126,Roads,Completed,NA-THIRUVOTTIYUR,7,813000,"ATTENDING PATCH WORK AT GLASS FACTORY ROAD AND RAMASAMY NAGAR IN DN - 07, UNIT - 02, ZONE -01.",Own Sources,1,2015-16,2016-17 NA/2015-16/22133,Roads,Completed,NA-THIRUVOTTIYUR,2,195000,Laying Cement Concrete Road at Periya kuppam 1 st street in Div-2.Unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22136,Roads,Completed,NA-THIRUVOTTIYUR,2,283000,Laying Cement Concrte Road at Periya kuppam 2nd street inDiv-2.Unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22167,Roads,Completed,NA-THIRUVOTTIYUR,2,365000,"Laying Cement concrete Road at Periya kuppam 3rd street in Div-2, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/22171,Roads,Completed,NA-THIRUVOTTIYUR,2,593000,Laying Cement concrete Road at Periya kuppam 4th street inDiv-2.Unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22174,Roads,Completed,NA-THIRUVOTTIYUR,2,212000,Laying Cement Concrete Road at Indra nagar 2nd street in Div-2.unit-1.Zone-1,Own Sources,1,2015-16,2016-17 NA/2015-16/22179,Roads,Completed,NA-THIRUVOTTIYUR,2,379000,"Laying Cement Concrete Road at Indra nagar 3rd street in Div-2, Unit-1. Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/22181,Roads,Completed,NA-THIRUVOTTIYUR,2,142000,"Laying Cement Concrete Road at Indra nagar 4th street in Div-2, Unit-1, Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/22184,Roads,Completed,NA-THIRUVOTTIYUR,2,270000,"Laying Cement concrete Road at Indra nagar 5th street in Div-2, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/22189,Roads,Completed,NA-THIRUVOTTIYUR,2,536000,"Laying Cement Concrete Road at Kamalammal nagar 2nd street in Div-2, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/22193,Roads,Completed,NA-THIRUVOTTIYUR,2,506000,Laying Cement Concrete Road At Kamalammal nagar 3rd street in Div-2. unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22198,Roads,Completed,NA-THIRUVOTTIYUR,2,663000,Laying Cement Concrete Road at Manamazhil mandram street inDiv-2.Unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22210,Roads,Completed,NA-THIRUVOTTIYUR,2,125000,Laying Cement Concrete Road at Nehru nagar 1st cross street in Div-2.Unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22217,Roads,Completed,NA-THIRUVOTTIYUR,2,213000,Laying Cement Concrete Road at Nehru nagar 2nd cross street inDiv-2.Unit-1.Zone-1,Own Sources,1,2015-16,2016-17 NA/2015-16/22221,Roads,Completed,NA-THIRUVOTTIYUR,2,691000,"Laying Cement Concrete Road at Nehru nagar 3rd cross link street in Div-2, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/22224,Roads,Completed,NA-THIRUVOTTIYUR,2,438000,Laying Cement Concrete Road at Nehru nagar 3rd cross street in Div-2.Unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22226,Roads,Completed,NA-THIRUVOTTIYUR,2,777000,Laying Cement concrete Road at Nehru nagar 4th cross street in Div-2.Unit-1.Zone-1.,Own Sources,1,2015-16,2016-17 NA/2015-16/22357,Roads,Completed,NA-THIRUVOTTIYUR,6,483000,"Repair to the Flood Damage B.T.Road by Paver Finisher at Kalaignar Nagar 6th street in Dn-6,U-2,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/2342,Buildings,Completed,NA-THIRUVOTTIYUR,11,992000,"PROVIDING BIO-TOILET WITH (2+1 EUROPEAN WATER CLOSET SEATING ARRANGEMENTS ) AT ELLAI AMMAN KOIL STREET IN DN.11, U-3, Z-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/2365,Buildings,Completed,NA-THIRUVOTTIYUR,6,992000,"PROVIDING BIO-TOILET (2+1) AT JOTHI NAGAR IN DIVISION-06, UNIT-02,ZONE-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/23721,Roads,Completed,NA-THIRUVOTTIYUR,4,339000,"Laying of cement concrete Road at Kamaraj nagar 1st cross st 1 st cross lane in Div-4, Unit-1, Zone-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/23738,Roads,Completed,NA-THIRUVOTTIYUR,6,856000,"LAYING OF CEMENT CONCRETE ROAD AT KALAIVANNAR NAGAR (junction of rajashanmugam nagar 15th to sakthiganapathy nagar 2 nd st) in Div-6,U-2,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/23760,Roads,Completed,NA-THIRUVOTTIYUR,6,957000,"LAYING OF CEMENT CONCRETE ROAD AT KALAIVANNAR NAGAR (junctionof sakthiganapathy nagar to shanmugapuram extension) in Div-6, U-2, Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/23774,Roads,Completed,NA-THIRUVOTTIYUR,6,865000,"LAYING OF CEMENT CONCRETE ROAD AT PONNIAMMAN NAGAR NETHAJI 5TH STREET IN DN-6,U-2,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/23776,Roads,Completed,NA-THIRUVOTTIYUR,6,308000,"LAYING OF CEMENT CONCRETE ROAD AT PONNIAMMAN NAGAR 4TH IN DN-6,U-2,Z-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/23777,Roads,Completed,NA-THIRUVOTTIYUR,6,399000,"LAYING OF CEMENT CONCRETE ROAD AT PONNIAMMAN NAGAR VALLUVAR 3RD CROSS STREET IN DN-6,U-2,Z-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/23783,Roads,Completed,NA-THIRUVOTTIYUR,7,507000,"LAYING CEMENT CONCRETE ROAD AT PERIYAR NAGAR 1st STREET IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/23784,Roads,Completed,NA-THIRUVOTTIYUR,7,1847000,"STRENGTHENING AND RELAYING BT ROAD AT RAMASAMY NAGAR MAIN ROAD IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/23786,Roads,Completed,NA-THIRUVOTTIYUR,7,202000,"STRENGTHENING AND RELAYING BT ROAD AT RAMASAMY NAGAR 5 th STREET IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/23787,Roads,Completed,NA-THIRUVOTTIYUR,7,184000,"STRENGTHENING AND RELAYING BT ROAD AT RAMASAMY NAGAR 6 th STREET IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/23819,Roads,Completed,NA-THIRUVOTTIYUR,8,387000,"LAYING BT ROAD AT S.P. KOIL 1st STREET IN DN - 08, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/2391,Buildings,Completed,NA-THIRUVOTTIYUR,11,300000,"Fencing, Water supply and Electrical arrangements for Bio- Toilet at Ellaiamman Koil Street in Dn-11, U-3, Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/24588,Buildings,Completed,NA-THIRUVOTTIYUR,6,200000,"Improvements to Ammaunavagam at Sathiyamoorthy Nagar in Div-6,Unit-2,Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/24711,Roads,Completed,NA-THIRUVOTTIYUR,7,342000,"LAYING CEMENT CONCRETE ROAD AT CHARLES NAGAR 4TH STREET 2ND CROSS ST IN DIVISION-7,UNIT-2,ZONE-1",Own Sources,1,2015-16,2017-18 NA/2015-16/2512,Buildings,Completed,NA-THIRUVOTTIYUR,7,990000,"PROVIDING BIO-TOILET (2+1) AT JN OF MANALI ROAD AND BASIN ROAD IN DIVISION-07, UNIT-02,ZONE-01.",Own Sources,1,2015-16,2016-17 NA/2015-16/25182,Roads,Completed,NA-THIRUVOTTIYUR,6,477000,"Laying of cement concrete road at Rajashanmugam nagar 9th street (part) in div-6,unit-2,zone-1.(Councillor Fund 2015-2016)",Own Sources,1,2015-16,2017-18 NA/2015-16/25227,Buildings,Completed,NA-THIRUVOTTIYUR,6,998000,"Proposed Construction of Division Office at Jothi Nagar 10th Street,in Div-6,U-2,Z-1",Own Sources,1,2015-16,2017-18 NA/2015-16/2524,Buildings,Completed,NA-THIRUVOTTIYUR,7,300000,"Fencing, Water supply and Electrical arrangements for Bio- Toilet at jn of basin and manali road in Dn-07, U-2, Z-1",Own Sources,1,2015-16,2017-18 NA/2015-16/25355,Roads,Completed,NA-THIRUVOTTIYUR,6,131000,"Providing the Quarry rubbish and other improvements to Ambedkar nagar pillayarkoil Street, in Div-6, Unit -2, Zone-1.",Own Sources,1,2015-16,2017-18 NA/2015-16/25369,Buildings,Completed,NA-THIRUVOTTIYUR,6,280000,"Improvements and Mainteance middle school at Ramanathapuram in Dv-4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/25935,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,968000,Construction of side drain work at Sakthipuram in Div-5.Unit-1.Zone-1,Own Sources,1,2015-16,2016-17 NA/2015-16/25976,Roads,Completed,NA-THIRUVOTTIYUR,8,717000,"LAYING OF CEMENT CONCRETE ROAD AT ANNA NAGAR 1ST TO 3RD STREET AND 3RD CROSS STREET IN DIVISION -08, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/25977,Roads,Completed,NA-THIRUVOTTIYUR,8,1367000,"LAYING OF CEMENT CONCRETE ROAD AT M.G.R NAGAR ( S.P. KOIL STREET) 1ST ,2ND LANE AND CROSS LANE IN DIVISION -08, UNIT-02, ZONE-01",Own Sources,1,2015-16,2017-18 NA/2015-16/25978,Roads,Completed,NA-THIRUVOTTIYUR,8,309000,"LAYING OF CEMENT CONCRETE ROAD AT S.P KOIL CROSS STREET IN DIVISION -08, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/25979,Roads,Completed,NA-THIRUVOTTIYUR,8,250000,"LAYING OF CEMENT CONCRETE ROAD AT S.P KOIL BACK SIDE CROSS STREET IN DIVISION -08, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/25980,Roads,Completed,NA-THIRUVOTTIYUR,8,247000,"LAYING OF CEMENT CONCRETE ROAD AT S.P KOIL BACK SIDE 2ND CROSS STREET IN DIVISION -08, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/25981,Roads,Completed,NA-THIRUVOTTIYUR,8,400000,"LAYING OF CEMENT CONCRETE ROAD AT S.P KOIL 2ND CROSS STREET IN DIVISION -08, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/26008,Roads,Completed,NA-THIRUVOTTIYUR,13,326000,"Laying Cement Concrete Road At VARADHARAJAN 3rd CROSS LANE IN DIV-13,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/26009,Roads,Completed,NA-THIRUVOTTIYUR,13,258000,"Laying Cement Concrete Road At VARADHARAJAN 1st CROSS LANE IN DIV-13,U-3,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/26015,Roads,Completed,NA-THIRUVOTTIYUR,13,844000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30) AT GANDHI NAGAR 1 , 2 ,3 & 4 STREETS (WESTERN SIDE) L - 152.00.00 W-3.30 AREA-250Sq.m IN DN -13 U-3 Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/26237,Roads,Completed,NA-THIRUVOTTIYUR,1,725000,"LAYING CEMENT CONCRETE ROAD AT NETTUKUPPAM COMMUNITY HALL APPROACH ROAD IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/26247,Roads,Completed,NA-THIRUVOTTIYUR,1,810000,"LAYING CONCRETE ROAD AT THALANKUPPAM CROSS STREET (OHT BACK SIDE) IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/26274,Roads,Completed,NA-THIRUVOTTIYUR,6,900000,"Open Side Drain at T.S.Gopal Nagar 1st in Div-6,Unit-2,Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/26499,Buildings,Completed,NA-THIRUVOTTIYUR,1,205000,"IMPROVEMENT WORKS TO SCHOOLS AT S.V.M. NAGAR , NETTUKUPPAM , THALANKUPPAM AND KAMARAJ NAGAR IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/26587,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,962000,"Proposed Open Side Drain & Road Crossing Drain at Kalaingar Nagar 8th Street,in Dn-6,U-2,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/26621,Buildings,Completed,NA-THIRUVOTTIYUR,4,998000,"Proposed Construction of Anganwadi Centre No.13,at Mangalliamman Koil Street,Ernavoor in Dn-4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/26765,Roads,Completed,NA-THIRUVOTTIYUR,6,1464000,"REPAIR TO THE FLOOD DAMAGE B.T ROAD BY PAVER FINISHER AT MADHURA NAGAR MAIN ROAD (PART)IN DN-6, U-2, Z-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/26806,Culvert,Completed,NA-THIRUVOTTIYUR,6,175000,"Proposed Construction of Culvert at Shanmugampuram 2nd Street,in Dn-6,U-2,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/26982,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,238000,"Improvement to Open Side Drain Wall Raising at V.P Nagar 4th Street,in Dn-4,Unit-1,Zone-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/27258,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,800000,"PROPOSED OPEN SIDE DRAIN AT RAJASHANMUGAM NAGAR 10TH STREET IN DN-6,U-2,Z-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/27662,Roads,Completed,NA-THIRUVOTTIYUR,9,276000,"BURIAL GROUND TOILET SEWAGE PIPE LINE WORK FROM BURIAL GROUND TO APPARSWAMY KOIL STREET IN DIVISION-09, UNIT-02, ZONE-1",Own Sources,1,2015-16,2016-17 NA/2015-16/27663,Roads,Completed,NA-THIRUVOTTIYUR,8,998000,"PROVIDING AND FIXING OF RAINWATER HARVESTING WORK AND PATCH WORK IN VARIOUS LOCATION IN DIVISION-08, UNIT-02 ZONE-1",Own Sources,1,2015-16,2018-19 NA/2015-16/27702,Buildings,Completed,NA-THIRUVOTTIYUR,6,992000,"Proposed Construction oF GYM at Sathiyamoorthy Nagar 2nd Street,in Dn-6,U-2,Z-1",Own Sources,1,2015-16,2017-18 NA/2015-16/28315,Roads,Completed,NA-THIRUVOTTIYUR,6,890000,"Providing Top Cover Slab at Sivasakthi Nagar 1,2,3,4,6,in Div-6,Unit-2,Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/28845,Roads,Completed,NA-THIRUVOTTIYUR,6,458000,"Providing Top Cover Slab in Open Side Drain at Saraswathi Nagar 12th Street,in Dn-6,U-2,Z-1,",Own Sources,1,2015-16,2016-17 NA/2015-16/2905,Roads,Completed,NA-THIRUVOTTIYUR,4,539000,Providing the various street Name Board in Dn-4 Unit-1 Zone-1,Own Sources,1,2015-16,2016-17 NA/2015-16/29174,Buildings,Completed,NA-THIRUVOTTIYUR,1,385000,"IMPROVEMENTS AN MAINTANANCE TO AMMA UNAVAGAM AT K.H.ROAD IN DIVISION-1,UNIT-1,ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/29496,Buildings,Completed,NA-THIRUVOTTIYUR,1,65000,"IMPROVEMENT WORKS TO PUBLIC CONVEINANANCE AT MUGATHUVARAKUPPAM IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/29497,Buildings,Completed,NA-THIRUVOTTIYUR,1,995000,"CONSTRUCTION OF ANGANWADI BUILDING AT MUGATHUVARAKUPPAM IN DN - 01 , UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/29501,Buildings,Completed,NA-THIRUVOTTIYUR,1,54000,"IMPROVEMENT WORKS TO DENTAL CILINIC AT THALANKUPPAM IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/29503,Buildings,Completed,NA-THIRUVOTTIYUR,1,400000,"IMPROVEMENT WORKS TO ANGANWADI BUILDING AT ULAGANATHAPURAM AND J.J.NAGAR IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/29506,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,900000,"REPAIR AND IMPROVEMENTS TO SIDE DRAIN AT THALANKUPPAM CROSS STREETS IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/29770,Roads,Completed,NA-THIRUVOTTIYUR,6,918000,"PROPOSED OPEN SIDE DRAIN & ROAD CROSSING DRAIN AT KALAINGAR NAGAR 12TH STREET IN DIVISION -6,UNIT-2,ZONE-1",Own Sources,1,2015-16,2016-17 NA/2015-16/29880,Roads,Completed,NA-THIRUVOTTIYUR,1,980000,"PROVIDING STREET FURNITURE AT SATHIYAVANIMUTHU NAGAR , ULAGANATHAPURAM AND ENNOREKUPPAM STREETS IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/29884,Roads,Completed,NA-THIRUVOTTIYUR,1,980000,"PROVIDING STREET FURNITURE AT THALANKUPPAM , NETTUKUPPAM AND MUGATHUVARAKUPPAM STREETS IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/29886,Buildings,Completed,NA-THIRUVOTTIYUR,4,323000,"Improvement works in Angawadi centre at Ramanathapuram 10th Street,in Div-4,U-1,Z-1",Own Sources,1,2015-16,2016-17 NA/2015-16/29998,Buildings,Completed,NA-THIRUVOTTIYUR,1,995000,"CONSTRUCTION OF GYM BUILDING AT NETTUKUPPAM IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2017-18 NA/2015-16/30114,Parks,Completed,NA-THIRUVOTTIYUR,5,326000,"ANNUAL MAINTENANCE OF PARK AT ALL CARGO LOGISTIC COMPANY OSR LAND IN DN-5, UNIT-2, ZONE-1",Own Sources,1,2015-16,2018-19 NA/2015-16/30115,Parks,Completed,NA-THIRUVOTTIYUR,5,425000,"ANNUAL MAINTENANCE OF PARK AT SAKTHIPURAM (SRI RANGAM NEW TOWN) IN DN-5, UNIT-2, ZONE-1",Own Sources,1,2015-16,2018-19 NA/2015-16/30116,Parks,Completed,NA-THIRUVOTTIYUR,5,343000,"ANNUAL MAINTENANCE OF PARK AT HANSA GARDEN OSR LAND IN DN-5, UNIT-2, ZONE-1",Own Sources,1,2015-16,2018-19 NA/2015-16/30281,Buildings,Completed,NA-THIRUVOTTIYUR,7,995000,"CONSTRUCTION OF ANGANWADI BUILDING AT BALAKRISHNAN NAGAR MAIN ROAD IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/30283,Buildings,Completed,NA-THIRUVOTTIYUR,7,997000,"CONSTRUCTION OF ANGANWADI BUILDING AT KARGIL NAGAR MAIN ROAD IN DN - 07, UNIT - 07, ZONE - 01.",Own Sources,1,2015-16,2018-19 NA/2015-16/30284,Buildings,Completed,NA-THIRUVOTTIYUR,7,314000,"CONSTRUCTION OF SHED AND WATER SUPPLY ARRANGEMENTS AT SATHANGADU DUMPING GROUND IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/30287,Buildings,Completed,NA-THIRUVOTTIYUR,7,121000,"REPAIR AND MAINTNANCE TO KARGIL NAGAR SCHOOL IN DN - 07, UNIT -02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/30288,Buildings,Completed,NA-THIRUVOTTIYUR,7,250000,"CONSTRUCTION OF SEGREATION SHED AT RAJAJI NAGAR IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/30305,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,210000,"COSTRUCTION OF ROAD CROSSING CULVET AT PERIYAR NAGAR IN DN- 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/30444,Roads,Completed,NA-THIRUVOTTIYUR,9,650000,"LAYING OF CEMENT CONCRETE ROAD AT VILLAGE STREET, 1ST LANE APPARSAMY 1ST CROSS LANE AND CROSS LANE IN DIVISION-9, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/31004,Buildings,Completed,NA-THIRUVOTTIYUR,4,90000,"Improvements to corporation school at Eranavoor in Div-4, Unit-1, Zone-1",Own Sources,1,2015-16,2017-18 NA/2015-16/31063,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,163000,"DISMANTLING AND RECONSTRUCTION OF DAMAGED RAD CROSSING SIDE RAIN AT ULAGANATHAPURAM 6 th STREET AND S.V.M. NAGAR 9 th STREET IN DIVISION-1,UNIT-1,ZONE-1",Own Sources,1,2015-16,2016-17 NA/2015-16/33256,Roads,Completed,NA-THIRUVOTTIYUR,7,970000,"LAYING CEMENT CONCRETE ROAD AT ANNA NAGAR 1 st STREET IN DN - 07, UNIT - 02, ZONE - 01.",MLACDS,1,2015-16,2016-17 NA/2015-16/33257,Roads,Completed,NA-THIRUVOTTIYUR,7,995000,"LAYING CEMENT CONCRETE ROAD AT ANNA NAGAR 2 nd STREET IN DN - 07, UNIT - 02, ZONE - 01.",MLACDS,1,2015-16,2016-17 NA/2015-16/33562,Buildings,Completed,NA-THIRUVOTTIYUR,11,295000,"PROVIDING RAIN WATER HARVESTING STRUCTURE BY USING PRECAST WELL RINGS AND PROVIDING CHUTE PIPE AT VARIOUS STREETS IN DIV-11, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/33565,Buildings,Completed,NA-THIRUVOTTIYUR,11,250000,"REPAIRS AND IMPROVEMENTS TO ANGANWADI AND CHS CAMPUS AT MARKET LANE IN DIV-11, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2018-19 NA/2015-16/33567,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,11,564000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT SANNATHI STREET IN DIV-11, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/33578,Buildings,Completed,NA-THIRUVOTTIYUR,11,245000,"REPAIRS AND IMPROVEMENTS TO ZONAL OFFICE MAIN BUILDING IN ZONAL OFFICE CAMPUS AT T.H.ROAD IN DIV-11, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2017-18 NA/2015-16/33580,Buildings,Completed,NA-THIRUVOTTIYUR,11,595000,"REPAIRS AND IMPROVEMENTS TO MEETING HALL IN ZONAL OFFICE AT T.H..ROAD IN DIV-11, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/33581,Buildings,Completed,NA-THIRUVOTTIYUR,11,225000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT T.H.ROAD DIV-11, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/33582,Roads,Completed,NA-THIRUVOTTIYUR,10,189000,"PROVIDING CEMENT CONCRETE PATCHES AT VARIOUS STREETS IN DIV-10, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/33583,Roads,Completed,NA-THIRUVOTTIYUR,10,219000,"PROVIDING BITUMIONOUS PATCHES AT VARIOUS STREETS IN DIV-10, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/3361,Buildings,Completed,NA-THIRUVOTTIYUR,1,490000,"IMPROVEMENTS TO AMMA CANTEEN AT PATTINATHAR KOIL ST IN DN.9, U-2, Z-1",Own Sources,1,2015-16,2017-18 NA/2015-16/33848,Buildings,Completed,NA-THIRUVOTTIYUR,8,597000,"ADDITIONAL AND IMPROVEMENT WORK DIVISION OFFICE AT PERIYAR NAGAR IN DIVISION-8, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/3385,Buildings,Completed,NA-THIRUVOTTIYUR,11,751000,"ADDITIONAL IMPROVEMENTS OF AMMA UNAVAGAM AT WEST MADA STREET IN DN.10, UNIT-3, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/5511,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,840000,"PROVIDING LOOSE RCC COVER SLAB AT PERIYAR NAGAR 1 st STREET SIDE DRAIN IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/5512,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,788000,"PROVIDING LOOSE COVER RCC SLAB AT PERIYAR NAGAR 2 nd STREET SIDE DRAIN IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/5513,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,790000,"PROVIDING LOOSE RCC COVER SLAB AT PERIYAR NAGAR 3 rd STREET SIDE DRAININ DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/5514,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,630000,"PROVIDING LOOSE RCC COVER SLAB AT CHARLES NAGAR 2 nd STREET SIDE DRAIN IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/5515,Roads,Completed,NA-THIRUVOTTIYUR,1,988000,"Road cut restoration work (Due to CMWSSB- UG DRAINAGE SYSTEM) at Ennorekuppam 3 Street, 4 Street, 5 Street, Mugathuvarakuppam 4 Street, 5 Street, 5 Cross and Nettukuppam 1 Street IN DN - 01, UNIT - 01, ZONE - 01. (L- 933 m)",Deposit Works,1,2015-16,2016-17 NA/2015-16/5518,Roads,Completed,NA-THIRUVOTTIYUR,1,986000,"Road cut restoration work (Due to CMWSSB- UG DRAINAGE SYSTEM) at Nettukuppam Chinnaamman Koil 1 Street, 2 Street, 3 Street , 4 Street, 5 Street and Beach Road IN DN - 01, UNIT - 01, ZONE - 01. (L- 908 m)",Deposit Works,1,2015-16,2016-17 NA/2015-16/5964,Roads,Completed,NA-THIRUVOTTIYUR,13,621000,"Laying cement concrete road (Using M30) at Varatharajan Street from Village street to Ch-80m in Dn -13, Unit- 3, Zone-I",Own Sources,1,2015-16,2016-17 NA/2015-16/5967,Roads,Completed,NA-THIRUVOTTIYUR,13,621000,"Laying cement concrete road (Using M30) at Varatharajan Street from Ch-80m to Ch-160m in Dn -13, Unit- 3, Zone-I",Own Sources,1,2015-16,2016-17 NA/2015-16/5968,Buildings,Completed,NA-THIRUVOTTIYUR,1,980000,"IMPROVEMENTS TO SATHIYAVANIMUTHU NAGAR BURIAL GROUND IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2015-16,2016-17 NA/2015-16/6052,Buildings,Completed,NA-THIRUVOTTIYUR,11,195000,"ADDITIONAL IMPROVEMENTS TO NOONMEAL CENTRE AND DINNING HALL AT MARKET LANE CPS CAMPUS IN DN-11,UNIT-3,ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/6098,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,325000,"IMPROVEMENT OF SIDE DRAIN WORKS @ KALAINGAR NAGAR 4th STREET IN DIVISION-06, UNIT-2, ZONE-1.",Own Sources,1,2015-16,2016-17 NA/2015-16/6099,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,530000,"IMPROVEMENT OF SIDE DRAIN WORKS @ KALAINGAR NAGAR 10th STREET IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2015-16,2016-17 NA/2015-16/6400,Buildings,Completed,NA-THIRUVOTTIYUR,2,995000,"Construction of New Public Convenience with Disabled friendly Toilet at Chinna kuppam Karumariamman koil st in Dn-2 Unit-1, Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/6546,Buildings,Completed,NA-THIRUVOTTIYUR,7,430000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT BALAKRISHNA NAGAR MAIN ROAD IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2015-16,2017-18 NA/2015-16/6617,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,983000,"IMPROVEMENTS OF SIDE DRAIN @ PONNIAMMAN NAGAR 2nd STREET (V.O.C STREET ) IN DIVISION-06, UNIT-02, ZONE-01",Own Sources,1,2015-16,2018-19 NA/2015-16/7433,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,587000,"Providing to top Cover Slab in Open Side Drain @ Girija Nagar in,Girija Nagar Main Road, Mullai Nagar, Selvaganapathi Street, Eranavoor,in Div -4 ,Unit-1,Zone-1",Own Sources,1,2015-16,2016-17 NA/2015-16/7633,Buildings,Completed,NA-THIRUVOTTIYUR,3,413000,"Construction of Sump with water supply arrangements for Chennai Primary School kasi koil kuppam in Dn3, U-1, Z-1 under Councillar Fund 2015-16",Own Sources,1,2015-16,2016-17 NA/2015-16/7634,Buildings,Completed,NA-THIRUVOTTIYUR,3,413000,"Construction of Sump with water supply arrangements for Chennai Primary School at Annai Sivagami Nagar Dn-3, U-1, Z-1 under councillar fund 2015-16",Own Sources,1,2015-16,2016-17 NA/2015-16/8053,Buildings,Completed,NA-THIRUVOTTIYUR,3,873000,"Improvements to Kasi Koil Kuppam Burial Ground Compound wall (East Side) and Entrance Gates in Div-3, Unit-1, Zone-1 under Councillar Fund 2015-16",Own Sources,1,2015-16,2016-17 NA/2015-16/9040,Roads,Completed,NA-THIRUVOTTIYUR,13,581000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30) AT UNITED COLONY( FROM VARADHARAJAN MAIN ROAD TO DEAD END) L-80.00 W-4.80 AREA-384sq.m IN DN -13 ,UNIT-3, ZONE-1",Own Sources,1,2015-16,2016-17 NA/2015-16/9354,Roads,Completed,NA-THIRUVOTTIYUR,13,932000,PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30) AT VILLAGE 8th STREET IN DIV-13 U-3 Z-1(COUNCILLAR FUND 2015-2016) L-140.00 W-3.7 AREA-518.00 Sq.m,Own Sources,1,2015-16,2016-17 NA/2015-16/9385,Roads,Completed,NA-THIRUVOTTIYUR,13,898000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD (USING M30) PILLAIYAR KOIL STREET -2 & VILLAGE 7th STREET IN DIV -13 U-3 Z-1(COUNCILLAR FUND 2015-2016) (L-62,125 W-3.5,2.2 AREA-492 Sq.m",Own Sources,1,2015-16,2016-17 NA/2015-16/9836,Buildings,Completed,NA-THIRUVOTTIYUR,13,978000,"Construction of new SI ROOM DN13, UNIT-03, ZONE-01",Own Sources,1,2015-16,2016-17 NB/2015-16/0232,Buildings,Completed,NB-MANALI,18,722000,PROPOSED CONSTRUCTION OF PUBLIC CONVEYANCE AT CPCL LAYOUT IN DN-18 U-5 ZN-II,Own Sources,2,2015-16,2016-17 NB/2015-16/0366,Electrical,Completed,NB-MANALI,19,716900,Provision of Nos of 6 mtr M.S Lamp Post with Single Straight Bracket with LED 40-50 Watts Led fittinh at MMDA 2nd main road park in dn-19 u-5 zn-ii,Own Sources,2,2015-16,2016-17 NB/2015-16/10271,Roads,Completed,NB-MANALI,16,122000,"PROVIDING HOUSE KEEPING FOR CPS-3 AT MANALI NEWTOWN IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/10272,Roads,Completed,NB-MANALI,16,285000,"PROVIDING HOUSE KEEPING FOR CPS-1&5 AT MANALI NEWTOWN IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/10538,Buildings,Completed,NB-MANALI,18,500000,"DESILTING AND MAINTENANCE FOR STORM WATER DRAIN IN DIVISION-18,UNIT-05,ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/11165,Road Cut,Completed,NB-MANALI,17,998000,"RESTORATION OF ROAD-CUT MADE BY CMWSSB AT THIYAGI VISWANATHADASS NAGAR AND SAKTHIAMMAN KOIL NAGAR IN DN-17, U-4, Z-2.",Deposit Works,2,2015-16,2016-17 NB/2015-16/11372,Storm Water Drain,Completed,NB-MANALI,16,993000,"CONSTRUCTION OR R R MASONTRY WALL TO KANNIAMMANPET KANNIKOIL STREET POND WEST SIDE IN DN ;16, UN;4, ZN;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/11373,Storm Water Drain,Completed,NB-MANALI,16,993000,"CONSTRUCTION OR R R MASONTRY WALL TO KANNIAMMANPET KANNIKOIL STREET POND EAST SIDE IN DN ;16, UN;4, ZN;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/11391,Buildings,Completed,NB-MANALI,17,990000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT VINAYAGAPURAM BURIAL GROUND (WEST AND SOUTH) IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/12103,Buildings,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF NNMP SHED DINNING HALL AT CPCL LAYOUT(NEAR BY METRO WATER OFFICE) IN DN-18,U-5,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/12104,Buildings,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF AMMA DINNING HALL GROUND FLOOR+FIRST FLOOR AT THIRUVALLUVAR STREET IN DN-18,U-5,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/12105,Buildings,Completed,NB-MANALI,18,998000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO PUBLIC CONVENIENCE AT CPCL LAYOUT IN DN-18, UNIT-5,ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/12425,Buildings,Completed,NB-MANALI,21,350000,"PROPOSED LAYING PIPE LINE AND CHAMBER AT THAMAIRIKULAM 3RD STREET AND THIRU VI KA STREET TO JALAKADAMARIAMMAN KOIL LINK STREET IN DN-21,U-5,Z-II",Own Sources,2,2015-16,2016-17 NB/2015-16/12797,Buildings,Completed,NB-MANALI,19,997000,"PROPOSED CONSTRUCTION OF STORE ROOM , SHREDDING MACHINERY ROOM AND FOOTPATH AT ARULANANDHAM NAGAR 2ND LANE IN DN-19, UNIT-05, ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/12818,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR CHINNATHOPPU VADAPERUMBAKKAM(NEAR BY COMMUNITY CENTER) POND IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/12819,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT PARK OSR LAND C.K MADHAVAN NAGAR(CHETTIMEDU) IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/12820,Buildings,Completed,NB-MANALI,17,940000,"PROVIDING ELECTRICAL AND DRAINAGE FACILITIES TO MULTIPURPOSE HALL AT ARIYALUR MAIN ROAD IN DN-17,U-4,Z-II",Own Sources,2,2015-16,2016-17 NB/2015-16/13840,Buildings,Completed,NB-MANALI,15,998000,"CONSTRUCTION OF COMPOUND WALL AT COMMUNITY CENTER EAST SIDE AT MANALI NEW TOWN 80 FEET ROAD IN DN-15,UN-4,ZN-2",Own Sources,2,2015-16,2016-17 NB/2015-16/13895,Buildings,Completed,NB-MANALI,19,998000,"Proposed construction of NNMP shed with Dining hall at CMS Manjambakkam in DN-19, U-5 & Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/15397,Buildings,Completed,NB-MANALI,18,320000,"MAINTENANCE FOR PATCH WORK AT ANBAZHAGAN, VIMALAPURAM,BHARATHIYAR STREET AND IMPROVEMENT OF CPCL PARK AT NEDUCHEZHIYAN STREET IN DN-18,U-5,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/16280,Buildings,Completed,NB-MANALI,19,995000,"Proposed construction of 16th ceremony hall at Kamaraj salai (Junction of 100feet road) in dn-19, unit-5, zone-02.",Own Sources,2,2015-16,2017-18 NB/2015-16/16367,Parks,Completed,NB-MANALI,19,625000,"proposed construction of Food feeding Plat form for birds, approach footpath & Warmup Area inside of the park at MMDA 2nd main road in Dn-19, U-05, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/16369,Parks,Completed,NB-MANALI,19,518000,"proposed construction of Warmup Area inside of the park at MMDA 2nd main road in Dn-19, U-05, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/1649,Buildings,Completed,NB-MANALI,20,992000,"GOOD EARTH FILLING FOR THE NEWLY PROPOSED ZONAL OFFICE BUILDING SITE ( SOUTH SIDE) AT KAMARAJ SALAI IN DN;20, UNIT; 5, ZONE; 2.",Own Sources,2,2015-16,2016-17 NB/2015-16/1650,Buildings,Completed,NB-MANALI,20,967000,"GOOD EARTH FILLING FOR THE NEWLY PROPOSED ZONAL OFFICE BUILDING SITE ( NORTH SIDE) AT KAMARAJ SALAI IN DN;20, UNIT; 5, ZONE; 2.",Own Sources,2,2015-16,2016-17 NB/2015-16/16533,Buildings,Completed,NB-MANALI,19,851000,"REPAIRS AND IMPROVEMENT TO EXISTING CMS OLD BUILDINGS AT KAMARAJAR STREET (MANJAMBAKKAM) IN DN-19,U-5,Z-2.",Own Sources,2,2015-16,2018-19 NB/2015-16/16707,Parks,Completed,NB-MANALI,19,997000,GREENERY ARRANGEMENT FOR MMDA-2ND MAIN ROAD PARK IN DIV-19 UNIT-5 ZONE-2,Own Sources,2,2015-16,2016-17 NB/2015-16/16708,Parks,Completed,NB-MANALI,16,995000,"SUPPLY AND SPREADING OF Red Earth and Sand ,MANURE MMDA 2ND Main Road Park in Div-19 Unit-05 Zone-2",Own Sources,2,2015-16,2016-17 NB/2015-16/17028,Storm Water Drain,Completed,NB-MANALI,20,300000,"IMPROVEMENT WORKS OF BURIAL GROUND AT KAMARAJ SALAI AND PERIATHOPPU SRINVASAPERUMAL KOIL STREET IN DN;20, UNIT;5, ZONE;02.",Own Sources,2,2015-16,2016-17 NB/2015-16/17029,Storm Water Drain,Completed,NB-MANALI,20,222000,"PROVIDING S W D AT SRINIVASAPERUMAL KOIL KEELANDAI STREET 2ND LANE AT DN;20, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17031,Buildings,Completed,NB-MANALI,20,265000,"PROVIDING S W D AT SRINIVASAPERUMAL KOIL KEELANDAI ST. 4TH LANE AT DN;20, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17034,Storm Water Drain,Completed,NB-MANALI,20,365000,"PROVIDING S W D WORK AT LAL BHAGATHUR SHASTRI 1ST , 2ND, AND 3RD CROSS LANE IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17141,Storm Water Drain,Completed,NB-MANALI,20,135000,"PROVIDING S W D WORKS AT RAJEEV GANDHI CROSS STREET IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17178,Storm Water Drain,Completed,NB-MANALI,20,428000,"RAISING AND IMPROVEMENT WORKS OF S W D AT CHANDRAN STREET IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17190,Storm Water Drain,Completed,NB-MANALI,20,998000,"RAISING AND IMPROVEMENT WORKS OF S W D AT RAJEEVE GANDHI STREET IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17501,Storm Water Drain,Completed,NB-MANALI,18,955000,"RAISING AND IMPROVEMENT TO EXISTING S W D AT 10 TH STREET ( VAIKADU VILLAGE) in dn;18, unit;5, zone;ii.",Own Sources,2,2015-16,2016-17 NB/2015-16/17502,Storm Water Drain,Completed,NB-MANALI,18,827000,"RAISING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT CPCL 8TH CROSS STREET & 9TH STREET(VAIKADU VILLAGE) IN DN-18,U-5,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/17534,Buildings,Completed,B-Buildings,21,998000,"PROPOSED ADDITIONAL CONSTRUCTION OF PRIMARY HEALTH CENTER FIRST FLOOR BUILDING AT NEDUNZHIYAN STREET IN DN 21, UNIT;05, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17536,Parks,Completed,NB-MANALI,20,365000,"IMPROVEMENT WORKS FOR LAKE VIEW PARK AT CHINNAMATHUR ROAD IN DN;20, UNIT;5, ZONE02.",Own Sources,2,2015-16,2016-17 NB/2015-16/17538,Buildings,Completed,B-Buildings,21,580000,"ELECTRICAL WORK& PLUMPING WORKS AND FINISHING WORKS IN PRIMARY HEALTH CENTER FIRST FLOOR AT NEDUNZHIYAN STREET, IN DN;21, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17851,Storm Water Drain,Completed,NB-MANALI,21,750000,"DE-SILTIG AND IMPROVEMENT TO S W D WORKS AR VARATHARAJAN STREET IN DN;21, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17852,Storm Water Drain,Completed,NB-MANALI,21,998000,"DE-SILTING AND IMPROVEMENT TO S W D WORKS AT SANNATHY STREET ( FROM E.V.R PERIYAR STREET TO KAMARAJAR SALAI ) IN DN;21, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17853,Storm Water Drain,Completed,NB-MANALI,21,550000,"RAISING AND IMPROVEMENT WORKS OF S W D AT KATKANJI STREET IN DN;21, UNIT;05, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17854,Storm Water Drain,Completed,NB-MANALI,21,350000,"DE-SILTING AND IMPROVEMENT WORKS TO S W D AT SRINIVASAN 2ND LANE IN DN;21, UNIT;05, ZONE ,2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17855,Storm Water Drain,Completed,NB-MANALI,21,360000,"DE-SILTING AND IMPROVEMENTS WORKS TO S W D AT THAMARAIKULAM CROSS STREET IN DN;21, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/17856,Buildings,Completed,NB-MANALI,16,993000,"CONSTRUCTION OF RANDOM RUBBLE MASONRY WALL TO KULAKARAI SALAI POND EAST SIDE IN DN; 16, U;4, Z;2.",Own Sources,2,2015-16,2017-18 NB/2015-16/17857,Buildings,Completed,NB-MANALI,16,993000,"CONSTRUCTION OF RANDOM RUBBLE MASONRY WALL TO KULAKARAI SALAI POND NORTH SIDE IN DN; 16, U;4, Z;2.",Own Sources,2,2015-16,2017-18 NB/2015-16/17886,Roads,Completed,NB-MANALI,21,998000,PROVIDING CEMENT CONCRETE FLOORING FOR (NORTH WEST SIDE) MANALI BUS STAND AT NEDUNCHEZIYAN STREET IN DN-21 U-5 ZN-2,Own Sources,2,2015-16,2016-17 NB/2015-16/17887,Roads,Completed,NB-MANALI,21,998000,PROVIDING CEMENT CONCRETE FLOORING FOR(NORTH EAST SIDE)MANALI BUS STAND AT NEDUNCHEZIYAN STREET IN DN-21 U-5 ZN-2,Own Sources,2,2015-16,2016-17 NB/2015-16/17956,Buildings,Completed,NB-MANALI,19,990000,"CONSTRUCTION OF COMPOUND WALL & IMPROVEMENTS OF OPEN SPACE INSIDE THE ICDS CENTER NO;22 AT ATHIKULAM STREET & PROVIDING RWH AT VARIOUS ROADS IN DN-19,U-5,Z-2",Own Sources,2,2015-16,2016-17 NB/2015-16/18047,Buildings,Completed,NB-MANALI,16,993000,"CONSTRUCTION OF RANDOM RUBBLE MASONRY WALL TO KANNIAMMANPET KANNI KOIL STREET POND (SOUTH SIDE PART)IN DN; 16, U;4, Z;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/18188,Buildings,Completed,NB-MANALI,17,230000,"DRAINAGE AND ELECTRICAL FACILITIES TO TOILET BLOCK AT THIYAGI VISWANANDHA DASS NAGAR IN THEEYAMBAKKAM IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/18204,Buildings,Completed,NB-MANALI,19,997000,"Proposed construction of Compound wall for all around NNMP shed at MMDA 15th street in Dn-19, U-5, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/18410,Electrical,Completed,NB-MANALI,19,632400,"Supply and Erection of 5 Nos of 6 mtr G I lamp post withSingle Arch bracket with 40w -50w LED Fitting set at MMDA 2nd MAIN Road PARK , Ward-19, Zone-II, Manali .",Own Sources,2,2015-16,2019-20 NB/2015-16/18411,Electrical,Completed,NB-MANALI,19,861900,"Supply and Erection of 15 Nos of 6 mtr G I lamp post with Double Arch bracket with 90w -120w LED Fitting set at MMDA 2nd MAIN Road PARK , Ward-19, Zone-II, Manali .",Own Sources,2,2015-16,2019-20 NB/2015-16/18753,Buildings,Completed,NB-MANALI,16,999000,"CONSTRUCTION OF ADDTIONAL TOILET BLOCK AT SADAIYANKUPPAM IN DN-16,UNIT-4,ZONE-II",Own Sources,2,2015-16,2016-17 NB/2015-16/18782,Buildings,Completed,NB-MANALI,19,988000,"SUPPLYING LMV AND LABOURS FOR LOADING AND UNLOADING FOOD MATERIALS SUPPLIED FROM FOOD RELIVE CENTER TO RELIVE CAMP IN-19, U-5, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/19023,Storm Water Drain,Completed,NB-MANALI,21,999000,"DE-SILTING AND IMPROVEMENTS TO S W D AT P.R.K SHARMA STREET( FROM E.V.R PERIYAR STREET TO KAMARAJAR SALAI ) IN DN-21, UNIT-5, ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/19449,Roads,Completed,NB-MANALI,19,617000,"FACE LIFTING OF FLOOD RELIEF CENTER (GOVT.HIGHER SECONDARY SCHOOL) ENTRANCE AT MMDA 3rd MAIN ROAD & M.G.R.STREET IN DN-19, U-5, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/19538,Buildings,Completed,B-Buildings,21,998000,"CONSTRUCTION OF COMPOUND WALL FOR PRIMARY HEALTH CENTRE AT NEDUNCHEZHIAN STREET IN DN-21,U-5,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/2203,Roads,Completed,NB-MANALI,16,150000,"PROVIDING NAME BOARDS ,HOT APPLIED THERMO PLASTIC COMPOUND AND FIXING UDIRECTIONAL REFLECTIVE PAVEMENT MARKER (RPM) OR ROAD STUDS BONED TO SPEED BREAKERS AT ELANTHANOOR PERUMAL KOIL STREET AND TNHB PHASE 1 60 FEET ROAD IN DN-16 UN-4 ZN-2",Own Sources,2,2015-16,2016-17 NB/2015-16/22915,Roads,Completed,NB-MANALI,19,4179000,"STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT MMDA 1ST MAIN ROAD ,div -19 , UNIT -5, Z-02.",Loans And Grants,2,2015-16,2016-17 NB/2015-16/22921,Roads,Completed,NB-MANALI,19,6617000,"STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT MMDA 2nd MAIN ROAD ,div -19 , UNIT -5, Z-02.",Loans And Grants,2,2015-16,2016-17 NB/2015-16/22932,Roads,Completed,NB-MANALI,19,4405000,"STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT MMDA 3rd MAIN ROAD ,div -19 , UNIT -5, Z-02.",Loans And Grants,2,2015-16,2016-17 NB/2015-16/22935,Roads,Completed,NB-MANALI,18,288000,"STRENTHENING AND LAYING BT ROAD BY BAVER FINISHER AT RAJABATHUR STREET ,div -18 , UNIT -05, Z-02.",Loans And Grants,2,2015-16,2016-17 NB/2015-16/23030,Storm Water Drain,Completed,NB-MANALI,20,998000,"RAISING AND IMPROVEMENT WORKS OF S W D AT OTRAIVADAI STREET IN DN;20, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23035,Storm Water Drain,Completed,NB-MANALI,20,998000,"PROVINDING WORKS OF S W D AT SRINIVASAPERUMAL KOIL 1ST, 2ND , 5TH, 6TH AND 8TH CROSS LANE IN DN;20, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23041,Storm Water Drain,Completed,NB-MANALI,20,798000,"RAISING AND IMPROVEMENT WORKS OF S W D AT VENU GOPAL STREET IN DN;20, U;5, Z;II .",Own Sources,2,2015-16,2016-17 NB/2015-16/23043,Storm Water Drain,Completed,NB-MANALI,20,750000,"IMPROVEMENT WORKS OF S W D AT SANTHANA KRISHNAN 2ND AND 3RD LANE AND LALBHAGATHUR SHASTRI CROSS 2ND AND 3RD LANE IN DN;20, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23052,Storm Water Drain,Completed,NB-MANALI,20,500000,"PROVINDING WORKS OF S W D AT SRINIVASAPERUMAL KOIL 4TH , AND 7TH CROSS LANE IN DN;20, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23300,Storm Water Drain,Completed,NB-MANALI,18,585000,"IMPROVEMENT WORKS OF S W D AT CPCL 1ST CROSS STREET IN DN;18, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/23301,Storm Water Drain,Completed,NB-MANALI,18,301000,"RAISING AND IMPROVEMENT WORKS OF S W D AT NERUJI 1ST LANE IN DN;18, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/23309,Storm Water Drain,Completed,NB-MANALI,18,500000,"IMPROVEMENT WORKS OF S W D AT NERUJI 2ND LANE IN DN;18, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/23312,Storm Water Drain,Completed,NB-MANALI,18,790000,"RAISING AND IMPROVEMENT WORKS OF S W D AT GRAMA STREET IN DN;18, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23319,Storm Water Drain,Completed,NB-MANALI,18,998000,"RAISING AND IMPROVEMENT WORKS OF S W D AT CPCL 3 RD CROSS STREET ( FROM CHAINAGE 0 M TO 104M) IN DN;18, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23335,Storm Water Drain,Completed,NB-MANALI,18,350000,"RAISING AND IMPROVEMENT WORKS OF S W D PART( FROM 104M TO 128M) AT CPCL 3 RD CROSS STREET IN DN;18, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23342,Storm Water Drain,Completed,NB-MANALI,18,370000,"RAISING AND IMPROVEMENT WORKS OF S W D AT ZHAHEER HUSAIN 2ND , 3RD CROSS LANE IN DN;18, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23347,Storm Water Drain,Completed,NB-MANALI,18,505000,"RAISING AND IMPROVEMENT WORKS OF S W D AND C. C ROAD AT SALAIMANAGAR CROSS LANE IN DN;18, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/2336,Roads,Completed,NB-MANALI,17,280000,"PROVIDING AND FIXING GAS CONNECTION,TRUSS AND SHEET FOR AMMA CANTEEN AT VADAPERUMBAKKAM IN MRH ROAD (NEAR COMMUNITY CENTER CHINNATHOPPU)IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/23515,Storm Water Drain,Completed,NB-MANALI,21,950000,"DE-SILTING AND IMPROVEMENTS TO S W D AT JALAKANDA MARIAMMAN KOIL STREET IN DN;21, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/23722,Buildings,Completed,NB-MANALI,16,420000,"PROVIDING VINYL FLOORING AND GYM APPARATES TO THE EXISTING GYM BUILDING AT ADJECENT TO KANNIAMMANPET BURIAL GROUND IN DN-16,UN-4,ZN-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23725,Road Cut,Completed,NB-MANALI,16,130000,"IMPROVEMENTS AND REPAIR WORK P C TOILET AT KADAPAKKAM VICHURE LINK ROAD IN DN -16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23727,Road Cut,Completed,NB-MANALI,16,145000,"IMPROVEMENTS AND REPAIR WORK FOR CHENNAI MIDDLE SCHOOL AT ANDARKUPPAM IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23728,Buildings,Completed,NB-MANALI,16,310000,"CONSTRUCTION OF ENTRANCE PATHWAY FLOORING FOR GYM BUILDING AT KANNIAMMANPETTAI BURIAL GROUND IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23729,Buildings,Completed,NB-MANALI,16,160000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT SADAYANKUPPAM IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23730,Buildings,Completed,NB-MANALI,16,165000,"IMPROVEMENTS AND REPAIR WORK FOR UNIT OFFICE-4 AT ANDARKUPPAM REDHILLS ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23731,Road Cut,Completed,NB-MANALI,16,930000,"PROPOSED CONSTRUCTION COMPOUND WALL PARK (EAST AND NORTH SIDE) AT NEHRU NAGAR (M.R.B NAGAR) IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2017-18 NB/2015-16/23732,Buildings,Completed,NB-MANALI,16,980000,"PROPOSED CONSTRUCTION COMPOUND WALL PARK (WEST AND SOUTH SIDE) AT NEHRU NAGAR (M.R.B NAGAR) IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2017-18 NB/2015-16/23733,Road Cut,Completed,NB-MANALI,16,980000,"PROPOSED CONSTRUCTION COMPOUND WALL PLAY FILED (NORTH AND EAST SIDE) AT NEHRU NAGAR (M.R.B NAGAR) IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23735,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION COMPOUND WALL PLAY FILED (SOUTH AND EAST SIDE) AT NEHRU NAGAR (M.R.B NAGAR) IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23736,Buildings,Completed,NB-MANALI,16,650000,"PROPOSED CONSTRUCTION COMPOUND WALL PLAY FILED (WEST SIDE) AT NEHRU NAGAR (M.R.B NAGAR) IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23737,Roads,Completed,NB-MANALI,16,850000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KANNIYAMMANPET GANGAIYAMMAN KOIL STREET,V.O.C STREET,VINAYAGAR KOIL STREET,PERUMAL KOIL STREET,KANNIYAMMAN KOIL STREET AND KANNIYAMMANPET 2 GANGAIAMMAN KOIL STREET,PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/23739,Road Cut,Completed,NB-MANALI,16,860000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KADAPAKKAM MAIN ROAD PERUMAL KOIL STREET LINK ROAD,KADAPAKKAM ANDARKUPPAM REDHILLS LINK ROAD IN DN-16,U-4,Z-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/23744,Road Cut,Completed,NB-MANALI,16,960000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KANNIAMMAN KOIL LINK STREET,KAMARAJPURAM KADAPAKKAM LINK ROAD,KAMARAJPURAM 1ST,2ND,3RD,4TH,5TH STREET,KAMARAJPURAM BHARATHI STREET IN DIVISION-16,UNIT-4, ZONE-2.",Deposit Works,2,2015-16,2016-17 NB/2015-16/23745,Buildings,Completed,NB-MANALI,16,360000,"PROVIDING HUME PIPE ACROSS THE FLOOD DAMAGED ROAD PORTION AT MANALI NEWTOWN 23RD MAIN ROAD,18TH MAIN ROAD,ANDARKUPPAM PERUMAL KOIL STREET,ANDARKUPPAM MAIN ROAD AND KANNIAMMAN KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23746,Buildings,Completed,NB-MANALI,16,100000,"PROVIDING RAIN WATER HARVESTING TO CPS 1,3&5 AT MANALI NEWTOWN IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23747,Road Cut,Completed,NB-MANALI,16,132000,"REPAIRS TO BUS SHELTER @ TPP SALAI (JUNCTION OF ANDARKUPPAM REDHILLS MAIN ROAD) IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23748,Buildings,Completed,NB-MANALI,16,45000,"PROVIDING INSPECTION CHAMBER AND LAYING PVC PIPE ACROSS THE ROAD @ANDARKUPPAM LANE IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/23749,Road Cut,Completed,NB-MANALI,16,450000,"RESTORATION OF ROAD CUT MADEBY CMWSSB WITH KADAPAKKAM VICHURE LINK ROAD IN DN-16,U-4,Z-2.",Deposit Works,2,2015-16,2016-17 NB/2015-16/23752,Road Cut,Completed,NB-MANALI,16,750000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT SADAYANKUPPAM 1ST,2ND,3RD,4TH STREET,SADAYANKUPPAM PERUMAL KOIL STREET AND SADAYANKUPPAM AMMAN KOIL STREET IN DIVISION-16,UNIT-4, ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/2376,Buildings,Completed,NB-MANALI,17,840000,"CONSTRUCTION OF COMPOUND WALL ,GATE AND GATE PILLAR AT SOUTH SIDE (PART) OF BURIAL GROUND AT SAMUVEL NAGAR IN DN-17,U-4,Z-II",Own Sources,2,2015-16,2016-17 NB/2015-16/23901,Buildings,Completed,NB-MANALI,16,980000,"SUPPLYING AND WORKING,LABOURS,TRACTOR,DIESEL ENGINE & TATA ACE FOR FLOOD DAMAGED AREA IN DIVISION-DN-15,DN-16,DN-17,UNIT-04,ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/24309,Buildings,Completed,NB-MANALI,19,510000,"ANNUAL MAINTENANCE WORKS FOR ROAD, PARK,BUILDING IN DN -19, U -05, ZONE -2.",Own Sources,2,2015-16,2016-17 NB/2015-16/24310,Parks,Completed,NB-MANALI,19,999000,"PROVIDING WATER FACILITIES ARRANGEMENT TO INSIDE THE PARK AT MMDA 2ND MAIN ROAD IN DIVISION -19, UNIT -05,ZONE -2.",Own Sources,2,2015-16,2016-17 NB/2015-16/24702,Roads,Completed,NB-MANALI,15,683000,"Forming and strengthening Road at Lakshmi nagar 1st cross street & 2nd cross street in Dn-15, U-05, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/24713,Roads,Completed,NB-MANALI,15,987000,"Forming and strengthening Flood Damaged Road at 7th street manali new town & old nappalaiyam road in Dn-15, U-05, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/24907,Roads,Completed,NB-MANALI,20,998000,"SUPPLYING AND FIXING OF REFLECTIVE STREET NAME BOARD(46Nos) AT VARIOUS STREET IN DN-20,UN-5 Z-2",Own Sources,2,2015-16,2016-17 NB/2015-16/24908,Roads,Completed,NB-MANALI,20,520000,"SUPPLYING AND FIXING OF REFLECTIVE STREET NAME BOARD(27Nos) AT VARIOUS STREET IN DN-20,UN-5 Z-2",Own Sources,2,2015-16,2016-17 NB/2015-16/25030,Buildings,Completed,NB-MANALI,16,730000,"IMPROVEMENT TO YOGA AND MEDITATION HALL AT MANALI NEW TOWN CPS 4 IN DN-16 , U-4, Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/25181,Roads,Completed,NB-MANALI,17,980000,"Forming and strengthening Flood damaged roads at puzhal union road in division 17, unit - 04, zone-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/25365,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR KOSAPUR SRI VEMBULI AMMAN KOIL POND GATE AND GATE PILLAR EASTSIDE AND SOUTHSIDE IN DN-17,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/25420,Buildings,Completed,NB-MANALI,15,930000,"Restoration of Road cut Made by CMWSSB at Edayanchavdi main Road In DN-15,U-4,ZN-2",Deposit Works,2,2015-16,2016-17 NB/2015-16/25528,Buildings,Completed,NB-MANALI,15,998000,"Improvements to chennai middle school at manali new town in dn-15, U-4, Z-2",Own Sources,2,2015-16,2016-17 NB/2015-16/25562,Buildings,Completed,NB-MANALI,15,997000,"Construction of Dining hall At CPS Old nappalaiyam in Dn-15, U-05, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/25575,Roads,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR KOSAPUR SRI VEMBULI AMMAN KOIL POND WEST SIDE AND NORTH SIDE IN DN-17,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/25578,Roads,Completed,NB-MANALI,17,924000,"PROVIDING IMPROVEMENTS TO FOOTPATH,ROAD AND OTHER MAINTENANCE WORK IN DN-17,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/25582,Buildings,Completed,NB-MANALI,17,980000,"RESTORATION OF ROAD - CUT MADE BY TANGEDCO AT VADAPERUMBAKKAM PERUMAL KOVIL STREET, OTTRAVADAI STREET AND ANNA STREET IN DN-17, U-4, Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/25658,Roads,Completed,NB-MANALI,18,61062,"ATTENDING PATCH WORKS AT NERUJI 2ND,3RD STREET,ANNA 5TH CROSS STREET,ANNA 4TH CROSS STREET,GRAMMA STREET,1STREET,ANNA STREET 4TH LANE AND OTHERS. IN DN;18, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/26176,Storm Water Drain,Completed,NB-MANALI,15,990000,"Road cut Restoration at Edayanchavdi main Road From amma canteen In DN-15,U-4,ZN-2",Deposit Works,2,2015-16,2016-17 NB/2015-16/26178,Road Cut,Completed,NB-MANALI,15,780000,"Road cut Restoration at Edayanchavdi main Road From Gangai Amman koil (0-225) In DN-15,U-4,ZN-2",Deposit Works,2,2015-16,2017-18 NB/2015-16/26239,Buildings,Completed,NB-MANALI,19,481000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENT FOR 16TH CEREMONY SHED AT M M D A 2ND ROAD IN DN-19, UNIT-5, ZONE-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/26606,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT ELANDANUR PERUMAL KOIL STREET IN DIVISION-16,UNIT-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/26725,Parks,Completed,NB-MANALI,18,965000,"MAINTENANCE OF PARK AND PLAY FIELD AREAS FOR FOUR MONTHS IN DIVISION 15, 16, 17, 18, 19, 20 & 21, UNIT 04 & 05, ZONE 02.",Own Sources,2,2015-16,2016-17 NB/2015-16/26730,Storm Water Drain,Completed,NB-MANALI,21,475000,"DE-SILTING AND IMPROVEMENT TO S W D AT RATHAKRISHAN STREET ( E.V.R. PERIYAR STREET TO POONGAVANAM STREET) AND IMPROVEMENT TO 2NOs.OF DRAIN CULVERT IN DN;21, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/26809,Footpath,Completed,NB-MANALI,18,494000,"CONSTRUCTION OF FOOT PATH WAY FOR SIVAN KOIL OPPOSITE AT BHARATHIAR STREET IN DN ;18, UNIT;05, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/2731,Buildings,Completed,NB-MANALI,16,999000,"PROPOSED CONSTRUCTION OF COMPOUND TO EAST SIDE OF BURIAL GROUND TO KULAKARAI(K.G.L NAGAR) IN DN-16,UN-4,ZN-2",Own Sources,2,2015-16,2016-17 NB/2015-16/27417,Roads,Completed,NB-MANALI,19,834000,"REPAIRS AND IMPROVEMENT TO EXISTING AMMA UNAVAGAM AT KAMRAJ STREET, MANJAMBAKKAM IN DN-19, UNIT-5,ZONE-2",Own Sources,2,2015-16,2016-17 NB/2015-16/27600,Roads,Completed,NB-MANALI,16,965000,"ATTENDING PATCH WORK AT BURMA NAGAR 1ST STREET TO 3RD STREET,BURMA NAGAR 12TH STREET TO16TH STREET AND ELANTHANOOR PERUMAL KOIL STREET IN DN-16,UNIT-4,ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/27601,Roads,Completed,NB-MANALI,16,990000,"ATTENDING PATCH WORK AT SADAYAANKUPPAM 1ST STREET TO 4TH STREET,MANALI NEWTOWN 80TH STREET TO 91ST STREET IN DN-16,UNIT-4,ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/27602,Roads,Completed,NB-MANALI,16,930000,"LAYING THE B.T. ROAD PATCH WORK AT MANALI NEWTOWN 63RD STREET TO 79TH STREET,M.N.T 78TH BLOCK 21ST MAIN ROAD,124TH BLOCK 22ND MAIN ROAD,130TH BLOCK 23RD MAIN ROAD IN DN-16,UNIT-4,ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/27622,Roads,Completed,NB-MANALI,15,990000,"Attending patch work At Old colony 1st & 2nd street, Chinna eachanguzhi salai (TH road to End) Lakhmi Nagar 1st,2nd & 3rd Street,New Napalayam Gangai amman koil 2nd corss street, Edayanchavadi cross street,Manali New Town 36th block 16feet road 2nd street,in DN-15, U-04, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/27623,Roads,Completed,NB-MANALI,15,982000,"Attending patch work At Manali New Town 5th block10th Main road, Manali New Town 10th block 16th street, Manali New Town 42th block 17th,18th,19th,20th & 21th street, In DN-15, U-04, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/27624,Roads,Completed,NB-MANALI,15,975000,"Attending patch work At Manali New Town 42th block road 22th,23th street, Manali New Town 44th block road 25th street, Manali New Town 31th block road 32th street, Periya Eachanguzhi street,New colony cross street in DN-15, U-04, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/27625,Roads,Completed,NB-MANALI,15,948699,"Attending patch work At Old Napalayam salai, New colony main street , New colony 1st street New colony 2nd street New colony 3rd street, Manali new town 8th main road, 28th street and 7th block in DN-15, U-04, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/27626,Roads,Completed,NB-MANALI,15,368000,"Attending patch work At Edyanchavadi Cross street,Old Nappalayam New Colony (Gangaiamman Koil Street),New Napalayam gangaiamman koil 1st Cross street,New Napalayam perumalkoil street extension road In DN-15, U-04, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/2767,Buildings,Completed,NB-MANALI,19,920000,"IMPROVEMENTS TO DIVISION OFFICE, CI ROOM, SI ROOM AND LABOUR SHED AT 2nd MAIN ROAD MMDA MATHUR IN DN 19 U 5 Z2",Own Sources,2,2015-16,2016-17 NB/2015-16/27867,Buildings,Completed,NB-MANALI,19,990000,"CONSRTUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 107 TH STREET IN DN-19, UNIT-5, ZONE-2",Own Sources,2,2015-16,2016-17 NB/2015-16/27972,Buildings,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF COMPOUND WALL AT FRONT SIDE AND OTHER SIDE TO OSR LAND (NO. 73) @ REDHILLS ROAD (AVP ROAD) IN DN;18,UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/28133,Storm Water Drain,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF COMPOUND WALL (0 M TO 85M) TOWARDS EASTERN SIDE TO OSR LAND (NO. 73) @ REDHILLS ROAD (AVP ROAD) IN DN;18,UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/28421,Storm Water Drain,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF RETAINING WALL AT CPCL LAYOUT BURIAL GROUND ROAD(REACH-1) IN DN-18,U-5,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/28422,Buildings,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF RETAINING WALL AT CPCL LAYOUT BURIAL GROUND ROAD (REACH-2) IN DN-18,U-5,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/28423,Buildings,Completed,NB-MANALI,18,541000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT CPCL CREMATORIUM IN DN-18, U-5, Z-2.",Own Sources,2,2015-16,2018-19 NB/2015-16/28431,Buildings,Completed,NB-MANALI,19,375000,"Supplying and Fixing of stainless steel for warmup area in side of the park At MMDA 2nd main Road in Dn-19, U-05, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/28438,Buildings,Completed,NB-MANALI,19,998000,"Addition Improvement Work for Gazebo in side the park At MMDA 2nd main Road in Dn-19, U-5, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/28506,Buildings,Completed,NB-MANALI,20,599000,"RAISING AND PROVIDING CC ROAD AROUND TEMPLE AND TEMPLE TO MAIN ROAD IN DIVISION 20, UNIT 05, ZONE 02.",Own Sources,2,2015-16,2016-17 NB/2015-16/28572,Buildings,Completed,NB-MANALI,19,999000,"CONSTRUCTION OF TOILET BLOCK (4+4) AT PONNIAMMAN KOIL BURIAL GROUND STREET IN DN-19,UNIT-05,ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/29376,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT KANNIAMMAN PAT II PERUMAL KOIL STREET IN DIVISION-16,UNIT-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/29377,Buildings,Completed,NB-MANALI,21,998000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT KADAPPAKKAM MAIN ROAD IN DIVISION-16,UNIT-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/29383,Roads,Completed,NB-MANALI,16,935000,"LAYING OF CEMENT CONCRETE ROAD AT ANDAR KUPPAAM LANES IN DN;16, UNIT;4, ZONE.II.",Own Sources,2,2015-16,2016-17 NB/2015-16/29384,Roads,Completed,NB-MANALI,16,935000,"LAYING OF CEMENT CONCRETE ROAD AT KANNIAMMAN KOIL AND GANGAIAMMAN KOIL STREET IN DN;16, UNIT;4, ZONE.II.",Own Sources,2,2015-16,2016-17 NB/2015-16/29705,Storm Water Drain,Completed,NB-MANALI,19,512000,"Desilting and improvements to existing storm water drain at various streets IN DN-19,UNIT-5,Z-02",Own Sources,2,2015-16,2016-17 NB/2015-16/29741,Storm Water Drain,Completed,NB-MANALI,21,998000,"DE-SILTING AND IMPROVEMENTS TO S W D AT NEDUNCHEZIYAN ST. EXTN ( CHAINAGE 0 M TO 200M).IN DN;21, UNIT;5, ZONE.II.",Own Sources,2,2015-16,2016-17 NB/2015-16/29742,Storm Water Drain,Completed,NB-MANALI,21,620000,"IMPROVEMENT TO FOOT PATH NEDUNCHEZHIYAN STREET EXTN. IN DN 21, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/29744,Storm Water Drain,Completed,NB-MANALI,21,998000,"DE-SILTING AND IMPROVEMENTS TO S W D AT NEDUNCHEZIYAN ST EXTN ( CHAINAGE 200 M TO 400M).IN DN;21, UNIT;5, ZONE.II.",Own Sources,2,2015-16,2016-17 NB/2015-16/29784,Buildings,Completed,NB-MANALI,21,420000,"IMPROVEMENT TO CPS AT PADASALAI STREET IN DN;21, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/29878,Buildings,Completed,NB-MANALI,19,999600,"CONSTRUCTION OF COMPOUND WALL AND SEPTIC TANK AT PONNIAMMAN KOIL BURIAL GROUND STREET IN DN-19,UNIT-05,ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/30009,Roads,Completed,NB-MANALI,17,998000,"FORMING AND LAYING ROAD WITH GSB AND WMM AT AMBETHKAR 3RD STREET KOSAPURE IN DN-17,UNIT02,ZONE-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/30384,Storm Water Drain,Completed,NB-MANALI,21,940000,"DESILTING AND IMPROVEMENTS T0 SWD AT AMBEDKAR STREET(FROM ANBALAGAN STREET TO E.V.R PERIYAR STREET) IN DN-21,U-5,ZN-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/30385,Storm Water Drain,Completed,NB-MANALI,21,990000,"DESILTING AND IMPROVEMENTS T0 SWD AT AMBEDKAR STREET(FROM E.V.R PERIYAR STREET TO KAMARAJ STREET) IN DN-21,U-5,ZN-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/30387,Storm Water Drain,Completed,NB-MANALI,21,940000,"DESILTING AND IMPROVEMENTS T0 SWD AT SRINIVASAN STREET(FROM ANBALAGAN STREET TO E.V.R PERIYAR STREET) IN DN-21,U-5,ZN-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/30389,Storm Water Drain,Completed,NB-MANALI,21,990000,"DESILTING AND IMPROVEMENTS T0 SWD AT SRINIVASAN STREET(FROM E.V.R PERIYAR STREET TO KAMARAJ STREET) IN DN-21,U-5,ZN-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/30390,Storm Water Drain,Completed,NB-MANALI,21,580000,"DESILTING AND IMPROVEMENTS T0 SWD AT THIRUVENKADAM STREET(FROM ANBALAGAN STREET TO THIRUVALLUVAR STREET) IN DN-21,U-5,ZN-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/30406,Buildings,Completed,NB-MANALI,16,998000,"CONSTRUCTION OF COMPOUND WALL TO CMS ANDARKUPPAM IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/30408,Buildings,Completed,NB-MANALI,16,998000,"CONSTRUCTION OF COMPOUND WALL TO CPS KULAKARAI IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/30491,Buildings,Completed,NB-MANALI,16,998000,"CONSTRUCTION OF COMPOUND WALL TO VACANT LAND SOUTH AND EAST SIDE AT KANNIAMMANPET 2 PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2017-18 NB/2015-16/30492,Buildings,Completed,NB-MANALI,16,998000,"CONSTRUCTION OF COMPOUND WALL TO VACANT LAND WEST AND NORTH SIDE AT KANNIAMMANPET 2 PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2017-18 NB/2015-16/30670,Storm Water Drain,Completed,NB-MANALI,18,998000,"DE-SILTING , RAISING AND IMPROVEMENT WORKS OF S W D AT LABBAI MEDU SHEIK ANSARI STREET ( PART),SHEIK ANSARI 1ST & 2ND STREET AND A.F. GARDERN 1ST STREET EXTENSION IN N;18, UNIT;5, ZONE;II",Own Sources,2,2015-16,2016-17 NB/2015-16/31291,Roads,Completed,NB-MANALI,19,661000,"FORMING AND LAYING FLOOD DAMAGE ROADS AT SRINIVASA NAGAR CROSS STREET IN DN-19,U-5,Z-2(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/31311,Roads,Completed,NB-MANALI,19,658000,"FORMING AND LAYING FLOOD DAMAGE ROAD AT SRINIVASA NAGAR MAIN ROAD IN DN-19,U-5,Z-2(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/31344,Buildings,Completed,NB-MANALI,19,999000,"Construction of additional class room inside the C.M.S campus at kamaraj salai(manjambakkam) in DN-19,UN-5,Z-02(MANALI)",Own Sources,2,2015-16,2019-20 NB/2015-16/31395,Buildings,Completed,NB-MANALI,19,998000,"Proposed construction of Dinning Hall for Amma Unavagam at MMDA 4th Cross Street in dn-19,un-05,zn-02(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/31491,Culvert,Completed,NB-MANALI,19,996000,"Construction of Box Culvert Double Vent of size (3000mm X 3000mm) at M.G.R street in Dn-19,Un-05,Z-02(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/31557,Buildings,Completed,NB-MANALI,19,999000,"Construction of compound wall,sump,water supply and Electrical arrangements to Amma Unavagam at MMDA 4th cross street in Dn-9,un-05,zn-02(manali)",Own Sources,2,2015-16,2016-17 NB/2015-16/31707,Roads,Completed,NB-MANALI,19,259000,"Forming and laying flood damaged road at Telecom Nagar 2nd cross street in Dn-19, U-5, Z-02.",Own Sources,2,2015-16,2016-17 NB/2015-16/31812,Storm Water Drain,Completed,NB-MANALI,21,500000,"DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN AT POONGAVANAM STREET SOUTH SIDE(FROM THIRU.VI.KA STREET TO JALAGANDAMARIAMMAN KOIL 3RD LANE)IN DIVISION-21,UNIT-5,ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/31833,Roads,Completed,B-Buildings,21,580000,"CONSTRUCTION OF SECURITY ROOM AND IMPROVEMENTS TO PRIMARY HEALTH CENTER IN FIRST FLOOR AT NEDUNZHIYAN STREET IN DN-21,UNIT-5,ZONE-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/31856,Buildings,Completed,NB-MANALI,20,584000,"ANNUAL MAINTENANCE FOR BUILDINGS, PARKS, ROADS AND BURIAL GROUNDS ETC., IN DIVISION 20, UNIT 05, ZONE 02.",Own Sources,2,2015-16,2016-17 NB/2015-16/31865,Buildings,Completed,NB-MANALI,19,543000,"REPAIR AND IMPROVEMENT TO EXISTING RAIN WATER HARVESTING OPEN WELL AND PROVIDING RAIN WATER HARVESTING INSIDE THE PARK AND OSR LANDS AT VARIOUS STREETS IN DN-19,UN-5,ZN-02(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/31963,Storm Water Drain,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF NEW CULVERT AND SUPPLYING AND FILLING WITH GOOD EARTH AT AAMULLAIVOYAL - VAIKADU ROAD IN DIV - 18, U - 5, Z - 2.",Own Sources,2,2015-16,2017-18 NB/2015-16/31965,Storm Water Drain,Completed,NB-MANALI,18,914000,"MAINTENANCE WORKS FOR BUILDING , ROAD, FOOT PATHWAY, SWD, PARK , PLAY GROUND IN DN ;18, UNIT;5, ZONR;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/32003,Parks,Completed,NB-MANALI,19,940000,"PROVIDING AND FIXING PLAY APPARATUS (MINI KFS,DOUBLEBAR) INSIDE THE PARK AT MMDA 2ND MAIN ROAD IN DN-19,UN-05,ZN-2(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/32541,Parks,Completed,NB-MANALI,19,950000,"PROVIDING AND FIXING PLAY APPARATUS(KFS,SWING 4SE(FRP)) INSIDE THE PARK AT MMDA 2ND MAIN ROAD IN DN-19,UN-5,ZN-2(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/32543,Parks,Completed,NB-MANALI,19,960000,"PROVIDING AND FIXING PLAY APPARATUS(LONDON BRIDGE(1),SWING 2SE(BUCH)) INSIDE THE PARK AT MMDA 2ND MAIN ROAD IN DN-19,UN-5,ZN-2(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/32605,Road Cut,Completed,NB-MANALI,17,660000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KOSAPUR PERUMAL KOIL MAIN ROAD(PHASE-II) IN DIVISION-17,UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/32606,Road Cut,Completed,NB-MANALI,17,430000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KOSAPUR PERUMAL KOIL MAIN ROAD PHASE-2 (PART)IN DIVISION-17,UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/32607,Road Cut,Completed,NB-MANALI,17,470000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KOSAPUR VENUGOPAL SAMY STREET IN DIVISION-17,UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/32608,Road Cut,Completed,NB-MANALI,17,470000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KOSAPUR PADASALAI STREET IN DIVISION-17,UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/32634,Road Cut,Completed,NB-MANALI,17,240000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KOSAPUR PERUMAL KOIL 2ND CROSS STREET IN DIVISION-17,UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/32636,Road Cut,Completed,NB-MANALI,17,240000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KOSAPUR PERUMAL KOIL 3RD CROSS STREET IN DIVISION-17,UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/32638,Road Cut,Completed,NB-MANALI,17,240000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT KOSAPUR PERUMAL KOIL 4TH CROSS STREET IN DIVISION-17,UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2017-18 NB/2015-16/32641,Storm Water Drain,Completed,NB-MANALI,17,980000,"DUE TO MONSOON 2016 USING JCB AND POCLAIN FOR FORMATION OF EARTHERN CANAL AND DESILTING OF EXISTING SWD IN DIV - 17, U - 4, Z - 2",Deposit Works,2,2015-16,2017-18 NB/2015-16/32742,Roads,Completed,NB-MANALI,18,998000,"LAYING OF GOOD EARTH FILING AT VAIKKADU AMMULAVOYIL ROAD IN DN;18, U;5, ZONE;II( CHAINAGE; 0M TO 700 M)",Own Sources,2,2015-16,2016-17 NB/2015-16/32744,Roads,Completed,NB-MANALI,18,889000,"LAYING OF GOOD EARTH FILLING AND PILES AT VAIKKADU AMMULAVOYIL ROAD ( CHAINAGE; 700M TO 1020M) IN DN;18, U;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/32745,Roads,Completed,NB-MANALI,18,146000,"LAYING OF GSB, WMM ATGRAMA STREET 3RD CROSS LANE IN DN;18, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2018-19 NB/2015-16/32746,Roads,Completed,NB-MANALI,18,165000,"LAYING OF GSB, WMM AT HARIKRISHAPURAM PERUMAL KOIL LANE IN DN;18, UNIT;5, ZONE;II.",Own Sources,2,2015-16,2016-17 NB/2015-16/32798,Parks,Completed,NB-MANALI,19,442000,"PROVIDING AND FIXING PLAY APPARTUS (CEMENT BENCH,COLOUR WASHING etc.,) INSIDE THE PARK AT MMDA 2ND MAIN ROAD IN DN 19,UN-5,ZN-2(MANALI)",Own Sources,2,2015-16,2017-18 NB/2015-16/32812,Road Cut,Completed,NB-MANALI,15,998000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT VARIOUS DIVISION(15,16,17),UNIT-4,ZONE-2.",Deposit Works,2,2015-16,2016-17 NB/2015-16/32825,Roads,Completed,NB-MANALI,17,972000,"FORMING AND LAYING (GSB & WMM) AT V.S.MANI NAGAR CROSS STREET(REACH-1) (NEAR V.S.MANI NAGAR PARK) IN DN-17,UN-04,ZN-2(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/32832,Roads,Completed,NB-MANALI,17,986000,"FORMING AND LAYING (GSB & WMM) AT V.S.MANI NAGAR CROSS STREET(REACH-2) (NEAR V.S.MANI NAGAR PARK) IN DN-17,UN-04,ZN-2(MANALI)",Own Sources,2,2015-16,2016-17 NB/2015-16/32994,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF SOLID WASTE MANAGEMENT AND VERMI COMPOST UNIT AT SAMUEL NAGAR BURIAL GROUND IN DN-17, UNIT-04, ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/32995,Buildings,Completed,NB-MANALI,17,996000,"ADDITIONAL CONSTRUCTION OF SOLID WASTE MANAGEMENTS AND VERMI COMPOST UNIT IN SAMUEL NAGAR BURIAL GROUND AT DN-17, UNIT-04, ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/32996,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF CARE TAKER ROOM , TOILET ROOM AND SUMP AT SAMUEL NAGAR BURIAL GROUND AT DN-17, UNIT-04, ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/32997,Buildings,Completed,NB-MANALI,17,997000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO SOLID WASTE MANAGEMENT AND VERMI COMPOST UNIT AT SAMUEL NAGAR BURIAL GROUND IN DN-17, UNIT-04, ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/32998,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF STORE ROOM, SHREDDING MACHINERY ROOM AND FOOTPATH AT SAMUEL NAGAR BURIAL GROUND IN DN-17,UNIT-04,ZONE-02",Own Sources,2,2015-16,2016-17 NB/2015-16/33232,Roads,Completed,NB-MANALI,19,733000,"RESTORATION ROAD CUT MADE BY TANGEDCO AT CHINNA MATHUR ROAD(EXTN) IN DN-19,UN-5,ZN-2",Deposit Works,2,2015-16,2016-17 NB/2015-16/33653,Buildings,Completed,NB-MANALI,19,985000,"Proposed construction of compound wall for all around the NNMP shed at Arulanantham nagar cross street in DN-19, U-5, Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/33723,Roads,Completed,NB-MANALI,18,620000,"PROVIDING AND LAYING OF QUARRY RUBBISH AND WMM AT ESWARAN KOIL STREET( AMMAN ST) IN DN;18, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/33767,Storm Water Drain,Completed,NB-MANALI,21,584000,"DESILTING, IMPROVEMENTS AND MAINTENANCE OF STROM WATER DRAIN AT DIVISION 21, UNIT 05, ZONE 02.",Own Sources,2,2015-16,2016-17 NB/2015-16/33983,Playfields,Completed,NB-MANALI,15,990000,"CONSTRUCTION OF DISABLED TOILET AND FORMING PATHWAY IN CHILDRENS PLAY AREA AT MANALI NEW TOWN BLOCK NO 26 CPS10 IN DN.15, UNIT-4, ZONE-II",Own Sources,2,2015-16,2016-17 NB/2015-16/34701,Buildings,Completed,B-Buildings,21,730000,"PROPOSED CONSTRUCTION OF OUT PATIENT BLOCK AND RAISING GROUND FLOOR ROOF SLAB IN MEDICAL OFFICER ROOM AT PRIMARY HEALTH CENTER IN DIVISION 21, UNIT 05, ZONE 02",Own Sources,2,2015-16,2016-17 NB/2015-16/34807,Buildings,Completed,NB-MANALI,17,150000,"IMPROVEMENT WORKS TO PUBLIC CONVENIENCE AT CHINNATHOPPU IN DN-17, U-4, Z-2.",Own Sources,2,2015-16,2017-18 NB/2015-16/35109,Buildings,Completed,NB-MANALI,15,997000,"Proposed Construction of Open Auditorium CMS manali new town 35th street in Dn-15, U-4, Z-2.",Own Sources,2,2015-16,2019-20 NB/2015-16/5783,Storm Water Drain,Completed,NB-MANALI,21,800000,"PROPOSED CONSTRUCTION OF SWD AT MUNUSAMY STREET 1ST LANE,2ND LANE ,3RD LANE IN DN-18 U-5 ZN-II",Own Sources,2,2015-16,2016-17 NB/2015-16/5861,Buildings,Completed,NB-MANALI,21,900000,PROVIDING CEMENT CONCRETE FLOORING FOR MANALI BUS STAND AT NEDUNCHEZIYAN STREET (REACH 2) IN DN-21 U-5 ZN-2,Own Sources,2,2015-16,2016-17 NB/2015-16/5941,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF COMPOUND WALL IN NORTH AND WEST SIDE OF BURIAL GROUND AT KAMARAJAR SALAI , IN DN;20, UNIT; 5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/6006,Buildings,Completed,NB-MANALI,15,180000,"PROVIDING DRAINAGE ARRANGEMENT FOR PUBLIC CONVEYANCE AT OLDNAPPALAYAM IN DN-15,U-4,Z-II",Own Sources,2,2015-16,2016-17 NB/2015-16/6784,Footpath,Completed,NB-MANALI,20,998000,"PROVIDING OF HARD EARTH FILLING IN NORTH SIDE IN BURIAL GROUND AT KAMARAJAR SALAI IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/7048,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF COMPOUND WALL EAST AND SOUTH SIDE OF V.O.C PLAY GROUND AT SANTHANA KRISHNAN STREET IN DN;20, U;05, Z;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/7397,Buildings,Completed,NB-MANALI,17,990000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT VADAPERUMBAKKAM SAMUVEL NAGAR BURIAL GROUND ROAD (NEAR BY LADIES TOILET P C) IN DN-17,UN-4,ZN-2",Own Sources,2,2015-16,2016-17 NB/2015-16/7398,Buildings,Completed,NB-MANALI,17,990000,"PROPOSED CONSTRUCTION OF GYM BUILDING AT VADAPERUMBAKKAM SAMUVEL NAGAR BURIAL GROUND ROAD (NEAR BY LADIES TOILET P C) IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/7399,Buildings,Completed,NB-MANALI,17,970000,"ELECTRICAL ARRANGEMENT AND EQUIPMENT TOOL OF GYM BUILDING AT VADAPERUMBAKKAM SAMUVEL NAGAR BURIAL GROUND ROAD (NEAR BY LADIES TOILET P C) IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/7712,Buildings,Completed,NB-MANALI,18,990000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT CPCL LAYOUT 3RD CROSS STREET IN DN-18,UN-5,ZN-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/7713,Buildings,Completed,NB-MANALI,18,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL ,PLAY APPARATUS AND FOOTPATH AT CPCL LAYOUT 3RD CROSS STREET IN DN-18,U-5,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/7714,Storm Water Drain,Completed,NB-MANALI,18,950000,"RAISING AND IMPROVEMENTS TO SWD AT THIRUVALLUVAR STREET (FROM JUNCTION OF PADASALAI STREET TO SIR.C.V. RAMAN STREET) IN DN-18,U-05,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8232,Buildings,Completed,NB-MANALI,16,750000,"PROVIDING PLAY APPARATUS AND RAISING THE GROUND LEVEL TO THE EXIST OPEN LAND AT PERUMAL KOIL STREET KANNIAMMANPET-2 IN DN-16,U-4,Z-II.",Own Sources,2,2015-16,2017-18 NB/2015-16/8234,Buildings,Completed,NB-MANALI,16,284000,"PROVIDING PLAY APPARATUS TO THE CHILDREN PLAY SPACE-1 AT MANALI NEW TOWN IN DN-16,U-4,Z-II.",Own Sources,2,2015-16,2017-18 NB/2015-16/8235,Buildings,Completed,NB-MANALI,16,284000,"PROVIDING PLAY APPARATUS TO THE CHILDREN PLAY SPACE-3 AT MANALI NEW TOWN IN DN-16,U-4,Z-II.",Own Sources,2,2015-16,2017-18 NB/2015-16/8236,Buildings,Completed,NB-MANALI,16,990000,"CONSTRUCTION OF MULTIPURPOSED HALL AT RAJIV GANDHI NAGAR IN DN-16,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8238,Buildings,Completed,NB-MANALI,16,442000,"CONSTRUCTION OF OPEN AIR AUDITORIUM AT BURMA NAGAR IN DN-16,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8251,Buildings,Completed,NB-MANALI,15,990000,"CONSTRUCTION OF GYM BUILDING AT CHILDREN PLAY SPACE IN MANALI NEWTOWN 11TH MAIN ROAD IN DN-15,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8252,Buildings,Completed,NB-MANALI,15,998000,"CONSTRUCTION OF GAZEBO AT CHILDREN PLAY SPACE IN MANALI NEW TOWN 11TH MAIN ROAD IN DN-15,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8253,Buildings,Completed,NB-MANALI,15,970000,ELECTRICAL ARRAGEMENT AND EQIPMENT TOOL OF GYM BUILDING AT CHILDREN PLAY SPACE IN MANALI NEW TOWN 11TH MAIN ROAD IN DN-15 U-4 ZN-II,Own Sources,2,2015-16,2016-17 NB/2015-16/8288,Buildings,Completed,NB-MANALI,21,1999000,"PROPOSED CONSTRUCTION OF 1+1 CLASS ROOM(G F+F F) AT CPS PADASALAI STREET IN DN-21,U-5,Z-II.",MLACDS,2,2015-16,2016-17 NB/2015-16/8401,Buildings,Completed,NB-MANALI,17,540000,"ELECTRICAL AND DRAINAGE ARRANGEMENT FOR MULTIPURPOSE HALL AT VADAPERUMBAKKAM IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8404,Buildings,Completed,NB-MANALI,17,540000,"ELECTRICAL AND DRAINAGE ARRANGEMENT FOR MULTIPURPOSE HALL AT PERIYAR NAGAR IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8405,Buildings,Completed,NB-MANALI,17,580000,"ELECTRICAL AND DRAINAGE ARRANGEMENT FOR MULTIPURPOSE HALL AT THEEYAMBAKKAM IN DN-17,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/8455,Roads,Completed,NB-MANALI,19,990000,"CONSTRUCTION OF ADDITIONAL OFFICE ROOM IN WARD OFFICE 1 ST FLOOR At MMDA 2nd cross Street IN DN 19,UNIT 5 ZONE 2.",Own Sources,2,2015-16,2016-17 NB/2015-16/8512,Buildings,Completed,NB-MANALI,15,100000,"PROVIDING HOUSE KEEPING FOR CPS-9 AT MANALI NEWTOWN IN DN- 15,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/8515,Buildings,Completed,NB-MANALI,16,170000,"PROPOSED CONSTRUCTION OF ROAD SIDE TOILET ADJECENT TO CPS-5 IN DN-16,U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/8516,Storm Water Drain,Completed,NB-MANALI,16,380000,"IMPROVEMENT THE EXISTING SIDE DRAIN AT MANALI NEWTOWN 21 ST MAIN ROAD IN DN-16.U-4,Z-2.",Own Sources,2,2015-16,2016-17 NB/2015-16/8710,Storm Water Drain,Completed,NB-MANALI,20,998000,"IMPROVEMENT WORKS OF S W D AT BALARAMAN STREET ( KAMARAJ SALAI TO DOOR NO 15) IN DN;20, UNIT;05, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/8711,Storm Water Drain,Completed,NB-MANALI,20,998000,"RAISING AND IMPROVEMENT WORKS OF S W D AT BALARAMAN STREET ( DOOR NO 15TO BALARAMAN 2ND STREET ) IN DN;20, U;05, Z;02.",Own Sources,2,2015-16,2016-17 NB/2015-16/8961,Buildings,Completed,NB-MANALI,16,993000,"CONSTRUCTION OF R R MASONRY WALL TO KANNIAMMANPET KANNIKOILSTREET POND ( KANNI KOIL STREET END) TO SOUTH SIDE WALL IN DN; 16, U;4, Z;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/8963,Buildings,Completed,NB-MANALI,16,993000,"CONSTRUCTION OF R R MASONRY WALL TO KANNIAMMANPET KANNIKOILSTREET POND ( FROM KADAPPAKKAM MAIN ROAD END) TO SOUTH SIDE WALL IN DN; 16, U;4, Z;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/9063,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT NORTH SIDE OF BURIAL GROUND IN BURMA NAGAR IN DN;16, U;04, ZONE;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/9407,Storm Water Drain,Completed,NB-MANALI,20,415000,"IMPROVEMENT WORKS OF S W D AT BALARAMAN STREET ( BALARAMAN 2ND ST. TO CHINNA MATHUR ROAD) IN DN;20, U;5, Z;2.",Own Sources,2,2015-16,2016-17 NB/2015-16/9638,Buildings,Completed,NB-MANALI,16,580000,"HIRING OF JCB WITH FRONT END LOADER AND BACK HOE FOR THE ARRANGEMENT OF TEMPORARY EARTHERN SWD AND CLEANING OF WRONG VEGETATION TO CANAL & DESILTING,ENCROACHMENT REMOVAL, REMOVAL OF DEBRIS ECT IN DN-16,U-4,Z-II.",Own Sources,2,2015-16,2016-17 NB/2015-16/9796,Electrical,Completed,B-Buildings,21,538200,"Supply & erection of 30KVA DG set at primary health center in Div-21 of Zone-II, Manali (As per 2013-14 SOR)",Own Sources,2,2015-16,2016-17 NC/2015-16/0137,Parks,Completed,NC-MADHAVARAM,25,344000,"Annual Maintenance of Park at Pathmavathy Nagar Park in Dn-25, Unit-06, Zone-03",Own Sources,3,2015-16,2016-17 NC/2015-16/0168,Parks,Completed,NC-MADHAVARAM,26,370000,"Maintenance of Park at Secretariat Colony in Dn-26, Unit-7, Zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/0281,Roads,Completed,NC-MADHAVARAM,32,920000,"Laying of Cement Concrete Road by RMC M 30 grade at V.O.C Street in Ward-32, Unit-8,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/0571,Parks,Completed,NC-MADHAVARAM,28,207000,"MAINTENANCE OF PARK AT PADMAGIRI NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 28, UNIT 7, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/10692,Buildings,Completed,NC-MADHAVARAM,27,899000,"Improvements to kummarappa pond at perumal koil street in div-27,unit-7,zone-5.",Own Sources,3,2015-16,2016-17 NC/2015-16/11076,Storm Water Drain,Completed,NC-MADHAVARAM,29,993000,"IMPROVEMENTS AND REPAIRS TO SIDE DRAIN AT BUTHAPIRAN STREET AND DEVARAJAN STREET IN DN-29,U-7,Z-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/12232,Buildings,Completed,NC-MADHAVARAM,22,999000,"CONSTRUCTION OF MULTIPURPOSE HALL AT KANNAPPASAMY NAGAR 26TH STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/12546,Parks,Completed,NC-MADHAVARAM,30,188000,"MAINTENANCE OF PARK AT V.R.D. NAGAR JUNCTION OF PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 30, UNIT8, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/13228,Buildings,Completed,NC-MADHAVARAM,22,258000,"IMPROVEMENTS AND MAINTANACE WORK AT AMMA UNAVAGAM (PHASE I) G.N.T. SERVICE ROAD IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/13521,Parks,Completed,NC-MADHAVARAM,30,93000,"MAINTENANCE OF PARK AT SIVASAKTHI NAGAR AND ARUL NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 30, UNIT8, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/13523,Parks,Completed,NC-MADHAVARAM,30,179000,"MAINTENANCE OF PARK AT RING ROAD HOUSING SECTOR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 30, UNIT8, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/13525,Parks,Completed,NC-MADHAVARAM,31,203000,"MAINTENANCE OF PARK AT K.K.R. NAGAR AND M.R.H. ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 31, UNIT 8, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/13753,Parks,Completed,NC-MADHAVARAM,32,88000,"MAINTENANCE OF PARK ATLAKSHMIPURAM TEACHERS COLONY 4TH CROSS STREET QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER- 2015 TO DECEMBER - 2015 IN DN 32, UNIT 8, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/13754,Parks,Completed,NC-MADHAVARAM,32,58000,"MAINTENANCE OF PARK ATLAKSHMIPURAM TEACHERS COLONY 6TH MAIN ROAD QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 32, UNIT 8, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/13864,Road Cut,Completed,NC-MADHAVARAM,22,330000,"CEMENT CONCRETE PATCHES AT VALLUVAR STREET TO KANNAPPASAMY NAGAR MAIN STREET JUNCTION IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/13881,Roads,Completed,NC-MADHAVARAM,25,999500,"FORMING AND RELAYING OF BT ROAD AT NAGAPPA ESTATE CROSS STREET IN DN 25, UNIT 6, ZONE III. (CHAINAGE (0 TO 110M)",Own Sources,3,2015-16,2016-17 NC/2015-16/14518,Buildings,Completed,NC-MADHAVARAM,31,259000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PC AT KANNABIRAN KOVIL STREET JUNCTION OF VINAYAGAR KOVIL STREET IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14520,Buildings,Completed,NC-MADHAVARAM,31,415000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PC AT KANNABIRAN KOVIL STREET JUNCTION OF INDITAL COMPANY IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14523,Buildings,Completed,NC-MADHAVARAM,31,434000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PC AT KOLKATTA SHOP MAIN ROAD NEAR BY THIRUVALLUVAR STREET IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14526,Buildings,Completed,NC-MADHAVARAM,31,239000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PC AT MUTHUMARIAMMAN KOVIL STREET JUNCTION OF THIRUVALLUVAR STREET IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14836,Storm Water Drain,Completed,NC-MADHAVARAM,24,998000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV-24,UNIT-6,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14837,Storm Water Drain,Completed,NC-MADHAVARAM,25,998000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV- 25,UNIT-6,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14839,Storm Water Drain,Completed,NC-MADHAVARAM,30,998000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV-30 ,UNIT-8,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14840,Storm Water Drain,Completed,NC-MADHAVARAM,31,998000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV-31,UNIT-8,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14849,Storm Water Drain,Completed,NC-MADHAVARAM,27,999000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV- 27,UNIT-7,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14850,Storm Water Drain,Completed,NC-MADHAVARAM,26,995000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV- 26,UNIT-7,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14852,Storm Water Drain,Completed,NC-MADHAVARAM,28,995000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV-28,UNIT-7,ZONE-3",Own Sources,3,2015-16,2017-18 NC/2015-16/14854,Storm Water Drain,Completed,NC-MADHAVARAM,33,995000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV- 33,UNIT-8,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/14856,Storm Water Drain,Completed,NC-MADHAVARAM,32,995000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV- 32,UNIT-8,ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/15061,Buildings,Completed,NC-MADHAVARAM,33,371000,REPAIRS AND IMPROVEMENTS TO PUBLIC CONVEYANCE AT NETHAJI STREET AND VASUDEVA THOTTAM IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/15104,Buildings,Completed,NC-MADHAVARAM,31,502000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PC AT MAA POO VEDA STREET IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15126,Parks,Completed,NC-MADHAVARAM,28,993000,"Providing and Fixing Stainless Steel Pipe Hand Rails along path way to around Childrens Play Space Area at Padmagiri nagar Park in Ward 28,Unit-7,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15129,Parks,Completed,NC-MADHAVARAM,28,385000,"Improvements to Park at Padmagiri nagar in Ward-28, Unit-7,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15179,Parks,Completed,NC-MADHAVARAM,32,525000,"Repairs and Improvements to Park at Teachers Colony 4th Cross Street in Ward-32,Unit-8,Zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/15193,Parks,Completed,NC-MADHAVARAM,32,300000,"Repairs and Improvements to Park at Teachers Colony 6th Main Road in Ward-32, Unit-8,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15451,Roads,Completed,NC-MADHAVARAM,31,579000,"IMPROVEMENTS TO SIDE DRAIN AT PANDIAN STREET IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/15464,Parks,Completed,NC-MADHAVARAM,33,58000,"MAINTENANCE OF PARK AT SELVAM NAGAR (QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD FROM OCT-2015 TO DEC-2015) IN DIVISION-33, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15469,Parks,Completed,NC-MADHAVARAM,33,82000,"MAINTENANCE OF PARK AT V.G.P. SANTHOSH NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 33, UNIT 8, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/15471,Parks,Completed,NC-MADHAVARAM,33,85000,"MAINTENANCE OF PARK AT THANIKACHALAM NAGAR B BLOCK 5TH MAIN ROAD (QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD FROM OCTOBER-2015 TO DECEMBER-2015 IN DIVISION-33, UNIT-8, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/15647,Parks,Completed,NC-MADHAVARAM,22,124000,"MAINTENANCE OF PARK AT MACRO MARVEL PARK - I & II QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/15648,Parks,Completed,NC-MADHAVARAM,24,87000,"MAINTENANCE OF PARK AT D.G. NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/15649,Parks,Completed,NC-MADHAVARAM,25,84000,"MAINTENANCE OF PARK AT PADMAVATHI NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/15653,Parks,Completed,NC-MADHAVARAM,25,185000,"MAINTENANCE OF PARK AT COLLECTOR NAGAR HERBAL PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/15654,Parks,Completed,NC-MADHAVARAM,25,85000,"MAINTENANCE OF PARK AT SRINIVASA NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/15658,Parks,Completed,NC-MADHAVARAM,22,88000,"MAINTENANCE OF PARK AT GURUSHANTHI NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/15660,Buildings,Completed,NC-MADHAVARAM,31,721000,"IMPROVEMENTS TO SIDE DRAIN AT KOLKATTA SHOP ROAD IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15737,Buildings,Completed,NC-MADHAVARAM,30,234000,"PROVIDING SANITARY AND ELECTRICAL ARRANGEMENTS TO BABY MILK FEEDING ROOM IN MADHAVARAM BUS TERMINUS CAMPUS AT M.R.H. ROAD IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15878,Roads,Completed,NC-MADHAVARAM,31,918000,"IMPROVEMENTS TO SIDE DRAIN AT FROM K.K.R. ESTATE TO GNT ROAD IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/15967,Parks,Completed,NC-MADHAVARAM,23,58000,"MAINTENANCE OF PARK AT AMBATHUR TO REDHILLS ROAD PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 23, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/16169,Buildings,Completed,NC-MADHAVARAM,29,57500,"Improvements to Shopping Complex No.8 at Devarajan street in Div-29, Unit-7, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16172,Buildings,Completed,NC-MADHAVARAM,29,450000,"Improvements to Chennai Middle School at Devarajan street in Div-29, Unit-7, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16173,Buildings,Completed,NC-MADHAVARAM,29,48000,"Improvements to Water Supply arrangements for Public Conveyance at E.V.R Street in div-29, Unit-7, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16175,Buildings,Completed,NC-MADHAVARAM,29,12000,"Improvements to Electrical arrangements for Community Center at Devarajan street in div-29, Unit-7, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16198,Buildings,Completed,NC-MADHAVARAM,29,90000,"Improvements to false Ceiling to Amma Unavagam at Devarajan Street in Ward - 29, Unit - 7,Zone - 3.",Own Sources,3,2015-16,2017-18 NC/2015-16/16199,Buildings,Completed,NC-MADHAVARAM,29,243000,"Improvements to shopping Complexes ( 1 to 7) at Devarajan Street in Ward - 29, Unit-7,Zone - 3.",Own Sources,3,2015-16,2017-18 NC/2015-16/16200,Buildings,Completed,NC-MADHAVARAM,29,46000,Improvements to Public Cnvenience at Karunanaidhi Street in Ward - 29 Unit - 7 Zone-3,Own Sources,3,2015-16,2016-17 NC/2015-16/16274,Parks,Completed,NC-MADHAVARAM,26,83000,"MAINTENANCE OF PARK AT SECRETARIAT COLONY QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 26, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/16392,Buildings,Completed,NC-MADHAVARAM,32,960000,"Construction of Compound Wall to OSR Land at Teachers Colony 5th Main Road (South and Western Sides ) in Ward-32, Unit-8,Zone-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/16396,Buildings,Completed,NC-MADHAVARAM,22,998000,"PROVIDING TOILET AND STORE ROOM AT KANNAPPASAMY NAGAR 26TH STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16398,Electrical,Completed,NC-MADHAVARAM,22,530000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND ELECTRICAL ITEMS FOR MULTI PURPOSE HALL AT KANNAPPASAMY NAGAR 26TH STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16400,Buildings,Completed,NC-MADHAVARAM,22,998000,"CONSTRUCTION OF GYM BUILDING AT KO.SU. MANI STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16401,Buildings,Completed,NC-MADHAVARAM,22,999000,"CONSTRUCTION AND PROVIDING TOILET AND REST ROOM IN GYM BUILDING AT KO.SU.MANI STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16404,Buildings,Completed,NC-MADHAVARAM,22,530000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS AT KO.SU.MANI STREET GYM BUILDING IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16407,Roads,Completed,NC-MADHAVARAM,30,879000,"IMPROVEMENTS TO SIDE DRAIN AT RAJAJI STREET IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16408,Buildings,Completed,NC-MADHAVARAM,22,992000,"PROVIDING ILB.AND STREET NAME BOARD AT VARIOUS STREETS DN 22 , UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16409,Roads,Completed,NC-MADHAVARAM,30,827000,"IMPROVEMENTS TO SIDE DRAIN AT BHARATHIYAR STREET MAIN ROAD PART-1 IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16410,Roads,Completed,NC-MADHAVARAM,30,579000,"IMPROVEMENTS TO SIDE DRAIN AT PUKRAJ NAGAR 6TH STREET IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/16412,Roads,Completed,NC-MADHAVARAM,30,735000,"IMPROVEMENTS TO SIDE DRAIN AT PUKRAJ NAGAR 4TH STREET IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16413,Roads,Completed,NC-MADHAVARAM,30,753000,"IMPROVEMENTS TO SIDE DRAIN AT FROM ARINJAR ANNA STREET TO MMC ROAD IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/16414,Roads,Completed,NC-MADHAVARAM,30,843000,"IMPROVEMENTS TO SIDE DRAIN AT MMC ROAD FROM MRH ROAD TO JUNCTION OF RIZWAN ROAD PART-II IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16418,Buildings,Completed,NC-MADHAVARAM,25,978000,"PROVIDING ILB AND STREET NAME BOARD AT VARIOUS STREETS IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16420,Roads,Completed,NC-MADHAVARAM,30,827000,"IMPROVEMENTS TO SIDE DRAIN AT BHARATHIYAR MAIN ROAD PART-II IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16423,Roads,Completed,NC-MADHAVARAM,30,709000,"IMPROVEMENTS TO SIDE DRAIN AT MMC ROAD FROM JUNCTION OF RIZWAN ROAD TO ARUL NAGAR IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16430,Buildings,Completed,NC-MADHAVARAM,22,992000,"PROVIDING ILB AND STREET NAME BOARD AT DIVISION 22 VARIOUS STREETS IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16544,Storm Water Drain,Completed,NC-MADHAVARAM,25,297000,"DESILTING AND IMPROVEMENT TO STORM WATER DRAIN AT VARIOUS STREETS IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16545,Roads,Completed,NC-MADHAVARAM,25,600000,"Attending patch works at various places in Div-25,Unit-6,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16618,Storm Water Drain,Completed,NC-MADHAVARAM,22,198000,"DESILTING AND IMPROVEMENT OF STORM WATER DRAIN AT VARIOUS STREETS IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/16658,Parks,Completed,NC-MADHAVARAM,31,80000,"IMPROVEMENTS TO EXISTING PART (NEAR GREEN PARK RC APPARTMENTS) MRH ROAD IN DIVISION-31, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/16903,Roads,Completed,NC-MADHAVARAM,24,484000,"FORMING WBM ROAD AT MADURA MATTUR 6TH MAIN ROAD IN 4TH CROSS STREET, IN DIV-24, UNIT-6, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/17680,Footpath,Completed,NC-MADHAVARAM,30,995000,"REPAIRS AND IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT RAJAJI STREET IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/17899,Electrical,Completed,NC-MADHAVARAM,22,871600,"Provision of 15 nos of 6 mtr lamp post with straight bracket WITH Hot dip zinc galvanising with 40w to 50 w LED Fitting at K.S.Nanar & Jeeva street Burial Ground , 1no of 9 mtr lamp post with Triple straight bracket WITH Hot dip zinc galvanising with 90w to 120 w LED Fitting at Valluvar street junction in Division-22 of zone-III (Madhavaram)(Sch of rate 2015-16)",Own Sources,3,2015-16,2016-17 NC/2015-16/18063,Roads,Completed,NC-MADHAVARAM,26,544000,IMPROVEMENTS TO B ROAD (PART) AT TRUCK TERMINAL IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/18072,Roads,Completed,NC-MADHAVARAM,33,360000,"SUPPLYING AND FIXING TABLET STONE USING RED GRANITE STONE OF SIZE (36X24) AT VARIOUS PLACES IN DN -33, UNIT -8, ZONE -3.",Own Sources,3,2015-16,2016-17 NC/2015-16/18075,Footpath,Completed,NC-MADHAVARAM,26,995000,"RAPAIRS AND IMPROVEMENT TO AD ROOM AND ARO ROOM IN ZONAL OFFICE INSIDE AT TATTAN KULAM STREET IN DN -26, UNIT -7, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/18286,Buildings,Completed,NC-MADHAVARAM,25,428000,"CONSTRUCTION OF SUMP NEAR BY AMMA UNAVAGAM AT E.M.S. STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/19516,Storm Water Drain,Completed,NC-MADHAVARAM,31,795000,"IMPROVEMENTS TO THE SIDE DRAIN AT DHANSINGH MAISTRY STREET FROM MUTHUMARIAMMAN KOVIL STREET TO UDAIYAR THOTTAM 2ND ST IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/19517,Roads,Completed,NC-MADHAVARAM,22,481000,"FORMING AND ATTENDING BT PATCHES AT GANDHI MAIN STREET (VEGITARIAN VILLAGE TO VADAPERUMPAKKAM ROAD) IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/19537,Storm Water Drain,Completed,NC-MADHAVARAM,31,795000,"IMPROVEMENTS TO SIDE DRAIN AT DHANSINGH MASITRY STREET FROM UDAIYAR THOTTAM 2ND STREET TO UDIAYAR THOTTAM 7TH STREET IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21590,Roads,Completed,NC-MADHAVARAM,30,519000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Pukraj Nagar 1st street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21598,Roads,Completed,NC-MADHAVARAM,30,467000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Pukraj Nagar 2nd street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21623,Roads,Completed,NC-MADHAVARAM,30,543000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Pukraj Nagar 4th street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21628,Roads,Completed,NC-MADHAVARAM,30,402000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Pukraj Nagar 5th street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21638,Roads,Completed,NC-MADHAVARAM,30,987000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Roja Nagar extn 1st main road,Kanmal Nagar in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21643,Roads,Completed,NC-MADHAVARAM,30,987000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Roja Nagar extn ,VS Mani Nagar in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21650,Roads,Completed,NC-MADHAVARAM,30,226000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Siva Sakthi Nagar 5th cross street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21656,Roads,Completed,NC-MADHAVARAM,30,226000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Siva Sakthi Nagar 6th cross street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21663,Roads,Completed,NC-MADHAVARAM,30,1259000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at Rajaji Street, Metha Nagar in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21677,Roads,Completed,NC-MADHAVARAM,30,769000,"Attending to Temporary Restoration of Damaged Interiors roads due to flood in North-East Mansoon-2015 at V.R.D. Nagar 1st Main road in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21772,Roads,Completed,NC-MADHAVARAM,31,750000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Kolkatta shop road in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21776,Roads,Completed,NC-MADHAVARAM,31,453000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at KKR Nagar 1st Main road Cross Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21790,Roads,Completed,NC-MADHAVARAM,30,604000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at KKR Nagar 2nd Main road Cross Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21792,Roads,Completed,NC-MADHAVARAM,31,968000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Pandian Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21797,Roads,Completed,NC-MADHAVARAM,31,1243000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Muthumariamman Kovil Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21803,Roads,Completed,NC-MADHAVARAM,31,566000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at St.Francis Colony in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21807,Roads,Completed,NC-MADHAVARAM,31,708000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Palanippa nagar Main Road in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21814,Roads,Completed,NC-MADHAVARAM,31,1203000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Dhansingh Maistry in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/21823,Roads,Completed,NC-MADHAVARAM,31,691000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at T.V.K. 1st Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22465,Roads,Completed,NC-MADHAVARAM,30,440000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Ring Road Housing Sector 1st Cross Street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22470,Roads,Completed,NC-MADHAVARAM,30,358000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Ring Road Housing Sector 2nd Main road in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22471,Roads,Completed,NC-MADHAVARAM,31,709000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Duraisamy Naicker Street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22483,Roads,Completed,NC-MADHAVARAM,30,235000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Pukraj Nagar 6th Main road 2nd cross street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22493,Roads,Completed,NC-MADHAVARAM,30,268000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Pukraj Nagar 6th Main road 3rd cross street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22505,Roads,Completed,NC-MADHAVARAM,30,567000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Bharathiyar 1st street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22517,Roads,Completed,NC-MADHAVARAM,31,788000,"Strengthening and Relaying Bituminous Road by Paver Finisher at KKR Estate 1st Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22519,Roads,Completed,NC-MADHAVARAM,31,1899000,"Strengthening and Relaying Bituminous Road by Paver Finisher at KKR Estate 2nd Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22520,Roads,Completed,NC-MADHAVARAM,31,1112000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Ravi Garden in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22521,Roads,Completed,NC-MADHAVARAM,31,150000,"Strengthening and Relaying Bituminous Road by Nagathamman kovil 1st street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22523,Roads,Completed,NC-MADHAVARAM,31,164000,"Strengthening and Relaying Bituminous Road by Nagathamman kovil 2nd street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22524,Roads,Completed,NC-MADHAVARAM,31,172000,"Strengthening and Relaying Bituminous Road by Nagathamman kovil 3rd street in Div-31, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22557,Roads,Completed,NC-MADHAVARAM,30,282000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Ring Road Housing Sector 2nd cross street in Div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22733,Storm Water Drain,Completed,NC-MADHAVARAM,23,255000,"IMPROVEMENT TO PC (FEMALE) AT ERATAMALAI SRINIVASAN STREET IN DN-23,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22750,Buildings,Completed,NC-MADHAVARAM,23,435000,"IMPROVEMENT TO PC (MALE) AT ERATAMALAI SRINIVASAN STREET IN DN-23,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22830,Buildings,Completed,NC-MADHAVARAM,23,450000,"IMPROVEMENTS TO PC AT GANGATHARAN STREET IN DN-23,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/22971,Parks,Completed,NC-MADHAVARAM,33,82000,"MAINTENANCE OF PARK AT V.G.P. SANTHOSH NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 33, UNIT 8, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/22978,Parks,Completed,NC-MADHAVARAM,33,85000,"MAINTENANCE OF PARK AT THANIKACHALAM NAGAR B BLOCK 5TH MAIN ROAD (QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD FROM JANUARY-2016 TO MARCH-2016 IN DIVISION-33, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/22982,Parks,Completed,NC-MADHAVARAM,33,58000,"MAINTENANCE OF PARK AT SELVAM NAGAR (QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD FROM JANUARY-2016 TO MARCH-2016 IN DIVISION-33, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/22988,Parks,Completed,NC-MADHAVARAM,31,218000,"MAINTENANCE OF PARK AT K.K.R. GARDEN QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARACH 2016 IN DN 31, UNIT 8, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/23054,Roads,Completed,NC-MADHAVARAM,24,512000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Gandhi nagar 2nd Street in Div-24, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23055,Roads,Completed,NC-MADHAVARAM,24,285000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Gandhi Nagar 3rd street in Div-24, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23056,Roads,Completed,NC-MADHAVARAM,22,960000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PILLAYAR KOIL STREET IN DIVISION 22 UNIT 6 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23057,Roads,Completed,NC-MADHAVARAM,24,681000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Grace Nagar 4th street in Div-24, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23058,Roads,Completed,NC-MADHAVARAM,24,681000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Grace nagar 5th street in Div-24, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23059,Roads,Completed,NC-MADHAVARAM,22,1549000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SIVARAJ 2ND STREET IN DIVISION 22 UNIT 6 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23060,Roads,Completed,NC-MADHAVARAM,24,1566000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Gandhi nagar 1st street in Div-24, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23061,Roads,Completed,NC-MADHAVARAM,22,585000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SIVARAJ 2ND CROSS STREET IN DIVISION 22 UNIT 6 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23062,Roads,Completed,NC-MADHAVARAM,24,716000,"Strengthening and Relaying Bituminous Road by Paver Finisher at shakthi nagar extn 12th Street in Div-24, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23063,Roads,Completed,NC-MADHAVARAM,24,1112000,"Strengthening and Relaying Bituminous Road by Paver Finisher at shakthi nagar extn 11th steeet in Div-24, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23064,Roads,Completed,NC-MADHAVARAM,24,512000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Kamala nagar 4th street in Div-24, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23065,Roads,Completed,NC-MADHAVARAM,22,651000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT K.V.K. SWAMY STREET IN DIVISION 22 UNIT 6 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23066,Roads,Completed,NC-MADHAVARAM,25,547000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Raasi nagar 2nd street in Div-25, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23067,Roads,Completed,NC-MADHAVARAM,22,913000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL STREET IN DIVISION 22 UNIT 6 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23068,Roads,Completed,NC-MADHAVARAM,25,785000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Birala Avenve Near service road in Div-25, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23069,Roads,Completed,NC-MADHAVARAM,22,761000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PANNEERSELVAM STREET IN DIVISION 22 UNIT 6 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23070,Roads,Completed,NC-MADHAVARAM,22,1235000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT LALBAGADUR SASTRI STREET IN DIVISION 22 UNIT 6 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23071,Roads,Completed,NC-MADHAVARAM,22,1187000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Bharathiyar Street in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23072,Roads,Completed,NC-MADHAVARAM,22,627000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Balaji nagar-kumari nagar (near) in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23073,Roads,Completed,NC-MADHAVARAM,26,275000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 1 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23074,Roads,Completed,NC-MADHAVARAM,26,776000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 2 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23076,Roads,Completed,NC-MADHAVARAM,22,605000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Balaji nagar-pilayar koil street in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23077,Roads,Completed,NC-MADHAVARAM,26,182000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 3 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23078,Roads,Completed,NC-MADHAVARAM,22,308000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Meenakshi Nagar Estn. in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23079,Roads,Completed,NC-MADHAVARAM,26,1022000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 4 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23081,Roads,Completed,NC-MADHAVARAM,26,659000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 5 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23082,Roads,Completed,NC-MADHAVARAM,22,6108000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Sivanthi Adittanar Nagar in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23085,Roads,Completed,NC-MADHAVARAM,26,833000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 6 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23086,Roads,Completed,NC-MADHAVARAM,22,997000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Vegitarian Village - Sakkubai Choudri St. in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23087,Roads,Completed,NC-MADHAVARAM,26,513000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 7 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23088,Roads,Completed,NC-MADHAVARAM,27,679000,"LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 1ST STREET IN DIV-27, UNIT-7, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23089,Roads,Completed,NC-MADHAVARAM,26,195000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SEETHAPATHY STREET PART 8 IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23090,Roads,Completed,NC-MADHAVARAM,22,1225000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Mahaveer Garden 7th Street in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23091,Roads,Completed,NC-MADHAVARAM,27,679000,"LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 2ND STREET IN DIV-27, UNIT-7, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23092,Roads,Completed,NC-MADHAVARAM,22,1669000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Balaji Nagar Extn. in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23093,Roads,Completed,NC-MADHAVARAM,22,409000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Thirumalai nagar 8th and 9th street. in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23094,Roads,Completed,NC-MADHAVARAM,27,668000,"LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 3RD STREET IN DIV-27, UNIT-7, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23095,Roads,Completed,NC-MADHAVARAM,22,1747000,"Strengthening and Relaying Bituminous Road by Paver Finisher at Krishna Nagar 1st street. in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23096,Roads,Completed,NC-MADHAVARAM,22,1021000,"Strengthening and Relaying Bituminous Road by Paver Finisher at KS nagar 14th cross. in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23097,Roads,Completed,NC-MADHAVARAM,22,1430000,"Strengthening and Relaying Bituminous Road by Paver Finisher at New krishna nagar in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23098,Roads,Completed,NC-MADHAVARAM,28,1004000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT MARI STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23100,Roads,Completed,NC-MADHAVARAM,27,820000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 4TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23101,Roads,Completed,NC-MADHAVARAM,30,278000,"Laying cement concrete road by using RMC30 at pukraj nagar 6th main road in dn-30,unit-8, zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/23102,Roads,Completed,NC-MADHAVARAM,27,709000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 5TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23103,Roads,Completed,NC-MADHAVARAM,30,681000,"Laying cement concrete road by using RMC 30 at Bazaar 1st street in dn-30 ,unit-8,zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/23104,Roads,Completed,NC-MADHAVARAM,30,419000,"Laying cement concrete road by using RMC 30 at Bazaar street 2nd street in dn-30 ,unit-8,zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/23105,Roads,Completed,NC-MADHAVARAM,28,318000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT MARI 1ST STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23106,Roads,Completed,NC-MADHAVARAM,28,461000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT RAMAKRISHNAN STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23107,Roads,Completed,NC-MADHAVARAM,23,1089000,"STRENGTHENING AND RELAYING BITUMINOUS ROAD BY PAVER FINISHER AT ANJA STREET IN DIV-23, UNIT-6, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23108,Roads,Completed,NC-MADHAVARAM,28,681000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SIVA BOOSHANAN STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23109,Roads,Completed,NC-MADHAVARAM,28,882000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT AMIRTHAMMAL 1ST STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23110,Roads,Completed,NC-MADHAVARAM,28,1055000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT AMIRTHAMMAL 2ND STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23111,Roads,Completed,NC-MADHAVARAM,27,435000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 6TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23112,Roads,Completed,NC-MADHAVARAM,28,1055000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT AMIRTHAMMAL 3RD STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23113,Roads,Completed,NC-MADHAVARAM,26,5024000,"STRENGTHENING AND RELAYING BITUMINOUS ROAD BY PAVER FINISHER AT AADHINATH NAGAR MAIN ROAD IN DIV-26, UNIT-7, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23114,Roads,Completed,NC-MADHAVARAM,27,436000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 7TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23115,Roads,Completed,NC-MADHAVARAM,28,833000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT YASODHAMMAL STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23116,Roads,Completed,NC-MADHAVARAM,26,3047000,"STRENGTHENING AND RELAYING BITUMINOUS ROAD BY PAVER FINISHER AT AADHINATH NAGAR 1ST STREET IN DIV-26, UNIT-7, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23117,Roads,Completed,NC-MADHAVARAM,28,503000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT MUNUSAMY 1ST STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23118,Roads,Completed,NC-MADHAVARAM,27,721000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 8TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23119,Roads,Completed,NC-MADHAVARAM,28,672000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SAMY STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23120,Roads,Completed,NC-MADHAVARAM,27,361000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 9TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23121,Roads,Completed,NC-MADHAVARAM,28,178000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT ARIGNAR ANNA 1ST LANE IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23122,Roads,Completed,NC-MADHAVARAM,27,361000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 10TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23123,Roads,Completed,NC-MADHAVARAM,28,301000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT ARIGNAR ANNA 6TH STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23124,Roads,Completed,NC-MADHAVARAM,27,694000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 11TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23125,Roads,Completed,NC-MADHAVARAM,28,451000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT ANNAI INDRA NAGAR BHARATHY STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23126,Roads,Completed,NC-MADHAVARAM,27,761000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 12TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23127,Roads,Completed,NC-MADHAVARAM,28,420000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT MURUGESAN STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23128,Roads,Completed,NC-MADHAVARAM,27,257000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 13TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23129,Roads,Completed,NC-MADHAVARAM,28,427000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT RAJKANNU STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23130,Roads,Completed,NC-MADHAVARAM,28,377000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SASTRY NAGAR CROSS STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23131,Roads,Completed,NC-MADHAVARAM,28,801000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PALANI STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23132,Roads,Completed,NC-MADHAVARAM,27,257000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT EDIMA NAGAR 14TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23133,Roads,Completed,NC-MADHAVARAM,28,607000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT MANICKAM MANI STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23134,Roads,Completed,NC-MADHAVARAM,27,256000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT C.K.M NAGAR CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23135,Roads,Completed,NC-MADHAVARAM,28,1349000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT CHANDRAN STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23137,Roads,Completed,NC-MADHAVARAM,27,1037000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT S.S.V KOIL STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23138,Roads,Completed,NC-MADHAVARAM,27,580000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL ROAD CROSS IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23139,Roads,Completed,NC-MADHAVARAM,27,655000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL THOTTAM IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23141,Roads,Completed,NC-MADHAVARAM,28,512000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PACHAYAPPAN GARDEN 1ST STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23142,Roads,Completed,NC-MADHAVARAM,27,1144000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL THOTTAM 1ST STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23143,Roads,Completed,NC-MADHAVARAM,28,280000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PACHAYAPPAN GARDEN 4TH STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23144,Roads,Completed,NC-MADHAVARAM,27,519000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL THOTTAM 1ST CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23145,Roads,Completed,NC-MADHAVARAM,28,554000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PACHAYAPPAN GARDEN 5TH STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23146,Roads,Completed,NC-MADHAVARAM,28,547000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PACHAYAPPAN GARDEN 6TH STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23147,Roads,Completed,NC-MADHAVARAM,27,500000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL THOTTAM 2ND & 3RD STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23148,Roads,Completed,NC-MADHAVARAM,28,288000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PACHAYAPPAN GARDEN 7TH STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23149,Roads,Completed,NC-MADHAVARAM,27,573000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL THOTTAM 2ND CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23150,Roads,Completed,NC-MADHAVARAM,28,308000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PACHAYAPPAN GARDEN 8TH STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23151,Roads,Completed,NC-MADHAVARAM,28,385000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PACHAYAPPAN GARDEN 9TH STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23152,Roads,Completed,NC-MADHAVARAM,27,973000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL THOTTAM 2ND CROSS 1ST STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23153,Roads,Completed,NC-MADHAVARAM,28,852000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PERIYASAMY STREET OTHAVADAI IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23154,Roads,Completed,NC-MADHAVARAM,27,208000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL THOTTAM 2ND CROSS 2ND & 3RD STREET STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23155,Roads,Completed,NC-MADHAVARAM,28,774000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT SAIBABA NAGAR STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23156,Roads,Completed,NC-MADHAVARAM,28,1430000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT MERRYLAND MAIN STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23157,Roads,Completed,NC-MADHAVARAM,28,273000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT MERRYLAND 1ST CROSS STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23158,Roads,Completed,NC-MADHAVARAM,27,949000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL 2ND STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23159,Roads,Completed,NC-MADHAVARAM,28,273000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT MERRYLAND 2ND CROSS STREET MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23160,Roads,Completed,NC-MADHAVARAM,27,1213000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL 4TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23161,Roads,Completed,NC-MADHAVARAM,28,186000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 1ST STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23162,Roads,Completed,NC-MADHAVARAM,27,607000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL 5TH STREET PART IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23163,Roads,Completed,NC-MADHAVARAM,28,154000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 3RD STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23164,Roads,Completed,NC-MADHAVARAM,27,1273000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT PERUMAL KOIL 6TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23165,Roads,Completed,NC-MADHAVARAM,28,589000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 4TH STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23167,Roads,Completed,NC-MADHAVARAM,27,2867000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT MURUGASEN GARDEN IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23168,Roads,Completed,NC-MADHAVARAM,28,589000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 5TH STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23169,Roads,Completed,NC-MADHAVARAM,28,883000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 6TH STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23170,Roads,Completed,NC-MADHAVARAM,27,1261000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT NORTH TELEPHONE COLONY 4TH & 5TH STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23171,Roads,Completed,NC-MADHAVARAM,28,654000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 7TH STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23172,Roads,Completed,NC-MADHAVARAM,27,502000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SRINIVASA PERUMAL KOIL CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23174,Roads,Completed,NC-MADHAVARAM,28,146000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 1ST CROSS STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23175,Roads,Completed,NC-MADHAVARAM,27,502000,LAYING CEMENT CONCRETE ROAD BY RMC30 AT SRINIVASA PERUMAL KOIL CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3.,Own Sources,3,2015-16,2016-17 NC/2015-16/23176,Roads,Completed,NC-MADHAVARAM,28,146000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 2ND CROSS STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23177,Roads,Completed,NC-MADHAVARAM,28,272000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 3RD CROSS STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23178,Roads,Completed,NC-MADHAVARAM,28,568000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT PADMAGIRI NAGAR 4TH CROSS STREET PERIYASEKKARU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23179,Roads,Completed,NC-MADHAVARAM,28,479000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT SAROJINI AVENUE 1ST STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23180,Roads,Completed,NC-MADHAVARAM,28,479000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT SAROJINI AVENUE 2ND STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23181,Roads,Completed,NC-MADHAVARAM,28,479000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT SAROJINI AVENUE 3RD STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23182,Roads,Completed,NC-MADHAVARAM,28,387000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT MEENAKSHI BHARATHI CO OPERATIVE NAGAR PHASE I 2ND STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23183,Roads,Completed,NC-MADHAVARAM,28,387000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT MEENAKSHI BHARATHI CO OPERATIVE NAGAR PHASE I 3RD STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23184,Roads,Completed,NC-MADHAVARAM,28,149000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT BANK COLONY 2ND STREET EXTENSION IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23185,Roads,Completed,NC-MADHAVARAM,28,257000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT JOHN VASU STREET EXTENSION IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23186,Roads,Completed,NC-MADHAVARAM,28,858000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT V.R.T. GARDEN STREET PART IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23187,Roads,Completed,NC-MADHAVARAM,28,716000,STRENGTHENING AND LAYING BITUMINOUS ROAD BY USING PAVER FINISHER AT ELUMALAI STREET PART MOOLACHATRAM IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23188,Roads,Completed,NC-MADHAVARAM,33,379000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT AMBUJAMMAL STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23189,Roads,Completed,NC-MADHAVARAM,33,1182000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT PONNIAMMAN KOIL STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23190,Roads,Completed,NC-MADHAVARAM,33,434000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT THIRUPPUR KUMARAN STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23191,Roads,Completed,NC-MADHAVARAM,33,1108000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT V.O.C. 1ST STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23192,Roads,Completed,NC-MADHAVARAM,33,796000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT NEHRU STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23194,Roads,Completed,NC-MADHAVARAM,33,1501000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT NARAYANASWAMY STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23198,Roads,Completed,NC-MADHAVARAM,33,1500000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT NETHAJI 2ND STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23200,Roads,Completed,NC-MADHAVARAM,33,305000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT NETHAJI CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23202,Roads,Completed,NC-MADHAVARAM,33,307000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT VEERAPANDIAN STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23204,Roads,Completed,NC-MADHAVARAM,33,1421000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT SATHIYAMOORTHY STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23224,Roads,Completed,NC-MADHAVARAM,33,582000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT PATEL STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23225,Roads,Completed,NC-MADHAVARAM,33,673000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT POONGAVANAM THOTTAM IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23226,Roads,Completed,NC-MADHAVARAM,33,459000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT BAJANAI KOIL 1ST STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23227,Roads,Completed,NC-MADHAVARAM,33,697000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT BAJANAI KOIL 2ND STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23228,Roads,Completed,NC-MADHAVARAM,33,673000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT BAJANAI KOIL 3RD STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23229,Roads,Completed,NC-MADHAVARAM,33,478000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT BAJANAI KOIL 4TH STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23230,Roads,Completed,NC-MADHAVARAM,33,501000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT PERIYA SALAI 1ST CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23231,Roads,Completed,NC-MADHAVARAM,33,354000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT PERIYA SALAI 2ND CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23232,Roads,Completed,NC-MADHAVARAM,33,273000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT PERIYA SALAI 3RD CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23233,Roads,Completed,NC-MADHAVARAM,33,997000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT PERIYA SALAI 5TH CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23234,Roads,Completed,NC-MADHAVARAM,33,524000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT PERIYA SALAI 6TH CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23237,Roads,Completed,NC-MADHAVARAM,33,598000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT VASUDEVA THOTTAM 1ST CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23238,Roads,Completed,NC-MADHAVARAM,33,630000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT VASUDEVA THOTTAM 2ND CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23239,Roads,Completed,NC-MADHAVARAM,33,532000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT VASUDEVA THOTTAM 3RD CROSS STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23240,Roads,Completed,NC-MADHAVARAM,33,153000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT RAJAJI 5TH STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23241,Roads,Completed,NC-MADHAVARAM,33,355000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT Thanikachalam Nagar B blk 6/3 Street IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23242,Roads,Completed,NC-MADHAVARAM,33,306000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT Thanikachalam Nagar A blk 2/1 Street IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23243,Roads,Completed,NC-MADHAVARAM,33,654000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT RANGANATHAN SALAI IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23244,Roads,Completed,NC-MADHAVARAM,33,164000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT N.S.K. NAGAR 1ST STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23245,Roads,Completed,NC-MADHAVARAM,33,574000,LAYING CEMENT CONCRETE ROAD BY RMC 30 AT N.S.K. NAGAR 2ND STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23246,Roads,Completed,NC-MADHAVARAM,28,186000,STRENGTHENING AND RELAYING BITUMINOUS ROAD BY PAVER FINISHER AT PADMAGIRI NAGAR 2ND STREET PERIYASEKKADU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/23332,Roads,Completed,NC-MADHAVARAM,32,830000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Sarathi Nagar 2nd Street in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23333,Roads,Completed,NC-MADHAVARAM,32,461000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Sarathi Nagar 3rd Street in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23336,Roads,Completed,NC-MADHAVARAM,32,990000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Teachers Colony 4th Main road in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23337,Roads,Completed,NC-MADHAVARAM,32,808000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Teachers Colony 5th Main road in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23338,Roads,Completed,NC-MADHAVARAM,32,1155000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Teachers Colony 6th Main road in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23339,Roads,Completed,NC-MADHAVARAM,32,465000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Teachers Colony 6th cross street in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23341,Roads,Completed,NC-MADHAVARAM,32,947000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Bharathiyar street Extn in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23343,Roads,Completed,NC-MADHAVARAM,32,251000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Nandha Nagar in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23344,Roads,Completed,NC-MADHAVARAM,32,503000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in NorthEast Monsoon-2015 at Venkateswara Nagar in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23345,Roads,Completed,NC-MADHAVARAM,32,998000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Ganapathy Nagar in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23346,Parks,Completed,NC-MADHAVARAM,22,124000,"MAINTENANCE OF PARK AT MACRO MARVEL PARK - I & II QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/23354,Roads,Completed,NC-MADHAVARAM,32,188000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Lalitha Nagar in Div-32, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/23359,Roads,Completed,NC-MADHAVARAM,32,675000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Bharathi Nagar in Div-32, Unit-8, Zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/23360,Roads,Completed,NC-MADHAVARAM,32,50000,"Attending to Temporary Restoration of Damaged Interior roads due to floods in North-East Monsoon-2015 at Shankar Nagar in Div-32, Unit-8, Zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/23394,Parks,Completed,NC-MADHAVARAM,22,88000,"MAINTENANCE OF PARK AT GURUSHANTHI NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/23399,Parks,Completed,NC-MADHAVARAM,25,84000,"MAINTENANCE OF PARK AT PADMAVATHI NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/23404,Parks,Completed,NC-MADHAVARAM,25,185000,"MAINTENANCE OF PARK AT COLLECTOR NAGAR HERBAL PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/23408,Parks,Completed,NC-MADHAVARAM,24,87000,"MAINTENANCE OF PARK AT D.G. NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/23411,Parks,Completed,NC-MADHAVARAM,25,85000,"MAINTENANCE OF PARK AT SRINIVASA NAGAR PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/23416,Parks,Completed,NC-MADHAVARAM,23,58000,"MAINTENANCE OF PARK AT AMBATHUR TO REDHILLS ROAD PARK QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 23, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/23422,Parks,Completed,NC-MADHAVARAM,30,189000,"MAINTENANCE OF PARK AT V.R.D. NAGAR JUNCTION OF PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY 2016 TO MARCH 2016 IN DN 30, UNIT8, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/23427,Parks,Completed,NC-MADHAVARAM,30,93000,"MAINTENANCE OF PARK AT SIVASAKTHI NAGAR AND ARUL NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 30, UNIT8, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/23483,Parks,Completed,NC-MADHAVARAM,31,218000,"MAINTENANCE OF PARK AT K.K.R. GARDEN QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER 2015 TO DECEMBER 2015 IN DN 31, UNIT 8, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24185,Parks,Completed,NC-MADHAVARAM,31,203000,"MAINTENANCE OF PARK AT K.K.R. NAGAR AND M.R.H. ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER - 2015 TO DECEMBER - 2015 IN DN 31, UNIT 8, ZONE III",Own Sources,3,2015-16,2016-17 NC/2015-16/24222,Parks,Completed,NC-MADHAVARAM,31,58000,"MAINTENANCE OF PARK ATLAKSHMIPURAM TEACHERS COLONY 6TH MAIN ROAD QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER- 2015 TO DECEMBER - 2015 IN DN 32, UNIT 8, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24223,Parks,Completed,NC-MADHAVARAM,32,88000,"MAINTENANCE OF PARK ATLAKSHMIPURAM TEACHERS COLONY 4TH CROSS STREET QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF JANUARY- 2016 TO MARCH - 2016 IN DN 32, UNIT 8, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/24226,Parks,Completed,NC-MADHAVARAM,28,207000,"MAINTENANCE OF PARK AT PADMAGIRI NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER- 2015 TO DECEMBER- 2015 IN DN 28, UNIT 7, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24235,Parks,Completed,NC-MADHAVARAM,26,83000,"MAINTENANCE OF PARK AT SECRETARIAT COLONY QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF OCTOBER- 2015 TO DECEMBER- 2015 IN DN 26, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24260,Roads,Completed,NC-MADHAVARAM,28,4101000,"ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT KUMARAN NAGAR MAIN STREET, KK THAZHAI IN DIVISION 28 UNIT 7 ZONE 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24262,Roads,Completed,NC-MADHAVARAM,28,1953000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT SEEYALAN STREET PERIYASEKKADU IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24263,Roads,Completed,NC-MADHAVARAM,28,467000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT ARINGNAR ANNA NAGAR MAIN STREET IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24264,Roads,Completed,NC-MADHAVARAM,28,1402000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT KUMARAN STREET EXTENSION IN DIVISION 28 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24265,Roads,Completed,NC-MADHAVARAM,27,254000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD ATMURUGESAN GARDEN IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24266,Roads,Completed,NC-MADHAVARAM,27,2216000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT PERUMAL KOIL STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24268,Roads,Completed,NC-MADHAVARAM,27,799000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT SOUTH TELEPHONE COLONY IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24269,Roads,Completed,NC-MADHAVARAM,27,420000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT NORTH TELEPHONE COLONY IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24270,Roads,Completed,NC-MADHAVARAM,27,1402000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT KUMARAPPAPURAM MAIN ROAD IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24271,Roads,Completed,NC-MADHAVARAM,27,897000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT BHARATHIDASAN STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24272,Roads,Completed,NC-MADHAVARAM,27,981000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT KRISHNA NAGAR IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24273,Roads,Completed,NC-MADHAVARAM,27,336000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT RAMANA NAGAR AVENUE IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24274,Roads,Completed,NC-MADHAVARAM,27,299000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT GANESH NAGAR IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24275,Roads,Completed,NC-MADHAVARAM,27,770000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT ALEX NAGAR A COLONY MAIN ROAD IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24276,Roads,Completed,NC-MADHAVARAM,27,467000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT TELUGU COLONY 1ST STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24277,Roads,Completed,NC-MADHAVARAM,27,701000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT PERUMAL KOIL 2ND CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24278,Roads,Completed,NC-MADHAVARAM,27,779000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT PERUMAL KOIL 4TH CROSS STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24279,Roads,Completed,NC-MADHAVARAM,29,311000,ATTENDING PATCH WORKS TO FLOOD DAMAGED ROAD AT PARTHASARATHY STREET IN DIVISION 29 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/24383,Roads,Completed,NC-MADHAVARAM,33,390000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT ANNA STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24385,Roads,Completed,NC-MADHAVARAM,33,289000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT KAMARAJAR ST SOUTH IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24387,Roads,Completed,NC-MADHAVARAM,33,374000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT KAMARAJAR ST WEST IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24389,Roads,Completed,NC-MADHAVARAM,33,638000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT PRAKASH NAGAR 10TH STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24391,Roads,Completed,NC-MADHAVARAM,33,290000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT PRAKASH NAGAR 4TH MAIN ROAD IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24393,Roads,Completed,NC-MADHAVARAM,33,463000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT PRAKASH NAGAR 7TH STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24395,Roads,Completed,NC-MADHAVARAM,33,401000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT PRAKASH NAGAR 8TH STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24396,Roads,Completed,NC-MADHAVARAM,33,492000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT SELVAM NAGAR 2ND MAIN ROAD IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24397,Roads,Completed,NC-MADHAVARAM,33,162000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT ANNAI INDIRA STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24398,Roads,Completed,NC-MADHAVARAM,33,174000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT ETTIAPPAN STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24400,Roads,Completed,NC-MADHAVARAM,33,40000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT IYYAR THOTTAM IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24401,Roads,Completed,NC-MADHAVARAM,33,161000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT SATHYAMOORTHY NAGAR IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24402,Roads,Completed,NC-MADHAVARAM,33,436000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THANIGACHALAM NAGAR A BLOCK 2ND CROSS STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24406,Roads,Completed,NC-MADHAVARAM,33,280000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THANIGACHALAM NAGAR A BLOCK 3RD CROSS STREET IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24409,Roads,Completed,NC-MADHAVARAM,33,493000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THANIGACHALAM NAGAR B BLOCK 5TH MAIN ROAD IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24410,Roads,Completed,NC-MADHAVARAM,33,941000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT VGP NAGAR IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24413,Roads,Completed,NC-MADHAVARAM,33,257000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT VIDHYA NAGAR IN DN 33, U 8, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24414,Roads,Completed,NC-MADHAVARAM,33,756000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT MOHAN NAGAR MAIN ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24416,Roads,Completed,NC-MADHAVARAM,33,566000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT MOHAN NAGAR 1ST STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24417,Roads,Completed,NC-MADHAVARAM,33,327000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT MOHAN NAGAR 2ND STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24419,Roads,Completed,NC-MADHAVARAM,33,461000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT BHARATHIYAR NAGAR 1ST STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24420,Roads,Completed,NC-MADHAVARAM,33,463000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT BHARATHIYAR NAGAR 2ND STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24422,Roads,Completed,NC-MADHAVARAM,33,405000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT VOC STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24423,Roads,Completed,NC-MADHAVARAM,33,517000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUVALLUVAR STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24424,Roads,Completed,NC-MADHAVARAM,33,450000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT BHARATHIYAR STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24425,Roads,Completed,NC-MADHAVARAM,33,395000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT VGP 1ST STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24427,Roads,Completed,NC-MADHAVARAM,33,432000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT VGP 2ND STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24429,Roads,Completed,NC-MADHAVARAM,33,336000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT VGP 3RD STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24430,Roads,Completed,NC-MADHAVARAM,33,239000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT KASIAMMAL NAGAR 2ND STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24433,Roads,Completed,NC-MADHAVARAM,33,420000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT MADURAI MANAVALAN NAGAR MAIN ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24434,Roads,Completed,NC-MADHAVARAM,33,579000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT BRINDAVAN THOTTAM MAIN ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24439,Roads,Completed,NC-MADHAVARAM,33,1600000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT SRI RAMAN SALAI NORTH IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24440,Roads,Completed,NC-MADHAVARAM,33,740000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD ATTHANIGACHALAM NAGAR G BLOCK 8TH MAIN ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24441,Roads,Completed,NC-MADHAVARAM,33,360000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THANIGACHALAM NAGAR G BLOCK 1ST STREET ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24443,Roads,Completed,NC-MADHAVARAM,33,349000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THANIGACHALAM NAGAR G BLOCK 2ND STREET ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24444,Roads,Completed,NC-MADHAVARAM,33,709000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT SELVAM NAGAR EXTENSION NATESAN STREET IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24448,Roads,Completed,NC-MADHAVARAM,33,782000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THIYAGARAJAN MAIN ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24450,Roads,Completed,NC-MADHAVARAM,33,935000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT SRI RAMAN SALAI SOUTH IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24451,Roads,Completed,NC-MADHAVARAM,33,1029000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT MUNUSAMY NAGAR EXTN IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24453,Roads,Completed,NC-MADHAVARAM,33,1655000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT RAJAJI SALAI IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24456,Roads,Completed,NC-MADHAVARAM,33,756000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT MOHAN NAGAR IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24459,Roads,Completed,NC-MADHAVARAM,33,1094000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT VPC NAGAR MAIN ROAD IN DN 33,U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24465,Roads,Completed,NC-MADHAVARAM,22,2760000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUNEELAGANDAR NAGAR 1ST STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24466,Roads,Completed,NC-MADHAVARAM,22,2760000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUNEELAGANDAR NAGAR 2ND STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24467,Roads,Completed,NC-MADHAVARAM,22,2240000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUNEELAGANDAR NAGAR 3RD STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24469,Roads,Completed,NC-MADHAVARAM,23,3706000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT OTRAVADAI MAIN STREET IN DN 23, U 6, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24471,Roads,Completed,NC-MADHAVARAM,23,1731000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUPUR KUMARAN STREET IN DN 23, U 6, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24472,Roads,Completed,NC-MADHAVARAM,23,331000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT ANNA NAGAR 5TH STREET IN DN 23, U 6, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24473,Roads,Completed,NC-MADHAVARAM,23,471000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT BAJANAI KOIL STREET IN DN 23, U 6, and Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24474,Roads,Completed,NC-MADHAVARAM,23,291000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT LAKSHMIAMMAN KOIL STREET IN DN 23, U 6, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24476,Roads,Completed,NC-MADHAVARAM,23,112000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT St. ANTHONIYAR MAIN 2ND STREET IN DN 23, U 6, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24477,Roads,Completed,NC-MADHAVARAM,23,676000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUVEEDIYAMMAN KOIL STREET IN DN 23, U 6, Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/24487,Roads,Completed,NC-MADHAVARAM,22,418000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BHARATHIDASAN STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24489,Roads,Completed,NC-MADHAVARAM,22,660000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT GURUSHANTHI NAGAR IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24490,Roads,Completed,NC-MADHAVARAM,22,341000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT MAHAVEER GARDEN IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24491,Roads,Completed,NC-MADHAVARAM,22,506000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT SANKARALINGANAR STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24492,Roads,Completed,NC-MADHAVARAM,22,546000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT SIVARAJ 1ST CROSS STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24494,Roads,Completed,NC-MADHAVARAM,22,356000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRU.VI. KA. STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24497,Roads,Completed,NC-MADHAVARAM,22,500000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT V.O.C STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24498,Roads,Completed,NC-MADHAVARAM,22,566000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT VALLUVAR STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24500,Roads,Completed,NC-MADHAVARAM,25,776000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT COLLECTOR NAGAR MAIN ROAD IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24505,Roads,Completed,NC-MADHAVARAM,25,198000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR 10TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24506,Roads,Completed,NC-MADHAVARAM,25,330000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR 1ST STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24508,Roads,Completed,NC-MADHAVARAM,25,440000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR MAIN 2ND STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24510,Roads,Completed,NC-MADHAVARAM,25,440000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR MAIN 3RD STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24512,Roads,Completed,NC-MADHAVARAM,25,110000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR 4TH STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24513,Roads,Completed,NC-MADHAVARAM,25,176000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR MAIN 5TH STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24514,Roads,Completed,NC-MADHAVARAM,25,220000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR MAIN 6TH STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24517,Roads,Completed,NC-MADHAVARAM,25,176000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR MAIN 7TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24519,Roads,Completed,NC-MADHAVARAM,25,154000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR MAIN 8TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24521,Roads,Completed,NC-MADHAVARAM,25,176000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT BALAJI NAGAR MAIN 9TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24523,Roads,Completed,NC-MADHAVARAM,25,220000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT MAHA LAKSHMI NAGAR 1ST STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24524,Roads,Completed,NC-MADHAVARAM,25,198000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT MAHA LAKSHMI NAGAR 2ND STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24525,Roads,Completed,NC-MADHAVARAM,25,198000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT MAHA LAKSHMI NAGAR 3RD STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24526,Roads,Completed,NC-MADHAVARAM,25,176000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT MAHA LAKSHMI NAGAR 4TH STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24527,Roads,Completed,NC-MADHAVARAM,25,220000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT MAHA LAKSHMI NAGAR 5TH STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24529,Roads,Completed,NC-MADHAVARAM,25,264000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT MAHA LAKSHMI NAGAR MAIN ROAD IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24530,Roads,Completed,NC-MADHAVARAM,25,121000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUVALLUVAR 1ST CROSS STREET IN DN 25, UNIT 6, ZONE III. ",Own Sources,3,2015-16,2016-17 NC/2015-16/24531,Roads,Completed,NC-MADHAVARAM,25,330000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUVALLUVAR 1ST STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24534,Roads,Completed,NC-MADHAVARAM,25,55000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUVALLUVAR 2ND CROSS STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24537,Roads,Completed,NC-MADHAVARAM,25,583000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT THIRUVALLUVAR 2ND STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24540,Roads,Completed,NC-MADHAVARAM,25,1018000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT VEERARAGAVALU NAGAR MAIN STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24542,Roads,Completed,NC-MADHAVARAM,25,690000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT VEERARAGAVALU NAGAR MAIN 2ND STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24543,Roads,Completed,NC-MADHAVARAM,25,345000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT VEERARAGAVALU NAGAR MAIN 3RD STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24545,Roads,Completed,NC-MADHAVARAM,25,220000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT VEERARAGAVALU NAGAR MAIN 4TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24547,Roads,Completed,NC-MADHAVARAM,25,220000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT VEERARAGAVALU NAGAR MAIN 5TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24548,Roads,Completed,NC-MADHAVARAM,25,220000,"ATTENDING BT PATCH WORK TO FLOOD DAMAGED ROAD AT VEERARAGAVALU NAGAR MAIN 6TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/24703,Buildings,Completed,NC-MADHAVARAM,33,250000,REPAIRS AND IMPROVEMENTS WORK AT AMMA UNAVAGAM IN NEHRU STREET AT DN 33 UNIT 8 ZONE III.,Own Sources,3,2015-16,2016-17 NC/2015-16/24897,Roads,Completed,NC-MADHAVARAM,33,848000,PROVIDING AND LAYING WET MIX AT DAMAGED PATCH WORK BY USING WET MIX AT VARIOUS STREET IN DN-33 UNIT-8 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/25145,Buildings,Completed,NC-MADHAVARAM,30,627000,"REPAIRS AND IMPROVEMENTS TO PARK AT RING ROAD HOUSING SECTOR IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/25152,Buildings,Completed,NC-MADHAVARAM,23,995000,"WHITE WASHING,COLOUR WASHING AND LETTER WRITING AT COMPOST YARD IN DN-23,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/25162,Buildings,Completed,NC-MADHAVARAM,32,280000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL ( H.M ROOM BLOCK) BUILDING AT LAKSHMI NARAYANA PERUMAL KOVIL STREET IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/25163,Buildings,Completed,NC-MADHAVARAM,32,635000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL (GROUND FLOOR) AT LAKSHMI NARAYANA PERUMAL KOVIL STREET IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/25165,Buildings,Completed,NC-MADHAVARAM,32,409000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL (FIRST FLOOR) AT LAKSHMI NARAYANA PERUMAL KOVIL STREET IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/25166,Buildings,Completed,NC-MADHAVARAM,32,446000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL COMPOUND WALL AND PLAY GROUND AT LAKSHMI NARAYANA PERUMAL KOVIL STREET IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/25995,Roads,Completed,NC-MADHAVARAM,33,977000,"Repairs and Improvents Work to Canal Retaining Wall in 80 Feet road, Chandra prabhu clny and Selvam nagar main road in DN 33, U 8,Z 3",Own Sources,3,2015-16,2016-17 NC/2015-16/26126,Storm Water Drain,Completed,NC-MADHAVARAM,27,997000,IMPROVEMENTS TO SIDE DRAIN AT ALEX NAGAR A COLONY AND EASWARAN KOIL STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/26129,Buildings,Completed,NC-MADHAVARAM,27,755000,IMPROVEMENTS IN DIVISION 27 OFFICE AT KRISHNA NAGAR IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/26179,Buildings,Completed,NC-MADHAVARAM,26,960000,"PROVIDING E-SEVA CENTRE,TOILET AND OTHER IMPROVEMENTS (FLOOD DAMAGED) TO THE DIVISION OFFICE AT THANIGACHALAM NAGAR 'F' BLOCK 11TH STREET (JUNCTION OF 3RD STREET) IN DIV-26,UN-7,Z-03",Own Sources,3,2015-16,2017-18 NC/2015-16/26416,Buildings,Completed,NC-MADHAVARAM,32,554000,CONSTRUCTION OF FOUNTAIN IN POND AT KUMARAN STREET IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/26803,Buildings,Completed,NC-MADHAVARAM,26,594000,"PROVIDING G.I SHED ROOF(ENTRANCE),ELECTRICAL ARRANGEMENTS AND R.O PLANT(GROUND & FIRST FLOOR) TO HEALTH POST AT SAMI NAGAR IN DIV-26,UN-7,Z-03",Own Sources,3,2015-16,2016-17 NC/2015-16/2686,Roads,Completed,NC-MADHAVARAM,25,2283000,"FORMING AND LAYING BT ROAD AT RAGAVENDRA NAGAR MAIN STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/27137,Parks,Completed,NC-MADHAVARAM,30,881000,"Installation of Tower Clock at VRD Nagar Park, KKR Garden Park, and Ring Road Housing Sector Park in Div-30 & 31, Unit-8, Zone-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/27153,Buildings,Completed,NC-MADHAVARAM,26,575000,"CONSTRUCTION OF TOILET,BATHROOM AND OTHER IMPROVEMENTS TO NIGHT SHELTER AT TRUCK TERMINAL IN DIV-26,UN-7,Z-03",Own Sources,3,2015-16,2017-18 NC/2015-16/27164,Parks,Completed,NC-MADHAVARAM,28,588000,"Installation of Tower Clock at Padmagiri Nagar Park, V.G.P Nagar Park in Div-28 & 33, Unit-7 & 8, Zone-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/27327,Storm Water Drain,Completed,NC-MADHAVARAM,32,999000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT VIVEKANANDHA STREET (SOUTH SIDE) FROM THIRUVALLUVAR STREET TO KADAPPAH ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27357,Storm Water Drain,Completed,NC-MADHAVARAM,32,994000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT VIVEKANANDHA STREET (NORTH SIDE) FROM THIRUVALLUVAR STREET TO KADAPPAH ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27378,Storm Water Drain,Completed,NC-MADHAVARAM,32,998000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT V.O.C. STREET (SOUTH SIDE) FROM THILAGAR STREET TO PRH ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27383,Storm Water Drain,Completed,NC-MADHAVARAM,32,999000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT V.O.C. STREET (NORTH SIDE) FROM THILAGAR STREET TO PRH ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27385,Storm Water Drain,Completed,NC-MADHAVARAM,32,983000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT NETHAJI STREET (SOUTH SIDE) FROM THIRUVALLUVAR STREET TO PRH ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27387,Storm Water Drain,Completed,NC-MADHAVARAM,32,987000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT NETHAJI STREET (NORTH SIDE) FROM THIRUVALLUVAR STREET TO PRH ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27401,Storm Water Drain,Completed,NC-MADHAVARAM,32,853000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT LAKSHMI NARAYANA PERUMAL KOIL STREET FROM VILLIVAKKAM ROAD TO PRH ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27406,Storm Water Drain,Completed,NC-MADHAVARAM,32,987000,IMPROVEMENTS AND RAISING THE SIDE DRAIN AT KUMARAN STREET FROM VILLIVAKKAM ROAD TO GANGAI AMMAN KOIL STREET IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/27535,Buildings,Completed,NC-MADHAVARAM,27,524000,PROVIDING ZEN MODULAR SHELTER WITH ONE YEAR MAINTENANCE AT EDAIMA NAGAR IN DIV-27 UNIT-7 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/27539,Buildings,Completed,NC-MADHAVARAM,27,682000,PROVIDING 7000 LITRES ZEN -ECO DIGESTER WITH ONE YEAR MAINTENANCE AT EDAIMA NAGAR IN DIV-27 UNIT-7 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/27542,Buildings,Completed,NC-MADHAVARAM,24,524000,PROVIDING ZEN MODULAR SHELTER WITH ONE YEAR MAINTENANCE AT METUR LINK ROAD IN DIV-24 UNIT-6 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/27545,Buildings,Completed,NC-MADHAVARAM,24,682000,PROVIDING 7000 LITRES ZEN -ECO DIGESTER WITH ONE YEAR MAINTENANCE AT METTUR LINK ROAD IN DIV-24 UNIT-6 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/27546,Buildings,Completed,NC-MADHAVARAM,33,524000,PROVIDING ZEN MODULAR SHELTER WITH ONE YEAR MAINTENANCE AT GNT ROAD IN DIV-33 UNIT-8 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/27549,Buildings,Completed,NC-MADHAVARAM,33,682000,PROVIDING 7000 LITRES ZEN -ECO DIGESTER WITH ONE YEAR MAINTENANCE AT GNT ROAD IN DIV-33 UNIT-8 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/27825,Buildings,Completed,NC-MADHAVARAM,24,996000,"IMPROVEMENTS AND REPAIRS TO SANMUGAPURAM SCHOOL COMPOUND WALL EAST SIDE BHARATHIDHASAN STREET IN DN-24,U-6,Z-3",Own Sources,3,2015-16,2016-17 NC/2015-16/27832,Buildings,Completed,NC-MADHAVARAM,24,840000,"CONSTRUCTION OF COMPOUND WALL AT CPS AND BARATHI NAGAR 6TH STREET IN DN-24,U-6,Z-3",Own Sources,3,2015-16,2016-17 NC/2015-16/28425,Buildings,Completed,NC-MADHAVARAM,25,998000,"Newly Constructionof NNMP Shed Madura meatupalyam in DN -25, Unit -6, Zone -3",Own Sources,3,2015-16,2017-18 NC/2015-16/28427,Roads,Completed,NC-MADHAVARAM,29,587000,ATTENDING THE PATCH WORKS WITH WET MIX MACADAM AT ADHIRAJ STREET IN DIVISION 29 UNIT 7 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/28429,Buildings,Completed,NC-MADHAVARAM,25,998000,"Newly Constructionof at Kichen Shed and Store Room @ Madura meatupalyam in DN -25, Unit -6, Zone -3",Own Sources,3,2015-16,2017-18 NC/2015-16/29379,Roads,Completed,NC-MADHAVARAM,26,210000,"Providing JCB fpr removal garbage and Temporary Trench cutting (During Mansoon) Omakuam Dumping Ground in div-26, Unit-7, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/29756,Buildings,Completed,NC-MADHAVARAM,25,997000,"CONSTRUCTION OF MULTI PURPOSE HALL AT ANNA STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2017-18 NC/2015-16/30127,Roads,Completed,NC-MADHAVARAM,26,743000,FORMING AND LAYING OF BT ROADS AT VAJRAVEL 1ST STREET DN-26 UNIT-7 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/30128,Roads,Completed,NC-MADHAVARAM,26,953000,FORMING AND LAYING OF BT ROADS AT THIRUMALAI NAGAR EXTENSION 4TH MAIN ROAD DN-26 UNIT-7 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/30227,Buildings,Completed,NC-MADHAVARAM,24,820000,"CONSTRUCTION OF COMPOUND WALL AT SINGARAVELAN STREET OSR LAND IN DN-24,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30228,Storm Water Drain,Completed,NC-MADHAVARAM,23,500000,"IMPROVEMENTS TO SIDE DRAINS AT TALAMUTHU NATARAJAN AND ST.ANTHONIYAR KOIL STREET IN DN-23,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30280,Buildings,Completed,NC-MADHAVARAM,29,995000,"CONSTRUCTION OF COMPOUND WALL IN CHINASAKADU CHENNAI MIDDLE SCHOOL NORTH SIDE IN DN-29,U-7,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30548,Buildings,Completed,NC-MADHAVARAM,26,816000,CONSTRUCTION OF COMPOUND WALL AT NORTH EAST SIDE OF OMAKULAM TRANSFER STATION AT OMAKULAM MEDU IN DIV- 26. UNIT- 07. ZONE -03,Own Sources,3,2015-16,2016-17 NC/2015-16/30574,Buildings,Completed,NC-MADHAVARAM,26,816000,CONSTRUCTION OF COMPOUND WALL AT NORTH WEST SIDE OF OMAKULAM TRANSFER STATION AT OMAKULAM MEDU IN DIVISION- 26. UNIT -07. ZONE- 03,Own Sources,3,2015-16,2016-17 NC/2015-16/30575,Buildings,Completed,NC-MADHAVARAM,26,816000,CONSTRUCTION OF COMPOUND WALL AT EAST SIDE OF OMAKULAM TRANSFER STATION AT OMAKULAM MEDU IN DIVISION - 26. UNIT -07. ZONE- 03,Own Sources,3,2015-16,2016-17 NC/2015-16/30587,Buildings,Completed,NC-MADHAVARAM,26,762000,"IMPROVEMENTS TO OMAKULAM TRANSFER STATION AT OMAKULAM MEDU IN DIV-26, UNIT-7, ZONE-3.",Own Sources,3,2015-16,2017-18 NC/2015-16/30601,Buildings,Completed,NC-MADHAVARAM,23,465000,"IMPROVEMENTS TO DIVISION OFFICE AT GNT ROAD IN DN-23,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30602,Buildings,Completed,NC-MADHAVARAM,24,791000,"CONSTRUCTION OF COMPOUND WALL AT OSR LAND (SOUTH SIDE) NEAR AMMA UNAVAGAM IN DN-24,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30603,Buildings,Completed,NC-MADHAVARAM,22,420000,"IMPROVEMENTS TO DIVISION OFFICE AT GANDHI MAIN ROAD IN DN-22,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30608,Roads,Completed,NC-MADHAVARAM,24,780000,"ATTENDING PATCH WORK AT KADDAPA ROAD,SURAPATTU MAIN ROAD NEAR BRIDGE IN DN-24,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30614,Buildings,Completed,NC-MADHAVARAM,23,995000,"IMPROVEMENTS TO FOOT BALL GROUND AND AUDITORIUM ROOM IN DN-23,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30618,Roads,Completed,NC-MADHAVARAM,33,494000,"REPAIRS AND IMPROVEMENT TO PARK AT THANIKACHALAM NAGAR 5 TH MAIN ROAD IN N -33 UNIT -8, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/30622,Roads,Completed,NC-MADHAVARAM,26,847000,FORMING AND LAYING OF BT ROADS AT THIRUPPATHI THANGAVEL NAGAR MAIN ROAD DN-26 UNIT-7 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/30623,Roads,Completed,NC-MADHAVARAM,26,953000,FORMING AND LAYING OF BT ROADS AT THIRUPPATHI THANGAVEL NAGAR 5TH STREET DN-26 UNIT-7 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/30625,Storm Water Drain,Completed,NC-MADHAVARAM,33,145000,REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT SELVAM NAGAR MAIN ROAD IN DN-33 UNIT-8 ZONE-6,Own Sources,3,2015-16,2016-17 NC/2015-16/30662,Parks,Completed,NC-MADHAVARAM,30,966000,"CONSTRUCTION OF COMPOUND WALL OF VRD NAGAR PARK EXTENDED PORTION IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30664,Roads,Completed,NC-MADHAVARAM,30,357000,"Improvements & Painting Works at Unit Office-8 MRH road in div-30, Unit-8, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30751,Buildings,Completed,NC-MADHAVARAM,24,545000,"CONSTRUCTION OF COMPOUND WALL AT SIVAPRAGASAM NAGAR COMMUNITY HALL IN DN-24,U-6,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30765,Buildings,Completed,NC-MADHAVARAM,30,335000,"REPAIRS AND IMPROVEMENTS PC AT BHARATHIYAR STREET IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/30806,Buildings,Completed,NC-MADHAVARAM,29,990000,"CONSTRUCTION OF CYCLE STAND AT CHENNAI MIDDLE SCHOOL IN DAVARAJAN STREET IN DN-29,U-7,Z-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/31009,Buildings,Completed,NC-MADHAVARAM,22,704000,"Providing Water Supply arrangements to NNMP Center at Perumal Kovil street in div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/31018,Buildings,Completed,NC-MADHAVARAM,22,376000,"Providing Electfication and Drainage arrangements to NNMP Center at Perumal Kovil street in div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/32872,Roads,Completed,NC-MADHAVARAM,33,999000,FORMING AND LAYING WBM ROAD AT SUMATHI NAGAR MAIN ROAD IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2017-18 NC/2015-16/32873,Roads,Completed,NC-MADHAVARAM,33,998000,FORMING AND LAYING WBM ROAD AT ELIZABETH NAGAR MAIN ROAD IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/32874,Roads,Completed,NC-MADHAVARAM,33,997000,FORMING AND LAYING WBM ROAD AT ELIZABETH NAGAR 1ST STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2015-16,2016-17 NC/2015-16/32882,Roads,Completed,NC-MADHAVARAM,22,995000,"IMPROVEMENTS TO STORM WATER DRAIN MARIAMMAL NAGAR MAIN STREET IN DN-22,U-6,Z-3.",Own Sources,3,2015-16,2018-19 NC/2015-16/33020,Storm Water Drain,Completed,NC-MADHAVARAM,27,995000,"IMPROVEMENTS TO SIDE DRAIN AT MANDAVELI 1st STREET IN DN-27,U-7,Z-3.",Own Sources,3,2015-16,2018-19 NC/2015-16/33025,Storm Water Drain,Completed,NC-MADHAVARAM,27,995000,"IMPROVEMENTS TO SIDE DRAIN AT MANDAVELI 2nd STREET IN DN-27,U-7,Z-3.",Own Sources,3,2015-16,2018-19 NC/2015-16/33026,Storm Water Drain,Completed,NC-MADHAVARAM,27,985000,"IMPROVEMENTS TO SIDE DRAIN AT SATHYASAI NAGAR AND RAMA KANNAMMA STREET IN DN-27,U-7,Z-3.",Own Sources,3,2015-16,2018-19 NC/2015-16/33068,Roads,Completed,NC-MADHAVARAM,22,994000,"IMPROVEMENTS TO STORM WATER DRAIN AT GURUSHANTHI NAGAR MAIN ROAD IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2018-19 NC/2015-16/33070,Buildings,Completed,NC-MADHAVARAM,25,400000,"REPAIR AND IMPROVEMENTS TO TOILET AT KADHIRVEDU NEAR CMS SCHOOL IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/33443,Culvert,Completed,NC-MADHAVARAM,22,960000,"Improvements to side drain at Valluvar street, Perumal Kovil street. Paneer selvam street. Lal Bhaghadur Sastri street and Ko.Si. Mani in Div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2018-19 NC/2015-16/33463,Buildings,Completed,NC-MADHAVARAM,22,710000,"Improvements to Chennai Middle School at Gandhi Street in div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2018-19 NC/2015-16/33472,Buildings,Completed,NC-MADHAVARAM,22,765000,"Improvements to Chennai Middle School at K.S.Nagar 6th steet in div-22, Unit-6, Zone-3.",Own Sources,3,2015-16,2018-19 NC/2015-16/33486,Storm Water Drain,Completed,NC-MADHAVARAM,26,892000,"IMPROVEMENT TO THE SIDE DRAIN AT SEETHAPATHY STREET IN DN 26, UNIT-7, ZONE III",Own Sources,3,2015-16,2018-19 NC/2015-16/33489,Parks,Completed,NC-MADHAVARAM,26,92000,MAINTENANCE OF PARK AT SECRETARIATE COLONY JUNCTION OF PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DIVISION-26 UNIT-7 ZONE-3,Own Sources,3,2015-16,2016-17 NC/2015-16/33490,Roads,Completed,NC-MADHAVARAM,26,981000,"PROVIDING AND FIXING STREET NAME BOARD AT VINAYAGAPURAM,VILLIVAKKAM ROAD,GANDHI STREET, KAMARAJAR STREET AND VARIOUS STREET IN DN-26 UNIT-7 ZONE-3",Own Sources,3,2015-16,2017-18 NC/2015-16/33491,Roads,Completed,NC-MADHAVARAM,26,926000,"PROVIDING AND FIXING STREET NAME BOARD AT GANESH NAGAR,SUBRAMANIAN NAGR,PARIMALAM NAGAR,SECRETAIRIT COLONY AND VARIOUS STREET IN DN-26 UNIT-7 ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/33492,Roads,Completed,NC-MADHAVARAM,26,999000,"PROVIDING AND FIXING STREET NAME BOARD AT SASTHIRY NAGAR, SASTHIRY NAGAR EXTN,THIRUMALAI NAGAR,THIRUMALAI NAGAR EXTN AND VARIOUS STREET IN DN-26 UNIT-7 ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/33493,Roads,Completed,NC-MADHAVARAM,26,954000,"PROVIDING AND FIXING STREET NAME BOARD AT VAJRAVEL NAGAR,THANGAVEL NAGAR,THIRUPATHY THANGAVRL NAGAR,THANIGAI NAGAR AND VARIOUS STREET IN DN-26 UNIT-7 ZONE-3",Own Sources,3,2015-16,2017-18 NC/2015-16/33494,Roads,Completed,NC-MADHAVARAM,26,981000,"PROVIDING AND FIXING STREET NAME BOARD AT MAJASTIC COLONY, THANIGACHALAM F BLOCK,NATESHAN NAGAR,DEVAGI NAGAR AND VARIOUS STREET IN DN-26 UNIT-7 ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/33521,Parks,Completed,NC-MADHAVARAM,22,97000,"MAINTENANCE OF PARK AT GURUSANTHI NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-22, UNIT-6, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33530,Parks,Completed,NC-MADHAVARAM,22,133000,"MAINTENANCE OF PARK AT MACRO MARVEL 1ST CROSS STREET AND MACRO MARVEL 2ND CROSS STREET OF PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-22 , UNIT-6, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33535,Parks,Completed,NC-MADHAVARAM,23,91000,"MAINTENANCE OF PARK AT AMBATTUR RED HILLS ROAD OF PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-23 , UNIT-6, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33536,Parks,Completed,NC-MADHAVARAM,24,95000,"MAINTENANCE OF PARK AT DG NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-24 , UNIT-6, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33537,Parks,Completed,NC-MADHAVARAM,25,93000,"MAINTENANCE OF PARK AT PADMAVATHY NAGR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN- 25, UNIT- 6, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33538,Parks,Completed,NC-MADHAVARAM,25,94000,"MAINTENANCE OF PARK AT SRINIVASA NAGAR MAIN ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-25 , UNIT-,6 ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33539,Parks,Completed,NC-MADHAVARAM,25,121000,"MAINTENANCE OF PARK AT COLLECTOR NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN- 25, UNIT- 6, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33540,Parks,Completed,NC-MADHAVARAM,28,230000,"MAINTENANCE OF PARK AT PADMAGIRI NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-28 , UNIT-7, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33549,Parks,Completed,NC-MADHAVARAM,30,102000,"MAINTENANCE OF PARK AT SIVASAKTHI NAGAR AND RC FLATS PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-30 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33550,Parks,Completed,NC-MADHAVARAM,30,196000,"MAINTENANCE OF PARK AT RING ROAD HOUSING SECTOR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-30 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33551,Parks,Completed,NC-MADHAVARAM,30,205000,"MAINTENANCE OF PARK AT V.R.D. NAGAR PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN- 30, UNIT-8, ZONE-III",Own Sources,3,2015-16,2016-17 NC/2015-16/33552,Parks,Completed,NC-MADHAVARAM,31,214000,"MAINTENANCE OF PARK AT K.K.R. NAGAR 1ST MAIN ROAD AND MRH ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN- 31 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2017-18 NC/2015-16/33555,Parks,Completed,NC-MADHAVARAM,31,288000,"MAINTENANCE OF PARK AT K.K.R GARDEN 2ND MAIN ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-31 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2017-18 NC/2015-16/33556,Parks,Completed,NC-MADHAVARAM,32,97000,"MAINTENANCE OF PARK AT TEACHERS COLONY 4TH CROSS ST PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-32 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2017-18 NC/2015-16/33557,Parks,Completed,NC-MADHAVARAM,32,94000,"MAINTENANCE OF PARK AT TEACHERS COLONY 6TH MAIN ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-32 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2017-18 NC/2015-16/33558,Parks,Completed,NC-MADHAVARAM,33,63000,"MAINTENANCE OF PARK AT SELVAM NAGAR EXTENSION PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-33 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2017-18 NC/2015-16/33559,Parks,Completed,NC-MADHAVARAM,33,87000,"MAINTENANCE OF PARK AT VGP NAGAR MAIN ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-33 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2017-18 NC/2015-16/33560,Parks,Completed,NC-MADHAVARAM,33,88000,"MAINTENANCE OF PARK AT THANICKACHALAM NAGAR B BLK 6TH MAIN ROAD PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF APRIL 2016 TO JUNE 2016 IN DN-33 , UNIT-8, ZONE-III",Own Sources,3,2015-16,2017-18 NC/2015-16/4919,Buildings,Completed,NC-MADHAVARAM,25,778000,"PROVIDING WATER SUPPLY ARRANGEMENT TO CHENNAI MIDDLE SCHOOL AT GANDHI MAIN STREET IN DN 22, UNIT 6, ZONE III.",Own Sources,3,2015-16,2016-17 NC/2015-16/5118,Parks,Completed,NC-MADHAVARAM,33,117000,"IMPROVEMENT TO PARK IN V.G.P NAGAR IN DIVISION-33, UNIT-8, ZONE-3",Own Sources,3,2015-16,2016-17 NC/2015-16/8135,Buildings,Completed,NC-MADHAVARAM,24,660000,"Additional Work OF Gas Room and Septic Tank to AMMA UNAVAGAM at Cuddappa Road Puthagaram in Dn : 24, U : 6, Z: 3",Own Sources,3,2015-16,2016-17 NC/2015-16/9782,Roads,Completed,NC-MADHAVARAM,28,865000,"Widening the road at Moolachatram Main road (Both sides) IN Ward-28,Unit-7,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/9784,Roads,Completed,NC-MADHAVARAM,28,275000,"Widening the road at V.N.G road (Both sides) in Ward-28,Unit-7,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/9787,Storm Water Drain,Completed,NC-MADHAVARAM,33,193000,"Improvements to the Storm Water drain at Anna Street in Ward-33, Unit-8,Zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/9792,Storm Water Drain,Completed,NC-MADHAVARAM,33,315000,"Improvements of Retaining wall at Thanikachalam Nagar 80 feet road in Ward-33, Unit-8,Zone-3",Own Sources,3,2015-16,2016-17 NC/2015-16/9794,Storm Water Drain,Completed,NC-MADHAVARAM,33,950000,"Improvements to Strom Water Drain at Kasiammal nagar 1st street in Ward-33,Unit-7,Zone-3.",Own Sources,3,2015-16,2016-17 NC/2015-16/9797,Storm Water Drain,Completed,NC-MADHAVARAM,33,485000,"Improvements to Strom Water Drain at V.G.P nagar 1st Street in Ward-33, Unit-8,Zone-3",Own Sources,3,2015-16,2016-17 ND/2015-16/0078,Buildings,Completed,ND-TONDIARPET,46,870000,Providing drainage arrangements and electrical arrangements and other works in cms at C Kalyanapuram in ward.46 u.11 z.4,Own Sources,4,2015-16,2016-17 ND/2015-16/0196,Buildings,Completed,ND-TONDIARPET,36,970000,"Petty repair works carrying out (Day to Day) to Chennai High school,Chennai Primary school at Sharma nagar,Public convenience at Dr.Ambedkar street,N.N.M.P.Shed at S.A.Colony,Indhira Gandhi nagar etc in Div-36,Unit-9,Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/0454,Buildings,Completed,ND-TONDIARPET,45,600000,"IMPROVEMENT WORK TO PUBLIC TOILET AT GANESHAPURAM MAIN ROAD AND SUNDARAM MAIN ROAD IN DN.45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/0459,Buildings,Completed,ND-TONDIARPET,45,997000,"IMPROVEMENT WORKS TO SANJAY NAGAR PARK AT SANJAY NAGAR IN DN.45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/0720,Playfields,Completed,ND-TONDIARPET,35,995000,"IMPROVEMENTS TO CHILDREN PLAY PLACE AND ANGANVADI COLOUR WASHING IN 4TH BLOCK 52TH STREET AT MUTHAMIL NAGAR ,DIVISION-35, UNIUT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/0879,Buildings,Completed,ND-TONDIARPET,35,970000,"IMPROVEMENTS TO CHILDREN PLACE SPACE AT 199TH STREET, 203TH STREET AND 210TH STREET MUTHAMIL NAGAR AT DIVISION-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/10365,Roads,Completed,ND-TONDIARPET,40,1186000,"Laying CC Road at Jeeva Nagar 1st Street in DN-40,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/10396,Storm Water Drain,Completed,ND-TONDIARPET,45,970000,"IMPROVEMENT TO STROM WATER DRAIN AT CLINIC ROAD FROM JUNCTION OF B.V. COLONY CHRUCH TO E.H. ROAD IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/10444,Buildings,Completed,ND-TONDIARPET,46,997000,"REPAIRS AND IMPROVEMENT, LAYING CEMENT CONCRETE AND OTHER WORKS AT CHENNAI CORPORATION HOSPITAL IN DN -46 ,UNIT-11,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/10509,Roads,Completed,ND-TONDIARPET,46,995000,"Providing Silt Catch it and Vertical Gartings in the Exisiting Storm Water Drain at S.M.Nagar main road in DN -46,Unit -11,Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/10601,Playfields,Completed,ND-TONDIARPET,48,585000,"PROVIDING GYM APPARATUS IN GYM @ KANNI KOVIL ST IN DN-48, U-11, Z-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/10626,Buildings,Completed,ND-TONDIARPET,36,1957000,Construction Of Dinning Hall CHS At Sharmanagar 2nd Main Road in DN-36 Unit-09 Zone-04,MLACDS,4,2015-16,2016-17 ND/2015-16/10705,Electrical,Completed,ND-TONDIARPET,45,981300,"Provision of 50nos of 3mtr Garden Lamp Post with 20 watts LED Fitting at Sundaram 5th street Park,Sanjay nagar Park,Ganesapuram Park,MM Garden Park in Division 45,Unit 11,Zone 4.",Own Sources,4,2015-16,2016-17 ND/2015-16/10799,Buildings,Completed,ND-TONDIARPET,43,791000,"Improvements to chennai middle school (south block) at vinayagapuram in div-43,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/10810,Buildings,Completed,ND-TONDIARPET,43,895000,"RAISING THE LEVEL AND LAYING CONCRETE TILES &PROVIDING ROOFING ARRANGEMENT TO INFRONT OF CHENNAI MIDDLE SCHOOL AT VINAYAGAPURAM ION DIV-43,UNIT-10,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/10830,Roads,Completed,ND-TONDIARPET,40,994000,"PROVIDING STREET NAME BOARDS AT AMMANIAMMAL GARDEN,SIVAN NAGAR AND VOC NAGAR IN DN-40, UNIT-10, ZONE-04 (WARD COUNCILLOR SCHEME)",Own Sources,4,2015-16,2016-17 ND/2015-16/10831,Buildings,Completed,ND-TONDIARPET,40,990000,"CONSTRUCTION OF YOGA STAGE IN CHENNAI CORPORATION PARK AT ELLAYA STREET IN DIV-40,UNIT-10,ZONE-04. (WARD COUNCILLOR SCHEME)",Own Sources,4,2015-16,2016-17 ND/2015-16/10832,Roads,Completed,ND-TONDIARPET,44,395000,"Engaging of Technical Assistant(Grade-I & Grade-II) to Assist the A.E in Division-44,45,46 & 48 in Unit-11, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/10923,Buildings,Completed,ND-TONDIARPET,43,958000,"Construction of Disabled Frienly Toilet at S.N Cheety Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/10973,Buildings,Completed,ND-TONDIARPET,38,652000,"Facelifting work to P.C at Parameshwari Nagar in Dn-38, Unit-9,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/11059,Parks,Completed,P-Parks and Playfields,34,7485000,"proposed new morden park at union carbide colony 9th street in dn-34,unit-9,zone-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/11064,Buildings,Completed,ND-TONDIARPET,36,420000,"Construction of Disabled Frienly Toilet at Ambedkar Street (Suzhlpunal Karai) in DN-36,U-09,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11065,Buildings,Completed,ND-TONDIARPET,36,472000,"Construction of Disabled Frienly Toilet at EH ROAD (Sharmanagar) in DN-36,U-09,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11066,Buildings,Completed,ND-TONDIARPET,36,420000,"Construction of Disabled Frienly Toilet at Sastri Nagar 16th Street in DN-36,U-09,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11067,Buildings,Completed,ND-TONDIARPET,36,420000,"Construction of Disabled Friendly Toilet at Indira Gandhi Nagar in DN-36,U-09,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/1108,Roads,Completed,ND-TONDIARPET,42,230000,"Providing Chain Link Fencing To Open Area At Seniamman Koil Street (Near Agastiyar Appartments) In Div-42,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/11084,Buildings,Completed,ND-TONDIARPET,43,506000,"Proposed Construction of Single room Building and Baby toilet for NNMP Shed at SN chetty Street in Dn-43, Ut-10, Zn-4",Own Sources,4,2015-16,2016-17 ND/2015-16/1117,Roads,Completed,ND-TONDIARPET,42,991000,"Laying cc road by RMC infront of the G block at Thilagar nagar Tsunami quarters in div -42 unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/11218,Buildings,Completed,ND-TONDIARPET,42,990000,Improvements to toilet in Dhobikana at gothandaraman lane in ward 42 unit 10 zone 4,Own Sources,4,2015-16,2016-17 ND/2015-16/11226,Buildings,Completed,ND-TONDIARPET,42,990000,"Improvements to the ICDS at Rettaikuzhi street in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11230,Buildings,Completed,ND-TONDIARPET,42,807000,Improvements to the AMMA UNAVAGAM AT seniamman koil street in ward 42 unit 10 zone 4,Own Sources,4,2015-16,2016-17 ND/2015-16/11245,Roads,Completed,ND-TONDIARPET,42,1430000,"Relaying the BT Road @ Appasamy Pillai Thottam Main Street Dn-42,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/11316,Roads,Completed,ND-TONDIARPET,42,365000,"Relaying the BT Road T.H.Road 3rd lane in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11317,Roads,Completed,ND-TONDIARPET,42,668000,"Relaying the Bt road @T.H,Road 4TH lane in dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11320,Roads,Completed,ND-TONDIARPET,42,410000,"Relaying the BT Road @Arani ragan Street in Dn-42,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/11322,Roads,Completed,ND-TONDIARPET,42,2938000,"Relaying the BT Road @Arani ragan 1st Street in Dn-42,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/11325,Roads,Completed,ND-TONDIARPET,42,546000,"Relaying the BT Road@ Chellappa Colony (T.H Road) in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11327,Roads,Completed,ND-TONDIARPET,42,910000,"Relaying the BT Road @ Mayar Basudev 2nd lane in dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11330,Roads,Completed,ND-TONDIARPET,42,583000,"Relaying the BT Road @ Veera Kutty garden(Slums) in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11335,Roads,Completed,ND-TONDIARPET,42,1300000,"Relaying the BT Road@ West Krishnappa Thottam 2nd Street in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11336,Buildings,Completed,ND-TONDIARPET,42,998000,Providing lighting arrangements and SS hand rails to jeeva park at T.H Road in ward 42 unit 10 zone 4,Own Sources,4,2015-16,2016-17 ND/2015-16/11343,Roads,Completed,ND-TONDIARPET,42,999000,"Relaying the Bt road @ West Krishnappa Thottam 1st street in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11344,Parks,Completed,ND-TONDIARPET,42,982000,Providing SS hand rail to Tower park and play apparatus area inside park at TH Road in ward 42 unit 10 zone 4,Own Sources,4,2015-16,2016-17 ND/2015-16/11368,Roads,Completed,ND-TONDIARPET,42,1090000,"Relaying the BT Raods @ Selva Vinayagar Koil Street in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11371,Roads,Completed,ND-TONDIARPET,42,999000,"Relaying the BT Road @West Krishappa Garden 3rd Street in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11402,Roads,Completed,ND-TONDIARPET,42,437000,"Relaying Of BT Road @West Veera Kutty Street In Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11423,Roads,Completed,ND-TONDIARPET,42,990000,"providing and fixing street name board at Mayor Basudev 1st, 2nd streets, Veerakutty Street, Kothandaraman Street, TH Road, Service lane, Seniamman Koil Main Street, MCM Garden 1st, 2nd & 3rd and various street in ward 42 unit 10 zone 4",Own Sources,4,2015-16,2016-17 ND/2015-16/11430,Buildings,Completed,ND-TONDIARPET,42,900000,Providing iron sheet shed for dhobikana at kothandaraman street in Dn-42 Unit-10 Zone-04,Own Sources,4,2015-16,2016-17 ND/2015-16/11590,Buildings,Completed,ND-TONDIARPET,38,999000,"Improvements to Anganwadi Center No 12092,12096 & 12130, 12131 at New Vinobha Nagar 1st Street, Nethaji Nagar 6th Street and Navalar Nagar A Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/11658,Buildings,Completed,ND-TONDIARPET,47,990000,"Repairs and improvements @ Dr.Ambedhar Nagar GYM Building in DN -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/11659,Buildings,Completed,ND-TONDIARPET,47,767000,"Repairs and improvements @ Harinarayana puram (Old Class Road) GYM Building in DN -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/11727,Buildings,Completed,ND-TONDIARPET,47,960000,"Repairs and improvements @ PC at Thiyagappa street in DN -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/11849,Roads,Completed,ND-TONDIARPET,37,670000,"Restoration Of Road Cut Estimate At Dhamodhar Nagar 1st Street,7th Street And Udayasuriyan Nagar In Div-37,Unit-09,Zone",Deposit Works,4,2015-16,2016-17 ND/2015-16/11861,Parks,Completed,ND-TONDIARPET,37,897000,"IMPROVEMENTS TO CHILDRENS PLAY SPACE AT K.K.D.NAGAR 7TH BLOCK - 2ND STREET,IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/11872,Parks,Completed,ND-TONDIARPET,37,751000,"IMPROVEMENTS TO PARK AT K.K.D.NAGAR 8TH BLOCK - 9TH MAIN ROAD IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/11873,Parks,Completed,ND-TONDIARPET,37,822000,"DEMOLITION & RE-CONSTRUCTION OF COMPOUND WALL TO CHILDRENS PLAY SPACE IN BETWEEN M.K.B.NAGAR 14TH & 15TH CENTRAL CROSS STREETS IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/11917,Parks,Completed,ND-TONDIARPET,43,457000,"Improvement to S.N Cheety Street and M.G.R Nagar Park in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11933,Parks,Completed,ND-TONDIARPET,46,995000,"REPAIRS AND IMPROVEMENTS TO ROAD SIDE PARK AT JUNCTION MOORTINGAR STREET AND EH ROAD IN DN-46,UNIT-11,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/11971,Buildings,Completed,ND-TONDIARPET,35,970000,"PROVIDING AND FIXING STREET FURNITURE VARIOUS STREET AT ERUKKENCHERRY IN DIV-35, U NIT-9, ZONE-4 COUNCILAR FUND (2015-16)",Own Sources,4,2015-16,2016-17 ND/2015-16/11984,Buildings,Completed,ND-TONDIARPET,35,970000,"PROVIDING AND FIXING STREET FURNITURE VARIOUS STREET AT KANNADASAN NAGAR INDIV-35, UNIT-09, ZONE-4 COUNCILAR FUND (2015-16)",Own Sources,4,2015-16,2016-17 ND/2015-16/12009,Parks,Completed,ND-TONDIARPET,37,855000,"IMPROVEMENTS TO CHILDRENS PLAY SPACE IN BETWEEN M.K.B.NAGAR 14TH & 15TH CENTRAL CROSS STREETS IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12010,Parks,Completed,ND-TONDIARPET,37,578000,"IMPROVEMENTS TO PARK AT M.K.B.NAGAR 4TH CROSS STREET IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12139,Parks,Completed,ND-TONDIARPET,37,745000,"IMPROVEMENTS TO PLAYGROUND AT M.K.B.NAGAR 3RD CROSS STREET IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12274,Roads,Completed,ND-TONDIARPET,40,3200000,"Relaying the CC Road at Jeeva Nagar Main Road in Dn-40,U-10,Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12291,Buildings,Completed,ND-TONDIARPET,43,850000,"Construction of Single Room Building community Hall at kasimanagar 3rd Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12403,Roads,Completed,ND-TONDIARPET,39,998000,"Attending Patch work in Cross Road Lane, Thiyagi perumal Koil Lane, TH Road Lane, Market form 8th Lane in Dn.39 U-10, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12536,Buildings,Completed,ND-TONDIARPET,43,947000,"PROPOSED CONSTRUCTION OF PATH WAY AROUND PARK (AT C.D.H (MAIN BUILDING BACK SIDE)IN DN-43,UN-10,ZN-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12542,Buildings,Completed,ND-TONDIARPET,43,907000,"PROPOSED CONSTRUCTION OF OPEN GYM AT INSIDE OF C.D.H PARK (BACKSIDE OF MAIN GATE) IN DN- 43,UN-10,ZN-4",Own Sources,4,2015-16,2017-18 ND/2015-16/12565,Buildings,Completed,ND-TONDIARPET,36,883000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT SHARMA NAGAR 2ND MAIN ROAD IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12566,Buildings,Completed,ND-TONDIARPET,36,984000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL (INSIDE BUILDING) AT SHARMA NAGAR 2ND MAIN ROAD IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12567,Buildings,Completed,ND-TONDIARPET,36,921000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL (OUTSIDE BUILDING) AND COMPOUND WALL (C.P.S & C.H.S CAMPUS) AT SHARMA NAGAR 2ND MAIN ROAD IN DN- 36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12568,Buildings,Completed,ND-TONDIARPET,36,994000,"PROVIDING PATHWAY (From compound wall gate to C.P.S.Building) AND IMPROVEMENTS TO PLAY AREA IN CHENNAI PRIMARY SCHOOL AND CHENNAI HIGH SCHOOL CAMPUS AT SHARMA NAGAR 2ND MAIN ROAD IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/12580,Roads,Completed,ND-TONDIARPET,40,4990000,"Relaying the C.C Road at Thiruvalluvar Nagar Housing Board (Huts) in Dn-40,U-10,Z-4",Own Sources,4,2015-16,2017-18 ND/2015-16/12633,Buildings,Completed,ND-TONDIARPET,46,998000,"IMPROVEMENT WORKS TO DIVISION OFFICE IN DN-46, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12637,Buildings,Completed,ND-TONDIARPET,47,980000,"Improvements to Dispensary @ at Harinarayanapuram in DN -47, Unit-11, Zone -04.",Own Sources,4,2015-16,2017-18 ND/2015-16/12650,Buildings,Completed,ND-TONDIARPET,47,960000,"Improvements @ Meenambal Nagar 1st Street (CPS) School in DN -47,Unit -11, Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/12651,Footpath,Completed,ND-TONDIARPET,48,890000,"LAYING CEMENT CONCRETE FOR WIDENING ROAD PORTION AT NAILAPPA VATHIYAR STREET IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2015-16,2016-17 ND/2015-16/12652,Footpath,Completed,ND-TONDIARPET,48,900000,"WIDENING ROAD PORTION AT SOLAIYAPPAN STREET IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2015-16,2016-17 ND/2015-16/12653,Footpath,Completed,ND-TONDIARPET,48,940000,"LAYING CEMENT CONCRETE FOR WIDENING ROAD PORTION AT JAMAL SOWCAR STREET, JAMAL SOWCAR LANE AND NATARAJ ST IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2015-16,2016-17 ND/2015-16/12656,Footpath,Completed,ND-TONDIARPET,48,780000,"Widening Road Portion at D.B.K Street in Dn-48,U-11,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/12658,Footpath,Completed,ND-TONDIARPET,48,900000,"LAYING CEMENT CONCRETE FOR WIDENING ROAD PORTION AT KANNI KOVIL STREET,BASUVAYAN ST IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2015-16,2016-17 ND/2015-16/12659,Footpath,Completed,ND-TONDIARPET,48,940000,"WIDENING ROAD PORTION AT NAMACHIVAYAN STREET, BUDDHA ST AND MUTHUMARIYAMMAN ST IN DN-48,U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12665,Buildings,Completed,ND-TONDIARPET,47,710000,"Improvements @ NNMP Shed at Meenambal Nagar in DN -47,Unit -11,Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/12666,Buildings,Completed,ND-TONDIARPET,47,670000,"Improvements @ NNMP Shed at Ananthanayagi Nagar 2nd Street in DN -47,Unit -11,Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/12668,Storm Water Drain,Completed,ND-TONDIARPET,46,325000,"Repairs to Storm Water Drains at AB Kalyanapuram Main Road,Mosque Street ,Palla 2nd Street and S.M nagar main road in Ward-46, Unit-11,Zone-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/12674,Roads,Completed,ND-TONDIARPET,48,940000,"LAYING ILB FOR WIDENING ROAD PORTION AT SUBBAMMAL STREET , AMMAIYAPPAN ST AND THANGAVELU ST IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2015-16,2016-17 ND/2015-16/12677,Storm Water Drain,Completed,ND-TONDIARPET,48,135000,"ANNUAL MAINTENANCE FOR SUNDARAMURTHY PARK AT TELUGU STREET IN DN-48, U-11, Z-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/12689,Buildings,Completed,ND-TONDIARPET,39,846000,"Improvements to Public Convenience inside Dhobikana at Irusappa Street in Dn.39, U-10, Zone-4",Own Sources,4,2015-16,2017-18 ND/2015-16/12692,Buildings,Completed,ND-TONDIARPET,48,375000,"IMPROVEMENT OF I.C.D.S IN CENTER NO;206 AT KANNIKOVIL STREET IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/12697,Buildings,Completed,ND-TONDIARPET,48,970000,"IMPROVEMENT TO THE HEALTH POST AT MOTTAI THOTTAM IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/12699,Buildings,Completed,ND-TONDIARPET,48,940000,"IMPROVEMENT TO THE COMMUNITY CENTER AT PARTHASARATHY STREET IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/12703,Buildings,Completed,ND-TONDIARPET,48,865000,"IMPROVEMENT TO THE UNIT OFFICE AT PARTHASARATHY STREET IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/12705,Buildings,Completed,ND-TONDIARPET,39,970000,"Improvements to NNMP Centre at Irusappa street, Butchammal street, Dhanapal Nagar, and Poondi Thangammal Street In Division 39 Unit 10 Zone 4",Own Sources,4,2015-16,2016-17 ND/2015-16/12706,Buildings,Completed,ND-TONDIARPET,48,700000,"IMPROVEMENT TO THE GYM BUILDING AT KANNI KOVIL STREET DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/1271,Bridges,Completed,ND-TONDIARPET,36,740000,"Improvements To Bridge at Meenambal salai West side (Foot path & Handrail) in Dn-36, Unit-9, Zone-4",Own Sources,4,2015-16,2017-18 ND/2015-16/12780,Roads,Completed,ND-TONDIARPET,41,1810000,"Relaying of C.C at Periyar Nagar Cross Street in Div-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12781,Roads,Completed,ND-TONDIARPET,41,970000,"Relaying of C.C at Nehru Nagar Moopanar Street in Div-41,Un-10,Zn-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12787,Roads,Completed,ND-TONDIARPET,41,980000,"Relaying of C.C at Drivers Colony in Div-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12796,Buildings,Completed,ND-TONDIARPET,43,919000,"Construction of First Floor Communiy Hall (UPHC) at Kasimanagar 3rd Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12798,Buildings,Completed,ND-TONDIARPET,35,986000,"IMPROVEMENTS TO CHILDRAN PLAY SPACE AT 151TH STREET, 6TH BLOCK,MUTHAMIL NAGAR IN DIV-35, UNIT-9, ZONE4",Own Sources,4,2015-16,2016-17 ND/2015-16/12813,Parks,Completed,ND-TONDIARPET,35,850000,"IMPROVEMENTS TO KRISHNAN PARK AT GANDHI NAGAR IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/12827,Roads,Completed,ND-TONDIARPET,34,700000,"RAISING AND FORMING THE NEW ROAD AT KATTABOMMAN 7thSTREET AND PANNAIMARA STREET AND N.C.L NAGAR 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12830,Buildings,Completed,ND-TONDIARPET,35,940000,"IMPROVEMENTS TO ANGANWADI CENTRES: .12077,12070,12071, 12073, 12074,12075 AT MUTHAMIL NAGAR AND KANNDASAN NAGAR IN DV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/12831,Roads,Completed,ND-TONDIARPET,34,930000,"RAISING AND FORMING THE NEW ROAD AT NACHEAMMAI NAGAR MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12832,Buildings,Completed,ND-TONDIARPET,42,995000,"Imporvement Work in Unit Office,JE Room & C.I Room in Dn-42,Unit-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12835,Roads,Completed,ND-TONDIARPET,34,665000,"RAISING AND FORMING THE NEW ROAD AT NACHIAMMAI NAGAR 3rd,5th,6th AND 7th STREETIN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12838,Roads,Completed,ND-TONDIARPET,34,680000,"RAISING AND FORMING THE NEW ROAD AT VADHATHAMURUGAPPAN 2nd STREET AND 1st CROSS STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12842,Roads,Completed,ND-TONDIARPET,34,900000,"RAISING AND FORMING THE NEW ROAD AT THIRUTHANGAL NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/12843,Roads,Completed,ND-TONDIARPET,34,740000,"RAISING AND FORMING THE NEW ROAD AT THIRUTHANGAL NAGAR 1st STREET AND R.V NAGAR 3rd STREET 1st CROSS STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/12866,Roads,Completed,ND-TONDIARPET,47,838000,"PROVIDING PORTABLE TOILETS 4 NOS WITH WATER TANK 2000lt ON RENTAL BASIS AND MAINTANANCE FOR ONE YEAR AT CB ROAD UNDER FLY OVER IN DN-47,U-11,Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12914,Roads,Completed,ND-TONDIARPET,41,940000,"Relaying of Cement Concrete Road @Aziz Nagar 1st Street in Dn-41,U-10,Z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/12930,Roads,Completed,ND-TONDIARPET,41,500000,"Relaying of Cement Concrete Road @ Adiparasakthi Street in Mooppanar Nagar in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12937,Roads,Completed,ND-TONDIARPET,41,988000,"Relaying of Cement Concrete Road @ C.P Cittarasu Street Anna Nagar in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12958,Roads,Completed,ND-TONDIARPET,41,993000,"Relaying of Cement Concrete Road @Gandhi Street mooppanar Nagar in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12960,Roads,Completed,ND-TONDIARPET,41,580000,"Relaying Of Cement Concrete Roads@Vela nagar 3rd street Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12961,Roads,Completed,ND-TONDIARPET,41,966000,"Relaying of Cement Concrete Road @ J.J Nagar,B Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12962,Roads,Completed,ND-TONDIARPET,43,995000,"Foming Pathway Inside of Christian Burial Ground ( North Side) in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12963,Roads,Completed,ND-TONDIARPET,41,970000,"Relaying Of Cement Concrete Roads@Vela nagar 2rd street Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12964,Roads,Completed,ND-TONDIARPET,41,992000,"Relaying Of Cement Concrete Roads@Vela nagar 1st street Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12965,Roads,Completed,ND-TONDIARPET,43,999000,"Foming Pathway Inside of Christian Burial Ground ( South Side) in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12970,Roads,Completed,ND-TONDIARPET,41,310000,"Relaying Of Cement Concrete Roads@Thiruvallur nagar, 5TH Street Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12971,Roads,Completed,ND-TONDIARPET,41,966000,"Relaying of Cement Concrete Road @ J.J Nagar, C Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12972,Roads,Completed,ND-TONDIARPET,41,298000,"Relaying of Cement Concrete Road @ J.J Nagar, C1 Block 1st Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12974,Roads,Completed,ND-TONDIARPET,41,298000,"Relaying of Cement Concrete Road @ J.J Nagar, C1 Block 2nd Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12976,Roads,Completed,ND-TONDIARPET,41,298000,"Relaying of Cement Concrete Road @ J.J Nagar, C1 Block 4th Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12977,Roads,Completed,ND-TONDIARPET,41,989000,"Relaying Of Cement Concrete Roads@Thiruvallur nagar, 4TH Street Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12978,Roads,Completed,ND-TONDIARPET,41,298000,"Relaying of Cement Concrete Road @ J.J Nagar, C10 Block 1st Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12979,Roads,Completed,ND-TONDIARPET,41,298000,"Relaying of Cement Concrete Road @ J.J Nagar, C10 Block 2nd Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12981,Roads,Completed,ND-TONDIARPET,41,298000,"Relaying of Cement Concrete Road @ J.J Nagar, C10 Block 3rd Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12982,Roads,Completed,ND-TONDIARPET,41,100000,"Relaying of Cement Concrete Road @ J.J Nagar, C10 Block 4th Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12983,Roads,Completed,ND-TONDIARPET,41,998000,"Relaying Of Cement Concrete Roads@Thiruvallur nagar,2TH Street Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12985,Roads,Completed,ND-TONDIARPET,41,995000,"Relaying Of Cement Concrete Roads@Sasthri street mooppanar nagar Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12986,Roads,Completed,ND-TONDIARPET,41,100000,"Relaying of Cement Concrete Road @ J.J Nagar, C10 Block 6th Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12987,Roads,Completed,ND-TONDIARPET,41,100000,"Relaying of Cement Concrete Road @ J.J Nagar, C10 Block 7th Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12988,Roads,Completed,ND-TONDIARPET,41,997000,"Relaying the CC Roads @ J.J Nagar, d Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12990,Roads,Completed,ND-TONDIARPET,41,990000,"Relaying Of Cement Concrete Roads@Sanjai gandhi street mooppanar nagar Dn-41, U-10, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/12991,Roads,Completed,ND-TONDIARPET,41,398000,"Relaying of Cement Concrete Road @ J.J Nagar, C11 Block 2nd Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12996,Roads,Completed,ND-TONDIARPET,41,600000,"Relaying the CC Roads @ J.J Nagar,G Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/12999,Roads,Completed,ND-TONDIARPET,41,623000,"Relaying the CC Roads @ J.J Nagar, H Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13000,Roads,Completed,ND-TONDIARPET,41,519000,"Relaying of Cement Concrete Road @ J.J Nagar, C12 Block 5th Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13001,Roads,Completed,ND-TONDIARPET,41,714000,"Relaying the CC Roads @ J.J Nagar, I Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13003,Roads,Completed,ND-TONDIARPET,41,660000,"Relaying the CC Roads @ J.J Nagar, J Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13004,Roads,Completed,ND-TONDIARPET,41,309000,"Relaying of Cement Concrete Road @ J.J Nagar, C12 Block 7th Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13005,Roads,Completed,ND-TONDIARPET,41,710000,"Relaying the CC Roads @ J.J Nagar, K Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13006,Roads,Completed,ND-TONDIARPET,41,560000,"Relaying the CC Roads @ J.J Nagar, I Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13007,Roads,Completed,ND-TONDIARPET,41,298000,"Relaying of Cement Concrete Road @ J.J Nagar, C2 Block 1st Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13012,Roads,Completed,ND-TONDIARPET,41,320000,"Relaying of Cement Concrete Road @ J.J Nagar, C2 Block 4th Street in Dn-41,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13014,Roads,Completed,ND-TONDIARPET,41,990000,"Relaying the CC Roads @Kamaraj Street mooppanar nagar in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2017-18 ND/2015-16/13019,Roads,Completed,ND-TONDIARPET,41,322000,"Relaying the CC Roads @J.J nagar,c4 block 1st Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13021,Roads,Completed,ND-TONDIARPET,41,322000,"Relaying the CC Roads @J.J nagar,c4 block 3rd Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13024,Roads,Completed,ND-TONDIARPET,41,322000,"Relaying the CC Roads @J.J nagar,c5 block 2ND Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13025,Roads,Completed,ND-TONDIARPET,41,220000,"Relaying the CC Roads @J.J nagar,c5 block 3rd Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13030,Roads,Completed,ND-TONDIARPET,41,488000,"Relaying the CC Roads @J.J nagar,c7 block 1th Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13031,Roads,Completed,ND-TONDIARPET,41,216000,"Relaying the CC Roads @J.J nagar,c7 block 2ND Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13032,Roads,Completed,ND-TONDIARPET,41,348000,"Relaying the CC Roads @J.J nagar,c8 block 1st Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13033,Roads,Completed,ND-TONDIARPET,41,368020,"Relaying the CC Roads @J.J nagar,c8 block 2nd Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13034,Roads,Completed,ND-TONDIARPET,41,322000,"Relaying the CC Roads @J.J nagar,c9 block 1st Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13037,Roads,Completed,ND-TONDIARPET,41,209000,"Relaying the CC Roads @J.J nagar,c6 block 1st Street in Dn-41,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13078,Buildings,Completed,ND-TONDIARPET,39,720000,"Improvement to H.M. ROOM at T.H. ROAD School in dn 39, u-10, zone 4.",Own Sources,4,2015-16,2016-17 ND/2015-16/13107,Buildings,Completed,ND-TONDIARPET,39,626000,"Improvement to 16th day Ceremony hall in dn 39,U-10, zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/13121,Buildings,Completed,ND-TONDIARPET,38,418000,"Improvements to Anganwadi Center No 12087,12088,12089 at Netaji Nagar 6th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/13135,Buildings,Completed,ND-TONDIARPET,41,960000,"IMPROVEMENTS TO DISPENSARY BUILDING AT SIVAJI NAGAR AMMAN KOIL STREET IN DN-41 , UNIT-10 AND ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/13152,Roads,Completed,ND-TONDIARPET,47,978000,"LAYING OF CEMENT CONCRETE PATCH WORK ATVARIOUS STREET IN DN- 47,UNIT- 11 ZONE- 4",Own Sources,4,2015-16,2016-17 ND/2015-16/13162,Storm Water Drain,Completed,ND-TONDIARPET,40,923000,"IMPROVEMENTS TO SWD AT KAMARAJAR SALAI,A.E KOIL STREET,T.H ROAD,JEEVA NAGAR MAIN ROAD,CORPORATION COLONY IN DN-40,U-10,Z-IV",Own Sources,4,2015-16,2016-17 ND/2015-16/13166,Storm Water Drain,Completed,ND-TONDIARPET,35,810000,"Rising storm water drain at Cauvery Salai 6th street to Canal in Division 35, unit 9, zone 4.",Own Sources,4,2015-16,2016-17 ND/2015-16/13172,Storm Water Drain,Completed,ND-TONDIARPET,35,670000,"raising the storm water drain at south Avenue Road (from mosque to canal) in Division 35, unit 9, zone 4.",Own Sources,4,2015-16,2016-17 ND/2015-16/13175,Buildings,Completed,ND-TONDIARPET,39,990000,"Improvement to Division Office Building at Cheriyan Nagar in dn 39,U-10, zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/13194,Buildings,Completed,ND-TONDIARPET,41,983000,"improvements to amma vunavagam-1 and health building at ANNAI SATHYA NAGAR in dn-41, unit-10 and zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/13201,Buildings,Completed,ND-TONDIARPET,41,950000,"PROVIDING COLOUR IRON SHEET ROOF FOR CHAPATHI CENTRE AT AMMA VUNAVAGAM-2 AT J.J NAGAR IN DN-41, UNIT-10 AND ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/13204,Buildings,Completed,ND-TONDIARPET,40,993000,"Construction Sump and Kitchen shed for inside the NNMP Shed (cente.no-0412 & 0411) at V.O.C Nagar in Dn-40,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13205,Parks,Completed,ND-TONDIARPET,41,992000,"IMPROVEMENTS TO PARK AT MGR NAGAR 5TH STREET IN DN-41,UNIT-10 AND ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/13206,Buildings,Completed,ND-TONDIARPET,41,981000,"IMPROVEMENTS TO BRIDGE ACROSS LINK CANAL AT MANALI SALAI IN DN-41, UNIT-10 AND ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/13280,Roads,Completed,ND-TONDIARPET,47,910000,"Constinon of Sigle Compactor Bins Plotform at various Place in DN - 47, unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/13414,Roads,Completed,ND-TONDIARPET,36,1600000,"Relaying of BT Course By Paver At Bharathiyar Street in DN-36, U-09, Z-04",MLACDS,4,2015-16,2016-17 ND/2015-16/13416,Roads,Completed,ND-TONDIARPET,36,1490000,"Relaying of BT Course By Paver At Bharathiyar Street Extension in DN-36, U-09, Z-04",MLACDS,4,2015-16,2016-17 ND/2015-16/13417,Roads,Completed,ND-TONDIARPET,36,420000,"Relaying of BT Course By Paver At Bharathidhasan 1st Street in DN-36, U-09, Z-04",MLACDS,4,2015-16,2016-17 ND/2015-16/13422,Buildings,Completed,ND-TONDIARPET,42,995000,"PROVIDING E SEVA ROOM AND SUMP FOR UNIT OFFICE - 10 CAMPUS AT RATHNA SABAPATHI STREET IN DN-42, UNIT-10, ZONE-04",Own Sources,4,2015-16,2017-18 ND/2015-16/13423,Buildings,Completed,ND-TONDIARPET,42,981000,"Providing RWH at Kailasam Street, TH Road 4th Lane, and 540 TH Road School in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13424,Roads,Completed,ND-TONDIARPET,42,921000,"IMPROVEMENTS TO FOOT PATH AT T.H ROAD IN DN-42,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/13425,Buildings,Completed,ND-TONDIARPET,42,720000,"Improvements to Existing centermedian at T.H road in Dn-42,u-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13876,Road Cut,Completed,ND-TONDIARPET,38,980000,"Attending Patch works at Ellaya Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/13981,Playfields,Completed,ND-TONDIARPET,40,989000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAILS AND L.E.D LIGHT ARRANGEMENTS TO CHILDRENS PLAY FIELD AT THIRUVALLUVAR NAGAR IN DN-40,UNIT-10,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/13983,Playfields,Completed,ND-TONDIARPET,37,962000,"Improvements to Park and Play field at Golden Complex 1st Sector in Div - 37, Unit - 9, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/13999,Parks,Completed,ND-TONDIARPET,38,998000,"Removal of excess earth and Levelling for filling earth at Nehru nagar park in DN.38,Unit.9,Zone.4",Own Sources,4,2015-16,2016-17 ND/2015-16/14003,Buildings,Completed,ND-TONDIARPET,35,500000,"IMPROVEMENTS TO AMMA UNVAGAM PHASE-1 ,6TH MAIN ROAD ,MUTHAMIL NAGAR, DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/14005,Parks,Completed,ND-TONDIARPET,38,994000,"Raising the Surface Level and Filling with good earth at Nehru Nagar Park in Dn.38,Unit.9,Zone.4",Own Sources,4,2015-16,2016-17 ND/2015-16/14006,Buildings,Completed,ND-TONDIARPET,35,950000,"IMPROVEMNTS TO DIVISION OFFICE-35 AT KRISHNAMORTHY SALAI ,UNIT-9, ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/14008,Buildings,Completed,ND-TONDIARPET,36,850000,"Improvements to NNMP Shed at SA Clony 8th Street and Gandhi Nagar 7th Street in Div - 36, Unit - 9, Zone - 4",Own Sources,4,2015-16,2017-18 ND/2015-16/14013,Parks,Completed,ND-TONDIARPET,38,902000,"Filling of Good earth (South side corner) at Nehru nagar park in Dn.38,Unit.9,Zone.4",Own Sources,4,2015-16,2016-17 ND/2015-16/14022,Parks,Completed,P-Parks and Playfields,38,999000,"Suppling and Fixing Stainless Steel Hand rails (North side) at Nehru nagar park in Dn.38, Unit.9,Zone.4",Own Sources,4,2015-16,2018-19 ND/2015-16/14029,Buildings,Completed,ND-TONDIARPET,34,300000,"CONSTRUCTION OF DISABLE FRINDLY TOILET AT MANALI SALAI ,SEETHARAM NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/14030,Parks,Completed,P-Parks and Playfields,38,981000,"Suppling and Fixing Stainless steel Hand rails(East and West side) at Nehru nagar park in Dn.38, Unit.9,Zone.9",Own Sources,4,2015-16,2018-19 ND/2015-16/14196,Playfields,Completed,ND-TONDIARPET,40,820000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAILS ,STAINLESS STEEL PLAY APPARATUS TO CHILDREN'S PLAY FIELD AT THIRUVALLUVAR NAGAR IN DN-40, UNIT-10, ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/14232,Parks,Completed,ND-TONDIARPET,46,922000,"IMPROVEMENTS TO CHILDRENS PARK AT S.M.NAGAR MAIN ROAD IN DN-46,UNIT-11,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/14247,Parks,Completed,ND-TONDIARPET,40,885000,"MAINTENANCE OF THANTHAI PERIYAR PARK IN DN-40, U-10, Z-4 (1YEAR)",Own Sources,4,2015-16,2016-17 ND/2015-16/14250,Parks,Completed,ND-TONDIARPET,40,224000,"MAINTENANCE OF THE CROSS ROAD PARK (PRINDHAVANAM)PARKIN DN-40, U-10,Z-4. (1YEAR)",Own Sources,4,2015-16,2016-17 ND/2015-16/14252,Parks,Completed,ND-TONDIARPET,41,425000,"MAINTENANCE OF M.G.R.NAGAR PARK IN DN-4I, U-10, Z-4 (1YEAR)",Own Sources,4,2015-16,2016-17 ND/2015-16/14254,Parks,Completed,ND-TONDIARPET,42,332000,"MAINTENANCE OF R.K.NAGAR, M.L.A. OFFICE PARK AT RETTAI KZHIL STREET IN DN-42, U-10, Z-4 (1YEAR)",Own Sources,4,2015-16,2016-17 ND/2015-16/14255,Parks,Completed,ND-TONDIARPET,42,457000,"MAINTENANCE OF JEEVA PARK @ T.H.ROAD IN DN-42, U-10, Z-4 (1YEAR)",Own Sources,4,2015-16,2016-17 ND/2015-16/14256,Parks,Completed,ND-TONDIARPET,42,333000,"MAINTENANCE OF SIR THIYAGARAJA PARK @ T.H. ROAD IN DN-42, U-10, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/14282,Roads,Completed,ND-TONDIARPET,38,950000,"Attending Patch work at Nehru Nagar Main Road, Nehru Nagar 12th Street, Nehru Nagar 2nd Street, Sanjay Gandhi Nagar Main Road in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/14307,Roads,Completed,ND-TONDIARPET,41,910000,"PROVIDING AND FIXING STREET NAME BOARD AT VELAN NAGAR 1ST TO 3RD STREET,KUMARAN NAGAR 1ST TO 5TH STREET IN DN-41 ,UNIT-10 AND ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/14376,Roads,Completed,ND-TONDIARPET,45,572000,"ATTENDING BT PATCH WORK IN VARIOUS ROADS AND STREET IN DN-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/14786,Buildings,Completed,ND-TONDIARPET,43,497000,"Providing and Fixing RO plant at CMS Pudumanaikuppam Main street in Div-43, Ut-10, Zn-4",Own Sources,4,2015-16,2016-17 ND/2015-16/14795,Buildings,Completed,ND-TONDIARPET,43,497000,"Providing and Fixing RO plant at CMS Vinayagapuram street in Div 43, Ut 10, Zn-4",Own Sources,4,2015-16,2016-17 ND/2015-16/14796,Buildings,Completed,ND-TONDIARPET,43,550000,"Providing and Fixing RO plant at CMS Kummallamman Kovil street in Div 43, Ut-10, Zn-4",Own Sources,4,2015-16,2016-17 ND/2015-16/14799,Buildings,Completed,ND-TONDIARPET,43,837000,"Providing and Fixing RO plant inside Dhobhikhana at CDH in Div 43, Ut10, Zn4",Own Sources,4,2015-16,2016-17 ND/2015-16/15294,Roads,Completed,ND-TONDIARPET,46,270000,"Writing name boards for conservancy particulars at various streets Dn-46,Unit-11,Z-05.",Own Sources,4,2015-16,2017-18 ND/2015-16/15891,Buildings,Completed,ND-TONDIARPET,34,975000,"PAINTING AND WRITING LETTERS TO TRI CYCLE AND COMPACTOR BIN IN DN-34 TO 37,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/16061,Buildings,Completed,ND-TONDIARPET,47,760000,"Repairs and Improvements to Division Office 47 at JJ Nagar in Dn -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2018-19 ND/2015-16/16064,Storm Water Drain,Completed,ND-TONDIARPET,47,569000,"PROVIDING GRATING ARRANGEMENTS TOS W D AT THAYAGAPPA ST ,EGAPPAN ST ,C B ROAD,KANNAN ST, K H ROAD PITTYMUSAMY STAND KAMARAJ NAGAR IN DN -47, UNIT -11 ,ZONE - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/16321,Parks,Completed,ND-TONDIARPET,37,999000,"Providing Greenary Arrangements and Improvements to Park at M.K.B Nagar 13th East Cross Street in Dn-37, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/16349,Electrical,Completed,ND-TONDIARPET,37,995000,"Electrification of school building and provision of Tube light, Fan,Plug point Etc in Chennai Middle and primary school at RR Nagar, KKD Nagar, Udayasuruyan Nagar Division 37, Unit-09, Zone IV",Own Sources,4,2015-16,2018-19 ND/2015-16/16351,Electrical,Completed,ND-TONDIARPET,46,967000,"Electrification of school Building and provision of Tube Light, Fan,Plug point etc in Chennai High Sec school Block 1 &2 at Moothingar Road, Division 46, Unit - 11, Zone IV",Own Sources,4,2015-16,2018-19 ND/2015-16/16353,Electrical,Completed,ND-TONDIARPET,46,825000,"Electrification of school Building and provision of Tube Light, Fan,Plug point etc in Chennai Higher Sec school Block 1 &2 at C Kalyanapuram at Division 46, Unit - 11, Zone IV",Own Sources,4,2015-16,2018-19 ND/2015-16/16378,Roads,Completed,ND-TONDIARPET,42,510000,"Realying of CC Road @Mayor Basudev 1st Street in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/16387,Buildings,Completed,ND-TONDIARPET,36,520000,Newly Construction of Children Play Space At S.A Colony 2nd Street in DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/16388,Buildings,Completed,ND-TONDIARPET,36,350000,Newly Construction of Children Play Space At S.A Colony 6th Street in DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/16487,Playfields,Completed,ND-TONDIARPET,35,950000,"IMPROVEMENTS TO CHILDREN PLAY SPACE AT 3RD MAIN ROAD , MUTHAMIL NAGAR IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/16489,Buildings,Completed,ND-TONDIARPET,35,600000,"IMPROVEMENTS TO ANGANWADI CENTER NO.12071 AT 3RD MAIN ROAD , MUTHAMIL NAGAR IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/1654,Buildings,Completed,ND-TONDIARPET,44,2000000,"CONSTRUCTION OF ANGANWADI OFFICE BUILDING(FRIST FLOOR) AT ANBAZHAGAN STREET UNDER PERAMBUR MLA SCHEME IN DIV -44, UNIT-11, ZONE-4.",MLACDS,4,2015-16,2016-17 ND/2015-16/16624,Buildings,Completed,ND-TONDIARPET,35,980000,"IMPROVMENTS TO CHENNAI CORPORATION MIDDLE SCHOOL AT CHINNADI MADAM T.H. ROAD IN DN 35,UNIT- 9,ZONE 4",Own Sources,4,2015-16,2017-18 ND/2015-16/16627,Storm Water Drain,Completed,ND-TONDIARPET,36,285000,"Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on Various Location in Division-36, Unit-09, Zone-04",Own Sources,4,2015-16,2018-19 ND/2015-16/16730,Roads,Completed,ND-TONDIARPET,45,490000,"SWD INTER CONNECTION WORK BETWEEN MPM STREET AND B.B.ROAD IN DN -45, UNIT -11, ZONE -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/16756,Parks,Completed,ND-TONDIARPET,37,999000,"Providing Greenary and Water Supply Arrangements to Park and Play Field at Golden Complex 1st Sector in Div-37, Unit - 9, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/16797,Storm Water Drain,Completed,ND-TONDIARPET,35,970000,"DESILTING OF KODUNGAIYUR CANAL FROM NORTH AVENUE ROAD TO TH ROAD IN DN-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/16799,Storm Water Drain,Completed,ND-TONDIARPET,35,980000,"DESILTING OF KODUNGAIYUR CANAL FROM KAMARAJ SALAI TO MUTHAMIL NAGAR NORTH AVENUE IN DN-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/16939,Buildings,Completed,ND-TONDIARPET,42,925000,"ADDITIONAL IMPROVEMENTS TO A.D ELECTRICAL OFFICE AT T.H ROAD IN DN-42, UNIT-10, ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/17162,Buildings,Completed,ND-TONDIARPET,38,983000,PROVIDING RAIN WATER HARVESTING AT VARIOUS STREETS IN DIV-38 UNIT-09 ZONE-4,Own Sources,4,2015-16,2017-18 ND/2015-16/17233,Buildings,Completed,ND-TONDIARPET,43,987000,"CONSTRUCTION OF COMPOUND WALL AND URGENT TOILET BLOCK REPAIRS WORKS TO ELECTRICAL JE OFFICE BUILDING AT CDH IN DIV-43,UNIT-10,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/17391,Buildings,Completed,ND-TONDIARPET,43,981000,PROVIDING RAIN WATER HARVESTING IN KANAKA PILLAI STREETS AT DIV -43 UNIT-10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/17393,Buildings,Completed,ND-TONDIARPET,43,981000,PROVINDING RAIN WATER HARVESTING AT VARATHA RAJA PERUMAL KOIL STREETS IN DIV -43 UNIT-10 ZONE -4,Own Sources,4,2015-16,2016-17 ND/2015-16/17394,Buildings,Completed,ND-TONDIARPET,43,981000,"PROVINDING RAIN WATER HARVESTING AT S.N CHETTY ROAD ,SINGARAVELAN NAGAR,PUDHUMANAI KUPPAM IN DIV-43 UNIT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/17395,Buildings,Completed,ND-TONDIARPET,43,981000,"PROVDING RAINWATER HARVESTING AT AMARANJI PURAM,JEEVARATHINAM SALAI,THANDAVARAYAN STREET IN DIV -43 UNIT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/17414,Buildings,Completed,ND-TONDIARPET,42,981000,"PROVIDING RAIN WATER HARVESTING AT CHELLAPPA STREET, TH ROAD, SENIAMMAN KOIL STREET AND NNMP SHEDS(RETTAIKUZHI STREETS) IN DIV-42 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/17417,Buildings,Completed,ND-TONDIARPET,42,981000,PROVIDING RAIN WATER HARVESTING AT RATHNA SABAPATHI STREETS AND M.C.M. GARDEN STREETS IN DIV-42 UNIT-10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/17418,Buildings,Completed,ND-TONDIARPET,40,981000,PROVDING RAIN WATER HARVESTING AT V.O.C.NAGAR AND MADHA KOIL STREETS IN DIV -40 UNIT-10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/17419,Buildings,Completed,ND-TONDIARPET,40,981000,PROVDING RAIN WATER HARVESTING AT CROSS ROAD AND KAMARAJ SALAI IN DIV -40 UNIT-10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/17613,Buildings,Completed,ND-TONDIARPET,39,998000,"Improvements to cps in Cheriyan Nagar in Div-39,Un-10,Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/17640,Buildings,Completed,ND-TONDIARPET,43,856000,"Construction of Toilet Block in CMS at Kummalamman Koil Street Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/17681,Buildings,Completed,ND-TONDIARPET,43,615000,"Construction of Dinning Hall and Improvements to HM Room in CMS at Kummalamman Koil Street In DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/17959,Parks,Completed,ND-TONDIARPET,45,977000,"Improvements to O.P. lane Park in Dn-45, Unit-11, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/17960,Roads,Completed,ND-TONDIARPET,45,990000,"PROVIDING STREET NAME BOARD TO B.V COLONY 19,20,21ST STREETS, BALAMURUGAN STREET, DESIGANAND PURAM FIRST, SECOND AND POWER LANE STREETS, SUNDRAM LANES, SUNDARAM STREETS AND VARIOUE STREET IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/17962,Roads,Completed,ND-TONDIARPET,45,990000,"providing wet-mix macadam to flood affected roads (Sundaram 1st street, Appu Street, Sundaram 6th street, Balakrishan Street, Sanjay Nagar, Stephenson Road, A.A.Road, B.B.19th Street, Mayor Krishnamurthy main road, Desiga nandhapura 1st Street, Desiga nandhapura 2nd Street in dn-45,unit-11,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/17963,Roads,Completed,ND-TONDIARPET,45,998000,"CONSTRUCTION OF SANITARY COMPLEX TO ZONE-4 LORRY STATION IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/17992,Buildings,Completed,ND-TONDIARPET,42,658000,IMPROVEMENTS TO PUBLIC CONVENIENCE KAILSHAM STREET IN DIV-42 UNIT-10 ZONE -4,Own Sources,4,2015-16,2017-18 ND/2015-16/17998,Buildings,Completed,ND-TONDIARPET,47,860000,"Repairs and Improvements to Harinarayanapuram (CPS) School in DN -47,Unit -11,Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/18000,Buildings,Completed,ND-TONDIARPET,47,560000,"Improvements and Providing water supply Arrangements to Harinarayanapuram (CPS) School in DN -47,Unit -11,Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/18009,Parks,Completed,ND-TONDIARPET,47,999000,"FORMATION OF NEW PRAK AT BHARATHI NAGAR HOUSING BOARD IN DIV -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/18012,Parks,Completed,ND-TONDIARPET,47,950000,"Improment and Greenarly Arrangements New Park at Bharthi Nagar Housing Board In IN DIV -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/18052,Buildings,Completed,ND-TONDIARPET,47,976000,"Improvements and Providing water Supply Arragements Drianage Arregements and RO Plant @ Meenambal Nagar 1st Street (CPS) School in DN -47,Unit -11, Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/18098,Parks,Completed,ND-TONDIARPET,38,999002,"Supplying and Fixing Stainless Steel Hand Rails to Ellaya Street Park in Dn-38, Unit-9, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18125,Storm Water Drain,Completed,ND-TONDIARPET,42,980000,IMPROVEMENT TO STORM WATER DRAIN KAILASHAM STREET( CH O TO 190) METER IN DIV -42 UNIT -10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/18130,Storm Water Drain,Completed,ND-TONDIARPET,42,823000,DISMANTLING AND IMPROVEMENTS TO STORM WATER DRAIN KAILASHAM STREET IN DIV -42 UNIT-10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/18136,Buildings,Completed,ND-TONDIARPET,43,995000,"Improvements to Existing Toilet Block in CMS at Kummalamman Koil Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/18143,Buildings,Completed,ND-TONDIARPET,40,721000,PROVIDING RAIN WATER HARVESTING IN VAITHIYANATHAN STREET IN DIV -40 UNIT-10 ZONE-4,Own Sources,4,2015-16,2017-18 ND/2015-16/18145,Buildings,Completed,ND-TONDIARPET,43,996000,"Improvement to the Pudumanaikuppam CMS (South Block) in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/18179,Parks,Completed,ND-TONDIARPET,40,810000,"Providing Elevation Work and Lighting Arrangements in Periyar Park at A.E. Koil Street in DN-40, Unit-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/18180,Parks,Completed,ND-TONDIARPET,40,480000,"Provinding Stainless Steel Handrails Work in Periyar Park at A.E.Koil Street in Dn-40, Unit-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/18183,Parks,Completed,ND-TONDIARPET,40,993000,"Providing Toilet Facilities and Other Improvement Works in Periyar Park at A.E.Koil Street in DN-40, UNIT-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/18184,Parks,Completed,ND-TONDIARPET,40,930000,"Providing Water Supply Arrangaements and Other Ornamental Works in Periyar Park at A.E.Koil Street in DN-40, UNIT-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/18207,Buildings,Completed,ND-TONDIARPET,42,999000,"Improvements to the ICDS at T.H Road in Dn-42,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/18208,Buildings,Completed,ND-TONDIARPET,43,987000,"Construction of Multipurpose Hall at Jeevarathinam Salai in DN-43,U-10,Z-04(Counsilor Fund)",Own Sources,4,2015-16,2016-17 ND/2015-16/18278,Buildings,Completed,ND-TONDIARPET,39,995000,"Proposed Construction of Gym Building at A.E Koil Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/18292,Parks,Completed,ND-TONDIARPET,43,770000,"ANNUAL MAINTENANCE OF PARK AT CD HOSPITAL PARK ,OPP MAIN BUILDING PARK FOR TWO YEARS IN DIV-43,UNIT-10,Z-4 ( BY EMPLOYED QUALIFIED DIPLAMO IN HORTICULTURIST ONLY)",Own Sources,4,2015-16,2019-20 ND/2015-16/18293,Parks,Completed,ND-TONDIARPET,43,700000,"Annual Maintenance to the Park at Sooriya narayanan street for two years in Division 43,Unit 10,Zone 4.( BY EMPLOYED QUALIFIED DIPLAMO IN HORTICULTURIST ONLY)",Own Sources,4,2015-16,2019-20 ND/2015-16/18294,Parks,Completed,ND-TONDIARPET,43,780000,"Annual maintenance Park at Kasi medu Burial Ground Park,Suriya narayana Street Park at Div-43, Unit-10,ZO-4( BY EMPLOYED QUALIFIED DIPLAMO IN HORTICULTURIST ONLY)",Own Sources,4,2015-16,2019-20 ND/2015-16/18295,Parks,Completed,ND-TONDIARPET,43,780000,"PROVIDING SECURITY ARRANGEMENTS TO PARK AT CD HOSPITAL PARK TWO YEARS IN DIV-43,UNIT-10,Z-4",Own Sources,4,2015-16,2019-20 ND/2015-16/18296,Parks,Completed,ND-TONDIARPET,38,930000,"Annual Maintenance to Park at Patel Nagar in two years in Dn.38,Unit-9,Zone-4.( BY EMPLOYED QUALIFIED IN HORTICULTURIST ONLY)",Own Sources,4,2015-16,2019-20 ND/2015-16/18306,Parks,Completed,ND-TONDIARPET,38,795000,"Annual maintenance of Park (OSR Land) at Ellaya Street in Dn.38,Unit-9,Zone-4.( BY EMPLOYED QUALIFIED DIPLAMO IN HORTICULTURIST ONLY)",Own Sources,4,2015-16,2019-20 ND/2015-16/18342,Buildings,Completed,ND-TONDIARPET,39,988000,"Construction of Dinning Hall 1 In Chennai Primary School near Toilet Block at S.N.Chetty Street in Dn-39,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/18351,Buildings,Completed,ND-TONDIARPET,39,997000,"Improvements to Chennai Primary School in Toilet Block at S.N.Chetty Road in Dn-39,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/18402,Storm Water Drain,Completed,ND-TONDIARPET,42,856000,LAYING HUME PIPE AT SENNIAMMAN KOIL STREET DIV-42 UNIT-10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/18561,Buildings,Completed,ND-TONDIARPET,39,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI HIGHER SECONDARY SCHOOL FOR GROUND FLOORS (NORTHERN SIDE BLOCK AND EASTERN SIDE BOCK) AT 731 TH ROAD IN DIV-39,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18563,Buildings,Completed,ND-TONDIARPET,39,950000,"PROVIDING AND FIXING RO PLANT TO CHENNAI MIDDLE SCHOOL FOR GROUDFLOOR,FIRST FLOOR &SECOND FLOOR(ANNEXURE BLOCK) AT 731 TH ROAD IN DIV-39,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18564,Buildings,Completed,ND-TONDIARPET,39,950000,"PROVIDING AND FIXING RO PLANT TO CHENNAI PRIMARY SCHOOL FOR GROUND FLOOR,FIRST FLOOR &SECOND FLOOR(OPP TO ANNEXURE BLOCK) AT 731 TH ROAD IN DIV-39,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18565,Buildings,Completed,ND-TONDIARPET,39,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI MIDDLE URDHU SCHOOL AT CERIYAN NAGAR IN DIV-39,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18566,Buildings,Completed,ND-TONDIARPET,39,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI PRIMARY SCHOOL FOR GROUND FLOOR &FIRST FLOOR AT CHERIYAN NAGAR IN DIV-39,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18567,Buildings,Completed,ND-TONDIARPET,39,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI HIGH SCHOOL AT CHERIYAN NAGAR IN DIV-39,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18568,Buildings,Completed,ND-TONDIARPET,39,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI PRIMARY SCHOOL AT IRUSAPPA STREET IN DIV-39,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18569,Buildings,Completed,ND-TONDIARPET,42,950000,"PROVIDING AND FIXING RO PLANT TO CHENNAI HIGHER SECONDARY SCHOOL(SOUTHERN SIDE BLOCK) AT 540 TH ROAD IN DIV-42,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18570,Buildings,Completed,ND-TONDIARPET,42,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI HIGH SCHOOL(NORTHERN SIDE BLOCK) AT 540 TH ROAD IN DIV-42,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18571,Buildings,Completed,ND-TONDIARPET,42,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI HIGHER SECONDARY SCHOOL FOR LAB BUILDING AT 540 TH ROAD IN DIV-42,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18572,Buildings,Completed,ND-TONDIARPET,42,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI MIDDLE SCHOOL AT SENI AMMAN KOIL STREET IN DIV-42,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18575,Buildings,Completed,ND-TONDIARPET,40,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI MIDDLE SCHOOL AT KAMARAJAR SALAI IN DIV-40UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18576,Buildings,Completed,ND-TONDIARPET,40,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI PRIMARY SCHOOL) AT THIRUVALLUVAR NAGAR IN DIV-40,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18577,Buildings,Completed,ND-TONDIARPET,41,950000,"PROVIDING AND FIXING RO PLANT TO CHENNAI MIDDLE SCHOOL) AT CORNATION NAGAR IN DIV-41,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18578,Buildings,Completed,ND-TONDIARPET,41,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI PRIMARY SCHOOL) AT ANNA NAGAR IN DIV-41,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18579,Buildings,Completed,ND-TONDIARPET,41,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI PRIMARY SCHOOL) AT JJ NAGAR IN DIV-41,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18580,Buildings,Completed,ND-TONDIARPET,41,475000,"PROVIDING AND FIXING RO PLANT TO CHENNAI PRIMARY SCHOOL) AT MGR NAGAR IN DIV-41,UNIT-10,ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/18590,Buildings,Completed,ND-TONDIARPET,41,886000,"ADDITIONAL IMPROVEMENTS TO WARD OFFICE AND IMPROVEMENTS TO FOOTPATH AT JJ NAGAR A1 STREET IN DIV-41,UNIT-10,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18606,Buildings,Completed,ND-TONDIARPET,39,989000,"Construction of Dinning Hall 2 In Chennai Primary School in A Block at S.N.Chetty Street in Dn-39,Un-10,Zn-04",Own Sources,4,2015-16,2016-17 ND/2015-16/18618,Buildings,Completed,ND-TONDIARPET,42,994000,"IMPROVEMENT WORKS TO SCIENCE LAB BUILDING AT 540 TH ROAD IN DIV-42,UNIT-10,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18621,Buildings,Completed,ND-TONDIARPET,42,692000,"Providing Speaker amplifier arrangements&electrical arrangements to chennai higher secondary school at 540TH Road in div-42,unit=-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18659,Buildings,Completed,ND-TONDIARPET,40,981000,"PROVIDING RAIN WATER HARVESTING AT A.A THOTTAM ,TSUNAMI QURTERS,JEEVA NAGAR,VOC NAGAR MARKET ROAD, IN DIV-40 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18660,Buildings,Completed,ND-TONDIARPET,42,981000,"PROVIDING RAIN WATER HARVESTING AT THIRUVALLUVAR NAGAR,SENIAMMAN KOIL STREET,TANK STREET IN DIV-42 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18661,Buildings,Completed,ND-TONDIARPET,39,981000,"PROVIDING RAIN WATER HARVESTING AT AE KOIL STREET,QQ SCHEME ROAD, IRUSAPPA STREET IN DIV-39 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18662,Buildings,Completed,ND-TONDIARPET,39,981000,"PROVIDING RAIN WATER HARVESTING AT CHERIYAN NAGAR,ASHOK NAGAR,SN ROAD IN DIV-39 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18663,Buildings,Completed,ND-TONDIARPET,39,981000,"PROVIDING RAIN WATER HARVESTING AT TH ROAD, A.E KOIL STREET IN DIV-42 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18664,Buildings,Completed,ND-TONDIARPET,41,981000,"PROVIDING RAIN WATER HARVESTING AT MANALI SALAI,THIRUVALLUVAR NAGAR,LIME CLINN ROAD IN DIV-41 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18665,Buildings,Completed,ND-TONDIARPET,43,981000,"PROVIDING RAIN WATER HARVESTING AT KUMMALAMMAN KOIL ,VINAYAGAPURM,PUDHUMANAIKUPPAM SCHOOL BUILDING ,CDH OP BLOCK,CORPORATION BUILDINGS DIV-43 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18666,Buildings,Completed,ND-TONDIARPET,41,981000,"PROVIDING RAIN WATER HARVESTING JJ NAGAR,EZHIL NAGAR ,CORNATION NAGAR,KUMARAN NAGAR,SIVAJI NAGAR AT VARIOUS STREETS IN DIV-41 UNT-10 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18689,Buildings,Completed,ND-TONDIARPET,39,536000,"providing pressed tiles for leaky roof and laying cement concrete flooring for rearside of building at CPS cheriyan nagar in div-39,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18750,Roads,Completed,ND-TONDIARPET,45,976000,"providing wet-mix macadam to flood affected roads (B.V colony 12th to 15th street, B.V colony 20th,21th street sundaram streets, op lane, desigananthapuram, and balamurugan street) in dn-45,unit-11,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/18794,Buildings,Completed,ND-TONDIARPET,42,515000,CONSTRUCTION OF COMPOSIT YARD KAILASHAM STREET IN DIV-42 UNIT-10 ZONE-4,Own Sources,4,2015-16,2016-17 ND/2015-16/18937,Roads,Completed,ND-TONDIARPET,44,990000,"Estimate for Carrying out petty repairs (Day to Day) in Road Maintenance at various Street in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/18939,Storm Water Drain,Completed,ND-TONDIARPET,44,999000,"PROPOSED DAY TO DAY REPAIR (PETTY) WORK IN VARIOUS STORM WATER DRAIN IN DN-44, UNIR-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/19154,Storm Water Drain,Completed,ND-TONDIARPET,37,995000,"Demolition And Reconstruction of Storm Water Drain at Sathyamoorthy Nagar Main Road Junction of M.K.B.Nagar Central Avenue Road in Dn:37, U:9, Z:IV",Own Sources,4,2015-16,2016-17 ND/2015-16/19507,Storm Water Drain,Completed,ND-TONDIARPET,37,897000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT M.K.B.NAGAR WEST AVENUE SERVICE ROAD (EAST SIDE) FROM MEENAMBAL BRIDGE STARTING POINT TO CHAINAGE 50m IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/19512,Storm Water Drain,Completed,ND-TONDIARPET,37,897000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT M.K.B.NAGAR WEST AVENUE SERVICE ROAD (EAST SIDE) FROM CHAINAGE 50-100m IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/19535,Roads,Completed,ND-TONDIARPET,39,988000,"Raising the level to avoid water stagnation to rear side of Fisherman colony Tenements in div-39,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/19536,Buildings,Completed,ND-TONDIARPET,40,998000,"Improvements to Play field inside chennai primary school ground at Thiruvalluvar nagar in div-40,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/19542,Roads,Completed,ND-TONDIARPET,41,873000,"Raising the level to avoid water stagnation rear side of cornation nagar Tenements in div-41,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/19604,Storm Water Drain,Completed,ND-TONDIARPET,37,819000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT M.K.B.NAGAR WEST AVENUE SERVICE ROAD (EAST SIDE) FROM CHAINAGE 100m TO CANAL DISPOSAL IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/19607,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE O- 29m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19616,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 29-58m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/19630,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 58-87m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19633,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 87-116m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19635,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 116-145m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19653,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 145-174m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19680,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 174-203m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19682,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 203-232m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19685,Storm Water Drain,Completed,ND-TONDIARPET,36,998000,"DISMANTLING & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT S.A.COLONY FROM AMMAN KOIL STREET CHAINAGE 232-261m IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2019-20 ND/2015-16/1974,Buildings,Completed,ND-TONDIARPET,46,820000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS (DAY TO DAY) IN THE FOLLOWING SCHOOL, HOSPITAL, NNMP SHED & P.C IN DN-46, UNIT -11, ZONE -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/19858,Parks,Completed,ND-TONDIARPET,40,510000,"Annual Maintenance of Park at Ellaya Street Park (EMMAR Properties) for one year in Ward 40, Unit 10,Zone-4.(By qualified horticulturist only)",Own Sources,4,2015-16,2016-17 ND/2015-16/19859,Parks,Completed,ND-TONDIARPET,40,200000,"Providing Security arrangements to Thiruvalluvar nagar Park for one year in Ward 40, Unit 10,Zone-4.(By qualified horticulturist only)",Own Sources,4,2015-16,2017-18 ND/2015-16/19862,Parks,Completed,ND-TONDIARPET,40,200000,"Providing Security arrangements to Ellaya street Park (EMMAR PROP.) for two years in Ward 40, Unit 10,Zone-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/19866,Parks,Completed,ND-TONDIARPET,40,320000,"Annual Maintenance of Park at Thiruvalluvar nagar Park for one year in Ward 40, Unit 10,Zone-4.(By qualified horticulturist only)",Own Sources,4,2015-16,2016-17 ND/2015-16/20151,Storm Water Drain,Completed,ND-TONDIARPET,39,670000,"Improvement SWD at T.H road and North Terminus Road in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/20157,Roads,Completed,ND-TONDIARPET,39,593000,"Attending Cement Concrete Patches at A.A Scheme road and Irussappa Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/20160,Buildings,Completed,ND-TONDIARPET,41,999000,"Raising the Compoud wall and other improvement to CMS at Cornation nagar in Ward-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/20204,Buildings,Completed,ND-TONDIARPET,41,828000,"Improvement to Muti Purpose Hall at J.J Nagar Ward-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/20235,Roads,Completed,ND-TONDIARPET,43,997000,"Attending Patches at Pillayar Koil Street, Kannkar Street, Thandavarayan Street in Ward-43, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/20639,Parks,Completed,ND-TONDIARPET,46,995000,"Annual maintenance of Foot ball Ground ( operating of Mechanical sprinklers and Maintaining Grass and lawns and irrigation system ) at samandhypoocolony in Div-46,unit-11,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/20660,Storm Water Drain,Completed,ND-TONDIARPET,37,708000,"Laying Cement Concrete Road at Sathyamoorthy Nagar Main Road Junction of M.K.B.Nagar Central Avenue Road in Dn:37, U:9, Z:IV",Own Sources,4,2015-16,2016-17 ND/2015-16/20857,Roads,Completed,ND-TONDIARPET,48,651861,"Attending BT Patch work at Muthaiya Street in DN -48, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/20884,Roads,Completed,ND-TONDIARPET,37,654000,"FORMING ROAD AT ABIRABI AVENU AND SRINIVASAN STREET IN DN-37,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/20886,Roads,Completed,ND-TONDIARPET,41,1687985,"Attending B.T Patch work at Cornation nagar 3rd street(parthasarathy street) in Dn-41,Un-10,Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/20932,Roads,Completed,ND-TONDIARPET,37,964000,"PATCH WORK AT AMBEDKAR NAGAR AND UDHAYASURIYAN NAGAR IN DN-37,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/20944,Roads,Completed,ND-TONDIARPET,37,860000,"FORMING ROAD AT GOODSHED ROAD STREET IN DN-37,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/2096,Buildings,Completed,ND-TONDIARPET,45,985000,"IMPROVEMENT WORKS TO ZONE-4/LORRY STATION AT B.B ROAD IN DN.45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21004,Roads,Completed,ND-TONDIARPET,41,290897,"Attending patch work at cornation nagar 2nd street (MarimuthuStreet) in Dn-41, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21011,Roads,Completed,ND-TONDIARPET,41,309456,"Attending patch work at Anna Road in annai sathya nagar main street in Dn-41, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21014,Roads,Completed,ND-TONDIARPET,41,221694,"Attending patch work at Periyar salai in annai sathya nagar in Dn-41, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21017,Roads,Completed,ND-TONDIARPET,41,626793,"Attending patch work at Thoppai vinayagar koil street in Dn-41, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21029,Roads,Completed,ND-TONDIARPET,39,354000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at A.E KOIL Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21030,Roads,Completed,ND-TONDIARPET,39,218000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Veeraragavan Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21032,Roads,Completed,ND-TONDIARPET,39,204000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Butchammal Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21039,Roads,Completed,ND-TONDIARPET,39,147000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Poondi thangammal Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21044,Roads,Completed,ND-TONDIARPET,39,144000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Ponnuswamy Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21047,Roads,Completed,ND-TONDIARPET,39,325000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Vasar varathappan Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21049,Roads,Completed,ND-TONDIARPET,39,144000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Desiya Nagar in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21051,Roads,Completed,ND-TONDIARPET,39,151000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Cheriyan Nagar in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21053,Roads,Completed,ND-TONDIARPET,39,471000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Q.Q Scheme Road in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21055,Roads,Completed,ND-TONDIARPET,39,790000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Avoor Muthaiya Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21058,Roads,Completed,ND-TONDIARPET,39,846000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nammaiah Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21062,Roads,Completed,ND-TONDIARPET,39,900000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Venkatesan Ali Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/21203,Roads,Completed,ND-TONDIARPET,37,76322,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT ABIRAMI AVENUE 14TH 2ND LANE IN DIV-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21204,Roads,Completed,ND-TONDIARPET,37,221388,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT ABIRAMI AVENUE 14TH STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21205,Roads,Completed,ND-TONDIARPET,37,637471,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT BHAVANI STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21206,Roads,Completed,ND-TONDIARPET,37,152643,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT LENIN STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21207,Roads,Completed,ND-TONDIARPET,37,158135,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 10TH STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21208,Roads,Completed,ND-TONDIARPET,37,265666,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 1ST STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21209,Roads,Completed,ND-TONDIARPET,37,202412,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 2ND STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21210,Roads,Completed,ND-TONDIARPET,37,170785,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 3RD STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21211,Roads,Completed,ND-TONDIARPET,37,189762,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 4TH STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21212,Roads,Completed,ND-TONDIARPET,37,208738,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 7TH STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21213,Roads,Completed,ND-TONDIARPET,37,132833,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 8TH STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21215,Roads,Completed,ND-TONDIARPET,37,259341,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 5TH STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21216,Roads,Completed,ND-TONDIARPET,37,196087,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SASIREKHAMMA 6TH STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21217,Roads,Completed,ND-TONDIARPET,37,259341,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SRINIVASA 2ND LANE IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21218,Roads,Completed,ND-TONDIARPET,37,132833,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SUSILA NAGAR 1ST STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21221,Roads,Completed,ND-TONDIARPET,37,189762,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT VEDHAMUTHU STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21222,Roads,Completed,ND-TONDIARPET,37,202412,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT SUSILA NAGAR MAIN ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21234,Roads,Completed,ND-TONDIARPET,37,316269,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 2ND CROSS STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21235,Roads,Completed,ND-TONDIARPET,37,259341,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 3RD CROSS STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21237,Roads,Completed,ND-TONDIARPET,37,308998,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 4TH CROSS STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21238,Roads,Completed,ND-TONDIARPET,37,331422,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 6TH MAIN ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21239,Roads,Completed,ND-TONDIARPET,37,196087,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 1ST STREET LINK ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21240,Roads,Completed,ND-TONDIARPET,37,132833,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 2ND LINK ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21241,Roads,Completed,ND-TONDIARPET,37,189762,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 3RD LINK ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21242,Roads,Completed,ND-TONDIARPET,37,331422,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT M.K.B.NAGAR 4TH LINK ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21244,Roads,Completed,ND-TONDIARPET,37,328920,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT J.J NAGAR MAIN ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21247,Roads,Completed,ND-TONDIARPET,37,316269,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT NORTH AVENUE SERVICE ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21248,Roads,Completed,ND-TONDIARPET,37,197338,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT K.K.D NAGAR 6TH BLOCK 1ST CROSS STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21250,Roads,Completed,ND-TONDIARPET,37,189762,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT K.K.D NAGAR 8TH MAIN ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21251,Roads,Completed,ND-TONDIARPET,37,357557,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT K.K.D NAGAR 7TH MAIN ROAD IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21252,Roads,Completed,ND-TONDIARPET,37,268168,"ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS )AT PADMAVATHY STREET IN DIVISION-37,UNIT-09,ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21487,Roads,Completed,ND-TONDIARPET,38,1081000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nehru Nagar Main Road, Durga Devi Nagar Main Road, Karunanidhi Nagar Market Street and Sundaram Pillai Nagar 4th Main Road in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21491,Roads,Completed,ND-TONDIARPET,38,344000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar 'A' Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21492,Roads,Completed,ND-TONDIARPET,38,234000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar 1st Cross Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21495,Roads,Completed,ND-TONDIARPET,38,574000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar 2nd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21497,Roads,Completed,ND-TONDIARPET,38,233000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar 2nd Cross Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21499,Roads,Completed,ND-TONDIARPET,38,269000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar Cross Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21505,Roads,Completed,ND-TONDIARPET,36,126508,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT SARAVANAN STREET IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21521,Roads,Completed,ND-TONDIARPET,36,223473,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT MR NAGAR 2ND CROSS STREET IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21550,Roads,Completed,ND-TONDIARPET,36,292219,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT MR NAGAR 1ST STREET IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21555,Roads,Completed,ND-TONDIARPET,36,499217,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT MR NAGAR 1ST MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21565,Roads,Completed,ND-TONDIARPET,36,312863,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT THIRUVALLUVAR NAGAR 13TH MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21569,Roads,Completed,ND-TONDIARPET,36,462099,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT VIVEAKANANDA NAGAR 2ND MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21577,Roads,Completed,ND-TONDIARPET,36,474139,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT NAKEEREN STREET IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21589,Roads,Completed,ND-TONDIARPET,36,363577,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT THIRUVALLUVAR NAGAR 7TH STREET IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21605,Roads,Completed,ND-TONDIARPET,38,179000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at New Vinobha Nagar 1st Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21614,Roads,Completed,ND-TONDIARPET,38,162000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at New Vinobha Nagar 3rd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21618,Roads,Completed,ND-TONDIARPET,36,510200,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT WEST AVENUE 2ND MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21622,Roads,Completed,ND-TONDIARPET,38,312000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar Main Road in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21626,Roads,Completed,ND-TONDIARPET,38,313000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Karunanidhi Nagar 3rd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21631,Roads,Completed,ND-TONDIARPET,38,734000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar 3rd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21635,Roads,Completed,ND-TONDIARPET,36,826470,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT WEST AVENUE 1ST MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21649,Roads,Completed,ND-TONDIARPET,38,521000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar 4th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21655,Roads,Completed,ND-TONDIARPET,36,614742,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT THIRUVALLUVAR NAGAR 8TH MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21657,Roads,Completed,ND-TONDIARPET,38,410000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Nethaji Nagar 5th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21660,Roads,Completed,ND-TONDIARPET,38,202000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Sastri Nagar Main Road in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21665,Roads,Completed,ND-TONDIARPET,38,224000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Vaidhyanathan Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21667,Roads,Completed,ND-TONDIARPET,36,126508,ATTENDING PATCH WORK (2015 FLOOD DAMAGED ROADS) AT AVAIYAR STREET IN DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/21671,Roads,Completed,ND-TONDIARPET,38,224000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Vinobha Nagar 6th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21742,Buildings,Completed,ND-TONDIARPET,36,200000,"Painting Work, Gas Connection and Electrical Work At Amma Unavagam Phase II At Suzhlpunal Karai in Dn-36 U-09 Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/21841,Roads,Completed,ND-TONDIARPET,41,940000,"LAYING CC ROAD AT MUNIESWARAN NAGAR 1 ST STREET IN DN-41, UNIT-10 AND ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/21926,Roads,Completed,ND-TONDIARPET,44,333000,"LAYING CC ROAD AT ANNA NAGAR 1ST STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21931,Roads,Completed,ND-TONDIARPET,44,253000,"LAYING CC ROAD AT ANNA NAGAR 2ND STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21937,Roads,Completed,ND-TONDIARPET,44,250000,"LAYING CC ROAD AT ANNA NAGAR 3RD STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21941,Roads,Completed,ND-TONDIARPET,44,249000,"LAYING CC ROAD AT ANNANAGAR 4TH STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21945,Roads,Completed,ND-TONDIARPET,44,370000,"LAYING CC ROAD AT ANNA NAGAR 5TH STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21949,Roads,Completed,ND-TONDIARPET,44,333000,"LAYING CC ROAD AT AMBDHAR STREET(KAKANIJI NAGAR) IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21955,Roads,Completed,ND-TONDIARPET,44,134000,"LAYING CC ROAD AT ARIYA SHANKARAN STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21968,Roads,Completed,ND-TONDIARPET,44,338000,"LAYING CC ROAD AT BARATHITHSAN STREET(KAKANJI COLONY) IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21969,Roads,Completed,ND-TONDIARPET,44,266000,"LAYING CC ROAD AT KAMACHI STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21978,Roads,Completed,ND-TONDIARPET,44,166000,"LAYING CC ROAD AT THILAGAR STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/21981,Roads,Completed,ND-TONDIARPET,44,1104000,"LAYING BT ROAD AT NATTAL GARDEN 1ST STREET IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/22003,Roads,Completed,ND-TONDIARPET,34,1652000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KALASHATHAMMAN KOIL STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22021,Roads,Completed,ND-TONDIARPET,34,517000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22022,Roads,Completed,ND-TONDIARPET,34,463000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NEW JUMBULI RAGAVAN NAGAR STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22035,Roads,Completed,ND-TONDIARPET,34,1062000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT ANNAI THERASHA NAGAR 1ST STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22037,Roads,Completed,ND-TONDIARPET,34,204000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22038,Roads,Completed,ND-TONDIARPET,45,583000,"LAYING OF BT ROAD KASTHURIBAI GANDHI NAGAR IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/22044,Roads,Completed,ND-TONDIARPET,34,991000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT GOVINDASWAMY STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22051,Roads,Completed,ND-TONDIARPET,34,918000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT MUNUSWAMY STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22061,Roads,Completed,ND-TONDIARPET,34,938000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT ANDAL NAGAR 1ST STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22064,Roads,Completed,ND-TONDIARPET,45,526000,"LAYING OF BT ROAD AT KASTHURUIBAI GANDHI NAGAR 2ND STREET IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/22065,Roads,Completed,ND-TONDIARPET,34,478000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR 3rd STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22066,Roads,Completed,ND-TONDIARPET,34,840000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT ANDAL NAGAR 2ND STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22067,Roads,Completed,ND-TONDIARPET,35,3096000,"Relaying of Cement Concrete Road by RMC M30 Grade at Sivasankaran street , in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22069,Roads,Completed,ND-TONDIARPET,34,509000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT BESATHA STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22071,Roads,Completed,ND-TONDIARPET,34,877000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT POOKAVANAM NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22072,Roads,Completed,ND-TONDIARPET,34,433000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR 4th STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22075,Roads,Completed,ND-TONDIARPET,45,437000,"LAYING OF BT ROAD AT KASTHURIBAI GANDHI NAGAR 3RD STREET IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/22076,Roads,Completed,ND-TONDIARPET,34,586000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR 5th STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22078,Roads,Completed,ND-TONDIARPET,34,1804000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 2ND STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22079,Roads,Completed,ND-TONDIARPET,34,433000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR 6th STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22080,Roads,Completed,ND-TONDIARPET,34,399000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 1ST CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22082,Roads,Completed,ND-TONDIARPET,34,274000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 2ND CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22083,Roads,Completed,ND-TONDIARPET,34,642000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR 7th STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22084,Roads,Completed,ND-TONDIARPET,34,305000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 3RD CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22086,Roads,Completed,ND-TONDIARPET,34,455000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 4TH CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22087,Roads,Completed,ND-TONDIARPET,34,483000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT RAGAVAN NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22089,Roads,Completed,ND-TONDIARPET,34,385000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 5TH CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22090,Roads,Completed,ND-TONDIARPET,45,364000,"LAYING OF BT ROAD B V COLONY 11TH STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22093,Roads,Completed,ND-TONDIARPET,34,422000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT RAGAVAN NAGAR 1st CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22094,Roads,Completed,ND-TONDIARPET,34,377000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 6TH CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22095,Roads,Completed,ND-TONDIARPET,34,1370000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NEW JUMBULI PANDARANGAN STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22096,Roads,Completed,ND-TONDIARPET,34,527000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 7TH CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22098,Roads,Completed,ND-TONDIARPET,35,1019000,"Relaying of Cement Concrete Road by RMC M30 Grade solaiyamman street , in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22099,Roads,Completed,ND-TONDIARPET,34,340000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 8TH CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22101,Roads,Completed,ND-TONDIARPET,34,545000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 9TH CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22103,Roads,Completed,ND-TONDIARPET,34,1777000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT NEW JUMBULI THAMODHRAN STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22104,Roads,Completed,ND-TONDIARPET,45,590000,"LAYING OF BT ROAD B V COLONY 22ND STREET IN DN -45,UNIT-11,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/22105,Roads,Completed,ND-TONDIARPET,34,598000,"RE-LAYING B.T COURSE BY PAVER FINISHER ATANNAI VELAKANI NAGAR 1ST CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22106,Roads,Completed,ND-TONDIARPET,34,785000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT GOPAL REDDY STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22107,Roads,Completed,ND-TONDIARPET,34,284000,"RE-LAYING B.T COURSE BY PAVER FINISHER ATANNAI VELAKANI NAGAR 2ND CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22108,Roads,Completed,ND-TONDIARPET,36,1110000,"Relaying of BT Course By Paver At 14th West Cross Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22109,Roads,Completed,ND-TONDIARPET,34,252000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT HARBOUR COLONY 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22111,Roads,Completed,ND-TONDIARPET,45,645000,"LAYING OF BT ROAD B V COLONY 24TH STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22112,Roads,Completed,ND-TONDIARPET,35,1690000,"Relaying of Cement Concrete Road by RMC M30 Grade at solaiyamman 1st Street , in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22113,Roads,Completed,ND-TONDIARPET,35,460000,"Relaying of Cement Concrete Road by RMC M30 Grade at solaiyamman 2nd Street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22114,Roads,Completed,ND-TONDIARPET,45,578000,"LAYING OF BT ROAD BV COLONY 26TH STREET IN DN 45 ,UNIT-11,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22116,Roads,Completed,ND-TONDIARPET,36,1110000,"Relaying of BT Course By Paver At 17th West Cross Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22118,Roads,Completed,ND-TONDIARPET,35,197000,"Relaying of Cement Concrete Road by RMC M30 Grade at muthamil nagar V block 134th street , in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22120,Roads,Completed,ND-TONDIARPET,35,103000,"Relaying of Cement Concrete Road by RMC M30 Grade at muthamil nagar VI block 166th street, in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22122,Roads,Completed,ND-TONDIARPET,35,103000,"Relaying of Cement Concrete Road by RMC M30 Grade at muthamil nagar VI block 167th street , in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22127,Roads,Completed,ND-TONDIARPET,35,206000,"Relaying of Cement Concrete Road by RMC M30 Grade at muthamil nagar VI block 168th street , in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22131,Roads,Completed,ND-TONDIARPET,35,982000,"Relaying of Cement Concrete Road by RMC M30 Grade at muthamil nagar 2ndblock rear canal service road , in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22138,Roads,Completed,ND-TONDIARPET,35,376000,"Relaying of Cement Concrete Road by RMC M30 Grade at muthamil nagar VIII block 195th street in Division - 35, Unit - 9, Zone - IV.",Own Sources,4,2015-16,2016-17 ND/2015-16/22142,Roads,Completed,ND-TONDIARPET,35,1638000,"Relaying of Road with BC by Paver Finish at Sathyavani Muthu Salai in DN-35, Unit-09, Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22149,Roads,Completed,ND-TONDIARPET,37,2820000,"Relaying of bituminous course road with paver finisher at T.V.K link road in Div - 37, Unit - 09, Zone - 04",Own Sources,4,2015-16,2016-17 ND/2015-16/22170,Roads,Completed,ND-TONDIARPET,37,1200000,"Relaying of bituminous course road with paver finisher at Ambedkar street in Div - 37, Unit - 09, Zone - 04",Own Sources,4,2015-16,2016-17 ND/2015-16/22175,Roads,Completed,ND-TONDIARPET,37,607000,"Relaying of bituminous course road with paver finisher at Perumal street in Div - 37, Unit - 09, Zone - 04",Own Sources,4,2015-16,2016-17 ND/2015-16/22182,Roads,Completed,ND-TONDIARPET,36,573000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 2nd Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22185,Roads,Completed,ND-TONDIARPET,36,573000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 3rd Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22186,Roads,Completed,ND-TONDIARPET,36,344000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 4th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22188,Roads,Completed,ND-TONDIARPET,34,1191000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT AMUTHAM NAGAR MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/22190,Roads,Completed,ND-TONDIARPET,36,344000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 5th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22192,Roads,Completed,ND-TONDIARPET,36,344000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 6th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22195,Roads,Completed,ND-TONDIARPET,36,245000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 7th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22197,Roads,Completed,ND-TONDIARPET,36,344000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 9th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22199,Roads,Completed,ND-TONDIARPET,36,344000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 10th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22201,Roads,Completed,ND-TONDIARPET,36,400000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 11th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22205,Roads,Completed,ND-TONDIARPET,36,400000,"Laying Cement Concrete Road By RMC At Karunanithi Salai 12th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/22225,Roads,Completed,ND-TONDIARPET,36,1354000,"Laying Cement Concrete Road By RMC At Indira Gandhi Nagar 1st Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22227,Roads,Completed,ND-TONDIARPET,36,1354000,"Laying Cement Concrete Road By RMC At Indira Gandhi Nagar 2nd Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22228,Roads,Completed,ND-TONDIARPET,36,356000,"Laying Cement Concrete Road By RMC At Indira Gandhi Nagar 1st Cross Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22229,Roads,Completed,ND-TONDIARPET,36,356000,"Laying Cement Concrete Road By RMC At Indira Gandhi Nagar 2nd Cross Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22230,Roads,Completed,ND-TONDIARPET,36,356000,"Laying Cement Concrete Road By RMC At Indira Gandhi Nagar 3rd Cross Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22231,Roads,Completed,ND-TONDIARPET,36,356000,"Laying Cement Concrete Road By RMC At Indira Gandhi Nagar 4th Cross Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22232,Roads,Completed,ND-TONDIARPET,36,514000,"Laying Cement Concrete Road By RMC At Salaima Nagar 1st Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22233,Roads,Completed,ND-TONDIARPET,36,366000,"Laying Cement Concrete Road By RMC At Salaima Nagar 2nd Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22234,Roads,Completed,ND-TONDIARPET,36,145000,"Laying Cement Concrete Road By RMC At Salaima Nagar 3rd Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22235,Roads,Completed,ND-TONDIARPET,36,262000,"Laying Cement Concrete Road By RMC At Salaima Nagar 4th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22239,Roads,Completed,ND-TONDIARPET,36,730000,"Laying Cement Concrete Road By RMC At Bharathi Nagar 1st Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22240,Roads,Completed,ND-TONDIARPET,36,516000,"Laying Cement Concrete Road By RMC At Bharathi Nagar 2nd Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22241,Roads,Completed,ND-TONDIARPET,36,460000,"Laying Cement Concrete Road By RMC At Bharathi Nagar 3rd Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22242,Roads,Completed,ND-TONDIARPET,36,432000,"Laying Cement Concrete Road By RMC At Bharathi Nagar 4th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22249,Roads,Completed,ND-TONDIARPET,36,344000,"Laying Cement Concrete Road By RMC At Bharathi Nagar 5th Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22258,Roads,Completed,ND-TONDIARPET,36,2397000,"Laying Cement Concrete Road By RMC At Bharathi Nagar Main Street in DN-36, U-09, Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/22455,Roads,Completed,ND-TONDIARPET,48,165711,"Providing Patch work at Arumugam Street in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22456,Roads,Completed,ND-TONDIARPET,48,670420,"Providing Patch work at Parathasarathy 9th Street in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22457,Roads,Completed,ND-TONDIARPET,48,759809,"Providing Patch work at Parathasarathy Street in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22459,Roads,Completed,ND-TONDIARPET,48,517777,"Providing Patch work at M.S.naidu Street in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22461,Roads,Completed,ND-TONDIARPET,48,402252,"Providing Patch work at RAMANUJA IYAR Street in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22463,Roads,Completed,ND-TONDIARPET,48,473082,"Providing Patch work at Mannappan Street in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22464,Roads,Completed,ND-TONDIARPET,48,594098,"Providing Patch work at East Cementry Road in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22466,Roads,Completed,ND-TONDIARPET,48,491641,"Providing Patch work at Arani gangan Street in DN -48, unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/22566,Storm Water Drain,Completed,ND-TONDIARPET,37,531000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT MULLAI NAGAR BRIDGE SERVICE ROAD (SOUTHSIDE) CHAINAGE 0-40m IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/22593,Storm Water Drain,Completed,ND-TONDIARPET,37,996000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT M.K.B.NAGAR 1 TO 6 MAIN ROADS AND UDHAYASURIYAN NAGAR IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/22919,Roads,Completed,ND-TONDIARPET,40,384000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT AA SCHEME ROAD IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/22922,Roads,Completed,ND-TONDIARPET,40,295000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT AE KOIL STREET IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/22925,Roads,Completed,ND-TONDIARPET,40,186000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT CORPORATION COLONY 2nd STREET IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/22927,Roads,Completed,ND-TONDIARPET,40,180000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT CORPORATION COLONY 3rd STREET IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/22929,Roads,Completed,ND-TONDIARPET,40,316000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT CORPORATION COLONY 4th STREET IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/22930,Roads,Completed,ND-TONDIARPET,40,358000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT THIRUVALLUVAR NAGAR K STREET IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/22931,Roads,Completed,ND-TONDIARPET,40,162000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT THIRUVALLUVAR NAGAR M STREET IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/22933,Roads,Completed,ND-TONDIARPET,40,330000,"ATTENDING TEMPORARY RESTORATION TO THE DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTHEAST MONSOON 2015 AT THIRUVALLUVAR NAGAR 1st MAIN ROAD IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/23822,Roads,Completed,ND-TONDIARPET,43,273000,"FOR REPAIRS TO THE FLOOD DAMEGED Road at Kannkar Street in Dn-43,u-10,z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23832,Roads,Completed,ND-TONDIARPET,43,451000,"The Flood Damage Road at Pillaiyar Koil Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23833,Roads,Completed,ND-TONDIARPET,43,318000,"The Flood Damage Road at Kasipuram B Block 1st Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23835,Roads,Completed,ND-TONDIARPET,43,195000,"The Flood Damage Road at Kasipuram B Block 2nd Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23836,Roads,Completed,ND-TONDIARPET,43,150000,"The Flood Damage Road at Kasipuram B Block 3rd Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23837,Roads,Completed,ND-TONDIARPET,43,147000,"The Flood Damage Road at Kasipuram B Block 4th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23839,Roads,Completed,ND-TONDIARPET,43,184000,"The Flood Damage Road at Kasipuram B Block 5th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23840,Roads,Completed,ND-TONDIARPET,43,205000,"The Flood Damage Road at Kasipuram B Block 6th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23841,Roads,Completed,ND-TONDIARPET,43,210000,"The Flood Damage Road at Kasipuram B Block 7th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23842,Roads,Completed,ND-TONDIARPET,43,180000,"The Flood Damage Road at Kasipuram B Block 8th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23843,Roads,Completed,ND-TONDIARPET,43,307000,"The Flood Damage Road at Kasipuram B Block 9th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23844,Roads,Completed,ND-TONDIARPET,43,191000,"The Flood Damage Road at Kasipuram B Block 10th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23846,Roads,Completed,ND-TONDIARPET,43,234000,"The Flood Damage Road at Kasipuram B Block 11th Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23915,Buildings,Completed,ND-TONDIARPET,40,967000,"IMPROVEMENTS TO AMMA UNAVAGAM AT MANGAMMAL THOTTAM IN DN-40, UNIT-10, ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23919,Buildings,Completed,ND-TONDIARPET,40,972000,"Improvements to Division Office at Ammaniammal Thottam in Dn-40, Unit-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/23920,Buildings,Completed,ND-TONDIARPET,40,997000,"PROPOSED CONSTRUCTION OF AMMA WATER R.O.PLANT AT VAIDHIYANATHAN STREET IN DN-40, UNIT-10, ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/23927,Parks,Completed,ND-TONDIARPET,42,857000,improvements to corporation park at rettaikuzli street in ward.42 unit.10 zone.4,Own Sources,4,2015-16,2016-17 ND/2015-16/23929,Footpath,Completed,ND-TONDIARPET,42,550000,"IMPROVEMENTS TO FOOTPATH AT KESAVAN STREET IN DN-42, UNIT-10, ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/23930,Buildings,Completed,ND-TONDIARPET,42,510000,"Improvements To The Zonal Office Building for Election Facilition Center DN-42, Unit-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/23931,Storm Water Drain,Completed,ND-TONDIARPET,42,958000,"Repair and Improvements to Existing SWD at Rathinasabapathi Street in Dn-42, Unit-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/24240,Buildings,Completed,ND-TONDIARPET,36,838000,"Providing Portable Toilets 4 Nos with Water Tank 2000lt on Rental basis and Maintenance for one year at Sidco Nagar Main Road Opp to Vasuki Park, in Dn-36, Unit-9, Zone IV.",Own Sources,4,2015-16,2017-18 ND/2015-16/24243,Storm Water Drain,Completed,ND-TONDIARPET,36,753000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT THIRUVALLUVAR NAGAR 8TH MAIN ROAD CHAINAGE 100-145m, IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/24244,Storm Water Drain,Completed,ND-TONDIARPET,36,797000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT WEST AVENUE (WEST SIDE) FROM DOOR NO:130 TO PUDHUNAGAR 7TH STREET IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/24247,Storm Water Drain,Completed,ND-TONDIARPET,36,381000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT WEST AVENUE (WEST SIDE) FROM PUDHUNAGAR 7TH STREET TO AMMAN TEMPLE (NEAR JUNCTION OF CENTRAL AVENUE) IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/24390,Storm Water Drain,Completed,ND-TONDIARPET,43,765000,"Desilting,Repairs and Improvements to SWD at Singaravelan Nagar in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/24681,Storm Water Drain,Completed,ND-TONDIARPET,47,976000,Construction of retaning wall at ambhedhar canal in dn 47 u 11 z 4 (reach 1),Own Sources,4,2015-16,2016-17 ND/2015-16/24693,Storm Water Drain,Completed,ND-TONDIARPET,47,995000,Construction of retaning wall at ambhedhar canal in dn 47 u 11 z 4 (reach2),Own Sources,4,2015-16,2016-17 ND/2015-16/24694,Storm Water Drain,Completed,ND-TONDIARPET,47,986000,Construction of retaning wall at ambhedhar canal in dn 47 u 11 z 4 (reach 3),Own Sources,4,2015-16,2016-17 ND/2015-16/24723,Roads,Completed,ND-TONDIARPET,35,990000,"Name of work: PROVIDING RAIN WATER HARVESTING SYSTEM USING PRE-CAST RCC WELL RINGS COVERED WITH RCC COVER SLAB AND PVC PIPE AT VARIOS STREET IN DN-35,UNIT-09, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/24885,Buildings,Completed,ND-TONDIARPET,44,993000,"Estimate for carrying out petty repairs (Day to Day) in the following buildings School, Hospital, NNMP Shed and P.C in Dn-44, unit-11, zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/24895,Parks,Completed,ND-TONDIARPET,37,863000,"ANNUVAL MAINTANANCE OF PARK AT JAWAHAR STREET, LINGASAN STREET, VIVAKANANDA STREET, DR.AMBADKAR STREET, PARK FOR 1 YEAR IN DIVISION - 37, UNIT - 9, ZONE - 4.",Own Sources,4,2015-16,2017-18 ND/2015-16/24896,Parks,Completed,ND-TONDIARPET,37,854000,"ANNUVAL MAINTANANCE OF PARK AT SRINIVASA STREET, GANDHI STREET, SASIRAKKAMA NAGAR, KANNADASAN NAGAR 7TH BLOCK, PARK FOR 1YEAR IN DIVISION - 37, UNIT - 9, ZONE - 4.",Own Sources,4,2015-16,2017-18 ND/2015-16/24933,Roads,Completed,ND-TONDIARPET,42,141000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Anna Street in Dn-42, Unit-10, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/24935,Roads,Completed,ND-TONDIARPET,42,693000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Rettai Kuzhi Street in Dn-42, Unit-10, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/24936,Roads,Completed,ND-TONDIARPET,42,128000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Krishnappa Thottam 1st Street in Dn-42, Unit-10, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/24990,Roads,Completed,ND-TONDIARPET,42,182000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Krishnappa Thottam 2nd Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/24991,Roads,Completed,ND-TONDIARPET,42,281000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Krishnappa Thottam 3rd Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/24993,Roads,Completed,ND-TONDIARPET,42,308000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Krishnappa Thottam Main Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/24996,Roads,Completed,ND-TONDIARPET,42,681000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Rathinasapabathy Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/24997,Roads,Completed,ND-TONDIARPET,42,316000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Kesavan Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25005,Roads,Completed,ND-TONDIARPET,42,287000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Kothandaraman Lane in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25007,Roads,Completed,ND-TONDIARPET,42,700000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Mayor Basudev Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25009,Roads,Completed,ND-TONDIARPET,42,206000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Thirunavukarasu Thottam 1st Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25011,Roads,Completed,ND-TONDIARPET,42,177000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Thirunavukarasu Thottam 2nd Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25013,Roads,Completed,ND-TONDIARPET,42,206000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Thirunavukarasu Thottam 3rd Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25014,Roads,Completed,ND-TONDIARPET,42,247000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Thirunavukarasu Thottam 4th Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25015,Roads,Completed,ND-TONDIARPET,42,253000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Thirunavukarasu Thottam 5th Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25017,Roads,Completed,ND-TONDIARPET,42,573000,"Attending Temporary Restoration to the Damaged Interior Roads affected due to Flood in North East Monsoon 2015 at Veerakutty Street in Dn-42, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25069,Parks,Completed,ND-TONDIARPET,48,940000,"Providing Children Play Field at Parthasarathy Nagar in Dn-48, Unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/25170,Storm Water Drain,Completed,ND-TONDIARPET,38,974000,"DEWATERING OF FLOOD STAGNATION OF AREA BY USING 52.50 TO 60.00HP MOTOR PUMP AT ELAYA STREET,ENNORE HIGH ROAD AND DURGA DEVI NAGAR INSIDE OF TNEB OFFICE IN DN-38 UNIT-09 ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/2520,Parks,Completed,ND-TONDIARPET,36,970000,"IMPROVEMENTS AND GREENARY ARRANGEMENT TO PARK AT VASUGI PARK IN DIV-36,UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/25270,Buildings,Completed,ND-TONDIARPET,43,955000,"Construction of Compound Wall at Jeevarathinam Salai in DN-43,U-10,Z-04(Councilor Fund)",Own Sources,4,2015-16,2016-17 ND/2015-16/25349,Buildings,Completed,ND-TONDIARPET,43,965000,"Partition works to community center at Kasima Nagar 3rd Street in DN-43,U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/25370,Buildings,Completed,ND-TONDIARPET,41,970000,"IMPROVEMENTS TO P.C AT LIME KLIN ROAD IN DN-41, UN-10, ZN-04",Own Sources,4,2015-16,2016-17 ND/2015-16/25752,Buildings,Completed,ND-TONDIARPET,37,964000,"Painting K.D.G Compound Wall at T.H.Road in Dn.37,Unit.9,Zone.4",Own Sources,4,2015-16,2016-17 ND/2015-16/25795,Buildings,Completed,ND-TONDIARPET,47,468000,CONSTRUCTION OF COMPOUND WALL AT C B ROAD FOR ROADWIDENING FOR BRIDGES IN DN 47 U 11 Z4,Own Sources,4,2015-16,2016-17 ND/2015-16/25867,Roads,Completed,ND-TONDIARPET,34,910000,"RAISING AND FORMING THE ROAD AT PALPANNAI SALAI CROSS STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/25868,Roads,Completed,ND-TONDIARPET,34,705000,"RAISING AND FORMING THE ROAD AT HARBOUR COLONY 1st STREET AND METTU STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/25871,Roads,Completed,ND-TONDIARPET,34,870000,"LAYING ROAD BY INTERLOCKING BLOCK AT SAGAYA NAGAR IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/25879,Roads,Completed,ND-TONDIARPET,34,410000,"RAISING AND FORMING THE ROAD AT VENKATESWARA COLONY 6th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26114,Electrical,Completed,ND-TONDIARPET,39,957100,"Provision of 12 Nos. of 8 Mtr G.I Lamp Post with Straight bracket with 165W LED Fitting at Cherian Nagar, Chennai High School Play Ground in Dn:39, Zone IV.",Own Sources,4,2015-16,2019-20 ND/2015-16/26125,Electrical,Completed,ND-TONDIARPET,39,569200,"Electrification work in Chennai Higher Secondary School, Playground and Park Maintenance at No.731, T.H Road in Dn:39, Zone IV",Own Sources,4,2015-16,2016-17 ND/2015-16/26138,Electrical,Completed,ND-TONDIARPET,39,579100,"Electrification work in Chennai Urudu Middle School, Playground and Park Maintenance at Cherian Nagar main Street in Dn:39, Zone IV",Own Sources,4,2015-16,2016-17 ND/2015-16/26147,Electrical,Completed,ND-TONDIARPET,39,805700,"Electrification work in Corporation Hospital at Cherian Nagar 4th Street in Dn:39, Zone IV",Own Sources,4,2015-16,2019-20 ND/2015-16/26165,Electrical,Completed,ND-TONDIARPET,39,853700,"Electrification Work in Chennai High School, Playground and Park Maintenance at Cherian Nagar, Kannupillai Street in Dn:39, Zone IV",Own Sources,4,2015-16,2016-17 ND/2015-16/26203,Storm Water Drain,Completed,ND-TONDIARPET,37,968000,"Improvements to existing strom water drain at MKB nagar North Avenue Chainage from 0m to 50m in DIV-37, UNIT-9, ZONE-4..",Own Sources,4,2015-16,2016-17 ND/2015-16/26204,Storm Water Drain,Completed,ND-TONDIARPET,37,968000,"Improvements to existing strom water drain at MKB nagar North Avenue Chainage from 50m to 100m in DIV-37, UNIT-9, ZONE-4..",Own Sources,4,2015-16,2016-17 ND/2015-16/26205,Storm Water Drain,Completed,ND-TONDIARPET,37,968000,"Improvements to existing strom water drain at MKB nagar North Avenue Chainage from 100m to 150m in DIV-37, UNIT-9, ZONE-4..",Own Sources,4,2015-16,2016-17 ND/2015-16/26206/C,Storm Water Drain,Completed,ND-TONDIARPET,37,968000,"Improvements to existing strom water drain at MKB nagar North Avenue Chainage from 150m to 200m in DIV-37, UNIT-9, ZONE-4..",Own Sources,4,2015-16,2016-17 ND/2015-16/26207,Storm Water Drain,Completed,ND-TONDIARPET,37,968000,"Improvements to existing strom water drain at MKB nagar North Avenue Chainage from 200m to 250m in DIV-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26292,Buildings,Completed,ND-TONDIARPET,48,920000,"Day to Day building maintenance IN DN-48, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26293,Roads,Completed,ND-TONDIARPET,48,940000,"Day to Day Road maintenance in DN-48, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26295,Storm Water Drain,Completed,ND-TONDIARPET,48,960000,"Day to Day maintenance SWD in DN -48,Unit -11, Zone 4",Own Sources,4,2015-16,2016-17 ND/2015-16/26297,Roads,Completed,ND-TONDIARPET,48,940000,"Maintenance for Attending CC Patch work at Various street in DN-48, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26298,Buildings,Completed,ND-TONDIARPET,48,960000,"Providing compound Wall Around Corporation Land at Pathasarathy Nagar in DN-48, U -11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26300,Buildings,Completed,ND-TONDIARPET,48,360000,"Providing grill gate and Repairs to Sunshade in CMS at Buddha Street in Dn-48, U-11,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/2660,Roads,Completed,ND-TONDIARPET,45,993000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DN-45,UNIT-11,ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/26648,Electrical,Completed,ND-TONDIARPET,37,929600,"Provision of 46 nos of 3mtr Garden Lamp post with 20Watts LED Fitting at Lenin Street Park, Agasthiyar Street Park, 13th East Cross Street PArk, 16th East Cross Street Park, Srinivasan street Park, 4th Cross Street Park, Udyasuriyan Nagar Street PArk in Division 37, Unit 09, Zone IV",Own Sources,4,2015-16,2016-17 ND/2015-16/26654,Electrical,Completed,ND-TONDIARPET,37,953600,"Provision of 48 Nos of 3mtr Garden Lamp Post with 20Watts LED Fitting at Vivekananda Nagar Park, Ambedkar Street Park, Gandhiji Street Park, Jawahar Street Park, KKD Nagar 8th block Park, KKD Nagar 7th block Park, Valluvar Park in Division 37, Unit 09, Zone IV",Own Sources,4,2015-16,2016-17 ND/2015-16/26664,Electrical,Completed,ND-TONDIARPET,46,847900,"Provision of 42 Nos of 3mtr Garden Lamp Post with 20Watts LED Fitting at Trichy Chinnasamy Street Park, Jawahar Nagar Park, Kakkanji Colony Park, SM Nagar Park in Division 44 & 46, Unit 11, Zone IV",Own Sources,4,2015-16,2016-17 ND/2015-16/2679,Footpath,Completed,ND-TONDIARPET,48,800000,"IMPROVEMENT TO THE PLAY GROUND @ KANNIKOVIL ST IN DN-48, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26800,Playfields,Completed,ND-TONDIARPET,46,980000,"Provision of 20 nos of 9.2mtr Post with 55 nos of 400 Watts MH FL Fitting in Newly Developed Foot Ball Ground at Samanthipoo colony (Western Side) in Division 46, Zone IV.",Own Sources,4,2015-16,2017-18 ND/2015-16/26801,Playfields,Completed,ND-TONDIARPET,46,990000,"Provision of 11 nos of 9.2mtr Post with 50 nos of 400 Watts MH FL Fitting in Newly Developed Foot Ball Ground at Samanthipoo colony (Eastern Side) in Division 46, Zone IV.",Own Sources,4,2015-16,2017-18 ND/2015-16/2683,Buildings,Completed,ND-TONDIARPET,48,770000,"PROVIDING WATER SUPPLY ARRANGEMENTS FOR CORPORATION BUILDING @ VARIOUS STREET IN DN-48, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/26920,Storm Water Drain,Completed,ND-TONDIARPET,37,996000,"Demolition And Re-Construction of Storm Water Drain at Sathyamoorthy Nagar Main Road Junction of North Avenue Road to Canal, Chainage 0m to 20m in Dn:37, U:9, Z:IV",Own Sources,4,2015-16,2016-17 ND/2015-16/27017,Buildings,Completed,ND-TONDIARPET,43,2350000,"Construction of ICDS at Kasipuram B Block 10th Street(councilar Fund) in DN-43,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27174,Buildings,Completed,ND-TONDIARPET,42,983000,"Improvements to health post at ADHAR room, Gym building and other improvements at TH Road in ward.42 unit.10 zone.4",Own Sources,4,2015-16,2016-17 ND/2015-16/27215,Roads,Completed,ND-TONDIARPET,44,992000,"RELAYING CC ROAD AT VANNAI PANDIAN STREET IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/27217,Roads,Completed,ND-TONDIARPET,44,789000,"RELAYING BT ROAD AT NATTAL GARDEN 2ND STREET(0m To 90m) IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27248,Roads,Completed,ND-TONDIARPET,44,789000,"RELAYING BT ROAD AT NATTAL GARDEN 2ND STREET(90 m TO 180 m) IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27251,Roads,Completed,ND-TONDIARPET,44,789000,"RELAYING BT ROAD AT NATTAL GARDEN 2ND STREET(180 m TO 270 m) IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27252,Roads,Completed,ND-TONDIARPET,44,653000,"RELAYING BT ROAD AT NATTAL GARDEN 2ND STREET(270 m TO 345 m) IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27299,Roads,Completed,ND-TONDIARPET,34,867000,"DE-WATERING OF FLOOD STAGNATION AREA BY USING 30 HP MOTOR PUMP AT GOVINDASWAMY STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27380,Buildings,Completed,ND-TONDIARPET,39,578000,"Additional Work to Multi purpose Hall at S.N Chetty Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27517,Footpath,Completed,ND-TONDIARPET,47,657000,FORMING NEW FOOT PATH AT K.H ROAD IN DN 47 UNIT 11 ZONE 4,Own Sources,4,2015-16,2016-17 ND/2015-16/27522,Parks,Completed,ND-TONDIARPET,46,965000,"Improvements to Sathyamoorthy Nagar park ( CCTV, Park Street lights and Fountain Rectification )in DN -46, unit -11, Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/27543,Parks,Completed,ND-TONDIARPET,46,960000,"Installation & Commissioning of CCTV Systems at Samanthypoo Colony Football Ground in DN -46,Unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/27590,Roads,Completed,ND-TONDIARPET,37,953000,"Relaying of Cement Concrete Road by RMC M30 Grade at Golden Complex First Sector in div-37,unit-9,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27592,Roads,Completed,ND-TONDIARPET,37,953000,"Relaying of Cement Concrete Road by RMC M30 Grade at Golden Complex Third Sector in div-37,unit-9,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27644,Parks,Completed,ND-TONDIARPET,34,955000,"ANNUAL MAINTENANCE (2016)TO PARKS AT VENKATESWARA COLONY 5THSTREET,UNION CARPIT COLONY 14TH STREET, BINNYNAGAR MAIN ROAD, KAVARI NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27869,Footpath,Completed,ND-TONDIARPET,48,985000,"PROVIDING CONCRETE PLATFORM WITH DRAINAGE ARRANGMENTS AT PARTHASARATHY NAGAR IN DN-48, U-11, Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27884,Footpath,Completed,ND-TONDIARPET,48,700000,"Providing Pathway with Greenery @ Parthasarathy nagar in Dn-48, U-11, z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27892,Buildings,Completed,ND-TONDIARPET,48,680000,"REPAIRS AND IMPROVEMENT TO THE WEATHEARING COURSE, DRAINAGE AND ELECTRICAL ARRANGMENTS TO THE COMMUNITY CENTER AT PARTHASARATHY NAGAR IN DN-48, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27924,Buildings,Completed,ND-TONDIARPET,42,780000,"Conversion of class rooms in to Smart class room and Head mistress room and Providing drinage arrangements to to north and south block at Chennai higher secondary school 540 Th road in div-42,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27925,Roads,Completed,ND-TONDIARPET,34,970000,"RAISING THE ROAD AT DURGAI ANENU 1st AND 2nd MAIN ROAD (PARTIALLY),DURGAI AVENU 6th,9th AND 14th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27941,Buildings,Completed,ND-TONDIARPET,40,992000,"Attending Leaky roof and laying pressed tiles and necessary improvements to toilet block at Chennai primary school at Thiruvalluvar nagar in div-40,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/27960,Roads,Completed,ND-TONDIARPET,34,980000,"RAISING THE ROAD AT HARBOUR COLONY 2nd,3rd,4th AND 5th CROSS STREETS IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27965,Roads,Completed,ND-TONDIARPET,34,980000,"RAISING THE ROAD AT HARBOUR COLONY 6th,7th,8th AND 9th CROSS STREETS IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27989,Buildings,Completed,ND-TONDIARPET,45,999000,"Estimate for carrying out petty repairs (Day to Day) in Corporation building at Various Street in Dn.45, Unit.11, Zone.4.",Own Sources,4,2015-16,2016-17 ND/2015-16/27999,Storm Water Drain,Completed,ND-TONDIARPET,34,975000,"REPAIRS AND IMPROVEMENTS TO SWD AT UC COLONY 14 th STREET,AMUTHAM NAGAR JUNCTION AND ARUL NAGAR MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28012,Buildings,Completed,ND-TONDIARPET,43,543000,"Providing and fixing RO Plant to CD hospital new block (first floor)in div-43,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28013,Buildings,Completed,ND-TONDIARPET,43,978000,"providing aluminium partition for fever ward,chiken pox ward,dyaria ward,Admission ward,out patient ward,and repair works to pathway and the rear side footpath in cd hospital in div-43,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28017,Roads,Completed,ND-TONDIARPET,34,950000,"FORMING NEW ROAD AT DURGAI AVENUE 15TH CROSS ST IN DN-34 ,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28018,Roads,Completed,ND-TONDIARPET,34,998000,"FORMING NEW ROAD AT DURGAI AVENUE 16TH CROSS ST IN DN-34 ,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28019,Subway,Completed,ND-TONDIARPET,43,910000,"IMPROVEMENTS TO SUBWAY(WEST SIDE) AT TH ROAD IN DN-43,UNIT- 10,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28021,Subway,Completed,ND-TONDIARPET,43,938000,"IMPROVEMENTS TO SUBWAY(EAST SIDE) AT TH ROAD IN DN-43 UNIT-10 ZONE-04",Own Sources,4,2015-16,2016-17 ND/2015-16/28045,Roads,Completed,ND-TONDIARPET,48,970000,"Maintenance for Attending B.T. Patch Work at Various Street in Dn-48, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28120,Roads,Completed,ND-TONDIARPET,37,697000,"Forming Agathiyar 2nd street by WMM in DN-37, U-09, Z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/28172,Roads,Completed,ND-TONDIARPET,37,697000,"Forming Agathiyar 3rd Street By Wmm In Dn-37, U-09, Z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/28173,Roads,Completed,ND-TONDIARPET,37,697000,"Forming Agathiyar 1st Street by WMM in DN-37, U-09, Z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/28174,Roads,Completed,ND-TONDIARPET,37,986000,"Improvements to Amma unavagam at KKD nagar 7th Block in Div-34, Unit-9,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28281,Storm Water Drain,Completed,ND-TONDIARPET,37,996000,"Demolition And Re-Construction of Storm Water Drain at Sathyamoorthy Nagar Main Road Junction of North Avenue Road to Canal, Chainage 20m to 40m in Dn:37, U:9, Z:IV",Own Sources,4,2015-16,2016-17 ND/2015-16/28282,Storm Water Drain,Completed,ND-TONDIARPET,37,996000,"Demolition And Re-Construction of Storm Water Drain at Sathyamoorthy Nagar Main Road Junction of North Avenue Road to Canal, Chainage 40m to 60m in Dn:37, U:9, Z:IV",Own Sources,4,2015-16,2016-17 ND/2015-16/28284,Storm Water Drain,Completed,ND-TONDIARPET,37,855000,"Demolition And Re-Construction of Storm Water Drain And Providing Column With Gate at Sathyamoorthy Nagar Main Road Junction of North Avenue Road to Canal, Chainage 60m to 70m in Dn:37, U:9, Z:IV",Own Sources,4,2015-16,2016-17 ND/2015-16/28285,Buildings,Completed,ND-TONDIARPET,34,997000,"CONSTRUCTION OF COMPOSED YARD AT ARUL NGAR MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28286,Buildings,Completed,ND-TONDIARPET,34,997000,"CONSTRUCTION OF STORE ROOM FOR COMPOSED YARD AT ARUL NAGAR MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28287,Roads,Completed,ND-TONDIARPET,37,999000,"Laying of Cement Concrete Road at Sathyamoorthy Nagar Main Road Junction of North Avenue Road To Canal, Chainage 0M To 70M in Dn:37, U:9, Z:IV",Own Sources,4,2015-16,2016-17 ND/2015-16/28288,Roads,Completed,ND-TONDIARPET,44,989000,"RELAYING CC ROAD AT PERIYAR STREET IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28289,Storm Water Drain,Completed,ND-TONDIARPET,44,987000,"PROVIDING RAIN WATER HARVESTING AND SILT CATCH PIT STRUCTURES AT VARIOUS STREET IN DN-44, UNIT-11, ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/28293,Roads,Completed,ND-TONDIARPET,44,957000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and Providing Thermo Plastic Compound marking Road pavement markers and signage boards at various IRR Road in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/28313,Buildings,Completed,ND-TONDIARPET,44,912000,"Improvements to Park and Children Play ground at Thirchy Chinnasamy street, K.v.k samy street, Anna nagar 5th street in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/2840,Buildings,Completed,ND-TONDIARPET,47,990000,"REPAIR AND IMPROVEMENT TO CHS IN GROUND FLOOR @HARAINARAYANA PURAM IN DN-47, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28467,Parks,Completed,ND-TONDIARPET,37,938000,"PROVIDING FOOTPATH FOR MULLAI NAGAR BURIAL GROUND FROM 0M TO 100M IN DIV 37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28468,Parks,Completed,ND-TONDIARPET,37,938000,"PROVIDING FOOTPATH FOR MULLAI NAGAR BURIAL GROUND FROM 100M TO 200M IN DIV 37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28470,Parks,Completed,ND-TONDIARPET,37,938000,"PROVIDING FOOTPATH FOR MULLAI NAGAR BURIAL GROUND FROM 200M TO 300M IN DIV 37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28471,Parks,Completed,ND-TONDIARPET,37,938000,": PROVIDING FOOTPATH FOR MULLAI NAGAR BURIAL GROUND FROM 200M TO 300M IN DIV 37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28563,Buildings,Completed,ND-TONDIARPET,37,710000,"PROVIDING LABOUR REST ROOM AND COLOUR WASHING FOR AE OFFICE AT KDG IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28567,Storm Water Drain,Completed,ND-TONDIARPET,35,995000,"PROPOSED DAY TO DAY REPAIR(PETTY) WORKS IN VARIOUS STROM WATER DRAIN IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28673,Roads,Completed,ND-TONDIARPET,34,932000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT NARASIMMA REDDIYAR NAGAR 1st,2nd,4th STREET,NARAYANASWAMY GARDEN1st,2nd MAIN ROAD AND NARAYANASWAMY GARDEN 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28677,Roads,Completed,ND-TONDIARPET,34,891000,"PROVIDING STREET FURNISHERS ,THERMO PLASTER AND STUDS AT NARAYANASWAMY GARDEN 3rd MAIN RAOD,PRAVATHY NAGAR 2nd,3rd STREET,SCHOOL ROAD AND JAI BALAJI 1st MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28681,Roads,Completed,ND-TONDIARPET,34,855000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT VENKATESWARA NAGAR(Part-1) 2nd,3rd,4th STREET,VENKATESWARA NAGAR(Part-1) 1st AND 2nd CROSS STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28682,Roads,Completed,ND-TONDIARPET,34,955000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT VENKATESWARA NAGAR(Part-1) 3rd,4th CROSS STREET,SENTHIL NAGAR 2nd STREET,NARAYANASWAMY GARDEN 1st,5th STREET AND PARVATHY NAGAR 1st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28683,Roads,Completed,ND-TONDIARPET,34,430000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT UNION CARBIDE COLONY 1st AND 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28684,Roads,Completed,ND-TONDIARPET,34,889000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT UNION CARBIDE COLONY 4th,6th,9th,17th AND 18th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28685,Roads,Completed,ND-TONDIARPET,34,622000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT UNION CARBIDE COLONY 14th STREET,VENKATESWARA NAGAR(part-II) 1st AND 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28688,Roads,Completed,ND-TONDIARPET,34,990000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT BINNY NAGAR MAIN ROAD,MILK COLONY ROAD,JAI BALAJI NAGAR 1st CROSS STREET,SENTHIL NAGAR MAIN ROAD,RAGAVENDHRA NAGAR 2nd STREET,UNION CARBIDE COLONY 22nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28691,Roads,Completed,ND-TONDIARPET,34,922000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT UNION CARBIDE COLONY 5th STREET,NARASIMMA REDDIYAR NAGAR 3rd,5th STREET AND 4th CROSS STREET,NARAYANASWAMY GARDEN 3rd,4th,6th,7th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28693,Roads,Completed,ND-TONDIARPET,34,956000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT NARAYANASWAMY GARDEN 8th,9th STREET,UNION CARBIDE COLONY 8th,10th,13th,16th,20th AND 21st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28694,Roads,Completed,ND-TONDIARPET,34,896000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT VENKATESWARA COLONY 3rd,4th,5th,7th STREET,VENKATESWARA NAGAR(Part-1) 1st STREET AND VENKATESWARA NAGAR(Part-II) 3rd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28696,Roads,Completed,ND-TONDIARPET,34,999000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT VENKATESWARA NAGAR(Part-II) 1st CROSS STREET,SAGAYA NAGAR,CHINNA PAPPAMMAL STREET,SENTHIL NAGAR 1st STREET,KUMARAN NAGAR 1st ,3rd STREET AND MAIN ROAD,ANNAI AVENU 1st STREETIN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28698,Roads,Completed,ND-TONDIARPET,34,967000,"PROVIDING STREET FURNISHERS, THERMO PLASTER AND STUDS AT ANNAI AVENU 2nd,3rd STREET,UNION CARBIDE COLONY 3rd,7th,11th,12th AND 15th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28701,Roads,Completed,ND-TONDIARPET,34,982000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT VENKATESWARA COLONY 8th,9th STREET AND MAIN ROAD ,SOLAIAMMAN KOIL MAIN ROAD,LAKSHMI AMMAN KOIL STREET,M.R.L COLONY 1st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28703,Roads,Completed,ND-TONDIARPET,34,887000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT KATTABOMMAN 1st,2nd,6th,7th STREET,JAI BALAJI NAGAR 1st,2nd STREET AND KUMARAN NAGAR 2nd STREETIN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28704,Roads,Completed,ND-TONDIARPET,34,593000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT UNION CARBIDE COLONY 19th STREET,VENKATESWARA COLONY 6th STREET,RISWAN SALAI AND KATTABOMMAN 9th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28705,Roads,Completed,ND-TONDIARPET,34,458000,"PROVIDING STREET FURNISHERS,THERMO PLASTER AND STUDS AT KATTABOMMAN MAIN ROAD,JAI BALAJI 2nd MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28796,Roads,Completed,ND-TONDIARPET,46,765000,"FORMATION OF FOOTPATH AT MOORTHINGAR STREET OPPOSITE RAVEESWARAN TEMPLE IN DN-46, UNIT-11, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/28834,Buildings,Completed,ND-TONDIARPET,34,997000,"WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO COMPOSED YARD AT ARUL NAGAR MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/28846,Buildings,Completed,ND-TONDIARPET,37,600000,"Improvements to NNMP SHED at M.G.R. Nagar in Dn - 37, Unit - 9, Zone - 4.",Own Sources,4,2015-16,2016-17 ND/2015-16/29082,Storm Water Drain,Completed,ND-TONDIARPET,37,531000,"CONSTRUCTION OF STORM WATER DRAIN AT M.K.B.NAGAR 1ST CROSS STREET FROM WEST AVENUE CHAINAGE 0-45M IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/29089,Storm Water Drain,Completed,ND-TONDIARPET,37,531000,"CONSTRUCTION OF STORM WATER DRAIN AT M.K.B.NAGAR 1ST CROSS STREET FROM WEST AVENUE CHAINAGE 45-90M IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/29093,Culvert,Completed,ND-TONDIARPET,37,741000,"PROVIDING PIPE CULVERTS AT VARIOUS LOCATIONS INSIDE KODUNGAIYUR DUMPING GROUND IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/29185,Roads,Completed,ND-TONDIARPET,34,710000,"Attending BT Patch at Kadumpadiamman Koil Street (From Union Carbide Colony 18th Street to Thendral Nagar 4th Street ) and Vedandamurugappan Koil Street in Div - 34, Unit - 10, zone - 4",Own Sources,4,2015-16,2017-18 ND/2015-16/29195,Roads,Completed,ND-TONDIARPET,37,381000,"PROVIDING STAINLESS STEEL NAME BOARDS ( FOR DEMARCATING GARBAGE DUMPING LOCATIONS BY VARIOUS ZONES ) INSIDE KODUNGAIYUR DUMPING GROUND IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/29213,Buildings,Completed,ND-TONDIARPET,47,985000,CONSTRUCTION OF CENTRE MEDERIAN AT K H ROAD IN DN 47 U11 Z4,Own Sources,4,2015-16,2016-17 ND/2015-16/29311,Roads,Completed,ND-TONDIARPET,46,998000,"FORMATION OF FOOTPATH ATS M NAGAR MAIN ROAD NEAR GROUP BIN LOCATION IN DN-46, UNIT-11,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/29558,Roads,Completed,ND-TONDIARPET,35,976000,"Providing street name board Thermoplast and reflectors in 152nd,154th,156 157 158 159 151 150 161 160 149 148 147 146 145 144th street muthamil nagar in div-35, unit-9, zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/29581,Roads,Completed,ND-TONDIARPET,35,978000,"Providing street name board thermoplast and reflectors in 143 142 135 193 179 129 177 130 131 132 133 128 127 125 124th street muthamil nagar in div-35, unit-9, zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/29587,Roads,Completed,ND-TONDIARPET,35,971000,"Providing street name board thermoplast and reflectors in 123 122 121 120 119 118 117 116 115 114 112 113 111 162 163 196th street muthamil nagar in div-35, unit-9, zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/29595,Roads,Completed,ND-TONDIARPET,35,970000,"Providing street name board thermoplast and reflectors in 191 192 164 153 155 176 126 muthamil nagar ambedkar 2nd lane ambedkar street (tamil horzon colony)in div-35, unit-9, zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/29597,Roads,Completed,ND-TONDIARPET,35,966000,"Providing name board thermoplast and reflectors in muthamil nagar west avenue road( from south avenue to ambedkar street), west avenue road(from north avenue to 61st street), Muthamil nagar South Avenue Road (From West Avenue to Masqu ),Muthamil nagar South Avenue Road (From T.H.Road to Masqu ) EVR Periyar Salai (Kodungaiyur),Cauvery Salai Main Road in div-35, unit-9, zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/29849,Roads,Completed,ND-TONDIARPET,35,970000,"Providing street name boards in Manvazhar street Nayanar street Rajavelu street Kumaran street Selva perumal koil street Sathiyavani muthu street( Chinandi Madam ) CSI School street N.v.n street in div-35, u-9,z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/29999,Footpath,Completed,ND-TONDIARPET,37,475000,"CONSRTUCTION OF PEDESTAL AND FIXING OF SINTEX TANK AT KDG FOR FIRE FIGHTING TO ZONE-9,WRITING NAME BOARDS AND PAINTING FOR (ZONES-3,4,5,6,7,8 &9) IN DN-37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30003,Roads,Completed,ND-TONDIARPET,37,998000,"CONSRTUCTION OF PEDESTAL AND FIXING OF SINTEX TANK AT KDG FOR FIRE FIGHTING TO ZONE-3,ZONE-4,ZONE-5 IN DN-37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30004,Roads,Completed,ND-TONDIARPET,37,998000,"CONSRTUCTION OF PEDESTAL AND FIXING OF SINTEX TANK AT KDG FOR FIRE FIGHTING TO ZONE-6,ZONE-7 AND ZONE-8 IN DN-37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30031,Roads,Completed,ND-TONDIARPET,40,560000,"Improvement to Bin and Transformer at Various Streeets in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30035,Roads,Completed,ND-TONDIARPET,44,590000,"Relaying BT Road at Udayakumar Street in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30039,Footpath,Completed,ND-TONDIARPET,40,890000,"Improvements to Foot Path at Kamaraj Street in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30040,Footpath,Completed,ND-TONDIARPET,40,999000,"Improvements to Foot Path at AA Scheme Road in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30043,Footpath,Completed,ND-TONDIARPET,40,998000,"Improvements to Foot Path at AE Koil Street (From Kamaraj Street to Periyar Park) in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30044,Footpath,Completed,ND-TONDIARPET,40,910000,"Improvements to Foot Path at AE Koil Street (From Kamaraj Street to Om Sakthi Vinayagar Koil) in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30046,Footpath,Completed,ND-TONDIARPET,40,999000,"Improvements to Foot Path at Kamaraj Street (From AE Koil Street to AA Scheme Road) in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30052,Footpath,Completed,ND-TONDIARPET,40,647000,"Improvements to Foot Path at Vaithyanathan Street (South Side) in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30056,Footpath,Completed,ND-TONDIARPET,40,346000,"Removing & Fixing IRC Kerbs(North & South) and Improvements to Foot Path at Seniamman Koil Street(Junction Of Old Vaithyanathan & New Vaithyanathan Street) in Dn-40,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30190,Buildings,Completed,ND-TONDIARPET,42,531000,"ATTENDING SPECIAL IMPROVEMENTS (THESE BLOCKS COMES UNDER TRAINING CENTER) TO TOILET BLOCKS IN 4TH BLOCK AND OTHER IMPROVEMENTS IN CPS AND C.HR.S.S AT C-KALYANAPURAM IN DN-46,U-11,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/30221,Roads,Completed,ND-TONDIARPET,43,995000,"Improvement Works at Thiruvalluvar 1st to 4th Street,Tandiar nagar 1st to 7th Street,St.Xavier Street,S.N.Chetty Streeet 8th Lane,Puthumanaikuppam Main street and1st Street in Dn-43,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30355,Footpath,Completed,ND-TONDIARPET,42,410000,"Improvements to Footpath at kailasham street in Dn-42, Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30366,Footpath,Completed,ND-TONDIARPET,42,999000,"Improvements to Footpath at Seniamman Koil street in Dn-42,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30377,Footpath,Completed,ND-TONDIARPET,42,965000,"Improvements to footpath at kailasham street (Left Side) in Dn-42,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30634,Roads,Completed,ND-TONDIARPET,34,995000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) FOR ROAD PATCH WORK AT VARIOUS STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30635,Storm Water Drain,Completed,ND-TONDIARPET,34,996000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) IN STORM WATER DRAIN AT VARIOUS STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30696,Buildings,Completed,ND-TONDIARPET,37,990000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) IN ALL CORPORATION BUILDINGS IN DN-37,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30705,Roads,Completed,ND-TONDIARPET,39,999000,"REPAIRS AND IMPROVEMENT TO ORPHANAGE BUILDING GROUND FLOOR AT VEERARAGAVAN ROAD CHERIAN NAGAR IN DN-39, UNIT-10,ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/30706,Roads,Completed,ND-TONDIARPET,39,999000,"REPAIRS AND IMPROVEMENT TO ORPHANAGE BUILDING FIRST FLOOR AT VEERARAGAVAN ROAD, CHERIAN NAGAR IN DN-39, UNIT-10,ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/30707,Roads,Completed,ND-TONDIARPET,37,995000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) FOR ROAD PATCH WORK AT VARIOUS STREET IN DN-37,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30711,Storm Water Drain,Completed,ND-TONDIARPET,37,996000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) IN STORM WATER DRAIN AT VARIOUS STREET IN DN-37,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30712,Roads,Completed,ND-TONDIARPET,36,990000,"Providing Street Name Board At S.A Colony 1st Street to S.A Colony 10th Street And S.A Colony 7th Street 1st Cross lane to S.A Colony 7th Street 4th Cross lane And S.A Colony 8th Street 1st Cross lane to S.A Colony 8th Street 4th Cross lane And S.A Colony 9th Street 1st Cross lane to S.A Colony 9th Street 7th Cross lane And S.A Colony Karimedu 1st Street, S.A Colony Karimedu 2nd Street And S.A Colony Karimedu 1st Cross Street, S.A Colony Karimedu 2nd Cross Street in Div-36, U-9, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30713,Footpath,Completed,ND-TONDIARPET,38,205000,"Improvement to FootPath at Ilaiya Mudhali Street(From Kailasham st to Vaithyanathan Bridge Slope) in Dn-38,Unit-09,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30714,Roads,Completed,ND-TONDIARPET,36,990000,"Providing Street Name Board At Gandhi Nagar 1st Street to 8th Street And Pudhu Nagar 1st Street to 5th Street And Pudhu Nagar 1st Cross Street to Pudhu Nagar 3rd Cross Street And Karunanthi Salai 8th Street And Salaima Nagar 1st Street to 6th Street Div-36, U-9, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30715,Roads,Completed,ND-TONDIARPET,36,990000,"Providing Street Name Board Vivekanatha 1st Street, Vivekanatha 2nd Street, Visalakshi Street, Veeramuniyar Street, Kambar Street, V.V Giri Street, Tholakappiyar Street, Sanji Gandhi Street, Park Street, Nakkiran Street, Appar Street, Avviyar Street, Kalamegam Street, Puzhalangthi Street, Nandanar Street, Manikavasakar Street, Gandhi Street, Eswari Street, T.V.K Street, 1st West Main Road, And 2nd West Main Road in Div-36,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30717,Roads,Completed,ND-TONDIARPET,39,998000,"FORMING FOOTPATH AT NORTH TERMINUS ROAD ( NORTH SIDE FROM T H ROAD JUNCTION TO 260 M CHAINAGE) IN DN-39, UNIT-10 ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/30723,Roads,Completed,ND-TONDIARPET,39,734000,"FORMING FOOTPATH AT NORTH TERMINIOUS ROAD ( NORTH SIDE AND SOUTH SIDE ) IN DN-39, UNIT-10 ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/30747,Parks,Completed,ND-TONDIARPET,45,840000,"ANNUVAL MAINTENANCE OF DESIKANANDAPURAM PARK,VYASRARNAGAR PARK & KASTHURI BAI GANDHI PARK (ONE YEAR) IN DIV 45,UNIT--11,ZONE -4",Own Sources,4,2015-16,2016-17 ND/2015-16/30769,Storm Water Drain,Completed,ND-TONDIARPET,36,990000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) IN STORM WATER DRAIN AT VARIOUS STREET IN DN-36,U-9,Z-4",Own Sources,4,2015-16,2017-18 ND/2015-16/30771,Buildings,Completed,ND-TONDIARPET,36,990000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) IN ALL CORPORATION BUILDINGS IN DN-36,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30773,Roads,Completed,ND-TONDIARPET,36,990000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) FOR ROAD PATCH WORK AT VARIOUS STREET IN DN-36,U-9,Z-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/30804,Roads,Completed,ND-TONDIARPET,37,996000,"ESTIMATE FOR CARRYING OUT FOR ROAD PATCH WORK AT VARIOUS STREETS IN DIV-35,UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30809,Buildings,Completed,ND-TONDIARPET,35,998000,"ESTIMATE FOR CARRYING OUT PEPAIRS WORKS IN VARIOUS BUILDING IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30815,Storm Water Drain,Completed,ND-TONDIARPET,35,998000,"ESTIMATE FOR CARRYING OUT FOR PEPARIS WORK IN STORM WATER DRAIN AT VARIOUS STREET IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30824,Buildings,Completed,ND-TONDIARPET,35,985000,"Providing stair case for Laboratory in Chennai High School Kamaraj Salai in div-35, unit-9, zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30827,Buildings,Completed,ND-TONDIARPET,42,221000,"Dismantling at Zone Annexure Building in Dn-42,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30834,Roads,Completed,ND-TONDIARPET,36,842000,"Proviiding Street Name Board Thermoplastic and Reflectors At Dr. Radha Krishnan Salai, Vadivudaiamman Street, Valmeegi Street, 10th West Cross Street And West Service Road 14th West Cross Street And 17th West Cross Street in DN-36 U-09 Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/30835,Roads,Completed,ND-TONDIARPET,36,833000,"Proviiding Street Name Board Thermoplastic and Reflectors At T.V.K 1st Link Road, T.V.K 1st Link Road (T.V Nagar), T.V.K 1st Link Road Extension Vasugi Nagar 2nd Street to Vasugi Nagar 7th Street in DN-36 U-09 Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/30836,Roads,Completed,ND-TONDIARPET,35,930000,"Providing Name board in K.k.d.nagar 2nd block 6th street,K.k.d.nagar 2nd block 7th street,K.k.d.nagar 2nd block 1st main road 1st lane,K.k.d.nagar 2nd block 2nd street,K.k.d.nagar 2nd block 5th lane,K.k.d.nagar 2nd main road,K.k.d.nagar 3rd block 1st lane,K.k.d.nagar 3rd block 2nd lane,K.k.d.nagar 3rd block 3rd cross street,K.k.d.nagar 3rd block 4th street,K.k.d.nagar 3rd main road in div-35, unit-9, zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30839,Roads,Completed,ND-TONDIARPET,36,800000,"Providing Street Name Board At Karunanthi Salai 1st Street to Karunanthi Salai 17th Street , Karunanthi Salai Main Street,Rajivigandi Street Div-36, U-9, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30842,Roads,Completed,ND-TONDIARPET,36,750000,"Providing Street Name Board At Indira Gandhi Nagar 1st Street, Indira Gandhi Nagar 2nd Street And Salaima Nagar 1st Street to Salaima Nagar 6th Street And Bharathi Nagar 1st Street to Bharathi Nagar 5th Street, Bharathi Nagar Main Street in Div-36, U-9, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30850,Roads,Completed,ND-TONDIARPET,37,268000,"Providing name board in Debar Nagar 10th 11th, Dhamodar Nagar Link Road,JJ Nagar Main Road, Dhamodar Nagar Link Road in div-37 , u-09 , z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/30851,Roads,Completed,ND-TONDIARPET,37,858600,"Providing name board in Dhamodar Nagar 5th 6th 7th 8th, Debar Nagar 5th 6th 7th 8th 9th, MGR Nagar 6th cross street 5th 6th, Udayasuriyan 5th 6th 7th 8th 9th, JJ Nagar 5th 6th 7th 8th in div-37 , u-09 , z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/30852,Roads,Completed,ND-TONDIARPET,37,939000,"Providing name board in Dhamodar Nagar 1st Cross 1st 2nd 3rd 4th, Debar Nagar 1st 2nd 3rd 4th, MGR Nagar 1st 2nd 3rd 4th, Udayasuriyan 1st 2nd 3rd 4th, JJ Nagar 1st 2nd 3rd 4th in div-37 , u-09 , z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/30853,Roads,Completed,ND-TONDIARPET,37,967000,"Providing name board thermoplast and reflectors in Sannadhi Street , Lakshmi Street , Navoroji Street , Srinivasan 2nd Lane , Palani Street , Pathmavathy Street , Gandhi Street in div-37 , u-09 , z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/30854,Roads,Completed,ND-TONDIARPET,37,674000,"Providing name board thermoplast and reflectors in Ganapathy Street , Ganapathy Extension , Eswaran Street , Jawahar 1st Lane , Jawahar 2nd Lane , Jawahar 1st Street in div-37 , u-09 , z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/30970,Roads,Completed,ND-TONDIARPET,39,999000,"REPAIRS AND IMPROVEMENT TO CHENNAI HIGH SCHOOL AT T H ROAD IN DN-39, UNIT-10, ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/30971,Roads,Completed,ND-TONDIARPET,39,998000,"REPAIRS AND IMPROVEMENT TO HEALTH POST AT CHERIAN NAGAR IN DN -39, UNIT-10, ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/30979,Roads,Completed,ND-TONDIARPET,44,970000,"PROVIDING AND FIXING STREET NAME BOARD FURNITURE AT VARIOUS STREET (UNDER WARD MEMBER DEVELOPMENT SCHEME 2015-16) IN DIV-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/30981,Roads,Completed,ND-TONDIARPET,41,990000,"Improvement To Foot path at Ennor High road and Manali Salai in ward-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30982,Storm Water Drain,Completed,ND-TONDIARPET,41,620000,"Construction of Storm Water Drain and Widening the Road at MGR Nagar Canal road in Ward-41, unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/30999,Storm Water Drain,Completed,ND-TONDIARPET,39,890000,"Improvement to Centre Median and Foothpath at T.H Road and Cross road in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31001,Roads,Completed,ND-TONDIARPET,41,998000,"Improvement to Foothpath and Centre Median at S.N Chetty Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31003,Roads,Completed,ND-TONDIARPET,44,727000,"Relaying CC Road at Vinayakar Koil Street in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31005,Roads,Completed,ND-TONDIARPET,39,620000,"Providing Patches and Speed breaker Irusappa Street, Cherian Nagar, Nammaiya Street, Desiya Nagar, Ashok Nagar in War-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31006,Roads,Completed,ND-TONDIARPET,44,727000,"Relaying CC Road at Vinayakar Koil Lane in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31011,Roads,Completed,ND-TONDIARPET,44,855000,"Relying BT Road at Panner Selvam Street in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31012,Roads,Completed,ND-TONDIARPET,44,426000,"Relaying BT Road at Padasalai Street in Dn-44, Unit-11, Zone-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/3104,Buildings,Completed,ND-TONDIARPET,36,307000,"Construction Of Compound Wall Work At S.A Colony 6th Street in DN-36, Unit-9, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31111,Buildings,Completed,ND-TONDIARPET,34,987000,"PROVIDING GRILL AND REPAIRS WORK AT SEETHARAM NAGAR IN DN - 34, UNIT - 9, ZONE - 4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31112,Buildings,Completed,ND-TONDIARPET,34,973000,"PROVIDING GREENERY ARRANGEMENTS (GRASS & TREE PLANTATION) , PLUMBING AND OTHER IMPROVEMENT WORKS AT SEETHARAM NAGAR BURIAL GROUND IN DN - 34, UNIT - 9, ZONE - 4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31113,Roads,Completed,ND-TONDIARPET,34,600000,"IMPROVEMENTS TO THE EXISTING BURIAL GROUND AT SITARAM NAGAR IN DN-34, UNIT-9, ZONE=4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31121,Parks,Completed,ND-TONDIARPET,38,570000,"ANNUAL MAINTENANCE OF NERU NAGAR PARK IN DN.38,UNIT-10,ZONE-04.(BY QUALIFIED HORTICULTURIST ONLY)",Own Sources,4,2015-16,2019-20 ND/2015-16/31122,Parks,Completed,ND-TONDIARPET,38,790000,"SECURITY ARRANGEMENTS TO NERU NAGAR PARK IN DN.38,UNIT-10,ZONE-04.",Own Sources,4,2015-16,2019-20 ND/2015-16/31124,Parks,Completed,ND-TONDIARPET,38,600000,"WATER LORRY ARRANGEMENTS TO NERU NAGAR PARK IN DN.38,UNIT-10,ZONE-04.",Own Sources,4,2015-16,2017-18 ND/2015-16/31208,Buildings,Completed,ND-TONDIARPET,40,797000,"Urgent modification works and improvements to footpath around the Community centre at Tsunami quarters in div-40,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/3121,Roads,Completed,ND-TONDIARPET,45,999000,"ROAD WIDENING TO CLINIC ROAD USING INTERLOCKING PAVER BLOCKS IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31238,Buildings,Completed,ND-TONDIARPET,40,931000,"Improvements works to community centre at mangammal thottam in div-40,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31242,Roads,Completed,ND-TONDIARPET,38,825000,"Improvements to foot path and Providing belmouth at ellaya street in div-38 ,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31245,Roads,Completed,ND-TONDIARPET,40,663000,"Improvements to footpath and centre median at TH Road in div-40,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31248,Buildings,Completed,ND-TONDIARPET,46,550000,"ATTENDING SPECIAL IMPROVEMENTS (THESE BLOCKS COMES UNDER TRAINING CENTER) TO TOILET BLOCKS IN 2ND BLOCK AND OTHER IMPROVEMENTS IN C.HR.S.S AT C-KALYANAPURAM IN DN-46,U-11,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/31249,Buildings,Completed,ND-TONDIARPET,46,530000,"ATTENDING SPECIAL IMPROVEMENTS TO TOILET BLOCKS IN CHENNAI MIDDLE SCHOOL AT MOORTINGAR STREET IN DN-46,U-11,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/31257,Electrical,Completed,ND-TONDIARPET,41,240000,"Additional Work to Multipurpose Hall at Govidasamy Nagar in Ward-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31333,Buildings,Completed,ND-TONDIARPET,41,935000,"Improvement to S.I Room AND other Improvements to Footpath at J.J Nagar in Ward-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31335,Roads,Completed,ND-TONDIARPET,38,700000,"REPAIRS AND IMPROVEMENT TO FOOTPATH AT ILAYA MUDALI STREET IN DN-38, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31358,Buildings,Completed,ND-TONDIARPET,43,814000,"Raising Manhole and Bin Painting at Pudumanaikuppam 1to7 and Vinayagapuram 1to12 Street Location in DN-43 U-10,Z-04",Own Sources,4,2015-16,2016-17 ND/2015-16/31399,Buildings,Completed,ND-TONDIARPET,46,570000,"ATTENDING SPECIAL IMPROVEMENTS (THESE BLOCKS COMES UNDER TRAINING CENTER) TO TOILET BLOCKS IN 1ST AND 3RD BLOCKS AND OTHER IMPROVEMENTS IN CPS AND C.HR.S.S AT C-KALYANAPURAM IN DN-46,U-11,Z-04",Own Sources,4,2015-16,2018-19 ND/2015-16/31401,Buildings,Completed,ND-TONDIARPET,46,580000,"ATTENDING SPECIAL CONSTRUCTION OF GATES AND GATE PILLER AND OTHER IMPROVEMENTS IN CHENNAI MIDDLE SCHOOL AT MOORTINGAR STREET IN DN-46,U-11,Z-04",Own Sources,4,2015-16,2018-19 ND/2015-16/31408,Roads,Completed,ND-TONDIARPET,44,745000,"RELAYING CC ROAD AT MOHAMED ISMAIL STREET IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31459,Roads,Completed,ND-TONDIARPET,44,998000,"SUPPLYING AND LAYING THERMO PLASTIC PAINT, SUPPLYING AND FIXING STUDS, RAISING MANHOLE DOORS & ETC., AT VARIOUS STREET IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31460,Roads,Completed,ND-TONDIARPET,44,997000,"SUPPLYING AND LAYING THERMO PLASTIC PAINT, SUPPLYING AND FIXING STUDS, RAISING MANHOLE DOORS & ETC., AT VARIOUS STREET IN DN-44, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31468,Roads,Completed,ND-TONDIARPET,39,975000,"Laying Cement Concerte road Widing at Avoor Muthiah, Venketasan Ali Street, Washer Varadappa Street, in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/3147,Buildings,Completed,ND-TONDIARPET,35,990000,"PROPOSED DAY TO DAY REPAIR (PETTY) WORK IN VARIOUS BUILDINGS IN DN-35, U-9, Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31470,Roads,Completed,ND-TONDIARPET,39,980000,"Laying Cement Concerte road Widing at Veerargavan Road, Nammaiya Maistry Street, in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31472,Roads,Completed,ND-TONDIARPET,39,980000,"Laying Cement Concerte road Widing at Poondi Thangammal Street, Butchammal Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31483,Buildings,Completed,ND-TONDIARPET,39,980000,"Construction of Safety Wall around Transformer with S.S pipe at S.N Chetty Street, Market Farm Street, Washer Varadappa (M) in Ward-39, Unit-10, Zone-5",Own Sources,4,2015-16,2016-17 ND/2015-16/31514,Roads,Completed,ND-TONDIARPET,39,999000,"Laying Cement Concerete Road at Market Farm 8th Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31515,Buildings,Completed,ND-TONDIARPET,39,950000,"Improvement to CPS School at Irusappa Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31522,Road Cut,Completed,ND-TONDIARPET,43,507000,"Restoration of road cut made (Pollution Control Board) at V.P Koil Street and T.H Road in DN-43,U-10,Z-04",Own Sources,4,2015-16,2017-18 ND/2015-16/31613,Electrical,Completed,ND-TONDIARPET,47,903700,"Electrification Work in Chennai Middle School and primary School at Harinaryanapuram in Division 47, Zone IV",Own Sources,4,2015-16,2019-20 ND/2015-16/31621,Electrical,Completed,ND-TONDIARPET,47,812400,"Electrification Work at Meenambal Nagar Hospital Provision of Tube Light, Fan, Plug Point etc in Meenambal Nagar Hospital in Division 47, Unit 11, Zone IV",Own Sources,4,2015-16,2019-20 ND/2015-16/31658,Roads,Completed,ND-TONDIARPET,40,999000,"RELAYING OF THE BT ROAD BY PAVER FINISHER AT SENIAMMAN KOIL STREET IN DN-40,U-10,Z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/31660,Roads,Completed,ND-TONDIARPET,40,984000,"RELAYING OF THE BT ROAD BY PAVER FINISHER AT VOC NAGAR MAIN ROAD IN DN-40,U-10,Z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/31661,Roads,Completed,ND-TONDIARPET,40,280000,"RELAYING OF THE BT ROAD BY PAVER FINISHER AT JN OF SENIAMMAN KOIL STREET AND JN OF VOC NAGAR MAIN ROAD IN DN-40,U-10,Z-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/31733,Footpath,Completed,ND-TONDIARPET,38,595000,"Improvents to FootPath at Nehru Nagar in Dn-38,Unit-09,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31737,Parks,Completed,ND-TONDIARPET,37,950000,"PROPOSED FORMATION OF PARK AT MULLAI NAGAR BURIGAL GROUND IN DN.37,UNIT-9,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31738,Parks,Completed,ND-TONDIARPET,37,880000,"SUPPLYING AND PROVIDING RED EARTH, MANURE AND G2 GRASS AT MULLAI NAGAR BURIGAL GROUND PARK IN DN.37,UNIT-9,ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/31741,Electrical,Completed,P-Parks and Playfields,47,99200000,"Proposed Formation of ECO park in Bharathy Nagar at Chennai Div-47, Unit-11, Zone-4.",Own Sources,4,2015-16,2020-21 ND/2015-16/31822,Footpath,Completed,ND-TONDIARPET,43,996000,"IMPROVEMENTS TO FOOTPATH AT SURIYA NARAYANA ROAD WEST SIDE (Reach-1) FROM VEDAPARRI GROUND TO JEEVARATHINAM ROAD IN Dn-43,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31830,Footpath,Completed,ND-TONDIARPET,43,996000,"IMPROVEMENTS TO FOOTPATH AT SURIYA NARAYANA ROAD WEST SIDE (Reach-2) FROM JEEVARATHINAM ROAD TO BURIAL GROUND IN Dn-43,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31845,Footpath,Completed,ND-TONDIARPET,43,997000,"IMPROVEMENTS TO FOOTPATH AT SURIYA NARAYANA ROAD EAST SIDE (Reach-2) FROM JEEVARATHINAM ROAD TO DIVISION OFFICE IN Dn-43,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31851,Footpath,Completed,ND-TONDIARPET,43,995000,"IMPROVEMENTS TO FOOTPATH AT SURIYA NARAYANA ROAD EAST SIDE (Reach-1) FROM OPPOSITE BURIAL GROUND TO JEEVARATHINAM ROAD IN Dn-43,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31852,Roads,Completed,ND-TONDIARPET,43,958000,"IMPROVEMENTS TO TRAFFIC ISLAND IN T.H ROAD NEAR APPOLLO HOSPITAL AND TRANSFORMER FENCING WALL WITH S.S HAND RAIL IN SURIYA NARAYANA ROAD IN Dn-43,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31866,Roads,Completed,ND-TONDIARPET,38,982000,"IMPROVEMENTS TO TRAFFIC ISLAND NEAR JUNCTION OF VAITHIYANATHAN BRIDGE IN Dn-38,U-10,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31976,Roads,Completed,ND-TONDIARPET,37,984000,"PROVIDING STREET NAME BOARD AT KANNADHASAN NAGAR IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/31977,Roads,Completed,ND-TONDIARPET,37,984000,"PROVIDING STREET NAME BOARD AT KRISHNAMOORTHY NAGAR IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/32095,Buildings,Completed,ND-TONDIARPET,40,834000,"Providing Aluminium Partition and Drainage Arrangements to Community Centre at Tsunami Quarters in Div - 40, Unit - 10, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/32096,Buildings,Completed,ND-TONDIARPET,42,430000,"Providing Portable toilet 2 nos for Women with Water Tank 2000lt on Rental Basis and Maintenance for One Year at Kailasam Huts in Dn-42,Unit-10,Zone-04",Own Sources,4,2015-16,2018-19 ND/2015-16/32097,Buildings,Completed,ND-TONDIARPET,42,972000,"mprovements to Main Building ( Third Floor and Auditorium ) CHSS at 540 TH Road in Div - 42, Unit - 10, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/32099,Buildings,Completed,ND-TONDIARPET,42,993000,"Improvements to Public Conveniance inside Dhobhikhana at Kothandaraman Street in Div - 42, Unit - 10, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/32100,Roads,Completed,ND-TONDIARPET,42,765000,"Laying CC Road by RMC to inside the Dhobikhana at Kothandaraman Street in Div - 42, Unit - 10, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/32300,Electrical,Completed,ND-TONDIARPET,43,998000,"Replace of Copper Wire and Panel Board in C.D.H.Out Patient Ward and Old Ward at C.D.H in Division 43, Zone IV",Own Sources,4,2015-16,2017-18 ND/2015-16/32303,Roads,Completed,ND-TONDIARPET,40,120000,"Improvements to Island at T.H.Road in DN -40, Unit -10, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/32534,Roads,Completed,ND-TONDIARPET,37,997000,"Laying Bitumen Concrete Road by Paver Finish at mkb nagar 8th cross in Div-37, Unit-9, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/32548,Roads,Completed,ND-TONDIARPET,39,585000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT KANNU STREET IN DN -39 UNIT-10, ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/32552,Roads,Completed,ND-TONDIARPET,39,997000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AND TOILET BLOCK WASHER VARADHAPPA STREET IN DN-39, UNIT-10,ZONE-4",Own Sources,4,2015-16,2017-18 ND/2015-16/32580,Roads,Completed,ND-TONDIARPET,37,999000,Widening the existing C.C Road in between S.W.D and the existing Road @ Sathyamurthy Nagar Main Road West side from North Avenue to Central Avenue in Dn-37; Unit-9 Zone-4,Own Sources,4,2015-16,2017-18 ND/2015-16/32581,Roads,Completed,ND-TONDIARPET,37,999000,Widening the existing C.C Road in between S.W.D and the existing Road @ Sathyamurthy Nagar Main Road East side from North Avenue to Central Avenue in Dn-37; Unit-9 Zone-4,Own Sources,4,2015-16,2016-17 ND/2015-16/32591,Storm Water Drain,Completed,ND-TONDIARPET,37,377000,"Providing Silt Catch Pit @ Sathiya Murthy Nagar Main Road [From North Avenue To Central Avenue ] West Side in Dn-37; unit-9, Zone-4",Own Sources,4,2015-16,2018-19 ND/2015-16/32886,Buildings,Completed,ND-TONDIARPET,37,850000,"PAINTING AND WRITING LETTERS TO NEW COMPACTOR BIN AT VARIOUS PLACES IN DIV-34 TO 37 , U-9 ,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/32896,Buildings,Completed,ND-TONDIARPET,37,990000,"FORMATION OF ENTRANCE GATE FOR MULLAI NAGAR BURIAL GROUND IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33018,Electrical,Completed,ND-TONDIARPET,38,918300,"Provision of 20 Nos. of 6 Mtr Street Lamp Post with Hot dip galvanising with Single bracket with 26 Nos of 40W LED Fitting in Newly formed Park at Nehru Nagar Main Street in Dn:38, Zone IV.",Own Sources,4,2015-16,2019-20 ND/2015-16/33069,Storm Water Drain,Completed,ND-TONDIARPET,47,596000,"Desilting of flood stagnation area by using 60 HP Motor pump at Meenambal Nagar, Ambedkar Nagar and CB Road in Div- 47 Unit-11 Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/33131,Footpath,Completed,ND-TONDIARPET,42,433000,"Painting road side park & PC compound wall,transformer fencing, centermedian and foot path at S.N Chetty street,senniammankovil street and T H road in ward.42 &43 unit.10 zone.4",Own Sources,4,2015-16,2016-17 ND/2015-16/33191,Roads,Completed,ND-TONDIARPET,40,756000,"Providing wet mix macadam for road formation inside P.W.D Quaters in Dn-40,U-10,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33192,Roads,Completed,ND-TONDIARPET,40,995000,"Providing colour washing and other improvement works in Kamarajar salai and Ilaya street in Dn-40,U-10,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33198,Storm Water Drain,Completed,ND-TONDIARPET,41,847000,"Dewatering of Flood Stagnation of Area by Using 52.50 to 60.00HP Motor at Parthasarathy Street, Marimuthu Street, Kumaran Nagar, M.G.R Nagar in Dn-41 and Senniamman Nagar Huts, Kailasam Street in Dn-42, Unit-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/33199,Parks,Completed,ND-TONDIARPET,42,990000,"PROVIDING SECURITY ARENGEMENTS IN VARIOUS PARKS AT THANTHIPERIYAR PARK, CROSS ROAD PARK, JEEVA PARK, RETTAI KZHIL PARK AND THIYAGARAYA PARK IN DN 40 & 42, U-10, Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33258,Footpath,Completed,ND-TONDIARPET,43,707000,"Improvement to Footpath at Kummalamman Koil Street ward-43, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33260,Roads,Completed,ND-TONDIARPET,43,998000,"Improvement to Footpath at Jeevarathinam Salai and Varadharaja Perumal Koil Street in ward-43, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33369,Roads,Completed,ND-TONDIARPET,34,996000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 1st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33370,Roads,Completed,ND-TONDIARPET,34,996000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33372,Roads,Completed,ND-TONDIARPET,34,600000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 7th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33377,Roads,Completed,ND-TONDIARPET,34,570000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 8th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33379,Roads,Completed,ND-TONDIARPET,34,845000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 9th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33381,Roads,Completed,ND-TONDIARPET,34,996000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 10th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/33435,Roads,Completed,ND-TONDIARPET,34,990000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 11th STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33436,Roads,Completed,ND-TONDIARPET,34,997000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 12th STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33437,Roads,Completed,ND-TONDIARPET,34,997000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 15th STREET IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33497,Buildings,Completed,ND-TONDIARPET,47,998000,CONSTRUCTION OF CREACH BUILDIND AT BHARATHI NAGAR 6TH STREET NEAR N N M P SHED IN DN 47 U 11 Z 4,Own Sources,4,2015-16,2016-17 ND/2015-16/33609,Roads,Completed,ND-TONDIARPET,40,998000,"Forming foot path and improvements to foot path and widening the portion along PWD Quarters compound wall at kamarajar salai in div-40,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33610,Buildings,Completed,ND-TONDIARPET,43,917000,"PROVIDING ARRANGEMENTS FOR AMMA KUDI NEER CENTRE INSIDE THE CDH IN DIV-43,UNIT-10,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/33856/C,Buildings,Completed,ND-TONDIARPET,46,500000,"Annual Maintenance of Works in DN -46, Unit -11, Zone -04",Own Sources,4,2015-16,2016-17 ND/2015-16/33909,Electrical,Completed,ND-TONDIARPET,47,871000,"Provision of 62.5 KVA Generator Set in 24 Hours Maternity Hospital at Meenambal Nagar in Dn:47, Zone IV",Own Sources,4,2015-16,2019-20 ND/2015-16/3417,Roads,Completed,ND-TONDIARPET,36,950000,"Estimate for Carrying Out Petty Repair Works (Day To Day) at M.R Nagar 1st cross st To M.R Nagar 6th Cross st, T.V Nagar 1st Main Road To T.V Nagar 9th Main Road, Sharmanagar 4th Cross st To Sharmanagar 15th Cross St, Karunanithi Salai 1st st To Karunanithi Salai 11th st and Other Streets B.T Roads, and CC Roads in Dn-36, Unit-9, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/34366,Roads,Completed,ND-TONDIARPET,40,994000,"PROVIDING STREET NAME BOARDS AT KEERAI THOTTAM 1 TO 7TH STREETS, LAKSHMI COLONY, MANGAMMAL GARDEN, SIVAGAMI NAGAR IN DIV-40,UNIT-10,ZONE-4(WARD COUNCILLOR SCHEME)",Own Sources,4,2015-16,2016-17 ND/2015-16/34367,Roads,Completed,ND-TONDIARPET,40,994000,"PROVIDING STREET NAME BOARDS AT AT TSUNAMI QUARTERS 1 TO 9TH STREET, AA GARDEN MAIN ROAD AND STREETS, SENIAMMAN KOIL STREETS, AMBETHKAR NAGAR IN DIV-40,UNIT-10,ZONE-4(WARD COUNCILLOR SCHEME)",Own Sources,4,2015-16,2016-17 ND/2015-16/34370,Roads,Completed,ND-TONDIARPET,40,994000,"PROVIDING STREET NAME BOARDS AT VOC NAGAR LINK STREETS, NEW VAITHYANATHAN ROAD, OLD VAITHYANATHAN ROAD IN DIV-40,UNIT-10,ZONE-4(WARD COUNCILLOR SCHEME)",Own Sources,4,2015-16,2016-17 ND/2015-16/34371,Roads,Completed,ND-TONDIARPET,42,994000,"PROVIDING STREET NAME BOARDS ATKRISHNAPPA GARDEN,RATHINASABAPATHY STREET AND LANE,MAYOR BASUDEV1ST STREET,TSUNAMI TENEMENTS E,F,G,H,I,J BLOCKS IN DN-42, UNIT-10, ZONE-04 (WARD COUNCILLOR SCHEME)",Own Sources,4,2015-16,2016-17 ND/2015-16/34372,Roads,Completed,ND-TONDIARPET,42,994000,"PROVIDING STREET NAME BOARDS AT SENIAMMAN KOIL STREETS,THILAGAR NAGAR SLUM TENEMENTS,ANNA STREET,JEEVA STREET,A.P.GARDEN 1TO 4 STREETS IN DN-42, UNIT-10, ZONE-04 (WARD COUNCILLOR SCHEME)",Own Sources,4,2015-16,2016-17 ND/2015-16/34475,Roads,Completed,ND-TONDIARPET,45,998000,"CONSTRUCTION OF AMMA UNAVAGAM (PHASE II) AT SANJAY NAGAR (ADJ. TO MELPATTI PONNAPPAN STREET) IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/34502,Roads,Completed,ND-TONDIARPET,40,538000,"Urgent Improvements to footpath and centre median at TH Road (Eastern Side & Western Side) in div-40,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/34626,Roads,Completed,ND-TONDIARPET,39,997000,"Attending Patches at AA Scheme road in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/34676,Roads,Completed,ND-TONDIARPET,39,997000,"Attending Patches at A.E Koil street in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/34713,Roads,Completed,ND-TONDIARPET,38,997000,"Attending Patches at Ilaya Street in Ward-38, Unit-09, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/34851,Buildings,Completed,ND-TONDIARPET,39,575000,"Providing Gym Apparatus, water Supply Arrangements,and Electrifications at A.E Koil Street in Dn-39, Un-10, Zn-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/34855,Buildings,Completed,ND-TONDIARPET,47,840000,"Repairs and Improvements to Kannan Street (CMS Buddha ) School in DN -47,Unit -11,Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/34856,Buildings,Completed,ND-TONDIARPET,47,810000,"Improvements and Providing Water Supply Arrangements to Kannan Street (CMS Buddha ) School in DN -47,Unit -11,Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/34927,Buildings,Completed,ND-TONDIARPET,42,965000,"Improvements to Main Building (Ground Floor, First Floor and Second Floor) CHSS at 540, TH Road, in Div-42, Unit-10, Zone IV",Own Sources,4,2015-16,2016-17 ND/2015-16/34964,Parks,Completed,ND-TONDIARPET,42,745000,"PROVIDING SECURITY ARENGEMENTS IN VARIOUS PARKS, AT THANTHIPERIYAR PARK, CROSS ROAD PARK, JEEVA PARK,RETTAI KZHIL PARK AND THIYAGARAYA PARK IN DN-40&42, U-10, Z-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/34967,Parks,Completed,ND-TONDIARPET,40,256000,"MAINTENANCE OF THANTHAI PERIYAR PARK IN DN-40, U-10, Z-4 (6 MONTH)",Own Sources,4,2015-16,2017-18 ND/2015-16/34968,Parks,Completed,ND-TONDIARPET,40,111000,"MAINTENANCE OF THE CROSS ROAD PARK (PRINDHAVANAM)PARKIN DN-40, U-10,Z-4. (6 MONTH )",Own Sources,4,2015-16,2017-18 ND/2015-16/34970,Parks,Completed,ND-TONDIARPET,42,116500,"MAINTENANCE OF RETTAI KUZHI STREET PARK IN DN-42, U-10, Z-4",Own Sources,4,2015-16,2017-18 ND/2015-16/34971,Parks,Completed,ND-TONDIARPET,42,123000,"MAINTENANCE OF JEEVA PARK @ T.H.ROAD IN DN-42, U-10, Z-4",Own Sources,4,2015-16,2017-18 ND/2015-16/34973,Parks,Completed,ND-TONDIARPET,42,124000,"MAINTENANCE OF SIR THIYAGARAJA PARK @ T.H. ROAD IN DN-42, U-10, Z-4.",Own Sources,4,2015-16,2017-18 ND/2015-16/34991,Parks,Completed,ND-TONDIARPET,40,215000,"Maintenance of Park at Thiruvalluvar nagar Park in Ward 40, Unit 10,Zone-4.(6 MONTH)",Own Sources,4,2015-16,2017-18 ND/2015-16/34992,Parks,Completed,ND-TONDIARPET,40,342000,"Maintenance of Park at Ellaya Street Park (EMMAR Properties) in Ward 40, Unit 10,Zone-4.(6 MONTH)",Own Sources,4,2015-16,2017-18 ND/2015-16/35020,Parks,Completed,ND-TONDIARPET,40,924000,"Forming Greenary and Plants in Periyar Park at A.E. Koil Street in Dn-40,Unit-10,Zone-04.",Own Sources,4,2015-16,2017-18 ND/2015-16/35050,Storm Water Drain,Completed,ND-TONDIARPET,36,826000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT THIRUVALLUVAR NAGAR 8TH MAIN ROAD CHAINAGE 50-100m, IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/35058,Electrical,Completed,ND-TONDIARPET,43,687400,"Electrification work in Gassifier Unit Building and Office Building at Kasimedu Hindu Burial Ground at S.N Chetty Street in Dn43, Zone IV",Own Sources,4,2015-16,2019-20 ND/2015-16/35071,Storm Water Drain,Completed,ND-TONDIARPET,36,826000,"DEMOLITION & RE-CONSTRUCTION OF EXISTING STORM WATER DRAIN AT THIRUVALLUVAR NAGAR 8TH MAIN ROAD CHAINAGE 0-50m, IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/35105,Buildings,Completed,ND-TONDIARPET,48,870000,"IMPROVEMENT TO THE MULTIPURPOSE HALL @ KANNI KOVIL ST IN DN-48, U-11, Z-4.",Own Sources,4,2015-16,2018-19 ND/2015-16/35129,Buildings,Completed,ND-TONDIARPET,45,996000,"IMPROVEMENTS TO ILANGO NAGAR HOSPITAL MAIN BUILDING IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2015-16,2019-20 ND/2015-16/35130,Roads,Completed,ND-TONDIARPET,38,745000,"SUPPLYING AND INSTALATION OF E-TOILET INSIDE PATAL ROAD HIGHER SEC SCHOOL ( SET -1) IN DN -38, UNIT -10, ZONE-04",Own Sources,4,2015-16,2019-20 ND/2015-16/35137,Buildings,Completed,ND-TONDIARPET,34,990000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2016-2017)) IN ALL CORPORATION BUILDINGS IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2019-20 ND/2015-16/4108,Roads,Completed,ND-TONDIARPET,42,985000,"Raising manhole doors and Providing new doors at Seniamman koil st.,Rettai kuli st.,Rathna Sabapathy st.,Veera kutty st.,T.H road in Dn-42,U-10,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/4289,Buildings,Completed,ND-TONDIARPET,40,981000,"Improvements to existing students and teachers toilet blocks in chennai middle school at kamarajar salai in Dn-40,Unit-10,Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/5707,Roads,Completed,ND-TONDIARPET,44,900000,"LAYING ROAD BY INTERLOCKING AT SATHYAVANI MURTHY STREET IN DN-44, UNIT-11, ZONE-04",Own Sources,4,2015-16,2018-19 ND/2015-16/5854,Buildings,Completed,ND-TONDIARPET,44,980000,"CARRYING OUT PETTY REPAIRS(DAY TO DAY) IN THE FOLLOWING BUILDING SCHOOL, HOSPITAL, NNMP SHED in div - 44 Unit - 11 Zone -4",Own Sources,4,2015-16,2016-17 ND/2015-16/5872,Playfields,Completed,ND-TONDIARPET,34,995000,"RAISING THE PLAY FIELD AT BINNY NAGAR MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/5958,Buildings,Completed,ND-TONDIARPET,42,660000,"Improvements to Health post at Thilagar Nagar in Div-42,Unit-10,Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6254,Footpath,Completed,ND-TONDIARPET,37,875000,"Construction Raising of Compound wall, Filling of Earth and Foot Path in Play Ground at Debar Nagar 7th Street in Div - 37, Unit - 9, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/6359,Buildings,Completed,ND-TONDIARPET,43,305000,"Conversion of Strom Room to Common Collection Centre in Side Gym Building at S.N Chetty Street in Ward-43, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6361,Buildings,Completed,ND-TONDIARPET,43,285000,"Conversion of S.I Strom room to Arasu Cable tv room inside inside Gym Building at S.N Chetty Street in Ward-43, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6362,Buildings,Completed,ND-TONDIARPET,43,721000,"Improvement Work to Division Office and Improvements to Footpath at S.N Chetty Street in Ward-43, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6364,Roads,Completed,ND-TONDIARPET,40,553000,"Construction of Sump and Water Supply Arrangement to Ellaya Park at Ellaya Street in Ward-40, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6403,Roads,Completed,ND-TONDIARPET,37,998000,"CONSTUCTION OF PEDESTAL AND FIXING OF SINTEX TANK AT KDG FOR FIRE FIGHTING IN DN -37, UNIT -9 ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6413,Buildings,Completed,ND-TONDIARPET,44,990000,"PROVIDING WATER SUPPLY ARRANGEMENTS FOR CORPORATION VARIOUS BUILDING ( CMS, HEALTH POST, NNMP SHED) IN DN-44, U-11, Z-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/6465,Buildings,Completed,ND-TONDIARPET,35,965000,"IMPROVEMENTS TO CHILDREN PLAY (NNMP SHED CENTRE NO.12068) SPACE AT 4TH BLOCK, 4TH MAIN ROAD , MUTHAMIL NAGAR IN DIVISION-35, UNIT-9,ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6527,Buildings,Completed,ND-TONDIARPET,37,472000,"INSALATION OF NEW NAME BOARD FOR THE KODUNGAYUR DUMPING GROUND IN DIV 37, UNIT 9 ZONE 4",Own Sources,4,2015-16,2016-17 ND/2015-16/6712,Buildings,Completed,ND-TONDIARPET,39,648000,"Improvements to Toilet Block in Corporation Primary and C.H.S.S School at T.H Road in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6713,Buildings,Completed,ND-TONDIARPET,39,997000,"Improvement to Corporation High School at First Floor (West Block) in Cheriyan Nagar Main Road in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6714,Buildings,Completed,ND-TONDIARPET,39,994000,"Improvement to Corporation High School at Second Floor (West Block) in Cheriyan Nagar Main road in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6715,Buildings,Completed,ND-TONDIARPET,39,967000,"Construction of compound Wall to Chennai High School at T.H Road in Ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6717,Buildings,Completed,ND-TONDIARPET,41,993000,"Providing Safety Wall Around the Transformer at J.J Nagar A1 Street, J.J Nagar 1st Street, Valli Kalyana Mandapam, Anna Nagar, Periyar Street, Pumping Station Road,Manali Salai, Ennore Salai, Thoppai Vingeshwar Koil Street,Devi Karumariamman Koil Street, in Ward-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6718,Buildings,Completed,ND-TONDIARPET,41,679000,"Providing Safety Wall Around the Transformer at Ezhil Nagar A Block 5th Street, Ezhil Nagar A Block 4th Street, Anna Nagar karunanidhi, Ezhil Nagar B Block Street, Sivaji Nagar Main Street, Amman Koil Street, in Ward-41, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6940,Roads,Completed,ND-TONDIARPET,44,991000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DN-44,UNIT-11,ZONE-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/6960,Playfields,Completed,ND-TONDIARPET,34,980000,"REPAIRS AND IMPROVEMENTS TO PLAY FIELD AT VENKATESWARA NAGAR 3rd STREET AND JAI BALAJI NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6961,Playfields,Completed,ND-TONDIARPET,34,960000,"REPAIRS AND IMPROVEMENTS TO PLAY FIELD AT ANBU NAGAR AND S.R NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6962,Playfields,Completed,ND-TONDIARPET,34,860000,"REPAIRS AND IMPROVEMENTS TO PLAY FIELD AT VIJAYALAKSHMI NAGAR AND GANESH NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6963,Playfields,Completed,ND-TONDIARPET,34,600000,"REPAIRS AND IMPROVEMENTS TO PLAY FIELD AT THENDRAL NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6965,Parks,Completed,ND-TONDIARPET,34,990000,"REPAIRS AND IMPROVEMENTS TO PARK AT VENKATESWARA COLONY AND UNION CARBIDE COLONY IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6966,Parks,Completed,ND-TONDIARPET,34,980000,"REPAIRS AND IMPROVEMENTS TO PARK AT BINNY NAGAR AND CAVAREY NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/6979,Playfields,Completed,ND-TONDIARPET,34,960000,"REPAIRS AND IMPROVEMENTS TO PLAY FIELD AT K.K.R TOWN AND THAI NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/7002,Roads,Completed,ND-TONDIARPET,47,993000,"Road Cut Restoration Made by CMWSSB @ Bharthiyar Nagar Main Street and Sathiyamoorthy Street in DN -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/7008,Buildings,Completed,ND-TONDIARPET,47,350000,"Improvements to NNMP Shed at Meenambal Nagar ( No : 090413) in Dn.47, Unit.11, Zone.4.",Own Sources,4,2015-16,2016-17 ND/2015-16/7072,Buildings,Completed,ND-TONDIARPET,34,990000,"ESTIMATE FOR CARRYING OUT PETTY REPAIRS(DAY TO DAY-(2015-2016)) IN ALL CORPORATION BUILDINGS IN DN-34,U-9,Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/7293,Playfields,Completed,ND-TONDIARPET,36,780000,Improvements To Play Ground At Sharmanagar 9th Street in DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/7295,Playfields,Completed,ND-TONDIARPET,36,710000,Improvements To Play Ground At Sharmanagar 6th Street in DN-36 U-09 Z-04,Own Sources,4,2015-16,2016-17 ND/2015-16/7328,Buildings,Completed,ND-TONDIARPET,48,990000,"Estimate for carrying out petty repairs (Day to Day) in Corporation building at Various Street in Dn.48, Unit.11, Zone.4.",Own Sources,4,2015-16,2016-17 ND/2015-16/7330,Storm Water Drain,Completed,ND-TONDIARPET,48,940000,"Estimate for carrying out petty repairs (Day to Day) in Various Storm Water Drain in Dn.48, Unit.11, Zone.4.",Own Sources,4,2015-16,2016-17 ND/2015-16/7866,Roads,Completed,ND-TONDIARPET,43,2097000,"Laying the BT Road at St.xaviour Street (Extension) in Dn-43,u-10,z-04(l-240 w-7.5)",Own Sources,4,2015-16,2016-17 ND/2015-16/7869,Roads,Completed,ND-TONDIARPET,43,823000,"Laying BT Road at Thiruvalluvar Nagar 1st Street(M.G.R Nagar) in DN-43,U-10,Z-04(l-90,w-7.5)",Own Sources,4,2015-16,2016-17 ND/2015-16/7880,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Sigirinthapalayam 1st in DN -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2017-18 ND/2015-16/7881,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Sigirinthapalayam 5th st in DN -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2017-18 ND/2015-16/7882,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Sigirinthapalayam 6th st in DN -47, Unit -11, Zone -04.",Own Sources,4,2015-16,2017-18 ND/2015-16/7883,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Sigirinthapalayam 7th st in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7884,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC (East to West )st in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7885,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC (West to North )st in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7886,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC (North to South) st in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7887,Roads,Completed,ND-TONDIARPET,47,800000,"Relaying of Cement Concrete Road at Jeeva Nagar 6th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7888,Roads,Completed,ND-TONDIARPET,47,850000,"Relaying of Cement Concrete Road at Jeeva Nagar 5th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7889,Roads,Completed,ND-TONDIARPET,47,830000,"Relaying of Cement Concrete Road at Jeeva Nagar 4th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7891,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 7th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7893,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 9th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7894,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 10th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7913,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 11th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7914,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 12th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7915,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 13th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7916,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 14th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7917,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 15th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7918,Roads,Completed,ND-TONDIARPET,47,820000,"Relaying of Cement Concrete Road at Jeeva Nagar 16th street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7919,Roads,Completed,ND-TONDIARPET,47,650000,"Relaying of Cement Concrete Road at Jeeva Nagra 1st Street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7920,Roads,Completed,ND-TONDIARPET,47,880000,"Relaying of Cement Concrete Road at Sigirithapalayam 9th Street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7921,Roads,Completed,ND-TONDIARPET,47,880000,"Relaying of Cement Concrete Road at Sigirithapalayam 8th Street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7922,Roads,Completed,ND-TONDIARPET,47,850000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC 4th cross street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7923,Roads,Completed,ND-TONDIARPET,47,850000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC 3rd cross street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7924,Roads,Completed,ND-TONDIARPET,47,850000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC 2nd cross street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7925,Roads,Completed,ND-TONDIARPET,47,850000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC Ist cross street in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/7926,Roads,Completed,ND-TONDIARPET,47,990000,"Relaying of Cement Concrete Road at Bharathi Nagar TNSBC (South to west )st in DN -47, Unit - 11, Zone -04",Own Sources,4,2015-16,2017-18 ND/2015-16/8006,Buildings,Completed,ND-TONDIARPET,43,963000,"Improvements to fish market at cg colony in div-43 ,unit-10,zone-4",Own Sources,4,2015-16,2017-18 ND/2015-16/8008,Buildings,Completed,ND-TONDIARPET,43,904000,"Improvements to fish market at Kasipuram in div-43 ,unit-10,zone-4",Own Sources,4,2015-16,2017-18 ND/2015-16/8097,Storm Water Drain,Completed,ND-TONDIARPET,39,684000,"Improvements to existing damaged swd at Aavoor Muthiah street In ward-39, Unit-10, Zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/8109,Buildings,Completed,ND-TONDIARPET,35,989000,"IMPROVEMENTS TO GYM AT 4TH BLOCK,MUTHAMIL NAGAR IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2015-16,2016-17 ND/2015-16/8152,Roads,Completed,ND-TONDIARPET,45,425000,"Attending Cement Concrete Patch work in various roads and streets in Dn-45, unit -11, Zone - 4",Own Sources,4,2015-16,2016-17 ND/2015-16/8156,Buildings,Completed,ND-TONDIARPET,45,510000,"CONSTRUCTION OF DISABLED FRIENDLY TOILET AT GANESAPURAM MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/8160,Buildings,Completed,ND-TONDIARPET,43,579000,"Improvements to public convenience at singara velan nagar in div-43,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/8161,Buildings,Completed,ND-TONDIARPET,43,368000,"Improvements to public convenience at otthai vadai street in div-43,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/8948,Buildings,Completed,ND-TONDIARPET,36,1900000,"NEWLY CONSTRUCTION OF MULTIPURPOSE HALL BUILDING AT BHARATHI NAGAR EAST IN DIV-36, UNIT-9, ZONE-4",MLACDS,4,2015-16,2017-18 ND/2015-16/8964,Buildings,Completed,ND-TONDIARPET,36,1900000,"NEWLY CONSTRUCTION OF MULTIPURPOSE HALL BUILDING AT KARUNANITHI SALAI 8TH STREET IN DIV-36, UNIT-9, ZONE-4",MLACDS,4,2015-16,2016-17 ND/2015-16/8979,Storm Water Drain,Completed,ND-TONDIARPET,35,996000,"Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on Various Location in Division-35, Unit-09, Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/8981,Storm Water Drain,Completed,ND-TONDIARPET,34,670000,"PROVIDING SILT CATCH PIT AND VERTICAL GRATINGS IN THE EXISTING STORM WATER DRAIN AT UNION CARBIDE COLONY 14T STREET,ARUL NAGAR MAIN ROAD,SCHOOL ROAD, M.R.L COLONY 1ST STREET AND SENTHIL NAGAR 2ND STREET IN DN-34, U-9, Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/9042,Buildings,Completed,ND-TONDIARPET,43,971000,", Providing Aluminium Partition for ANM Course at CDH (Toilet block ground floor)in div-43,unit-10,zone-4",Own Sources,4,2015-16,2016-17 ND/2015-16/9050,Buildings,Completed,ND-TONDIARPET,43,981000,"Providing Aluminium Partition for ANM Course at CDH (Northrn block first floor)in div-43,unit-10,zone-4",Own Sources,4,2015-16,2017-18 ND/2015-16/9057,Buildings,Completed,ND-TONDIARPET,48,2980000,"Construction of Multi Propose Hall @ Andiyappan Street . DN -48, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/9058,Buildings,Completed,ND-TONDIARPET,48,2980000,"Construction of ICDS @ Andiyappan Street DN -48, Unit -11, Zone -04.",Own Sources,4,2015-16,2016-17 ND/2015-16/9160,Roads,Completed,ND-TONDIARPET,45,995000,"PROVIDING SILT CATCH PIT AND VERTICAL GRATINGS IN THE EXISTING STORM WATER DRAIN AT VARIOUS LOCATION IN DN-45, U-11, Z-4",Own Sources,4,2015-16,2016-17 ND/2015-16/9448,Road Cut,Completed,ND-TONDIARPET,36,69000,"RESTORATION OF ROAD CUT MADE BY TNEB ON BHARATHI NAGAR 1ST CROSS STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9450,Road Cut,Completed,ND-TONDIARPET,36,213000,"RESTORATION OF ROAD CUT MADE BY TNEB ON BHARATHI NAGAR MAIN ROAD IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9452,Road Cut,Completed,ND-TONDIARPET,36,325000,"RESTORATION OF ROAD CUT MADE BY TNEB ON PUDHU NAGAR 8TH STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9460,Road Cut,Completed,ND-TONDIARPET,36,42000,"RESTORATION OF ROAD CUT MADE BY TNEB ON THIRUGNANA SAMBANDAR STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9465,Road Cut,Completed,ND-TONDIARPET,36,213000,"RESTORATION OF ROAD CUT MADE BY TNEB ON RAJIV GANDHI NAGAR 2ND STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9467,Road Cut,Completed,ND-TONDIARPET,36,154000,"RESTORATION OF ROAD CUT MADE BY TNEB ON BHARATHIYAR STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9468,Road Cut,Completed,ND-TONDIARPET,36,42000,"RESTORATION OF ROAD CUT MADE BY TNEB ON VADIVUDAIAMMAN STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9502,Buildings,Completed,ND-TONDIARPET,35,485000,"PROVIDING AND FIXING RO PLANT FOR DRINKING WATER CHENNAI PRIMARY SCHOOL ERUKKENDCHERRY IN DN-35,UNIT-09,ZONE-04",MLACDS,4,2015-16,2016-17 ND/2015-16/9611,Road Cut,Completed,ND-TONDIARPET,36,325000,"RESTORATION OF ROAD CUT MADE BY TNEB ON SHARMANAGAR 10TH MAIN ROAD IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9613,Road Cut,Completed,ND-TONDIARPET,36,325000,"RESTORATION OF ROAD CUT MADE BY TNEB ON MR NAGAR 1ST CROSS STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9614,Road Cut,Completed,ND-TONDIARPET,36,255000,"RESTORATION OF ROAD CUT MADE BY TNEB ON VISHALAKSHI STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9616,Road Cut,Completed,ND-TONDIARPET,36,255000,"RESTORATION OF ROAD CUT MADE BY TNEB ON VISHALAKSHI 2ND CROSS STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9617,Road Cut,Completed,ND-TONDIARPET,36,538000,"RESTORATION OF ROAD CUT MADE BY TNEB ON THIRUVALLUVAR NAGAR 2ND MAIN ROAD IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9618,Road Cut,Completed,ND-TONDIARPET,36,538000,"RESTORATION OF ROAD CUT MADE BY TNEB ON THIRUVALLUVAR NAGAR 3RD MAIN ROAD IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9620,Road Cut,Completed,ND-TONDIARPET,36,538000,"RESTORATION OF ROAD CUT MADE BY TNEB ON SASTRI NAGAR 1ST STREET IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9621,Road Cut,Completed,ND-TONDIARPET,36,112000,"RESTORATION OF ROAD CUT MADE BY TNEB ON WEST 1ST MAIN ROAD IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9622,Road Cut,Completed,ND-TONDIARPET,36,42000,"RESTORATION OF ROAD CUT MADE BY TNEB ON WEST 2ND MAIN ROAD IN DIVISION-36, UNIT-9, ZONE-4",Deposit Works,4,2015-16,2016-17 ND/2015-16/9764,Buildings,Completed,ND-TONDIARPET,40,700000,"Engaging of Technical Assistant (Grade I & Grade II) to Assist the AE in Division-38,39,40,41,42,43and47 in Unit-10, Zone-04.",Own Sources,4,2015-16,2016-17 ND/2015-16/9815,Roads,Completed,ND-TONDIARPET,43,3341000,"Lating BT Road at Balakrishan Street in DN-43,U-10,Z-04(L-465M,W-6M)",Own Sources,4,2015-16,2016-17 ND/2015-16/9833,Buildings,Completed,ND-TONDIARPET,45,970000,"IMPROVEMENT TO STORM WATER DRAIN AT CLINIC ROAD FROM THE JUNCTION OF B V COLONY ROUNDANA TO CHRUCH IN DN-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/9835,Buildings,Completed,ND-TONDIARPET,45,190000,"IMPROVEMENTS TO AMMA UNAVAGAM GANESHAPURAM DN-45, UNIT-11, ZONE-4.",Own Sources,4,2015-16,2016-17 ND/2015-16/9863,Storm Water Drain,Completed,ND-TONDIARPET,36,259000,"Providing Silt Catch Pit & Vertical Gratings in the existing Storm Water Drain on Various Location (List Enclosed) in Division-36, Unit-09, Zone-04",Own Sources,4,2015-16,2016-17 ND/2015-16/9954,Buildings,Completed,ND-TONDIARPET,46,820000,CONSTRUCTION OF SECURITY ROOM AND OTHER IMPROVEMENT TO GATE AT C-KALYANAPURAM HR SEC SCHOOL IN DN-46 UNIT-11 ZONE -4,Own Sources,4,2015-16,2018-19 ND/2015-16/9956,Roads,Completed,ND-TONDIARPET,46,992000,"BEAUTIFICATION OF FOOTPATH AND FORMATION OF ROAD SIDE PARK EDGE PLANT AND GREENERY TO THE BUS STAND AT C- KALYANAPURAM IN DN 46, UNIT 11,ZONE 4",Own Sources,4,2015-16,2018-19 NE/2015-16/0184,Buildings,Completed,NE-ROYAPURAM,53,3520000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT SRINIVASAPURAM IN WARD-53, UNIT-12, ZONE-5",Earmarked Fund,5,2015-16,2016-17 NE/2015-16/0272,Buildings,Completed,NE-ROYAPURAM,53,883000,"Providing Water Supply Arrangement and Improvement to Lorry Service Station at basin Bridge Road in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0274,Buildings,Completed,NE-ROYAPURAM,53,993000,"Construction of Machanic Shed at Basin Brigde road in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0304,Footpath,Completed,NE-ROYAPURAM,59,638000,"Forming of Footpath Ellis Road (LHS) from Anna Salai (Grand park) to Bombaying Textiles in Dn-59,U-14,Z-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/0630,Buildings,Completed,NE-ROYAPURAM,62,560000,"ATTENDING PATCH WORK FOR AFPECTED PORTION AT RAJAJAJI SALAI SERVICE ROAD IN DN-60,U-13,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/0695,Roads,Completed,NE-ROYAPURAM,50,611000,"Laying of cement concrete road with RMC M30 at Jeevarathinam Nagar 1st street in Ward-50, Unit-12, Zone-V",Own Sources,5,2015-16,2017-18 NE/2015-16/0696,Roads,Completed,NE-ROYAPURAM,50,917000,"Laying of cement concrete road with RMC M30 at Jeevarathinam Nagar 2nd street in Ward-50, Unit-12, Zone-V",Own Sources,5,2015-16,2017-18 NE/2015-16/0697,Roads,Completed,NE-ROYAPURAM,50,834000,"Laying of cement concrete road with RMC M30 at Jeevarathinam Nagar 3rd street in Ward-50, Unit-12, Zone-V",Own Sources,5,2015-16,2017-18 NE/2015-16/0698,Roads,Completed,NE-ROYAPURAM,50,740000,"Laying of cement concrete road with RMC M30 at Jeevarathinam Nagar 4th street in Ward-50, Unit-12, Zone-V",Own Sources,5,2015-16,2017-18 NE/2015-16/0703,Roads,Completed,NE-ROYAPURAM,60,498000,"RELAYING THE ROAD WITH BCCMP AT METTU STREET IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0704,Roads,Completed,NE-ROYAPURAM,60,531000,"RELAYING THE ROAD WITH BCCMP AT ADIAPATHAM STREET IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0705,Roads,Completed,NE-ROYAPURAM,60,252000,"RELAYING THE ROAD WITH BCCMP AT AYYASAMY 1ST LANE IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0706,Roads,Completed,NE-ROYAPURAM,60,252000,"RELAYING THE ROAD WITH BCCMP AT AYYASAMY 2ND LANE IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0707,Roads,Completed,NE-ROYAPURAM,60,2566000,"RELAYING THE ROAD WITH BCCMP AT NARAYANAPPA STREET IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0710,Roads,Completed,NE-ROYAPURAM,60,854000,"RELAYING THE ROAD WITH BCCMP AT JAFFER SARANG 1ST LANE IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0711,Roads,Completed,NE-ROYAPURAM,60,210000,"RELAYING THE ROAD WITH BCCMP AT SUBBU STREET IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0712,Roads,Completed,NE-ROYAPURAM,60,593000,"RELAYING THE ROAD WITH BCCMP AT BARRACKS STREET IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0714,Roads,Completed,NE-ROYAPURAM,60,1020000,"RELAYING THE ROAD WITH BCCMP AT GOOMS STREET IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0715,Roads,Completed,NE-ROYAPURAM,60,881000,"LAYING THE ROAD WITH CC AT MEERALI STREET(From Angappan Street) IN DN-60, U-13, Z-5(L-65m W-8.00m)",Own Sources,5,2015-16,2016-17 NE/2015-16/0716,Roads,Completed,NE-ROYAPURAM,60,990000,"RELAYING THE ROAD WITH BCCMP AT PHILIPS STREET IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0780,Buildings,Completed,NE-ROYAPURAM,62,999000,"CONSTRUCTION OF GATE AND GATE PILLAR , TOILET ROOM IN E-SEVA MAIYAM AT ADHIKESAVALU STREET IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/0924,Storm Water Drain,Completed,NE-ROYAPURAM,55,825000,"REPAIRS AND IMPROVEMENT TO SWD AT AANAIKKONAN STREET , SEVENWELLS STREET , BARRACKS STREET , GIRIGORI STREET , ST.XAVIER STREET , AMMAN KOIL STREET , P.V.IYER STREET SUBRAMANI STREET IN WARD 55,UNIT 13, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/0925,Roads,Completed,NE-ROYAPURAM,55,428000,"PROVIDING AND LAYING CEMENT CONCRETE PATCHES AT HAZARAT STREET,,AACHARAPPAN STREET, SEVENWELLS STREET, ETC., IN WARD 55, UNIT 13, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10386,Buildings,Completed,NE-ROYAPURAM,61,998000,"SPECIAL IMPROVEMENTS TO ICDS IN URUDU SCHOOL CAMPUS AND IMPROVEMENTS TO CMS AT LANGS GARDEN ROAD IN DN-61,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/10422,Roads,Completed,NE-ROYAPURAM,56,999000,"Laying cement concrete road at shanmugaran street(from st xavier st 0m to 350m) in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10424,Roads,Completed,NE-ROYAPURAM,56,578000,"laying cement concrete road at shanmugaran street (350m to old jail road)in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10425,Roads,Completed,NE-ROYAPURAM,56,386000,"Laying cement concrete road at Pidariyar koil 1st street and lane in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10428,Storm Water Drain,Completed,NE-ROYAPURAM,56,599000,"Imrpovements to atthipata pond at salai vinagar koil street in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10435,Storm Water Drain,Completed,NE-ROYAPURAM,56,910000,"Improvements to existing srorm water drian (water sagenation at ATTHIPATTAH POND)at salai vinagar koil street in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10438,Roads,Completed,NE-ROYAPURAM,56,516000,"profile correction at thaippan street (420m to old jail road) in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10469,Buildings,Completed,NE-ROYAPURAM,58,593000,"Supplying and fixing driking water treatment plant (R O Plant) inside C H S at Rotlers Street under M.L.A.C.D Scheme 2015-2016 in Dn-58, Unit-14, Zone-5",MLACDS,5,2015-16,2017-18 NE/2015-16/10501,Buildings,Completed,NE-ROYAPURAM,61,826000,"IMPROVEMENTS TO BINNY ROAD BRIDGE FOOTPATH (BOTH SIDE) AND CENTER MEDIAN AT BINNY ROAD IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/10547,Roads,Completed,NE-ROYAPURAM,56,980000,"laying interlocking blocks both side of the road edge at Geills Street in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10548,Roads,Completed,NE-ROYAPURAM,56,990000,"laying interlocking block bothside of the roadedge at ramaswamy street in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10550,Roads,Completed,NE-ROYAPURAM,56,670000,"Laying the interlocking blocks bothside road edge portion at malayappan street in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/10552,Buildings,Completed,NE-ROYAPURAM,52,994000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS TO VARIOUS ROADS IN DN-52, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/10786,Buildings,Completed,NE-ROYAPURAM,62,300000,"PROVIDING HANDRAIL AND ELECTRICAL CONNECTION FOR E-SEVA MAIYAM AT ADHIKESAVALU STREET IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/10787,Buildings,Completed,NE-ROYAPURAM,62,887000,"SPECIAL IMPROVEMENTS TO ICDS -2NOS AT NAVALAR NEDUCHEZIAN COLONY IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/10853,Roads,Completed,NE-ROYAPURAM,49,998000,"Relaying B.T Concrete Road at Balu Street at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/10856,Roads,Completed,NE-ROYAPURAM,49,610000,"Relaying B.T Concrete Road at Venkatachalam Street at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/10859,Roads,Completed,NE-ROYAPURAM,49,629000,"Relaying B.T Concrete Road at Bala Arunachalam Streetat Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/10864,Roads,Completed,NE-ROYAPURAM,49,828000,"Relaying B.T Concrete Road at Solaiappan Street (Reach 1 ) at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/11046,Roads,Completed,NE-ROYAPURAM,49,828000,"Relaying B.T Concrete Road at Solaiappan Street (Reach 2 ) at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/11115,Buildings,Completed,NE-ROYAPURAM,52,996000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS TO VARIOUS STREETS IN DN-52, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/1136,Bridges,Completed,NE-ROYAPURAM,61,984000,"IMPROVEMENTS TO GENGU SUBWAY NORTH SIDE IN DN-61,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/1137,Bridges,Completed,NE-ROYAPURAM,61,919000,"IMPROVEMENTS TO GENGU SUBWAY SOUTH SIDE IN DN-61,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/1140,Bridges,Completed,NE-ROYAPURAM,61,886000,"IMPROVEMENTS TO FOOTPATH AT SOUTH SIDE AND PAINTING BLACK AND WHITE FOR KERB IN GENGU SUBWAY AT MAYOR RAMANATHAN ROAD IN DN-61,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/11424,Footpath,Completed,NE-ROYAPURAM,62,999000,"PAINTING BLACK AND WHITE FOR AUGUST 15TH AT DY MAYOR KABALAMOORTHY SALAI, ARUNACHALAM STREET,ADHITAHANAR SALAI, DRIVER STREET,MONTIETH LANE,EGMORE HIGH ROAD,DR.MAYOR RAMANATHAN SALAI AND PAINTING THE COMPOUND WALL AROUND MAY DAY PARK AT DY MAYOR KABALAMOORTHY SALAI IN DN-61 & 62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/11515,Roads,Completed,NE-ROYAPURAM,53,996000,"Improvement to Gym building at Bodaraja nagar and Kathpada main road in ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/11521,Roads,Completed,NE-ROYAPURAM,53,994000,"IMPROVEMENTS TO EXISTING PUBLIC CONVENIENCE AT SRINIVASPURAM 2ND STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/11559,Storm Water Drain,Completed,NE-ROYAPURAM,61,581000,"IMPROVEMENTS TO STROM WATER DRAIN IN SANTHOSH NAGAR IN VERIES LANE IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/11569,Buildings,Completed,NE-ROYAPURAM,61,131000,"IMPROVEMENTS TO PUBLIC CONVEYENCE AT SANTHOSH NAGAR IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/11573,Storm Water Drain,Completed,NE-ROYAPURAM,61,477000,"IMPROVEMENTS TO THE STROM WATER DRAIN IN PIPE LINE WORK AT RANGACHARI STREET & VARIES STREETS IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/11825,Buildings,Completed,NE-ROYAPURAM,61,850000,"IMPROVEMENTS TO STORM WATER DRAIN AND PROVIDING SOAK PIT,SILT COLLECTION TANK AND GRATINGS IN EXISTING SWD DRAIN AT VARIOUS STREET IN WARD-61,UN-14,Z-05",Own Sources,5,2015-16,2017-18 NE/2015-16/11860,Roads,Completed,NE-ROYAPURAM,49,290000,"PROVIDING CONCRETE PLATFORM FOR KEEPING BINS AT VARIOUS ROADS IN WARD 49, UNIT 12, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/11926,Roads,Completed,NE-ROYAPURAM,55,990000,"Attending profile correction UNDER WARD COUNCILLOR DEVELOPMENT SCHEME FOR THE YEAR OF 2014 -15 at Pannaikara andiappan street and Portghese church lane in Dn.55,Unit -13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/11942,Roads,Completed,NE-ROYAPURAM,55,990000,"Attending profile correction UNDER WARD COUNCILLOR DEVELOPMENT SCHEME FOR THE YEAR OF 2015.16 at Kutty(M)street (From St.Xaviers st) in Dn-55,Unit -13,Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/11943,Roads,Completed,NE-ROYAPURAM,55,990000,"Attending profile correction UNDER WARD COUNCILLOR DEVELOPMENT SCHEME FOR THE YEAR OF 2015.16 at Kutty (M) street (From seven wells street) and Ramalingam street in Dn.55,Unit -13,Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/11944,Roads,Completed,NE-ROYAPURAM,55,990000,"Attending profile correction UNDER WARD COUNCILLOR DEVELOPMENT SCHEME FOR THE YEAR OF 2015.16 at Egavalli amman street and Irusappan street in Dn-55,Unit -13,Zone - 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12199,Buildings,Completed,NE-ROYAPURAM,49,755000,"Providing Staircase and Water Supply arrangement to Gym building at Singara Garden 4th Street in ward-49, Unit-12, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/12211,Buildings,Completed,NE-ROYAPURAM,61,172000,"IMPROVEMENTS TO ANDERSON BRIDGE FOOTPATH (BOTH SIDE) AND CENTER MEDIAN AT ANDERSON BRIDGE ROAD IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/12216,Storm Water Drain,Completed,NE-ROYAPURAM,49,998000,"Improvement to SWD Drain 2 x 2 '6 at New Thandravarayan street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/12219,Storm Water Drain,Completed,NE-ROYAPURAM,49,998000,"Improvement to SWD Drain 2 x 2 '6 at Soliappan street (Reach1) in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/12224,Storm Water Drain,Completed,NE-ROYAPURAM,49,998000,"Improvement to SWD Drain 2 x 2 '6 at Kothandraman street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/12293,Roads,Completed,NE-ROYAPURAM,57,915000,"Attending WET MIX CC PACHES VARADHAPPAMUTHIYA STREET AND NATUPILLAYAR KOIL street and Various Street in Dn.57,U-13,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/12461,Electrical,Completed,NE-ROYAPURAM,59,942000,"Repairs and Improvements to Public Convenience at N.S.C Bose road in Dn-59,U-14,Z-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/12462,Electrical,Completed,NE-ROYAPURAM,59,959000,"Repairs and Improvements to Public Convenience at S.M.Nagar Main Road JN of Gandhi Nagar 6th Main Road in Dn-59,U-14,Z-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/12463,Electrical,Completed,NE-ROYAPURAM,59,860000,"Repairs and improvements to public convenience at S.M nagar Main Road from the Junction of Anna Salai in dn-59, unit-14, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/12501,Roads,Completed,NE-ROYAPURAM,62,99200,"SUPPLYING AND LAYING WETMIX AT VARIOUS STREETS IN WARD 62,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2019-20 NE/2015-16/12502,Buildings,Completed,B-Buildings,58,990000,IMPROVEMENTS TO URBAN PRIMARY HEALTH CENTER ROTLER STREET IN DIV-58 UNIT-14 ZONE-5,Own Sources,5,2015-16,2018-19 NE/2015-16/12521,Parks,Completed,NE-ROYAPURAM,58,998000,ANNUAL MAINTENANCE OF MYLADY'S PARK AT DIV-58 UNIT-14 ZONE-05 (Maintenance Period 6Month ),Own Sources,5,2015-16,2016-17 NE/2015-16/12636,Storm Water Drain,Completed,NE-ROYAPURAM,61,467000,"IMPROVEMENTS TO THE STORM WATER DRAIN IN PIPE LINE WORK AT GANDHI IRWIN ROAD PHANTHYEN ROAD IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/12721,Roads,Completed,NE-ROYAPURAM,54,630000,"Providing Interlocking paver blocks at peddu street(Eastern side) in Div-54,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12722,Roads,Completed,NE-ROYAPURAM,54,637000,"Providing Interlocking paver blocks at western side of peddu street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12724,Roads,Completed,NE-ROYAPURAM,54,987000,"Providing Interlocking paver blocks at eastern side of Amman koil street in div-54,unit-13, zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12725,Roads,Completed,NE-ROYAPURAM,54,987000,"Providing Interlocking paver blocks at northern side of Amman koil street in div-54,unit-13,zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/12744,Roads,Completed,NE-ROYAPURAM,54,466000,"Providing Interlocking paver blocks at south side of lawyer chinnathambi street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12745,Roads,Completed,NE-ROYAPURAM,54,480000,"Providing Interlocking paver blocks at north side of lawyer chinnathambi street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12746,Roads,Completed,NE-ROYAPURAM,54,608000,"Providing Interlocking paver blocks at south side of krishnappa agaraharam street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12747,Roads,Completed,NE-ROYAPURAM,54,614000,"Providing Interlocking paver blocks at north side of krishnappa agarhaarm street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12748,Roads,Completed,NE-ROYAPURAM,54,755000,"Providing Interlocking paver blocks at south side of krishnappa tank street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12749,Roads,Completed,NE-ROYAPURAM,54,755000,"Providing Interlocking paver blocks at north side of krishnappa tank street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12751,Roads,Completed,NE-ROYAPURAM,54,466000,"Providing Interlocking paver blocks at south side of Telegraph abhai street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12752,Roads,Completed,NE-ROYAPURAM,54,480000,"Providing Interlocking paver blocks at nortth side of Telegraph abhai street in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12753,Roads,Completed,NE-ROYAPURAM,54,654000,"Providing Interlocking paver blocks at south side of Telegraph abhai lane in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/12754,Roads,Completed,NE-ROYAPURAM,54,675000,"Providing Interlocking paver blocks at north side of Telegraph abhai lane in div-54,unit-13,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/1292,Buildings,Completed,NE-ROYAPURAM,51,644000,"Improvement to CPS Tamil in East Cemetry Road in Div-51,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/13267,Buildings,Completed,NE-ROYAPURAM,57,992000,"PROPOSED CONSTRUCTION OF 16TH CEREMONY HALL AT KALYANIPURAM IN VOC SALAI IN DIV-57, UN IT-13, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/13268,Electrical,Completed,NE-ROYAPURAM,61,997000,"Proposed construction of 16th Ceremony Hall at P.C.O Road, ( ward councilor development scheme fund) in Dn-61, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13271,Buildings,Completed,NE-ROYAPURAM,61,967000,ATTENTING PATCH WORK AT BOOPATHY NAGAR IN DIV-61 UNIT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/13321,Buildings,Completed,NE-ROYAPURAM,57,999000,"ADDITIONAL IMPROVEMENTS TO 16TH DAY CEREMONY HALL AT KALYANAPURAM IN DIV-57,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/13394,Buildings,Completed,NE-ROYAPURAM,53,989000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT VARIOUS LOCATIONS IN DN-53,UNIT-10, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/13396,Buildings,Completed,NE-ROYAPURAM,53,987000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT P.P.AMMAN KOIL EAST STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/13399,Buildings,Completed,NE-ROYAPURAM,53,989000,"IMPROVEMENTS TO NNMP SHED NO : 90201 AND 90202 AT WALL TAX ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/13401,Buildings,Completed,NE-ROYAPURAM,53,990000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS CORPORATION BUILDINGS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/13403,Footpath,Completed,NE-ROYAPURAM,53,989000,"IMPROVEMENTS TO NNMP SHED NO : 33603090210 and 33603090211 AT P.P.AMMAN KOIL EAST STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/13537,Roads,Completed,NE-ROYAPURAM,61,999000,"RELAYING OF THE ROAD WITH BCCMP 40mm THICK BY PAVER FINISHER AT DR. P.V. CHERIAN CRESCENT ROAD (FROM ETHIRAJ SALAI TO DOOR NO: 34) IN DIVISION-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/13538,Roads,Completed,NE-ROYAPURAM,61,999900,"RELAYING OF THE ROAD WITH BCCMP 40mm THICK BY PAVER FINISHER AT DR.P.V.CHERIAN CRESCENT ROAD (FROM DOOR NO: 34 TO DOOR NO: 26/39) IN DN-61,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/13539,Roads,Completed,NE-ROYAPURAM,61,998000,"RELAYING OF THE ROAD WITH BCCMP 40mm THICK BY PAVER FINISHER AT DR.P.V.CHERIAN CRESCENT ROAD (FROM DOOR NO: 26/39 TO INDIA TOURISM OFFICE) IN DN-61, UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/13561,Buildings,Completed,NE-ROYAPURAM,51,990000,"Construction Of Amma Unavagam in Manikandan 6th Street in Ward-51,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13562,Roads,Completed,NE-ROYAPURAM,51,990000,"Additional Works to Amma Unavagam in Mainkandan 6th Street in Ward-51,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13608,Roads,Completed,NE-ROYAPURAM,49,940000,"Relaying B.T Concetre Road at Thandaravayan Street (From Jn of Modal Mat School to Dead End) in ward-49, unit-12, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13612,Parks,Completed,NE-ROYAPURAM,50,963000,"Renovation of Park at N.R.T. Service Road in Ward-50, Unit-12, Zone-V. (Under Councillor's Ward Improvement Scheme)",Own Sources,5,2015-16,2016-17 NE/2015-16/13778,Buildings,Completed,NE-ROYAPURAM,50,550000,"Improvements to GYM building and Supplying gym equipements at Arthoon road and Suryanarayana street in Ward-50, Unit-12, Zone-V (Under Councillor's Ward Improvement Scheme)",Own Sources,5,2015-16,2016-17 NE/2015-16/13779,Buildings,Completed,NE-ROYAPURAM,50,989000,Repairs to leaky terrace and providing sunshade and other improvements to corporation urudhu school at arthoon road in ward.50 u.12 z.5,Own Sources,5,2015-16,2017-18 NE/2015-16/13780,Footpath,Completed,NE-ROYAPURAM,50,961000,improvements to foot path at GM petai road in ward .50 u 12 z.5,Own Sources,5,2015-16,2016-17 NE/2015-16/13782,Footpath,Completed,NE-ROYAPURAM,50,757000,Improvements to foot path at north mada church street in ward.50 u.12 z.5,Own Sources,5,2015-16,2017-18 NE/2015-16/13789,Buildings,Completed,NE-ROYAPURAM,51,985000,"Providing Drainage and Water Supply Arrangements to Amma Unavagam in Manikandan 6th Street in Ward-51,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13793,Roads,Completed,NE-ROYAPURAM,57,999000,"Attending profile correction at Varadhappa muthiya street and Various Streets in Dn.57,U-13,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/13794,Roads,Completed,NE-ROYAPURAM,57,995000,"Attending profile correction at Nattu pillayar koil street and Various Streets in Dn.57,U-13,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/13795,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending profile correction at Thathaa muthiya street and Various Streets in Dn.57,U-13,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/13797,Parks,Completed,NE-ROYAPURAM,53,990000,"PROVIDING STAINLESS STEEL HANDRAILS (PART-1)TO MINT MODERN CITI PARK IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/13798,Parks,Completed,NE-ROYAPURAM,53,990000,"PROVIDING STAINLESS STEEL HANDRAILS(PART-2) TO MINT MODERN CITI PARK IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/13799,Buildings,Completed,NE-ROYAPURAM,53,998000,"ADDITIONAL IMPROVEMENTS TO MULTI PURPOSE HALL AT P.P.AMMAN KOIL EAST STREET IN DN-53, UNIT-12, ZONE-05(FOR M.L.A'S FUND)",MLACDS,5,2015-16,2016-17 NE/2015-16/13800,Buildings,Completed,NE-ROYAPURAM,53,989000,"IMPROVEMENTS AND REPAIRS WORK IN CARE TAKER ROOM IN BURIAL GROUND AT KATHPADA ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/13809,Buildings,Completed,NE-ROYAPURAM,49,570000,"Improvement to Dispensary at G.A Road 5th lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2017-18 NE/2015-16/13818,Roads,Completed,NE-ROYAPURAM,49,997000,"Laying Cement Concrete road at Grace Garden 1st Lane at Ward-49,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13822,Roads,Completed,NE-ROYAPURAM,49,997000,"Laying Cement Concrete road at Grace Garden 2nd Lane at Ward-49,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13824,Roads,Completed,NE-ROYAPURAM,49,997000,"Laying Cement Concrete road at Grace Garden 3rd Lane at Ward-49,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13825,Roads,Completed,NE-ROYAPURAM,49,997000,"Laying Cement Concrete road at Grace Garden 4th Lane at Ward-49,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13826,Roads,Completed,NE-ROYAPURAM,49,997000,"Laying Cement Concrete road at Grace Garden 5th Lane at Ward-49,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13829,Roads,Completed,NE-ROYAPURAM,49,962000,"Laying Cement Concrete road at Grace Garden Main Street Reach 1 at Ward-49,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/13834,Roads,Completed,NE-ROYAPURAM,49,962000,"Laying Cement Concrete road at Grace Garden Main Street Reach 2 at Ward-49,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14027,Storm Water Drain,Completed,NE-ROYAPURAM,58,265000,"IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS PLACES IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/14113,Roads,Completed,NE-ROYAPURAM,51,980000,"Providing Electrical and Other Improvements to Amma Unavagam in Mainkandan 6th Street in Ward-51,Unit-12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14260,Roads,Completed,NE-ROYAPURAM,49,991000,"Providing Signboards at various locations and various streets in ward-49, unit-12, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14261,Roads,Completed,NE-ROYAPURAM,53,991000,"Providing Sign boards at various locations in ward-53, unit-12, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14262,Roads,Completed,NE-ROYAPURAM,53,991000,"Providing street Name board at various streets, in ward-53, unit-12, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14312,Buildings,Completed,NE-ROYAPURAM,58,149700,"PROVIDING WATER SUPPLY ARRANGEMENTS AND ELECTRICAL ARRANGEMENTS TO THE EXISTING NIGHT SHELTER AT STRINGERS STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/14318,Roads,Completed,NE-ROYAPURAM,61,337000,"IMPROVEMENTS TO FOOTPATH AT CASA MAJOR ROAD IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/14320,Buildings,Completed,NE-ROYAPURAM,58,145000,"Repairs and improvements to the existing amma unavagam at whannels road and DRO office at samy street and in div-58,unit-14,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/14322,Buildings,Completed,NE-ROYAPURAM,61,456000,"PROVIDING WELDMESH BARRICADING WALL NEAR CANAL AT ETHIRAJ SALAI IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/14329,Buildings,Completed,NE-ROYAPURAM,58,497000,"Additional Improvements to boxing shed at sydenhams road in div-58,unit-14,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/14351,Roads,Completed,NE-ROYAPURAM,61,154000,"PROVIDING STREET FURNITURES AT THAMIL SALAI IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/14364,Footpath,Completed,NE-ROYAPURAM,58,994000,"Repairs and Improvements to the existing footpath around Jermiah park in Vepery church road in div-58,unit-14,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/14367,Roads,Completed,NE-ROYAPURAM,53,990000,"IMPROVEMENT TO NNMP SHED CENTRE NO.213,216 AND REPAIRS TO SUMP IN STANLY NAGAR IN DN-53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14368,Roads,Completed,NE-ROYAPURAM,53,995000,"Improvement to NNMP Shed Centre No.212,214,215 and Chennai Primary School at Stanly Nagar in DN-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14537,Buildings,Completed,NE-ROYAPURAM,61,778260,"IMPROVEMENT TO THE STORM WATER DRAIN & TOILET WORK IN GUNGU SUBWAY BRIDGE IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/14592,Buildings,Completed,NE-ROYAPURAM,53,998000,"Forming Footpath Inside the Basin Bridge Burial Ground in Dn -53, Unit-12, Zone -5",Own Sources,5,2015-16,2016-17 NE/2015-16/14599,Roads,Completed,NE-ROYAPURAM,50,234000,"Providing concrete platform for compactor bins at various streets in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/14617,Roads,Completed,NE-ROYAPURAM,53,690000,"Providing Speed Breaker and B.T Patches work at various street in ward-53,unit-12, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14703,Roads,Completed,NE-ROYAPURAM,52,635000,"Providing B.T Patches Work at Various Street in Ward-52, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14729,Buildings,Completed,NE-ROYAPURAM,52,310000,"Providing concrete platform for compactor bins at various places and attending repairs to the damaged roads with RMC M30 in Ward-52, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/1486,Roads,Completed,NE-ROYAPURAM,60,102000,"RELAYING THE ROAD WITH BCCMP AT ROFLERS LANE IN DN-60, U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/14878,Buildings,Completed,NE-ROYAPURAM,50,377000,Improvements to Storm Water Drain and providing diesel motor for removing wastage stagination water in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/15004,Buildings,Completed,NE-ROYAPURAM,62,906000,"LAYING CEMENT CONCRETE PAVEMENTS TO CHS AT WEST COOVAM RIVER ROAD IN DIVISION-62, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/15008,Buildings,Completed,NE-ROYAPURAM,59,990000,"LAYING CEMENT CONCRETE PAVEMENTS PATCHES AT MUKTHARUNISHA STREET, BANGARU STREET, ANNA SAMY STREET, BALA MUTHU STREET, THAYAR SHAHIB STREET, THAYAR SHAHIB 1ST LANE, THAYAR SHAHIB 2ST LANE, SATHIYAVANI MUTHU NAGAR MAIN RAOD, IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/15041,Buildings,Completed,NE-ROYAPURAM,62,990000,"CONSTRUCTION OF RCC CENTER MEDIAN FOR COOVAM RIVER BRIDGE AT ARUNACHALAM STREET IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/15056,Buildings,Completed,NE-ROYAPURAM,63,994000,"Construction of disabled toilets for physically challenged at Dams road and E.B.Link road in Dn-63,U-14,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/15211,Buildings,Completed,NE-ROYAPURAM,59,980000,"ATTENDING PATCH WORK WITH READY MIX M40 GRADE IN MINT STREET, LAKUMODOSS STREET, NAINIYAPPAN STREET, RASSAPPA (C) STREET EDAPALAYAM STREET, PARAMA CHETTY STREET, GANDHI NAGAR 1ST MAIN ROAD, 2ND MAIN ROAD, S.M NAGAR MAIN ROAD, BANGAR AMMAN STREET, MANNAR STREET, S.N STREET, PALLAVAN BRIDGE, AND VARIOUS STREETS IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/15237,Roads,Completed,NE-ROYAPURAM,62,990000,"Providing Construction Chamber and 1 to 8 laying PVC pipe Connection in Anju kudisai 9 TO 13 Lane in DN -62, Unit -14, Zone ? 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/15239,Roads,Completed,NE-ROYAPURAM,62,978000,"Providing Construction Chamber and 1 to 8 laying PVC pipe Connection in Anju kudisai 14 TO 18 Lane in DN -62, Unit -14, Zone ? 5.",Own Sources,5,2015-16,2018-19 NE/2015-16/15241,Roads,Completed,NE-ROYAPURAM,62,917000,ATTENDING PATCH WORKS AT WEST COOVAM ROAD IN DIV-62 UNIT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/15259,Buildings,Completed,NE-ROYAPURAM,51,992000,"Providing water facility and other additional work to Dinning hall under WDS in Chennai High School at Manikandan 8th Street,Old Washermenpet in Division -51,Unit -12,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/15326,Buildings,Completed,NE-ROYAPURAM,52,348000,"Improvements the nnmp shed no 90120&90121at w block at model lane tenements in dn-52,u-13,z-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/15582,Buildings,Completed,NE-ROYAPURAM,59,993000,"PROVIDING AND FIXING STREET NAME BOARD AT VARIOUS STREET IN DIVISION-59, UNIT-14, ZONE-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/15588,Buildings,Completed,NE-ROYAPURAM,59,805000,"REPAIR AND IMPROVEMENTS TO TWO WHEELER PARKING PLACE AT EDAPALAYAM (NORTHERN SIDE) IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/15697,Parks,Completed,NE-ROYAPURAM,63,610000,"CONSTRUCTION OF TRAFFIC ISLAND IN JN OF SAMY (N) STREET AND DAMS ROAD IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/15698,Buildings,Completed,NE-ROYAPURAM,63,984000,"PROVIDING AND FIXING STREET NAME BOARD AT VARIOUS STREET IN DIVISION-63, UNIT-14, ZONE-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/15715,Buildings,Completed,NE-ROYAPURAM,59,835000,"REPAIR AND IMPROVEMENTS TO TWO WHEELER PARKING PLACE AT EDAPALAYAM (SOUTHERN SIDE) IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/15884,Electrical,Completed,NE-ROYAPURAM,59,969000,"IMPROVEMENTS TO SERVICE ROAD AT PALLAVAN BRIDGE IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/15886,Buildings,Completed,NE-ROYAPURAM,59,998000,"PROVIDING CHAIN LINK (COTTED) FENCING COOVAM SIDE AT PALLAVAN SALAI OVER BRIDGE SERVICE ROAD IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/15899,Roads,Completed,NE-ROYAPURAM,53,999000,"ATTENDING REPAIRS TO DAMAGED ROAD PORTION AT KANNAN STREET IN DN53,U12,Z5.",Own Sources,5,2015-16,2016-17 NE/2015-16/15917,Buildings,Completed,NE-ROYAPURAM,53,993000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AD DR.V.R.ROAD IN DN-53, UNIT-12, ZONE-09",Own Sources,5,2015-16,2016-17 NE/2015-16/15918,Buildings,Completed,NE-ROYAPURAM,53,993000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AT CANAL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/15919,Roads,Completed,NE-ROYAPURAM,53,996000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS TO VARIOUS STREETS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/15920,Roads,Completed,NE-ROYAPURAM,53,996000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS TO VARIOUS ROADS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/15921,Buildings,Completed,NE-ROYAPURAM,53,994000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AT NORTH WALL ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/15923,Roads,Completed,NE-ROYAPURAM,55,763000,IMPROVEMENTS AND REPAIRS TO EXISTING TRANSFORMER IN DIV-55 UNIT-13 ZONE-5,Own Sources,5,2015-16,2018-19 NE/2015-16/15946,Buildings,Completed,NE-ROYAPURAM,52,140000,Improvements to arasu cable tv office at mc road shopping complex in ward.52 unit.12 zone.5,Own Sources,5,2015-16,2018-19 NE/2015-16/15950,Buildings,Completed,NE-ROYAPURAM,61,360000,"IMPROVEMENTS TO THE STORM WATER DRAIN PIPE LINE WORK AT GUNGU SUBWAY BRIDGE NEAR AMMA UNAVAGAM AND VENGU PILLAI STREET,VARIES STREETS IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/15954,Roads,Completed,NE-ROYAPURAM,49,575000,"PROVIDING STAINLESS STEEL NAME BOARD AT THANDAVARAYA (G) STREET AND MUTHAMIZH NAGAR, RWH AT VARIOUS STREETS IN WARD 49, UNIT 12, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/16104,Footpath,Completed,NE-ROYAPURAM,57,980000,"Providing granite footpth at Ramanan street from V.O.C salai to Bomiyar street junction in Dn-57,U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16109,Footpath,Completed,NE-ROYAPURAM,57,980000,"Providing granite footpth at Ramanan street from Bomiyar street junction to vaikunda vathiyar street in Dn-57, U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16110,Footpath,Completed,NE-ROYAPURAM,57,997000,"Providing granite footpth at Ramanan street from V.O.C salai to Murugappa street in Dn-57, U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16112,Footpath,Completed,NE-ROYAPURAM,57,997000,"Providing granite footpth at Ramanan street from Murugappa street to Kandappa street in Dn-57,U-13,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16115,Roads,Completed,NE-ROYAPURAM,57,997000,"Providing interlocking blocks to the north side of Audhiappa street in Dn-57.U-13,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16136,Roads,Completed,NE-ROYAPURAM,57,997000,"Providing interlocking blocks to the south side of Audhiappa street in Dn-57. U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16140,Roads,Completed,NE-ROYAPURAM,57,997000,"Providing interlocking blocks to Thatha muthaiya street in Dn-57. U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16141,Footpath,Completed,NE-ROYAPURAM,57,660000,"Providing granite footpth at Ramanan street from vaikuda vathiyar street to Audhiappa street junction in Dn-57, U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16156,Buildings,Completed,NE-ROYAPURAM,58,93500,"Dismantling the existing sunshades at Allikulam shopping complex in div-58,unit-14, zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/16160,Buildings,Completed,NE-ROYAPURAM,58,313000,"Additional Improvements to mother feeding room at CWIC AT karriappa street in div-58,unit-14,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/1618,Buildings,Completed,NE-ROYAPURAM,58,999000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT VAIKOKARAN STREET IN DIV-58, UNIT,-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/1619,Buildings,Completed,NE-ROYAPURAM,59,997000,"CONSTRUCTION OF ROAD SIDE CHILDRENS PLAY AREA AT S.M. NAGAR MAIN ROAD IN DIVISION-59, UNIT-14, ZONE-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/16203,Footpath,Completed,NE-ROYAPURAM,57,660000,"Providing granite footpth at Ramanan street from Kandappa street to Kalathiappan street junction in Dn-57, U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16285,Storm Water Drain,Completed,NE-ROYAPURAM,57,886000,"PROVIDING STAIRCASE,WATER AND ELECTRICAL FACILITIES TO 16TH DAY CEREMONY HALL AT KALYANAPURAM IN DIV-57,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/16293,Buildings,Completed,NE-ROYAPURAM,51,593000,"Providing watersupply arrangements and other additional work for common collection center in Division office at Manikandan 3rd street in Div-51,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/16371,Buildings,Completed,NE-ROYAPURAM,52,972000,Construction of Accessible Toilet for Differently abled Toilet and other improvements to Ladies side Toilet Block at Raman 8th Street in ward.52 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/16379,Buildings,Completed,NE-ROYAPURAM,52,989000,"Construction of accessible toilet for differently abled at Cemetry road, Durai street, Jaganathan street in Ward-52, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/16381,Roads,Completed,NE-ROYAPURAM,57,990000,"Providing interlocking blocks to south side of Thatha muthaiya street in Dn-57, U-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/16460,Buildings,Completed,NE-ROYAPURAM,61,973000,"PROVIDING AND FIXING STREET NAME BOARD AT VARIOUS STREET IN DIV-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/16678,Buildings,Completed,NE-ROYAPURAM,60,998000,"Face lifting of Beach Station Subway in Western Side Northern Entries at Rajaji Salai Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/16681,Buildings,Completed,NE-ROYAPURAM,60,997000,"Face lifting of Beach Station Subway in Western Side Southern Entries at Rajaji Salai Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/16762,Buildings,Completed,NE-ROYAPURAM,50,993000,"Construction of accessible toilet for differently abled at Suryanarayana street, Market lane, Thambu lane (Sheik maistry street Jn.) in ward.50 unit.12 zone.5",Own Sources,5,2015-16,2016-17 NE/2015-16/16901,Roads,Completed,NE-ROYAPURAM,60,999000,"Face lifting of Beach Station Subway in Eastern Side Northern Entries at Rajaji Salai Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/16905,Roads,Completed,NE-ROYAPURAM,60,810000,"Face lifting of Beach Station Subway in Eastern Side Southern Entries at Rajaji Salai Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/16935,Roads,Completed,NE-ROYAPURAM,60,497000,"Providing Stainless Steel Handrail in Beach Station Subway at Rajaji Salai in Ward-60,Unit-13,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17039,Buildings,Completed,NE-ROYAPURAM,58,999000,"Improvements to allikullam swimming pool in Div-58,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/1704,Buildings,Completed,NE-ROYAPURAM,51,690000,"Improvement to CPS Urdhu primary school in East Cemetry Road in Div 51,Unit 12,Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17040,Buildings,Completed,NE-ROYAPURAM,58,820000,"Additional Improvements to allikullam swimming pool in Div-58,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/17041,Roads,Completed,NE-ROYAPURAM,58,710000,"Providing stainless steel handrails and painting to footpath at Allikullam Swimming pool in Div-58,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/1732,Buildings,Completed,NE-ROYAPURAM,51,257000,"Improvement to CUHS at East Cemetry Road in Div-51,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/17510,Buildings,Completed,NE-ROYAPURAM,52,197000,"construction of friendly disable toilet at anjeneyar nagar 4 th street pc in dn-52,u-12,z-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/17634,Buildings,Completed,NE-ROYAPURAM,53,994000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AT KANNAN STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/17723,Roads,Completed,NE-ROYAPURAM,59,996000,ATTENDING PATCHES WORK AT NARANAYAPPA STREET DIV-59 UNIT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/17727,Roads,Completed,NE-ROYAPURAM,59,994000,ATTENDING PATCH WORK AT ELLIS ROAD IN DIV-59 UNIT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/17728,Roads,Completed,NE-ROYAPURAM,59,990000,ATTENDING PATCHES AT THAYAR SHAIB STREET AND ANNA SAMY STREET IN DIV-59 UNIT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/17780,Roads,Completed,NE-ROYAPURAM,49,498000,"Providing Compound Wall and Extension Store Room in Amma Unavagam at Thandavarayan Gramini Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17781,Buildings,Completed,NE-ROYAPURAM,49,993000,"Providing Additional Room for Amma Unavagam at Thandavarayan Gramini Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17782,Roads,Completed,NE-ROYAPURAM,49,990000,"Providing Tiles for Additional Room at Amma Unavagam in Thandavarayan Gramini Street at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17783,Buildings,Completed,NE-ROYAPURAM,49,998000,"Removing AC Sheet and Providing Concrete Roof at Parking Area at Amma Unavagam in Thandavarayan Gramini Street at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17785,Buildings,Completed,NE-ROYAPURAM,49,993000,"Providing Electrical Arrangement and Bore Well , Color Washing for Additional Room at Amma Unavagam in Thandavarayan Gramini Street at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17836,Buildings,Completed,NE-ROYAPURAM,49,992000,"Covered Opened Area Adjoining of Amma Unavagam at Thandaravayan Gramini Street in Ward-49,Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17841,Buildings,Completed,NE-ROYAPURAM,49,694000,"Providing Water Supply Arrangement Adjoining of Amma Unavagam at Thandaravayan Gramini Street in Ward-49,Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/17842,Roads,Completed,NE-ROYAPURAM,50,288000,"Attending patch work to the damaged roads in Ward-50, Unit-12, Zone-V",Own Sources,5,2015-16,2016-17 NE/2015-16/17928,Buildings,Completed,NE-ROYAPURAM,53,995000,"PETTY REPAIR WORK CARRIYING OUT(DAY TO DAY) TO NORTH REGIONAL OFFICE BUILDING AT B.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/17929,Buildings,Completed,NE-ROYAPURAM,53,995000,"PETTY REPAIR WORK CARRYING OUT(DAY TO DAY) TO VARIOUS CORPORATION BUILDING IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/18193,Footpath,Completed,NE-ROYAPURAM,53,595000,"REPAIRS AND IMPROVEMENTS TO FOOTPATH AT VARIOUS STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/18194,Footpath,Completed,NE-ROYAPURAM,53,595000,"REPAIRS AND IMPROVEMENTS TO FOOT PATH AT VARIOUS LOCATIONS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/18195,Footpath,Completed,NE-ROYAPURAM,53,595000,"IMPROVEMENTS TO FOOTPATH AT VARIOUS ROADS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/18196,Roads,Completed,NE-ROYAPURAM,53,596000,"REPAIRS AND IMPROVEMENTS TO C.C ROAD AT VARIOUS STREETS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/18197,Roads,Completed,NE-ROYAPURAM,53,596000,"REPAIRS AND IMPROVEMENTS TO C.C ROAD AT VARIOUS LOCATIONS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/18198,Roads,Completed,NE-ROYAPURAM,53,596000,"REPAIRS AND IMPROVEMENTS TO C.C ROAD AT VARIOUS ROADS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/18284,Buildings,Completed,NE-ROYAPURAM,55,106000,CONVERTING TWO WHEELER SHED INTO ARASU CABLE OFFICE ROOM (E-Seva) AT SHANMUGAM STREET IN DIV-55 UNIT-13 ZONE-5.,Own Sources,5,2015-16,2018-19 NE/2015-16/18285,Buildings,Completed,NE-ROYAPURAM,55,990000,"Improvements to the existing LIBRARY at Aacharappan Street (junction of Thatha Muthaiyappan Street) and Improvement to existing anganwadi and metro water office building at sevenwells street in Dn.55,Unit - 13,Zone - V.",Own Sources,5,2015-16,2018-19 NE/2015-16/18353,Roads,Completed,NE-ROYAPURAM,63,990000,"ATTENDING PATCH WORK AT BURA SHAHIB STREET IN DIVISION-63, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/18357,Roads,Completed,NE-ROYAPURAM,63,987000,"ATTENDING PATCH WORK AT VENKATESAN MAIN ROAD, VENKATESAN 2ND CROSS STREET, VENKATESAN 2ND LANE IN DIVISION -63, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/18360,Roads,Completed,NE-ROYAPURAM,63,988000,"ATTENDING PATCH WORK AT SYED ABDULLAH STREET, GULAB MOIDEEN STREET, JOHN MOHAMED STREET IN DIVISION-63, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/18423,Roads,Completed,NE-ROYAPURAM,53,790000,"LAYING CEMENT CONCRETE ROAD AT PADAVATTAMMAN KOIL LANE AND 1ST LANE IN DN53,U12,Z5.",Own Sources,5,2015-16,2016-17 NE/2015-16/18459,Roads,Completed,NE-ROYAPURAM,49,808000,"Laying Cement Concerte Road at Old AmaranjiPuram Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/18460,Roads,Completed,NE-ROYAPURAM,49,970000,"Laying Cement Concerte Road at Old AmaranjiPuram Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/18544,Roads,Completed,NE-ROYAPURAM,50,520000,"CONSTRUCTION OF SUMP IN CHENNAI HIGH SCHOOL AT S N CHETTY STREET AND CONSTRUCTION OF PLATFORM FOR DUST BIN IN DN -50, UNIT-12,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/18545,Roads,Completed,NE-ROYAPURAM,50,997000,"DEMOLITION OF COMPOSED YARD AND CONSTRUCTION OF TOILET TO DIVISION OFFICE-50 AT EAST KALMANDAPAM ROAD IN WARD-50, U-12, Z-5",Own Sources,5,2015-16,2017-18 NE/2015-16/18604,Storm Water Drain,Completed,NE-ROYAPURAM,62,632000,"LAYING PIPELINE FOR DEDRAIN THE RAIN WATER INTO COOVAM RIVER AT EAST COOVAM ROADAND WEST COOVAM ROAD AND PROVIDING RAIN WATER HARVESTING AT VARIOUS PLACES IN DN -62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/18745,Footpath,Completed,NE-ROYAPURAM,62,999448,"IMPROVEMENTS TO FOOTPATH AT SWAMY NAIKEN STREET(FROM PALANIANDAVAR KOIL STREET TO ARUNACHALAM ROAD) IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2018-19 NE/2015-16/18759,Footpath,Completed,NE-ROYAPURAM,62,983346,"IMPROVEMENTS TO FOOTPATH AT SWAMY NAIKEN STREET(FROM ARUNACHALAM ROAD TO KURUVAPPA STREET) IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2018-19 NE/2015-16/18763,Footpath,Completed,NE-ROYAPURAM,62,988284,"IMPROVEMENTS TO FOOTPATH AT SWAMY NAIKEN STREET(FROM KURUVAPPA STREET TO WEST COOUM ROAD IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2018-19 NE/2015-16/18764,Footpath,Completed,NE-ROYAPURAM,62,692966,"IMPROVEMENTS TO FOOTPATH AT SWAMY NAIKEN STREET(FROM EAST COOUM ROAD TO PALANIANDAVAR KOIL STREET )DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2018-19 NE/2015-16/18797,Buildings,Completed,NE-ROYAPURAM,55,476000,IMPROVEMENTS AND ALTERATION TO THE EXISTING BUILDING INSIDE METRO WATER OFFICE AT SEVEN WELLS STREET IN DN-55 UNIT-13 ZONE-5.,Own Sources,5,2015-16,2017-18 NE/2015-16/18849,Buildings,Completed,NE-ROYAPURAM,62,982000,"PROVIDING AND FIXING STREET NAME BOARD AT VARIOUS STREET IN DIVISION-62, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/18856,Storm Water Drain,Completed,NE-ROYAPURAM,61,980000,"REPAIR AND IMPROVEMENTS TO STORM WATER DRAIN AT RANGACHARIAR AND Dr.NATESAN STREET IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2017-18 NE/2015-16/18914,Buildings,Completed,NE-ROYAPURAM,52,930000,"PROVIDING PLATFORM,WATER SUPPLY AND ELECTRICAL ARRANCEMENTS FOR E TOILET AT MC ROAD,OSH ROAD AND INSIDE THE ANNA PARK IN DN-52,U-13,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/18915,Roads,Completed,NE-ROYAPURAM,52,980000,"providing centre median at mc road subway in dn-56,u-12,z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/18916,Roads,Completed,NE-ROYAPURAM,52,994000,"providing roofing arrangements for motor room and improvements to mc road subway in dn-52,u-12.z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/18923,Roads,Completed,NE-ROYAPURAM,50,687000,"Repairs and Improvements to Councillor Office room, Construction of store room for conservancy workers at East Kalmandapam road in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/19072,Buildings,Completed,NE-ROYAPURAM,53,826000,"Balance Improvements to Public Convenience at Srinivasapuram 2nd Street in Dn-53,Unit-12, Zone-5",Own Sources,5,2015-16,2017-18 NE/2015-16/19165,Parks,Completed,NE-ROYAPURAM,53,994000,"PROVIDING GRANITE FOOT PATH (NORTH SIDE)AT MINT MODERN CITI PARK IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/19166,Parks,Completed,NE-ROYAPURAM,53,995000,"PROVIDING GRANITE FLOORING WORK (SOUTH SIDE) AT MINT MODERN CITI PARK IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/19241,Buildings,Completed,B-Buildings,51,992000,"Urgent repairs to the existing Dispensary at East Cemetry Road in Div-51,Unit-12,Zone -5.",Own Sources,5,2015-16,2016-17 NE/2015-16/19299,Buildings,Completed,NE-ROYAPURAM,50,987000,Construction of compound wall for CUPS School in (Northern side and southern side)at Arthoon road in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2017-18 NE/2015-16/19301,Roads,Completed,NE-ROYAPURAM,62,997000,"Construction of Side drain at Navalar Neduchziyan Nagar Streets in DN -62, Unit -14, Zone -05.",Own Sources,5,2015-16,2017-18 NE/2015-16/19541,Buildings,Completed,NE-ROYAPURAM,50,990000,Construction of compound wall for CUPS School in (Eastern side and Western side) at Arthoon road in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2017-18 NE/2015-16/19543,Buildings,Completed,NE-ROYAPURAM,50,990000,Providing children play space and entrance flooring at CUPS at Arthoon Road in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/19562,Buildings,Completed,NE-ROYAPURAM,52,997000,"PROVIDING STREET FURNITURES At CEMENTRY LANE,THOPPAI STREET,RAMAN STREET,ROPE GODOWN STREET,MODEL LINE SECOND LANE,O.S.H STREET,ANJENEYA NAGAR 9TH STREET,ANJENEYA NAGAR 9TH A STREET,ANJENEYA NAGAR 6,7,8TH STREE,ANJENEYA NAGAR 5TH STREET,ANJENEYA NAGAR 3RD STREET,ANJENEYA NAGAR 2ND STREET,ANJENEYA NAGAR 1ST STREET,NAGATHA KOIL LANE,MANIGARI XHEMTRY ROAD,MOSQUE STREET,BAJANAI KOIL STREET,BARBER LANE AND VARIOUS STREETS UNDER WARD COUNSILOR FUND (2015-16) IN DN 52, UNIT- 12, ZONE -5",Own Sources,5,2015-16,2019-20 NE/2015-16/19725,Buildings,Completed,NE-ROYAPURAM,49,875000,"Improvement to Kitchen Shed at Appasamy Street for passage rear side at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/19766,Storm Water Drain,Completed,NE-ROYAPURAM,62,998000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT AYYA(M) STREET AND SINGANNA (C) STREET JN OF EAST COOVAM SALAI IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/19784,Buildings,Completed,NE-ROYAPURAM,49,734000,"Improvement to NNMP Shed and Improvement to Passage for CHS at Appasamy Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/19787,Roads,Completed,NE-ROYAPURAM,49,930000,"Attending Patches Work at M.C Road And G.A Road at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/19788,Roads,Completed,NE-ROYAPURAM,49,918000,"Attending Patches Work at Somu 6th Lane, Venkatpathy Street, Venkatramajam Street, Alvadan Street, at Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/19790,Roads,Completed,NE-ROYAPURAM,49,520000,"Providing Compund wall Adjoining of Police Quarter at Solaiappan Street in ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/19818,Bridges,Completed,NE-ROYAPURAM,51,690000,"PROVIDING RAIN WATER HARVESTING STRUCTURE AT VARIOUS STREET , SUPPYING OF 4 HP DIESEL ENGINE, , SUPPLYING OF HIRE VEHICLE AND LABOURS FOR FLOOD WORK IN DN 51,UNIT12, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/19824,Bridges,Completed,NE-ROYAPURAM,53,990000,"DESILTING AND REMOVAL OF JUNGLE AT SRINIVASAPURAM CANAL WITH JCB, DISMANTLING THE SWD TOP SLAB AND REMOVE THE SILT AND OTHER REPAIRS FOR FLOOD WORK AT DN-53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/19955,Buildings,Completed,NE-ROYAPURAM,49,865000,"Improvement to Amma Unavagam at Singara Garden 4th Lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/19966,Buildings,Completed,NE-ROYAPURAM,49,987000,"Improvement to Tax Collector room in amma Unavagam at Singara Garden 4th Lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/20182,Roads,Completed,NE-ROYAPURAM,51,770000,"PROVIDING RAIN WATER HARVESTING STRUCTURE AT VARIOUS STREET , SUPPLYING OF HIRE VEHICLE , JCB AND LABOURS FOR FLOOD WORK IN DN 51,UNIT12, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/20213,Buildings,Completed,NE-ROYAPURAM,60,990000,"Providing Day to Day Work at Various location in Ward-60, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/20230,Buildings,Completed,NE-ROYAPURAM,60,400000,"Wall Cladding and Improvement Work to Traffic Island at Rajaj Salai In ward-60, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/20239,Roads,Completed,NE-ROYAPURAM,60,394000,"Providing Humepipe Line Work for the Damaged Strom water Drain at Rajai Salai (Clive battery) in Ward-60, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/20313,Buildings,Completed,NE-ROYAPURAM,53,997000,"IMPROVEMENTS TO E.E.ROOM AND A.D. ELECTRICAL OFFICE ROOM AT NORTH REGIONAL OFFICE IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/20401,Roads,Completed,NE-ROYAPURAM,54,995000,"ATTENDING PROFILE CORRECTION AT ALIYUR MUTHIAH STREET OF CHAINAGE 0-50M STARTING FROM AMMAN KOIL STREET TO KUPPIAR STREET IN DIV-54,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/20402,Roads,Completed,NE-ROYAPURAM,54,995000,"ATTENDING PROFILE CORRECTION AT ALIYUR MUTHIAH STREET OF CHAINAGE 50M TO 100M IN DIV-54,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/20404,Roads,Completed,NE-ROYAPURAM,54,995000,"ATTENDING PROFILE CORRECTION AT ALIYUR MUTHIAH STREET OF CHAINAGE 100M TO 150M IN DIV-54,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/20405,Roads,Completed,NE-ROYAPURAM,54,995000,"ATTENDING PROFILE CORRECTION AT ALIYUR MUTHIAH STREET OF CHAINAGE 150M TO 200M IN DIV-54,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/20406,Roads,Completed,NE-ROYAPURAM,54,999000,"SUPPLYING AND FIXING OF INTERLOCKING PAVER BLOCKS AT BOTH SIDES OF ALIYUR MUTHIAH STREET IN DIV-54,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/20407,Buildings,Completed,NE-ROYAPURAM,58,999000,"IMPROVEMENTS TO COMMUNITY CENTER AT KANNAPPAR THIDAL IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/20689,Roads,Completed,NE-ROYAPURAM,58,600000,"SUPPLYING AND SPREADING OF WET MIX MACHADAM AT VARIOUS PLACES IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/20779,Buildings,Completed,NE-ROYAPURAM,55,995000,IMPROVEMENTS AND ALTERATION WORK TO THE EXISTING CORPORATION BUILDING AT SEVEN WELLS STREET IN DN-55 UNIT-13 ZONE-5.,Own Sources,5,2015-16,2019-20 NE/2015-16/20795,Buildings,Completed,NE-ROYAPURAM,53,995000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AND IMPROVEMENTS TO P.C AT V.O.C.SALAI IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/20797,Buildings,Completed,NE-ROYAPURAM,53,995000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AND IMPROVEMENTS TO P.C AT C.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/2091,Roads,Completed,NE-ROYAPURAM,52,840000,"IMPROVEMENTS TO FOOTPATH,CENTRE MEDIAN,TRAFFIC ISLAND AT NRT ROAD,CHEMTERY ROAD IN DN-52,U-12,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21033,Buildings,Completed,NE-ROYAPURAM,56,980000,"Improvements to cuhs at amman koil street in Dn.56,Unit-13,ZOne-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21034,Roads,Completed,NE-ROYAPURAM,56,960000,"Attending Patch work and edge portion with cc in venkata street,saivamuthai street,saiva muthaiya 1 to 5 street in Dn.56,Unit-13,ZOne-5.",Own Sources,5,2015-16,2019-20 NE/2015-16/21035,Roads,Completed,NE-ROYAPURAM,56,218000,"CONSTRUCTION OF COMPOUND WALL FOR VACANT LAND NEAR BISHOP CHOORIE SCHOOL AT PRAKASAM SALAI in Dn.56,Unit-13,ZOne-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/21036,Buildings,Completed,NE-ROYAPURAM,55,439000,"IMPROVEMENTS TO KINDER GARDEN CLASS ROOM,CONSTRUCTION OF BABY TOILET AND GIRLS TOILET IN CMS AT PROTUGUESE CHURCH STREET IN DIV-55 ,UNIT-13 ,ZONE-5.",Own Sources,5,2015-16,2019-20 NE/2015-16/21037,Buildings,Completed,NE-ROYAPURAM,56,310000,"PROVIDING PLATFORM, WATER SUPPLY ARRANGEMENT, ELECTRICAL ARRANGEMENT AND DRAINAGE ARRANCEMENT TO E-TOILET AT AMMAN KOIL STREET in Dn.56,Unit-13,ZOne-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/21070,Buildings,Completed,NE-ROYAPURAM,57,990000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL LAB BUILDING AT V.O.C SALAI IN DIV-57,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21090,Buildings,Completed,NE-ROYAPURAM,63,701000,"IMPROVEMENTS TO P.C AT SOUTH COOVUM RIVER ROAD IN DIV-63,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21097,Roads,Completed,NE-ROYAPURAM,54,690000,"LAYING PIPELINE ACROSS AMMAN KOIL STREET,TIRUPALLI STREET AND RAMANAN ROAD IN DIV-54,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21105,Roads,Completed,NE-ROYAPURAM,49,657000,"Attending to temporary restoration of damaged interior road due to flood in North East Monsoon 2015 at M.C.Road (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21106,Roads,Completed,NE-ROYAPURAM,49,408000,"Attending Patches work by paver finisher at Somu 6th Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21107,Roads,Completed,NE-ROYAPURAM,49,680000,"Attending Patches work by Paver Finisher at Singara Garden 4th Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21108,Roads,Completed,NE-ROYAPURAM,49,363000,"Attending Patches work by Paver Finisher at Singara Garden 8th Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21109,Roads,Completed,NE-ROYAPURAM,49,227000,"Attending Patches work by Paver Finisher at Bashyam Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/2114,Storm Water Drain,Completed,NE-ROYAPURAM,58,95000,"DEMOLITION AND RECONSTRUCTION OF THE EXISTING OF DILAPIDATED STORMWATER DRAIN INFRONT OF THE COMMUNITY HALL AT SYDENHAMS ROAD AND IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/21865,Buildings,Completed,NE-ROYAPURAM,50,882000,Raising Compound Wall and other Improvements to Community Center at Shaik Masitry Street in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2018-19 NE/2015-16/22664,Buildings,Completed,NE-ROYAPURAM,50,562000,providing head room and other improvements to NNMP Shed at AJ COLONY in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/2304,Buildings,Completed,NE-ROYAPURAM,61,560000,"Repairs to Improvement to Compound wall and Painting Footpath, Park Inside at Mayor SundaraRov Park @ Rukumani Lashmipathi Salai in DN -61, Unit -14, Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/2306,Storm Water Drain,Completed,NE-ROYAPURAM,61,195000,"Repairs to Improvement to S.W.D at Halls Road in DN -61, Unit -14, Zone -05.",Own Sources,5,2015-16,2019-20 NE/2015-16/23857,Buildings,Completed,NE-ROYAPURAM,53,820000,"IMPROVEMENTS TO NNMP SHED NO : 3360390212, 90214 AND 90215 CHENNAI CORPORATION PRIMARY SCHOOL CAMPUS AT STANLEY NAGAR IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23860,Buildings,Completed,NE-ROYAPURAM,53,795000,"IMPROVEMENTS TO NNMP SHED NO : 3360390223 ,3360390224 AND 3360390225,3360390226 AT SEENIVASAPURAM 2ND STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2018-19 NE/2015-16/23861,Parks,Completed,NE-ROYAPURAM,53,989000,"PROVIDING PLANTER BOX (NEAR EAST SIDE COMPOUND WALL) AND GREENERY ARRANGEMENT WORK AT NORTH REGIONAL OFFICE BUILDING CAMPUS IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23862,Buildings,Completed,NE-ROYAPURAM,53,820000,"IMPROVEMENTS TO NNMP SHED NO : 3360390205 AND 90206 AT PENSIONER'S LANE 4TH STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23863,Buildings,Completed,NE-ROYAPURAM,53,820000,"IMPROVEMENTS TO NNMP SHED NO : 3360390220 AND 90222 NEAR AMMA UNAVAGAM AT DR.V.R.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23864,Buildings,Completed,NE-ROYAPURAM,53,820000,"IMPROVEMENTS TO NNMP SHED NO : 3360390227 AND 90228 NEAR RATION SHOP AT SEENIVASAPURAM IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2018-19 NE/2015-16/23867,Buildings,Completed,NE-ROYAPURAM,53,820000,"IMPROVEMENTS TO ICDS CENTRE NO : 3360390208 ,3360390209 (NEAR I.T.I) AT KATHBADA MAIN ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2018-19 NE/2015-16/23869,Buildings,Completed,NE-ROYAPURAM,53,820000,"IMPROVEMENTS TO ICDS CENTER NO : 3360390217,3360390219,AND 3360390221(NEAR LIBRARY) AT DR.V.R.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23870,Buildings,Completed,NE-ROYAPURAM,53,986000,"IMPROVEMENTS TO S.I OFFICE AT DR.V.R.ROAD AND IMPROVEMENTS TO C.I OFFICE AT T.H.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23871,Buildings,Completed,NE-ROYAPURAM,53,985000,"IMPROVEMENTS TO DEPUTY COMMISIONER OFFICE IN NORTH REGIONAL OFFICE AT B.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2018-19 NE/2015-16/23872,Buildings,Completed,NE-ROYAPURAM,53,988000,"IMPROVEMENTS TO TOWN PLANNING SECTION OFFICE IN NORTH REGIONAL OFFICE BUILDINGS AT B.B. ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23902,Buildings,Completed,NE-ROYAPURAM,53,995000,"CONSTRUCTION OF DISABLE FRIENDLY TOILET BLOCK AND IMPROVEMENTS TO P.C AT POJARAJAN MAIN STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23903,Buildings,Completed,NE-ROYAPURAM,53,995000,"CONSTRUCTION OF DISABLE FRIENDLY TOILET BLOCK AND IMPROVEMENTS TO P.C AT PENSIONERS 3RD STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23904,Buildings,Completed,NE-ROYAPURAM,53,995000,"CONSTRUCTION OF DISABLE FRIENDLY TOILET BLOCK AND IMPROVEMENTS TO P.C AT KATHBADA MAIN STREET(NEAR MUNEESWARAR TEMPLE) IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23905,Buildings,Completed,NE-ROYAPURAM,53,995000,"CONSTRUCTION OF DISABLE FRIENDLY TOILET AND IMPROVEMENTS TO EXISTING P.C. AT P.P.AMMAN KOIL 2ND STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23906,Buildings,Completed,NE-ROYAPURAM,53,995000,"CONSTRUCTION OF DISABLE FRIENDLY TOILET AND IMPROVEMENTS TO EXISTING P.C AT P.P.AMMAN KOIL 4TH STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23907,Buildings,Completed,NE-ROYAPURAM,53,995000,"CONSTRUCTION OF DISABLE TOILET AND IMPROVEMENTS TO EXISITING P.C AT KATHBADA MAIN ROAD( OPPOSITE TO LABOUR LANE) IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23908,Buildings,Completed,NE-ROYAPURAM,53,995000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AND IMPROVEMENTS TO EXISTING P.C AT B.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/23909,Buildings,Completed,NE-ROYAPURAM,53,995000,"CONSTRUCTION OF DISABLE TOILET AND IMPROVEMENTS TO EXISITING P.C. AT RAMA DOSS NAGAR IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23910,Footpath,Completed,NE-ROYAPURAM,53,998000,"IMPROVEMENTS TO FOOTPATH AT B.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23911,Footpath,Completed,NE-ROYAPURAM,53,994000,"ADDITIONAL IMPROVEMENTS TO FOOTPATH AT B.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/23912,Buildings,Completed,NE-ROYAPURAM,53,989000,"IMPROVEMENTS TO ELECTION FACILITION CENTER AT RDC BUILDING IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/24225,Buildings,Completed,B-Buildings,51,662000,"Construction of Room at Second Floor for SI in Dispensary at East Cemetry Road in Division 51,Unit 12,Zone 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/24325,Buildings,Completed,NE-ROYAPURAM,55,145000,"Providing disabled toilet inside barracks street PC at barracks street in ward 55, unit 13, Zone 5.",Own Sources,5,2015-16,2018-19 NE/2015-16/24758,Roads,Completed,NE-ROYAPURAM,56,950000,"REFORMING CC ROAD FOR THE MISSING LINK WITH RMC 30 GRADE AT AMMAN KOIL STREET(ashivadapuram main rd to davidson street ) IN DN 56,U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/24772,Roads,Completed,NE-ROYAPURAM,56,560000,"ATTENDING PATCH WORK FOR THE FLOOD AFPECTED PORTIONWITH RMC 30 GRADE AT AMMAN KOIL STREET( DAVIDSON STREET TO PRAGASAM SALAI) IN DN 56,U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/25099,Buildings,Completed,NE-ROYAPURAM,58,999000,"IMPROVEMENT TO STORM WATER DRAIN AND RAISING AND LOWERING MAN HOLE DOOR AT VARIES STREET IN-58, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2019-20 NE/2015-16/26504,Roads,Completed,NE-ROYAPURAM,57,2524000,"RELAYING THE ROAD WITH BCCMP AT BASIN WATER WORKS STREET IN DN-57, U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/2669,Roads,Completed,NE-ROYAPURAM,60,399000,"RELAYING THE ROAD WITH BCCMP AT Pogada Lane IN DN-60, U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27110,Storm Water Drain,Completed,NE-ROYAPURAM,58,400000,"DESILTING THE CANAL BEHIND SALT COTTAURS IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/27119,Roads,Completed,NE-ROYAPURAM,58,330000,"PAINTING TO DOVETON FLYOVER BRIDGE AT BOTH SIDES IN DIV-58,UNIT-14,ZONE-6.",Own Sources,5,2015-16,2016-17 NE/2015-16/27123,Storm Water Drain,Completed,NE-ROYAPURAM,58,747000,"DEMOLITION AND RECONSTRUCTION OF THE DILAPIDATED STORM WATER DRAIN AT VEPERY HIGH ROAD AND INSIDE THE DIVISION OFFICE IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/27170,Parks,Completed,NE-ROYAPURAM,59,952000,ANNUAL MAINTENANCE OF SIVANANDHA SALAI ROAD SIDE PARK AT SIVANANDHA SALAI IN DN-59 UNIT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/27181,Buildings,Completed,NE-ROYAPURAM,58,982000,"Providing and Fixing street Name Board at Various street in div-58, unit-14, zone-05",Own Sources,5,2015-16,2016-17 NE/2015-16/27206,Buildings,Completed,NE-ROYAPURAM,62,186000,"PAINTING BLACK AND WHITE FOR FOOTPATH KERB FOR REPUBLIC DAY AT KABALA MOOTHY SALAI AND ARUNCHALA STREET IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/27342,Buildings,Completed,NE-ROYAPURAM,60,943000,"Painting center median at North fort side road,NSC Bose Road,Rajaji salai (RBI Subway to clive battery)in view of Republic day in div-60,unit-13,zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27348,Roads,Completed,NE-ROYAPURAM,60,999000,"Painting nepiar bridge in view of Republic day at kamarajar salai in div60,unit-13,zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27349,Roads,Completed,NE-ROYAPURAM,60,900000,"Painting Reserve bank subway in view of Republic day at Rajaji salai in div60.unit-13,zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27365,Roads,Completed,NE-ROYAPURAM,60,997000,"Painting foot path Kerb wall at Kamarajar salai, Flag staff house road , Rajaji salai ,Notrh fort side road,NSC Bose road div-60,unit-13,zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27391,Roads,Completed,NE-ROYAPURAM,63,567000,"Providing Interlocking Blocks at Byram Jung Bhabur 2nd street, Kaliman puran 2nd street, Maroof shabib 2nd street, Raza Hyder street in ward-63, unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27405,Buildings,Completed,NE-ROYAPURAM,49,999000,PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV-49 UNT-12 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/27410,Roads,Completed,NE-ROYAPURAM,60,999000,PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV-60 UNT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/27640,Buildings,Completed,NE-ROYAPURAM,58,590000,"PROVIDING WATER SUPPLY ARRANGEMENT AND FRC BENCHES TO THE FOOTBALL GROUND AT NAVAL HOSPITAL ROAD IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/27669,Buildings,Completed,NE-ROYAPURAM,50,898000,"PROVIDING AND FIXING CABLE TV NAME BOARD AT VARIOUS STREET IN DIVISION-49 TO 63, UNIT-12,13,14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27703,Parks,Completed,NE-ROYAPURAM,52,999000,"Supply Spradding of Red Earth, Manure, Sand for Anna Park in Div-52 unit-12 zone-5",Own Sources,5,2015-16,2019-20 NE/2015-16/27731,Buildings,Completed,NE-ROYAPURAM,61,983000,"IMPROVEMENTS TO CENTRE MEDIAN AND FOOTPATH PAINTING FOR REPUBLIC DAY CELEBRATION AT PANTHEON ROAD, RUKMANI LAKSHMIBATHY SALAI, ETHIRAJ SALAI , MONTIATH ROAD, KASA MAJOR ROAD, ATHITHANAR SALAI, IN DIV-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27850,Buildings,Completed,NE-ROYAPURAM,61,975000,"IMPROVEMENTS TO CENTRE MEDIAN AND FOOTPATH PAINTING FOR REBUBLIC DAY CELEBRATION AT PCO ROAD, EGMORE HIGH ROAD, HALLS ROAD, NAYAR BRIDGE, GANDHI ERVIN BRIDGE, GANDHI ERVIN ROAD, WANELLS ROAD, IN DIV-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/27862,Buildings,Completed,NE-ROYAPURAM,50,792000,"Black and white washing to footpath kerbs and painting to centre median at M.S. Koil street, Suryanarayana street, East Kalmandapam road and West madha church street in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/27863,Buildings,Completed,NE-ROYAPURAM,50,913000,Improvements to health post at venkatesan street in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/28082,Roads,Completed,NE-ROYAPURAM,59,248000,"LAYING CC ROAD WITH M30 GRADE CONCRETE AT ELLISPURAM 1ST,2ND,3RD LANES IN DN-59,U-14,Z-5",Own Sources,5,2015-16,2017-18 NE/2015-16/28083,Roads,Completed,NE-ROYAPURAM,59,1142000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT SAMUTHRA STREET IN DN -59,U-14,Z-5",Own Sources,5,2015-16,2017-18 NE/2015-16/28084,Roads,Completed,NE-ROYAPURAM,59,809000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT KALAPPA (A) STREET IN DN -59,U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28085,Roads,Completed,NE-ROYAPURAM,59,674000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT JESSAN STREET IN DN-59, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28086,Roads,Completed,NE-ROYAPURAM,59,767000,"Relaying of road with BCCMP 30mm thick by paver finisher at Venkatachalam (M) Street in Dn-59, Unit-14, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/28087,Roads,Completed,NE-ROYAPURAM,59,418000,"Relaying of road with BCCMP 30mm thick by paver finisher at Paramasivam (c) Street in Dn-59, Unit-14, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/28090,Roads,Completed,NE-ROYAPURAM,61,2385000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT SANTHOSH NAGAR ROAD (TNSCB) IN DN-59, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28091,Roads,Completed,NE-ROYAPURAM,61,687000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT CHINNAKULANDHAI LANE IN DN-61, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28092,Roads,Completed,NE-ROYAPURAM,61,979000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT SUBBAN STREET IN DN-61, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28093,Roads,Completed,NE-ROYAPURAM,61,256000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT SUNDAR STREET IN DN-61, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28094,Roads,Completed,NE-ROYAPURAM,61,394000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT NATESAN STREET IN DN-61, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28095,Roads,Completed,NE-ROYAPURAM,61,255000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT BOOPATHY NAGAR 1ST AND 2ND STREET IN DN-61, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28096,Roads,Completed,NE-ROYAPURAM,61,557000,"LAYING CC ROAD WITH M30 GRADE OF CEMENT CONCRETE ROAD AT BOOPATHY NAGAR PART IN DN-61, U-14, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28097,Roads,Completed,NE-ROYAPURAM,61,2025000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT TRANSPORT LANE IN DN - 61, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28098,Roads,Completed,NE-ROYAPURAM,61,337000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT MUNUSAMY LANE IN DN - 61, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28103,Buildings,Completed,NE-ROYAPURAM,62,997000,"CONSTRUCTION OF COMPOUND WALL AROUND PC AND IMPROVEMENTS TO PC AT EAST COOVAM ROAD IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28106,Buildings,Completed,NE-ROYAPURAM,62,239000,"IMPROVEMENTS TO AMMA UNAVAGAM AT WEST COOVAM ROAD IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28108,Roads,Completed,NE-ROYAPURAM,62,2409000,"Relaying of road with BCCMP 30mm thick by paver finisher at Samy (p) Street from Kalavai st to West coovam river road in Dn-62, Unit-14, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/28117,Buildings,Completed,NE-ROYAPURAM,62,548000,"REPAIRS AND IMPROVEMENTS TO GYM BUILDING AT COX'S COLONY IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28121,Roads,Completed,NE-ROYAPURAM,62,2266000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT NAGAMANI STREET AND DEVARAJ SARANG STREET IN DN - 62, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28122,Roads,Completed,NE-ROYAPURAM,62,539000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT OLD BUNGALOW STREET IN DN - 62, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28123,Buildings,Completed,P-Parks and Playfields,58,950000,"IMPROVEMENTS TO FOOTPATH AND PROVIDING FENCING ARRANGEMENTS TO THE NAVAL HOSPITAL ROAD IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28125,Buildings,Completed,NE-ROYAPURAM,58,800000,"IMPROVEMENTS TO CMS MAIN BLOCK AT V.K PILLAI STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28126,Buildings,Completed,NE-ROYAPURAM,58,850000,"ADDITIONAL IMPROVEMENTS TO CMS MAIN BLOCK AT V.K PILLAI STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28127,Buildings,Completed,NE-ROYAPURAM,58,860000,"IMPROVEMENTS AND PAINTING TO CMS MAIN BLOCK AND STAGE AT VATHIYAR KANDAPPA STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28128,Storm Water Drain,Completed,NE-ROYAPURAM,58,998000,"Improvements to SWD at E.V.R. Periyar Salai (inside church) in Dn.58, Unit-14, Zone-V.",Own Sources,5,2015-16,2019-20 NE/2015-16/28130,Storm Water Drain,Completed,NE-ROYAPURAM,58,997000,"Improvements to Storm Water Drain (Inside Church) at E.V.R. Periyar Salai in Dn.58, Unit-14, Zone-V.",Own Sources,5,2015-16,2018-19 NE/2015-16/28132,Buildings,Completed,NE-ROYAPURAM,58,674000,"IMPROVEMENT TO CMS ANNEXE BLOCK AT V.K PILLAI STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28134,Roads,Completed,NE-ROYAPURAM,58,623000,"PAINTING TO FOOTPATH AT VARIOUS ROADS IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/28135,Buildings,Completed,NE-ROYAPURAM,58,870000,"Improvements to the community college and cms main block at V.K pillai street in div-58,unit-14,zone-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28136,Buildings,Completed,NE-ROYAPURAM,58,879000,"PAINTING TO THE EXISTING COMMUNITY COLLEGE,KITCHEN SHED,NNMP SHEDS AND CIMS AT V.K PILLAI STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28137,Storm Water Drain,Completed,NE-ROYAPURAM,58,999000,"Dismantling roof slab, desilting and Improvements to SWD at E.V.R. Periyar Salai (inside church) in Dn.58, Unit-14, Zone-V.",Own Sources,5,2015-16,2018-19 NE/2015-16/28138,Roads,Completed,NE-ROYAPURAM,58,534000,"PAINTING TO FOOTPATH AT VARIOUS ROADS IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/28146,Buildings,Completed,NE-ROYAPURAM,58,747000,"IMPROVEMENTS TO IID CLASSROOM AND COMPOUND WALL AT V.K PILLAI SCHOOL CAMPUS IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/28157,Roads,Completed,NE-ROYAPURAM,63,1031000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE ATELLAPPA (n) 2ND LANE IN DN - 63, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28159,Roads,Completed,NE-ROYAPURAM,63,433000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT HARRIS LANE IN DN - 63, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28164,Roads,Completed,NE-ROYAPURAM,63,503000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT ARUMUGAM STREET & WELDER STREET IN DN - 63, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28165,Roads,Completed,NE-ROYAPURAM,63,478000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT QURBAN ALI STREET IN DN - 63, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28166,Roads,Completed,NE-ROYAPURAM,63,1908000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT BOOTHAPERUMAL KOIL 1ST AND 2ND LANE IN DN - 63, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28170,Roads,Completed,NE-ROYAPURAM,63,86000,"LAYING OF C.C ROAD WITH M30 GRADE OF CEMENT CONCRETE AT ELLAPPA (N) 1ST LANE IN DN - 63, U-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28342,Buildings,Completed,NE-ROYAPURAM,62,986000,"IMPROVEMENTS TO GYM BUILDING GROUND FLOOR AT ARUNACHALAM STREET IN DIV-62,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/28357,Roads,Completed,NE-ROYAPURAM,60,949000,"Relaying B.T Patches at Various Street in Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28380,Parks,Completed,NE-ROYAPURAM,62,977000,"CONSTRUCTION OF COMPOUND WALL AND OUTER FLOORING ARRANGEMENTS FOR GROUND FLOOR TO GYM AT ARUNACHALAM STREET IN DIV-62,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/28780,Subway,Completed,NE-ROYAPURAM,61,990000,"IMPROVEMENTS TO GENGU REDDY SUB WAY REPUBLIC DAY CELEBRATION AT DN-61,UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/28784,Subway,Completed,NE-ROYAPURAM,61,97000,"REPAIR AND IMPROVEMENT TO ROAD SIDE PARK COMPOUND WALL AT L.G. ROAD IN DIVISION-61, UNIT-14, ZONE-05",Own Sources,5,2015-16,2019-20 NE/2015-16/28899,Roads,Completed,NE-ROYAPURAM,53,584000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT CANAL ROAD STANLEY NAGAR 5 TH STREET P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/28904,Roads,Completed,NE-ROYAPURAM,53,993000,"Providing stainless steel handrails and Fencing at C.B road at ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/28922,Roads,Completed,NE-ROYAPURAM,53,760000,"Attending Patches work and Painting at CB road in ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29025,Storm Water Drain,Completed,NE-ROYAPURAM,53,999000,"CONSRUCTION OF STORM WATER DRAIN AT KANNAN STREET ROUNDANA (FROM CH-70M TO 140M ) IN DN-53,UNIT-12,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29031,Buildings,Completed,NE-ROYAPURAM,53,996000,"Improvement to P.C at Kathpada 1st Street, Kathivakam High Road Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2017-18 NE/2015-16/29169,Buildings,Completed,NE-ROYAPURAM,53,584000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT C B ROAD P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/29330,Footpath,Completed,NE-ROYAPURAM,53,997000,"Improvement to Footpath at Kannan Street (From Parthasarathy Bridge junction to Bojarajan Nagar Railway gate junction) in ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29344,Storm Water Drain,Completed,NE-ROYAPURAM,53,990000,"Improvement to Storm Water Drain at Srinivasapuram (Ch 90 to 180) in ward-53, unit-12, zone-5",Own Sources,5,2015-16,2017-18 NE/2015-16/29346,Storm Water Drain,Completed,NE-ROYAPURAM,53,995000,"Improvement to Storm Water Drain at Srinivasapuram (Ch 180 to 270) in ward-53, unit-12, zone-5",Own Sources,5,2015-16,2017-18 NE/2015-16/29456,Buildings,Completed,NE-ROYAPURAM,59,537000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT RATTAN BAZZAR IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29459,Buildings,Completed,NE-ROYAPURAM,59,964000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT WALL TAX ROAD IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29460,Buildings,Completed,NE-ROYAPURAM,59,992000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT PALLAVAN NAGAR IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/2952,Buildings,Completed,NE-ROYAPURAM,61,997000,"CONSTRUCTION OF TOILET ROOM,KITCHEN FLOORING TILES AND ALUMINIUM WORK IN AMMA CANTEEN AT VARADARAJAPURAM PANTHEON SALAI IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/2954,Electrical,Completed,NE-ROYAPURAM,61,998000,"PROVIDING ELECTRICAL,WATER SUPPLY AND FALL CEILING ARRANGEMENTS IN AMMA CANTEEN AT VARADARAJAPURAM PANTHEON SALAI IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/29543,Buildings,Completed,NE-ROYAPURAM,55,695000,"PROVIDING ELECTRICAL ARRANGEMENTS TO COMMUNITY HALL AT ST. XAVIER STREET IN DIVISION-55, UNIT-13, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29639,Buildings,Completed,NE-ROYAPURAM,59,988000,"PROVIDING FALSE CEALING AND SUPPLY OF VESSELS, TABLE AND OTHER EQUIPMENT TO AMMA UNAVAGAM AT FRAZER BRIDGE ROAD IN DIV-59, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/29644,Buildings,Completed,NE-ROYAPURAM,62,684000,"SUPPLY OF VESSELS, TABLE AND OTHER EQUIPMENT TO AMMA UNAVAGAM AT ARUNACHALAM MAIN ROAD IN DIV-62, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/29850,Roads,Completed,NE-ROYAPURAM,53,997000,"Improvement to Footpath at Kannan Street ( from Bojarajan Nagar Railway gate junction to kannan street DN 53 END )in ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29852,Buildings,Completed,NE-ROYAPURAM,53,999000,"CONSRUCTION OF STORM WATER DRAIN AT KANNAN STREET ROUNDANA (FROM CH-0M TO 70M ) IN DN-53,UNIT-12,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29937,Buildings,Completed,NE-ROYAPURAM,63,998000,"Improvements to Amma unavagam at Veerabathran street in Dn.63,Unit.14,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/29977,Roads,Completed,NE-ROYAPURAM,51,997000,"IMPROVEMENTS TO CPS BUILDING AT CEMETERY ROAD IN DN-51, UNIT-12,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29981,Roads,Completed,NE-ROYAPURAM,53,999000,"REPAIRS AND IMPROVEMENT TO FOOTPATH AT C B ROAD IN DN -53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29982,Roads,Completed,NE-ROYAPURAM,53,997000,"REPAIRS AND IMPROVEMENTS TO LORRY STATION AT BASIN BRIDGE ROAD IN DN-53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29983,Roads,Completed,NE-ROYAPURAM,53,584000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT SRINIVASAPURAM P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/29985,Roads,Completed,NE-ROYAPURAM,53,999000,"REPAIRS AND IMPROVEMENT V R ROAD ISLAND PARK AND PARASURAMAN STREET PARK IN DN -53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/29986,Roads,Completed,NE-ROYAPURAM,53,584000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT BOJARAJAN NAGAR P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/29987,Roads,Completed,NE-ROYAPURAM,53,998000,"FORMING FOOTPATH ,PROVIDING GRILL, REPAIRS STORM WATER DRAIN AND OTHER IMPROVEMENT WORKS AT DR VIJAYARAGAVALU ROAD ,ROUNDANA PARK IN DN-53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/29988,Bridges,Completed,NE-ROYAPURAM,53,999000,"CONSTRUCTION OF COMPOUND WALL AND ATTENDING PATCH WORK AT KATPADHA 3 RD LANE IN DN-53,,UNIT-12, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30066,Buildings,Completed,NE-ROYAPURAM,51,965000,"Providing head room and other Improvements to NNMP Shed no.0813,0814,0815 (3.nos). at Cemetry Road ( pandian park) in Div 51 Unit 12 Zone 5",Own Sources,5,2015-16,2018-19 NE/2015-16/30077,Roads,Completed,NE-ROYAPURAM,53,295000,"Relaying B.T Road at Kathbada 3rd lane in ward-53, Unit-12, Zome-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30079,Roads,Completed,NE-ROYAPURAM,53,1430000,"Laying Cement Concetre Road at Bojaraja Nagar 1st street in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30093,Roads,Completed,NE-ROYAPURAM,60,5562000,"RELAYING THE ROAD WITH BCCMP AT AREMENIAN STREET IN DN -60 , U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30094,Roads,Completed,NE-ROYAPURAM,60,1167000,"RELAYING THE ROAD WITH BCCMP AT MUTHUMARI STREET IN DN -60 ,U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30095,Roads,Completed,NE-ROYAPURAM,60,796000,"RELAYING THE ROAD WITH BCCMP AT PERIYANNA (M) STREET IN DN -60 ,U-13, Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30096,Roads,Completed,NE-ROYAPURAM,60,356000,"RELAYING THE ROAD WITH BCCMP AT GOPAL STREET IN DN -60 ,U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30097,Roads,Completed,NE-ROYAPURAM,60,431000,"RELAYING THE ROAD WITH BCCMP AT MOORTHINGAL LANE IN DN -60 ,U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30098,Roads,Completed,NE-ROYAPURAM,60,779000,"RELAYING THE ROAD WITH BCCMP AT ARBUTNOT LANE IN DN -60 ,U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30099,Roads,Completed,NE-ROYAPURAM,60,653000,"RELAYING THE ROAD WITH BCCMP AT KANDAPPA STREET IN DN -60 ,U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30100,Roads,Completed,NE-ROYAPURAM,60,464000,"RELAYING THE ROAD WITH BCCMP AT FRANCIS JOSEPH STREET IN DN -60 ,U-13,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30102,Roads,Completed,NE-ROYAPURAM,60,1030000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VADA MARACOIR STREET IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/30103,Roads,Completed,NE-ROYAPURAM,60,447000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT IBRAHIM 1ST LANE IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/30104,Roads,Completed,NE-ROYAPURAM,60,4343000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT KATCHALEESWARAR AGRAHARAM STREET IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/30105,Roads,Completed,NE-ROYAPURAM,60,1391000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT VENKATLINGAM LANE IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/30106,Roads,Completed,NE-ROYAPURAM,60,309000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT THAMBU (C) LANE IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/30107,Roads,Completed,NE-ROYAPURAM,60,13300000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT ERABALU STREET IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/30109,Parks,Completed,NE-ROYAPURAM,60,510000,Supplying of Security Cabins and Garden Tools and Equipments for Secretariat Park at Rajaji salai in Div-60 Unit-13 Zone-5.,Own Sources,5,2015-16,2017-18 NE/2015-16/30110,Roads,Completed,NE-ROYAPURAM,54,262000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT AMMAN KOIL 2ND LANE IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/30111,Roads,Completed,NE-ROYAPURAM,54,321000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT NAMMALVAR LANE IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/30112,Roads,Completed,NE-ROYAPURAM,54,3049000,"RELAYING OF C.C.ROAD WITH M 30 GRADE CEMENT CONCRETE AT MULLAH STREET IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/30218,Roads,Completed,P-Parks and Playfields,58,992000,"IMPROVEMENTS TO THE EXISTING FOOTBALL GROUND AT NAVAL HOSPITAL ROAD IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/30231,Roads,Completed,NE-ROYAPURAM,53,980000,"Laying Cement Concetre patches at P.P Amman 1st, 2nd, 3rd, 4th, 5th, 6th Street, P.P Amman koil east Main road, Bojaraja Nagar Main Street in Ward-53, Unit-53, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30232,Roads,Completed,NE-ROYAPURAM,53,980000,"Laying Cement Concetre Patches at Stanley Nagar 1st, 2nd, 3rd 4th, 5th Street and Nehru memorial Nagar at Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30242,Footpath,Completed,NE-ROYAPURAM,58,999000,"Improvements to Granite foot path at Ritherton road east side (From Doveton signal ch Om to 145m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/30243,Footpath,Completed,NE-ROYAPURAM,58,998000,"Improvements to Granite foot path at Ritherton road east side(From ch 145m to 290m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/30244,Footpath,Completed,NE-ROYAPURAM,58,998000,"Improvements to Granite foot path at Ritherton road east side(From ch 290m to 435m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/30245,Footpath,Completed,NE-ROYAPURAM,58,999000,"Improvements to Granite foot path at Ritherton road east side(From ch 435m to 580m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/30246,Footpath,Completed,NE-ROYAPURAM,58,998000,"Improvements to Granite foot path at Ritherton road east side(From ch 580m to 725m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/30247,Footpath,Completed,NE-ROYAPURAM,58,998000,"Improvements to Granite foot path at Ritherton road east side(From ch 725m to 870m the junction of poonamalli high road) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/30267,Buildings,Completed,NE-ROYAPURAM,58,730000,"Improvements to Public Convenience at Kannappar Thidal (Near Home for homeless) In Ward-58, Unit-14, Zone-5",Own Sources,5,2015-16,2018-19 NE/2015-16/30405,Buildings,Completed,NE-ROYAPURAM,61,980000,"PROPOSED CONSTRUTION OF G.F AT GYM BUILDING AT CHINNAKULANDAI LANE IN DN-61,U-14,Z-5",Own Sources,5,2015-16,2018-19 NE/2015-16/30472,Buildings,Completed,NE-ROYAPURAM,61,360000,"IMPROVEMENT TO ANGANVADI COMPOUND WALL AT L.G. ROAD VARADARAJAPURAM IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/30534,Roads,Completed,NE-ROYAPURAM,53,988000,"Laying Cement Concetre Road adjoining of Lorry Depo Near Basin Bridge road Reach 1 in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30537,Roads,Completed,NE-ROYAPURAM,53,992000,"Laying Cement Concetre Road adjoining of Lorry Depo Near Basin Bridge road Reach 2 in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30538,Roads,Completed,NE-ROYAPURAM,53,988000,"Laying Cement Concetre Road adjoining of Lorry Depo Near Basin Bridge road Reach 3 in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30540,Roads,Completed,NE-ROYAPURAM,53,988000,"Laying Cement Concetre Road adjoining of Lorry Depo Near Basin Bridge road Reach 4 in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30541,Roads,Completed,NE-ROYAPURAM,53,998000,"Construction of Compund wall at Lorry Depo near Basin Bridge in Ward-53, Unit-12, Zone-5",Own Sources,5,2015-16,2017-18 NE/2015-16/30544,Parks,Completed,NE-ROYAPURAM,50,972000,Providing pathway and water supply arrangements to kamaraj park junction of lotus ramaswamy street in ward.50 unit.12 zone.v,Own Sources,5,2015-16,2016-17 NE/2015-16/30545,Parks,Completed,NE-ROYAPURAM,50,989000,Improvements to kamaraj park at S N Chetty street in ward.50 unit.12 zone.v,Own Sources,5,2015-16,2016-17 NE/2015-16/30546,Buildings,Completed,NE-ROYAPURAM,52,690000,Improvements to GYM building inside anna play ground at M C road in ward.52 unit.12 zone .5,Own Sources,5,2015-16,2016-17 NE/2015-16/30547,Storm Water Drain,Completed,NE-ROYAPURAM,52,649000,providing rainwater harvesting and silt pit to storm water drain at various street in ward.52 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/30550,Roads,Completed,NE-ROYAPURAM,56,650000,"REFORMING CC ROAD FOR THE MISSING LINK WITH RMC 30 GRADE AT AMMAN KOIL STREET (90M TO VARADAPPA MUDALI ST) IN DN-56,U-13,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/30551,Roads,Completed,NE-ROYAPURAM,56,950000,"REFORMING CC ROAD FOR THE MISSING LINK WITH RMC 30 GRADE AT AMMAN KOIL STREET ( PEDARIYAR KOIL ST TO 90M) IN DN-56,U-13,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/30560,Roads,Completed,NE-ROYAPURAM,58,620000,"ATTENDING REPAIRS TO THE DAMAGED ROAD AT VARIOUS PLACES IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/30561,Parks,Completed,NE-ROYAPURAM,60,974000,Maintenance of Secretariat Park at Rajajisalai in Div-60 Unit-13 Zone-5 Gardener Maintenance Period of 5 Months (Per Day 24 Gardeners),Own Sources,5,2015-16,2017-18 NE/2015-16/30564,Parks,Completed,NE-ROYAPURAM,61,990000,"IMPROVEMENTS TO GREENARY, PLANTS & ELECTRICAL AND FOOTPATH LIGHT ARRANGEMENTS TO GREATER CHENNAI CORPORATION PARK AT ETHIRAJ LANE IN DIVISION-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30565,Parks,Completed,NE-ROYAPURAM,61,991000,"IMPROVEMENTS TO GREATER CHENNAI CORPORATION PARK FOR FOOTPATH AND PAINTING AT ETHIRAJ LANE IN DIVISION-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/30567,Parks,Completed,NE-ROYAPURAM,61,880000,"IMPROVEMENTS TO EB ROOM, LABOUR DRESSING, ROOM AND PARK MATERIAL STORE ROOM FOR MAYOR SUNDARA RAO PARK AT RUKMANI LAKSHMIPATHY SALAI IN DIVISION-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/30569,Parks,Completed,NE-ROYAPURAM,62,999000,"PROVISION OF BIO-TOILET -INSTALLATION AT EAST COOVAM ROAD (OPP TO VENKATESAN STREET IN DIV-62, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/30570,Parks,Completed,NE-ROYAPURAM,62,974000,"IMPROVEMENTS TO GREENERY ARRANGEMENTS TO MAY DAY PARK AT MAYOR KABALA MOORTHY SALAI IN DIVISION-62, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/3058,Buildings,Completed,NE-ROYAPURAM,51,568000,"Repairs And Maintenance Of Chennai Primary School Cemetery Road In Division 51, Unit 12, Zone 05",Own Sources,5,2015-16,2016-17 NE/2015-16/30580,Buildings,Completed,NE-ROYAPURAM,50,915000,providing water supply arrangements and other Improvements to corporation primary school at durai street in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/30582,Buildings,Completed,NE-ROYAPURAM,50,993000,Raising compound wall and improvements to C.H.S.S at S.N street in ward.50 unit.12 zone 5,Own Sources,5,2015-16,2016-17 NE/2015-16/30585,Parks,Completed,NE-ROYAPURAM,50,996000,Providing stainless steel hand rail at northern side pathway at N.R.T Park in Ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/30586,Parks,Completed,NE-ROYAPURAM,50,995000,Providing stainless steel hand rail at southern side pathway at N.R.T Park in Ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/30613,Buildings,Completed,NE-ROYAPURAM,61,452000,"PROVIDING ELETRIFICAL AND DRAINAGE ARRANGEMENTS TO GYM BUILDING AT CHINNAKULANDAI LANE IN DN-61,U-14,Z-5",Own Sources,5,2015-16,2018-19 NE/2015-16/30637,Parks,Completed,NE-ROYAPURAM,60,993000,"Formation of greeneries and Plantations at Southern side of Secretariat Park at Rajaji Salai in Dn-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/30645,Buildings,Completed,NE-ROYAPURAM,50,896000,Construction of toilet block and lighting arrangements inside park at NRT Service road in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/30646,Storm Water Drain,Completed,NE-ROYAPURAM,50,572000,"Providing FRC doors and pipe line for rain water disposal at kasigarden 1st & 2nd street from St. Xavier street in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/30647,Buildings,Completed,NE-ROYAPURAM,50,770000,"Improvements to NNMP SHED No.1090,1091 at shaik maistry street in ward.50 unit.12 zone.5",Own Sources,5,2015-16,2016-17 NE/2015-16/30855,Footpath,Completed,NE-ROYAPURAM,58,996000,"Improvements to Granite foot path at Ritherton road west side(From ch 400m to 600m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2017-18 NE/2015-16/30856,Footpath,Completed,NE-ROYAPURAM,58,999000,"Improvements to Granite foot path at Ritherton road west side(From ch 200m to 400m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2017-18 NE/2015-16/30857,Footpath,Completed,NE-ROYAPURAM,58,999000,"Improvements to Granite foot path at Ritherton road west side(From Doveton signal ch Om to 200m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2017-18 NE/2015-16/30858,Footpath,Completed,NE-ROYAPURAM,58,997000,"Improvements to Granite foot path at Ritherton road west side(From ch 600m to 870m) in Dn.58,Unit.14,Zone.05.",Own Sources,5,2015-16,2017-18 NE/2015-16/30864,Roads,Completed,NE-ROYAPURAM,58,972000,"Providing Pipe line for disposal of rain water at E.V.K. Sampath Salai (Ch.0m to 210m) in Ward-58, Unit-14, Zone-V.",Own Sources,5,2015-16,2018-19 NE/2015-16/30865,Roads,Completed,NE-ROYAPURAM,58,998000,"IMPROVEMENT TO STORM WATER DRAIN AT ROTTI KIDANGU THIRU VENGADAM STREET IN DN-58, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/30866,Storm Water Drain,Completed,NE-ROYAPURAM,58,974000,"Providing Pipe line for disposal of rain water at E.V.K. Sampath Salai (Ch.210m to 400m) in Ward-58, Unit-14, Zone-V.",Own Sources,5,2015-16,2019-20 NE/2015-16/30867,Storm Water Drain,Completed,NE-ROYAPURAM,58,976000,"Providing Pipe line for disposal of rain water at E.V.K. Sampath Salai (Ch.400m to 585m) in Ward-58, Unit-14, Zone-V.",Own Sources,5,2015-16,2018-19 NE/2015-16/30911,Parks,Completed,NE-ROYAPURAM,59,816000,"PROVIDING STAINLESS STEEL HAND RAIL IN FRONT OF TNPSC AT FRAZER BRIDGE ROADS (LHS) IN DIVSION 59, UNIT14, ZONE V",Own Sources,5,2015-16,2016-17 NE/2015-16/30912,Buildings,Completed,NE-ROYAPURAM,59,993000,"PROVIDING STAINLESS STEEL HAND RAILS AND LAYING FOOTPATH TILES AT FRAZER BRIDGE ROAD MMC HOSTEL IN DN-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31015,Parks,Completed,NE-ROYAPURAM,53,759000,"House keeping for RDC North Office and Zonal Office-V in Dn-53, Unit-12, Zone-V.",Own Sources,5,2015-16,2018-19 NE/2015-16/31079,Roads,Completed,NE-ROYAPURAM,53,999000,"REPAIRS AND IMPROVEMENTS TO URDHU SCHOOL AT JAYARAM STREET IN DN-53,UNIT-12,ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31082,Buildings,Completed,NE-ROYAPURAM,60,965000,"Construction of Additional Women Toilets Block at Annai Sathya Nagar in Dn.60, unit-13, zone-5",Own Sources,5,2015-16,2017-18 NE/2015-16/31083,Buildings,Completed,NE-ROYAPURAM,60,965000,"Construction of Additional Men Toilets Block at Annai Sathya Nagar in Dn.60, unit-13, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31239,Buildings,Completed,NE-ROYAPURAM,49,565000,"Providing Bore Work and Electrical Arrangement for CWC Hospital in Ward-49, Unt-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31290,Roads,Completed,NE-ROYAPURAM,50,985000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT EAST MADHA CHURCH STREET IN DN-50, UNIT-12,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/31449,Roads,Completed,NE-ROYAPURAM,58,998000,ANNUAL MANITENANCE OF MY LADYS PARK AT DN-58 (MAINTENANCE PERIOD FOR SIX MONTH,Own Sources,5,2015-16,2016-17 NE/2015-16/31450,Buildings,Completed,NE-ROYAPURAM,59,586000,"IMPROVEMENTS TO STORM WATER DRAIN AND PROVIDING SLIT CATCH PIT AT S.M NAGAR MAIN ROAD, AND PALLAVAN SALAI IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/31451,Buildings,Completed,NE-ROYAPURAM,59,989000,"DESILTING AND IMPROVEMENTS TO SIDE DRAIN AT GANDHI NAGAR E-BLOCK , MAIN ROAD 1ST STREET TO 9TH STREET IN DIVISION-59 UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/31452,Buildings,Completed,NE-ROYAPURAM,59,780000,"DESILTING AND IMPROVEMENTS TO SIDE DRAIN AT PALLAVAN NAGAR IN DIVISION-59 UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/31453,Buildings,Completed,NE-ROYAPURAM,59,991000,"IMPROVEMENTS TO STATUE THIRU. TANGUTURI PRAKASAM PANTHALU AND CENTER MEDIAN OPP TO RAJA ANNA MALAI MANDRAM (SIGNAL) AT MUTHU SAMY SALAI IN DN-59, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/31463,Roads,Completed,NE-ROYAPURAM,58,912000,"ATTENDING PATCH WORK AT VALIYAMMAL STREET (WEST SIDE) IN DIVISION-58, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31464,Roads,Completed,NE-ROYAPURAM,60,995000,"Granite Cladding Flooring Work at Secretary Park at Rajaji Salai at Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31466,Buildings,Completed,NE-ROYAPURAM,60,999000,"Providing separator for parking beneath bridge at Rajaji Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31513,Buildings,Completed,NE-ROYAPURAM,49,998000,"Providing of Gents Gym for Corporation Staff in Zonal Office at Basin Bridge Road in Ward-53 unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31611,Footpath,Completed,NE-ROYAPURAM,60,998000,"Improvement to Footpath at North Fort Side Road in Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31612,Roads,Completed,NE-ROYAPURAM,60,880000,"Providing Submergible motor for Collecting Well of Reverse Bank Subway in ward-60, unit-13, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/31734,Parks,Completed,NE-ROYAPURAM,52,998000,"SUPPLYIND AND FIXING PLAY APPARATUS AND COLOUR WASHING IN O.S.H ROAD PLAY GROUND UNDER WARD COUNSILOR FUND(2015-2016) IN DN-52,U-12,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/31761,Buildings,Completed,NE-ROYAPURAM,56,980000,"CONSTRUCTION OF COMPOUND WALL AT TERRACE GARDEN PARK AT EBRAHIM SALAI (mc road to 130m)IN DN-56,U-13,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/31763,Buildings,Completed,NE-ROYAPURAM,56,990000,"CONSTRUCTION OF COMPOUND WALL AT TERRACE GARDEN PARK AT EBRAHIM SALAI(130M TO 260) IN DN-56,U-13,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/31826,Buildings,Completed,NE-ROYAPURAM,50,825000,Improvements to chennai urudhu school ( south side building) and toilet block in Arthoon road at ward.50 unit .12 zone.v,Own Sources,5,2015-16,2016-17 NE/2015-16/31828,Buildings,Completed,NE-ROYAPURAM,50,872000,Providing stainless steel hand rail at easternside and westernside pathway at N.R.T Park in ward.50 unit.12 zone.v,Own Sources,5,2015-16,2016-17 NE/2015-16/31873,Roads,Completed,NE-ROYAPURAM,58,594000,"ATTENDING PATCH WORK AT VALIYAMMAL STREET (SOUTH) AND PROVIDING SPEED BREAKER AT NAVAL HOSPITAL ROAD AND BARRACKS ROAD IN DIVISION-58, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32042,Buildings,Completed,NE-ROYAPURAM,59,534000,"PAINTING OF GARBAGE REMOVAL PARTICULARS IN METAL COMPACTOR BINS IN ROADS AT VARIOUS STREET IN DIV-58,59, UNIT-14, ZONE-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/32224,Buildings,Completed,NE-ROYAPURAM,60,993000,"Improvement to Walking Pathway inside the Secretariat Park in Rajaji Salai in ward-60, unit-14, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32225,Roads,Completed,NE-ROYAPURAM,60,935000,"Laying the B.T patches in front of Annai Sathya nagar Public convenience in ward-60, unit-13, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32226,Buildings,Completed,NE-ROYAPURAM,60,996000,"Providing water Supply arrangement to Secretariat park in Rajaji Salai in ward-60, Unit-13, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32227,Buildings,Completed,NE-ROYAPURAM,60,990000,"Providing Stainless Handrail in Secretariat Park Backside of Fountain in rajaji Salai in ward-60, unit-13, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32228,Parks,Completed,NE-ROYAPURAM,60,990000,"Providing Stainless Handrail in Secretariat Park Adjust side to Fountain in rajaji Salai in ward-60, unit-13, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32229,Buildings,Completed,NE-ROYAPURAM,60,991000,"Providing Stainless Handrail in Secretariat Park Southern side in rajaji Salai in ward-60, unit-13, zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32231,Roads,Completed,NE-ROYAPURAM,60,992000,"Providing street Name board at Various Street in ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32232,Roads,Completed,NE-ROYAPURAM,60,992000,"Providing street Name board at Various Street in ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32233,Roads,Completed,NE-ROYAPURAM,60,995000,"Providing Granite Flooring at Southern side Secretariat Park in Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32234,Parks,Completed,NE-ROYAPURAM,60,998000,"Providing Granite Flooring at Southern side Secretariat Park in Ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32235,Roads,Completed,NE-ROYAPURAM,60,686000,"Improvement to Center Median and Traffic island in Rajaji Salai in ward-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32239,Parks,Completed,NE-ROYAPURAM,60,991000,"Greenery Arrangement to Secretariat Park at Rajaji Salai in Div-60, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32253,Buildings,Completed,NE-ROYAPURAM,62,624000,"PAINTING OF GARBAGE REMOVAL PARTICULARS IN METAL COMPACTOR BINS IN ROADS AT VARIOUS STREET IN DIV-61,62,63, UNIT-14, ZONE-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/32297,Buildings,Completed,NE-ROYAPURAM,61,500000,"PROVIDING AND FIXING OF GYM APPARATUS IN GYM BUILDING AT CHINNAKULANDAI LANE IN DN-61,U-14,Z-5",Own Sources,5,2015-16,2018-19 NE/2015-16/32308,Roads,Completed,NE-ROYAPURAM,51,62000,"Black and white painting to footpath kerbs at Cemetry road and providing speed breaker at Kalingarayan 1st street in Ward-51, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/32338,Buildings,Completed,NE-ROYAPURAM,59,520000,"IMPROVEMENTS TO STORM WATER DRAIN AND PROVIDING SLIT CATCH PIT AT GANDHI NAGAR E-BLOCK 1ST STREET TO 6TH STREET IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/32347,Roads,Completed,NE-ROYAPURAM,56,450000,"IMPROVEMENTS TO CENTER MEDIAN AT DIVISION OFFICE OPPOSITE IN DIV-56, UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32352,Buildings,Completed,NE-ROYAPURAM,58,280000,"PROVIDING WATER AND ELECTRICAL FACILITIES AT A.P ROAD CMS,DRO OFFICE,ALLIKULLAM SHOPPING COMPLEX, AND COUNCILOR OFFICE IN DIV-58, UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32357,Buildings,Completed,NE-ROYAPURAM,54,999000,"providing gym equipment and Improvements to gym at walltax in Dn.54,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/32358,Buildings,Completed,NE-ROYAPURAM,54,999000,"Improvements to the children creche,old aged school and gym at wall tax road in Dn-54,Unit-13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/32368,Roads,Completed,NE-ROYAPURAM,49,969000,PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DIV-49 UNT-12 ZONE-5,Own Sources,5,2015-16,2018-19 NE/2015-16/32411,Parks,Completed,NE-ROYAPURAM,56,704000,"CONSTRUCTION OF COMPOUND WALL AT TERRACE GARDEN PARK(260M TO 325M)AT EBRAHIM SALAI IN DN-56,U-13,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32513,Roads,Completed,NE-ROYAPURAM,55,999000,"REPAIRS AND IMPROVEMENTS TO BARRACKS PLAY GROUND,16 TH DAYS CEREMONY HALL AND GYM AT PORTIGUESE CHURCH STREET IN DN-55 ,UNIT-13, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32528,Buildings,Completed,NE-ROYAPURAM,61,821000,"PROVIDING VESSELS,KITCHEN-WARE AND STAINLESS STEEL ROUND TABLE TO AMMA UNAVAGAM AT PANTHEON SALAI IN DIV-61,UN-14,Z-5",Own Sources,5,2015-16,2016-17 NE/2015-16/32549,Buildings,Completed,NE-ROYAPURAM,50,997000,Providing rainwater harvesting at various street in ward.50 unit.12 zone 5,Own Sources,5,2015-16,2016-17 NE/2015-16/32550,Buildings,Completed,NE-ROYAPURAM,50,89000,"REPAIRS AND IMPROVEMENT TO FOOTPATH AT WEST MADHA STREET { OPP TO PETERS SCHOOL} IN DN 50,UNIT-12,ZONE-5",Own Sources,5,2015-16,2018-19 NE/2015-16/32551,Buildings,Completed,NE-ROYAPURAM,50,999000,"IMPROVEMENT TO FOOTPATH AT MS KOIL STREET AND EAST KALMANDAPAM ROAD IN DN-50, UNIT-12,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/32570,Roads,Completed,NE-ROYAPURAM,55,1475000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at St Xavier Street (Part) by paver finisher in Dn.55,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32571,Roads,Completed,NE-ROYAPURAM,55,1880000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Seven Wells Street (Part) by paver finisher in Dn.55,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32572,Roads,Completed,NE-ROYAPURAM,55,1864000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Portughese Church Street (Part) by paver finisher in Dn.55,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32573,Roads,Completed,NE-ROYAPURAM,55,1159000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Barracks Street (Part) by paver finisher in Dn.55,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32574,Roads,Completed,NE-ROYAPURAM,55,413000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Barracks 1st Lane (Part) by paver finisher in Dn.55,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32575,Roads,Completed,NE-ROYAPURAM,54,2318000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Mint Street (Part) Reach-I by paver finisher in Dn.54,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32576,Roads,Completed,NE-ROYAPURAM,54,2283000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Mint Street (Part) Reach-II by paver finisher in Dn.54,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32577,Roads,Completed,NE-ROYAPURAM,54,1756000,"Attending to Temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Mint Street (Part) Reach-III by paver finisher in Dn.54,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32578,Roads,Completed,NE-ROYAPURAM,54,999000,"ATTENDING PROFILE CORRECTION AT WALL TAX ROAD And Various Street IN DIV-54,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/3258,Road Cut,Completed,NE-ROYAPURAM,59,690000,"Restoration of Road cut made by TNEB at Rasappa (C) St, Isaac St, Mint St (Total Length-350 M) in Div-59, Unit-14, Zone-5.",Deposit Works,5,2015-16,2016-17 NE/2015-16/32582,Roads,Completed,NE-ROYAPURAM,58,968000,"Providing centermedian at Narayana guru salai and water table and improvements to footpath at Ritherdon road in Dn-58,Unit-14, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32585,Roads,Completed,NE-ROYAPURAM,58,974000,"Attending repairs to damaged roads at Mookkathal street, Vaikkakaran stret, Baracks street, Stringer street and Naval Hospital Road in Ward-58, Unit-14, Zone-5.",Own Sources,5,2015-16,2018-19 NE/2015-16/3259,Road Cut,Completed,NE-ROYAPURAM,59,868000,"Restoration of Road cut made by TNEB at Devaraj (M) St, Edapalayam Road, Periara St (Total length-360 M) in Div-59, Unit-14, Zone-5.",Deposit Works,5,2015-16,2016-17 NE/2015-16/3260,Road Cut,Completed,NE-ROYAPURAM,59,710000,"Restoration of Road cut made by TNEB at Naniappan St, E.K. Agraharam St, Venkatachala (M) St, Mannar St Dhannppa St, Ayya (P) St, Ragunayakalu St (Total Length-360 M) in Div-59, Unit-14, Zone-5.",Deposit Works,5,2015-16,2016-17 NE/2015-16/32617,Roads,Completed,NE-ROYAPURAM,58,965000,"Attending repairs to the damaged roads at Jothivenkatachalam street, Kalathiappa street, Dr. Alagappa road, Jothivenkatachalam street and providing speed breaker at Jothivenkatachalam street, Raja Muthiah salai in Ward-58, Unit-14, Zone-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/32619,Roads,Completed,NE-ROYAPURAM,50,480000,"Attending to temporary restoration of damaged interior road due to flood in north east monsoon 2015 at Andiappan Street (Part) by Paver finisher in Dn.50,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32620,Roads,Completed,NE-ROYAPURAM,50,1028000,"Attending to temporary restoration of damaged interior road due to flood in north east monsoon 2015 at Flagstaff Street (Part) by Paver finisher in Dn.50,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32621,Roads,Completed,NE-ROYAPURAM,50,552000,"Attending to temporary restoration of damaged interior road due to flood in north east monsoon 2015 at North Madha Church Street (Part) by Paver finisher in Dn.50,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32622,Roads,Completed,NE-ROYAPURAM,50,552000,"Attending to temporary restoration of damaged interior road due to flood in north east monsoon 2015 at P.V.Koil Street (Part) by Paver finisher in Dn.50,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32623,Roads,Completed,NE-ROYAPURAM,50,1449000,"Attending to temporary restoration of damaged interior road due to flood in north east monsoon 2015 at Sheik Maistry Street (Part) by Paver finisher in Dn.50,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32624,Roads,Completed,NE-ROYAPURAM,50,1028000,"Attending to temporary restoration of damaged interior road due to flood in north east monsoon 2015 at St.Xavier Street (part) by Paver finisher in Dn.50,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32656,Roads,Completed,NE-ROYAPURAM,58,976000,"Attending repairs to the damaged roads at Vadamalai st., Vepery church road, EVK Sampath road, Mattukkara Veerabathran street and Woothukkattan street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/32657,Roads,Completed,NE-ROYAPURAM,51,837000,"Attending to temporary restoration of damaged interior road due to flood in North East Monsoon 2015 at Manikandan 6th Street (Part) by paver finisher in Dn.51,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32658,Roads,Completed,NE-ROYAPURAM,51,412000,"Attending to temporary restoration of damaged interior road due to flood in North East Monsoon 2015 at Ramanujam Street and JP Koil Street (Part)by paver finisher in Dn.51,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32659,Roads,Completed,NE-ROYAPURAM,51,620000,"Attending to temporary restoration of damaged interior road due to flood in North East Monsoon 2015 at Perambalu Street (Part) by paver finisher in Dn.51,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32660,Roads,Completed,NE-ROYAPURAM,56,539000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Seivamuthaiya 1st Lane to 5th Lanes (Part) by Paver finisher in Dn.56,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32661,Roads,Completed,NE-ROYAPURAM,56,468000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Shanmugam Lane (Part) by Paver finisher in Dn.56,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32662,Roads,Completed,NE-ROYAPURAM,56,3589000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Coral Merchant Street (Part) by Paver finisher in Dn.56,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32663,Roads,Completed,NE-ROYAPURAM,56,464000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Savrimuthu Lane (Part) by Paver finisher in Dn.56,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32664,Roads,Completed,NE-ROYAPURAM,56,177000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Asirvathapuram 5th Lane (Part) by Paver finisher in Dn.56,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32665,Roads,Completed,NE-ROYAPURAM,58,970000,"Attending repairs to the damaged roads at Kariappa street and Clements road in Ward-58, Unit-14, Zone-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/32666,Roads,Completed,NE-ROYAPURAM,57,2212000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Mint Street (Part) by Paver finisher Dn.57,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32667,Roads,Completed,NE-ROYAPURAM,57,2585000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at N.S.C.Bose Road (Part) by Paver finisher Dn.57,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32668,Roads,Completed,NE-ROYAPURAM,57,3161000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Anna Pillai Street (Part) by Paver finisher Dn.57,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32669,Roads,Completed,NE-ROYAPURAM,60,2458000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Linghi ( C ) Street (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32670,Roads,Completed,NE-ROYAPURAM,60,4636000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Thambu ( C ) Street (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32671,Roads,Completed,NE-ROYAPURAM,60,632000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Muthumari Street (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32672,Roads,Completed,NE-ROYAPURAM,60,302000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Tuckers Lane (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32673,Roads,Completed,NE-ROYAPURAM,60,2458000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Mokker Nallamuthu Street (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32674,Roads,Completed,NE-ROYAPURAM,60,1264000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Second Beach Lane(Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32675,Roads,Completed,NE-ROYAPURAM,60,737000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Phillips street (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32676,Roads,Completed,NE-ROYAPURAM,60,579000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Sunguram ( C ) Street (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32677,Roads,Completed,NE-ROYAPURAM,60,702000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Periyana (M) Street (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32679,Roads,Completed,NE-ROYAPURAM,60,309000,"Attending to temporary restoration of damaged interior roads due to floods in North East Monsoon 2015 at Edge Mosque Lane (Part) by paver finisher in Dn.60,Unit-13,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32707,Buildings,Completed,NE-ROYAPURAM,51,998000,"Renovation of Laboratory building in Chennai High School in Manikandan 8th Street Under WDS IN DN-51 ,UNIT-12,ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/32848,Footpath,Completed,NE-ROYAPURAM,50,819000,Improvements to Centre median and Foot path at S.N street and M.S kovil street in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2016-17 NE/2015-16/32910,Buildings,Completed,NE-ROYAPURAM,58,981000,"IMPROVEMENTS TO YOGA STAGE, PROVIDING TILES, NAME BOARD AND STATUE AT MY LADIES PARK IN DIVISION-58, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/3292,Buildings,Completed,NE-ROYAPURAM,51,999000,"IMPROVEMENT TO STORM WATER DRAIN AND CHOKE PIT ,SILT COLLECTION TANK AND GRATTING AT VARIOUS STREET IN DN -51, UNIT-12 ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/32923,Buildings,Completed,NE-ROYAPURAM,58,990000,"IMPROVEMENTS TO FOOTPATH, PAINTING COMPOUND WALL AND REPAIRS TO FOUNTAIN WEST AND EAST SIDE AT MY LADIES PARK IN DIVISION-58, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/32926,Buildings,Completed,NE-ROYAPURAM,58,994000,"IMPROVEMENTS TO FOOTPATH AND PAINTING COMPOUND WALL AND WATER ARRANGEMENTS AT MY LADIES PARK IN DIVISION-58, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/32975,Roads,Completed,NE-ROYAPURAM,57,910000,"IMPROVEMENTS TO BUS SHELTER AT THE JUNCTION OF WATER BASIN STREET IN DIV-57,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32976,Roads,Completed,NE-ROYAPURAM,57,990000,"IMPROVEMENTS TO BUS SHELTER NEAR THACKER CHURCH AT PRAKASAM SALAI IN DIV57,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2019-20 NE/2015-16/32977,Roads,Completed,NE-ROYAPURAM,57,940000,"IMPROVEMENTS TO BUS SHELTER NEAR CORPORATION SHOPPING COMPLEX AT WALL TAX ROAD IN DIV-57,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32978,Roads,Completed,NE-ROYAPURAM,57,960000,"IMPROVEMENTS TO BUS SHELTER AT KALYANAPURAM AT WALL TAX ROAD IN DIV-57,UNIT-13,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32979,Roads,Completed,NE-ROYAPURAM,57,999000,"ATTENDING PROFILE CORRECTION AT WALL TAX ROAD AND AT VARIOUS PLACES IN DIV-57,UNIT-13, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/32999,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending profile correction in TNHB tenements at Elephant gate bridge road and various places in Dn-57,Unit-13,Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33000,Buildings,Completed,NE-ROYAPURAM,57,999000,"Improvements to corporation play ground at Water basin street in Dn.57,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33001,Buildings,Completed,NE-ROYAPURAM,57,998000,"Providing electrical arrangements and fixing electrical name board to Amma unavagam and various corporation buildings in Dn.57,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33002,Buildings,Completed,NE-ROYAPURAM,57,999000,"Improvements to Greater Corporation printing press at Walltax road Dn.57,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33039,Roads,Completed,NE-ROYAPURAM,59,1097000,"Attending Patch work by Paver finisher at Frazer Bridge Road in Dn.59,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33040,Roads,Completed,NE-ROYAPURAM,59,2161000,"Attending Patch work by Paver finisher at Mint Street in Dn.59,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33042,Roads,Completed,NE-ROYAPURAM,58,1123000,"Attending Patch work by Paver finisher at R.T. (M) Street, Dn-58, Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33048,Roads,Completed,NE-ROYAPURAM,61,2247000,"Attending Patch work by Paver finisher at Montieth Road in Dn.61,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33050,Roads,Completed,NE-ROYAPURAM,62,1475000,"Attending Patch work by Paver finisher at Singanna Street in Dn.62,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33051,Roads,Completed,NE-ROYAPURAM,62,686000,"Attending Patch work by Paver finisher at Mangapathy Street in Dn.62,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33053,Roads,Completed,NE-ROYAPURAM,63,1264000,"Attending Patch work by Paver finisher at Burrah (S) Street in Dn.63,Unit-14,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33054,Roads,Completed,NE-ROYAPURAM,63,2881000,"Attending Patch work by Paver finisher at South Coovam River Road in Dn.63,Unit-14, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33132,Buildings,Completed,NE-ROYAPURAM,55,929000,"REPAIRS AND IMPROVEMENTS TO COMMUNITY HALL AT ST. XAVIER STREET IN DIVISION-55, UNIT-13, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/33176,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street from the junction of prakasam salai (From ch 0m to 55m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33177,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street (From ch 55m to 110m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33178,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street (From ch 110m to 165m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33179,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street (From ch 165m to 220m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33180,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street (From ch 220m to 275m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33181,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street (From ch 275m to 330m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33182,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street (From ch 330m to 385m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33183,Roads,Completed,NE-ROYAPURAM,55,999000,"Attending profile correction at P.V.Iyer street (From ch 385m to 440m) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33185,Roads,Completed,NE-ROYAPURAM,52,997000,"PAINTING TO ROYAPURAM OLD BRIDGE IN DIV-52,UNIT-12,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33186,Roads,Completed,NE-ROYAPURAM,52,997000,"PAINTING TO ROYAPURAM NEW BRIDGE IN DIV-50,UNIT-12,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33187,Roads,Completed,NE-ROYAPURAM,50,999000,"IMPROVEMENTS TO FOOTPATH AT CEMETRY ROAD IN DIV-52,UNIT-12,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33189,Storm Water Drain,Completed,NE-ROYAPURAM,55,999000,"Improvements to storm water drain at P.V.Iyer street (north side) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33190,Storm Water Drain,Completed,NE-ROYAPURAM,55,999000,"Improvements to storm water drain at P.V.Iyer street (south side) in Dn.55,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33333,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Ayyappa street (From ch 0m to 65m) in Dn.60,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33334,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Ayyappa street (From ch 65m to 130m) in Dn.60,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33336,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Ayyappa street (From ch 130m to 195m) in Dn.60,Unit.14,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33337,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Ayyappa street (From ch 195m to 265m) in Dn.60,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33339,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Narayana sarang garden street (From ch 0m to 55m) in Dn.60,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33340,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Narayana sarang garden street (From ch 55m to 110m) in Dn.60,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33341,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Adham street (From ch 0m to 70m) in Dn.60,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33342,Roads,Completed,NE-ROYAPURAM,60,999000,"Attending profile correction to cement concrete road at Adham street (From ch 70m to 140m) in Dn.60,Unit.13,Zone.05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33592,Roads,Completed,NE-ROYAPURAM,55,999000,"Providing interlocking tiles to south side of P.V.Iyer street in Dn-55, Unit-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33593,Roads,Completed,NE-ROYAPURAM,55,999000,"Providing interloking tiles to north side of P.V.Iyer street in Dn-55, Unit-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33622,Buildings,Completed,NE-ROYAPURAM,60,999000,"Proposed construction of to ground floor of Amma unavagam at Ayyappa street in Dn-60,Unit-13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33623,Buildings,Completed,NE-ROYAPURAM,60,999000,"Improvements to ground floor of Amma unavagam at Ayyappa street in Dn-60,Unit-13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33624,Buildings,Completed,NE-ROYAPURAM,60,999000,"Additional improvements to ground floor of Amma unavagam at Ayyappa street in Dn-60,Unit-13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33625,Buildings,Completed,NE-ROYAPURAM,60,999000,"Proposed construction of first floor floor of Amma unavagam at Ayyappa street in Dn-60,Unit-13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33626,Buildings,Completed,NE-ROYAPURAM,60,999000,"Improvements to first floor of Amma unavagam at Ayyappa street in Dn-60,Unit-13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33627,Buildings,Completed,NE-ROYAPURAM,60,999000,"Providing electrical and plumbing arrandements to Amma unavagam at Ayyappa street Dn-60,Unit-13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33714,Buildings,Completed,NE-ROYAPURAM,60,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT INSIDE TAMIL NADU SECRETRAIT IN DIV -60,UNIT -13,ZONE -5",Own Sources,5,2015-16,2017-18 NE/2015-16/33715,Buildings,Completed,NE-ROYAPURAM,60,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT INSIDE TAMIL NADU SECRETRAIT IN DIV -60,UNIT -13,ZONE -5",Own Sources,5,2015-16,2017-18 NE/2015-16/33717,Buildings,Completed,NE-ROYAPURAM,60,714000,"SUPPLY AND INSTALLATION FOR E-TOILET (SHE TOILET) INCLUDING NAPKIN VENDING MACHINE INSIDE TAMIL NADU SECRETRAIT IN DIV-60 UNIT-13, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/33718,Buildings,Completed,NE-ROYAPURAM,60,714000,"SUPPLY AND INSTALLATION FOR E-TOILET (SHE TOILET) INCLUDING NAPKIN VENDING MACHINE INSIDE TAMIL NADU SECRETRAIT IN DIV-60 UNIT-13, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/33775,Roads,Completed,NE-ROYAPURAM,61,560000,"LAYING OF CEMENT CONCRETE ROAD AT BASHA 1st STREET,BASHA LANE AND KRISHNAPPA STREET(PART) IN DN61,U14,Z5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33810,Buildings,Completed,NE-ROYAPURAM,50,242000,Repairs to old corporation school converting night shelter at market lane in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2018-19 NE/2015-16/33811,Footpath,Completed,NE-ROYAPURAM,50,995000,"Improvements to Foot path at S N street and painting centre median and kerb wall at M.S kovil street, S N street East kalmandappam road in ward.50 unit.12 zone.5",Own Sources,5,2015-16,2018-19 NE/2015-16/33812,Buildings,Completed,NE-ROYAPURAM,50,286000,construction of ramp and other improvements to corporation buildings { election work} in ward.50 unit.12 zone.5,Own Sources,5,2015-16,2018-19 NE/2015-16/33815,Roads,Completed,NE-ROYAPURAM,60,996000,"LAYING OF INTERLOCKING BLOCKS ON EASTERN SIDE OF JEHAANGIR STREET IN DN60,U13,Z5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33816,Roads,Completed,NE-ROYAPURAM,60,995000,"LAYING OF INTERLOCKING BLOCKS ON WESTERN SIDE OF JEHAANGIR STREET IN DN60,U13,Z5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33819,Roads,Completed,NE-ROYAPURAM,59,765000,"LAYING OF CEMENT CONCRETE ROAD AT BANGARA AMMAN KOIL STREET IN DN59,U14,Z5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33821,Road Cut,Completed,NE-ROYAPURAM,62,342000,"RESTORATION OF ROAD CUT AT SAMI STREET IN DN62,U14,Z5.",Deposit Works,5,2015-16,2017-18 NE/2015-16/33830,Buildings,Completed,NE-ROYAPURAM,53,990000,"Improvements to public convienience at Stanley nagar 5th street in Div-53,Unit-12,Zone-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/33831,Buildings,Completed,NE-ROYAPURAM,53,997000,"Additional improvements to the public convineince at Stanley nagar 5th street & Providing FRC manhole doors at various places in Div-53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33832,Buildings,Completed,NE-ROYAPURAM,53,985000,"Improvements to P.C at C.B road in Div-53,Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33844,Footpath,Completed,NE-ROYAPURAM,57,997000,"Improvements to granite footpath at Ramanan street south side in Dn-57, Unit-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33845,Footpath,Completed,NE-ROYAPURAM,57,998000,"Improvements to granite footpath at Ramanan street north side in Dn-57, Unit-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33846,Footpath,Completed,NE-ROYAPURAM,57,997000,"Improvements to granite footpath at Anna (p) street in Dn-57, Unit-13, Z-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/33868,Buildings,Completed,NE-ROYAPURAM,57,999000,"Improvements to NNMP shed and providing dining area in CHS in Dn-57,Unit-13,Z-05.",Own Sources,5,2015-16,2018-19 NE/2015-16/33874,Buildings,Completed,NE-ROYAPURAM,57,998000,"Additional improvements to NNMP shed and providing dining area in CHS in Dn-57,Unit-13,Z-05.",Own Sources,5,2015-16,2018-19 NE/2015-16/33927,Storm Water Drain,Completed,NE-ROYAPURAM,53,990000,"Desilting the B canal and clearing the flora jungle from chainage of 0 to 50m in Div:53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33928,Storm Water Drain,Completed,NE-ROYAPURAM,53,990000,"Desilting the B canal and clearing the flora jungle from chainage of 50 to 100m in Div:53,Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33929,Storm Water Drain,Completed,NE-ROYAPURAM,53,990000,"Desilting the B canal and clearing the flora jungle from chainage of 100 to 150m in Div:53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33930,Storm Water Drain,Completed,NE-ROYAPURAM,53,999000,"Desilting the B canal and clearing the flora jungle from chainage of 150 to 200M in Div:53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33931,Storm Water Drain,Completed,NE-ROYAPURAM,53,997000,"Desilting the B canal and clearing the flora jungle from chainage of 200 to 250m in Div-53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33932,Storm Water Drain,Completed,NE-ROYAPURAM,53,997000,"Desilting the B canal and clearing the flora jungle from chainage of 250 to 300m in Div-53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33933,Storm Water Drain,Completed,NE-ROYAPURAM,53,997000,"Desilting the B canal and clearing the flora jungle from chainage of 300 to 350m in Div-53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33934,Storm Water Drain,Completed,NE-ROYAPURAM,53,997000,"Desilting the B canal and clearing the flora jungle from chainage of 350 to 400m in Div-53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33935,Storm Water Drain,Completed,NE-ROYAPURAM,53,990000,"Desilting the B canal and clearing the flora jungle from chainage of 400 to 450m in Div-53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33936,Storm Water Drain,Completed,NE-ROYAPURAM,53,990000,"Desilting the B canal and clearing the flora jungle from chainage of 450 to 500m in Div:53, Unit-12, Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33956,Buildings,Completed,NE-ROYAPURAM,57,997000,"Improvements to H.M room,staff room of Chennai high school at V.O.C salai in Dn-57,Unit-13,Z-05.",Own Sources,5,2015-16,2018-19 NE/2015-16/33967,Parks,Completed,NE-ROYAPURAM,61,972000,"IMPROVEM,ENTS TO GREENARAY , PLANTS FOR MAYOR SUNDAR ROA PARK AT RUKMANI LAKSMIPAHY SALAI IN DIVISION-61, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/33968,Footpath,Completed,NE-ROYAPURAM,61,994000,"IMPROVEMENTS TO ELECTRICAL AND WATER SUPPLY ARRANGEMENTS TO MAYOR SUNDARA RAO PARK AT RUKMANI LAKSHMIPATHY SALAI IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/33969,Electrical,Completed,NE-ROYAPURAM,61,991000,"IMPROVEMENTS TO FOOTPATH AND PAINTING FOR MAYAR SUNDHAR RAO PARK AT RUKMANI LAKSHMI PATHY SALAI IN DIVISION - 61, UNIT - 14, ZONE - 5",Own Sources,5,2015-16,2016-17 NE/2015-16/33980,Roads,Completed,NE-ROYAPURAM,62,990000,"IMPROVEMENTS TO FOOTPATH, PROVIDING GRILL AND SHELTER TO MAY DAY PARK AT DUPUTY MAYAR KABALAMOORTHY ROAD IN DIVISION - 62, UNIT - 14, ZONE - 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/33981,Footpath,Completed,NE-ROYAPURAM,62,995000,"IMPROVEMENTS TO PAINTING, ART WORK TO MAY DAY PARK AT DEPUTY MAYOR KABALAMOORTHY ROAD IN DIVISION-62, UNIT-14, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/33982,Roads,Completed,NE-ROYAPURAM,62,957000,"IMPROVEMENTS TO ELECTRICAL ARRANGEMENTS AND GARDEN WATER SUPPLY ARRANGEMENTS TO MAY DAY PARK AT DEPUTY MAYOR KABALA MOORTHY SALAI IN DIV-62, UNIT-14",Own Sources,5,2015-16,2016-17 NE/2015-16/34074,Parks,Completed,NE-ROYAPURAM,61,991000,"IMPROVEMENTS TO FOOTPATH AND CONSTRUCTIONS OF COMPOUND WALL TO GANDHI IRVIN PARK AT GANDHI IRVIN ROAD IN DIVISION-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/34075,Buildings,Completed,NE-ROYAPURAM,61,899000,"IMPROVEMENTS TO WATER SUPPLY ARRANGEMENTS AND PAINTING WORKS TO GANDHI IRVIN PARK AT GANDHI IRVIN ROAD IN DIVISION-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/34076,Footpath,Completed,NE-ROYAPURAM,61,990000,"IMPROVEMENTS TO ELECTRICAL ARRANGEMENTS AND PROVIDING CHILDRENS PLAYMATERIAL TO GANDHI IRVIN PARK AT GANDHI IRVIN ROAD IN DIVISION-61, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/34091,Buildings,Completed,NE-ROYAPURAM,61,989000,"IMPROVEMENTS AND FORMING GREENARY AND PLANTS TO GANDHI ERVIN PARK AT GANDHI IRVIN ROAD IN DIVISION-61, UNIT-14, ZONE-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/34131,Buildings,Completed,NE-ROYAPURAM,59,993000,"ATTENDING PATCH WORK WITH M20 GRADE READY MIX AT PALLAVAN NAGAR AND SATHIYAVANI MUTHU NAGAR IN DIVISION-59, UNIT-14, ZONE-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/34135,Buildings,Completed,B-Buildings,55,769000,"IMPROVEMENTS TO WATER SUPPLY ARRANGEMENTS AND ELECTRICAL ARRANGEMENTS TO HEALTH CENTER (1st Floor) AT APPU MAISTRY STREET IN DIVISION-55, IUNIT-13, ZONE-05.",Own Sources,5,2015-16,2017-18 NE/2015-16/34136,Buildings,Completed,B-Buildings,55,629000,"REPAIRS AND IMPROVEMENTS TO HEALTH CENTER (1ST FLOOR) AT APPU MAISTRY STREET IN DIVISION-55, UNIT-13, ZONE-05",Own Sources,5,2015-16,2017-18 NE/2015-16/34562,Buildings,Completed,B-Buildings,63,975000,Improvements to Health Post at Kanchipuram Pachaiappan Street in Division 63 Zone 5,Own Sources,5,2015-16,2017-18 NE/2015-16/34620,Roads,Completed,NE-ROYAPURAM,49,227000,"Attending Patches work by Paver Finisher at Bashyam Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/34621,Roads,Completed,NE-ROYAPURAM,49,281000,"Attending to temporary restoration of damaged interior road due to flood in North East Monsoon 2015 at Singara Garden 8th Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/34622,Roads,Completed,NE-ROYAPURAM,49,351000,"Attending to temporary restoration of damaged interior road due to flood in North East Monsoon 2015 at Somu 6th Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/34623,Roads,Completed,NE-ROYAPURAM,49,527000,"Attending to temporary restoration of damaged interior road due to flood in North East Monsoon 2015 at Singara Garden 4th Street (Part) by paver finisher in Dn.49,Unit-12,Zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/34873,Buildings,Completed,NE-ROYAPURAM,49,950000,"TO CARRY OUT THE MOONSON RELATED WORKS ATTENDING WATER STAGNATION TO PROVIDING LINK TO SWD AT VARIOUS STREET DIV-49, UNIT-12, ZONE-5",Own Sources,5,2015-16,2018-19 NE/2015-16/3545,Playfields,Completed,NE-ROYAPURAM,58,690000,"IMPROVEMENTS TO TRAFIC ISLAND AT Sydams Road (opp to Taluka Office ) in Ward-58, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/3557,Buildings,Completed,NE-ROYAPURAM,58,658000,"IMPROVEMENTS TO PC at Sydams Road (in front of My Lady?s Parks) in Ward-58, Unit-14, Zone-5.",Own Sources,5,2015-16,2017-18 NE/2015-16/3927,Storm Water Drain,Completed,NE-ROYAPURAM,61,151000,"IMPROVEMENTS TO STORM WATER DRAIN AT HALLS ROAD & BOOPATHI NAGAR IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/3929,Buildings,Completed,NE-ROYAPURAM,61,179000,"IMPROVEMENTS TO PUBLIC CONVEYANCE AT VARIOUS LOCATION & AMMA UNAVAGAM AND SCHOOLS IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/3931,Buildings,Completed,NE-ROYAPURAM,61,82000,"IMPROVEMENTS TO GROUP PIN AT VARIOUS STREETS IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/3932,Roads,Completed,NE-ROYAPURAM,61,119000,"ROAD WIDENING AT ATHITHANAR SALAI AND ATTENDING CC PATCHWORK AT RAMANATHAN SALAI, PANTHEON SALAI IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/3933,Buildings,Completed,NE-ROYAPURAM,61,158000,"POOPATHI NAGAR PUBLIC CONVEYANCE DRAINAGE ARRENGEMENTS IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/3934,Buildings,Completed,NE-ROYAPURAM,61,256000,"GUNGE SUB WAY BRIDGE FROM POLICE QUARTERS WELL TO PIPE LINE ARRENGEMENTS IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/4235,Buildings,Completed,NE-ROYAPURAM,58,670000,"Demolition of existing dangerous shopping complex, 'B' Block building opp. to Salt Quarters Kannapar Thidal in Div-58, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/4236,Buildings,Completed,NE-ROYAPURAM,58,670000,"Demolition of existing dangerous shopping complex, 'A' Block building opp. to Salt Quarters Kannapar Thidal in Div-58, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/4320,Roads,Completed,NE-ROYAPURAM,58,970000,"Supplying and Providing FRC Doors for Various Street at SWD in DN -58, Unit -14, zone -4.",Own Sources,5,2015-16,2016-17 NE/2015-16/4486,Playfields,Completed,NE-ROYAPURAM,61,690000,"PROVIDING FENCING ARRANGEMENTS AND CONSTRUCTION OF REST ROOM IN PLAY GROUND AT RANGACHARI STREET IN DN-61,U-14,Z-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/4509,Roads,Completed,NE-ROYAPURAM,58,419000,"ATTENDING PATCH WORKS AT VARIOUS PLACES,IMPROVEMENTS TO FOOTPATH AT JYOTHI VENKATACHALAM STREET,PROVIDING PLATFORMS FOR COMPACTOR BINS AT VARIOUS PLACES AND PROVIDING GOAL POST TO NAVAL HOSPITAL PLAYFIELD IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/4560,Buildings,Completed,NE-ROYAPURAM,51,960000,improvements to division .51 office at manigandan 3st street in ward.51 u.12 z.5,Own Sources,5,2015-16,2016-17 NE/2015-16/4723,Storm Water Drain,Completed,NE-ROYAPURAM,58,999000,"Improvements to storm water drain and Providing Soak pit,silt collection tank and gratings in existing SWD at various streets in ward-58,unit-14,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/4819,Footpath,Completed,NE-ROYAPURAM,55,680000,"REPAIRS AND IMPROVEMENTS TO FOOTPATH AT OLD JAIL ROAD , PORTUEGHESE STREET AND CEMENT CONCRETE FOR BINS AT VARIOUS STREETS IN WARD- 55, UNIT 13, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/4911,Buildings,Completed,NE-ROYAPURAM,53,999000,"IMPROVEMENT TO URDHU SCHOOL BUILDING AT KATPADHA 1 ST CROSS STREET IN DN -53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/4912,Buildings,Completed,NE-ROYAPURAM,53,999000,"CONSTRUCTION OF COMPOUND WALL ,IMPROVEMENT TO NNMP SHED ,TOILET AND URDHU SCHOOL FLOORING TILES AT KATPADA 1 ST CROSS STREET IN DN-53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/4914,Buildings,Completed,NE-ROYAPURAM,53,1090000,"IMPROVEMENT TO STORM WATER DRAIN AND CHOKE PIT ,SILT COLLECTION TANK AND GRATTING AT VARIOUS STREET IN DN -53, UNIT-12 ZONE-5",Own Sources,5,2015-16,2017-18 NE/2015-16/4915,Buildings,Completed,NE-ROYAPURAM,53,999000,"IMPROVEMENT TO FOOTPATH AT VARIOS STREET (NORTH WALL ROAD,BASIN BRIDGE ROAD, PADAVATTAMMAN KOIL STREET, DR V R ROAD ) IN DN -53, UNIT-12, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/5031,Roads,Completed,NE-ROYAPURAM,61,99300,"SUPPLYING AND LAYING WETMIX AT VARIOUS STREETS IN WARD 61,UNIT-14,ZONE-5.",Own Sources,5,2015-16,2019-20 NE/2015-16/5032,Buildings,Completed,NE-ROYAPURAM,61,51500,"REPAIRS AND IMPROVEMENTS AT WATER SUPPLY ARRENGEMENTS IN VARIOUS PUBLIC TOILET IN DN-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/5716,Buildings,Completed,NE-ROYAPURAM,61,992000,"IMPROVEMENTS TO FOOTPATH EAST SIDE IN Dr.NAIR BRIDGE FROM JUNCTION OF P.H ROAD TO GANDHI IRWIN ROAD IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/5809,Buildings,Completed,NE-ROYAPURAM,62,950000,"Providing Construction of Shed with Toilet Room @ Amma Unavagam at Arunasalam Street in DN -62, Unit -14, Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/5812,Buildings,Completed,NE-ROYAPURAM,62,998000,"Improvements to Amma Unavagam at Arunachalam Main Street in DN -62, Unit -14, Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/5813,Buildings,Completed,NE-ROYAPURAM,62,828000,"Improvement Electrical & Water Supply Arrangements at Amma Unavagam @ Arunasalam main Street in DN -62, Unit -14, Zone -05",Own Sources,5,2015-16,2016-17 NE/2015-16/5829,Buildings,Completed,NE-ROYAPURAM,61,989000,"IMPROVEMENTS TO FOOTPATH WEST SIDE IN Dr.NAIR BRIDGE FROM JUNCTION OF P.H ROAD TO GANDHI IRWIN ROAD IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/5831,Parks,Completed,NE-ROYAPURAM,61,502000,"PROVIDING RED-OXIDE FLOORING AND STAINLESS STELL HANDRAIL TO FOOTPATH AT GANDHI IRWIN BRIDE ROAD IIN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/5922,Storm Water Drain,Completed,NE-ROYAPURAM,52,287000,Repairs to storm water drain at various street in ward.52 unit.12 zone.v,Own Sources,5,2015-16,2016-17 NE/2015-16/6255,Storm Water Drain,Completed,NE-ROYAPURAM,49,17500,"PROVIDING RAINWATER HARVESTING WELL AT SINGARARDEN 4TH STREET IN WARD 49,UNIT 12, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/6257,Storm Water Drain,Completed,NE-ROYAPURAM,49,220000,"PROVIDING CONCRETE PATCHES AT VARIOUS STREETS IN WARD 49, UNIT 12, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/6290,Buildings,Completed,NE-ROYAPURAM,51,990000,"Construction of Dinning Hall at Chennai high school at Manikandan 8th Street under WDS in Div -51,Unit -12,Zone -5.",Own Sources,5,2015-16,2016-17 NE/2015-16/6301,Buildings,Completed,NE-ROYAPURAM,51,885000,"IMPROVEMENT WORKS TO ANGANVADI CENTRE IN EAST CEMETRY ROAD SLUM BOARD,OLD WASHERMENPET IN DIV-51,UNIT-12,ZONE-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/6354,Buildings,Completed,NE-ROYAPURAM,55,555000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT NAATTU PILLAIYAR KOVIL STREET IN WARD-55, UNIT-13, ZONE-V.",Own Sources,5,2015-16,2019-20 NE/2015-16/6424,Buildings,Completed,NE-ROYAPURAM,58,987000,IMPROVEMENTS TO ASSIANT ENGINEER OFFICE AND WARD COUNCILLOR OFFICE DIV-58 UNIT-14 ZONE-5,Own Sources,5,2015-16,2016-17 NE/2015-16/6452,Buildings,Completed,NE-ROYAPURAM,62,800000,"Construction of Sump and Improvements Road Side Parks and Providing Flooring in Milk Booth New Amma Uvanavagam at Arunachalam Main Streetin DN -62, Unit ? 14, Zone -05",Own Sources,5,2015-16,2016-17 NE/2015-16/6598,Buildings,Completed,NE-ROYAPURAM,57,994000,"Providing Roofing with Ornamental Sheet for Corporation Shopping Complex and Various street at V.O.C Salai In ward-57, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/6599,Buildings,Completed,NE-ROYAPURAM,57,998000,"Improvement to Corporation Shopping Complex, Water Supply arrangement, Electrical Work and Colour Washing and Various at V.O.C Salai In ward-57, Unit-13, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/6642,Buildings,Completed,NE-ROYAPURAM,63,995000,"Improvetoment Division Office at Veerapadra Street in Ward-63, Unit-14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/6643,Buildings,Completed,NE-ROYAPURAM,63,989000,"Improvement to corporation buildings at Veerapadra Street in Ward-63, Unit14, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/7356,Buildings,Completed,NE-ROYAPURAM,62,984000,"DEMOLISHING THE EXISTING DISPENSARY OLD BUILDING AND CONSTRUCTION OF COMPOUND WALL AT ADIKESAVULU STREET (OPP TO UNIT 14 OFFICE )IN DN-62,U-14,Z-5",Own Sources,5,2015-16,2017-18 NE/2015-16/7420,Buildings,Completed,NE-ROYAPURAM,51,761392,"Providing Rainwater harvesting @ Various places in Division 51,Unit 12,Zone 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7679,Buildings,Completed,B-Buildings,49,897000,"Providing Floor Tiles Work For CWC Hospital at Solaippan Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/7682,Buildings,Completed,B-Buildings,49,568996,"Dismantling and Reconstruction Compound Wall at CWC at Solaippan Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/7705,Buildings,Completed,B-Buildings,49,997000,"Improvement to EDD Clinic for CWC at Solaippan Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/7710,Buildings,Completed,NE-ROYAPURAM,49,516000,"Improvement To Division Office at Kotharadraman Street in ward-49+, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/7773,Buildings,Completed,NE-ROYAPURAM,49,988000,"Construction of Stair Case room at C.I Office Room at Kothardraman Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/7780,Buildings,Completed,NE-ROYAPURAM,58,854000,"Constructions of Compound Wall and E.B. Cabal 16th days Creameries Building in Kanappan Thadal in DN -58, Unit -14, Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/7781,Buildings,Completed,NE-ROYAPURAM,58,910000,"Constructions of 16th days Creameries Building in Kanappan Thadal in DN -58, Unit -14, Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/7784,Buildings,Completed,NE-ROYAPURAM,58,905000,"Providing Drainage and Water Supplying Arrangement for 16th days Creameries Building in Kanappan Thadal in DN -58, Unit -14, Zone -05.",Own Sources,5,2015-16,2016-17 NE/2015-16/7788,Roads,Completed,NE-ROYAPURAM,62,836000,"Providing Construction Chamber and 9 to 18 laying PVC pipe Connection in Amma Nagar in DN -62, Unit -14, Zone ? 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7790,Roads,Completed,NE-ROYAPURAM,62,980000,"Providing Construction Chamber and 1 to 8 laying PVC pipe Connection in Amma Nagar 1 TO 8 Lane in DN -62, Unit -14, Zone ? 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7822,Buildings,Completed,NE-ROYAPURAM,59,975000,"CONSTRUCTION OF BASEMENT, WATER SUPPLY ARRANGEMENTS AND ELECTRICAL ARRANGEMENTS TO NAMMA TOILET AT E.V.R ROAD, BROADWAY BUS STAND AND FRAZER BRIDGE ROAD IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7824,Buildings,Completed,NE-ROYAPURAM,59,986000,"IMPROVEMENTS TO AMMA UNAVAGAM INSIDE OF RAJIV GOVERNMENT HOSPITAL EVR ROAD IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7841,Roads,Completed,NE-ROYAPURAM,57,998000,"Providing stainless steel hand rail to footpath at Elephant gate bridge road south side in Dn.57.Unit.13,Zone-05.",Own Sources,5,2015-16,2016-17 NE/2015-16/7851,Buildings,Completed,NE-ROYAPURAM,49,407000,"Providing Metal Iron Sheet Work for Division-49 Office at Kothadraman Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/7942,Electrical,Completed,NE-ROYAPURAM,59,938000,"IMPROVEMENTS AND MAINTAINCE OF AMMA UNAVAGAM AT BALAMUTHU STREET IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7943,Buildings,Completed,NE-ROYAPURAM,59,590000,"IMPROVEMENTS OF UNANAI HOSPITAL AT BALAMUTHU STREET IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7950,Buildings,Completed,NE-ROYAPURAM,59,994000,"ADDITIONAL IMPROVEMENTS TO AMMA UNAVAGAM AT FRAZER BRIDGE ROAD IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7987,Roads,Completed,NE-ROYAPURAM,55,280000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS ROADS IN WARD 55,UNIT 13, ZONE 5.",Own Sources,5,2015-16,2016-17 NE/2015-16/7989,Storm Water Drain,Completed,NE-ROYAPURAM,61,999705,"CONSTRUCTION OF STORM WATER DRAIN AT KENNET LANE (CHAINAGE FROM GANDHI IRWIN ROAD 0 TO 160 M) IN DIV-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8036,Storm Water Drain,Completed,NE-ROYAPURAM,61,747000,"CONSTRUCTION OF STORM WATER DRAIN AT KENNET LANE (CHAINAGE FROM PANTHEON SALAI 0 TO 160 M) IN DIV-61, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8237,Roads,Completed,NE-ROYAPURAM,50,1669000,"Laying of C.C. Road with RMC M30 Grade of Cement concrete at Kasi Garden 1st street in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/8239,Roads,Completed,NE-ROYAPURAM,50,1682000,"Laying of C.C. Road with RMC M30 Grade of Cement concrete at Kasi Garden 2nd street in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/8240,Roads,Completed,NE-ROYAPURAM,50,2350000,"Laying of C.C. Road with RMC M30 Grade of Cement concrete at Kasi Garden cross lane in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2016-17 NE/2015-16/8241,Roads,Completed,NE-ROYAPURAM,50,725000,"Laying of C.C. Road with RMC M30 Grade of Cement concrete at Kasi Garden 3rd street in Ward-50, Unit-12, Zone-V.",Own Sources,5,2015-16,2017-18 NE/2015-16/8408,Roads,Completed,NE-ROYAPURAM,49,662000,"Laying Cement Concrete Road at New Kamaraj Nagar 1st Lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8410,Roads,Completed,NE-ROYAPURAM,49,668000,"Laying Cement Concrete Road at New Kamaraj Nagar 2nd Lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8413,Roads,Completed,NE-ROYAPURAM,49,642000,"Laying Cement Concrete Road at New Kamaraj Nagar 3rd Lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8414,Roads,Completed,NE-ROYAPURAM,49,899000,"Laying Cement Concrete Road at New Kamaraj Nagar 4th Lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8415,Roads,Completed,NE-ROYAPURAM,49,238000,"Laying Cement Concrete Road at New Kamaraj Nagar 5th Lane in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8416,Roads,Completed,NE-ROYAPURAM,49,911000,"Laying Cement Concrete Road at Pudumamai Kuppam 1st Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8417,Roads,Completed,NE-ROYAPURAM,49,419000,"Laying Cement Concrete Road at Pudumamai Kuppam 2nd Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8418,Roads,Completed,NE-ROYAPURAM,49,419000,"Laying Cement Concrete Road at Pudumamai Kuppam 3rd Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8576,Buildings,Completed,NE-ROYAPURAM,61,311000,"PAINTING TO FOOTPATH AT GANDHI IRWIN ROAD,GANDHI IRWIN BRIDGE ROAD AND WHANNELS ROAD IN DIV 61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/8577,Buildings,Completed,NE-ROYAPURAM,61,677000,"PAINTING TO FOOTPATH AT PANTHEON ROAD,R.L SALAI,ETHIRAJ SALAI, VARIOUS STREET IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/8578,Buildings,Completed,NE-ROYAPURAM,61,409000,"PAINTING TO FOOTPATH AT Dr.NAIR BRIDGE,POLICE COMMISIONER ROAD,HALLS ROAD AND EGMORE HIGH ROAD VARIOUS STREET IN DIV-61,UN-14 Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/8579,Buildings,Completed,NE-ROYAPURAM,61,293000,"PAINTING TO FOOTPATH AT ADITHANAR SALAI,CASA MAJOR ROAD,MONTIETH ROAD AND L.G ROAD IN DIV-61,UN-14,Z-05",Own Sources,5,2015-16,2016-17 NE/2015-16/8617,Buildings,Completed,NE-ROYAPURAM,49,929000,"Providing Colour Washing to Chennai Higher Secondary School at Appasamy Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8618,Roads,Completed,NE-ROYAPURAM,49,547000,"Improvement to Chennai Higher Secondary School at Appasamy Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8627,Roads,Completed,NE-ROYAPURAM,58,986000,"RESTORATION OF ALLIKULAM LINK ROAD CORPORATION PUBLIC CONVENIENCE TO CENTRAL STATION INN GATE IN DIV-58, UNIT-14, ZONE-05",Own Sources,5,2015-16,2016-17 NE/2015-16/8628,Buildings,Completed,NE-ROYAPURAM,59,828000,"IMPROVEMENTS TO CENTRE MEDIAN AND FOOTPATH PAINTINGS FOR REPUBLIC DAY CELEBRATION AT, SOUTH MINT STREET, MEMORIAL HALL ROAD, EVENING BAZZAR ROAD, RATTAN BAZZAR ROAD, MUTHU SAMY SALAI, N.S.C BOSE ROAD IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/8629,Buildings,Completed,NE-ROYAPURAM,59,990000,"ATTENDING PATCH WORKWITH READY MIX M40 GRADE AT INSIDE OF BROADWAY BUS STAND (SOUTH) IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8630,Buildings,Completed,NE-ROYAPURAM,59,978000,"ATTENDING PATCH WORKWITH READY MIX M40 GRADE AT INSIDE OF BROADWAY BUS STAND (NORTH) IN DIVISION-59, UNIT-14, ZONE-5",Own Sources,5,2015-16,2016-17 NE/2015-16/8631,Buildings,Completed,NE-ROYAPURAM,59,930000,"IMPROVEMENTS TO CENTRE MEDIAN AND FOOTPATH PAINTINGS FOR REPUBLIC DAY CELEBRATION AT, SIVANANDHA SALAI, WALLAJA ROAD, PALLAVAN SALAI, PALLAVAN BRIDGE IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/8633,Buildings,Completed,NE-ROYAPURAM,59,999000,"CONSTRUCTION OF MULTI PURPOSE HALL (BLOCK-II) AT S.M NAGAR MAIN ROAD(WARD-59 COUNCILOR SCHEME) IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/8702,Buildings,Completed,NE-ROYAPURAM,59,991000,"REPARIS AND IMPROVEMENTS OF ANGANWADI CENTER NO: 03068,03101; 03067, 03078; 03066, 030100; AT S.M NAGAR MAIN ROAD IN DIVISION-59, UNIT-14, ZONE-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/9026,Storm Water Drain,Completed,NE-ROYAPURAM,62,980000,"PROVIDING INSPECTION CHAMBERS AND PVC PIPE CONNECTION AT ANJU KUDISAI 18 TO 25 LANES & NAVALAR NEDUNCHELIYAN NAGAR IN DN 62, UNIT 14, ZONE 5.",Own Sources,5,2015-16,2019-20 NE/2015-16/9193,Buildings,Completed,NE-ROYAPURAM,62,700000,"Construction of Kitchen shed with store at CHS at Westcoovam River Road in Dn-62,U-14,Z-5 in MLA Chepauk Thiruvallikeni Constituency Developement Fund",MLACDS,5,2015-16,2016-17 NE/2015-16/9500,Buildings,Completed,B-Buildings,58,998000,"Improvements to the CWIC at kariappa street in div-58,unit-14,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/9516,Buildings,Completed,NE-ROYAPURAM,58,999000,"Proposed construction of Boxing shed at my ladies gardern premisses in div-58,unit-14,zone-5.",Own Sources,5,2015-16,2016-17 NE/2015-16/9832,Storm Water Drain,Completed,NE-ROYAPURAM,56,670000,"improvements to storm water drain at geils street in dn-56,u-13,z-5.",Own Sources,5,2015-16,2016-17 NF/2015-16/0003,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,998000,"Providing Modern Stainless Steel Bus Shelter at Pulianthope High road Near Police Station, Dn 77, Unit 17, Zone 6 (WARD COUNCILOR FUND 2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/0035,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,326000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT BRICK LINE ROAD 5TH LANE IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/0076,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,698000,"Improvements To Old Zonal Office Building in Dr.Ambedkar Collage Road for conversion of new E-seva center in Dn-73, Unit-17 Zone-VI.",Own Sources,6,2015-16,2016-17 NF/2015-16/0098,Bridges,Completed,NF-THIRU-VI-KA NAGAR,67,980000,"Attending Patch work (Flood Damaged Road ) at Various street (Loco scheme 2nd street , Jambulingam main raod , rangasayee street in Dn 67 Unit 15 Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/0155,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,978000,"Attending Patch work (Flood Damaged Road ) at Various street GKM Colony main road , biset road, muthukumarppa street in Dn 67 Unit 15 Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/0311,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,266000,"IMPORVEMENTS TO LAB AND CLASS ROOM AT GKM COLONY 12th(PABAMMALSTREET) CPS COUNCILOR FUND (2014-15) IN DN-67,UN-15,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/0602,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,947000,"Improvements of E-SEVA Room at Siva Rao Road, Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2018-19 NF/2015-16/0677,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,510000,"LAYING CEMENT CONCRETE ROAD AT SOMIYA RAJA LANE IN DN 67, UNIT -15, ZONE -6",Own Sources,6,2015-16,2016-17 NF/2015-16/0678,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,671000,LAYING CEMENT CONCRETE ROAD AT GOVERDANDOSS STREET IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/0731,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,421000,"ANNUAL MAINTENANCE OF THANTHAI PERIYAR PARK AT SENTHIL NAGAR 13TH STREET IN DIV-65,UNIT-15,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/0739,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,756000,"Laying cement concrete road M-20 grade concrete at corporation line 1& 2 in dn-75,un-17-zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/0740,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,422000,"ANNUAL MAINTENANCE OF PARK AT SENTHIL NAGAR 10TH STREET IN DIV-65,UNIT-15,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/0742,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,422000,"ANNUAL MAINTENANCE OF JANAGIRAM REDDY COLONY PARK IN DIV-65,UNIT-15,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/0779,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,259000,"LAYING CEMENT CONCRETE ROAD M -20 AT DEVI BHAVANI ELLAIYAMMAN KOIL LANE 1ST & 2ND IN DN-75 UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/0786,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,610000,"LAYING CEMENT CONCRETE ROAD M20 AT BRICK LIN ROAD 4TH LANE IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/0793,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,743000,"PROVIDING STREET FURNITURE AT VARIOUS STREET IN DN-74, UNIT-17, ZONE-6.(WARD COUNCILLORS FUND-2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/0795,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,743000,"PROVIDING STREET FURNITURE AT VARIOUS STREET IN DN-74, UNIT-17, ZONE-6 (WARD COUNCILLOR FUND-2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/0798,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,743000,"PROVIDING STREET FURNITURE AT VARIOUS STREETS IN DN-74, UNIT-17, ZONE-6 (WARD COUNCILLOR FUND -2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/0815,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,22800,"Improvements to M.P.M. street Burial ground in Division-70, Unit- Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/10098,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,985000,ATTENDING BT PATCH WORKS WITH PAVER FINISHER AT KAMBAR NAGAR VALMIKI STREET IN DN-65,Own Sources,6,2015-16,2016-17 NF/2015-16/10099,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,962000,"ATTENDING BT PATCH WORK AT SENTHIL NAGAR 8TH STREET, TEACHERS GUILD COLONY ANNAI THERESA NAGAR, THIRUMURUGAN NAGAR SRINIVASA NAGAR 1 ST, IN DN-65, U-15, Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/10346,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,980000,"Restoration of Road Cut by TNEB at stephenson road (cook road junction to new flat junction) in Dn -73,U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10359,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,980000,Restoration of Road Cut by TNEB at stephenson road (from new flat junction to canal junction) in dn 73 unit 17 zone6,Own Sources,6,2015-16,2016-17 NF/2015-16/10364,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,963000,"Restoration of Road Cut by TNEB at stephenson road (from canal junction to ambedkar collage road ) in dn 73, unit17,zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10367,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,270000,"SUPPLY AND FIXING MANHOLE DOORS AT VARIOUS STREET IN DN -73, UNIT17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/10370,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,66000,"ATTENDING PATCH WORK AT NEW FERRANCE ROAD IN DN 73, UNIT 17 ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10384,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,108000,"REPAIRS AND IMPROVEMENT WORK AT WADIA HEALTH POST AT COOKS ROAD IN DN 73 ,UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10387,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,120000,IMPROVEMENTS TO UNIT ACCOUNTING CELL ( UAC ) DEPARTMENT AT ZONAL OFFICE BUILDING IN DIVISION 69 UNIT 16 ZONE 06,Own Sources,6,2015-16,2017-18 NF/2015-16/10388,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,75000,IMPROVEMENTS TO ELECTION DEPARTMENT(KOLATHUR) AT ZONAL OFFICE BUILDING IN DIVISION 69 UNIT 16 ZONE 06,Own Sources,6,2015-16,2017-18 NF/2015-16/10391,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,63000,IMPROVEMENTS WORKS FOR FOOTPATH AND ZONAL OFFICE BUILDING AT ANDERSON ROAD IN DIVISION 69 UNIT 16 ZONE 06,Own Sources,6,2015-16,2017-18 NF/2015-16/10412,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,865000,"LAYING CEMENT CONCRETE ROAD AT SOMARAMASAMY MAIN ROAD IN DN 67, UNIT -15, ZONE -6",Own Sources,6,2015-16,2016-17 NF/2015-16/10414,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,660000,"LAYING CEMENT CONCRETE ROAD AT MOORTHY RAJA IN DN 67, UNIT -15, ZONE -6",Own Sources,6,2015-16,2016-17 NF/2015-16/10426,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,15600,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS AT CHS AMMAYIAMMAL STREET IN DN 73,UNIT 17,ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10429,Bridges,Completed,NF-THIRU-VI-KA NAGAR,73,14900,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS AT URDHU SCHOOL AT MANNAR SAMY KOIL STREET IN DN 73,UNIT 17,ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10430,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,21000,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS IN AMMA UNAVAGAM AT OLD ZONE -3 OFFICE IN DN 73 UNIT 17, ZONE -6",Own Sources,6,2015-16,2016-17 NF/2015-16/10431,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,38000,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS IN CHS AT THIRUVENKATA SAMYSTREET IN DN 73 UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10433,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,26200,"REPAIRS TO BOREWELL MOTORS AND PLUMBING WORKS IN NNMP SHED AT NEW FERRANCE ROAD IN DN 73, UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10461,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,60000,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS IN HOSPITAL AT THIRUVENKATASAMY STREET IN DN 73, UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10467,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,580000,LAYING OF CEMENT CONCRETE ROAD M20 IN VASUKI NAGAR 1ST STREET IN DN-72 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/10605,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,468000,"PROPOSED TREE PLANTATION FOR 1000 TREE AT VARIOUS STREETS IN DN-75, U-17,Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/10638,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,932000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT PADAVATTAMMAN KOIL STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/10675,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,580000,LAYING OF CEMENT CONCRETE ROAD M20 IN VASUKI NAGAR 2ND STREET IN DN - 72 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/10682,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,701000,LAYING OF CEMENT CONCRETE ROAD IN VASUKI NAGAR 4TH STREET IN DN-72 ZONE - 6,Own Sources,6,2015-16,2016-17 NF/2015-16/10684,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,697000,LAYING OF CEMENT CONCRETE ROAD M20 IN VASUKI NAGAR 1ST CROSS STREET IN DN-72 ZONE-6,Own Sources,6,2015-16,2016-17 NF/2015-16/10691,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,570000,LAYING OF CEMENT CONCRETE ROAD M20 IN VASUKI NAGAR 3RD STREET IN DN 72 ZONE-6,Own Sources,6,2015-16,2016-17 NF/2015-16/10806,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,20300,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS IN NNMP SHED AT GANDHI NAGAR IN DN 73, UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10807,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,16200,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS IN PUBLIC CONVENIYANCE AT NEW FERRANCE ROAD IN DN 73, UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10808,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,33910,"REPAIRS TO BOREWELL, MOTORS AND PLUMBING WORKS IN PUBLIC CONVENIYANCE AT GANDHI NAGAR IN DN 73, UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10809,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,11300,"WRITTING ELECTION BOOTH NUMBER AT VARIOUS SCHOOL BUILDINGS ,NNMP SHED IN DN 73, UNIT 17,ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/10842,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,840000,LAYING CEMENT CONCRETE ROAD AT MES ROAD (FROM VENKATESWARA 2 ND STREET JUNCTION TO JAMUNA BAI NAGAR JUNCTION) IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2017-18 NF/2015-16/1091,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,98000,"Providing Footpath in Stephenson road in Dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/11306,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,700000,IMMPROVEMENTS TO CPS PAPAMMAL SCHOOL COUNCILAR FUND IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/11340,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,20000,"SUPPLY OF RED EARTH AND MANURE FOR TREE PLANTATION AT GKM COLONY BURIAL GROUND IN DN-65, U-15, ZN-6",Own Sources,6,2015-16,2016-17 NF/2015-16/11342,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,945000,"ATTENDING BT PATCH WORKS WITH PAVER FINISHER AT VARIOUS ROADS IN DN 65 , U-15, Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/1139,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,320000,"Repairs and Improvements to TB Hospital at pulianthope high road in Dn 77, U 17, Z 6",Own Sources,6,2015-16,2018-19 NF/2015-16/11413,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,670000,"IMPORVEMENTS TO THE FOOTPATH AT COOKS ROAD (EAST SIDE) IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/11517,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,998000,"Providing Retro Reflection Stainless Steel Street Name Boards at various Streets under Ward Councillor Fund 2015-16 Year in Dn.78,Unit-17,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/11519,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,834000,"PROPOSED CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER AT CHOOLAI HIGH ROAD JN OF SAMI PILLAI STREET - UNDER WARD COUNCILLOR FUND 2015-16 IN DN-78, U-17, Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/11524,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,876000,"ATTENDING PATCH WORK AT SILANTHI KUTTAI KOLATHUR MAIN ROAD IN DN 65 , U-15 , ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/11525,Playfields,Completed,NF-THIRU-VI-KA NAGAR,70,994000,"Providing Modern Fencing for Play Ground at (Arundhathi Nagar)Perambur High Road Jamaliya IN DIV -70,UNIT-16,ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/11527,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,964000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DOCTORS COLONY, JAYANTHI NAGAR, RAJAN NAGAR ,IN DN 65, U-15,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/11628,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,589000,CONSTRUCTION OF ADDITIONAL ROOM IN FIRST FLOOR URBAN PRIMARY HEALTH CENTRE T.V.K. NAGAR IN DIV-68 UNIT-16 ZONE-6,Own Sources,6,2015-16,2016-17 NF/2015-16/11874,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,87500,PROVIDING DISABLE TOILET TO PC AT ANDERSON ROAD AND MADURAI STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/11937,Footpath,Completed,NF-THIRU-VI-KA NAGAR,65,963000,"PROVIDING RAIN WATER HARVESTING SYSTEM USING PRECAST RCC WELL RINGS AND CONSTRUCTION OF SILT CATCH PIT CONNECTING WITH THE WELL AT VARIOUS STREETS IN DN 65, U-15, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/11954,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,410000,"Improvements to Slaughter house (Cow) in Dn 72 , Unit 17 , Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/12024,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,880000,PROVIDING FOOT PATH AT KENNEDY SQUARE 1 ST NORTH STREET PARK WEST AND SOUTH SIDE IN DN 68 UNIT 16 ZONE 6 (HONOURABLE MAYOR FUND ),Own Sources,6,2015-16,2017-18 NF/2015-16/12090,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,128000,"Construction OF Composting Yard at Division office Campus and Perambur Barracks Road in DN -76, Unit 17, Zone -6",Own Sources,6,2015-16,2016-17 NF/2015-16/12094,Footpath,Completed,NF-THIRU-VI-KA NAGAR,76,110000,"Providing Concreting Plat form for foot path at Angalamman koil Street in Dn -76, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/12097,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,45000,"Construction OF Composting Yard at Basin Bridge Road in DN -77, Unit 17, Zone -6",Own Sources,6,2015-16,2016-17 NF/2015-16/12108,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,583000,"PROVIDING RAIN WATER HARVESTING SYSTEM USING PRECAST RCC WELL RINGS AND CONSTRUCTION OF SILT CATCH PIT CONNECTING WITH THE WELL AT VARIOUS STREETS IN DN - 76, UNIT - 17, ZONE - VI",Own Sources,6,2015-16,2018-19 NF/2015-16/12358,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,220000,"IMPROVEMENTS TO TOILET IN CPS AT MANGALAPURI IN DN-71,UNIT-16,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/12366,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,560000,FORMING VOLLEY BALL COURT AND PROVIDING WATER SUPPLY ARRANGEMENT WITH BORE WELL AT KENNEDY SQUARE 1 ST NORTH STREET PARK IN DN 68 UNIT 16 ZONE 6 (HONOURABLE MAYOR FUND),Own Sources,6,2015-16,2017-18 NF/2015-16/12373,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,50000,"Providing PVC doors to the public convenience (Alexander street,New ferrance road,strahns road) in dn-73,unit-17,zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/12382,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,854000,"SUPPLYING AND PLANTATION FOR MURASOLIMARAN PARK (PHASE -2) AT PERAMBUR DN-70,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/12431,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,700000,REPAIRS AND WATER SUPPLY ARRANGEMENTS TO NNMP SHED (07032 & 07033) AT GOPALAPURAM IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/1253,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,174000,HIRING OF JCB FOR DESILTING EGANKIPURAM CANAL IN Dn-71 U-16 Z 6,Own Sources,6,2015-16,2016-17 NF/2015-16/12555,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,523000,"PROPOSED CONSTRUCTION OF AUDITORIUM AT CMS, TANA STREET UNDER WARD COUNCILOR FUND 2015-16 IN DN - 78, UNIT- 17, ZONE - VI.",Own Sources,6,2015-16,2016-17 NF/2015-16/12559,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,385500,IMPROVEMENTS TO JANAGIRAM COLONY PARK in Dn-65 U-15 Zn-6,Own Sources,6,2015-16,2016-17 NF/2015-16/12572,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,795000,IMPROVEMENTS TO CGHSS SCHOOL (COUNCILAR FUND) IN MARKET STREET IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/1265,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,871000,"LAYING CEMENT CONCRETE ROAD M20 CONCRETE AT MEDAVAKKAM TANK 2ND STREET 1ST,2ND,3RD LANES IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/1272,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,871000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT MEDAVAKKAM 2ND STREET 4TH,5TH ,6TH LANES IN DN-74, UNIT-17, ZONE-6 .",Own Sources,6,2015-16,2017-18 NF/2015-16/1276,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,142000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT SUBURAYAN 4TH STREET 6TH LANE IN DN-74, UNIT-17, ZONE-6 .",Own Sources,6,2015-16,2018-19 NF/2015-16/1281,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,481000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT BAJANAI KOIL STREET IN DN-74, UNIT-17, ZONE-6 .",Own Sources,6,2015-16,2018-19 NF/2015-16/12828,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,430000,"Laying of cement concrete road RMC M20 in Padission lane in dn-73,unit-17,zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/12904,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,380000,CONSTRUCTION OF CARETAKER ROOM AT KENNEDY SQUARE 1ST NORTH STREET PARK IN DIV 68 UNIT 16 ZONE 6.(HONOURABLE MAYOR FUND),Own Sources,6,2015-16,2017-18 NF/2015-16/12939,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,890000,"RELAYING OF CC ROAD AT SACHIDANANDAM STREET SLUM IN DN-78, U-17, ZN6",Own Sources,6,2015-16,2016-17 NF/2015-16/1294,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,980000,LAYING CEMENT CONCRETE ROAD AT JAGANATHAN STREET (FROM KANNABIRAN STREET JUNCTION TO SIVAGAMI JUNCTION) IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/1297,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,999000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT CHANGALVARAYAN 1ST&2ND LANES IN DN-74, UNIT-17, ZONE-6",Own Sources,6,2015-16,2018-19 NF/2015-16/13029,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,698000,PROVIDING CYCLE SHED AND FRONT ENTRANCE PARK TO CMS GOPALAPURAM AT SRP KOIL STREET (NORTH) IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/13038,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,656000,IMPROVEMENTS TO 16TH CERMNORY HALL OPPOSITE TO THANGAL BURIAL GROUND AT PALLAVAN SALAI IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2017-18 NF/2015-16/13150,Footpath,Completed,NF-THIRU-VI-KA NAGAR,67,980000,PROVIDING FOOT PATH NORTH SIDE AND SOUTH SIDE OF THE POND AT KANAKAR STREET IN DN 67 UNIT 15 ZONE -6,Own Sources,6,2015-16,2016-17 NF/2015-16/13157,Footpath,Completed,NF-THIRU-VI-KA NAGAR,67,880000,PROVIDING FOOT PATH EAST SIDE AND WEST SIDE OF THE POND AT KANAGAR STREET IN DN-67 UNIT-15 ZONE -6 (MAYOR FUND),Own Sources,6,2015-16,2016-17 NF/2015-16/13470,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,660000,"Repairs and Maintenance to Compound Wall at Old Lorry Shed in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2018-19 NF/2015-16/13634,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,549000,RELAYING THE ROAD AT RAJAJI NAGAR 7TH STREET IN DN-65 U-15 Z-06.,Own Sources,6,2015-16,2016-17 NF/2015-16/13762,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,972000,"Attending B.T. patch work at various street in dn-73,unit-17,zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/13764,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,410000,"Attending CC patch work at various streets in dn-73,unit-17,zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/13821,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,997000,PROVIDING STREET FURNITURE AT VARIOUS STREETS IN DIV 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/13827,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,997000,PROVIDING STREET FURNITURE AT VARIOUS STRETS IN DIV 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/13879,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,392500,"Relaying the BT Road at Vinayagar kovili street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13880,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,437000,"Relaying the BT Road at Lakshmi nagar 1st street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13882,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,450300,"Relaying the BT Road at Lakshmi nagar 2nd street (Reach II ) in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13883,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,226300,"Relaying the BT Road at Lakshmi nagar 3rd street (Reach II ) in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13886,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,484700,"Relaying the BT Road at Lakshmi nagar 5th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13887,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,375600,"Relaying the BT Road at Lakshmi nagar 6th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13891,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,165000,"Relaying the BT Road at Bharath avenue 3rd street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13893,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,265000,"Relaying the BT Road at Bharath avenue 2nd street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13897,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,446700,"Relaying the BT Road at Bharath avenue 1st street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13901,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,422000,"Relaying the BT Road at Rajarajeshwari nagar 3rd street( Poompuhar nagar 2nd st Near PhaseI)in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13902,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,508000,"Relaying the BT Road at Rajarajeshwari nagar 4th street (Poompuhar nagar 2nd st Near PhaseII) in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13903,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,355700,"Relaying the BT Road at Rajarajeshwari nagar 5th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13904,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,503900,"Relaying the BT Road at Rajarajeshwari nagar 6th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13905,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,680000,"Relaying the Lowlying CC Road portion at Murugan nagar 6th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13916,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,700000,"Relaying the Lowlying CC Road portion at Murugan nagar 4th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/13917,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,225000,"Relaying the Lowlying CC Road portion at Murugan nagar 2nd street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/1396,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,111000,"Repair to public convenience at various street in dn-68,unit-16,zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/14330,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,87000,"Providing pipeline facilities at Basin Elephant road in div-77,unit-17,zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/14331,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,162000,"Dismantling and reconstruction of compound wall to the football ground and to the existing park at basin elephant road in div-77, unit-17,zone-5.",Own Sources,6,2015-16,2016-17 NF/2015-16/14334,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,74000,"Construction of Roadside park at munusamy street in div-77,unit-17,zone-5.",Own Sources,6,2015-16,2016-17 NF/2015-16/14336,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,142000,"Improvements to K.P park, health post and division office in div-77,unit-17,zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/14424,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,144000,"Improvement and Repairs to TPF Park at Basin Elephant Gate Road in DN -77, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/14431,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,61000,"Improvement to Ladies Toilet Repair to Champer Pipe at Basin Bridge Road in DN -77, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/14437,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,112000,"Construction of Compound wall to Urban Primary Health Centre at Conronsmith Nagar in DN -76, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/14439,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,55000,"Providing Cattle drop to Conronsmith Nagar UPHC in DN -76, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/1448,Footpath,Completed,NF-THIRU-VI-KA NAGAR,67,980000,LAYING CEMENT CONCRETE ROAD AT JAGANATHAN STREET (FROM THANDHORI AMMAN KOIL STREET JUNCTION TO KANNABIRAN STREET JUNCTION) IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/14500,Buildings,Completed,B-Buildings,64,20231713,Construction of Gasifier Crematorium at Nearmai Nagar Burial Ground in Dn-64 U-15 Z-6,Own Sources,6,2015-16,2020-21 NF/2015-16/1454,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1000000,"PROVIDING STREET FURNITURES IN VARIOUS STREET IN DN-65, UNIT-15, ZONE-VI(UNDER WARD COUNCILER FUND YEAR 2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/14748,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,620000,"Laying cement concrete road with M30 grade at Poompugar nagar 28th street Lane in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/14881,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,208000,"Improvements to Public convinence at Chinniah lane in Division-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/14887,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,90000,"Improvements to Road Side Park at Strnans Road and Angalamman koil Street in DN -76, Unit -17, Zone -6.",Own Sources,6,2015-16,2016-17 NF/2015-16/14889,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,68000,"Improvements to SWD at Angalamman koil Street in DN -76, Unit -17, Zone -6.",Own Sources,6,2015-16,2016-17 NF/2015-16/14892,Footpath,Completed,NF-THIRU-VI-KA NAGAR,76,624000,"Improvement to Footpath and SWD Repair at Strahans Road in DN -76, Unit -17, Zone -6",Own Sources,6,2015-16,2020-21 NF/2015-16/14893,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,160000,Desilting and improvements to SWD at Kuppusamy Street in Dn66 U16 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/14899,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,990000,Providing well type RWH 120CM Dia at Various Location in Dn66 U16 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/14929,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,237000,DESILTING OF OPEN NATURALCANAL IN DOSS NAGAR PALLAM IN DIVISION-72 UNIT -17 ZONE -6,Own Sources,6,2015-16,2016-17 NF/2015-16/14969,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,92000,"Supplying and Providing Waste Plastic Collection Bins 5Nos at Various Location (Div 66,68,69) in Dn66 U16 Z06",Own Sources,6,2015-16,2016-17 NF/2015-16/14970,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,980000,Providing Well Type RWH at Various Location in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/14972,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,990000,Providing Well type RWH 120CM Dia Various Location in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/15067,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,798000,"IMPROVEMENTS TO CENTER MEDIUM AT KUNNOR HIGH ROAD IN DIV-71, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/15086,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,400000,"IMPROVEMENT TO PUBLIC TOILET AT V.O.C NAGAR 1ST STREET IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/15087,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,690000,"IMPROVEMENT TO PUBLIC CONVENIENCE AT SASTHIRI NAGAR 7TH STREET IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/15093,Parks,Completed,NF-THIRU-VI-KA NAGAR,78,468000,"PROPOSED TREE PLANTATION FOR 1000 TREE AT VARIOUS STREETS IN DN-78, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/15225,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,690000,"IMPROVEMENT TO GYM AT DECOSTER ROAD IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/15333,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,489000,"Repairs and Improvements to Existing S.I Office at Kutty Thambiran Street in Dn-73,Unit-17,Zone-VI",Own Sources,6,2015-16,2016-17 NF/2015-16/15642,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,12000,"REPAIRS TO PLUMBING WORK IN DISPENSARY (NEAR OLD ZONE -03) AT AMBEDKAR COLLAGE ROAD IN DN- 73, UNIT-17, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/15706,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,280000,"Improvements to Existing SWD at Jeganathan salai in Div-66,Unit-16, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/15757,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,990000,"IMPROVEMENT WORKS (LEFT SIDE FROM GATE)AT MURASOLIMARAN PARK (SOUTH) IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2019-20 NF/2015-16/15759,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,990000,IMPROVEMENT WORKS (RIGHT SIDE FROM GATE)TO MURASOLI MARAN PARK (SOUTH ) IN DN-71 UNIT-16 ZONE-6,Own Sources,6,2015-16,2019-20 NF/2015-16/15812,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1000000,"PROVIDING STREET FURNITURES IN VARIOUS STREET IN DN-65, UNIT-15, ZONE-VI(UNDER WARD COUNCILER FUND YEAR 2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/1596,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,744000,CONSTRUCTION OF COMPOUND WALL IN KENNEDY SQUQRE 1 ST NORTH STREET PARK IN DN 68 UNIT 16 ZONE 6 (HONOURABLE MAYOR FUND),Own Sources,6,2015-16,2017-18 NF/2015-16/1612,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,910000,PROVIDING FOOTPATH AT KENNEDY SQUARE 1S TNORTH STREET PARK EAST AND NORTH SIDE IN DN 68 UNIT 16 ZONE 6 (HONOURABLE MAYOR FUND),Own Sources,6,2015-16,2017-18 NF/2015-16/16281,Overbridges,Completed,NF-THIRU-VI-KA NAGAR,72,300000,"PROPOSED TREE PLANTATION FOR 500 TREE AT VARIOUS STREET IN DIVISION-72, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/16345,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,420000,"Repairs and improvements to the PC @ strahns road first street in dn-73,unit-17,zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/16448,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,985000,ATTENDING PATCH WORK AT SUBBA STREET V.VKOIL STREET TKMUDALISTREET PERIYATHAMBI STREET NARASINGAPERUMAL KOIL STREET IN D-78 UNIT-17 ZONE-6,Own Sources,6,2015-16,2016-17 NF/2015-16/16452,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,982000,"ATTENDING PATCH WORK AT ANGALAMMAN KOIL STREET,ASTAPUJAM SALAI AP1ST LANE SATTANNAN STREET, IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/16471,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,66600,"IMPROVEMENTS TO DIVISION OFFICE AT OLD SLAUGHTER HOUSE ROAD IN DIV-77,UNIT-17,ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16475,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,89000,"Improvements to bus stands at various places ,road side park at basin elephant road and providing drain facilities to pulliyanthope 1st street in div-77,unit-17,zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16476,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,463000,"Improvements to public convenience to various places in div-77,unit-17,zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16477,Electrical,Completed,NF-THIRU-VI-KA NAGAR,77,83000,"Providing electrical arrangements to public convenience at various places in div-77,unit-17,.zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16478,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,224000,"Attending cement concrete patches at various roads in div-77,unit-17,zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16507,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,980000,"providing well type RWH at various location in dn 73,unit 17,zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/16691,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,792500,"Relaying the BT Road at Tiruppathy nagar extn (north) Puthar street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16693,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,580000,"Relaying the BT Road at Sri jeyaram nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/16698,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,816000,"Relaying the BT Road at Valarmathi nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16907,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,906000,"MAINTENANCE OF PARKS AT BASIN ELEPHANT GATE ROAD IN DN-77, U-17, Z-6.( FOR TWO YEARS)",Own Sources,6,2015-16,2018-19 NF/2015-16/16908,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,480000,"IMPROVEMENT TO STORM WATER DRAIN AT PULIYANTHOPPE 4TH STREET AND OTHER STREETS IN DN-77 UNIT-17 ,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/16927,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,995000,"ATTENDING PATCH WORK AT VARIOUS STREETS AND FOUR TABLE PLANT IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/16954,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,613000,DESLILTING OF OTTERI NULLAH CANAL INSIDE THE GMR POWER STATION VASUKI NAGAR TO BASIN BRIDGE RAILWAY TRACK IN DN-72 UNIT -17 ZONE-6,Own Sources,6,2015-16,2018-19 NF/2015-16/16999,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,993000,LAYING CC ROAD SHANTHI COLONY MAIN ROAD IN MH ROAD JUNCTION TO SHANTHI COLONY 2 ND LANE AT DIV 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2018-19 NF/2015-16/17001,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,990000,"CONSTRUCTION OF SUMP AND IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT STRANGS ROAD IN DIV-76,UN-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/17005,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,345000,"Improvements to Anganwadi( No.657) at State bank colony 1st street in Division-70,Unit-16,Zone-6",Own Sources,6,2015-16,2019-20 NF/2015-16/17006,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,985000,"IMPROVEMENTS TO COMMUNITY HALL AT ANGALAMMAN KOIL STREET IN DIV-76,UN-17,Z-08",Own Sources,6,2015-16,2016-17 NF/2015-16/17082,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,770000,IMPROVEMENTS TO CONFERENCE HALL AND PROVIDING WATER SUPPLY AND DRAINAGE ARRANGEMENTS TO PUBLIC TOILET AT ZONAL OFFICE IN DIV 69 UNIT 16 ZONE 6.,Own Sources,6,2015-16,2016-17 NF/2015-16/17308,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,890000,"Attending Patchwork at Anjugam nagar,Sarojini nagar,V.P.Sindhan nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/17310,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,540000,"Attending Patchwork at Poompugar nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/17358,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,75000,"Improvements to Park at Thenpalani nagar Thiru.Vi.Ka street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/17392,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,160000,"Improvements to V.O.C nagar Park in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/17499,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,38000,"Providing Inlet Chamber for Lowlying portion at Anjugam nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/17509,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,98000,"Improvements to Existing SWD at various streets in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/17769,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,997000,"LAYING OF BT ROAD IN SLAUGHTER HOUSE NEAR BONE SHED IN DN.72, UNIT-17, ZONE 06.",Own Sources,6,2015-16,2016-17 NF/2015-16/17930,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,998000,"LAYING OF BT ROAD IN SLAUGHTER HOUSE NEAR COW SHED IN DN.72, UNIT-17, ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/17931,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,999000,"LAYING OF BT ROAD IN SLAUGHTER HOUSE NEAR GOAT SHED IN DN.72, UNIT-17, ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/18010,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,365000,IMPROVEMENTS TO CEMENT CONCRETE PATCH AND FRC DOOR IN VARIOUS STREET IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/18013,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,274000,"Rain Water Harvesting Work at Various Streets in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/1808,Electrical,Completed,NF-THIRU-VI-KA NAGAR,78,571000,"PROVIDING NEW E-SEVA CENTER IN UNIT OFFICE AT ARUNACHALAM PANDARAM STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18084,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,609000,"ATTENDING C.C PATCH WORK AND PROVIDING FLOORING FOR GROUP BINS AT VARIOUS STREET IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18117,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,880000,"ATTENDING PATCH WORK AND MINI HOT MIX PLANT IN VARIOUS STREETS IN DN-75, UNIT-17, ZONE-6. IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/18287,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,294000,"Patch Work at Various Streets in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/18289,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,272000,"Repairs and Maintenance Of Storm Water Drain Work at Various Streets in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/1847,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,39000,"REPAIRS AND IMPROVEMENT WORK AT AMMA UNAVAGAM AN DIVISION OFFICE 68 IN DN 68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/18479,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,594000,ATTENDING CC PATCH WORK AT VARIOUS STREETS IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/1848,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,249000,"Improvements to Road Side Park at Pallavan Salai in Dn 68, Unit-16, Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/18480,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,890000,Laying of Wet Mix at various places in Dn 73 Unit 17 Z 06,Own Sources,6,2015-16,2016-17 NF/2015-16/18481,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,915594,"Temporary restoration of B.T road due to flood at Lal singh street in dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18482,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,460822,"Temporary restoration of B.T road due to flood at Narayana samy street in dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18483,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,592538,"Temporary restoration of B.T road due to flood at Parthasarathy street in dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18484,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,503382,"Temporary restoration of B.T road due to flood at Kutty thambiran street in dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18485,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,674451,"Temporary restoration of B.T road due to flood at Ammaiammal street in dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18497,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,999000,"Repairs to the Storm Water Drain at P.H.Road in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/1850,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,86000,"SUPPLYING AND DELIVERY OF B.R.C.WELDMESH PARTITION AT VARIOUS STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/18501,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,997000,"Vacant Land Cleaning and Road Maintenance at various street in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/18679,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,636000,Supplying and Erecting of Portable PC's at Pulianthope High Road in Dn 73 Unit 17 Z 6,Own Sources,6,2015-16,2016-17 NF/2015-16/18687,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,292766,"Temporary restoration of B.T road due to flood at Ramasamy Street (from pulianthope high road to natcharamal street) in dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/18870,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,913000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND OTHER IMPROVEMENTS TO NNMP SHED AT SACHIDANANDAM 2ND LANE IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/18927,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,693000,RAISING OF JAMALIYA SLUM BOARD A BLOCK AND D BLOCK ROAD AT JAMALIYA IN DN 68 UNIT 16 ZONE6,Own Sources,6,2015-16,2016-17 NF/2015-16/18929,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,695000,RAISING OF JAMALIYA SLUM BOARD E BLOCK ROAD AT JAMALIYA IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/18932,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,835000,LAYING CC ROAD SHANTHI COLONY MAIN ROAD IN SHANTHI COLONY 2 ND LANE TO 1 ST LANE AT DN 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2018-19 NF/2015-16/18933,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,798730,LAYING CC ROAD IN SHANTHI COLONY MAIN ROAD 1ST LANE TO LAST END AT DN 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2018-19 NF/2015-16/1899,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,887000,"CONSTRUCTION OF BATHROOM ,TOILET AND OTHER IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL IN GROUND FLOOR AT ERRAN STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/1900,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,33000,"Attending patch work at Belvidor village in Dn-73,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/1903,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,841000,"CONSTRUCTION OF BATHROOM,TOILET AND OTHER IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL IN 1ST & 2ND FLOOR AT ERRAN STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/19052,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,635000,"Relaying the Flood affected road at Krishna nagar main road in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19054,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,650000,"Relaying the Flood affected road at Krishna nagar 1st & 2nd street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19055,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,765000,"Relaying the Flood affected road at Krishna nagar 3rd street & Aandal avenue 3rd street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19056,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,710000,"Relaying the Flood affected road at Venkatesan street & Karthick street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19057,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,510000,"Relaying the flood affected road portion at Valliammai street & Rajabathar street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19058,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,710000,"Relaying the flood affected road at Thangavel street( From Govindasamy street to Ayyalu street) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19059,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,635000,"Relaying the flood affected road portion at Thangavel street (From Ayyalu street to Aandal avenue 3rd street) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19060,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,870000,"Relaying the flood affected road portion at Sakthivel nagar 4th,5th & 6th street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19061,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,770000,"Relaying the flood affected road portion at Kumaran nagar 2nd main road in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19062,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,235000,"Relaying the flood affected road portion at Chelliamman colony 1st street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19063,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,695000,"Relaying the Lowlying Flood affected road portion at Chelliamman colony 2nd street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19065,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,765000,"Relaying the flood affected road portion at Sakthivel nagar 7th street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/1908,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,30000,"REPAIRS TO BOREWELL ,MOTORS, AND PLUMBING WORK IN PUBLIC CONVEYNIENCE AT DR AMBEDKAR COLLEGE ROAD (NEAR DECASTER ROAD JUNCTION ) IN DN 73, UNIT 17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/19080,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,620000,"Relaying the Flood affected road portion at Lakshman nagar west street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19081,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,590000,"Relaying the Flood affected road portion at Periyar nagar 5th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19083,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,400000,"Raising the Lowlying BT road at Lakshman nagar 2nd cross street Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19084,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,880000,"Relaying the Flood affected road at Lakshman nagar 1st cross & 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19085,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,490000,"Relaying the Flood affected road portion at Kumaran nagar 3rd street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19086,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,845000,"Relaying the Flood affected road portion at Veeraragavan street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19087,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,510000,"Relaying the Lowlying Flood affected road portion at Mery Helan street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19089,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,825000,"Relaying the Flood affected road portion at Ragavan street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19091,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,855000,"Relaying the Flood affected road portion at Shanthi street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19092,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,800000,"Relaying the Flood affected road portion at Kandasamy salai ( From Karthikeyan salai to Periyar nagar 9th street) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19093,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,620000,"Relaying the Flood affected road portion at Kandasamy salai ( From Periyar nagar 9th street to Venkatesan salai) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19094,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,795000,"Relaying the Flood affected road portion at Kumarasamay street & Loganathan street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19096,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,475000,"Relaying the Flood affected road portion at Raja garden in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19097,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,590000,"Relaying the Flood affected road portion at Balasubramaniam salai (Venkatesan salai to Periyar nagar 9th street) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19098,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,650000,"Relaying the Flood affected road portion at Balasubramaniam salai ( Periyar nagar 9th street to Karthikeyan salai) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19100,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,850000,"Relaying the Flood affected road portion at Sakthivel nagar School road in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19104,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,530000,"Relaying Flood affected road at Duraisamy street & Shumundeeshwari street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19124,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,307000,IMPROVEMENTS TO THIRU VI KA NAGAR DAY CARE CENTRE IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/19125,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,226000,REPAIRS AND IMPROVEMENTS TO PUBLIC TOILET AT THILLAI NAYAGAM PILLAI STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/19130,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,977000,RAISING OF MADURAI SAMY MADAM 2 ND STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/19193,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,790000,"Raising the lowlying Flood affected road portion at rajarajeswari nagar 1st,2nd and3rd street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19194,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,525000,"Raising the low laying flood affected road portion at Poombughar nagar 2nd street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19195,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,580000,"Rising the low laying flood affected road portion at Poombughar nagar 27th street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19196,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,860000,"Raising the low laying flood affected portion at Vijaya nagar and vijaya nagar extn in division-64,unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19197,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,840000,"Raising the low laying flood affected road portion at Vivek nagar 1st,2nd, 3rd street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19198,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,430000,"Raising the low laying flood affected road portion at Vivek nagar 4th and 5th street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19199,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,215000,"Raising the low laying flood affected road portion at Vetrivelnagar 1st & 2 nd street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19200,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,810000,"Raising the low laying flood affected portion at Balakumaran nagar B part Main road in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19201,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,600000,"Raising the low laying flood affected road portion at poombughar nagar 10th street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19202,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,680000,"Raising the low laying flood affected road portion at Meenakshi nagar(Cont of Perundevi nagar), in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19203,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,510000,"Raising the low laying flood effected road portion at Perundevi nagar, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19204,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,860000,"Raising the low laying flood affected road portion at Bharath avenue 1st main road and 4th avenue in division-64, unit-15, zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/19205,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,450000,"Raising the low laying flood affected portion at Velmurugan 4th avenue, in division-64, unit-16, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19224,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,510000,"Raising the low laying flood affected road portion at Buddhar street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19225,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,650000,"Rising the low laying flood affected road portion at Poombughar nagar 3rd street, in division-64,unit-15,zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19226,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,305000,"Raising the low laying flood affected portion at Balakumaran nagar A part in division-64, unit-16, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19227,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,265000,"Raising the low laying flood affected portion at Bavani nagar in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19228,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,570000,"Raising the low laying flood affected portion at poombughar nagar 4th street in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19229,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,420000,"Raising the low laying flood affected portion at Balakumaran nagar B part 1st & 2nd street, in division-64, unit-15, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19238,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,460000,"DESILTING THE EGANGIPURAM CANAL FROM RAJIVI GANDHI NAGAR TO KONNUR HIGH ROAD IN DN-71,U-16,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19259,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,76000,"REPAIRS AND MAINTENANCE AT LAB & GANDHI PARK IN DN-70,UNIT-16,ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19261,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,988400,"ATTENDING PATCH WORK AT VARIOUS STREETS BASHYAM STREET AND 3RD MAIN ROAD AND STREETS IN DN 71 UNIT -16,ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/19293,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,978000,"DESILTING THE EGANGIPURAM CANAL FROM PERAMBUR HIGH ROAD TO EGANGIPURAM ROAD CULVERT IN DN-71,U-16,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19294,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,510000,"DESILTING THE CHANNEL FROM PULIYANTHOPE HIGH ROAD BRIDGE TO INFALL POINT OF OTTERI NULLAH CANAL,IN DN-72,UNIT-17,ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19295,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,174000,"DESILTING THE CANAL FROM VILLIVAKKAM RAILWAY STATION TO KOLATHUR MAIN ROAD,IN DN-65,UNIT-15,ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19296,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,460000,"DESILTING THE AYANAVARAM RAILWAY CANAL,IN DN-69,UNIT-16,ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19330,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,300000,"PROPOSED TREE PLANTATION FOR 650 TREE AT VARIOUS ROAD SIDE ,PARKS, AND SCHOOL BUILDINGS IN DIVISION -73, UNIT-17, ZONE-6",Own Sources,6,2015-16,2018-19 NF/2015-16/19472,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,920000,"Attending patch work for flood affected roads at Kandasamy salai,Balasubram,anian salai,Venkataman salai,Jeganathan salai,Siva elango salai,Periyar nagar 5th cross,6th cross & 7th cross street,Lakshman nagar west street,1st cross & 2nd cross street in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19474,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,920000,"Attending patch work for flood affected roads at Karthick street,Kumaran nagar 3rd cross street,Krishna nagar main road,Sakthivel nagar school road,3rd street & 7th street,Ayyalu street,Thangavel street,Kuppusamy street,Suganraj street,Bashyam street in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19478,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,820000,"Attending patch work for flood affected roads at Anjugam nagar,Ganapathy rao nagar,Samtharia colony,Vetrivel nagar,Somanathapuram,Nermai nagar,Velavan nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19480,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,820000,"Attending patch work for flood affected roads Sarojini nagar,Kaveri nagar,South mada street,East mada street,Yamuna nagar,Appasamy street,Vasantham nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19489,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,820000,"Attending patch work for flood affected roads at Poompugar nagar ,Shanthi nagar,Ashoka avenue, Arjun nagar,Murugan nagar,Rajan nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19490,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,820000,"Attending patch work for flood affected roads at Jeyaram nagar,Venkateshwara nagar,Thenpalani nagar,Balaji nagar,Tirupathi nagar,Valarmathi nagar in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19496,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,855000,"Replacing damaged Manhole covers at Various locations in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19508,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,960000,"Replacing damaged Manhole covers at various locations in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/19546,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,50000,"Providing Inlet chamber for Lowlying portion at Poompugar nagar 11th cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19550,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,98000,"Supplying and Providing JCB & TATA ACE Motor vechicle for Flood work in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19551,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,405000,"Raising the Lowlying Road portion at Lakshmi nagar Nehru street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19560,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,880400,Raising the lowlying flood affected road portion at Poompugar Nagar 20th street in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/19561,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,863800,Raising the lowlying flood affected road portion at Poompugar Nagar 21ST street in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/19564,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,863800,Raising the lowlying flood affected road portion at Poompugar Nagar 18th street in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/19565,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,332200,Raising the lowlying flood affected road portion at Vasantham nagar 1st street in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/19566,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,859300,Raising the lowlying flood affected road portion at Kamarajar street West portion ( Tiruveethiamman kovil street to Vasantham nagar 1st street) in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/19567,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,804300,Raising the lowlying flood affected road portion at Gandhi nagar 1 to 5th street in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/19568,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,730000,Raising the lowlying flood affected road portion at Kamarajar street East part( From Vasantham nagar 1st street to Appasamy street) in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/19569,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,219900,"Raising the lowlying flood affected road portion at TNHB Colony West street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19570,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,308700,"Raising the lowlying flood affected road portion at samtharia colony 3rd street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19571,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,828400,"Raising the lowlying flood affected road portion at Sarojini nagar 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19572,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,804300,"Raising the lowlying flood affected road portion at Kaveri nagar 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19573,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,804300,"Raising the lowlying flood affected road portion at Meenakshi nagar in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19574,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,308700,"Raising the lowlying flood affected road portion at Anjugam nagar 8th street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19575,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,459500,"Raising the lowlying flood affected road portion at Padma nagar 1st street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19576,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,741400,"Raising the lowlying flood affected road portion at Padma nagar Main road and 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19577,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,739600,"Raising the lowlying flood affected road portion at Kaveri nagar Main road in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19578,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,900000,"Relaying Cement concrete road for Flood affected Lowlying portion at Haridoss nagar 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19580,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,413800,"Relaying Cement concrete road for Flood affected Lowlying portion at Haridoss nagar 2nd street Lane in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19581,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,726000,"Raising the Lowlying Flood affected road portion at MN nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19582,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,888000,"Raising the Lowlying Flood affected road portion at MN nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19583,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,741000,"Raising the Lowlying Flood affected road portion at MN nagar 2nd & 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19584,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,741000,"Raising the Lowlying Flood affected road portion at MN nagar 4th,5th & 6th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/19763,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,535000,PROVIDING WELL TYPE RWH IN DIVISION-68 UNIT-16 ZONE-06,Own Sources,6,2015-16,2016-17 NF/2015-16/19792,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,680000,"IMPROVEMENT WORK IN NNMP CENTRE 07084 AT NARASIMA NAGAR IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/19805,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,690000,"IMPROVEMENT WORK IN NNMP CENTRE 07081 , 07111 AT NARASIMA NAGAR IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/19807,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,690000,"IMPROVEMENT WORK IN NNMP CENTRE 07083,07094 AT NARASIMA NAGAR IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/19831,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,960000,LAYING BITUMINOUS ROAD BY PAVER FINISHER WITH CAMBER CORRECTION AT MADURAI SAMY MADAM 2 ND STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/19843,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,630000,"REPAIRS AND IMPROVEMENTS TO DILAPILATED STORM WATER DRAIN AT OPPOSITE TO DOOR NO 31-A/ 73,MATHAVARAM HIGH ROAD IN DIV-69 UNIT-16 ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/19865,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,970000,"IMPROVEMENT TO PRIMARY SCHOOL AT AMMAIYAMMAL IN DN-73, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/19901,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,327000,"PROVIDING RAIN WATER HARVESTING USING PRECAST RCC WELL RING AT VARIOUS LOCATION IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/19906,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,607000,"IMPROVEMENTS TO HOSPITAL AT C.R.GARDEN IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/19907,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,134000,"PROVIDING FRC DOOR AT VARIOUS STREET (PERAMBUR BARRACKS ROAD,TANA STREET,V.V KOIL STREET) IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/19911,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,223000,"PROVIDING BABY TOILET AND IMPROVEMENTS TO NNMP SHED NO(052) AT ASTAPUJAM STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/19912,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,32500,"WELDMESH PARTITION ARRANGEMENTS FOR WINDOWS TO CHENNAI MIDDLE SCHOOL AT TANA STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/19914,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,33000,"ATTENDING CEMENT CONCRETE PATCH WORK AT VARIOUS STREET(SYDHANAMS ROAD,ASTAPUJAM STREET) IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/19957,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,860000,"Raising the low laying flood affected portion at poombughar nagar 9th street in division-64, unit-15,zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/19998,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,99000,"IMPROVEMENT TO PARK AT ANGALAMMAN KOVIL STREET IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20001,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,855000,"Raising the low laying flood affected portion at Ragavan street, in division-66, unit-16, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/20002,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,167000,"IMPROVEMENTS TO PUBLIC CONVEYENCE AT ANGALAMMAN KOVIL STREET IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20003,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,920000,"Raising the low laying flood affected portion at Shanthi street, in division-66, unit-16, zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/20030,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,997000,"Patch Work (Bitumen Concrete)at various Streets in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20050,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,500000,"Raising the Lowlying Flood affected road portion at Veeraragavan street in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/2010,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,999000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT CHELLAPA STREET NEAR SCHOOL IN DN-75, UNIT-17, ZONE-6. (WARD COUNCILLOR FUND.2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/2013,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,999000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER AT CHELLAPA STREET NEAR VINAYAGAR KOVIL IN DN-75, UNIT-17, ZONE-6. (WARD COUNCILLOR FUND.2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/2015,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,998000,PROPOSED CONSTRUCTION OF MORDERN STAINLESS STEEL BUS SHELTER AT( G 3 POLICE STATION OPPOSITE ) UNDER COUNSILLOR FUND IN DN 73 UNIT 17 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/20529,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,995000,"CONVERTING AND MODIFYING THE OLD GYM BUILDING INTO AMMA UNAVAGAM PHASE 2 AT BOGIPALAYAM IN DN-77, UNIT-17,ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20620,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,600000,"FORMING AND LAYING OF BT ROAD IN GKM COLONY 39TH STREET IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20628,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,521000,"FORMING AND LAYING OF BT ROAD AT KAMBAR NAGAR EXTN - GANDHI AVENUE IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2017-18 NF/2015-16/20694,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,879000,"IMPROVEMENTS TO THE EXISTING BT ROAD BY CC ROAD AT KALVAKARAI STREET (REACH 1) IN DIV 72,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20695,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,831000,"IMPROVEMENTS TO THE EXISTING BT ROAD BY CC ROAD AT KALVAKARAI STREET (REACH 2) IN DIV 72,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20739,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,882000,"Rectification and relaying the Flood affected road with BM 50mm Thick and BC 30mm Thick in Paver Finisher at Constable Road From Anderson road To Mylappa street junction in Div-69, Unit-16, Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/2074,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2120000,"RELAY ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT SOMASUNDARAM NAGAR MAIN STREET IN DN-71,U-16,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20747,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,706000,"Rectification and relaying the Flood affected road with BM 50mm Thick and BC 30mm Thick in Paver Finisher at Constable Road From Mylappa Street junction to Door.no:44 in Div-69, Unit-16, Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/2075,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2120000,"RELAY ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT SOMASUNDARAM NAGAR 1st STREET IN DN-71,U-16,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20757,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,997000,"IMPROVEMENT TO CHENNAI PRIMARY SCHOOL AT COOKS ROAD IN DN -73, UNIT-17, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/2076,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2120000,"RELAY ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT SOMASUNDARAM NAGAR 2nd STREET IN DN-71,U-16,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/2078,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,578000,"RESTORATION OF ROAD CUT AT BASHAYAM REDDY 2ND STREET ,BASHAYAM REDDY 3RD STREET IN DN 71 UN 16 Z 6",Deposit Works,6,2015-16,2016-17 NF/2015-16/20794,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,995000,"DISMANTLING EXISTING STORM WATER DRAIN TOP SLAB AND RAISING RCC WALL , RELAYING TOP SLAB AT MANNAR SWAMY KOIL STREET FROM PULIYANTOPE HIGH ROAD TO 110 M CHAINAGE IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20810,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,660000,"ANNUAL MAINTANENANCE OF C.S.NAGAR PARK IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/20811,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,970000,"DISMANTLING EXISTING STORM WATER DRAIN TOP SLAB AND RAISING RCC WALL , RELAYING TOP SLAB AT MANNAR SWAMY KOIL STREET FROM EXISTIING CHAINAGE 100 M (210M -310M) IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20817,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,970000,"DISMANTLING EXISTING STORM WATER DRAIN TOP SLAB AND RAISING RCC WALL , RELAYING TOP SLAB AT MANNAR SWAMY KOIL STREET FROM EXISTIING CHAINAGE 100 M (110M -210M) IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20824,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,852000,"Relaying BT road with BC 30mm thick at Sannathi street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20842,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,977000,"ATTENDING TO TEMPORARY RESTORATION OF DEMAGED ROAD BARACKA ROAD 1ST STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20844,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,756000,"Raising the Lowlying Flood affected road portion at Agastheeswarar naagr 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20845,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,860000,"Raising the Lowlying Flood affected road portion at Agastheeswarar naagr 2nd & 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20847,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,890000,"Raising the Lowlying Flood affected road portion at Gangadevi nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20848,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,874300,"Raising the Lowlying Flood affected road portion at Gangadevi nagar 1st cross street & Lane in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/20969,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,208000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT CHANDRAYOGI SAMATHI STREET (FROM JUNCTION OF PH ROAD TO POLICE BOOTH) IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/20980,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,980000,"ATTENDING BT PATCH WORK BY PAVER FINISHER AT SHANTI NAGAR, KABILAR STREET AND BUNDER GARDEN 2nd STREET IN DN 69,",Own Sources,6,2015-16,2016-17 NF/2015-16/2116,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,636000,"RESTORATION OF ROAD CUT AT BASHAYAM REDDY 1STD STREET ,CHANDRAYOGI SAMATHI STREET IN DN 71 UN 16 Z 6",Own Sources,6,2015-16,2016-17 NF/2015-16/2122,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,396000,"Desilliting and Repair @ Providing and SWD at V.O.C Nagar , Mosqid Street, DN -72, Unit -17, Zone -04.",Own Sources,6,2015-16,2016-17 NF/2015-16/2166,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,694000,RESTORATION OF ROAD CUT AT RAJIVI GANDHI NAGAR IN DN 71 UN 16 Z 6,Own Sources,6,2015-16,2018-19 NF/2015-16/2167,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,607000,RESTORATION OF ROAD CUT AT BRISHLY NAGAR LANE IN DN 71 UN 16 Z 6,Deposit Works,6,2015-16,2016-17 NF/2015-16/2168,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,776000,RESTORATION OF ROAD CUT AT EKANGIPURAM 4TH STREET IN DN 71 UN 16 Z 6,Deposit Works,6,2015-16,2016-17 NF/2015-16/2169,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,880000,RESTORATION OF ROAD CUT AT KRISHNA DOSS MAIN ROAD IN DN 71 UN 16 Z 6,Own Sources,6,2015-16,2018-19 NF/2015-16/2170,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,578000,RESTORATION OF ROAD CUT AT MALAYAPPAN STREET IN DN 71 UN 16 Z 6,Own Sources,6,2015-16,2017-18 NF/2015-16/21704,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,980000,"Desilting the Railway Canal Between Dass nagar and Otterinullah Canal ch.0m to 250m in DN72,Unit-17,Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/21707,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,980000,"Desilting the Railway Canal Between Dass nagar and Otterinullah Canal ch.250m to 500m in DN72,Unit-17,Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/21711,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,980000,"Desilting the Railway Canal Between Dass nagar and Otterinullah Canal ch.500m to 750m in DN72,Unit-17,Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/21784,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,582000,"ATTENDING REPAIR WORKS AND REPLACING DAMAGED MANHOLE COVERS AT VARIOUS LOCATIONS IN DN - 69, UNIT- 16, ZONE- VI",Own Sources,6,2015-16,2016-17 NF/2015-16/21795,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,159000,"ATTENDING PATCH WORK AT SHANTHI NAGAR AND MH ROAD IN DN - 69, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/21866,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,197000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINFISHER AT CHANDRAYOGI SAMATHI STREET (FROM POLICE BOOTH TO CHENNAI PRIMARY SCHOOL) IN DA-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/21867,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,369000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT CHANDRAYOGI SAMATHI STREET (FROM CHENNAI PRIMARY SCHOOL TO PANANTHOPE RAILWAY COLONY) IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/21869,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,184000,"PROVIDING ADDITIONAL BORE WELL TO MURASOLIMARAN PARK AT PERAMBUR HIGH ROAD (SOUTH) IN DN-71,UNIT-16,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/21871,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,117000,"DESILTING OF STORM WATER IN BASIYAM REDDY 3RD STREET IN DN-71, U-16, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/21872,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,4667000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT CHANDRAYOGI SAMATHI STREET IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/21873,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,430000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT KRISHNADOSS ROAD (FROM CHENNAI PRIMARY SCHOOL TO JUNCTION OF KRISHNADOSS 2ND STREET) IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/21874,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,809000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT KRISHNADOSS ROAD (FROM JUNCTION OF KRISHNADOSS 2ND STREET TO PTC DEPOT) IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/21878,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,347000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT MALAYAPPAN STREET (TO BEGINING OF BRISLY NAGAR 5TH STREET) IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/21879,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,610000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH SDBC 40MM THICK BY PAVER FINISHER AT MALAYAPPAN STREET IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/21882,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,51000,"Providing water supply arrangements to lorry station at PH road in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/21883,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,72000,"Repair works to amma unavagam at perambur high road (south) in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/2216,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,999000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT TRUST SQUARE MAIN STREET IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/2225,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,997000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT TRUST SQUARE ( NORTH SIDE ) IN DN-74, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/22324,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,977000,"IMPROVEMENTS TO THE URUDHU SCHOOL AT BOGIPALAYAM AND WOMEN SELF HELP GROUP BUILDING AT MOTHILAL STREET IN DN-77,U-17,Z-6",Own Sources,6,2015-16,2018-19 NF/2015-16/22448,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,994000,"Providing and Laying Wet Mix at Demellows road, Old slaughter house road, St jeswanthamal st, Katur nalla muthu st etc in Dn 77, U-17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/22449,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,820000,"SUPPLYING AND PAVING INTER LOCKING BLOCKS AT SOUTHERN SIDE OF DEMELLOWS ROAD IN DN-77,U-17,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/22450,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,805000,"SUPPLYING AND PAVING INTER LOCKING BLOCKS AT NORTHERN SIDE OF DEMELLOWS ROAD IN DN-77,U-17,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/22451,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,309000,"PROVIDING GROUP BIN PLATFORM AT DEMELLOWS ROAD AND FACE LIFT WORK IN FRONT OF PC AT BASIN ELEPHANT GATE ROAD IN DN-77,U-17,Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/22452,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,931000,"Providing and Laying Wet Mix at Elephant Gate Bridge road, Khaja sahib st, Bogipalayam 2nd st, lane, Pulianthope High road, PK colony, Sundarapuram etc. in Dn 77, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/2246,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,561000,Relaying Cement Concrete road with M30 Grade at G.K.M COLONY 35TH STREET EXTN in Dn65 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/22665,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,988000,"ATTENDING BT PATCH WORK BY PAVER FINISHER AT BUNDERGARDEN MAIN ROAD AND JAWAHAR STREET, GOWTHAMAPURAM IN DN 69,",Own Sources,6,2015-16,2016-17 NF/2015-16/22728,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,524000,PROVIDING ZEN MODULAR SHELTER WITH ONE YEAR MAINTENANCE AT BAKTHAVATCHALAM PARK IN PATTALAM IN DN 76 UNIT17 ZONE 06,Own Sources,6,2015-16,2017-18 NF/2015-16/22761,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,978000,"IMPROVEMENT TO NIGHT SHELTER AND PROVIDING G.I SHEET SHED AND IN FRONT OF SHELTER IN DN-77,U-17,Z-6",Own Sources,6,2015-16,2018-19 NF/2015-16/22771,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,530000,"PROVIDING 16 NOS OF GI SHEET AT KP PARK (FOR SLUM AREA PEOPLES) IN DN-77,U-17,Z-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/22994,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,209000,"MAINTANENCE OF PARK BY PRIVATATION ENGAGING OUTSOURCING AT RAGHAVAN STREET in Div-69,UnIt-16,Z-6",Own Sources,6,2015-16,2018-19 NF/2015-16/22996,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,216000,MAINTENANCE OF PARK BY PRIVATATION ENGAGING OUT SOURCING AT VENKATESWARA NAGAR 1ST STREET PARK IN DIV 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2018-19 NF/2015-16/23317,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,993000,"ADDITIONAL IMPROVEMENT WORKS TO AMMA UNAVAGAM PHASE 2 AT BOGIPALAYAM IN DN-77, UNIT-17,ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23320,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,650000,IMPROVEMENT TO STORM WATER DRAIN AT LOCO SCHEME 2ND STREET IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23323,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,33000,"Repair and Improvements to Public Convenient at Puliyanthope 5th Street and Sivarajapuram in Dn -77, U -17, Z -6.",Own Sources,6,2015-16,2018-19 NF/2015-16/23325,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,387000,MAINTAINES ANANDAN PARK BY ENGAGING OUT SOURCING FOR 12 MONTHS IN DN 67 UNIT 15 ZONE 6,Own Sources,6,2015-16,2017-18 NF/2015-16/23327,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,140000,"PROVIDING LABOUR FOR CLEANING , HIRE CHARGES TATA ACE AND LAYING WET MIX MACADAM AT VARIOUS STREET IN DN 67 UNIT 15 ZOE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23410,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1320000,"Relaying BC 30mm thick with camber correction at Katur nalla muthu Street, Dn 77, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23414,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,687000,"Relaying BC 30mm thick with Camber correction at Avadi srinivasa street, Dn 77, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23415,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1360000,LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT ANBAZHAGAN NAGAR 4 TH STREET IN DIV 68 UNIT 16 ONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23418,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,440000,LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT BALAMUARUGAN STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23419,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,990000,Repair works to collapsed swd at Sembium Redhills road Near Annai sathya nagar to plot no 4 in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/23420,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,490000,LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CONNECTION AT DHANAMMALL STREET IN DIV 68 UNIT 16 ONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23421,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1820000,LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CONNECTION AT ESI HOSPITAL ROAD IN DIV 68 UNIT 16 ONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23426,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,640000,LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION ATGANDHI STREEET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23428,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,2280000,LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KKR AVENUE IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23432,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,290000,LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CONNECTION AT KAMARAJ NAGAR 1ST STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23434,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1164000,"LAYING OF CEMENT CONCRETE ROAD RMC M30 IN V.O.C NAGAR 3RD CROSS STREET IN DN-72,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23436,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,752400,"Relaying BC 30mm thick with Camber correction at Mothilal Street, Dn 77, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23437,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,395000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KAMARAJ NAGAR 2N STREET IN DN - 68, UNIT - 16, ZONE - 06",Own Sources,6,2015-16,2016-17 NF/2015-16/23439,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,290000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KAMARAJ NAGAR 3RD STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23440,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1158000,"Relaying BC 30mm thick with Camber correction at Khaja Sahib Street, Dn 77, U 17, Z 6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23442,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,2260000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KENNADY SQUARE MAIN ROAD IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23450,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,2340000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KENNADY SQUARE CROSS STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23459,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,7302000,"LAYING OF CEMENT CONCRETE ROAD RMC M30 IN V.O.C EXTN 1 TO 18 LANES IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/23465,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1100000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KENNADY SQUARE 3RD NORTH STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23468,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,687000,"Relaying BC 30mm thick with Camber correction at Bogipalayam 2nd main road, Dn 77, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23478,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,220000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KENNADY SQUARE 3RD NORTH 1ST LANE IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23482,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,519000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balaji nagar 2nd cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23486,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,158000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balaji nagar 7th cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23487,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,226000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balaji nagar 8th cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23488,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,307000,"Relaying BC 30mm thick with Camber correction at Oil Mil Street, Dn 77, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23489,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,265000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CONNECTION AT KENNADY SQUARE 3RD NORTH 2ND LANE IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/2349,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,790000,"Raising the Lowlying BT Road at Thenpalani nagar Rajaji street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23492,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,229000,"Raising the Lowlying BT Road with BC 30 mm thick at Tirupathi nagar extn Indira avenue in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23495,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,313000,"Raising the Lowlying BT Road with BC 30 mm thick at Tirupathi nagar extn Kamaraj street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23496,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,465000,"Raising the Lowlying BT Road with BC 30 mm thick at Tirupathi nagar extn Vallalar street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/2350,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,720000,"Raising and Forming CC Road with M30 Grade at Murugan nagar 1st lane in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23500,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,490000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT KENNADY SQUARE 3RD NORTH 3RD LANE IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23501,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,634215,"RELAYING OF CEMENT ONCRETE ROAD RMC M30 IN GREY NAGAR 1ST STREET IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23503,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,247000,"Raising the Lowlying BT Road with BC 30 mm thick at sundharam nagar green land avenue in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23505,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,3100000,"Relaying BC 30mm thick with Camber correction at Astabujam road, Dn 78, U 17, Z 6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23510,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,950000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT LAKSHMI NAGAR 2ND STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23513,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,444000,"Raising the Lowlying BT Road with BC 30 mm thick at srinagar colony middle street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23514,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,508000,"Raising the Lowlying BT Road with BC 30 mm thick at srinagar colony 1st cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23516,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,550000,"Raising the Lowlying BT Road with BC 30 mm thick at srinagar colony west street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23517,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,287000,"Raising the Lowlying BT Road with BC 30 mm thick at srinagar colony anex 2nd cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23519,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1110000,"Relaying BC 30mm thick with Camber correction at Subba (N) Street, Dn 78, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/2352,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,640000,"Raising for Lowlying BT Road with BC 40mm thick at Ganapathy street(Poompugar nagar) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23521,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,920000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT LAKSHMI NAGAR 3RD STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/2353,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,365000,"Raising for Lowlying BT Road with BC 40mm thick at Vijaya Nagar Extension in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23532,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,230000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT MIR-SAJJATH HUSSAIN STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23534,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,760000,"Raising the Lowlying BT Road with BC 30 mm thick at Siva parvathy nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23536,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1445000,"Relaying BC 30mm thick with Camber correction at Vadamalai street, Dn 78, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23537,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,460000,"Raising the Lowlying BT Road with BC 30 mm thick at Somanathapuram 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23538,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,280000,"Raising the Lowlying BT Road with BC 30 mm thick at Somanathapuram 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23539,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,140000,"Raising the Lowlying BT Road with BC 30 mm thick at Balakumaran nagar B Part 1st cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/2354,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,496500,"Raising for Lowlying BT Road with BC 40mm thick at Vijaya Nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23541,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,570000,"LAYING BITUMINOUS ROAD BY PAVER FINISHER WITH CAMBER CORRECTION AT PANDIAN STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23546,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,420000,"Raising the Lowlying BT Road with BC 30 mm thick at Thiruveethiamman kovil street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23548,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,325000,"Raising the Lowlying CC Road with M30 at Thenpalani nagar ext Nehru street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23549,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,161000,"Raising the Lowlying CC Road with M30 at Ambedkar nagar 1st cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/2355,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,175600,"Raising for Lowlying BT Road with BC 40mm thick at V.P.Sindhan nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23551,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,570000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT PONNU SAMY NAGAR MAIN STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23552,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1220000,"Relaying the Lowlying CC Road with M30 at East street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23553,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,308000,"Relaying the Lowlying CC Road with M30 at East street 1st cross in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23554,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,286000,"Relaying the Lowlying CC Road with M30 at East street 2nd cross in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23555,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,455000,"Relaying the Lowlying CC Road with M30 at Thiruveethiamman koil 1st cross in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23556,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,934885,"RELAYING OF CEMENT CONRETE ROAD RMC M30 IN GREY NAGAR 2ND STREET IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/23557,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,660000,"Relaying the Lowlying CC Road with M30 at Thiruveethiamman koil 2nd cross in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23558,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,915000,"Relaying BC 30mm thick with Camber correction at Kariappa Street, Dn 78, U 17,Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23560,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,548000,"Relaying the BT Road with BC 30 mm thick at Mettu street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/23561,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,495000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT PONNU SAMY NAGAR 1ST STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23562,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,479379,"LAYING OF BT ROAD AT THILLAI NAGAR 2ND MAIN ROAD IN DN-65, U-15, ZN-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23563,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,846000,"Relaying the BT Road with BC 30 mm thick at West mada street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/23565,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,420000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT PONNU SAMY NAGAR 2ND STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23567,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,475000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT PONNU SAMY NAGAR 3RD STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23569,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,3055000,"Relaying BC 30mm thick with Camber correction at Rangaiah Street, Dn 78, U 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/2357,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,807100,"Relaying the road at Uma maheshwari nagar 4th street Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23570,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,890000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT PONNU SAMY NAGAR 3RD CROSS STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23571,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,882782,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN GREY NAGAR 3RD STREET IN DN-73 UNIT-17,ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/23574,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,665000,"Relaying the Lowlying BT Road with BC 30mm thick at Prabhu street in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23576,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,775000,"Relaying the Lowlying BT Road with BC 30mm thick at kumaran nagar 7th cross street in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23579,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,396375,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN GREY NAGAR 1ST CROSS STREET IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23581,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,626000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT RAGHAVAN STREET (GEORGE COLONY) IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23584,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1045000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23585,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,130000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT SEETHAPATHY STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23586,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,330000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road 1 Cross Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23588,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,3900000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT MADURAI SWAMY MADAM STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23589,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,330000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road 2nd Cross Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23590,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,352800,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road 3rd Cross Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23591,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,330000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road 4th Cross Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23592,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,396375,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN GREY NAGAR 2ND CROSS STREET IN DN73, UNIT-17,ZONE-VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23593,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,245800,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road 5th Cross Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23594,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,900000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT MOHAMADIAN STREET IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23595,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,338900,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road 6th Cross Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23597,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,199000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Slum Clearance Board Tenement Main Road 7th Cross Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23598,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,468000,"Laying Cement Concrete Road RMC 30 At Adisesha Nagar 1st Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23599,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,461000,"Laying Cement Concrete Road RMC 30 At Adisesha Nagar 2nd Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23600,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,530000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi 1st Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23601,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,685000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi 2nd Street in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23602,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,373000,"Laying Cement Concrete Road RMC 30 At Chandrayogi Samadhi Street lane in DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23603,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,615222,"LAYING OF BT ROAD AT AKBAR SQUARE 3RD STREET IN DN-65, U-15, ZN-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23604,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1670000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT PRAKASH AVENUE IN DN - 68, UNIT -16, ZONE -06",Own Sources,6,2015-16,2016-17 NF/2015-16/23606,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1050000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT SABAPATHY STREET IN DN - 68, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23611,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,503450,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN GREY NAGAR 3RD CROSS STREET IN DN73, UNIT-17,ZONE-VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23613,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1110000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CONNECTION AT WATKIN STREET IN DN - 68, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23614,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,261375,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN GREY NAGAR KRIHNAPILLAI STREET IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23615,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,422741,"LAYING OF BT ROAD AT KRISHNA NAGAR 4TH STREET IN DN-65, U-15, ZN-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23617,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,420000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT TEEDS GARDEN 1ST CROSS STREET IN DN - 68, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23618,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1445000,"Relaying BC 30mm thick with Camber correction at Nammalwar Street, Dn 78, U 17,Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23619,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1271838,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN PERIYAR NAGAR MAIN ROAD IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23620,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,448000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT TEEDS GARDEN 2ND STREET IN DN - 68, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23622,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1290000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT TEEDS GARDEN 3RD STREET IN DN - 68, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23623,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,812868,"LAYING OF BT ROAD AT KAMBAR NAGAR 6TH STREET IN DN-65, U-15, ZN-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23624,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,420000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CORRECTION AT TEEDS GARDEN 3RD CROSS STREET IN DN - 68, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23625,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1974000,"LAYING BITUMINOUS ROAD AT PAVER FINISHER WITH CAMBER CONNECTION AT TEEDS GARDEN 4TH STREET IN DN - 68, UNIT - 16, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/23626,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,925000,"Relaying BC 30mm thick with Camber correction at Chokavel subramani Koil Street, Dn 78, U 17,Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23628,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,444954,"LAYING OF BT ROAD AT THIRUVALLUVAR STREET IN DN-65, U-15, ZN-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23629,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1270000,"Relaying BC 30mm thick with Camber correction at Narasinga Perumal Koil Street, Dn 78, U 17,Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23632,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1585000,"Relaying BC 30mm thick with Camber correction at Tk Mudalil Street, Dn 78, U 17,Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23633,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1184829,"LAYING OF BT ROAD AT RANGADOSS REDDY COLONY MAIN ROAD IN DN-65, U-15, ZN-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23634,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1285000,"Relaying BC 30mm thick with Camber correction at Periya Thambil Street, Dn 78, U 17,Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23635,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1275000,"Relaying BC 30mm thick with Camber correction at Mookatha Streetl Street, Dn 78, U 17,Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/23636,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,3246000,"Relaying Cement Concrete Road RMC 30 At Andiyappan Street in Dn-68 ,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23638,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1218000,"Laying Cement Concrete Road RMC 30 At Teeds Garden 5th Street in Dn-68,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23639,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,4290000,"Laying Cement Concrete Road RMC 30 At Othavadai 1st Street in Dn-68,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23640,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1402000,"Laying Cement Concrete Road RMC 30 At Othavadai 2nd Street in DN-68,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23649,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1497000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar Main Road 4th street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23650,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,694000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar Main Road 5th street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23651,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,758000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar Main Road 6th street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23652,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1510000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar Main Road 7th street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23653,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,725000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar Main Road 8th street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23654,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,725000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar Main Road 9th street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23656,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,407000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar 1st Cross street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2017-18 NF/2015-16/23657,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,561000,"Laying Cement Concrete Road RMC 30 At Thiru.Vi.Ka.Nagar 2nd Cross street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2017-18 NF/2015-16/23658,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1163000,"Laying Cement Concrete Road RMC 30 At voc Nagar 1 Cross street in dn72,unit-17,zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23659,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1163000,"Laying Cement Concrete Road RMC 30 At v.o.c.Nagar 2nd Cross Street in DN-72,Unit-17,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/23662,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,183410,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN PERIYAR NAGAR 8TH CROSS STREET IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23663,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,1173095,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN BABU STREET IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23664,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,485319,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN BABU LANE IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23666,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,727075,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN ANANDAVINAYAKAR KOIL STREET IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23667,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,872839,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN HAJIMOHAMMED HABBAS STREET IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23668,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,316119,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN K.M.GARDEN 10TH STREET IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23669,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,249803,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN K.M.GARDEN 11THSTREET IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23670,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,445678,"RELAYING OF CEMENT CONCRETE ROAD RMC M30 IN K.M.GARDEN 15TH STREET IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23674,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,774000,LAYING BT ROAD BY PAVER FINISHER AT THILLAINAYAGAM MAIN STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23676,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,355000,LAYING CC ROAD AT THILLAINAYAGAM 1 ST STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23677,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,500000,LAYING BT ROAD BY PAVER FINISHER AT THILLAINAYAGAM 2 ND STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23678,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,660000,LAYING BT ROAD BY PAVER FINISHER AT ELUMALAI STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23679,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,984000,LAYING BT ROAD BY PAVER FINISHER AT THIRUNAVUKARASU STREET IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23694,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,397000,LAYING BT ROAD BY PAVER FINISHER AT PRAKASH LANE DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/23798,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1321000,"Relaying RMC M30 Grade Cement concrete road at Thiru vi ka nagar main road, Dn 72, U 17, Z 6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23826,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,250000,"Raising the Lowlying BT Road with BC 30 mm thick at Gandhi Nagar Kasthuribai street Div-67,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23827,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1560000,"Raising the Lowlying BT Road with BC 30 mm thick at Kumaran Nagar Main Road Div-67,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23828,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,775000,"Raising the Lowlying BT Road with BC 30 mm thick at Sai Nagar 4th street in Div-67,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23829,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1870000,"Raising the Lowlying BT Road with BC 30 mm thick at Sai Nagar 3rd street in Div-67,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/23848,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,635000,"RELAYING B.T ROAD BY PAVER AT SAMBANTHAN STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23849,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1167000,"RELAYING B.T ROAD BY PAVER AT SUBRAMANI STREET IN DN-70,UNIT- 16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23850,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2645000,"RELAYING B.T ROAD BY PAVER AT VADIVELU STREET IN DN-70,UNIT- 16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23852,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,882000,"RELAYING B.T ROAD BY PAVER AT CHINNAIYA COLONY 1ST MAIN ROAD IN DN-70,UNIT- 16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23853,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,3160000,"RELAYING B.T ROAD BY PAVER AT BHARATHI ROAD IN DN-70,UNIT- 16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23854,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,900000,"RELAYING B.T ROAD BY PAVER AT RAMAKRISHNAN STREET IN DN-70,UNIT- 16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23855,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,381000,"RELAYING B.T ROAD BY PAVER AT VENKATARAMAN STREET IN DN-70,UNIT- 16,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/23881,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,335000,Repair works to Damaged SWD at Sembium Red Hills road near Vivek Nagar in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/23882,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,992000,Repair works to Damaged swd at Ganapathy Rao Nagar in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/23884,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,950000,"Repair works to Damaged swd at Sembium Red Hills road (From Somanathapuram to OPP to Ewarwin school) in Dn64 U15 Z06",Own Sources,6,2015-16,2016-17 NF/2015-16/2450,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,93000,"IMPROVEMENTS TO PUBLIC CONVIENCE (LADIES AND GENTS) AT PERAMBUR HIGH ROAD IN DIV-71,UN-16,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/24574,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,678000,PROVIDING INTERLOCKING PAVER BLOCK AT JAMALIYA SLUM BOARD ROAD IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/24607,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,930000,Repair works to Damaged SWD at Samtharia Colony 4th street Junction in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/24617,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,970000,Repair works to Damaged SWD at Sembium Redhills road (From Amsavision to Lakshmi amman koil st) in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/24622,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,870000,Construction of SWD at Haridoss 2nd Street to Haridoss Pond in Dn64 U15 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/24661,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,880000,"REPAIRS AND IMPROVEMENT TO PARK AT CONRON SMITH NAGAR STREET IN DN -76, UNIT-16, ZONE-6",Own Sources,6,2015-16,2018-19 NF/2015-16/24748,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,940000,"Repairs works & Improvements for Scout building at Jawahar nagar 1st circular road in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/24790,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,85000,"Desilting and Raising the Chamber for SWD at Gandhimathi street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/24800,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,564000,"IMPROVEMENTS AND REPAIR PUBLIC CONVEYENCE AT DEMOLLOWS ROAD INSIDE RATION OFFICE IN DN-77, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/24886,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,476000,"IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT POWDER MILL ROAD PULIANTOPE (opposite to RTO office ) IN DN-72,U-17,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/24887,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1880000,"ATTENDING TO TEMPORARY RESTORATION OF DEMAGED ROADA.K. SAMY NAGAR 1ST STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/24979,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,54600,"IMPROVEMENT TO DRAIN WORK AT MOSQUE STREET IN DN-77, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/24983,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,49500,"Repair and Improvements to Gym Building and NNMP Shed at P.K Colony and Demellos Road in Dn -77, U -17, Z -6.",Own Sources,6,2015-16,2018-19 NF/2015-16/24992,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,33000,"IMPROVEMENT TO T.B HOSPITAL BUSSTOP AT PULIYANTHOPE MAIN ROAD IN DN-77, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/24998,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,770000,"CHANGING THE DELABILEATED RCC ROOF FOR DRESS STORAGE ROOM AT DHOBIKANA STORAGE ROOM NO 6 IN DN76, UNIT-17,ZONE-6",Own Sources,6,2015-16,2018-19 NF/2015-16/25082,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,990000,"IMPROVEMENT TO STORM WATER DRAIN AND RAISING AND LOWERING MAN HOLE DOOR AT VARIOUS STREET IN-76, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2020-21 NF/2015-16/25086,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,930000,"DESILTING AND IMPROVEMENT TO STORM WATER DRAIN AT AMMAIAMMAL STREET,STRAHNS ROAD,NATCHARAMMAL LANE AND OTHER STREETS IN-73, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/25178,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,382000,"Construction Of compound wall & pavements in open gym @ Haridoss Kulam In Dn-64 , Unit-15, Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/25179,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,955000,"PROVIDING AND FIXING OF ARASU E-SEVA CENTRE SIGNAGE NAME BOARD AT DN 64 TO 78, UNITS-15,16 AND 17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/25184,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,420000,"ATTENDING PATCH WORK AT NEW FERRANCE ROAD AND KUTTY THAMBIRAN STREET IN DN-73, U-17, Z-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/25203,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,873000,"PROVIDING ADDITIONAL BOYS TOILET IN EAST SIDE FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT DN-64, UNIT-15, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/25243,Subway,Completed,NF-THIRU-VI-KA NAGAR,65,684000,"REGRADING THE CHANNEL FROM SENTHIL NAGAR TO KOLATHUR RETTAERI ALONG 100 FEET ROAD EASTERN SIDE IN DN-65,UNIT-15,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/25257,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,980000,"REGRADING THE CHANNEL FROM SENTHIL NAGAR TO KOLATHUR RETTAERI ALONG 100 FEET ROAD WESTERN SIDE IN DN-65,UNIT-15,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/25263,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,979000,"IMPROVEMENT TO FLOOD AFFECTED CANAL BANK AND CONSTRUCTION OF PARAPET WALL AT EKANGIPURAM CANAL (NEAR KH ROAD) IN DIV-71, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/25849,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,913000,"PROVIDING ADDITIONAL GIRLS TOILET IN NORTH SIDE FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT DN-64, UNIT-15, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/25856,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,913000,"PROVIDING ADDITIONAL GIRLS TOILET IN EAST SIDE FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT DN-64, UNIT-15, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/25860,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,913000,"PROVIDING ADDITIONAL BOYS TOILET IN NORTH SIDE FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT DN-64, UNIT-15, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/25974,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,892000,"PROVIDING WEATHERING COURSE AND OTHER IMPROVEMENTS TO AMMA UNAVAGAM AT KURAVAN KULAM STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/26028,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,790000,"IMPROVEMENTS TO STORM WATER DRAINS IN MD.HUSSAIN COLONY,VEENUS NGR,JAYANTHI NAGAR,VIVEKANANDHA NGR MAIN RD AT DN-65,U-15,ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/2604,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,820000,"LAYING OF CC ROAD AT KAMBAR NAGAR 1ST CROSS ST IN DIV-65,UNIT-15,ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/26118,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,36000,"LAYING WET MIX TO FLOOD AFFECTED ROADS AT KRISHNADOSS MAIN ROAD,MALAYAPPAN STREET,SUBBURAYAN STREET,TANK BUND ROAD,K.H.ROAD IN DN-71,UNIT-16,ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/26160,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,997000,"PROVIDING STREET FURNITURES AT(EGANGIPURAM, KRISHNADOSS ROAD,MANGALAPURI,HYDER GARDAN,BASHYAM REDDY STREET,BRISHLY NAGAR,AADISHESHA NAGAR) UNDER WARD COUNCILOR FUND (2015-16) IN DN-71,UN-16,Z-6",Own Sources,6,2015-16,2017-18 NF/2015-16/26278,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,867000,"FORMING OF SPEED BREAKER AS PER IRC STANDARDS AT VARIOUS STREETS IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2016-17 NF/2015-16/2657,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,71,361000,RESTORATION OF ROAD CUT AT KONNUR HIGH ROAD IN DN 71 UN 16 Z 6,Deposit Works,6,2015-16,2016-17 NF/2015-16/26668,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,176000,"PROPOSED CONSTRUCTION OF ADDITIONAL TOILET ELECTRICAL WORK FOR BOYS NORTH AND EAST SIDE IN GOVERNMENT HIGHER SECONDARY SCHOOL AT DN64, UNIT-15, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/26675,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,952000,"PROPOSED CONSTRUCTION OF ADDITIONAL TOILET PLUMBING WORK FOR BOYS AND GIRLS IN NORTH AND EAST SIDE AT GOVERNMENT HIGHER SECONDARY SCHOOL AT DN-64, UNIT-15, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/26977,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,850000,"MAINTENANCE TO TROPICAL DRY EVER GREEN FOREST ( HERBAL PARK) AT OTTERI IN DN-74, UNIT-17, ZONE-6. ( FOR SIX MONTHS)",Own Sources,6,2015-16,2016-17 NF/2015-16/26978,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,771000,"PROVIDING AND LAYING INTER LOCKING BLOCKS IN ROAD SIDES AT TRUST SQUIRE IN DN-74, U-17, Z-6. ( WARD COUNCILLOR FUND)",Own Sources,6,2015-16,2018-19 NF/2015-16/26979,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,400000,"PROVIDING AND FIXING STORM WATER DRAIN FRAME WITH MAN HOLE COVER IN VARIOUS STREETS IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/26980,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,500000,"IMPROVEMENTS TO PUBLIC TOILETS AT RANGANATHAPURAM, MEDAVAKKAM TANK ROAD, SUBURAYAN 1ST STREET, S.V.M. NAGAR IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/27009,Playfields,Completed,NF-THIRU-VI-KA NAGAR,74,350000,"IMPROVEMENTS TO RANGANATHAN CHILDRENS PLAY GROUND AT MEDAVAKKAM TANK ROAD IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/27010,Playfields,Completed,NF-THIRU-VI-KA NAGAR,74,350000,"IMPROVEMENTS TO CHILDRENS PLAY GROUND AT A.K. SAMY NAGAR 1ST STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/27012,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1040000,"ATTENDING TO TEMPORARY RESTORATION OF DEMAGED ROAD AT OTHAVADAI STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/27013,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,997000,"RELAYING BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT SAMY BAKTHAN STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/27014,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1100000,"ATTENDING TO TEMPORARY RESTORATION OF DEMAGED ROAD AT BARAKKA ROAD 2nd STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/2727,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,995000,"PROVIDING STREET FURNITURE IN VARIOUS STREETS IN DN-75, UNIT-17, ZONE-6 (ward councillor fund 2015-2016)",Own Sources,6,2015-16,2016-17 NF/2015-16/27320,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,364000,"IMPROVEMENTS TO PARK AT THIRU VI KA NAGAR PALLAVAN SALAI IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/27347,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,985000,"CONSTRUCTION OF CHAPPATHY ROOM IN AMMA UNAVAGAM AND IMPROVEMENTS TO BIO-GAS PLANT AT LOGO WORKS SCHEME 1ST STREET IN DIV-67,UN-15,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/27547,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,955000,"IMPROVEMENTS TO STORM WATER DRAIN IN SENTHIL NAGAR 2ND MAIN ROAD IN DN-65, U-15, ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/27551,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,890000,"IMPROVEMENTS TO STORM WATER DRAIN IN SENTHIL NAGAR 3RD MAIN ROAD DN-65, U-15, ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/27594,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,959000,"IMPROVEMENTS TO STORM WATER DRAIN IN RANGA DOSS COLONY, TEACHERS GUILD COLONY AND NETHAJI NAGAR IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/27609,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,938000,"PROPOSED CONSTRUCTION OF SWD AT MD.HUSSAIN COLONY MAIN ROAD IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2016-17 NF/2015-16/27611,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,945000,"PROPOSED CONSTRUCTION OF SWD AT THIRUMALAI NAGAR IN DN-65, U-15,ZN-6",Own Sources,6,2015-16,2016-17 NF/2015-16/27672,Parks,Completed,NF-THIRU-VI-KA NAGAR,73,498000,MAINTENANCE OF WADIA PARK AT NEW FERANCE ROAD FOR 12 MONTHS IN DN 73 UNIT 17 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/27698,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,498000,"IMPROVEMENTS TO LKG ROOM ,COLOUR WASHING AND COMPOUND WALL REPAIR WORK AT CMS EGANKIPURAM UNDER WARD COUNCILOR FUND (2015-16) IN DN-71 UNIT-16 ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/27715,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,317000,Maintenance of Vadivel(M)2nd cross street park and Kannabiran kovil street Park at Perambur in division 70 unit 16 zone 6 (By QualifiedHorticulturist For one year) .,Own Sources,6,2015-16,2017-18 NF/2015-16/27717,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,906000,": Annual Maintenance of Park at Murasolimaran Park in Dn.70,Unit-16,Zone-6(By QualifiedHorticulturist For one year)",Own Sources,6,2015-16,2017-18 NF/2015-16/2774,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,59000,"Improvements to Manhole Door Work at Sivaraj Road and Demellows Road In Dn -77,U -17, Z -6.",Own Sources,6,2015-16,2018-19 NF/2015-16/27743,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,715000,Laying Cement Concrete Road at G.K.M COLONY 7TH STREET IN Dn 67 Unit 15 Zone 6,Own Sources,6,2015-16,2016-17 NF/2015-16/27765,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,840000,"Construction of Modern Stainless Steel Bus Shelter at Paper Mils Road (Near Lakshmi Amman Koil), Division 64, Unit 15, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/27767,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,840000,"Construction of Modern Stainless Steel Bus Shelter at Paper Mils Road Neermai Nagar Bus Stop Right Side, Division 64, Unit 15, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/27770,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,840000,"Construction of Modern Stainless Steel Bus Shelter at Paper Mils Road Neermai Nagar Bus Stop Left Side Division 64, Unit 15, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2017-18 NF/2015-16/27772,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,840000,"Construction of Modern Stainless Steel Bus Shelter at Paper Mils Road Raja Garden Division 66, Unit 16, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2017-18 NF/2015-16/27773,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,840000,"Construction of Modern Stainless Steel Bus Shelter at 70FT ROAD Paper Mils Road and Sivaelango Salai Junction Division 66, Unit 16, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2017-18 NF/2015-16/27778,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,840000,"Construction of Modern Stainless Steel Bus Shelter at 80ft Road, Balaji Nagar Kumaran Nagar Junction North Side, Division 66, Unit 16, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2017-18 NF/2015-16/27785,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,997000,"TOILET RENOVATION WORK AT BRISHLY NAGAR PUBLIC CONVENIENCE UNDER WARD COUNCILOR FUND (2015-2016)IN DN-71,UNIT-16,ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/27795,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,840000,"Construction of Modern Stainless Steel Bus Shelter at Karthigayan Salai, Near Periyar Nagar Hospital Left Side, Division 66, Unit 16, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/27801,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,840000,"Construction of Modern Stainless Steel Bus Shelter at Karthigayan Salai, Near Periyar Nagar Hospital right Side, Division 66, Unit 16, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/27804,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,840000,"Construction of Modern Stainless Steel Bus Shelter at Paper Mils Road( Near Don Bossco School, Division 66, Unit 16, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2017-18 NF/2015-16/27807,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,780000,"IMPROVEMENT WORKS AT MURASOLIMARAN PARK (SOUTH) IN DN-71,Unit-16,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/27809,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,840000,"Construction of Modern Stainless Steel Bus Shelter at Jawaharlal Nehru Salai, Senthil Nagar Bus Stop Division 65, Unit 15, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2017-18 NF/2015-16/27813,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,840000,"Construction of Modern Stainless Steel Bus Shelter at Jawaharlal Nehru Salai, Retteri Junction Division 65, Unit 15, Zone 6.(MAYOR FUND - 2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/27821,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,650000,"IMPROVEMENTS TO COMMUNITY CENTER AT VENKATATHIRI STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/27901,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,890000,Improvements to SWD at Ashtabujam road in Dn78 Unit 17 Z6,Own Sources,6,2015-16,2017-18 NF/2015-16/27916,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,597000,"CONSTRUCTION OF COMPOUND WALL,GAS ROOM AND OTHER IMPROVEMENTS TO AMMA UNAVAGAM IN DIV-68,UN-16,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/27953,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,890000,"Supplying and Erecting of Portable PC's at Strahns Road Near Otteri Bridge in dn-73 unit-17,zone-06",Own Sources,6,2015-16,2019-20 NF/2015-16/27957,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,990000,"IMPROVEMENT TO STORM WATER DRAIN AT PULIYANTHOPE HIGH ROAD FROM DR.AMBEDKAR COLLEGE ROAD TO PERIYAR NAGAR IN DN-73,UNIT-17,ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/27974,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,760000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT CHELLAPPA STREET IN DN-75, U-17,Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/27983,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,880000,CONSTRUCTION OF INSPECTION CHAMBER AND PIPE LAYING THROUGH OUT THE LENGTH OF BASIN BRIDGE ROAD FOR REMOVAL OF RAIN WATER STAGNATION IN DN-72 UNIT-17 ZONE-6,Own Sources,6,2015-16,2018-19 NF/2015-16/28006,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,280000,"Desilting and repair to SWD at Sivarajapuram main street, Sundarapuram 2nd main street and Door raising work at various street in Dn 77, U 17, Z 6.",Own Sources,6,2015-16,2018-19 NF/2015-16/28088,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,930000,"RENOVATION OF OLD SHED AT ZONE VI LORRY STATION AT PERAMBUR HIGH ROAD (SOUTH) IN DN-71,UNIT-16,ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/28156,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,973000,"IMPROVEMENTS TO UNUSED SCHOOL BUILDING FOR PROVIDING DIVISION OFFICE AT OLD SLAUGHTER HOUSE ROAD IN DN-77 UNIT-17, ZONE-VI",Own Sources,6,2015-16,2018-19 NF/2015-16/28176,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,448000,"DISMANTLING AND RECOSTRUCTION OF DAMAGED PORTION OF COMPOUND WALL AT ZONE 06 LORRY STATION IN DN-71,UNIT-16,ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/28367,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,471000,"Improvement of Ganeshpuram Subway and Motor Room in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2019-20 NF/2015-16/28393,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,66000,"PROVIDING ROOF GARDEN AT ZONE-VI OFFICE TERRACE IN DN-71 UNIT-16, ZONE-VI",Own Sources,6,2015-16,2016-17 NF/2015-16/28399,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,115000,"SUPPLYING AND FIXING STORM WATER DRAIN MANHOLE WITH FRAME AND WET MIX AT VARIOUS LOCATION IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/28564,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,41000,WATER SUPPLY ARRANGEMENTS TO AMMA UNAVAGAM AT PAPER MILLS ROAD IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/28566,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,57000,"WATER SUPPLY ARRANGEMENTS ,DRAINAGE ARRANGEMENTS TO AMMA UNAVAGAM AT THIRU VI KA NAGAR IN DN 68 UNIT 16 ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/28667,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,930000,"Construction of Compound wall for OSR Land at Anjugam nagar 4th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/28669,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,580000,"Improvements and fixing Ornamental plants,grass and trees for OSR Land at Anjugam nagar 4th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/28672,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,995000,"Construction of Compound wall for OSR Land at Shanthi nagar and Bharathi nagar junction in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/28679,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,924000,"Improvements to Dilapilated Portion (due to flood) of SWD Opp to D.No:101 at P.H.Road in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/28700,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,440000,Maintainance of park by private agency for the Period of Two years at Periyar Nagar 21st street Park in Dn-66 U-16 Z-06,Own Sources,6,2015-16,2018-19 NF/2015-16/28706,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1080000,"ATTENDING TO TEMPORARY RESTORATION OF DEMAGED ROAD AT SANKARABAKTHAN STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/28711,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,255000,"ANNUAL MAINTENANCE AT PATTEL PARK IN CHELLAPPA STREET IN DN-75, U-17, ZONE-6. (12 MONTHS)",Own Sources,6,2015-16,2017-18 NF/2015-16/28787,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,430000,"LAYING CEMENT CONCRETE ROAD AT HENDRICK LANE AND RANGA LANE IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2018-19 NF/2015-16/28789,Bridges,Completed,NF-THIRU-VI-KA NAGAR,78,810000,"LAYING CEMENT CONCRETE ROAD AT KANCHIPURAM MUNUSAMY STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2018-19 NF/2015-16/28792,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,634000,"PROVIDING STREET NAME BOARD AT VARIOUS STREET (WARD COUNCILLOR FUND 2015-2016) IN DIVISION-78, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/28873,Playfields,Completed,NF-THIRU-VI-KA NAGAR,74,370000,"IMPROVEMENTS TO CHILDREN PLAY GROUND AND PROVIDING PLAY APPARATUS AT S.V. M. NAGAR IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/29077,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,999000,"Supply and Errection of Green Outdoor Gym at Kennedy Square 1st North Street Park in Dn-68, Unit-16, Zone-6 ( MAYOR FUND2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/29083,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,999000,"Supply and Errection of Green Outdoor Gym at Haridass Kulam Park in Dn-64, Unit-15, Zone-6 ( MAYOR FUND2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/29086,Footpath,Completed,NF-THIRU-VI-KA NAGAR,75,997000,"FORMING FOOT PATH AT CHELLAPA STREET JUN OF EDWARD PARK TO VINAYAGAR TEMPLE IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/29088,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,999000,"Supply and Errection of Green Outdoor Gym at Thiru Veethi Amman Kulam Park in Dn-64, Unit-15, Zone-6 ( MAYOR FUND2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/29091,Parks,Completed,NF-THIRU-VI-KA NAGAR,69,999000,"Supply and Errection of Green Outdoor Gym at Gowthamapuram Slum in Dn-69, Unit-16, Zone-6 ( MAYOR FUND2015-16)",Own Sources,6,2015-16,2016-17 NF/2015-16/29170,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,1499000,"CONSTRUCTION OF CYCLE SHED AND WATCH MAN ROOM, DINING HALL AT CHENNAI HIGH SCHOOL CHINNABABU STREET IN DN-74, U-17, Z-6 ( M. L.A. FUND )",MLACDS,6,2015-16,2017-18 NF/2015-16/29177,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1290000,"ATTENDING TO TEMPORARY RESTORATION OF DEMAGED ROAD AT SUBURAYAN MAIN STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29178,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,71000,"Repairs to Footpath at M.H.Road (near toilet) in Dn-70, Unit-16, Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/29181,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,127000,"REPAIRS AND IMPROVEMENTS TO NNMP SHED AT CHELLAPA STREET IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29182,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,184000,"REPAIRS AND IMPROVEMENTS TO HEALTH POST AT CHELLAPPA STREET IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29183,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,187000,"IMPROVEMENTS TO MULTIPURPOSE HALL AT S.S. PURAM 1ST STREET IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29187,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,163000,"CONSTRUCTION OF COMPOSED YARD IN OTTERI DUMPING GROUND ,VENKADATHIRI STREET IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29191,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,76000,"SUPPLYING AND FIXING MAN HOLE COVER WITH FRAME IN STROM WATER DRAIN IN VARIOUS STREETS IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29193,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,105000,"IMPROVEMENTS TO PUBLIC CONVEYANCE AT VENKATTAMMAL SAMATHI STREET IN DN-75, U-17, Z-6",Own Sources,6,2015-16,2016-17 NF/2015-16/29194,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,31500,"WATER SUPPLY ARRANGEMENTS NNMP SHEDS AT VALLUVAN STREET, CHELLAPPA STREET IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29236,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,970000,Attending Repair works to AE Office at Jawahar Nagar 3rd Circular road in Dn66 U16 Z06,Own Sources,6,2015-16,2017-18 NF/2015-16/29252,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,250000,Repair works to SWD at Devaki Ammal street From Sivalingam street to Annal Ganthi street in Dn66 U16 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/29254,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,866000,Repair works to SWD for Collopsed portion at Ram Nagar 3rd Main road in Dn66 U16 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/29316,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,50000,Providing Drainage Connction and improvements to Amma Unavagam in Dn66 U16 Z06,Own Sources,6,2015-16,2016-17 NF/2015-16/29357,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,450000,"Construction and Repairs to existing Compound wall at Jawahar nagar 1st circular road in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/29388,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,2300000,"CONSTRUCTION OF NNMP SHED (NO:661) AT OLD VLZHAIMA NAGAR (MLA FUND) IN DN-73,UNIT-17,ZONE-6",MLACDS,6,2015-16,2017-18 NF/2015-16/29434,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,94000,"REPAIRING TRANSFORMER AROUNDING WALL AT SRP KOIL ST , FISH MARKET IN DN 68 UNIT 16 ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/29696,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,998000,"Supply and Errection of Green Outdoor Gym at Murasoli Maran Park in Dn-70, Unit-16, Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/29720,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,500000,"PROVIDING FENCING AND IMPROVEMENTS TO LKG CLASS ROOMS AT CHENNAI PRIMARY SCHOOL MANGALAPURAM UNDER WARD COUNCILOR FUND (2015-16) IN DN-71, UNIT-6,ZONE-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/29757,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,458000,"PROVIDING AND RAIN HARVESTING WELL TYPE IN VARIOUS LOCATION IN HERBAL PARK, BARAKKA ROAD PLAY GROUND IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/29811,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,169000,MAINTENANCE OF PARK BY PRIVATATION OUT SOURCING ENGAGING AT SAJJID HUSSAIN PARK AT PAPER MILLS ROAD IN DN 68 UNIT 16 ZONE 6 (1 YEAR),Own Sources,6,2015-16,2017-18 NF/2015-16/29817,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,169000,MAINTENANCE OF PARK BY PRIVATATION ENGAGING OUT SOURCING AT KKR AVENUE NEAR PALLAVAN SALAI IN DN 68 UNIT 16 ZONE 6 (1YEAR),Own Sources,6,2015-16,2017-18 NF/2015-16/29824,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,169000,MAINTENANCE OF PARK BY PRIVATATION ENGAGING OUT SOURCING AT GEORGE COLONY PARK IN DN 68 UNIT 16 ZONE 6 (1 YEAR),Own Sources,6,2015-16,2017-18 NF/2015-16/29855,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,885000,EROSION CONTROL TO THE POND AT THIRUVEETHIYAMMAN KOIL STREET NORTH & EAST SIDE (MAYOR FUND) IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/2988,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,82000,"IMPROVEMENTS TO PUBLIC CONVIENCE (LADIES AND GENTS) AT RAJIV GANDHI NAGAR IN DIV-71,UN-16,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/30072,Footpath,Completed,NF-THIRU-VI-KA NAGAR,70,556000,"Maintenance to FootPath and Centre Median damaged due to vardha cyclone at Various Streets(patel road,school road,meenatchi street etc..,) in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/30167,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,720000,PROVIDING INTERLOCKING BLOCK TO THE POND AT THIRUVEETHIYAMMAN KOIL STREET NORTH & EAST SIDE IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2015-16,2017-18 NF/2015-16/30168,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,885000,EROSION CONTROL TO THE POND AT THIRUVEETHIYAMMAN KOIL STREET SOUTH & WEST SIDE (MAYOR FUND) IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/30169,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,720000,PROVIDING INTERLOCKING BLOCK TO THE POND AT THIRUVEETHIYAMMAN KOIL STREET SOUTH & WEST SIDE . IN DN 64 UNIT 15 ZONE 6,Own Sources,6,2015-16,2017-18 NF/2015-16/30201,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,780000,"PROVIDING SECURITY ARRENGEMENTS AT OTTERI DUMPING GROUND IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/30202,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,740000,"PROVIDING AND MARKING ROAD MARGINS AND REFLECTIVE STUDS AT FLOOD DAMAGED ROAD ( CHINNA BABU ST, SUBURAYAN 2ND ST, VARADHAMMAL MAIN ST,AND OTHER STREETS ) IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/30204,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,274000,"ATTENDING TO TEMPORARY RESTORATION OF DEMAGED ROAD AT RAMALINGAPURAM (CHENGALVARAYAN STREET& RANGANATHAPURAM STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/30206,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,155000,"SUPPLYING AND FIXING CONSTRUCTION OF INSPECTION CHAMBER IN DRAIN MAN HOLE COVER WITH FRAME IN OTHAVADAI STREET LANES IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/30265,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,679000,"PATCH WORK FOR DAMAGED ROAD AT VENKATESAPURAM MAIN ROAD,BRIGHTENS ROAD,DECASTER ROAD,VOC NAGAR AND OTHYER STREETS IN DN-72 U-17 Z-6",Own Sources,6,2015-16,2018-19 NF/2015-16/30274,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,38000,ADDITIONAL WATER SUPPLY ARRANGEMENTS TO PC AT THIKKAKULAM IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/30484,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,418000,"RELAYING BITUMINOUS CONCRETE 30MM THICK AT A.K.SAMY NAGAR 9TH STREET 1ST AND 2ND LANE IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/3055,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,225000,"DEMOLITION OF SIDE DRAIN AND PROPOSED CONSTRUCTION OF STORM WATER DRAIN 600MMX750MM AT PULIANTHOPE HIGH ROAD AT GANDHI NAGAR IN DN.73, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/3062,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,83000,"IMPROVEMENTS TO VARIOUS SCHOOL BUILDINGS AT IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/3064,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,985000,Relaying BT Road with Paver finisher at Loco scheme upperbridge road south side in Dn-67 Unit-15 Zone-6,Own Sources,6,2015-16,2016-17 NF/2015-16/30730,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,900000,"FILLING RIVER SAND OF PARK AT KENNADI SQUARE 1st NORTH STREET IN DN-68, U-16, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/30732,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,37400,"REPAIRS AND IMPROVEMENTS TO THE NNMP SHED NO 070212 & 07034 AT THIRU. VI. KA. NAGAR IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/30733,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,36000,REPAIRING WATER SUPPLY ARRANGEMENT TO DIVISION OFFICE BUILDING IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/3080,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,985000,Relaying BT Road with Paver finisher at Loco scheme lowerbridge road south side in Dn-67 Unit-15 Zone-6,Own Sources,6,2015-16,2016-17 NF/2015-16/3081,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,740000,Relaying BT Road with Paver finisher at Loco scheme upperbridge road north side in Dn-67 Unit-15 Zone-6,Own Sources,6,2015-16,2016-17 NF/2015-16/30814,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,877000,"LAYING CEMENT CONCRETE ROAD AT GOVINDAN STREET IN DN-78,UNIT-17,ZONE-06",Own Sources,6,2015-16,2018-19 NF/2015-16/3082,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,740000,Relaying BT Road with Paver finisher at Loco scheme lowerbridge road north side in Dn-67 Unit-15 Zone-6,Own Sources,6,2015-16,2016-17 NF/2015-16/3084,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,455000,Relaying BT Road with Paver finisher at Loco scheme upperbridge road west side in Dn-67 Unit-15 Zone-6,Own Sources,6,2015-16,2016-17 NF/2015-16/3086,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,455000,Relaying the BT Road with Paver finisher at Loco scheme bridge Road West side in Dn 67 Unit 15 Zone 6,Own Sources,6,2015-16,2016-17 NF/2015-16/3093,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,930000,"Restoration of Road cut made by TNEB at Jegannathan salai (from Siva Elango salai to Kandasamy salai) in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/30942,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,983000,"PROVIDING FOOTPATH AND IMPROVEMENTS TO COMPOUND WALL TO KOLAM AT KANAKAR STREET IN DIV-67,UN-15,Z-06",Own Sources,6,2015-16,2016-17 NF/2015-16/3095,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,415000,"Restoration of Road cut made by TNEB at Siva elango salai (70' road) in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/30954,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,824000,"LAYING CEMENT CONCRETE ROAD AT V.V KOVIL STREET FROM T.K.MUDALI IN DN-78,UNIT-17,ZONE-06",Own Sources,6,2015-16,2018-19 NF/2015-16/30963,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,780000,"PROVIDING BORE-WELL AND CONSTRUCTION OF STORM WATER DRAIN TO CONNECTING THIRUVEETHI AMMAN KOIL STREET AND TANK IN DIV-64,UN-15,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/30984,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,600000,"Improvements to Centermedian at Sive elango salai inDiv-66,Unit-16,Zone-6",Own Sources,6,2015-16,2018-19 NF/2015-16/30986,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,657000,"Widening the road and Improvements to SWD at Jeganathan salai in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/30993,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,530000,"Forming of Speed breaker as per IRC Standards at Lakshman nagar main road,Ram nagar & Ramamoorthy colony main road in Div-66, Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/30994,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,770000,"Forming of Speed breaker as per IRC Standards at Ragavendra link road, Kumaran nagar 3rd main road & Varatharajan street in Div-66, Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/30995,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,988000,"Dismantling existing colapsed SWD and Reconstruction of RCC SWD at Gandhimathi street ( From Nagammal street to Rgavan street) in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/30996,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,972000,"Dismantling existing colapsed SWD and Reconstruction of RCC SWD at Gandhimathi street ( From Ragavan street to Shanthi street) in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/30997,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,960000,"Dismantling existing colapsed SWD and Reconstruction of RCC SWD at Gandhimathi street ( From Shanthi to Manavalan street) in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31070,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,295000,"Relaying the Lowlying BT Road with BC 30 mm thick at Rajarajeshwari nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31071,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,340000,"Relaying the Lowlying BT Road with BC 30 mm thick at Rajarajeshwari nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31117,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,810000,"IMPROVEMENT TO FOOTPATH AT STRAHNS ROAD (NORTH SIDE) IN DN-73, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31137,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,147000,WATER SUPPLY ARRANGEMENT TO NNMP SHED NO 070210 AT THIRU VI KA NAGAR IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/31138,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,27800,"REPAIRS AND OTHER OTHER IMPROVEMENT WORKS TO NNMP SHED NO 07043& 07103 AT MADURAI SAMY MADAM ST IN DN 68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/31139,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,37600,REPAIRING WATER SUPPLY ARRANGEMENT TO JAMALYA SLUM BOARD NNMP SHED IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/31140,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,45000,"REPAIRING WATER SUPPLY ARRANGEMENTS TO GEORGE COLONY PARK IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/31154,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,460000,"Relaying the Lowlying BT Road with BC 30 mm Rajarajeshwari nagar 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31155,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,680000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vivek nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31157,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,340000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vivek nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31158,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,295000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vivek nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31159,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,295000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vivek nagar 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31160,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,340000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vivek nagar 4th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31161,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,255000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vetrivel nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31162,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,285000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vetrivel nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31164,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,595000,"Relaying the Lowlying BT Road with BC 30 mm thick at Kamarajar salai( From Gandhi nagar to Vasan street jn) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31166,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,665000,"Relaying the Lowlying BT Road with BC 30 mm thick at Kamarajar salai( From Vasan street jn to Appasamy street) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31167,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,285000,"Relaying the Lowlying BT Road with BC 30 mm thick at Gandhi nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31168,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,210000,"Relaying the Lowlying BT Road with BC 30 mm thick at Gandhi nagar 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31169,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,225000,"Relaying the Lowlying BT Road with BC 30 mm thick at Gandhi nagar 5th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31170,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,640000,"Relaying the Lowlying BT Road with BC 30 mm thick at Velmurugan nagar 4th avenue in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31171,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,880000,"Relaying the Lowlying BT Road with BC 30 mm thick at Perundevi amman nagar main street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31172,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,850000,"Relaying the Lowlying BT Road with BC 30 mm thick at Perundevi amman nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31173,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,370000,"Relaying the Lowlying BT Road with BC 30 mm thick at TNHB Colony East street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31174,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,425000,"Relaying the Lowlying BT Road with BC 30 mm thick at Samtharia colony 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31175,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,595000,"Relaying the Lowlying BT Road with BC 30 mm thick at Kaveri nagar main road ( Sarajini nagar main road to Varalakshmi nagar) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31176,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,590000,"Relaying the Lowlying BT Road with BC 30 mm thick at Kaveri nagar main road ( From Varalakshmi nagar to Poompugar nagar) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31177,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,850000,"Relaying the Lowlying BT Road with BC 30 mm thick at Kaveri nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31178,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,425000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balakumaran nagar 'a' part in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31179,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,510000,"Relaying the Lowlying BT Road with BC 30 mm thick at Meenakshi nagar (North portion) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31180,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,425000,"Relaying the Lowlying BT Road with BC 30 mm thick at Meenakshi nagar ( South portion) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31181,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,320000,"Relaying the Lowlying BT Road with BC 30 mm thick at TNHB Colony east in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31182,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,390000,"Relaying the Lowlying BT Road with BC 30 mm thick at Padma nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31183,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,340000,"Relaying the Lowlying BT Road with BC 30 mm thick at Padma nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31185,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,340000,"Relaying the Lowlying BT Road with BC 30 mm thick at Padma nagar 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31186,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,310000,"Relaying the Lowlying BT Road with BC 30 mm thick at Agastheeswarar nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31187,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,275000,"Relaying the Lowlying BT Road with BC 30 mm thick at Agastheeswarar nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31188,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,290000,"Relaying the Lowlying BT Road with BC 30 mm thick at Agastheeswarar nagar 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31189,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,850000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balakumaran nagar 'B' part main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31190,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,800000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balakumar nagar 'B' part 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31192,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,765000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balakumaran nagar 'B' part 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31194,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,640000,"Relaying the Lowlying BT Road with BC 30 mm thick at Poompugar nagar 9th street (West side) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31195,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,595000,"Relaying the Lowlying BT Road with BC 30 mm thick at Poompugar nagar 9th street ( East side) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31196,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,325000,"Relaying the Lowlying BT Road with BC 30 mm thick at Bhavani nagar in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31200,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,965000,"Relaying the Lowlying BT Road with BC 30 mm thick at Anjugam nagar 1st street and anjugam nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31201,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,640000,"Relaying the Lowlying BT Road with BC 30 mm thick at krija nagar east cross street & Jeyaram nagar 4th main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31202,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,700000,"Relaying the Lowlying BT Road with BC 30 mm thick at Somanathapuram 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31205,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,780000,"Formation of Park and Providing Greenery arrangements & Drip Irrigation at Thiruveethiamman kovil street pond in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/31206,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,366000,"Relaying the Lowlying BT Road with BC 30 mm thick at Samtharia colony 4th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31207,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,325000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vasan street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31209,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,310000,"Relaying the Lowlying BT Road with BC 30 mm thick at Vasantham nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31227,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,610000,"Relaying the existing BT Road with BC 30mm thick at Durga colony extn east portion in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31301,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,130000,"Restoration of Roadcut made by TNEB at Jeganathan salai in Div-66,unit-16,Zone-6 (Wide Chellon no: NF/2015-16/0028850, Date : 26.02.2015, Amount : 14,75,791.00 )",Own Sources,6,2015-16,2017-18 NF/2015-16/31302,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,509000,"CONSTRUCTION OF TOILET ROOM (NORTH SIDE) AT FIRST FLOOR IN CMS AT TANA STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/31305,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,971000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT TANA STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/31306,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,621000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT TANA STREET IN DIV-78, UN-17, Z-06.",Own Sources,6,2015-16,2020-21 NF/2015-16/31307,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,610000,"Restoration of Roadcut made by TNEB at Venkatraman salai ( From Jeganathan salai to Karthikeyan salai) in Div-66,Unit-16,Zone-6. ( Wide Chellon no: NF/2015-16/0028850 ,Date : 26.02.2015, Amount : 14,75,791.00 )",Own Sources,6,2015-16,2016-17 NF/2015-16/31309,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,610000,"Restoration of Roadcut made by TNEB at Venkatraman salai ( From Karthikeyan salai to GKM Colony) in Div-66,Unit-16,Zone-6. ( Wide Chellon no: NF/2015-16/0028850 ,Date : 26.02.2015, Amount : 14,75,791.00 )",Own Sources,6,2015-16,2016-17 NF/2015-16/31430,Playfields,Completed,NF-THIRU-VI-KA NAGAR,72,933000,"CONSTRUCTION OF COMPOUND WALL AFTER DISMANTLED EXISTING DAMAGED COMPOUND WALL IN KASTURIBHAI COLONY A BLOCK PLAY GROUND EAST SIDE IN DN 72,UNIT 17,ZONE 6",Own Sources,6,2015-16,2017-18 NF/2015-16/31435,Playfields,Completed,NF-THIRU-VI-KA NAGAR,72,794000,"CONSTRUCTION OF COMPOUND WALL AFTER DISMANTLED EXISTING DAMAGED COMPOUND WALL IN KASTURIBHAI COLONY A BLOCK PLAY GROUND WEST SIDE IN DN 72,UNIT 17,ZONE 6",Own Sources,6,2015-16,2017-18 NF/2015-16/31525,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,993000,"RAISING THE EXISTING BT SURFACE AT MANNARSAMY STREET IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2015-16,2018-19 NF/2015-16/31568,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,605000,"Relaying the existing BT Road with BC 30 mm thick at Durga colony extn West portion in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31569,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,790000,"Relaying the existing BT Road with BC 30 mm thick at Poompugar nagar 17th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31570,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,425000,"Relaying the existing BT Road with BC 30 mm thick at Poompugar nagar 9th cross street Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31571,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,790000,"Relaying the existing BT Road with BC 30 mm thick at Poompugar nagar 10th cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31572,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,760000,"Relaying the existing BT Road with BC 30 mm thick at Nermai nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31574,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,425000,"Relaying the existing BT Road with BC 30 mm thick at Nermai nagar 1st street ( West side ) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31575,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,485000,"Relaying the existing BT Road with BC 30 mm thick at Nermai nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31576,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,235000,"Relaying the existing BT Road with BC 30 mm thick at Dhanammal nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31577,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,390000,"Relaying the existing BT Road with BC 30 mm thick at Dhanammal nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31578,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,285000,"Relaying the existing BT Road with BC 30 mm thick at Dhanammal nagar 2nd & 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31579,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,380000,"Relaying the existing BT Road with BC 30 mm thick at Dhanammal nagar 4th & 5th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31585,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,886000,"Relaying the existing BT Road with BC 30 mm thick at sarojini nagar 2nd main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31586,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,925000,"Relaying the existing BT Road with BC 30 mm thick at anjugam nagar west main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31592,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,380000,"Relaying the existing BT Road with BC 30 mm thick at Anjugam nagar 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31593,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,274000,"Relaying the existing BT Road with BC 30 mm thick at Anjugam nagar 8th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31595,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,470000,"Relaying the existing BT Road with BC 30 mm thick at Sarojini nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31596,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,305000,"Relaying the existing BT Road with BC 30 mm thick at Sarojini nagar 3rd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31597,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,670000,"Relaying the existing BT Road with BC 30 mm thick at balaji naagr 6th cross street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31598,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,450000,"Relaying the existing BT Road with BC 30 mm thick at MN Nagar 1st street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31599,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,545000,"Relaying the existing BT Road with BC 30 mm thick at MN Nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31600,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,290000,"Relaying the existing BT Road with BC 30 mm thick at MN Nagar 3rd & 4th street Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31601,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,320000,"Relaying the existing BT Road with BC 30 mm thick at MN Nagar 5th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31602,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,390000,"Relaying the existing BT Road with BC 30 mm thick at MN Nagar 6th & 7th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31604,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,560000,"Relaying the Lowlying BT Road with BC 30 mm thick at Anjugam nagar 15th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31605,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,157000,"Relaying the Lowlying BT Road with BC 30 mm thick at Gandhi nagar 2nd street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31606,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,485000,"Relaying the BT Road at MN Nagar main road in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31607,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,700000,"Relaying the BT Road Poompugar nagar 13th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31608,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,885000,"Relaying the BT Road Poompugar nagar 26th street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31609,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,665000,"Raising & Relaying the Lowlying BT Road Sasthiri street & Rajaji street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31610,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,900000,"Relaying the BT Road at Sarojini nagar 1st street & North mada street in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/31717,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,743000,"Forming and laying of BT Road at muthamizh nagar 2nd street and gkm colony 31st str to gandhi avenue extn in Dn-65,u-15,Zn-6",Own Sources,6,2015-16,2019-20 NF/2015-16/31728,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,390000,"PROVIDING ,RETAINING WALL AND SUPPLYING STORM WATER DRAIN DOORS IN VARIOUS STREETS IN DV-72, UNIT-17, ZONE-6",Own Sources,6,2015-16,2018-19 NF/2015-16/31732,Playfields,Completed,NF-THIRU-VI-KA NAGAR,72,548000,"IMPROVEMENTS TO CHILDREN PLAY GROUND AT POWDER MILLS ROAD IN DV-72, UNIT-17,ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/31819,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,881000,"Repairs and improvements to the existing main building in chs at school road kolathur in dn -64, unit-15, zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/31849,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,46800,REPAIRS AND IMPROVEMENTS TO PUBLIC CONVINIENCE AT PALLAVAN SALAI IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/31980,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,950000,"RELAYING OF CEMENT CONCRETE ROAD RMC M20 IN SHEIK MOIDEEN SUBEDHAR STREET IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2015-16,2018-19 NF/2015-16/32017,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,815000,"Repairs and Improvements To Existing Community hall @ New Ferrance Road in Dn-73, Unit-17 , Zone-VI.",Own Sources,6,2015-16,2017-18 NF/2015-16/32065,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,928000,"Forming Of Speed Breaker As Per IRC Standards at Anjugam Nagar, Haridoss Street Samthariya Colony,Vetrivel Nagar , Sarojini Nagar and various streets In Dn -64, Unit -15, Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/32069,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,925000,"Forming Of Speed Breaker As Per IRC Standards at Poombugar Nagar,Kamaraj Nagar,Subramani Nagar, Ganapathy Nagar and various streets in Dn -64, Unit -15, Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/32070,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,927000,"Forming Of Speed Breaker As Per IRC Standards at Thenpalani Nagar, Jayaram Nagar,Venkateswar Nagar ,Thanigai Nagar,Lakshmi Nagar and various streets in Dn -64, Unit -15, Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/32071,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,924000,"Forming Of Speed Breaker As Per IRC Standards at Balaji Nagar,Tirupathi Nagar,Velmurugan Nagar,Valarmathi Nagar and various streets in Dn -64, Unit -15, Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/32072,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,926000,"Forming Of Speed Breaker As Per IRC Standards at Balakumaran Nagar 'A' & 'B' Part ,Srinagar Colony,Ramdoss Nagar,United Colony and various streets in Dn -64, Unit -15, Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/32129,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,280000,"LAYING CEMENT CONCRETE ROAD AT THIRUNAVUKARASU STREET (DOOR NO 61 TO 63) IN DN-69, UNIT-16, ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/32154,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,960000,"REPAIRS AND IMPROVEMENT TO EXISTING C BLOCK SCHOOL BUILDING AND AUDITORIUM IN GIRLS HIGH SCHOOL AT COOKS ROAD IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/32254,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,937000,"Temporary restoration to flood affected S.W.D portion at junctions of srinivasan street,kumaraswamy street and P.H.Road(North) in div-70,unit-16,zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32331,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,581000,"SUPPLY,INSTALLATION AND ONE YEAR MAINTENANCE FOR SMART TOILET (LADIES) AT SUNDARAPURAM PLAY GROUND IN DN - 77, UNIT - 17, ZONE - 6.",Own Sources,6,2015-16,2016-17 NF/2015-16/32343,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,674000,"Providing Electrical,Santiary Arrangements & other Improvements Work To The Erection E-Toilet & SSS Toilet @ North Redhills Road, Poombuhar Nagar 1st Main Road And Anjugam Nagar 4th Street In Dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/32460,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,804000,"STRENGTHENING THE SINKING PORTIONS AT VIVEKANANDHA NAGAR MAIN ROAD LOCATION- 1 & 2 IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/32766,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,259000,"improvement works at Rangasayee School in Div-67, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/32778,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,546000,"Providing Rain water harvesting system using precast RCC Well rings and construction of Silt catch pit connecting with the Well at various streets in Div-70, Unit-16, Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/32878,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,868000,"STRENGTHENING THE SINKING PORTIONS AT VIVEKANANDHA NAGAR MAIN ROAD LOCATION 3 & 4 IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/32892,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,12200,"PROVIDING DIGITAL NAME BOARDS AT AMMA UNAVAGAM, IN VARIOUS LOCATIONS IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/32912,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,454000,"Relaying the BT Road at Siva Sakthi Nagar Extn 4th street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32913,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,366000,"Relaying the BT Road at Siva Sakthi Nagar 2nd Cross Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32915,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,239000,"Relaying the BT Road at Alazhgiri Street, Thenpalani Nagar in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/32917,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,266000,"Relaying the BT Road at R.K.R Nagar 1st Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32918,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,887000,"Relaying the BT Road at Poombughar Nagar 29th Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32919,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,394000,"Relaying the BT Road at Poombughar Nagar 29th Cross Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32920,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,545000,"Relaying the BT Road at Poombughar Nagar 11th Cross Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32921,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,859000,"Relaying the BT Road at Poombughar Nagar 7th Cross Street From Jn Of Kaveri Nagar Main Road To Poombughar Nagar 2nd Main Road (Reach1) in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32934,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,859000,"Relaying the BT Road at Poombughar Nagar 7th Cross Street From Poombughar 2nd Main Road To Poombughar Nagar 17th Street (Reach-2) in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/32935,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,887000,"Relaying the BT Road at Poombughar Nagar 8th Cross Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32936,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,760000,"Relaying the BT Road at Poombughar Nagar 23rd Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32937,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,242000,"Relaying the BT Road at Anjugam Nagar 12th Cross Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32938,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,267000,"Relaying the BT Road at Anjugam Nagar 11th Cross Street in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/32942,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,97000,"Construction Of Inspection Chamber At Various Street in Dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2017-18 NF/2015-16/32949,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,100000,"Construction of Inspection Chamber and Inlet chamber for exisitng storm water drain at Rajan nagar main road, Vijaya nagar ,Sarojini nagar and other streets in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/32957,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,73000,"Dewatering of Pond and Water Stagination of Flood Affteced area by Using JCP And Motor Pump Set at Haridoss Nagar And Sivasakthi Nagar In Dn-64, Unit-15,Zone-06",Own Sources,6,2015-16,2017-18 NF/2015-16/32958,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,972000,"Providing Street Furniture @ TNHB Colony, Ganapathy Rao Nagar, Samithriya Colony, Somanathapuram, Kaveri Nagar And Various Street in dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/32959,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,974000,"Providing Street Furniture @ Srinagar Colony, Rajan Nagar, KS Nagar, Bhavani Nagar And Various Street in Dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/32960,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,976000,"Providing Street Furniture @ Mankali Neethiman Nagar, Agatheeswar Nagar, Ganga Devi Nagar, Varlakshmi Nagar And Various Street in Dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/32961,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,978000,"Providing Street Furniture @ Arjun Nagar, Ashok Avenue Bharat Avenue, Velavan Nagar ,Balakumaran Nagar 'A' part & 'c'part, Bharathi Street, Dhanammal Nagar And Various Street in Dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/32962,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,980000,"Providing Street Furniture @ Sundaram Nagar, Meenachi Nagar, Sriperumdevi Ammal Nagar, Ramdoss Nagar,Vivek Nagar,Girija Nagar,Siva Sakthi Nagar And Various Street in Dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/33058,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,283000,REPAIRS AND OTHER IMPROVEMENTS WORK TO DISPENSARY BUILDING AT JAIBEAM NAGAR IN DIV-68 UNIT-16 ZONE-6,Own Sources,6,2015-16,2016-17 NF/2015-16/33073,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,710000,"Erosion control to the Pond at Haridoss nagar Lake West side ( Mayor fund) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/33074,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,720000,"Erosion control to the Pond at Haridoss nagar Lake East side ( Mayor fund) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/33077,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,830000,"Erosion control to the Pond at Haridoss nagar Lake North & South side ( Mayor fund) in Div-64,Unit-15,Zone-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/33212,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,979000,"CONSTRUCTION OF URINAL ROOM WITH G.I SHEET ROOFING IN CHENNAI GIRLS HIGHER SECONDARY AT MARKET STREET IN DIV-67,UN-16,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/33213,Electrical,Completed,NF-THIRU-VI-KA NAGAR,67,956000,"PROVIDING WATER SUPPLY,DRAINAGE,ELECTRICAL AND FLOORING ARRANGEMENTS TO URINAL ROOM IN CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT MARKET STREET IN DIV-67,UN-16,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/33214,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,972000,"CONSTRUCTION OF R.C.C COMPOUND WALL (115 M) AT THIRUVEETHI AMMAN KOIL STREET IN DIV-64,UN-15,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/33293,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,972000,"PROPOSED CONSTRUCTION OF STORM WATER DRAIN 4-4 AT SIVANANDHA NAGAR (REACH-1) IN DN-65, U-15,ZN-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33320,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,968500,"PROPOSED CONSTRUCTION OF STORM WATER DRAIN 4-4 AT SIVANANDHA NAGAR (REACH-2) IN DN-65, U-15,ZN-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33349,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,347000,Providing Sheet and Gate arrangements at Stephenson road in Dn 73 U 17 Z 6,Own Sources,6,2015-16,2017-18 NF/2015-16/33365,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,37000,"REPAIRING WATER SUPPLY ARRANGEMENTS TO KKR PARK IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33366,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,98000,"REPAIRS AND OTHER IMPROVEMENTS TO URUDHU SCHOOL IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33367,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,740000,"PROPOSED CONSTRUCTION OF CRECH AT TEEDS GARDEN 1ST STREET IN DN-68, UNIT16, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/33368,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,52000,PROVIDING RAIN WATER HARVESTING SYSTEM USING PRECAST RCC WELL RINGS AND CONSTRUCTION OF SLIT CATCH PIT CONNECTING WITH WELL AT JAMALYA SLUM BOARD IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/33392,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,134000,"PAINTING FOOT PATH KERB AT PALLAVAN SALAI , PAPER MILLS ROAD AND SRP KOIL ST IN DN-68, U-16, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/33507,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,373000,"Maintanance of Ragiv Gandhi park (1 YEARS) at P.H.Road in div-70,uint-16,zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/33532,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,34000,"PROVIDING ELECTRICAL ARRENGEMENTS MULTI PURPOSE HALL AT S.S.PURAM A BLOCK 1ST STREET IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/33533,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,116000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT VENGATAMMAL SAMATHI STREET AND PROVIDING FOOTPATH AT AMMA UNAVAGAM IN BRICKLIN ROAD IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/33534,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,140000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT SS PURAM 10TH STREET IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/33590,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,929000,"IMPROVEMENTS TO VARIOUS MAINTENANCE TO BUILDINGS AND ROADS IN DN-69 UNIT-16, ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/33595,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,154000,RAISING AND LOWERING FRC MANHOLE DOORS AND REPLCING DAMAGED MANHOLE DOORS AT VARIOUS STREETS IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/33656,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,998000,"REPAIRS AND IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT DECASTER ROAD IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/33727,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,590000,"Relaying the Lowlying BT Road with BC 30 mm thick at Anjugam Nagar 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33728,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,415000,"Relaying the Lowlying BT Road with BC 30 mm thick at Balakumaran Nagar 1st main road street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33729,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,690000,"Relaying the Lowlying BT Road with BC 30 mm thick at Ragavendra Nagar in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33730,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,315000,"Relaying the Lowlying BT Road with BC 30 mm thick at Varalakshmi Nagar 1st street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33731,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,405000,"Relaying the Lowlying BT Road with BC 30 mm thick at Varalakshmi Nagar 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33732,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,343000,"Relaying the Lowlying BT Road with BC 30 mm thick at Kaveri Nagar 1st street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33733,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,335000,"Relaying the Lowlying BT Road with BC 30 mm thick at Chiti Babu Nagar in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33734,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,720000,"Relaying the Lowlying BT Road with BC 30 mm thick at Velumurugan Nagar 1st Main Road in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33735,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,315000,"Relaying the Lowlying BT Road with BC 30 mm thick at Bharathi street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33736,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,490000,"Relaying the Lowlying BT Road with BC 30 mm thick at Poompughar Nagar West 1st street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33737,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,365000,"Relaying the Lowlying BT Road with BC 30 mm thick at Poompughar Nagar west 2nd Street in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33738,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,310000,"Relaying the Lowlying BT Road with BC 30 mm thick at Dhannammal Nagar Extn in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33739,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,545000,"Relaying the Lowlying BT Road with BC 30 mm thick at Bajanai Koil Street (Reach-1) in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33740,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,545000,"Relaying the Lowlying BT Road with BC 30 mm thick at Bajanai Koil Street (Reach-2) in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33746,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,530000,"Relaying the Lowlying BT Road with BC 30 mm thick at Poompughar Nagar 1st Cross Street(Reach1) in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33747,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,530000,"Relaying the Lowlying BT Road with BC 30 mm thick at Poompughar Nagar 1st Cross Street(Reach2) in Div-64,Unit-15,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/33876,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,189000,"PROVIDING FOOT PATH BLOCK & WHITE PAINTING IN MEDAVAKKAM TANK ROAD IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/34027,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,995000,"PROVIDING WELD MESH PARTITION FOR THE ROOF STRUCTURE TO SLAUGHTER HOUSE IN DIV-72,UNIT-17,ZONE-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/34028,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,998000,"Providing Roof structure for the Slaughter house of chainage 0 to 35 m in Div-72,unit,17,zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34029,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,998000,"Providing Roof structure for the Slaughter house of chainage 35 to 70 m in Div-72,unit,17,zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/34030,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,988000,"Providing Roof structure for the Slaughter house of chainage 70 to 104 m in Div-72,unit,17,zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/34119,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,58000,"Improvements to Playground and painting footpath at Jawahar nagar 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/34120,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,155000,"Improvements to Group pin at Papermills road, Kumaran nagar,Temple road & Periyar nagar in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/34121,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,41000,"Improvements and Repair works to Storm water drain and Fixing FRC Doors at Kumaran nagar, SRP Koil street & Krishnamurthy street Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/34234,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,256000,"Repairs & Improvements to the existing ward member office & E-Seva centre at Anjugam Nagar 4th street in Dn-64,Unit-15,Zone-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34235,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,269000,"Repairs & Improvements to the existing CI Office at Anjugam Nagar 18th street in Dn-64 Unit-15 Zone-6 .",Own Sources,6,2015-16,2016-17 NF/2015-16/3425,Bridges,Completed,NF-THIRU-VI-KA NAGAR,73,990000,IMPROVEMENT TO GHSS IN (A BLOCK AND B.C BLOCK ) AT COOKS ROAD IN DN 73 UNIT 17 ZONE 6 (WARD COUNCILLOR FUND 2015-2016),Own Sources,6,2015-16,2016-17 NF/2015-16/3426,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,995000,IMPROVEMENT TO GHSS IN (A BLOCK ) AT COOKS ROAD IN DN 73 UNIT 17 ZONE 6 (WARD COUNCILLOR FUND 2015-2016),Own Sources,6,2015-16,2016-17 NF/2015-16/34279,Playfields,Completed,NF-THIRU-VI-KA NAGAR,68,75000,SUPPLYING AND FIXING OF FRC MANHOLE DOORS AT VARIOUS STREET IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2018-19 NF/2015-16/34373,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,123000,"Attending repair works for Street name boards at K.C.Garden 2,3,4,5 & 6th street, ,SRP Colony 5, 6 & 7th streets, Prabu street,Dhakshnamoorthy cross street ,Sakthivel nagar 4th c/s street and varies streets in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2017-18 NF/2015-16/34404,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,597000,"RELAYING THE BT ROAD AT SWAMY DESIKHA NANDHA SALAI (FROM CHAINAGE 0 TO 130 MTR.)IN DIV-72, UNIT-17, ZONE-6. (WARD COUNCILOR FUND 16-17)",Own Sources,6,2015-16,2016-17 NF/2015-16/34405,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,532000,"RELAYING THE BT ROAD AT DR AMBEDKAR NAGAR MAIN ROAD (FROM CHAINAGE 110 TO 200 MTR )IN DIV-72, UNIT-17, ZONE-6. (WARD COUNCILOR FUND 16-17)",Own Sources,6,2015-16,2016-17 NF/2015-16/34406,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,545000,"RELAYING THE BT ROAD AT DR. AMBEDKAR NAGAR MAIN ROAD (FROM CHAINAGE 0 TO 110 MTR.) IN DIV-72, UNIT-17, ZONE-6. (WARD COUNCILOR FUND 16-17)",Own Sources,6,2015-16,2016-17 NF/2015-16/34407,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,583000,"RELAYING THE BT ROAD AT SWAMY DESIKHA NANDHA SALAI (FROM CHAINAGE 130 TO 240 MTR.)IN DIV-72, UNIT-17, ZONE-6. (WARD COUNCILOR FUND 16-17)",Own Sources,6,2015-16,2016-17 NF/2015-16/34408,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,994000,"Construction of Amma Unavagam at Karthikeyan salai Inside of Periyar nagar peripheral Hospital Campus in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/34417,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,745000,"Arrangements for Roofing,Water supply and Electrical works for Amma Unavagam at Karthikeyan salai Inside of Periyar nagar peripheral Hospital Campus in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/34418,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,929000,"Construction of SWD for interconnection at Manavalan street to Karthik street and Manavalan street to Ganthimathi street in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/34429,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,590000,"Providing SWD Link for Karthick street(From Karthick street to Kumaran nagar 80' road ) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2018-19 NF/2015-16/34430,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,940000,"Providing SWD Link at Gandhimathi street ( From Manavalan street to Selvam nagar) in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2018-19 NF/2015-16/34431,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,780000,"Providing SWD Link for Nagammal st in Div-66,Unit-16,Zone-6",Own Sources,6,2015-16,2018-19 NF/2015-16/34432,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,817000,"LAYING OF BT ROAD AT V.O.C NAGAR 1ST STREET (FROM DR.AMBEDKAR COLLEGE ROAD TO DOOR NO.20 OF V.O.C.NAGAR 1ST STREET) IN DN.72, UNIT-17, ZONE-06. (WARD COUNCILOR FUND 2016-17).",Own Sources,6,2015-16,2016-17 NF/2015-16/34470,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,930000,"Construction of Storm water drain Inter link at Gandhimathi street (From Selvam nagar to Gandhimathi lane) in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/34509,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,60000,REPAIRS AND IMPROVEMENTS TO URUDHU SCHOOL IN DIV-68 UNIT-16 ZONE-6,Own Sources,6,2015-16,2017-18 NF/2015-16/34615,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,115000,REPAIRS AND IMPROVEMENTS TO PUBLIC CONVINIENCE AT SRP KOIL ST IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2017-18 NF/2015-16/34619,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,283400,REPLACING DAMAGED MANHOLE DOORS AT VARIOUS STREETS IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2017-18 NF/2015-16/34630,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,493921,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT NEW STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34631,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,742857,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT VENGATESAN (N) STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34632,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,663389,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT VENGATESHA BAKTHAN STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34633,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,915615,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT EDWARD PARK STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34634,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,345515,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT CONRON SMITH MAIN ROAD IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34635,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,414618,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT JAI NAGAR LAYOUT SECOND STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34636,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,518272,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT NEW SACHIDANANDAM LANE IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/34637,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,518272,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT HAJI MOHAMMED HAFFIS STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34638,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,518272,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT JAI NAGAR LAYOUT MAIN STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34639,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,518272,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD ATJAI NAGAR LAYOUT FIRST STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34641,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,1359297,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT ANGALAMMAN KOIL STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34643,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,500997,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT SACHIDANANDAM STREET (STRAHANS ROAD TO NEW STREET) IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34645,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,255210,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT BINNY LANE IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2017-18 NF/2015-16/34646,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,255210,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT CONRONSMITH FIRST STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34647,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,255210,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT CONRONSMITH SECOND STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34648,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,255210,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT CONRONSMITH THIRD STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34649,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,255210,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT CONRONSMITH FOURTH STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34650,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,255210,"TEMPORARY RESTORATION OF BT ROAD DUE TO FLOOD AT CONRONSMITH FIFTH STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2015-16,2016-17 NF/2015-16/34677,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,880000,"ATTENDING PATCH WORK (FLOOD) AT GURUSAMY STREET(GEORGE COLONY) IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34719,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,830000,"ATTENDING PATCH WORK (FLOOD) AT LAKSHMI NAGAR MAIN ROAD AND PATHAM STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34720,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,560000,"ATTENDING PATCH WORK (FLOOD) AT TEEDS GARDEN 5TH STREET (PART) AND TEEDS GARDEN 6TH STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34721,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,565000,"ATTENDING PATCH WORK (FLOOD) AT KAMARAJ STREET MAIN ROAD, KAMARAJ 1ST STREET (PART) AND SIVAPATHAM STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34723,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,332452,"ATTENDING PATCH WORK (FLOOD) AT KENNADY SQUARE 1ST NORTH STREET (PART) IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34724,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,715000,"ATTENDING PATCH WORK (FLOOD) AT THILLAI NAYAGAM 3RD STREET AND 6TH STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34725,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,460000,"ATTENDING PATCH WORK (FLOOD) AT THILLADI VALLIAMMAI STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34726,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,660000,"ATTENDING PATCH WORK (FLOOD) AT STATE BANK COLONY (NORTH SIDE) AND JAMALIA LANE IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34727,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,650000,"ATTENDING PATCH WORK (FLOOD) AT APPORAO GARDEN MAIN ROAD, 1ST STREET AND 2ND STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34728,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,775000,"ATTENDING PATCH WORK (FLOOD) AT ELANGO STREET AND CHOLAN STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34731,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,585000,"ATTENDING PATCH WORK (FLOOD) AT STATE BANK COLONY (NORTH SIDE) AND JAMALIA LANE IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34732,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,766000,"ATTENDING PATCH WORK (FLOOD) AT STATE BANK COLONY MAIN ROAD IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34733,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,610000,"ATTENDING PATCH WORK (FLOOD) AT MADURAISAMY MADAM 1ST STREET, STATE BANK COLONY 1ST STREET AND 2ND STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34767,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,1975000,"ATTENDING PATCH WORK (FLOOD) AT CHALLAPPA STREET IN DN- 75, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34779,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,148000,"ATTENDING PATCH WORK (FLOOD) AT TEEDS GARDEN 2ND CROSS STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34780,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,885000,"ATTENDING PATCH WORK (FLOOD) AT THIRU.VI.KA NAGAR 22ND STREET (WEST SIDE) IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34781,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,365000,"ATTENDING PATCH WORK (FLOOD) AT THIRU.VI.KA NAGAR 22ND STREET (EAST SIDE) IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34782,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,357000,"ATTENDING PATCH WORK (FLOOD) AT CHERAN STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34783,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,322000,"ATTENDING PATCH WORK (FLOOD) AT PALLAVAN LANE IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34784,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,213000,"ATTENDING PATCH WORK (FLOOD) AT HEMAVATHI STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34788,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,730000,"ATTENDING PATCH WORK (FLOOD) AT ANGALAMMAN KOIL STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34789,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,220000,"ATTENDING PATCH WORK (FLOOD) AT SAITTANATHAN STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34790,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,530000,"ATTENDING PATCH WORK (FLOOD) AT KUTTI STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34791,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,565000,"ATTENDING PATCH WORK (FLOOD) AT SACHIANANTHA STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34792,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,575000,"ATTENDING PATCH WORK (FLOOD) AT VENKATACHALAM STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34793,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1020000,"ATTENDING PATCH WORK (FLOOD) AT ARUNACHALAM STREET AND MOOKU STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34794,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,600000,"ATTENDING PATCH WORK (FLOOD) AT VALLAM BANGARU STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34819,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,645000,"ATTENDING PATCH WORK (FLOOD) AT MUTHU STREET IN DN-78, UNIT-16, ZONE-6",Own Sources,6,2015-16,2016-17 NF/2015-16/34859,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,310000,"SERVICING OF ELECTRICAL CREMATORIUM AT GKM COLONY BUTMEDU BURIAL GROUND IN DIV-65, U-15, Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/34932,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,1900000,"ATTENDING PATCH WORK (FLOOD) AT RAGAVAN STREET IN DN-69, UNIT-16, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/34940,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,280000,"ATTENDING PATCH WORK (FLOOD) AT SARASWATHI SQUARE IN DN-70, UNIT-16, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/34942,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,930000,"ATTENDING PATCH WORK (FLOOD) AT VASAN STREET, VANKATRAMAN STREET AND SARASWATHY STREEET IN DN-70, UNIT-16, ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/35141,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,315000,"REPAIR AND IMPROVEMENT TO CHENNAI HIGH SCHOOL AT AMMAIYAMMAL STREET IN DN-73, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2020-21 NF/2015-16/3584,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,368000,"PROVIDING STAINLESS STEEL HANDRAIL,WATER FALL,LIGHTING AND GREENARY ARRANGEMENT TO FOUNTAIN AT SYDEHAMS RAOD JUNCTION OF CHOOLAI HIGH ROAD IN DIV-78,UN-17,Z-06",Own Sources,6,2015-16,2017-18 NF/2015-16/3593,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,996000,Laying of Cuddapah flooring inside slaughter house in Dn.72 Unit 14 Zone 6,Own Sources,6,2015-16,2016-17 NF/2015-16/3643,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,921000,"PROPOSED CONSTRUCTION OF SWD WITH PRECAST DRAINS FOR ROAD CROSSINGS AT VIVEKANANDHA NAGAR MAIN ROAD LOCATIONS 1&2,AND THIRUMALAI NAGAR IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2017-18 NF/2015-16/3748,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,788000,"LAYING OF CC ROAD AT THIRUMALAI NAGAR 3RD STR AND 1ST MAIN ROAD IN DN-65,U-15,ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/3917,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,470000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AND NOON MEAL CENTER AT SUBURAYAN 1ST STREET IN DN-74, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/4087,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,20600,"Providing and inspector Chamber at Sundarapuram and Basin Bridge Junction in DN -77, Unit -17, Zone -6.",Own Sources,6,2015-16,2016-17 NF/2015-16/4088,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,33000,"Repair to Celling Plasting at Sundarapuram School in DN -77, Unit -17, Zone -6.",Own Sources,6,2015-16,2016-17 NF/2015-16/4089,Grade Separator,Completed,NF-THIRU-VI-KA NAGAR,77,34000,"Providing Composed Yard at Nallathambi Community Hall in DN -77, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/4090,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,124000,"Providing to Ramp in PC and Metal Sheet Dust Bins at Various Place in DN -77, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/4091,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,89200,"Providing Erecting motor and Repair ton Bore well motor at Various Corporation Building DN -77, Unit -17, Zone -06.",Own Sources,6,2015-16,2016-17 NF/2015-16/4097,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,468000,"PROPOSED TREE PLANTATION FOR 1000TREE AT VARIOUS STREETS IN DN-74. U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/4229,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,610000,"IMPROVEMENTS TO ICDS AT SIVARAJA PURAM & OLD SLAUGHTER HOUSE ROAD AND IMPROVEMENTS TO COUNCILOR OFFICE IN DN-77,UNIT-17,ZONE-06",Own Sources,6,2015-16,2018-19 NF/2015-16/4242,Electrical,Completed,NF-THIRU-VI-KA NAGAR,72,1394100,Provision of Special type 20mtrs high mast with 6nos of 2000watts M.H Fitting at Basin bridge Jn. Basin bridge and Sathya Moorthy road opp. of police booth in dn 72 zone 6,Own Sources,6,2015-16,2016-17 NF/2015-16/4695,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,39000,"Repair work towards Centre Median at Demellows road, Dn 77, Unit 17, Zone 6.",Own Sources,6,2015-16,2016-17 NF/2015-16/4699,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,47600,"Supplying And Laying Wet Mix at Various Streets in DN -77, Unit -17, Zone -6.",Own Sources,6,2015-16,2016-17 NF/2015-16/4702,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,160000,"Improvement to SWD at Stephson Park in DN -73, Unit -17, Zone -4",Own Sources,6,2015-16,2016-17 NF/2015-16/4777,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,515000,"PROPOSED CONSTRUCTION OF STORM WATER DRAIN 4'-4' AT SIVANANDHA NAGAR (REACH-3) IN DN-65,U-15, ZN-6",Own Sources,6,2015-16,2019-20 NF/2015-16/5127,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,325000,"WIDENING OF ROAD AT PAPER MILLS ROAD FROM SANKARAMADAM STREET TO SUNDARAVINAYAGAR KOIL STREET IN DN-69, U-16, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/5731,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,375000,"Restoration of Road cut made by TNEB at Jegannathan salai (from Kandasamy salai to TNEB office) in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/5732,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,530000,"Restoration of Road cut made by CMWSSB at Siva Elango salai in Div-66,Unit-16,Zone-6.",Own Sources,6,2015-16,2018-19 NF/2015-16/5868,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,379000,"Supply of Bituminous Concrete for attending patchwork at various streets in Unit-15 & 16, Zone -6.",Own Sources,6,2015-16,2016-17 NF/2015-16/5882,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,560000,"Restoration of Road cut made by TNEB at Poompugar nagar police booth to Poompugar nagar 25th street in Div-64,Unit-15,Zone-6.",Deposit Works,6,2015-16,2018-19 NF/2015-16/5883,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,510000,"Restoration of Road cut made by TNEB at Poompogar nagar 25th street to kamarajar salai in Div-64,Unit-15,Zone-6.",Deposit Works,6,2015-16,2018-19 NF/2015-16/5884,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,510000,"Restoration of Road cut made by TNEB at Appasamy road to Periyar nagar EB Substation in Div-64,Unit-15,Zone-6.",Deposit Works,6,2015-16,2018-19 NF/2015-16/6107,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,978000,"Rehabilitation of Thiruveethi amman street Pond at Poompugar nagar in Div-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/6110,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,990000,"Rehabilitation of Haridoss Street pond in DN-64, Unit-15, Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/6122,Electrical,Completed,NF-THIRU-VI-KA NAGAR,77,1224900,Supply and erection of 20mtrs high mast with 6nos of 2000watts M.H. Fitting at Sundarapuram play ground in div 77 in zone VI,Own Sources,6,2015-16,2016-17 NF/2015-16/6217,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,991000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT BELLVEDAR VILLAGE IN DN.73 UNIT.17, ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/6426,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,732000,"MAINTENANCE TO TROPICAL DRY EVER GREEN FOREST (HERBAL PARK) AT OTTERI IN DN 74, UNIT-17, ZONE-6.(6 MONTHS)",Own Sources,6,2015-16,2016-17 NF/2015-16/6655,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,297000,"IMPROVEMENTS TO ICDS AT GKM COLONY,26TH STREET IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/6685,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,93000,"Improvement to Exacting Women to PC at Angalamman Koil Street in Div - 76, Unit - 17, Zone - 6",Own Sources,6,2015-16,2016-17 NF/2015-16/6687,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,257000,"Improvements to Existing P.C. at Angalamma koil Street in DN -76, Unit -17, Zone -6",Own Sources,6,2015-16,2016-17 NF/2015-16/6695,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,430000,"ATTENDING PATCH WORK IN VARIOUS STREETS IN DN-75, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/6755,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,998000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREETS (PART - I) UNDER WARD COUNCILLOR FUND 2015-2016 YEAR IN DN-76, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/6761,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,998000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREETS (PART - II) UNDER WARD COUNCILLOR FUND 2015-16 YEAR IN DN - 76, U-17, ZONE - VI",Own Sources,6,2015-16,2016-17 NF/2015-16/6859,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,250000,"PLUMBING WORKS, WATER SUPPLY ARRANGEMENTS & ELECTRICAL WORKS THILLAI NAYAGAM PILLAI PC IN DIV 68 UNIT 16 ZONE 6",Own Sources,6,2015-16,2016-17 NF/2015-16/6860,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,248000,PROVIDING NEW BORE & PLUMBING WORKS ARRANGEMENTS AT S.R.P KOIL STREET (NORTH) PC IN DIV 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/7318,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,470000,"ATTENDING PATCH WORK IN VARIOUS STREETS IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/7327,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,139000,"ADDITIONAL IMPROVEMENTS TO ELECTRICAL ARRENGEMENTS AT AMMA CANTEEN BRICKLIN ROAD IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/7377,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,852000,"SUPPLYING AND PLANTATION FOR MURASOLIMARAN PARK (PHASE -1) AT PERAMBUR DN-70,UNIT-16,ZONE-6",Own Sources,6,2015-16,2017-18 NF/2015-16/7422,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,487000,"Providing Rain water harvesting system using precast RCC Well rings and construction of Silt catch pit connecting with the Well at various streets in Div-70, Unit-16, Zone-06.",Own Sources,6,2015-16,2016-17 NF/2015-16/7480,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,73000,IMPROVEMENTS TO ELECTION DEPT(THIRU.VI.KA. NAGAR) AT ZONAL OFFICE BUILDING IN DIVISION 69 UNIT 16 ZONE 06,Own Sources,6,2015-16,2017-18 NF/2015-16/7505,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,700000,IMMPROVEMENT TO CHS SCHOOL SOMIYA STREET (COUNCILAR FUND) IN DN 67 UNIT15 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/7628,Playfields,Completed,NF-THIRU-VI-KA NAGAR,68,195000,PROVIDING AND FIXING NEW ROOF SHEETS TO ( PLAYERS REST AREA ) RELAYING FOOT PATH IN ENTERANCE AREA IN THIRU VI KA NAGAR PLAY GROUND AT PALLAVAN SALAI IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/7696,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,997000,"SPECIAL IMPROVEMENTS TO H.M.ROOM AND STUDENTS DINING HALL IN CHGSS AT SCHOOL ROAD IN DN-70, UNIT-16, ZONE-06(FOR WARD COUNCILLOR'S FUND)",Own Sources,6,2015-16,2017-18 NF/2015-16/8136,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,496000,"Repairs And Improvements to Storm Water Drain at Narasimman Nagar 4th Cross Street From Otteri Nalla to Narasimman Nagar 4th Street Dn: 72,U: 16, Z: 6",Own Sources,6,2015-16,2016-17 NF/2015-16/8247,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,999000,PROVIDING STREET FURNITURES AT VARIOUS STREETS (WARD COUNCILOR FUND) IN DN-72 UNIT-17 ZONE 6,Own Sources,6,2015-16,2016-17 NF/2015-16/8430,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,6500,WRITING ELECTION BOOTH NUMBERS IN VARIOUS SCHOOLS FOR ELECTION PURPOSE IN DIV 69 UNIT 69 ZONE 06,Own Sources,6,2015-16,2017-18 NF/2015-16/8434,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,260000,"ATTENDING MOTOR REPAIRS, PLUMBING WORKS, SAND FILLING AND PROVIDING NEW BORE IN BUNDER GARDEN IN DN 69 UNIT 16 ZONE 6",Own Sources,6,2015-16,2017-18 NF/2015-16/8537,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,975000,IMPROVEMENTS TO AMMA UNAVAGAM AND PROVIDING WATER SUPPLY ARRANGEMENTS IN DN OFFICE AT PAPER MILLS ROAD IN DN 68 U 16 Z 6,Own Sources,6,2015-16,2016-17 NF/2015-16/8622,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,951000,"Laying Cement Concrete road with M30 Grade concrete at Mosque lane, Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/8986,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,412000,"Laying Cement Concrete Road with RMC M30 Grade Concrete at Jangar Maya Badar lane in Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/8987,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,985000,"Laying RMC M30 Grade Cement Concrete road at Kuzhandhai Street, Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/8988,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,845000,"Laying RMC M30 Grade Cement Concrete road at KP PARK 25th Block in Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/8989,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,835000,"Laying RMC M30 Grade Cement Concrete Road at KP Park 27th Block, Dn 77, Unit 17, Zone 6.",Own Sources,6,2015-16,2016-17 NF/2015-16/8994,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,486000,RAISING OF COMPOUND WALL CHENNAI PRIMARY SCHOOL AT MADURAI SAMY MADAM IN DIV-68 UNIT-16 ZONE-6,Own Sources,6,2015-16,2016-17 NF/2015-16/9076,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,70,769000,"Road Cut Restroration of Made By CMWSSB at Jamaliya Nagar in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/9079,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,70,296000,"Road Cut Restroration of Made By CMWSSB at P.H.Road 2nd Street in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/9080,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,70,247000,"Road Cut Restroration of Made By CMWSSB at P.H.Road Lane in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/9081,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,70,306000,"Road Cut Restoration of Made By CMWSSB at State Bank Colony 1st Street in Dn-70,Unit-16,Zone-6",Own Sources,6,2015-16,2016-17 NF/2015-16/9137,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,986000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SACHIDANANDHAM STREET & DEVARAJAN STREET IN DN-76,UNIT-17,ZONE-6(CHALLAN NO:NF/2014-15/0028863 DT26.02.2015)",Deposit Works,6,2015-16,2018-19 NF/2015-16/9145,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,376000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (CHALLAN NO:NF/2014-15/0028863 DT26.02.2015) AT GOOD PET PALLAM 1 & 2ND STREETS IN DN-76,UNIT-17,ZONE-6",Deposit Works,6,2015-16,2017-18 NF/2015-16/9416,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,537971,"Repair and improvement works in public convenience at Basin Elephant Gate road in Div-77,Unit-17,Zone-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/9475,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,904000,"Improvements to the school building in chennai primary school at new ferrance road in dn-73,unit-17,zone-6",Own Sources,6,2015-16,2017-18 NF/2015-16/9519,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,998000,"IMPROVEMENTS TO CHS ST STRAHANS ROAD UNDER WARD COUNCILOR FUND IN DN-76,UINT-17, ZONE-VI",Own Sources,6,2015-16,2016-17 NF/2015-16/9523,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,986000,"RESTORATION OF ROAD CUT MADE BY TNEB AT MUTHUKUMARAPPA SALAI , LOCO SCHEME 2ND STREET GKM COLONY MAIN ROADIN DN-67,UNIT-15,ZONE-6",Deposit Works,6,2015-16,2016-17 NF/2015-16/9680,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,935000,"WIDENING THE EXISTING PAPER MILLS ROAD NORTH SIDE FROM THILLAI NAYAGAM 2ND STREET TO THILLAI NAYAGAM MAIN ROAD IN DN-68, U-16, Z.6.",Own Sources,6,2015-16,2016-17 NF/2015-16/9681,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,990000,"WIDENING THE EXISTING PAPER MILLS ROAD NORTH SIDE FROM THILLAI NAYAGAM MAIN ROAD TO RAGAVAN STREET IN DN-68, UNIT-16, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/9682,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,990000,"ATTENDING PATCH WORK AT PILKINGTON ROAD,MYLLAPPA STREET, BANGARU STREET, BUNDER GARDEN MAIN ROAD AND VARIOUS STREETS IN DN-69, UNIT-16, ZONE-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/9776,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,800000,"Laying RMC M30 Grade Cement Concrete road at KP park 28th Block in Dn 77, Unit 17, Zone 6.",Own Sources,6,2015-16,2016-17 NF/2015-16/9777,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,799000,"Laying RMC M30 Grade Cement Concrete road at KP PARK 30th Block in Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/9778,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,799000,"Laying RMC M30 Grade cement Concrete road at KP Park 32nd Block in Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/9780,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,977000,"Laying RMC M30 Grade cement Concrete road at KP Park 34th Block in Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/9786,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,197000,"Laying RMC M30 Grade Cement Concrete Road at Canal Street in Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/9788,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,214000,"Laying RMC M30 Grade Cement Concrete road at Chinna thambi lane in Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/9791,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,981000,"Laying RMC M30 Grade Cement Concrete road at Ruthrapa Street, Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/9821,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,468000,"PROPOSED TREE PLANTATION FOR 1000 TREE AT VARIOUS STREETS IN DN-77, U-17, Z-6.",Own Sources,6,2015-16,2016-17 NF/2015-16/9826,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,975000,"Improvement Works towards Nalla thambi Community hall at Bogipalayam, Dn 77, Unit 17, Zone 6",Own Sources,6,2015-16,2016-17 NF/2015-16/9908,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,990000,"ATTENDING PATCH WORK AT KENNEDY SQUARE , K.K.R.AVENUE, MADURASAMY MADAM, PALLAVAN SALAI AND VARIOUS STREETS IN DN-68, U-16, Z-6.",Own Sources,6,2015-16,2016-17 NG/2015-16/11374,Roads,Completed,NG-AMBATTUR,88,178000,"Road Cut Restoration Work At C-Sector 9th street in Div-88, Unit-19, Zone-7.",Grants,7,2015-16,2016-17 NG/2015-16/11376,Roads,Completed,NG-AMBATTUR,88,352000,"Road Cut Restoration Work At C-Sector 10th street in Div-88, Unit-19,Zone-7.",Grants,7,2015-16,2016-17 NG/2015-16/11377,Roads,Completed,NG-AMBATTUR,88,202000,"Road Cut Restoration Work At Park road (W 568) in Div-88, Unit-19, Zone-7.",Grants,7,2015-16,2016-17 NG/2015-16/11378,Roads,Completed,NG-AMBATTUR,88,480000,"Road Cut Restoration Work At B-Sector 1st Street in Div-88, Unit-19, Zone-7.",Grants,7,2015-16,2016-17 NG/2015-16/11493,Buildings,Completed,NG-AMBATTUR,92,2740000,"PROVIDING RAIN WATER HARVESTING SYSTEM USING PRECAST RCC WELL RINGS COVERD WITH RCC COVER SLAB AND CONSTRUCTION OF SILT CATCH PIT CONNECTED TO THE WELL WITH PVC PIPE IN DIV-83,84,90,91,92,93 UNIT-20,ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/11536,Buildings,Completed,NG-AMBATTUR,82,1800000,"CONSTRUCTION OF 16 TH CEREMONY SHED AT GANGAI NAGAR ( KALLIKUPPAM ) IN DN 82, UNIT 18, ZONE 7.",MLACDS,7,2015-16,2016-17 NG/2015-16/11668,Buildings,Completed,NG-AMBATTUR,85,2100000,"CONSTRUCTION OF N.N.M.P SHED AT BADMANABAN STREET, VARADHARAJAPURAM IN DIVISION 85,UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/11779,Buildings,Completed,NG-AMBATTUR,85,2100000,"CONSTRUCTION OF N.N.M.P SHED AT DOBI COLONY KAMARAJAPURAM IN DIVISION 85,UNIT-19,ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12127,Storm Water Drain,Completed,NG-AMBATTUR,79,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (With out frame) at Various streets in Dn-79, Unit-18, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12131,Storm Water Drain,Completed,NG-AMBATTUR,80,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (Without Frame) at Various streets in Dn-80, Unit-18, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12133,Storm Water Drain,Completed,NG-AMBATTUR,81,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (without frame) at Various streets in Dn-81, Unit-18, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12135,Storm Water Drain,Completed,NG-AMBATTUR,82,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (with out Frame) at Various Street in Dn-82, Unit-18, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12136,Storm Water Drain,Completed,NG-AMBATTUR,85,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (with out Frame) at Various Street in Dn-85, Unit-19, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12140,Storm Water Drain,Completed,NG-AMBATTUR,86,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (without Frame) at Various street in Dn-86, Unit-19, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12142,Storm Water Drain,Completed,NG-AMBATTUR,87,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (with out Frame) at Various Street in Dn-87, Unit-19, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12144,Storm Water Drain,Completed,NG-AMBATTUR,88,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating(without Frame) at various street in Dn-88, Unit-19, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12145,Storm Water Drain,Completed,NG-AMBATTUR,89,419000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings and FRP Grating (with out Frame) at various street in Dn-89, Unit-19, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12209,Buildings,Completed,NG-AMBATTUR,85,2100000,"CONSTRUCTION OF N.N.M.P SHED AT KUMARAN STREET, RAMAPURAM IN DIVISION 85,UNIT-19,ZONE-7",Own Sources,7,2015-16,2017-18 NG/2015-16/12210,Buildings,Completed,NG-AMBATTUR,85,2100000,"CONSTRUCTION OF N.N.M.P SHED AT NEHRU STREET, TEACHERS COLONY IN DIVISION 85,UNIT-19,ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/12603,Buildings,Completed,NG-AMBATTUR,87,464000,"Providing Rental Modular Toilet on Contract basis and Maintenance for one year at Amma Unavagam,State High Ways 205,Thirumalai Colony in Dn-87, Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13276,Roads,Completed,NG-AMBATTUR,90,4775000,"Forming and Relaying the BT Roads at Jegathambigai Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/13291,Roads,Completed,NG-AMBATTUR,90,4535000,"Forming and Relaying the BT Roads at Elango Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/13307,Roads,Completed,NG-AMBATTUR,90,4535000,"Forming and Relaying the BT Roads at Sundharar Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/13387,Parks,Completed,NG-AMBATTUR,79,464000,"PLANTATION FOR 1000 TREES AT VARIOUS STREET IN DN-79,UNIT-18, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13390,Parks,Completed,NG-AMBATTUR,80,487000,"PLANTATION FOR 1050 TREES AT VARIOUS STREET IN DN-80,UNIT-18, ZONE-7",Own Sources,7,2015-16,2017-18 NG/2015-16/13392,Parks,Completed,NG-AMBATTUR,81,150000,"PLANTATION FOR 325 TREES AT VARIOUS STREET IN DN-81,UNIT-18, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13395,Parks,Completed,NG-AMBATTUR,82,840000,"PLANTATION FOR 1810 TREES AT VARIOUS STREET IN DN-82,UNIT-18, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13397,Parks,Completed,NG-AMBATTUR,86,836000,"PLANTATION FOR 1800 TREES IN ATHIPET DUMPING YARD, KALAIVANAR NAGAR ROAD, SINDHU NADHI ROAD, KOTHAVAR ST, GOPAL SAMY NAGAR PARK, V G N SANTHI NAGAR, MANNURPET SCHOOLVARIOUS STREET IN DN-86,UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13400,Parks,Completed,NG-AMBATTUR,86,650000,"PLANTATION FOR 1400 TREES IN REDDY ST, SOUTH REDDY ST, CHELLAI AMMAN KOIL TANK & MAIN ROAD, I C F COLONY ROADS, SINDHU NADHI MAIN ROAD VARIOUS STREET IN DN-86,UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13406,Parks,Completed,NG-AMBATTUR,89,464000,"PLANTATION FOR 1000 TREES AT VARIOUS STREET IN DN-89,UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13408,Parks,Completed,NG-AMBATTUR,88,325000,"PLANTATION FOR 700 TREES AT VARIOUS STREET IN DN-88,UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13520,Parks,Completed,NG-AMBATTUR,83,695000,"PLANTATION FOR 1500 TREES AT VARIOUS STREET IN DIV -83, UNIT -20, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13541,Storm Water Drain,Completed,NG-AMBATTUR,90,2361000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings Covered with RCC CoverSlab with silt catch pit and pvc pipe at Various street in Dn-90, Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/13543,Parks,Completed,NG-AMBATTUR,84,465000,"PLANTATION FOR 1000 TREES AT VARIOUS STREET IN DIV-84 UNIT-20, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13556,Storm Water Drain,Completed,NG-AMBATTUR,83,2400000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings Covered with RCC CoverSlab and Silt Catch Pit and PVC Pipe at Various Street in Dn-83 Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13571,Storm Water Drain,Completed,NG-AMBATTUR,84,2400000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings Covered with RCC CoverSlab and Silt Catch Pit and PVC Pipe at Various Street in Dn-84 Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13588,Buildings,Completed,NG-AMBATTUR,92,2340000,"PROVIDING RAIN WATER HARVESTING SYSTEM USING PRECAST RCC WELL RINGS COVERD WITH RCC COVER SLAB AND CONSTRUCTION OF SILT CATCH PIT CONNECTED TO THE WELL WITH PVC PIPE AT VARIOUS STREET IN DIV-92 UNIT-20,ZONE-7",Own Sources,7,2015-16,2017-18 NG/2015-16/13703,Storm Water Drain,Completed,NG-AMBATTUR,93,2360000,"Providing Rain Water Harvesting System Using Pre-Cast RCC well Rings Covered with RCC CoverSlab and Silt Catch Pit and PVC Pipe at Various Street at 50 Locations in Dn-93 Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13777,Parks,Completed,NG-AMBATTUR,87,468000,"Plantation for 1000 trees At Various Street In Division 87, Unit 19, Zone 7.",Own Sources,7,2015-16,2016-17 NG/2015-16/13867,Buildings,Completed,NG-AMBATTUR,92,464000,"Providing Rental Modular Toilet on Contract basis and Maintenance for one year at Pari Road infront of EB Park in Dn-92, Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13870,Buildings,Completed,NG-AMBATTUR,92,464000,"Providing Rental Modular Toilet on Contract basis and Maintenance for one year at Pari Road inside 7H Bus Depot in Dn-92, Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/13947,Parks,Completed,NG-AMBATTUR,91,468000,"Providing Tree planting at Chennai Corporation Parks, Buildings and various streets in Dn-91, Unit-20, Zone-VII",Own Sources,7,2015-16,2016-17 NG/2015-16/13949,Parks,Completed,NG-AMBATTUR,90,468000,"Digging of earth work and supply & Plantation 1000 Nos of tree sapling 8 feet hight & Provide manure red earth & soil in 1:1:1 Proposion and Supply fixing on tree guard of 4 feet hight in div-90, unit-20, Zone-07 (Ambattur).",Own Sources,7,2015-16,2017-18 NG/2015-16/13953,Parks,Completed,NG-AMBATTUR,93,468000,"Digging of earth work and supply & Plantation 1000 Nos of tree sapling 8 feet hight & Provide manure red earth & soil in 1:1:1 Proposion and Supply fixing on tree guard of 4 feet hight in div-93, unit-20, Zone-07 (Ambattur)",Own Sources,7,2015-16,2016-17 NG/2015-16/14205,Parks,Completed,NG-AMBATTUR,85,696000,"PLANTATION FOR 1500 TREES IN TEACHERS COLONY, VARADHARAJAPURAM, RAMAPURAM, KAMARAJAPURAM, MANGALAPURAM, VARIOUS STREET IN DN-85, UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/14471,Buildings,Completed,NG-AMBATTUR,83,1875000,"CONSTRUCTION OF NNMP SHED AT THATHANKUPPAM IN DIV 83, UNIT-20, ZONE-07 (AMBATTUR)",MLACDS,7,2015-16,2016-17 NG/2015-16/14572,Buildings,Completed,NG-AMBATTUR,85,2360000,"PROVIDING RAIN WATER HARVESTING SYSTEM USING PRE-CAST RCC WELL RINGS COVERED WITH RCC COVER SLAB AND SILT CATCH PIT AND PVC PIPE AT VARIOS STREET IN DN-85,UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/15689,Buildings,Completed,NG-AMBATTUR,90,880000,"Providing Rental Modular Toilet (2Set )on Contract basis and Maintenance for one year at Thiruvaliswarar Nagar, Padipudhu Nagar in Dn-90, Unit-20 Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/15927,Buildings,Completed,NG-AMBATTUR,87,1150000,"Repair and improvements to school building (Building blocks) CMS Dr. Moorthy nagar in ward-87,Unit-19,Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/16045,Buildings,Completed,NG-AMBATTUR,87,98000,"Repairs and Improvements to school (Water supply arrangements) CMS.Dr.Moorthy Nagar in ward-87,Unit-19,Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/16047,Buildings,Completed,NG-AMBATTUR,87,173000,"Repairs and improvements to school (Electrical arrangements)CMS.Dr.Moorthy Nagar in ward-87,Unit-19,Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/16049,Buildings,Completed,NG-AMBATTUR,87,1040000,"Repairs and improvements to schools (Pavement and compound wall) CMS,Dr.Moorthy Nagar in ward-87,Unit-19,Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/16272,Roads,Completed,NG-AMBATTUR,86,1090000,"Temporary Restoration at Menambedu Main Road in Division-86, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/16787,Buildings,Completed,NG-AMBATTUR,88,139900,"Improvements Work to CSC E-Seva Center at C-Sector Park in Division-88, Unit-19, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/17119,Roads,Completed,NG-AMBATTUR,90,4370000,"Forming and Relaying the BT Roads at Appar Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17144,Buildings,Completed,NG-AMBATTUR,90,4370000,"Forming and Relaying the BT Roads at Thirunagasambandar Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17147,Buildings,Completed,NG-AMBATTUR,90,4370000,"Forming and Relaying the BT Roads at Avvai Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17148,Buildings,Completed,NG-AMBATTUR,90,4830000,"Forming and Relaying the BT Roads at Manikkavasakar Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17150,Roads,Completed,NG-AMBATTUR,90,3496000,"Forming and Relaying the BT Roads at Vetrivinayagar Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17188,Roads,Completed,NG-AMBATTUR,90,3850000,"Forming and Relaying the BT Roads at Vetrivinayagar 1st Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17189,Roads,Completed,NG-AMBATTUR,90,950000,"Forming and Relaying the BT Roads at Thiruganasambandar Cross Street in Dn-90,Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17337,Buildings,Completed,NG-AMBATTUR,84,880000,"Providing Rental Modular Toilet (2Set )on Contract basis and Maintenance for one year at East Avenue Road in Dn-84, Unit-20 Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/1734,Parks,Completed,NG-AMBATTUR,81,2263000,"PROVIDING GREENARY ARRANGEMENT, CHILDREN PLAY EQUIPMENTS,GYM MATERIALS AND FIXING OF SS HAND RAILS AT SECRETRIATE COLONY PARK IN DIV-81,UNIT-18, ZONE-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/17347,Buildings,Completed,NG-AMBATTUR,91,880000,"Providing Rental Modular Toilet (2Set )on Contract basis and Maintenance for one year at Mogappair Eri Scheme 1st Main Road in Dn-91, Unit-20 Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/17348,Buildings,Completed,NG-AMBATTUR,91,880000,"Providing Rental Modular Toilet (2Set )on Contract basis and Maintenance for one year at Mogappair West Bus Stand Park in Dn-91, Unit-20 Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/17349,Buildings,Completed,NG-AMBATTUR,91,880000,"Providing Rental Modular Toilet (2Set )on Contract basis and Maintenance for one year at Reddipalayam Main Road in Dn-91, Unit-20 Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/17431,Buildings,Completed,NG-AMBATTUR,86,2100000,"CONSTRUCTION OF N.N.M.P SHED AT ALAMARAM STREET, PERIYA COLONY, ATHIPET IN DIVISION 86,UNIT-19,ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/1977,Electrical,Completed,P-Parks and Playfields,84,2999900,Proposed Erection of 50 Nos of 7 Mtr Street lamp post with Single St Bracket with 90 Watts LED fitting & 87 Nos 3 Mtr Street Lamp Post at Park in IInd & IVth Street in TNHB & KR Nagar Park in Div 84 & Park at OSR Land at MTH Road in W 85 Ambattur Zone VII,Own Sources,7,2015-16,2019-20 NG/2015-16/20909,Roads,Completed,NG-AMBATTUR,93,1330000,"Attending BT patch work at various street in Div 93, Unit -20, Zone-VII",Own Sources,7,2015-16,2016-17 NG/2015-16/20966,Roads,Completed,NG-AMBATTUR,84,772389,"ATTENDING FLOOD PATCH WORK IN DIVISION - 83 AND 84 ,UNIT-20, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/21016,Roads,Completed,NG-AMBATTUR,92,480000,"Attending Patch work for flood damage road at Panneer Nagar Main Road,Veeramamunivar Salai, Seethakadi salai and Bharathidasan salai in Dn-92",Own Sources,7,2015-16,2016-17 NG/2015-16/23329,Buildings,Completed,NG-AMBATTUR,91,846000,CONSTRUCTION OF 16TH DAY CEREMONY HALL MOGAPPAIR ERI SCHEME 7TH MAIN ROAD IN DIV 91 UNIT-20 ZONE-7(AMBATTUR),Own Sources,7,2015-16,2016-17 NG/2015-16/24311,Buildings,Completed,NG-AMBATTUR,86,780000,PROVIDING AND FIXING OF ARASU E-SEVA CENTRE SIGNAGE NAME BOARDS 13 NOS AT VARIOUS STREETS IN ZONE-7,Own Sources,7,2015-16,2016-17 NG/2015-16/24516,Roads,Completed,NG-AMBATTUR,84,1510000,"Proposed laying of Cement Concrete Road at Chavadi 2NDCross Street in in Div - 84, Zone - 7",Own Sources,7,2015-16,2017-18 NG/2015-16/24566,Roads,Completed,NG-AMBATTUR,84,610000,"Proposed laying of Cement Concrete Road at vanniar I st cross Street in in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24572,Roads,Completed,NG-AMBATTUR,84,1160000,"Proposed laying of Cement Concrete Road at Bramin Street to Periyar Nagar in in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24575,Roads,Completed,NG-AMBATTUR,84,1160000,"Proposed laying of Cement Concrete Road at Bharathi nagar cross Street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24581,Roads,Completed,NG-AMBATTUR,84,1740000,"Proposed laying of Cement Concrete Road at Chavadi perumal koil alround in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24584,Roads,Completed,NG-AMBATTUR,84,460000,"Proposed laying of Cement Concrete Road at Kakkai Nagar Cross Street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24587,Roads,Completed,NG-AMBATTUR,84,1200000,"Proposed laying of Cement Concrete Road at Reddy Cross Street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24589,Roads,Completed,NG-AMBATTUR,84,610000,"Proposed laying of Cement Concrete Road at Bramin Cross(Pattaravakkam) Street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24593,Roads,Completed,NG-AMBATTUR,84,610000,"Proposed laying of Cement Concrete Road at Bramin Cross(Korattur) Street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24595,Roads,Completed,NG-AMBATTUR,84,1740000,"Proposed laying of Cement Concrete Road at Pattaravakkam Bajanai koil street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24597,Roads,Completed,NG-AMBATTUR,84,870000,"Proposed laying of Cement Concrete Road at Pattaravakkam Bajanai koil Cross street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24598,Roads,Completed,NG-AMBATTUR,84,2030000,"Proposed laying of Cement Concrete Road at Gangai amman Koil 1st and 2nd street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24599,Roads,Completed,NG-AMBATTUR,84,1450000,"Proposed laying of Cement Concrete Road at Sasthiri square street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24604,Roads,Completed,NG-AMBATTUR,83,1130000,"Proposed laying of Cement Concrete Road at Kumaran nagar Extention in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24605,Roads,Completed,NG-AMBATTUR,83,455000,"Proposed laying of Cement Concrete Road at Vivekanandha nagar in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24606,Roads,Completed,NG-AMBATTUR,83,380000,"Proposed laying of Cement Concrete Road at Vanasakthi nagar in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24608,Roads,Completed,NG-AMBATTUR,83,455000,"Proposed laying of Cement Concrete Road at Sri Iyyappa Kumaran nagar in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24610,Roads,Completed,NG-AMBATTUR,83,532000,"Proposed laying of Cement Concrete Road at Ganapathi nagar in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24612,Roads,Completed,NG-AMBATTUR,83,379000,"Proposed laying of Cement Concrete Road at Sri Devi nagar in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24614,Roads,Completed,NG-AMBATTUR,83,2270000,"Proposed laying of Cement Concrete Road at Srinivasapuram 7th and 8th Cross street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24615,Roads,Completed,NG-AMBATTUR,83,810000,"Proposed laying of Cement Concrete Road at VENKATRAMAN NAGAR KRISHNAMASARI STREET in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24616,Roads,Completed,NG-AMBATTUR,83,1450000,"Proposed laying of Cement Concrete Road at NORTH RAILWAY STATION ROAD 1,2 AND 3rd CROSS STREET in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24619,Roads,Completed,NG-AMBATTUR,83,1450000,"Proposed laying of Cement Concrete Road at METTU STREET 1,2,3 AND 4th CROSS STREET in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24620,Roads,Completed,NG-AMBATTUR,83,1450000,"Proposed laying of Cement Concrete Road at THATHANKUPPAM STREET in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24621,Roads,Completed,NG-AMBATTUR,83,1450000,"Proposed laying of Cement Concrete Road at NEW GANDHI STREET in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24641,Roads,Completed,NG-AMBATTUR,83,852000,"Proposed laying of Bituminous Concrete Road at TNHB 61st street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24679,Roads,Completed,NG-AMBATTUR,83,612000,"Proposed laying of Bituminous Concrete Road at TNHB 65TH street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24680,Roads,Completed,NG-AMBATTUR,83,852000,"Proposed laying of Bituminous Concrete Road at TNHB 66TH street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24682,Roads,Completed,NG-AMBATTUR,83,852000,"Proposed laying of Bituminous Concrete Road at TNHB 67TH street in Div - 83, Zone - 7",Own Sources,7,2015-16,2017-18 NG/2015-16/24683,Roads,Completed,NG-AMBATTUR,83,741000,"Proposed laying of Bituminous Concrete Road at TNHB 27TH street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24684,Roads,Completed,NG-AMBATTUR,83,1290000,"Proposed laying of Bituminous Concrete Road at TNHB 26TH street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24685,Roads,Completed,NG-AMBATTUR,83,741000,"Proposed laying of Bituminous Concrete Road at TNHB 29TH street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24686,Roads,Completed,NG-AMBATTUR,83,2910000,"Proposed laying of Bituminous Concrete Road at Station Road in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24689,Storm Water Drain,Completed,NG-AMBATTUR,86,964000,Removal of obstruction weeds and blockages in ambattur telephone exchange canal from L.S 0m to L.S 550m,Own Sources,7,2015-16,2016-17 NG/2015-16/24691,Storm Water Drain,Completed,NG-AMBATTUR,86,995000,Removal of obstruction weeds and blockages in Padikuppam canal from L.S 0m to L.S 840m,Own Sources,7,2015-16,2016-17 NG/2015-16/24744,Roads,Completed,NG-AMBATTUR,83,1360000,"Proposed laying of Bituminous Concrete Road at Perumal Koil 1st And 2nd Street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24751,Roads,Completed,NG-AMBATTUR,83,679000,"Proposed laying of Bituminous Concrete Road at TVS Nagar Extension in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24753,Roads,Completed,NG-AMBATTUR,83,767000,"Proposed laying of Bituminous Concrete Road at Kanni Ammal Street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24757,Roads,Completed,NG-AMBATTUR,83,806000,"Proposed laying of Bituminous Concrete Road at Sivalinga Puram 1st, 2nd,3rd And 4th Cross Street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24765,Roads,Completed,NG-AMBATTUR,83,2888000,"Proposed laying of Bituminous Concrete Road at Andal Koil Street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24770,Roads,Completed,NG-AMBATTUR,83,1925000,"Proposed laying of Bituminous Concrete Road at Collector Nagar in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24774,Roads,Completed,NG-AMBATTUR,83,1909000,"Proposed laying of Bituminous Concrete Road at Bajanai Koil Street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24780,Roads,Completed,NG-AMBATTUR,84,569000,"Proposed laying of Bituminous Concrete Road at TNHB 5th street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24792,Roads,Completed,NG-AMBATTUR,84,773000,"Proposed laying of Bituminous Concrete Road at TNHB 14th street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24796,Roads,Completed,NG-AMBATTUR,84,773000,"Proposed laying of Bituminous Concrete Road at TNHB 18th Extention in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24798,Roads,Completed,NG-AMBATTUR,83,1336000,"Proposed laying of Bituminous Concrete Road at Ambedkar street to Kankanchi street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/24799,Roads,Completed,NG-AMBATTUR,84,2910000,"Proposed laying of Bituminous Concrete Road at East Avenue Cross Street in Div - 84, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/25673,Storm Water Drain,Completed,NG-AMBATTUR,92,600000,"Attending Moonsoon works by Supplying and providing RCC Hume pipes of 450mm Dia, and 600mm Dia, at flood affected area in Division-83,84 AND 92, Unit-20, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/26257,Roads,Completed,NG-AMBATTUR,79,930000,"PRE MONSON WORK TO PROVIDING GSB, WMM, MOTOR(5HP,2HP),TATA ACE, DESILTING, AND BACK HOE LADDER IN DN-79,UNIT-18,ZONE-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/26422,Storm Water Drain,Completed,NG-AMBATTUR,83,868000,"Desilting at Korattur canal from Aavin milk diary road (0 to 240 M Railway tracK) in Div-83,Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/26432,Storm Water Drain,Completed,NG-AMBATTUR,83,990000,"Desilting at Korattur canal from Aavin milk diary road (240 to 330 M Railway tracK) in Div-83,Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/26433,Storm Water Drain,Completed,NG-AMBATTUR,83,940000,"Desilting at Korattur canal from Aavin milk diary road (330 to 420 M Railway tracK) in Div-83,Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/26435,Storm Water Drain,Completed,NG-AMBATTUR,83,902000,"Desilting at Korattur canal from Aavin milk diary road (420 to 599 M Railway tracK) in Div-83,Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/27199,Storm Water Drain,Completed,NG-AMBATTUR,90,980000,"REMOVAL OF OBSTRUCTION , WEEDS AND BLOCKAGES IN PADIKUPPAM CANAL FROM 0 TO 1500",Own Sources,7,2015-16,2016-17 NG/2015-16/27428,Roads,Completed,NG-AMBATTUR,86,900000,"ATTENDING MONSOON WORK SUCH AS SUPPLYING AND PROVIDING MORTOR PUMP, POWER SAW, TELESCOPIC SAW, ROPE, HOSE PIPE, GSB,WMM,PCC,RMC M15, DESILTING ETC AT FLOOD AFFECTED AREA IN DIVISION-86, UNIT -19, ZONE-07.",Own Sources,7,2015-16,2016-17 NG/2015-16/27446,Roads,Completed,NG-AMBATTUR,86,900000,"ATTENDING MONSOON WORK BY PROVIDING BACK HOE LOADER (JCB) AT FLOOD AFFECTED AREA IN DIVISION-86, UNIT -19, ZONE-07.",Own Sources,7,2015-16,2016-17 NG/2015-16/27447,Roads,Completed,NG-AMBATTUR,86,900000,"ATTENDING MONSOON WORK BY PROVIDING MOTOR PUMP , TATA ACE LABOURS AND TIPPER AT FLOOD AFFECTED AREA IN DIVISION-86, UNIT -19, ZONE-07.",Own Sources,7,2015-16,2016-17 NG/2015-16/27617,Roads,Completed,NG-AMBATTUR,80,285000,"PRE MONSOON WORK OF TO PROVIDING, JCB, TATA ACE, TIPPER, AND DESILTING IN DN 80, UNIT-18, ZONE - 7.",Own Sources,7,2015-16,2016-17 NG/2015-16/27824,Roads,Completed,NG-AMBATTUR,89,900000,"Name of work:ATTENDING MONSOON WORK SUCH AS SUPPLYING AND PROVIDING 5HP MOTOR PUMP, POWER SAW, TELESCOPIC SAW, ROPE, HOSE PIPE, JCB,TIPPER,TATA ACE, LABOUR ETC AT FLOOD AFFECTED AREA IN DIVISION-89, UNIT -19, ZONE-07.",Own Sources,7,2015-16,2016-17 NG/2015-16/27858,Storm Water Drain,Completed,NG-AMBATTUR,83,900000,"Attending flood relief work using Pocklin in the Division-83, Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/27871,Roads,Completed,NG-AMBATTUR,86,510000,"Attending Moonsoon works by Supplying and providing RCC Hume pipes of 300mm Dia, 600mm Dia, 750mm Dia,900mm Dia at flood affected area in division-85 and Division-86, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/27881,Roads,Completed,NG-AMBATTUR,86,900000,"Attending Moonsoon work by providing RCC Hume Pipes, Desilting, Back Noe Loader(JCB), Sand Bags at Ram Poornam Nagar & Natesan Nagar Main Road in Division-86, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/27918,Roads,Completed,NG-AMBATTUR,85,1000000,"ATTENDING MONSOON WORK SUCH AS SUPPLYING AND PROVIDING MORTOR PUMP, POWER SAW, TELESCOPIC SAW, ROPE, HOSE PIPE, GSB,WMM,PCC,RMC M15, DESILTING ETC AT FLOOD AFFECTED AREA IN DIVISION-85, UNIT -19, ZONE-07.",Own Sources,7,2015-16,2016-17 NG/2015-16/27931,Roads,Completed,NG-AMBATTUR,85,1000000,"ATTENDING MONSOON WORK BY PROVIDING TATA ACE LABOURS, BACK HOE LOADER (JCB) AND TIPPER AT FLOOD AFFECTED AREA IN DIVISION-85, UNIT -19, ZONE-07",Own Sources,7,2015-16,2017-18 NG/2015-16/27954,Roads,Completed,NG-AMBATTUR,85,730000,"ATTENDING MONSOON WORK BY PROVIDING MOTOR PUMP, SAND BAGS AT FLOOD AFFECTED AREA IN DIVISION-85, UNIT -19, ZONE-07.",Own Sources,7,2015-16,2017-18 NG/2015-16/28089,Roads,Completed,NG-AMBATTUR,81,880000,"PRE MONSON WORK TO PROVIDING GSB, WMM, MOTOR(5HP), SAND BAGS, TATA ACE AND BACK HOE LABOUR IN DN-81,UNIT-18,ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/28504,Roads,Completed,NG-AMBATTUR,86,2480000,"Temporary Restoration to rain damages roads at Mother Therasa St, VOC 1st Cross Street, VOC 2nd Cross Street, Gopalsamy St, Subash Nagar, Tower Line St, Pillayar Kovil Street,Ceon Street,Ambethkar Street,Thirukumaran Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2015-16,2017-18 NG/2015-16/2852,Buildings,Completed,NG-AMBATTUR,81,726000,"Providing Water Supply Arrangements to Public Convenience at Ambattur O.T.Bus Terminus Division -81,Unit-18,Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/31316,Buildings,Completed,NG-AMBATTUR,87,464000,"Providing Rental Moduler on Contract Basis and Maintenance for One Year at Padi Sivan Koil in Div-87, Unit-19, ZOne-7 Ambattur",Own Sources,7,2015-16,2017-18 NG/2015-16/31868,Roads,Completed,NG-AMBATTUR,86,2050000,"Laying of Cement Concrete Road at Mettu 1st street, Kavarai 1st street,Kavarai 2nd street,Kavarai 4th street in Division-86, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31878,Roads,Completed,NG-AMBATTUR,85,2999000,"Laying of Bituminous Concrete Road at Thanthai Periyar street, Houshing board Quartres in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31880,Roads,Completed,NG-AMBATTUR,85,2650000,"Laying of Bituminous Concrete Road at Pillayar koil Cross Street, TIC Backside (Hariharan Street, annai Sathya nagar) in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31881,Roads,Completed,NG-AMBATTUR,85,1773000,"Laying of Bituminous Concrete Road at MKB Nagar Main Road in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31890,Roads,Completed,NG-AMBATTUR,85,2385000,"Laying of Bituminous Concrete Road at Sivanandha nagar 2nd street, Sivanandha nagar1st ,2nd , 3rd cross Street in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31891,Roads,Completed,NG-AMBATTUR,85,2165000,"Laying of Bituminous Concrete Road at Kannadasan Street, Elango Street, Elango 1st, 2nd Cross Street in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31892,Roads,Completed,NG-AMBATTUR,85,2000000,"Laying of Bituminous Concrete Road at Ambethkar Street in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31893,Roads,Completed,NG-AMBATTUR,85,2650000,"Laying of Bituminous Concrete Road at Pillayar kovil Street, Ambethkar Street Extension in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/31941,Roads,Completed,NG-AMBATTUR,86,2960000,"Providing and Laying BT Road at kavarai 5th,6th & 7th cross streets, Mettu 2nd Street in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31942,Roads,Completed,NG-AMBATTUR,86,1690000,"Providing and Laying BT Road at Kavarai 3rd Street, Mettu 3rd Street in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31943,Roads,Completed,NG-AMBATTUR,86,2740000,"Providing and Laying BT Road at kavarai street in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31944,Roads,Completed,NG-AMBATTUR,86,2650000,"Providing and Laying BT Road at Mariamman street in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31945,Roads,Completed,NG-AMBATTUR,86,2550000,"Providing and Laying BT Road at Mettu 4th & 5th streets in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31946,Roads,Completed,NG-AMBATTUR,86,2800000,"Providing and Laying BT Road at Mettu 6th & 7th streets in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31947,Roads,Completed,NG-AMBATTUR,86,2970000,"Providing and Laying BT Road at Mettu 8th & 9th streets in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31948,Roads,Completed,NG-AMBATTUR,86,2800000,"Providing and Laying BT Road at Mettu 10th street & Udayar Palayam Main Road in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31949,Roads,Completed,NG-AMBATTUR,86,1840000,"Providing and Laying BT Road at Gandhi street in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31950,Roads,Completed,NG-AMBATTUR,86,1890000,"Providing and Laying BT Road at Perumal Kovil street in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31951,Roads,Completed,NG-AMBATTUR,86,2140000,"Providing and Laying BT Road at V.O.C street in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31952,Roads,Completed,NG-AMBATTUR,86,1520000,"Providing and Laying BT Road at Chinna Colony in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31953,Roads,Completed,NG-AMBATTUR,86,2960000,"Providing and Laying BT Road at Mettu Main Road in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31954,Roads,Completed,NG-AMBATTUR,86,2580000,"Providing and Laying BT Road at Bajanai Kovil Street Reach 1 in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31955,Roads,Completed,NG-AMBATTUR,86,2580000,"Providing and Laying BT Road at Bajanai Kovil Street Reach 2 in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31956,Roads,Completed,NG-AMBATTUR,86,2750000,"Providing and Laying BT Road at Athipet Main Road Reach 1 in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31957,Roads,Completed,NG-AMBATTUR,86,2750000,"Providing and Laying BT Road at Athipet Main Road Reach 2 in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/31958,Roads,Completed,NG-AMBATTUR,86,2750000,"Providing and Laying BT Road at Athipet Main Road Reach 3 in Division 86, Unit 19, Zone 7",Own Sources,7,2015-16,2016-17 NG/2015-16/32386,Buildings,Completed,NG-AMBATTUR,89,589000,"Providing Footpath with Interlocking Blocks, Rain Water Harvesting and repair works to the West End Colony 16th street Reach 1, Anna Nagar West Extension in Division:89, Unit:19, Zone:7.",Own Sources,7,2015-16,2016-17 NG/2015-16/32741,Roads,Completed,NG-AMBATTUR,89,660000,"Providing Footpath with Interlocking Blocks, Rain Water Harvesting and repair works to 17th street Reach 1 in Division:89, Unit:19, Zone:7.",Own Sources,7,2015-16,2016-17 NG/2015-16/33785,Buildings,Completed,NG-AMBATTUR,88,557000,"CONSTRUCTION OF AMMA KUDINEER AT KALIVANAR NAGAR MAIN ROAD, PADI IN DIVISION 88, UNIT-19, ZONE-7",Own Sources,7,2015-16,2017-18 NG/2015-16/3393,Buildings,Completed,NG-AMBATTUR,80,270000,"IMPROVEMENT FOR SERVICE CENTER (E-SEVA) AT PUDUR MAIN ROAD IN DN-80, UNIT-18, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/34084,Roads,Completed,NG-AMBATTUR,85,1990000,"Laying of Cement Concrete Road at Aathiamman Street, amman kovil street in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/34085,Roads,Completed,NG-AMBATTUR,85,2240000,"Laying of Cement Concrete Road at Kakkanji Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/34086,Roads,Completed,NG-AMBATTUR,85,1360000,"Laying of Cement Concrete Road at Raman street in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/34087,Roads,Completed,NG-AMBATTUR,85,2280000,"Laying of Cement Concrete Road at Sivan kovil street in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/34088,Roads,Completed,NG-AMBATTUR,85,1162000,"Laying of Cement Concrete Road at Kamaraj Street in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/34089,Roads,Completed,NG-AMBATTUR,85,1990000,"Laying of Cement Concrete Road at Kamber Street Reach 1 in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/34090,Roads,Completed,NG-AMBATTUR,85,1140000,"Laying of Cement Concrete Road at Kamber Street Reach 2 in Division-85, Unit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/34241,Roads,Completed,NG-AMBATTUR,83,2800000,"Proposed laying of Bituminous Concrete Road at Mathanankuppam Lakeview Street From ch 800m to 1200m in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/34242,Roads,Completed,NG-AMBATTUR,83,2800000,"Proposed laying of Bituminous Concrete Road at Mathanankuppam Lakeview Street From ch 400m to 800m in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/34243,Roads,Completed,NG-AMBATTUR,83,2800000,"Proposed laying of Bituminous Concrete Road at Mathanankuppam Lakeview Street From ch 0m to 400m in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/34244,Roads,Completed,NG-AMBATTUR,83,2860000,"Proposed laying of Cement Concrete Road at Srinivasapuram 5th & 6th Cross streets in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/34246,Roads,Completed,NG-AMBATTUR,83,2840000,"Proposed laying of Cement Concrete Road at Srinivasapuram 1st & 2nd Cross streets in Div - 83, Zone - 7",Own Sources,7,2015-16,2017-18 NG/2015-16/34248,Roads,Completed,NG-AMBATTUR,83,2680000,"Proposed laying of Cement Concrete Road at PALLA 1st, 2nd, 3rd,4th and 5th cross streets in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/34702,Roads,Completed,NG-AMBATTUR,83,612000,"Proposed laying of Bituminous Concrete Road at TNHB 62th street in Div - 83, Zone - 7",Own Sources,7,2015-16,2016-17 NG/2015-16/3763,Roads,Completed,NG-AMBATTUR,88,352000,"Road Cut Restoration Work At West Gate road in Div-88, Unit-19, Zone-7.",Deposit Works,7,2015-16,2016-17 NG/2015-16/3924,Parks,Completed,NG-AMBATTUR,89,4682000,"Improvement and Providing, Greeneries, Bore well, FRP Bench, Footpath , Play apparatus, Tower Clock at Golden Colony Park in Dn-89,Unit-19, Zone-7.",Own Sources,7,2015-16,2018-19 NG/2015-16/5280,Buildings,Completed,NG-AMBATTUR,93,464000,"Providing Rental Modular Toilet on Contract basis and Maintenance for one year at Golden George Nagar Bridge in Dn-93, Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/6670,Buildings,Completed,NG-AMBATTUR,92,464000,"Providing Rental Modular Toilet on Contract basis and Maintenance for one year at Mangal Eri Park inside at Vellalar street in Dn-92, Unit-20, Zone-7",Own Sources,7,2015-16,2016-17 NG/2015-16/6789,Buildings,Completed,NG-AMBATTUR,86,3000000,"Proposed Construction of Over Head Tank, Sump And Fire Fighting With Water Supply Arrangments For Dumping Yard At Athipattu Division-86, Ubnit-19, Zone-7.",Own Sources,7,2015-16,2016-17 NG/2015-16/7175,Storm Water Drain,Completed,NG-AMBATTUR,88,626000,"REPAIRS WORKS TO EXISTING STORM WATER DRAIN FROM PARK ROAD JUNCTION TO A.P PLOT 13TH STREET ON NORTH MAIN ROAD IN DN-88, UNIT-19, ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/7310,Buildings,Completed,NG-AMBATTUR,90,464000,"Providing Rental Moduler Toilet on Contract Basis and Maintenance for one year at Near Park MMM, 1st Street, Jayalalitha Nagar in Div-90, Unit-20, Zone-7 Ambattur",Own Sources,7,2015-16,2016-17 NG/2015-16/7782,Buildings,Completed,NG-AMBATTUR,79,347000,"PROPOSED COMMAN SERVICE CENTER IN DN-79, UNIT-18,ZONE-7",Own Sources,7,2015-16,2016-17 NG/2015-16/8906,Buildings,Completed,NG-AMBATTUR,85,4739000,"Design manufacture supply burial ground of fixing erection gasifier and alternative fuel LPG fired furnac at vanagaram burial ground in dn-85, unit-19, zone-07.",Own Sources,7,2015-16,2017-18 NG/2015-16/9685,Parks,Completed,NG-AMBATTUR,92,468000,"Providing Tree planting at Chennai Corporation Parks, Buildings and various street in Dn-92, Unit-20, Zone-VII",Own Sources,7,2015-16,2016-17 NH/2015-16/0171,Playfields,Completed,NH-ANNA NAGAR,95,1480000,"IMPROVEMENT TO PLAY GROUNDAT THIRUVALLUVAR KUDIERUPU IN DN-95,U-21,Z-08",MLACDS,8,2015-16,2016-17 NH/2015-16/0840,Parks,Completed,NH-ANNA NAGAR,101,970000,"IMPROVEMENTS TO NEW AVADI ROAD ROAD SIDE PARK IN DN-101,U-22,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/10285,Buildings,Completed,NH-ANNA NAGAR,107,3000000,"CONSTRUCTION OF COMMUNITY HALL AT VENKATACHALAPATHY STREET IN WARD 107, UNIT-23, ZONE-8",MPLADS,8,2015-16,2016-17 NH/2015-16/10293,Buildings,Completed,NH-ANNA NAGAR,104,480000,"PROVIDING AND FIXING RO PLANT FOR DRINKING WATER AT CHENNAI MIDDLE SCHOOL,VELLALA STREET IN DN-104, UNIT-23,ZONE-8(EGMORE CONSTIUENCY MLA FUND)",MLACDS,8,2015-16,2016-17 NH/2015-16/10381,Buildings,Completed,NH-ANNA NAGAR,97,1410000,"Proposed Construction of Public Distribution System Outlet (Ration Shop) at Pachaikkal Veerasamy Tenements in DN - 97, Unit- 21, Zone - VIII under the MLACD Scheme.",MLACDS,8,2015-16,2016-17 NH/2015-16/10383,Roads,Completed,NH-ANNA NAGAR,101,170000,"IMPROVEMENT TO C.C ROAD AT ANNAI SATHYA NAGAR 3RD STREET TO NEW AVADI ROAD JUNCTION ( NEAR RTO OFFICE ) IN DN-101,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/10427,Buildings,Completed,NH-ANNA NAGAR,108,480000,PROVIDING AND FIXING RO PLANT FOR DRINKING WATER AT CHSS AT BAGATH SINGH 2ND STREET IN DN- 108 UNIT - 22 ZONE -8 ( M P FUND ),MPLADS,8,2015-16,2017-18 NH/2015-16/10437,Buildings,Completed,NH-ANNA NAGAR,102,2000000,"Proposed Demolition and Reconstruction of NNMP Shed No.05020 at Gajalakshmi Colony (under MLA fund scheme 2014-15) in Dn-102, Unit-23, Zone-8.",MLACDS,8,2015-16,2016-17 NH/2015-16/10475,Buildings,Completed,NH-ANNA NAGAR,107,986000,"PROVIDING WATER SUPPY,ELECTRICAL AND DRAINAGE ARRANGEMENTS TO COMMUNITY HALL AT SATHYAMOORTHY SALAI IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/10502,Roads,Completed,NH-ANNA NAGAR,101,635000,"PROVIDING BORE ARRANGEMENT AT VARIOUS PARKS IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2018-19 NH/2015-16/10504,Buildings,Completed,NH-ANNA NAGAR,107,987000,"PROVIDING G.I SHEET ROOFING SHED,STAINLESS STEEL PLAY APPARATUS IN FRONT OF DAY CARE CENTER IN CHENNAI HIGH SCHOOL AT MCHNICOLS ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/10813,Roads,Completed,NH-ANNA NAGAR,99,460000,"STAINLESS STEEL ARRANGEMENTS IN E-TOILETS AND LAYING ANTISKID TILES AT 16TH MAIN ROAD, 2ND AVENUE, W BLOCK IN DN-99,U-21,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/10863,Parks,Completed,NH-ANNA NAGAR,94,999500,IMPROVEMENTS TO THE PARK AT BURIAL GROUND AT MTH ROAD IN DN.94.,Own Sources,8,2015-16,2016-17 NH/2015-16/11349,Buildings,Completed,NH-ANNA NAGAR,98,81000,"DEMOLITION OF EXISTING PUBLIC CONVIENENCE AT AMBEDHKAR NAGAR 2ND STREET IN DN-98,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/11356,Buildings,Completed,NH-ANNA NAGAR,98,65000,"DEMOLITION OF EXISTING PUBLIC CONVIENENCE AT PUDHU NAGAR 4TH STREET IN DN-98,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/11416,Parks,Completed,NH-ANNA NAGAR,101,880000,"PROPOSED TREE PLANTATION FOR 1000 TREES AT VARIOUS STREETS IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11475,Buildings,Completed,NH-ANNA NAGAR,102,840000,"Repairs and Improvements to ICDS centre no.500 at TP Chathiram 11th cross street and ICDS Centre No.409 at TP Chathiram 18th cross street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11478,Buildings,Completed,NH-ANNA NAGAR,102,960000,"Providing Bio gas plant and other Improvements to Amma Unavagam at Tamizhar Nagar in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11479,Buildings,Completed,NH-ANNA NAGAR,102,710000,"Repairs and Improvements to Public Convenience at Thiruveethiamman Koil Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11481,Buildings,Completed,NH-ANNA NAGAR,102,720000,"Repairs and Improvements to ICDS centre no.470 at kumaran nagar and ICDS centre No.5053 at New Mandapam Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11482,Buildings,Completed,NH-ANNA NAGAR,102,996000,"Repairs and Improvements to Road side park at New Avadi Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11483,Buildings,Completed,NH-ANNA NAGAR,102,960000,"Repairs and Improvements to footpath at southern side of New Avadi Road (from first avenue road to mandapam road) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11547,Parks,Completed,NH-ANNA NAGAR,97,399000,"PROPOSED TREE PLANTATION FOR 500 TREES IN VARIOUS STREETS IN DN - 97, UNIT - 21, ZONE ? VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/11649,Roads,Completed,NH-ANNA NAGAR,101,998000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 2ND & 7TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11662,Buildings,Completed,NH-ANNA NAGAR,108,447000,"PROVIDING PATH WAY AND IMPROVEMENTS TO COMPOUND WALL TO CHILDRENS PLAY FIELD AT N.G.O. COLONY 2ND STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2015-16,2016-17 NH/2015-16/11663,Footpath,Completed,NH-ANNA NAGAR,108,910000,"REPAIRS AND IMPROVEMENTS TO FOOT PATH AT PASUMPON STREET 'P' AND 'O' BLOCK IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2015-16,2016-17 NH/2015-16/11775,Roads,Completed,NH-ANNA NAGAR,101,960000,"RELAYING AND STRENGHTHENING OF EXISTING ROAD AT ANNAI SATHYA NAGAR 12TH STREET (STARTING FROM ANNA NAGAR 2ND MAIN ROAD TO DOOR NO. 325) IN DN-101,UNIT-22,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11776,Roads,Completed,NH-ANNA NAGAR,101,997000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 4TH & 1ST STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11777,Roads,Completed,NH-ANNA NAGAR,101,997000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 5TH & 3RD STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/11886,Storm Water Drain,Completed,NH-ANNA NAGAR,98,315000,"PROVIDING RAIN WATER HARVESTING WELL AT VARIOUS STREET IN DN-98,U-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11898,Parks,Completed,NH-ANNA NAGAR,94,649000,"PROPOSED TREE PLANTATION IN VARIOUS STREETS IN DN - 94, UNIT - 21, ZONE ? VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/11899,Parks,Completed,NH-ANNA NAGAR,94,318000,PROVIDING RAIN WATER HARVESTING WELL AT VARIOUS STREET IN DN 94 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/11900,Roads,Completed,NH-ANNA NAGAR,94,104000,"CONSTRUCTION OF DECOMPOSED YARD AT RK LINK ROAD IN DN.94,U-21,Z-5.",Own Sources,8,2015-16,2016-17 NH/2015-16/11905,Roads,Completed,NH-ANNA NAGAR,101,997000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 6TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11906,Roads,Completed,NH-ANNA NAGAR,101,970000,"RELAYING AND STRENGTHENING OF EXISTING ROAD AT ANNAI SATHYA NAGAR 12TH STREET (STARTING FROM DOOR NO.325 TO 'O' BLOCK 35TH STREET) IN DN-101,UNIT-22,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/11908,Roads,Completed,NH-ANNA NAGAR,101,999000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 9TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11909,Roads,Completed,NH-ANNA NAGAR,101,998000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 10TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11910,Roads,Completed,NH-ANNA NAGAR,95,369000,"PROVIDING NEW SPEED BREAKS AT VARIOUS STREETS IN DN - 95, UNIT -21, ZONE -8",Own Sources,8,2015-16,2018-19 NH/2015-16/11912,Roads,Completed,NH-ANNA NAGAR,101,998000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 11TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11914,Buildings,Completed,NH-ANNA NAGAR,101,970000,"REPAIR & IMPROVEMENT TO TERRACE FLOORING OF SHOPPING COMPLEX AT CREASENT ROAD IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/11918,Storm Water Drain,Completed,NH-ANNA NAGAR,97,360000,PROVIDING RAIN WATER HARVESTING WELL AT VARIOUS STREET IN DN 97 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/12281,Parks,Completed,NH-ANNA NAGAR,102,918000,"ANNUAL MAINTENANCE OF PARK AT G' BLOCK PARK, ANNA NAGAR EAST IN DN-102, UNIT-23, ZONE-8. ( TWO YEARS)",Own Sources,8,2015-16,2017-18 NH/2015-16/12399,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Additional Improvements to UPH center first floor at Pulla Avenue in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/12400,Buildings,Completed,NH-ANNA NAGAR,102,800000,"Providing Aluminium partition, furniture and electrical works to UPH Centre first floor at Pulla Avenue in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/12505,Roads,Completed,NH-ANNA NAGAR,100,408000,"PROPOSED TREE PLANTATION FOR 1000 TREES IN VARIOUS STREETS IN DN - 100, UNIT - 22, ZONE ? VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/12551,Buildings,Completed,NH-ANNA NAGAR,101,799000,"IMPROVEMENTS AND PROVIDING ELECTRICAL LAMP POST AND COMPOUND WALL IN BOGANVILLA PARK AT ANNA NAGAR IN DN-101,U-22,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/12784,Footpath,Completed,NH-ANNA NAGAR,100,755000,"IMPROVEMENTS TO FOOTPATH @ AC-BLOCK 4th STREET IN DIVISION-100, UNIT-22, ZONE-08.(FLOOD AFFECTED)",Own Sources,8,2015-16,2016-17 NH/2015-16/12799,Buildings,Completed,NH-ANNA NAGAR,94,251000,"CONSTRUCTION OF STORE ROOM AT AMMA UNAVAGAM AT SIVAN KOIL NORTH MADA STREET IN DIV-94,UNIT-21,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/13048,Parks,Completed,NH-ANNA NAGAR,96,399000,"PROPOSED TREE PLANTATION FOR 500 TREES IN VARIOUS STREETS IN DN - 96, UNIT - 21, ZONE ? VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/13198,Buildings,Completed,NH-ANNA NAGAR,107,928000,"PROVIDING WATER SUPPLY,ELECTRICAL AND DRAINAGE ARRANGEMENTS TO NIGHT SHELTER AT DASPURAM IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/13263,Buildings,Completed,NH-ANNA NAGAR,95,990000,"PROVIDING BUS SHELETER AT 18 TH MAIN ROAD VASANTHAM COLONY (ward councillor fund 2015-2016) DN-95, UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/13287,Buildings,Completed,NH-ANNA NAGAR,101,825000,"REPAIR AND IMPROVEMENT TO SHOPPING COMPLEX AT CREASENT ROAD IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/13547,Buildings,Completed,NH-ANNA NAGAR,100,986000,"PROVIDING STREET NAME BOARD @ VARIOUS STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/13628,Buildings,Completed,NH-ANNA NAGAR,106,600000,"CONVERSATION OF NIGHT SHELTER BUILDING EXISTING CPS AT M.H COLONY IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/1365,Roads,Completed,NH-ANNA NAGAR,94,983000,"PROVIDING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT VARIOUS STREETS (WARD COUNCILLOR FUND2015-16) IN DIN-94,U-21,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/13650,Buildings,Completed,NH-ANNA NAGAR,106,127000,"SUPPLYING AND FIXING HAND BORE AT KAKKAN NAGAR IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/13677,Buildings,Completed,NH-ANNA NAGAR,95,980000,"PROVIDING AND FIXING OF STREET NAME BOARD USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT VARIOUS STREETS (WARD COUNCILLOR FUND 2015-16) IN DN - 95, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/13679,Buildings,Completed,NH-ANNA NAGAR,99,970000,"PROVIDING AND FIXING OF STREET NAME BOARD USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT VARIOUS STREETS (WARD COUNCILLOR FUND 205-16) IN DN - 99, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/13716,Buildings,Completed,NH-ANNA NAGAR,98,998000,"CONSTRUCTION OF MULTI PURPOSE HALL BY WARD COUNSILOR FUND AT DR.AMBEDKAR NAGAR 2ND STREET IN DN-98, U-23, Zn.08.",Own Sources,8,2015-16,2016-17 NH/2015-16/13746,Buildings,Completed,NH-ANNA NAGAR,107,981000,"PROPOSED CONSTRUCTION OF NIGHT SHELTER WITH G.I ROOF SHED AT MCHNICOLS ROAD (DASPURAM) IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/13844,Parks,Completed,NH-ANNA NAGAR,107,998000,PROPOSED TREE PLANTATION FOR 1000 TREE AT VARIOUS STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/14157,Roads,Completed,NH-ANNA NAGAR,107,999000,"PROVIDING NEW SPEED BREAKERS AT VARIOUS STREETS IN DN - 107, UNIT - 23, ZONE -8.",Own Sources,8,2015-16,2016-17 NH/2015-16/14352,Roads,Completed,NH-ANNA NAGAR,100,388000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/14378,Parks,Completed,NH-ANNA NAGAR,96,668000,"ADDITIONAL IMPROVEMENTS TO O.S.R LAND PARK NEAR SAYANEE COMPLEX IN KONNUR HIGH ROAD IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2015-16,2016-17 NH/2015-16/14395,Buildings,Completed,NH-ANNA NAGAR,100,1486000,"CONSTRUCTION OF ADDITIONAL CLASS ROOM @ NADAMUNI STREET(MLA FUND 2015-16 ) IN DIVISION-100, UNIT-22, ZONE-08.",MLACDS,8,2015-16,2017-18 NH/2015-16/14406,Roads,Completed,NH-ANNA NAGAR,98,680000,"PLANTING TREES AT VARIOUS STREET IN DN-98,U-23,Z-8.",Own Sources,8,2015-16,2018-19 NH/2015-16/14409,Buildings,Completed,NH-ANNA NAGAR,102,990000,"Improvements to Chennai Middle School Aminjikarai (old building - Ground floor) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/14411,Buildings,Completed,NH-ANNA NAGAR,102,955000,"Improvements to Chennai Middle School Aminjikarai (old building - first floor) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/14413,Buildings,Completed,NH-ANNA NAGAR,102,990000,"Improvements to Chennai Middle School Aminjikarai (old building - second floor) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/14414,Buildings,Completed,NH-ANNA NAGAR,102,935000,"Painting works and terrace flooring work to CMS Aminjikarai in Dn-102, U-23, Z-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/14465,Buildings,Completed,NH-ANNA NAGAR,102,998000,"Improvements by converting the existing room into Library Room at Chennai primary School Manjakolai in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/14589,Storm Water Drain,Completed,NH-ANNA NAGAR,106,949000,"Providing RWH structure using precast well ring size, 1200(outer dia) x 4500mm (height) (300mm x 15no's) x 40mm (thick) using 1:1.5:3 concrete necessary earthwork excavation ,filling with 20mm HBG metal out side peripheral of the well, providing of FRP frame of size 600mm dia & connected to the silt catch pit 450mm x 450mm x 450mm using 160mm dia PVC pipe . including cost. conveyance, cleaning the site and finishing etc., complete at Various streets in Dn-106, Unit-22, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/14611,Parks,Completed,NH-ANNA NAGAR,106,975000,"IMPROVEMENTS TO PLAY GROUND AT METHA NAGAR IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/14612,Roads,Completed,NH-ANNA NAGAR,105,558000,"PROPOSED TREE PLANTATION FOR 1000 TREES AT VARIOUS STREETS IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/14613,Footpath,Completed,NH-ANNA NAGAR,102,900000,"Repairs and Improvements to footpath at New Avadi Road(Northern side) from 1st avenue road to mandapam road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/14641,Storm Water Drain,Completed,NH-ANNA NAGAR,106,949000,"Providing RWH struture using precast well ring size, 1200(outer dia) x 4500mm (height) (300mm x 15 no's) x 40mm (thick) using 1:1.5:3 concrete nessary earthwork excavation, filling with 20mm HBG metal out side peripheral of the well, providing of FRP frame of size 600mm dia and connected to the silt catch pit 450mm x 450mm x 450mm using 160mm dia PVC pipe.including cost,conveyance,clearing the site and finishing etc., complete AT Various streets In Dn-106,Unit-22,Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/14713,Roads,Completed,NH-ANNA NAGAR,101,990000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM 1ST STREET (CHAINAGE FROM 0 TO 125 ) IN DN-101 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/14735,Buildings,Completed,NH-ANNA NAGAR,104,580000,REPAIRS AND IMPROVEMENT WORKS AT CHENNAI MIDDLE SCHOOL IN PULLAPURAM IN DN-104 UNIT-23 ZONE-8,Own Sources,8,2015-16,2017-18 NH/2015-16/14757,Parks,Completed,NH-ANNA NAGAR,106,950000,"Repair and improvements of gym at metha nagar park in Dn-106, Unit-22, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/14810,Storm Water Drain,Completed,NH-ANNA NAGAR,97,880000,"DISMANTLING RCC ROOF, REPAIR AND DESILTING TO STORM WATER DRAIN AT P.E.KOIL WEST MADA STREET FROM VELLALAR STREET TO P.E.KOIL NORTH MADA STREET IN DN-97,U-21, Zone VIII.",Own Sources,8,2015-16,2016-17 NH/2015-16/14822,Electrical,Completed,NH-ANNA NAGAR,107,523000,"PROVIDING SHED WITH G.I SHEET TO ENTRANCE FOR DINING PURPOSE IN AMMA UNAVAGAM AT MANGALAPURAM 16th STREET IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/14853,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Improvements to Chennai Middle School at Tamizhar Nagar in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/14897,Buildings,Completed,NH-ANNA NAGAR,100,986000,"PROVIDING STREET NAME BOARD @ VARIOUS STREET IN DIVISION-100,UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/15078,Roads,Completed,NH-ANNA NAGAR,101,995000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM 3RD CROSS STREET IN DN-101 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/15081,Roads,Completed,NH-ANNA NAGAR,101,994000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM 5TH CROSS STREET IN DN-101 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/15089,Buildings,Completed,NH-ANNA NAGAR,102,998000,"Painting work for Zonal Office 8 Building(outer side) at Pulla Avenue in Dn-102, Unit-23, Zone-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/15106,Roads,Completed,NH-ANNA NAGAR,101,996000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM 1ST CROSS STREET IN DN-101,U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/15108,Roads,Completed,NH-ANNA NAGAR,101,112000,"ATTENDING WETMIX PATCHWORK AT VARIOUS STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/15109,Roads,Completed,NH-ANNA NAGAR,101,998000,"RELAYING OF ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT E-BLOCK 1A IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/15178,Buildings,Completed,NH-ANNA NAGAR,106,498000,"REPAIR AND IMPROVEMENTS WORKS CENTER NO:33603020104 ICDS BUILDING AT METHA NAGAR IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/15222,Buildings,Completed,NH-ANNA NAGAR,102,998000,"Painting work for Ground, first and second floor of Zonal Office 8 Building (inner side) at Pulla Avenue in Dn-102, Unit-23, Zone-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/15235,Parks,Completed,NH-ANNA NAGAR,102,660000,"Providing Tree planting at various streets in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/15244,Storm Water Drain,Completed,NH-ANNA NAGAR,102,995000,"Providing Rainwater harvesting structure at New Avadi Road, L block, G Block, D Block and other various locations in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/15315,Storm Water Drain,Completed,NH-ANNA NAGAR,97,999000,"DISMANTLING RCC ROOF, REPAIR AND DESILTING TO STORM WATER DRAIN ALONG CHETTY STREET FROM DURAISAMY STREET TO MUTHAMMAN KOIL STREET IN DN-97,U-21, Zone VIII.",Own Sources,8,2015-16,2016-17 NH/2015-16/15328,Buildings,Completed,NH-ANNA NAGAR,108,990000,"PROVIDING ADDITIONAL CLASS ROOM TO CHENNAI HIGH SCHOOL 'N' BLOCK' AT BHAGAT SINGH 2ND STREET IN DN.108, UNIT.22, ZONE.8 (ANNA NAGAR MLA FUNDS FOR THE YEAR 2014 - 2015)",MLACDS,8,2015-16,2016-17 NH/2015-16/15429,Buildings,Completed,NH-ANNA NAGAR,107,586900,ANNUAL MAINTANANCE OF HARRINGTON ROAD SUB WAY ENGAGING FOR MOTOR MECHANICAND WATCH MAN FOR ONE YEAR IN DN 107ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/15526,Storm Water Drain,Completed,NH-ANNA NAGAR,102,990000,"Providing Rain water Harvesting structure at Gajapathy Street, Pulla Avenue, Arumugan Street, first main Road east, Gajalakshmi colony and other locations in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/15535,Roads,Completed,NH-ANNA NAGAR,98,940000,"PROVIDING RAIN WATER HARVESTING STRUCTURE (WELL RING TYPE WITH RCC COVER SLAB) AT VARIOUS STREET IN DN-98,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/15543,Buildings,Completed,NH-ANNA NAGAR,106,986000,"REPAIR AND IMPROVEMENTS TO CHAIRMAN ROOM, CONSTRUCTION ROOM OF SI ROOM AT DIVISION OFFICE IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/15546,Buildings,Completed,NH-ANNA NAGAR,108,500000,"PROVIDING ADDITIONAL TOILET BLOCK IN THIRD FLOOR TO CHENNAI HIGH SCHOOL 'N' BLOCK AT BHAGAT SINGH IN DN.108, UNIT.22, ZONEE.8 (ANNA NAGAR MLA FUNDS FOR THE YEAR 2014 - 2015)",MLACDS,8,2015-16,2016-17 NH/2015-16/15632,Parks,Completed,NH-ANNA NAGAR,102,695000,"Improvements to compound wall(east side) at Skating park Pulla Avenue in Dn-102, Unit-23, Zone -08.",Own Sources,8,2015-16,2016-17 NH/2015-16/15636,Buildings,Completed,NH-ANNA NAGAR,97,182000,"REPAIR WORKS IN WARD OFFICE AND CHENNAI PRIMARY SCHOOL AT SABAPATHY STREET IN WARD-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/15638,Buildings,Completed,NH-ANNA NAGAR,97,85000,"MINOR REPAIR WORKS IN AMMA UNAVAGAM AT PERIYAR SALAI IN WARD-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2017-18 NH/2015-16/15639,Storm Water Drain,Completed,NH-ANNA NAGAR,97,155000,"STORM WATER DRAIN MAN HOLE DOOR RAISING AND RECTIFYING OF TOP SLAB OF DAMAGED DOORS AT VARIOUS STREETS IN WARD - 97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/15682,Buildings,Completed,NH-ANNA NAGAR,102,165000,"Providing Concrete Platform for Dust Bins at Various Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/15683,Roads,Completed,NH-ANNA NAGAR,102,650000,"Restoration of Road cut made by TNEB at 18th ,26th and 27th streets in 'L' Block @ Dn-102,Unit-23,Zone-VIII.",Deposit Works,8,2015-16,2016-17 NH/2015-16/15684,Roads,Completed,NH-ANNA NAGAR,102,540000,"Restoration Of Road Cut Made by TNEB at R.V Nagar main rd (Eastern side) @ Dn-102,Unit-23 , Zone-VIII.",Deposit Works,8,2015-16,2016-17 NH/2015-16/15686,Roads,Completed,NH-ANNA NAGAR,102,206000,"Improvements to Centre Median at Pulla Avenue and 1st Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/15687,Buildings,Completed,NH-ANNA NAGAR,102,313000,"Providing security room at Zonal office 8 building at Pulla avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/15692,Roads,Completed,NH-ANNA NAGAR,102,535000,"Restoration Of Road Cut Made by TNEB at R.V Nagar main rd (western side) @ Dn-102,Unit-23 , Zone-VIII.",Deposit Works,8,2015-16,2016-17 NH/2015-16/15719,Road Cut,Completed,NH-ANNA NAGAR,102,245000,"Restoration of Road cut made by TNEB at Nadamuni Street in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2015-16,2016-17 NH/2015-16/15893,Road Cut,Completed,NH-ANNA NAGAR,102,990000,"Restoration of Road cut made by TNEB at First Main Road(east) and East Club Road in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2015-16,2016-17 NH/2015-16/15894,Road Cut,Completed,NH-ANNA NAGAR,102,980000,"Restoration of Road cut made by TNEB at TP chatiram 15th Cross Street, Cemetry Road and 3rd Cross Street in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2015-16,2016-17 NH/2015-16/15924,Footpath,Completed,NH-ANNA NAGAR,99,999000,REPAIRS AND IMPROVEMENTS TO FOOT PATH AT 16TH MAIN ROAD IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/15926,Footpath,Completed,NH-ANNA NAGAR,99,999000,REPAIRS AND IMPROVEMENTS TO FOOTPATH AT VARIOUS STREET IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2015-16,2018-19 NH/2015-16/15933,Road Cut,Completed,NH-ANNA NAGAR,102,560000,"Restoration of Road cut made by TNEB at Gajapathy street and jayammal street in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2015-16,2016-17 NH/2015-16/15934,Road Cut,Completed,NH-ANNA NAGAR,102,210000,"Restoration of Road cut made by CMWSSB at TP Chathiram main road (from junction of TP 18th cross street to 25 cross street) in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2015-16,2016-17 NH/2015-16/16042,Parks,Completed,NH-ANNA NAGAR,95,690000,"Annual Maintenance of Park at I Block 2nd street and 38th street (Two years) in Dn.95,Unit-21,Zone-8. (By Employed Qualified Horticulturist for Two years only)",Own Sources,8,2015-16,2018-19 NH/2015-16/16043,Buildings,Completed,NH-ANNA NAGAR,95,478000,"IMPROVEMENTS TO I BLOCK 2nd STREET PARK AND 38th STEET PARK IN DN.95,UNIT-21,ZONE-8.",Own Sources,8,2015-16,2018-19 NH/2015-16/16044,Footpath,Completed,NH-ANNA NAGAR,95,450000,IMPROVEMENTS TO FLOOD DAMAGED ROAD FOOT PATH AT I BLOCK 2ND STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/16046,Parks,Completed,NH-ANNA NAGAR,95,790000,"PROVIDING SECURITY ARRANGEMENTS TO I BLOCK 2nd STREET PARK AND 38th STREET PARK (TWO YEARS) IN DN.95,UNIT-21,ZONE-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/16088,Buildings,Completed,NH-ANNA NAGAR,104,998000,"IMPROVEMENTS TO ICDS INSIDE CMS PULLAPURAM IN DN 104,UNIT-22,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/16268,Buildings,Completed,NH-ANNA NAGAR,101,1100000,"PROPOSED ADDITIONAL CONSTRUCTION OF GROUND FLOOR CLASS ROOM AT CPS NADUVANGARAI (BREWERY ROAD)IN DN-101,U-22,Z-08(MLA FUND 2015-16)",MLACDS,8,2015-16,2016-17 NH/2015-16/16390,Playfields,Completed,NH-ANNA NAGAR,99,680000,SUPPLYING AND FIXING PLAY APPARATUS @ RBI PARK IN DN 99 U 21 Z 8,Own Sources,8,2015-16,2016-17 NH/2015-16/16399,Buildings,Completed,NH-ANNA NAGAR,102,990000,"Improvements to CGHSS Annexure Building at Manjakollai Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16402,Buildings,Completed,NH-ANNA NAGAR,102,820000,"Improvement to ICDS Centre No.454 at VOC Nagar Main Road and ICDS Centre No.50223 and 5050 at Gujji Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16456,Buildings,Completed,NH-ANNA NAGAR,102,650000,"Improvements to NNMP Shed at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16458,Storm Water Drain,Completed,NH-ANNA NAGAR,102,165000,"Providing FRC Doors at various street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16459,Parks,Completed,NH-ANNA NAGAR,102,940000,"ANNUAL MAINTENANCE OF PARK AT SHENOY NAGAR SCATTING PARK , ANNA NAGAR EAST IN DN-102, UNIT-23, ZONE-8.(ONE YEAR)",Own Sources,8,2015-16,2016-17 NH/2015-16/16463,Playfields,Completed,NH-ANNA NAGAR,102,512000,"Improvements to Play Ground inside TNSCB at five row house slum board in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16524,Buildings,Completed,NH-ANNA NAGAR,101,500000,"CONSTRUCTION OF TOILET BLOCK AT CPS NADUVANGARAI IN DN-101,U-22,Z-08(MLA FUND 2015-16)",MLACDS,8,2015-16,2016-17 NH/2015-16/16714,Parks,Completed,NH-ANNA NAGAR,99,158800,PROVIDING RAIN WATER HARVESTING AT VARIOUS PLACES IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/16716,Storm Water Drain,Completed,NH-ANNA NAGAR,95,995000,PROVIDING RAIN WATER HARVESTING AT VARIOUS PLACES IN DN 95 UNIT 21 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/16912,Roads,Completed,NH-ANNA NAGAR,103,767000,"LAYING THE ROAD WITH CEMENT CONCRETE AT SEMMENPETTAI MAIN ROAD (FROM CHURCH) IN DN-103, UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/16914,Roads,Completed,NH-ANNA NAGAR,108,998000,"LAYING CEMENT CONCRETE ROAD AT QUAIDE MILLATH STREET (CH.0 TO 100 MTR.) IN DN. 108, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16915,Roads,Completed,NH-ANNA NAGAR,103,950000,"LAYING THE ROAD WITH CEMENT CONCRETE AT SEMMENPETTAI 1ST STREET, 2ND STREET AND 3RD STREET AND LANES IN DN-103, UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/16916,Roads,Completed,NH-ANNA NAGAR,103,726000,"LAYING THE ROAD WITH CEMENT CONCRETE AT SEMMENPETTAI MAIN ROAD (FROM KELLYS SIGNAL) AND 2ND STREET IN DN-103, UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/16917,Roads,Completed,NH-ANNA NAGAR,103,990000,"LAYING THE ROAD WITH CEMENT CONCRETE AT T.P.CHATHIRAM 20TH CROSS STREET,26TH CROSS STREET AND 17TH CROSS STREET IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/16918,Roads,Completed,NH-ANNA NAGAR,103,994000,"LAYING THE ROAD WITH CEMENT CONCRETE AT RANI ANNA NAGAR IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/16919,Roads,Completed,NH-ANNA NAGAR,108,999000,"LAYING CEMENT CONCRETE ROAD AT QUAIDE MILLATH STREET (CH.100 TO 200 MTR.) IN DN.108, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16920,Roads,Completed,NH-ANNA NAGAR,108,700000,"LAYING CEMENT CONCRETE ROAD AT AZAD NAGAR MAIN ROAD IN DN.108, UNIT-22, ZONE 08.",Own Sources,8,2015-16,2016-17 NH/2015-16/16923,Roads,Completed,NH-ANNA NAGAR,108,998000,"LAYING CEMENT CONCRETE ROAD AT AZAD NAGAR 3RD STREET N DN.108, UNIT-22, ZONE 08.",Own Sources,8,2015-16,2016-17 NH/2015-16/17045,Parks,Completed,NH-ANNA NAGAR,101,668000,"SECURITY ARRANGEMENTS OF BOUGAINVILLA PARK, C BLOCK PARK, 2ND MAIN ROAD PARK IN DIVISION-101, UINT-22, ZONE-08 (FOR THE PERIOD OF ONE YEAR)",Own Sources,8,2015-16,2016-17 NH/2015-16/17076,Buildings,Completed,NH-ANNA NAGAR,104,987000,ANNUAL MAINTANANCE AND IMPROVEMENT WORKS TO CHENNAI HIGHER SECONDARY SCHOOL AT GAGADEESWARAR KOIL STREET IN DN-104 UNIT-23 ZONE -8 (BLOCK B),Own Sources,8,2015-16,2016-17 NH/2015-16/17078,Buildings,Completed,NH-ANNA NAGAR,97,39000,"REPAIRING THE EXISTING BORE AT CPS, VELLALA STREET IN DN-97,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/17087,Roads,Completed,NH-ANNA NAGAR,101,159000,"IMPROVEMENT TO CENTRE MERIDIAN AT ANNA NAGAR 2ND & 3RD AVENUE IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/17140,Buildings,Completed,NH-ANNA NAGAR,104,455000,PROVIDING AND FIXING GI SHEET SHED AND IMPROVEMENT WORKS TO TPF IN DN-104 UNIT-23 ZONE -8,Own Sources,8,2015-16,2016-17 NH/2015-16/17186,Parks,Completed,NH-ANNA NAGAR,99,999000,REPAIRS TO THE CENTRE MEDIAN AT 4TH AVENUE ROAD FROM 12TH MAIN ROAD TO 100 FEET ROAD IN DN.99.,Own Sources,8,2015-16,2016-17 NH/2015-16/17214,Parks,Completed,NH-ANNA NAGAR,99,527000,"PROPOSED TREE PLANTATION FOR 750 TREES AT VARIOUS STREETS IN DN.99,UNIT-21,ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/17476,Roads,Completed,NH-ANNA NAGAR,106,470000,"ATTENDING PATCHWORK AT VARIOUS STREETS IN DN-106, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/17478,Parks,Completed,NH-ANNA NAGAR,100,735000,"MAINTENANCE FOR SWEEPING LABOUR AND FOUNTAIN CLEANING OF DR.VISWESWARAYA TOWER PARK ( PERIOD FOR SIX MONTHS) IN DN- 100, UNIT- 22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/17479,Parks,Completed,NH-ANNA NAGAR,100,866000,"MAINTENANCE FOR GREENERY AREA OF DR. VISWESWARAYA TOWER PARK (BY EMPLOYING QUALIFIED HORTICULTURIST) FOR A PERIOD OF SIX MONTH IN DN-100, UNIT- 22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/17480,Parks,Completed,NH-ANNA NAGAR,100,989000,"PROVIDING SECURITY GUARDS TO DR. VISWESWARAIAH TOWER PARK (ONE YEAR) IN DN-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/17496,Parks,Completed,NH-ANNA NAGAR,94,690000,"REPAIR AND IMPROVEMENTS OF GYM AND SUPPLYING GYM MATERIAL AT SIDCO NAGAR 1ST MIN ROAD IN DN-94, UNIT-21, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/17533,Parks,Completed,NH-ANNA NAGAR,100,336000,"MAINTENANCE OF DR. VISWESWARAYA TOWER PARK INSIDE ELECTRIC MOTOR AND WATER LINE(LANDSCAPE AREA,TOILET AREA,DRINKING WATER LINE),TOWER CLOCK SERVICES AT ANNA NAGAR IN DN-100, UNIT- 22, ZONE -8.",Own Sources,8,2015-16,2016-17 NH/2015-16/17667,Buildings,Completed,NH-ANNA NAGAR,104,550000,PROVIDING AND PLANTING TREES AT VARIOUS STREETS IN DN-104 UNIT-23 ZONE -8,Own Sources,8,2015-16,2016-17 NH/2015-16/17695,Buildings,Completed,NH-ANNA NAGAR,97,201200,"PROVIDING ELECTRICAL ARRANGEMENTS, WATER FACILITIES, PLUMBING WORKS AND OTHER WORKS IN PUBLIC CONVIENIENCE AT SOLAI 3RD STREET IN DN- 97, UNIT- 21, Z- 8",Own Sources,8,2015-16,2016-17 NH/2015-16/17774,Parks,Completed,NH-ANNA NAGAR,100,818000,"MAINTENANCE FOR GREENERY AREA OF 7th MAIN ROAD PARK FOR A PERIOD OF TWO YEARS IN DIVISION-100, UNIT- 22, ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/17776,Parks,Completed,NH-ANNA NAGAR,100,727000,"MAINTANANCE OF ARUMBAKKAM BURIAL GROUND FOR A PERIOD OF TWO YEARS IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/17878,Roads,Completed,NH-ANNA NAGAR,100,466000,"ATTENDING PATCH WORK @ VARIOUS STREETS IN DN-100, UNIT-22,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/17944,Roads,Completed,NH-ANNA NAGAR,95,730000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT VALALAR KUDIYIRUPU 6TH STREET IN DN-95,U-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/17948,Parks,Completed,NH-ANNA NAGAR,107,990000,IMPROVEMENT TO THE CENTER MEDIAN AT MC NICHOLS ROAD (REACH 2)IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/17950,Playfields,Completed,NH-ANNA NAGAR,107,740000,"IMPROVEMENTS TO DR.AMBEDHKAR PLAY GROUND AT MAYOR SATHYAMOORTHY SALAI IN DN-107, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/17951,Parks,Completed,NH-ANNA NAGAR,107,990000,IMPROVEMENT TO THE CENTER MEDIAN AT MC NICHOLS(REACH 3) IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/18014,Buildings,Completed,NH-ANNA NAGAR,107,986000,"PROVIDING WATER SUPPLY,ELECTRICAL,FLOORING TILES AND DRAINAGE ARRANGEMENTS TO MULTIPURPOSE HALL GROUND FLOOR INSIDE OF CHETPET DHOBIKANA AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/18015,Buildings,Completed,NH-ANNA NAGAR,107,995000,"CONSTRUCTION OF MULTIPURPOSE HALL 1ST FLOOR INSIDE OF CHETPET DHOBIKANA AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/18016,Buildings,Completed,NH-ANNA NAGAR,107,970000,"CONSTRUCTION OF STAIRCASE ROOM,WEATHERING COURSE AND ELECTRICAL ARRANGEMENTS TO MULTIPURPOSE HALL 1ST FLOOR INSIDE OF CHETPET DHOBIKANA AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/18017,Storm Water Drain,Completed,NH-ANNA NAGAR,106,949000,"Providing RWH structure using precast well ring size, 1200(outer dia) x 4500mm (height) (300mm x 15no's) x 40mm (thick) using 1:1.5:3 concrete necessary earthwork excavation ,filling with 20mm HBG metal out side peripheral of the well, providing of FRP frame of size 600mm dia & connected to the silt catch pit 450mm x 450mm x 450mm using 160mm dia PVC pipe . including cost. conveyance, cleaning the site and finishing etc., complete at Various streets in Dn-106, Unit-22, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18018,Buildings,Completed,NH-ANNA NAGAR,107,994000,"CONSTRUCTION OF MULTIPURPOSE HALL GROUND FLOOR INSIDE OF CHETPET DHOBIKANA AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/18054,Roads,Completed,NH-ANNA NAGAR,102,905000,"Improvements to C C road at Masuthi street from ch. 0 to 75 mtr. in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18055,Roads,Completed,NH-ANNA NAGAR,102,825000,"Improvements to C C road at Masuthi Street from ch. 75 to 102.50 mtr. and Masuthi 1st cross Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18189,Road Cut,Completed,NH-ANNA NAGAR,103,791000,"RESTORATION OF ROAD CUT AT LANDONS ROAD AND MURARI AVENUE IN DN-103, UNIT-23, ZONE-8.",Deposit Works,8,2015-16,2016-17 NH/2015-16/18190,Road Cut,Completed,NH-ANNA NAGAR,103,997000,"RESTORATION OF ROAD CUT AT PARASU STREET, SIVASANKAR STREET, APPA GARDEN IN DN-103, UNIT-23, ZONE-8.",Deposit Works,8,2015-16,2016-17 NH/2015-16/18349,Buildings,Completed,NH-ANNA NAGAR,108,615000,PROVIDING ELECTRICAL ARRANGEMENTS AND SHED TO SUBSTATION AT MGR STREET IN DN 108 UNIT 22 ZONE 8,Own Sources,8,2015-16,2017-18 NH/2015-16/1836,Buildings,Completed,NH-ANNA NAGAR,97,980000,"IMPROVEMENT TO CHENNAI PRIMARY SCHOOL AT VELLALA STREET IN DN-97 , U-21 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/1837,Buildings,Completed,NH-ANNA NAGAR,101,910000,"REPAIRS AND IMPROVEMENTS TO OFFICE AT LORRY DEPOT IN DN-101,UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/1838,Buildings,Completed,NH-ANNA NAGAR,101,760000,"REPAIRS AND IMPROVEMENTS TO MECHANICAL SHED AT LORRY DEPOT IN DN-101, UNIT-22, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/18448,Roads,Completed,NH-ANNA NAGAR,102,954000,"Improvements to C C road at Masuthi 2nd Cross Street in Dn.102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18521,Parks,Completed,NH-ANNA NAGAR,100,960000,"IMPROVEMENTS TO TOWER PARK IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/18523,Parks,Completed,NH-ANNA NAGAR,100,700000,"IMPROVEMENTS TO AL BLOCK PARK 1st AND 3rd STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/18554,Parks,Completed,NH-ANNA NAGAR,108,274000,"ANNUAL MAINTENANCE OF PARK AT M.M.D.A.COLONY R BLOCK PARK (TWO YEARS) IN DN 108,UNIT-22,ZONE-08.(BY EMPOLYED QUALIFIED HORTICULTURIST ONLY).",Own Sources,8,2015-16,2018-19 NH/2015-16/18701,Buildings,Completed,NH-ANNA NAGAR,99,295000,"IMPROVEMENT WORKS TO CI OFFICE 2ND FLOOR AT H-BLOCK 15TH STREET,DN-99,UNIT-21,ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/18726,Buildings,Completed,NH-ANNA NAGAR,102,397000,"Improvements to Hospital Building at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18728,Parks,Completed,NH-ANNA NAGAR,107,465000,IMPROVEMENT TO THE CENTER MEDIAN AT CHARI ROAD IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/18729,Buildings,Completed,NH-ANNA NAGAR,102,275000,"Providing Aluminium Partion and electrical work for Divisional Electrical office at Corporation shopping complex at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18730,Parks,Completed,NH-ANNA NAGAR,107,835000,IMPROVEMENT TO THE CENTER MEDIAN AT HARRINGTON ROAD (I.O.B TO VAMBUILAMMA KOIL) IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/18736,Roads,Completed,NH-ANNA NAGAR,100,699000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AB-BLOCK 3rd STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18737,Roads,Completed,NH-ANNA NAGAR,100,900000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AC-BLOCK 1st STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18738,Roads,Completed,NH-ANNA NAGAR,100,870000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AC-BLOCK 3rd STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18739,Roads,Completed,NH-ANNA NAGAR,100,834000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AE-BLOCK 1st STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18740,Roads,Completed,NH-ANNA NAGAR,100,885000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AJ-BLOCK 3rd STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18741,Roads,Completed,NH-ANNA NAGAR,100,998000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AJ-BLOCK 5th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18742,Roads,Completed,NH-ANNA NAGAR,100,441000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AG-BLOCK 1ST STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18775,Buildings,Completed,NH-ANNA NAGAR,101,115000,"IMPROVEMENT TO THE PIPELINE INTER CONNECTION AT VARIOUS STREETS IN DN-101, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18784,Buildings,Completed,NH-ANNA NAGAR,102,399000,"IMPROVEMENTS TO MULTIPURPOSE HALL AT VS PURAM 2ND STREET IN DN 102,UNIT 23,ZONE 8",Own Sources,8,2015-16,2017-18 NH/2015-16/18785,Roads,Completed,NH-ANNA NAGAR,102,985000,"Improvements to Centre Median at First Avenue Road (from junction of 6th avenue road to ch.150m) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18786,Roads,Completed,NH-ANNA NAGAR,102,995000,"Improvements to Traffic island and Centre Median at first avenue road(from jn. of 6th avenue road to new avadi road and chintamani signal to ch 30m) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18787,Parks,Completed,NH-ANNA NAGAR,102,990000,"Providing fencing for greenary area at G Block park(North-east side) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18788,Buildings,Completed,NH-ANNA NAGAR,102,398000,"Providing water supply and electrical arrangements to the multipurpose hall at VS puram 2nd Street in Dn-102, Unit-23, Zone -08.",Own Sources,8,2015-16,2017-18 NH/2015-16/18789,Buildings,Completed,NH-ANNA NAGAR,102,135000,"Supplying of 5 HP motor, tree cut machine to division office 102 in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/18790,Storm Water Drain,Completed,NH-ANNA NAGAR,102,160000,"Providing Inlet chamber at Gajapathy Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18828,Storm Water Drain,Completed,NH-ANNA NAGAR,106,727000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT METAL FACTORY ROAD IN DN-106,U.-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18846,Roads,Completed,NH-ANNA NAGAR,94,989000,"IMPROVEMENTS TO FLOOD AFFECTED ROAD ATTENDING PATCH WORK AT SIDCO NAGAR 3RD MAIN ROAD IN DIV 94,UNIT-21,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/18877,Roads,Completed,NH-ANNA NAGAR,95,600000,"ATTENDING PATCH WORK AT I BLOCK 11TH STREET IN DN-95,U-21,Z-08 (Flood Damaged roads)",Own Sources,8,2015-16,2016-17 NH/2015-16/18884,Roads,Completed,NH-ANNA NAGAR,95,1135000,"ATTENDING PATCH WORK AT 2ND AVENUE IN DN-95,U-21,Z-08 (Flood affected roads)",Own Sources,8,2015-16,2016-17 NH/2015-16/18979,Buildings,Completed,NH-ANNA NAGAR,107,503000,"CONSTRUCTION OF BATHROOM AND OTHER IMPROVEMENTS TO PUBLIC CONVENIENCE INSIDE OF CHETPET DHOBIKANA SOUTH SIDE AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/18980,Buildings,Completed,NH-ANNA NAGAR,107,491000,"CONSTRUCTION OF BATHROOM AND OTHER IMPROVEMENTS TO PUBLIC CONVENIENCE INSIDE OF CHETPET DHOBIKANA EAST SIDE AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/18981,Buildings,Completed,NH-ANNA NAGAR,107,519000,"IMPROVEMENTS TO SIDE DRAIN (EAST) INSIDE OF CHETPET DHOBIKANA AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/18982,Playfields,Completed,NH-ANNA NAGAR,99,399900,"IMPROVEMENTS TO PLAY GROUND AND CI BUILDING AT 'H'BLOCK 15TH ,STREET PARK IN DN-99,UNIT-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/18983,Parks,Completed,NH-ANNA NAGAR,99,990000,"IMPROVEMENTS TO BPC PARK AT 15TH ,MAIN ROAD DN-99,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18984,Parks,Completed,NH-ANNA NAGAR,99,990000,"IMPROVEMENTS TO PLAY GROUND AT AF BLOCK ,1ST STREET DN-99,ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/18987,Storm Water Drain,Completed,NH-ANNA NAGAR,99,990000,"IMPROVEMENTS TO SWD AT SCHOOL ROAD AT EAST MAIN ROAD, DN-99 ,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18988,Storm Water Drain,Completed,NH-ANNA NAGAR,99,990000,"IMPROVEMENTS TO SWD AT 6TH AVENU, FOR ,100 FT ROAD ,5TH AVENU JUNCTION AT DN-99,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/18989,Storm Water Drain,Completed,NH-ANNA NAGAR,99,990000,"IMPROVEMENTS TO SWD AT 2ND AVENU FOR ,13TH MAIN ROAD TO 10TH ,MAIN ROAD DN-99,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/19008,Storm Water Drain,Completed,NH-ANNA NAGAR,103,996000,"REPAIRS TO EXISTING STORM WATER DRAINS AT KELLYS ROAD, BALFOUR ROAD, MILLERS ROAD, BRANSON GARDEN ROAD IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/19010,Storm Water Drain,Completed,NH-ANNA NAGAR,103,995000,"REPAIRS TO EXISTING STORM WATER DRAINS AT RAJARATHINAM STREET, BARNABY ROAD, UMAYAL STREET, BANK STREET, TEMPLE STREET, HALLS ROAD IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/19049,Buildings,Completed,NH-ANNA NAGAR,98,467000,"IMPROVEMENT TO PUBLIC CONVIENIENT AT PUMPING STATION ROAD IN DN-98,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/19053,Buildings,Completed,NH-ANNA NAGAR,107,356000,"ATTENDING LEAKY ROOF AND OTHER IMPROVEMENTS TO COUNCILLOR OFFICE AT RAMANATHAN SALAI IN DIV-107,UN23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19068,Buildings,Completed,NH-ANNA NAGAR,107,985000,"DISMANTLING AND RE-CONSTRUCTION OF STORM WATER DRAIN(DUE TO HEAVY RAIN) DAMAGED PORTION AT MAYOR CHITTY BABU STREET,MAYOR RAMANATHAN SALAI,MCHNICOLS ROAD,SATHYAMOORTHY SALAI,SANTHOS STREET IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19251,Parks,Completed,NH-ANNA NAGAR,100,398000,"PROVIDING SECURITY GUARDS TO AL BLOCK 14th MAIN ROAD PARK (TWO YEARS) IN DN-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/19252,Parks,Completed,NH-ANNA NAGAR,100,398000,"PROVIDING SECURITY GUARDS TO AD BLOCK PARK (TWO YEARS) IN DN-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/19253,Parks,Completed,NH-ANNA NAGAR,100,398000,"PROVIDING SECURITY GUARDS TO AL BLOCK PARK AND PLAY GROUND (TWO YEARS) IN DN-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/19254,Parks,Completed,NH-ANNA NAGAR,100,634000,"Annual Maintenance of Park at AD Block Park in Dn-100,Unit-22,Zone-8.(Employed Qualified Horticulturist only)",Own Sources,8,2015-16,2017-18 NH/2015-16/19255,Parks,Completed,NH-ANNA NAGAR,100,690000,"Maintenance of park at AL Block 14th Main Road park (By employing qualified horticulturist for only) in Dn.100,Unit-22,Zone-8.",Own Sources,8,2015-16,2018-19 NH/2015-16/19256,Parks,Completed,NH-ANNA NAGAR,100,722000,"ANNUAL MAINTENANCE OF PARK AT AL BLOCK 3rd STREET IN DN.100,UNIT 22,ZONE 8.(Employed Qualified Horticulturist only)",Own Sources,8,2015-16,2017-18 NH/2015-16/19272,Parks,Completed,NH-ANNA NAGAR,100,900000,"CONSTRUCTION OF RAIN SHELTER @ TOWER PARK IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/19286,Buildings,Completed,NH-ANNA NAGAR,100,587000,"IMPROVEMENTS AND REPAIRS WORKS OF AD BLOCK PARK IN DIVISION-100, UNIT-22, ZONE-8. (UNDER MAINTENANCE)",Own Sources,8,2015-16,2016-17 NH/2015-16/19290,Parks,Completed,NH-ANNA NAGAR,101,980000,"ANNUAL MAINTENANCE OF BOGANVILLA PARK IN DN-101,U-22,Z-08( qualified horticulturist for period of 2 years)",Own Sources,8,2015-16,2018-19 NH/2015-16/19292,Parks,Completed,NH-ANNA NAGAR,101,510000,"ANNUAL MAINTENANCE OF C-BLOCK PARK & 2ND MAIN ROAD PARK IN DN-101,U-22,Z-08 ( qualified horticulturist for period of 2 years)",Own Sources,8,2015-16,2018-19 NH/2015-16/19360,Roads,Completed,NH-ANNA NAGAR,98,990000,"ATTENDING PATCHWORK BY PAVER FINISHER AT VARIOUS STREETS IN DN-98, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/19361,Roads,Completed,NH-ANNA NAGAR,98,991000,"ATTENDING PATCHWORK BY PAVER FINISHER AT VARIOUS STREETS IN DN-98, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/19384,Buildings,Completed,NH-ANNA NAGAR,103,870000,"Improvements to Walls & Painting Work to the Existing School Building Northern side Building at Thiyagappa Street in Dn-103, Unit-23, Zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/19385,Buildings,Completed,NH-ANNA NAGAR,103,964000,"Improvements to the Existing School Building (Northern Side Building) at Thiyagappa Street in Dn-103, Unit-23, Zone-8",Own Sources,8,2015-16,2017-18 NH/2015-16/19386,Buildings,Completed,NH-ANNA NAGAR,103,970000,"Additional Improvements to the Existing School Building First Floor( North side Building) at Thiyagappa Street in Dn-103, Unit-23, Zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/19390,Electrical,Completed,NH-ANNA NAGAR,103,740000,"Providing Aluminium Door and Electrical Arrangements to the Existing School Building (Northern side) at Thiyagappa Street in Dn-103, Unit-23, Zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/19532,Roads,Completed,NH-ANNA NAGAR,107,530000,"LAYING OF CC ROAD AT APPA RAO STREET ROAD IN DN-107,UNIT-23,ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19534,Parks,Completed,NH-ANNA NAGAR,106,960000,"REPAIR AND IMPROVEMENTS TO PARK AT COLLECTORATE COLONY MAIN ROAD IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/19628,Roads,Completed,NH-ANNA NAGAR,97,1059000,"ATTENDING BT PATCH WORK AT SABAPATHY STREET FROM WARD - 97 OFFICE TO RAJU STREET (FLOOD DAMAGED ROAD) IN DN - 97, UNIT-21, ZONE - 21",Own Sources,8,2015-16,2016-17 NH/2015-16/19629,Roads,Completed,NH-ANNA NAGAR,97,636000,"ATTENDING PATCHWORK WITH WET MIX MACADAM AT VARIOUS STREETS DURING MONSOON SEASON AT VARIOUS STREETS IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/19717,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"DISMALTING TOP SLAB AND RE-CONSTRUCTION OF SWD AT ANNA NAGAR 2ND AVENUE ( FROM CHINTHAMANI SIGNAL TO BUS STOP ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19720,Storm Water Drain,Completed,NH-ANNA NAGAR,101,990000,"DEMOLITION AND RE-CONSTRUCTION OF STORM WATER DRAIN AT ANNA NAGAR 3RD AVENUE ( CHAINAGE FROM 0M TO 50M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19722,Buildings,Completed,NH-ANNA NAGAR,98,270000,"CONSTRUCTION OF COMPOUND WALL AT DIVISION OFFICE IN DN-98,U-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19723,Parks,Completed,NH-ANNA NAGAR,101,850000,"IMPROVEMENT AND FIXING PLAY APPARATUS TO PARK AT O-BLOCK 25TH STREET IN DIV- 101,UNIT-22,ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/19724,Buildings,Completed,NH-ANNA NAGAR,98,180000,"PROVIDING WEATHERING COURSE AT DIVISION OFFICE IN DN-98,U-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19739,Storm Water Drain,Completed,NH-ANNA NAGAR,99,999500,IMPROVEMENTS TO STORM WATER DRAIN AT 6TH AVENUE AT THE JUNCTION OF 13 TH MAIN ROAD IN DN.99 UNIT-21 ZONE-8,Own Sources,8,2015-16,2016-17 NH/2015-16/19770,Storm Water Drain,Completed,NH-ANNA NAGAR,101,985000,"DEMOLITION AND RE-CONSTRUCTION OF STORM WATER DRAIN AT ANNA NAGAR 3RD AVENUE ( CHAINAGE FROM 50M TO100M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19786,Roads,Completed,NH-ANNA NAGAR,98,250000,"PROVIDING M20 GRADE CONCRETE FOR FLOORING IN DN-98,U-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19840,Parks,Completed,NH-ANNA NAGAR,99,409000,"IMPROVEMENTS TO SWD AT H BLOCK 24TH STREET, JUNCTION OF 6TH AVENU AT DN-99,ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19841,Parks,Completed,NH-ANNA NAGAR,99,398000,"ATTENDING PATCH WORKS AND PROVIDING NEW SPEED BREAKS AT VARIOUS STREET IN DN-99, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/19870,Storm Water Drain,Completed,NH-ANNA NAGAR,106,847000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT VELLALA STREET (FROM THE JUNCTION OF PERUMAL KOIL STREET TO S.S.SAHIB STREET) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/19959,Storm Water Drain,Completed,NH-ANNA NAGAR,107,715000,"DESILTING STORM WATER DRAIN AT MANGALAPURAM 5TH STREET,RAJAMMAL STREET,PUMPING STATION ROAD,JOTHIYAMMAL NAGAR IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/19960,Parks,Completed,NH-ANNA NAGAR,107,990000,IMPROVEMENT TO THE CENTER MEDIAN AT MC NICHOLS ROAD (REACH-1) IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2015-16,2016-17 NH/2015-16/19962,Buildings,Completed,NH-ANNA NAGAR,107,800000,CONSTRUCTION 2nd FLOOR AND IMPROVEMENT TO DIVISION OFFICE BUILDING IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/1997,Roads,Completed,NH-ANNA NAGAR,106,999000,"PROVIDING AND LAYING SPEED BREAKERS AT VARIOUS STREET IN DN -106,U-22,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/20014,Buildings,Completed,NH-ANNA NAGAR,108,116000,SUPPLYING AND FIXING MOTOR @ R.BLOCK PARK IN DN 108 UNIT 22 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/20015,Footpath,Completed,NH-ANNA NAGAR,108,129000,REPAIR WORK TO 100FT ROAD FOOTPATH IN DN 108 UNIT 22 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/20236,Roads,Completed,NH-ANNA NAGAR,105,797000,"IMPROVEMENTS TO FLOOD AFFECTED ROAD AT VINAYAGAPURAM 3RD STREET (REACH FROM 120 M TO 230 M) IN DIV- 105,UNIT-22,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/20295,Roads,Completed,NH-ANNA NAGAR,96,117000,"PROVIDING AND SUPPLYING WET MIX MACADAM FOR FLOOD PATCH AT VARIOUS STREETS IN DN-96, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/20304,Roads,Completed,NH-ANNA NAGAR,96,73000,"PROVIDING PLATFORM FOR BINS AT VARIOUS STREETS IN DN-96,UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/20305,Buildings,Completed,NH-ANNA NAGAR,96,53000,"PROVIDING AND FIXING E-SEVA SIGN BOARD IN DN-96,U-21,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/20306,Buildings,Completed,NH-ANNA NAGAR,96,175000,"IMPROVEMENTS TO FOOT PATH AT OFFICER COLONY IN DN-96,U-21,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/20346,Roads,Completed,NH-ANNA NAGAR,106,977000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT METHA NAGAR MAIN ROAD (FROM 220 TO 330M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/20347,Roads,Completed,NH-ANNA NAGAR,106,977000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT METHA NAGAR MAIN ROAD (FROM 110 TO 220M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/20350,Roads,Completed,NH-ANNA NAGAR,106,977000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT METHA NAGAR MAIN ROAD (FROM SHOBAN BABU STATUE TO 110M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/20382,Footpath,Completed,NH-ANNA NAGAR,108,985000,"REPAIRS AND IMPROVMENTS TO SWD & FOOT PATH @ ANNA SAMI STREET,SAMAYABURATHAMAN STREET, AND VINOBAJI STREET IN DN 108 UNIT 22 ZONE 8",Own Sources,8,2015-16,2016-17 NH/2015-16/20383,Storm Water Drain,Completed,NH-ANNA NAGAR,108,980000,CONSTRUCTION OF INLET CHAMBER TO CONNECTING EXISTING STORM WATER DRAIN AND FOOTPATH IN DN 108 UNIT 22 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/20392,Storm Water Drain,Completed,NH-ANNA NAGAR,108,949000,"REPAIRS AND IMPROVEMENTS TO SWD AT VALLALAR STREET AND PADMANABA NAGAR IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2015-16,2016-17 NH/2015-16/20395,Storm Water Drain,Completed,NH-ANNA NAGAR,108,955000,"REPAIRS AND IMPROVEMENTS TO SWD AT VEERAPANDI NAGAR 3RD AND 1ST STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2015-16,2016-17 NH/2015-16/20427,Roads,Completed,NH-ANNA NAGAR,94,864000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT PERUMAL KOIL NORTH MADA IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/20430,Roads,Completed,NH-ANNA NAGAR,101,411000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD BY PAVER FNISHER AT N-BLOCK 19TH & 20TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/20508,Buildings,Completed,NH-ANNA NAGAR,101,400000,"DISMALTING TOP SLAB AND RE-CONSTRUCTION OF SWD AT ANNA NAGAR 2ND AVENUE ( FROM BUS STOP TO VISHNU EYE CARE HOSPITAL ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/20509,Buildings,Completed,NH-ANNA NAGAR,101,400000,"DISMALTING TOP SLAB AND RE-CONSTRUCTION OF SWD AT ANNA NAGAR 2ND AVENUE ( FROM VISHNU EYE CARE HOSPITAL TO SHENOY NAGAR 2ND MAIN ROAD ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/20641,Buildings,Completed,NH-ANNA NAGAR,106,998000,"CONSTRUCTION TAX COLLECTOR ROOM, PROVIDING STAIR CASE AND IMPROVEMENTS WORKS AT DIVISION OFFICE IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/20768,Buildings,Completed,NH-ANNA NAGAR,102,990000,"Repairs and Improvements to the existing Gym Building at New Avadi Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/20770,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Supplying of Gym Apparatus to the existing Gym at New Avadi Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/20792,Buildings,Completed,NH-ANNA NAGAR,107,760000,PROVIDING TAMILNADU ARASU CABLE T V [ TAC ]OFFICE INSIDE DIVISON OFFICE IN DN 107 U 23 Z 08,Own Sources,8,2015-16,2016-17 NH/2015-16/2095,Roads,Completed,NH-ANNA NAGAR,106,706000,"RELAYING OF C.C ROAD AT PETER RAJA STREET IN DN-106, UNIT - 22, ZONE - 8",Own Sources,8,2015-16,2016-17 NH/2015-16/2113,Roads,Completed,NH-ANNA NAGAR,106,990000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DN -106,U-22,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21498,Roads,Completed,NH-ANNA NAGAR,102,465000,"Attending patch work(flood damaged road) at Jayammal Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21500,Roads,Completed,NH-ANNA NAGAR,102,720000,"Attending patch work(flood damaged road) at Chellammal Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21506,Roads,Completed,NH-ANNA NAGAR,102,1140000,"Attending patch work(flood damaged road) at 3rd cross street(east) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21529,Roads,Completed,NH-ANNA NAGAR,102,800000,"Attending patch work (flood damaged road) at Convent Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21640,Roads,Completed,NH-ANNA NAGAR,100,1250000,"ATTENDING PATCH WORK AT 9th MAIN ROAD (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21648,Roads,Completed,NH-ANNA NAGAR,100,802000,"ATTENDING PATCH WORK AT AC-BLOCK 4th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21658,Roads,Completed,NH-ANNA NAGAR,100,942000,"ATTENDING PATCH WORK AT AH BLOCK 5th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21662,Roads,Completed,NH-ANNA NAGAR,100,518000,"ATTENDING PATCH WORK AT U-BLOCK 10th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21668,Roads,Completed,NH-ANNA NAGAR,100,518000,"ATTENDING PATCH WORK AT V-BLOCK 12th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21726,Roads,Completed,NH-ANNA NAGAR,100,776000,"ATTENDING PATCH WORK AT Z-BLOCK 6th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21732,Roads,Completed,NH-ANNA NAGAR,100,366000,"ATTENDING PATCH WORK AT Z-BLOCK 10th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21736,Roads,Completed,NH-ANNA NAGAR,100,379000,"ATTENDING PATCH WORK AT Z-BLOCK 12th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21740,Roads,Completed,NH-ANNA NAGAR,100,515000,"ATTENDING PATCH WORK AT Z-BLOCK 13th STREET (FLOOD AFFECTED) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/2175,Buildings,Completed,NH-ANNA NAGAR,103,550000,"IMPROVEMENTS TO NIGHT SHELTER AT SEMMENPETTAI IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21827,Roads,Completed,NH-ANNA NAGAR,108,194000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT AVVAI NAGAR WEST STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21966,Buildings,Completed,NH-ANNA NAGAR,103,879000,"REPAIRS AND IMPROVEMENTS TO THE STREET LIGHT OFFICE AT KELLYS ROAD IN DN-103,U-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/21986,Roads,Completed,NH-ANNA NAGAR,97,1810000,"ATTENDING BT PATCH WORK AT MUTHAMMAN KOIL STREET (FLOOD DAMAGED ROAD) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/21989,Roads,Completed,NH-ANNA NAGAR,106,379000,"ATTENDING PATCH WORK BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT LAKSHMI AMMAL STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21991,Roads,Completed,NH-ANNA NAGAR,97,1524000,"ATTENDING BT PATCH WORK AT P.E.KOIL MAIN STREET (FLOOD DAMAGED ROAD) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/21992,Roads,Completed,NH-ANNA NAGAR,106,388000,"ATTENDING PATCH WORK BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT OFFICERS COLONY 1ST STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21995,Roads,Completed,NH-ANNA NAGAR,106,610000,"ATTENDING PATCH WORK BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT VELLALA STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21998,Roads,Completed,NH-ANNA NAGAR,106,795000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT VADA AGARAM (PART) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/21999,Roads,Completed,NH-ANNA NAGAR,106,719000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT RAJESWARI STREET (FROM 130M TO 260M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22001,Roads,Completed,NH-ANNA NAGAR,106,977000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT METHA NAGAR MAIN ROAD (FROM 330 TO 440M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22010,Roads,Completed,NH-ANNA NAGAR,94,458000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT NORTH JAGANATHAN NAGAR 4TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22011,Roads,Completed,NH-ANNA NAGAR,94,560000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT PERIYAR NAGAR IN DN-94, U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22015,Roads,Completed,NH-ANNA NAGAR,94,453000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT SIDCO NAGAR 9TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22016,Roads,Completed,NH-ANNA NAGAR,94,453000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT SIDCO NAGAR 8TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22019,Roads,Completed,NH-ANNA NAGAR,106,719000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT RAJESWARI STREET (FROM 260M TO 390M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22024,Roads,Completed,NH-ANNA NAGAR,94,416000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT NORTH JAGANATHAN NAGAR 7TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22028,Roads,Completed,NH-ANNA NAGAR,94,379000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT BABA NAGAR 13TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22030,Roads,Completed,NH-ANNA NAGAR,94,458000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT BABA NAGAR 11TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22031,Roads,Completed,NH-ANNA NAGAR,94,458000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT BABA NAGAR 10TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22032,Roads,Completed,NH-ANNA NAGAR,94,458000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT BABA NAGAR 9TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22034,Roads,Completed,NH-ANNA NAGAR,94,458000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT BABA NAGAR 7TH STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22040,Roads,Completed,NH-ANNA NAGAR,106,525000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT MURALIDHARAN STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22047,Roads,Completed,NH-ANNA NAGAR,94,910000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT BARATHI NAGAR MAIN STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22048,Roads,Completed,NH-ANNA NAGAR,94,425000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT CHETY THOPPU IIN DN-94, U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22049,Roads,Completed,NH-ANNA NAGAR,94,910000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT RAMAKRISHNA NAGAR IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22058,Roads,Completed,NH-ANNA NAGAR,94,855000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT MOUNASAMY ST IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22060,Roads,Completed,NH-ANNA NAGAR,94,471000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT RAMAMANDIRAM STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22062,Roads,Completed,NH-ANNA NAGAR,94,564000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT VELLALA STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22063,Roads,Completed,NH-ANNA NAGAR,94,587000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT SIVAN KOIL KULAKARI SALAI STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22081,Roads,Completed,NH-ANNA NAGAR,106,567000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT AMMAI AMMAL LANE IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22091,Roads,Completed,NH-ANNA NAGAR,106,719000,"STRENGTHENING AND RELAYING THE ROAD BY PAVER FINISHER (FLOOD DAMAGED ROAD) AT RAJESWARI STREET (FROM JUNCTION OF METHA NAGAR MAIN ROAD TO 130M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22119,Roads,Completed,NH-ANNA NAGAR,97,909000,"ATTENDING BT PATCH WORK AT DURAISAMY STREET (FLOOD DAMAGED ROAD) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/22128,Roads,Completed,NH-ANNA NAGAR,97,1279000,"ATTENDING BT PATCH WORK AT KUPPUSWAMY NAGAR 2ND STREET (FLOOD DAMAGED ROAD) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/22130,Roads,Completed,NH-ANNA NAGAR,97,1899000,"ATTENDING BT PATCH WORK AT P.E.KOIL WEST MADA STREET (FLOOD DAMAGED ROAD) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/22183,Roads,Completed,NH-ANNA NAGAR,101,997000,"RELAYING ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT F-BLOCK 2ND STREET (CHAINAGE FROM 0M TO 150M ) IN DN-101,U-22,Z-08 ( FLOOD DAMAGE )",Own Sources,8,2015-16,2016-17 NH/2015-16/22187,Roads,Completed,NH-ANNA NAGAR,101,362000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTH MONSOON 2015 AT I-BLOCK 11th STREET IN DN-101,U-22,Z-08 (FLOOD DAMAGE )",Own Sources,8,2015-16,2016-17 NH/2015-16/22191,Roads,Completed,NH-ANNA NAGAR,101,997000,"RELAYING ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT ANNA NAGAR 3RD MAIN ROAD IN DN-101,U-22,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/22196,Roads,Completed,NH-ANNA NAGAR,101,998000,"RELAYING ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT F-BLOCK 2ND STREET (CHAINAGE FROM 150M TO 300M ) IN DN-101,U-22,Z-08 (FLOOD DAMAGE )",Own Sources,8,2015-16,2016-17 NH/2015-16/22200,Roads,Completed,NH-ANNA NAGAR,101,635000,Attending to temporary Restoration of Damaged Interior road Due to flood in north monsoon 2015 at f block first st in dn 101 zone 8,Own Sources,8,2015-16,2016-17 NH/2015-16/22202,Roads,Completed,NH-ANNA NAGAR,101,998000,"RELAYING ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT O-BLOCK 31ST , 32ND &35TH STREET IN DN-101,U-22,Z-08 ( FLOOD DAMANGE )",Own Sources,8,2015-16,2016-17 NH/2015-16/22203,Roads,Completed,NH-ANNA NAGAR,95,354000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT NAGESHWARAOA COLONY IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22204,Roads,Completed,NH-ANNA NAGAR,101,998000,"LAYING OF CEMENT CONCRETE ROAD AT BHARATHIPURAM 2ND STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/22207,Roads,Completed,NH-ANNA NAGAR,95,1470000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT CHENNAI BATTAI ROAD IN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22208,Roads,Completed,NH-ANNA NAGAR,101,997000,"RELAYING ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT F-BLOCK 6TH STREET IN DN-101,U-22,Z-08 (FLOOD DAMAGE )",Own Sources,8,2015-16,2016-17 NH/2015-16/22209,Roads,Completed,NH-ANNA NAGAR,95,354000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT ADHI NAIDU STREET IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22211,Roads,Completed,NH-ANNA NAGAR,95,354000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT THIRUVIKA MAIN ST IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22212,Roads,Completed,NH-ANNA NAGAR,95,354000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT I BLOCK 37TH STREET IIN DN95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22213,Roads,Completed,NH-ANNA NAGAR,95,354000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT I BLOCK 35RD STREET IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22214,Roads,Completed,NH-ANNA NAGAR,95,354000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT I BLOCK 33RD STREET IIN DN-95, U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22216,Roads,Completed,NH-ANNA NAGAR,101,750000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO FLOOD IN NORTH MONSOON 2015 AT B-BLOCK 11TH STREET JAYA LAKSHMI COLONY (CHAINAGE 0M TO 120M) IN DN-101,U-22,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/22219,Roads,Completed,NH-ANNA NAGAR,101,997000,"RELAYING ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT N-BLOCK 26TH STREET & F-BLOCK 3RD STREET(part) IN DN-101,U-22,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/22292,Roads,Completed,NH-ANNA NAGAR,105,656000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT THIRUVEETHIAMMAN KOIL STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22293,Roads,Completed,NH-ANNA NAGAR,105,471000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT JAGANATHA NAGAR 1ST MAIN RAOD IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22294,Roads,Completed,NH-ANNA NAGAR,105,480000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT SANJEEVI STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22295,Roads,Completed,NH-ANNA NAGAR,105,295000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT MU.VARADHARAJAN STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22296,Roads,Completed,NH-ANNA NAGAR,105,609000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT VIVEKANDHA STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22297,Roads,Completed,NH-ANNA NAGAR,105,471000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT MURUGESHAN STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22298,Roads,Completed,NH-ANNA NAGAR,105,499000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT MARIAMMAN KOIL STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22300,Roads,Completed,NH-ANNA NAGAR,105,258000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT VENKATAKRISHNA NAGAR 1ST STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22304,Roads,Completed,NH-ANNA NAGAR,105,379000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT VENKATAKRISHNA NAGAR 2ND STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22305,Buildings,Completed,NH-ANNA NAGAR,95,996000,"IMPROVEMENT TO STORM WATER DRAIN ALONG EAST MAIN ROAD EAST SIDE FROM OPP DOOR NO-W380 TO BLOCK NO-109 IN DN-95, U-21, Z-8.(FLOOD EFFECTED AREA)",Own Sources,8,2015-16,2017-18 NH/2015-16/22306,Roads,Completed,NH-ANNA NAGAR,105,314000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT VGN NAGAR MAIN ROAD IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22307,Buildings,Completed,NH-ANNA NAGAR,95,329000,"RELAYING THE ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT I BLOCK 10TH STREET IN DN.95, UNIT 21, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22308,Roads,Completed,NH-ANNA NAGAR,105,331000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT RAZACK GARDEN AVENUE IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22310,Roads,Completed,NH-ANNA NAGAR,105,795000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT ASHOKA STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22311,Buildings,Completed,NH-ANNA NAGAR,95,995000,"IMPROVEMENT TO STORM WATER DRAIN ALONG EAST MAIN ROAD EAST SIDE FROM THIRUMANGALAM POLICE STATION TO OPP DOOR NO-W380 IN DN-95, U-21, Z-8.(FLOOD EFFECTED AREA)",Own Sources,8,2015-16,2017-18 NH/2015-16/22312,Roads,Completed,NH-ANNA NAGAR,105,379000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT KAMALA NEHRU NAGAR 2ND STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22313,Buildings,Completed,NH-ANNA NAGAR,95,998000,"IMPROVEMENT TO STORM WATER DRAIN ALONG EAST MAIN ROAD EAST SIDE BLOCK NO-109 JUNCTION OF NORTH MAIN ROAD IN DN-95, U-21, Z-8.(FLOOD EFFECTED AREA)",Own Sources,8,2015-16,2017-18 NH/2015-16/22314,Roads,Completed,NH-ANNA NAGAR,105,332000,"ATTENDING PATCH WORK (FLOOD DAMAGED) ROAD AT PERIYAR PATHAI WEST EXTN., IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22332,Buildings,Completed,NH-ANNA NAGAR,100,989000,"IMPROVEMENTS TO EXISTING COMPOUND WALL AT ARUMBAKKAM BURIAL GROUND IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22358,Buildings,Completed,NH-ANNA NAGAR,103,620000,"IMPROVEMENTS TO THE EXISTING WARD COUNCILLOR ROOM AND REPAIRS TO THE LEAKY ROOF FOR DIVISION OFFICE IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22399,Roads,Completed,NH-ANNA NAGAR,103,600000,"ATTENDING PATCH WORK AT VALLIAMMAL STREET IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22402,Roads,Completed,NH-ANNA NAGAR,103,540000,"ATTENDING PATCH WORK AT WADDELS ROAD IN DN-103, U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22403,Roads,Completed,NH-ANNA NAGAR,103,221000,"ATTENDING PATCH WORK AT LAKSHMI STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22406,Roads,Completed,NH-ANNA NAGAR,103,194000,"ATTENDING PATCH WORK AT DAMODHARAMOORTHY STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22407,Roads,Completed,NH-ANNA NAGAR,103,148000,"ATTENDING PATCH WORK AT VEERA RAGANVAN STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/2244,Footpath,Completed,NH-ANNA NAGAR,101,390000,"PROVIDING AND LAYING FOOT PATH AT SHENOY NAGAR MAIN ROAD IN DN-101,U-22,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22535,Roads,Completed,NH-ANNA NAGAR,103,810000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT UMAYAL ROAD (CH O -143) IN DN-103,U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/22538,Roads,Completed,NH-ANNA NAGAR,95,470000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT MULLAI NAGAR 1ST STREET IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22539,Roads,Completed,NH-ANNA NAGAR,95,1200000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT THIRU NAGAR 20TH STREET IN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22543,Roads,Completed,NH-ANNA NAGAR,95,423000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT I BLOCK 36TH STREET IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22544,Roads,Completed,NH-ANNA NAGAR,95,423000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT I BLOCK 34TH STREET IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22548,Roads,Completed,NH-ANNA NAGAR,95,285000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT POST OFFICE STREET IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22549,Roads,Completed,NH-ANNA NAGAR,95,1162000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT SRINIVASA AVENUE ( FROM SRINIVASA AVENUE TO BARATHI VIDALAYA SCHOOL) IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22550,Roads,Completed,NH-ANNA NAGAR,95,932000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT PONNAN KINARU STREET IIN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/22561,Roads,Completed,NH-ANNA NAGAR,99,395000,"PROVIDING CHILDREN PLAY APPARATUS AND IMPROVEMENTS TO PLAY GROUND AT H BLOCK 15TH STREET IN DN-99,UNIT-21,ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/2257,Buildings,Completed,NH-ANNA NAGAR,101,859000,"Improvement to footpath around 'c' block park in dn-101,unit-22,zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22578,Roads,Completed,NH-ANNA NAGAR,107,300000,PROVIDING OF PATCH WORK JAGANATHAPURAM 2nd STREET IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2015-16,2016-17 NH/2015-16/22594,Roads,Completed,NH-ANNA NAGAR,99,1780000,"ATTENDING PATCHES FLOOD DAMAGED ROADS WITH PAVER FINISHER AT G BLOCK 13TH & 19TH STREET,IN DN-99,UNIT-21,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22670,Roads,Completed,NH-ANNA NAGAR,99,2494000,"ATTENDING PATCHES FLOOD DAMAGED ROADS WITH PAVER FINISHER AT H BLOCK 25 26 27, 28,& 29TH STREET,DN-99,UNIT-21,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/22687,Roads,Completed,NH-ANNA NAGAR,99,940000,"ATTENDING PATCHES FLOOD DAMAGED ROADS WITH PAVER FINISHER AT PONNI COLONY MAIN ROAD,DN-99,UNITY-21,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/2277,Buildings,Completed,NH-ANNA NAGAR,102,420000,"Improvements to the existing Councillor Office at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/2280,Buildings,Completed,NH-ANNA NAGAR,102,800000,"Improvements to the existing Division Office at Gajapathy Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/23328,Roads,Completed,NH-ANNA NAGAR,107,4800000,PROVIDING OF PATCH WORK AT HARRINGTON ROAD IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/2338,Buildings,Completed,NH-ANNA NAGAR,102,460000,"Improvements to public convenience and disabled toilet at cemetry road and 1st main road west in dn-102,unit-23,zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24394,Buildings,Completed,NH-ANNA NAGAR,95,994000,IMPROVEMENTS TO EXISTING STORM WATER DRAIN ALONG THIRUMANGALAM ROAD FROM CANAL TO DOOR NO 36/1 IN DN-95 UNIT-21 ZONE-08,Own Sources,8,2015-16,2016-17 NH/2015-16/24405,Buildings,Completed,NH-ANNA NAGAR,95,994000,IMPROVEMENTS TO EXISTING STORM WATER DRAIN ALONG THIRUMANGALAM ROAD FROM DOOR NO 36/1 TO JUNCTION OF THIRUNAGAR 5TH STREET IN DN-95 UNIT-21 ZONE-08,Own Sources,8,2015-16,2016-17 NH/2015-16/24426,Buildings,Completed,NH-ANNA NAGAR,95,994000,"IMPROVEMENT TO STORM WATER DRAIN ALONG EAST MAIN ROAD WEST SIDE FROM DOOR NO-374 TO JUNCTION OF IMAYAM COLONY. IN DN-95, U-21, Z-8.(FLOOD EFFECTED AREA)",Own Sources,8,2015-16,2017-18 NH/2015-16/24432,Buildings,Completed,NH-ANNA NAGAR,95,993000,"IMPROVEMENT TO STORM WATER DRAIN ALONG EAST MAIN ROAD WEST SIDE FROM SCHOOL ROAD TO DOOR NO-W380. IN DN-95, U-21, Z-8.(FLOOD EFFECTED AREA)",Own Sources,8,2015-16,2017-18 NH/2015-16/24437,Buildings,Completed,NH-ANNA NAGAR,95,997000,"IMPROVEMENT TO STORM WATER DRAIN ALONG EAST MAIN ROAD WEST SIDE FROM DOOR NO-W380 TO DOOR NO-374. IN DN-95, U-21, Z-8.(FLOOD EFFECTED AREA)",Own Sources,8,2015-16,2016-17 NH/2015-16/24438,Buildings,Completed,NH-ANNA NAGAR,102,998000,"Proposed construction of Compound Wall(North western side) at CGHS School at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24442,Buildings,Completed,NH-ANNA NAGAR,102,999000,"Proposed construction of Compound Wall(South western side) at CGHS School at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24461,Buildings,Completed,NH-ANNA NAGAR,102,765000,"Repairs and Improvements to Conference Hall Room(North side) and painting work all around compound wall at CGHS School at Pulla Avenue in Dn-102,U-23,Z-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/24462,Buildings,Completed,NH-ANNA NAGAR,102,980000,"Improvements to CGHS School(North Block) at Pulla Avenue in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/24463,Buildings,Completed,NH-ANNA NAGAR,102,997000,"Repairs and Improvements to CGHSS (West Block- Ground Floor and First Floor) at Pulla Avenue in Dn-102,U-23,Z-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/24464,Roads,Completed,NH-ANNA NAGAR,102,825000,"Painting work to CGHSS(west block) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24580,Buildings,Completed,NH-ANNA NAGAR,98,280000,"IMPROVEMENTS TO DIVISION OFFICE AT ASPRIN GARDEN IN DN-98,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/24662,Parks,Completed,NH-ANNA NAGAR,102,180000,"Improvements to G Block Park at Second Avenue Road Extension in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24706,Roads,Completed,NH-ANNA NAGAR,102,225000,"Attending CC patch work at Various streets in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24731,Footpath,Completed,NH-ANNA NAGAR,102,215000,"Forming footpath at Bervery Road (from junction of pulla avenue road to amma unavagam) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24743,Buildings,Completed,NH-ANNA NAGAR,102,235000,"Providing Platform to the surrounding of E Toilet at KG road and Cemetry Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24801,Storm Water Drain,Completed,NH-ANNA NAGAR,101,995000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 6TH AVENUE (CHAINAGE FROM 0M TO 100M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/24803,Buildings,Completed,NH-ANNA NAGAR,102,980000,"Improvements to CPS at Manjokollai Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24827,Storm Water Drain,Completed,NH-ANNA NAGAR,101,950000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 6TH AVENUE (CHAINAGE FROM 100M TO 200M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/24832,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 6TH AVENUE (CHAINAGE FROM 200M TO 300M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/24838,Buildings,Completed,NH-ANNA NAGAR,102,475000,"Providing Aluminium Partition to Revenue Department at Zonal office Building(Ground Floor) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24839,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 6TH AVENUE (CHAINAGE FROM 400M TO 500M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/24843,Buildings,Completed,NH-ANNA NAGAR,102,300000,"Improvements to Zonal Office Building(first floor) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24847,Buildings,Completed,NH-ANNA NAGAR,102,275000,"Providing Aluminium Partition to Town planning section(RDC office - Second floor) at Zonal office Building in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/24854,Buildings,Completed,NH-ANNA NAGAR,102,250000,"Forming Roof Top Gardening at Zonal Office 8 at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/24879,Roads,Completed,NH-ANNA NAGAR,96,112000,"LAYING RAIN DAMAGED PATCH WITH WET MIX MACADAM AT K.H.ROAD AND N.M.K. STREET IN DN-96, U-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/25066,Buildings,Completed,NH-ANNA NAGAR,98,53000,"PROVIDING AND FIXING E-SEVA SIGN BOARD IN DN-98,U-23,Z-8",Own Sources,8,2015-16,2018-19 NH/2015-16/25174,Buildings,Completed,NH-ANNA NAGAR,108,1500000,"CONSTRUCTION OF RATION SHOP AT N.G.O. COLONY MAIN ROAD IN DN.108, UNIT.22, ZONE.8 (ANNA NAGAR CONSITUENCY M.L.A. FUND)",MLACDS,8,2015-16,2016-17 NH/2015-16/25304,Roads,Completed,NH-ANNA NAGAR,94,966000,"ATTENDING PATCH WORK AT NORTH JAGANTHAN NAGAR 1ST STREET DIV-94,UNIT-21,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/2532,Buildings,Completed,NH-ANNA NAGAR,102,725000,"Improvements to AHO(central) room, Engineering Section, Birth and Death counter at Zonal office in Dn-102, Unit--23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/25368,Roads,Completed,NH-ANNA NAGAR,106,590000,"PROVIDING AND LAYING CEMENT CONCRETE M20 IN ROAD SIDE AT RANGARAJULU STREET,INDHARANI LANE, RAGAVAN STREET, RANGANAYAGI AMMAL STREET, IN DN 106, UNIT 22, ZONE 08.",Own Sources,8,2015-16,2016-17 NH/2015-16/2537,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Improvements to Common Service Centre at Zonal Office in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/25377,Roads,Completed,NH-ANNA NAGAR,106,589000,"PROVIDING AND LAYING CEMENT CONCRETE M20 IN ROAD SIDE AT KANNAPPAN STREET,MURALIDHARAN STREET , DURAI SAMY STREET, AMMAYE AMMAL LANE, IN DN 106, UNIT 22, ZONE 08.",Own Sources,8,2015-16,2016-17 NH/2015-16/25665,Buildings,Completed,NH-ANNA NAGAR,106,225000,"REPAIRS WORKS AT ICDS BUILDING IN METHA NAGAR, COLLECTORATE COLONY 6TH CROSS STREET, INDHRANI NAGAR, M.H COLONY IN DN-106,U-22,Z-VIII.",Own Sources,8,2015-16,2016-17 NH/2015-16/25755,Buildings,Completed,NH-ANNA NAGAR,102,970000,"Improvements to CGHSS (west block - Second floor) at Pulla Avenue in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/25756,Buildings,Completed,NH-ANNA NAGAR,102,530000,"Improvements to CGHSS(west block - Terrace floor) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/25757,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Improvements to Kitchen shed at CMS, Aminijikarai at Poonamalle High Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/25758,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Repairs and Improvements to CMS, Aminijikarai at PH Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/25789,Buildings,Completed,NH-ANNA NAGAR,108,1500000,"CONSTRUCTION OF RATION SHOP AT PARI STREET IN DN.108, UNIT.22, ZONE.8 (ANNA NAGAR CONSITUENCY M.L.A. FUND)",MLACDS,8,2015-16,2016-17 NH/2015-16/25873,Roads,Completed,NH-ANNA NAGAR,105,618000,"Relaying the road at Ambedkar Street in Div -105, Unit -22, Zone -8.",Own Sources,8,2015-16,2017-18 NH/2015-16/25875,Roads,Completed,NH-ANNA NAGAR,100,1142000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT Y BLOCK MAIN ROAD IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/26020,Footpath,Completed,NH-ANNA NAGAR,100,262000,"IMPROVEMENTS TO FOOTPATH AT AJ BLOCK 1st STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26021,Footpath,Completed,NH-ANNA NAGAR,100,328000,"IMPROVEMENTS TO FOOTPATH AT AJ BLOCK 2nd STREET IN DIVISION-100,UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26034,Storm Water Drain,Completed,NH-ANNA NAGAR,100,993000,"IMPROVEMENTS TO FOOTPATH AND STROM WATER DRAIN AT 2nd AVENUE (JN OF IN FRONT OF LG SHOW ROOM TO MV HOSPITAL) IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26036,Storm Water Drain,Completed,NH-ANNA NAGAR,100,997000,"IMPROVEMENTS TO STROM WATER DRAIN AT 2nd AVENUE (JN OF 6th MAIN ROAD TO AAVIN MILK BOOTH ) IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/26037,Storm Water Drain,Completed,NH-ANNA NAGAR,100,995000,"IMPROVEMENTS TO FOOTPATH AND STROM WATER DRAIN AT 2nd AVENUE (JN OF AAVIN MILK BOOTH TO INFRONT OF OLD EMPLOYMENT OFFICE) IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26069,Storm Water Drain,Completed,NH-ANNA NAGAR,100,995000,"IMPROVEMENTS TO STROM WATER DRAIN AT 2nd AVENUE (JN OF INFRONT OF OLD EMPLOYMENT OFFICE TO 3rd MAIN ROAD ) IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26070,Storm Water Drain,Completed,NH-ANNA NAGAR,100,913000,"IMPROVEMENTS TO STROM WATER DRAIN AT 2nd AVENUE (JN OF 3rd MAIN ROAD TO TOWERS CLUB ) IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26075,Roads,Completed,NH-ANNA NAGAR,95,860000,RELAYING OF FLOOD DAMAGED ROAD DUE TO NORTH EAST MONSOON AT 20TH MAIN ROAD (FROM D.NO 1333 TO CHURCH STREET ) IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/26134,Buildings,Completed,NH-ANNA NAGAR,106,410000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT OFFICERS COLONY 3RD STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26135,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 0M TO 80M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26143,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 560M TO 640M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26188,Buildings,Completed,NH-ANNA NAGAR,103,989000,"Providing Fencing Arrangements Around Transformer at T.P Chathiram 1st street,2nd street,14th street,Siva Shankaran Street,Taylors Road,E.V.R Salai (Near Guest Hospital) and Kilpauk Garden Road in Dn-103,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/26193,Buildings,Completed,NH-ANNA NAGAR,103,593000,"Providing Fencing Arrangements Around Transformer at Kilpauk garden 2nd Street,New Avadi Road,and E.V.R Salai (near OSR land) in Dn-103,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/26195,Buildings,Completed,NH-ANNA NAGAR,103,651000,PROVIDING AND FIXING STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREETS IN DN 103 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/26197,Buildings,Completed,NH-ANNA NAGAR,103,998000,"PROVIDING AND FIXING STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREETS IN DN 103, U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/26215,Roads,Completed,NH-ANNA NAGAR,98,999000,"FORMING GRANITE FOOTPATH AT ASPIRAN GARDEN 1ST STREET SOUTH SIDE ( FROM DOOR NO:27/17 TO DOOR NO:6 ) IN DN-98,U-23,Z-08 ( ward councilar fund 2015-16)",Own Sources,8,2015-16,2016-17 NH/2015-16/26216,Roads,Completed,NH-ANNA NAGAR,98,999000,"FORMING GRANITE FOOTPATH AT ASPIRAN GARDEN 1ST STREET NORTH SIDE ( DOOR NO:20/48 TO DOOR NO:5/9) IN DN-98,U-23,Z-08 ( ward councilar fund 2015-16)",Own Sources,8,2015-16,2016-17 NH/2015-16/26307,Storm Water Drain,Completed,NH-ANNA NAGAR,101,998000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 80M TO 160M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26311,Storm Water Drain,Completed,NH-ANNA NAGAR,101,996000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 160M TO 240M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26319,Storm Water Drain,Completed,NH-ANNA NAGAR,101,996000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 240M TO 320M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26333,Storm Water Drain,Completed,NH-ANNA NAGAR,101,996000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 320M TO 400M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26337,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 400M TO 480M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26344,Footpath,Completed,NH-ANNA NAGAR,106,22000,"REPAIRS WORK AT METHA NAGAR GYM IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26345,Storm Water Drain,Completed,NH-ANNA NAGAR,101,996000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD EAST SIDE (CHAINAGE FROM 480M TO 560M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26468,Culvert,Completed,NH-ANNA NAGAR,96,690000,"DISMANTLING AND RE CONSTRUCTION OF CULVERT TOP SLAB AT JUN. OF GANDHI NAGAR NEAR CHRUCH IN DN -96, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/26601,Roads,Completed,NH-ANNA NAGAR,105,510000,"Laying Cement Concert road at venkatakrishna nagar 4th street (ch 0 to 45) in division-105, unit-22, zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/26613,Roads,Completed,NH-ANNA NAGAR,105,531000,"Laying Cement Concert road at venkatakrishna nagar 4th street (ch 45 to 92) in division-105, unit-22, zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/2667,Storm Water Drain,Completed,NH-ANNA NAGAR,106,990000,"RAISING AND LOWERING CMWSSB DOOR AT VARIOUS STREET IN DN-106 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/2668,Storm Water Drain,Completed,NH-ANNA NAGAR,106,900000,"SUPPLYING AND FIXING MANHOLE DOOR IN STORM WATER DRAIN AT VARIOUS STREET IN DN-106 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26782,Roads,Completed,NH-ANNA NAGAR,101,995000,"LAYING OF CEMENT CONCRETE ROAD AT BHARATHIPURAM 3RD STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26791,Roads,Completed,NH-ANNA NAGAR,101,998000,"LAYING OF CEMENT CONCRETE ROAD AT BHARATHIPURAM 4TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/26808,Roads,Completed,NH-ANNA NAGAR,102,600000,"Attending patchwork at Old Bus Stand Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/2684,Parks,Completed,NH-ANNA NAGAR,102,770000,"Improvements to Traffic Island at Kilpauk Garden Road junction of TP chatiram main road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/26933,Roads,Completed,NH-ANNA NAGAR,95,155000,FORMING FOOTPATH AT REDDY STREET AND OTHER IMPROVEMENT WORKS AT VARIOUS PLACES IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2017-18 NH/2015-16/27064,Roads,Completed,NH-ANNA NAGAR,106,447000,Strengthening and relaying the road by paver finisher at indrani lane in Division-106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27087,Roads,Completed,NH-ANNA NAGAR,97,922000,"RELAYING OF CC ROAD AT GURUVAPPA MAISTRY STREET IN DN-97 , U-21 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/27092,Roads,Completed,NH-ANNA NAGAR,103,910000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT BANK STREET AND NEW AVADI ROAD LANE IN DN-103,U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27095,Buildings,Completed,NH-ANNA NAGAR,103,999000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT CHATHUR POOJA DOSS ROAD HALLS ROAD YMCA LANE IN DN-103,U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27096,Roads,Completed,NH-ANNA NAGAR,106,843000,strengthening and relaying of road by paver finisher at Raghavan street in dn-106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27098,Buildings,Completed,NH-ANNA NAGAR,103,996000,"IMPROVEMENTS WORK IN DIVISION OFFICE AT TEMPLE STREET IN Dn-103,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/27102,Roads,Completed,NH-ANNA NAGAR,106,528000,strengthening and relaying of road by paver finisher at sannathi street in dn 106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27103,Roads,Completed,NH-ANNA NAGAR,106,766000,Strengthening and relaying of road by paver finisher at Railway colony 3rd street in dn 106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27104,Roads,Completed,NH-ANNA NAGAR,106,588000,Strengthening and relaying of road by paver finisher at Railway colony 3rd street extension in dn 106 unit 22 zone 8,Own Sources,8,2015-16,2016-17 NH/2015-16/27105,Roads,Completed,NH-ANNA NAGAR,106,447000,Strengthening and relaying of road by paver finisher at vimala street in dn 106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27106,Roads,Completed,NH-ANNA NAGAR,106,1810000,Strengthening and relaying of road by paver finisher at collectorate colony main road in dn 106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27155,Roads,Completed,NH-ANNA NAGAR,103,240000,"ATTENDING PATCH WORK AT MUTHU SOLAI STREET IN DN-103, U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27156,Roads,Completed,NH-ANNA NAGAR,106,1205000,strengthening and relaying of road by RMC 30 at MH colony 2nd main road in division-106 unit-22 zone-8,Own Sources,8,2015-16,2017-18 NH/2015-16/27157,Roads,Completed,NH-ANNA NAGAR,103,148000,"ATTENDING PATCH WORK AT APPAVOO AVENUE IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27158,Roads,Completed,NH-ANNA NAGAR,103,240000,"ATTENDING PATCH WORK AT THIRUVEETHI AMMAN KOIL STREET IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27160,Roads,Completed,NH-ANNA NAGAR,103,332000,"ATTENDING PATCH WORK AT MANDAPAM ROAD IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27161,Roads,Completed,NH-ANNA NAGAR,103,332000,"ATTENDING PATCH WORK AT RAMANATHAN STREET IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27184,Roads,Completed,NH-ANNA NAGAR,101,995000,"LAYING OF CEMENT CONCRETE ROAD AT PERIYAKUDAL STREET (CHAINAGE FROM 0M TO 90M) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/27186,Roads,Completed,NH-ANNA NAGAR,101,996000,"LAYING OF CEMENT CONCRETE ROAD AT PERIYAKUDAL STREET (CHAINAGE FROM 90M TO 180M) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/27187,Parks,Completed,NH-ANNA NAGAR,95,124000,"IMPROVEMENTS TO KAMBER KUDIERUPU PLAY GROUND IN DN.95, UNIT 21, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27190,Roads,Completed,NH-ANNA NAGAR,101,960000,"LAYING OF CEMENT CONCRETE ROAD AT PERIYAKUDAL 1ST AND 3RD LANE IN DN-101,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/27197,Roads,Completed,NH-ANNA NAGAR,101,620000,"LAYING OF CEMENT CONCRETE ROAD AT PERIYAKUDAL 2ND LANE IN DN-101,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/27209,Roads,Completed,NH-ANNA NAGAR,105,527000,"Laying Cement Concert road at venkatakrishna nagar 4th street (ch 92 to 140) in division-105, unit-22, zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/27220,Roads,Completed,NH-ANNA NAGAR,103,1250000,"ATTENDING PATCH WORK AT KELLYS ROAD IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27221,Roads,Completed,NH-ANNA NAGAR,103,332000,"ATTENDING PATCH WORK AT SUNDARLAL NAHATHA AVENUE IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27222,Parks,Completed,NH-ANNA NAGAR,102,997000,"Providing fencing for greenary area at Pulla Avenue Park(North - west side) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/27223,Roads,Completed,NH-ANNA NAGAR,103,332000,"ATTENDING PATCH WORK AT BRANSON GARDEN STREET IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27224,Roads,Completed,NH-ANNA NAGAR,103,510000,"ATTENDING PATCH WORK AT SIVASANKARAN STREET IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27225,Roads,Completed,NH-ANNA NAGAR,103,240000,"ATTENDING PATCH WORK AT APPA GARDEN STREET IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27227,Roads,Completed,NH-ANNA NAGAR,103,332000,"ATTENDING PATCH WORK AT RAJARATHINAM STREET IN DN-103,U-23.Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27241,Storm Water Drain,Completed,NH-ANNA NAGAR,106,64000,"PROVIDING SILT CATCH PIT AT AMMAI AMMAL STREET IN DN-106,UNIT-22,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/27243,Roads,Completed,NH-ANNA NAGAR,103,715000,"RELAYING WITH BCCMP1 BY PAVER FINISHER AT PARASU PILLAI STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27244,Roads,Completed,NH-ANNA NAGAR,103,1770000,"RELAYING WITH BCC BY PAVER FINISHER AT THIYAGAPPA STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27247,Roads,Completed,NH-ANNA NAGAR,103,1314000,"RELAYING WITH BCC BY PAVER FINISHER AT KUMMALAMMAN KOIL STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27254,Roads,Completed,NH-ANNA NAGAR,103,2283000,"RELAYING WITH BCC BY PAVER FINISHER AT VASU STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27287,Roads,Completed,NH-ANNA NAGAR,103,2646000,"RELAYING WITH BCCMP1 BY PAVER FINISHER AT THAMBUSAMY STREET IN DN-103,U-23",Own Sources,8,2015-16,2016-17 NH/2015-16/27291,Roads,Completed,NH-ANNA NAGAR,104,259000,"ATTENDING PATCHES AT VELLALA STREET IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27292,Roads,Completed,NH-ANNA NAGAR,104,1026000,"ATTENDING PATCHES AT LETTANGS ROAD IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27301,Roads,Completed,NH-ANNA NAGAR,104,656000,"ATTENDING PATCHES AT POTTERS STREET IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27302,Roads,Completed,NH-ANNA NAGAR,104,563000,"ATTENDING PATCHES AT WEST THANDAVARAYAN STREET IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27306,Roads,Completed,NH-ANNA NAGAR,104,749000,"ATTENDING PATCHES AT PONNAN STREET IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27308,Roads,Completed,NH-ANNA NAGAR,104,333000,"ATTENDING PATCHES AT DIWAN RAMA ROAD IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27312,Roads,Completed,NH-ANNA NAGAR,104,887000,"ATTENDING PATCHES AT SARAVANA PERUMAL STREET IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27315,Roads,Completed,NH-ANNA NAGAR,104,518000,"ATTENDING PATCHES AT EVR 1ST LANE IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27319,Roads,Completed,NH-ANNA NAGAR,104,887000,"ATTENDING PATCHES AT SUNDARAM LANE IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27321,Roads,Completed,NH-ANNA NAGAR,107,495000,PROVIDING OF PATCH WORK AT CHARI ROAD IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27328,Roads,Completed,NH-ANNA NAGAR,107,885000,PROVIDING OF PATCH WORK AT MC NICHOLS ROAD 3rd LANE IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27340,Roads,Completed,NH-ANNA NAGAR,107,128000,PROVIDING OF PATCH WORK AT MC NICHOLS SERVICE ROAD IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27341,Roads,Completed,NH-ANNA NAGAR,104,1026000,"ATTENDING PATCHES AT DR.ALAGAPPA ROAD IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27344,Roads,Completed,NH-ANNA NAGAR,107,110000,PROVIDING OF PATCH WORK AT SCHOOL ROAD IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27359,Roads,Completed,NH-ANNA NAGAR,107,880000,PROVIDING OF PATCH WORK AT MAYOR CHITTI BABU STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27366,Roads,Completed,NH-ANNA NAGAR,107,240000,PROVIDING OF PATCH WORK AT VENKATACHALAPATHY STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27371,Roads,Completed,NH-ANNA NAGAR,107,194000,PROVIDING OF PATCH WORK ATJAGANATHAPURAM 1st STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27376,Roads,Completed,NH-ANNA NAGAR,107,110000,PROVIDING OF PATCH WORK AT VAIDYANATHAN STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27382,Roads,Completed,NH-ANNA NAGAR,102,998000,"Attending BT patchwork at Central Street, Kanniyamman Kovil Street and other various street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/27393,Roads,Completed,NH-ANNA NAGAR,104,599000,"RELAYING OF THE ROAD WITH DBM 50MM AND BC 40MM THICK BY PAVER FINISHER AT AUDIYAPPA STREET IN DIVISION-104, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27403,Roads,Completed,NH-ANNA NAGAR,104,638000,"RELAYING OF THE ROAD WITH DBM 50MM AND BC 40MM THICK BY PAVER FINISHER AT WEST THANDAVARAYAN STREET IN DIVISION-104, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27409,Roads,Completed,NH-ANNA NAGAR,104,319000,"RELAYING OF THE ROAD WITH DBM 50MM AND BC 40MM THICK BY PAVER FINISHER AT GANGADEESHWARAR 1ST LANE IN DIVISION-104, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27412,Buildings,Completed,NH-ANNA NAGAR,96,230000,"PROVIDING CONSTRUCTION OF COMPOUND WALL AT CHENNAI HIGHER SECONDARY SCHOOL PALAVAYAL SALAI IN DN-96 U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27416,Buildings,Completed,NH-ANNA NAGAR,96,600000,"IMPROVEMENTS TO CHS AT PALAVAYAL IN DN-96, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27420,Buildings,Completed,NH-ANNA NAGAR,96,997000,"REPAIRS AND IMPROVEMENTS TO SCIENCE LAB AT CHS PALAVAYAL IN DN-96, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27421,Roads,Completed,NH-ANNA NAGAR,96,995000,"PROVIDING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT VARIOUS STREETS IN DN-96, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27503,Roads,Completed,NH-ANNA NAGAR,106,365000,strengthening and relaying of road by RMC 30 at mh colony 2nd Cross Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2017-18 NH/2015-16/27505,Roads,Completed,NH-ANNA NAGAR,106,335000,strengthening and relaying of road by RMC 30 at mh colony 3rd Cross Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2017-18 NH/2015-16/27506,Roads,Completed,NH-ANNA NAGAR,106,380000,strengthening and relaying of road by RMC 30 at mh colony 4th Cross Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2017-18 NH/2015-16/27507,Roads,Completed,NH-ANNA NAGAR,106,360000,strengthening and relaying of road by RMC 30 at Indira Gandhi Nagar 1st Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2017-18 NH/2015-16/27508,Roads,Completed,NH-ANNA NAGAR,106,264000,strengthening and relaying of road by RMC 30 at Indira Gandhi Nagar 2nd Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2017-18 NH/2015-16/27511,Roads,Completed,NH-ANNA NAGAR,106,200000,strengthening and relaying of road by RMC 30 at Indira Gandhi Nagar 3rd Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27514,Roads,Completed,NH-ANNA NAGAR,106,240000,strengthening and relaying of road by RMC 30 at Indira Gandhi Nagar 4th Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27526,Roads,Completed,NH-ANNA NAGAR,106,200000,strengthening and relaying of road by RMC 30 at Indira Gandhi Nagar 5th Street in division-106 unit-22 zone-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27565,Roads,Completed,NH-ANNA NAGAR,97,249000,"RELAYING OF CC ROAD AT MUTHAMMAN KOIL 2ND STREET IN DN-97, U-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27569,Roads,Completed,NH-ANNA NAGAR,97,363000,"RELAYING OF CC ROAD AT KUNJITHAM GURUSWAMY STREET IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27574,Roads,Completed,NH-ANNA NAGAR,97,392000,"RELAYING OF CC ROAD AT THANTHAI PERIYAR NAGAR 3RD STREET IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27578,Roads,Completed,NH-ANNA NAGAR,97,648000,"RELAYING OF CC ROAD AT VEERASAMY 1ST STREET IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27579,Roads,Completed,NH-ANNA NAGAR,97,874000,"RELAYING OF CC ROAD AT PALANI ANDAVAR KOIL LANE IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/27665,Roads,Completed,NH-ANNA NAGAR,100,1238000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT Y-BLOCK 3rd STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27666,Roads,Completed,NH-ANNA NAGAR,100,895000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT Y-BLOCK 8th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27667,Roads,Completed,NH-ANNA NAGAR,100,1238000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT Y-BLOCK 9th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27668,Roads,Completed,NH-ANNA NAGAR,100,718000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AUROVILLA FLAT STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27670,Buildings,Completed,NH-ANNA NAGAR,100,336000,"IMPROVEMENTS OF ALL ANGANWADI, AMMAUNAVAGAM ,N.S.K NAGAR SCHOOL AND PC WORKS IN DIVISION-100, UNIT-22, ZONE-08.(UNDER MAINTENANCE)",Own Sources,8,2015-16,2016-17 NH/2015-16/27769,Storm Water Drain,Completed,NH-ANNA NAGAR,97,900000,"DEMOLITION AND RE-CONSTRUCTION OF STORM WATER DRAIN AT SABAPATHY STREET ( REACH-III) FROM NIRMAL SCHOOL OPP. TO AYANAVARAM ROAD IN DN-97,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/27836,Roads,Completed,NH-ANNA NAGAR,101,996000,"ATTENDING BITUMINOUS PATCH WORK AT VARIOUS STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/27870,Roads,Completed,NH-ANNA NAGAR,99,1130000,RELAYING OF ROAD WITH BCCMP BY PAVER AT H BLOCK 11 TH STREET ON DN 99 UNIT 21 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/27872,Footpath,Completed,NH-ANNA NAGAR,103,835000,"IMPROVEMENT TO FOOTPATH AT RANGANATHAN AVENUE ROAD (LEFT SIDE) IN DN-103,UNIT-23,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/27873,Footpath,Completed,NH-ANNA NAGAR,103,901000,"IMPROVEMENT TO FOOTPATH AT RANGANATHAN AVENUE ROAD ( RIGHT SIDE) IN DN-103,UNIT-23,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/27946,Buildings,Completed,NH-ANNA NAGAR,98,2271000,"CONSTRUCTION OF MULTI PURPOSE HALL AT LOCKMA NAGAR IN DN-98,UNIT-23,Z-8.",MLACDS,8,2015-16,2017-18 NH/2015-16/27947,Roads,Completed,NH-ANNA NAGAR,99,309000,REALYING OF ROAD WITH BCCMP BY PAVER AT H BLOCK 12TH STREET ON DN99 UNIT21 ZONE-8,Own Sources,8,2015-16,2016-17 NH/2015-16/27950,Roads,Completed,NH-ANNA NAGAR,99,309000,"REALYING OF ROAD WITH BCCMP BY PAVER AT H BLOCK 13TH STREET ON DN 99 ,UNIT 21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/27951,Storm Water Drain,Completed,NH-ANNA NAGAR,99,999000,"Proposed Construction Of 2-2SWD at H block. 3rd Street,6th and 8th Street in DN 99,U-21,Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/27969,Roads,Completed,NH-ANNA NAGAR,103,935000,"LAYING ROAD WITH CEMENT CONCRETE AT KAMARAJAR NAGAR, ANTHONY CHURCH STREET AND MILLERS LANE IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27976,Footpath,Completed,NH-ANNA NAGAR,103,960000,"IMPROVEMENTS TO FOOT PATH AND SWD AT RAMANATHAN STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/27977,Footpath,Completed,NH-ANNA NAGAR,103,909000,"IMPROVEMENTS TO FOOT PATH AT LANDONS ROAD,PROF.SUBRAMANIYAM STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28042,Roads,Completed,NH-ANNA NAGAR,100,995000,"LAYING OF CEMENT CONCRETE ROAD AT SABARI STREET IN DN.100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28043,Roads,Completed,NH-ANNA NAGAR,100,995000,"LAYING OF CEMENT ROAD AT NATHAMUNI 2ND STREET LINK ROAD IN DN.100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28046,Footpath,Completed,NH-ANNA NAGAR,103,940000,"IMPROVEMENTS OF FOOT PATH DR.VASUDEVAN STREET AND LAKSHMI STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28062,Parks,Completed,NH-ANNA NAGAR,102,990000,"Providing fencing for greenary area at G Block park(South-west side) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28063,Parks,Completed,NH-ANNA NAGAR,102,985000,"Providing ramp and handrails for Chennai Girl Higher Secondary School at Pulla Avenue, Chennai Middle Schools at Gujji Street and PH road, Chennai Primary School at Tamilar Nagar and Manjakollai Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28064,Roads,Completed,NH-ANNA NAGAR,102,890000,"Improvements to Centre Median at Pulla Avenue Road(from junction of Poonamallee Road to Ayyavoo Street) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2019-20 NH/2015-16/28066,Roads,Completed,NH-ANNA NAGAR,102,998500,"Providing Shahabed flooring tiles in Skating Court at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28067,Parks,Completed,NH-ANNA NAGAR,102,990000,"Providing handrail for Skating court alround at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28068,Roads,Completed,NH-ANNA NAGAR,102,735000,"Providing Pvc coated wire fencing at alround skating court at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28069,Footpath,Completed,NH-ANNA NAGAR,103,979000,"IMPROVEMENTS TO FOOT PATH AND SWD AT KILPAUK GARDEN 2ND STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28070,Parks,Completed,NH-ANNA NAGAR,102,997000,"Providing fencing for greenary area at Pulla Avenue Park(South - east side) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/28071,Roads,Completed,NH-ANNA NAGAR,106,950000,"RELAYING ROAD BY PAVER FINISHER AT COLLECTORATE COLONY 3RD CROSS STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28072,Parks,Completed,NH-ANNA NAGAR,102,995000,"Providing fencing for greenary area at alround Skating Court at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28073,Parks,Completed,NH-ANNA NAGAR,102,998000,"Providing fencing for greenary area at alround Volley Ball Court at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/28074,Roads,Completed,NH-ANNA NAGAR,106,677000,"RELAYING ROAD BY PAVER FINISHER AT COLLECTORATE COLONY 6TH CROSS STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28076,Parks,Completed,NH-ANNA NAGAR,102,998000,"Providing fencing for greenary area at alround Tennis Court at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/28077,Parks,Completed,NH-ANNA NAGAR,102,998000,"Providing fencing for greenary area at east and west side of Basket Ball Court at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/28179,Roads,Completed,NH-ANNA NAGAR,106,640000,"RELAYING THE ROAD BY PAVER FINISHER AT VELLALA STREET (FROM THE JUNCTION OF EAST ARASAMARAM STREET TO 160M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28238,Roads,Completed,NH-ANNA NAGAR,98,440000,"Laying of cement concrete road at Ambedkar nagar 2nd street (From Ch 300m to 360m ) in Dn-98,U-23,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28335,Roads,Completed,NH-ANNA NAGAR,106,640000,"RELAYING THE ROAD BY PAVER FINISHER AT VELLALA STREET (FROM JUNCTION 160M TO 320M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28337,Roads,Completed,NH-ANNA NAGAR,106,800000,"RELAYING THE ROAD BY PAVER FINISHER AT JAYARAMAN STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/28350,Roads,Completed,NH-ANNA NAGAR,104,995000,LAYING CEMENT CONCRETE ROAD AT SHANMUGARAYAN STREET ( 0 M TO 125 M ) IN DN-104 UNIT-23 ZONE -8,Own Sources,8,2015-16,2016-17 NH/2015-16/28373,Roads,Completed,NH-ANNA NAGAR,104,995000,LAYING CEMENT CONCRETE ROAD AT SHANMUGARAYAN STREET ( 125 M TO 250 M ) IN DN-104 UNIT-23 ZONE -8,Own Sources,8,2015-16,2016-17 NH/2015-16/28376,Roads,Completed,NH-ANNA NAGAR,97,1941000,"RELAYING OF ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT ELUMALAI STREET IN DN-97,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/28392,Buildings,Completed,NH-ANNA NAGAR,102,998000,"Improvements to CGHSS (south block - first floor) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/28395,Buildings,Completed,NH-ANNA NAGAR,107,148000,PROVIDING OF PATCH WORK RAJAMMAL STREET( NORTH) AT IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/28398,Buildings,Completed,NH-ANNA NAGAR,102,930000,"Improvements to CGHSS (south block - second floor) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/28401,Roads,Completed,NH-ANNA NAGAR,108,970000,"LAYING CEMENT CONCRETE ROAD WITH RMC30 AT PASUMPON STREET 'N' & 'O' BLOCK IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28402,Roads,Completed,NH-ANNA NAGAR,108,975000,"LAYING CEMENT CONCRETE ROAD WITH RMC30 AT AVVAI NAGAR WEST STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28403,Roads,Completed,NH-ANNA NAGAR,108,570000,"LAYING CEMENT CONCRETE ROAD WITH RMC30 AT NEHRU & ANDAVAR LINK STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28405,Roads,Completed,NH-ANNA NAGAR,108,993000,"LAYING CEMENT CONCRETE ROAD WITH DURAISAMI RAJA STREET( From chinage 100m to 250m) IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28407,Roads,Completed,NH-ANNA NAGAR,108,450000,"LAYING CEMENT CONCRETE ROAD WITH ANNAMALAI MESTRI STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28408,Buildings,Completed,NH-ANNA NAGAR,102,965000,"Improvements to CGHSS (south block - Third floor) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/28409,Roads,Completed,NH-ANNA NAGAR,108,470000,"LAYING CEMENT CONCRETE ROAD WITH RMC30 AT BHARATHIYAR 5TH CROSS STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28411,Roads,Completed,NH-ANNA NAGAR,108,580000,"LAYING CEMENT CONCRETE ROAD WITH DURAISAMI RAJA STREET( From chinage 0.00m to 100m) IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28412,Roads,Completed,NH-ANNA NAGAR,108,355000,"IMPROVEMENTS TO THE CARRIAGE WAY @ NEHRU STREET(PART) CHOOLAIMDEU IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28413,Roads,Completed,NH-ANNA NAGAR,108,620000,"RASING TO THE ROAD @ SAMYAPURATHUAMMAN STREET (FLOOD DAMAGE) IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28414,Roads,Completed,NH-ANNA NAGAR,108,890000,"LAYING CEMENT CONCRETE FOR WIDENING PORTION AT ANDAVAR STREET (NORTHERN SIDE) IN DN-108,U-22.Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/28415,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Painting works to CGHSS(south block - inner side) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/28416,Roads,Completed,NH-ANNA NAGAR,108,890000,"LAYING CEMENT CONCRETE FOR WIDENING PORTION AT ANDAVAR STREET (SOUTHERN SIDE) IN DN-108,U-22,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/28417,Roads,Completed,NH-ANNA NAGAR,108,685000,"IMPROVEMENTS TO THE STROM WATER DRAIN AT ANDAVAR STREET IN DIVISION-108, UNIT22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28575,Parks,Completed,NH-ANNA NAGAR,100,985000,"IMPROVEMENTS TO THE GYM BUILDING AT 7TH MAIN ROAD (WEST) IN DIVISION -100,UNIT-22,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/28615,Buildings,Completed,NH-ANNA NAGAR,100,759000,"PROVIDING GYM EQUIPMENTS AND COMPOUND FENCING AT 7th MAIN ROAD GYM IN DIVISION -100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28619,Buildings,Completed,NH-ANNA NAGAR,104,973000,IMPROVEMENT WORKS TO CHENNAI MIDDLE SCHOOL AT VELLALA STREET IN DN-104 UNIT-23 ZONE -8,Own Sources,8,2015-16,2016-17 NH/2015-16/28621,Buildings,Completed,NH-ANNA NAGAR,104,170000,"LETTER WRITTING IN VARIOUS STREET AND PLACE IN DIV 104, UNIT - 23 , ZONE - 8",Own Sources,8,2015-16,2016-17 NH/2015-16/28648,Buildings,Completed,NH-ANNA NAGAR,101,430000,"PROVIDING NORTHERN SIDE GATE AND FENCING AT AMMA ARANGAM IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/28718,Footpath,Completed,NH-ANNA NAGAR,95,397000,"PROPOSED TO FLOOD DAMAGED FOOTPATH WORK (EASTERN SIDE) AT 21ST MAIN ROAD IN DN-95, U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/28719,Footpath,Completed,NH-ANNA NAGAR,95,459000,IMPROVEMENTS TO FLOOD DAMAGED ROAD FOOT PATH AT THIRUVALLUVAR KUDIERUPU FROM 6TH AVENUE TO I BLOCK 21ST STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/28721,Footpath,Completed,NH-ANNA NAGAR,95,452000,IMPROVEMENTS TO FLOOD DAMAGED ROAD FOOT PATH AT I BLOCK 1ST STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/28724,Storm Water Drain,Completed,NH-ANNA NAGAR,101,35000,"CONSTRUCTION OF INSPECTION CHAMBER AT VARIOUS STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/28733,Buildings,Completed,NH-ANNA NAGAR,95,917000,"IMPROVEMENTS TO EXISTING SWD IN VIJAYALAKSHMIPURAM FROM THANTHONIYAMMAN KOIL 3RD STREET EXTN TO THANTHONIYAMMAN KOIL 1ST STREET EXTN DOOR NO 12/1 IN DN - 95, UNIT - 21, ZONE - 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28735,Buildings,Completed,NH-ANNA NAGAR,95,924000,"IMPROVEMENTS TO EXISTING SWD IN VIJAYALAKSHMIPURAM FROM THANTHONIYAMMAN KOIL 1ST STREET EXTN DOOR NO 12/1 TO THANTHONIYAMMAN KOIL 1ST MAIN ROAD DOOR NO 7/7 IN DN - 95, UNIT - 21, ZONE - 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28737,Roads,Completed,NH-ANNA NAGAR,95,385000,"Relaying the road with camber correction by paver finisher at South Thirumalai Nagar Main Road in Dn.95, Unit 21, Zone 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28741,Roads,Completed,NH-ANNA NAGAR,95,347000,"RELAYING THE ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT SOUTH THIRUMALAI NAGAR 2ND STREET IN DN.95, UNIT 21, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/28837,Buildings,Completed,NH-ANNA NAGAR,101,998000,"CONSTRUCTION OF TOILET BLOCK AND SUMP AT VELANGADU CREMANTORIUM IN DN-101,U-22,Z-08 (swachh bharat scheme)",Own Sources,8,2015-16,2017-18 NH/2015-16/28862,Roads,Completed,NH-ANNA NAGAR,101,177000,"PAINTING WORK IN DISPENSARY AT BHARATHIPURAM 4TH STREET ( flood damaged ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/28877,Buildings,Completed,NH-ANNA NAGAR,94,398000,"IMPROVEMENT WATER ARRANGEMENT AND ELECTRICAL WORK IN DIVISION OFFICE, AT NORTH MADA STREET DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/29048,Storm Water Drain,Completed,NH-ANNA NAGAR,103,999000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT T.P .CHATHIRAM MAIN ROAD FROM D.NO:38 TO CHAINAGE 140m IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29111,Roads,Completed,NH-ANNA NAGAR,101,990000,"DEMOLITION AND RE-CONSTRUCTION OF STORM WATER DRAIN AT ANNA NAGAR 3RD AVENUE ( CHAINAGE FROM 150M TO 200M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/29112,Storm Water Drain,Completed,NH-ANNA NAGAR,101,985000,"DEMOLITION AND RE-CONSTRUCTION OF STORM WATER DRAIN AT ANNA NAGAR 3RD AVENUE ( CHAINAGE FROM 200M TO 250M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/29114,Roads,Completed,NH-ANNA NAGAR,101,990000,"DEMOLITION AND RE-CONSTRUCTION OF STORM WATER DRAIN AT ANNA NAGAR 3RD AVENUE ( CHAINAGE FROM 250M TO300M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/29115,Roads,Completed,NH-ANNA NAGAR,101,990000,"DEMOLITION AND RE-CONSTRUCTION OF STORM WATER DRAIN AT ANNA NAGAR 3RD AVENUE ( CHAINAGE FROM 300M TO350M ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/29138,Parks,Completed,NH-ANNA NAGAR,95,395000,"ANNUAL MAINTENANCE OF PARK AT THIRU NAGAR PARK (ONE YEAR) IN DN.95,UNIT-21,ZONE-8.(By Employed Qualified Horticulturist Only)..",Own Sources,8,2015-16,2018-19 NH/2015-16/29139,Parks,Completed,NH-ANNA NAGAR,95,385000,"Annual Maintenance of Park at W Block C Sector 2nd street Park (Two years) in Dn.95,Unit-21,Zone-8.(By Employed Qualified Horticulturist only).",Own Sources,8,2015-16,2017-18 NH/2015-16/29140,Footpath,Completed,NH-ANNA NAGAR,95,450000,IMPROVEMENTS TO FLOOD DAMAGED ROAD FOOT PATH AT I BLOCK 5TH STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/29141,Footpath,Completed,NH-ANNA NAGAR,95,450000,IMPROVEMENTS TO FLOOD DAMAGED ROAD FOOT PATH AT THIRUVALLUVAR KUDIERUPU FROM 18TH MAIN ROAD TO I BLOCK 21ST STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/29142,Buildings,Completed,NH-ANNA NAGAR,99,288000,PROVIDING AND LAYING SHAHABAD STONE FLOORING AND WEATHERING COARSE IN CHENNAI ELEMENTARY SCHOOL AT THILLAYADI VALLIYAMMAI NAGAR (PILLAYAR KOVIL STREET) IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/29143,Parks,Completed,NH-ANNA NAGAR,99,390000,"PROVIDING ELECTRIFICATION AND FACE LIFTING TO THE CI BUILDING AT H BLOCK 15th STREET PARK IN DN .99,UNIT-21,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/29211,Roads,Completed,NH-ANNA NAGAR,103,438000,"PROVIDING CONCRETE FLAT FROM INSIDE DIVISION OFFICE CUMPUS AT TEMPLE STREET(EASTEN SIDE) IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29217,Roads,Completed,NH-ANNA NAGAR,106,850000,"STRENGTHENING AND RELAYING THE ROAD BY RMC 30 AT MADHA KOIL STREET(FROM 0M T0 150M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/29333,Parks,Completed,NH-ANNA NAGAR,97,366000,"PROVIDING PLAY APPARATUS IN PARK AT VELLALA STREET IN DN-97, UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/29345,Buildings,Completed,NH-ANNA NAGAR,103,438000,"PROVIDING CONCRETE FLAT FROM INSIDE DIVISION OFFICE CUMPUS AT TEMPLE STREET(WESTEN SIDE) IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29352,Buildings,Completed,NH-ANNA NAGAR,103,473700,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT VALLIAMMAL STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29354,Storm Water Drain,Completed,NH-ANNA NAGAR,103,999000,"IMPROVEMENT TO FOOT PATH AT ORMES ROAD IN FRONT OF BAIN SCHOOL (FROM KELLYS ROAD JN) CHAINAGE (150m -300m) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/29355,Storm Water Drain,Completed,NH-ANNA NAGAR,103,991000,"IMPROVEMENT TO FOOT PATH AT ORMES ROAD IN FRONT OF BAIN SCHOOL IN DN-103,U-23,Z-8. (CHAINAGE OM-150m)",Own Sources,8,2015-16,2017-18 NH/2015-16/29356,Footpath,Completed,NH-ANNA NAGAR,103,952000,"IMPROVEMENT AND REPAIR OF FOOT PATH AND STORM WATER DRAIN ALONG SILVAN LODGE COLONY 1ST STREET,SILVAN LODGE COLONY 2ND STREET AND SILVAN LODGE 3RD STREET IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29361,Footpath,Completed,NH-ANNA NAGAR,103,999000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT KELLYS ROAD IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29368,Footpath,Completed,NH-ANNA NAGAR,103,998000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT THAMBUSAMY ROAD AND WADDELS ROAD IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29396,Footpath,Completed,NH-ANNA NAGAR,101,600000,"REPAIR AND IMPROVEMENT TO FOOT PATH & SWD AT ANNA NAGAR 2ND MAIN ROAD WESTERN SIDE ALL ROAD JUNCTIONS IN DN-101 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/29400,Storm Water Drain,Completed,NH-ANNA NAGAR,97,980000,"REPAIRS, DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN ALONG BHATTACHARY STREET FROM N.M.K.STREET TO DOOR NO. 34 / 23 (REACH I) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2017-18 NH/2015-16/29405,Storm Water Drain,Completed,NH-ANNA NAGAR,97,996000,"REPAIRS, DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN ALONG SOLAIAMMAN KOIL STREET FROM MUTHAMMAN KOIL STREET TO DOOR NO. 25 / 7A (REACH I) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/29407,Roads,Completed,NH-ANNA NAGAR,106,999000,"STRENGTHENING AND RELAYING THE ROAD BY RMC 30 AT AMMAN KOIL STREET IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/29420,Roads,Completed,NH-ANNA NAGAR,106,690000,"STRENGTHENING AND RELAYING THE ROAD BY RMC 30 AT MADHA KOIL STREET(FROM 150M T0 255M) IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/29454,Roads,Completed,NH-ANNA NAGAR,97,207000,"PATCH WORK OF CC ROAD AT KULAKKARAI STREET IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/29465,Footpath,Completed,NH-ANNA NAGAR,103,998000,"IMPROVEMENTS TO THE EXISTING FOOTPATH & CENTRE MEDIAN AT KILPAUK GARDEN ROAD IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29549,Roads,Completed,NH-ANNA NAGAR,106,999000,PROVIDING NEW SPEED BREAKS BY PAVER FINISHER AT VARIOUS STREET IN DN - 106 UNIT - 22 ZONE - 8,Own Sources,8,2015-16,2016-17 NH/2015-16/29621,Roads,Completed,NH-ANNA NAGAR,94,880000,Annual Maintenances Of Villivakkam Sub Way Engaging of Watch man and Electrician For One Year in division-94. Unit-21. Zone-8.,Own Sources,8,2015-16,2017-18 NH/2015-16/29761,Buildings,Completed,NH-ANNA NAGAR,95,950000,"IMPROVEMENT TO THIRUNAGAR PARK IN DN-95, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/29821,Buildings,Completed,NH-ANNA NAGAR,101,2082000,"PROPOSED CONSTRUCTION OF NNMP SHED CENTER NO:33603050217 AT N BLOCK 24TH STREET IN DN 101,UNIT 22,ZONE VIII (MLA FUND 2015-2016)",MLACDS,8,2015-16,2016-17 NH/2015-16/29890,Storm Water Drain,Completed,NH-ANNA NAGAR,97,45000,"IMPROVEMENT TO ROAD CUT PRE CAST SLAB AT NMK STREET IN DN-97, U-21, Z-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/29892,Roads,Completed,NH-ANNA NAGAR,97,880000,"ATTENDING BT PATCH WORK AT CHETTY STREET (FLOOD DAMAGED ROAD) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/29893,Roads,Completed,NH-ANNA NAGAR,97,1090000,"ATTENDING BT PATCH WORK AT THANTHAI PERIYAR NAGAR 1ST STREET (FLOOD DAMAGED ROAD) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/29926,Footpath,Completed,NH-ANNA NAGAR,95,398000,"PROPOSED TO FLOOD DAMAGED FOOTPATH WORK (WESTERN SIDE) AT 21ST MAIN ROAD IN DN-95, U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/29927,Buildings,Completed,NH-ANNA NAGAR,95,931000,"IMPROVEMENT TO STORM WATER DRAIN ALONG 20TH MAIN ROAD FROM 18TH MAIN ROAD TO DOOR NO-1222. IN DN-95, UNIT-21,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29929,Buildings,Completed,NH-ANNA NAGAR,95,953000,"IMPROVEMENT TO STORM WATER DRAIN ALONG 20TH MAIN ROAD FROM DOOR NO-1222 TO DOOR NO-1216. IN DN-95, UNIT-21,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29931,Buildings,Completed,NH-ANNA NAGAR,95,965000,"IMPROVEMENT TO STORM WATER DRAIN ALONG 20TH MAIN ROAD DOOR NO-1216 TO ICF CANNAL. IN DN-95, UNIT-21,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29953,Buildings,Completed,NH-ANNA NAGAR,103,251000,"REPAIR AND IMPROVEMENTS TO THE FLOORING AND ELECTRICAL FITTINGS AT WARD COUNCILLORS ROOM IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/29955,Buildings,Completed,NH-ANNA NAGAR,102,990000,"Improvements to the Chennai Middle School at Gujji Main Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/29967,Playfields,Completed,NH-ANNA NAGAR,102,995000,"Providing Ro plant and water supply arrangement to JJ Indoor stadium at Playground street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/30027,Footpath,Completed,NH-ANNA NAGAR,102,998000,"Forming footpath at D Block 8th Street south side (from jn of Rv Nagar Main road to D Block 5th Street) and R.V.Nagar Main Road west side(from jn of Mahatma Gandhi Road to D Block 8th Street) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30030,Parks,Completed,NH-ANNA NAGAR,102,990000,"Laying Rmc in skating court at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30034,Footpath,Completed,NH-ANNA NAGAR,102,880000,"Forming footpath at D Block 8th Street (from jn of Second avenue road extension to D Block 5th Street) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30036,Parks,Completed,NH-ANNA NAGAR,102,997000,"Raising the existing skating court at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30089,Buildings,Completed,NH-ANNA NAGAR,101,1500000,"PROPOSED CONSTRUCTION OF WATER PURIFIER SYSTEM 2NOS AT CREASENT GROUND IN DN 101,U-22,Z-08 ( MLA FUND 2015-2016)",MLACDS,8,2015-16,2016-17 NH/2015-16/30165,Buildings,Completed,NH-ANNA NAGAR,107,285000,IMPROVEMENT TO INTERIOR AND DAMODHARAN STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/30176,Roads,Completed,NH-ANNA NAGAR,107,495000,IMPROVEMENT TO INTERIOR ROAD VENKATASAMY STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/30192,Roads,Completed,NH-ANNA NAGAR,96,999000,"LAYING CEMENT CONCRETE ROAD AT K. H. ROAD LANE IN DN.96, UNIT-21, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30193,Roads,Completed,NH-ANNA NAGAR,107,578000,IMPROVEMENT TO INTERIOR ROAD DHANAMMAL STREET IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/30194,Roads,Completed,NH-ANNA NAGAR,96,407000,"LAYING CEMENT CONCRETE ROAD AT K. H. ROAD 4TH LANE IN DN.96, UNIT-21, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30195,Roads,Completed,NH-ANNA NAGAR,96,999000,"LAYING CEMENT CONCRETE ROAD AT K. H. ROAD 5TH LANE IN DN.96, UNIT-21, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30196,Footpath,Completed,NH-ANNA NAGAR,96,930000,"RELAYING OF CEMENT CONCRETE ROAD AT DURAISAMY STREET IN DN-96,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/30203,Roads,Completed,NH-ANNA NAGAR,107,798000,IMPROVEMENT TO INTERIOR ROAD MUKTHA GARDEN IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/30219,Roads,Completed,NH-ANNA NAGAR,107,590000,IMPROVEMENT TO INTERIOR ROAD ARANGANATHAPURAM IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/30225,Roads,Completed,NH-ANNA NAGAR,107,597000,IMPROVEMENT TO INTERIOR ROAD VIVEKANANDA STREET IN DIN-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/30229,Roads,Completed,NH-ANNA NAGAR,105,949000,"Relaying the road at Thiruveethiamman Koil Street in Div -105, Unit -22, Zone -8.",Own Sources,8,2015-16,2017-18 NH/2015-16/30252,Buildings,Completed,NH-ANNA NAGAR,103,181500,"Providing Water Supply and Electrical Work at Amma Unavagam at Poonemalle High Road (Old Zonal Office) in Dn-103, U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30253,Buildings,Completed,NH-ANNA NAGAR,103,119500,"Providing Water Supply Arrangements at Bashyam Park at Halls Road Junction of Taylors Road in Dn-103, U-23, Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30254,Buildings,Completed,NH-ANNA NAGAR,103,216000,"Repairs and Improvements to Night Shelter at Semmanpettai in Dn-103, U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30255,Buildings,Completed,NH-ANNA NAGAR,103,16400,"Repairs to P.C at Semmanpettai in Dn-103, U-23, Z-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/30256,Buildings,Completed,NH-ANNA NAGAR,103,13800,"Repairs to Bore at KELLYS ROAD Ration Shop in Dn:103, U:23, Z:VIII",Own Sources,8,2015-16,2017-18 NH/2015-16/30257,Buildings,Completed,NH-ANNA NAGAR,103,21000,"Repairs and Improvements to Park at Prof.Subramaniyam Street in Dn-103, U-23, Z-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/30258,Buildings,Completed,NH-ANNA NAGAR,103,26700,"Improvements to PC at Valliammal Street, Kamarajar Nagar in Dn:103, U:23, Z:VIII",Own Sources,8,2015-16,2017-18 NH/2015-16/30259,Buildings,Completed,NH-ANNA NAGAR,103,116000,"Providing Water Supply at Road Side Park at PH Road Near HDFC Bank in Dn:103, U:23, Z:VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/30278,Storm Water Drain,Completed,NH-ANNA NAGAR,97,736000,"REPAIRS, DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN ALONG PALANI ANDAVAR KOIL STREET (FROM DOOR NO. 30/2 TO DOOR NO. 224/117) IN DN-97, U-21, Z-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/30279,Storm Water Drain,Completed,NH-ANNA NAGAR,97,604000,"REPAIRS, DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN ALONG ELUMALAI STREET (FROM DOOR NO. 126/147 TO DOOR NO. 30/2) IN DN-97, U-21, Z-VIII",Own Sources,8,2015-16,2017-18 NH/2015-16/30331,Footpath,Completed,NH-ANNA NAGAR,107,849000,IMPROVEMENT TO FOOT PATH MAYOR SATHYMOORTHY SALAI(MAYOR RAMANATHAN TO T.V.NAIR ) IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/30378,Buildings,Completed,NH-ANNA NAGAR,106,122000,"REPAIRS WORKS AT AMMAN KOIL PC,LIME KILN STREET PC,VELLALA STREET PC,PERUMAL KOIL STREET PC IN DN106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30394,Buildings,Completed,NH-ANNA NAGAR,106,70000,"REPAIRS AND IMPROVEMENTS WORKS IN STORM WATER DRAIN AT NORTH KASARATH THOTTAM IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30397,Parks,Completed,NH-ANNA NAGAR,101,985000,"FORMING PARK INSIDE VELANGADU CREMANTORIUM( WESTERN SIDE ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/30399,Parks,Completed,NH-ANNA NAGAR,101,995000,"PROVIDING FOOTPATH, CHAINLINK FENCING AT VELANGADU CREMANTORIUM (NEAR BIO METHANATION PLANT) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/30400,Parks,Completed,NH-ANNA NAGAR,106,38000,"REPAIRS WORKS AT METAL FACTORY PARK IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30403,Buildings,Completed,NH-ANNA NAGAR,106,122000,"REPAIRS AND IMPROVEMENTS TO PLAY GROUND AT COLLECTOR COLONY IN DN-106,UNIT-22,Z-08. DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30409,Roads,Completed,NH-ANNA NAGAR,101,544000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD BY PAVER FNISHER AT E-BLOCK 1ST STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/30415,Roads,Completed,NH-ANNA NAGAR,94,45000,"PROVIDING MS SHEET DOOR, TABLE AND CHAIR IN DIVSION OFFICE AND AMMA UNAVAGAM IN DN 94 ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30418,Roads,Completed,NH-ANNA NAGAR,101,831000,"ATTENDING PATCH WORK TO FLOOD DAMAGED ROAD BY PAVER FNISHER AT SHENOY NAGAR WEST 3RD MAIN ROAD IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/3044,Buildings,Completed,NH-ANNA NAGAR,108,995000,"CONSTRUCTION OF ADDITIONAL CLASS ROOM FIRST FLOOR AT O-BLOCK CHENNAI PRIMARY SCHOOL @ BHAGATH SINGH 2ND STREET IN DIVISION-108, UNIT-22, ZONE-8.(ANNA NAGAR MLA FUNDS FOR THE YEAR 2014 - 2015)",MLACDS,8,2015-16,2016-17 NH/2015-16/30460,Parks,Completed,NH-ANNA NAGAR,99,1242000,"ATTENDING FLOOD, BT PATCH WORK @ H-BLOCK-2,4,5 STREETS (FLOOD DAMAGED ROADS) IN DN 99, UNIT -21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30461,Parks,Completed,NH-ANNA NAGAR,99,367000,"MAINTENANCE OF PARK AT 15TH MAIN ROAD PARK (SIX MONTHS) IN DIVISION 99,UNIT -21,ZONE-08.(BY EMPLOYED QUALIFIED HORTICULTURIST ONLY)",Own Sources,8,2015-16,2018-19 NH/2015-16/30463,Roads,Completed,NH-ANNA NAGAR,99,1040000,"ATTENDING PATCH WORK FLOOD DAMAGED ROAD AT FROM 2ND AVENUE TO 11TH MAIN ROAD, 5TH STREET AND 2ND STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30464,Parks,Completed,NH-ANNA NAGAR,99,996000,"ATTENDING FLOOD, PATCHES ROAD AT H-BLOCK 3, 6 AND BELLY AREA STREET - IN DN 99,UNIT -21,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30523,Roads,Completed,NH-ANNA NAGAR,99,850000,"ATTENDING PATCH WORK FLOOD DAMAGED ROAD AT FROM 17TH MAIN ROAD TO THIRUMOOLAR COLONY AMMAN KOIL STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30526,Footpath,Completed,NH-ANNA NAGAR,99,1670000,"ATTENDING PATCH WORK FLOOD DAMAGED ROAD AT FROM 2ND AVENUE TO 12TH MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30527,Roads,Completed,NH-ANNA NAGAR,99,1090000,"ATTENDING PATCH WORK FLOOD DAMAGED ROAD AT FROM 12TH MAIN ROAD TO AF ? BLOCK 8TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30579,Buildings,Completed,NH-ANNA NAGAR,107,986000,"IMPROVEMENTS TO FOOT PATH AT MAYOR SATHYAMOORTHY SALAI NEAR DIVISION OFFICE IN DN - 107, UNIT - 23, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30584,Roads,Completed,NH-ANNA NAGAR,100,998000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT Z-BLOCK 1st STREET IN DIV-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30596,Buildings,Completed,NH-ANNA NAGAR,103,83000,"Providing Water Supply Arrangements to PC at Rani Anna Nagar in Dn:103, U:23, Z:VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/30597,Buildings,Completed,NH-ANNA NAGAR,103,113000,"Providing Water Supply Arrangements at Amma Unavagam inside of KMC Hospital in Dn:103, U:23, Z:VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/30598,Buildings,Completed,NH-ANNA NAGAR,103,164000,"Improvements to Chappathi Centre at HALLS Lane in Dn-103, Unit-23,Zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30599,Buildings,Completed,NH-ANNA NAGAR,103,35200,"Repairs and improvement to Division Office in Dn-103, Unit-23, Zone-8",Own Sources,8,2015-16,2017-18 NH/2015-16/30640,Storm Water Drain,Completed,NH-ANNA NAGAR,101,586000,"CONSTRUCTION OF SWD AT JAYALAKSHMI COLONY( REACH FROM 2ND MAIN ROAD TO DOOR NO 29/1) IN DN-101,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30643,Storm Water Drain,Completed,NH-ANNA NAGAR,101,590000,"REPAIR AND IMPROVEMENT TO SWD AT JAYALAKSHMI COLONY( REACH FROM DOOR NO.29/1 T0 DOOR NO. 2/3 ) IN DN-101,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30673,Buildings,Completed,NH-ANNA NAGAR,95,998000,"IMPROVEMENT TO THIRUNAGAR GYM EQUPMENTS IN DN-95, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30679,Roads,Completed,NH-ANNA NAGAR,100,997000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 14th MAIN ROAD (FROM JN OF 11TH MAIN ROAD TO DOOR NO-AL-213) IN DIV-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30684,Roads,Completed,NH-ANNA NAGAR,100,997000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 14th MAIN ROAD (FROM JN OF DOOR NO-AL-213 TO AL-222) IN DIV-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30686,Roads,Completed,NH-ANNA NAGAR,100,997000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AB BLOCK 5th STREET (FROM JN OF 3rd MAIN ROAD TO DOOR NO-AB-38) IN DIV-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30689,Roads,Completed,NH-ANNA NAGAR,100,970000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AB BLOCK 5th STREET (FROM JN OF DOOR NO-AB-38 TO 6th MAIN ROAD ) IN DIV-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30722,Buildings,Completed,NH-ANNA NAGAR,96,609000,"PROVIDING BARICADING AROUND TRANSFORMER AT VARIOUS STREET IN DN-96,U-21,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30757,Buildings,Completed,NH-ANNA NAGAR,99,397000,"PROVIDING ALUMINIUM PARTITION AND SS HANDRAIL TO THE CI BUILDING AT H BLOCK 15TH STREET PARK IN DN-99,UNIT-21,ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/30759,Storm Water Drain,Completed,NH-ANNA NAGAR,97,453000,"REPAIRS, DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN ALONG DURAISWAMY STREET (FROM DOOR NO. 23A/40 TO DOOR NO. 7/1) IN DN-97, U-21, Z-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/30761,Buildings,Completed,NH-ANNA NAGAR,99,998000,"CONSTRUCTION OF SUMP, ELECTRICAL AND WATER SUPPLY ARRANGEMENTS TO CHENNAI PRIMARY SCHOOL AT THILLAYADI VALLIYAMMAI NAGAR (PILLAYAR KOIL STREET) IN DN 99 UNIT 21 ZONE 08",Own Sources,8,2015-16,2016-17 NH/2015-16/30764,Parks,Completed,NH-ANNA NAGAR,106,998000,"REPAIRS AND IMPROVEMENTS WORKS IN PLAY GROUND AT COLLECTORATE COLONY MAIN ROAD IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/30798,Buildings,Completed,NH-ANNA NAGAR,95,986000,"IMPROVEMENT TO SWD DRAIN AND DEMOLISHING THE OLD DRAIN TOP SLAB AND RAISING THE CC WALL ALONG THANTHONRIAMMAN KOVIL STREET FROM WELCOME COLONY LANE TO DOOR NO-24. IN DN-95, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30799,Buildings,Completed,NH-ANNA NAGAR,95,960000,"IMPROVEMENT TO SWD DRAIN AND DEMOLISHING THE OLD DRAIN TOP SLAB AND RAISING THE CC WALL ALONG THANTHONRIAMMAN KOVIL STREET FROM DOOR NO-24 TO JOHN WILLIAMS MATRIC SCHOOL. IN DN-95, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30800,Buildings,Completed,NH-ANNA NAGAR,95,973000,"IMPROVEMENT TO SWD DRAIN AND DEMOLISHING THE OLD DRAIN TOP SLAB AND RAISING THE CC WALL ALONG THANTHONRIAMMAN KOVIL STREET FROM JOHN WILLIAMS MATRIC SCHOOL TO MTH ROAD. IN DN-95, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30876,Roads,Completed,NH-ANNA NAGAR,99,1340000,"ATTENDING PATCH WORK FLOOD DAMAGED ROAD AT G-BLOCK 7TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/30919,Buildings,Completed,NH-ANNA NAGAR,108,127000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE SSS TOILET @ O BLOCK MAIN ROAD IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30923,Buildings,Completed,NH-ANNA NAGAR,108,127000,"REPAIRS AND IMPROVEMENTS TO GROUP BIN @ WATER TANK ROAD IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/30976,Roads,Completed,NH-ANNA NAGAR,105,998000,"Providing Street name board at various streets in dn-105, unit-22, zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/31014,Buildings,Completed,NH-ANNA NAGAR,104,128000,PAINTING AND IMPROVEMENT WORKS TO AMMA UNAVAGAM AT SUNDARAM LANE IN DN-104 UNIT-23 ZONE -8,Own Sources,8,2015-16,2016-17 NH/2015-16/31114,Parks,Completed,NH-ANNA NAGAR,97,808000,"MAINTENANCE OF VELLALA STREET PARK IN DN-97, UNIT-21, ZONE-8.(2-YEAR)",Own Sources,8,2015-16,2018-19 NH/2015-16/31115,Parks,Completed,NH-ANNA NAGAR,97,684000,"MAINTENANCE OF PACHEIKAL VEERASAMY STREET PARK IN DN-97, UNIT-21, ZONE-8. (2-YEAR)",Own Sources,8,2015-16,2018-19 NH/2015-16/31143,Buildings,Completed,NH-ANNA NAGAR,99,240000,IMPROVEMENTS TO KITCHEN SHED IN CHENNAI PRIMARY SCHOOL AT THILLAYADI VALLIYAMMAI NAGAR (PILLAYAR KOIL STREET )IN DIVISION 99 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/31148,Buildings,Completed,NH-ANNA NAGAR,99,270000,IMPROVEMENTS TO TOILET ROOMS IN CHENNAI PRIMARY SCHOOL AT THILLAYADI VALLIYAMMAI NAGAR (PILLAYAR KOIL STREET )IN DIVISION 99 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/3132,Roads,Completed,NH-ANNA NAGAR,105,600000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT THIRUVEETH AMMAN KOIL 5TH LANE, 6TH LANE AND PERUMAL KOIL GARDEN 2ND LANE IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31361,Playfields,Completed,NH-ANNA NAGAR,100,542000,"PROVIDING GYM EQUIPMENTS AT N.S.K NAGAR 3rd STREET IN DIVISION -100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31363,Roads,Completed,NH-ANNA NAGAR,100,985000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AB-BLOCK 1st STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31364,Roads,Completed,NH-ANNA NAGAR,100,823000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AB-BLOCK 4th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31365,Roads,Completed,NH-ANNA NAGAR,100,740000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AI-BLOCK 1st STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31366,Roads,Completed,NH-ANNA NAGAR,100,992000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AJ-BLOCK 1st STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31367,Roads,Completed,NH-ANNA NAGAR,100,992000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AJ-BLOCK 2nd STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31368,Roads,Completed,NH-ANNA NAGAR,100,999000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT Y-BLOCK 5th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31369,Roads,Completed,NH-ANNA NAGAR,100,999000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AH BLOCK 4th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31370,Roads,Completed,NH-ANNA NAGAR,100,984000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 3rd MAIN ROAD (FROM JN OF 4th MAIN ROAD TO DOOR NO- R-95) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31390,Roads,Completed,NH-ANNA NAGAR,100,984000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 3rd MAIN ROAD (FROM JN OF DOOR NO- U-89B TO DOOR NO- U-94) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31391,Roads,Completed,NH-ANNA NAGAR,100,984000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 3rd MAIN ROAD (FROM JN OF 2nd AVENUE TO DOOR NO-W-55) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31392,Roads,Completed,NH-ANNA NAGAR,100,984000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 3rd MAIN ROAD (FROM JN OF DOOR NO-W-55 TO X-BLOCK 5th STREET) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31393,Roads,Completed,NH-ANNA NAGAR,100,953000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/31394,Roads,Completed,NH-ANNA NAGAR,100,560000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AE-BLOCK 6th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31403,Buildings,Completed,NH-ANNA NAGAR,103,507000,"REPAIR AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT RANI ANNA NAGAR IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31415,Roads,Completed,NH-ANNA NAGAR,96,995000,"LAYING CEMENT CONCRETE ROAD AT PONNU SAMY LANE IN DN-96, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31419,Roads,Completed,NH-ANNA NAGAR,96,998000,"LAYING CEMENT CONCRETE ROAD AT PONNU SAMY STREET IN DN-96,. UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31423,Roads,Completed,NH-ANNA NAGAR,96,815000,"LAYING CEMENT CONCRETE ROAD AT CHETTY THOTTAM LANE IN DN.-96, UNIT-21, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/31465,Roads,Completed,NH-ANNA NAGAR,95,54000,"SUPPLYING AND FIXING NAME BOARD FOR TACTV CENTRE IN WARD OFFICE AT I-BLOCK 16TH STREET IN DN-95, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/31467,Buildings,Completed,NH-ANNA NAGAR,95,375000,"REPAIR AND IMPROVEMENT TO ANGANWADI AT RAJIV GANDHI STREET IN DN-95,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/31502,Buildings,Completed,NH-ANNA NAGAR,103,750000,"PROVIDING PERCOLATION PITS AT T.P.CHATHIRAM IN DN-103,Unit-23,Zone-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/31663,Storm Water Drain,Completed,NH-ANNA NAGAR,98,960000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREETS IN DN-98,U-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/31712,Buildings,Completed,NH-ANNA NAGAR,101,900000,"CONSTRUCTION OF TOILET BLOCK AT LORRY STATION IN DN-101,U-22,Z-08(swachh bharat scheme)",Own Sources,8,2015-16,2017-18 NH/2015-16/31782,Roads,Completed,NH-ANNA NAGAR,94,864000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT MOPPLIAMMAN KOIL STREET) IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/31797,Storm Water Drain,Completed,NH-ANNA NAGAR,98,998000,"REPAIR AND IMPROVEMENT TO SWD AT RAJI STREET FROM RAJI STREET TO AYANAVARAM ROAD IN DN-98,U-23,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/31799,Storm Water Drain,Completed,NH-ANNA NAGAR,98,996000,"DISMALTING TOP SLAB AND RE-CONSTRUCTION OF SWD AT PUDHU NAGAR ( CHAINAGE FROM 0M TO 110M ) IN DN-98 ,U-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/31928,Storm Water Drain,Completed,NH-ANNA NAGAR,103,991000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT T.P .CHATHIRAM MAIN ROAD FROM CHAINAGE 140m TO 280m IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/32091,Roads,Completed,NH-ANNA NAGAR,105,999000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE CONCRETE AT KAVITHA LANE AND ELANGO ADIGAL STREET IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/32092,Roads,Completed,NH-ANNA NAGAR,105,999900,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE CONCRETE AT ANNA STREET IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/32183,Buildings,Completed,NH-ANNA NAGAR,102,997000,"Improvements to CGHSS (south block - Ground floor) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/32184,Buildings,Completed,NH-ANNA NAGAR,102,996000,"Providing PVC doors and electrical arrangements at CGHSS (South side block) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32185,Buildings,Completed,NH-ANNA NAGAR,102,820000,"Improvements to CGHSS (North side block - Near RO plant) at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/32186,Footpath,Completed,NH-ANNA NAGAR,102,998000,"Improvements to footpath at Mandapam Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32187,Buildings,Completed,NH-ANNA NAGAR,102,970000,"Improvements to footpath at New Avadi Road west side (from junction of Mandapam Road to Kilpauk water station) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32188,Buildings,Completed,NH-ANNA NAGAR,102,995000,"Improvements to footpath at New Avadi Road east side (from kilpauk water station, Ch 0m to Ch 85m) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32189,Footpath,Completed,NH-ANNA NAGAR,102,975000,"Improvements to footpath at New Avadi Road east side (from kilpauk water station, Ch 85m to Ch 160m) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32191,Storm Water Drain,Completed,NH-ANNA NAGAR,102,304000,"Improvements to the existing SWD at G Block 9th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/32201,Storm Water Drain,Completed,NH-ANNA NAGAR,102,280000,"Repairs to SWD at First Avenue Road(near bata showroom) and Second Avenue Road Extension in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32204,Roads,Completed,NH-ANNA NAGAR,102,920000,"LAYING OF CEMENT CONCRETE ROAD AT KUMARAN NAGAR 1 ST STREET & 2 ND STREET IN DN 102, UNIT 23, ZONE 8",Own Sources,8,2015-16,2017-18 NH/2015-16/32208,Roads,Completed,NH-ANNA NAGAR,102,800000,"Strengthening and Relaying of the Road with DBM 50mm and BC40mm after camber correction at Mandapam Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32210,Buildings,Completed,NH-ANNA NAGAR,102,990000,"Proposed Construction of Amma Kudineer Plant room at New Avadi Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32211,Buildings,Completed,NH-ANNA NAGAR,102,465000,"Providing water supply arrangements and name board at Zonal office 8 in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32212,Buildings,Completed,NH-ANNA NAGAR,102,870000,"Providing table for roof top dinning hall at Zonal office 8 in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2019-20 NH/2015-16/32274,Roads,Completed,NH-ANNA NAGAR,101,400000,"PROVIDING ELECTRICAL AND PLUMBLING WORK AT ELECTRICAL J.E ROOM AT AMMA ARANGAM IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2018-19 NH/2015-16/32277,Roads,Completed,NH-ANNA NAGAR,101,815000,"IMPROVEMENTS AND LAYING OF C C ROAD FROM BREWERY ROAD TO DOOR NO. 12A AT BREWERY ROAD EXTENTION LANE IN DN.101, UNIT-22,ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32279,Roads,Completed,NH-ANNA NAGAR,101,500000,"PROVIDING PIPELINE CONNECTION AT BREWERY ROAD( NEAR LORRY STATION) IN DN.101, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/32280,Roads,Completed,NH-ANNA NAGAR,101,865000,"IMPROVEMENTS AND LAYING OF C C ROAD FROM DOOR NO. 12A OF BREWERY ROAD EXTENTION LANE TO ANNA NAGAR A BLOCK 3RD STREET AT BREWERY ROAD EXTENTION LANE IN DN.101, UNIT-22, ZONE-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32282,Roads,Completed,NH-ANNA NAGAR,101,998000,"ROAD WIDENING AT E BLOCK 1A ( NEAR VALLIAMMAL COLLEGE ) IN DN-101 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32337,Storm Water Drain,Completed,NH-ANNA NAGAR,101,400000,"CONSTRUCTION OF COMPOUND WALL AT BHARATHIPURAM 3RD STREET(FROM EAST TO WEST ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/32340,Buildings,Completed,NH-ANNA NAGAR,101,400000,"CONSTRUCTION OF COMPOUND WALL AT BHARATHIPURAM 3RD STREET( FROM SOUTH TO NORTH ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/32356,Buildings,Completed,NH-ANNA NAGAR,103,24000,"Repairs to Bore well and Motor at Chennai Middle School , Thiyagappa Street in Dn:103, U:23, Z:VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/32417,Parks,Completed,NH-ANNA NAGAR,102,202000,"Improvements to children playground at L block 19th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/32421,Buildings,Completed,NH-ANNA NAGAR,102,180000,"Improvements to children playground at Big street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/32450,Storm Water Drain,Completed,NH-ANNA NAGAR,95,450000,"IMPROVEMENTS TO STORM WATER DRAIN ALONG VIJAYALAKSHMI PURAM FROM (TRANSFARMAR TO THANTHONDRI AMMAN KOVIL 1ST STREET IN DN-95, U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32455,Footpath,Completed,NH-ANNA NAGAR,95,440000,"FOOTPATH REPAIR WORKS IN NEW AVADI ROAD NORTH SIDE ( FROM SLAUGHTER HOUSE TO ICF SIGNAL ) IN DN-95, U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32461,Footpath,Completed,NH-ANNA NAGAR,95,398000,"PROVIDING OUTSIDE PHYSICAL FIT INSTRUMENT AT I-BLOCK 38TH STREET PARK IN DN-95,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32463,Footpath,Completed,NH-ANNA NAGAR,95,387000,"PROVIDING OUTSIDE PHYSICAL FIT INSTRUMENT AT W-BLOCK GANDHI PARK IN DN-95,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32464,Playfields,Completed,NH-ANNA NAGAR,95,365000,"PROVIDING OUTSIDE PHYSICAL FIT INSTRUMENT AT THIRU NAGAR IN DN-95,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32469,Roads,Completed,NH-ANNA NAGAR,95,140000,"PROPOSED FIXING OF MODERN URINALS AT JUNCTION OF 18TH MAIN ROAD AND 100FT ROAD IN DN-95,U-21,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/32476,Roads,Completed,NH-ANNA NAGAR,101,865000,"PROVIDING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT P.P THOOTAM IN DN-101,U-22,Z-8 (COUNCILLOR FUND 2015-16)",Own Sources,8,2015-16,2017-18 NH/2015-16/32477,Roads,Completed,NH-ANNA NAGAR,101,970000,"PROVIDING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT ANNAI SATHYA NAGAR IN DN-101,U-22,Z-8 (COUNCILLOR FUND 2015-16)",Own Sources,8,2015-16,2017-18 NH/2015-16/32479,Roads,Completed,NH-ANNA NAGAR,101,995000,"IMPROVEMENT TO BIOGAS PLANT AREA VACANT SPACE AT VELANGADU CREMANTORIUM IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/32481,Buildings,Completed,NH-ANNA NAGAR,101,400000,"CONSTRUCTION OF COMPOUND WALL & IMPROVEMENT TO NNMP SHED FLOOR AREA AT BHARATHIPURAM 3RD STREET ( FROM EAST TO WEST REACH -II ) IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/32490,Buildings,Completed,NH-ANNA NAGAR,96,266000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2015-16,2017-18 NH/2015-16/32499,Roads,Completed,NH-ANNA NAGAR,103,910000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KILPAUK GARDEN ROAD 1 ST STREET AND T.P.CHATHIRAM 2ND STREET IN DN-103,U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/32501,Roads,Completed,NH-ANNA NAGAR,103,940000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT HARLEYS LANE AND THIRU NARAYANA AVENUE IN DN-103,U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/32505,Roads,Completed,NH-ANNA NAGAR,103,960000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KILPAUK GARDEN ROAD(LANE) IN DN-103,U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/32515,Roads,Completed,NH-ANNA NAGAR,103,810000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT UMAYAL ROAD (CH 143 -286) IN DN-103,U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/32521,Roads,Completed,NH-ANNA NAGAR,105,786000,"Relaying The Road at Muthamiaz kavalar street in dn-105, unit-22, zone-8",Own Sources,8,2015-16,2017-18 NH/2015-16/32770,Roads,Completed,NH-ANNA NAGAR,97,239000,"ATTENDING CC ROAD PATCH WORK AT P.E.KOIL STREET LANE (NEAR P.E.KOIL WEST MADA STREET) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/32771,Roads,Completed,NH-ANNA NAGAR,97,157000,"ATTENDING CC ROAD PATCH WORK AT VELLALAR STREET LANE OPPOSITE ANNA STREET IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/32781,Storm Water Drain,Completed,NH-ANNA NAGAR,97,457000,"REPAIRS, DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN ALONG SOLAIAMMAN KOIL STREET FROM DOOR NO.25 / 7A TO VEERASAMY IST STREET JUNCTION (REACH II) IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/32787,Storm Water Drain,Completed,NH-ANNA NAGAR,97,999000,"DISMANTLING RCC ROOF, REPAIR AND DESILTING TO STORM WATER DRAIN ALONG MUTHAMMAN KOIL STREET FROM DOOR NO.128 / 67 TO THANTHAI PERIYAR NAGAR MAIN ROAD (REACH II) IN DN-97,U-21, Zone VIII.",Own Sources,8,2015-16,2016-17 NH/2015-16/32807,Roads,Completed,NH-ANNA NAGAR,104,340000,"PROVIDING SPEED BREAKERS AT LAWDERS GATE MAIN STREET AND VARIOUS STREETS IN DN-104, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/32837,Roads,Completed,NH-ANNA NAGAR,105,219000,"IMPROVEMENTS TO CHENNAI CORPORATION SCHOOL IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/32928,Parks,Completed,NH-ANNA NAGAR,95,315000,PROVIDING RAIN WATER HARVESTING WELL AT VARIOUS STREET IN DN 95 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/32929,Parks,Completed,NH-ANNA NAGAR,95,540000,"TREE PLANTING AT VARIOUS TREE IN DN.95 , UNIT 21, ZONE 08",Own Sources,8,2015-16,2016-17 NH/2015-16/32992,Storm Water Drain,Completed,NH-ANNA NAGAR,105,998000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT WATER TANK ROAD FROM JUNCTION OF RAZACK GARDEN ROAD TO CHAINAGE 49M ( TOWARDS WEST) IN DN:105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2019-20 NH/2015-16/32993,Storm Water Drain,Completed,NH-ANNA NAGAR,105,997000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT WATER TANK ROAD FROM JUNCTION OF RAZACK GARDEN ROAD CHAINAGE 49-103M ( TOWARDS WEST) IN DN:105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2019-20 NH/2015-16/33135,Roads,Completed,NH-ANNA NAGAR,100,425000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AB-BLOCK 2nd STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33136,Roads,Completed,NH-ANNA NAGAR,100,962000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 10th MAIN ROAD (JN AJ-BLOCK 5TH STREET TO 7th MAIN ROAD) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33137,Roads,Completed,NH-ANNA NAGAR,100,741000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 10th MAIN ROAD (JN OF SHANTHI COLONY 4th AVENUE TO AJ BLOCK 5th STREET ) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33138,Roads,Completed,NH-ANNA NAGAR,100,968000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 11th MAIN ROAD (JN OF SHANTHI COLONY 4th AVENUE TO DOOR NO: AK-17 ) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33139,Roads,Completed,NH-ANNA NAGAR,100,998000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 11th MAIN ROAD (JN OF DOOR NO:AK-17 TO DOOR NO: AK-49A ) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33142,Roads,Completed,NH-ANNA NAGAR,100,998000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT V-BLOCK 14th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33143,Roads,Completed,NH-ANNA NAGAR,100,999000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT X-BLOCK 5th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33144,Roads,Completed,NH-ANNA NAGAR,100,999000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT AK-BLOCK( 5th ,6th,7th,8th,9th )STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33145,Roads,Completed,NH-ANNA NAGAR,100,891000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT U-BLOCK(8th AND 9th) STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33146,Roads,Completed,NH-ANNA NAGAR,100,818000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 10th MAIN ROAD EXTENSION IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33148,Roads,Completed,NH-ANNA NAGAR,100,998000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT U-BLOCK 7th STREET IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33151,Roads,Completed,NH-ANNA NAGAR,100,174000,"IMPROVEMENTS OF STROM WATER DRAIN @ 5th AVENUE IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/33152,Storm Water Drain,Completed,NH-ANNA NAGAR,100,121000,"PROVIDING SILT CATCH PIT AT Y-BLOCK 6th STREET IN DIVISION-100. UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/33153,Buildings,Completed,NH-ANNA NAGAR,100,117000,"ATTENDING CEMENT CONCRETE PATCH AND MANHOLE DOOR AT VARIOUS STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/33171,Parks,Completed,NH-ANNA NAGAR,100,820000,"MAINTENANCE FOR GREENERY AREA OF DR. VISWESWARAYA TOWER PARK (BY EMPLOYING QUALIFIED HORTICULTURIST) FOR A PERIOD OF SIX MONTH IN DN-100, UNIT- 22, ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/33172,Parks,Completed,NH-ANNA NAGAR,100,614000,"MAINTENANCE OF DR. VISWESWARAYA TOWER PARK INSIDE ELECTRIC MOTOR AND WATER LINE(LANDSCAPE AREA,TOILET AREA,DRINKING WATER LINE),TOWER CLOCK SERVICES (ONE YEAR) AT ANNA NAGAR IN DN-100, UNIT- 22, ZONE -8.",Own Sources,8,2015-16,2017-18 NH/2015-16/33173,Parks,Completed,NH-ANNA NAGAR,100,828000,"MAINTENANCE FOR SWEEPING LABOUR AND FOUNTAIN CLEANING OF DR.VISWESWARAYA TOWER PARK ( PERIOD FOR SIX MONTHS) IN DN- 100, UNIT- 22,ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/33174,Parks,Completed,NH-ANNA NAGAR,100,479000,"ANNUAL MAINTENANCE OF DR. VISWESWARAYA TOWER PARK TOILET CLEANING MAINTENANCE FOR ONE YEAR IN DN-100, UNIT- 22, ZONE-8 .",Own Sources,8,2015-16,2018-19 NH/2015-16/33175,Buildings,Completed,NH-ANNA NAGAR,100,420000,"IMPROVEMENTS OF TOWER PARK AND PROVIDING BIN PLATFORM IN DIVISION-100, UNIT-22, ZONE-08.(UNDER MAINTENANCE)",Own Sources,8,2015-16,2016-17 NH/2015-16/33281,Roads,Completed,NH-ANNA NAGAR,96,155000,"ROAD CUT RESTORATION MADE BY CMWSSB AT BHARATHAMADA STREET IN DN-96, U-21, Z-8.",Deposit Works,8,2015-16,2016-17 NH/2015-16/33283,Roads,Completed,NH-ANNA NAGAR,96,185000,"ROAD CUT RESTORATION MADE BY CMWSSB AT BOOSANAM STREET IN DN-96, U-21, Z-8.",Deposit Works,8,2015-16,2016-17 NH/2015-16/33288,Roads,Completed,NH-ANNA NAGAR,96,162000,"ROAD CUT RESTORATION MADE BY CMWSSB AT PONNUSAMY STREET IN DN-96, U-21, Z-8.",Deposit Works,8,2015-16,2016-17 NH/2015-16/33348,Footpath,Completed,NH-ANNA NAGAR,97,999000,"DISMANTLING RCC ROOF, REPAIR AND DESILTING TO STORM WATER DRAIN ALONG CHETTY STREET FROM DOOR NO. 44/51 TO DURAISAMY STREET IN DN-97, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33430,Buildings,Completed,NH-ANNA NAGAR,102,76000,"Providing wooden name board at Zonal office -8 in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/33432,Roads,Completed,NH-ANNA NAGAR,102,495000,"Improvements to Centre Median at First avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/33433,Roads,Completed,NH-ANNA NAGAR,102,450000,"Improvements to Centre Median at First avenue Road(west side) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/33444,Roads,Completed,NH-ANNA NAGAR,105,549000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE CONCRETE AT E-BLOCK 6TH CROSS STREET IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/33445,Roads,Completed,NH-ANNA NAGAR,105,549000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE CONCRETE AT E-BLOCK 1ST CROSS STREET IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/33450,Roads,Completed,NH-ANNA NAGAR,105,704000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE CONCRETE AT E-BLOCK 3RD CROSS STREET AND 3RD LANE IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/33457,Buildings,Completed,NH-ANNA NAGAR,98,65000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND WEATHERING COURSE POINTING TO DIVISION OFFICE BUILDING IN DIV-98,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/33516,Buildings,Completed,NH-ANNA NAGAR,96,144000,"REPAIR AND IMPROVEMENTS TO UNIT OFFICE AT UNITED INDIA NAGAR IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2015-16,2017-18 NH/2015-16/33518,Roads,Completed,NH-ANNA NAGAR,96,87300,"Improvements to Amma unavagam at K.h.road and K.K.Nagar in division-96,Unit-21,Zone-8",Own Sources,8,2015-16,2016-17 NH/2015-16/33519,Roads,Completed,NH-ANNA NAGAR,96,153000,"PROVIDING WATER SUPPLY ARRENGEMENTS AT PALAVAYAL SCHOOL,DIVISION -96 OFFICE BUILDING, HEALTH CENTER ,UNITED INDIA NAGAR 1ST STREET IN DN-96, U-21, Z-8 .",Own Sources,8,2015-16,2016-17 NH/2015-16/33520,Buildings,Completed,NH-ANNA NAGAR,96,113000,"PROVIDING NAME BOARD ARRENGEMENTS AND PLATFORM FOR DUST BIN AT VARIOUS LOCATION IN DN-96, U-21, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33602,Buildings,Completed,NH-ANNA NAGAR,100,46000,"PROVIDING ALUMINIUM PARTITION AND ELECTRICAL ARRANGEMENTS AT DIVISION OFFICE (E-COUNTER) IN DIVISION-100, UNIT-22, ZONE-08.(UNDER MAINTENANCE)",Own Sources,8,2015-16,2016-17 NH/2015-16/33645,Buildings,Completed,NH-ANNA NAGAR,107,710000,"SUPPLYING AND FIXING OF NAMMA TOILET WITH OUT SEWERAGE RGE.WOMEN -1, REG.MEN-1, URINAL 1 AT LOCATION 1, M.S.NAGAR IN DN-107,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33655,Roads,Completed,NH-ANNA NAGAR,103,223000,"ATTENDING PATCH WORK AND PROVIDING PIPE LINE AT VARIOUS STREET IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/33657,Roads,Completed,NH-ANNA NAGAR,103,998000,"PROVIDING SPEED BREAKER AT VARIOUS STREETS IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2017-18 NH/2015-16/33662,Buildings,Completed,NH-ANNA NAGAR,94,97000,"CONSTRUCTION OF BABY DISABLE TOILET INSIDE NNMP SHED AT SIDCO NAGAR 42 ND STREET INDN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/33710,Buildings,Completed,NH-ANNA NAGAR,104,733000,"SUPPLYING AND FIXING OF NAMMA TOILET WITH OUT SEWERAGE RGE.WOMEN -1, REG.MEN-1, URINAL 1 AT PURASAWALKAM IN DIVISION-104,UNIT-23,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/33720,Roads,Completed,NH-ANNA NAGAR,101,105000,"REPAIR AND IMPROVEMENT TO FOOTPATH AT ANNA NAGR 3RD MAIN ROAD IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/33722,Buildings,Completed,NH-ANNA NAGAR,107,710000,"SUPPLYING AND FIXING OF NAMMA TOILET WITH OUT SEWERAGE RGE.WOMEN -1, REG.MEN-1, URINAL 1 AT LOCATION 1 MAYOR RAMANATHAN STREET IN DN-107,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33754,Roads,Completed,NH-ANNA NAGAR,105,673023,"Relaying the road at Thiruppur Kumaran Street in Div -105, Unit -22, Zone -8.",Own Sources,8,2015-16,2017-18 NH/2015-16/33755,Buildings,Completed,NH-ANNA NAGAR,105,455000,"REPAIR AND IMPROVEMENT TO DIVISION OFFICE AT KANNAKI STREET IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/33756,Buildings,Completed,NH-ANNA NAGAR,105,215000,"IMPROVEMENT TO AMMA UNAVAGAM AT SBI STAFF COLONY 6TH STREET,MARIYAMMAN KOIL STREET IN DN-105,U-22,Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/33768,Buildings,Completed,NH-ANNA NAGAR,108,154400,"REPAIR WORKS TO THE N-BLOCK CHENNAI HIGH SCHOOL @ BAHAT SING 2ND STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33771,Storm Water Drain,Completed,NH-ANNA NAGAR,101,95000,"PROVIDING WATER TABLE AT C-BLOCK 10TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/33813,Buildings,Completed,NH-ANNA NAGAR,98,42800,"REPAIRS TO FLOORING,ELECTRICAL AND PLUMBING WORK IN ICDS AT AMBEDHKAR NAGAR AND SAMI DOSSPURAM P.C IN DIV-98,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/33814,Buildings,Completed,NH-ANNA NAGAR,98,45000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO AMMA UNAVAGAM PHASE-2 AT AYANAVARAM TANK ROAD IN DIV-98,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/33937,Buildings,Completed,NH-ANNA NAGAR,100,77000,"IMPROVEMENTS OF AMMA UNAVAGAM (3rd AVENUE & 7th MAIN ROAD) AND CPS (NSK NAGAR ) IN DIVISION-100, UNIT-22, ZONE-08.(UNDER MAINTENANCE)",Own Sources,8,2015-16,2016-17 NH/2015-16/33948,Buildings,Completed,NH-ANNA NAGAR,107,363000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN (DUE TO HEAVY DRAIN) DAMAGED PORTION AT CHITTI BABU STREET IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/33949,Buildings,Completed,NH-ANNA NAGAR,107,83000,"PROVIDING MOTOR AND WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL,P.C AT DASPURAM,HEALTH POST AT JAGANATHAPURAM IN DIV-107,UN-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/33950,Buildings,Completed,NH-ANNA NAGAR,107,50000,"PROVIDING DRAINAGE ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT SCHOOL ROAD IN DIV-107,UN-23,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/33953,Buildings,Completed,NH-ANNA NAGAR,104,122000,"IMPROVEMENT WORKS TO STROM WATER DRAIN AT VARIOUS STREET IN DIVISION 104, UNIT 23, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/33962,Roads,Completed,NH-ANNA NAGAR,104,395000,"PROVIDING SPEED BREAKERS AT PANDARAM STREET , MENOD STREET AND VARIOUS STREETS IN DN-104, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/33963,Roads,Completed,NH-ANNA NAGAR,104,395000,"PROVIDING SPEED BREAKERS AT SUNDARAM STREET, LETTANGS ROAD AND VARIOUS STREETS IN DN-104, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34021,Buildings,Completed,NH-ANNA NAGAR,104,120000,"PROVIDING PIPE LINE AT THIDEER NAGAR AND PONNAN STREET IN DN-104, UNIT-23,ZONE-VIII",Own Sources,8,2015-16,2016-17 NH/2015-16/34219,Roads,Completed,NH-ANNA NAGAR,103,870000,"LAYING CEMENT CONCRETE ROAD AT RANI ANNA NAGAR MAIN ROAD, LANES (WEST SIDE) AND T.P.CHATHIRAM 2ND STREET IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34220,Roads,Completed,NH-ANNA NAGAR,103,810000,"LAYING CEMENT CONCRETE ROAD AT HALLS ROAD NEW QUARTERS IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34221,Roads,Completed,NH-ANNA NAGAR,103,399000,"LAYING CEMENT CONCRETE ROAD AT RANI ANNA NAGAR MAIN ROAD FROM EAST TO WEST & LANES (EAST SIDE) IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34222,Roads,Completed,NH-ANNA NAGAR,103,875000,"LAYING CEMENT CONCRETE ROAD AT RANI ANNA NAGAR MAIN ROAD & LANES (SOUTH SIDE) IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34290,Buildings,Completed,NH-ANNA NAGAR,107,332000,PROVIDING AND FIXING IRON HEIGHT RESTRICTION BAR AT HARRINGTON ROAD SUBWAY(WESTERN SIDE)IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/34291,Buildings,Completed,NH-ANNA NAGAR,107,313000,"PROVIDING AND FIXING TRAFFIC SIGNAGE BOARD, PAVEMENT MARKER,REFLECTOR PAINT, NAME BOARD FOR IRON HEIGHT RESTRICTION BAR AT HARRINGTON ROAD SUBWAY IN DIV-107 U-23 Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34293,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (FROM CH 75.00m TO 90.00) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34294,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (JN OF MILLERS ROAD TO CH 15.00m) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34295,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (FROM CH 15.00m TO 30.00) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34296,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (FROM CH 30.00m TO 45.00) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34297,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (FROM CH 45.00m TO 60.00) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34298,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (FROM CH 60.00m TO 75.00) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34299,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (FROM CH 90.00m TO 105.00) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34300,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD (FROM CH 105.00m TO 120.00) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34301,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWALKKAM HIGH ROAD (JN OF BRICKLINE ROAD TO CH 30) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34302,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SWD AT PURASAIWAKKAM HIGH ROAD TO (JN OF BRICKLINE ROAD TO VASANTH & CO) IN DN-103,U-23,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34386,Buildings,Completed,NH-ANNA NAGAR,103,880000,"PROVIDING AND FIXING STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREET IN DN-103,U-23,Z-8 (WARD COUNCILLOR SCHEME 2016-17).",Own Sources,8,2015-16,2017-18 NH/2015-16/34445,Storm Water Drain,Completed,NH-ANNA NAGAR,103,970000,"PROVIDING CONCRETE CENTRE MEDIAM AT KELLYS ROAD IN DN-103,U-23,Z-8.( WARD CONCILOR SCHEME 2016-17)",Own Sources,8,2015-16,2017-18 NH/2015-16/34449,Roads,Completed,NH-ANNA NAGAR,103,970000,"PROVIDING CONCRETE CENTRE MEDIAM AT TAYLORS ROAD IN DN-103,U-23,Z-8.( WARD CONCILOR SCHEME 2016-17)",Own Sources,8,2015-16,2017-18 NH/2015-16/34451,Roads,Completed,NH-ANNA NAGAR,103,980000,"RELAYING ROAD AT BARNABY LANE IN DN-103,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34714,Roads,Completed,NH-ANNA NAGAR,94,998000,"INSTALLATION, COMMISSIONING OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITRES / HOUR CAPACITY AT SIDCO NAGAR VILLIVAKKAM 4TH STREET ROAD IN DN 94,UNIT-21, ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34740,Roads,Completed,NH-ANNA NAGAR,99,1618000,"REALYING OF ROAD WITH BCCMP BY PAVER AT KATHIRAVAN COLONY IN DN 99 ,UNIT 21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34741,Roads,Completed,NH-ANNA NAGAR,100,3894000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 5TH MAIN ROAD IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34750,Roads,Completed,NH-ANNA NAGAR,105,1242000,"RELAYING OF ROAD WITH BCCMP BY PAVER AT PERUMAL KOIL GARDEN, KAMALA NEHRU NAGAR 2ND STREET,VOC STREET,VIVEKANANDHAR STREET IN DN-105 UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/34777,Roads,Completed,NH-ANNA NAGAR,94,364000,PROVIDING SWD MANHOLE DOOR FOR DAMAGE PLACE VARIOUS PLACE IN DIVISION -94 ZONE-8,Own Sources,8,2015-16,2017-18 NH/2015-16/34798,Roads,Completed,NH-ANNA NAGAR,94,582000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT AMMAN KUTTAI MAIN ROAD IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34800,Roads,Completed,NH-ANNA NAGAR,101,548000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD AT B-BLOCK 11TH STREET(CHAINAGE 120M TO 250M) IN DN-101,U-22,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/34820,Buildings,Completed,NH-ANNA NAGAR,94,146000,REPAIR AND IMPROVEMENT TO NNMP SHED AT SIDCO NAGAR 10TH STREET IN DN-94 UNIT-21 ZONE ? 8,Own Sources,8,2015-16,2017-18 NH/2015-16/34821,Buildings,Completed,NH-ANNA NAGAR,94,111000,REPAIR AND IMPROVEMENT TO AMMA UNAVAGAM AT SIVAN KOIL NORTH MADA STREET & RAJAMANGALAM MAIN ROAD IN DN-94 UNIT-21 ZONE ? 8,Own Sources,8,2015-16,2017-18 NH/2015-16/34822,Buildings,Completed,NH-ANNA NAGAR,94,98000,"REPAIR BORE , REPLACING MOTOR AT CMS AND DIVISION OFFICE SIVAN KOIL NORTH MADA STREET IN DN-94 UNIT-21 ZONE ? 8",Own Sources,8,2015-16,2017-18 NH/2015-16/34823,Buildings,Completed,NH-ANNA NAGAR,94,225000,REPAIR AND IMPROVEMENT TO VILLIVAKKAM SUBWAY IN DN-94 UNIT-21 ZONE ? 8,Own Sources,8,2015-16,2017-18 NH/2015-16/34824,Storm Water Drain,Completed,NH-ANNA NAGAR,94,350000,REPAIR DAMAGED SWD AT MTH ROAD NEAR BURIAL GROUND AND REPLACING DAMAGED SWD MANHOLE DOOR IN VARIOUS STREET IN DN-94 UNIT-21 ZONE ? 8,Own Sources,8,2015-16,2017-18 NH/2015-16/34825,Roads,Completed,NH-ANNA NAGAR,94,51000,ATTENDING WMM PATCH AT SIDCO NAGAR 2ND MAIN ROAD IN DN-94 UNIT-21 ZONE ? 8,Own Sources,8,2015-16,2017-18 NH/2015-16/34903,Roads,Completed,NH-ANNA NAGAR,95,610000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT NAGESHWARA COLONY, EAST MADA STREET, VILLIVAKKAM STATION ROAD IN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34904,Roads,Completed,NH-ANNA NAGAR,95,594000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT PILLAYAR KOIL STREET & KUMARASAMY CROSS STREET IN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34905,Roads,Completed,NH-ANNA NAGAR,95,762000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT AGATHEESWARAN COLONY 7TH STREET IN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34906,Roads,Completed,NH-ANNA NAGAR,95,732000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT KUMARASAMY STREET IN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34907,Roads,Completed,NH-ANNA NAGAR,95,916000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT THIRUVALLUVAR KUDI IRUPU I-BLOCK 18TH STREET IN DN-95,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34908,Parks,Completed,NH-ANNA NAGAR,94,55000,CONSTRUCTION OF INLET CHAMBER AT RK LINK ROAD IN DN 94 UNIT 21 ZONE 08,Own Sources,8,2015-16,2016-17 NH/2015-16/34909,Buildings,Completed,NH-ANNA NAGAR,94,245000,"IMPROVEMENTS TO CENTRE VERANDAH IN UPHS AT RAJAMANGALAM MAIN ROAD IN DN.94, U-21,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34913,Roads,Completed,NH-ANNA NAGAR,94,150000,"IMPROVEMENT TO BABA NAGAR 6TH LANE IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/34914,Roads,Completed,NH-ANNA NAGAR,94,640000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT RAJAMAGALAM 5TH, 6TH AND 8TH STREET IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34915,Roads,Completed,NH-ANNA NAGAR,94,640000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT RAJAMAGALAM 1ST, 3RD, & 4TH STREETIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34916,Roads,Completed,NH-ANNA NAGAR,94,460000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT MTH ROAD SERVICE ROAD SOUTH IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34917,Roads,Completed,NH-ANNA NAGAR,94,396000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT SIDCO NAGAR 92ND STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34918,Roads,Completed,NH-ANNA NAGAR,94,800000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT KAMARAJAR NAGAR IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34919,Roads,Completed,NH-ANNA NAGAR,94,203000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT NORTH JAGANTHAN ANNEXE IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34920,Roads,Completed,NH-ANNA NAGAR,94,800000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT MTH ROAD SERVICE ROAD NORTH IN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34921,Roads,Completed,NH-ANNA NAGAR,94,364000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT NORTH JAGANTHAN 2ND STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34922,Roads,Completed,NH-ANNA NAGAR,94,230000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTING ROAD)BY PAVER AT PERIYAR NAGAR 2ND STREET IIN DN-94,U-21,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/34924,Storm Water Drain,Completed,NH-ANNA NAGAR,94,330000,"DESILTING SUBWAY WELL AND WATER COLLECTION POINT IN ROAD SIDE WELL AT VILLIVAKKAM SUBWAY IN DN- 94, UNIT 21, ZONE VIII.",Own Sources,8,2015-16,2017-18 NH/2015-16/34925,Storm Water Drain,Completed,NH-ANNA NAGAR,94,310000,"DESILTING BURIAL GROUND SWD AND CHAIN LINK FENCING ENCROACHMENT LAND NEAR MTH ROAD SWD AT MTH ROAD IN DN-94,U-21,Z-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/34929,Roads,Completed,NH-ANNA NAGAR,94,830000,"IMPROVEMENTS TO THE SWD AT SIDCO NAGAR 6TH & 7TH STREET & SUPPLYING OF FRC & FRP MANHOLE DOOR IN -94,UNIT -21,ZONE-08",Own Sources,8,2015-16,2017-18 NH/2015-16/34938,Buildings,Completed,NH-ANNA NAGAR,107,340000,PROVIDING AND FIXING IRON HEIGHT RESTRICTION BAR AT HARRINGTON ROAD SUBWAY (EASTERN SIDE) IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2015-16,2016-17 NH/2015-16/34958,Buildings,Completed,NH-ANNA NAGAR,107,470000,"ATTENDING PATCH WORK KANDAN STREET, SUBBARAYAN STREET AND MANGALAPURAM 4TH STREET AT IN DIV-107 U-23 Z-8",Own Sources,8,2015-16,2017-18 NH/2015-16/34959,Buildings,Completed,NH-ANNA NAGAR,103,790000,ATTENDING OF PATCH WORK UMAYAL ROAD AT IN DIV-103 U-23 Z-8,Own Sources,8,2015-16,2017-18 NH/2015-16/34960,Buildings,Completed,NH-ANNA NAGAR,103,600000,ATTENDING OF PATCH WORK PARASUPILLAI STREET AT IN DIV-103 U-23 Z-8,Own Sources,8,2015-16,2017-18 NH/2015-16/34988,Buildings,Completed,NH-ANNA NAGAR,99,660000,ATTENDING PATCH WORK AT VARIOUS STREET IN DIVISION 99 UNIT 21 ZONE-8,Own Sources,8,2015-16,2017-18 NH/2015-16/34989,Buildings,Completed,NH-ANNA NAGAR,99,470000,ATTENDING PATCH WORK AT VARIOUS STREET IN DIVISION- 99 UNIT 21 ZONE-8,Own Sources,8,2015-16,2017-18 NH/2015-16/35045,Roads,Completed,NH-ANNA NAGAR,104,567000,"LAYING OF CC ROAD AT MADAM 1ST LANE IN DN-104,UNIT-23,ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/35046,Roads,Completed,NH-ANNA NAGAR,104,522000,"LAYING OF CC ROAD AT MADAM 2ND LANE IN DN-104,UNIT-23,ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/35047,Roads,Completed,NH-ANNA NAGAR,104,535000,"LAYING OF CC ROAD AT BHAKTHAVATCHALAM STREET IN DN-104, UNIT-23,ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/35048,Roads,Completed,NH-ANNA NAGAR,104,1265000,"LAYING OF CC ROAD AT RATHINASAPABATHY STREET IN DN-104, UNIT-23,ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/35056,Buildings,Completed,NH-ANNA NAGAR,94,980000,"Installation of Water Treatment Plant, Maintenance and Operation of the plant at SIDCO NAGAR 4TH MAIN ROAD in Dn-94, Unit-21, Zone-08.",Own Sources,8,2015-16,2018-19 NH/2015-16/35061,Roads,Completed,NH-ANNA NAGAR,99,300000,"Laying of CC Road at 13th Main Road To 4th avenue End 14th Main road in Dn99,unit-21,zone-08",Own Sources,8,2015-16,2017-18 NH/2015-16/35062,Roads,Completed,NH-ANNA NAGAR,100,370000,"Laying CC Road AT 7TH MAIN ROAD IN DN-100,UNIT-22,ZONE-08",Own Sources,8,2015-16,2017-18 NH/2015-16/35107,Parks,Completed,NH-ANNA NAGAR,104,997000,"Proposed construction of Compound wall and improvement works and greenary arrangement in Ottari Burial Ground in Div -104 Unit - 23 Zone -8,",Own Sources,8,2015-16,2018-19 NH/2015-16/3764,Roads,Completed,NH-ANNA NAGAR,105,600000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT PANCHALIAMMAN KOIL LANE AND VOC STREET IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2018-19 NH/2015-16/3765,Roads,Completed,NH-ANNA NAGAR,105,600000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT PERUMAL KOIL GARDEN 1ST LANE IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/3806,Buildings,Completed,NH-ANNA NAGAR,101,500000,"REPAIR AND IMPROVEMENT WORK AT KITCHEN SHED NADUVAKKARI AT BREWERY ROAD IN DN-101, U-22 , Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/3847,Buildings,Completed,NH-ANNA NAGAR,103,480000,"PROVIDING AND FIXING R.O PLANT FOR DRINKING WATER TO CPS AND CHS AT THIYAGAPPA STREET IN DN-103, U -23, Z -8. (MP FUND)",MPLADS,8,2015-16,2017-18 NH/2015-16/3849,Footpath,Completed,NH-ANNA NAGAR,101,998000,"IMPROVEMENT TO FOOTPATH AT ANNA NAGAR 6TH AVENUE IN DN-101 , U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/3916,Buildings,Completed,NH-ANNA NAGAR,97,160000,"Supplying and Erecting Street Name Boards at various Streets in Dn-97, Unit-21, Zone-VIII",Own Sources,8,2015-16,2017-18 NH/2015-16/4002,Roads,Completed,NH-ANNA NAGAR,101,660000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORECTION BY PAVER FINISHER AT F-BLOCK 7TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/4035,Buildings,Completed,NH-ANNA NAGAR,106,338000,"Improvements to e-seva centre in Division office and School in div-106,Unit-22,Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/4227,Buildings,Completed,NH-ANNA NAGAR,102,540000,"Improvements to Centre Median at New Avadi Road (from mandapam street to palliarasan street) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/4245,Roads,Completed,NH-ANNA NAGAR,103,999000,"LAYING CEMENT CONCRETE ROAD AT KAMARAJAR NAGAR (FROM LAKSHMI STREET JN. TO T.P.CHATHIRAM 24TH CROSS STREET JN.) , 9,10 LANES AND KAMARAJAR NAGAR - KOIL STREET IN DN-103,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/4337,Buildings,Completed,NH-ANNA NAGAR,99,970000,PROPOSED MODERN BUS SHELTER AT SHANTHI COLONY NADASEN CO-OPERATIVEBANK (COUNCILLOR FUND 2015-16) IN DN 99 UNIT21 ZONE 8,Own Sources,8,2015-16,2016-17 NH/2015-16/4481,Roads,Completed,NH-ANNA NAGAR,102,996000,"Improvements to Road Side park at New Avadi Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/4818,Buildings,Completed,NH-ANNA NAGAR,104,1496000,PROPOSED CONSTRUCTION OF OPEN AIR AUDITORIUM AT CHENNAI HIGHER SECONDARY SCHOOL IN GANGADEESWARAR KOIL STREET IN DN- 104 UNIT-23 ZONE-8 ( EGMORE CONSITUENCY M L A FUND ),MLACDS,8,2015-16,2016-17 NH/2015-16/4821,Buildings,Completed,NH-ANNA NAGAR,104,1496000,PROPOSED CONSTRUCTION OF OPEN AIR AUDITORIUM AT CHENNAI MIDDLE SCHOOL IN VELLALA STREET IN DN- 104 UNIT-23 ZONE-8 (EGMORE CONSITUENCY M L A FUND),MLACDS,8,2015-16,2016-17 NH/2015-16/4822,Buildings,Completed,NH-ANNA NAGAR,104,1496000,PROPOSED CONSTRUCTION OF OPEN AIR AUDITORIUM AT CHENNAI MIDDLE SCHOOL IN SUNDARAM STREET DN- 104 UNIT-23 ZONE-8 (EGMORE CONSITUENCY M L A FUND ),MLACDS,8,2015-16,2016-17 NH/2015-16/4891,Buildings,Completed,NH-ANNA NAGAR,100,781000,"ADDITONAL CONSTRUCTION OF GYM AT NSK NAGAR 3RD STREET IN DN-100,U-22,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/5022,Buildings,Completed,NH-ANNA NAGAR,101,400000,"REPAIR AND IMPROVEMENT WORK AT CHENNAI PRIMARY SCHOOL NADUVAKKARI IN DN-101, U-22 , Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/5054,Parks,Completed,NH-ANNA NAGAR,102,913000,"Improvement and greenery works to skating park (East side) shenoy nagar in dn-102,unit-23, zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/5059,Parks,Completed,NH-ANNA NAGAR,102,960000,"Providing water supply arrangements and electrical work at Pulla Avenue Park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/5063,Parks,Completed,NH-ANNA NAGAR,102,995000,"Improvements to tennis court and greenery work at Pulla Avenue park in Dn-102, Unit-23, Zone-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/5175,Parks,Completed,NH-ANNA NAGAR,102,960000,"Painting works and wire fencing at skating park shenoy nagar in dn-102,unit-23, zone-08.",Own Sources,8,2015-16,2017-18 NH/2015-16/5344,Buildings,Completed,NH-ANNA NAGAR,101,550000,"CONSTRUCTION OF COMPOUND WALL AT DIVISION OFFICE IN WARD-101,UNIT-21,ZONE-08",Own Sources,8,2015-16,2017-18 NH/2015-16/5345,Buildings,Completed,NH-ANNA NAGAR,101,400000,"IMPROVEMENT AND CONSTRUCTION OF COMPOUND WALL INSIDE LORRY STATION IN DN-101 , U-21, Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/5471,Roads,Completed,NH-ANNA NAGAR,107,990000,"PROVIDING STREET FURNITURE AT VARIOUS STREETS IN DN-107, UNIT-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/5547,Roads,Completed,NH-ANNA NAGAR,101,2382000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER WITH CAMBER CORRECTION AT IST MAIN ROAD IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/5548,Roads,Completed,NH-ANNA NAGAR,101,3090000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER WITH CAMBER CORRECTION AT 7TH CROSS STREET SHENOY NAGAR IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/5551,Roads,Completed,NH-ANNA NAGAR,96,165000,"LAYING OF CEMENT CONCRETE ROAD AT NEW STREET 1ST LANE IN DN-96,U-21,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/5552,Roads,Completed,NH-ANNA NAGAR,96,165000,"LAYING OF CEMENT CONCRETE ROAD AT NEW STREET 2ND LANE IN DN-96,U-21,Z-08 ( FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/5553,Roads,Completed,NH-ANNA NAGAR,96,165000,"LAYING OF CEMENT CONCRETE ROAD AT NEW STREET 3RD LANE IN DN-96,U-21,Z-08 ( FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/5554,Roads,Completed,NH-ANNA NAGAR,96,165000,"LAYING OF CEMENT CONCRETE ROAD AT NEW STREET 4TH LANE IN DN-96,U-21,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/5555,Roads,Completed,NH-ANNA NAGAR,96,165000,"LAYING OF CEMENT CONCRETE ROAD AT NEW STREET 5TH LANE IN DN-96,U-21,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/5556,Roads,Completed,NH-ANNA NAGAR,96,288000,"LAYING OF CEMENT CONCRETE ROAD AT PALAYAKARAN STREET 1ST LANE IN DN-96,U-21,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/5557,Roads,Completed,NH-ANNA NAGAR,96,271000,"LAYING OF CEMENT CONCRETE ROAD AT PALAYAKARAN STREET 2NDLANE IN DN-96,U-21,Z-08 (FLOOD DAMAGE)",Own Sources,8,2015-16,2016-17 NH/2015-16/5650,Roads,Completed,NH-ANNA NAGAR,101,995000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM 2ND STREET IN DN-101,U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/5651,Roads,Completed,NH-ANNA NAGAR,101,990000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM 3RD STREET IN DN-101,U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/5659,Roads,Completed,NH-ANNA NAGAR,101,989000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM 4TH STREET IN DN-101,U-22, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/5970,Storm Water Drain,Completed,NH-ANNA NAGAR,103,380000,"PROVIDING SWD MANHOLE DOOR FOR DAMAGE PLACE VARIOUS PLACE IN DIVISION -103,UNIT-23 ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/6414,Buildings,Completed,NH-ANNA NAGAR,104,480000,PROVIDING AND FIXING RO PLANT FOR DRINKING WATER AT GANGADEESWARAR KOIL STREET CHENNAI HIGHER SECONDARY SCHOOL IN DN- 104 UNIT - 23 ZONE -8 ( M P FUND ),MPLADS,8,2015-16,2017-18 NH/2015-16/6432,Buildings,Completed,NH-ANNA NAGAR,104,480000,PROVIDING AND FIXING RO PLANT FOR DRINKING WATER AT SUNDARAM STREET CHENNAI MIDDLE SCHOOL IN DN - 104 UNIT - 23 ZONE - 8 ( M P FUND),MPLADS,8,2015-16,2017-18 NH/2015-16/6437,Buildings,Completed,NH-ANNA NAGAR,105,801000,"LAYING CEMENT CONCERT ROAD AT RANI ANNA NAGAR MAIN ROAD (REACH-1) IN DIVISION 105, UNIT 22, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/6440,Buildings,Completed,NH-ANNA NAGAR,105,800000,"LAYING CEMENT CONCERT ROAD AT RANI ANNA NAGAR MAIN ROAD (REACH-2) IN DIVISION 105, UNIT 22, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/6441,Buildings,Completed,NH-ANNA NAGAR,105,787000,"LAYING CEMENT CONCERT ROAD AT NEW NATARAJA PURAM (REACH-1) IN DIVISION 105, UNIT 22, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/6443,Roads,Completed,NH-ANNA NAGAR,105,802000,"LAYING CEMENT CONCERT ROAD AT NEW NATARAJA PURAM (REACH-2) IN DIVISION 105, UNIT 22, ZONE 8.",Own Sources,8,2015-16,2016-17 NH/2015-16/6602,Road Cut,Completed,NH-ANNA NAGAR,96,500000,"ROAD CUT RESTORATION MADE BY CMWSSB AT APPADURAI 1ST STREET IN DIVISION-96, UNIT-21, ZONE-8",Deposit Works,8,2015-16,2016-17 NH/2015-16/6721,Roads,Completed,NH-ANNA NAGAR,101,930000,"LAYING OF INTERLOCK BLOCKS ALONG THE SIDES OF C C ROAD AT BREWERY ROAD FROM JN. OF 3RD AVENUE (0M TO 300M) IN DN.101, UNIT-22, ZONE 08.",Own Sources,8,2015-16,2016-17 NH/2015-16/6786,Storm Water Drain,Completed,NH-ANNA NAGAR,95,447000,"DESILTING OF STROM WATER DRAIN AT TVS CANAL TO AGATHIYAR NAGAR IN DN 95, UNIT 21, ZONE 08",Own Sources,8,2015-16,2016-17 NH/2015-16/6842,Buildings,Completed,NH-ANNA NAGAR,99,995000,STRENGTHENING CI OFFICE BUILDING AT H-BLOCK 15TH STREET ANNA NAGAR DN-99 UNIT-21 ZONE - 8,Own Sources,8,2015-16,2016-17 NH/2015-16/7054,Buildings,Completed,NH-ANNA NAGAR,99,995000,"ADDITIONAL IMPROVEMENT WORKS TO CI OFFICE AT H-BLOCK 15TH STREET, DN.99 UNIT-21 ZONE-8",Own Sources,8,2015-16,2017-18 NH/2015-16/7391,Buildings,Completed,NH-ANNA NAGAR,105,700000,"Improvements to kitchen shed at CMS 'c' block,arumbakkam in dn-105,unit-22,zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/7537,Roads,Completed,NH-ANNA NAGAR,103,999000,"ATTENDING PATCHWORK AT VARIOUS STREETS IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/7797,Buildings,Completed,NH-ANNA NAGAR,102,550000,"Construction of SI Room and Labour Rest Room at first floor of division office-102 at Gajapathy street in dn-102,unit-23,zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/7827,Buildings,Completed,NH-ANNA NAGAR,95,435000,"CONSTRUCTION OF BIO DECOMPOSED PLANT @ NEW AVADI ROAD, THIRU NAGER PARK IN DN 95 UNIT 21 ZONE 8",Own Sources,8,2015-16,2016-17 NH/2015-16/8073,Playfields,Completed,NH-ANNA NAGAR,98,999000,"PROPOSED CONSTRUCTION OF PATH WAY AT EXISTING PLAY GROUND AND PROVIDING PLAY APPARATUS AT LOCKMA NAGAR IN DIVISION-98,UNIT-23,ZONE-8",Own Sources,8,2015-16,2016-17 NH/2015-16/8074,Buildings,Completed,NH-ANNA NAGAR,98,23000,"PROVIDING MAN HOLE DOOR AT CK STREET,AYANAVARAM ROAD IN DN-98,U-23,Z-8",Own Sources,8,2015-16,2018-19 NH/2015-16/8163,Storm Water Drain,Completed,NH-ANNA NAGAR,96,998000,"RE-CONSTRUCTION OF STORM WATER DRAIN AT DURAISAMY STREET IN DN -96,UNIT - 21, ZONE - 8",Own Sources,8,2015-16,2016-17 NH/2015-16/8402,Roads,Completed,NH-ANNA NAGAR,101,71000,"PROVIDING GROUP BIN FLOORING AT VARIOUS STREET IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/8407,Roads,Completed,NH-ANNA NAGAR,101,39000,"BLACK & WHITE PAINTING TO FOOTPATH AT ANNA NAGAR 1ST MAIN ROAD IN DN-101,UNIT-22,ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/8409,Roads,Completed,NH-ANNA NAGAR,101,156000,"IMPROVEMENT TO FOOTPATH AT SHENOY NAGAR 3RD CROSS STREET IN DN-101,U-22,,Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/8412,Roads,Completed,NH-ANNA NAGAR,101,999000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 8TH STREET IN DN-101,U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/8422,Roads,Completed,NH-ANNA NAGAR,101,998000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 10TH CROSS STREET IN DN-101,U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/8435,Roads,Completed,NH-ANNA NAGAR,101,990000,"LAYING OF CEMENT CONCRETE ROAD AT PONNUVEL PILLAI THOTTAM MAIN ROAD ( CHAINAGE FROM 125 TO 250 ) IN DN-101,U-21, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/8508,Buildings,Completed,NH-ANNA NAGAR,94,899000,"IMPROVEMENTS TO CORPORATION SCHOOL AT NORTH SIVAN KOIL STREET IN DN- 94,U-21,Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/8614,Roads,Completed,NH-ANNA NAGAR,101,185000,"PROVIDING SINGLE BIN FLOORING AND PAINTING AT VARIOUS STREET IN DN-101, U-22 , Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/8624,Buildings,Completed,NH-ANNA NAGAR,95,1480000,"CONSTRUCTION OF MULTI PURPOSE HALL( GROUND & FIRST FLOOR AT THIRUNAGAR 17TH STREET IN DN-95,U-21,Z-8",MLACDS,8,2015-16,2016-17 NH/2015-16/8643,Roads,Completed,NH-ANNA NAGAR,108,700000,"PROPOSED TREE PLANTATION FOR 1000 TREE AT VARIOUS STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/8646,Roads,Completed,NH-ANNA NAGAR,108,989833,"PROVIDING NEW SPEED BREAKS AT VARIOUS STREETS IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/8694,Road Cut,Completed,NH-ANNA NAGAR,101,165000,"REPAIR AND IMPROVEMENT TO FOOTPATH AT C-BLOCK 7TH STREET IN DN-101,U-22, Z-08",Own Sources,8,2015-16,2016-17 NH/2015-16/8838,Buildings,Completed,NH-ANNA NAGAR,106,216000,"REPAIRS WORKS IN AMMA UNAVAGAM AT COLLECTORATE COLONY IN DN-106,U-22,Z-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/8840,Roads,Completed,NH-ANNA NAGAR,106,658000,"REPAIRS AND IMPROVEMENTS TO CENTRE MEDIAN AT NELSON MANICKAM ROAD IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/8842,Roads,Completed,NH-ANNA NAGAR,106,520000,"PROVIDING SPEED BREAKERS AT VARIOUS STREETS IN DN-106, UNIT-22, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/8891,Roads,Completed,NH-ANNA NAGAR,106,920000,"SUPPLYING AND FIXING STAINLESS STEEL HAND RAIL TO THE EXISTING CENTRE MEDIAN AT NELSON MANIKKAM ROAD ( FROM NEIL KAMAL TO HDFC BANK REACH I ) IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/8893,Roads,Completed,NH-ANNA NAGAR,106,920000,"SUPPLYING AND FIXING STAINLESS STEEL HAND RAIL TO THE EXISTING CENTRE MEDIAN AT NELSON MANIKKAM ROAD ( HDFC BANK TO METHA NAGAR REACH-II ) IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/8942,Roads,Completed,NH-ANNA NAGAR,106,694000,"RELAYING OF C.C ROAD AT ARUNACHALAPURAM STREET IN DIVISION - 106, UNIT - 22, ZONE - 8",Own Sources,8,2015-16,2016-17 NH/2015-16/8945,Buildings,Completed,NH-ANNA NAGAR,106,443000,"RELAYING OF C.C ROAD AT PATEL STREET IN DIVISION - 106, UNIT - 22, ZONE - 8",Own Sources,8,2015-16,2016-17 NH/2015-16/8947,Roads,Completed,NH-ANNA NAGAR,106,456000,"RELAYING OF C.C ROAD AT AMBEDKAR STREET IN DIVISION - 106, UNIT - 22, ZONE - 8",Own Sources,8,2015-16,2016-17 NH/2015-16/9174,Roads,Completed,NH-ANNA NAGAR,107,995000,"STRENGTHENING AND RELAYING THE ROAD AT PILLAIYAR KOIL STREET IN DN-107, U-23, Z-8. ( WARD COUNCILLOR FUND 2016-2017)",Own Sources,8,2015-16,2016-17 NH/2015-16/9176,Buildings,Completed,NH-ANNA NAGAR,107,997000,"PROVIDING DRINAGE WATER SUPPLY AND ELECTRICAL ARRANGEMENT TO CPS AT MC NICHOLS ROAD IN DIV-107, UN-23, Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/9178,Roads,Completed,NH-ANNA NAGAR,107,397000,"WIDENING THE ROAD AT PUMPING STATION ROAD IN DN-107, U-23, Z-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/9181,Buildings,Completed,NH-ANNA NAGAR,107,997000,"PROVIDING FLOORING,PAINTING AND IMPROVEMENTS TO CPS SCHOOL AT MCHNICOL ROAD IN DIV-107, UN-23, Z-08",Own Sources,8,2015-16,2017-18 NH/2015-16/9417,Buildings,Completed,NH-ANNA NAGAR,107,850000,IMPROVEMENT TO L.K.G CLASS ROOM AND AUDITORIAM COLOUR WASINE LETTER WRITING WALL PAINING AT SUBBARAYAN C.H.S.S SCHOOL IN DIV-107 U-23 Z-8,Own Sources,8,2015-16,2016-17 NH/2015-16/9602,Buildings,Completed,NH-ANNA NAGAR,104,890000,"IMPROVEMENT WORKS TO COMPOUND WALL AROUND E B TRANSFORMERS AT DR.ALAGAPPA ROAD,SUNDARAM STREET, PURASAIWAKKAM HIGH ROAD, GANGADEESWARAR KOIL ST, BRICKLIN ROAD, VELLALA STREET,SARAVANA PERUMAL KOIL STREET, SHANMUGARAYAN STREET. IN DN104, UNIT-23 , ZONE -8",Own Sources,8,2015-16,2016-17 NH/2015-16/9695,Buildings,Completed,NH-ANNA NAGAR,102,735000,"Improvements to Old Hospital Building at VS puram in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/9702,Roads,Completed,NH-ANNA NAGAR,107,997000,"STRENGTHENING AND RELAYING THE ROAD AT KUPPUSAMY STREET IN DN-107, U-23, Z-8. ( WARD COUNCILLOR FUND 2016-2017)",Own Sources,8,2015-16,2017-18 NH/2015-16/9705,Buildings,Completed,NH-ANNA NAGAR,107,830000,"IMPROVEMENTS TO EXISTING GYM AT PLAY GROUND AND MAYAR RAMANATHAN SALAI IN DN-107, UNIT-23, ZONE-8.",Own Sources,8,2015-16,2016-17 NH/2015-16/9718,Roads,Completed,NH-ANNA NAGAR,102,255000,"Providing water supply and electrical arrangements at CHGSS at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2015-16,2016-17 NH/2015-16/9767,Road Cut,Completed,NH-ANNA NAGAR,101,300000,"RESTORATION OF ROADCUT MADE BY TNEB AT BHARATHI PURAM 4TH STREET IN DN-101,U-22,Z-08",Deposit Works,8,2015-16,2016-17 NH/2015-16/9771,Road Cut,Completed,NH-ANNA NAGAR,101,420000,"RESTORATION OF ROADCUT MADE BY TNEB AT BHARATHI PURAM 2ND STREET IN DN-101,U-22,Z-08",Deposit Works,8,2015-16,2016-17 NH/2015-16/9819,Buildings,Completed,NH-ANNA NAGAR,98,146000,"DEMOLITION OF EXISTING PUBLIC CONVIENENCE AT LOCKMA NAGAR IN DN-98,U-23,Z-8",Own Sources,8,2015-16,2016-17 NH/2015-16/9963,Roads,Completed,NH-ANNA NAGAR,107,998000,"STRENGTHENING AND RELAYING THE ROAD AT HARRINGTON ROAD 14TH AVENUE IN DN-107, U-23, Z-8. ( WARD COUNCILLOR FUND 2016-2017)",Own Sources,8,2015-16,2017-18 NJ/2015-16/0045,Roads,Completed,NJ-TEYNAMPET,115,1709000,"Proposed laying of Bituminous Concrete Road at Shaik Dawood street in Dn-115,U-27,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/0376,Buildings,Completed,NJ-TEYNAMPET,121,487000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT VEERA PERUMAL KOIL STREET IN DN-121,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/0378,Buildings,Completed,NJ-TEYNAMPET,121,812000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT BANGARU AMMAL STREET IN DN-121,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/0547,Buildings,Completed,NJ-TEYNAMPET,126,948000,"Raising and lowering of SWD Manhole with Construction of Inspection chamber at lazarus church road, in div-126,u-25 z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/0581,Buildings,Completed,NJ-TEYNAMPET,114,290000,"PROVIDING DRINKING WATER SUPPLY ARRANGEMENTS AND IMPROVEMENTS TO R.O MACHINE AND ROOM AT MARINA BEACH SERVICE ROAD NEAR LABOUR STATUE IN DN-114,UNIT-27A,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/0637,Parks,Completed,NJ-TEYNAMPET,111,800000,"ANNUAL MAINTENANCE OF PARK AT COLLEGE LANE PARK (TWO YEAR) IN DIVISION -111,UNIT-24,ZONE-IX.",Own Sources,9,2015-16,2017-18 NJ/2015-16/0638,Parks,Completed,NJ-TEYNAMPET,111,994000,"ANNUAL MAINTENANCE OF PARK AT HODDOWS ROAD PHASE - I & II PARK ( TWO YEAR) IN DIVISION -111,UNIT-24,ZONE-IX",Own Sources,9,2015-16,2018-19 NJ/2015-16/10158,Buildings,Completed,NJ-TEYNAMPET,109,478000,"PROVIDING AND FIXING R O PLANT TO THIRUVALLUVARPURAM CPS SCHOOL(MP FUND 2015-16) IN DIV-109,U-24,Z-9",MPLADS,9,2015-16,2018-19 NJ/2015-16/10163,Buildings,Completed,NJ-TEYNAMPET,109,478000,"PROVIDING AND FIXING RO PLANT TO EAST NAMACHIVAYAPURAM CPS SCHOOL (UNDER MLA CONSTITUENCY DEVELOPMENT SCHEME 2015-2016) IN DN-109, UNIT-24 , ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10171,Roads,Completed,NJ-TEYNAMPET,119,1280000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT NALLANNA STREET ( UNDER MLA SCHEME ) IN DIVISION -119, UNIT- 24,ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10174,Roads,Completed,NJ-TEYNAMPET,119,330000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT VATHIARCHINNAIAH STREET IN DIVISION -119,UNIT-24,ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10175,Roads,Completed,NJ-TEYNAMPET,119,340000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT NALLANNA LANE (UNDER MLA,S SCHEME ) IN DIVISION -119, UNIT- 24,ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10176,Roads,Completed,NJ-TEYNAMPET,119,590000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT LEONARD STREET (UNDER MLA SCHEME ) IN DIVISION -119, UNIT- 24,ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10177,Roads,Completed,NJ-TEYNAMPET,119,590000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT V.M.STREET 2ND LANE (UNDER MLA SCHEME ) IN DIVISION -119, UNIT- 24,ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10178,Roads,Completed,NJ-TEYNAMPET,119,890000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT MUSTHURA BEGAM STREET (UNDER MLA SCHEME ) IN DIVISION -119, UNIT- 24,ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10183,Buildings,Completed,NJ-TEYNAMPET,110,2480000,"CONSTRUCTION OF MODERN TOILET AT SCHOOL ROAD INSIDE THE BOYS HIGHER SECONDARY SCHOOL IN DIVISION-110, UNIT-24, ZONE-09.",MLACDS,9,2015-16,2017-18 NJ/2015-16/10201,Buildings,Completed,NJ-TEYNAMPET,110,2480000,"CONSTRUCTION OF MODERN TOILET AT SCHOOL ROAD INSIDE THE GIRLS HIGHER SECONDARY SCHOOL IN DIVISION-110, UNIT-24, ZONE-09.",MLACDS,9,2015-16,2017-18 NJ/2015-16/1021,Buildings,Completed,NJ-TEYNAMPET,126,855000,Lowering the SWD manhole equal to the level of road for free fall of rain water at santhom high road in div126 u 25 z 9,Own Sources,9,2015-16,2016-17 NJ/2015-16/10214,Buildings,Completed,NJ-TEYNAMPET,118,478000,"PROVIDING AND FIXING R OPLANT TO MUTHIAH STREET MIDDLE SCHOOL (UNDER MLA,S SCHEME 2015-16) IN DN -118,UNIT-24,ZONE-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/10230,Roads,Completed,NJ-TEYNAMPET,119,305000,"IMPROVEMENT CEMENT CONCRET ROAD AT BEGAM 1ST STREET IN DN-119,UNIT-24,ZONE-9",MLACDS,9,2015-16,2018-19 NJ/2015-16/10235,Roads,Completed,NJ-TEYNAMPET,119,310000,"IMPROVEMENT CEMENT CONCRET ROAD AT BEGUM 2 ND STREET IN DN-119,UNIT-24,ZONE-9",MLACDS,9,2015-16,2018-19 NJ/2015-16/10236,Roads,Completed,NJ-TEYNAMPET,119,476000,"IMPROVEMENT CEMENT CONCRET ROAD AT BEGUM 4TH STREET IN DN-119,UNIT-24,ZONE-9",MLACDS,9,2015-16,2018-19 NJ/2015-16/10240,Buildings,Completed,NJ-TEYNAMPET,124,246000,"PROVIDING PLATFORM AND WATER SUPPLY ARRANGEMENTS FOR E-TOILET AT SLATERPURAM IN DN-124, UNIT-25, ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/1030,Buildings,Completed,NJ-TEYNAMPET,126,991000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT SRINGERI MUTT ROAD IN DIV-126,UNIT-25,ZONE-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/10395,Buildings,Completed,NJ-TEYNAMPET,113,2000000,"CONSTRUCTION OF ADDITIONAL CLASS ROOM AT CORPORATION MIDDLE SCHOOL RAMA STREET IN DN 113, UNIT-26,ZONE-9 (UNDER MLA FUND)",MLACDS,9,2015-16,2017-18 NJ/2015-16/10416,Buildings,Completed,NJ-TEYNAMPET,112,2500000,"CONSTRUCTION OF ADDITIONAL CLASS ROOM AT CHOOLAI MEDU HIGHER SECONDARY SCHOOL IN DN 112, UNIT-26,ZONE-9 (UNDER MLA FUND)",Own Sources,9,2015-16,2016-17 NJ/2015-16/10419,Buildings,Completed,NJ-TEYNAMPET,112,2500000,"CONSTRUCTION OF KITCHEN CUM DINING HALL AT CHOOLAI MEDU HIGHER SECONDARY SCHOOL IN DN 112, UNIT-26,ZONE-9 (UNDER MLA FUND)",MLACDS,9,2015-16,2017-18 NJ/2015-16/10442,Buildings,Completed,NJ-TEYNAMPET,117,2500000,"CONSTRUCTION OF KITCHEN CUM DINING HALL AT SOUTH BOAG ROAD IN ERIKARAI CORPORATION MIDDLE SCHOOL IN DN 117, UNIT-26,ZONE-9 (UNDER MLA FUND)",Own Sources,9,2015-16,2016-17 NJ/2015-16/1056,Roads,Completed,NJ-TEYNAMPET,123,999000,"ATTENDING PATCH WORK AT RAMACHANDRA ROAD, JUSTICE SUNDARAM ROAD, DR.RANGA ROAD IN DN.123, UNIT.25, ZONE.09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/10562,Roads,Completed,NJ-TEYNAMPET,110,630000,Relaying the Road with BC 40mm Thick by Paver Finisher at Kakkan Colony 1st street (Under MLA constituency Development Scheme 2015-16) in Dn-110Unit-24 Zone-09,MLACDS,9,2015-16,2017-18 NJ/2015-16/10577,Roads,Completed,NJ-TEYNAMPET,119,404000,"IMPROVMENT OF CEMENT CONCRETE ROAD AT SANDA VELLI 1 STREET IN DN-119,UNIT-24,ZONE-09",MLACDS,9,2015-16,2018-19 NJ/2015-16/10578,Roads,Completed,NJ-TEYNAMPET,119,404000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT SANDA VELLI 2ND STREET IN DIN-119,UNIIT-24,ZONE-09",MLACDS,9,2015-16,2018-19 NJ/2015-16/10579,Roads,Completed,NJ-TEYNAMPET,119,404000,"IMPROVENTS TO CEMENT CONCRETE ROAD AT SANDA VELLI 3RD STREET IN DN-119,UNIT-24,ZONE-09",MLACDS,9,2015-16,2018-19 NJ/2015-16/10581,Roads,Completed,NJ-TEYNAMPET,119,431000,"IMPROVENTS TO CEMENT CONCRETE ROAD AT SANDA VELLI 4 TH STREET IN DN-119,UNIT-24,ZONE-09",MLACDS,9,2015-16,2018-19 NJ/2015-16/10583,Buildings,Completed,NJ-TEYNAMPET,111,1794000,"PROPOSED CONSTRUCTION OF NNMP SHED NO.03020 AT SUTHANTHIRA NAGAR IN DIVISION-111,U 24,ZONE-09",MLACDS,9,2015-16,2017-18 NJ/2015-16/1071,Roads,Completed,NJ-TEYNAMPET,123,990000,"ATTENDING PATCH WORK AT LADY DESIKACHARI ROAD, DESIKA ROAD, VISWESWARAPURAM, C.V.RAMAN ROAD IN DN.123, UNIT.25, ZONE.09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/10757,Roads,Completed,NJ-TEYNAMPET,111,900000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT PADMAVATHIAR STREET IN DIVISION-111,UNIT-24,ZONE-09,",MLACDS,9,2015-16,2016-17 NJ/2015-16/10759,Roads,Completed,NJ-TEYNAMPET,111,350000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT WEST END STREET IN DIVISION-111,UNIT-24,ZONE-09",MLACDS,9,2015-16,2017-18 NJ/2015-16/10821,Buildings,Completed,NJ-TEYNAMPET,111,2700000,"CONSTRUCTION OF ADDITIONAL CLASS ROOMS AT CHENNAI CORPORATION HIGHSCHOOL AT MODEL SCHOOL ROAD IN DIVISION-111,UNIT-24,ZONE-09",MLACDS,9,2015-16,2018-19 NJ/2015-16/10826,Footpath,Completed,NJ-TEYNAMPET,118,697000,"IMPROVEMENTS TO THE FOOTPATH AT POES ROAD 1ST STREET SUCH AS REPLACEMENT OF MAN HOLE, GRATING ,WALK WAY WITH CONCRETE,REPLACEMENT OF KERBS AND PROVIDING WATER TABLE IN DN-118,UNIT-24, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/10862,Footpath,Completed,NJ-TEYNAMPET,118,697000,"IMPROVEMENTS TO THE FOOTPATH AT POES ROAD 2ND STREET SUCH AS REPLACEMENT OF MAN HOLE, GRATING ,WALK WAY WITH CONCRETE,REPLACEMENT OF KERBS AND PROVIDING WATER TABLE IN DN-118,UNIT-24, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/10867,Footpath,Completed,NJ-TEYNAMPET,118,496000,"IMPROVEMENTS TO THE FOOTPATH AT POES ROAD 3RD STREET SUCH AS REPLACEMENT OF MAN HOLE, GRATING ,WALK WAY WITH CONCRETE,REPLACEMENT OF KERBS AND PROVIDING WATER TABLE IN DN-118,UNIT-24, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/1090,Buildings,Completed,NJ-TEYNAMPET,117,283000,IMPROVEMENTS TO ICDS (CENTER NO 33603080214 AND 33603080215) AT SOUTH BOAG ROAD (117 DIVISION OFFICE BACK SIDE) IN DIVISION 117 UNIT 26 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/1092,Buildings,Completed,NJ-TEYNAMPET,117,325000,"IMPROVEMENTS TO ICDS (CENTER NO 33603080115) AT SOUTH BOAG ROAD (BLOCK 16 OPPOSITE) IN DN 117, U 26, Z09",Own Sources,9,2015-16,2016-17 NJ/2015-16/1093,Buildings,Completed,NJ-TEYNAMPET,117,305000,"IMPROVEMENTS TO ICDS (CENTER NO 33603080216) AT SOUTH BOAG ROAD (BLOCK 20) IN DN 117, U 26, Z09",Own Sources,9,2015-16,2016-17 NJ/2015-16/10932,Buildings,Completed,NJ-TEYNAMPET,114,996000,"SPECIAL IMPROVEMENTS TO ICDS BUILDING AT ARUNACHALAM STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/10975,Buildings,Completed,NJ-TEYNAMPET,111,1600000,"PROPOSED CONSTRUCTION OF KITCHEN SHED AT CHENNAI CORPORATION HIGH SCHOOL AT MODEL SCHOOL ROAD(UNDER MLA FUND) IN DIV 111, U-24, Z-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/1101,Buildings,Completed,NJ-TEYNAMPET,117,274000,"IMPROVEMENTS TO ICDS (CENTER NO 33603080208 AND 33603080209) AT THIRU.VI.KA.KUDIRUPPU IN DN 117, U 26, Z 09",Own Sources,9,2015-16,2016-17 NJ/2015-16/1102,Buildings,Completed,NJ-TEYNAMPET,117,341000,"IMPROVEMENTS TO ICDS (CENTER NO 33603080210 AND 33603080211) AT NAKKERAN NAGAR IN DN 117, U 26, Z09",Own Sources,9,2015-16,2016-17 NJ/2015-16/11133,Footpath,Completed,NJ-TEYNAMPET,118,600000,"IMPROVEMENTS TO THE FOOTPATH AT MURRAYS GATE ROAD SUCH AS REPLACEMENT OF MAN HOLE, GRATING , WALK WAY WITH CONCRETE, REPACEMENT OF KERBS AND PROVIDING WATER TABLE IN DIV 118,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11142,Footpath,Completed,NJ-TEYNAMPET,111,635000,IMPROVEMENTS TO FOOTPATH AT HADDOWS ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/11144,Footpath,Completed,NJ-TEYNAMPET,111,150000,IMPROVEMENT TO FOOTPATH AT PETERS ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/11145,Footpath,Completed,NJ-TEYNAMPET,111,800000,IMPROVEMENT TO FOOTPATH AT ANDERSON ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/11146,Road Cut,Completed,NJ-TEYNAMPET,111,350000,REPAIRS AND IMPROVEMENTS TO PC AT SUDHANTHIRA NAGAR AND SEWAGE CONNECTION TO SSS TOILETS IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/11147,Footpath,Completed,NJ-TEYNAMPET,118,454000,Fixing of FRP Vertical Grating and Improvement to damaged manholes of storm water drain at Kasturi Rangan main road in Dn-118 Unit-24 Zone-09,Own Sources,9,2015-16,2017-18 NJ/2015-16/11354,Storm Water Drain,Completed,NJ-TEYNAMPET,110,310000,"PROVIDING OPEN WELL RAIN WATER HARVESTING AT VARIOUS ROADS IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11355,Parks,Completed,NJ-TEYNAMPET,121,468000,"TREE PLANTATION AT VARIOUS ROADS IN DIV 121, UNIT-27, ZONE-9",Thanniraivu Thittam,9,2015-16,2016-17 NJ/2015-16/11407,Buildings,Completed,NJ-TEYNAMPET,124,102000,"Providing Vertical grating to the Existing SWD at Kutchery Road in Division 124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/11420,Parks,Completed,NJ-TEYNAMPET,124,468000,"Tree Plantation at various important streets in division-124, Unit-25, Zone-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/11444,Footpath,Completed,NJ-TEYNAMPET,111,612000,FORMING FOOTPATH AT HADDOWS ROAD 1ST STREET IN DIVISION 111 UNIT 24 ZONE 9,Own Sources,9,2015-16,2017-18 NJ/2015-16/11449,Footpath,Completed,NJ-TEYNAMPET,111,492000,FORMING FOOTPATH AT HADDOWS ROAD 2ND STREET IN DIVISION 111 UNIT 24 ZONE 9,Own Sources,9,2015-16,2017-18 NJ/2015-16/11470,Road Cut,Completed,NJ-TEYNAMPET,113,237000,"RESTORATION OF ROAD CUT MADE BY TNEB AT JAGANATHAN ROAD IN DN 113,UNIT-26,ZONE-9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/11472,Road Cut,Completed,NJ-TEYNAMPET,113,96000,"RESTORATION OF ROAD CUT MADE BY TNEB AT KUMARAPPA STREET IN DN 113,UNIT-26,ZONE-9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/11473,Road Cut,Completed,NJ-TEYNAMPET,113,96000,"RESTORATION OF ROAD CUT MADE BY TNEB AT KRISHNAMMA ROAD IN DN 113,UNIT-26,ZONE-9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/11474,Road Cut,Completed,NJ-TEYNAMPET,113,170000,"RESTORATION OF ROAD CUT MADE BY TNEB AT NOOR VEERASAMY STREET IN DN 113,UNIT-26,ZONE-9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/11476,Road Cut,Completed,NJ-TEYNAMPET,113,222000,"RESTORATION OF ROAD CUT MADE BY TNEB AT PRAGADAMBAL STREET IN DN 113,UNIT-26,ZONE-9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/11477,Road Cut,Completed,NJ-TEYNAMPET,113,490000,"RESTORATION OF ROAD CUT MADE BY TNEB AT RAMA STREET IN DN 113,UNIT-26,ZONE-9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/11556,Buildings,Completed,NJ-TEYNAMPET,116,805000,"DEMOLISHING THE EXISTING GROUND FLOOR OF DAMAGED OLD SCHOOL BUILDING AND PROVIDING BARIGAURD USING G.I SHEET FOR COMPOUND WALL AT VENKATRANGAM STREET IN DN-116,U-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11558,Buildings,Completed,NJ-TEYNAMPET,120,400000,"PROVIDING BOREWELL, WATER SUPPLY ARRANGEMENTS AND LAYING FLOORING TO ICDS -2NOS AT NADUKUPPAM 5TH STREETAND ELECTRICAL IMPROVEMENTS TO CGHS AT IRRUSAPPAN STREET IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11575,Roads,Completed,NJ-TEYNAMPET,114,802000,"Re-Laying the Road with Bituminous Coarse 40mm thick by Paver finisher at Khana bagh Street in Dn-114,Unit-27,Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/11582,Roads,Completed,NJ-TEYNAMPET,124,995000,Forming and Widening the Road with DBM 50mm and BC 30mm thick by Paver Finisher at Slaterpuram (From Jn of Nattan Thottam to Shanmugam Street ) in Dn-124 Unit-25 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/11586,Footpath,Completed,NJ-TEYNAMPET,124,995000,Forming the Footpath at Slaterpuram East Side (From Jn of Mundakkanni Amman Koil Street to Jn of Nattan Thottam ) in Dn-124 Unit-25 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/11595,Road Cut,Completed,NJ-TEYNAMPET,113,237000,"RESTORATION OF ROAD CUT MADE BY TNEB AT VIDYODAYA MAIN ROAD IN DN 113,UNIT-26,ZONE-9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/11617,Buildings,Completed,NJ-TEYNAMPET,116,427000,"PROVIDING ROOFING AND ELECTRICAL ARRANGEMENTS FOR PUBLIC CONVENIENCE AT PALANI AMMAN KOIL 6TH STREET IN DN-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11751,Footpath,Completed,NJ-TEYNAMPET,115,998000,"IMPROVEMENTS TO FOOTPATH NORTH AND SOUTH SIDE AT DR.BESANT ROAD ( FOR GLOBAL INVERSTOR'S MEET) IN DN-115,UNIT-27,,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11883,Roads,Completed,NJ-TEYNAMPET,113,983000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point at various streets in Div 113, U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11922,Buildings,Completed,NJ-TEYNAMPET,122,983000,"PROVIDING RAIN WATER HARVESTING STRUCTURE (WELL RING TYPE WITH RCC COVER SLAB) AT WATER STAGNATION AT VARIOUS STREETS IN DIVISION - 122, UNIT - 26, ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11946,Buildings,Completed,NJ-TEYNAMPET,112,983000,"Providing Rain Water Harvesting Structure (Well Ring Type With RCC Cover Slab) at water stagnation point at various streets in Division - 112, Unit - 26, Zone - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11973,Roads,Completed,NJ-TEYNAMPET,111,975000,"ATTENDING PATCH WORK WITH PAVER FINISHER AT MOORS ROAD AND CONTRONSMITH ROAD IN DN - 111, UNIT - 24, ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/11997,Buildings,Completed,NJ-TEYNAMPET,118,988000,"IMPROVEMENT TO AMMA UNAVAGAM AT SRINIVASA PERUMAL KOVIL STREET IN DIVISION-118, UNIT-24, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12046,Parks,Completed,NJ-TEYNAMPET,117,568000,"IMPROVEMENTS TO OSR LAND AT CHARI STREET ,VIJAYA RAGHAVA ROAD AND ANNA SALAI IN DN 117 ,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12054,Road Cut,Completed,NJ-TEYNAMPET,110,622000,"RESTORATION OF ROAD CUT MADE BY T.N.E.B AT SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/12057,Road Cut,Completed,NJ-TEYNAMPET,110,232000,"RESTORATION OF ROAD CUT MADE BY TNEB AT NEW STREET IN DN 110,UNIT 24,ZONE 9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/12063,Buildings,Completed,NJ-TEYNAMPET,125,985000,IMPROVEMENTS TO OLD AGE HOME AT DOOMING KUPPAM IN DIVISION 125 UNIT 25 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/12083,Buildings,Completed,NJ-TEYNAMPET,114,998000,"CONVERTION OF EXISTING UNUSED SCHOOL BUILDING INTO NIGHT SHELTER AT LOCK NAGAR IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12092,Buildings,Completed,NJ-TEYNAMPET,109,820000,"PROVIDING RAIN WATER HARVESTING STRUCTURE(WELL RING TYPE WITH RCC COVER SLAB) AT VARIOUS LOCATIONS IN DN-109,U-24,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12098,Roads,Completed,NJ-TEYNAMPET,112,245000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT BHARATHEESWARAR COLONY 3RD CROSS STREET IN DIV-112,U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12110,Buildings,Completed,NJ-TEYNAMPET,109,664000,"DISMANTLING AND RECONSTRUCTION OF COMMPOUND WALL IN GILL NAGAR PARK AT CENTRAL SCHOOL ROAD SIDE IN DN-109, U-24, Z-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/12128,Footpath,Completed,NJ-TEYNAMPET,118,630000,IMPROVEMENTS TO FOOTPATH AT KASTURI RANGAN SALAI AND FIXING VERTICAL GRATING IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/12198,Footpath,Completed,NJ-TEYNAMPET,113,945000,"PROVIDING AND LAYING CEMENT CONCRETE INTER LOCKING PAVER BLOCKS FOR ROAD EDGES AT JAMBULINGAM STREET IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12201,Footpath,Completed,NJ-TEYNAMPET,113,480000,"PROVIDING AND LAYING CEMENT CONCRETE INTERLOCKING PAVER BLOCKS FOR ROAD EDGES AT PRAKASAM 1ST LANE IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12205,Footpath,Completed,NJ-TEYNAMPET,113,554000,"PROVIDING AND LAYING CEMENT CONCRETE INTERLOCKING PAVER BLOCKS FOR ROAD EDGES AT VIDYODAYA 2ND CROSS STREET IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12208,Footpath,Completed,NJ-TEYNAMPET,113,980000,"PROVIDING AND LAYING CEMENT CONCRETE INTERLOCKING PAVER BLOCKS FOR ROAD EDGES AT VIDYODAYA 1ST MAIN ROAD IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12239,Footpath,Completed,NJ-TEYNAMPET,111,993000,CONSTRUCTION OF COMPOUND WALL AT ANDERSON SALAI ROAD SIDE PARK IN DN-111 UNIT-24 ZONE-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/1227,Roads,Completed,NJ-TEYNAMPET,124,975000,"MAINTENANCE OF PRE FABRICATED URINAL UNITS AT VARIOUS LOCATION IN DIVISIONS-123,124,125, AND 126 IN UNIT-25 ,ZONE-09. (PERIOD06.06.2015 TO 06.05.2016)11MONTHS",Own Sources,9,2015-16,2019-20 NJ/2015-16/12272,Footpath,Completed,NJ-TEYNAMPET,120,400000,"REPAIRS AND IMPROVEMENTS TO GRANITE KERB WALLS AND GRANITE FOOTPATH AT MARINA BEACH SERVICE ROAD IN DN 120, UNIT 27, ZONE 9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/12282,Buildings,Completed,NJ-TEYNAMPET,111,980000,"IMPROVEMENTS TO AMMA UNAVAGAM -II AT WALLACE GARDEN 2ND STREET IN DIVISION-111,UNIT-24,ZONE-9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/12339,Roads,Completed,NJ-TEYNAMPET,109,990000,Filling of Red Earth and Providing Steel Fencing over compound wall to Gill Nagar Central School Road Play Ground In Dn-109 Unit-24 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/12369,Storm Water Drain,Completed,NJ-TEYNAMPET,110,996000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT KAMARAJAPURAM 4TH STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12374,Storm Water Drain,Completed,NJ-TEYNAMPET,110,997000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT KAMARAJAPURAM MAIN ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12377,Storm Water Drain,Completed,NJ-TEYNAMPET,110,998000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT KAKKAN COLONY IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12383,Footpath,Completed,NJ-TEYNAMPET,116,997000,"IMPROVEMENTS TO THE TRANSFORMERS LOCATED IN SUNGUWAR STREET,CAR STREET,SINGACHARI STREETAND PARTHASARATHY TEMPLE IN DIV-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12387,Footpath,Completed,NJ-TEYNAMPET,116,997000,"IMPROVEMENTS TO THE TRANSFORMERS LOCATED IN Dr.BESANT ROAD,V.R PILLAI STREET,SIVARAJA PURAM AND T.P KOVIL STREET IN DIV-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12388,Road Cut,Completed,NJ-TEYNAMPET,110,643000,"RESTORATION OF ROAD CUT MADE BY T.N.E.B AT KOTHARI ROAD IN DN 110,UNIT 24,ZONE 9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/12391,Footpath,Completed,NJ-TEYNAMPET,116,997000,"IMPROVEMENTS TO THE TRANSFORMERS LOCATED IN B.V (N) STREET,KARPAGA KANNIAMMAN KOVIL,BHARAT SCOUT AND CANAL STREET IN DIV-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12409,Roads,Completed,NJ-TEYNAMPET,126,750000,"ARRANGEMENTS TO SCAFFOLDING, CHAIR AND PANDHAL FOR IMMERSION OF VINAYAGAR STATUE AT LOOP ROAD BEACH IN DIV-126, UNIT-25, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12429,Parks,Completed,NJ-TEYNAMPET,110,468000,"PLANTATION OF DIFFERENT TYPE OF TREES AT VARIOUS STREETS IN DIVISION-110,UNIT-24,ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/12486,Buildings,Completed,NJ-TEYNAMPET,125,479000,IMPROVEMENTS TO PUBLIC CONVENIENCE LOOP ROAD (NEAR MARINA BEACH) IN DIV-125 UNIT-25 ZONE-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/12488,Buildings,Completed,NJ-TEYNAMPET,112,768000,"Providing Rain Water Harvesting Structure (Well Ring Type With RCC Cover Slab) at Corporation Buildings and Parks in Various Street In Division - 112, Unit - 26, Zone - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12491,Buildings,Completed,NJ-TEYNAMPET,117,768000,"Providing Rain Water Harvesting Structure (Well Ring Type With RCC Cover Slab) at corporation buildings and Parks in Various Street In Division - 117, Unit - 26, Zone - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12492,Buildings,Completed,NJ-TEYNAMPET,122,768000,"Providing Rain water Harvesting structure (well ring type with cover slab) at Corporation buildings and parks at various streets in Div 122,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/12500,Buildings,Completed,NJ-TEYNAMPET,125,482000,IMPROVEMENTS TO PUBLIC CONVENIENCE LOOP ROAD IN DIV-125 UNIT-25 ZONE-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/12503,Buildings,Completed,NJ-TEYNAMPET,115,996000,"CONVERTING OLD UNUSED CMS TO NIGHT SHELTER AT SUBRAMANIYA GARDEN STREET IN Dn-115,U-27,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/12504,Buildings,Completed,NJ-TEYNAMPET,115,997000,"ELETRICAL AND PLUMBING ARRANGEMENTS FOR NEWLY FORMING NIGHT SHELTER AT SUBRAMANIYA GARDEN STREET IN Dn-115,U-27,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/12561,Buildings,Completed,NJ-TEYNAMPET,124,347000,"Improvement works to ICDS No.33603110322, 33603110323, 33603110324 at Mundagakanni Amman Koil Street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/12562,Buildings,Completed,NJ-TEYNAMPET,124,985000,Forming the Footpath at Slaterpuram West Side (From Jn of Mundakkanni Amman Koil Street to Jn of Nattan Thottam ) in Dn-124 Unit-25 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/12639,Buildings,Completed,NJ-TEYNAMPET,114,407000,"LAYING AND FLOORING GRANITE SLAB BEHIND LABOUR STATUE IN MARINA BEACH,PROVIDING EWC CLOSET AT MARINA SWIMMING POOL PC AND LABOUR STATUE PC AND IMPROVEMENTS TO TOILET BLOCKS AND CONVERTING THE TOILET TO CONSERVENCE STORE ROOM IN 114-DIVISION OFFICE IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/1308,Buildings,Completed,NJ-TEYNAMPET,126,990000,"ADDITIONAL and IMPROVEMENT TO SSA BUILDING AT FORTH (4th) TRUST CROSS STREET IN DIVISION-126,UNIT-24,ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/13432,Buildings,Completed,NJ-TEYNAMPET,117,983000,"Providing Rain Water Harvesting Structure (Well Ring Type With RCC Cover Slab) at water stagnation point at various streets in Division - 117, Unit - 26, Zone - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/13437,Roads,Completed,NJ-TEYNAMPET,109,468000,"TREE PLANTATION AT ROAD SIDE IN DIV 109, UNIT-24, ZONE-9",Thanniraivu Thittam,9,2015-16,2016-17 NJ/2015-16/13442,Roads,Completed,NJ-TEYNAMPET,114,468000,"TREE PLANTATION AT ROAD SIDE IN DIV 114, UNIT-27, ZONE-9",Thanniraivu Thittam,9,2015-16,2016-17 NJ/2015-16/13443,Roads,Completed,NJ-TEYNAMPET,115,468000,"TREE PLANTATION AT ROAD SIDE IN DIV 115, UNIT-27, ZONE-9",Thanniraivu Thittam,9,2015-16,2016-17 NJ/2015-16/13444,Roads,Completed,NJ-TEYNAMPET,116,468000,"TREE PLANTATION AT ROAD SIDE IN DIV 116, UNIT-27, ZONE-9",Thanniraivu Thittam,9,2015-16,2016-17 NJ/2015-16/13449,Roads,Completed,NJ-TEYNAMPET,120,468000,"TREE PLANTATION AT ROAD SIDE IN DIV 120, UNIT-27, ZONE-9",Thanniraivu Thittam,9,2015-16,2016-17 NJ/2015-16/13647,Buildings,Completed,NJ-TEYNAMPET,126,768000,"PROPOSED CONSTRUCTION OF RAIN WATER HARVESTING AT CORPORATION BUILDINGS AND PARKS AT VARIOUS STREETS IN DN.126,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/13661,Footpath,Completed,NJ-TEYNAMPET,117,563000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT BHARTHI NAGAR 3RD STREET IN DIV 117, UNIT-26 ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13662,Parks,Completed,NJ-TEYNAMPET,126,468000,"Tree Plantation at various important streets in division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/13668,Footpath,Completed,NJ-TEYNAMPET,117,510000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT BHARTHI NAGAR 4TH STREET IN DIV 117, UNIT-26 ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13670,Footpath,Completed,NJ-TEYNAMPET,117,996000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT BHARTHI NAGAR 1ST STREET IN DIV 117, UNIT-26 ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13676,Footpath,Completed,NJ-TEYNAMPET,117,752000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT BHARTHI NAGAR 2ND STREET, 2ND LANE AND 3RD LANE IN DIV 117, UNIT-26 ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13682,Footpath,Completed,NJ-TEYNAMPET,117,930000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT THILAK STREET (SOUTHERN SIDE) IN DIV 117, UNIT-26 ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13687,Footpath,Completed,NJ-TEYNAMPET,117,670000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT THILAK STREET (EASTERN SIDE) IN DIV 117, UNIT-26 ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13689,Footpath,Completed,NJ-TEYNAMPET,117,550000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT THILAK STREET EXTN IN DIV 117, UNIT-26 ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13710,Buildings,Completed,NJ-TEYNAMPET,113,768000,"Providing Rain water harvesting structure(Well ring type with cover slab) at various corporation buildings and parks in Div 113, U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/13817,Buildings,Completed,NJ-TEYNAMPET,109,768000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point in various streets in Div-109, U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13906,Buildings,Completed,NJ-TEYNAMPET,110,768000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point in various streets in Div-110, U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13907,Buildings,Completed,NJ-TEYNAMPET,111,768000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point in various streets in Div-111, U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/13909,Buildings,Completed,NJ-TEYNAMPET,115,784000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point in various streets in Div-115, U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/13910,Buildings,Completed,NJ-TEYNAMPET,116,768000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point in various streets in Div-116, U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/13911,Buildings,Completed,NJ-TEYNAMPET,118,768000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point in various streets in Div-118, U-24,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/13919,Buildings,Completed,NJ-TEYNAMPET,110,934000,"PROVIDING NEW BORE WELL AND WATER SUPPLY ARRANGEMENTS TO CGHS SCHOOL, CBHS SCHOOL AT SCHOOL ROAD, CMS AT APPASAMY STREET, DIVISION 110 OFFICE AT KUTTY STREET, ZONAL OFFICE 9 CAMPUS AT LAKE AREA 4TH CROSS STREET AND PUBLIC CONVENIENCE AT JAYALAKSHMI PURAM 2ND STRET IN DIVISION-110, UNIT-24, ZONE-IX.",Own Sources,9,2015-16,2017-18 NJ/2015-16/13940,Buildings,Completed,NJ-TEYNAMPET,126,983000,"Providing Rain water harvesting structure (well ring type with cover slab ) at water stagnation point at various streets in Dn 126, Unit-25,Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/1395,Buildings,Completed,NJ-TEYNAMPET,124,900000,"Proposed Construction of toilet block for Chennai Middle School at Slater Puram in division-124, Unit-25, Zone-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/1403,Buildings,Completed,NJ-TEYNAMPET,123,900000,"Proposed Construction of toilet block for Chennai Middle School at St.Mary's Road in division-123, Unit-25, Zone-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/14217,Roads,Completed,NJ-TEYNAMPET,125,870000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD (UNDER COUNCILOR FUND) AT VARIOUS STREETS IN DN-125,UNIT- 25 ,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14218,Roads,Completed,NJ-TEYNAMPET,125,870000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD (UNDER COUNCILOR FUND) AT VARIOUS STREETS IN DN-125,UNIT- 25 ,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14222,Parks,Completed,NJ-TEYNAMPET,109,754000,"PROVIDING PLANTS AND GREENERY ARRANGEMENT AT GILL NAGAR PARK IN DN-109, U-24, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14226,Buildings,Completed,NJ-TEYNAMPET,115,975000,"CONSTRUCTION OF WAITING HALL IN DE-ADDICTION CENTER AT MIRZA HYDER ALI KHAN STREET IN DN-115,UNIT-27,ZONE-9[ FOR WARD COUNCILLOR FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/14231,Buildings,Completed,NJ-TEYNAMPET,115,691000,"PROVIDING DRAINAGE, WATER ARRANGEMENTS AND ELECTRICAL ARRANGEMENTS AND LAYING WEATHERING COURSE FOR NEWLY FORMING WAITING HALL IN DE-ADDICTION CENTER AT MIRZA HYDER ALI KHAN STREET IN DN-115,UNIT-27,ZONE-9 [ FOR WARD COUNCILLOR FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/14293,Buildings,Completed,NJ-TEYNAMPET,117,563000,"IMPROVEMENTS WORK AT GIRIAPPA ROAD RATION SHOP IN DN.117, UNIT-26, ZONE-9 (UNDER WARD COUNCILLOR FUND)",Own Sources,9,2015-16,2016-17 NJ/2015-16/1430,Buildings,Completed,NJ-TEYNAMPET,111,374000,"IMPROVEMENTS TO ICDS BUILDING CENTRE NO 03079,03080 AT MODEL SCHOOL ROAD IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14308,Buildings,Completed,NJ-TEYNAMPET,112,415000,"ATTENDING PATCH WORK FOR CC ROAD AT DOSSPURAM 9th STREET IN DN-112,U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/1431,Buildings,Completed,NJ-TEYNAMPET,111,286000,"IMPROVEMENTS TO ICDS BUILDING CENTRE NO 03018 AT THIDEER NAGAR IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/1432,Buildings,Completed,NJ-TEYNAMPET,111,275000,"IMPROVEMENTS TO ICDS BUILDING CENTRE NO 03017 AT THIDDER NAGAR IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/1433,Buildings,Completed,NJ-TEYNAMPET,111,438000,"IMPROVEMENTS TO ICDS BUILDING CENTRE NO 03019,03020,03095 AT SUDHANTHIRA NAGAR IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14349,Parks,Completed,NJ-TEYNAMPET,125,468000,"Tree Plantation at Various important Street in Dn.125, Unit-25,Zone-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/1435,Storm Water Drain,Completed,NJ-TEYNAMPET,111,325000,PROVIDING VERTICAL GRATING TO AVVAI SHANMUGAM SALI IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/1436,Parks,Completed,NJ-TEYNAMPET,111,129000,"MAINTENANCE OF HADDOWS ROAD PARK FOR 4 MONTHS AT HADDOWS ROAD IN DIVISION- 111, UNIT-24, ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/14423,Parks,Completed,NJ-TEYNAMPET,111,993000,IMPROVEMENTS TO SPENCER PARK IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/14428,Storm Water Drain,Completed,NJ-TEYNAMPET,111,820000,RAISING OR LOWERING MAN HOLE DOORS AND CONSTRUCTION OF SOCK PIT ARRANGEMENT FOR SSS TOILETS IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/14429,Roads,Completed,NJ-TEYNAMPET,111,920000,"ATTENDING PATCH WORK WITH WET MIX AT VARIOUS PLACES DUE NORTH EAST MONSOON IN DIVISION 109,110,111,118 AND 119 UNIT 24 ZONE 09",Own Sources,9,2015-16,2016-17 NJ/2015-16/14432,Buildings,Completed,NJ-TEYNAMPET,111,340000,PROVIDING AND LAYING PVC PIPE LINE TO DRAIN OUT THE RAIN WATER AT WHITES ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/14433,Buildings,Completed,NJ-TEYNAMPET,111,835000,WRITTING LETTERS FOR CONSERVENCY INFORMATION TO ALL THE STREETS IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2017-18 NJ/2015-16/14435,Buildings,Completed,NJ-TEYNAMPET,118,990000,IMPROVEMENTS TO UNDER FLY OVER PORTION IN ( T.T.K ROAD AND CATHIDERAL ROAD ) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2018-19 NJ/2015-16/14438,Storm Water Drain,Completed,NJ-TEYNAMPET,118,650000,RAISING OR LOWERING MAN HOLE DOORS IN VARIOUS LOCATIONS IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/14529,Buildings,Completed,NJ-TEYNAMPET,110,982000,"PROVIDING AND FIXING GALVANAISHED IRON SHEET SHED FOR COMPOSED YARD AT INSIDE NUNGAMBAKKAM BURIAL GROUND IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14533,Buildings,Completed,NJ-TEYNAMPET,110,977000,"IMPROVEMENTS TO COMPOSED YARD AT INSIDE NUNGAMBAKKAM BURIAL GROUND IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14545,Buildings,Completed,NJ-TEYNAMPET,110,840000,"PROVIDING NEW BORE WELL AND WATER SUPPLYING ARRANGEMENTS TO COMPOSED YARD AT INSIDE NUNGAMBAKKAM BURIAL GROUND IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14585,Buildings,Completed,NJ-TEYNAMPET,109,890000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS FOR AMMAUNAVAGAM AT WEST NAMACHIVAYAPURAM IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14596,Roads,Completed,NJ-TEYNAMPET,126,995000,"Providing Speed Breakers as per IRC design [Clause 5, 6 of IRC: 99-1988] with Bituminous Concrete (as per clause 509 of MORT&H specification) to the required grade level andalignment and rolled with vibratory roller etc., complete and as directed by Engineers and as per the plan enclosed.at West Circular Road And various locations in div 126,unit-25,zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14598,Roads,Completed,NJ-TEYNAMPET,126,995000,"Attending Patch work by using BT hot mix from area of 5m2 to 25 m2 at Vengadakrishna Road And various road in division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14664,Storm Water Drain,Completed,NJ-TEYNAMPET,111,915000,"PROVIDING RAIN WATER HARVESTING AND PIPE LINE AT GREAMS ROAD JUNCTION OF ANDERSEN ROAD AND COLLEGE ROAD IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/1468,Footpath,Completed,NJ-TEYNAMPET,112,997000,"IMPROVEMENTS THE EXISTING FOOT PATH AT TRUSTPURAM 6th CROSS STREET (From Puliyur main road to Puliyur 1st main road) IN Dn-112,U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14772,Buildings,Completed,NJ-TEYNAMPET,118,679000,"ATTENDING REPAIRS & IMPROVEMENTS TO THE SUMP IN AMMA UNAVAGAM AT SRINIVASA PERUMAL 2nd STREET AT Dn-118,U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/14814,Storm Water Drain,Completed,NJ-TEYNAMPET,113,170000,"Providing FRP Gratings existing Storm Water Drain at Jaganathan Road in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14815,Storm Water Drain,Completed,NJ-TEYNAMPET,113,184000,"Providing FRP Gratings for existing Storm Water Drain at Nageswara Rao Road in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14816,Storm Water Drain,Completed,NJ-TEYNAMPET,113,97000,"Providing FRP Gratings for existing Storm Water Drain at Josier Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14817,Storm Water Drain,Completed,NJ-TEYNAMPET,113,195000,"Providing FRP Gratings for existing Storm Water Drain at Thirumurthy Nagar Main Road in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14818,Storm Water Drain,Completed,NJ-TEYNAMPET,113,183000,"Providing FRP Gratings for existing Storm Water Drain at Thirumurthy Nagar 5th Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14827,Buildings,Completed,NJ-TEYNAMPET,114,998000,"Providing Rain water harvesting structure(Well ring type with cover slab) at various places in Div-114, U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14828,Buildings,Completed,NJ-TEYNAMPET,115,998000,"Providing Rain water harvesting structure(Well ring type with cover slab) at Corporation buildings in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14829,Buildings,Completed,NJ-TEYNAMPET,116,985000,"Providing Rain water harvesting structure(Well ring type with cover slab) at water stagnation point in parks,playground,COC buildings in Div-116, U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14832,Buildings,Completed,NJ-TEYNAMPET,120,998000,"Providing Rain water harvesting structure(Well ring type with cover slab) at Corporation buildings in Div-120, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14835,Storm Water Drain,Completed,NJ-TEYNAMPET,113,145000,"Providing FRP Gratings for existing Storm Water Drain at Vidyodaya Main Road in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14838,Storm Water Drain,Completed,NJ-TEYNAMPET,113,130000,"Providing FRP Gratings for existing Storm Water Drain at Vidyodaya 2nd Cross Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14841,Storm Water Drain,Completed,NJ-TEYNAMPET,113,97000,"Providing FRP Gratings for existing Storm Water Drain at Vidwan Sundaram Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14842,Storm Water Drain,Completed,NJ-TEYNAMPET,113,115000,"Providing FRP Gratings for existing Storm Water Drain at Vaidyanathan Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14845,Storm Water Drain,Completed,NJ-TEYNAMPET,113,233000,"Providing FRP Gratings for existing Storm Water Drain at Veerabadran Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14847,Storm Water Drain,Completed,NJ-TEYNAMPET,113,108000,"Providing FRP Gratings for existing Storm Water Drain at Duraisamy Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14855,Storm Water Drain,Completed,NJ-TEYNAMPET,113,359000,"Providing FRP Gratings for existing Storm Water Drain at Cathedral Garden Road in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14858,Storm Water Drain,Completed,NJ-TEYNAMPET,113,93000,"Providing FRP Gratings for existing Storm Water Drain at Krishna Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14860,Storm Water Drain,Completed,NJ-TEYNAMPET,113,135000,"Providing FRP Gratings for existing Storm Water Drain at Jambulingam Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14861,Storm Water Drain,Completed,NJ-TEYNAMPET,113,240000,"Providing FRP Gratings for existing Storm Water Drain at Bala Muthu krishna Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14868,Storm Water Drain,Completed,NJ-TEYNAMPET,113,114000,"Providing FRP Gratings for existing Storm Water Drain at Porur Somasundaram Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14869,Storm Water Drain,Completed,NJ-TEYNAMPET,113,236000,"Providing FRP Gratings for existing Storm Water Drain at Parthasarathy puram in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14871,Storm Water Drain,Completed,NJ-TEYNAMPET,113,94000,"Providing FRP Gratings for existing Storm Water Drain at Kolamani Amman Koil Street in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14877,Storm Water Drain,Completed,NJ-TEYNAMPET,113,67000,"Providing FRP Gratings for existing Storm Water Drain at Pillayar koil Lane in Div 113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14883,Buildings,Completed,NJ-TEYNAMPET,124,768000,"Proposed Construction of Rain water Harvesting at various Corporation Buildings and Parks in Div-124,Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14900,Roads,Completed,NJ-TEYNAMPET,116,547000,"PROVIDING CATTLE TRAP AND RAILING AT SUNGUVAR STREET IN DN-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/14948,Buildings,Completed,NJ-TEYNAMPET,113,535000,"Construction of compound wall for Dispensary at Noor Veerasamy street in Div 113, Unit-26,Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/1497,Buildings,Completed,NJ-TEYNAMPET,123,900000,"Proposed Construction of toilet block for Chennai Middle School at Eldams Road in division-123, Unit-25, Zone-9",MLACDS,9,2015-16,2017-18 NJ/2015-16/15064,Storm Water Drain,Completed,NJ-TEYNAMPET,126,995000,RELAYING OF EXISTING FOOTPATH AT SANTHOM HIGH ROAD NEAR SANGEETHA HOTEL AND NEAR AMMA UNAVAGAM IN DIV-126 UNIT-25 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/15065,Roads,Completed,NJ-TEYNAMPET,126,985000,ATTENDING PATCH WORK AT VARIOUS STREETS IN DIV-126 UNIT-25 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/1513,Parks,Completed,NJ-TEYNAMPET,119,310000,"ANNUAL MAINTENENCE OF PARK OF PARTHASARATHY PARK(TWO YEAR) AT V.M STREET IN DIVISION-119,UNIT-24,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/15230,Buildings,Completed,NJ-TEYNAMPET,125,405000,"Providing Concrete Platforms for Dust bins at Various Streets in Div 125,Unit-25,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/15592,Buildings,Completed,NJ-TEYNAMPET,109,770000,"DISMANTLING AND RECONSTRUCTION OF COMMPOUND WALL IN GILL NAGAR PARK AT SANMUGANAR SALAI SIDE IN DN-109, U-24, Z-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/15595,Buildings,Completed,NJ-TEYNAMPET,118,995000,"FORMING OF VOLLEY BALL COURT AT MUTHIAH STREET IN DIV-118, UNIT-24, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/15599,Buildings,Completed,NJ-TEYNAMPET,118,285000,"IMPROVEMENTS TO ICDS BUILDING CENTRE NO 080305 AT MUTHAIYA STREET IN DN 118,UNIT 24,ZONE 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/15600,Buildings,Completed,NJ-TEYNAMPET,118,315000,"IMPROVEMENTS TO ICDS BUILDING CENTRE NO 080303 and 080304 AT POES ROAD IN DN 118,UNIT 24,ZONE 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/15601,Buildings,Completed,NJ-TEYNAMPET,118,335000,"IMPROVEMENTS TO ICDS BUILDING CENTRE NO 080301 and 080302 AT AMMAIAPPAN LANE IN DN 118,UNIT 24,ZONE 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/1564,Buildings,Completed,NJ-TEYNAMPET,116,967000,"IMPROVEMENTS THE WARD COUNCILOR BUILDINGS IN Dr.BESANT ROAD IN Dn-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/15836,Storm Water Drain,Completed,NJ-TEYNAMPET,121,619000,"CONSTRUCTION OF STORM WATER DRAIN AT DOOR NO OLD 70/ NEW NO 144 AT P.S SIVA SAMY SALAI IN DN-121,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/15851,Buildings,Completed,NJ-TEYNAMPET,119,760000,"IMPROVEMENTS TO THE NNMV CENTERS 3360303030220,221 AT SAIVA MUTHAYA STREET IN DN-119 U-24 Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/15858,Buildings,Completed,NJ-TEYNAMPET,120,130000,PROVIDING VIP TOILETS ARRANGEMANTS FOR REBUBLIC DAY IN LADY WELINGTON SCHOOL CAMPUS IN DN-120 U-27 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/15890,Buildings,Completed,NJ-TEYNAMPET,114,508000,"PROVIDING R.O WATER PURIFYING MACHINE AND WATER SUPPLY ARRANGEMENTS TO AMMA UNAVAGAM AT VALLABA AGRAHARAM STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/15922,Buildings,Completed,NJ-TEYNAMPET,109,590000,Providing and laying Interlocking Paver Blocks Inside Division Office at Shanmuganar Salai in DN-109 Unit-24 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/15989,Storm Water Drain,Completed,NJ-TEYNAMPET,114,784000,"Providing Rain water harvesting structure(Well ring type with cover slab) at corporation buildings in Div-114, U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/15995,Buildings,Completed,NJ-TEYNAMPET,116,40000,"IMPROVMENT TO SEPTIC TANK FOR PUBLIC CONVENIENCE AT MARINA SERVICE ROAD IN DN-116, UNIT-27, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/16052,Buildings,Completed,NJ-TEYNAMPET,126,400000,"FORMING ROOF TOP GARDENING IN CHENNAI HIGH SCHOOL AT SINGERI MUTT ROAD IN DN 126,UNIT-26, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/16055,Buildings,Completed,NJ-TEYNAMPET,119,750000,PROVIDING NEW BOREWELL ARRANGEMENTS AND IMPROVEMENTS TO THE URUTHU SCHOOL BUILDING AT PETERS ROAD IN DN-119 U-24 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/16057,Buildings,Completed,NJ-TEYNAMPET,125,761000,"IMPROVEMENTS TO ICDS REPAIRS IN VARIOUS STREET AND SUPPLY AND FIXING BABY FRIENDLY TOILET CENTER NO;33603110414,33603110417,3360311419",Own Sources,9,2015-16,2016-17 NJ/2015-16/16254,Buildings,Completed,NJ-TEYNAMPET,126,700000,"PROVIDING ANTI SKID TILES AROUND WOOODEN FLOOR, PLUMBING WORK ,ELECTRICAL WORK ,BADMINTON COURT INSIDE OF ALFONSAPLAYGROUND AT SOUTH CANAL BANK ROAD, MANDAVELIPAKKAM, DIVISION.126, UNIT.25, ZONE.9",Own Sources,9,2015-16,2018-19 NJ/2015-16/16647,Buildings,Completed,NJ-TEYNAMPET,125,826000,IMPROVEMENTS TO KITCHEN SHED AND CONSTRUCTION OF SUMP AT KARANEESWARAR PAGODA STREET IN DIV -125 UNIT-25 ZONE-9,Own Sources,9,2015-16,2017-18 NJ/2015-16/16648,Buildings,Completed,NJ-TEYNAMPET,113,347000,"PROVIDING PLATFORM AROUND E-TOILET AND WATER SUPPLY ARRANGEMENTS AT HABIBULLAHA ROAD IN DIV 113, UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/16664,Parks,Completed,NJ-TEYNAMPET,114,110000,"Proposed construction of roof top garden at corporation office in div-114, u-27, z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/16690,Footpath,Completed,NJ-TEYNAMPET,119,997000,"ATTENDING PATCH WORK WITH BC 40MM THICK BY USING PAVER FINISHER AT VARIOUS STREETS IN DIVISION-119 UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/16734,Roads,Completed,NJ-TEYNAMPET,113,913000,"Attending the Patch work with BC 40mm thick by Paver Finisher at Cathedral Garden Road,Kodambakkam High Road Bala Muthukrishnan Street Valluar Kottam High Road and Various Damaged Roads in Dn-113 Unit-26 Zone-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/16891,Buildings,Completed,NJ-TEYNAMPET,119,768000,IMPROVEMENTS TO THE COC SCHOOL BUILDING(ELECTION BOOTHS) AT SAIVA MUTHAYA 6 TH STREET IN DN-119 U-24 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/16892,Footpath,Completed,NJ-TEYNAMPET,119,985000,PROVIDING FLOORING ARRANGEMENTS FOR WASHING AREA IN DHOBI KANA AT MUTHAYA GARDEN STREET IN DN-119 U-24 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/16894,Footpath,Completed,NJ-TEYNAMPET,119,615000,LAYING GRANITE FLOORING ARROUND THE DIVISION OFFICE AT CIT COLONY IN DN-119 U-24 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/16899,Buildings,Completed,NJ-TEYNAMPET,119,985000,ADDITIONAL IMPROVEMENTS WORK FOR SI OFFICE AT UNIT OFFICE CAMPUS IN DN-119 U-24 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/17044,Buildings,Completed,NJ-TEYNAMPET,124,588000,"IMPROVEMENTS TO THE PUBLIC CONVEYENCE AT SARADHAPURAM IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/17204,Roads,Completed,NJ-TEYNAMPET,126,359000,"Removal of Fallen Tree due to North east mansoon in Dn-126.Unit-25,Zone-9",Own Sources,9,2015-16,2019-20 NJ/2015-16/17208,Parks,Completed,NJ-TEYNAMPET,120,995000,"CONSTRUCTION OF ROAD SIDE PARK AT LLOYDS COLONY IN DN-120, U-27 Z-9",MLACDS,9,2015-16,2016-17 NJ/2015-16/17209,Parks,Completed,NJ-TEYNAMPET,120,990000,"WATER SUPPLY AND ELECTRICAL WORKS ,GREENERY ARRANGEMENTS FOR ROAD SIDE PARK AT LLOYDS COLONY IN DN-120 U-27 Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/17381,Buildings,Completed,NJ-TEYNAMPET,116,895000,"LAYING WHEATHERING COARSE,PRESSED TILES AND CHEMICAL TREATMENT IN CMS AT QUAID-E-MILLATH ROAD IN Dn-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/17402,Buildings,Completed,NJ-TEYNAMPET,109,230000,"IMPROVEMENTS AND RAISING OF DAMAGED RETAINING WALL AT SANKARAPURAM 1ST STREET IN DIV 109,UNIT-24,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/17403,Buildings,Completed,NJ-TEYNAMPET,109,230000,"IMPROVEMENTS AND RAISING OF DAMAGED RETAINING WALL AT VADAGARAM SALAI IN DIV 109,UNIT-24, ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/17405,Buildings,Completed,NJ-TEYNAMPET,109,187000,"IMPROVEMENTS AND RAISING OF DAMAGED RETAINING WALL AT BASHA STREET IN DIV 109,UNIT-24,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/17406,Buildings,Completed,NJ-TEYNAMPET,109,430000,"SUPPLY OF PRIVATE LABOURS 60 DAYS FOR FLOOD WORK AND FOR CLEANING OF BUS ROUTE ROADS IN DIV 109,110 AND 111 ,UNIT-24,ZONE-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/17407,Buildings,Completed,NJ-TEYNAMPET,109,253000,"IMPROVEMENTS AND RAISING OF DAMAGED RETAINING WALL AT THIRUVENKADAPURAM 2ND STREET IN DIV 109,UNIT-24,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/17415,Storm Water Drain,Completed,NJ-TEYNAMPET,111,529000,"FIXING FRP VERTICAL GRATING AND IMPROVEMENTS TO DAMAGED MANHOLES OF STORM WATER DRAIN AT MODEL SCHOOL ROAD WITH A LENGTH OF 621m IN DN 111,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/17522,Buildings,Completed,NJ-TEYNAMPET,111,990000,CONSTRUCTION OF SUMP AND WATER SUPPLY ARRANGEMENTS TO CHENNAI HIGHER SECONDARY SCHOOL AT MODEL SCHOOL ROAD IN DIV 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/17523,Buildings,Completed,NJ-TEYNAMPET,111,980000,IMPROVEMENTS TO BASKET BALL GROUND AT CHENNAI HIGHER SECONDARY SCHOOL AT MODEL SCHOOL ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2017-18 NJ/2015-16/17524,Buildings,Completed,NJ-TEYNAMPET,111,475000,IMPROVEMENTS TO MODEL SCHOOL IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/17528,Buildings,Completed,NJ-TEYNAMPET,111,998000,CHANGE OF DAMAGED ASBESTOS ROOF INTO G.I SHEET WITH FALSE CEILING TO CHENNAI PRIMARY SCHOOL (COCHIN HOUSE) AT ANDERSON ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2017-18 NJ/2015-16/17532,Parks,Completed,NJ-TEYNAMPET,113,995000,"PROVIDING FIXING STAINLESSTEEL HAND RAIL FOR ARROUND WALLKER PATH AT SHARMA PARK HABIBULLAH ROAD(UNDER WARD COUNCILLOR SCHEME 2015-2016) IN DN 113,UNIT 26,ZONE 9",Earmarked Fund,9,2015-16,2016-17 NJ/2015-16/17541,Roads,Completed,NJ-TEYNAMPET,119,690000,BLOCK AND WHITE PAINTING AND IMPROVEMENTS TO THE FOOTPATH AT VARIOUS STREETS IN DIVISION -119 UNIT-24 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/17542,Roads,Completed,NJ-TEYNAMPET,121,970000,Attending the Patch work with DBM 50MM Thick by Paver Finisher at Avvai Shanmugam Salai in Dn-121 Unit-27 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/17686,Storm Water Drain,Completed,NJ-TEYNAMPET,122,995000,PROVIDING AND LAYING PVC PIPE LINE ACROES THE STREET TO OPEN CANAL FOR DRAIN OUT THE RAIN WATER AT ALAYAMMAN KOVIL STREET IN DIVSION 122 UNIT 26 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/17687,Buildings,Completed,NJ-TEYNAMPET,122,600000,PROVIDING WATER SUPPLY ARRANGEMENTS TO E-TOILET AT VARIOUS LOCATION IN DIVISION 122 UNIT 26 ZONE 09,Own Sources,9,2015-16,2017-18 NJ/2015-16/17708,Roads,Completed,NJ-TEYNAMPET,113,813000,"ATTENDING CONCRETE PATCHES USING M20 &M40 CONCRETE IN IMPORTANT BRR/IRR ROADS IN DIV-113,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/17844,Parks,Completed,NJ-TEYNAMPET,122,940000,"ANNUAL MAINTENANCE OF PARK FOR ONE YEAR AT TURN BULLS ROAD (INCLUDING WATER SUPPLY BY PRIVATE LORRY) IN DN-122,UNIT-26,ZONE-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/1797,Road Cut,Completed,NJ-TEYNAMPET,114,152000,"RESTORATION OF ROAD CUT ROADCUT MADE BY CMWSSB AT SUBATHRAL ST IN DN-114,UNIT-27,ZONE-9.",Deposit Works,9,2015-16,2016-17 NJ/2015-16/1809,Buildings,Completed,NJ-TEYNAMPET,116,875000,"IMPROVEMENTS TO AYURVEDIC DISPENSARY AT NAMACHIVAYAM STREET IN Dn-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/1810,Buildings,Completed,NJ-TEYNAMPET,116,821000,"IMPROVEMENTS TO NUHM AT Dr.BESANT ROAD INSIDE UNIT-27 OFFICE CAMPUS IN DIV-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18269,Buildings,Completed,NJ-TEYNAMPET,117,800000,"PROPOSED CONSTRUCTION OF GALVANISED IRON SHEET ROOFING ABOVE RATION SHOP IN DR.GIRIAPPA ROAD IN DIV 117,UNIT-26,ZONE-9 (UNDER WARD COUNCILLOR FUND SCHEME)",Own Sources,9,2015-16,2016-17 NJ/2015-16/18276,Buildings,Completed,NJ-TEYNAMPET,117,770000,"IMPROVEMENTS TO GYM BUILDING AT (IN BETWEEN BLOCK 32 AND 33) DR THOMAS ROAD IN DIV 117,UNIT-26,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/18280,Buildings,Completed,NJ-TEYNAMPET,117,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT VIJAYARAGHAVA ROAD (BEHIND VIJAYA RAGHAVA ROAD PC) IN DIV 117,UNIT-26,ZONE-9 (UNDER WARD COUNCILLOR FUND )",Own Sources,9,2015-16,2016-17 NJ/2015-16/18424,Roads,Completed,NJ-TEYNAMPET,110,340000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT POONANGAIPURAM 1ST STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/18426,Roads,Completed,NJ-TEYNAMPET,118,960000,ATTENDING BT PATCH WORK WITH BC 40MM THICK BY USING PAVER FINISHER AT VARIOUS STREETS IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/18449,Buildings,Completed,NJ-TEYNAMPET,126,234000,IMPROVEMENT OF AMMA UNAVAGAM IN SANTHOM HIGH ROAD IN DN-126 UNIT-25 ZONE - 9,Own Sources,9,2015-16,2016-17 NJ/2015-16/18487,Roads,Completed,NJ-TEYNAMPET,126,626000,"Flood damaged repair works in Leith Castle South Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18488,Storm Water Drain,Completed,NJ-TEYNAMPET,126,188000,"Flood damaged repair works in Lieth Castle Centre Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18489,Roads,Completed,NJ-TEYNAMPET,125,990000,ATTENDING BT PATCH WORK WITH PAVER FINISHER AT VARIOUS STREETS IN DIVISION 125 UNIT 25 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/18490,Roads,Completed,NJ-TEYNAMPET,121,990000,Attending the Patch work with GSB and WMM at Avvai Shanmugam Salai in Dn-121 Unit-27 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/18506,Buildings,Completed,NJ-TEYNAMPET,120,580000,"CONVERTING THE STORE ROOM INTO E-SEVA MAIYAM IN 120-DIVISION OFFICE AT GAJAP[ATHY 1ST LANE IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18514,Buildings,Completed,NJ-TEYNAMPET,117,999000,"PROPOSED DESILTING WORK USING POCLAIN AND FLOAT PLATFORM IN MAMBALAM CANAL FROM G.N.CHETTY ROAD TO VIJAYA RAGAVA ROAD (NAKEERAN NAGAR) IN DN 117,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18516,Buildings,Completed,NJ-TEYNAMPET,117,990000,"PROPOSED DESILTING WORK USING POCLAIN AND FLOAT PLATFORM IN MAMBALAM CANAL FROM VIJAYA RAGAVA ROAD TO THEYAGARAYA ROAD (THIRU-VI-KA KUDIYEERUPU) IN DN 117,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18517,Buildings,Completed,NJ-TEYNAMPET,113,997000,"Desilting of Storm Water Drain at Various Streets in div 113, Unit-26,zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18529,Roads,Completed,NJ-TEYNAMPET,124,360000,"Removal of Fallen Tree due to North east mansoon in Dn-124.Unit-25,Zone-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/18546,Buildings,Completed,NJ-TEYNAMPET,124,999000,"Desilting and Removal of floating materials / Hyacinth garbages and Preventive measures for mosquito menance along Buckingham canal by using poclain vehicle along Kalvivaru Street 0m to 100m (from Mk amman koil st Railway station to Kutchery Road ) in div-124,unit-25, zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/1859,Buildings,Completed,NJ-TEYNAMPET,113,685000,IMPROVEMENTS TO ICDS CENTER NO 02044 AT DHARMAPURAM MAIN ROAD IN DIVISION 113 UNIT 26 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/18600,Storm Water Drain,Completed,NJ-TEYNAMPET,113,997000,"IMPROVEMENTS TO STORM WATER DRAIN AT HABIBULLAH ROAD FROM KRISHNABAI STREET CHAINAGE 270M TO 360M IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18602,Storm Water Drain,Completed,NJ-TEYNAMPET,113,998000,"IMPROVEMENTS TO STORM WATER DRAIN AT HABIBULLAH ROAD FROM KRISHNABAI STREET CHAINAGE 450M TO NORTH USMAN ROAD IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18603,Roads,Completed,NJ-TEYNAMPET,114,998000,"SUPPLYING WETMIX , SAND FOR POT HOLES AT VARIOUS PLACES IN DN-114,115,116,120 AND 121 ,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18640,Buildings,Completed,NJ-TEYNAMPET,110,719000,"De-watering of Rain Water at low lying area using Diesel Pump set motor in Div 110,Unit-24,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18672,Roads,Completed,NJ-TEYNAMPET,115,989000,"PROVIDING AND FIXING SS GRILL FOR CENTER MEDIAN IN WEST COTT ROAD FROM CHAINAGE 0-105m IN DN -115 ,U-27,Z-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/18673,Roads,Completed,NJ-TEYNAMPET,115,989000,"PROVIDING AND FIXING SS GRILL FOR CENTER MEDIAN IN WEST COTT ROAD FROM CHAINAGE 105-210m IN DN -115 ,U-27,Z-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/18674,Roads,Completed,NJ-TEYNAMPET,115,989000,"PROVIDING AND FIXING SS GRILL FOR CENTER MEDIAN IN WEST COTT ROAD FROM CHAINAGE 210-315m IN DN -115 ,U-27,Z-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/18675,Roads,Completed,NJ-TEYNAMPET,115,989000,"PROVIDING AND FIXING SS GRILL FOR CENTER MEDIAN IN WEST COTT ROAD FROM CHAINAGE 315-420 m IN DN -115 ,U-27,Z-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/18690,Buildings,Completed,NJ-TEYNAMPET,117,595000,"Repairs and Improvements to Public Conveyance at Mambalam High Road and Giriappa Road (Drivers colony) in 117,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18710,Roads,Completed,NJ-TEYNAMPET,124,408000,"Flood Damaged repair work in Vedha Desikar Street in Division-124, Unit-25, Zone-9.",Grants,9,2015-16,2016-17 NJ/2015-16/18711,Roads,Completed,NJ-TEYNAMPET,124,174000,"Flood Damaged repair work in R.K Mutt Road in Division-124, Unit-25, Zone-9.",Grants,9,2015-16,2016-17 NJ/2015-16/18713,Roads,Completed,NJ-TEYNAMPET,125,836000,"Flood Damaged repair work in Bazaar Road in Division-125, Unit-25, Zone-9",Grants,9,2015-16,2016-17 NJ/2015-16/18714,Roads,Completed,NJ-TEYNAMPET,124,348000,"Flood Damaged repair work in Karneeswarar Koil Street in Division-125, Unit-25, Zone-9",Grants,9,2015-16,2016-17 NJ/2015-16/18722,Buildings,Completed,NJ-TEYNAMPET,123,326000,"PROPOSED CONSTRUCTION OF SUMP FOR CHENNAI MIDDLE SCHOOL AT ST. MARY'S ROAD IN DIV-123, UNIT-25, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18725,Buildings,Completed,NJ-TEYNAMPET,110,960000,"REPAIRS TO LEAKY TERRACE ROOF AT CHENNAI GIRLS HIGHER SECONDARY SCHOOL.SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18760,Buildings,Completed,NJ-TEYNAMPET,117,595000,"Repairs and Improvements to Public Conveyance at M.K.Radha Nagar and SSpuram in Div-117,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18852,Buildings,Completed,NJ-TEYNAMPET,126,54000,"Flood damaged repair works in Jonahan Street Lane in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18853,Roads,Completed,NJ-TEYNAMPET,126,310000,"Flood damaged repair works in West Circular Road in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18854,Roads,Completed,NJ-TEYNAMPET,126,207000,"Flood damaged repair works in Devanathan Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/18993,Roads,Completed,NJ-TEYNAMPET,110,408000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT SIVAGANGA ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/18994,Roads,Completed,NJ-TEYNAMPET,110,946000,"Attending patch work by using cement concrete for various streets in Div 110, Unit-24,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19007,Storm Water Drain,Completed,NJ-TEYNAMPET,126,695000,"Improvement of Storm Water Drain from Madha Church Road to 3rd Trust Link Street (up 0 to 50 m ) in Div 126,Unit-25,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19014,Storm Water Drain,Completed,NJ-TEYNAMPET,126,695000,"Improvement of Storm Water Drain from Madha Church Road to 3rd Trust Link Street (up 50 to 100 m ) in Div 126,Unit-25,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19135,Roads,Completed,NJ-TEYNAMPET,126,929000,"White Marking in both Sides and pedestrian Crossings and Fixing RPM Studs &median Marker at Santhome High Road in Div-126,Unit-25,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19160,Buildings,Completed,NJ-TEYNAMPET,114,2364000,"Out sourcing Men and Material for cleaning of public convenience at Marina service road in dn-114,116 and 125 Unit-27A Zone-9.(6-Location-180 days)",Own Sources,9,2015-16,2016-17 NJ/2015-16/19191,Roads,Completed,NJ-TEYNAMPET,111,105000,"Improvements the Traffic Island in Junction of Anna Salai and Peters Road at Dn- 111,U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/19209,Roads,Completed,NJ-TEYNAMPET,111,980000,ATTENDING CEMENT CONCRETE PATCH WORK AT VARIOUS DAMAGED ROADS IN DIVISION 111 AND 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/19212,Footpath,Completed,NJ-TEYNAMPET,111,997000,"PROPOSED CONSTRUCTION OF SIDE DRAIN AT THIDEER NAGAR GREAMS ROAD IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/19213,Storm Water Drain,Completed,NJ-TEYNAMPET,118,998000,CONSTRUCTION OF STORM WATER DRAIN AT MAYOR SUNDER RAO ROAD FROM 81M TO 160M IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/19214,Roads,Completed,NJ-TEYNAMPET,118,990000,"IMPROVEMENTS TO FOOTPATH AND KERB WALL PAINTING AT BINNY ROAD,T.T.K ROAD,KASTURI ESTATE CROSS STREETS AND CATHEDRAL ROAD IN DIVISION 118 UNIT 24 ZONE 09",Own Sources,9,2015-16,2016-17 NJ/2015-16/19215,Storm Water Drain,Completed,NJ-TEYNAMPET,118,995000,CONSTRUCTION OF STORM WATER DRAIN AT MAYOR SUNDER RAO ROAD FROM 161M TO 240M IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/19218,Roads,Completed,NJ-TEYNAMPET,122,370000,De-watering of Stagnating Rain water at low lying area using Diesel pump set motor in Division 122 Unit 26 Zone 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/19219,Roads,Completed,NJ-TEYNAMPET,122,980000,ATTENDING CEMENT CONCRETE PATCH WORK AT VARIOUS DAMAGED ROADS IN DIVISION 122 UNIT 26 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/19221,Storm Water Drain,Completed,NJ-TEYNAMPET,122,820000,CONSTRUCTION OF STORM WATER DRAIN ACROSS TTK ROAD (JUNCTION OF KB DASAN SALAI) IN DIVISION 122 UNIT 26 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/1927,Buildings,Completed,NJ-TEYNAMPET,126,600000,IMPROVEMENT TO ANGANVADI CENTER IN ALFONSA GROUND AT SOUTH CANAL BANK ROAD DIV 126 U 25 Z 9,Own Sources,9,2015-16,2016-17 NJ/2015-16/19287,Storm Water Drain,Completed,NJ-TEYNAMPET,124,470000,"Desilting of Storm Water Drain at various streets in Div 124,Unit-25,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19370,Roads,Completed,NJ-TEYNAMPET,112,990000,"Attending patch work for B.T.roads damaged during North east monsoon at Various locations in Dn112, unit-26,zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19381,Footpath,Completed,NJ-TEYNAMPET,110,185000,"IMPROVEMENTS TO FOOT PATH AT LAKE AREA 2ND CROSS STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19382,Footpath,Completed,NJ-TEYNAMPET,110,151000,"IMPROVEMENTS TO FOOT PATH AT LAKE AREA 3RD CROSS STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19467,Footpath,Completed,NJ-TEYNAMPET,110,332000,"Improvements to foot path at lake area 4th cross street in dn 110,unit 24,zone 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19469,Footpath,Completed,NJ-TEYNAMPET,110,252000,"IMPROVEMENTS TO FOOT PATH AT LAKE AREA 5TH CROSS STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19470,Footpath,Completed,NJ-TEYNAMPET,110,173000,"IMPROVEMENTS TO FOOT PATH AT LAKE AREA 6TH CROSS STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19471,Footpath,Completed,NJ-TEYNAMPET,110,159000,"IMPROVEMENTS TO FOOT PATH AT LAKE AREA 7 TH CROSS STREET IN DIVISION- 110, UNIT 24, ZONE- 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19482,Footpath,Completed,NJ-TEYNAMPET,110,281000,"IMPROVEMENTS TO FOOT PATH AT LAKE AREA 1ST CROSS STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19501,Buildings,Completed,NJ-TEYNAMPET,123,1000000,"BLACK AND WHITE WASHING FOR FOOTPATH KERB AT VARIOUS ROAD IN DIV-123, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/19513,Footpath,Completed,NJ-TEYNAMPET,113,998000,"FORMING FOOT PATH AT HABIBULLAH ROAD FROM THIRUMALAI PILLAI ROAD TO DOOR NO 66/141 ON BOTH SIDES TOWARDS EASTERN SIDE IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19606,Roads,Completed,NJ-TEYNAMPET,117,1000000,REPAIRS AND IMPROVEMENTS TO SLUM TENEMENT CEMENT CONCRETE AT VARIOUS ROADS IN DN-117 UNIT-26 ZONE-9,Own Sources,9,2015-16,2017-18 NJ/2015-16/19610,Footpath,Completed,NJ-TEYNAMPET,117,1000000,BLACK AND WHITE WASHING FOR FOOTPATH KERB AT VARIOUS BRR ROAD IN DN-117 UNIT-26 ZONE-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/19658,Buildings,Completed,NJ-TEYNAMPET,114,558000,"PROVIDING NAME BOARDS FOR E-SEVA MAIYAM AND PC'S IN DN-114,115,116,120 AND 121 UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19659,Buildings,Completed,NJ-TEYNAMPET,114,476000,"CONSTRUCTION OF STORM WATER DRAIN AT JN OF PILLAYAR KOIL STREET AND QUIDE-EMILLATH SALAI IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19667,Buildings,Completed,NJ-TEYNAMPET,115,352000,"ADDITIONAL IMPROVMENTS TO AMMA UNAVAGAM AT SOORAPPA STREET IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/19668,Roads,Completed,NJ-TEYNAMPET,115,593000,"IMPROVEMENTS AND PAINTING TO CMS AT SOORAPPA STREET IN DN.115, UNIT-27, ZONE-IX",Own Sources,9,2015-16,2016-17 NJ/2015-16/19670,Buildings,Completed,NJ-TEYNAMPET,114,455000,"CONSTRUCTION OF STORM WATER DRAIN AT SYDOJI STREET FROM DOOR NO OLD3.NEW 5 TO JN OF BELLS ROAD IN DN-114,UNIT-27,ZONE-5",Own Sources,9,2015-16,2016-17 NJ/2015-16/19821,Buildings,Completed,NJ-TEYNAMPET,114,995000,"PROVIDING BARRICADING ARRANGEMENT AND MONITORING TOWER IN VIEW OF KANNUMPONGAL FESTIVAL 2016 AT MARINA BEACH FROM NAPPIER BRIDGE TO LIGHT HOUSE IN DIV 114,116,120,121,125 U-25,U-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20036,Footpath,Completed,NJ-TEYNAMPET,114,976000,REPAIRS TO FOOTPATH AT VARIOUS ROAD IN DN-114 UNIT-27 ZONE-9,Own Sources,9,2015-16,2017-18 NJ/2015-16/20077,Roads,Completed,NJ-TEYNAMPET,109,890000,"ATTENDING THE PATCH WORK AND FILLING POT HOLES BY WMM AND CC AT SHANMUGANAR SALAI, THIRUVALLUAR PURAM 1ST STREET ,THIRUVENKATAM MAIN ROAD ,ARTHAREYAPURAM MAIN ROAD SHANKARAPURAM MAIN ROAD AND ANNA NEDUM PATHAI AND VARIOUS STREET IN DN-109 UNIT-24 ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/20109,Buildings,Completed,NJ-TEYNAMPET,114,523000,"REPAIRS TO PUBLIC CONVENIENCE AT VARIOUS ROAD (6) LOCATION IN DN-114 UNIT-24 ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20119,Buildings,Completed,NJ-TEYNAMPET,120,434000,MAINTENANCE OF ICDS CENTRE IN DN-120 UNIT-27 ZONE-9,Own Sources,9,2015-16,2017-18 NJ/2015-16/20181,Buildings,Completed,NJ-TEYNAMPET,120,546000,MAINTANANCE OF COC SCHOOL BUILDING IN DN-120 UNIT-27 ZONE-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/20308,Buildings,Completed,NJ-TEYNAMPET,114,998000,"PROVIDING PIPELINE AND CHAMBERS FOR DEDRAIN THR RAIN WATER FROMCLOW LYING AREA AT LOCK NAGAR IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/2042,Roads,Completed,NJ-TEYNAMPET,123,999000,"ATTENDING THE PATCH WORK AT ASHOKA STREET, ANANDHA STREET, BEEMANNA GARDEN STREET, LUZ AVENUE 5TH STREET IN DN.123,UNIT.25,ZONE.09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/20420,Roads,Completed,NJ-TEYNAMPET,113,16300,"FLOOD DAMAGED REPAIRS TO THE RAMANUJAM STREET IN DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20462,Parks,Completed,NJ-TEYNAMPET,126,152000,"Flood damaged repair works in 5th Trust Cross Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20463,Roads,Completed,NJ-TEYNAMPET,111,690000,"IMPROVEMENTS TO PLAY GROUND AT GOPALAPURAM IN DIVISION-111,UNIT-24,ZONE-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/20485,Roads,Completed,NJ-TEYNAMPET,126,968000,"Engaging mini lorry including 6 labours hiring for removal of excess sand on road and water table in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2019-20 NJ/2015-16/20501,Storm Water Drain,Completed,NJ-TEYNAMPET,118,993000,"PROVIDING AND FIXING FRP VERTICAL GRATTING AND CHUTE PIPE FOR EXISTING STORM WATER DRAIN AT CATHEDRAL ROAD IN DN- 118,UNIT 24, Zone-IX",Own Sources,9,2015-16,2016-17 NJ/2015-16/20572,Roads,Completed,NJ-TEYNAMPET,114,693000,"Flood Damaged repairs to the Big street in Div-114, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20573,Roads,Completed,NJ-TEYNAMPET,114,819000,"Flood Damaged repairs to the Mayor chiti babu street in Div-114, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20575,Roads,Completed,NJ-TEYNAMPET,114,183000,"Flood Damaged repairs to the CHELLA PILLAIYAR KOIL street in Div-114, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20577,Roads,Completed,NJ-TEYNAMPET,114,964000,"Flood Damaged repairs to the VICTORIA HOSTEL ROAD in Div-114, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20578,Roads,Completed,NJ-TEYNAMPET,114,221000,"Flood Damaged repairs to the ELLIS ROAD STREET in Div-114, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20579,Roads,Completed,NJ-TEYNAMPET,114,632000,"Flood Damaged repairs to the KUPPU MUTHU STREET in Div-114, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/20763,Roads,Completed,NJ-TEYNAMPET,110,313000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT HARRINGTON ROAD 3RD AVENUE IN DIVISION-110,UNIT-24,ZONE-09",Grants,9,2015-16,2016-17 NJ/2015-16/21130,Buildings,Completed,NJ-TEYNAMPET,117,275000,"Providing Water supply arrangements and Drainage for Public Conveyance at Dr.Giriappa South P.C,DR.Girippa North P.C, M.K.Radha Nagar P.C,S.S.Puram P.C and Theyagaraya Road P.C in Div 117,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21135,Roads,Completed,NJ-TEYNAMPET,117,366000,"Attending Cement Concrete patch work at various BRR/IRR Roads in Div 117,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/2144,Buildings,Completed,NJ-TEYNAMPET,111,975000,"MAINTENANCE OF PRE FABRICATED URINAL UNITS AT VARIOUS LOCATION IN DIVISIONS-109,110,111,118 AND 119 IN UNIT-24,ZONE-09 (PERIOD :06.06.2015 TO 06.05.2016 -11 MONTHS)",Own Sources,9,2015-16,2019-20 NJ/2015-16/21472,Roads,Completed,NJ-TEYNAMPET,126,349000,"Flood damaged repair works in Kuppaimedu road in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21473,Roads,Completed,NJ-TEYNAMPET,109,549000,Flood Damaged repairs to the Thiruvenkadapuram 2nd street in Dn-109 Unit-24 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/21476,Roads,Completed,NJ-TEYNAMPET,122,720000,"FLOOD DAMAGED REPAIRS TO THE ALWARPET STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21478,Roads,Completed,NJ-TEYNAMPET,126,76000,"Flood damaged repair works in Periyapalli Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21479,Roads,Completed,NJ-TEYNAMPET,110,645000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT SCHOOL ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21480,Roads,Completed,NJ-TEYNAMPET,109,340000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT HARRINGTON ROAD 4TH AVENUE IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21482,Roads,Completed,NJ-TEYNAMPET,110,681000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT AVENUE ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21483,Roads,Completed,NJ-TEYNAMPET,122,485000,"FLOOD DAMAGED REPAIRS TO THE BOAT CLUB 1ST AVENUE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21484,Roads,Completed,NJ-TEYNAMPET,110,837000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT LAKE AREA 1ST MAIN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21485,Roads,Completed,NJ-TEYNAMPET,110,824000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT SIR MATHAVAN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21486,Roads,Completed,NJ-TEYNAMPET,110,209000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT HARRINGTON ROAD 2ND AND 6TH AVENUE IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21488,Roads,Completed,NJ-TEYNAMPET,110,350000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT LAKE AREA 2ND CROSS STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21489,Roads,Completed,NJ-TEYNAMPET,122,450000,"FLOOD DAMAGED REPAIRS TO THE BOAT CLUB 2ND AVENUE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21490,Roads,Completed,NJ-TEYNAMPET,122,115000,"FLOOD DAMAGED REPAIRS TO THE CRESCENT STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21493,Roads,Completed,NJ-TEYNAMPET,122,435000,"FLOOD DAMAGED REPAIRS TO THE PUGHS ROAD (PART) IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21494,Roads,Completed,NJ-TEYNAMPET,113,130000,"FLOOD DAMAGED REPAIRS TO THE VIDHYODAYA 2ND STREET IN DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21501,Roads,Completed,NJ-TEYNAMPET,109,222000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT VANNIAR STREET IN DIVISION-109,UNIT-24,ZONE-09",Grants,9,2015-16,2016-17 NJ/2015-16/21502,Roads,Completed,NJ-TEYNAMPET,109,389000,Flood Damaged repairs to the Sherfudeen Street in Dn-109 Unit-24 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/21503,Roads,Completed,NJ-TEYNAMPET,109,132000,Flood Damaged repairs to the Selva vinayakar Koil Street in Dn-109 Unit-24 Zone-09,Own Sources,9,2015-16,2016-17 NJ/2015-16/21504,Roads,Completed,NJ-TEYNAMPET,113,196000,"Flood Damaged repairs to the Vidhyodaya East main Road IN DIV 113, U 26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21507,Roads,Completed,NJ-TEYNAMPET,113,261000,"Flood Damaged Repairs to Vidyodaya II Cross Street in Div 113, U -26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21525,Roads,Completed,NJ-TEYNAMPET,125,805000,"Flood Damaged repair work in Devadi street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21534,Roads,Completed,NJ-TEYNAMPET,113,130000,"Flood Damaged Repairs to Chockalingam Street in Div 113, U -26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21552,Roads,Completed,NJ-TEYNAMPET,126,75000,"Flood damaged repair works in Arulappan Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21554,Roads,Completed,NJ-TEYNAMPET,113,449000,"Flood Damaged Repairs to Melpadimuthu Street in Div 113, U-26, z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21556,Roads,Completed,NJ-TEYNAMPET,124,46000,"FLOOD DAMAGED REPAIRS TO MANDAVELI STREET ,MANDAVELI LANE, SOLAIAPPAN STREET, NATTU MUTHU STREET, AND KESAVAPERUMAL STREET IN DIV-124, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21557,Roads,Completed,NJ-TEYNAMPET,126,432000,"Flood damaged repair works in 4th Trust Link Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21561,Roads,Completed,NJ-TEYNAMPET,113,470000,"Flood Damaged Repairs to Balamuthu krishna street in Div 113, U-26, z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21562,Roads,Completed,NJ-TEYNAMPET,118,855000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT AMMAIAPPAN STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21563,Roads,Completed,NJ-TEYNAMPET,122,700000,"FLOOD DAMAGED REPAIRS TO THE CHITHARANJAN SALAI IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21567,Roads,Completed,NJ-TEYNAMPET,126,216000,"Flood damaged repair works in Jonahan Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21568,Roads,Completed,NJ-TEYNAMPET,111,150000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT GULAM ABBAS ALIGHAN BAHADUR STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21570,Roads,Completed,NJ-TEYNAMPET,113,170000,"Flood Damaged Repairs to Saradhambal street in Div 113, U-26, z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21573,Roads,Completed,NJ-TEYNAMPET,126,201000,"Flood damaged repair works in Malaiyappan Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21575,Roads,Completed,NJ-TEYNAMPET,126,916000,"Flood damaged repair works in Norton Road in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21576,Roads,Completed,NJ-TEYNAMPET,113,295000,"Flood Damaged Repairs to Kumarappa Street in Div 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21578,Roads,Completed,NJ-TEYNAMPET,111,810000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT GREAMS LANE IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21579,Roads,Completed,NJ-TEYNAMPET,116,250000,"Flood Damaged repairs to the Narayana Krishnarajapuram in Div-116, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21581,Roads,Completed,NJ-TEYNAMPET,113,193000,"Flood Damaged Repairs to Noorveerasamy street in Div 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21583,Roads,Completed,NJ-TEYNAMPET,125,567000,"Flood Damaged repair work in Valleswarar Koil street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21586,Roads,Completed,NJ-TEYNAMPET,116,380000,"Flood Damaged repairs to the Peyalwar Koil Street in Div-116, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21587,Roads,Completed,NJ-TEYNAMPET,126,1000000,"Flood damaged repair works in 2nd Trust Main road Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21588,Roads,Completed,NJ-TEYNAMPET,122,98000,"FLOOD DAMAGED REPAIRS TO THE CENOTAPH 2ND LANE IN DIV-122, UNIT-26, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21591,Roads,Completed,NJ-TEYNAMPET,116,500000,"Flood Damaged repairs to the Thulasingaperumal 2nd lane in Div-116, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21593,Roads,Completed,NJ-TEYNAMPET,113,183000,"Flood Damaged Repairs to Krishna Street in Div 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21595,Roads,Completed,NJ-TEYNAMPET,111,1600000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT ANDERSON ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21596,Roads,Completed,NJ-TEYNAMPET,126,340000,"Flood damaged repair works in 2nd Trust Link Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21597,Roads,Completed,NJ-TEYNAMPET,116,219000,"Flood Damaged repairs to the Old Firewood Street in Div-116, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21602,Roads,Completed,NJ-TEYNAMPET,125,419000,"Flood Damaged repair work in Appu street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21604,Roads,Completed,NJ-TEYNAMPET,113,310000,"Flood Damaged Repairs to Nageshwara Road in Div 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21606,Roads,Completed,NJ-TEYNAMPET,126,305000,"Flood damaged repair works in Trustpakkam North Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21607,Roads,Completed,NJ-TEYNAMPET,111,472000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT COLLEGE LANE IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21608,Roads,Completed,NJ-TEYNAMPET,125,406000,"Flood Damaged repair work in G.N street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21610,Roads,Completed,NJ-TEYNAMPET,113,299000,"Flood Damaged Repairs to Mohan Kumaramangalam Street in Div 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21611,Roads,Completed,NJ-TEYNAMPET,126,534000,"Flood damaged repair works in Trustpakkam South Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21613,Roads,Completed,NJ-TEYNAMPET,123,155000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT THIRUVALLUVAR SALAI IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21615,Roads,Completed,NJ-TEYNAMPET,116,588000,"Flood Damaged repairs to the Kasim Ali 1st Street in Div-116, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21617,Roads,Completed,NJ-TEYNAMPET,126,305000,"Flood damaged repair works in Thiruvalluvarpet Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21620,Roads,Completed,NJ-TEYNAMPET,125,367000,"Flood Damaged repair work in Nainar Nadar street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21621,Roads,Completed,NJ-TEYNAMPET,116,392000,"Flood Damaged repairs to the Sunguvar Street in Div-116, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21625,Roads,Completed,NJ-TEYNAMPET,125,225000,"Flood Damaged repair work in Muthukrishnan street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21632,Roads,Completed,NJ-TEYNAMPET,126,279000,"Flood damaged repair works in 2nd Loop Street and Lane in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21634,Roads,Completed,NJ-TEYNAMPET,125,210000,"Flood Damaged repair work in Thandavarayan street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21639,Roads,Completed,NJ-TEYNAMPET,125,641000,"Flood Damaged repair work in P.V.Koil 3rd street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21641,Roads,Completed,NJ-TEYNAMPET,126,121000,"FLOOD DAMAGED REPAIRS TO THE LEITH CASTLE NORTH ST, LAZARUS CHURCH 2ND ST, LAZARUS CHURCH ROAD, 8TH TRUST STREET, 9TH TRUST STREET, NORTAN 3RD STREET, ARUNA GIRI STREET, AND MARI CHETTI STREET IN DIV-126, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21645,Roads,Completed,NJ-TEYNAMPET,125,314000,"Flood Damaged repair work in Arundale street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21646,Roads,Completed,NJ-TEYNAMPET,111,320000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT GULAM ABBAS ALIGHAN 1 ST STREET IN DN -111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21653,Roads,Completed,NJ-TEYNAMPET,112,575000,"Flood Damaged Repair Work in Trurstpuram IInd cross Street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21654,Roads,Completed,NJ-TEYNAMPET,111,192000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT NAWAB HABIBULLAH 1 ST STREET IN DN-111, UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21659,Roads,Completed,NJ-TEYNAMPET,125,185000,"Flood Damaged repair work in Custain Beach Road in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21666,Roads,Completed,NJ-TEYNAMPET,115,367000,"Flood Damaged repairs to the Chinnappa Street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21672,Roads,Completed,NJ-TEYNAMPET,125,158000,"Flood Damaged repair work in Lein Perira street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21673,Roads,Completed,NJ-TEYNAMPET,115,314000,"Flood Damaged repairs to the Ramasamy street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21675,Roads,Completed,NJ-TEYNAMPET,125,262000,"Flood Damaged repair work in Lalitha Nagar 1st street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21676,Roads,Completed,NJ-TEYNAMPET,111,262000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT NAWAB HABIBULLAH 2 ND STREET IN DN -111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21682,Roads,Completed,NJ-TEYNAMPET,115,131000,"Flood Damaged repairs to the Haji Shaik Hussain Street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21683,Roads,Completed,NJ-TEYNAMPET,125,314000,"Flood Damaged repair work in Lalitha Nagar 2nd street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21687,Roads,Completed,NJ-TEYNAMPET,115,989000,"Flood Damaged repairs to the Angamuthu Street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21690,Roads,Completed,NJ-TEYNAMPET,125,144000,"Flood Damaged repair work in Kangeyapuram street in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21697,Roads,Completed,NJ-TEYNAMPET,113,1590000,"LAYING CEMENT CONCRETE ROAD AT GANGAIKARAIPURAM IN DN-113,U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21698,Roads,Completed,NJ-TEYNAMPET,115,820000,"Flood Damaged repairs to the Jaan-e Jahan Khan Road in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21701,Roads,Completed,NJ-TEYNAMPET,125,328000,"Flood Damaged repair work in Dooming Lane in Division-125, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21702,Roads,Completed,NJ-TEYNAMPET,111,1500000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT MODEL SCHOOL ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21710,Roads,Completed,NJ-TEYNAMPET,115,350000,"Flood Damaged repairs to the koya arunagiri 2nd and 3rd street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21715,Roads,Completed,NJ-TEYNAMPET,124,332000,"Flood Damaged repair work in V.C.Garden 1st street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21716,Roads,Completed,NJ-TEYNAMPET,115,138000,"Flood Damaged repairs to the Gafoor 3rd Lane in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21717,Roads,Completed,NJ-TEYNAMPET,112,475000,"Flood Damaged Repair Work in Puliyur 2nd Main Road at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21718,Roads,Completed,NJ-TEYNAMPET,122,65000,"FLOOD DAMAGED REPAIRS TO THE ADYAR CLUB GATE ROAD, OLD TOWER BLOCK ROAD, CENOTAPH 1ND LANE, LOTUS COLONY, AND NANTHANAM EXT 5TH STREET IN DIV-123, UNIT-26, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21720,Roads,Completed,NJ-TEYNAMPET,115,504000,"Flood Damaged repairs to the Hakkim Maqdoom Ashraff Street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21721,Roads,Completed,NJ-TEYNAMPET,112,950000,"Flood Damaged Repair Work in Puliyur 1st Main Road at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21722,Roads,Completed,NJ-TEYNAMPET,124,185000,"Flood Damaged repair work in V.C.Garden 2nd street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21725,Roads,Completed,NJ-TEYNAMPET,125,16300,"FLOOD DAMAGED REPAIRS TO THE DOOMING STREET, AND ROSARY CHURCH 1ST LANE IN DIV-125, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21727,Roads,Completed,NJ-TEYNAMPET,112,565000,"Flood Damaged Repair Work in Railway Border Road at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21728,Roads,Completed,NJ-TEYNAMPET,124,157000,"Flood Damaged repair work in Kallukaran street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21729,Roads,Completed,NJ-TEYNAMPET,115,414000,"Flood Damaged repairs to the Gaffur Street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21730,Roads,Completed,NJ-TEYNAMPET,112,1300000,"Flood Damaged Repair Work in Sivan Kovil Street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21735,Roads,Completed,NJ-TEYNAMPET,112,248000,"Flood Damaged Repair Work in Sowrashtra Nagar 7th Cross Street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21739,Roads,Completed,NJ-TEYNAMPET,112,235000,"Flood Damaged Repair Work in Sowrashtra Nagar 1st Street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21743,Roads,Completed,NJ-TEYNAMPET,115,78000,"Flood Damaged repairs to the Gaffur 1st Lane in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21746,Roads,Completed,NJ-TEYNAMPET,124,235000,"Flood Damaged repair work in Chitrakulam South street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21747,Roads,Completed,NJ-TEYNAMPET,112,350000,"Flood Damaged Repair Work in Vannarapathai at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21749,Roads,Completed,NJ-TEYNAMPET,113,87000,"FLOOD DAMAGED REPAIRS TO THE MANGADU SAMY STREET DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21750,Roads,Completed,NJ-TEYNAMPET,112,520000,"Flood Damaged Repair Work in Sivan Kovil Cross Street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21754,Roads,Completed,NJ-TEYNAMPET,112,870000,"Flood Damaged Repair Work in Vellalar street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21760,Roads,Completed,NJ-TEYNAMPET,112,174000,"Flood Damaged Repair Work in Alagiri Puram 1st Street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21765,Roads,Completed,NJ-TEYNAMPET,112,575000,"Flood Damaged Repair Work in Trustpuram 1st Cross Street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21768,Roads,Completed,NJ-TEYNAMPET,124,524000,"Flood Damaged repair work in Mundagakanni Amman Koil street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21769,Roads,Completed,NJ-TEYNAMPET,112,523000,"Flood Damaged Repair Work in Tamilnadu Housing Board Quatars at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21771,Roads,Completed,NJ-TEYNAMPET,124,249000,"Flood Damaged repair work in Thiruvalluvar Koil street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21780,Roads,Completed,NJ-TEYNAMPET,124,720000,"Flood Damaged repair work in Alamelumanga Puram in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21789,Roads,Completed,NJ-TEYNAMPET,124,220000,"Flood Damaged repair work in Nanjunda Rao colony in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21801,Roads,Completed,NJ-TEYNAMPET,124,340000,"Flood Damaged repair work in Abraham Street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21804,Roads,Completed,NJ-TEYNAMPET,124,1221000,"Flood Damaged repair work in North Mada Street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21809,Roads,Completed,NJ-TEYNAMPET,124,1221000,"Flood Damaged repair work in South Mada Street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21811,Roads,Completed,NJ-TEYNAMPET,113,408000,"Flood Damaged Repairs to Vaidhyanathan Street in Div 113, U -26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21847,Roads,Completed,NJ-TEYNAMPET,113,16300,"FLOOD DAMAGED REPAIRS TO THE PORUR SOMASUNDHARAM STREET IN DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/21849,Roads,Completed,NJ-TEYNAMPET,124,349000,"Flood Damaged repair work in Nattu Subrayan Street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21851,Roads,Completed,NJ-TEYNAMPET,122,54000,"Flood Damaged repair work to Thiruvalluar Salai (Part ) in Division-122, Unit-26, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21856,Roads,Completed,NJ-TEYNAMPET,124,728000,"Flood Damaged repair work in Adam Street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21861,Roads,Completed,NJ-TEYNAMPET,124,163000,"Flood Damaged repair work in Muntakkanni Amman Koil 4th STreet in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21888,Roads,Completed,NJ-TEYNAMPET,124,491000,"Flood Damaged repair work in Saradhapuram Main Road street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21891,Roads,Completed,NJ-TEYNAMPET,124,373000,"Flood Damaged repair work in Thiru-Vi-Ka Street in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21903,Storm Water Drain,Completed,NJ-TEYNAMPET,118,64000,"Providing Storm Water Drain Connection at Junction of Srinivasa Perumal Sanadhi 2nd Street to Ganapathy Colony 2nd Street , Royapettaha in Div 118,Unit-24,Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/21904,Roads,Completed,NJ-TEYNAMPET,124,212000,"Flood Damaged repair work in Madavaperumal Koil 1stLane in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/21909,Buildings,Completed,NJ-TEYNAMPET,118,156000,"Supply of wet mix for attending pot holes in various streets in Div 118,Unit,24,Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/21914,Buildings,Completed,NJ-TEYNAMPET,111,93000,"Improvements to Amma Unavagam at Model School Road in Div 111, Unit-24,Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/21961,Roads,Completed,NJ-TEYNAMPET,123,809000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT PRITHIVE AVENUE IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21975,Roads,Completed,NJ-TEYNAMPET,123,970000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT BAWA SALAI IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/21980,Roads,Completed,NJ-TEYNAMPET,123,515000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT BEEMANNA GARDEN STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/22151,Roads,Completed,NJ-TEYNAMPET,120,122000,"Flood Damaged repairs to the Venkatesapuram 1st street in Div-120, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/22172,Roads,Completed,NJ-TEYNAMPET,120,964000,"Flood Damaged repairs to the E_Depot lorry station road in Div-120, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/22302,Roads,Completed,NJ-TEYNAMPET,110,408000,"LAYING OF PATCH WORK IN FLOOD DAMAGED ROAD AT MAHALINGAM STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/22432,Roads,Completed,NJ-TEYNAMPET,126,367000,"Flood damaged repair works in Pattammal Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/22433,Roads,Completed,NJ-TEYNAMPET,126,31000,"Flood damaged repair works in 1st Trust Cross Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/22435,Roads,Completed,NJ-TEYNAMPET,126,1000000,"Flood damaged repair works in Sringeri Mutt Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/22686,Roads,Completed,NJ-TEYNAMPET,122,152000,"FLOOD DAMAGED REPAIRS TO THE TURN BULLS 4TH CROSS STREET IN DIV-122, UNIT-26, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/22697,Roads,Completed,NJ-TEYNAMPET,123,114000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT C.P RAMASAMY ROAD INSIDE DN-123 OFFICE IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/22701,Roads,Completed,NJ-TEYNAMPET,123,65000,"FLOOD DAMAGED REPAIRS TO THE CANAL BANK ROAD, R.A PURAM 7TH MAIN ROAD, R.A PURAM 1ST CROSS STREET, LUZ AVENUE, WARAN ROAD, KABALI THOTTAM, AND SEETHAMMAL ROAD IN DIV-123, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/23017,Subway,Completed,NJ-TEYNAMPET,109,301000,"DESILTING OF OPEN WELL AND REPAIRS TO MOTARS,ELECTRICAL STARTER AT NUNGAMBAKKAM SUBWAY IN DIV-109,U-24,Z-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/23032,Roads,Completed,NJ-TEYNAMPET,113,457000,"FLOOD DAMAGED REPAIRS TO THE VEERAPATHIRAN STREET IN DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23033,Roads,Completed,NJ-TEYNAMPET,113,337000,"FLOOD DAMAGED REPAIRS TO THE PILLAIYAR KOIL STREET IN DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23036,Roads,Completed,NJ-TEYNAMPET,113,294000,"FLOOD DAMAGED REPAIRS TO THE KOLLAMAMANIAMMAN KOIL STREET IN DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23037,Roads,Completed,NJ-TEYNAMPET,113,667000,"FLOOD DAMAGED REPAIRS TO THE KANNAIAH STREET IN DIV 113, U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23039,Roads,Completed,NJ-TEYNAMPET,113,1226000,"FLOOD DAMAGED REPAIRS TO THE PERIYAR ROAD IN DIV 113,U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23040,Roads,Completed,NJ-TEYNAMPET,113,272000,"FLOOD DAMAGED REPAIRS TO THE JAGANATHAN STREET IN DIV 113,U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23042,Roads,Completed,NJ-TEYNAMPET,113,1335000,"FLOOD DAMAGED REPAIRS TO THE NEW TANK STREET IN DIV 113,U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23045,Roads,Completed,NJ-TEYNAMPET,113,572000,"FLOOD DAMAGED REPAIRS TO THE KUMARAPAPA LANE IN DIV 113,U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23046,Roads,Completed,NJ-TEYNAMPET,113,27000,"FLOOD DAMAGED REPAIRS TO THE BALU STREET IN DIV 113,U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/23047,Roads,Completed,NJ-TEYNAMPET,113,340000,"FLOOD DAMAGED REPAIRS TO THE VIDHYODAYA MAIN ROAD IN DIV 113,U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/2395,Footpath,Completed,NJ-TEYNAMPET,117,295000,"Improvement to Granite Footpath work at G.N Chetty Road in Dn-117,Unit - 26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24293,Storm Water Drain,Completed,NJ-TEYNAMPET,123,999000,"IMPROVEMENTS TO STORM WATER DRAIN AND PVC PIPE FIXING WORK AT C.P.RAMASAMY ROAD IN DIV-123, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/24538,Bridges,Completed,NJ-TEYNAMPET,118,87500,Repair works to cooking center at Gopalapuram in Dn-118 Unit-24 Zone-9,Own Sources,9,2015-16,2018-19 NJ/2015-16/24577,Buildings,Completed,NJ-TEYNAMPET,113,986000,"Removal of floating materials /obstruction weeds Hyacinth/Garbages / plastic items , Thermo coal etc and preventive measures to mosquito menace along Mambalam Canal from Vidyothaya Main Road to Venkat narayana Street in Dn.113,117 & 122 in Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24667,Parks,Completed,P-Parks and Playfields,114,981000,"PROVIDING AND LAYING BLACK GRANITE IN ANNA PARK NORTH SIDE AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN-114, UNIT - 27A, ZONE -9",Own Sources,9,2015-16,2018-19 NJ/2015-16/24671,Parks,Completed,P-Parks and Playfields,114,981000,"PROVIDING AND LAYING BLACK GRANITE IN ANNA PARK EAST SIDE AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN-114, UNIT - 27A, ZONE - 9",Own Sources,9,2015-16,2018-19 NJ/2015-16/24775,Roads,Completed,NJ-TEYNAMPET,118,997000,PROVIDING AND FIXING STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREETS IN DN 118 U-24 Z-9 (Ward Councillor Fund),Own Sources,9,2015-16,2016-17 NJ/2015-16/24807,Roads,Completed,NJ-TEYNAMPET,112,560000,"Flood Damaged Repair Work in sivan koil south stret at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24814,Roads,Completed,NJ-TEYNAMPET,112,280000,"Flood Damaged Repair Work in swarnambigai street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24816,Roads,Completed,NJ-TEYNAMPET,112,910000,"Flood Damaged Repair Work in south sivan koil street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24819,Roads,Completed,NJ-TEYNAMPET,112,550000,"Flood Damaged Repair Work in ganga nagar 1st main road at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24820,Roads,Completed,NJ-TEYNAMPET,112,217000,"Flood Damaged Repair Work in ganga nagar 4th cross street at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24826,Roads,Completed,NJ-TEYNAMPET,112,660000,"Flood Damaged Repair Work in pandiyan avenue at Div-112,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/24899,Buildings,Completed,NJ-TEYNAMPET,109,997000,"DISMANTLING AND CONSTRUCTION OF COMPOUND WALL AND SIDE DRAIN AT GILL NAGAR PARK (NORTH SIDE) FLOOD DAMAGED IN DN-109,U-24,Z-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/24924,Parks,Completed,P-Parks and Playfields,114,990000,"PROVIDING AND LAYING OF MARKAPUR LIMESTONE(SOUTH WEST) AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN. 114, UNIT - 27A, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/24925,Parks,Completed,P-Parks and Playfields,114,990000,"PROVIDING AND LAYING OF MARKAPUR LIMESTONE(NORTH SIDE) AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN. 114, UNIT - 27A, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/24926,Parks,Completed,P-Parks and Playfields,114,981000,"PROVIDING AND LAYING BLACK GRANITE IN ANNA PARK CENTER SIDE AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN-114, UNIT - 27A, ZONE - 9",Own Sources,9,2015-16,2018-19 NJ/2015-16/24929,Parks,Completed,P-Parks and Playfields,114,981000,"PROVIDING AND LAYING BLACK GRANITE IN ANNA PARK SOUTH SIDE AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN-114, UNIT - 27A, ZONE -9",Own Sources,9,2015-16,2018-19 NJ/2015-16/24975,Roads,Completed,NJ-TEYNAMPET,120,2735000,"RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT LLOYDC COLONY LI,LS,LN,LM BLOCK ROADS IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/24981,Roads,Completed,NJ-TEYNAMPET,120,2900000,": RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT LLOYDS COLONY LA,LR,LG,LP BLOCK ROADS IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/24982,Roads,Completed,NJ-TEYNAMPET,120,985000,"RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT LLOYDS COLONY RK,RM,RP BLOCK ROADS IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/24984,Roads,Completed,NJ-TEYNAMPET,120,985000,"RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT LLOYDS COLONY RL,RM,RP BLOCK ROADS IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/25068,Storm Water Drain,Completed,NJ-TEYNAMPET,112,525000,"REPAIRS TO SWD AT SIVAN KOIL STREET IN DN - 112,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2018-19 NJ/2015-16/25074,Storm Water Drain,Completed,NJ-TEYNAMPET,110,997000,"Dismantling top slab and Raising storm water drain at Tank bund road from ch.309m to 410m southern side in Division-110, Unit-24, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/25076,Storm Water Drain,Completed,NJ-TEYNAMPET,109,979000,"Dismantling top slab and Raising storm water drain at Tank bund road from ch.410m to 491m southern side in Division.110, Unit-24, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/25078,Storm Water Drain,Completed,NJ-TEYNAMPET,109,895000,"Dismantling top slab and Raising storm water drain at Tank bund road from ch.505m to 560m southern side in Division-110, Unit-24, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/25135,Parks,Completed,P-Parks and Playfields,114,979000,"PROVIDING AND LAYING OF MARKAPUR LIMESTONE(MIDDLE SIDE) AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN. 114, UNIT - 27A, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/25136,Parks,Completed,P-Parks and Playfields,114,990000,"PROVIDING AND LAYING OF MARKAPUR LIMESTONE(SOUTH SIDE) AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN. 114, UNIT - 27A, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/25137,Parks,Completed,P-Parks and Playfields,114,990000,"PROVIDING AND LAYING OF MARKAPUR LIMESTONE(NORTH EAST SIDE) AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN. 114, UNIT - 27A, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/25138,Parks,Completed,P-Parks and Playfields,114,979000,"PROVIDING AND LAYING OF GRANITE PILLAR IN ANNA PARK NORTH EAST AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN. 114, UNIT - 27A, ZONE - 9",Own Sources,9,2015-16,2018-19 NJ/2015-16/25139,Parks,Completed,P-Parks and Playfields,114,979000,"PROVIDING AND LAYING OF GRANITE PILLAR IN ANNA PARK SOUTH WEST AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN. 114, UNIT - 27A, ZONE - 9",Own Sources,9,2015-16,2018-19 NJ/2015-16/2517,Roads,Completed,NJ-TEYNAMPET,116,961000,"ATTENDING PATCH WORK AT SOUTH MADA STREET IN FRONT OF PARTHASARATHI TEMPLE IN DN-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/25260,Roads,Completed,NJ-TEYNAMPET,120,2619000,"RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT LLOYDS COLONY A TO G BLOCK ROADS IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/2543,Buildings,Completed,NJ-TEYNAMPET,112,300000,"Construction of Baby Friendly Toilet and Improvements to ICDC (center no.33603040125) at Choolaimedu High Road in dn-112,unit-26,z-9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/25619,Buildings,Completed,NJ-TEYNAMPET,126,820000,"Electrical and Plumbing work for full rooms in MP office at santhome high road in din-126,unit-25,zone-9",Own Sources,9,2015-16,2019-20 NJ/2015-16/25624,Buildings,Completed,NJ-TEYNAMPET,126,560000,"Providing wooden door, Ventilator, Air conditioner, Wall mounting fan and LED light in MP office at Santhome High Road in Div.126, U-25, Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/25749,Buildings,Completed,NJ-TEYNAMPET,124,600000,"IMPROVEMENTS TO HOMEOPATHY HOSPITAL AT MANDAVELI STREET IN DN-124,U-25,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/25782,Buildings,Completed,NJ-TEYNAMPET,126,828000,"Repairs and Conversion of Electrical Sub Station to South Chennai MP Office at Santhome High Road in Div-126,Unit-25,Zone-09",Own Sources,9,2015-16,2018-19 NJ/2015-16/25851,Storm Water Drain,Completed,NJ-TEYNAMPET,118,998000,CONSTRUCTION OF STORM WATER DRAIN AT MAYOR SUNDER RAO ROAD FROM JUNCTION OF ANNA SALAI 0M TO 80M IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/25866,Buildings,Completed,NJ-TEYNAMPET,110,365000,"PROPOSED CONSTRUCTION FOR COMPOUND WALL AT APPA SWAMI STREET DISPENSARY IN DN 110, UNIT 24, ZONE 9",Own Sources,9,2015-16,2018-19 NJ/2015-16/26080,Storm Water Drain,Completed,NJ-TEYNAMPET,110,424000,"REPAIRS TO STROM WATER DRAIN AT MAHALINGAPURAM MAIN ROAD NEAR BY LOYOLA COLLEGE COMPOUND WALL IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/26246,Footpath,Completed,NJ-TEYNAMPET,126,57000,"Flood Damaged repair work in 4th Trust Cross Street in Division-126, Unit-25, Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/26251,Buildings,Completed,NJ-TEYNAMPET,123,995000,"IMPROVEMENTS TO STORM WATER DRAIN AT TTK ROAD AND SEETHAMMAL SALAI IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/26252,Storm Water Drain,Completed,NJ-TEYNAMPET,123,900000,"DESILTING OF STORM WATER DRAIN AT THIRUVALLUVAR SALAI IN DN 123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/26253,Storm Water Drain,Completed,NJ-TEYNAMPET,123,950000,"DESILTING OF STROM WATER DRAIN AT ELDAMS ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/26256,Buildings,Completed,NJ-TEYNAMPET,123,900000,"IMPROVEMENTS TO HAKKING COMMITTE OFFICE AT R.A.PURAM 3RD CROSS ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/26455,Buildings,Completed,NJ-TEYNAMPET,113,140000,"Construction of Compound Wall at Mambalam Canal Near Balamandhir Kamaraj Trust in Div 113.Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/26614,Roads,Completed,NJ-TEYNAMPET,125,243000,"PROVIDING AND FIXING OF ARASU E-SEVA CENTRE SIGNAGE NAME BOARD AT IN DIV-123,124,125,126 UNIT-25 ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/26616,Buildings,Completed,NJ-TEYNAMPET,110,743000,"PROVIDING AND FIXING STAINLESS STEEL NAME BOARDS FOR ARASU E SEVAI CENTRES AND IMPROVEMENTS TO FOOT PATH AT VARIOUS LOCATIONS IN DIVISION-110, UNIT- 24, ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/26789,Buildings,Completed,NJ-TEYNAMPET,118,762000,"IMPROVEMENTS THE DESPENSARY AT AMMAIAPPAN STREET IN Dn-118,U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/26796,Buildings,Completed,NJ-TEYNAMPET,114,997000,"ADDITIONAL IMPROVEMENTS TO NIGHT SHELTER AT LOCK NAGAR IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/27246,Roads,Completed,NJ-TEYNAMPET,123,550000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT H.D.RAJA STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27255,Roads,Completed,NJ-TEYNAMPET,123,433000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT EAST ABIRAMAPURAM 1ST STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27256,Roads,Completed,NJ-TEYNAMPET,123,260000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT RAMARAO STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27257,Roads,Completed,NJ-TEYNAMPET,123,490000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT R.A.PURAM 6TH MAIN ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27259,Roads,Completed,NJ-TEYNAMPET,123,260000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT ANANTHAPURAM IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27262,Roads,Completed,NJ-TEYNAMPET,123,260000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT BEEMANNA GARDEN 1ST STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27264,Roads,Completed,NJ-TEYNAMPET,123,190000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT DR.RANGA LANE IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27266,Roads,Completed,NJ-TEYNAMPET,123,175000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT LUZ AVENUE 4TH CROSS STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27268,Roads,Completed,NJ-TEYNAMPET,123,870000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT RAMACHANDRA ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27269,Roads,Completed,NJ-TEYNAMPET,123,380000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT JUSTICE SUNDARAM ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27271,Roads,Completed,NJ-TEYNAMPET,123,280000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT BASKARAPURAM IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27278,Roads,Completed,NJ-TEYNAMPET,123,450000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT LUZ AVENUE 2ND LANE IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27280,Roads,Completed,NJ-TEYNAMPET,123,180000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT LUZ AVENUE 3RD LANE IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27283,Roads,Completed,NJ-TEYNAMPET,123,690000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT ABIRAMAPURAM 4TH STREET PART IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27284,Roads,Completed,NJ-TEYNAMPET,123,100000,"ATTENDING THE TEMPORARY RESTORATION FOR FLOOD DAMAGE ROAD AT BHARATHIYAR SALAI IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27351,Roads,Completed,NJ-TEYNAMPET,117,1150000,"FLOOD DAMAGED REPAIRS TO THE NEW GIRI ROAD IN DN-117,UNIT-26, ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27360,Roads,Completed,NJ-TEYNAMPET,117,450000,"FLOOD DAMAGED REPAIRS TO THE VAIDHYARAMAN STREET IN DN-117,UNIT-26, ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27368,Roads,Completed,NJ-TEYNAMPET,117,117000,"FLOOD DAMAGED REPAIRS TO THE BASUDEV STREET IN DN-117,UNIT-26,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27372,Buildings,Completed,NJ-TEYNAMPET,117,250000,"FLOOD DAMAGED ROADS REPAIRS ATDR.B.NARASIMMAN ROAD 2ND STREET IN DIV 117,UNIT-26,ZONE-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/27379,Roads,Completed,NJ-TEYNAMPET,117,480000,"FLOOD DAMAGED REPAIRS TO THE ARCOT ROAD IN DN-117,UNIT-26,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/27530,Roads,Completed,NJ-TEYNAMPET,115,477000,"Flood Damaged repairs to the Thangavelu (V)Street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/27533,Roads,Completed,NJ-TEYNAMPET,115,390000,"Flood Damaged repairs to the koya arunagiri 1st and 5th Street in Div-115, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/27673,Roads,Completed,NJ-TEYNAMPET,117,457000,"FLOOD DAMAGED ROADS REPAIRS AT VIJAYARAGHAVA 1ST STREET IN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/27674,Buildings,Completed,NJ-TEYNAMPET,114,24500,"supplying and fixing of over head tank, health faucet and taps in NUHM Building at Arunachalam street in DIV -114, UNIT -27, ZONE- 9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/27675,Buildings,Completed,NJ-TEYNAMPET,114,24900,"supplying and fixing of Jet motor, Kitchen sink and ball valve in Disabled children school at arunachalam street in DIV 114, UNIT 27, ZONE 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/27676,Electrical,Completed,NJ-TEYNAMPET,114,24900,"supplying and fixing of wash basin, flush cock, tube light with patty and pipe laying in community hall building at arunachalam street in DIV 114, UNIT- 27, ZONE - 9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/27677,Electrical,Completed,NJ-TEYNAMPET,114,24900,"supplying and fixing of over head tank, wash basin, ball valve, fan, pipe laying and motor repair in Division office building at arunachalam street in DIV 114, UNIT- 27, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/27678,Electrical,Completed,NJ-TEYNAMPET,114,24900,"supplying and fixing of over head tank, fan and motor repair in Amma Unavagam at Arunachalam street in DIV 114, UNIT -27, ZONE 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/27679,Buildings,Completed,NJ-TEYNAMPET,114,24900,"supplying and fixing of 1 HP Jet motor, taps,ball valve and pipe laying in AMMA UNAVAGAM at vallabha agraharam street in DIV-114, UNIT-27, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/27680,Electrical,Completed,NJ-TEYNAMPET,114,24900,"supplying and fixing of Over head tank, Fan and Taps in CMS School at Vallabha agraharam street in DIV 114, UNIT -27, ZONE 9",Own Sources,9,2015-16,2018-19 NJ/2015-16/27681,Buildings,Completed,NJ-TEYNAMPET,114,24000,"supplying and fixing of over head tank, Tubelight & patty in public convienence building at victoria hostel Road in DIV 114, UNIT-27, ZONE - 9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/27683,Buildings,Completed,NJ-TEYNAMPET,114,24900,"supplying and fixing of electrical items in amma unavagam building at K.G.Hospital in DIV 114, UNIT- 27, ZONE - 9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/27686,Buildings,Completed,NJ-TEYNAMPET,114,24500,"supplying and fixing of plumbing material in CMS at Bangaru street in DIV 114, UNIT- 27, ZONE - 9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/27687,Buildings,Completed,NJ-TEYNAMPET,114,24500,"supplying and fixing of plumbing material in cms at Bells Road in DIV 114, UNIT- 27, ZONE - 9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/27692,Parks,Completed,NJ-TEYNAMPET,114,990000,"SUPPLYING OF TREES IN MARINA BEACH LAWN FROM 1 TO 14, IN DIVISION 114,116,120,121 AND 125, UNIT 25 AND 27, ZONE - 9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/27735,Roads,Completed,NJ-TEYNAMPET,113,821000,"WIDENING THE ROAD WITH CEMENT CONCRETE AT PRAKASAM STREET IN DIV 113,U-26, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/27777,Buildings,Completed,NJ-TEYNAMPET,113,500000,", Arrangements of Barricading and plywood partition etc in Div 113,U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/27799,Parks,Completed,NJ-TEYNAMPET,116,666000,"Repairs to Wire Fencing For Lawn No. 5,6,7,and 8 at Marina Beach in Dn-116, Unit-27,Zone-9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/27808,Parks,Completed,NJ-TEYNAMPET,120,2735000,"RELAYING OF BT ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHING AT LLOYDS COLONY MAIN ROAD ROADS IN DIV 120,UNIT 27,ZONE",Own Sources,9,2015-16,2017-18 NJ/2015-16/27880,Buildings,Completed,NJ-TEYNAMPET,118,995000,IMPROVEMENTS TO DIVISION OFFICE CAMPUS AT MUTHAIYA STREET IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2017-18 NJ/2015-16/27885,Buildings,Completed,NJ-TEYNAMPET,118,980000,IMPROVEMENTS TO SANITARY INSPECTOR ROOM AND CONSERVANCY INSPECTOR ROOM IN FIRST FLOOR AT MUTHAIYA STREET IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2015-16,2018-19 NJ/2015-16/27897,Buildings,Completed,NJ-TEYNAMPET,111,265000,"SUPPLYING AND FIXING PARKS FUNCTIONING TIME INFORMATION NAME BOARD TO DIVISIONS 109,110,111,118 AND 119 UNIT-24, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/27911,Footpath,Completed,NJ-TEYNAMPET,121,715000,IMPROVEMENTS TO FOOTPATH AT DR.RADHA KRISHNAN SALAI AND BEACH SERVICE ROAD IN DIVISION 121 UNIT 27 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/27917,Buildings,Completed,NJ-TEYNAMPET,111,680000,DISMANTLING AND RE-CONSTRUCTION OF COMPOUND WALL AT CHENNAI MIDDLE SCHOOL AT MODEL SCHOOL ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/28023,Roads,Completed,NJ-TEYNAMPET,115,500000,GREENARY ARRANGEMENTS FOR CENTREMEDIUM AT WEST COTT ROAD IN DN-115 U-27 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/28032,Roads,Completed,NJ-TEYNAMPET,121,995000,"IMPROVEMENTS TO THE PUBLIC CONVENIENCE AND BATHROOM AT THIRUVEETHI AMMAN KOIL STREET IN DN-121 U-27, Z-9[COUNCILAR FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/28033,Roads,Completed,NJ-TEYNAMPET,121,995000,CONSTRUCTION OF ROAD SIDE PARK AT THIRUVEETHI AMMAN KOIL STREET IN DN -121 U-27 Z-9[COUNCILAR FUND],Own Sources,9,2015-16,2016-17 NJ/2015-16/2838,Buildings,Completed,NJ-TEYNAMPET,119,990000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING OLD BUILDINGS OF DHOBI KANA AT MUTHAIYA GARDEN STREET, IN DIVISION-119,UNIT-24,ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/28496,Footpath,Completed,NJ-TEYNAMPET,125,420000,REPAIRS AND IMPROVEMENTS TO FOOT PATH AND KERB WALLS AT BEACH SERVICE ROAD IN DIVISION 125 UNIT 25 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/28499,Footpath,Completed,NJ-TEYNAMPET,122,720000,"IMPROVEMENTS TO FOOT PATH AND PAINTING OF KERB WALLS AT T.T.K ROAD,CHAMIERS ROAD AND TURN BULLS ROAD IN DIVISION 122 UNIT 26 ZONE 09",Own Sources,9,2015-16,2016-17 NJ/2015-16/28517,Buildings,Completed,NJ-TEYNAMPET,111,599000,"REPAIR AND MAINTENANCE OF PUBLIC CONVENIENCE AT 29, GREAMS ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/28588,Buildings,Completed,NJ-TEYNAMPET,118,995000,"ADDITIONAL WORKS FOR THE PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT MARIYAPPAN STREET IN DIVISION-118, UNIT-24, ZONE-9 ( UNDER M.L.A SCHEME)",MLACDS,9,2015-16,2017-18 NJ/2015-16/28610,Parks,Completed,NJ-TEYNAMPET,114,468000,"Repairs to Wire Fencing at Rear Side of Lawn No. 1,2,3,4 at Marina Beach in Dn-114 Unit-27A,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/28678,Roads,Completed,NJ-TEYNAMPET,117,523000,"FLOOD DAMAGED ROADS REPAIRS AT THILAK STREET IN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/28686,Buildings,Completed,NJ-TEYNAMPET,110,994000,"IMPROVEMENTS TO ZONAL OFFICE BUILDING AT LAKE AREA 4th CROSS STREET IN DN: 110, UNIT:24, ZONE: 09",Own Sources,9,2015-16,2016-17 NJ/2015-16/28838,Storm Water Drain,Completed,NJ-TEYNAMPET,110,860000,"ADDITIONAL IMPROVEMENT WORKS TO AMMA UNAVAGAM IN 110 DIVISION OFFICE CAMPUS AT KUTTY STREET IN DIVISION-110, UNIT-24, ZONE-IX",Own Sources,9,2015-16,2016-17 NJ/2015-16/28934,Roads,Completed,NJ-TEYNAMPET,122,970000,"IMPROVEMENTS TO THE OSR LAND (UNDER WARD COUNCILLOR SCHEME) AT RATHNA NAGAR IN DN-122,U-26,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/29008,Roads,Completed,NJ-TEYNAMPET,118,633000,"Providing Stainless Steel Hand Rail at Poes Garden in Dn-118,U-24,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29058,Roads,Completed,NJ-TEYNAMPET,113,3070000,"Improvements to Cement Concrete Road at Habibulla road (Vidhyodhaya main road to G.N.Chetty road) in Dn113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/2914,Roads,Completed,NJ-TEYNAMPET,117,300000,"Attending Patch work at Bharathi Nagar 3rd Street for Flood damages caused to Infra structure in Div 117,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29219,Roads,Completed,NJ-TEYNAMPET,113,1800000,"Laying Cement Concrete Road at Habibulla road (Thirumalai pillai road to Vidhyodhaya main road) in Dn113,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29234,Buildings,Completed,NJ-TEYNAMPET,109,996000,"CONSTRUCTION OF MULTIPURPOSE HALL AT WEST NAMACHIVAYAPURAM (WARD COUNCILLOR FUND) IN DN 109,UNIT-26,ZONE-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/2924,Roads,Completed,NJ-TEYNAMPET,116,942000,"LAYING CEMENT CONCRETE ROAD WITH RMC40 GRADE AT SIVRAJAPURAM SLUM AT Dn-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29293,Roads,Completed,NJ-TEYNAMPET,111,322000,"RELAYING OF CEMENT CONCRETE ROAD AT TANK BUND ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29300,Roads,Completed,NJ-TEYNAMPET,117,999000,"FLOOD DAMAGED ROADS REPAIRS AT DR GIRIAPPA ROAD (DRIVERS COLONY) IN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29348,Roads,Completed,NJ-TEYNAMPET,122,112000,"FLOOD DAMAGED REPAIRS TO THE T.T.K ROAD 2ND STREET IN DN - 122,UNIT- 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29438,Roads,Completed,NJ-TEYNAMPET,117,817000,"FLOOD DAMAGED ROADS REPAIRS AT SARANGAPANI STREET IN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29481,Footpath,Completed,NJ-TEYNAMPET,118,995000,"IMPROVEMENTS TO FOOTPATH AND KERB WALLS AT CATHEDRAL ROAD AND T.T.K ROAD IN DIVISION- 118, UNIT- 24, ZONE- IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/29483,Roads,Completed,NJ-TEYNAMPET,117,130000,"FLOOD DAMAGED ROADS REPAIRS AT THILAK STREET EXTN IN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29489,Buildings,Completed,NJ-TEYNAMPET,113,998000,"ADDITIONAL IMPROVEMENTS TO AMMA UNAVAGAM AT SARATHY STREET IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/29515,Roads,Completed,NJ-TEYNAMPET,111,780000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT RUTLAND GATE 2 ND STREET DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29517,Roads,Completed,NJ-TEYNAMPET,111,3830000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT WALLACE GARDEN 2 ND STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29528,Roads,Completed,NJ-TEYNAMPET,119,886000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT BEGUM MAIN ROAD IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29530,Roads,Completed,NJ-TEYNAMPET,122,1960000,"RELAYING B.T. ROAD AT DR. RADHAKRISHNAPURAM IN DN -122, UNIT - 26, ZONE - 9",Own Sources,9,2015-16,2017-18 NJ/2015-16/29534,Roads,Completed,NJ-TEYNAMPET,119,5088000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT VENKATACHALAM (M) STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29536,Roads,Completed,NJ-TEYNAMPET,119,820000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SRIPURAM 2 ND STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29537,Roads,Completed,NJ-TEYNAMPET,119,1430000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT IYYAM PERUMAL STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29539,Roads,Completed,NJ-TEYNAMPET,119,499000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT AVVAI SHANMUGAM SALAI 2 ND LANE IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/2955,Footpath,Completed,NJ-TEYNAMPET,117,236000,"Improvement to Granite Footpath work at North cresent street in Dn-117,Unit - 26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/29554,Roads,Completed,NJ-TEYNAMPET,118,1620000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT GANAPATHY COLONY 1 ST STREET DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29560,Roads,Completed,NJ-TEYNAMPET,118,1410000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT GANAPATHY COLONY 2 N CROSS STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29562,Roads,Completed,NJ-TEYNAMPET,118,3640000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SREEMAN SRINIVASAN ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29563,Roads,Completed,NJ-TEYNAMPET,118,897000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT ELANGO SALAI CROSS STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29582,Roads,Completed,NJ-TEYNAMPET,118,900000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SIVASANKARAN SALAI IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29584,Roads,Completed,NJ-TEYNAMPET,118,3130000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT MURRAYS GATE SALAI IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29646,Roads,Completed,NJ-TEYNAMPET,118,3240000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT CHOCKKALINGAM COLONY MAIN ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29654,Roads,Completed,NJ-TEYNAMPET,118,1280000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SCHEME ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29658,Roads,Completed,NJ-TEYNAMPET,118,1795534,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT POES ROAD (NALLAN STREET) DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29664,Roads,Completed,NJ-TEYNAMPET,118,859000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT KASTHURI ESTATE DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29671,Roads,Completed,NJ-TEYNAMPET,110,1130000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT NEW STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29680,Roads,Completed,NJ-TEYNAMPET,110,634000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT HARRINGTON ROAD 9 TH AVENUE IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29682,Roads,Completed,NJ-TEYNAMPET,109,827000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT BAJANAI KOIL 5 TH STREET IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29683,Roads,Completed,NJ-TEYNAMPET,109,594000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SOUTH GANGAIAMMAN KOIL 1 ST ND 2 ND CROSS STREET IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29684,Roads,Completed,NJ-TEYNAMPET,109,1385000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SOUTH GANGAIAMMAN KOIL 2 ND STREET IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29685,Roads,Completed,NJ-TEYNAMPET,109,2159000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT THIRUVALLUR PURAM 2 ND STREET (PAR-2) DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29686,Roads,Completed,NJ-TEYNAMPET,109,740000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT BAJANAI KOIL 2 ND LANE IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/29687,Roads,Completed,NJ-TEYNAMPET,109,1129000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT VANNIER 2 ND STREET PART IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/29688,Roads,Completed,NJ-TEYNAMPET,109,1012000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SANKARAPURAM 3 RD STREET IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/30309,Parks,Completed,NJ-TEYNAMPET,120,369000,"Repairs to Wire Fencing at Rear Side of Lawn No. 9 and 10 at Marina Beach in Dn-120, Unit-27,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30337,Roads,Completed,NJ-TEYNAMPET,114,240000,"PROVIDING AND STICKING NAME BOARDS FOR CHANGING NAME FROM CHENNAI CORPORATION TO GREATER CHENNAI CORPORATION FOR VARIOUS PC'S IN DN-114,115,116,120 & 121 , UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/30342,Roads,Completed,NJ-TEYNAMPET,114,800000,"Improvements to footpath in Bells road adjacent to chepauk stadium in Div-114, Unit-27,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30344,Roads,Completed,NJ-TEYNAMPET,114,997000,"SUPPLYING OF VARIOUS PLANTS IN MARINA BEACH WALL PLANTER BOX IN DIV 114,116,120,121 AND 125, UNIT-27A, ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/30482,Buildings,Completed,NJ-TEYNAMPET,116,410000,"ATTENDING PATCH WORK AT SOUTH MADA STREET IN FRONT OF PARTHA SARATHI TEMPLE REACH 2 IN Dn-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/30487,Parks,Completed,NJ-TEYNAMPET,121,995000,"Providing and laying of red earth, river sand and manure in planter box at marina beach (from Labour statue to Gandhi statue) in Dn-114,116,120 & 121, U-27A, Z-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/3053,Buildings,Completed,NJ-TEYNAMPET,110,387000,"Repairs and Improvements to the Electrical crematorium at Nungambakkam Burial Ground, Sterling road in Division- 110, Unit- 24, Zone-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30734,Roads,Completed,NJ-TEYNAMPET,121,930000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT ROTARY NAGAR 1st, 2 nd, 3rd, 4th, 5th, 6th, 8th and 9th STREET IN DN 121, U -27, ZONE -9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30737,Roads,Completed,NJ-TEYNAMPET,121,847000,"IMPROVEMENT TO THE EXISTING ROAD WORK AT ROTARY NAGAR 15th STREET TO ROTARY NAGAR 17th STREET IN DN 121, U -27, Z - 9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30738,Roads,Completed,NJ-TEYNAMPET,121,996000,"SUPPLYING AND LAYING OF G-2 GRASS AND PLANTS IN MARINA BEACH LAWN NO 11 TO 14, U - 25 & 27 IN DIV 121 & DIV 125 ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/30739,Roads,Completed,NJ-TEYNAMPET,121,998000,"SUPPLYING AND LAYING OF RED SOIL, SAND, MANURE ETC., IN MARINA BEACH LAWN AREA , DN, 114,116,120,121 AND 125, UNIT 25 AND 27, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/30740,Roads,Completed,NJ-TEYNAMPET,121,917000,"IMPROVEMENT TO EXISTING ROAD WORK AT ROTARY NAGAR MAIN ROAD(PART) IN DN - 121, U -27, Z-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30741,Roads,Completed,NJ-TEYNAMPET,121,750000,"IMPROVEMENT TO EXISTING ROAD WORK AT MECCAPURAM 1 TO 3rd STREET IN DN - 121, U - 27, Z -9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30742,Roads,Completed,NJ-TEYNAMPET,121,724000,"SUPPLYING AND LAYING OF SHADE GRASS AND SUPPLYING OF PLANTS IN MARINA BEACH LAWN 1,2,3,7 AND 12 IN DIV 114,116 AND 121, UNIT 27, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/30794,Roads,Completed,NJ-TEYNAMPET,121,970000,"SUPPLYING OF VARIOUS PLANTS IN MARINA BEACH PLANTER BOX,DIV 114,116,120,121 AND 125, UNIT - 25 AND 27, ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/30796,Parks,Completed,NJ-TEYNAMPET,125,360000,"MAINTENANCE OF PRE FABRICATED URINAL UNITS AT VARIOUS LOCATIONS IN DIVISIONS-123,124,125 & 126 IN UNIT-25,ZONE-09 PERIOD (01.06.2016 TO 30.09.2016) 4 MONTHS",Own Sources,9,2015-16,2019-20 NJ/2015-16/3091,Buildings,Completed,NJ-TEYNAMPET,110,324000,"Proposed Construction of Toilet Block for inside the Corporation Middle School at Jayalakshmi puram main road in Division- 110, Unit- 24, Zone-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/30973,Parks,Completed,NJ-TEYNAMPET,120,225000,"SUPPLYING AND FIXING SPRINGLER AND WATER SUPPLY ARRANGEMENTS FOR MARINA BEACH(LAWN-9 AND 10 ) IN DN-120, U-27,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/30974,Parks,Completed,NJ-TEYNAMPET,116,450000,"SUPPLYING AND FIXING SPRINGLER AND WATER SUPPLY ARRANGEMENTS FOR MARINA BEACH(LAWN-5,6,7, AND 8) IN DN-116, U-27,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/3099,Parks,Completed,NJ-TEYNAMPET,111,291000,"Improvements the park at Domodharan Street (near Division Office-111) in Dn-111,U-24,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/31027,Buildings,Completed,NJ-TEYNAMPET,121,378000,"REPAIRS OF WIRE FENCING FOR LAWN 11 AND 12 AT MARINA BEACH IN DN 121, UNIT 27A, ZONE - 9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/31052,Roads,Completed,NJ-TEYNAMPET,109,539000,"IMPROVEMENT TO CEMENT CONCRETE ROAD AT CHINAPPA NAGAR IN DN-109,UNIT-24,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/31084,Roads,Completed,NJ-TEYNAMPET,117,453000,"FLOOD DAMAGED ROADS REPAIRS AT RAJAN STREETIN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/31088,Parks,Completed,NJ-TEYNAMPET,114,256000,"SUPPLYING AND FIXING SPRINKLER AND WATER SUPPLY ARRANGEMENTS FOR MARINA BEACH(LAWN-1,2,3 AND 4) IN DN-114, U-27A,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/31090,Roads,Completed,NJ-TEYNAMPET,109,309541,"IMPROVEMENT TO CEMENT CONCRETE ROAD AT VANNIAR LANE IN DIV-109,U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/31094,Buildings,Completed,NJ-TEYNAMPET,125,300000,"SUPPLYING AND FIXING SPRINKLER AND WATER SUPPLY ARRANGEMENTS FOR MARINA BEACH(LAWN-13 AND 14 ) IN DN-125, U-27- A ,ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/31096,Buildings,Completed,NJ-TEYNAMPET,125,414000,"Repairs of Wire Fencing for Lawn No. 13 and 14 at Marina Beach in Dn - 125, Unit - 27-A, Zone - 9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/31385,Roads,Completed,NJ-TEYNAMPET,116,672000,"Improvements works to amma drinking water scheme at V.R pillai street in dn-116, unit-27,zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/31387,Roads,Completed,NJ-TEYNAMPET,116,207000,"Providing Paver blocks for Amma Kudineer and Providing interlocking tiles for footpath at Bharathi salai in Dn-116, unit-27, zone-9.",Own Sources,9,2015-16,2018-19 NJ/2015-16/31478,Roads,Completed,NJ-TEYNAMPET,123,1350000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT NAINAN STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2017-18 NJ/2015-16/31485,Roads,Completed,NJ-TEYNAMPET,123,1900000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT R.A.PURAM 5TH MAIN ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2017-18 NJ/2015-16/31494,Roads,Completed,NJ-TEYNAMPET,123,1400000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT SRI LAPTHI COLONY IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2017-18 NJ/2015-16/31517,Buildings,Completed,NJ-TEYNAMPET,116,890000,"PROVIDING AND FIXING NEW NAME BOARD (GREATER CHENNAI CORPORATION) IN VARIOUS LOCATIONS AT CORPORATION BUILDINGS IN DN-114,115 AND 116, UNIT-27, ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/31519,Buildings,Completed,NJ-TEYNAMPET,121,595000,"PROVIDING AND FIXING NEW NAME BOARD (GREATER CHENNAI CORPORATION) IN VARIOUS LOCATIONS AT CORPORATION BUILDINGS IN DN-120 AND 121, UNIT-27, ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/31524,Footpath,Completed,NJ-TEYNAMPET,121,750000,"IMPROVEMENTS TO FOOT PATH AND KERB WALLS AT DR.RADHA KRISHNAN SALAI IN DIVISION -121, UNIT- 27, ZONE- IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/31622,Roads,Completed,NJ-TEYNAMPET,123,1650000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT RAMALINGESWARAR KOIL STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2017-18 NJ/2015-16/31625,Roads,Completed,NJ-TEYNAMPET,123,4350000,"COLD MILLING AND RELAYING OF THE ROAD WITH CBC40MM THICK BY PAVAR FINISH AT THIRUVALLUVAR SALAI IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2015-16,2017-18 NJ/2015-16/32045,Roads,Completed,NJ-TEYNAMPET,120,3241000,"IMPROVEMENT TO THE EXISTING CEMENT CONCRETE ROAD NEELEM BASHA THARGA 1 TO 11 STREET IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/32047,Roads,Completed,NJ-TEYNAMPET,120,534000,"IMPROVEMENT TO THE EXISTING CEMENT CONCRETE ROAD AT CANAL BANK STREET IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/32048,Buildings,Completed,NJ-TEYNAMPET,120,3406000,"IMPROVEMENT TO THE EXISTING CEMENT CONCRETE ROAD AT SUTHANDRA NAGAR 1 TO 4 STREET IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/32049,Buildings,Completed,NJ-TEYNAMPET,120,716000,"IMPROVEMENT TO THE EXISTING CEMENT CONCRETE ROAD AT DR NATESAN 1 ST LANE IN DIV 120,UNIT 27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/32155,Roads,Completed,NJ-TEYNAMPET,125,990000,"Relaying of cement concrete Road at Ekambaram Street in Div-125,Unit-25,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/32158,Roads,Completed,NJ-TEYNAMPET,125,872000,"Relaying of Cement concrete Road at Arumugam Street in Div-125,Unit-25,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/32161,Roads,Completed,NJ-TEYNAMPET,125,482000,"Relaying of cement concrete Road at Munusamy Street in Div-125,Unit-25,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/32833,Buildings,Completed,NJ-TEYNAMPET,117,381000,"FLOOD DAMAGED ROADS REPAIRS AT MAMBALAM HIGH ROAD IN DIV 117,UNIT-26,ZONE-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/32870,Roads,Completed,NJ-TEYNAMPET,117,900000,"FLOOD DAMAGED ROADS REPAIRS AT BHARATHI NAGAR 1ST STREETIN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/3289,Buildings,Completed,NJ-TEYNAMPET,117,300000,"Attending Patch work at Giri Road (Part) for Flood damages caused to Infra structure in Div 117,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33201,Buildings,Completed,NJ-TEYNAMPET,116,326000,"IMPROVEMENT TO AMMA UNAVAGAM AT V.R.PILLAI STREET IN DN-116,U-27,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/33202,Buildings,Completed,NJ-TEYNAMPET,116,995000,"IMPROVEMENTS TO UNIT 27 OFFICE CAMPUS AT DR.BESANT ROAD IN DN-116,U-27,Z-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/33215,Road Cut,Completed,NJ-TEYNAMPET,123,495000,"RESTORATION OF ROAD CUT AT RAMACHANDRA ROAD MADE BY METRO WATER SEWERAGE BOARD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/33228,Parks,Completed,NJ-TEYNAMPET,116,578000,"Providing well and plumbing arrangements for marina lawn No 3 and 4 in div-114, lawn no 5 and 8 in div-116 and lawn no 14 in div-125, U-27, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33231,Roads,Completed,NJ-TEYNAMPET,116,482000,"LAYING OF CEMENT CONCRETE ROAD M30 AT NEELI VEERASAMY STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33294,Roads,Completed,NJ-TEYNAMPET,116,432000,"LAYING OF CEMENT CONCRETE ROAD M30 AT SWAMY STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33296,Roads,Completed,NJ-TEYNAMPET,116,816000,"LAYING OF CEMENT CONCRETE ROAD M30 AT GANAPATHY STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33297,Roads,Completed,NJ-TEYNAMPET,116,666000,"LAYING OF CEMENT CONCRETE ROAD M30 AT HANUMANTHAROYAN KOIL STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33299,Roads,Completed,NJ-TEYNAMPET,116,444000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT THANIKACHALAM STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33300,Roads,Completed,NJ-TEYNAMPET,116,593000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT THOPE VENKATACHALAM STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33301,Roads,Completed,NJ-TEYNAMPET,116,273000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT VEERAPERUMAL STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33302,Roads,Completed,NJ-TEYNAMPET,116,576000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT RAJA HANUMANTHA LALA STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33303,Roads,Completed,NJ-TEYNAMPET,116,340000,"LAYING OF CEMENT CONCRETE ROAD M30 AT ELLAMMAN KOIL STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33304,Roads,Completed,NJ-TEYNAMPET,116,845000,"LAYING OF CEMENT CONCRETE ROAD M30 AT EAST TANK SQUARE STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33305,Roads,Completed,NJ-TEYNAMPET,116,556000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT KANDDAPPAN STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33306,Roads,Completed,NJ-TEYNAMPET,116,774000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT NAMACHIVAYAM STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33307,Roads,Completed,NJ-TEYNAMPET,116,444000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT NARASIMHAN LANE STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33308,Roads,Completed,NJ-TEYNAMPET,116,1178000,"LAYING OF CEMENT CONCRETE ROAD M30 AT ALANGATHA STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33309,Roads,Completed,NJ-TEYNAMPET,116,835000,"LAYING OF CEMENT CONCRETE ROAD M30 AT SOUTH TANK SQUARE STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33310,Roads,Completed,NJ-TEYNAMPET,116,343000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT PARTHASARATHY SWAMY LANE IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33311,Roads,Completed,NJ-TEYNAMPET,116,2096000,"LAYING OF CEMENT CONCRETE ROAD M30 AT SUNGUWAR STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33312,Roads,Completed,NJ-TEYNAMPET,116,254000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT NEELI VEERASAMY 2nd LANE IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33313,Buildings,Completed,NJ-TEYNAMPET,116,454000,"IMPROVEMET OF CEMENT CONCRETE ROAD AT NEELI VEERASAMY 1st LANE IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33314,Roads,Completed,NJ-TEYNAMPET,116,1049000,"LAYING OF CEMENT CONCRETE ROAD M30 AT ESWARADOSS LALA STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33315,Roads,Completed,NJ-TEYNAMPET,116,1411000,"LAYING OF CEMENT CONCRETE ROAD M30 AT VENKATACHALAM STREET IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/3343,Footpath,Completed,NJ-TEYNAMPET,118,998000,"IMPROVEMENTS TO GRANITE FOOTPATH AT MUTHAIYA STREET (NORTH SIDE) FROM CATHEDRAL ROAD CHAINAGE 90.00 M TO 220.00 M IN DIV 118,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33612,Footpath,Completed,NJ-TEYNAMPET,114,746000,"SUPPLYING AND FIXING STAINLESS STEEL PIPES AT KAMARAJAR SALAI FOOT PATH EAST SIDE FROM GALLERY 1 TO GALLERY 14 DAMAGED PORTION IN DIVISION 114,116,120 & 125 ,UNIT 27A,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/3363,Footpath,Completed,NJ-TEYNAMPET,118,995000,"IMPROVEMENTS TO GRANITE FOOTPATH AT MUTHAIYA STREET (NORTH SIDE) CATHEDRAL ROAD CHAINAGE 0.00M TO 90.00 M IN DIV 118,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33651,Buildings,Completed,NJ-TEYNAMPET,116,24980,"supplying and fixing of Mono block motor, Health Faucet, taps, flush cock, western closet, pipe laying and table glass in unit office building at Dr. Besant road in DIV 116, UNIT- 27, ZONE -9",Own Sources,9,2015-16,2018-19 NJ/2015-16/33652,Buildings,Completed,NJ-TEYNAMPET,115,24990,"Supplying and fixing of Over head tank, wash basin, flush cock, taps, motor repair and pipe laying in urudu school at besant road in DIV 115, UNIT- 27, ZONE -9",Own Sources,9,2015-16,2017-18 NJ/2015-16/3366,Footpath,Completed,NJ-TEYNAMPET,118,997000,"IMPROVEMENTS TO GRANITE FOOTPATH AT MUTHAIYA STREET (SOUTH SIDE) FROM CATHEDRAL ROAD IN DIVISION- 118,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33682,Buildings,Completed,NJ-TEYNAMPET,110,628000,"IMPROVEMENTS TO ELECTION RETURNING OFFICER ROOM IN SECOND FLOOR AT ZONAL OFFICE 9 LAKE AREA 4TH CROSS STREET IN DIVISION 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33758,Roads,Completed,NJ-TEYNAMPET,117,427000,"FLOOD DAMAGED ROADS REPAIRS AT DR SADASIVAM ROAD IN DIV 117,UNT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/33873,Buildings,Completed,NJ-TEYNAMPET,115,540000,"MAINTENANCE OF PRE FABRICATED URINAL UNITS AT VARIOUS LOCATIONS IN DIVISIONS-114,115,116,120 & 121 IN UNIT-27,ZONE-09 PERIOD (01.06.2016 TO 30.09.2016) 4 MONTHS",Own Sources,9,2015-16,2019-20 NJ/2015-16/33915,Roads,Completed,NJ-TEYNAMPET,109,360000,"MAINTENANCE OF PRE FABRICATED URINAL UNITS AT VARIOUS LOCATIONS IN DIVISIONS-109,110,111,118 & 119 IN UNIT-24,ZONE-09 PERIOD (01.06.2016 TO 30.09.2016) 4 MONTHS",Own Sources,9,2015-16,2019-20 NJ/2015-16/33921,Buildings,Completed,NJ-TEYNAMPET,115,24900,"Plastering the old damaged roof & painting the walls in division office at devaraj street in div-115,unit-27,zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/33939,Buildings,Completed,NJ-TEYNAMPET,115,24500,"Supplying and fixing of plumbing and electrical materials in amma unavagam at westcot road in div-115,u-27,z-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/33941,Buildings,Completed,NJ-TEYNAMPET,115,24500,"Supplying and fixing of plumbing and electrical materials in cms at Beasant road in div-115,u-27,z-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/3400,Roads,Completed,NJ-TEYNAMPET,118,1456000,Relaying the Road with BC 40mm Thick by Paver Finisher at Kasthuri Estate 2nd Street (Under MLA constituency Development Scheme 2015-16) in Dn-118 Unit-24 Zone-09,MLACDS,9,2015-16,2016-17 NJ/2015-16/3401,Roads,Completed,NJ-TEYNAMPET,109,2460000,Relaying the Road with BC 40mm Thick by Paver Finisher at Basha Street (Under MLA constituency Development Scheme 2015-16) in Dn-109 Unit-24 Zone-09,MLACDS,9,2015-16,2016-17 NJ/2015-16/34360,Roads,Completed,NJ-TEYNAMPET,115,1130000,"RELAYING THE EXISTING B.T. ROAD WITH C.C. ROAD AT IRUSAPPAN STREET IN DN-115, U-27, Z-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/34361,Roads,Completed,NJ-TEYNAMPET,115,990000,"RELAYING THE EXISTING C.C. ROAD AT GULAM HUSSAIN ALI KHAN STREET IN DN-115, U-27, Z-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/34362,Roads,Completed,NJ-TEYNAMPET,115,880000,"RELYING THE EXISTING C.C. ROAD AT HUSSAIN ALI KHAN ST AND HUSSAIN ALI KHAN 1st STREET IN DN-115, U-2, Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/34480,Roads,Completed,NJ-TEYNAMPET,124,77000,"Flood Damaged repair work in Ganapathy Colony in Division-124, Unit-25, Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/3465/C,Roads,Completed,NJ-TEYNAMPET,117,130000,"Attending Patch at Jayammal Street for Flood damages caused to Infra structure in Div 117,Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/35075,Roads,Completed,NJ-TEYNAMPET,126,1000000,"Repairs and Maintenance of footpath at various street in Div-126,Unit-25,Zone-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/4016,Buildings,Completed,BR-Bus Route Roads,113,900000,"IMPROVEMENTS TO ROUND TANA PARK AT VALLUVAR KOTTAM HIGH ROAD IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4041,Buildings,Completed,NJ-TEYNAMPET,114,387000,"IMPROVEMENTS TO CMS SCHOOL AND CREATING NEW MODEL CLASS ROOMS FOR LKG SECTION AT TYPHOON ALI KHAN STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4042,Buildings,Completed,NJ-TEYNAMPET,114,490000,"Attending patch work bituminous coarse 40mm thick by paver finishing at Victoria Hostel Road,Mayor Citibabu Street,Quaid-E- Millath Road,Subathral Street,Ellis Road and Kuppu muthu Street in dn-114,Unit-27,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/4043,Buildings,Completed,NJ-TEYNAMPET,120,175000,"PROVIDING BOREWELL AND FIXING MOTOR FOR PC AT KANDAPPA STREET IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4045,Buildings,Completed,NJ-TEYNAMPET,120,252000,"CONSTRUCTION AND RAISING THE COMPOUND WALL IN ICDS AT V.R STREET IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4046,Buildings,Completed,NJ-TEYNAMPET,116,349000,"DEMOLISING THE OLD BUILDING AT FIRST FLOOR AND PRECAUTION WORKS AT GROUND FLOOR IN CMS SCHOOL CAMPUS AT V.R STREET IN DN-116,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4053,Parks,Completed,NJ-TEYNAMPET,118,400000,"ANNUAL MAINTENANCE OF THIRU.VI.KA.PARK (TWO YEARS) AT SRINIVASAPERUMALSANATHY 2ND STREET IN DN-118 ,UNIT-24 ,ZONE-9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/4083,Roads,Completed,NJ-TEYNAMPET,110,636000,"LAYING CEMENT CONCRETE ROAD WITH RMC M40 GRADE AT APPU STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4084,Parks,Completed,NJ-TEYNAMPET,118,877000,"IMPROVEMENTS WORKS FOR GOMATHY NARAYANASAMY PARK AT MUTHIYA STREET IN Dn-118,U-24,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4113,Parks,Completed,NJ-TEYNAMPET,118,530000,"ANNUAL MAINTENANCE OF G.N. PARK AT MUTHIAH STREET FOR TWO YEARS IN DIV-118,UNIT-24,ZONE-9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/4116,Buildings,Completed,NJ-TEYNAMPET,119,970000,"CONSTRUCTION OF COMPOUND WALL AND PROVIDING BOREWELL AND WATER SUPPLY ARRANGEMENTS AT DHOBIKANA AT MUTHAIYA GARDEN STREET, IN DIVISION-119,UNIT-24,ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/4174,Parks,Completed,NJ-TEYNAMPET,109,345000,"ANNUAL MAINTENANCE OF NAMACHIVAYAPURAM PARK AT WEST NAMACHIVAYAPURAM ( TWO YEARS ) IN DIVISION -109, UNIT-24, ZONE-IX.",Own Sources,9,2015-16,2018-19 NJ/2015-16/4216,Buildings,Completed,NJ-TEYNAMPET,114,541000,"IMPROVEMENTS TO CMS SCHOOL AND CREATING NEW MODEL CLASS ROOMS FOR LKG SECTION AT CMS BANGARU STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4219,Buildings,Completed,NJ-TEYNAMPET,114,434000,"IMPROVEMENTS TO CUMS SCHOOL AND CREATING NEW MODEL CLASS ROOMS FOR LKG SECTION AT CUMS VALLABA AGRAHARAM STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/4221,Parks,Completed,NJ-TEYNAMPET,126,952000,"OUT SOURCING FOR PARK BY PRIVATE AGENCY AT LOOP ROAD (FOR 2 YEARS) IN DIV 126,UNIT-25,ZONE-9 (BY QUALIFIED HORTICULTURIST)",Own Sources,9,2015-16,2017-18 NJ/2015-16/4223,Parks,Completed,NJ-TEYNAMPET,112,483000,MAINTANANCE TO ANBHALAGAN PARK AT 6TH STREET TRUSTPURAM (PRIVATE OF CONSERVENCY) FOR TWO YEARS IN DN 112 UNIT 26 ZONE 9.,Own Sources,9,2015-16,2018-19 NJ/2015-16/4386,Roads,Completed,NJ-TEYNAMPET,114,1497000,"Providing and fixing SS Grill for centre median in front of Madras University at Wallaja road in dn-114 Unit-27,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/4414,Roads,Completed,NJ-TEYNAMPET,121,995000,"Attending patch work Bituminous coarse 40mm thick by paver finishing at various street in dn-121,Unit-27,Zone-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/4422,Footpath,Completed,NJ-TEYNAMPET,114,717000,"Maintenance of pre fabricated urinal unit in dn-114,115,116 and 120 ,unit-27,zone-9.",Own Sources,9,2015-16,2019-20 NJ/2015-16/4562,Footpath,Completed,NJ-TEYNAMPET,122,740000,"FORMING THE RUBBER MOULDED GREY PREMIUM CONCRETE FOOTPATH AT TURNBULLS ROAD EXTENSION IN DN-122, UNIT-26, ZONE-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/5004,Buildings,Completed,NJ-TEYNAMPET,109,290000,"DESILITING OF OPEN WELL AND REPAIRS TO MOTOR PUMP AT NUNGAMBAKKAM SUBWAY DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5055,Storm Water Drain,Completed,NJ-TEYNAMPET,117,995000,"IMPROVEMENTS TO S.W.D AT G.N.CHETTY ROAD (FROM DR.B.NARASHIMAN ROAD TO DR.GIRIAPPA ROAD) IN DIV 117 UNIT-26, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5342,Roads,Completed,NJ-TEYNAMPET,111,468000,"LAYING OF CEMENT CONCRETE AT BUDHI BEGUM 1ST LANE IN DN111,U24,Z9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/5393,Buildings,Completed,NJ-TEYNAMPET,114,186500,"CONVERTING THE ELECTRICAL ROOM INTO E-SEVA ROOM IN DIVISION OFFICE CAMPUS AT ARUNACHALAM STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5429,Parks,Completed,NJ-TEYNAMPET,111,380000,"ANNUAL MAINTENANCE OF CORPORATION PARK AT NUNGAMBAKKAM 4 TH LANE IN DIVISION-111,UNIT-24 ,ZONE-09",Own Sources,9,2015-16,2017-18 NJ/2015-16/5431,Parks,Completed,NJ-TEYNAMPET,111,510000,"ANNAUL MAINTENANCE OF CORPORATION PARK (TWO YEARS ) AT SATHYAM THEATRE BACK SIDE AT WHITES SALAI IN DIVISION-111,UNIT-4 ,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/5434,Parks,Completed,NJ-TEYNAMPET,111,300000,"ANNUAL MAINTENENCE OF KO.SI. MANI PARK AT THIRU.VI.KA SALAI (TWO YEARS) IN DIVISION-111,UNIT-24,ZONE-9",Own Sources,9,2015-16,2018-19 NJ/2015-16/5443,Parks,Completed,NJ-TEYNAMPET,111,680000,"ANNUAL MAINTENECE OF SPENCER PLAZA PARK AT BINNY SALAI SPENCER PLAZA (TWO YEARS) IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2015-16,2018-19 NJ/2015-16/5480,Parks,Completed,NJ-TEYNAMPET,123,990000,"PLANTATION OF NAGESHWARA PARK AT LUZ CHURCH ROAD IN DN:123, UNIT.25, ZONE.9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5682,Footpath,Completed,NJ-TEYNAMPET,113,998000,IMPROVEMENTS TO FOOTPATH AT GOPATHY NARAYANA SALAI IN DIVSION 113 UNIT 26 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/5755,Footpath,Completed,NJ-TEYNAMPET,118,526000,"FORMING FOOT PATH AT RATHINAM STREET AT DN-118,UNIT-24,ZONE,9",Deposit Works,9,2015-16,2016-17 NJ/2015-16/5795,Footpath,Completed,NJ-TEYNAMPET,118,834000,"FORMING FOOTPATH AT BASENT ROAD AT DN-118,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5819,Footpath,Completed,NJ-TEYNAMPET,118,600000,"FORMING FOOTPATH AT GANAPATHY COLONY 2ND STREET AT DN-118, UNIT-24, ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5820,Footpath,Completed,NJ-TEYNAMPET,118,595000,"FORMING FOOTPATH AT GOVARDHAN STREETIN BOTH SIDE AT DN-118,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5823,Footpath,Completed,NJ-TEYNAMPET,118,959000,"REPAIR AND IMPROVMENT TOFOOTPATH AT AVAI SHANMUGAM SALAI IN DN-118,UNIT-24,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/5897,Buildings,Completed,NJ-TEYNAMPET,123,995000,"IMPROVEMENTS TO KITCHEN SHED FOR MIDDLE SCHOOL AT ST. MARY'S ROAD IN DN.123, UNIT.25, ZONE-9 (WARD MEMBER DEVELOPMENT SCHEME - 2015-16)",Own Sources,9,2015-16,2016-17 NJ/2015-16/6138,Buildings,Completed,NJ-TEYNAMPET,123,999000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT THIRUVALLUVAR SALAI IN DN.123, UNIT.25, ZONE.9 (WARD MEMBER DEVELOPMENT SCHEME 2015-16)",Own Sources,9,2015-16,2016-17 NJ/2015-16/6267,Roads,Completed,NJ-TEYNAMPET,111,857000,"providing speed breakers at various streets in dn 111,unit 24,zone 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6268,Roads,Completed,NJ-TEYNAMPET,119,862000,"PROVIDING SPEED BREAKERS AT VARIOUS STREETS IN DN 119,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6724,Buildings,Completed,NJ-TEYNAMPET,109,595000,"IMPROVEMENTS TO AMMA UNAVAGAM AT SHANMUGANAR SALAI IN DN:109, UNIT:24, ZONE:9",Own Sources,9,2015-16,2017-18 NJ/2015-16/6802,Buildings,Completed,NJ-TEYNAMPET,110,978000,"IMPROVEMENTS TO NIGHT SHELTERS AT KAMDHAR NAGAR 1ST STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6887,Storm Water Drain,Completed,NJ-TEYNAMPET,122,300000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT ADAYAR CLUB GATE ROAD IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6910,Storm Water Drain,Completed,NJ-TEYNAMPET,122,300000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT ABM AVENUE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6948,Storm Water Drain,Completed,NJ-TEYNAMPET,122,130000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT GANAPATHY COLONY MAIN ROAD IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6976,Storm Water Drain,Completed,NJ-TEYNAMPET,122,53000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT GANAPATHY COLONY 3RD STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6989,Storm Water Drain,Completed,NJ-TEYNAMPET,122,150000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT BOAT CLUB 2ND AVENUE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/6990,Storm Water Drain,Completed,NJ-TEYNAMPET,122,140000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT BOAT CLUB 1ST AVENUE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7091,Buildings,Completed,NJ-TEYNAMPET,110,715000,"CONSTRUCTION OF R.O.PLANT ROOM AND WATER SUPPLAY ARRANGEMENTS AT CHENNAI GIRLS HIGHER SECONDARY SCHOOL AND KAMDHAR NAGAR PRIMARY SCHOOL,SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",MPLADS,9,2015-16,2018-19 NJ/2015-16/7219,Storm Water Drain,Completed,NJ-TEYNAMPET,122,160000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT CHITHARANJAN ROAD IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7220,Storm Water Drain,Completed,NJ-TEYNAMPET,122,50000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT T.T.K 1ST CROSS STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7235,Storm Water Drain,Completed,NJ-TEYNAMPET,122,125000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT CHAMIERS 4TH LANE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7236,Storm Water Drain,Completed,NJ-TEYNAMPET,122,56000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT CHAMIERS 3RD LANE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7275,Storm Water Drain,Completed,NJ-TEYNAMPET,122,89000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 4TH STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7276,Storm Water Drain,Completed,NJ-TEYNAMPET,122,83000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 12TH STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7280,Storm Water Drain,Completed,NJ-TEYNAMPET,122,93000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 11TH STREET IN DN - 122, UNIT - 26, ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7283,Storm Water Drain,Completed,NJ-TEYNAMPET,122,139000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 10TH STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7290,Storm Water Drain,Completed,NJ-TEYNAMPET,122,40000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 9TH STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7291,Storm Water Drain,Completed,NJ-TEYNAMPET,122,57000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 7TH STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7296,Storm Water Drain,Completed,NJ-TEYNAMPET,122,78000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 1ST STREET IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7301,Storm Water Drain,Completed,NJ-TEYNAMPET,122,135000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT NANDANAM EXTN 1ST MAIN ROAD IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7402,Storm Water Drain,Completed,NJ-TEYNAMPET,117,379000,"Providing vertical gratings existing Storm water drain at Dr.Thomas Road in Dn-117, Unit-26, Zone-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/7403,Storm Water Drain,Completed,NJ-TEYNAMPET,117,379000,"Providing vertical gratings existing Storm water drain at Bagirathiammal Street in Dn-117, Unit-26, Zone-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/7405,Storm Water Drain,Completed,NJ-TEYNAMPET,117,148000,"Providing vertical gratings existing Storm water drain at Chevaliar Sivaji Ganesan Road (TNSCB) in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7407,Storm Water Drain,Completed,NJ-TEYNAMPET,117,148000,"Providing vertical gratings existing Storm water drain at Sarangapani Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7485,Storm Water Drain,Completed,NJ-TEYNAMPET,122,60000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT CENATOPH 1ST LANE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7487,Storm Water Drain,Completed,NJ-TEYNAMPET,122,110000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT CENATOPH 2ND LANE IN DN - 122,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7489,Footpath,Completed,NJ-TEYNAMPET,119,995000,"PROVIDING STAINLESS STEEL HANDRAIL AT AVVAI SHANMUGAM SALAI REACH-I (From Indian Bank to HDFC Bank ATM) IN DIVISION-119,UNIT-24,ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7490,Footpath,Completed,NJ-TEYNAMPET,119,995000,"PROVIDING STAINLESS STEEL HANDRAIL AT AVVAI SHANMUGAM SALAI REACH-II (From HDFC Bank ATM to Red Rose Building) IN DIVISION-119,UNIT-24,ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7491,Footpath,Completed,NJ-TEYNAMPET,119,995000,"PROVIDING STAINLESS STEEL HANDRAIL AT AVVAI SHANMUGAM SALAI REACH-III (From Tea Shop to Lakshmipuram Main Road) IN DIVISION-119,UNIT-24,ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7492,Footpath,Completed,NJ-TEYNAMPET,119,995000,"PROVIDING STAINLESS STEEL HANDRAIL AT AVVAI SHANMUGAM SALAI REACH-IV (From Lakshmipuram Main Road to Jn.of TTK Raod) IN DIVISION-119,UNIT-24,ZONE-9.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7539,Storm Water Drain,Completed,NJ-TEYNAMPET,117,359000,"Providing vertical gratings existing Storm water drain at Lakshmi Colony in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7542,Storm Water Drain,Completed,NJ-TEYNAMPET,117,548000,"Providing vertical gratings existing Storm water drain at North Cresent Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7544,Storm Water Drain,Completed,NJ-TEYNAMPET,117,352000,"Providing vertical gratings existing Storm water drain at Saravana Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7546,Storm Water Drain,Completed,NJ-TEYNAMPET,117,100000,"Providing vertical gratings existing Storm water drain at Arcot Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7549,Storm Water Drain,Completed,NJ-TEYNAMPET,117,642000,"Providing vertical gratings existing Storm water drain at Mambalam High Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7550,Storm Water Drain,Completed,NJ-TEYNAMPET,117,352000,"Providing vertical gratings existing Storm water drain at Ramakrishna Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7555,Storm Water Drain,Completed,NJ-TEYNAMPET,117,454000,"Providing vertical gratings existing Storm water drain at Arulamabal Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7589,Storm Water Drain,Completed,NJ-TEYNAMPET,114,245000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT CHELLA PILLAYAR KOIL STREET JN OF FAKKIR STREET IN DN-114,UNIT-27,ZONE-9 [FOR WARD COUNCILLOR FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/7594,Storm Water Drain,Completed,NJ-TEYNAMPET,114,996000,"CONSTRUCTION OF RCC STORM WATER DRAINAGE AT FAKKIR STREET FROM MARKET JN TO BHARATHI SALAI IN DN-114,UNIT-27,ZONE-9 [ FOR COUNCILLOR WARD FUND ]",Own Sources,9,2015-16,2016-17 NJ/2015-16/7649,Buildings,Completed,NJ-TEYNAMPET,109,478000,"PROVIDING AND FIXING RO PLANT TO SANKARAPURAM CHS SCHOOL IN DN-109,U-24,Z-9(MP FUND 2015-16)",MPLADS,9,2015-16,2018-19 NJ/2015-16/7655,Electrical,Completed,NJ-TEYNAMPET,120,3923700,"Supply Erection and Commissioning of THREE nos of 30 mtr High mast lighting at one of Marina beach service Road near Avvaiyar Statue and two nos of Light house back side in div-120&125, Unit 27A, Zone-IX",Own Sources,9,2015-16,2016-17 NJ/2015-16/7715,Roads,Completed,NJ-TEYNAMPET,119,990000,"ATTENDING BT PATCH WORK FOR DAMAGED ROADS V.M STREET, AVVAI SHANMUGAM SALAI AND TEACHERS COLONY IN DIVISION-119,UNIT-24,ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/7730,Buildings,Completed,NJ-TEYNAMPET,112,572000,"Construction of Decomposting Yard at Puliyur 1st main Road in Dn-112,U-26,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7815,Storm Water Drain,Completed,NJ-TEYNAMPET,112,876000,"IMPROVEMENTS AND REPAIRS TO STORM WATER DRAIN AT SOWRASTRA NAGAR 8TH STREET IN DIV 112, UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7864,Footpath,Completed,NJ-TEYNAMPET,125,650000,REPAIRS AND IMPROVEMENTS TO FOOT PATH AND KERB WALLS AND PROVIDING BARRICADING WORKS AT MARINA BEACH FOR GLOBAL INVESTORS MEET PROGRAM IN DIVISION 125 UNIT 25 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/7899,Storm Water Drain,Completed,NJ-TEYNAMPET,112,183000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT ZAKARIA COLONY MAIN ROAD IN DN - 112, UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7929,Storm Water Drain,Completed,NJ-TEYNAMPET,112,143000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT ZAKARIA COLONY 4TH MAIN ROAD IN DN - 112, UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7931,Storm Water Drain,Completed,NJ-TEYNAMPET,112,159000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT PULIYUR MAIN ROAD IN DN - 112, UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/7934,Storm Water Drain,Completed,NJ-TEYNAMPET,112,203000,"REPAIRS TO SWD AND PROVIDING VERTICAL GRATING, PVC PIPE AT SIVAN KOIL STREET IN DN - 112, UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/8172,Buildings,Completed,NJ-TEYNAMPET,116,199000,SUPPLYING AND INSTALATION OF PRE-FABRICATED URINAL AT B.V.NAICKEN STREET NEAR TRANSFORMER AND T.H.ROAD NEAR CORPORATION MIDDLE SCHOOL,Own Sources,9,2015-16,2019-20 NJ/2015-16/8262,Storm Water Drain,Completed,NJ-TEYNAMPET,111,990000,"DRAIN OUT THE RAIN WATER FROM ROAD SIDE AT WHITES ROAD (NEAR JUNCTION OF ANNA SALAI AND NEAR HOBART MUSLIM GIRLS HR SEC SCHOOL) DIVISION -111, UNIT-24, ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/8269,Roads,Completed,NJ-TEYNAMPET,119,996000,"SUPPALYING AND PLANTATIONS FOR CENTRE MEDIAN AT Dr.RADHA KRISHANAN SALAI IN DIVISIONS : 118,119,121,&125 ,UNIT-24 & 25, ZONE-IX.",Own Sources,9,2015-16,2016-17 NJ/2015-16/8276,Roads,Completed,NJ-TEYNAMPET,114,977000,"LAYING CEMENT CONCRETE ROAD AT FAKKIR STREET [ FROM JN OF PILLAYAR KOIL STREET TO JN HABIBULLAH STREET ] IN DN-114,UNIT-27,ZONE-9 [FOR COUNCILLOR WARD FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/8280,Roads,Completed,NJ-TEYNAMPET,114,771000,"LAYING CEMENT CONCRETE ROAD AT FAKKIR STREET [FROM JN HABIBULLAH STREET TO BHARATHI SALAI ] IN DN-114,UNIT-27,ZONE-9[ FOR COUNCILLOR WARD FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/8296,Buildings,Completed,NJ-TEYNAMPET,120,925000,"IMROVEMENTS TO CHENNAI MIDDLE SCHOOL AT BESANT PALLI STREET IN DN-120,UNIT-14,ZONE-9 [ FOR COUNCILLOR WARD FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/8303,Playfields,Completed,NJ-TEYNAMPET,120,381000,"IMPROVEMENTS TO CHILDREN PLAY GROUND AT NADUKUPPAM IN DN-120,UNIT-27,ZONE-9 [FOR COUNCILLOR WARD FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/8337,Roads,Completed,NJ-TEYNAMPET,113,999000,"LAYING CEMENT CONCRETE ROAD AT SHENOY ROAD IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/8338,Roads,Completed,NJ-TEYNAMPET,113,568000,"LAYING CEMENT CONCRETE ROAD AT NORTH MADA STREET IN DIV 113,UNIT-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/8340,Parks,Completed,NJ-TEYNAMPET,113,717000,"2015-16 ,MAINTENECE WORK OUT SOURCING OF CORPORATION PARK (Near Diagnostic Lab ) AT KODAMBAKKAM HIGH ROAD FOR TWO YEARS IN DIV 113,U 26,Z 9 .(BY qualified Horticulturist only)",Own Sources,9,2015-16,2017-18 NJ/2015-16/8463,Roads,Completed,NJ-TEYNAMPET,113,135000,RESTORATION OF ROAD CUT AT KANNAIAH STREET IN DIVISION 113 UNIT 26 ZONE 09,Deposit Works,9,2015-16,2016-17 NJ/2015-16/8487,Buildings,Completed,NJ-TEYNAMPET,121,995000,Improvement to the Footpath from front of Chennai Boy High School to Door No.62 at LLOYDS Road IN DN-121 U-27 Z-9 (Councillor Ward Fund),Own Sources,9,2015-16,2018-19 NJ/2015-16/8526,Buildings,Completed,NJ-TEYNAMPET,125,353000,"REPAIRS AND IMPROVEMENTS TO TOILET INSIDE CREMATORIUM BUILDING IN MYLAPORE BURIAL GROUND IN DIVISION - 125, UNIT - 25, ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/8583,Footpath,Completed,NJ-TEYNAMPET,117,462000,"FORMING THE RUBBER MOULDED GREY PREMIUM CONCRETE FOOTPATH AT HINDI PRACHARA SABHA IN DN - 117,UNIT - 26,ZONE - 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/8587,Storm Water Drain,Completed,NJ-TEYNAMPET,113,880000,"Improvements to SWD at Dharmapuram Main road (from Kodambakkam High road to Dharmapuram 1st street ) in Dn113, Unit-26,Zone-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/8590,Storm Water Drain,Completed,NJ-TEYNAMPET,109,589000,"DESILTING AND IMPROVEMENT OF OPEN STROM WATER DRAIN OF PROVIDING TOP SLAB FROM THIRUVENKADAPURAM 2ND STREET CANAL TO CHOOLAIMEDU HIGH ROAD IN DN 109,U-24,Z-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/8612,Footpath,Completed,NJ-TEYNAMPET,121,500000,IMPROVEMENTS TO THE FOOTPATH AND KERB WALLS AT DR RADHA KRISHNAN SALAI IN DIVSION 121 UNIT 27 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/8895,Roads,Completed,NJ-TEYNAMPET,113,700000,"LAYING CEMENT CONCRETE AT PRAGASAM STREET IN DIV 113,U-26,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9138,Footpath,Completed,NJ-TEYNAMPET,113,150000,"Providing vertical gratings existing Storm water drain at Krishnama Road in Dn-113, Unit-26, Zone-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/9198,Footpath,Completed,NJ-TEYNAMPET,113,110000,"Providing vertical gratings existing Storm water drain at krishabhai street in Dn -113, Unit-26, Zone-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/9199,Footpath,Completed,NJ-TEYNAMPET,113,325000,"Providing vertical gratings existing Storm water drain at Prakasam street in Dn -113, Unit-26, Zone-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/9201,Footpath,Completed,NJ-TEYNAMPET,113,80000,"Providing vertical gratings existing Storm water drain at Habibulla Road (Thirumalai Pillai to Krishnabhai Street) in Dn -113, Unit-26, Zone-09",Own Sources,9,2015-16,2016-17 NJ/2015-16/9229,Buildings,Completed,NJ-TEYNAMPET,121,325000,"REPAIRS AND IMPROVEMENTS TO GRANITE KERB WALLS AND GRANITE FOOTPATH AT MARINA BEACH SERVICE ROAD IN DN 121, UNIT 27, ZONE 9.",Own Sources,9,2015-16,2017-18 NJ/2015-16/9242,Parks,Completed,NJ-TEYNAMPET,119,995000,"REPAIRS TO TO THE PATH WAY AND IMPROVEMENTS TO THE PARK AT CIT COLONY IN DIVISION-119, UNIT-24, ZONE-IX. (Under Counciler Fund)",Own Sources,9,2015-16,2016-17 NJ/2015-16/9256,Buildings,Completed,NJ-TEYNAMPET,115,555000,"IMPROVEMENTS TO CMS AT SOORAPAN STREET AND PROVIDING WATER SUPPLY ARRANGEMENTS AND RAIN WATER HARVESTING IN AMMA UNAVAGAM AT WEST COTT ROAD IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9257,Buildings,Completed,NJ-TEYNAMPET,115,956000,"IMPROVMENTS TO CHENNAI PRIMARY SCHOOL AT DR.BESANT ROAD IN DN-115,UNIT-27,ZONE-9[ FOR WARD COUNCILLOR FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/9263,Buildings,Completed,NJ-TEYNAMPET,115,998000,"IMPROVEMENTS TO CUMS AND ICDS AT DR. BESANT ROAD AND IMPROVEMENTS TO ICDS AT THIRUNAVUKKARASU STREET IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9265,Roads,Completed,NJ-TEYNAMPET,119,990000,ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 119 UNIT 24 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/9301,Parks,Completed,NJ-TEYNAMPET,119,980000,IMPROVEMENTS TO THE PARTHA SARATHY PARK AT VM STREET IN DN-119 U-24 Z-9,Own Sources,9,2015-16,2016-17 NJ/2015-16/9341,Parks,Completed,NJ-TEYNAMPET,113,220000,IMPROVEMENTS TO THE PLAY FIELDS AND FORMING ADDITIONAL PATHWAY TO PERIYAR PARK AT KODAMBAKKAM HIGH ROAD IN DIVISION 113 UNIT 26 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/9430,Roads,Completed,NJ-TEYNAMPET,111,997000,ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVSION 111 UNIT 124 ZONE 09,Own Sources,9,2015-16,2016-17 NJ/2015-16/9503,Buildings,Completed,NJ-TEYNAMPET,114,957000,"ATTENDING REPAIR WORKS FOR CUMS VALLABA AGRAHARAM STREET,ADDITIONAL IMPROVEMENTS TO TOILET BLOCK AT CMS AT BELLS ROAD , REPAIR WORKS AT KAMARAJAR SALAI AND MARINA SERVICE ROAD IN DN-114, UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9513,Buildings,Completed,NJ-TEYNAMPET,115,345000,"CONSTRUCTION OF COMPOUND WALL AND OTHER IMPROVEMENTS TO NUHM AT ROB 6TH STREET IN DN-115,UNIT-27,ZONE-9[FOR WARD COUNCILLOR FUND]",Own Sources,9,2015-16,2016-17 NJ/2015-16/9537,Playfields,Completed,NJ-TEYNAMPET,120,997000,"ADDITIONAL IMPROVMENTS TO CHILDREN PLAY GROUND AT NADUKUPPAM 6TH STREET IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9720,Buildings,Completed,NJ-TEYNAMPET,116,979000,"IMPROVEMENTS WORKS AT CMS IN QUIAD-E-MILLATH ROAD IN Dn-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9722,Storm Water Drain,Completed,NJ-TEYNAMPET,109,59000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT RAJAVEETHI IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9726,Storm Water Drain,Completed,NJ-TEYNAMPET,109,65000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT BAJANAI KOIL STREET EAST IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9728,Buildings,Completed,NJ-TEYNAMPET,116,952000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT PALANI AMMAN KOIL 6TH STREET IN DN-116,U-27,Z-9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9735,Storm Water Drain,Completed,NJ-TEYNAMPET,109,53000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT BAJANAI KOIL STREET SOUTH IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9748,Storm Water Drain,Completed,NJ-TEYNAMPET,109,65000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT BAJANAI KOIL STREET NORTH IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9758,Storm Water Drain,Completed,NJ-TEYNAMPET,109,61000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT BAJANAI KOIL CROOS STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9760,Storm Water Drain,Completed,NJ-TEYNAMPET,109,66000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT SANKARAPURAM MAIN ROAD IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9775,Buildings,Completed,NJ-TEYNAMPET,118,900000,"IMPROVEMENTS TO DISPENSARY GROUND FLOOR & FIRST FLOOR AT AMMAIYAPPAN STREET IN DIVISION-118,UNIT-24,ZONE-9",Own Sources,9,2015-16,2017-18 NJ/2015-16/9856,Storm Water Drain,Completed,NJ-TEYNAMPET,109,54000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT SANKARAPURAM 1ST STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9858,Storm Water Drain,Completed,NJ-TEYNAMPET,109,53000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT SANKARAPURAM 3RD STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9859,Storm Water Drain,Completed,NJ-TEYNAMPET,109,50000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT SANKARA PURAM 4TH STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9860,Storm Water Drain,Completed,NJ-TEYNAMPET,109,44000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT BASHA STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9862,Storm Water Drain,Completed,NJ-TEYNAMPET,109,70000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT ABITH NAGAR IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9865,Storm Water Drain,Completed,NJ-TEYNAMPET,109,87000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT THIRUVENGADAPURAM 1ST STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9866,Storm Water Drain,Completed,NJ-TEYNAMPET,109,65000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT ANNA NEDUMPATHAI IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9867,Storm Water Drain,Completed,NJ-TEYNAMPET,109,65000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT KALYANAPURAM IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9870,Storm Water Drain,Completed,NJ-TEYNAMPET,109,65000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT SHANMUGANAR SALAI IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9871,Storm Water Drain,Completed,NJ-TEYNAMPET,109,57000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT THIRUVALLUVAR PURAM 1ST STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NJ/2015-16/9872,Storm Water Drain,Completed,NJ-TEYNAMPET,109,68000,"PROVIDING AND FIXING FRP VERTICAL GRATTING TO THE EXISTING STORM WATER DRAIN AT THIRUVENGADAPURAM MAIN ROAD IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2015-16,2016-17 NK/2015-16/0011,Electrical,Completed,NK-KODAMBAKKAM,130,870000,Improvement to CMS at amman koil street in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/0207,Roads,Completed,NK-KODAMBAKKAM,140,660000,"PROPOSED CEMENT CONCRETE ROAD (M20) GRADE AT PUSHPAVATHY AMMAL CANAL ROAD (REACH-2)FROM PUSHPAVATHY AMMAL 2ND STREET TO GOVINDAN ROAD IN DIV-140,U-30,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/0209,Roads,Completed,NK-KODAMBAKKAM,140,660000,"PROPOSED CEMENT CONCRETE ROAD (M20) GRADE AT PUSHPAVATHY AMMAL CANAL ROAD (REACH-1)FROM LAKSHMI STREET TO PUSHPAVATHY AMMAL 2ND STREET IN DIV-140,U-30,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/0260,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,927000,"REPAIR AND IMPROVEMENTS SWD VARIOUS STREET IN DIVISION - 141,UNIT -30, ZONE - 10.",Own Sources,10,2015-16,2016-17 NK/2015-16/0365,Roads,Completed,NK-KODAMBAKKAM,131,995000,"PROPOSED CONSTRUCTION OF MODERN STAINLESS STEEL BUS SHELTER AT WEST SIDE P.T.RAJAN SALAI (OFF SIVAN PARK) IN DIVISION-131,UNIT-28, ZONE-10 (UNDER WARD COUNCILLOR FUND)",Own Sources,10,2015-16,2016-17 NK/2015-16/0668,Buildings,Completed,NK-KODAMBAKKAM,141,151000,"ANNUAL MAINTENANCE OF BIO GAS PLANT AT CIT NAGAR AMMA UNAVAGAM IN DIVISION - 141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/0808,Buildings,Completed,NK-KODAMBAKKAM,130,628000,"PROVIDING e TOILET (MALE TOILET) AT NORTH MADA STREET IN DIV-130,UNIT-29, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/0809,Buildings,Completed,NK-KODAMBAKKAM,130,628000,"PROVIDING e TOILET (FEMALE TOILET) AT NERKUNDRAM PATHAI STREET EAST IN DIV-130, UNIT-29, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/0900,Footpath,Completed,NK-KODAMBAKKAM,134,617000,"IMPROVEMENTS TO THE FOOTPATH AND STROMWATERDRAIN AT SUBRAMANIA NAGAR 1 ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/0906,Footpath,Completed,NK-KODAMBAKKAM,135,875000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT VEERASAMY STREET AND GIRI STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/0913,Buildings,Completed,NK-KODAMBAKKAM,133,527000,IMPROVEMENTS TO THE EXISTING NNMPSHED (ANGANWADI ) AT VARIOUS STREET IN DN 133 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/1006,Buildings,Completed,NK-KODAMBAKKAM,130,573000,"PROPOSED SUPPLYING AND FIXING OF MOBILE URINALS AT FIVE DIFFERENT LOCATIONS IN DIV-130, UNIT-29,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10076,Roads,Completed,NK-KODAMBAKKAM,140,871000,"ATTENDING THE PATCH WORK AT DHANABAL STREET, KANNIYAMMAN KOIL STREET AND VARIOUS STREET IN DIVISION-140, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/10079,Parks,Completed,NK-KODAMBAKKAM,140,983001,"PROVIDING CURVED PLANTES BOX IN NORTH SIDES OF MAIN ENTRY OF TDR LAND PARK AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10081,Buildings,Completed,NK-KODAMBAKKAM,140,995000,"PROVIDING OUTSIDE THE FOOTPATH PLANTING TREE WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10082,Parks,Completed,NK-KODAMBAKKAM,140,859000,"PROVIDING THE PEBBLE PATH WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10084,Buildings,Completed,NK-KODAMBAKKAM,140,699000,"PROPOSED CONSTRUCTION WORK FOR ELECTRICAL WORKERS ROOM IN DIVISION OFFICE AT KODAMBAKKAM ROAD IN DIVISION-140, UNIT-30,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10086,Buildings,Completed,NK-KODAMBAKKAM,140,857000,"PROPOSED ADDITIONAL CONSTRUCTION WORK FOR YOGA CENTRE AT ELLAIAMMAN KOIL STREET IN DIV-140,UNIT-30, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10087,Buildings,Completed,NK-KODAMBAKKAM,140,788000,"PROPOSED FALSE CEILING AND GRANITE FLOORING WORK FOR YOGA CENTRE AT ELLAIAMMAN KOIL STREET IN DIVISION-140, UNIT-30,ZONE-10",Own Sources,10,2015-16,2019-20 NK/2015-16/10181,Parks,Completed,NK-KODAMBAKKAM,136,920000,"ANNUAL MAINTENANCE TO NATESAN PARK AT VENKATNARAYANA ROAD IN DIV 136,U 30,Z 10(Employed qualified 2 years diploma horticulture only)",Own Sources,10,2015-16,2019-20 NK/2015-16/10274,Buildings,Completed,NK-KODAMBAKKAM,138,997000,"CONSTRUCTION OF COMPOSTING YARD (FOR DIVISION-137) AT PACHAYAPPEN FIRST STREET BURIAL GROUND IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10351,Parks,Completed,NK-KODAMBAKKAM,140,982000,"PROVIDING THE SEATING ARRANGEMENTS WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10355,Buildings,Completed,NK-KODAMBAKKAM,139,320000,"SUPPLY AND FIXING OF CRUSHER MACHINE AND FINISHING WORK FOR BIO-GAS PLANT IN SAIDAPET BURIAL GROUND AT DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10368,Buildings,Completed,NK-KODAMBAKKAM,142,989000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL GROUND FLOOR AT VACANT LAND IN V.V.KOIL STREET AT DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/10375,Buildings,Completed,NK-KODAMBAKKAM,142,980000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL FIRST FLOOR AT VACANT LAND IN V.V.KOIL STREET AT DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/10401,Buildings,Completed,NK-KODAMBAKKAM,142,970000,"PROPOSED CONSTRUCTION OF ELECTRICAL AND PLUMPING WORK FOR MULTIPURPOSE HALL AT VACANT LAND IN V.V.KOIL STREET AT DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/10402,Parks,Completed,NK-KODAMBAKKAM,140,988000,"PROVIDING THE SOUTH SIDE PARKING BAY WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10403,Parks,Completed,NK-KODAMBAKKAM,140,988000,"PROVIDING THE NORTH SIDE PARKING BAY WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10404,Parks,Completed,NK-KODAMBAKKAM,140,992000,"PROVIDING THE PLAY APPARATUS WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10405,Buildings,Completed,NK-KODAMBAKKAM,140,992000,"PROVIDING THE RACK WATER FALLS WORK IN PARK AT THE TDR LAND AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10445,Buildings,Completed,NK-KODAMBAKKAM,139,413000,"PROVIDING AND BARRICADING TRANSFORMER AT RAJAMBAL ST AND VARIOUS LOCATIONS IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10450,Buildings,Completed,NK-KODAMBAKKAM,142,996007,"IMPROVEMENTS TO THE SLUM LANE 1 AT THIDEER NAGAR BY PROVIDING TILES (UNDER WARD COUNCILOR FUND 2015-16) IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/10566,Buildings,Completed,NK-KODAMBAKKAM,138,715000,"IMPROVEMENT OF SWD AT PUGALENDHI STREET ,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10567,Buildings,Completed,NK-KODAMBAKKAM,138,985000,"ADDITIONAL CONSTRUCTION OF COMPOSTING YARD AT PACHAYAPPEN FIRST CROSS STREET ,BURIAL GROUND IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10664,Roads,Completed,NK-KODAMBAKKAM,136,442000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT GANTHI STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10667,Roads,Completed,NK-KODAMBAKKAM,142,980000,"LAYING CEMENT CONCRETE ROAD AT MOSQUE PALLAM 1ST STREET IN DIV-142,U-30,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/10712,Roads,Completed,NK-KODAMBAKKAM,136,708000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT JAWAHARRLAL NAHRU STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10714,Roads,Completed,NK-KODAMBAKKAM,136,307000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT KRISHANASAMY STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10715,Roads,Completed,NK-KODAMBAKKAM,136,642000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT VASAN ROAD IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10716,Roads,Completed,NK-KODAMBAKKAM,136,1058000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT THANJORE ROAD IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10717,Roads,Completed,NK-KODAMBAKKAM,136,1104000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT CAR TRACK ROAD IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10719,Roads,Completed,NK-KODAMBAKKAM,136,506000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT LAKSHMI NARASHIMMAN STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10720,Roads,Completed,NK-KODAMBAKKAM,136,1403000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT NATHAMUNI STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10721,Roads,Completed,NK-KODAMBAKKAM,136,827000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT NANA STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10722,Roads,Completed,NK-KODAMBAKKAM,136,920000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT SAMBASIVAM STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10723,Roads,Completed,NK-KODAMBAKKAM,136,764000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT SINGARAM STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10724,Roads,Completed,NK-KODAMBAKKAM,136,2163000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT RAJAMANNAR STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10725,Roads,Completed,NK-KODAMBAKKAM,136,861000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT KUPPUSAMY STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10726,Roads,Completed,NK-KODAMBAKKAM,136,920000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT KAMALABAI STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10728,Roads,Completed,NK-KODAMBAKKAM,136,1081000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT GOPALAKRISHNAN STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10729,Roads,Completed,NK-KODAMBAKKAM,136,630000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT MUTHU KRISHNAN STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10730,Roads,Completed,NK-KODAMBAKKAM,136,920000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT SRINIVASA ROAD IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10731,Roads,Completed,NK-KODAMBAKKAM,136,1834000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT VENKATRAMAN STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10732,Roads,Completed,NK-KODAMBAKKAM,136,2024000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT SIVAPRAKASAM STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10733,Roads,Completed,NK-KODAMBAKKAM,136,1519000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT MAHALAKSHMI STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/10837,Playfields,Completed,NK-KODAMBAKKAM,137,985000,IMPROMENTS TO PLAY GROUND PATHWAY AT 10TH SECTOR 61ST STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/10838,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,996007,"IMPROVEMENTS TO THE SLUM LANE 2 AT THIDEER NAGAR BY PROVIDING TILES (UNDER WARD COUNCILOR FUND 2015-16)IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/10841,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,391414,"IMPROVEMENTS TO THE SLUM LANE 3 AT THIDEER NAGAR BY PROVIDING TILES (UNDER WARD COUNCILOR FUND 2015-16)IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/10844,Playfields,Completed,NK-KODAMBAKKAM,137,995000,IMPROMENTS TO CHILDRANS PLAY GROUND AT 10TH SECTOR 61ST STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/10855,Buildings,Completed,NK-KODAMBAKKAM,142,990000,"PROVIDING SHED IN THE TERRACE OF COMMUNITY HALL AT SAAMIYAR THOTTAM IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2017-18 NK/2015-16/10857,Buildings,Completed,NK-KODAMBAKKAM,142,970000,"IMPROVEMENTS TO THE DINNING AREA OF COMMUNITY HALL AT SAAMIYAR THOTTAM IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2017-18 NK/2015-16/10890,Roads,Completed,NK-KODAMBAKKAM,141,888000,"RELAYING ROAD WITH CEMENT CONCRETE [M30 GRADE] AT C.I.T NAGAR 1ST MAIN ROAD LANE IN DIV-141, U-30,Z-10",Deposit Works,10,2015-16,2016-17 NK/2015-16/10891,Parks,Completed,NK-KODAMBAKKAM,141,982000,PROVIDING GREENERY ARRANGEMENTS AND IMPROVEMENT WORK IN CIT NAGAR 3RD MAIN ROAD PARK (UNDER WARD COUNCELLOR FUND) IN DIV 141 U 28 Z 10,Own Sources,10,2015-16,2017-18 NK/2015-16/11021,Roads,Completed,NK-KODAMBAKKAM,137,699000,LAYING CEMENT CONCRETE ROAD AT SIVALINGAM STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/11044,Roads,Completed,NK-KODAMBAKKAM,139,196000,"ENGAGING ADDITIONAL PRIVATE AUTO VEHICLE WITH 6 PRIVATE LABORS FOR 2 MONTHS TO DN-139, UNIT-28, ZONE-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/11045,Buildings,Completed,NK-KODAMBAKKAM,135,650000,"IMPROVEMENTS TO THE EXISTING NNMP SHED AT BRINDAVAN STREET (080308,080309), THAMBAIAH ROAD(080310,080311), ESWARAN KOIL STREET(080312) IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11244,Electrical,Completed,NK-KODAMBAKKAM,137,519000,"Supply,Installation,Testing & Commissioning fo 1no of 30KVA, 3phase Diseal Generator sets at Nesapakkam Burial Ground in Div 137,Zone -X area",Own Sources,10,2015-16,2016-17 NK/2015-16/11332,Buildings,Completed,NK-KODAMBAKKAM,134,790000,"ENGAGING TECHNICAL ASSISTANT TO DN-132,133,134 & 135 IN U-31,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/11333,Buildings,Completed,NK-KODAMBAKKAM,134,955000,"IMPROVEMENTS TO THE EXISTING NNMP SHED (ANGANWADI) AT RANGARAJAPURAM 3RD STREET(33603080119,33603080120,33603080121) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11433,Roads,Completed,NK-KODAMBAKKAM,139,436000,"PROPOSED REPLAYING OF ROAD USING CEMENT CONCRETE AT SEETHA ST IN D-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11437,Roads,Completed,NK-KODAMBAKKAM,139,847000,"PROPOSED RELAYING OF ROAD USING OF CEMENT CONCRETE AT ARUMUGAM ST (BHARATHI BLOCK) IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11516,Roads,Completed,NK-KODAMBAKKAM,140,416000,"PROVIDING RAIN WATER HARVESTING STRUCTURE [ WELL RING TYPE WITH RCC COVER SLAB ] AT GOVINDAN ROAD AND VARIOUS STREETS IN DIV-140, U-30, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11551,Buildings,Completed,NK-KODAMBAKKAM,142,430000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS PLACES IN Division-142, Unit - 30, Zone -10",Own Sources,10,2015-16,2016-17 NK/2015-16/11578,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,360000,"CONSTRUCTION OF RAIN WATER HARVESTING STRUCTUR USING PRECAST WELL RING AT ASHOKPILLER ROAD AND VARIOUS STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11650,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,416000,"PROVIDING RAIN WATER HARVESTING STRUCTURE [ WELL RING TYPE WITH RCC COVER SLAB ] AT NORTH USMAN ROAD AND VARIOUS STREETS IN DIVISION -136, UNIT -30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11674,Roads,Completed,NK-KODAMBAKKAM,141,416000,"PROVIDING RAIN WATER HARVESTING STRUCTURE [ WELL RING TYPE WITH RCC COVER SLAB ] AT BURKIT ROAD AND VARIOUS STREETS IN DIV-141, U-30, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11702,Parks,Completed,NK-KODAMBAKKAM,136,297000,"TREE PLANTING IN VARIOUS STREETS IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/11887,Roads,Completed,NK-KODAMBAKKAM,141,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DIVISION-141, UNIT-30 AND ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/11963,Roads,Completed,NK-KODAMBAKKAM,132,948000,"Out sourcing private workers for house keeping work for 1 year at 2 Government schools in Div 132 ,Unit-31,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/11969,Footpath,Completed,NK-KODAMBAKKAM,132,2250000,"FORMING PATHWAY AT 12TH AVENUE PLAY GROUND IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11976,Buildings,Completed,NK-KODAMBAKKAM,138,485000,"LAYING OF CEMENT CONCRETE ROAD AT PILLAYARKOIL STREET JAFFERKHANPET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11977,Buildings,Completed,NK-KODAMBAKKAM,138,625000,"LAYING CEMENT CONCRETE ROAD AT AYYAVOO 5YH STREET JAFFERKHANPET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11980,Buildings,Completed,NK-KODAMBAKKAM,138,790000,"IMPROVEMENT WORK OF PLAY GROUND AT PARI NAGAR KANNAKI STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11982,Footpath,Completed,NK-KODAMBAKKAM,132,2300000,"FORMING FOOTPATH AND PROVIDING STAINLESS STEEL HANDRAILS AT 12TH AVENUE PLAYGROUND IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/11983,Buildings,Completed,NK-KODAMBAKKAM,138,981000,"IMPROVEMENT WORK OF CPS AT GOVINDASAMY STREET MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11985,Buildings,Completed,NK-KODAMBAKKAM,138,979000,"IMPROVEMENT WORK OF CHSS AT GOVINDASAMY STREET MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/11990,Footpath,Completed,NK-KODAMBAKKAM,132,2300000,"PROVIDING BORE WELL ARRANGEMENTS AND PLAY APPARATUS AT 12TH AVENUE PLAYGROUND IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/11991,Footpath,Completed,NK-KODAMBAKKAM,134,988000,"IMPROVEMENTS TO THE FOOTPATH AT U.I.COLONY 2ND CROSS STREET, 3RD CROSS STREET & PARK VIEW ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11992,Footpath,Completed,NK-KODAMBAKKAM,134,990000,"PROVIDING FOOTPATH AND IMPROVEMENTS TO THE STORM WATER DRAIN AT U.I.COLONY 2ND MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11993,Footpath,Completed,NK-KODAMBAKKAM,134,336000,"IMPROVEMENTS TO THE FOOTPATH AT N S K SALAI IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/11994,Road Cut,Completed,NK-KODAMBAKKAM,134,815000,"RESTORATION ROAD CUT MADE BY TNEB AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Deposit Works,10,2015-16,2016-17 NK/2015-16/11995,Road Cut,Completed,NK-KODAMBAKKAM,134,838000,"RESTORATION ROAD CUT MADE BY TNEB AT DR.GOPALAMENON ROAD,U.I.COLONY 2ND MAIN ROAD, U.I.COLONY 2ND CROSS STREET AND KAMARAJAR COLONY 1ST STREET IN DN-134,U-31,Z-10",Deposit Works,10,2015-16,2016-17 NK/2015-16/11996,Buildings,Completed,NK-KODAMBAKKAM,134,517000,"IMPROVEMENTS TO THE EXISTING NNMP SHED AT CRP GARDEN (No:33603080128,33603080129,33603080130)AND KAMARAJAR COLONY 3RD STREET (NO:33603080122,33603080123,33603080124) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12060,Parks,Completed,NK-KODAMBAKKAM,141,296999,"TREE PLANTING IN VARIOUS STREETS IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/12095,Buildings,Completed,NK-KODAMBAKKAM,141,989000,"PROPOSED CONSTRUCTION OF CREECH BUILDING AT KAMARAJAR COLONY IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/12117,Buildings,Completed,NK-KODAMBAKKAM,138,425000,"LAYING OF CEMENT CONCRETE ROAD AT GOVINDASAMY STREET JAFFERKHANPET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/12166,Buildings,Completed,NK-KODAMBAKKAM,133,319000,IMPROVEMENTS TO ROAD SIDE PARK AT JN OF 11 TH AVENUE AND GOVINDAN ROAD AND ROAD PATCH WORK AT ASHOK NAGAR 52ND STREET IN DN 133 UNIT 31 ZONE 10 I,Own Sources,10,2015-16,2016-17 NK/2015-16/12217,Buildings,Completed,NK-KODAMBAKKAM,139,750000,IMPROVEMENT WORK ON GYM AT R R COLONY PLAY GROUND IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2017-18 NK/2015-16/12259,Roads,Completed,NK-KODAMBAKKAM,139,799000,"PROPOSED LEVELLING OF R.R.COLONY PLAY GROUND IN R.R.COLONY 2ND LINK ST IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12367,Roads,Completed,NK-KODAMBAKKAM,142,517000,"TREE PLANTING IN VARIOUS STREETS IN DIV-142, U-30, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12415,Footpath,Completed,NK-KODAMBAKKAM,134,995000,"PROVIDING FOOTPATH AT NTR STREET AND THIRUVALLUVAR STREET (SOTHERN SIDE) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12418,Footpath,Completed,NK-KODAMBAKKAM,134,664000,"REPAIRS TO THE EXISTING FOOTPATH AT U.I.COLONY OUTER CIRCULAR ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12432,Footpath,Completed,NK-KODAMBAKKAM,134,718000,"REPAIRS TO THE EXISTING FOOTPATH AT PASUMARTHY STREET AND U.I.COLONY 3RD MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12434,Roads,Completed,NK-KODAMBAKKAM,137,988000,"ATTENDING THE PATCH WORK AT 4th SECTOR, 14 th STREET, 20 th STREET AND VARIOUS STREET IN DIVISION- 137, UNIT-28, ZON-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/12435,Roads,Completed,NK-KODAMBAKKAM,137,987000,"ATTENDING THE PATCH WORK AT 7th SECTOR 33 rd STREET, 64 th STREET AND VARIOUS STREET IN DIVISION- 137, UNIT-28, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/12525,Buildings,Completed,NK-KODAMBAKKAM,140,675000,"IMPROVEMENTS TO THE NNMP SHED AT VAZAITHOPPU,SCHOOL ROAD AND ADHI KESAVA PERUMAL KOVIL ST IN DN-140,UT-30,ZONE-10",Own Sources,10,2015-16,2019-20 NK/2015-16/12631,Buildings,Completed,NK-KODAMBAKKAM,141,660000,"IMPROVEMENTS WORK TO ICDS AT C.I.T NAGAR 4TH MAIN ROAD , C.I.T NAGAR 5TH MAIN ROAD AND VARIOUS STREETS IN DIVISION - 141 , UNIT - 30, ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/12889,Footpath,Completed,NK-KODAMBAKKAM,139,997000,"IMPROVEMENT WORKS ON FOOTPATH AT R.R.COLONY 3RD ST IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/12898,Buildings,Completed,NK-KODAMBAKKAM,139,874000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR AMMA UNAVAGAM AND COMPOSTING YARD AT NORTH PORTION OF SAIDAPET BURIAL GROUND IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12903,Roads,Completed,NK-KODAMBAKKAM,139,697000,"PROPOSED LAYING OF ROAD USING CEMENT CONCRETE FOR COMPOSTING YARD AND BIO-GAS PLANT PATHWAY AT SAIDAPET BURIAL GROUND IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/12926,Buildings,Completed,NK-KODAMBAKKAM,128,999000,"Proposed Construction of Bio-Gas plant for Amma Unavagam (Civil work) at Kamarajar Salai, Virugambakkam, Chennai in Dn - 128, Unit - 29, Zone - 10.",Own Sources,10,2015-16,2018-19 NK/2015-16/13255,Buildings,Completed,NK-KODAMBAKKAM,141,747000,"ADDITIONAL CONSTRUCTION OF COMPOSITE YARD AT NEW BOAG ROAD ( KANNAMAA PET BURIAL GROUND) IN DIVISIOON - 141, UNIT -30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/13350,Buildings,Completed,NK-KODAMBAKKAM,139,447000,"PROVIDING AND FIXING CRUSHER MACHINE AND ELECTRICAL,PLUMBING WORK IN BURIYAL GROUND AT WEST JONES ROAD IN DIV 139 U 28 Z 10",Own Sources,10,2015-16,2016-17 NK/2015-16/13527,Parks,Completed,NK-KODAMBAKKAM,131,986000,"Annual Maintenance of Sivan Park at P.T.Rajan Salai in Dn 131, U 28,Zone-X. (Employed qualified Diploma Horticulturist only)",Own Sources,10,2015-16,2016-17 NK/2015-16/13531,Parks,Completed,NK-KODAMBAKKAM,140,300000,"TREE PLANTING AT VARIOUS STREETS IN DIVISION-140, UNIT-30, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/13569,Roads,Completed,NK-KODAMBAKKAM,139,983000,"ENGAGING ADDITIONAL PRIVATE AUTO VEHICLE WITH 6 PRIVATE LABORS FOR 10 MONTHS TO DN-139, UNIT-28, ZONE-X.",Own Sources,10,2015-16,2018-19 NK/2015-16/13576,Buildings,Completed,NK-KODAMBAKKAM,140,394000,"PROPOSED CONSTRUCTION WORK FOR UNDER GROUND SUMP IN AMMA UNAVAGAM AT KODAMBAKKAM SALAI IN DIVISION-140, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/13577,Roads,Completed,NK-KODAMBAKKAM,140,2142000,"PROVIDING RAIN WATER HARVESTING AT ADHIKESAVA PERUMAL KOIL STREET AND VARIOUS STREETS IN DIV-140, U-30, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/13579,Buildings,Completed,NK-KODAMBAKKAM,140,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO WITH PRIVATE LABOURS 6 NOS FOR DIVISION WORK IN DIV-140, U-30, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/13580,Buildings,Completed,NK-KODAMBAKKAM,140,860000,"PROVIDING PERGOLA AND STAINLESS STEEL HANDRAILS WORK FOR PARK AT ELLAIAMMAN KOIL STREET IN DIV-140, U-30, Z- 10.",Own Sources,10,2015-16,2016-17 NK/2015-16/13625,Buildings,Completed,NK-KODAMBAKKAM,128,2195000,"Providing Rain Water Harvesting Structure using precast well ring size 1200 (outer dia) x 4500mm (Height) (300mm x 15 nos) x40mm (thk) using 1:1.5:3 concrete necessary earthwork excavation, filling with 20mm HBG metal out side peripheral of the well, providing of RCC frame of size 1300 dia. 150mm ht and 100mm width covered with RCC cover slab 1300mm dia & 100mm thk, connected to the silt catch pit 450mm x 450mm x 450mm using 160mm dia PVC pipe, including cost Conveyance, cleaning the site and finishing etc., complete at Various Locations in Dn - 128, Unit - 29, Zone - 10.",Own Sources,10,2015-16,2017-18 NK/2015-16/13636,Electrical,Completed,NK-KODAMBAKKAM,137,460500,"Supply and Erection of 6nos of 6mtr GI lamp post and 8nos of 3mtr GI Lamp post in the Nesapakkam Burial Ground ( Earikarai street ) in Div 137,Zone -X area",Own Sources,10,2015-16,2016-17 NK/2015-16/1371,Electrical,Completed,NK-KODAMBAKKAM,134,750000,"Electrification of Operation theater fitting at EOC Vadapalani,Saidapet in Division 134,142 Under Zone-X",Own Sources,10,2015-16,2018-19 NK/2015-16/13765,Electrical,Completed,NK-KODAMBAKKAM,140,996400,"SUPPLY AND ERECTION OF 15 NOS OF 6 MTR GI PIPE POST AND 24 NOS OF 2 MTR GI LAMP POST WITH LED FITTING IN THE KODAMBAKKAM ROAD PARK AT DIV-140, ZONE-X AREA",Own Sources,10,2015-16,2016-17 NK/2015-16/13767,Electrical,Completed,NK-KODAMBAKKAM,140,987700,"SUPPLY AND ERECTION OF 15 NOS OF 6 MTR GI LAMP POST AND WITH LED FITTING IN THE KODAMBAKKAM ROAD PLAY GROUND AT DIV-140, ZONE-X AREA",Own Sources,10,2015-16,2016-17 NK/2015-16/13775,Electrical,Completed,NK-KODAMBAKKAM,132,995800,"Supply and Erection of 17nos of 6mtr GI lamp post and 21 nos of 2mtr GI lamp post with LED fitting in the 1st Avenue Park at Div 132,Zone -X area",Own Sources,10,2015-16,2017-18 NK/2015-16/13968,Road Cut,Completed,NK-KODAMBAKKAM,137,324000,DEPOSIT WORK RESTORATION OF ROAD CUT MADE CMWSS BOARD AT RAJAMANNAR SALAI AND MUNUSAMY SALAI IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/14144,Buildings,Completed,NK-KODAMBAKKAM,139,839000,"CONSTRUCTION OF CRUSHER MACHINE SHED AT BURIYAL GROUND AT WEST JONES ROAD IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/14195,Buildings,Completed,NK-KODAMBAKKAM,138,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO.WITH PRIVATE LABOURS 6 NO.FOR DIVISION WORK IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/14420,Buildings,Completed,NK-KODAMBAKKAM,137,2102000,PROVIDING RAIN WATER HARVESTING STRUCTURE (WELL RING TYPE WITH RCC COVER SLAB)AT VARIOUS PLACE (FOR 60NOS)IN DN.137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/14457,Buildings,Completed,NK-KODAMBAKKAM,138,2150000,"CONSTRUCTION OF RAIN WATER HARVESTING STRUCTUR USING PRECAST WELL RING AT ASHOK PILLER ROAD AND VARIOUS STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/14502,Roads,Completed,NK-KODAMBAKKAM,141,2142000,"PROVIDING RAIN WATER HARVESTING AT C.I.T NAGAR 1ST CROSS STREET AND VARIOUS STREETS IN DIV-141, U-30, Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/14513,Roads,Completed,NK-KODAMBAKKAM,136,2142000,"PROVIDING RAIN WATER HARVESTING AT YOGAMBAL STREET AND VARIOUS STREETS IN DIV-136, U-30, Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/14522,Roads,Completed,NK-KODAMBAKKAM,142,2142000,"Providing rain water harvesting at kavarai street various places in Division -142,Unit -30,Zone -10",Own Sources,10,2015-16,2017-18 NK/2015-16/14534,Roads,Completed,NK-KODAMBAKKAM,131,2150000,"CONSTRUCTION OF RAIN WATER HARVESTING STRUCTUR USING PRECAST WELL RING AT 1st,2nd,5th,6th SECTOR AND VARIOUS STREET IN DIV-131,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/14610,Electrical,Completed,NK-KODAMBAKKAM,134,686000,"Electrification and erection of lamp Post of K.K.Park in Corporation Colony Div 134,Zone X",Own Sources,10,2015-16,2016-17 NK/2015-16/14821,Parks,Completed,NK-KODAMBAKKAM,131,890000,"STAINLESS STEEL MULTI PLAY SYSTEM-V (12 STATION) AT SIVAN PARK IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15060,Buildings,Completed,NK-KODAMBAKKAM,128,978000,"Supplying and Fixing of Fitting for Bio-Gas plant for Amma Unavagam at Kamarajar Salai, Virugambakkam, Chennai in Dn - 128, Unit - 29, Zone - 10.",Own Sources,10,2015-16,2018-19 NK/2015-16/1512,Buildings,Completed,NK-KODAMBAKKAM,141,985000,"IMPROVEMENT TO SCHOOL BUILDING AT KANNAMMAPET IN DIVISION - 141, UNIT - 30, ZONE - 10",Own Sources,10,2015-16,2016-17 NK/2015-16/15136,Roads,Completed,NK-KODAMBAKKAM,131,877000,"LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM 3rd STREET (PART) IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15203,Roads,Completed,NK-KODAMBAKKAM,128,697000,"Erection, Labour and Transportation Charges for Bio-Gas plant for Amma Unavagam at Kamarajar Salai, Virugambakkam, Chennai in Dn - 128, Unit - 29, Zone - 10.",Own Sources,10,2015-16,2018-19 NK/2015-16/15214,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,320000,"SWD RENOVATION AT R.K SHANMUGAM SALAI IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15478,Roads,Completed,NK-KODAMBAKKAM,139,638000,"PROPOSED RELAYING OF ROAD USING CEMENT CONCRETE AT SCHOOL 1ST,6TH AND 8TH ST IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/15480,Roads,Completed,NK-KODAMBAKKAM,139,525000,"ATTENDING THE PATCH WORK USING BY CEMENT CONCRETE AT SAKUNDALA ST AND VARIOUS STREETS IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15547,Electrical,Completed,NK-KODAMBAKKAM,131,532300,"Provision of 8 Nos of 6 mtr lamp post with 16 nos of 90w- 120w LED fitting in the Road side Park at Rani Anna nagar blocks in between 13,14 & 16,17 and blocks in between 19,20 & 21,22 at Division 131 Div. Zone X .",Own Sources,10,2015-16,2016-17 NK/2015-16/15553,Electrical,Completed,NK-KODAMBAKKAM,131,523000,"Provision of 20 Nos of 3mtr lamp post with 2 x18w CFL and 2 nos of 6 mtr Lamp post with led fittings and others in the Road side Park at Rani Anna nagar Division 131,Zone X",Own Sources,10,2015-16,2016-17 NK/2015-16/15680,Buildings,Completed,NK-KODAMBAKKAM,141,990000,PROVIDING SHED AND FLOORING WORK ON 16TH DAY CEREMONY HALL(UNDER WARD COUNCILLOR FUND) AT KAMARAJ COLONY IN DIV 141 U 30 Z 10,Own Sources,10,2015-16,2017-18 NK/2015-16/15681,Buildings,Completed,NK-KODAMBAKKAM,141,963000,"IMPROVEMENT WORK ON 16TH DAY CEREMONY HALL IN KAMARAJ COLONEY AND MULTIPURPOSE HALL IN CIT NAGR 4TH MAIN ROAD(UNDER WARD COUNCILLOR FUND) DIV-141,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15716,Buildings,Completed,NK-KODAMBAKKAM,136,944000,"Construction of Compound wall with Granite slab at Jeeva park from south west Jn of G.N.Chetty Road and Rajamannar Street to towards at Rajamannar Street and Toilet Block inside of park at G.N.Chetty Road in Dn 136,Unit-30,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15847,Roads,Completed,NK-KODAMBAKKAM,131,300000,"ATTENDING PATCH WORK 2nd SECTOR 8th STREET AND VARIOUS STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15928,Playfields,Completed,NK-KODAMBAKKAM,138,840000,IMPROVEMENTS OF PLAYGROUND AT BHARATHIDASAN COLONY 4TH STREET IN DN 138 UNIT 28 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/15931,Parks,Completed,NK-KODAMBAKKAM,138,800000,IMPROVEMENTS OF PARK AT BHARATHIDASANCOLONY 5TH STREET IN DN 138 UNIT 28 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/15932,Playfields,Completed,NK-KODAMBAKKAM,138,910000,IMPROVEMENTS OF PLAYGROUND AT BHARATHIDASANCOLONY MAIN ROAD(NEHRU AVENUE ) IN DN 138 UNIT 28 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/15944,Footpath,Completed,NK-KODAMBAKKAM,142,917000,"PROVIDING HAND RAIL AND PLATFORM IN THE TANK SQUARE EAST STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/15965,Buildings,Completed,NK-KODAMBAKKAM,139,972000,"IMPROVEMENT AND REPAIR WORK ON ANGANWADI AT R.V.NAGAR MN BLOCK AND VARIOUS STREETS IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/15983,Parks,Completed,NK-KODAMBAKKAM,138,340000,"PROVINDING GREENARY AND IMPROVEMENTS WORK AT BHARATHIDASAN COLONY 5TH STREET PARK IN DIVISION -138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/16004,Footpath,Completed,NK-KODAMBAKKAM,142,917000,"PROVIDING HAND RAIL AND PLATFORM IN THE TANK SQUARE WEST STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/16012,Footpath,Completed,NK-KODAMBAKKAM,142,917000,"PROVIDING HAND RAIL AND PLATFORM IN THE TANK SQUARE STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/16013,Footpath,Completed,NK-KODAMBAKKAM,142,917000,"PROVIDING HAND RAIL AND PLATFORM IN THE JONES ROAD SIDE IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/16019,Electrical,Completed,NK-KODAMBAKKAM,137,870200,"Supply and Erection of 11nos of 6mtr GI lamp post and 32nos of 2mtr GI Lamp post in the 12th sector park in Div 137,Zone -X area",Own Sources,10,2015-16,2016-17 NK/2015-16/16024,Roads,Completed,NK-KODAMBAKKAM,139,421000,"PAVING THE PAVER BLOCK AT VSM GARDEN LANE ST AND VARIOUS STREETS IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/16170,Buildings,Completed,NK-KODAMBAKKAM,133,980000,IMPROVEMENTS TO CPS (PULIYUR SCHOOL) AT N.S.K.SALAI IN DN 133 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/16180,Roads,Completed,NK-KODAMBAKKAM,139,890000,"PROPOSED LAYING OF CEMENT CONCRETE ROAD AT WIDENING PORTION OF ERIKKARAI ST IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/16427,Parks,Completed,NK-KODAMBAKKAM,131,733000,PROVIDING CHAIRS AND FLOORING WORK ON RANI ANNA NAGAR PARK IN DIVISION 131 U28 Z10,Own Sources,10,2015-16,2016-17 NK/2015-16/16626,Buildings,Completed,NK-KODAMBAKKAM,139,927000,PROVIDING GRANITE FLOORING AND GREENERY WORK ON PARK AT ELLAI AMMAN KOVIL STREET IN DIV 140 U 30 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/16680,Roads,Completed,NK-KODAMBAKKAM,138,981000,"LAYING SPEED BREAKERS AT KANCHI NATARAJAN SALAI AND VARIOUS STREETS IN DN-138,UN-28,ZO-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/16720,Roads,Completed,NK-KODAMBAKKAM,142,875000,"LAYING CEMENT CONCRETE ROAD AT V.S MUDHALI STREET(REACH-1) IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/16760,Roads,Completed,NK-KODAMBAKKAM,142,875000,"LAYING CEMENT CONCRETE ROAD AT SUBRAMANIYA SAMY KOIL STREET(REACH-2) IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/16786,Roads,Completed,NK-KODAMBAKKAM,138,980000,"LAYING SPEED BREAKERS AT BHARATHIDASAN COLONY MAIN ROAD AND VARIOUS STREETS IN DN-138,UN-28,ZO-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/16862,Roads,Completed,NK-KODAMBAKKAM,137,486000,LAYING CEMENT CONCRETE ROAD AT RAJIVGANDHI 1 ST CROSS ST.AND 2ND CROSS STIN IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/16865,Roads,Completed,NK-KODAMBAKKAM,137,512000,PATCH WORK AT VARIOUS STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/16866,Roads,Completed,NK-KODAMBAKKAM,137,932000,PROVIDING SPEED BREAKER AT VARIOUS STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2017-18 NK/2015-16/16960,Buildings,Completed,NK-KODAMBAKKAM,137,2022000,MAINTANANCE WORK OF GASIFIER AND CREMATORIUM AT ERIKARAI STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2017-18 NK/2015-16/17015,Playfields,Completed,NK-KODAMBAKKAM,131,987000,"PROVIDING AND LAYING SPEED BREAKERS AT 2nd SECTOR 9th STREET, JEEVANANTHAM SALAI AND VARIOUS STREETS IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17048,Buildings,Completed,NK-KODAMBAKKAM,141,621000,"REMOVAL OF DEBRIS IN VARIOUS ROADS AND STREETS AND DUMPING THE SAME IN PDG FROM DIVISION-136 & 141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/17068,ROB,Completed,NK-KODAMBAKKAM,140,930000,"SUPPLY AND FIXING PLAY SYSTEMS IN PARK AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT,30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/17104,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,560000,"DESILITING OF MGR CANAL USING JCB WITH LABOUR FROM ADYAR RIVER TO ANNA MAIN ROAD IN DIVISION -138,UNIT-28,ZONE-1O.",Own Sources,10,2015-16,2016-17 NK/2015-16/17156,Buildings,Completed,NK-KODAMBAKKAM,142,875000,"LAYING CEMENT CONCRETE ROAD AT SUBRAMANIYA SAMY KOIL STREET(REACH-1) IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/17311,Roads,Completed,NK-KODAMBAKKAM,139,621000,"LAYING AND SPREADING OF WET MIX AT DEVANAIDU ST IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17422,Parks,Completed,NK-KODAMBAKKAM,140,993000,"SUPPLY AND FIXING GATE AND NAME BOARD IN PARK AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT,30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/17423,Parks,Completed,NK-KODAMBAKKAM,140,944000,"PROVIDING STAINLESS STEEL HANDRAIL IN PARK NORTH SIDE WEST SIDE AND GYM OUTER SIDE AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17577,Buildings,Completed,NK-KODAMBAKKAM,137,850000,PROVIDING PLAT FORM FOR GROUP BIN AND PATCH WORK AT ANNA MAIN ROAD AND NSC BOSE ROADDN 128 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/17627,Roads,Completed,NK-KODAMBAKKAM,137,758000,"Providing House Keeper arrangements at government schools (for one year) in Dn-128, U-29, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/17678,Buildings,Completed,NK-KODAMBAKKAM,140,247000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE PUBLIC CONVEYANCE AT ATHI KESAVA PERUMAL KOVIL ST IN DN-140,UT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/17905,Roads,Completed,NK-KODAMBAKKAM,131,437000,"IMPROVEMENTS TO GROUP BIN AT VARIOUS STREETS IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/17918,Roads,Completed,NK-KODAMBAKKAM,131,441000,"PROPOSED CONSTRUCTION OF TOILET BLOCK IN ANGANWADI CENTER NO:364,364A,(OLD NO:360) AT VIJAYARAGAVAPURAM 6th CROSS STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/17952,Roads,Completed,NK-KODAMBAKKAM,139,207000,"LAYING AND SPREADING OF WET MIX IN VADIVEL LANE ST AT DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17977,Roads,Completed,NK-KODAMBAKKAM,132,800000,"LAYING OF CEMENT CONCRETE ROAD AT SOMA SUNDARA BHARATHI NAGAR 5TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17978,Roads,Completed,NK-KODAMBAKKAM,132,890000,"LAYING OF CEMENT CONCRETE ROAD AT SOMA SUNDARA BHARATHI NAGAR 4TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17979,Roads,Completed,NK-KODAMBAKKAM,132,820000,"LAYING OF CEMENT CONCRETE ROAD AT SOMA SUNDARA BHARATHI NAGAR 3RD STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17980,Roads,Completed,NK-KODAMBAKKAM,132,850000,"LAYING OF CEMENT CONCRETE ROAD AT SOMA SUNDARA BHARATHI NAGAR 2ND STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/17981,Roads,Completed,NK-KODAMBAKKAM,132,485000,"LAYING OF CEMENT CONCRETE ROAD AT SOMA SUNDARA BHARATHI NAGAR 1ST STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18085,Roads,Completed,NK-KODAMBAKKAM,142,701000,"PROVIDING INTERLOCKING PAVER BLOCKS AT KUYAVAR STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/18086,Roads,Completed,NK-KODAMBAKKAM,142,701000,"PROVIDING INTERLOCKING PAVER BLOCKS AT MOSQUE LANE.MOSQUE PALLAM 1 STREET,MOSQUE PALLAM 2 STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/18087,Footpath,Completed,NK-KODAMBAKKAM,142,984000,"PROVIDING PLATFORM IN THE ABDHUL RAZACK STREET EAST SIDE IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/18094,Footpath,Completed,NK-KODAMBAKKAM,142,984000,"PROVIDING PLATFORM IN THE ABDHUL RAZACK STREET WEST SIDE IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/18095,Footpath,Completed,NK-KODAMBAKKAM,142,701000,"PROVIDING INTERLOCKING PAVER BLOCKS AT KAMBAR STREET,NADARAJAN STREET,SAIDAI SAMBANTHAM STREET(SUBRAMANIYA SALAI) IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/18096,Footpath,Completed,NK-KODAMBAKKAM,142,701000,"PROVIDING INTERLOCKING PAVER BLOCKS AT BALAKRUSHNAN STREET,RAMASAMY STREET,MUNUSAMY STREET,KUMARASAMY STREET,ADHIKESAVAN STREET,KAMAKODI STREET,(SUBRAMANIYA SALAI) IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/18331,Parks,Completed,NK-KODAMBAKKAM,131,991000,"PROVIDING STAINLESS STEEL HAND RAIL GREENERY AREA AT 2nd SECTOR PLAY GROUND IN DN-131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18332,Playfields,Completed,NK-KODAMBAKKAM,131,998000,"SUPPLYING AND FIXING PLAY APPARATUS AT 2nd SECTOR PLAY GROUND IN DN-131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18333,Buildings,Completed,NK-KODAMBAKKAM,131,989000,"IMPROVEMENTS TO INDOOR STADIUM AND PATHWAY OTHER REPAIRS AT 2nd SECTOR PLAY GROUND IN DN-131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18334,Parks,Completed,NK-KODAMBAKKAM,131,988000,"PROVIDING STAINLESS STEEL HAND RAIL GREENERY AREA AT SIVAN PARK ON NORTHERN RING PARK IN DN-131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2019-20 NK/2015-16/18336,Parks,Completed,NK-KODAMBAKKAM,137,997000,"REPAIRS TO PATHWAY (OUTER) AT 12th SECTOR PARK IN DN-137, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18337,Parks,Completed,NK-KODAMBAKKAM,137,998000,"IMPROVEMENTS TO PATHWAY (CENTER) AT 12th SECTOR PARK IN DN-137, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18338,Parks,Completed,NK-KODAMBAKKAM,137,840000,"STAINLESS STEEL MULTI PLAY SYSTEM-V (12 STATION) AT 11th SECTOR PLAY GROUND IN DN-137, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18352,Footpath,Completed,NK-KODAMBAKKAM,135,590000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT JANAIKIRAMAN STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18359,Footpath,Completed,NK-KODAMBAKKAM,135,410000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT RAJAGOPLAN STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18364,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,965000,"DISMANTLING AND RECONSTRUCTION OF SWD AT THAMBAIAH ROAD ( FROM JUBLIE ROAD TO BRINDAVAN STREET) UNDER WARD COUNCILLOR SCHEME (2015-16) IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18365,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,965000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT STATION ROAD (FROM KRISHNAMOORTHY STREET TO LAKE VIEW ROAD) UNDER WARD COUNCILOR SCHEME(2015-16) IN DIV 135,UNIT-31,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/18367,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,982000,"MANHOLE DOOR RAISING AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/18369,Buildings,Completed,NK-KODAMBAKKAM,134,500000,"PROVIDING FENCING AND CONSTRUCTION OF OPERATOR ROOM FOR RANGARAJAPURAM TWO WHEELER SUBWAY IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/18435,Footpath,Completed,NK-KODAMBAKKAM,139,990000,PROVIDING AND LAYING OF GRANITE FOOTPATH AT WIDENING PORTION OF GANGAI AMMAN KOIL STREET IN DIV-139 U-28 Z10,Own Sources,10,2015-16,2017-18 NK/2015-16/18999,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,999000,"Dismantling Existing Storm Water Drain and Newly Construct at Karumariyamman Koil Street( CH 200.00M-256.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/19042,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,681000,"Dismantling Existing Storm Water Drain and Newly Construct at Kumaran Colony 7th Street (CH 80.00M-115.00M) Div-130,Unit-29.Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/19139,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,680000,"Dismantling Existing Storm Water Drain and Newely Construct at KUMARAN COLONY 8TH STREET (CH 40.00M-75.00M) Div-130,Unit-29.Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/19143,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,989000,"Dismantling Existing Storm Water Drain and Newely Construct at Karumariyamman Koil Street( CH 150.00M-200M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/19161,Buildings,Completed,NK-KODAMBAKKAM,129,692000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING IN DIV 129,UNIT-29,ZONE-10",Own Sources,10,2015-16,2019-20 NK/2015-16/19162,Buildings,Completed,NK-KODAMBAKKAM,130,692000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING IN DIV 130,UNIT-29,ZONE-10",Own Sources,10,2015-16,2019-20 NK/2015-16/19163,Buildings,Completed,NK-KODAMBAKKAM,130,340000,"PROVIDING SECURITY ARRANGEMENTS (DAY AND NIGHT) FOR C.M.S. AMMAN KOIL STREET (EAST) FOR ONE YEAR IN DIV 130,UNIT-29, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/19164,Buildings,Completed,NK-KODAMBAKKAM,135,340000,"PROVIDING SECURITY ARRANGEMENTS (DAY AND NIGHT ) TO C.P.S. AT ESWARAN KOIL STREET IN DIV 135, UNIT-31,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/19176,Buildings,Completed,NK-KODAMBAKKAM,132,340000,"PROVIDING SECURITY ARRANGEMENTS (DAY AND NIGHT) FOR C.P.S KANNIAPPA NAGAR SCHOOL IN DIV 132,UNIT-31,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/19177,Buildings,Completed,NK-KODAMBAKKAM,127,680000,"PROVIDING SECURITY ARRANGEMENTS (DAY AND NIGHT) FOR C.P.S SCHOOL ROAD KOYAMBEDU, CHSS SCHOOL ROAD -KOYAMBEDU AND C.M.S.SCHOOL ROAD - T.S.D NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/19179,Buildings,Completed,NK-KODAMBAKKAM,127,948000,"OUT SOURCING OF PRIVATE WORKERS IN SCHOOLS AT SCHOOL ROAD CHS KOYAMBEDU, SCHOOL ROAD CPS KOYAMBEDU AND SCHOOL ROAD CMS TDS NAGAR IN DIV 127,UNIT-29,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/19185,Buildings,Completed,NK-KODAMBAKKAM,127,692000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING IN DIV-127,UNIT -29, ZONE-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/19186,Buildings,Completed,NK-KODAMBAKKAM,128,948000,"OUT SOURCING OF PRIVATE WORKERS IN SCHOOLS AT CHS VIRUGAMBAKKAM,CPS VIRUGAMBAKKAM,CPS PILLAYAR KOIL STREET NESAPAKKAM ANS CPS PILLAYARKOIL STREET NEW BUILDING IN DIV 128,UNIT-29, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/19187,Buildings,Completed,NK-KODAMBAKKAM,128,900000,"PROVIDING SECURITY ARRANGEMENTS (DAY AND NIGHT) FOR C.P.S.PILLAIYAR KOIL STREET NESAPAKKAM(1) BLOCK NEW BUILDING NESAPAKKAM(2) BLOCKS , CPS SCHOOL STREET VIRUGAMBAKKAM AND CHSS SCHOOL STREET VIRUGAMBAKKAM (FOR ONE YEAR) IN DIV 128, UNIT-29,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/19223,Buildings,Completed,NK-KODAMBAKKAM,140,236000,"OUT SOURCING PRIVATE LABOUR FOR CONSERVANCY WORK NAMMA TOILET AT ELLAI AMMAN KOIL STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/1923,Roads,Completed,NK-KODAMBAKKAM,139,589000,"RELAYING OF ROAD USING BY CEMENT CONCRETE AT R.V.NAGAR 75TH STREET(REACH-1) IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/1934,Roads,Completed,NK-KODAMBAKKAM,139,712000,"PROPOSED RELAYING OF ROAD USING CEMENT CONCRETE AT R.V.NAGAR AA-X BLOCK ROAD IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19363,Buildings,Completed,NK-KODAMBAKKAM,137,650000,"Forming shuttle cock court ,Pathway floor titles,Handrails and Elecrical Arrangements for Park at Earrikarai Street and Drainage arrangements for Nesapakkam Chennai Higher Secondary School at Earikkarai Street in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19364,Buildings,Completed,NK-KODAMBAKKAM,137,860000,"Paving the Floor with Rubber moulded Grey premium Concrete paviors ,Compound Wall, Water Pipes, Supply of Motors for Nesapakkam Chennai Higher Secondary School Complex at Earikkarai Street in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19365,Buildings,Completed,NK-KODAMBAKKAM,137,980000,"Raising the Ground level with Wetmix Ground Floor Verandah Laying with Tiles and Renewal of Drainage arrangements for Nesapakkam Chennai Higher Secondary School at Earikkarai Street in Division -137,Unit-28, Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19366,Buildings,Completed,NK-KODAMBAKKAM,137,995000,"Providing water pipeline, Electrical works compound wall (part) Raising ,Painting, colour washing for Burial Ground at Errikarai Street in Dn 137, Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/1949,Roads,Completed,NK-KODAMBAKKAM,139,590000,"PROPOSED LAYING OF ROAD USING BY CEMENT CONCRETE AT R.V.NAGAR 70TH STREET IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/1951,Roads,Completed,NK-KODAMBAKKAM,139,574000,"PROPOSED LAYING OF ROAD USING BY CEMENT CONCRETE AT R.V.NAGAR 72TH STREET REACH-1 IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/1953,Roads,Completed,NK-KODAMBAKKAM,139,220000,"PROPOSED LAYING OF ROAD USING BY CEMENT CONCRETE AT R.V.NAGAR OBLOCK ROAD IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/1955,Buildings,Completed,NK-KODAMBAKKAM,137,834000,IMPROMENTS TO COMPOUND WALL AND CYCLE STAND FOR C.M.S.AT SANKARALINGANOR STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/19591,Buildings,Completed,NK-KODAMBAKKAM,138,320000,"SUPPLYING AND LAYING PIPE LINE FOR STORM WATER DRAIN AT ASHOK PILLER ROAD IN DIVISION -138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/19679,Buildings,Completed,NK-KODAMBAKKAM,137,780000,"Providing water and drainage arrangements Ground level raising ,compound wall, motors for Nesapakkam C.H.S.School of Annexure building on Eastern side of Road at Errikkarai Street and Providing Borewell water supply for M.G.R.Nagar C.M.School at Kamarajar Street and water line for P.C and Road Patch with M20 Concrete at Anna Main Road in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19681,Buildings,Completed,NK-KODAMBAKKAM,137,880000,"Raising the Ground level and Paving with Rubber moulded Grey Premium Concret Paviors, Water and Drainage pipe lines, Flooring Providing Toilet Doors , Ground Floor for Grill and wall Painting for B Block Building at Inside of M.G.R.Nagar Chennai Middle School Complex at Kamarajar Street in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19683,Buildings,Completed,NK-KODAMBAKKAM,136,905000,"Providing and erecting of Poly carbonate roof shelter with vertical support stainless steel post , Streel trusses and Hand rail at inside of Jeeva Park walking Pathway at G.N.Road in Dn-136, Unit-30,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19684,Buildings,Completed,NK-KODAMBAKKAM,136,760000,"Paving the Granite slab for Jeeva Park Compound wall Bay walls and Pillar Bottoms on Rajamannar Street facing alround and pathway painting at G.N.Road in Dn.136,Unit-30,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/19686,Buildings,Completed,NK-KODAMBAKKAM,136,924000,"Providing and Laying Granite slab for walking area with side wall , fancy lights for park main entrances Gate pillars , FRP gratings and Compound wall Granite slab nosing for Jeeva Park at G.N.Road and Laying Pipelines at acrossing the Road near Vivek & Co at North Usman Road in Dn.136,Unit30,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/1975,Buildings,Completed,NK-KODAMBAKKAM,139,970000,"CONSTRUCTION OF RETAINING WALL FOR WIDENING PORTION OF NEW BUS STAND AT WEST JONES ROAD IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/1976,Roads,Completed,NK-KODAMBAKKAM,139,999000,"LAYING OF CEMENT CONCRETE ROAD FOR WIDENING PORTION OF NEW BUS STAND AT GANGAIAMMAN KOIL STREET IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/1979,Roads,Completed,NK-KODAMBAKKAM,139,310000,"LAYING WET MIX FOR WIDENING PORTION OF NEW BUS STAND AT GANGAIAMMAN KOIL STREET IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/19853,Electrical,Completed,NK-KODAMBAKKAM,142,999900,"Provision of 25HP Submersible pumps with electrification Bazzer road Sub Way,Saidapet ,Divisons 142, Zone-X",Own Sources,10,2015-16,2019-20 NK/2015-16/1992,Roads,Completed,NK-KODAMBAKKAM,139,418000,"PROPOSED RELAYING OF ROAD USING CEMENT CONCRETE AT R.V.NAGAR AA-ZZ BLOCK ROAD IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/1996,Roads,Completed,NK-KODAMBAKKAM,139,589000,"PROPOSED LAYING OF ROAD USING BY CEMENT CONCRETE AT R.V.NAGAR 75TH STREET REACH-2 IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/2003,Parks,Completed,NK-KODAMBAKKAM,131,441000,"PROVIDING SECURITY ARRANGEMENT AT SIVAN PARK , K.K.NAGAR IN DN- 131,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/2004,Roads,Completed,NK-KODAMBAKKAM,139,908000,"PROPOSED RELAYING OF ROAD USING CEMENT CONCRETE AT R.V.NAGAR 72TH STREET REACH-2 IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20132,Buildings,Completed,NK-KODAMBAKKAM,132,690000,"Out Sourcing of Private workers for public conveyance cleaning at Kamraj Salai (Ashok Nagar) P.C. and Saidapet Road P.C. in Dn.132,Unit-31,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/20139,Roads,Completed,NK-KODAMBAKKAM,134,990000,"PROVIDING RAIN WATER HAVERSTING (28 NOS) AT ( SUBRAMANIA NAGAR AND VARIOUS STREET ) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20158,Roads,Completed,NK-KODAMBAKKAM,134,990000,"PROVIDING RAIN WATER HAVERSTING (28 NOS) AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20164,Roads,Completed,NK-KODAMBAKKAM,135,990000,"PROVIDING RAIN WATER HAVERSTING (28 NOS) AT VARIUOS STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20171,Roads,Completed,NK-KODAMBAKKAM,133,990000,"PROVIDING RAIN WATER HAVERSTING (28 NOS) AT ( DURAISAMYROAD, N.S.K SALAI AND VARIOUS STREETS ) IN DN-133,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20175,Roads,Completed,NK-KODAMBAKKAM,133,990000,"PROVIDING RAIN WATER HAVERSTING (28 NOS) AT VARIOUS STREET IN DN-133,U-31,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/20363,Buildings,Completed,NK-KODAMBAKKAM,133,690000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING AT NALLAN KUPPAM PC,KAVARAI P.C,N.S.K.SALAI P.C AND PALAYAKARAN STREET P.C IN DIV-133, UNIT -31, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/20364,Buildings,Completed,NK-KODAMBAKKAM,134,690000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING AT DR.GOPAL MENON MAIN ROAD P.C, 60 HUTS SALAI P.C AND AKBARABAD MAIN ROAD P.C IN DIV-134, UNIT -31, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/20365,Buildings,Completed,NK-KODAMBAKKAM,134,690000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING AT RANGARAJAPURAM MAIN ROAD (3 PC) IN DIV-134, UNIT -31, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/20366,Buildings,Completed,NK-KODAMBAKKAM,135,460000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING AT DURAISAMY BRIDGE SALAI PC AND MADLEY BRIDGE SALAI PC IN DIV-135, UNIT -31, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/20367,Buildings,Completed,NK-KODAMBAKKAM,135,340000,"PROVIDING SECURITY ARRANGEMENTS (DAY AND NIGHT) TO PLAY GROUND AT BAKTHAVATCHALAM STREET IN DIV 135,UNIT-31,ZONE-X",Own Sources,10,2015-16,2018-19 NK/2015-16/20370,Parks,Completed,NK-KODAMBAKKAM,127,355000,"ANNUAL MAINTENANCE OF PARK AT OSR 1 TO 12 OSR SAF GAMES VILLAGE FOR KOYAMBEDU IN DN-127, U-29, Z-10. ( FOR TWO MONTHS )",Own Sources,10,2015-16,2016-17 NK/2015-16/20446,Buildings,Completed,NK-KODAMBAKKAM,140,966000,"PROVIDING PLANTS WORK IN THE OUTER SIDE AT PARK IN KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/20447,Buildings,Completed,NK-KODAMBAKKAM,135,995000,"DEMOLITION AND RECONSTRUCTION OF SUMP AT CHENNAI PRIMARY SCHOOL ESWARAN KOIL STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20448,Buildings,Completed,NK-KODAMBAKKAM,140,957000,"LAYING THE FOOTPATH IN FRONT OF PARK AT KODAMPAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/2051,Buildings,Completed,NK-KODAMBAKKAM,139,997000,PROVIDING SHED AND FLOORING WORK IN FRONT OF AUDITORIUM AT CHS SCHOOL JAFFERKHANPET IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/20553,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,991000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20554,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,997000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/20558,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,979000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT RANGARAJAPURAM MAIN ROAD, CORPORATION COLONY MAIN ROAD AND RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20580,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,998000,"IMPROVEMENTS TO STORM WATER DRAIN AT NORTH USMAN ROAD (FROM SOMASUNDARAM STREET TO MURUGAN IDILY) IN DIV 136,UNIT-30,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/20696,Buildings,Completed,NK-KODAMBAKKAM,134,990000,"IMPROVEMENTS TO THE EXISTING CPS AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/20698,Buildings,Completed,NK-KODAMBAKKAM,134,615000,IMPROVEMENTS TO C.H.SCHOOL AT RANGARAJAPURAM MAINROAD IN DN 134 UNIT31ZONE10,Own Sources,10,2015-16,2016-17 NK/2015-16/20702,Buildings,Completed,NK-KODAMBAKKAM,134,980000,"RAISING THE FLOORS WITH TILES FOR GROUND FLOOR CLASS ROOMS IN CPS AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20703,Buildings,Completed,NK-KODAMBAKKAM,138,907000,"REMOVAL OF GARBAGE USING PRIVATE VEHICLE FOR FLOOD WORK 2015, IN DIVISION -138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/20711,Roads,Completed,NK-KODAMBAKKAM,135,883600,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING BC 40MM THICK BY PAVER FINISHER AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/20713,Roads,Completed,NK-KODAMBAKKAM,135,989000,"ATTENDING PATCH WORKS USING BC 40MM THICK BY PAVER FINISHER AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21022,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,980000,"IMPROVEMENTS TO STORM WATER DRAIN AT LOGANATHAN STREET(CHAINAGE FROM 0M TO 75M) IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21046,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,980000,"IMPROVEMENTS TO STORM WATER DRAIN AT LOGANATHAN STREET (CHAINAGE FROM 75M TO 150M) IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21073,Roads,Completed,NK-KODAMBAKKAM,128,970000,"RAISING THE ROAD LEVEL WITH USING WETMIX AT UDHAYAM COLONY AND VEMBULIAMMAN KOIL STREET IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21154,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,980000,"CONSTRUCTION OF STORM WATER DRAIN AT VENKATESAPURAM ROAD(CHAINAGE FROM 0M TO 65M) AT DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21163,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,985000,"CONSTRUCTION OF STORM WATER DRAIN AT VENKATESAPURAM ROAD (CHAINAGE FROM 65M TO 130M) IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21187,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,980000,"IMPROVEMENTS TO STORM WATER DRAIN AT VEMBULIAMMAN KOIL STREET (CHAINAGE FROM 0M TO 80M) IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21191,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,980000,"IMPROVEMENTS TO STORM WATER DRAIN AT VEMBULIAMMAN KOIL STREET (CHAINAGE FROM 80M TO 160M) IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21192,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,980000,"IMPROVEMENTS TO STORM WATER DRAIN AT VEMBULIAMMAN KOIL STREET (CHAINAGE FROM 160M TO 273M) IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21193,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,980000,"IMPROVEMENTS TO STORM WATER DRAIN AT VEMBULIAMMAN KOIL STREET (CHAINAGE FROM 273M TO 385M) IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21194,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,990000,"IMPROVEMENTS TO STORM WATER DRAIN AT UDHAYAM COLONY IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/21512,Roads,Completed,NK-KODAMBAKKAM,134,965000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT WEST AVENUE AND CENTRAL AVENUE IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21572,Roads,Completed,NK-KODAMBAKKAM,134,996000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT MURUGESAN STREET AND CHAKRAPANI STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21584,Roads,Completed,NK-KODAMBAKKAM,134,872000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT ANNA MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21592,Roads,Completed,NK-KODAMBAKKAM,140,754000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROAD AT ELLAIAMMAN KOIL STREET, KARANI GARDEN 1ST STREET IN DIVISION-140, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/21594,Buildings,Completed,NK-KODAMBAKKAM,140,764000,"FLOOD AFFECTED WORK FOR REPAIRS AND WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT SCHOOL ROAD AND VARIOUS SCHOOLS IN DIVISION-140, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/21603,Roads,Completed,NK-KODAMBAKKAM,134,996000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT THIRUVALLUVAR STREET AND SUBRAMANIAN NAGAR CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21670,Roads,Completed,NK-KODAMBAKKAM,135,987000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT VEEASAMY STREET, THIRUVENGADAM STREET, HANUMAR KOIL 1ST STREET, KISHNAMOORTHY STREET, MOORTHY STREET AND HANUMAR KOIL STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21680,Roads,Completed,NK-KODAMBAKKAM,135,974000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT KASI VISWANATHAN KOIL STREET, PUNJAB THOTTAM, SATION ROAD(PART), BABU RAJENDRA PRASAD 2ND STREET, PATEL STREET AND LAKSHMI NARAYANAN STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21706,Roads,Completed,NK-KODAMBAKKAM,136,996000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT MAMBALAM HIGH ROAD REACH - 1 IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/21708,Roads,Completed,NK-KODAMBAKKAM,135,972000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT RAMAKRISHNAPURAM 1ST, 2ND & 3RD STREET, POSTAL COLONY CROSS STREET, BARODA STREET, MAHADEVAN STREET, ESWARAN KOIL STREET AND SRINIVASA(P) STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21709,Roads,Completed,NK-KODAMBAKKAM,136,996000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT VIYASAR STREET AND MAMBALAM HIGH ROAD REACH - 2 IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/21738,Roads,Completed,NK-KODAMBAKKAM,135,975000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT JUBLIEE ROAD AND UMAPATHY STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21755,Roads,Completed,NK-KODAMBAKKAM,135,892000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING BC 40MM THICK BY PAVER FINISHER AT UMAPATHY STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21757,Roads,Completed,NK-KODAMBAKKAM,141,837000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROAD AT MANNAR STREET, DAMODHARAN STREET IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/21761,Roads,Completed,NK-KODAMBAKKAM,141,963000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROAD AT C.I.T NAGAR 4TH MAIN ROAD, MADHURAI VEERAN KOIL STREET IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/21762,Roads,Completed,NK-KODAMBAKKAM,135,558000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING BC 40MM THICK BY PAVER FINISHER AT POSTAL COLONY 3RD & 4TH STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21766,Roads,Completed,NK-KODAMBAKKAM,135,558000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING BC 40MM THICK BY PAVER FINISHER AT VELU STREET,POSTAL COLONY 1ST &2ND STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/21970,Roads,Completed,NK-KODAMBAKKAM,129,560000,"De-watering of Rain water at low lying area using Diesel pump set motor at flood work in Dn 129 in Unit-29,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22129,Buildings,Completed,NK-KODAMBAKKAM,128,930000,"CONSTRUCTION OF COMPOUND WALL ON OSR LAND AT VEMBULIAMMAN KOIL STREET IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/22315,Roads,Completed,NK-KODAMBAKKAM,133,872000,"Attending Patch Work for Flood Affected Roads in Dn. 133, Unit-31, Zone - X (Muthulamman Koil Street and Palayakkaran Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22316,Roads,Completed,NK-KODAMBAKKAM,133,772000,"Attending Patch Work for Flood Affected Roads in Dn. 133, Unit-31, Zone - X (Subbrayan Nagar 4th Street, VOC 1st Main Road and Muthuvel Street )",Own Sources,10,2015-16,2016-17 NK/2015-16/22320,Roads,Completed,NK-KODAMBAKKAM,130,682000,"Attending Patch Work for Flood Affected Roads in Dn. 130, Unit-29, Zone - X (Dharansingh Colony 2nd Street, Venkateswara Street, Thiru Nagar 5th Street, NGO COlony 1st Street, Kumaran Colony 7th Street and Kumaran Nagar 9th Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22322,Roads,Completed,NK-KODAMBAKKAM,130,607000,"Attending Patch Work for Flood Affected Roads in Dn. 130, Unit-29, Zone - X (Thiru Nagar 1st Street, Thiru Nagar 6th Street, Gangaiamman Koil Street Saligramam, Balaji Avenue and South Sivan Koil Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22323,Roads,Completed,NK-KODAMBAKKAM,137,791000,"ATTANDING THE PATCH WORK FOR FLOOD AFFECTED ROADS AT KHAN NAGAR MAIN ROAD,AND 10TH SECTOR 63RD STREET SALAI IN DN 137 UNIT 28 ZONE 10",Own Sources,10,2015-16,2016-17 NK/2015-16/22325,Roads,Completed,NK-KODAMBAKKAM,137,906000,ATTENDING THE PATCH WORK FLOOD AFFECTED ROADS AT ALGIRISAMY SALAI AND VENKATRAMAN SALAI IN DN 137 UNIT 28 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/22326,Roads,Completed,NK-KODAMBAKKAM,128,823000,"Attending Patch Work for Flood Affected Roads in Dn. 128, Unit-29, Zone - X (CRR Puram Phase 1, AVM Colony, Ganapathrai Nagar Main Road, Kamarajar Salai, Elango Nagar and Vuyaputhira Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22327,Roads,Completed,NK-KODAMBAKKAM,128,942000,"Attending Patch Work for Flood Affected Roads in Dn. 128, Unit-29, Zone - X (Erikkarai Street, Elango Nagar South Street, Krishna Nagar, AVM Avenue 1st Main Road, Kambar Street, Pilliayar Koil Street, Kanniamman Koil Street and Pachaiappan Koil Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22328,Roads,Completed,NK-KODAMBAKKAM,128,943000,"Attending Patch Work for Flood Affected Roads in Dn. 128, Unit-29, Zone - X (Vinayagam Street, Jeevanandham Salai, East Vanniar Street, Pillaiyar Koil Street Nesapakkam, MAriamman Koil Street, AVM Avenue 2nd Main Road and Periyar Nagar)",Own Sources,10,2015-16,2016-17 NK/2015-16/22329,Roads,Completed,NK-KODAMBAKKAM,128,909000,"Attending Patch Work for Flood Affected Roads in Dn. 128, Unit-29, Zone - X (Vembuliamman Koil Street, Vembuliamman Koil1st Cross Street and New Colony)",Own Sources,10,2015-16,2016-17 NK/2015-16/22330,Roads,Completed,NK-KODAMBAKKAM,128,753000,"Attending Patch Work for Flood Affected Roads in Dn. 128, Unit-29, Zone - X (Udhayam Colony, Lambert Nagar and Bazzar Road)",Own Sources,10,2015-16,2016-17 NK/2015-16/22331,Roads,Completed,NK-KODAMBAKKAM,137,971000,ATTENDING THE PATCH WORK FOR FLOOD AFFECTED ROAD AT PONNAMBALAM SALAI AND 11TH SECTOR 69TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/22333,Roads,Completed,NK-KODAMBAKKAM,137,834000,ATTANDING THE PATCHWORK FLOOD AFFECTED ROADS AT 10TH SECTOR 60TH STREET AND 9TH SECTOR 53RD STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/22334,Roads,Completed,NK-KODAMBAKKAM,129,865000,"Attending Patch Work for Flood Affected Roads in Dn. 129, Unit-29, Zone - X (Kaveri Street, Devaraj Nagar, Gandhi Nagar Ladies Hostel and Logaiya Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22335,Roads,Completed,NK-KODAMBAKKAM,129,915000,"Attending Patch Work for Flood Affected Roads in Dn. 129, Unit-29, Zone - X (Abusali Road and Navaneethammal Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22342,Roads,Completed,NK-KODAMBAKKAM,127,816000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS IN DN 127,U - 29, ZONE -10 (AVVAI THIRU NAGAR CROSS STREET,KANAGASABAI COLONY BAKTHAVATCHALAM STREET, THIRU-VI-KA STREET AND VENKATESA NAGAR 2ND cross streeet)",Own Sources,10,2015-16,2016-17 NK/2015-16/22343,Roads,Completed,NK-KODAMBAKKAM,136,995000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT COATS ROAD IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22344,Roads,Completed,NK-KODAMBAKKAM,127,498000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (Sayee Nagar 1st Main Road)",Own Sources,10,2015-16,2016-17 NK/2015-16/22346,Roads,Completed,NK-KODAMBAKKAM,127,710000,"Attending patch work for flood affected roads in div-127, unit-29, zone-10 (Chinmaya nagar stage 2nd street and Kumaran nagar 1st cross street, Chinmaya nagar stage II ext 1st street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22347,Roads,Completed,NK-KODAMBAKKAM,127,538000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (Thiruveedhi Amman Koil Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22348,Roads,Completed,NK-KODAMBAKKAM,136,999000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT MASILAMANI STREET , Dr.SINGARAVELU STREET, MAYILAI RANGANATHAN STREET IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22349,Roads,Completed,NK-KODAMBAKKAM,127,747000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (SAF Games Village 1st Cross Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22350,Roads,Completed,NK-KODAMBAKKAM,127,747000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (SAF Games Village 2nd Cross Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22351,Roads,Completed,NK-KODAMBAKKAM,136,995800,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT RAGAVAIAH ROAD IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22352,Roads,Completed,NK-KODAMBAKKAM,127,934000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (Natesan Nagar 1st Cross Street and Nerkundram Road)",Own Sources,10,2015-16,2016-17 NK/2015-16/22353,Roads,Completed,NK-KODAMBAKKAM,127,698000,"Attending patch work for flood affected roads in div-127, unit-29, zone-10 (Sastri street and Sayee nagar III main road)",Own Sources,10,2015-16,2016-17 NK/2015-16/22354,Roads,Completed,NK-KODAMBAKKAM,127,747000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (Natesan Nagar 2nd Main Road and Sayee Nagar 2nd Main Road)",Own Sources,10,2015-16,2016-17 NK/2015-16/22355,Roads,Completed,NK-KODAMBAKKAM,127,847000,"Attending patch work for flood affected roads in div-127, unit-29, zone-10 Kumaran Nagar 3rd main road, Venkatesa nagar Ext 2 3rd main road and Venkatesa nagar 1st cross street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22356,Roads,Completed,NK-KODAMBAKKAM,127,747000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (SAF games Village 1st Cross Street and Koyambedu North Mada Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22359,Roads,Completed,NK-KODAMBAKKAM,127,732000,"Attending Patch Work for Flood Affected Roads in Dn. 127, Unit-29, Zone - X (Natesan NAgar 3rd Main Road and TSD Nagar 1st Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/22360,Roads,Completed,NK-KODAMBAKKAM,127,598000,"Attending patch work for flood affected roads in div-127, unit-29, zone-10 (P.A.Colony main road and Kumaran nagar 1st main road)",Own Sources,10,2015-16,2016-17 NK/2015-16/22362,Roads,Completed,NK-KODAMBAKKAM,127,698000,"Attending patch work for flood affected roads in div-127, unit-29, zone-10 (Kumaran nagar 2nd main road and Engineer sampath garden)",Own Sources,10,2015-16,2016-17 NK/2015-16/22363,Roads,Completed,NK-KODAMBAKKAM,132,1120000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT INDRA COLONY 1ST STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22366,Roads,Completed,NK-KODAMBAKKAM,136,999000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT BAZULLA ROAD ( SERVICE ROAD ) IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22367,Roads,Completed,NK-KODAMBAKKAM,136,998000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT SOMASUNDHARAM STREET AND RAMA STREET IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22368,Roads,Completed,NK-KODAMBAKKAM,133,655000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 2nd AVENUE (PART) IN DIV-133, UNIT-31, ZONE-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/22369,Roads,Completed,NK-KODAMBAKKAM,136,997000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT HANUMANTHA STREET AND VIYASAR STREET IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/22370,Roads,Completed,NK-KODAMBAKKAM,138,700000,"ATTENDING PATCH WORK EOR FLOOD AFFECTED ROADS USING PAVER FINISHER AT PILLAIYAR KOIL STREET AND PACHAIAPPAN STREET,JAFFERKHANPET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22371,Roads,Completed,NK-KODAMBAKKAM,132,400000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT INDRA COLONY 2ND STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22372,Roads,Completed,NK-KODAMBAKKAM,136,996000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT RAJACHAR STREET AND COATS ROAD REACH - 2 IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22373,Roads,Completed,NK-KODAMBAKKAM,133,380000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT DHANASEKARAN STREET EXTN., IN DIV-133, UNIT-31, ZONE-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/22374,Roads,Completed,NK-KODAMBAKKAM,136,995000,"ATTENDING THE FLOOD AFFECTED PATCH WORK AT SIVAGNANAM STREET AND USMAN ROAD (SERVICE ROAD ) IN DIVISION-136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22375,Roads,Completed,NK-KODAMBAKKAM,132,552000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT INDRA COLONY 3RD STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22376,Roads,Completed,NK-KODAMBAKKAM,132,467000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT INDRA COLONY 4TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22377,Roads,Completed,NK-KODAMBAKKAM,133,440000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT APPASAMY STREET IN DIV-133, UNIT-31, ZONE-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/22378,Roads,Completed,NK-KODAMBAKKAM,138,570000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROAD USING PAVER FINISHER AT KK SALAI AND THIRU NAGAR PERIYAR STREET JAFFERKHANPET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22379,Roads,Completed,NK-KODAMBAKKAM,133,250000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT VEDHAMMAL AVENUE IN DIV-133, UNIT-31, ZONE-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/22380,Roads,Completed,NK-KODAMBAKKAM,133,290000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 16TH STREET IN DIV-133, UNIT-31, ZONE-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/22382,Roads,Completed,NK-KODAMBAKKAM,133,265000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT MARIAMMAN KOIL STREET IN DIV-133, UNIT-31, ZONE-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/22388,Roads,Completed,NK-KODAMBAKKAM,134,921000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT NTR STREET AND U.I.COLONY 4TH CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22389,Roads,Completed,NK-KODAMBAKKAM,141,710000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROAD AT C.I.T NAGAR 3RD MAIN ROAD AND C.I.T NAGAR 3RD MAIN ROAD EXTN 1&2 STREET IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22390,Roads,Completed,NK-KODAMBAKKAM,134,946000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT U.I.COLONY 4TH MAIN ROAD AND INNER CIRCULAR ROAD AFFECTED BY FLOOD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22391,Roads,Completed,NK-KODAMBAKKAM,141,875000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROAD AT POLICE QUARTERS ROAD , MOOOSA STREET IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22392,Roads,Completed,NK-KODAMBAKKAM,134,999000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT U.I.COLONY 1ST MAIN ROAD,AZIZ NAGAR MAIN ROAD AND PADMANABAN STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22393,Roads,Completed,NK-KODAMBAKKAM,134,889000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT KAMARAJAR COLONY AND AZIZ NAGAR 1ST & 3RD STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22396,Roads,Completed,NK-KODAMBAKKAM,134,984000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT RANGARAJAPURAM MAIN ROAD, U.I.COLONY PARK VIEW ROAD AND GUGAN STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22398,Roads,Completed,NK-KODAMBAKKAM,134,960000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT VISWANATHAPUARM 1ST STREET, NSK SERVICE ROAD, RAILWAY BORDER ROAD AND RATHINAMMAL STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22401,Roads,Completed,NK-KODAMBAKKAM,134,957000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT STATION VIEW ROAD, VISWANATHAPURAM 2ND STREET,TANK STREET AND CHAKRAPANI STREET EXTN., IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22411,Roads,Completed,NK-KODAMBAKKAM,135,872000,"ATTENDING PATCH WORK BY PAVER FINISHER AT VINAYAGAM STREET (FROM MOORTHY STREET TO SRINIVASA(I) IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22412,Roads,Completed,NK-KODAMBAKKAM,135,510000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT POSTAL COLONY 4TH STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22413,Roads,Completed,NK-KODAMBAKKAM,135,772000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS BY PAVER FINISHER AT GOPALAN STREET, BALAKISHNAN(M) STREET AND POSTAL COLONY 3RD STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22416,Roads,Completed,NK-KODAMBAKKAM,135,872000,"ATTENDING PATCH WORK BY PAVER FINISHER AT VINAYAGAM STREET (FROM SRINIVASA(I) STREET TO DEAD END) IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22417,Roads,Completed,NK-KODAMBAKKAM,135,875000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22419,Roads,Completed,NK-KODAMBAKKAM,133,720000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP AND ENGAGING PRIVATE LABOURS IN DN-133,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22421,Roads,Completed,NK-KODAMBAKKAM,134,793000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22424,Roads,Completed,NK-KODAMBAKKAM,134,940000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22532,Roads,Completed,NK-KODAMBAKKAM,128,1677000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Vembuliamman Koil 1st Cross Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/22546,Roads,Completed,NK-KODAMBAKKAM,130,2637000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Kumaran Colony Main Road in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/22683,Buildings,Completed,NK-KODAMBAKKAM,127,993000,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET IN NATESAN NAGAR, SAI NAGAR, AND POST ADIUT COLONY AND VARIOUS STREET IN DN-127, U-29, Z-10 (UNDER WARD COUNCILLOR FUND)",Own Sources,10,2015-16,2018-19 NK/2015-16/22749,Buildings,Completed,NK-KODAMBAKKAM,134,530000,"IMPROVEMENTS TO THE EXISTING PUBLIC CONVENIENCE AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/22770,Buildings,Completed,NK-KODAMBAKKAM,127,993000,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET IN SEMATHAMMAN 1ST & 2ND NAGAR, AND SEMATHAMMAN 1ST AND 2ND SECTOR AND VARIOUS STREET IN DN-127, U-29, Z-10 ( UNDER WARD COUNCILLOR FUND )",Own Sources,10,2015-16,2018-19 NK/2015-16/22791,Buildings,Completed,NK-KODAMBAKKAM,139,853000,"REMOVAL OF GARBAGE USING PRIVATE VEHICLE FOR FLOOD WORK 2015,IN DIV -139,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/22793,Buildings,Completed,NK-KODAMBAKKAM,139,426000,"REMOVAL OF GARBAGE USING PRIVATE VEHICLE FOR FLOOD WORK 2015,IN DIVISION -139,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/22819,Buildings,Completed,NK-KODAMBAKKAM,139,993000,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET IN KULASEKARAPURAM STREET AND VARIOUS STREET IN DN-127, U-29, Z-10 (UNDER WARD COUNCILLOR FUND)",Own Sources,10,2015-16,2018-19 NK/2015-16/22938,Roads,Completed,NK-KODAMBAKKAM,132,990000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS PLACES IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/22942,Roads,Completed,NK-KODAMBAKKAM,132,990000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS PLACES IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23044,Buildings,Completed,NK-KODAMBAKKAM,139,77000,"IMPROVEMENT WORK ON R.R.COLONY PLAY GROUND COMPOUND WALL AND IN-DOOR STADIUM PAINTING WORK IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23080,Buildings,Completed,NK-KODAMBAKKAM,139,69000,"IMPROVEMENT WORK ON WEST SAIDAPET BUS STAND COMPOUND WALL AND E-SEVA AT WEST JONES ROAD IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/23083,Buildings,Completed,NK-KODAMBAKKAM,139,385000,"IMPROVEMENT WORK ON AMMA KUDINEER AT R.R.COLONY 3RD ST (NEAR AAVIN MILK BOOTH) IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23084,Buildings,Completed,NK-KODAMBAKKAM,139,353000,"REPAIR AND MAINTENANCE WORK ON COMMUNITY HALL AT VADIVEL MAIN ST IN DIV-139,U-28,ZZ-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23140,Roads,Completed,NK-KODAMBAKKAM,139,1760000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT PERUMAL KOIL WEST MADA ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23166,Roads,Completed,NK-KODAMBAKKAM,139,977000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT NEW COLONY MAIN ROAD IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23173,Roads,Completed,NK-KODAMBAKKAM,139,496000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE THICK AT R.R.COLONY 1ST LINK ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23193,Roads,Completed,NK-KODAMBAKKAM,139,1008000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE THICK AT R.R.COLONY 1ST CROSS ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23195,Roads,Completed,NK-KODAMBAKKAM,139,1008000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT R.R.COLONY 2ND CROSS ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23196,Roads,Completed,NK-KODAMBAKKAM,139,1090000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT R.R.COLONY 3RD ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23197,Roads,Completed,NK-KODAMBAKKAM,139,556000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT MANICKAM ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23199,Roads,Completed,NK-KODAMBAKKAM,139,1257000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT S.V.CHIDAMBARAM SALAI IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23201,Roads,Completed,NK-KODAMBAKKAM,139,916000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT VADIVEL MAIN ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23203,Roads,Completed,NK-KODAMBAKKAM,139,475000,"PROPOSED RELAYING OF ROAD USING BY BITUMINOUS CONCRETE AT C.P.SUNDARAMOORTHI ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23206,Roads,Completed,NK-KODAMBAKKAM,139,858000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT PUNNIYAKODI ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23207,Roads,Completed,NK-KODAMBAKKAM,139,865000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT AMMA KANNAMMA ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23208,Roads,Completed,NK-KODAMBAKKAM,139,423000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT ALAYA MAISTRY ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23209,Roads,Completed,NK-KODAMBAKKAM,139,385000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT THILAGAR ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23210,Roads,Completed,NK-KODAMBAKKAM,139,447000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT POONGAVANAM ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23211,Roads,Completed,NK-KODAMBAKKAM,139,837000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT GOVINDASAMY ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23212,Roads,Completed,NK-KODAMBAKKAM,139,285000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT NAKKEERAN ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23213,Roads,Completed,NK-KODAMBAKKAM,139,433000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT APPAIYA MAISTRY ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23214,Roads,Completed,NK-KODAMBAKKAM,139,774000,"PROPOSED RELAYING OF ROAD USING BY CEMENT CONCRETE AT BALAKRISHNAN ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23253,Roads,Completed,NK-KODAMBAKKAM,137,800000,RELAYING THE ROAD WITH FAVERING FINISHER AT 8TH SECTOR 39TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23254,Roads,Completed,NK-KODAMBAKKAM,137,623000,RELAYING THE ROAD WITH FAVER FINISHER AT 9TH SECTOR 47TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23255,Roads,Completed,NK-KODAMBAKKAM,137,550000,RELAYING THE ROAD WITH FAVER FINISHER AT 9TH SECTOR 48TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23256,Roads,Completed,NK-KODAMBAKKAM,137,326000,RELAYING THE ROAD WITH FAVER FINISHER AT 9TH SECTOR 50TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23257,Roads,Completed,NK-KODAMBAKKAM,137,1231000,RELAYING THE ROAD WITH FAVER FINISHER AT 11TH SECTOR 66TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23258,Roads,Completed,NK-KODAMBAKKAM,137,2067000,RELAYING THE ROAD WITH FAVER FINISHING AT 11TH SECTOR 71TH STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23259,Roads,Completed,NK-KODAMBAKKAM,142,4761000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT ALANDUR ROAD IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23260,Roads,Completed,NK-KODAMBAKKAM,142,1466000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT SUBRAMANIYASAMY KOIL STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23261,Roads,Completed,NK-KODAMBAKKAM,142,2346000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT PERUMAL KOIL STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23262,Roads,Completed,NK-KODAMBAKKAM,142,1311000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT THIRUVALLUVAR STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23263,Roads,Completed,NK-KODAMBAKKAM,142,764000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT BRAHMIN STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23265,Roads,Completed,NK-KODAMBAKKAM,142,2468000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT KOTHAVALCHAVADI STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23266,Roads,Completed,NK-KODAMBAKKAM,142,586000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT NARAYANASAMY MAIN STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23267,Roads,Completed,NK-KODAMBAKKAM,142,820000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT NARAYANASAMY I STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23268,Roads,Completed,NK-KODAMBAKKAM,142,1318000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT NARAYANASAMY II STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23270,Roads,Completed,NK-KODAMBAKKAM,142,669000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT RAMAPURAM RAMASAMY STREET IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23271,Roads,Completed,NK-KODAMBAKKAM,142,1954000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT BAZAAR ROAD IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23272,Roads,Completed,NK-KODAMBAKKAM,142,1424000,"RELAYING ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER AT JEENIS ROAD IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23274,Roads,Completed,NK-KODAMBAKKAM,127,329000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at Bakthavatchalam Street in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23275,Roads,Completed,NK-KODAMBAKKAM,127,531000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at Natesan Nagar 2nd Cross Street in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23276,Roads,Completed,NK-KODAMBAKKAM,127,1090000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at West Mada Street in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23278,Roads,Completed,NK-KODAMBAKKAM,127,1580000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at Sundaram Street in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23279,Roads,Completed,NK-KODAMBAKKAM,131,2304000,"LAYING OF CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 3rd STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23280,Roads,Completed,NK-KODAMBAKKAM,127,1564000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at Jai Nagar 2nd Main Road in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23281,Roads,Completed,NK-KODAMBAKKAM,127,934000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at Krishna Street in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23282,Roads,Completed,NK-KODAMBAKKAM,127,1375000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at Kamarajar Salai in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23288,Roads,Completed,NK-KODAMBAKKAM,127,439000,"Relaying of the road by using BC 30 mm thick with Mechanical Paver Finisher at Sayee Nagar Annex in Dn. 127, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/23297,Roads,Completed,NK-KODAMBAKKAM,137,330000,RELAYING THE ROAD WITH FAVER FINISHER AT 11TH SECTOR 72ND STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23298,Roads,Completed,NK-KODAMBAKKAM,137,550000,RELAYING THE ROAD WITH FAVER FINISHER AT PUGALENTHI STREET EXTN.IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/23299,Roads,Completed,NK-KODAMBAKKAM,137,1662000,LAYING CEMENT CONCRETE ROAD AT PONMANACHEMAL STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2017-18 NK/2015-16/23306,Roads,Completed,NK-KODAMBAKKAM,131,2400000,"LAYING OF CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 4th STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/23314,Roads,Completed,NK-KODAMBAKKAM,137,1581000,LAYING CEMENT CONCRETE ROAD AT THIRU VI KA STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2017-18 NK/2015-16/23318,Roads,Completed,NK-KODAMBAKKAM,137,1581000,LAYING CEMENT CONCRETE ROAD AT THOLKAPIER STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2017-18 NK/2015-16/23322,Roads,Completed,NK-KODAMBAKKAM,136,890000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT RAMA STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23326,Roads,Completed,NK-KODAMBAKKAM,132,770000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS (FROM 1.12.2015 TO 17.12.2015) IN DN-132,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23365,Roads,Completed,NK-KODAMBAKKAM,127,793000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING ENGAGING JCB AND TIPPER LORRY & PRIVATE LABOURS FOR NIGHT WORK IN DIV-127,UNIT-29,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/23370,Roads,Completed,NK-KODAMBAKKAM,136,1605000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT RAJACHAR STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23373,Roads,Completed,NK-KODAMBAKKAM,136,1243000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT MURUKESAN STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23376,Roads,Completed,NK-KODAMBAKKAM,136,4203000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT RAGAVAIAH ROAD IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23378,Roads,Completed,NK-KODAMBAKKAM,136,911000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT HANUMANTHA STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23379,Roads,Completed,NK-KODAMBAKKAM,136,1026000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT YOGAMBAL STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23380,Roads,Completed,NK-KODAMBAKKAM,136,658000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT LAKSHMANAN STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23382,Roads,Completed,NK-KODAMBAKKAM,136,1869000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT RAJABATHAR STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23384,Roads,Completed,NK-KODAMBAKKAM,136,1139000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT GOPALAKRISHNAN STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23385,Roads,Completed,NK-KODAMBAKKAM,136,330000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT RAMACHANTHIRA STREET IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/23386,Roads,Completed,NK-KODAMBAKKAM,136,765000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT RADHAKRISHNAN STREET IN DIVISION - 136, UNIT - 30, ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/23387,Roads,Completed,NK-KODAMBAKKAM,136,999000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT RAMASAMY STREET IN DIVISION - 136, UNIT - 30, ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/23390,Roads,Completed,NK-KODAMBAKKAM,136,1349000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT MOTILAL STREET IN DIVISION - 136, UNIT - 30, ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/23680,Buildings,Completed,NK-KODAMBAKKAM,139,986000,PAINTING WORK AND PLUMBING WORK IN CPS & CHS SCHOOL AT JAFFERKHANPET MAIN ROAD IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/23800/C,Roads,Completed,NK-KODAMBAKKAM,128,575000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS IN DN-128,U-29,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23806,Roads,Completed,NK-KODAMBAKKAM,128,885000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS AT VEMBULIAMMAN KOIL STREET IN DN-128,U-29,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/23820,Roads,Completed,NK-KODAMBAKKAM,128,700000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING SUPPLY OF DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS AT VEMBULIAMMAN KOIL STREET IN DN-128,U-29,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/2397,Electrical,Completed,NK-KODAMBAKKAM,139,113700,"Electrification of Bus Stand with provision of 8 nos of 400 W MH Fitting at west jones road in Division - 139, zone -X",Own Sources,10,2015-16,2016-17 NK/2015-16/23976,Roads,Completed,NK-KODAMBAKKAM,136,915000,"RELAYING ROAD WITH CEMENT CONCRETE (M40 GRADE) AT NEW POSTAL COLONY IN DIVISION-136,UNIT-30,ZONE-10(UNDER M.L.A FUND)",MLACDS,10,2015-16,2017-18 NK/2015-16/23980,Roads,Completed,NK-KODAMBAKKAM,136,924000,"RELAYING ROAD WITH BITUMINOUS CONCRETE USING MECHANICAL PAVER FINISHER AT DURAISAMY ROAD SERVICE ROAD IN DIVISION-136,UNIT-30,ZONE-10(UNDER M.L.A FUND)",Deposit Works,10,2015-16,2016-17 NK/2015-16/23981,Roads,Completed,NK-KODAMBAKKAM,136,1016000,"RELAYING ROAD WITH BITUMINOUS CONCRETE USING MECHANICAL PAVER FINISHER AT RAJA STREET IN DIVISION-136,UNIT-30,ZONE-10(UNDER M.L.A FUND)",MLACDS,10,2015-16,2016-17 NK/2015-16/23982,Roads,Completed,NK-KODAMBAKKAM,136,1289000,"RELAYING ROAD WITH BITUMINOUS CONCRETE USING MECHANICAL PAVER FINISHER AT NORTH USMAN ROAD SERVICE ROAD IN DIVISION-136,UNIT-30,ZONE-10(UNDER M.L.A FUND)",MLACDS,10,2015-16,2017-18 NK/2015-16/23984,Roads,Completed,NK-KODAMBAKKAM,136,1292000,"RELAYING ROAD WITH BITUMINOUS CONCRETE USING MECHANICAL PAVER FINISHER AT NORTH USMAN ROAD SERVICE ROAD IN DIVISION-136,UNIT-30,ZONE-10(UNDER M.L.A FUND)",MLACDS,10,2015-16,2016-17 NK/2015-16/2404,Buildings,Completed,B-Buildings,131,900000,"PROVIDING ALUMINIUM COMPOSITE BOARD UPHC AT VIJAYARAGAVAPURAM 5TH STREET IN DN-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/24227/C,Roads,Completed,NK-KODAMBAKKAM,139,827000,"WIDENING OF ROAD AT APPADURAI STREET(CHAINAGE FROM MUNUSAMY ST TO KANNAMMAL ST JN) IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/24241,Roads,Completed,NK-KODAMBAKKAM,139,548000,"WIDENING OF ROAD AT APPADURAI STREET(CHAINAGE FROM KANNAMMAL ST TO GANGAI AMMAN KOIL STJN NEAR P.C) IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/24254/C,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT V.S MUDHALI STREET(REACH-2) IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/24257,Footpath,Completed,NK-KODAMBAKKAM,138,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DN-138, UNIT-28 AND ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/24447,Buildings,Completed,NK-KODAMBAKKAM,142,995000,"REMOVAL OF GARBAGE USING PRIVATE VEHICLE FOR FLOOD WORK 2015,IN DIV -142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/24480,Roads,Completed,NK-KODAMBAKKAM,131,583000,"ESTIMATE FOR FLOOD RELIEF WORK INCLUDING HIRING DIESEL PUMP, ENGAGING JCB & DIPPER LORRY AND PRIVATE LABOURS (FROM 14.11.2015 TO 26.12.2015) IN DN-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/24482,Roads,Completed,NK-KODAMBAKKAM,131,252000,"ESTIMATE FOR FLOOD RELIEF WORK SUPPLY OF WMM & MINI LORRY (TATA ACE ) UNDER DAILY HIRING INCLUDING 6 LABOURS FOR REMOVAL OF DEBRIS,GARBAGE AND CLEANING THE WATER TABLE AND FOOTPATHIN BUS ROUTE AND INTERIOR ROAD IN DIV-131, U-28, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/24541,Roads,Completed,NK-KODAMBAKKAM,139,351000,"WIDENNING OF ROAD AT GANGAI AMMAN KOIL ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/24611,Subway,Completed,NK-KODAMBAKKAM,142,540000,"DESILTING OF ALANDUR SUBWAY ,JONES ROAD SUBWAY PROVIDING WATER PROOF LEAKAGE CHEMICAL TO ARREST LEAKAGE IN DIV 142, UNIT-30, ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/24624,Parks,Completed,NK-KODAMBAKKAM,136,930000,"IMPROVEMENTS TO PANAGAL PARK IN DN 136,UNIT-30,ZONE-08.",Own Sources,10,2015-16,2016-17 NK/2015-16/24631,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,988000,"REPAIR AND DESILTING OF SWD AT LAKSHMANASAMY SALAI,80 FEED ROAD AND VARIOUS STREET IN DN-131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2019-20 NK/2015-16/24636,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,860000,"REPAIRS TO THE SWD AT ARUNACHALAM ROAD (WEST SIDE) AND ARCOT ROAD IN DN-129, UNIT-29, ZONE-10 (UNDER WARD COUNCILLOR FOUND 2015-2016)",Own Sources,10,2015-16,2018-19 NK/2015-16/24638,Roads,Completed,NK-KODAMBAKKAM,129,468000,"PROVIDING HUME PIPE CONNECTION AT ARUNACHALAM ROAD AND ARCOT ROAD IN DN-129, UNIT-29, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/24640,Roads,Completed,NK-KODAMBAKKAM,129,975000,"RAISING THE ROAD LEVEL AT KUMARAN COLONY 1st STREET AND LOGAIAH STREET IN DN-129, UNIT-29, ZONE10",Own Sources,10,2015-16,2018-19 NK/2015-16/24642,Buildings,Completed,NK-KODAMBAKKAM,134,950000,IMPROVEMENTS TO MATERNITY HOSPITAL AT N.S.K SALAI IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/24643,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,995000,"DESILTING OF SWD AT BHARATHIDASAN COLONY IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/24647,Buildings,Completed,NK-KODAMBAKKAM,134,980000,IMPROVEMENTS TO AMMAUNAVAGAM AT KAMARAJAR COLONY IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/24692,Buildings,Completed,NK-KODAMBAKKAM,138,672000,"SUPPLYING AND LAYING OF RCC PIPE FOR EXTENTION OF SWD AT JUNCTION OF BHARATHIDASAN COLONY AND 60 FEET ROAD AND VARIOUS IMPROVEMENT WORK IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/24733,Roads,Completed,NK-KODAMBAKKAM,130,537000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Karumariamman Koil Street (Part - I) in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/24739,Roads,Completed,NK-KODAMBAKKAM,130,909000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Pillaiyar Koil Street (Part - I) in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/24755,Buildings,Completed,NK-KODAMBAKKAM,128,970000,"CONSTRUCTION OF ADDITIONAL ROOM IN AMMA UNAVAGAM 2 AT ELANGO NAGAR IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/24788,Buildings,Completed,NK-KODAMBAKKAM,134,474000,"Out sourcing private workers for house keeping work for 1 year at 1 Government schools in Div 134 ,Unit-31,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/24889,Buildings,Completed,NK-KODAMBAKKAM,139,982000,IMPROVEMENT AND REPAIR WORK ON CPS AT SCHOOL STREET IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2018-19 NK/2015-16/24900,Roads,Completed,NK-KODAMBAKKAM,127,975000,"ATTENDING PATCH WORK USING CEMENT CONCRETE ROAD USING M40 GRADE IN FRONT OF X1 & X2 BLOCKS AT SAF GAMES VILLAGE CROSS ROAD IN DN-127, UNIT-29,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/24905,Roads,Completed,NK-KODAMBAKKAM,127,946000,"ATTENDING PATCH WORK USING CEMENT CONCRETE ROAD USING M40 GRADE IN OTHER CROSS STREETS AT SAF GAMES VILLAGE IN DN-127, UNIT-29,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/25037,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,700000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT S.V.LINGAM SALAI IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/25039,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,980000,"DISMANTLING THE EXISTING RCC SLAB AND RECONSTRUCTION OF STORM WATER DRAIN SLAB AT 19TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/25049,Buildings,Completed,NK-KODAMBAKKAM,134,620000,"CONSTRUCTION OF COMPOSITE YARD AT CORPORATION COLONY 2ND STREET IN DIV-134, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/25050,Buildings,Completed,NK-KODAMBAKKAM,128,975000,"CONSTRUCTION OF SUMP AND OTHER IMPROVEMENTS IN AMMA UNAVAGAM 2 AT ELANGO NAGAR IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/25051,Buildings,Completed,NK-KODAMBAKKAM,128,980000,"IMPROVEMENTS TO AMMA UNAVAGAM2 AT ELANGO NAGAR IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/25052,Buildings,Completed,NK-KODAMBAKKAM,128,700000,"PROVIDING BORE WELL AND OTHER IMPROVEMENTS TO AMMA UNAVAGAM 2 AT ELANGO NAGAR IN DIV-128, U-29, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/25194,Buildings,Completed,NK-KODAMBAKKAM,137,660000,"Providing Pathway at Children Play Ground 10th Sector 61th Street in Dn.137,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/25195,Buildings,Completed,NK-KODAMBAKKAM,137,660000,"Providing Pathway at Play Ground 10th Sector 61th Street in Dn.137,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/25196,Buildings,Completed,NK-KODAMBAKKAM,137,237000,"Providing Water , Drainage Pipe lines Electrical works and Building inside wall Painting for C.M.S. at Sankaralinganar Street in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/25197,Buildings,Completed,NK-KODAMBAKKAM,137,986000,"Proposed Compound wall raising ,Cup-boards Flooring , Aluminium Doors and Windows , Water Supply and Drainage arrangements and Painting for Corporation Health Post at Errikarai Street in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/25198,Buildings,Completed,NK-KODAMBAKKAM,138,690000,"Construction of Toilet Block with Septic Tank,Water Supply Drainage arrangements Approached Road Lain with RMC M20 Concrete at Ambedkhar Colony in Dn.138,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/25411,Buildings,Completed,NK-KODAMBAKKAM,138,425000,"SUPPLYING AND LAYING OF WET MIX , ENGAGING LABOUR AND REPAIR THE BOREWELL MOTORS FOR FLOOD WORK IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/25973,Buildings,Completed,NK-KODAMBAKKAM,136,840000,"IMPROVEMENTS JEEVA PARK TO GREENARY ARRANGEMENTS AT DIV-136,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/26066,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,730000,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT 18TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26073,Buildings,Completed,NK-KODAMBAKKAM,137,990000,"Additional improvements to Burial Ground at Errikarai Street in Dn.137,Unit-28, Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/26240,Roads,Completed,NK-KODAMBAKKAM,137,950000,SUPPLYING GOOD EARTH AND WMM FOR RAISING THE ROAD AT N.S.C.BOSE ROAD IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2017-18 NK/2015-16/26258,Roads,Completed,NK-KODAMBAKKAM,137,990000,LAYING CEMENT CONCRETE ROAD AT NSC BOSE ROAD BHARATHI NAGAR IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2017-18 NK/2015-16/26360,Roads,Completed,NK-KODAMBAKKAM,131,556000,"LAYING CEMENT CONCRETE ROAD AT KANNIGAPURAM 4th STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/26365,Roads,Completed,NK-KODAMBAKKAM,131,618000,"LAYING CEMENT CONCRETE ROAD AT M.G.R. NAGAR STAUNTSOMU STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/26459,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,988000,"PROVIDING TOP SLAB FOR SWD AT SAF GAMES VILLAGE SIDE DRAIN AND REPLACING OF DAMAGED SWD DOORS AT VARIOUS STREETS IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/26472,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,990000,"CONSTRUCTION OF STORM WATER DRAIN AT KUMARAN NAGAR (JUNCTION OF KUMARAN NAGAR 3RD STREET) IN DIV 127, UNIT-29,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/26473,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,994000,"DEMOLISHION AND CONSTRUCTION OF STORM WATER DRAIN AT SRI AYYAPPA NAGAR (JUNCTION SRI AYYAPPA NAGAR 2ND MAIN ROAD AND 1ST MAIN ROAD) IN DIV 127, UNIT-29,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/26474,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,995000,"DEMOLISHION AND CONSTRUCTION OF STORM WATER DRAIN AT SRINIVASA NAGAR (JUNCTION OF SRINIVASA NAGAR MAIN ROAD) IN DIV 127, UNIT-29,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26488,Buildings,Completed,NK-KODAMBAKKAM,137,960000,"SUPPLY OF BOBCAT S 130 (IMPORTED) FOR RENTAL BASIS IN UNIT 28, DIV 131,137, 138 AND 139 IN ZONE 10",Own Sources,10,2015-16,2017-18 NK/2015-16/26493,Buildings,Completed,NK-KODAMBAKKAM,136,960000,"SUPPLY OF BOBCAT S 130 (IMPORTED) FOR RENTAL BASIS IN UNIT 30, DIV 136,140, 141 AND 142 IN ZONE 10",Own Sources,10,2015-16,2017-18 NK/2015-16/26544,Buildings,Completed,NK-KODAMBAKKAM,130,967000,"Outsourcing , Sweeping and Toilet Cleaning Work to Urban Primary Health Center (UPHC) at Rajangam Mathya Veethy in Dn. 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/26546,Buildings,Completed,NK-KODAMBAKKAM,130,679000,"Providing Security Arrangements (Day and Night Watch Man for One Year) to Urban Primary Health Center (UPHC) at Rajangam Mathya Veethy in Dn. 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/26550,Buildings,Completed,NK-KODAMBAKKAM,139,154000,"REMOVAL OF GARBAGE AND REMOVAL OF JAFFERKHANPET CANAL SILT USING PRIVATE POCLAIN FOR FLOOD WORK 2015 IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/26578,Buildings,Completed,NK-KODAMBAKKAM,139,972000,CONSTRUCTION OF COMPOUND WALL ON SAIDAPET BURIYAL GROUND(WEST SIDE) AT GANGAI AMMAN KOVIL STREET IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2018-19 NK/2015-16/26617,Buildings,Completed,NK-KODAMBAKKAM,138,999000,"PROVIDING SECURITY GUARDS FOR AMMA UNAVAGAM IN DN-131,137 & 138,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26620,Buildings,Completed,NK-KODAMBAKKAM,136,999000,"PROVIDING SECURITY GUARDS FOR AMMA UNAVAGAM IN DN-136,140 & 141,U-30,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26622,Buildings,Completed,NK-KODAMBAKKAM,142,668000,"PROVIDING SECURITY GUARDS FOR AMMA UNAVAGAM IN DN-139 & 142,U28 & 30,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26623,Buildings,Completed,NK-KODAMBAKKAM,134,999000,"PROVIDING SECURITY GUARDS FOR AMMA UNAVAGAM IN DN-132,133 & 134,U-31,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26628,Buildings,Completed,NK-KODAMBAKKAM,135,999000,"PROVIDING SECURITY GUARDS FOR AMMA UNAVAGAM IN DN-130 & 135,U-29 & 31,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26642,Buildings,Completed,NK-KODAMBAKKAM,127,999000,"PROVIDING SECURITY GUARDS FOR AMMA UNAVAGAM IN DN-127,128 & 129,U-29,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26760,Buildings,Completed,NK-KODAMBAKKAM,134,999000,"PROVIDING SECURITY GUARDS FOR ELECTRICAL SUB STATION IN DN-128,134,135 & 136 ,U-29,30 & 31,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26764,Buildings,Completed,NK-KODAMBAKKAM,131,960000,"DEMOLITION AND RECONSTRUCTION OF COMPOUND WALL AT RANI ANNA NAGAR (BLOCK- 23 & AVM BURIAL GROUND) , PROVIDING AND LAYING PAVER BLOCK RANIANNA NAGAR (BLOCK NO-37) IN DN-131,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/26771,Buildings,Completed,NK-KODAMBAKKAM,138,189000,"OUT SOURCING OF PRIVATE WORKERS FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT MGR NAGAR ANNA MAIN ROAD IN DN-138,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26772,Buildings,Completed,NK-KODAMBAKKAM,136,94800,"PROVIDING HOUSE KEEPING ARRANGEMENT FOR GOVERNMENT SCHOOL RAMANATHAN STREET IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2015-16,2018-19 NK/2015-16/26878,Roads,Completed,NK-KODAMBAKKAM,130,600000,"Enganging private Auto with 6 private labours to Dn-130, U-29, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/26932,Buildings,Completed,NK-KODAMBAKKAM,134,874000,"PAINTING WORK FOR EXISTING CORPORATION COMMUNITY HALL AT DR.AMBDKAR ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/26940,Buildings,Completed,NK-KODAMBAKKAM,133,475000,"PROVIDING MAN POWER FOR HOUSE KEEPING WORK AT CORPORATION SCHOOLS & TOILETS ( , C.P.S. & C.H.S. PULIYUER, ) IN DN-,133, , U-31, Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/27179,Buildings,Completed,NK-KODAMBAKKAM,134,940000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING CORPORATION COMMUNITY HALL T DR.AMBEDKAR ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27192,Parks,Completed,NK-KODAMBAKKAM,127,644000,"ANNUAL MAINTENANCE OF PARK AT OSR 9 TO 12 OSR SAF GAMES VILLAGE FOR KOYAMBEDU IN DIV-127, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27193,Parks,Completed,NK-KODAMBAKKAM,127,775000,"ANNUAL MAINTENANCE OF PARK AT OSR 5 TO 8 OSR SAF GAMES VILLAGE FOR KOYAMBEDU IN DIV-127, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27198,Parks,Completed,NK-KODAMBAKKAM,127,775000,"ANNUAL MAINTENANCE OF PARK AT OSR 1 TO 4 OSR SAF GAMES VILLAGE FOR KOYAMBEDU IN DIV-127, U-29, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27272,Buildings,Completed,NK-KODAMBAKKAM,134,679000,"Providing Security Guards for Maternity Hospital at Arcot Road in Dn-134, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/27273,Buildings,Completed,NK-KODAMBAKKAM,134,967000,"Out Sourcing of Private Labours for Maternity Hospital at Arcot Road in Div-134, U-31, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/27329,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,987000,"IMPROVEMENTS TO STROMWATERDRAIN AT ASHOKNAGAR 57,58,59,60, AND 61ST STREET AND BALAKRISHNA STREET IN DN 133 ,UNIT 31 ZONE 10",Own Sources,10,2015-16,2017-18 NK/2015-16/27450,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NOS. FOR DIVISION WORK IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/2746,Roads,Completed,NK-KODAMBAKKAM,129,980000,"IMPROVEMENTS TO FOOT PATH AT POSTALCOLONY 4 TH STREET, RAM COLONY, BALAKRISHNAN STREET, Dr. SUBBARAYAN NAGAR 5 TH AND 8TH STREET IN DN 133 , UNIT 31 ZONE 10",Own Sources,10,2015-16,2016-17 NK/2015-16/27510,Roads,Completed,NK-KODAMBAKKAM,131,460000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM PERIYAR STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/27581,Footpath,Completed,NK-KODAMBAKKAM,135,989000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AT SRINIVASA(I) STREET, VIVEGANATHAPURAM 1ST STREET AND VINAYAGAM STREET IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/27583,Roads,Completed,NK-KODAMBAKKAM,127,989000,"LAYING OF CEMENT CONCRETE USING M40 GRADE ROAD AT SAF GAMES VILLAGE AND PAJANAI KOVIL STREET (LANES) IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/27627,Parks,Completed,NK-KODAMBAKKAM,138,200000,"IMPROVEMENT OF PARK AND GREENARY ARRANGEMENT AT BHARATHIDASAN COLONY 6TH STREET,KKNAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/27646,Buildings,Completed,NK-KODAMBAKKAM,140,667000,"IMPROVEMENTS TO THE OFFICE FOR ARASU CABLE TV AND REPAIRS TO THE AMMA UNAVAGAM IN DN-140,UT-30,ZONE-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/27699,Buildings,Completed,NK-KODAMBAKKAM,142,991000,"MAINTENANCE AND REPAIRING OF THE COMPRESSION MOTOR,JET MOTOR AND OTHER WORKS AT CGHSS SCHOOL, EOC HOSPITAL AND DHOBIKANA IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/27730,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT SUBRAMANIYA MUDHALI STREET(REACH-1)1 IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27733,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT SUBRAMANIYA MUDHALI STREET(REACH-2) IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27734,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT KARNEESWARAR KOIL STREET(REACH-1) IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27736,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT KARNEESWARAR KOIL STREET(REACH-2) IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27744,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT K.P KOIL STREET(REACH-2) IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27747,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT K.P KOIL STREET(REACH-1) IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/27750,Roads,Completed,NK-KODAMBAKKAM,142,893000,"LAYING CEMENT CONCRETE ROAD AT KAVARAI STREET(REACH-1) IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/2776,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,920000,IMPROVEMENTS TO STROM WATER DRAN AT N.S.K SALAI (BOTH SIDES ) IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/2781,Roads,Completed,NK-KODAMBAKKAM,131,868000,"LAYING OF SPEED BREAKERS AT RANI ANNA NAGER,A.P.PATRO SALAI AND VARIOUS STREETS IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/27826,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,465000,"IMPROVEMENT WORKS FOR AMMA UNAVAGAM , MANHOLE DOOR RAISING WORK , SCHOOL RAMPS AND NNMP SHED COMPOUND WALL IN DIV-140, U-30,Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/27840,Roads,Completed,NK-KODAMBAKKAM,131,885000,"SUPPLY OF MINI LORRY (TATA ACE ) UNDER DAILY HIRING INCLUDING 6 LABOURS FOR REMOVAL OF DEBRIS AND CLEANING THE WATER TABLE AND FOOTPATH IN BUS ROUTE AND INTERIOR ROAD IN DIV-131, U-28, Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/27920,Buildings,Completed,NK-KODAMBAKKAM,140,311000,"ANNUAL MAINTENANCE OF ROAD SIDE PARK AT ELLAIAMMAN KOIL STREET (KITTU PARK) (1 YEAR) IN DIV-140, U-30, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/27923,Bridges,Completed,NK-KODAMBAKKAM,140,930000,"SUPPLYING AND FIXING REFLECTOR AND LAYING THERMOPLASTIC AT K.R.KOIL STREET AND VARIOUS STREETS IN DIV-140, U-30, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/28169,Buildings,Completed,NK-KODAMBAKKAM,132,810000,"IMPROVEMENTS TO NNMP SHED AT ASHOKNAGAR 1ST STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28328,Parks,Completed,NK-KODAMBAKKAM,131,413000,"Annual Maintenance of Ranianna nagar park and play field in Dn 131, U 28,Zone-X.(Employed qualified Diploma Horticulturist only)",Own Sources,10,2015-16,2018-19 NK/2015-16/28344,Roads,Completed,NK-KODAMBAKKAM,130,990000,Improvement to SWD at Various Street in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28346,Roads,Completed,NK-KODAMBAKKAM,130,780000,Providing Transformer D wart wall at various street in DN-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28347,Roads,Completed,NK-KODAMBAKKAM,130,955000,Attending patch work using RMC 40 at Vijaya cross street in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28354,Parks,Completed,NK-KODAMBAKKAM,128,906000,"Providing Security Arrangements (Day and Night Watch Man for One Year) to OSR Land Park and Play fields at Vembuli amman Koil Street, Indra Nagar, Lambert Nagar and Annaji Park in Dn. 128, Unit- 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/28355,Roads,Completed,NK-KODAMBAKKAM,130,995000,Attending patch work using RMC 40 at Alagiri nagar 1st street ( CH 120-180 ) in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28356,Roads,Completed,NK-KODAMBAKKAM,130,990000,Attending patch work using RMC 40 at Alagiri nagar 1st street ( CH 180-225 ) in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28360,Roads,Completed,NK-KODAMBAKKAM,130,988000,Attending patch work at various street in Dn-130 u-29 z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28361,Roads,Completed,NK-KODAMBAKKAM,130,880000,Dismantling of SWD top slab and Providing wet mix macadam at Alagiri nagar 1st street in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28362,Roads,Completed,NK-KODAMBAKKAM,130,994000,Attending patch work using RMC 40 at Alagiri nagar 1st street ( CH 0-60 ) in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28363,Roads,Completed,NK-KODAMBAKKAM,130,995000,Attending patch work using RMC 40 at Alagiri nagar 1st street ( CH 60-120 ) in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28365,Roads,Completed,NK-KODAMBAKKAM,130,400000,Providing and Laying wet mix macadam at Vijaya cross street in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28368,Roads,Completed,NK-KODAMBAKKAM,130,420000,Providing and laying wet mix macadam at Alagiri nagar 6th street in Dn-130 U -29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28369,Roads,Completed,NK-KODAMBAKKAM,130,999000,"Providing Natural manure garden ( west side ) at CMS Building in Dn 130,U 29,Z 10",Own Sources,10,2015-16,2018-19 NK/2015-16/28374,Roads,Completed,NK-KODAMBAKKAM,130,600000,"Enganging private Auto with 6 private labours to Dn-130, U-29, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28375,Parks,Completed,NK-KODAMBAKKAM,128,340000,"Providing Security Arrangements (Day and Night Watch Man for One Year) to Burial Ground at Erikkarai Street in Dn. 128, Unit- 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/28390,Roads,Completed,NK-KODAMBAKKAM,130,999000,"Raising the Road Level using Wet Mix Macadam at Various Street for Flood Affected Area in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2019-20 NK/2015-16/28391,Buildings,Completed,NK-KODAMBAKKAM,130,494000,"Outsourcing and Sweeping Work in CMS at Amman Koil Street, Vadapalani and in 16th Ceremony Hall at South Mada Street in Dn. 130, Unit- 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/28434,Roads,Completed,NK-KODAMBAKKAM,128,600000,"Enganging private Auto with 6 private labours to Dn-128, U-29, Zone-10",Own Sources,10,2015-16,2019-20 NK/2015-16/28437,Parks,Completed,NK-KODAMBAKKAM,128,745000,"Improvements to the Park at CRR Puram phase 4 park in Div-128, Unit-29, Zone-10",Own Sources,10,2015-16,2019-20 NK/2015-16/28447,Roads,Completed,NK-KODAMBAKKAM,128,990000,Attending patch work using RMC 40 at Various street in Dn-128 u-29 z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28459,Parks,Completed,NK-KODAMBAKKAM,128,635000,"Improvements to the Park at Lakshmi nagar park in Div-128, Unit-29, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28461,Parks,Completed,NK-KODAMBAKKAM,128,750000,"Improvements to the Park at Annaji nagar park in Div-128, Unit-29, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28472,Buildings,Completed,NK-KODAMBAKKAM,142,980000,"Providing Housekeeping services for EOC Hospital in Jeenis Road Saidapet at Dn142,Unit-30 ,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28473,Buildings,Completed,NK-KODAMBAKKAM,138,375000,"Out sourcing of Private workers for Cleaning Schools at CHSS MGR Nagar Govindasamy Street and in Dn.138,Unit-28,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28475,Buildings,Completed,NK-KODAMBAKKAM,137,226000,"Providing Security Arrangements (Day and Night) for CHS at Kamaraj Street M.G.R. Nagar in Div 137,Unit-28,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28476,Buildings,Completed,NK-KODAMBAKKAM,138,226000,"Providing Security Arrangements (Day and Night) for CHSS Govindasamy Street in Dn138, Unit-28,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28477,Buildings,Completed,NK-KODAMBAKKAM,136,226000,"Providing Security Arrangements for CMS Prakasam School in Dn136, Unit-30,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28479,Buildings,Completed,NK-KODAMBAKKAM,136,233000,"Out Sourcing of Private workers for Cleaning schools at CMS Prakasam Street in Dn.136, Unit-30,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28483,Roads,Completed,NK-KODAMBAKKAM,129,996000,Attending patch work using RMC 40 at Shakthi vinayagar koil street CH 0-90 ma in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28485,Roads,Completed,NK-KODAMBAKKAM,129,760000,Attending patch work using RMC 40 at Kanara bank colony canal road CH 75-125 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28486,Roads,Completed,NK-KODAMBAKKAM,129,997000,Attending patch work using RMC 40 at Thivakar 3rd street s in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2016-17 NK/2015-16/28487,Roads,Completed,NK-KODAMBAKKAM,129,997000,Attending patch work using RMC 40 at Ponniamman koil street CH 0-90 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28488,Roads,Completed,NK-KODAMBAKKAM,129,996000,Attending patch work using RMC 40 at Ponniamman koil street CH 90 - 170 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2019-20 NK/2015-16/28489,Roads,Completed,NK-KODAMBAKKAM,129,998000,Attending patch work using RMC 40 at SK Babu street in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28490,Roads,Completed,NK-KODAMBAKKAM,129,998000,Attending patch work using RMC 40 at Shakthi vinayagar koil street CH 90-170 m in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28492,Roads,Completed,NK-KODAMBAKKAM,137,395000,"ATTENDING CEMENT CONCRETE PATCH WORK AT GANESAN STREET RAJIV GANDHI NAGAR IN DIV-137, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/28494,Roads,Completed,NK-KODAMBAKKAM,129,996000,Attending patch work using RMC 40 at mageeth street ( CH 100-153) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28495,Roads,Completed,NK-KODAMBAKKAM,129,999000,Attending patch work using RMC 40 at mageeth street ( CH 0 - 50 ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28497,Roads,Completed,NK-KODAMBAKKAM,137,560000,"LAYING OF CEMENT CONCRETE ROAD AT M.G.R.CROSS STREET AND RAISING MANHOLE DOOR AT RAJIV GANDHI STREET , MGR STREET AND KAMARAJ STREET IN DIV-137, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/28498,Roads,Completed,NK-KODAMBAKKAM,129,997000,Attending patch work using RMC 40 at mageeth street ( CH 50 - 100 ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28503,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,760000,"CONSTRUCTION OF STORM WATER DRAIN AT VIJAYARAGAVAPURAM M.G.R. STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/28519,Roads,Completed,NK-KODAMBAKKAM,129,990000,Attending patch work using RMC 40 at Thasaratha puram 5th street ( CH 0 - 80 ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28521,Roads,Completed,NK-KODAMBAKKAM,129,650000,Attending patch work using RMC 40 at Thasaratha puram 5th street ( CH 80-120 ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28522,Roads,Completed,NK-KODAMBAKKAM,129,860000,Attending patch work using RMC 40 at Vivekanantha street canal road in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2016-17 NK/2015-16/28524,Roads,Completed,NK-KODAMBAKKAM,130,800000,Dismantling SWD Top slab and Providing wet mix macadam at ponnammal street and kumaran colony 7th street in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28525,Roads,Completed,NK-KODAMBAKKAM,130,470000,Dismantling SWD Top slab and Providing wet mix macadam at kumaran colony 8th street in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28526,Roads,Completed,NK-KODAMBAKKAM,130,960000,Providing Transformer D wart walls at Alagiri nagar main road and Nerkundram pathai in Dn-130 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/28531,Buildings,Completed,NK-KODAMBAKKAM,141,483000,"Out sourcing of Private work for Public Toilet cleaning at CIT Nagar, 4th Cross Street and South West Boag Road in Dn 141,Unit-30,Zone-10",Own Sources,10,2015-16,2019-20 NK/2015-16/28532,Buildings,Completed,NK-KODAMBAKKAM,142,505000,"Out Sourcing of Private workers for Jeenis Road and Vegetable Market Public Conveyance Cleaning at Dn.142, Unti-30, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28533,Buildings,Completed,NK-KODAMBAKKAM,142,505000,"Out Sourcing of Private workers for Abdul Razack Road and Thideer Nagar Public Conveyance Cleaning at Dn.142, Unti-30, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28537,Buildings,Completed,NK-KODAMBAKKAM,138,480000,"Out Sourcing of Private Workers for Public Toilet Cleaning at Ashok Pillar Salai and 60' Feet Road in Dn 138, Unit-28,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28538,Buildings,Completed,NK-KODAMBAKKAM,138,480000,"Out Sourcing of Private Workers for Public Toilet Cleaning at Govindasamy Street and Pachaiyappan Street in Dn.138, Unit-28,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28634,Buildings,Completed,NK-KODAMBAKKAM,139,983000,"ENGAGING PRIVATE AUTO VEHICLE WITH 6 PRIVATE LABORS FOR 10 MONTHS TO DN-139, UNIT-28, ZONE-X.",Own Sources,10,2015-16,2018-19 NK/2015-16/28726,Buildings,Completed,P-Parks and Playfields,137,998000,"Improvements to Pathway at 8th Sector Park (North Side) in Dn.137, Unit-28, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28728,Buildings,Completed,P-Parks and Playfields,137,998000,"Improvements to Pathway at 8th Sector Park (South Side) in Dn.137, Unit-28, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28729,Buildings,Completed,NK-KODAMBAKKAM,137,690000,"Providing Compound Wall Additional Fencing ,Gate Pillars , Play apparatus and Improvements to Play Ground at 61st Street ,10th sector in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/28732,Buildings,Completed,P-Parks and Playfields,137,527000,"Providing Water Supply arrangements , Play Apparatus at 8th Sector Park in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28736,Buildings,Completed,P-Parks and Playfields,137,998000,"Improvements to Tennis Court and Yogha Mandapam at 8th Sector Park in Dn.137,Unit-28, Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/28829,Parks,Completed,NK-KODAMBAKKAM,140,947000,"Providing Art works in the Park at kodambakkam road in Division-140,Unit-30,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/28871,Electrical,Completed,NK-KODAMBAKKAM,138,369600,Provision of 18 Nos of 3mtr lamp post with 2x18w CFL and 2 nos of 6 mtr Lamp Post with 90W - 120W LED Fitting in the Road side Park at Bharathidasan colony 4 TH Street Division 138 Div. Zone X,Own Sources,10,2015-16,2018-19 NK/2015-16/28971,Roads,Completed,NK-KODAMBAKKAM,131,985000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 1st STREET(FROM P.V.RAJAMANNAR SALAI) IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/28982,Roads,Completed,NK-KODAMBAKKAM,131,985000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 1st (FROM VIJAYARAGAVAPURAM 3rd STREET) IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/29006,Buildings,Completed,NK-KODAMBAKKAM,137,927000,"Providing Additional Improvements to Burial Ground at Errikarai Street in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/29018,Buildings,Completed,NK-KODAMBAKKAM,140,621000,"PROPOSED CONSTRUCTION OF CRECHE BUILDING AT CMS METTUPALAYAM (SCHOOL ROAD) DIV-140, U-30,Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/29019,Buildings,Completed,NK-KODAMBAKKAM,140,930000,"SUPPLYING AND FIXING REFLECTOR AND LAYING THERMOPLASTIC AT ADHIKESAVA PERUMAL KOIL STREET AND VARIOUS STREETS IN DIV-140, U-30, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/29021,Buildings,Completed,NK-KODAMBAKKAM,140,464000,"IMPROVEMENT WORKS FOR PARK AT ELLAIAMMAN KOIL STREET IN DIV-140, U-30,Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/29022,Buildings,Completed,NK-KODAMBAKKAM,140,2484000,"INSTALLATION OF WATER TREATMENT PLANT,MAINTENANCE AND OPERATION OF THE PLANTS (AMMA KUDINEER) IN DIVISION-140, UNIT-30, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/29023,Buildings,Completed,NK-KODAMBAKKAM,140,875000,"IMPROVEMENTS WORKS FOR HEALTH POST AT GOVINDAN ROAD AND CHSS, CMS AT VARIOUS STREETS IN DIV-140, U-30,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/29027,Buildings,Completed,NK-KODAMBAKKAM,140,692000,"RELAYING OF ROAD WITH CEMENT CONCRETE (M20 GRADE) AT JAYACHANRAN LANE IN DIV-140, U-30, Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/29039,Roads,Completed,NK-KODAMBAKKAM,129,340000,Attending patch work using RMC40 at Sountharajan 3rd croos street in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29060,Buildings,Completed,NK-KODAMBAKKAM,129,980000,"Providing & laying wet mix macadam at Ekambaram street, Bangaru street & vittalachari street in Dn-129 U-29 Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/29074,Buildings,Completed,NK-KODAMBAKKAM,129,980000,Attending pacth work using RMC40 at Ekambram street in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29076,Roads,Completed,NK-KODAMBAKKAM,129,960000,Attending pacth work using RMC40 Bangaru street in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29144,Buildings,Completed,NK-KODAMBAKKAM,138,375000,"Out sourcing of Private workers for Cleaning Schools at CPS MGR Nagar Govindasamy Street in Dn.138,Unit-28,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/29145,Buildings,Completed,NK-KODAMBAKKAM,137,960000,"Construction of Multipurpose Hall at Anna Main Road in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2017-18 NK/2015-16/29148,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,923000,"Outsourcing of Public Toilet at Samiyaar Thottam,Salavaiyar Colony,Gothamedu and Kothavalchavadi Street in Division-142,Unit-30,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/29206,Buildings,Completed,NK-KODAMBAKKAM,129,978000,Attending pacth work using RMC40 Vittalachari cross street in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29221,Buildings,Completed,NK-KODAMBAKKAM,137,586000,"Electrical and Improvements to Multipurpose Hall at Anna Main Road in Dn.137,Unit-28,Zone-10",Own Sources,10,2015-16,2017-18 NK/2015-16/29301,Roads,Completed,NK-KODAMBAKKAM,131,425000,"CONSTRUCTION OF STORM WATER DRAIN AT SIVALINGAPURAM F-BLOCK IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/29302,Roads,Completed,NK-KODAMBAKKAM,131,440000,"ATTENDING CEMENT CONCRETE PATCH WORK AND RAISING DOOR SOB SALAI ,SIVALINGAPURAM C,D,F,J,L BLOCK,VIJAYARAGAVAPURAM 5th CROSS STREET AND VARIOUS STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/29303,Roads,Completed,NK-KODAMBAKKAM,131,744000,"LAYING CEMENT CONCRETE ROAD AT KANNIGAPURAM 3rd STREET (FROM AVM BURIAL GROUND) IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/29315,Buildings,Completed,NK-KODAMBAKKAM,134,755000,"CONSTRUCTION OF 16TH CEREMONY HALL AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/29318,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,890000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VALLIAMMAL GARDEN MAIN ROAD (CH 0-100m) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/29326,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,890000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VALLIAMMAL GARDEN MAIN ROAD (CH 100-200m) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/29339,Footpath,Completed,NK-KODAMBAKKAM,135,990000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING FOOTPATH AT BRINDAVAN STREET (FROM THAMBAIAH ROAD TO DURAISAMY SUBWAY) IN DN-135,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/29340,Parks,Completed,NK-KODAMBAKKAM,139,995000,"PROVINDING AND LAYING OF GRANITE IN PILLAIYAR KOVIL STREET PARK AT DIV-139,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/29359,Roads,Completed,NK-KODAMBAKKAM,142,992000,"PROVIDING PLATFORM AT SOUTH SIDE OF EAST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/29375,Buildings,Completed,NK-KODAMBAKKAM,141,996000,"PROVIDING IRON SHEET FOR YARD WALL AT MODEL HOUSE ROAD IN DIVISION - 141, UNIT - 30, ZONE -10.",Own Sources,10,2015-16,2018-19 NK/2015-16/29381,Buildings,Completed,NK-KODAMBAKKAM,141,985000,"IMPROVEMENTS TO FLOOD AFFECTED CHENNAI HIGH SCHOOL BUILDING AT CIT NAGAR 4 th MAIN ROAD IN DIVISION- 141, UNIT -30, ZONE -10",Own Sources,10,2015-16,2019-20 NK/2015-16/29386,Parks,Completed,NK-KODAMBAKKAM,127,487000,Supplying and fixing of GYM equipment at Brindavanam nagar play field maligai street in Dn-127 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29387,Parks,Completed,NK-KODAMBAKKAM,127,920000,"Providing flooring , benches and painting of compound wall and grill at Brindavanam nagar maligai street play field in Dn-127 U-29 Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/29444,Roads,Completed,NK-KODAMBAKKAM,136,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DN-141, UNIT-30, ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/29448,Roads,Completed,NK-KODAMBAKKAM,136,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR FOOD WASTE COLLECTION , MARKET WASTE COLLECTION AND GARDEN WASTE COLLECTION IN DN-141 & DN - 136, UNIT-30, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/29477,Buildings,Completed,NK-KODAMBAKKAM,141,760000,"OPERATION AND MAINTENANCE FOR ELECTRICAL CREMATORIUM AT KANNAMAPET BURIAL GROUND IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2015-16,2018-19 NK/2015-16/29494,Buildings,Completed,NK-KODAMBAKKAM,139,326000,IMPROVEMENT WORK ON AMMA UNAVAGAM AND BARRICATING FOR FALLEN SAIDAPET BURIYAL GROUND COMPOUND WALL (WEST SIDE) NEAR AMMA UNAVAGAM IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/29505,Buildings,Completed,NK-KODAMBAKKAM,139,352000,IMPROVEMENT WORK IN E SEVA ROOM AT GANGAI AMMAN KOVIL STREET(NEAR SAIDAPET BURIYAL GROUND) IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/29507,Buildings,Completed,NK-KODAMBAKKAM,139,128000,SUPPLYING AND LAYING OF STONE DUST FOR PLAY GROUND R.R COLONY 1ST LINK STREET IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/29540,Buildings,Completed,NK-KODAMBAKKAM,137,262000,"IMPROVEMENT TO THE STAGE IN CHSS AT ERIKARAI STREET IN DN-137,U-28,ZO-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/29721,Roads,Completed,NK-KODAMBAKKAM,130,642000,"Raising and Leveling of the road by using GSB and WMM at Gangaiamman Colony 1st Street in Dn. 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2016-17 NK/2015-16/29722,Roads,Completed,NK-KODAMBAKKAM,130,996000,"Laying of Bituminous Road using Paver Machine at Kumaran Colony 9th Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2017-18 NK/2015-16/29726,Roads,Completed,NK-KODAMBAKKAM,130,998000,"Laying of Bituminous Road using Paver Machine at Kumaran Colony 7th Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2017-18 NK/2015-16/29781,Roads,Completed,NK-KODAMBAKKAM,129,990000,Attending patch work using RMC 40 at Aranganathan street in Dn-129 u-29 z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29786,Roads,Completed,NK-KODAMBAKKAM,129,840000,Attending patch work using RMC 40 at Purushothamman street in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29787,Roads,Completed,NK-KODAMBAKKAM,129,995000,Attending patch work using RMC 40 at Jeeva street CH 0-55 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29789,Roads,Completed,NK-KODAMBAKKAM,129,985000,Attending patch work using RMC 40 at Jeeva street CH 55-110 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29791,Roads,Completed,NK-KODAMBAKKAM,129,995000,Attending patch work using RMC 40 at Anna street CH 0-55 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29792,Roads,Completed,NK-KODAMBAKKAM,129,980000,Attending patch work using RMC 40 at Anna street CH 55 - 110 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29794,Roads,Completed,NK-KODAMBAKKAM,129,990000,Attending patch work using RMC 40 at Anna street CH 110 - 160 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29796,Roads,Completed,NK-KODAMBAKKAM,129,998000,Attending patch work using RMC 40 at Kannaiya street CH 55 - 110 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29802,Roads,Completed,NK-KODAMBAKKAM,127,950000,Painting of Kerb stones ( OSR 1 to 12) at SAF Games Village all park in Dn-127 U-29 z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29804,Parks,Completed,NK-KODAMBAKKAM,127,666000,Painting work for Jai nagar park compound wall and grill painting in Dn-127 U-29 z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/29807,Roads,Completed,NK-KODAMBAKKAM,127,255000,"Providing Ramp at all Group bins and around Brindhavanam nagar ,roja street play field in Dn-127 U-29 z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/29815,Roads,Completed,NK-KODAMBAKKAM,130,950000,"Raising, Leveling and strengthening of the road at Amman Koil Street (West) in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/29818,Roads,Completed,NK-KODAMBAKKAM,130,867900,"Raising, Leveling and strengthening at Kumaran Colony 9th street (under MLA Scheme 2015-16)T.Nagar Constitution in Dn - 130, Unit - 29, Zone - X.",MLACDS,10,2015-16,2016-17 NK/2015-16/29822,Roads,Completed,NK-KODAMBAKKAM,130,849500,"Raising, Leveling and strengthening at Kumaran Colony 7th and 8th street (under MLA Schem 2015-16) T.Nagar Constitution in Dn - 130, Unit - 29, Zone - X.",MLACDS,10,2015-16,2016-17 NK/2015-16/29825,Roads,Completed,NK-KODAMBAKKAM,130,920300,"Raising, Leveling and strengthening at Bajanai Kil 1st Street and 1st Cross Street under (MLA Scheme 2015-16) T.Nagar Constitution in Dn - 130, Unit - 29, Zone - X.",MLACDS,10,2015-16,2016-17 NK/2015-16/29826,Roads,Completed,NK-KODAMBAKKAM,130,778000,"Raising, Leveling and strengthening of the road at Bajanai Koil 2nd Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2017-18 NK/2015-16/29830,Roads,Completed,NK-KODAMBAKKAM,130,808000,"Raising, Leveling and strengthening at Gangaiamman Koil Street and Rajanga madhiya Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2017-18 NK/2015-16/29831,Roads,Completed,NK-KODAMBAKKAM,130,789000,"Raising, Leveling and strengthening of the road at Ponnamal Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2017-18 NK/2015-16/29867,Buildings,Completed,NK-KODAMBAKKAM,137,999000,"PROVIDING SECURITY GUARDS FOR AMMA UNVAGAM (PART-II) IN DN-137,139 & 142 ,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/29922,Roads,Completed,NK-KODAMBAKKAM,130,858000,"Laying of Bituminous Road using Paver Finisher at Bajanai Koil 1st Street and 1st Cross Street under (MLA Scheme 2015-16) T.Nagar Constituency in Dn - 130, Unit - 29, Zone - X.",MLACDS,10,2015-16,2017-18 NK/2015-16/29956,Roads,Completed,NK-KODAMBAKKAM,130,805000,"Laying of Bituminous Road using Paver Finisher at Bajanai Koil 2nd Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/29958,Roads,Completed,NK-KODAMBAKKAM,130,830000,"Laying of Bituminous Road using Paver Finisher at Gangaiamman Koil Street and Rajanga Madhiya Veedhi Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2017-18 NK/2015-16/29969,Buildings,Completed,NK-KODAMBAKKAM,141,2484000,"Installation of Water Treatment Plant, Maintenance and Operation of the plants (Amma Kudineer) at CIT Nagar 4 th main Road in Division -141, Unit -30, Zone -10.",Own Sources,10,2015-16,2018-19 NK/2015-16/29972,Buildings,Completed,NK-KODAMBAKKAM,141,980000,"PROVIDING ELECTRICAL CONNECTION TO THE AMMA KUDINEER AND IMPROVEMENTS TO THE MOTOR , BOURWELL AND ELECTRICAL WORKS AFFECTED DUE TO THE MONSOON AT VARIOUS PLACES IN DIVISION-141,UT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/29991,Parks,Completed,NK-KODAMBAKKAM,139,998000,"CONSTRUCTION OF COMPOUND WALL FROM SUNDARAMOORTHY STREET IN PILLAYARKOVIL STREET PARK IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/29992,Parks,Completed,NK-KODAMBAKKAM,139,992000,"CONSTRUCTION OF PATH WAY,SUMP AND WATCHMEN ROOM IN PILLAYAR KOVIL STREET PARK IN AT DIV-139,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/29997,Parks,Completed,NK-KODAMBAKKAM,139,998000,"CONSTRUCTION OF COMPOUND WALL FROM JAFFERKHANPET MAIN ROAD SIDE IN PILLAYARKOVIL STREET PARK AT DIV-139,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/30001,Parks,Completed,NK-KODAMBAKKAM,139,997000,"CONSTRUCTION OF GAZEEBO AND KERB WALL AT PILLAIYAR KOVIL STREET PARK IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/30007,Parks,Completed,P-Parks and Playfields,138,916000,Improvements to Childern Play Space at Thiru nagar ganaoli st and V.M.Balakrishnan street in Dn 138 Unit 28Zone-X,Own Sources,10,2015-16,2017-18 NK/2015-16/30033,Electrical,Completed,NK-KODAMBAKKAM,139,154900,"Supply and Fixing of 3 nos (40-50)w , 2 nos of (90-120)w LED Fitting and other Electrification at West Jones Road burrial ground in Division 139, Zone-X",Own Sources,10,2015-16,2018-19 NK/2015-16/30069,Parks,Completed,NK-KODAMBAKKAM,132,980000,"ANNUAL MAINTENANCE OF 1ST AVENUE PARK AT ASHOK NAGAR IN DIV-132, U-31, Z-10 (QUALIFIED HORTICULTURIST ONLY)",Own Sources,10,2015-16,2018-19 NK/2015-16/30217,Buildings,Completed,NK-KODAMBAKKAM,134,663000,"ADDITION AND IMPROVEMENTS TO THE EXISTING GYM BUILDING AT KAMARAJAR COLONY SCHOOL CAMPUS IN DN-134, U-31, Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/30286,Roads,Completed,NK-KODAMBAKKAM,129,990000,"Repairs to Footpath at Arcot Road North Side ( CH 0 - 300 ) in Dn. 129, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30299,Roads,Completed,NK-KODAMBAKKAM,129,996000,"Repairs to Footpath at Arcot Road North Side ( CH 600 - 1000 ) in Dn. 129, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30301,Roads,Completed,NK-KODAMBAKKAM,129,995000,"Repairs to Footpath at Arcot Road South Side ( CH 0 - 500 ) in Dn. 129, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30303,Roads,Completed,NK-KODAMBAKKAM,129,990000,"Repairs to Footpath at Arcot Road South Side ( CH 500 - 1000 ) in Dn. 129, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30324,Footpath,Completed,NK-KODAMBAKKAM,127,996000,"Improvements to Footpath at Sayee nagar 1st main road west side CH ( 270 - 360 m ) in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/30326,Footpath,Completed,NK-KODAMBAKKAM,127,990000,"Attending patch work using RMC 40 at Thiruvalluvar street Mettukulam in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/30330,Roads,Completed,NK-KODAMBAKKAM,127,993000,"Attending patch work using RMC 40 at Burial Ground Road CH - 0 - 100 M in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2015-16,2019-20 NK/2015-16/30334,Roads,Completed,NK-KODAMBAKKAM,127,700000,"Laying of road using RMC 40 at Burial Ground Road CH - 200 - 250 M in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2015-16,2019-20 NK/2015-16/30335,Electrical,Completed,NK-KODAMBAKKAM,139,947000,"Supply and Erection of 17nos of 6 Mtr Lamp post Hot dip zinc galvanising with Double straight Bracket with 34 nos of (40-50)w at West Jones Road burrial ground in Division 139, Zone-X",Own Sources,10,2015-16,2018-19 NK/2015-16/30336,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,990000,"Improvement to SWD at Chinmaya nagar stage 1 , Kaveri street & Mahalingam street in Dn-127 U-29 Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/30346,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,950000,Improvement to SWD at Jai nagar & Velan cross street in Dn-127 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/30347,Roads,Completed,NK-KODAMBAKKAM,131,510000,"PROVIDING AND LAYING GRANITE FLOORING,ALUMINIUM COMPOSITE PANEL , AMMA KUDINEER AT RAJAMANNAR SALAI IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/30351,Roads,Completed,NK-KODAMBAKKAM,127,987000,"Providing and Laying wet mix macadam at Mettu kulam in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/30352,Roads,Completed,NK-KODAMBAKKAM,127,988000,"Providing and Laying wet mix macadam at Burial ground road in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/30413,Buildings,Completed,NK-KODAMBAKKAM,141,910000,"REMOVAL OF GARBAGE USING PRIVATE VEHICLE FOR FLOOD WORK 2015 IN DIV -136,140&141,UNIT-30,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/30453,Parks,Completed,NK-KODAMBAKKAM,136,460000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL ( NEAR WATER FOUNTAIN PATH WAY) AT NATESAN PARK ( VENKATNARAYANA ROAD) IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2015-16,2018-19 NK/2015-16/30458,Parks,Completed,NK-KODAMBAKKAM,127,620000,"ANNUAL MAINTENANCE OF PARK AT JAI NAGAR PARK-2 IN DN-127, U-29, Z-10.(Employed qualified horticulturist for one year only)",Own Sources,10,2015-16,2019-20 NK/2015-16/30459,Parks,Completed,NK-KODAMBAKKAM,127,740000,"ANNUAL MAINTENANCE OF PARK AT JAI NAGAR PARK-1, IN DN-127, U-29, Z-10.(Employed qualified horticulturist for one year only)",Own Sources,10,2015-16,2019-20 NK/2015-16/30474,Electrical,Completed,NK-KODAMBAKKAM,136,199800,"Electrification work at Chennai Higher Secondary school CIT Nagar, Kannammapet and Prakasam Road in div-136 and 141, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30477,Roads,Completed,NK-KODAMBAKKAM,130,732500,"Relaying of Bituminous road using Paver machine at Kumaran Colony 8th Street, (Under MLA Scheme 2015-16) T.Nagar Constituency in Dn - 130, Unit - 29, Zone - X.",MLACDS,10,2015-16,2016-17 NK/2015-16/30488,Buildings,Completed,NK-KODAMBAKKAM,139,484000,"SUPPLY AND INSTALLING SCRUBBING UNIT ACCESSORIES IN THE EXISTING GASIFIRE CREMATORIUM AT WEST SAIDAPET BURIAL GROUND IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/30524,Roads,Completed,NK-KODAMBAKKAM,134,990000,"LAYING CEMENT CONCRETE ROAD WITH M40 GRADE OF CONCRETE AT CRP GARDEN 2ND STREET(CH 0-65.00M) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/30604,Parks,Completed,NK-KODAMBAKKAM,139,249000,"PROVIDING GREENERY PLANTS TO PILLAIYAR KOVIL STREET PARK IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/30617,Buildings,Completed,NK-KODAMBAKKAM,136,467000,"MAINTENANCE OF AMMA CANTEEN, KANNADASAN STREET PC , PRAKASAM ROAD SCHOOL AND VARIOUS LOCATION IN DIVISION - 136, UNIT-30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/30652,Buildings,Completed,NK-KODAMBAKKAM,127,650000,"IMPROVEMENTS TO SIX ANGANVADIES IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/30658,Parks,Completed,NK-KODAMBAKKAM,127,230000,"BORING, SUPPLYING AND FIXING OF MOTOR FOR DIVISON OFFICE AT AVVAITHIRUNAGAR 1ST STREET IN DN-127, UNIT-29, ZONE10.",Own Sources,10,2015-16,2018-19 NK/2015-16/30660,Parks,Completed,NK-KODAMBAKKAM,127,991000,"PROVIDING STAINLESS STEEL HANDRAIL AT JAI NAGAR PARK IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/30663,Parks,Completed,NK-KODAMBAKKAM,127,988000,"PLANTING OF TREES AND PROVIDING RAIN SHED AT JAI NAGAR PARK IN DN-127, UNIT-29, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/30774,Roads,Completed,NK-KODAMBAKKAM,131,791000,"PROVIDING AND LAYING THERMOPLASTIC PAINT AND REFLECTOR AT BOBBILIRAJA SALAI,13th SECTOR 83,86,87,88,89,90,91,92, STREET,PANEER SELVAN SALAI,KODIKATHTHAKUMARAN AND T.S.LAKHSMANAN SALAI IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/30780,Roads,Completed,NK-KODAMBAKKAM,134,990000,"LAYING CEMENT CONCRETE ROAD USING M40 GRADE OF CONCRETE AT CRP GARDEN 2ND STREET(CH 65-130.00M) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/30781,Roads,Completed,NK-KODAMBAKKAM,134,999000,"LAYING CEMENT CONCRETE ROAD USING M40 GRADE OF CONCRETE AT CRP GARDEN 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/30785,Roads,Completed,NK-KODAMBAKKAM,134,999000,"LAYING CEMENT CONCRETE ROAD USING M40 GRADE OF CONCRETE AT CRP GARDEN 3RD STREET(CH 0-130.00M) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/30787,Roads,Completed,NK-KODAMBAKKAM,134,999000,"LAYING CEMENT CONCRETE ROAD USING M40 GRADE OF CONCRETE AT CRP GARDEN 4TH STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/30789,Roads,Completed,NK-KODAMBAKKAM,134,741000,"LAYING CEMENT CONCRETE ROAD USING M40 GRADE OF CONCRETE AT CRP GARDEN 3RD STREET (CH 130-170.00M) AND 4TH STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/30810,Buildings,Completed,NK-KODAMBAKKAM,127,990000,"PROPOSED CONSTRUCTION OF TOILET BLOCK FIRST FLOOR IN CHENNAI MIDDLE SCHOOL AT T.S.D NAGAR ARUMBAKKAM IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/30812,Buildings,Completed,NK-KODAMBAKKAM,127,992000,"PROPOSED CONSTRUCTION OF TOILET BLOCK SECOND FLOOR IN CHENNAI MIDDLESCHOOL AT T.S.D NAGAR ARUMBAKKAM IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/30860,Roads,Completed,NK-KODAMBAKKAM,130,972000,"Laying of BT Road using Mechanical Paver Finisher at Amman Koil Street West in DN. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2017-18 NK/2015-16/30861,Roads,Completed,NK-KODAMBAKKAM,130,805000,"Laying of BT Road using Mechanical Paver Finisher at Ponnammal Street in DN. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/30875,Electrical,Completed,NK-KODAMBAKKAM,133,373600,"Electrification of Chennai High Secondary school at N.S.K Salai,Puliyur, Kodambakkam in Div-133 Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30878,Electrical,Completed,NK-KODAMBAKKAM,134,395000,"Electrification of Chennai school at Ranagarajuram,Kamarajar colony,Puliyur Kodambakkam in Div-133,134 Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30914,Roads,Completed,NK-KODAMBAKKAM,130,860000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Kanniappa Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/30926,Roads,Completed,NK-KODAMBAKKAM,130,566000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at South Sivan Koil Street (East)(Part - II) in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/31023,Roads,Completed,NK-KODAMBAKKAM,136,590000,"ADDITIONAL ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO WITH PRIVATE LABOURS 6 NO FOR DIVISION WORK IN DIV-136, U-30, Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31054,Parks,Completed,NK-KODAMBAKKAM,131,237000,"ANNUAL MAINTENANCE FOR ARTIFICIAL FALLS AT SIVAN PARK IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31065,Roads,Completed,NK-KODAMBAKKAM,131,643000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 6th CROSS STREET IN DIV- 131,U-28,Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31076,Roads,Completed,NK-KODAMBAKKAM,131,828000,"LAYING CEMENT CONCRETE ROAD AT SIVALINGAPURAM 84th STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/31078,Footpath,Completed,NK-KODAMBAKKAM,139,2484000,"Installation of Water Treatment Plant, Maintenance and Operation of the plants(Amma Kudineer) in Div-139,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/31080,Parks,Completed,NK-KODAMBAKKAM,131,860000,"Supplying and fixing motors for borewell,Fountain etc in Sivan Park in Dn 131 Unit 28 Zone-X",Own Sources,10,2015-16,2018-19 NK/2015-16/31086,Parks,Completed,NK-KODAMBAKKAM,131,996000,Additional improvements to Fountain in Sivan Park in Dn 131 Unit 28 Zone-X,Own Sources,10,2015-16,2018-19 NK/2015-16/31093,Roads,Completed,NK-KODAMBAKKAM,131,754000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 2nd STREET (FROM VIJAYARAGAVAPURAM 5th STREET ) IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31095,Roads,Completed,NK-KODAMBAKKAM,131,754000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 2nd STREET (FROM VIJAYARAGAVAPURAM 1st STREET ) IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/31098,Roads,Completed,NK-KODAMBAKKAM,139,973000,"PROPOSED RELAYING OF ROAD USING BITUMINOUS CONCRETE AT R.R.COLONY EAST STREET DIV-139,UNIT-28,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/31191,Parks,Completed,NK-KODAMBAKKAM,140,995000,"CONSTRUCTION OF COMPOUND WALL GRILL FENCING WORK IN THE PARK AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/31193,Parks,Completed,NK-KODAMBAKKAM,140,950000,"PROVIDING THE PLAY APPARATUS IN PARK AT KODAMBAKKAM ROAD IN DIV-140,U-30,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/31197,Parks,Completed,NK-KODAMBAKKAM,140,989000,"CONSTRUCTION OF SKATING AREA AND FOOTPATH IN THE PARK AT KODAMBAKKAM ROAD PARK IN DIV-140,UNIT-30, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/31199,Parks,Completed,NK-KODAMBAKKAM,140,986000,"IMPROVEMENTS TO THE PARK BY PROVIDING GOOD EARTH TO THE PLAY AREA AND FOOTPATH AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/31213,Roads,Completed,NK-KODAMBAKKAM,130,680000,"Relaying of Bituminous Road using Paver Finisher at N.G.O. Colony 1st Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2016-17 NK/2015-16/31217,Roads,Completed,NK-KODAMBAKKAM,130,556000,"Leveling and Strengthening of Road at N.G.O. Colony 1st Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/31236,Roads,Completed,NK-KODAMBAKKAM,130,995000,"Strengthening, Leveling and Laying of Bituminous Road by using Paver Finisher at Bakthavatchalam Colony 2nd Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/31251,Footpath,Completed,NK-KODAMBAKKAM,142,985000,"PROVIDING PLATFORM AT NORTH SIDE OF EAST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/31253,Footpath,Completed,NK-KODAMBAKKAM,142,669000,"LAYING CEMENT CONCRETE ROAD AT SUBRAMANIASAMY KOIL EAST STREET IN DIVISION-142, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/31281,Footpath,Completed,NK-KODAMBAKKAM,127,470000,"Forming parking area at SAF Games Village in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/31282,Buildings,Completed,NK-KODAMBAKKAM,138,645000,"IMPROVEMENTS TO THE EXISTING ANGANVADI NO.8095 AT ANNA MAIN ROAD , IN DN138, UNIT 28, ZONE10.",Own Sources,10,2015-16,2019-20 NK/2015-16/31285,Electrical,Completed,NK-KODAMBAKKAM,127,199800,"Electrification work at chennai higher secondary school koyambedu in div 127,zone-X",Own Sources,10,2015-16,2018-19 NK/2015-16/31292,Roads,Completed,NK-KODAMBAKKAM,130,535000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Karumariamman Koil Street (Part - II) in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/31294,Electrical,Completed,NK-KODAMBAKKAM,128,199800,"Electrification work at chennai higher secondary school virugambakkm in div-128,zone-x.",Own Sources,10,2015-16,2018-19 NK/2015-16/31297,Roads,Completed,NK-KODAMBAKKAM,130,945000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Gangaiamman Koil Street (Part - I) in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/31299,Roads,Completed,NK-KODAMBAKKAM,130,940000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Gangaiamman Koil Street (Part - II) in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/31300,Roads,Completed,NK-KODAMBAKKAM,130,939000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Gangaiamman Koil Street (Part - III) in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/31317,Buildings,Completed,NK-KODAMBAKKAM,138,201000,"IMPROVEMENTS AND CONSTRUCTION OF COMPOUND WALL FOR ANGANVADI AT PAALAI STREET IN DN 138, UNIT 28, ZONE 10",Own Sources,10,2015-16,2016-17 NK/2015-16/31331,Buildings,Completed,NK-KODAMBAKKAM,139,849000,"CONSTRUCTION OF MULTI PURPOSE HALL AT R.R.COLONY 3RD STREET (NEAR AAVIN MILK BOOTH) IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/3140,Electrical,Completed,NK-KODAMBAKKAM,138,226000,"Work: Provision of 6 Nos 6 MTR LONG G.I OCTAGONAL STREET LAMP POST WITH 1MTR SINGLE BRACKET with 40W - 50W LED Fitting at Ganga Nagar in Division-138, Zone-X.",Own Sources,10,2015-16,2016-17 NK/2015-16/31404,Roads,Completed,NK-KODAMBAKKAM,130,866000,"Relaying of Road by using BC 40 mm thick with Paver Finisher at Gangaiamman Koil Street (Part - IV) in Dn. 130, Unit- 29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/31490,Footpath,Completed,NK-KODAMBAKKAM,133,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NOS. FOR DIVISION WORK IN DIVISION-133, UNIT-31 AND ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/31493,Footpath,Completed,NK-KODAMBAKKAM,135,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NOS. FOR DIVISION WORK IN DIVISION-135, UNIT-31 AND ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/31499,Roads,Completed,NK-KODAMBAKKAM,142,720000,"LAYING CEMENT CONCRETE ROAD AT SUBRAMANIASAMY KOIL WEST STREET IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/31501,Buildings,Completed,NK-KODAMBAKKAM,142,983000,"PROVIDING THE COMPOUND WALL IN UPHSC NORTH AND WEST SIDE AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31505,Buildings,Completed,NK-KODAMBAKKAM,142,989000,"PROVIDING THE COMPOUND WALL WITH SS WORK IN UPHSC EAST AND SOUTH SIDE AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31511,Buildings,Completed,NK-KODAMBAKKAM,142,988000,"PROVIDING THE COMPOUND WALL WITH GRANITE AND INTERLOCKING PAVER BLOCKS WORK IN UPHSC EAST AND SOUTH SIDE AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31708,Parks,Completed,NK-KODAMBAKKAM,142,910000,"IMPROVEMENTS TO THE PARK BY PROVIDING SKATING AREA AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31710,Parks,Completed,NK-KODAMBAKKAM,142,909000,"IMPROVEMENTS TO THE PARK AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31713,Road Cut,Completed,NK-KODAMBAKKAM,137,677000,ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE CMWSS BOARD AT 10TH SECTOR 64TH STREET IN DN 137 UNIT 28 ZONE 10.,Deposit Works,10,2015-16,2017-18 NK/2015-16/31721,Buildings,Completed,NK-KODAMBAKKAM,132,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NOS. FOR DIVISION WORK IN DIVISION-132, UNIT-31 AND ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/31735,Parks,Completed,NK-KODAMBAKKAM,131,2484000,"Installation of Water Treatment Plant, Maintenance and Operation of the plants (Amma Kudineer) at PT RAJAN SALAI ( SIVAN PARK ) in Div-131,U-28,Z-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31749,Parks,Completed,NK-KODAMBAKKAM,142,609000,"IMPROVEMENTS TO THE PARK AT OSR LAND IN THADIRATHINAM STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31790,Parks,Completed,NK-KODAMBAKKAM,142,901000,"IMPROVEMENTS TO THE PARK BY CONSTRUCTING COMPOUND WALL WORK AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/31821,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,995000,"IMPROVEMENTS TO STORM WATER DRAIN AT ALAGAMPERUMAL KOIL 1ST STREET IN DIV-130, U-29, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/31829,Buildings,Completed,NK-KODAMBAKKAM,132,295000,"CONSTRUCTION OF E-SEVA ROOM AT 9TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/31864,Buildings,Completed,NK-KODAMBAKKAM,132,980000,"IMPROVEMENTS TO EXISTING COMPOUND WALL AT 90TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/31931,Roads,Completed,NK-KODAMBAKKAM,141,975000,"LAYING OF SPEED BREAKERS AT SOUTH DHANDAPANI STREET AND VARIOUS STREETS IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/32077,Roads,Completed,NK-KODAMBAKKAM,142,970000,"LAYING CEMENT CONCRETE ROAD AT TANK SQUARE STREET FROM SUBRAMANIA MUDALI STREET TO KARNEESWARAR KOIL STREET IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/32079,Roads,Completed,NK-KODAMBAKKAM,142,425000,"LAYING CEMENT CONCRETE ROAD AT SEMBADA STREET FROM DOOR NO 52 TO V.S.MUDALI STREET IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/32080,Roads,Completed,NK-KODAMBAKKAM,142,843000,"LAYING CEMENT CONCRETE ROAD AT SEMBADA STREET FROM OTHAVADAI STREET TO DOOR NO 52 IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2015-16,2017-18 NK/2015-16/32125,Buildings,Completed,NK-KODAMBAKKAM,129,996000,Laying of the road using RMC 40 at Logaiya street Ch 0-75 in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/32128,Buildings,Completed,NK-KODAMBAKKAM,129,995000,Laying of the road using RMC 40 at Logaiha street CH 75-150 m in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/32133,Roads,Completed,NK-KODAMBAKKAM,129,996000,Laying of the road using RMC 40 at Kumaran colony 1st street ( ch 0-45 m ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/32134,Roads,Completed,NK-KODAMBAKKAM,129,995000,Laying of the road using RMC 40 at Kumaran colony 1st street ( ch 45-90 m ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/32136,Roads,Completed,NK-KODAMBAKKAM,129,995000,Laying of the road using RMC 40 at Kumaran colony 1st street ( ch 90 - 130 m ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/32148,Roads,Completed,NK-KODAMBAKKAM,129,990000,Laying of the road using RMC 40 at Kumaran colony 1st street ( ch 130 - 180 m ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/32149,Roads,Completed,NK-KODAMBAKKAM,129,994000,Laying of the road using RMC 40 at Kumaran colony 1st street ( ch 150 - 180 m ) in Dn-129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/32295,Roads,Completed,NK-KODAMBAKKAM,137,801000,SUPPLYING AND FIXING OF REFLECTORS AND LAYING OF THERMOPLASTIC PAINT AT T.K.BHANI STREET AND ANNAI SATHIYA NAGAR 11TH STREET AT VARIOUS STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/32296,Roads,Completed,NK-KODAMBAKKAM,137,801000,S/F OF REFLECTORS AND LAYING OF THERMOPLASTIC PAINT AT 10TH SECTOR 64TH STREET AND 10TH SECTOR 59TH STREET AT VARIOUS STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/32304,Roads,Completed,NK-KODAMBAKKAM,138,640000,"PROVIDING AND LAYING HOT APPLIED THERMOPLASTIC COMPOUND & SUPPLYING AND FIXING OF REFLECTERS AT VASUDEVAN NAGAR JAYABALAN STREET, AND VARIOUS STREET IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/32306,Roads,Completed,NK-KODAMBAKKAM,139,995000,"PROVIDING AND LAYING THERMOPLASTIC PLASTIC PAINT AND REFLECTICVE STUDS IN RR COLONY 2nd STREET AND VARIOUS STREETS IN DIV 139 , UNIT 28 , ZONE 10.",Own Sources,10,2015-16,2016-17 NK/2015-16/32310,Roads,Completed,NK-KODAMBAKKAM,138,890000,"PROVIDING AND LAYING HOT APPLIED THERMOPLASTIC COMPOUND & SUPPLYING AND FIXING OF REFLECTERS AT ANJUGAM NAGAR, AND VARIOUS STREET IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/32311,Roads,Completed,NK-KODAMBAKKAM,138,680000,"PROVIDING AND LAYING HOT APPLIED THERMOPLASTIC COMPOUND & SUPPLYING AND FIXING OF REFLECTERS AT SABTHAGIRI COLONY , AND VARIOUS STREET IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/32312,Buildings,Completed,NK-KODAMBAKKAM,138,900000,"IMPROVEMENTS WORKS TO CPS AT GOVINDASMY STREET, MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/32315,Buildings,Completed,NK-KODAMBAKKAM,138,935000,"CONSTRUCTION COMPOUND WALL AND OTHERS IMPROVEMENTS WORKS TO CPS AT GOVIDASAMY STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/32332,Buildings,Completed,NK-KODAMBAKKAM,138,375000,"IMPROVEMENT OF PC AT GOVINDASAMY STREET AND PACHAYAPPAN STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/32359,Roads,Completed,NK-KODAMBAKKAM,130,997000,"Strengthening and Relaying of Road by Paver Finsiher at Mannar 1st Street from Nerkundram Pathai in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/32360,Roads,Completed,NK-KODAMBAKKAM,130,995000,"Strengthening and Relaying of Road by Paver Finsiher at Mannar 1st Street from Thiru Nagar 1st Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2018-19 NK/2015-16/32362,Roads,Completed,NK-KODAMBAKKAM,130,654000,"Laying of road by using BC 40mm thick by Paver finisher at Gangai Amman colony 1st street DIV-130,UNIT-29,ZONE-X",Own Sources,10,2015-16,2016-17 NK/2015-16/32366,Roads,Completed,NK-KODAMBAKKAM,128,960000,"Strengthening and Laying of Road by using BC 40mm Thick by paver Finisher at Srinivasan Street from Elumalai Street in Dn - 128, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/32367,Roads,Completed,NK-KODAMBAKKAM,128,983000,"Strengthening and Laying of Road by using BC 40mm Thick by Paver Finisher at Srinivasan Street in Dn - 128, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/32392,Roads,Completed,NK-KODAMBAKKAM,130,995000,"Laying of Wet Mix Macadam at Gangaiamman Koil Street Dn-130,Unit-29,Zone-X",Own Sources,10,2015-16,2018-19 NK/2015-16/32394,Roads,Completed,NK-KODAMBAKKAM,129,949000,"Attending Patch Work for Flood Affected Roads in Dn. 129, Unit-29, Zone - X (Dhasarathapuram Main Road and Kaveri Rangan Nagar)",Own Sources,10,2015-16,2016-17 NK/2015-16/32397,Roads,Completed,NK-KODAMBAKKAM,129,747000,"Attending Patch Work for Flood Affected Roads in Dn. 129, Unit-29, Zone - X (MGR Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/32398,Roads,Completed,NK-KODAMBAKKAM,129,791000,"Attending Patch Work for Flood Affected Roads in Dn. 129, Unit-29, Zone - X (Khusaldass Street and KG Nair Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/32399,Roads,Completed,NK-KODAMBAKKAM,129,654000,"Attending Patch Work for Flood Affected Roads in Dn. 129, Unit-29, Zone - X (Duraiarasan Street)",Own Sources,10,2015-16,2016-17 NK/2015-16/32508,Parks,Completed,NK-KODAMBAKKAM,127,980000,"Providing Stage,foot path and improvements to park at SAF Games Village park 4 in Dn-127, U-29 ,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/32545,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,639000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AND STORM WATER DRAIN AT CORPORATION COLONY 1ST MAIN ROAD (60 HUTS) IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/32610,Roads,Completed,NK-KODAMBAKKAM,134,988000,"ATTENDING PATCH WORK USING BC 40MM THICK BY PAVER FINISHER AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/32710,Road Cut,Completed,NK-KODAMBAKKAM,137,638000,ATTENDING DEPOSIT WORK RESORATION OF ROAD CUT MADE CMWSSBOARD AT 10TH SECTOR 60TH STREET IN DN 137 UNIT 28 ZONE 10.,Deposit Works,10,2015-16,2016-17 NK/2015-16/32711,Road Cut,Completed,NK-KODAMBAKKAM,137,610000,ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE CMWSSBOARD AT 10TH SECTOR 62ST STREET IN DN 137 UNIT 28 ZONE 10.,Deposit Works,10,2015-16,2017-18 NK/2015-16/32712,Road Cut,Completed,NK-KODAMBAKKAM,137,660000,ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE CMWSSBOARD AT 10TH SECTOR 61nd STREET IN DN 137 UNIT 28 ZONE 10.,Deposit Works,10,2015-16,2017-18 NK/2015-16/32713,Road Cut,Completed,NK-KODAMBAKKAM,137,729000,ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE BY CMWSSBOARD AT 10TH SECTOR 63RD STREET & KANAGASABAI STREET IN DN 137 UNIT 28 ZONE 10.,Deposit Works,10,2015-16,2017-18 NK/2015-16/32716,Buildings,Completed,NK-KODAMBAKKAM,133,258000,"SUPPLYING AND FIXING R. O. PLANT TO CPS.,(PULIYUR) N.S.K. SALAI IN DIVISION-133, UNIT-31, ZONE-10. (UNDER T.NAGAR CONSTITUENCY MLA FUND 2015-16)",MLACDS,10,2015-16,2017-18 NK/2015-16/32717,Buildings,Completed,NK-KODAMBAKKAM,133,515000,"SUPPLYING AND FIXING R. O. PLANT TO C.H.S.S., (PULIYUR), N.S.K. SALAI IN DIVISION-133, UNIT-31, ZONE-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2015-16)",MLACDS,10,2015-16,2017-18 NK/2015-16/32718,Buildings,Completed,NK-KODAMBAKKAM,133,258000,"SUPPLYING AND FIXING R. O. PLANT TO CPS.,MULLAI NAGAR IN DIVISION-133, UNIT-31, ZONE-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2015-16)",MLACDS,10,2015-16,2018-19 NK/2015-16/32719,Roads,Completed,NK-KODAMBAKKAM,133,950000,PROVIDING CEMENT CONCRETE ROAD AT SUBBARAYA NAGAR 8 TH CROSS STREET AND ASHOK NAGAR 10 TH CROSS STREETS IN DN 133 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/32722,Buildings,Completed,NK-KODAMBAKKAM,134,985000,IMPROVEMENTS TO GROUND ROOMS IN ZONALOFFICE 10 AT N.S.K SALAI IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/32723,Buildings,Completed,NK-KODAMBAKKAM,134,890000,PROVIDING AND FIXING TILE AND ELECTRICAL ARRANGEMENTS TO GROUND FLOOR ROOMS IN ZONALOFFICE 10 BUILDING AT N.S.K SALAI IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/32725,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,995000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT THIRUVALLUVAR STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/32727,Roads,Completed,NK-KODAMBAKKAM,134,999000,"IMPROVEMENTS TO THE EXISTING FOOTPATH AND STORM WATER DRAIN AT U.I.COLONY INNER CIRCULAR ROAD, PARK VIEW ROAD AND OTHER STREETS IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/32765,Roads,Completed,NK-KODAMBAKKAM,131,451000,"RELAYING THE BITUMINOUS CONCRETE ROAD AND CAMBER CORRECTION BY PAVER FINICER AT DIVAKAR STREETIN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/32767,Roads,Completed,NK-KODAMBAKKAM,131,451000,"RELAYING THE BITUMINOUS CONCRETE ROAD AND CAMBER CORRECTION BY PAVER FINICER AT SURYA STREETIN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/32768,Roads,Completed,NK-KODAMBAKKAM,131,698000,"RELAYING THE BITUMINOUS CONCRETE ROAD AND CAMBER CORRECTION BY PAVER FINICER AT KANNAMMAL STREETIN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/32854,Parks,Completed,NK-KODAMBAKKAM,142,972000,"PROPOSED CONSTRUCTION WORK FOR AMMA DRINKING WATER [NEAR CBHSS] AT KODAMBAKKAM ROAD IN DIV-140, U-30,Z-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/32856,Parks,Completed,NK-KODAMBAKKAM,140,838000,"ANNUAL MAINTENANCE OF AMMA PARK AT TDR LAND AT KODAMBAKKAM ROAD IN DIVISION - 140, UNIT-30,ZONE-10 (2 YEARS)",Own Sources,10,2015-16,2018-19 NK/2015-16/32898,Roads,Completed,NK-KODAMBAKKAM,136,667000,"PROVIDING WHITE MARKING AND REFLECTOR AT VASAN STREET, GANDHI STREET AND VARIOUS STREET IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2015-16,2016-17 NK/2015-16/33332,Buildings,Completed,NK-KODAMBAKKAM,134,776000,CONSTRUCTION OF PYRAMID FOR MEDITATION AT ANNAPARK IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/33335,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,900000,IMPROVEMENTS TO STROM WATER DRAIN AT VISWANATHAPURAM 1 ST MAIN ROAD (REACH 1 ) IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2017-18 NK/2015-16/33338,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,620000,IMPROVEMENTS TO STROM WATER DRAIN AT VISWANATHAPURAM 1 ST MAIN ROAD (REACH 2 ) IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/33376,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,767000,"Dismantling Existing Storm Water Drain and Newly Construct at Kumaran Colony 8th Street( CH 0.00M-40.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/33382,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,770000,"Dismantling Existing Storm Water Drain and Newly Construct at Kumaran Colony 7th Street( CH 0.00M-40.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/33383,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,770000,"Dismantling Existing Storm Water Drain and Newly Construct at Kumaran Colony 7th Street( CH 40.00M-80.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/33390,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,959000,"Dismantling Existing Storm Water Drain and Newly Construct at Karumariyamman Koil Street( CH 0.00M-50.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/33398,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,956000,"Dismantling Existing Storm Water Drain and Newly Construct at Karumariyamman Koil Street( CH 50.00M-100.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/33399,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,958000,"Dismantling Existing Storm Water Drain and Newly Construct at Karumariyamman Koil Street( CH 100.00M-150.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/33636,Buildings,Completed,NK-KODAMBAKKAM,130,998000,"Improvement Work to Public Shelter in Front of Vadapalani Murugan Temple at Palani Andavar Koil Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2016-17 NK/2015-16/33637,Buildings,Completed,NK-KODAMBAKKAM,137,143000,"Providing Govt E Service Centre at inside of 137th Division Office complex at 61st Sreet,10th Sector in Div-137, U-28 ,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/33658,Buildings,Completed,NK-KODAMBAKKAM,132,517500,"PROVIDING R.O.PLANT AT KANNIYAPPA NAGAR CORPORATION SCHOOL IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2015-16)",MLACDS,10,2015-16,2017-18 NK/2015-16/33672,Roads,Completed,NK-KODAMBAKKAM,128,650000,"Enganging private Auto with 6 private labours to Dn-128, U-29, Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/33686,Buildings,Completed,NK-KODAMBAKKAM,130,515000,"Supplying and Fixing of R.O.Plant to Chennai Middle School at Amman Koil Street, vadapalani in Dn - 130, Unit - 29, Zone - X. (Under T.nagar Constituency MLA Fund)",MLACDS,10,2015-16,2018-19 NK/2015-16/33793,Roads,Completed,NK-KODAMBAKKAM,135,757000,"LAYING DBM 50mm THICK BY PAVER FINISHER AT KUPPAIAH STREET IN DN 135,UNIT31,ZONE10",Own Sources,10,2015-16,2016-17 NK/2015-16/33794,Roads,Completed,NK-KODAMBAKKAM,135,845000,"LAYING DBM 50mm THICK BY PAVER FINISHER AT VEERASAMY STREET IN DN 135,UNIT31,ZONE10",Own Sources,10,2015-16,2016-17 NK/2015-16/33795,Roads,Completed,NK-KODAMBAKKAM,135,698000,"LAYING DBM 50mm THICK BY PAVER FINISHER AT LAKE VIEW ROAD (REACH 1) IN DN 135,UNIT31,ZONE10",Own Sources,10,2015-16,2016-17 NK/2015-16/33799,Roads,Completed,NK-KODAMBAKKAM,135,698000,"LAYING DBM 50mm THICK BY PAVER FINISHER AT LAKE VIEW ROAD (REACH 2) IN DN 135,UNIT31,ZONE10",Own Sources,10,2015-16,2016-17 NK/2015-16/33824,Roads,Completed,NK-KODAMBAKKAM,130,604000,"Relaying of the road by suing BC with Mechanical Paver Finisher at Gangaiamman Colony 2nd Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/33825,Roads,Completed,NK-KODAMBAKKAM,130,256000,"Relaying of the road by using BC with Mechanical Paver Finisher at Vivekanandha Colony in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/33826,Roads,Completed,NK-KODAMBAKKAM,130,230000,"Relaying of the road by using BC with Mechanical Paver Finisher at Mettu Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2015-16,2016-17 NK/2015-16/33955,Buildings,Completed,NK-KODAMBAKKAM,130,947000,"Supplying and Erection of Display Board to Public Shelter in Front of Vadapalani Murugan Temple at Palani Andavar Koil Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2016-17 NK/2015-16/33989,Roads,Completed,NK-KODAMBAKKAM,132,930000,"Removal of Debris at Important Roads and important streets and dumping the same in PDG from Div 132,133,134 and 135 in Unit -31,Zone10",Own Sources,10,2015-16,2018-19 NK/2015-16/33991,Roads,Completed,NK-KODAMBAKKAM,130,930000,"Removal of Debris at Important Roads and important streets and dumping the same in PDG from Div 127,128,129 and 130 in Unit -31,Zone10",Own Sources,10,2015-16,2018-19 NK/2015-16/34100,Roads,Completed,NK-KODAMBAKKAM,130,993000,"Removal of Debris at Important Roads and important streets and dumping the same in KDG from Div 127,128,129 and 130 in Unit -29, Zone10",Own Sources,10,2015-16,2018-19 NK/2015-16/34101,Roads,Completed,NK-KODAMBAKKAM,133,993000,"Removal of Debris at Important Roads and important streets and dumping the same in KDG from Div 132,133,134 and 135 in Unit -31, Zone10",Own Sources,10,2015-16,2018-19 NK/2015-16/34116,Roads,Completed,NK-KODAMBAKKAM,142,930000,"Removal of Debris at Important Roads and important streets and dumping the same in PDG from Div 140 and 142 in Unit -30,Zone10",Own Sources,10,2015-16,2018-19 NK/2015-16/34117,Roads,Completed,NK-KODAMBAKKAM,131,930000,"Removal of Debris at Important Roads and important streets and dumping the same in PDG from Div 131 and 137 in Unit -28,Zone10",Own Sources,10,2015-16,2018-19 NK/2015-16/34118,Roads,Completed,NK-KODAMBAKKAM,139,930000,"Removal of Debris at Important Roads and important streets and dumping the same in PDG from Div 138 and 139 in Unit -28,Zone10",Own Sources,10,2015-16,2018-19 NK/2015-16/34228,Buildings,Completed,NK-KODAMBAKKAM,130,890000,"Proposed Fixing of Street Name Board Using Stainless Steel Pipe of Retro Reflective Street at Various Street in Dn -130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2018-19 NK/2015-16/34229,Buildings,Completed,NK-KODAMBAKKAM,130,800000,"Providing Sump and Borewell Arrangements to Health Post and Construction of Dwart Wall for High Mast at Alagar Perumal Koil Street, Palani Andavar Koil Street, South Mada Street and North Mada Street in Dn - 130, Unit - 29, zone - X.",Own Sources,10,2015-16,2017-18 NK/2015-16/34259,Roads,Completed,NK-KODAMBAKKAM,132,980000,"ROADCUT RESTORATION AT 9TH AVENUE (FROM JUNCTION OF 6TH AVENUE TO JUNCTION OF 47TH STREET) IN DIV-132, U-31, Z-10",Deposit Works,10,2015-16,2016-17 NK/2015-16/34260,Roads,Completed,NK-KODAMBAKKAM,132,980000,"ROADCUT RESTORATION AT 9TH AVENUE (FROM JUNCTION OF 47TH STREET TO JUNCTION OF 10TH AVENUE) IN DIV-132, U-31, Z-10",Deposit Works,10,2015-16,2016-17 NK/2015-16/34568,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Laying of the road using RMC 40 ( Ch 0-60 ) at Mettukulam Barathi street in div-127, unit-29, zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/34569,Roads,Completed,NK-KODAMBAKKAM,127,988000,"Laying of the road using RMC 40 ( Ch 60 - 120 ) at Mettukulam Barathi street in div-127, unit-29, zone-10",Own Sources,10,2015-16,2019-20 NK/2015-16/34570,Roads,Completed,NK-KODAMBAKKAM,129,993000,"Laying of the road using RMC 40 at Thivagar nagar 1st street in Dn: 129, Unit 29, Zone 10",Own Sources,10,2015-16,2018-19 NK/2015-16/34571,Roads,Completed,NK-KODAMBAKKAM,129,850000,"Laying of the road using RMC 40 at Jaya prakash narayanan street in Dn: 129, Unit 29, Zone 10",Own Sources,10,2015-16,2018-19 NK/2015-16/34572,Roads,Completed,NK-KODAMBAKKAM,129,490000,Attending patch work using RMC 40 at Thivagar 2nd street in Dn- 129 U-29 Z-10,Own Sources,10,2015-16,2018-19 NK/2015-16/34590,Roads,Completed,NK-KODAMBAKKAM,130,669000,"Raising and Widening of Road at Alagiri Nagar 2nd Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2015-16,2016-17 NK/2015-16/34662,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,998000,DESILTING OF STORM WATER DRAIN USING HEAVY DUTY SUPER SUCKER MACHINES AT KUMARAN COLONY 1st STREET AND VARIOUS STREET IN DN-129 U-29 Z-10,Own Sources,10,2015-16,2017-18 NK/2015-16/34663,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,998000,"DESILTING OF STORM WATER DRAIN USING HEAVY DUTY SUPER SUCKER MACHINES AT KALIAMMAN KOIL STREET AND VARIOUS STREET IN DN-127,U-29,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/34664,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"DESILTING OF STORM WATER DRAIN USING HEAVY DUTY SUPER SUCKER MACHINES AT ALAGIRI NAGAR 1ST STREET AND VARIOUS STREET IN DN-130,U-29,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/34665,Roads,Completed,NK-KODAMBAKKAM,142,1852000,"ATTENDING PATCH WORK AT EAST JONES ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY USING MECHANICAL PAVER FINISHER IN DIVISION-142,UNIT-30.ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/34681,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 0.00M-55.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/34682,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 55.00M-109.00M) Div-130,Unit-29,Zone-10",Own Sources,10,2015-16,2017-18 NK/2015-16/34684,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 109.00M-164.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/34685,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 164.00M-218.00M Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/34686,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 218.00M-273.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34687,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 273.00M-328.00M) Div-130,Unit-29,Zone-10",Own Sources,10,2015-16,2019-20 NK/2015-16/34688,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 328.00M-382.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34689,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 382.00M-437.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34690,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 437.00M-491.00M)Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/34691,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 491.00M-546.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/34693,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 546.00M-600.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/34694,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,998000,"Dismantling Existing Storm Water Drain and Newly Construct at KUMARAN COLONY MAIN ROAD( CH 600.00M-655.00M) Div-130,Unit-29,Zone-10",Own Sources,10,2015-16,2018-19 NK/2015-16/34703,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,973000,"Dismantling Existing Storm Water Drain and Newly Construct at ALAGIRI NAGAR 5th Street( CH 0.00M-49.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34704,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,987000,"Dismantling Existing Storm Water Drain and Newly Construct at Alagiri Nagar MAIN ROAD( CH 0.00M-58.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34705,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,984000,"Dismantling Existing Storm Water Drain and Newly Construct at Alagiri Nagar 3rd Street( CH 0.00M To 58.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34707,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,868000,"Dismantling Existing Storm Water Drain and Newly Construct at NGO Colony Main Road( CH 0.00m-55.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/34708,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,868000,"Dismantling Existing Storm Water Drain and Newly Construct at NGO Colony Main Road( CH 55.00M-110.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/34709,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,868000,"Dismantling Existing Storm Water Drain and Newly Construct at NGO Colony Main Road( CH 110.00M-165.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/34710,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,868000,"Dismantling Existing Storm Water Drain and Newly Construct at Dharansingh Colony (CH 0.00M -55.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34711,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,868000,"Dismantling Existing Storm Water Drain and Newly Construct at Dharansingh Colony (CH 55.00M - 110.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/34712,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,868000,"Dismantling Existing Storm Water Drain and Newly Construct at Dharansingh Colony (CH 110.00-165.00M) Div-130,Unit-29,Zone-10.",Own Sources,10,2015-16,2019-20 NK/2015-16/35084,Buildings,Completed,NK-KODAMBAKKAM,127,838000,"IMPROVEMENTS TO SCHOOL BUILDING FOR CHENNAI MIDDLE SCHOOL AT ARUMBAKKAM IN DIV-127, U-29, Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/3523,Buildings,Completed,B-Buildings,131,975000,"SUPLAYING AND FIXING OF FALL CELLING AND COMPOSITE ALUMINIUM BOARD UPHC AT VIJAYARAGAVAPURAM 5TH STREET IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/4013,Buildings,Completed,NK-KODAMBAKKAM,141,993000,"IMPROVEMENT WORKS TO EXISTING FOOTPATH AT SADULLAH STREET AND VARIOUS STREETS IN DIVISION - 141, UNIT -30 , ZONE - 10",Own Sources,10,2015-16,2016-17 NK/2015-16/4030,Roads,Completed,NK-KODAMBAKKAM,137,998000,PROVIDING SPEED BREAKERS AT VARIOUS STREET IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/4262,Bridges,Completed,NK-KODAMBAKKAM,139,999000,"ALUMINIUM COMPOSITE PANEL WORK INFRONT OF UPHC IN R.R.COLONY 2ND LINK STREET AT DIV-139,U-28,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/4358,Buildings,Completed,NK-KODAMBAKKAM,139,999000,"CONSTRUCTION OF COMPOUND WALL FOR UPHC BUILDING AT R.R.COLONY 2ND LINK ST IN DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/4364,Buildings,Completed,NK-KODAMBAKKAM,139,891000,"IMPROVEMENT WORKS FOR UPHC IN R.R.COLONY 2ND LINK ST AT DIV-139,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/4425,Buildings,Completed,NK-KODAMBAKKAM,132,970000,"PROPOSED CONSTRUCTION OF SUMP AND FIXING TILES AT AMMA UNAVAGAM AT 90TH STREET IN DN-132,U-31,Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/4433,Buildings,Completed,NK-KODAMBAKKAM,132,875000,"PROVIDING WATER SUPPLY, SANITARY AND ELECTRICAL ARRANGEMENTS TO AMMA UNAVAGAM AT 90TH STREET IN DN-132, U-31,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/4507,Roads,Completed,NK-KODAMBAKKAM,134,993000,"ATTENDING PATCH WORK USING DBM 50 MM AND BC40 MM WITH PAVER FINISHER AT KAMARAJAR COLONY 4TH STREET AND KAMARAJAR COLONY CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/4510,Roads,Completed,NK-KODAMBAKKAM,133,992000,"ATTENDING PATCH WORK USING BC40 MM WITH PAVER FINISHER AT VARIOUS STREET IN DN-133,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/4788,Buildings,Completed,NK-KODAMBAKKAM,139,996000,"IMPROVEMENTS TO THE COMMUNITY HALL AT VADIVEL STREET IN DN-139,U-28,Z-10",Own Sources,10,2015-16,2018-19 NK/2015-16/4941,Buildings,Completed,NK-KODAMBAKKAM,133,421000,ATTENDING LEAKROOF TO ANGANWADI AND CPS AT MULLAINAGAR IN DN 133 UNIT 31 ZONE 10,Own Sources,10,2015-16,2016-17 NK/2015-16/5121,Footpath,Completed,NK-KODAMBAKKAM,131,986500,"FORMING GRANITE FOOTPATH A.P.PATRO SALAI AT (P.T.RAJAN SALAI TO JEEVANANTHAM SALAI EXTENSION) IN DN 131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2018-19 NK/2015-16/5122,Footpath,Completed,NK-KODAMBAKKAM,131,976000,"FORMING GRANITE FOOTPATH A.P.PATRO SALAI AT (JEEVANANTHAM SALAI EXTENSION TO SIVALINGAPURAM 82 nd STREET) IN DN 131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/5123,Footpath,Completed,NK-KODAMBAKKAM,131,976000,"FORMING GRANITE FOOTPATH A.P.PATRO SALAI AT(JUNCTION OF KAMARAJAR SALAI TOWARDS -100M) IN DN 131, UNIT-28, ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/5160,Road Cut,Completed,NK-KODAMBAKKAM,132,675000,"RESTRUCTION OF ROAD CUT AT 87TH STREET, KAMARAJAR SAALAI IN DN-132, U-31, Z-10",Deposit Works,10,2015-16,2016-17 NK/2015-16/5299,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,990000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/5302,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,970000,"DESILTING AND IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/5306,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,990000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN-135,U-31,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/5348,Parks,Completed,NK-KODAMBAKKAM,131,998000,"CONSTRUCTION OF SUMP AND OTHER IMPROVEMENT WORK AT SIVAN PARK IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/5366,Buildings,Completed,NK-KODAMBAKKAM,142,619000,"IMPROVEMENTS TO THE PARK AT THE OSR LAND IN WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/5389,Buildings,Completed,NK-KODAMBAKKAM,139,881000,"PROPOSED RENOVATION OF EXISTING REPAIRED GASIFIER CREMATORIUM AT WEST JONES ROAD BURIAL GROUND IN DIVISION -139,UNIT - 28, ZONE- 10.",Own Sources,10,2015-16,2016-17 NK/2015-16/5390,Buildings,Completed,NK-KODAMBAKKAM,139,943000,"OPERATION AND MAINTENANCE OF GASIFIER CREMATORIUM AT WEST JONES ROAD BURIAL GROUND IN DIVISION -139,UNIT - 28,ZONE- 10",Own Sources,10,2015-16,2017-18 NK/2015-16/5572,Roads,Completed,NK-KODAMBAKKAM,128,985000,Relaying of the road using BC 40mm thick by paver finisher at Kamarajar salai (from Baskar colony 2nd srteet JN to SBI Colony 1st street ) in Dn-128 U-29 Z-10,Own Sources,10,2015-16,2016-17 NK/2015-16/5825,Buildings,Completed,NK-KODAMBAKKAM,127,962000,"providing chairs, fixing GYM apparatus , providing play apparatus etc at natesa nagar children play space in dn 127,unit -29,zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/6063,Roads,Completed,NK-KODAMBAKKAM,131,975000,"PROVIDING AND LAYING SPEED BREAKERS AT 13th SECTOR 83rd,87th STREET AND VARIOUS STREETS IN DIV-131,U-28,Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/6189,Roads,Completed,NK-KODAMBAKKAM,127,930000,"ATTENDING PATCH WORK AT NATESAN NAGAR 1ST MAIN ROAD JUNCTION OF CHITTRAI STREET AND PROVIDING AND FIXING OF THERMO PLASTIC PAINT AND REFELECTER AT CHITTIRAI STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/6415,Buildings,Completed,NK-KODAMBAKKAM,131,981000,IMPROVEMENT TO 1 ST SECTOR PARK IN DIV 131 U 28 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/6473,Parks,Completed,NK-KODAMBAKKAM,137,2238000,MAINTANCE OF BURIYAL GROUND AT ERIKARAI STREET IN 137 UNIT28 ZONE10,Own Sources,10,2015-16,2017-18 NK/2015-16/6550,Buildings,Completed,NK-KODAMBAKKAM,141,939000,"CONSTRUCTION OF COMPOSTING YARD AT KANNAMAPET BURIAL GROUND IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/6556,Buildings,Completed,NK-KODAMBAKKAM,141,885000,"CONSTRUCTION OF COMPOSITE YARD (FOR DIVISION-136 ) AT KANNAMAPET BURIYAL GROUND IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/6983,Buildings,Completed,NK-KODAMBAKKAM,139,526000,"ADDITIONAL INCORPORATION OF THE LPG BURNER SYSTEM IN THE EXISTING GASIFIRE CREMATORIUM IN WEST JONES ROAD BURIAL GROUND AT DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/6984,Buildings,Completed,NK-KODAMBAKKAM,129,969000,"Supply of mini lorry (Tata ace ) under daily hiring including 6 labour for cleaning the water table and footpath in bus route and interior roads in Div-129,unit-29 ,zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7010,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,695000,"Providing Rainwater harvesting at various streets in div 131,unit-28, zone-10",Own Sources,10,2015-16,2017-18 NK/2015-16/7139,Roads,Completed,NK-KODAMBAKKAM,131,374000,"Laying cement concrete road at D block sivalingapuram ,K.K.Nagar in Dn-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7140,Roads,Completed,NK-KODAMBAKKAM,131,391000,"Laying cement concrete road at F block sivalingapuram,K.K.Nagar in Dn-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7143,Roads,Completed,NK-KODAMBAKKAM,131,374000,"Laying cement concrete road at J block sivalingapuram ,K.K.Nagar in Dn-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7144,Roads,Completed,NK-KODAMBAKKAM,131,552000,"Laying cement concrete road at E block sivalingapuram ,K.K.Nagar in Dn-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7145,Roads,Completed,NK-KODAMBAKKAM,131,374000,"Laying cement concrete road at L block sivalingapuram , K.K.Nagar in Dn-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7147,Roads,Completed,NK-KODAMBAKKAM,131,374000,"Laying cement concrete road at C block sivalingapuram ,K.K.Nagar in Dn-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7151,Roads,Completed,NK-KODAMBAKKAM,131,552000,"Laying cement concrete road at B block sivalingapuram,K.K.Nagar in Dn-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7241,Buildings,Completed,NK-KODAMBAKKAM,132,990000,"CONSTRUCTION OF AMMA UNAVAGAM AT 90TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/7242,Buildings,Completed,NK-KODAMBAKKAM,132,990000,"FLOORING AND PARTITIONS ARRANGEMENTS IN AMMA UNAVAGAM AT 90TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2015-16,2017-18 NK/2015-16/7621,Roads,Completed,NK-KODAMBAKKAM,129,969000,"Supply of mini lorry (Tata ace ) under daily hiring including 6 labour for cleaning the water table and footpath in bus route and interior roads in Div-129,unit-29 ,zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7631,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,862000,RAISING OF MANHOLE DOORS AT VARIOUS STREETS IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/7658,Buildings,Completed,NK-KODAMBAKKAM,131,628000,"PROVIDING E-TOILET (MALE TOILET) AT SIVAN PARK, K.K.NAGAR IN DN-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7661,Buildings,Completed,NK-KODAMBAKKAM,131,628000,"PROVIDING E-TOILET (FEMALE TOILET) AT SIVAN PARK, K.K.NAGAR IN DN-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7664,Buildings,Completed,NK-KODAMBAKKAM,131,628000,"PROVIDING E-TOILET (MALE TOILET) AT 6th SECTOR PLAY FIELD , K.K.NAGAR IN DN-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7783,Roads,Completed,NK-KODAMBAKKAM,131,982000,"LAYING OF CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 3rd STREET ( BETWEEN VIJAYARAGAVAPURAM 2& 4th CROSS STREET) IN DN-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7961,Roads,Completed,NK-KODAMBAKKAM,132,900000,"LAYING OF CEMENT CONCRETE(M40) ROAD AT 7TH AVENUE EXTENSION(EAST SIDE) AT DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/7965,Roads,Completed,NK-KODAMBAKKAM,132,940000,"LAYING OF CEMENT CONCRETE(M40) ROAD AT 7TH AVENUE EXTENSION(WEST SIDE) AT DIV-132, U-31, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8029,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,989000,"CONSTRUCTION OF STORM WATER DRAIN OF SIZE 600 X 750MM AT SRI SAYEE NAGAR ANNEXE (FROM JN OF KAALIAMMAN KOVIL STREET TO EXISTING CANAL) IN DN-127, UNIT-29, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/8128,Buildings,Completed,NK-KODAMBAKKAM,132,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DN-132, UNIT-31,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8130,Buildings,Completed,NK-KODAMBAKKAM,133,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DN-133, UNIT-31,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8131,Buildings,Completed,NK-KODAMBAKKAM,134,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DN-134, UNIT-31,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8132,Buildings,Completed,NK-KODAMBAKKAM,135,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DN-135, UNIT-31,ZONE-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8165,Electrical,Completed,NK-KODAMBAKKAM,137,975000,ADDITIONAL WORK FOR AMMAUNAVAGAM AT ANNA MAIN ROAD IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2015-16,2016-17 NK/2015-16/8223,Buildings,Completed,NK-KODAMBAKKAM,139,998000,"CONSTRUCTION OF COMPOSTING YARD AT SAIDAPET BURIAL GROUND IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8258,Buildings,Completed,NK-KODAMBAKKAM,139,998000,"CONSTRUCTION OF COMPOSTING YARD AT SAIDAPET BURIAL GROUND FOR DIV-131 IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8267,Roads,Completed,NK-KODAMBAKKAM,136,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DIVISION-136, UNIT-30 AND ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/8268,Roads,Completed,NK-KODAMBAKKAM,136,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DIVISION-136, UNIT-30 AND ZONE-10.",Own Sources,10,2015-16,2017-18 NK/2015-16/8277,Buildings,Completed,NK-KODAMBAKKAM,141,672000,"OPERATION AND MAINTENANCE FOR ELECTRICAL CREMATORIUM AT KANNAMAPET BURIAL GROUND ( 6 MONTH ) IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2015-16,2018-19 NK/2015-16/8306,Buildings,Completed,NK-KODAMBAKKAM,128,969000,"SUPPLYING OF EACH ONE OPERATOR AND ASSISTANT AT VIRUGAMBAKKAM ELECTRICAL CREMATORIUM IN DIVISION-128,UNIT-29,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/8308,Buildings,Completed,NK-KODAMBAKKAM,128,279000,"OPERATION MAINTANANCE PERIOD COMPLETION INTIMATION AND THE RENEWAL OF OPERATION AND MAINTANANCE CONTRACT OF THE EXISTING ELECTRICAL CREMATORIUM AT THANGAL ERIKARAI STREET,VIRUGAMBAKKAM BURIAL GROUND IN DIVISION-128,UNIT-29,ZONE-10.",Own Sources,10,2015-16,2018-19 NK/2015-16/8335,Buildings,Completed,NK-KODAMBAKKAM,127,1690000,"PROPOSED CONSTRUCTION OF NNMP SHED(CENTRE NO 04106)( UNDER MLA FUND) AT KULASEKARAPURAM IN DIV 127, UNIT-29,ZONE- 10.",MLACDS,10,2015-16,2017-18 NK/2015-16/8399,Buildings,Completed,NK-KODAMBAKKAM,141,693000,IMPROVEMENT WORK ON KANNAMALPETTAI BURIYAL GROUND PC AND CIT NAGAR SCHOOL DRAINAGE CONNECTION IN DIV 141 U 30 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/8411,Buildings,Completed,NK-KODAMBAKKAM,141,328000,REPAIR AND IMPROVEMENT WORK ON LALITHAPURAM AMMA UNAVAGAM IN DIV 141 U 30 Z 10,Own Sources,10,2015-16,2017-18 NK/2015-16/8444,Roads,Completed,NK-KODAMBAKKAM,141,984000,"ATTENDING THE PATCH WORK AT CIT NAGAR 4 th MAIN ROAD, CIT NAGAR 2nd MAIN ROAD AND VARIOUS STREET IN DIVISION-141, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/8491,Buildings,Completed,NK-KODAMBAKKAM,140,2494000,"PROPOSED NEW CONSTRUCTION WORK FOR GYM BUILDING (FIRST FLOOR) AT VAZHAITHOPPU PLAY GROUND IN DIV-140, U-30,Z-10. [UNDER SAIDAPET M.L.A FUND (2015-16)]",MLACDS,10,2015-16,2016-17 NK/2015-16/8603,Buildings,Completed,NK-KODAMBAKKAM,138,998000,"CONSTRUCTION OF COMPOSTING YARD AT PACHAYAPPEN FIRST STREET BURIAL GROUND IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/8653,Roads,Completed,NK-KODAMBAKKAM,142,990000,"LAYING CEMENT CONCRETE ROAD AT MOSQUE PALLAM 2ND STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/8654,Roads,Completed,NK-KODAMBAKKAM,142,754000,"LAYING CEMENT CONCRETE ROAD AT MOSQUE PALLAM 3RD STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/8655,Roads,Completed,NK-KODAMBAKKAM,142,732000,"LAYING CEMENT CONCRETE ROAD AT MOSQUE PALLAM 4TH STREET IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/8657,Buildings,Completed,NK-KODAMBAKKAM,140,1421000,"PROPOSED NEW CONSTRUCTION WORK FOR MULTI PURPOSE HALL (GROUND FLOOR) AT VAZHAITHOPPU PLAY GROUND IN DIV-140, UNIT-30, Z-10. [UNDER SAIDAPET M.L.A FUND (2015-16)]",MLACDS,10,2015-16,2016-17 NK/2015-16/8662,Roads,Completed,NK-KODAMBAKKAM,142,987000,"LAYING CEMENT CONCRETE ROAD AT PILLAIYAR KOIL STREET (FROM PILLAIYAR KOIL LANE TO BALAJI STREET) IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/8668,Roads,Completed,NK-KODAMBAKKAM,142,980000,"LAYING CEMENT CONCRETE ROAD AT PILLAIYAR KOIL STREET (FROM PILLAIYAR KOIL LANE TO JONES ROAD SUBWAY) IN DIVISION -142,UNIT -30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/8904,Buildings,Completed,NK-KODAMBAKKAM,140,599000,"PROPOSED NEW CONSTRUCTION WORK FOR MULTI PURPOSE HALL PHASE 1 AT KUMARAN COLONY 1 ST STREET IN DIV-140,UNIT-30, Z-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/8913,Roads,Completed,NK-KODAMBAKKAM,133,606000,PROVIDING CEMENT CONCRETE ROAD WITH M 20 GRADE CONCRETE IN ASHOK NAGAR 10TH AND 14TH STREET IN DN 133 UNIT31 ZONE.10 (UNDER WARD COUNCILOR SCHEME ),Own Sources,10,2015-16,2016-17 NK/2015-16/8937,Buildings,Completed,NK-KODAMBAKKAM,137,986000,"PROVIDING PATHWAY FOR INSIDE OF BURIAL GROUND AT EARIKKARAI STREET IN DN-137,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8956,Buildings,Completed,NK-KODAMBAKKAM,137,995000,"PROVIDING PATHWAY FOR INSIDE OF BURIAL GROUND AND PROVIDING AND FIXING NAME BOARD AT EARIKKARAI STREET IN DN-137,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8965,Buildings,Completed,NK-KODAMBAKKAM,139,986000,"PROVIDING SHED AND FLOORING WORK IN FRONT OF CPS SCHOOL JAFFERKHANPET IN DIV 139 U 28 Z 10",Own Sources,10,2015-16,2016-17 NK/2015-16/8966,Buildings,Completed,NK-KODAMBAKKAM,137,978000,"RAISING TO THE EXISTING COMPOUND WALL FOR BURIAL GROUND AT EARIKKARAI STREET IN DN-137,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/8968,Buildings,Completed,NK-KODAMBAKKAM,139,965000,IMPROVEMENT WORK ON CPS & CHS SCHOOL JAFFERKHANPET IN DIV 139 U 28 Z 10,Own Sources,10,2015-16,2016-17 NK/2015-16/8970,Buildings,Completed,NK-KODAMBAKKAM,137,991000,"IMPROVEMENTS TO THE EXISTING TOILET AND REST ROOM AT BURIAL GROUND AT EARIKKARAI STREET IN DN-137,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9066,Parks,Completed,NK-KODAMBAKKAM,139,486000,"GREENERY ARRANGEMENTS TO SAIDAPET BURIAL GROUND IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2019-20 NK/2015-16/9075,Parks,Completed,NK-KODAMBAKKAM,131,995000,"CONSTRUCTION OF PUMP ROOM AND WATER FALLS AND OTHER IMPROVEMENT WORK AT SIVAN PARK IN DIV-131,U-28,Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9279,Buildings,Completed,NK-KODAMBAKKAM,137,980000,"Providing Yoga Medai Roof with Truss, flooring at inside of Park at Errikarai Salai in Div 137, Unit-28, Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9280,Buildings,Completed,NK-KODAMBAKKAM,137,950000,"Construction of Yoga Medai with Roof at 11th sector Park, Construction of Dust Bin at Anna Main Road , attending Road with P.C.C. Work at Jai Balaji Nagar and Anna Main Road , and construction of Yoga Medai platform and Additional room for Watchman at Park at Errikarai Salai in Dn-137,Unit-28,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9320,Roads,Completed,NK-KODAMBAKKAM,141,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DIVISION-141, UNIT-30 AND ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/9355,Roads,Completed,NK-KODAMBAKKAM,140,590000,"ENGAGING PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DIVISION-140, UNIT-30 AND ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/9445,Buildings,Completed,NK-KODAMBAKKAM,136,986000,"Construction of R.C.C. Gate Pillar and Improvements of Compound wall with Grill fencing and Granite slab at Jeeva Park from South east Junction of G.N.Chetty Road and Rajamannar Street to towards North at G.N.Chetty Road in Div 136,Unit-30,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9446,Buildings,Completed,NK-KODAMBAKKAM,136,995000,"Improvements to Jeeva Park Compound wall with Grill and Granite slab and footpath Grill Fencing from east of main Gate to towards east Junction of Rajamannar Street in Div 136,Unit-30,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9447,Buildings,Completed,NK-KODAMBAKKAM,136,995000,"Providing Compound wall with Grill fencing and Granite slab and providing Grill fencing for footpath in front of Jeeva Park from west of main gate towards west and Junction of Rajamannar Street at G.N.Chetty Road in Div 136,Unit-30,Zone-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9781,Electrical,Completed,NK-KODAMBAKKAM,142,960000,"Supply and Installation of 14 no?s of 2 ton Split AC for the use of Operation Theater, Post Operation ward and Scanning Room at EOC Saidapet in Division 142 Zone-X",Own Sources,10,2015-16,2018-19 NK/2015-16/9799,Buildings,Completed,NK-KODAMBAKKAM,139,980000,"PROPOSED ESTABLISHMENT OF KITCHEN WASTE DIGESTER AT SAIDAPET BURIAL GROUND IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9801,Buildings,Completed,NK-KODAMBAKKAM,139,970000,"PROPOSED CONSTRUCTION AND INSTALLATION OF GAS HOLDER, UTILIZATION SYSTEM OF OF KITCHEN WASTE BASED BIO-GAS PLANT AT SAIDAPET BURIAL GROUND IN DIV-139, U-28, Z-10",Own Sources,10,2015-16,2016-17 NK/2015-16/9921,Buildings,Completed,NK-KODAMBAKKAM,136,993000,"REPAIRS AND IMPROVEMENTS TO THE VENKATNARAYANA ROAD, KANADASAN STREET, PANAGAL PARK, ANANDAN STREET, JAWAHARLAL NEHRU STREET AND RAILWAY BORDER STREET PUBLIC CONVENIENCE IN DIVISION - 136, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/9922,Buildings,Completed,NK-KODAMBAKKAM,136,985000,"PROVIDING AND FIXING AUTOMATIC CONTROL FOR ALL MOTOR IN DIVISION-136, 140,141,& 142, UNIT-30, ZONE-10.",Own Sources,10,2015-16,2016-17 NK/2015-16/9930,Roads,Completed,NK-KODAMBAKKAM,142,991000,"LAYING OF CEMENT CONCRETE ROAD AT KUYAVAR STREET(FROM SESACHALAM STREET TO BALAJI STREET) AT DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/9931,Roads,Completed,NK-KODAMBAKKAM,142,744000,"LAYING OF CEMENT CONCRETE ROAD AT KRISHNAPPA(P) 1ST STREET AT DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/9932,Roads,Completed,NK-KODAMBAKKAM,142,917000,"LAYING OF CEMENT CONCRETE ROAD AT KRISHNAPPA(P) 2ND STREET AT DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/9933,Roads,Completed,NK-KODAMBAKKAM,142,939000,"LAYING OF CEMENT CONCRETE ROAD AT KUYAVAR STREET(FROM BALAJI STREET TO EAST JONES ROAD) AT DIVISION -142,UNIT-30,ZONE -10",Own Sources,10,2015-16,2016-17 NK/2015-16/9935,Buildings,Completed,NK-KODAMBAKKAM,142,590000,"ENGAGING ADDITIONAL PRIVATE LOAD AUTO VEHICLE 1 NO. WITH PRIVATE LABOURS 6 NO. FOR DIVISION WORK IN DN-142, UNIT-30 AND ZONE-10",Own Sources,10,2015-16,2017-18 NL/2015-16/0178,Buildings,Completed,NL-VALASARAVAKKAM,149,260000,"FORMATION OF TAMIL NADU ARASU CABLE CENTRE INSIDE UNIT-33 OFFICE COMPLEX AT NAKKEERAN STRRET IN DN-149,UNIT-33,ZONE XI.",Grants,11,2015-16,2016-17 NL/2015-16/0501,Roads,Completed,NL-VALASARAVAKKAM,150,617000,"ROAD CUT RESTORATION AT ALPHA COLLEGE ROAD, PERUMAL KOIL STREET, PERUMAL KOIL 1ST TO 4TH AND PERUMAL KOIL MAIN ROAD IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/0504,Roads,Completed,NL-VALASARAVAKKAM,150,708000,"ROAD CUT RESTORATION AT PANCHOLAI STREET, THIRUVENGADAM STREET, MAHATMA STREET, NEHRU STREET, RAJIV GANDHI STREET, BHARATHIYAR STREET, PERUMAL KOIL 3RD STREET, PERUMAL KOIL 2ND STREET AND SIVABOOTHA KAMATCHI NAGAR IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/0890,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,737000,"Dismantling and Reconstruction of Side Drain at Ponniamman Koil 1st Street & kamarajar street culvert (Councillor fund) in Division -147, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/0892,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,737000,"Dismantling and Reconstruction of Side Drain at Seemathamman Nagar Main Road & karapagavinayagar colony culvert (Councillor fund) in Division -147, Unit-32, Zone-XI",Own Sources,11,2015-16,2018-19 NL/2015-16/10239,Roads,Completed,NL-VALASARAVAKKAM,144,215000,"IMPROVEMENTS TO THE DAMAGED BRIDGE IN VGP AMUDHA NAGAR DUE TO NORTH EAST MONSOON FLOOD IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/1024,Roads,Completed,NL-VALASARAVAKKAM,150,792000,"ROAD CUT RESTORATION AT KAMACHI NAGAR, PILLAIYAR KOIL 1ST STREET TO 4TH STREET AND THERUVETHI AMMAN KOIL STREET IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/10765,Buildings,Completed,NL-VALASARAVAKKAM,155,206000,"Improvements of Urban Primary Health Center (UPHC) at Bajanai koil street in Dn-155, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/1116,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,890000,"Improvement to Side Drain at Sakthi Nagar 15th Street in Dn.145, U-33, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/1125/C,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,947000,"Improvement to Side Drain at Sakthi Nagar 6th and 7th Streets in Dn.145, U-33, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/12018,Roads,Completed,NL-VALASARAVAKKAM,155,4950000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kothari Nagar 1st Cross street, Kothari Nagar 1st street, Kothari Nagar 2nd street, Kothari Nagar EVR street, Kothari Nagar 3rd street, Kothari Nagar 4th street, Kothari Nagar 5th street, Kothari Nagar 6thstreet, Kothari Nagar 7th street, Kothari Nagar 8th street, Kothari Nagar 9th street in division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/12020,Road Cut,Completed,NL-VALASARAVAKKAM,155,4810000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Thirumalai nagar Nehru Street, Nehru street lane, Padmavathy street, Kathaie amman street, Om Eswar street, Maha vishnu street, Angel street,Angel street lane, Seven hills street, Thirumalai street in division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/12064,Road Cut,Completed,NL-VALASARAVAKKAM,155,4661000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Nadarajan Street,Kalyanaponnappan street, Kalyanaponnappan street Lane, Narasimman Nagar 1st Street, Narasimman Nagar 2nd street, Thirumalai Nagar Sanjayram street, Pasupathy street, Rajeshwari street 155, unit-34, zone- 11",Own Sources,11,2015-16,2018-19 NL/2015-16/12065,Road Cut,Completed,NL-VALASARAVAKKAM,155,3424000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kothari Nagar 1st Main road, Kothari Nagar 2nd Main road, Kothari Nagar 10th street, Kothari Nagar 11th street, in division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/1240,Roads,Completed,NL-VALASARAVAKKAM,150,773000,"ROAD CUT RESTORATION AT CHETTIYAR AGARAM MAIN ROAD IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/1280,Road Cut,Completed,NL-VALASARAVAKKAM,151,945000,"CMWSSB- Road cut restoration work using GSB, WMM and RMC40 at Anna Street,Astalakshmi Nagar Main Road,Lakshmi Nagar 10th Cross Street,Anna Salai, Lakshmi Nagar Extn 1st Main Road,Chinna Porur Hospital Road,Chinna Porur Bajanai Koil Street,Chinna Porur Navamani Street,Thiraviyam Nagar 1st Street,Ganapathy Nagar Main Road,Senthil Nagar 1st Cross Street in Dn-151, U-34, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/1284,Road Cut,Completed,NL-VALASARAVAKKAM,151,913000,"CMWSSB- Road cut restoration work using GSB, WMM and RMC40 at Officers Colony Main Road, Anjeneyar Koil Street, Ramakrishna Main Road, St.John School Street,Pilayar Koil Street, Thirumurugan Nagar 2nd Cross Street, New Colony Main Road, New Colony 3rd Cross Street (East). in Dn-151, U-34, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/12886,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,810000,"Improvements to side drain at Rajivi gandhi salai C/s Street in Dn-148,Un-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/1295,Buildings,Completed,NL-VALASARAVAKKAM,147,572000,"Improvement of Division Office Compound Wall at Gangaiamman Koil Street Maanthoppu Colony in Div-147, Unit-32, Zone-11",Own Sources,11,2015-16,2017-18 NL/2015-16/13146,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,810000,"Improvements to side drain at Rajivi gandhi salai in Dn-148,Un-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/13151,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,850000,"Improvements to side drain at Azhagiri salai in Dn-148,Un-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/13171,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,790000,"Improvements to side drain at Balaji Nagar 7th Street in Dn-148,Un-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/13326,Parks,Completed,NL-VALASARAVAKKAM,143,940000,Execution of Maintenance Works at Various Park's for Dn.143 to 155 in Zone-XI,Own Sources,11,2015-16,2016-17 NL/2015-16/1347,Roads,Completed,NL-VALASARAVAKKAM,150,2347000,"ROAD CUT RESTORATION AT THUNDALAM MAHALAKSHMI NAGAR, SRI PRASANTH NAGAR MAIN ROAD, SRI PRASANTH NAGAR VIMAL SANTH STREET, SRI PRASANTH NAGAR SAYAR BAI STREET, SRI PRASANTH NAGAR SANTHOSH BAI STREET AND SRI PRASANTH NAGAR SAMULAL STREET IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/1350,Roads,Completed,NL-VALASARAVAKKAM,150,2347000,"ROAD CUT RESTORATION AT SRI PRASANTH JAWAHAR STREET, MARUTHI NAGAR NEHRU STREET, MARUTHI NAGAR KUMARAN STREET, MARUTHI NAGAR KAMARAJAR STREET AND MARUTHI NAGAR THILAGAR STREET IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/1355,Roads,Completed,NL-VALASARAVAKKAM,150,2279000,"ROAD CUT RESTORATION AT MARUTHI NAGAR PHASE III 2ND STREET, BALAJI NAGAR MAIN ROAD, BALAJI NAGAR THILAGAR STREET, BALAJI NAGAR BHARATHIYAR STREET, BALAJI NAGAR THIRUVALLUVAR STREET AND BALAJI NAGAR RADHA KRISHNA STREET IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/13602,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,994000,"IMPROVEMNETS TO THE STORM WATER DRAIN AT ABIRAMI NAGAR 5th Street in Div -144, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/1362,Roads,Completed,NL-VALASARAVAKKAM,150,2347000,"ROAD CUT RESTORATION AT RAJAJI STREET(RAMANAR STREET), PUNIYAKOTTI NAGAR MAIN ROAD, VIJAYALAKSHMI NAGAR 1ST STREET, VIJAYALAKSHMI NAGAR 2ND STREET, MOORTHY NAGAR 1ST CROSS STREET, MOORTHY NAGAR 2ND CROSS STREET AND SAMAYAPURAM NAGAR 1ST STREET IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/1363,Roads,Completed,NL-VALASARAVAKKAM,150,2279000,"ROAD CUT RESTORATION AT SRIRAM NAGAR 2ND STREET, SRIRAM NAGAR 3RD STREET, SAMAYAPURAM NAGAR MAIN ROAD AND SAMAYAPURAM NAGAR 2ND STREET IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/1367,Roads,Completed,NL-VALASARAVAKKAM,155,1437000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Royala Nagar 4th Cross Street, Bakthivedhananda 1st Avenue in DN - 155, Unit - 34, Zone - 11",Own Sources,11,2015-16,2016-17 NL/2015-16/1370,Roads,Completed,NL-VALASARAVAKKAM,155,1196000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Egambara(n) Naicker Street, Balaji Avenue 2nd Street, Amman Nagar 3rd Street in DN - 155, Unit - 34, Zone - 11",Own Sources,11,2015-16,2016-17 NL/2015-16/13747,Road Cut,Completed,NL-VALASARAVAKKAM,144,1609400,"FORMING ROAD CUT RESTORATION WORK IN MMDA COLONY 1st MAIN ROAD TO MMDA COLONY 7th BLOCK MAIN ROAD IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/1387,Roads,Completed,NL-VALASARAVAKKAM,155,1478000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Amman Nagar 1st Main Road, Amman Nagar 1st street, Royala Nagar 5th Cross Street, Bakyalakshmi Nagar 2nd Street In division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/13932,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,810000,"Improvements to side drain at C.D.N.Nagar 21st st in Dn148,U33,Zn 11",Own Sources,11,2015-16,2017-18 NL/2015-16/1465,Buildings,Completed,NL-VALASARAVAKKAM,152,416000,Formation of tamilnadu e-seva maiyam in zonal office 11 at div152 unit33 zone11,Own Sources,11,2015-16,2016-17 NL/2015-16/14780,Buildings,Completed,NL-VALASARAVAKKAM,151,286000,"Providing Electrical arrangement and Other Improvements to Amma Unavagam at Chinna Porur, Hospital Road in Dn151,U34, Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/15038,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,985000,"Improvement work of Storm Water Drain of Side Drain at various street in DIV-143,DIV-144,DIV-146 and DIV-147, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/15039,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Providing SWD Cover Slab and Chute Pipe at Various Streets in Dn-151 & 153. Unit-34, Zone-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/15040,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,973000,"Repairs and Maintenance to Strom Water Drain at Venkateswara nagar, Shanthi nagar and Gangai amman koil street in Dn-154 & Kamarajar salai, Alagapuri Nagar and Bakthivedananda Avenue Dn-155, Unit-34, Zone-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/15053,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,781000,"Maintenance of Existing SWD In Madurai meenatchi Nagar Main Road, Singaravelan St, OM Sakthi Nagar Main Road, Azhagiri St, Chowdry Nagar 3rd St, Suresh Nagar 1st St, Suresh Nagar 4th St in Division - 152, Zone - XI",Own Sources,11,2015-16,2017-18 NL/2015-16/15062,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,650000,"Repair and Maintenance of SWD At Kaveri Nagar 2nd Street, Karambakkam 1st Main Road, Arunachalam Nagar 2nd Street, Viswanathan Nagar 2nd Street, Samayapuram 4th Street, Mandaveli Cross Street, Ponni Nagar Mahaveer Street, Ponni Nagar Raja Rajan Street, Sengutuvan Cross Street, In Dn - 150, Unit ? 34 And Zone - XI",Own Sources,11,2015-16,2017-18 NL/2015-16/15154,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,628000,"Improvements Repair works to Storm Water Drain at Various Street (Nagireddy Street, AGS Colony Main Road, BVR nagar main road, Venkateswara nagar main road, Vishlathchi Street, Nehru Street and Kattabomman Street in Dn.149.U-33, Z-XI.",Own Sources,11,2015-16,2017-18 NL/2015-16/15161,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,994000,"Improvement work of Storm Water Drain of Side Drain at various street in DIV-148, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/15425,Roads,Completed,NL-VALASARAVAKKAM,154,994000,"Forming road cut restoration using GSB WMM PCC1:2:4 Ambal Nagar and Shanthi Nagar in Dn154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/15428,Roads,Completed,NL-VALASARAVAKKAM,155,995000,"Forming road cut restoration using GSB,WMM,PCC1;2;4 Natesan Nagar and Kannadhasan Nagar in Dn155, u-34, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/15672,Roads,Completed,NL-VALASARAVAKKAM,155,998000,"Attending Patch work with GSB and WMM at Various streets in Dn, 150,151, 153, 154 and 155, Unit-34, Zone-11.",Own Sources,11,2015-16,2018-19 NL/2015-16/1571,Buildings,Completed,NL-VALASARAVAKKAM,153,257000,"Forming E - Seva Center at Sakthi Nagar Main Road,porur, in Dn-153, U-34, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/15935,Buildings,Completed,NL-VALASARAVAKKAM,155,175000,"Repair and Maintenance to Amma unavagam at Bajanai koil street in Division-155, Unit-34, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/15937,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,2748000,"Demolition of Existing Side Drain And Construction of SWD 2'0 X 2'6 in Perumal Koil Street in Div-144, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/16095,Roads,Completed,NL-VALASARAVAKKAM,153,310000,"Attending patch work with GSB and WMM at various streets, Mangala Nagar in Division-153, Unit-34, Zone-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/16298,Buildings,Completed,NL-VALASARAVAKKAM,149,177000,"Improvement Works (Ramps and 3S Toilet Platform) in Burial Ground Brindravan Nagar in Division 149, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/16654,Roads,Completed,NL-VALASARAVAKKAM,151,154000,"Attending GSB & Patch Work at School Road and Hospital Road in Division-151,Unit-34,Zone-11",Own Sources,11,2015-16,2017-18 NL/2015-16/16668,Buildings,Completed,NL-VALASARAVAKKAM,144,876000,"Construction of New Compound Wall at 144 Division office in MMDA Colony 6th Block in Div-144,Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/16958,Roads,Completed,NL-VALASARAVAKKAM,147,998000,"ATTENDING PATCH WORK WITH GSB AND WMM AT VARIOUS STREETS IN DIV-143,144,146 & 147 IN UNIT-32, ZONE-XI",Own Sources,11,2015-16,2018-19 NL/2015-16/16959,Roads,Completed,NL-VALASARAVAKKAM,148,998000,"Attending patch at various streets using GSB WMM in Dn 145,148,149,152 in U 33 Z 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17088,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,980000,"Improvements to Existing Side Drain at R E Nagar 5th Street,(SOUTH) in Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/17105,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Improvements to Existing Side Drain at BALA MURUGAN KOIL STREET FIRST AND SECOND STREET IN DN.153 ,U-34,Z-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/17106,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Improvements to Existing Side Drain at ESWARAN KOIL STREET IN DN.153,U-34,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/17108,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,998000,"Improvements to Existing Side Drain at ESWARAN KOIL 1 st STREET R.E nagar third STREET IN DN.153 ,U-34,Z-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/17110,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,987000,"Improvements to Existing Drain at GANESH AVENUE 8th STREET IN DN.153 ,U-34,Z-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/17114,Buildings,Completed,NL-VALASARAVAKKAM,155,994000,"Construction of Compound wall at Amman Nagar OSR land in DN- 155, U-34, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/1712,Roads,Completed,NL-VALASARAVAKKAM,154,783000,"Forming roadcut restoration of under ground sewage and water supply facilities using GSB, WMMand RMC 40 at Kamaraj Street Lane, Pethaniya Street, Balambigai Nagar Main Road Lane and Balambigai Nagar 1st Street in division 154, unit-34,zone -11",Own Sources,11,2015-16,2016-17 NL/2015-16/17139,Buildings,Completed,NL-VALASARAVAKKAM,148,294000,"Improvements to AmmaUnavagam at Jayaram Nagar in Dv-148,U-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/1718,Roads,Completed,NL-VALASARAVAKKAM,154,1230000,"Forming roadcut restoration of under ground sewage and water supply facilities using GSB, WMMand RMC 40 at Jalaluddin street, Kamaraj 1st Street, Kamaraj 2nd Street, Kamaraj 3rd Street and Pethaniya Cross Street in division 154, unit-34,zone -11",Own Sources,11,2015-16,2016-17 NL/2015-16/17200,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,945000,"Improvements to Side Drain at Anna Nagar thangal street in DN-154 UNIT-34 ,ZONE-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/17216,Buildings,Completed,NL-VALASARAVAKKAM,145,711000,"Improvement to Amma Unavagam at Madha Koil Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2017-18 NL/2015-16/17222,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,746000,"Improvement to Side Drain at Sakthi Nagar C Block 21st Street in Dn 145, Unit 33, Zone 11 (Councilor Fund)",Own Sources,11,2015-16,2017-18 NL/2015-16/17226,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,746000,"Improvement to Side Drain at Sakthi Nagar 15th Street in Dn 145, Unit 33, Zone 11 (Councilor Fund)",Own Sources,11,2015-16,2017-18 NL/2015-16/17227,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,746000,"Improvement to Side Drain at Sakthi Nagar C Block 23rd Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2017-18 NL/2015-16/17317,Roads,Completed,NL-VALASARAVAKKAM,145,863000,"Forming the Cement Concrete Road at Krishna Nagar 5th Cross Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17318,Roads,Completed,NL-VALASARAVAKKAM,145,802000,"Forming the Cement Concrete Road at Pallavan Nagar V.O.C. Street (Part) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17320,Roads,Completed,NL-VALASARAVAKKAM,145,999000,"Forming the Cement Concrete Road at Sakthi Nagar 13th Street and M.B.B.R Avenue (Reach -1) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17321,Roads,Completed,NL-VALASARAVAKKAM,145,999000,"Forming the Cement Concrete Road at Sakthi Nagar 13th Street and M.B.B.R Avenue (Reach -2) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17322,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,977000,"Improvement to Side Drain at Muniappa Nagar Thiruvalluvar Salai (Reach-1) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17323,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,977000,"Improvement to Side Drain at Muniappa Nagar Thiruvalluvar Salai (Reach-2) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17324,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,927000,"Improvement to Side Drain at Krishna Nagar 5th Cross Street and Cross Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17326,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,728000,"Improvement to Side Drain at Sakthi Nagar 13th Street and M.B.B.R. Avenue in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17328,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,906000,"Improvement to Side Drain at Santha Avenue Main Road in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17331,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,662000,"Improvement to Side Drain at Sakthi Nagar C Block 24th Street in Dn 145, Unit 33, Zone 11 (Councilor Fund)",Own Sources,11,2015-16,2017-18 NL/2015-16/17387,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,890000,"Improvement to Side Drain at Pallvan Nagar Chelliamman Koil Street (Reach -2) and School 3rd Cross Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17388,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,890000,"Improvement to Side Drain at Pallvan Nagar Chelliamman Koil Street (Reach -1) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17424,Roads,Completed,NL-VALASARAVAKKAM,150,994000,"Supplying and Fixing Street Name Board at Arunachalam Nagar, Budhar Colony, Devi Nagar, Karambakkam Cross Streets, Mahalakshmi Nagar, Mothi Nagar, Ponni Nagar and Kaveri Nagar all Streets In Dn 150 U 34 Z XI",Own Sources,11,2015-16,2016-17 NL/2015-16/17525,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,987000,"Improvements to Existing Side Drain at at Thiruveethi Amman Koil 2nd Street in Dn-153, U-34, Zone-XI",Own Sources,11,2015-16,2020-21 NL/2015-16/1754,Roads,Completed,NL-VALASARAVAKKAM,155,1435000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Royala Nagar 2nd Cross Street, Royala Nagar 6th Cross Street, Eswaran Nagar 4th Street in division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/1755,Roads,Completed,NL-VALASARAVAKKAM,155,1374000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Royala Nagar 1st Cross Street, Moogambigai Nagar in Dn -155, Unit - 34, Zone - 34",Own Sources,11,2015-16,2016-17 NL/2015-16/1756,Roads,Completed,NL-VALASARAVAKKAM,155,1412000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Periyar Salai, Amman Nagar 2nd Cross Street, Royala Nagar 1st Cross Street, Bakyalakshmi Nagar 1st Street in division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/1757,Roads,Completed,NL-VALASARAVAKKAM,155,1351000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kannadasan Nagar 1st Street, Amman Nagar 2nd Street, Bakthivedhananda Avenue 2nd Street, Bakyalakshmi Nagar 3rd Street, Bakyalakshmi Nagar 4th Street, Royala Nagar 3rd Cross Street in division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/1761,Roads,Completed,NL-VALASARAVAKKAM,155,1282000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Eswaran Nagar 1st Street, Eswaran Nagar 2nd Street, Eswaran Nagar 3rd Street, Balaji Avenue 1st Street, Azhagapuri Nagar 1st Main Road in division 155, unit-34, zone- 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17651,Roads,Completed,NL-VALASARAVAKKAM,145,809000,"Forming the Cement Concrete Road at Muniappan Nagar Thiruvalluvar Salai (Reach -3) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/17692,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,728000,"Improvement to Side Drain at Sakthi Nagar 13th Street and M.B.B.R. Avenue (Reach -2) in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/19677,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,721000,"CONSTRUCTION OF RAIN WATER PUMPING STATION FOR DEWATERING THE STAGINATED RAIN WATER (DUE TO NORTH EAST MONSOON) FROM SRI KRISHNA NAGAR 27TH STREET IN DIV-147, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/1980,Buildings,Completed,NL-VALASARAVAKKAM,155,997000,"Construction of 16th day CEREMANEY HALL at Bajanai Koi Street in Division - 155, Unit - 34, Zone - 11",Own Sources,11,2015-16,2016-17 NL/2015-16/1991,Roads,Completed,NL-VALASARAVAKKAM,155,993000,"Supplying and fixing of street name board at Giri Nagar, Thamil Nagar, Alagapuri Nagar, Andavar Nagar, Sriram Nagar, Bakyalakshmi Nagar, Thirupathi Nagar, Royala Nagar 2nd &3rd Main Road, Chellamal Nagar, Moogambikai nagar, Egambara(n) naicker street, Sri Karpagamabal Nagar (Thiruvalluvar Salai) and Nethaji Nagar , in DN-155, UNIT-34 ,ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2024,Roads,Completed,NL-VALASARAVAKKAM,155,993000,"Suppling and Fixing Name Board at Sri Lakshmi Nagar, Barathi Nagar, Madhavan Street, Bakthivedhandha avenue, Gandhi nagar, Eswaran Koil Street, Annai Sathya Nagar, Kamatchi Amman Koil Street, Kannadhasan Nagar, Sundari Garden,Moogambikai Street, Jai Balaji Nagar Annex and Vivekanandha Nagar in Divison - 155, Unit - 34, Zone - 11",Own Sources,11,2015-16,2016-17 NL/2015-16/20252,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,874000,"Desilting at Nolambur Canal Kavimani Salai to Mugappair West Main Road Chainage 735 to 1200m at Dn-143, Unit-32, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/20512,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,962000,"Preventive measures of mosquito menace removal of Hyacinth, Floating materials in waterways at Kambar Nagar Bridge to VGP Amutha Nagar in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/20542,Roads,Completed,NL-VALASARAVAKKAM,150,996000,"Supplying and Fixing Street Name Board at S.S. Nagar, Samayapuram Nagar, Sriram Nagar, Murthi Nagar, Visvanathan Nagar and Cross Streets, Jaya Nagar and Chettiyar Agaram all Streets In Dn 150 U 34 Z XI",Own Sources,11,2015-16,2016-17 NL/2015-16/20543,Roads,Completed,NL-VALASARAVAKKAM,150,998000,"Supplying and Fixing Street Name Board at Maruthi Nagar Thundalam Anna Nagar, Vijayalakshmi Nagar, Thundalam T.V.K. Nagar all Streets In Dn 150 U 34 Z XI",Own Sources,11,2015-16,2016-17 NL/2015-16/20546,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,999000,"Improvements to side drain at K.V.K.Samy street in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/20547,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,998000,"Improvements to side drain at Kumaran street in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/20549,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,700000,"Improvements to side drain at Anjukoum street in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/20550,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,700000,"Improvements to side drain at Anjukoum street Kadambadiamman koil in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/2060,Roads,Completed,NL-VALASARAVAKKAM,154,1380000,"Forming road cut restoration using GSB, WMM, RMC 40 for under ground sewage system and water supply facilities work at periyar 1st street, udayar st & venkateswara nagar 6th st in division -154, Unit-34, Zone-11",Own Sources,11,2015-16,2017-18 NL/2015-16/2061,Roads,Completed,NL-VALASARAVAKKAM,154,1150000,"Forming road cut restoration using GSB, WMM, RMC 40 for under ground sewage system and water supply facilities work at venkateswara nagar 11th st & 13th street in division -154, Unit-34, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/2065,Roads,Completed,NL-VALASARAVAKKAM,154,1120000,"Forming road cut restoration using GSB, WMM, RMC 40 for under ground sewage system and water supply facilities work at venkateswara nagar 26th st, jaganatha street & Natarajan street in division -154, Unit-34, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/20655,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,720000,"Improvements to side drain at Balaji nagar 5th street in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/20656,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,720000,"mprovements to side drain at Balaji nagar 6th street in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/20658,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,689000,"Improvements to side drain at Sarswathi nagar 5th street in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/20663,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,998000,"Improvements to side drain at Saraswathi nagar Main Road (saraswathi nagar 5th street to saraswathi nagar 3rd street in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/2068,Roads,Completed,NL-VALASARAVAKKAM,154,1170000,"Forming road cut restoration using GSB, WMM, RMC 40 for under ground sewage system and water supply facilities work at Balambigai nagar 4th st, Burial ground(Star st) & Ambedkar st in division -154, Unit-34, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/20686,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,998000,"Improvements to side drain at Saraswathi nagar Main Road (Saraswathi nagar 3rd street to Thiruvalluvar salai in Div-148,Un-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/2070,Buildings,Completed,NL-VALASARAVAKKAM,154,990000,"Construction of 16th day ceremony hall at Kambar salai in Dn-154, Unit-34, Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/2085,Roads,Completed,NL-VALASARAVAKKAM,143,1499000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Vembuliamman Koil Street, Madha Koil 1st Street, Vallalar Street and Tanu Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2102,Roads,Completed,NL-VALASARAVAKKAM,143,1375000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Vallalar Street Pradana Road, 2nd Main Road Cross Street, 1st Main Road, 1st Main Road Cross Street and Madha Koil 4th Street to Madha Koil 8th Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2109,Roads,Completed,NL-VALASARAVAKKAM,143,1220000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Chinna Nolambur Union Salai (Reach-2) in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2110,Roads,Completed,NL-VALASARAVAKKAM,143,1377000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at 8th Street 2nd Cross Street and Perumal Koil Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/21102,Roads,Completed,NL-VALASARAVAKKAM,155,950000,"Attending Patch for Flood Damage Roads at Ragavendra 1st Street and Ragavendra 2nd Street in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21113,Roads,Completed,NL-VALASARAVAKKAM,155,975000,"Attending Patch for Flood Damage Roads at Nehru Nagar Main Road and Moogambigai Nagar 4th Street, in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21155,Roads,Completed,NL-VALASARAVAKKAM,148,456000,"Attenting patch work at Abirami nagar 1st street and jayaram nagar 1st street+ C.D.N.nagar main road c.d.n.nagar 13th street to c.d.n.nagar 16th street junction in Div-148,Un-33,ZO-11",Own Sources,11,2015-16,2016-17 NL/2015-16/21158,Roads,Completed,NL-VALASARAVAKKAM,148,950000,"Attenting patch work at Abirami nagar 2nd street jayaram nagar 1st main road+Anbu Nagar 9th street in Div-148,Un-33,ZO-11",Own Sources,11,2015-16,2016-17 NL/2015-16/21159,Roads,Completed,NL-VALASARAVAKKAM,148,950000,"Attenting patch work at Abirami nagar 3rd street jayaram nagar main road +Anbu Nagar 9th street+Anbu Nagar 5th street +Anbu Nagar 3rd street in Div-148,Un-33,ZO-11",Own Sources,11,2015-16,2016-17 NL/2015-16/21165,Buildings,Completed,NL-VALASARAVAKKAM,152,963000,"Providing G.I. Sheet Roof in front of the zonal office and improvements works in ground floor at arcot road in div 152, unit 33 zone X1",Own Sources,11,2015-16,2017-18 NL/2015-16/21167,Roads,Completed,NL-VALASARAVAKKAM,155,898000,"Attending Patch for Flood Damage Roads at Moogambigai Nagar 1st Street, Moogambigai Nagar 2nd Street and Moogambigai Nagar 3rd Street in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21168,Roads,Completed,NL-VALASARAVAKKAM,155,870000,"Attending Patch for Flood Damage Roads at Gangai Avenue 1st Street,Gangai Avenue 2nd Street, Eswaran Koil Street and Ragavendra 3rd Street in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21169,Roads,Completed,NL-VALASARAVAKKAM,155,999000,"Attending Patch for Flood Damage Roads at Anish Nagar 1st Street and Anish Nagar 2nd Street in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21171,Roads,Completed,NL-VALASARAVAKKAM,155,975000,"Attending Patch for Flood Damage Roads at Sathya Sivam Street and Sathya Sivam Street Lane in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21172,Roads,Completed,NL-VALASARAVAKKAM,155,999000,"Attending Patch for Flood Damage Roads at Annai Sathya Nagar 1st Street in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21173,Roads,Completed,NL-VALASARAVAKKAM,155,912000,"Attending Patch for Flood Damage Roads at Annai Sathya Nagar 2nd Street in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21174,Roads,Completed,NL-VALASARAVAKKAM,155,961000,"Attending Patch for Flood Damage Roads at Annai Sathya Nagar 3rd Street in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21175,Roads,Completed,NL-VALASARAVAKKAM,155,966000,"Attending Patch for Flood Damage Roads at Annai Sathya Nagar 4th Street, Annai Sathya NAgar 4th Street 1st Lane and Annai Sathya NAgar 4th Street 2nd Lane in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21176,Roads,Completed,NL-VALASARAVAKKAM,155,981000,"Attending Patch for Flood Damage Roads at Rayala Nagar 2nd Main Road (from Thiruvalluvar salai to Bakiyalakshmi Nagar) , in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21177,Roads,Completed,NL-VALASARAVAKKAM,155,981000,"Attending Patch for Flood Damage Roads at Rayala Nagar 2nd Main Road (from Bakiyalakshmi Nagar to Rayala Nagar 4th Street) in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21178,Roads,Completed,NL-VALASARAVAKKAM,155,981000,"Attending Patch for Flood Damage Roads at Rayala Nagar 3rd Main Road (from Thiruvalluvar salai to Bakiyalakshmi Nagar), in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21179,Roads,Completed,NL-VALASARAVAKKAM,155,981000,"Attending Patch for Flood Damage Roads at Rayala Nagar 3rd Main Road (from Bakiyalakshmi Nagar to Rayala Nagar 4th Street) in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/2118,Buildings,Completed,NL-VALASARAVAKKAM,152,967000,"Improvement works at zonal office first floor, Arcot Road in div 152 unit 33 zone11",Own Sources,11,2015-16,2016-17 NL/2015-16/21219,Roads,Completed,NL-VALASARAVAKKAM,155,968000,"Attending Patch for Flood Damage Roads at Natesan Nagar Main Road, Kothari Nagar 1st Main Road and Gangaiya Avenue Main Road in Dn-155, Unit - 34, Zone - XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/2132,Buildings,Completed,NL-VALASARAVAKKAM,152,756100,providing aluminium partition second floor and E.E. Room toilet ground floor at zonal office 11 in div 152 unit33 zone11,Own Sources,11,2015-16,2017-18 NL/2015-16/2133,Parks,Completed,NL-VALASARAVAKKAM,155,854000,"ANNUAL MAINTENANCE OF PARK AT JAI BALAJI NAGAR, ALAGAPURI NAGAR IN DN.155, U 34,ZONE XI.(EMPLOYED QUALIFIED DIPLOMA IN HORTICULTURE FOR TWO YEARS PARK MAINTENANCE)",Own Sources,11,2015-16,2017-18 NL/2015-16/2134,Parks,Completed,NL-VALASARAVAKKAM,155,850000,"ANNUAL MAINTENANCE OF PARK AT GIRI NAGAR, ESWARAN NAGAR IN DN.155, U 34,ZONE XI.(EMPLOYED QUALIFIED DIPLOMA IN HORTICULTURE FOR TWO YEARS PARK MAINTENANCE)",Own Sources,11,2015-16,2017-18 NL/2015-16/2135,Parks,Completed,NL-VALASARAVAKKAM,155,420000,"ANNUAL MAINTENANCE OF PARK AT KURINJI NAGAR PARK IN DN 154, U 34,ZONE XI.(EMPLOYED QUALIFIED DIPLOMA IN HORTICULTURE FOR TWO YEARS PARK MAINTENANCE)",Own Sources,11,2015-16,2017-18 NL/2015-16/2136,Parks,Completed,NL-VALASARAVAKKAM,155,422000,"ANNUAL MAINTANANCE OF PARK AT K.P. NAGAR PARK IN DIVISION - 155, UNIT-34, ZONE-11. (EMPLOYED QUALIFIED DIPLOMA IN HORICULTURE FOR TWO YEARS PARK MAINTANANCE)",Own Sources,11,2015-16,2017-18 NL/2015-16/2137,Parks,Completed,NL-VALASARAVAKKAM,150,760000,"ANNUAL MAINTENANCE OF SRI PARASNATH NAGAR PARK AT (CHENNAI CORPORATION PARK ) SANTHOSH BHAI STREET IN DN.150, U 34, Z 11. (EMPLOYED QUALIFIED DIPLOMA IN HORTICULTURE FOR TWO YEARS PARK MAINTENANCE)",Own Sources,11,2015-16,2017-18 NL/2015-16/21758,Roads,Completed,NL-VALASARAVAKKAM,152,585000,"Strengthening and relaying the existing bituminous damaged road at suresh nagar 1st street, Division-152, U-33, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/21773,Roads,Completed,NL-VALASARAVAKKAM,152,161000,"Strengthening and relaying the existing bituminous damaged road at suresh nagar 2nd street, Division-152, U-33, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/21781,Roads,Completed,NL-VALASARAVAKKAM,152,743000,"Strengthening and relaying the existing bituminous damaged road at kadambadi Amman Sannathi Street, Division-152, U-33, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/21786,Roads,Completed,NL-VALASARAVAKKAM,152,677000,"Strengthening and relaying the existing bituminous damaged road at Kadambadi Amman 3rd Street, Division-152, U-33, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/2179,Parks,Completed,NL-VALASARAVAKKAM,152,997800,"Improvement of Children play ground at veerapa nagar in division 152, unit - 33, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/21796,Roads,Completed,NL-VALASARAVAKKAM,152,931000,"Strengthening and relaying the existing bituminous damaged road at SVS Nagar 1st main road , Division-152, U-33, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/21800,Roads,Completed,NL-VALASARAVAKKAM,144,737000,"LAYING OF CEMENT CONCRETE ROAD AT FISH MARKET ROAD IN DIV-144, UNIT-32, ZONE-XI",Loans And Grants,11,2015-16,2016-17 NL/2015-16/21802,Roads,Completed,NL-VALASARAVAKKAM,153,865000,"Providing B.T Patch Work Flood Damage Road at Ganesh Avenue 9th Street in Dn-153, U-34, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/21805,Roads,Completed,NL-VALASARAVAKKAM,152,251000,"Strengthening and relaying the existing bituminous damaged road at Kannammal 2nd cross street, Division-152, U-33, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/21812,Roads,Completed,NL-VALASARAVAKKAM,153,811000,"Providing B.T Patch Work Flood Damage Road at Nakkeran Street in Dn-153, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21825,Roads,Completed,NL-VALASARAVAKKAM,153,811000,"Providing B.T Patch Work Flood Damage Road at Udaya Nagar Main Road in Dn-153, U-34,Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/21832,Roads,Completed,NL-VALASARAVAKKAM,153,865000,"Providing B.T Patch Work Flood Damaged Road at Ganesh Avenue 8th Street in Dn-153, U-34, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/21838,Roads,Completed,NL-VALASARAVAKKAM,153,919000,"Providing B.T Patch Work Flood Damaged Road at Ganga Kaveri Street in Dn-153,U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21843,Roads,Completed,NL-VALASARAVAKKAM,153,998000,"Providing B.T Patch Work Flood Damaged Road at Ramasamy Nagar 3rd Street, Ramasamy Nagar 4th Street in Dn-153, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/21854,Roads,Completed,NL-VALASARAVAKKAM,153,811000,"Providing B.T Patch Work Flood Damaged Road at Ekambaram Street, Adhibhagavan Nagar 2nd Street. in Dn-153, U-34,Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/2208,Roads,Completed,NL-VALASARAVAKKAM,143,1365000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Kamaraj Street, Thilagar Street, Mahathma Gandhi Cross Street and Gurusamy Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2210,Roads,Completed,NL-VALASARAVAKKAM,143,1482000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at 3rd Main Road and 2nd Main Road in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2211,Roads,Completed,NL-VALASARAVAKKAM,143,895000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Madha Koil 3rd Street, Madha Koil 2nd Street and Sakthi Nagar 2nd Avenue in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2212,Roads,Completed,NL-VALASARAVAKKAM,143,1486000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Mugappair west Cross Street, Mugappair 7th Cross Street, 8th Cross Street, Channel Road and Sakthi Nagar 3rd Avenue in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2213,Roads,Completed,NL-VALASARAVAKKAM,143,1435000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Sakthi Nagar 4th Avenue 1st Cros Street and Channel Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2214,Roads,Completed,NL-VALASARAVAKKAM,143,1499000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Mugappair Bharathi Salai in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2222,Roads,Completed,NL-VALASARAVAKKAM,143,1496000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at 4th Cross Street, Andal ammal Street, Pratish Street, R.R. Street and Mahathma Gandhi Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/22244,Roads,Completed,NL-VALASARAVAKKAM,152,915500,"Attending FLOOD damaged roads Patch work at Sarojini street, Dhanalakshmi St and Elumalai St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22245,Roads,Completed,NL-VALASARAVAKKAM,152,764500,"Attending FLOOD damaged roads Patch work at Singaravelan street and Durai Raj St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22246,Roads,Completed,NL-VALASARAVAKKAM,152,757500,"Attending FLOOD damaged roads Patch work at Jeevanandhan street and Varathan St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22247,Roads,Completed,NL-VALASARAVAKKAM,152,656000,"Attending FLOOD damaged roads Patch work at Thiruppur Kumaran Street and Sai Ram Avenue 1st Street in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22248,Roads,Completed,NL-VALASARAVAKKAM,152,641000,"Attending FLOOD damaged roads Patch work at Arumuga Navalar street and Suresh Nagar Main Road in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22250,Roads,Completed,NL-VALASARAVAKKAM,152,650000,"Attending FLOOD damaged roads Patch work at Ramalinga Vallalar street and Varathan St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22251,Roads,Completed,NL-VALASARAVAKKAM,152,550000,"Attending FLOOD damaged roads Patch work at Kanthan street, Krishanan Kovil St, Velankanni School Road and Thiruvalluvar St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22252,Roads,Completed,NL-VALASARAVAKKAM,152,625000,"Attending FLOOD damaged roads Patch work at Kadamban street, Velankanni School Road, Thiruvalluvar St, Azhagiri St, Prakasam Salai, and Chowdry Nagar Main Road in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22253,Roads,Completed,NL-VALASARAVAKKAM,152,625000,"Attending FLOOD damaged roads Patch work at Seyon street and Vani Nagar in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22254,Roads,Completed,NL-VALASARAVAKKAM,152,410000,"Attending FLOOD damaged roads Patch work at Rukmani devi street and Sai Ram Avenue 2nd Street in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22255,Roads,Completed,NL-VALASARAVAKKAM,152,748000,"Attending FLOOD damaged roads Patch work at Annai Theresa Street and Kamarajar St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22256,Roads,Completed,NL-VALASARAVAKKAM,152,966000,"Attending FLOOD damaged roads Patch work at Muthumari amman koil street (Janaki Nagar Et),Subramaniya Samy Nagar main road, Subramaniya Samy Nagar 2nd, 3rd Street in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22257,Roads,Completed,NL-VALASARAVAKKAM,152,641000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 9th street in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22259,Roads,Completed,NL-VALASARAVAKKAM,152,966000,"Attending FLOOD damaged roads Patch work at Chowdry nagar 11th street,Subramaniya Samy Nagar 4th,5th,6th,7th Street SVS Nagar 2nd Main Road in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22260,Roads,Completed,NL-VALASARAVAKKAM,152,275000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 3rd street and Bharthiyar 3rd Cross St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22261,Roads,Completed,NL-VALASARAVAKKAM,152,600000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 4th street and Chowdry Nagar 5th street in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22262,Roads,Completed,NL-VALASARAVAKKAM,152,417000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 6th street and Lamech St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22264,Roads,Completed,NL-VALASARAVAKKAM,152,388000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 8th street,Subramaniya Samy Nagar Main Road and Subramaniya Samy Nagar 2nd Street in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22265,Roads,Completed,NL-VALASARAVAKKAM,152,833000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 10th street, Kamarajar St and Bharathi Nagar in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22266,Roads,Completed,NL-VALASARAVAKKAM,152,453000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 1st street and SVS Nagar Annexe 5th St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22267,Roads,Completed,NL-VALASARAVAKKAM,152,417000,"Attending FLOOD damaged roads Patch work at Chowdry Nagar 2nd street and SVS Nagar Annexe 1st St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22268,Roads,Completed,NL-VALASARAVAKKAM,152,417000,"Attending FLOOD damaged roads Patch work at Muthulakshmi street,SVS Nagar 13th St and SVS Annexe 2nd St in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22273,Roads,Completed,NL-VALASARAVAKKAM,152,750000,"Attending FLOOD damaged roads Patch work at Janaki Nagar 6th street and Majestic Colony Main Road in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22274,Roads,Completed,NL-VALASARAVAKKAM,152,367000,"Attending FLOOD damaged roads Patch work at Janaki Radha Street in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22280,Roads,Completed,NL-VALASARAVAKKAM,152,600000,"Attending FLOOD damaged roads Patch work at Bethaniya Nagar main road Reach-1 ch. 0.00 m to 150.00 m in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22281,Roads,Completed,NL-VALASARAVAKKAM,152,600000,"Attending FLOOD damaged roads Patch work at Bethaniya Nagar main road Reach-2 ch. 151.00 m to 300.00 m in Division 152, unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22572,Roads,Completed,NL-VALASARAVAKKAM,151,919000,"Providing BT Patch Work for the Flood Damaged Road at Lakshmi Nagar 3rd Cross Street (West), in Dn-151, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/22574,Roads,Completed,NL-VALASARAVAKKAM,151,919000,"Providing BT Patch Work for the Flood Damaged Road at Lakshmi Nagar 3rd Cross Street (East) in Dn-151, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/22582,Roads,Completed,NL-VALASARAVAKKAM,151,971000,"Providing BT Patch Work for the Flood Damaged Road at Lakshmi Nagar Extn 7th Main Road, in Dn-151, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/22584,Roads,Completed,NL-VALASARAVAKKAM,151,541000,"Providing BT Patch Work for the Flood Damaged Road at Navamani Street, n Dn-151, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/22613,Roads,Completed,NL-VALASARAVAKKAM,148,253000,"Relaying The Road with Cement Concrete at CDN Nagar 5th c/s st+ Periyar Nagar Azhgiri Salai in Div 148,U 33 Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22653,Roads,Completed,NL-VALASARAVAKKAM,148,251000,Relaying The Road with Cement Concrete at CDN Nagar 3rd c/s st + Kannadhsan street in Dn 148 U 33 Zn 11,Loans And Grants,11,2015-16,2016-17 NL/2015-16/22669,Roads,Completed,NL-VALASARAVAKKAM,148,897000,"Relaying The Road with Cement Concrete at CDN Nagar 1st c/s street +Gandhi street in Dn 148, U 33, Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22676,Roads,Completed,NL-VALASARAVAKKAM,148,586000,Relaying The Road with Cement Concrete at Balaji Nagar 5th st in Dn 148 U 33 Zn 11,Loans And Grants,11,2015-16,2016-17 NL/2015-16/22684,Roads,Completed,NL-VALASARAVAKKAM,148,275000,Relaying The Road with Cement Concrete at Balaji Nagar 6th st in Dn 148 U 33 Zn 11,Loans And Grants,11,2015-16,2016-17 NL/2015-16/22692,Roads,Completed,NL-VALASARAVAKKAM,148,794000,"Relaying Road with Cement Concrete at Mettukuppam Mandaveli St in Dn 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22703,Roads,Completed,NL-VALASARAVAKKAM,148,793000,"Relaying Road with Cement Concrete at Mettukuppam Othavadai St in Div 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22706,Roads,Completed,NL-VALASARAVAKKAM,148,207000,"Relaying Road with Cement Concrete at Periyar Nagar Anna Salai 4th c/s St in Div 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22711,Roads,Completed,NL-VALASARAVAKKAM,148,654000,"Relaying Road with Cement Concrete at Periyar Nagar Anna Salai 2nd c/s St in Div 148, U 33,Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22715,Roads,Completed,NL-VALASARAVAKKAM,148,342000,"Relaying Road with Cement Concrete at Periyar Nagar Anna Salai 1st c/s St in Dn 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22722,Roads,Completed,NL-VALASARAVAKKAM,148,443000,"Relaying Road with Cement Concrete at Periyar Nagar Azhagiri Salai in Div 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22730,Roads,Completed,NL-VALASARAVAKKAM,148,1380000,"Relaying Road with Cement Concrete at Nesammal Nagar Madhavan St in Div 148, U 33,Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22731,Roads,Completed,NL-VALASARAVAKKAM,148,249000,"Relaying Road with Cement Concrete at Sakthivel Nagar 1st St in Dn 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22732,Roads,Completed,NL-VALASARAVAKKAM,148,490000,"Relaying Road with Cement Concrete at Periyar Nagar Balavinayagar St in Div 148, U 33,Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22735,Roads,Completed,NL-VALASARAVAKKAM,148,972000,"Relaying Road with Thangal karai Main Road reach-2 in Dn 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22739,Roads,Completed,NL-VALASARAVAKKAM,148,585000,"Relaying Road with Periyar Nagar Anna Salai in Dn 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22823,Roads,Completed,NL-VALASARAVAKKAM,149,629000,"Attending the Patch Work at Cheran Street and Chozan Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22824,Roads,Completed,NL-VALASARAVAKKAM,149,649000,"Attending the Patch Work at Kattabomman Street, Nakeeran Street and Agasthiyar Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22833,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending the Patch Work at Gandhi Road Part -1 and Nehru Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22834,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending the Patch Work at Gandhi Road Part -2 and Radha Krishnan Salai in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22835,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending the Patch Work at Gandhi Road Part -3 and Thiruvalluvar Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22836,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending the Patch Work at Gandhi Road Part -4 and Vanjinathan Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22837,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending Attending the Patch Work at Gandhi Road Part -5 and Sri Aravinthar Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22838,Roads,Completed,NL-VALASARAVAKKAM,149,811000,"Attending the Patch Work at Kamarajar Salai Part -1 Marutham Street and Mullai Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/2284,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,400000,"DESILTING IN OFFICERS COLONY,ANJENEAYER KOVIL St,RAM KRISHNA NAGAR MAIN ROAD,NEW COLONY 1st CROSS St,NEW COLONY MAIN ROAD,THIRUMURUGAN NAGAR MAIN ROAD, KAMALA NAGAR MAIN ROAD&LANE, ANNA SALAI,LAKSHMI NAGAR EXT 1st MAIN ROAD KUPPUSWAMY St, PERUMAL KOIL St, POOTHAPEDU MAIN ROAD, NSC BOSE NAGAR LAKSHMI St,VENKATESHWARA NAGAR 23rd St. IN DIVISION-151,UNIT-34,ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/22840,Roads,Completed,NL-VALASARAVAKKAM,149,811000,"Attending the Patch Work at Kamarajar Salai Part -2 and Syndicate Colony Main Road in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22841,Roads,Completed,NL-VALASARAVAKKAM,149,811000,"Attending the Patch Work at Kamarajar Salai Part -3 and SBS Colony Main Road in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22843,Roads,Completed,NL-VALASARAVAKKAM,149,405000,"Attending the Patch Work at Kamarajar Salai Part -4 and Thirumalai Nagar Main Road in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22845,Roads,Completed,NL-VALASARAVAKKAM,149,346000,"Attending the Patch Work at Patel Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22848,Roads,Completed,NL-VALASARAVAKKAM,149,649000,"Attending the Patch Work at Chithambaranar Street and Murali Krishna Nagar Main Road in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22851,Roads,Completed,NL-VALASARAVAKKAM,149,425000,"Attending the Patch Work at Park Street and Ramesh 1st Street to 4th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22855,Roads,Completed,NL-VALASARAVAKKAM,149,649000,"Attending the Patch Work at Indra Street, Velan Nagar Main Road and Velan Nagar 1st Street to 2nd Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22857,Roads,Completed,NL-VALASARAVAKKAM,149,884000,"Attending the Patch Work at Rajaji Street and Velan Nagar 3rd Street to 6th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22859,Roads,Completed,NL-VALASARAVAKKAM,149,541000,"Attending the Patch Work at C.V. Raman Street Part -1 and Velan Nagar 7th Street to 9th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22860,Roads,Completed,NL-VALASARAVAKKAM,149,541000,"Attending the Patch Work at C.V. Raman Street Part -2 and Radha Avenue 1st Street to 4th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22864,Roads,Completed,NL-VALASARAVAKKAM,149,779000,"Attending the Patch Work at V.V. Giri Street and Radha Avenue 5th Street to 7th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22866,Roads,Completed,NL-VALASARAVAKKAM,149,486000,"Attending the Patch Work at Play Ground Street and Anbu Nagar 1st Street to 2nd Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22867,Roads,Completed,NL-VALASARAVAKKAM,149,681000,"Attending the Patch Work at Bharathiyar Street and Lakshmi Nagar 1st Street to 4th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22868,Roads,Completed,NL-VALASARAVAKKAM,149,486000,"Attending the Patch Work at Kambar Street Part -1 and Lakshmi Nagar 5th Street, 7th Street to 10th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22869,Roads,Completed,NL-VALASARAVAKKAM,149,486000,"Attending the Patch Work at Kambar Street Part -2 and AKR Nagar Main Road in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22872,Roads,Completed,NL-VALASARAVAKKAM,149,811000,"Attending the Patch Work at Indra Gandhi Road Part -1 and Angalaparameshwari Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22873,Roads,Completed,NL-VALASARAVAKKAM,144,1446000,"FORMING AND LAYING THE BT ROAD AT PERUMAL KOIL STREET (REACH-1) IN DIV-144,UNIT-32, ZONE-XI",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22875,Roads,Completed,NL-VALASARAVAKKAM,149,811000,"Attending the Patch Work at Indra Gandhi Road Part -2 and AKR Nagar 1st Street to 2nd Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22877,Roads,Completed,NL-VALASARAVAKKAM,149,811000,"Attending the Patch Work at Indra Gandhi Road Part -3 , AKR Nagar 3rd Street to 5th Street , in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22879,Roads,Completed,NL-VALASARAVAKKAM,149,811000,"Attending the Patch Work at Indra Gandhi Road Part -4 and Vijaya Nagar 1st Street to 2nd Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22881,Roads,Completed,NL-VALASARAVAKKAM,149,584000,"Attending the Patch Work at AGS Colony Main Road Part -1, Kanagathara Nagar Main Road and Sannathi Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22883,Roads,Completed,NL-VALASARAVAKKAM,149,584000,"Attending the Patch Work at AGS Colony Main Road Part -2, Thirukural Street, Thirupughazhal Street, Vyasar Street and Andal Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22884,Roads,Completed,NL-VALASARAVAKKAM,149,551000,"Attending the Patch Work at Sri Balaji Nagar, Senathiapathi Street, Arunagiri Street and Gugan Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22886,Roads,Completed,NL-VALASARAVAKKAM,149,941000,"Attending the Patch Work at BVR Nagar Main Road, Vel Murugan Street and Velavan Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22887,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending the Patch Work at Sabari Street, Thirupathi Main Road, Thirupathi Nagar 1st Street and 2nd Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22888,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending the Patch Work at Samantham Nagar Main Road and Thirupathi Nagar 3rd Street to 6th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22889,Roads,Completed,NL-VALASARAVAKKAM,149,973000,"Attending the Patch Work at Sastha Nagar 1st Street to 3rd Street and Brindavan Nagar 2nd Street, 5th Street and 8th Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22890,Roads,Completed,NL-VALASARAVAKKAM,149,1298000,"Attending the Patch Work at Venkateswara Nagar Main Road, Ramanujam Street, Antony Street, Chellammal Stree and Krishnamachari Street in Dn-149, Unit-33, Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/22893,Roads,Completed,NL-VALASARAVAKKAM,144,1446000,"FORMING AND LAYING THE BT ROAD AT PERUMAL KOIL STREET (REACH-2) IN DIV-144,UNIT-32, ZONE-XI",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22895,Roads,Completed,NL-VALASARAVAKKAM,144,1093000,"FORMING AND LAYING THE BT ROAD AT SATHYAMOORTHY NAGAR 1st, 2nd STREET AND SRI VENKATESWARA NAGAR MAIN ROAD EXTN. AND SRI VENKATESWARA NAGAR 1st CROSS STREET EXTN. IN DIV-144,UNIT-32, ZONE-XI",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22898,Roads,Completed,NL-VALASARAVAKKAM,150,1710000,"Laying CC road at Rajeshwari nagar 1st street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22900,Roads,Completed,NL-VALASARAVAKKAM,148,169700,Relaying the road at CDN Nagar Annexe 2nd st (part)in Dn 148 U 33 Z 11,Loans And Grants,11,2015-16,2016-17 NL/2015-16/22902,Roads,Completed,NL-VALASARAVAKKAM,150,2520000,"Laying CC road at Rajeshwari nagar 2nd street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22903,Roads,Completed,NL-VALASARAVAKKAM,150,810000,"Laying CC road at Mullai street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22905,Roads,Completed,NL-VALASARAVAKKAM,150,1400000,"Laying CC road at Arunachalam nagar 2nd street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22906,Roads,Completed,NL-VALASARAVAKKAM,150,348000,"Laying CC road at Arunachalam nagar 4th street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22907,Roads,Completed,NL-VALASARAVAKKAM,150,749000,"Laying CC road at Thiruvengadam 3rd street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22908,Roads,Completed,NL-VALASARAVAKKAM,150,571000,"Laying CC road at Avvai street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22909,Roads,Completed,NL-VALASARAVAKKAM,148,328000,Relaying the road at CDN Nagar Annexe 20th st+CDN Nagar Annexe 2nd st (part)+Periyar Anna Salai in Dn 148 U 33 Z 11,Loans And Grants,11,2015-16,2016-17 NL/2015-16/22910,Roads,Completed,NL-VALASARAVAKKAM,148,471000,Relaying the road at CDN Nagar 19th street+Thangal karai main road in Dn 148 U 33 Z 11,Loans And Grants,11,2015-16,2016-17 NL/2015-16/22911,Roads,Completed,NL-VALASARAVAKKAM,150,1727000,"Laying CC road at Arunachalam nagar 3rd street in Dn-150, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22923,Roads,Completed,NL-VALASARAVAKKAM,148,959000,"Relaying Road Thangal kara main road Reach I in Dn 148, U 33,Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22934,Roads,Completed,NL-VALASARAVAKKAM,148,712000,"Relaying Road at Meenakshi Amman Kumaran St in Div-148, U 33 Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22936,Roads,Completed,NL-VALASARAVAKKAM,145,1864000,"Forming and Laying BT roads at Sakthi nagar 9 to 12 streets in DN-145, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22940,Roads,Completed,NL-VALASARAVAKKAM,148,659000,"Relaying Road Abirami Nagar 2nd c/s St+Kanndhsan Streetin Div-148, U 33 Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22941,Roads,Completed,NL-VALASARAVAKKAM,145,1496000,"Forming and Laying BT roads at Sakthi nagar 13 th cross street in DN-145, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22948,Roads,Completed,NL-VALASARAVAKKAM,145,2870000,"Laying CC road at Thiruvalluvar 1 to 6 streets in DN-145, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22953,Roads,Completed,NL-VALASARAVAKKAM,145,3034000,"Forming the Cement Concrete Road at Palvadi 1st to 4th Streets, Erikarai St lane, Pallavan Nagar VOC st, Senthamizh Nagar Kumuthavalli avenue in DN-145, Unit-33, Zone-XI.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22964,Roads,Completed,NL-VALASARAVAKKAM,145,3031000,"Laying CC road at Sakthi nagar 2nd, 7thj, 15th part streets, Agathiyar nagar 2nd st, Sri krishna nagar 5th cross st, Moogambigai 8th cross st, Valliammal nagar 10th & 11 th streets in DN-145, U-34, Z-11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22966,Roads,Completed,NL-VALASARAVAKKAM,145,3090000,"Forming the Cement Concrete Road at Sakthi Nagar 3rd to 6th Streets and Sakthi Nagar C Block 20th, 24th and 25 Streets in DN-145, Unit-33, Zone-XI",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22984,Roads,Completed,NL-VALASARAVAKKAM,148,782000,"Relaying Road at Meenakshi Amman Nagar KVK Street in Div 148, U 33, Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22989,Roads,Completed,NL-VALASARAVAKKAM,148,495000,"Relaying Road at CDN Nagar 18th Street in Dn 148, U 33, Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/2299,Road Cut,Completed,NL-VALASARAVAKKAM,147,160000,"Road Cut Restoration Work Using GSB, WMM and RMC40 at Pallavan Nagar 6th Cross Street,Sri Krishna Nagar 19th Street,Sri Krishna Nagar 5th Street,Sri Krishna Nagar 2nd Main Road in Div-147,U-32,Z-X1.",Own Sources,11,2015-16,2016-17 NL/2015-16/22995,Roads,Completed,NL-VALASARAVAKKAM,148,856000,"Relaying Road at Meenakshi Amman Nagar VV Giri St in Dn 148, U 33, Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22997,Roads,Completed,NL-VALASARAVAKKAM,148,900000,"Relaying Road at Meenakshi Amman Nagar NSK St in Div 148, U 33, Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22998,Roads,Completed,NL-VALASARAVAKKAM,148,793000,"Relaying Road at Meenakshi Amman Nagar VOC St in Dn 148, U 33, Zn 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/22999,Roads,Completed,NL-VALASARAVAKKAM,148,750000,"Relaying Road at Abirami Nagar 3rd cross Street+Abirami Nagar 1st & 2nd cross street in Div 148, U 33, Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23001,Roads,Completed,NL-VALASARAVAKKAM,148,722000,"Relaying Road at Angamuthu Salai in Div 148, U 33, Z 11",Loans And Grants,11,2015-16,2016-17 NL/2015-16/2305,Parks,Completed,NL-VALASARAVAKKAM,152,979000,"Providing Children Playing Equipments & Greenary Arrangements In Veerapa Nagar Play Ground In Unit - 33, Division - 152, in Zone - XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2319,Playfields,Completed,NL-VALASARAVAKKAM,151,545000,Improvement of play fields at lakshmi Nagar Extenssion 6th Main Road in Dn 151 U 34 Zone 11.,Own Sources,11,2015-16,2016-17 NL/2015-16/2323,Playfields,Completed,NL-VALASARAVAKKAM,151,540000,Improvement of play fields at lakshmi Nagar 5th cross street in Dn 151 U 34 Zone 11.,Own Sources,11,2015-16,2016-17 NL/2015-16/23704,Roads,Completed,NL-VALASARAVAKKAM,150,897000,"ATTENDING PATCH WORK AT SRI PARASNATH NAGAR MAIN ROAD IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23708,Roads,Completed,NL-VALASARAVAKKAM,150,818000,"ATTENDING PATCH WORK AT SAYAR BAI AND SANTHOSH BAI STREET IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23709,Roads,Completed,NL-VALASARAVAKKAM,150,714000,"ATTENDING PATCH WORK AT MARUTHI NAGAR KUMARAN STREET AND SIVAN NAGAR MAIN ROAD ANNEX IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23713,Roads,Completed,NL-VALASARAVAKKAM,150,885000,"ATTENDING PATCH WORK AT SAMAYAPURAM 2ND CROSS STREEET AND SIVAN NAGAR MAIN ROAD ANNEX IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23715,Roads,Completed,NL-VALASARAVAKKAM,150,838000,"ATTENDING PATCH WORK AT PUNNIYAKOTTI NAGAR MAIN ROAD IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23716,Roads,Completed,NL-VALASARAVAKKAM,150,913000,"ATTENDING PATCH WORK AT THUNDALAM ANNA NAGAR PERUMAL KOIL 1ST STREET AND SAMAYAPURAM 4TH STREET REACH - 2 (CHAINAGE 201 M TO 320 M) IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23718,Roads,Completed,NL-VALASARAVAKKAM,150,913000,"ATTENDING PATCH WORK AT SAMAYAPURAM 4TH STREET REACH - 1 (CHAINAGE 0 M TO 200 M) IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23720,Roads,Completed,NL-VALASARAVAKKAM,150,740000,"ATTENDING PATCH WORK AT SAMAYAPURAM 5TH STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23726,Roads,Completed,NL-VALASARAVAKKAM,150,840000,"ATTENDING PATCH WORK AT THUNDALAM ALPHA COLLEGE ROAD IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23734,Roads,Completed,NL-VALASARAVAKKAM,150,751000,"ATTENDING PATCH WORK AT JAYA NAGAR CSI CHURCH STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23741,Roads,Completed,NL-VALASARAVAKKAM,150,913000,"ATTENDING PATCH WORK AT ANNAI ANJUGAM NAGAR AND JAI NAGAR MOSQUE STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23768,Roads,Completed,NL-VALASARAVAKKAM,150,986000,"ATTENDING PATCH WORK AT THUNDALAM ANNA NAGAR SANNATHI STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23792,Roads,Completed,NL-VALASARAVAKKAM,150,913000,"ATTENDING PATCH WORK AT THIRU. VI. KA 1ST AND 2ND STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23795,Roads,Completed,NL-VALASARAVAKKAM,150,995000,"ATTENDING PATCH WORK AT KARAMBAKKAM 1ST AND 3RD STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23797,Roads,Completed,NL-VALASARAVAKKAM,150,913000,"ATTENDING PATCH WORK AT DOSS MAIN ROAD REACH - 1 (CHAINAGE 0M TO 200 M) IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23801,Roads,Completed,NL-VALASARAVAKKAM,150,913000,"ATTENDING PATCH WORK AT DOSS MAIN ROAD REACH - 1 (CHAINAGE 201 M TO 400 M) IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23802,Roads,Completed,NL-VALASARAVAKKAM,150,959000,"ATTENDING PATCH WORK AT MOORTHY NAGAR 1ST, 2ND AND 3RD STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/23803,Road Cut,Completed,NL-VALASARAVAKKAM,153,616000,"CMWSSB- Road cut restoration work using GSB, WMM and RMC40 at R.E. Nagar 6th Street, Balamurugan Koil 1st to 2nd Street, Kattabomman Street, Ramakrishna Nagar 5th Avenue, Somasundaram 5th Avenue, Ramamoorthy Avenue 4th Street, Anna Street. Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/23805,Roads,Completed,NL-VALASARAVAKKAM,150,959000,"ATTENDING PATCH WORK AT PADMAVATHY NAGAR AND CROSS STREETS IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23807,Roads,Completed,NL-VALASARAVAKKAM,150,821000,"ATTENDING PATCH WORK AT SUBAGIRI NAGAR MAIN ROAD IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23810,Roads,Completed,NL-VALASARAVAKKAM,150,914000,"ATTENDING PATCH WORK AT DAS 1ST, 2ND AND 3RD STREET IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/23811,Road Cut,Completed,NL-VALASARAVAKKAM,153,632000,"CMWSSB- Road cut restoration work using GSB, WMM and RMC40 at R.E. Nagar Main Road Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/23817,Roads,Completed,NL-VALASARAVAKKAM,150,730000,"ATTENDING PATCH WORK AT DAS MAIN ROAD REACH - 3 ( CHAINAGE 401 M TO 560 M) IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/2406,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,998000,"Desilting work at SWD and Side Drain in Rajeswari Nagar, Kaveri Nagar, Arunachalam Nagar, Dharmaraja Nagar, Ponni Nagar, Viswanathan Nagar, Mothi Nagar, Devi Nagar, Kanthasamy Nagar, Buddhar Colony, Samayapuram, Mahalakshmi Nagar, Maruthi Nagar, Sivabootham Pilliyar Koil Street, Sivabootham Perumal Koil, Subahagiri Nagar, Thiru. Vi. Ka Nagar and Thundalam in Dn-150,Uint-34,Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/2413,Buildings,Completed,NL-VALASARAVAKKAM,151,998000,"CONSTRUCTION OF ADDITIONAL SHED IN AMMA CANTEEN AT ANJENEYAR KOIL STREET IN DN-151,U-34,Z-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/24313,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,927000,"IMPROVEMENTS TO STORM WATER DRAIN AT KULAKARAI STREET FROM SVS NAGAR 4TH STREET TO SVS NAGAR 1ST STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2017-18 NL/2015-16/24314,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,900000,"IMPROVEMENTS TO STORM WATER DRAIN AT KULAKARAI STREET FOM SVS NAGAR 1ST STREET TO AMBEDKAR STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/24315,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,993000,"IMPROVEMENTS TO STORM WATER DRAIN AT SCHOOL ROAD ON NORTHERN SIDE FROM SVS NAGAR 1ST MAIN ROAD IN DN151,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/24316,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,996000,"IMPROVEMENTS TO STORM WATER DRAIN AT SCHOOL ROAD ON SOUTHERN SIDE FROM SVS NAGAR 1ST MAIN ROAD IN DN151,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/24339,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,997000,"IMPROVEMENTS TO STORM WATER DRAIN AT ANNA STREET FROM LAKSHMI NAGAR 1ST MAIN ROAD TO SENTHIL NAGAR 5TH CROSS STREET IN DN151,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/24340,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,997000,"IMPROVEMENTS TO STORM WATER DRAIN AT ANNA STREET FROM SENTHIL NAGAR 5TH CROSS STREET TO HOSPITAL ROAD IN DN151,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/24341,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,997000,"IMPROVEMENTS TO STORM WATER DRAIN AT ANNA STREET FROM HOSPITAL ROAD TO KUPPUSAMY STREET IN DN151,U34,Z11.",Own Sources,11,2015-16,2018-19 NL/2015-16/24342,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,997000,"IMPROVEMENTS TO STORM WATER DRAIN AT ANNA STREET FROM KUPPUSAMY STREET TO GANAPATHY STREET IN DN151,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/24634,Buildings,Completed,NL-VALASARAVAKKAM,144,2777000,"CONSTRUCTION OF 2ND FLOOR IN WARD COUNCILOR CUM DIVISION OFFICE BUILDING IN MMDA COLONY 6th BLOCK 33rd STREET IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2468,Buildings,Completed,NL-VALASARAVAKKAM,151,768000,construction of compound wall at school road near 16th day ceremany hall in Dn:151 u 34 z 11.,Own Sources,11,2015-16,2016-17 NL/2015-16/2477,Footpath,Completed,NL-VALASARAVAKKAM,151,930000,"CONSTRUCTION OF PATHWAY AND SUPPLY,FIXING OF BENCH IN SCHOLL ROAD NEAR 16TH DAT CEREMANAY HALL IN DN 151 U 34 Z 11.",Own Sources,11,2015-16,2017-18 NL/2015-16/24821,Roads,Completed,NL-VALASARAVAKKAM,148,864500,"Attenting patch work at Balaji Nagar 2nd street and Anbu nagar Main road+ Anbu nagar 11th street in Div-148,Un-33,ZO-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24833,Roads,Completed,NL-VALASARAVAKKAM,148,864500,"Attenting patch work at Bhuvaneshwari Nagar Bhuvaneswari nagar Ganapathy + Gajalakshmi street +Kavi arasu Kannadhasan Street in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24836,Roads,Completed,NL-VALASARAVAKKAM,148,648375,"Attenting patch work at Bhuvaneshwari Nagar Bhuvaneswari nagar Ganapathy + Gajalakshmi street =Anbu Nagar 8th street in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24840,Roads,Completed,NL-VALASARAVAKKAM,148,706800,"Attenting patch work at Bhuvaneshwari Nagar GanapathyStreet to+ Lakshmi Nagar 4th c/s street junction + Gajalakshmi StreetStreet in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24841,Roads,Completed,NL-VALASARAVAKKAM,148,577600,"Attenting patch work at CDN Nagar 1st Street part1+ Pillaiyar Koil Street+ Anbu nagar 7th street in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24845,Roads,Completed,NL-VALASARAVAKKAM,148,577600,"Attenting patch work at C.D.N Nagar 1st Street part 2 + School street+ Pillayar koil street in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24846,Roads,Completed,NL-VALASARAVAKKAM,148,858880,"Attenting patch work at C.D.N Nagar 2nd Street +Dr.MGR salai to school street in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24848,Roads,Completed,NL-VALASARAVAKKAM,148,874000,"Attenting patch work at C.D.N Nagar 3rd Street junction to C.D.N Nagar 7th Street+C.D.N Nagar main road in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24849,Roads,Completed,NL-VALASARAVAKKAM,148,874000,"Attenting patch work at C.D.N Nagar 4th Street+ Kamaraj salai Devi karumari amman nagar 1st street junction to Dr.MGR Salai junction in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24850,Roads,Completed,NL-VALASARAVAKKAM,148,950000,"Attenting patch work at C.D.N Nagar 9th Street+ Kamaraj Salai Meenakshi Ammam Nagar Avvaiyar street junction to Devi karumari amman nagar 1st street junction in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24851,Roads,Completed,NL-VALASARAVAKKAM,148,950000,"Attenting patch work at C.D.N Nagar 10th Street + MettuKuppam Main Road Lakshmi Nagar 1st Main Road junction to Lakshmi nagar 4th c/s street junction in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24852,Roads,Completed,NL-VALASARAVAKKAM,148,950000,"Attenting patch work at C.D.N Nagar 11th Street+ Mettu kuppam Main Road Periyar Nagar Thangal Karai Street to Lakshmi Nagar 1st Main Road Junction in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24857,Roads,Completed,NL-VALASARAVAKKAM,148,997000,"Attenting patch work at Meenakshi Amman Nagar Avvaiyar Street to Ganapathi street junction + Meenakshi Amman Nagar Anjugam Street in DN-148,UN-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/24868,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,585000,Repair storm water drain and other Improvements works at various places in div 152 unit 33 zone11,Own Sources,11,2015-16,2016-17 NL/2015-16/2487,Roads,Completed,NL-VALASARAVAKKAM,143,1265000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at 12th Cross Street, Aishwarya Nagar, Padasalai Cross Street, VGN Avenue and VGN Avenue Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2488,Roads,Completed,NL-VALASARAVAKKAM,143,1363000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Chruch Street and 3rd Main Road, Ramalingam Street, 3rd Main Road Cross Street, 2nd Avenue, 2nd Street, 1st Street and Sakthi Nagar 1st Avenue in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2489,Roads,Completed,NL-VALASARAVAKKAM,143,1449000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Gajalakshmi Nagar 1st Street to Gajalakshmi 5th Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2490,Roads,Completed,NL-VALASARAVAKKAM,143,1478000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Church Street (Reach-1) in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2493,Roads,Completed,NL-VALASARAVAKKAM,143,1496000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at V.O.C. Street, Church Oppsite Road and Gajalakshmi Nagar 5th Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2495,Playfields,Completed,NL-VALASARAVAKKAM,151,215000,SUPPLYING AND FIXING OF GYM METERIAL AT BAJANAI KOIL STREET IN DN 151 U 34 Z 11.,Own Sources,11,2015-16,2016-17 NL/2015-16/2496,Roads,Completed,NL-VALASARAVAKKAM,143,1484000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Sriram Nagar Main Road, Chruch Road (Reach -2) and Gajalakshmi Nagar Main Road in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2497,Roads,Completed,NL-VALASARAVAKKAM,143,1472000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at 4th Main Road, Chanakiyan 1st Cross Street, Annamalai Avenue Park Street and Gopi Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2498,Roads,Completed,NL-VALASARAVAKKAM,143,1496000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at 2nd Cross Stret, 3rd Cross Street and Archana Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2501,Roads,Completed,NL-VALASARAVAKKAM,150,2113000,"ROAD CUT RESTORATION AT SAMAYAPURAM NAGAR 6TH STREET,KARAMBAKKAM 1ST STREET AND CHETTIYAR AGARAM MAIN CROSS STREET IN DN 150, UNIT-34, ZONE-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/2519,Roads,Completed,NL-VALASARAVAKKAM,143,1365000,"CMWSSB - Sewerage Facilities - Road cut restoration work using GSB, WMM and RMC40 at Vignesh Nagar Main Road, Vignesh Nagar and VGN Avenue Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25550,Roads,Completed,NL-VALASARAVAKKAM,151,360000,"ATTENDING LEVEL CORRECTION AT KUPPUSAMY STREET IN DN151,U34,Z11.",Own Sources,11,2015-16,2017-18 NL/2015-16/25594,Buildings,Completed,NL-VALASARAVAKKAM,144,998000,Construction Adhar Card centre at poonamallee high road div 144 unit 32 zone11,Own Sources,11,2015-16,2016-17 NL/2015-16/25644,Roads,Completed,NL-VALASARAVAKKAM,153,997000,"Providing B.T Patch Work Flood Damaged Road at Ramasamy Nagar Main Road in Dn-153, U-34, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/25655,Roads,Completed,NL-VALASARAVAKKAM,144,999990,"ATTENDING BT PATCH WORK AT AYYAVU NAGAR 2nd MAIN ROAD, AYYAVU NAGAR 1st, 2nd & 3rd CROSS STREETS IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25662,Roads,Completed,NL-VALASARAVAKKAM,144,964000,"ATTENDING BT PATCH AT EB OFFICE ROAD AND METTUKUPPAM MAIN ROAD (REACH 1) IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25663,Roads,Completed,NL-VALASARAVAKKAM,153,997000,"Providing B.T Patch Work Flood Damaged Road at Udaya Nagar 3rd Street in Dn-153, U-34, Z-XI..",Own Sources,11,2015-16,2016-17 NL/2015-16/25664,Roads,Completed,NL-VALASARAVAKKAM,144,915500,"ATTENDING BT PATCH AT EB OFFICE ROAD AND METTUKUPPAM MAIN ROAD (REACH 2) IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25666,Roads,Completed,NL-VALASARAVAKKAM,153,811000,"Providing B.T Patch Work Flood Damaged Road at Subashree Nagar 1st Main Road in Dn-153, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/25667,Roads,Completed,NL-VALASARAVAKKAM,144,999900,"ATTENDING BT PATCH AT OM SAKTHI NAGAR MAIN ROAD & VENKATESWARA NAGAR MAIN ROAD (REACH 1) IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25668,Roads,Completed,NL-VALASARAVAKKAM,153,811000,"Providing B.T Patch Work Flood Damaged Road at Sterling Avenue Main Road in Dn-153, U-34,Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25670,Roads,Completed,NL-VALASARAVAKKAM,153,811000,"Providing B.T Patch Work Flood Damaged Road at Cheran Street in Dn-153, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/25674,Roads,Completed,NL-VALASARAVAKKAM,144,920000,"ATTENDING BT PATCH WORK AT SANNATHI STREET & SATHYAMOORTHY NAGAR MAIN ROAD IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25677,Roads,Completed,NL-VALASARAVAKKAM,151,997000,"Providing B.T Patch Work Flood Damaged Road at Suresh Nagar Main Road and R.E Nagar 9th Street in Dn-153, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/25693,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,991000,"IMPROVEMENTS TO CULVERTS AT ANNA STREET FROM LAKSHMI NAGAR 1ST MAIN ROAD TO GANAPATHY STREET IN DN-151,U-34,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/25697,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,996000,"IMPROVEMENTS TO SIDE DRAIN AND CULVERT AT GANAPATHY STREET IN DN - 151, U - 34, Z - 11",Own Sources,11,2015-16,2016-17 NL/2015-16/25704,Buildings,Completed,NL-VALASARAVAKKAM,151,997000,"PAINTING THE OP,LABOUR WARD, NAMBIKKAI NILAIYAM, RCTC BUILDING, DENTAL BLOCK AND VACCINATION ROOM INSIDE CHINNA PORUR HOSPITAL IN DN - 151 U - 34 Z - 11",Own Sources,11,2015-16,2017-18 NL/2015-16/25709,Buildings,Completed,NL-VALASARAVAKKAM,151,993000,"IMPROVEMENTS TO THE SIDDHA BLOCK, OFFICE ROOM, OPERATION THEATRE, SHED, QUARTERS TYPE - I, TYPE - II AND TYPE - III BLOCKS INSIDE CHINNA PORUR HOSPITAL IN DN - 151 U - 34 Z - 11",Own Sources,11,2015-16,2016-17 NL/2015-16/25714,Buildings,Completed,NL-VALASARAVAKKAM,151,505000,"REPAIRS AND IMPROVEMENTS TO THE COMPOUND WALL AT CHINNA PORUR HOSPITAL IN DN - 151, U - 34, Z - 11",Own Sources,11,2015-16,2017-18 NL/2015-16/25723,Roads,Completed,NL-VALASARAVAKKAM,144,999000,"ATTENDING BT PATCH WORK AT KAMATCHI NAGAR 1ST MAIN ROAD, MMDA 4TH BLOCK MAIN ROAD IN DIV-144, UNIT-32, ZONE-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/25725,Roads,Completed,NL-VALASARAVAKKAM,152,300000,"Strengthening and realaying the existing bituminous damaged road at Subramainya Swamy nagar 1st street In Dn-152, Zone - XI",Loans And Grants,11,2015-16,2016-17 NL/2015-16/25729,Roads,Completed,NL-VALASARAVAKKAM,144,840000,"ATTENDING BT PATCH WORK AT VGP AMUDHA NAGAR 1ST MAIN ROAD, VARALAKSHMI NAGAR 3RD STREET IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25734,Roads,Completed,NL-VALASARAVAKKAM,144,999000,"ATTENDING BT PATCH WORK AT VISWAS NAGAR MAIN ROAD IN DIV-144, UNIT-32. ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25760,Roads,Completed,NL-VALASARAVAKKAM,144,990000,"ATTENDING BT PATCH WORK AT VARALAKSHMI NAGAR 3rd MAIN ROAD & 1st STREET IN DIV-144, UNIT-32. ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25766,Roads,Completed,NL-VALASARAVAKKAM,144,999000,"ATTENDING BT PATCH WORK AT MMDA 7th BLOCK MAIN ROAD IN DIV-144, UNIT-32. ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25776,Roads,Completed,NL-VALASARAVAKKAM,144,999000,"ATTENDING PATCH WORK BT ROAD AT VENKATESWARA NAGAR MAIN ROAD (REACH-2) & VENKATESWARA NAGAR 4TH STREET IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/25779,Buildings,Completed,NL-VALASARAVAKKAM,144,999000,"PROVIDING WATER SUPPLY,ELECTRICAL AND OTHER ARRANGEMENTS TO NEW FAIR PRICE CANTEEN AT AMMA UNAVAGAM IN DN144,U32,Z11.",Own Sources,11,2015-16,2017-18 NL/2015-16/25854,Roads,Completed,NL-VALASARAVAKKAM,153,811000,"Relaying the Flood Damaged road at Udaya Nagar Extn Main Road in Dn-153, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/25885,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,984000,"IMPROVEMENTS TO THE SIDE DRAIN AT GANGAI AMMAN KOIL STREET IN DN-154,U-34,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/25897,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,848000,"IMPROVEMENTS TO THE SIDE DRAIN AT VENUGOPAL STREET IN DN-154,U-34,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/25899,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,999000,"IMPROVEMENTS TO THE SIDE DRAIN AT KALAINGAR STREET IN DN-154,U-34,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/25900,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,997000,"IMPROVEMENTS TO THE SIDE DRAIN AT AGATHIYAR STREET AND GANGAI AMMAN KOIL STREET IN DN-154,U-34,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/25901,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,884000,"IMPROVEMENTS TO THE SIDE DRAIN AT BALAMBIGAI NAGAR 1ST MAIN ROAD STREET IN DN-154,U-34,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/25926,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,714000,"Construction of New Side Drain at Madhavan Street in DN - 155, U- 34,Z- 11",Own Sources,11,2015-16,2018-19 NL/2015-16/26400,Roads,Completed,NL-VALASARAVAKKAM,154,1000000,"Attending Patch for Flood Damage Roads at Venkateswara nagar 8th,9th, 15th and 26 th streets in division-154, unit-34, zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/26403,Roads,Completed,NL-VALASARAVAKKAM,154,926000,"Attending Patch for Flood Damage Roads at Venkateswara nagar 17th and 19 street in division-154, unit-34, zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/26406,Roads,Completed,NL-VALASARAVAKKAM,154,974000,"Attending Patch for Flood Damage Roads at Venkateswara nagar 5th, 16th and 11 th street in division-154, unit-34, zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/26407,Roads,Completed,NL-VALASARAVAKKAM,154,788000,"Attending Patch for Flood Damage Roads at Balambigai nagar main road (part), 1st street and lane and 2nd street in division-154, unit-34, zone11",Own Sources,11,2015-16,2016-17 NL/2015-16/26413,Roads,Completed,NL-VALASARAVAKKAM,154,740000,"Attending Patch for Flood Damage Roads at Umargayan, Jalauddin, Avvaiyar, Khalidhasan in division-154, unit-34, zone11",Own Sources,11,2015-16,2016-17 NL/2015-16/26415,Roads,Completed,NL-VALASARAVAKKAM,154,880000,"Attending Patch for Flood Damage Roads at Kanniappan, Ponnuswamy, Ramalingam streets in division-154, unit-34, zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/26540,Roads,Completed,NL-VALASARAVAKKAM,150,913000,"ATTENDING PATCH WORK AT DHARMARAJA NAGAR AND THUNDALAM ANNA NAGAR NATARAJA STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/26541,Roads,Completed,NL-VALASARAVAKKAM,150,963000,"ATTENDING PATCH WORK AT MOORTHY NAGAR MAIN ROAD AND THUNDALAM ANNA NAGAR PALANI STREET IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/26542,Roads,Completed,NL-VALASARAVAKKAM,150,914000,"ATTENDING PATCH WORK AT THIRU. VI. KA NAGAR 3RD STREET AND THUNDALAM ANNA NAGAR PHASE - 2 2ND MAIN ROAD IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/26543,Roads,Completed,NL-VALASARAVAKKAM,150,947000,"ATTENDING PATCH WORK AT ADHIYAMAN STREET AND THUNDALAM T.V.K NAGAR MAIN ROAD IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/26553,Roads,Completed,NL-VALASARAVAKKAM,150,969000,"ATTENDING PATCH WORK AT SAMAYAPURAM 1ST STREET AND SUBAGIRI NAGAR ROAD IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/26554,Roads,Completed,NL-VALASARAVAKKAM,150,821000,"ATTENDING PATCH WORK AT CVK STREET AND MAHALAKSHMI NAGAR IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/26558,Roads,Completed,NL-VALASARAVAKKAM,150,999000,"ATTENDING PATCH WORK AT MARAGATHAM 1ST AND 2ND STREET IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/26562,Roads,Completed,NL-VALASARAVAKKAM,150,511000,"ATTENDING PATCH WORK AT MOTHI NAGAR CROSS STREET REACH 1 (CHAINAGE FORM 0 M TO 150 M) IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/26566,Roads,Completed,NL-VALASARAVAKKAM,150,521000,"ATTENDING PATCH WORK AT THUNDALAM THIRUVEETHI AMMAN KOIL STREET REACH 1 (CHAINAGE FORM 0 M TO 150 M) IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/26581,Roads,Completed,NL-VALASARAVAKKAM,150,657000,"ATTENDING PATCH WORK AT THUNDALAM ANNA NAGAR BHARATHIYAR STREET IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/26624,Roads,Completed,NL-VALASARAVAKKAM,145,641000,"Attending the BT patch work at Pallavan Nagar VOC Street in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26625,Roads,Completed,NL-VALASARAVAKKAM,145,649000,"Attending the BT patch work at Pallavan Nagar Thiruvalluvar Street in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26627,Roads,Completed,NL-VALASARAVAKKAM,150,985000,"ATTENDING PATCH WORK AT SAMYAPURAM MAIN ROAD IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/26678,Roads,Completed,NL-VALASARAVAKKAM,145,1062000,"Attending the BT patch work at Pallavan Nagar pillaiyar koil Street (from Door No.02 to Door no.42 )in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26683,Roads,Completed,NL-VALASARAVAKKAM,145,969000,"Attending the BT patch work at Pallavan Nagar pillaiyar koil Street (from Door No.42 to Door no.96 )in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26684,Roads,Completed,NL-VALASARAVAKKAM,145,944000,"Attending the BT patch work at Pallavan Nagar Erikkarai Street (from Door No.72 to Door no.142 )in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26685,Roads,Completed,NL-VALASARAVAKKAM,145,983000,"Attending the BT patch work at Pallavan Nagar Erikkarai Street (from Door No.142to Door no.56 )in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26687,Roads,Completed,NL-VALASARAVAKKAM,145,979743,"Attending the BT patch work at Pallavan Nagar Erikkarai Street (from Door No.86 to Door no.89A )in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26688,Roads,Completed,NL-VALASARAVAKKAM,145,528000,"Attending the BT patch work at Pallavan Nagar Gandhi Street in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26690,Roads,Completed,NL-VALASARAVAKKAM,145,849000,"Attending the BT patch work at Pallavan Nagar Bharadi Street in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26692,Roads,Completed,NL-VALASARAVAKKAM,145,735000,"Attending the BT patch work at Pallavan Nagar Kambar Street and Pallavan Nagar Kttabomman 2nd cross street in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26693,Roads,Completed,NL-VALASARAVAKKAM,145,769000,"Attending the BT patch work at Pallavan Nagar Kttabomman street (from Door No.16 to Door no.78) in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26695,Roads,Completed,NL-VALASARAVAKKAM,145,805000,"Attending the BT patch work at Pallavan Nagar Kttabomman street (from Door No.78 to Door no.152) in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26696,Roads,Completed,NL-VALASARAVAKKAM,145,1025000,"Attending the BT patch work at Saraswathi nagar 1st street in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26699,Roads,Completed,NL-VALASARAVAKKAM,145,692000,"Attending the BT patch work at Saraswathi nagar 1st street (From Door no.12 to Door no.84) in Dn-145, Unit-33 Zone-11",Own Sources,11,2015-16,2016-17 NL/2015-16/26700,Roads,Completed,NL-VALASARAVAKKAM,145,979000,"Attending the BT patch work at Rajiv Gandhi nagar Annex-1 in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26702,Roads,Completed,NL-VALASARAVAKKAM,145,953000,"Attending the BT patch work at Rajiv Gandhi nagar Annex-1 Door No.42 to Door no 142 in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26704,Roads,Completed,NL-VALASARAVAKKAM,145,886000,"Attending the BT patch work at Rajiv Gandhi nagar Annex-2 (part-1) in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26705,Roads,Completed,NL-VALASARAVAKKAM,145,828000,"Attending the BT patch work at Rajiv Gandhi nagar Annex-2 (part-2) in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26706,Roads,Completed,NL-VALASARAVAKKAM,145,1061000,"Attending the BT patch work at Rajiv Gandhi nagar Pandiyan Door No.36 to Door No.82 in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26707,Roads,Completed,NL-VALASARAVAKKAM,145,1073000,"Attending the BT patch work at Rajiv Gandhi nagar Pandiyan Door No.82 to Door No.73 in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26708,Roads,Completed,NL-VALASARAVAKKAM,145,1154000,"Attending the BT patch work at Rajiv Gandhi nagar Pandiyan Door No.73 to Door No.104A in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26709,Roads,Completed,NL-VALASARAVAKKAM,145,979000,"Attending the BT patch work at Vallalar Street in Dn-145, U-33, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26773,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Improvements to the Existing Storm Water Drain From CSI Church Road to the Reach of 145m in Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2020-21 NL/2015-16/26807,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Improvements to the Existing Storm Water Drain From Balamurugan Koil 2nd Street Culvert to the Reach of 145m in Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2020-21 NL/2015-16/26837,Buildings,Completed,NL-VALASARAVAKKAM,145,994000,"PROVIDING AND FIXING STREET NAME BOARDS AT V.O.C STREET AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26838,Buildings,Completed,NL-VALASARAVAKKAM,145,993000,"PROVIDING AND FIXING STREET NAME BOARDS AT RAJIV GANDHI NAGAR ANNEX 2 AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26839,Buildings,Completed,NL-VALASARAVAKKAM,145,992000,"PROVIDING AND FIXING STREET NAME BOARDS AT KRISHNA NAGAR 3RD STREET AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26840,Buildings,Completed,NL-VALASARAVAKKAM,145,991000,"PROVIDING AND FIXING STREET NAME BOARDS AT SAKTHI NAGAR 25TH CROSS STREET C BLOCK AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26841,Buildings,Completed,NL-VALASARAVAKKAM,145,993000,"PROVIDING AND FIXING STREET NAME BOARDS AT MOOGAMBIGAI 1ST MAIN ROAD AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26842,Buildings,Completed,NL-VALASARAVAKKAM,145,994000,"PROVIDING AND FIXING STREET NAME BOARDS AT SARASWATHI NAGAR 2ND STREET AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/26843,Buildings,Completed,NL-VALASARAVAKKAM,145,991000,"PROVIDING AND FIXING STREET NAME BOARDS AT CHELLIAMMAN NAGAR CHITHIRAI STREET AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26844,Buildings,Completed,NL-VALASARAVAKKAM,145,995000,"PROVIDING AND FIXING STREET NAME BOARDS AT VALLIAMMAI NAGAR 3RD STREET AND VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26845,Buildings,Completed,NL-VALASARAVAKKAM,145,997000,"PROVIDING AND FIXING STREET NAME BOARDS AT VARIOUS STREETS IN DN-145,U-33,Z-11",Own Sources,11,2015-16,2018-19 NL/2015-16/26846,Buildings,Completed,NL-VALASARAVAKKAM,144,994000,"PROVIDING AND FIXING STREET NAME BOARDS AT VARIOUS STREETS IN DN-144,U-32,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/26853,Buildings,Completed,NL-VALASARAVAKKAM,143,999000,"PROVIDING AND FIXING STREET NAME BOARDS UNDER COUNCILLORS WARD DEVELOPMENT SCHEME WORKS AT GOODWILL ROAD AND VARIOUS STREETS IN DN-143,U-32,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/26854,Buildings,Completed,NL-VALASARAVAKKAM,143,999000,"PROVIDING AND FIXING STREET NAME BOARDS UNDER COUNCILLORS WARD DEVELOPMENT SCHEME WORKS AT PAADA SALAI STREET AND VARIOUS STREETS IN DN-143,U-32,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/26855,Buildings,Completed,NL-VALASARAVAKKAM,143,999000,"PROVIDING AND FIXING STREET NAME BOARDS UNDER COUNCILLORS WARD DEVELOPMENT SCHEME WORKS AT V.G.N. NAGAR PHASE-II CHANNEL STREET AND VARIOUS STREETS IN DN-143,U-32,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/26883,Roads,Completed,NL-VALASARAVAKKAM,147,311000,"Attending the patch work at Astalakshmi Nagar 20th street from Astalakshmi nagar 3rd main road to dead end in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26884,Roads,Completed,NL-VALASARAVAKKAM,147,448000,"Attending the patch work at Astalakshmi nagar 21st street from Astalskhmi nagar 3rd main road to dead end in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26885,Roads,Completed,NL-VALASARAVAKKAM,147,893000,"Attending the patch work at Astalakshmi nagar 13th street from Astalakshmi nagar 3rd main road to Dead end,Meenakchi street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26886,Roads,Completed,NL-VALASARAVAKKAM,147,963000,"Attending the patch work at Astalakshmi nagar 3rd main road from Astalakshmi nagar 21st street to Astalakshmi nagar 17th street,Iyyappan street,Karmegam street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26887,Roads,Completed,NL-VALASARAVAKKAM,147,980000,"Attending the patch work at Astalakshmi nagar 3rd main road from Sri Krishna nagar 2nd main road to Astalakshmi Nagar 21st street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26888,Roads,Completed,NL-VALASARAVAKKAM,147,920000,"Attending the patch work at M.G.Chakarabani nagar 14th street from M.G. Chkarabani nagar main road to Sri Lakshmi nagar in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26889,Roads,Completed,NL-VALASARAVAKKAM,147,822000,"Attending the patch work at Perumal koil Street from D.NO.101 to D.No.220,Kovil patti gopalakrishna street. in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26890,Roads,Completed,NL-VALASARAVAKKAM,147,990000,"Attending the patch work at Rukmani Nagar 2nd street from Rukmani nagar 3rd street to Sri Krishna nagar 24th street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26891,Roads,Completed,NL-VALASARAVAKKAM,147,974000,"Attending the patch work at Rukmani Nagar 3rd Street,Vallar street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26892,Roads,Completed,NL-VALASARAVAKKAM,147,806000,"Attending the patch work at sri krishna nagar 5th cross street from sri krishna nagar 1st main road to Sri krishna nagar extn,Astalakshmi nagar 3rd main road in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26893,Roads,Completed,NL-VALASARAVAKKAM,147,881000,"Attending the patch work at sri krishna nagar 1st main road from Sri Krishna Nagar 3rd cross street to Sri Krishna nagar 5th cross street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26894,Roads,Completed,NL-VALASARAVAKKAM,147,857000,"Attending the patch work at sri krishna nagar 1st main road from sri krishna nagar 5th cross street to D.No.62 in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26895,Roads,Completed,NL-VALASARAVAKKAM,147,980000,"Attending the patch work at Srinivasan Nagar 2nd street,Sri krishna nagar 1st main road, Devi karumarraiamman street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26896,Roads,Completed,NL-VALASARAVAKKAM,147,785000,"Attending the patch work at Sri Krishna Nagar 3rd main road from Om Sakthi Nagar 3rd street to Bharathi Nagar 3rd street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26897,Roads,Completed,NL-VALASARAVAKKAM,147,945000,"Attending the patch work at Perumal Koil Street from D.No.62 to D.No.101,Rukmani nagar 3rd street in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26898,Roads,Completed,NL-VALASARAVAKKAM,147,975000,"Attending the patch work at Perumal koil street from D.No. 01 to D.No.62 in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/26899,Roads,Completed,NL-VALASARAVAKKAM,147,227000,"Attending the patch work at sri krishna nagar 3rd main road from sri krishna nagar 20th street to dead end in Div-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2703,Roads,Completed,NL-VALASARAVAKKAM,143,1290000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at J.J. Nagar West 3rd Main Road 1st Cross Street, 18th Cross Street, 10th Main Road, 16th Cross Street and 15th Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2704,Roads,Completed,NL-VALASARAVAKKAM,143,1387000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Vellalar 6th Main Road, Madha Koil 7th Street and Madha Koil 8th Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2705,Roads,Completed,NL-VALASARAVAKKAM,143,1362000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Madha Koil 1st Street to Madha Koil 6th Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2706,Roads,Completed,NL-VALASARAVAKKAM,143,1439000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at 9th Cross Street, J.J. Nagar West 4th Main Road,2nd Main Road and Goodwin Road in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/27063,Roads,Completed,NL-VALASARAVAKKAM,150,521000,"ATTENDING PATCH WORK AT THUNDALAM THIRUVEETHI AMMAN KOIL STREET REACH 2 (CHAINAGE FORM 151 M TO 300 M) IN DN.150, UNIT 34, ZONE 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/2707,Roads,Completed,NL-VALASARAVAKKAM,143,1425000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at DABC Main Road and Pathma Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/27072,Roads,Completed,NL-VALASARAVAKKAM,150,511000,"ATTENDING PATCH WORK AT SIVABOOTHAM PERUMAL KOIL STREET IN DN.150, UNIT 34, ZONE 11.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/2708,Roads,Completed,NL-VALASARAVAKKAM,143,1446000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Selva Vinayagar Koil Street and Cross Street and J.J. Nagar West 1st Main Road in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2709,Roads,Completed,NL-VALASARAVAKKAM,143,1316000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at 8th Block Main Street and Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2710,Roads,Completed,NL-VALASARAVAKKAM,143,1256000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at 7th Cross Street to 9th Cross Street, Goodwill Road, 5th Main Road and Gobi Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2712,Roads,Completed,NL-VALASARAVAKKAM,143,1325000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at JJ Nagar West 3rd Main Road and Mithilam Road in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2713,Roads,Completed,NL-VALASARAVAKKAM,143,1289000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Gurusamy Road, VGN 1st Cross Street and VGN 2nd Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2714,Roads,Completed,NL-VALASARAVAKKAM,143,1182000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at VGN 3rd Cross Street, Channel Road, Anusha Street, Archana Street and 17th Cross Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2715,Roads,Completed,NL-VALASARAVAKKAM,143,1278000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Thilagar Street, VGN 3rd Cross Street, Magathma Gandhi Street and VOC Street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2716,Roads,Completed,NL-VALASARAVAKKAM,143,1398000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Ramalingam Road, Nerkundram Main Road and College Road in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2720,Roads,Completed,NL-VALASARAVAKKAM,143,1463000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at 8th Main Road, 9th Main Road, Andalammal Street and VGN 5th Cross Street",Own Sources,11,2015-16,2016-17 NL/2015-16/2721,Roads,Completed,NL-VALASARAVAKKAM,143,1398000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Madha Koil Street (Nerkundram Road to Nolambur Phase-2 Road), Nolambur Phase-2 Road and Union Road (Perumal Koil Street to Nerkundram Road) Reach-2 in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2725,Roads,Completed,NL-VALASARAVAKKAM,143,1423000,"CMWSSB - Water Supply Facilities - Road cut restoration work using GSB, WMM and RMC40 at Bharathi Salai and 4th Main Road in Dn-143, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/2733,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,884000,"DESILTING OF STORM WATER DRAIN AT PILLAYAR KOIL STREET, BARATHYAR STREET, VADAVENNIAMMAN NAGAR, ABIRAMI NAGAR MAIN ROAD, MMDA COLONY 1ST MAIN ROAD(EB OFFICE MAIN ROAD, PERUMAL KOIL STREET, SRI VENKATEHWARA NAGAR, VENKATESHWARA NAGAR, OHM SHAKTHI NAGAR, KQANNAN NGAR, KAMATCHI NAGAR, MADURAI NAICKEN STREET, SANNATHI STREET, SATHYAMOORTHY NAGAR MAIN ROAD, 7TH BLOCK IN DIV-144, U-32, Z-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2749,Buildings,Completed,NL-VALASARAVAKKAM,144,999000,"MLA FUND: CONSTRUCTION OF TOILET BLOCK IN VILLIVAKKAM PANCHAYAT UNION PRIMARY SCHOOL IN DIV-144, UNIT-32, ZONE-XI",MLACDS,11,2015-16,2016-17 NL/2015-16/27493,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,586000,"Improvements to side drain at Devi karumariamman nagar 2nd street in DIN-148,UN-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/27495,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,815000,"Improvements to side drain at Kadambadiamman nagar Ranagasamy street (Angala parameshwari street to jayalaksmi street} in DIN-148,UN-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/27496,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,790000,"Improvements to side drain at Gaja laksmi street in DIN-148,UN-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/27498,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,929000,"Improvements to side drain at N.TPatel road in DIN-148,UN-33,ZO-11",Own Sources,11,2015-16,2017-18 NL/2015-16/27779,Buildings,Completed,NL-VALASARAVAKKAM,144,999000,"PROVIDING GLADING ARRANGEMENTS TO NEW FAIR PRICE CANTEEN AT AMMA UNAVAGAM IN DN144,U32,Z11.",Own Sources,11,2015-16,2017-18 NL/2015-16/27780,Buildings,Completed,NL-VALASARAVAKKAM,144,999000,"PROVIDING SUBSIDY TIFFEN CENTRE AT AMMA UNAVAGAM IN DN144,U32,Z11.",Own Sources,11,2015-16,2017-18 NL/2015-16/27990,Buildings,Completed,NL-VALASARAVAKKAM,149,575000,"Improvements to flood damaged at Brindhavan Nagar Burial Ground Compound Wall in Division 149, Unit 33, Zone-11",Own Sources,11,2015-16,2017-18 NL/2015-16/28278,Buildings,Completed,NL-VALASARAVAKKAM,144,936000,Constructions of Electrical JE Office at V.G.P. Amutha nager div 144 unit32 zone11,Own Sources,11,2015-16,2018-19 NL/2015-16/28612,Parks,Completed,NL-VALASARAVAKKAM,146,830000,"IMPROVEMENT WORKS TO PARK AT METRO NAGAR PARK IN DIV-146, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2018-19 NL/2015-16/28614,Buildings,Completed,NL-VALASARAVAKKAM,144,235000,"IMPROVEMENT WORKS TO THE AMMA UNAVAGAM IN METTUKUPPAM ROAD IN DIV-144,UNIT-32, ZONE-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/28717,Buildings,Completed,NL-VALASARAVAKKAM,146,796000,"Improvement works to Amma Unavagam at South Mada street in Dn-146, Unit-32, Zone-XI",Own Sources,11,2015-16,2019-20 NL/2015-16/2877,Parks,Completed,NL-VALASARAVAKKAM,149,760000,"ANNUAL MAINTENANCE OF FATHIMA NAGAR THANTHAI PERIYAR PARK AT Dr.RADHAKRISHNAN SALAI (CHENNAI CORPORATION PARKS) FOR TWO YEAR IN DN.149, U 33, Z 11. (TO DEPLOY QUALIFIED PERSONNEL WITH DIPLOMA IN HORTICULTURE)",Own Sources,11,2015-16,2017-18 NL/2015-16/2878,Parks,Completed,NL-VALASARAVAKKAM,149,410000,"ANNUAL MAINTENANCE OF BRINDAVAN NAGAR PARK (CHENNAI CORPORATION PARKS) FOR TWO YEAR IN DN.149, U 33, Z 11. (TO DEPLOY QUALIFIED PERSONNEL WITH DIPLOMA IN HORTICULTURE)",Own Sources,11,2015-16,2017-18 NL/2015-16/2879,Parks,Completed,NL-VALASARAVAKKAM,149,695000,"ANNUAL MAINTENANCE OF THIRU.VI.KA PARK AT GANDHI ROAD (CHENNAI CORPORATION PARKS) FOR TWO YEAR IN DN.149, U 33, Z 11. (TO DEPLOY QUALIFIED PERSONNEL WITH DIPLOMA IN HORTICULTURE)",Own Sources,11,2015-16,2017-18 NL/2015-16/2881,Parks,Completed,NL-VALASARAVAKKAM,153,410000,"ANNUAL MAINTENANCE OF KANNIAPPAN SALAI CHENNAI CORPORATION PARK AT DN.153,U 34,ZONE XI.(EMPLOYED QUALIFIED DIPLOMA IN HORTICULTURE FOR TWO YEARS PARK MAINTENANCE)",Own Sources,11,2015-16,2018-19 NL/2015-16/28864,Parks,Completed,NL-VALASARAVAKKAM,143,999990,"FORMATION OF PARK AT NOLAMBUR PHASE-1, 6TH MAIN ROAD IN DN143,U32,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/28879,Buildings,Completed,NL-VALASARAVAKKAM,155,482000,"Additional Construction of 16th Ceremony Hall at Bajanai koil street in Division-155, Unit-34, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/2888,Parks,Completed,NL-VALASARAVAKKAM,151,650000,"ANNUAL MAINTENANCE THE EXISTING SABARI NAGAR PARK FOR THE PERIOD OF TWO YEARS IN DN.151, U 34, ZONE 11.(BY EMPLOYED QUALIFIED HORTICULTURIST ONLY)",Own Sources,11,2015-16,2018-19 NL/2015-16/28880,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,860000,"Improvement to SWD Flood damaged at Rajiv Gandhi nagar main road, Moogambigai nagar main road in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/28881,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,931000,"Improvement to SWD Flood damaged at Reddy Street and Madha koil Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/28882,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,945000,"Improvement to SWD Flood damaged at Perumal koil street and Dayasathen street , Karunigar Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2015-16,2016-17 NL/2015-16/2889,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,970000,"Desilting Strom water Drain and Side Drain Senthamil Nagar, Alagapuri Nagar, Sriram Nagar, Bajajnai Koil Street, Mullai Nagar, Bharathi Nagar, Natarajan Street, Annai Sathya Nagar, G.R. Nagar, Royala Nagar, Bakthi Vedhanantha Avenue, Harishanakar Strret, Amman Nagar, Thiruvalluvar Salai, Kanndasan nagar and Bharathi salai in Division 155, Unit 34, Zone 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/28896,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,995000,"Desilting at Virugambakkam Canal from Bhuvaneswari Nagar to Iyyappa Nagar Dn-148 and Dn-145, Unit-33, Zone-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/2890,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,990000,"Desilting Strom water Drain and Side Drain at Shanthi nagar, Anandham nagar, Kurinji nagar, Venkateswara nagar, Balambigai nagar, Ambal nagar, Thangal street and Gangai amman koil street in Division - 154, Unit - 34, Zone - 11",Own Sources,11,2015-16,2016-17 NL/2015-16/28915,Buildings,Completed,NL-VALASARAVAKKAM,152,585000,Annual Maintenance at Zonal Office Building (aro and uac section) in div 152 unit-33 Zone-11,Own Sources,11,2015-16,2016-17 NL/2015-16/2893,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,785000,"Desilting Storm water drain and Side drain at Chowdry nagar, Janagi nagar, Prakasam st, P.N. Ramamurthy st, Madurai meenakshi nagar, Majestic colony, Bethaniya nagar, Ambedkar road, Thiruvalluvar road, Alappakkam road, Thiruvalluvar st, SVS nagar annex, Suresh nagar, Kalaignar st, Anna st, Rajaji avenue and Periyar st in Dn-152, U-33, z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/2908,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,884000,"DESILTING OF SWD AT SRI KRISHNA NAGAR 1st,2nd & 3rd MAIN ROAD,SEEMATHAMMAN NAGAR MAIN ROAD,KARUNATHI STREET,KAMARAJAR STREET,ALLAPAKKAM MAIN ROAD,BHARATHI NAGAR 3rd STREET,M.G.CHAKRABANI MAIN ROAD,OM SAKTHI NAGAR 1st STREET,OM SAKTHI NAGAR MAIN ROAD,THEEDER NAGAR MAIN ROAD SRI DEVI NAGAR MAIN ROAD IN DIV-147,UNIT-32,ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/2911,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,855000,"Desilting of Storm Water Drain and Side Drain at Kamatchi Nagar, Velan Nagar, Brindavan Nagar, Balaji Nagar, Palaniappa Nagar, West Kamakodi Nagar, and AKR Nagar in Division 149, Unit 33, Zone-11",Own Sources,11,2015-16,2017-18 NL/2015-16/2919,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,998000,"Desilting of Storm water drain and Side drain at various street in Dn-145,U-33,Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/29190,Buildings,Completed,NL-VALASARAVAKKAM,148,600000,Providing and fixing E Toilet at Periyar Nagar Thangal Karai in Dn 148 U 33 Zn 11,Own Sources,11,2015-16,2016-17 NL/2015-16/29192,Buildings,Completed,NL-VALASARAVAKKAM,148,600000,Providing and fixing E Toilet at Periyar Nagar Thangal Karai in Dn 148 U 33 Zn 11,Own Sources,11,2015-16,2016-17 NL/2015-16/2920,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,998000,"DESILTING OF SWD AT RAJIV GANDTHI NAGAR,M.G.R.STREET,BHARATHIDHASAN NAGAR 1st to 14th STREET & CROSS STREET,GANAPATHY NAGAR 2nd STREET,VENKATESHWARA ST,PRIEYAR ST,ANNA ST, CHRUCH ST, SOUTH MADA ST,NORTH MADA ST, WEST MADA ST,METRO NAGAR 1st, 2nd,4th & 7th AVENUE,RAJIV GANDHI NAGAR MAIN ROAD.INDHIRA GANDHI STREET,CHOLLAN NAGAR, CHOLLAN NAGAR CROSS STREET,KANDHAN STREET,LALLBAGADTHUR STREET,GANGAIAMMAN NAGAR 1st to 13th STREET & CROSS STREET. IN DIV-146,UNIT-32,ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/29216,Buildings,Completed,NL-VALASARAVAKKAM,149,959000,"Improvements to Damaged interlocking paver block Floor due to North east Monsoon on flood at Unit Office in Dn 149, Unit 33, Zone-11",Own Sources,11,2015-16,2018-19 NL/2015-16/2926,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,998000,"De-Silting of Storm Water Drain at Various Street in Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/2930,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,995000,"Desilting of swd and side drain at madha koil nagar 1st to 4th street, perumal koil st, church road, 4th block 1st, 4th, 8th street, vembuliamman koil st, phase-II salai main road, phase-II 2nd and 4th main road, bharathi salai, mugappair west main road,service road, voc main road, ramalingam salai, phase-I 1st, 2nd and 8th main road, 5th block sivan koil st, thiruvalluvar salai in D-143, U-32, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/29367,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,995000,Improvements to flood damaged storm water drains at Various places in Dn.149 U 33 Z 11,Own Sources,11,2015-16,2016-17 NL/2015-16/29372,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,995000,Improvements to side drain at balambigai nagar 4th Street from Kambar salai to balambigai nagar 4th Street (Reach 1) in Dn 154 U 34 Z 11,Own Sources,11,2015-16,2016-17 NL/2015-16/29541,Roads,Completed,NL-VALASARAVAKKAM,145,996000,"Relaying The BT Road at Azhakammal 1st Main Road, Sakthi Nagar 8th Street & Moogambigai 1st Main Road In Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29551,Roads,Completed,NL-VALASARAVAKKAM,145,985000,"Relaying The BT Road at Azhakammal 2nd Main Road , Moogambigai 2nd Main Road , Moogambigai 3rd Main Road In Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29561,Roads,Completed,NL-VALASARAVAKKAM,145,984000,"Relaying The BT Road at Reddy Street , Rajiv Gandhi Nagar Main Road , New colony In Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29583,Buildings,Completed,NL-VALASARAVAKKAM,152,610000,Annual Maintanance of Amma Unavagam at Thiruvalluvar Street In div152 unit 33 zone11,Own Sources,11,2015-16,2016-17 NL/2015-16/29591,Buildings,Completed,NL-VALASARAVAKKAM,152,966000,Improvements and gas pipe connections in Amma Unavagam at Thiruvalluvar Salai In div 152 unit 33 zone11,Own Sources,11,2015-16,2017-18 NL/2015-16/29631,Roads,Completed,NL-VALASARAVAKKAM,145,985000,"RELAYING THE BT ROAD AT Madha Koil Main Road (REACH-1) Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29670,Roads,Completed,NL-VALASARAVAKKAM,145,986000,"RELAYING THE BT ROAD AT NEW COLONY 3RD STREET, NEW COLONY 4TH STREET, NEW COLONY 5TH STREET, NEW COLONY 1ST CROSS STREET, NEW COLONY 2ND CROSS STREET, PALVADI STREET EXTENSION IN Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29672,Roads,Completed,NL-VALASARAVAKKAM,145,814000,"Relaying the BT Road in Sivanthi Avenue 2nd Main Road (Reach - 1) Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29675,Roads,Completed,NL-VALASARAVAKKAM,145,744000,"Relaying the BT Road at Sivanthi Avenue 1st Main Road (Reach - 1) in Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29676,Roads,Completed,NL-VALASARAVAKKAM,145,765000,"Relaying the BT Road at Sivanthi Avenue 1st Main Road (Reach - 2) Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29759,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,671000,"IMPROVEMNTS TO STORM WATER DRAIN FIOOD DAMAGED AT BHARATHI SALAI AND MUGAPPAIR WEST MAIN ROAD (PLOT No. A 869) IN DN 143, U-32, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/29764,Buildings,Completed,NL-VALASARAVAKKAM,150,497000,"PAINTING AND REPAIRING WORK AT THUNDALAM THIRU. VI. KA - LIBRARY IN DIV - 150, UNIT - 34, ZONE - 11",Own Sources,11,2015-16,2017-18 NL/2015-16/29837,Roads,Completed,NL-VALASARAVAKKAM,143,998000,"LAYING BITUMINOUS COURSE AT SAKTHI NAGAR 2ND AVENUE (REACH-1) IN DN143,U33,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29841,Roads,Completed,NL-VALASARAVAKKAM,143,998000,"LAYING BITUMINOUS COURSE AT SAKTHI NAGAR 2ND AVENUE (REACH-2) AND PHASE-II 1ST CROSS STREET IN DN143,U32,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29856,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,984000,"IMPROVEMENTS TO SIDE DRAIN AT BALAMBIGAI NAGAR 5TH STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/29872,Buildings,Completed,NL-VALASARAVAKKAM,154,500000,"Improvements to Division office in Dn -154,Unit-34, Zone- 11",Own Sources,11,2015-16,2017-18 NL/2015-16/29941,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,571000,"Improvements Storm water drain & Side drain at C.S.I School Street & Chettiyar agaram street in DIN-150,UN-34,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/30028,Parks,Completed,NL-VALASARAVAKKAM,151,999000,"Improvements to compound wall at (Porur) TCG Park in Dn -151, U-34, Zone-11",Own Sources,11,2015-16,2017-18 NL/2015-16/30037,Buildings,Completed,NL-VALASARAVAKKAM,155,500000,"Improvements to Division office building, PrimaryHealth Centre and at Bajanai koil street in Division, Unit-34, Zone-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/30078,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"Construction of Multi Purpose hall at Alagapuri Nagar and Motor shed at Giri Nagar in Division -155, Unit-34, Zone-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/30088,Roads,Completed,NL-VALASARAVAKKAM,145,814000,"Relaying the BT Road in Sivanthi Avenue 2nd Main Road (Reach - 2) Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/30090,Roads,Completed,NL-VALASARAVAKKAM,145,985000,"RELAYING THE BT ROAD AT Madha Koil Main Road (REACH-2) Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/30091,Roads,Completed,NL-VALASARAVAKKAM,145,992000,"Relaying The BT Road at Perumal koil Main Road In Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/30117,Buildings,Completed,NL-VALASARAVAKKAM,144,585000,Attending patch works and Annual maintenance in div 144 unit32 zone11,Own Sources,11,2015-16,2016-17 NL/2015-16/30133,Roads,Completed,NL-VALASARAVAKKAM,145,942000,"Relaying the BT Road at karnikar street Dn-145, U-33, Z-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/30156,Buildings,Completed,NL-VALASARAVAKKAM,144,957000,"PROVIDING FLOORING AND ROOFING ARRANGEMENTS TO THE EXISTING PRIMARY HEALTH CENTRE AT PH ROAD IN DIV-144, UNIT-32,ZONE-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/3030,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,962000,"DESILTING OF STORM WATER DRAIN AT BYPASS SERVICE ROAD (FROM MOUNT POONAMALLEE ROAD TO VANAGARAM POONAMALLEE HIGH ROAD) TWO SIDES AND ARCOT ROAD (FROM RAJESHWARI NAGAR TO A1 MUTTON STALL) IN DN 150, U - 34, Z XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/30328,Road Cut,Completed,NL-VALASARAVAKKAM,149,654000,"Restoration of Road Cut Made by TANGEDCO at Ganthi Road and Alwarthirunagar Annex Main Road in Division 149,Unit -33, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/30348,Road Cut,Completed,NL-VALASARAVAKKAM,149,879000,"Restoration of Road Cut Made by TANGEDCO at Radha Krishna Salai in Division 149,Unit -33, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/30350,Road Cut,Completed,NL-VALASARAVAKKAM,149,383000,"Restoration of Road Cut Made by TANGEDCO at Vanjinathan Street and Park Street in Division 149,Unit -33, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/30880,Buildings,Completed,NL-VALASARAVAKKAM,152,740000,"Improvement in Auditior section and Other works, at zonal office ground floor in div152 unit 33 zoneXI",Own Sources,11,2015-16,2017-18 NL/2015-16/30882,Buildings,Completed,NL-VALASARAVAKKAM,152,792000,"Improvements to admin section, Electrical section and Conservancy section, at zonal office second floor in div 152, unit 33, zone XI",Own Sources,11,2015-16,2017-18 NL/2015-16/30928,Buildings,Completed,NL-VALASARAVAKKAM,152,997000,Improvements works to north east room at first floor zonal office in div 152 unit 33 zone11,Own Sources,11,2015-16,2018-19 NL/2015-16/31224,Roads,Completed,NL-VALASARAVAKKAM,146,999000,"Supplying and Fixing Street Name Board at Gangaiamman Nagar main road 1st the 13th street and cross streets, Samayapuram mariamman koil street, Indira gandhi street, Church street, Priyar street, Bharathiyar street, Chollan nagar and cross street, Kandhan street and cross streets in Dn-146, Unit-32, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/31241,Roads,Completed,NL-VALASARAVAKKAM,146,997000,"Supplying and Fixing Street Name Board at Dhanlakshmi nagar 1st to 17th st and cross streets, New subramani nagar Ayyappa nagar 1st 6th street and cross street, Muthumariamman koil street in Dn-146, Unit-32, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/31243,Roads,Completed,NL-VALASARAVAKKAM,146,998000,"Supplying and Fixing Street Name Board at Ambethkar nagar, Perumal koil street, Ayyavu Nayakkar street, North, South, West mada streets and cross street, Karunakara perumal koil street, Kamaraj nagar main road, 1st, 2nd, 3rd streets, Venugopal st, Ponniamman street and cr st, Nehru street, Rajiv gandhi street, Anna street MGR street, Sithivinayagar koil 2nd and cross street, Kannaki , Jeeva street, Gandhi street and various streets in Dn-146, Unit-32, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/3134,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,437000,"IMPROVEMENTS TO THE CULVERT AT THE JUNCTION OF ABIRAMI NAGAR 6th STREET & JAYARAM NAGAR MAIN ROAD AND 7TH BLOCK MAIN ROAD IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31518,Roads,Completed,NL-VALASARAVAKKAM,143,959000,"Relaying the BT Road at Sriram nagar main road (Reach-I) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31520,Roads,Completed,NL-VALASARAVAKKAM,143,959000,"Relaying the BT Road at Sriram nagar main road (Reach-II) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31590,Roads,Completed,NL-VALASARAVAKKAM,143,959000,"Relaying the BT Road at Phase-1 4th main road (Reach-1) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31591,Roads,Completed,NL-VALASARAVAKKAM,143,832000,"Relaying the BT Road at phase-1 4th main road (Reach-2) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31615,Roads,Completed,NL-VALASARAVAKKAM,143,987000,"Relaying the BT Road at Vellalar pradhana salai (Reach-I) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31617,Roads,Completed,NL-VALASARAVAKKAM,143,987000,"Relaying the BT Road at Vellalar pradhana salai (Reach-2) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31618,Roads,Completed,NL-VALASARAVAKKAM,143,771000,"Relaying the BT Road at Vellalar pradhana salai (Reach-3) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31623,Roads,Completed,NL-VALASARAVAKKAM,143,995000,"Relaying the BT Road at pada salai street (From Gajalakshmi nagar 1st main road To Plot no 28/7 in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31626,Roads,Completed,NL-VALASARAVAKKAM,143,995000,"Relaying the BT Road at pada salai street (From Plot no 28/7 To Sakthi nagar 2nd Avenue) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31628,Roads,Completed,NL-VALASARAVAKKAM,143,925000,"Relaying the BT Road at Union road (From Phase-2 salai To Gangaiamman Street in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31634,Roads,Completed,NL-VALASARAVAKKAM,143,925000,"Relaying the BT Road at Union road (From Gnagai amman street To matha koil 8th street ) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31637,Roads,Completed,NL-VALASARAVAKKAM,143,925000,"Relaying the BT Road at Union road (From matha koil 8th street To matha koil 1st street ) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31638,Roads,Completed,NL-VALASARAVAKKAM,143,925000,"Relaying the BT Road at Union road (From matha koil 1st street To permal koil street ) in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31640,Roads,Completed,NL-VALASARAVAKKAM,143,925000,"Relaying the BT Road at Union road (From permal koil street To plot no A69/19 )in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/31641,Roads,Completed,NL-VALASARAVAKKAM,143,925000,"Relaying the BT Road at Union road (From plot no A69/19 TO Gajalakshmi nagar road )in Division -143, Unit-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/3173,Road Cut,Completed,NL-VALASARAVAKKAM,146,467000,"CMWSSB - Road cut restoration work using GSB, WMM and RMC40 at Ramadoss Salai, Periyar Street, Dhanalakshmi Nagar, Balaraman Street and Metro Nagar 7th Avenue in Dn-146, Unit-32 Zone -11",Own Sources,11,2015-16,2016-17 NL/2015-16/31785,Parks,Completed,NL-VALASARAVAKKAM,147,998000,"Improvements to Park at Pallavan Nagar in Dn 147, U 32, Zone 11",Own Sources,11,2015-16,2017-18 NL/2015-16/31795,Roads,Completed,NL-VALASARAVAKKAM,154,860000,"RESTORATION OF ROAD CUT AT KURINJI NAGAR 1st CROSS STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2017-18 NL/2015-16/3181,Road Cut,Completed,NL-VALASARAVAKKAM,146,722000,"CMWSSB - Road cut restoration work using GSB, WMM and RMC40 at Ramadoss Salai, Periyar Street and Balaraman Street in Dn-146, Unit-32 Zone -11",Own Sources,11,2015-16,2016-17 NL/2015-16/32135,Buildings,Completed,NL-VALASARAVAKKAM,152,843000,"Providing Additional wooden Storage rack in second floor south west room at zonal office in div 152, unit 33, zone XI",Own Sources,11,2015-16,2018-19 NL/2015-16/32214,Road Cut,Completed,NL-VALASARAVAKKAM,152,994000,"Restoration of road cut made by CMWSSB at Thiru Nagar, Bharathiyar Street and V.O.C. Street in Dn 152, Unit 33, Zone 11.",Own Sources,11,2015-16,2016-17 NL/2015-16/32298,Roads,Completed,NL-VALASARAVAKKAM,154,521000,Improvements to side drain at balambigai nagar 4th Street from balambigai nagar 4th Street to balambigai nagar 5th Street(Reach 2) in Dn 154 U 34 Z 11,Own Sources,11,2015-16,2017-18 NL/2015-16/32791,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,368000,"Improvement to SWD at MGR Street, Ramadoss street, Balaraman Street, Metro Nagar 7th Avenue, K.K.Salai, Bharathiyar Nagr 1st to 12th street, Metro Nagar 2nd Avenue, PH road and various in Dn-146, Unit-32, Zone-XI",Own Sources,11,2015-16,2018-19 NL/2015-16/32794,Buildings,Completed,NL-VALASARAVAKKAM,146,78000,"Providing RO process water system at Ganapathy nagar Division office and PH road Amma Unavagam in Dn-146, Unit-32, Zone-XI",Own Sources,11,2015-16,2018-19 NL/2015-16/32900,Roads,Completed,NL-VALASARAVAKKAM,148,500000,"Improvements side drain & culverts at Lakshmi nagar 4th street & Balaji nagar 1st street& Anbu nagar 7th street & Thanthai Periyar Nagar Junction in DIN-148,UN-33,Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/32905,Road Cut,Completed,NL-VALASARAVAKKAM,149,528000,"Restoration of road cut at Sri Devi Kuppam Main Road (Reach 1) in Dn 149, Unit 33, Zone 11.",Own Sources,11,2015-16,2017-18 NL/2015-16/32927,Road Cut,Completed,NL-VALASARAVAKKAM,149,528000,"Restoration of road cut at Sri Devi Kuppam Main Road (Reach 2) in Dn 149, Unit 33, Zone 11.",Own Sources,11,2015-16,2017-18 NL/2015-16/33003,Road Cut,Completed,NL-VALASARAVAKKAM,154,747000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT VENKATESWARA NAGAR 2nd AND12th CROSS STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/33005,Road Cut,Completed,NL-VALASARAVAKKAM,154,884000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT VENKATESWARA NAGAR 3rd STREET AND AVVAIYAR STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/33006,Road Cut,Completed,NL-VALASARAVAKKAM,154,809000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT VENKATESWARA NAGAR 8th AND 17th STREETS IN DN154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/33007,Road Cut,Completed,NL-VALASARAVAKKAM,154,555000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT VENKATESWARA NAGAR NAGAR 10th STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/33008,Road Cut,Completed,NL-VALASARAVAKKAM,154,869000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT VENKATESWARA NAGAR 12th STREET IN DN154,U34,Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/33056,Parks,Completed,NL-VALASARAVAKKAM,153,998000,"Improvements to the Kanniappan Salai Park, Shuttle court at Arivarasan Salai and Ramakrishna Nagar Park in Div-153, U-34, Z-11.",Own Sources,11,2015-16,2020-21 NL/2015-16/33393,Roads,Completed,NL-VALASARAVAKKAM,146,84000,"Attending the patch work WMM & GSB at Vaigaasi Street (Near Metro Nagar 1st Avenue) in Dn-146, Unit-32, Zone-XI",Own Sources,11,2015-16,2019-20 NL/2015-16/33446,Buildings,Completed,NL-VALASARAVAKKAM,155,599000,"IMPROVEMENTS TO CHENNAI SCHOOL AT EASWARAN KOIL STREET IN DN155,U34,Z11.",Own Sources,11,2015-16,2017-18 NL/2015-16/34083,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,984000,"Desilting of Storm water drain and side drain at various street in Dn-148, U-33, Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/34281,Buildings,Completed,NL-VALASARAVAKKAM,144,998000,"Providing wooden Storage rack and improvement works in second floor south west room at zonal office in div 152, unit 33, zone XI",Own Sources,11,2015-16,2018-19 NL/2015-16/34885,Roads,Completed,NL-VALASARAVAKKAM,154,850000,"Attending Patch for Flood Damage Roads at Anna nagar Thangal street in division-154, unit-34, zone11",Own Sources,11,2015-16,2016-17 NL/2015-16/3502,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Improvements to Exiting Side Drain at Bharathi Nagar 1st Street, R E Nagar (West) 3rd & 4th Street, & Lane, in Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/3503,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Improvements to Exiting Side Drain at Perumal Koil 1st to 2nd Street, R.E. Nagar 2nd Street (West), Erikarai Street. in Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/3504,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,998000,"Improvements to Exiting Side Drain at Perumal Koil Cross Street, R.E Nagar 1st Street (West), in Dn-153, U-34, Zone-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/3633,Road Cut,Completed,NL-VALASARAVAKKAM,147,167000,"CMWSSB-Water Supply Facilities-Road cut restoration work using GSB,WMM and RMC40 at Sri krishna nagar 2nd main road,Sri krishna nagar 19th street,Pillaiyar koil street,Gandhi street in Dn-147,Unit-32,Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/3697,Buildings,Completed,NL-VALASARAVAKKAM,151,1600000,CONSTRUCTION OF ADDITIONAL CLASS ROOM AT VILLIVAKKAM MIDDILE SCHOOL POOTHABEDU SCHOOL ROAD IN DN 151 U 34 Z 11.,MLACDS,11,2015-16,2019-20 NL/2015-16/3882,Buildings,Completed,NL-VALASARAVAKKAM,151,878000,IMPROVEMENT OF ELECTRICAL CEREMATION BUILDING IN ARCOT ROAD IN DN 151 U 34 Z 11.,Own Sources,11,2015-16,2016-17 NL/2015-16/4032,Buildings,Completed,NL-VALASARAVAKKAM,155,730000,"Construction of Compound Wall at Thiruvalluvar Salai near Burial ground in Division - 155, Unit - 34, Zone - XI",Own Sources,11,2015-16,2016-17 NL/2015-16/4225,Parks,Completed,NL-VALASARAVAKKAM,150,231000,"Providing water supply and Electrical works in Chennai Corporation Park at Ponniamman Koil Street in Dn-150, U-34, Z-11",Own Sources,11,2015-16,2016-17 NL/2015-16/4306,Buildings,Completed,NL-VALASARAVAKKAM,150,820000,"Construction of Compound wall, water Supply Arrangement and painting works in Community Hall at Mullai Street in Dn-150, U-34, Z-11",Own Sources,11,2015-16,2019-20 NL/2015-16/4432,Buildings,Completed,NL-VALASARAVAKKAM,146,980000,Providing water supply and electrical works at Amma Unavagam at Ganapathy Nagar S.No.526 in Dn 146 U 32 Z 11.,Own Sources,11,2015-16,2018-19 NL/2015-16/4442,Buildings,Completed,NL-VALASARAVAKKAM,146,998000,"Providing Glading Arrangements to New Fair Price Canteen at Ganapathy Nagar in Dn-146, Unit-32, Z-XI.",Own Sources,11,2015-16,2018-19 NL/2015-16/4443,Buildings,Completed,NL-VALASARAVAKKAM,146,998000,"Providing Subsidy Tiffen Centre at Ganapathy Nagar Survey No 526 in Dn-146, Unit-32, Z-XI.",Own Sources,11,2015-16,2018-19 NL/2015-16/4497,Roads,Completed,NL-VALASARAVAKKAM,150,721000,"ATTENDING CEMENT CONCRETE PATCH WORK AT PONNI AMMAN KOIL 1ST STREET, PONNI AMMAN KOIL STREET, JAIN KOIL STREET, PONNI NAGAR AVVAI STREET, BUDDHAR COLONY, PILLIYAR KOIL STREET, MANDAVELI AND CROSS STREETS, KARAMBAKKAM 1ST STREET, RAJESWARI NAGAR MAIN ROAD, RAJESWARI NAGAR 1ST STREET, RAJESWARI NAGAR 2ND STREET, BRAHMIN STREET, KARAMBAKKAM 1ST MAIN ROAD, SCHOOL STREET, KAVERI NAGAR MAIN ROAD, KAVERI NAAGAR 2ND STREET, KAVERI NAGAR 3RD STREET, PONNI NAGAR KAMBAR STREET, C.V.K STREET AND KANDASWAMY STREET KANTHA KANNAN STREET IN DN - 150 U - 34, ZONE - 11",Own Sources,11,2015-16,2017-18 NL/2015-16/4506,Roads,Completed,NL-VALASARAVAKKAM,153,135000,"Providing water supply arrangements for Bio-toilet at Wireless station road,porur, at Division -153, Unit-34, Zone-11",Own Sources,11,2015-16,2020-21 NL/2015-16/4798,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,2999000,"Improvements of SIde drain at Rajivagandhi Annex Bharathiyar Street, Moogambigai Nagar 1st, 7th and 8th Streets in Dn-145, U-33, Z-11",Own Sources,11,2015-16,2017-18 NL/2015-16/4885,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,2999000,"Improvements of Side drain at New Colony 1st to 5th Streets and Alagammal Nagar 2nd to 5th Streets in Dn - 145, Z - 34, Z - 11.",Own Sources,11,2015-16,2017-18 NL/2015-16/5210,Road Cut,Completed,NL-VALASARAVAKKAM,147,998000,"Road cut restoration work using GSB, WMM and RMC40 at Sri Krishna nagar 3rd main road and Astalakshmi nagar 3rd main road and in Dn-147, Uint-32, Zone-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/5603,Buildings,Completed,NL-VALASARAVAKKAM,147,2000000,DEMOLITION AND RECONSTRUCTION OF ANGANWADI BUILDING AT PERUMAL KOIL STREET IN DN-147. UNIT-32. ZONE-XI,MLACDS,11,2015-16,2016-17 NL/2015-16/5848,Footpath,Completed,NL-VALASARAVAKKAM,155,1700000,"Forming Footpath at Moogambigai Street In Dn-155,Unit-34 Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/6339,Roads,Completed,NL-VALASARAVAKKAM,143,750000,"FORMING AND LAYING BT ROAD AT SRIRAM NAGAR CROSS STREET IN DN-143, UNIT-32, ZONE-XI",Own Sources,11,2015-16,2016-17 NL/2015-16/6519,Buildings,Completed,NL-VALASARAVAKKAM,151,994000,"Additional Improvements to Amma Unavagam at Chinna Porur, Hospital Road in Dn151,U34, Z11.",Own Sources,11,2015-16,2016-17 NL/2015-16/6937,Parks,Completed,NL-VALASARAVAKKAM,151,870000,"Annual Maintenance of Park at Mount Poonthamallee Road (Near TCG Software Company), Porur for two years maintenance in Dn.151, U-34, Z-XI. (By qualified diploma holder with two years experience horticulturist only)",Own Sources,11,2015-16,2017-18 NL/2015-16/7416,Playfields,Completed,NL-VALASARAVAKKAM,152,997400,"Improvement of Children play ground at kadamban street in Division - 152 , Unit , 33 in Zone XI",Own Sources,11,2015-16,2016-17 NL/2015-16/7417,Buildings,Completed,NL-VALASARAVAKKAM,143,232000,Formation of E-seva in div office at sriram nager div143 unit 32 zone11,Own Sources,11,2015-16,2017-18 NL/2015-16/7684,Buildings,Completed,NL-VALASARAVAKKAM,146,233000,"Formation of E-Seva in div office at Survey No,526, Ganapathy Nagar in Dn 146, Unit-32, Zone-XI",Own Sources,11,2015-16,2017-18 NL/2015-16/7816,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,962000,"Improvements to Side drain at Amman Nagar main road, K.P. Nagar main road, and Hari shankar street in Dn-155, Unit-34, Zone-11.",Own Sources,11,2015-16,2017-18 NL/2015-16/7817,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,884000,"Improvements to Side drain at Rayala nagar 2nd main road and Rayala nagar 3rd main road in Dn-155, Unit-34, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/8839,Playfields,Completed,NL-VALASARAVAKKAM,149,987000,"Improvement to children's play area at Palaniappa Nagar Krishna street in Dn.149,Unit-33,Zone-XI.",Own Sources,11,2015-16,2017-18 NL/2015-16/9418,Roads,Completed,NL-VALASARAVAKKAM,155,940000,"Attending Patch work with GSB at Various streets in Division -150, 151, 153, 154 and 155, Unit-34, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/9506,Buildings,Completed,NL-VALASARAVAKKAM,155,146000,"Providing Platform all around BIO Toilet at Dn.151, 153, 154 and 155, U-34, Z-XI.",Own Sources,11,2015-16,2016-17 NL/2015-16/9573,Roads,Completed,NL-VALASARAVAKKAM,143,930000,"Attending Patch work with GSB at Various streets in Division -143.144,146 and 147, Unit-32, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/9577,Roads,Completed,NL-VALASARAVAKKAM,145,630000,"Attending Patch work with GSB at Various streets in Division -145.148,149 and 152, Unit-33, Zone-11.",Own Sources,11,2015-16,2016-17 NL/2015-16/9967,Roads,Completed,NL-VALASARAVAKKAM,148,135490,"Laying Cement Concrete Road at CDN Nagar 5th Street in DN-148, Unit-33, Zone-XI.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/9969,Roads,Completed,NL-VALASARAVAKKAM,148,293700,"Laying Cement Concrete Road at CDN Nagar 7th Street in DN-148, Unit-33, Zone-XI.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/9970,Roads,Completed,NL-VALASARAVAKKAM,148,407800,"Laying Cement Concrete Road at CDN Nagar 6th Street in DN-148, Unit-33, Zone-XI.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/9971,Roads,Completed,NL-VALASARAVAKKAM,148,227500,"Laying Cement Concrete Road at CDN Nagar 13th Street in DN-148, Unit-33, Zone-XI.",Loans And Grants,11,2015-16,2016-17 NL/2015-16/9974,Roads,Completed,NL-VALASARAVAKKAM,148,354100,"Laying Cement Concrete Road at CDN Nagar 14th Street in DN-148, Unit-33, Zone-XI.",Loans And Grants,11,2015-16,2016-17 NM/2015-16/0577,Footpath,Completed,NM-ALANDUR,166,811000,"FORMING FOOTPATH AT POONTHOTTAM MAIN ROAD IN DN 166, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/0635,Parks,Completed,NM-ALANDUR,167,974000,"IMPROVEMENT WORK IN EXISTING INDEPENDENCE DAY PARK TO PAINTING COMPOUND WALL, TOILET AND FOOT PATH IN DIVISION-167 UNIT-36 ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/0723,Footpath,Completed,NM-ALANDUR,157,159000,"PROVIDING INTERLOCKING BLOCK AT NARMADHA STREET IN DIV-157, UNIT- 35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/0988,Buildings,Completed,NM-ALANDUR,162,445000,"IMPROVEMENT WORKS AT BURIAL GROUND TG NAGAR 2nd MAIN ROAD IN DN-162,U-36,Z-XII.",Own Sources,12,2015-16,2016-17 NM/2015-16/0989,Buildings,Completed,NM-ALANDUR,162,246000,"IMPROVEMENT WORKS AT BURIAL GROUND TG NAGAR 1st MAIN ROAD IN DN-162,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/10001,Culvert,Completed,NM-ALANDUR,156,250000,"Providing RCC Culvert at Mugalivakkam Main Road in Dn-156, U-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/10151,Buildings,Completed,NM-ALANDUR,158,268000,"Painting works to Kalaiarangam & Ration Shop at IDPL campus in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/10154,Buildings,Completed,NM-ALANDUR,158,235000,"Renovation works to IDPL Entry gate in Di-158,U-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/10248,Roads,Completed,NM-ALANDUR,164,645000,"IMPROVEMENT WORKS TO CEMENT CONCRETE ROAD AT KABILAR STREET (FROM BALUSAMY STREET TO KABILAR STREET EXTN ) IN DN-164, UNIT-37, ZONE-12. UNDER COUNCILLOR FUND",Own Sources,12,2015-16,2016-17 NM/2015-16/10259,Roads,Completed,NM-ALANDUR,164,645000,"IMPROVEMENT WORKS TO CEMENT CONCRETE ROAD AT KABILAR STREET (FROM KABILAR STREET EXNT TO VENGATACHALAM STREET ) IN DN-164, UNIT-37, ZONE-12. UNDER COUNCILLOR FUND",Own Sources,12,2015-16,2016-17 NM/2015-16/11363,Roads,Completed,NM-ALANDUR,162,758000,"LAYING OF CEMEND CONCETE ROAD WITH M30 IN DURAIRAJ 1ST STREET Divi-162,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/11405,Roads,Completed,NM-ALANDUR,162,522000,"LAYING OF CEMEND CONCETE ROAD WITH M30 IN BHARTHIYAR 2ND STREET DIV-162, U-36, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/11411,Roads,Completed,NM-ALANDUR,162,430000,"LAYING OF CEMEND CONCETE ROAD WITH M30 IN BHARATHIYAR LANE ATDIV-162,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/11417,Roads,Completed,NM-ALANDUR,162,656000,"LAYING OF CEMEND CONCETE ROAD WITH M30 IN BHARATHIYAR EXNT AND RAILWAY ROAD OF DIV-162, U-36, Z-12",Own Sources,12,2015-16,2017-18 NM/2015-16/11762,Buildings,Completed,NM-ALANDUR,163,120000,"IMPROVEMENT WORKS TO URBAN DEVELOPMENTS HEALTH BUILDING AT MANNADIAMMAN KOIL STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/11854,Buildings,Completed,NM-ALANDUR,163,2500000,"PROPOSED CONSTRUCTION OF KARIYA MANDAPAM AT BALAKRISHNAPURAM BURIAL GROUND IN DN-163,U-36,Z-12 (COUNCILLOR FUND)",Own Sources,12,2015-16,2016-17 NM/2015-16/11893,Buildings,Completed,NM-ALANDUR,161,188000,"PROVIDING BORE WELL ARRANGEMENTS WORKS TO CHENNAI PRIMARY SCHOOL AT AR LANE IN DIV-161 ,U-36, Z-XII.",Own Sources,12,2015-16,2016-17 NM/2015-16/11901,Buildings,Completed,NM-ALANDUR,161,172000,"Improvements Works to Division Office Building at Raja Street in Division-161, Unit-36, Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/11935,Roads,Completed,NM-ALANDUR,162,708000,"LAYING OF CEMEND CONCETE ROAD WITH M30 IN DURAIRAJ STREET DIV-162, U-36, Z-12.",Own Sources,12,2015-16,2017-18 NM/2015-16/11936,Roads,Completed,NM-ALANDUR,161,180000,"IMPROVEMENTS WORKS TO MURUGAN NAGAR PARK IN DN-161,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/12047,Storm Water Drain,Completed,NM-ALANDUR,161,990000,"Improvement of Side Drain at JEEVAN NAGAR MAIN ROAD WEST SIDE in Division -161 Unit-36, Zone-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/12235,Buildings,Completed,NM-ALANDUR,157,967000,"IMPROVEMENTS WORKS OF SWD AT PRASED GARDEN ROAD (COUNCILLOR FUND) IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12236,Buildings,Completed,NM-ALANDUR,157,400000,"IMPROVEMENTS WORKS OF SWD AT MGR NAGER 3RD STREET (COUNCILLOR FUND) IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12237,Buildings,Completed,NM-ALANDUR,157,332000,"IMPROVEMENTS WORKS OF SWD AT MGR NAGER 2ND STREET (COUNCILLOR FUND) IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12238,Buildings,Completed,NM-ALANDUR,157,415000,"IMPROVEMENTS WORKS OF SWD AT MGR NAGER 1ST STREET (COUNCILLOR FUND) IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12241,Buildings,Completed,NM-ALANDUR,157,886000,"IMPROVEMENTS WORKS OF SWD AT MGR NAGER MAIN ROAD (COUNCILLOR FUND) IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12585,Roads,Completed,NM-ALANDUR,165,991000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/12591,Roads,Completed,NM-ALANDUR,165,967000,"PROVIDING OF NAME BOARD IN VARIOUS STREET (NILAMANGAI NAGAR AND VANUVAMPET AREA) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/12596,Roads,Completed,NM-ALANDUR,165,967000,"PROVIDING OF NAME BOARD IN VARIOUS STREET (BHARATH NAGAR AREA) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/12829,Roads,Completed,NM-ALANDUR,158,316000,"Providing and closing the open Earthern Drain from Thulasingapuram to Adyar river in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12845,Storm Water Drain,Completed,NM-ALANDUR,165,854000,"IMPROVEMENT WORKS TO SIDE DRAIN AT BALAJI NAGAR 10TH STREET SOUTH SIDE IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/12846,Storm Water Drain,Completed,NM-ALANDUR,165,995000,"IMPROVEMENT WORKS TO SIDE DRAIN AT BALAJI NAGAR MAIN ROAD (FROM BALAJI NAGAR 3RD STREET TO LAKSHMI NAGAR 1ST STREET) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/12847,Storm Water Drain,Completed,NM-ALANDUR,165,854000,"IMPROVEMENT WORKS TO SIDE DRAIN AT BALAJI NAGAR 13TH STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/12860,Buildings,Completed,NM-ALANDUR,165,993000,"Improvement works to CPS at Ram Nagar in Dn-165, U-37,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12868,Buildings,Completed,NM-ALANDUR,160,321000,"Improvements to the existing Super Bazzar Complex for changing of Dhanraj hospital at New street in Dn-160, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/12890,Buildings,Completed,NM-ALANDUR,165,990000,"PROVIDING PLAY APPARATUS,ALUMINIUM PARTITION AND IIMPROVEMENT WORKS IN CPS AT RAM NAGAR IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/12933,Buildings,Completed,NM-ALANDUR,160,995000,"Improvements work to Gandhi Hospital At Sowri Street in Dn-160, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/13058,Roads,Completed,NM-ALANDUR,162,950000,"Windning of the road using pavablocks in Bharathiyar Railway road in DIV-162, U-36, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13101,Roads,Completed,NM-ALANDUR,162,915000,"widening of the road using pavarblocks in durairaj street DIV-162, U-36, Z-12.",Own Sources,12,2015-16,2017-18 NM/2015-16/13165,Roads,Completed,NM-ALANDUR,156,777000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT Annai Velankanni nagar Phase-I, Annai Velankanni nagar Phase-II,AGS Colony Krishnaveni street,Ramachandra nagar IN DIV 156,UNIT-35,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13212,Storm Water Drain,Completed,NM-ALANDUR,160,721000,"Improvements to the existing Storm Water drain at James street in Dn-160, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/13237,Footpath,Completed,NM-ALANDUR,166,472000,"FORMING FOOTPATH AND LAYING INTERLOCKING PAVER BLOCKS AT NEHRU NEDUNCHALAI (IN FRONT OF SBI COLONY PARK ) IN DN 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13238,Culvert,Completed,NM-ALANDUR,166,92000,"CONSTRUCTION OF CULVERT AT RATHINAPURAM MALAI SARIVU SALAI IN DN 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13239,Footpath,Completed,NM-ALANDUR,166,956000,"FORMING FOOTPATH AT KAMARAJAR STREET, GANDHI NAGAR IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13308,Roads,Completed,NM-ALANDUR,167,922000,"WIDENING THE ROAD USING INTER LOCKING PAVER BLOCKS AT CIVIL AVIATION COLONY MAIN ROAD, CIVIL AVIATION 1ST STREET, CIVIL AVIATION COLONY 1ST CROSS STREET, CIVIL AVIATION COLONY 2ND STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13322,Electrical,Completed,NM-ALANDUR,166,250000,Supply and fixing of 10 mtrs minimast in div 166,Earmarked Fund,12,2015-16,2016-17 NM/2015-16/13338,Buildings,Completed,NM-ALANDUR,156,350000,"PROVIDING OF RAIN WATER HARVESTING STRUCTURE AT TEN LOCATIONS USING PRECAST WELL RING SIZE 1200(OUTER DIA) X 4500MM HIEGHT (300MM X 15 NOS) 40MM THICK USING 1:1.5:3 CONCRETE NECESSARY EARTH WORK EXCAVATION , FILLING WITH 20MM HBG METAL OUT SIDE PERIPHERAL OF THE WELL, PROVIDING OF RCC COVER SLAB 1300MM DIA 150MM HIEGHT AND 100MM WIDTH COVERED WITH RCC COVER SLAB 1300MM DIA & 100MMTHICK, CONNECTER TO THE SILT CATCH PIT 450MM X 4500 X 450MM USING 160MM DIA PVC PIPE, INCLUDING COST, CONVEYANCE, CLEANING THE SITE AND FINISHING ETC., COMPLETED IN DIV-156,UNIT-35, ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13377,Road Cut,Completed,NM-ALANDUR,160,969000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN 160, 35 Z 12",Own Sources,12,2015-16,2016-17 NM/2015-16/13441,Parks,Completed,NM-ALANDUR,156,692000,"Providing and fixing Stainless Steel childrens Play apparatus at Kumudham nagar park in Division-156, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/13452,Parks,Completed,NM-ALANDUR,156,245000,"Providing Perculation Pit for Corporation parks in Dn-156, U-35, Zn-12",Own Sources,12,2015-16,2017-18 NM/2015-16/13455,Parks,Completed,NM-ALANDUR,157,290000,"Providing and fixing Stainless Steel childrens Play apparatus at Kaviya Garden park in Division-157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/13548,Roads,Completed,NM-ALANDUR,167,895000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13551,Culvert,Completed,NM-ALANDUR,163,201000,"PROPOSED CONSTRUCTION OF RCC CULVERTE AT BALAKRISHNAPURAM 6TH STREET IN DN63,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/13557,Roads,Completed,NM-ALANDUR,167,883000,"PROVIDING RETRO REFLECTIVE STREET NAME BOARD AT VARIOUS STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13574,Roads,Completed,NM-ALANDUR,166,895000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13584,Roads,Completed,NM-ALANDUR,166,888000,"PROVIDING RETRO REFLECTIVE STREET NAME BOARD AT VARIOUS STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13641,Storm Water Drain,Completed,NM-ALANDUR,167,617000,"CONSTRUCTION OF SIDE DRAIN AT KANNAN NAGAR 5TH STREET, IN DN 167, UNIT 37, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/13655,Storm Water Drain,Completed,NM-ALANDUR,159,698000,"IMPROVEMENT WORKS TO EXISTING STORM WATER DRAIN AT DR.AMBEDKAR STREET NORTH SIDE IN DN-159 , UNIT-35 , ZONE-12 .",Own Sources,12,2015-16,2016-17 NM/2015-16/13658,Buildings,Completed,NM-ALANDUR,160,139000,"DEMOLISHING OF DHANRAJ HOSPITAL BUILDING AT APPAVU STREET IN DN-160,U-35,Z-12",Own Sources,12,2015-16,2017-18 NM/2015-16/13659,Storm Water Drain,Completed,NM-ALANDUR,159,698000,"IMPROVEMENT WORKS TO EXISTING STORM WATER DRAIN AT DR.AMBEDKAR STREET SOUTH SIDE IN DN-159 , UNIT-35 , ZONE-12 .",Own Sources,12,2015-16,2016-17 NM/2015-16/13672,Storm Water Drain,Completed,NM-ALANDUR,159,986000,IMPROVEMENT TO EXISTING STORM WATER DRAIN. KAMARAJ STREET NORTH SIDE AT DIV 159 U-35 Z-12,Own Sources,12,2015-16,2016-17 NM/2015-16/13698,Buildings,Completed,NM-ALANDUR,163,946000,REPAIR AND IMPROVEMENTS WORKS TO BURIAL GROUND AT BALAKRISHNAPURAM IN DN 163 U.36.Z.12,Own Sources,12,2015-16,2016-17 NM/2015-16/13699,Buildings,Completed,NM-ALANDUR,163,948000,"ADDITION IMPROVEMENT WORKS TO AMMA UNAVAGAM AT BALAKRISHNAPURAM MAIN ROAD IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2017-18 NM/2015-16/13707,Storm Water Drain,Completed,NM-ALANDUR,159,986000,IMPROVEMENT TO EXISTING STORM WATER DRAIN. KAMARAJ STREET SOUTH SIDE AT DIV 159 U-35 Z-12,Own Sources,12,2015-16,2016-17 NM/2015-16/13721,Roads,Completed,NM-ALANDUR,158,628000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DIV 158,UNIT-35,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13761,Parks,Completed,NM-ALANDUR,162,850000,"Improvement work of park at Thillai ganga nagar 33rd street in Div-162, U-36, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13766,Parks,Completed,NM-ALANDUR,157,990000,PROVIDING STAINLESS STEEL HANDRAIL TO THE PATHWAY AT THE PARK AT BELL NAGAR IN DIV -157 UNIT -35 ZONE-12.(UNDER COUNCILLOR WARD IMPROVEMENT FUND),Own Sources,12,2015-16,2016-17 NM/2015-16/13768,Buildings,Completed,NM-ALANDUR,157,990000,PROVIDING STAINLESS STEEL HANDRAIL TO THE INNER SIDE OF THE PATHWAY AT THE PARK AT MACRO MARVEL IN DIV -157 UNIT -35 ZONE-12.(UNDER COUNCILLOR WARD IMPROVEMENT FUND),Own Sources,12,2015-16,2016-17 NM/2015-16/13770,Parks,Completed,NM-ALANDUR,157,990000,PROVIDING STAINLESS STEEL HANDRAIL TO THE OUTER SIDE OF THE PATHWAY AT THE PARK AT MACRO MARVEL IN DIV -157 UNIT -35 ZONE-12.(UNDER COUNCILLOR WARD IMPROVEMENT FUND),Own Sources,12,2015-16,2016-17 NM/2015-16/13805,Parks,Completed,NM-ALANDUR,164,870000,"Improvement works to Children's park at Nehru street in Division-164, Unit-37,Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/13806,Parks,Completed,NM-ALANDUR,164,880000,"Improvement works to Children's park at Nanganallur 29th street in Division-164, Unit-37,Zone-12.",Own Sources,12,2015-16,2017-18 NM/2015-16/13813,Roads,Completed,NM-ALANDUR,158,325000,"Attending Patch work at Anna main road in Dn-158, U-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/14148,Storm Water Drain,Completed,NM-ALANDUR,164,936000,"IMPROVEMENT TO EXISTING STORM WATER DRAIN AT NERU COLONY MAIN ROAD ( FROM NANGANALLUR 5TH MAIN ROAD TO NEHRU COLONY 10TH STREET ) IN DIVISION-164, UNIT-37, ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/14152,Storm Water Drain,Completed,NM-ALANDUR,164,936000,"IMPROVEMENT TO EXISTING STORM WATER DRAIN AT NERU COLONY MAIN ROAD ( FROM NEHRU COLONY 10TH STREET TO NEHRU COLONY 6th STREET ) IN DIVISION-164, UNIT-37, ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/14167,Storm Water Drain,Completed,NM-ALANDUR,165,960000,"Improvement works to side drain at Nethaji street in Div 165,Unit 37,Zone 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/14466,Parks,Completed,NM-ALANDUR,156,952000,"Improvement works to Sabari nagar park at Mugalivakkam in Dn-156,U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/1447,Buildings,Completed,NM-ALANDUR,157,131000,"Providing Electrical Fittings and arrangements for the of community hall 1st floor at MG road in Dn 157, Unit 35, Zn 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14621,Roads,Completed,NM-ALANDUR,156,250000,"FORMING ROAD USING GSB, WMM AT SUBHASHREE NAGAR IV EXTN 1ST STREET IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14624,Roads,Completed,NM-ALANDUR,156,226000,"FORMING ROAD USING GSB, WMMAT KUTRALAM NAGAR IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14625,Roads,Completed,NM-ALANDUR,156,167000,"FORMING ROAD USING GSB, WMMAT MADHA KOIL STREET IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14626,Roads,Completed,NM-ALANDUR,156,278000,"FORMING ROAD USING GSB, WMM AT SS KOIL STREET EXTN IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14627,Roads,Completed,NM-ALANDUR,156,104000,"FORMING ROAD USING GSB, WMM AT ARUNAGIRI STREET IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14629,Roads,Completed,NM-ALANDUR,156,167000,"FORMING ROAD USING GSB, WMMAT SUBBAIAH NAGAR IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14637,Roads,Completed,NM-ALANDUR,156,313000,"FORMING ROAD USING GSB, WMM AT RAJESWARI AVENUE YAMUNA STREET IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14638,Roads,Completed,NM-ALANDUR,156,292000,"FORMING ROAD USING GSB, WMMAT RAJESWARI AVENUE PONNI STREET IN DIVISION 156, UNIT 35, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14730,Playfields,Completed,NM-ALANDUR,164,864000,"ADDITIONAL WORKS AND FIXING GYM EQUIPMENT FOR NEW COLONY 2ND STREET GYM AT DIV-164, UNIT- 37 ZONE- 12",Own Sources,12,2015-16,2016-17 NM/2015-16/14886,Buildings,Completed,NM-ALANDUR,158,715000,"Improvement works to Public Convenience at Ramar koil street in Dn-158, U-35,Zn-12",Own Sources,12,2015-16,2018-19 NM/2015-16/14888,Storm Water Drain,Completed,NM-ALANDUR,158,769000,"Improvement works to side drain at Sundar Nagar 2nd Avenue Western Side(Councillor Scheme) in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/14916,Storm Water Drain,Completed,NM-ALANDUR,158,691000,"Improvement works to side drain at Sundar Nagar 3rd Avenue eastern Side(Councillor Scheme) in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/15116,Culvert,Completed,NM-ALANDUR,164,625000,"Improvement works to culverts at nehru colony main road junction of 5th and 6th , 8th street and nehru colony 17th street junction of naganallur 5th main road in division-164 , unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/15124,Culvert,Completed,NM-ALANDUR,164,860000,"Laying of culverts at nehru colony main road junction of 11th street and nehru colony 13th street jn of nanganalure 5th main road and Nanganallur 25th street, 13th, 27th, and 37th street junction of Nanganallur 3rd main road in division-164 , unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/15162,Buildings,Completed,NM-ALANDUR,162,999000,"CONSTRUCTION OF NAMMA TOILET AT THILLAI GANGA NAGAR 4TH MAIN ROAD IN DIVISION- 162, UNIT- 36, ZONE- 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/15188,Buildings,Completed,NM-ALANDUR,162,973000,"Construction of compound wall and fencing on the western side of Park with children play ground at Thiruvalluvar Nagar 3rd street in Dn - 162, U - 36, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/15524,Buildings,Completed,NM-ALANDUR,163,998000,"CONSTRUCTION OF ARASU CABLE TACTV COMMON SERVICE CENTER AT PARTHASARATHY NAGAR 8TH EXNT IN DN-163,36,Z-12",Own Sources,12,2015-16,2017-18 NM/2015-16/15531,Buildings,Completed,NM-ALANDUR,159,980000,"Improvements works at division office building for providing Arasu cable TACTV common service centre at Kamaraj street in Division - 159, Unit - 35, Zone - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/15904,Buildings,Completed,NM-ALANDUR,167,970000,"ADDITIONAL IMPROVEMENTS TO YOGA PLATFORM AND YOGA CENTRE AT INDEPENDENCEDAY PARK, IN DN 167, UNIT 37, ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/15947,Roads,Completed,NM-ALANDUR,166,1160000,"LAYING RMC 30 GRADE CEMENT CONCRETE ROAD AT B.V.NAGAR 17TH STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/16108,Storm Water Drain,Completed,NM-ALANDUR,166,1095000,"CONSTRUCTION OF STORM WATER DRAIN AT B.V.NAGAR 17TH STREET AND PROVIDING STREET SIGN BOARD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/16144,Road Cut,Completed,NM-ALANDUR,158,956000,"Road cut Restoration at Anna Nagar 1st main road in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16155,Buildings,Completed,NM-ALANDUR,158,217000,"Improvements work to amma unavagam at Bajanai koil street in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16187,Buildings,Completed,NM-ALANDUR,160,852000,"Improvement works to Zonal Office building at New street in dn-160, U-35, Zn-12",Own Sources,12,2015-16,2017-18 NM/2015-16/16194,Buildings,Completed,NM-ALANDUR,160,139000,"Improvement works to NNMP shed at Ramasamy bandhu lane in Dn-160,U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16197,Buildings,Completed,NM-ALANDUR,160,274000,"Improvement works to Gandhi hospital at sowri street in Dn-160,U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16239,Roads,Completed,NM-ALANDUR,165,47000,"Providing Silt catch Pit At South sector& New colony 2nd street in Dn-165, U-37, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16279,Roads,Completed,NM-ALANDUR,167,990000,"ATTENDING PATCH WORKS MADE BY CMWSSB AT VARIOUS STREETS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/16306,Buildings,Completed,NM-ALANDUR,157,651000,"CONSTRUCTION OF SWD AT DOOR.NO: 2/471 TO DEAD END DR. AMBEDKAR NAGAR CHURCH STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16323,Buildings,Completed,NM-ALANDUR,157,176000,"IMPROVEMENTS WORKS OF SWD AT INDRA NAGER 1ST CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16324,Buildings,Completed,NM-ALANDUR,157,183000,"IMPROVEMENTS WORKS OF SWD AT INDRA NAGAR 2ND CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16325,Buildings,Completed,NM-ALANDUR,157,509000,"IMPROVEMENTS WORKS OF SWD AT INDRA NAGAR 2ND MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16331,Buildings,Completed,NM-ALANDUR,157,242000,"IMPROVEMENTS WORKS OF SWD AT KRISHNA NAGAR 5TH CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16332,Buildings,Completed,NM-ALANDUR,157,998000,"IMPROVEMENTS WORKS OF SWD AT PERIYA SALAI STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16342,Buildings,Completed,NM-ALANDUR,157,277000,"IMPROVEMENTS WORKS OF SWD AT KRISHNA NAGER 3RD CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16424,Buildings,Completed,NM-ALANDUR,157,633000,"CONSTRUCTION OF SWD AT DISPOSAL POINT TO DOOR.NO : 2/471 DR. AMBEDKAR NAGAR CHURCH STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16462,Roads,Completed,NM-ALANDUR,157,356000,"RAISING THE ROAD AT DR.AMBEDKAR NAGAR CHURCH STREET EXTEN IN DN -157, UNIT -35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/16568,Roads,Completed,NM-ALANDUR,166,984000,"ATTENDING PATCH WORKS AT VARIOUS STREETS IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/17338,Roads,Completed,NM-ALANDUR,161,1395000,"LAYING CC ROAD FOR USING RMC M30 CONCRETE AT SUBRAMANIYA SWAMY KOIL STREET ( COUNCILLOR FUND) IN DN-161,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/17340,Roads,Completed,NM-ALANDUR,161,1445000,"LAYING CC ROAD FOR USING RMC M30 CONCRETE AT ALAGIRI STREET (COUNCILLOR FUND) IN DN-161,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/17663,Roads,Completed,NM-ALANDUR,157,158000,"RAISING THE ROAD AT MUKTHI ENCLAVE 1ST CROSS STREET IN DIV -157 ,UNIT-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/17671,Roads,Completed,NM-ALANDUR,157,127000,"RAISING THE ROAD AT AMBEDKAR NAGAR 4TH MAIN ROAD IN DIV -157 ,UNIT-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/17672,Roads,Completed,NM-ALANDUR,157,320000,"RAISING THE ROAD AT METTU COLONY ANNA STREET IN DIV -157 ,UNIT-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/17674,Roads,Completed,NM-ALANDUR,157,360000,"ROAD WIDENING AT RIVER VIEW COLONY MAIN ROAD IN DIV -157 ,UNIT-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/17848,Roads,Completed,NM-ALANDUR,162,999000,"PROVIDING GSB AND WMM AT VARIOUS STREET IN DIV-162,Unit-36, ZONE12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18447,Storm Water Drain,Completed,NM-ALANDUR,165,626000,"Improvement works to side drain at Elango Street in dn-165, U-37, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/18530,Buildings,Completed,NM-ALANDUR,160,740000,"Providing Flooring tiles for class rooms at Chennai Primary School at Jaal Street in Dn.160, U - 36, z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18531,Buildings,Completed,NM-ALANDUR,160,440000,"Construction of Open Stage and providing flooring tiles for class rooms at Chennai High School at Jaal Street in Dn.160, U - 35, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18724,Storm Water Drain,Completed,NM-ALANDUR,164,640000,"Improvement works to existing storm water drain at Brindhavan nagar 2nd streets in Dn-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2017-18 NM/2015-16/18773,Roads,Completed,NM-ALANDUR,165,424000,"SUPPLYING AND FIXING STAINLESS STEEL NAME BOARDS FOR CORPORATION BUILDINGS IN DN-165,U-37,ZN-12",Own Sources,12,2015-16,2016-17 NM/2015-16/18812,Storm Water Drain,Completed,NM-ALANDUR,167,250000,"CONSTRUCTION OF SIDE DRAIN AT NANGANALLUR 46TH STREET 2ND CROSS STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18813,Storm Water Drain,Completed,NM-ALANDUR,167,580000,"CONSTRUCTION OF SIDE DRAIN AT LAKSHMI NAGAR 2ND STREET (3RD STAGE) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18814,Storm Water Drain,Completed,NM-ALANDUR,167,860000,"CONSTRUCTION OF SIDE DRAIN AT LAKSHMI NAGAR 3RD STAGE MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18822,Storm Water Drain,Completed,NM-ALANDUR,167,300000,"CONSTRUCTION OF CULVERT AT HINDU COLONY 23RD CROSS STREET JN OF 22ND STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2018-19 NM/2015-16/18823,Culvert,Completed,NM-ALANDUR,167,430000,"CONSTRUCTION OF CULVERT AT TNGO COLONY MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2018-19 NM/2015-16/18824,Culvert,Completed,NM-ALANDUR,167,855000,"CONSTRUCTION OF CULVERT AT NANGANALLUR 40TH, 42ND, 44TH STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18825,Culvert,Completed,NM-ALANDUR,167,855000,"CONSTRUCTION OF CULVERT AT AGS COLONY 4TH AND 5TH STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18833,Storm Water Drain,Completed,NM-ALANDUR,166,860000,"IMPROVEMENT TO EXISTING STORM WATER DRAIN AT KAMARAJAR STREET(OODAI STREET) IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18850,Culvert,Completed,NM-ALANDUR,164,375000,"Laying of Box culverts at naganallur 38th street culvert and 37th extn jn of naganallur .3rd main road in Dn-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/18882,Footpath,Completed,NM-ALANDUR,165,510000,"REPAIR AND IMPROVEMENT WORKS TO FOOTPATH AT VARIOUS STREETS IN DN-165,UNIT-37,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/18921,Roads,Completed,NM-ALANDUR,156,638000,"PROVIDING AND LAYING GSB & WMM AT THIRPURASUNDHARI AVENUE IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/19168,Storm Water Drain,Completed,NM-ALANDUR,164,905000,"providing storm water drain at nanganallur 38th street (north side) in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/19169,Storm Water Drain,Completed,NM-ALANDUR,164,905000,"providing storm water drain at thillai ganga nagar 5th main road (east side) in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/19172,Storm Water Drain,Completed,NM-ALANDUR,164,945000,"Improvement works to existing storm water drain at nanganallur 37th extn (north side) in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/19174,Storm Water Drain,Completed,NM-ALANDUR,164,690000,"Improvement works to existing storm water drain at nanganallur 22nd street (south side) in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/19181,Storm Water Drain,Completed,NM-ALANDUR,164,525000,"Improvement works to existing storm water drain at Brindhavan nagar 1st street in Dn-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2018-19 NM/2015-16/19872,Road Cut,Completed,NM-ALANDUR,157,226000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KAVIYA GARDEN MULLAI STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19873,Road Cut,Completed,NM-ALANDUR,157,61000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KAVIYA GARDEN KURINJI STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19874,Road Cut,Completed,NM-ALANDUR,157,154000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT VALLISWARAN KOIL STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19875,Road Cut,Completed,NM-ALANDUR,157,43000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KAVIYA GARDEN KRISHNAKAMALAM IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19876,Road Cut,Completed,NM-ALANDUR,157,90000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KAVIYA GARDEN MANORANJITHAM STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19877,Road Cut,Completed,NM-ALANDUR,157,95000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KAVIYA GARDEN PATTURAJA STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19878,Road Cut,Completed,NM-ALANDUR,157,60000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM 1st LEFT CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19879,Road Cut,Completed,NM-ALANDUR,157,332000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM 1st MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19880,Road Cut,Completed,NM-ALANDUR,157,58000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM 2nd LEFT CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19881,Road Cut,Completed,NM-ALANDUR,157,54000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM 2nd MAIN ROAD 2nd CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19882,Road Cut,Completed,NM-ALANDUR,157,183000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM 2nd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19883,Road Cut,Completed,NM-ALANDUR,157,44000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM 3rd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19886,Road Cut,Completed,NM-ALANDUR,157,33000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM 3rd MAIN ROAD RIGHT CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19887,Road Cut,Completed,NM-ALANDUR,157,137000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT Dr. AMBEDKAR NAGAR 2nd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19888,Road Cut,Completed,NM-ALANDUR,157,109000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT Dr. AMBEDKAR NAGAR 4th MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19889,Road Cut,Completed,NM-ALANDUR,157,114000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT Dr. AMBEDKAR NAGAR 5th MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19890,Road Cut,Completed,NM-ALANDUR,157,70000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYAR SALAI 2nd CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19891,Road Cut,Completed,NM-ALANDUR,157,140000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYAR SALAI 3rd CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19892,Road Cut,Completed,NM-ALANDUR,157,68000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYAR SALAI 4th CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19893,Road Cut,Completed,NM-ALANDUR,157,128000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYAR SALAI 5th CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19894,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGAR 1st MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19895,Road Cut,Completed,NM-ALANDUR,157,56000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGAR 2nd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19896,Road Cut,Completed,NM-ALANDUR,157,81000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGAR 3rd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19897,Road Cut,Completed,NM-ALANDUR,157,239000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGAR MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19898,Road Cut,Completed,NM-ALANDUR,157,136000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGAR 3rd CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19899,Road Cut,Completed,NM-ALANDUR,157,64000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGAR 6th & 7th STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19900,Road Cut,Completed,NM-ALANDUR,157,145000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PRESIDENT MUNUSAMY NAGAR IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19915,Road Cut,Completed,NM-ALANDUR,157,214000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MGR NAGAR 1st STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19916,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MGR NAGAR 2nd STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19918,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MGR NAGAR 3rd STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19923,Road Cut,Completed,NM-ALANDUR,157,38000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MACROMARVEL RIVER COUNTRY 6th CROSS STREET EAST IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19924,Road Cut,Completed,NM-ALANDUR,157,94000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SETHULAKSHMI AVENUE RIGHT 1ST CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19938,Road Cut,Completed,NM-ALANDUR,157,94000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PILLAYAR KOIL 5th STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19940,Road Cut,Completed,NM-ALANDUR,157,111000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19941,Road Cut,Completed,NM-ALANDUR,157,94000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR 1st CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19942,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR 2nd CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19943,Road Cut,Completed,NM-ALANDUR,157,145000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PILLAYAR KOIL 4TH STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19944,Road Cut,Completed,NM-ALANDUR,157,103000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PILLAYAR KOIL 1ST STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19945,Road Cut,Completed,NM-ALANDUR,157,46000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PILLAYAR KOIL 2nd STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19946,Road Cut,Completed,NM-ALANDUR,157,43000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PILLAYAR KOIL 3rd STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19949,Road Cut,Completed,NM-ALANDUR,157,89000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR 3rd CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19951,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PARTHASARATHY NAGER ASTALAKSHMI AVENUE IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19973,Road Cut,Completed,NM-ALANDUR,157,196000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PRASHAD GARDEN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19975,Road Cut,Completed,NM-ALANDUR,157,86000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT Dr.AMBEDKAR NAGAR 3rd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19976,Road Cut,Completed,NM-ALANDUR,157,97000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR 2nd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19977,Road Cut,Completed,NM-ALANDUR,157,128000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT NEHRU STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19978,Road Cut,Completed,NM-ALANDUR,157,70000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR 3rd MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19979,Road Cut,Completed,NM-ALANDUR,157,67000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR 4th CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19980,Road Cut,Completed,NM-ALANDUR,157,29000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BELL NAGAR LINK ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19981,Road Cut,Completed,NM-ALANDUR,157,57000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19982,Road Cut,Completed,NM-ALANDUR,157,72000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT GIRI GORI NAGER 1ST MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19983,Road Cut,Completed,NM-ALANDUR,157,43000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT INDRA NAGER 1ST CROSS STREET LEFT IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19985,Road Cut,Completed,NM-ALANDUR,157,59000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MACRO MARVEL 4TH RIGHT CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19986,Road Cut,Completed,NM-ALANDUR,157,56000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MACRO MARVEL 5TH RIGHT CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19988,Road Cut,Completed,NM-ALANDUR,157,47000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MG SALAI- METTU COLONY BAJANAI KOIL STREET LINK ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19989,Road Cut,Completed,NM-ALANDUR,157,197000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MGR NAGER MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19990,Road Cut,Completed,NM-ALANDUR,157,102000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT NARKUDEESHWARER SALAI IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19991,Road Cut,Completed,NM-ALANDUR,157,54000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYAR SALAI CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19993,Road Cut,Completed,NM-ALANDUR,157,61000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGER 4TH STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19994,Road Cut,Completed,NM-ALANDUR,157,46000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT SATHIYA NAGER 5TH STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19996,Road Cut,Completed,NM-ALANDUR,157,57000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT TANK STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/19997,Road Cut,Completed,NM-ALANDUR,157,70000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT VALLESHWARAR KOIL CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20020,Buildings,Completed,NM-ALANDUR,157,113000,"IMPROVEMENTS WORKS OF PAINTING AT ICDS-01 IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2037,Storm Water Drain,Completed,NM-ALANDUR,161,998000,"IMPROVEMENT TO SWD AT MASTHANGORI STREET IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20451,Roads,Completed,NM-ALANDUR,158,293000,"Laying WMM road at M.G.R Nagar in Div-158, Unit-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20458,Storm Water Drain,Completed,NM-ALANDUR,158,355000,"Demolition of dilapidated culvert and construction of new culvert at Ramar koil street in Dn-158, U-35, Zn-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20464,Culvert,Completed,NM-ALANDUR,158,632000,"Demolition of dilapidated culvert and construction of new culvert at Madhavapuram west street, Vembuliamman koil street, Sowri street in Dn-160, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20466,Storm Water Drain,Completed,NM-ALANDUR,160,339000,"Improvements to side drain at Maduvankarai 2nd cross street in Dn-160, U-35,Zn-12",Own Sources,12,2015-16,2017-18 NM/2015-16/20467,Culvert,Completed,NM-ALANDUR,165,926000,"Demolition of dilapidated culvert and construction of new culvert at Thamirabarani street, Gothavari street, Thiruvalluvar street in Div-165,U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20500,Storm Water Drain,Completed,NM-ALANDUR,161,985000,"IMPROVEMENT OF SIDE DRAIN AT MUTTHIYAL REDDY 2ND LANE IN DN 161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/20507,Roads,Completed,NM-ALANDUR,160,969000,SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DIV.160 UNIT.35 ZONE.12.,Own Sources,12,2015-16,2016-17 NM/2015-16/20555,Culvert,Completed,NM-ALANDUR,166,975000,"DEMOLITION AND RECONSTRUCTION OF DILAPIDATED EXISTING CULVERT AT NEHRU NEDUNCHALAI JN OF B.V.NAGAR 13TH STREET, B.V.NAGAR 3RD STREET B.V.NAGAR 11TH STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20561,Storm Water Drain,Completed,NM-ALANDUR,166,952000,"IMPROVEMENTS TO EXISTING SIDE DRAIN AT NEHRU NEDUNCHALAI (FROM KAMARAJAR STREET TO TEACHERS COLONY 1ST STREET) IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2018-19 NM/2015-16/20584,Storm Water Drain,Completed,NM-ALANDUR,167,771000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT KANAGAMBAL COLONY MAIN ROAD (WESTEN SIDE) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20586,Storm Water Drain,Completed,NM-ALANDUR,167,527000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT KANAGAMBAL COLONY MAIN ROAD (EASTEN SIDE) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20587,Storm Water Drain,Completed,NM-ALANDUR,167,379000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT VENUGOPALAPURAM 1ST STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20590,Storm Water Drain,Completed,NM-ALANDUR,167,895000,"CONSTRUCTION OF SIDE DRAIN AT HINDU COLONY 11TH CROSS STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20602,Culvert,Completed,NM-ALANDUR,167,691000,"CONSTRUCTION OF CULVERT AT RANGA COLONY STATE BANK MAIN COLONY VISHWANATHAPURAM MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20604,Culvert,Completed,NM-ALANDUR,165,926000,"Demolition of dilapidated culvert and construction of new culvert at Tagore street, Balaji nagar 4th street,Vel nagar Extn main road,Vel nagar 2nd street in Div-165,U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20605,Culvert,Completed,NM-ALANDUR,165,461000,"Demolition of dilapidated culvert and construction of new culvert at Thamarai street, Sakthi nagar Extn in Div-165,U-35, Zn-12",Own Sources,12,2015-16,2017-18 NM/2015-16/20606,Culvert,Completed,NM-ALANDUR,167,710000,"CONSTRUCTION OF CULVERT AT HINDU COLONY 11TH CROSS STREET, HINDU COLONY 5TH CROSS STREET, HINDU COLONY 10TH CROSSS STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20611,Storm Water Drain,Completed,NM-ALANDUR,165,654000,"Improvement works to side drain at sakthi nagar Extn in dn-165, U-37, Zn-12",Own Sources,12,2015-16,2017-18 NM/2015-16/20754,Buildings,Completed,NM-ALANDUR,164,71000,"Maintenance works to amma unavagam and school building at krishnasamy street in Dn-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20892,Roads,Completed,NM-ALANDUR,156,953000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT MADHA NAGAR MAIN ROAD IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20894,Roads,Completed,NM-ALANDUR,156,353000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT RAJARAJESHWARI AVEUE NETHAJI STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20901,Roads,Completed,NM-ALANDUR,162,300000,"Attending patch work Thillaiganga Nagar 43rd street in Dn-162, U-36, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20902,Roads,Completed,NM-ALANDUR,156,180000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT MARIAMMAN KOIL STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20905,Roads,Completed,NM-ALANDUR,162,860000,"Attending patch work Thillai ganga nagar 1st main road in Dn-162, U-36Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20906,Roads,Completed,NM-ALANDUR,162,250000,"Attending patch work Thillaiganga Nagar 41st street in Dn-162, U-36, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20908,Roads,Completed,NM-ALANDUR,156,118000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT GOWRI NAGAR 1ST STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20912,Roads,Completed,NM-ALANDUR,156,656000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT L&D COLONY CRR PURAM IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20913,Roads,Completed,NM-ALANDUR,162,285000,"Attending patch work Thillaiganga Nagar 44th street in Dn-162, U-36, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20914,Roads,Completed,NM-ALANDUR,162,875000,"Attending patch work Thillaiganga Nagar 3rd main road in Dn-162, U-36, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20918,Roads,Completed,NM-ALANDUR,156,593000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT ARUMUGAM NAGAR 1ST AND 2ND STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20920,Roads,Completed,NM-ALANDUR,156,215000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT VND NAGAR GANGA SALAI IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20924,Roads,Completed,NM-ALANDUR,156,251000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT CAWARI STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20927,Roads,Completed,NM-ALANDUR,164,875000,"Attending patch work Nanganallur 3rd main road in Dn-164, U-37, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20928,Roads,Completed,NM-ALANDUR,164,535000,"Attending patch work Nanganallur 21st street in Dn-164, U-37, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20929,Roads,Completed,NM-ALANDUR,164,535000,"Attending patch work Nanganallur 23rd street in Dn-164, U-37, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20930,Roads,Completed,NM-ALANDUR,156,180000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT MAHALAKSMI NAGAR EXTN IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20933,Roads,Completed,NM-ALANDUR,156,180000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT ANNAI THERASA STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20943,Roads,Completed,NM-ALANDUR,156,180000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT VOC STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20945,Roads,Completed,NM-ALANDUR,156,353000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT KRISHNA NAGAR 3RD MAIN ROAD IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20949,Roads,Completed,NM-ALANDUR,156,593000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT KRISHNA NAGAR 2ND MAIN ROAD IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20954,Roads,Completed,NM-ALANDUR,156,185000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT KRISHNA NAGAR EXTN IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20958,Roads,Completed,NM-ALANDUR,156,593000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT JAYACHANDRAN STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20961,Roads,Completed,NM-ALANDUR,156,593000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT RATHI STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20963,Roads,Completed,NM-ALANDUR,156,215000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT KARTHICK BALAJI STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20965,Roads,Completed,NM-ALANDUR,156,353000,"ATTENDING OF PATCH WORK OF FLOOD DAMAGED ROADS TEMPORARY RESTORATION AT BARANI STREET IN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/20993,Roads,Completed,NM-ALANDUR,166,657000,"ATTENDING PATCH WORK AT ELANGO STREET GANDHI NAGAR IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20994,Roads,Completed,NM-ALANDUR,166,657000,"ATTENDING PATCH WORK AT ANNA STREET GANDHI NAGAR IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/20997,Roads,Completed,NM-ALANDUR,166,355000,"ATTENDING PATCH WORK AT PERRIYAPALAYATHU AMMAN KOIL STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21001,Roads,Completed,NM-ALANDUR,166,431000,"ATTENDING PATCH WORK AT RAGHUPATHY NAGAR 7TH STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21028,Roads,Completed,NM-ALANDUR,166,988000,"ATTENDING PATCH WORK AT NEHRU NEDUNCHALAI IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21054,Roads,Completed,NM-ALANDUR,167,925000,"ATTENDING PATCH WORK AT VOLTAS COLONY 5TH STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21059,Roads,Completed,NM-ALANDUR,167,1696000,"ATTENDING PATCH WORK AT NANGANALLUR 100 FEET ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21066,Roads,Completed,NM-ALANDUR,167,762000,"ATTENDING PATCH WORK AT NANGANALLUR 46TH STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21068,Roads,Completed,NM-ALANDUR,167,1021000,"ATTENDING PATCH WORK AT EAST MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21225,Parks,Completed,NM-ALANDUR,165,260000,"ANNUAL MAINTENANCE OF PARK AT BHARATH NAGAR PARK IN DN.165,UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/21227,Parks,Completed,NM-ALANDUR,165,255000,"ANNUAL MAINTENANCE OF PARK AT N M NAGAR NETHAJI STREET PARK IN DN.165,UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/21228,Parks,Completed,NM-ALANDUR,165,252000,"ANNUAL MAINTENANCE OF PARK AT ADAMBAKKAM LAKSHMI NAGAR 1ST PARK IN DN.165, UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/21229,Parks,Completed,NM-ALANDUR,165,274000,"ANNUAL MAINTENANCE OF PARK AT SOUTH SECTOR KUNDRAKUDI NAGAR PARK IN DN.165, UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/21230,Parks,Completed,NM-ALANDUR,165,256000,"ANNUAL MAINTENANCE OF PARK AT BALAJI NAGAR PARK IN DN.165,UNIT-37,ZONE-12 (By qualified horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/21233,Parks,Completed,NM-ALANDUR,165,258000,"ANNUAL MAINTENANCE OF PARK AT SURENDERA NAGAR PARK 3RD STREET IN DN.165,UNIT-37,ZONE-12 (By Employed Qualified Horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/21323,Parks,Completed,NM-ALANDUR,167,260000,"MAINTENANCE OF PARK AT JAIN COLONY PARK IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21324,Buildings,Completed,NM-ALANDUR,167,933000,"Additional Improvement work to the CI and SI office at nanganallur 100 feet road in Dn - 167,U - 37, Z - 12",Own Sources,12,2015-16,2017-18 NM/2015-16/21325,Parks,Completed,NM-ALANDUR,167,256000,"MAINTENANCE OF PARK AT KANNIGA COLONY II street IN DN.167, U -37 , Z-12.(By employed qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21326,Parks,Completed,NM-ALANDUR,167,995000,"PROVIDING AND FIXING STAINLESS STEEL RAILS AT LAKSHMI NAGAR 3RD STAGE 7TH STREET PARK IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21327,Parks,Completed,NM-ALANDUR,167,254000,"MAINTENANCE OF PARK AT HINDU COLONY 26th STREET PARK IN DN.167, U -37 , Z-12.(By employed qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21328,Parks,Completed,NM-ALANDUR,167,270000,"MAINTENANCE OF PARK AT VOLTAS COLONY PARK 3rd street IN DN.167, U -37 , Z-12.(By employed qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21329,Parks,Completed,NM-ALANDUR,167,250000,"MAINTENANCE OF PARK AT KANNAN NAGAR I MAIN ROAD IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21330,Parks,Completed,NM-ALANDUR,167,252000,"MAINTENANCE OF PARK AT NANGANALLUR 46th STREET PARK IN DN.167, U -37 , Z-12.(By employed qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21331,Parks,Completed,NM-ALANDUR,167,252000,"MAINTENANCE OF PARK AT LAKSHMI NAGAR 7th STREET PARK IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21333,Parks,Completed,NM-ALANDUR,167,988000,"MAINTENANCE OF PARK AT INDEPENDENTS DAY PARK IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21334,Parks,Completed,NM-ALANDUR,167,259000,"MAINTENANCE OF PARK AT MMTC Colony Eswaran st Park IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21335,Parks,Completed,NM-ALANDUR,167,257000,"MAINTENANCE OF PARK AT LAKSHMI NAGAR 4th Stage IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21336,Parks,Completed,NM-ALANDUR,167,261000,"MAINTENANCE OF PARK AT CIVIL AVIATION COLONY SRI RAM COLONY PARK IN DN.167, U -37 , Z-12.(By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21337,Parks,Completed,NM-ALANDUR,167,254000,"MAINTENANCE OF PARK AT VIJAY AVENUE PARK IN DN.167, U -37, Z-12. (By qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21338,Parks,Completed,NM-ALANDUR,167,256000,"MAINTENANCE OF PARK AT KANNAN NAGAR I cross street IN DN.167, U -37 , Z-12. (By employed qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/21509,Roads,Completed,NM-ALANDUR,165,322000,Attending the BT Patch work for Flood Damaged Road At North new street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21510,Roads,Completed,NM-ALANDUR,165,268000,Attending the BT Patch work for Flood Damaged Road At Balaji nagar 10th street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21511,Roads,Completed,NM-ALANDUR,165,334000,Attending the BT Patch work for Flood Damaged Road At Sakthi nagar extn in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21513,Roads,Completed,NM-ALANDUR,165,447000,Attending the BT Patch work for Flood Damaged Road At Mullai street and Kurinji street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21515,Roads,Completed,NM-ALANDUR,165,877000,Attending the BT Patch work for Flood Damaged Road At Thamarai street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21519,Roads,Completed,NM-ALANDUR,165,447000,Attending the BT Patch work for Flood Damaged Road At Chidambaranar street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21520,Roads,Completed,NM-ALANDUR,165,143000,Attending the BT Patch work for Flood Damaged Road At Patel street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21526,Roads,Completed,NM-ALANDUR,165,334000,"Attending the BT Patch work for Flood Damaged Road At Lakshmi nagar 1st cross street,Kurinji street and Thazhambu street in Division 165 Unit 37 Zone 12",Own Sources,12,2015-16,2016-17 NM/2015-16/21527,Roads,Completed,NM-ALANDUR,165,334000,Attending the BT Patch work for Flood Damaged Road At Lakshmi nagar 2nd cross street and Balaji nagar 5th street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21528,Roads,Completed,NM-ALANDUR,165,460000,Attending the BT Patch work for Flood Damaged Road At Palandiamman koil street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21530,Roads,Completed,NM-ALANDUR,165,430000,Attending the BT Patch work for Flood Damaged Road AtAmman koil street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21531,Roads,Completed,NM-ALANDUR,165,143000,Attending the BT Patch work for Flood Damaged Road At Saraswathi nagar 2nd street and araswathi nagar main road in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21532,Roads,Completed,NM-ALANDUR,165,525000,Attending the BT Patch work for Flood Damaged Road At Income tax colony 1st street and Income tax colony 4th street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21535,Roads,Completed,NM-ALANDUR,165,334000,Attending the BT Patch work for Flood Damaged Road At Balaji angar 13th street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21540,Roads,Completed,NM-ALANDUR,165,334000,Attending the BT Patch work for Flood Damaged Road At Indra nagar 2nd street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/21692,Roads,Completed,NM-ALANDUR,162,645000,"Attending patch work Thillaiganga Nagar 8th street in Dn-162, U-36, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2172,Buildings,Completed,NM-ALANDUR,157,350000,"RELAYING AND STRENGTHING OF CC ROAD AT RIVER VIEW COLONY 4TH MAIN ROAD EXTENSION IN DIV-157,UNIT-35, ZONE-12",Own Sources,12,2015-16,2017-18 NM/2015-16/21810,Roads,Completed,NM-ALANDUR,166,237000,"ATTENDING PATCH WORK AT POONTHOTTAM 3RD STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21819,Roads,Completed,NM-ALANDUR,167,190000,"ATTENDING PATCH WORK AT NEW VINAYAGAR KOIL STREET 1ST LANE IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21829,Roads,Completed,NM-ALANDUR,167,536000,"ATTENDING PATCH WORK AT NANGANALLUR 39TH STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21831,Roads,Completed,NM-ALANDUR,167,357000,"ATTENDING PATCH WORK AT NANGANALLUR 6TH MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21833,Roads,Completed,NM-ALANDUR,167,178000,"ATTENDING PATCH WORK AT LAKSHMI NAGAR 6TH STREET 3RD STAGE IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21836,Roads,Completed,NM-ALANDUR,167,536000,"ATTENDING PATCH WORK AT NANGANALLUR 43RD STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/21837,Roads,Completed,NM-ALANDUR,167,208000,"ATTENDING PATCH WORK AT LAKSHMI NAGAR 2ND STREET 3RD STAGE IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/22472,Road Cut,Completed,NM-ALANDUR,157,72000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DHARMARAJAPURAM MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22473,Road Cut,Completed,NM-ALANDUR,157,72000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DHARMARAJAPURAM 1ST STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22474,Road Cut,Completed,NM-ALANDUR,157,186000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PILLAIYAR KOIL STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22478,Road Cut,Completed,NM-ALANDUR,157,89000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MUTHALAMMAN KOIL STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22479,Road Cut,Completed,NM-ALANDUR,157,170000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT GIRI GORI NAGERMUTHALAMMAN KOIL STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22480,Road Cut,Completed,NM-ALANDUR,157,66000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT GIRI GORI NAGER 1ST STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22481,Road Cut,Completed,NM-ALANDUR,157,101000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT GIRI GORI NAGER 2ND STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22482,Road Cut,Completed,NM-ALANDUR,157,247000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT CRR PURAM PHASE -3 IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22484,Road Cut,Completed,NM-ALANDUR,157,76000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYA COLONY, THULUGATHAMMAN KOIL IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22485,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYA COLONY, EAST STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22486,Road Cut,Completed,NM-ALANDUR,157,237000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYA COLONY, BAJANAI KOIL STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22487,Road Cut,Completed,NM-ALANDUR,157,303000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KRISHNA NAGER , PERIYAR SALAI IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22489,Road Cut,Completed,NM-ALANDUR,157,95000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT METTU COLONY TANK STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22490,Road Cut,Completed,NM-ALANDUR,157,161000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PERIYA PALAYATHAMMAN KOIL STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22491,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER SALAI IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22492,Road Cut,Completed,NM-ALANDUR,157,66000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT METTU COLONY BAJANAI KOIL STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22494,Road Cut,Completed,NM-ALANDUR,157,66000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT METTU COLONY BAJANAI KOIL 2ND STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22495,Road Cut,Completed,NM-ALANDUR,157,67000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT METTU COLONY NEHRU STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22497,Road Cut,Completed,NM-ALANDUR,157,48000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT METTU COLONY LINK ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22498,Road Cut,Completed,NM-ALANDUR,157,123000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT METTU COLONY PERIYA PALAYATHAMMAN KOIL 1ST STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22499,Road Cut,Completed,NM-ALANDUR,157,114000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT METTU COLONY PERIYA PALAYATHAMMAN KOIL 2ND STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22500,Road Cut,Completed,NM-ALANDUR,157,66000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KAMARAJAR SALAI IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22501,Road Cut,Completed,NM-ALANDUR,157,162000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER 1ST MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22502,Road Cut,Completed,NM-ALANDUR,157,38000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER 1ST MAIN ROAD 1ST CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22503,Road Cut,Completed,NM-ALANDUR,157,48000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER 1ST MAIN ROAD 2ND CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22504,Road Cut,Completed,NM-ALANDUR,157,29000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER 1ST MAIN ROAD 3RD CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22506,Road Cut,Completed,NM-ALANDUR,157,105000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER RIVER VIEW COLONY LINK ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22507,Road Cut,Completed,NM-ALANDUR,157,180000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER CHURCH STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22508,Road Cut,Completed,NM-ALANDUR,157,152000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT DR.AMBEDKAR NAGER CHURCH ROAD EXTEN IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22509,Road Cut,Completed,NM-ALANDUR,157,85000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MUTHI ENCLAVE MAIN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22510,Road Cut,Completed,NM-ALANDUR,157,19000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT MUTHI ENCLAVE 1ST CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22511,Road Cut,Completed,NM-ALANDUR,157,76000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT VELAN NAGER IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22512,Road Cut,Completed,NM-ALANDUR,157,190000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KRISHNA ENCLAVE IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22513,Road Cut,Completed,NM-ALANDUR,157,48000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT KRISHNA ENCLAVE CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22514,Road Cut,Completed,NM-ALANDUR,157,266000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PARTHASARATHY NAGER ASTALAKSHMI IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22515,Road Cut,Completed,NM-ALANDUR,157,66000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT PARTHASARATHY NAGER IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22558,Road Cut,Completed,NM-ALANDUR,157,275000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BALARAMAN GARDEN ROAD IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22559,Road Cut,Completed,NM-ALANDUR,157,38000,"ATTENDING ROAD CUT RESTORATION MADE BY CMWSSB AT BALARAMAN NAGER 1ST CROSS STREET IN DIV-157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22565,Roads,Completed,NM-ALANDUR,161,1235000,"FORMING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT JEEVAN NAGAR 2ND MAIN ROAD IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22597,Roads,Completed,NM-ALANDUR,158,455000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY MAIN ROAD IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22603,Roads,Completed,NM-ALANDUR,158,478000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY 3RD STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22604,Roads,Completed,NM-ALANDUR,158,710000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY 4TH STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22605,Roads,Completed,NM-ALANDUR,158,730000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY 5TH STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22606,Roads,Completed,NM-ALANDUR,158,556000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY 2ND STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22607,Roads,Completed,NM-ALANDUR,158,661000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY 1ST STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22608,Roads,Completed,NM-ALANDUR,158,528000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY 9TH STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22609,Roads,Completed,NM-ALANDUR,158,551000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY 6TH STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22610,Roads,Completed,NM-ALANDUR,158,127000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANAPATHYPURAM COLONY - WOODGREEK JOINT ROAD IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22611,Roads,Completed,NM-ALANDUR,158,1110000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT MANGO GROOVE STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22612,Roads,Completed,NM-ALANDUR,158,1550000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT NANDAMBAKKAM BURIAL GROUND ROAD IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22614,Roads,Completed,NM-ALANDUR,158,1805000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT PADMINI GARDEN IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22615,Roads,Completed,NM-ALANDUR,158,765000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT GANGAIAMMAN KOIL STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22618,Roads,Completed,NM-ALANDUR,161,789000,"LAYING CC ROAD USING RMC 3O CONCRETE AT RAJA STREET 1ST LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22619,Roads,Completed,NM-ALANDUR,161,501000,"LAYING CC ROAD USING RMC 3O CONCRETE AT RAJA STREET 2ND LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22620,Roads,Completed,NM-ALANDUR,161,595000,"LAYING CC ROAD USING RMC 3O CONCRETE AT RAJA STREET 3RD LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22621,Roads,Completed,NM-ALANDUR,161,192000,"LAYING CC ROAD USING RMC 3O CONCRETE AT RAJA STREET 4TH LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22622,Roads,Completed,NM-ALANDUR,161,260000,"LAYING CC ROAD USING RMC 3O CONCRETE AT RAJA STREET 5TH LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22623,Roads,Completed,NM-ALANDUR,158,2358000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT KARUMARIAMMAN KOIL STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22624,Roads,Completed,NM-ALANDUR,161,283000,"LAYING CC ROAD USING RMC 3O CONCRETE AT RAJA STREET 6TH LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22625,Roads,Completed,NM-ALANDUR,161,235000,"LAYING CC ROAD USING RMC 3O CONCRETE AT MASTHAN GORI LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22626,Roads,Completed,NM-ALANDUR,161,195000,"LAYING CC ROAD USING RMC 3O CONCRETE AT GOOD SHED 3RD LANE IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22627,Roads,Completed,NM-ALANDUR,161,2749000,"LAYING CC ROAD USING RMC 3O CONCRETE AT VELACHERY ROAD IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22628,Roads,Completed,NM-ALANDUR,158,722000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT GANAPATHYPURAM COLONY 7TH STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22630,Roads,Completed,NM-ALANDUR,158,1528000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT HARIKRISHNA COLONY IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22632,Roads,Completed,NM-ALANDUR,158,645000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT SWAMY COLONY IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22633,Roads,Completed,NM-ALANDUR,158,1673000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT ESWARAN KOIL STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22634,Roads,Completed,NM-ALANDUR,158,1369000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT WEST LAKEVIEW STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22635,Roads,Completed,NM-ALANDUR,158,2466000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT ARCOTPET STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22636,Roads,Completed,NM-ALANDUR,158,2058000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT WEST MADA STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22637,Roads,Completed,NM-ALANDUR,158,937000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT NORTH MADA STREET IN DIV-158,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22639,Roads,Completed,NM-ALANDUR,160,481000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT MADHAVAPURAM NORTH STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22640,Roads,Completed,NM-ALANDUR,160,2787000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT LUSKAR STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22650,Roads,Completed,NM-ALANDUR,161,2357000,"LAYING CC ROAD USING RMC 3O CONCRETE AT NORTH RAJA STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22651,Roads,Completed,NM-ALANDUR,161,2357000,"LAYING CC ROAD USING RMC 3O CONCRETE AT SOUTH RAJA STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22654,Roads,Completed,NM-ALANDUR,161,1444000,"FORMING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT JEEVAN NAGAR MAIN ROAD IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22655,Roads,Completed,NM-ALANDUR,161,775000,"FORMING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT VEDAGIRI STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22656,Roads,Completed,NM-ALANDUR,161,269000,"FORMING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 2ND CROSS STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22657,Roads,Completed,NM-ALANDUR,161,367000,"FORMING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY 3RD STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22658,Roads,Completed,NM-ALANDUR,161,156000,"FORMING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT LYOUDS AVENUE 2ND STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22659,Roads,Completed,NM-ALANDUR,161,309000,"FORMING AND RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT THIRUVALLUVAR 1ST STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/22737,Roads,Completed,NM-ALANDUR,160,363000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT MADHAVAPURAM SOUTH STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22738,Roads,Completed,NM-ALANDUR,160,702000,"RELAYING AND STRENGTHENING BT ROAD BY USING PAVER FINISHER AT MADHAVAPURAM WEST STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22740,Roads,Completed,NM-ALANDUR,160,1262000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT KOTHAVAL STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22741,Roads,Completed,NM-ALANDUR,160,732000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT MADUVANKARAI 1ST STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22742,Roads,Completed,NM-ALANDUR,160,1154000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT KADUMBADI AMMAN KOIL STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22743,Roads,Completed,NM-ALANDUR,160,1154000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT HUSSAIN SUBEDHAR STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22744,Roads,Completed,NM-ALANDUR,160,382000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT ESWARAN KOIL LANE IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22745,Roads,Completed,NM-ALANDUR,160,2609000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT VEMBULIAMMAN KOIL STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22746,Roads,Completed,NM-ALANDUR,160,449000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT PERIYAPALAYATHAMMAN STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22747,Roads,Completed,NM-ALANDUR,160,698000,"RELAYING AND STRENGTHENING CC ROAD BY USING RMC-30 AT MADUVANKARAI 5TH STREET IN DIV-160,U-35,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/22839,Culvert,Completed,NM-ALANDUR,164,326000,"Providing Box culvert at nanganallur 21st street for nanganallur 4th main road crossing purpose in Division-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/22842,Culvert,Completed,NM-ALANDUR,164,290000,"Providing Box culvert at nanganallur 37th street extn for nanganallur 2nd main road crossing purpose in Division-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/22861,Culvert,Completed,NM-ALANDUR,162,250000,"Providing box culvert at thillaiganga nagar 28th street for thillaiganga nagar 3rd main road crossing purpose in division-162, unit-36, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23389,Roads,Completed,NM-ALANDUR,162,325000,"Attending patch work at thillaiganga nagar 31st street extn in division-162, unit-36, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23790,Buildings,Completed,NM-ALANDUR,164,600000,"Improvement works to division office building at krishnasamy street in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23851,Storm Water Drain,Completed,NM-ALANDUR,162,890000,"Improvement works to existing strom water drain at thillaiganga nagar 25th street in division-162, unit-36, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23856,Storm Water Drain,Completed,NM-ALANDUR,162,995000,"Improvement works to existing strom water drain at Bharathiyar 2nd street in division-162, unit-36, zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/23874,Buildings,Completed,NM-ALANDUR,156,373000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SS GREEN PARK AT MADHANANDHAPURAM MAIN ROAD IN DN.156, U - 35, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23875,Buildings,Completed,NM-ALANDUR,156,280000,"REPAIRS AND IMPROVEMENTS TO CORPORATION PARK AT KUMUDHAM NAGAR IN DN.156, U- 35, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23876,Buildings,Completed,NM-ALANDUR,156,104000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENTS TO CORPORATION PUBLIC CONVENIENCE AT MUGALIVAKKAM TO MANAPAKKAM LINK ROAD IN DN.156, U - 35, Z -12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23877,Buildings,Completed,NM-ALANDUR,156,104000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENTS TO PUBLIC CONVENIENCE AT MADHANANDHAPURAM MAIN ROAD IN DN.156, U - 35, Z -12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23886,Buildings,Completed,NM-ALANDUR,156,57000,"CONSTRUCTION OF INLET CHAMBERS AT RANIJI NAGAR , MADHANANDHAPURAM IN DN.156, U - 35, Z -12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23990,Roads,Completed,NM-ALANDUR,156,183000,"PROVIDING AND LAYING GSB & WMM AT ALAMELU STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23991,Roads,Completed,NM-ALANDUR,156,220000,"PROVIDING AND LAYING GSB & WMM AT ANDAL AVENUE 1ST STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23993,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT ANDAL AVENUE 2ND STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23994,Roads,Completed,NM-ALANDUR,156,855000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER MAIN ROAD IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23995,Roads,Completed,NM-ALANDUR,156,428000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER KUMARASAMY STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23996,Roads,Completed,NM-ALANDUR,156,880000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER DEVARAJ STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23997,Roads,Completed,NM-ALANDUR,156,733000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER MAIN RAGUPATHY STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23998,Roads,Completed,NM-ALANDUR,156,391000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER MAIN SARASWATHI Extn IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/23999,Roads,Completed,NM-ALANDUR,156,440000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER MAIN SUBRAMANI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24000,Roads,Completed,NM-ALANDUR,156,880000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER KALAIMAGAL STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24001,Roads,Completed,NM-ALANDUR,156,874000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER YAMUNA STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24002,Roads,Completed,NM-ALANDUR,156,306000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER ARUNAGIRI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24003,Roads,Completed,NM-ALANDUR,156,880000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER VISWANATHAN STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24004,Roads,Completed,NM-ALANDUR,156,306000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR ARUNAGIRI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24005,Roads,Completed,NM-ALANDUR,156,183000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR GULASEKARAN STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24006,Roads,Completed,NM-ALANDUR,156,183000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR BALARAMAN STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24007,Roads,Completed,NM-ALANDUR,156,244000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR PATCHAIYAPPAN STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24008,Roads,Completed,NM-ALANDUR,156,880000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR NATHAMUNAI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24009,Roads,Completed,NM-ALANDUR,156,195000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR PAPATHIYAMAML STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24010,Roads,Completed,NM-ALANDUR,156,183000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR GOVINDHARAJ STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24011,Roads,Completed,NM-ALANDUR,156,733000,"PROVIDING AND LAYING GSB & WMM AT MURUGESANAR STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24012,Roads,Completed,NM-ALANDUR,156,366000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR SUBRAMANI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24013,Roads,Completed,NM-ALANDUR,156,122000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR MANICKKAMI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24014,Roads,Completed,NM-ALANDUR,156,366000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR MARAGATHAM STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24015,Roads,Completed,NM-ALANDUR,156,855000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR MUTHAMMAL STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24016,Roads,Completed,NM-ALANDUR,156,880000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR NATARAJ STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24017,Roads,Completed,NM-ALANDUR,156,195000,"PROVIDING AND LAYING GSB & WMM AT BHARATHAMADHA STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24018,Roads,Completed,NM-ALANDUR,156,659000,"PROVIDING AND LAYING GSB & WMM AT BLACKBERRY STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24019,Roads,Completed,NM-ALANDUR,156,806000,"PROVIDING AND LAYING GSB & WMM AT ORCHID STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24020,Roads,Completed,NM-ALANDUR,156,306000,"PROVIDING AND LAYING GSB & WMM AT DAFFODIL STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24021,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT SUNFLOWER STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24022,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT TULIP STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24023,Roads,Completed,NM-ALANDUR,156,440000,"PROVIDING AND LAYING GSB & WMM AT ASTROS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24024,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT JASMINE STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24025,Roads,Completed,NM-ALANDUR,156,366000,"PROVIDING AND LAYING GSB & WMM AT MARRY GOLD STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24026,Roads,Completed,NM-ALANDUR,156,840000,"PROVIDING AND LAYING GSB & WMM AT LAVENDER STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24027,Roads,Completed,NM-ALANDUR,156,806000,"PROVIDING AND LAYING GSB & WMM AT BLOOMING GARDEN MAIN ROAD IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24028,Roads,Completed,NM-ALANDUR,156,611000,"PROVIDING AND LAYING GSB & WMM AT SAROJINI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24029,Roads,Completed,NM-ALANDUR,156,244000,"PROVIDING AND LAYING GSB & WMM AT RAMAMURTHY AVE.SUBULAKSHMI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24044,Roads,Completed,NM-ALANDUR,156,874000,"PROVIDING AND LAYING GSB & WMM AT SUBBAIYA NAGAR MAIN ROAD IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24059,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT SUBHASRI NAGAR 6TH STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24060,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT SUBHASRI NAGAR 7TH STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24061,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT SUBHASRI NAGAR 9TH STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24062,Roads,Completed,NM-ALANDUR,156,366000,"PROVIDING AND LAYING GSB & WMM AT SUBHASRI NAGAR 10TH STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24074,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT SHANMUGA NAGAR KAMBER STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24075,Roads,Completed,NM-ALANDUR,156,440000,"PROVIDING AND LAYING GSB & WMM AT SHANMUGA NAGAR BHARATHIDASAN STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24076,Roads,Completed,NM-ALANDUR,156,440000,"PROVIDING AND LAYING GSB & WMM AT SHANMUGA NAGAR BHARATHIYAR STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24077,Roads,Completed,NM-ALANDUR,156,153000,"PROVIDING AND LAYING GSB & WMM AT SHANMUGA NAGAR KANNADHASAN STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24085,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SANTOSH NAGAR EXTN-VALLI IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24086,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SANTOSH NAGAR EXTN-BHARATHIYAR STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24087,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SANTOSH NAGAR EXTN-VAIRAMUTHU STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24088,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SANTOSH NAGAR EXTN-KANNADASAN STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24093,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SANTHOSH NAGAR EXTN-PATTUKOTTAI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24094,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SANTHOSH NAGAR EXTN-MARUTHA KASI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24099,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SUBAIYANAGAR VENKADACHALAM STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/2412,Road Cut,Completed,NM-ALANDUR,162,936000,"ROAD CUT RESTORATION AT VARIOUS STREET IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24165,Roads,Completed,NM-ALANDUR,156,440000,"PROVIDING AND LAYING GSB & WMM AT SANTHOSH NAGAR IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24167,Roads,Completed,NM-ALANDUR,156,330000,"PROVIDING AND LAYING GSB & WMM AT SANTHOSH NAGAR 1ST CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24169,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SANTHOSH NAGAR 2ND CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24171,Roads,Completed,NM-ALANDUR,156,440000,"PROVIDING AND LAYING GSB & WMM AT SANTHOSH NAGAR EXTN IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24173,Roads,Completed,NM-ALANDUR,156,366000,"PROVIDING AND LAYING GSB & WMM AT SANTHOSH NAGAR EXTN 2ND CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24186,Roads,Completed,NM-ALANDUR,156,366000,"PROVIDING AND LAYING GSB & WMM AT SUBHASHREE NAGAR EXTN-4 IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24188,Roads,Completed,NM-ALANDUR,156,183000,"PROVIDING AND LAYING GSB & WMM AT SUBHASHREE NAGAR EXTN-4,2ND MAIN ROAD IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24189,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SUBHASHREE NAGAR EXTN-2,1ST CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24190,Roads,Completed,NM-ALANDUR,156,220000,"PROVIDING AND LAYING GSB & WMM AT SUBHASHREE NAGAR EXTN-2,2ND CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24192,Roads,Completed,NM-ALANDUR,156,220000,"PROVIDING AND LAYING GSB & WMM AT SUBHASHREE NAGAR EXTN-3,1ST CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24193,Roads,Completed,NM-ALANDUR,156,220000,"PROVIDING AND LAYING GSB & WMM AT SUBHASHREE NAGAR EXTN-3,2ND CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24194,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT SUBHASHREE NAGAR EXTN-3,3RD CROSS STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24217,Roads,Completed,NM-ALANDUR,156,550000,"PROVIDING AND LAYING GSB & WMM AT SUBSRI NAGAR EXTN 2-4 MAIN ROAD IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24219,Roads,Completed,NM-ALANDUR,156,245000,"PROVIDING AND LAYING GSB & WMM AT SUBSRI NAGAR EXTN 2-3 MAIN ROAD IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24298,Storm Water Drain,Completed,NM-ALANDUR,165,668000,IMPROVEMENT WORKS TO SIDE DRAIN AT SOUTH SECTOR 2ND STREET IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2015-16,2016-17 NM/2015-16/24323,Storm Water Drain,Completed,NM-ALANDUR,162,747000,"IMPROVEMENT WORKS TO SIDE DRAIN AT THILLAIGANGA NAGAR 29TH STREET IN DN-162, UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/24327,Buildings,Completed,NM-ALANDUR,162,188000,"PROVIDING PLATFORM AND STAINLESS STEEL HAND RAILS FOR SSS TOILET AT NOBLE STREET IN DN-162,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/24333,Roads,Completed,NM-ALANDUR,156,855000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER EXT IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24334,Roads,Completed,NM-ALANDUR,156,880000,"PROVIDING AND LAYING GSB & WMM AT VGN LAKSHMI NAGAER MAIN SARASWATHI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24335,Roads,Completed,NM-ALANDUR,156,293000,"PROVIDING AND LAYING GSB & WMM AT THIRUVALLUVAR NAGAR NATHAMUNAI STREET EXTN IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24336,Roads,Completed,NM-ALANDUR,156,369000,"PROVIDING AND LAYING GSB & WMM AT LAVENDER STREET EXTN IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24337,Roads,Completed,NM-ALANDUR,156,318000,"PROVIDING AND LAYING GSB & WMM AT SUBBAIYA NAGAR MAIN ROAD EXTN IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24351,Storm Water Drain,Completed,NM-ALANDUR,165,793000,IMPROVEMENT WORKS TO SIDE DRAIN AT BHAVANI STREET IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2015-16,2016-17 NM/2015-16/24353,Storm Water Drain,Completed,NM-ALANDUR,165,729000,"Improvement works to side drain at Godhavari street (From Kaveri street to Thamirabarani street) west side in Division-165, Unit-37,Zone-12",Own Sources,12,2015-16,2017-18 NM/2015-16/24354,Storm Water Drain,Completed,NM-ALANDUR,165,902000,IMPROVEMENT WORKS TO SIDE DRAIN AT THAMIRABARANI STREET IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2015-16,2017-18 NM/2015-16/24358,Storm Water Drain,Completed,NM-ALANDUR,165,766000,IMPROVEMENT WORKS TO SIDE DRAIN AT THIRUVALLUVAR STREET (Thiruvalluvar cross lane to Valmigi street) STREET Counsillor fund 2016-17)IN DIV 165 UNIT 37 ZONE 12,Own Sources,12,2015-16,2018-19 NM/2015-16/24359,Storm Water Drain,Completed,NM-ALANDUR,165,279000,IMPROVEMENT WORKS TO SIDE DRAIN AT VALMIGI STREET WEST ( Counsillor fund 2016-17) IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2015-16,2017-18 NM/2015-16/24367,Storm Water Drain,Completed,NM-ALANDUR,165,986000,IMPROVEMENT WORKS TO SIDE DRAIN AT SOUTH SECTOR 4TH STREET IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2015-16,2017-18 NM/2015-16/24371,Storm Water Drain,Completed,NM-ALANDUR,165,977000,IMPROVEMENT WORKS TO SIDE DRAIN AT BHARADHIDASAN STREET IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2015-16,2016-17 NM/2015-16/24386,Storm Water Drain,Completed,NM-ALANDUR,162,985000,"Improvement works to existing storm water drain at Bharathiyar 2nd street extn in division-162, unit-36, zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/24399,Culvert,Completed,NM-ALANDUR,162,270000,"Providing box culvert at Bharathiyar street extn for Bhirandhavan nagar 1st street cross purpose in division-162, unit-36, zone-12",Own Sources,12,2015-16,2018-19 NM/2015-16/24428,Parks,Completed,NM-ALANDUR,165,998000,"Improvement works to Balaji nagar park in Dn-165, U-37, Zn-12(Councillor ward Development fund)",Own Sources,12,2015-16,2017-18 NM/2015-16/24435,Culvert,Completed,NM-ALANDUR,162,350000,"Providing box culvert at Thilai ganga Nagar 25th street for Thilai ganga 3rd main road crossing purpose in division-162,unit-36,zone-12",Own Sources,12,2015-16,2017-18 NM/2015-16/24563,Parks,Completed,NM-ALANDUR,165,998000,"Improvement works to Lakshmi nagar park in Dn-165, U-37, Zn-12(Councillor ward Development fund)",Own Sources,12,2015-16,2017-18 NM/2015-16/24746,Buildings,Completed,NM-ALANDUR,156,350000,"SUPPLYING AND FIXING OF STAINLESS STEEL SIGNAGE NAME BOARDS FOR E - SEVAI CENTRES IN VARIOUS DIVISIONS FROM DN.156 TO DN.161 (6 DIVISIONS) , U - 35, ZONE - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/24806,Storm Water Drain,Completed,NM-ALANDUR,166,292000,"ADDITIONAL IMPROVEMENT TO THE EXISTING VETERNARY CLINIC AT NEHRU NEDUNCHALAI, IN DN 166, UNIT 37, ZONE 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/2499,Parks,Completed,NM-ALANDUR,161,945000,"Improvement Works To T.N.G.O Colony Park With Stainless Steel Childrens Play Apparatus in Dn-161,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2507,Parks,Completed,NM-ALANDUR,167,560000,"Providing greenery arrangements and herbal plantation at Independence day Park in Dn 167, U 37,Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/25207,Roads,Completed,NM-ALANDUR,165,293000,"Laying of Wet MIx Mecadam at Income tax colony 4th street in Dn-165, U-37, Zn-12",Own Sources,12,2015-16,2017-18 NM/2015-16/25681,Storm Water Drain,Completed,NM-ALANDUR,167,645000,"IMPROVEMENT TO THE EXISTING SWD AT M.G.R ROAD (FROM HINDU COLONY 4TH CROSS STREET TO 5TH CROSS STREET) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/25785,Roads,Completed,NM-ALANDUR,167,772000,"LAYING INTERLOCKING PAVER BLOCKS FOR ROAD WIDENING AREA AT SRIVIDHYA NAGAR MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/25799,Parks,Completed,NM-ALANDUR,165,978000,"IMPROVEMENT WORKS AT SOUTH SECTOR 2ND STREET AND KUNDRAKUDI NAGAR 4TH STREET PARK IN DIV- 165, UNIT-37, ZONE 12",Own Sources,12,2015-16,2017-18 NM/2015-16/25861,Roads,Completed,NM-ALANDUR,167,829000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/25864,Roads,Completed,NM-ALANDUR,167,979000,"PROVIDING RETRO REFLECTIVE STREET NAME BOARD AT VARIOUS STREET IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/2609,Storm Water Drain,Completed,NM-ALANDUR,162,500000,"IMPROVEMENTS WORKS OF EXISTING SWD (COUNCIOLR FUND ) AT KANNAN COLONY 1ST STREET IN DIV-162,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2610,Storm Water Drain,Completed,NM-ALANDUR,162,347000,"IMPROVEMENTS WORKS OF EXISTING SWD ( COUNCIOLR FUND ) AT KANNAN COLONY 4TH STREET IN DIV-162,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2612,Storm Water Drain,Completed,NM-ALANDUR,162,611000,"IMPROVEMENTS WORKS OF EXISTING SWD ( COUNCIOLR FUND ) AT KANNAN COLONY 5TH STREET IN DIV-162,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2613,Storm Water Drain,Completed,NM-ALANDUR,162,500000,"IMPROVEMENTS WORKS OF EXISTING SWD (COUNCIOLR FUND ) AT KANNAN COLONY 2ND STREET IN DIV-162,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2614,Storm Water Drain,Completed,NM-ALANDUR,162,480000,"IMPROVEMENTS WORKS OF EXISTING SWD ( COUNCIOLR FUND ) AT KANNAN COLONY 3RD STREET IN DIV-162,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2618,Storm Water Drain,Completed,NM-ALANDUR,162,497000,"IMPROVEMENTS WORKS OF EXISTING SWD (SOUTH SIDE) (COUNCIOLR FUND) AT MARZON 6TH STREET IN DIV-162,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26272,Buildings,Completed,NM-ALANDUR,164,525000,"Maintenance works to CPS (Chennai primary school building and toilet room building) at vembuli amman koil street in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/26279,Buildings,Completed,NM-ALANDUR,162,350000,"SUPPLYING AND FIXING OF STAINLESS STEEL SIGNAGE NAME BOARD FOR E - SEVAI CENTRES IN VARIOUS DIVISIONS FROM DN.162 TO 167, U - 36, ZONE - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/26391,Roads,Completed,NM-ALANDUR,166,772000,"PROVIDING RETRO REFLECTIVE DIGITAL NAME BOARD AT CORPORATION BUILDINGS AND ROAD SIGNAGE BOARD IN DN 166, U 37, Z 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/26425,Culvert,Completed,NM-ALANDUR,166,728000,"IMPROVEMENT WORKS TO COMMUNITY HALL BUILDING AT NEHRU COLONY MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/26570,Roads,Completed,NM-ALANDUR,164,115000,"Maintenance works to inspection chamber at Nehru colony main road in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/26660,Roads,Completed,NM-ALANDUR,166,808000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/26766,Roads,Completed,NM-ALANDUR,160,134000,"ATTENDING OF PATCH WORK AT NATHAM SUBEDHAR STREET IN DN-160,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26767,Roads,Completed,NM-ALANDUR,160,839000,"ATTENDING OF PATCH WORK AT EKAMBARA DHABEDAR STREET IN DN-160,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26768,Roads,Completed,NM-ALANDUR,160,671000,"ATTENDING OF PATCH WORK AT MUKTHAMIJI STREET IN DN-160,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26770,Roads,Completed,NM-ALANDUR,160,402000,"ATTENDING OF PATCH WORK AT SANNIYASI SUBEDHARI STREET IN DN-160,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26882,Buildings,Completed,NM-ALANDUR,163,223000,"IMPROVEMENT WORKS TO (NNMP) BUILDING AT PARAMESHWARI NAGAR 3RD STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26900,Buildings,Completed,NM-ALANDUR,163,103000,"IMPROVEMENT WORKS TO(NNMP) BUILDING AT PILLAIYARKOIL STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26901,Buildings,Completed,NM-ALANDUR,163,134000,"IMPROVEMENT WORKS TO (NNMP) BUILDING AT MANNADIAMMAN KOIL STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26903,Buildings,Completed,NM-ALANDUR,163,70000,"IMPROVEMENT WORKS TO PUBLIC CONVENIENCES AT MANNADIAMMAN KOIL STREET IN DN163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26904,Buildings,Completed,NM-ALANDUR,163,75000,"IMPROVEMENT WORKS TO PUBLIC CONVENIENCES AT BALAKRISHNAPURAM 1ST STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26905,Buildings,Completed,NM-ALANDUR,163,114000,"IMPROVEMENT WORKS TO IMPROVEMENT WORKS TO PUBLIC CONVENIENCES AT BALAKRISHNAPURAM ( N.G.O COLOUNY) STREET IN DN163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26906,Storm Water Drain,Completed,NM-ALANDUR,163,310000,"DESILDING OF CANAL CLEANING ADAMBAKKAM CANAL(FROM ADAMBAKKAM TO VELLACHERY) BY ENGAGING MACHINERIES IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26909,Storm Water Drain,Completed,NM-ALANDUR,163,869000,"CONSTRUCTION OF IMBROVEMENTE WORKS TO SIDE DRAIN AT PARAMESHWARINAR MAIN ROAD (JN OF RAMAKRISHNAPURAM 1ST STREET) STREET IN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26910,Electrical,Completed,NM-ALANDUR,163,500000,"ELECTRICAL ARRANGEMENT AND IMPROVEMENT WORKS TO SHANTHI NAGAR 4TH STREET PARK IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26911,Storm Water Drain,Completed,NM-ALANDUR,163,66000,"IMBROVEMENTE WORKS TO SIDE DRAIN AT SHANTHI NAGAR 3RD (JN OF SURENTHRANAGAR 6TH&3 RD CROSS STRRET) STREET IN-163,U-36,Z-12",Own Sources,12,2015-16,2017-18 NM/2015-16/26912,Roads,Completed,NM-ALANDUR,163,329000,"RESTORATION OF ROAD CUT AT PARTHASARATHY NAGAR 2ND STREET (ROAD CUT NEAD BY TNEB) IN DN163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26914,Roads,Completed,NM-ALANDUR,163,945000,"ATTENDING PATCH WORK AT PARTHASARATHY 8TH STREET ,SANNATHI STREET RAMAKRISHNAPURAM 1ST,2ND AND 3RD IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26915,Culvert,Completed,NM-ALANDUR,163,420000,"CONSTRUCTION OF RCC CULVERTS AT EARIKKARAI STREET IN DN-163,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26916,Culvert,Completed,NM-ALANDUR,163,428000,"CONSTRUCTION OF RCC CULVERTS AT BALAKRISHNAPURAM 6TH STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2018-19 NM/2015-16/26917,Culvert,Completed,NM-ALANDUR,163,441000,"CONSTRUCTION OF RCC CULVERTS AT SHANTHI NAGAR 7TH STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26918,Culvert,Completed,NM-ALANDUR,163,426000,"CONSTRUCTION OF RCC CULVERTS AT SHANTHI NAGAR 9TH STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/26919,Roads,Completed,NM-ALANDUR,163,988000,"LAYING OF CEMENT CONCRETE ROAD AT MOSTHAN GORI (LANE) STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27067,Buildings,Completed,NM-ALANDUR,164,530000,"IMPROVEMET WORKS TO HEALTH CENTER AT NEW COLONY IN DIVISION-164, UNIT-37, ZONE-12.",Deposit Works,12,2015-16,2016-17 NM/2015-16/27075,Buildings,Completed,NM-ALANDUR,164,990000,"CONSTRUCTION OF HEALTH CENTER FIRST FLOOR AT NEW COLONY IN DIVISION-164, UNIT-37, ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/27084,Parks,Completed,NM-ALANDUR,156,998000,"Providing Stainless Steel Hand Rail to Footpath and FRP Benches at Sabari Nagar 2nd Main Road park in Dn-156,U-35,Zn-12(Councillor Scheme)",Own Sources,12,2015-16,2016-17 NM/2015-16/27086,Roads,Completed,NM-ALANDUR,156,996000,"Supplying and Fixing Stainless steel street name board at various streets in Dn-156, U-35, Zn-12(Councillor Scheme)",Own Sources,12,2015-16,2016-17 NM/2015-16/27088,Parks,Completed,NM-ALANDUR,156,997000,"Providing Stainless steel hand rail to footpath at E.V.P Rajeswari Avenue - V.N.D Sindhu Salai Park in Dn-156, U-35, Zn-12(Councillor Scheme)",Own Sources,12,2015-16,2016-17 NM/2015-16/27101,Buildings,Completed,NM-ALANDUR,163,950000,"SUPPLYING WATER,DRAINAGE,ELECTRICAL AND IMPROVEMENT WORKS TO (NUHM) AT MANNADIAMMAN KOIL STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27185,Buildings,Completed,NM-ALANDUR,163,806000,ADDITIONAL IMPROVEMENTS WORKS TO (CMS) AT KARNEELAKAR STREET IN DN-163 U/36 Z-XII,Own Sources,12,2015-16,2017-18 NM/2015-16/27194,Buildings,Completed,NM-ALANDUR,165,999000,"Construction Of Multi Purpose Hall at Muthaiyal Reddy Nagar Main road in Division-165,Unit-37,Zone-12.(Councillor Fund)",Own Sources,12,2015-16,2018-19 NM/2015-16/27216,Buildings,Completed,NM-ALANDUR,163,950000,"CONSTRUCTION OF ADDITIONAL BUILDING (FIRST FLOOR) FOR NUHM BUILDING AT MANNADIAMMAN KOIL STREET IN DN.163, U - 36, ZONE - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/27275,Roads,Completed,NM-ALANDUR,167,825000,"LAYING CEMENT CONCRETE ROAD USING M30 GRADE CONCRETE AT SRIVIDHYA NAGAR 1ST STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/27293,Storm Water Drain,Completed,NM-ALANDUR,167,646000,"IMPROVEMENT TO THE EXISTING SWD AT LAKSHMI NAGAR 7TH STREET EXTN (FROM 7TH STREET EXTN 1ST CROSS LANE TO NANGANALLUR 100 FEET ROAD) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/27318,Buildings,Completed,NM-ALANDUR,160,785000,"IMPROVEMENT WORKS TO LIC OFFICE BUILDING AT NEW STREET IN DN-160, U-35,ZN-12",Own Sources,12,2015-16,2016-17 NM/2015-16/2734,Buildings,Completed,NM-ALANDUR,162,546000,"Maintenance of COC building at various street DIV-162,U-36,Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/27475,Storm Water Drain,Completed,NM-ALANDUR,159,761000,"IMPROVEMENT EXISTING STROM WATER DRAIN AT EVR EAST STREET IN DN-159,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27476,Storm Water Drain,Completed,NM-ALANDUR,159,761000,"IMPROVEMENT EXISTING STROM WATER DRAIN AT EVR WEST STREET IN DN-159,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27477,Storm Water Drain,Completed,NM-ALANDUR,159,704000,"IMPROVEMENT EXISTING STORM WATER DRAIN AT BHARATHIYAR STREET EAST SIDE IN WARD COUNCILLOR FUND IN DN-159,U-35,ZONE-12",Own Sources,12,2015-16,2017-18 NM/2015-16/27478,Storm Water Drain,Completed,NM-ALANDUR,159,704000,"IMPROVEMENT EXISTING STROM WATER DRAIN AT BHARATHIYAR STREET WEST SIDE IN WARD COUNCILLOR FUND IN DN-159,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27485,Buildings,Completed,NM-ALANDUR,166,996000,"ADDITIONAL IMPROVEMENT TO EXISTING HEALTH CENTRE ( UNDER NUHM SCHEME) AT K.K. NAGAR MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/27573,Buildings,Completed,NM-ALANDUR,156,973000,"CONSTRUCTION OF ADDITIONAL FIRST FLOOR BUILDING IN HOSPITAL AT PADASALAI STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27585,Buildings,Completed,NM-ALANDUR,156,933000,"CONSTRUCTION OF ADDITIONAL FIRST FLOOR BUILDING ELECTRICAL WORK & STAIR CASE OF HOSPITAL AT PADASALAI STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27851,Storm Water Drain,Completed,NM-ALANDUR,162,663000,"IMPROVEMENT TO SIDE DRAIN AT THILLAI GANGA NAGAR 8TH STREET IN DN-162,U-36,Z-XII",Own Sources,12,2015-16,2017-18 NM/2015-16/27852,Buildings,Completed,NM-ALANDUR,162,186000,"MAINTANANCE WORK OF COC BULIDINGS AT VARIOUS STREET IN DN-162,U-36,Z-XII.",Own Sources,12,2015-16,2017-18 NM/2015-16/27856,Storm Water Drain,Completed,NM-ALANDUR,162,121000,"CONSTRUCTION OF GROUP BIN PLATFORM AT VARIOUS STREET IN DN-162,U-36,Z-XII",Own Sources,12,2015-16,2017-18 NM/2015-16/27882,Buildings,Completed,NM-ALANDUR,156,295000,"IMPROVEMENT TO OLD HOSPITAL BUILDING AT PADASALAI STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27914,Storm Water Drain,Completed,NM-ALANDUR,159,345000,"IMPROVEMENT EXISTING STORM WATER DRAIN AT ANNA STREET IN WARD COUNCILLOR FUND IN DN-159,U-35,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/27970,Parks,Completed,NM-ALANDUR,166,280000,"MAINTENANCE OF PARK AT GANDHI NAGAR ANNA PARK IN DN.166, U -37 , Z-12.(By employed qualified Horticulture only) period for one year",Own Sources,12,2015-16,2017-18 NM/2015-16/2814,Buildings,Completed,NM-ALANDUR,162,389000,"Construction of Indoor Game Shed at Noble 1st street .DIV-162,U-36,Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/28300,Buildings,Completed,NM-ALANDUR,164,190000,"Maintenance works to CI Office at Ellaimuthamman koil street in division-164, unit-37, zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/28989,Roads,Completed,NM-ALANDUR,163,326000,"RESTORATION OF ROAD CUT (ROAD CUT MATE BY TANGO) AT EARIKKARAI STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/29042,Storm Water Drain,Completed,NM-ALANDUR,164,558000,"Maintenance works to Storm water drain at nanganallur 23rd street and 12th street extn in Dn-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/29046,Parks,Completed,NM-ALANDUR,164,230000,"Maintenance works to Children's park (Bat mitten court) at nehru street in Dn-164, Unit-37, Zone-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/29070,Roads,Completed,NM-ALANDUR,162,984000,SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DIV.162 UNIT.36 ZONE.12.,Own Sources,12,2015-16,2016-17 NM/2015-16/29072,Roads,Completed,NM-ALANDUR,162,984000,SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DIV.162 UNIT.36 ZONE.12.,Own Sources,12,2015-16,2016-17 NM/2015-16/29312,Buildings,Completed,NM-ALANDUR,162,246000,"MAINTENANCE WORKS TO PC TOILET AT KANNAN COLONY AND MKN ROAD IN DN-162,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/29313,Buildings,Completed,NM-ALANDUR,162,259000,"Providing M30 Ramp at thilai ganga nagar 6th main road in dn-12,u-36,z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/29362,Footpath,Completed,NM-ALANDUR,162,640000,"PROVIDING AND LAYING INTER LOCKING BLOCKS AT THILLAIGANGA NAGAR 32ND STREET,THILLAIGANGA NAGAR 33RD STREET AND THILLAIGANGA NAGAR 4TH MAIN ROAD IN DN-162,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/29693,Buildings,Completed,NM-ALANDUR,162,970000,"ATTENDING ROAD PATCH AND PROVIDING SPEED BREAKER AT VARIOUS STREET IN DIVISION-162,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/29724,Footpath,Completed,NM-ALANDUR,163,292000,"REPAIR WORK TO FOOT PATH AT SHANTHI NAGAR 1ST STREET TO 5TH STREET AND PARTHASARATHY 1ST STREET TO 5TH STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/29728,Roads,Completed,NM-ALANDUR,163,294000,"LAYING CC ROAD AT SHANTHI NAGAR 1ST CROSS LANE (KRISHNAPURAM) IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/29846,Parks,Completed,NM-ALANDUR,164,254000,"ANNUAL MAINTENANCE OF PARK AT NANGANALLUR 29th STREET PARK IN DN 164,U-36,Z12 (by Employed Qualified Horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/29851,Parks,Completed,NM-ALANDUR,164,270000,"ANNUAL MAINTENANCE OF PARK AT NEHRU STREET PARK IN DN -164,U-36, Z-12 (by Employed Qualified Horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/29853,Parks,Completed,NM-ALANDUR,162,276000,"ANNUAL MAINTENANCE OF PARK AT THIRUVALLUVAR NAGAR 1ST STREET PARK IN DN 162,U-36 Z-12 (by Employed Qualified Horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/29854,Parks,Completed,NM-ALANDUR,162,268000,"MAINTENANCE OF PARK AT THILLAI GANGA NAGAR 33th STREET PARK IN DN 162,U-36 Z-12 (by Employed Qualified Horticulturist for one year)",Own Sources,12,2015-16,2017-18 NM/2015-16/29902,Parks,Completed,NM-ALANDUR,161,582000,ANNUAL MAINTENANCE WORKS AT TNGO COLONY 2ND STREET PARK IN DN 161 U 36 Z 12 ( by Employed Qualified Horticulturist for one year),Own Sources,12,2015-16,2017-18 NM/2015-16/3027,Buildings,Completed,NM-ALANDUR,166,994000,"IMPROVEMENTS WORK TO THE CONSERVANCY WORKERS LABOUR ROOM, STORE ROOM AND AMMA UNAVAGAM AT NEHRU HIGH ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/30398,Roads,Completed,NM-ALANDUR,157,465000,"RAISING THE ROAD AT CRR PURAM PHASE-III 3RD CROSS STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30432,Roads,Completed,NM-ALANDUR,157,158000,"RAISING THE ROAD AT CRR PURAM PHASE-III 2ND CROSS STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30433,Roads,Completed,NM-ALANDUR,157,160000,"RAISING THE ROAD AT CRR PURAM PHASE-III 1ST CROSS STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30434,Roads,Completed,NM-ALANDUR,157,543000,"RAISING THE ROAD AT KRISHANA NAGAR 1ST CROSS STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30435,Roads,Completed,NM-ALANDUR,157,388000,"RAISING THE ROAD AT CRR PURAM PHASE-III DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30436,Roads,Completed,NM-ALANDUR,157,310000,"RAISING THE ROAD AT DR.AMBEDKAR SALAI DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30437,Roads,Completed,NM-ALANDUR,157,310000,"RAISING THE ROAD AT VALLISWARAN KOIL STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30438,Roads,Completed,NM-ALANDUR,157,196000,"RAISING THE ROAD AT KAVIYA GARDEN PATTUROJA STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30439,Roads,Completed,NM-ALANDUR,157,273000,"RAISING THE ROAD AT KAVIYA GARDEN SEMBARUTHI STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30440,Roads,Completed,NM-ALANDUR,157,264000,"RAISING THE ROAD AT PERIYA COLONY THULUKATHAMMAN KOIL STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30441,Roads,Completed,NM-ALANDUR,157,309000,"RAISING THE ROAD AT KAVIYA GARDEN MULLAI STREET DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30442,Roads,Completed,NM-ALANDUR,157,170000,"RAISING THE ROAD AT NAVARATHNA FLATS DIV -157, U-35, Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30466,Storm Water Drain,Completed,NM-ALANDUR,162,165000,"IMPROVEMENTS TO SIDE DRAIN AT THILLAI GANGA NAGAR 20TH STREET IN DN-162,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/30483,Roads,Completed,NM-ALANDUR,167,950000,"LAYING CEMENT CONCRETE ROAD USING M30 GRADE CONCRETE AT SRIVIDHYA NAGAR MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/30793,Parks,Completed,NM-ALANDUR,163,887000,"PROVIDING TOILET,WATER SUPPLY ARRANGEMENT AND IMPROVEMENTS WORKS TO PARK AT SHANTHI NAGAR 4TH STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/30977,Roads,Completed,NM-ALANDUR,161,960000,"PROVIDING AND LAYING GSB, WMM AT VARIOUS STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/31636,Roads,Completed,NM-ALANDUR,164,992000,SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DIV.164 UNIT.37 ZONE.12.,Own Sources,12,2015-16,2016-17 NM/2015-16/31677,Roads,Completed,NM-ALANDUR,157,307000,"Raising the road at Narkudeswarar koil street in Dn-157, Unit-35,Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/31680,Roads,Completed,NM-ALANDUR,157,516000,"Raising the road at Astalakshmi Nagar 1st street in Dn-157, Unit-35,Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/31681,Roads,Completed,NM-ALANDUR,157,992000,"SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DIV.157 UNIT.35 ZONE.12.",Own Sources,12,2015-16,2016-17 NM/2015-16/31695,Buildings,Completed,NM-ALANDUR,160,977000,"Providing Aluminium partition at Zonel Office Building 2nd floor at new street in Dn-160, Unit-35, Zn-12",Own Sources,12,2015-16,2018-19 NM/2015-16/31696,Buildings,Completed,NM-ALANDUR,160,424000,"Providing Flooring and Painting works to Zonel office building 2nd floor at New street in Dn-160, U-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/31706,Storm Water Drain,Completed,NM-ALANDUR,167,667000,"CONSTRUCTION OF SIDE DRAIN AT STATE BANK COLONY MAIN ROAD (1ST STREET AND 1ST LANE) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/31752,Buildings,Completed,NM-ALANDUR,162,496000,"MAINTENANCE WORKS TO BURIAL GROUND AT KANNAN COLONY IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/31787,Buildings,Completed,NM-ALANDUR,162,190000,"CONSTRUCTION OF HANDICAP TOILET AT KANNAN COLONY IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/31903,Buildings,Completed,NM-ALANDUR,162,249000,"MAINTENANCE WORKS TO DIVISION OFFICE BUILDINGS AT THILLAII GANGA NAGAR 1ST MAIN RAOD IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/32313,Electrical,Completed,NM-ALANDUR,167,809500,Erection of 27 nos of 2 mtrs GI lamp posts with single arch bracket with with 15 watts LED fittings at Kannan Nagar 1st Cross Street and Lakshmi Nagar 4th stage Park in divisions 167 in zone XII.,Own Sources,12,2015-16,2016-17 NM/2015-16/32314,Electrical,Completed,NM-ALANDUR,167,996200,Erection of 24 nos of 2 mtrs GI lamp posts with single arch bracket with with 15 watts LED fittings and 4 nos of 6 mtrs lamp posts with 150 watts LED fittings at Kanniga Colony park and Voltas Colony 3rd street Park in divisions 167 in zone XII.,Own Sources,12,2015-16,2016-17 NM/2015-16/32317,Electrical,Completed,NM-ALANDUR,167,888700,Erection of 30 nos of 2 mtrs GI lamp posts with single arch bracket with with 15 watts LED fittings at Nanganallur 46th street and Civil Aviation Colony Park in divisions 167 in zone XII.,Own Sources,12,2015-16,2016-17 NM/2015-16/32319,Roads,Completed,NM-ALANDUR,156,194000,"PROVIDING AND LAYING GSB & WMM AT MUNUSAMY STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/32320,Roads,Completed,NM-ALANDUR,156,397000,"PROVIDING AND LAYING GSB & WMM AT SIVAKAMI STREET IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/32322,Electrical,Completed,NM-ALANDUR,167,952600,Erection of 21 nos of 2 mtrs GI Lamp posts with single arch bracket with 15 watts LED fittings and 6 nos of 6 Mtrs lamp posts with 150 watts LED fittings at Voltas Colony 1st street Park in Division 167 in Zone- XII.,Own Sources,12,2015-16,2016-17 NM/2015-16/32326,Electrical,Completed,NM-ALANDUR,167,847000,"Erection of 29 nos of 2 mtrs GI lamp posts with single arch bracket with with 15 watts LED fittings at Nehru Nedunchalai , Jain Staff Colony and Kannan Nagar 1st Main Road Park in divisions 167 in zone XII.",Own Sources,12,2015-16,2016-17 NM/2015-16/32420,Electrical,Completed,NM-ALANDUR,167,799600,Supply and fixing of 25 nos of 15 Watts LED fittings and 8 nos of 40-50 Watts LED fittings and 12 nos of 150-165 watts LED Fittings at Independence day park in Divisions 167 in zone XII.,Own Sources,12,2015-16,2017-18 NM/2015-16/32422,Electrical,Completed,NM-ALANDUR,164,533000,Erection of 11 nos of 2 mtrs GI lamp posts with single arch bracket with with 15 watts LED fittings and 6 nos of 6 mtrs lamp posts with 150 watts LED fittings at Nehru street Park in divisions 164 in zone XII.,Own Sources,12,2015-16,2016-17 NM/2015-16/3243,Buildings,Completed,NM-ALANDUR,161,996000,"IMPROVEMENTS WORKS TO OFFICERS COLONY PARK WITH STAINLESS STEEL CHILDRENS PLAY APPRATUS IN DN-161,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/32441,Parks,Completed,NM-ALANDUR,167,52000,Writing Instruction Name Board at various Parks Walls in Dn:167 Unit:36 Zone:12,Own Sources,12,2015-16,2016-17 NM/2015-16/32442,Footpath,Completed,NM-ALANDUR,167,694000,Repair works to Footpath at Nanganallur 45th street in Dn:167 Unit:36 Zone:12,Own Sources,12,2015-16,2016-17 NM/2015-16/32445,Buildings,Completed,NM-ALANDUR,167,171000,Repair works and Water supply arrangements to Corporation Buildings and Parks in Dn:167 Unit:36 Zone:12,Own Sources,12,2015-16,2016-17 NM/2015-16/32452,Buildings,Completed,NM-ALANDUR,167,54000,Construction of compound wall (partly) in Lakshmi nagar park at Nanganallur 46th street in Dn:167 U:36 Zone:12,Own Sources,12,2015-16,2016-17 NM/2015-16/32454,Buildings,Completed,NM-ALANDUR,167,970000,"MAINTAINENCE FOR BUILDING AND EXISTING PARKS AT SBI COLONY PARK, 100 FEET ROAD PARK AND 100 FEET ROAD SKATING CENTER, IN DN 167, UNIT 37, ZONE 12",Own Sources,12,2015-16,2017-18 NM/2015-16/3255,Parks,Completed,NM-ALANDUR,161,855000,"Improvement works to jeevan nagar park with Stainless Steel Childrens play apparatus in Dn-161,U-36,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/32562,Storm Water Drain,Completed,NM-ALANDUR,167,260000,"CONSTRUCTION OF CULVERT AT VISHWANATHAPURAM MAIN ROAD (JN OF RANGA COLONY AND STATE BANK COLONY MAIN ROAD) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/32598,Buildings,Completed,NM-ALANDUR,166,206000,"IMPROVEMENT AND REPAIR WORKS TO THE AMMA UNAVAGAM AND DIVISION OFFICE BUILDING AT NEHRU NEDUNCHALAI IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/32777,Storm Water Drain,Completed,NM-ALANDUR,162,264000,"IMPROVEMENTS TO SIDE DRAIN AT THILLAI GANGA NAGAR 28TH STREET IN DN-162,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/32893,Roads,Completed,NM-ALANDUR,156,124000,"PROVIDING AND LAYING GSB & WMM AT RGL PH-3 IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/32894,Roads,Completed,NM-ALANDUR,156,255000,"PROVIDING AND LAYING GSB & WMM AT KALIYAN AVENUE IN DN-156, U-35, Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/33599,Buildings,Completed,NM-ALANDUR,156,545000,"REPAIRS AND IMPROVEMENTS TO E.V.RAJESWARI PARK AT SINDHU SALAI IN DN.156, U - 35, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/33601,Electrical,Completed,NM-ALANDUR,160,336800,"Supply and Installation of new EB meter panel and cable laying for the meter, 100KVA genset and motor room in Zonal office, Zone XII",Own Sources,12,2015-16,2016-17 NM/2015-16/33604,Electrical,Completed,NM-ALANDUR,160,720900,"Erection of 13 Nos of 6 mtr lamp post with single straight bracket and 40-50W LED fittings in New street Park, Division 160, zone XII.",Own Sources,12,2015-16,2016-17 NM/2015-16/33607,Roads,Completed,NM-ALANDUR,165,126000,"Providing Hand Rail and Platform to modular Toilet (SSS) at In Div-165,U-37,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/33633,Electrical,Completed,NM-ALANDUR,162,978700,Removal and Refixing of 40 nos of 6m MS street lamp post with single arch bracket with 90-120W LED fittings in division 162 in zone XII due to storm water drain construction in M.K.N Road. (Sch of rate 2015-16),Own Sources,12,2015-16,2016-17 NM/2015-16/33634,Electrical,Completed,NM-ALANDUR,161,873600,"Replacement of damaged 4 x 25 sqmm Alu cables of 1780 Mtrs with 4 x 16 sqmm Alu Cable at M.K.N Road in Div 161, Zone XII and Removal and Refixing of 15 nos of 6m MS street lamp post with single arch bracket with 90-120W LED fittings in division 161 , Zone XII due to storm water drain construction in M.K.N Road. (Sch of rate 2015-16)",Own Sources,12,2015-16,2016-17 NM/2015-16/33696,Electrical,Completed,NM-ALANDUR,163,534500,Supply and Erection of 8 nos of 6m GI Lamp post with 4 nos of 90-120W LED Fittings and 4 nos of 40-50W LED Fittings in East Karikalan Street Tank pathway in division 163 in zone XII. (Sch of rate 2015-16),Own Sources,12,2015-16,2016-17 NM/2015-16/33803,Roads,Completed,NM-ALANDUR,156,117000,"PROVIDING AND LAYING GSB & WMM AT AMIRTHALINGAM 2nd, STREET IN DN - 156, U - 35, Z -12.",Own Sources,12,2015-16,2016-17 NM/2015-16/33804,Roads,Completed,NM-ALANDUR,156,270000,"PROVIDING AND LAYING GSB & WMM AT AMIRTHALINGAM 1ST STREET IN DN -156, U -35 , Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/33881,Storm Water Drain,Completed,NM-ALANDUR,161,300000,"IMPROVEMENTS WORKS TO SIDE DRAIN AT SIDCO NAGAR (EAST SIDE) IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/33882,Buildings,Completed,NM-ALANDUR,161,322000,"IMPROVEMENTS WORKS TO PC AT VOC NAGAR IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/33883,Parks,Completed,NM-ALANDUR,161,172000,"IMPROVEMENT WORKS TO TNGO COLONY PARK IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/34015,Roads,Completed,NM-ALANDUR,161,157000,"IMPROVEMENTS WORKS TO JEEVAN NAGAR PARK IN DN-161,U-36,Z-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/34072,Roads,Completed,NM-ALANDUR,158,975000,"Attending patch work due to flood at Defence Colony 1st Avenue From 4th cross street to 8th cross street in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34073,Roads,Completed,NM-ALANDUR,158,928000,"Attending patch work due to flood at Defence Colony 1st Avenue From 8th cross street to 13th cross street in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34093,Buildings,Completed,NM-ALANDUR,161,104000,"IMPROVEMENT WORKS TO GROUP BIN PLATFORM AT VARIOUS STREET AND WRITING NAME BOARD AT COC BUILDINGS IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/34096,Roads,Completed,NM-ALANDUR,158,827000,"Attending patch work due to flood at Defence Colony 2nd Avenue From Koothalamman koil to 8th cross street in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34097,Roads,Completed,NM-ALANDUR,158,539000,"Attending patch work due to flood at Defence Colony 2nd Avenue From 8th cross street to 4th cross street in Dn-158, U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34158,Buildings,Completed,NM-ALANDUR,161,209000,"IMPROVEMENTS WORKS TO CHENNAI PRIMARY SCHOOL AT AR LANE IN DIV-161 ,U-36, Z-XII.",Own Sources,12,2015-16,2016-17 NM/2015-16/34272,Parks,Completed,NM-ALANDUR,161,484000,"IMPROVEMENT WORKS TO FOOTPATH AT TNGO COLONY 1ST STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2018-19 NM/2015-16/34409,Storm Water Drain,Completed,NM-ALANDUR,158,149000,"Desilting of Storm water drain and providing Silt Catch Pit at Padmini Garden in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34410,Storm Water Drain,Completed,NM-ALANDUR,158,80000,"Desilting of Storm water drain and providing Silt Catch Pit at Koothalamman Koil street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34411,Storm Water Drain,Completed,NM-ALANDUR,158,86000,"Desilting of Storm water drain and providing Silt Catch Pit at Bajanai Koil Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34412,Storm Water Drain,Completed,NM-ALANDUR,158,100000,"Desilting of Storm water drain and providing Silt Catch Pit at Ramar Koil Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34413,Storm Water Drain,Completed,NM-ALANDUR,158,93000,"Desilting of Storm water drain at Defence colony 1st & 2nd main road in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34468,Buildings,Completed,NM-ALANDUR,160,266000,"Improvements works to side drain at city link road in Dn 160, Unit 35, Zn 12",Own Sources,12,2015-16,2016-17 NM/2015-16/34469,Buildings,Completed,NM-ALANDUR,160,124000,"Improvements works to gandhi hospital at sowri street in Dn 160, Unit 35, Zn 12",Own Sources,12,2015-16,2016-17 NM/2015-16/34471,Electrical,Completed,NM-ALANDUR,165,746000,"Erection of 20 nos of 2 mts GI lamp posts with single arch bkt with 15W led fittings and 2 nos of 6m lamp post with 150W LED Fittings at South sector 2nd st and Lakshmi Nagar 1st st Park in div 165, Z-XII",Own Sources,12,2015-16,2017-18 NM/2015-16/34472,Electrical,Completed,NM-ALANDUR,165,648000,"Erection of 11 nos of 6 mtr GI Lamp posts with single arch bkt 12 nos of 90-120W LED fittings at Balaji Nagar 10th st park in div 165, Z-XII",Own Sources,12,2015-16,2017-18 NM/2015-16/34561,Roads,Completed,NM-ALANDUR,165,809000,"Improvement Works to CPS at South New Street in Div-165, Unit-37, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34658,Parks,Completed,NM-ALANDUR,161,479000,"IMPROVEMENT WORKS TO FOOTPATH AT JEEVAN NAGAR 3RD STREET AND JEEVAN NAGAR 2ND STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2018-19 NM/2015-16/34683,Electrical,Completed,NM-ALANDUR,156,736000,REMOVAL AND REFIXING OF 40 NOS OF 6 MTRS MS LAMP POSTS AND 3 NOS OF KIOSK PILLAR BOX AT VARIOUS LOCATIONS DUE TO CONSTRUCTION OF STORM WATER DRAIN IN DIV 156 IN ZONE XII,Own Sources,12,2015-16,2017-18 NM/2015-16/34738,Parks,Completed,NM-ALANDUR,161,178000,"IMPROVEMENTS WORKS TO AMMA UNAVAGAM AT VELACHERY ROAD IN DN-161,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/34847,Roads,Completed,NM-ALANDUR,157,877000,REMOVAL AND REFIXING OF 50 NOS OF 6 MTRS MS LAMP POSTS AND 3 NOS OF KIOSK PILLAR BOX AT VARIOUS LOCATIONS DUE TO CONSTRUCTION OF STORM WATER DRAIN IN DIV 157 IN ZONE XII,Own Sources,12,2015-16,2017-18 NM/2015-16/34889,Roads,Completed,NM-ALANDUR,163,956000,"ATTENDING PATCH WORK AT RAMAKRISHNAPURAM 2ND AND 3RD STREET,PALANDIYAMMAN KOIL STREET,IN DN-163,UNIT-36,ZONE-12",Own Sources,12,2015-16,2017-18 NM/2015-16/35023,Storm Water Drain,Completed,NM-ALANDUR,163,310000,"DESILDING OF CANAL CLEANING ADAMBAKKAM CANAL(FROM ADAMBAKKAM TO VELLACHERY) BY ENGAGING MACHINERIES IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2017-18 NM/2015-16/3588,Parks,Completed,NM-ALANDUR,162,990000,"Construction the park with play apparatus in Thiruvalluvar Nagar 3rd street in Dn - 162, U - 36, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/3677,Buildings,Completed,NM-ALANDUR,157,993000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 1ST MAIN ROAD IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3678,Buildings,Completed,NM-ALANDUR,157,644000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 2ND MAIN ROAD IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3679,Buildings,Completed,NM-ALANDUR,157,711000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 2ND STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3680,Buildings,Completed,NM-ALANDUR,157,427000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 4TH STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3681,Buildings,Completed,NM-ALANDUR,157,285000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 7TH STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3682,Buildings,Completed,NM-ALANDUR,157,998000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 1ST STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3684,Buildings,Completed,NM-ALANDUR,157,298000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 2ND CROSS STREET(SOUTH SIDE) IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3685,Buildings,Completed,NM-ALANDUR,157,338000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 6TH STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3686,Buildings,Completed,NM-ALANDUR,157,270000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 1ST CROSS STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3688,Buildings,Completed,NM-ALANDUR,157,575000,"IMPROVEMENTS WORKS OF EXSITING SWD AT DR.AMBEDKAR SALAI IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3689,Buildings,Completed,NM-ALANDUR,157,474000,"IMPROVEMENTS WORKS OF EXSITING SWD AT DHARMARAJAPURAM 1ST MAIN ROAD IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3690,Buildings,Completed,NM-ALANDUR,157,710000,"IMPROVEMENTS WORKS OF EXSITING SWD AT GIRI GORI NAGER 1ST CROSS STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3724,Buildings,Completed,NM-ALANDUR,157,298000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 4TH CROSS STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3726,Buildings,Completed,NM-ALANDUR,157,270000,"IMPROVEMENTS WORKS OF EXSITING SWD AT SATHIYA NAGER 2ND CROSS STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3755,Buildings,Completed,NM-ALANDUR,162,812000,REPAIR AND SERVICE OF GASIFIER EQUIPMENTS & MACHINERIES AT BALAKRISHNAPURAM BURIAL GROUND IN DN-163 U-36 Z-12,Own Sources,12,2015-16,2017-18 NM/2015-16/3766,Buildings,Completed,NM-ALANDUR,157,884000,"IMPROVEMENTS WORKS OF EXSITING SWD AT GIRI GORI NAGER MAIN ROAD IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3767,Buildings,Completed,NM-ALANDUR,157,349000,"IMPROVEMENTS WORKS OF EXSITING SWD AT GIRI GORI NAGER MURUGATHAMMAN KOIL STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3768,Buildings,Completed,NM-ALANDUR,157,638000,"IMPROVEMENTS WORKS OF EXSITING SWD AT INDRA NAGER THULUKATHAMMAN KOIL STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3770,Buildings,Completed,NM-ALANDUR,157,710000,"IMPROVEMENTS WORKS OF EXSITING SWD AT PERIYA COLONY EAST STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3773,Buildings,Completed,NM-ALANDUR,157,526000,"IMPROVEMENTS WORKS OF EXSITING SWD AT GIRI GORI NAGER 1ST STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3779,Buildings,Completed,NM-ALANDUR,157,995000,"IMPROVEMENTS WORKS OF EXSITING SWD AT PERIYA COLONY TO BAJANI KOIL STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3782,Buildings,Completed,NM-ALANDUR,157,526000,"IMPROVEMENTS WORKS OF EXSITING SWD AT DHARMARAJAPURAM MAIN ROAD IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3783,Buildings,Completed,NM-ALANDUR,157,330000,"CONSTRUCTION OF SWD AT METTU COLONY ANNA STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3784,Buildings,Completed,NM-ALANDUR,157,924000,"CONSTRUCTION OF SWD AT KAMARAJAR SALAI IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3786,Buildings,Completed,NM-ALANDUR,157,280000,"CONSTRUCTION OF SWD AT MEETU COLONY BAJANI KOIL STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3794,Buildings,Completed,NM-ALANDUR,157,924000,"CONSTRUCTION OF SWD AT METTU COLONY TANK STREET IN DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/3813,Buildings,Completed,NM-ALANDUR,157,179000,"CONSTRUCTION OF SWD AT MOTTATHAMMAN KOIL STREET DIV-157, UNIT-35, ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/4047,Buildings,Completed,NM-ALANDUR,164,936000,"IMPROVEMENT WORKS OF 16TH DAY CEREMONY HALL AT NANGANALLUR 4th MAIN ROAD IN DIVISION - 164, UNIT - 37, ZONE - 12",Own Sources,12,2015-16,2016-17 NM/2015-16/4139,Roads,Completed,NM-ALANDUR,161,905000,"PATCH WORK FOR VARIOUS STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/4811,Buildings,Completed,NM-ALANDUR,159,2348000,"CONSTRUCTION OF GYM BUILDING WITH GYM EQUIPMENTS (UNDER 2015-16 WARD COUNCILLOR FUND) AT KAMARAJ STREET, IN DN 159, UNIT 35, ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/4882,Culvert,Completed,NM-ALANDUR,167,543000,"CONSTRUCTION OF CULVERT AT M.G.R ROAD (JUNCTION OF HINDU COLONY 15TH STREET) IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/4887,Culvert,Completed,NM-ALANDUR,167,527000,"CONSTRUCTION OF CULVERT AT MMTC COLONY (JUNCTION OF KANNAN NAGAR 3RD MAIN ROAD AND SARVAMANGALA NAGAR) IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5015,Storm Water Drain,Completed,NM-ALANDUR,159,644000,"IMPROVEMENT TO EXISTING STORM WATER DRAIN AT THIRU.VI.KA STREET IN 159,UNIT-35, ZONE-12.(UNDER 2015-2016 COUNCILLAR FUND )",Own Sources,12,2015-16,2016-17 NM/2015-16/5078,Storm Water Drain,Completed,NM-ALANDUR,160,102000,"Desilting of Storm water drain and providing Silt Catch Pit at Dharmaraja Koil Street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5079,Storm Water Drain,Completed,NM-ALANDUR,160,90000,"Desilting of Storm water drain and providing Silt Catch Pit at Venu Street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5082,Storm Water Drain,Completed,NM-ALANDUR,160,107000,"Desilting of Storm water drain and providing Silt Catch Pit at James Street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5084,Storm Water Drain,Completed,NM-ALANDUR,160,86000,"Desilting of Storm water drain and providing Silt Catch Pit at Vembuli amman Koil Street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5085,Storm Water Drain,Completed,NM-ALANDUR,160,110000,"Desilting of Storm water drain and providing Silt Catch Pit at New street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5086,Storm Water Drain,Completed,NM-ALANDUR,160,86000,"Desilting of Storm water drain and providing Silt Catch Pit at Appavu Street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5087,Storm Water Drain,Completed,NM-ALANDUR,160,86000,"Desilting of Storm water drain and providing Silt Catch Pit at Paruthivakkam Street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5088,Storm Water Drain,Completed,NM-ALANDUR,160,104000,"Desilting of Storm water drain and providing Silt Catch Pit at Madurai Street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5090,Storm Water Drain,Completed,NM-ALANDUR,160,163000,"Desilting of Storm water drain and providing Silt Catch Pit at Vembuli Subedhar street in Din-160,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5112,Roads,Completed,NM-ALANDUR,161,240000,"IMPROVEMENTS WORKS TO SSS TOILET BLUE BIKES ROAD IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/5212,Storm Water Drain,Completed,NM-ALANDUR,156,91000,"Desilting of Storm water drain and providing Silt Catch Pit at s.s.koil street and ags colony ph-2 in Din-156,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5238,Buildings,Completed,NM-ALANDUR,166,730000,"IMPROVEMENTS TO NNMP SHED CENTER NO:51,61 & 50 AT NEHRU NEDUNCHALAI AND NNMP SHED CENTER NO 58,59 AT KALAIMATHY NAGAR, BURMA THAMIZHLAR COLONY IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5246,Buildings,Completed,NM-ALANDUR,166,500000,"Additional improvements works to unit office : 37 at Nehru Nedunchalai in Dn -166, U-37, Zn 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5249,Storm Water Drain,Completed,NM-ALANDUR,156,215000,"Desilting of Storm water drain and providing Silt Catch Pit at perumal koil street ,kumuthan nagar main road in Din-156,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5250,Storm Water Drain,Completed,NM-ALANDUR,156,130000,"Desilting of Storm water drain and providing Silt Catch Pit at Kumutham nager 5th Street and kumutham nagar east main roadin Din-156,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5251,Storm Water Drain,Completed,NM-ALANDUR,156,124000,"Desilting of Storm water drain and providing Silt Catch Pit at subashhree nager ,kumutham nagar 4th cross street, ags colony in Din-156,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5252,Storm Water Drain,Completed,NM-ALANDUR,156,50000,"Desilting of Storm water drain and providing Silt Catch Pit at A.G.S.colony phase-2 in Din-156,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5253,Storm Water Drain,Completed,NM-ALANDUR,156,158000,"Desilting of Storm water drain and providing Silt Catch Pit at easwaran koil street,mugalivakkam to manapakkam main road in Din-156,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5254,Storm Water Drain,Completed,NM-ALANDUR,156,129000,"Desilting of Storm water drain and providing Silt Catch Pit at subasri nagar in Din-156,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5265,Storm Water Drain,Completed,NM-ALANDUR,158,53000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 9th Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5266,Storm Water Drain,Completed,NM-ALANDUR,158,22000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 7th Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5267,Storm Water Drain,Completed,NM-ALANDUR,158,42000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 6th Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5268,Storm Water Drain,Completed,NM-ALANDUR,158,55000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 5th Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5269,Storm Water Drain,Completed,NM-ALANDUR,158,60000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony main road in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5270,Storm Water Drain,Completed,NM-ALANDUR,158,54000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 4th Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5271,Storm Water Drain,Completed,NM-ALANDUR,158,34000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 3rd Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5272,Storm Water Drain,Completed,NM-ALANDUR,158,55000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 2nd Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5273,Storm Water Drain,Completed,NM-ALANDUR,158,50000,"Desilting of Storm water drain and providing Silt Catch Pit at Ganapathy colony 1st Street in Din-158,Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5285,Storm Water Drain,Completed,NM-ALANDUR,165,150000,"Desilting and repair works to storm water drain at Vel nagar Extn main road in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5286,Storm Water Drain,Completed,NM-ALANDUR,165,9200,"Desilting works to storm water drain at Nethaji street in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5287,Storm Water Drain,Completed,NM-ALANDUR,165,132999,"Desilting and repair works to storm water drain at Balaji nagar main road in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5288,Storm Water Drain,Completed,NM-ALANDUR,165,141999,"Desilting and repair works to storm water drain at Thiruvalluvar street in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5289,Storm Water Drain,Completed,NM-ALANDUR,165,166000,"Desilting and repair works to storm water drain at Balaji nagar extn main road in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5290,Storm Water Drain,Completed,NM-ALANDUR,165,154000,"Desilting and repair works to storm water drain at Valmigi street in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5291,Storm Water Drain,Completed,NM-ALANDUR,165,143000,"Desilting and repair works to storm water drain at Balaji nagar 3rd street in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5292,Storm Water Drain,Completed,NM-ALANDUR,165,6400,"Desilting works to storm water drain at Bharathidasan street in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5293,Storm Water Drain,Completed,NM-ALANDUR,165,9900,"Desilting works to storm water drain at New colony 1st street in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5297,Storm Water Drain,Completed,NM-ALANDUR,165,23000,"Desilting works to storm water drain at Thiruvalluvar street in Dn - 165, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5440,Storm Water Drain,Completed,NM-ALANDUR,167,774000,"Construction of side drain at Kannagambal colony main road in Dn - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5455,Culvert,Completed,NM-ALANDUR,166,480000,"Demolition and Reconstruction of culvert at B.V nagar 16th street, Ragupathy nagar 2nd and 3rd street in Dn - 166, U - 37, Z -12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5464,Storm Water Drain,Completed,NM-ALANDUR,160,680000,"Improvements work to existing Storm water drain at Maduvankarai 5th street in Dn-160, U-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5465,Buildings,Completed,NM-ALANDUR,160,457000,"Improvements work to existing Storm water drain at Maduvankarai 4th street in Dn-160, U-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5502,Buildings,Completed,NM-ALANDUR,166,737000,"CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENT WORKS TO K.K.NAGAR PLAY FIELD IN DN 166, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5543,Buildings,Completed,NM-ALANDUR,163,704000,"Proposed fixing of street name boards using SS.Pipe and Retro reflective sheets in various streets in DN-163,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5613,Culvert,Completed,NM-ALANDUR,167,511000,"CONSTRUCTION OF CULVERT AT NANGANALLUR 46TH STREET JUNCTION OF LAKSHMI NAGAR 2ND STREET, 5TH STREET 6TH, STREET IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5614,Culvert,Completed,NM-ALANDUR,167,498000,"CONSTRUCTION OF CULVERT AT LAKSHMI NAGAR MAIN ROAD(3 STAGE) JUNCTION OF LAKSHMI NAGAR 1ST, 2ND 6TH, 7TH STREET IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5689,Road Cut,Completed,NM-ALANDUR,161,995000,"IMPROVEMENT TO SWD AT VEDHAGIRI (NORTH SIDE)STREET IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5690,Road Cut,Completed,NM-ALANDUR,161,995000,"IMPROVEMENT TO SWD AT VEDHAGIRI (SOUTH SIDE)STREET IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5691,Road Cut,Completed,NM-ALANDUR,161,996000,"IMPROVEMENT TO SWD AT ALAGIRI STREET IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5692,Storm Water Drain,Completed,NM-ALANDUR,161,320000,"IMPROVEMENT TO SWD AT OFFICERS COLONY 5TH STREET IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5752,Storm Water Drain,Completed,NM-ALANDUR,166,970000,"IMPROVEMENT TO THE EXISTING STORM WATER DRAIN AT B.V.NAGAR 9TH STREET(PART), B.V.NAGAR 12TH STREET(PART) AND RAGHUPATHI 6TH STREET(PART) IN DN 166, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/5826,Buildings,Completed,NM-ALANDUR,163,867000,"IMPROVEMENT AND REPAIR WORKS TO C.M.S AT KARNEEGAR STREET IN DN-163,U-36,Z-12",Own Sources,12,2015-16,2016-17 NM/2015-16/5894,Storm Water Drain,Completed,NM-ALANDUR,161,545000,"IMPROVEMENT TO SWD AT MASTHAN GORI 1ST LANE IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/6199,Roads,Completed,NM-ALANDUR,167,959000,"CONSTRUCTION OF SILT CATCH PIT AT NANGANALLUR 100 FEET ROAD, LAKSHMI NAGAR MAIN ROAD, LAKHMI NAGAR 1ST STREET TO 7TH STREET IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2017-18 NM/2015-16/6200,Roads,Completed,NM-ALANDUR,167,953000,"CONSTRUTION OF SILT CATCH PIT AT HINDU COLONY 1ST CROSS STREET TO 25TH CROSS STREET IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2018-19 NM/2015-16/6208,Storm Water Drain,Completed,NM-ALANDUR,166,982000,"IMPROVEMENT TO THE EXISTING STORM WATER DRAIN AT B.V.NAGAR 3RD STREET EAST AND WEST SIDE (FROM B.V.NAGAR 9TH STREET TO B.V.NAGAR 3RD MAIN ROAD) IN DN 166, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/6210,Roads,Completed,NM-ALANDUR,164,935000,"WIDENING OF CEMENT CONCRETE ROAD USING PAVER BLOCK AT NEHRUCOLONY MAIN ROAD (WEST SIDE) IN DIVISION-164, UNIT-37, ZONE-12.",Own Sources,12,2015-16,2017-18 NM/2015-16/6224,Parks,Completed,NM-ALANDUR,167,310000,"ADDITIONAL IMPROVEMENT TO THE EXISTING PARK AT KANNIGA COLONY 2ND STREET IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/6225,Roads,Completed,NM-ALANDUR,167,982000,"LAYING INTERLOCKING PAVER BLOCK AT LAKSHMI NAGAR MAIN ROAD IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/6230,Roads,Completed,NM-ALANDUR,167,969000,"LAYING INTERLOCKING PAVER BLOCK AT LAKSHMI NAGAR 1ST STREET, 2ND STREET, 4TH STREET IN DN 167, U 37, Z 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/6273,Roads,Completed,NM-ALANDUR,164,983000,"PROVIDING RETRO REFLECTIVE STREET NAME BOARD AT VARIOUS STREET IN DIVISION-164, UNIT-37, ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/6333,Roads,Completed,NM-ALANDUR,164,935000,"WIDENING OF CEMENT CONCRETE ROAD USING PAVER BLOCK AT NEHRUCOLONY MAIN ROAD (EAST SIDE) IN DIVISION-164, UNIT-37, ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/6334,Roads,Completed,NM-ALANDUR,164,935000,"ATTENDING ROAD PATCH WOKS AND PROVIDING SPEED BREAKER AT VARIOUS STREETS IN DN-164 , UNIT-37 , ZONE -12.",Own Sources,12,2015-16,2016-17 NM/2015-16/6434,Footpath,Completed,NM-ALANDUR,160,598000,"Providing Footpath and Name Signage Board at Railway Station Road in Div-160, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/6445,Roads,Completed,NM-ALANDUR,160,284000,"Providing footpath and hand rail to Mobile toilet at MKN Road in Div 160, U 35, Zn 12",Own Sources,12,2015-16,2016-17 NM/2015-16/6446,Buildings,Completed,NM-ALANDUR,160,455000,"Improvements to Councillor room at Super Bazzar in Dn 160, Unit 35, Zn 12",Own Sources,12,2015-16,2016-17 NM/2015-16/6477,Storm Water Drain,Completed,NM-ALANDUR,165,980000,Improvements works to side drain at Thamarabrani street in dn 165 z.12,Own Sources,12,2015-16,2016-17 NM/2015-16/6484,Storm Water Drain,Completed,NM-ALANDUR,165,947958,Improvements works to side drain at New colony 1st street in dn 165 z.12,Own Sources,12,2015-16,2016-17 NM/2015-16/6486,Storm Water Drain,Completed,NM-ALANDUR,165,934000,Improvements works to side drain at vell nagar 1st street in dn 165 z.12,Own Sources,12,2015-16,2016-17 NM/2015-16/6489,Storm Water Drain,Completed,NM-ALANDUR,165,978000,Improvements works to side drain at thiruvalluvar nagar in dn 165 z.12,Own Sources,12,2015-16,2016-17 NM/2015-16/6529,Roads,Completed,NM-ALANDUR,157,577000,"PROVIDING SPEED BREAKERS AT VARIOUS STREETS IN DIV 157, U 35, ZN 12",Own Sources,12,2015-16,2016-17 NM/2015-16/6851,Electrical,Completed,NM-ALANDUR,165,998000,"Erection of 16 nos of 7mtr GI lamp posts with single arch bkt with 21 nos of 90-120W LED fittings at new colony burial gnd and muthiyal reddy nagar burial gnd in div-165, Z-XII, Alandur",Own Sources,12,2015-16,2017-18 NM/2015-16/6853,Parks,Completed,NM-ALANDUR,160,917000,"Improvements to the Park at New Street in Dn-160,U-35, Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/6975,Culvert,Completed,NM-ALANDUR,165,339000,"CONSTRUCTION OF CALVERT AND IMPROVEMENTS TO SIDE DRAIN AT BALAJI NAGAR MAIN ROAD IN DIV 165,UNIT 37,ZONE12.",Own Sources,12,2015-16,2016-17 NM/2015-16/7077,Culvert,Completed,NM-ALANDUR,165,316000,"CONSTRUCTION OF CALVERT AND IMPROVEMENTS TO SIDE DRAIN AT NEW COLONY 2ND STREET(JN OF NEW COLONY 5TH STREET) IN DIV 165,UNIT 37,ZONE12.",Own Sources,12,2015-16,2016-17 NM/2015-16/7374,Parks,Completed,NM-ALANDUR,156,876000,"Tree Saplings Planting at various streets in Dn-156,U-35,Zone-12",Own Sources,12,2015-16,2018-19 NM/2015-16/7384,Buildings,Completed,NM-ALANDUR,160,996000,"Improvements to the Super Bazzar Building to shifting Hospital at New Street in Dn - 160, U - 35, Zn-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/7424,Storm Water Drain,Completed,NM-ALANDUR,165,244000,"IMPROVEMENTS WORK TO SIDE DRAIN AT INCOME TAX COLONY 3RD STREET IN DIV 165,UNIT 37,ZONE12.",Own Sources,12,2015-16,2016-17 NM/2015-16/7775,Storm Water Drain,Completed,NM-ALANDUR,164,995000,"IMPROVEMENT WORKS TO EXISTING STORM WATER DRAIN AT THILLAI GANGA NAGAR 5TH MAIN ROAD IN DIVISION-164, UNIT-37, ZONE-12.",Own Sources,12,2015-16,2016-17 NM/2015-16/8190,Road Cut,Completed,NM-ALANDUR,161,317000,"IMPROVEMENT TO SWD AT LYODS AVENUE STREET IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8191,Storm Water Drain,Completed,NM-ALANDUR,161,395000,"IMPROVEMENT TO SWD AT JEEVAN NAGAR MAIN ROAD (EAST SIDE) IN DN-161,U-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8224,Buildings,Completed,NM-ALANDUR,161,286000,"CONSTRUCTION OF COMPOUND WALL IN GYM BUILDING AT RAJA STREET IN DN-161,U-36,Z-XII",Own Sources,12,2015-16,2017-18 NM/2015-16/8278,Roads,Completed,NM-ALANDUR,166,500000,"LAYING M40 GRADE CONCRETE INTERLOCKING PAVER BLOCK AT COLLEGE ROAD EXTN IN DN - 166, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/8300,Buildings,Completed,NM-ALANDUR,161,540000,"CONSTRUCTION OF MULTIPURPOSE BUILDING AT RAJA STRRET in Division -161 Unit-36, Zone-XII",Own Sources,12,2015-16,2016-17 NM/2015-16/8467,Roads,Completed,NM-ALANDUR,158,1415000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Sundar Nagar 1st Avenue in Dn-158,Unit-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8468,Roads,Completed,NM-ALANDUR,158,967000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Sundar Nagar 3rd Avenue in Dn-158,Unit-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8475,Roads,Completed,NM-ALANDUR,158,571000,"Relaying and Strengthening CC roaad by using RMC 30 grade at Thulasingapuram Main Road in Dn-158,Unit-35,Zn-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8552,Roads,Completed,NM-ALANDUR,163,176000,"WIDENING AT EARIKKARAI STREET IN DIVITION-163,UNIT-36,ZONE-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8557,Storm Water Drain,Completed,NM-ALANDUR,165,751000,"DESILTING OF VEERANGAL ODAI IN DIFFERENT LOCATIONS FROM INDRA NAGAR TO BHUVANESHVARI NAGAR 4TH STREET IN DIV 165,UNIT 37,ZONE 12.2.",Own Sources,12,2015-16,2016-17 NM/2015-16/8717,Roads,Completed,NM-ALANDUR,157,363000,"Relaying and Strengthening of CC Road by using RMC M-30 at kaviya garden kurinji street in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8718,Roads,Completed,NM-ALANDUR,157,382000,"Relaying and Strengthening of CC Road by using RMC M-30 at crr puram 1st left cross street in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8719,Roads,Completed,NM-ALANDUR,157,908000,"Relaying and Strengthening of CC Road by using RMC M-30 at crr puram 1st main road in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8720,Roads,Completed,NM-ALANDUR,157,218000,"Relaying and Strengthening of CC Road by using RMC M-30 at crr puram 2nd left cross street in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8721,Roads,Completed,NM-ALANDUR,157,600000,"Relaying and Strengthening of CC Road by using RMC M-30 at CRR PURAM 2ND MAIN ROAD 2ND CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8722,Roads,Completed,NM-ALANDUR,157,955000,"Relaying and Strengthening of CC Road by using RMC M-30 at CRR PURAM 2ND MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8723,Roads,Completed,NM-ALANDUR,157,908000,"Relaying and Strengthening of CC Road by using RMC M-30 at CRR PURAM 3RD MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8724,Roads,Completed,NM-ALANDUR,157,403000,"Relaying and Strengthening of CC Road by using RMC M-30 at CRR PURAM 3ND MAIN ROAD RIGHT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8725,Roads,Completed,NM-ALANDUR,157,159000,"Relaying and Strengthening of CC Road by using RMC M-30 at CRR PURAM LINK ROAD 2ND MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8726,Roads,Completed,NM-ALANDUR,157,218000,"Relaying and Strengthening of CC Road by using RMC M-30 at CRR PURAM LINK ROAD 1ST CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8727,Roads,Completed,NM-ALANDUR,157,191000,"Relaying and Strengthening of CC Road by using RMC M-30 at CRR PURAM LINK ROAD 1ST MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8728,Roads,Completed,NM-ALANDUR,157,272000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER 1ST MAIN RIGHT 2ND CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8729,Roads,Completed,NM-ALANDUR,157,345000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER 1ST MAIN RIGHT 3RD CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8730,Roads,Completed,NM-ALANDUR,157,544000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER 1ST MAIN RIGHT 1ST CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8732,Roads,Completed,NM-ALANDUR,157,726000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER 2ND MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8734,Roads,Completed,NM-ALANDUR,157,581000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER 4TH MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8735,Roads,Completed,NM-ALANDUR,157,665000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER 5TH MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8736,Roads,Completed,NM-ALANDUR,157,295000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER SALAI in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8737,Roads,Completed,NM-ALANDUR,157,363000,"Relaying and Strengthening of CC Road by using RMC M-30 at DR. AMBEDKAR NAGER 3RD LEFT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8740,Roads,Completed,NM-ALANDUR,157,655000,"Relaying and Strengthening of CC Road by using RMC M-30 at MUKTHI ENCLAVE MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8741,Roads,Completed,NM-ALANDUR,157,272000,"Relaying and Strengthening of CC Road by using RMC M-30 at MUKTHI ENCLAVE RIGHT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8742,Roads,Completed,NM-ALANDUR,157,567000,"Relaying and Strengthening of CC Road by using RMC M-30 at NARKUNDEESHWARAR SALAI in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8747,Roads,Completed,NM-ALANDUR,157,1964000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYAR SALAI 1ST CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8748,Roads,Completed,NM-ALANDUR,157,372000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYAR SALAI 2ND CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8749,Roads,Completed,NM-ALANDUR,157,454000,"Relaying and Strengthening of CC Road by using RMC M-30 at PRASAD GARDEN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8751,Roads,Completed,NM-ALANDUR,157,204000,"Relaying and Strengthening of CC Road by using RMC M-30 at KRISHNNA ENCLAVE 2ND RIGHT LEFT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8762,Roads,Completed,NM-ALANDUR,157,817000,"Relaying and Strengthening of CC Road by using RMC M-30 at VALLISWARAN KOIL STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8769,Roads,Completed,NM-ALANDUR,157,749000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYAR SALAI 3RD CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8770,Roads,Completed,NM-ALANDUR,157,437000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYAR SALAI 4TH CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8771,Roads,Completed,NM-ALANDUR,157,819000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYAR SALAI 5TH CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8772,Roads,Completed,NM-ALANDUR,157,386000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYAR SALAI 5TH MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8774,Roads,Completed,NM-ALANDUR,157,431000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR 4TH MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8775,Roads,Completed,NM-ALANDUR,157,431000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR 3RD MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8776,Roads,Completed,NM-ALANDUR,157,454000,"Relaying and Strengthening of CC Road by using RMC M-30 at PRESIDENT MUNUSAMY NAGAR in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8777,Roads,Completed,NM-ALANDUR,157,204000,"Relaying and Strengthening of CC Road by using RMC M-30 at RAMACHANDRA COLONY ROAD 3RD LEFT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8778,Roads,Completed,NM-ALANDUR,157,182000,"Relaying and Strengthening of CC Road by using RMC M-30 at RAMACHANDRA COLONY IST MAIN IST CROSS TO 3RD CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8779,Roads,Completed,NM-ALANDUR,157,454000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR IST MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8780,Roads,Completed,NM-ALANDUR,157,590000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELL NAGAR MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8781,Roads,Completed,NM-ALANDUR,157,600000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELLS NAGAR 5TH CROSS STREET NEW in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8782,Roads,Completed,NM-ALANDUR,157,454000,"Relaying and Strengthening of CC Road by using RMC M-30 at M.G.R NAGAR 3RD STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8783,Roads,Completed,NM-ALANDUR,157,1200000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY 1ST MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8784,Roads,Completed,NM-ALANDUR,157,318000,"Relaying and Strengthening of CC Road by using RMC M-30 at KAVIYA GARDEN KRISHNAKAMALAMin Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8786,Roads,Completed,NM-ALANDUR,157,600000,"Relaying and Strengthening of CC Road by using RMC M-30 at MAROMARVEL RIVER COUNTRY 7TH CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8787,Roads,Completed,NM-ALANDUR,157,181000,"Relaying and Strengthening of CC Road by using RMC M-30 at PURACHI THALAIVI NAGAR 2ND LEFT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8788,Roads,Completed,NM-ALANDUR,157,600000,"Relaying and Strengthening of CC Road by using RMC M-30 at SETHU LAKSHMNI AVENUE RIGHT IST CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8789,Roads,Completed,NM-ALANDUR,157,819000,"Relaying and Strengthening of CC Road by using RMC M-30 at MAROMARVEL RIVER COUNYRT 2ND CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8790,Roads,Completed,NM-ALANDUR,157,786000,"Relaying and Strengthening of CC Road by using RMC M-30 at MARO MARVEL MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8791,Roads,Completed,NM-ALANDUR,157,204000,"Relaying and Strengthening of CC Road by using RMC M-30 at KRISHNA ENCLAVE IST RIGHT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8793,Roads,Completed,NM-ALANDUR,157,600000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY KRISHNA STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8794,Roads,Completed,NM-ALANDUR,157,546000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY GOTHAVARI STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8795,Roads,Completed,NM-ALANDUR,157,363000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY GANGA STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8796,Roads,Completed,NM-ALANDUR,157,227000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY IST MAIN ROAD , 2ND MAIN ROAD JOINT ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8801,Roads,Completed,NM-ALANDUR,157,204000,"Relaying and Strengthening of CC Road by using RMC M-30 at DOCTORS GARDEN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8803,Roads,Completed,NM-ALANDUR,157,295000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR IST MAIN ROAD 3RD CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8804,Roads,Completed,NM-ALANDUR,157,437000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR 5TH STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8805,Roads,Completed,NM-ALANDUR,157,145000,"Relaying and Strengthening of CC Road by using RMC M-30 at PURACHITHALAIVI NAGAR 2ND RIGHT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8806,Roads,Completed,NM-ALANDUR,157,181000,"Relaying and Strengthening of CC Road by using RMC M-30 at PURACHI THALAVI NAGAR MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8807,Roads,Completed,NM-ALANDUR,157,145000,"Relaying and Strengthening of CC Road by using RMC M-30 at PURACHITHALAIVI NAGAR 1ST RIGHT GROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8808,Roads,Completed,NM-ALANDUR,157,181000,"Relaying and Strengthening of CC Road by using RMC M-30 at PURACHITHALAIVI NAGAR 3RD GROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8809,Roads,Completed,NM-ALANDUR,157,2729000,"Relaying and Strengthening of CC Road by using RMC M-30 at SEDHU LAKSHMI AVENUE MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8810,Roads,Completed,NM-ALANDUR,157,1092000,"Relaying and Strengthening of CC Road by using RMC M-30 at KRISHNA ENCLAVE MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8811,Roads,Completed,NM-ALANDUR,157,600000,"Relaying and Strengthening of CC Road by using RMC M-30 at PILLAYR KOIL 5TH STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8812,Roads,Completed,NM-ALANDUR,157,3820000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYAR SALAI KRISHNA NAGAR in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8813,Roads,Completed,NM-ALANDUR,157,681000,"Relaying and Strengthening of CC Road by using RMC M-30 at MEGANTHI BROTHERS MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8814,Roads,Completed,NM-ALANDUR,157,363000,"Relaying and Strengthening of CC Road by using RMC M-30 at NEHRU STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8816,Roads,Completed,NM-ALANDUR,157,901000,"Relaying and Strengthening of CC Road by using RMC M-30 at SETHU LAKSHMI AVENUE RIGHT 2ND MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8818,Roads,Completed,NM-ALANDUR,157,477000,"Relaying and Strengthening of CC Road by using RMC M-30 at KAVIYA GARDEN MANORANGITHAM STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8819,Roads,Completed,NM-ALANDUR,157,499000,"Relaying and Strengthening of CC Road by using RMC M-30 at KAVIYA GARDEN PATTURAJA STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8820,Roads,Completed,NM-ALANDUR,157,499000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELL NAGAR IST CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8821,Roads,Completed,NM-ALANDUR,157,1271000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8822,Roads,Completed,NM-ALANDUR,157,499000,"Relaying and Strengthening of CC Road by using RMC M-30 at M.G.R NAGAR 1ST STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8823,Roads,Completed,NM-ALANDUR,157,295000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELL NAGAR 7TH CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8824,Roads,Completed,NM-ALANDUR,157,250000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELL NAGAR 6TH CROSS STREET EAST in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8825,Roads,Completed,NM-ALANDUR,157,227000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELL NAGAR 5TH CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8826,Roads,Completed,NM-ALANDUR,157,318000,"Relaying and Strengthening of CC Road by using RMC M-30 at MACRO MARVEL RIVER COUNTRY 1ST CROSS STREET EAST in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8827,Roads,Completed,NM-ALANDUR,157,250000,"Relaying and Strengthening of CC Road by using RMC M-30 at MACRO MARVEL RIVER COUNTRY 4TH CROSS STREET EAST in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8828,Roads,Completed,NM-ALANDUR,157,227000,"Relaying and Strengthening of CC Road by using RMC M-30 at MACRO MARVEL RIVER COLNTRY 5TH CROSS STREET EAST in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8829,Roads,Completed,NM-ALANDUR,157,204000,"Relaying and Strengthening of CC Road by using RMC M-30 at MACRO MARVEL RIVER COUNTRY 6TH CROSS STREET EAST in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8830,Roads,Completed,NM-ALANDUR,157,546000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELL NAGAR 2ND CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8831,Roads,Completed,NM-ALANDUR,157,546000,"Relaying and Strengthening of CC Road by using RMC M-30 at M.G.R. NAGAR 2ND STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8832,Roads,Completed,NM-ALANDUR,157,409000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR 6TH AND 7TH STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8833,Roads,Completed,NM-ALANDUR,157,722000,"Relaying and Strengthening of CC Road by using RMC M-30 at INDRA NAGAR 2ND MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8834,Roads,Completed,NM-ALANDUR,157,454000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR 2ND MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8836,Roads,Completed,NM-ALANDUR,157,499000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGAR IST STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8843,Roads,Completed,NM-ALANDUR,157,1317000,"Relaying and Strengthening of CC Road by using RMC M-30 at GARDEN ROAD TO RAMACHANDRA COLONY in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8844,Roads,Completed,NM-ALANDUR,157,1203000,"Relaying and Strengthening of CC Road by using RMC M-30 at KAVIYA GARDEN MULLAI STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8845,Roads,Completed,NM-ALANDUR,157,409000,"Relaying and Strengthening of CC Road by using RMC M-30 at MACRO MARVEL RIVER COLONY 3RD CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8848,Roads,Completed,NM-ALANDUR,157,681000,"Relaying and Strengthening of CC Road by using RMC M-30 at SAHAJ ENCLAVE MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8849,Roads,Completed,NM-ALANDUR,157,477000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY 5TH MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8850,Roads,Completed,NM-ALANDUR,157,363000,"Relaying and Strengthening of CC Road by using RMC M-30 at BELL NAGAR 3RD CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8852,Roads,Completed,NM-ALANDUR,157,272000,"Relaying and Strengthening of CC Road by using RMC M-30 at C.R.R.PURAM PHASE-III IST CROSS ROAD LEFT STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8853,Roads,Completed,NM-ALANDUR,157,182000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYA COLONY BAJANAI 1st KOIL STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8855,Roads,Completed,NM-ALANDUR,157,1907000,"Relaying and Strengthening of CC Road by using RMC M-30 at BAJANAI KOIL STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8857,Roads,Completed,NM-ALANDUR,157,545000,"Relaying and Strengthening of CC Road by using RMC M-30 at BAJANAI KOIL 1ST STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8858,Roads,Completed,NM-ALANDUR,157,681000,"Relaying and Strengthening of CC Road by using RMC M-30 at BAJANAI KOIL 2ND STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8859,Roads,Completed,NM-ALANDUR,157,408000,"Relaying and Strengthening of CC Road by using RMC M-30 at PILLAYR KOIL 4TH STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8860,Roads,Completed,NM-ALANDUR,157,363000,"Relaying and Strengthening of CC Road by using RMC M-30 at SATHIYA NAGER 3RD CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8861,Roads,Completed,NM-ALANDUR,157,3499000,"Relaying and Strengthening of CC Road by using RMC M-30 at INDRA NAGER THULUGATHAMMAN KOIL STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8862,Roads,Completed,NM-ALANDUR,157,3101000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW AVENUE in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8863,Roads,Completed,NM-ALANDUR,157,1050000,"Relaying and Strengthening of CC Road by using RMC M-30 at PILLAYR KOIL MAIN ROAD in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8864,Roads,Completed,NM-ALANDUR,157,227000,"Relaying and Strengthening of CC Road by using RMC M-30 at BALARAM GARDEN 1ST CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8866,Roads,Completed,NM-ALANDUR,157,281000,"Relaying and Strengthening of CC Road by using RMC M-30 at PILLAYR KOIL 2ND STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8867,Roads,Completed,NM-ALANDUR,157,227000,"Relaying and Strengthening of CC Road by using RMC M-30 at PILLAYR KOIL 3RD STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8868,Roads,Completed,NM-ALANDUR,157,453000,"Relaying and Strengthening of CC Road by using RMC M-30 at ASTALAKISHMI AVENVE RIGHT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8869,Roads,Completed,NM-ALANDUR,157,1952000,"Relaying and Strengthening of CC Road by using RMC M-30 at ASTALAKISHMI AVENVE LEFT CROSS STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8871,Roads,Completed,NM-ALANDUR,157,2301000,"Relaying and Strengthening of CC Road by using RMC M-30 at PERIYA COLONY COLONY EAST STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8873,Roads,Completed,NM-ALANDUR,157,314000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY TEASTA STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/8874,Roads,Completed,NM-ALANDUR,157,773000,"Relaying and Strengthening of CC Road by using RMC M-30 at RIVER VIEW COLONY YAMUNA STREET in Div -157, Unit-35, Zone-12",Own Sources,12,2015-16,2016-17 NM/2015-16/9044,Storm Water Drain,Completed,NM-ALANDUR,165,735000,"IMPROVEMENT WORKS TO SIDE DRAIN AT MULLAI STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/9045,Storm Water Drain,Completed,NM-ALANDUR,165,935000,"IMPROVEMENT WORKS TO SIDE DRAIN AT THAMARAI STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/9047,Storm Water Drain,Completed,NM-ALANDUR,165,748000,"IMPROVEMENT WORKS TO SIDE DRAIN AT BALAJI NAGAR 11TH STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/9049,Roads,Completed,NM-ALANDUR,165,996000,Attending the BT Patch work at Various street in Division 165 Unit 37 Zone 12,Own Sources,12,2015-16,2016-17 NM/2015-16/9053,Buildings,Completed,NM-ALANDUR,156,670000,"CONSTRUCTION OF COMPOUND WALL FOR COMMUNITY HALL WITH GATE AND GATE PILLAR (SOUTH SIDE) AT SELVALAKSHMI NAGAR , MUGALIVAKKAM IN DN . 156, U - 35, ZONE - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/9055,Footpath,Completed,NM-ALANDUR,156,880000,"PAVING PAVER BLOCK AROUND COMMUNITY HALL AT A.G.S.COLONY 3RD PHASE , MUGALIVAKKAM IN DN.156, U - 35, ZONE - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/9483,Parks,Completed,NM-ALANDUR,167,850000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND PLAY FIELD AT LAKSHMI NAGAR EAST MAIN ROAD(4TH STAGE) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/9484,Storm Water Drain,Completed,NM-ALANDUR,167,393000,"IMPROVEMENT TO THE EXISTING SWD AT VENUGOPALAPURAM 2nd STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2015-16,2016-17 NM/2015-16/9527,Parks,Completed,NM-ALANDUR,167,590000,"Providing water supply and electrical arrangements to the existing SBI colony park at State bank colony (Near Nehru nedunsalai) in Dn - 167, U - 36, Z - 12",Own Sources,12,2015-16,2016-17 NM/2015-16/9529,Buildings,Completed,NM-ALANDUR,167,850000,"Additional improvements to the JE office at nanganallur 100 feet road in Dn - 167, U - 36, Z - 12",Own Sources,12,2015-16,2016-17 NM/2015-16/9531,Buildings,Completed,NM-ALANDUR,167,850000,"Proposed construction of CI and SI office at nanganallur 100 feet road in Dn - 167, U - 36, Z - 12",Own Sources,12,2015-16,2016-17 NM/2015-16/9579,Buildings,Completed,NM-ALANDUR,163,980000,ADDITIONAL CONSTRUCTION WORK OF URBAN DEVELOPMENTS HEALTH BUILDING AT MANNADIAMMAN KOIL STREET IN DN 163 U.36 Z.12,Grants,12,2015-16,2016-17 NM/2015-16/9598,Roads,Completed,NM-ALANDUR,167,750000,"WIDENING THE ROAD USING INTERLOCKING PAVER BLOCKS AT KANIGA COLONY 1ST AND 2ND STREET, IN DN 167, UNIT 37, ZONE 12",Own Sources,12,2015-16,2016-17 NM/2015-16/9608,Footpath,Completed,NM-ALANDUR,167,240000,"ADDITIONAL IMPROVEMENT TO THE SSS TOILET AT NANGANALLUR 6TH MAIN ROAD, HINDU COLONY 15TH STREET AND LAKSHMI NAGAR 4TH STAGE PARK, IN DN 167, UNIT 37, ZONE 12",Own Sources,12,2015-16,2016-17 NN/2015-16/0026,Road Cut,Completed,NN-ADYAR,181,880000,"Restoration of Road Cut at Coastal Road,Gangai Street,Kaveri Street,Thirumurugan Street (made by TANTRANSCO TNEB) in Dn 181, Unit 38, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/0054,Buildings,Completed,NN-ADYAR,178,994000,"Provision of additional Store room and Water Arrangement in Div 178 , Unit Office Unit 39, Zone XIII.",Own Sources,13,2015-16,2017-18 NN/2015-16/0142,Buildings,Completed,NN-ADYAR,174,764000,"IMPROVEMENTS TO THE GROUND FLOOR OF THE 'A' BLOCK [8TH STD BLOCK]AT THE CHENNAI HIGHER SECONDARY SCHOOL IN DN-174,UT-40A ,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/0143,Buildings,Completed,NN-ADYAR,174,970000,"IMPROVEMENTS TO THE FRIST FLOOR OF THE 'A' BLOCK [8TH STD BLOCK]AT THE CHENNAI HIGHER SECONDARY SCHOOL IN DN-174,UT-40A ,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/0145,Buildings,Completed,NN-ADYAR,174,955000,"RAISING THE COMPOUND WALL (WEST AND NORTH SIDE) THE CHENNAI HIGHER SECONDARY SCHOOL AT MADUVANKARAI AT FIVE FURLONG ROAD IN DN-174,UT-40A ,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/0146,Buildings,Completed,NN-ADYAR,174,685000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND RAISING THE COMPOUND WALL AT SOUTH SIDE OF CHENNAI HIGHER SECONDARY SCHOOL IN MADUVINKARAI AT FIVE FUR LONG ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/0185,Buildings,Completed,NN-ADYAR,182,970000,"CONSTRUCTION OF MULTIPURPOSE HALL AT THIRUVEETHI AMMAN KOIL STREET(SHOP NO-1) IN DIVISION-182,UNIT,38, ZONE-13.(M.L.A SCHEME FUND)",MLACDS,13,2015-16,2017-18 NN/2015-16/0221,Buildings,Completed,NN-ADYAR,182,970000,"CONSTRUCTION OF MULTIPURPOSE HALL AT THIRUVEETHI AMMAN KOIL STREET(SHOP NO-2) IN DIVISION-182,UNIT,38, ZONE-13.(M.L.A SCHEME FUND)",MLACDS,13,2015-16,2017-18 NN/2015-16/0263,Buildings,Completed,NN-ADYAR,181,970000,"CONSTRUCTION OF MULTIPURPOSE HALL AT MARUDEESHWARAR NAGAR ,THIRUVANMIYUR IN DIVISION-181,UNIT,38, ZONE-13.(M.L.A SCHEME FUND)",MLACDS,13,2015-16,2016-17 NN/2015-16/0269,Buildings,Completed,NN-ADYAR,181,970000,"CONSTRUCTION OF MULTIPURPOSE HALL AT MUTHULAKSHMI STREET ,LAKSHMIPURAM IN DIVISION-181,UNIT,38, ZONE-13.(M.L.A SCHEME FUND)",MLACDS,13,2015-16,2016-17 NN/2015-16/0318,Buildings,Completed,NN-ADYAR,178,143000,"Provision of room for Public E- Seva in Unit Office 39 , Div 178 , Zone XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/0375,Buildings,Completed,NN-ADYAR,180,875000,"IMPROVEMENTS AND WATER SUPPLY , DRAINAGE ARRANGEMENTS TO CPS AT PERUMAL KOIL STREET IN DIV-180,U-39,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/0383,Buildings,Completed,NN-ADYAR,180,900000,"IMPROVEMENTS AND WATER SUPPLY , DRAINAGE ARRANGEMENTS TO CHSS AT PEELIAMMAN KOIL STREET IN DIV-180,U-39,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/0533,Roads,Completed,NN-ADYAR,180,749000,"Restoration of Road Cut at V.V KOIL STREET,TARAMANI (From 100FT ROAD TO T.K.KABALI STREET CHAINAGE 0m to 265m (made by TANTRANSCO TNEB Laying of 230 KV 1X1200 SQ.MM UG CABLE) in Dn 180, Unit 39, Zone 13.",Deposit Works,13,2015-16,2016-17 NN/2015-16/0534,Roads,Completed,NN-ADYAR,180,719000,"Restoration of Road Cut at V.V KOIL STREET,TARAMANI (From T.K.KABALI STREET TO CSIR ROAD CHAINAGE 265m to 515m (made by TANTRANSCO TNEB Laying of 230 KV 1X1200 SQ.MM UG CABLE) in Dn 180, Unit 39, Zone 13.",Deposit Works,13,2015-16,2016-17 NN/2015-16/0535,Roads,Completed,NN-ADYAR,180,544000,"Restoration of Road Cut at KAMARAJ NAGAR 1ST MAIN ROAD AND CROSS ROAD (From WEST AVENUE TO L.B ROAD CHAINAGE 0m to 190m (made by TANTRANSCO TNEB Laying of 230 KV 1X1200 SQ.MM UG CABLE) in Dn 180, Unit 39, Zone 13.",Deposit Works,13,2015-16,2017-18 NN/2015-16/0654,Buildings,Completed,NN-ADYAR,170,982000,"Providing Garbage Bin Platform in Various Street in Div 170 , Unit 40 A , Zone XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/0655,Buildings,Completed,NN-ADYAR,170,998000,"Improvement of Treatment plant Bay in Slaughter House in Div 170 , Unit 40 A, Zone XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/0656,Buildings,Completed,NN-ADYAR,178,997000,"Improvement to Ground Floor in Unit office of Storage Room , Chairman Room, Tax Collector Room , Electrical Room in Div 178, Unit 39, Zone XIII.",Own Sources,13,2015-16,2017-18 NN/2015-16/0821,Buildings,Completed,NN-ADYAR,182,568000,"Providing Water Supply arrangement and Greenery to CHSS at Bharathidasan Street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/0826,Playfields,Completed,NN-ADYAR,177,775000,"REPAIRS AND IMPROVEMENTS TO THE BADMINTON COURT AT SHAWDOS COLONY IN DN-177,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/0827,Buildings,Completed,NN-ADYAR,182,378000,"Construction of Disabled Public Convenience at ECR Road and Thiruveethiamman Koil Street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/0828,Buildings,Completed,NN-ADYAR,176,886000,"Construction of Disabled Public Convenience (5 Nos) at Arunachalapuram Main Road, Kakkan Colony, Thiruvalluvar Nagar, Urur Kuppam in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/0829,Playfields,Completed,NN-ADYAR,177,569000,"IMPROVEMENTS TO PLAY FIELD AT ANDAL NAGAR 2ND MAIN ROAD IN DN-177,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/0831,Playfields,Completed,NN-ADYAR,177,525000,"IMPROVEMENTS TO PLAY FIELD AT TELEPHONE COLONY IN DN-177,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/0834,Playfields,Completed,NN-ADYAR,177,956000,"IMPROVEMENTS TO CHILDRENS PLAY FIELD AT RAMAKRISHNA NAGAR 3RD MAIN ROAD IN DN-177,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/0837,Playfields,Completed,NN-ADYAR,177,781000,"IMPROVEMENTS TO CHILDRENS PLAY FIELD AT LAKSHMI HYGREEVA NAGAR 4TH CROSS STREET IN DN-177,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/0865,Buildings,Completed,NN-ADYAR,172,206000,"Providing eSeva Centre at New Street in Dn-172, Unit-40, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/0951,Buildings,Completed,NN-ADYAR,171,300000,"PROVIDING TOILET FACILITY FOR THE DIFFERENTLY ABLE PEOPLE IN THE EXISTING PUBLIC CONVENIENCES AT LDG ROAD, GANDHIMANDAPAM, VELACHERY - HALDA CHILDREN PARK AND RICHARDS PARK IN DIVISION 171, UNIT 40, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/0978,Buildings,Completed,NN-ADYAR,170,994000,"Improvement of Slaughter Area Building in Slaughter House in Div 170 , Unit 40 A, Zone XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/0983,Buildings,Completed,NN-ADYAR,176,340000,"Providing eSeva Centre at Shastri nagar 8th Cross street in Dn-176, Unit-38, Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/10089,Footpath,Completed,NN-ADYAR,175,998000,Improvements to Footpath at Gandhi Nagar 4th Main Road in Dn-175 Unit-40 Zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/10108,Roads,Completed,NN-ADYAR,179,998000,"Proposed Fixing of Street name Boards using stainless steel pipe and Retro Reflective streets in Dn-179,Unit- -39, Zone - 13",Own Sources,13,2015-16,2016-17 NN/2015-16/10118,Playfields,Completed,NN-ADYAR,179,94000,"Repair works to Compound Wall for Children's Play Ground at Seethapathy Nagar 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/10122,Roads,Completed,NN-ADYAR,179,610000,"Attending Cement Concrete patch work at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/10153,Storm Water Drain,Completed,NN-ADYAR,181,920000,providing rainwater harvesting in division 181.,Own Sources,13,2015-16,2016-17 NN/2015-16/10157,Buildings,Completed,NN-ADYAR,181,1291000,"LAYING CEMENT CONCRETE ROAD AT MARUTHUPANDIYAN STREET IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/10173,Storm Water Drain,Completed,NN-ADYAR,170,386000,PROPOSED CONSTRUCTION OF STORM WATER DRAIN CROSSING ROADS AT POOMAGAL MAIN ROAD AND POOMAGAL 3RD STREET IN DN-170 UNIT-40 A ZONE-13,Own Sources,13,2015-16,2017-18 NN/2015-16/10252,Buildings,Completed,NN-ADYAR,180,985500,"Providing Retro Reflection stainless steel street name board at MGR street, Karunanithi street and Thamirabharani street in Division - 180, Unit - 39, Zone - 13",Own Sources,13,2015-16,2017-18 NN/2015-16/10253,Buildings,Completed,NN-ADYAR,180,999000,Construction of Revetment using Random Rubble Masonry to Pond at tharamani Bus Stand Dn- 180 Unit -39 Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/10254,Buildings,Completed,NN-ADYAR,180,947000,"Improvements to footpath and Tharamani Bus Shelter at Junction of Peeliyamman Koil Street in Dn 180, Unit 39, Zone 13. (UNDER COUNCILOR SCHEME WORK).",Own Sources,13,2015-16,2016-17 NN/2015-16/10258,Buildings,Completed,NN-ADYAR,181,991000,"PROVIDING WALKING AROUND THE POND AT JUNCTION OF PEELIYAMMAN KOIL STREET IN DN-180, UNIT-39, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/10278,Parks,Completed,NN-ADYAR,182,925000,"Improvements to Park at Thiruvalluvar Nagar 2nd Avenue in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/10290,Roads,Completed,NN-ADYAR,181,1291000,"LAYING OF CEMENT CONCRETE ROAD USING M30 GRADE OF CONCRETE AT YAMUNA STREET IN DIVISION - 181,UNIT-38, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/10291,Buildings,Completed,NN-ADYAR,174,208000,"DEMOLITION OF EXISTING BUILDING OF DIVISIONAL OFFICE 174 AT FIVE FURLONG ROAD IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/10294,Buildings,Completed,NN-ADYAR,170,733000,"IMPROVEMENTS TO PUBLIC CONVEYENCE AT REDDY STREET IN DN-170,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/10304,Buildings,Completed,NN-ADYAR,180,920000,"Maintenance to Amma Unavagam, Public Convenience at Taramani and Pammal Nallathambi Street, Repairs to School Building & Dispensary in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/10358,Parks,Completed,NN-ADYAR,182,711000,"Improvements to Park at Kannappa Nagar in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/1060,Buildings,Completed,NN-ADYAR,172,979000,"Providing Computer Lab to Chennai High School and Improvements to Chennai Primary School at New Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1064,Buildings,Completed,NN-ADYAR,176,712000,"Construction of Disabled Public Convenience (4 Nos) at 6th Avenue near Fish Market, Beant Avenue, Kabali Thottam, Venkateshwara Nagar 5th Street in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/11459,Footpath,Completed,NN-ADYAR,173,565000,"Improvements to Footpath and Providing water table at Sathya Dev Avenue in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/11460,Roads,Completed,NN-ADYAR,173,592000,"Attending Patch work to Damaged portions BCCMP 40mm thick by paver finisher at M.R.C. Nagar Main Road in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/11462,Roads,Completed,NN-ADYAR,175,285000,Construction of Compound wall and Providing Barricading arrangements for water screen show Adyar River and Providing Barricading arrangements at Elliot's Beach for Dome show related to Global Investors Meet 2015 in Zone-13.,Own Sources,13,2015-16,2016-17 NN/2015-16/11463,Roads,Completed,NN-ADYAR,175,335000,"Improvements to Footpath at D.D. Road (Malar Hospital side) in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1150,Parks,Completed,NN-ADYAR,181,53000,"OUTSOURCING MAINTENANCE OF TIGAR VARATHACHARI STREET PARK(6 MONTH) IN DIV-181,UNIT-38,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/1151,Parks,Completed,NN-ADYAR,181,89000,"ANNUAL OUTSOURCING MAINTENANCE OF GANGAI STREET PARK AT KALASHETHRA COLCNY IN DIV-181,UNIT-38,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/1152,Parks,Completed,NN-ADYAR,181,67000,"ANNUAL OUTSOURCING MAINTENANCE OF C.G.O.COLONY PARK AT THIRUVANMIYUR IN DIV-181, UNIT-38,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/1153,Parks,Completed,NN-ADYAR,181,68000,"ANNUAL OUTSOURCING MAINTENANCE O F MAHALAKSMI AVENUE PARK AT(6 MONTH) KALASHETHRA COLONY IN DIV-181,UNIT-38,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/11672,Footpath,Completed,NN-ADYAR,172,655000,"Providing Black and White Washing Footpath Kerbs for Global Investor Meeting at Gandhi Mandapam Road and Sardar Patel Road in Dn-172, Unit-40, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/1169,Roads,Completed,NN-ADYAR,179,999000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Dhandeeswaram Nagar 10th Main Road, Dhandeeswaram 4th Avenue, Seethapathy Nagar Extn., Bharathi Street, Rajambal Street, Rani Street, Gandhi Road, New Colony 2nd Street & New Colony Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/11691,Footpath,Completed,NN-ADYAR,174,715000,"Defacing the Walls and Greenery improvements works in Center median at Velachery Main road in Dn-174, Unit-40A, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/11692,Footpath,Completed,NN-ADYAR,174,655000,"Painting black and white for footpaths, Center median and trees at Velachery main road in Dn 174, Unit 40(A), Zone-13. In the view of Global Investors Meet 2015 in Chennai.",Own Sources,13,2015-16,2016-17 NN/2015-16/11695,Footpath,Completed,NN-ADYAR,173,960000,"Attending Patch work to Damaged portions BCCMP 40mm thick by paver finisher at Thandavarayan street in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/11699,Footpath,Completed,NN-ADYAR,181,1598000,"LAYING CEMENT CONCRETE ROAD AT RAJARAJAN STREET IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/1172,Buildings,Completed,NN-ADYAR,179,161000,"Providing facilities for disabled person in Public Convenience at Thiruveethiamman Koil Street in Dn 179, Unir 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1182,Buildings,Completed,NN-ADYAR,179,999000,"Proposed fixing of Street Name Boards using Stainless Steel pipe and Retro Reflective Sheet at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1190,Roads,Completed,NN-ADYAR,171,961000,"CONSTRUCTION OF CONCRETE PLATFORM FOR GARBAGE BIN PLACEMENT IN VARIOUS STREETS IN DIVISION 171, UNIT 40, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1203,Buildings,Completed,NN-ADYAR,173,977000,"Providing Shed, Water Supply arrangement and Improvements for Noonmeal Centre Building at Kumarasamy Raja Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1206,Buildings,Completed,NN-ADYAR,179,998000,"Proposed Construction of Modern Stainless Steel Bus Shelter - I at Velachery - Tambaram Main Road (Jn. of Vijaya Nagar Bus Terminus, Eastern Side) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1208,Buildings,Completed,NN-ADYAR,179,998000,"Proposed Construction of Modern Stainless Steel Bus Shelter - II at Velachery - Tambaram Main Road (Jn. of Vijaya Nagar Bus Terminus, Eastern Side) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/12177,Roads,Completed,NN-ADYAR,173,944000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF AMBEDKAR MANIMANDAPAM TO JN OF AYYAPPAN TEMPLE AT Dr.D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/12179,Roads,Completed,NN-ADYAR,173,922000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF AYYAPPAN TEMPLE TO JN OF BANK OF BARODA AT Dr.D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/12180,Roads,Completed,NN-ADYAR,173,915000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF BANK OF BARODA TO JN OF T.T.K.HOUSE AT Dr.D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/12181,Roads,Completed,NN-ADYAR,173,917000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF T.T.K.HOUSE TO JN OF KARPAGAM AVENUE AT Dr.D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/12182,Roads,Completed,NN-ADYAR,173,958000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF KARPAGAM AVENUE TO JN OF M.R.C.CENTRE AT Dr.D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/12184,Roads,Completed,NN-ADYAR,173,924000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF M.R.C.CENTRE TO JN OF SCRB TAMILNADU AT Dr.D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/12185,Roads,Completed,NN-ADYAR,173,921000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAIL FOR CENTRE MEDIAN JN OF SCRB TAMILNADU TO JN OF FORESHORE ESTATE AT Dr.D.G.S.DINAKARAN SALAI IN DN-173, U- 40, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/12186,Buildings,Completed,NN-ADYAR,173,840000,"Providing Wall Painting and Sign Boards at Various Streets in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/12187,Buildings,Completed,NN-ADYAR,173,111000,"Improvements to Guest House at Dr.DGS Dinakaran Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/12188,Buildings,Completed,NN-ADYAR,173,232000,"Improvements to Roadside Park at South Kesava Puram in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1237,Roads,Completed,NN-ADYAR,171,988000,"Repair & Maintenance of Culvert at Jothiammalnagar, Service yard at Lorry Station Zone-13, Ward Councillor Office Room and Providing SS Name Board in five streets in Dn-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1238,Buildings,Completed,NN-ADYAR,178,322000,"Providing facilities for disabled person in Public Convenience at Vijaya Nagar Bus Terminus in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1251,Roads,Completed,NN-ADYAR,171,843000,"IMPROVEMENTS AND REPAIR WORKS TO THE PUBLIC CONVENIENCE AT SATHYA NAGAR IN DIVISION 171, UNIT 40, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/12626,Buildings,Completed,NN-ADYAR,181,980000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT VARIOUS STREETS IN DIVISION 181 ,UNIT 38, ZONE 13.UNDER COUNCILLOR FUND.AT KALAKSHETRA COLONY.","Loans, Grants And Own Sources",13,2015-16,2016-17 NN/2015-16/12661,Buildings,Completed,NN-ADYAR,181,128000,DEMOLITION OF DILAPIDATED BUILDING AT MALAVIYA AVENUE THIRUVANMIYUR IN DIVISION 181 UNIT 38 ZONE 13.,Own Sources,13,2015-16,2017-18 NN/2015-16/1270,Roads,Completed,NN-ADYAR,179,999000,"Raising & Lowering 45cm or 60cm dia cast iron manhole frames and door for CMWSSB Sewer manholes at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/12737,Buildings,Completed,NN-ADYAR,171,982000,"PAINTING FOOTPATH KERB AT ANNA SALAI, SARDAR PATEL ROAD, TALUK OFFICE ROAD, PAINTING KERBS IN FLYOVER BRIDGES NEAR IIT MADRAS, ADYAR SIGNAL AND DEFACING THE WALL WRITINGS & PAINTING AT ANNA SALAI, SARDAR PATEL ROAD, TALUK OFFICE ROAD IN VIEW OF GLOBAL INVESTORS MEET AT CHENNAI.",Own Sources,13,2015-16,2016-17 NN/2015-16/12839,Buildings,Completed,NN-ADYAR,170,979000,"IMPROVEMENTS TO THE GASIFIER ROOM AT ARULAYAMPET BURIAL GROUND IN DN-170,UT-40A ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/12840,Buildings,Completed,NN-ADYAR,170,762000,"PROVIDING MAIN GATE AND PAINTING THE OUTER WALLS OF THE CHENNAI HIGHER SECONDARY SCHOOL AT LITTLE MOUNT IN DN-170,UT-40A ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/12841,Buildings,Completed,NN-ADYAR,170,980000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE HEALTH POST AT V G P SALAI AND CHENNAI HIGHER SECONDARY SCHOOL AT CHINNAMALAI IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1291,Buildings,Completed,NN-ADYAR,172,255000,"Providing Weathering course to Chennai High School at New Street in Dn-172, Unit-40, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/13051,Storm Water Drain,Completed,NN-ADYAR,179,948000,"Construction of Side Drain in Size of 600x750mm at Dhandeeswaram Nagar 12th Cross Street (from the Jn. of Tansi Nagar 6th Street to Jn. of Vealchery - Taramani 100 feet road) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/13712,Buildings,Completed,NN-ADYAR,176,953000,"Imrpovement to Footpath at Besant Nagar 3rd,4th Main Road, 5th Main Road, 5th Avenue, Sastri Nagar 4th cross Street Avenue Road in Dn-176, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/13720,Electrical,Completed,NN-ADYAR,178,993000,"Additional and rewiring of Unit-39 in velachery div-178,Zone-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/13724,Buildings,Completed,NN-ADYAR,177,980000,"IMPROVEMENTS TO THE MULTIPURPOSE HALL AT AMBEDKAR NAGAR 11TH STREET IN DN-177,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/13729,Buildings,Completed,NN-ADYAR,172,1987000,"Construction of Compound Wall and Cement Concrete Tiles flooring around New Shopping Complex Building at Eari Karai Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/13849,Electrical,Completed,NN-ADYAR,179,345400,"Provosion of New Service connection in E Toilet, Namme Toilet, Buriel Ground and Additional wiring of Amma Unavagam in velachery div-179, Zone-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/13946,Playfields,Completed,NN-ADYAR,181,920000,improvements and repair works to playgroung at vaigai street thiruvanmiyur in division 181.,Own Sources,13,2015-16,2017-18 NN/2015-16/13952,Buildings,Completed,NN-ADYAR,178,765000,"Improvement to Existing Toilet in Brahamin Street in Div 178 , Unit 39, Zone XIII.",Own Sources,13,2015-16,2019-20 NN/2015-16/13954,Buildings,Completed,NN-ADYAR,178,765000,"Improvement to Existing Toilet in Orandiamman Street in Div 178 , Unit 39, Zone XIII.",Own Sources,13,2015-16,2019-20 NN/2015-16/13986,Storm Water Drain,Completed,NN-ADYAR,178,991000,"Demolision and Construction and raising of Cover Slab in Throwpathy Amman 5Th Street in Div 178 , Unit 39, Zone XIII.( 0 to 80 M )",Own Sources,13,2015-16,2017-18 NN/2015-16/14153,Storm Water Drain,Completed,NN-ADYAR,170,900000,"DESILTING OF CANAL CLEANING @ REDDY GARDEN AND GUINDY ESTATE IN DN.170,UNIT-40A ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/14180,Buildings,Completed,NN-ADYAR,172,402000,"Improvements to Public Convenience at Earikarai Street Near Burial Ground, Ponniamman Koil Street & Kotturpuram Chitra Nagar in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/14201,Buildings,Completed,NN-ADYAR,180,995000,"CONSTRUCTION OF MULTI PURPOSE HALL-1 AT ANNA THIDAL ROAD,THANTHAI PERIYAR NAGAR,THARAMANI IN DN-180,UNIT-39,ZONE-13. UNDER THE SCHEME OF MLA FUND",MLACDS,13,2015-16,2017-18 NN/2015-16/14268,Storm Water Drain,Completed,NN-ADYAR,174,450000,"RAISING AND LOWERING THE MANHOLE DOOR AT VARIOUS STREETS IN DN-174,UT-40A,ZONE-13.(MOSQUE COLONY 1ST AND 17 TH STREET AND VARIOUS STREETS)",Own Sources,13,2015-16,2016-17 NN/2015-16/14275,Buildings,Completed,NN-ADYAR,180,995000,"CONSTRUCTION OF MULTIPURPOSE HALL-2 ANNA THIDAL ROAD, THANTHAI PERIYAR NAGAR, THARAMANI IN DN-180, UNIT-39, ZONE-13 UNDER SCHEME OF MLA FUND",MLACDS,13,2015-16,2017-18 NN/2015-16/14296,Buildings,Completed,NN-ADYAR,181,968000,IMPROVEMENTS AND RPAIR WORKS TO BURAIL GROUND AT RAJA SRINIVASA NAGAR IN DIVISION 181,Own Sources,13,2015-16,2017-18 NN/2015-16/14890,Storm Water Drain,Completed,NN-ADYAR,179,916000,"Construction of Side Drain in Size of 600x600mm at Tansi Nagar 7th Street (from the Jn. of Tansi Nagar 3rd Street to Jn. of Tansi Nagar 5th Street) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/15098,Roads,Completed,NN-ADYAR,175,980000,"Attending Patch work to Damaged portions BCCMP 40mm thick by paver Finisher at Kamarajar Avenue 1st, 2nd street, Venkatrathinam nagar, Kasthuri bai nagar 3rd main road and Gandhi Nagar 1st cross street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/15105,Roads,Completed,NN-ADYAR,173,740000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at D.G.S. Dinakaran Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/15122,Storm Water Drain,Completed,NN-ADYAR,175,897000,"Construction of Silt catch pit to Storm Water Drain at Various Streets in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1528,Parks,Completed,NN-ADYAR,178,147000,"MAINTENANCE OF PARK FOR 6 MONTHS AT A.G.S. COLONY 4TH MAIN ROAD (Jn. of 4th Cross Street) IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1531,Parks,Completed,NN-ADYAR,178,147000,"MAINTENANCE OF PARK FOR 6 MONTHS AT A.G.S. COLONY 4TH MAIN ROAD IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1533,Parks,Completed,NN-ADYAR,180,67000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 13TH WEST STREET, KAMARAJAR NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1534,Parks,Completed,NN-ADYAR,180,109000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 2ND WEST STREET, KAMARAJAR NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1536,Parks,Completed,NN-ADYAR,180,132000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 4TH WEST STREET, KAMARAJAR NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/15446,Roads,Completed,NN-ADYAR,176,996000,PROVIDING STREET FURNITURES AT SASTRI NAGAR 5 TH CROSS AND VARIOUS STREETS (WARD COUNCILOR FUND) IN DIVISION - 176 UNIT - 38 ZONE - 13,Own Sources,13,2015-16,2016-17 NN/2015-16/15463,Roads,Completed,NN-ADYAR,176,995000,PROVIDING STREET FURNITURES AT BESANT NAGAR 8 TH CROSS AND VARIOUS STREETS (WARD COUNCILOR FUND) IN DIVISION - 176 UNIT - 38 ZONE - 13,Own Sources,13,2015-16,2016-17 NN/2015-16/15536,Roads,Completed,NN-ADYAR,182,990000,"PROVIDING STREET FURNITURES AT AVVAI NAGAR AND VARIOUS STREETS(WARD COUNCILOR FUND) IN DN-182,UNIT-38,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/15555,Buildings,Completed,NN-ADYAR,172,985000,Proposed Construction of Kerosene Pump Room and Electrical work for shops at Lake View Road in Dn-172 U-40 Z-13,Own Sources,13,2015-16,2017-18 NN/2015-16/15657,Buildings,Completed,NN-ADYAR,170,998000,"Providing catch silt pit and FRC doors at Labour Colony Main Road, Gandhi Nagar,Ambal Nagar ,Munusamy Street and Dhanakodi Raj Street in Dn 170,Unit-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/15906,Buildings,Completed,NN-ADYAR,170,586000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AROUND TNEB TRANSFORMER AT POONAMALEE ROAD (INFRONT OF C.M.S SCHOOL) AND CART TRACT STREET EKADUTHANGAL (OPP CLASSIC ENGINEERING COMPANY) DIV 170, UNIT 40A,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/15943,Roads,Completed,NN-ADYAR,170,375000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE BURIAL GROUND AT ARULAYAMPET AND GUINDY ESTATE IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/15953,Electrical,Completed,NN-ADYAR,175,559000,"Providing GYM Materials With Annual Maintenance Cost for the Materials at Thiruvengadam Street in Dn-175, Unit-40 Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/15957,Buildings,Completed,NN-ADYAR,175,823000,"Providing GYM Materials With Annual Maintenance Cost for the Materials at Venkatarathinam Nagar in Dn-175, Unit-40 Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/15960,Roads,Completed,NN-ADYAR,182,982000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Thiruveethiamman Koil Street, 4th Seaward road, Kuppam Beach Road, Pillaiyar Koil Street in Div - 182, U - 38, Zone - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16070,Footpath,Completed,NN-ADYAR,181,246000,"Improvement to Footpath at Coastal Road and Various Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16139,Road Cut,Completed,NN-ADYAR,182,640000,"Attending Patch Work at Balakrishna Road junction of Kuppam Beach Road to 4th Sea Ward Road in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/16391,Buildings,Completed,NN-ADYAR,172,994000,"Proposed construction of light duty steel truss roofing work and Flooring at new shopping complex buildings Erikarai street, Dn172, U 40, Z13.",Own Sources,13,2015-16,2017-18 NN/2015-16/16464,Storm Water Drain,Completed,NN-ADYAR,176,971000,"Proposed Rain Water Harvesting at Various Street in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16495,Storm Water Drain,Completed,NN-ADYAR,174,270000,"PROVIDING VERTICAL GRATING ARRANGEMENTS TO THE STROM WATER DRAIN AT VELECHERY MAIN ROAD AND FIVE FUR LONG IN DN-174 UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/16509,Roads,Completed,NN-ADYAR,182,999000,"PROVIDING STREET FURNITURES AT THIRUVALLUVAR NAGAR 1ST AND 2ND MAIN ROAD AND KAMARAJ NAGAR 3RD AND 4TH MAIN ROAD( WARD COUNCILOR FUND) IN DIVISION 182, UNIT 38, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16521,Parks,Completed,NN-ADYAR,175,106000,"Water supply and Drainage connection Arrangements to e-Toilet at Indira nagar 4th cross street Park in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16522,Roads,Completed,NN-ADYAR,175,995000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D. Road, Adyar River (EARTH FILLING-1) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/16534,Buildings,Completed,NN-ADYAR,175,425000,"PROVIDING GYM MATERIALS WITH ANNUAL MAINTENANCE COST FOR THE MATERIALS AT GANDHI NAGAR CANAL BANK ROAD IN DN-175, UNIT-40, ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/16727,Buildings,Completed,NN-ADYAR,175,680000,"Repairs and Improvements works to Regional Joint Commisioner office Rest Room, and Town Planning Execiutive Engineer Office at Dr. Muthulakshmi Salai in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16748,Roads,Completed,NN-ADYAR,170,999000,"Attending the patches at car track road,poonamaliee road,Gandhi nager main road,poomagal road,kalaimagal nager 2nd main road in div-170,Unit-40(A),Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/16749,Roads,Completed,NN-ADYAR,170,924000,"Attending the patches at Reddy street,Hospital road,V.G.P salai,Alandhur service road in div-170,Unit-40(A),Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/16754,Buildings,Completed,NN-ADYAR,171,945000,"Providing Rain Water Harvesting at Srinagar Colony, Wast CIT Nagar, LDG Road, Penpet, Railway Border 1st Street, Ranjith Road, Model Autment Road, Thomas Nagar in Dn-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16790,Roads,Completed,NN-ADYAR,179,259000,"Providing Interlocking Blocks the road side berms at Seva Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16793,Roads,Completed,NN-ADYAR,179,481000,"Providing Interlocking Blocks the road side berms at Seshadripuram Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16796,Roads,Completed,NN-ADYAR,179,440000,"Providing Interlocking Blocks the road side berms at Seva Nagar 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16798,Roads,Completed,NN-ADYAR,179,750000,"Providing Interlocking Blocks the road side berms at Seva Nagar 4th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16801,Roads,Completed,NN-ADYAR,179,212000,"Providing Interlocking Blocks the road side berms at Seva Nagar Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16805,Roads,Completed,NN-ADYAR,179,956000,"Formation of Road at Kambar Street Extension Chainage 0 - 73m) (Connecting to MRTS Railway Station) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16816,Buildings,Completed,NN-ADYAR,170,995000,"Proposed construction of compound wall, Platform ,water arrangements to e-toilet at Nagi Reddy Garden in div 170, Unit-40a",Own Sources,13,2015-16,2016-17 NN/2015-16/16828,Roads,Completed,NN-ADYAR,182,912000,"Attending Flood damaged portions to BCCMP 40mm thick by paver finisher at Vaalmegi nagar 1st sea ward road in DN-182, Unit-38, Zone- XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/1695,Footpath,Completed,NN-ADYAR,173,498000,"Improvements to Footpath at Thiruveedhiamman Koil Street (from the junction of R.K.Nagar 2nd Main Road to Sringeri Mutt Road) in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16981,Buildings,Completed,NN-ADYAR,176,978000,"Providing Face lifting PC at Besant Nagar 6th Avenue Elliots Beach in Dn-176, Uni-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/16985,Roads,Completed,NN-ADYAR,182,900000,"Attending Patch work to Damaged portions BCCMP 40mm thick by paver Finisher at Various Streets in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17062,Roads,Completed,NN-ADYAR,180,987000,"Attending Patch work to Damaged portions BCCMP 40mm thick by paver Finisher at Kamarajar Nagar (west) 1st Main Road, Kamarajar Nagar 2nd Main Road, Judges Avenue and Anna Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17085,Roads,Completed,NN-ADYAR,182,980000,"Proposed Rain Water Harvesting at New Beach road, 2nd Seaward road, Balakrishna road, ECR road in Division 182, Unit 38, Zone-XIII",Own Sources,13,2015-16,2018-19 NN/2015-16/17128,Storm Water Drain,Completed,NN-ADYAR,179,411000,"Supplying and laying of PVC pipe line of 160mm dia and Providing silt catch pit work along Bhuvaneswari Nagar 1st Main Road in Div -179, Unit 39, Zone - XIII",Own Sources,13,2015-16,2019-20 NN/2015-16/17171,Storm Water Drain,Completed,NN-ADYAR,179,634000,"Construction of Side Drain in size of 600x750 mm along V.G.P. Selva Nagar Extn., 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17179,Storm Water Drain,Completed,NN-ADYAR,179,760000,"Construction of Side Drain in size of 600x750 mm along V.G.P. Selva Nagar Extn., 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17181,Storm Water Drain,Completed,NN-ADYAR,179,760000,"Construction of Side Drain in size of 600x750 mm along V.G.P. Selva Nagar Extn., 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17264,Parks,Completed,NN-ADYAR,178,124000,"MAINTENANCE OF PARK FOR 6 MONTHS AT A.G.S. COLONY 4TH MAIN ROAD IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17265,Parks,Completed,NN-ADYAR,178,123000,"MAINTENANCE OF PARK FOR 6 MONTHS AT A.G.S. COLONY 4TH MAIN ROAD (JN. OF 4TH CROSS STREET) IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17266,Parks,Completed,NN-ADYAR,180,120000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 4TH WEST STREET, KAMARAJ NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17267,Parks,Completed,NN-ADYAR,180,117000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 2ND WEST STREET, KAMARAJ NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17268,Parks,Completed,NN-ADYAR,180,58000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 13TH WEST STREET, KAMARAJ NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17269,Parks,Completed,NN-ADYAR,176,265000,"MAINTENANCE OF PARK FOR 6 MONTHS AT Dr. MUTHULAKSHMI PARK AT D.D. ROAD IN DN 176, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17271,Parks,Completed,NN-ADYAR,176,131000,"MAINTENANCE OF PARK FOR 6 MONTHS AT BESANT NAGAR 4TH AVENUE IN DN 176, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17272,Parks,Completed,NN-ADYAR,176,136000,"MAINTENANCE OF PARK FOR 6 MONTHS AT PADMANABHAN NAGAR 5TH STREET IN DN-176,UNIT- 38,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/17273,Parks,Completed,NN-ADYAR,182,86000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 43RD CROSS STREET IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17275,Parks,Completed,NN-ADYAR,182,102000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 7TH CROSS STREET IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17277,Parks,Completed,NN-ADYAR,182,112000,"MAINTENANCE OF PARK FOR 6 MONTHS AT JOURNALIST COLONY IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17280,Parks,Completed,NN-ADYAR,182,140000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 1ST AVENUE IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17283,Parks,Completed,NN-ADYAR,182,128000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 2ND AVENUE IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17285,Parks,Completed,NN-ADYAR,182,51000,"MAINTENANCE OF PARK FOR 6 MONTHS AT AIBEA NAGAR IN 182, UNIT-38, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17289,Parks,Completed,NN-ADYAR,182,88000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 69TH CROSS STREET, VALMIGI NAGAR IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17363,Storm Water Drain,Completed,NN-ADYAR,173,409000,"Laying of pipe for rain water disposal at D.G.S.Dinakaran Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2019-20 NN/2015-16/17451,Parks,Completed,NN-ADYAR,173,835000,"Out Sourcing Maintenance of Parks (6 Months) at Kamarajar Salai, East Avenue, Central Avenue, Krishnapuri, MRC Nagar, Vasantha Avenue, Sathyadev Avenue and Guest House Park in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/17498,Storm Water Drain,Completed,NN-ADYAR,170,849000,"DESILTING OF CANAL CLEANING @ GUINDY CANAL IN DN 170, UNIT 40A, ZONE -13",Own Sources,13,2015-16,2016-17 NN/2015-16/1752,Buildings,Completed,NN-ADYAR,176,3720000,"Construction of fruit and flower shop at D.D.Road in Div 176, Unit 38, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/17590,Parks,Completed,NN-ADYAR,179,364000,"Proposed Construction of Compound wall for Children's Play Ground at Park Avenue 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/17763,Parks,Completed,NN-ADYAR,172,123000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT CHITRA NAGAR, KOTTURPURAM IN DN 172, UNIT 40, ZONE 13",Own Sources,13,2015-16,2018-19 NN/2015-16/17767,Parks,Completed,NN-ADYAR,172,656000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT RIVER VIEW ROAD, KOTTURPURAM IN DN 172, UNIT 40, ZONE 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/17768,Parks,Completed,NN-ADYAR,172,166000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT DHANDAYUTHAPANI NAGAR IN DN 172, UNIT 40, ZONE 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/17770,Parks,Completed,NN-ADYAR,172,65000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT KOTTUR GARDEN 4TH MAIN ROAD (SENIOR CITIZEN PARK) IN DN 172, UNIT 40, ZONE 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/17771,Parks,Completed,NN-ADYAR,177,131000,"MAINTENANCE OF PARK FOR 6 MONTHS AT NNGO COLONY 2ND MAIN ROAD IN DN 177, UNIT 40A, ZONE 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/17772,Parks,Completed,NN-ADYAR,177,65000,"MAINTENANCE OF PARK FOR 6 MONTHS ATL.H. NAGAR 4TH CROSS STREET IN DN 177, UNIT 40A, ZONE 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/17794,Parks,Completed,NN-ADYAR,174,194000,"Maintenance of Park for 6 months at Secretariat Colony, City Limit Road in Dn 174, Unit 40A, Zone 13",Own Sources,13,2015-16,2018-19 NN/2015-16/17969,Parks,Completed,NN-ADYAR,175,287000,"Maintenance of park at Indira nagar 4 th,cross street for six months in Dn 175,Unit 40,Zone 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/17970,Parks,Completed,NN-ADYAR,171,134000,"OUTSOURCING MAINTENANCE OF PARK AT CHINNAMALAI (HALDA JN) PARK(6 MONTH) IN DIV-171,UNIT-40,ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/18008,Roads,Completed,NN-ADYAR,181,992000,"Proposed Rain water Harvesting at Beach road,Coastel road,Muthulakshmi salai,Mahalakshmi salai,Arundel beach road,Sivagami puram in DN-181,Unit-38,Zone-13",Own Sources,13,2015-16,2018-19 NN/2015-16/18043,Roads,Completed,NN-ADYAR,175,980000,"Forming Interlocking block for parking area below Fly Over at Sardar Patel Road and Dr. Muthulakshmi salai in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18044,Buildings,Completed,NN-ADYAR,174,939000,"PROPOSED ADDITIONAL CONSTRUCTION OF FIRST FLOOR AT MULTIPURPOSE HALL IN VELACHERY MAIN ROAD KANNIGAPURAM. DVN-174, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/18049,Footpath,Completed,NN-ADYAR,175,515000,"Painting Footpath Kerbs and Centre Median at Sardar Patel Road, Dr.Muthulakshmi Salai and Kalki Krishnamoorthy Salai in Dn.175, Unit-40, Zone-13 in the view of Republic Day Celebration 2016",Own Sources,13,2015-16,2017-18 NN/2015-16/18050,Roads,Completed,NN-ADYAR,175,996000,"Forming Interlocking Block for Parking area below Fly over at Durgabai Deshmukh Road in DIV-175,UNIT-40,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18058,Buildings,Completed,NN-ADYAR,174,852000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND FLOORING AT MULTIPURPOSE HALL IN VELACHERY MAIN ROAD KANNIGAPURAM IN DN-174,U-40A,Z-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18146,Roads,Completed,NN-ADYAR,179,999000,"Providing and Laying of road with Wet mix macadam at Bharani Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18148,Culvert,Completed,NN-ADYAR,179,955000,"Desilting of 6 vent culvert (Disposal Point) in Velachery MRTS Railway Bridge, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/18149,Storm Water Drain,Completed,NN-ADYAR,179,196000,"Desilting of Storm Water Drain at Velachery - Taramani 100 feet road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/18220,Parks,Completed,NN-ADYAR,181,53000,"OUT SOURCING MAITENANCE OF TIGER VARATHACHARI STREET PARK(6 MONTH) IN DN-181, UNIT-38, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/18221,Parks,Completed,NN-ADYAR,181,68000,"ANNUAL OUT SOURCING MAITENANCE OF TIGER MAHALAKSHMI AVENUE PARK(6 MONTH) KALASHEKTRA COLONY IN DN-181, UNIT-38, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/18222,Parks,Completed,NN-ADYAR,181,67000,"ANNUAL OUTSOURCING MAINTENANCE OF C.G.E COLONY PARK IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18223,Buildings,Completed,NN-ADYAR,181,89000,"ANNUAL OUTSOURCING MAINTENANCE OF GANGAI STREET PARK AT KALAKSHETRA COLONY IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18226,Buildings,Completed,NN-ADYAR,174,657000,"IMPROVEMENTS TO THE NNMP SHED AT KANNIGAPURAM 6TH STREET IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/1835,Parks,Completed,NN-ADYAR,179,59000,"Maintenance of Park for 6 months at Bharathiyar Park, Velachery Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/18354,Roads,Completed,NN-ADYAR,170,988000,"Attending the patches at Kathipara road,Aruliyampettai main road,Aruliyampettai 1st road,reddy 3rd street in div-170,Unit-40(A),Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/18368,Roads,Completed,NN-ADYAR,175,960000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D. Road, Adyar River (EARTH FILLING-2) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18370,Roads,Completed,NN-ADYAR,175,995000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D. Road, Adyar River (EARTH FILLING-3) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18371,Roads,Completed,NN-ADYAR,175,995000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D. Road, Adyar River (EARTH FILLING-4) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18373,Roads,Completed,NN-ADYAR,175,995000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D. Road, Adyar River (EARTH FILLING-5) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18376,Roads,Completed,NN-ADYAR,175,995000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D. Road, Adyar River (EARTH FILLING-6) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18379,Roads,Completed,NN-ADYAR,175,999000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D.Road, Adyar River (EARTH FILLING& WET MIX FILLING) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18380,Roads,Completed,NN-ADYAR,175,767000,"Making arrangement on the bund to provide access,viewing area,parking area etc for water screen show at D.D. Road, Adyar River ( WET MIX FILLING) for GLOBAL INVESTERS MEET-2015 IN Dn.175, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18428,Buildings,Completed,NN-ADYAR,172,168000,"Improvements to Caretaker Room and Burning Machine area of Burial Ground at Erikarai Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/18532,Storm Water Drain,Completed,NN-ADYAR,170,995000,"PROPOSED AND CONSTRUCTION OF STORM WATER DRAIN AT POOMAGAL 3RD STREET LINK TO GANABATHY STREET IN DN-170,U-40(A),Z-13",Own Sources,13,2015-16,2017-18 NN/2015-16/18591,Buildings,Completed,NN-ADYAR,175,525000,"Providing Rain Water Harvesting at Various Streets in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1865,Buildings,Completed,NN-ADYAR,178,284600,"Outsourcing scavening work for chennai higher secondary school at rajalakshmi nagar ii main road in Division - 178, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/1867,Buildings,Completed,NN-ADYAR,179,189700,"Outsourcing scavenging work for Chennai Primary school at Udayam nagar in Division - 179, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/1868,Buildings,Completed,NN-ADYAR,178,189700,"Outsourcing scavenging works for Chennai Primary School at Rajalakshmi Nagar II main road in Division - 178, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/1870,Buildings,Completed,NN-ADYAR,180,284600,"Outsourcing scavenging work for Chennai Primary School at Perumal Koil street in Division - 180, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/18702,Roads,Completed,NN-ADYAR,170,650000,"FORMING THE ROAD WITH WETMIX AT PILLAYAR KIOL 3rd,4th,5th ST AND BALAJI NAGAR 1st MAIN ROAD AND BALAJI NAGAR 3RD CROSS ST IN DN-170,UT-40a,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18703,Roads,Completed,NN-ADYAR,170,640000,"FORMING THE ROAD WITH WETMIX AT ACCHUDAN NAGAR 2nd ST,GANAPATHI NAGAR 1st ST AND NEHRU ST IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18704,Roads,Completed,NN-ADYAR,170,660000,"FORMING THE ROAD WITH WETMIX AT KATTABOMAN ST,RAJIV GANDHI NAGAR,ACCHUDAN NAGAR 1st ST AND PILLAYAR KOIL 2nd ST IN DN-170,UT-40a,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/1871,Buildings,Completed,NN-ADYAR,180,284600,"Outsourcing scavenging work for Chennai Higher Secondary School at Bharathiar street (Taramani) in Division - 180, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18765,Buildings,Completed,NN-ADYAR,181,875000,"ATTENDING OF CEMENT CONCRETE PATCHES AT DR,RADAKRIHNAN SALAI, ARUNDEL BEACH ROAD, T M MASITRY ROAD AND COASTEL ROAD,IN DIVISION 181 UNIT 38 ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/18766,Roads,Completed,NN-ADYAR,181,740000,"ATTENDDING PATCHES WITH GSP AND WMM AT ANNA STREET, VALMIKI STREET, PILLIYAR KOIL STREET KALASHTERA ROAD IN DIVISION 181 UNIT 38 ZONE 13",Own Sources,13,2015-16,2017-18 NN/2015-16/18778,Roads,Completed,NN-ADYAR,172,547000,"Attending Patch work using Wet Mix Macadam for the low lying/ undulated portion at West canal bank Road opposite to Kotturpuram Railway Station in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18779,Buildings,Completed,NN-ADYAR,181,600000,"REPAIR WORKS TO CORPORTION SCHOOLS AT OODAIKUPPAM PRIMARY SCHOOL, GANDHIGRAMAM SCHOOL AND THIRUVANMIYUR KUPPAM PRIMARY SCHOOL EFFECTED BY MONSOON RAIN IN DIVISION 181 UNIT 38 ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/18800,Roads,Completed,NN-ADYAR,179,798000,"Raising of road with Wet mix macadam at V.G.P. Selva Nagar 1st Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18801,Roads,Completed,NN-ADYAR,179,520000,"Raising of road with Wet mix macadam at V.G.P. Selva Nagar 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18802,Roads,Completed,NN-ADYAR,179,68000,"Raising of road with Wet mix macadam at Bhuvaneswari Nagar 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18803,Roads,Completed,NN-ADYAR,179,245000,"Raising of road with Wet mix macadam at Bhuvaneswari Nagar 3rd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18806,Roads,Completed,NN-ADYAR,179,423000,"Raising of road with Wet mix macadam at Balamurugan Nagar 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18808,Roads,Completed,NN-ADYAR,179,643000,"Raising of road with Wet mix macadam and bituminous macadam at Seethram Nagar 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18809,Roads,Completed,NN-ADYAR,179,869000,"Attending patch work with wet mix macadam at various Street in Div-179, unit-39, Zone-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/18811,Roads,Completed,NN-ADYAR,179,948000,"Attending patch work with Bituminous course at various streets in Dn-179,U-39,Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/18819,Parks,Completed,NN-ADYAR,171,761000,"GREENERY IMPROVEMENT OF CENTER MEDIAN AT GANDHI MANDABAM ROAD AND KAVERI NAGAR(70 'feet) ROAD IN DIV-171 & 172,UNIT-40,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18821,Roads,Completed,NN-ADYAR,171,995000,"Painting Footpath Kerbs, Centre Median and Trees at Sardar Patel Road in Dn-171, Unit-40, Zone-13 in the view of Republic Day Celebration 2016",Own Sources,13,2015-16,2017-18 NN/2015-16/18896,Buildings,Completed,NN-ADYAR,170,766000,"Provosion of Name Board in Various Road in MTC Bus stop in Div 170,174,177,178,179 and 180 in Unit 39 and 40A, Zone - XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/18906,Buildings,Completed,NN-ADYAR,177,632000,"IMPROMENT WORK FOR COMBOUND WALL AND FLOORING AT N.N.M.P SHED IN 66 th STREET, AMBETHKAR NAGAR , VELACHERY. DVN-177, U- 40A, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18920,Roads,Completed,NN-ADYAR,176,965000,"Attending Patch work to Damaged portions BCCMP 40mm thick by paver Finisher at various street in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/18935,Buildings,Completed,NN-ADYAR,177,687000,"IMPROUMENT WORK FOR FLOORING AND COMBOUND WALL RAISING AT GYM IN 22 nd STREET, AMBETHKAR NAGAR, VELACHERY. IN DVN-177, U-40A, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18938,Buildings,Completed,NN-ADYAR,177,736000,"IMPROUMENT WORK FOR FLOORING AND COMBOUND WALL RAISING AT GYM IN 20 TH STREET, AMBETHKAR NAGAR, VELACHERY. IN DVN-177, U-40A, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18940,Buildings,Completed,NN-ADYAR,177,494000,"IMPROVEMENT WORK FOR FLOORING AND COMBOUND WALL RAISING AT GYM IN 3rd STREET, AMBETHKAR NAGAR, VELACHERY. IN DVN-177, U-40A, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18942,Buildings,Completed,NN-ADYAR,172,597000,"Improvements to Road and SWD at Karamarajar salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/18943,Buildings,Completed,NN-ADYAR,172,890000,"PROPOSED CONSTRUCTION OF WATER SUPPLY AND ELECTRICAL WORK AT MULTI PURPOSE HALL AT PONDICHERY ROAD. DN-172,U-40,Z13",Own Sources,13,2015-16,2017-18 NN/2015-16/19322,Roads,Completed,NN-ADYAR,177,271000,"Laying WMM Water Logging Area at Ganesh Nagar 2nd Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19323,Roads,Completed,NN-ADYAR,177,245000,"Laying WMM Water Logging Area at Ganesh Nagar 1st Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19324,Roads,Completed,NN-ADYAR,177,242000,"Laying WMM Water Logging Area at Joseph colony Cross Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19325,Roads,Completed,NN-ADYAR,177,190000,"Laying WMM Water Logging Area at Joseph colony 1st Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19326,Roads,Completed,NN-ADYAR,177,522000,"Laying WMM Water Logging Area at Nethaji colony 1st,2nd & 3rd cross street in dn-177 U-40a Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19327,Roads,Completed,NN-ADYAR,177,879000,"Laying WMM Water Logging Area at Ramakrishna Nagar 2nd Main Road and Ramakrishna Nagar 4th street in Dn-177, Unit-40A, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/19329,Roads,Completed,NN-ADYAR,177,586000,"Laying WMM Water Logging Area at Amman Koil Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19331,Roads,Completed,NN-ADYAR,177,754000,Laying WMM Water Logging Area at Andal nagar Extn 1st street in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/19332,Roads,Completed,NN-ADYAR,177,915000,"Laying WMM Water Logging Area at E.B Colony 3rd Street - 2nd Cross Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19333,Roads,Completed,NN-ADYAR,177,296000,"Laying WMM Water Logging Area at AGS colony 3rd main road in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19334,Roads,Completed,NN-ADYAR,177,557000,"Laying WMM Water Logging Area at Andal Nagar Extn 2nd Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19335,Roads,Completed,NN-ADYAR,171,510000,"Providing patch work at various streets damaged due to heavy rain and flood using Wet Mix Macadam in Dn-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/19338,Roads,Completed,NN-ADYAR,177,66000,"Laying WMM Water Logging Area at Andal nagar Extn 2nd street -1st lane in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19339,Roads,Completed,NN-ADYAR,177,82000,"Laying WMM Water Logging Area at Andal nagar Extn 2nd street -2nd lane in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19340,Roads,Completed,NN-ADYAR,177,273000,"Laying WMM Water Logging Area at Andal Nagar Extn 3rd Street in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19341,Roads,Completed,NN-ADYAR,177,631000,"Laying WMM Water Logging Area at Nethaji Colony 3rd Main Road in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19344,Roads,Completed,NN-ADYAR,177,82000,"Laying WMM Water Logging Area at Andal nagar Extn 2nd street -3rd lane in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/19357,Roads,Completed,NN-ADYAR,177,932000,"Laying WMM Water Logging Area at Ambethkar Nagar 13th cross street, Ambethkar Nagar 86th, 154th, 155th, 156, 163rd, 164th Lane, Venkateshwara Nagar 6th cross Street, Mahalakshmi Nagar 3rd cross street, TNHB Colony 2nd street, 11th Street,TNHB Colony 14th, 55th, 58th and 99th Lane in Dn-177, Unit-40A, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/19358,Roads,Completed,NN-ADYAR,178,945000,"Providing and Laying Wet Mix Macadam for attending patch works at Jaganathapuram 1st main road, Yamuna Street, M.G.R Nagar 10th and 11th street, Throbathyamman koil Street, Vaigai Street, Narmatha Street, Bhavani Street, and Pazhaniappa street in Dn-178, Unit-39, zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/19832,Storm Water Drain,Completed,NN-ADYAR,181,980000,"REPAIRS AND RECONSRUCTION OF STORM WATER DRAIN EFFECTED BY MANSOON RAIN AT DR. RADAKRISHANAN ROAD, MALAVIYA AVENUE KALASHTRA ROAD DIVISION 181 UNIT 38 ZONE13",Own Sources,13,2015-16,2017-18 NN/2015-16/1987,Buildings,Completed,NN-ADYAR,175,210000,"Repairs and Improvements to Public Information Centre Zonal Office Building at Dr.Muthulakshmi Salai in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/20005,Roads,Completed,NN-ADYAR,177,219000,Laying WMM Water Logging Area at EX serviceman colony 2nd main road in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20006,Roads,Completed,NN-ADYAR,177,257000,Laying WMM Water Logging Area at ASK nagar 3rd cross street in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20007,Roads,Completed,NN-ADYAR,177,213000,Laying WMM Water Logging Area at ASK Nagar 2nd street in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20008,Roads,Completed,NN-ADYAR,177,129000,Laying WMM Water Logging Area at ASK Nagar 3rd street in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20009,Roads,Completed,NN-ADYAR,177,190000,Laying WMM Water Logging Area at ASK Nagar 4th street in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20010,Roads,Completed,NN-ADYAR,177,480000,Laying WMM Water Logging Area at New secretariat colony 5th street in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20011,Roads,Completed,NN-ADYAR,177,250000,Laying WMM Water Logging Area at New secretariat colony 3rd street in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20012,Roads,Completed,NN-ADYAR,177,720000,Laying WMM Water Logging Area at Gangai nagar 4th main road in dn-177 U-40a Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20044,Roads,Completed,NN-ADYAR,175,729000,Attending emergency patch work at Gandhi Nagar II Main road in Div175 Zone-13,Own Sources,13,2015-16,2016-17 NN/2015-16/20120,Storm Water Drain,Completed,NN-ADYAR,172,998000,"DESILTING OF SWD AT VARIOUS STREETS (KOTTURPURAM 1ST CROSS STREET, 2ND CROSS STREET, 3RD MAIN ROAD, 2ND MAIN ROAD, DHANDAYUTHAPANI NAGAR 2ND STREET, CROSS STREET) IN DIVISION - 172, UNIT-40, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/20165,Buildings,Completed,NN-ADYAR,N13,183000,"SUPPLYING AND FIXING OF STREET NAME BOARD WITH EMBOSSING TYPE BANNER FOR GANDHI NAGAR 4TH MAIN ROAD AS PA . RAMACHANDRA ADITHANAR SALAI IN DN-175, UNIT-40, Z-13.",Own Sources,,2015-16,2016-17 NN/2015-16/20184,Buildings,Completed,NN-ADYAR,172,984000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND SHOPS PASSAGE LIGHTING WORKS AT LAKE VIEW ROAD DN-172,U-40,Z13.",Own Sources,13,2015-16,2017-18 NN/2015-16/20373,Buildings,Completed,NN-ADYAR,170,985000,"IMPROVEMENTS TO THE PLAY GROUND AND PROVIDING RO WATER DRINKING AREA AT THE CHSS AT CHINNA MALAI IN DN-170,UT-39,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/20375,Buildings,Completed,NN-ADYAR,174,875000,"IMPROVEMENTS TO THE TOILET AND ELECTRICAL ARRANGEMENTS TO THE COMMUNITY HALL AT CHAKARAPANI ST IN DN-174,UT-40A,ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/20380,Roads,Completed,NN-ADYAR,174,610000,"PROVIDING WET MIX MACADAM AT DAMAGED ROADS OF GANESH NAGAR MAIN ROAD,CITY LIMIT ROAD,PILLAYAR KOIL ST,CHAKARAPANI ST,FIVE FUR LONG ROAD AND CART TRACK ROAD ETC IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/20397,Buildings,Completed,NN-ADYAR,174,680000,"IMPROVEMENTS TO THE PRIMARY SCHOOL AND HIGHER SECONDARY SCHOOL KITCHEN SHED AT CHENNAI HIGHER SECONDARY SCHOOL IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/20419,Storm Water Drain,Completed,NN-ADYAR,181,970000,"REPAIRS TO STORM WATER DRAIN AT KAMARAJ NAGAE 1ST , 2ND STREETS, SIVASUNDER AVENUE 1ST 2ND STREETS , VALAMIKI STREET, THIRUVALLUVAR SALAI IN DIVISION 181 UNIT38 ZONE 13",Own Sources,13,2015-16,2020-21 NN/2015-16/20423,Buildings,Completed,NN-ADYAR,179,508000,"Improvements to Community Hall at Seva Nagar 1st Street In Dn-179,Unit-39,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20473,Roads,Completed,NN-ADYAR,179,595000,"Raising of road with Wet mix macadam and bituminous macadam at Arumuga Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/20479,Roads,Completed,NN-ADYAR,179,305000,"Raising of road with Wet mix macadam at mahaver Nagar in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/20482,Roads,Completed,NN-ADYAR,179,285000,"Raising of road with Wet mix macadam at amirtham avenue in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/20484,Roads,Completed,NN-ADYAR,179,473000,"Raising of road with Wet mix macadam and bituminous macadam at kamaraj street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/20487,Roads,Completed,NN-ADYAR,179,363000,"Raising of road with Wet mix macadam at pillaiyar koil (annai indira nagar)street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/20490,Roads,Completed,NN-ADYAR,179,585000,"Raising of road with Wet mix macadam at gar Baby na1st cross street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/20493,Roads,Completed,NN-ADYAR,179,375000,"Raising of road with Wet mix macadam at Tansi Nagar 18th street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/20496,Roads,Completed,NN-ADYAR,179,999000,"Raising of road with Wet mix macadam and bituminous macadam at Tansi Nagar 17th street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/20499,Buildings,Completed,NN-ADYAR,179,158000,"Proposed Construction of Gate and Gate Pillar in Community Hall Campus at Seva Nager 2nd street Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/20504,Buildings,Completed,NN-ADYAR,176,305000,"Providing Barricading arrangements at Elliats Beach for New year-2016 (First January) and Pongal festival-2016 in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/20505,Buildings,Completed,NN-ADYAR,179,200000,"Improvements to Repairs compound wall for Community Hall Campus at Seva Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/20527,Roads,Completed,NN-ADYAR,179,874000,"Attending patch work with wet mix macadam at velachery main road in Div-179, unit-39, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20537,Buildings,Completed,NN-ADYAR,181,174000,"Providing Barricading arrangements at Astalakshmi koil Beach and New Beach at Thiruvanmiyur in Division-181, Unit-38, Zone-13. for Pongal festival 2016.",Own Sources,13,2015-16,2017-18 NN/2015-16/20538,Roads,Completed,NN-ADYAR,170,973000,"Attending the patches at Mettu street,Munusamy street,thirugnana sampathar street,pillayar koil 1st2nd3rd 4th 5th&6th street, Nehru 3rd streein div-170,Unit-40(A),Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20559,Roads,Completed,NN-ADYAR,182,998000,"Attending the patch work by using wet mix macadam in various streets in dn 182 unit- 38 , zone13",Own Sources,13,2015-16,2017-18 NN/2015-16/20574,Roads,Completed,NN-ADYAR,177,294000,"Laying GSB& WMM at Water Logging Area at RAMAKRISHNA NAGAR 1 ST MAIN ROAD in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20576,Roads,Completed,NN-ADYAR,177,130000,"Laying GSB& WMM at Water Logging Area at EB COLONY 2ND STREET in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20581,Roads,Completed,NN-ADYAR,177,717000,"Laying GSB& WMM at Water Logging Area at RAMAKRISHNA NAGAR MAIN ROAD in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20583,Roads,Completed,NN-ADYAR,177,267700,"Laying GSB& WMM at Water Logging Area at RADHA NAGAR 1ST STREET in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20585,Roads,Completed,NN-ADYAR,177,415000,"Laying GSB& WMM at Water Logging Area at ASTALAKSHMI NAGAR 5 TH STREET in Dn-177,U-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20627,Roads,Completed,NN-ADYAR,173,992000,"PROVIDING AND FIXING SS HANDRAILS FOR CENTRE MEDIAN QUIBBLE ISLAND CEMETERY TO PATTINAMPAKKAM SIGNAL(PART-1) AT D.G.S.DINAKARAN SALAI IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/20632,Roads,Completed,NN-ADYAR,173,992000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAILS FOR CENTRE MEIAN QUIBBLE ISLAND CEMETERY TO PATTINAMPAKKAM SIGNAL (PART-2) AT D.G.S.DINAKARAN SALAI IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/20633,Roads,Completed,NN-ADYAR,173,992000,"PROVIDING AND FIXING STAINLESS STEEL HANDRAILS FOR CENTRE MEDIAN QUIBBLE ISLAND CEMETERY TO PATTINAMPAKKAM SIGNAL (PART-3) AT D.G.S.DINAKARAN SALAI IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/20634,Roads,Completed,NN-ADYAR,173,995000,"PROVIIDNG AND FIXING STAINLESS STEEL HANDRAILS FOR CENTRE MEDIAN QUIBBLE ISLAND CEMETERY TO PATTINAMPAKKAM SIGNAL(PART-4) AT D.G.S. DINAKARAN SALAI IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/20636,Roads,Completed,NN-ADYAR,173,815000,"PAINTING BLACK AND WHITE TO THE FOOT PATH KERB AND CENTRE MEDIAN KERB WALL AT DURGA BAI DESHMUK SALAI AND D.G.S.DINAKARAN SALAI IN VIEW OF REBUBLIC DAY ' 2016 IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/20646,Roads,Completed,NN-ADYAR,180,816000,"Attending the urgent Patch work at flood damaged road by using we mix macadam and GSB at LB Road 3rd street, Karunanidhi street thanthai periyar nagar in Dn-180, unit-39, Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/20679,Storm Water Drain,Completed,NN-ADYAR,177,971000,CONSTRUCTION OF STORM WATER DRAIN AT ASTHALAKSHMI NAGAR 1ST AND 2ND STREET IN DIV 177 UNIT 40A ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/20680,Storm Water Drain,Completed,NN-ADYAR,177,971000,CONSTRUCTION OF STORM WATER DRAIN AT ASTHALAKSHMI NAGAR 3RD STREET IN DIV 177 UNIT 40A ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/20736,Storm Water Drain,Completed,NN-ADYAR,177,971000,"CONSTRUCTION OF CULVERT AND STORM WATER DRAIN AT ASTHA LAKSHMI NAGAR 3RD,6TH AND 9TH STREET EXTENSION ROAD CROSSING IN DIV 177 UNIT 40A ZONE 13",Own Sources,13,2015-16,2017-18 NN/2015-16/20741,Storm Water Drain,Completed,NN-ADYAR,177,971000,CONSTRUCTION OF STORM WATER DRAIN AT ASTHA LAKSHMI NAGAR 4TH STREET IN DIV 177 UNIT 40A ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/20743,Storm Water Drain,Completed,NN-ADYAR,177,971000,CONSTRUCTION OFCULVERT AND STORM WATER DRAIN AT ASTHA LAKSHMI NAGAR AT 4TH AND 5TH STREET EXTESION ROAD CROSSING IN DIV 177 UNIT 40A ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/20744,Storm Water Drain,Completed,NN-ADYAR,177,971000,CONSTRUCTION OF STORM WATER DRAIN AT ASTHA LAKSHMI NAGAR 5TH STREET IN DIV 177 UNIT 40A ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/20745,Storm Water Drain,Completed,NN-ADYAR,177,971000,CONSTRUCTION OF STORM WATER DRAIN AT ASTHA LAKSHMI NAGAR 5TH EXTENSION IN DIV 177 UNIT 40A ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/2079,Buildings,Completed,NN-ADYAR,173,530000,"Repairs and Improvements to Tamil Nadu Local Bodies Ombudsman Office at D.G.S. Dinakaran Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/20934,Roads,Completed,NN-ADYAR,174,985000,"PROVIDING GRANULAR SUB BASE AND WET MIX MACADAM TO THE DAMAGED ROAD AT VELECHERY MAIN ROAD AND ANBIL DHARUMALINGAM ,PERIYAR ,AND VEERA PANDIYA KATTABOMMAN -CROSS ST IN DN-174,UT-40A,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/20960,Roads,Completed,NN-ADYAR,174,965000,"PROVIDING GRANULAR SUB BASE AND WET MIX MACADAM AT RACE COURSE INTERIOR ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/20984,Buildings,Completed,NN-ADYAR,174,185000,"PROVIDING TEMPORARY SHED FOR S.I OFFICE,C.I OFFICE ,TAX COLLECTOR OFFICE,AND LABOUR ROOM AT FIVE FUR LONG ROAD IN DN-174,UT-40A, ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/21332,Storm Water Drain,Completed,NN-ADYAR,170,375000,"PROVIDING GRANITE FOOTPATH WEST SIDE(REACH-2) AT COUSTOMS COLONY IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/21383,Roads,Completed,NN-ADYAR,182,803000,"Proposed laying of bituminous concrete road at srinivasapuram 2nd main road in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/22286,Storm Water Drain,Completed,NN-ADYAR,172,923000,"Improvements to the Storm Water Drain at Junction of Kottupuram Main Road and inside of Childrens Play ground (flood Damaged SWD) in Dn-172,Unit-40,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/22287,Buildings,Completed,B-Buildings,172,990000,"Improvements to the (NUMH) Dispensary at Dhandayudapani Nagar 2nd Street d (flood Damaged Building) in Dn-172,Unit-40,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/22288,Buildings,Completed,B-Buildings,172,900000,"Improvements to Flood damaged Health Post Building and Damaged Compound wall at Dhandayuthapani Nagar 2nd Street in Dn-172,Unit-40,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/22525,Roads,Completed,NN-ADYAR,171,969000,"Supply and Laying Quarry Rubbish at Model Higher Secondary School & Thiruvalluvar Grukulam School (Flood Relief Camp Site) for Restoration and Leveling of Slushy Ground Surface in div-171,unit-40A,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/22563,Footpath,Completed,NN-ADYAR,172,978000,"Repairs to Footpath, Painting Black and White washes for Kerbs & Centre Median at Gandhi Mandapam Road & Sardar Patel Road in Dn-172, Unit-40, Zone13",Own Sources,13,2015-16,2017-18 NN/2015-16/22568,Buildings,Completed,NN-ADYAR,172,890000,"Improvements to Flood Damaged Park and construction of Compound wall at Dhandayudapani Nagar 2nd Street in Dn.172,Unit-40,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/22878,Buildings,Completed,NN-ADYAR,172,973000,"Reconstruction of Collapsed Compound Wall During Flood for CPS and Improvements to CPS at Chitra Nagar Kotturpuram in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/22952,Roads,Completed,NN-ADYAR,182,2606386,"Proposed laying of bituminous concrete road at Kannappa nagar Extn in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/22954,Roads,Completed,NN-ADYAR,182,281000,"Proposed laying of bituminous concrete road at Kannappa nagar 4th cross street in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/22959,Roads,Completed,NN-ADYAR,182,214000,"Proposed relaying of bituminous concrete road at Gangai street lane-2 in Division -181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/22960,Roads,Completed,NN-ADYAR,182,378000,"Proposed relaying of Bituminous concrete road at Sevagan street in Division - 181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/22962,Roads,Completed,NN-ADYAR,182,1360000,"Proposed laying of bituminous concrete road at Journalist colony XXXIII road in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/23362,Buildings,Completed,B-Buildings,172,540000,"Providing Interlocking Block and Antiskid Tiles in pathway around Health Post Building at Dhandayuthapani Nagar 2nd Street in Dn-172,Unit-40,Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/23675,Storm Water Drain,Completed,NN-ADYAR,177,991000,"CONSTRUCTION OF STROM WATER DRAIN@ 3rd MAIN ROAD KAKAN NAGAR VELACHERY REACH-2 (48 TO 94) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/23740,Storm Water Drain,Completed,NN-ADYAR,177,997000,"CONSTRUCTION OF STORM WATER DRAIN@ 4TH MAIN ROAD AMBETHKAR NAGAR VELACHERY REACH-3 (95 TO 141) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/23743,Buildings,Completed,NN-ADYAR,172,498000,"Electrical arrangement and Water Supply arrangement during flood for CPS at Chitra Nagar Kotturpuram in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2019-20 NN/2015-16/23775,Storm Water Drain,Completed,NN-ADYAR,177,993000,"CONSTRUCTION OF STORM WATER DRAIN@ 3rd MAIN ROAD KAKAN NAGAR VELACHERY REACH-1 (0 TO 47) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/23799,Storm Water Drain,Completed,NN-ADYAR,177,983000,"CONSTRUCTION OF STORM WATER DRAIN @4th MAIN ROAD AT AMBETHKAR NAGAR REACH-4 (142 TO 188) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/23808,Storm Water Drain,Completed,NN-ADYAR,177,989000,"CONSTRUCTION OF STORM WATER DRAIN @4th MAIN ROAD AT AMBETHKAR NAGAR REACH-5 (189 TO 235) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/23818,Storm Water Drain,Completed,NN-ADYAR,177,998000,"CONSTRUCTION OF STORM WATER DRAIN @4th MAIN ROAD AT AMBETHKAR NAGAR REACH-6 (236 TO 282) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/23821,Storm Water Drain,Completed,NN-ADYAR,177,998000,"CONSTRUCTION OF STORM WATER DRAIN @4th MAIN ROAD AT AMBETHKAR NAGAR REACH-7 (283 TO 329 M) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/23939,Storm Water Drain,Completed,NN-ADYAR,177,705000,"CONSTRUCTION OF STORM WATER DRAIN @4th MAIN ROAD AT AMBETHKAR NAGAR REACH-8 (330 TO 362 M) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/23940,Storm Water Drain,Completed,NN-ADYAR,177,998000,"CONSTRUCTION OF STORM WATER DRAIN@EX-SERVICE MAN COLONY 1st MAIN ROAD REACH-1 (0 TO 47 M) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/24221,Storm Water Drain,Completed,NN-ADYAR,177,998000,"CONSTRUCTION OF STORM WATER DRAIN@EX-SERVICE MAN COLONY 1st MAIN ROAD REACH-2 (48 TO 94 M) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/24232,Storm Water Drain,Completed,NN-ADYAR,177,994000,"CONSTRUCTION OF STORM WATER DRAIN@EX-SERVICE MAN COLONY 1st MAIN ROAD REACH-3 (95 TO141 M) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/24233,Buildings,Completed,NN-ADYAR,172,949000,"REPAIR AND IMPROVEMENT WORK TO CHS AT NEW STREET KOTTUR IN DN-172, UNIT-40, ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24236,Storm Water Drain,Completed,NN-ADYAR,179,957000,"Proposed Construction of Side Drain in Size of 600x750 mm along Kamachi amman street(Ch 0-70 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/24238,Storm Water Drain,Completed,NN-ADYAR,177,997000,"CONSTRUCTION OF STORM WATER DRAIN@ ASK NAGAR 1st MAIN ROAD REACH-4 (142 TO 188 M) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/24239,Storm Water Drain,Completed,NN-ADYAR,177,842000,"CONSTRUCTION OF STORM WATER DRAIN@ ASK NAGAR 1st MAIN ROAD REACH-5 (189 TO 218 M) IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/24261,Storm Water Drain,Completed,NN-ADYAR,179,957000,"Proposed Construction of Side Drain in Size of 600x750 mm along Kamachi amman street(Ch 70-140 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/24280,Storm Water Drain,Completed,NN-ADYAR,179,704000,"Proposed Construction of Side Drain in Size of 600x750 mm along sivasakthi street(Ch 0-50 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/24281,Storm Water Drain,Completed,NN-ADYAR,179,704000,"Proposed Construction of Side Drain in Size of 600x750 mm along sivasakthi street(Ch 50-100 m) in Dn-179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/24283,Storm Water Drain,Completed,NN-ADYAR,179,815000,"Proposed Construction of Side Drain in Size of 600x750 mm along vallalar street in Dn-179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/24287,Storm Water Drain,Completed,NN-ADYAR,179,812000,"Proposed Construction of Side Drain in Size of 600x750 mm along Bharani Street in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2017-18 NN/2015-16/24288,Storm Water Drain,Completed,NN-ADYAR,179,989000,"Proposed Construction of Side Drain in Size of 600x750 mm along Uthayam Nagar Extn in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2017-18 NN/2015-16/24290,Storm Water Drain,Completed,NN-ADYAR,177,950000,"CONSTRUCTION OF STORM WATER DRAIN (1200X1200) @1st MAIN ROAD AMBETHKAR NAGAR, VELACHERY IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/24292,Roads,Completed,NN-ADYAR,170,938000,"Attending the urgent, patch work at flood damgaed road by using wet mix macadam in Alandur service road, hospital road, poonamalle road, corporation road, gandhi nagar main road, poomagal main road and various streets in DN-170, Unit -40A, Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/24449,Road Cut,Completed,NN-ADYAR,178,765000,"Restoration of Road Cut made by TANGEDCO at Ram nagar north extn main road (ch 0-293) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24452,Road Cut,Completed,NN-ADYAR,178,765000,"Restoration of Road Cut made by TANGEDCO at Ram nagar north extn main road (ch 293-586) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24455,Road Cut,Completed,NN-ADYAR,178,878000,"Restoration of Road Cut made by TANGEDCO at Ram nagar 5th Street, Ram Nagar 8th Main Road and Jaganathapuram 3rd Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24458,Road Cut,Completed,NN-ADYAR,178,822000,"Restoration of Road Cut made by TANGEDCO at Ram Nagar 3rd Street and Ram Nagar 3rd Cross Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24468,Buildings,Completed,NN-ADYAR,172,998000,"DESILTING OF SWD AT VARIOUS STREETS (DHANDAYUTHAPANI NAGAR 1ST STREET & KOTTURPURAM 1ST MAIN ROAD) IN DIVISION - 172,UNIT-40, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/24479,Roads,Completed,NN-ADYAR,182,990000,"IMPROVEMENT OF FOOTPATH AT SOUTH AVENUE STREET(Right side) IN DIVISION-182, UNIT-38, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/24704,Road Cut,Completed,NN-ADYAR,178,518000,"Restoration of Road Cut made by TANGEDCO at Vijaya Nagar 1st Main Road (Ch 0-198 m) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24708,Road Cut,Completed,NN-ADYAR,178,518000,"Restoration of Road Cut made by TANGEDCO at Vijaya Nagar 1st Main Road (Ch 198-396 m) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24716,Road Cut,Completed,NN-ADYAR,178,938000,"Restoration of Road Cut made by TANGEDCO at Vijaya Nagar 2nd Main Road, Vijaya Nagar 2nd Cross Street and Vijaya Nagar 4th Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24721,Road Cut,Completed,NN-ADYAR,178,793000,"Restoration of Road Cut made by TANGEDCO at Devikarumariamman Nagar Main Road, Devikarumariamman Nagar 1st Avenue, Devikarumariamman Nagar 2nd Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24724,Road Cut,Completed,NN-ADYAR,178,748000,"Restoration of Road Cut made by TANGEDCO at Throwpathy Amman Koil Main Road (Ch 0-287 m) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24728,Road Cut,Completed,NN-ADYAR,178,748000,"Restoration of Road Cut made by TANGEDCO at Throwpathy Amman Koil Main Road (Ch 287 - 574 m) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24730,Road Cut,Completed,NN-ADYAR,178,908000,"Restoration of Road Cut made by TANGEDCO at Rajalakshmi Nagar 4th Cross Street, 7th Cross Street, 1st Street, 10th Street, 2nd Main Road, 8th Cross Street and Brahmin Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24734,Road Cut,Completed,NN-ADYAR,178,935000,"Restoration of Road Cut made by TANGEDCO at Pillaiyar Koil Street, Telugu Brahmin Street, Maheswari Nagar, Jaganathapuram Main Road, Throwpathy Amman Koil 2nd Street and Lakshmipuram 1st Cross Street & Devikarumariamman Nagar 6th Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/24909,Footpath,Completed,NN-ADYAR,172,850000,"Painting Footpath Kerbs and Centre Median at Sardar Patel Road and Gandhi Mandapam Road in Dn.172, Unit-40, Zone-13 in the view of Republic Day Celebration 2016.",Own Sources,13,2015-16,2017-18 NN/2015-16/25109,Roads,Completed,NN-ADYAR,180,993000,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET IN THARAMANI AND MGR NAGAR(UNDER WARD COUNCILLOR FUND) IN DN-180, U-39, Z-13",Own Sources,13,2015-16,2018-19 NN/2015-16/25148,Buildings,Completed,NN-ADYAR,180,993000,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET IN THANTHAI PERIYAR NAGAR AND BHARATHI NAGAR(UNDER WARD COUNCILLOR FUND) IN DN-180, U-39, Z-13",Own Sources,13,2015-16,2018-19 NN/2015-16/25231,Buildings,Completed,NN-ADYAR,N13,920000,"IMPROVEMENTS TO THE GROUND AND FRIST FLOOR OF THE CHENNAI CORPORATION HIGHER SECONDARY SCHOOL AT LITTLE MOUNT IN DN-170,UT-40A,ZONE-13.",Own Sources,,2015-16,2017-18 NN/2015-16/25241,Storm Water Drain,Completed,NN-ADYAR,179,815000,"Proposed Construction of Side Drain in Size of 600x750 mm along V.G.P. Selva Nagar Extn., 3rd Street (Ch 0-60 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/25246,Storm Water Drain,Completed,NN-ADYAR,179,815000,"Proposed Construction of Side Drain in Size of 600x750 mm along V.G.P. Selva Nagar Extn., 3rd Street (Ch 60-120 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2017-18 NN/2015-16/25248,Storm Water Drain,Completed,NN-ADYAR,179,755000,"Proposed Construction of Side Drain in Size of 600x750 mm along V.G.P. Selva Nagar Extn., 3rd Street (Ch 120-175 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2017-18 NN/2015-16/25251,Storm Water Drain,Completed,NN-ADYAR,179,949000,"Proposed Construction of Side Drain in Size of 600x750 mm along Venus Colony 2nd srteet (Ch 0-70 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/25269,Roads,Completed,NN-ADYAR,175,6338000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Arangannal Salai in DN-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/25275,Storm Water Drain,Completed,NN-ADYAR,179,946000,"Proposed Construction of Side Drain in Size of 600x750 mm along Venus Colony 2nd srteet (Ch 70-140 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/25307,Roads,Completed,NN-ADYAR,175,847000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Bakthachavalam Nagar V Street (Part) in DN-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/25336,Roads,Completed,NN-ADYAR,175,1185000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Anna Avenue in DN-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/25353,Roads,Completed,NN-ADYAR,175,1163000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Justice Ramasamy Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/25354,Roads,Completed,NN-ADYAR,175,4044000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Indra Nagar I Main Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/25356,Storm Water Drain,Completed,NN-ADYAR,179,812000,"Proposed Construction of Side Drain in Size of 600x750 mm along Venus Colony 2nd srteet (Ch 140-200 m) in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2016-17 NN/2015-16/25360,Storm Water Drain,Completed,NN-ADYAR,179,946000,"Proposed Construction of Side Drain in Size of 600x750 mm along Dhandeeswaram nagar 10th cross street in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2018-19 NN/2015-16/25361,Storm Water Drain,Completed,NN-ADYAR,179,700000,"Proposed Construction of Side Drain in Size of 600x750 mm along Dhandeeswaram 12thcross street in Dn- 179, Unit -39, Zone- 13",Own Sources,13,2015-16,2017-18 NN/2015-16/25362,Roads,Completed,NN-ADYAR,175,537000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Indra Nagar XXII Cross Street (Link) in DN-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/25384,Roads,Completed,NN-ADYAR,176,915000,"Attending temporary restoration of damaged road at Karpagam garden 1st main road (part),Karpagam garden 1st cross street(part),Padmanabha nagar 5th street,Sasthiri nagar 1st cross street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25470,Roads,Completed,NN-ADYAR,176,997000,"Attending temporary restoration of damaged road at Besant nagar xxiii street,Besant nagar xxxiii street,Besant nagar xxxi street,Besant nagar vi street,Besant nagar vii street,Besant nagar viii street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/2559,Buildings,Completed,NN-ADYAR,180,518000,"Improvements and repair work of NNMP sheds at Godavari street , Perumal kovil street , Taramani bus stand road , Kanagam nehru street , Valluvar nagar Thiruvanmiyur in DN-180 , U-39 , Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/25781,Roads,Completed,NN-ADYAR,173,987000,"Painting the Foot Path Kerbs and Water table at Durgabai Deshmukh Road, DR.D G S Dinakaran Salai, P.S. Kumarasamy Raja Road, Brodies Castle Road in Dn-173, Unit-40, Zone-13 in view of Celebration of Republic Day 2016",Own Sources,13,2015-16,2018-19 NN/2015-16/25791,Playfields,Completed,NN-ADYAR,179,998000,"Improvements to Children's Play Ground at Park avenue 3rd cross street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2017-18 NN/2015-16/25802,Buildings,Completed,NN-ADYAR,173,170000,"Water Supply arrangements to Chennai Middle School at N.S.Garden Street in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/25825,Roads,Completed,NN-ADYAR,176,940000,"Attending temporary restoration of damaged road at Orur alcot kuppam,Orur kuppam,Sasthiri nagar viii cross street,Sasthiri nagar xi cross street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25827,Roads,Completed,NN-ADYAR,176,817000,"Attending temporary restoration of damaged road at Sasthiri nagar x cross street,Sasthiri nagar xii cross street,Sasthiri nagar xxii street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25829,Roads,Completed,NN-ADYAR,176,1550000,"Attending temporary restoration of damaged road at Ellaiamman koil street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25831,Roads,Completed,NN-ADYAR,176,948000,"Attending temporary restoration of damaged road at Karpagam garden 1st link street,Karpagam garden 2nd link street,Padmanabha nagar 2nd street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25832,Roads,Completed,NN-ADYAR,176,490000,"Attending temporary restoration of damaged road at Arunachalapuram 2nd street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25833,Roads,Completed,NN-ADYAR,176,1130000,"Attending temporary restoration of damaged road at Arunachalapuram main road due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25834,Roads,Completed,NN-ADYAR,176,660000,"Attending temporary restoration of damaged road at Besant nagar 27th cross street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/25840,Buildings,Completed,NN-ADYAR,173,908000,"Providing Drinking Water Sump arrangement and Painting work to Chennai Middle School at N.S.Garden Street in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/25859,Playfields,Completed,NN-ADYAR,179,515000,"Providing play apparatus to Children's Play Ground at Park avenue 3rd cross street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2017-18 NN/2015-16/25863,Roads,Completed,NN-ADYAR,179,435000,"Raising of road with wetmix macadam at Venus Colony 2nd Street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2017-18 NN/2015-16/26004,Buildings,Completed,NN-ADYAR,175,490000,"Providing Toilets to Zonal office Building (3rd Floor) at Dr. Muthulakshmi Salai in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26010,Roads,Completed,NN-ADYAR,176,634000,"Attending temporary restoration of damaged road at Besant nagar 28th cross street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/26011,Roads,Completed,NN-ADYAR,176,653000,"Attending temporary restoration of damaged road at Besant nagar 25th cross street due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/26012,Roads,Completed,NN-ADYAR,176,1520000,"Attending temporary restoration of damaged road at Besant nagar 2nd main road due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/26013,Roads,Completed,NN-ADYAR,176,2610000,"Attending temporary restoration of damaged road at Besant nagar 3rd main road due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/26014,Roads,Completed,NN-ADYAR,176,3100000,"Attending temporary restoration of damaged road at Besant nagar 4th main road due to floods in North East Monsoon 2015 in Division - 176, Unit - 38,Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/26025,Roads,Completed,NN-ADYAR,179,809000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at venus colony 2nd street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/26048,Roads,Completed,NN-ADYAR,179,398000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at Sivasakthi street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/26055,Roads,Completed,NN-ADYAR,178,749000,"Relaying of road with B.T. Course by using Paver Finisher at Narmadha Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26068,Roads,Completed,NN-ADYAR,178,291000,"Relaying of road with B.T. Course by using Paver Finisher at Bhavani Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/2607,Buildings,Completed,NN-ADYAR,178,996000,"Improvement to First Floor in Unit office of CI Room , SI Room ,AE, Room ,in Div 178, Unit 39, Zone XIII.",Own Sources,13,2015-16,2019-20 NN/2015-16/26072,Roads,Completed,NN-ADYAR,178,600000,"Relaying of road with B.T. Course by using Paver Finisher at Vijaya Nagar 9th Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26074,Roads,Completed,NN-ADYAR,178,555000,"Relaying of road with B.T. Course by using Paver Finisher at Vijaya Nagar 10th Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26078,Roads,Completed,NN-ADYAR,177,760000,"Attending temporary ( wmm ) restoration of damaged road at MGR Nagar 3 & 4th Cross Street TNHB Colony 5th Street and Astalakshminagar 4th Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/26079,Roads,Completed,NN-ADYAR,177,680000,"Attending temporary (wmm) restoration of damaged road at GangaiNagar 2nd Cross Street, Astalakshmi Nagar 1st Street and Andal Nagar EXtn due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/26098,Roads,Completed,NN-ADYAR,178,910000,"Relaying of road with B.T. Course by using Paver finisher at A.G.S. Colony 4th Cross Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26109,Roads,Completed,NN-ADYAR,178,877000,"Relaying of road with B.T. Course by using Paver finisher at Kalki Nagar Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26112,Roads,Completed,NN-ADYAR,178,307000,"Relaying of road with B.T. Course by using Paver finisher at A.G.S. Colony 7th Main Road (Part) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26117,Roads,Completed,NN-ADYAR,178,752000,"Relaying of road with B.T. Course by using Paver finisher at M.G.R. Nagar 6th Cross Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26121,Roads,Completed,NN-ADYAR,178,861000,"Relaying of road with B.T. Course by using Paver finisher at Palaniyappa Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26122,Roads,Completed,NN-ADYAR,179,443000,"Relaying of road with B.T. Course by using Paver finisher at Anna nagar 2nd main road main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26127,Roads,Completed,NN-ADYAR,178,442000,"Relaying of road with B.T. Course by using Paver finisher at M.G.R. Nagar 5th Cross Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26130,Roads,Completed,NN-ADYAR,179,715000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at Dhandeeswaram nagar 10th main road main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26133,Roads,Completed,NN-ADYAR,178,674000,"Relaying of road with B.T. Course by using Paver finisher at Deviakrumariamman Nagar 9th Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26136,Roads,Completed,NN-ADYAR,179,971000,"Attending temporary restoration of damaged road at Muthukrishnan Street (PART) due to flood in North East Mon soon 2015 in Dn-179,U-39,Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/26139,Roads,Completed,NN-ADYAR,179,735000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at Venus colony 2nd cross street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26140,Roads,Completed,NN-ADYAR,178,265000,"Relaying of road with B.T. Course by using Paver finisher at M.G.R. Nagar 14th Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26142,Roads,Completed,NN-ADYAR,179,909000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at VGP Selva nagar extn.(PART) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26145,Roads,Completed,NN-ADYAR,178,351000,"Relaying of road with B.T. Course by using Paver finisher at Devikarumariamman Nagar 6th Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26148,Roads,Completed,NN-ADYAR,178,342000,"Relaying of road with B.T. Course by using Paver finisher at Orandiamman Koil Lane in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26150,Roads,Completed,NN-ADYAR,179,976000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at Bhuvaneswari nagar 2nd cross street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26151,Roads,Completed,NN-ADYAR,178,922000,"Relaying of road with B.T. Course by using Paver finisher at Jaganathapuram 2nd Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26154,Roads,Completed,NN-ADYAR,179,1279000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at Bhuvaneswari nagar 1st main road (PART) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26162,Roads,Completed,NN-ADYAR,178,984000,"Relaying of road with B.T. Course by using Paver finisher at Rajalakshmi Nagar 2nd Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26164,Roads,Completed,NN-ADYAR,178,815000,"Relaying of road with B.T. Course by using Paver finisher at Throwpathy Amman Koil Main Road (Ch 0-180) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26166,Roads,Completed,NN-ADYAR,179,440000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at Dhandeeswaram 1st cross street (PART) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26167,Roads,Completed,NN-ADYAR,178,788000,"Relaying of road with B.T. Course by using Paver finisher at Throwpathy Amman Koil Main Road (Ch 180-360) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26168,Roads,Completed,NN-ADYAR,179,666000,"Attending to Temporary Restoration B.T. Course by using Paver finisher at Dhandeeswaram nagar 10th cross street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26169,Roads,Completed,NN-ADYAR,178,836000,"Relaying of road with B.T. Course by using Paver finisher at Throwpathy Amman Koil Main Road (Ch 360-545) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26171,Roads,Completed,NN-ADYAR,179,1459000,"Attending temporary restoration of damaged road at VGP Selva nagar 2nd main road due to flood in North East Mon soon 2015 in Dn-179,U-39,Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/26172,Roads,Completed,NN-ADYAR,178,532000,"Relaying of road with B.T. Course by using Paver finisher at Maheswari Nagar in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26173,Roads,Completed,NN-ADYAR,178,605000,"Strengthening of road with B.T. Course by using Paver finisher at Vallalar Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26180,Roads,Completed,NN-ADYAR,178,962000,"Strengthening of road with B.T. Course by using Paver finisher at A.G.S. Colony 4th Cross Street Extn., in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26213,Storm Water Drain,Completed,NN-ADYAR,177,990000,Strengthening and Relaying of Damaged road at ASK NAGAR MAIN ROAD in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26217,Storm Water Drain,Completed,NN-ADYAR,177,870000,Strengthening and Relaying of Damaged road at L.H Nagar 1st Main Road& 1st Cross STreet in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26221,Storm Water Drain,Completed,NN-ADYAR,177,740000,Strengthening and Relaying of Damaged road at MGR Nagar 3rd & 4th Cross STreet in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26222,Storm Water Drain,Completed,NN-ADYAR,177,820000,Strengthening and Relaying of Damaged road at Astalakshmi Nagar 4th Street & Ngo colony 3rd Main Road in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26223,Storm Water Drain,Completed,NN-ADYAR,177,960000,Strengthening and Relaying of Damaged road at Mahalakshmi Nagar 3rd Cross Street & TNHB Colony 5th Street in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26224,Storm Water Drain,Completed,NN-ADYAR,177,790000,Strengthening and Relaying of Damaged road at Dr.Ambedkar Nagar 6th Main Road in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26225,Storm Water Drain,Completed,NN-ADYAR,177,740000,Strengthening and Relaying of Damaged road at Vel Nagar 2nd Street &Krishna Raja Nagar 3rd Street in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26226,Storm Water Drain,Completed,NN-ADYAR,177,850000,Strengthening and Relaying of Damaged road at L.H Nagar 2nd Cross Street & 3rd Cross Street in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26227,Storm Water Drain,Completed,NN-ADYAR,177,780000,Strengthening and Relaying of Damaged road at L.H Nagar 2nd Main Road in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26228,Storm Water Drain,Completed,NN-ADYAR,177,780000,Strengthening and Relaying of Damaged road at Lake View Street in Dn-177 U-40A Z-13,Own Sources,13,2015-16,2016-17 NN/2015-16/26229,Roads,Completed,NN-ADYAR,177,999000,"Strengthening and Relaying of Damaged road at A.S.K Nagar South Cross Street , TNHB Colony 5th Avenue & Venkateswara Nagar 5th Main Road in Dn-177 U-40A Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/26264,Roads,Completed,NN-ADYAR,179,1457000,"Proposed laying of Bituminous concrete road at Spic Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26302,Roads,Completed,NN-ADYAR,182,2849000,"Proposed relaying of Bituminous concrete road at Kalakshetra road in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/2636,Roads,Completed,NN-ADYAR,179,987000,"Attending Patch work at Velachery Main Road (from Jn. of I.I.T. Gate to Jn. of Jaganathapuram 1st Main Road) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26368,Roads,Completed,NN-ADYAR,182,720000,"Proposed relaying of Bituminous concrete road at Karunanithi Street in Division - 181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/26369,Roads,Completed,NN-ADYAR,182,851000,"Proposed relaying of Bituminous concrete road at Sivasundar Avenue 2nd Avenue in Division- 181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/26370,Roads,Completed,NN-ADYAR,182,448000,"Proposed relaying of Bituminous concrete road at Kambar street in Division - 181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/26371,Roads,Completed,NN-ADYAR,182,720000,"Proposed relaying of bituminous concrete road at Appar street in Division- 181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/26372,Roads,Completed,NN-ADYAR,182,550000,"Proposed relaying of bituminous concrete road at Karikalan street in Division - 181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/26374,Roads,Completed,NN-ADYAR,182,214000,"Proposed relaying of bituminous concrete road at Gangai street lane-1 in Division -181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/26375,Roads,Completed,NN-ADYAR,182,1651000,"Proposed relaying of Bituminous concrete road at Tiger varathachari road in Division - 181, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/26590,Road Cut,Completed,NN-ADYAR,179,938000,"Restoration of Road Cut made by TANGEDCO at VGP Selva nagar 2nd main road (ch 0-360m) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26591,Road Cut,Completed,NN-ADYAR,179,938000,"Restoration of Road Cut made by TANGEDCO at VGP Selva nagar 2nd main road (ch 360-720 m) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26593,Road Cut,Completed,NN-ADYAR,179,905000,"Restoration of Road Cut made by TANGEDCO at Bhuvaneshwari nagar 1st main road,Bhuvaneshwari nagar 2nd main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/2665,Buildings,Completed,NN-ADYAR,178,866000,"Provision of Ladies Toilet and Improvement to Amma Canteen in Division 178, Unit 39,Zone XIII.",Own Sources,13,2015-16,2017-18 NN/2015-16/26665,Storm Water Drain,Completed,NN-ADYAR,173,189000,"REPAIRS TO THE DAMAGED STROM WATER DRAIN AT KAMARAJAR SALAI IN DN-173,UT-40,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26804,Roads,Completed,NN-ADYAR,172,2130000,"Proposed laying of Cement Concrete Road at Thiruveethiamman Koil Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26816,Roads,Completed,NN-ADYAR,172,967000,"Relaying the road with BCCMP1 30mm thick using by Paver Finisher at Kottur Garden 4th Main Road Extn.(Reach-1) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/26861,Storm Water Drain,Completed,NN-ADYAR,174,993000,"CONSTRUCTION OF STORM WATER DRAIN @ VANDIKARAN STREET VELACHRY FROM LINK ROAD REACH -1 ( 0 to 47 ) IN DVN-174, UNIT-40A, ZONE - 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26868,Storm Water Drain,Completed,NN-ADYAR,174,985000,"CONSTRUCTION OF STORM WATER DRAIN @ VANDIKARAN STREET VELACHRY FROM LINK ROAD REACH -2(48 TO 94) IN DVN-174, UNIT-40A, ZONE - 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26869,Buildings,Completed,NN-ADYAR,174,982000,"CONSTRUCTION OF STORM WATER DRAIN @ VANDIKARAN STREET VELACHRY FROM LINK ROAD REACH -3 ( 95 to141) IN DVN-174, UNIT-40A, ZONE - 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26872,Buildings,Completed,NN-ADYAR,174,989000,"CONSTRUCTION OF STORM WATER DRAIN @ VANDIKARAN STREET, VELACHERY FROM LINK ROAD REACH-4 (142 TO 188) IN DVN-174, UNIT-40A, ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26873,Buildings,Completed,NN-ADYAR,174,988000,"CONSTRUCTION OF STORM WATER DRAIN @ VANDIKARAN STREET VELACHRY FROM LINK ROAD REACH -5(189 TO 235) IN DVN-174, UNIT-40A, ZONE - 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26877,Buildings,Completed,NN-ADYAR,174,992000,"CONSTRUCTION OF STORM WATER DRAIN @ VANDIKARAN STREET VELACHERY FROM LINK ROAD REACH-6 (236 TO 283) IN DVN-174, UNIT-40A, ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26921,Buildings,Completed,NN-ADYAR,174,980000,"IMPROVEMENTS TO THE LKG AND UKG BLOCK AT THE CHENNAI PRIMARY SCHOOL IN FIVE FUR LONG ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26922,Buildings,Completed,NN-ADYAR,174,985000,"IMPROVEMENTS TO THE 6TH STD BLOCK AT CHENNAI HIGH SCHOOL IN FIVE FURLONG ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/26930,Playfields,Completed,NN-ADYAR,174,998000,"PROVIDING PLAY MATERIAL AND GREENARY TO THE PARK AT SECRETARIAT COLONY IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/26945,Roads,Completed,NN-ADYAR,172,983000,"Relaying the road with BCCMP1 30mm thick including camber correction using by Paver Finisher at Mannappa Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27133,Electrical,Completed,NN-ADYAR,173,845000,"Providing 14Nos of 6mtr G.I Lamp posts with 90w-120w LED Fittings at School Road and Thiruvenkadam Street in Division - 173, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/27139,Buildings,Completed,NN-ADYAR,174,985000,"IMPROVEMENTS AND PROVIDING R.O.PLANT TO THE COMMUNITY CENTRE AT CHAKARAPANI STREET IN DN-174,UT-40A,ZONE-13",Own Sources,13,2015-16,2018-19 NN/2015-16/27239,Storm Water Drain,Completed,NN-ADYAR,179,299000,"Dismantling Existing drain and Construction of Storm Water Drain in size of 1200x1200 mm (From Kanchi I.T.I. to Anna Nagar 2nd Main Road) at Tansi Nagar 19th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27325,Road Cut,Completed,NN-ADYAR,178,912000,"Restoration of Road Cut made by TANGEDCO at Throwpathy Amman Koil 3rd Street, Throwpathy Amman Koil 5th Street & Sankar Nagar in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27331,Roads,Completed,NN-ADYAR,182,1917000,"Proposed laying of bituminous concrete road at Journalist colony XXX road in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/27332,Roads,Completed,NN-ADYAR,182,896000,"Proposed laying of bituminous concrete road at Kannappa Nagar I Main road in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/27333,Roads,Completed,NN-ADYAR,182,1262000,"Proposed laying of bituminous concrete road at Kannappa Nagar II Main road in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/27334,Roads,Completed,NN-ADYAR,182,659000,"Proposed laying of bituminous concrete road at Kannappa Nagar III Main road in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/27335,Roads,Completed,NN-ADYAR,182,700000,"Proposed laying of bituminous concrete road at Kannappa Nagar I Cross Street in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/27336,Roads,Completed,NN-ADYAR,182,357000,"Proposed laying of bituminous concrete road at Kannappa Nagar II Cross Street in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/27337,Roads,Completed,NN-ADYAR,182,367999,"Proposed laying of bituminous concrete road at Kannappa Nagar III Cross Street in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/27479,Buildings,Completed,NN-ADYAR,172,494000,"Construction of Compound wall to Flood Damaged Burial Ground at Lake View Road in Dn.172,Unit-40, Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/27509,Buildings,Completed,NN-ADYAR,179,965000,"Proposed Construction of RCC retaining wall on Kallukuttai Lake (Northern Side) at Bharani Street (Ch 0-25m) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27513,Buildings,Completed,NN-ADYAR,179,965000,"Proposed Construction of RCC retaining wall on Kallukuttai Lake (Northern Side) at Bharani Street (Ch 25-50m) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27515,Buildings,Completed,NN-ADYAR,179,965000,"Proposed Construction of RCC retaining wall on Kallukuttai Lake (Northern Side) at Bharani Street (Ch 50-75m) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2020-21 NN/2015-16/27613,Footpath,Completed,NN-ADYAR,176,540000,"Painting Footpath Kerbs, Trees and Centre Median at D.D. Road, Besant Avenue and Besant nagar 3rd Avenue in Dn-176, Unit-38, Zone-13. In the view of Republic Day Celebration 2016",Own Sources,13,2015-16,2017-18 NN/2015-16/27630,Roads,Completed,NN-ADYAR,N13,985000,"PROVIDING GRANITE FOOTPATH WEST SIDE(REACH-1) AT CUSTOMS COLONY IN DN-170,UT-40A,ZONE-13.",Own Sources,,2015-16,2016-17 NN/2015-16/27648,Buildings,Completed,NN-ADYAR,171,833000,"IMPROVEMENTS AND PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO THE PUBLIC CONVENIENCE AT VENKATAPURAM IN DN-171,UT-39,ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/27653,Buildings,Completed,NN-ADYAR,171,990000,"IMPROVEMENTS AND REPAIR WORKS TO THE PUBLIC CONVENIENCE AT VENKATAPURAM IN DN-171,UT-39,ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/27685,Buildings,Completed,NN-ADYAR,176,123000,"ANNUAL MAINTENANCE FOR ONE YEAR FOR MALE & FEMALE BIO TOILET AT ELLIOTS BEACH IN DIVISION - 176, ZONE - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/27697,Roads,Completed,NN-ADYAR,172,986000,"Relaying the road with BCCMP1 30mm thick using by Paver Finisher at Kandasamy Street in DN-172, Unit-40, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/27707,Roads,Completed,NN-ADYAR,172,986000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Perumal Koil Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27711,Roads,Completed,NN-ADYAR,172,640000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Perumal Koil 1st Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27713,Roads,Completed,NN-ADYAR,172,810000,"Relaying the road with BCCMP1 40mm thick using by Paver Finisher at Lake View Road (Only Damaged Portion Reach-1) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27714,Roads,Completed,NN-ADYAR,172,987000,"Relaying the road with BCCMP1 30mm thick using by Paver Finisher at Ranjith Road in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27718,Roads,Completed,NN-ADYAR,172,909000,"Relaying the road with BCCMP1 40mm thick using by Paver Finisher at Arunachalam Road (Reach-1) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27722,Roads,Completed,NN-ADYAR,172,731000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Vellaiyan Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27729,Roads,Completed,NN-ADYAR,172,833000,"Relaying the road with BCCMP 40mm thick including camber correction using by Paver Finisher at Ambadi Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27732,Roads,Completed,NN-ADYAR,172,391000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at South Lock Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27783,Roads,Completed,NN-ADYAR,172,366000,"Restoration of Road Cut by DBMC 50mm using Paver Finisher at South Lock Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27887,Roads,Completed,NN-ADYAR,172,872000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at River View Road (Reach-1) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27888,Roads,Completed,NN-ADYAR,172,980000,"Relaying the road with BCCMP1 30mm thick using by Paver Finisher at Naidu Street in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27891,Roads,Completed,NN-ADYAR,170,970000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 3RD STREET (REACH-1)IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27896,Roads,Completed,NN-ADYAR,170,998000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 5TH STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27898,Roads,Completed,NN-ADYAR,170,991000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 5TH CROSS STREET,6TH CROSS STREET &7TH CROSS STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27899,Roads,Completed,NN-ADYAR,170,918000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 6TH STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27902,Roads,Completed,NN-ADYAR,170,994000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 7TH CROSS STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27905,Roads,Completed,NN-ADYAR,170,999000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 8TH STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27906,Roads,Completed,NN-ADYAR,170,918000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 9TH STREET&LABOUR COLONY 10TH STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27910,Roads,Completed,NN-ADYAR,170,680000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT PILLAIYAR KOIL 1ST STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27926,Roads,Completed,NN-ADYAR,170,744000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT KATTABOMMAN STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27927,Roads,Completed,NN-ADYAR,170,580000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT ACHUTHANAGAR 3RD STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27928,Roads,Completed,NN-ADYAR,170,774000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT ACHUTHANAGAR 2ND STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27929,Roads,Completed,NN-ADYAR,170,621000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LAXMI VINAYAGA KOIL STREET IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27930,Roads,Completed,NN-ADYAR,179,945000,"Providing and Laying Thermoplastic Marking, Reflective road studs and Street Name Board at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27933,Roads,Completed,NN-ADYAR,179,956000,"Providing and Laying Thermoplastic Marking, Reflective road studs and Street Name Board at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27935,Roads,Completed,NN-ADYAR,179,616000,"Providing and Laying Thermoplastic Marking, Reflective road studs and Street Name Board at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27939,Roads,Completed,NN-ADYAR,179,921000,"Providing and Laying Thermoplastic Marking, Reflective road studs and Street Name Board at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27940,Buildings,Completed,NN-ADYAR,170,994000,"IMPROVEMENTS TO EXISTING COMPOUND WALL AT ARULAMPET BURIAL GROUND IN DIVISION - 170, UNIT - 40A, ZONE -13.",Own Sources,13,2015-16,2016-17 NN/2015-16/27943,Roads,Completed,NN-ADYAR,179,952000,"Providing and Laying Thermoplastic Marking, Reflective road studs and Street Name Board at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27944,Roads,Completed,NN-ADYAR,179,972000,"Providing and Laying Thermoplastic Marking, Reflective road studs and Street Name Board at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/27948,Buildings,Completed,NN-ADYAR,180,497000,"PROVIDING R.O. PLANT TO CHENNAI HIGHER SECONDARY SCHOOL AT TARAMANI (UNDER MLA FUND) IN DN 180, UNIT 39, ZONE 13.",MLACDS,13,2015-16,2017-18 NN/2015-16/27952,Buildings,Completed,NN-ADYAR,180,435000,"PROVIDING COMPUTER WITH PRINTER TO CHENNAI HIGHER SECONDARY SCHOOL AT TARAMANI (UNDER MLA FUND) IN DN 180, UNIT 39, ZONE 13.",MLACDS,13,2015-16,2017-18 NN/2015-16/27961,Buildings,Completed,NN-ADYAR,178,631000,"PROVIDING R.O. PLANT & COMPUTER WITH PRINTER TO CHENNAI HIGHER SECONDARY SCHOOL AT RAJALAKSHMI NAGAR (UNDER MLA FUND) IN DN 178, UNIT 39, ZONE 13.",MLACDS,13,2015-16,2017-18 NN/2015-16/28014,Parks,Completed,P-Parks and Playfields,174,32500000,"FORMATION OF NEW PARK AT PHEONIX MALL RADHA MOHAN STREET, VELACHERY, IN DIVISION -174,UNIT-40A ,ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/28031,Footpath,Completed,NN-ADYAR,171,436000,"Repair work to the existing granite footpath at flood relief camp site (Rajaji Memorial Hall) due to heavy flood during December 2015 in Dn-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/28041,Buildings,Completed,NN-ADYAR,170,593000,"IMPROVEMENTS TO EXISTING COMPOUND WALL AT ALANDUR SERVICE ROAD (SLOTTED HOUSE) AND ARULAMPET BURIAL GROUND IN DIVISION - 170, UNIT - 40A, ZONE -13.",Own Sources,13,2015-16,2016-17 NN/2015-16/28057,Storm Water Drain,Completed,NN-ADYAR,179,705000,"Proposed Construction of Side Drain in size of 600x750 mm at Dhandeeswaram 10th Main Road (Ch 0-50m) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/28060,Storm Water Drain,Completed,NN-ADYAR,179,645000,"Proposed Construction of Side Drain in size of 600x750 mm at Dhandeeswaram 10th Main Road (Ch 50-95m) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/28141,Roads,Completed,NN-ADYAR,170,800000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 11TH STREET, 8TH CROSS STREET&PILLAYAR KOIL 2ND STREET IN DIV - 170, U - 40A, ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/28153,Roads,Completed,NN-ADYAR,178,861000,"Providing and Laying Thermoplastic Marking, Reflective road studs and Street Name board at Various Streets in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/28162,Roads,Completed,NN-ADYAR,170,924000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT PILLAIYAR KOVIL 4TH STREET V - IN DI170, U - 40A, ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/28212,Buildings,Completed,NN-ADYAR,180,230000,"Improvements to PC at kanagam Burial Ground in Dn-180,Unit-39,Zone-13",Own Sources,13,2015-16,2019-20 NN/2015-16/28218,Buildings,Completed,NN-ADYAR,179,3810000,"Proposed Construction of Modern Gym Building in children's play Ground at Ramagiri Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/28277,Buildings,Completed,NN-ADYAR,178,978000,"Demolition and Construction of Compound Wall in Padmavathi Nagar Children's Play Ground in Div 178, Unit 39 , Zone XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/28296,Roads,Completed,NN-ADYAR,170,947000,"RAISING AND RELAYING THE B.T . COURSE 50MM TK .BY USING PAVER FINISHER AT PILLAIYAR KOVIL 3RD STREET IN DN-170,U-40(A) ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/28318,Playfields,Completed,NN-ADYAR,179,370000,"Improvements to Children's Play Ground at Velachery Main Road (in front of Sutherland) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/28320,Buildings,Completed,NN-ADYAR,179,862000,"Providing and Laying interlocking blocks & Stainless Steel hand rail around 'e' toilet & Namma toilet in Velachery MRTS Railway Station Campus, Velachery - Tambaram Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/28436,Buildings,Completed,NN-ADYAR,170,800000,"IMPROVEMENTS TO THE SECOND FLOOR OF THE CHENNAI CORPORATION HIGHER SECONDARY SCHOOL AT LITTLE MOUNT IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/28491,Footpath,Completed,NN-ADYAR,173,960000,"Improvements to Footpath at School Road (Northern Side)in Division - 173, Unit - 40, Zone - XIII",Own Sources,13,2015-16,2018-19 NN/2015-16/28501,Footpath,Completed,NN-ADYAR,173,700000,"Improvements to Footpath at School Road (Southern Side) in Division - 173, Unit - 39, Zone - XIII",Own Sources,13,2015-16,2018-19 NN/2015-16/28507,Roads,Completed,NN-ADYAR,177,862000,"Relaying of road using paver finisher at Ganesh nagar main road (t.p colony)&Ganesh nagar 2nd cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28529,Roads,Completed,NN-ADYAR,177,943000,"Strengthing & Relaying of road using paver finisher at Kakkan nagar 5th main road ,kakkan nagar 4th cross street &5 th cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28530,Roads,Completed,NN-ADYAR,177,943000,"Strengthing & Relaying of road using paver finisher at Sasthri nagar 5th street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28535,Roads,Completed,NN-ADYAR,177,962000,"Strengthing & Relaying of road using paver finisher at Sasthri nagar 3rd street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28539,Roads,Completed,NN-ADYAR,177,950000,"Strengthing & Relaying of road using paver finisher at Nehru nagar Ganthiyar street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28540,Roads,Completed,NN-ADYAR,177,648000,"Strengthing & Relaying of road using paver finisher at Nehru nagar anna street in Dn-177,U-40(A),Z-XIII..",Own Sources,13,2015-16,2016-17 NN/2015-16/28541,Roads,Completed,NN-ADYAR,177,609000,"Strengthing & Relaying of road using paver finisher at Nehru nagar Elango street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28542,Roads,Completed,NN-ADYAR,177,727000,"Strengthing & Relaying of road using paver finisher at Nehru nagar Avvaiyar street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28543,Roads,Completed,NN-ADYAR,177,923000,"Strengthing & Relaying of road using paver finisher at Nehru nagar kambar street in Dn-177,U-40(A),Z-XIII..",Own Sources,13,2015-16,2016-17 NN/2015-16/28544,Roads,Completed,NN-ADYAR,177,996000,"Strengthing & Relaying of road using paver finisher at periyar 2nd street in Dn-177,U-40(A),Z-XIII..",Own Sources,13,2015-16,2016-17 NN/2015-16/28545,Roads,Completed,NN-ADYAR,177,786000,"Strengthing & Relaying of road using paver finisher at periyar 3rd &6th street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28546,Roads,Completed,NN-ADYAR,177,982000,"Strengthing & Relaying of road using paver finisher at periyar 8th &11th street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28547,Roads,Completed,NN-ADYAR,177,982000,"Strengthing & Relaying of road using paver finisher at EX-Serviceman colony 2nd main road &kakkakan nagar 1st cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28548,Roads,Completed,NN-ADYAR,177,648000,"Strengthing & Relaying of road using paver finisher at kannan nagar 2nd cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28549,Roads,Completed,NN-ADYAR,177,570000,"Strengthing & Relaying of road using paver finisher at kannan nagar 3rd cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28550,Roads,Completed,NN-ADYAR,177,550000,"Strengthing & Relaying of road using paver finisher at sasthiri nagar 2nd street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28551,Roads,Completed,NN-ADYAR,177,589000,"Strengthing & Relaying of road using paver finisher at sasthiri nagar 3rd street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28552,Roads,Completed,NN-ADYAR,177,998000,"Strengthing & Relaying of road using paver finisher at periyar nagar 1st main road in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28553,Roads,Completed,NN-ADYAR,177,903000,"Strengthing & Relaying of road using paver finisher at kakkan nagar 2nd main road in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28554,Roads,Completed,NN-ADYAR,177,982000,"Strengthing & Relaying of road using paver finisher at kakkan nagar 3rd main road in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28562,Buildings,Completed,NN-ADYAR,181,950000,IMPROVEMNTS TO CORPORTION SCHOOLS AT ODDAIKUPPAM KUPPAM AND GANDHIGRMAM IN DIVISION 181 UNIT 38 ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/28584,Roads,Completed,NN-ADYAR,177,890000,"Raising and Relaying of Road using paver finisher at T.N.H.B Colony 1st street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28600,Roads,Completed,NN-ADYAR,177,995000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 8th cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28601,Roads,Completed,NN-ADYAR,177,681000,"Raising and Relaying of Road using paver finisher at T.N.H.B Colony 2ND street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28602,Roads,Completed,NN-ADYAR,177,760000,"Raising and Relaying of Road using paver finisher at T.N.H.B Colony 11th street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28603,Roads,Completed,NN-ADYAR,177,682000,"Raising and Relaying of Road using paver finisher at T.N.H.B Colony 2nd avenue in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28604,Roads,Completed,NN-ADYAR,177,792000,"Raising and Relaying of Road using paver finisher at T.N.H.B Colony 12th &14th street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28605,Roads,Completed,NN-ADYAR,177,910000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 2nd main road street (reach-1) in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28606,Roads,Completed,NN-ADYAR,177,850000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 3rd main road street (REACH-1) in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28607,Roads,Completed,NN-ADYAR,177,666000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 3rd cross street (REACH-1) in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28608,Roads,Completed,NN-ADYAR,177,988000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 6th,7th ,9th &cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28617,Roads,Completed,NN-ADYAR,177,997000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 10th cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28618,Roads,Completed,NN-ADYAR,177,825000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 17th cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28620,Roads,Completed,NN-ADYAR,177,802000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 22nd cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28635,Roads,Completed,NN-ADYAR,177,802000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 11TH &12TH cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28636,Roads,Completed,NN-ADYAR,177,802000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 13TH &14TH cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28638,Roads,Completed,NN-ADYAR,177,890000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 15TH &16TH cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28639,Roads,Completed,NN-ADYAR,177,849000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 18TH &20TH cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28640,Roads,Completed,NN-ADYAR,177,661000,"Raising and Relaying of Road using paver finisher at Dr.ambethkar nagar 21ST & 23RD cross street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/28756,Roads,Completed,NN-ADYAR,176,998000,"DESILTING OF SWD AT VARIOUS STREETS IN DIVISION - 176, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/28764,Parks,Completed,NN-ADYAR,181,998000,"DESILTING OF SWD AT VARIOUS STREETS IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/28767,Parks,Completed,NN-ADYAR,181,998000,"DESILTING OF SWD AT VARIOUS STREETS IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/28773,Roads,Completed,NN-ADYAR,173,2297000,"Relaying of road with BC 30mm thick by Paver at Rohini Garden Cross Street in Division - 173, Unit - 40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/28847,Storm Water Drain,Completed,NN-ADYAR,180,637000,"Desilting of SWD at Tharamani 100 feet road in Dn-180, Unit-39, Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/29036,Buildings,Completed,NN-ADYAR,179,3810000,"Proposed Construction of Modern Gym Building in play Ground at V.G.P. Selva Nagar 2nd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/29037,Roads,Completed,NN-ADYAR,176,968000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREETS IN DN-176,UNIT- 38 ,ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/29132,Buildings,Completed,NN-ADYAR,181,990000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT AMBEDKAR ST NSK ST , PERIYAR ST NATAESAN ST, BHARATHIYAR STEET , KAMARAGURU 1,2, 3, ST, AND LAKAHMIPURAM AREA IN DN 181 UNIT 38 ZONE 13",Own Sources,13,2015-16,2018-19 NN/2015-16/29173,Roads,Completed,NN-ADYAR,176,917200,"PROPOSE FORMING AND IMPROVEMENTS TO LAYING OF BT ROADS FOR FRUIT AND FLOWER SHOP AT DHURGHABAI DESHMUCK ROAD, ADYAR. DN-176,UNIT- 38",Own Sources,13,2015-16,2016-17 NN/2015-16/29203,Buildings,Completed,NN-ADYAR,172,766000,"Improvements to Public Convenience at Ponniamman Koil Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29697,Roads,Completed,NN-ADYAR,179,5940000,"Relaying of road with B.T. Course by using Paver finisher at Bharani Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29699,Roads,Completed,NN-ADYAR,179,1020000,"Relaying of road with B.T. Course by using Paver finisher at Tansi Nagar 14th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29709,Roads,Completed,NN-ADYAR,179,1147000,"Relaying of road with B.T. Course by using Paver finisher at Tansi Nagar 15th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29710,Roads,Completed,NN-ADYAR,179,943000,"Relaying of road with B.T. Course by using Paver finisher at Tansi Nagar 19th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29711,Roads,Completed,NN-ADYAR,179,585000,"Relaying of road with B.T. Course by using Paver finisher at Film Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29715,Roads,Completed,NN-ADYAR,179,384000,"Relaying of road with B.T. Course by using Paver finisher at Ayodhya Colony Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29719,Roads,Completed,NN-ADYAR,179,512000,"Relaying of road with B.T. Course by using Paver finisher at Ayodhya Colony1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29746,Roads,Completed,NN-ADYAR,179,2048000,"Relaying of road with B.T. Course by using Paver finisher at Sastri Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29754,Roads,Completed,NN-ADYAR,179,1334000,"Relaying of road with B.T. Course by using Paver finisher at V.G.P. Selva Nagar 2nd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29755,Roads,Completed,NN-ADYAR,179,472000,"Relaying of road with B.T. Course by using Paver finisher at Ramagiri Nagar 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29762,Roads,Completed,NN-ADYAR,179,508000,"Relaying of road with B.T. Course by using Paver finisher at Ramagiri Nagar 2nd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29773,Roads,Completed,NN-ADYAR,179,696000,"Relaying of road with B.T. Course by using Paver finisher at Ramagiri Nagar Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29777,Roads,Completed,NN-ADYAR,179,392000,"Relaying of road with B.T. Course by using Paver finisher at Ramagiri Nagar 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29779,Roads,Completed,NN-ADYAR,179,939000,"Relaying of road with B.T. Course by using Paver finisher at Dhandeeswaram nagar 6th main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29780,Roads,Completed,NN-ADYAR,179,972000,"Relaying of road with B.T. Course by using Paver finisher at Raja Street (Seethapathy Nagar) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29782,Roads,Completed,NN-ADYAR,179,2016000,"Relaying of road with B.T. Course by using Paver finisher at V.G.P. Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29785,Roads,Completed,NN-ADYAR,179,562000,"Relaying of road with B.T. Course by using Paver finisher at Dhandeeswaram Nagar 9th Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29788,Roads,Completed,NN-ADYAR,179,598000,"Relaying of road with B.T. Course by using Paver finisher at Dhandeeswaram Nagar 9th Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29790,Roads,Completed,NN-ADYAR,179,897000,"Relaying of road with B.T. Course by using Paver finisher at Dhandeeswaram Nagar 12th Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/29793,Roads,Completed,NN-ADYAR,179,2200000,"Relaying of road with B.T. Course by using Paver finisher at Dhandeeswaram Nagar 3rd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29800,Roads,Completed,NN-ADYAR,179,388000,"Relaying of road with B.T. Course by using Paver finisher at Jeeva Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29801,Roads,Completed,NN-ADYAR,179,677000,"Relaying of road with B.T. Course by using Paver finisher at Balakrishna Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29803,Roads,Completed,NN-ADYAR,179,1042000,"Relaying of road with B.T. Course by using Paver finisher at Kambar Street (Annai Indira Nagar) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29806,Roads,Completed,NN-ADYAR,179,660000,"Relaying of road with B.T. Course by using Paver finisher at Mahatma Gandhi Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29809,Roads,Completed,NN-ADYAR,179,1400000,"Relaying of road with B.T. Course by using Paver finisher at V.G.P. Selva Nagar 4th Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29810,Roads,Completed,NN-ADYAR,179,795000,"Relaying of road with B.T. Course by using Paver finisher at Balamurugan Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29814,Roads,Completed,NN-ADYAR,179,524000,"Relaying of road with B.T. Course by using Paver finisher at Tansi Nagar 21st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29819,Roads,Completed,NN-ADYAR,179,680000,"Relaying of road with B.T. Course by using Paver finisher at Tansi Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29823,Roads,Completed,NN-ADYAR,179,1364000,"Relaying of road with B.T. Course by using Paver finisher at Dhandeeswaram Nagar Main Road (Part) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/29904,Roads,Completed,NN-ADYAR,180,990000,"Raising of Manhole Doors at Taramani & Thiruvanmiyur in Various locations (Name of the road enclosed) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/30313,Buildings,Completed,NN-ADYAR,173,450000,"Construction of Creache in Greenways road in Division-173,Unit-40,Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/3039,Footpath,Completed,NN-ADYAR,179,998000,"Proposed Fixing of Street name Boards using stainless steel pipe and Retro Reflective streets in Dn-179,Unit- -39, Zone - 13",Own Sources,13,2015-16,2017-18 NN/2015-16/3047,Footpath,Completed,NN-ADYAR,179,164000,"IMPROVEMENTS TO FOOTPATH AT RAJA STREET IN DN-179, UNIT -39 ,ZONE- 13",Own Sources,13,2015-16,2017-18 NN/2015-16/3054,Roads,Completed,NN-ADYAR,179,199000,"IMPROVEMENTS TO FOOTPATH AT DHANDEESWARAM NAGAR 3rd MAIN ROAD IN DN-179, UNIT -39 ,ZONE -13",Own Sources,13,2015-16,2017-18 NN/2015-16/30590,Roads,Completed,NN-ADYAR,171,262000,"Attending Patch Work at North and West C.I.T. Nagar and East Road West C.I.T Nagar in Dn.171, Unit 40, Zone 13",Own Sources,13,2015-16,2016-17 NN/2015-16/3079,Electrical,Completed,NN-ADYAR,175,1888000,"PROVIDING WIRING INSTALLATION FOR 3RD FLOOR OF ZONAL OFFICE AND IMPROVING THE TNEB SERVICE CONNECTION, C.T. METERING AND POWER PANEL BOARDS ZONAL OFFICE AT ADYAR IN DIVISION-175,ZONE-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/30805,Roads,Completed,NN-ADYAR,170,999000,"RAISING AND RELAYING THE B.T COURSE 50MM TK. BY USING PAVER FINISHER AT LABOUR COLONY 3RD STREET (REACH-2)IN DN - 170, U - 40(A), ZONE - 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/30894,Buildings,Completed,NN-ADYAR,171,296000,"Raising the height and repairing the damaged suriya nagar burial ground compound wall on eastern side in dn-171,u-40,z-13",Own Sources,13,2015-16,2017-18 NN/2015-16/30906,Buildings,Completed,NN-ADYAR,178,415000,"Improvements to T.U.C.S. Shop No. 20 at Orandiamman Koil Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/3094,Buildings,Completed,NN-ADYAR,179,116000,"Additional improvements to 'e' Toilet Velachery Main Road ( in Front of Temple Tank ) Dn 179, Unit 39, Zone 13 .",Own Sources,13,2015-16,2016-17 NN/2015-16/30944,Footpath,Completed,NN-ADYAR,170,980000,"PROVIDING GRANITE FOOTPATH EAST SIDE(REACH-1) AT CUSTOM COLONY IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/3097,Buildings,Completed,NN-ADYAR,171,870000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE PUBLIC CONVIENCE AT JOTHIAMMAL NAGAR, GOVT FARM, RICHARDS PARK AND HEALTH POST AT HOSPITAL ROAD IN DIVISION-171, UNIT-40, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/3103,Storm Water Drain,Completed,NN-ADYAR,170,575000,"DESILITING LABOUR COLONY 1ST STREET TO 11TH STREET AND JOTHYAMMAL NAGAR, CHETTY THOTTAM ,NERUPPU MEDU IN DIV-170,UNIT-40A,ZONE13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31270,Roads,Completed,NN-ADYAR,171,93000,"SUPPLYING AND FIXING OF REVERSE OSMOSIS PLANT (R.O.PLANT) AT LORRY STATION AND TALUK OFFICE IN DN- 171,U-40 ,ZONE -13",Own Sources,13,2015-16,2017-18 NN/2015-16/31347,Buildings,Completed,NN-ADYAR,173,1396000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KUTTI II STREET IN DN -173 U - 40 Z - 13,Own Sources,13,2015-16,2017-18 NN/2015-16/31437,Buildings,Completed,NN-ADYAR,177,969000,"LAYING CEMENT CONCTRETE ROAD @ TNHB COLONY 1&5 TH LANE IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/31439,Buildings,Completed,NN-ADYAR,177,967000,"LAYING CEMENT CONCTRETE ROAD @ TNHB COLONY 6&7 TH LANE IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/31446,Buildings,Completed,NN-ADYAR,177,999000,"LAYING CEMENT CONCTRETE ROAD @ TNHB COLONY 8,9&10TH LANE IN DVN-177, UNIT-40A, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/3154,Footpath,Completed,NN-ADYAR,179,197000,"Improvements to Footpath at Murphydoss Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31662,Roads,Completed,NN-ADYAR,179,338000,"Raising of road with Wet mix macadam at Tansi Nagar 21st street in Dn 179, Unit 39, Zone 13",Own Sources,13,2015-16,2017-18 NN/2015-16/31670,Storm Water Drain,Completed,NN-ADYAR,179,702000,Proposed Construction of Side Drain in Size of 600x750 mm at Bharathi street (Part) Jn. of sastri street to Jn. of Balaji street in velachery div-179 unit-39 zone-13,Own Sources,13,2015-16,2017-18 NN/2015-16/31678,Storm Water Drain,Completed,NN-ADYAR,179,992000,Proposed Construction of Side Drain in Size of 600x750 mm at Sastri Street (Part) Jn. of Karikalan street to Jn. of Bharathi street in velachery div-179 unit-39 zone-13,Own Sources,13,2015-16,2017-18 NN/2015-16/31684,Buildings,Completed,NN-ADYAR,174,295000,"REPAIRS AND IMPROVEMENTS TO THE NNMP SHED AT MOSQUE COLONY 6th ST IN DN-174,UT-40A,ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/31697,Roads,Completed,NN-ADYAR,171,988000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Thomas Nagar 1st Street in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31701,Roads,Completed,NN-ADYAR,171,833000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at Thomas Nagar 2nd Street in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31703,Roads,Completed,NN-ADYAR,171,994000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at Todhunder Nagar (south side) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31704,Roads,Completed,NN-ADYAR,171,994000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at Todhunder Nagar (North side) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31730,Roads,Completed,NN-ADYAR,179,985000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at various streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31751,Roads,Completed,NN-ADYAR,172,875000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at River View Road (Reach-2) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31760,Roads,Completed,NN-ADYAR,170,647000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT VINAYAGAPURAM SLUM LANE - 1 IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31764,Roads,Completed,NN-ADYAR,170,621000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT VINAYAGAPURAM SLUM LANE - 2 IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31766,Roads,Completed,NN-ADYAR,170,625000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT VINAYAGAPURAM SLUM LANE - 3 IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31768,Roads,Completed,NN-ADYAR,170,624000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT VINAYAGAPURAM SLUM LANE - 4 IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31769,Roads,Completed,NN-ADYAR,170,606000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT VINAYAGAPURAM SLUM LANE - 5 IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31770,Roads,Completed,NN-ADYAR,170,975000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT RATHINA THOTTAM REACH - 1 ( 0 - 100 M) IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31771,Roads,Completed,NN-ADYAR,170,988000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT RATHINA THOTTAM REACH - 2 ( 100 - 200 M) IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31772,Buildings,Completed,NN-ADYAR,179,293000,"Improvements to Amma Unavagam at New Colony Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31773,Roads,Completed,NN-ADYAR,170,610000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT RATHINA THOTTAM REACH - 3 ( 200 - 260 M) IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31777,Buildings,Completed,NN-ADYAR,177,999000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL -1 @PANDIDURAI ST VELACHERY IN DVN-174, UNIT-40A, ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31779,Footpath,Completed,NN-ADYAR,170,985000,"PROVIDING GRANITE FOOTPATH NORTH AND SOUTH SIDE(REACH-3) AT HOSPITAL ROAD IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31784,Roads,Completed,NN-ADYAR,174,900000,"RAISING AND RELAYING OF BT ROAD AT GOKULAM COLONY REACH-1 ,AFFECTED DUE TO FLOODS IN NORTH EAST MONSOON 2015 IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31788,Roads,Completed,NN-ADYAR,174,886000,"RAISING AND RELAYING OF BT ROAD AT GOKULAM COLONY REACH-2 ,AFFECTED DUE TO FLOODS IN NORTH EAST MONSOON 2015 IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31792,Roads,Completed,NN-ADYAR,170,968000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT ARULAMPET CROSS STREET IN DIVISION - 170, UNIT-40A, ZONE -13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31793,Buildings,Completed,NN-ADYAR,177,998000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL @PANDIDURAI ST VELACHERY IN DVN-174, UNIT-40A, ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31794,Buildings,Completed,NN-ADYAR,170,989000,"CONSTRUCTION OF MULTI PURPOSE HALL AT CHETTY THOTTAM MAIN ROAD IN DIVISION - 170, UNIT-40A, ZONE -13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31796,Buildings,Completed,NN-ADYAR,177,991000,"PROVIDING COMPOUND WALL AND FLOORING AND BOREWELL IN THE MULTIPURPOSE HALL IN PANDIDURAI ST VELACHERY IN DVN-174, UNIT-40A, ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31806,Roads,Completed,NN-ADYAR,175,988000,"Strengthening and relaying with BCCMP 40mm with paver finishing of Gandhi Nagar 2nd Main Road (from the Junction of Gandhi Nagar 4th main road to Gandhi Nagar 2nd cross street) in Dn-175,Unit-40,Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31807,Roads,Completed,NN-ADYAR,175,988000,"Strengthening and relaying with BCCMP 40mm with paver finishing of Gandhi Nagar 2nd Main Road (from the Junction of Gandhi Nagar 2nd cross street to Gandhi Nagar 3rd cross street) in Dn-175,Unit-40,Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31823,Roads,Completed,NN-ADYAR,175,970000,"Strengthening and relaying with BCCMP 40mm with paver finishing of Gandhi Nagar 2nd Main Road (from the Junction of Gandhi Nagar 3rd cross street to Gandhi Nagar Canal bank road) in Dn-175,Unit-40,Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31843,Buildings,Completed,NN-ADYAR,170,974000,"CONSTRUCTION OF MULTIPURPOSE HALL - 2 AT CHETTY THOTTAM MAIN ROAD IN DIVISION - 170, UNIT -40 A, ZONE 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31854,Footpath,Completed,NN-ADYAR,170,990000,"PROVIDING GRANITE FOOTPATH SOUTH SIDE(REACH-1) AT HOSPITAL ROAD IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31858,Footpath,Completed,NN-ADYAR,170,990000,"PROVIDING GRANITE FOOTPATH NORTH SIDE (REACH-1) AT HOSPITAL ROAD IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31869,Buildings,Completed,NN-ADYAR,171,984000,"REPAIRS AND IMPROVEMENTS TO THE DIVISION OFFICE ANNEX BUILDING AFFECTED DUE TO MONSOON AT RICHARDS PARK IN DN-171,UT-40,ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31874,Buildings,Completed,NN-ADYAR,176,390000,"Providing Electrical arrangement and Improvement to Sump in Health Post at Besant Nagar 1st Avenue in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31894,Buildings,Completed,NN-ADYAR,171,990000,"CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENTS TO THE HEALTH POST AT HOSPITAL ROAD IN DN-171,UT-40,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31897,Buildings,Completed,NN-ADYAR,172,990000,"PROVIDING AND FIXING NAME BOARD AT VARIOUS LOCATIONS IN GREATER CHENNAI CORPORATION BUILDINGS IN DN-171 AND 172, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/31898,Buildings,Completed,NN-ADYAR,173,988000,"PROVIDING AND FIXING NAME BOARD AT VARIOUS LOCATIONS IN GREATER CHENNAI CORPORATION BUILDINGS IN DN-173 AND 175,UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/31899,Buildings,Completed,NN-ADYAR,181,990000,"PROVIDING AND FIXING NAME BOARD AT VARIOUS LOCATIONS IN GREATER CHENNAI CORPORATION BUILDINGS IN DN-176,181 AND 182, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/31966,Buildings,Completed,NN-ADYAR,171,990000,"PROVIDING STAINLESS STEEL HANDRAIL AT THE OUTER SIDE OF THE PATHWAY IN THE PARK AT VELECHERY MAIN ROAD IN DN-171,UT-40,ZONE-13 (UNDER COUNCILLOR FUND)",Own Sources,13,2015-16,2018-19 NN/2015-16/31971,Buildings,Completed,NN-ADYAR,171,990000,"PROVIDING STAINLESS STEEL HANDRAIL AT THE INNER SIDE OF THE PATHWAY IN THE PARK AT VELECHERY MAIN ROAD IN DN-171,UT-40,ZONE-13(UNDER COUNCILLOR FUND)",Own Sources,13,2015-16,2018-19 NN/2015-16/31981,Buildings,Completed,NN-ADYAR,179,621000,"Improvements to open Air Auditorium at Gandhi Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2018-19 NN/2015-16/31982,Roads,Completed,NN-ADYAR,179,878000,"Formation of road with B.T. Course by using Paver finisher at Bhuvaneshwari Nagar 2nd Main Road Extn., (Ch 0-60m)in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31983,Parks,Completed,NN-ADYAR,179,878000,"Formation of road with B.T. Course by using Paver finisher at Bhuvaneshwari Nagar 2nd Main Road Extn., (Ch 60m - 120m)in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/31990,Roads,Completed,NN-ADYAR,179,641000,"Formation of Road at Bhuvaneswari Nagar 2nd Main Road (Part) From Jn. of Bhuvaneswari Nagar 1st Main Road to Jn. of 2nd Cross Street (Ch 60m - 120m) in Dn 179,unit-39,zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31992,Parks,Completed,NN-ADYAR,179,641000,"Formation of Road at Bhuvaneswari Nagar 2nd Main Road (Part) From Jn. of Bhuvaneswari Nagar 1st Main Road to Jn. of 2nd Cross Street (Ch 0 - 60m) in Dn 179,unit-39,zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/31997,Buildings,Completed,NN-ADYAR,172,866000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at River View Road (Reach-3) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32005,Roads,Completed,NN-ADYAR,171,1989000,"Relaying of roads with Paver at East Mada street - Srinagar Colony in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32006,Roads,Completed,NN-ADYAR,171,2406000,"Relaying of roads with Paver in Zone at Temple Avenue - Srinagar Colony in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32007,Roads,Completed,NN-ADYAR,171,2124000,"Relaying of roads with Paver in Zone at North Avenue - Srinagar Colony in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32008,Roads,Completed,NN-ADYAR,171,4940000,"Laying cement concrete roads AT West Road - West CIT Nagar in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32009,Roads,Completed,NN-ADYAR,171,4940000,"Laying cement concrete roads at East Road - West CIT Nagar in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32010,Roads,Completed,NN-ADYAR,171,4398000,"Laying cement concrete roads at South Road - West CIT nagar in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32011,Roads,Completed,NN-ADYAR,171,3379000,"Laying cement concrete roads at 1 Cross Street - West CIT Nagar in Div-171, Unit-40, Zone - XIIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32012,Roads,Completed,NN-ADYAR,171,3585000,"Laying cement concrete roads at II Cross Street - West CIT Nagar in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32013,Roads,Completed,NN-ADYAR,171,3622000,"Laying cement concrete roads at III Cross Street - West CIT Nagar in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32014,Roads,Completed,NN-ADYAR,171,2126000,"Laying cement concrete roads at Govt. Farm I&II Street in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32015,Roads,Completed,NN-ADYAR,171,5281000,"Laying cement concrete roads at Vengadapuram slum I to VI street in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32018,Roads,Completed,NN-ADYAR,171,11033000,"Laying cement concrete roads at Vengadapuram Tenements I TO XV streets in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/32019,Roads,Completed,NN-ADYAR,171,15492000,"Laying cement concrete roads at Rengarajapuram I TO VI streets in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/32020,Roads,Completed,NN-ADYAR,171,2084000,"Laying cement concrete roads at Ponniammankoil street in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/32021,Roads,Completed,NN-ADYAR,171,5130000,"Laying cement concrete roads at Surya nagar slum roads in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/32022,Roads,Completed,NN-ADYAR,171,3530000,"Laying cement concrete roads at Gandhipuram I TO III street in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/32023,Roads,Completed,NN-ADYAR,171,3530000,"Laying cement concrete roads at Subbupillai thottam I TO III street in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/32024,Roads,Completed,NN-ADYAR,171,380000,"Laying cement concrete roads at Bharathidasan III cross street in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32025,Roads,Completed,NN-ADYAR,171,1517000,"Laying cement concrete roads at Bharathidasan East street in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32026,Roads,Completed,NN-ADYAR,171,2025000,"Laying cement concrete roads at Railway Border I street (Kavery Nagar) in Div-171, Unit-40, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/32040,Roads,Completed,NN-ADYAR,171,534000,"Improvement and Repairs to Returning officer office at Saidapet in Dn-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32041,Roads,Completed,NN-ADYAR,171,989000,"Forming and laying the Road for Returning Officer office at Saidapet inside the Richards park in Dn-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/3205,Buildings,Completed,NN-ADYAR,180,2860000,PROPOSED CONSTRUCTION OF AMMA UNAVAGAM AT GOTHAWARI STREET BHARATHI NAGAR TARAMANI IN DIVISION-180 UNIT-39 ZONE-XIII,Own Sources,13,2015-16,2017-18 NN/2015-16/3206,Parks,Completed,NN-ADYAR,176,914250,"Improvements to Road side Park at Besant nagar 24th cross Street and Besant Nagar 4th Main road (Anna School Campus) in Dn-176, Unit -38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32241,Roads,Completed,NN-ADYAR,178,334000,"Proposed laying of Bituminous Concrete road at Vijaya Nagar 12th Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32243,Roads,Completed,NN-ADYAR,178,1076000,"Proposed laying of Bituminous Concrete road at Ram Nagar 8th Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32244,Roads,Completed,NN-ADYAR,178,367000,"Proposed laying of Bituminous Concrete road at A.G.S. Colony 5th Main Road (Part) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32245,Roads,Completed,NN-ADYAR,178,833000,"Proposed laying of Bituminous Concrete road at Yamuna Street (Part) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32247,Roads,Completed,NN-ADYAR,178,581000,"Proposed laying of Bituminous Concrete road at Alagappa Nagar Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32248,Roads,Completed,NN-ADYAR,178,577000,"Proposed laying of Bituminous Concrete road at Srinivasa Nagar 1st Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32250,Roads,Completed,NN-ADYAR,178,417000,"Proposed laying of Bituminous Concrete road at Vijaya Nagar 4th Cross Street (Part) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32251,Roads,Completed,NN-ADYAR,178,899000,"Proposed laying of Cement Concrete road at Throwpathy Amman Koil 2nd Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/32252,Roads,Completed,NN-ADYAR,179,1154000,"Proposed laying of Cement Concrete road at Karunambigai Colony in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32255,Roads,Completed,NN-ADYAR,179,1100000,"Proposed laying of Cement Concrete road at East Mada Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32256,Roads,Completed,NN-ADYAR,179,448000,"Proposed laying of Cement Concrete road at East Mada Lane in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32258,Roads,Completed,NN-ADYAR,179,1448000,"Proposed laying of Cement Concrete road at Putherikarai Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32259,Roads,Completed,NN-ADYAR,179,920000,"Proposed laying of Cement Concrete road at Theradi Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32266,Roads,Completed,NN-ADYAR,171,541000,"Providing Thermoplastic Compound marking and Road Pavement Markers at Todhunder Nagar Main Road in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32267,Roads,Completed,NN-ADYAR,171,959000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Todhunder Nagar Main Road (6th Reach ) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32268,Roads,Completed,NN-ADYAR,171,989000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Todhunder Nagar Main Road (5th Reach ) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32269,Roads,Completed,NN-ADYAR,171,957000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Todhunder Nagar Main Road (4th Reach ) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32270,Roads,Completed,NN-ADYAR,171,966000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Todhunder Nagar Main Road (3rd Reach ) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32271,Roads,Completed,NN-ADYAR,171,975000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Todhunder Nagar Main Road (2nd Reach ) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32272,Roads,Completed,NN-ADYAR,171,969000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Todhunder Nagar Main Road from the junction of Anna Salai (1st Reach ) in DN-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32345,Buildings,Completed,NN-ADYAR,174,999000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL IN 3rd ST MASUTHI COLONY,VELACHERY IN DVN-174, UNIT-40A, ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/32346,Electrical,Completed,NN-ADYAR,174,867000,"PROPOSED ADDITIONAL CONSTRUCTION OF FIRST FLOOR IN MULTIPURPOSE HALL IN 3rd ST MASUTHI COLONY,VELACHERY IN DVN-174, UNIT-40A, ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/32462,Roads,Completed,NN-ADYAR,182,993000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Thiruvalluvar Nagar 2nd Avenue from Thiruvalluvar Nagar 1st Avenue to New Beach Road in DN-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32465,Roads,Completed,NN-ADYAR,182,985000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Thiruvalluvar Nagar 2nd Avenue from TNHB Flats (Kurinji, Mullai Flats) to 2nd Avenue Park in DN-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32466,Roads,Completed,NN-ADYAR,182,979000,"Relaying the road with BCCMP 30mm thick using by Paver Finisher at Thiruvalluvar Nagar 2nd Avenue from New Beach Road to TNHB Flats (Kurinji, Mullai Flats) in DN-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32468,Roads,Completed,NN-ADYAR,182,655000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Thiruvalluvar Nagar 2nd Avenue in DN-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32471,Roads,Completed,NN-ADYAR,182,2484000,"INSTALLATION OF WATER TREATMENT PLANT, MAINTENANCE AND OPERATION OF THE PLANT AT BALAKRISHNA STREET, THIRUVANMIYUR IN DIVISION - 182, UNIT - 39, ZONE - XIII",Own Sources,13,2015-16,2018-19 NN/2015-16/32589,Roads,Completed,NN-ADYAR,180,2624000,"Proposed laying of Bituminous Concrete road at Kamarajar Nagar 1st Main Road in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/32590,Roads,Completed,NN-ADYAR,180,2147000,"Proposed laying of Bituminous Concrete road at Canal Road in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/32625,Roads,Completed,NN-ADYAR,180,1625000,"Proposed laying of Bituminous Concrete road at 2nd West Street, Kamaraj Nagar in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/32626,Roads,Completed,NN-ADYAR,180,694000,"Proposed laying of Bituminous Concrete road at 3rd West Street, Kamaraj Nagar in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/32627,Roads,Completed,NN-ADYAR,180,2848000,"Proposed laying of Cement Concrete road at Ilaiyaraja Kudieruppu 1st, 2nd, 3rd & Link Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32628,Roads,Completed,NN-ADYAR,180,1042000,"Proposed laying of Cement Concrete road at J.P. Nagar, Thiruvanmiyur - Gandhi Street (Part) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32629,Roads,Completed,NN-ADYAR,180,4304000,"Proposed laying of Cement Concrete road at M.G.R. Nagar - Kamarajar Street, Karumariamman Koil Street, Periyar Street, Anna Street, Ambedkar Street, Karunanidhi Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/32630,Roads,Completed,NN-ADYAR,180,1984000,"Proposed laying of Cement Concrete road at M.G.R. Nagar - Anna Lane, Ambedkar Lane, Kamarajar Lane, Karunanidhi 1st Lane, Karunanidhi 2nd Lane, Karunanidhi 3rd Lane, Mariamman Koil 1st Lane, 2nd Lane, 3rd Lane, 4th Lane, 5th Lane & 6th Lane in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32631,Roads,Completed,NN-ADYAR,180,2380000,"Proposed laying of Cement Concrete road at Taramani - Perumal Koil Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32632,Roads,Completed,NN-ADYAR,180,1392000,"Proposed laying of Cement Concrete road at Taramani - Govindapillai Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32633,Roads,Completed,NN-ADYAR,180,2940000,"Proposed laying of Cement Concrete road at Taramani - Anna Street (Part), M.G. Nagar - T.K. Kabali Street (Part) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32635,Roads,Completed,NN-ADYAR,180,3486000,"Proposed laying of Cement Concrete road at Taramani - V.O.C. Street, Indira Gandhi Street, Kamarajar Street, Thiru. Vi.Ka. Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32639,Roads,Completed,NN-ADYAR,180,930000,"Proposed laying of Cement Concrete road at Taramani - Avvaiyar Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32642,Roads,Completed,NN-ADYAR,180,2251000,"Proposed laying of Cement Concrete road at Anna Nagar - Tamirabarani Street, Godavari Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32645,Roads,Completed,NN-ADYAR,180,2486000,"Proposed laying of Cement Concrete road at Anna Nagar - Vaigai Street, M.G. Nagar - Rajiv Gandhi Street, Kamarajar 1st Lane, Kamarajar 2nd Lane, Kamarajar 3rd Lane & Kamarajar 4th Lane in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32646,Roads,Completed,NN-ADYAR,180,6811000,"Proposed laying of Cement Concrete road at T.P. Nagar - Pillaiyar Koil Street, Nethaji Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/32648,Roads,Completed,NN-ADYAR,180,1311000,"Proposed laying of Cement Concrete road at M.G. Nagar - Periyar Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32649,Roads,Completed,NN-ADYAR,180,1675000,"Proposed laying of Cement Concrete road at M.G. Nagar - Quidemilleth Street, Avvaiyar Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32650,Roads,Completed,NN-ADYAR,180,1240000,"Proposed laying of Cement Concrete road at M.G. Nagar - Kamarajar Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32651,Roads,Completed,NN-ADYAR,180,2528000,"Proposed laying of Cement Concrete road at M.G. Nagar - Mosque Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32750,Road Cut,Completed,NN-ADYAR,178,736000,"Relaying of road with B.T. Course by using Paver finisher at Murugu Nagar 3rd Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32751,Road Cut,Completed,NN-ADYAR,178,736000,"Relaying of road with B.T. Course by using Paver finisher at Murugu Nagar 4th Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/32760,Electrical,Completed,NN-ADYAR,176,905000,"Providing Electrification for the proposed Fruits shops and Flower Shops at Durgabai Deshmuk road, (Near Thiru.Vi.Ka Bridge) Adyar, in Division-176, Zone-13",Own Sources,13,2015-16,2019-20 NN/2015-16/32762,Electrical,Completed,NN-ADYAR,176,800000,"Providing Electrical metering panel baords, Power Distribution panel boards and laying of 3 1/2 x 120sqmm cable for proposed fruit shops and flower shops at Durgabai Deshmuk road, Adyar (Near T.V.K Bridge) in Div-176, Zone-13.",Own Sources,13,2015-16,2019-20 NN/2015-16/3287,Buildings,Completed,NN-ADYAR,170,189000,"OUTSOURCING OF PRIVATE CONSERVANCY OF CPS AT POONAMALLEE SCHOOL in Div 170, 40A, Zone - XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/3290,Roads,Completed,NN-ADYAR,176,975000,RELAYING THE ROAD WITH B.T SURFACE BY USING PAVER FINISHER AT PARAMESWARI NAGAR 1st STREET (ANWAR MIYAN GARDEN) IN DN-176 UNIT -38 ZONE-13,Own Sources,13,2015-16,2016-17 NN/2015-16/3291,Buildings,Completed,NN-ADYAR,171,94000,Outsourcing Scavenging Work for the CPS at Vengadapuram in Dn-171 Unit-40 Zone - 13,Own Sources,13,2015-16,2016-17 NN/2015-16/3296,Buildings,Completed,NN-ADYAR,170,280000,Outsourcing of Private Conservancy for CHSS (Maduvankarai )at Anna Salai in Dn -170 unit -40A Zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/3298,Buildings,Completed,NN-ADYAR,172,189000,Outsourcing Scavenging work for the CPS at Kotturpuram in Dn -172 unit -40 Zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/3301,Buildings,Completed,NN-ADYAR,172,284000,"Outsourcing Scavenging work for the CHS, CPS and KGS at New street in Dn -172 unit -40 Zone -13",Own Sources,13,2015-16,2016-17 NN/2015-16/3305,Buildings,Completed,NN-ADYAR,173,189000,Outsourcing of Private Conservancy in C.M.S at Park View street in Dn -173 unit -40 zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/33091,Roads,Completed,NN-ADYAR,170,776000,"Attending the temperory restoration of damaged roads at kalaimagal nager cross street due to flood in north East mansoon 2015 in DIV-170,Unit-40(A), ZONE-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/3310,Buildings,Completed,NN-ADYAR,175,380000,Outsourcing Scavenging work for the CHS And CPS at Kamaraj Avenue in Dn -175 unit -40 zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/33107,Buildings,Completed,NN-ADYAR,170,940000,"REPAIRS AND IMPROVEMENTS TO THE BURNING SHED AT ARULAYAMPET BURIAL GROUND IN DN-170 UT-40A, ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/33109,Electrical,Completed,NN-ADYAR,171,965000,"REPAIRS AND IMPROVEMENTS TO THE TOILET AT CHENNAI HIGHER SECONDARY SCHOOL at Little Mount IN DN-170,UNIT-40A,ZONE-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/33111,Electrical,Completed,NN-ADYAR,170,990000,"PROVIDING GRANITE FOOTPATH AT SOUTH SIDE OF HOSPITAL ROAD (REACH-2),NEAR PARSAN COMPLEX) IN DN -170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/33112,Electrical,Completed,NN-ADYAR,170,990000,"PROVIDING GRANITE FOOTPATH AT NORTH SIDE OF HOSPITAL ROAD (REACH-2),OPP TO PARSAN COMPLEX) IN DN -170,UT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/3312,Buildings,Completed,NN-ADYAR,175,189000,Outsourcing Scavenging work for the CPS at Indira Nagar 29th Cross Street in Dn -175 unit -40 zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/3314,Buildings,Completed,NN-ADYAR,177,189000,Outsourcing Scavenging work for the CPS at TNHB Colony 3 rd Avenue in Dn-177 Unit-40A zone - 13,Own Sources,13,2015-16,2016-17 NN/2015-16/3315,Parks,Completed,NN-ADYAR,174,380000,Outsourcing scavenging work for the Chennai High School & Middle School at Five Furlong Road in Dn -174 Unit -40A Zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/3316,Buildings,Completed,NN-ADYAR,174,189000,Outsourcing scavenging work for the Chennai Primary School at Five Furlong Road in Dn -174 Unit -40A Zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/33271,Buildings,Completed,NN-ADYAR,172,882000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at River View Road (Reach-4) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/33273,Buildings,Completed,NN-ADYAR,172,887000,"Relaying the road with BCCMP 40mm thick using by Paver Finisher at River View Road (Reach-5) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/33291,Roads,Completed,NN-ADYAR,172,930000,"Relaying the road with BCCMP1 40mm thick using by Paver Finisher at Arunachalam Road (Reach-2) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/33316,Roads,Completed,NN-ADYAR,172,610000,"Relaying the road with BCCMP1 30mm thick using by Paver Finisher at Kottur Garden 4th Main Road Extn.(Reach-2) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/33319,Roads,Completed,NN-ADYAR,172,790000,"Relaying the road with BCCMP1 40mm thick using by Paver Finisher at Lake View Road (Only Damaged Portion Reach-2) in DN-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/33352,Road Cut,Completed,NN-ADYAR,176,844000,"Widening the Road Portion by Paver Finisher at Durgabai Deshmukh Road (near Flower Bazar) in Dn-176, Uni-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/3337,Storm Water Drain,Completed,NN-ADYAR,170,226000,"Desilting munuswamy street poomagal main road dhanakotti raja street thiruvasagam street pillaiyar koil 1,2,3 street balaji nagar main road reddy street 1,2,3 arulayammanpet 1,2 street in div -170,unit-40A,zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/33479,Buildings,Completed,NN-ADYAR,180,994000,"Providing Retro Reflection stainless steel street name board at Kanagam and Tharamani in Dn-180, Unit- 39, Zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/33687,Roads,Completed,NN-ADYAR,174,970000,"Attending temporary restoration of damaged road at Angalamman Koil II Street, City Limit Road ( Secreteriate Colony), Chandran Street, Gulmohar Avenue due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33689,Roads,Completed,NN-ADYAR,174,970000,"Attending temporary restoration of damaged road at Narasingapuram 7th Street, Sathanipet I & II Street and Balaji Avenue due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33695,Roads,Completed,NN-ADYAR,174,875000,"Attending temporary restoration of damaged road at Cross street connecting Periyar, Anbil Dharmalingam, Veerapandiya Kattabhomman and Madhavan Streets due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33697,Roads,Completed,NN-ADYAR,174,987000,"Attending temporary restoration of damaged road at Raceview colony II Street, Narasingapuram Main Road and Narasingapuram III Cross Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33699,Roads,Completed,NN-ADYAR,174,994000,"Attending temporary restoration of damaged road at Pillayar Koil Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33700,Roads,Completed,NN-ADYAR,174,470000,"Attending temporary restoration of damaged road at Ganesh Nagar Nethaji Road, Sengeniamman Koil Main Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33701,Roads,Completed,NN-ADYAR,174,988000,"Attending temporary restoration of damaged road at Cartrack due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33703,Roads,Completed,NN-ADYAR,174,623000,"Attending temporary restoration of damaged road at Ambedkarnagar due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33704,Roads,Completed,NN-ADYAR,174,350000,"Attending temporary restoration of damaged road at Radhakrishna Street, Madhavan Street and Nedunchezhian Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33705,Roads,Completed,NN-ADYAR,174,995000,"Attending temporary restoration of damaged road at Veerapandia Kattabhomman Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33706,Roads,Completed,NN-ADYAR,174,995000,"Attending temporary restoration of damaged road at Anbil Dharmalingam Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33707,Roads,Completed,NN-ADYAR,174,976000,"Attending temporary restoration of damaged road at Gandhi Street, and at the junction of Anna Garden II Street & Velachery Main Road due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33708,Roads,Completed,NN-ADYAR,174,1640000,"Attending temporary restoration of damaged road at Periyar Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33709,Roads,Completed,NN-ADYAR,174,948000,"Attending temporary restoration of damaged road at Janakpuri I and II Street due to floods in North East Monsoon 2015 in Division - 174, Unit - 40A, Zone - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/33938,Roads,Completed,NN-ADYAR,176,994200,"Improvement to the road side park And DD road using the WMM ,GSB, at (near the flower shop) in Dn-176, unit-38, zone-13",Own Sources,13,2015-16,2017-18 NN/2015-16/34012,Buildings,Completed,NN-ADYAR,182,970000,"IMPROVEMENTS TO BURIAL GROUND AT 7 TH CROSS STREET, THIRUVANMIYUR IN DIVISION 182 UNIT 38 ZONE 13",Own Sources,13,2015-16,2017-18 NN/2015-16/34013,Footpath,Completed,NN-ADYAR,182,830000,PROVIDING COMPOUND WALL AND IMPROVEMENT WORKS TO AMMA KUDINEER THITTAM AT BALAKRISHNA ROAD IN DIVISION 182 UNIT 38 ZONE 13,Own Sources,13,2015-16,2017-18 NN/2015-16/34103,Buildings,Completed,NN-ADYAR,175,316000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at Gandhi Nagar Canal Bank Road in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34104,Buildings,Completed,NN-ADYAR,175,346000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at Gandhi Nagar Canal Bank Road in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34105,Buildings,Completed,NN-ADYAR,173,344000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at Anna Sathya Nagar (Adyar Bridge) ,in Div-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34106,Buildings,Completed,NN-ADYAR,173,316000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at Anna Sathya Nagar (Adyar Bridge) ,in Div-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34107,Buildings,Completed,NN-ADYAR,173,344000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at Karpagam avenue in Division ?173, Unit ? 40, Zone ? 13 -",Own Sources,13,2015-16,2016-17 NN/2015-16/34108,Buildings,Completed,NN-ADYAR,173,316000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at Karpagam avenue in Division ?173, Unit ? 40, Zone ? 13 -",Own Sources,13,2015-16,2016-17 NN/2015-16/34109,Buildings,Completed,NN-ADYAR,175,316000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at Baktavatchalam Nagar Kamaraj Avenue 1st Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34110,Buildings,Completed,NN-ADYAR,175,316000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at Baktavatchalam Nagar Kamaraj Avenue 1st Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34111,Buildings,Completed,NN-ADYAR,175,316000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at Aishwarya Colony 14th Cross Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34112,Buildings,Completed,NN-ADYAR,175,316000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at Aishwarya Colony 14th Cross Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34113,Roads,Completed,NN-ADYAR,180,316000,"Supply, Installation of Smart Toilet (Disabled) with free maintenance for three Years at Indra nagar Nagar in Dn-175, Unit-40, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/34114,Roads,Completed,NN-ADYAR,180,316000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at Indra nagar in Dn-175 Unit-40, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/34115,Roads,Completed,NN-ADYAR,175,316000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at Indra nagar XVIII cross street in Dn-175, Unit-40, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/34125,Buildings,Completed,NN-ADYAR,173,316000,"Supply, Installation of Smart Toilet (Ladies) with free maintenance for three Years at R.K.Nagar IV cross street (Gents) in Division ?173, Unit ? 40, Zone ? 13",Own Sources,13,2015-16,2016-17 NN/2015-16/34126,Buildings,Completed,NN-ADYAR,173,344000,"Supply, Installation of Smart Toilet (Gents) with free maintenance for three Years at R.K.Nagar IV cross street in Division ?173, Unit ? 40, Zone ? 13",Own Sources,13,2015-16,2016-17 NN/2015-16/34434,Buildings,Completed,NN-ADYAR,171,982000,"Proposed Construction of Multi Purpose Hall at jothiammal nagar in Div - 171, Unit 40, Zone - XIII.",Own Sources,13,2015-16,2018-19 NN/2015-16/34435,Buildings,Completed,NN-ADYAR,171,942000,"Provision of water supply and Electrical Supply for Multi Purpose Hall at jothiammal nagar in div-171, Unit-40, Zone-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/34462,Roads,Completed,NN-ADYAR,173,2739000,"Relaying of road with BC 30mm thick by Paver at M.R.C. Nagar Main Road in Division - 173, Unit - 40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/34463,Roads,Completed,NN-ADYAR,173,979000,"Relaying of road with BC 30mm thick by Paver at Vasantha Avenue in Division - 173, Unit - 40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/34464,Roads,Completed,NN-ADYAR,173,968000,"Relaying of road with BC 30mm thick by Paver at Kasturi Avenue in Division - 173, Unit - 40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/34465,Roads,Completed,NN-ADYAR,173,1409000,"Relaying of road with BC 30mm thick by Paver at South Canal Bank 1st Loop Street in Division - 173, Unit - 40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/34466,Roads,Completed,NN-ADYAR,173,3008000,"Relaying of road with BC 30mm thick by Paver at Thandavarayan Street in Division - 173, Unit - 40, Zone - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/34491,Buildings,Completed,NN-ADYAR,178,998000,"DESILTING OF SWD AT VARIOUS STREETS USING SUCKER IN DIVISIONS 178, 179 & 180",Own Sources,13,2015-16,2016-17 NN/2015-16/34492,Playfields,Completed,NN-ADYAR,182,992000,"DESILTING OF SWD AT VARIOUS STREETS IN DIVISION-174, ZONE - XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/34796,Footpath,Completed,NN-ADYAR,176,393800,"Improvement of footpath in Besant nagar 6th avenue in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2019-20 NN/2015-16/34832,Roads,Completed,NN-ADYAR,177,678000,"ROPOSED LAYING OF CEMENT CONCRETE ROAD AT INDRA GANDHI NAGAR III STREET in DN-177,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/34833,Roads,Completed,NN-ADYAR,177,1525000,Proposed Laying of Cement Concrete Road at Kakkan Nagar 1st Cross Street in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34834,Roads,Completed,NN-ADYAR,177,2188000,Proposed Laying of Cement Concrete Road at Kakkan Nagar 2nd Cross Street in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34835,Roads,Completed,NN-ADYAR,177,1876000,Proposed Laying of Cement Concrete Road at Kakkan Nagar 3rd Cross Street in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34836,Storm Water Drain,Completed,NN-ADYAR,177,2940000,Proposed Laying of Cement Concrete Road at Kakkan Nagar 2nd Main Road in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34837,Roads,Completed,NN-ADYAR,177,1738000,"ROPOSED LAYING OF CEMENT CONCRETE ROAD AT INDRA GANDHI NAGAR V STREET in DN-177,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/34838,Roads,Completed,NN-ADYAR,177,1171000,"ROPOSED LAYING OF CEMENT CONCRETE ROAD AT INDRA GANDHI NAGAR IV STREET in DN-177,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/34839,Roads,Completed,NN-ADYAR,177,1525000,Proposed Laying of Cement Concrete Road at Sasthiri Nagar 2nd Main Road in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34840,Roads,Completed,NN-ADYAR,177,1482000,Proposed Laying of Cement Concrete Road at Sasthiri Nagar 4th CrossStreet in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34841,Roads,Completed,NN-ADYAR,177,3874000,Proposed Laying of Cement Concrete Road at Periyar Nagar 1st Street in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34842,Roads,Completed,NN-ADYAR,177,3192000,Proposed Laying of Cement Concrete Road at Kakkan Nagar 3rd Main Road in Division - 177 Unit -40A Zone -13,Own Sources,13,2015-16,2017-18 NN/2015-16/34875,Roads,Completed,NN-ADYAR,179,995000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at various streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/34975,Roads,Completed,NN-ADYAR,182,990000,"IMPROVEMENT OF FOOTPATH AT SOUTH AVENUE STREET(Left side) IN DIVISION-182, UNIT-38, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/34990,Buildings,Completed,NN-ADYAR,176,830000,"PROPOSED CONSTRUCTION OF MOTOR AND E.B ROOM FOR FRUIT AND FLOWER SHOP AT DHURGHABAI DESHMUCK ROAD, ADYAR IN DIV 176, UNIT-38, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/3611,Buildings,Completed,NN-ADYAR,180,310000,"DESILTING OF STORM WATER DRAIN AT 100 FT ROAD TARAMANI IN DIVISION - 180, UNIT - 39, ZONE - 13",Own Sources,13,2015-16,2016-17 NN/2015-16/3709,Footpath,Completed,NN-ADYAR,182,240000,"IMPROVEMENTS TO THE FOOTPATH AT MANGALAERI MAIN ROAD IN DN-182,U-40A,Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/3992,Buildings,Completed,NN-ADYAR,181,970000,"PROVIDING FLOORING AND ROOF TRUSS AT GYM BUILDING , VALMIKI STREET IN DN-181,U-38,Z-13.UNDER WARD COUNCILLOR FUND.",Own Sources,13,2015-16,2016-17 NN/2015-16/3993,Buildings,Completed,NN-ADYAR,181,980000,"PROVIDING FLOORING AND ROOF TRUSS AT GYM BUILDING , MUTHULAKSHMI STREET IN DN-181,U-38,Z-13 UNDER WARD COUNCILLOR FUND.",Own Sources,13,2015-16,2016-17 NN/2015-16/4110,Storm Water Drain,Completed,NN-ADYAR,176,951000,"Desilting and Repairs to Existing Storm Water Drain at Sastri Nagar 1st Main Road, 1st Avenue, 1st Cross Street, Jeevarathinam Nagar, Parameswari Nagar, Karpagam Garden 8th, 9th, 10th, 11th, 13th Cross Street, MG Road, Ramasamy Garden, Vasanthapress Salai, Kabali Thoattam, Venkateshwara Nagar, Parameshwari Nagar 1st street, Sastri Nagar 9th Lane, 2nd Cross street, Padmanathan 5th, 4th, 3rd, 1st Street, Besant Avenue and Adyar Bridge Road in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4172,Buildings,Completed,NN-ADYAR,182,918000,"Improvement to Park at Journalist Colony in Dn-182, Unit - 38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4199,Storm Water Drain,Completed,NN-ADYAR,173,814000,"Desilting and Improvement to Existing Storm Water Drain at Kesavaperumal Puram Cresent, Central, North Avenue, Greenways Road Extn., Bagirathi Ammal Street, Raja Street, Raja Street Extn, R.K.Mutt Road, Krishnapuri Main Road in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4201,Storm Water Drain,Completed,NN-ADYAR,173,935000,"Desilting and Improvement to Existing Storm Water Drain at Sathyadev Avenue West, East, Extn, Thandavarayan Street, Rohini Garden, Karpagam Avenue 4th Street, 4th Main Road, Janaki Avenue, Dr.D.G.S.Dinakaran Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4238,Storm Water Drain,Completed,NN-ADYAR,180,435000,"IMPROVEMENTS OF RAISING MANHOLE DOOR AT BHARATHI NAGAR, THANTHAI PERIYAR NAGAR, ANNA STREET ( copy of road enclosed ) IN TARAMANI DN-180 , U-39 , Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/4243,Roads,Completed,NN-ADYAR,182,658000,"Forming Road at Pillaiyar Koil Street (Rajaji Nagar) in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/4244,Parks,Completed,NN-ADYAR,182,402000,"Providing 8 Walking Track and S.S.Handrails in Park at Journalist colony in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4251,Road Cut,Completed,NN-ADYAR,181,870000,"Restoration of Road Cut at Kalashektra Road,Justice Ramajayam Salai,Kamaraj Salai,Muthulakshmi Salai,TMM Street (made by TANTRANSCO TNEB) in Dn 181, Unit 38, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4256,Storm Water Drain,Completed,NN-ADYAR,182,940000,"DESILTING OF STROM WATER DRAINS AT SOUTH AVENUE, 6,8,9,13,14 EAST STREET, KAMARAJ NAGAR 3RD MAIN ROAD,5TH EAST STREET,KANNAPPA NAGAR,4TH MAIN ROAD,GANAPATPHY STREET,DHARRAAMBAL STREET,RAJAJI NAGAR MAIN ROAD,RAJAJI NAGAR 1ST CROSS STREET,CHITRAKULAM STREET,BHARATHIDASAN STREET,NORTH MADA STREET,PILLYAR KOIL STREET(RAJAJI NAGAR),ABIYA NAGAR THIRUVANMIYUR IN DIVISION-182 UNIT-38 ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/4434,Parks,Completed,NN-ADYAR,182,210000,"PROVIDING PLAY APPARATUS AND PARK BENCH IN PARK AT THIRUVALLUVAR NAGAR 1ST AVENUE IN DN-182, UNIT-38, ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/4460,Road Cut,Completed,NN-ADYAR,181,880000,"Restoration of Road Cut at Anna Street,Appar Sreet,Sivasundar Avenue(made by TANTRANSCO TNEB) in Dn 181, Unit 38, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4502,Parks,Completed,NN-ADYAR,173,962000,"GREENERY IMPROVEMENT OF CENTER MEDAN AT D.G.S DINAGAR SALAI D.D ROAD AND GREENWAYS ROAD IN DIV-173,UNIT-40,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/4532,Storm Water Drain,Completed,NN-ADYAR,174,982000,"DESILTING OF STORM WATER DRAIN AND MISSING MANHOLE DOOR AT VARIOUS STREET IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4535,Storm Water Drain,Completed,NN-ADYAR,171,978000,"DE-SILTING AND IMPROVEMENTS TO STORM WATER DRAIN AT ALL THE STREETS IN JOTHIAMMAL NAGAR, VENGADAPURAM AND SRINAGAR COLONY, GOVERNMENT FORM, MOSQUE GARDEN, CHINNAYA THOTTAM, VINAYAGAR KIOL STREET, IN DIVISION 171, UNIT 40 , ZONE 13",Own Sources,13,2015-16,2016-17 NN/2015-16/4538,Storm Water Drain,Completed,NN-ADYAR,174,961000,"DESILTING OF STORM WATER DRAIN AND MISSING MANHOLE DOOR AT VARIOUS STREET IN DN-174,UT40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/4555,Roads,Completed,NN-ADYAR,175,360000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT GANDHI NAGAR 1,2,3 & 4th MAIN ROAD, GANDHI NAGAR 2nd CROSS STREET,CANAL BANK ROAD,PUMPING STATION ROAD,CRESCENT PARK 1 & 2nd ROAD, CRESCENT AVENUE, CANAL 3rd CROSS STREET IN DN-175, UNIT-40, ZONE-13",Own Sources,13,2015-16,2017-18 NN/2015-16/4561,Storm Water Drain,Completed,NN-ADYAR,179,759000,"Desilting, Repairs and Providing Silt Catch Pit to Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/4565,Storm Water Drain,Completed,NN-ADYAR,179,998000,"Desilting, Repairs and Providing Silt Catch Pit to Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/4567,Storm Water Drain,Completed,NN-ADYAR,179,790000,"Desilting, Repairs and Providing Silt Catch Pit to Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/4568,Storm Water Drain,Completed,NN-ADYAR,179,852000,"Desilting, Repairs and Providing Silt Catch Pit to Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/4693,Storm Water Drain,Completed,NN-ADYAR,180,640000,"DESILTING OF STORM WATER DRAIN AT WEST AVENUE ROAD ( NORTH & SOUTH SIDE ) AND C.S.I.R ROAD ( NORTH & SOUTH SIDE ) IN DIVISION - 180, UNIT - 39, ZONE - 13",Own Sources,13,2015-16,2016-17 NN/2015-16/4697,Buildings,Completed,NN-ADYAR,179,1899000,"Supply and Fixing of Namma Toilet 1+2 Women, 2 Regular Men, 2 Urinal on the inside of Velachery MRTS Railway Station Campus at Velachery - Tambaram Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4758,Buildings,Completed,NN-ADYAR,175,396000,"Water supply and Drainage connection Arrangements at Kasthuribai nagar 2nd cross street (In front of Metro water office) in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4780,Buildings,Completed,NN-ADYAR,175,375000,"Water supply and Drainage connection Arrangements at Kasthuribai nagar 2nd cross street (Junction of Kasthuribai nagar 2nd Main road) in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4781,Buildings,Completed,NN-ADYAR,175,350000,"Water supply and Drainage connection Arrangements at Indira Nagar 3rd Avenue (Junction of L.B.Road) in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/4973,Roads,Completed,NN-ADYAR,182,980000,"Relaying the Road with BCCMP 40mm thick by paver finisher at Rajaji Nagar Pillaiyar Koil Street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/5018,Parks,Completed,NN-ADYAR,173,998000,"IMPROVEMENTS TO TRAFFIC ISLAND AT R.K.MUTT ROAD IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/5019,Parks,Completed,NN-ADYAR,173,690000,"ADDITIONAL IMPROVEMENTS TO TRAFFIC ISLAND R.K.MUTT ROAD IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/5020,Parks,Completed,NN-ADYAR,173,910000,"IMPROVEMENTS TO TRAFFIC ISLAND NEAR RAJ PALACE AT.P.S.KUMARASAMY RAJA SALAI AND NEAR AYYAPPAN TEMPLE AT D.G.S.DINAKARAN SALAI IN DN-173, UNIT-40, ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/5317,Roads,Completed,NN-ADYAR,176,766000,"Attending Cement Concrete Road Patch work at Thiruvalluvar Nagar 1st and 2nd Street, Ellaiamman Koil Street and Bajanai Koil Street in Urur Alcot Kuppam in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/5407,Storm Water Drain,Completed,NN-ADYAR,172,978000,"Desilting and Improvement to Exisiting Storm Water Drain at Guruvappa Street, Pondichery road,Peeliamman Koil Street, Kottur Garden II Cross Street, Narikuravar Colony, Angalamman Koil Street, Kottur Garden Cresent road, Sriram Nagar Main Road, Pallipattu Main Road and CPT Polytechnic in Dn-172, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/5411,Road Cut,Completed,NN-ADYAR,179,565000,"Restoration of Road Cut made by CMWSSB at Bethel Avenue Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/5423,Storm Water Drain,Completed,NN-ADYAR,179,252000,"Desilting and Improvements to Storm Water Drain at Dhandapani Street & Shanthi 2nd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/5425,Road Cut,Completed,NN-ADYAR,179,590000,"Restoration of Road Cut made by CMWSSB at V.G.P. Selva Nagar 2nd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/5430,Road Cut,Completed,NN-ADYAR,179,507000,"Restoration of Road Cut made by CMWSSB at Bethel Avenue 1st Street, 2nd, 3rd & 4th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/5432,Road Cut,Completed,NN-ADYAR,179,397000,"Restoration of Road Cut made by CMWSSB at V.G.P. Selva Nagar Extn., 5th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/5433,Road Cut,Completed,NN-ADYAR,179,449000,"Restoration of Road Cut made by CMWSSB at V.G.P. Selva Nagar 3rd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/5478,Buildings,Completed,NN-ADYAR,175,425000,Improvements and proposed Construction of Baby toilet for NNMP Shed No:33603110111 at Mallipoo Nagar in Dn-175 Unit-40 Zone-13,Own Sources,13,2015-16,2016-17 NN/2015-16/5567,Buildings,Completed,NN-ADYAR,182,995000,"Proposed Footpath Repair and Providing Bin platform & Rain water Harvesting at various streets in Division 182, Unit 38, Zone-XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/5573,Buildings,Completed,NN-ADYAR,182,617000,"Proposed rain water Harvesting at Various streets in Division-182, Unit-38, Zone-13",Own Sources,13,2015-16,2016-17 NN/2015-16/5607,Storm Water Drain,Completed,NN-ADYAR,180,995000,"DISMANTLING AND CONSTRUCTION OF ROAD SIDE DRAIN AT 3RD WEST STREET, KAMARAJ NAGAR, THIRUVANMIYUR IN DN-180,U39,Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/5615,Buildings,Completed,NN-ADYAR,181,967000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREETS IN DN-181,UNIT- 38 ,ZONE-13",Own Sources,13,2015-16,2016-17 NN/2015-16/5680,Buildings,Completed,NN-ADYAR,179,995000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Baby Nagar 1st cross street, Baby Nagar 2nd Main Road, Balaji Street, Seshadripuram in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/5757,Buildings,Completed,NN-ADYAR,175,640000,Repairs and Improvements to Baby toilet for NNMP Shed No:33603110119 at Indira Nagar 18th Cross Street in Dn-175 Unit-40 Zone -13,Own Sources,13,2015-16,2016-17 NN/2015-16/5830,Buildings,Completed,NN-ADYAR,182,818000,"Providing Weathering Course arrangement & Improvement to Electrical Room, Revenue Room & Worker Rest Room in Unit-38 Office at 8th East Street Thiruvanmiyur in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/5935,Playfields,Completed,NN-ADYAR,178,988000,"IMPROVEMENTS TO PLAY GROUND (UNDER COUNCILOR FUND) AT RAMNAGAR 7th MAIN ROAD DN -178,UNIT- 39,ZONE -13",Own Sources,13,2015-16,2016-17 NN/2015-16/5944,Footpath,Completed,NN-ADYAR,176,782000,"Improvements to footpath at 6th Street & Ellaiamman Koil Street at Sastri Nagar in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6027,Roads,Completed,NN-ADYAR,177,670000,"LAYING INTERLOCKING PAVER BLOCK (ILP 80 A) ROAD SIDE AT MAHALAKSHMI NAGAR 7 TH CROSS STREET -1 IN DIV-177 , UNIT-40 A , ZONE -13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6033,Roads,Completed,NN-ADYAR,177,755000,"LAYING INTERLOCKING PAVER BLOCKS (ILP 80 A)ROAD SIDE AT MAHALAKSHMI NAGAR 8th CROSS STREET IN DN-177 UNIT-40A ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6036,Roads,Completed,NN-ADYAR,177,739000,"LAYING INTERLOCKING PAVER BLOCKS (ILP 80 A)ROAD SIDE AT MAHALAKSHMI NAGAR 9th CROSS STREET IN DN-177 UNIT-40A ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6106,Roads,Completed,NN-ADYAR,179,995000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Tansi Nagar 7th Street, 3rd Street & 20th Street, Dhandeeswaram Nagar 10th Cross Street & in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6112,Buildings,Completed,NN-ADYAR,175,997000,Improvements and water Supply works to Hospital Building at Venkatarathinam Nagar in Dn 175 Unit 40 Zone-13,Own Sources,13,2015-16,2017-18 NN/2015-16/6329,Road Cut,Completed,NN-ADYAR,179,304000,"Restoration of Road Cut made by CMWSSB at V.G.P. Selva Nagar Extn., 3rd and 4th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6331,Road Cut,Completed,NN-ADYAR,179,860000,"Restoration of Road Cut made by CMWSSB at V.G.P. Selva Nagar Extn., 1st Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6332,Road Cut,Completed,NN-ADYAR,179,989000,"Restoration of Road Cut made by CMWSSB at Sarathy Nagar 5th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6393,Parks,Completed,NN-ADYAR,178,998000,"PROVIDING STAINLESS STEEL HAND RAIL AND IMPROVEMENT TO GRANITE FOOT PATH TO PARK & PLAY FIELD (UNDER COUNCILOR FUND) AT A.G.S. COLONY 4TH CROSS STREET JN. OF A.G.S. COLONY 4TH MAIN ROAD IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6396,Parks,Completed,NN-ADYAR,178,976000,"PROVIDING PLAY APPARATUS TO PARK & PLAY FIELD AT A.G.S. COLONY 4TH CROSS STREET JN. OF A.G.S. COLONY 4TH MAIN ROAD (UNDER COUNCILOR FUND) IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6410,Buildings,Completed,B-Buildings,177,999000,"PROPOSED CONSTRUCTION OF ADDITIONAL ROOM (TB CENTRE) AT THE HEALTH POST AT SASTHIRI NAGAR 4 TH STREET IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6466,Buildings,Completed,NN-ADYAR,179,4980000,"Proposed Construction of AMMA UNAVAGAM under the Velachery - Tambaram Flyover Bridge, Opp. to Velachery MRTS Railway Station at Velachery Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6507,Storm Water Drain,Completed,NN-ADYAR,181,985000,"Providing rain water harvesting arrangements at various street in division 181,u-38,z-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6539,Footpath,Completed,NN-ADYAR,181,277000,"IMPROVEMENTS AND REPAIRING WORKS OF CENTER MEDIAN AND ROAD SIDE PARK AT VALMIKI STREET, TIGER VARADHACHARI STREET,7TH AVENUE IN DN-181,U-38,Z-13",Own Sources,13,2015-16,2017-18 NN/2015-16/6622,Buildings,Completed,NN-ADYAR,182,323000,"Providing Baby Toilet arrangements in NNMP Shed 4 Nos: 100416, 100415, 100411, 100412 and Improvements to NNMP Shed at Avvai Nagar in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6667,Storm Water Drain,Completed,NN-ADYAR,179,2048000,"Proposed Construction of Side Drain in Size of 600x750 mm along V.G.P. Selva Nagar Extn., 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6726,Storm Water Drain,Completed,NN-ADYAR,179,2294000,"Proposed Construction of Side Drain in Size of 600x750 mm along V.G.P. Selva Nagar Extn., 4th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6741,Storm Water Drain,Completed,NN-ADYAR,179,1618000,"Proposed Construction of Side Drain in Size of 600x750 mm along V.G.P. Selva Nagar Extn., 5th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/6744,Storm Water Drain,Completed,NN-ADYAR,179,1465000,"Proposed Construction of Side Drain in Size of 600x750 mm along Dhandeeswaram Nagar 4th Avenue (From Jn. of Dhandeeswaram 7th Main Road to Jn. of Dhandeeswaram 4th Avenue West 2nd Cross Street) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2020-21 NN/2015-16/6837,Buildings,Completed,NN-ADYAR,170,996000,"Improvement to the existing Toilet in Nerupu Medu in Div - 170, Unit 40A, Zone - XIII.",Own Sources,13,2015-16,2017-18 NN/2015-16/6841,Buildings,Completed,NN-ADYAR,174,853000,"Improvement to the existing Toilet in Race Coure Road in Div - 174, Unit 40A, Zone - XIII.",Own Sources,13,2015-16,2018-19 NN/2015-16/6874,Buildings,Completed,NN-ADYAR,171,597000,"Improvements and repair works to the Public convenience at Jothiammal Nagar in Division - 171, Unit-40 , Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/6893,Buildings,Completed,NN-ADYAR,174,247000,"IMPROVEMENTS TO PUBLIC CONVEYENCE AT LINK ROAD AND VELACHERY MAIN ROAD IN DN-174,UNIT-40(A),ZONE-XIII",Own Sources,13,2015-16,2016-17 NN/2015-16/6978,Buildings,Completed,NN-ADYAR,181,915000,"MAINTENANCE OF PUBLIC CONVENIENCE AND PROVIDING RAMP,STAIRCASE HANDRAIL IN PUBLIC CONVENIENCE AND CORPORATION BUILDING AT ASTALAKSHMI KOIL STREET,ANNA COLONY,VAIGAI STREET IN DN-181,U-38,Z-13",Own Sources,13,2015-16,2016-17 NN/2015-16/7009,Buildings,Completed,NN-ADYAR,181,1598000,"LAYING CEMENT CONCRETE ROAD AT NAVABHARATH COLONY II STREET IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/7075,Roads,Completed,NN-ADYAR,179,512000,"Raising and Laying of C.C. Road at Varadharajapuram 2nd Lane in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7093,Buildings,Completed,NN-ADYAR,171,863000,"PAINTING FOOTPATH KERBS, MEDIANS, ROAD SIDE TREES IN VIEW OF THE HON'BLE PRIME MINISTER'S VISIT, INDEPENDENCE DAY CELEBRATIONS IN TALUK OFFICE ROAD, SARDAR PATEL ROAD AND GANDHIMANDAPAM ROAD IN DIVISION 171& 172, UNIT 40, ZONE 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7131,Buildings,Completed,NN-ADYAR,179,661000,"Improvements In First Floor To Velachery Health Post At Seva Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2017-18 NN/2015-16/7316,Buildings,Completed,NN-ADYAR,175,2575000,"Restoration of Road cut made by TNEB along Kasthuribai Nagar Canal Bank Road in Dn 175, Unit 40, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7319,Buildings,Completed,NN-ADYAR,179,216000,"Providing Water Supply and Drainage Arrangements to Namma Toilet inside of Velachery MRTS Railway Station Campus in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7320,Buildings,Completed,NN-ADYAR,179,171000,"Providing Water Supply and Drainage Arrangements to 'e' Toilet Velachery Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7359,Buildings,Completed,NN-ADYAR,176,235787,"Amma unavakam and sanitary office facility improvements at ramasamy avenue(shastry nagar near) in unit-38, zone13, Dn-176",Own Sources,13,2015-16,2016-17 NN/2015-16/7362,Roads,Completed,NN-ADYAR,175,1835000,"Restoration of Road cut made by TNEB along Kamarajar Avenue 1st street in Dn 175, Unit 40, Zone 13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7446,Buildings,Completed,NN-ADYAR,175,450000,"Repairs and Improvements to Toilet (gents and Ladies), 1st Floor, Regional Joint Commissioner Office (South) Annex Building at Thiruvengadam Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7862,Footpath,Completed,NN-ADYAR,174,570000,"Painting black and white for foot paths and trees at Race course road, Velachery main road, Five furlong road in Dn 174, Unit 40(A), Zone 13 in the view of Independence day Celebration 2015.",Own Sources,13,2015-16,2016-17 NN/2015-16/7865,Buildings,Completed,NN-ADYAR,176,455000,"Providing Bio Toilet Platform and Water Supply arrangement at Besant Nagar 2nd Avenue and Elliots Beach in Dn-176, Unit-38, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/7911,Footpath,Completed,NN-ADYAR,175,407000,"Painting Footpath Kerbs and Centre Median at Sardar Patel Road, Dr.Muthulakshmi Salai and Kalki Krishnamoorthy Salai in Dn.175, Unit-40, Zone-13 in the view of Independence Day Celebration 2015",Own Sources,13,2015-16,2016-17 NN/2015-16/7912,Footpath,Completed,NN-ADYAR,173,910000,"Painting Footpath Kerbs, Trees and Centre Median at Durgabai Deshmukh Road, DR.D G S Dinakaran Salai, R. K. Mutt Road, P.S. Kumarasamy Raja Road, Brodies Castle Road in Dn.173, Unit-40, Zone-13 in the view of Independence Day Celebration 2015",Own Sources,13,2015-16,2016-17 NN/2015-16/7927,Footpath,Completed,NN-ADYAR,176,440000,"Painting Footpath Kerbs, Trees and Centre Median at D.D. Road, Besant Avenue and Besant nagar 3rd Avenue in Dn-176, Unit-38, Zone-13. In the view of Independence Day Celebration 2015",Own Sources,13,2015-16,2017-18 NN/2015-16/8180,Buildings,Completed,NN-ADYAR,182,458000,"Providing Bio Toilet Platform (2 Nos) and Water Supply arrangement at Thiruvalluvar nagar Beach and Avai Nagar in Dn-182, Unit-38, Zone-13.",Own Sources,13,2015-16,2018-19 NN/2015-16/8263,Buildings,Completed,NN-ADYAR,170,990000,"PROVIDING AND FIXING STAINLESS STEEL NAME BOARD USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DN-170,UT-40A ,ZONE-13.(V G P SALAI,GANAPATHY COLONY ,ALANDUR ROAD ETC.,)UNDERCOUNCILLOR WARD IMPROVEMENT FUND",Own Sources,13,2015-16,2016-17 NN/2015-16/8322,Buildings,Completed,NN-ADYAR,175,515000,"Repairs and Improvements to Public conveyance at Canal Bank Road (Aranganal salai) in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/8323,Buildings,Completed,NN-ADYAR,175,825000,"Repairs and Improvements to Ground Floor and 1st Floor Zonal office Building at Dr.Muthulakshmi Salai in Div-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/8324,Buildings,Completed,NN-ADYAR,175,830000,"Repairs and Improvements to 2nd Floor Zonal office Building at Dr.Muthulakshmi Salai in Div-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/8326,Buildings,Completed,NN-ADYAR,175,980000,"Forming Road at Parking area In Front of Division Office Building-175 at Thiruvengadam Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/8837,Buildings,Completed,NN-ADYAR,172,273000,"Painting Black and White at Kamarajar Salai, P.S.K.Salai, Durgabai Deshmuk in view of CM visit to Ramachandra Adithanar Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/8888,Roads,Completed,NN-ADYAR,175,600000,Construction Basement and Beautification for Bio - Toilet at Indira Nagar 2nd Avenue in Dn-175 Unit - 40 Zone - 13,Own Sources,13,2015-16,2016-17 NN/2015-16/9118,Roads,Completed,NN-ADYAR,176,777000,"Restoration of Road cut made by TNEB along Karpagam garden 2nd cross street in DN 176, Unit 38, zone 13",Own Sources,13,2015-16,2017-18 NN/2015-16/9120,Roads,Completed,NN-ADYAR,176,352000,"Restoration of Road cut made by TNEB along Jeevarathinam Nagar 1st street (Shanthi colony) in Dn 176, Unit 38, Zone 13",Own Sources,13,2015-16,2017-18 NN/2015-16/9187,Buildings,Completed,NN-ADYAR,181,475000,PAVING WITH INTERLOCK PAVERS AND PROVIDING WITH INSPECTION CHAMBERS AT DOBIKANA IN THIRUVANMIYUR AT DIVISION 181,Own Sources,13,2015-16,2017-18 NN/2015-16/9299,Buildings,Completed,NN-ADYAR,181,1363515,"LAYING CEMENT CONCRETE ROAD AT ARUNDEL BEACH ROAD IN DIVISION - 181, ZONE - XIII",Own Sources,13,2015-16,2017-18 NN/2015-16/9471,Buildings,Completed,NN-ADYAR,170,969000,"Construction of Multi Purpose Hall in Alandur Road in Div - 170, Unit 40A, Zone - XIII.",Own Sources,13,2015-16,2016-17 NN/2015-16/9472,Buildings,Completed,NN-ADYAR,170,857000,"Provision of water Supply and Electrical Supply for Multi Purpose Hall in Alandur Road in Div - 170, Unit 40A, Zone -III.",Own Sources,13,2015-16,2016-17 NN/2015-16/9498,Buildings,Completed,NN-ADYAR,173,974000,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE AT VARIOUS STREET AND PROVIDING S.S. HANDRAIL NEAR DIVISION OFFICE FOOTPATH AT KAMARAJAR SALAI IN DN-173, UNIT-40, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/9634,Roads,Completed,NN-ADYAR,175,982000,PROVIDING STREET NAME BOARD AT VARIOUS STREET (WARD COUNCILAR FUND) IN DN-175 UNIT-40 ZONE-13,Own Sources,13,2015-16,2016-17 NN/2015-16/9636,Roads,Completed,NN-ADYAR,175,982000,PROVIDING STREET NAME BOARD AT VARIOUS STREET (WARD COUNCILAR FUND) IN DN-175 UNIT-40 ZONE-13,Own Sources,13,2015-16,2016-17 NN/2015-16/9686,Buildings,Completed,NN-ADYAR,174,474000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND PLATFORM TO THE BIO TOILET AT RACE COURSE ROAD IN DN-174,UT-40A, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/9687,Buildings,Completed,NN-ADYAR,174,746000,"LAYING CC ROAD AT NEHRU NAGAR 4th STREET IN DN-174,UNIT-40A,ZONE-13.",Own Sources,13,2015-16,2017-18 NN/2015-16/9691,Buildings,Completed,NN-ADYAR,171,973500,"PROVIDING EWC AND MINOR REPAIRS TO THE PUBLIC TOILETS AT GOVERNMENT FORM ESTATE, SURYA NAGAR, VELACHERY MAIN ROAD, PARK, RAILWAY BORDER I STREET, JOTHIAMMAL NAGAR (NEW) IN DIV-171, UNIT-40, ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/9717,Buildings,Completed,NN-ADYAR,171,978000,"PROVIDING ACCESS PLATFORM, RAMP, WATER SUPPLY AND ELECTRICITY ARRANGEMENTS TO THE E-TOILETS AT VELACHERY MAIN ROAD AND TALUK OFFICE ROAD IN DIV-171, UNIT-40,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/9837,Buildings,Completed,NN-ADYAR,174,880000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND PLATFORM TO THE E-TOILET AT VELACHERY MAIN ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/9839,Buildings,Completed,NN-ADYAR,174,485000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND PLATFORM TO THE E-TOILET AT RACE COURSE ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/9853,Buildings,Completed,NN-ADYAR,177,744000,"Improvement work to Primary school in TNHB colony in Div -177, Unit 40A, Zone XIII.",Own Sources,13,2015-16,2017-18 NN/2015-16/9864,Buildings,Completed,NN-ADYAR,177,688000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND PLATFORM TO THE E-TOILET AT CITY LINK ROAD IN DN-177,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NN/2015-16/9868,Buildings,Completed,NN-ADYAR,177,810000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND PLATFORM TO THE E-TIOLETS AT TNHB COLONY AND SAKTHI VIJAYALAKSHAMI NAGAR IN DN-177,UT-40A,ZONE-13.",Own Sources,13,2015-16,2016-17 NP/2015-16/0130,Storm Water Drain,Completed,NP-PERUNGUDI,189,830000,"Raising and covering the existing storm water drain in Thulukanathamman Koil 16thStreet to 15th Street in DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/0165,Storm Water Drain,Completed,NP-PERUNGUDI,189,830000,"Raising and covering the existing storm water drain in Thulukanathamman Koil Main Road upto Thulukanathamman koil 17th street in DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/0306,Storm Water Drain,Completed,NP-PERUNGUDI,168,972000,"Improvement to NORTH side Side Drain at Indira street North Side in DN-168,UNIT-42,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/0391,Storm Water Drain,Completed,NP-PERUNGUDI,168,970000,"Improvements and repairs toSOUTH side drain at INDHIRA street in DN-168,UNIT-42,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/0393,Storm Water Drain,Completed,NP-PERUNGUDI,168,910000,"Improvements and repairs to INDHIRA 1ST AND 2nd Cross street in DN-168,unit-42,zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/0508,Storm Water Drain,Completed,NP-PERUNGUDI,185,993000,"IMPROVEMENT OF SIDE DRAIN BY RAISING SIDE WALL AND PROVIDING TOP SLAB AT M.K.STALIN STREET IN DIV-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/0509,Storm Water Drain,Completed,NP-PERUNGUDI,185,993000,"IMPROVEMENT OF SIDE DRAIN BY RAISING SIDE WALL AND PROVIDING TOP SLAP AT RADHA KRISHNAN STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/0540,Roads,Completed,NP-PERUNGUDI,184,995000,LAYING OF CEMENT CONCRETE ROAD AT HERITAGE VIJAYANDRA NAGAR MAIN ROAD(TELEPHONE NAGAR 16TH CROSS STREET TO HERITAGE NAGAR 2ND CROSS STREET)IN DN-184 UNIT-41 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/10331,Buildings,Completed,NP-PERUNGUDI,185,973000,"CONSTRUCTION OF ANGANVADI AT BURMA COLONY ROAD IN DIV-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/10332,Buildings,Completed,NP-PERUNGUDI,185,459000,"CONSTRUCTION OF TOILET,WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO ANGANVADI AT BURMA COLONY ROAD IN DN-185 UNIT-41 ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/10349,Buildings,Completed,NP-PERUNGUDI,185,946000,IMPROVEMENTS TO ANGANVADI AT KUPPAM BEACH IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/10356,Buildings,Completed,NP-PERUNGUDI,188,990000,"CONSTRUCTION OF MULTI PURPOSE HALL AT MAHALAKSHMI NAGAR BHARATHIYAR SALAI IN DN - 188, UNIT - 42, ZONE - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/10366,Buildings,Completed,NP-PERUNGUDI,188,990000,"CONSTRUCTION OF MULTI PURPOSE HALL AT MYLLAI BALAJI NAGAR 2ND BLOCK IN DN-188,U-42,Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/10399,Roads,Completed,NP-PERUNGUDI,191,356000,Forming Cement Concrete Road at Rice Mill road- Cross Street in Dn-191 U-43 Z-14 (Ward Councilor Fund 2015-16),Own Sources,14,2015-16,2016-17 NP/2015-16/10517,Buildings,Completed,NP-PERUNGUDI,188,600000,"CONSTRUCTION OF FRONT SHED, OUTER FLOORING & WATER SUPPLY ARRANGEMENTS TO MULTIPURPOSE HALL AT MAHALAKSHMI NAGAR BHARATHIYAR SALAI AND MYILLAI BALAJI NAGAR 2ND BLOCK IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/10520,Buildings,Completed,NP-PERUNGUDI,191,987000,"Proposed Construction of Multipurpose Hall at Ex-service man colony 2nd Street in dn-191, U-43, Z-14 (Ward Councilor Fund-2015-16)",Own Sources,14,2015-16,2016-17 NP/2015-16/10533,Playfields,Completed,NP-PERUNGUDI,191,984000,"Proposed Construction of Children Play Field in Pallavan Nagar 1st Street in dn-191, U-43, Z-14 (Ward Councilor Fund-2015-16)",Own Sources,14,2015-16,2016-17 NP/2015-16/10535,Parks,Completed,NP-PERUNGUDI,191,619000,"Proposed Construction of Park with Children Play Field in Pallavan Nagar 2nd Street in dn-191, U-43, Z-14 (Ward Councilor Fund-2015-16)",Own Sources,14,2015-16,2016-17 NP/2015-16/10850,Roads,Completed,NP-PERUNGUDI,188,420000,"PROVIDING STREET FURNITURES AT GOVINDASAMY NAGAR 1 TO 11 STREETS IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2017-18 NP/2015-16/10860,Playfields,Completed,NP-PERUNGUDI,190,997000,"Proposed construction of Children play Filed at Kovalam nagar in Dn-190, U-43, Z-14 (Ward Councilor Fund 2015-16)",Own Sources,14,2015-16,2016-17 NP/2015-16/10869,Buildings,Completed,NP-PERUNGUDI,184,991000,CONSTRUCTION OF MULTIPURPOSE HALL(PHASE-2) WEST SIDE AT MGR SALAI JN OF TNEB OFFICE ROAD IN DIV 184 UNIT 41 ZONE 14,MLACDS,14,2015-16,2016-17 NP/2015-16/10870,Roads,Completed,NP-PERUNGUDI,190,997000,"Proposed construction of RCC Road crossing Culverts at Various streets in Dn-190, U-43, Z-14 (Ward Councilor Fund 2015-16)",Own Sources,14,2015-16,2016-17 NP/2015-16/10872,Storm Water Drain,Completed,NP-PERUNGUDI,190,998000,"Proposed construction of All around the M S Fencing work at Thandukkaraikulam in Dn-190, U-43, Z-14 (Ward Councilor Fund 2015-16)",Own Sources,14,2015-16,2016-17 NP/2015-16/10873,Buildings,Completed,NP-PERUNGUDI,184,648000,"CONSTRUCTION OF COMPOUD WALL, SEPTIC TANK , ELECTRICAL ARRANGEMENTS AND WATER SUPPLY ARRANGEMENTS TO MULTI PURPOSE HALL PHASE 2 , WEST SIDE AT MGR SALAI JN OF TNEB OFFICE ROAD IN DIV - 184 , UNIT -41, ZONE -14.",Own Sources,14,2015-16,2016-17 NP/2015-16/11176,Storm Water Drain,Completed,NP-PERUNGUDI,185,686000,CONSTRUCTION OF SIDE DRAIN AT KARISHNA NAGAR 2ND STREET IN DIV 185 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/11219,Buildings,Completed,NP-PERUNGUDI,186,992000,"CONSTRUCTION OF CARETAKER ROOM AND PROVIDING WATER SUPPLY ARRANGEMENTS,FOOT PATH AT SEEVARAM BURIAL GROUND IN DN-186,UNIT-41,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11362,Road Cut,Completed,NP-PERUNGUDI,168,980000,"RESTORATION OF ROAD CUT [TANGEDCO] IN THE KUBERAMUNUSWAMY STREET AND NANGANALLUR 6 TH MAIN ROAD IN DN-168,UNIT-42,ZONE-14.",Deposit Works,14,2015-16,2016-17 NP/2015-16/11670,Roads,Completed,NP-PERUNGUDI,183,948000,"Laying cement concrete road at Muthalamman kovil 1st street in division-183 unit41, zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/11677,Roads,Completed,NP-PERUNGUDI,183,963000,"Laying Cement Concrete Road at Muthalamman Koil 2nd Street in Division-183, Unit-41, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11679,Roads,Completed,NP-PERUNGUDI,183,775000,"Laying Cement Concrete road at Muthalamman Kovil 3rd street in Division-183, Unit-41, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11681,Roads,Completed,NP-PERUNGUDI,183,878000,"Laying Cement Concrete road at Bajanai Kovil 4th street in Division-183, Unit-41, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11683,Roads,Completed,NP-PERUNGUDI,183,980000,"Laying Cement Concrete road at Bajanai Kovil 5th street in Division-183, Unit-41, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11686,Roads,Completed,NP-PERUNGUDI,183,803000,"Laying Cement Concrete road at Bajanai Kovil 6th street in Division-183, Unit-41, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11688,Roads,Completed,NP-PERUNGUDI,183,839000,"Laying Cement Concrete road at Bajanai Kovil 7th street in Division-183, Unit-41, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11693,Roads,Completed,NP-PERUNGUDI,183,884000,"Laying Cement Concrete road at Bajanai Kovil 8th street in Division-183, Unit-41, Zone-14",Grants,14,2015-16,2016-17 NP/2015-16/11894,Buildings,Completed,NP-PERUNGUDI,185,993000,"CONSTRUCTION OF COMPOUND WALL AT OSR LAND BACKSIDE OF LAKSHMAN NAGAR RATION SHOP IN DIV 185 ,UNIT 41,ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/11957,Roads,Completed,NP-PERUNGUDI,188,950000,"STRENGTHENING AND LAYING OF BT ROAD AT KRISHNA NAGAR MAIN ROAD FROM PALLAVARAM MUNICIPALITY TO RAJESWARI AVENUE IN DN - 188, U -42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11958,Roads,Completed,NP-PERUNGUDI,188,960000,"STRENGTHENING AND LAYING OF BT ROAD AT KRISHNA NAGAR MAIN ROAD FROM RAJESWARI AVENUE TO KRISHNA NAGAR 5TH CROSS STREET IN DN - 188, U -42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/11999,Roads,Completed,NP-PERUNGUDI,186,915000,"Restoration of Metro water road cut at 5NOS of Bethel nagar 1st street ,Manikodi srinivasan nagar 4th street , Kamarjar nagar 1st main road , Kamarjar nagar 1st cross street & Kamarjar nagar 2nd cross street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12001,Roads,Completed,NP-PERUNGUDI,186,817000,"Restoration of Metro water road cut at 3NOS of Kamarjar nagar 2nd main road, Kamarjar nagar 3rd cross street & Kamarjar nagar 4th cross street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12002,Roads,Completed,NP-PERUNGUDI,186,915000,"Restoration of Metro water road cut at 6NOS of Kamarjar nagar 5th cross street, Kamarjar nagar 6th cross street, Kamarjar nagar 7th cross street , Kamarjar nagar 8th cross street, Kamarjar nagar 10th cross street & Kamarjar nagar 11th cross street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12003,Roads,Completed,NP-PERUNGUDI,186,814000,"Restoration of Metro water road cut at 4NOS of Kamarjar nagar 9th cross street , Kamarjar nagar 12th cross street, Kurnchi nagar 1st cross street & Kurnchi nagar 2nd cross street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12004,Roads,Completed,NP-PERUNGUDI,186,916000,"Restoration of Metro water road cut at 4NOS of Kurnchi nagar 3rd cross street, Kurnchi nagar main road, Kurnchi nagar 4th cross street & Kurnchi nagar 5th cross street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2017-18 NP/2015-16/12005,Roads,Completed,NP-PERUNGUDI,186,864000,"Restoration of Metro water road cut at 6NOS of Kurnchi nagar 6th cross street, Kurnchi nagar 7th cross street, Kurnchi nagar 8th cross street Kurnchi nagar 9th cross street, Kurnchi nagar 10th cross street, Kurnchi nagar 11th cross street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12006,Roads,Completed,NP-PERUNGUDI,186,802000,"Restoration of Metro water road cut at AT 8NOS OF Rathinamani nagar 1st cross street, Rathinamani nagar 2nd cross street , Rathinamani nagar 3rd cross street , Rajalakshmi avenue main road, Rajalakshmi avenue 1st cross street, Rajalakshmi avenue 2nd cross street, Rajalakshmi avenue 3rd cross street, Rajalakshmi avenue 4th cross street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12007,Roads,Completed,NP-PERUNGUDI,186,869000,"Restoration of Metro water road cut at 5NOS of Kurnchi nagar 12th cross street, Kurnchi nagar 13th cross street, Kurnchi nagar 14th cross street & Kurnchi nagar 15th cross street & Rathinamani nagar main road in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12008,Roads,Completed,NP-PERUNGUDI,186,769000,Restoration of Metro water road cut at 2NOS of Rajalakshmi avenue 5th cross street & Pillyar koil 4th street in Dn-186 Unit-41 Zone-14,Own Sources,14,2015-16,2016-17 NP/2015-16/12437,Roads,Completed,NP-PERUNGUDI,183,981000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUTTING AT LAKSHMANA PERUMAL NAGAR 3RD STREET, LAKSHMANA PERUMAL NAGAR 5TH CROSS STREET, IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/12439,Road Cut,Completed,NP-PERUNGUDI,183,920000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUTTING AT LAKSHMANA PERUMAL NAGAR 4TH STREET, LAKSHMANA PERUMAL NAGAR 6TH STREET, VENKATESHWARA NAGAR 1ST STREET, IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/12442,Road Cut,Completed,NP-PERUNGUDI,183,900000,"RESTORATION OF METRO WATER (CMWSSB)ROAD CUTTING AT VENKATESHWARA NAGAR 10TH STREET, VENKATESHWARA NAGAR 14TH STREET, VENKATESHWARA NAGAR 15TH STREET, VENKATESHWARA NAGAR 16TH STREET IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/12445,Road Cut,Completed,NP-PERUNGUDI,183,920000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT BAY WATCH BLUE BAY CROSS ROAD, VENKATESHWARA NAGAR 21 STREET, AGS COLONY 3RD CROSS STREET, AGS COLONY 2ND STREET IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/12449,Road Cut,Completed,NP-PERUNGUDI,183,900000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT VENKATESHWARA NAGAR 19TH STREET, (KALKI 1ST STREET), IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/12451,Road Cut,Completed,NP-PERUNGUDI,183,920000,"RESTORATION OF METRO WATER (CMWSSB)ROAD CUTTING AT VENKATESHWARA NAGAR 7TH STREET, BEACH ROAD IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2017-18 NP/2015-16/12455,Roads,Completed,NP-PERUNGUDI,185,857000,"RESTORATION OF METRO WATER ROAD CUTTING (CMWSSB) AT SANTHOSH NAGAR MAIN ROAD TO SHANTHI NAGAR STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12472,Roads,Completed,NP-PERUNGUDI,185,708100,"RESTORATION OF METRO WATER ROAD CUTTING (CMWSSB) AT HARIVARDHAN STREET, PAUL RAJ MAIN ROAD & PAUL RAJ NAGAR 2ND CROSS STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12474,Roads,Completed,NP-PERUNGUDI,185,776000,"RESTORATION OF METRO WATER ROAD CUTTING (CMWSSB) AT JEEVANATHAN STREET, KARUNATHI CHOLAN STREET,KARUNATHI CHOLAN CROSS STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12476,Roads,Completed,NP-PERUNGUDI,185,802000,"RESTORATION OF METRO WATER ROAD CUTTING (CMWSSB) AT LAKSHMANAN NAGAR, KARUNATHI 1ST STREET, LAKSHMAN NAGAR- KARUNATHI 2ND STREET & LAKSHMANAN NAGAR - Periya nayaki street IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/12479,Roads,Completed,NP-PERUNGUDI,185,817000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUTTING AT JAYASHANKAR NAGAR, JAYASHANKAR NAGAR - KO SILAMANI SALAI, JAYASHANKAR NAGAR IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/1420,Roads,Completed,NP-PERUNGUDI,184,986000,FORMING AND LAYING OF CEMENT CONCRETE ROAD AT HINDU BURIAL GROUND (EAST SIDE) AT SCHOOL ROAD IN DN 184 UT 41 ZONE14,Own Sources,14,2015-16,2016-17 NP/2015-16/14600,Buildings,Completed,NP-PERUNGUDI,189,994000,"Additional construction and Improvements to Amma Unavagam at Mada Veethi in Dn 189,Unit 43, Zone XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/14739,Roads,Completed,NP-PERUNGUDI,189,980000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and Providing Thermo Plastic Compound marking Road pavement markers and signage boards at KAMAKOTTI NAGAR ,A.G.S.COLONY,V.G.P SHANTHI NAGAR,ADHISAMY NAGAR,MANOKAR NAGAR,RAJALAKSHMI NAGAR,CYNDICATE BANK COLONY,I.I.T COLONY in Dn 189, Unit-43, Zone-14",Own Sources,14,2015-16,2017-18 NP/2015-16/14753,Roads,Completed,NP-PERUNGUDI,188,970000,"STRENGTHENING AND LAYING OF BT ROAD AT KRISHNA NAGAR MAIN ROAD (FROM KRISHNA NAGAR 5TH STREET TO VISHAL NAGAR EXTN) IN DN-188,U-42,Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/14848,Footpath,Completed,NP-PERUNGUDI,186,546000,"Providing interlocking block at dumping ground to corporation road in perungudi dumping ground in dn-186, U-41, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/14873,Roads,Completed,NP-PERUNGUDI,186,995000,"Laying cement concrete approach Road at corporation road to cmwssb gate in perungudi dumping ground in dn- 186, u-41, z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/14876,Roads,Completed,NP-PERUNGUDI,186,995000,"Laying cement concrete approach Road at cmwssb gate TO Dumping ground gate in perungudi dumping ground in dn- 186, u-41, z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/15169,Roads,Completed,NP-PERUNGUDI,168,910000,"IMPROVEMENTS TO KUPPUSAMY STREET(SOUTH SIDE ) SIDE DRAIN FLOOD WORK IN DN-168, UNIT-2,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/15172,Roads,Completed,NP-PERUNGUDI,168,970000,"IMPROVEMENT TO THILAGAR STREET AND VIJAYAGANAPATHY NAGAR 1 ST STREET SIDE DRAIN IN FLOOD WORK DIVISION-168,UNIT-42,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/15668,Roads,Completed,NP-PERUNGUDI,168,970000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGNAGE BOARD,PAVEMENT MARKER,ROAD STRUDS IN DN-168,UNIT-42,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/15795,Footpath,Completed,NP-PERUNGUDI,184,696000,FORMING FOOT PATH AND WATER TABLE AT RAMAPPA NAGAR MAIN ROAD (NORTH SIDE) FROM JN. OF PILLAYAR KOVIL STREET TO RAMAPPA NAGAR 1ST CROSS STREET IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/15807,Footpath,Completed,NP-PERUNGUDI,184,729000,FORMING FOOT PATH AND WATER TABLE AT RAMAPPA NAGAR MAIN ROAD (SOUTH SIDE) FROM JN. OF PILLAYAR KOVIL STREET TO RAMAPPA NAGAR 1ST CROSS STREET IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/15815,Footpath,Completed,NP-PERUNGUDI,184,696000,FORMING FOOT PATH AND WATER TABLE AT RAMAPPA NAGAR MAIN ROAD (SOUTH SIDE) FROM JN. OF RAMAPPA NAGAR 1ST CROSS STREET TO CHURCH MAIN ROAD IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/15817,Footpath,Completed,NP-PERUNGUDI,184,696000,FORMING FOOT PATH AND WATER TABLE AT RAMAPPA NAGAR MAIN ROAD (NORTH SIDE) FROM JN. OF RAMAPPA NAGAR 1ST CROSS STREET TO CHURCH MAIN ROAD IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/15835,Footpath,Completed,NP-PERUNGUDI,184,983000,FORMING FOOT PATH AND WATER TABLE AT CHURCH MAIN ROAD (FROM JN. OF RAMAPPA NAGAR MAIN TO CHURCH SCHOOL)NORTH SIDE IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/15842,Footpath,Completed,NP-PERUNGUDI,184,981000,FORMING FOOT PATH AND WATER TABLE AT CHURCH MAIN ROAD (FROM JN. OF CHURCH SCHOOL T0 CBI COLONY MAIN ROAD)(NORTH SIDE) IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/15853,Roads,Completed,NP-PERUNGUDI,184,640000,"LAYING CEMENT CONCRETE ROAD AND FORMING ILP AT CBI COLONY 5TH MAIN ROAD EXTN IN DIV 184, UNIT 41, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/15903,Buildings,Completed,NP-PERUNGUDI,185,383000,"IMPROVEMENTS TO ANGANVADI (PROVIDING PAINTING AND OTHER WORKS) AT BURMA COLONY IN DIV-185, U-41, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/16438,Roads,Completed,NP-PERUNGUDI,190,980000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and Providing Thermo Plastic Compound marking Road pavement markers and signage boards at various Street in Dn 190, Unit-43, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/16501,Roads,Completed,NP-PERUNGUDI,185,785000,"FORMING AND LAYING OF CC ROAD AT VEMBULI AMMAN 1st STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/16503,Roads,Completed,NP-PERUNGUDI,185,588000,"FORMING AND LAYING OF CC ROAD AT VEMBULI AMMAN 2nd STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/16504,Roads,Completed,NP-PERUNGUDI,185,686000,"FORMING AND LAYING OF CC ROAD AT VEMBULI AMMAN 3rd STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/16505,Roads,Completed,NP-PERUNGUDI,185,588000,"FORMING AND LAYING OF CC ROAD AT VEMBULI AMMAN 4th STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/16510,Roads,Completed,NP-PERUNGUDI,185,986000,"FORMING AND LAYING OF CC ROAD AT VEMBULI AMMAN MAIN ROAD (ECR MAIN ROAD TO VEMBULI AMMAN 1st STREET) IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/16512,Roads,Completed,NP-PERUNGUDI,185,986000,"FORMING AND LAYING OF CC ROAD AT VEMBULIL AMMAN MAIN ROAD (VEMBULI AMMAN 1st STREET TO 4tH STREET) IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/16516,Roads,Completed,NP-PERUNGUDI,183,995000,RAISING THE ROAD BY CEMENT CONCRETE AT ANNA NAGAR (SOUTH ) IN DIV 183 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/16517,Roads,Completed,NP-PERUNGUDI,183,995000,RAISING THE ROAD BY CEMENT CONCRETE AT ANNA NAGAR (NORTH ) IN DIV 183 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/16518,Storm Water Drain,Completed,NP-PERUNGUDI,183,993000,REPAIRS AND IMPROVEMENTS TO SWD AT ANNA NAGAR ALL ROUND GYM BUILDINGS (SOUTH) SIDE IN DIV 183 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/16519,Storm Water Drain,Completed,NP-PERUNGUDI,183,993000,REPAIRS AND IMPROVEMENTS TO SWD AT ANNA NAGAR ALL ROUND GYM BUILDINGS (NORTH) SIDE IN DIV 183 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/16869,Buildings,Completed,NP-PERUNGUDI,184,974000,"CONSTRUCTION OF COMPOUND WALL FOR VACANT LAND AT RAMAPPA NAGAR MAIN ROAD AND JUNCTION OF PILLAYAR KOIL MAIN ROAD ( NEAR MULTIPURPOSE HALL, GYM BUILDING ] IN DIV 184 UNIT 41 ZONE 14",Own Sources,14,2015-16,2016-17 NP/2015-16/1743,Buildings,Completed,NP-PERUNGUDI,184,1410000,CONSTRUCTION OF RATION SHOP AT JN. OF RAMAPPA NAGAR MAIN ROAD AND PILLAYAR KOIL STREET (GROUND FLOOR) IN DIV 184 UNIT 41 ZONE 14,MLACDS,14,2015-16,2016-17 NP/2015-16/1750,Buildings,Completed,NP-PERUNGUDI,184,1350000,"CONSTRUCTION OF GYM BUILDING 1ST FLOOR AT JN OF RAMAPPA NAGAR MAIN ROAD AND PILLAIYAR KOIL STREET (ABOVE RATION SHOP) IN DIV 184,UNIT 41,ZONE 14.",MLACDS,14,2015-16,2016-17 NP/2015-16/18020,Roads,Completed,NP-PERUNGUDI,185,860000,"FORMING AND LAYING OF CC ROAD AT M.G.R MAIN ROAD IN DN-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/18024,Roads,Completed,NP-PERUNGUDI,185,635000,"FORMING AND LAYING OF C ROAD AT M.G.R 1 ST STREET IN DN-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/18025,Roads,Completed,NP-PERUNGUDI,185,535000,"FORMING AND LAYING OF C ROAD AT M.G.R 2 ND STREET IN DN-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/18027,Roads,Completed,NP-PERUNGUDI,185,585000,"FORMING AND LAYING OF CC ROAD AT M.G.R 3 RD STREET IN DN-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/18028,Roads,Completed,NP-PERUNGUDI,185,990000,"FORMING AND LAYING OF CC ROAD AT KOLAVIZHIAMMAN 4 TH STREET IN DN-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/18030,Roads,Completed,NP-PERUNGUDI,185,970000,"FORMING AND LAYING OF CC ROAD AT KOLAVIZHIAMMAN MAIN ROAD STREET IN DN-185,UNIT-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/18031,Roads,Completed,NP-PERUNGUDI,185,890000,"FORMING AND LAYING OF CC ROAD IN KOLAVIZHIAMMAN 5 TH STREET IN DN-185,U-41,ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/18132,Electrical,Completed,NP-PERUNGUDI,188,997900,"PROVISION OF 19 NOS OF 6MTR HOT DIP ZINC GALVANISING WITH SINGLE STRAIGHT BRACKET WITH 90-120W LAED FITTING AT SADASIVAM NAGAR 5TH MAIN ROAD BURRIAL GROUND IN DIV-188, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/18275,Electrical,Completed,NP-PERUNGUDI,185,782700,"Provision of 13 nos of 6mtr Hot dip zinc galvanising with single straight bracket with 12nos of 90-120W LED Fitting set and 2nos of 250W MH FL at Fitting at Palavakam Burial Ground in Div-185,Zone-14 area,",Own Sources,14,2015-16,2016-17 NP/2015-16/1874,Buildings,Completed,NP-PERUNGUDI,184,999000,CONSTRUCTION OF MULTIPURPOSE HALL(PHASE-1) EAST SIDE AT MGR SALAI JN OF TNEB OFFICE ROAD IN DIV 184 UNIT 41 ZONE 14,MLACDS,14,2015-16,2016-17 NP/2015-16/1875,Buildings,Completed,NP-PERUNGUDI,184,361000,"CONSTRUCTION OF SEPTIC TANK AND PROVIDING ELECTRICAL AND WATER SUPPLY ARRANGEMENTS FOR MULTIPURPOSE HALL PHASE 1 , EAST SIDE AT MGR SALAI JN OF TNEB OFFICE ROAD IN DIV 184 UNIT 41 ZONE 14",MLACDS,14,2015-16,2016-17 NP/2015-16/18795,Buildings,Completed,NP-PERUNGUDI,184,735000,"ANNUAL MAINTENANCE OF TELEPHONE NAGAR PARK, PERUNGUDI IN DIVISION 184, UNIT 41, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/18998,Culvert,Completed,NP-PERUNGUDI,168,990000,CONSTRUCTION OF ROAD CULVERT AND REPAIRS TO SIDE DRAIN FLOOD WORK AT VARIOUS STREET IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/20691,Roads,Completed,NP-PERUNGUDI,187,938000,"ATTENDING PATCH WORK WITH WMM AT DEIVANNAI NAGAR,KARTHIKEYAPAURAM 1ST TO 12TH STREET,ESWARAN KOVIL MAIN ROAD ,PONNIAMMAN KOVIL MAIN ROAD AND OTHER VARIOUS STREET IN DN-187, UNIT- 42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20715,Roads,Completed,NP-PERUNGUDI,189,850000,"PROVIDING PATCH WORKS DUE TO RAIN AT V.G.P SHANTHI NAGAR 1ST MAIN ROAD ,KAVIMANI STREET TO V.G.P SHANTHI NAGAR CHURCH AVENUE EXTN,V.G.P SHANTHI NAGAR LAKSHMI STREET,V.G.P SHANTHI NAGAR BHARATHI STREET ,V.G.P SHANTHI NAGAR SANTHOSH STREET ,V.G.P SHANTHI NAGAR KURUNJI STREET ,V.G.P SHANTHI NAGAR 4TH STREET (AVVAI) ,VARATHARAJAN NAGAR 1ST STREET,MEENATCHIPURAM 2ND STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20719,Roads,Completed,NP-PERUNGUDI,189,660000,"PROVIDING PATCH WORKS AT MEENATCHIPURAM 1ST STREET,RAJALAKSHMI NAGAR 1ST MAIN ROAD,I.I.T COLONY 1ST MAIN ROAD IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20731,Roads,Completed,NP-PERUNGUDI,169,856000,"PROVIDING PATCHES AT B.T. ROADS ( DUE TO RAIN) AT SHEELA NAGAR MAIN ROAD, ANNAITHERESA NAGAR 2nd STREET, ANNAI THERESA NAGAR 2nd CROSS STREET AND ANNAI THERESA NAGAR 7th STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20746,Roads,Completed,NP-PERUNGUDI,169,846000,"PROVIDING PATCHES TO BT ROADS (DUE TO HEAVY RAIN) AT ANNAI THERESA NAGAR 8th,14th,10th STREET, ESWARAN KOVIL STREET, NANJIL STREET, RAMALINGAM STREET EXTN, SADASIVAM NAGAR MAIN ROAD AND SENKAZHANI AMMAM KOVIL STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20749,Roads,Completed,NP-PERUNGUDI,169,860000,"PROVIDING PATCHES TO BT ROADS (DUE TO HEAVY RAIN) MANDAVELI STREET, HINDU COLONY 1st MAIN ROAD, IYYAN THIRUVALLUVAR STREET, BALAJI NAGAR MAIN ROAD, MURUGAPPAN STREET, ARUL JYOOTHI SALAI, PERUMAL NAGAR MAIN ROAD, VEMBULI PANNAIKARAN STREET, BALAJI NAGAR 5th STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20750,Roads,Completed,NP-PERUNGUDI,169,810000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT MGR STREET, EPR NAGAR AND GANESH NAGAR IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20751,Roads,Completed,NP-PERUNGUDI,169,570000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT RAVANAN NAGAR, SARATHI NAGAR, KANAGAVALLI STREET, BHARATHI STREET, KARIYAN PONNAN STREET AND NSC BOSE ROAD IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20764,Roads,Completed,NP-PERUNGUDI,188,930000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT RAM NAGAR SOUTH 3RD MAIN ROAD, 8TH CROSS STREET, 6TH CROSS STREET, 7TH CROSS STREET AND 9TH MAIN ROAD IN DN-188, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20780,Roads,Completed,NP-PERUNGUDI,188,820000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT RAM NAGAR 5TH CROSS STREET, RAJAJI NAGAR 3RD STREET, DR. AMBETHKAR SALAI, LAKSHMI NAGAR MAIN ROAD, DR. RAMMOORTHY NAGAR 3RD STREET, WEST ANNA NAGAR 3RD STREET, 6TH STREET AND 8TH STREET IN DN- 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/20785,Roads,Completed,NP-PERUNGUDI,188,340000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT VGP RAJESH NAGAR MAIN ROAD, RAJESH NAGAR PARK ROAD, LIC NAGAR 2ND STREET, 1ST STREET, KUBERAN NAGAR EXTN MAIN ROAD, PERIYAR NAGAR 7TH STREET, 6TH STREET, PERIYAR NAGAR EXTN II 7TH STREET, LIC NAGAR 5TH STREET, MAHALAKSHMI NAGAR 3RD STREET, MYLLAI BALAJI NAGAR 1ST BLOCK 1ST MAIN ROAD, 1ST BLOCK 2ND MAIN ROAD, 4TH BLOCK 1ST MAIN ROAD, 2ND MAIN ROAD AND 1ST STREET IN DN- 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/20788,Roads,Completed,NP-PERUNGUDI,187,990000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT IYYAPPA NAGAR 2ND STREET, 6TH STREET, 8TH STREET, 12TH STREET AND 10TH STREET IN DN-187, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20791,Roads,Completed,NP-PERUNGUDI,187,830000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT IYYAPPA NAGAR 13TH STREET, 1ST STREET, LAKE VIEW MAIN ROAD, BAJANAI KOIL 2ND STREET, NEW KUBERA NAGAR 5HT STREET AND NEW KUBERA NAGAR 7TH STREET IN DN-187, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20793,Roads,Completed,NP-PERUNGUDI,187,720000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT DEIVANAI NAGAR 4TH STREET, KARTHIKEYAPURAM 2ND CROSS STREET, SARASWATHI STREET AND BHUVANESHWARI STREET IN DN-187, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20796,Roads,Completed,NP-PERUNGUDI,187,870000,"PROVIDING PATCHES TO BT ROADS ( DUE TO HEAVY RAIN) AT ADHI SANKARN STREET, IYYAPPA NAGAR SANNATHI STREET, PONNIAMMAN KOIL STREET AND ESWARAN KOIL STREET IN DN-187, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20890,Roads,Completed,NP-PERUNGUDI,186,820000,"PROVIDING PATCHES AT BT ROAD DUE TO RAIN AT CORPORATION ROAD AND PANCHAYAT MAIN ROAD IN DN 186,U-41 Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20898,Roads,Completed,NP-PERUNGUDI,184,984000,"PROVIDING PATCHES AT BT ROAD DUE TO RAIN AT RAMAPPA NAGAR MAIN ROAD, CHARCH ROAD ANNANEDUN SALAI AND SCHOOL ROAD IN DN 184,U-41 Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20947,Roads,Completed,NP-PERUNGUDI,183,925000,"PROVIDING PATCHES TO BT ROADS (DUE TO HEAVY RAIN) AT JAGANATHAN STREET, KAVERY NAGAR, VENKATESWARA 9TH STREET, KALATHUMEDU STREET AND SWAMY NATHAN NAGAR 11TH STREET IN DIV-183, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/20955,Roads,Completed,NP-PERUNGUDI,183,912000,"PROVIDING PATCHES TO BT ROADS (DUE TO HEAVY RAIN) AT VENKATESAPURAM MAIN ROAD, SWAMY NATHAN NAGAR 4TH STREE, SWAMY NATHAN NAGAR 5TH STREET, A.G.S COLONY 4TH STREET, A.G.S COLONY 2ND CROSS STREET, LAKSHMANAN PERUMAL NAGAR (RAJA STREET) & NEHRU NAGAR 1ST MAIN ROAD IN DIV-183, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/20957,Roads,Completed,NP-PERUNGUDI,183,817000,"PROVIDING PATCHES TO BT ROADS (DUE TO HEAVY RAIN) AT VENKATESWARA NAGAR 21ST STREET, DR.VAITHAGI STREET, SELVRAJ AVENUE & THULAKATHAMMAN KOIL STREET IN DIV-183, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/20962,Roads,Completed,NP-PERUNGUDI,183,985000,"PROVIDING PATCHES TO BT ROADS (DUE TO HEAVY RAIN) AT SANAGAM COLONY 3RD STREET, ELANGO NAGAR SOUTH GANDHI STREET, ELANGO NAGAR WATER TANK, KUPPAM BEACH ROAD, VENKATESHWARA NAGAR 1ST STREET, THIRUVEEDHI AMMAN KOIL STREET & AGS COLONY 2ND MAIN ROAD IN DIV-183, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/20968,Roads,Completed,NP-PERUNGUDI,185,952000,"PROVIDING PATCHES TO B.T ROAD DUE TO RAIN AT Masuthi street,Senganiamman koil street,Vellakenikulam street,Kareem nagar.Kareem nagar 1 st cross street,kareem nagar 2 nd street,kareem nagar 3 rd cross street,pachayyapan main road in dn -185,unit-41,zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20989,Roads,Completed,NP-PERUNGUDI,185,970000,"PROVIDING PATCHES TO B.T ROAD DUE TO RAIN AT Aanbalagan 1 st,anbalagan 2 nd st,anbalagan 3 rd st,pachayappan 1 st,pachayappan 2 nd st,pachayappan 3 rd st,DSG nagar main road,DSG nagar 1 main road DSG nagar 2 nd main road,jayashanka nagar 1 st st dn -185,unit-41,zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20996,Roads,Completed,NP-PERUNGUDI,190,995000,"PROVIDING PATCH WORKS DUE TO RAIN AT BHAVANIYAMMAN KOIL STREET,WELL APPROACH SALAI IN DN-190,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/20998,Roads,Completed,NP-PERUNGUDI,185,990000,"PROVIDING PATCHES TO B.T ROAD DUE TO RAIN AT meetpar church road,govindhan nagar main road,thagoor st,thiru vi ka 1 st cross st,thiru vi ka 2 nd cross, dn -185,unit-41,zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/21007,Roads,Completed,NP-PERUNGUDI,185,952000,"PROVIDING PATCHES TO B.T ROAD DUE TO RAIN AT SANTHOSH NAGAR MAIN ROAD,st thomas street,saibaba street,rajeshwari street,shanthi nagar,kandhasamy 1 st st,kandhasamy nagar 3 rd st,kandhasamy nagar 4 th st, dn -185,unit-41,zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/21013,Roads,Completed,NP-PERUNGUDI,185,993000,"PROVIDING PATCHES TO B.T ROAD DUE TO RAIN AT paul raj nagar,burma colony 3 rd main road,burma colony 4 th main road,estate 1 st main road dn -185,unit-41,zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/21678,Roads,Completed,NP-PERUNGUDI,189,640000,"PROVIDING PATCH WORKS AT KAMAKOTTI NAGAR 1ST MAIN ROAD,KAMAKOTTI NAGAR 3RD MAIN ROAD,ASTALAKSHMI AVENUE MAIN ROAD,AMBEDKAR CROSS STREET,MANOKAR NAGAR MAIN ROAD IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/21699,Roads,Completed,NP-PERUNGUDI,190,235000,"PROVIDING PATCH WORKS DUE TO RAIN AT CITI BABU NAGR,NEHRU STREET IN DN-190,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22007,Buildings,Completed,NP-PERUNGUDI,186,272000,CONSTRUCTION OF 600MM DIA RCC HUME PIPE ROAD CROSS CULVERT (FOR FLOOD) AT VARIOUS STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/22025,Storm Water Drain,Completed,NP-PERUNGUDI,186,236000,DESILTING OF STORM WATER DRAIN (FOR FLOOD) AT VARIOUS STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/22340,Roads,Completed,NP-PERUNGUDI,168,735000,"PROVIDING PATCHES AT B.T.ROADS DUE TO RAIN AT DHROWPATHY AMMAN KOIL STREET, Navalar street ,Guberamunuswamy street, parthiban street , Anna salai, Nanganallur 6th main road, Barathidasan street, M.G.nagar street and lakshmi nagar 10 th street in DN-168,UNIT-42, ZONE-1",Own Sources,14,2015-16,2016-17 NP/2015-16/22345,Roads,Completed,NP-PERUNGUDI,168,920000,"PROVIDING PATCHES TO B.T.ROADS DUE TO RAIN AT Balammal nagar main road , N.S.C.BOSE ROAD, Ponnusamay street and MGR STREET IN DN-168,UNIT-42,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/22383,Roads,Completed,NP-PERUNGUDI,189,840000,"PROVIDING PATCH WORKS DUE TO RAIN AT V.G.P SHANTHI NAGAR V.O.C STREET , V.G.P SHANTHI NAGAR- VALLALAR STREET,LABOUR COLONY MAIN ROAD IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22573,Roads,Completed,NP-PERUNGUDI,184,7600000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT ANNANAGAR AND NEHRU NAGAR 9TH LINK ROAD IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/22602,Roads,Completed,NP-PERUNGUDI,191,974000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PERUMAL AVENUE IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22642,Roads,Completed,NP-PERUNGUDI,190,259000,"Strengthening and laying of B.T Road at Pillaiyar Koil Street in Dn -190, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22643,Roads,Completed,NP-PERUNGUDI,191,877000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PART-III IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22644,Roads,Completed,NP-PERUNGUDI,190,506000,"Strengthening and laying of B.T Road at Devi Karumaiyamman Nagar Dn -190, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22645,Roads,Completed,NP-PERUNGUDI,190,1375000,"Strengthening and laying of B.T Road at Adhimoolam NagarDn -190, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22646,Roads,Completed,NP-PERUNGUDI,190,623000,"Strengthening and laying of B.T Road at Adhimoolam Nagar-IIDn -190, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22652,Roads,Completed,NP-PERUNGUDI,191,678000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR 11TH CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22661,Roads,Completed,NP-PERUNGUDI,191,1398000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PART-II 1ST MAIN ROAD IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22663,Roads,Completed,NP-PERUNGUDI,191,779000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PART-II 2ND MAIN ROAD IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22667,Roads,Completed,NP-PERUNGUDI,191,389000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PART-II 3RD MAIN ROAD IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22671,Roads,Completed,NP-PERUNGUDI,191,118000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PART-II 1ST MAIN ROAD 1ST CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22672,Roads,Completed,NP-PERUNGUDI,191,2805000,"Strengthening and laying of B.T Road at Anchanayar Nagar Kannadasan StreetDn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22673,Roads,Completed,NP-PERUNGUDI,191,1403000,"Strengthening and laying of B.T Road at Anchanayar Nagar Mahaverar streetDn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22675,Roads,Completed,NP-PERUNGUDI,191,161000,"Strengthening and laying of B.T Road at Bharathiyar Cross StreetDn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22677,Roads,Completed,NP-PERUNGUDI,191,259000,"Strengthening and laying of B.T Road at Jeganathapuram Cross Street ExtnDn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22678,Roads,Completed,NP-PERUNGUDI,191,427000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PART-II 2ND MAIN ROAD 1ST CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22679,Roads,Completed,NP-PERUNGUDI,191,740000,"Strengthening and laying of B.T Road at Kamarajar street Dn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22685,Roads,Completed,NP-PERUNGUDI,191,291000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SAI GANESH NAGAR PART-II 2ND MAIN ROAD 2ND CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22690,Roads,Completed,NP-PERUNGUDI,191,791000,"STRENGTHENING AND LAYNG OF B.T ROAD AT SUBASH CHANDRABOSH STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22693,Roads,Completed,NP-PERUNGUDI,191,1206000,"STRENGTHENING AND LAYNG OF B.T ROAD AT VANCHINATHAN STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22694,Roads,Completed,NP-PERUNGUDI,185,750000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALAKALAI NAGAR 2nd LINK STREET DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22698,Roads,Completed,NP-PERUNGUDI,185,1070000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALAKALAI NAGAR 2nd LINK 1st CROSS STREET DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22702,Roads,Completed,NP-PERUNGUDI,191,271000,"Strengthening and laying of B.T Road at Mahaveer 1st Cross Street in Dn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22704,Roads,Completed,NP-PERUNGUDI,191,265000,"Strengthening and laying of B.T Road at Mahaveer 2nd Cross StreetDn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22707,Roads,Completed,NP-PERUNGUDI,191,259000,"Strengthening and laying of B.T Road at Mahaveer 3rd Cross StreetDn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22708,Roads,Completed,NP-PERUNGUDI,191,285000,"Strengthening and laying of B.T Road at Manimegalai Street Dn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22709,Roads,Completed,NP-PERUNGUDI,191,150000,"Strengthening and laying of B.T Road at Quaide ? E -Milleth 2nd Cross street in Dn -191, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/22713,Roads,Completed,NP-PERUNGUDI,185,921000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PALKALAI NAGAR 3rd LINK STREET IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22714,Roads,Completed,NP-PERUNGUDI,185,1038000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT VGP 2nd CROSS ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22716,Roads,Completed,NP-PERUNGUDI,185,1038000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT VGP 4th CROSS ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22718,Roads,Completed,NP-PERUNGUDI,185,940000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PART II VGP 1st MAIN ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22719,Roads,Completed,NP-PERUNGUDI,185,1096000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PART II VGP 2nd MAIN ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22720,Roads,Completed,NP-PERUNGUDI,185,940000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT VGP 6th CROSS ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22723,Roads,Completed,NP-PERUNGUDI,185,778000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT PART III VGP 1st MAIN ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22725,Roads,Completed,NP-PERUNGUDI,185,1165000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT VGP 2nd MAIN ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22726,Roads,Completed,NP-PERUNGUDI,185,778000,"STRENGTHENING AND LAYING OF BT ROAD WITH PAVER FINISH AT VGP 4th MAIN ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/22736,Roads,Completed,NP-PERUNGUDI,188,230000,"PROVIDING STREET NAME BOARD AT GOVINDASAMY NAGAR 11TH STREET AND CAVERY STREET IN DN-188, U - 42, Z - 14",Own Sources,14,2015-16,2017-18 NP/2015-16/22757,Roads,Completed,NP-PERUNGUDI,188,670000,"STRENGTHENING AND LAYING OF B.T ROAD AT DR.RAMAMURTHY NAGAR 1ST.STREET IN DN-188,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22764,Roads,Completed,NP-PERUNGUDI,187,826000,"STRENGTHENING AND LAYING OF B.T ROAD AT ETHIRAJULU STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22765,Roads,Completed,NP-PERUNGUDI,188,1300000,"STRENGTHENING AND LAYING OF BT ROAD AT DR. RAMAMURTHY NAGAR 2ND STREET IN DN - 188, U-42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/22766,Roads,Completed,NP-PERUNGUDI,187,627000,"STRENTHENING AND LAYING OF B.T ROAD AT JAMES ROAD IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22767,Roads,Completed,NP-PERUNGUDI,188,1111000,"STRENGTHENING AND LAYING OF B.T ROAD AT PARK SQUARE COLONY 1ST.STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22768,Roads,Completed,NP-PERUNGUDI,187,3410000,"STRENGTHENING AND LAYING OF B.T ROAD AT KAMARAJ STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22769,Roads,Completed,NP-PERUNGUDI,187,6210000,"STRENGTHENING AND LAYING OF B.T ROAD AT KARTHIKEYAPURAM YERIKARAI STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22773,Roads,Completed,NP-PERUNGUDI,187,2892000,"STRENGTHENING AND LAYING OF B.T ROAD AT KARTHIKEYAPURAM 5TH.STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22774,Roads,Completed,NP-PERUNGUDI,188,1380000,"STRENGTHING AND LAYING OF BT ROAD AT RAMAMURTHY NAGAR GANDHI STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22775,Roads,Completed,NP-PERUNGUDI,187,2411000,"STRENGTHENING AND LAYING OF B.T ROAD AT KARTHIKEYAPURAM 6TH.STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22776,Roads,Completed,NP-PERUNGUDI,187,2990000,"STRENGTHENING AND LAYING OF B.T ROAD AT KARTHIKAYAPURAM 9TH.STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22777,Roads,Completed,NP-PERUNGUDI,187,3519000,"STRENGTHENING AND LAYING OF B.T ROAD AT SATH SANGAM STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22778,Roads,Completed,NP-PERUNGUDI,188,1360000,"STRENGTHING AND LAYING OF BT ROAD AT NATARAJAN STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22779,Roads,Completed,NP-PERUNGUDI,187,1351000,"STRENGTHENING AND LAYING OF B.T ROAD AT VENKATESA PERUMAL 2ND STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22780,Roads,Completed,NP-PERUNGUDI,187,249000,"STRENGTHENING AND LAYING OF B.T ROAD AT BAJANAI KOIL 4TH.STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22781,Roads,Completed,NP-PERUNGUDI,188,1650000,"STRENGTHING AND LAYING OF BT ROAD AT GANAPATHY STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22782,Roads,Completed,NP-PERUNGUDI,188,633000,"STRENGTHING AND LAYING OF BT ROAD AT SAI STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22783,Roads,Completed,NP-PERUNGUDI,187,221000,"STRENGTHENING AND LAYING OF B.T ROAD AT BAJANAI KOIL 3RD.STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22785,Roads,Completed,NP-PERUNGUDI,187,1639000,"STRENGTHENING AND LAYING OF B.T ROAD AT PARK SQUARE COLONY IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22786,Roads,Completed,NP-PERUNGUDI,188,578000,"STRENGTHING AND LAYING OF BT ROAD AT SAKTHI NAGAR 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22787,Roads,Completed,NP-PERUNGUDI,187,358000,"STRENGTHENING AND LAYING OF B.T ROAD AT PERUNDEVI STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22788,Roads,Completed,NP-PERUNGUDI,187,531000,"STRENGTHENING AND LAYING OF B.T ROAD AT KARTHIKEYAPURAM 3RD.1ST.CROSS STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22789,Roads,Completed,NP-PERUNGUDI,187,1111000,"STRENGTHENING AND LAYING OF B.T ROAD AT LAKE VIEW MAIN ROAD EXTN IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22790,Roads,Completed,NP-PERUNGUDI,188,685000,"STRENGTHING AND LAYING OF BT ROAD AT SAKTHI NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22794,Roads,Completed,NP-PERUNGUDI,187,627000,"STRENGTHENING AND LAYING OF B.T ROAD AT NEW KUBARAN NAGAR 6TH.STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22795,Roads,Completed,NP-PERUNGUDI,188,723000,"STRENGTHING AND LAYING OF BT ROAD AT SAKTHI NAGAR 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22797,Roads,Completed,NP-PERUNGUDI,187,3410000,"STRENGTHENING AND LAYING OF B.T ROAD AT PONNIAMMAN KOIL STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22798,Roads,Completed,NP-PERUNGUDI,187,826000,"STRENGTHENING AND LAYING OF B.T ROAD AT KULAKARAI STREET IN DN-187,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22799,Roads,Completed,NP-PERUNGUDI,188,495000,"STRENGTHING AND LAYING OF BT ROAD AT ALAYAMMAN NAGAR 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22800,Roads,Completed,NP-PERUNGUDI,188,700000,"STRENGTHING AND LAYING OF BT ROAD ALAYAMMAN NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22801,Roads,Completed,NP-PERUNGUDI,188,3300000,"STRENGTHING AND LAYING OF BT ROAD AT LAKSHMI NAGAR MAIN ROAD( PART) STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22802,Roads,Completed,NP-PERUNGUDI,188,880000,"STRENGTHING AND LAYING OF BT ROAD AT LAKSHMI NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22803,Roads,Completed,NP-PERUNGUDI,188,880000,"STRENGTHING AND LAYING OF BT ROAD AT LAKSHMI NAGAR 3ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22805,Roads,Completed,NP-PERUNGUDI,188,1267000,"STRENGTHING AND LAYING OF BT ROAD AT LAKSHMI NAGAR 4TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22807,Roads,Completed,NP-PERUNGUDI,188,1060000,"STRENGTHING AND LAYING OF BT ROAD AT LAKSHMI NAGAR 5TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22808,Roads,Completed,NP-PERUNGUDI,188,864000,"STRENGTHING AND LAYING OF BT ROAD AT LAKSHMI NAGAR 6TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22809,Roads,Completed,NP-PERUNGUDI,188,2049000,"STRENGTHING AND LAYING OF BT ROAD AT LAKSHMI NAGAR 8TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22810,Roads,Completed,NP-PERUNGUDI,188,2313000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22812,Roads,Completed,NP-PERUNGUDI,188,650000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22813,Roads,Completed,NP-PERUNGUDI,188,570000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22814,Roads,Completed,NP-PERUNGUDI,188,570000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN ENFIELD AVENUE IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22815,Roads,Completed,NP-PERUNGUDI,188,260000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN-II VEDHANTHA DESIGAN STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22816,Roads,Completed,NP-PERUNGUDI,188,300000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN-II 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22817,Roads,Completed,NP-PERUNGUDI,188,255000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN-II 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22818,Roads,Completed,NP-PERUNGUDI,188,400000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN-II 4TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22820,Roads,Completed,NP-PERUNGUDI,188,288000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN-II 5TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22821,Roads,Completed,NP-PERUNGUDI,188,336000,"STRENGTHING AND LAYING OF BT ROAD AT PERIYAR NAGAR EXTN-II 6TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22825,Roads,Completed,NP-PERUNGUDI,188,1757000,"STRENGTHING AND LAYING OF BT ROAD AT VEERAMANI STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22826,Roads,Completed,NP-PERUNGUDI,188,1687000,"STRENGTHING AND LAYING OF BT ROAD AT BHARATHIDASAN STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22827,Roads,Completed,NP-PERUNGUDI,188,648000,"STRENGTHING AND LAYING OF BT ROAD AT KANCHI KAMACHI NAGAR MAIN ROAD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22828,Roads,Completed,NP-PERUNGUDI,188,432000,"STRENGTHING AND LAYING OF BT ROAD AT KANCHI KAMACHI NAGAR 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22829,Roads,Completed,NP-PERUNGUDI,188,370000,"STRENGTHING AND LAYING OF BT ROAD AT KANCHI KAMACHI NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22831,Roads,Completed,NP-PERUNGUDI,188,226000,"STRENGTHING AND LAYING OF BT ROAD AT KANCHI KAMACHI NAGAR 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/22847,Roads,Completed,NP-PERUNGUDI,188,930000,"ATTENDING PATCH WORKS, SUPPLYING AND FIXING OF RCC HUME PIPES AT VARIOUS STREETS IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/23015,Roads,Completed,NP-PERUNGUDI,190,549000,"Providing and laying the B.T Road at Bharathidasan 1st street Extn in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23019,Roads,Completed,NP-PERUNGUDI,190,915000,"Providing and laying the B.T Road at Bharathidasan 2nd street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23020,Roads,Completed,NP-PERUNGUDI,190,285000,"Providing and laying the B.T Road at Bharathidasan 2nd street Extn in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23021,Roads,Completed,NP-PERUNGUDI,190,812000,"Providing and laying the B.T Road at Bharathidasan 1st street -1st Cross street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23022,Roads,Completed,NP-PERUNGUDI,190,633000,"Providing and laying the B.T Road at Bharathidasan 1st street -2nd Cross street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23023,Roads,Completed,NP-PERUNGUDI,190,490000,"Providing and laying the B.T Road at Bharathidasan 1st street -3rd Cross street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23024,Roads,Completed,NP-PERUNGUDI,190,193000,"Providing and laying the B.T Road at Bharathidasan 1st street -4th Cross street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23025,Roads,Completed,NP-PERUNGUDI,190,133000,"Providing and laying the B.T Road at Bharathidasan 1st street -5th Cross street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23026,Roads,Completed,NP-PERUNGUDI,190,76000,"Providing and laying the B.T Road at Bharathidasan 1st street -6th Cross street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23027,Roads,Completed,NP-PERUNGUDI,190,179000,"Providing and laying the B.T Road at Bharathidasan 1st street -7th Cross street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23028,Roads,Completed,NP-PERUNGUDI,190,552000,"Providing and laying the B.T Road at Bharathidasan Well approach road in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23029,Roads,Completed,NP-PERUNGUDI,190,554000,"Providing and laying the B.T Road at Bharathiyar street in Dn-190,Unit-43,Zone14",Own Sources,14,2015-16,2016-17 NP/2015-16/23248,Roads,Completed,NP-PERUNGUDI,191,950000,"STRENGTENING AND LAYING OF B.T ROAD AT GREEN COURT MAIN ROAD IN DN-191,UN IT-43,ZONE-14",Deposit Works,14,2015-16,2016-17 NP/2015-16/23251,Roads,Completed,NP-PERUNGUDI,191,811000,"STRENGTENING AND LAYING OF B.T ROAD AT GRENEN COURT 1ST STREET IN DN-191,UN IT-43,ZONE-14",Deposit Works,14,2015-16,2016-17 NP/2015-16/23252,Roads,Completed,NP-PERUNGUDI,191,970000,"STRENGTENING AND LAYING OF B.T ROAD AT GRENEN COURT 2ND STREET IN DN-191,UN IT-43,ZONE-14",Deposit Works,14,2015-16,2016-17 NP/2015-16/23395,Roads,Completed,NP-PERUNGUDI,189,910000,"PROVIDING AND LAYING OF B.T ROAD AT JAYABAL NAGAR,KAMATCHI COLONY,KAMATCHI COLONY 1ST STREET,KAMATCHI COLONY 2ND STREET,KAVIMANI STREET TO VGP SHANTHI NAGAR (CHURCH AVENUE) REACH-2 IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/23398,Roads,Completed,NP-PERUNGUDI,189,772000,"PROVIDING AND LAYING OF B.T ROAD AT KAVIMANI STREET EXTENSION,KRISHNA NAGAR 1ST CROSS STREET, KRISHNA NAGAR 2ND CROSS STREET,KRISHNA NAGAR MAIN ROAD IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/23791,Roads,Completed,NP-PERUNGUDI,190,690000,"PROVIDING AND LAYING OF GSB AND INTERLOCKING BLOCKS AT CITIBABU NAGAR 1ST CROSS STREET ,,ALAGIRI STREET,KOVALAN NAGAR CROSS STREET,VIVEKANANDA NAGAR 3RD STREET-CROSS STREET, LAKSHMI NARAYANA PERUMAL KOIL STREET IN DN-190,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/23878,Roads,Completed,NP-PERUNGUDI,188,630000,"STRENGTHENING AND LAYING OF BT ROAD AT SAROJ NAGAR CROSS STREET IN DN - 188, U- 42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/24493,Roads,Completed,NP-PERUNGUDI,188,700000,"STRENGTHENING AND LAYING OF BT ROAD AT SAROJ NAGAR MAIN ROAD FROM (DR. RAMMOORTHY NAGAR 3RD STREET) IN DN-188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/24503,Roads,Completed,NP-PERUNGUDI,188,226000,"STRENGTHENING AND LAYING OF BT ROAD THANTHAI PERIYAR NAGAR NEHRU STREET IN DN-188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/24507,Roads,Completed,NP-PERUNGUDI,188,940000,"STRENGTHING AND LAYING OF BT ROAD AT JV NAGAR IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24532,Roads,Completed,NP-PERUNGUDI,188,2121000,"STRENGTHENING AND LAYING OF BT ROAD AT GOVINDAN STREET IN DN - 188 U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/24564,Roads,Completed,NP-PERUNGUDI,188,2121000,"STRENGTHENING AND LAYING OF BT ROAD AT NARAYANAN STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/24567,Electrical,Completed,NP-PERUNGUDI,191,999800,Provision of 20Nos of 6Mtr Lamp Post with 90-120W LED Fittings at Pudu Nagar 5th street Jalladaianpettai Burial Ground in Div 191in Zone 14,Own Sources,14,2015-16,2016-17 NP/2015-16/24571,Roads,Completed,NP-PERUNGUDI,169,708000,"ATTENDING PATCH WORK AT RAMALINGA NAGAR MAIN ROAD 0/0M TO 200M, SRI RAMAR KOVIL STREET, ARIVOLI STREET AND RAMKUMAR STREET 0/0M TO 65M IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/24582,Buildings,Completed,NP-PERUNGUDI,185,997000,"PROVIDING KATCHA DRAIN USING BY JCB AT VARIOUS STREET IN DN -185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/24591,Storm Water Drain,Completed,NP-PERUNGUDI,185,989000,"CONSTRUCTION OF CULVERT AT MGR NAGAR 1ST AND 2ND CROSS STREET,KANDASAMY NAGAR 4TH AND 6TH STREET AND VARIOUS STREET IN DN-185 UNIT-41 ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/24592,Storm Water Drain,Completed,NP-PERUNGUDI,185,989000,CONSTRUCTION OF SIDE DRAIN AT KRISHNA NAGAR 6TH STREET IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2015-16,2017-18 NP/2015-16/24633,Roads,Completed,NP-PERUNGUDI,189,970000,"Proposed speed breakers as per IRC Design with Bitminous concrete and providing Thermo Plastic Compound marking,Road pavement markers and signage boards at various streets in DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/24639,Roads,Completed,NP-PERUNGUDI,188,925000,"SUPPLYING AND FIXING OF RCC HUME PIPES AND ATTENDING OF PATCH WORKS AT VARIOUS STREETS IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24808,Roads,Completed,NP-PERUNGUDI,188,2121000,"STRENGTHING AND LAYING OF BT ROAD AT SRINIVASAN STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24813,Roads,Completed,NP-PERUNGUDI,188,2121000,"STRENGTHING AND LAYING OF BT ROAD AT VENKATESH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24817,Roads,Completed,NP-PERUNGUDI,188,2121000,"STRENGTHING AND LAYING OF BT ROAD AT KRISHNA STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24818,Roads,Completed,NP-PERUNGUDI,188,2065000,"STRENGTHING AND LAYING OF BT ROAD AT GANESH AVENUE IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24822,Roads,Completed,NP-PERUNGUDI,188,1652000,"STRENGTHING AND LAYING OF BT ROAD AT JESUDOSS STREET IN DN-188,U-42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/24825,Roads,Completed,NP-PERUNGUDI,188,1928000,"STRENGTHING AND LAYING OF BT ROAD AT SRIRAM STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24828,Roads,Completed,NP-PERUNGUDI,188,1652000,"STRENGTHING AND LAYING OF BT ROAD AT VAIGAI STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24831,Roads,Completed,NP-PERUNGUDI,188,1652000,"STRENGTHING AND LAYING OF BT ROAD AT THIRUVALLUVAR STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24834,Roads,Completed,NP-PERUNGUDI,188,1652000,"STRENGTHING AND LAYING OF BT ROAD AT STS STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24835,Roads,Completed,NP-PERUNGUDI,188,1818000,"STRENGTHING AND LAYING OF BT ROAD AT SRI NAGAR 6TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24860,Roads,Completed,NP-PERUNGUDI,183,992000,"ATTENDING PATCH WORK WITH WMM AT MGR NAGAR VARIOUS STREET IN DN-183,UNIT-41,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/24875,Buildings,Completed,NP-PERUNGUDI,183,964000,"Repairs to Toilet Block and other Improvements to Fish Market at Kottivakkam in Division 183, Unit 41, Zone 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24912,Roads,Completed,NP-PERUNGUDI,188,1928000,"STRENGTHING AND LAYING OF BT ROAD AT SRI NAGAER 5TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24913,Roads,Completed,NP-PERUNGUDI,188,1928000,"STRENGTHING AND LAYING OF BT ROAD AT SRI NAGAR 4TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24914,Roads,Completed,NP-PERUNGUDI,188,1928000,"STRENGTHING AND LAYING OF BT ROAD AT SRI NAGAR 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24915,Roads,Completed,NP-PERUNGUDI,188,1928000,"STRENGTHING AND LAYING OF BT ROAD AT SRI NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24916,Roads,Completed,NP-PERUNGUDI,188,4324000,"STRENGTHING AND LAYING OF BT ROAD AT PARTHASARATHY STREET IN DN-188,U-42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/24918,Roads,Completed,NP-PERUNGUDI,188,4958000,"STRENGTHING AND LAYING OF BT ROAD AT MUTHUMARIAMMAN KOIL STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24920,Roads,Completed,NP-PERUNGUDI,188,1928000,"STRENGTHING AND LAYING OF BT ROAD AT GANGAI STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24928,Roads,Completed,NP-PERUNGUDI,188,1928000,"STRENGTHING AND LAYING OF BT ROAD AT CAVERY STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24930,Roads,Completed,NP-PERUNGUDI,188,1377000,"STRENGTHENING AND LAYING OF BT ROAD AT ARUMUGAM STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24931,Roads,Completed,NP-PERUNGUDI,188,1032000,"STRENGTHENING AND LAYING OF BT ROAD AT THANTHAI PERIYAR NAGAR NESAMANI STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24934,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT THANTHAI PERIYAR NAGAR JV NAGAR IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24941,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT THANTHAI PERIYAR NAGAR SCHOOL STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24942,Roads,Completed,NP-PERUNGUDI,188,2065000,"STRENGTHENING AND LAYING OF BT ROAD AT THANTHAI PERIYAR NAGAR KANNADHASAN STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24943,Roads,Completed,NP-PERUNGUDI,188,2065000,"STRENGTHENING AND LAYING OF BT ROAD AT THANTHAI PERIYAR NAGAR BHARATHIYAR STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24945,Roads,Completed,NP-PERUNGUDI,188,826000,"STRENGTHENING AND LAYING OF BT ROAD AT WEST ANNA NAGAR 12TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24946,Roads,Completed,NP-PERUNGUDI,188,619000,"STRENGTHENING AND LAYING OF BT ROAD AT WEST ANNA NAGAR 9TH CROSS STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24947,Roads,Completed,NP-PERUNGUDI,188,1322000,"STRENGTHENING AND LAYING OF BT ROAD AT WEST ANNA NAGAR 9TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24948,Roads,Completed,NP-PERUNGUDI,188,1446000,"STRENGTHENING AND LAYING OF BT ROAD AT WEST ANNA NAGAR 6TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24950,Roads,Completed,NP-PERUNGUDI,188,3856000,"STRENGTHENING AND LAYING OF BT ROAD AT WEST ANNA NAGAR 5TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24951,Roads,Completed,NP-PERUNGUDI,188,3856000,"STRENGTHENING AND LAYING OF BT ROAD AT WEST ANNA NAGAR 4TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24952,Roads,Completed,NP-PERUNGUDI,188,743000,"STRENGTHENING AND LAYING OF BT ROAD AT RAGAVENDRA 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24953,Roads,Completed,NP-PERUNGUDI,188,743000,"STRENGTHENING AND LAYING OF BT ROAD AT RAGAVENDRA 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24955,Roads,Completed,NP-PERUNGUDI,188,785000,"STRENGTHENING AND LAYING OF BT ROAD AT SENGAZHANIAMMAN KOIL STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24956,Roads,Completed,NP-PERUNGUDI,188,3222000,"STRENGTHENING AND LAYING OF BT ROAD AT KANNAIAMMAN KOIL STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24958,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 13TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24959,Buildings,Completed,NP-PERUNGUDI,183,226000,Additional improvements to Anganvadi at New Colony at Kuppam road Side in Dn 183 Unit 41 Zone XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/24960,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 12TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24961,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 11TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24963,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 10TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24965,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 9TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24968,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 8TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24969,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 7TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24970,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 6TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24971,Roads,Completed,NP-PERUNGUDI,188,2844000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 5TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24973,Roads,Completed,NP-PERUNGUDI,188,2815000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 4TH STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24974,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24976,Roads,Completed,NP-PERUNGUDI,188,2892000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24977,Roads,Completed,NP-PERUNGUDI,188,1446000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH EXTN 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24978,Roads,Completed,NP-PERUNGUDI,188,2410000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR 18TH MAIN ROAD IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/24980,Roads,Completed,NP-PERUNGUDI,188,2410000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR 17TH MAIN ROAD IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25000,Roads,Completed,NP-PERUNGUDI,188,2410000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR 16TH MAIN ROAD IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25003,Roads,Completed,NP-PERUNGUDI,188,1156000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR 15TH MAIN ROAD IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25004,Roads,Completed,NP-PERUNGUDI,188,867000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR 14TH MAIN ROAD IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25006,Roads,Completed,NP-PERUNGUDI,188,626000,"STRENGTHENING AND LAYING OF BT ROAD AT MANIAMMAI STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25008,Roads,Completed,NP-PERUNGUDI,188,537000,"STRENGTHENING AND LAYING OF BT ROAD AT MURTHY STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25010,Roads,Completed,NP-PERUNGUDI,188,2093000,"STRENGTHENING AND LAYING OF BT ROAD AT MANNADIAMMAN KOIL STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25012,Roads,Completed,NP-PERUNGUDI,188,2493000,"STRENGTHENING AND LAYING OF BT ROAD AT BAJANAI KOIL STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25016,Roads,Completed,NP-PERUNGUDI,188,2065000,"STRENGTHENING AND LAYING OF BT ROAD AT THIRUMURUGAN STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25020,Roads,Completed,NP-PERUNGUDI,188,378000,"STRENGTHENING AND LAYING OF BT ROAD AT GOVINDASAMY NAGAR 2ND CROSS STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25022,Roads,Completed,NP-PERUNGUDI,188,358000,"STRENGTHENING AND LAYING OF BT ROAD AT GOVINDASAMY NAGAR 1ST CROSS STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25023,Roads,Completed,NP-PERUNGUDI,188,619000,"STRENGTHENING AND LAYING OF BT ROAD AT GOVINDASAMY NAGAR 2ND MAIN ROAD IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25024,Roads,Completed,NP-PERUNGUDI,188,516000,"STRENGTHENING AND LAYING OF BT ROAD AT JEEVA NAGAR 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25064,Buildings,Completed,NP-PERUNGUDI,185,610000,"CONSTRUCTION OF TOILET AND PEBBLE WALK AREA AT VGP PARK IN DIVISION-185, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2018-19 NP/2015-16/25070,Roads,Completed,NP-PERUNGUDI,188,454000,"STRENGTHENING AND LAYING OF BT ROAD AT JEEVA NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25071,Roads,Completed,NP-PERUNGUDI,188,2231000,"STRENGTHENING AND LAYING OF BT ROAD AT JEEVA NAGAR 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25072,Roads,Completed,NP-PERUNGUDI,188,330000,"STRENGTHENING AND LAYING OF BT ROAD AT ARUMUGAM NAGAR 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25073,Roads,Completed,NP-PERUNGUDI,188,440000,"STRENGTHENING AND LAYING OF BT ROAD AT ARUMUGAM NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25075,Roads,Completed,NP-PERUNGUDI,188,275000,"STRENGTHENING AND LAYING OF BT ROAD AT ARUMUGAM NAGAR 1ST STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25077,Roads,Completed,NP-PERUNGUDI,188,991000,"STRENGTHENING AND LAYING OF BT ROAD AT EMARALDE STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25079,Roads,Completed,NP-PERUNGUDI,188,1239000,"STRENGTHENING AND LAYING OF BT ROAD AT GOVINDARAJ IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25080,Roads,Completed,NP-PERUNGUDI,188,2065000,"STRENGTHENING AND LAYING OF BT ROAD AT ISWARIYA NAGAR 2ND CROSS STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25081,Roads,Completed,NP-PERUNGUDI,188,1074000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESHWARI NAGAR 4TH CROSS STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25083,Roads,Completed,NP-PERUNGUDI,188,1515000,"STRENGTHING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 3RD STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25085,Roads,Completed,NP-PERUNGUDI,188,723000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 2ND STREET IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25087,Roads,Completed,NP-PERUNGUDI,188,578000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 1ST CROSS STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25088,Roads,Completed,NP-PERUNGUDI,188,991000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 7TH STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25089,Roads,Completed,NP-PERUNGUDI,188,371000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 6TH STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25090,Roads,Completed,NP-PERUNGUDI,188,785000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 5TH STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25091,Roads,Completed,NP-PERUNGUDI,188,677000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 4TH STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25093,Roads,Completed,NP-PERUNGUDI,188,1074000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 1ST STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25094,Roads,Completed,NP-PERUNGUDI,188,895000,"STRENGTHENING AND LAYING OF BT ROAD AT ST. MARYS ROAD IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25096,Roads,Completed,NP-PERUNGUDI,188,3518000,"STRENGTHENING AND LAYING OF BT ROAD AT RAJARAJESWARI NAGAR 1ST MAIN ROAD IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25097,Roads,Completed,NP-PERUNGUDI,188,2479000,"STRENGTHENING AND LAYING OF BT ROAD AT KUBERA NAGAR EXTN 3RD STREET (PART) IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25098,Roads,Completed,NP-PERUNGUDI,188,1446000,"STRENGTHENING AND LAYING OF BT ROAD AT KUBERA NAGAR EXTN 4TH STREET (PART) IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25100,Roads,Completed,NP-PERUNGUDI,188,1431000,"STRENGTHENING AND LAYING OF BT ROAD AT KUBERA NAGAR EXTN 2ND STREET (PART) IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25101,Roads,Completed,NP-PERUNGUDI,188,1400000,"STRENGTHENING AND LAYING OF BT ROAD AT SHIVA VISHUNU KOIL STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25102,Roads,Completed,NP-PERUNGUDI,188,1835000,"STRENGTHENING AND LAYING OF BT ROAD AT SHARMA LAYOUT MAIN ROAD IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25104,Roads,Completed,NP-PERUNGUDI,188,3181000,"STRENGTHENING AND LAYING OF BT ROAD AT BRINDHAVAN STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25105,Roads,Completed,NP-PERUNGUDI,188,2306000,"STRENGTHENING AND LAYING OF BT ROAD AT KUMARAN STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25106,Roads,Completed,NP-PERUNGUDI,188,1198000,"STRENGTHENING AND LAYING OF BT ROAD AT SRINIVASAN STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25108,Roads,Completed,NP-PERUNGUDI,188,867000,"STRENGTHENING AND LAYING OF BT ROAD AT JAGANATHAN STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25110,Roads,Completed,NP-PERUNGUDI,188,743000,"STRENGTHENING AND LAYING OF BT ROAD AT SEETHAPATHI STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25111,Roads,Completed,NP-PERUNGUDI,188,220000,"STRENGTHENING AND LAYING OF BT ROAD AT KARUNAIGANAPATHI STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25112,Roads,Completed,NP-PERUNGUDI,188,578000,"STRENGTHENING AND LAYING OF BT ROAD AT VENKATESAN STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25113,Roads,Completed,NP-PERUNGUDI,188,826000,"STRENGTHENING AND LAYING OF BT ROAD AT AAVIN GARDEN STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25114,Roads,Completed,NP-PERUNGUDI,188,275000,"STRENGTHENING AND LAYING OF BT ROAD AT MANIKANDAN 4TH STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25116,Roads,Completed,NP-PERUNGUDI,188,241000,"STRENGTHENING AND LAYING OF BT ROAD AT MANIKANDAN 3RD STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25117,Roads,Completed,NP-PERUNGUDI,188,275000,"STRENGTHENING AND LAYING OF BT ROAD AT MANIKANDAN 2ND STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25118,Roads,Completed,NP-PERUNGUDI,188,413000,"STRENGTHENING AND LAYING OF BT ROAD AT KAMAKODI STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25119,Roads,Completed,NP-PERUNGUDI,188,413000,"STRENGTHENING AND LAYING OF BT ROAD AT N.V RAJAN STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25122,Roads,Completed,NP-PERUNGUDI,188,2699000,"STRENGTHENING AND LAYING OF BT ROAD AT THILAKAR AVENUE 7TH CROSS STREET (PART) IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25123,Roads,Completed,NP-PERUNGUDI,188,2333000,"STRENGTHENING AND LAYING OF BT ROAD AT EARIKARAI MAIN ROAD IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25124,Roads,Completed,NP-PERUNGUDI,188,3229000,"STRENGTHENING AND LAYING OF BT ROAD AT THILAKAR AVENUE 1ST MAIN ROAD IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25125,Roads,Completed,NP-PERUNGUDI,188,991000,"STRENGTHENING AND LAYING OF BT ROAD AT KALAYANA KANDHASAMY STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25126,Roads,Completed,NP-PERUNGUDI,188,429000,"STRENGTHENING AND LAYING OF BT ROAD AT AADHI STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25128,Roads,Completed,NP-PERUNGUDI,188,550000,"STRENGTHENING AND LAYING OF BT ROAD AT MGR 2ND STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25130,Roads,Completed,NP-PERUNGUDI,188,826000,"STRENGTHENING AND LAYING OF BT ROAD AT MGR 1ST STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25131,Roads,Completed,NP-PERUNGUDI,188,1999000,"STRENGTHENING AND LAYING OF BT ROAD AT BHARATHIYAR STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25133,Roads,Completed,NP-PERUNGUDI,188,330000,"STRENGTHENING AND LAYING OF BT ROAD AT KRISHNA NAGAR 5TH CROSS STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25141,Roads,Completed,NP-PERUNGUDI,188,330000,"STRENGTHENING AND LAYING OF BT ROAD AT KRISHNA NAGAR 3RD CROSS STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25142,Roads,Completed,NP-PERUNGUDI,188,330000,"STRENGTHENING AND LAYING OF BT ROAD AT KRISHNA NAGAR 2ND CROSS STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25143,Roads,Completed,NP-PERUNGUDI,188,413000,"STRENGTHENING AND LAYING OF BT ROAD AT KRISHNA NAGAR 1ST CROSS STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25144,Roads,Completed,NP-PERUNGUDI,188,1253000,"STRENGTHENING AND LAYING OF BT ROAD AT UNMAI NAGAR 1ST STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25146,Roads,Completed,NP-PERUNGUDI,188,4131000,"STRENGTHENING AND LAYING OF BT ROAD AT LIC NAGAR 6TH STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25147,Roads,Completed,NP-PERUNGUDI,188,1115000,"STRENGTHENING AND LAYING OF BT ROAD AT MYLLAI KARBAGAMBAL NAGAR 3RD STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25149,Roads,Completed,NP-PERUNGUDI,188,661000,"STRENGTHENING AND LAYING OF BT ROAD AT MYLLAI KARBAGAMBAL NAGAR 2ND STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25150,Roads,Completed,NP-PERUNGUDI,188,516000,"STRENGTHENING AND LAYING OF BT ROAD AT MYLLAI KARBAGAMBAL NAGAR 1ST STREET IN DN - 188, U - 42, Z- 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25180,Roads,Completed,NP-PERUNGUDI,188,1032000,"STRENGTHENING AND LAYING OF BT ROAD AT MYLLAI KARPAGAMBAL NAGAR MAIN ROAD IN DN-188,U-42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/25212,Roads,Completed,NP-PERUNGUDI,188,447000,"STRENGTHENING AND LAYING OF BT ROAD AT KABALEESWARAR NAGAR 3RD STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25213,Roads,Completed,NP-PERUNGUDI,188,688000,"STRENGTHENING AND LAYING OF BT ROAD AT KABALEESWARAR NAGAR 2ND STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25215,Roads,Completed,NP-PERUNGUDI,188,757000,"STRENGTHENING AND LAYING OF BT ROAD AT KABALEESWARAR NAGAR 1ST STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25216,Roads,Completed,NP-PERUNGUDI,188,1191000,"STRENGTHENING AND LAYING OF BT ROAD AT ENFIELD AVENUE 3RD STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25217,Roads,Completed,NP-PERUNGUDI,188,1122000,"STRENGTHENING AND LAYING OF BT ROAD AT ENFIELD AVENUE 2ND STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25218,Roads,Completed,NP-PERUNGUDI,188,1253000,"STRENGTHENING AND LAYING OF BT ROAD AT ENFIELD AVENUE 1ST STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25219,Roads,Completed,NP-PERUNGUDI,188,895000,"STRENGTHENING AND LAYING OF BT ROAD AT ANNA NAGAR 11TH MAIN ROAD IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25220,Roads,Completed,NP-PERUNGUDI,188,1377000,"STRENGTHENING AND LAYING OF BT ROAD AT ANNA NAGAR 10TH MAIN ROAD IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25221,Roads,Completed,NP-PERUNGUDI,188,1300000,"STRENGTHENING AND LAYING OF BT ROAD AT ANNA NAGAR 8TH MAIN ROAD IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25222,Roads,Completed,NP-PERUNGUDI,188,1115000,"STRENGTHENING AND LAYING OF BT ROAD AT SARATHY NAGAR 2ND STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25223,Roads,Completed,NP-PERUNGUDI,188,826000,"STRENGTHENING AND LAYING OF BT ROAD AT ANNA NAGAR 4TH MAIN ROAD IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25224,Roads,Completed,NP-PERUNGUDI,188,826000,"STRENGTHENING AND LAYING OF BT ROAD AT ANNA NAGAR 3RD MAIN ROAD IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25225,Roads,Completed,NP-PERUNGUDI,188,1239000,"STRENGTHENING AND LAYING OF BT ROAD AT VENKATRAMANAN STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25226,Roads,Completed,NP-PERUNGUDI,188,192000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR EXTN 5TH CROSS STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25228,Roads,Completed,NP-PERUNGUDI,188,275000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR EXTN 4TH CROSS STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25229,Roads,Completed,NP-PERUNGUDI,188,712000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR EXTN 3RD CROSS STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25232,Roads,Completed,NP-PERUNGUDI,188,464000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR EXTN 2ND CROSS STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25233,Roads,Completed,NP-PERUNGUDI,188,309000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR EXTN 1ST CROSS STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25234,Roads,Completed,NP-PERUNGUDI,188,220000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR 8TH STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25235,Roads,Completed,NP-PERUNGUDI,188,468000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR 7TH STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25237,Roads,Completed,NP-PERUNGUDI,188,991000,"STRENGTHENING AND LAYING OF BT ROAD AT MAHALAKSHMI NAGAR 4TH STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25238,Roads,Completed,NP-PERUNGUDI,188,991000,"STRENGTHENING AND LAYING OF BT ROAD AT SIGAMANI NAGAR 3RD STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25240,Roads,Completed,NP-PERUNGUDI,188,330000,"STRENGTHENING AND LAYING OF BT ROAD AT SIGAMANI NAGAR 2ND STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25242,Roads,Completed,NP-PERUNGUDI,188,1074000,"STRENGTHENING AND LAYING OF BT ROAD AT SIGAMANI NAGAR 1ST STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25244,Roads,Completed,NP-PERUNGUDI,188,1363000,"STRENGTHENING AND LAYING OF BT ROAD AT SIGAMANI NAGAR MAIN ROAD IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/25418,Roads,Completed,NP-PERUNGUDI,168,900000,ATTENDING PATCH WORK AT VARIOUS STREET IN DN-168 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/25671,Roads,Completed,NP-PERUNGUDI,188,984000,"STRENGTHENING AND LAYING OF BT ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 5TH STREET IN DN-188,U-42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/25672,Roads,Completed,NP-PERUNGUDI,188,826000,"STRENGTHENING AND LAYING OF BT ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD (PART) IN DN-188,U-42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/25675,Roads,Completed,NP-PERUNGUDI,188,1900000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH 10TH MAIN ROAD (PART) IN DN-188,U-42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/25676,Roads,Completed,NP-PERUNGUDI,188,1900000,"STRENGTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH 12TH MAIN ROAD (PART) IN DN-188,U-42, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/25741,Playfields,Completed,NP-PERUNGUDI,189,930000,"Strengthening of Nasan Kulam Bund (North Side) and forming Kabadi Ground at Thullukkanathamman Koil Street in Dn-189, Unit-43, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/25744,Playfields,Completed,NP-PERUNGUDI,189,992000,"Repairs and improvement to cremation Hall at Thullukknathamman Koil Street in Dn189, Unit-43, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/26232,Storm Water Drain,Completed,NP-PERUNGUDI,185,984000,"CONSTRUCTION OF CULVERT AT CANAL,MAHATHMA GANDHI 1ST STREET,GOVINDAN NAGAR MAIN ROAD AND VARIOUS STREET IN DN-185 UNIT-41 ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/26233,Storm Water Drain,Completed,NP-PERUNGUDI,185,986000,CONSTRUCTION OF SIDE DRAIN AT KARUMARI AMMA KOVIL STREET IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2015-16,2017-18 NP/2015-16/26234,Storm Water Drain,Completed,NP-PERUNGUDI,169,985000,"CONSTRUCTION OF CULVERT AT ARUL JOTHI STREET,RAMALINGAM MAIN ROAD, BALAJI NAGAR MAIN ROAD AND VARIOUS STREET IN DN-169 UNIT-42 ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/26235,Storm Water Drain,Completed,NP-PERUNGUDI,169,982000,"CONSTRUCTION OF CULVERT AT MURUGAPPAN STREET BALAJI NAGAR 18TH STREET,PUZHITHIVALKKAM BUS STAND,GANESH NAGAR , ERIKARAI STREET AND LAYING HUME PIPE IN DN-169 UNIT-42 ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/26236,Storm Water Drain,Completed,NP-PERUNGUDI,169,993000,RAISING AND PROVIDING TOP SLAB TO SIDE DRAIN AT NSC BOSE STREET IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2017-18 NP/2015-16/2654,Roads,Completed,NP-PERUNGUDI,186,988000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGNAGE BOARD,PAVEMENT MARKER,ROAD STRUDS AT VARIOUS STREET IN DN-186,UNIT-41,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/2656,Roads,Completed,NP-PERUNGUDI,186,988000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGNAGE BOARD,PAVEMENT MARKER,ROAD STRUDS AT CORPORATION ROAD AND THIRUMALAI NAGAR IN DN-186, UNIT-41, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/26667,Roads,Completed,NP-PERUNGUDI,183,980000,"LAYING OF CEMENT CONCRETE ROAD AT PURATCHI THALAIVI MAIN ROAD FROM THARAMANI ROAD TO PURATCHI THALAIVI 6TH CROSS STREE IN DN-183,UNIT-41,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/26677,Roads,Completed,NP-PERUNGUDI,183,986000,"LAYING OF CEMENT CONCRETE ROAD AT PURATCHI THALAIVI MAIN ROAD FROM PURATCHI THALAIVI 6TH CROSS STREE TO M.G.R.STREET IN DN-183,UNIT-41,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/26679,Roads,Completed,NP-PERUNGUDI,183,970000,"LAYING OF CEMENT CONCRETE ROAD AT PURATCHI THALAIVI 1ST CRO9SS,2ND CROSS,3RD CROSS IN DN-183,UNIT-41,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/26680,Roads,Completed,NP-PERUNGUDI,183,970000,"LAYING OF CEMENT CONCRETE ROAD AT PURATCHI THALAIVI 4TH CRO9SS,5THCROSS,6TH CROSS IN DN-183,UNIT-41,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/26681,Roads,Completed,NP-PERUNGUDI,183,934000,"LAYING OF CEMENT CONCRETE ROAD AT PURATCHI THALAIVI 7TH CRO9SS,9THCROSS,10TH CROSS,11TH CROSS STREET IN DN-183,UNIT-41,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/26682,Roads,Completed,NP-PERUNGUDI,183,977000,"LAYING OF CEMENT CONCRETE ROAD AT PURATCHI THALAIVI 8TH CROSS,12TH CROSS,13TH CROSS, IN DN-183,UNIT-41,ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/27212,Parks,Completed,NP-PERUNGUDI,184,723000,"ANNUAL MAINTENANCE OF CBI COLONY PARK, PERUNGUDI IN DIVISION 184, UNIT 41, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/27214,Parks,Completed,NP-PERUNGUDI,184,735000,"ANNUAL MAINTENANCE OF THIRIVALLUVAR PARK, PERUNGUDI IN DIVISION 184, UNIT 41, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/27346,Buildings,Completed,NP-PERUNGUDI,183,92000,Repairs and Improvements to AMMA UNAVAGAM at Velachery-Tharamani road in Dn 183 Unit 41 Zone XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/27350,Buildings,Completed,NP-PERUNGUDI,183,267000,"Repairs and Improvements to Amma Unavagam at ECR in Division 183, Unit 41, Zone 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/27353,Storm Water Drain,Completed,NP-PERUNGUDI,183,359000,"Replacing the damaged gratings at Nehru nagar,Venkateswara streets and Sangam colony in Dn 183 Unit 41 Zone XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/27355,Buildings,Completed,NP-PERUNGUDI,183,138000,Supplying and Filling Earth at Natco Colony Corporation Park and Lakshmi Nagar Jaganathan Street Park in Dn 183 Unit 41 Zone XIV,Own Sources,14,2015-16,2017-18 NP/2015-16/27358,Roads,Completed,NP-PERUNGUDI,183,928000,"Attending Patch Work at Lakshmana Perumal 5th Street, Venkateshwara Nagar, Elango Nagar, Judges Colony, New Colony and AGS 2nd Main Road In Dn 183 Unit 41 Zone XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/27361,Storm Water Drain,Completed,NP-PERUNGUDI,183,697000,"Improvements To Side Drain at Natesan Colony Sriram Avenue 1st Street, Providing Inspection Chambers to Side Drain at Srinivasa Avenue 2nd Street (Bay 8-13) and Repairs to Various Streets Stroam Water Drain in Dn 183 Unit 41 Zone XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/27364,Roads,Completed,NP-PERUNGUDI,183,233000,"Providing Rain Water Harvesting well, RCC and Pre Cast Slab Work at ECR Road in Dn 183 Unit 41 Zone XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/27369,Storm Water Drain,Completed,NP-PERUNGUDI,183,666000,IMPROVEMENT TO SIDE DRAIN BY RAISING SIDE WALL AND COVERING WITH TOP SLAB AT SRINIVASA NAGAR 2ND STREET (ON WESTERN AND SOUTHERN SIDE PART) IN DN 183UNIT-41 ZONE-XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/27465,Storm Water Drain,Completed,NP-PERUNGUDI,183,907000,Construction of culverts at various Streets (9 locations) in Dn 183 Unit 41 Zone XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/27466,Buildings,Completed,NP-PERUNGUDI,188,744000,"Improvements to Toilet Block at Sanitary Inspector Office and other Improvements to E Seva Centre at Kulakarai Street in Division 188, Unit 42, Zone 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/27467,Culvert,Completed,NP-PERUNGUDI,188,995000,Construction of Culvert at Narayanapuram Eri at the Junction of Balaambugan Nagar in Dn 188 Unit 42 Zone XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/27469,Buildings,Completed,NP-PERUNGUDI,189,998000,"Proposed construction of Store Room in second floor and other improvements to Division-189 office at Thulukanathamman koil street in Dn-189,UnitT-43,Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/27716,Roads,Completed,NP-PERUNGUDI,190,834000,"PROVIDING AND LAYING GSB, AT RAJESH AVENUE (AMBAL NAGAR)IN DN- 190 UNIT-43 ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/27719,Roads,Completed,NP-PERUNGUDI,190,810000,"PROVIDING AND LAYING GSB, AT AMBAL NAGAR 1ST MAIN ROAD AND DILLIBABU STREET IN DN-190 UNIT-43 ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/27817,Storm Water Drain,Completed,NP-PERUNGUDI,188,940000,"IMPROVEMENTS TO SIDE DRAIN AT GOVINDASAMY NAGAR 11TH STREET IN DN - 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/28302,Roads,Completed,NP-PERUNGUDI,185,983000,"Laying Cement Concrete Road By RMC At Anbazagan Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28321,Roads,Completed,NP-PERUNGUDI,185,974000,"Laying Cement Concrete Road By RMC At Anbazagan Main Road and 1st Cross Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28322,Roads,Completed,NP-PERUNGUDI,185,988000,"Laying Cement Concrete Road By RMC At Anbazagan 2nd Cross Street and 3rd Cross Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28323,Roads,Completed,NP-PERUNGUDI,185,939000,"Laying Cement Concrete Road By RMC At Narayanasamy Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28324,Roads,Completed,NP-PERUNGUDI,185,705000,"Laying Cement Concrete Road By RMC At NSK Krishnan Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28325,Roads,Completed,NP-PERUNGUDI,185,956000,"Laying Cement Concrete Road By RMC At Aasai Thambi Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28330,Roads,Completed,NP-PERUNGUDI,185,964000,"Laying Cement Concrete Road By RMC At Pachaiyappar 1st, 10th & 11th Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28340,Roads,Completed,NP-PERUNGUDI,185,982000,"Laying Cement Concrete Road By RMC At Kolavizhiamman 8th Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28341,Roads,Completed,NP-PERUNGUDI,185,983000,"Laying Cement Concrete Road By RMC At DSG nagar 3 rd Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28345,Roads,Completed,NP-PERUNGUDI,185,779000,"Laying Cement Concrete Road By RMC At DSG nagar 1 st street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28349,Roads,Completed,NP-PERUNGUDI,185,655000,"Laying Cement Concrete Road By RMC At DSG mian road in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28351,Roads,Completed,NP-PERUNGUDI,185,974000,"Laying Cement Concrete Road By RMC At Kolavizhiamman 5th (c)street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28353,Roads,Completed,NP-PERUNGUDI,185,724000,"Laying Cement Concrete Road By RMC At Kolavizhiamman 6th and 9th Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28359,Roads,Completed,NP-PERUNGUDI,185,706000,"Laying Cement Concrete Road By RMC At Kolavizhiamman 7th Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28364,Roads,Completed,NP-PERUNGUDI,185,934000,"Laying Cement Concrete Road By RMC At Kolavizhiamman 10th Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28366,Roads,Completed,NP-PERUNGUDI,185,980000,"Laying Cement Concrete Road By RMC At Kolavizhiamman 11th & 12th Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28370,Roads,Completed,NP-PERUNGUDI,185,779000,"Laying Cement Concrete Road By RMC At Kolavizhiamman 13th, 14th & 15th Street in DN- 185, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28432,Buildings,Completed,NP-PERUNGUDI,186,921000,"CONSTRUCTION OF MULTIPURPOSE HALL AT KURINCHI NAGAR 14TH STREET IN DN-186,U-41, ZONE14.",Own Sources,14,2015-16,2016-17 NP/2015-16/28625,Parks,Completed,NP-PERUNGUDI,189,940000,".Additional Improvements to Mooligai Park at Thambaram-Velachery Main road, Thamarai Kulam and IIT Colony Park in Dn 189 Unit 43 Zone XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/28631,Parks,Completed,NP-PERUNGUDI,169,910000,IMPROVEMENT TO AGS COLONY PARK IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/28643,Parks,Completed,NP-PERUNGUDI,169,911000,REPAIRS AND IMPROVEMENT TO ANNAI THERASA NAGAR PARK IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/28645,Buildings,Completed,NP-PERUNGUDI,188,975000,"Repairs to Division 188 Office Toilet Block, Councillor Office and Primary Health Center at Madipakkam Bus Terminus in Division 188, Unit 42, Zone 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/28646,Parks,Completed,NP-PERUNGUDI,169,914000,REPAIRS AND IMPROVEMENT TO BALAJI NAGAR PARK AND PLAY GROUND IN DIVISION -169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/28649,Buildings,Completed,NP-PERUNGUDI,188,845000,"Improvements to Toilet block and other Improvements to Conservancy Annex Building at Myllai Balaji Nagar 3rd Block in Division 188, Unit 42, Zone 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/28655,Buildings,Completed,NP-PERUNGUDI,190,942000,Repairs and Improvements to the exisitng building to convert as E-Seva room at Velachery -Tambaram Main road Near Amma Unavagam in Dn 190 Unit 43 Zone XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/28660,Buildings,Completed,NP-PERUNGUDI,191,457000,"Repair and Improvement to E Sevai Centre and Other Maintenance works in Dn-191, Unit-43, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28661,Buildings,Completed,NP-PERUNGUDI,191,490000,"Proposed additional construction of handicapped toilet and Other Improvements to PC at Kalai Koothu Nagar and Gandhi Street in Dn-191, Unit-43, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/28664,Buildings,Completed,NP-PERUNGUDI,191,415000,.Changing the name as Greater Chennai in Corporation Buildings in Dn 191 Unit 43 Zone XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/28725,Parks,Completed,NP-PERUNGUDI,169,911000,CONSTRUCTION OF COMPOUND WALL AT SARATHY NAGAR 2ND STREET PARK IN DIVISION -169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/28800,Roads,Completed,NP-PERUNGUDI,186,995000,"PROVIDING AND LAYING PAVAR BLOCK AND RAISING MAN HOLE DOORS AT CORPORATION ROAD AND RAJIV NAGAR 1ST MAIN ROAD IN DIVISION-186,U-42,Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/28842,Buildings,Completed,NP-PERUNGUDI,184,997000,PROPOSED CONSTRUCTION OF PUBLIC CONVENIENCE AT ERRIKARAI SALAI IN DIVISION -184 UNIT-41 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/29035,Roads,Completed,NP-PERUNGUDI,168,999000,PROVIDING SPEED BREAKERS AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGNAGE BOARD PAVEMENT MARKER AND ROAD STRUDS AT RAJARATHINAM STREET AND VARIOUS STREET IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/29120,Roads,Completed,NP-PERUNGUDI,169,998999,"PROVIDING SPEED BREAKERS AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGNAGE BOARD PAVEMENT MARKER AND ROAD STRUDS AT ANNAI THERASA NAGAR, SADASIVAM NAGAR , BAJANAI KOIL STREET AND VARIOUS STREET IN DIVISION -169 UNIT-42 ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/29175,Roads,Completed,NP-PERUNGUDI,184,999000,PROVIDING SPEED BREAKERS AS PER IRC DESIGN WIH BITUMINOUS CONCREE AND ALSO FIXING SIGNAGE BOARD PAVEMENT MARKERS AND ROAD STRUDS AT VARIOUS STREET IN DIVISION -184 UNIT-41 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/29180,Roads,Completed,NP-PERUNGUDI,185,999664,PROVIDING SPEED BREAKERS AS PER IRC DESIGN WIH BITUMINOUS CONCREE AND ALSO FIXING SIGNAGE BOARD PAVEMENT MARKERS AND ROAD STRUDS AT VARIOUS STREET IN DIVISION -185 UNIT-41 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/29329,Roads,Completed,NP-PERUNGUDI,184,955000,LAYING CEMENT CONCRETE ROAD AT THIRUVALLUVAR STREET (FROM JN OF SAIAYUSH POOJA TO CMWSSB WATER POINT) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/29446,Roads,Completed,NP-PERUNGUDI,186,961000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 2ND MAIN ROAD WEST SIDE IN DN-186, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/29464,Roads,Completed,NP-PERUNGUDI,184,955000,LAYING CEMENT CONCRETE ROAD AT THIRUVALLUVAR STREET (FROM CMWSSB WATER POINT TO PARK END) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/29467,Roads,Completed,NP-PERUNGUDI,184,817000,LAYING CEMENT CONCRETE ROAD AT THIRUVALLUVAR STREET (FROM PARK END TO JN OF KARPAGAVINAYAGAR KOIL ST ) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/29535,Roads,Completed,NP-PERUNGUDI,183,346000,"Laying of cement concrete road at sathya nagar 1st street at division 183,unit-41,zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/29547,Roads,Completed,NP-PERUNGUDI,183,362000,"Laying of cement concrete road at sathya nagar 2nd street in division 183,unit-41,zone -14",Own Sources,14,2015-16,2016-17 NP/2015-16/29550,Roads,Completed,NP-PERUNGUDI,183,416000,"Laying of cement concrete road at sathya nagar 3rd street in division 183,unit-41,zone -14",Own Sources,14,2015-16,2016-17 NP/2015-16/29553,Roads,Completed,NP-PERUNGUDI,183,375000,"Laying of cement concrete road at sathya nagar 4th street in division 183,unit-41,zone -14",Own Sources,14,2015-16,2016-17 NP/2015-16/29559,Roads,Completed,NP-PERUNGUDI,183,340000,"Laying of cement concrete road at sathya nagar 5th street in division 183,unit-41,zone -14",Own Sources,14,2015-16,2016-17 NP/2015-16/29568,Buildings,Completed,NP-PERUNGUDI,168,997000,PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT KUBERN MUNUSAMY STREET NEAR ANGANWADI CENTER IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/29585,Roads,Completed,NP-PERUNGUDI,186,927000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 2ND MAIN ROAD EAST SIDE IN DN -186, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/29588,Buildings,Completed,NP-PERUNGUDI,186,517000,"CONSTRICTION OF CEMENT CONCRITE WALL AND IMPROVEMENT TO KULAM AT VEEMPULIAMMAN KOIL STREET IN DN-186, UNIT-41, ZONE-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/29883,Roads,Completed,NP-PERUNGUDI,186,824000,"FORMING WITH GSB AT SEEVARAM 1ST STREETN AND 3RD STREET IN DN-186, UNIT-41, ZONE14.",Own Sources,14,2015-16,2016-17 NP/2015-16/29960,Roads,Completed,NP-PERUNGUDI,186,799000,"FORMING WITH GSB AT MANIKODISRINIVASAN NAGAR 3RD STREET, 5TH STREET AND SENTHIL NAGAR MAIN ROAD IN DN-186, UNIT-41, ZONE14.",Own Sources,14,2015-16,2016-17 NP/2015-16/29963,Roads,Completed,NP-PERUNGUDI,186,841000,"FORMING WITH GSB AT MANIKODISRINIVASAN NAGAR MAIN ROAD, 1ST STREET AND 2ND STREET IN DN-186, UNIT-41, ZONE14.",Own Sources,14,2015-16,2017-18 NP/2015-16/29965,Roads,Completed,NP-PERUNGUDI,186,979000,"FORMING WITH GSB AT PANCHAYAT MAIN ROAD, VEERAPANDIYA KATTABOMMAN STREET IN DN-186, UNIT-41, ZONE14.",Own Sources,14,2015-16,2016-17 NP/2015-16/29966,Roads,Completed,NP-PERUNGUDI,186,900000,"FORMING WITH GSB AT VEERAVANCHINATHAN MAIN ROAD , 1ST STREET AND SOWDHARIYA NAHGAR IN DN-186, UNIT-41, ZONE14.",Own Sources,14,2015-16,2016-17 NP/2015-16/29973,Roads,Completed,NP-PERUNGUDI,184,952000,LAYING CEMENT CONCRETE ROAD AT THIRUVALLUVAR STREET (FROM JN OF MGR SALAI TO E B POST 1437) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/29975,Roads,Completed,NP-PERUNGUDI,184,944000,LAYING CEMENT CONCRETE ROAD AT THIRUVALLUVAR STREET (FROM CASA GRAND TO EB POST 1437) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/29979,Roads,Completed,NP-PERUNGUDI,184,621000,LAYING CEMENT CONCRETE ROAD AT THIRUVALLUVAR STREET (FROM SAIAYUSH POOJA TO CASA GRAND) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/30080,Roads,Completed,NP-PERUNGUDI,169,440000,SUPPLY OF TATA ACE AND LABOUR FOR HIRE BASIC WITH INCLUDING FUEL CHARGES AND DRIVERS SALARY FOR FLOOD WORK IN DIV 169 UNIT 42 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/30147,Buildings,Completed,NP-PERUNGUDI,169,996000,PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT 1.(ANGANVADI) PUZHUTHIVAKKAM BUS STAND ENTRANCE IN DIVISION -169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/30148,Buildings,Completed,NP-PERUNGUDI,169,997000,PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL 2 ( ANGANVADI) . AT PUZHUTHIVAKKAM BUS STAND BACK SIDE OF AMMA UNAVAGAM IN DIVISION -169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/30149,Buildings,Completed,NP-PERUNGUDI,169,995000,PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL 3(ANGANVADI) AT PUZHUTHIVAKKAM BUS STAND ( SOUTH SIDE ) IN DIVISION -169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/30152,Buildings,Completed,NP-PERUNGUDI,169,997000,PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL 4(ANGANVADI) AT PUZHUTHIVAKKAM BUS STAND ( SOUTH WEST ) IN DIVISION -169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/30164,Playfields,Completed,NP-PERUNGUDI,189,995000,"IMPROVEMENTS TO KAMAKOTTI NAGAR 4TH STREET PLAY GROUND IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/30577,Roads,Completed,NP-PERUNGUDI,184,874000,RESTORATION OF ROAD CUT BY CMWSSB AT TELEPHONE NAGAR MAIN ROAD IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2017-18 NP/2015-16/30581,Roads,Completed,NP-PERUNGUDI,184,787000,FORMING OF ROAD AT TELEPONE NAGAR MAIN ROAD IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2017-18 NP/2015-16/30648,Buildings,Completed,NP-PERUNGUDI,191,950000,"Proposed construction of compound wall at Ex-service man colony Amma unavagam in DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/30754,Parks,Completed,NP-PERUNGUDI,189,980000,"Annual Maintenance of Park and Children play ground at Thamarai kullam in pallikaranai in dn-189, unit-43,zone-14.",Own Sources,14,2015-16,2017-18 NP/2015-16/30767,Roads,Completed,NP-PERUNGUDI,184,996000,"LAYING B T ROAD BY PAVER FINISHER AT SERAN SENGUTTUVAN STREET, SAIAYUSH POOJA AVENUE CROSS STREETS IN DN 184 UT 41 ZONE 14",Own Sources,14,2015-16,2016-17 NP/2015-16/30770,Roads,Completed,NP-PERUNGUDI,184,990000,LAYING B T ROAD BY PAVER FINISHER AT SAIAYUSH POOJA AVENUE MAIN ROAD IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/30903,Buildings,Completed,NP-PERUNGUDI,189,830000,"Providing & FIxing S.S. Name Board, S.S. Letters and Painting for Compound wall & Walking Track at Thamarai Kulam in Dn 189, Unit 43, Zone 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/30939,Storm Water Drain,Completed,NP-PERUNGUDI,188,980000,"CONSTRUCTION OF PRECAST CULVERT AT KUBERAN NAGAR EXTN MAIN ROAD IN DN- 188, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/31024,Roads,Completed,NP-PERUNGUDI,187,995000,"LAYING OF BT ROAD AT MADIPAKKAM MAIN ROAD (FROM PONNIAMMAN KOIL STREET TO PLOT NO: 5/360) AT DN - 187, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/31050,Road Cut,Completed,NP-PERUNGUDI,184,999000,"RESTORATION OF ROAD CUT [CMWSSB] AT TELEPHONE NAGAR 11TH CROSS STREET, 12TH CROSS STREET, 13TH CROSS STRET,14TH CROSS STREET, 17TH CROSS STREET ,19TH CROSS STREET IN DN-184 , U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/31055,Road Cut,Completed,NP-PERUNGUDI,184,991000,"RESTORATION OF ROADCUT [CMWSSB] AT TELEPHONE NAGAR 2ND CROSS STREET, 3RD CROSS STREET, 4TH CROSS STREET, 5TH CROSS STREET, 15TH CROSS STRRET, 17TH CROSS STREET, 18TH CROSS STREET AND TELEPHONE NAGAR MAIN ROAD (SOUTH ) IN DN-184, U-41, Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/31056,Road Cut,Completed,NP-PERUNGUDI,184,993000,"RESTORATION OF ROAD CUT [CMWSSB] AT TELEPHONE 1ST CROSS STREET, 7TH CROSS STREET, 8TH CROSS STREET, 9TH CROSS STREET, 10TH CROSS STREET, TELEPHONE NAGAR MAIN ROAD (NORTH ) PILLAYAR KOIL STREET IN DN-184 , U-41 Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/31125,Roads,Completed,NP-PERUNGUDI,191,2411000,"Forming,Strengthening and laying of B.T Road From Selene Estate Park to India bulls E1 Building (Phase-II) in DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/31126,Roads,Completed,NP-PERUNGUDI,191,2411000,"Forming,Strengthening and laying of B.T Road From India bulls E1 Building to D3 Building (Phase-II) in DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/31130,Buildings,Completed,NP-PERUNGUDI,191,248000,Improvements to Health Centre at Thiruvalluvar nagar at Jalladampet in Dn 191 Unit 43 Zone XIV,Own Sources,14,2015-16,2016-17 NP/2015-16/31131,Buildings,Completed,NP-PERUNGUDI,191,266000,"Improvements to Anganwadis at Thiruvalluvar nagar ,Jayanthi Natarajan street and Veerathamman Koil street in Jalladampet in Dn 191 Unit 43 Zone XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/31690,Roads,Completed,NP-PERUNGUDI,187,950000,"LAYING OF BT ROAD AT MADIPAKKAM MAIN ROAD (FROM PLOT NO: 67 TO NEHRU 2ND STREET ) IN DN - 187, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/31691,Roads,Completed,NP-PERUNGUDI,187,950000,"LAYING OF BT ROAD AT MADIPAKKAM MAIN ROAD (FROM NEHRU 2ND STREET TO PLOT NO: 5/128) IN DN - 187, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/31702,Roads,Completed,NP-PERUNGUDI,187,995000,"LAYING OF BT ROAD AT MADIPAKKAM MAIN ROAD (FROM PLOT NO: 5/128 TO MADAVAKKAM - MOUNT ROAD) IN DN - 187, U - 42, Z - 14",Own Sources,14,2015-16,2016-17 NP/2015-16/31743,Road Cut,Completed,NP-PERUNGUDI,184,907000,"RESTORATION OF CMWSSB ROAD CUT AT CBI COLONY 1ST CROSS , 2ND CROSS STREET,CBI COLONY 2ND MAIN ROAD AND ERIKARAI CROSS STREET IN DN 184 UT 41 ZONE 14",Own Sources,14,2015-16,2017-18 NP/2015-16/31744,Road Cut,Completed,NP-PERUNGUDI,184,918000,"RESTORATION OF CMWSSB ROAD CUT AT CBI COLONY 3RD CROSS , 4TH CROSS STREET,CBI COLONY 3RD MAIN ROAD AND ERIKARAI STREET IN DN 184 UT 41 ZONE 14",Own Sources,14,2015-16,2017-18 NP/2015-16/31745,Road Cut,Completed,NP-PERUNGUDI,184,882000,"RESTORATION OF CMWSSB ROAD CUT AT CBI COLONY 5TH CROSS , 6TH CROSS STREET,AND RAMAPPA NAGAR 2ND CROSS STREET IN DN 184 UT 41 ZONE 14",Own Sources,14,2015-16,2016-17 NP/2015-16/31827,Roads,Completed,NP-PERUNGUDI,188,985000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT DR. AMBETHKAR SALAI FROM MADIPAKKAM BUS TERMINUS TO MAHALAKSHMI NAGAR MAIN ROAD IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/31838,Roads,Completed,NP-PERUNGUDI,188,990000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT DR. AMBETHKAR SALAI FROM MAHALAKSHMI NAGAR MAIN ROAD TO LIC NAGAR 4TH MAIN ROAD IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/31900,Buildings,Completed,NP-PERUNGUDI,191,993000,Providing Front and side shed and other improvements to Lapersy Hospital at Madambakkam in Dn 191 Unit 43 Zone XIV,Own Sources,14,2015-16,2017-18 NP/2015-16/31901,Buildings,Completed,NP-PERUNGUDI,191,975000,Providing cycle shed and other improvements to Lapersy Hospital at Madambakkam in Dn 191 Unit 43 Zone XIV,Own Sources,14,2015-16,2017-18 NP/2015-16/31902,Buildings,Completed,NP-PERUNGUDI,191,949000,Construction of Compound wall to Lapersy Hospital at Madambakkam in Dn 191 Unit 43 Zone XIV,Own Sources,14,2015-16,2017-18 NP/2015-16/3191,Roads,Completed,NP-PERUNGUDI,169,2384000,"STRENGTHENING AND LAYING OF B T ROAD AT GANGAI ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3193,Roads,Completed,NP-PERUNGUDI,169,2500000,"STREBGTHENING AND LAYING OF BT ROAD AT YAMUNAI ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3194,Roads,Completed,NP-PERUNGUDI,169,3440000,"STRENGTHEBING AND LAYING OF BT ROAD AT VAIGAI ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3195,Roads,Completed,NP-PERUNGUDI,169,2616000,"STRENGTHENING AND LAYING OF BT ROAD AT KAVERI ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3196,Roads,Completed,NP-PERUNGUDI,169,2384000,"STRENGTHENING AND LAYING OF BT ROAD AT SRI RAMAR KOVIL ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3197,Roads,Completed,NP-PERUNGUDI,169,1570000,"STRENGTHEING AND LAYING OF BT ROAD AT CHOKKANATHAN ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3198,Roads,Completed,NP-PERUNGUDI,169,2616000,"STRENGTHEING AND LAYING OF BT ROAD AT SIVASUBRAMANIYAN PILLAYAR KOVIL ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3199,Roads,Completed,NP-PERUNGUDI,169,2272000,"STRENGTHEING AND LAYING OF BT ROAD AT SIVARAMAN ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3200,Roads,Completed,NP-PERUNGUDI,169,2396000,"STRENGTHEING AND LAYING OF BT ROAD AT RAMKUMAR ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3201,Roads,Completed,NP-PERUNGUDI,169,2396000,"STRENGTHEING AND LAYING OF BT ROAD AT VIDHYA SURABI SCHOOL ST IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/32098,Roads,Completed,NP-PERUNGUDI,186,755000,"Restoration of Metro water road cut at 3NOS of Kumaran nagar main road, Saravana nagar main road and Saravana nagar 1st street in Dn-186 Unit-41 Zone-14",Own Sources,14,2015-16,2017-18 NP/2015-16/32101,Roads,Completed,NP-PERUNGUDI,186,758000,"Restoration of Metro water road cut at 4NOS of Saravana nagar 2nd,3rd street,Saravana nagar Ramachandaran street and Thanikachalam street in Dn-186, Unit-41, Zone-14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32103,Roads,Completed,NP-PERUNGUDI,186,772000,"Restoration of Metro water road cut at 5NOS of Janagiraman nagar main road,1st,2nd,3rd and Panchyat 1st cross street in Dn-186,Unit-41,Zone-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32104,Roads,Completed,NP-PERUNGUDI,186,839000,"Restoration of Metro water road cut at 3NOS of Karunanithi street ,Panchyat 3rd cross street and Panchyat 3rd link road in Dn-186, Unit-41, Zone-14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32105,Roads,Completed,NP-PERUNGUDI,186,772000,"Restoration of Metro water road cut at 3NOS of Rajiv nagar 1st,2nd main road and Rajiv nagar 1st cross street in Dn-186, Unit-41, Zone-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32106,Roads,Completed,NP-PERUNGUDI,186,839000,"Restoration of Metro water road cut at 4NOS of Rajiv nagar 2nd,3rd,4th and 5th cross street in Dn-186,Unit-41, Zone-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32107,Roads,Completed,NP-PERUNGUDI,186,818000,"Restoration of Metro water road cut at 4NOS of Siva Vishnu street, Thamarai nagar, Venkateswara nagar main road and Ellim nagar 3rd cross street in Dn-186,Unit-41, Zone-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32108,Roads,Completed,NP-PERUNGUDI,186,772000,"Restoration of Metro water road cut at 5NOS of Ellim nagar poonga north street, poonga east street, poonga south street, poonga west street and vargees street in Dn-186,Unit-41,Zone-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32109,Roads,Completed,NP-PERUNGUDI,186,772000,"Restoration of Metro water road cut at 4NOS of selvaganapathi avenue 1st,2nd main road, selvaganapathi avenue 1st street and 2nd street in Dn-186,Unit-41, Zone-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32112,Roads,Completed,NP-PERUNGUDI,186,660000,"Restoration of Metro water road cut at 3NOS of Thirumalai nagar annex bharathi street and seevaram 2nd street in Dn-186, Unit-41, Zone-14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32305,Roads,Completed,NP-PERUNGUDI,188,992000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and Providing Thermo Plastic Compound marking Road pavement markers and signage boards at various Street in Dn 188, Unit-42, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/32309,Culvert,Completed,NP-PERUNGUDI,188,995000,"PROPOSED CONSTRUCTION OF R.C.C CULVERTS AT VARIOUS LOCATIONS IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32339,Roads,Completed,NP-PERUNGUDI,184,849000,RESTORATION OF ROAD CUT BY CMWSSB AT TELEPHONE NAGAR EXTN (KURUNJIINAGAR ANEXE) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2017-18 NP/2015-16/32486,Roads,Completed,NP-PERUNGUDI,169,381000,SUPPLY OF BOAT FOR HIRE BASIC WITH INCLUDING LABOUR AND DRIVERS SALARY FOR FLOOD WORK IN DIV 169 UNIT 42 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/32488,Roads,Completed,NP-PERUNGUDI,169,696000,SUPPLY OF TIPPER VECHILE FOR HIRE BASIC WITH INCLUDING FUEL CHARGES AND DRIVERS SALARY FOR FLOOD WORK IN DIV 169 UNIT 42 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/32557,Buildings,Completed,NP-PERUNGUDI,191,920000,"IMPROVEMENTS TO SIDE DRAIN AT GANDHI STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/32604,Roads,Completed,NP-PERUNGUDI,189,995000,"PROVIDING HERBAL PLANTS TO ROADSIDE PARK IN VELACHERY TAMBARAM MAIN ROAD IN FRONT OF APPASWAMY APARTMENTS IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32609,Roads,Completed,NP-PERUNGUDI,190,310000,"IMPROVEMENTS TO ROAD FOR GSB WORK AT PAZHANDIYAMMAN KOIL CROSS STREET,KRISHNA NAGAR CROSS STREET,VIVEKANANDA NAGAR 2ND MAIN ROAD -CROSS STREET IN DN-190,UNIT-43,ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/32612,Roads,Completed,NP-PERUNGUDI,189,990000,"ADDITIONAL IMPROVEMENTS TO ROADSIDE PARK IN VELACHERY TAMBARAM MAIN ROAD IN FRONT OF APPASWAMY APARTMENTS IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/32743,Roads,Completed,NP-PERUNGUDI,186,982000,"PROVIDING INTER LOCKING BLOCK APPROACH ROAD AT PERUNGUDI DUMPING GROUND TO PALLAVARAM RADIAL ROAD ( EAST SIDE) IN DN-186, U-41, Z-14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32748,Roads,Completed,NP-PERUNGUDI,186,982000,"PROVIDING INTER LOCKING BLOCK APPROACH ROAD AT PERUNGUDI DUMPING GROUND TO PALLAVARAM RADIAL ROAD ( WEST SIDE) IN DN-186, U-41, Z-14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32759/C,Roads,Completed,NP-PERUNGUDI,186,758000,"PROVIDING INTER LOCKING BLOCK APPROACH ROAD AT PERUNGUDI DUMPING GROUND TO PALLAVARAM RADIAL ROAD ( NORTH SIDE) IN DN-186, U-41, Z-14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32763,Roads,Completed,NP-PERUNGUDI,168,930000,"Restoration of road cut(CMWSSB) at Chozhan street ,Jhon kennedy street,kamaraj street ,voc street,Kuberamunuswamy street,usha nagar 2nd street,3rd street ,Natesan street,Rajagopalan street,Rajarathinam street,MGR 2nd cross street,.M.G.Nagar main road and union carbide colony in DN-168,UNIT-42,ZONE-14",Deposit Works,14,2015-16,2017-18 NP/2015-16/32779,Roads,Completed,NP-PERUNGUDI,189,994000,"REPAIRS TO DAMAGED TILES, PROVIDING PARK CHAIR ETC TO ROADSIDE PARK AT KAMAKOTTI NAGAR 1ST MAIN ROAD PARK IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32782,Roads,Completed,NP-PERUNGUDI,189,998000,"PROVIDING LIGHTING ARRANGEMENTS TO THE ROADSIDE PARK AT KAMAKOTTI NAGAR 1ST MAIN ROAD IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32786,Roads,Completed,NP-PERUNGUDI,189,997000,"PROVIDING GYM EQUIPMENT ETC TO THE ROADSIDE PARK AT KAMAKOTTI NAGAR 1ST MAIN ROAD IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32793,Roads,Completed,NP-PERUNGUDI,189,993000,"PROVIDING SAND FOR CHILDREN PLAY AREA ETC TO THE ROADSIDE PARK AT KAMAKOTTI NAGAR 1ST MAIN ROAD IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32796,Roads,Completed,NP-PERUNGUDI,189,990000,"PROVIDING LIGHTING ARRANGEMENTS AND IMPROVEMENT WORKS IN ROADSIDE PARK AT ASTALAKSHMI NAGAR IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32799,Roads,Completed,NP-PERUNGUDI,190,925000,"PROVIDING CHAIN LINK FENCING TO AMMAN TANK ON SOUTH AND WEST SIDE IN DIVISION 190, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32800,Roads,Completed,NP-PERUNGUDI,190,850000,"PROVIDING CHAIN LINK FENCING TO AMMAN TANK ON EAST SIDE IN DIVISION 190, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32801,Roads,Completed,NP-PERUNGUDI,190,790000,"PROVIDING CHAIN LINK FENCING TO AMMAN TANK ON NORTH SIDE IN DIVISION 190, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32803,Roads,Completed,NP-PERUNGUDI,190,947000,"PROVIDING PATHWAY TO AMMAN TANK ON NORTH SIDE AND WEST SIDE IN DIVISION 190, UNIT 43, ZONE 14.",Own Sources,14,2015-16,2017-18 NP/2015-16/32911,Buildings,Completed,NP-PERUNGUDI,185,996687,CONSTRUCTION OF ANGANVADI AT GOVENDAN NAGAR DN-185 UNIT-14 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/32924,Buildings,Completed,NP-PERUNGUDI,185,508235,"CONSTRUCTION OF TOILET , WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO ANGANVADI AT GOVENDAN NAGAR IN DN-185 UNIT-41 ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/33255,Roads,Completed,NP-PERUNGUDI,185,910000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT MGR SALAI 5TH, 6TH,7TH,8TH STREET IN DIVISION 185,UNIT41-ZONE14",Own Sources,14,2015-16,2017-18 NP/2015-16/33259,Road Cut,Completed,NP-PERUNGUDI,185,894000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT VGP 4TH MAIN ROAD TO BEACH NORTHERN ROAD IN DIVISION 185,UNIT41-ZONE14",Own Sources,14,2015-16,2017-18 NP/2015-16/33261,Road Cut,Completed,NP-PERUNGUDI,185,894000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT VGP 4TH LINK TO KALAIGNAR KARUNANIDHI SALAI IN DIVIS ION-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/33262,Road Cut,Completed,NP-PERUNGUDI,185,878000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT DOOR NO.121 TO KALAIGNAR KARUNANIDHI END ROAD AND M.G.R.SALAI IN DIVIS ION-185, UNIT-41, ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/33263,Road Cut,Completed,NP-PERUNGUDI,185,1645000,"RESTORATION OF METRO WATER ROAD CUTTING AT (10 ROADS) BHARATHIYAR NAGAR 2 ND STREET, BHARATHIYAR NAGAR 2 ND STREET, BHARATHIYAR NAGAR 3RD STREET, BHARATHIYAR NAGAR 4TH STREET, MA.PO.C STREET,MASUQUE STREET GANDHI NAGAR MAIN ROAD, GANDHI NAGAR 3RD STREET, GANDHI NAGAR 4TH STREET,GANDHI NAGAR 1ST STREET, MAHATHMA GANDHI STREET IN DN-185,U-42, Z-14",Own Sources,14,2015-16,2017-18 NP/2015-16/33840,Roads,Completed,NP-PERUNGUDI,188,930000,"SUPPLYING AND FIXING OF RCC HUME PIPES 450 MM DIA (1.5 FEET), 600 MM DIA (2 FEET) AND ATTENDING PATCH WORKS AT VARIOUS STREETS IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/34314,Roads,Completed,NP-PERUNGUDI,186,993000,ATTENDING WMM PATCH WORK AND PROVIDING CATCH PIT AT VARIOUS STTREET IN DN-186 UNIT-41 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3459,Roads,Completed,NP-PERUNGUDI,169,1221000,"STRENGTHENING AND LAYING OF BT ROAD AT JAMES STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3460,Roads,Completed,NP-PERUNGUDI,169,1458000,"STRENGTHENING AND LAYING OF BT ROAD AT JAMES CROSS STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3461,Roads,Completed,NP-PERUNGUDI,169,991000,STRENTHING AND LAYING OF BT ROAD AT VASUKIYAR STREET IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/34928,Road Cut,Completed,NP-PERUNGUDI,183,2313000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT KUPPAM BEACH ROAD, L.P NAGAR MAIN ROAD, ELLAYAMMA NAGAR CROSS STREET, SWAMINATHAN 6TH STREET, VENKATESHWARA 3RD CROSS STREET, VENKATESHWARA 2ND CROSS STREET, SWAMINATHAN 5TH STREET,SWAMINATHAN 2ND CROSS STREET, SWAMINATHAN2ND STREET, VEMBULIAMMAN STREET, IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2017-18 NP/2015-16/34930,Buildings,Completed,NP-PERUNGUDI,187,336000,"Repairs to Damaged drain due to Flood at Sabari Salai and improvements to Div office and Amma Unavagam in Dn -187,U-42, Z - 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/34931,Buildings,Completed,NP-PERUNGUDI,187,244000,"Repairs to Damaged Bin Platform due to flood at various streets and Improvements to Amma Unavagam in Dn -187, U -42, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/34948,Footpath,Completed,NP-PERUNGUDI,184,2707000,"RESTORATION OF METROWATER ROAD CUTTING AT C.B.I 2ND MAIN ROAD,C.B.I COLONY 1ST MAIN ROAD,LAKSHMAN SALAI, LAKSHMAN SALAI CROSS STREET,CBI COLONY MAIN ROAD ,ANNA SALAI MAIN ROAD FROM SCHOOL JUNCTION UP TO OMR,SASTRI STREET,AVVAI STREET,MANIMEGALAI STREET, BALAGANGATHARAR STREET, V O C STREET, GANDHI STREET , VIVEKANANTHAR STREETIN DN-184 UNIT-41 ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/34949,Footpath,Completed,NP-PERUNGUDI,184,1012000,"RESTORATION OF METROWATER ROAD CUTTING AT GOVINDASAMY NAGAR, BHARATHIYAR NAGAR,BHARATHIDASAN STREET,SEKIYAR STREET, KAMBAN STREET IN DN-184 UNIT-41 ZONE-14",Own Sources,14,2015-16,2017-18 NP/2015-16/3498,Roads,Completed,NP-PERUNGUDI,169,15731000,STRENTHENING AND LAYING OF BT ROAD AT RAMNAGAR SRINIVASAN SALAI IN DN-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3501,Roads,Completed,NP-PERUNGUDI,169,3440000,STRENTHENING AND LAYING OF BT ROAD AT RAMALINGAM NAGAR 1ST STREET IN DN-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/35021,Buildings,Completed,NP-PERUNGUDI,185,76000,REPAIRS AND IMPROVEMENTS TO PALAVAKKAM BEACH PC AND THIRUVALLUVAR NAGAR PC IN DIV 185 UNIT 41 ZONE 14,Own Sources,14,2015-16,2018-19 NP/2015-16/3520,Roads,Completed,NP-PERUNGUDI,169,3440000,STRENTHENING AND LAYING OF BT ROAD AT KALAIVANAR STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3521,Roads,Completed,NP-PERUNGUDI,169,3350000,STRENTHENING AND LAYING OF BT ROAD AT RAM NAGAR 1ST STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3522,Roads,Completed,NP-PERUNGUDI,169,3120000,"STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 33rd STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2015-16,2016-17 NP/2015-16/3524,Roads,Completed,NP-PERUNGUDI,169,3330000,STRENTHENING AND LAYING OF BT ROAD AT RAM NAGAR 2ND STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3525,Roads,Completed,NP-PERUNGUDI,169,3280000,STRENTHENING AND LAYING OF BT ROAD AT RAM NAGAR 3RD STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3527,Roads,Completed,NP-PERUNGUDI,169,6509000,STRENTHENING AND LAYING OF BT ROAD AT BAGEERATHI NAGAR SUNDARAJAN SALAI IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3528,Roads,Completed,NP-PERUNGUDI,169,687000,STRENTHENING AND LAYING OF BT ROAD AT BAGEERATHI NAGAR SUNDARAJAN SALAI CROSS IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3529,Roads,Completed,NP-PERUNGUDI,169,3915000,STRENTHENING AND LAYING OF BT ROAD AT VIVEKANANDAR STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3530,Roads,Completed,NP-PERUNGUDI,169,2085000,STRENTHENING AND LAYING OF BT ROAD AT ARIVOLI STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3531,Roads,Completed,NP-PERUNGUDI,169,4277000,STRENTHENING AND LAYING OF BT ROAD AT BRINDAVAN STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3532,Roads,Completed,NP-PERUNGUDI,169,1414000,STRENTHENING AND LAYING OF BT ROAD AT BRINDAVAN 1ST CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3533,Roads,Completed,NP-PERUNGUDI,169,1507000,STRENTHENING AND LAYING OF BT ROAD AT BRINDAVAN 2ND CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3534,Roads,Completed,NP-PERUNGUDI,169,1682000,STRENTHENING AND LAYING OF BT ROAD AT BRINDAVAN 3rd CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3535,Roads,Completed,NP-PERUNGUDI,169,1332099,STRENTHENING AND LAYING OF BT ROAD AT BRINDAVAN 4th CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3536,Roads,Completed,NP-PERUNGUDI,169,1621000,STRENTHENING AND LAYING OF BT ROAD AT BRINDAVAN 5th CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3537,Roads,Completed,NP-PERUNGUDI,169,4373000,STRENTHENING AND LAYING OF BT ROAD AT BRINDAVAN 6th CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3538,Roads,Completed,NP-PERUNGUDI,169,3729000,STRENTHENING AND LAYING OF BT ROAD AT MULLAI STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3539,Roads,Completed,NP-PERUNGUDI,169,582000,STRENTHENING AND LAYING OF BT ROAD AT RAMALINGA NAGAR MAIN ROAD LANE STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3540,Roads,Completed,NP-PERUNGUDI,169,1474000,STRENTHENING AND LAYING OF BT ROAD AT SANKARDASAR STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3541,Roads,Completed,NP-PERUNGUDI,169,833000,STRENTHENING AND LAYING OF BT ROAD AT SRINIVASA NAGAR 5TH CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3543,Roads,Completed,NP-PERUNGUDI,169,1228000,STRENTHENING AND LAYING OF BT ROAD AT SRINIVASA NAGAR 6TH CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3544,Roads,Completed,NP-PERUNGUDI,169,1228000,STRENTHENING AND LAYING OF BT ROAD AT RAM NAGAR SOUTH IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3549,Roads,Completed,NP-PERUNGUDI,169,1868000,STRENTHENING AND LAYING OF BT ROAD AT SANKARA NAGAR IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3553,Roads,Completed,NP-PERUNGUDI,169,1222000,STRENTHENING AND LAYING OF BT ROAD AT PANDIYAR STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3558,Roads,Completed,NP-PERUNGUDI,169,1576000,STRENTHENING AND LAYING OF BT ROAD AT T.R.BALU STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3559,Roads,Completed,NP-PERUNGUDI,169,1693000,STRENTHENING AND LAYING OF BT ROAD AT G K AVENUE STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3560,Roads,Completed,NP-PERUNGUDI,169,1133000,STRENTHENING AND LAYING OF BT ROAD AT THIRUVALLUVAR STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3561,Roads,Completed,NP-PERUNGUDI,169,591000,STRENTHENING AND LAYING OF BT ROAD AT THIRUVALLUVAR CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3562,Roads,Completed,NP-PERUNGUDI,169,1434874,STRENTHENING AND LAYING OF BT ROAD AT ANNAI THERESA NAGAR 14th St.Extn.STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3563,Roads,Completed,NP-PERUNGUDI,169,1459000,STRENTHENING AND LAYING OF BT ROAD AT RAM NAGAR NORTH EXTN (SADASIVAM NAGAR 1st LINK ROAD) IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3564,Roads,Completed,NP-PERUNGUDI,169,1084000,STRENTHENING AND LAYING OF BT ROAD AT NEELAMEGAN STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3565,Roads,Completed,NP-PERUNGUDI,169,3677000,STRENTHENING AND LAYING OF BT ROAD AT RAM NAGAR 7TH STREET RING ROAD IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3566,Roads,Completed,NP-PERUNGUDI,169,9783000,STRENTHENING AND LAYING OF BT ROAD AT JK SALAI IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2017-18 NP/2015-16/3567,Roads,Completed,NP-PERUNGUDI,169,1693000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 19TH STREET EXTN IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3568,Roads,Completed,NP-PERUNGUDI,169,1035000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 29TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3569,Roads,Completed,NP-PERUNGUDI,169,1576000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 30TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3570,Roads,Completed,NP-PERUNGUDI,169,759000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 31ST STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3571,Roads,Completed,NP-PERUNGUDI,169,993000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 32ND STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3572,Roads,Completed,NP-PERUNGUDI,169,1120000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 34TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3573,Roads,Completed,NP-PERUNGUDI,169,530000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 35TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3574,Roads,Completed,NP-PERUNGUDI,169,1080000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 36TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3575,Roads,Completed,NP-PERUNGUDI,169,876000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 37TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3576,Roads,Completed,NP-PERUNGUDI,169,1230000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 38TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3577,Roads,Completed,NP-PERUNGUDI,169,2600000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 39TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3578,Roads,Completed,NP-PERUNGUDI,169,1290000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 40TH STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3579,Roads,Completed,NP-PERUNGUDI,169,643000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 40TH CROSS STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3580,Roads,Completed,NP-PERUNGUDI,169,886000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR 41ST STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3581,Roads,Completed,NP-PERUNGUDI,169,1350000,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR EXTN 1ST STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3582,Roads,Completed,NP-PERUNGUDI,169,1303317,STRENTHENING AND LAYING OF BT ROAD AT BALAJI NAGAR EXTN 2ND STREET IN DIV-169 U-42 Z-14,Own Sources,14,2015-16,2016-17 NP/2015-16/3665,Roads,Completed,NP-PERUNGUDI,184,930000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT JN OF MGR SALAI AND AMMA UNNAVAGAM (REACH-II) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/3666,Roads,Completed,NP-PERUNGUDI,184,930000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT JN OF MGR SALAI AND AMMA UNNAVAGAM (REACH-1) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/3667,Roads,Completed,NP-PERUNGUDI,184,930000,FORMING AND LAYING OF BT ROAD BY PAVER FINISHER AT JN OF MGR SALAI AND AMMA UNNAVAGAM (REACH-3) IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/3937,Roads,Completed,NP-PERUNGUDI,187,997000,"PROVIDING STREET NAME BOARD AT NEW KUBERAN NAGAR MAIN ROAD, DR. TK MOORTHI STREET, DEIVANAI NAGAR 1ST STREET TO 4TH STREET AND VARIOUS OTHER STREET IN DIV 187 UNIT 42 ZONE 14",Own Sources,14,2015-16,2016-17 NP/2015-16/3938,Roads,Completed,NP-PERUNGUDI,187,999000,"PROVIDING STREET NAME BOARD AT PONNIAMMMAN KOVIL 1ST CROSS STREET , 2ND CROSS STREET, PONNIAMMAN KOVIL EAST AND WEST STREET , SANKARAN STREET ,GOPAL STREET AND VARIOUS OTHER STREET IN DIV 187 UNIT 42 ZONE 14",Own Sources,14,2015-16,2016-17 NP/2015-16/3939,Roads,Completed,NP-PERUNGUDI,187,998000,"PROVIDING STREET NAME BOARD AT KARTHIKEYAPURAM 1ST STREET TO 13TH STREET , VEERASAMY STREET, ETHIRAJULU STREET AND VARIOUS OTHER STREET IN DIV 187 UNIT 42 ZONE 14",Own Sources,14,2015-16,2016-17 NP/2015-16/3968,Buildings,Completed,NP-PERUNGUDI,168,1600000,"CONSTRUCTION OF RATION SHOP AT LAKSHMINAGAR 10TH STREET VACCANT LAND IN DN-168,UNIT-42,ZONE-14",MLACDS,14,2015-16,2016-17 NP/2015-16/4718,Buildings,Completed,NP-PERUNGUDI,186,2990000,"PROPOSED CONSTRUCTION OF 3 CLASS ROOM WITH STAIRE CASE IN PANCHAYAT UNION PRIMARY SCHOOL AT SCHOOL ROAD IN DN-186, UNIT-41, ZONE-14.( M.L.A. FUND)",MLACDS,14,2015-16,2016-17 NP/2015-16/5618,Roads,Completed,NP-PERUNGUDI,184,963000,PROVIDING SPEED BREAKERS AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGNAGE BOARD PAVEMENT MARKER AND ROAD STRUDS IN DN 184 UT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/5903,Buildings,Completed,NP-PERUNGUDI,191,2124000,"Proposed Construction of NNMP Shed at Veerathamman Koil Street in Dn-191,Unit 43,Zone 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/6278,Road Cut,Completed,NP-PERUNGUDI,184,2250000,RESTORATION OF ROAD CUT BY TANGEDCO AT ANNANEDUNSALAI( FROM MGR SALAI JUNCTION TO KAMARAJAR NAGAR MAIN ROAD) IN DN 184 UT 41 ZONE 14,Deposit Works,14,2015-16,2016-17 NP/2015-16/6517,Buildings,Completed,NP-PERUNGUDI,191,2424000,"Proposed Construction of Amma Unavagam at Ex Servicemen Colony 2nd Street in Dn191, Unit-43, Zone-14",Own Sources,14,2015-16,2016-17 NP/2015-16/6735,Culvert,Completed,NP-PERUNGUDI,190,975000,"Construction of R.C.C Culvert at vivekandhar nagar,Sri nagar & sai ganesh nagar area in Dn -190, Unit-43, Zone-14",Own Sources,14,2015-16,2017-18 NP/2015-16/6787,Parks,Completed,NP-PERUNGUDI,189,950000,"Repairs and Improvements to Astalakshmi nagar park in dn 189,unit-43,zone-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/7901,Buildings,Completed,NP-PERUNGUDI,191,782000,Improvements to Amma Unavagam at Rice Mill Road in Dn-191 :Unit-43 :Zone-14,Own Sources,14,2015-16,2017-18 NP/2015-16/7938,Playfields,Completed,NP-PERUNGUDI,190,500000,Proposed Chain Link Fencing work around the Chitherri at Kovalan nagar 1st main road in Dn-190; Unit-43 : Zone-14,Own Sources,14,2015-16,2017-18 NP/2015-16/7946,Buildings,Completed,NP-PERUNGUDI,191,787000,Construction of Raising Compound wall at Village Buriyal Ground in Dn-191: Unit-43: zone-14,Own Sources,14,2015-16,2017-18 NP/2015-16/7980,Buildings,Completed,NP-PERUNGUDI,184,998000,"CONSTRUCTION OF COMPOUND WALL AT SCHOOL ROAD IN HINDU BURIAL GROUND ,INBETWEEN SCHOOL GROUND(WEST SIDE) IN DN 184 UT 41 ZONE 14",Own Sources,14,2015-16,2016-17 NP/2015-16/8357,Roads,Completed,NP-PERUNGUDI,190,6750000,"Strengthening and laying of B.T Road at Bhavaniyamman Koil Street in Dn -190, Unit- 43, Zone- XIV",Own Sources,14,2015-16,2016-17 NP/2015-16/8560,Buildings,Completed,NP-PERUNGUDI,186,971000,CONSTRUCTION OF COMPOUND WALL AT PANCHAYAT ROAD JUCTION OF PANCHAYAT 3RD CROSS STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/8562,Buildings,Completed,NP-PERUNGUDI,186,776000,REPAIRS AND IMPROVEMENTS TO ANGANWADI AT PANCHAYAT OFFICE ROAD INSIDE OF DIV 186 UNIT 41 ZONE 14,Own Sources,14,2015-16,2016-17 NP/2015-16/8565,Buildings,Completed,NP-PERUNGUDI,184,998000,"DEMOLITION AND CONSTRUCTION OF ANGANWADI BUILDING AT ANNANEDUNSALAI (NEAR JUNCTION OF KARPAGAVINAYAGAR KOIL STREET)IN DIV 184 UNIT 41 ,ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/8566,Buildings,Completed,NP-PERUNGUDI,184,997000,"PROVIDING WATER SUPPLY,DRAINAGE ,ELECTRICAL ARRANGEMENTS ,FABRICATION AND OTHERS WORKS FOR ANGANWADI BUILDING AT ANNANEDUNSALAI (NEAR JUNCTION OF KARPAGAVINAGAR KOIL STREET)IN DIV 184,UNIT 41,ZONE 14.",Own Sources,14,2015-16,2016-17 NP/2015-16/8915,Buildings,Completed,NP-PERUNGUDI,186,995000,"CONSTRUCTION OF COMPOUND WALL,FOOT PATH AND I IN BURIAL GROUND AT INDUSTRIAL ESTATE SEEVARAM IN DN-186, U-41, Z-14.",Own Sources,14,2015-16,2016-17 NP/2015-16/8990,Buildings,Completed,NP-PERUNGUDI,186,985000,CONSTRUCTION OF COMPOUND WALL AND FILLING GOOD EARTH IN BURIAL GROUND (NORTH SIDE) AT INDUSTRIAL ESTATE 2ND STREET IN DN-186 UNIT-41 ZONE-14,Own Sources,14,2015-16,2016-17 NP/2015-16/9106,Roads,Completed,NP-PERUNGUDI,190,974000,"Strengthening the Cement Concrete road at Immanuvel 2nd Street and Gandhi cross st in Dn-190, U-43,Z-14",Own Sources,14,2015-16,2016-17 NP/2015-16/9697,Roads,Completed,NP-PERUNGUDI,186,851000,"RESTORATION OF CMWSSB ROAD CUT AT SENTHIL NAGAR 1ST TO 5TH CROSS STREET IN DIVISION 186,UNIT41-ZONE14",Own Sources,14,2015-16,2017-18 NP/2015-16/9700,Roads,Completed,NP-PERUNGUDI,183,806000,"RESTORATION OF METRO WATER ROAD CUTTING AT KAVERI BEACH ROAD 5TH STREET, MUTHALAMMAN KOIL STREET IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/9704,Roads,Completed,NP-PERUNGUDI,183,886000,":RESTORATION OF METRO WATER ROAD CUTTING AT KUPPAM BEACH ROAD, MUTHALAMMAN KOIL 1ST STREET, MUTHALAMMAN KOIL 3RD STREET IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/9707,Roads,Completed,NP-PERUNGUDI,183,861000,":RESTORATION OF METRO WATER ROAD CUTTING AT MUTHALAMMAN KOIL 4TH STREET, MUTHALAMMAN KOIL 5TH STREET, MUTHALAMMAN KOIL 6TH STREET, PILLAIYAR KOIL 1ST STREET, PILLAIYAR KOIL 7TH STREET, JAGANATHAN STREET, MUTHALAMMAN KOIL 2ND STREET IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NP/2015-16/9725,Roads,Completed,NP-PERUNGUDI,185,790000,"RESTORATION OF METRO WATER ROAD (CMWSSB) CUTTING AT ESTATE ROAD, ESTATE CROSS STREET IN DIVISION 185,UNIT41-ZONE14",Own Sources,14,2015-16,2016-17 NQ/2015-16/0766,Buildings,Completed,NQ-SHOZHINGANALLUR,192,4070000,"Proposed Construction of Compound Wall at Senkeni Amman Koil Tank , Foot Path & Retaining Wall in DN-192, UNIT-44,ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/0817,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,810000,"DESILTING OF SWD AT VARIOUS STREETS IN KANNAGI NAGAR IN DN-195,U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/0971,Roads,Completed,NQ-SHOZHINGANALLUR,193,546000,"DESILDING OF THE EXISTING ROAD SIDE DRAIN AT VENKATESHWARA NAGAR 1 TO 7 STREETS, SUBURAYALU NAGAR AND EXISTING STORM WATER DRAIN AT MURUGESAN STREETS IN WARD-193 , UNIT-45 , ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/10321,Buildings,Completed,NQ-SHOZHINGANALLUR,195,750000,"IMPROVEMENTS TO PARK AT KANNAGI NAGAR MAIN ROAD IN DIVISION 195,UNIT45,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/11107,Buildings,Completed,NQ-SHOZHINGANALLUR,200,995000,"IMPROVEMENTS TO BURIAL GROUND BY CARE TAKER ROOM AT PONDICHERRY PATTAI SALAI IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/11229,Footpath,Completed,NQ-SHOZHINGANALLUR,200,495000,"FORMING OF FOOTPATH AT PAZHATHOTTA SALAI IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/11404,Roads,Completed,NQ-SHOZHINGANALLUR,194,998000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT KUMARAN KUDIL MAIN ROAD, RAJ NAGAR IST MAIN ROAD, 2ND MAIN ROAD, 3RD MAIN ROAD, ESWARAN KOIL MAIN ROAD, RAJU GARDEN IST MAIN ROAD, SECRETARIAT COLONY IST MAIN ROAD, CHANDRASEKAR AVENUE IST MAIN ROAD, 2ND MAIN ROAD, 3RD MAIN ROAD, NANTHINI HOSPITAL ROAD, RAJ NAGAR IST, 2ND, 6TH, 8TH, 9TH AND VARIOUS STREET IN DN-194, U-45, Z-15 (UNDER WARD COUNCILOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/11772,Roads,Completed,NQ-SHOZHINGANALLUR,196,860000,"IMPROVEMENTS TO ROADS BY USING GSBAND DUSTAT SHALIMAR GARDEN,CLASSIC ENCLAVE ,PONURANGAM STREET IN DIVISION 196,UNIT44,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/12089,Roads,Completed,NQ-SHOZHINGANALLUR,194,999000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT PILLAIYAR KOIL STREET, K.E.P.AVENUE, BHARATHIYAR NAGAR 4TH STREET, 5TH, 6TH STREET, MOUNTBATTEN ROAD, VPG AVENUE 4TH, 5TH, 6TH, 7TH CROSS STREET, ROYAL AVENUE MAIN ROAD, ROYAL AVENUE 2ND STREET, 3RD STREET, 4TH STREET, BV AVENUE MAIN ROAD, SECRETARIAT COLONY 2ND, 3RD, 4TH, 5TH MAIN ROAD AND VARIOUS STREET IN DN-194, U-45, Z-15 (UNDER WARD COUNCILOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/12093,Roads,Completed,NQ-SHOZHINGANALLUR,194,999000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT MGR STREET, AZHIKANDESWARAR NAGAR MAIN ROAD, IST STREET, 2ND STREET, BALAJI NAGAR 1ST, 2ND, 3RD, 4TH STREET, BHARATHIYAR IST, 2ND, 3RD STREET, KRISHNA NAGAR IST, 2ND, 3RD STREET, ESWARAN KOIL IST STREET, KUMARAN KUDIL ANNEXE IST MAIN ROAD, 2ND MAIN ROAD AND VARIOUS STREETS IN DN-194, U-45, Z-15 (UNDER WARD COUNCILLOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/12340,Roads,Completed,NQ-SHOZHINGANALLUR,199,990000,"PROVIDING AND FIXING STREET FURNITURE AT VGP 1ST,2ND &3RD MAIN ROAD,NILA STREET,KOVALAN STREET,TAMARAI STREET,DR.SIVARAMAN SALAI.VAIGAI STREET,KAVERI STREET,THILAGAR STREET,VALLUVAR STREET AND LENIN STREET USING COUNSILLOR FUND IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/12341,Roads,Completed,NQ-SHOZHINGANALLUR,199,990000,"PROVIDING AND FIXING STREET FURNITURE AT KANNADASAN STREET,NEELAKADAL STREET,MAHAVEERAR STREET,BAYVIEW STREET,MADURASHMI STREET,MAZHAVARAYAR STREET,THEERAN CHINNAMALAI STREET,RAJIV GANDHI STREET,ANNAI TERASA STREET,JEEVE STREET,VASUKI STREET,AMURTHA STREET,ROJA STREET,MULLAI STREET,MALLAIGAI STREET AND SHESADRI STREET USING COUNSILLOR FUND IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/12397,Roads,Completed,NQ-SHOZHINGANALLUR,196,808000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT GANGAIAMMAN KOIL STREET,DR AMBEDKAR STREET,TEACHERS COLONY AND OTHER VARIOUS STREET IN DN-196 U-44 Z-15 (COUNCILOR FUND)",Own Sources,15,2015-16,2016-17 NQ/2015-16/12508,Roads,Completed,NQ-SHOZHINGANALLUR,196,985000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT BETHAL NAGAR,HANUMAN COLONY,RAJAN NAGAR AND OTHER VARIOUS STREET IN DN-196 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/12513,Roads,Completed,NQ-SHOZHINGANALLUR,196,985000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT BAYWATCH FORM,PANDIYAN SALAI,BISMIILAH NAGAR AND OTHER VARIOUS STREET IN DN-196 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/12518,Roads,Completed,NQ-SHOZHINGANALLUR,196,985000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT POTHIGAI STREET,SHALIMAR GARDEN,VOC STREEET AND OTHER VARIOUS STREET IN DN-196 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/12833,Roads,Completed,NQ-SHOZHINGANALLUR,194,950000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT BHARATHI NAGAR IST, 2ND, 3RD, 4TH STREET, KAMARAJAR STREET, VPG AVENUE, IST MAIN ROAD, SRINIVASA NAGAR, C.S.NAGAR, SECRETARIAT COLONY IST, 2ND CIRCLE ROAD, AMBAL AVENUE IST TO 3RD ST., KUMARAGURU AVENUE IST TO 5TH STREET, KAMARAJ STREET AND VARIOUS STREETS IN DN-194 U-45, Z-15 (UNDER WARD COUNCILOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/12837,Roads,Completed,NQ-SHOZHINGANALLUR,194,950000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE ARROWS AT GUINDY ENGINEERING COLLEGE IST MAIN ROAD, IST TO 4TH LANE, ESWARAN KOIL 2ND STREET, RAJU GARDEN 2ND MAIN ROAD, DEVARAJ AVENUE IST TO 3RD CROSS STREET, DEVARAJ NAGAR MAIN ROAD, MOUNTBATTEN IST TO 4TH CROSS STREET, CHANDRASEKAR NAGAR MAIN ROAD, KUMARANKUDIL 5TH CROSS STREET, RAJU NAGAR IST, 2ND STREET AND VARIOUS STREETS IN DN-194, U-45, Z-15 (UNDER WARD COUNCILOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/13275,Roads,Completed,NQ-SHOZHINGANALLUR,200,68000,"PATCH WORK FOR POUND STREET USING CONCRETE IN DN 200 , U45, Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/13380,Roads,Completed,NQ-SHOZHINGANALLUR,194,990000,"Providing and Laying of RCC Hume Pipe at Various Street (VPG Avenue, Bharathiyar Nagar Main Road Etc..,) in Dn-194 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/13685,Buildings,Completed,NQ-SHOZHINGANALLUR,196,955000,"CONSTRUCTIONS OF TOILET AND IMPROVEMENTS TO PLAY APPARATUS AND RAIN WATER HARVESTING AT VGP PARK, INJAMBAKKAM ,DIV 196,UNIT44,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/13873,Buildings,Completed,NQ-SHOZHINGANALLUR,197,3720000,Construction of Compound Wall for Muslim Burrial Ground at Kuppusamy Street Krapakkam in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2017-18 NQ/2015-16/13875,Buildings,Completed,NQ-SHOZHINGANALLUR,197,3720000,Construction of Compound Wall for Hindu Burrial Ground (1) at Kuppusamy Street Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2017-18 NQ/2015-16/14206,Buildings,Completed,NQ-SHOZHINGANALLUR,200,825000,"ADDITIONAL IMPROVEMENTS WORKS TO AMMAUNAVAGAM BY PROVIDING FURINTURE GAS CONECTION AND ,ELECTRICAL FITTING WORKS ETC AT 66TH STREET (TNSCB) IN DN 200 UNIT 45 ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14321,Roads,Completed,NQ-SHOZHINGANALLUR,194,950000,Raising the Road With WMM and Dust at Chandrasekaran Avenue 5th Street in Dn-194 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/14323,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,990000,"Providing Side Drain at Kumaran Kudil Annexe Main Road in Dn-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14324,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,990000,"Providing Side Drain at Kumaran Kudil Annexe 1st Street in Dn-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14327,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,990000,"Providing Side Drain at Kumaran Kudil Annexe 3rd Street, Kumaran Kudil Annexe 4th Street, Kumaran Kudil Annexe 5th Street in Dn-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14328,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,990000,"Providing Side Drain at Kumaran Kudil 6th Cross Street, Kumaran Kudil Annexe 6th Street in Dn-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14358,Parks,Completed,NQ-SHOZHINGANALLUR,193,267000,"OUTSOURCING MAINTENANCE OF PARK AT COSTOMS COLONY IN DIV-193,U44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14359,Roads,Completed,NQ-SHOZHINGANALLUR,193,714000,"RAISING THE EXISTING ROAD AT THIRUVALLUVAR NAGAR 5TH STREET IN DN-193,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14361,Buildings,Completed,NQ-SHOZHINGANALLUR,200,980000,"IMPROVEMENTS TO BURIAL GROUND BY CARE TAKER ROOM AT VEERAVANJINATHAN SALAI IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14440,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,990000,"Providing Side Drain at Alagappa Nagar 1st Cross Street, Alagappa Nagar 2nd Cross Street, Alagappa Nagar 3rd Cross Street in Dn-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14441,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,990000,"Providing Side Drain at Alagappa Nagar 4th Cross Street and Guindy Engineering College Road in Dn-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14650,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,999000,"Providing Side Drain at Boopathy Nagar 1st, 2nd, 3rd and 4th Street in DN - 197, U - 45, Z - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14652,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,999000,"Providing Side Drain at Senkeniamman Koil Street & Village High Road in DN - 197, U - 45, Z - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14654,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,999000,"Providing Side Drain at School Road in DN - 197, U - 45, Z - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/1476,Buildings,Completed,NQ-SHOZHINGANALLUR,195,122000,"Providing Inspection Chambers at Various Places at Kannagi Nagar in Dn:195, U:45, Z:XV",Own Sources,15,2015-16,2016-17 NQ/2015-16/1477,Playfields,Completed,NQ-SHOZHINGANALLUR,195,187000,"Improvements to Kannagi Nagar Park in 10th Cross Street by providing Stainless Steel Play Apparatus etc in Dn:195, U:45, Z:XV",Own Sources,15,2015-16,2016-17 NQ/2015-16/14771,Roads,Completed,NQ-SHOZHINGANALLUR,196,770000,"WIDENING THE EXISTING ROAD AT NANJUNDARAO SALAI CH(300-600) IN DN-196 UNIT-44,ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/14779,Roads,Completed,NQ-SHOZHINGANALLUR,196,988800,"IMPROVEMENTS TO ROADS BY USING GSB,WMM AT AAVIN STREET,THANTHI PERIYAR STREET,CHINNADI KUUPAM ROAD,",Own Sources,15,2015-16,2016-17 NQ/2015-16/15356,Roads,Completed,NQ-SHOZHINGANALLUR,193,998000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE AND DOUBLE ARROWS AT KARPAGA VINAYAGAR NAGAR 2ND STREET, 1ST CROSS STREET, KARPAGA VINAYAGAR 12TH CROSS ST TO 29 CROSS STREET AND VARIOUS STREET IN DN-193, U-45, Z-15 (UNDER WARD COUCILOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/15359,Roads,Completed,NQ-SHOZHINGANALLUR,193,998000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE AND DOUBLE ARROWS AT MAHATMA GANDHI NAGAR IST CROSS ROAD, 2ND CROSS ROAD, 2ND MAIN ROAD, 3RD MAIN ROAD, 4TH MAIN ROAD, 3RD CROSS STREET, 4TH CROSS STREET, M.C.N.NAGAR 5TH STREET, 6TH STREET, 7TH STREET, KARPAGA VINAYAGAR NAGAR 30, 31, 32 CROSS STREET AND VARIOUS STREET IN DN-193, U-45, Z-15 (UNDER WARD COUCILOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/15364,Roads,Completed,NQ-SHOZHINGANALLUR,193,998000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE AND DOUBLE ARROWS AT SAI NAGAR MAIN ROAD, SAI NAGAR 1ST, 2ND, 3RD CROSS STREET, SAI BABA NAGAR, RE NAGAR, SHANTHI NIKETHAN COLONY MAIN ROAD, THIRUVALLUVAR NAGAR 5TH CROSS, GANESH NAGAR MAIN ROAD, GANESH NAGAR 7TH, 8TH, 9TH AND 10TH CROSS STREET, VENKATESWARA NAGAR COMPANY STREET, VENKATESWARA NAGAR 11TH, 12TH STREET AND VARIOUS STREET IN DN-193, U-45, Z-15 (UNDER WARD COUCILOR FUND 2015-16)",Own Sources,15,2015-16,2016-17 NQ/2015-16/15489,Buildings,Completed,NQ-SHOZHINGANALLUR,199,357000,"IMPROVEMENT TO AMMA UNAVAGAM, VVVS SALAI AT NAINAR KUPPAM IN DN199 UNIT45 ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15548,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,580000,"CONSTRUCTION OF SIDE DRAIN AT SRI KARPAGA VINAYAGAR 2ND CROSS STREET IN DN-193, U- 45 ,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15550,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,660000,"CONSTRUCTION OF SIDE DRAIN AT SRI KARPAGA VINAYAGAR 5TH CROSS STREET IN DN-193, U- 45 ,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15552,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,510000,"CONSTRUCTION OF SIDE DRAIN AT SRI KARPAGA VINAYAGAR 4TH CROSS STREET IN DN-193, U- 45 ,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15571,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,620000,"CONSTRUCTION OF SIDE DRAIN AT SRI KARPAGA VINAYAGAR 33RD CROSS STREET IN DN-193, U- 45 ,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15577,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,990000,"CONSTRUCTION OF SIDE DRAIN AT MRG NAGAR IN DIVISION -195, UNIT - 45, ZONE - 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/15597,Parks,Completed,NQ-SHOZHINGANALLUR,193,137000,"OUTSOURCING MAINTENANCE OF PARK AT R.E NAGAR IN DIV-193,U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15659,Buildings,Completed,NQ-SHOZHINGANALLUR,193,990000,"IMPROVEMENTS TO BURIAL GROUND( CONSTRUCTION OF COMPOUND WALL, GRILL GATE AND PROVIDING WATER SUPPLY ETC) AT SUBRAYAN NAGAR 4TH STREET IN DN-193,UNIT-45,ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/15695,Roads,Completed,NQ-SHOZHINGANALLUR,194,995000,"Raising the Road with GSB and Dust at Raju Nagar 2nd Cross street, Secretariat colony south 2nd cross street, Secretariat colony 5th cross street,Secretariat colony 4th circle road,Secretariat colony 2nd lane south,Secretariat colony south 1st cross street,sulaima nagar kumaraguru avenue,raju garden 1st cross street, mount batten 1st cross sreet, JK Avenue in Dn-194 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15700,Roads,Completed,NQ-SHOZHINGANALLUR,194,998000,"Attending CC Patch work at Manthoppu pillayar koil street,Sulaima Nagar 1st cross street and Ariyathamman koil street in Dn-194 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15701,Roads,Completed,NQ-SHOZHINGANALLUR,194,998000,"Attending CC Patch work at Anna Street, Kumaran Kudil 4th Cross Street, Pillayar Koil 1st cross Street, Pillayar Koil Street, Sulaima Nagar 3rd Cross Lane, Krishna Nagar 3rd Cross street in Dn-194 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15824,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,990000,"CONSTRUCTION OF SIDE DRAIN AT BHARATHIYAR NAGAR 1ST STREET IN DIVISION -195, UNIT - 45, ZONE - 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/15828,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,990000,"CONSTRUCTION OF SIDE DRAIN AT VOC STREET IN DIVISION -195, UNIT - 45, ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/15830,Roads,Completed,NQ-SHOZHINGANALLUR,195,174000,"PROVIDING SOURCE SEGERATION AWARNESS NAME BOARD AT VARIOUS STREET IN DN-195,UNIT -45 , ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/15880,Roads,Completed,NQ-SHOZHINGANALLUR,194,999000,"PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT KUMARAN KUDIL, SECRETARIAT COLONY AND VARIOUS LOCATIONS IN 194 UNIT 45 ZONE15",Own Sources,15,2015-16,2017-18 NQ/2015-16/15987,Roads,Completed,NQ-SHOZHINGANALLUR,198,959000,"Improvement to Road at at Sea Cliff Main Road, 1st Drive, IInd Drive, IIIrd Drive and IVth Drive in Div-198, Unit - 45, Zone - 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/1616,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1600000,"Construction of Public Distribution shop (Ration shop) at Aringar Anna Street, Karapakkam in Dn.197, U-45, Z/15",MLACDS,15,2015-16,2016-17 NQ/2015-16/16386,Parks,Completed,NQ-SHOZHINGANALLUR,193,178000,"OUTSOURCING MAINTENANCE OF PARK AT SAI NAGAR IN DN-193,U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/16739,Roads,Completed,NQ-SHOZHINGANALLUR,195,960000,"FORMING AND LAYING C.C ROAD AT NEHRU NAGAR 3RD MAIN ROAD IN DIV -195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/16741,Roads,Completed,NQ-SHOZHINGANALLUR,193,999000,"FORMING AND RAISING THE EXISTING ROAD WITH GSB AND WMM AT SAI NAGAR 10TH AND 1ST CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/16747,Roads,Completed,NQ-SHOZHINGANALLUR,193,999000,"FORMING AND RAISING THE EXISTING ROAD AT KARPAGA VINAYAGA NAGAR 25TH STREET AND MAHATMAGANTHI NAGAR 12 CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/16818,Roads,Completed,NQ-SHOZHINGANALLUR,200,998000,"WIDENING OF ROAD USING RMC15 CONCRETE AT TNSCB 49th AND58th CROSS STREET & 10th AVENUE IN DN 200,U45,Z15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/16819,Roads,Completed,NQ-SHOZHINGANALLUR,200,998000,"WIDENING OF ROAD USING RMC15 CONCRETE AT TNSCB 65-68th CROSS STREET IN DN 200,U45,Z15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/16945,Buildings,Completed,NQ-SHOZHINGANALLUR,194,130000,"PROVIDING WATER PIPE LINE FOR RO AND FURNITURE TO THE DIVISION OFFICE IN DN-194, Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/16980,Buildings,Completed,NQ-SHOZHINGANALLUR,197,999000,Providing Revetment in All round of Pond at Gangaiamman koil Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/17122,Parks,Completed,NQ-SHOZHINGANALLUR,196,826000,"IMPROVEMENTS TO BURIAL GROUND AT HARICHANDRA MAIN ROAD IN DIVISION 196,UNIT-44,ZONE 15",Own Sources,15,2015-16,2017-18 NQ/2015-16/17287,Roads,Completed,NQ-SHOZHINGANALLUR,198,858000,"Providing Side Barms at Seacliff Main Road ( VGP layout) in Dn-198, Unit-45, Zone-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/17295,Roads,Completed,NQ-SHOZHINGANALLUR,198,792000,"Providing Side Barms at 1st Drive, 2nd Drive, 3rd Drive and 4th Drive ( VGP layout) in Dn-198, Unit-45, Zone-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/17513,Buildings,Completed,NQ-SHOZHINGANALLUR,197,698000,"Improvements to Staircase, Zonal officer room and Computer room in Zonal office building at Rajiv gandhi salai in Dn.197, Unit-45, Zone-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/17514,Buildings,Completed,NQ-SHOZHINGANALLUR,197,995000,"Construction of A.E.Electrical office and store room at Rajiv gandhi salai in Dn.197, Unit-45, Zone-15",Own Sources,15,2015-16,2017-18 NQ/2015-16/17974,Roads,Completed,NQ-SHOZHINGANALLUR,195,998000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE AND DOUBLE ARROWS AT NEHRU NAGAR 1ST MAIN ROAD TO NEHRU NAGAR 14TH CROSS STREET,AND OTHER VARIOUS STREET IN DN-195, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/17986,Roads,Completed,NQ-SHOZHINGANALLUR,195,980000,"PROVIDING GSB AND QUARRY DUST AT 2ND CROSS STREET IN EZIHIL NAGAR,DIVISION 195,UNIT45,ZONE 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/17987,Roads,Completed,NQ-SHOZHINGANALLUR,195,830000,"PROVIDING GSB AND QUARRY DUST AT 4TH CROSS STREET IN EZIHIL NAGAR,DIVISION 195,UNIT45,ZONE 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/17988,Buildings,Completed,NQ-SHOZHINGANALLUR,195,997000,"IMPROVEMETS TO THE PARK (WATER LINE ARRANGEMENTS AND RAIN WATER HARVESTING) AT ANNAI INDRA NAGAR IN DIVISION 195,UNIT 45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18156,Roads,Completed,NQ-SHOZHINGANALLUR,195,998000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE AND DOUBLE ARROWS AT KANNAGI NAGAR 10TH MAIN ROAD TO KANNAGI NAGAR 68TH CROSS STREET,AND OTHER VARIOUS STREET IN DN-195, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18171,Roads,Completed,NQ-SHOZHINGANALLUR,195,998000,"PROVIDING AND FIXING OF STREET FURNITURE SINGLE AND DOUBLE ARROWS AT KANNAGI NAGAR 1ST MAIN ROAD TO KANNAGI NAGAR 9TH MAIN ROAD,AND OTHER VARIOUS STREET IN DN-195, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18178,Buildings,Completed,NQ-SHOZHINGANALLUR,195,985000,"IMPROVEMENTS TO PARK (WATER ARRANGEMENTS AND PATH WAY) AT KANNAGI NAGAR 9TH MAIN ROAD IN DIVISION 195 UNIT 45,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18192,Roads,Completed,NQ-SHOZHINGANALLUR,199,980000,"ROADCUT RESTORATION BY USING CONCRETE FOR GANGAI AMMAN KOIL WEST AND EAST STREET IN DN 199, U44,Z15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/18320,Roads,Completed,NQ-SHOZHINGANALLUR,195,990000,Providing and Laying GSB and WMM at Thiruvalluvar Street in Dn-195 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/18323,Roads,Completed,NQ-SHOZHINGANALLUR,197,991000,Providing and Laying WMM at Village High Road (From KK Salai to MGR Street) in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/18324,Roads,Completed,NQ-SHOZHINGANALLUR,197,991000,Providing and Laying WMM at MGR Street and Approach of Village High Road in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/18326,Roads,Completed,NQ-SHOZHINGANALLUR,197,990000,Providing and Laying GSB and WMM at Nethaj Street in Dn-195 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/18541,Buildings,Completed,NQ-SHOZHINGANALLUR,192,989000,"CONSTRUCTION OF SIDE DRAIN AT RAJENDRA NAGAR 9TH & 10TH CROSS STREET AND 7TH CROSS STREET AT DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18542,Buildings,Completed,NQ-SHOZHINGANALLUR,192,989000,"CONSTRUCTION OF SIDE DRAIN AT RAJENDRA NAGAR 8TH CROSS STREET AT DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18543,Buildings,Completed,NQ-SHOZHINGANALLUR,192,989000,"CONSTRUCTION OF SIDE DRAIN AT RAJENDRA NAGAR 6TH CROSS STREET AT DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18646,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,997000,"Construction of Side Drain at Thiruvalluvar street ,MRG Nagar and Saraswathi Nagar in Dn:195, U:45, Z:15",Own Sources,15,2015-16,2017-18 NQ/2015-16/18650,Buildings,Completed,NQ-SHOZHINGANALLUR,195,997000,"Construction of Compound Wall in Front of AMMA UNAVAGAM in 2nd Main Road in Dn:195, U:45, Z:15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18936,Roads,Completed,NQ-SHOZHINGANALLUR,195,990000,"CONSTRUCTION OF SIDE DRAIN AT KANNAGI NAGAR 9TH MAIN ROAD DOOR NO-9645 TO DOOR NO-991 IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18941,Roads,Completed,NQ-SHOZHINGANALLUR,195,990000,"CONSTRUCTION OF SIDE DRAIN AT KANNAGI NAGAR 9TH MAIN ROAD DOOR NO-991 TO DOOR NO-1041 IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/18944,Roads,Completed,NQ-SHOZHINGANALLUR,196,820000,ATTENDING PATCH WORK WITH GSB AND WMM AT RAJAN NAGAR 2ND STREET IN DN-196 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/18949,Roads,Completed,NQ-SHOZHINGANALLUR,197,726000,"Providing and Laying GSB and Dust at Kanthasamy Street , Arunachalam Street, Pandiyan Street, Murugesan Street, Narayanasamy Street, Madurai Street,Velu Street and Nadu 1st street in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19003,Roads,Completed,NQ-SHOZHINGANALLUR,193,996000,"Providing and laying road with GSB & WMM at Harihanth link road, Kulakarai 3rd street, Subburaya nagar 4th street in Dn.193, Zone 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19006,Roads,Completed,NQ-SHOZHINGANALLUR,193,985000,"Providing Hume pipe for disposal of rain water at Karpaga vinayagar nagar 3rd street, Customs colony and various street in D.193, Zone 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19070,Parks,Completed,NQ-SHOZHINGANALLUR,193,998000,"Improvement to park with SS play aparatus and watch man shed at Sai Nagar in Dn.193, Zone 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19082,Parks,Completed,NQ-SHOZHINGANALLUR,194,877000,"Improvement park with SS play aparatus, Greenary at PTC quarters in Dn.194, Zone 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19273,Roads,Completed,NQ-SHOZHINGANALLUR,198,890000,Attending Patch Work at Village High Road in Dn-198 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/19274,Roads,Completed,NQ-SHOZHINGANALLUR,198,900000,"Attending Patch Work at Ponniamman kovil 5th cross street, D. Balachandar naikar street,Village High Road 33rd cross street,Village High Road 34th cross street,Village High Road 37th cross street in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19275,Roads,Completed,NQ-SHOZHINGANALLUR,198,980000,"Attending Patch Work at Village High Road 38th cross st(arumugam st), S.R Kanniappan naikar street,Village High Road 32rd corss street,Village High Road 30th cross street,C. Duraisamy street in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19306,Roads,Completed,NQ-SHOZHINGANALLUR,198,950000,Attending Patch Work at Modern Layout 8th Avenue in Dn-198 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/19309,Roads,Completed,NQ-SHOZHINGANALLUR,198,910000,Attending Patch Work at Modern Layout 8th Avenue Extn in Dn-198 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/19310,Roads,Completed,NQ-SHOZHINGANALLUR,198,980000,"Attending Patch Work at Modern Layout 7th Avenue, Modern Layout 8th Avenue Cross Street, in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19312,Roads,Completed,NQ-SHOZHINGANALLUR,198,990000,"Attending Patch Work at Gangai amman kovil st (church road), Gangai amman kovil 2nd street, Gangai amman kovil 3rd cross street in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19435,Roads,Completed,NQ-SHOZHINGANALLUR,197,990000,Attending Patch Work at Nehru Street Sholinganallur in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/19436,Roads,Completed,NQ-SHOZHINGANALLUR,196,997000,"IMPROVEMENTS TO ROADS BY USING GSB,WMM,AT POOMBUGAR STREET,POOMBUGAR EXTN ,RAJA MEENATCHI STREETIN DIVISION 196,UNIT44,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19438,Roads,Completed,NQ-SHOZHINGANALLUR,196,995000,"IMPROVEMENTS TO ROADS BY USING GSB,WMM AT GOVINDA ROYAL ENCLAVE MAIN ROAD AND 1ST STREET IN DIVISION 196,UNIT44,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19440,Roads,Completed,NQ-SHOZHINGANALLUR,196,910000,"IMPROVEMENTS TO THE ROAD BY USING GSB,WMM AT HANUMAN COLONY 3RDSTREET,7TH STREET,8THSTREET IN DIVISION 196,UNIT44,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19458,Parks,Completed,NQ-SHOZHINGANALLUR,200,250000,"OUTSOURCING MAINTENANCE OF PARKS FOR 3 MONTHS AT TNSCB 1st MAIN ROAD PARK, TNSCB 33rd CROSS STREET PARK IN DN 200 AND OUTSOURCING MAINTENANCE OF PARKS FOR 3 MONTHS AT AMURTHA STREET VGPLAYOUT PARK IN UTHANDI IN DN 199 , Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19461,Buildings,Completed,NQ-SHOZHINGANALLUR,200,640000,"IMPROVEMENTS TO PRIMARY SCHOOL BY PROVIDING PLUMBING,ELECTRICAL WORKS AND FLOOR LEVEL RAISING WORKS AT P. U. MIDDLE SCHOOL AT TNSCB -TSUNAMI NAGAR IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19475,Roads,Completed,NQ-SHOZHINGANALLUR,197,880000,"Providing and Laying GSB and Dust at Anna 2nd Cross Street,Manimegalai nagar 2nd Street and Various Streets in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/19479,Roads,Completed,NQ-SHOZHINGANALLUR,197,980000,Providing and Laying GSB and Dust at Kumaraswamy Nagar Main Road in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/19493,Roads,Completed,NQ-SHOZHINGANALLUR,197,917000,"Providing and Laying Hume Pipe and Chamber at Dharma Raja Koil Street,Neduncheliyan Salai,Devaraj Nagar 1st cross,2nd cross,3rd cross,4th cross,2main road,3rd Main Road in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20000,Roads,Completed,NQ-SHOZHINGANALLUR,198,810000,"Forming and Laying Using GSB and Dust at Sai illam Main Road,Sai illaam 3rd & 4th Street in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20004,Roads,Completed,NQ-SHOZHINGANALLUR,198,940000,"Forming and Laying Using GSB and Dust at Sai illam 1st,2nd , 5th and 6 street in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20258,Roads,Completed,NQ-SHOZHINGANALLUR,198,990000,"Providing and Laying GSB and Dust at SA Ragava Naicker Street, SR Boopathy Naicker Street, Vaithiyalingam Salai, LJ Avenue in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20261,Roads,Completed,NQ-SHOZHINGANALLUR,198,991000,Providing and Laying GSB and Dust at Spring Garden 2nd Street in Dn-198 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/20266,Roads,Completed,NQ-SHOZHINGANALLUR,197,980000,Providing and Laying GSB and Dust at Govt Higher Secondary School Inside (North Side) in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/20269,Roads,Completed,NQ-SHOZHINGANALLUR,197,979000,Providing and Laying GSB and Dust at Govt Higher Secondary School Inside (South Side) in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/20271,Roads,Completed,NQ-SHOZHINGANALLUR,197,390000,Attending patch work at Village high road approach of narayanasamy nagar 4th street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/20280,Roads,Completed,NQ-SHOZHINGANALLUR,197,990000,"Providing and Laying GSB and Dust at Anna 1st Cross Street,Senganiamman koil Street,Sadagoban Street in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20284,Roads,Completed,NQ-SHOZHINGANALLUR,197,950000,"Providing and Laying WMM at Devaraj Nagar 1st main road, Devaraj Nagar 1st Cross Street in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20288,Roads,Completed,NQ-SHOZHINGANALLUR,197,940000,"Providing and Laying WMM at Devaraj Nagar 2nd Main Road,Devaraj Nagar 3rd cross street in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20291,Roads,Completed,NQ-SHOZHINGANALLUR,197,960000,Providing and Laying WMM at Devaraj Nagar 3rd main road and CGS Farm Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/20302,Roads,Completed,NQ-SHOZHINGANALLUR,197,932000,Providing and Laying GSB and Dust at inside of Shopping Complex Old Market in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/20303,Roads,Completed,NQ-SHOZHINGANALLUR,197,900000,Providing and Laying GSB and Dust at inside of Shopping Complex New Market in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/20411,Roads,Completed,NQ-SHOZHINGANALLUR,193,956000,"PROVIDING AND LAYING WMM NEW GANESH NAGAR 11TH TO 17TH CROSS STREET AND 8TH CROSS STREET IN DN-193, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20412,Roads,Completed,NQ-SHOZHINGANALLUR,193,683000,"PROVIDING AND LAYING WMM AT NEW GANESH NAGAR 1ST, 2ND AND 3RD CROSS STREET IN DN-193, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20413,Roads,Completed,NQ-SHOZHINGANALLUR,193,788000,"PROVIDING AND LAYING WMM AT NEW GANESH NAGAR 4TH AND 5TH CROSS STREET IN DN-193,U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20415,Roads,Completed,NQ-SHOZHINGANALLUR,193,990000,"PROVIDING AND LAYING WMM AT SAI NAGAR EXTN 1ST AND 2ND CROSS STREET IN DN-193,U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20533,Buildings,Completed,NQ-SHOZHINGANALLUR,196,815000,"IMPROVEMENTS TO ROADS BY USING GSB,QUARRY DUST,AT PALLAVAN NAGAR,GOVINDAN ENCLAVE IN DIV-196,UNIT-44",Own Sources,15,2015-16,2016-17 NQ/2015-16/20699,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,992000,"IMPROVEMENTS TO SIDE DRAIN AT MURUGASEAN SALAI FROM NEELANKARAI LINK ROAD IN DIVISION- 193, UNIT-45, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/20704,Roads,Completed,NQ-SHOZHINGANALLUR,192,812000,"FORMING AND LAYING ROAD WITH WMM IN GAJIRA GARDEN 1ST STREET & SUN RISE AVENUE IN DN-192, U- 44 , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20707,Roads,Completed,NQ-SHOZHINGANALLUR,192,873000,"FORMING AND LAYING ROAD WITH GSB & WMM IN GAJIRA GARDEN 1ST CROSS STREET & 4TH CROSS STREET IN DIV-192, U-44 ,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20708,Roads,Completed,NQ-SHOZHINGANALLUR,192,959000,"FORMING ROAD WITH GSB, WMM & QUARRY RUBISH CLRI NAGAR & CHENGANIAMMAN KOIL STREET IN DIV-192, U- , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20729,Roads,Completed,NQ-SHOZHINGANALLUR,192,968000,"FORMING AND LAYING ROAD WITH GSB & WMM IN GAJIRA GARDEN 6TH CROSS & 3RD CROSS STREET IN DIN-192, U- 44 , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20733,Roads,Completed,NQ-SHOZHINGANALLUR,192,978000,"FORMING ROAD WITH GSB & WMM IN GAJIRA NAGAR 2ND STREET IN DIV-192, U- , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20740,Roads,Completed,NQ-SHOZHINGANALLUR,192,764000,"FORMING AND LAYING ROAD WITH GSB & WMM IN GAJIRA GARDEN 2ND & 5TH CROSS STREET IN DIV-192, U-44 , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20778,Roads,Completed,NQ-SHOZHINGANALLUR,196,883000,"FORMING ROAD WITH GSB & WMM IN 2ND AVENUE 2ND CROSS STREET & CHERAN NAGAR 1ST CROSS STREET IN DIV-196, U-44 , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20782,Roads,Completed,NQ-SHOZHINGANALLUR,196,781000,"FORMING AND LAYING ROAD WITH GSB & WMM 2ND AVENUE 2ND CROSS STREET (Reach-1) IN DIV-196, U- 44 , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20783,Roads,Completed,NQ-SHOZHINGANALLUR,196,825000,"FORMING AND LAYING ROAD WITH GSB & WMM IN 2ND AVENUE 6TH CROSS STREET(Reach-1) IN DIV-196, U- , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20826,Roads,Completed,NQ-SHOZHINGANALLUR,196,825000,"FORMING AND LAYING ROAD WITH GSB & WMM IN 2ND AVENUE 6TH CROSS STREET(Reach-2) IN DIV-196, U- , Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20830,Roads,Completed,NQ-SHOZHINGANALLUR,196,464000,"FORMING AND LAYING ROAD WITH GSB & WMM IN 2ND AVEUE 2ND CROSS STREET (Reach-2) IN DIV-196, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20832,Roads,Completed,NQ-SHOZHINGANALLUR,196,713000,"FORMING AND LAYING ROAD WITH GSB & WMM IN BRINDAVANAM STREET IN DIV-196, U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20834,Roads,Completed,NQ-SHOZHINGANALLUR,196,951000,"FORMING AND LAYING ROAD WITH GSB & WMM IN 2ND AVENUE 7TH CROSS STREET IN DIV-196, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20841,Roads,Completed,NQ-SHOZHINGANALLUR,196,781000,"FORMING AND LAYING ROAD WITH GSB & WMM IN PRARTHANA 2ND AVENUE IN DIV-196, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20859,Roads,Completed,NQ-SHOZHINGANALLUR,197,3780000,"Forming and laying of BT road with using paver finisher at Neduncheliyan Salai in Dn.197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20861,Roads,Completed,NQ-SHOZHINGANALLUR,197,2750000,"Forming and laying of BT road with using paver finisher at Devaraj Nagar 3rd Main Road in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20864,Roads,Completed,NQ-SHOZHINGANALLUR,197,952000,"Forming and laying of BT road with using paver finisher at Devaraj Nagar 1st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20865,Roads,Completed,NQ-SHOZHINGANALLUR,197,1727000,"Forming and laying of BT road with using paver finisher at Devaraj Nagar 2nd Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20867,Roads,Completed,NQ-SHOZHINGANALLUR,197,1390000,"Forming and laying of BT road with using paver finisher at Devaraj Nagar 4th Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20873,Roads,Completed,NQ-SHOZHINGANALLUR,197,2020000,"Forming and laying of BT road with using paver finisher at Dharmaraja koil Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20878,Roads,Completed,NQ-SHOZHINGANALLUR,197,15700000,"Forming and laying of BT road with using paver finisher at School Road in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20887,Roads,Completed,NQ-SHOZHINGANALLUR,197,471000,"Forming and laying of BT road with using paver finisher at N K S Nagar, in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20893,Roads,Completed,NQ-SHOZHINGANALLUR,197,660000,"Forming and laying of BT road with using paver finisher at C G S Farm Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20900,Roads,Completed,NQ-SHOZHINGANALLUR,197,1820000,"Forming and laying of BT road with using paver finisher at Ezhil Nagar Main Road in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20904,Roads,Completed,NQ-SHOZHINGANALLUR,197,467000,"Forming and laying of BT road with using paver finisher at Ezhil Nagar 4th Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20910,Roads,Completed,NQ-SHOZHINGANALLUR,197,1320000,"Forming and laying of BT road with using paver finisher at Devaraj Nagar 1st Main Road in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20916,Roads,Completed,NQ-SHOZHINGANALLUR,197,890000,"Forming and laying of BT road with using paver finisher at Kamber Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20919,Roads,Completed,NQ-SHOZHINGANALLUR,197,2070000,"Forming and laying of BT road with using paver finisher at Kalaimagal Nagar 2nd Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20922,Roads,Completed,NQ-SHOZHINGANALLUR,197,2430000,"Forming and laying of BT road with using paver finisher at Govindasamy Nagar Main Road in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20926,Roads,Completed,NQ-SHOZHINGANALLUR,197,1510000,"Forming and laying of BT road with using paver finisher at Ganesh Nagar Main Road in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20931,Roads,Completed,NQ-SHOZHINGANALLUR,197,1910000,"Forming and laying of BT road with using paver finisher at Ganesh Nagar 1st Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20935,Roads,Completed,NQ-SHOZHINGANALLUR,197,3788000,"Forming and laying of BT road with using paver finisher at M G R Street-Sholinganallur in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20936,Roads,Completed,NQ-SHOZHINGANALLUR,192,174000,"FORMING AND LAYING OF CC ROAD USING M30 GRADE CONCRETE AT SENGENIAMMAN KOIL STREET IN DIVISON - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20941,Roads,Completed,NQ-SHOZHINGANALLUR,192,633000,"FORMING AND LAYING OF CC ROAD USING M30 GRADE CONCRETE AT SENGENIAMMAN KOIL 6TH CROSSS STREET IN DIVISON - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20950,Roads,Completed,NQ-SHOZHINGANALLUR,192,385000,"FORMING AND LAYING OF CC ROAD USING M30 GRADE CONCRETE AT SENGENIAMMAN KOIL 7TH CROSS STREET IN DIVISON - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20956,Roads,Completed,NQ-SHOZHINGANALLUR,192,299000,"FORMING AND LAYING OF CC ROAD USING M30 GRADE CONCRETE AT SENGENIAMMAN KOIL 8TH CROSS STREET IN DIVISON - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20959,Roads,Completed,NQ-SHOZHINGANALLUR,197,989000,"Forming and laying of Cement Concrete Road at Eswaran Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20964,Roads,Completed,NQ-SHOZHINGANALLUR,197,570000,"Forming and laying of Cement Concrete Road at Lakshmi Vinayagar koil 1st Street Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20971,Roads,Completed,NQ-SHOZHINGANALLUR,197,730000,"Forming and laying of Cement Concrete Road at Aringar Anna 1st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20973,Roads,Completed,NQ-SHOZHINGANALLUR,197,1285000,"Forming and laying of Cement Concrete Road at Indiragandhi 1st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20977,Roads,Completed,NQ-SHOZHINGANALLUR,197,325000,"Forming and laying of Cement Concrete Road at Bharathidasan 1st & 2nd Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20979,Roads,Completed,NQ-SHOZHINGANALLUR,197,2290000,"Forming and laying of Cement Concrete Road at Kadumbadi Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20986,Roads,Completed,NQ-SHOZHINGANALLUR,197,855000,"Forming and laying of Cement Concrete Road at Village High Road 21st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20987,Roads,Completed,NQ-SHOZHINGANALLUR,197,705000,"Forming and laying of Cement Concrete Road at Village High Road 28th Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20992,Roads,Completed,NQ-SHOZHINGANALLUR,197,620000,"Forming and laying of Cement Concrete Road at School Road 3rd Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20995,Roads,Completed,NQ-SHOZHINGANALLUR,197,205000,"Forming and laying of Cement Concrete Road at School Road 4th Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/20999,Roads,Completed,NQ-SHOZHINGANALLUR,197,205000,"Forming and laying of Cement Concrete Road at School Road 5th Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21000,Roads,Completed,NQ-SHOZHINGANALLUR,197,530000,"Forming and laying of Cement Concrete Road at School Road 6th Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21003,Roads,Completed,NQ-SHOZHINGANALLUR,197,508000,"Forming and laying of Cement Concrete Road at School Road 7th Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21010,Roads,Completed,NQ-SHOZHINGANALLUR,197,255000,"Forming and laying of Cement Concrete Road at Govindasamy Nagar 2nd Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21012,Roads,Completed,NQ-SHOZHINGANALLUR,197,1120000,"Forming and laying of Cement Concrete Road at Govindasamy Nagar 3rd Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21015,Roads,Completed,NQ-SHOZHINGANALLUR,197,300000,"Forming and laying of Cement Concrete Road at Nehru 1st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21018,Roads,Completed,NQ-SHOZHINGANALLUR,192,642000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT KAKAN STREET IN DIVISION - 192,UNIT - 44, ZONE - 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21020,Roads,Completed,NQ-SHOZHINGANALLUR,197,508000,"Forming and laying of Cement Concrete Road at Nehru 2nd Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21038,Roads,Completed,NQ-SHOZHINGANALLUR,197,336000,"Forming and laying of Cement Concrete Road at Govindasamy Nagar 1st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21040,Roads,Completed,NQ-SHOZHINGANALLUR,197,532000,"Forming and laying of Cement Concrete Road at Dharmaraja koil 1st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21045,Roads,Completed,NQ-SHOZHINGANALLUR,197,360000,"Forming and laying of Cement Concrete Road at Village High Road 14th Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21048,Roads,Completed,NQ-SHOZHINGANALLUR,197,917000,"Forming and laying of Cement Concrete Road at Kaliamman Koil 1st Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21050,Roads,Completed,NQ-SHOZHINGANALLUR,197,954000,"Forming and laying of Cement Concrete Road at Kaliamman Koil 2nd Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21052,Roads,Completed,NQ-SHOZHINGANALLUR,197,640000,"Forming and laying of Cement Concrete Road at Kaliamman Koil 4th Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21056,Roads,Completed,NQ-SHOZHINGANALLUR,197,492000,"Forming and laying of Cement Concrete Road at Kaliamman Koil 5th Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21060,Roads,Completed,NQ-SHOZHINGANALLUR,197,2000000,"Forming and laying of Cement Concrete Road at Kaliamman Koil 6th Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21067,Roads,Completed,NQ-SHOZHINGANALLUR,197,2440000,"Forming and laying of Cement Concrete Road at Kaliamman Koil 7th Cross Street in Dn-197, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21101,Roads,Completed,NQ-SHOZHINGANALLUR,192,286000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT THIRUVALLUVAR NAGAR 1ST CROSS STREET IN DIVISION - 192,UNIT - 44,ZONE - 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21103,Roads,Completed,NQ-SHOZHINGANALLUR,192,143000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT THIRUVALLUVAR NAGAR 2ND CROSS STREET IN DIVISION - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21104,Roads,Completed,NQ-SHOZHINGANALLUR,194,362000,Attending bituminous patch work at boundary salai in Dn-194 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21110,Roads,Completed,NQ-SHOZHINGANALLUR,192,219000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT THIRUVALLUVAR NAGAR 3RD CROSS STREET IN DIVISION - 192,UNIT - 44,ZONE - 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21111,Roads,Completed,NQ-SHOZHINGANALLUR,194,387000,Attending bituminous patch work at Industrial estate road in Dn-194 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21112,Road Cut,Completed,NQ-SHOZHINGANALLUR,200,980000,"RESTORATION OF ROADCUT USING GSB AND CONCRETE AT PIDARIAMMAN KOIL STREET IN DN 200, U45,Z15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/21114,Roads,Completed,NQ-SHOZHINGANALLUR,192,113000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT THIRUVALLUVAR NAGAR 4TH CROSS STREET IN DIVISION - 192,UNIT - 44,ZONE - 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21118,Roads,Completed,NQ-SHOZHINGANALLUR,194,260000,Attending bituminous patch work at VPG avenue in Dn-194 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21131,Roads,Completed,NQ-SHOZHINGANALLUR,192,484000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT QUIDE MILLATH STREET IN DIVISION - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21134,Roads,Completed,NQ-SHOZHINGANALLUR,192,399000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT ANBALAGAN STREET IN DIVISION - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21140,Roads,Completed,NQ-SHOZHINGANALLUR,192,2446000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT PERIYA NEELANKARAI KUPPAM 1 TO 11 CROSS STREETS IN DIVISION - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21145,Roads,Completed,NQ-SHOZHINGANALLUR,192,747000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT 3 CROSS STREETS IN ARIGNAR ANNA 4TH STREET IN DIVISION - 192,UNIT - 44,ZONE - 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21146,Roads,Completed,NQ-SHOZHINGANALLUR,192,1424000,"FORMING AND LAYING CC ROAD USING M30 GRADE CONCRETE AT CHINNA NEELANKARAI KUPPAM 4 TO 8 TH CROSS STREET IN DIVISION - 192,UNIT - 44,ZONE - 15M",Own Sources,15,2015-16,2016-17 NQ/2015-16/21214,Roads,Completed,NQ-SHOZHINGANALLUR,196,6950000,Forming and Laying of BT road at Injambakkam to Vettuvankeni link road in Dn-196 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21243,Roads,Completed,NQ-SHOZHINGANALLUR,197,2650000,ATTENDING PATCH WORK IN FLOOD DAMAGED ROAD AT GANGAIAMMAN KOIL STREET IN DN-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21245,Roads,Completed,NQ-SHOZHINGANALLUR,197,1160000,ATTENDING PATCH WORK IN FLOOD DAMAGED ROAD AT INDRA GANDHI MAIN ROAD IN DN-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21246,Roads,Completed,NQ-SHOZHINGANALLUR,197,2270000,ATTENDING PATCH WORK IN FLOOD DAMAGED ROAD AT KUPPUSAMY STREET IN DN-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21249,Roads,Completed,NQ-SHOZHINGANALLUR,194,7250000,Laying cement concrete road at secretariat colony 4th circle road in DN-194 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21254,Roads,Completed,NQ-SHOZHINGANALLUR,195,2250000,"FORMING AND LAYING OF BT ROAD AT EZHIL NAGAR 1ST CROSS STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21255,Roads,Completed,NQ-SHOZHINGANALLUR,192,1480000,"Attending Patch Work at Kazura Garden 2nd Main Road,Kazura Garden 5th, 6th & 7th Cross Street in Dn-192 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21260,Roads,Completed,NQ-SHOZHINGANALLUR,196,946000,"REPAIRES AND ATTENDING PATCHES WITH BITUMINOUS COURSE AT KAMARAJAR NAGAR WARD-196,U-44 ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21261,Roads,Completed,NQ-SHOZHINGANALLUR,196,855000,"REPAIRES AND ATTENDING PATCHES WITH BITUMINOUS COURSE AT RAMALINGA NAGAR MAIN ROAD WARD-196,U-44 ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21262,Roads,Completed,NQ-SHOZHINGANALLUR,196,855000,"REPAIRES AND ATTENDING PATCHES WITH BITUMINOUS COURSE AT BHARATHI NAGAR TO RAMALINGA NAGAR MAIN ROAD WARD-196,U-44 ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21263,Roads,Completed,NQ-SHOZHINGANALLUR,193,720000,"REPAIRES AND ATTENDING PATCHES WITH BITUMINOUS COURSE AT MAHATMA GANDHI NAGAR 1ST MAIN ROAD FROM 3RD MAIN ROAD TO KAMARAJAR STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21264,Roads,Completed,NQ-SHOZHINGANALLUR,193,720000,"REPAIRES AND ATTENDING PATCHES WITH BITUMINOUS COURSE AT MAHATMAGANDHI NAGAR 1ST MAIN ROAD FROM B CANAL TO 3RD MAIN ROAD WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21265,Roads,Completed,NQ-SHOZHINGANALLUR,195,5380000,"FORMING AND LAYING OF BT ROAD AT KANNAGI NAGAR 9TH MAIN ROAD IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21269,Roads,Completed,NQ-SHOZHINGANALLUR,193,1620000,"FORMING AND LAYIING BITUMINOUSE COURSE AT BURIAL GROUND ROAD IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21270,Roads,Completed,NQ-SHOZHINGANALLUR,193,305000,"FORMING AND LAYIING BITUMINOUSE COURSE AT NEW GANESH NAGAR 7TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21271,Roads,Completed,NQ-SHOZHINGANALLUR,193,718000,"FORMING AND LAYIING BITUMINOUSE COURSE AT NEW GANESH NAGAR 6TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21272,Roads,Completed,NQ-SHOZHINGANALLUR,193,1019000,"FORMING AND LAYIING BITUMINOUSE COURSE AT NEW GANESH NAGAR 5TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21273,Roads,Completed,NQ-SHOZHINGANALLUR,193,772000,"FORMING AND LAYIING BITUMINOUSE COURSE AT NEW GANESH NAGAR 4TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21274,Roads,Completed,NQ-SHOZHINGANALLUR,193,739000,"FORMING AND LAYIING BITUMINOUSE COURSE AT NEW GANESH NAGAR 3RD STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21275,Roads,Completed,NQ-SHOZHINGANALLUR,193,348000,"FORMING AND LAYIING BITUMINOUSE COURSE AT NEW GANESH NAGAR 2ND STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21276,Roads,Completed,NQ-SHOZHINGANALLUR,193,197000,"FORMING AND LAYIING BITUMINOUSE COURSE AT NEW GANESH NAGAR 1ST STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21277,Roads,Completed,NQ-SHOZHINGANALLUR,193,566000,"FORMING AND LAYIING BITUMINOUSE COURSE AT KARPAGA VINAYAGAR NAGAR 6TH MAIN ROAD (PART) IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21278,Roads,Completed,NQ-SHOZHINGANALLUR,193,348000,"FORMING AND LAYIING BITUMINOUSE COURSE AT KARPAGA VINAYAGAR NAGAR 25TH CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21280,Roads,Completed,NQ-SHOZHINGANALLUR,195,2440000,"FORMING AND LAYING OF BT ROAD AT EZHIL NAGAR 4TH CROSS STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21281,Roads,Completed,NQ-SHOZHINGANALLUR,193,495000,"FORMING AND LAYIING BITUMINOUSE COURSE AT KARPAGA VINAYAGAR NAGAR 24TH CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21282,Roads,Completed,NQ-SHOZHINGANALLUR,193,800000,"FORMING AND LAYIING BITUMINOUSE COURSE AT KARPAGA VINAYAGAR NAGAR 23RD CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21283,Roads,Completed,NQ-SHOZHINGANALLUR,193,309000,"FORMING AND LAYIING BITUMINOUSE COURSE AT KARPAGA VINAYAGAR NAGAR 22ND CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21284,Roads,Completed,NQ-SHOZHINGANALLUR,193,520000,"FORMING AND LAYIING BITUMINOUSE COURSE AT KARPAGA VINAYAGAR NAGAR 21ST CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21285,Roads,Completed,NQ-SHOZHINGANALLUR,193,480000,"FORMING AND LAYIING BITUMINOUSE COURSE AT KARPAGA VINAYAGAR NAGAR 20TH CROSS STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21286,Roads,Completed,NQ-SHOZHINGANALLUR,193,1365000,"FORMING AND LAYIING BITUMINOUSE COURSE AT MAHATMA GANTHI NAGAR 12TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21287,Roads,Completed,NQ-SHOZHINGANALLUR,193,719000,"FORMING AND LAYIING BITUMINOUSE COURSE AT MAHATMA GANTHI NAGAR 10TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21288,Roads,Completed,NQ-SHOZHINGANALLUR,193,522000,"FORMING AND LAYIING BITUMINOUSE COURSE AT MAHATMA GANTHI NAGAR 4TH STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21289,Roads,Completed,NQ-SHOZHINGANALLUR,193,330000,"FORMING AND LAYIING BITUMINOUSE COURSE AT MAHATMA GANTHI NAGAR 3RD STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21290,Roads,Completed,NQ-SHOZHINGANALLUR,193,3982000,"LAYING CEMENT CONCRETE ROAD AT SUBRAYA NAGAR 1 TO 4 STREET IN WARD-193, ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21291,Roads,Completed,NQ-SHOZHINGANALLUR,193,2554000,"LAYING CEMENT CONCRETE ROAD AT SUBRAYA NAGAR 1 TO 3 CROSS STREET IN WARD-193, ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21292,Roads,Completed,NQ-SHOZHINGANALLUR,193,1392000,"LAYING CEMENT CONCRETE ROAD AT ARIGNAR ANNA NAGAR 1 TO 4 CROSS STREET IN WARD-193, ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21293,Roads,Completed,NQ-SHOZHINGANALLUR,193,1272000,"LAYING CEMENT CONCRETE ROAD AT ARIGNAR ANNA NAGAR 8TH STREET IN WARD-193, ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21294,Roads,Completed,NQ-SHOZHINGANALLUR,195,1920000,"FORMING AND LAYING OF BT ROAD AT EZHIL NAGAR 2ND CROSS STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21295,Roads,Completed,NQ-SHOZHINGANALLUR,193,2432000,"LAYING CEMENT CONCRETE ROAD AT ARIGNAR ANNA NAGAR 7TH STREET IN WARD-193, ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21296,Roads,Completed,NQ-SHOZHINGANALLUR,193,5100000,"LAYING CEMENT CONCRETE ROAD AT ARIGNAR ANNA NAGAR 1ST STREET IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21297,Roads,Completed,NQ-SHOZHINGANALLUR,193,1035000,LAYING CEMENT CONCRETE ROAD AT KARPAGA VINAYAGAR NAGAR 1 TO 5 LANES IN WARD-193 ZONE-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21299,Roads,Completed,NQ-SHOZHINGANALLUR,195,4100000,"FORMING AND LAYING OF CC ROAD AT EZHIL NAGAR IN BETWEEN BLOCK(NOS 12-14,34-36,42-39) IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21300,Roads,Completed,NQ-SHOZHINGANALLUR,195,3580000,"FORMING AND LAYING OF C.C ROAD AT EZHIL NAGAR INBETWEEN BLOCK(NOS 23-17,28-26 AND INFORNT OF BLOCK.21) IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21302,Roads,Completed,NQ-SHOZHINGANALLUR,195,2500000,"FORMING AND LAYING OF BT ROAD AT EZHIL NAGAR 1ST MAIN ROAD IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21303,Roads,Completed,NQ-SHOZHINGANALLUR,195,1860000,"FORMING AND LAYING OF BT ROAD AT EZHIL NAGAR 2ND MAIN ROAD IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21304,Roads,Completed,NQ-SHOZHINGANALLUR,195,2380000,"FORMING AND LAYING OF BT ROAD AT EZHIL NAGAR 3RD MAIN ROAD IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21305,Roads,Completed,NQ-SHOZHINGANALLUR,195,2920000,"FORMING AND LAYING OF BT ROAD AT EZHIL NAGAR 3RD CROSS STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21306,Roads,Completed,NQ-SHOZHINGANALLUR,195,1380000,"FORMING AND LAYING OF C.C ROAD AT NEHRU NAGAR 1ST CROSS STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21311,Roads,Completed,NQ-SHOZHINGANALLUR,198,1867000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD AT PILLAYAR KOIL STREET IN DIV-198,U-44,ZONE -15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21312,Roads,Completed,NQ-SHOZHINGANALLUR,198,1852000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD AT BHARATHI NAGAR 1 STREET IN DIV-198,U-44,ZONE -15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21313,Roads,Completed,NQ-SHOZHINGANALLUR,195,2070000,"FORMING AND LAYING OF C.C ROAD AT NEHRU NAGAR 2ND CROSS STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21314,Roads,Completed,NQ-SHOZHINGANALLUR,198,624000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD AT BHARATHI NAGAR 2ND STREET IN DIV-198,U-44,ZONE -15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21315,Roads,Completed,NQ-SHOZHINGANALLUR,198,732000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD AT BHARATHI NAGAR 3RD STREET IN DIV-198,U-44,ZONE -15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21316,Roads,Completed,NQ-SHOZHINGANALLUR,198,1361000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD AT BHARATHI NAGAR 4TH STREET IN DIV-198,U-44,ZONE -15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21319,Roads,Completed,NQ-SHOZHINGANALLUR,195,654000,"FORMING AND LAYING OF C.C ROAD AT NEHRU NAGAR 3RD CROSS STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21320,Roads,Completed,NQ-SHOZHINGANALLUR,195,4030000,"FORMING AND LAYING OF C.C ROAD AT OKKIYAM PETTAI BURIAL GROUND ROAD IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21340,Roads,Completed,NQ-SHOZHINGANALLUR,195,990000,"PROVIDING AND LAYING GSB AND QUARRY DUST AT Ezhil Nagar East of Blocks-2 (School Road),Ezhil Nagar cross street in front of Block-4(in front of Ration shop), Ezhil Nagar cross street in between Block-3&4, Ezhil Nagar cross street in between Block-4&6 IN DN-195 UNIT-45 ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21342,Roads,Completed,NQ-SHOZHINGANALLUR,198,2250000,Forming and Laying of BT Road at Modern Lyout 12th Avenue in Dn-198 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21703,Roads,Completed,NQ-SHOZHINGANALLUR,200,2784000,"RELAYING OF CC ROAD USING M30 CONCRETE AT SENGANIAMMAN KOIL STREET IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21759,Roads,Completed,NQ-SHOZHINGANALLUR,200,1284000,"RELAYING OF CC ROAD USING M30 CONCRETE AT PANCHAYAT OFFICE MAIN ROAD IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21774,Roads,Completed,NQ-SHOZHINGANALLUR,200,380000,"RELAYING OF CC ROAD USING M30 CONCRETE AT KARUMAKARIYA SALAI IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21778,Roads,Completed,NQ-SHOZHINGANALLUR,200,2664000,"RELAYING OF CC ROAD USING M30 CONCRETE AT BAJANAI KOIL STREET IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21787,Roads,Completed,NQ-SHOZHINGANALLUR,200,2597000,"RELAYING OF CC ROAD USING M30 CONCRETE AT SENGOTHAI AMMAN KOIL STREET IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21793,Roads,Completed,NQ-SHOZHINGANALLUR,200,2210000,"RELAYING OF CC ROAD USING M30 CONCRETE AT PIDARI AMMAN KOIL STREET IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21798,Roads,Completed,NQ-SHOZHINGANALLUR,200,2987000,"RELAYING OF CC ROAD USING M30 CONCRETE AT KAMARAJAR STREET,ANNAI INDIRAGANDHI STREET,PANCHAYAT OFFICE CROSS STREET IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21799,Roads,Completed,NQ-SHOZHINGANALLUR,196,910000,"FORMING AND LAYING ROAD WITH GSB & WMM IN 2ND AVENUE 1ST CROSS STREET IN DIV-196, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21806,Roads,Completed,NQ-SHOZHINGANALLUR,200,3080000,"RELAYING OF CC ROAD USING M30 CONCRETE AT AMBEDKAR STREET,ELLAIAMMAN KOIL STREET,ANNA SALAI CROSS STREET IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21808,Roads,Completed,NQ-SHOZHINGANALLUR,200,2485000,"RELAYING OF CC ROAD USING M30 CONCRETE AT MAYANA SALAI,CHERAN STREET,POUND STREET IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21813,Roads,Completed,NQ-SHOZHINGANALLUR,199,1983000,"RELAYING OF CC ROAD USING M30 CONCRETE AT THADUMARIAMMAN KOIL STREET IN DN 199,U44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21816,Roads,Completed,NQ-SHOZHINGANALLUR,199,900000,"RELAYING OF CC ROAD USING M30 CONCRETE ATRICE MILL STREET(SUNDARA VINAYAGAR STREET)IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21822,Roads,Completed,NQ-SHOZHINGANALLUR,199,997000,"RELAYING OF CC ROAD USING M30 CONCRETE AT VENKATASUBRAMANIAM LANE(VVVS LANE)IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21830,Roads,Completed,NQ-SHOZHINGANALLUR,199,831000,"RELAYING OF CC ROAD USING M30 CONCRETE AT THANTHONI AMMAN KOIL STREET-EXTN IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21834,Roads,Completed,NQ-SHOZHINGANALLUR,199,1784000,"RELAYING OF CC ROAD USING M30 CONCRETE ATMUTHALAMMAN KOIL STREET IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/21839,Roads,Completed,NQ-SHOZHINGANALLUR,195,910000,Forming and Laying of BT Road Using Paver Finisher at Pillayar koil Street (From Pillayar Temple to Kannagi Nagar link Road in Dn-195 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21840,Roads,Completed,NQ-SHOZHINGANALLUR,195,600000,Forming and Laying of BT Road Using Paver Finisher at Madha koil Street (From Door No-302 to Plot No-521A) IN Dn-195 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21876,Roads,Completed,NQ-SHOZHINGANALLUR,193,357000,"REPAIRES AND ATTENDING BITUMINOUS PATCHES AT MAHATMAGANDHI NAGAR 3RD MAIN ROAD IN WARD-193, ZONE-15..",Own Sources,15,2015-16,2016-17 NQ/2015-16/21885,Roads,Completed,NQ-SHOZHINGANALLUR,195,550000,Attending Bituminous Patches With DBM and BC at Balamurugan garden 1st main road in ward-193 Unit-45 Zone-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21892,Roads,Completed,NQ-SHOZHINGANALLUR,193,398000,"Attending Bituminous Patches With DBM and BC at Pillayar koil street and Sai Nagar 1st & 2nd Main Road in Ward - 193, UNIT-45 , ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21895,Buildings,Completed,NQ-SHOZHINGANALLUR,193,139000,"PROVIDING ENTRANCE GATE TO THE EXISTING WARD -193, z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/21971,Roads,Completed,NQ-SHOZHINGANALLUR,195,780000,Forming and Laying of BT Road USing Paver Finisher at Madha koil Street (From OMR Service Road to Door No-302) in Dn-195 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/21988,Roads,Completed,NQ-SHOZHINGANALLUR,195,910000,Forming and Laying of BT Road Using Paver Finisher at Pillayar koil Street (From OMR Service Road to Pillayar Temple) in Dn-195 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/22554,Roads,Completed,NQ-SHOZHINGANALLUR,193,997000,"Providing and laying the road using GSB & WMM at Sri Sai Nagar 1st cross street, 4th cross street and Kulakarai street in Dn.193, zone 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/22562,Roads,Completed,NQ-SHOZHINGANALLUR,193,709000,Providing and laying the road using GSB and WMM at Karpaga Vinayaga Nagar 3rd main road and 20th cross street in Dn.193,Own Sources,15,2015-16,2017-18 NQ/2015-16/22688,Roads,Completed,NQ-SHOZHINGANALLUR,197,770000,Providing and Laying GSB and Dust For Inside of Middle School at Gajarajan Main Road Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/22696,Roads,Completed,NQ-SHOZHINGANALLUR,197,630000,Providing and Laying GSB and Dust For Inside of High School (Northenrn Side) at Gangaiamman koil Street Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/22705,Roads,Completed,NQ-SHOZHINGANALLUR,197,656000,Providing and Laying GSB and Dust at Gandhi 2nd Street Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/22924,Roads,Completed,NQ-SHOZHINGANALLUR,196,13300000,Forming and Laying of BT road at Anna Enclave in Dn-196 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/22937,Roads,Completed,NQ-SHOZHINGANALLUR,198,910000,"Providing and Laying GSB and Dust at J Nagar 1st cross street, J Nagar 2nd cross street, and J Nagar 3rd cross street in Dn-198, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/22944,Roads,Completed,NQ-SHOZHINGANALLUR,198,820000,"Providing and Laying GSB and Dust at J Nagar 4th cross street, and Spring Gardan 2nd street Extn., in Dn-198 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/22947,Roads,Completed,NQ-SHOZHINGANALLUR,196,1340000,FORMING AND LAYING OF BT ROAD AT RAJARATHINAM AVENUE IN DN-196 U-44 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/23034,Roads,Completed,NQ-SHOZHINGANALLUR,198,940000,Improvement School Providing and Laying GSB and Dust at Kudimiyandi Thoppu Govt Higher Secondary School in Dn-198 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/23051,Roads,Completed,NQ-SHOZHINGANALLUR,198,890000,Providing and Laying GSB and Dust at V G P South Avenue NRI Layout in Dn-198 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/23247,Roads,Completed,NQ-SHOZHINGANALLUR,197,830000,Providing and Laying GSB and Dust For Inside of Middle School at K.K.Salai in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/2385,Roads,Completed,NQ-SHOZHINGANALLUR,198,1690000,Improvements to the Burial Ground By Laying Cement Concrete Road at Sathiyavani muthu Street in Dn-198 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/24249,Buildings,Completed,NQ-SHOZHINGANALLUR,198,229000,"PAINTING WITH WRITING LETTER OF VARIOUS DUST BINS AND TRICYCLE IN DN-198,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/24557,Roads,Completed,NQ-SHOZHINGANALLUR,193,722000,"FORMING AND RAISING THE EXISITNG ROAD AT MURUGESAN STREET (WEST TO EAST) MARUTHI NAGAR 2ND MAIN ROAD TO SRINIVASA NAGAR IN WARD-193, UNIT-45, ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/24590,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,990000,"CONSTRUCTION OF SIDE DRAIN AT ANNAI INDIRA NAGAR MAIN ROAD IN DN-195M UNIT-45, ZONE-15.",Own Sources,15,2015-16,2017-18 NQ/2015-16/24609,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,995000,"CONSTRUCTION OF SIDE DRAIN AT NETHAJI STREET IN DN-195M UNIT-45, ZONE-15.",Own Sources,15,2015-16,2017-18 NQ/2015-16/24705,Roads,Completed,NQ-SHOZHINGANALLUR,195,960000,"LAYING WITH GSB ROAD AT MRG NAGAR, KANNAGI NAGAR 8TH MAIN ROAD, 11TH MAIN ROAD IN DN-195, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/24710,Roads,Completed,NQ-SHOZHINGANALLUR,196,940000,"FORMING AND LAYING ROAD WITH GSB AND WMM AT 2ND CROSS & 3RD CROSS STREET IN DN-196, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/24738,Roads,Completed,NQ-SHOZHINGANALLUR,196,960000,"FORMING AND LAYING ROAD WITH GSB AND WMM AT IST AVENUE 4TH AND 5TH CROSS STREET IN DN-196, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/24811,Roads,Completed,NQ-SHOZHINGANALLUR,193,720000,Forming the ExIsting Road With GSB and WMM at sai nagar extension 2nd main road in Dn-193 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/24815,Roads,Completed,NQ-SHOZHINGANALLUR,193,998000,Forming the ExIsting Road With GSB and WMM at sai nagar extension 3rd cross street in Dn-193 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/24824,Roads,Completed,NQ-SHOZHINGANALLUR,193,960000,Forming the Existing Road With GSB and WMM at sai nagar extension 4th to 7th cross street in Dn-193 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/24888,Roads,Completed,NQ-SHOZHINGANALLUR,197,830000,Raising GSB and Dust for Inside of Amma Unavagam at Kaliamman koil Main Road in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/24893,Buildings,Completed,NQ-SHOZHINGANALLUR,197,990000,"Proposed Construction of Toilet, Near MLA Office Building at Rajiv Gandhi Salai in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/24927,Roads,Completed,NQ-SHOZHINGANALLUR,196,950000,"PROVIDING HUME PIPE AT ANNA ENCLAVE AND INJAMBAKKAM VETUVANKENI LINK ROAD IN DIVISION 196,UNIT44,ZONE 15",Own Sources,15,2015-16,2017-18 NQ/2015-16/25230,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,996000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT SINGARAVELAN 15TH CROSS STREET IN DN-192,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/25236,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,997000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT SINGARAVELAN 2ND MAIN ROAD (0 TO 110M) IN DN-192,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/25245,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,998000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT SINGARAVELAN 2ND MAIN ROAD (110M TO 220M) IN DN-192,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/25580,Roads,Completed,NQ-SHOZHINGANALLUR,196,920000,"RAISING THE ROAD WITH GSB WMM AT SN NAGAR 3RD STREET,4TH STREET,AND VARIOUS STREET.IN DIV 196,UNIT 44, ZONE 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/26398,Roads,Completed,NQ-SHOZHINGANALLUR,196,997000,"FORMING AND LAYING ROAD WITH GSB & WMM AT IST AVENUE IST CROSS STREET IN DN-196, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/26574,Buildings,Completed,NQ-SHOZHINGANALLUR,200,800000,"IMPROVEMENTS TO COMPOSITE YARD BY PROVIDING STREET FURNITURE AND PAINTING WORKS ETC IN 9TH AVENUE ROAD IN DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/26577,Buildings,Completed,NQ-SHOZHINGANALLUR,200,475000,"WRITING LETTERS IN DUSTBIN AND TRICYCLE IN VARIOUS LOCATIONS OF DN 200,U45,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/26762,Culvert,Completed,NQ-SHOZHINGANALLUR,193,185000,"Providing painting for compactor bin at various street in div-193,unit-45, zone-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/26776,Roads,Completed,NQ-SHOZHINGANALLUR,193,708000,"RAISING AND IMPROVEMEMNT TO THE EXISTING ROAD WITH WMM AT MCN NAGAR EXTN AND KULAKARAI SALAI IN WARD-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/27367,Roads,Completed,NQ-SHOZHINGANALLUR,195,980000,"FORMING AND LAYING THE B.T ROAD WITH PAVER FINISHER AT VIVEKANANDAR STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/27398,Roads,Completed,NQ-SHOZHINGANALLUR,195,980000,"FORMING AND LAYING THE B.T ROAD WITH PAVER FINISHER AT VIVEKANANDAR 1ST STREET IN DIV-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/27531,Buildings,Completed,NQ-SHOZHINGANALLUR,200,600000,"IMPROVEMENTS TO PRIMARY SCHOOL AT MGR STREET BY USING FLOORING ,PLUMBING, PAINTING WORKS ETC.,",Own Sources,15,2015-16,2016-17 NQ/2015-16/27762,Buildings,Completed,NQ-SHOZHINGANALLUR,198,990000,"IMPROVEMENTS TO PARK (TOILET, SEPTIC TANK,ELECTRICAL ARRANGEMENTS AND WATER SUPPLY ARRANGEMENTS) AT SEA CLIFF MAIN ROAD IN DN-198, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/27776,Buildings,Completed,NQ-SHOZHINGANALLUR,198,895000,"IMPROVEMENTS TO PARK AT E12 TNHB PARK ( FIXING SS CHILDRENS PLAY APPARATUS AT SEACLIFF MAIN ROAD PARK) IN DN-198, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/27835,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,498000,"LAYING CEMENT CONCRETE ROAD AND IMPROVEMENTS TO SIDE DRAIN AT THERADI STREET IN DN-193, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/27959,Roads,Completed,NQ-SHOZHINGANALLUR,197,178000,Providing and Laying Dust at New Kumaran Nagar 2nd Main Road and New Kumaran Nagar 2nd to 17th Cross Street and Various Streets in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/28079,Roads,Completed,NQ-SHOZHINGANALLUR,200,430000,"ROADCUT RESTORATION BY USING CONCRETE AT TNSCB 91st , 20TH ,54th, 61st CROSS STREET, 8 TH,4TH, & 6th AVENUE IN DN 200, U45, Z15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/29542,Buildings,Completed,NQ-SHOZHINGANALLUR,198,920000,"Maintenance contract for Providing house keeping services for community Toilets (or public conveniences ) at Neelangarai ,Injamjbakkam ,Sholinganallur, Uthandi in U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/29834,Roads,Completed,NQ-SHOZHINGANALLUR,192,980000,"RELAYING BT COURSE WITH PAVER FINISH AT KAZURA GARDEN IST MAIN ROAD FROM ECR TO DOOR NO. 2/781 IN DN-192, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/29836,Roads,Completed,NQ-SHOZHINGANALLUR,192,970000,"RELAYING BT COURSE WITH PAVER FINISH AT KAZURA GARDEN IST MAIN ROAD FROM VINAYAGAR TEMPLE TO DOOR NO. 2/783 in Dn-192, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/29842,Roads,Completed,NQ-SHOZHINGANALLUR,192,740000,"RELAYING BT COURSE WITH PAVER FINISH AT KAZURA GARDEN Ist MAIN ROAD (From ECR to Door No.782) in Dn-192, U-44, Z-15",Own Sources,15,2015-16,2017-18 NQ/2015-16/29845,Roads,Completed,NQ-SHOZHINGANALLUR,192,810000,"RELAYING BT COURSE WITH PAVER FINISH AT KAZURA GARDEN IST MAIN ROAD (From Door No.782 to Pillaiyar Temple) in Dn-192, Z-15",Own Sources,15,2015-16,2017-18 NQ/2015-16/29865,Buildings,Completed,NQ-SHOZHINGANALLUR,195,270000,"PROVIDING PAINTING WORKS TO COMPOSITE YARD AT KANNAGI NAGAR 17TH MAIN ROAD IN DIV-195, U-45, Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/29866,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,359000,"CONSTRUCTION OF SIDE DRAIN AT NEHRU NAGAR 10TH STREET IN DIV-195, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/29868,Roads,Completed,NQ-SHOZHINGANALLUR,195,396000,"ATTENDING PATCHES WITH GSB AND WMM AT THIRUVALLUVAR STREET , SANTHOM AVENUE IN DN-195, U-45, Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/29869,Roads,Completed,NQ-SHOZHINGANALLUR,198,990000,Attending Patch Work at Mayana Salai in Dn-198 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/29870,Buildings,Completed,NQ-SHOZHINGANALLUR,195,111000,"PROVIDING NAME BORDS AND WRITTING NAME WORK TO POLICE BOOTH AND DUST BIN AT KANNAGI NAGAR, EZHIL NAGAR AND VARIOUS OTHER STREET IN DIV-195,U-45,Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/29871,Roads,Completed,NQ-SHOZHINGANALLUR,198,990000,"Attending Patch Work at Parameshwar Nagar,Mayana Salai in Dn-198 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/29879,Roads,Completed,NQ-SHOZHINGANALLUR,198,999000,"Providing and Fixing of Street Furniture Single Arrows at Village High Road,Sathyavani Muthu Street,Annai Indira Street,LR Rajarathinam Street,Ambedkar Street,Parameshwar Street,Vaidiyalingam Street,Kamaraj Street, Ponniyamman koil 1st and 2nd street, Yadaval street,VOC Street, TNHB Link Road, Pillayar Koil Street,Govind Reddy Street,Bharathi Nagar 1st,2nd,3rd,4th & 5th Main Road,GHangaiamman koil Street, Pondicherry Salai,Rajiv gandhi nagar 3rd and 4th street,Kudimiyandi thoppu school street,Panayur kuppam Main Road,Ambedkar Street, Padavettamman koil street,Quidamillath street,Velu Naiker Street,Kudimiyandi thoppu school 3rd to 9th Street,Kudimiyandi thoppu school North Street, Kudimiyandi thoppu school North 1st and 2nd Cross Street in Dn-198 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/29934,Parks,Completed,NQ-SHOZHINGANALLUR,197,85000,Outsourcing Maintenance of Parks Located at Sholinganallur Devaraj Nagar in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/29970,Buildings,Completed,NQ-SHOZHINGANALLUR,197,998000,improvement work to zonal office building and Auditor room Amma Makkal Sevai Maiyam & E Seva centre in Dn-197 U45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/30075,Roads,Completed,NQ-SHOZHINGANALLUR,192,349000,"Providing cement concrete patch work at Kazura Garden Ist and 2nd Main Road in Dn-192, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/30124,Roads,Completed,NQ-SHOZHINGANALLUR,193,180000,"Providing ramp to existing side drain at karapaga vinayagar 12th main road and sri sai nagar 1st main road in div-193, u-45, z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/30234,Buildings,Completed,NQ-SHOZHINGANALLUR,193,111000,"Providing grill door for ration shop at gangai amman street in Dn- 193, U-45, Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/30239,Roads,Completed,NQ-SHOZHINGANALLUR,193,730000,"Forming and Raising The Existing Road with GSB at Karpaga Vinayaga Nagar 3rd ,4th,5th and 33 Street in DN -193 U -45 Z-15",Own Sources,15,2015-16,2017-18 NQ/2015-16/30282,Parks,Completed,NQ-SHOZHINGANALLUR,197,69000,Outsourcing Maintenance of Parks Located at Central Avenue in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/30448,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,890000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT RAJENDRA NAGAR 2ND CROSS STREET AT DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2015-16,2016-17 NQ/2015-16/30450,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,768000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT RAJENDRA NAGAR 4TH CROSS STREET AT DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2015-16,2017-18 NQ/2015-16/30811,Roads,Completed,NQ-SHOZHINGANALLUR,196,700000,"IMPROVEMENTS TO ROADS BY USING WMM AT CHOLAMANDALADEVI NAGAR 7 TO 13 STREETS IN DIVISION 196,UNIT 45,ZONE15",Own Sources,15,2015-16,2017-18 NQ/2015-16/31039,Buildings,Completed,NQ-SHOZHINGANALLUR,199,97000,"IMPROVEMENTS TO PARK BY PROVIDING PAVER BLOCK AND NUMBER MARKING WORKS ETC AT VGP LAYOUT IN DN 199, U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/31040,Buildings,Completed,NQ-SHOZHINGANALLUR,199,195000,"PAINTING WITH LETTER WRITING OF VARIOUS DUST BINS AND TRICYCLE IN DN 199, U44, Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/31041,Buildings,Completed,NQ-SHOZHINGANALLUR,199,447000,"IMPROVEMENTS TO PRIMARY SCHOOL USING PAINTING,PLUMBING AND ELECTRICAL WORKS IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/31263,Parks,Completed,NQ-SHOZHINGANALLUR,197,223000,Outsourcing Maintenance of Parks Located at Kumarasamy Nagar in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/31264,Parks,Completed,NQ-SHOZHINGANALLUR,197,215000,Outsourcing Maintenance of Parks Located at Rajiv Gandhi Salai (TECH-KI) in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/31278,Footpath,Completed,NQ-SHOZHINGANALLUR,197,274000,Providing and Laying Interlocking Paving Block Inside of Lorry Shed at Rajiv Gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/31538,Roads,Completed,NQ-SHOZHINGANALLUR,198,950000,"Providing and Laying GSB AND WMM at Lilly Pond 1st Street in Dn-198, U-44, Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/31539,Roads,Completed,NQ-SHOZHINGANALLUR,198,890000,"Providing and Laying GSB AND WMM at Lilly Pond 2nd Street in Dn-198, U-44, Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/31643,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,330000,"Restoration of road cut,Road cut made by CMWSSB at Chandrasekaran avenue 1st main road in dn 194,U-45,Zone-15",Deposit Works,15,2015-16,2017-18 NQ/2015-16/31644,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,312000,"Restoration of road cut, Road cut made by CMWSSB at Chandrasekar avenue 2nd main road in dn-194,U-45,Zone-15.",Deposit Works,15,2015-16,2017-18 NQ/2015-16/31645,Parks,Completed,NQ-SHOZHINGANALLUR,194,121000,"OUTSOURCING MAINTENANCE OF PARK AT SAKTHI SRINIVASAN NAGAR AND P.T,C QUARTERS IN DN-194,U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/31646,Parks,Completed,NQ-SHOZHINGANALLUR,194,147000,"OUTSOURCING MAINTENANCE OF PARK AT CHANDRASEKARAN AVENUE IN DN-194, U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/31647,Parks,Completed,NQ-SHOZHINGANALLUR,194,473000,Outsourcing Maintenance of Parks Located at Secretariat Colony in Dn-194 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/31800,Road Cut,Completed,NQ-SHOZHINGANALLUR,199,870000,"RESTORATION OF ROADCUT BY USING M10 CONCRETE AT THANDUMARIAMMAN KOIL STREET,MUTHALAMMAN KOIL STREET IN DN 199,U44,Z15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/31802,Road Cut,Completed,NQ-SHOZHINGANALLUR,199,870000,"RESTORATION OF ROADCUT BY USING M10 CONCRETE AT MG RATHINAM STREET, JEEVARATHINAM STREET IN DN 199,U44,Z15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/31895,Buildings,Completed,NQ-SHOZHINGANALLUR,193,242000,"IMPROVEMENT TO THE EXISTING CORPORATION BUILDING AT KARPAGA VINAYAGA NAGAR 1ST MAIN ROAD IN DIV-193, U-45, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/31979,Buildings,Completed,NQ-SHOZHINGANALLUR,198,72000,"Improvements to the Existing Community Toilets & Painting for dust bins located DN 197,198 ,U-44, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/31986,Roads,Completed,NQ-SHOZHINGANALLUR,196,495000,"FORMING AND LAYING ROAD WITH GSB AND DUST AT PRARTHANA PARK IST AND 2ND STREET IN DN-196, Z-15",Own Sources,15,2015-16,2017-18 NQ/2015-16/32152,Buildings,Completed,NQ-SHOZHINGANALLUR,192,347000,"CONSTRUCTION OF DUSTBIN PLATFORM AT VARIOUS LOCATION AND VARIOUS DIVISION IN DN-192 & 197 , U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/32321,Buildings,Completed,NQ-SHOZHINGANALLUR,197,368000,"SUPPLYING STAINLESS STEEL AND AIR CONDITIONER FOR PARK E-SEVA, AUDITOR ROOM (ZONAL OFFICE INSIDE) AT RAJIV GANDHI SALAI IN DIV-197,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/32439,Roads,Completed,NQ-SHOZHINGANALLUR,195,690000,IMPROVEMENTS TO BRR FOOT PATH AT KANNAGI NAGAR IN DIV 195 UNIT 44 ZONE 15,Own Sources,15,2015-16,2016-17 NQ/2015-16/32512,Buildings,Completed,NQ-SHOZHINGANALLUR,193,132000,"PROVIDING MH DOOR TO THE EXISTING STORM WATER DRAIN AT MURUGESAN STREET IN DN-193, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/32539,Roads,Completed,NQ-SHOZHINGANALLUR,197,998000,"Providing and Laying GSB and WMM at Periyar Street,Ambedkar Street, Periyapalayathamman Koil Street and Vaithiyalingam Street in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/32653,Parks,Completed,NQ-SHOZHINGANALLUR,192,61000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT WORKERS ESTATE IN DIV-192, UNIT-44, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/3278,Parks,Completed,NQ-SHOZHINGANALLUR,194,561000,"OUTSOURCING MAINTENANCE OF PARK AT CHANDRASEKARAN AVENUE IN DN-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3280,Parks,Completed,NQ-SHOZHINGANALLUR,194,980000,"OUTSOURCING MAINTENANCE OF PARK AT SECRETARIAT COLONY IN DN-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3281,Parks,Completed,NQ-SHOZHINGANALLUR,194,400000,"OUTSOURCING MAINTENANCE OF PARK AT SAKTHI SRINIVASAN NAGAR AND P.T.C QUARTERS IN DN-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3285,Parks,Completed,NQ-SHOZHINGANALLUR,195,880000,"OUTSOURCING MAINTENANCE OF PARKS AT ANNAI INDIRA NAGAR, KANNAGI NAGAR 8th, 2nd MAIN ROAD, KANNAGI NAGAR 7th CROSS STREET IN DN-195, U-45, Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/3295,Parks,Completed,NQ-SHOZHINGANALLUR,192,184000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT WORKERS ESTATE IN DIV-192, UNIT-44, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/3304,Parks,Completed,NQ-SHOZHINGANALLUR,196,345000,"OUTSOURCING MAINTENANCE OF VGP PARK AT INJAMBAKKAM IN DIV-196, UNIT-44, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/33086,Roads,Completed,NQ-SHOZHINGANALLUR,197,62000,Outsourcing Maintenance of Parks Located at Neduncheliyan Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/3309,Parks,Completed,NQ-SHOZHINGANALLUR,200,415000,OUTSOURCING MAINTENENCE OF PARKS LOCATED AT CHEMMANCHERRY 1ST MAIN ROAD (TNSCB) IN DN-200 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/3350,Parks,Completed,NQ-SHOZHINGANALLUR,197,255000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT SHOLINGANALLUR DEVARAJ NAGAR IN DN-197,UNIT-45 ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3351,Parks,Completed,NQ-SHOZHINGANALLUR,197,133000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT CENTRAL AVENUE IN DN-197,UNIT-45 ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3352,Parks,Completed,NQ-SHOZHINGANALLUR,197,190000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT ELCOT SALAI IN DN-197,UNIT-45 ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3353,Parks,Completed,NQ-SHOZHINGANALLUR,197,640000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT RAJIV GANDHI SALAI (TECH-KI) IN DN-197,UNIT-45 ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3355,Parks,Completed,NQ-SHOZHINGANALLUR,197,187000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT NEDUNCHELIYAN STREET IN DN-197,UNIT-45 ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/33643,Parks,Completed,NQ-SHOZHINGANALLUR,196,125000,"OUTSOURCING MAINTENANCE OF VGP PARK AT INJAMBAKKAM IN DIV-196, UNIT-44, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/3367,Parks,Completed,NQ-SHOZHINGANALLUR,197,664000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT KUMARASAMY NAGAR IN DN-197,UNIT-45 ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3369,Parks,Completed,NQ-SHOZHINGANALLUR,200,94000,OUTSOURCING MAINTENENCE OF PARKS LOCATED AT CHEMMANCHERRY 33RD CROSS STREET (TNSCB) IN DN-200 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/33716,Buildings,Completed,NQ-SHOZHINGANALLUR,192,127000,"REPAIR WORKS TO TOILET AND PROVIDING CASUARINA POST FENCHING AT NEELANGARAI IN DIVISION 192 UNIT44, Z-15",Own Sources,15,2015-16,2017-18 NQ/2015-16/33753,Buildings,Completed,NQ-SHOZHINGANALLUR,192,186000,URGENT REPAIR WORKS TO SCHOOL AT KAPALEESWARAR NAGAR IN DIVISION 192 UNIT 44 ZONE 15,Own Sources,15,2015-16,2017-18 NQ/2015-16/33878,Parks,Completed,NQ-SHOZHINGANALLUR,195,452000,"OUTSOURCING MAINTENANCE OF PARKS AT ANNAI INDIRA NAGAR ,KANNAGI NAGAR 8th, 2nd MAIN ROAD, KANNAGI NAGAR 7th CROSS STREET IN DN-195,U-44,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/34453,Roads,Completed,NQ-SHOZHINGANALLUR,198,880000,"ATTENDING PATCH WORK USING BT AT TNHB C4 ROAD ,D34,D35 ROADS AT SHOLINGANALLUR TNHB LAYOUT IN DIV 198 U 44 Z15",Own Sources,15,2015-16,2017-18 NQ/2015-16/34753,Roads,Completed,NQ-SHOZHINGANALLUR,195,74000,"PROVIDING SPEED BREAKER WITH IRC SPECIFICATION THERMO PLASTIC PAINT AND STUDS AT KANNAGI NAGAR 6TH MAIN ROAD IN DN-195,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/3683,Parks,Completed,NQ-SHOZHINGANALLUR,193,534300,"OUTSOURCING MAINTENANCE OF PARK AT SAI NAGAR IN DIV-193,UNIT-44,ZONE-15 (9 MONTHS)",Own Sources,15,2015-16,2016-17 NQ/2015-16/3691,Parks,Completed,NQ-SHOZHINGANALLUR,193,95000,"OUTSOURCING MAINTENANCE OF PARK AT R.E NAGAR DIV-193,UNIT-44,ZONE-15 (9 MONTHS)",Own Sources,15,2015-16,2016-17 NQ/2015-16/3693,Parks,Completed,NQ-SHOZHINGANALLUR,193,798600,"OUTSOURCING MAINTENANCE OF PARK AI CUSTOMS COLONY IN DIVISION-193,UNIT-45,ZONE-15 (9 MONTHS)",Own Sources,15,2015-16,2016-17 NQ/2015-16/3735,Parks,Completed,NQ-SHOZHINGANALLUR,199,197000,"OUTSOURCING MAINTENANCE OF PARKS LOCATED AT VGP LAYOUT 1 - UTHANDI IN DN 199,U44,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/4234,Roads,Completed,NQ-SHOZHINGANALLUR,193,1529000,"PROVIDING PAVER BOLCK TO THE ANANTHA NAGAR MAIN ROAD ON BOTH SIDES IN DIV-193,U-45,ZONE-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/4237,Roads,Completed,NQ-SHOZHINGANALLUR,193,2998000,"PROVIDING PAVER BLOCK TO THE VINAYAGA NAGAR MAIN ROAD ON BOTH SIDES IN DIV-193,U-45,Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/4387,Buildings,Completed,NQ-SHOZHINGANALLUR,200,940000,Construction of Dress Changing Room and Toilet Room for Conservancy Labour at (Inside Division Office) Palathotta Salai in Dn-200 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/4742,Buildings,Completed,NQ-SHOZHINGANALLUR,192,1450000,"Improvement and repair works to Community hall at Chinna neelankari in division 192, Zone-XV",Own Sources,15,2015-16,2016-17 NQ/2015-16/6857,Roads,Completed,NQ-SHOZHINGANALLUR,199,775000,"IMPROVEMENTS TO CC ROAD BY ATTENDING PATCH WORK USING M15 CONCRETE IN MG RATHINAM STREET,JEEVARATHINAM STREET,VALLALAR STREET AND GANGAI AMMAN KOIL EAST&WEST STREET IN DN 199,U44 ,Z15",Own Sources,15,2015-16,2016-17 NQ/2015-16/7007,Roads,Completed,NQ-SHOZHINGANALLUR,196,688000,"FORMING THE ROAD WITH GSB AND QUARRY DUST AT I ST AVENUE 1ST CROSS STREET IN DIVISION 196,UNIT-44,ZONE15",Own Sources,15,2015-16,2016-17 NQ/2015-16/7645,Buildings,Completed,NQ-SHOZHINGANALLUR,192,1249000,"IMPROVEMENT OF BURIAL GROUND AT KABALEESWARAR NAGAR 4TH NORTH MAIN ROAD IN DIVISION 192, UNIT 44, ZONE 15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/7691,Roads,Completed,NQ-SHOZHINGANALLUR,196,820000,"IMPROVEMENTS TO ROADS BY USING GSB,DUST AT GOPINATH 2ND STREET,3RD STREET,4TH STREET,GOPINATH CROSS STREET IN DN-196 U-44 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/8367,Roads,Completed,NQ-SHOZHINGANALLUR,193,81000,"PROVIDING PAVER BLOCK TO THE EXISTING WARD-193 OFFICE CYCLE SHED IN WARD-193, UNIT-45, ZONE-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/8573,Roads,Completed,NQ-SHOZHINGANALLUR,196,575000,Forming and Laying of CC Road at cholan nagar in Dn-196 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/8581,Roads,Completed,NQ-SHOZHINGANALLUR,195,819000,"Forming and laying of BT road at KANNAGI NAGAR 3 adukku 22nd cross street by using paver finisher in Dn.195, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/8997,Buildings,Completed,NQ-SHOZHINGANALLUR,198,2900000,"IMPROVEMENTS AND DEVELOPING TO THE PONNIYAMMAN KOIL POND BY COUNSILOR FUND in Div-198,U-44,Z-15.",Own Sources,15,2015-16,2016-17 NQ/2015-16/9004,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,1281000,"Restoration of road cut made by CMWSSB at Parameswaran nagar 1st street and Annai indra nagar in Div-198,U-44,Z-15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/9021,Road Cut,Completed,NQ-SHOZHINGANALLUR,193,960000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KASTHURIBAI NAGAR 1ST MAIN ROAD,1ST STREET AND 2ND STREET IN DN-193 U-45 Z-15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/9025,Road Cut,Completed,NQ-SHOZHINGANALLUR,193,968000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KASTHURIBAI NAGAR 3RD,4TH,5TH,6TH,7TH,8TH AND 9TH STREET IN DN-193 U-45 Z-15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/9030,Road Cut,Completed,NQ-SHOZHINGANALLUR,196,995000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KASTHURIBAI NAGAR 10TH,11TH,12TH,13TH,14TH,15TH,16TH STREET AND 1ST,2ND,3RD,4TH,5TH,6TH LANE IN DN-193 U-45 Z-15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/9034,Road Cut,Completed,NQ-SHOZHINGANALLUR,193,605000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KASTHURIBAI NAGAR 1ST,2ND,3RD AND 4TH CROSS STREET IN DN-193 U-45 Z-15",Deposit Works,15,2015-16,2016-17 NQ/2015-16/9413,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,2930000,"Construcion of Side Drain at Mount Batten4th Cross Street, Sulaima Nagar 2nd Cross Street, Sulaima Nagar Link Street, Sulaima Nagar 3rd Cross Street, Krishna Nagar Arul Avenue in Dn-194, U-45, Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/9893,Roads,Completed,NQ-SHOZHINGANALLUR,197,872000,Forming and Laying of BT Road With Using Paver Finisher at Village High Road 25th Cross Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/9898,Roads,Completed,NQ-SHOZHINGANALLUR,197,1692000,Forming and Laying of BT Road With Using Paver Finisher at Bharathidasan Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/9900,Roads,Completed,NQ-SHOZHINGANALLUR,197,922000,Providing and Laying CC Road at School 2nd Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/9901,Roads,Completed,NQ-SHOZHINGANALLUR,197,4048000,Forming and Laying of BT Road With Using Paver Finisher at Sadagoban Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/9902,Roads,Completed,NQ-SHOZHINGANALLUR,197,5331000,"Forming and Laying of BT Road With Using Paver Finisher at Ezhil Nagar 1st, 2nd, & 3rd Street in Dn-197 U-45 Z-15",Own Sources,15,2015-16,2016-17 NQ/2015-16/9903,Roads,Completed,NQ-SHOZHINGANALLUR,197,3093000,Forming and Laying of BT Road With Using Paver Finisher at Devaraj Nagar 2nd Main Road in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/9904,Roads,Completed,NQ-SHOZHINGANALLUR,197,2959000,Forming and Laying of BT Road With Using Paver Finisher at Ekambaram Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/9905,Roads,Completed,NQ-SHOZHINGANALLUR,197,2959000,Forming and Laying of BT Road With Using Paver Finisher at Ganesh Nagar 2nd & 3rd Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 NQ/2015-16/9906,Roads,Completed,NQ-SHOZHINGANALLUR,197,5774000,Forming and Laying of BT Road With Using Paver Finisher at Kaliamman koil Street in Dn-197 U-45 Z-15,Own Sources,15,2015-16,2016-17 P/2015-16/16759,Parks,Completed,P-Parks and Playfields,101,3200000,"Providing Package Sewage Treatment Plant Including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at Bougainvillea Park, Anna Nagar in Dn-101, Zone - VIII",Own Sources,8,2015-16,2017-18 P/2015-16/16761,Parks,Completed,P-Parks and Playfields,74,4950000,"Providing Packaged Sewage Treatment Plant including Supply,Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at Otteri Herbal Park in Dn-74, Zone - VI.",Own Sources,6,2015-16,2017-18 P/2015-16/35027,Playfields,Completed,P-Parks and Playfields,137,9000000,"IMPROVEMENTS TO THE EXISTING PLAY GROUND AT ERIKKARAI ROAD ,NESAPPAKKAM IN DN-137,ZONE-10.",Own Sources,10,2015-16,2019-20 Q/2015-16/29416,Buildings,Completed,Q-Solid Waste Management,72,17938000,"Installation of Bio Methanisation plant of 5 MTPD of 2 units at Pulianthope Slaughter house in Dn 72, zone VI ?Using BARC tech (NISARGRUNA TECHNOLOGY)",Own Sources,6,2015-16,2018-19 RC/2015-16/1613,Buildings,Completed,P-Parks and Playfields,77,2800000,"PROPOSED DEVELOPMENT AND BEAUTIFICATION OF BASIN BRIDGE ROAD PARK,DN-77,ZONE-6",Own Sources,6,2015-16,2019-20 RC/2015-16/31676,Electrical,Completed,P-Parks and Playfields,99,942100,"Provision of 20 nos 6 mtr lamp post with 1 mtr stright bracket and 20 nos of 40w to 50w LED fitting at J Block Park and 15 th main road parkin div -99,zone-VIII",Own Sources,8,2015-16,2019-20 RC/2015-16/5125,Parks,Completed,P-Parks and Playfields,83,23673372,"CREATION OF NEW PARK AT THAMARAIKULAM, (ENTRANCE ARCH,WALKWAY PERGOLAS,TOILET BLOCK,YOGA STAGE-PYRAMID,WATER FOUNTAIN,COMPOST PIT,RAIN WATER HARVESTING)KORATTUR IN D-83,ZONE - VII",Own Sources,7,2015-16,2018-19 RC/2015-16/5834,Parks,Completed,P-Parks and Playfields,92,15439000,"IMPROVEMENTS TO THE PARK AT E.B.ROAD,MUGAPPAIR EAST IN DN-92,UNIT-20,ZONE-7.",Own Sources,7,2015-16,2018-19 RN/2015-16/0666,Parks,Completed,P-Parks and Playfields,N01,3998000,"FORMATION OF PATHWAY, CONSTRUCTION OF GAZEBO, GREENERY WORKS AND OTHER IMPROVEMENT WORKS TO THE EXISTING PARK AT KRISHNA NAGAR IN DN-28, ZONE - III.",Own Sources,,2015-16,2017-18 RN/2015-16/8954,Parks,Completed,P-Parks and Playfields,18,14300000,"PROPOSED CONSTRUCTION OF PARK CPCL LAYOUT IN DN. 18, ZONE - 2",Own Sources,2,2015-16,2018-19 RN/2015-16/9493,Parks,Completed,P-Parks and Playfields,N01,7802625,"PROPOSED CONSTRUCTION OF PARK AT ANDARKUPPAM, REDHILLS ROAD IN DN. 18, ZONE - 2",Own Sources,,2015-16,2019-20 RS/2015-16/0411,Playfields,Completed,RS-Regional office - South,167,4965000,PROVIDING OF LITE ROOFING FOR SKATING FIELD AT HINDU COLONY IN DIVISION-167 ZONE-12,Own Sources,12,2015-16,2016-17 RS/2015-16/13378,Parks,Completed,P-Parks and Playfields,193,4260000,PROVIDING LIGHTING ARRANGEMENTS GREENEARY SITTING BENCH AND WATCHMEN SHED IN ANANDANAGAR PARK AT THURAIPAKKAM IN DIVISION 193 ZONE 15,Own Sources,15,2015-16,2017-18 RS/2015-16/13861,Electrical,Completed,RS-Regional office - South,186,980300,"Additional cable laying of 142 mtr 4x25 sqmm cable,776mtr 3 1/2 x120 sqmm cable and 2nos supply & erection of kiosk pillar box at perungudi dumping ground in div 186, Zone-XIV",Own Sources,14,2015-16,2016-17 RS/2015-16/13866,Electrical,Completed,RS-Regional office - South,186,741300,"Additional cable laying of 476mtr 3 1/2 x120 sqmm cable and Cement concrete fencing around 4nos of High mast at perungudi dumping ground in div 186, Zone-XIV",Own Sources,14,2015-16,2016-17 RS/2015-16/14211,Parks,Completed,P-Parks and Playfields,179,3800000,PROVIDING COMPOUND WALL AND WALK WAY IN THE O.S.R LAND BATHEL AVENUE MAIN ROAD IN DIV -179 U.39 ZONE 13,Own Sources,13,2015-16,2019-20 RS/2015-16/14896,Parks,Completed,P-Parks and Playfields,156,6105601,PROPOSED PARK AT SABARI NAGER CHENNAI DIV 156 ZONE 12,Own Sources,12,2015-16,2018-19 RS/2015-16/14903,Parks,Completed,P-Parks and Playfields,198,4910000,PROPOSED PARK AT TNHB OSR LAND CHENNAI Z-15 DIV-198,Own Sources,15,2015-16,2018-19 RS/2015-16/1494,Buildings,Completed,Q-Solid Waste Management,186,2299000,"PROVIDING SUMP WORK IN PERUNGUDI DUMPING YARD AT CORPORATION ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2015-16,2017-18 RS/2015-16/15100,Parks,Completed,P-Parks and Playfields,169,4999500,PROPOSED PARK AT OSR SITE BALAJI NAGAR- 31 ST STREET IN DIV -169 Z- 14,Own Sources,14,2015-16,2017-18 RS/2015-16/16728,Parks,Completed,P-Parks and Playfields,173,2075000,PROVIDING PATHWAY INSIDE THE PLAY GROUND AT RK MUTT ROAD IN DIV -173 Z-13,Own Sources,13,2015-16,2017-18 RS/2015-16/3043,Electrical,Completed,RS-Regional office - South,186,997000,"Supply and Laying of additional cable laying of 800mtr 4x25 sqmm,975mtr 3 1/2 x120 sqmm ,6nos of bus bar pillar box at perungudi dumping ground in div 186, Zone-XIV",Own Sources,14,2015-16,2016-17 RS/2015-16/3152,Parks,Completed,P-Parks and Playfields,143,8492000,"Proposed Development of Park at Nolambur Phase I, 9th Main Road, Dn - 143, Zone - 11",Own Sources,11,2015-16,2017-18 RS/2015-16/32050,Buildings,Completed,RS-Regional office - South,186,993400,"Repair and Maintenance for Compound wall in South side at Perungudi dumping ground in div-186,UNIT-41,ZONE-14",Own Sources,14,2015-16,2016-17 RS/2015-16/3237,Parks,Completed,P-Parks and Playfields,143,10645000,"Proposed Construction of Park at Nolambur, Phase - 2, 7th Cross Street, Dn - 143, Zone - 11 - Part - 1",Own Sources,11,2015-16,2017-18 RS/2015-16/3419,Parks,Completed,P-Parks and Playfields,198,15690000,"Proposed construction of Park at TNHB Site, Zone XV, Dn - 198 - Part 1",Own Sources,15,2015-16,2019-20 RS/2015-16/3718,Parks,Completed,P-Parks and Playfields,184,13000000,Construction of Compound wall around the OSR land near Faery Estate private limited at Anna Nedunsalai in Div -184 Zone-14,Own Sources,14,2015-16,2019-20 RS/2015-16/3868,Parks,Completed,P-Parks and Playfields,193,4995000,PROVIDING COMPOUND WALL AROUND ANANDA NAGAR PARK WITH SHUTTLE CORK COURT PATH WAY TOILET AND SUMP IN DN193 ZONE15 AT ANANDA NAGAR MAIN ROAD,Own Sources,15,2015-16,2017-18 RS/2015-16/4098,Parks,Completed,P-Parks and Playfields,198,14300700,"Proposed construction of Park at TNHB Site, Zone XV, Dn - 198 - Part 2",MPLADS,15,2015-16,2019-20 RS/2015-16/4178,Parks,Completed,P-Parks and Playfields,156,17635000,"Proposed Development of Park at Nathamuni Street, Thiruvalluvar Nagar Park, Dn 156, Z 12",Own Sources,12,2015-16,2017-18 RS/2015-16/4468,Parks,Completed,P-Parks and Playfields,191,5924000,"PROVIDING WALKWAY, TENNIS COURT,YOGA STAGE AND SCATTING COURT AT JAYACHANDRAN NAGAR 1ST MAINROAD IN DN-191,UNIT-43, ZONE-14",Own Sources,14,2015-16,2019-20 RS/2015-16/4700,Parks,Completed,P-Parks and Playfields,184,10867000,"PROVIDING PATHWAY, WATER SUPPLY ARRANGEMENT ELECTRICAL ARRANGEMENT,GREENEARY,CHILDRAN PLAY FIELD,AND SCATTING COURT FOR OSR LAND[GIVEN BY FAERY ESTATED] AT ANNA NEDUNCHALAI IN DN-184,UNIT-41,ZONE-14",Own Sources,14,2015-16,2019-20 RS/2015-16/4767,Parks,Completed,P-Parks and Playfields,193,4990000,"PROVIDING COMPOUNDWALL AND ,PATHWAY IN BALAMURAGAN GARDEN 3rdMAIN ROAD PARK AT THURAIPAKKAM IN DN193 ZONE15",Own Sources,15,2015-16,2019-20 RS/2015-16/4778,Parks,Completed,P-Parks and Playfields,184,12589000,"PROVIDING PARK WITH, PATH WAY, GREENARY,COMPOUND WALL,ELECTRICAL AND WATER SUPPLY ARRANGEMENTS (O.S.R.LAND RS NO 36/15)AT ANNA NEDUNCHALAI IN DN-184, UNIT-41, ZONE-14",Own Sources,14,2015-16,2018-19 RS/2015-16/4808,Parks,Completed,P-Parks and Playfields,193,4145164,"PROVIDING WATERSUPPLY ARRANGEMENT ,LIGHTING ARRANGEMENT ,SHUTTLE COCK COURT, AND GREENARY FOR BALAMURUGAN GARDEN 3rd MAIN ROAD PARK AT THURAIPAKKAM IN DN193 ZONE15",Own Sources,15,2015-16,2019-20 RS/2015-16/8669,Parks,Completed,P-Parks and Playfields,191,5995000,"Construction of compound wall around OSR land at Jayachandran Nagar, 1st Main Road in Div 191; U-43; Z-14",Own Sources,14,2015-16,2019-20 SP/2015-16/3069,Footpath,Completed,SP-SPECIAL PROJECTS,N13,15199000,"PROPOSED CONSTRUCTION OF FOOTPATH AT RADHAKRISHNAN NAGAR MAIN ROAD FROM MALAVIKA AVENUE 3RD STREET IN DIV-181,ZONE-13.",Own Sources,,2015-16,2016-17 SP/2015-16/3070,Footpath,Completed,SP-SPECIAL PROJECTS,9,56500000,"DEVELOPMENT OF PEDESTRIAN WAY AROUND MYLAPORE TEMPLE TANK AND STREETS IN DIV-124, ZONE-9.",Own Sources,1,2015-16,2017-18 SP/2015-16/3078,Roads,Completed,SP-SPECIAL PROJECTS,N13,10380000,"STRENGTHENING OF THE ROAD WITH DBM AND BCCMP AT RADHAKRISHNAN NAGAR MAIN ROAD FROM MALAVIKA AVENUE IN DIV-181,ZONE-13.",Own Sources,,2015-16,2016-17 L/2016-17/18144,Electrical,Completed,L-Electrical,1,2221300,"Removal and Re-fixing of 520 nos. of damaged street lamp posts due to Vardah Cyclone in various locations in divisions 1 to 14, Zone-1 Thiruvottriyur",Own Sources,1,2016-17,2017-18 L/2016-17/18663,Electrical,Completed,L-Electrical,1,399500,"Removal and refixing , Replacement of accessories and maintaince work for 16MTR High Mast at the junction of thazankuppam market & Bus stand area in division 1, Zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/11036,Roads,Completed,NA-THIRUVOTTIYUR,1,898000,"STRENGTHING AND RELAYING BT ROAD BY PAVER FINISHER AT THIRUVALLUVAR NAGAR 1ST STREET IN DN-01,UNIT-01,ZONE-01.",Own Sources,1,2016-17,2016-17 NA/2016-17/11043,Roads,Completed,NA-THIRUVOTTIYUR,1,1286000,"STRENGTHING AND RELAYING BT ROAD BY PAVER FINISHER AT ENNOREKUPPAM 1ST STREET IN DN-01,UNIT-01,ZONE-01.",Own Sources,1,2016-17,2016-17 NA/2016-17/11086,Roads,Completed,NA-THIRUVOTTIYUR,1,4800000,"LAYING CEMENT CONCRETE ROAD AT SATHIYAVANI MUTHU NAGAR 2ND MAIN ROAD IN DN-01,UNIT-01,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/1543,Buildings,Completed,NA-THIRUVOTTIYUR,1,995000,"CONSTRUCTION OF AMMA UNAVAGAM ( PHASE 2 ) AT J.J. NAGAR IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2016-17,2016-17 NA/2016-17/16760,Buildings,Completed,NA-THIRUVOTTIYUR,1,28000,"REPAIR AND IMPROVEMENTS TO AMMA UNAVAGAM AT K.H.ROAD IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2016-17,2017-18 NA/2016-17/16761,Buildings,Completed,NA-THIRUVOTTIYUR,1,65000,"REPAIR AND IMPROVEMENTS TO CPS AT MUGATHUVARAKUPPAM & ENNOREKUPPAM IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2016-17,2017-18 NA/2016-17/16827,Buildings,Completed,NA-THIRUVOTTIYUR,1,204000,"Re-construction of Angan vadi at S,P.Koil street, and Unit office and periyar nagar Amma unnavagam in Dn-8,Unit-2,Zone-I.",Own Sources,1,2016-17,2017-18 NA/2016-17/6834,Buildings,Completed,NA-THIRUVOTTIYUR,1,435000,"Maintenance To Chennai Primary School (cps) at Annai sivagami Nagar in DN-3, Unit-1, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/9114,Buildings,Completed,NA-THIRUVOTTIYUR,1,945000,"CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENTS TO AMMA UNAVAGAM AT J.J. NAGAR IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2016-17,2018-19 NA/2016-17/9116,Buildings,Completed,NA-THIRUVOTTIYUR,1,710000,"REPAIR AND IMPROVEMENTS TO THALANKUPPAM ANGANWADI IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2016-17,2018-19 NA/2016-17/9119,Buildings,Completed,NA-THIRUVOTTIYUR,1,400000,"IMPROVEMENTS TO ANGANWADI BUILDING AT MUGATHUVARAKUPPAM IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2016-17,2017-18 NA/2016-17/9120,Buildings,Completed,NA-THIRUVOTTIYUR,1,304000,"REPAIR AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT NETTUKUPPAM, THALANKUPPAM, S.V.M. NAGAR AND J.J. NAGAR IN DN - 01, UNIT - 01, ZONE - 01.",Own Sources,1,2016-17,2017-18 NA/2016-17/9122,Buildings,Completed,NA-THIRUVOTTIYUR,1,80000,"REPAIR AND IMPROVEMENTS TO NETTUKUPPAM MIDDLE SCHOOL IN DN-01, UNIT-01, ZONE-01.",Own Sources,1,2016-17,2017-18 L/2016-17/13793,Electrical,Completed,L-Electrical,2,381000,Installation and Erection of 8 nos. of new KIOSK Pillars and 3 Phase Analogue Timers and raising of existing 14 nos. KIOSK pillars in higher elevated level from ground level in various divisions in Zone-I,Own Sources,1,2016-17,2017-18 NA/2016-17/0024,Buildings,Completed,NA-THIRUVOTTIYUR,2,164000,"Improvement and Painting works in C.M.S at K.H.road in Div-2, Unit-1, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/0544,Buildings,Completed,NA-THIRUVOTTIYUR,2,147000,"Providing Segregation Room at K.H ROAD in Div-2,Unit-1,Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/13031,Buildings,Completed,NA-THIRUVOTTIYUR,2,110000,"Repair and improvement work at Periya kuppam public convaniance and Nehru nagar CMS in Div-2, Unit-1, Zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14368,Buildings,Completed,NA-THIRUVOTTIYUR,2,176000,"Repair and improvement works in various location of public conveniance at Periyakuppam (3 Nos) and Chinnakuppam (2 nos) in Dn-2, U-1, Z-1",Own Sources,1,2016-17,2018-19 NA/2016-17/14376,Buildings,Completed,NA-THIRUVOTTIYUR,2,159000,"Repair and Improvement Works in Various Location of Public convenience at Anna Nagar, Sasthiri Nagar and Nehru Nagar, K.H.Road, Valluvar nagar, Sweeper colony (6 Nos) in Dn-2, Unit-1, Zone-1",Own Sources,1,2016-17,2018-19 NA/2016-17/14382,Buildings,Completed,NA-THIRUVOTTIYUR,2,170000,"Repair and Improvement Works in various Location of Public Convenience at South Lock Road, Kamalammal Nagar, Kattu Kuppam and M.G.R.Nagar (5 Nos) in Div-2, Unit-1, Zone-1",Own Sources,1,2016-17,2018-19 NA/2016-17/14389,Buildings,Completed,NA-THIRUVOTTIYUR,2,441000,",Forming, Strenthening and Re laying B,T,road by paver finisher at Kattukuppam Bajanai koil street (110M-W-4.00)in Div-2,Unit-1,Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/14468,Roads,Completed,NA-THIRUVOTTIYUR,2,390000,"Forming, Strenthening and Re laying BT road by paver finisher at Kattukuppam main road (L-100M, W-4M) in Div-2, Unit-1, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/14473,Roads,Completed,NA-THIRUVOTTIYUR,2,1568000,"LAYING THE CEMENT CONCRETE ROAD AT ULAGATHAMMAN KOIL STREET(M.150.W.6.00) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14477,Roads,Completed,NA-THIRUVOTTIYUR,2,835000,"LAYING THE CEMENT CONCRETE ROAD AT ELLAYAMMAN KOIL BACK SIDE STREET(M.160.W-3.00) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14478,Roads,Completed,NA-THIRUVOTTIYUR,2,426000,"LAYING THE CEMENT CONCRETE ROAD AT THADAVAKARA KUPPAM(M.70,W.3.50) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14484,Roads,Completed,NA-THIRUVOTTIYUR,2,607000,"LAYING THE CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR(M.100.W3.50) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14488,Roads,Completed,NA-THIRUVOTTIYUR,2,273000,"LAYING THE CEMENT CONCRETE ROAD AT SWEEPERS COLONY 1ST STREET(M.55.W.3) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14489,Roads,Completed,NA-THIRUVOTTIYUR,2,467000,"LAYING THE CEMENT CONCRETE ROAD AT BATHRAKALIYAMMAN NAGAR 3RD STREET(M.94.W.3) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14490,Roads,Completed,NA-THIRUVOTTIYUR,2,298000,"LAYING THE CEMENT CONCRETE ROAD AT BATHRAKALIYAMMAN NAGAR 2ND STREET(M.60,W.3) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14492,Roads,Completed,NA-THIRUVOTTIYUR,2,345000,"LAYING THE CEMENT CONCRETE ROAD AT BATHRAKALIYAMMAN NAGAR MAIN STREET (L-52 m, W-4 m) IN DIVISION-2, UNIT-1, ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14493,Roads,Completed,NA-THIRUVOTTIYUR,2,493000,"LAYI NG THE CEMENT CONCRETE ROAD AT BATHRAKALIYAMMAN NAGAR 1ST STREET(M.85,W.3.50) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14494,Roads,Completed,NA-THIRUVOTTIYUR,2,497000,"LAYING THE CEMENT CONCRETE ROAD AT RAMAMURTHY NAGAR 2ND STREET(M.100,W.3.00) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14495,Roads,Completed,NA-THIRUVOTTIYUR,2,422000,"LAYING THE CEMENT CONCRETE ROAD AT RAMAMURTHY NAGAR 1ST STREET(M.85,W.3.00) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14496,Roads,Completed,NA-THIRUVOTTIYUR,2,556000,"LAYING THE CEMENT CONCRETE ROAD AT THILAGAR NAGAR 5TH CROSS STREET(M.112,W.3.00) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14497,Roads,Completed,NA-THIRUVOTTIYUR,2,189000,"LAYI NG THE CEMENT CONCRETE ROAD AT THILKAR NAGAR 1ST STREET(M.38,W.3.00) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14515,Roads,Completed,NA-THIRUVOTTIYUR,2,149000,"LAYI NG THE CEMENT CONCRETE ROAD AT KAMALAMMAL NAGAR 1ST STREET(M-36.00-W.2.50) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14516,Roads,Completed,NA-THIRUVOTTIYUR,2,345000,"LAYING THE CEMENT CONCRETE ROAD AT INDRA NAGAR 1ST STREET(L-52, W-4.00) IN DIVISION-2, UNIT-1, ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14517,Roads,Completed,NA-THIRUVOTTIYUR,2,849000,"LAYI NG THE CEMENT CONCRETE ROAD AT THILAGAR NAGAR MAIN ROAD(M-171,W-3.00) IN DIVISION-2,UNIT-1,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14518,Roads,Completed,NA-THIRUVOTTIYUR,2,482000,"LAYING THE CEMENT CONCRETE ROAD AT THILAGAR NAGAR 3RD STREET (L-97.00 M, W-3.00)IN DIVISION-2, UNIT-1, ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14519,Roads,Completed,NA-THIRUVOTTIYUR,2,522000,"LAYING THE CEMENT CONCRETE ROAD AT THILAGAR NAGAR 2ND STREET (L-105 M, W-3.00)IN DIVISION-2, UNIT-1, ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/15534,Roads,Completed,NA-THIRUVOTTIYUR,2,987000,"LAYING OF CEMENT CONCRETE ROAD AT SATHYAMOORTHY NAGAR 6TH STREET IN DIVISION-6, UNIT-2, ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/1562,Roads,Completed,NA-THIRUVOTTIYUR,2,777000,"Providing street name boards at chinnakuppam, periya kuppam, Nehru nagar, Indra nagar and Kamalammal nagar (28 nos) in D-2, U-1, Z-1",Own Sources,1,2016-17,2018-19 NA/2016-17/16970,Buildings,Completed,NA-THIRUVOTTIYUR,2,120000,"Repairing and Providing Compound wall at Sastri nagar burial ground in Div-2,U-1,Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16972,Buildings,Completed,NA-THIRUVOTTIYUR,2,250000,"Providing Roof Asbestos sheet,False ceiling Electrical work and motor repair work at Unit office in D-2,U-1,Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16976,Buildings,Completed,NA-THIRUVOTTIYUR,2,80000,"Repair works at Periyakuppam(CPS) and K.H.Road (CMS) Schools in Div-2, U-1, Z-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16979,Buildings,Completed,NA-THIRUVOTTIYUR,2,60000,"Repairing work at Periyakuppam Public Convineance in DIV-2, U-1, Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16981,Buildings,Completed,NA-THIRUVOTTIYUR,2,70000,"Repairing works at Chinnakuppam public convenance in Div-2,U-1.Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16983,Buildings,Completed,NA-THIRUVOTTIYUR,2,75000,"Repairing works at K.H.Road amma unavagam in Div-2, U-1, Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/3124,Buildings,Completed,NA-THIRUVOTTIYUR,2,264000,"Additional Works in chinna kuppam Public Convenience at Karumariamman koil street in Div-2, Unit-1,Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/4638,Buildings,Completed,NA-THIRUVOTTIYUR,2,329000,Additional works in AMMA UNAVAGAM-2 at Village streets in D-2.U-1.Z-1.,Own Sources,1,2016-17,2016-17 NA/2016-17/8676,Buildings,Completed,NA-THIRUVOTTIYUR,2,339000,"Maintanance works to Public conveinance at valluvar nagar m,g,r,nagar,Zion nagar,kamalammal nagar,Periya kuppam (CPS) Nehru Nagar (CMS)etc in D-2,U-1.Z-1",Own Sources,1,2016-17,2016-17 P/2016-17/19503,Parks,Completed,P-Parks and Playfields,2,3816000,"FORMATION OF NEW PARK AT THALLANKUPPAM SLUM BOARD QUARTERS, KATHIVAKKAM HIGH ROAD, ENNORE IN DN-1, ZONE - I",Grants,1,2016-17,2018-19 L/2016-17/12885,Electrical,Completed,L-Electrical,3,1116000,Provision of 25 nos of 6 mtr GI lamp mpost with single bracket with 40 w LED fittings at TNSCB RC- north Dn 3 etc in div-3 zone-1 (sor 2015-16),Deposit Works,1,2016-17,2017-18 L/2016-17/9475,Electrical,Completed,L-Electrical,3,3357000,Renovation work of 79 nos 8/9 mtr lamp post converted into 6 mtr lamp post with Double bracket and provision of 8 nos. of new 6 mtr G.I lamp post with Double Bracket with 40w LED fittings,Own Sources,1,2016-17,2016-17 NA/2016-17/12601,Roads,Completed,NA-THIRUVOTTIYUR,3,2182000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 4th STREET IN DIVISION-03, UNIT-01, ZONE-01.(L-510m, B-4.5m, Area- 2295 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12603,Roads,Completed,NA-THIRUVOTTIYUR,3,2250000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 5th STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 525m, B- 4.5m, Area - 2362sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12604,Roads,Completed,NA-THIRUVOTTIYUR,3,2166000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 6th STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 507m, B- 4.5m, Area - 2282sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12605,Roads,Completed,NA-THIRUVOTTIYUR,3,2250000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 7th STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 528m, B- 4.5m, Area - 2376sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12607,Roads,Completed,NA-THIRUVOTTIYUR,3,2250000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 8th STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 528m, B- 4.5m, Area - 2376sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12608,Roads,Completed,NA-THIRUVOTTIYUR,3,2146000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 10th STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 500m, B- 4.5m, Area - 2250sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12610,Roads,Completed,NA-THIRUVOTTIYUR,3,1635000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR CROSS STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 380m, B- 4.5m, Area - 1710sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12611,Roads,Completed,NA-THIRUVOTTIYUR,3,1500000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR MARKET STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 375m, B- 4.2m, Area - 1575sqm)",Own Sources,1,2016-17,2017-18 NA/2016-17/12612,Roads,Completed,NA-THIRUVOTTIYUR,3,629000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ TSUNAMI QUARTERS MAIN ROAD 01 IN DIVISION-03, UNIT-01, ZONE-01.(L- 105m, B-7m, Area - 735 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12614,Roads,Completed,NA-THIRUVOTTIYUR,3,661000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ TSUNAMI QUARTERS MAIN ROAD 04 IN DIVISION-03, UNIT-01, ZONE-01.(L- 110m, B-7m, Area - 770 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12616,Roads,Completed,NA-THIRUVOTTIYUR,3,1009000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ TSUNAMI QUARTERS MAIN ROAD 05 IN DIVISION-03, UNIT-01, ZONE-01.(L- 168m, B-7m, Area - 1176 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12617,Roads,Completed,NA-THIRUVOTTIYUR,3,629000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ TSUNAMI QUARTERS MAIN ROAD 06 IN DIVISION-03, UNIT-01, ZONE-01.(L- 204m, B-3.7m, Area - 755 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12618,Roads,Completed,NA-THIRUVOTTIYUR,3,661000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ TSUNAMI QUARTERS MAIN ROAD 08 IN DIVISION-03, UNIT-01, ZONE-01.(L- 215m, B-3.7m, Area - 796 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12619,Roads,Completed,NA-THIRUVOTTIYUR,3,652000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ TSUNAMI QUARTERS MAIN ROAD 09 IN DIVISION-03, UNIT-01, ZONE-01.(L- 210m, B-3.7m, Area - 777 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12622,Roads,Completed,NA-THIRUVOTTIYUR,3,827000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ TSUNAMI QUARTERS CROSS ROAD 23 & APPROACH ROAD 02 IN DIVISION-03, UNIT-01, ZONE-01.(L- 267m, B-3.7m, Area - 988 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12623,Roads,Completed,NA-THIRUVOTTIYUR,3,747000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 1ST STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 300m, B-3 m, Area - 900 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12628,Roads,Completed,NA-THIRUVOTTIYUR,3,674000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 2ND STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 200m, B-4 m, Area - 800 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12630,Roads,Completed,NA-THIRUVOTTIYUR,3,674000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 3RD STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 200m, B-4 m, Area - 800 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12631,Roads,Completed,NA-THIRUVOTTIYUR,3,674000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 4TH STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 200m, B-4 m, Area - 800 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12632,Roads,Completed,NA-THIRUVOTTIYUR,3,674000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 5TH STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 200m, B-4 m, Area - 800 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12634,Roads,Completed,NA-THIRUVOTTIYUR,3,524000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 1ST CROSS STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 153m, B-4 m, Area - 612 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12635,Roads,Completed,NA-THIRUVOTTIYUR,3,399000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 2ND CROSS STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 102m, B-4.5 m, Area - 459 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12636,Roads,Completed,NA-THIRUVOTTIYUR,3,399000,"FORMING, STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ KVK KUPPAM 3RD CROSS STREET IN DIVISION-03, UNIT-01, ZONE-01.(L- 103m, B-4.5 m, Area - 464 sqm)",Own Sources,1,2016-17,2016-17 NA/2016-17/12638,Roads,Completed,NA-THIRUVOTTIYUR,3,1295000,"FORMING AND STRENGTHENING THE CEMENT CONCRETE ROAD AT J.J.NAGAR 1ST STREET IN DIVISION-3, UNIT-1, ZONE-1(L-160M, B-4M, AREA - 640 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/12639,Roads,Completed,NA-THIRUVOTTIYUR,3,1295000,"FORMING AND STRENGTHENING THE CEMENT CONCRETE ROAD AT J.J.NAGAR 2ND STREET IN DIVISION-3, UNIT-1, ZONE-1(L-160M, B-4M, AREA - 640 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/12640,Roads,Completed,NA-THIRUVOTTIYUR,3,1295000,"FORMING AND STRENGTHENING THE CEMENT CONCRETE ROAD AT J.J.NAGAR 3RD STREET IN DIVISION-3, UNIT-1, ZONE-1(L-160M, B-4M, AREA - 640 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/12641,Roads,Completed,NA-THIRUVOTTIYUR,3,1295000,"FORMING AND STRENGTHENING THE CEMENT CONCRETE ROAD AT J.J.NAGAR 4TH STREET IN DIVISION-3, UNIT-1, ZONE-1(L-160M, B-4M, AREA - 640 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/12642,Roads,Completed,NA-THIRUVOTTIYUR,3,1295000,"FORMING AND STRENGTHENING THE CEMENT CONCRETE ROAD AT J.J.NAGAR 5TH STREET IN DIVISION-3, UNIT-1, ZONE-1(L-160M, B-4M, AREA - 640 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/12643,Roads,Completed,NA-THIRUVOTTIYUR,3,1700000,"FORMING AND STRENGTHENING THE CEMENT CONCRETE ROAD AT J.J.NAGAR 1ST & 2ND CROSS STREET IN DIVISION-3, UNIT-1, ZONE-1(L-210M, B-4M, AREA - 840 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/13245,Buildings,Completed,NA-THIRUVOTTIYUR,3,327000,"Improvements to pubic convenience in Etps colony (Near kathivakkam Railway station) at D-3, U-1, Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/14756,Buildings,Completed,NA-THIRUVOTTIYUR,3,774000,"Imporvemnets to amma unavagam phase 2 at nethaji nagar in div-3, unit,1, zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/1630,Roads,Completed,NA-THIRUVOTTIYUR,3,420000,"providing Street name boards at various streets in Div-3,Un-1,Z-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16977,Buildings,Completed,NA-THIRUVOTTIYUR,3,182000,"Additional work to Amma Unavagam phase 2 at nethaji nagar in Division 3, Unit-1, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/17473,Roads,Completed,NA-THIRUVOTTIYUR,3,2250000,"STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING AT ALL INDIA RADIO NAGAR RAILWAY BORDER ROAD IN DIVISION-03, UNIT-01,ZONE-01. (LENGTH - 320 M, AREA - 2000 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/17474,Roads,Completed,NA-THIRUVOTTIYUR,3,1155000,"STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING AT PERIYA KASI KOIL KUPPAM MAIN ROAD IN DIVISION-03, UNIT-01,ZONE-01.(LENGTH-340 M, AREA-1530 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/17478,Roads,Completed,NA-THIRUVOTTIYUR,3,452000,"STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING AT TSUNAMI QUARTERS 1ST MAIN ROAD IN DIVISION-03, UNIT-01,ZONE-01.(LENGTH - 100 M, AREA - 700 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/17481,Roads,Completed,NA-THIRUVOTTIYUR,3,452000,"STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING AT TSUNAMI QUARTERS 5TH MAIN ROAD IN DIVISION-03, UNIT-01,ZONE-01.(LENGTH - 100 M, AREA - 700 SQM)",Own Sources,1,2016-17,2017-18 NA/2016-17/6827,Buildings,Completed,NA-THIRUVOTTIYUR,3,290000,"Maintenance to Chennai Primary School at Kasi Koil Kuppam in DN-3, UNIT-1, ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/7149,Buildings,Completed,NA-THIRUVOTTIYUR,3,995000,"NEW CONSTRUCTION OF AMMA UNAVAGAM AT ENNORE EXPRESS ROAD NEAR NETHAJI NAGAR IN DIV-03, UNIT-1, ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/8664,Roads,Completed,NA-THIRUVOTTIYUR,3,2538000,"RESTORATION, FORMING STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 1ST STREET IN DIVISION-03, UNIT-01, ZONE-01.(L=530.00, W=4.50, A=2385.00 SQM",Deposit Works,1,2016-17,2016-17 NA/2016-17/9383,Roads,Completed,NA-THIRUVOTTIYUR,3,2460000,"RESTORATION, FORMING STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 2ND STREET IN DIVISION-03, UNIT-01, ZONE-01.(L=514.00, W=4.50, A=2313.00 SQM",Deposit Works,1,2016-17,2016-17 NA/2016-17/9468,Roads,Completed,NA-THIRUVOTTIYUR,3,2450000,"RESTORATION, FORMING STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 3RD STREET IN DIVISION-03, UNIT-01, ZONE-01.(L=513.00, W=4.50, A=2308.50 SQM",Deposit Works,1,2016-17,2016-17 NA/2016-17/9471,Roads,Completed,NA-THIRUVOTTIYUR,3,2400000,"RESTORATION, FORMING STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 9TH STREET IN DIVISION-03, UNIT-01, ZONE-01.(L=525.00, W=4.30, A=2257.50 SQM",Deposit Works,1,2016-17,2016-17 NA/2016-17/9473,Roads,Completed,NA-THIRUVOTTIYUR,3,700000,"RESTORATION, FORMING STRENGTHENING AND RELAYING THE BT ROAD BY PAVER FINISHING @ ANNAI SIVAGAMI NAGAR 11TH STREET IN DIVISION-03, UNIT-01, ZONE-01.(L=146.00, W=4.50, A=657.00 SQM",Deposit Works,1,2016-17,2016-17 P/2016-17/19669,Parks,Completed,P-Parks and Playfields,3,4202000,"Formation of New Park-2 at Tsunami Quarters, AIR Nagar, Ennore. in Division-3, Unit-1, Zone-1",Grants,1,2016-17,2018-19 NA/2016-17/1038,Buildings,Completed,NA-THIRUVOTTIYUR,4,399000,"Improvement works at Ramanathapuram (Chennai Middle School) in Div-4, Unit-1, Zone-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/1161,Buildings,Completed,NA-THIRUVOTTIYUR,4,59000,"Improvements to rain water pipe line laying work at Ramanathapuram 6th street in Div-4, Unit-1, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/11995,Buildings,Completed,NA-THIRUVOTTIYUR,4,726000,"Improvements of Amma Unavagam at Kamaraj Nagar (Kathivakkam High Road) in Div-4,Unit-1,Zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/1333,Buildings,Completed,NA-THIRUVOTTIYUR,4,174000,"Improvement & Mainteance work in at Chennai primary & High school , Eranavoor in Div-4,Unit-1,Z-1",Own Sources,1,2016-17,2016-17 NA/2016-17/1336,Buildings,Completed,NA-THIRUVOTTIYUR,4,995000,"Proposed construction of AMMA UNAVAGAM-2 at Mullai nagar (manali express road)in Div-4, Unit-1, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/13983,Buildings,Completed,NA-THIRUVOTTIYUR,4,151000,"Repair and Mainteance work in PC at Thiruveethiamman koil 5th street ,Eranavoor in div-4,unit-1,zone-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/14759,Buildings,Completed,NA-THIRUVOTTIYUR,4,251000,"Improvements and Maintenance work At Ramanathapuram health post 1st street in Div-4, U-1, Z-1,",Own Sources,1,2016-17,2017-18 NA/2016-17/15761,Buildings,Completed,NA-THIRUVOTTIYUR,4,150000,"Improvement and Mainteance of Chennai Middle School at Ramanathapuram in Div-4, Unit-1, Zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16717,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,675000,"IMPROVEMENTS TO OPEN SIDE DRAIN AT THIRUVEETHIAMMAN KOVIL 13 TH STREET ERANAVOOR IN DIV-4, UNIT-1, ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16729,Buildings,Completed,NA-THIRUVOTTIYUR,4,50000,"Improvement to Open Side Drain at Perumal Koil 1st Street,in Div-4,Uint-1,Zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16736,Roads,Completed,NA-THIRUVOTTIYUR,4,125000,"Providing the Name Board at Various streets in Dn-4, Unit-1, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/17304,Buildings,Completed,NA-THIRUVOTTIYUR,4,159000,"Improvements to Anganwadi Centre No.13, at Mahkaliamman Koil Street Ernavoor in Div-4, Unit-1, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/4476,Buildings,Completed,NA-THIRUVOTTIYUR,4,1220000,"Proposed construction of Anganwadi Centre No.12 at Thiruvethiamman koil 1st street in Div-4, Unit-1, Zone-1.",MLACDS,1,2016-17,2019-20 NA/2016-17/4491,Buildings,Completed,NA-THIRUVOTTIYUR,4,1220000,"Proposed construction of Anganwadi Building Centre No.10.at Thiruveethiamman koil 1st Street in Div-4, Unit-1, Zone-1",MLACDS,1,2016-17,2019-20 NA/2016-17/6752,Buildings,Completed,NA-THIRUVOTTIYUR,4,999000,"Improvements & Maintenance in health post at ramanathapuram 1st street in Div-4, Unit-1, Zone-1.",Own Sources,1,2016-17,2018-19 NA/2016-17/7116,Buildings,Completed,NA-THIRUVOTTIYUR,4,149000,"Improvement works in Amma Unavagam at Bajani koil street in Div-4,Unit-1,Zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/8294,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,75000,"Improvements to C.C Road and storm water drain at Poombukar nagar in div-4, Unit-1, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/10539,Buildings,Completed,NA-THIRUVOTTIYUR,5,929000,"Proposed Construction of Dressing Room For Conservancy Labours And C.I Store Room at Ramakrishna Nagar 2nd Main Road in DN-5, U-2, Z-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/12907,Buildings,Completed,NA-THIRUVOTTIYUR,5,259000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT BHARATHIYAR NAGAR 2ND STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2016-17,2016-17 NA/2016-17/13191,Parks,Completed,NA-THIRUVOTTIYUR,5,194000,"REPAIRS AND IMPROVEMENTS WORKS TO GCC PARK AT HANSA GARDEN OSR IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2016-17,2016-17 NA/2016-17/13713,Buildings,Completed,NA-THIRUVOTTIYUR,5,360000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT BHARATH NAGAR IN DN-5,U-2,ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16424,Parks,Completed,NA-THIRUVOTTIYUR,5,365000,"REPAIRS AND IMPROVEMENTS TO GCC PARK (All cargo logistic OSR land) DAMAGE DUE TO VARDHA CYCLONE AT WIMCO NAGAR,ERNAVOOR IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16435,Parks,Completed,NA-THIRUVOTTIYUR,5,81000,"REPAIRS AND IMPROVEMENTS TO GCC PARK (HANSA GARDEN OSR land) DAMAGE DUE TO VARDHA CYCLONE AT AJAX,THIRUVOTTIYUR, IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16439,Parks,Completed,NA-THIRUVOTTIYUR,5,440000,"REPAIRS AND IMPROVEMENTS TO GCC PARK DAMAGE DUE TO VARDHA CYCLONE AT SAKTHI PURAM,SRI RANGAM NEW TOWN, IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16601,Buildings,Completed,NA-THIRUVOTTIYUR,5,197000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM DAMAGE DUE TO VARDHA CYCLONE AT BHARATHIYAR NAGAR 2ND STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16618,Roads,Completed,NA-THIRUVOTTIYUR,5,131000,"PROVIDING STREET NAME BOARDS DAMAGE DUE TO VARDHA CYCLONE IN DN-5,UNIT-2 ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16737,Buildings,Completed,NA-THIRUVOTTIYUR,5,37000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM DAMAGE DUE TO VARDHA CYCLONE AT MANICKAM NAGAR IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/6428,Buildings,Completed,NA-THIRUVOTTIYUR,5,37500,"Maintenance work to park in Sakthipuram at Division - 5, Unit-2, Zone-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/6429,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,36000,"Desilting to Storm water Drain at MRF Road in Division-5, Unit-2, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/7168,Buildings,Completed,NA-THIRUVOTTIYUR,5,995000,"NEW CONSTRUCTION OF AMMA UNAVAGAM AT MANICKAM NAGAR IN DIV-05, UNIT-2, ZONE-1",Own Sources,1,2016-17,2016-17 NA/2016-17/7289,Roads,Completed,NA-THIRUVOTTIYUR,5,119000,"SUPPLY OF LABOUR FOR MAINTENANCE INTERIOR ROADS IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2016-17,2016-17 NA/2016-17/7865,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,445000,"Maintenance to Storm water Drain at MRF Road in Division-5, Unit-2, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/9740,Buildings,Completed,NA-THIRUVOTTIYUR,5,778000,"ADDITIONAL WORKS TO AMMA UNAVAGAM AT MANICKAM NAGAR MAIN ROAD IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2016-17,2016-17 NA/2016-17/0630,Buildings,Completed,NA-THIRUVOTTIYUR,6,256000,"Improvements and mainteance work in Chennai School at Sathiyamoorthy nagar in Div-6, Unit-2, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/0631,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,135000,"Desilting in open side drain use by JCB at Manli express road in div-6,unit-2,zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/11996,Buildings,Completed,NA-THIRUVOTTIYUR,6,816000,"Improvements to Amma Unavagam at Jothi Nagar 10th Street,in Div-6,Unit-2,Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/17104,Buildings,Completed,NA-THIRUVOTTIYUR,6,80000,"Repairs and Improvements to Amma unavagam at jothi nagar 10th street in Dn-6, U-2, Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/17110,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,750000,"Improvements open side drain at jothi nagar 10th st in Div-6, Unit-2, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/17113,Buildings,Completed,NA-THIRUVOTTIYUR,6,181000,"Improvements to Amma unavagam (Drainage work) in Div-06, Unit-02, Zone-01",Own Sources,1,2016-17,2016-17 NA/2016-17/17306,Roads,Completed,NA-THIRUVOTTIYUR,6,125000,"Providing the Name Board Various Street in Div-6,Unit-2,Zone-1",Own Sources,1,2016-17,2017-18 NA/2016-17/17483,Roads,Completed,NA-THIRUVOTTIYUR,6,322000,"Strengthening and relaying existing road by Paver finisher at Kalaignar nagar, Raja shanmugam nagar in Div-6, U-2, Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/1943,Buildings,Completed,NA-THIRUVOTTIYUR,6,995000,"Proposed construction of AMMAUNAVAGAM-2 at jothi nagar (Manali Express road) in div-6,unit-2,zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/2619,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,993000,"Desilting and Repair Work in Open Side Drain at Jothi Nagar 10th st (Manali Express Road)in Div-6, Unit-2, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/6393,Roads,Completed,NA-THIRUVOTTIYUR,6,911000,"Laying of cement concrete road at Ambedkar nagar,pillayar kovil st in div-6,unit-2,zone-1(councillor Fund)",Own Sources,1,2016-17,2018-19 NA/2016-17/6395,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,275000,"PROPOSED CONSTRUCTION OF OPEN SIDE DRAIN AT T.S.GOPAL NAGAR 1st ST IN DIV -6,UNIT-2,ZONE-1",Own Sources,1,2016-17,2016-17 NA/2016-17/7178,Buildings,Completed,NA-THIRUVOTTIYUR,6,265000,"Supplying and fixing stainless steel children play apparatus to the Chennai School at sathiyamoorthy nagar in Div-6, Unit-2, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/7256,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,250000,"Repair work and maintenance in open side drain at Kalaingar Nagar 10th cross st in Div-6, Unit-2, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/7921,Roads,Completed,NA-THIRUVOTTIYUR,6,999000,"Laying oF Cement Concrete Road at Fish Market Road Ambedkar Nagar in Div-6,Unit-2 Zone-1",Own Sources,1,2016-17,2018-19 NA/2016-17/9063,Buildings,Completed,NA-THIRUVOTTIYUR,6,73000,"Provide the Well Rings for amma unavagam at Sathiyamoorthy Nagar in Div-6, Unit-2, Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/9064,Buildings,Completed,NA-THIRUVOTTIYUR,6,121000,"Improvements and maintenance in open side drain at sakthi Ganapathy Nagar 2nd street,in Div-6,Unit-2,Zone-1",Own Sources,1,2016-17,2016-17 BR/2016-17/9733,Storm Water Drain,Completed,BR-Bus Route Roads,7,6830000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Basin Road in div 07, Zone -01.",Grants,1,2016-17,2017-18 NA/2016-17/11045,Roads,Completed,NA-THIRUVOTTIYUR,7,3558000,"FORMING, STRENGTHING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR CAPTAN PRASATH STREET IN DN-07, UNIT-02, ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11061,Roads,Completed,NA-THIRUVOTTIYUR,7,2860000,"FORMING, STRENGTHING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR NAYAK KAMARAJ STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11065,Roads,Completed,NA-THIRUVOTTIYUR,7,2860000,"FORMING, STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR RAGAVAN STREET IN DN-7, UNIT-2, ZONE-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/11066,Roads,Completed,NA-THIRUVOTTIYUR,7,2860000,"FORMING, STRENGTHING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR MUGILAN STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11067,Roads,Completed,NA-THIRUVOTTIYUR,7,2788000,"FORMING, STRENGTHING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR NAYAK KRISHNAN STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11068,Roads,Completed,NA-THIRUVOTTIYUR,7,2860000,"FORMING, STRENGTHING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR CHIPPAI SELVAKUMAR STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11070,Roads,Completed,NA-THIRUVOTTIYUR,7,1789000,"FORMING, STRENGTHING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR CHIPPAI JAYAVEL STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11072,Roads,Completed,NA-THIRUVOTTIYUR,7,1432000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR CHIPPAI SENTHIL STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11075,Roads,Completed,NA-THIRUVOTTIYUR,7,1789000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR ABDUL SARDAR STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11076,Roads,Completed,NA-THIRUVOTTIYUR,7,1789000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR SABIBULLA STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11077,Roads,Completed,NA-THIRUVOTTIYUR,7,1789000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR JAWAN PALANI STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11079,Roads,Completed,NA-THIRUVOTTIYUR,7,1789000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR NAYAK MANIKAM STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11081,Roads,Completed,NA-THIRUVOTTIYUR,7,1789000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR CHIPPAI KUMARAN STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11084,Roads,Completed,NA-THIRUVOTTIYUR,7,2387000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR CHIPPAI VADIVEL STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/11085,Roads,Completed,NA-THIRUVOTTIYUR,7,2330000,"FORMING , STRENGTHENING AND LAYING BT ROAD BY PAVER FINISHER AT KARGIL NAGAR CROSS STREET IN DN-07,UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/5667,Buildings,Completed,NA-THIRUVOTTIYUR,7,995000,"CONSTRUCTION OF AMMA UNAVAGAM ( PHASE - II ) AT RAMASAMY NAGAR IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2016-17,2016-17 NA/2016-17/6384,Buildings,Completed,NA-THIRUVOTTIYUR,7,390000,"REPAIR AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT PERIYAR NAGAR , M.G.R. NAGAR, RAJAJI NAGAR AND KARGIL NAGAR IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2016-17,2018-19 NA/2016-17/9127,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,875000,"REPAIR AND IMPROVEMENTS TO SIDE DRAIN AND ROAD CROSSING CULVERT AT RAJAJI NAGAR AND KARGIL NAGAR IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2016-17,2018-19 NA/2016-17/9128,Buildings,Completed,NA-THIRUVOTTIYUR,7,999000,"REPAIR AND IMPROVEMENTS TO PUMP ROOM AT KARGIL NAGAR IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2016-17,2018-19 NA/2016-17/9129,Buildings,Completed,NA-THIRUVOTTIYUR,7,960000,"CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENTS TO BALAKRISHNA NAGAR ANGANWADI CENTER IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2016-17,2016-17 NA/2016-17/9130,Buildings,Completed,NA-THIRUVOTTIYUR,7,950000,"CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENTS TO AMMA UNAVAGAM AT RAMASAMY NAGAR IN DN - 07, UNIT - 02, ZONE - 01.",Own Sources,1,2016-17,2016-17 NA/2016-17/16019,Buildings,Completed,NA-THIRUVOTTIYUR,8,627000,"Construction of (PHASE-2) Amma UNAVAGAM at Ennore Express road opp Musthan koil street in Dn-8, Unit-2, Zone-I. (Vardha cyclone)",Own Sources,1,2016-17,2017-18 NA/2016-17/1667,Buildings,Completed,NA-THIRUVOTTIYUR,8,82000,"ADDITIONAL AND IMPROVEMENT WORK IN AMMA UNAVAGAM IN DIVISION-08,UNIT,02, ZONE-01",Own Sources,1,2016-17,2016-17 NA/2016-17/1726,Buildings,Completed,NA-THIRUVOTTIYUR,8,998000,"CONSTRUCTION OF NEW PUBLIC CONVENIENCE TOILET IN MASTHAN KOIL STREET IN ENNORE EXPRESS ROAD IN DIVISION -08, UNIT-02,ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/5516,Buildings,Completed,NA-THIRUVOTTIYUR,8,995000,"NEWLY CONSTRUCTION OF AMMA UNAVAGAM(PHASE 2) AT ENORE EXPRESS ROAD IN DIV-08, UNIT-2, ZONE-1",Own Sources,1,2016-17,2016-17 NA/2016-17/8611,Buildings,Completed,NA-THIRUVOTTIYUR,8,450000,"Addidtional and Improvement works in Anganwadi center no-36 at Periyar nagar in Dn-8,Unit-2,Zone-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/9643,Buildings,Completed,NA-THIRUVOTTIYUR,8,887000,"ADDITIONAL IMPROVEMENT WORK OF AMMA UNAVAGAM (PHASE- 2) AT ENORE EXPRESS ROAD IN DIV-08, UNIT-2, ZONE-I.",Own Sources,1,2016-17,2016-17 NA/2016-17/17072,Buildings,Completed,NA-THIRUVOTTIYUR,9,757000,"Errection of New Chimmney work at Greater Chennai Corporation Thiruvottiyur Crematorjum in Dn-9, Unit-2, Zone-I.",Own Sources,1,2016-17,2017-18 NA/2016-17/1718,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,9,259000,"PROVIDING AND LAYING OF STORM WATER LINE IN KILIJOSIYAM NAGAR IN DIVISION-09, UNIT-02, ZONE-01.",Own Sources,1,2016-17,2017-18 NA/2016-17/6606,Buildings,Completed,NA-THIRUVOTTIYUR,9,670000,"Additional and improvement of School Building at Tiruvattiuyur kuppam in Division-09, Unit-02,Zone-1",Own Sources,1,2016-17,2016-17 NA/2016-17/16633,Buildings,Completed,NA-THIRUVOTTIYUR,10,637000,"REPAIRS WORK AND IMPROVEMENT WORK AT AMMA UNAVAGAM DAMAGE DUE TO VARDHA CYCLONE AT NORTH MADA STREET DIV-10,U-3,Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16635,Buildings,Completed,NA-THIRUVOTTIYUR,10,593000,"REPAIR AND IMPROVEMENT WORKS TO PUBLIC CONVIENCE DAMAGE DUE TO VARDHA CYCLONE AT SANATHI STREET ( EAST TANK ROAD ) IN DIV-10,U-3,Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16636,Roads,Completed,NA-THIRUVOTTIYUR,10,115000,"SUPPLYING AND FIXING STREET NAME BOARD DAMAGE DUE TO VARDHA CYCLONE AT VARIOUS STREET IN DIVISION -10, UNIT-3, ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16980,Buildings,Completed,NA-THIRUVOTTIYUR,10,412000,"REPAIR AND IMPROVEMENT WORKS TO PUBLIC CONVENIENCE DAMAGE DUE TO VARDHA CYCLONE AT POOTHOTAM STREET (INSIDE COLLEGE ) IN DIV-10,U-3,Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/7796,Roads,Completed,NA-THIRUVOTTIYUR,10,316000,"Providing and Fixing of Rain Water Harsvesting at Various streets in Many Location In Division -10, Unit-3, Zone -1",Own Sources,1,2016-17,2018-19 NA/2016-17/1560,Buildings,Completed,NA-THIRUVOTTIYUR,11,285000,"Improvement (Water supply and electrical arrangements) to anganwadi building and toilet block of Market Lane CPS campus in Dn-11, Unit-03, Zone-1.",Own Sources,1,2016-17,2018-19 NA/2016-17/16557,Buildings,Completed,NA-THIRUVOTTIYUR,11,117000,"Repairs to Amma Unavagam (Phase-1) Damage due to Vardha Cyclone at T.H.Road in Division-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16569,Buildings,Completed,NA-THIRUVOTTIYUR,11,252000,"Repairs and Improvements to Anganwadi Shed no.44 and 48 Damage due to Vardha Cyclone at Vedhachalam Avenue in Division-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/16608,Buildings,Completed,NA-THIRUVOTTIYUR,11,903000,"Repairs and Improvements to CHS Market Lane Damage due to Vardha Cyclone in Division-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/17475,Roads,Completed,NA-THIRUVOTTIYUR,11,2250000,"Laying BT Road at Municipal Road (Zonal Office Road) Damage due to Vardha Cyclone in Division-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/17491,Buildings,Completed,NA-THIRUVOTTIYUR,11,468000,"Repairs and Improvements to Greater Chennai Corporation Shopping Complex (Taluk Office, Central Bank of India and Tamil Nadu Civil Suppliers Office) Damage due to Vardha Cyclone at T.H.Road in Division-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2017-18 NA/2016-17/4126,Buildings,Completed,NA-THIRUVOTTIYUR,11,495000,"Reparirs and Improvements to around Meeting Hall and Toilet Block (Ground Floor) in Zonal Office Building at T.H.Road in Division-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/5018,Buildings,Completed,NA-THIRUVOTTIYUR,11,2995000,"Demolishing and Reconstruction of Anganwadi Building ( Shed no. 56, 49 and 29) at Ennore Express Road in Div-11, U-3, Z-1. (Under MLA fund)",MLACDS,1,2016-17,2020-21 NA/2016-17/5318,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,11,338000,"Repairs and Improvements to M.L.A. Office at T.H.Road (Zonal Office Inside) in Division-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2018-19 NA/2016-17/7902,Buildings,Completed,NA-THIRUVOTTIYUR,11,995000,"Proposed construction of Amma Unavagam Phase-2, at Ellai amman Koil Street in Div-11, Unit-3, Zone-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/7904,Buildings,Completed,NA-THIRUVOTTIYUR,11,180000,"Repairs and improvements to all Public conveniences at various streets in Division-11, Unit-3, Zone-1,",Own Sources,1,2016-17,2018-19 NA/2016-17/14270,Buildings,Completed,NA-THIRUVOTTIYUR,12,849000,"Additional Construction and Improvements of anganwadi building at Vanniyar street in Dn-12, U-3, Z-1",Own Sources,1,2016-17,2016-17 NA/2016-17/14286,Buildings,Completed,NA-THIRUVOTTIYUR,12,413000,"Providing and Relaying BT Road at Sirinivasapuram north to south Street in Div-12, U-3 ,Z-1",Own Sources,1,2016-17,2016-17 NA/2016-17/14613,Roads,Completed,NA-THIRUVOTTIYUR,12,408000,"Providing and Relaying BT Road at Sirinivasapuram east/west Street in Div-12, U-3 ,Z-1",Own Sources,1,2016-17,2016-17 NA/2016-17/14891,Roads,Completed,NA-THIRUVOTTIYUR,12,142000,"Providing and Relaying BT Road at Balakrishna Naidu Colony 5th Street in Div-12, U-3 ,Z-1",Own Sources,1,2016-17,2016-17 NA/2016-17/4866,Buildings,Completed,NA-THIRUVOTTIYUR,12,243000,"Construction of Sump with water supply arrangements & Sewer line repair for Greater Chennai Clinic ( Health post ) at B.K.N colony in DIV-12,U-3,Z-1.",Own Sources,1,2016-17,2016-17 NA/2016-17/5732,Buildings,Completed,NA-THIRUVOTTIYUR,12,839000,"Newly Construction of Amma Unavagam (Phase -2) at Vanniyar street in DIV-12, U-3, Z-1",Own Sources,1,2016-17,2016-17 BR/2016-17/9734,Storm Water Drain,Completed,BR-Bus Route Roads,13,3648000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at TOLGATE ROAD (MGR salai) in div 13, Zone -01.",Grants,1,2016-17,2017-18 BR/2016-17/9735,Storm Water Drain,Completed,BR-Bus Route Roads,13,5590000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Village Road in div - 13, Zone -01",Grants,1,2016-17,2017-18 NA/2016-17/16589,Roads,Completed,NA-THIRUVOTTIYUR,13,247000,"SUPPLYING AND FIXING STREET NAME BOARD DAMAGE DUE TO VARDHA CYCLONE AT VARIOUS STREET IN DIVISION -13,UNIT-3,ZONE-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16627,Buildings,Completed,NA-THIRUVOTTIYUR,13,46000,"REPAIR WORK AND IMPROVEMENT WORK TO AMMA UNAVAGAM DAMAGE DUE TO VARDHA CYCLONE AT M.G.R ROAD IN DIV-13,U-3,Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/16629,Parks,Completed,NA-THIRUVOTTIYUR,13,148000,"REPAIRS AND IMPROVEMENTS WORK TO GCC PARK M.G.R ROAD DAMAGE DUE TO VARDHA CYCLONE IN DIV-13,U-3,Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/17468,Roads,Completed,NA-THIRUVOTTIYUR,13,841000,"Providing and Relaying M30 CC Road at Village Street 1,2,3 lanes in Div-13, U-3, Z-1",Own Sources,1,2016-17,2017-18 NA/2016-17/8633,Buildings,Completed,NA-THIRUVOTTIYUR,13,514000,"REPAIRS AND IMPROVEMANT WORKTO NNMP SHED CENTRE NO :76 DAMAGE DUE TO VARDHA CYCLONE AT VARADHARAJAN STREET IN DIV -13,U-3,Z-1.",Own Sources,1,2016-17,2017-18 L/2016-17/11496,Electrical,Completed,L-Electrical,14,2015000,"Provision of 45 nos. of 6 mtr G.I lamp post with Single Bracket with 40w LED fittings fittings at TNSCB Tenements at Fishermen colony at Thiruchinnakuppam in Division-14, Zone-I [SOR-2015-16]",Deposit Works,1,2016-17,2018-19 NA/2016-17/14887,Buildings,Completed,NA-THIRUVOTTIYUR,14,128000,"PROVIDING BIN PLATFORM AND WELL RING FOR COMPOSING AT VARIOUS STREET IN DIVISION-14, UNIT-03, ZONE-01.",Own Sources,1,2016-17,2016-17 NA/2016-17/15209,Buildings,Completed,NA-THIRUVOTTIYUR,14,133000,"IMPROVEMENTS TO P.C AT THIRUCHINAN KUPPAM & N.T.O KUPPAM IN DIVISION-14,UNIT-03, ZONE-01.",Own Sources,1,2016-17,2016-17 L/2016-17/18141,Electrical,Completed,L-Electrical,15,1418000,"Removal,refixing & erection of street lamp post in various locations of division 15 to 21 due to damages in vardha cyclone, zone-2",Own Sources,2,2016-17,2017-18 NB/2016-17/0473,Buildings,Completed,NB-MANALI,15,998000,"Proposed construction of compound wall for OSR land at manali new town 43rd street (west and north side) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/0478,Buildings,Completed,NB-MANALI,15,998000,"Proposed construction of compound wall for OSR land at manali new town 43rd street (East and South side) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/0480,Buildings,Completed,NB-MANALI,15,860000,"Proposed construction of compound wall for Flood damaged area at new colony old nappalayam (west and north side) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/0483,Parks,Completed,NB-MANALI,15,988000,"IMPROVEMENT WORKS AT PARKS IN DIVISION 15, 16 & 17 , UNIT 4 AND ZONE 2.",Own Sources,2,2016-17,2016-17 NB/2016-17/0600,Buildings,Completed,NB-MANALI,15,997000,"Construction of gate, gate pillar, sump & painting for park at manali new town block no 26 CPS10 in DN-15, U-04, Zone-II.",Own Sources,2,2016-17,2016-17 NB/2016-17/0616,Parks,Completed,NB-MANALI,15,997000,"Providing the yoga plat form, water supplying and greenering work in side of manali new town block no 26 CPS10th park in Dn-15, U-4, Zone-II.",Own Sources,2,2016-17,2017-18 NB/2016-17/0619,Playfields,Completed,NB-MANALI,15,900000,"Supplying and fixing Water supply and sewer connection in side of park childrens play area at manali new town block no 26 CPS10th in Dn-15, U-4, Zone-II.",Own Sources,2,2016-17,2016-17 NB/2016-17/0623,Playfields,Completed,NB-MANALI,15,995000,"Supplying and fixing play apparatus in side childrens play area at manali new town block no 26 CPS10th in Dn-15, U-4, Zone-II.",Own Sources,2,2016-17,2016-17 NB/2016-17/10625,Buildings,Completed,NB-MANALI,15,995000,"Construction of Retaining wall for Flood affected area at Edayanchavadi main road (North side Reach 1) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/10626,Buildings,Completed,NB-MANALI,15,994000,"Construction of Retaining wall for Flood affected area at Edayanchavadi main road (North side Reach 2) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/10628,Buildings,Completed,NB-MANALI,15,992000,"Construction of Retaining wall for Flood affected area at Edayanchavadi main road (North side Reach 3) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/10631,Road Cut,Completed,NB-MANALI,15,525000,"Road cut restoration for CMWSSB At Manali new town 10th block 4th Main road and 45th block 27th street in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2017-18 NB/2016-17/10632,Road Cut,Completed,NB-MANALI,15,123000,"Road cut Restoration at Edayanchavdi main Road from gangai amman koil street (225-257) In DN-15,U-4,ZN-2",Deposit Works,2,2016-17,2017-18 NB/2016-17/11826,Buildings,Completed,NB-MANALI,15,995000,"IMPROVEMENTS AND CONSTRUCTION OF SIDE DRAIN, CULVERT AND SEPTIC TANK AT OLD NAPPALAYAM AND MANALI NEW TOWN IN DN-15, U-4, Z-02.",Own Sources,2,2016-17,2018-19 NB/2016-17/1260,Roads,Completed,NB-MANALI,15,880000,"Forming & Laying Cement concrete Road at Perumal koil 4th cross street (kannikoil medu) & Thulasi nagar park street IN DN-15,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/1261,Roads,Completed,NB-MANALI,15,995000,"PROPOSED LAYING OF C.C ROAD AT KANNIKOIL MEDU 1ST, 2ND, 3RD AND 4TH CROSS STREET IN DN-15, U-4, ZONE-02.",Own Sources,2,2016-17,2018-19 NB/2016-17/1262,Roads,Completed,NB-MANALI,15,997000,"PROPOSED LAYING OF C.C ROAD AT OLD NAPPALAYAM THIRUMURUGAN NAGAR STREET AND LAKSHMINAGAR 2ND STREET 1ST CROSS AND 1ST LANE IN DN-15, U-4, ZONE-02.",Own Sources,2,2016-17,2018-19 NB/2016-17/1268,Roads,Completed,NB-MANALI,15,930000,"IMPROVEMENTS AND MAINTENANCE TO SIDE DRAIN, AND PARKS FOR FLOOD AFFECTED AREA AT EECHANKUZHI AND MANALI NEW TOWN IN DN-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/1269,Roads,Completed,NB-MANALI,15,960000,"Laying Cement concrete Road at Perumal koil 1st cross street, Perumal koil 2nd cross street & Perumal koil 3rd cross street (kannikoil medu) IN DN-15, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/12747,Storm Water Drain,Completed,NB-MANALI,15,970000,"PROPOSED CONSTRUCTION OF STORM WATER DRAIN AND CULVERT AT MANALI NEW TOWN 16TH MAIN ROAD IN DN-15, U-4, ZONE-02.",Own Sources,2,2016-17,2018-19 NB/2016-17/12752,Buildings,Completed,NB-MANALI,15,900000,"Construction and Improvement works for Disable toilet, public toilet and multipurpose hall at Edayanchavadi main road in Dn-15, U-4, Zone-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/13217,Buildings,Completed,NB-MANALI,15,650000,"Construction of Retaining wall For Flood affected area at Edyanchavadi main road (North side Reach 4) in DN-15, UN-4, ZONE-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/13389,Electrical,Completed,NB-MANALI,15,393000,"Painting and Numbering of street lamp posts and Pillar boxes in Div- 15,16 &17 (Unit-4) of Zone-II, Manali (As per 2015-16 SOR)","Loans, Grants And Own Sources",2,2016-17,2016-17 NB/2016-17/13477,Storm Water Drain,Completed,NB-MANALI,15,997000,"PROPOSED CONSTRUCTION OF STORM WATER DRAIN AND CULVERT AT OLD NAPPALAYAM AND MANALI NEW TOWN 16TH MAIN ROAD (65 to 130.00M) IN DN-15, U-4, ZONE-02.",Own Sources,2,2016-17,2018-19 NB/2016-17/13667,Road Cut,Completed,NB-MANALI,15,2965000,"Restoration of road cut made by CMWSSB At Old Napalayam salai (New colony to Old colony ) in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2018-19 NB/2016-17/13668,Road Cut,Completed,NB-MANALI,15,783000,"Restoration of road cut made by CMWSSB At Old colony 1st street,Old colony 2nd street, Old colony cross street in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2018-19 NB/2016-17/13669,Road Cut,Completed,NB-MANALI,15,968000,"Restoration of road cut made by CMWSSB At Lakshmi Nagar 1st street in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2017-18 NB/2016-17/13670,Road Cut,Completed,NB-MANALI,15,1100000,"Restoration of road cut made by CMWSSB At Lakshmi Nagar 2nd street in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2017-18 NB/2016-17/13671,Road Cut,Completed,NB-MANALI,15,1002000,"Restoration of road cut made by CMWSSB At Lakshmi Nagar 3rd street andLakshmi Nagar cross street in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2017-18 NB/2016-17/13672,Road Cut,Completed,NB-MANALI,15,930000,"Restoration of road cut made by CMWSSB At Ponniamman Nagar 1st street, Ponniamman Nagar 2nd street, Ponniamman Nagar 3rd street, Ponniamman Nagar 1st cross street and Ponniamman Nagar 2nd cross street in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2018-19 NB/2016-17/13673,Road Cut,Completed,NB-MANALI,15,1065000,"Restoration of road cut made by CMWSSB At Ponniamman Nagar 3rd cross street, Ponniamman Nagar 4th cross street, Periya Eachanguzhi salai and Vadugar Palayam salai in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2018-19 NB/2016-17/13674,Road Cut,Completed,NB-MANALI,15,957000,"Restoration of road cut made by CMWSSB At New colony 1st street New colony 2nd street, New colony 3rd street, New colony main street ( T.H.Road to 3rd street ) and New colony cross street in Dn-15, U-4, Zone-02.",Deposit Works,2,2016-17,2017-18 NB/2016-17/14204,Buildings,Completed,NB-MANALI,15,120000,"Maintenance and Improvements of PC at old nappalayam new colony in Dn-15, U-4, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/14893,Parks,Completed,NB-MANALI,15,470000,"IMPROVEMENT WORKS AT MANALI NEW TOWN BLOCK NO 26th CPS 10th PARK IN DN-15, U-4, ZONE-02.",Own Sources,2,2016-17,2018-19 NB/2016-17/15799,Buildings,Completed,NB-MANALI,15,91000,"REPAIRS WORK DUE TO VARDAH CYCLONE FOR AMMAUNAVAGAM AT EDAYANCHAVADI MAIN ROAD IN DN-15, U-4, Z-II",Own Sources,2,2016-17,2017-18 NB/2016-17/15801,Buildings,Completed,NB-MANALI,15,174000,"REPAIRS WORK DUE TO VARDAH CYCLONE FOR CHENNAI PRIMARY SCHOOL AT EDAYANCHAVADI MAIN ROAD IN DN-15, U-4, Z-II",Own Sources,2,2016-17,2017-18 NB/2016-17/15802,Buildings,Completed,NB-MANALI,15,99000,"REPAIRS WORK DUE TO VARDAH CYCLONE CHENNAI PRIMARY SCHOOL AT SERVICE ROAD (NAPPALAYAM) MAIN ROAD IN DN-15, U-4, Z-II",Own Sources,2,2016-17,2017-18 NB/2016-17/15803,Buildings,Completed,NB-MANALI,15,90000,"REPAIRS WORK DUE TO VARDAH CYCLONE FOR NNMP SHED AT CHINNA ECHANKUZHI IN DN-15, U-4, Z-II",Own Sources,2,2016-17,2017-18 NB/2016-17/15804,Buildings,Completed,NB-MANALI,15,92000,"REPAIRS WORK DUE TO VARDAH CYCLONE FOR AMMAUNAVAGAM AT MANALI NEW TOWN 80FEET ROAD IN DN-15, U-4, Z-II",Own Sources,2,2016-17,2017-18 NB/2016-17/17674,Electrical,Completed,NB-MANALI,15,315000,"Repairs to Electrical wiring and fittings in Parks of Unit-4, ward-15 to 17 , zone-2","Loans, Grants And Own Sources",2,2016-17,2017-18 NB/2016-17/3475,Storm Water Drain,Completed,NB-MANALI,15,950000,"Improvement the Flood damaged open side drain and culvert at Old nappalyam in Dn-15, U-4, Z-02",Own Sources,2,2016-17,2016-17 NB/2016-17/3488,Roads,Completed,NB-MANALI,15,998000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MANALI NEW TOWN 1ST AND 30TH BLOCK DN-15,UNIT-4, ZONE-2.",Deposit Works,2,2016-17,2017-18 NB/2016-17/3508,Storm Water Drain,Completed,NB-MANALI,15,870000,"Maintenance and Improvement to Side drain at new colony, old colony (nappalayam) & Earthen Side drain at Andarkuppam in Dn-15 & 16, U-4, Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/3718,Buildings,Completed,NB-MANALI,15,940000,"Additional Improvements Works for gazebo manali new town block no 26 CPS 10 in side of park in Dn-15, U-04, Zone-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/3719,Buildings,Completed,NB-MANALI,15,930000,"Improvements Works for manali new town block no 26 CPS 10 park in Dn-15, U-04, Zone-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/3720,Buildings,Completed,NB-MANALI,15,730000,"Additional Improvements Works for amma canteen at Edayanchawadi main street in Dn-15, U-4, Zone-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7122,Culvert,Completed,NB-MANALI,15,995000,"Improvement for Flood affected culvert at manli new town 80feet Road in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7159,Buildings,Completed,NB-MANALI,15,990000,"Proposed construction of public conveniences at old colony (old nappalayam) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7236,Buildings,Completed,NB-MANALI,15,990000,"Proposed construction of public conveniences at Periya eachankuzhi in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/7491,Buildings,Completed,NB-MANALI,15,975000,"Proposed Construction of Retaining wall for Flood affected area at manali new town CMDA canal (Near by vinayakar koil phase1) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7527,Buildings,Completed,NB-MANALI,15,974000,"Proposed Construction of Retaining wall for Flood affected area at manali new town CMDA canal (Near by vinayakar koil phase2) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7528,Buildings,Completed,NB-MANALI,15,973000,"Proposed Construction of Retaining wall for Flood affected area at manali new town CMDA canal (Near by vinayakar koil phase3) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7529,Buildings,Completed,NB-MANALI,15,972000,"Proposed Construction of Retaining wall for Flood affected area at manali new town CMDA canal (Near by vinayakar koil phase4) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7773,Storm Water Drain,Completed,NB-MANALI,15,997000,"Proposed construction of storm water Darin in Flood affected area at New colony 1st street & cross street part1 ( Old nappalayam) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/7777,Storm Water Drain,Completed,NB-MANALI,15,996000,"Proposed construction of storm water Darin in Flood affected area at New colony 2nd street & cross street part2 (Old nappalayam) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/7783,Storm Water Drain,Completed,NB-MANALI,15,998000,"Proposed construction of storm water Darin in Flood affected area at New colony 3rd street & cross street part3 (Old nappalayam) in Dn-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8042,Buildings,Completed,NB-MANALI,15,398000,"Improvements and Repairs to monsoon Flood damaged Amma unavakam at manali new town in Dn-15, U-4, Zone-02",Own Sources,2,2016-17,2016-17 NB/2016-17/8051,Storm Water Drain,Completed,NB-MANALI,15,950000,"WIDENING DEEPENING AND CLEANING OF FLOOD AFFECTED CANAL FOR USING POCLAIN AND JCB MACHINE AT 80FEET ROAD IN DN-15,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8063,Buildings,Completed,NB-MANALI,15,990000,"DUE TO MONSOON 2016 USING JCB FOR FORMATION OF EARTHEN CANAL AND DESILTING OF EXISTING SWD IN DN-15,U-4,Z-II.",Own Sources,2,2016-17,2017-18 NB/2016-17/8064,Storm Water Drain,Completed,NB-MANALI,15,750000,"WIDENING DEEPENING AND CLEANING OF FLOOD AFFECTED OLD NAPALAYAM CANAL USING POCLAIN AND JCB MACHINE IN DN-15,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8269,Buildings,Completed,NB-MANALI,15,840000,"Construction of Compound wall For Flood affected area at Edyanchavadi main street (South side Reach 2 ) in DN-15, UN-4, ZONE-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/8270,Buildings,Completed,NB-MANALI,15,840000,"Construction of Compound wall For Flood affected area at Edyanchavadi main street (South side Reach 1) in DN-15, UN-4, ZONE-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/8271,Buildings,Completed,NB-MANALI,15,996000,"Construction of Compound wall For Flood affected area at Edyanchavadi main street (North side Reach 3 ) in DN-15, UN-4, ZONE-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8272,Buildings,Completed,NB-MANALI,15,997000,"Construction of Compound wall For Flood affected area at Edyanchavadi main street (North side Reach 2) in DN-15, UN-4, ZONE-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8273,Buildings,Completed,NB-MANALI,15,998000,"Construction of Compound wall For Flood affected area at Edyanchavadi main street (North side Reach 1) in DN-15, UN-4, ZONE-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8703,Buildings,Completed,NB-MANALI,15,980000,"ANNUAL MAINTENANCE FOR PARK, ROADS, BURIAL GROUNDS AND BUILDINGS IN DIVISION 15. UNIT 04, ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8964,Buildings,Completed,NB-MANALI,15,995000,"CONSTRUCTION OF COMPOUND WALL FOR FLOOD AFFECTED AREA AT THULASI NAGAR PARK (WEST AND NORTH SIDE) IN DN-15, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8975,Buildings,Completed,NB-MANALI,15,997000,"CONSTRUCTION OF COMPOUND WALL FOR FLOOD AFFECTED AREA AT THULASI NAGAR PARK (EAST AND SOUTH SIDE) IN DN-15, U-4, Z-02.",Own Sources,2,2016-17,2019-20 NB/2016-17/11264,Buildings,Completed,NB-MANALI,16,890000,"CONSTRUCTION SOURCE SEGREGATION SHED INSIDE ANDARKUPPAM BURIAL GROUND IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/13365,Buildings,Completed,NB-MANALI,16,570000,"CONSTRUCTION OF STORE ROOM,GAS ROOM,TOILET & GAS CONNECTION IN AMMA UNAVAGAM AT BURMA NAGAR IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2019-20 NB/2016-17/13691,Road Cut,Completed,NB-MANALI,16,814000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BURMA NAGAR 3RD,4TH & 5TH STREET IN DN-16,U-4,Z-2.",Deposit Works,2,2016-17,2018-19 NB/2016-17/13692,Road Cut,Completed,NB-MANALI,16,975000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BURMA NAGAR 6TH,7TH,8TH,9TH,10TH,11TH &14TH STREET IN DN-16,U-4,Z-2.",Deposit Works,2,2016-17,2017-18 NB/2016-17/13725,Road Cut,Completed,NB-MANALI,16,922000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BURMA NAGAR 16TH,17TH,18TH &19TH STREET IN DN-16,U-4,Z-2.",Deposit Works,2,2016-17,2017-18 NB/2016-17/13726,Road Cut,Completed,NB-MANALI,16,826000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT IRULLAR COLONY (ST COLONY) BURMA NAGAR 1ST CROSS STREET IN DN-16,U-4,Z-2.",Deposit Works,2,2016-17,2017-18 NB/2016-17/13727,Road Cut,Completed,NB-MANALI,16,604000,"RESTORATION OF ROAD CUT MADEBY CMWSSB AT BURMA NAGAR 2ND & 3RD CROSS STREET IN DN-16,U-4,Z-2.",Deposit Works,2,2016-17,2017-18 NB/2016-17/13728,Buildings,Completed,NB-MANALI,16,120000,"IMPROVEMENTS AND REPAIR TO PUBLIC CONVENIENCE AT BURMA NAGAR BURIAL GROUND ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/13729,Buildings,Completed,NB-MANALI,16,75000,"IMPROVEMENTS AND REPAIR TO PUBLIC CONVENIENCE AT KANNIAMMAN PETTAI 2 IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/13730,Buildings,Completed,NB-MANALI,16,75000,"IMPROVEMENTS AND REPAIR TO PUBLIC CONVENIENCE AT KAMARAJAPURAM IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/13731,Buildings,Completed,NB-MANALI,16,75000,"IMPROVEMENTS AND REPAIR TO PUBLIC CONVENIENCE AT SADAYANKUPPAM IRULAR COLONY IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/13732,Buildings,Completed,NB-MANALI,16,998000,"CONSTRUCTION OF COMMUNITY TOILET BLOCK AT IRULAR COLONY IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2016-17,2019-20 NB/2016-17/14308,Buildings,Completed,NB-MANALI,16,180000,"IMPROVEMENTS AND REPAIR TO PUBLIC CONVENIENCE AT BURMA NAGAR PLAY GROUND IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15777,Buildings,Completed,NB-MANALI,16,175000,"REPAIR WORK DUE TO VARDAH CYCLONE COMPOUND WALL AT CHENNAI MIDDLE SCHOOL ANDARKUPPAM REDHILLS ROAD IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15789,Buildings,Completed,NB-MANALI,16,178000,"REPAIR WORK DUE TO VARDAH CYCLONE COMPOUND WALL AT AMMA UNAVAGAM ANDARKUPPAM REDHILLS ROAD IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15790,Buildings,Completed,NB-MANALI,16,70000,"REPAIR WORK DUE TO VARDAH CYCLONE WASHING AREA ROOF IRON SHEET AT AMMA UNAVAGAM ANDARKUPPAM REDHILLS ROAD (NEAR BY UNIT OFFICE-4) IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15791,Buildings,Completed,NB-MANALI,16,85000,"REPAIR WORK DUE TO VARDAH CYCLONE SHREDDING YARD ROOF IRON SHEET AT KANNIAMMANPET IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15792,Buildings,Completed,NB-MANALI,16,175000,"REPAIR WORK DUE TO VARDAH CYCLONE COMPOUND WALL AT PLAY GROUND TNHB PHASE 1 IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15793,Buildings,Completed,NB-MANALI,16,188000,"REPAIR WORK DUE TO VARDAH CYCLONE STREET NAME BOARD AT VARIOUS STREET IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15794,Buildings,Completed,NB-MANALI,16,177000,"REPAIR WORK DUE TO VARDAH CYCLONE UNIT OFFICE-4 AT ANDARKUPPAM REDHILLS ROAD IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15795,Buildings,Completed,NB-MANALI,16,57000,"REPAIR WORK DUE TO VARDAH CYCLONE GATE AT KANNIAMMANPET, KAMARAJAPURAM, KULAKARAI (K.G.L NAGAR) BURIAL GROUND IN DN-16,U-4,ZN-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16110,Parks,Completed,NB-MANALI,16,856000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR VARIOUS PARK AT UNIT-4 (DN-15,DN-16 DN-17),Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/1885,Buildings,Completed,NB-MANALI,16,998000,"ADDITIONAL CONSTRUCTION OF MULTIPURPOSE HALL AT ELANDANUR PERUMAL KOIL STREET IN DN-16,U-4,Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/1886,Roads,Completed,NB-MANALI,16,850000,"PROVIDING SUMP,SEPTIC TANK,WATER SUPPLY AND ELECTRICAL WORK ARRANGEMENTS FOR MULTIPURPOSE HALL AT ELANDANUR PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/1887,Buildings,Completed,NB-MANALI,16,999000,"ELECTRICAL AND ADDITIONAL CONSTRUCTION OF MULTIPURPOSE HALL AT KANNIAMMAN PAT II PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/8714,Roads,Completed,NB-MANALI,16,498000,"FORMING AND LAYING THE BITUMINOUS COURSE AT VADIVUDAI AMMAN NAGAR 1ST STREET(EXT) IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8730,Roads,Completed,NB-MANALI,16,498000,"FORMING AND LAYING THE BITUMINOUS COURSE AT VADIVUDAI AMMAN NAGAR 2ND STREET(EXT) IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8749,Roads,Completed,NB-MANALI,16,498000,"FORMING AND LAYING THE BITUMINOUS COURSE AT VADIVUDAI AMMAN NAGAR 3RD STREET(EXT) IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8750,Roads,Completed,NB-MANALI,16,498000,"FORMING AND LAYING THE BITUMINOUS COURSE AT VADIVUDAI AMMAN NAGAR 4TH STREET(EXT) IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8751,Roads,Completed,NB-MANALI,16,6912000,"FORMING AND LAYING THE BITUMINOUS COURSE AT KGL NAGAR IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8752,Roads,Completed,NB-MANALI,16,1004000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KADAPPAKKAM VICHUR LINK ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8753,Roads,Completed,NB-MANALI,16,1606000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KADAPPAKKAM MAIN ROAD TO PERUMAL KOIL STREET LINK IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8754,Roads,Completed,NB-MANALI,16,230000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KANNIAMMAN PET GANGAI AMMAN KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8755,Roads,Completed,NB-MANALI,16,1376000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KADAPPAKKAM ANDARKUPPAM REDHILLS LINK ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8756,Roads,Completed,NB-MANALI,16,459000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KANNIAMMANPET 2 PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8757,Roads,Completed,NB-MANALI,16,344000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KANNIAMMANPET VINAYAGAR KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8784,Roads,Completed,NB-MANALI,16,344000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KANNIAMMANPET V.O.C STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8785,Roads,Completed,NB-MANALI,16,445000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KANNIAMMANPET PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8788,Roads,Completed,NB-MANALI,16,367000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KANNIAMMANPET 2 GANGAI AMMAN KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8790,Roads,Completed,NB-MANALI,16,1613000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM RADHAKRISHNAN PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/8791,Roads,Completed,NB-MANALI,16,195000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM 1ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8792,Roads,Completed,NB-MANALI,16,195000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM 2ND STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8794,Roads,Completed,NB-MANALI,16,207000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM 3RD STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8796,Roads,Completed,NB-MANALI,16,207000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM 4TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8798,Roads,Completed,NB-MANALI,16,230000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM 5TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8800,Roads,Completed,NB-MANALI,16,390000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM KANNIAMMAN KOIL LINK ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8802,Roads,Completed,NB-MANALI,16,194000,"RELAYING THE EXISTING BITUMINOUS ROAD AT KAMARAJAPURAM BHARATHI STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8803,Roads,Completed,NB-MANALI,16,2579000,"RELAYING THE EXISTING BITUMINOUS ROAD AT ELANTHANOOR PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/9189,Roads,Completed,NB-MANALI,16,1104000,"RELAYING THE EXISTING BITUMINOUS ROAD AT ANDARKUPPAM PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/9199,Roads,Completed,NB-MANALI,16,970000,"DUE TO MONSOON 2016 USING JCB & POCLAIN FOR FORMATION OF EARTHERN CANAL AND DESILTING OF EXISTING SWD IN DN-16,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/14090,Buildings,Completed,NB-MANALI,17,741000,"RESTORATION OF ROAD-CUT MADE BY CMWSSB AT PERIYAR NAGAR MAIN ROAD (350M) IN DN-17, U-4, Z-2.",Deposit Works,2,2016-17,2018-19 NB/2016-17/14254,Buildings,Completed,NB-MANALI,17,100000,"IMPROVEMENT WORKS TO PUBLIC CONVENIENCE AT SAMUVEL NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/14255,Buildings,Completed,NB-MANALI,17,385000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT THEEYAMBAKKAM IN DN-17, U-4, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/14256,Buildings,Completed,NB-MANALI,17,50000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT KATHAKUZHI IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/14257,Buildings,Completed,NB-MANALI,17,25000,"IMPROVEMENT WORKS TO PUBLIC CONVENIENCE AT PERUMAL KOIL STREET (VADAPERUMBAKKAM) IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/14258,Road Cut,Completed,NB-MANALI,17,741000,"RESTORATION OF ROAD-CUT MADE BY CMWSSB AT PERIYAR NAGAR 5 STREETS REACH-1 (350M) IN DN-17, U-4, Z-2.",Deposit Works,2,2016-17,2018-19 NB/2016-17/14259,Road Cut,Completed,NB-MANALI,17,2543000,"RESTORATION OF ROAD-CUT MADE BY CMWSSB AT PERIYAR NAGAR 5 STREETS REACH- 2 (1200M) IN DN-17, U-4, Z-2.",Deposit Works,2,2016-17,2018-19 NB/2016-17/14264,Road Cut,Completed,NB-MANALI,17,1059000,"RESTORATION OF ROAD-CUT MADE BY CMWSSB AT SOWBAKIYA NAGAR (500M) IN DN-17, U-4, U-2",Deposit Works,2,2016-17,2018-19 NB/2016-17/14266,Road Cut,Completed,NB-MANALI,17,634000,"RESTORATION OF ROAD CUT MADE BY CMWSSB IN VARIOUS STREETS IN KOSAPPUR 2ND PART IN DN-17, U-4, Z-2.",Deposit Works,2,2016-17,2017-18 NB/2016-17/15776,Buildings,Completed,NB-MANALI,17,370000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN SOURCE SEGREGATION SHED IN DN:17, U:4, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/15818,Storm Water Drain,Completed,NB-MANALI,17,58000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN CHENNAI PRIMARY SCHOOL IN ARIYALOOR IN DN:17, U:4, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/15820,Storm Water Drain,Completed,NB-MANALI,17,64000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN CHENNAI PRIMARY SCHOOL AT VADAPERUMBAKKAM IN DN:17, U:4, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/16511,Buildings,Completed,NB-MANALI,17,17900,"REPAIR WORKS DUE TO VARDAH CYCLONE IN CHENNAI PRIMARY SCHOOL IN THEEYAMBAKKAM IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16513,Buildings,Completed,NB-MANALI,17,21900,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR NNMP CENTER IN KOSAPPUR IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16518,Buildings,Completed,NB-MANALI,17,8900,"REPAIR WORKS DUE TO VARDAH CYCLONE IN NNMP SHED IN CHETTIMEDU IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16519,Roads,Completed,NB-MANALI,17,470000,"SUPPLYING AND FIXING NAME BOARDS AFFECTED DUE TO VARDAH CYCLONE IN VARIOUS PLACES IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16543,Buildings,Completed,NB-MANALI,17,62000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN AMMA UNAVAGAM AT VADAPERUMBAKKAM IN DN-17, U-4, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16548,Buildings,Completed,NB-MANALI,17,62000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN AMMA UNAVAGAM IN KOSAPPUR IN DN-17, U-4, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/7269,Buildings,Completed,NB-MANALI,17,996000,"Proposed construction of flood Retaining wall at Kosapur Sowbakia Nagar tank (Phase 1) in Dn-17, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7277,Buildings,Completed,NB-MANALI,17,997000,"Proposed construction of flood Retaining wall at Kosapur Sowbakia Nagar tank (Phase 2) in Dn-17, U-4, Z-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/7279,Buildings,Completed,NB-MANALI,17,995000,"Proposed construction of flood Retaining wall at Kosapur Sowbakia Nagar tank (Phase 3) in Dn-17, U-4, Z-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/7281,Buildings,Completed,NB-MANALI,17,998000,"Proposed construction flood Retaining wall at C.K Madhavan nagar (Phase 2 Cettimedu) in Dn-17, U-4, Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/7426,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF FLOOD RETAINING WALL AT KATHAKUZHI TANK IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/7427,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF FLOOD RETAINING WALL AT THEEYAMBAKKAM POND IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/7428,Buildings,Completed,NB-MANALI,17,998000,"PROPOSED CONSTRUCTION OF FLOOD RETAINING WALL AT THIYAGIVISWANATHA DASS OSR LAND IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/8000,Parks,Completed,NB-MANALI,17,510000,"FLOOD DAMAGED - SUPPLYING AND LAYING TREES AND PLANTS AT VARIOUS PARKS IN DN-15,16 & 17 ,U-4,Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/9201,Roads,Completed,NB-MANALI,17,760000,"FORMING AND LAYING THE BITUMINOUS COURSE AT KOSAPUR SUDUKADU SALAI IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/9203,Roads,Completed,NB-MANALI,17,1658000,"FORMING AND LAYING THE BITUMINOUS COURSE AT DHANALAKSHMI NAGAR IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/9204,Roads,Completed,NB-MANALI,17,1935000,"FORMING AND LAYING THE BITUMINOUS COURSE AT BALAJI NAGAR IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/9205,Roads,Completed,NB-MANALI,17,995000,"FORMING AND LAYING THE BITUMINOUS COURSE AT THIDIL NAGAR IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/9206,Roads,Completed,NB-MANALI,17,1866000,"FORMING AND LAYING THE BITUMINOUS COURSE AT SAMUVEL BURIAL GROUND ROAD IN DN-17,U-4,Z-2.",Own Sources,2,2016-17,2016-17 BR/2016-17/17744,Roads,Completed,BR-Bus Route Roads,18,940000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Kamaraj salai, Kosapur vadaperumpakkam road and Andarkuppam CMDA link road, inZone-2",Grants,2,2016-17,2017-18 NB/2016-17/0481,Parks,Completed,NB-MANALI,18,988000,"IMPROVEMENT WORKS AT PARK IN DIVISION 18, 19, 20 AND 21 UNIT 5 . ZONE 2.",Own Sources,2,2016-17,2016-17 NB/2016-17/0657,Buildings,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF FLOOD RETAINING WALL AT (JAKEER HUSIN STREET JUNCTION TO BHARATHIYAR STREET BURIAL GROUND ) IN DN;18.UNIT;5, ZONE;2.REACH;1(OM TO 175M)",Own Sources,2,2016-17,2016-17 NB/2016-17/12815,Parks,Completed,NB-MANALI,18,965000,"MAINTENANCE OF ALL PARKS AND PLAY FIELD AREAS FOR FOUR MONTHS IN DIVISION 15, 16, 17, 18, 19, 20 AND 21 UNIT 04 & 05 ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/13315,Buildings,Completed,NB-MANALI,18,996000,"PROVIDING CC ROADS, STROM WATER DRAINS AND CULVERT AT (FLOOD DAMAGED AREAS) AT LABBAMEDU SECOND STREET, LINK ROAD FROM NEDUNCHEZHIAN STREET TO CPCL NINTH STREET AND EKAMBARAM STREET IN DIVISION 18, UNIT 05, ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/13435,Storm Water Drain,Completed,NB-MANALI,18,948000,"WIDENING, DEEPENING AND CLEANING OF FLOOD AFFECTED CANAL BY USING POCLAIN AND JCB MACHINE FROM POLICE QUARTERS TO PUZHAL SURPLUS AND FROM CPCL COMPANY TO T.P.P SALAI 200 FEET ROAD JUNCTION IN DN:18,UNIT:5, ZONE:2.",Own Sources,2,2016-17,2019-20 NB/2016-17/14401,Buildings,Completed,NB-MANALI,18,992000,"DESILTING, MAINTENANCE AND IMPROVEMENTS OF STROM WATER DRAIN AT VARIOUS STREETS IN DIVISION 18, UNIT 05 AND ZONE 02,",Own Sources,2,2016-17,2016-17 NB/2016-17/14985,Storm Water Drain,Completed,NB-MANALI,18,992000,"DESILTING, MAINTENANCE AND IMPROVEMENTS OF STORM WATER DRAIN IN BHARATHIYAR STREET, ANNA ST, ZAHEER HUSSIAN STREET AND VARIOUS STREETS IN DIVISION 18, UNIT 05 AND ZONE 02,",Own Sources,2,2016-17,2019-20 NB/2016-17/14993,Buildings,Completed,NB-MANALI,18,920000,"ANNUAL MAINTENANCE FOR ROADS, TOILETS, BUILDINGS, PARKS, STROM WATER DRAINS AND BURIAL GROUNDS IN DIVISION 18, UNIT 05, ZONE 02.",Own Sources,2,2016-17,2018-19 NB/2016-17/15013,Buildings,Completed,NB-MANALI,18,940000,"ANNUAL MAINTENANCE FOR ROADS, TOILETS, BUILDINGS, PARKS, STROM WATER DRAINS AND BURIAL GROUNDS IN DIVISION 18, 19, 20 & 21 UNIT 05, ZONE 02.",Own Sources,2,2016-17,2018-19 NB/2016-17/15528,Buildings,Completed,NB-MANALI,18,930000,"IMPROVEMENTS WORKS TO PUBLIC CONVENIENCE IN DIVISION 18, 19 AND 21 UNIT 05 ZONE 02.",Own Sources,2,2016-17,2017-18 NB/2016-17/15766,Buildings,Completed,NB-MANALI,18,32000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN AMMA UNAVAGAM AT EGAMBARAM STREET IN DN 18, UNIT;5, Z0NE.2",Own Sources,2,2016-17,2017-18 NB/2016-17/15769,Buildings,Completed,NB-MANALI,18,53000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN AMMA UNAVAGAM AT CPCL 3rd STREET AT CPCL LAYOUT IN DN 18, UNIT;5, Z0NE.2",Own Sources,2,2016-17,2017-18 NB/2016-17/15773,Storm Water Drain,Completed,NB-MANALI,18,155000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN S W D AT BHARATHIYAR STREET IN DN 18, UNIT;5, Z0NE.2",Own Sources,2,2016-17,2017-18 NB/2016-17/15775,Buildings,Completed,NB-MANALI,18,979000,"REPAIR WORKS DUE VARDAH CYCLONE IN CREMATION SHED COMPOUND WALL AT BURIAL GROUND ROAD CPCL LAYOUT IN DN;18, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15798,Roads,Completed,NB-MANALI,18,105000,"REPAIR WORKS DUE TO VARDAH CYLONE IN SWD IN HARIKRISHNAPURAM PERUMAL KOIL STREET IN DN:18, U:5, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/15809,Storm Water Drain,Completed,NB-MANALI,18,135000,"REPAIR WORKS DUE VARDAH CYCLONE TO SWD IN SIR C V RAMAN STREET IN DN:18, U:5, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/15811,Storm Water Drain,Completed,NB-MANALI,18,44000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR SWD IN THIRUVALLUR 1ST LANE IN DN:18, U:5, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/15812,Storm Water Drain,Completed,NB-MANALI,18,105000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR SWD IN GRAMA STREET IN DN:18, U:5, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/15814,Storm Water Drain,Completed,NB-MANALI,18,135000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR SWD IN CPCL LAYOUT 2ND MAIN ROAD IN DN 18, U:5, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/15815,Storm Water Drain,Completed,NB-MANALI,18,200000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR SWD IN CPCL LAYOUT 3RD MAIN ROAD IN DN:18, U:5, Z:2",Own Sources,2,2016-17,2017-18 NB/2016-17/16522,Buildings,Completed,NB-MANALI,18,17600,"REPAIR WORKS DUE TO VARDAH CYCLONE IN CHENNAI PRIMARY SCHOOL IN NEDUNCHEZHIAN STREET IN DN-18, U-5, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16524,Roads,Completed,NB-MANALI,18,62000,"SUPPLYING AND REFIXING DAMAGED NAME BOARDS DUE TO VARDAH CYCLONE IN VARIOUS PLACES IN DN-18, U-5, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/16563,Buildings,Completed,NB-MANALI,18,970000,"REPAIR WORKS DUE TO VARDHA CYCLONE FOR PARKS IN DN-18, 19, 20, 21 IN U-5, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16681,Buildings,Completed,NB-MANALI,18,17000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN NNMP CENTER AT THIRUVALLUR STREET IN DN-18, U-5, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/16684,Buildings,Completed,NB-MANALI,18,18000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR NNMP CENTER IN EGAMBARAM STREET IN DN-18, U-5, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/16688,Buildings,Completed,NB-MANALI,18,13000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN NNMP CENTER IN CPCL 1ST MAIN ROAD IN DN-18, U-5, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/16780,Roads,Completed,NB-MANALI,18,880000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR VARIOUS ROADS IN DN-17, DN-18, U-4, U-5, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/2339,Storm Water Drain,Completed,NB-MANALI,18,998000,"IMPROVEMENT WORKS OF EARTH WORKS AND SILT REMOVING AND STRENGTHENING POND BY USING POCLAIN MACHINE AT ZAHIR HUSSAIN POND IN FLOOD FUND IN DN ;18, UNIT;5, ZONE-2",Own Sources,2,2016-17,2016-17 NB/2016-17/2700,Storm Water Drain,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF FLOOD RETAINING WALL AT (JAKEER HUSIN STREET JUNCTION TO BHARATHIYAR STREET BURIAL GROUND ) IN DN;18.UNIT;5, ZONE;2.REACH;2(175M TO 350M)",Own Sources,2,2016-17,2016-17 NB/2016-17/2713,Storm Water Drain,Completed,NB-MANALI,18,998000,"CONSTRUCTION OF FLOOD RETAINING WALL AT (JAKEER HUSIN STREET JUNCTION TO BHARATHIYAR STREET BURIAL GROUND ) IN DN;18.UNIT;5, ZONE;2.REACH;3(350M TO 525M)",Own Sources,2,2016-17,2016-17 NB/2016-17/6571,Roads,Completed,NB-MANALI,18,467000,"FLOOD DAMAGED ROAD - LAYING CC ROAD AT HARIKRISHNAPURAM PERUMAL KOIL LANE IN DIVISION 18,UNIT 05,ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/6864,Buildings,Completed,NB-MANALI,18,999000,"FLOOD DAMAGED - PROPOSED CONSTRUCTION OF CREMATION ROOM AND STORAGE ROOM AT BARATHIYAR STREET BURIAL GROUND INSIDE IN DIVISION 18, UNIT 05, ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/6865,Buildings,Completed,NB-MANALI,18,999000,"PROVIDING FLOOD RETAINING WALL AND COMPOUND WALL AT BARATHIYAR STREET BURIAL GROUND AND ELECTRICAL AND WATER SUPPLY ARRANGEMENTS IN CREMATION ROOM IN DIVISION 18, UNIT 05 ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8003,Parks,Completed,NB-MANALI,18,510000,"FLOOD DAMAGED - SUPPLYING AND LAYING TREES AND PLANTS AT VARIOUS PARKS IN DN-18,19,20 & 21 ,U-5,Z-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/8507,Buildings,Completed,NB-MANALI,18,983000,"ANNUAL MAINTENANCE FOR BUILDINGS, PARKS, ROAD AND BURIAL GROUND IN DIVISION - 18, UNIT - 5 AND ZONE - 2",Own Sources,2,2016-17,2016-17 NB/2016-17/9377,Storm Water Drain,Completed,NB-MANALI,18,992000,"WIDENING, DEEPENING AND CLEANING OF FLOOD AFFECTED CANAL BY USING POCLAIN AND JCP MACHINE AT CPCL FROM CHINNAMATHUR ROAD TO 200 FEET ROAD AND FROM VAIKADU AMULAVAYAL ROAD TO SRF AND TPP SALAI JUNCTION AND 200 FEET ROAD JUNCTION IN DIVISION.18, UITN 05, ZONE 02.",Own Sources,2,2016-17,2019-20 NB/2016-17/0006,Buildings,Completed,NB-MANALI,19,900000,"Proposed construction of compound wall for OSR land at CPCL 2nd street in DN-19, UN-5, ZONE-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/0007,Buildings,Completed,NB-MANALI,19,900000,"Proposed construction of compound wall for OSR land at CPCL 2nd main road in DN-19, UN-5, ZONE-02.",Own Sources,2,2016-17,2016-17 NB/2016-17/0008,Buildings,Completed,NB-MANALI,19,900000,"Proposed construction of compound wall for OSR land at CPCL 3rd street in Dn-19, U-5, Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/0009,Buildings,Completed,NB-MANALI,19,998000,"Proposed construction of compound wall for OSR land at CPCL 1st main raod (North to East) in road in Dn-19, U-5, Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/0010,Buildings,Completed,NB-MANALI,19,998000,"Proposed construction of compound wall for OSR land at CPCL 1st main raod (south to west) in road in Dn-19, U-5, Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/0011,Buildings,Completed,NB-MANALI,19,999000,"Proposed construction of compound wall for OSR land at CPCL 13th street (south to west) in road in Dn-19, U-5, Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/0012,Buildings,Completed,NB-MANALI,19,999000,"Proposed construction of compound wall for OSR land at CPCL 13th street (west to north) in road in Dn-19, U-5, Z-2.",Own Sources,2,2016-17,2016-17 NB/2016-17/0013,Buildings,Completed,NB-MANALI,19,990000,"Proposed construction of compound wall for OSR land at CPCL 12ht street (south to west) in road in Dn-19, U-5, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/0014,Buildings,Completed,NB-MANALI,19,990000,"Proposed construction of compound wall for OSR land at CPCL 12ht street (West to north) in road in Dn-19, U-5, Z-2.",Own Sources,2,2016-17,2019-20 NB/2016-17/0136,Buildings,Completed,NB-MANALI,19,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 21th STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0167,Buildings,Completed,NB-MANALI,19,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 41th STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0177,Buildings,Completed,NB-MANALI,19,975000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 10th STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0178,Buildings,Completed,NB-MANALI,19,941000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 83rd STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0179,Buildings,Completed,NB-MANALI,19,995000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 65th STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0180,Buildings,Completed,NB-MANALI,19,995000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 40TH STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0181,Buildings,Completed,NB-MANALI,19,960000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 6TH STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0182,Buildings,Completed,NB-MANALI,19,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT MMDA 118TH STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0183,Roads,Completed,NB-MANALI,19,998000,"LAYING OF C.C. ROAD AT OMAKULAM CROSS STREET IN DN-19,U-5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0188,Roads,Completed,NB-MANALI,19,414000,"LAYING OF C.C. ROAD AT(FLOOD DAMAGED ROAD) MMDA 75TH STREET IN DN-19,U- 5,Z-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0190,Roads,Completed,NB-MANALI,19,369000,"LAYING OF CC ROAD (FLOOD DAMAGED ROAD) AT NEHRU NAGAR IN DN -19,U-5,ZN-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0191,Roads,Completed,NB-MANALI,19,337000,"LAYING OF C.C.ROAD(FLOOD DAMAGED ROAD) AT MMDA 2ND CROOS STREET IN DN-19,U-5,ZN-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0291,Roads,Completed,NB-MANALI,19,698000,"strengthing the shoulders of both sides on newly layed Road at (CPCL 1st main Road,2nd main Road,CPCL 1st street to 13th streets) in Dn-19,u-5,zn-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0293,Roads,Completed,NB-MANALI,19,862000,"Providing and laying of RMC (M-30) for parking arrangements to park at mmda 3rd cross street in dn-19,u-5,zn-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0315,Roads,Completed,NB-MANALI,19,625000,"strengthing the shoulders of both sides on newly layed road at (babhuji nagar 1st,2nd ,3rd street and 4rh street ) in dn-19,u-5,zn-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0317,Roads,Completed,NB-MANALI,19,625000,"strengthing the shoulders of both sides on newly layed road at (chinna samy 3rd street (part), 5th,6th , and srinivasa street ). in dn-19,u-5,zn-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0506,Buildings,Completed,NB-MANALI,19,903000,"providing Greenery arrangements(creepers) North to South to around GAZEBO at mmda 2nd main Road indn-19,u-5,zn-2(manali)",Own Sources,2,2016-17,2016-17 NB/2016-17/0509,Buildings,Completed,NB-MANALI,19,821000,"Providing Greenery arrangements (creepers) East to West and water supply arrangements to existing park at mmda 2nd main Road in dn-19,u-5,zn-2",Own Sources,2,2016-17,2016-17 NB/2016-17/0543,Parks,Completed,NB-MANALI,19,66000,"providing Greenery arrangements to existing at mmda 2nd main road in dn-19,u-5,zn-2",Own Sources,2,2016-17,2019-20 NB/2016-17/0579,Roads,Completed,NB-MANALI,19,681000,"forming and laying of cc road (near by govt.high school) at mmda 3rd main road in dn-19,u-5,zn-2",Own Sources,2,2016-17,2016-17 NB/2016-17/12111,Roads,Completed,NB-MANALI,19,425000,"Restoration of Road Cut made by TANGEDCO at MMDA 63rd street,MMDA 61st Street and MMDA 69th Street in Dn-19,U-05,ZN-02",Deposit Works,2,2016-17,2017-18 NB/2016-17/12112,Roads,Completed,NB-MANALI,19,590000,"Restoration of Road Cut made by TANGEDCO at MMDA 47th street,MMDA36th Street and MMDA 35th Street in Dn-19,U-05,ZN-02",Deposit Works,2,2016-17,2017-18 NB/2016-17/12310,Parks,Completed,NB-MANALI,19,980000,"PAINTING , COLOUR WASHING ,ARCHITECTURAL PAINTING AND ART WORK IN PARK AT MMDA 2ND MAIN ROAD IN DN-19,U-05,ZN-2(MANALI)",Own Sources,2,2016-17,2017-18 NB/2016-17/12312,Roads,Completed,NB-MANALI,19,381000,"Restoration of Road cut made by TANGEDCO at mmda 45th and mmda 56th street in Dn-19,U-05,Zn-02",Deposit Works,2,2016-17,2017-18 NB/2016-17/12314,Roads,Completed,NB-MANALI,19,588000,"Restoration of road cut made by TANGEDCO at MMDA 44th street and MMDA 44th street 1st cross in dn-19,u-05,zn-02",Deposit Works,2,2016-17,2017-18 NB/2016-17/12315,Roads,Completed,NB-MANALI,19,420000,"Restoration of road cut made by TANGEDCO at MMDA 70th and MMDA 57th street in dn-19,u-05,zn-02",Deposit Works,2,2016-17,2017-18 NB/2016-17/12370,Roads,Completed,NB-MANALI,19,986000,"RESTORATION OF CC ROAD CUT AT MMDA 41ST STREET (FROM 1ST CROSS TO 2ND MAIN ROAD) in div -19 , UNIT -5, Z-02.",Deposit Works,2,2016-17,2016-17 NB/2016-17/12374,Buildings,Completed,NB-MANALI,19,797000,"Proposed construction of disable person toilet in manjambakkam middle school,Rain water harvesting and platform in Chennai primary school at mmda 59th street and and improvements to Amma unavagam at mmda 46 th street in div - 19, unit -05, zone - 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/12384,Buildings,Completed,NB-MANALI,19,563000,"PROVIDING RAINWATER HARVESTING AND SUPPLYING AND FIXING OF BOLLARDS , BARRICATION AT MMDA 2ND MAIN ROAD PARK ,PARTION WORK IN SCHOOL CLASS ROOMS AT MMDA 3RD MAIN ROAD IN DN-19, U-05,ZN-02 (MANALI)",Own Sources,2,2016-17,2019-20 NB/2016-17/14100,Buildings,Completed,NB-MANALI,19,900000,":PROPOSED AND CONSTRUCTION OF COMMUNITY TOILET AT THIDEER NAGAR IN DN-19,U-05,ZN-2",Own Sources,2,2016-17,2019-20 NB/2016-17/15027,Parks,Completed,NB-MANALI,19,865000,"IMPROVEMENTS TO MMDA 2ND MAIN ROAD PARK IN DN-19,U-05,ZN-2",Own Sources,2,2016-17,2019-20 NB/2016-17/15029,Buildings,Completed,NB-MANALI,19,985000,"SUPPLYING AND FIXING G.I.SHEET ALROUND AMMA UNAVAGAM AT MMDA 4TH CROSS STREET AND 16TH CEREMONY HALL IN DN-19,U-5,ZN-2",Own Sources,2,2016-17,2017-18 NB/2016-17/15039,Parks,Completed,NB-MANALI,19,985000,"SUPPLYING AND FIXING WELLRING FOR TREE GRATING,HONEY COMB BRICKS FOR GARDEN WORKS,GRANITE SLAB AND REFIXING OF ACUPUNCTURE WALK AT MMDA 2ND MAIN ROAD PARK IN DN-19,U-05,ZN-2",Own Sources,2,2016-17,2019-20 NB/2016-17/15270,Buildings,Completed,NB-MANALI,19,985000,"PROPOSED CONSTRUCTION OF SOURCE SEGREGATION SHED AT KAMARAJAR SALAI (BURIAL GROUND) IN DN-19,U-05,ZN-2",Own Sources,2,2016-17,2018-19 NB/2016-17/15605,Roads,Completed,NB-MANALI,19,963000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT ,MMDA 1ST STREET,MMDA 2ND STREET, MMDA 3RD STREET AND MMDA 1ST CROSS STREET IN DN-19,U-05,ZN-02(MANALI)",Deposit Works,2,2016-17,2016-17 NB/2016-17/15611,Buildings,Completed,NB-MANALI,19,900000,"Construction of interior works for Gazebo (plumbing and ornamental works) inside the park at MMDA 2nd Main Road in Dn-19,u-05,zn-02",Own Sources,2,2016-17,2019-20 NB/2016-17/15780,Storm Water Drain,Completed,NB-MANALI,19,239000,"DAMAGED INFRASTRUCTURE REPAIR WORK DUE TO VARADHA CYCLONE (SWD) AT MMDA 2ND AND 3RD CROSS STREET IN DN-19,U-05,ZN-02",Own Sources,2,2016-17,2017-18 NB/2016-17/15782,Parks,Completed,NB-MANALI,19,125000,"DAMAGED INFRASTRUCTURE REPAIR WORK DUE TO VARADHA CYCLONE (GRILL,PLAY APPRATUS) AT MMDA 2ND MAIN ROAD PARK,MMDA 71TH STREET AND TEACHERS NAGAR IN DN-19,U-05,ZN-02",Own Sources,2,2016-17,2017-18 NB/2016-17/15784,Footpath,Completed,NB-MANALI,19,135000,":DAMAGED INFRASTRUCTURE REPAIR WORK DUE TO VARADHA CYCLONE (FOOT PATH AND STREET FURNISHING) AT MMDA 1ST ,2ND AND 3R MAIN ROAD,LAKE VIEW APARTMENT PARKAND ELLATHARSI STREET IN DN-19,U-05,ZN-02",Own Sources,2,2016-17,2017-18 NB/2016-17/15785,Buildings,Completed,NB-MANALI,19,228000,":DAMAGED INFRASTRUCTURE REPAIR WORK DUE TO VARADHA CYCLONE (PURLIN AND PLUMBING WORKS) AT ARULANDHA NAGAR COMPOSED YARD AND AMMA UNAVAGAM MMDA 46TH STREET AND MANJAMBAKKAM IN DN-19,U-05,ZN-02",Own Sources,2,2016-17,2017-18 NB/2016-17/17715,Roads,Completed,NB-MANALI,19,963000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT ,MMDA 28TH STREET,MMDA 37TH STREET AND MMDA 46TH STREET IN DN-19,U-05,ZN-02(MANALI)",Deposit Works,2,2016-17,2016-17 NB/2016-17/18229,Electrical,Completed,NB-MANALI,19,46000,"Supply and Erection 3 No of 3 mtr GI Lamp Post With 3 nos of 2x18 w CFL Garden type fittings in MMDA 34th street PARK in div - 19 , Zone-II, Manali .","Loans, Grants And Own Sources",2,2016-17,2017-18 NB/2016-17/18709,Roads,Completed,NB-MANALI,19,89000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT MMDA 49TH STREETT IN DN-19,U-05,ZN-02(MANALI)",Deposit Works,2,2016-17,2017-18 NB/2016-17/18727,Roads,Completed,NB-MANALI,19,872000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT ,MMDA 6TH ,7TH,8TH,48TH,29TH & 59TH STREET,MMDA 4TH CROSS STREET AND MMDA 33RD STREET 1ST CROSS IN DN- 19,U-05,ZN-02(MANALI)",Deposit Works,2,2016-17,2016-17 NB/2016-17/19015,Roads,Completed,NB-MANALI,19,975000,"RESTORATION OF ROAD CUT MADE BY (TANGEDCO) AT 58TH,64TH,65TH,66TH,67TH, AND MMDA 2ND CROSS STREET IN DN-19,U-05,ZN-02(MANALI)",Deposit Works,2,2016-17,2016-17 NB/2016-17/4569,Parks,Completed,NB-MANALI,19,995000,"IMPROVEMENTS WORKS IN PARK DUE TO FLOOD DAMAGED PORTIONS AT MMDA 2ND MAIN ROAD IN DIVISION 19, UNIT 05, ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/4572,Storm Water Drain,Completed,NB-MANALI,19,995000,"Repairs and improvements to existing storm water drain and desilting at various streets dn-19,u-05,zn-2(manali).",Own Sources,2,2016-17,2016-17 NB/2016-17/5750,Road Cut,Completed,NB-MANALI,19,874000,"Restoration of Road cut made by TANGEDCO at MMDA 1st Main Road in dN-19,U-05,ZN-02(MANALI).",Deposit Works,2,2016-17,2016-17 NB/2016-17/5754,Roads,Completed,NB-MANALI,19,996000,"Restoration of Road cut made by TANGEDCO at MMDA 2nd Main Road in dN-19,U-05,ZN-02(MANALI).",Deposit Works,2,2016-17,2016-17 NB/2016-17/5755,Roads,Completed,NB-MANALI,19,999000,"Restoration of Road cut made by TANGEDCO at MMDA 3rd Main Road Dn-19,u-05,Zn-2 (manali)",Deposit Works,2,2016-17,2017-18 NB/2016-17/6809,Roads,Completed,NB-MANALI,19,998000,"CONSTRUCTION STORE ROOM AND FACE LIFTING OF ENTRANCE OF PARK STORE AT MMDA 2ND MAIN ROAD IN DN-19,UNIT-5,ZONE-2",Own Sources,2,2016-17,2017-18 NB/2016-17/7531,Buildings,Completed,NB-MANALI,19,810000,"CONSTRUCTION OF COMPOUND WALL FOR FLOOD AFFECTED POND AT KULAKARAI STREET(EAST AND SOUTH SIDE ) IN DN-19, UN-5, ZONE-02.",Own Sources,2,2016-17,2017-18 NB/2016-17/7556,Roads,Completed,NB-MANALI,19,890000,"RESTORATION OF CC ROAD CUT MADE BY (TANGEDCO) AT MMDA 4TH,5TH,9TH,38TH,40TH,42ND,43RD,50TH,53RD, 54TH AND 55TH STREET in div -19 , U-5,ZN-2",Deposit Works,2,2016-17,2017-18 BR/2016-17/9756,Storm Water Drain,Completed,BR-Bus Route Roads,20,11295000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Chinnamathur Road in div 20, Zone -02.",Grants,2,2016-17,2017-18 NB/2016-17/0157,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF TOILET BLOCK INSIDE LORRY DEPOT AT KAMARAJAR SALAI , IN DN;20, UNIT;5, ZONE;II.",Own Sources,2,2016-17,2016-17 NB/2016-17/11011,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF LAKE BOUNDARY FLOOD RETAINING WALL AT KAMARAJAR SALAI ( NEW M G R NAGAR 1ST STREET) (REACH-2) IN DN ;20, UNIT;05, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/11301,Buildings,Completed,NB-MANALI,20,897000,"CONSTRUCTION OF COMPOUND WALL(NORTH SIDE OFSHEDDING MACHINE SHED)IN SIDE THE DUMPING YARD AT KAMARAJAR SALAI , IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2016-17 NB/2016-17/11411,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF LAKE BOUNDARY FLOOD RETAINING WALL AT KAMARAJAR SALAI ( NEW M G R NAGAR 1ST STREET) (REACH-3) IN DN ;20, UNIT;05, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/11625,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF LAKE BOUNDARY FLOOD RETAINING WALL AT KAMARAJAR SALAI ( NEW M G R NAGAR 1ST STREET) (REACH-4) IN DN ;20, UNIT;05, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/11847,Buildings,Completed,NB-MANALI,20,940000,"ANNUAL MAINTENANCE FOR BUILDINGS, PARKS, BURIAL GROUND AND ROADS IN DIVISION 20, UNIT 05 ZONE 02.",Own Sources,2,2016-17,2016-17 NB/2016-17/12094,Buildings,Completed,NB-MANALI,20,540000,"CONSTRUCTION OF SOURCE SEGREGATION SHED AND FENCING THE EXITING COMPOUND WALL IN THE BURIAL GROUND AT SRINIVASAPERUMAL KOIL STREET IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/12908,Buildings,Completed,NB-MANALI,20,710000,"CONSTRUCTION OF PUBLIC CONVENIENCE AT JUNCTION OF BURIAL GROUND ROAD AND OTTRAIVADAI STREET IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2018-19 NB/2016-17/13428,Storm Water Drain,Completed,NB-MANALI,20,950000,"WIDENING, DEEPENING AND CLEANING OF FLOOD AFFECTING CANAL BY USING POCLAIN AND JCB MACHINE FROM POLICE QUARTERS TO TTP SALAI 200 FEET ROAD JUNCTION AND KAMARAJAR SALAI FROM FIRE SERVICE STATION TO CPCL ( BOTH SIDES OF ROAD) IN DN;20 & 21,UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/13722,Buildings,Completed,NB-MANALI,20,760000,"IMPROVEMENT WORKS INSIDE THE DUMPING YARD (FORMING EARTHEN ROAD ,PROVIDING BORE, PLUMBING WORKS AND J.C.B. WORKS) AT KAMARAJAR SALAI, IN DN;20, UNIT;5, ZONE;2",Own Sources,2,2016-17,2019-20 NB/2016-17/13723,Buildings,Completed,NB-MANALI,20,950000,"IMPROVEMENT WORKS INSIDE LORRY DEPOT( FENCING WORKS ,FILLING WORKS & PROVIDING KERB WALL AND OTHER WORKS) AT KAMARAJAR SALAI IN DN;20 ,UNIT;5, ZONE;2.",Own Sources,2,2016-17,2018-19 NB/2016-17/14972,Buildings,Completed,NB-MANALI,20,990000,"CLEARING OF GARBAGES ON (WEST SIDE) INSIDE TPF TO FACILITATE FOR THE PROPOSED CONSTRUCTION OF TALUK OFFICE ,COURT , AND REGISTER OFFICE AT KAMARAJAR SALAI, IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2018-19 NB/2016-17/15036,Storm Water Drain,Completed,NB-MANALI,20,365000,"MAINTENANCE WORKS TO BUILDINGS, ROAD, FOOTPATHS, SWD, PARKS AND PLAYFIELD DN;21, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2016-17 NB/2016-17/15462,Buildings,Completed,NB-MANALI,20,829000,"CLEANING GARBAGE ON ( EAST SIDE) INSIDE OF TPF TO FECILITATES FOR THE COURT, RESISTER OFFICE,AT KAMARAJAR SALAI. IN DN;20, UNIT;5, ZONE;2",Own Sources,2,2016-17,2018-19 NB/2016-17/15743,Buildings,Completed,NB-MANALI,20,332000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR SHREDDING MACHINE SHED IN DUMPING YARD AT KAMARAJAR SALAI IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15744,Buildings,Completed,NB-MANALI,20,209000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR LORRY DEPOT AT KAMARAJAR SALAI IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15745,Buildings,Completed,NB-MANALI,20,244000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR AMMA UNAVAGAM AT KAMARAJAR SALAI(NEAR FIRE SERVICE STATION) AND ( NEW MGR NAGAR IST STREET) IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15748,Storm Water Drain,Completed,NB-MANALI,20,200000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR S W D AT THAMARAIKULAM 2ND STREET AND LAL BAGATHUR SHASTRI STREET DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/15759,Buildings,Completed,NB-MANALI,20,20900,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR ALUMINIUM DOOR AND WINDOWS IN DIVISION OFFICE BUILDING AT NEW M G R NAGAR IST STREET IN DN20, UNIT;5, ZONE;2,.",Own Sources,2,2016-17,2017-18 NB/2016-17/16759,Buildings,Completed,NB-MANALI,20,6700,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR NNMP SHED AT KALTHOTTAM MGR STREET, SRINIVASAPERUMAL KOIL STREET AND NEW MGR NAGAR 1ST STREET IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2017-18 NB/2016-17/9491,Storm Water Drain,Completed,NB-MANALI,20,982000,"DE-SILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2016-17 L/2016-17/13826,Electrical,Completed,L-Electrical,21,229600,"Replacement of 8 nos of Damaged Kiosk Pillar Boxes at Thiruvenkadam St, and Various locations in Division ,18,19,20 and,21 in Zone II(Manali)(Sch of Rate 2015-16)",Own Sources,2,2016-17,2017-18 NB/2016-17/0001,Buildings,Completed,NB-MANALI,21,510000,"MAINTENANCE WORKS FOR SCHOOL BUILDING, GYM AND SWD IN DN.21, UNIT;5, ZONE;II.",Own Sources,2,2016-17,2016-17 NB/2016-17/0996,Buildings,Completed,NB-MANALI,21,379000,"MAINTENANCE WORKS TO BUILDINGS, ROAD, FOOTPATHS, SWD, PARKS AND PLAYFIELD DN;21, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2016-17 NB/2016-17/14788,Electrical,Completed,NB-MANALI,21,620000,"Painting and Numbering of Street Lamp Post and Pillar Boxes in Division-18,19,20 and 21, of Zone-II, Manali(As per 2015-16 SOR) Description: Painting and Numbering of Street Lamp Post and Pillar Boxes in Division-18,19,20 and 21, of Zone-II, Manali(As per 2015-16 SOR)","Loans, Grants And Own Sources",2,2016-17,2016-17 NB/2016-17/15110,Buildings,Completed,NB-MANALI,21,970000,"PROPOSAL FOR SUPPLY OF BIO - GAS PLANT IN AMMA CANTEEN AT PADASALAI STREET IN DIV - 21, U - 5, Z - 2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16496,Buildings,Completed,NB-MANALI,21,18000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR AMMA UNAVAGAM AT JALAGANDA MARIAMMAN STREET IN DN-21, U-5, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/16500,Buildings,Completed,NB-MANALI,21,17000,"REPAIR WORKS DUE TO VARDAH CYCLONE FOR AMMA UNAVAGAM IN PADASALAI STREET IN DN-21, U-5, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16501,Buildings,Completed,NB-MANALI,21,17000,"REPAIR WORKS DUE TO VARDAH CYCLONE IN CHENNAI PRIMARY SCHOOL IN PADASALAI STREET AT DN-21, U-5, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16505,Buildings,Completed,NB-MANALI,21,17300,"REPAIR WORKS DUE TO VARDAH CYCLONE AT ZONAL OFFICE BUILDING IN PADASALAI STREET IN DN-21, U-5, Z-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/16506,Buildings,Completed,NB-MANALI,21,22000,"REPAIR WORKS DUE VARDAH CYCLONE IN URBAN PRIMARY HEALTH CENTER AT PADASALAI STREET IN DN-21, U-5, Z-2",Own Sources,2,2016-17,2017-18 NB/2016-17/19275,Electrical,Completed,NB-MANALI,21,81700,"Supply and fixing 21 nos of 1x18 w CFL Garden type fittings in various PARK , Ward-18,20 & 21, (Unit - 5) Zone-II, Manali .",Own Sources,2,2016-17,2017-18 NB/2016-17/3853,Roads,Completed,NB-MANALI,21,997000,"CONSTRUCTION OF GATE PILLARS,COMPOUND WALL,IMPROVEMENTS TO PASSENGER WAITING HALL AND LAYING CEMENT CONCRETE FLOORING IN APPROACH ROAD FOR NEDUNCHEZHIAN STREET IN FRONT OF MANALI BUS STAND AT NEDUNCHEZIAN STREET IN DN-21,UNIT-5,ZONE-2.",Own Sources,2,2016-17,2017-18 NB/2016-17/9494,Storm Water Drain,Completed,NB-MANALI,21,940000,"DE-SILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN;21, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2016-17 NB/2016-17/9777,Buildings,Completed,NB-MANALI,21,227000,"MAINTENANCE WORKS TO BUILDINGS, ROAD, FOOTPATHS, SWD, PARKS AND PLAYFIELD DN;21, UNIT;5, ZONE;2.",Own Sources,2,2016-17,2016-17 BR/2016-17/9766,Storm Water Drain,Completed,BR-Bus Route Roads,22,21125000,"Strengthening and relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Gandhi Main Road in div 22, Zone -03.",Grants,3,2016-17,2017-18 L/2016-17/13745,Electrical,Completed,L-Electrical,22,191500,Provision for supply and fixing 12 nos of Automatic Timer unit at various locations in division-22 of zone-3.,Own Sources,3,2016-17,2018-19 L/2016-17/13824,Electrical,Completed,L-Electrical,22,172400,"Removal & Refixing of 39nos of Kiosk Pillar Box at Various location in Div- 22,23,24 and 28, Zone-III, Madhavaram .",Own Sources,3,2016-17,2019-20 L/2016-17/14898,Electrical,Completed,L-Electrical,22,181100,"Painting of 1018 Nos of 6mtr lamp post, single straight bracket,4 Nos of 9mtr Lamp post & 38 nos of KIOSK Pillar box at Various streets in Div-22 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2018-19 NC/2016-17/1034,Buildings,Completed,NC-MADHAVARAM,22,993000,"IMPROVEMENTS AND REPAIRS TO DIVISION OFFICE ,CORPORATION BUILDINGS,PARKS AND ROADS IN DN-22,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/10493,Buildings,Completed,NC-MADHAVARAM,22,689000,"IMPROVEMENT AND WATER FLOOR ARRANGMENT NNMB SHED AT GANDHI ST, JEEVA ST IN DN22 UNIT 6 ZONE3",Own Sources,3,2016-17,2016-17 NC/2016-17/10495,Buildings,Completed,NC-MADHAVARAM,22,639000,IMPROVEMENT AND WATER SUPPLY &ELECTRICALS WORK AT NSC BOSE ST TOILETIN DN22 UNIT6 ZONE3,Own Sources,3,2016-17,2016-17 NC/2016-17/10503,Buildings,Completed,NC-MADHAVARAM,22,622000,IMPROVEMENT AND WATERSUPPLY ELECTRICAL &WALLTILES KANNAPPASAMY NAGAR SCHOOL TOILET INSIDE IN DN22 UNIT 6 ZONE3,Own Sources,3,2016-17,2018-19 NC/2016-17/10724,Roads,Completed,NC-MADHAVARAM,22,2011000,"FORMING BT ROAD BY PAVER FINISHER AT THAMIZHAN NAGAR MAIN STREET IN DN 22, UNIT 6, ZONE 3.",Own Sources,3,2016-17,2016-17 NC/2016-17/10726,Roads,Completed,NC-MADHAVARAM,22,1361000,"FORMING BT ROAD BY PAVER FINISHER AT SIVARAJ 1ST STREET IN DN 22, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/12767,Buildings,Completed,NC-MADHAVARAM,22,970000,"REPAIRS AND IMPROVEMENTS TO EXISTING BUILDING FOR AMMAKUDENEER AT GANDHI MAIN ROAD IN DN-22,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/15905,Parks,Completed,NC-MADHAVARAM,22,163000,"REPAIRS AND IMPROVEMENTS TO MACRO MARVEL PARK (DAMAGE DUE TO VARDHA CYCLON) IN DN-22,U-6,Z-3",Own Sources,3,2016-17,2017-18 NC/2016-17/15908,Parks,Completed,NC-MADHAVARAM,22,190000,"REPAIRS AND IMPROVEMENTS TO GURUSHANTHI NAGAR PARK(DAMAGE DUE TO VARDHA CYCLON) IN DN-22,U-6,Z-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/16464,Buildings,Completed,NC-MADHAVARAM,22,150000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM (DAMAGE DUE TO VARDHA CYCLON) AT PERUMAL KOIL STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/16562,Footpath,Completed,NC-MADHAVARAM,22,120000,"REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE (DAMAGE DUE TO VARDHA CYCLON) AT GANDHI 1st STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/16959,Buildings,Completed,NC-MADHAVARAM,22,800000,"REPAIRS AND IMPROVEMENTS TO NNMP SHED (DAMAGE DUE TO VARDHA CYCLON) AT K.S NAGAR 6th STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17025,Buildings,Completed,NC-MADHAVARAM,22,120000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM (DAMAGE DUE TO VARDHA CYCLON) AT G.N.T SERVICE ROAD IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17026,Roads,Completed,NC-MADHAVARAM,22,172000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT GEEVA MAIN STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17128,Roads,Completed,NC-MADHAVARAM,22,172000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT MERCY NAGAR IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17129,Roads,Completed,NC-MADHAVARAM,22,446000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT KRISHNA NAGAR 1st STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17130,Roads,Completed,NC-MADHAVARAM,22,446000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT KRISHNA NAGAR 2nd STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17131,Roads,Completed,NC-MADHAVARAM,22,994000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT BHARATHIDHASAN STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17132,Roads,Completed,NC-MADHAVARAM,22,172000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT VOC STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17134,Roads,Completed,NC-MADHAVARAM,22,514000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT RETTAIMALAI SRINIVASAN STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17135,Roads,Completed,NC-MADHAVARAM,22,950000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT AMBEDKAR STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17136,Roads,Completed,NC-MADHAVARAM,22,1045000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT ANNA NINIAVU NAGAR MAIN STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17137,Roads,Completed,NC-MADHAVARAM,22,583000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT GANGADARAN 1st STREET IN DIVISION-22,UNIT-6,ZONE-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17138,Roads,Completed,NC-MADHAVARAM,22,377000,"ATTENDING TEMPORARY RESTORATION OF DAMAGED ROADS DUE TO CYCLONE AT GANGADARAN 2nd STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17177,Buildings,Completed,NC-MADHAVARAM,22,100000,"REPAIRS AND IMPROVEMENTS TO SCHOOL BUILDING (DAMAGE DUE TO VARDHA CYCLON) AT GANDHI MAIN STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17179,Buildings,Completed,NC-MADHAVARAM,22,150000,"REPAIRS AND IMPROVEMENTS TO SCHOOL BUILDING (DAMAGE DUE TO VARDHA CYCLON) AT K.S NAGAR MIDDLE SCHOOL IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17187,Buildings,Completed,NC-MADHAVARAM,22,150000,"REPAIRS AND IMPROVEMENTS TO NNMP SHED (DAMAGE DUE TO VARDHA CYCLON) AT JEEVA STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17206,Buildings,Completed,NC-MADHAVARAM,22,300000,"REPAIRS AND IMPROVEMENTS TO BURIAL GROUND (DAMAGE DUE TO VARDHA CYCLON) AT KANADA PALAYAM JEEVE STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17207,Roads,Completed,NC-MADHAVARAM,22,290000,"REPAIRS AND NEW FIXING TO STREET NAME BOARD (DAMAGE DUE TO VARDHA CYCLON) AT VARIOUS STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17208,Footpath,Completed,NC-MADHAVARAM,22,1027000,"REPAIRS AND IMPROVEMENTS TO FOOT PATH(DAMAGE DUE TO VARDHA CYCLON) AT GANDHI MAIN ROAD ,GURUSHANTHI MAIN ROAD,THIRUNEELA GANDAN MAIN STREET,1sT,2nd AND 3rd STREET IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/2717,Storm Water Drain,Completed,NC-MADHAVARAM,22,885000,"Construction of culvert at Vegiterian Village in Div-22, Unit-6, zone-3",Own Sources,3,2016-17,2018-19 NC/2016-17/2725,Storm Water Drain,Completed,NC-MADHAVARAM,22,837000,"Construction of culvert at Devi Nagar, Madha Nagar, Tamizhan Nagar, in Div-22, Unit-6, Zone-3",Own Sources,3,2016-17,2018-19 NC/2016-17/2810,Storm Water Drain,Completed,NC-MADHAVARAM,22,604000,"Consturction of Culvert at Bhuvaneshwari Nagar, Adhinath Baghavan Garden in Div-22, Unit-6, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/2811,Storm Water Drain,Completed,NC-MADHAVARAM,22,650000,"Construction of Culver at Kanchi Arul Nagar and K.S. Nagar 28th street in div-22, Unit-6, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/2918,Storm Water Drain,Completed,NC-MADHAVARAM,22,775000,"Desilting of Side drain at K.S. Nagar, Lalbhaghadhur sastri st, Pillaiyar kovil st, Vallouvar st, Perumal kovil st, Panner selvam st, Jeeva 2nd st, Gurusanthi Nagar, Shathini Avenue, Mariammal Nagar, Mahavir Garden, Thirunneelakand Nagar, Meenakshi nagar, Mahalakshmi nagar, Sakthivel Nagar, Indra Nagar and Vellaichamy st in div-22, Unit6, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/3733,Buildings,Completed,NC-MADHAVARAM,22,998000,"CONSTRUCTION OF CULVERT AND IMPROVEMENT TO SIDE DRAIN AT ATHINATH BHAVAN COLONY ,SATHIVAL NAGAR AND THIRU NELAGANDAN NAGAR IN DN-22,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/3737,Storm Water Drain,Completed,NC-MADHAVARAM,22,999000,"CONSTRUCTION OF SIDE DRAIN AT MATHA NAGAR (NORTH) IN DN-22,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/3741,Roads,Completed,NC-MADHAVARAM,22,999000,"SUPPLYING AND FIXING OF NAME BOARD AT SATHIVAL NAGAR ,THIRU NELAGANDAN NAGAR ,MATHA NAGAR ,JOSEP NAGAR ,SRIDEVI NAGAR ,RAGAVENDRA NAGAR AND ATHI BAHAVAN GARDEN IN DN-22,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/5720,Buildings,Completed,NC-MADHAVARAM,22,585000,"SUPPLYING AND FIXING TWO FEET DIA HUME PIPE AT MAHAVERAR GARDEN AND EATHIRAJ AVENU IN DN-22,U-6,Z-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/6229,Roads,Completed,NC-MADHAVARAM,22,374000,"Restoration of Road Cut Made by CMWSS Board at Sivaraj 1st Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6232,Roads,Completed,NC-MADHAVARAM,22,374000,"Restoration of Road Cut Made by CMWSS Board at V.O.C Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6233,Roads,Completed,NC-MADHAVARAM,22,715000,"Restoration of Road Cut Made by CMWSS Board at Mariyammal Nagar Main Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6234,Roads,Completed,NC-MADHAVARAM,22,156000,"Restoration of Road Cut Made by CMWSS Board at Mariyammal Nagar 1st Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6235,Roads,Completed,NC-MADHAVARAM,22,664000,"Restoration of Road Cut Made by CMWSS Board at Mariyammal Nagar 2nd Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6236,Roads,Completed,NC-MADHAVARAM,22,609000,"Restoration of Road Cut Made by CMWSS Board at Thiruneelagandan 4th Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6237,Roads,Completed,NC-MADHAVARAM,22,446000,"Restoration of Road Cut Made by CMWSS Board at Thiruneelagandan 5th Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6252,Roads,Completed,NC-MADHAVARAM,22,72000,"Restoration of Road Cut Made by CMWSS Board at Thamizhan Nagar 2nd Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6253,Roads,Completed,NC-MADHAVARAM,22,72000,"Restoration of Road Cut Made by CMWSS Board at Thamizhan Nagar 3rd Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6254,Roads,Completed,NC-MADHAVARAM,22,137000,"Restoration of Road Cut Made by CMWSS Board at Thamizhan Nagar 4th Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6255,Roads,Completed,NC-MADHAVARAM,22,442000,"Restoration of Road Cut Made by CMWSS Board at Kanchi Arul Nagar Main Road in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6256,Roads,Completed,NC-MADHAVARAM,22,258000,"Restoration of Road Cut Made by CMWSS Board at Kanchi Arul Nagar 1st Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6257,Roads,Completed,NC-MADHAVARAM,22,239000,"Restoration of Road Cut Made by CMWSS Board at Kanchi Arul Nagar 2nd Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6258,Roads,Completed,NC-MADHAVARAM,22,220000,"Restoration of Road Cut Made by CMWSS Board at Sathivel Nagar 34th Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6259,Roads,Completed,NC-MADHAVARAM,22,376000,"Restoration of Road Cut Made by CMWSS Board at Sathivel Nagar 29th Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6260,Roads,Completed,NC-MADHAVARAM,22,221000,"Restoration of Road Cut Made by CMWSS Board at Sathivel Nagar 31th Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6261,Roads,Completed,NC-MADHAVARAM,22,922000,"Restoration of Road Cut Made by CMWSS Board at Gandhi Main Road in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6262,Roads,Completed,NC-MADHAVARAM,22,751000,"Restoration of Road Cut Made by CMWSS Board at K.S Main Road South in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6263,Roads,Completed,NC-MADHAVARAM,22,751000,"Restoration of Road Cut Made by CMWSS Board at K.S Main Road North in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6264,Roads,Completed,NC-MADHAVARAM,22,801000,"Restoration of Road Cut Made by CMWSS Board at K.S Nagar 1st Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6265,Roads,Completed,NC-MADHAVARAM,22,590000,"Restoration of Road Cut Made by CMWSS Board at K.S Nagar 2nd Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6271,Roads,Completed,NC-MADHAVARAM,22,528000,"Restoration of Road Cut Made by CMWSS Board at Sathivel Nagar 32th Street in div-22, Unit-6, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/8634,Buildings,Completed,NC-MADHAVARAM,22,998000,"Supply, Installation and Commissioning of High Quality Treated Drinking Water Plant (RO/UV Filtration of 2000 litres / Hours Capacity at Gandhi Main street in div-22, Unit-6, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/8635,Buildings,Completed,NC-MADHAVARAM,22,980000,"Operation and Maitenance of High Quality Treated Drinking Water Plant (RO/UV Filtration of 2000 litres / Hours Capacity For 1 year Period at Gandhi Main street in div-22, Unit-6, Zone-3",Own Sources,3,2016-17,2018-19 P/2016-17/19671,Parks,Completed,P-Parks and Playfields,22,3622000,"FORMATION OF NEW PARK AT MACRO MARVEL VEGETARIAN VILLAGE,PUZHAL IN DN-22, UNIT-6, ZONE-3",Grants,3,2016-17,2019-20 L/2016-17/13746,Electrical,Completed,L-Electrical,23,191500,Provision for supply and fixing 12 nos of Automatic Timer Unit at various locations in division-23 of zone-3.,Own Sources,3,2016-17,2018-19 L/2016-17/14900,Electrical,Completed,L-Electrical,23,156300,"Painting of 761 Nos of 6mtr lamp post, single straight bracket,20 Nos of 9mtr Lamp post in Div.23 & 74 nos of KIOSK Pillar box at Various streets in Div-23 and Div 24 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2018-19 NC/2016-17/1032,Buildings,Completed,NC-MADHAVARAM,23,996000,"IMPROVEMENTS AND REPAIRS TO DIVISION OFFICE ,CORPORATION BUILDINGS,PARKS AND ROADS IN DN-23,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/10743,Roads,Completed,NC-MADHAVARAM,23,2286000,"FORMING BT ROAD BY PAVER FINISHER AT SRI BALAJI NAGAR MAIN ROAD IN DN 23, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/10746,Roads,Completed,NC-MADHAVARAM,23,273000,"FORMING BT ROAD BY PAVER FINISHER AT SRI BALAJI NAGAR 1ST STREET IN DN 22, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/10748,Roads,Completed,NC-MADHAVARAM,23,196000,"FORMING BT ROAD BY PAVER FINISHER AT SRI BALAJI NAGAR 2ND STREET IN DN 22, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/10749,Roads,Completed,NC-MADHAVARAM,23,131000,"FORMING BT ROAD BY PAVER FINISHER AT BALAJI NAGAR 3RD STREET IN DN 23, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/10750,Roads,Completed,NC-MADHAVARAM,23,131000,"FORMING BT ROAD BY PAVER FINISHER AT BALAJI NAGAR 4TH STREET IN DN 23, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/10751,Roads,Completed,NC-MADHAVARAM,23,131000,"FORMING BT ROAD BY PAVER FINISHER AT BALAJI NAGAR 5TH STREET IN DN 23, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/10752,Roads,Completed,NC-MADHAVARAM,23,131000,"FORMING BT ROAD BY PAVER FINISHER AT BALAJI NAGAR 6TH STREET IN DN 23, UNIT 6, ZONE 3",Own Sources,3,2016-17,2016-17 NC/2016-17/12942,Buildings,Completed,NC-MADHAVARAM,23,998000,"CONSTRUCTION OF AMMA UNAVAGAM PHASE -II AT EMS STREET IN DIV-23, UNIT-6, ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17230,Buildings,Completed,NC-MADHAVARAM,23,200000,"REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE (DAMAGE DUE TO VARDHA CYCLON) AT GNT SERVICE ROAD IN DIVISION-23,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17231,Buildings,Completed,NC-MADHAVARAM,23,300000,"REPAIRS AND IMPROVEMENTS TO NNMP SHED (DAMAGE DUE TO VARDHA CYCLON) AT THIRUVEETHI AMMAN KOIL STREET AND LAKSHMI AMMAN KOIL STREET IN DIVISION-23,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17232,Buildings,Completed,NC-MADHAVARAM,23,600000,"REPAIRS AND IMPROVEMENTS TO BURIAL GROUND (DAMAGE DUE TO VARDHA CYCLON) AT GNT ROAD IN DIVISION-23,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17234,Roads,Completed,NC-MADHAVARAM,23,190000,"REPAIRS AND NEW FIXING TO STREET NAME BOARD (DAMAGE DUE TO VARDHA CYCLON) AT VARIOUS STREET IN DIVISION-23,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17235,Storm Water Drain,Completed,NC-MADHAVARAM,23,300000,"REPAIRS AND IMPROVEMENTS TO SWD (DAMAGE DUE TO VARDHA CYCLON) AT ST.ANTHONEYAR KOIL 4th STREET IN DIVISION-23,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/2915,Storm Water Drain,Completed,NC-MADHAVARAM,23,474000,"Desiliting of side Drain at Stephen Thirumaran street,Stephen Thirumaran 1st cross street,Thalanuthu natarajan street, St.Antony kovil main street,St.Antony kovil 3rd street,Lakshmi amman kovil 2nd cross street,Lakhmi ammam kovil 3rd cross strret,St.Antony kovil main street,Otrai vadai street in div-23, Unit-6, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/3655,Buildings,Completed,NC-MADHAVARAM,23,998000,"PROVIDING ROOFING ARRANGEMENTS AT FOOT BALL GROUND FOR OPEN GALARY (EASTEN SIDE) AT ERATTAIMALAI SRINIVASAN STREET IN DN 23, UNIT 6,ZONE III.",Own Sources,3,2016-17,2016-17 NC/2016-17/3743,Playfields,Completed,NC-MADHAVARAM,23,998000,"IMPROVEMENTS TO PLAY FIELD AT ANNA NINAIVU NAGAR ANGANVADI CENTER AND CONSTRUCTION OF CULVET IN DN-23,U-6,Z-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/4083,Roads,Completed,NC-MADHAVARAM,23,267000,"Restoration of Road Cut Made by CMWSS Board at St. Anthoniyar 4th Cross Street in div-23, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4626,Roads,Completed,NC-MADHAVARAM,23,286000,"Restoration of Road Cut Made by CMWSS Board at Gangadharan 3rd Street in div-23, Unit-6, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5026,Roads,Completed,NC-MADHAVARAM,23,203000,"Restoration of Road Cut Made by CMWSS Board at South Telephone Colony 1st Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/7406,Buildings,Completed,NC-MADHAVARAM,23,990000,"PROVIDING ROOFING ARRANGEMENTS AT FOOT BALL GROUND FOR OPEN GALARY (WESTERN SIDE) AT ERATTAIMALAI SRINIVASAN STREET IN DN 23, UNIT-6, ZONE III.",Own Sources,3,2016-17,2016-17 NC/2016-17/8620,Roads,Completed,NC-MADHAVARAM,23,880000,"CONSTRUCTION OF COMPOUND WALL AT OSR LAND NEAR GNT ROAD (EAST SIDE) IN DN-23,U-6,Z-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/8622,Roads,Completed,NC-MADHAVARAM,23,590000,"CONSTRUCTION OF COMPOUND WALL AT OSR LAND NEAR GNT ROAD(SOUTH SIDE AND PARTLY EAST SIDE) IN DN-23,U-6,Z-3.",Own Sources,3,2016-17,2018-19 P/2016-17/19672,Parks,Completed,P-Parks and Playfields,23,2856000,"FORMATION OF PARK AT GANGADHARAN STREET,PUZHAL IN DN-23, UNIT-6, ZONE-3",Grants,3,2016-17,2018-19 BR/2016-17/11278,Roads,Completed,BR-Bus Route Roads,24,4200000,"Restoration of road cut at Surapet main road ( from sembium redhills road to 650 m ) in div -24 , zone - 03",Deposit Works,3,2016-17,2016-17 BR/2016-17/8797,Roads,Completed,BR-Bus Route Roads,24,940000,"Supplying and fixing of Front facia & Back drop in the stainless steel Bus shelter at various bus route roads in zone - 1 , 2 & 3.",Own Sources,3,2016-17,2018-19 L/2016-17/13747,Electrical,Completed,L-Electrical,24,191500,Provision for supply and fixing 12 nos of Automatic Timer Unit at various locations in division-24 and 25 of zone-3.,Own Sources,3,2016-17,2018-19 L/2016-17/14903,Electrical,Completed,L-Electrical,24,192800,"Painting of 855 Nos of 6mtr lamp post, single straight bracket,178 Nos of 9mtr Lamp post at Various streets in Div-24 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2018-19 NC/2016-17/10763,Roads,Completed,NC-MADHAVARAM,24,2155000,"Forming BT Road by paver finisher at Community Hall Street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10764,Roads,Completed,NC-MADHAVARAM,24,915000,"Forming BT Road by paver finisher at Jasmin 1st Street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10765,Roads,Completed,NC-MADHAVARAM,24,883000,"Forming BT Road by paver finisher at Jasmin 2nd Street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10766,Roads,Completed,NC-MADHAVARAM,24,915000,"Forming BT Road by paver finisher at Pattalamman Nagar in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10767,Roads,Completed,NC-MADHAVARAM,24,1079000,"Forming BT Road by paver finisher at Ayyappan Nagar 2nd street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10768,Roads,Completed,NC-MADHAVARAM,24,3587000,"Forming BT Road by paver finisher at Thirumal Nagar 1st Main Road in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10769,Roads,Completed,NC-MADHAVARAM,24,3700000,"Forming BT Road by paver finisher at Thirumal nagar 2nd main road and 10 to 15 street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10771,Roads,Completed,NC-MADHAVARAM,24,1698000,"Forming BT Road by paver finisher at Thiruvalluvar street (Puthagaram) in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10772,Roads,Completed,NC-MADHAVARAM,24,706000,"Forming BT Road by paver finisher at Uma Nagar in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10773,Roads,Completed,NC-MADHAVARAM,24,1560000,"Forming BT Road by paver finisher at Uma Nagar Main Street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10774,Roads,Completed,NC-MADHAVARAM,24,1045000,"Forming BT Road by paver finisher at padma nagar main road in Div-24, unit- 6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10777,Roads,Completed,NC-MADHAVARAM,24,491000,"Forming BT Road by paver finisher at jayam nagar 1st street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10782,Roads,Completed,NC-MADHAVARAM,24,1437000,"Forming BT Road by paver finisher at jaya Bharathi 1st street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10783,Roads,Completed,NC-MADHAVARAM,24,849000,"Forming BT Road by paver finisher at jaya Bharathi 2nd street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10787,Roads,Completed,NC-MADHAVARAM,24,719000,"Forming BT Road by paver finisher at jaya Bharathi 3rd street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10788,Roads,Completed,NC-MADHAVARAM,24,176000,"Forming BT Road by paver finisher at Subam Nagar 1st street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10790,Roads,Completed,NC-MADHAVARAM,24,432000,"Forming BT Road by paver finisher at Subam Nagar 2nd street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10791,Roads,Completed,NC-MADHAVARAM,24,327000,"Forming BT Road by paver finisher at Subam Nagar 3rd street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10793,Roads,Completed,NC-MADHAVARAM,24,196000,"Forming BT Road by paver finisher at Subam Nagar 4th street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10794,Roads,Completed,NC-MADHAVARAM,24,360000,"Forming BT Road by paver finisher at Subam Nagar 5th street in Div-24, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/17030,Roads,Completed,NC-MADHAVARAM,24,480000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROADS DUE TO CYCLONE AT SANTHOSH NAGAR MAIN ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17093,Roads,Completed,NC-MADHAVARAM,24,250000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SRI VENKATESWARA NAGAR 1ST STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17094,Roads,Completed,NC-MADHAVARAM,24,394000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SRI VENKATESWARA NAGAR 2ND STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17095,Roads,Completed,NC-MADHAVARAM,24,294000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SARATHY NAGAR EXTN 9T STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17097,Roads,Completed,NC-MADHAVARAM,24,311000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SARATHI NAGAR EXTN 10TH STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17098,Roads,Completed,NC-MADHAVARAM,24,186000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SARATHI NAGAR EXTN 16TH STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17099,Roads,Completed,NC-MADHAVARAM,24,549000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT BALA VINAYAKARKOIL MAIN ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17100,Roads,Completed,NC-MADHAVARAM,24,206000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT AYYAPPAN NAGAR 1ST STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17101,Roads,Completed,NC-MADHAVARAM,24,111000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SRI RAM NAGAR 1ST STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17123,Roads,Completed,NC-MADHAVARAM,24,186000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SRI VENKATESWARA NAGAR 4TH STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17142,Roads,Completed,NC-MADHAVARAM,24,189000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SRI RAM NAGAR 2ND STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17150,Roads,Completed,NC-MADHAVARAM,24,686000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT RAJAMMAL NAGAR MAIN ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17151,Roads,Completed,NC-MADHAVARAM,24,309000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT BHARATH NAGAR 1ST STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17153,Roads,Completed,NC-MADHAVARAM,24,627000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT THIRUMAL NAGAR 21ST STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17154,Roads,Completed,NC-MADHAVARAM,24,859000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT JP NAGAR 1ST MAIN ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17155,Roads,Completed,NC-MADHAVARAM,24,580000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT JP NAGAR 2ND MAIN ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17157,Roads,Completed,NC-MADHAVARAM,24,534000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT JP NAGAR 3RD MAIN ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17180,Roads,Completed,NC-MADHAVARAM,24,617000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT DG NAGAR MAIN ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17181,Roads,Completed,NC-MADHAVARAM,24,1302000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT BHARATHIDASAN NAGAR 1ST STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17182,Roads,Completed,NC-MADHAVARAM,24,1199000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT BHARATHIDASAN NAGAR 2ND MAIN ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17184,Roads,Completed,NC-MADHAVARAM,24,1336000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SIVA PRAKASAM NAGAR PILLAYAR KOIL STREET IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17186,Roads,Completed,NC-MADHAVARAM,24,857000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT METTR LINK UNION ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17188,Roads,Completed,NC-MADHAVARAM,24,651000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT METTR LINK ROAD IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17189,Roads,Completed,NC-MADHAVARAM,24,617000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT SIVAPRAKASAM NAGAR NORTH IN DN 24, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17210,Roads,Completed,NC-MADHAVARAM,24,343000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT MATHEW CROSS STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17211,Roads,Completed,NC-MADHAVARAM,24,240000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT PERIYAR STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17212,Roads,Completed,NC-MADHAVARAM,24,172000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT VINAYAKAR KOIL 1ST STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17213,Roads,Completed,NC-MADHAVARAM,24,343000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT PADASALAI STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17214,Roads,Completed,NC-MADHAVARAM,24,463000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT N.S.K STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17216,Roads,Completed,NC-MADHAVARAM,24,360000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT JOHN VICTOR STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17220,Roads,Completed,NC-MADHAVARAM,24,412000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT RENGA AVENUE 1ST STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17221,Roads,Completed,NC-MADHAVARAM,24,412000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT RENGA AVENUE 2ND STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17222,Roads,Completed,NC-MADHAVARAM,24,514000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT RENGA AVENUE 3RD STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17223,Roads,Completed,NC-MADHAVARAM,24,514000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT RENGA AVENUE 4TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17224,Roads,Completed,NC-MADHAVARAM,24,514000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT RENGA AVENUE 5TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17225,Roads,Completed,NC-MADHAVARAM,24,514000,"ATTENDING TO TEMPORARY RESTORATION OF DAMAGED INTERIOR ROAD DUE TO CYCLONE AT RENGA AVENUE 6TH STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2017-18 NC/2016-17/17382,Buildings,Completed,NC-MADHAVARAM,24,340000,"REPAIRS AND IMPROVEMENTS TO SCHOOL BUILDING (DAMAGE DUE TO VARDHA CYCLON) AT BALAVINAYAKAR KOIL STREET,SURAPAATU SCHOOL,BHARATHIDASAN NAGAR IN DIVISION-24,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17386,Buildings,Completed,NC-MADHAVARAM,24,105000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM (DAMAGE DUE TO VARDHA CYCLON) AT CADAPPA ROAD IN DIVISION-24,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17392,Buildings,Completed,NC-MADHAVARAM,24,125000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM (DAMAGE DUE TO VARDHA CYCLON) AT METTUR ROAD IN DIVISION-24,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17396,Buildings,Completed,NC-MADHAVARAM,24,180000,"REPAIRS AND IMPROVEMENTS TO BURIAL GROUND (DAMAGE DUE TO VARDHA CYCLON) ATCADAPPA ROAD,SURAPATTU,BHARATHIDASAN NAGAR IN DIVISION-24,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17411,Roads,Completed,NC-MADHAVARAM,24,410000,"REPAIRS AND NEW FIXING TO STREET NAME BOARD (DAMAGE DUE TO VARDHA CYCLON) AT VARIOUS STREET IN DIVISION-24,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/2708,Storm Water Drain,Completed,NC-MADHAVARAM,24,831000,"Construction of culvert at D.G Nagar, School street, J.P Nagar, Surapattu Main road, Sivaprakasam Nagar (North) 2nd Street, Pillaiyar koil street, Sivaprakasam Nagar (North) Kalyanamandabam in Div-24, Unit-6, Zone-3",Own Sources,3,2016-17,2018-19 NC/2016-17/2715,Storm Water Drain,Completed,NC-MADHAVARAM,24,649000,"Construction of culvert at Annai Indira Gandhi Nagar, Rajiv Gandhi Nagar, Bajanai Koil street, Bharathidasan Nagar, 4th and 6th street, sivaprakasam Nagar (south) in Div-24, unit-6, zone-3",Own Sources,3,2016-17,2018-19 NC/2016-17/3466,Storm Water Drain,Completed,NC-MADHAVARAM,24,842000,"Desilting of Side drain at Iyyan Thiruvalluvar Salai, Santhish nagar Main road, Puthagaram service road and Surapattu service road in Div-24, unit-6, Zone-3",Own Sources,3,2016-17,2018-19 NC/2016-17/4161,Buildings,Completed,NC-MADHAVARAM,24,998000,"RAISING THE OSR LAND AT KADAPA ROAD NEAR AMMMAUNAVAGAM IN DN-24,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/4242,Buildings,Completed,NC-MADHAVARAM,24,998000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT MURUGAMEDU AND BALA VINAYAGAR KOIL STREET IN DN-24,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/4245,Buildings,Completed,NC-MADHAVARAM,24,999000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT SURAPET MAIN ROAD AND JP NAGAR IN DN-24,U-6,Z-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/5185,Roads,Completed,NC-MADHAVARAM,24,332000,"Restoration of Road Cut at Elizabath Nagar Main road in div-24, Unit-6, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5186,Roads,Completed,NC-MADHAVARAM,24,271000,"ROAD CUT RESTORATION AT VELMURUGAN MAIN ROAD IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5332,Roads,Completed,NC-MADHAVARAM,24,226000,"ROAD CUT RESTORATION AT VELMURUGAN 1ST STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5333,Roads,Completed,NC-MADHAVARAM,24,479000,"Road cut restoration at vijayalakshmi nagar main road,division-24,unit-6,zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5353,Roads,Completed,NC-MADHAVARAM,24,226000,"Road cut restoration at vijayalakshmi nagar 2nd street in division-24,unit-6,zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5361,Roads,Completed,NC-MADHAVARAM,24,63000,"Road cut restoration at vijayalakshmi nagar 3rd street in division-24,unit-6,zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5365,Roads,Completed,NC-MADHAVARAM,24,301000,"ROAD CUT RESTORATION AT VELMURUGAN 2nd STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5368,Roads,Completed,NC-MADHAVARAM,24,249000,"ROAD CUT RESTORATION AT VELMURUGAN 3RD STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5369,Roads,Completed,NC-MADHAVARAM,24,127000,"ROAD CUT RESTORATION AT VELMURUGAN 4TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5371,Roads,Completed,NC-MADHAVARAM,24,86700,"ROAD CUT RESTORATION AT VELMURUGAN 5TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5373,Roads,Completed,NC-MADHAVARAM,24,220000,"ROAD CUT RESTORATION AT RANGANATHAN NAGAR 1ST STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5375,Roads,Completed,NC-MADHAVARAM,24,295000,"Road cut restoration at sathya moorthy nagar main road in division-24,unit-6,zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5377,Roads,Completed,NC-MADHAVARAM,24,95900,"Road cut restoration at thirumal nagar 10 th main road in division-24,unit-6,zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5380,Roads,Completed,NC-MADHAVARAM,24,183000,"Road cut restoration at thirumal nagar 11th main road in division-24,unit-6,zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5382,Roads,Completed,NC-MADHAVARAM,24,142000,"ROAD CUT RESTORATION AT THIRUMAL NAGAR 1st STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5386,Roads,Completed,NC-MADHAVARAM,24,137000,"ROAD CUT RESTORATION AT THIRUMAL NAGAR 2nd STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5387,Roads,Completed,NC-MADHAVARAM,24,74000,"ROAD CUT RESTORATION AT THIRUMAL NAGAR 3rd STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5390,Roads,Completed,NC-MADHAVARAM,24,156000,"ROAD CUT RESTORATION AT THIRUMAL NAGAR 12th STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5392,Roads,Completed,NC-MADHAVARAM,24,97000,"ROAD CUT RESTORATION AT THIRUMAL NAGAR 5th STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5468,Buildings,Completed,NC-MADHAVARAM,24,736000,"Supply and errection of gas holder and burning system of Bio Gas Plant at Kadappa Road in Div-24, Unit-6, Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/5470,Buildings,Completed,NC-MADHAVARAM,24,630000,"Construction of Bio Gas Plant at Kadappa Road in Div-24, Unit-6, Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/5482,Roads,Completed,NC-MADHAVARAM,24,178000,"ROAD CUT RESTORATION AT THIRUMAL NAGAR 23rd STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5489,Roads,Completed,NC-MADHAVARAM,24,235000,"ROAD CUT RESTORATION AT RANGANATHAN 2ND STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5495,Roads,Completed,NC-MADHAVARAM,24,124000,"ROAD CUT RESTORATION AT VENGATASAI NAGAR EXTN 16TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5501,Roads,Completed,NC-MADHAVARAM,24,164000,"ROAD CUT RESTORATION AT VENGATASAI NAGAR EXTN 17TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5515,Roads,Completed,NC-MADHAVARAM,24,61900,"ROAD CUT RESTORATION AT VENGATASAI NAGAR EXTN 18TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5522,Roads,Completed,NC-MADHAVARAM,24,252000,"ROAD CUT RESTORATION AT GRACE NAGAR MAIN ROAD IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5523,Roads,Completed,NC-MADHAVARAM,24,166000,"ROAD CUT RESTORATION AT KAMARAJ NAGAR 2ND STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5526,Storm Water Drain,Completed,NC-MADHAVARAM,24,970000,"REPAIRS AND IMPROVEMENTS TO SILT CATCHPIT AND IMPROVEMENTS TO STORM WATER DRAIN AT IYAN THIRUVALLUVAR SALAI IN DN-24,U-6,Z-3",Own Sources,3,2016-17,2018-19 NC/2016-17/5528,Roads,Completed,NC-MADHAVARAM,24,230000,"ROAD CUT RESTORATION AT KAMARAJ NAGAR 3RD STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5534,Roads,Completed,NC-MADHAVARAM,24,184000,"ROAD CUT RESTORATION AT KAMARAJ NAGAR 4TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5539,Roads,Completed,NC-MADHAVARAM,24,106000,"ROAD CUT RESTORATION AT KAMARAJ NAGAR 5TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5545,Roads,Completed,NC-MADHAVARAM,24,378000,"ROAD CUT RESTORATION AT KAMARAJ NAGAR 8TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5549,Roads,Completed,NC-MADHAVARAM,24,310000,"ROAD CUT RESTORATION AT SINGARAVELAN NAGAR 1ST STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5552,Roads,Completed,NC-MADHAVARAM,24,313000,"ROAD CUT RESTORATION AT SINGARAVELAN NAGAR 2ND STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5554,Roads,Completed,NC-MADHAVARAM,24,129000,"ROAD CUT RESTORATION AT SINGARAVELAN NAGAR 4TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5559,Roads,Completed,NC-MADHAVARAM,24,137000,"ROAD CUT RESTORATION AT SAKTHI NAGAR 2ND STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5564,Roads,Completed,NC-MADHAVARAM,24,274000,"ROAD CUT RESTORATION AT SAKTHI NAGAR 3RD STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5580,Roads,Completed,NC-MADHAVARAM,24,249000,"ROAD CUT RESTORATION AT SAKTHI NAGAR 5TH STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5582,Roads,Completed,NC-MADHAVARAM,24,110000,"ROAD CUT RESTORATION AT GANDHI NAGAR 1ST STREET IN DIVISION-24,UNIT-6,ZONE-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5597,Roads,Completed,NC-MADHAVARAM,24,78800,"ROAD CUT RESTORATION AT MAHADEVI NAGAR 1ST STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5602,Roads,Completed,NC-MADHAVARAM,24,80000,"ROAD CUT RESTORATION AT MAHADEVI NAGAR 2ND STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5604,Roads,Completed,NC-MADHAVARAM,24,313000,"ROAD CUT RESTORATION AT JEYALAKSHMI NAGAR IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5606,Roads,Completed,NC-MADHAVARAM,24,415000,"ROAD CUT RESTORATION AT SUBBAN NAGAR 1-5 STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5610,Roads,Completed,NC-MADHAVARAM,24,143000,"ROAD CUT RESTORATION AT RANGANATHAN NAGAR IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5612,Roads,Completed,NC-MADHAVARAM,24,146000,"ROAD CUT RESTORATION AT THIRMAL NAGAR 13TH STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5613,Roads,Completed,NC-MADHAVARAM,24,378000,"ROAD CUT RESTORATION AT LAKSHMI NAGAR IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5615,Roads,Completed,NC-MADHAVARAM,24,489000,"ROAD CUT RESTORATION AT KAMALA NAGAR IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5617,Roads,Completed,NC-MADHAVARAM,24,553000,"ROAD CUT RESTORATION AT SUBASH NAGAR EXTN IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5915,Roads,Completed,NC-MADHAVARAM,24,166000,"ROAD CUT RESTORATION AT THIRMAL NAGAR 19TH STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5916,Roads,Completed,NC-MADHAVARAM,24,147000,"ROAD CUT RESTORATION AT THIRMAL NAGAR 21TH STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5917,Roads,Completed,NC-MADHAVARAM,24,189000,"ROAD CUT RESTORATION AT THIRMAL NAGAR 24TH STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5921,Roads,Completed,NC-MADHAVARAM,24,114000,"ROAD CUT RESTORATION AT VENGATA SAI NAGAR EXTN IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5923,Roads,Completed,NC-MADHAVARAM,24,645000,"ROAD CUT RESTORATION AT RAGAVAN STREET IN DIVISION-24,UNIT-6,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/8627,Storm Water Drain,Completed,NC-MADHAVARAM,24,970000,"REPAIRC AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SURAPATTU MAIN ROAD JUNCTION OF VERARAGAVAN NAGAR ,BRITANIYA NAGAR,IYYAN THIRUVALLUVAR SALAI JUNCTION OF VENKADA SAI NAGAR EXTENSION 2nd STREET IN DN-24,U-6,Z-3.",Own Sources,3,2016-17,2018-19 P/2016-17/19673,Parks,Completed,P-Parks and Playfields,24,3582000,"FORMATION OF NEW PARK AT PUTHAGARAM,SURAPET,PUZHAL (SRI LAKSHMI AMMAN NAGAR) IN DN-24,U-6,Z-03",Grants,3,2016-17,2018-19 L/2016-17/13823,Electrical,Completed,L-Electrical,25,181200,"Removal & Refixing of 41nos of Kiosk Pillar Box at Various location in Div- 25,26,27,30 and 31, Zone-III, Madhavaram .",Own Sources,3,2016-17,2019-20 L/2016-17/14905,Electrical,Completed,L-Electrical,25,158400,"Painting of 749 Nos of 6mtr lamp post, single straight bracket,82 Nos of 9mtr Lamp post & 44 nos of KIOSK Pillar box at Various streets in Div-25 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2017-18 NC/2016-17/10595,Roads,Completed,NC-MADHAVARAM,25,871000,"Forming BT Road by paver finisher at Mathew Street in Div-25, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10598,Roads,Completed,NC-MADHAVARAM,25,1524000,"Forming BT Road by paver finisher at V.O.C Street in Div-25, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10599,Roads,Completed,NC-MADHAVARAM,25,1470000,"Forming BT Road by paver finisher at Srinivasan main 1st Street in Div-25, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10603,Roads,Completed,NC-MADHAVARAM,25,849000,"Forming BT Road by paver finisher at Little Avenue street in Div-25, unit-6,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/11745,Buildings,Completed,NC-MADHAVARAM,25,980000,"Construction of New Amma Unavagam at M.G.R Street in div-25, Unit-6, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/11907,Buildings,Completed,NC-MADHAVARAM,25,980000,"ADDITIONAL IMPROVEMENTS TO AMMA UANAVAGAM AT M.G.R NAGAR IN DIV-25,UNIT-6,ZONE-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/12965,Roads,Completed,NC-MADHAVARAM,25,300000,"PROVIDING STREET NAME BOARDS AT VARIOUS LOCATIONS AND HIRING JCB IN DIV-25,UNIT-6,ZONE-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/17275,Buildings,Completed,NC-MADHAVARAM,25,250000,"REPAIRS AND IMPROVEMENTS TO SCHOOL BUILDING (DAMAGE DUE TO VARDHA CYCLON) AT REDHILS -SEMBIUM MAIN ROAD IN DIVISION-25,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17282,Buildings,Completed,NC-MADHAVARAM,25,200000,"REPAIRS AND IMPROVEMENTS TO NNMP SHED (DAMAGE DUE TO VARDHA CYCLON) AT ESM STREET AND ANNA STREET IN DIVISION-25,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17289,Buildings,Completed,NC-MADHAVARAM,25,550000,"REPAIRS AND IMPROVEMENTS TO BURIAL GROUND (DAMAGE DUE TO VARDHA CYCLON) AT BHARATHIYAR STREET IN DIVISION-25,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17293,Buildings,Completed,NC-MADHAVARAM,25,400000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM (DAMAGE DUE TO VARDHA CYCLON) AT EMS STREET,M.G.R NAGAR AND PADMAVATHI NAGAR IN DIVISION-25,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17305,Footpath,Completed,NC-MADHAVARAM,25,910000,"REPAIRS AND IMPROVEMENTS TO FOOT PATH (DAMAGE DUE TO VARDHA CYCLON) AT COLLECTOR NAGAR,VERARAGAVELU NAGAR,BADHAMAVATHI NAGAR,EMS STREET IN DIVISION-25,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17318,Parks,Completed,NC-MADHAVARAM,25,600000,"REPAIRS AND IMPROVEMENTS TO COLLECTOR NAGAR, PADMAVATHI NAGAR AND SRINIVASA NAGAR PARK IN DN-25,U-6,Z-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17372,Roads,Completed,NC-MADHAVARAM,25,190000,"REPAIRS AND NEW FIXING TO STREET NAME BOARD (DAMAGE DUE TO VARDHA CYCLON) AT VARIOUS STREET IN DIVISION-25,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/2910,Buildings,Completed,NC-MADHAVARAM,25,421000,"Desilting of SWD at collector nagar main street,padmavathy nagarand veeraraghavelu nagar and Rasi nagarmain street and BABUJI NAGAR and David jayavelu street in division 25 ,unit-6 and zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/3448,Buildings,Completed,NC-MADHAVARAM,25,369000,"CONSTRUCTION OF RCC BOX CULVERT AT RASI NAGAR 4TH STREET (BIRLA AVENUE) IN DN: 25,UNIT-6,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/3815,Buildings,Completed,NC-MADHAVARAM,25,260000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT EMS STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2016-17 NC/2016-17/3816,Buildings,Completed,NC-MADHAVARAM,25,315000,"REPAIR AND IMPROVEMENTS TO NNMP SHED AT EMS STREET IN DN 25, UNIT 6, ZONE III.",Own Sources,3,2016-17,2016-17 NC/2016-17/5134,Road Cut,Completed,NC-MADHAVARAM,25,770000,"Road Cut Restoration made by CMWSSB at Thiruvalluvar Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5135,Road Cut,Completed,NC-MADHAVARAM,25,768000,"Road Cut Restoration made by CMWSSB at VOC Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5136,Road Cut,Completed,NC-MADHAVARAM,25,400000,"Road Cut Restoration made by CMWSSB at CMS Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5137,Road Cut,Completed,NC-MADHAVARAM,25,330000,"Road Cut Restoration made by CMWSSB at Mathew Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5138,Road Cut,Completed,NC-MADHAVARAM,25,525000,"Road Cut Restoration made by CMWSSB at Chelli amman koil Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5139,Road Cut,Completed,NC-MADHAVARAM,25,105000,"Road Cut Restoration made by CMWSSB at Thiruvalluvar 1st Cross Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5140,Road Cut,Completed,NC-MADHAVARAM,25,530000,"Road Cut Restoration made by CMWSSB at Vinayagar koil Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5141,Road Cut,Completed,NC-MADHAVARAM,25,207000,"Road Cut Restoration made by CMWSSB at SSV Mils Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5142,Road Cut,Completed,NC-MADHAVARAM,25,990000,"Road Cut Restoration made by CMWSSB at Mahalaxmi Nagar in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5143,Road Cut,Completed,NC-MADHAVARAM,25,344000,"Road Cut Restoration made by CMWSSB at Sathyamoorthy Nagar Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5144,Road Cut,Completed,NC-MADHAVARAM,25,220000,"Road Cut Restoration made by CMWSSB at Birla avenue 2nd Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5145,Road Cut,Completed,NC-MADHAVARAM,25,182000,"Road Cut Restoration made by CMWSSB at Essaiah Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5146,Road Cut,Completed,NC-MADHAVARAM,25,940000,"Road Cut Restoration made by CMWSSB at Collector Nagar Main Road in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5147,Road Cut,Completed,NC-MADHAVARAM,25,600000,"Road Cut Restoration made by CMWSSB at Rasi Nagar 1st to 4th Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5148,Road Cut,Completed,NC-MADHAVARAM,25,160000,"Road Cut Restoration made by CMWSSB at Elumali Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5149,Road Cut,Completed,NC-MADHAVARAM,25,175000,"Road Cut Restoration made by CMWSSB at Padmavathy Nagar 8th Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5150,Road Cut,Completed,NC-MADHAVARAM,25,210000,"Road Cut Restoration made by CMWSSB at Padmavathy Nagar 10th Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5151,Road Cut,Completed,NC-MADHAVARAM,25,78000,"Road Cut Restoration made by CMWSSB at Padmavathy Nagar 11th Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5152,Road Cut,Completed,NC-MADHAVARAM,25,210000,"Road Cut Restoration made by CMWSSB at Lakshmi Kanthammal Street in DN -25, Unit -6, Zone -03.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5389,Storm Water Drain,Completed,NC-MADHAVARAM,25,998000,CONSTRUCTION OF NEW STORM WATER DRAIN AT VEERA RAGA VALU NAGAR 2ND MAIN ROAD AT DIV-25 UNIT-6 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/5395,Storm Water Drain,Completed,NC-MADHAVARAM,25,999000,CONSTRUCTION OF NEW STORM WATER DRAIN AT PADAMAVATHY NAGAR MAIN ROAD JUNCTION OF VEERA RAGA VALU NAGAR 2ND MAIN ROAD AT DIV-25 UNIT-6 ZONE-3,Own Sources,3,2016-17,2017-18 NC/2016-17/5398,Storm Water Drain,Completed,NC-MADHAVARAM,25,997000,CONSTRUCTION OF NEW STORM WATER DRAIN AT VEERA RAGA VALU NAGAR AT DIV-25 UNIT-6 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/5821,Buildings,Completed,NC-MADHAVARAM,25,998000,"Construction of Amma Unavagam Phase -II at Padmavathy Nagar in Div-25, Unit-6, Zone-3",Own Sources,3,2016-17,2017-18 P/2016-17/19674,Parks,Completed,P-Parks and Playfields,25,4456000,"FORMATION OF NEW PARK AT BIRLA AVENUE NEAR PADMAVATHY NAGAR SERVICE ROAD,KATHIRVEDU,PUZHAL IN DN-25,ZONE III",Grants,3,2016-17,2018-19 P/2016-17/19675,Parks,Completed,P-Parks and Playfields,25,9248000,"FORMATION OF NEW PARK AT PADMAVATHI NAGAR 7TH STREET,KATHIRVEDU,PUZHAL IN DIVISION 25 UNIT 6 ZONE 3",Grants,3,2016-17,2018-19 BR/2016-17/9764,Storm Water Drain,Completed,BR-Bus Route Roads,26,9760000,"Strengthening and relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Villivakkam Road in div 26, Zone -03.",Grants,3,2016-17,2017-18 L/2016-17/13740,Electrical,Completed,L-Electrical,26,161100,"Supply & Fixing 10 nos of 63amp / 3Phase analogue automatic street lighting ON/OFF controlling timer units at Various locations in Div- 26 , Zone-III, Madhavaram.",Own Sources,3,2016-17,2018-19 L/2016-17/14901,Electrical,Completed,L-Electrical,26,172800,"Painting of 732 Nos of 6mtr lamp post, single straight bracket, 87 nos of 8mtr lamp post with Single St. Bracket, 50 nos of 8mtr lamp post with drouble St. Bracket, 4 nos of 8mtr lamp post with Triple St. Bracket & 29 nos of KIOSK Pillar box at Various streets in Div- 26 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2017-18 NC/2016-17/0903,Storm Water Drain,Completed,NC-MADHAVARAM,26,111000,PROVIDING GULLY CONNECTION AND CONNECTING SIDE DRAIN APPROACHES TO SWD AT PRH ROAD IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/0904,Buildings,Completed,NC-MADHAVARAM,26,104000,PROVIDING AND FIXING STOP GATE FOR COLLECTION OF PARKING FEES AT TRUCK TERMINAL IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/0905,Buildings,Completed,NC-MADHAVARAM,26,43000,REPAIRS TO PUBLIC CONVEYANCE AT TRUCK TERMINAL OPPOSITE TO ADMINISTRATIVE BUILDING IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/0907,Parks,Completed,NC-MADHAVARAM,26,283000,PROVIDING HOUSE FLY CONTROL SPRAYER ARRANGEMENTS AND FIXING PLANTATION ARRANGEMENT AROUND OMAKULAM DUMPING GROUND AT MRH ROAD IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/1027,Buildings,Completed,NC-MADHAVARAM,26,230000,PROVIDING WATER SUPPLY ARRANGEMENTS TO ZEN TOILET AND IMPROVEMENTS AND MAINTENANCE TO PUBLIC CONVEYANCE AT VINAYAPURAM IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/10588,Roads,Completed,NC-MADHAVARAM,26,2177000,"Forming BT Road by paver finisher at Adhi Nath Nagar 2nd street in Div-26, unit-7,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/10591,Roads,Completed,NC-MADHAVARAM,26,1079000,"Forming BT Road by paver finisher at Lotus colony 3rd street part in Div-26, unit-7,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/11254,Buildings,Completed,NC-MADHAVARAM,26,996000,ADDITIONAL IMPROVEMENTS AND PROVIDING KITCHEN ARRANGEMENTS TO AMMA UNAVAGAM AT TRUCK TERMINAL IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2017-18 NC/2016-17/12892,Buildings,Completed,NC-MADHAVARAM,26,336000,REPAIR TO TOILET DRAINAGE LINE ZONAL OFFICER ROOM AT ZONAL OFFICE AT THANTTAN KULAM ROAD IN DIV-26 UNIT-7 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/17027,Roads,Completed,NC-MADHAVARAM,26,845000,"Attending patchwork (Damage due to Vardha Cyclone) at CMDA Truck Terminal Main Road in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17032,Roads,Completed,NC-MADHAVARAM,26,535000,"Attending patchwork (Damage due to Vardha Cyclone) at CMDA Truck Terminal Main B Road in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17035,Roads,Completed,NC-MADHAVARAM,26,247000,"Attending patchwork (Damage due to Vardha Cyclone) at CMDA Truck Terminal Main C Road in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17037,Roads,Completed,NC-MADHAVARAM,26,126000,"Attending patchwork (Damage due to Vardha Cyclone) at CMDA Truck Terminal Main F Road in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17047,Buildings,Completed,NC-MADHAVARAM,26,141000,"Construction of Compound wall with Greenary (Damaged due to Vardha Cyclone) to the Park at Secretariate Colony in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17049,Buildings,Completed,NC-MADHAVARAM,26,42000,"Construction of Compound wall (Damaged due to Vardha Cyclone) to the Division 26 Office at Thanikachalam Nagar F Block 11th Street in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17056,Buildings,Completed,NC-MADHAVARAM,26,289000,"Construction of Compound wall (Damaged due to Vardha Cyclone) to Shelter For Homeless at CMDA Truck Terminal in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17063,Roads,Completed,NC-MADHAVARAM,26,415000,"Repairing to the Street Name Board (Damage due to Varadha Cyclone) at Various Street in Dn-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17125,Buildings,Completed,NC-MADHAVARAM,26,48000,"Repairing to the Amma Unavagam (Damage due to Vardha cyclone) at CMDA Truck Terminal in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17127,Buildings,Completed,NC-MADHAVARAM,26,25000,"Repairing to the Amma Unavagam (Damage due to Vardha cyclone) at Vinayagapuram in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17133,Buildings,Completed,NC-MADHAVARAM,26,30000,"Repairing to the Amma Unavagam (Damage due to Vardha cyclone) at Thanikachalam Nagar F Block in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17410,Roads,Completed,NC-MADHAVARAM,26,610000,"Relaying of B.T. Course by Paver Finisher (Damage due to Vardha Cyclone) at Thirumalai Nagar East Main Road in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17413,Roads,Completed,NC-MADHAVARAM,26,170000,"Relaying of B.T. Course by Paver Finisher (Damage due to Vardha Cyclone) at Thirumalai Nagar Ranganathan Avenue in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17419,Roads,Completed,NC-MADHAVARAM,26,343000,"Relaying of B.T. Course by Paver Finisher (Damage due to Vardha Cyclone) at Thirumalai Nagar Extn 1st Main Road in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17420,Roads,Completed,NC-MADHAVARAM,26,377000,"Relaying of B.T. Course by Paver Finisher (Damage due to Vardha Cyclone) at Seethapathy Street in Div-26, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/2321,Storm Water Drain,Completed,NC-MADHAVARAM,26,300000,"Desilting and Improvement to the side drain at Surapatu street, Kamarajar st, Nehru st, Perumal Kovil st, Anna st, Sathiya murthy st, Thilagar st, Gandhi st, Villivakkam road, PRH road, Sastri nagar 1st Main road, Thirumalai Nagar Extn 1st main road to Thanikachalam Nagar F block 2nd main road, Thirumalai nagar 1st 2nd and 3rd main road, East and West Main road, Vajaravel nagar, Main road, 1st street to 4th street, Devagi Nagar 1st cross st, 2nd and 3rd street, Natraj nagar main road, Seethapathy st, in Div-26, Unit-7, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/5101,Roads,Completed,NC-MADHAVARAM,26,292000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 3rd Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5102,Roads,Completed,NC-MADHAVARAM,26,502000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 4th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5103,Roads,Completed,NC-MADHAVARAM,26,182000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 5th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5104,Roads,Completed,NC-MADHAVARAM,26,223000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 6th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5105,Roads,Completed,NC-MADHAVARAM,26,97000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 7th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5106,Roads,Completed,NC-MADHAVARAM,26,729000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 8th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5107,Roads,Completed,NC-MADHAVARAM,26,111000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 9th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5108,Roads,Completed,NC-MADHAVARAM,26,292000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 10th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5109,Roads,Completed,NC-MADHAVARAM,26,97000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 11th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5110,Roads,Completed,NC-MADHAVARAM,26,292000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 12th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5111,Roads,Completed,NC-MADHAVARAM,26,223000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 13th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5112,Roads,Completed,NC-MADHAVARAM,26,292000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 14th Street in Dn-26 , U-7 ,z-3.",Deposit Works,3,2016-17,2016-17 NC/2016-17/5113,Roads,Completed,NC-MADHAVARAM,26,222000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 15th Street in Dn-26 , U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5115,Roads,Completed,NC-MADHAVARAM,26,111000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 16th Street in Dn-26 , U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5116,Roads,Completed,NC-MADHAVARAM,26,125000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 17th Street in Dn-26 , U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5117,Roads,Completed,NC-MADHAVARAM,26,125000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 18th Street in Dn-26 , U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5118,Roads,Completed,NC-MADHAVARAM,26,125000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 19th Street in Dn-26 , U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5119,Roads,Completed,NC-MADHAVARAM,26,111000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 20th Street in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5120,Roads,Completed,NC-MADHAVARAM,26,223000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 21th Street in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5121,Roads,Completed,NC-MADHAVARAM,26,145000,"Restoration of Road cut made by CMWSSB at Secretariat Colony 2nd Cross Street in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5122,Roads,Completed,NC-MADHAVARAM,26,292000,"Restoration of Road cut made by CMWSSB at Pachai Ammal Nagar in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5123,Roads,Completed,NC-MADHAVARAM,26,309000,"Restoration of Road cut made by CMWSSB at Karthick Nagar in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5124,Roads,Completed,NC-MADHAVARAM,26,275000,"Restoration of Road cut made by CMWSSB at Kanniappan Street in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5125,Roads,Completed,NC-MADHAVARAM,26,321000,"Restoration of Road cut made by CMWSSB at Govindaappan Street in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5127,Roads,Completed,NC-MADHAVARAM,26,127000,"Restoration of Road cut made by CMWSSB at Villivakkam Road (IR) in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5128,Roads,Completed,NC-MADHAVARAM,26,857000,"Restoration of Road cut made by CMWSSB at Suriya Nagar in Dn-26 ,U-7 ,z-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5378,Roads,Completed,NC-MADHAVARAM,26,999000,FORMING AND LAYING WBM ROAD AT DEVAKI NAGAR(RING ROAD) IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/5379,Roads,Completed,NC-MADHAVARAM,26,997000,FORMING AND LAYING WBM ROAD AT NAGALAKSHIMI NAGAR IN DIVISION 26 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/5824,Buildings,Completed,NC-MADHAVARAM,26,998000,"Construction of Amma Unavagam Phase -II at Truck Terminal in Div-26, Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/5889,Parks,Completed,NC-MADHAVARAM,26,999000,"IMPROVEMENTS TO PARK AT SECRETARIATE COLONY PARK IN DN 26, UNIT-7, ZONE III.",Own Sources,3,2016-17,2017-18 BR/2016-17/18286,Roads,Completed,BR-Bus Route Roads,27,19000000,"Repair and Restoration of Relaying the road with DBM & CBC after cold milling by paver Finisher along with traffic improvements work at Kumarappa puram main road ( part ) from Madhavaram milk colony main road to Assisi Nagar Main Road in Dn -27, Zone -3",Own Sources,3,2016-17,2017-18 BR/2016-17/18288,Roads,Completed,BR-Bus Route Roads,27,5400000,"Repair and Restoration of Relaying the road with DBM & CBC after cold millimg by paver Finisher along with traffic improvements work at Kumarappa puram main road from Assisi Nagar Main Road to to Manjambakkam main road in Dn -27, Zone -3",Own Sources,3,2016-17,2017-18 L/2016-17/13742,Electrical,Completed,L-Electrical,27,177200,"Supply & Fixing 11 nos of 63amp / 3Phase analogue automatic street lighting ON/OFF controlling timer units at Various locations in Div- 27 and Div- 30 , Zone-III, Madhavaram.",Own Sources,3,2016-17,2018-19 L/2016-17/14902,Electrical,Completed,L-Electrical,27,140200,"Painting of 774 Nos of 6mtr lamp post, single straight bracket,4 nos of 8mtr lamp post with Triple St. Bracket & 36 nos of KIOSK Pillar box at Various streets in Div- 27 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2017-18 NC/2016-17/10583,Roads,Completed,NC-MADHAVARAM,27,829000,"Forming BT Road by paver finisher at Duraisamy Street in Div-27, unit- 7,zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/14220,Buildings,Completed,NC-MADHAVARAM,27,409000,"Improvement to Chennai Middle school at Madhavaram Milk colony in division-27,Unit-7,Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/14222,Buildings,Completed,NC-MADHAVARAM,27,84000,"Improvemenrts to water supply arrangements to the park/play ground at venkateswara nagar 2nd street in Division-27,unit-7,Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/14223,Buildings,Completed,NC-MADHAVARAM,27,105000,"Improvements to existing Strom water drain at perumal koil main road Jn. of Perumal koil 1st, street in Division-27.Unit-7,Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/14224,Roads,Completed,NC-MADHAVARAM,27,341000,"Restoration of road portion (existing Heritage mandapam)Near Door No.410/2, at manjambakkam link road,Assessi nagar in division-27,Unit-7,Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/14225,Roads,Completed,NC-MADHAVARAM,27,209000,"Improvements to the existing Kumarappa puram main road existing Strom water drain portion from Jn. of Kamban nagar main road to 240 M in Division-27,Unit-7,Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/17380,Electrical,Completed,NC-MADHAVARAM,27,81000,"Repairs and improvements to NNMP Shed (Damage due to Vardha Cyclone) at Srinivasa Perumal Koil Street in Div-27, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17393,Buildings,Completed,NC-MADHAVARAM,27,428000,"Repairs and Damage in amma Unavagam (Damage due to Vardha Cyclone) at Perumal Koil Street in Div-27, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17398,Roads,Completed,NC-MADHAVARAM,27,367000,"Supplying and fixing of metro rreflective sign board in Div-27, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17402,Roads,Completed,NC-MADHAVARAM,27,924000,"Repairs and Improvements to Storm Water Drain (Damage due to Vardha Cyclone) at Edaima Nagar, Eswaran Koil Street, Mandaveli Main Road, Bhavani Amman Koil Street in Div-27, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17432,Buildings,Completed,NC-MADHAVARAM,27,660000,"Repairs to Gasifier Cerematorium at Mandaveli Burial Ground in Div-27, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17486,Buildings,Completed,NC-MADHAVARAM,27,71000,"Repairs and Improvements to Play ground (Damage due to Vardha Cyclone) at Assis Nagar in Div-27, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/2640,Storm Water Drain,Completed,NC-MADHAVARAM,27,250000,"Desiliting Of Side Drain at Perumal Koil Street,Mandaveli Main Road,Mandaveli 4th St,Alex nagar A Colony 2nd St,Alex Nagar A Colony Main Road (Bharathidasan St), Kamban Nagar Main Road,Mandhaveli 1st St,Perumal Koil 1st St, Bavani Amman Koil St,Easwaran Koil St Perumal Koil,South Telephone Colony,Devi Nagar Kumarappapuram Main Road, Kumarappapuram Main Road,Nehru St,Perumal Koil St (Edima Nagar),Duraiswami Street in Div-27 , Unit-7, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/3933,Roads,Completed,NC-MADHAVARAM,27,155000,"Restoration of Road cut made by CMWSS Board at Alex Nagar A - Colony in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/3939,Roads,Completed,NC-MADHAVARAM,27,424000,"Restoration of Road cut made by CMWSS Board at Alex Nagar A - Colony 3rd Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/3956,Roads,Completed,NC-MADHAVARAM,27,243000,"Restoration of Road cut made by CMWSS Board at Alex Nagar A - Colony 1st Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/3957,Roads,Completed,NC-MADHAVARAM,27,360000,"Restoration of Road cut made by CMWSS Board at Alex Nagar A - Colony 2nd Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/3963,Roads,Completed,NC-MADHAVARAM,27,278000,"Restoration of Road cut made by CMWSS Board at Barathidasan Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/3986,Roads,Completed,NC-MADHAVARAM,27,233000,"Restoration of Road cut made by CMWSS Board at Basiyam Nagar Street in div-27,Unit-7,Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/3988,Roads,Completed,NC-MADHAVARAM,27,167000,"Restoration of Road cut made by CMWSS Board at Alex Nagar C- Colony in div-27,Unit-7,Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5022,Roads,Completed,NC-MADHAVARAM,27,216000,"Restoration of Road Cut Made by CMWSS Board at North Telephone 2nd Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5036,Roads,Completed,NC-MADHAVARAM,27,444000,"Restoration of Road Cut Made by CMWSS Board at Duraiswamy Nayakar Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5038,Roads,Completed,NC-MADHAVARAM,27,266000,"Restoration of Road Cut Made by CMWSS Board at Easwari nagar Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5043,Roads,Completed,NC-MADHAVARAM,27,107000,"Restoration of Road Cut Made by CMWSS Board at Lakshmi Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5049,Roads,Completed,NC-MADHAVARAM,27,288000,"Restoration of Road Cut Made by CMWSS Board at Thiruvalluvar Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5172,Roads,Completed,NC-MADHAVARAM,27,132000,"Restoration of Road Cut Made by CMWSS Board at Venugopal Street in div-27, Unit-7, Zone-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5879,Roads,Completed,NC-MADHAVARAM,27,999000,"PROVISION OF FIXING STREET NAME BOARD AT KRISHNA NAGAR EXTN, TELEPHONE COLONY SOUTH STREET, KAMBAN NAGAR ALEX NAGAR 'A' COLONY AND VERIOUS STREET IN DN 27, UNIT 7, ZONE III.",Own Sources,3,2016-17,2016-17 NC/2016-17/5885,Storm Water Drain,Completed,NC-MADHAVARAM,27,999000,CONSTRUCTION SIDE DRAIN AT KUMARAPPAPURAM MAIN ROAD JUNCTION AT DEVI NAGAR IN DN-27 UNIT-07 ZONE-03,Own Sources,3,2016-17,2016-17 NC/2016-17/6409,Storm Water Drain,Completed,NC-MADHAVARAM,27,990000,CONSTRUCTION SIDE DRAIN AT KUMARAPPAPURAM MAIN ROAD JUNCATION ATKAMBAN NAGAR IN DN-27 UNIT-07 ZONE-03,Own Sources,3,2016-17,2016-17 NC/2016-17/6445,Buildings,Completed,NC-MADHAVARAM,27,998000,"Construction of Compound wall for Heritage Mandabam at Kumarappapuram Main road (Milk Colony) in div-27, Unit-7, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/7206,Buildings,Completed,NC-MADHAVARAM,27,988000,"Removal of Existing Heritage Mandabam for Re-Use at Kumarappapuram Main road (Milk Colony) in div-27, Unit-6, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/7224,Buildings,Completed,NC-MADHAVARAM,27,987000,"Re-Construction of Heritage Mandabam to the nearest location of Kumarappapuram Main road (Milk colony) in div-27, Unit-7, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/7456,Electrical,Completed,NC-MADHAVARAM,27,641700,"Erection of 48 nos of 6m lamp post with arch bracket and provision , erection of 2nos 6m lamp post with arch bracket at assisi nagar main road(Kumarapapuram Main Road) in div-27, zone III, Madhavaram",Own Sources,3,2016-17,2017-18 NC/2016-17/7457,Electrical,Completed,NC-MADHAVARAM,27,882100,"Laying of 4x16sq.mm cable and removal of 48 nos of 6m lamp post at assisi nagar main road (Kumarapapuram main road) in div-27, zone III, madhavaram",Own Sources,3,2016-17,2017-18 NC/2016-17/8112,Buildings,Completed,NC-MADHAVARAM,27,359000,"Providing Curved Chajja Stone, Ceiling stone and Laying Inter lock block in frontage of Heritage Mandapam at Kumarappapuram Main road in div-27, Unit-7, Zone-3.",Own Sources,3,2016-17,2016-17 B/2016-17/18918,Buildings,Completed,B-Buildings,28,4000000,"SUPPLYING, ERECTING AND COMMISIONING THE GASIFIER WITH NECESSARY CIVIL CONSTRUCTION IN SASTHRI NAGAR IN DN-28 ZONE-3",Own Sources,3,2016-17,2019-20 BR/2016-17/9759,Storm Water Drain,Completed,BR-Bus Route Roads,28,6665000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Moolachatram road in div 28, Zone -03.",Grants,3,2016-17,2017-18 BR/2016-17/9760,Storm Water Drain,Completed,BR-Bus Route Roads,28,2144000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at VNG Road in div 28 , Zone -03.",Grants,3,2016-17,2017-18 L/2016-17/13736,Electrical,Completed,L-Electrical,28,161100,"Supply & Fixing of 10 nos of 63amp / 3Phase analogue automatic street lighting ON/OFF controlling timer units at Various locations in Div- 28 , Zone-III, Madhavaram .",Own Sources,3,2016-17,2018-19 L/2016-17/14879,Electrical,Completed,L-Electrical,28,146500,"Painting of 736 Nos of 6mtr lamp post single straight bracket, 49 Nos of 8mtr lamp post & 24 nos of KIOSK Pillar box at Various streets in Div-28 of Zone-III",Own Sources,3,2016-17,2018-19 L/2016-17/17524,Electrical,Completed,L-Electrical,28,2241700,"Removal and refixing of street lamp post at various locations from div-22 to 33, damaged due to vardha cyclone in Zone-III.",Own Sources,3,2016-17,2017-18 NC/2016-17/10516,Roads,Completed,NC-MADHAVARAM,28,436000,"Forming BT Road by paver finisher at Kannappa Naicken street in Div-28, unit-7, zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10521,Roads,Completed,NC-MADHAVARAM,28,392000,"Forming BT Road by paver finisher at Vng 1st cross street in Div-28, unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10524,Roads,Completed,NC-MADHAVARAM,28,219000,"Forming BT Road by paver finisher at VNG 2nd Cross Street in Div-28, unit-7, zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10527,Roads,Completed,NC-MADHAVARAM,28,181000,"Forming BT Road by paver finisher at Kuppu 1st cross street in Div-28, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10530,Roads,Completed,NC-MADHAVARAM,28,153000,"Forming BT Road by paver finisher at Kuppu 2nd cross street in Div-28, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10533,Roads,Completed,NC-MADHAVARAM,28,1132000,"Forming BT Road by paver finisher at Kuppu 3rd Cross street in Div-28, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10536,Roads,Completed,NC-MADHAVARAM,28,131000,"Forming BT Road by paver finisher at Kuppu 4th Cross street in Div-28, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10540,Roads,Completed,NC-MADHAVARAM,28,131000,"Forming BT Road by paver finisher at Kuppu 5th cross street in Div-28, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10543,Roads,Completed,NC-MADHAVARAM,28,491000,"Forming BT Road by paver finisher at Meenakshi Bharathi Co operative Nagar (Aringar anna street) in Div-28, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/13225,Buildings,Completed,NC-MADHAVARAM,28,845000,"Construction of Dinning Hall at K.K Thazhai main road Opp to Padavathamman koil street in div-28, unit-7, zone -3",Own Sources,3,2016-17,2017-18 NC/2016-17/17337,Roads,Completed,NC-MADHAVARAM,28,309000,"Attending to temporary restoration of damaged interior roads due to flood in North East Monsoon-2016 at Bank Colony 3rd Street in Div-28, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17343,Roads,Completed,NC-MADHAVARAM,28,275000,"Attending to temporary restoration of damaged interior roads due to flood in North East Monsoon-2016 at Bank Colony 2nd Street in Div-28, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17352,Roads,Completed,NC-MADHAVARAM,28,206000,"Attending to temporary restoration of damaged interior roads due to flood in North East Monsoon-2016 at Ganapathy Nagar in Div-28, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17356,Roads,Completed,NC-MADHAVARAM,28,172000,"Attending to temporary restoration of damaged interior roads due to flood in North East Monsoon-2016 at Moolachatram MainRoad in Div-28, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17361,Roads,Completed,NC-MADHAVARAM,28,309000,"Attending to temporary restoration of damaged interior roads due to flood in North East Monsoon-2016 at Moolachatram Perumal Koil Road in Div-28, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17371,Roads,Completed,NC-MADHAVARAM,28,335000,"Repairs and new fixing Street Name Board damaged due to 2016 Vardha Cyclone in Div-28, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/19233,Buildings,Completed,NC-MADHAVARAM,28,259000,Repairs and Maintenance of Play Field at Bank Colony 5th street in Div-28 Unit-7 Zone-3,Own Sources,3,2016-17,2016-17 NC/2016-17/3117,Road Cut,Completed,NC-MADHAVARAM,28,998000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT ARUL NAGAR TO GANAPATHY NAGAR APPROACH ROAD [FROM MILK COLONY MAIN ROAD TO ARUL NAGAR NAGAR 3RD STREET] IN WARD-28, UNIT-7, ZONE-3. (LENGTH 700 M)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3118,Road Cut,Completed,NC-MADHAVARAM,28,650000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT ARUL NAGAR TO GANAPATHY NAGAR APPROACH ROAD [FROM MOOLACHATRAM MAIN ROAD TO ARUL NAGAR 3RD STREET] IN WARD-28, UNIT-7, ZONE-3. (LENGTH 353 M)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3443,Roads,Completed,NC-MADHAVARAM,28,738000,"Restoration of Road Cut Made by CMWSS Board at John Vasu Street and Extn Street in Ward-28, Unit-7,Zone-3. (Length 399 m)",Deposit Works,3,2016-17,2017-18 NC/2016-17/3447,Roads,Completed,NC-MADHAVARAM,28,425000,"Restoration of Road Cut made by CMWSS Board at Arul nagar 2nd Street in Ward-28, Unit-7,Zone-3. (Length 208 m)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3450,Roads,Completed,NC-MADHAVARAM,28,326000,"Restoration of Road Cut made by CMWSS Board at Perumal Koil Street in Ward -28, Unit-7,Zone-3.( Length 160m)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3451,Roads,Completed,NC-MADHAVARAM,28,995000,"Restoration of Road Cut made by CMWSS Board at Moolachatram Main Road in Ward-28, Unit-7, Zone-3. (Length 640 m)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3615,Roads,Completed,NC-MADHAVARAM,28,995000,"Restoration of Road Cut made by CMWSS Board at MMC Gate to Booster R-1in Ward -28, Unit-7,Zone-3.( Length 600m)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3617,Roads,Completed,NC-MADHAVARAM,28,999000,"Restoration of Road Cut made by CMWSS Board at MMC Gate to Booster R-2 in Ward -28, Unit-7,Zone-3.( Length 620m)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3622,Roads,Completed,NC-MADHAVARAM,28,998000,"Restoration of Road Cut made by CMWSS Board at MMC Gate to Booster R-3 in Ward -28, Unit-7,Zone-3.( Length 630m)",Deposit Works,3,2016-17,2016-17 NC/2016-17/3626,Roads,Completed,NC-MADHAVARAM,28,999000,"Restoration of Road Cut made by CMWSS Board at MMC Gate to Booster R-4 in Ward -28, Unit-7,Zone-3.( Length 650m)",Deposit Works,3,2016-17,2016-17 NC/2016-17/4315,Storm Water Drain,Completed,NC-MADHAVARAM,28,998000,"Repairs and Improvements to Storm Water Drain at Arul Nagar - Ganapathy Nagar Approach Road (From Milk Colony Main Road to Amma Unavagam) in Ward - 28, Unit-7,Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/5071,Roads,Completed,NC-MADHAVARAM,28,995000,"Repairs and Improvements to Storm Water Drain at Arul Nagar - Ganapathy Nagar Approach Road (From Moolachatram Main Road to Bank Colony 2nd Street) in Ward - 28, Unit-7,Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/5072,Roads,Completed,NC-MADHAVARAM,28,999000,"Repairs and Improvements to Storm Water Drain at Arul Nagar - Ganapathy Nagar Approach Road (From Amma Unavagam to Bank Colony 2nd Street) in Ward - 28, Unit-7,Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/5567,Buildings,Completed,NC-MADHAVARAM,28,740000,Repairs and maintenance of Park at Pathmagiri Nagar in div-28 Unit-7 Zone-3,Own Sources,3,2016-17,2016-17 L/2016-17/13737,Electrical,Completed,L-Electrical,29,145000,"Supply & Fixing 9 nos of 63amp / 3Phase analogue automatic street lighting ON/OFF controlling timer units at Various locations in Div- 29, 32 & 33 , Zone-III, Madhavaram.",Own Sources,3,2016-17,2018-19 L/2016-17/13829,Electrical,Completed,L-Electrical,29,184200,"Removal & Refixing of 36 nos of KIOSK Pillar box at various locations in Div-29, 32 & 33, Zone-III, Madhavaram.",Own Sources,3,2016-17,2019-20 L/2016-17/14881,Electrical,Completed,L-Electrical,29,95600,"Painting of 532 Nos of 6mtr lamp post, 4 Nos of 8mtr lamp post & 21 nos of KIOSK Pillar box at Various streets in Div-29 of Zone-III",Own Sources,3,2016-17,2018-19 NC/2016-17/0280,Buildings,Completed,NC-MADHAVARAM,29,994000,"CONSTRUCTION OF COMPOUND WALL TO COMPOST YARD AT VELU STREET NORTH WEST IN WARD-29, UNIT-7, ZONE-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/0334,Buildings,Completed,NC-MADHAVARAM,29,994000,"CONSTRUCTION OF COMPOUND WALL TO COMPOST YARD AT VELU STREET SOUTH WEST IN WARD-29, UNIT-7, ZONE-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/0917,Buildings,Completed,NC-MADHAVARAM,29,953000,PROVIDING WATER SUPPLY ARRANGEMENTS AND SUPPLYING AND FIXING STEEL TRUSS AND ALUMINIUM SHEET TO COMPOST YARD AT VELU STREET IN DIV- 29 UNIT-7 ZONE-3,Own Sources,3,2016-17,2018-19 NC/2016-17/10552,Roads,Completed,NC-MADHAVARAM,29,1223000,"Forming BT Road by paver finisher at Apparaj 3rd cross street extn in Div-29, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10555,Roads,Completed,NC-MADHAVARAM,29,535000,"Forming BT Road by paver finisher at Apparaj 1st Cross Street in Dn-29, Unit-7, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10565,Roads,Completed,NC-MADHAVARAM,29,153000,"Forming BT Road by paver finisher at Apparaj 3rd cross street in Div-29, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10570,Roads,Completed,NC-MADHAVARAM,29,436000,"Forming BT Road by paver finisher at Parthasarathy 4th cross street in Div-29, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10576,Roads,Completed,NC-MADHAVARAM,29,262000,"Forming BT Road by paver finisher at Parthasarathy 4th cross street 3rd lane in Div-29, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10579,Roads,Completed,NC-MADHAVARAM,29,844000,"Forming BT Road by paver finisher at Aathiraj street in Div-29, unit-7,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/13681,Storm Water Drain,Completed,NC-MADHAVARAM,29,998000,"FLOOD EMERGENCY WORK USING BACKHOE LOADER IN DIVISIONS 26, 27, 28 AND 29 UNIT 7 ZONE 3",Own Sources,3,2016-17,2017-18 NC/2016-17/17251,Buildings,Completed,NC-MADHAVARAM,29,382000,"Consatruction of Compound Wall to Burial Ground at Karunanidhi Street (Damaged due to Vardha Cyclone) in Ward-29, Unit-7,Zone-3 (Length 35m)",Own Sources,3,2016-17,2017-18 NC/2016-17/17252,Buildings,Completed,NC-MADHAVARAM,29,140000,"Consatruction of Compound Wall to Ward Office at Devarajan Street (Damaged due to Vardha Cyclone) in Ward-29, Unit-7,Zone-3 (Length 8.20 m)",Own Sources,3,2016-17,2017-18 NC/2016-17/17253,Buildings,Completed,NC-MADHAVARAM,29,41000,"Providing and fixing of Corrugated Sheet to Class rooms CMS at Devarajan Street Chinnasekkadu (Damaged due to Vardha Cyclone) in Ward -29, Unit-7,Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17255,Roads,Completed,NC-MADHAVARAM,29,448000,"Laying of Bituminous Course by Paver Finisher at Chandramman Koil street (Damaged due to Vardha Cyclone) in Ward 29, Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17258,Roads,Completed,NC-MADHAVARAM,29,257000,"Laying of Bituminous Course by Paver Finisher at Parthasarathy street (Damaged due to Vardha Cyclone) in Ward 29, Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17259,Roads,Completed,NC-MADHAVARAM,29,308000,"Laying of Bituminous Course by Paver Finisher at Raji street (Damaged due to Vardha Cyclone) in Ward 29, Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17262,Roads,Completed,NC-MADHAVARAM,29,412000,"Laying of Bituminous Course by Paver Finisher at Thiruvalluvar Street (Damaged due to Vardha Cyclone) in Ward 29, Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17265,Roads,Completed,NC-MADHAVARAM,29,515000,"Laying of Bituminous Course by Paver Finisher at Vedhagiril street (Damaged due to Vardha Cyclone) in Ward 29, Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17280,Roads,Completed,NC-MADHAVARAM,29,1800000,"Laying of Bituminous Course by Paver Finisher at Apparaj 2nd Cross Street (Damaged due to Vardha Cyclone) in ward 29,Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/17286,Roads,Completed,NC-MADHAVARAM,29,778000,"Laying of Bituminous Course by Paver Finisher at Apparaj 4th Cross Street (Damaged due to Vardha Cyclone) in ward 29 Unit-7,Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/19895,Storm Water Drain,Completed,NC-MADHAVARAM,29,690000,"IMPROVEMENTS TO SWD AT PERUMAL KOIL STREET JUNCTION OF DEVARAJAN STREET IN DN-29,U-7,Z-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/2322,Storm Water Drain,Completed,NC-MADHAVARAM,29,555000,"Desilting of Storm Water Drains and Side drains at Devarajan st, Perumal Kovil st, and Perumal Kovil st Extn and Various street in div-29, Unit-7, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/3627,Roads,Completed,NC-MADHAVARAM,29,120000,"Restoration of Roadcut made by CMWWS Board at Vedagiri Cross street in Ward-29, Unit-7,Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/3637,Roads,Completed,NC-MADHAVARAM,29,150000,"Restoration of road cut made by CMWSS Board at Parthsarathy 4th cross 3rd lane in div-29, Unit-7, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/3640,Roads,Completed,NC-MADHAVARAM,29,405000,"Restoration of Road cut made by CMWSS Board at Perumal Kovil street extn., in div-29, Unit-7, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/3641,Roads,Completed,NC-MADHAVARAM,29,170000,"Restoration of Road cut made by CMWSS Board at Kannan street, in div-29, Unit-7, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/3645,Roads,Completed,NC-MADHAVARAM,29,500000,"Restoration of Road cut made by CMWSS Board at Namakara Munian Street in div-29, Unit-7, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/3646,Roads,Completed,NC-MADHAVARAM,29,140000,"Restoration of Road cut made by CMWSS Board at Parthasarathy 4th cross Street in div-29, Unit-7, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/3648,Roads,Completed,NC-MADHAVARAM,29,516000,"Restoration of Road cut made by CMWSS Board at Krishnan Street in div-29, Unit-7, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/3649,Roads,Completed,NC-MADHAVARAM,29,192000,"Restoration of Road cut made by CMWSS Board at Parthasarathy 4th cross 1st lane in div-29, Unit-7, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/3961,Roads,Completed,NC-MADHAVARAM,29,206000,"Restoration of road cut made by CMWSS Board at Perumal kovil 4th cross street in Div-29,Unit-7,zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/3962,Roads,Completed,NC-MADHAVARAM,29,59000,"Restoration of road cut made by CMWSS Board at Apparaj 3rd cross street in Div-29,Unit-7,zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/3964,Roads,Completed,NC-MADHAVARAM,29,295000,"Restoration of road cut made by CMWSS Board at Apparaj street in Div-29,Unit-7,zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/3969,Roads,Completed,NC-MADHAVARAM,29,491000,"Restoration of road cut made by CMWSS Board at Velu street in Div-29,Unit-7,zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/3970,Roads,Completed,NC-MADHAVARAM,29,206000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT KRISHNAN STREET BALIPALYAM IN DIV-29,UNIT-7,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4122,Roads,Completed,NC-MADHAVARAM,29,185000,"RESTORATION OF ROAD CUT AT PARTHASARATHY 6TH CROSS STREET IN DN-29,UNIT-7,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4123,Roads,Completed,NC-MADHAVARAM,29,237000,"RESTORATION OF ROAD CUT AT APPARAJ 4TH CROSS STREET IN DN-29,UNIT-7,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4124,Roads,Completed,NC-MADHAVARAM,29,240000,"RESTORATION OF ROAD CUT AT APPARAJ 5TH CROSS STREET IN DN-29,UNIT-7,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4125,Roads,Completed,NC-MADHAVARAM,29,323000,"RESTORATION OF ROAD CUT AT APPARAJ 6TH CROSS STREET IN DN-29,UNIT-7,ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4395,Buildings,Completed,NC-MADHAVARAM,29,865000,"CONSTRUCTION OF DINING HALL TO COMMUNITY CENTER AT DEVARAJAN STREET IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/4846,Buildings,Completed,NC-MADHAVARAM,29,287000,"CONSTRUCTION OF KITCHEN SHED TO COMMUNITY CENTER AT DEVARAJAN STREET IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/4847,Storm Water Drain,Completed,NC-MADHAVARAM,29,141000,PROVIDING RAIN WATER DISPOSAL ARRANGEMENTS AT MUNUSAMY 1ST CROSS STREET IN DN-29 UNIT-07 ZONE-03,Own Sources,3,2016-17,2017-18 NC/2016-17/4848,Storm Water Drain,Completed,NC-MADHAVARAM,29,285000,PROVIDING RAIN WATER DISPOSAL ARRANGEMENTS AT MUNUSAMY 6th CROSS STREET IN DN-29 UNIT-07 ZONE-03,Own Sources,3,2016-17,2017-18 NC/2016-17/4849,Roads,Completed,NC-MADHAVARAM,29,218000,LAYING OF WET MIX MACADAM AT VEDACHALAM STREET IN DN-29 UNIT-07 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/4850,Buildings,Completed,NC-MADHAVARAM,29,533000,CONSTRUCTION OF WASHING PLATFORM FOR KITCHEN SHED INSIDE OF CMS AT DEVARAJAN STREET IN DN-29 UNIT-07 ZONE-03,Own Sources,3,2016-17,2016-17 NC/2016-17/5070,Roads,Completed,NC-MADHAVARAM,29,150000,LAYING OF WET MIX MACCADAM AT KANNABIRAN CROSS STREET IN DIVISION 29 UNIT 7 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/5394,Roads,Completed,NC-MADHAVARAM,29,62000,LAYING OF WET MACADIAM ROAD AT PERUMAL KOIL 1ST CROSS STREET IN DN-29 UNIT-7 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/5396,Roads,Completed,NC-MADHAVARAM,29,197000,LAYING OF WET MACADIAM ROAD AT PERUMAL KOIL 3RD CROSS STREET IN DN-29 UNIT-7 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/5399,Roads,Completed,NC-MADHAVARAM,29,180000,"LAYING OF WETMIX MACADAM ROAD AT PERUMAL KOIL CROSS LANE IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/5400,Roads,Completed,NC-MADHAVARAM,29,80000,"LAYING OF WETMIX MACADAM ROAD AT DEVARAJAN 4TH CROSS STREET IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2016-17,2016-17 BR/2016-17/9761,Storm Water Drain,Completed,BR-Bus Route Roads,30,2915000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Thanikachalam Nagar F block 1 st Main Road in div 30, Zone -03.",Grants,3,2016-17,2017-18 BR/2016-17/9762,Storm Water Drain,Completed,BR-Bus Route Roads,30,4700000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Milk colony Road (From Thapal peeti To Medimix) in div 30, Zone -03.",Grants,3,2016-17,2017-18 L/2016-17/14904,Electrical,Completed,L-Electrical,30,165000,"Painting of 730 Nos of 6mtr lamp post, single straight bracket, 110 nos of 8mtr lamp post with Single Arch Bracket, 4 nos of 8mtr lamp post with Triple St. Bracket, 32 nos of 2/3mtr lamp post & 28 nos of KIOSK Pillar box at Various streets in Div- 30 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2017-18 NC/2016-17/12778,Roads,Completed,NC-MADHAVARAM,30,852000,"Construction of Inlet Chamber in between MRH Road (Bosco School, Sivasakthi Park and Madhavaram Bus Terminus) in div- 30 & 31, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/13684,Storm Water Drain,Completed,NC-MADHAVARAM,30,998000,"FLOOD EMERGENCY WORK USING BACKHOE LOADER IN DIVISIONS 30, 31,32 AND 33 UNIT 8 ZONE 3",Own Sources,3,2016-17,2017-18 NC/2016-17/15129,Buildings,Completed,NC-MADHAVARAM,30,981000,"Improvements to Division-30 office, Lorry Station and NNMP Shed at Rajaji Street in Div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/15746,Roads,Completed,NC-MADHAVARAM,30,587000,"Providing and Laying Cement Concrete Ramp for Bus Terminus at MRH road in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/16889,Buildings,Completed,NC-MADHAVARAM,30,97000,"REPAIRS AND IMPROVEMENTS TO PC AT MADHAVARAM BUS TERMINOUS IN DN-30, UNIT-8, ZONE-3",Own Sources,3,2016-17,2016-17 NC/2016-17/17034,Parks,Completed,NC-MADHAVARAM,30,746000,"Reparis and Improvements to Parks (Damaged due to Varadha Cyclone) at VRD Nagar in Division-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17272,Roads,Completed,NC-MADHAVARAM,30,891000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at VRD Nagar 1st Main Road in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17276,Roads,Completed,NC-MADHAVARAM,30,891000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at VRD Nagar 1st cross street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17277,Roads,Completed,NC-MADHAVARAM,30,891000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at VRD Nagar 2nd cross street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17281,Roads,Completed,NC-MADHAVARAM,30,529000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Roja Nagar 2nd main road in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17284,Roads,Completed,NC-MADHAVARAM,30,617000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Roja Nagar Extn in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17285,Roads,Completed,NC-MADHAVARAM,30,548000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Roja Nagar B colony (Alex Nagar) in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17288,Roads,Completed,NC-MADHAVARAM,30,412000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Kanmol Nagar in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17290,Roads,Completed,NC-MADHAVARAM,30,275000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at S.V. koil street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17314,Roads,Completed,NC-MADHAVARAM,30,1234000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Thiruvalluvar street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17421,Parks,Completed,NC-MADHAVARAM,30,154000,"Reparis and Improvements to Parks (Damaged due to Varadha Cyclone) at Roja Nagar Play ground in Division-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17426,Roads,Completed,NC-MADHAVARAM,30,474000,"Reparis & New fixing of street name board (Damaged) due to Varatha Cyclone at various street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/2376,Storm Water Drain,Completed,NC-MADHAVARAM,30,475000,"Desilting of side drains at S.V. Kovil st, Mariamman kovil st, Rajaji st, Pukraj st, Bharathiyar st, Sivasakthi Ngar, VRD Nagar, Bharathiyar st, Extn, MRD Road, Mohan Garden, Padmavathy Nagar, and Kamaraj street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/2377,Storm Water Drain,Completed,NC-MADHAVARAM,30,481000,"Desilting of side drains at V.O.C street, Udaiyar thottam, Pandian st, Dhansingh Maistry st, Kanchi ponnu smay thottam, Rizwan road, Milik colony road, MRH road, KKR Nagar, Muthumariamman kovil st, Thiru-vee-ka st, Thiruvalluvar st, Kannabiran kovil st, Ambedkar st, Kolkatta shop road, Palaniappa Nagar, and KKR Garden in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/3581,Parks,Completed,NC-MADHAVARAM,30,295000,"Improvement to Childrens Play Field at Pukraj nagar 1st main road in Div-30, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/4658,Roads,Completed,NC-MADHAVARAM,30,599000,"Restoration of Road cut at Aringer Anna Street Part-II in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4659,Roads,Completed,NC-MADHAVARAM,30,326000,"Restoration of Road cut at Roja Nagar 1st extn in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4680,Roads,Completed,NC-MADHAVARAM,30,331000,"Restoration of Road cut at Pukraj Nagar 6th main road in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4681,Roads,Completed,NC-MADHAVARAM,30,497000,"Restoration of Road cut at Mariamman Koil Street in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4684,Roads,Completed,NC-MADHAVARAM,30,278000,"Restoration of Road cut at Kanmol Nagar in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4685,Roads,Completed,NC-MADHAVARAM,30,282000,"Restoration of Road cut at Roja Nagar Extn 2nd Street in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4687,Roads,Completed,NC-MADHAVARAM,30,477000,"Restoration of Road cut at V.R.D Nagar 1st Main Road in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4690,Roads,Completed,NC-MADHAVARAM,30,255000,"Restoration of Road cut at Padmavathy Nagar Extn in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4691,Roads,Completed,NC-MADHAVARAM,30,235000,"Restoration of Road cut at Padmavathy Nagar 2nd Main Road in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4720,Roads,Completed,NC-MADHAVARAM,30,598000,"Restoration of Road cut at Aringnar Anna street Part-I in Div-30, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6578,Storm Water Drain,Completed,NC-MADHAVARAM,30,997000,"Raising and Improvements to Side drain at Rajaji street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/6579,Storm Water Drain,Completed,NC-MADHAVARAM,30,998000,"Raising and Improvements to Side drain at S,V, Koil street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/6580,Storm Water Drain,Completed,NC-MADHAVARAM,30,986000,"Raising and Improvements to Side drain at Mariamman Koil street in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/6581,Storm Water Drain,Completed,NC-MADHAVARAM,30,998000,"Raising and Improvements to Side drain at Bharathiyar Street Main Road in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/7805,Roads,Completed,NC-MADHAVARAM,30,989000,"Providing and fixing street name board at V.S. Mani Nagar, Masilamani Nagar and Various stree in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/8153,Roads,Completed,NC-MADHAVARAM,30,998000,RAISING AND FORMING WIDENING THE ROAD AT RING ROAD HOUSING SECTOR 2ND MAIN ROAD IN DN-30 UNIT-8 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/8154,Roads,Completed,NC-MADHAVARAM,30,999000,RAISING AND FORMING WIDENING THE ROAD AT WESTERN SIDE RING ROAD HOUSING SECTOR 2ND MAIN ROAD IN DN-30 UNIT-8 ZONE-3,Own Sources,3,2016-17,2016-17 NC/2016-17/9794,Roads,Completed,NC-MADHAVARAM,30,196000,"Forming BT road by Paver Finisher at Jeeva Garden in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/9818,Roads,Completed,NC-MADHAVARAM,30,1176000,"Forming Bt Road by Paver Finisher at Aringar Anna Street Extn in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/9823,Roads,Completed,NC-MADHAVARAM,30,116000,"Forming BT Road by Paver Finisher at Jeeva Garden 2nd street in Div-30, Unit-8, zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/9828,Roads,Completed,NC-MADHAVARAM,30,3483000,"Forming BT Road by Paver Finisher at V.S Mani nagar 1st street extn in Div-30, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/9833,Roads,Completed,NC-MADHAVARAM,30,3308000,"Forming BT Road by Paver Finisher at V.S Mani nagar 2nd street extn in Div-30, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/9836,Roads,Completed,NC-MADHAVARAM,30,3047000,"Forming BT Road by Paver Finisher at V.S Mani nagar 3rd street extn in Div-30, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/9843,Roads,Completed,NC-MADHAVARAM,30,3134000,"Forming BT Road by Paver Finisher at V.S Mani nagar 4th street extn in Div-30, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/9846,Roads,Completed,NC-MADHAVARAM,30,2612000,"Forming BT Road by Paver Finisher at V.S Mani nagar 5th street extn in Div-30, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 BR/2016-17/17746,Roads,Completed,BR-Bus Route Roads,31,950000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Madhavaram Redhills road, GNT road, Villivakkam redhills road,Kolathur redhills road etc., in Zone-3",Grants,3,2016-17,2017-18 L/2016-17/13743,Electrical,Completed,L-Electrical,31,193300,"Supply & Fixing 12 nos of 63amp / 3Phase analogue automatic street lighting ON/OFF controlling timer units at Various locations in Div- 31 , Zone-III, Madhavaram.",Own Sources,3,2016-17,2018-19 L/2016-17/14906,Electrical,Completed,L-Electrical,31,155000,"Painting of 723 Nos of 6mtr lamp post, single straight bracket, 60 nos of 8mtr lamp post with Single Arch Bracket, 15nos of 8mtr lamp post with single st. bracket, 4 nos of 8mtr lamp post with Triple Arch Bracket, 38 nos of 2/3mtr lamp post & 32 nos of KIOSK Pillar box at Various streets in Div- 31 of Zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2016-17,2017-18 NC/2016-17/0686,Parks,Completed,NC-MADHAVARAM,31,815000,REPAIRS AND IMPROVEMENTS TO PARK AT KKR GARDEN IN DIVISION 31 UNIT 8 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/0687,Buildings,Completed,NC-MADHAVARAM,31,233000,IMPROVEMENTS TO ANGANWADI AND ANGANWADI CAMPUS BUILDING AT KANNABIRAN KOIL STREET IN DIVISION 31 UNIT 8 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/12788,Buildings,Completed,NC-MADHAVARAM,31,62000,"Urgent Reparis to PC at Ambedkar Nagar and Thideer Nagar Areas in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/17279,Roads,Completed,NC-MADHAVARAM,31,522000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Roja Nagar 1st main road in div-30, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17295,Roads,Completed,NC-MADHAVARAM,31,480000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Burma colony main road in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17309,Roads,Completed,NC-MADHAVARAM,31,891000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Kolkatta shop main road in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17315,Roads,Completed,NC-MADHAVARAM,31,720000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Kannabiran koil street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17319,Roads,Completed,NC-MADHAVARAM,31,541000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Udaiyar thottam 1st street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17321,Roads,Completed,NC-MADHAVARAM,31,960000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at KKR Nagar in div-31 Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17417,Parks,Completed,NC-MADHAVARAM,31,816000,"Reparis and Improvements to Parks (Damaged due to Varadha Cyclone) at KKR Nagar & KKR Garden in Division-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17428,Roads,Completed,NC-MADHAVARAM,31,474000,"Reparis & New fixing of street name board (Damaged) due to Varatha Cyclone at various street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17441,Roads,Completed,NC-MADHAVARAM,31,275000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Kannapuram 1st street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/3485,Buildings,Completed,NC-MADHAVARAM,31,729000,"Repairs and Improvements to existing PC at Muthumariamman kovil st, KKR Estate and Kannabiran kovil st (Jangiri shop) in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/3489,Buildings,Completed,NC-MADHAVARAM,31,568000,"Reparis and Improvements existing PC at Kannabiran Kovil st (Indital Company), Udaiyar thottam and Pandian street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/3503,Storm Water Drain,Completed,NC-MADHAVARAM,31,866000,"Construction of Side Drain at Ambedkar Nagar from Jn of GNT Road to Ambedhkar Nagar 3rd Main Road in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/3504,Storm Water Drain,Completed,NC-MADHAVARAM,31,866000,"Construction of Side Drain at Ambedkar Nagar from Ambedhkar Nagar 2nd Main Road to Ambedhkar Nagar 1st Main Road in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/3505,Storm Water Drain,Completed,NC-MADHAVARAM,31,866000,"Construction of Side drain at Ambedkar Nagar from Ambedhkar Nagar 1st Main Road to Kolkatta Shop 3rd Street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/4128,Roads,Completed,NC-MADHAVARAM,31,157000,"Restoration of Road Cut at Udaiyar Thottam 7th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4129,Roads,Completed,NC-MADHAVARAM,31,176000,"Restoration of Road Cut at Udaiyar Thottam 6th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4218,Roads,Completed,NC-MADHAVARAM,31,170000,"Restoration of Road Cut at Udaiyar Thottam 4th in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4219,Roads,Completed,NC-MADHAVARAM,31,220000,"Restoration of Road Cut at Udaiyar Thottam 3rd in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4221,Roads,Completed,NC-MADHAVARAM,31,261000,"Restoration of Road Cut at Udaiyar Thottam 2nd in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4397,Roads,Completed,NC-MADHAVARAM,31,710000,"Restoration of Road Cut at KKR Garden 2nd Main road in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4398,Roads,Completed,NC-MADHAVARAM,31,406000,"Restoration of Road cut at KKR Garden 4th Main road in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4401,Roads,Completed,NC-MADHAVARAM,31,339000,"Restoration of Road cut at KKR Garden 3rd Main road in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4402,Roads,Completed,NC-MADHAVARAM,31,100000,"Restoration of Road Cut at KKR Garden 2nd cross street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4404,Roads,Completed,NC-MADHAVARAM,31,486000,"Restoration of Road Cut at KKR Garden 1st Main road in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4702,Roads,Completed,NC-MADHAVARAM,31,162000,"Restoration of Road Cut at KKR Garden 1st cross street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4705,Roads,Completed,NC-MADHAVARAM,31,246000,"Restoration of Road Cut at KKR Garden 1st street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2018-19 NC/2016-17/4707,Roads,Completed,NC-MADHAVARAM,31,85000,"Restoration of Road Cut at KKR Garden 7th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4708,Roads,Completed,NC-MADHAVARAM,31,85000,"Restoration of Road Cut at KKR Garden 10th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/4709,Roads,Completed,NC-MADHAVARAM,31,352000,"Restoration of Road Cut at Royal Avenue in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5205,Roads,Completed,NC-MADHAVARAM,31,569000,"Restoration of Road Cut at Anna Nagar 4th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5206,Roads,Completed,NC-MADHAVARAM,31,694000,"Restoration of Road Cut at Dhansingh Maistry street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2018-19 NC/2016-17/5207,Roads,Completed,NC-MADHAVARAM,31,166000,"Restoration of Road Cut at KKR Nagar 2nd Avenue street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5208,Roads,Completed,NC-MADHAVARAM,31,175000,"Restoration of Road Cut at KKR Nagar 3rd Avenue street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5209,Roads,Completed,NC-MADHAVARAM,31,507000,"Restoration of Road Cut at Muthumariamman Kovil street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5210,Roads,Completed,NC-MADHAVARAM,31,461000,"Restoration of Road Cut at Ambedkar Nagar 1st Main road in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5213,Roads,Completed,NC-MADHAVARAM,31,258000,"Restoration of Road Cut at Ambedkar Nagar 1st street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5214,Roads,Completed,NC-MADHAVARAM,31,286000,"Restoration of Road Cut at Ambedkar Nagar 2nd street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5215,Roads,Completed,NC-MADHAVARAM,31,274000,"Restoration of Road Cut at Ambedkar Nagar 3rd street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5216,Roads,Completed,NC-MADHAVARAM,31,258000,"Restoration of Road Cut at Ambedkar Nagar 4th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5217,Roads,Completed,NC-MADHAVARAM,31,239000,"Restoration of Road Cut at Ambedkar Nagar 5th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5218,Roads,Completed,NC-MADHAVARAM,31,239000,"Restoration of Road Cut at Ambedkar Nagar 6th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5219,Roads,Completed,NC-MADHAVARAM,31,242000,"Restoration of Road Cut at Ambedkar Nagar 7th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5220,Roads,Completed,NC-MADHAVARAM,31,221000,"Restoration of Road Cut at Ambedkar Nagar 8th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5221,Roads,Completed,NC-MADHAVARAM,31,873000,"Restoration of Road Cut at Pandian street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2018-19 NC/2016-17/5223,Roads,Completed,NC-MADHAVARAM,31,200000,"Restoration of Road Cut at Palaniappa Nagar 3rd street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5227,Roads,Completed,NC-MADHAVARAM,31,221000,"Restoration of Road Cut at Palaniappa Nagar 4th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5228,Roads,Completed,NC-MADHAVARAM,31,221000,"Restoration of Road Cut at Palaniappa Nagar 5th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5230,Roads,Completed,NC-MADHAVARAM,31,378000,"Restoration of Road Cut at Thiru-vee-ka Nagar 1st street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5234,Roads,Completed,NC-MADHAVARAM,31,338000,"Restoration of Road Cut at Thiru-vee-ka Nagar 2nd street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5236,Roads,Completed,NC-MADHAVARAM,31,312000,"Restoration of Road Cut at Thiru-vee-ka Nagar 3rd street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5237,Roads,Completed,NC-MADHAVARAM,31,278000,"Restoration of Road Cut at Thiru-vee-ka Nagar 4th street in div-31, Unit-8, Zone-3.",Deposit Works,3,2016-17,2017-18 NC/2016-17/5466,Buildings,Completed,NC-MADHAVARAM,31,630000,"Construction of Bio Gas Plant at Muthumariamman Koil Street in Div-31, Unit-8, Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/5479,Buildings,Completed,NC-MADHAVARAM,31,736000,"Supply and errection of gas holder and burning system of Bio Gas Plant at Muthumariamman Koil Street in Div-31, Unit-8, Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/5866,Storm Water Drain,Completed,NC-MADHAVARAM,31,950000,"Raising and Improvements to side drain at Thiruvalluvar street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2016-17 NC/2016-17/5873,Storm Water Drain,Completed,NC-MADHAVARAM,31,950000,"Raising and Improvements to Side drain at Kannabiran koil street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/5875,Storm Water Drain,Completed,NC-MADHAVARAM,31,950000,"Raising and Improvements to Side Drain at Muthumariamman koil street in Div-31, Unit-8, Zone-3",Own Sources,3,2016-17,2016-17 NC/2016-17/5880,Storm Water Drain,Completed,NC-MADHAVARAM,31,998000,"Raising and Improvements to Side drain at Pandian street in div-31, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/5946,Roads,Completed,NC-MADHAVARAM,31,62000,REPAIRS AND IMPROVEMENTS TO PUBLIC CONCENIANCE AT AMBEDHKAR NAGAR AND THIDEER NAGAR AREAS IN DIVISION 31 UNIT 8 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/9852,Roads,Completed,NC-MADHAVARAM,31,839000,"Forming BT Road by Paver Finisher at K.K.R nagar extn in Div-31, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 BR/2016-17/11279,Roads,Completed,BR-Bus Route Roads,32,4190000,"Restoration of road cut at Surapet main road ( from CANAL to 650 m ) in div -24 , zone - 03",Deposit Works,3,2016-17,2016-17 BR/2016-17/6503,Roads,Completed,BR-Bus Route Roads,32,3800000,"Restoration of Road Cut at Villivakam road (From junction of surapet main road to 500 Meters ) in Dn-26 and 32, Zone-03",Deposit Works,3,2016-17,2016-17 BR/2016-17/6511,Roads,Completed,BR-Bus Route Roads,32,3800000,"Restoration of Road Cut at Villivakam road (From the Junction of kadappa road to a length of 500 Meters) in Dn-26 and 32, Zone-03",Deposit Works,3,2016-17,2016-17 BR/2016-17/9763,Storm Water Drain,Completed,BR-Bus Route Roads,32,2260000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Cudappa road in div 32, Zone -03.",Grants,3,2016-17,2016-17 L/2016-17/14882,Electrical,Completed,L-Electrical,32,131300,"Painting of 613 Nos of 6mtr lamp post, 73Nos of 8mtr lamp post & 25 nos of KIOSK Pillar box at Various streets in Div-32 of Zone-III.",Own Sources,3,2016-17,2018-19 NC/2016-17/0688,Buildings,Completed,NC-MADHAVARAM,32,982000,IMPROVEMENTS TO CHENNAI HIGHER SECONDARY SCHOOL AT BHARATHIAR STREET IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/0901,Buildings,Completed,NC-MADHAVARAM,32,100700,REPAIRS AND IMPROVEMENTS TO PUBLIC TOILET AT ASHOKA STREET IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2016-17,2016-17 NC/2016-17/10403,Roads,Completed,NC-MADHAVARAM,32,545000,"Forming BT road by Paver Finisher at Bharathiyar 1st cross street in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/11348,Buildings,Completed,NC-MADHAVARAM,32,998000,"Construction of Gym Building at Asshoka street in Div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/17254,Roads,Completed,NC-MADHAVARAM,32,644000,"Attending to temporary restoration of damaged interior roads due to Varadha Cyclone at Nandha Nagar in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17260,Roads,Completed,NC-MADHAVARAM,32,446000,"Attending to temporary restoration of damaged interior roads due to Varadha Cyclone at sarathy ngr 2nd street in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17261,Roads,Completed,NC-MADHAVARAM,32,556000,"Attending to temporary restoration of damaged interior roads due to Varadha Cyclone at sarathy ngr 3rd street in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17264,Roads,Completed,NC-MADHAVARAM,32,703000,"Attending to temporary restoration of damaged interior roads due to Varadha Cyclone at Ganapathy Nagar in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17266,Roads,Completed,NC-MADHAVARAM,32,668000,"Attending to temporary restoration of damaged interior roads due to Varadha Cyclone at Venkateshwara Nagar in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17401,Parks,Completed,NC-MADHAVARAM,32,164000,"Reparis and Improvements to Parks (Damaged due to Varadha Cyclone) at Teachers colony 4th cross street in Division-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17415,Parks,Completed,NC-MADHAVARAM,32,165000,"Reparis and Improvements to Parks (Damaged due to Varadha Cyclone) at Teachers colony 6thmain road in Division-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17430,Roads,Completed,NC-MADHAVARAM,32,240000,"Reparis & New fixing of street name board (Damaged) due to Varatha Cyclone at various street in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/18028,Buildings,Completed,NC-MADHAVARAM,32,713000,"Construction of Shed for source seggregation at Ashoka street inside PC and improvements of PC Ashoka street in Div-32, Unit-8, Zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/18031,Buildings,Completed,NC-MADHAVARAM,32,437000,"Construction of Source seggreation shed at Teachers colony 7th main road in div-32, unit-8, zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/2359,Storm Water Drain,Completed,NC-MADHAVARAM,32,338000,"Desilting of Side drain at Thiruvalluvar st, Vivekananda st, Nethaji st, Sankaralingam st, Kadappah road, E.V.R. st, Teacher colony 5th Main road, V.O.C st, Gangaiamman kovil st, Amman kovil st, Kumaran st, Lakshmi Narayana Perumal Kovil st, Bharathiyar st, Rajaji st, Thilagar st Villivakkam road, Bajanai kovil st, Ashoka st, Kalingnar st, and Kamaraj st in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/4967,Roads,Completed,NC-MADHAVARAM,32,321000,"Restoration of Road cut at Annai parasakthi nagar in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4971,Roads,Completed,NC-MADHAVARAM,32,453000,"Restoration of Road cut at Annai siva sakthi nagar in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4972,Roads,Completed,NC-MADHAVARAM,32,169000,"Restoration of Road cut at Devi nagar in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4973,Roads,Completed,NC-MADHAVARAM,32,223000,"Restoration of Road cut at Kalamagal nagar 3rd street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4976,Roads,Completed,NC-MADHAVARAM,32,167000,"Restoration of Road cut at Kasthuri nagar 1st street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4981,Roads,Completed,NC-MADHAVARAM,32,287000,"Restoration of Road cut at Kasthuri nagar 2nd street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4982,Roads,Completed,NC-MADHAVARAM,32,381000,"Restoration of Road cut at Kasthuri nagar 3rd street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4985,Roads,Completed,NC-MADHAVARAM,32,388000,"Restoration of Road cut at Kasthuri nagar 4th street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4986,Roads,Completed,NC-MADHAVARAM,32,430000,"Restoration of Road cut at Kasthuri nagar 5th street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4989,Roads,Completed,NC-MADHAVARAM,32,822000,"Restoration of Road cut at Kumaran street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2018-19 NC/2016-17/4990,Roads,Completed,NC-MADHAVARAM,32,165000,"Restoration of Road cut at Vinayagar koil street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4991,Roads,Completed,NC-MADHAVARAM,32,203000,"Restoration of Road cut at Sapthagiri nagar in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4993,Roads,Completed,NC-MADHAVARAM,32,848000,"Restoration of Road cut at Adhilakshmi nagar in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4994,Roads,Completed,NC-MADHAVARAM,32,170000,"Restoration of Road cut at Sri ramanujar nagar in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4995,Roads,Completed,NC-MADHAVARAM,32,545000,"Restoration of Road cut at Sarathy nagar 1st street in div-32, Unit-8, Zone-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5956,Buildings,Completed,NC-MADHAVARAM,32,491000,"Improvements to NHUM at Gangai Amman Koil Street in Div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/5958,Buildings,Completed,NC-MADHAVARAM,32,616000,"Reparis and Improvements to Amma Unavagam at Gangai Amman Koil street in div-32, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 BR/2016-17/9765,Storm Water Drain,Completed,BR-Bus Route Roads,33,2350000,"STRENGHTENING AND RELAYING THE road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Prakash nagar main road in div 33, Zone -03.",Grants,3,2016-17,2017-18 L/2016-17/13735,Electrical,Completed,L-Electrical,33,123500,Removing & refixing of 6 Nos of 6mtr lamp post at Kasi Amman Nagar Main Road in Div-33 of Zone-III (Madhavaram),Own Sources,3,2016-17,2019-20 L/2016-17/13739,Electrical,Completed,L-Electrical,33,145000,"Supply & Fixing 9 nos of 63amp / 3Phase analogue automatic street lighting ON/OFF controlling timer units at Various locations in Div- 33 , Zone-III, Madhavaram.",Own Sources,3,2016-17,2018-19 L/2016-17/14883,Electrical,Completed,L-Electrical,33,152300,"Painting of 767 Nos of 6mtr lamp post, 45 Nos of 8mtr lamp post & 26 nos of KIOSK Pillar box at Various streets in Div-33 of Zone-III",Own Sources,3,2016-17,2018-19 NC/2016-17/10467,Roads,Completed,NC-MADHAVARAM,33,732000,"PROVIDING AND LAYING BT ROAD WITH PAVER FINISHER AT GANDHI NAGAR MAIN ROAD IN DN-33 UNIT-8,ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10485,Roads,Completed,NC-MADHAVARAM,33,663000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT ANNAPOORNA NAGAR 1ST CROSS STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10510,Roads,Completed,NC-MADHAVARAM,33,937000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT ANNAPOORNA NAGAR 2ND CROSS STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10512,Roads,Completed,NC-MADHAVARAM,33,1363000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT ANNAPOORNA NAGAR EXTN. IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10514,Roads,Completed,NC-MADHAVARAM,33,745000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT KANDAN NAGAR 3RD STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10519,Roads,Completed,NC-MADHAVARAM,33,322000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT SUMATHI NAGAR 1ST CROSS STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10525,Roads,Completed,NC-MADHAVARAM,33,322000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT SUMATHI NAGAR 2ND STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10529,Roads,Completed,NC-MADHAVARAM,33,994000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT SRIKRISHNA NAGAR IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10545,Roads,Completed,NC-MADHAVARAM,33,392000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT SUFFER AVENUE IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10550,Roads,Completed,NC-MADHAVARAM,33,687000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT MAHAVISHNU NAGAR 1ST STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10558,Roads,Completed,NC-MADHAVARAM,33,687000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT MAHAVISHNU NAGAR 2ND STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10563,Roads,Completed,NC-MADHAVARAM,33,687000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT MAHAVISHNU NAGAR 3RD STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10569,Roads,Completed,NC-MADHAVARAM,33,687000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT MAHAVISHNU NAGAR 4TH STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10572,Roads,Completed,NC-MADHAVARAM,33,719000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT DILLY AVENUE IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10577,Roads,Completed,NC-MADHAVARAM,33,392000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT LAKSHMI NAGAR IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10581,Roads,Completed,NC-MADHAVARAM,33,1226000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT ELIZABETH NAGAR 1ST STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10586,Roads,Completed,NC-MADHAVARAM,33,980000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT ELIZABETH NAGAR 2ND STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10601,Roads,Completed,NC-MADHAVARAM,33,443000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT RAGAVENDRA NAGAR MAIN ROAD IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10606,Roads,Completed,NC-MADHAVARAM,33,414000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT RAGAVENDRA NAGAR 1ST STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10608,Roads,Completed,NC-MADHAVARAM,33,392000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT NSS NAGAR IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10610,Roads,Completed,NC-MADHAVARAM,33,853000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT VISHNU NAGAR MAIN ROAD AT DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10612,Roads,Completed,NC-MADHAVARAM,33,784000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT MAHAVISHNU NAGAR MAIN ROAD AT DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/10613,Roads,Completed,NC-MADHAVARAM,33,540000,"PROVIDING AND LAYING OF BT ROAD WITH PAVER FINISHER AT GANDHI NAGAR 3RD STREET IN DN-33,UNIT-8 ZONE-3",Own Sources,3,2016-17,2017-18 NC/2016-17/16831,Storm Water Drain,Completed,NC-MADHAVARAM,33,980000,"Repairs to canal retaining wall at 80 feet road in Division 33,Unit 8, Zone 3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17333,Roads,Completed,NC-MADHAVARAM,33,549000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Periyar Nagar main road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17336,Roads,Completed,NC-MADHAVARAM,33,720000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Rangasamy road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17344,Roads,Completed,NC-MADHAVARAM,33,446000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Chandraprabhu Colony 7th Main Road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17346,Roads,Completed,NC-MADHAVARAM,33,412000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Chandraprabhu Colony Main Road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17349,Roads,Completed,NC-MADHAVARAM,33,480000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Anna Street in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17350,Roads,Completed,NC-MADHAVARAM,33,412000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Anna 1st Street in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17357,Roads,Completed,NC-MADHAVARAM,33,377000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Brindavan garden Main Road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17359,Roads,Completed,NC-MADHAVARAM,33,343000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Thanigachalam Nagar B Blk 1st Cross St in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17362,Roads,Completed,NC-MADHAVARAM,33,343000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Thanigachalam Nagr B Blk 2nd Cross St in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17363,Roads,Completed,NC-MADHAVARAM,33,308000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Sriraman Salai North in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17366,Roads,Completed,NC-MADHAVARAM,33,343000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Thanigachalam Nagar A blk 1st Cross St in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17369,Roads,Completed,NC-MADHAVARAM,33,343000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Thanigachalam Nagr A Blk 2nd Cross St in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17375,Roads,Completed,NC-MADHAVARAM,33,497000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Kamarajar Street South West in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17376,Roads,Completed,NC-MADHAVARAM,33,583000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Madurai Manavalan Nagar in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17377,Roads,Completed,NC-MADHAVARAM,33,240000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Thanigachalam Nagar G Blk 8th Main Road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17385,Roads,Completed,NC-MADHAVARAM,33,412000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Selvam Nagar 2nd Main Road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17389,Roads,Completed,NC-MADHAVARAM,33,172000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Selvam Nagar 1st Main Road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17390,Roads,Completed,NC-MADHAVARAM,33,240000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Selvam Nagar 1st Street in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17394,Roads,Completed,NC-MADHAVARAM,33,583000,"Attending temporary restoration of damaged interior roads due to Varadha Cyclone at Sarangapani Street in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17435,Parks,Completed,NC-MADHAVARAM,33,466000,"Reparis and Improvements to park (Damaged due to varatha cyclone) at Thanikachalam Nagar, Selvam Nagar and VGP Nagar in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/17439,Roads,Completed,NC-MADHAVARAM,33,942000,"Reparis and New fixing of street name board (damaged due to varatha cyclone) at various street in div-33, unit-8, zone-3.",Own Sources,3,2016-17,2017-18 NC/2016-17/2360,Storm Water Drain,Completed,NC-MADHAVARAM,33,520000,"Desilting of Side Drains at VGP Santhose Nagar Main road, Brindhavan Nagar Main road, Kamaraj nagar west, Chakarpani st, Mahathma Gandhi stg, Krishna Nagar Main road, Anna street, Anna st, Anna st, Sarangapani st, Sundramurthy st, Thiruvlluvar st, Kambar st, Selvam Nagar Main road, Thiyagarajan salai, Selvam Nagar 2nd main road, Sriram Salai, Vasudeva Mudhali st, Shanthi colony, Thanikachalam Nagar 2nd main road, Thanikachalam Nagar A block 1st main road, Thanikachalam Nagar b blk 5th main road, Manavalan st, Balakrishna Nagar, Anna poorna Nagar, Periyar Nagar main road, Vidhya Nagar Main road, V.P.C Nagar main road, Srinivasa Nagar main road, Munusamy Nagar main road and Prakash Nagar main road in div-33, Unit-8, Zone-3.",Own Sources,3,2016-17,2018-19 NC/2016-17/4200,Road Cut,Completed,NC-MADHAVARAM,33,467000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT BALAKRISHNA MURTHY MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/4201,Road Cut,Completed,NC-MADHAVARAM,33,108000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT BALAKRISHNA NAGAR IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4202,Road Cut,Completed,NC-MADHAVARAM,33,350000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT BHARATHI NAGAR 1ST STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/4243,Road Cut,Completed,NC-MADHAVARAM,33,79000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT GANDHI NAGAR 2nd STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4905,Road Cut,Completed,NC-MADHAVARAM,33,696000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT ANNA STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/4906,Road Cut,Completed,NC-MADHAVARAM,33,129000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT ANNAI SATHYA NAGAR 1ST CROSSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5279,Road Cut,Completed,NC-MADHAVARAM,33,366000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT IYYER THOTAM 1ST STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5280,Road Cut,Completed,NC-MADHAVARAM,33,369000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT IYYER THOTAM 2ND STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5370,Road Cut,Completed,NC-MADHAVARAM,33,725000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT PERIYAR NAGAR ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5374,Road Cut,Completed,NC-MADHAVARAM,33,338000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT PERIYA SALAI STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5376,Road Cut,Completed,NC-MADHAVARAM,33,160000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT RAJAJI 3RD STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5404,Road Cut,Completed,NC-MADHAVARAM,33,115000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT RAJAJI 4TH STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5405,Road Cut,Completed,NC-MADHAVARAM,33,134000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT RAJAJI 5TH STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5409,Road Cut,Completed,NC-MADHAVARAM,33,484000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT RAJAJI ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5415,Road Cut,Completed,NC-MADHAVARAM,33,201000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT RAMALINGA COLONY B BLOCK MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5416,Road Cut,Completed,NC-MADHAVARAM,33,529000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT CHANDRA PRABHU COLONY 4TH MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5418,Road Cut,Completed,NC-MADHAVARAM,33,218000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT CHANDRA PRABHU COLONY 5TH STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5420,Road Cut,Completed,NC-MADHAVARAM,33,256000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT CHANDRA PRABHU COLONY 6TH STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5421,Road Cut,Completed,NC-MADHAVARAM,33,293000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT CHANDRA PRABHU COLONY 2ND MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5423,Road Cut,Completed,NC-MADHAVARAM,33,86000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SARANGAPANI STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/5424,Road Cut,Completed,NC-MADHAVARAM,33,156000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SELVAM NAGAR 3RD CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5425,Road Cut,Completed,NC-MADHAVARAM,33,110000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SELVAM NAGAR 4TH CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5427,Road Cut,Completed,NC-MADHAVARAM,33,132000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SELVAM NAGAR 6TH CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5430,Road Cut,Completed,NC-MADHAVARAM,33,338000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SELVAM NAGAR MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5433,Road Cut,Completed,NC-MADHAVARAM,33,258000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SRI RAMAN SALAI 1ST CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5439,Road Cut,Completed,NC-MADHAVARAM,33,437000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SRI RAMAN SALAI CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5441,Road Cut,Completed,NC-MADHAVARAM,33,132000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SUNDARAMOORTHY ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5442,Road Cut,Completed,NC-MADHAVARAM,33,101000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANGARAJ STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5445,Road Cut,Completed,NC-MADHAVARAM,33,891000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR 80 FEET ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5460,Road Cut,Completed,NC-MADHAVARAM,33,169000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR A BLOCK 1ST MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5563,Road Cut,Completed,NC-MADHAVARAM,33,83000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT SRI RAMAN SALAI 2ND CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/5830,Buildings,Completed,NC-MADHAVARAM,33,998000,"Construction of amma unavagam phase-II at Annai sathya nagar in div 33,unit-8,zone-3",Own Sources,3,2016-17,2017-18 NC/2016-17/6613,Road Cut,Completed,NC-MADHAVARAM,33,437000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR 1st MAIN ROAD 1st,3rd & 4th CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6614,Road Cut,Completed,NC-MADHAVARAM,33,641000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR 2nd MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6615,Road Cut,Completed,NC-MADHAVARAM,33,477000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR 3rd MAIN ROAD 1st, 2nd CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6616,Road Cut,Completed,NC-MADHAVARAM,33,678000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR 4TH MAIN ROAD 1st, 3rd, 4th & 5th CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6620,Road Cut,Completed,NC-MADHAVARAM,33,650000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR 80 FEET ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6622,Road Cut,Completed,NC-MADHAVARAM,33,461000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THIRUVALLUVAR MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6623,Road Cut,Completed,NC-MADHAVARAM,33,553000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT VGP NAGAR 1st & 2nd STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6625,Road Cut,Completed,NC-MADHAVARAM,33,207000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT VOC STREETIN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/6812,Road Cut,Completed,NC-MADHAVARAM,33,640000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT THANIKACHALAM NAGAR 2nd MAIN ROAD 1st,2nd & 3rd CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2016-17 NC/2016-17/6814,Road Cut,Completed,NC-MADHAVARAM,33,696000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT BRINDHAVAN GARDEN MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Deposit Works,3,2016-17,2017-18 NC/2016-17/7492,Roads,Completed,NC-MADHAVARAM,33,693000,"PROVIDING AND LAYING WMM PATCH AND ALONG WITH STORM WATER DRAIN COVER SLAB AT THANIGACHALLAM NAGAR A BLOCK 3RD MAIN,THANIGACHALLAM NAGAR A BLOCK 3RD STREET AND VERIOUS STREET IN DN-33 UNIT-8 ZONE-3",Own Sources,3,2016-17,2016-17 NC/2016-17/7494,Roads,Completed,NC-MADHAVARAM,33,285500,"PROVIDING AND FIXING STREET NAME BOARD AT SUNDARAMOORTHY ROA,D ETHIRAJ ROAD, SRIRAMAN SALAI CROSS STREET, KAMBAR STREET AND VERIOUS STREET IN DN-33 UNIT-8 ZONE-3",Own Sources,3,2016-17,2016-17 P/2016-17/19676,Parks,Completed,P-Parks and Playfields,33,3473000,"FORMATION OF NEW PARK AT 80 FEET ROAD, THANIKACHALAM NAGAR,PONNIAMMANMEDU,MADHAVARAM IN DIVISION 33 UNIT 8 ZONE 3",Grants,3,2016-17,2018-19 BR/2016-17/10380,Roads,Completed,BR-Bus Route Roads,34,7125000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Kadumbadiamman koil street from Jn nof Tondiarpet high road to Jn of Vazhuthalaimedu road in Division -34 , Zone -04.",Grants,4,2016-17,2017-18 BR/2016-17/10423,Roads,Completed,BR-Bus Route Roads,34,9000000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Vazhuthalaimedu road from Jn of Kadumbadi amman koil street to jn of Balji palayam road in Division -34 , Zone -04.",Grants,4,2016-17,2017-18 BR/2016-17/10424,Roads,Completed,BR-Bus Route Roads,34,1635000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Palpannai salai (From jn of Manali salai to Jn of Kariya perumal koil street in Division -34 , Zone -04.",Grants,4,2016-17,2017-18 BR/2016-17/9579,Roads,Completed,BR-Bus Route Roads,34,4930000,"Strengthening and Relaying with DBM 50mm thick and CBC 40mm thick by Paver finishe using Plastic Waste along with Traffic Improvement work at College road in Dn.164, Zone-12",Grants,4,2016-17,2017-18 BR/2016-17/9580,Roads,Completed,BR-Bus Route Roads,34,570000,"Strengthening and Relaying with DBM 50mm thick and CBC 40mm thick by Paver finishe using Plastic Waste along with Traffic Improvement work at balusamy street in Dn.164, Zone-12",Grants,4,2016-17,2017-18 BR/2016-17/9581,Roads,Completed,BR-Bus Route Roads,34,1560000,"Strengthening and Relaying with DBM 50mm thick and CBC 40mm thick by Paver finishe using Plastic Waste along with Traffic Improvement work at krishna samy street in Dn.164, Zone-12",Grants,4,2016-17,2017-18 BR/2016-17/9582,Roads,Completed,BR-Bus Route Roads,34,5920000,"Strengthening and Relaying with DBM 50mm thick and CBC 40mm thick by Paver finishe using Plastic Waste along with Traffic Improvement work at balaji nagar main road in Dn.165, Zone-12",Grants,4,2016-17,2017-18 BR/2016-17/9583,Roads,Completed,BR-Bus Route Roads,34,7650000,"Strengthening and Relaying with DBM 50mm thick and CBC 40mm thick by Paver finishe using Plastic Waste along with Traffic Improvement work at thillai ganga nagar 2ND main road in Dn.162, Zone-12",Grants,4,2016-17,2017-18 L/2016-17/13770,Electrical,Completed,L-Electrical,34,185200,Replacement of 7 nos of Damaged Kiosk Pillar Boxes at various location in Division 34 and 35 in Zone IV.,Own Sources,4,2016-17,2017-18 L/2016-17/13785,Electrical,Completed,L-Electrical,34,48700,"Estimate for raising of 11 nos of Kiosk Pillar Boxes from the Ground Level at various location in Division 34,35,36,37,44,45 and 46 in Zone IV.",Own Sources,4,2016-17,2017-18 L/2016-17/19382,Electrical,Completed,L-Electrical,34,132200,"Numbering of 5831 Nos of Lamp Post at Various Location in Division 34,35 and 36",Own Sources,4,2016-17,2018-19 ND/2016-17/10108,Roads,Completed,ND-TONDIARPET,34,733000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 2nd MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/1466,Buildings,Completed,ND-TONDIARPET,34,987000,"FORMING NEW PLAY FIELD AT THENDRAL NAGAR 3rd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/16089,Parks,Completed,ND-TONDIARPET,34,160000,Attending repair works at park in Venkateshwara Colony 5th street due to Cyclone (Varadah) in div-34 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16092,Parks,Completed,ND-TONDIARPET,34,115000,Attending repair works at park in Binny nagar Main road due to Cyclone (Varadah) in div-34 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16093,Parks,Completed,ND-TONDIARPET,34,34000,Attending repair works at park in Union carbide colony 14th street due to Cyclone(Varadah) in div-34 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16094,Parks,Completed,ND-TONDIARPET,34,48500,Attending repair works at park in Kaveri nagar due to Cyclone(Varadah) in div-34 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16234,Roads,Completed,ND-TONDIARPET,34,250000,"SUPPLYING OF NEW TRI-CYCLE (COUNCILLOR FUND) IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/16426,Buildings,Completed,ND-TONDIARPET,34,8000,Attending repair works to Assistant Engineer office Building at Venketeshwara colony main road due to cyclone (varadah) in div-34 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16429,Buildings,Completed,ND-TONDIARPET,34,81500,Attending repair works to Compost yard at Arul nagar main road due to cyclone (varadah) in div-34 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16430,Buildings,Completed,ND-TONDIARPET,34,28700,Attending repair works to burial ground at Manali salai due to cyclone (varadah) in div-34 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/18792,Parks,Completed,ND-TONDIARPET,34,547000,"ANNUAL MAINTENANCE TO PARKS (2017) AT VENKATESWARA COLONY 5th STREET,UNION CARBIDE COLONY 14th STREET, BINNYNAGAR MAIN ROAD, KAVARI NAGAR IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2018-19 ND/2016-17/19235,Buildings,Completed,ND-TONDIARPET,34,335000,"Segregation center at Seetharam Nagar burial ground in div-34, unit-09, zone-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/19360,Buildings,Completed,ND-TONDIARPET,34,410000,Newly Construction of Well Ring Compost Yard at Division-34 Various places in Dn-34 U-09 Z-04,Own Sources,4,2016-17,2017-18 ND/2016-17/1967,Storm Water Drain,Completed,ND-TONDIARPET,34,997000,"DESILTING AND IMPROVEMENTS TO SWD AT MILK COLONY ROAD,N.S.K SALAI MAIN ROAD,SEETHARAM NAGAR 5th STREET,UNION CARBIDE COLONY 2nd,3rd,14th & 18th STREET,ARUL NAGAR MAIN ROAD,KATTABOMMAN MAIN ROAD,SEETHARAM NAGAR MAIN ROAD,VENKATESWARA COLONY MAIN ROAD,3rd & 5th STREET,SRI BALAJI NAGAR AND PALPANNAI SALAI IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2018-19 ND/2016-17/1971,Storm Water Drain,Completed,ND-TONDIARPET,34,995000,"DESILTING AND IMPROVEMENTS TO SWD AT VEDHATHAMURUGAPPAN STREET,(OTHAVADAI STREET),KADUMPADI AMMMAN KOIL STREET,KAVERI NAGAR MAIN ROAD,C.S.I SCHOOL ROAD,BALAJI NAGAR(GOYATHOPPU),SENTHIL NAGAR 2nd STREET,GANESH NAGAR MAIN ROAD,JUMBULI STREET(BHARATHI STREET),M.R.L COLONY 1st STREET,THENDRAL NAGAR 1st,3rd AND 4th STREET,RAVI GARDEN 1st,2nd,3rd,4th AND MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4746,Roads,Completed,ND-TONDIARPET,34,948000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 1st MAIN ROAD FROM JUNCTION OF VALUTHALAIMADU ROAD TO DURGAI AVENU 9th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4748,Roads,Completed,ND-TONDIARPET,34,989000,"RAISING AND FORMING THE ROAD AT DURGAI AVENUU 2nd MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4749,Roads,Completed,ND-TONDIARPET,34,711000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 3rd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4751,Roads,Completed,ND-TONDIARPET,34,995000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 5th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4770,Roads,Completed,ND-TONDIARPET,34,924000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 6th STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/4771,Roads,Completed,ND-TONDIARPET,34,995000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 13th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4772,Roads,Completed,ND-TONDIARPET,34,998000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 14th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4773,Roads,Completed,ND-TONDIARPET,34,998000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 16th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/5901,Roads,Completed,ND-TONDIARPET,34,120000,"RAISING AND FORMING THE ROAD AT VIJAY NAGAR IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5903,Roads,Completed,ND-TONDIARPET,34,343000,"RAISING AND FORMING THE ROAD AT GANESH NAGAR 1st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5904,Roads,Completed,ND-TONDIARPET,34,313000,"RAISING AND FORMING THE ROAD AT GANESH NAGAR 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5908,Roads,Completed,ND-TONDIARPET,34,241000,"RAISING AND FORMING THE ROAD AT GANESH NAGAR 3rd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5909,Roads,Completed,ND-TONDIARPET,34,576000,"RAISING AND FORMING THE ROAD AT PERIYAR NAGR IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5910,Roads,Completed,ND-TONDIARPET,34,356000,"RAISING AND FORMING THE ROAD AT SASTHRI NAGAR 1st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5911,Roads,Completed,ND-TONDIARPET,34,210000,"RAISING AND FORMING THE ROAD AT SASTHRI NAGAR 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5912,Roads,Completed,ND-TONDIARPET,34,356000,"RAISING AND FORMING THE ROAD AT SASTHRI NAGAR 3rd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5913,Roads,Completed,ND-TONDIARPET,34,300000,"RAISING AND FORMING THE ROAD AT BHARATHIDHASAN STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5980,Roads,Completed,ND-TONDIARPET,34,855000,"RAISING AND FORMING THE ROAD AT DURGAI AVENU 1st MAIN ROAD FROM JUNCTION OF DURGAI AVENU 13th STREET TO DURGAI AVENU 16 TH STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/6685,Storm Water Drain,Completed,ND-TONDIARPET,34,986000,"Desilting of Kodungaiyur Canal From Kamarajar Salai (Moolakadai junction) to Teachers Colony in Division-34, Unit-9, Zone-IV",Own Sources,4,2016-17,2019-20 ND/2016-17/8290,Parks,Completed,ND-TONDIARPET,34,492000,"ANNUAL MAINTENANCE TO BURIAL GROUND AT SEETHARAM NAGAR MANALI SALAI IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/9509,Roads,Completed,ND-TONDIARPET,34,388000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VIJAYALAKSHMI NAGAR MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9531,Roads,Completed,ND-TONDIARPET,34,388000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT VIJAYALAKSHMI NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9585,Roads,Completed,ND-TONDIARPET,34,625000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT RAGAVAN NAGAR NEW STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9586,Roads,Completed,ND-TONDIARPET,34,939000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT RAGAVAN NAGAR MAIN ROAD IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9587,Roads,Completed,ND-TONDIARPET,34,908000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT S.R NAGAR 1st STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9588,Roads,Completed,ND-TONDIARPET,34,803000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT S.R NAGAR 2nd STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9589,Roads,Completed,ND-TONDIARPET,34,742000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KADUMPADIAMMAN KOIL 4th STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9590,Roads,Completed,ND-TONDIARPET,34,499000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT KADUMPADIAMMAN KOIL 1st CROSS STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9591,Roads,Completed,ND-TONDIARPET,34,268000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SUGANTHAMAL NAGAR MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9592,Roads,Completed,ND-TONDIARPET,34,540000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SUGANTHAMAL NAGAR 1st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9593,Roads,Completed,ND-TONDIARPET,34,275000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SUGANTHAMAL NAGAR 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9594,Roads,Completed,ND-TONDIARPET,34,275000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SUGANTHAMAL NAGAR 3rd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9595,Roads,Completed,ND-TONDIARPET,34,275000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SUGANTHAMAL NAGAR 4th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9596,Roads,Completed,ND-TONDIARPET,34,2131000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 1st MAIN ROAD IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9598,Roads,Completed,ND-TONDIARPET,34,396000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 1st STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9599,Roads,Completed,ND-TONDIARPET,34,396000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 2nd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9600,Roads,Completed,ND-TONDIARPET,34,472000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 3rd STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9601,Roads,Completed,ND-TONDIARPET,34,646000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 4th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9602,Roads,Completed,ND-TONDIARPET,34,665000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 5th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9603,Roads,Completed,ND-TONDIARPET,34,615000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 6th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9604,Roads,Completed,ND-TONDIARPET,34,222000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 7th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9606,Roads,Completed,ND-TONDIARPET,34,207000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 8th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9607,Roads,Completed,ND-TONDIARPET,34,317000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 9th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9608,Roads,Completed,ND-TONDIARPET,34,411000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 10th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9609,Roads,Completed,ND-TONDIARPET,34,476000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 11th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9610,Roads,Completed,ND-TONDIARPET,34,378000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 12th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9611,Roads,Completed,ND-TONDIARPET,34,661000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 13th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9612,Roads,Completed,ND-TONDIARPET,34,789000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 14th STREET IN DN-34,U-9,Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9613,Roads,Completed,ND-TONDIARPET,34,378000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 15th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9615,Roads,Completed,ND-TONDIARPET,34,820000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT DURGAI AVENU 16th STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9616,Roads,Completed,ND-TONDIARPET,34,513000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT MAM RAMASAMY STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9617,Roads,Completed,ND-TONDIARPET,34,356000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SUBAM NAGAR IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9618,Roads,Completed,ND-TONDIARPET,34,906000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT PALPANNAI SALAI CROSS STREET IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9619,Roads,Completed,ND-TONDIARPET,34,1168000,"RE-LAYING B.T COURSE BY PAVER FINISHER AT SOUNDARYA NAGAR IN DN-34,U-9,Z-4.",Own Sources,4,2016-17,2016-17 L/2016-17/13775,Electrical,Completed,L-Electrical,35,704900,"Replacement of 440nos of Damaged 2core SMC Fuse Boxes and 50nos of 4core SMC Fuse Boxes at Thendral Nagar, Durgai Avenue, Muthamizh Nagar,Kannadosan Nagar, Sulpunal Karai and Vivekanandar Nagar Division 34,35 & 36 in Zone IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/10023,Roads,Completed,ND-TONDIARPET,35,860000,"Relaying of B.T.Course by Paver Finisher at Dr Anna Salai in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10033,Roads,Completed,ND-TONDIARPET,35,947000,"Relaying of B.T.Course by Paver Finisher at KKD Nagar 3rd main road Partly in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10034,Roads,Completed,ND-TONDIARPET,35,196000,"Relaying of B.T.Course by Paver Finisher at Cauvery Salai 4th street in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10035,Roads,Completed,ND-TONDIARPET,35,1041000,"Relaying of B.T.Course by Paver Finisher at KKD Nagar 6th main road Partly in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10082,Roads,Completed,ND-TONDIARPET,35,101000,"Relaying of B.T.Course by Paver Finisher at Cauvery Salai 5th street in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11082,Storm Water Drain,Completed,ND-TONDIARPET,35,698000,"Providing Rain water harvesting at Gandhi nagar and repair works for SWD at TH Road in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/11143,Road Cut,Completed,ND-TONDIARPET,35,838000,"Providing Portable Toilets 4 Nos with Water Tank 2000 Lit on Rental Basis and Maintenance for one Year at Muthamil nagar 8th Block Market in div-35,unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/11148,Road Cut,Completed,ND-TONDIARPET,35,961000,"Restoration of Road cut made by TANGEDCO at EVR Salai, Teachers 4th cross Street, Retamalai Street,Nethaji Street, Bakthavachalam Street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11149,Road Cut,Completed,ND-TONDIARPET,35,998000,"Restoration of Road cut made by TANGEDCO at Teachers colony Main Street, Teachers 5th cross street, Naayanar Street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11150,Road Cut,Completed,ND-TONDIARPET,35,967000,"Restoration of Road cut made by TANGEDCO at vetrivel street, kalaimagal street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11151,Road Cut,Completed,ND-TONDIARPET,35,954000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 161,164,165,166,167,168, Street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11152,Road Cut,Completed,ND-TONDIARPET,35,978000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 6th Block 155,156,157,158,159,160,162,163 Street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11153,Road Cut,Completed,ND-TONDIARPET,35,996000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 6th block Souh Avenue in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11154,Road Cut,Completed,ND-TONDIARPET,35,998000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 7th block North Avenue Road in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11155,Road Cut,Completed,ND-TONDIARPET,35,992000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 7th block179,180,181 street div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11156,Road Cut,Completed,ND-TONDIARPET,35,934000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 7th block 176,177,178 Street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11157,Road Cut,Completed,ND-TONDIARPET,35,945000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 8th BLOCK 202Street and 7th block 174,175 Street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11158,Road Cut,Completed,ND-TONDIARPET,35,907300,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 8th block 197,198,199,200,201 Street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11159,Road Cut,Completed,ND-TONDIARPET,35,977000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 8th Block 194,195,196 in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11160,Road Cut,Completed,ND-TONDIARPET,35,983000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 8th Block 192,203,204,205 street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11161,Road Cut,Completed,ND-TONDIARPET,35,852000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 8TH bLOCK 191,193 street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2018-19 ND/2016-17/11162,Road Cut,Completed,ND-TONDIARPET,35,993000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 8th block East Avenue Road in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2018-19 ND/2016-17/11163,Road Cut,Completed,ND-TONDIARPET,35,967000,"Restoration of Road cut made by TANGEDCO at Krishnamoorthy salai in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2017-18 ND/2016-17/11164,Road Cut,Completed,ND-TONDIARPET,35,900000,"Restoration of Road cut made by TANGEDCO at Muthamil nagar 8th block 206,207,208,209,210th street in div-35,unit-9, Zone-4",Deposit Works,4,2016-17,2018-19 ND/2016-17/11795,Buildings,Completed,ND-TONDIARPET,35,642000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Moolakadai Junction in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/11797,Buildings,Completed,ND-TONDIARPET,35,642000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Moolakadai Junction in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/11798,Buildings,Completed,ND-TONDIARPET,35,642000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for one year at K.K.D Nagar Bus Depot in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/11799,Buildings,Completed,ND-TONDIARPET,35,642000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for one year at K.K.D Nagar Bus Depot in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/14245,Buildings,Completed,ND-TONDIARPET,35,162000,"Improvements to Public Toilet at Chinnandimadam in div35, unit-9, zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/14250,Buildings,Completed,ND-TONDIARPET,35,212000,"improvements to Public Toilet at Anjugam nagar in Divison-35, unit-9, zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/15032,Buildings,Completed,ND-TONDIARPET,35,1550000,Proposed Construction of Compost Yard and Compound Wall at Muthamil Nagar 50th Street Kodungaiyur in Div-35 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/15382,Buildings,Completed,ND-TONDIARPET,35,400000,Improvements to Chennai High School at Kamarajar Salai In Div-35 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/1631,Storm Water Drain,Completed,ND-TONDIARPET,35,960000,"Improvements to Park at West Avenue Road, south avenue road, east avenue road, north avenue road Muthamil Nagar in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1644,Storm Water Drain,Completed,ND-TONDIARPET,35,968000,"Improvements to Park at Thiruvalluvar Salai, Sidco 1st,2nd,3rd Main road, KKD nagar 3rd Main road in Dn-35, U-9, Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1648,Storm Water Drain,Completed,ND-TONDIARPET,35,964000,"Desilting and Improvements of Storm Water Drains at 5th main road,Muthamil nagar, Anna salai, TH Road, in Dn-35, U-9, Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/16585,Buildings,Completed,ND-TONDIARPET,35,45500,"Attending Repair Works at Anganvadi Centre no 1159 in 3rd block Muthamil Nagar 52nd Street (due to Cyclone Vardah) in Dn-35,u-9,z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/16612,Buildings,Completed,ND-TONDIARPET,35,92000,"Attending Repair Works at Anganwadi building No.1156 Muthamil Nagar 1st block (due to Cyclone Vardah) in Dn-35,u-9,z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/16623,Buildings,Completed,ND-TONDIARPET,35,87000,"Attending Repair Works at Amma unavagam in MuthamilNagar 6th main road (Due to Cyclone Vardah) in Dn-35, U-09,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16626,Buildings,Completed,ND-TONDIARPET,35,858300,"Replacing the Street Name board at various street due to Cyclone Vardah in Dn-35, unit-09, Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16630,Buildings,Completed,ND-TONDIARPET,35,129300,"Attending Repair work at Division office, Unit office etc due to Cyclone Vardah in Divison-35, Unit-09,Zone-04",Own Sources,4,2016-17,2017-18 ND/2016-17/1685,Parks,Completed,ND-TONDIARPET,35,995000,"Improvements to Children Play Space at KKD nagar 4th block 2nd street (Councilar Ward Fund) in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/1729,Playfields,Completed,ND-TONDIARPET,35,994000,"Providing greenery and Lighting arrangement for children Play space at KKD nagar 4th block 2nd street (Councillar Fund) in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/1735,Parks,Completed,ND-TONDIARPET,35,940000,"Providing greenery and Lighting arrangement for children Play space at 9th street 1st block Muthamil nagar (COUNCILLOR FUND) in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/18708,Parks,Completed,ND-TONDIARPET,35,280000,Annual maintainance of parks at 9th street Muthamil nagar and Krishnan street in div-35 unit-9 Zone-4,Own Sources,4,2016-17,2018-19 ND/2016-17/19475,Storm Water Drain,Completed,ND-TONDIARPET,35,960000,"Desilting and improvements of existing storm water drain at West Avenue Road, south avenue road, east avenue road, north avenue road Muthamil Nagar in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/2083,Buildings,Completed,ND-TONDIARPET,35,984000,"PROPOSED DAY TO DAY REPAIR(PETTY) WORKS IN PARK IMPROVEMENTS IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/5100,Buildings,Completed,ND-TONDIARPET,35,982000,"LAYING ROOF AND BRICKWORK FOR AMMA UNAVAGAM PHASE-2 IN DIV-35, UNIT-,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/5167,Buildings,Completed,ND-TONDIARPET,35,989000,"Laying Tiles work and weathering course at Amma Unavagam Phase -2 at Division -35, unit-9, zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/5776,Buildings,Completed,ND-TONDIARPET,35,989000,"CONSTRUCTION OF RCC STRUCTURE WORK AT AMMA UNAVAGAM PHASE-II AT GNT ROAD( EH ROAD) IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6020,Buildings,Completed,ND-TONDIARPET,35,3500000,"DEMOLISION OF EXSISTING NNMP SHED AND ADDITIONAL CONSTRUCTION OF CHENNAI PRIMARY SCHOOL (GROUND, FIRST AND SECOND FLOOR) (MLA FUND) AT ANNA SALAI IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/6118,Buildings,Completed,ND-TONDIARPET,35,350000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT ANNA SALAI, ERUKKENCHERRY IN DIV-35,UNIT-9,ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/6244,Buildings,Completed,ND-TONDIARPET,35,986000,"Improvements to Burial Ground Assistant Room and care taker room at Mullai Nagar Burial Ground in Division-37, Unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6583,Storm Water Drain,Completed,ND-TONDIARPET,35,986000,"Desilting of Kodungaiyur Canal From 191st street 8th block Muthamil Nagar to Sathiyavani Muthu salai bridge (Chinnandimadam) in Division-35, Unit-9, Zone-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/6587,Storm Water Drain,Completed,ND-TONDIARPET,35,976000,"Improvements to Exsisting storm water drain at Tondiarpet High Road West avenue Road, KKD Nagar 5th cross street,KKD Nagar 3rd Main Road and Providing Cross pipes between TH Road to Canal in Div-35, Unit-9, Zone-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/6684,Storm Water Drain,Completed,ND-TONDIARPET,35,986000,"Desilting of Kodungaiyur Canal From Cauvery Salai Bridge to south avenue road Bridge in Division-35, Unit-9, Zone-IV",Own Sources,4,2016-17,2019-20 ND/2016-17/6872,Buildings,Completed,ND-TONDIARPET,35,200000,"Supplying of New Tri-Cycle (Councillor Fund) for Div-35, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/6874,Buildings,Completed,ND-TONDIARPET,35,996000,"Providing Conservancy labours rest Room at division Office in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/7843,Storm Water Drain,Completed,ND-TONDIARPET,35,997000,"Providing cross pipe and Storm water drain link with exsisting Storm Water Drain at 4th block, 5th block, muthamil nagar in div-35, unit-9, zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/8013,Storm Water Drain,Completed,ND-TONDIARPET,35,990000,"Providing cross pipe and Storm water drain link with exsisting Storm Water Drain at 6th block, 8th block, muthamil nagar in div-35, unit-9, zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/8014,Storm Water Drain,Completed,ND-TONDIARPET,35,995000,"Providing Hume pipe connection at Kamarajar Salai in div-35, unit-9, zone-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/8018,Playfields,Completed,P-Parks and Playfields,35,992000,"Improvements to Childrens Play Space at 6th main road, 2nd Block,muthamil Nagar in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/8043,Storm Water Drain,Completed,ND-TONDIARPET,35,984000,"Raising the exsisting storm water drain at Sidco 1st main road from KKD nagar 3rd main road in div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/8049,Storm Water Drain,Completed,ND-TONDIARPET,35,988000,"Raising the exsisting storm water drain at Sidco 1st main road from Sidco main road in div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/8056,Storm Water Drain,Completed,ND-TONDIARPET,35,993000,"Raising the exsisting storm water drain at Sidco 2Nd main road from KKD nagar 3rd main road in div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/8072,Buildings,Completed,ND-TONDIARPET,35,976000,"Providing Platform for bins at various locations in div-35, unit-9, zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/8180,Storm Water Drain,Completed,ND-TONDIARPET,35,992000,"Demolision and reconstruction of Storm water drain at Thiruvalluvar Salai From Ambedkar street to Ambedkar 1st street (RCC wall) in div-35, Unit-9, Zone-IV",Own Sources,4,2016-17,2018-19 ND/2016-17/8183,Storm Water Drain,Completed,ND-TONDIARPET,35,990000,"Demolision and reconstruction of Storm water drain at Thiruvalluvar Salai From Kodungaiyur Canal in TH Road to Ambedkar street (RCC wall) in div-35, Unit-9, Zone-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/8240,Storm Water Drain,Completed,ND-TONDIARPET,35,970000,Raising exsisting Storm water drain at Union Salai in Div-35 Unit-9 Zone-IV,Own Sources,4,2016-17,2017-18 ND/2016-17/8265,Buildings,Completed,ND-TONDIARPET,35,500000,"IMPROVEMENTS TO HEALTH POST AT DR. ANNA SALAI KODUGAIYUR IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/8441,Playfields,Completed,P-Parks and Playfields,35,987000,"Improvements to Play Ground at 3rd Main road 4th block Muthamil Nagar in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/8515,Playfields,Completed,P-Parks and Playfields,35,989000,"Improvements to Play Ground at 3rd Main road 4th block Muthamil Nagar and lighting arrangements at children Play space in 151st street 6th block Muthamil nagar in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/9746,Buildings,Completed,ND-TONDIARPET,35,993000,"Providing Electricalarrangements and water supply arrangements at Amma Unavagam phase-2 in Div-35, Unit-9, Zone-4",Own Sources,4,2016-17,2016-17 L/2016-17/13780,Electrical,Completed,L-Electrical,36,522200,"Replacement of 1348mtr 2x16sq.mm pvc Aluminium cable in the place of overhead wire at bharathi nagar, pudhu nagar, sharma nagar,S.A.colony, papathi amman koil street and various location in Div-36,Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/13781,Electrical,Completed,L-Electrical,36,542000,"Replacement of 1348mtr 2x16sq.mm pvc Aluminium cable in the place of overhead wire at M.R nagar, Rajiv gandhi nagar, Lakshmi amman nagar, sivagami street and various location in Div-36,Zone IV",Own Sources,4,2016-17,2016-17 ND/2016-17/10097,Roads,Completed,ND-TONDIARPET,36,339000,"Relaying of B.T.Course by Paver Finisher at Gandhi Nagar Main Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10102,Roads,Completed,ND-TONDIARPET,36,872000,"Relaying of B.T.Course by Paver Finisher at Eswari in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10104,Roads,Completed,ND-TONDIARPET,36,682000,"Relaying of B.T.Course by Paver Finisher at Kalamegam Street in Div-35, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10107,Roads,Completed,ND-TONDIARPET,36,314000,"Relaying of B.T.Course by Paver Finisher at Kalasathamman Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10110,Roads,Completed,ND-TONDIARPET,36,514000,"Relaying of B.T.Course by Paver Finisher at Kamatchi Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10112,Roads,Completed,ND-TONDIARPET,36,134000,"Relaying of B.T.Course by Paver Finisher at Bhagavathi 1st Cross Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10119,Roads,Completed,ND-TONDIARPET,36,263000,"Relaying of B.T.Course by Paver Finisher at Bhagavathi Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10121,Roads,Completed,ND-TONDIARPET,36,625000,"Relaying of B.T.Course by Paver Finisher at Nandanar Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10123,Roads,Completed,ND-TONDIARPET,36,183000,"Relaying of B.T.Course by Paver Finisher at Pugazhendhi Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10127,Roads,Completed,ND-TONDIARPET,36,340000,"Relaying of B.T.Course by Paver Finisher at Sundarar Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10130,Roads,Completed,ND-TONDIARPET,36,1864000,"Relaying of B.T.Course by Paver Finisher at Vasugi Nagar 2nd Main Road in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10133,Roads,Completed,ND-TONDIARPET,36,372000,"Relaying of B.T.Course by Paver Finisher at T.V Nagar 13th Cross Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10137,Roads,Completed,ND-TONDIARPET,36,181000,"Relaying of B.T.Course by Paver Finisher at Saravanan Cross Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10138,Roads,Completed,ND-TONDIARPET,36,546000,"Relaying of B.T.Course by Paver Finisher at T.V Nagar 10th Cross Street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/14778,Buildings,Completed,ND-TONDIARPET,36,330000,Maintanence Work at CHS at Sharmanagar 2nd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2016-17,2017-18 ND/2016-17/14779,Buildings,Completed,ND-TONDIARPET,36,400000,Maintanence Work at CPS at Sharmanagar 2nd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2016-17,2017-18 ND/2016-17/16048,Buildings,Completed,ND-TONDIARPET,36,420500,Attending Repair and maintenance Work at Vasugi Nagar Park Due to Cyclone ( Vardha) in Dn-36 U-09 Z-04,Own Sources,4,2016-17,2017-18 ND/2016-17/16073,Buildings,Completed,ND-TONDIARPET,36,216500,Attending Repair and Maintenance Work at MR Nagar Park Due to Cyclone ( Vardha) in Dn-36 U-09 Z-04,Own Sources,4,2016-17,2017-18 ND/2016-17/17613,Parks,Completed,ND-TONDIARPET,36,347000,"Annual Maintenance of Park at Sharma Nagar 1st main road,Sharma Nagar 3rd main road and 14th west cros street (6 Months) in DN-36,U-9,Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/18682,Buildings,Completed,ND-TONDIARPET,36,540000,Newly Construction of Compost Yard at 18th West Cross Street in DN-36 U-09 Z-04,Own Sources,4,2016-17,2018-19 ND/2016-17/18790,Buildings,Completed,ND-TONDIARPET,36,515000,"Newly Construction of Well Ring Compost Yard at West avenue Road, T.v.k 1st link Road ( T.V Nagar), T.v.k 1st link Road and T.v.k 2nd Link Road in Dn-36 U-09 Z-04",Own Sources,4,2016-17,2018-19 ND/2016-17/19935,Buildings,Completed,ND-TONDIARPET,36,985000,"PROPOSED DAY TO DAY REPAIR(PETTY) WORKS IN VARIOUS BUILDINGS IN DIV-36, UNIT-9, ZONE-4",Own Sources,4,2016-17,2019-20 ND/2016-17/2463,Storm Water Drain,Completed,ND-TONDIARPET,36,990000,"Name of work: Improvements to SWD at Bharathiyar Street, West Avenue Road (East Side), West Avenue Road (West Side), S.A Colony 1st Street to S.A Colony 10th Street, 2nd West Main Road in Dn-36, U-9, Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/2465,Storm Water Drain,Completed,ND-TONDIARPET,36,990000,"Name of work: Improvements to SWD at T.V.K 2nd Link Road, Viveakananda Nagar 2nd Street, T.V Nagar 7th Main Road, Kalamegam Street, Rajiv Gandhi Nagar 3rd Street, T.V Nagar 1st Main Road, Anna Salai Sastri Nagar (East Side), Anna Salai Sastri Nagar (West Side), S.A Colony 7th Street, Karunanithi Salai Main Street, Sharmanagar 1st main Road in Dn-36, U-9, Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/2466,Storm Water Drain,Completed,ND-TONDIARPET,36,990000,"Name of work: Improvements to SWD at Ethiraj Samy Salai, MR Nagar 5th cross Street, MR Nagar 1st Cross Street, MR Nagar 3rd Main Road, Vadivudaiamman Street, Vasugi Nagar 4th Street, Radhakrishnan Road, Nakeeran Street, Sidco Main Road, Park Street, Vasugi Nagar 6th Street, T.V Nagar 13th Main Road, T.V Nagar 5th Main Road ,T.V Nagar 4th cross Street, T.V.K 1st link Road (Service Road), Sharmanagar 2nd Main Road, Sharmanagar 9th Street in Dn-36, U-9, Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/3568,Storm Water Drain,Completed,ND-TONDIARPET,36,990000,"DESILTING OF VYSARPADI LINK CANAL FROM CLINIC ROAD TO HOUSE NO. 217 IN DIVISION 36,UNIT 9,ZONE 4",Own Sources,4,2016-17,2016-17 ND/2016-17/3569,Buildings,Completed,ND-TONDIARPET,36,980000,"Repairs and Improvements to P.C at E H Road,Sasthri nagar and IndiraGandhi nagar in Dn 36,Unit 9,Zone 4",Own Sources,4,2016-17,2018-19 ND/2016-17/5717,Roads,Completed,ND-TONDIARPET,36,990000,"Providing Street Name Board at N.s.k Street, Pandit nehru Street, Sivaraj Street, Siva Shanmugam Street, Dr.Ambedkar Street, Dr. Annie Besent Street, Jeevanandam Street, Kulasekaradasar Street, Kuppu Swamy Dasar Street, Mahatma Gandhi Street, Marai Malai Adigal Street, Bharathi Nagar East Street, Bharathi Nagar East Cross Street, Pudhu Nagar 6th Street,Pudhu Nagar 7th Street,Pudhu Nagar 8th Street, Rajiv Gandhi Nagar 6th Street, Rajiv Gandhi Nagar 7th Street, Rajiv Gandhi Nagar Main Street, Amman Koil Street, Saravanan Street and Pudhu Nagar A Block in Dn-36 U-09 Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/5718,Roads,Completed,ND-TONDIARPET,36,990000,"Providing Street Name Board at Sastri Nagar 1st Street to Sastri 19th Street, Sastri Nagar Anna Salai and Gandhi Nagar Main Street in Dn-36 U-09 Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/5733,Buildings,Completed,ND-TONDIARPET,36,999000,CONSTRUCTION OF COMPOUND WALL AND FOOT PATH TO PARK AT SA COLONY 8TH STREET 3RD CROSS IN DN-36 U-09 Z-04,Own Sources,4,2016-17,2016-17 ND/2016-17/5906,Parks,Completed,ND-TONDIARPET,36,799000,Improvement to Division Office Park At Sharmanagar 1st Main Road in Dn-36 U-09 Z-04,Own Sources,4,2016-17,2016-17 ND/2016-17/5937,Parks,Completed,ND-TONDIARPET,36,999000,IMPROVEMENTS GREEYNARY AND LIGHITING ARRANGEMENT INCLUDING PLAY APPARATUS TO PARK AT SA COLONY 8TH STREET 3RD CROSS IN DN-36 U-09 Z-04,Own Sources,4,2016-17,2017-18 ND/2016-17/6215,Storm Water Drain,Completed,ND-TONDIARPET,36,995000,"IMPROVEMENTS TO SWD AT VADIVUDAIAMMAN STREET, WEST AVENUE 2ND MAIN ROAD, THIRUVALLUVAR NAGAR 12TH MAIN ROAD, ETHIRAJ SAMY SALAI IN DN-36 U-09 Z-04",Own Sources,4,2016-17,2018-19 ND/2016-17/6239,Buildings,Completed,ND-TONDIARPET,36,980000,"Repairs and Improvements to C.H.S,C.P.S at Sharma nagar in Div - 36 Unit-9,Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/6241,Buildings,Completed,ND-TONDIARPET,36,995000,"Improvements to SI & CI Office at Sasthri Nagar 11th street in Div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6242,Buildings,Completed,ND-TONDIARPET,36,981000,"Improvements to gym at 15 West Cross Road in div-36, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6378,Playfields,Completed,ND-TONDIARPET,36,999000,"DEMOLITION & RE-CONSTRUCTION OF COMPOUND WALL FOR THE CHILDREN'S PLAY SPACE IN BETWEEN 17TH & 18TH WEST CROSS STREETS IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/6778,Buildings,Completed,ND-TONDIARPET,36,940000,BIN PLATFORM FLOORING FOR AT VARIOES LOCATION IN DN-36 U-09 Z-04,Own Sources,4,2016-17,2016-17 ND/2016-17/7231,Buildings,Completed,ND-TONDIARPET,36,200000,"Supplying of New Tri-Cycle (Councillor Fund) for Div-36, Unit-9, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/7378,Buildings,Completed,ND-TONDIARPET,36,836322,IMPROVEMENTS TO AMMA UNAVAGAM SHARMA NAGAR IN DN.36 UNIT.9 ZONE.4,Own Sources,4,2016-17,2018-19 ND/2016-17/7995,Buildings,Completed,ND-TONDIARPET,36,600000,DESILTING OF VYASARPADI LINK CANAL FROM HOUSE NO . 217 TO E.H ROAD CANAL MOUTH END TO ERUKKENCHERY (NEAR VAM MAHAL) IN DN-36 U-09 Z-04,Own Sources,4,2016-17,2017-18 ND/2016-17/8440,Buildings,Completed,ND-TONDIARPET,36,3985000,"Demolision of Exsisting Councilor and divsion Office and New construction of Multi purpose Hall (MLA FUND) in Div-36, Unit-9, Zone-4",MLACDS,4,2016-17,2017-18 ND/2016-17/8781,Parks,Completed,ND-TONDIARPET,36,538000,"IMPROVEMENTS TO THE EXISTING CHILDREN'S PLAY SPACE IN BETWEEN 17TH & 18TH WEST CROSS STREETS IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9486,Buildings,Completed,ND-TONDIARPET,36,985000,"Repairs and Improvements to P.C at Papathi amman street,Ambedkar street (East),and Ambedkar street (west) in Dn 36,Unit-9,Zone-4",Own Sources,4,2016-17,2018-19 BR/2016-17/10428,Roads,Completed,BR-Bus Route Roads,37,4935000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Ramakrishnan street from Jn of TVK link road to jn os saravanan street in Division -37 , Zone -04.",Grants,4,2016-17,2017-18 L/2016-17/13771,Electrical,Completed,L-Electrical,37,199980,"Replacement of 8 nos of Damaged Kiosk Pillar Boxes at various location in Division 36,37,44,45 and 46 in Zone IV.",Own Sources,4,2016-17,2017-18 L/2016-17/17835,Electrical,Completed,L-Electrical,37,3371000,"Provision of 37 Nos of 8Mtr Double Straight Bracket GI Street Lamp Post with 90 Watts LED Fitting in Centre Median at Manali Salai (KDG Road) in Dn:37, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/0804,Roads,Completed,ND-TONDIARPET,37,999000,"FIXING STREET NAME BOARDS (COUNCILLOR FUND) AT VARIOUS STREETS IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/0805,Roads,Completed,ND-TONDIARPET,37,799000,"FIXING STREET NAME BOARDS (COUNCILLOR FUND) AT VARIOUS STREETS IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/0806,Roads,Completed,ND-TONDIARPET,37,999000,"FIXING STREET NAME BOARDS (COUNSILOR FUND) AT VARIOUS STREETS IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10030,Roads,Completed,ND-TONDIARPET,37,407000,"Relaying of B.T.Course by Paver Finisher at Selvaraj Street in Div-37 Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10032,Roads,Completed,ND-TONDIARPET,37,363000,"Relaying of B.T.Course by Paver Finisher at Lenin Street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10036,Roads,Completed,ND-TONDIARPET,37,2478000,"Relaying of B.T.Course by Paver Finisher at KKD nagar 9th main road in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10041,Roads,Completed,ND-TONDIARPET,37,677000,"Relaying of B.T.Course by Paver Finisher at KKD nagar 8th main road in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10042,Roads,Completed,ND-TONDIARPET,37,625000,"Relaying of B.T.Course by Paver Finisher at KKD nagar 7th main road in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10043,Roads,Completed,ND-TONDIARPET,37,2434000,"Relaying of B.T.Course by Paver Finisher at KKD nagar 6th Main road in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10044,Roads,Completed,ND-TONDIARPET,37,418000,"Relaying of B.T.Course by Paver Finisher at KKD nagar 6th main cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10046,Roads,Completed,ND-TONDIARPET,37,195000,"Relaying of B.T.Course by Paver Finisher at KKD nagar 6th block 4th cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10047,Roads,Completed,ND-TONDIARPET,37,453000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 19th central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10048,Roads,Completed,ND-TONDIARPET,37,1355000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 19th East Cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10049,Roads,Completed,ND-TONDIARPET,37,456000,"Relaying of B.T.Course by Paver Finisher at MKB nagar 18th central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10051,Roads,Completed,ND-TONDIARPET,37,1355000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 18th east cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10052,Roads,Completed,ND-TONDIARPET,37,456000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 17th Central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10053,Roads,Completed,ND-TONDIARPET,37,1437000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 17th East Crioss street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10054,Roads,Completed,ND-TONDIARPET,37,479000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 16th Central Cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10055,Roads,Completed,ND-TONDIARPET,37,1437000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 16Th East Cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10057,Roads,Completed,ND-TONDIARPET,37,479000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 15th central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10058,Roads,Completed,ND-TONDIARPET,37,1082000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 15th east cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10059,Roads,Completed,ND-TONDIARPET,37,471000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 14th Central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10060,Roads,Completed,ND-TONDIARPET,37,1478000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 14th East cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10061,Roads,Completed,ND-TONDIARPET,37,456000,"Relaying of B.T.Course by Paver Finisher at MKB nagar 13th central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10062,Roads,Completed,ND-TONDIARPET,37,1478000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 13th East cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10064,Roads,Completed,ND-TONDIARPET,37,456000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 12th central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10065,Roads,Completed,ND-TONDIARPET,37,1355000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 12th East cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10066,Roads,Completed,ND-TONDIARPET,37,456000,"Relaying of B.T.Course by Paver Finisher at MKB nagar 11th central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10068,Roads,Completed,ND-TONDIARPET,37,1355000,"Relaying of B.T.Course by Paver Finisher at MKB nagar 11th East cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10069,Roads,Completed,ND-TONDIARPET,37,456000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 10th central cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10071,Roads,Completed,ND-TONDIARPET,37,1355000,"Relaying of B.T.Course by Paver Finisher at in MKB Nagar 10th East Cross street Div-37, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10072,Roads,Completed,ND-TONDIARPET,37,628000,"Relaying of B.T.Course by Paver Finisher at MKB nagar 3rd cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10075,Roads,Completed,ND-TONDIARPET,37,628000,"Relaying of B.T.Course by Paver Finisher at MKB nagar 2nd cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10076,Roads,Completed,ND-TONDIARPET,37,871000,"Relaying of B.T.Course by Paver Finisher at in MKB nagar 1st cross street Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10077,Roads,Completed,ND-TONDIARPET,37,209000,"Relaying of B.T.Course by Paver Finisher at inValluvar Cross street Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10078,Roads,Completed,ND-TONDIARPET,37,1957000,"Relaying of B.T.Course by Paver Finisher at Valluvar street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10080,Roads,Completed,ND-TONDIARPET,37,656000,"Relaying of B.T.Course by Paver Finisher at in 2nd street KSS madam Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10081,Roads,Completed,ND-TONDIARPET,37,1103000,"Relaying of B.T.Course by Paver Finisher at in 4th street KSS madam Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10083,Roads,Completed,ND-TONDIARPET,37,458000,"Relaying of B.T.Course by Paver Finisher at in 2nd cross street KSS madam Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10084,Roads,Completed,ND-TONDIARPET,37,1396000,"Relaying of B.T.Course by Paver Finisher at in 1st street KSS madam Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10085,Roads,Completed,ND-TONDIARPET,37,846000,"Relaying of B.T.Course by Paver Finisher at in TH road 1st street Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10087,Roads,Completed,ND-TONDIARPET,37,872000,"Relaying of B.T.Course by Paver Finisher at in Suseela Nagar 1st street Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10088,Roads,Completed,ND-TONDIARPET,37,314000,"Relaying of B.T.Course by Paver Finisher at KKD Nagar 6th block 5th cross sreetin Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10089,Roads,Completed,ND-TONDIARPET,37,416000,"Relaying of B.T.Course by Paver Finisher at KKD nagar 6th block 1st cross street in Div-37, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10090,Roads,Completed,ND-TONDIARPET,37,2645000,"Relaying of B.T.Course by Paver Finisher at Ramakrishnan street partly in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10091,Roads,Completed,ND-TONDIARPET,37,558000,"Relaying of B.T.Course by Paver Finisher at in Lingasan street Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10092,Roads,Completed,ND-TONDIARPET,37,319000,"Relaying of B.T.Course by Paver Finisher at Thiyagarajan street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10094,Roads,Completed,ND-TONDIARPET,37,246000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 6th cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10095,Roads,Completed,ND-TONDIARPET,37,750000,"Relaying of B.T .Course by Paver Finisher at Vivekanandha street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10096,Roads,Completed,ND-TONDIARPET,37,932000,"Relaying of B.T.Course by Paver Finisher at MKB Nagar 9th cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10098,Roads,Completed,ND-TONDIARPET,37,136000,"Relaying of B.T.Course by Paver Finisher at Abirami avenue 14th street 2nd lane in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10100,Roads,Completed,ND-TONDIARPET,37,591000,"Relaying of B.T .Course by Paver Finisher at Vedhamuthu street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10113,Roads,Completed,ND-TONDIARPET,37,481000,"Relaying of B.T.Course by Paver Finisher at Abirami Avenue 14th Street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10114,Roads,Completed,ND-TONDIARPET,37,215000,"Relaying of B.T.Course by Paver Finisher at subramani cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10115,Roads,Completed,ND-TONDIARPET,37,2239000,"Relaying of B.T.Course by Paver Finisher at MKB nagar 5th cross steet in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10116,Roads,Completed,ND-TONDIARPET,37,1231000,"Relaying of B.T.Course by Paver Finisher at M.K.B Nagar 7th cross street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10117,Roads,Completed,ND-TONDIARPET,37,1313000,"Relaying of B.T.Course by Paver Finisher at Kannan street in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10207,Roads,Completed,ND-TONDIARPET,37,671000,"Relaying of B.T.Course by Paver Finisher at 3rd street KSS madam in Div-37,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11300,Buildings,Completed,ND-TONDIARPET,37,984000,"Construction of Conservancy Labour rest room and Improvements to Division Office in Division-37, Unit-9, Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/13049,Buildings,Completed,ND-TONDIARPET,37,838000,"Providing Portable Toilets 4 Nos For Women with Water Tank 2000lt on Rental basis and maintenance for one year at Good Shed Road, Vyasarpadi, in Dn-37 Unit-09, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/13051,Buildings,Completed,ND-TONDIARPET,37,838000,"Providing Portable Toilets 4 Nos For Men with Water Tank 2000lt on Rental basis and maintenance for one year at Good Shed Road, Vyasarpadi, in Dn-37 Unit-9, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/13052,Buildings,Completed,ND-TONDIARPET,37,838000,"Providing Portable Toilets 4 Nos with Water Tank 2000lt on Rental basis and maintenance for one year at Sathya Moorthy Nagar Main Road, Mullai Nagar Bus Depot, in Dn-37 Unit-9, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/13607,Parks,Completed,ND-TONDIARPET,37,938000,"Improvements to center meridian including black and white painting and planting trees inside Kodungaiyur Dumping Ground in Div-37, Unit-9, Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/13608,Buildings,Completed,ND-TONDIARPET,37,986000,"Improvements and repairs to Weigh Bridge room and colour washing the existing compound wall at Kodungaiyur Dumping Ground in Division-37, Unit-9, Zone-IV",Own Sources,4,2016-17,2018-19 ND/2016-17/13842,Storm Water Drain,Completed,ND-TONDIARPET,37,200000,Supplying of New Tri-cycle (Councillor Fund ) for Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2016-17 ND/2016-17/14199,Buildings,Completed,ND-TONDIARPET,37,150000,Improvements to Public Convenience at JJ Nagar Main road in div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/14200,Buildings,Completed,ND-TONDIARPET,37,150000,Improvements to Public Convenience at JJ nagar 1st street in div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/14414,Buildings,Completed,ND-TONDIARPET,37,300000,Improvements to Chennai Primary School at Rajaratinam Nagar in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/14418,Buildings,Completed,ND-TONDIARPET,37,400000,Improvements to Chennai Primary School at MGR Nagar in div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/14419,Buildings,Completed,ND-TONDIARPET,37,400000,Improvements to Chennai Primary School at KKD Nagar 8th Block in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/15286,Buildings,Completed,ND-TONDIARPET,37,1414000,Construction of New Compost Yard with Secondary Segregation Shed including Shredding machine and Sieves at Mullai Nagar burial ground in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/15287,Buildings,Completed,ND-TONDIARPET,37,400000,Improvements to Chennai Primary School at MKB nagar 13th East cross street in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/15288,Buildings,Completed,ND-TONDIARPET,37,400000,Improvements to Chennai Primary School at Udhayasuriyan Nagar in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2018-19 ND/2016-17/15669,Roads,Completed,ND-TONDIARPET,37,1500000,Relaying of Cement Concrete road at Mullai Nagar Burial Ground in Div-37 Unit-9 Zone-4.,MLACDS,4,2016-17,2017-18 ND/2016-17/15992,Buildings,Completed,ND-TONDIARPET,37,69000,Attending Repair and maintenance work for Health post at 14th East Cross street MKB Nagar due to Cyclone (Varadah) in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/15993,Buildings,Completed,ND-TONDIARPET,37,141600,Attending repair and maintenance works to Assistant Engineer Office at 4th cross street MKB Nagar due to Cyclone (Varadah) in Div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/15994,Buildings,Completed,ND-TONDIARPET,37,379000,Attending repair and maintenance works to chennai primary school at 4th cross street MKB nagar due to Cyclone (Varadah) in Div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16002,Parks,Completed,ND-TONDIARPET,37,102000,Attending repair and maintenance works to park at MKB nagar 4th cross street due to cyclone (Varadah) in div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16003,Parks,Completed,ND-TONDIARPET,37,113000,Attending repair and maintenance work to the park at Gandhi Street due to cyclone (Varadah) in div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16004,Parks,Completed,ND-TONDIARPET,37,41000,Attending repair and maintenance works to Park at Ambedkar street due to cyclone (Varadah) in div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16005,Parks,Completed,ND-TONDIARPET,37,98000,Attending repairs and maintenance work to the Road side park at TH Road due to cyclone (Varadah) in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16016,Playfields,Completed,ND-TONDIARPET,37,27000,Attending repair and maintenance works to play field at RR nagar due to cyclone (Varadah) in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16037,Playfields,Completed,ND-TONDIARPET,37,160000,Attending repair and maintenance works at play field in Srinivasan street due to cyclone (Varadah) in div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16038,Playfields,Completed,ND-TONDIARPET,37,87800,Attending repairs and maintenance work to Play field at Udhayasuriyan Nagar due to Cyclone (Varadah) in div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16041,Playfields,Completed,ND-TONDIARPET,37,101000,Attending repair and maintenance works to the play field at Central Avenue road MKB nagar due to cyclone (Varadah) in Div-37 UNit-9 ZOne-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16042,Parks,Completed,ND-TONDIARPET,37,41100,Attending repairs and maintenance works to the park at 16th east cross street MKB nagar due to cyclone (Varadah) in Div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16047,Parks,Completed,ND-TONDIARPET,37,73000,Attending repair and maintenance works to park at Srinivasan street due to cyclone (Varadah) in div-37 unit -9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16055,Parks,Completed,ND-TONDIARPET,37,136000,Attending repair and maintenance works at park in Jawahar street due to cyclone (Varadah) in Div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16059,Parks,Completed,ND-TONDIARPET,37,20500,Attending repair and maintenance work at Park in KKD nagar 7th block due to cyclone (Varadah) in div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16066,Playfields,Completed,ND-TONDIARPET,37,42000,Attending repair and maintenance work to the play field at KKD nagar 8th block due to cyclone (Varadah) in div-37 Unit-9 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/1629,Storm Water Drain,Completed,ND-TONDIARPET,37,541000,"Desilting of S.W.D at S.M.Nagar Main Road (East Side) in Div-37, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/16349,Buildings,Completed,ND-TONDIARPET,37,179000,Attending repair and maintenance works to Auditorium at 7th block KKD nagar due to Cyclone (Varadah) in Div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16351,Buildings,Completed,ND-TONDIARPET,37,162500,Attending repair and maintainance works to Plastic shredding machine at TH road due to Cyclone(Varadah) in Div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16354,Buildings,Completed,ND-TONDIARPET,37,21500,Attending repairs and maintainence works to Night shelter at TH road due to Cyclone(Varadah) in Div-37 unit-9 zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/1636,Storm Water Drain,Completed,ND-TONDIARPET,37,541000,"Improvements to Park at S.M.Nagar Main Road (West Side) in Div-37, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/16398,Roads,Completed,ND-TONDIARPET,37,527000,"Replacing damaged street name board due to cyclone (varadha) at various places in div-37 unit-9, zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/1649,Storm Water Drain,Completed,ND-TONDIARPET,37,227000,"Desilting of S.W.D at J.J.Nagar Main Road in Div-37, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/1651,Storm Water Drain,Completed,ND-TONDIARPET,37,125000,"Improvements to Park at M.K.B Nagar 2nd Main road in Div-37, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/1653,Storm Water Drain,Completed,ND-TONDIARPET,37,125000,"Improvements to Park at M.K.B Nagar 3rd Main road in Div-37, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/1654,Storm Water Drain,Completed,ND-TONDIARPET,37,177000,"Desilting of S.W.D at M.K.B Nagar 4th Cross Street in Div-37, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/17364,Buildings,Completed,ND-TONDIARPET,37,330000,"Providing RCC Well ring (Well Type Composting) at Central Avenue road, TVK Link road, Tondiarpet High road in div-37 unit-9 Zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/1767,Storm Water Drain,Completed,ND-TONDIARPET,37,163000,"Improvements to Park at Manali Salai , Pathmavathy Street ,Balakrishnan Street , Abirami Avenue 14th Street , Ramakrishnan Street , Sarvappalli Street , Susila Nagar , Bhavani Street , Vivekanandha Street in Div-37 , Unit-9 , Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1771,Storm Water Drain,Completed,ND-TONDIARPET,37,325000,"Improvements to Park at T.H Road 1st Lane , M.K.B Nagar 4th , 5th & 6th Main Road , K.K.D Nagar 9th Main Road, Palani Street , Srinivasan Street , Lingesan Street , Service Road , Lurthu Mada Street in Div-37 , Unit-9 , Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1777,Storm Water Drain,Completed,ND-TONDIARPET,37,188000,"Improvements to Park at Goodshed Road in Div-37 , Unit-9 , Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1778,Storm Water Drain,Completed,ND-TONDIARPET,37,188000,"Improvements to Park at East Avenue Road in Div-37 , Unit-9 , Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1780,Storm Water Drain,Completed,ND-TONDIARPET,37,247000,"Desilting of S.W.D at M.K.B Nagar 5th Cross Street in Div-37 , Unit-9 , Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1810,Storm Water Drain,Completed,ND-TONDIARPET,37,223000,"Desilting of S.W.D at Ganapathy Street , M.K.B 1st Main Road , M.K.B 7th & 10th Main Road , Sasirekhamma 1st & 2nd street and Eswaran Street , R.R Nagar 1st , 2nd & 3rd Main Road , 4th Main Road , 'E' Block 6th Lane and 'K' Block 1st Lane in Div-37 , Unit-9 , Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/18575,Roads,Completed,ND-TONDIARPET,37,1500000,"Annual Maintainance of Corporation Park at Vivekanandha Street, Lingesan park, Sasirekkama park,Gandhi street park,Dr Ambedkar street park,Jawahar street park,Srinivasan street Park,16th East cross street MKB nagar,11th East cross street,4th cross street & golden complex in div-37, Unit-9, Zone-IV",Own Sources,4,2016-17,2018-19 ND/2016-17/1874,Storm Water Drain,Completed,ND-TONDIARPET,37,312000,"Desilting of S.W.D at Meenambal Salai (south) in Div-37, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/19706,Parks,Completed,ND-TONDIARPET,37,431000,"Maintenance of park at Jawahar street, Lingesan street, Vivekanandha street, Dr Ambedkar street, for three months in div-37 Unit-9 Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/19707,Parks,Completed,ND-TONDIARPET,37,426000,"Annual maintenance of park at Srinivasan street, gandhi street, Sasirekkama nagar, Kannadasan nagar 7th block park for three months",Own Sources,4,2016-17,2017-18 ND/2016-17/19708,Parks,Completed,ND-TONDIARPET,37,326000,"Maintenance of Park at MKB nagar 4th cross street,13th east cross street,16th east cross street in Div-37 Unit-9 Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/19936,Buildings,Completed,ND-TONDIARPET,37,989000,Annual maintainance of all corporation buildigs (day to day) in div-37 unit-9 zone-4,Own Sources,4,2016-17,2019-20 ND/2016-17/6030,Storm Water Drain,Completed,ND-TONDIARPET,37,985000,"RAISING THE EXSISTING STORM WATER DRAIN IN UDHAYASURIYAN NAGAR IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6032,Storm Water Drain,Completed,ND-TONDIARPET,37,985000,"Name of Work: RAISING THE EXSISTING STORM WATER DRAIN IN PALANI STREET IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6041,Storm Water Drain,Completed,ND-TONDIARPET,37,985000,"RAISING THE EXSISTING STORM WATER DRAIN IN NORTH AVENUE ROAD IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/6106,Storm Water Drain,Completed,ND-TONDIARPET,37,970000,"RAISING THE EXSISTING STORM WATER DRAIN IN MANALI SALAI (MKB NAGAR) IN DIV-37, UNIT-9, ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/6147,Buildings,Completed,ND-TONDIARPET,37,432000,"IMPROVEMENTS TO AMMA UNAVAGAM AT 7TH BLOCK KKD NAGAR IN DIVISION-37 , UNIT-9, ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/6176,Buildings,Completed,ND-TONDIARPET,37,465000,"IMPROVEMENTS TO AMMA UNAVAGAM AT MKB NAGAR IN DIVISION-37 , UNIT-9, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6243,Roads,Completed,ND-TONDIARPET,37,994000,"Providing WMM and laying Cement Concrete Road At Mullai Nagar Burial Ground in Div-37, Unit-9, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6245,Parks,Completed,ND-TONDIARPET,37,993000,"Filling Burial area of Mullai Nagar Burial Gound in Div-37, Unit-9,Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6246,Buildings,Completed,ND-TONDIARPET,37,524000,"Improvements to Chennai Primary School KKD nagar 8th block in Div-37, Unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6247,Playfields,Completed,ND-TONDIARPET,37,471000,"Improvements to Mullai Nagar Football ground in div-35, unit-9,zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/6354,Storm Water Drain,Completed,ND-TONDIARPET,37,493000,"PROVIDING PIPE CULVERT AT VARIOUS LOCATIONS INSIDE KODUNGAIYUR DUMPING GROUND IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/6360,Storm Water Drain,Completed,ND-TONDIARPET,37,493000,"PROVIDING PIPE CULVERT AT VARIOUS LOCATIONS INSIDE KODUNGAIYUR DUMPING GROUND IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/6376,Buildings,Completed,ND-TONDIARPET,37,334000,"PROVIDING GATE PILLARS AND GATE ( @ GATE N0-3 LOCATION ) AND RE-CONSTRUCTION OF DAMAGED COMPOUND WALL AT KODUNGAIYUR DUMPING GROUND IN DN-36, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/7085,Parks,Completed,ND-TONDIARPET,37,663000,"OUTSOURCING MAINTENANCE OF PARK LOCATED AT MULLAI NAGAR BURIGAL GROUND IN DIVISION-37, UNIT-9, ZONE-4.(FOR ONE YEAR)",Own Sources,4,2016-17,2017-18 ND/2016-17/7520,Storm Water Drain,Completed,ND-TONDIARPET,37,999000,"Demolition and Re-Construction of storm water drain at Goods shed Road From Opposite D/No.:31 to Opposite D/No.:162 in Dn:37, U:9, Z:IV",Own Sources,4,2016-17,2018-19 ND/2016-17/7522,Buildings,Completed,ND-TONDIARPET,37,752000,"Improvement and repairs to night shelter at TH road (Opp to KDG) in Div-37, Unit-9, zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/7524,Buildings,Completed,ND-TONDIARPET,37,952000,IMPROVEMENTS AND REPAIRS TO C.M.S SCHOOL AT MGR NAGAR IN DIV-37 UNIT-9 ZONE-4,Own Sources,4,2016-17,2017-18 ND/2016-17/7526,Storm Water Drain,Completed,ND-TONDIARPET,37,999000,"Demolition and Re-Construction of Storm Water Drain at goods shed road From Opposite D/No:162 to Opposite D/No:214 in Dn:37, U:9, Z:IV",Own Sources,4,2016-17,2017-18 ND/2016-17/7538,Storm Water Drain,Completed,ND-TONDIARPET,37,999000,"Demolition and Re-Construction of storm water drain at Goods shed Road From Opposite D/No.:214 to Opposite D/No.:273 in Dn:37, U:9, Z:IV",Own Sources,4,2016-17,2017-18 ND/2016-17/7834,Storm Water Drain,Completed,ND-TONDIARPET,37,974000,"Desilting of Kodungaiyur Canal from Meenambal Salai to Susila nagar main road in div-37, Unit-9,Zone-4.",Own Sources,4,2016-17,2019-20 ND/2016-17/7838,Storm Water Drain,Completed,ND-TONDIARPET,37,974000,"Desilting of Kodungaiyur Canal from Susila nagar main road to KDG main gate in div-37, Unit-9,Zone-4.",Own Sources,4,2016-17,2019-20 ND/2016-17/7840,Storm Water Drain,Completed,ND-TONDIARPET,37,974000,"Desilting of Kodungaiyur canal from KDG main gate to div-41 limit in div-37, unit-9, zone-4",Own Sources,4,2016-17,2019-20 ND/2016-17/8778,Parks,Completed,ND-TONDIARPET,37,797000,"IMPROVEMENTS TO THE EXISTING PARK AT 16TH EAST CROSS STREET IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/8779,Parks,Completed,P-Parks and Playfields,37,808000,"IMPROVEMENTS TO THE EXISTING PARK AT AMBEDKAR STREET IN KRISHNAMURTHY NAGAR IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2018-19 ND/2016-17/8780,Parks,Completed,P-Parks and Playfields,37,588000,"PROVIDING WATER SUPPLY ARRANGEMENTS, GREENERY WORKS AND CHILDREN'S PLAY APPARATUS TO THE EXISTING PARK ATAMBEDKAR STREET IN KRISHNAMURTHY NAGAR IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2018-19 ND/2016-17/8896,Parks,Completed,P-Parks and Playfields,37,856000,"IMPROVEMENTS TO THE EXISTING PARK AT ESWARAN STREET, SARADA NAGAR IN DN-37, UNIT-9, ZONE-4.",Own Sources,4,2016-17,2018-19 ND/2016-17/9141,Buildings,Completed,ND-TONDIARPET,37,938000,PROVIDING BIN PLATFORM FLOORING FOR VARIOUS LOCATIONS IN DIV-37 UNIT-9 ZONE-4,Own Sources,4,2016-17,2016-17 Q/2016-17/11811,Buildings,Completed,Q-Solid Waste Management,37,9000000,"CONSTRUCTION OF COMPOUND WALL AT KODINGAIYUR DUMPING YARD (CH 0-675 M) IN DIVISION-37, UNIT-09, ZONE-04.",Own Sources,4,2016-17,2017-18 Q/2016-17/11812,Buildings,Completed,Q-Solid Waste Management,37,9000000,"CONSTRUCTION OF COMPOUND WALL AT KODINGAIYUR DUMPING YARD (CH 676-1350 M) IN DIVISION-37, UNIT-09, ZONE-04.",Own Sources,4,2016-17,2017-18 Q/2016-17/11813,Buildings,Completed,Q-Solid Waste Management,37,9000000,"CONSTRUCTION OF COMPOUND WALL AT KODINGAIYUR DUMPING YARD (CH 1351-2025 M) IN DIVISION-37, UNIT-09, ZONE-04",Own Sources,4,2016-17,2018-19 Q/2016-17/11814,Buildings,Completed,Q-Solid Waste Management,37,9000000,"CONSTRUCTION OF COMPOUND WALL AT KODINGAIYUR DUMPING YARD(CH 2026-2700 M) IN DIVISION-37, UNIT-09, ZONE-04",Own Sources,4,2016-17,2018-19 Q/2016-17/11815,Buildings,Completed,Q-Solid Waste Management,37,3833000,"CONSTRUCTION OF LEACHEATEE COLLECTING TANK AND CHAMBER AT KODINGAIYUR DUMPING GROUND IN DN-37, UNIT-09, ZONE-04.",Own Sources,4,2016-17,2018-19 BR/2016-17/10429,Roads,Completed,BR-Bus Route Roads,38,3135000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements Mannapan street from jn of Pitty munusamy street to jn Elaya street Division -38 , Zone -04.",Grants,4,2016-17,2017-18 BR/2016-17/9663,Roads,Completed,BR-Bus Route Roads,38,8760000,"Strengthening and relaying of existing cement concrete road with M40 Concrete at Ellaya street (From Thyagappa street to Perumal koil garden 2 nd street in div 38 , Zone -04.",Grants,4,2016-17,2017-18 L/2016-17/13786,Electrical,Completed,L-Electrical,38,564600,"Replacement of 1005 Mtrs of 2 x 16 Sqmm PVC Alu,Cable at Durgha Devi Nagar, Phase I in Dn:38, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/15875,Electrical,Completed,L-Electrical,38,181100,"Replacement of 537 Mtrs of 4 x16 Sqmm PVC Alu.Cable at Ellaya Mudali Street, Northern side in Dn:38, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/18163,Electrical,Completed,L-Electrical,38,546700,"Replacement of 1314 Mts of 2 x 16 Sqmm PVC Alu.Cable at Annai Santhya Nagar in Dn:38, Zone IV.",Own Sources,4,2016-17,2017-18 L/2016-17/18165,Electrical,Completed,L-Electrical,38,414600,"Replacement 743 Mts of 4 x 16 Sqmm PVC Alu.Cable at Durga Devi Nagar, Phase II in Dn:38, Zone IV.",Own Sources,4,2016-17,2017-18 L/2016-17/18215,Electrical,Completed,L-Electrical,38,683100,"Replacement of 1622Mtrs of 2 x16 Sqmm PVC Alu.Cable at Nethaji Nagar 5th St, Main Street and Gandhi Nagar in Dn:38, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/18783,Electrical,Completed,L-Electrical,38,502300,"Replacement of 1016 Mtr of 2 x 16 Sqmm PVC Alu.Cable at Patel Nagar in Dn:38, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/7238,Electrical,Completed,L-Electrical,38,180800,"Replacement of 5 Nos. of Old Pillar box by New Kiosk Pillar Box at Various Places in Dn:38, Zone IV",Own Sources,4,2016-17,2016-17 L/2016-17/8007,Electrical,Completed,L-Electrical,38,158000,"890 Nos.of painting of Various Street Lamp Posts in Dn:38,40,43, Zone IV",Own Sources,4,2016-17,2016-17 ND/2016-17/10884,Buildings,Completed,ND-TONDIARPET,38,998000,"Additional Construction to Amma Unavagam at Nehru Nagar Main Road In Ward-38, Unit-9, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10887,Buildings,Completed,ND-TONDIARPET,38,820000,"Providing Water Supply, Electrical and Colour Washing to Amma Unavagam at Nehru Nagar Main Road In Ward-38, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/11030,Buildings,Completed,ND-TONDIARPET,38,838000,"Providing Portable Toilets 4 Nos For Gents with Water Tank 2000lt on Rental basis and maintenance for one year at Ilaya Street in Dn-40, Unit-10, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/11908,Buildings,Completed,ND-TONDIARPET,38,838000,"Providing Portable Toilets 4 Nos For Women with Water Tank 2000lt on Rental basis and maintenance for one year at Ilaya Street in Dn-40, Unit-10, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/13341,Storm Water Drain,Completed,ND-TONDIARPET,38,616000,"Construction of 600mm dia Pipe Drain between Elaya Street and Railway track to Drain off the surplus Water from Elaya Street in Division - 38, Unit - 9, Zone - 4.",Own Sources,4,2016-17,2018-19 ND/2016-17/13616,Buildings,Completed,ND-TONDIARPET,38,660000,"Improvements to Chennai Primary Health Centre at Annai Sandhya Nagar 1st Street in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/13617,Buildings,Completed,ND-TONDIARPET,38,884000,"Providing additional urinals and covering the RCC Roof slab and improvements to existing Toilet Block at CPS & CHSS Patel Nagar in Div-38, Unit-09, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/13618,Buildings,Completed,ND-TONDIARPET,38,998000,"Raising the Compound wall and Improvements to Play Area and Class Room at CPS & CHSS at Patel Nagar 4th Street in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/13619,Buildings,Completed,ND-TONDIARPET,38,163000,"Construction of Plat Form for E-Toilet at Vaidhyanathan Street in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/13769,Storm Water Drain,Completed,ND-TONDIARPET,38,840000,"Repairs, Improvements and Desilting to Existing Storm Water Drain at Nethaji Nagar 3rd and 4th Street, Lube Plant Road, Anna Street and Rajiv Gandhi Nagar Main Road in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/14097,Buildings,Completed,ND-TONDIARPET,38,13300,"Repairs and Maintenance to PC at Parameswari Nagar in Dn-38, Unit-9, Zone-04",Own Sources,4,2016-17,2017-18 ND/2016-17/15335,Road Cut,Completed,ND-TONDIARPET,38,1236000,"Restoration of roadcut made by TANTRANSCO at Nehru Nagar 12th Street in Dn ? 38, Unit ? 10, Zone ? IV",Deposit Works,4,2016-17,2017-18 ND/2016-17/1593,Roads,Completed,ND-TONDIARPET,38,772000,"Colour Washing at Vaidhyanathan bridge and Ennore high road Foot Path in Dn.38,Unit-9,Zone.4",Own Sources,4,2016-17,2016-17 ND/2016-17/16015,Parks,Completed,ND-TONDIARPET,38,546000,"Repairs and Improvements to the Park at Patel Nagar 4th Street affected due to Vardah Cyclone during December 2016 in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16035,Parks,Completed,ND-TONDIARPET,38,439000,"Repairs to Electrical Wiring and Fittings to the Park at Patel Nagar 4th Street affected due to Vardah Cyclone during December 2016 in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16185,Buildings,Completed,ND-TONDIARPET,38,17100,"Repairs to AC Sheet damaged due to Vardha cyclone for Kitchen Shed at CHSS , Patel Nagar 4th Street in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16556,Buildings,Completed,ND-TONDIARPET,38,125000,"Repairs to the Compound Wall damaged due to Vardah Cyclone at Division Office,Cherian Nagar in Dn-39, Unit-10, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/17497,Roads,Completed,ND-TONDIARPET,38,1560000,"Relaying of BT Road using Paver Finisher damaged due to Vardah Cyclone at Vaidyanathan 2nd Lane in Dn-38,Unit-9,Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/17498,Roads,Completed,ND-TONDIARPET,38,586000,"Relaying of BT Road using Paver Finisher damaged due to Vardah Cyclone at Vaidyanathan Service Lane in Dn-38,Unit-9,Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/17501,Roads,Completed,ND-TONDIARPET,38,899000,"Relaying of BT Road using Paver Finisher damaged due to Vardah Cyclone at Vaidyanathan 3rd Lane in Dn-38,Unit-9,Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/1801,Storm Water Drain,Completed,ND-TONDIARPET,38,82600,"Desilting of Storm water Drain at Patel Nagar Main Road in Dn.38, Unit - 9, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/1808,Storm Water Drain,Completed,ND-TONDIARPET,38,45000,"Desilting of Storm water Drain at Sastri Nagar Main Road in Dn.38, Unit - 9, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/3875,Roads,Completed,ND-TONDIARPET,38,947000,"Relaying of Cement Concrete Road by RMC M30 Concrete at Gandhi Nagar Main Road(Ward Councillor Fund 2016-17) in Dn-38, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/3890,Roads,Completed,ND-TONDIARPET,38,999900,"Relaying of Cement Concrete Road by RMC M30 Concrete at Karunanidhi Nagar 1st Street From Karunanidhi Nagar Market Street to Chainage 120m(Ward Councillor Fund 2016-17) in Dn-38,Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/3898,Roads,Completed,ND-TONDIARPET,38,978000,"Relaying of Cement Concrete Road by RMC M30 Concrete at Karunanidhi Nagar 1st Street From Chainage 120m to Sastri Nagar Main Road(Ward Councillor Fund 2016-17) in Dn-38, Unit-9, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4753,Footpath,Completed,ND-TONDIARPET,38,509000,"Maintainance of Ennore High road Footpath in Div-38, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4754,Storm Water Drain,Completed,ND-TONDIARPET,38,481000,"Maintainance of various storm water drains at Nehru Nagar, Nethaji Nagar, Karunanidhi Nagar in Div-38,Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4757,Buildings,Completed,ND-TONDIARPET,38,730000,"Mainainance of kitchen shed at Patel Nagar Childrens High School in Div-38, Unit-9, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4760,Buildings,Completed,ND-TONDIARPET,38,266000,"Maintainance of Amma Unavagam at New Vinobha Nagar in Div-38, Unit-9,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/8181,Roads,Completed,ND-TONDIARPET,38,999000,"Relaying of B.T.Road using Paver Finisher at Ellaya Street(From Jn of Vaidhyanathan Bridge to Ellaya Park Dn-40) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/8184,Roads,Completed,ND-TONDIARPET,38,986000,"Relaying of B.T.Road using Paver Finisher at Ellaya Street(From Ellaya Park Dn-40 to V.O.C.Nagar Main Street) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/8185,Roads,Completed,ND-TONDIARPET,38,980000,"Relaying of B.T.Road using Paver Finisher at Ellaya Street(From V.O.C.Nagar Main Street to V.O.C.Nagar 28th Cross Street) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/8186,Roads,Completed,ND-TONDIARPET,38,999000,"Relaying of B.T.Road using Paver Finisher at Ellaya Street(From V.O.C.Nagar 28th Cross Street to Thiravalluvar Quarters Entrance) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/8187,Roads,Completed,ND-TONDIARPET,38,955000,"Relaying of B.T.Road using Paver Finisher at Ellaya Street(From Thiruvalluvar Quarters Entrance to Prince Village Gate-1) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/8188,Roads,Completed,ND-TONDIARPET,38,989000,"Relaying of B.T.Road using Paver Finisher at Ellaya Street(From Prince Village Gate-1 to Jn of Kamaraj Salai) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/8189,Roads,Completed,ND-TONDIARPET,38,599000,"Relaying of B.T.Road using Paver Finisher at Ellaya Street(From Jn of Kamaraj Salai to Cross Road) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/9659,Roads,Completed,ND-TONDIARPET,38,906000,"Providing Center Median and Widening the Elaya Street from Rettai Kuzhai Street to Thilagar Nagar Ward-38, Unit-9, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9664,Roads,Completed,ND-TONDIARPET,38,974000,"Widening the Ellaya Street from Rettai Kuzhi Street to Mannappan Street (Western Side in Ward-38, Unit-9,. Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9665,Storm Water Drain,Completed,ND-TONDIARPET,38,998000,"Raising the Existing Storm Water Drain at Ennore High Road from Manali Salai to 120m in ward-38, Unit-9, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/9948,Roads,Completed,ND-TONDIARPET,38,430000,"Relaying the road with BM and BC using paver finishar at Durga Devi Nagar Main Road in DN-38,U-09,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/9958,Roads,Completed,ND-TONDIARPET,38,610000,"Relaying the road with BM and BC using paver finishar at Nehru Nagar 13th Street in DN-38,U-09,Z-04",Grants,4,2016-17,2017-18 ND/2016-17/9968,Roads,Completed,ND-TONDIARPET,38,1390000,"Relaying the road with BM and BC using paver finishar at Sundaram nagar 4th Main Road in DN-38,U-09,Z-04",Grants,4,2016-17,2016-17 D/2016-17/11554,Storm Water Drain,Completed,D-Storm Water Drains,39,945000,"SUPPLYING AND LAYING HDPE 300 MM DIA.PIPE AT AE KOIL STREET (FROM SUMP TO QQ SCHEME ROAD) IN DN.39, ZONE 4.",Own Sources,4,2016-17,2017-18 D/2016-17/4900,Storm Water Drain,Completed,D-Storm Water Drains,39,2278000,"Construction of RCC Sump at AE koil street, Dn.39, Zone 4",JNNURM,4,2016-17,2016-17 D/2016-17/7232,Storm Water Drain,Completed,D-Storm Water Drains,39,370000,Supplying and Laying HDPE 300m dia for interconnection from sump to DELIVERY HDPE PIPE at AE koil street in DN 39 Zone -4,Own Sources,4,2016-17,2017-18 L/2016-17/13759,Electrical,Completed,L-Electrical,39,811700,"Provision of 1 No. of 62.5 KVA Diesel Generator with AMF Control Panel for Storm Water Drain Pumping Station at A.E Koil Street in Dn:39, Zone IV",Own Sources,4,2016-17,2016-17 L/2016-17/13760,Electrical,Completed,L-Electrical,39,174000,"Supply and laying of 218 Mtrs of 3/12x 120 Sqmm PVC Alu.Cable for availing EB supply for Storm Water Drain Pumping Station at A.E Koil Street in Dn:39, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/15921,Electrical,Completed,L-Electrical,39,195800,"Replacement of 697 Mtrs of 2 x 16 Sqmm PVC Alu.Cable at A.E Koil St in Dn:39, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/16462,Electrical,Completed,L-Electrical,39,194500,"Replacement of 583 Mtrs of 2 x 16 Sqmm PVC Alu.Cable at Nammiha Maestry Street in Dn:39, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/11462,Buildings,Completed,ND-TONDIARPET,39,980000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period at AE Koil Street in Dn - 39,Unit-10, Zone -4",Own Sources,4,2016-17,2018-19 ND/2016-17/11616,Buildings,Completed,ND-TONDIARPET,39,900000,"Improvement to various work in various street in Dn-39, Unit-10, Zone-04",Own Sources,4,2016-17,2018-19 ND/2016-17/11617,Storm Water Drain,Completed,ND-TONDIARPET,39,998000,"Repairs and Maintenance work to SWD and Roads at various Streets in Dn-39, Un-10, Zn-IV.",Own Sources,4,2016-17,2016-17 ND/2016-17/13252,Buildings,Completed,ND-TONDIARPET,39,760000,"PROVIDING ARRANGEMENTS FOR AMMA KUDI NEER CENTRE AT A.E.KOIL STRET IN DN-39,U-10,Z-O4",Own Sources,4,2016-17,2016-17 ND/2016-17/13263,Buildings,Completed,ND-TONDIARPET,39,877000,"PROVIDING ROOFING ARRANGEMENTS FOR AMMA KUDI NEER CENTRE AT A.E.KOIL STRET IN DN-39,U-10,Z-O4",Own Sources,4,2016-17,2016-17 ND/2016-17/13472,Roads,Completed,ND-TONDIARPET,39,324000,"Relaying of B.T Road at Vanniar Street in Dn-39, Un-10, Zn-IV",Own Sources,4,2016-17,2016-17 ND/2016-17/14118,Buildings,Completed,ND-TONDIARPET,39,48500,"Repairs and maintenance work to P.C located at S.N Sheety Street in Dn-39, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/14913,Buildings,Completed,ND-TONDIARPET,39,550000,"Improvement works to CHS & CPS, CMS at T.H Road in div-39,un-10,Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/14922,Buildings,Completed,ND-TONDIARPET,39,380000,"improvements to C.H.S & C.P.S at New market form in div-39,un-10,zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/14923,Buildings,Completed,ND-TONDIARPET,39,490000,"Improvement works to Chennai urdu Primary School & C.H.S, C.P.S at CPT colony colony in div-39,un-10,zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/14928,Buildings,Completed,ND-TONDIARPET,39,127000,"Front Elevation Work in Gasifier at Hindu Burial Ground DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16517,Roads,Completed,ND-TONDIARPET,39,143000,"Providing Street Name Board at Namaya Street,Irusappa Steet, A.A.Scheme Road damaged due to Vardah Cyclone in Dn-39, Unit-10, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16528,Buildings,Completed,ND-TONDIARPET,39,420000,"Repairs to the Compound Wall damaged due to Vardah Cyclone at CHSS(East Side), No:731, T.H.Road in Dn-39, Unit-10, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16560,Footpath,Completed,ND-TONDIARPET,39,739000,"Repairs to Foot Path at T.H.Road near Cross Road in Dn-39, Unit-10, Zone-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16621,Buildings,Completed,ND-TONDIARPET,39,58700,"Repairs to Metal Sheet at Amma Kudineer Damaged due to Vardah Cyclone at A.E.Koil Street in Dn-39, Unit-10, Zone-04",Own Sources,4,2016-17,2017-18 ND/2016-17/3994,Roads,Completed,ND-TONDIARPET,39,952000,"Improvement to Center median and Footpath at S.N chetty Street, T.H road, Cross road in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/3996,Buildings,Completed,ND-TONDIARPET,39,792000,"Improvement to Toilet in Ground Floor, First Floor and Second Floor in Annuxere Building of CHSS at T.H road in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4000,Buildings,Completed,ND-TONDIARPET,39,723000,"Improvement to Toilet in Ground Floor and Second Floor in Corporation High School at Cherian Nagar in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4003,Roads,Completed,ND-TONDIARPET,39,995000,"Restoration of Road Cut made by TANGEDCO at Irussappan Main Street and Irussappan 1st Street in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4004,Roads,Completed,ND-TONDIARPET,39,832000,"Restoration of Road Cut made by TANGEDCO at A.E Koil Street Reach 1 in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4005,Roads,Completed,ND-TONDIARPET,39,864000,"Restoration of Road Cut made by TANGEDCO at S.N Cheety Street and Kannu Street in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4028,Roads,Completed,ND-TONDIARPET,39,998000,"Providing street Reflective Name board at Various Location in Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4035,Roads,Completed,ND-TONDIARPET,39,996000,"Providing Speed Breaker and Patch Work at Various Street in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4038,Storm Water Drain,Completed,ND-TONDIARPET,39,450000,"Desilting the Storm water drain at T.H Road, A.E Koil street, Veera ragavan Stret Kannu Pilla street and North Terminus road in Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4039,Roads,Completed,ND-TONDIARPET,39,450000,"Desilting the Storm water drain at Veeraragavan road, Avoor Muthiah Street,Market form 1st street, Market form 5th street, Market form 8th street, Cherain nagar main Road, Venkatesan ali Street Kannu Street, Theyagi permual Street, Washer Varadappa Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4040,Buildings,Completed,ND-TONDIARPET,39,679000,"Providing Staff Toilet in CHSS at T.H road in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4313,Roads,Completed,ND-TONDIARPET,39,893000,"Restoration of Road Cut made by TANGEDCO at A.E Koil Street Reach 2 in ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4406,Storm Water Drain,Completed,ND-TONDIARPET,39,800000,"Desilting the Storm water drain at Buchammal Street, Market forum 8th street, Poondi Thangammal Street, Cherian Nagar Main street, Market forum 4th street in Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/4407,Storm Water Drain,Completed,ND-TONDIARPET,39,400000,"Desilting the Storm water drain at Buchammal Street, Avoor Muthaiah Street Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/5960,Roads,Completed,ND-TONDIARPET,39,997000,"Laying Cement Concetre Road at T.H 1st Street in Ward-39, Unit--10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/5963,Roads,Completed,ND-TONDIARPET,39,998000,"Laying Cement Concetre Road at T.H 1st Cross Lane in Ward-39, Unit--10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/7013,Roads,Completed,ND-TONDIARPET,39,986000,"Improvement to Footpath at T.H road and Cross road in Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9089,Roads,Completed,ND-TONDIARPET,39,990000,"Providing rain water harvesting at Cherian Nagar, T.H Road, Dhanapal Nagar, Nammaiya Mastiry Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/9090,Roads,Completed,ND-TONDIARPET,39,987000,"Providing rain water harvesting at Poondi Thangammal Street, Nagooran thottam, Washer Varadappa Street in Ward-39, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9623,Roads,Completed,ND-TONDIARPET,39,989000,"Providing Galvanized Metal Sheet for barricading at (Linkiln) Canal Service road (Western Side) In ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9627,Roads,Completed,ND-TONDIARPET,39,980000,"Providing Galvanized Metal Sheet for barricading at (Linkiln) Canal Service road (Eastern Side) Ch 0 to 200 m In ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 L/2016-17/11841,Electrical,Completed,L-Electrical,40,4089700,"Estimate for conversion of 9 Nos of 20Mtr High Mast with 7 Nos of 210 to 230 Watts and 1 Nos of 16Mtr High Mast with 6 Nos of 160W to 200W LED FL fitting in Dn:38,39,40,41,43 and 47,Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/10001,Roads,Completed,ND-TONDIARPET,40,680000,"Relaying Of C.C Road at V.o.c nagar 19th link street in Div-40, Un-10, Zn-04.",Grants,4,2016-17,2016-17 ND/2016-17/10006,Roads,Completed,ND-TONDIARPET,40,540000,"Relaying of C.C Road at V.o.c nagar 1st link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10007,Roads,Completed,ND-TONDIARPET,40,180000,"Relaying of C.C Road at V.o.c nagar 20th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10011,Roads,Completed,ND-TONDIARPET,40,500000,"Relaying the road with BM and BC using paver finishar atSeniamman Koil 1si Street in DN-40,U-10,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/10016,Roads,Completed,ND-TONDIARPET,40,700000,"Relaying the road with BM and BC using paver finishar at TH Road 5thLane (From Corporation Colony 2nd Street to Seniamman Koil Street) in DN-40,U-10,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/10022,Roads,Completed,ND-TONDIARPET,40,189000,"Relaying the road with BM and BC using paver finishar at Thiruvalluvar Nagar Q Street in DN-40,U-10,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/10028,Roads,Completed,ND-TONDIARPET,40,298000,"Relaying of C.C Road at V.o.c nagar 21th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10029,Roads,Completed,ND-TONDIARPET,40,290000,"Relaying of C.C Road at V.o.c nagar 22th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10031,Roads,Completed,ND-TONDIARPET,40,405000,"Relaying of C.C Road at V.o.c nagar 23th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10122,Roads,Completed,ND-TONDIARPET,40,286000,"Relaying of C.C Road in V.o.c nagar 24th link street in Div-40, Un-10, Zn-04.",Grants,4,2016-17,2016-17 ND/2016-17/10124,Roads,Completed,ND-TONDIARPET,40,286000,"Relaying of C.C Road V.o.c nagar 25th link street in div-40, Un-10, Zn-04.",Grants,4,2016-17,2016-17 ND/2016-17/10126,Roads,Completed,ND-TONDIARPET,40,416000,"Relaying of C.C Road in Sivan Nagar 2nd Cross Street in Div-40, Un-10,Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10128,Roads,Completed,ND-TONDIARPET,40,145000,"Relaying of C.C Road at V.o.c nagar 29th link street in Div-40, Un-10,Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10129,Roads,Completed,ND-TONDIARPET,40,140000,"Relaying of C.C Road at V.o.c nagar 2nd link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10131,Roads,Completed,ND-TONDIARPET,40,495000,"Relaying of C.C Road at V.o.c nagar 30th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10132,Roads,Completed,ND-TONDIARPET,40,140000,"Relaying of C.C road at V.o.c nagar 4th link street in Div-40,Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10135,Roads,Completed,ND-TONDIARPET,40,232000,"Relaying of C.C Road at V.o.c nagar 8th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/10139,Roads,Completed,ND-TONDIARPET,40,480000,"Relaying of C.C Road at Sivan Nagar Cross Street in Div-40,Un-10,Zn-04.",Grants,4,2016-17,2016-17 ND/2016-17/10140,Roads,Completed,ND-TONDIARPET,40,790000,"Relaying of C.C Road at Sivan Nagar 2nd Street in Div-40,Un-10,Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/11265,Playfields,Completed,ND-TONDIARPET,40,980000,"Improvements to comopound wall at childrens ply field at eerai thottam in div-40,unit-10,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11267,Playfields,Completed,P-Parks and Playfields,40,970000,"Improvments to pathway and providing play apparatus to childrens play field at keerai thottam in div-40,unit-10,zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/11276,Playfields,Completed,P-Parks and Playfields,40,990000,"Providing water supply arrangements and electrical arrangements to childrens play field at keerai thottam in div-40,unit-10,zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/11585,Buildings,Completed,ND-TONDIARPET,40,997000,"Constructionf AMMA UNAVAGAM(phase 2) at keerai thottam in div-40,unit-10,zone4",Own Sources,4,2016-17,2016-17 ND/2016-17/11586,Buildings,Completed,ND-TONDIARPET,40,998000,"Roofing arrangements to AMMA UNAVAGAM(phase 2) at keerai thottam 2nd street in div-40 ,unit-10,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11587,Buildings,Completed,ND-TONDIARPET,40,971000,"Electrical arrangements and water supply arrangements tiles work for AMMA UNAVAGAM(phase2)at keerai thottam 2nd street in div-40 unit-10 ,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11588,Buildings,Completed,ND-TONDIARPET,40,995000,"Construction of multipurpose hall at keerai thottam in div-40,unit-10,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11871,Buildings,Completed,ND-TONDIARPET,40,995000,"Improvements works to Samudhaya sevai maiyam at keerai thottam2nd street in div-40,unit-10,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11904,Roads,Completed,ND-TONDIARPET,40,992000,"Raising the level to avoid water stagnation in rear side of Slum Tenements Block, 30 & 33 VOC Nagar in Div-40, Unit-10, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/13065,Roads,Completed,ND-TONDIARPET,40,191000,"IMPROVEMENTS TO EXISTING CC ROAD AT THIRUVALLUVAR KUDIYIRUPPU IN DN-40,U-10,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/13066,Roads,Completed,ND-TONDIARPET,40,319000,"IMPROVEMENTS TO WATER LOGGING AREAS AT JEEVA NAGAR MAIN ROAD IN DN-40,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/13068,Roads,Completed,ND-TONDIARPET,40,610000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS AT T.H ROAD,RAMA ARANGANNAL MAIN STREET,SENIAMMAN KOIL STREET AND OTHER ROADS IN DN-40,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/13071,Roads,Completed,ND-TONDIARPET,40,545000,"IMPROVEMENTS TO WATER LOGGING AREAS AT WESTERN SIDE OF AA SCHEME ROAD IN DN-40,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/13208,Roads,Completed,ND-TONDIARPET,40,159500,"Restoration of roadcut made by CMWSSB at Thiruvalluvar Nagar Quarters 'O' Street in Dn ? 40, Unit ? 10, Zone ? IV(From Elaya street jn. to O street end)",Own Sources,4,2016-17,2016-17 ND/2016-17/14087,Buildings,Completed,ND-TONDIARPET,40,74000,"Repairs and Maintenance work to PC at Ammaniammal Thottam in Dn-40, Unit-10, Zone-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/14092,Buildings,Completed,ND-TONDIARPET,40,23300,"Repairs and Maintenance work to PC at Jeeva Nagar in Dn-40, Unit-10, Zone-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/14103,Buildings,Completed,ND-TONDIARPET,40,42500,"Repairs and Maintenance work to PC at A.E. Koil Street(Keerai Thottam) in Dn-40, Unit-10, Zone-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/14416,Buildings,Completed,ND-TONDIARPET,40,518000,"Improvement to the School Building at Kamaraj Salai CMS in DN-40,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14576,Buildings,Completed,ND-TONDIARPET,40,49000,"Improvement to the School Building at THIRUVALLUVAR NAGAR CPS in DN-40,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/15805,Parks,Completed,ND-TONDIARPET,40,124000,"MAINTENANCE OF PARK (BRINDAVANAM) AT CROSS ROAD IN DN-40,UNIT-10,ZONE-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/15806,Parks,Completed,ND-TONDIARPET,40,509000,"MAINTENANCE OF THANTHAI PERIYAR PARK AT AE KOIL STREET IN DN-40,UNIT-10,ZONE-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/16115,Parks,Completed,ND-TONDIARPET,40,173000,"Repair and improvement of park due to vardha cyclone in Thiruvalluvar nagar park in Dn-40, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16118,Parks,Completed,ND-TONDIARPET,40,129000,"Repair and improvement of park due to vardha cyclone in Thiruvalluvar nagar Children?s park in Dn-40, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16119,Parks,Completed,ND-TONDIARPET,40,344000,"Repair and improvement of park due to vardha cyclone AT Elaya park in Dn-40, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16192,Parks,Completed,ND-TONDIARPET,40,56600,"Repair and improvement of park due to vardha cyclone at Cross Road (Brindhavan Park) in Dn-40, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16199,Parks,Completed,ND-TONDIARPET,40,491000,"Repair to Compound wall due to vardha cyclone at Cross Road(Periyar Park) in Dn-40, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16208,Parks,Completed,ND-TONDIARPET,40,270000,"Repair and improvement of park due to vardha cyclone at Cross Road (Periyar Park) in Dn-40, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16245,Electrical,Completed,ND-TONDIARPET,40,101000,"Supply and erection of 4 Nos of 2 Mtr Lamp Post with Arch bracket with 20W LED Fitting at Cross Road, OSR Land Park and Supply and fixing of 4 Nos. of 20W LED Fitting at Thiruvalluvar Nagar Park in Dn:40, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16250,Electrical,Completed,ND-TONDIARPET,40,245000,"Supply and erection of 12 Nos. of 2 Mtr Lamp Post with Arch bracket and 20W LED Fitting at Ellaya Street Park in Dn:40, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16259,Electrical,Completed,ND-TONDIARPET,40,366500,"Supply and erection of 18 Nos.of 2 Mtr Lamp Post with Arch bracket and 20W LED Fitting at Periayar Park at A.E Koil Street in Dn:40, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16458,Buildings,Completed,ND-TONDIARPET,40,112000,"Repair and Improvement works to CPS Kamaraj Salai due to vardha cyclone in Dn-40,Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/18453,Parks,Completed,ND-TONDIARPET,40,732000,"Annual Maintenance Of Park at Elaya Street Park For one Year in Dn-40,Unit-10,Zone-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/18454,Parks,Completed,ND-TONDIARPET,40,471000,"Annual Maintenance Of Park at Thiruvalluvar Nagar Park For one Year in Dn-40,Unit-10,Zone-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/2040,Roads,Completed,ND-TONDIARPET,40,998000,"Supplying and laying wetmix forinside the campus of gpwd quarters at kamarajar salai in div-40,unit-10,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/3603,Footpath,Completed,ND-TONDIARPET,40,181000,"PAINTING BLACK AND WHITE TO THE FOOTPATH KERB AND REPAIRS TO FOOTPATH AT KAMARAJAR SALAI AND A.A.SCHEME ROAD IN DN-40, UNIT-10, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/4389,Storm Water Drain,Completed,ND-TONDIARPET,40,599000,"PROVIDING RAINWATER HARVESTING ARRANGEMENTS IN JEEVA NAGAR 1ST AND 2ND STREETS IN DN-40,U-10,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4390,Storm Water Drain,Completed,ND-TONDIARPET,40,599000,"PROVIDING RAIN WATER HARVESTING ARRANGEMENTS AT JEEVA NAGAR 3RD AND 4TH STREET IN DN-40,U-10,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/6663,Roads,Completed,ND-TONDIARPET,40,273000,"Restoration of Road Cut made by TANGEDCO at Chelliamman koil street near thiruvalluvar nagar, Thiruvalluvar nagar 1st street in ward-40, unit-10, zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6671,Roads,Completed,ND-TONDIARPET,40,670000,"Restoration of Road Cut made by CMWSSB at Corporation colony main road in ward-40, unit-10, zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6672,Roads,Completed,ND-TONDIARPET,40,666000,"Restoration of Road Cut made by CMWSSB at Corporation Colony main road T.H road 5th lane in ward-40, unit-10, zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6673,Roads,Completed,ND-TONDIARPET,40,716000,"Restoration of Road Cut made by CMWSSB at Seniamman koil street to New vaidhyanatgan street in ward-40, unit-10, zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6678,Roads,Completed,ND-TONDIARPET,40,952000,"Restoration of Road Cut made by TANGEDCO at A.E Koil street in ward-40, unit-10, zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/6793,Roads,Completed,ND-TONDIARPET,40,998000,"IMPROVEMENT TO FOOTPATH AND PROVIDING G I SHEET DURING CM VISIT AT ILAYA MUDALI STREET (FROM GROSS ROAD TO KAMRAJ SALAI) IN DN-40,UNIT-10,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/8037,Storm Water Drain,Completed,ND-TONDIARPET,40,450000,"DESILTING AND OTHER IMPROVEMENT WORKS TO EXT.SWD AT CHELLIAMMAN KOIL ST., IN DN-40,U-10,Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/8252,Electrical,Completed,ND-TONDIARPET,40,252900,"Provision of 3 Nos. of 1.5 Ton Air Conditioner Unit at Health department in Community Center Building at T.H Road, Dn:40, Zone IV",Own Sources,4,2016-17,2019-20 ND/2016-17/8392,Roads,Completed,ND-TONDIARPET,40,997000,"Improvements to footpath and concrete patches at Cross Road in Dn-40, Unit-10, Zone IV",Own Sources,4,2016-17,2016-17 ND/2016-17/8394,Roads,Completed,ND-TONDIARPET,40,860000,"Improvements to Care Taker Room & Providing Water Sypply, Drainage Arrangements to Ellaya Park in Div-40, Unit-10, Zone IV",Own Sources,4,2016-17,2016-17 ND/2016-17/8407,Roads,Completed,ND-TONDIARPET,40,973000,"Improvements to footpath and Providing Concrete Belmouth at Elaya Street in Dn-38, Unit-09, Zone - IV",Own Sources,4,2016-17,2016-17 ND/2016-17/9019,Storm Water Drain,Completed,ND-TONDIARPET,40,450000,"DESILTING AND OTHER IMPROVEMENT WORKS TO EXT. SWD AT CORPORATION COLONY,THIRUVALLUVAR NAGAR 2ND AND 6TH MAIN ROAD IN DN-40,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/9918,Roads,Completed,ND-TONDIARPET,40,930000,"Relaying of c.c Road at Seniamman Koil 5th Street in div-40, un-10, zn-04.",Grants,4,2016-17,2016-17 ND/2016-17/9919,Roads,Completed,ND-TONDIARPET,40,299000,"Relaying of C.C Road in V.o.c nagar 10th link street in Div-40, un-10, Zn-04.",Grants,4,2016-17,2016-17 ND/2016-17/9949,Roads,Completed,ND-TONDIARPET,40,610000,"Relaying of C.C Road at V.o.c nagar 13th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/9951,Roads,Completed,ND-TONDIARPET,40,550000,"Relaying of C.C Road at V.o.c nagar 14th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/9953,Roads,Completed,ND-TONDIARPET,40,206000,"Relaying of C.C Road at V.o.c nagar 15th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/9955,Roads,Completed,ND-TONDIARPET,40,330000,"Relaying of C.C Road at V.o.c nagar 16th link street in Div-40, Un-10, Zn-04",Grants,4,2016-17,2016-17 ND/2016-17/9964,Roads,Completed,ND-TONDIARPET,40,330000,"Relaying of C.C Road at V.o.c nagar 17th link street in Div-40 Un-10, Zn-04",Grants,4,2016-17,2016-17 P/2016-17/19677,Parks,Completed,P-Parks and Playfields,40,3827000,"Formation of New Park at Tsunami Quarters 'B' Block, A.A Scheme Road, Tondiarpet in Dn-40, Unit-10, Zone-04.",Grants,4,2016-17,2018-19 P/2016-17/19678,Parks,Completed,P-Parks and Playfields,40,2840000,"Formation of New Park at Tsunami Quarters 'M' Block, A.A Scheme Road, Tondiarpet in Dn-40, Unit-10, Zone-4.",Grants,4,2016-17,2018-19 BR/2016-17/10434,Roads,Completed,BR-Bus Route Roads,41,5750000,"Strengthening and relayin the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Manali Salai (Part II) in division -41 , zone -4.",Grants,4,2016-17,2017-18 L/2016-17/11785,Electrical,Completed,L-Electrical,41,1444400,"Provision of 27 Nos of 6 Mtrs GI Lamp Post on Single Arch Bracket with 90W LED fitting at Lime kiln Road (Phase II Amma Varasandhai) in division 41,Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/15844,Electrical,Completed,L-Electrical,41,187200,"Painting a and numbering of Street lamp posts 6/7 Mtr and 9.2 Mtr at Various Location in Dn:41, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/16882,Electrical,Completed,L-Electrical,41,972000,"Provision of 8 Nos.of 8 Mtr Long Ocatagonal Mini Highmast Light with hexagonal lantern carriage with 3 Nos.of 70W -100W LED Flood light Fitting at Various Locations in Dn: 41, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/18121,Electrical,Completed,L-Electrical,41,637400,Estimate for removal and refixing of 153 No's street lamp posts affected due to VARDAH CYCLONE in Zone IV,Own Sources,4,2016-17,2016-17 L/2016-17/18204,Electrical,Completed,L-Electrical,41,198600,"Supply and fixing of 149 Nos of 1 mtr long G.I. Single Straight Bracket at Various Locations in Dn: 41,42 and 47, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/8559,Electrical,Completed,L-Electrical,41,1327400,"Provision of 25 Nos. of 6 Mtrs GI Lamp Post on Single Arch Bracket with 90W LED Fitting at Lime Kiln Road in Dn:41, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/11071,Electrical,Completed,ND-TONDIARPET,41,269200,"Provision of Lighting, Fan and Plug Point at Amma Vara Sanddhai in Lime Kiln Road in Dn 41,Zone IV",Own Sources,4,2016-17,2019-20 ND/2016-17/11460,Buildings,Completed,ND-TONDIARPET,41,980000,"Operation and Maintenacne of high Quality Treated Drinking water Plant (R.O-UV Filtration) of 2000 LIt - hour Capacity for 1 year Period in Div-41,Un-10, Zn-IV.",Own Sources,4,2016-17,2018-19 ND/2016-17/12772,Buildings,Completed,ND-TONDIARPET,41,884000,"Providing metal sheet for barricading (Westernside) @ lime kiln canal Service road (Amma Vara santhai) at Ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12775,Buildings,Completed,ND-TONDIARPET,41,717000,"Providing metal sheet for barricading (Easternside) @ lime kiln canal Service road (Amma Vara santhai) at Ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12776,Buildings,Completed,ND-TONDIARPET,41,998000,"Improvement the Canal retaining wall and construction of compund wall at Amma vara Santhai in ward-41, unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12779,Roads,Completed,ND-TONDIARPET,41,998000,"Widening the canal Service road and plantation for Amma vara Santhai in Ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12780,Roads,Completed,ND-TONDIARPET,41,925000,"Supply and fixing Name board for Amma vara Santhai at Lime kiln Service road in ward-41, unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12945,Buildings,Completed,ND-TONDIARPET,41,998000,"Fencing the vacant land and construction of composed yard at lime kiln road in div-41, un-10, zone-IV.",Own Sources,4,2016-17,2018-19 ND/2016-17/13262,Buildings,Completed,ND-TONDIARPET,41,894000,"Construction of sump and Formation of base for Amma Kudineer at J.J Nagr A1 Street, in Dn-41, Un-10, Zn-IV",Own Sources,4,2016-17,2016-17 ND/2016-17/13264,Buildings,Completed,ND-TONDIARPET,41,814000,"Providing Metal Sheet Roof Covering for Amma Kudineer at J.J Nagar A1 Street in Dn-41, Un-10, Zn-IV",Own Sources,4,2016-17,2016-17 ND/2016-17/13372,Roads,Completed,ND-TONDIARPET,41,846000,"Formation(Sub-Grade) of B-Canal Service Road From Chainage 300 to 375m in Dn-41, Unit-10, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/13373,Roads,Completed,ND-TONDIARPET,41,801000,"Formation(Sub-Grade) of B-Canal Service Road From Chainage 375 to 450m in Dn-41, Unit-10, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/13374,Roads,Completed,ND-TONDIARPET,41,636000,"Formation(Sub-Grade) of B-Canal Service Road From Chainage 450 to 510m in Dn-41, Unit-10, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/13375,Roads,Completed,ND-TONDIARPET,41,432000,"Formation(Sub-Grade) of B-Canal Service Road From Chainage 510 to 571m in Dn-41, Unit-10, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/14109,Buildings,Completed,ND-TONDIARPET,41,27300,"Repairs and maintenance work to P.C located at Anna nagar in Dn-41, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/14113,Buildings,Completed,ND-TONDIARPET,41,30700,"Repairs and maintenance work to P.C located at Amman Koil Street in Dn-41, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/14114,Buildings,Completed,ND-TONDIARPET,41,79000,"Repairs and maintenance work to P.C located at J.J Nagar in Dn-41, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/14307,Buildings,Completed,ND-TONDIARPET,41,375000,"Improvement work to Chennai Primary School Located at Anna nagar in Dn-41, Un-10,Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/14310,Buildings,Completed,ND-TONDIARPET,41,75000,"Improvement work to Chennai Primary School Located at J.J nagar in Dn-41, Un-10,Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/14544,Buildings,Completed,ND-TONDIARPET,41,630000,"Improvement works and Construction of kitchen shed in Chennai Primary School Located at M.G.R Nagar 3rd Street in Div-41, Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/14546,Buildings,Completed,ND-TONDIARPET,41,900000,"Improvements to various works in various streetin Div-41, Un-10, Zn-IV.",Own Sources,4,2016-17,2018-19 ND/2016-17/15336,Road Cut,Completed,ND-TONDIARPET,41,428000,"Restoration of roadcut made by TANTRANSCO at Kannagi nagar 5th street in Dn ? 41, Unit ? 10, Zone ? IV",Deposit Works,4,2016-17,2017-18 ND/2016-17/15339,Road Cut,Completed,ND-TONDIARPET,41,729000,"Restoration of roadcut made by TANTRANSCO at J.J Nagar A1Street in Dn ? 41, Unit ? 10, Zone ? IV",Deposit Works,4,2016-17,2016-17 ND/2016-17/15341,Road Cut,Completed,ND-TONDIARPET,41,938000,"Restoration of Roadcut made by TANTRANSCO at J.J Nagar A2 Street in Dn-41, Unit?10, Zone ? IV",Deposit Works,4,2016-17,2016-17 ND/2016-17/15343,Road Cut,Completed,ND-TONDIARPET,41,1356000,"Restoration of roadcut made by TANTRANSCO at Lime klin road (Amma Varachanthai) (From Manali Salai to Chainage- 260m) in Dn?41, Unit?10, Zone?IV",Deposit Works,4,2016-17,2016-17 ND/2016-17/15346,Road Cut,Completed,ND-TONDIARPET,41,1414000,"Restoration of roadcut made by TANTRANSCO at Lime klin road (Amma Varachanthai)(From Chainage- 260m to 530m) in Dn ? 41, Unit ? 10, Zone ? IV",Deposit Works,4,2016-17,2016-17 ND/2016-17/15756,Storm Water Drain,Completed,ND-TONDIARPET,41,996000,"Repairs and Maintenance work to SWD and Roads at various Streets in Dn-41,Un-10,Zn-IV.",Own Sources,4,2016-17,2016-17 ND/2016-17/15781,Buildings,Completed,ND-TONDIARPET,41,890000,"Construction of Rest Room for Conservancy workers and improvements to word office (Dn-47) at J.J nagar (Near Amma Kudineer) in Dn-41, Un-10, Zn-IV",Own Sources,4,2016-17,2018-19 ND/2016-17/16448,Buildings,Completed,ND-TONDIARPET,41,36700,"Improvements to amma unagavam due to vardha cyclone at J.JNagar in Dn-41,Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16453,Buildings,Completed,ND-TONDIARPET,41,18100,"Repair and Improvement works to CPS anna nagar due to vardha cyclone in Dn-41,Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16455,Buildings,Completed,ND-TONDIARPET,41,27000,"Repair and Improvement works to P.C at anna nagar due to vardha cyclone in Dn-41,Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/1677,Storm Water Drain,Completed,ND-TONDIARPET,41,860000,"DESILTING AND REPAIR TO EXE .SWD AT VAITHIYANATHAN SERVICE ROAD IN DN-41 ,UNIT-10 AND ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/1731,Storm Water Drain,Completed,ND-TONDIARPET,41,22500,"Desilting And Repairs to Existing SWD at Amman Koil Street In Div-41,Un-10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1732,Storm Water Drain,Completed,ND-TONDIARPET,41,174000,"Desilting And Repairs to Existing SWD at Sivaji Nagar Main Street In Div-41,Un-10,Zn- 04",Own Sources,4,2016-17,2016-17 ND/2016-17/1738,Storm Water Drain,Completed,ND-TONDIARPET,41,178000,"Desilting And Repairs to Existing SWD at Kumaran Nagar 1st Street In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1742,Storm Water Drain,Completed,ND-TONDIARPET,41,44000,"Desilting And Repairs to Existing SWD at Manali Salai In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1743,Storm Water Drain,Completed,ND-TONDIARPET,41,360000,"Desilting And Repairs to Existing SWD at Ennore High Road In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1745,Storm Water Drain,Completed,ND-TONDIARPET,41,870000,"Desilting And Repairs to Existing SWD at Periyar salai t In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1749,Storm Water Drain,Completed,ND-TONDIARPET,41,350000,"Desilting And Repairs to Existing SWD at Navalar Street In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/17508,Roads,Completed,ND-TONDIARPET,41,532000,"Relaying of Cyclone damaged B.T Road at Cornation Nagar slum tenements Road in Dn-41, Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/17509,Roads,Completed,ND-TONDIARPET,41,532000,"Relaying of Cyclone damaged B.T Road at Parthasarathy Street in Dn-41, Un-10,Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/17510,Roads,Completed,ND-TONDIARPET,41,1410000,"Relaying of Cyclone damaged B.T Road at Periyar Salai (Anna Nagar) in Dn-41,Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/17511,Roads,Completed,ND-TONDIARPET,41,399000,"Relaying of Cyclone damaged B.T Road at Old Pumping Station Road in Dn-41,Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/17512,Roads,Completed,ND-TONDIARPET,41,470000,"Relaying of Cyclone damaged B.T Road at Gandhi Street in Dn-41,Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/17513,Roads,Completed,ND-TONDIARPET,41,532000,"Relaying of Cyclone damaged B.T Road at Marimuthu Street in Dn-41,Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/17514,Roads,Completed,ND-TONDIARPET,41,532000,"Relaying of Cyclone damaged B.T Road at Kasthuri bai Street in Dn-41,Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/17515,Roads,Completed,ND-TONDIARPET,41,532000,"Relaying of Cyclone damaged B.T Road at Ramasamy Street in Dn-41,Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/1760,Storm Water Drain,Completed,ND-TONDIARPET,41,350000,"Desilting And Repairs to Existing SWD at Thiruvalluvar Nagar 4th Street In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1762,Storm Water Drain,Completed,ND-TONDIARPET,41,174000,"Desilting And Repairs to Existing SWD at Govindha Samy Nagar ( Bharathi Dasan Street ) Street In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1764,Storm Water Drain,Completed,ND-TONDIARPET,41,860000,"Desilting And Repairs to Existing SWD at Thiruvalluvar Street (Periyar Nagar) Street In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1766,Storm Water Drain,Completed,ND-TONDIARPET,41,550000,"Desilting And Repairs to Existing SWD at Cornation Nagar 1-4th street In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/1769,Storm Water Drain,Completed,ND-TONDIARPET,41,91000,"Desilting And Repairs to Existing SWD at Kannagi Nagar 5th Street In Div-41,Un- 10,Zn-04",Own Sources,4,2016-17,2016-17 ND/2016-17/19188,Storm Water Drain,Completed,ND-TONDIARPET,41,996000,"Repairs and Maintenance work to SWD and Roads at various Streets in Dn-40,Un-10,Zn-IV.",Own Sources,4,2016-17,2016-17 ND/2016-17/19189,Storm Water Drain,Completed,ND-TONDIARPET,41,996000,"Repairs and Maintenance work to SWD and Roads at various Streets in Dn-42,Un-10,Zn-IV.",Own Sources,4,2016-17,2016-17 ND/2016-17/19190,Storm Water Drain,Completed,ND-TONDIARPET,41,996000,"Repairs and Maintenance work to SWD and Roads at various Streets in Dn-43,Un-10,Zn-IV.",Own Sources,4,2016-17,2016-17 ND/2016-17/19462,Roads,Completed,ND-TONDIARPET,41,967000,"Providing Speed breaker at Various Street (Kumaran Nagar, Aziz Nagar, Cornation Nagar ) in Ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/3323,Roads,Completed,ND-TONDIARPET,41,610000,"Attending concrete patch work at various street and painting footpath, centre median at Ennure high road in dn 41",Own Sources,4,2016-17,2016-17 ND/2016-17/3953,Roads,Completed,ND-TONDIARPET,41,998000,"IMPROVEMENTS TO SLUM TENNAMANTS ROAD AT CORNATION NAGAR BLOCK-1 UNDER WARD COUNCILLORS SCHME 2016-17 IN DN-41, UNIT-10 AND ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/3954,Roads,Completed,ND-TONDIARPET,41,986000,"MPROVEMENTS TO SLUM TENNAMANTS ROAD AT CORNATION NAGAR BLOCK-2 UNDER WARD COUNCILLORS SCHME 2016-17 IN DN-41, UNIT-10 AND ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/3955,Roads,Completed,ND-TONDIARPET,41,985000,"IMPROVEMENTS TO SLUM TENNAMANTS ROAD AT CORNATION NAGAR BLOCK-3 UNDER WARD COUNCILLORS SCHEME 2016-17 IN DN-41, UNIT-10 AND ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/8106,Buildings,Completed,ND-TONDIARPET,41,981000,"Additional Works to the Corporation School at Anna nagar school in Div-41, un-10, Zn-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/8109,Buildings,Completed,ND-TONDIARPET,41,970000,"Additional Works to the Corporation School at Cornation Nagar school in Div-41, un-10, Zn-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/9077,Buildings,Completed,ND-TONDIARPET,41,990000,"Construction of Additional Room in Ward office and forming road side park at J.J Nagar in Ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9294,Roads,Completed,ND-TONDIARPET,41,4890000,"Widening and Strengthening 'B'Canal Service Road from Jn of Manali Salai Chainage From 0-150 m ( Reach 1) in Dn-41, Unit-10, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/9394,Roads,Completed,ND-TONDIARPET,41,4900000,"Widening and Strengthening 'B'Canal Service Road from Jn of Manali Salai Chainage From 150-300 m ( Reach 2) in Dn-41, Unit-10, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/9401,Roads,Completed,ND-TONDIARPET,41,4944000,"Widening and Strengthening 'B'Canal Service Road from Jn of Manali Salai Chainage From 300-450 m ( Reach 3) in Dn-41, Unit-10, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9404,Roads,Completed,ND-TONDIARPET,41,4995000,"Widening and Strengthening 'B'Canal Service Road from Jn of Manali Salai Chainage From 450-600 m ( Reach 4) in Dn-41, Unit-10, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9621,Roads,Completed,ND-TONDIARPET,41,981000,"Providing Speed breaker at Various Street in Ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9639,Roads,Completed,ND-TONDIARPET,41,982000,"Providing Galvanized Metal Sheet for barricading at (Linkiln) Canal Service road (Eastern Side) Ch 201 to 400 m In ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9640,Roads,Completed,ND-TONDIARPET,41,940000,"Providing Galvanized Metal Sheet for barricading at (Linkiln) Canal Service road (Eastern Side) Ch 401 to 600 m In ward-41, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9642,Roads,Completed,ND-TONDIARPET,41,958000,"Relaying B.T Patches at Various Street in at Various Street in Ward-41, Unit-10, zone-5",Own Sources,4,2016-17,2016-17 B/2016-17/0211,Buildings,Completed,B-Buildings,42,2495000,"PROPOSED CONVERSION OF OLD B & C WARD BLOCKS INTO HOSTEL FOR ANM TRAINING STUDENTS IN CD HOSPITAL CAMPUS AT TONDIARPET IN DN-42, ZONEIV.",Own Sources,4,2016-17,2016-17 L/2016-17/11134,Electrical,Completed,L-Electrical,42,1694000,"Provision of 42 Nos of 6 Mtrs Street Lamp Post with Hop dip zinc galvanising with single straight bracket with 40 W LED fitting at Seniamman Housing Board,in Dn.42,Zone IV",Deposit Works,4,2016-17,2018-19 L/2016-17/15845,Electrical,Completed,L-Electrical,42,180700,"Painting and numbering of 6/7 Mtr and 9.2 Mtr MS Lamp post at Various Location in Dn42 & 48, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/16887,Electrical,Completed,L-Electrical,42,364600,"Provision of 3 Nos.of 8 Mtr Long Ocatagonal Mini Highmast Light with hexagonal lantern carriage with 3 Nos.of 70W -100W LED Flood light Fitting at Various Locations in Dn: 42 and 48, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/18138,Electrical,Completed,L-Electrical,42,862700,"Replacement of 2078 Mtrs of 2x16 Sqmm Cable at Appasamy main 1st to 5th Street K.G. Garden, Rathanasabathy Lane in Division -42, Zone-IV",Own Sources,4,2016-17,2017-18 L/2016-17/18139,Electrical,Completed,L-Electrical,42,440100,"Replacement of 1042 Mtrs of 2x16 Sqmm Cable at Arani Rangan street in Division -42, Zone-IV",Own Sources,4,2016-17,2018-19 ND/2016-17/10740,Roads,Completed,ND-TONDIARPET,42,982000,"Laying B.T Road at Rettai Kuzhai Street and Thilagar Nagar Service Road Reach 1 in ward-42, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10742,Roads,Completed,ND-TONDIARPET,42,994000,"Laying B.T Road at Rettai Kuzhai Street and Thilagar Nagar Service Road Reach 2 in ward-42, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11456,Buildings,Completed,ND-TONDIARPET,42,980000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period in Dn -42,Unit-10,Zone -04",Own Sources,4,2016-17,2018-19 ND/2016-17/11783,Buildings,Completed,ND-TONDIARPET,42,838000,"Providing Portable Toilet 4 Nos with Water Tank 2000Lt on Rental Basis and Maintenance for one year at T.H Road (Opp: Post Office) in Division - 42, Unit - 10, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/13249,Buildings,Completed,ND-TONDIARPET,42,950000,"PROVIDING ROOFING ARRANGEMENTS,ELECTRICAL,WATER SUPPLY AND DRAINAGE ARRANGEMENTS TO NEWLY CONSTRUCTED AMMA KUDI NEER CENTER AT THILAGAR NAGAR IN DN-42,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/13251,Buildings,Completed,ND-TONDIARPET,42,189000,"PROVIDING NEW NAME BOARDS FOR VARIOUS CORPORATION INSTITUTIONS IN DN-42,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/14126,Buildings,Completed,ND-TONDIARPET,42,54300,"Repairs and Maintenance work PC at Kailasam Street in Dn-42, Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/14129,Buildings,Completed,ND-TONDIARPET,42,78300,"Repairs and Maintenance work PC at Seniamman Koil Street in Dn-42, Un-10, Zn-IV.",Own Sources,4,2016-17,2017-18 ND/2016-17/14575,Buildings,Completed,ND-TONDIARPET,42,660000,"Construction Toilet Building 540 CGHSS (Buddha School) @ T.H Road in Division-42,Unit-10,Zone-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14793,Parks,Completed,ND-TONDIARPET,42,550000,"Improvements to Thiyagaraya Park@ T.H Road inn Dn-42,U-10,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/14805,Storm Water Drain,Completed,ND-TONDIARPET,42,310000,"Thilagar Nagar Slum (Kudusei paguthi) Strom Water Drain & Rain Harvesting Well in Dn-42,u-10,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/15671,Parks,Completed,ND-TONDIARPET,42,133000,"ANNUAL MAINTENANCE OF RETTAIKUZHI STREET PARK (1 Year) IN DN-42,U-10,Z-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/15672,Parks,Completed,ND-TONDIARPET,42,150000,"ANNUAL MAINTENANCE OF THIYAGARAYA PARK @ T.H.ROAD (1 YEAR) IN Dn-42,U-10,Z-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/15736,Buildings,Completed,ND-TONDIARPET,42,994000,Construction of compost yard and providing GI Sheet roofing at thilagar nagar in ward.42 unit.10 zone.4,Own Sources,4,2016-17,2018-19 ND/2016-17/16009,Parks,Completed,ND-TONDIARPET,42,875000,"Repairs and Improvements at Jeeva Park affected due to Vardah Cyclone during December 2016 in Dn-42, Unit-10, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/1602,Footpath,Completed,ND-TONDIARPET,42,640000,"IMPROVEMENTS TO FOOTPATH AND CENTER MEDIAN AT T.H ROAD IN DN-42,U-10,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/16230,Parks,Completed,ND-TONDIARPET,42,303500,"ESTIMATE for Replacement of 920 Mtr 2 x16 Sqmm Cable and replacement of 5 Nos.of 20W LED Fitting at Thiyagaraya Park,Jeeva Park and Rettaikuzhi Street Park in Dn-42,Unit-10,Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16277,Parks,Completed,ND-TONDIARPET,42,231000,"Repairs and Improvements at Thiyagaraya Park affected due to Vardah Cyclone during December 2016 in Dn-42,U-10,Z-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16293,Parks,Completed,ND-TONDIARPET,42,98000,"Repairs and Improvements at Rettaikuzhi Street Park affected due to Varadah Cyclone during December 2016 in Dn-42,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16449,Footpath,Completed,ND-TONDIARPET,42,160000,"Improvements to Footpath at Veera Kutty Street ,Rettaikuzhi Street ,T.H Service Road & T.H Road in Dn-42,u-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16482,Buildings,Completed,ND-TONDIARPET,42,350000,"Repairs Works in Unit Office -10 due to Vardha cyclone in Dn-42,u-10,Z-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16495,Buildings,Completed,ND-TONDIARPET,42,86200,"Repairs Works at Amma Kudineer & Amma Unavagam due to vardha Cyclone in Dn-42,u-10,Z-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/16738,Parks,Completed,ND-TONDIARPET,42,253000,"Repair of Roadside Park @ Rathinasapathy lane due to Vardha Cyclone @ Dn-42,u-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/2772,Storm Water Drain,Completed,ND-TONDIARPET,42,989000,"REPAIRS AND IMPROVEMENTS TO CHENNAI CORPORATION PRIMARY SCHOOL , OLD WARD OFFICE,PUBLIC CONVENIENCE AT SENIAMMAN KOIL STREET AND HEALTH CENTER, AD ELECTRICAL OFFICE , CHENNAI GILRS HIGHER SECONDARY SCHOOL AT T.H.ROAD IN DN-42, UNIT-10, ZONE-04",Own Sources,4,2016-17,2017-18 ND/2016-17/2779,Storm Water Drain,Completed,ND-TONDIARPET,42,900000,"Desilting of SWD@ M.C.M Garden 1st,2nd,3rd,Kothadaraman Street,Arani Rangan Street,Verakutty Street in Dn-42,U-10,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/2794,Storm Water Drain,Completed,ND-TONDIARPET,42,980000,"Desliting od SWD @Rettaikuzhi Street,Kailasam Street,Seniamman Koil Street,Rathinasabathy in Dn-42,U-10,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/4403,Roads,Completed,ND-TONDIARPET,42,999000,"RAISING THE LEVEL AND LAYING INTERLOCKING PAVER BLOCK TO VEERAKUTTY SLUM TENEMENTS LANE&MAYOR BASUDEV 1ST CROSS LANE&SENIAMMAN KOIL LANE IN DIV-42,UNIT-10,ZONE-4(WARD COUNCILLOR SCHEME)",Own Sources,4,2016-17,2016-17 ND/2016-17/8241,Buildings,Completed,ND-TONDIARPET,42,999000,"CONSTRUCTION OF AMMA UNAVAGAM PHASE-II AT THILAGAR NAGAR IN DN-42,U-10,Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/8282,Buildings,Completed,ND-TONDIARPET,42,992000,"PROVIDING FLOORING ARRANGEMENT,DOORS TO NEWLY CONSTRUCTED AMMA UNAVAGAM AT THILAGAR NAGAR IN DN-42,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/8288,Buildings,Completed,ND-TONDIARPET,42,998000,"PROVIDING ROOFING,ELECTRICAL,WATER SUPPLY AND DRAINAGE ARRANGEMENTS TO NEWLY CONSTRUCTED AMMA UNAVAGAM AT THILAGAR NAGAR IN DN-42,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/8418,Buildings,Completed,ND-TONDIARPET,42,937000,"Urgent Improvement necessary works to Zonal Office Building and providing name board for all Public convenience in Dn-42, Unit-10, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/8686,Roads,Completed,ND-TONDIARPET,42,876000,"IMPROVEMENTS TO FOOTPATH AND CENTER MEDIAN AT T.H ROAD IN DN-42,U-10,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/8691,Roads,Completed,ND-TONDIARPET,42,663000,"IMPROVEMENTS TO ROADSIDE PARKS AT T.H ROAD,SENIAMMAN KOIL STREET,JEEVA PARK AND BIN PLATFORMS IN DN-42,U-10,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/8872,Roads,Completed,ND-TONDIARPET,42,967000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermo Plastic Compound marking Road pavement markers and signage boards at West Krishnappa Thottam 1st,2nd and 3rd Street,Rathanasapathy Street,Rettaikuzhi Street,Mayar Basudev Street,Veera kutty Street,Appaswamy Thottam Main Street, Mayar Basudev 2nd Street etc..in Dn-42,U-10,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9161,Roads,Completed,ND-TONDIARPET,42,550000,"Relaying the Road at Verrakutty Street in Dn-42,U-10,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/9216,Roads,Completed,ND-TONDIARPET,42,400000,"Relaying the Road at Kothandaraman Lane Dn-42,U-10,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9229,Roads,Completed,ND-TONDIARPET,42,795000,"Relaying the Road at Kothandaraman Street in Dn-42,U-10,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/9290,Buildings,Completed,ND-TONDIARPET,42,998000,"CONSTRUCTION OF AMMA KUDI NEER CENTRE AT THILAGAR NAGAR IN DIV-42,UNIT-10,ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/9304,Buildings,Completed,ND-TONDIARPET,42,242000,"PROVIDING ELECTRICAL FITTINGS TO NEWLY CONSTRUCTED AMMA KUDINEER CENTER AND AMMA UNAVAGAM AT THILAGAR NAGAR IN DN-42,U-10,Z-8.",Own Sources,4,2016-17,2017-18 BR/2016-17/10436,Roads,Completed,BR-Bus Route Roads,43,3530000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Jeevarathinam Salai in Division -43 , Zone -05.",Grants,4,2016-17,2017-18 L/2016-17/15887,Electrical,Completed,L-Electrical,43,196100,"Replacement of 703 Mtr of 2 x 16 Sq,mm PVC Alu.Cable at Othavadi Street and Aadi Dravidar Street in Dn:43, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/18775,Electrical,Completed,L-Electrical,43,188800,"Erection of 15 Nos of 6 Mtr lamp post at MGR Nagar in Division 43, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/18777,Electrical,Completed,L-Electrical,43,188800,"Erection of 15 Nos of 6 Mtr lamp post at Singaravelan Nagar in Division 43, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/12191,Buildings,Completed,ND-TONDIARPET,43,995000,"Improvements to Health Department office building and Improvements to Foot path at TH Road in div-43,unit-10,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12195,Buildings,Completed,ND-TONDIARPET,43,898000,"Providing Drainage arrangements, electrical arrangements and necessasary works to multipurpose hall at jeevarathinam salai in div-43,unit-10,zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12781,Buildings,Completed,ND-TONDIARPET,43,993000,"Improvement the old building and convert to Amma unavgam in CDH at ward-43, unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12782,Buildings,Completed,ND-TONDIARPET,43,997000,"Providing concrete Platform, Water supply, Electrical Arrangement to Amma umvagam at CDH in ward-43, unit-10, zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12785,Buildings,Completed,ND-TONDIARPET,43,800000,"Providing tiles and flooring work to Amma unavgam in CDH at ward-43, unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/13206,Parks,Completed,ND-TONDIARPET,43,926000,"Greenary Arrangements to Hindu Burial Ground in Dn-43,U-10,Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/13207,Buildings,Completed,ND-TONDIARPET,43,917000,"Improvement Work at Hindu Burial Ground in Dn-43,U-10,Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/13541,Buildings,Completed,ND-TONDIARPET,43,456000,"Construction of RCC Sump and Water Supply Arrangement to Amma Unavagam at CDH in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/13741,Buildings,Completed,ND-TONDIARPET,43,960000,"Construction of Compost Yard at Kasimedu Hindu Burial Ground in DN-43,U-10,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/14096,Buildings,Completed,ND-TONDIARPET,43,69000,"Repairs and Maintenance work PC at S.N Cheety Street in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14106,Buildings,Completed,ND-TONDIARPET,43,40900,"Repairs and Maintenance work PC at Singaravelan nagar in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14108,Buildings,Completed,ND-TONDIARPET,43,47000,"Improvement to the PC at S.N Cheety Street(Thideer Nagar) in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14110,Buildings,Completed,ND-TONDIARPET,43,120000,"Improvement to the PC at Othavadai Street in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14111,Buildings,Completed,ND-TONDIARPET,43,12000,"Repairs and Maintenance work PC at Adidravidar Street in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14112,Buildings,Completed,ND-TONDIARPET,43,6900,"Repairs and Maintenance work PC at New Amarajipuram in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14243,Buildings,Completed,ND-TONDIARPET,43,840000,"Improvement to the CMS at Pudumanaikuppam in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14659,Buildings,Completed,ND-TONDIARPET,43,524000,"Construction of Toilet Block ( 2 Gents and 2 Ladies) and Old Toilet Convert to Office Room at Hindu Burial Ground in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/14791,Buildings,Completed,ND-TONDIARPET,43,584000,"Improvement to the CMS ( North side Building) at Pudumanaikuppam in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16112,Parks,Completed,ND-TONDIARPET,43,190000,"Repair and improvement of park due to vardha cyclone in Hindhu burial ground park (Greenary Arrangement work ) in Dn-43, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16269,Electrical,Completed,ND-TONDIARPET,43,126000,"Supply and erection of 6 Nos. of 2 Mtr Lamp Post with Arch bracket and 20W LED Fitting at Park in Surya Narayana Street in Dn:43, Zone IV",Own Sources,4,2016-17,2017-18 ND/2016-17/16428,Buildings,Completed,ND-TONDIARPET,43,370600,"Repairs and Improvements at Kasimanagar Fish Market & C.G Colony Firsh Market affected due to Varadah Cyclone (AC sheet Damage)during December 2016 in Dn-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/1700,Storm Water Drain,Completed,ND-TONDIARPET,43,447000,"DESILTING TO EXE .SWD AT Kummalamman Koil Street,S.N Cheety Street,New Amaraji Puram,Jeevarathinam Salai,Tondiar Nagar Main Street IN DN-43 ,UNIT-10 AND ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/17530,Parks,Completed,ND-TONDIARPET,43,124000,"Repair and improvement of park due to vardha cyclone in CDH Park (Greenary Arrangement work ) in Dn-43, Un-10,Zn-IV",Own Sources,4,2016-17,2017-18 ND/2016-17/2236,Footpath,Completed,ND-TONDIARPET,43,526000,"IMPROVEMENTS TO FOOTPATH AND CENTER MEDIAN(C.M VISIT) AT S.N CHETTY STREET IN DN-43,U-10,Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/2519,Roads,Completed,ND-TONDIARPET,43,688000,"DEMOLITION OF SCHOOL BUILDING AT GUMMALAMMAN KOIL STREET IN DN-43,UNIT-10,ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/4290,Storm Water Drain,Completed,ND-TONDIARPET,43,942000,"Laying Cross Pipe at T.H Road Near C.D.H and S.N Cheety Street near DN Office in DN-43,U-10,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/6363,Footpath,Completed,ND-TONDIARPET,43,990000,IMPROVEMENTS TO FOOT PATH AT SURYANARAYANAN STREET IN DN - 43 UNIT-10 ZONE-04,Own Sources,4,2016-17,2016-17 ND/2016-17/6369,Footpath,Completed,ND-TONDIARPET,43,990000,REPAIRS AND IMPROVEMENTS TO CENTER MEDIAN AT SURYANARAYANAN STREET IN DN - 43 UNIT-10 ZONE-04,Own Sources,4,2016-17,2017-18 ND/2016-17/7098,Footpath,Completed,ND-TONDIARPET,43,987000,"Improvement to Footpath at Kummalamman Koil street and Jeevarathinam Road in Ward-43, Unit-10, Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/8409,Buildings,Completed,ND-TONDIARPET,43,966000,"Providing Aluminium Partition and Improvements to Toilet Block and other necessary work to UPHC at Kasima Nagar 3rd Street in Dn-43, Unit-10, Zone IV",Own Sources,4,2016-17,2016-17 ND/2016-17/1055,Buildings,Completed,ND-TONDIARPET,44,990000,"Desilting of Storm Water Drain at Various streets (Gopal street, Rajaji street, Melpatti ponnappan street, Manicka vinayagar koil street, Muthamizh street, Kattabomman street, Kattabomman Lane, Thiruvalluvar street, Manimegalaia street, Kamarajar street) in Dn-44,Unit-11,Zone IV.",Own Sources,4,2016-17,2016-17 ND/2016-17/10639,Roads,Completed,ND-TONDIARPET,44,338000,"RELAYING CC ROAD V.O.C 1ST LANE IN DN-44, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10640,Roads,Completed,ND-TONDIARPET,44,225000,"REPLAYING CC ROAD V.O.C 2ND LANE IN DN-44, UNIT-11, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10641,Roads,Completed,ND-TONDIARPET,44,225000,"REPLAYING CC ROAD V.O.C 3RD LANE IN DN-44, UNIT-11, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11253,Buildings,Completed,ND-TONDIARPET,44,756000,Improvements to Gym Building at Gandhiji 1st street in Div-44 Unit-11 Zone-4,Own Sources,4,2016-17,2017-18 ND/2016-17/16392,Buildings,Completed,ND-TONDIARPET,44,113000,"Repairs and Improvements Foot path at Veerapandian street, Palani Andavar koil street, Thulsingam street affected due to Vardah Cyclone during December 2016 in Dn-44, Unit-11, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/17544,Roads,Completed,ND-TONDIARPET,44,104000,"Relaying of road at Thulsingam street & Muniyappan street affected due to Vardah Cyclone during December 2016 in Dn-44, Unit-11, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/17578,Roads,Completed,ND-TONDIARPET,44,72000,"Repairs and Improvements at Thiruchi chinna samy Play field affected due to Vardah Cyclone during December 2016 in Dn-44, Unit-11, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/1840,Parks,Completed,ND-TONDIARPET,44,477000,"Annual Maintenance of Park at Jawahar Street Park and Subramani Street Park in Dn-44, Unit-11, Zone-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2089,Storm Water Drain,Completed,ND-TONDIARPET,44,990000,"Desilting of Storm Water Drain at Various streets (Palani Anadavar Koil Street, Kamaraj Nagar 1st street, Amman koil street, Anna street, Subramania Nagar Main Road, Thirupur kumaran street, Veerapandian street, Thiru.vi.Ka street, Kandan street, Voc street in Dn-44, Unit-11,Zone IV.",Own Sources,4,2016-17,2016-17 ND/2016-17/3833,Buildings,Completed,ND-TONDIARPET,44,997000,Improvements to Chennai Middle School at New Kamaraj nagar in Division-44 Unit-11 Zone-4 (Councillor fund ),Own Sources,4,2016-17,2017-18 ND/2016-17/7133,Buildings,Completed,ND-TONDIARPET,44,990000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM (PHASE II ) AT ANNA NAGAR 5TH STREET (AMMAN KOIL STREET) IN DN-44, UNIT-11, ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/7139,Buildings,Completed,ND-TONDIARPET,44,990000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO AMMA UNAVAGAM (PHASE II) AT ANNA NAGAR 5TH STREET(AMMAN KOIL STREET) IN DN-44, UNIT-11, ZONE-04",Own Sources,4,2016-17,2017-18 ND/2016-17/7252,Roads,Completed,ND-TONDIARPET,44,990000,"Annual maintenance to Corporation Roads (List enclosed) in Dn-44, Unit-11, Zone-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/7259,Buildings,Completed,ND-TONDIARPET,44,970000,"Annual maintenance to Corporation Buildings (List enclosed) in Dn-44, unit-11, zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/7754,Buildings,Completed,ND-TONDIARPET,44,997000,"Desilting fo Jawahar Canal from Rajangam Street to Rani Ammaiyar street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/7759,Buildings,Completed,ND-TONDIARPET,44,997000,"Desilting of Jawahar Canal from Rani Ammaiyar street to Thiruvallur Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2016-17,2018-19 ND/2016-17/8388,Roads,Completed,ND-TONDIARPET,44,999000,"Relaying CC Road at K.v.k Samy Lane, Kattabomman Lane, Thulsingam 2nd Cross street and Thiruch Chinna Samy Lane in Dn-44, Unti-11, Zone-04.",Own Sources,4,2016-17,2017-18 ND/2016-17/9393,Roads,Completed,ND-TONDIARPET,44,489000,"Relaying BT Road at Shathivel Street in Dn-44, Unit-11, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9397,Roads,Completed,ND-TONDIARPET,44,1633000,"Relaying BT Road at Kasthuribai Street in Dn-44, Unit-11, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9399,Roads,Completed,ND-TONDIARPET,44,2181000,"Relaying BT Road Gopal Street in Dn-44, Unit-11, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9400,Roads,Completed,ND-TONDIARPET,44,1387000,"Relaying BT Road at V.o.c Street (Periyar Nagar) in Dn-44, Unit-11, Zone-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9414,Roads,Completed,ND-TONDIARPET,44,1223000,"Relaying BT Road at Alagirisamy Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/9418,Roads,Completed,ND-TONDIARPET,44,689000,"Relaying BT Road at Siva Sakthi Vinayagar koil Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2016-17,2016-17 BR/2016-17/17647,Roads,Completed,BR-Bus Route Roads,45,2509000,Attending temporary repairs to damaged road due to Vardha Cyclone in North East Monsoon 2016 at Tondairpet High Road in Zone 4,Own Sources,4,2016-17,2017-18 BR/2016-17/17648,Roads,Completed,BR-Bus Route Roads,45,929000,"Attending temporary repairs to damaged road due to Vardha Cyclone in North East Monsoon 2016 at Ethiraj salai ,Moorthingar street and MKB nagar west avenue Road in Zone 4",Grants,4,2016-17,2017-18 BR/2016-17/17747,Roads,Completed,BR-Bus Route Roads,45,2470000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Thiruvottiyur high road,S.N chetty street,Thiruvalluvar salai,Vaidhyanathan street,Melpattiponnapan street etc., in Zone-4",Grants,4,2016-17,2017-18 ND/2016-17/0848,Storm Water Drain,Completed,ND-TONDIARPET,45,305000,"SWD INTER CONNECTION WORK BETWEEN GANESHAPURAM MAIN ROAD AND DR. AMBEDKAR COLLEGE ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/10142,Roads,Completed,ND-TONDIARPET,45,602000,"RELAYING CC ROAD AT AVVAI NAGAR 1ST STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10143,Roads,Completed,ND-TONDIARPET,45,602000,"RELAYING CC ROAD AT AVVAI NAGAR 2ND STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10192,Roads,Completed,ND-TONDIARPET,45,602000,"RELAYING CC ROAD AT AVVAI NAGAR 3RD STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10193,Roads,Completed,ND-TONDIARPET,45,636000,"RELAYING CC ROAD AT ERUKKANCHERY LANE IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10194,Roads,Completed,ND-TONDIARPET,45,977000,"RELAYING CC ROAD AT RENGANATHAPURAM IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10198,Roads,Completed,ND-TONDIARPET,45,1364000,"RELAYING CC ROAD AT APPU STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2017-18 ND/2016-17/10200,Roads,Completed,ND-TONDIARPET,45,864000,"RELAYING CC ROAD AT OP LANE DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10201,Roads,Completed,ND-TONDIARPET,45,195000,"RELAYING CC ROAD AT BB ROAD 7TH CROSS STREET DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10202,Roads,Completed,ND-TONDIARPET,45,210000,"RELAYING CC ROAD AT BB ROAD 8TH CROSS STREET DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10203,Roads,Completed,ND-TONDIARPET,45,296000,"RELAYING CC ROAD AT BB ROAD 9TH CROSS STREET DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10204,Roads,Completed,ND-TONDIARPET,45,392008,"RELAYING CC ROAD AT BB ROAD 10TH CROSS STREET DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/11303,Roads,Completed,ND-TONDIARPET,45,271200,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 1ST STREET IN DN-45,UN-11,ZN-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11304,Roads,Completed,ND-TONDIARPET,45,231000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 4TH STREET IN DN-45,UN-11,ZN-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11306,Roads,Completed,ND-TONDIARPET,45,195400,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 6TH STREET IN DN-45,UN-11,ZN-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11308,Roads,Completed,ND-TONDIARPET,45,267800,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 7TH STREET IN DN-45,UN-11,ZN-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11310,Roads,Completed,ND-TONDIARPET,45,287458,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 8TH STREET IN DIVISION-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11311,Roads,Completed,ND-TONDIARPET,45,249000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 27TH STREET IN DIVISION-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11312,Roads,Completed,ND-TONDIARPET,45,304000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 28TH STREET IN DIVISION-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11316,Roads,Completed,ND-TONDIARPET,45,254000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 29TH STREET IN DIVISION-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11317,Roads,Completed,ND-TONDIARPET,45,183000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 30TH STREET IN DIVISION-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11318,Roads,Completed,ND-TONDIARPET,45,245000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT BV COLONY 31st STREET IN DIVISION-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11400,Roads,Completed,ND-TONDIARPET,45,209000,"RELAYING OF BT ROAD IN BV COLONY 16TH STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11487,Buildings,Completed,ND-TONDIARPET,45,980000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period at.Dr.Ambethkar Collage Road (Opp to Division Office) in Dn-45, Unit-11, Zone-4",Own Sources,4,2016-17,2019-20 ND/2016-17/12372,Roads,Completed,ND-TONDIARPET,45,314000,"RELAYING OF BT ROAD IN RATHINAM NAGAR 2ND STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/12373,Roads,Completed,ND-TONDIARPET,45,314000,"RELAYING OF BT ROAD IN RATHINAM NAGAR 1ST STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/13939,Buildings,Completed,ND-TONDIARPET,45,88000,"REPAIR AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT BV COLONY 18TH STREET IN DIVISION-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/13941,Buildings,Completed,ND-TONDIARPET,45,81000,"REPAIR AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT BV COLONY 26TH STREET IN DIVISION-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/13942,Buildings,Completed,ND-TONDIARPET,45,71000,"REPAIR AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT BV COLONY 8TH STREET IN DIVISION-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/13943,Buildings,Completed,ND-TONDIARPET,45,97000,"REPAIR AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT MELAPATI PONNAPPAN STREET IN DIVISION-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/13944,Buildings,Completed,ND-TONDIARPET,45,97000,"REPAIR AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT GANESAPURAM MAIN ROAD IN DIVISION-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/14309,Buildings,Completed,ND-TONDIARPET,45,450000,"REPAIR AND IMPROVEMENTS TO THE CHENNAI HIGH SCHOOL AT GANESAPURAM MAIN ROAD IN DIVISION 45, UNIT-11,ZONE-4.",Own Sources,4,2016-17,2018-19 ND/2016-17/14366,Buildings,Completed,ND-TONDIARPET,45,410000,"CONSTRUCTION OF SOURCE SEGREGATE AT B. V. COLONY 8TH STREET IN DN-45,UN-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/14866,Buildings,Completed,ND-TONDIARPET,45,338000,"CONSTRUCTION OF MINI COMPOST YARD AT MPM STREET IN DN-45,UN-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/15600,Parks,Completed,ND-TONDIARPET,45,360000,"Revised Estimate for Annual Maintainance Of Desikanandapuram Park,Vyasar Nagar Park, Kasthuri Bai Gandhi Park (One Year) In Div-45,Unit-11,Zone-04",Own Sources,4,2016-17,2018-19 ND/2016-17/16201,Buildings,Completed,ND-TONDIARPET,45,223000,"REPAIR AND IMPROVEMENT OF DESINGANANTHAPURAM AND SANJAY NAGAR PARK AFFECTED DUE TO VARDAH CYCLONE DURING DECEMBER 2016 IN DIV-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16394,Roads,Completed,ND-TONDIARPET,45,31500,"REPAIR AND IMPROVEMENT OF STREET NAME BOARD AT VARIOUS STREET AFFECTED DUE TO VARDAH CYCLONE DURING DECEMBER 2016 IN DIV-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2017-18 ND/2016-17/17044,Roads,Completed,ND-TONDIARPET,45,590000,"RELAYING OF ROAD AT BV COLONY 20TH & 21ST CROSS STREET AND 21ST STREET AFFECTED DUE TO VARDHA CYCLONE DURING DECEMBER 2016 IN DIV-45,UNIT-11,ZONE-04",Own Sources,4,2016-17,2017-18 ND/2016-17/1978,Storm Water Drain,Completed,ND-TONDIARPET,45,465000,"DE-SILTING IN STORM WATER DRAIN AND REPAIR WORKS TO KAKANJI COLONY 1st STREET IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2018,Roads,Completed,ND-TONDIARPET,45,996000,"REPAIRS AND IMPROVEMETS TO STROM WATER DRAIN AT GANESHAPURAM MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2019,Roads,Completed,ND-TONDIARPET,45,997000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT CLINIC ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2020,Roads,Completed,ND-TONDIARPET,45,965000,"CONSTRUCTION OF SILT CATCH PIT TO SWD AT VARIOUS ROADS IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2333,Storm Water Drain,Completed,ND-TONDIARPET,45,830000,"DE-SILTING IN STORM WATER DRAIN AND REPAIR WORKS TO B.V. COLONY 1st STREET IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2334,Storm Water Drain,Completed,ND-TONDIARPET,45,705000,"DE-SILTING IN STORM WATER DRAIN AND REPAIR WORKS TO SUNDARAM MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2335,Storm Water Drain,Completed,ND-TONDIARPET,45,495000,"DE-SILTING IN STORM WATER DRAIN AND REPAIR WORKS TO GANESHAPURAM MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2336,Storm Water Drain,Completed,ND-TONDIARPET,45,730000,"DE-SILTING IN STORM WATER DRAIN AND REPAIR WORKS TO A.A.ROAD (FROM THE JUNCTION OF STEPHENSON ROAD TO KASTURIBHAI GANDHI NAGAR) IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2337,Storm Water Drain,Completed,ND-TONDIARPET,45,942000,"DE-SILTING IN STORM WATER DRAIN AND REPAIR WORKS TO A.A.ROAD (FROM THE JUNCTION OF B.B ROAD TO KASTURIBHAI GANDHI NAGAR) IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/2338,Storm Water Drain,Completed,ND-TONDIARPET,45,803000,"DE-SILTING IN STORM WATER DRAIN AND REPAIR WORKS TO KAKANJI COLONY 1st STREET (REACH-2) IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/3732,Storm Water Drain,Completed,ND-TONDIARPET,45,997000,"DESILTING WORK IN VYASARPADI LINK CANAL (FROM EH ROAD (JN. OF MOORTHINGAR STREET) UPTO SHARMA NAGAR MARKET) IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4454,Road Cut,Completed,ND-TONDIARPET,45,990000,"ROAD CUT RESTORATION WORK AT SUNDARAM MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4456,Road Cut,Completed,ND-TONDIARPET,45,990000,"ROAD CUT RESTORATION WORK AT GANESHAPURAM MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4457,Road Cut,Completed,ND-TONDIARPET,45,998000,"ROAD CUT RESTORATION WORK AT VYASAR NAGAR 6tH, 7th AND 8th STREETS IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4458,Storm Water Drain,Completed,ND-TONDIARPET,45,995000,"ROAD CUT RESTORATION WORK AT VYASAR NAGAR 1st, 2nd, 3rd, 4th and VYASAR NAGAR MAIN ROAD (STEPHENSON LANE) STREETS IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/4460,Road Cut,Completed,ND-TONDIARPET,45,998000,"ROAD CUT RESTORATION WORK AT SHANTHI NAGAR 4th, 5th, 6th STREETS and SHANTHI NAGAR MAIN ROAD /STREETS IN DIVISION-45, UNIT-11, ZONE-4.",Deposit Works,4,2016-17,2016-17 ND/2016-17/4462,Buildings,Completed,ND-TONDIARPET,45,926000,"IMPROVEMENTS TO LORRY STATION AE OFFICE, TIME KEEPER OFFICE AND PROVIDING LOCKER FACILITIES TO DRIVERS IN ZONE-4 LORRY STATION IN DIVISION-4, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/5986,Buildings,Completed,ND-TONDIARPET,45,999000,"PROVIDING STAINLESS STEEL STREET NAME BOARD TO VARIOUS STREETS IN DIVISION-45, UNIT-11, ZONE-4. (WARD COUNCILLOR FUND)",Own Sources,4,2016-17,2017-18 ND/2016-17/5987,Buildings,Completed,ND-TONDIARPET,45,999000,"IMPROVEMENTS TO KASTURIBHAI GANDHI PARK AT KASTURIBHAI GANDHI NAGAR IN DN-45,UNIT-11,ZONE-4. (WARD COUNCILLOR FUND)",Own Sources,4,2016-17,2017-18 ND/2016-17/5988,Buildings,Completed,ND-TONDIARPET,45,999000,"IMPROVEMENTS TO DESIGANANDA PARK AT GANASAPURAM IN DN 45,UNIT-11,ZONE-4 (WARD COUNCILLOR FUND)",Own Sources,4,2016-17,2017-18 ND/2016-17/5989,Buildings,Completed,ND-TONDIARPET,45,263000,"PROVIDING REVERSE OSMOSIS PLANT TO ZONE-4 LORRY STATION IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/5993,Storm Water Drain,Completed,ND-TONDIARPET,45,999000,"Improvement @ Repair works Day to Day SWD Varies Street in DN-45, Unit -11, Zone -04.",Own Sources,4,2016-17,2017-18 ND/2016-17/5995,Roads,Completed,ND-TONDIARPET,45,999000,"Estimate for carrying out petty repairs (Day to Day) in Road Maintenance at Various Street in Dn.45, Unit.11, Zone.4.",Own Sources,4,2016-17,2017-18 ND/2016-17/5996,Buildings,Completed,ND-TONDIARPET,45,999000,"Estimate for carrying out petty repairs (Day to Day) in Corporation building at Various Street in Dn.45, Unit.11, Zone.4.",Own Sources,4,2016-17,2017-18 ND/2016-17/7517,Buildings,Completed,ND-TONDIARPET,45,360000,IMPROVEMENT AND REPAIR WORK @ ICDS CENTRE 12022/33603120303 B.V. COLONY 1ST STREET & ICDS CENTRE 12023/33603120304 B.V. COLONY 6TH STREET IN DN-45 UNIT-11 ZONE 4,Own Sources,4,2016-17,2017-18 ND/2016-17/7519,Buildings,Completed,ND-TONDIARPET,45,433000,IMPROVEMENT AND REPAIR WORK @ ICDS CENTRE 12032/33603120317 KAKKAJI COLONY 4TH STREET & CENTRE 12026/33603120307 B.V . COLONY 18TH STREET IN DN-45 UNIT-11 ZONE 4.,Own Sources,4,2016-17,2017-18 ND/2016-17/9799,Roads,Completed,ND-TONDIARPET,45,804000,"RELAYING BT ROAD AT VYASAR NAGAR 1ST STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9800,Roads,Completed,ND-TONDIARPET,45,842000,"RELAYING BT ROAD AT VYASAR NAGAR 2ND STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9801,Roads,Completed,ND-TONDIARPET,45,727000,"RELAYING BT ROAD AT VYASAR NAGAR 3RD STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9810,Roads,Completed,ND-TONDIARPET,45,689000,"RELAYING BT ROAD VYASAR NAGAR 5TH STREET IN DN-45, UNIT-11, ZONE-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/9819,Roads,Completed,ND-TONDIARPET,45,689000,"RELAYING BT ROAD AT VYASAR NAGAR 6TH STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9820,Roads,Completed,ND-TONDIARPET,45,727000,"RELAYING BT ROAD AT VYASAR NAGAR 7TH STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9821,Roads,Completed,ND-TONDIARPET,45,745000,"RELAYING BT ROAD AT VYASAR NAGAR 8TH STREET IN DN-45, UNIT-11, ZONE-04",Own Sources,4,2016-17,2016-17 ND/2016-17/9822,Roads,Completed,ND-TONDIARPET,45,764000,"RELAYING BT ROAD AT SHANTHI NAGAR MAIN ROAD IN DN-45, UNIT-11, ZONE-04.",Own Sources,4,2016-17,2016-17 ND/2016-17/9825,Roads,Completed,ND-TONDIARPET,45,385000,"RELAYING OF BT ROAD IN SHANTHI NAGAR 1ST STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9826,Roads,Completed,ND-TONDIARPET,45,185000,"RELAYING OF BT ROAD IN SHANTHI NAGAR 2ND STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9827,Roads,Completed,ND-TONDIARPET,45,173000,"RELAYING OF BT ROAD IN SHANTHI NAGAR 3RD STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9830,Roads,Completed,ND-TONDIARPET,45,168000,"RELAYING OF BT ROAD IN SHANTHI NAGAR 4TH STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9880,Roads,Completed,ND-TONDIARPET,45,436000,"RELAYING OF BT ROAD IN SHANTHI NAGAR 5th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9881,Roads,Completed,ND-TONDIARPET,45,288000,"RELAYING OF BT ROAD IN SHANTHI NAGAR 6th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9882,Roads,Completed,ND-TONDIARPET,45,594000,"RELAYING OF BT ROAD IN BV COLONY 9th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9883,Roads,Completed,ND-TONDIARPET,45,351000,"RELAYING OF BT ROAD IN BV COLONY 10th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9884,Roads,Completed,ND-TONDIARPET,45,557000,"RELAYING OF BT ROAD IN BV COLONY 12th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9885,Roads,Completed,ND-TONDIARPET,45,391000,"RELAYING OF BT ROAD IN BV COLONY 13th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9886,Roads,Completed,ND-TONDIARPET,45,351000,"RELAYING OF BT ROAD IN BV COLONY 14th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9887,Roads,Completed,ND-TONDIARPET,45,243000,"RELAYING OF BT ROAD IN BV COLONY 15th STREET IN DN-45,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9888,Buildings,Completed,ND-TONDIARPET,45,993000,"PROVIDING FLOORING, WATER SUPPLY,DRAINAGE ARRANGEMENTS AND OTHER IMPROVEMENTS WORK TO AMMA UNAVAGAM PHASE-2 AT AT SANJAY NAGAR (ADJ. TO MELPATTI PONNAPPAN STREET) IN DIVISION-45, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/9890,Buildings,Completed,ND-TONDIARPET,45,996000,"CONSTRUCTION OF SUMP,ELECTRICAL,AND OUTER FLOORING ARRANGEMENTS TO AMMA UNAVAGAM PHASE-2 AT SANJAY NAGAR (ADJ. TO MELPATTI PONNAPPAN STREET) IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9891,Buildings,Completed,ND-TONDIARPET,45,997000,"PROVIDING ROOFING ARRANGEMENTS,ELECTRICAL,WATER SUPPLY AND DRAINAGE ARRANGEMENTS TO NEWLY CONSTRUCTED AMMA KUDI NEER CENTER AT DR.AMBEDHKAR COLLEGE ROAD(NEAR DIVISION OFFICE) IN DN-45,U-11,Z-4",Own Sources,4,2016-17,2016-17 BR/2016-17/17646,Roads,Completed,BR-Bus Route Roads,46,2927000,Attending temporary repairs to damaged road due to Vardha Cyclone in North East Monsoon 2016 at S.M.Nagar Service Road in Zone 4,Own Sources,4,2016-17,2017-18 BR/2016-17/5874,Roads,Completed,BR-Bus Route Roads,46,4350000,"Strengthening and relaying of existing cement concrete road with M40 Concrete at Moorthingar street from Raveeshwaran koil tank to 65M in div 46, Zone -04.",Own Sources,4,2016-17,2016-17 L/2016-17/12012,Electrical,Completed,L-Electrical,46,1723300,"Provision of 32 Nos of 6 Mtr G.I. Lamp Post with 32 Nos of 90 Watts LED Fitting on 26 Nos G.I. Single Straight Bracket and 6 Nos of G.I. Single Arch Bracket at Tamil Nadu Slum Clearance Board Tenements (960 Tenements G+7) Block 1 to 10 at Moorthingar Street in Division 46, Zone IV",Deposit Works,4,2016-17,2018-19 ND/2016-17/0437,Buildings,Completed,ND-TONDIARPET,46,670000,"IMPROVEMENTS TO STORM WATER DRAINAGE (EAST SIDE FROM 450 TO 900 MTRS) NEAR SM NAGAR MAIN ROAD PARK DN-46,U-11,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/0785,Storm Water Drain,Completed,ND-TONDIARPET,46,670000,"IMPROVEMENTS TO STORM WATER DRAINAGE (EAST SIDE FROM 0 TO 450 MTRS) NEAR SM NAGAR MAIN ROAD PARK DN-46,U-11,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/10144,Roads,Completed,ND-TONDIARPET,46,662453,"RELAYING OF B.T ROAD AT KENNEDY NAGAR 1ST STREET IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10145,Roads,Completed,ND-TONDIARPET,46,486909,"RELAYING OF B.T ROAD AT KENNEDY NAGAR 2ND STREET IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10148,Roads,Completed,ND-TONDIARPET,46,452954,"RELAYING OF B.T ROAD AT KENNEDY NAGAR 3RD STREET IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10149,Roads,Completed,ND-TONDIARPET,46,452954,"RELAYING OF B.T ROAD AT KENNEDY NAGAR 4TH STREET IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10152,Roads,Completed,ND-TONDIARPET,46,804554,"RELAYING OF B.T ROAD AT JOHN KENNEDY NAGAR IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2016-17,2016-17 ND/2016-17/10670,Roads,Completed,ND-TONDIARPET,46,2786705,"RELAYING THE CC ROAD AT OLD GOOD SHED ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10672,Roads,Completed,ND-TONDIARPET,46,1324000,"RELAYING THE CC ROAD AT MOORTHINGER STREET(AROUND SIVAN TEMPLE TANK- INTEAR ROAD) IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10673,Roads,Completed,ND-TONDIARPET,46,1144000,"RELAYING THE CC ROAD AT C KALYANAPURAM 1ST STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10675,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT C KALYANAPURAM 2ND STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10678,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT C KALYANAPURAM 4TH STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10679,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT C KALYANAPURAM 5TH STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10680,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT C KALYANAPURAM 6TH STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10681,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT C KALYANAPURAM 7TH STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10682,Roads,Completed,ND-TONDIARPET,46,904011,"RELAYING THE CC ROAD AT C KALYANAPURAM MAIN STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10684,Roads,Completed,ND-TONDIARPET,46,2116000,"RELAYING THE CC ROAD AT C KALYANAPURAM MAIN ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10685,Roads,Completed,ND-TONDIARPET,46,586600,"RELAYING THE CC ROAD AT GANANATHAR STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10686,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT SADAGOPALWAR STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10687,Roads,Completed,ND-TONDIARPET,46,1025000,"RELAYING THE CC ROAD AT VENKATASA PERUMAL KOVIL STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10688,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT SUNDARAM STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10689,Roads,Completed,ND-TONDIARPET,46,723000,"RELAYING THE CC ROAD AT MOORTHINGER 2ND STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10978,Storm Water Drain,Completed,ND-TONDIARPET,46,700000,"CONSTRUCTION OF 600MM DIA PIPE DRAIN BETWEEN VYASARPADI RAILWAY YARD, OLD GOOD SHED ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2018-19 ND/2016-17/11472,Buildings,Completed,ND-TONDIARPET,46,980000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period in Dn -46,Unit-11, Zone -04",Own Sources,4,2016-17,2019-20 ND/2016-17/12768,Footpath,Completed,ND-TONDIARPET,46,458000,"PROVIDING DRAINAGE ARRANGEMENT TO AMMA KUDINEER FOR DISPOSAL OF WATER AT 24 TH BLOCK OF SM NAGAR MAIN ROAD IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/13570,Storm Water Drain,Completed,ND-TONDIARPET,46,995000,"Desilting of Thamarai Kulam including removal of obstruction weeds, hyacynth and other floating materials using poclain, special type of float platform at Vyasarpadi Railway Yard, Old goods road, in DN-46, unit-11. Zone-4",Own Sources,4,2016-17,2017-18 ND/2016-17/17589,Parks,Completed,ND-TONDIARPET,46,995000,"Annual maintenance of Foot ball Ground ( operating of Mechanical sprinklers and Maintaining Grass and lawns and irrigation system ) at samandhypoocolony in Div-46,unit-11,zone-4",Own Sources,4,2016-17,2018-19 ND/2016-17/18029,Buildings,Completed,ND-TONDIARPET,46,1130000,"CONSTRUCTION OF RESOURCE RECOVERY CENTRE AT KRISHNAN STREET IN DN-46,UN-11,ZONE-04",Own Sources,4,2016-17,2019-20 ND/2016-17/18030,Buildings,Completed,ND-TONDIARPET,46,360000,"SUPPLYING AND PLACING OF WELL RING FOR COMPOST YARD AT KENNEDY NAGAR ,GOOD SHED ROAD,S.M NAGAR & KRISHNAN STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2019-20 ND/2016-17/3820,Buildings,Completed,ND-TONDIARPET,46,999000,"PROVIDING STREET FURNITURES AT VARIOUS STREET UNDER WARD COUNSILOR FUND (2016-17) IN DN 46, UNIT- 11, ZONE -4",Own Sources,4,2016-17,2018-19 ND/2016-17/3821,Roads,Completed,ND-TONDIARPET,46,999000,"LAYING CC ROAD AT KENNEDY NAGAR 5TH STREET UNDER WARD COUNSILOR FUND (2016-2017) IN DN 46,UNIT 11,ZONE 4",Own Sources,4,2016-17,2017-18 ND/2016-17/3822,Roads,Completed,ND-TONDIARPET,46,720000,"IMPROVEMENTS TO STORM WATER DRAINAGE (WEST SIDE FROM 450 TO 900 MTRS) NEAR SM NAGAR MAIN ROAD PARK IN DN-46,U-11,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/3991,Footpath,Completed,ND-TONDIARPET,46,710000,"IMPROVEMENTS TO STORM WATER DRAINAGE (WEST SIDE FROM 0 TO 450 MTRS) NEAR SM NAGAR MAIN ROAD PARK DN-46,U-11,Z-04",Own Sources,4,2016-17,2016-17 ND/2016-17/6294,Buildings,Completed,ND-TONDIARPET,46,970000,"IMPROVEMENTS TO P. C. AT GANDHI PURAM END OF ROAD COMMUNITY TOILET IN DN-46, U-11, Z.4.",Own Sources,4,2016-17,2016-17 ND/2016-17/6643,Roads,Completed,ND-TONDIARPET,46,970000,"ANNUAL MAINTENANCE OF SATHYAMOORTHY NAGAR PARK IN DN-46,UNIT-11, ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/8149,Buildings,Completed,ND-TONDIARPET,46,986000,"PROPOSED CONSTRUCTION WORK FOR AMMA DRINKING WATER AT S.M NAGAR 24TH BLOCK IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2016-17,2016-17 BR/2016-17/10430,Roads,Completed,BR-Bus Route Roads,47,2535000,"Strengthening and Relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Pitty munusamy street from Jn Kannan street to Jn Mannapan street in Division -47 , Zone -04.",Grants,4,2016-17,2017-18 BR/2016-17/17887,Roads,Completed,BR-Bus Route Roads,47,371000,Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 Suryanarayana street and Thiruvottriur High road in Zone 4,Grants,4,2016-17,2017-18 L/2016-17/15846,Electrical,Completed,L-Electrical,47,134200,"Painting and Numbering 6/7 Mtr and 9.2Mtr Lamp Post at Various Location in Dn:47, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/16883,Electrical,Completed,L-Electrical,47,972000,"Provision of 8 Nos.of 8 Mtr Long Ocatagonal Mini Highmast Light with hexagonal lantern carriage with 3 Nos.of 70W -100W LED Flood light Fitting at Various Locations in Dn: 42 and 47, Zone IV",Own Sources,4,2016-17,2017-18 L/2016-17/8194,Electrical,Completed,L-Electrical,47,170400,"Provision of 15 Nos of 90W LED fitting at C B Road in Div - 47, Zone IV",Own Sources,4,2016-17,2016-17 ND/2016-17/0279,Buildings,Completed,ND-TONDIARPET,47,400000,PROVINDING WATER SUPPLY AND DRANIAGE ARRANGEMENTS TO MEENAMBAL HOSPITAL AT K H ROAD IN DN 47 UNIT 11 ZONE 4,Own Sources,4,2016-17,2016-17 ND/2016-17/0436,Storm Water Drain,Completed,ND-TONDIARPET,47,264000,"PROVINDING F R C DOOR ARRANGEMENTS TO S W DRAIN AT K H ROAD ,C B ROAD AND RAJIVE GANDHI NAGAR IN DN 47 U 11 Z 4",Own Sources,4,2016-17,2016-17 ND/2016-17/10400,Roads,Completed,ND-TONDIARPET,47,554979,"RELAYING OF BT ROAD AT SATHYAMURTHI NAGAR MAIN STREET IN DN-47,U-11,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/10413,Roads,Completed,ND-TONDIARPET,47,871953,"RELAYING OF BT ROAD AT BHARATHI NAGAR MAIN STREET IN DN-47,U-11,Z-04",Grants,4,2016-17,2016-17 ND/2016-17/10979,Storm Water Drain,Completed,ND-TONDIARPET,47,990000,"Desilting of Ambehkar Canal in DN -47, Unit -11, Zone -04.",Own Sources,4,2016-17,2018-19 ND/2016-17/11387,Buildings,Completed,ND-TONDIARPET,47,518000,"PROVIDING WEATHERING COURSE AND ADDITIONAL IMPROVEMENTS TO AMMA UNAVAGAM AT SIGIRINTHAPALAYAM 5TH STREET KORUKUPET IN DIV-47,UN-11,Z- 04",Own Sources,4,2016-17,2016-17 ND/2016-17/11396,Parks,Completed,ND-TONDIARPET,47,858000,"ADDITIONAL WORK TO BHARATHI NAGAR PARK TNSCB IN DN-47,U-11,ZONE-04",Thanniraivu Thittam,4,2016-17,2017-18 ND/2016-17/11788,Buildings,Completed,ND-TONDIARPET,47,642000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Old Glass Factory in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/11791,Buildings,Completed,ND-TONDIARPET,47,642000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Old Glass Factory in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/11792,Buildings,Completed,ND-TONDIARPET,47,642000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Kamaraj Nagar 12th Street in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/11793,Buildings,Completed,ND-TONDIARPET,47,642000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Kamaraj Nagar 12th Street in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2016-17,2017-18 ND/2016-17/13272,Buildings,Completed,ND-TONDIARPET,47,625000,"CONSTRUCTION OF TOILETS AND ADDITIONAL IMPROVEMENTS TO CREACH BUILDING AT BHARATHI NAGAR 6TH STREET IN DN-47,U-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/15349,Electrical,Completed,ND-TONDIARPET,47,485400,"Electrification Work at Meenambal Nagar Hospital (E.O.C) in Division 47, Zone IV",Own Sources,4,2016-17,2019-20 ND/2016-17/16262,Buildings,Completed,ND-TONDIARPET,47,199000,"DISMANTLING AND RECONSTRUCTION OF COMPOUND WALL DUE TO VARDHAH CYCIONE AT THYAGAPPA STREET PC IN DN-47,U-11,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/16271,Buildings,Completed,ND-TONDIARPET,47,33200,"PROVIDING WATER SUPPLY ARRANGEMENTS FOR NNMP SHED 2NOS AT EGAPPAN STREET IN DN-47,U-11,Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/1702,Storm Water Drain,Completed,ND-TONDIARPET,47,131000,"DESILTING AND REPAIR TO EXE.SWD AT THYAGAPPA STREET IN DN-47,UNIT-11 AND ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/1705,Storm Water Drain,Completed,ND-TONDIARPET,47,308000,"DESILTING AND REPAIR TO EXE.SWD AT EGAPPAN STREET IN DN-47,UNIT-11 AND ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/1707,Storm Water Drain,Completed,ND-TONDIARPET,47,239000,"DESILTING AND REPAIR TO EXE.SWD AT MANNAPPAN STREET IN DN-47,UNIT-11 AND ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/1708,Storm Water Drain,Completed,ND-TONDIARPET,47,223000,"DESILTING AND REPAIR TO EXE .SWD AT SIGGIRINTHAPALAYAM 4th STREET IN DN-47,UNIT-11 AND ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/1711,Storm Water Drain,Completed,ND-TONDIARPET,47,323000,"DISILTING AND REPAIR TO EXE.SWD AT K.H ROAD DN-47,UNIT-11 AND ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/1713,Storm Water Drain,Completed,ND-TONDIARPET,47,220000,"DISILTING AND REPAIR TO EXE.SWD AT C.B ROAD DN-47,UNIT-11 AND ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/1714,Storm Water Drain,Completed,ND-TONDIARPET,47,394000,"DISILTING AND REPAIR TO EXE.SWD AT KANNAN STREET DN-47,UNIT-11 AND ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/18142,Buildings,Completed,ND-TONDIARPET,47,210000,"CONSTRUCTION OF COMPOST YARD AT C.B.ROAD (FLY OVER DOWN) AND BHARATHI NAGAR IN DN-47,U-11,Z-04",Own Sources,4,2016-17,2018-19 ND/2016-17/19561,Buildings,Completed,ND-TONDIARPET,47,336000,"CONSTRUCTION OF SOURCE SEGREGATE AT C.B.ROAD (FLY OVER DOWN)IN DN-47,U-11,Z-04",Own Sources,4,2016-17,2018-19 ND/2016-17/2346,Storm Water Drain,Completed,ND-TONDIARPET,47,162000,"DISILTING AND REPAIR TO EXE.SWD AT JAWMAAL SOWCAR STREET IN DN-47,UNIT-11,ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/4168,Storm Water Drain,Completed,ND-TONDIARPET,47,131000,"DISILTING AND REPAIR TO EXE.SWD AT PITTYMUNUSAMY STREET IN DN-47,UNIT-11,ZONE-4",Own Sources,4,2016-17,2018-19 ND/2016-17/7096,Buildings,Completed,ND-TONDIARPET,47,980000,REPAIRS AND IMPROVEMENTS TO C M S (RANGANATHAPURAM) AT KANNAN STREET IN DN 47 UNIT 11 ZONE 4,Own Sources,4,2016-17,2016-17 ND/2016-17/7652,Buildings,Completed,ND-TONDIARPET,47,643000,"ADDITIONAL IMPROVEMENTS TO MEENAMBAL NAGAR ECO HOSPITALS AT K.H.ROAD IN DN-47,U-11, Z-04",Own Sources,4,2016-17,2017-18 ND/2016-17/8006,Buildings,Completed,ND-TONDIARPET,47,950000,Improvements to AMMA UNAVAGAM at meenambal nagar 4th street in ward.47 unit.11 zone.4,Own Sources,4,2016-17,2017-18 ND/2016-17/8143,Roads,Completed,ND-TONDIARPET,47,770000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermo Plastic Compound marking Road pavement markers and signage boards At KAMARAJA NAGAR AND BHARATHI NAGAR IN DN-47,UNIT-11,ZONE-04",Own Sources,4,2016-17,2017-18 ND/2016-17/8148,Roads,Completed,ND-TONDIARPET,47,980000,"PROVIDING AND FIXING STREET NAME BOARD AT VARIOUS STREETS IN DN-47,U-11,ZONE-04",Own Sources,4,2016-17,2018-19 ND/2016-17/9326,Buildings,Completed,ND-TONDIARPET,47,752000,Improvements to public convenience at kamaraj nagar 2nd street in ward.47 unit.11 zone.4,Own Sources,4,2016-17,2016-17 ND/2016-17/9677,Roads,Completed,ND-TONDIARPET,47,959000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT MANAPPAN STREET, IN DN - 47, UNIT -11 , Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9678,Roads,Completed,ND-TONDIARPET,47,420000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT R K NAGAR 2ND TREET, IN DN - 47, UNIT -11 , Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9694,Roads,Completed,ND-TONDIARPET,47,479600,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT R K NAGAR 3RD TREET, IN DN - 47, UNIT -11 , Z-4",Own Sources,4,2016-17,2016-17 ND/2016-17/9713,Roads,Completed,ND-TONDIARPET,47,402000,"ATTENDING PATCH WORK BY USING PAVER FINISHER AT PITTY MUNUSAMY STREET, IN DN - 47, UNIT -11 , Z-4",Own Sources,4,2016-17,2016-17 L/2016-17/14567,Electrical,Completed,L-Electrical,48,772100,"Replacement of 765 Mtrs of 4x16 Sqmm Cable at TPF in Division 48,Zone IV",Own Sources,4,2016-17,2018-19 L/2016-17/18166,Electrical,Completed,L-Electrical,48,710200,"Replacement of 1587 Mtrs of 2x16 Sqmm Cable at West Cementry Road in Division -48, Zone-4.",Own Sources,4,2016-17,2018-19 L/2016-17/18167,Electrical,Completed,L-Electrical,48,564200,"Replacement of 1075 Mtrs of 4x16 Sqmm Cable at T H Road in Dn:48, Zone IV",Own Sources,4,2016-17,2018-19 L/2016-17/18196,Electrical,Completed,L-Electrical,48,972900,"Replacement of 2404 Mtrs of 2x16 Sqmm Cable at M S Naidu Street, Arumugam Street, Ramanujam Koodam Street and Shanmugarayan Street in Division -48, Zone-4.",Own Sources,4,2016-17,2017-18 L/2016-17/18201,Electrical,Completed,L-Electrical,48,946500,"Replacement of 2189 Mtrs of 2x16 Sqmm Cable at Kani Koil Street,Namachivaya Street, Kailaya Street,Arani Gangan Street and Basuvayan Street in Division -48, Zone-4.",Own Sources,4,2016-17,2018-19 L/2016-17/18232,Electrical,Completed,L-Electrical,48,770300,"Replacement of 1888 Mtrs of 2x16 Sqmm Cable at Gold Smith Street,Veerapathira Garden, Muniram Pandy Street, Sesha Chala Garden and Nainiappan lanes in Division -48, Zone-4.",Own Sources,4,2016-17,2017-18 L/2016-17/18234,Electrical,Completed,L-Electrical,48,725900,"Replacement of 1673 Mtrs of 2x16 Sqmm Cable at East Cementry Road in Division -48, Zone-4.",Own Sources,4,2016-17,2018-19 L/2016-17/18238,Electrical,Completed,L-Electrical,48,928500,"Replacement of 2189 Mtrs of 2x16 Sqmm Cable at Solaiappan Streets and lanes, Subburayalu Street, Avathana Ramasamy Street in Division -48, Zone-4.",Own Sources,4,2016-17,2018-19 L/2016-17/18240,Electrical,Completed,L-Electrical,48,991200,"Replacement of 2404 Mtrs of 2x16 Sqmm Cable at Nallappa Vathiyar Street,Telegu Chetty Street,Pondicherry Murugesan Street, Valluvan Street and Andiyappan Street in Division -48, Zone-4.",Own Sources,4,2016-17,2018-19 L/2016-17/18242,Electrical,Completed,L-Electrical,48,840700,"Replacement of 1802 Mtrs of 2x16 Sqmm Cable at Bommi Sivaramanlu Street and Mottai Garden 1 to 12th Street in Division -48, Zone-4.",Own Sources,4,2016-17,2018-19 ND/2016-17/10050,Roads,Completed,ND-TONDIARPET,48,817623,"RELAYING OF ROAD WITH PAVER FINISHER AT NAINIYAPPAN ST IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/10067,Roads,Completed,ND-TONDIARPET,48,1230857,"Relaying of B.T.Course by Paver Finisher at Telugu Street in Div-48, Unit-11,Zone-4",Own Sources,4,2016-17,2016-17 ND/2016-17/11463,Buildings,Completed,ND-TONDIARPET,48,980000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period in PARTHASARATHY ST Dn 48, UNIT-11- Zone -4.",Own Sources,4,2016-17,2019-20 ND/2016-17/13162,Roads,Completed,ND-TONDIARPET,48,840000,"Widening the Road at Solaiyappan 2nd and 3rd Street in DN -48, Unit - 11, Zone -04",Own Sources,4,2016-17,2016-17 ND/2016-17/13165,Roads,Completed,ND-TONDIARPET,48,800000,"Widening at MANNAPPAN LANE in DN -48, Unit - 11, Zone -04",Own Sources,4,2016-17,2016-17 ND/2016-17/13166,Roads,Completed,ND-TONDIARPET,48,900000,"Widening the Road at PARTHASARATHY 3RD STREET AND SOLAIYAPPAN 1st ST in DN -48, Unit - 11, Zone -04",Own Sources,4,2016-17,2016-17 ND/2016-17/13167,Roads,Completed,ND-TONDIARPET,48,810000,"Widening Road at KURASAN street in DN -48, Unit - 11, Zone -04",Own Sources,4,2016-17,2016-17 ND/2016-17/13168,Buildings,Completed,ND-TONDIARPET,48,940000,Widening the road at Mottai Thottam 1st and 2nd street in Div - 48 Unit-11 Zone-4,Own Sources,4,2016-17,2016-17 ND/2016-17/13169,Roads,Completed,ND-TONDIARPET,48,900000,"Widening the road at Parthasarathy 4th Street in DN -48, Unit - 11, Zone -04",Own Sources,4,2016-17,2016-17 ND/2016-17/13177,Roads,Completed,ND-TONDIARPET,48,610000,"WIDENING ROAD PORTION AT PARTHASARATHY ST IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2016-17,2016-17 ND/2016-17/13179,Roads,Completed,ND-TONDIARPET,48,680000,"WIDENING ROAD PORTION AT MINT SUBBU������������������LU ST IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2016-17,2016-17 ND/2016-17/13180,Roads,Completed,ND-TONDIARPET,48,860000,"WIDENING ROAD PORTION AT MUTHIYA STREET IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2016-17,2016-17 ND/2016-17/13181,Roads,Completed,ND-TONDIARPET,48,525000,"WIDENING ROAD PORTION AT ARUMUGAM STREET IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2016-17,2016-17 ND/2016-17/13183,Buildings,Completed,ND-TONDIARPET,48,465000,Widening the road ortion at Mannappan Street in Div - 48 Unit -11 Zone -4,Own Sources,4,2016-17,2016-17 ND/2016-17/13184,Roads,Completed,ND-TONDIARPET,48,485000,"WIDENING ROAD PORTION AT ANDIYAPPAN STREET IN DN.48, UNIT.11, ZONE.4",Own Sources,4,2016-17,2016-17 ND/2016-17/13265,Buildings,Completed,ND-TONDIARPET,48,760000,"Construction of sump and Metal Sheet Roof Covering For Amma Kudineer in Dn-48, Un-11, Zn-IV",Own Sources,4,2016-17,2016-17 ND/2016-17/15324,Buildings,Completed,ND-TONDIARPET,48,248000,"IMPROVEMENT OF I.C.D.S CENTER NO 208,209 ;IN PARTHASARATHY STREET IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/15327,Buildings,Completed,ND-TONDIARPET,48,248000,"IMPROVEMENT OF I.C.D.S CENTER NO;210 IN PARTHASARATHY STREET IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/15331,Buildings,Completed,ND-TONDIARPET,48,248000,"IMPROVEMENT OF I.C.D.S IN CENTER NO;215 AT ANDIYAPPAN ST IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/15333,Buildings,Completed,ND-TONDIARPET,48,248000,"IMPROVEMENT OF I.C.D.S CENTER NO;207,211 IN PARTHASARATHY STREET IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2016-17,2017-18 ND/2016-17/15848,Footpath,Completed,ND-TONDIARPET,48,235000,"REPAIRING FOR WEIGH BRIDGE AND DIGITAL WEIGHT INDICATER @ TPF IN DN-48, U-11, Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/16190,Buildings,Completed,ND-TONDIARPET,48,44000,"REPAIRS FOR WATER SUPPLY, DRAINAGE ARRANGEMENTS DUE TO VARDHA CYCLONE IN ICDS @ PARTHASARATHY ST IN DN-48, U-11, Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/16194,Buildings,Completed,ND-TONDIARPET,48,44000,"REPAIRS FOR DAMAGED A.C SHEET ROOF IN E SEVA @ PARTHASARATHY ST IN DN-48, U-11, Z-4(DUE TO VARDHA CYCLONE )",Own Sources,4,2016-17,2017-18 ND/2016-17/16197,Buildings,Completed,ND-TONDIARPET,48,44600,"REPAIRS FOR DAMAGED DOORS, WINDOWS AND WATER SUPPLY IN HOSPITAL @ T.H ROAD IN DN-48, U-11, Z-4(DUE TO VARDHA CYCLONE )",Own Sources,4,2016-17,2017-18 ND/2016-17/16204,Buildings,Completed,ND-TONDIARPET,48,42000,"REPAIRS FOR WATER SUPPLY, DRAINAGE ARRANGEMENTS IN HOSPITAL @ VENKATA KRISHNAN STREET IN DN-48, U-11, Z-4(DUE TO VARDHA CYCLONE )",Own Sources,4,2016-17,2017-18 ND/2016-17/16207,Buildings,Completed,ND-TONDIARPET,48,43400,"REPAIRS FOR DAMAGED DOOR, WINDOS,AND WATER SUPPLY IN DENTAL HOSPITAL @ T.H ROAD IN DN-48, U-11, Z-4( DUE TO VARDHA CYCLONE)",Own Sources,4,2016-17,2017-18 ND/2016-17/16213,Buildings,Completed,ND-TONDIARPET,48,44200,"REPAIRS FOR WATER SUPPLY, DRAINAGE ARRANGEMENTS DUE TO VARDHA CYCLONE IN MULTIPURPOSE HALL @ KANNI KOVIL STREET IN DN-48, U-11, Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/16219,Buildings,Completed,ND-TONDIARPET,48,87000,"REPAIRS FOR DAMAGED DOORS,WINDOWS ,WATER SUPPLY,AND DRAINAGE ARRANGEMENTS IN SI STORE ROOM @ RAMANUJAM STREET IN DN-48, U-11, Z-4(DUE TO VARDHA CYCLONE)",Own Sources,4,2016-17,2017-18 ND/2016-17/16220,Buildings,Completed,ND-TONDIARPET,48,89300,"REPAIRS FOR DAMAGED DOORS,WINDOWS AND WATER SUPPLY IN CMS @ BUDHA STREET IN DN-48, U-11, Z-4(DUE TO VARDHA CYCLONE)",Own Sources,4,2016-17,2017-18 ND/2016-17/16222,Buildings,Completed,ND-TONDIARPET,48,88000,"REPAIRS FOR DOORS ,WINDOWS AND WATER SUPPLY IN CMS @ NAINIYAPPAN STREET IN DN-48, U-11, Z-49DUE TO VARDHA CYCLONE)",Own Sources,4,2016-17,2017-18 ND/2016-17/16286,Buildings,Completed,ND-TONDIARPET,48,221000,"REPAIRS FOR COMPOUND WALL DUE TO VARDHA CYCLONE IN UNIT OFFICE @ PARTHASARATHY ST IN DN-48, U-11, Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/4087,Storm Water Drain,Completed,ND-TONDIARPET,48,305000,"DE SILTING OF STORM WATER DRAIN OF PARTHASARTHY STREET IN DN-48, U-11, Z-4",Own Sources,4,2016-17,2017-18 ND/2016-17/4095,Storm Water Drain,Completed,ND-TONDIARPET,48,71000,"DE SILTING OF STORM WATER DRAIN AT PARTHASARATHY 1 ST STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4097,Storm Water Drain,Completed,ND-TONDIARPET,48,52000,"DE SILTING OF STORM WATER DRAIN AT PARTHASARATHY 2 ND STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4099,Storm Water Drain,Completed,ND-TONDIARPET,48,158000,"DE SILTING OF STORM WATER DRAIN AT DBK STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4104,Storm Water Drain,Completed,ND-TONDIARPET,48,315000,"DE SILTING OF STORM WATER DRAIN AT MUTHAIYA STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4106,Storm Water Drain,Completed,ND-TONDIARPET,48,245000,"DE SILTING OF STORM WATER DRAIN AT NAINIYAPPAN STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4109,Storm Water Drain,Completed,ND-TONDIARPET,48,85000,"DE SILTING OF STORM WATER DRAIN AT ULARAMMAN KOIL STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4110,Storm Water Drain,Completed,ND-TONDIARPET,48,295000,"DE SILTING OF STORM WATER DRAIN AT MANNAPPAN STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/4112,Storm Water Drain,Completed,ND-TONDIARPET,48,71000,"DE SILTING OF STORM WATER DRAIN AT THULASINGAM STREET IN DN-48, U-11, Z-4.",Own Sources,4,2016-17,2017-18 ND/2016-17/5731,Roads,Completed,ND-TONDIARPET,48,971000,"PROVIDING AND FIXING STREET NAME BOARD FURNITURE AT VARIOUS STREET (UNDER WARD MEMBER DEVELOPMENT SCHEME 2016-17) IN DIV-48, UNIT-11, ZONE-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5739,Roads,Completed,ND-TONDIARPET,48,990000,"Improvement to CC Roads at Parasarthy Lane, Ammayappan Lane and DPK Lane in Dn-48, Unit-11, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5749,Roads,Completed,ND-TONDIARPET,48,990000,"Improvement to CC Roads at Solaiyappan Lane, and Avathanam Lane in Dn-48, Unit-11, Zone-4.",Own Sources,4,2016-17,2016-17 ND/2016-17/5766,Buildings,Completed,ND-TONDIARPET,48,217200,"REPAIRS FOR DAMAGED ROOF & WATER SUPPLY, IN AMMA CANTEEN @ BOMMI SIVA RAMULU STREET IN DN-48, U-11, Z-4.(DUE TO VARDHA CYCLONE)",Own Sources,4,2016-17,2017-18 ND/2016-17/5772,Buildings,Completed,ND-TONDIARPET,48,197000,"REPAIRS FOR DAMAGED ROOF & WATER SUPPLY, DRAINAGE ARRANGEMENTS IN AMMA CANTEEN @ KANNI KOIL STREET IN DN-48, U-11, Z-4.(DUE TO VARDHA CYCLONE )",Own Sources,4,2016-17,2017-18 ND/2016-17/9163,Buildings,Completed,ND-TONDIARPET,48,880000,PAINTING AND WRITING LETTERS TO COMPACTOR BIN AT VARIOUS PLACES IN DN.44 TO 48 UNIT.11 ZONE.4,Own Sources,4,2016-17,2016-17 BR/2016-17/8808,Roads,Completed,BR-Bus Route Roads,49,980000,"Supplying and fixing of Front facia & Back drop in the stainless steel Bus shelter at various bus route roads in zone - 4 , 5 & 6.",Own Sources,5,2016-17,2018-19 NE/2016-17/10722,Storm Water Drain,Completed,NE-ROYAPURAM,49,950000,"Desliting to Storm Water Drain at Various Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/13843,Buildings,Completed,NE-ROYAPURAM,49,2480000,"Construction of Multipurpose Hall adjoining of Amma Unavagam in First Floor at Thadavarayan ( G ) Street in Ward-49, Unit -12, Zone-5",Earmarked Fund,5,2016-17,2017-18 NE/2016-17/13901,Buildings,Completed,NE-ROYAPURAM,49,900000,"REPAIR AND MAINTENANCE OF PUBLIC CONVENIENCE AT DIVISION 49 AND 50,UNIT-12,ZONE-5",Own Sources,5,2016-17,2018-19 NE/2016-17/14248,Roads,Completed,NE-ROYAPURAM,49,107000,"Improvement to CHS at Appasamy Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2019-20 NE/2016-17/14249,Buildings,Completed,NE-ROYAPURAM,49,43000,"Improvement to CPS at Appasamy Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2019-20 NE/2016-17/16427,Buildings,Completed,NE-ROYAPURAM,49,382000,"Improvement to Chennai Hr.Sec. School Roofing in Appasamy Street ( Damaged on vardha Cyclone) in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/17087,Roads,Completed,NE-ROYAPURAM,49,778000,"Attending Patches work on damaged Vardha cyclone Kappal polu Street and Sanjevarayan Koil Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/17090,Roads,Completed,NE-ROYAPURAM,49,880000,"Attending Patches work on damaged Vardha cyclone at Solaiappan Street and Sri Rangammal Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/17091,Roads,Completed,NE-ROYAPURAM,49,424000,"Attending Patches work on damaged Vardha cyclone at Somu 1st street and Somu 2nd Street in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/2861,Roads,Completed,NE-ROYAPURAM,49,970000,"Relaying B.T Road concrete Road at Kappal Polu Street From Junction Balu Street Under Concuilor Scheme in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/2868,Roads,Completed,NE-ROYAPURAM,49,973000,"Relaying B.T Road concrete Road at Kappal Polu Street From Junction Bala Arunachalam Street Under Concuilor Scheme in Ward-49, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/2872,Buildings,Completed,NE-ROYAPURAM,49,996000,"Additional Improvement to Amma Unavagam at Thandavarayan (G) Street under Conculior Scheme in ward-49, unit-12, zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/9714,Roads,Completed,NE-ROYAPURAM,49,900000,"Painting Footpath at Rajaji Salai, Kamaraj Salai, Flag Staff Road, North Fort Road in ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2017-18 L/2016-17/13427,Electrical,Completed,L-Electrical,50,814900,"Supply and Erection of 15 nos of damaged Kiosk type pillar box at various locations in Div 49,50,52,53, 55,56 and 60 in Zone V",Own Sources,5,2016-17,2016-17 L/2016-17/14552,Electrical,Completed,L-Electrical,50,592100,"Replacement of 500 Nos of damaged 2 core SMC fuse boxes and 100 Nos of 4 core SMC fuse boxes at various location in Division 49,50,52,53,55,56 and 60 in Zone-05.",Own Sources,5,2016-17,2017-18 NE/2016-17/10318,Roads,Completed,NE-ROYAPURAM,50,848000,"Relaying the road by Paver finisher at Madha church street in Ward-50, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/12076,Storm Water Drain,Completed,NE-ROYAPURAM,50,950000,Desilting to storm water drain at various street inward.50 unit.12 zone.5,Own Sources,5,2016-17,2016-17 NE/2016-17/14682,Buildings,Completed,NE-ROYAPURAM,50,150000,Repairs and maintanance to corporation urudhu school at arthoon road in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2019-20 NE/2016-17/14842,Buildings,Completed,NE-ROYAPURAM,50,120000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO TWO LOCATIONS E TOILETS AT S.N.CHETTY STREET IN DN-50,UNIT-12, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/14843,Buildings,Completed,NE-ROYAPURAM,50,85000,"REPAIRS AND IMPROVEMENTS AND WATER SUPPLY ARRANGEMENTS TO PUBLIC CONVENIENCE AT A.J.COLONY IN DN-50, UNIT-12, ZONE-06",Own Sources,5,2016-17,2018-19 NE/2016-17/14844,Buildings,Completed,NE-ROYAPURAM,50,219000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT S.N.CHETTY STREET IN DN-50. UNIT-12, ZONE-06",Own Sources,5,2016-17,2018-19 NE/2016-17/14870,Buildings,Completed,NE-ROYAPURAM,50,150000,Repairs to corporation middle school at durai street in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2019-20 NE/2016-17/14874,Buildings,Completed,NE-ROYAPURAM,50,150000,Repairs to corporation high school at S.N chetty street in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2019-20 NE/2016-17/15375,Buildings,Completed,NE-ROYAPURAM,50,140000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT VENGATESAN STREET IN DN-50, UNIT-12, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/15376,Buildings,Completed,NE-ROYAPURAM,50,126000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT EAST MADHA KOIL 10TH LANE IN DN-50, UNIT-12, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/15377,Buildings,Completed,NE-ROYAPURAM,50,56000,"PROVIIDNG WATER SUPPLY ARRANGEMENTS TO CORPORATION SCHOOL AT S.N.CHETTY STREET IN DN-50, UNIT-12, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/15378,Buildings,Completed,NE-ROYAPURAM,50,156000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM CHAPPATHY CENTER AND E SEVA CENTER IN DIVISION OFFICE CAMPUS AT KALMANDDABAM ROAD IN DN-50, UNIT-12, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/16126,Parks,Completed,NE-ROYAPURAM,50,550000,GREENER ARRANGEMENT TO KAMARAJAR PARK AT SURIYANARAYANA STREET AND VENKATESAN STREET PARK IN DIV-50 UNIT-12 ZONE-5,Own Sources,5,2016-17,2017-18 NE/2016-17/16127,Parks,Completed,NE-ROYAPURAM,50,967000,Greenery Arrangement to N R T Park at N R T Service road in Div -50 unit-12 Zone-5,Own Sources,5,2016-17,2017-18 NE/2016-17/16290,Buildings,Completed,NE-ROYAPURAM,50,183000,Improvements to AMMA unavagam at S.N Street & M.S Street ( Due to vardha cyclone) in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2017-18 NE/2016-17/16294,Buildings,Completed,NE-ROYAPURAM,50,72000,Repairs and improvements to public convenience at north madha street & S.N street. ( Due to vardha cyclone) in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2017-18 NE/2016-17/16487,Buildings,Completed,NE-ROYAPURAM,50,27000,Improvements to sundaramoorthy park at venkatesan street in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2017-18 NE/2016-17/16491,Buildings,Completed,NE-ROYAPURAM,50,242000,Repairs to kamaraj park (3 nos) at suryanarayana street in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2017-18 NE/2016-17/16497,Buildings,Completed,NE-ROYAPURAM,50,89000,Repairs and improvements to division office ( Due to vardha cyclone) at east kalmandapam road in ward.50 unit.12 zone.5,Own Sources,5,2016-17,2017-18 NE/2016-17/17073,Footpath,Completed,NE-ROYAPURAM,50,664000,"Improvements to foot path at Arthoon road, M.S. Koil Street, S.N. Chetty Street and West Madha Church Street, East Madha Street in ward.50 unit.12 zone.5 ( Due to vardha cyclone)",Own Sources,5,2016-17,2017-18 NE/2016-17/3012,Buildings,Completed,NE-ROYAPURAM,50,997000,"Construction of Ladies GYM at Sheik Masitry Street in Ward-50, Unit-12, Zone-5 (Under Ward Development Scheme)",Own Sources,5,2016-17,2016-17 NE/2016-17/3016,Buildings,Completed,NE-ROYAPURAM,50,995000,"Providing Water Supply arrangements and drainage arrangement and other works to Ladies GYM at Sheik Masitry Street in Ward-50, Unit-12, Zone-5 (Under Ward Development Scheme)",Own Sources,5,2016-17,2016-17 NE/2016-17/3036,Buildings,Completed,NE-ROYAPURAM,50,560000,"Improvements to Road side park at A.J Colony Main Street and Venkatesan Street in Ward-50, Unit-12, Zone-V (Under Ward Development Scheme)",Own Sources,5,2016-17,2016-17 NE/2016-17/3040,Buildings,Completed,NE-ROYAPURAM,50,545000,"Providing Modern GYM Equipment's for (Ladies Gym) at Sheik Masitry Street in ward-50, unit-12, zone-5 (Under Ward Councillor Scheme)",Own Sources,5,2016-17,2016-17 NE/2016-17/3813,Roads,Completed,NE-ROYAPURAM,50,940000,"PAINTING AND IMPROVEMENTS TO FOOD PATH AT CEMETRY ROAD IN DIV-50,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/4075,Buildings,Completed,NE-ROYAPURAM,50,428000,"REPAIRS AND IMPROVEMENTS TO COMMUNITY HALL AT CANAL STREET AND NNMP SHED , CMS AT PADAVETTAMMAN KOIL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/4076,Buildings,Completed,NE-ROYAPURAM,50,485000,"REPAIRS AND IMPROVEMENTS TO MULTI PURPOSE HALL AT P.P.AMMAN KOIL STREET AND GYM BUILDING, MULTI PURPOSE HALL AT CANAL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/4077,Buildings,Completed,NE-ROYAPURAM,50,490000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT B.B.ROAD AND TAX COLLECTOR ROOM, NNMP SHED AT DR.V.R.ROAD AND ANDHRA BUS STAND PARK AT WALTAX ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/5469,Roads,Completed,NE-ROYAPURAM,50,997000,"Painting to Royapuram New Bridge in Dn-50,Unit-12,Zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/7061,Roads,Completed,NE-ROYAPURAM,50,870000,"IMPROVEMENTS TO FOOD PATH AT CEMETRY ROAD IN DIV-52,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/7062,Roads,Completed,NE-ROYAPURAM,50,890000,"Painting to Royapuram New Bridge in Dn-50,Unit-12,Zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/7931,Roads,Completed,NE-ROYAPURAM,50,980000,"Painting to Centermedian and footpath from MS koil street to Sn chetty street in dn-50,U-12,Z-05.",Own Sources,5,2016-17,2016-17 NE/2016-17/8684,Roads,Completed,NE-ROYAPURAM,50,200000,"Providing Cement Concrete Patch Works and Speed Break at Various Street in Dn-50, Unite-12, Zone-5",Own Sources,5,2016-17,2018-19 NE/2016-17/10373,Roads,Completed,NE-ROYAPURAM,51,951000,"Laying of B.T. Road by Paver Finisher at N.N.Garden 8th Street in Dn-51, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10376,Roads,Completed,NE-ROYAPURAM,51,458000,"Laying of B.T. Road by Paver Finisher at South Cemetry Road in Dn-51, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10388,Roads,Completed,NE-ROYAPURAM,51,774000,"Laying of B.T. Road by Paver Finisher at East Cemetry Road in Dn-51, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10389,Roads,Completed,NE-ROYAPURAM,51,1040000,"Laying of B.T. Road by Paver Finisher at West Cemetry Street in Dn-51, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10390,Roads,Completed,NE-ROYAPURAM,51,705000,"Laying of B.T. Road by Paver Finisher at Narayanappan Street in Dn-51, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/13905,Storm Water Drain,Completed,NE-ROYAPURAM,51,539000,"DESILTING OF STORM WATER DRAIN AT NARAYANAPPAN STREET,EAST CEMENTRY ROAD,WEST CEMENTRY ROAD,THULUKANAM STREET AND KALINGARAYAN STREET IN DN-51,UNIT-12,ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/14294,Buildings,Completed,NE-ROYAPURAM,51,195000,"Improvement to P.C at N.N.garden 8th street In ward-51, Unit-12, Zone-5",Own Sources,5,2016-17,2019-20 NE/2016-17/14673,Buildings,Completed,NE-ROYAPURAM,51,698000,"Repairs and Maintainance work in Chennai Urdu High School in East Cemetry Road in Div 51,Unit 12,Zone 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/15922,Buildings,Completed,NE-ROYAPURAM,51,441000,"Repairs to the compound wall in Chennai primary school damaged during vardha cyclone in Cemetry road in Div 51,Unit 12,Zone 5.",Own Sources,5,2016-17,2017-18 NE/2016-17/15923,Roads,Completed,NE-ROYAPURAM,51,37000,"Providing Name Boards in Bishop Lane,Manikandan 4th Street,N.N.Garden 3rd Street damaged in Vardha cyclone in Div 51,Unit 12,Zone 5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16032,Buildings,Completed,NE-ROYAPURAM,51,35000,"Repairs to the damages caused by Vardha Cyclone in Road Side Park located in Cemetry Road and Sanjeevarayan Koil Street in Div 51,Unit 12 Zone 5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16068,Roads,Completed,NE-ROYAPURAM,51,553000,"DESILTING OF STORM WATER DRAIN AT N.N GARDEN 8 TH LANE ,NARASAIAR STREET,RAMANUJAM STREET,JANDARA PILLAIYAR KOIL SREET AND VADIVELU STREET IN DN-51,UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/16254,Buildings,Completed,NE-ROYAPURAM,51,387000,"Repairs to the damages caused during Vardha Cyclone in Unit Office Building and Amma Unavagam in Perambalu Chetty Street in Div 51,Unit 12,Zone 5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16260,Buildings,Completed,NE-ROYAPURAM,51,772000,"Providing roof in First floor in Front side building and rectification of damages in toilet block during Vardha Cyclone in CMS Sanjeevarayan Koil Street in Div 51,Unit 12,Zone 5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17059,Footpath,Completed,NE-ROYAPURAM,51,212000,"Repairs to the footpath in Manikandan 9th Street (Vadivel Street) in Div 51,Unit 12,Zone 5.",Own Sources,5,2016-17,2017-18 NE/2016-17/2818,Roads,Completed,NE-ROYAPURAM,51,364000,"Relaying of Bituminous road in Manikandan 9th Street (Vadivel Street ) using Paver Finisher under WDS in Div 51,Unit 12,Zone 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/3264,Roads,Completed,NE-ROYAPURAM,51,778000,"Relaying of Bituminous road in Narayanappan street using paver finisher under WDS in Div 51, Unit 12 ,Zone 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/3265,Roads,Completed,NE-ROYAPURAM,51,826000,"Relaying of Bituminous Road in East Cemetry Road using paver finisher Under WDS in Div 51 , Unit 12 , Zone 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/3266,Roads,Completed,NE-ROYAPURAM,51,996000,"Relaying of Bituminous road in Kalingarayan Street using Paver finisher Under WDS in Div 51, Unit 12,Zone -5.",Own Sources,5,2016-17,2019-20 BR/2016-17/17650,Roads,Completed,BR-Bus Route Roads,52,1909000,"Attending temporary repairs to damaged roads due to Vardha Cyclone in North East Monsoon 2016 NRT Bridge Road, Thiru narayanaguru salai , Pantheon Road, Bharathi Salai in Zone 5",Own Sources,5,2016-17,2017-18 BR/2016-17/6654,Roads,Completed,BR-Bus Route Roads,52,5275000,"Laying of cement concrete road with M40 Concrete at Cementry road from RSRM Hospital to Manikandan 8th Street in div 52, Zone -05.",Grants,5,2016-17,2017-18 NE/2016-17/10321,Roads,Completed,NE-ROYAPURAM,52,1972000,"Relaying of road by Paver finisher at O.S.H. Road in Ward-52, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10340,Roads,Completed,NE-ROYAPURAM,52,837000,"Relaying of road by Paver finisher at Rama street in Ward-52, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10392,Roads,Completed,NE-ROYAPURAM,52,424000,"Laying of B.T. Road by Paver Finisher at Munusamy Garden 3rd Lane in Dn-52, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10399,Roads,Completed,NE-ROYAPURAM,52,246000,"Laying of B.T. Road by Paver Finisher at Jaganathan Street in Dn-52, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10402,Roads,Completed,NE-ROYAPURAM,52,223000,"Laying of B.T. Road by Paver Finisher at Robinson Park Colony 2nd Lane in Dn-52, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10716,Roads,Completed,NE-ROYAPURAM,52,124000,"Laying of C.C. Road with RMC M30 at Velayudhapandian Lane in Ward-52, Unit-12, Zone-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/10717,Roads,Completed,NE-ROYAPURAM,52,115000,"Laying of C.C. Road with RMC M30 at Adam street in Ward-52, Unit-12, Zone-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/10718,Roads,Completed,NE-ROYAPURAM,52,331000,"Laying of C.C. Road with RMC M30 at B.C. Press road 3rd lane in Ward-52, Unit-12, Zone-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/10719,Roads,Completed,NE-ROYAPURAM,52,149000,"Laying of C.C. Road with RMC M30 at B.C. Press road 1st lane in Ward-52, Unit-12, Zone-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/10780,Roads,Completed,NE-ROYAPURAM,52,521000,"Laying of C.C. Road with RMC M30 at Kannabiran koil street in Dn.52,Unit-12,Zone-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/10786,Roads,Completed,NE-ROYAPURAM,52,318000,"Laying of C.C. Road with RMC M30 at Kabila gananathar koil street in Dn.52,Unit-12,Zone-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/14856,Buildings,Completed,NE-ROYAPURAM,52,55000,"REPAIRS AND IMPROVEMENT TO THE CPS @ O.S.H ROAD IN DN-52, U-12, Z-5",Own Sources,5,2016-17,2019-20 NE/2016-17/14858,Buildings,Completed,NE-ROYAPURAM,52,85000,"REPAIR AND IMPROVEMENTS TO CTHS AT OSH ROAD IN DN-52,U-12,Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/16124,Parks,Completed,NE-ROYAPURAM,52,1738000,Greenery Arrangement to Anna park at Cementry Road in Div-52 unit-12 Zone-5,Own Sources,5,2016-17,2017-18 NE/2016-17/16125,Parks,Completed,NE-ROYAPURAM,52,443000,Greenery Arrangement to Basement Park at M C Road in Div-52 unit-12 Zone-5,Own Sources,5,2016-17,2017-18 NE/2016-17/16300,Parks,Completed,NE-ROYAPURAM,52,3191000,"IMPROVEMENTS TO COMPOUND WALL,PATHWAYS, PLAY AREA, GREENARIES INSIDE THE ANNA PARK IN DN-52,U-12,Z-5.( DUE TO VARDHA CYCLONE AFFECTED)",Own Sources,5,2016-17,2017-18 NE/2016-17/16452,Buildings,Completed,NE-ROYAPURAM,52,165500,"Repairs and Improvements to front shed at rsrm and stanley hospital amma unavagam damaged during Vardha Cyclone in dn-52,u-12,z-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17590,Footpath,Completed,NE-ROYAPURAM,52,361000,"REPAIRS TO THE FOOTPATH DAMAGED DUE TO VARDHA CYCLONE AT NRT ROAD, M.S KOIL STREET, CEMETRY ROAD IN DN-52, UNIT-12, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/3584,Roads,Completed,NE-ROYAPURAM,52,998000,"PROVIDING STREET NAME BOARDS AT VARIOUS STREETS UNDER WARD COUNCILLORS SCHEME IN DN52,U12,Z5.",Own Sources,5,2016-17,2016-17 NE/2016-17/3591,Roads,Completed,NE-ROYAPURAM,52,999000,"LAYING BITUMINOUS COURSE AT VELAYTHA PANDIAN STREET UNDER WARD COUNCILLORS SCHEME IN DN52,U12,Z5.",Own Sources,5,2016-17,2016-17 NE/2016-17/3593,Roads,Completed,NE-ROYAPURAM,52,999000,"LAYING BITUMINOUS COURSE AT ROBINSON PARK COLONY AND ROBINSON PARK COLONY 1ST LANE UNDER WARD COUNCILLORS SCHEME IN DN52,U12,Z5.",Own Sources,5,2016-17,2016-17 NE/2016-17/3709,Buildings,Completed,NE-ROYAPURAM,52,449000,"Providing water supply arrangement,electrical arrangements,platform arrangements,drainage arrangements, and roofing arrangements for AMMA DRINGWATER PROJECT inside annapark in dn-52,u-13,z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/3711,Playfields,Completed,NE-ROYAPURAM,52,480000,"Improvements the A cattle depot playground at osh road in dn-52,u-12,z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/4947,Roads,Completed,NE-ROYAPURAM,52,980000,"ATTENDING THE PATCH WORK BY PAVER FINISHER AT THOPPAI STREET, ANDIAPPAN STREET AND VARIOUS ROAD IN DN -52 UN-12 Zone-V",Own Sources,5,2016-17,2016-17 NE/2016-17/4948,Roads,Completed,NE-ROYAPURAM,52,980000,"ATTENDING THE PATCH WORK BY PAVER FINISHER AT RAMA NAICKEN STREET, RABINSON ROAD AND VARIOUS STREET IN DN -52 UN-12 Zone-V",Own Sources,5,2016-17,2016-17 NE/2016-17/5476,Roads,Completed,NE-ROYAPURAM,52,997000,"Painting to Royapuram Old Bridge in Dn-52,Unit-12,Zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/7015,Roads,Completed,NE-ROYAPURAM,52,992000,"Attending Patches Work at M.C Road and OSH Road in Ward-52, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/7016,Buildings,Completed,NE-ROYAPURAM,52,874000,"urgent repairs to pcs at old jail road,osh road,thoppai st, chemntry road, jaganatan st etc Work at Various Street in Ward-52, Unit-12, Zone-5",Own Sources,5,2016-17,2019-20 NE/2016-17/7064,Roads,Completed,NE-ROYAPURAM,52,990000,"Painting to Royapuram Old Bridge and providing greenary arrangements in NRT bridge in Dn-52,Unit-12,Zone-05",Own Sources,5,2016-17,2016-17 B/2016-17/14479,Buildings,Completed,B-Buildings,53,5000000,CONSTRUCTION OF ADDITIONAL TWO CLASS ROOMS AND TOILETS IN FIRST FLOOR AT CHENNAI MIDDLE SCHOOL PADAVETTAMAN KOIL STREET IN DIV-53 UNIT-12 ZONE-5,MLACDS,5,2016-17,2017-18 BR/2016-17/10450,Storm Water Drain,Completed,BR-Bus Route Roads,53,5840000,Strengthening and relaying the road with DBM and CBC after cold milling by paver finishing using plastic waste along with traffic improvements at Dr. Vijayaragavalu Salai in div 53 Zone -05.,Grants,5,2016-17,2017-18 BR/2016-17/18485,Road Cut,Completed,BR-Bus Route Roads,53,2415500,Restoration of Road cut at Cochraine Basin Road made byTRANTRANSCO - From junction of Basin Bridge road to CB road 3 rd lane in Division -53 Zone - 5,Deposit Works,5,2016-17,2018-19 BR/2016-17/18513,Road Cut,Completed,BR-Bus Route Roads,53,2465000,Restoration of Road cut at Cochraine Basin Road made byTRANTRANSCO - From CB road 3 rd lane to Anandanayak nagar 1 st street in Division -53 Zone - 5,Deposit Works,5,2016-17,2017-18 L/2016-17/13412,Electrical,Completed,L-Electrical,53,857500,"Supply and Erection of 16 nos of damaged Kiosk type pillar box at various locations in Div 53 , 54 , 55 and 57 in Zone V",Own Sources,5,2016-17,2016-17 L/2016-17/18815,Electrical,Completed,L-Electrical,53,165900,"Removal and Re-Erection of 30 mtrs Highmast at kannan rountana in Div 53 ,Unit - 12, Zone - 5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10349,Roads,Completed,NE-ROYAPURAM,53,401000,"Relaying of road by Paver finisher at Pensioners 3rd street in Ward-53, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10351,Roads,Completed,NE-ROYAPURAM,53,1218000,"Laying of B.T. Road by Paver Finisher at Pensioners 4th Street in Dn-53, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10352,Roads,Completed,NE-ROYAPURAM,53,1195000,"Relaying of road by Paver finisher at Kathiwakkam high road in Ward-53, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10353,Roads,Completed,NE-ROYAPURAM,53,2138000,"Relaying of road by Paver finisher at Kathbada main road in Ward-53, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10355,Roads,Completed,NE-ROYAPURAM,53,1238000,"Laying of B.T. Road by Paver Finisher at Canal Street in Dn-53, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10357,Roads,Completed,NE-ROYAPURAM,53,215000,"Relaying of road by Paver finisher at Pensioners 1st street in Ward-53, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10362,Roads,Completed,NE-ROYAPURAM,53,200000,"Relaying of road by Paver finisher at Pensioners 1st cross street in Ward-53, Unit-12, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10365,Roads,Completed,NE-ROYAPURAM,53,1212000,"Laying of B.T. Road by Paver Finisher at Pensioners 2nd Cross Street in Dn-53, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10368,Roads,Completed,NE-ROYAPURAM,53,553000,"Laying of B.T. Road by Paver Finisher at T.H. Road in Dn-53, Unit-12, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10611,Buildings,Completed,NE-ROYAPURAM,53,989000,"REPAIRS AND IMPROVEMENTS TO TOILET BLOCK AND OTHER IMPROVEMENTS TO LORRY SHED (NORTH CHENNAI) AT B.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/1074,Roads,Completed,NE-ROYAPURAM,53,985000,"Laying Cement Concrete Patches at various Street in ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/1075,Roads,Completed,NE-ROYAPURAM,53,971000,"Attending B.T Patches at Kannan Street, Bojaraja Nagar in ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/1077,Roads,Completed,NE-ROYAPURAM,53,975000,"Attending B.T Patches at Stanly Nagar, C.B Road in ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/10981,Roads,Completed,NE-ROYAPURAM,53,350000,"Laying of C.C. Road with RMC M30 at Chidambaram Nagar 4th Street in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10983,Roads,Completed,NE-ROYAPURAM,53,349000,"Laying C.C.Road with RMC30 at New Labour lane South in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10984,Roads,Completed,NE-ROYAPURAM,53,786000,"Laying C.C.Road with RMC30 at New Labour lane North in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10986,Roads,Completed,NE-ROYAPURAM,53,689000,"Laying C.C.Road with RMC30 at New Labour lane Cross Street in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10988,Roads,Completed,NE-ROYAPURAM,53,2852000,"Laying C.C.Road with RMC30 at P.P. Amman koil West street in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10990,Roads,Completed,NE-ROYAPURAM,53,1195000,"Laying C.C.Road with RMC30 at P.P. Amman koil 1st lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10992,Roads,Completed,NE-ROYAPURAM,53,809000,"Laying C.C.Road with RMC30 at P.P. Amman koil 2nd lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10993,Roads,Completed,NE-ROYAPURAM,53,812000,"Laying C.C.Road with RMC30 at P.P. Amman koil 3rd lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10994,Roads,Completed,NE-ROYAPURAM,53,763000,"Laying C.C.Road with RMC30 at P.P. Amman koil 5th lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10995,Roads,Completed,NE-ROYAPURAM,53,841000,"Laying C.C.Road with RMC30 at P.P. Amman koil 6th lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10996,Roads,Completed,NE-ROYAPURAM,53,627000,"Laying C.C.Road with RMC30 at P.P. Amman koil 7th lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10997,Roads,Completed,NE-ROYAPURAM,53,398000,"Laying C.C.Road with RMC30 at P.P. Amman koil 8th lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10998,Roads,Completed,NE-ROYAPURAM,53,473000,"Laying C.C.Road with RMC30 at P.P. Amman koil 9th lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/10999,Roads,Completed,NE-ROYAPURAM,53,1478000,"Laying C.C.Road with RMC30 at Corporation Tenements Road in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11000,Roads,Completed,NE-ROYAPURAM,53,530000,"Laying C.C.Road with RMC30 at Bojaraja Nagar 1st lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11002,Roads,Completed,NE-ROYAPURAM,53,1103000,"Laying C.C.Road with RMC30 at Bojaraja Nagar South lane in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11003,Roads,Completed,NE-ROYAPURAM,53,1109000,"Laying C.C.Road with RMC30 at Bojaraja Nagar (Hut Area) in Dn.53,Unit-12,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/12913,Buildings,Completed,NE-ROYAPURAM,53,51500,"REPAIRS AND IMPROVEMENTS TO ICDS CENTER NO : 33603090217 AT DR.V.R.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/12915,Buildings,Completed,NE-ROYAPURAM,53,206000,"REPAIRS AND IMPROVEMNETS TO ICDS CENTER NO : 33603090227 AT SEENIVASAPURAM IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/12920,Buildings,Completed,NE-ROYAPURAM,53,206000,"REPAIRS AND IMPROVEMENTS TO ICDS CENTER NO : 33603090213 AND 33603090216 AT STANLEY NAGAR IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/13494,Roads,Completed,NE-ROYAPURAM,53,998000,"RELAYING THE ROAD WITH BCCMP AT KATHBADA STRAEET (PART 1) IN DN-53 U-12Z-5 044/2806/27569/2014-15",Own Sources,5,2016-17,2018-19 NE/2016-17/13495,Roads,Completed,NE-ROYAPURAM,53,997000,"RELAYING THE ROAD WITH BCCMP AT KATHBADA STRAEET (PART 2) IN DN-53 U-12Z-5 044/2806/27569/2014-15",Own Sources,5,2016-17,2018-19 NE/2016-17/13496,Roads,Completed,NE-ROYAPURAM,53,930000,"RELAYING THE ROAD WITH BCCMP AT KATHBADA STRAEET (PART 3) IN DN-53 U-12Z-5 044/2806/27569/2014-15",Own Sources,5,2016-17,2018-19 NE/2016-17/13497,Roads,Completed,NE-ROYAPURAM,53,997000,"RELAYING THE ROAD WITH BCCMP AT KATHBADA STREET (PART 4)IN D-53 U-12 Z-5 044/2806/27569/2014-15",Own Sources,5,2016-17,2018-19 NE/2016-17/13986,Buildings,Completed,NE-ROYAPURAM,53,327000,"REPAIRS AND IMPROVEMENTS TO FLOOD RELIEF CENTER AT PADAVETTAMMAN KOIL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2019-20 NE/2016-17/13988,Roads,Completed,NE-ROYAPURAM,53,222000,"PROVIDING PVC PIPE FIXING FOR WATER STAGNATION AREA AT P.P.AMMAN KOIL 8TH ST,PADAVETTAMMAN KOIL ST AND RAMDOSS NAGAR IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2019-20 NE/2016-17/13989,Roads,Completed,NE-ROYAPURAM,53,371000,"REPAIRS TO DIESEL MOTORS FOR STAGNATION OF RAIN WATER AT RAINING SEASON IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2019-20 NE/2016-17/14290,Buildings,Completed,NE-ROYAPURAM,53,722000,"Improvement to P.C Dr. Vijayaragavalu Road, Srinivasapuram ,2nd street, Bojaraja Nagar Main Street, kannan street, north wall road, V.O.C Salai, Canal Road,C.B.Road C.B.Road Female in ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/14293,Buildings,Completed,NE-ROYAPURAM,53,715000,"Improvement to P.C P.P.Amman koil street 2nd street, P.P.Amman koil, 4rd street, P.P.Amman koil,6TH Street, Kathpada Main Road, New Labour Line, Ramdoss Nagar,Kathivakkam main road, Pensioners 3rd Cross Street, T.H.road, Basin bridge Road, Basin Bridgre inside park in ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/14869,Buildings,Completed,NE-ROYAPURAM,53,668000,"Improvement to CHS, CPS School in C.B road, Chennai Primary School in Bojaraja Nagar in Kathivakkam Road in Ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2018-19 NE/2016-17/14872,Buildings,Completed,NE-ROYAPURAM,53,353000,"Improvement to Chennai Urdu Boys Primary Scool in Kathpada 3rd Cross Street, Chennai Middle School Padavattamman Street in Ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2019-20 NE/2016-17/14967,Buildings,Completed,NE-ROYAPURAM,53,314000,"DESILTING OF STORM WATER DRAIN AT SRINIVASAPURAM 1ST STREET,DR.VIJAYARAGAVALU SALAI,PARASURAM MUDALI SALAI,AZEEZ GOUSE MOHAMMED GOUS STREET,SAJAMUNUSAMY CHETTY STREET,THIRUVOTTIYUR HIGH ROAD,BOJARAJAN NAGAR MAIN STREET,1 ST STREET,2ND STREET AND SOUTH LANE IN DN-53,UNIT-12,ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16014,Roads,Completed,NE-ROYAPURAM,53,430812,"DESILTING OF STORM WATER DRAIN AT PARTHASARATHY SERVICE ROAD, PENSIONERS 3RD,4TH AND 3RD CROSS STREET ,KATHPADA MAIN ROAD ,BASIN BRIDGE ROAD,C.B ROAD,PADAVATTAMMAN KOIL STREET,PEDDU (N)STREET AND NORTH WALL ROAD IN DN-53,UNIT-12,ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16020,Roads,Completed,NE-ROYAPURAM,53,348000,"DESILTING OF STORM WATER DRAIN AT STANLY NAGAR 4 TH STREET,5TH STREET,6TH STREET,INSIDE ITI (KATHPADA MAIN ROAD) TPF ROAD (BB ROAD) PP AMMAN KOIL EAST STREET AND 1 ST LANE ,NN NAGAR,KANNAN STREET IN DN-53,UNIT-12,ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16081,Parks,Completed,NE-ROYAPURAM,53,339000,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN MINT MODERN CITY PARK IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16454,Buildings,Completed,NE-ROYAPURAM,53,20900,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN ICDS CENTRE IN Dr.VIJAYARAGAVALU ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16494,Buildings,Completed,NE-ROYAPURAM,53,128700,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN LORRY STATION AT BASIN BRIDGE ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16515,Buildings,Completed,NE-ROYAPURAM,53,9700,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN AMMAUNAVAGAM AT PADAVATAMMAN KOIL STREET IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16521,Buildings,Completed,NE-ROYAPURAM,53,39800,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN CHENNAI PRIMARY SCHOOL(PADAVATAMMAN SCHOOL) AT BASIN BRIDGE ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16531,Buildings,Completed,NE-ROYAPURAM,53,9600,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN RELIEF CENTRE AT PADAVATAMMAN KOIL STREET IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16571,Buildings,Completed,NE-ROYAPURAM,53,152000,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN 53 DIVISIONAL OFFICE AT Dr.VIJAYARAGAVALU ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16625,Buildings,Completed,NE-ROYAPURAM,53,134000,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN B-DEPO AT BASIN BRIDGE ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17084,Buildings,Completed,NE-ROYAPURAM,53,20400,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE IN LIBRARY AT Dr.V.R.ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17105,Buildings,Completed,NE-ROYAPURAM,53,490000,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE (UNDER BUILDING CATEGOERY) AT RDC(NORTH) OFFICE AT BASIN BRIDGE ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17106,Buildings,Completed,NE-ROYAPURAM,53,86000,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE (UNDER BUILDING CATEGOERY) AT GYM KATHPADA MAIN ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17119,Buildings,Completed,NE-ROYAPURAM,53,71300,"RECTIFICATION OF DAMAGE CAUSED BY VARADAH CYCLONE (UNDER BUILDING CATEGOERY) AT AMMA UNAVAGAM AT Dr.V.R.ROAD IN DIV53,UNIT-12,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17424,Footpath,Completed,NE-ROYAPURAM,53,517000,"Repairs to the Footpath damaged due to Vardha Cyclone at Kannan street & kathpada main road in Ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/17425,Footpath,Completed,NE-ROYAPURAM,53,517000,"Repairs to the Footpath damaged due to Vardha Cyclone at V.O.C Salai and pethu naicker street near police quaters in Ward-53, Unit-12, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/17694,Buildings,Completed,NE-ROYAPURAM,53,829000,"Dismantling & construction of New compound wall and formation of footpath under the flyover near mint tower clock at Basin Bridge road in Dn-53,Un-12,Zn-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/17696,Roads,Completed,NE-ROYAPURAM,53,879000,"Formation of base and Cement Concrete m15, m30 Grade Under the flyover near mint tower clock at Basin Bridge road in Dn-53,Un-12,Zn-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/19038,Bridges,Completed,NE-ROYAPURAM,53,687000,"Repairs works at Gasifire crematorium at Moolakothalam Burial Ground in Dn-53, Unit-12, Zone-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/2405,Buildings,Completed,NE-ROYAPURAM,53,988000,"CONSTRUCTION OF RAIN WATER SUMP WORK AND MOTOR ROOM AT C.B.ROAD SUBWAY IN DN-53, UNIT-12, ZONE-05 049/2791/23/2017-18",Own Sources,5,2016-17,2017-18 NE/2016-17/2406,Buildings,Completed,NE-ROYAPURAM,53,986000,"PROPOSED CONSTRUCTION OF SUMP WORK AND OTER IMPROVEMENTS TO RDC(NORTH) BUILDING CAMPUS AT B.B.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/2410,Buildings,Completed,NE-ROYAPURAM,53,770000,"IMPROVEMENTS TO NNMP SHED NO : 3360390218 DIVISION OFFICE CAMPUS AT DR.V.R.ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/2411,Buildings,Completed,NE-ROYAPURAM,53,770000,"IMPROVEMENTS TO NNMP SHED NO : 3360390207 CHENNAI CORPORATION URDU SCHOOL CAMPUS AT KATHBADA 3RD CROSS STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/2412,Buildings,Completed,NE-ROYAPURAM,53,935000,"IMPROVEMENTS TO NNMP SHED NO : 3360390213 AND 3360390216 CHENNAI CORPORATION HIGH SCHOOL CAMPUS AT STANLEY NAGAR IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/2413,Buildings,Completed,NE-ROYAPURAM,53,770000,"IMPROVEMENTS TO NNMP SHED NO : 3360390203 AND 90204 CHENNAI CORPORATION MIDDLE SCHOOL CAMPUS AT PADAVETTAMMAN KOIL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/3541,Roads,Completed,NE-ROYAPURAM,53,988000,"PAINTING BLACK AND WHITE TO THE FOOTPATH KERB AND PATCH WORK AT C.B. ROAD IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/4068,Roads,Completed,NE-ROYAPURAM,53,570000,"REPAIRS AND IMPROVEMENTS TO ROADS AT SEENIVASAPURAM IST STREET, POJARAJAN NAGAR MAIN ROAD AND LANES AND CMS AT PADAVETTAMMAN KOIL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/4189,Buildings,Completed,NE-ROYAPURAM,53,994000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM(PHASE II) NEAR MINT BUS STAND AT PADAVETTAMMAN KOIL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/4190,Buildings,Completed,NE-ROYAPURAM,53,995000,"ADDITIONAL CONSTRUCTION OF AMMA UNAVAGAM NEAR MINT BUS STAND AT PADAVETTAMMAN KOIL STREET IN DN-53, UNIT-12, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/4827,Roads,Completed,NE-ROYAPURAM,53,998000,"Supply and Fixing Reflective Name board at Various Street (14) on Two side in Ward-53, Unit-12, Zone-5 Under Conucilor Scheme",Own Sources,5,2016-17,2016-17 NE/2016-17/4829,Roads,Completed,NE-ROYAPURAM,53,997000,"Supply and Fixing Reflective Name board at Various Street (14) on Two side in Ward-53, Unit-12, Zone-5 Under Conucilor Scheme",Own Sources,5,2016-17,2016-17 NE/2016-17/4830,Storm Water Drain,Completed,NE-ROYAPURAM,53,998000,"Construction of SWD of Size 2' x 2'6 R.C.C. Drain Opposite to Kollipuri Nagar Adjusted of C.B road in Ward-53, Unit-12, Zone-5 Under Conucilor Scheme",Own Sources,5,2016-17,2016-17 NE/2016-17/5503,Roads,Completed,NE-ROYAPURAM,53,980000,ATTENDING THE PATCH WORK BY PAVER FINISHER AT KATHIVAKKAM HIGH ROAD AND VARIOUS STREET IN DN -53 UN-12 Zone-V,Own Sources,5,2016-17,2016-17 NE/2016-17/5511,Roads,Completed,NE-ROYAPURAM,53,990000,"ATTENDING THE PATCH WORK BY PAVER FINISHER AT KATH BADA ROAD, T.H.ROAD AND VARIOUS ROAD IN DN -53 UN-12 Zone-V",Own Sources,5,2016-17,2016-17 L/2016-17/14606,Electrical,Completed,L-Electrical,54,592100,"Replacement of 500 Nos of damaged 2 core SMC fuse boxes and 200 Nos of 4 core SMC fuse boxes at various location in Division 53,55,57,59 and 58 in Zone-05.",Own Sources,5,2016-17,2017-18 NE/2016-17/0388,Storm Water Drain,Completed,NE-ROYAPURAM,54,999000,"Improvements to storm water drain at various places in Dn.54,Unit.13,Zone.05.",Own Sources,5,2016-17,2019-20 NE/2016-17/0390,Buildings,Completed,NE-ROYAPURAM,54,997000,"Improvements to Chennai middle school at Amman koil street in Dn-54,Unit-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/10802,Roads,Completed,NE-ROYAPURAM,54,980000,"DESILTING AND IMPROVEMENT TO STORM WATER DRAIN AT VAROUS STREETS IN DN-54, U-13, Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/11966,Buildings,Completed,NE-ROYAPURAM,54,998000,"Supply, Installation and Commissioning of High Quality Treated Drinking Water Plant ( RO / UV FILTRATION ) of 2000 liters / Hour capacity in Dn-54, Unit-13, Zone - 5",Own Sources,5,2016-17,2017-18 NE/2016-17/11971,Buildings,Completed,NE-ROYAPURAM,54,980000,"Operation and Maintenance of High Quality Treated Drinking Water Plant ( RO / UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period in Dn-54, Unit -13, Zone - 5",Own Sources,5,2016-17,2017-18 NE/2016-17/14165,Buildings,Completed,NE-ROYAPURAM,54,1650000,"PROPOSED CONSTRUCTION OF DISABLE FRIENDLY TOILET AND CONSTRUCTION OF ADDITIONAL TOILET AT V.O.C.SALAI IN DN-54, UNIT-12, ZONE-05",MLACDS,5,2016-17,2018-19 NE/2016-17/1513,Buildings,Completed,NE-ROYAPURAM,54,997000,"Improvements to the existing corporation buildings and other institutions at various places in Dn-54,U-14,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/1514,Buildings,Completed,NE-ROYAPURAM,54,999000,"Improvements to plumbing and electrical arrangements to the existing corporation buildings and other institutions at various places in Dn-54,U-14,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/15251,Storm Water Drain,Completed,NE-ROYAPURAM,54,996000,"Improvements to storm water drain at various places in Dn-54,Unit-14,Zone-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15255,Buildings,Completed,NE-ROYAPURAM,54,680000,"Providing water supply and electrical arrangements at various corporation buildings in Dn-54,Unit-14,Zone-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/15256,Buildings,Completed,NE-ROYAPURAM,54,320000,"Improvements to office buildings at Various places in Dn-54,Unit-14,Zone-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/15262,Buildings,Completed,NE-ROYAPURAM,54,760000,"IMPROVEMENT TO PUBLIC CONVEYENCE AT VARIOUS STREET IN DN-54, U-13, Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/15651,Roads,Completed,NE-ROYAPURAM,54,500000,"Providing heavy duty pumpsets for sucking the Stagnating water in Dn.54,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/15652,Roads,Completed,NE-ROYAPURAM,54,570000,"Laying pipe line arrangements at Wood warp street and V.O.C salai in Dn-54,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/16311,Buildings,Completed,NE-ROYAPURAM,54,250000,"Amma Unavagam Damaged at Mint Street due to Vardha Cyclone in Dn-54, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/16312,Buildings,Completed,NE-ROYAPURAM,54,208000,"Roof Sheet Damaged CMS School at Amman Koil Street due to Vardha Cyclone in Dn-54, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/17579,Roads,Completed,NE-ROYAPURAM,54,284000,"FOOTPATH DAMAGED AT WALL TAX ROAD DUE TO VARDHA CYCLONE IN DN-54, UNIT-13, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/0490,Buildings,Completed,NE-ROYAPURAM,55,359000,"Providing Ramp, Flooring, water supply arrangements , Electrical and colour washing at various corporation schools in ward 55, unit 13, Zone 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0493,Bridges,Completed,NE-ROYAPURAM,55,373000,"PROVIDING GATES WITH PILLAR, CONCRETE PATCHES,COLOUR WASHING AND PAINTING , IMPROVEMENTS TO CENTREMEDIAN AT OLD JAIL ROAD BRIDGE OPP TO OLD MINT BUS DEPPO IN WARD 55, UNIT 13, ZONE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/10808,Roads,Completed,NE-ROYAPURAM,55,55000,"Laying of C.C. Road with RMC M30 at Barracks 2nd Lane in Dn.55,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11128,Buildings,Completed,NE-ROYAPURAM,55,990000,"Providing water supply and electrical arrangements to Amma unavagam at St.Xaviour's street in Dn-55,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/11242,Buildings,Completed,NE-ROYAPURAM,55,980000,"Construction of sump in Amma unavagam at Periyannan street in Dn-55,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/11323,Buildings,Completed,NE-ROYAPURAM,55,325000,"Dismantling of existing corporation building at St.Xaviers street in Dn-55,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/14327,Storm Water Drain,Completed,NE-ROYAPURAM,55,368000,"Desilting to storm water drain at St.xaviert street, sevenwells street,Anaikara konar street,Girigory street & Barracks street in div-55,unit-13,zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/14329,Storm Water Drain,Completed,NE-ROYAPURAM,55,369000,"Desilting to storm water drain at Barracks street,P.V Iyer street,Davidson street and lane,Amman koil street in div-55,unit-13,zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/14331,Storm Water Drain,Completed,NE-ROYAPURAM,55,360000,"Desilting to stormwater drain at Subramani street,Sevenwells street,Paris Venkatachalam street,Nattu pillaiyar koil street and Prakasam salai in div-55,unit-13,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/15659,Roads,Completed,NE-ROYAPURAM,55,520000,"Laying pipe line to water Stagnating area at Girigowri street,Srinivasa street,Varadhappa muthiya street Dn-55,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15660,Roads,Completed,NE-ROYAPURAM,55,540000,"Laying pipe line arrangements to water stagnating area at Prakasam salai Dn-55,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15762,Buildings,Completed,NE-ROYAPURAM,55,210000,"IMPROVEMENT TO PUBLIC CONVEYENCE AT VARIOUS STREET IN DN-55, U-13, Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/16248,Playfields,Completed,NE-ROYAPURAM,55,234000,"Childerns play field and Compound wall (Part) damaged at seven wells street due to Vardha Cyclone in Dn-55, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/16251,Buildings,Completed,NE-ROYAPURAM,55,374000,"Toilet block damaged inside Amma unavagam Due to Vardha Cyclone at Nattu pillaiyar koil street in Dn-55, Unit-13, Zone-V",Own Sources,5,2016-17,2017-18 NE/2016-17/17580,Roads,Completed,NE-ROYAPURAM,55,277000,"IMPROVEMENTS TO EXISTING DAMAGED FOOTPATH DUE TO VARADHA CYCLONE AT OLD JAIL ROAD (PART) IN DN-55, UNIT-13, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/3325,Roads,Completed,NE-ROYAPURAM,55,610000,"Attending cement concrete patches at muthusha street from ch 0 to 80M in dn-55,unit-13,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3329,Roads,Completed,NE-ROYAPURAM,55,990000,"Attending cement concrete patches at mottaimesthiri street in dn-55,unit-13,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3353,Roads,Completed,NE-ROYAPURAM,55,880000,"Attending cement concrete patches at samayapurathu amman kovil street in dn-55,unit-13,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3355,Roads,Completed,NE-ROYAPURAM,55,610000,"Attending cement concrete patches at muthusha street from ch 80m to 160m in dn-55,unit-13,zone-05",Own Sources,5,2016-17,2017-18 NE/2016-17/3532,Buildings,Completed,NE-ROYAPURAM,55,377000,"IMPROVEMENTS TO RELIEF CENTRE IN DN 62, UNIT 14, ZONE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/4178,Storm Water Drain,Completed,NE-ROYAPURAM,55,998000,"Improvements to storm water drain at various streets in Dn-55,unit-13,Z-05",Own Sources,5,2016-17,2018-19 NE/2016-17/9056,Buildings,Completed,NE-ROYAPURAM,55,995000,"Proposed Construction of Amma Unavagam at St.Xavier street in Dn-55,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/9057,Buildings,Completed,NE-ROYAPURAM,55,990000,"Additional Improvements to Amma unavagam at St.Xavier street in dn-55,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/9058,Buildings,Completed,NE-ROYAPURAM,55,697000,"Improvements and Painting to existing Amma unavagam at St.Xaviers street in Dn-55,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/0257,Storm Water Drain,Completed,NE-ROYAPURAM,56,995000,"Improvement To Storm Water Drain and Providing Silt Catch Pit at Various Street in Ward-56, Unit-13, Zone-5",Own Sources,5,2016-17,2018-19 NE/2016-17/10344,Roads,Completed,NE-ROYAPURAM,56,206000,"Relaying of road by Paver finisher at Maduraivasal street in Ward-56, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10406,Roads,Completed,NE-ROYAPURAM,56,490000,"Laying of B.T. Road by Paver Finisher at Saivamuthaiya Street in Dn-56, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11004,Roads,Completed,NE-ROYAPURAM,56,1685000,"Laying C.C.Road with RMC30 at Venkata (I) Street in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11005,Roads,Completed,NE-ROYAPURAM,56,954000,"Laying C.C.Road with RMC30 at Venkatesan street in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11006,Roads,Completed,NE-ROYAPURAM,56,1351000,"Laying C.C.Road with RMC30 at Saiva muthiah (M) street in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11007,Roads,Completed,NE-ROYAPURAM,56,724000,"Laying C.C.Road with RMC30 at Thaiappan Lane in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11107,Roads,Completed,NE-ROYAPURAM,56,554000,"Laying C.C.Road with RMC30 at Madura Vasal Street in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11108,Roads,Completed,NE-ROYAPURAM,56,184000,"Laying C.C.Road with RMC30 at Portugeese Church 1st Lane in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11110,Roads,Completed,NE-ROYAPURAM,56,3694000,"Laying C.C.Road with RMC30 at BRN Garden Street in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11111,Roads,Completed,NE-ROYAPURAM,56,226000,"Laying C.C.Road with RMC30 at Appasamy Lane in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11112,Roads,Completed,NE-ROYAPURAM,56,2701000,"Laying C.C.Road with RMC30 at Katchaleeswara Garden Street in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11113,Roads,Completed,NE-ROYAPURAM,56,282000,"Laying C.C.Road with RMC30 at Katchaleeswarar Garden 1st Lane in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11114,Roads,Completed,NE-ROYAPURAM,56,320000,"Laying C.C.Road with RMC30 at Katchaleeswarar Garden 3rd Lane in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/11119,Roads,Completed,NE-ROYAPURAM,56,70000,"Laying C.C.Road with RMC30 at Prakasam Salai 1st Lane in Dn.56,Unit-13,Zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/14857,Buildings,Completed,NE-ROYAPURAM,56,165000,"URGENTS REPAIRS TO CHENNAI GIRLS URUDU SCHOOL IN AMMAN KOIL STREET IN DN-56,U-13,Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/14886,Buildings,Completed,NE-ROYAPURAM,56,271000,"URGENTS REPAIRS TO CHENNAI MIDDLE SCHOOL IN RAMASAMY STREET IN DN-56,U-13,Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/15185,Storm Water Drain,Completed,NE-ROYAPURAM,56,960000,"DESILTING THE STORM WATER DRAIN AT VARIOUS STREET IN DN-56,U-13,Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/16264,Buildings,Completed,NE-ROYAPURAM,56,521000,"URGENTS REPAIRS TO CHENNAI URUDU MIDDLE SCHOOL IN AMMAN KOIL STREET(DUR TO VARDHA CYCLONE) IN DN-56,U-13,Z-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16268,Buildings,Completed,NE-ROYAPURAM,56,827000,"URGENTS REPAIRS TO AMMAN UNAVAGAM IN CORAL MERCHANT STREET (DUR TO VARDHA CYCLONE) IN DN-56, UNIT-13, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/16275,Roads,Completed,NE-ROYAPURAM,56,174000,"URGENTS REPAIRS TO ROAD SIDE PARK IN CHAPPEL CHRUCH STREET AND PEDARIYAR KOIL STREET (DUO TO VARDHA CYCLONE) IN DN-56, UNIT-13, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/17581,Roads,Completed,NE-ROYAPURAM,56,733000,"IMPROVEMENTS TO EXISTING DAMAGED FOOTPATH DUE TO VARADHA CYCLONE AT PRAKASAM SALAI, IBRAHIM SALAI, OLD JAIL ROAD (PART) IN DN-56, UNIT-13, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/3356,Roads,Completed,NE-ROYAPURAM,56,980000,"providing street name board at thaiappan street, shanmugarayan street ,saivamuthaiya 1st to 5th street, Brn garden main street, thaiappan lane, appaswamy lane,ponniamman koil street,asirvadapuram 8 th to 12th street in dn-56,u-13,z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/3704,Buildings,Completed,NE-ROYAPURAM,56,980000,"Providing water supply arrangement,electrical arrangements,platform arrangements,drainage arrangements, and roofing arrangements for AMMA DRING WATER PROJECT at osh road in dn-52,u-13,z-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/6499,Roads,Completed,NE-ROYAPURAM,56,610000,"REFORMING CC ROAD FOR THE MISSING LINK WITH RMC 30 GRADE AT MADURAVASAL STREET (ST XAVIER ST TO FRANCILIN ST) IN DN-56,U-13,Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/6502,Roads,Completed,NE-ROYAPURAM,56,500000,"REFORMING CC ROAD FOR THE MISSING LINK WITH RMC 30 GRADE AT PEDARIYAR KOIL LANE(ST XAVIER ST TO DEADEND) IN DN-56,U-13,Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/6885,Buildings,Completed,NE-ROYAPURAM,56,136000,"PROVIDING FLOORING FOR KITCHEN AND MOSIQUTO NET FOR JOINARIES IN NIGHT SHELTERS AT BRN GARDEN IN DN-56,U-13,Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/0043,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending cement concrete patches at Pommliyar street (From ch 0m to 65m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0044,Roads,Completed,NE-ROYAPURAM,57,430000,"Attending cement concrete patches at Pommliyar street (From ch 65m to 83m) in Dn.57, Unit.13, Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0046,Roads,Completed,NE-ROYAPURAM,57,995000,"Attending cement concrete patches at Vaikunda vathiyar street (From ch 0m to 50m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0047,Roads,Completed,NE-ROYAPURAM,57,481000,"Attending cement concrete patches at Vaikunda vathiyar street (From ch 50m to 100m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0048,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 0m to 45m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0049,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 45m to 90m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0050,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 90m to 135m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0051,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 135m to 180m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0052,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 180m to 225m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0053,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 225m to 270m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0126,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending cement concrete patches at Veerappan street (From ch 0m to 50m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0128,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending cement concrete patches at Veerappan street (From ch 50m to 100m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0129,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Veerappan street (From ch 100m to 150m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2019-20 NE/2016-17/0131,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending cement concrete patches at Veerappan street (From ch 150m to 200m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0132,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Veerappan street (From ch 200m to 230m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0133,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at General muthaiya street (From ch 0m to 60m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0134,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending cement concrete patches at General muthaiya street (From ch 60m to 120m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0135,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending cement concrete patches at General muthaiya street (From ch 120m to 180m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0137,Roads,Completed,NE-ROYAPURAM,57,996000,"Attending cement concrete patches at General muthaiya street (From ch 180m to 240m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0138,Roads,Completed,NE-ROYAPURAM,57,997000,"Attending cement concrete patches at General muthaiya street (From ch 240m to 300m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0144,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 270m to 315m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0145,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 315m to 360m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0146,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 360m to 405m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0147,Roads,Completed,NE-ROYAPURAM,57,998000,"Attending cement concrete patches at Elephant gate road (From ch 405m to 430m) in Dn.57,Unit.13,Zone.05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0151,Buildings,Completed,NE-ROYAPURAM,57,997000,"Improvements to NNMP shed near corporation shopping complex at V.O.C.salai in Dn-57,Unit-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0380,Storm Water Drain,Completed,NE-ROYAPURAM,57,998000,"Improvements to storm water drain at various streets in Dn-57,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/10347,Roads,Completed,NE-ROYAPURAM,57,1029000,"Relaying of road by Paver finisher at Stinger street in Ward-57, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10409,Roads,Completed,NE-ROYAPURAM,57,1905000,"Laying of B.T. Road by Paver Finisher at Elephant Gate Street in Dn-57, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10412,Roads,Completed,NE-ROYAPURAM,57,1783000,"Laying of B.T. Road by Paver Finisher at Audiyappan Street (Part) Mint st to Ramanan St in Dn-57, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10417,Roads,Completed,NE-ROYAPURAM,57,561000,"Laying of B.T. Road by Paver Finisher at Anna (P) Street Part (Audiyappan st to Varatha (m) St) in Dn-57, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10973,Roads,Completed,NE-ROYAPURAM,57,645000,"Laying of C.C. Road with RMC M30 at Krishna Iyar Street in Dn.57,Unit-13,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10974,Roads,Completed,NE-ROYAPURAM,57,248000,"Laying of C.C. Road with RMC M30 at Balasubburayalu Lane in Dn.57,Unit-13,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11377,Buildings,Completed,NE-ROYAPURAM,57,980000,"Improvements to NNNP shed and CI office and providing false ceiling for Amma Unavagam and at Davision street in Dn-57,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/14335,Storm Water Drain,Completed,NE-ROYAPURAM,57,550000,"Desilting to storm water drain at Anna pillai street to Ambarson street, Davidson street, Ambarson street,Anna street in div-57,unit-13,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/14336,Storm Water Drain,Completed,NE-ROYAPURAM,57,550000,"Desilting to storm water drain at Thatha muthiappan street, Prakasam salai,south market lane,jatkapuram slum.Ramanan road north and south, audiappan street, kalyanpuram 1st street and cross street in div-57,unit-13,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/14712,Buildings,Completed,NE-ROYAPURAM,57,950000,"REPAIR AND MAINTENANCE OF PUBLIC CONVIENANCE AT VARIOUS PLACES IN WARD-56 & 57, UNIT-13, ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/1508,Buildings,Completed,NE-ROYAPURAM,57,997000,"Improvements to the existing corporation buildings and other institutions at various places in Dn-57,U-14,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/1510,Buildings,Completed,NE-ROYAPURAM,57,998000,"Improvements to plumbing and electrical arrangements to the existing corporation buildings and other institutions at various places in Dn-57,U-14,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/15250,Storm Water Drain,Completed,NE-ROYAPURAM,57,870000,"Improvements to storm water drain at various places in Dn-57,Unit-14,Zone-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15653,Roads,Completed,NE-ROYAPURAM,57,520000,"Providing rain water harvesting and gully connections at various places in Dn-57,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15656,Roads,Completed,NE-ROYAPURAM,57,540000,"Supplying and fixing SFRC manhole doors at Anna street,Davision street,Prakasam salai,Ramana road and various places Dn-57,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/16313,Buildings,Completed,NE-ROYAPURAM,57,410000,"P.C Damaged at Jatgapuram Slum due to Vardha Cyclone in Dn-57, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/16314,Roads,Completed,NE-ROYAPURAM,57,228000,"Chennai High School Damaged at Wall Tax Road due to Vardha Cyclone in Dn-57, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/3921,Storm Water Drain,Completed,NE-ROYAPURAM,57,999000,"Improvements to storm water drain at Anna (P) street from Prakasam salai to Naatu pillayar kovil street in Dn-57,unit-13,z-05",Earmarked Fund,5,2016-17,2018-19 NE/2016-17/3966,Storm Water Drain,Completed,NE-ROYAPURAM,57,998000,"Improvements to storm water drain at Anna (P) street from Naatu pillayar kovil street to V.O.C salai junction in Dn-57,unit-13,z-05",Earmarked Fund,5,2016-17,2018-19 NE/2016-17/3972,Storm Water Drain,Completed,NE-ROYAPURAM,57,997000,"Improvements to storm water drain at V.O.C salai and Ramanan street in Dn-57,unit-13,Z-05",Own Sources,5,2016-17,2018-19 NE/2016-17/4952,Roads,Completed,NE-ROYAPURAM,57,840000,"Providing pipe line arrangements and rain water harvesting at General muthaiya street in Dn-57,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/5886,Roads,Completed,NE-ROYAPURAM,57,997000,"SUPPLYING AND FIXING INTERLOCKING PAVER BLOCKS AT ELEPHANT GATE ROAD IN DIV-57,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/7926,Buildings,Completed,NE-ROYAPURAM,57,980000,"Construction of sump in Amma unavagam at davision street in dn-57,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/8044,Buildings,Completed,NE-ROYAPURAM,57,990000,"Improvements to Amma unavagam at davision street in dn-57,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/8817,Roads,Completed,NE-ROYAPURAM,57,820000,"SUPPLYING AND FIXING OF INTERLOCKING PAVER BLOCKS AT VEERAPPAN STREET IN DN-57,U-13,Z-05",Own Sources,5,2016-17,2018-19 NE/2016-17/9002,Buildings,Completed,NE-ROYAPURAM,57,995000,"Providing plumbing and electrical arrangements to Amma unavagam at Davision street in Dn-57,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/9155,Roads,Completed,NE-ROYAPURAM,57,820000,"SUPPLYING AND FIXING OF INTERLOCKING PAVER BLOCKS AT GENERAL MUTHAIYA STREET IN DN-57,U-13,Z-05",Own Sources,5,2016-17,2018-19 B/2016-17/0162,Buildings,Completed,B-Buildings,58,2500000,REPAIR AND IMPROVEMENT WORKS TO RIPON BUILDING CAMPUS AND AMMA MAALIGAI IN DN 58 ZONE 5.,Own Sources,5,2016-17,2017-18 B/2016-17/12898,Buildings,Completed,B-Buildings,58,380000,"ANNUAL MAINTENANCE CONTRACT FOR RODENT,MANAGEMENT AND PEST CONTROL FOR RIPON BUILDING, VICTORIA PUBLIC HALL AND AMMAMALIGAI IN DN-58,ZONE-V.",Own Sources,5,2016-17,2019-20 B/2016-17/17684,Buildings,Completed,B-Buildings,58,4400000,SUPPLYING AND FIXING OF FURNITURE IN ZONAL OFFICE IV IN DN 42 ZONE IV,Own Sources,5,2016-17,2018-19 B/2016-17/17685,Buildings,Completed,B-Buildings,58,4450000,SUPPLYING AND FIXING OF FURNITURE IN ZONAL OFFICE IV IN DN 42 ZONE IV,Own Sources,5,2016-17,2018-19 B/2016-17/17686,Buildings,Completed,B-Buildings,58,4625000,SUPPLYING AND FIXING OF FURNITURE IN ZONAL OFFICE IV IN DN 42 ZONE IV,Own Sources,5,2016-17,2017-18 B/2016-17/6296,Buildings,Completed,B-Buildings,58,1445000,"SUPPLY AND FIXING OF INSTALLATION, TESTING AND COMMISSIONING OF LED SIGN BOARD ( TAMIL & ENGLISH & LOGO) IN RIPON BUILDING CAMPUS DIVISION 58 ZONE 5.",Own Sources,5,2016-17,2017-18 L/2016-17/11167,Electrical,Completed,L-Electrical,58,985300,"Electrification work at Ripon building Ground floor Eastern side CE General,First floor Eastern side CE building,observer room and second floor Council hall HOD waiting Hall in Ripon building Premises in Dn -58, Zone-V",Own Sources,5,2016-17,2016-17 L/2016-17/12897,Electrical,Completed,L-Electrical,58,195100,"Electrfication work at Ripon building Ground floor Western side PRO office and security office in Ripon building Premises in Dn 58 ,Zone -V",Own Sources,5,2016-17,2016-17 NE/2016-17/0153,Buildings,Completed,NE-ROYAPURAM,58,996000,"Providing cement concrete ramp facility to TPF in Dn-58,U-14,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/10229,Roads,Completed,NE-ROYAPURAM,58,372000,"Relaying of road by Paver finisher at Dolly street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10251,Roads,Completed,NE-ROYAPURAM,58,547000,"Relaying of road by Paver finisher at Arani muthu street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10265,Roads,Completed,NE-ROYAPURAM,58,739000,"Relaying of road by Paver finisher at Kattur Sadaiyappan street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10266,Roads,Completed,NE-ROYAPURAM,58,381000,"Relaying of road by Paver finisher at Kandhappa street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10268,Roads,Completed,NE-ROYAPURAM,58,561000,"Relaying of road by Paver finisher at Bishop Lane in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10271,Roads,Completed,NE-ROYAPURAM,58,372000,"Relaying of road by Paver finisher at Muthu street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10273,Roads,Completed,NE-ROYAPURAM,58,323000,"Relaying of road by Paver finisher at Valluvan street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10274,Roads,Completed,NE-ROYAPURAM,58,323000,"Relaying of road by Paver finisher at Venkatachalam street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10275,Roads,Completed,NE-ROYAPURAM,58,323000,"Relaying of road by Paver finisher at Thirumalaiyappan street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10276,Roads,Completed,NE-ROYAPURAM,58,263000,"Relaying of road by Paver finisher at Subbu street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10294,Roads,Completed,NE-ROYAPURAM,58,3941000,"Relaying of road by Paver finisher at Devaraj (M) street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10302,Roads,Completed,NE-ROYAPURAM,58,1060000,"Relaying of road by Paver finisher at Ravanier street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10305,Roads,Completed,NE-ROYAPURAM,58,355000,"Relaying of road by Paver finisher at Kesavaier street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10341,Roads,Completed,NE-ROYAPURAM,58,679000,"Relaying of road by Paver finisher at Girigory street in Ward-55, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10443,Roads,Completed,NE-ROYAPURAM,58,389000,"Relaying of road by Paver finisher at Gengu (R) Lane in Ward-61, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10546,Bridges,Completed,NE-ROYAPURAM,58,660000,"IMPROVEMENTS TO COMPOUND WALL AND BORE WORK AT NEW MOORE MARKET ALLIKULAM IN DN-58, UNIT-14, ZONE-V",Own Sources,5,2016-17,2019-20 NE/2016-17/1106,Parks,Completed,NE-ROYAPURAM,58,620000,ANNUAL MAINTENANCE OF FOUNTAIN AT MY LADYS PARK INSIDE IN DN-58 UNIT-14 ZONE-5,Own Sources,5,2016-17,2017-18 NE/2016-17/11532,Buildings,Completed,NE-ROYAPURAM,58,546000,"DRAINAGE ARRANGEMENTS TO BIO METHANATION PLANT AT TRANSFER STATION OF ZONE-V IN DN-58, U-14, Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/1335,Buildings,Completed,NE-ROYAPURAM,58,339000,"IMPROVEMENT TO PUBLIC CONVEYANCE AT KANNAPPAR THIDAL IN DN-58, UNIT-14, ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/13595,Roads,Completed,NE-ROYAPURAM,58,1278000,"Relaying of road by paver finisher at Samy (P) Street in Ward-58, Unit-14, Zone-V.",MLACDS,5,2016-17,2017-18 NE/2016-17/13596,Roads,Completed,NE-ROYAPURAM,58,1361000,"Relaying of road by paver finisher at Venkatachalam street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/14377,Storm Water Drain,Completed,NE-ROYAPURAM,58,232000,"Desilting of storm water drain at Rippon building campus,New Moore market road,Venkatachalam street,Nellu jalladi street,Samy pillai street,Jermiah road (S),Jermiah road (N),Park station,Allikulam eastern side road,Vadamalai street,People park road in Ward-58 Unit-14 Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/14381,Storm Water Drain,Completed,NE-ROYAPURAM,58,231000,"Desilting of storm water drain at Thirunarayanaguru salai,Avathanapapier road,Kalathiappa road,People park road,Dharmaraja koil street in Ward-58 Unit-14 Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/14825,Buildings,Completed,NE-ROYAPURAM,58,814000,"Repairs and improvements to CMS, CGHSS at V.K.(P) Street, 3, A.P. Road, 72, A.P. Road, Vaikokaran Street and Rotler street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2018-19 NE/2016-17/14970,Buildings,Completed,NE-ROYAPURAM,58,460000,"DESILTING OF STORM WATER DRAIN AT VARIOUS PLACES IN DIV-58,UNIT-14,AZONE-5",Own Sources,5,2016-17,2019-20 NE/2016-17/14971,Buildings,Completed,NE-ROYAPURAM,58,700000,"DEIELTING FOR EVK SAMBATH SALAI,DR.ALAGAPPA ROAD,RITHEREN ROAD,JOTHI VENGADACHALAM SALAI,THIRUVENGADAM STREET,VEERASAMY STREET,BALAR KALVINILAYAM SALAI,VALLIAMMAL ROAD,BARRAKS ROAD,NAVAL HOSPITAL ROAD IN DN-58, U-14, Z-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/15308,Buildings,Completed,NE-ROYAPURAM,58,880000,"IMPROVEMENTS TO PUBLIC CONVIENENCE AT VARIOUS PLACES IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/15314,Buildings,Completed,NE-ROYAPURAM,58,75800,"IMPROVEMENT TO GARBAGE DUST BIN AT VARIOUS STREET IN DN-58, U-14, Z-5.",Own Sources,5,2016-17,2020-21 NE/2016-17/15317,Buildings,Completed,NE-ROYAPURAM,58,263000,"IMPROVEMENT TO MAN HOLE DOORS AT VARIES STREET IN DN-58, U-14, Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/15381,Buildings,Completed,NE-ROYAPURAM,58,96000,"PROVIDING RAINWATER HARVESTING AT SYDENHAMS LANE, GENERAL COLLEGE ROAD IN DN-58, U-14, Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/15383,Buildings,Completed,NE-ROYAPURAM,58,107000,"IMPROVEMENT TO PRE CAST SLAB AT POONAMALLI HIGH ROAD IN DN-58, U-14, Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/15384,Buildings,Completed,NE-ROYAPURAM,58,155000,"IMPROVEMENT TO SIDDA HOSPITAL AT EVK SAMBATH SALAI IN DN-58, U-14, Z-5.",Own Sources,5,2016-17,2019-20 NE/2016-17/16123,Parks,Completed,NE-ROYAPURAM,58,1655000,"PROPOSED PLANTING OF TREES VARIOUS STREETS IN DIV-49 TO 63,UNIT-12, 13,14, ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16440,Parks,Completed,NE-ROYAPURAM,58,586000,"Repairs to the My Ladies Park at Raja Muthiah Salai in Ward.58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/16445,Parks,Completed,NE-ROYAPURAM,58,559000,"Repairs to Ragavendra Park at A.P. Road in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/16463,Buildings,Completed,NE-ROYAPURAM,58,83000,"Repairs to the Amma Unavagam at Kalathiappa street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/16466,Buildings,Completed,NE-ROYAPURAM,58,314000,"Repairs to the Amma Unavagam at Whanels Road in Ward-58, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/17584,Roads,Completed,NE-ROYAPURAM,58,725000,"REPAIRS TO THE FOOTPATH AT DR. ALAGAPPA ROAD, JOTHIVENKATACHALAM ROAD, JETMAIAH ROAD AND E.V.K.SAMPATH SALAI IN DN-58, UNIT-14, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/17886,Parks,Completed,NE-ROYAPURAM,58,999000,"ANNUAL MAINTENANCE OF PARK AT MY LADYS PARK IN DN-58, UNIT-14 ZONE-5 (MAINTENANCE PERIOD FOR SIX MONTH)",Own Sources,5,2016-17,2017-18 NE/2016-17/18307,Buildings,Completed,NE-ROYAPURAM,58,357000,"IMPROVEMENTS TO COMMUNITY HALL AT KANNAPPA THIDAL SYTENKAMY ROAD IN DN 58,UNIT 14,ZONE 5",Own Sources,5,2016-17,2020-21 NE/2016-17/18487,Buildings,Completed,NE-ROYAPURAM,58,121000,"IMPROVEMENTS TO ICDS CENTRE NO.544542 AT STRINGERS STREET IN DN 58,UNIT 14 AND ZONE 5",Own Sources,5,2016-17,2020-21 NE/2016-17/18488,Storm Water Drain,Completed,NE-ROYAPURAM,58,298000,"REPAIRS TO STORM WATER DRAIN AT VARIOUS STREET IN DN 58,UNIT 24,ZONE 5",Own Sources,5,2016-17,2020-21 NE/2016-17/2203,Buildings,Completed,NE-ROYAPURAM,58,728000,"IMPROVEMENTS TO CORPORATION SHOPPING COMPLEX AT KALATHIAPPA STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/2221,Buildings,Completed,NE-ROYAPURAM,58,880000,"ADDITIONAL IMPROVEMENTS TO CORPORATION SHOPPING COMPLEX AT KALATHIAPPA STREET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/3636,Buildings,Completed,NE-ROYAPURAM,58,88000,"Improvements to community centre in kannapar thidal in dn-58, unit-14,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3642,Buildings,Completed,NE-ROYAPURAM,58,95400,"Improvements to CMS at No.3 A.P.Road in dn-58, unit-14,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3647,Buildings,Completed,NE-ROYAPURAM,58,80746,"Improvements to CMS No.72 at A.P.Road and Vaikkaran street in dn-58 ,unit-14,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3650,Buildings,Completed,NE-ROYAPURAM,58,277000,"Improvements to Anganwadi center at Stringer streets in dn-58,unti-14,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3651,Buildings,Completed,NE-ROYAPURAM,58,136000,"Improvements to Community center at Navel Hospital road in dn-58,unti-14,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/3652,Buildings,Completed,NE-ROYAPURAM,58,194000,"Providing Ramp and painting at various building in dn-58,unti-14,zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/4163,Buildings,Completed,NE-ROYAPURAM,58,116000,"Improvements to E-Seva maiyam and Eye Hospital and Alikulam Court in DN-58,Unit-14,Zone-05",Own Sources,5,2016-17,2016-17 NE/2016-17/5004,Buildings,Completed,NE-ROYAPURAM,58,466000,"PROVIDING FLOORING ARRANGEMENTS TO THE EXISTING SHOPPING COMPLEX AT KALATHIAPPA STREET AND SUPPLYING DIESEL PUMPSETS FOR RAIN WATER DISPOSAL IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/5888,Roads,Completed,NE-ROYAPURAM,58,375000,"SUPPLYING AND FIXING OF INTERLOCKING PAVER BLOCKS AT MUTHUMARIAMMAN STREET IN DIV-60,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/6212,Buildings,Completed,NE-ROYAPURAM,58,999000,"Additional Improvements Councillor office and chennai girls higher secondary school at Rotler street in dn-58, unit-14, zone-05",Own Sources,5,2016-17,2018-19 NE/2016-17/6886,Parks,Completed,NE-ROYAPURAM,58,999000,annual maintenance of Park at My ladys Park at Dn-58 (Maintance Period for six Month),Own Sources,5,2016-17,2016-17 NE/2016-17/10279,Roads,Completed,NE-ROYAPURAM,59,424000,"Relaying of road by Paver finisher at Narayanappa (M) street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10286,Roads,Completed,NE-ROYAPURAM,59,2944000,"Relaying of road by Paver finisher at Mint street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10296,Roads,Completed,NE-ROYAPURAM,59,656000,"Relaying of road by Paver finisher at Amman Koil street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10310,Roads,Completed,NE-ROYAPURAM,59,444000,"Relaying of road by Paver finisher at Anthony street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/11240,Buildings,Completed,NE-ROYAPURAM,59,983000,"IMPROVEMENTS AND PAINTING TO FOOTPATH AND CENTER MEDIAN AT SIVANANDHA SALAI AND WALLAJA ROAD IN DIVISION-59, UNIT-14, ZONE-05.",Own Sources,5,2016-17,2016-17 NE/2016-17/11241,Buildings,Completed,NE-ROYAPURAM,59,988000,"PROVIDING AND FIXING NAME BOARDS AT VARIOUS STREET IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2016-17,2016-17 NE/2016-17/14884,Buildings,Completed,NE-ROYAPURAM,59,970000,"Repairs and improvements to CMS, in sathyavani muthu nagar main road, mint street, ellispuram in Ward-59, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/14941,Buildings,Completed,NE-ROYAPURAM,59,560000,"DESILTING AND IMROVEMENTS TO STROM WATER DRAIN AT ELLIS ROAD, MUKTHARUNISHA ST, OWLIA SHAHIB ST, UNNIS ALI ST, ETC IN DN-59, UNIT-14, ZONE-5",Own Sources,5,2016-17,2016-17 NE/2016-17/14944,Buildings,Completed,NE-ROYAPURAM,59,554000,"DESILTING AND IMROVEMENTS TO STROM WATER DRAIN AT NSC BOSE ROAD, FRAZER BRIDGE ROAD, KELLYS, etc IN DN-59, UNIT-14, ZONE-5",Own Sources,5,2016-17,2016-17 NE/2016-17/16008,Buildings,Completed,NE-ROYAPURAM,59,920000,"REPAIRS AND MAINTAINCE OF ANGAN WADI AT , FRAZER BRIDGE ROAD, SATHIYAVANI MUTHU NAGAR MAIN ROAD , CHS ELLISPURAM, ELLIS PURAM IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/18652,Buildings,Completed,NE-ROYAPURAM,59,1520000,"CONSTRUCTION OF COMPOUND WALL AT MUTHU SAMY SALAI (LHS) IN DIV-59, UNIT-14, ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/18806,Buildings,Completed,NE-ROYAPURAM,59,413000,"DESILTING AND IMPROVEMENTS TO SATHYA VANI MUTHU NAGAR MAIN ROAD, 1ST STREET TO 9TH STREET, IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/18807,Buildings,Completed,NE-ROYAPURAM,59,523000,"DESILTING AND IMPROVEMENTS TO PALLAVAN NAGAR, GANDHI NAGAR 1ST TO 24TH STREET, IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/3256,Roads,Completed,NE-ROYAPURAM,59,999000,"WARD-59 COUNCILOR SCHEME 2016-17 PROVIDING INDIA MARK PUMP 11 AT VARIOUS PLACE IN DIVISION-59, UNIT-14, ZONE-05.",Own Sources,5,2016-17,2017-18 NE/2016-17/4029,Roads,Completed,NE-ROYAPURAM,59,999000,"WARD-59 COUNCILOR SCHEME 2016-17 ATTENDING CEMENT CONCRETE PAVEMENTS AND PATCHES AT MUKTHARUNISHA BEGUM ST, THAYAR SHAHIB ST, BALAMUTHU ST, THAYAR SHAHIB 2ND LANE, PALLAVAN NAGAR, SATHIYAVANI MUTHU NAGAR 1ST, 2ND, 3RD, 4TH, 5TH STREET, IN DN-59,UNIT-14,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/4031,Roads,Completed,NE-ROYAPURAM,59,993000,"WARD-59 COUNCILOR SCHEME 2016-17 ATTENDING CEMENT CONCRETE PAVEMENTS AND PATCHES AT DEVARAJA (M) ST, MINT ST, RAVANIYAR ST, EDAPALAYAM ST, STHAYAVANI MUTHU NAGAR MAIN ROAD IN DN-59,UNIT-14,ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/8225,Buildings,Completed,NE-ROYAPURAM,59,528000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT PALLAVAN NAGAR GANDHI NAGAR, S.M NAGAR MAIN ROAD, IN DN-59, UN-14, ZO-05",Own Sources,5,2016-17,2019-20 NE/2016-17/8226,Buildings,Completed,NE-ROYAPURAM,59,524000,"REPAIRS AND MAINTAINCE OF PUBLIC CONVENIENCE AT N.S.C BOSE ROAD, RATTAN BAZZAR, NAINIYAPPA NAICKAN ST, BROAD WAY BUS STAND (NORTH) AND (SOUTH), IN DN-59, UN-14, ZO-05",Own Sources,5,2016-17,2019-20 NE/2016-17/8227,Buildings,Completed,NE-ROYAPURAM,59,976000,"IMPROVEMENTS AND MAINTAINCE OF AMMA UNAVAGAM IN RAJIV GANDHI HOSPITAL AT EVR ROAD IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2016-17,2019-20 NE/2016-17/8228,Buildings,Completed,NE-ROYAPURAM,59,990000,"CONSTRUCTION OF PUBLIC CONVIENCE AT SATHYAVANI MUTHU NAGAR MAIN ROAD IN DIVISION-59, UNIT-14, ZONE-05",Own Sources,5,2016-17,2019-20 B/2016-17/14940,Buildings,Completed,B-Buildings,60,2543000,"FABRICATION, CONSTRUCTION AND ERECTION OF GREATER CHENNAI CORPORATION PAVILION INCLUDING SUPPLYING OF NEW MODELS AND INTERIOR DESIGN, VIDEO DEVICES AND MAN POWER FOR MANAGING, HOUSEKEEPING AND SECURITY FOR 43rd INDIA TOURIST AND INDUSTRIAL FAIR 2017 ISLAND GROUND IN DN-60 ,ZONE- V.",Own Sources,5,2016-17,2017-18 BR/2016-17/18380,Roads,Completed,BR-Bus Route Roads,60,1890000,"ROAD WIDENING BY REDUCING FOOTPATH AND PROVIDING CENTER MEDIAN FOR TRAFIIC DIVERSION AT IBRAHIMJI SALAI IN FROM JUNCTION OF RAJAJI SALAI TO EBRAHIMJI SALAI 2ND LANE DIVISION -60 ,ZONE 5",Deposit Works,5,2016-17,2017-18 BR/2016-17/18424,Roads,Completed,SP-SPECIAL PROJECTS,60,29400000,"Providing and paving with Granite Footpath along with railing of SS Pipe and Granite Pedestal Stones at Western and Eastern side of kamarajar Salai , Marina (From the junction of Swamy Sivananda salai to Flag Staff Road) in Dn-60, Zone-5",Own Sources,5,2016-17,2018-19 BR/2016-17/18425,Footpath,Completed,SP-SPECIAL PROJECTS,60,23800000,"Providing and paving with Granite Footpath along with railing of SS Pipe and Granite Pedestal Stones at Western and Eastern side of Rajaji Salai Marina (From the junction of Flag Staff Road-War memorial to Secretariat) in Dn-60, Zone-5",Own Sources,5,2016-17,2018-19 BR/2016-17/18491,Roads,Completed,BR-Bus Route Roads,60,1889000,"ROAD WIDENING BY REDUCING FOOTPATH AND PROVIDING CENTER MEDIAN FOR TRAFIIC DIVERSION AT IBRAHIMJI SALAI FROM JUNCTION OFEBRAHIMJI SALAI 2ND LANE TO THAMBU CHETTY STREET IN DIVISION -60 ,ZONE 5",Deposit Works,5,2016-17,2017-18 J/2016-17/18341,Bridges,Completed,J-Bridges,60,2000000,"Repair and Re-construction to Existing Bridge handrail at Reserve Bank in Division-60, Zone-V",Grants,5,2016-17,2017-18 L/2016-17/14502,Electrical,Completed,L-Electrical,60,975500,"Erection of 41 Nos 7mtr convertional Street Lamp post and laying of 2cx16 Sq.mm PVC Alu cable 782 mtrs, 4Cx16 Sq.mm pvc Alu cable 867 mtrs and 31/2x120Sqmm pvc Alu cable 40 Mtrs at Secretariat Park in Division- 60, Zone - 05",Own Sources,5,2016-17,2017-18 L/2016-17/14503,Electrical,Completed,L-Electrical,60,879900,"Erection of 49 nos 7mtr Street Lamp Post and laying of 2cx16Sq.mm PVC Alu cable 1033 mtrs at Secretariat Park in Division 60, Zone 05",Own Sources,5,2016-17,2017-18 L/2016-17/15682,Electrical,Completed,L-Electrical,60,172800,Supply and installing of 4 nos of 200 W Induction Lamp fittings at Kamarajar Salai in Div - 60 in Zone-5.,Own Sources,5,2016-17,2018-19 L/2016-17/15826,Electrical,Completed,L-Electrical,60,1242600,Fixing of 200 Nos of 6/7mtr and 96nos 8/9mtr post in various places in Dn.49 to 63 in Zone-05.,Own Sources,5,2016-17,2016-17 NE/2016-17/0139,Roads,Completed,NE-ROYAPURAM,60,998000,"Attending cement concrete patches at Muthu mariamman street (From ch 0m to 45m) in Dn.60,Unit.14,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0140,Roads,Completed,NE-ROYAPURAM,60,998000,"Attending cement concrete patches at Muthu mariamman street (From ch 45m to 90m) in Dn.60,Unit.14,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0142,Roads,Completed,NE-ROYAPURAM,60,998000,"Attending cement concrete patches at Muthu mariamman street (From ch 90m to 135m) in Dn.60,Unit.14,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0143,Roads,Completed,NE-ROYAPURAM,60,997000,"Attending cement concrete patches at Muthu mariamman street (From ch 135m to 180m) in Dn.60,Unit.14,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0149,Roads,Completed,NE-ROYAPURAM,60,998000,"Attending cement concrete patches at Muthu mariamman street (From ch 180m to 225m) in Dn.60,Unit.14,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0150,Roads,Completed,NE-ROYAPURAM,60,997000,"Attending cement concrete patches at Muthu mariamman street (From ch 225m to 260m) in Dn.60,Unit.14,Zone.05.",Own Sources,5,2016-17,2018-19 NE/2016-17/0259,Buildings,Completed,NE-ROYAPURAM,60,997000,"Improvement to Walker Pathway in Secretariat park at Rajaji Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0260,Parks,Completed,NE-ROYAPURAM,60,997000,"Supply of Red earth, Manure in Secretariat park at Rajaji Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0266,Roads,Completed,NE-ROYAPURAM,60,969000,"ATTENDING CEMENT CONCRETE PATCHES TO SULTAN STREET FROM CHAINAGE OF 0-50M IN DIV-60,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0267,Roads,Completed,NE-ROYAPURAM,60,969000,"ATTENDING CEMENT CONCRETE PATCHES TO SULTAN STREET FROM CHAINAGE OF 50 TO 100M IN DIV-60,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0268,Roads,Completed,NE-ROYAPURAM,60,969000,"ATTENDING CEMENT CONCRETE PATCHES TO SULTAN ROAD FROM CHAINAGE OF 100 TO 150M IN DIV-60,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0269,Roads,Completed,NE-ROYAPURAM,60,969000,"ATTENDING CEMENT CONCRETE PATCHES IN SULTAN ROAD FROM CHAINAGE OF 150 TO 200M IN DIV-60,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0270,Roads,Completed,NE-ROYAPURAM,60,997000,"ATTENDING CEMENT CONCRETE PATCHES AT VARADHARAJA MUDALI STREET FROM CHAINAGE OF 0 TO 50M IN DIV-60,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0271,Roads,Completed,NE-ROYAPURAM,60,997000,"ATTENDING CEMENT CONCRETE PATCHES AT VARADHARAJA MUDALI STREET FROM CHAINAGE OF 50 TO 100M IN DIV-60,UNIT-13,ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0418,Roads,Completed,NE-ROYAPURAM,60,994000,"LAYING INTERLOCKING BLOCKS ON THE SIDES OF THE CC ROAD AT JEHANGIR STREET,ARBUTNOT LANE AND GRANARY STREET IN DN60,U13,Z5.",Own Sources,5,2016-17,2016-17 NE/2016-17/0918,Roads,Completed,NE-ROYAPURAM,60,997000,"Painting nepiar bridge at kamarajar salai in ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0919,Roads,Completed,NE-ROYAPURAM,60,936000,"Painting Reserve bank subway at Rajaji salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0920,Roads,Completed,NE-ROYAPURAM,60,995000,"Painting foot path Kerb wall at Rajaii Salai, Kamarajar salai, and Notrh fort side road, at Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0921,Roads,Completed,NE-ROYAPURAM,60,998000,"Painting center median at Rajaji salai, North fort side road and Kamaraj salai at ward-60, Unit-13, zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0923,Roads,Completed,NE-ROYAPURAM,60,998000,"Laying Cement Concrete Road at Rajaji Salai Service Road (East Side) Ch 0 to 50 at Ward-60, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0925,Roads,Completed,NE-ROYAPURAM,60,997000,"Laying Cement Concrete Road at Rajaji Salai Service Road (East Side) Ch 51 to 100 at Ward-60, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0926,Roads,Completed,NE-ROYAPURAM,60,998000,"Laying Cement Concrete Road at Rajaji Salai Service Road (West Side) Ch 0 to 50 at Ward-60, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0927,Roads,Completed,NE-ROYAPURAM,60,998000,"Laying Cement Concrete Road at Rajaji Salai Service Road (West Side) Ch 51 to 100 at Ward-60, Unit-12, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0929,Buildings,Completed,NE-ROYAPURAM,60,998000,"Providing separator for parking beneath bridge at Rajaji Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0953,Roads,Completed,NE-ROYAPURAM,60,973000,"Laying the B.T road at Annai Sathya nagar North side in ward-60, unit-13, zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0955,Roads,Completed,NE-ROYAPURAM,60,968000,"Laying the B.T road at Annai Sathya nagar South side in ward-60, unit-13, zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/0956,Roads,Completed,NE-ROYAPURAM,60,971000,"Laying the B.T road at Annai Sathya nagar East side in ward-60, unit-13, zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/10420,Roads,Completed,NE-ROYAPURAM,60,255000,"Relaying of road by Paver finisher at Jones Lane in Ward-60, Unit-13, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/10421,Roads,Completed,NE-ROYAPURAM,60,478000,"Laying of B.T. Road by Paver Finisher at Kenndy (C) Street in Dn-60, Unit-13, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/1067,Roads,Completed,NE-ROYAPURAM,60,962000,"Attending B.T Patches at Various Streets in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/1069,Roads,Completed,NE-ROYAPURAM,60,966000,"Attending B.T Patches at Various Street in Ward-60, Unit-13,Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/1070,Roads,Completed,NE-ROYAPURAM,60,964000,"Laying Cement Concrete Patches at various Street in ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/1071,Roads,Completed,NE-ROYAPURAM,60,961000,"Laying Cement Concrete Patches at various Street in ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/11027,Parks,Completed,NE-ROYAPURAM,60,974000,Maintenance of Secretariat Park at Rajajisalai in Div-60 Unit-13 Zone-5 Gardener Maintenance Period of 5 Months (Per Day 24 Gardeners),Own Sources,5,2016-17,2018-19 NE/2016-17/11120,Roads,Completed,NE-ROYAPURAM,60,761000,"Laying C.C.Road with RMC30 at Adam street in Dn.60,Unit-13,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11121,Roads,Completed,NE-ROYAPURAM,60,2446000,"Laying C.C.Road with RMC30 at Ayyappa (C) street in Dn.60,Unit-13,Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11365,Buildings,Completed,NE-ROYAPURAM,60,980000,"Providing false ceiling with ornamental lights and sheets to Amma Unavagam at Ayyappa chetty street in Dn-60,U-13,Z-05.",Own Sources,5,2016-17,2019-20 NE/2016-17/13485,Roads,Completed,NE-ROYAPURAM,60,940000,RELAYING THE ROAD WITH BCCMP1 AT VENKAT MAISTRY STREET IN DN-60 U-13 Z-5,Own Sources,5,2016-17,2018-19 NE/2016-17/13486,Roads,Completed,NE-ROYAPURAM,60,996000,RELAYING THE ROAD WITH BCCMP1 AT TRUCKERS ROAD &GEORGE TOWN COURT APPROACH IN DN-60 U-13 Z-5,Own Sources,5,2016-17,2018-19 NE/2016-17/13563,Roads,Completed,NE-ROYAPURAM,60,980000,PROVIDING THE SPEED BREAK AT VARIOUS STREET IN DN-60 U-13 Z-5,Own Sources,5,2016-17,2018-19 NE/2016-17/13567,Roads,Completed,NE-ROYAPURAM,60,980000,PROVIDING THE SPEED NBREAK AT VARIOUS STREET IN DN-60 U-13 Z-5,Own Sources,5,2016-17,2018-19 NE/2016-17/13569,Roads,Completed,NE-ROYAPURAM,60,780000,PROVIDING THE SPEED NBREAK AT VARIOUS STREET IN DN-60 U-13 Z-5,Own Sources,5,2016-17,2018-19 NE/2016-17/14333,Storm Water Drain,Completed,NE-ROYAPURAM,60,498000,"Desilting to storm water drain at Ibrahim st, Varadharajan street,Jaffer syrang lane,Mooker Nallamuthu street,Rajaji salai and Post office street in div-60,unit-13,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/14334,Storm Water Drain,Completed,NE-ROYAPURAM,60,500000,"Desilting to storm water drain at Light House Road(West), Rajaji salai ,Kamarajar salai,Flag staff house road, North fort side road,NSC bose road(2479),sembudoss street and jones lane in div-60,unit-13,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/14890,Buildings,Completed,NE-ROYAPURAM,60,256000,"URGENTS REPAIRS TO CHENNAI URUDU SCHOOL IN ANGAPPAN (N) STREET IN DN-60, U-13, Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/15657,Roads,Completed,NE-ROYAPURAM,60,520000,"Providing rain water harvesting and gully connections at various places in Dn-60,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15658,Roads,Completed,NE-ROYAPURAM,60,540000,"Supplying and fixing SFRC manhole doors at various places Dn-60,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/16570,Buildings,Completed,NE-ROYAPURAM,60,264000,"Toilet block damaged Due to Vardha Cyclone at SathyaNagar in Dn-60, Unit-13, Zone-V",Own Sources,5,2016-17,2017-18 NE/2016-17/16578,Roads,Completed,NE-ROYAPURAM,60,268000,"Improvements and minor Repairs to the Existing Reserve Bank Subway Due to Vardha Cyclone at Rajaji Salai n Dn-60, Unit-13, Zone-V",Own Sources,5,2016-17,2017-18 NE/2016-17/16579,Bridges,Completed,NE-ROYAPURAM,60,195000,"Improvements and minor repairs to existing Pedatrien Subway in front of Beach Station Due to Vardha Cyclone at Rajaji Salai in Dn-60, Unit-13, Zone-V",Own Sources,5,2016-17,2017-18 NE/2016-17/17586,Footpath,Completed,NE-ROYAPURAM,60,456000,"IMPROVEMENTS AND REPAIRS TO DAMAGED DUE TO VARDHA CYCLONE AT KAMARAJ SALAI IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/17587,Roads,Completed,NE-ROYAPURAM,60,515000,"IMPROVEMENTS AND REPAIRS TO DAMAGED DUE TO VARDHA CYCLONE AT FLAG STAFF ROAD IN DN-60, UNIT-13, ZONE-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/17588,Footpath,Completed,NE-ROYAPURAM,60,832000,"IMPROVEMENTS AND REPAIRS TO DAMAGED FOOTPATH DUE TO VARDHA CYCLONE AT INFRONT OF SECREATARIAT RAJAJI SALAI IN DN-60, UNIT-13, ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/3473,Roads,Completed,NE-ROYAPURAM,60,999000,"Improvements to traffic island at various places in Dn.60,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/3974,Storm Water Drain,Completed,NE-ROYAPURAM,60,996000,"Improvements to storm water drain at Manady street in Dn-60,Unit-13,Z-05",Own Sources,5,2016-17,2018-19 NE/2016-17/3975,Storm Water Drain,Completed,NE-ROYAPURAM,60,995000,"Improvements to storm water drain at Mukkar Nallamuthu Street in Dn-60,Unit-13,Z-05",Own Sources,5,2016-17,2016-17 NE/2016-17/5969,Buildings,Completed,NE-ROYAPURAM,60,991000,"Improvement to Urdhu School at Angappan Naaickan Street in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/6444,Roads,Completed,NE-ROYAPURAM,60,978000,"Providing to Rain water haversting around war memorial at Rajaji salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6477,Parks,Completed,NE-ROYAPURAM,60,990000,"Improvement to Traffic Island Park at Rajaji Salai Junction of Flag Staff House road in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6478,Parks,Completed,NE-ROYAPURAM,60,988000,"Improvement to Traffic island Park Adjcent to War Memorial at Kamaraj Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6479,Roads,Completed,NE-ROYAPURAM,60,986000,"Improvement to Roadside Park infornt of Sathya Nagar at Kamaraj Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6481,Roads,Completed,NE-ROYAPURAM,60,660000,"Formation of Base for Base Plantation and Greenary Arrangement at South East side inside Secretariat Park in Rajali Salai at Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6482,Parks,Completed,NE-ROYAPURAM,60,944000,"Rectification of Damaged Walker Pathway inside Secretariat Park at Southside at Rajaji Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6483,Parks,Completed,NE-ROYAPURAM,60,976999,"Rectification of Damaged Walker Pathway inside Secretariat Park at Northside at Rajaji Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6484,Parks,Completed,NE-ROYAPURAM,60,997000,"Providing Interlocking Pathway and Greenary arrangement to inside island of Secretariat Park at Rajaji Salai Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/6705,Roads,Completed,NE-ROYAPURAM,60,990000,"Laying bituminous road at Adiapadham street in Dn-60,U-13,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/6889,Buildings,Completed,NE-ROYAPURAM,60,500000,"REPAIRS AND MAINTENANCE OF PUBLIC CONVENIENCE AT VARIOUS PLACE IN DIVISION-60,UNIT-13,ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/7002,Roads,Completed,NE-ROYAPURAM,60,986000,"Improvement to footpath and Defacing and Painting Kerb wall at Rajali Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/7006,Roads,Completed,NE-ROYAPURAM,60,989000,"Painting to Center Median at Rajali Salai in Ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2016-17 NE/2016-17/8814,Roads,Completed,NE-ROYAPURAM,60,870000,"SUPPLYING AND FIXING OF INTERLOCKING PAVER BLOCKS AT SULTAN STREET IN DN-60,U-13,Z-05",Own Sources,5,2016-17,2018-19 NE/2016-17/8994,Roads,Completed,NE-ROYAPURAM,60,990000,"Laying bituminous road at Adiapadham streets and lanes in Dn-60,U-13,Z-05.",Own Sources,5,2016-17,2016-17 NE/2016-17/9000,Roads,Completed,NE-ROYAPURAM,60,690000,"Laying bituminous road at Ibrahim 1st street in Dn-60,U-13,Z-05",Own Sources,5,2016-17,2016-17 NE/2016-17/9667,Roads,Completed,NE-ROYAPURAM,60,988000,"Providing Interlocking blocks at the road edge Angappan Naickan Street Eastern side in ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/9668,Roads,Completed,NE-ROYAPURAM,60,994000,"Providing Interlocking blocks at the road edge Angappan Naickan Street Western side in ward-60, Unit-13, Zone-5",Own Sources,5,2016-17,2017-18 BR/2016-17/13382,Road Cut,Completed,BR-Bus Route Roads,61,2037000,"Attending Roadcut Portion made by TNEB at Pantheon Road (From Junction of Langs Garden Road to Greams Road ) , in Ward-61 Zone -5",Deposit Works,5,2016-17,2016-17 BR/2016-17/17673,Roads,Completed,BR-Bus Route Roads,61,1695000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 Ethiraj salai, Halls road, Casa major road, pantheon road, Blackers road, PCO road, EVK sampath salai, Arunachalam street, Ibrahim street, West mada koil street, flag staff road in Zone 5",Grants,5,2016-17,2017-18 BR/2016-17/17749,Roads,Completed,BR-Bus Route Roads,61,1320000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Rajaji salai,kamaraj salai,S. N Chetty street,Pantheon road, Halls road, Casa major road,Egmore hogh road,Gandhi irwin road,etc., in Zone-5",Grants,5,2016-17,2017-18 BR/2016-17/18016,Roads,Completed,BR-Bus Route Roads,61,9750000,"Providing junction improvement and Traffic island works at Pantheon road at the junction of Adhithanar salai, PCO road, Rukmani Lakshmipathy salai and Pantheon road ( North and South ) in ward - 61, Zone - 5.",Own Sources,5,2016-17,2018-19 BR/2016-17/19793,Roads,Completed,BR-Bus Route Roads,61,2675000,"PROVIDING OF CRASH BARRIER TYPE CENTRE MEDIAN AT NAIR BRIDGE (from poonamalle rd.jn to pco rd.jn.) IN DIV -61,ZONE-5.",Own Sources,5,2016-17,2019-20 BR/2016-17/4637,Roads,Completed,BR-Bus Route Roads,61,621000,Providing Retro Reflective Sheet For Over Head Gantry Signboards at Ethiraj salai jn of R.k salai In Division - 61 Zone V,Own Sources,5,2016-17,2017-18 BR/2016-17/4654,Roads,Completed,BR-Bus Route Roads,61,530000,Providing Retro Reflective Sheet For Over Head Gantry Signboards at Pantheon road jn of R.K salai In Division - 61 Zone V,Own Sources,5,2016-17,2017-18 L/2016-17/13518,Electrical,Completed,L-Electrical,61,687300,"Supply and Erection of 12 nos of damaged Kiosk type pillar box at various locations in Div 58,59,61 and 62 in Zone V",Own Sources,5,2016-17,2016-17 L/2016-17/19045,Electrical,Completed,L-Electrical,61,110600,"Replacement of 200 mtrs of 2C x 16 Sq.mm PVC Alu cable and removal and refixing of 3 nos 6/7mtr lamp post at AR.Police Quarters, in Division-61, under Zone- V.",Own Sources,5,2016-17,2018-19 NE/2016-17/0440,Buildings,Completed,NE-ROYAPURAM,61,628000,"IMPROVEMENT TO SCHOOL AT VARIES STREETS IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0441,Buildings,Completed,NE-ROYAPURAM,61,180000,"IMPROVEMENT TO STORM WATER DRAIN AT AADHITHANAR SALAI IN DN-61, UNIT-, ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0442,Buildings,Completed,NE-ROYAPURAM,61,595000,"IMPROVEMENT TO PARK AT VARIES STREETS ( GUNGU SUBWAY, MAYER SUNDARAVA AND L.G ROAD ) IN DN-61, UNIT-, ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0443,Buildings,Completed,NE-ROYAPURAM,61,460000,"IMPROVEMENT TO STORM WATER DRAIN AT SETH COLONY & PIPELINE WORK AT VARIES STREETS AND CENTER MEDIA AT EGMORE IN DN-61, UNIT-, ZONE-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/0491,Buildings,Completed,NE-ROYAPURAM,61,248000,"IMPROVEMENTS TO P C AT KUZHANDAI VELU STREET IN DIV 61, UNIT 14, ZONE V.",Own Sources,5,2016-17,2018-19 NE/2016-17/0492,Buildings,Completed,NE-ROYAPURAM,61,220000,"IMPROVEMENT TO AMMA HOTEL AT EGMORE EYE HOSPITAL IN DIV 61, UNIT 14, ZONE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/10322,Roads,Completed,NE-ROYAPURAM,61,358000,"Laying of B.T. Road by Paver Finisher at LNP Koil Street in Dn-61, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10329,Roads,Completed,NE-ROYAPURAM,61,862000,"Laying of B.T. Road by Paver Finisher at Veerasamy Street in Dn-61, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10332,Roads,Completed,NE-ROYAPURAM,61,1338000,"Laying of B.T. Road by Paver Finisher at Gengu (R) Street in Dn-61, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10426,Roads,Completed,NE-ROYAPURAM,61,424000,"Relaying of road by Paver finisher at Vengu street in Ward-61, Unit-14, Zone-V.",Own Sources,5,2016-17,2017-18 NE/2016-17/11115,Buildings,Completed,NE-ROYAPURAM,61,645000,"PROVIDING WATER SUPPLY , ELECTRICAL AND WETHEARING COURSE ARRANGEMENTS TO NNMP SHED NO:33603030113 AT PCO SALAI IN DIV-61,U-14,Z-05",Own Sources,5,2016-17,2018-19 NE/2016-17/13200,Buildings,Completed,NE-ROYAPURAM,61,275000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT BOOBPATHI NAGAR( NEAR GENGU REDDY SUB WAY) IN DN-61, UNIT-14, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/13201,Buildings,Completed,NE-ROYAPURAM,61,90000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT VEERACHAMY STREET, PUBLIC CONVENIENCE'S AT MURTHY STREET AND TRANSPORT LINE IN DN-61, UNIT-14, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/13202,Buildings,Completed,NE-ROYAPURAM,61,71000,"DE SILTING WORK TO WELL INNER NEAR GENGU RETTY SUB WAY IN DN-61, UNIT-14, ZONE-05",Own Sources,5,2016-17,2018-19 NE/2016-17/14918,Buildings,Completed,NE-ROYAPURAM,61,245000,"IMPROVEMENTS TO PUBLIC CONVEYENCE AT GANDHI IRWN ROAD, EGMORE IN DN-61, U-14, Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/14920,Buildings,Completed,NE-ROYAPURAM,61,165000,"IMPROVEMENTS TO PUBLIC CONVEYENCE AT GOPALASAMY NAGAR, EGMORE IN DN-61, U-14, Z-5.",Own Sources,5,2016-17,2018-19 NE/2016-17/14938,Buildings,Completed,NE-ROYAPURAM,61,700000,"DESILTING AND IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS STREET IN DN-61, UNIT-14, ZONE-5",Own Sources,5,2016-17,2016-17 NE/2016-17/14948,Buildings,Completed,NE-ROYAPURAM,61,565000,"DESILTING AND IMROVEMENTS TO STROM WATER DRAIN AT , VELAYUDHAM ST, AND VARIOUS STREET IN DN-61, UNIT-14, ZONE-5",Own Sources,5,2016-17,2016-17 NE/2016-17/14950,Buildings,Completed,NE-ROYAPURAM,61,544000,"DESILTING AND IMROVEMENTS TO STROM WATER DRAIN AT , EGMORE HIGH ROAD, HALLS ROAD, AND VARIOUS STREET IN DN-61, UNIT-14, ZONE-5",Own Sources,5,2016-17,2016-17 NE/2016-17/15064,Buildings,Completed,NE-ROYAPURAM,61,526000,"IMPROVEMENTS TO THE EXISTING P.C. AT EGMORE HIGH ROAD IN DIV 61, UNIT 14, ZONE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/15506,Buildings,Completed,NE-ROYAPURAM,61,350000,"IMPROVEMENTS TO PC AT SANTHOSE NAGAR, RANGACHARI STREET, CHINNA KUZANDAI STREET IN DIV 61, UNIT 14, ZINE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/15507,Buildings,Completed,NE-ROYAPURAM,61,250000,"IMPROVEMENTS TO PC AT AYYASAMY STREET, LG ROAD, TRANSFARMAR STREET IN DIV 61, UNIT 14, ZINE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/15996,Electrical,Completed,NE-ROYAPURAM,61,573000,"Improvements to Amma Unavagam At pantheon road In div-61,unit-14,zone-05",Own Sources,5,2016-17,2017-18 NE/2016-17/16106,Buildings,Completed,NE-ROYAPURAM,61,87000,"Improvements to Amma Unavagam at Tamil Salai Inside of Children's Hospital in dn-61, unit-14, zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16113,Buildings,Completed,NE-ROYAPURAM,61,118000,"Improvements To Amma Unavagam at Gengu Reddy Road near Subway in dn-61, unit-14, zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16121,Parks,Completed,NE-ROYAPURAM,61,586000,GREENERY ARRANGEMENT TO GANDHI IRWIN ROAD PARK IN DIV-61 UNIT-14 ZONE-05,Own Sources,5,2016-17,2017-18 NE/2016-17/16136,Parks,Completed,NE-ROYAPURAM,61,997000,GREENERY ARRANGEMENT TO L.G.ROAD PARK IN DIV-61 UNIT-14 ZONE-05,Own Sources,5,2016-17,2017-18 NE/2016-17/16216,Buildings,Completed,NE-ROYAPURAM,61,2940000,"REPAIRS & IMPROVEMENT TO PARK IN LANGS GARDEN ROAD AT EGMORE (DUE O VARDHA CCLONE ) IN DN-61, UNIT-14, ZONE-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16258,Buildings,Completed,NE-ROYAPURAM,61,1173000,"RE CONSTRUCTION OF COMPOUND WALL WATER SUPPLY ARRANGEMENTS AND FORMING GREENERY AT GANDHI IRVIN PARK IN GANDHI IRVIN BRIDGE ROAD, DIVISION-61, UNIT-14, ZONE-05",Own Sources,5,2016-17,2017-18 NE/2016-17/16270,Buildings,Completed,NE-ROYAPURAM,61,1195000,"DEMOLITION AND RECONSTRUCTION OF TOILET AT CMS, VARADHARAJAPURAM IN DIV-61, UNIT-14, ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16389,Buildings,Completed,NE-ROYAPURAM,61,56000,"Repairs and Improvements to Chennai Urdu School at Varadharajapuram, Pudupet in Division-61, Unit-14, Zone-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16390,Buildings,Completed,NE-ROYAPURAM,61,109000,"Improvements to Chennai Middle school at Veerasamy street Dn-61, Unit-14, Zone-05",Own Sources,5,2016-17,2017-18 NE/2016-17/17688,Footpath,Completed,NE-ROYAPURAM,61,292000,"Improvements to Footpath at various steets in Division-61, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/17858,Storm Water Drain,Completed,NE-ROYAPURAM,61,644000,"PROVIDING AND FIXING FRC MISSING MAN HOLE DOORS AT VARIOUS STREET & PROVIDING BORE WELL AT RANGACHARI STREET IN DN 61,UNIT 14,ZONE 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/2490,Buildings,Completed,NE-ROYAPURAM,61,475000,"IMPROVEMENTS TO PC AT IYYASAMY STREET IN DIV 61, UNIT 14, ZONE 5,",Own Sources,5,2016-17,2018-19 NE/2016-17/3522,Storm Water Drain,Completed,NE-ROYAPURAM,61,127000,"REPAIRS TO STORM WATER DRAIN AT VARIOUS STREETS IN DN 61, UNIT 14, ZONE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/3533,Buildings,Completed,NE-ROYAPURAM,61,252000,"IMPROVEMENT TO NNMP SHED INCLUDING PAINTING , COLOUR WASHING , WATER SUPPLY ARRANGEMENTS , ELECTRICAL ARRANGEMENTS , VINYL BOARD (FOR VARADHARAJAPURAM CMS SCHOOL) AT PANTHEON SAALAI IN DN 61, UNIT 14, ZONE 5.",Own Sources,5,2016-17,2018-19 NE/2016-17/4179,Roads,Completed,NE-ROYAPURAM,61,999000,"LAYING OF CEMENT CONCRETE ROAD AT KENNET LANE UNDER WARD COUNCILLORS SCHEME WORKS IN DN61,U14,Z5.(REACH-1)",Own Sources,5,2016-17,2016-17 NE/2016-17/4423,Roads,Completed,NE-ROYAPURAM,61,998000,"LAYING OF CEMENT CONCRETE ROAD AT KENNET LANE UNDER WARD COUNCILLORS SCHEME WORKS IN DN61,U14,Z5.(REACH-2)",Own Sources,5,2016-17,2016-17 NE/2016-17/4424,Roads,Completed,NE-ROYAPURAM,61,997000,"LAYING OF CEMENT CONCRETE ROAD AT KENNET LANE UNDER WARD COUNCILLOR SCHEME WORKS IN DN61,U14,Z5.(REACH-3)",Own Sources,5,2016-17,2016-17 NE/2016-17/4568,Roads,Completed,NE-ROYAPURAM,61,998000,"IMPROVEMENTS TO VENGU STREET PLAY GROUND (FOR CONDUCTING BASKET BALL STATE LEVEL TOURNAMENT) IN DIV-61,UN-14,Z-05",Own Sources,5,2016-17,2017-18 NE/2016-17/6287,Buildings,Completed,NE-ROYAPURAM,61,363000,"IMPROVEMENT TO STORM WATER DRAIN AT VARIES STREETS IN DN-61, UNIT-, ZONE-5.",Own Sources,5,2016-17,2018-19 L/2016-17/14215,Electrical,Completed,L-Electrical,62,190100,"Provision of additional wiring and electrification work at Electrical Stores, Chintadripet in div 62 Zone 5",Own Sources,5,2016-17,2016-17 NE/2016-17/0193,Buildings,Completed,NE-ROYAPURAM,62,700000,"PAINTING WORK AND IMPROVEMENTS TO CORPORATION SCHOOLS AND CORPORATION BUILDINGS AT VARIOUS PLACES IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/0194,Buildings,Completed,NE-ROYAPURAM,62,409000,"REPAIRS AND IMPROVEMENTS TO CORPORATION SCHOOLS AND CORPORATION BUILDINGS AT VARIOUS PLACES IN DN-62, UNIT-14,ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/10334,Roads,Completed,NE-ROYAPURAM,62,616000,"Laying of B.T. Road by Paver Finisher at Athipattan Street in Dn-62, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10339,Roads,Completed,NE-ROYAPURAM,62,1943000,"Laying of B.T. Road by Paver Finisher at Iyya (M) Street in Dn-62, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/10343,Roads,Completed,NE-ROYAPURAM,62,4205000,"Laying of B.T. Road by Paver Finisher at West Coovam Road in Dn-62, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/13571,Roads,Completed,NE-ROYAPURAM,62,990000,PROVIDING THE SPEED BREAKERS AND ATTENDING PATCH WORK AT VARIOUS STREET IN DN-62 U-14 Z-5,Own Sources,5,2016-17,2018-19 NE/2016-17/14172,Buildings,Completed,NE-ROYAPURAM,62,900000,"REPAIRS AND IMPROVEMENTS WORKS TO PUBLIC CONVENIENCE AT VARIOUS PLACES IN DN-62,UNIT -14,ZONE-5",Own Sources,5,2016-17,2018-19 NE/2016-17/14907,Storm Water Drain,Completed,NE-ROYAPURAM,62,570000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIV-62, UNIT-14, ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/14958,Storm Water Drain,Completed,NE-ROYAPURAM,62,540000,"DESILTING OF STORM WATER DRAIN AT ARUNACHALAM STREET AND VARIOUS STREET IN DIV-62, UNIT-14, ZONE-5",Own Sources,5,2016-17,2017-18 NE/2016-17/16116,Buildings,Completed,NE-ROYAPURAM,62,116000,"Improvements to Amma Unavagam at West kuvam Road in Div-62,Unit-14,Zone-05",Own Sources,5,2016-17,2017-18 NE/2016-17/16117,Buildings,Completed,NE-ROYAPURAM,62,54000,"Improvements to Amma Unavagam at Arunahalam Street in Div-62,Unit-14,zone-05",Own Sources,5,2016-17,2017-18 NE/2016-17/16343,Buildings,Completed,NE-ROYAPURAM,62,110000,"Repairs and improvements to CHS at west coovam river road in dn-62, unit-14, zone-05",Own Sources,5,2016-17,2017-18 NE/2016-17/16347,Buildings,Completed,NE-ROYAPURAM,62,130000,"repairs and improvements to cms at adhikesavalu street in dn-62, unit-14, zone-05",Own Sources,5,2016-17,2017-18 NE/2016-17/17676,Storm Water Drain,Completed,NE-ROYAPURAM,62,160000,"Improvements to footpath at various streets in Dn.62,U-14,Z-05.",Own Sources,5,2016-17,2017-18 NE/2016-17/18086,Storm Water Drain,Completed,NE-ROYAPURAM,62,105000,"Demolishing and Reconstruction of Storm Water Drain at Arunachalam main road Junction of Nyniyappa (N) street in Dn 62,Unit 14,Zone 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/18087,Storm Water Drain,Completed,NE-ROYAPURAM,62,264000,"Repairing and Improvements for rain water disposal to Storm Water Side Drain at New Balakrishnan street and Mukkiyamman Street in Dn 62,Unit 14,Zone 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/18721,Storm Water Drain,Completed,NE-ROYAPURAM,62,437000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT BALAKRISHNAN STREET, NEW BALAKRISHNAN STREET AND KOVOOR VAITHIYANATHAN STREET IN DN 62,UNIT 14,ZONE 5",Own Sources,5,2016-17,2019-20 NE/2016-17/18948,Storm Water Drain,Completed,NE-ROYAPURAM,62,85000,"Closure of Storm Water Side Drain at Nainiyappa Street in DN 62,Unit 24,Zone 5.",Own Sources,5,2016-17,2019-20 NE/2016-17/2729,Storm Water Drain,Completed,NE-ROYAPURAM,62,996000,"Demolishing and reconstruction the existing storm water drain at ayya (m) street (east side) from palani andavar koil street to jn of east coovam road in dn-62, unit-14, zone-5(for ward councillor fund)",Own Sources,5,2016-17,2016-17 NE/2016-17/2743,Storm Water Drain,Completed,NE-ROYAPURAM,62,999000,"Demolishing and reconstruction the existing storm water drain at wallers road from ritchee street to jn of anna salai in dn-62, unit-14, zone-5(for ward councillor fund)",Own Sources,5,2016-17,2016-17 NE/2016-17/2759,Storm Water Drain,Completed,NE-ROYAPURAM,62,998000,"Demolishing and reconstruction the existing storm water drain at wallers road from singanna (c) street to ritchee street in dn-62, unit-14, zone-5(for ward councillor fund)",Own Sources,5,2016-17,2016-17 NE/2016-17/4520,Buildings,Completed,NE-ROYAPURAM,62,178000,COLOUR WASHING AND PAINTING OF LAB IN CHSS SCHOOL AT WEST KOOVAM ROAD IN DN-62 UNIT-14 ZONE-5.,Own Sources,5,2016-17,2018-19 NE/2016-17/9490,Buildings,Completed,NE-ROYAPURAM,62,987000,"REPAIRS AND IMPROVEMENTS TO PC AT KOVOOR VAITHYANATHAN STREET,PUMPING STATION ,NAVLAR NEDUCHEZIAN COLONY, IN DN-62,UNIT-14,ZONE--5",Own Sources,5,2016-17,2018-19 NE/2016-17/9497,Buildings,Completed,NE-ROYAPURAM,62,971000,"REPAIRS AND IMPROVEMENTS TO PC AT GOVINDHAN STREET,,RITCHEE STREET,COXS COLONY IN DN-62,UNIT-14,ZONE--5",Own Sources,5,2016-17,2018-19 NE/2016-17/9504,Buildings,Completed,NE-ROYAPURAM,62,449000,"CONSTRUCTION A COMPACTOR BIN STAGE FOR GARBAGE BINS AT VARIOUS PLACES IN DN-62,UINT-14,ZONE-5",Own Sources,5,2016-17,2018-19 D/2016-17/0949,Storm Water Drain,Completed,D-Storm Water Drains,63,999000,"Desilting of Cooum River, Below the bridge at Commander in Chief Road (near Ethiraj College ) including removal of obstruction weeds, hyacynth and other floating materials using poclain,special type of float platform and Ramp forming for Vehicle movement Div-63 ,Zone-V .",Own Sources,5,2016-17,2016-17 NE/2016-17/0718,Buildings,Completed,NE-ROYAPURAM,63,998000,"Improvements to community center at Veerabathran street in Dn-63,U-14,Z-05.",Own Sources,5,2016-17,2016-17 NE/2016-17/0840,Buildings,Completed,NE-ROYAPURAM,63,997000,"Improvements to compound wall and passage of the community center at Veerabathran street in Dn-63,U-14,Z-05.",Own Sources,5,2016-17,2016-17 NE/2016-17/10346,Roads,Completed,NE-ROYAPURAM,63,409000,"Laying of B.T. Road by Paver Finisher at Boobegam Street in Dn-63, Unit-14, Zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/11116,Roads,Completed,NE-ROYAPURAM,63,980000,"Improvements to center median at dams road and paiting to footpath at various places in Dn-63,U-14,Z-05.",Own Sources,5,2016-17,2016-17 NE/2016-17/11117,Buildings,Completed,NE-ROYAPURAM,63,890000,"Improvements to E-toilet at dams road and Public convinience at Veeranpuram in Dn-63,U-14,Z-05.",Own Sources,5,2016-17,2017-18 NE/2016-17/11251,Buildings,Completed,B-Buildings,63,820000,Additional Improvements to Health Post at Kanchipuram Pachaiappan Street in Division 63 Zone 5,Own Sources,5,2016-17,2017-18 NE/2016-17/14324,Storm Water Drain,Completed,NE-ROYAPURAM,63,347000,"Desilting of stormwater drain at Anna salai(lic),Anna salai(darga),Narayana street, velayudha street,Naggappa street,L.G Road,Venkatachala street,Kanchipuram pachiappan street,Goyyathope,Veerabadhran street,Aadhithanar Salai,Chandrababu street,Muniapillai streeet,Bharathi salai,G.P Road,Chellapillaiyar street div-63,unit-14,zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/14326,Storm Water Drain,Completed,NE-ROYAPURAM,63,346000,"Desilting to stormwater drain at Begum sahib street,Begum sahib 2nd,3rd and 4th streets,LGN Road,Pycrofts 1st street,Mohandoss road and lane, VN doss Road,Gopaldoss street,Burrah sahib street,Subbaraya street,Hussain mulk street,Nainiappa street,Veerapuram st, Fakhir sahib 3rd street and subedhar Hussain street in div-63,unit-14,zone-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/14721,Storm Water Drain,Completed,NE-ROYAPURAM,63,332000,"Desilting to stormwater drain at Nainiappa st,Gopaldoss Road,V.N doss road, mohandoss lane and road,Anna salai (lic),Naggappa st,L.G road, Venkatachala street,Goyyathope, Thiruvika salai,Begum sahib 10th street,Anna salai(dharga) in div-63,unit-14,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/14723,Storm Water Drain,Completed,NE-ROYAPURAM,63,332000,"DesiltinG to storm water drain at subbraya street, Burrah sahib st,Aadhithanar salai,veerabadran st,Kanchipuram pachiappan st,Chandra babu st,velayudam st,Narayana street opp.to mosque in div-63,unit-14,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/14724,Storm Water Drain,Completed,NE-ROYAPURAM,63,330000,"Desilting to storm water drain at Thiru vi ka salai,Chellapillaiyar koil st,Hussain mulk st,Veerapuram st,Fakhir sahib 3rd st,Subedar Hussain st,L.G road,Begum sahib,2nd and 10th st in div-63,unit-14,zone-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/15252,Storm Water Drain,Completed,NE-ROYAPURAM,63,999000,"Improvements to storm water drain at various places in Dn-63,Unit-13,Zone-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15253,Buildings,Completed,NE-ROYAPURAM,63,680000,"Providing water supply and electrical arrangements at various corporation buildings in Dn-63,Unit-13,Zone-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15254,Buildings,Completed,NE-ROYAPURAM,63,320000,"Improvements to office buildings at Various places in Dn-63,Unit-13,Zone-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15661,Storm Water Drain,Completed,NE-ROYAPURAM,63,520000,"Improvements to storm water drain at L.G.N slum in Dn-63,U-14,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/15662,Storm Water Drain,Completed,NE-ROYAPURAM,63,540000,"Improvements to storm water drain at G.P road,Chella pillayar koil street,Bharathi salai,Narayana naicken street,Kanchi pachaiyappa street and various places in Dn-63,U-14,Z-05.",Own Sources,5,2016-17,2018-19 NE/2016-17/16134,Parks,Completed,NE-ROYAPURAM,63,825000,GREENERY ARRANGEMENT TO L.G.ROAD PARK IN DIV-63 UNIT-14 ZONE-05,Own Sources,5,2016-17,2017-18 NE/2016-17/16224,Buildings,Completed,NE-ROYAPURAM,63,838000,"REPAIR & IMPROVEMENT TO PARK IN LANGS GARDEN ROAD EAST SIDE AT EGMORE IN DN-63, U1-14, Z-5.",Own Sources,5,2016-17,2017-18 NE/2016-17/16249,Buildings,Completed,NE-ROYAPURAM,63,375000,"IMPROVEMENTS TO PUBLIC CONVEYANCE AT SOUTH KOOVAM STREET IN DN-63, U-14, Z-5 (vardha cyclone)",Own Sources,5,2016-17,2017-18 NE/2016-17/4182,Buildings,Completed,NE-ROYAPURAM,63,998000,"IMPROVEMENTS TO CORPORATION SCHOOL CAMPUS AT NAGAPPAN STREET IN DIV-63,UNIT-14,ZONE-5.",Own Sources,5,2016-17,2016-17 NE/2016-17/6248,Roads,Completed,NE-ROYAPURAM,63,999000,"Improvement to PC at Kalimanpuram in Dn-63,U-14,Z-05",Own Sources,5,2016-17,2017-18 NE/2016-17/9879,Buildings,Completed,NE-ROYAPURAM,63,983000,"CONSTRUCTION OF PUBLIC CONVIENCE AT PUMPING STATION JN OF ARUNACHALAM STREET IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2016-17,2018-19 BR/2016-17/0030,Roads,Completed,BR-Bus Route Roads,64,2482000,Traffic Improvement Works at Various Bus Route Roads in Zone VI & VIII,Own Sources,6,2016-17,2019-20 L/2016-17/11413,Electrical,Completed,L-Electrical,64,938900,"Supply and replacement of 52nos of analogue timer units for the new fixing and for the completely worn-out units in various places in div 64,65 zone VI",Own Sources,6,2016-17,2017-18 L/2016-17/13266,Electrical,Completed,L-Electrical,64,749900,"Supply and replacement of 10nos of damaged Kiosk Pillar box with timer units in various places in div 64,65, 68 and 69 zone VI",Own Sources,6,2016-17,2017-18 L/2016-17/13966,Electrical,Completed,L-Electrical,64,1296100,Provision of additional new 7nos of 7mtr GI single arch lamp post (3nos with 150w to 165w LED Fittings for main track side and 4nos of additional arch bracket for service road side with 2x150w to 165w LED Fittings) with 13nos of LED Fittings at newly constructed Grade separator and 10nos of 8mtr double straight bracket at the portion of realingment of centre median by department of highways in Jawaharlal Nehru salai junction of perambur redhills road and Erattai eri kadappa road in zone VI (by Deposit Work),Deposit Works,6,2016-17,2017-18 L/2016-17/17550,Electrical,Completed,L-Electrical,64,1253100,Restoration of 286nos of damaged lamp post at various places in interior road and bus route road due to vardah cyclone in div 64 to 78 zone VI,Own Sources,6,2016-17,2017-18 L/2016-17/18704,Electrical,Completed,L-Electrical,64,894600,"Replacement of 500nos of damaged fuse box, removal of 53nos of damaged KIOSK Pillar boxes and 57nos of damaged lamp post at various places in interior road and bus route road due to vardah cyclone in div 64 to 78 zone VI",Own Sources,6,2016-17,2018-19 L/2016-17/18889,Electrical,Completed,L-Electrical,64,554200,Provision of additional new 8nos of 8mtr GI single arch lamp post with 4nos of LED Fittings at widening portion of Grade Seperator and pedestrian subway in kolathur irattai eri juction of Perambur Redhills road and inner ring road in zone VI (by Deposit Work),Deposit Works,6,2016-17,2017-18 NF/2016-17/10507,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,312000,"Relaying existing BT Road with BC 30mm thick at Yamuna Nagar 1st Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10518,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,920000,"Relaying existing BT Road with BC 30mm thick at selliamman Nagar 1st to 5th street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10522,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,348000,"Relaying existing BT Road with BC 30mm thick at Girjia Nagar 1st Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10535,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,483000,"Relaying existing BT Road with BC 30mm thick at Samudhriya Colony 2nd street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10538,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,486000,"Relaying existing BT Road with BC 30mm thick at Siva Sakthi Nagar Main Road in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10542,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,362000,"Relaying existing BT Road with BC 30mm thick at Thirupathi nagar 4th Cross street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10551,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,208000,"Relaying existing BT Road with BC 30mm thick at Anjugam Nagar 2nd cross street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10557,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,348000,"Relaying existing BT Road with BC 30mm thick at Anjugam Nagar 3rd cross street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10560,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,241000,"Relaying existing BT Road with BC 30mm thick at Girija nagar East Cross street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10564,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,756000,"Relaying existing BT Road with BC 30mm thick at Anjugam Nagar 1st Cross Main Road in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10567,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,329000,"Relaying existing BT Road with BC 30mm thick at TNHB Colony North Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10573,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,537000,"Relaying existing BT Road with BC 30mm thick at TNHB Colony East Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10578,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,174000,"Relaying existing BT Road with BC 30mm thick at Varadhan Kuttai 1st Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10582,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,146000,"Relaying existing BT Road with BC 30mm thick at Varadhan Kuttai 2nd Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10585,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,174000,"Relaying existing BT Road with BC 30mm thick at Varadhan Kuttai 3rd Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10587,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,146000,"Relaying existing BT Road with BC 30mm thick at Varadhan Kuttai 4th Street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10590,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,241000,"Relaying existing BT Road with BC 30mm thick at Girija Nagar 2nd street in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/12831,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,52000,"Repairs And Improvements to Amma Unavagam (Phase I) At Sembium Redhills Road in Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/13133,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,183000,"Writing Slogans For Compactor Metal Bins @ Various Locations In Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/13274,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,92000,"Supplying Gunny bags with sand filling for bund and baracading wall in SWD to avoid over flow @ Various street (Precaution Vardha Cyclone) in Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2016-17 NF/2016-17/14048,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,89000,"Repairs and Improvements Existing Public Convenience at Thiruveethi amman koil street in dn-64,unit-15,zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/14049,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,95000,"Repairs and Improvements Existing Public Convenience at Nermai Nagar in dn-64,unit-15,zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/14071,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,376000,"Temporary Restoration of Flood Damaged CC Road at Nermai Nagar Ambedkar Nagar 1st main road in dn-64,unit-15,zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/14075,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,64000,"Temporary Restoration of Flood Damaged Inspection Chamber at Various Streets in dn-64,unit-15,zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/14965,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,18000,"Providing Composed bins @ Nermai Nagar, Thiru.Vi.Ka. Nagar,Poombuhar Nagar 2nd Main Road in dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2016-17 NF/2016-17/16692,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,386000,"Providing Street Furniture Damaged Due to Vardha Cyclone @ Bhagavathi Ammal Street,Thirupathi Nagar, Balaji Nagar, Poombuhar Nagar, Rajan Nagar,Thenpalani Nagar, Vallar Street, Somanadhapuram 2nd Street, SS Avenue,Srivelmurugan Avenue And Various Street in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16726,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,170000,"Repairs & Improvements Exisitng Footpath Damaged due to Vardha Cyclone at VP Sindhan Nagar in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16732,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,348000,"Repairs & Improvements Exisitng Footpath Damaged due to Vardha Cyclone at V.V.Nagar Main Road in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16735,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,1025000,"Repairs & Improvements Exisitng Footpath Damaged due to Vardha Cyclone at Poompuhar Nagar 2nd Main Raod in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16742,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,1028686,"Repairs & Improvements Exisitng Footpath Damaged due to Vardha Cyclone at Balaji Nagar Main Road in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16747,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,340000,"Relaying BT Road Damaged Due To Vardha Cyclone at Shanthi Nagar 4th Cross Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16748,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,892000,"Relaying BT Road Damaged Due To Vardha Cyclone at Ambedkar Nagaer Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16750,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,840000,"Relaying BT Road Damaged Due To Vardha Cyclone at Anjugam Nagar 4th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16751,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,317000,"Relaying BT Road Damaged Due To Vardha Cyclone at Anjugam Nagar 7th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16753,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,343000,"Relaying BT Road Damaged Due To Vardha Cyclone at Yamuna Nagar In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16755,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,524000,"Relaying BT Road Damaged Due To Vardha Cyclone at Bharathi Nagar 1st Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16756,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,524000,"Relaying BT Road Damaged Due To Vardha Cyclone at Bharathi Nagar 2nd Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16763,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,345000,"Relaying BT Road Damaged Due To Vardha Cyclone at Bharathi Nagar 1st Cross Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16765,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,345000,"Relaying BT Road Damaged Due To Vardha Cyclone at Bharathi Nagar 2nd Cross Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16767,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,686000,"Relaying BT Road Damaged Due To Vardha Cyclone at Haridoss Nagar Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16772,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,518000,"Relaying BT Road Damaged Due To Vardha Cyclone at Thirupathi Nagar 5th Cross Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16775,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,524000,"Relaying BT Road Damaged Due To Vardha Cyclone at Lakshmi Nagar Avenue In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16776,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,280000,"Relaying BT Road Damaged Due To Vardha Cyclone at Ramakrishna Nagar In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16779,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,280000,"Relaying BT Road Damaged Due To Vardha Cyclone at Ganapathi Rao Nagar In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16795,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,820000,"Relaying BT Road Damaged Due To Vardha Cyclone at Velavan Nagar Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16798,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,653000,"Relaying BT Road Damaged Due To Vardha Cyclone at Thirumurugan Nagar 1st Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16799,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,554000,"Relaying BT Road Damaged Due To Vardha Cyclone at Thirumurugan Nagar 2nd Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16800,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,833000,"Relaying BT Road Damaged Due To Vardha Cyclone at Thirumurugan Nagar 3rd Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16803,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,605000,"Relaying BT Road Damaged Due To Vardha Cyclone at Velavan Nagar Service Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16805,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,452000,"Relaying BT Road Damaged Due To Vardha Cyclone at Sathya Sai Nagar In Dn-64,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/3364,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,839000,"Desilting & Improvements to the exisitng stormwater drain @ Anjugam Nagar 4th,11th,15th,18th,19th streets and other streets (IR Roads)in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3371,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,997000,"Desilting & Improvements to the exisitng stormwater drain @ Poompuhar nagar streets,Poompuhar nagar cross Streets and other streets(IR Roads) in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3386,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,998000,"Desilting & Improvements to the exisitng stormwater drain @ Raja Rajeshwari nagar ,Venkateshwara nagar, Jeyaram nagar, RKR nagar ,VV nagar,Murugan nagar, Annai sathya nagar, Haridoss streets and other streets(IR Roads) in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3387,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,842000,"Desilting & Improvements to the exisitng stormwater drain @ M.N.nagar,Agatheeswarar nagar,Subramani nagar, Quaida millath street, Thiru.Vi.Ka nagar and other streets(IR Roads) in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3398,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,989000,"Desilting & Improvements to the exisitng stormwater drain @ Balaji nagar,Nermai nagar,Thirupathi nagar ,Thirupathi nagar Extn and other streets (IR Roads)in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3399,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,923000,"Desilting & Improvements to the exisitng stormwater drain @ Velmurugan Avenue,Valarmathi Nagar,Dhanammal Nagar,United colony and other streets (IR Roads)in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3467,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,998000,"Desilting & Improvements to the exisitng stormwater drain @ Poombughar nagar 1st main road, Balaji Nagar main road, Kolathur South mada st, East mada st, Kolathur redhills road & sembium redhills road (BRR Roads)in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/5931,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,950000,"Proposed Construction Amma Unavagam at Anjugam Nagar 18th Main Road in Dn-64,unit-15,Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/6186,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,95000,"Repairs & Improvements to Amma Unavagam at Sembium Redhills Road in Dn-64, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/6274,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,666000,"Improvements and construction of inspection chamber to the existing storm water drain at Paper Mills Road, Redhills High Road And Other Streets in Dn-64,unit-15,Zone-06",Own Sources,6,2016-17,2018-19 NF/2016-17/6769,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,56000,"Painting works for Center median and Footpath at Sembium redhills road,Kolathur redhills road in dn-64,unit-15,zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/7312,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,600000,"Improvements to the existing Anjugam Nagar park at Anjugam Nagar 4th street in dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/7394,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,600000,"Improvements to the existing park at Poompuhar Nagar 4th street in dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/7395,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,600000,"Improvements to the existing V.V Nagar park at V.V Nagar in dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/7606,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,600000,"Improvements to the exisitng class room in Annexure building @ CHSS in School road in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/7610,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,600000,"Improvements to the exisitng class room in CPS @ School road in Dn-64,Unit-15,Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/9501,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,981000,"Forming Of Speed Breaker As Per IRC Standards at Poompuhar Nagar, Balaji Nagar, Jeyaraman Nagar, Tirupathi Nagar and various streets in Dn -64, Unit -15,Zone-6",Own Sources,6,2016-17,2016-17 NF/2016-17/9503,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,980000,"Forming Of Speed Breaker As Per IRC Standards at Nermai Nagar,Velvan Nagar,Lakshmi Nagar,Venkateshwara Nagar,Durga Colony and various streets in Dn -64, Unit -15,Zone-6",Own Sources,6,2016-17,2016-17 BR/2016-17/17755,Roads,Completed,BR-Bus Route Roads,65,1680000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Perambur Barracks road,Papermills road,Strahans road, Perambur high road north, Perambur high road north,Demollus road,Pulianthope high road,etc., in Zone-6",Grants,6,2016-17,2017-18 J/2016-17/18319,Bridges,Completed,J-Bridges,65,1500000,"Repair and Re- Constructions of hand rail wall in Bridges and Subways at Retteri Junction, Division-65, Zone-VI",Grants,6,2016-17,2017-18 NF/2016-17/10618,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1420000,"Relaying existing BT road with BC 30mm thick at Thiruvalluvar Nagar 1 to 5 streeets in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/10620,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1041000,"Relaying existing BT road with BC 30mm thick at Senthil Nagar 3rd main road in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10621,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1221000,"Relaying existing BT road with BC 30mm thick at Mahveer Nagar 1,2,3& 4th streets in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2019-20 NF/2016-17/10623,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,981000,"Relaying existing BT road with BC 30mm thick at Sastri nagar 1,2,3 street & Rohini streets in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/11423,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,989000,"CONSTRUCTION OF COMPOUND WALL,FALSE CEILING AND FLOORING TILES FOR AMMA UNAVAGAM G.K.M.COLONY AT JAMBULINGAM MAIN ROAD IN DIV:65,UNIT:15,ZONE:06",Own Sources,6,2016-17,2016-17 NF/2016-17/11879,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,183000,"Improvements to Dust bin at Thirumurugan nagar and Raising door work in various street in Div-65,Unit-15,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/11880,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,64000,"Improvement to well rings at Burial ground and tree guard at Division office in Dn-65,Unit-15,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14284,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,54000,MAINTENANCE OF PARK BY PRIVATE AGENCY AT MAHAVEER PARK IN DIV -65 U-15 ZONE -06,Own Sources,6,2016-17,2018-19 NF/2016-17/15208,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,85000,IMPROVEMENT AND MAINTANANCE OF CORPORATION PRIMARY SCHOOL IN SRINIVASAN NAGAR 3RD MAIN ROAD IN DN 65 UNIT 15 ZONE 06,Own Sources,6,2016-17,2016-17 NF/2016-17/16678,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,900000,"Construction of Compound wall for Dilapidated portion around Mr.Hussain Colony,Senthil Nagar 10th Street, R.K Syndicate Nagar park damaged due to Vardha Cyclone at Jangiram Reddy Colony In dn-65,Unit-15,Zone-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16687,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,76000,"Construction of Compound Wall For Dilapidated portion in CPS damaged due to Vardha Cyclone at Srinivaa Nagar 3rd Main Road in dn-65,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16715,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1170000,RESTORATON OF DAMAGED ROAD IN MURUGAN KOVIL STREET DUE TO VARDHA CYCLONE IN DIV 65 UNIT 15 ZONE 06,Own Sources,6,2016-17,2017-18 NF/2016-17/16722,Footpath,Completed,NF-THIRU-VI-KA NAGAR,65,1020000,RESTORATION OF DAMAGED IN FOOD PATH DUE TO VARDHA CYCLONE STREET IN SENTHIL NAGAR 2ND AND 3RD STREET THILAI NAGAR 1ST STREET JAYANTHINAGAR JAMBULINGAM MAIN ROAD AND OTHER STREETS DN65 UNIT 15 ZONE 06,Own Sources,6,2016-17,2017-18 NF/2016-17/16793,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,378000,"PROVIDING AND FIXING STREET FURNITURE (SA,DA) AT VARIOUS LOCATION IN DN65 U15 Z06",Own Sources,6,2016-17,2017-18 NF/2016-17/18404,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,63500,"MAINTENANCE OF PARK BY PRIVATE AGENCY AT RK SYNTICATE PARK IN DN-65,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/18605,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,58500,"Maintenance of Thanthai Periyar Park at Senthil nagar 13th street in Dn.65,Unit-15,Zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18606,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,64000,"Maintenance of Thanthai Periyar Park at Senthil nagar 10th street in Div-65,Unit-15,Zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/18608,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,63500,"Maintenance of Park at Janakiram reddy colony in Div-65,Unit-15,Zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/3430,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,490000,"REPAIRS AND IMPROVEMENTS TO FLOOD AFFECTED CMS FOR OPEN SPACE PROVIDING CONCRETE AT SRINIVASAN STREET IN DN-65, U-15, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/3444,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,786000,"Deslting & Improvements to the existing Storm water drain @ Rajaji nagar palani st,sasthri nagar ,Gkm colony 2nd,25th street Teachers colony main road, 2nd cross st and other streets in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2019-20 NF/2016-17/3446,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,716000,"Deslting & Improvements to the existing Storm water drain @ Vivekananda nagar, Venus nagar 1st,3rd,4th street Ganesh nagar 2nd street and other streets in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3453,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,623000,"Desilting & Improvements to the existing Storm water drain @ Subramanipuram 1st,2nd street,Rajan nagar main road,Srinivasa nagar 1st,2nd,3rd,street , Srinivasa nagar 5th ,6th cross street and other streets in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3454,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,536000,"Deslting & Improvements to the existing Storm water drain @ Janakiraman colony 1st cross street,Rangadoss colony 1st,2nd cross street,Nethaji nagar 1st,5th street and other streets in Dn-65, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/5153,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,115000,"IMPROVEMENT TO DIVISION OFFICE AND AMMA UNAVAGAM , SENTHIL NAGAR 10TH STREET PARK, MAGAVEER PARK IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/5154,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,79000,"REPAIR TO EXISTING SILT CATCH PITS AT SENTHIL NAGAR 1ST MAIN ROAD, SRINIVASAN NAGAR 1ST NAIN ROAD AND NETHAJI STREET, JUMBULINGAM MAIN ROAD IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/5155,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,154000,"PROVIDING DRYNAGE ARRANGEMENT TO TOILET BLOCK FOR CPS AT SRINIVASAN STREET IN DN-65, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/5224,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,184000,"RAISING AND LOWERING FLOOD AFFECTED STORM WATER DRAIN MANHOLE DOORS AND PIPELINES WORKS AT VARIOUS STREETS IN DN-65, U-5, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/5922,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,754000,"CONSTRUCTION OF TOILET BLOCK INSIDE OF CPS SCHOOL CAMPUS AT G.K.M COLONY 27TH STREET IN DIV-65,UN-15,Z-06 (MLA FUND 2015-2016)",MLACDS,6,2016-17,2017-18 NF/2016-17/5934,Electrical,Completed,NF-THIRU-VI-KA NAGAR,65,748000,"PROVIDING DEEP BORE WELL AND WATER SUPPLY ARRANGEMENTS TO CPS SCHOOL BUILDING AT G.K.M COLONY 27TH STREET IN DIV-65,UN-15,Z-06 (MLA FUND 2015-16)",MLACDS,6,2016-17,2017-18 NF/2016-17/5940,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,960000,"Proposed Construction of Amma Unavagam at GKM Colony Jambulingam main road in Dn-65,Unit-15,Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/6554,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,285000,"LOWERING AND RAISING TO FLOOD AFFECTED STORM WATER DRAIN MANHOLE DOORS AND PIPELINES AT VEENUS NAGAR AND VARIOUS STREETS IN DN-65, U-15, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/6555,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,475000,"Temporary Restoration of Flood Damaged pipe line to link Storm Water Drain and RWH at V.V.Nagar 2nd Street and Kolathur Redhills Road in Dn-65,Unit-15,Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/6557,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,189000,"IMPROVEMENT TO DUST BIN PAINTING WORK AT VARIES STREETS IN DN-65, U-15,Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/6560,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,102000,"IMPROVEMENTS TO FLOOD AFFECTED FOOTPATH WALL PAINTING WORK AT VARIOUS STREET IN DN-65, U-15,Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/6999,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,527000,"CONSTRUCTION OF SWD SIZE 600MM X 750 MM IN FLOOD AFFECTED AREA TO AVOID WATER STAGNATION AT APPAR STREET IN VENUS NAGAR IN DN-65, U-15,ZN-6.",Own Sources,6,2016-17,2019-20 NF/2016-17/7001,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,527000,"CONSTRUCTION OF SWD SIZE 600MM X 750 MM IN FLOOD AFFECTED AREA TO AVOID WATER STAGNATION AT VENUS NAGAR 7TH MAIN ROAD CONNECTING 100FT ROAD IN DN-65, U-15,ZN-6.",Own Sources,6,2016-17,2019-20 BR/2016-17/7592,Road Cut,Completed,BR-Bus Route Roads,66,280000,"Restoration of Road Cut made by service department at Venkataraman salai in Dn-66, Zone-06",Deposit Works,6,2016-17,2017-18 L/2016-17/13267,Electrical,Completed,L-Electrical,66,679200,"Supply and replacement of 10nos of damaged Kiosk Pillar box with timer units in various places in div 66,67,68 and 69 zone VI",Own Sources,6,2016-17,2017-18 NF/2016-17/10465,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,762000,"Relaying the BT road with BC 30mm thick at Aandal avenue 1st street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/10466,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,624000,"Relaying the BT road with BC 30mm thick at Thiyagarajan street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/11902,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,67000,Supplying of Red Earth and Manure for Tree planting at Lakshman nagar in Dn66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/13845,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,74000,"Attending Patchwork using M20 Grade concrete at Bhasyam street,Ramamoorthy colony main road,Temple 1st cross street,Venkatesan salai in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14676,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,834000,"Special Repair works and Providing Manholes arrangement for Existing SWD at siva Elanga salai ( Western side) in div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/14677,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,970000,"Special Repair works and Providing Manholes arrangement for Existing SWD at Siva elango salai (Eastern portion ) in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/15102,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,112000,"Attending Patchwork using M20 grade concrete at Nagammal street,Jeganathan salai,Periyar nagar 6th street in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/15183,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,60000,"Construction of Inspection chambers at Papermills road, S.R.P Colony,Krishna nagar in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/15198,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,240000,"Letter writing for Compactor bins at Various places in Div-66,Unit=16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/15202,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,66000,"Construction of Kitchen waste composed pit at Venkatesan salai,Jawahar nagar 5th main road,Ram nagar 3rd main road,Kumaran nagar main road,Chelliamman koil street and SRP Colony 6th street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/15241,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,36500,"Painting for Compactor bins at Various places in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/16641,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,420000,Repair works and improvements to Existing footpath at Siva Elango Salai In Dn66 U16 Z6,Own Sources,6,2016-17,2017-18 NF/2016-17/16642,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,690000,"Repair works and improvements to Existing footpath at Jawahar Nagar 1,2,3,4 Main Road in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16643,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,790000,"Repair works and improvements to Existing footpath at Jawahar Nagar 5,6 Main Road, 1,2,3 Cross Street in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16644,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,730000,"Repair works and improvements to Existing footpath at Jawahar Nagar 1 to 5 Circular Road, 2 Cross Street in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16645,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,490000,"Repair works and improvements to Existing footpath at Temple Road and 2 Cross Streets in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16646,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,650000,"Repair works and improvements to Existing footpath at Karthigeyan Salai in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16648,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,720000,"Repair works and improvements to Existing footpath at Kandhasamy Salai, Balasubramanian Salai, Jaganathan Salai, venkatraman Salai in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16649,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,650000,"Repair works and improvements to Existing footpath at Andal Avenue 1st,2nd Street, Krishna Nagar 1,2,3 Streets, Nagammall Street, Raghavan Street, Manavalan Street, in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16650,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,740000,"Repair works and improvements to Existing footpath at Kumaran Nagar 1 to 4 Cross Streets and 1 to 4 Main Road, Ramani Bai Colony, 80 Feet Road in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16651,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,755000,"Repair works and improvements to Existing footpath at Thangavel Street, Paul Vargheese Street, Veera Raghavan Street, Jayaraman Street(N),Kuppusamy Street, Ayyalu Street in Dn - 66, Unit - 16, Zone - 06.",Own Sources,6,2016-17,2017-18 NF/2016-17/16652,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,640000,"Repair works and improvements to Existing footpath at Lakshman Nagar Main Road, West Street, 2nd Cross Street, Sakthivel Nagar School Road, 7th Cross Street, 3rd Cross Street, 2nd Cross Street in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16653,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,800000,"Repair works and improvements to Existing footpath at Govindhasamy Street, Ram Nagar 1,2 Main Road, SRP Colony Main Road, SRP Colony 6,3,2,9, 13,14,7,8 Streetin Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16654,Footpath,Completed,NF-THIRU-VI-KA NAGAR,66,515000,"Repair works and improvements to Existing footpath at Chandrasekaran Salai, Periyar Nagar 5,6,7,8,9,10,19,20,21 Streets in Dn - 66, Unit - 16, Zone - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16713,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,735000,REPAIR WORKS AND IMPROVEMENTS TO PARK AT JAWAHAR NAGAR 5TH MAIN ROAD IN DN66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/16718,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,580000,REPAIR WORKS AND IMPROVEMENTS TO PARK AT PERIYAR NAGAR 20TH STREET IN DN66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/16721,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,510000,REPAIR WORKS AND IMPROVEMENTS TO PARK AT SAKTHIVEL NAGAR IN DN66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/16724,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,450000,REPAIR WORKS AND IMPROVEMENTS TO PARK AT JAWAHAR NAGAR 2ND CIRCULAR ROAD IN DN66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/16725,Playfields,Completed,NF-THIRU-VI-KA NAGAR,66,450000,REPAIR WORKS AND IMPROVEMENTS TO CHILDRENS PLAY FEILD AT RAM NAGAR 2ND MAIN ROAD IN DN66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/16730,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,255000,REPAIR WORKS AND IMPROVEMENTS TO AMMA UNAVAGAM P-II AT KARTHIKEYAN SALAI IN DN66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/17925,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,285000,"PROVIDING AND FIXING STREET FURNITURE (SA,DA) AT VARIOUS LOCATION IN DN66 U16 Z06",Own Sources,6,2016-17,2017-18 NF/2016-17/18168,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,165000,"Improvements to Footpath at Kandasamy salai & Periyar nagar 5th street junction in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/18169,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,69000,"Attending Repair works to E-Service center at Temple road in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/18172,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,34000,"Attending Repair works to Jawahar nagar 2nd circular and 5th main road parks in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/18173,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,19900,"Construction of Inlet chamber for Drainout purpose at SRP Colony 3rd street in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/18396,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,32500,"Attending repair works to Scout office at Jawahar nagar 1st circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/18397,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,65400,"Maintanance of Park by Private agency for at Sakthivel nagar park in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18398,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,130500,"Maintanance of Park by Private agency for six month at Jawahar nagar 5th main road in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18699,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,990000,"Supply,Installation and Commissioning of High quality treated Drinking water plant (RO/UV FILTRATION) of 2000 Litres/Hour capacity at Periyar nagar Pheriperal hospital campus,Karthikeyan salai in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/18700,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,980000,"Operation and Maintanance of High quality treated Drinking water plant (RO/UV Filtration) of 2000 Litres / Hour capacity for 1Year period at Periyar nagar Pheriperal hospital campus,Karthikeyan salai in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2019-20 NF/2016-17/3366,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,997000,Construction of Batmitton indoor stadium Boundary Wall at Jawahar nagar 1st Circular road in Dn66 U16 Z06,Own Sources,6,2016-17,2018-19 NF/2016-17/3432,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,53000,"Construction of Inspection chamber at Jeganathan salai,SRP Colony main road,Varadharajan street,Krishna nagar main road,Kuppusamy street,Sarashwathi street and various streets in div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3436,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,989000,Providing Roofing arrangements (Truss with Corrugated MS Sheet) for Batmitton indoor Stadium and 2Nos Batmitton Court at Jawahar Nagar 1st Circular Road in Dn66 U16 Z06,Own Sources,6,2016-17,2017-18 NF/2016-17/3438,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,998000,Construction of Batmitton indoor stadium Superstructure at Jawahar nagar 1st Circular road in Dn66 U16 Z06(Ward councilor devolopement Scheme2016-17),Own Sources,6,2016-17,2017-18 NF/2016-17/3511,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,984000,"Dismantling existing colapsed SWD and Reconstruction of RCC SWD at Nagammal street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/3512,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,970000,"Desilting of SWD at Jawahar nagar 1 to 6th main road, 1 to 5th circular road, Temple road and 5th cross street, Siva elango salai two sides in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/3513,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,970000,"Desilting of SWD at Periyar nagar Karthikeyan salai,Jeganathan salai,Balasubramaniam salai,Kandasamy salai,Venkatraman salai,Periyar nagar 14th & 16th street, 4th cross street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/3515,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,925000,"Desilting of SWD at Ramamoorthy colony,Lakshman nagar,Bashyam street,Sivaprakasam street,Kuppusamy street,Thiruvengadam street,Saraswati street,Thangavel street,Sivalingam street,Sivapoosanam street,Rangasamy street,Krishnamoorthy street and other streets in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/3516,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,870000,"Desilting of SWD at Chandrasekaran salai,Venkatesan salai,SRP colony main road and 2,3,4,6,7,8,9,10th streets,Ram nagar in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/3517,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,980000,"Desilting of SWD at Sakthivel nagar 1 to 7 streets,School road,Annal gandhi street,Ragavendra link road,Sakthivinayagar kovil street,Venugopal street,Govindasamy street,Krishnamoorthy street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/3518,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,760000,"Desilting of SWD at kumaran nagar,Chelliamman kudieruppu,Karthick street,Manavalan street,Gandhimathi street,Nagammal street,Kumaran nagar 1,2,4th cross street,Dhanraj street,Murthy street,Kannappan street,Boopathy street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/3519,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,838000,"Desilting of SWD at Papermills road two sides,Krishna nagar,Kumarasamy street,Aandal avenue 1,2,3 streets and Varatharajan street in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/3977,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,800000,Improvements and Existing Repair works to MLA office at Jawahar Nagar 1st Circular road in Dn66 U16 Z06,Own Sources,6,2016-17,2016-17 NF/2016-17/4852,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,110000,"Construction of Compound wall for EB Transformer at Ramamoorthy colony 3rd street and Attending Patchwork at Nagammal street,Periyar nagar 14th street and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/6733,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,375000,"Construction of RCC Sump for Amma unavagam at Periyar nagar Pheripheral hospital in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2016-17 NF/2016-17/6734,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,895000,"Providing Outer flooring Arrangement,Repair works to existing Compound wall,Rack arrangement,False ceiling arrangement For Amma unavagam Phase-II at Periyar nagar Pheripheral Hospital in Div-66,Unit-16,Zone-6",Own Sources,6,2016-17,2016-17 NF/2016-17/8059,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,165000,"Construction of Inspection chamber and Raising storm water drain MH doors at Kumaran nagar 4th cross street,Lakshman nagar main road,SRP Colony main road,Krishna nagar main road,Manavalan street,SRP Colony 2nd street ,Chandrasekaran salai and various streets and Repairs to BIO-GAS Plant grinting machine and Pipelines,etc,. in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/8162,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,845000,"Construction of Compound wall for Amma unavagam at Periyar nagar Peripheral hospital campus ,Karthikeyan salai in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/8726,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,21000,"Painting for Storm water drain Manholes Chute pipe portion at Jawahar nagar 1st main road,Karthikeyan salai,Balasubramanian salai,Chandrasekaran salai & Kumaran nagar 80feet road in Div-66,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/0669,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,57000,"Repair and Improvements to CHSS at Market street in Div-67,Unit-15,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/0670,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,115000,"Repair & Improvements to School & Anganvadi @ GKM Colony 27TH street in Div-67,Unit-15,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/0671,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,28000,"Repair and Improvements to Rangasayee school & Amma unavagam loco scheme in Div-67,Unit-15,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/0672,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,18000,"Raising the MH doors in GKM Colony Jumpulingam main road and various streets in Div-67,Unit-15,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/0673,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,63000,"Repair & Improvements to CHS Somiya Street & Anganvadi at GKM Colony 6th street in Div-67, Unit -15 , Zone - 6.",Own Sources,6,2016-17,2017-18 NF/2016-17/10952,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,235000,"Repairs and Improvements to existing flood affected Public convenience at Jeganathan salai in Div-67,Unit-15,Zone-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/13149,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,82000,"IMPROVEMENT TO MANHOLE DOOR RAICING WORK AT VARIOUS STREET IN FLOOD AFFECTED AREA IN DN-67, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/1524,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,351000,"TEMPORARY RESTORATION FLOOD DAMAGED CC ROAD PATCH WORK AT GKM COLONY 13TH TO 20TH STREET, SAI NAGAR, RANGASAYEE STREET AND VARIOUS STREET IN DN-67, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/16662,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,394000,"Construction of Dilapidated portion Compound Around Anandan park & Childrens park damaged due to Vardha Cyclone at Thanthondri Amman Koil Street in Dn-67,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16669,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,385000,"Construction of Compound wall for dilapidated portion in CMS damage due to Vardha Cyclone at Rangashyee st in Dn-67, Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16749,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,270000,"REPAIR WORKS AND IMPROVEMENTS TO COMPOUND WALL AT DIVISION -OFFICE CAMPUS IN DN - 67, UNIT - 15 ZONE - VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16768,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,377000,"PROVIDING AND FIXING STREET FURNITURE (SA,DA) AT VARIOUS LOCATION IN DN 67 U15 Z06",Own Sources,6,2016-17,2017-18 NF/2016-17/16808,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,920000,Relaying BT Road Damaged Due to Vadha Cyclone at GKM Colony Main road from 3rd street to 6th street in Dn 67 Unit 15 Zone 6,Own Sources,6,2016-17,2017-18 NF/2016-17/16828,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,920000,Relaying BT Road Damaged Due to Vadha Cyclone at GKM Colony Main road from 6th street to 8th street in Dn 67 Unit 15 Zone 6,Own Sources,6,2016-17,2017-18 NF/2016-17/16829,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,920000,Relaying BT Road Damaged Due to Vadha Cyclone at GKM Colony Main road from 8th street to 11th street in Dn 67 Unit 15 Zone 6,Own Sources,6,2016-17,2017-18 NF/2016-17/16843,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,920000,"Relaying BT Road Damaged Due to Vardha Cyclone at GKM Colony Main road From 1st street to 3rd street in Dn-67,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/17598,Footpath,Completed,NF-THIRU-VI-KA NAGAR,67,970000,"Repairs & Improvements Exisitng Footpath Damaged due to Vardha Cyclone at Muthukumarappa Salai in Dn-67,Unit-15,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/18158,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,460000,"REPAIR AND IMPROVEMENT TO FLOOD AFFECTED CHENNAI CORPORATION VARIOUS SCHOOLS AT DN-67, U-15, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/18159,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,29000,"REPAIR AND IMPROVEMENT TO FLOOD AFFECTED AMMA UNAVAGAM AT LOCO SCHEME 2ND STREET DN-67, U-15, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/18160,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,12700,"REPAIR AND IMPROVEMENT TO FLOOD AFFECTED ANAND PARK OPP DIVISION OFFICE DN-67, U-15, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/18161,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,63000,"IMPROVEMENT TO DUST BIN AND FLOOD AFFECTED FOOTPATH WALL PAINTING AT VARIOUS STREETS IN DN-67, U-15, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/18613,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,62500,"MAINTENANCE OF ANANDAN PARK AT THANTHONRIAMMAN KOIL STREET IN DIV 67, UNIT 15, ZONE 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/3357,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,252000,"Special Improvements Kithcen Shed and Toilet block at CHS School Somiya Street in div-67, Unit-15, Zone-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/3457,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,705000,"Deslting & Improvements to the existing Storm water drain @ Rangasayee street ,Markewt street, Loco scheme 1st, 2nd street GKM colony main road(1st to 9th st) and other streets in Dn-67, Unit-15, Zone-06",Own Sources,6,2016-17,2016-17 NF/2016-17/3461,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,700000,"Deslting & Improvements to the existing Storm water drain @ GKM colony (11 to 24 A St) GKM colony 9th,11th,12th,13th,17th,19th,22nd street and other streets in Dn-67, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3462,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,700000,"Deslting & Improvements to the existing Storm water drain @ Venkatesan nagar VOCst, Bharathiyar st, Kattabomman st (part) Sai nagar 2nd,3rd,4th street and other streets in Dn-67, Unit-15, Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/5175,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,990000,"Restoration of Roadcut made by TNEB at Muthukumarappa Street (From Kalaivanar st to East level crossing railway gate) in Dn-67,unit-15,Zone-06",Deposit Works,6,2016-17,2018-19 NF/2016-17/6731,Footpath,Completed,NF-THIRU-VI-KA NAGAR,67,227000,"IMPROVEMENT TO DUST BIN PAINTING WORK AT VARIOUS STREETS AND FOOTPATH PAINTING AT JUMBULINGAM MAIN ROAD & S.R.P KOVIL STREET IN DN-67, U-15, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/6779,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,500000,"Improvements to existing Flood affected Storm water drain and raising doors at Various streets in Div-67,Unit-15,Zone-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/7996,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,90000,"IMPROVEMENTS TO FLOOD AFFECTED MANHOLE DOORS AT VARIOUS STREETS IN DN-67, U-5, Z-6.",Own Sources,6,2016-17,2016-17 L/2016-17/13268,Electrical,Completed,L-Electrical,68,882900,"Supply and replacement of 13nos of damaged Kiosk Pillar box with timer units in various places in div 68,69, 70 and 73(p) zone VI",Own Sources,6,2016-17,2017-18 NF/2016-17/16639,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,445000,IMPROVEMENT WORKS AT HUSSAIN PARK AND KKR PARK DAMAGED BY VARDHA CYCLONE IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2016-17,2017-18 NF/2016-17/16700,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,403000,IMPROVEMENT WORKS TO THE DISPENSARY BUILDING AT PALLAVAN SALAI DAMAGED BY VARDHA CYCLONE IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2016-17,2017-18 NF/2016-17/16705,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,153000,IMPROVEMENT WORKS TO THE DISPENSARY BUILDING AT PAPER MILLS ROAD DAMAGED BY VARDHA CYCLONE IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2016-17,2017-18 NF/2016-17/18392,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,62000,"Maintanence of Park by Privatation Engaging Out Sourcing for six month at KKR Avenue Near Pallavan Salai in Dn 68, Unit 16, Zone 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/18393,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,70500,"Maintanence of Park by Privatation Engaging Out Sourcing for six month at Sajith Hussain Park at Paper Mills Road in Dn 68, Unit 16, Zone 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/18394,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,71500,"Maintanence of Park by Privatation Engaging Out Sourcing for six month at George Colony Park in Dn 68, Unit 16, Zone 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/2356,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,940000,"Dismantling and Reconstruction of Storm Water Drain From CPS Urudu (Ch 0 to 50) at Madurai Samy Madam Street in Dn-68, Unit-16, Zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/2639,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,940000,"Dismantling and Reconstruction of Storm Water Drain From CPS Urudu (Ch 51 to 100) at Madurai Samy Madam Street in Dn-68, Unit-16, Zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/2667,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,985000,"PROVIDING SPEED BREAKERS AT VARIOUS STREET IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3303,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,960000,"DESILTING OF SWD AT Madura Samy Madam Street, 2nd Street, Jai Beam Nagar, State Bank Colony And Various Street IN DN 68, UNIT-16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/3354,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,980000,"DESILTING OF SWD AT KENNADY SQUARE CROSS ST AND 1ST STREET, SRP KOIL STREET, PAPER MILS ROAD , KENNADY SQUARE MAIN ROAD AND VARIOUS STREET IN DN 68, UNIT-16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/3525,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,700000,"DISMANTLING, DESLITING AND RAISING BRICK WORK EXISTING STORM WATER DRAIN FROM ANDAL AVENUE 1 ST STREET TO KAMARAJAR NAGAR 3 rd STREET (0 TO 80 Mtr) AT S.R.P. KOIL STREET(NORTH) IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/4366,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,104000,"REPAIRING GROUP PINS AT MADURAI SAMY MADAM ST , FISH MARKET , PALLAVAN SALAI IN DN 68 UNIT 16 ZONE 6",Own Sources,6,2016-17,2017-18 NF/2016-17/5897,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,40000,"Repairing water supply arrangements to Dispensary building at Papermills road inDiv-68,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/5953,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1500000,"CONSTRUCTION OF PUBLIC DISTRIBUTION CENTER (RATION SHOP No CRS CA043) AND WATER SUPPLY ARRANGEMENT AT JAI BEAM NAGAR IN DN - 68, UNIT - 16, ZONE - 6 (MLA FUND 2015-2016)",MLACDS,6,2016-17,2017-18 NF/2016-17/6006,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1500000,"CONSTRUCTION OF PUBLIC DISTRIBUTION CENTER (RATION SHOP No CRS CA045) AND WATER SUPPLY ARRANGEMENT AT JAI BEAM NAGAR IN DN - 68, UNIT - 16, ZONE - 6 (MLA FUND 2014-2015)",MLACDS,6,2016-17,2017-18 NF/2016-17/6400,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,55000,"PROVIDING AND PLACING WELL RINGS FOR COMPOST YARD IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/6404,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,41000,"REPAIRING WATER SUPPLY ARRANGEMENTS TO NNMP SHED NO 07040 & 07041 TEEDS GARDEN 1 ST ST IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/6551,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,693000,"SPECIAL REPAIRS AND DESILTING WORKS OF SWD AT THIRU VI KA NAGAR MAIN ST PRAKASAM ST , GURUSAMY STREET ,LAKSHMI NAGAR AND VARIOUS STREET IN DN 68, UNIT-16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/6552,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,650000,"SPECIAL REPAIRS AND DESILTING WORKS OF SWD AT PONNUSAMY NAGAR 1 ST STREET , PONNUSAMY NAGAR 2 ND ST , PONNUSAMY NAGAR 3 RD STREET AND VARIOUS STREETS IN DN 68 UNIT 16 ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/6553,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,25000,"SUPPLY AND FIXING OF PUBLIC CONVINIENCE NAME BOARDS AT SRP KOIL ST , PALLAVAN SALAI , MADURAI SAMY MADAM ST , THILLAI NAYAGAM 2 ND ST IN DN 68 UNIT 16 ZONE 6",Own Sources,6,2016-17,2017-18 NF/2016-17/6603,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,700000,"DISMANTLING, DESLITING AND RAISING BRICK WORK EXISTING STORM WATER DRAIN FROM KAMARAJ 3 RD STREET TO KAMARAJ 1 ST STREET (81 TO 160 Mtr) AT S.R.P. KOIL STREET(NORTH) IN DN 68 UNIT 16 ZONE 6",Own Sources,6,2016-17,2018-19 NF/2016-17/6604,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,700000,"DISMANTLING, DESLITING AND RAISING BRICK WORK EXISTING STORM WATER DRAIN FROM KAMARAJ 1 ST STREET TO PALLAVAN SALAI JN (161 TO 240 Mtr) IN DN 68 UNIT 16 ZONE 6",Own Sources,6,2016-17,2018-19 NF/2016-17/8308,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,72000,REPAIRING DRAINAGE LINES AND OTHER IMPROVEMENT WORKS TO CMS AT THIRU. VI.KA.NAGAR IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2016-17,2017-18 NF/2016-17/9067,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,43600,REPAIRS AND IMPROVEMENTS TO THE NIGHT SHELTER AT DN 68 UNIT 16 ZONE 6,Own Sources,6,2016-17,2017-18 NF/2016-17/9068,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,219000,PROVIDING KITCHEN SHED AND OTHER IMPROVEMENTS WORKS TO CMS AT GOPALAPURAM IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2016-17,2017-18 BR/2016-17/18621,Footpath,Completed,BR-Bus Route Roads,69,195000,Providing and Laying of Disabled friendly Ramp for Stainless steel Bus shelters in various Bus route roads in Zone -6.,Own Sources,6,2016-17,2017-18 NF/2016-17/0316,Footpath,Completed,NF-THIRU-VI-KA NAGAR,69,196000,"REPAIRS TO FOOTPATH KERBS AND ILBK AND SWD AT SIRUVALLUR ROAD, CENTER MEDIAN AT PERAMBUR SIGNAL PILKINGTON ROAD AND REPAIRS TO FOOTPATH AND PAINTING AT ANDERSON ROAD IN DN 69, UNIT- 16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/0319,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,307000,"PROVIDING BOREWELL, IMPROVEMENTS TO WATER SUPPLY ARRANGEMENTS, DRAINAGE AND PVC DOORS TO TOILET BLOCKS AND REPAIRS TO JET PUMPS AND ELECTRIFICATION AT CHS BLOCK 1,2 & 3 AT BUNDER GARDEN STREET IN DN 69, UNIT- 16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/0343,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,77000,"REPAIRS TO TOILET, WATER SUPPLY AND DRAINAGE FACILITIES AT AMMA UNAVAGAM AT MH ROAD IN DN 69,UNIT-16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/0348,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,164000,"REPAIRS TO FLOORING, PAINTING, DRAINAGE, FRC DOORS AND ELECTRICAL ARRANGEMENTS TO DIVISION OFFICE BUILDING AT RAJA STREETAND LABOUR ROOM AND DISPENSARY AT KABILAR ST AND CI, AO OFFICE BUILDING AT ANDERSON ROAD IN DN 69, UNIT-16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/0351,Footpath,Completed,NF-THIRU-VI-KA NAGAR,69,72000,"PROVIDING DUSTBIN PLATFORM AT BUNDER GARDEN MAIN STREET AND CC PATCHES AT VARIOUS STREETS IN DN 69, UNIT-16, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/11954,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,67000,"REPAIRS WORKS FOR FLOORING, PLUMBING, DRAINAGE FACILITIES AT ZONAL OFFICE BUILDING IN DN 69, UNIT- 16, ZONE-VI",Own Sources,6,2016-17,2017-18 NF/2016-17/12753,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,91000,"PROVIDING ALUMINIUM PARTITION,VINYL FLOORING AND ROOFING FOR ADDITIONAL ARASU CABLE CENTER AT ZONAL OFFICE IN DN 69, UNIT-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/14318,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,273000,"REPAIRS AND MAINTENANCE OF PUBLIC CONVINEANCE PCs AT MH ROAD, PONNUVELPURAM, THIKKAKULAM, MADURAI STREET, ANDERSON ROAD IN DN 69, U-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/14461,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,134000,"PROVIDING SPEED BREAKERS AT SIRUVALLUR ROAD IN DN-69, UNIT-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/14471,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,71000,"REPAIRS TO TOILETS AND PROVIDING MS SHEET DOORS FOR TOILETS IN CHS BUNDER GARDEN STREET IN DN-69, UNIT-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/14684,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,44000,"PROVIDING SS HANDRAIL TO ENTRANCE RAMP AT CMS MADURAI STREET IN DN 69, UNIT-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/15325,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,27000,"PROVIDING DRINKING WATER STORAGE FACILITY AT AMMA UNAVAGAM IN DN 69, U-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/15332,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,37000,"SUPPLYING AND FIXING COMPOST BINS AT MADHAVARAM HIGH ROAD IN DN 69, U-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/15334,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,68000,"REPAIRS TO SWD RAGHAVAN STREET & SIRUVALLUR ROAD IN DN 69, U-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/16694,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,255000,"Providing Street Furniture Damaged Due to Vardha Cyclone @ Vasantha Garden,Papermills road chockalingham street and various streets",Own Sources,6,2016-17,2017-18 NF/2016-17/16789,Footpath,Completed,NF-THIRU-VI-KA NAGAR,69,1029000,"Repairs & Improvements Existing Footpath Damaged due to Vardha cyclone at Siruvallur road in Dn-69,Unit-16,Zone-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16792,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,92000,"CONSTRUCTION OF COMPOUND WALL FOR DILAPIDATED PORTION AT ISLAND PARK DAMAGED DUE TO VARDHA CYCLONE AT ANDERSON ROAD IN DN-69,UNIT-16,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16794,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,91000,"CONSTRUCTION OF LADIES GYM COMPOUND WALL FOR DILAPIDATED PORTION AT ISLAND PARK DAMAGED DUE TO VARDHA CYCLONE AT SADAYAPPAN DOSS STREET IN DN-69,UNIT-16,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16960,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,114000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO PUBLIC CONVENIENCE AT MADHAVARAM HIGH ROAD IN DN 69, U-16, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/17970,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,1326000,"RESTORATION OF ROADCUT MADE BY CMWSSB AT PILKINGDON ROAD IN DN - 69, UNIT - 16, ZONE - 06",Deposit Works,6,2016-17,2018-19 NF/2016-17/3359,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,970000,"DESILTING OF SWD AT RAGHAVAN ST, MH ROAD, KABILAR ST, JAWAHAR ROAD, BUNDER GARDEN MAIN STREET, 1STSTREET, 2ND STREET & VARIOUS STREET IN DN -69 UNIT-16 ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/3361,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,960000,"DESILTING OF SWD AT ANDERSON ROAD, PHILKINGTON ROAD, VASANTHA GARDEN MAIN ROAD, MADURAI STREET, & VARIOUS STREETS IN DN -69 UNIT-16 ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/3607,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,998000,"SPECIAL IMPROVEMENT AND PROVIDING PLAY APPARATUS FOR CHILDRENS AT MIDDLE SCHOOL MADURAI STREET IN DN-69, UNIT-16, ZONE-6.( UNDER WARD COUNCILOR DEVELOPMENT FUNDS FOR THE YEAR 2016-17)",Own Sources,6,2016-17,2017-18 NF/2016-17/3608,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,998000,"SPECIAL IMPROVEMENT TO CHENNAI HIGH SCHOOL BLACK-2 AT BUNDER GUARDEN IN DN-69, UNIT-16, ZONE-6.( UNDER WARD COUNCILOR DEVELOPMENT FUNDS FOR THE YEAR 2016-17)",Own Sources,6,2016-17,2017-18 NF/2016-17/3610,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,998000,"SPECIAL IMPROVEMENT TO CHENNAI MIDDLE SCHOOL AT KABILAR STREET, MADUMA NAGAR IN DN-69, UNIT-16, ZONE-6.( UNDER WARD COUNCILOR DEVELOPMENT FUNDS FOR THE YEAR 2016-17)",Own Sources,6,2016-17,2016-17 NF/2016-17/6637,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,700000,CONSTRUCTION OF STORM WATER DRAIN LINK AT JAWHAR STREET TO KABILAR STREET AND SWD LINK FROM ANDERSON ROAD TO RAILWAY CANAL IN DN 69 UNIT 16 ZONE 6.,Own Sources,6,2016-17,2019-20 B/2016-17/3286,Buildings,Completed,B-Buildings,70,12000000,"CONSTRUCTION OF TWO WHEELER PARKING WITH TOILET BLOCK IN GROUND FLOOR AND 2+2+2 CLASSROOMS (F.F+S.F+T.F) IN CPS AND C.M.S. TELEGU MEDIUM AND TAMIL MEDIUM SCHOOL, AT SCHOOL ROAD, (M.H.ROAD) PERAMBUR IN DN-70, ZONE-6",MLACDS,6,2016-17,2018-19 BR/2016-17/7585,Road Cut,Completed,BR-Bus Route Roads,70,395000,"Restoration of Road Cut at Perambur High Road (NORTH) (At the Junction of Perambur Railway station ) by CMWSSB in Dn-70, Zone-06",Deposit Works,6,2016-17,2017-18 BR/2016-17/7594,Road Cut,Completed,BR-Bus Route Roads,70,995000,"Restoration of Road Cut made by service department at Perambur papermills road in Dn-70, Zone-06",Deposit Works,6,2016-17,2017-18 J/2016-17/18334,Bridges,Completed,J-Bridges,70,408000,"Repair and Re-Construction of hand rail wall across Otteri Nallah canal at Stephenson road bridge in Dn-70, Zone-VI",Grants,6,2016-17,2017-18 NF/2016-17/11224,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,855000,"Electrical and plumbing arrangement for AMMA unavagam phase -2 at P.H.Road in div-70,uint-16,zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/12923,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1104000,"RELAYING B.T ROAD BY PAVER AT SCHOOL ROAD IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/13936,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,306000,"Providing and fixing of Unidirectional RPM or Road studs and painting the speed brakers at Various Street in Dn-70,Uint.-16, Zone.-6",Own Sources,6,2016-17,2019-20 NF/2016-17/15030,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,995000,"CONSTRUCTION OF MULTI PURPOSE HALL AT PERAMBUR HIGH ROAD (JAMALIA) IN DN-70, UNIT-16, ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16523,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,223000,"IMPROVEMENTS TO MURASOLIMARAN PARK DAMAGED DUE TO VARDHA CYCLONE AT PERAMBUR HIGH ROAD IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16525,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,172000,"IMPROVEMENTS TO PARK AT VADIVELU 2ND STREET,DAMAGED DUE TO VARDHA CYCLONE IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16527,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,177000,"IMPROVEMENTS TO GANDHI PARK ,DAMAGED DUE TO VARDHA CYCLONE AT PERAMBUR HIGH ROAD IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16758,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,371000,"Providing and fixing street furniture damaged due to vardha cyclone at various street ( bharathi main road,perambur high road etc..) in div-70,uint-16,zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/16778,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,207000,"CONSTRUCTION OF COMPOUND DAMAGED DUE TO VARDHA CYCLONE AT CGHSS SCHOOL BUILDING (SOUTH SIDE) AT M.H.ROAD(SCHOOL ROAD) IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/18006,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,268500,"Maintenance of Park at Murasolimaran Park in Dn.70,Unit-16,Zone-6(By QualifiedHorticulturist For six month)",Own Sources,6,2016-17,2018-19 NF/2016-17/18008,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,89500,Name of Work: Maintenance of Vadivel(M)2nd cross street park and Kannabiran kovil street Park at Perambur in division 70 unit 16 zone 6 (By QualifiedHorticulturist For six month),Own Sources,6,2016-17,2018-19 NF/2016-17/18011,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,90500,"MAINTANANCE OF RAGIV GANDHI PARK AT PH ROAD IN DN 70,UNIT 16, ZONE 6,",Own Sources,6,2016-17,2018-19 NF/2016-17/4573,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,999000,"Desilting of swd at p.h.road north and south ,Dr.Ambedkar collage road,m.p.m.street,m.h.road,jamaliya main road,p.h.road 1st street,state bank colony,and various road in div 70,uint-16,zone-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/4669,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,979000,"providing QET LAB (for 9th and 8th std) in ROOM No 16 & 17 at Chennai High school 9th.building at Southern side in School road in Division-70,Unit-16,Zone-6(WARD COUNSELOR FUND)",Own Sources,6,2016-17,2016-17 NF/2016-17/4670,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,985000,"providing COMPUTER LAB at Chennai High school 9th.building at Southern side in School road and H.M.building in Division-70,Unit-16,Zone-6(WARD COUNSELOR FUND)",Own Sources,6,2016-17,2016-17 NF/2016-17/4838,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,968000,providing false ceiling & dinning arrangement at ph-2 amma unavagam in DN 70 U 16 Z 6,Own Sources,6,2016-17,2016-17 NF/2016-17/6464,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,980000,Construction of Amma Unavagan phase-II at P.H.road (north) in dn-70 unit-16 zone-6,Own Sources,6,2016-17,2016-17 NF/2016-17/6720,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,999000,"DESILTING OF SWD AT VADIVEL MAIN STREET, BHARATHI MAIN ROAD, KUMARASAMY STREET, GOVINDAN STREET ,BHARATHY 1ST AND 2ND STREET,CHINAIYA COLONY 1ST AND 2ND MAIN ROAD AND VARIOUS STREET IN DN-70 UNIT-16, ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/8080,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,981000,"Dismantling and Reconstruction of Dilapilated portion of Storm Water Drain opp to Dn .No 123, 124 of Perambur High Road IN Dn 70, Unit 16, Zone 6",Own Sources,6,2016-17,2016-17 NF/2016-17/8821,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,264000,"improvement to amma unavagam building at Bharathi road due to vardha cyclone in Dn-70,Unit-16,zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/8830,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,340000,"SUPPLYING AND FIXING MANHOLE AT VARIOUS STREET IN DN-70,UNIT-16,ZONE-6",Own Sources,6,2016-17,2017-18 L/2016-17/13269,Electrical,Completed,L-Electrical,71,679200,"Supply and replacement of 10nos of damaged Kiosk Pillar box with timer units in various places in div 68,69, 71,75 and 76 zone VI",Own Sources,6,2016-17,2017-18 NF/2016-17/11088,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2290000,"LAYING OF BT ROAD AT MALAYAPPAN STREET IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2016-17,2019-20 NF/2016-17/11095,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,150000,"REPAIR AND MAINTENANCE WORKS TO AMMA UNAVAGAM AT PERAMBUR HIGH ROAD (SOUTH) IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/11385,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,308000,"SUPPLYING AND ERECTING OF PORTABLE PC's AT KONNUR HIGH ROAD IN DN-71,UNIT-16,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/13940,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,224000,"PAINTING TO FOOTPATH KERB AT PH ROAD (SOUTH) AND KH ROAD IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/16443,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,110000,CONSTRUCTION OF DAMAGED ROAD SIDE PARK COMPOUND WALL DUE TO VARDHA CYCLONE AT CHANDRAYOGI SAMADHI STREET IN DN-71 UNIT-16 ZONE-6,Own Sources,6,2016-17,2017-18 NF/2016-17/16720,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,40000,"CONCTRUCTION OF DAMAGED COMPUND WALL AT LORRY STATION DUE TO CYCLONE AT CHANDRAYOGI SAMADHI STREET IN DN71,UNIT16,ZONE6",Own Sources,6,2016-17,2017-18 NF/2016-17/16723,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,257000,"Construction of damaged compund wall due to VARADHA cyclone at ward office in perambur high road south in dn-71,unit-16,zone",Own Sources,6,2016-17,2017-18 NF/2016-17/17996,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,290000,"MAINTENANCE OF MURASOLI MARAN PARK AT PERAMBUR HIGH ROAD (SOUTH) IN Dn-71,UNIT-16,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/3486,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,980000,"Desilting of swd at chandrayogi samadhi street,samiyar madam street,tank bund road,new tank bund road,krishnadoss main road,kh road,ph road (south),bashyam reddy 3rd street",Own Sources,6,2016-17,2018-19 NF/2016-17/5850,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,995000,"DESILTING THE EGANGIPURAM CANAL FROM PERAMBUR HIGH ROAD TO EGANGIPURAM ROAD CULVERT IN DN-71, U-16, Z-6",Own Sources,6,2016-17,2016-17 NF/2016-17/5862,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,469000,"DESILTING THE CANAL FROM RAJIV GANDHI NAGAR TO KONNUR HIGH ROAD IN DN-71, U-16, Z-6",Own Sources,6,2016-17,2016-17 NF/2016-17/6010,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,988000,Construction of Amma Unavagan phase-II at chandrayogi samadhi street in dn-71 unit-16 zone-6,Own Sources,6,2016-17,2016-17 NF/2016-17/6187,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,910000,PROVIDING WATER SUPPLY AND DRAINAGE ARRANGEMENTS TO AMMA UNAVAGAM -PHASE II AT CHANDRAYOGI SAMADHI STEET IN DN 71 UNIT 16 ZONE 6,Own Sources,6,2016-17,2016-17 NF/2016-17/7525,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,790000,"Desilting and Repairs to swd at semathamman colony main street,semathamman colony 3rd street and krishnadoss road in Dn-71,Unit-16,Zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/7913,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,808000,"Forming Of Speed Breaker As Per IRC Standards at various streets in Dn -71, Unit -16, Zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/8016,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,990000,"Dismantling existing colapsed SWD and Reconstruction of RCC SWD at Krishnadass main road FROM COOKS ROAD TO RAIN TREE FLAT under ward councilor fund (2016-2017)in Div-71,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/8023,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,995000,"Dismantling existing colapsed SWD and Reconstruction of RCC SWD at Krishnadass road from raintree appartment TANCY under ward councilor fund (2016-2017) office in Div-71,Unit-16,Zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/8045,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,995000,"Dismantling existing colapsed SWD and Reconstruction of RCC SWD at krishnadass road FROM TANCY TO RANI KALYANA MANDABAM under ward councillor fund (2016-2017) Div-71,Unit-16,Zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/8369,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,119000,REPAIR AND ART WORKS TO LKG ROOM AT CHENNAI PRIMARY SCHOOL AT KRISHNADOSS ROAD IN DN-71 UNIT-16 ZONE-6,Own Sources,6,2016-17,2017-18 NF/2016-17/8370,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,74015,Providing name board and repair works to cattle depot at chandrayogi samadhi street in dn-71 unit-16 zone-6,Own Sources,6,2016-17,2017-18 BR/2016-17/19433,Road Cut,Completed,BR-Bus Route Roads,72,1940000,"Restoration or Road cut made by TANTRANSCO in Basin power house road( from GMR vasavi gate to police booth, in Div- 72,Zone-6",Deposit Works,6,2016-17,2017-18 L/2016-17/13270,Electrical,Completed,L-Electrical,72,679200,"Supply and replacement of 10nos of damaged Kiosk Pillar box with timer units in various places in div 68,69,72,77 and 78 zone VI",Own Sources,6,2016-17,2017-18 NF/2016-17/0728,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,450000,"IMPROVEMENT WORK IN NNMP CENTRE 070419 AT DOSS NAGAR IN DN-72, UNIT-17, ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/10894,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,907000,"Desilting the Railway Canal Between Dass nagar and Otterinullah Canal in DN72,Unit-17,Zone-06.",Own Sources,6,2016-17,2018-19 NF/2016-17/10895,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,742000,"DESILTING THE CHANNEL FROM PULIYANTHOPE HIGH ROAD BRIDGE TO INFALL POINT OF OTTERI NULLAH CANAL AND VASUKI NAGAR OTTERI NULLAH CANAL ,IN DN-72,UNIT-17,ZONE-06.",Own Sources,6,2016-17,2018-19 NF/2016-17/11314,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,9300,"SUPPLY AND FIXING PUBLIC CONVINIENCE NAME BOARDS AT VARIOS STREETS IN DN 72, UNIT 17 ZONE 6",Own Sources,6,2016-17,2018-19 NF/2016-17/11345,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,115000,"REPAIRS AND IMPROMENT WORKS AT COMPOUND WALL AT DECASTER ROAD (OPP)DOOR N0 21,IN DIV 72-UNIT 17-ZONE06",Own Sources,6,2016-17,2018-19 NF/2016-17/11638,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,214000,"SUPPLYING AND FIXING MANHOLE FRAME WITH DOOR AT VARIOUS STREES IN DN-72, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/11649,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,51000,"REPAIRS AND IMPROVEMENTS TO DESIGANANDHA PARK IN DN-72, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/11652,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,114000,REPAIRS AND IMPROVEMENTS TO SLAUGHTER HOUSE IN DN 72 UNIT 17 ZONE 6,Own Sources,6,2016-17,2018-19 NF/2016-17/11987,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,42000,"REPAIRING WATER SUPPLY ARRANGEMENTS THIRU.VI.KA. NAGAR SCHOOL DIV-72 , UNIT-17,ZONE-06.",Own Sources,6,2016-17,2018-19 NF/2016-17/12197,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,68300,"IMPROVEMENTS TO DIVISION OFFICE AT V.O.C. NAGAR 1ST STREET IN DN-72, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/12198,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,193000,"IMPROMENTS WORKS TO PLAY GROUND ATT.V.K NAGAR MAIN ROAD IN DIV72,UNIT 17,ZONE06",Own Sources,6,2016-17,2018-19 NF/2016-17/12939,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,46000,REPAIRING WATER SUPPLY ARRANGEMENTS AND DRAINAGE ARRANGEMENTS TO NARASIMA NAGAR SCHOOL IN DN 72 UNIT 17 ZONE 6,Own Sources,6,2016-17,2018-19 NF/2016-17/1302,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,840000,"LAYING OF CC ROAD AT NARASIMMAN NAGAR 1ST CROSS STREET (CH. 0 TO 100 MTR.) IN DN.72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2016-17 NF/2016-17/1455,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,858000,"LAYING OF CC ROAD AT NARASIMMAN NAGAR 1ST CROSS STREET (CH. 100 TO 204 MTR.) IN DN.72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2016-17 NF/2016-17/16773,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,253000,"PROVIDING AND FIXING STREET FURNITURE AT VARIOUS STREET DAMAGED DUE TO VARDHA CYCLONE IN DN-72,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/3378,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,996000,"Desilting in strom water drain at various street in dn-72, u-17, zone-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/4057,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,800000,"LAYING OF CC ROAD AT NARASIMMAN NAGAR 1 ST STREET ( CH. O TO 100 MTR.) IN DN. 72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/4058,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,750000,"LAYING OF CC ROAD AT NARASIMMAN NAGAR 1 ST STREET ( CH. 100 TO 200 MTR.) IN DN. 72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2016-17 NF/2016-17/4061,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,945000,"LAYING OF CC ROAD AT NARASIMMAN NAGAR 3 RD STREET (FROM HARNESS AND SADDLE FACTORY ROAD TO DOOR NO.24) IN DN.72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/4062,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,935000,"LAYING OF CC ROAD AT NARASIMMAN NAGAR 3 RD STREET (FROM DOOR NO.24 TO DOOR NO.40) IN DN. 72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/4065,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,940000,"LAYING OF CC ROAD AT NARASIMMAN NAGAR 3RD STREET (FROM DOOR NO.40 TO NARASIMMAN NAGAR 5TH STREET) IN DN.72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/4465,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,540000,LAYING CC ROAD M20 GRADE CONCRETE AT VASUKI NAGAR MAIN ROAD ( CH 0-60 ) IN DN 72 UNIT 17 ZONE 6,Own Sources,6,2016-17,2018-19 NF/2016-17/4466,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,540000,LAYING CC ROAD M20 GRADE CONCRETE AT VASUKI NAGAR MAIN ROAD ( (CH 60-120) IN DN 72 UNIT 17 ZONE 6,Own Sources,6,2016-17,2018-19 NF/2016-17/4467,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,680000,LAYING CC ROAD M20 GRADE CONCRETE AT SASTRI NAGAR 1 ST & 2 ND CROSS STREET IN DN 72 UNIT 17 ZONE 6,Own Sources,6,2016-17,2018-19 NF/2016-17/4468,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,690000,"LAYING CC ROAD M20 GRADE CONCRETE AT SASTRI NAGAR 19TH , 20TH , 21ST , 22ND STREET IN DN 72 UNIT 17 ZONE 6",Own Sources,6,2016-17,2018-19 NF/2016-17/6408,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,600000,"REPAIR AND IMPROVEMENT WORK AT AMMA UNAVAGAM, 2ND STREET, THIRU. VI. KA NAGAR, DN-72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/6412,Electrical,Completed,NF-THIRU-VI-KA NAGAR,72,255000,"IMPROVEMENT WORK AT AMMA UNAVAGAM, VENKATESAPURAM NEW COLONY, DN-72, UNIT-17, ZONE-06.",Own Sources,6,2016-17,2018-19 NF/2016-17/9037,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,110000,REPAIRS AND IMPROVEMENTS TO PC AT POWDER MILLS ROAD IN DN 72 UNIT 17 ZONE 6,Own Sources,6,2016-17,2018-19 BR/2016-17/0031,Roads,Completed,BR-Bus Route Roads,73,2459000,"Traffic Improvement works at Various Bus Route Roads in Zone - III, VI, VII & VIII",Own Sources,6,2016-17,2019-20 NF/2016-17/10784,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,370000,"IMPROVEMENTS TO NNMP SHED(NO:33603060103) AT NATCHARAMMAL STREET IN PULIANTHOPE DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/10885,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,173000,"Desilting of storm water drain (open drain) at stephenson road in dn-73,unit-17,zone-6",Own Sources,6,2016-17,2018-19 NF/2016-17/11390,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,960000,"CEILING RENOVATION WORK & COLOUR WASHING TO URUDHU SCHOOL AT MANNARSAMY KOIL STREET IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/11391,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,600000,"REPAIR AND ELECTRICAL ARRANGEMENT TO URUDHU SCHOOL AT MANNARSAMY KOIL STREET IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/12947,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,69200,Improvements and maintenance to Gandhi nagar PC at Pullianthop High road (Covering the PC from public view) in Dn 73 Unit 17 Z 6,Own Sources,6,2016-17,2017-18 NF/2016-17/12948,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,291000,Repairs and improvements to PC at Powdermills Road ground in Dn 73 Unit 17 Zone 6,Own Sources,6,2016-17,2017-18 NF/2016-17/12949,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,461000,Erecting portable PC at Powdermills Road ground in Dn 73 Unit 17 Zone 6,Own Sources,6,2016-17,2017-18 NF/2016-17/12950,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,56000,Repairs and Improvements to Powdermills road NNMP shed in Dn 73 Unit 17 Zone 6,Own Sources,6,2016-17,2017-18 NF/2016-17/12951,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,19000,Repairs and improvements to Thiruvengadasamy CMS and Cooks road footpath in Dn 73 Unit 17 Zone 6,Own Sources,6,2016-17,2017-18 NF/2016-17/1374,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,22000,"Repairs and Maintanence to CWC at Thiruvengada samy street @dn-73,unit-17,zone-VI",Own Sources,6,2016-17,2017-18 NF/2016-17/1375,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,18000,"Repairs and Improvements to existing Wadia Health post at Cooks Road @dn-73 , Unit-17, ZoneVI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1376,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,36000,"Repairs and Improvements to existing CPS at Cooks Road @dn-73, Unit-17, Zone-VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1377,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,47500,"Repairs And Improvements to the Existing Amma Unavagam at Old Zonal Office Building In DR.Ambedkar College Road @ Dn-73,Unit-17, Zone-VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1378,Electrical,Completed,NF-THIRU-VI-KA NAGAR,73,44500,"Refixing and of motors Affected by flooding at Various Places IN DN-73, Unit-17, ,Zone-VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1379,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,73000,"Rrepairs and Improvements To Existing Foot Path and open side drain at DR. Ambedkar College Road @ Dn-73, Unit-17, Zone-VI",Own Sources,6,2016-17,2017-18 NF/2016-17/1380,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,20000,"Repairs and Improvements to The Existing PC At Jn of Decaster Rd and Dr.Ambedkar College @ dn-73, Unit-17, Zone -VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1381,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,37000,"Improvements to the Existing Road side Park next to the division office 73 @ Dn-73 ,Unit-17, Zone-VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1383,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,18000,"Repairs and Improvements to AE/JE offie at new ferrance road @dn-73, unit-17,zone-VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1384,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,30000,"Construction of Inspection Chambers @ CMS at Ammaiammal street in DN-73,unit-17,zone-VI",Own Sources,6,2016-17,2017-18 NF/2016-17/1385,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,21500,"Repairs and improvements to NNMP shed at New ferrance road and Penshioners lane in DN-73,Unit-17,Zone-VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1386,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,100000,"Repairs And Improvements to Existing Amma Unavagam @New Ferrance road in Dn-73 ,Unit-17, Zone-VI.",Own Sources,6,2016-17,2017-18 NF/2016-17/1387,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,100000,"Repairs And Improvements To the Existing PC at Powder Mills road near the canal @dn-73,Unit-17,Zone-VI",Own Sources,6,2016-17,2017-18 NF/2016-17/14302,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,107000,REPAIR AND IMPROVEMENT WORKS TO PUBLIC CONVENIENCE AT GANDHI NAGAR SLUM IN DN 73 UNIT 17 ZONE 6,Own Sources,6,2016-17,2019-20 NF/2016-17/14537,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,247000,"REPAIR AND MAINTENENCE WORKS TO PUBLIC CONVENIENCE AT GRAY NAGAR 3RD STREET IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2019-20 NF/2016-17/14538,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,210000,REPAIR WORKS TO PUBLIC CONVENIENCE AT ALEXANDER LANE IN DN-73 U17 Z6,Own Sources,6,2016-17,2019-20 NF/2016-17/16733,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,126000,"Construction of dilaplated portion compound wall due to VARDHA cyclone in Old Zone -3 Building at Dr.Ambedkar college road in dn-73,unit-17,zone-6",Own Sources,6,2016-17,2017-18 NF/2016-17/17930,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,377000,"PROVIDING AND FIXING STREET FURNITURE AT VARIOUS LOCATION IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/18066,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,153000,"CONSTRUCTION PLATFORM AND PROVIDING BORE WELL AT GANDHI NAGAR PC IN DN-73 ,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18067,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,73,70000,"REPAIRS AND PROVIDING PLUMBING ARRANGEMENT AT DECASTER ROAD ELECTION CENTER AND DECASTER ROAD SCHOOL IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18068,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,43000,"REPAIRS AND PROVIDING PLUMBING ARRANGEMENT AT THIRUVENKATASAMY SCHOOL, THIRUVENKATASAMY HEALTH POST AND AMBEDKAR COLLAGE ROAD OLD ZONE 3 OFFICE IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18069,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,156000,"PROVIDING ROOF SLAB , SEWAGE LINE IN AMMA UNAVAGAM AT NEW FERRANCE ROAD IN DN -73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18070,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,24000,"REPAIRS AND PLUMBING ARRANGEMENT WADIA PARK AT NEW FERRANCE ROAD IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18071,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,59000,"PROVIDING PLUMBING ARRANGEMENT NNMP SHED ,PRIMARY SCHOOL AND A BLOCK AT COOK ROAD IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/18390,Parks,Completed,NF-THIRU-VI-KA NAGAR,73,63000,"ANNUAL MAINTENANCE OF VADIA PARK (FOR SIX MONTHS) AT NEW FERRANCE ROAD IN DN-73,UNIT-16,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/3745,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,83000,"ATTENDING PATCH WORK AT NACHARAMMAL LANE IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3758,Bridges,Completed,NF-THIRU-VI-KA NAGAR,73,21000,"SUPPLYING AND FIXING SINTEX TANK AND REPAIRS WATER SUPPLY ARRANGEMENT IN CHENNAI HIGH SCHOOL AT COOKS ROAD IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3759,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,31600,"REAPAIRS AND IMPROVEMENT TO WATER SUPPLY ARRANGEMENT TO CHENNAI HIGH SCHOOL AT AMMAYIAMMAL STREET IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3760,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,185000,"REPAIRS AND IMPROVEMENTS TO SWD PIPE LINE AND PROVIDING CHAMBERS AT AMMAYIAMMAL LANE AND ROAD CROSS OF DECASTER ROAD IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3761,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,16800,"SUPPLY AND FIXING NEW MOTOR AND REPAIRS PIPE LINES AT NEW FERRANCE ROAD PC IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3762,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,41000,"PROVIDING RAMP AT URDHU SCHOOL AND NACHARAMMAN STREET JUNCTION AT DN-73, UNIT-17, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3763,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,65000,"REPAIRS AND IMPROVEMENT TO GROUP BIN PLATFORM AT STARANCE ROAD IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3785,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,143000,"REPAIRS AND IMPROVEMENTS TO PULINTHOPE HEALTH POST AT AMBEDKAR COLLAGE ROAD IN DN_73, UNIT-17, ZONE_6",Own Sources,6,2016-17,2017-18 NF/2016-17/3804,Footpath,Completed,NE-ROYAPURAM,73,27000,"REPAIRS AND IMPROVEMENTS TO NEW FERRANCE ROAD AMMA UNAVAGAM ,COMMUNITY CENTER AND OLD DIVISION OFFICE AT BOLU (N) STREET IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3805,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,80000,"REPAIRS AND IMPROVEMENT TO FOOTPATH PAINTING AT COOKS ROAD IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3806,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,180000,"SUPPLY AND FIXING MANHOLE DOORS AT VARIOUS STREET IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/3807,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,47000,"REPAIRS AND IMPROVEMENT TO OLD ZONE 3 OFFICE AND AMMA UNAVAGAM AT AMBEDKAR COLLAGE ROAD IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/4787,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,229000,"REMOVAL OF HYACINTH IN OTTERI NULLAH CANAL AT STEPHENSON ROAD I DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/5315,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,995000,"RAISING COMPOUND WALL AND IMPROVEMENT TO TOILET BLOCK IN CHENNAI PRIMARY SCHOOL AT AMMAYIAMMAL STREET IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/6559,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,998000,"CONSTRUCTION OF ADDITIONAL ROOMS AT WADIA HEATH POST IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/6561,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,998000,"IMPROVEMENTS TO THE ADDITIONAL ROOMS AT WADIA HEATH POST IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/6562,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,999000,"IMPROVEMENTS TO THE ADDITIONAL ROOMS AT WADIA HEATH POST IN DN-73, UNIT-17,ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/7949,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,15600,"REPAIRS AND IMPROVEMENT TO WATER SUPPLY ARRENGEMENT TO CHENNAI HIGH SCHOOL AT DECASTER ROAD IN DN-73 ,UNIT-17, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/7953,Footpath,Completed,NF-THIRU-VI-KA NAGAR,73,18000,"REPAIRS AND IMPROVEMENT TO WATER SUPPLY ARRENGEMENT TO THIRUVENKATA SAMY STREET CHS AND URDHU SCHOOL CHS AT MANNAR SAMY KOIL STREET IN DN-73 ,UNIT-17, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/7954,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,35656,"REPAIRS AND IMPROVEMENT WATER SUPPLY ARRENGEMENT AND SUMP CLEANING TO CHENNAI HIGH SCHOOL AT AMMAYIAMMAL STREET IN DN-73 ,UNIT-17, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/7955,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,14500,"REPAIRS AND IMPROVEMENT TO WATER SUPPLY ARRENGEMENT TO NNMP SHED AT OLD VAZHMA NAGAR AND WARD OFFICE IN DN-73 ,UNIT-17, ZONE-6",Own Sources,6,2016-17,2017-18 NF/2016-17/8253,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,942000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH CEMENT CONCRETE ROAD WITH RMC M30 AT NACHIYARAMMAL LANE(FROM DECASTER ROAD TO EB TRANSFORM) IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/8254,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,871000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH CEMENT CONCRETE RMC M30 AT NACHIYARAMMAL LANE (FROM EB TRANSFORM TO EB PILLAR BOX) IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/8255,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,815000,"PROVIDING TEMPORARY RESTORATION DUE TO FLOOD AFFECTED ROAD WITH CEMENT CONCRETE RMC M30 AT NACHIYARAMMAL LANE(FROM EB PILLAR BOX TO NACHIYARAMMAL STREET) IN DN-73,UNIT-17,ZONE-6",Own Sources,6,2016-17,2018-19 NF/2016-17/8259,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,120000,"ADDITIONAL IMPROVEMENTS TO BIO-GAS PLANT AT NEW FARRANCE ROAD IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 L/2016-17/18739,Electrical,Completed,L-Electrical,74,115200,Shifting of 6 nos of OH Lamp post and laying of 130 mtrs of 31/2x25sq.mm.UG Cable at widened Road of ESI Hospital side of Medavakkam Tank Road ln dn 74 of zone-6.,Own Sources,6,2016-17,2017-18 NF/2016-17/10453,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,980000,"PROVIDING SPEED BREAKER AT VARIOUS STREET IN DN-74, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/15919,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,590000,"REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE AND AMMA UNAVAGAM AT SUBBARAYAN 2ND STREET IN DN-74, UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/15925,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,310000,"REPAIRS TO PUBLIC TOILET AND AMMA UNAVAGAM AT RANGANATHAPURAM IN DN-74,UNIT-17, ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/16301,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,239000,"IMPROVEMENTS TO SECRETARIAT COLONY PARK DEMAGED IN VARDHA CYCLONE IN DN-74, UN-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/16307,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,218000,"IMPROVEMENTS TO CHS COMPOUND WALL DAMAGED IN VARDHA CYCLONE IN DN-74, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/16319,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,113000,"IMPROVEMENTS TO CPS COMPOUND WALL IN VARDHA CYCLONE DAMAGE RENOVATION WORK IN DN-74, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/16489,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,345000,"IMPROVEMENT TO EVER GREEN HERBAL PARK ,DAMAGED DUE TO VARDHA CYCLONE AT OTTERI IN DN-74,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16764,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,259000,"PROVIDING AND FIXING STREET FURNITURE AT VARIOUS STREET DAMAGED DUE TO VARDHA CYCLONE IN DN-74,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/17998,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,909000,"MAINTENANCE TO TROPICAL DRY EVER GREEN FOREST (HERBAL PARK) AT OTTERI IN DN-74, U-17, Z.6 (FOR SIX MONTHS)",Own Sources,6,2016-17,2017-18 NF/2016-17/19877,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,88000,"Providing and laying wet mix macadam at road cut portion in nallaiyah naidu street in dn-74, unit-17, zone-06",Own Sources,6,2016-17,2018-19 NF/2016-17/3343,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,637396,"Desilting in Strom Water Drain in Secretriate colony 4th street,A.K,Samy 9th Street,Barackka Road,Swamipathhan street,Sankarabathan Street,Nallaiah Street & Others Street IN DN-74, U-17, Z-6",Own Sources,6,2016-17,2018-19 NF/2016-17/4630,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,850000,"MAINTENANCE TO TROPICAL DRY EVER GREEN FOREST (HERB PARK) AT OTTREI IN DN-74, U-17, Z-6. (FOR SIX MONTHS)",Own Sources,6,2016-17,2016-17 NF/2016-17/5282,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,605000,"RELAYING BITUMINOUS ROAD 40MM THICK IN HOT MIX PLANT AT S.V. M. NAGAR E BLOCK SIDE IN DN-74, U-17, Z-6. ( WARD COUNCILLOR FUND -2016-2017)",Own Sources,6,2016-17,2017-18 NF/2016-17/5288,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,998000,"RELAYING BITUMINOUS ROAD 40MM THICK IN HOT MIX PLANT AT S.V. M. NAGAR F BLOCK SIDE IN DN-74, U-17, Z-6. ( WARD COUNCILLOR FUND -2016-2017)",Own Sources,6,2016-17,2017-18 NF/2016-17/5292,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,589000,"RELAYING BITUMINOUS ROAD 40MM THICK IN HOT MIX PLANT AT S.V. M. NAGAR G & H BLOCK SIDE IN DN-74, U-17, Z-6. ( WARD COUNCILLOR FUND -2016-2017)",Own Sources,6,2016-17,2017-18 NF/2016-17/5297,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,755000,"RELAYING BITUMINOUS ROAD 40MM THICK IN HOT MIX PLANT AT S.V. M. NAGAR D BLOCK SIDE IN DN-74, U-17, Z-6. ( WARD COUNCILLOR FUND -2016-2017)",Own Sources,6,2016-17,2017-18 J/2016-17/18344,Bridges,Completed,J-Bridges,75,275000,"Repair and Re-Construction of hand rail wall to Existing Bridge across otteri nallah canal at Vasuki Nagar in Dn-75, Zone -VI",Grants,6,2016-17,2017-18 NF/2016-17/11094,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,880000,"PROVIDING SPEED BREAKER AT BRICKLIN ROAD CHELLAPPA STREET AND VARIOUS STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/11098,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,751000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT S. S. PURAM B' BLOCK 1ST STREET CH. 0 TO 100 . IN DN-75, U-17,Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/11216,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,720000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT S. S. PURAM B' BLOCK 1ST STREET CH 101. TO 195 . IN DN-75, U-17,Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/12535,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,43000,"SUPPLY AND FIXING STAINLESS STEEL HAND RAIL CHENNAI MIDDLE SCHOOL VENKATTAMMAL SAMATHI STREET IN DIVISION -75, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/12991,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,112000,"PROVIDING WATER SUPPLY ARRANGEMENTS & OTHER IMPROVEMENTS AT AMMA UNAVAGAM WITH GYM BUILDING S.S.PURAM. A BLOCK 2ND STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/13097,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,66000,"IMPROVEMENTS TO ROAD SIDE PARK AT KAMARAJ STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/13103,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,51000,"PROVIDING WATER SUPPLY ARRENGEMENTS AT VALLUVAN STREET AMMA UNAVAGAM & NNMP SHED IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/13104,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,74000,"PROVIDING CONSTRUCTION OF SHED FOR THANTHAI PERIYAR HOSPITAL AT CHELLAPPA STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/13106,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,43000,"IMPROVEMENTS TO GYM BUILDING AT S.S.PURAM B' BLOCK 2 ND STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/13110,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,426000,"Improvements to Padavattaman koil street C.H.S . IN SIide Bath Room FIRST FLOOR & GROUND FLOOR I n DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/13112,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,116000,"IMPROVEMENTS TO C.PS. AT CHELLAPPA STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14273,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,700000,"IMPROVEMENTS TO PUBLIC CONVENIYANCE AT PONNIYAMMAN KOIL STREET, S.S. PURAM A BLOCK , EDWARD PARK STREET , IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14342,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,410000,"REPAIRS AND IMPROVEMENTS AT CHENNAI HIGH SCHOOL PADAVATTAMMAN KOIL STREET IN DN-75, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/14729,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,25500,"Providing to group bin plot forms with various streets in dn-75, u-17, z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/1522,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,180000,"TEMPORARY FLOOD DAMAGED CC ROAD PATCHWORK AT BRICKLINE LANE AND VARIOUS STREET IN DN-75, U17,Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/15871,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,340000,"IMPROVEMENTS TO PATEL PARK & ROADSIDE PARK AT CHELLAPA STREET & TANA STREET IN DN-75,UNIT-17, ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/18361,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,111000,"ANNUAL MAINTENANCE OF PATEL PARK (OUT SOURCING FOR THE PERIOD OF 6 MONTHS) AT CHELLAPPA STREET IN DIV 75, UNIT 17, ZONE6.",Own Sources,6,2016-17,2017-18 NF/2016-17/19363,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,29200,"IMPROVEMENTS TO TOILET AT SS PURAM 10TH STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/3147,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,58600,"REPAIRS AND IMPROVEMENTS TO FLOOD AFFECTED THANTHAI PERIYAR HOSPITAL IN CHELLAPPA STREET IN DN 75, UNIT 17, ZONE 6.",Own Sources,6,2016-17,2016-17 NF/2016-17/3348,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,690000,"Desilting in strom water drain in Edward park street,Padavattamman koil street,Venkadathri street,Mooku street ,Thiru-vi-ka street & others Street in dn-75, u-17, z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/3437,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,180000,"TEMPORARY FLOOD DAMAGED CC ROAD PATCHWORK AT S.S.PURAM A-BLOCK 15TH STREET LANE AND VARIOUS STREET IN DN-75, U17,Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/4599,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,980000,"LAYING CEMENT CONCRETE ROAD M30 GRADE CONCRETE AT NARAYANA MESTHIRI 2ND LANE IN DN-75, U-17, ZONE-6. (WARD COUNCILLOR FUND -2016-2017)",Own Sources,6,2016-17,2017-18 NF/2016-17/4606,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,885000,"LAYING CEMENT CONCRETE ROAD M30GRADE CONCRETE AT HANUMANTHARAYAN KOIL STREET IN DN-75, U-17, Z-6. ( WARD COUNCILLOR FUND-2016-2017)",Own Sources,6,2016-17,2017-18 NF/2016-17/4613,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,845000,"LAYING CEMENT CONCRETE ROAD M20 GRADE CONCRETE AT EDWARD PARK LANE & S.S.PURAM B' BLOCK 8TH STREET IN DN-75, U-17, Z-6. (WARD COUNCILLOR FUND-2016-2017)",Own Sources,6,2016-17,2017-18 NF/2016-17/6284,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,145000,"PROVIDING COMPOSTING YARD AT PADAVETTAMMAN KOIL STREET AND RAISING AND LOWERING SWD MANHOLE DOORS AND CC PATCH WORK VARIOUS STREET IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/6556,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,59200,"LOWERING AND RAISING FLOOD AFFECTED SWD MANHOLE DOOR AT THIRU VI KA STREET, VALLUVAN STREET & VARIOUS STREETS IN DN 75, UNIT 17, ZONE 6",Own Sources,6,2016-17,2016-17 NF/2016-17/7142,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,874000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE AT S.S.PURAM B' BLOCK 7TH STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/7150,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,760000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE AT S.S.PURAM B' BLOCK 4TH CROSS STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/7151,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,848000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE AT S.S.PURAM B' BLOCK 6TH STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/7202,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,875000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE AT S.S.PURAM B' BLOCK 4TH STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/7203,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,881000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE AT S.S.PURAM B' BLOCK 3RD AND 1ST CROSS STREETS IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2017-18 NF/2016-17/7205,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,878000,"TEMPORARY RESTORATION OF FLOOD DAMAGED CEMENT CONCRETE ROAD M20 GRADE AT S.S.PURAM B' BLOCK MAIN STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/7769,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,746368,"ADDITIONAL IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT PADAVATTAMMAN KOIL STREET IN DN-75, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/7997,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,95000,"Repair and Improvements to GYM Building and Amma Unavagam at SS Puram B Block 4th cross street and Brickline road in Div-75,Unit-17,Zone-6.",Own Sources,6,2016-17,2017-18 BR/2016-17/17651,Roads,Completed,BR-Bus Route Roads,76,1439000,"Attending temporary repairs to damaged roads due to Vardha Cyclone in North East Monsoon 2016 Dr.Ambedkar College Road, Paper Mills Road, in Zone 6",Own Sources,6,2016-17,2017-18 BR/2016-17/17652,Footpath,Completed,BR-Bus Route Roads,76,645000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Medavakkam tank road,Strahans road and Perambur Barracks road in Zone 6",Own Sources,6,2016-17,2017-18 NF/2016-17/0782,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,977000,"IMPROVEMENTS TO SWD AT JUNCTION OF NAINIAPPAN STREET TO JUNCTION OF BARRACKS GATE ROAD IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/0784,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,975000,"IMPROVEMENTS TO SWD AT STRAHNS ROAD FROM JUNCTION OF ANGALAMMAN KOVIL STREET TO JUNCTION OF NAINIAPPAN STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/10633,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,435000,"LAYING OF BT ROAD AT ANJANEYAR KOVIL STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10634,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,375000,"LAYING OF BT ROAD AT MANGAPATHY STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/10636,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,440000,"LAYING OF BT ROAD AT BARRACKS GATE LANE IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/11514,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,588000,"IMPROVEMENT TO AMMA CANTEEN AT ANGALAMMAN KOIL STREET IN DN-76, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/11876,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,30000,"IMPROVEMENT TO PUPLICK CONVEYANCE AT VARIOUS STREET IN DN-76, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/14195,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,113000,IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT RAMANUJA GARDEN STREET IN DN-76 UNIT-17 ZONE-06,Own Sources,6,2016-17,2017-18 NF/2016-17/14196,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,235000,"IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT KM GARDEN FIRST STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/14197,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,253000,"IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT KM GARDEN 6TH STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/14207,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,84000,"IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT SACHIDANANDAM STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/14579,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,82000,"IMPROVEMENTS TO THE PUBLIC CONVENIENCE AT ANGALLAMAN KOIL STREET (NEAR JAI NAGAR LAYOUT) IN DN-76,UIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/14628,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,74000,"IMPROVEMENTS TO RELIF CENTRE, NEW FARRANCE ROAD NEAR KARUNANITHI PARK,CS PARK, CHS SCHOOL IN STRAHANS ROAD & HOSPITAL ENTERENCE IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/14629,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,160000,"IMPROVEMENTS TO SWD AT SACHIDANANDAM STREET & STRAHANS ROAD IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/14630,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,20000,"IMPROVEMENTS TO AMMA UNAVAGAM IN SACHIDHANANTHAM STREET AND DIVISION OFFICE WORK IN DHOBIKANA AT DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/14631,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,69000,"ADDITIONAL IMPROVEMENTS TO SWARNAJAYANTHI OFFICE(OLD CMS SCHOOL)AT DEVARAJ STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/14632,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,74000,"PROVIDING NEW GATE AT OLD DIVISION OFFICE AT PERAMBUR BARRACKS ROAD IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/14633,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,135000,"DISMANTLING AND RECONSTRUCTION OF SWD AT ANGINAYAR KOIL STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/14634,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,275000,"DISMANTLING AND RECONSTRUCTION OF SWD AT K.M.GARDEN 6TH STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/14635,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,170000,"IMPROVEMENTS TO K.M.GARDEN 1st STREET PUBLIC CONVENIENCE IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2018-19 NF/2016-17/16441,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,268000,"IMPROVEMENTS TO THE RELIEF CENTRE,DAMAGED DUE TO VARDHA CYCLONE AT PERAMBUR BARRACKS RD IN DIVISION -76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16514,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,290000,"IMPROVEMENTS TO DIVISION OFFICE ,DAMAGED DUE TO VARDHA CYCLONE AT CONRONSMITH NAGAR MAIN STREET IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16709,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,88000,"IMPROVEMENTS TO THE COMPOUND WALL OF ROAD SIDE PARK,DAMAGED DUE TO VARDHA CYCLONE AT C.S.NAGAR IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16710,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,135000,"IMPROVEMENTS TO THE STREET NAME BOARD AT VARIOUS PLACES DAMAGED DUE TO VARDHA CYCLONE IN DN -76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16711,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,1060000,"RELAYING OF THE BITUMINOUS ROAD AT SACHIDANANDAM STREET DAMAGED DUE TO VARDHA CYCLONE IN DN -76,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/18360,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,51000,"MAINTENANCE OF PARK (OUT SOURCING FOR THE PERIOD OF 6 MONTHS BHAKAVATCHALAM PARK AT ANGALAMMAN KOIL STREET IN DIV 76, UNIT 17, ZONE 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/18369,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,73000,"MAINTENANCE OF SELVAPATHY PARK (OUT SOURCING FOR THE PERIOD OF 6 MONTHS) AT STRAHANS ROAD IN DIV 76, UNIT 17, ZONE 6",Own Sources,6,2016-17,2018-19 NF/2016-17/3487,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,550000,"Desilting in strom water drain at various street in dn-76, u-17, z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/6535,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,224000,"IMPROVEMENT TO PATCH WORK AT VARIOUS STREETS IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/6536,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,999000,"IMPROVEMENT TO FOOTPATH AT PERAMBUR BARRACKS ROAD IN DN-76, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2020-21 NF/2016-17/6539,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,84000,"IMPROVEMENT TO RELIEF CENTER AT PERAMBUR BARRACKS ROAD IN DN-76, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/6811,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,29000,"IMPROVEMENT TO PUBLIC CONVEYANCE AT ANGALAMMAN KOIL STREET IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/6813,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,36000,"IMPROVEMENT TO DIVISION OFFICE IN DN-76, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/6815,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,315000,"IMPROVEMENT TO STORM WATER DRAIN AT K.M. GARDEN, DEVARAJ STREET IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2020-21 NF/2016-17/6817,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,94000,"IMPROVEMENT TO AMMA UNAVAGAM AND SCHOOL AT SACHIDANANDAM STREET & ABBAS STREET IN DN-76, UNIT-15, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/6821,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,998000,"IMPROVEMENT TO FOOTPATH AT AMBEDKAR SALAI AND PERAMBUR BARACKS ROAD IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/6824,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,910000,"IMPROVEMENT TO FOOTPATH AT AMBEDKAR SALAI AND STRAHENS ROAD IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/7403,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,99000,"IMPROVEMENT TO DEMELLOUS ROAD AND ANGALAMMAN KOIL STREET IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/7404,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,31000,"IMPROVEMENT TO E.B. COMPOND WALL AT STRAHENS ROAD NEAR SCHOOL IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2016-17 NF/2016-17/7656,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,998000,"IMPROVEMENT TO AMMA WATER SHED AT STRAHENS ROAD NEAR SCHOOL IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/7662,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,998000,"IMPROVEMENT TO HIGH SCHOOL AT STRAHENS ROAD IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2016-17,2020-21 NF/2016-17/10547,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,464261,"LAYING BT ROAD AT Angalamman North Mada Street IN DN-77 ,UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/10596,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,762486,"LAYING BT ROAD AT Bogipalayan 1st main road IN DN-77 ,UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/10602,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,170515,"LAYING BT ROAD AT TK.Mudali Street IN DN-77 ,UNIT-17, ZONE-06.",Own Sources,6,2016-17,2017-18 NF/2016-17/12849,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,66500,"Maintenance of New TPF Park (For Six Months) at Basin Elephant Gate road, DN - 77,UNIT - 17, ZONE - 6",Own Sources,6,2016-17,2018-19 NF/2016-17/14531,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,450000,"Improvements to Public convenience at Basin Elephant Gate road, Dn77, U17, Z6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14532,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,150000,"Improvements to Public convenience at Gurusamy nagar 10th street, Dn77, U17, Z6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14533,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,100000,"Improvements to Public convenience at Play Ground 1st street, Dn77, U17, Z6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14534,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,50000,"Improvements to Public convenience at Siva Rao road, Dn77, U17, Z6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14535,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,50000,"Improvements to Public convenience at Kumarasamy rajapuram, Dn77, U17, Z6.",Own Sources,6,2016-17,2017-18 NF/2016-17/14536,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,50000,"Improvements to Public convenience at Pulianthope 4th Street, Dn77, U17, Z6.",Own Sources,6,2016-17,2017-18 NF/2016-17/16353,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,770000,"Improvements to Amma park at Basin Elephant gate road (due to the affect of VARDHA cyclone ), DN77, U17, ZONE6",Own Sources,6,2016-17,2017-18 NF/2016-17/16456,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,259000,"Improvements to TPF park at Basin Elephant gate road (due to the affect of VARDHA cyclone ), DN77, U17, ZONE6",Own Sources,6,2016-17,2017-18 NF/2016-17/16485,Playfields,Completed,NF-THIRU-VI-KA NAGAR,77,666000,"Improvement work to Play ground Compound wall at Old slaughter house road( due to the affect of VARDHA cyclone) in division 77, U 17, Zone 6",Own Sources,6,2016-17,2017-18 NF/2016-17/16537,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,307000,"Improvements to Amma Unavagam at Demellows road (Due to the affect of VARDHA cyclone affect), DN77, U 17, Z-6",Own Sources,6,2016-17,2017-18 NF/2016-17/16734,Footpath,Completed,NF-THIRU-VI-KA NAGAR,77,610000,"Improvements to Footpath at Pulianthope High road (Due to the affect of VARDHA cyclone affect), DN 77, U 17, Zone 6.",Own Sources,6,2016-17,2017-18 NF/2016-17/16788,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,859000,"Relaying BT road in Angalamman hutting ground ( Due to the affect of VARDHA cyclone) in Dn77, U 17, Zone 6..",Own Sources,6,2016-17,2017-18 NF/2016-17/16796,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,608000,"Relaying BT road in Bogipalayam 1st lane ( Due to the affect of VARDHA cyclone) in Dn77, U 17, Zone 6..",Own Sources,6,2016-17,2017-18 NF/2016-17/16804,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,525000,"Relaying BT road in Bogipalayam 2nd lane ( Due to the affect of VARDHA cyclone) in Dn77, U 17, Zone 6..",Own Sources,6,2016-17,2017-18 NF/2016-17/16809,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,316000,"Relaying BT road in Bogipalayam 3rd lane ( Due to the affect of VARDHA cyclone) in Dn77, U 17, Zone 6..",Own Sources,6,2016-17,2017-18 NF/2016-17/16810,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,460000,"Relaying BT road in corporation lane ( Due to the affect of VARDHA cyclone) in Dn77, U 17, Zone 6..",Own Sources,6,2016-17,2017-18 NF/2016-17/16835,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,920000,"Relaying BT road in Kanagaraya thotam canal road ( Due to the affect of VARDHA cyclone) in Dn77, U 17, Zone 6..",Own Sources,6,2016-17,2017-18 NF/2016-17/3389,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,836300,"Desilting at various streets in Dn 77, Unit 17, Zone 6",Own Sources,6,2016-17,2018-19 NF/2016-17/5896,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,472000,"Improvements to Composed yard and Providing Pipe Line, Inspection Chamber & Speed Breaker at Various Location in Dn 77, U 17, Zone 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/5944,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,159000,"Improvement to School & ICDS at Various Location in Division- 77, U-17, Z- 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/7602,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,359000,"LAYING BT ROAD AT ST BAKTHAVARMAL STREET IN DN77,UNIT-17,ZN-06. (WARD COUNCILOR FUND 2016-17)",Own Sources,6,2016-17,2018-19 NF/2016-17/7612,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,382000,"LAYING BT ROAD AT ST MOHANLAL STREET IN DN-77 ,UNIT-17, ZONE-06, (WARD COUNCILOR FUND (2016-17)",Own Sources,6,2016-17,2018-19 NF/2016-17/7616,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,472000,"LAYING BT ROAD AT ST.JESVANTHAMMAL STREET IN DN-77, UNIT-17, ZONE-06. (WARD COUNCILOR FUND 2016-17).",Own Sources,6,2016-17,2018-19 NF/2016-17/8118,Culvert,Completed,NF-THIRU-VI-KA NAGAR,77,197000,"Improvements to Amma Unavagam, Public Toilets,Park & Bogipalayam Gym in Dn-77,U-17,Z- 6.",Own Sources,6,2016-17,2018-19 NF/2016-17/8765,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,1644000,"Construction of Multi Purpose Hall at Old Slaughter House Road in Division - 77,Unit - 17,Zone - 6.",MLACDS,6,2016-17,2017-18 NF/2016-17/11091,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1412409,"PROVIDING BT ROAD AT MANICKKAM STREET IN DN 78, U 17,Z 6,",Own Sources,6,2016-17,2016-17 NF/2016-17/11096,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,834700,"LAYING BT ROAD AT CKP KOVIL STREET IN DN 78,U 17,Z 6.",Own Sources,6,2016-17,2016-17 NF/2016-17/11103,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,860988,"LAYING BT ROSD AT ARIMUTHU STREET IN DN 78,U 17,Z 6.",Own Sources,6,2016-17,2017-18 NF/2016-17/11106,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,2526501,"LAYING BT ROAD AT V.V KOIL STREET IN DN 78, U 17, Z 6.",Own Sources,6,2016-17,2016-17 NF/2016-17/11109,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,871072,"LAYING BT ROAD AT ALATHUR SUBRAMANI STREET IN DN 78,U 17, Z 6.",Own Sources,6,2016-17,2016-17 NF/2016-17/16358,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,47000,"IMPROVEMENTS TO GYM BUILDING,DAMAGED DUE TO VARDHA CYCLONE AT ARUNACHALAM STREET IN DN-78,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/1647,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,215000,"IMPROVEMENTS TO GYM AT NEW MANNIKAM STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2016-17,2017-18 NF/2016-17/16508,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,82000,"IMPROVEMENTS TO AMMA UNNAVAGAM AT KURAVANKULAM ,DAMAGED DUE TO VARDHA CYCLONE IN DN-78,UNIT-17,ZONE-06",Own Sources,6,2016-17,2017-18 NF/2016-17/19482,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,54000,"IMPROVEMENTS TO BIN PLATFORMS AND WELL TYPE COMPOSED YARD AT VARIOUS STREET IN DN-78, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/19483,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,175000,"IMPROVEMENTS TO CMS AT TANA STREET IN DN-78, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/19484,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,150000,"IMPROVEMENTS TO ELECTRICAL ARRENGEMENTS FOR UNIT OFFICE AT ARUNACHALAM STREET AND CMS ERRAN STREET IN DN-78, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/19485,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,140000,"IMPROVEMENTS TO DIVISION OFFICE AT NEW MANIKKAM STREET CHOOLAI IN DN-78, U-17, Z-6",Own Sources,6,2016-17,2018-19 NF/2016-17/19486,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,190000,"IMPROVEMENT TO CHENNAI MIDDLE SCHOOL AT KURAVAN KULAM IN DN-78, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/19487,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,284000,"IMPROVEMENTS TO SI OFFICE AND CI OFFICE ROOM AT ASTABUJAM ROAD IN DN-78, U-17, Z-6.",Own Sources,6,2016-17,2018-19 NF/2016-17/19782,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,234000,"IMPROVEMENT TO FOOTPATH AT SYDHENAMS ROAD,PERRAMBUR BARRACKS ROAD,AND PROVIDING FRC DOOR AT CHOOLAI HIGH ROAD,SYDHENAMS ROAD,SATTANAN STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2016-17,2017-18 NF/2016-17/2026,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,81000,"IMPROVEMENTS TO AMMA UNAVAGAM, SCHOOL, DN OFFICE, CI OFFICE AT VARIOUS STREET IN DIV-78,UN-17,Z-06",Own Sources,6,2016-17,2018-19 NF/2016-17/2029,Electrical,Completed,NF-THIRU-VI-KA NAGAR,78,92000,"PROVIDING RAMP AND COLOUR WASHING TO CMS AT TANA STREET,KURAVANKULAM STREET FOR ELECTION BOOTH IN DIV-78,UN-17,Z-06",Own Sources,6,2016-17,2017-18 NF/2016-17/2082,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,75000,"PROVIDING PLATFORM TO GARBAGE BINS AT VARIOUS LOCATIONS IN DIV-78,UN-17,Z-06",Own Sources,6,2016-17,2018-19 NF/2016-17/3492,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,496000,"Desilting of swd at vv koil street,sydanams road,choolai high road,pb road,rangaiah street,vadamalai street,narasingaperumal street,new manikkam street in Dn-78,Un-17,Z-6",Own Sources,6,2016-17,2018-19 NF/2016-17/4916,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,88000,"PROVIDING RAMP AND COLOUR WASHING TO NOON MEALS CENTRE AT MANIKKAM STREET AND C.I LABOUR REST AT ARUNACHALAM STREET FOR UN-17,Z-06ELECTION BOOTH IN DIV-78,",Own Sources,6,2016-17,2017-18 NF/2016-17/8230,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,953000,Construction of Amma Unavagam at Tana Street in Division 78 Unit 17 Zone 6,Own Sources,6,2016-17,2016-17 NF/2016-17/8345,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,581000,Additional improvements to Amma Unavagam in Division 78 Unit 17 Zone 6,Own Sources,6,2016-17,2016-17 L/2016-17/13316,Electrical,Completed,L-Electrical,79,640800,"Replacement of 14 Nos of Damaged KIOSK Pillar with 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div 79, 80 & 82 in Ramnagar Section, Zone-VII, Ambattur",Own Sources,7,2016-17,2017-18 L/2016-17/13821,Electrical,Completed,L-Electrical,79,99400,"Removal & Refixing of 27 Nos of KIOSK Pillar At Various Locations In Div 79 to 93 in Zone-VII, Ambattur",Own Sources,7,2016-17,2017-18 L/2016-17/18126,Electrical,Completed,L-Electrical,79,2237800,"Removal and refixing of 289 nos of 6mtr lamp post , 39 nos of 8 mtr lamp post & Supply & Erection of 55 Nos 6 Mtr GI Lamp Post with Straight & Arch Bracket at various places in Division- 79 to 93 , Zone- VII",Own Sources,7,2016-17,2017-18 NG/2016-17/12821,Buildings,Completed,NG-AMBATTUR,79,245000,"Annual Maintenance Works at COC Buildings In Division-79, Unit-18, Zone-VII ( Ambattur )",Own Sources,7,2016-17,2018-19 NG/2016-17/14059,Buildings,Completed,NG-AMBATTUR,79,106000,"MAINTENANCE WORKS AT PUBLIC CONVENIENCE AT ORAGADAM IN DIVISION 79,UNIT-18,ZONE-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/16072,Parks,Completed,NG-AMBATTUR,79,790000,"REPAIR AND MAINTENANCE WORKS AT RAM NAGAR,LENIN NAGAR,LAKSHMIAMMAN NAGAR,GANDHI NAGAR PARKS DAMAGED DUE TO VARADHA CYCLONE IN DIV-79, UNIT-18, ZONE-VII.",Own Sources,7,2016-17,2017-18 NG/2016-17/4433,Storm Water Drain,Completed,NG-AMBATTUR,79,900000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-79,UNIT-18,ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/5436,Buildings,Completed,NG-AMBATTUR,79,1000000,"Construction of Amma Unavagam at Gandhi Main Road Oragadam in Div-79,Unit-18,Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/16423/C,Parks,Completed,NG-AMBATTUR,80,952000,"REPAIR AND MAINTENANCE WORKS AT THANGAL ERI PARK DAMAGED DUE TO VARADHA CYCLONE IN DIV-80, UNIT-18, ZONE-VII.",Own Sources,7,2016-17,2017-18 NG/2016-17/19859,Buildings,Completed,NG-AMBATTUR,80,160000,"PROVIDING ANNUAL MAINTENANCE FOR COC BUILDINGS, PARKS, ROADS AND STORM WATER DRAIN IN DIV 80",Own Sources,7,2016-17,2018-19 NG/2016-17/4434,Storm Water Drain,Completed,NG-AMBATTUR,80,900000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-80,UNIT-18,ZONE-7",Own Sources,7,2016-17,2018-19 BR/2016-17/14657,Roads,Completed,BR-Bus Route Roads,81,970000,Removing and refixing of 8 Numbers of Modern Statinless Steel Bus Shelter at various Bus Route Roads in Zone-7,Own Sources,7,2016-17,2019-20 L/2016-17/13371,Electrical,Completed,L-Electrical,81,860500,"Replacement of 19 Nos of KIOSK Pillar Box With 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div 81, 86,87 & 88 in AE/Padi Section, Zone-VII, Ambattur",Own Sources,7,2016-17,2017-18 NG/2016-17/14080,Buildings,Completed,NG-AMBATTUR,81,417000,"MAINTENANCE WORKS AT PUBLIC CONVENIENCE AT O.T BUSTAND,THIRUVALLUR NAGAR,KALYANAPURAM IN DIVISION:81,UNIT:18,ZONE-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/15021,Buildings,Completed,NG-AMBATTUR,81,674000,"ANNUAL MAINTENANCE FOR COC BUILDINGS,PARKS,ROADS,STORM WATER DRIANS IN DIVISION-81,UNIT-18,ZONE-7 AMBATTUR",Own Sources,7,2016-17,2018-19 NG/2016-17/16102,Parks,Completed,NG-AMBATTUR,81,219000,"REPAIR AND MAINTENANCE WORKS AT SECRETARIAT COLONY,THIRUVENGADAM NAGAR,KRISHNAPURAM, PARKS DAMAGED DUE TO VARADHA CYCLONE IN DIV-81, UNIT-18, ZONE-VII.",Own Sources,7,2016-17,2017-18 NG/2016-17/4436,Roads,Completed,NG-AMBATTUR,81,900000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-81,UNIT-18,ZONE-7",Own Sources,7,2016-17,2018-19 NG/2016-17/8721,Roads,Completed,NG-AMBATTUR,81,1280000,"FORMING AND STRENGTHENING OF B.T COURSE ROAD AT MURUGAPPA REDDY 1ST STREET AND CROSS STREET KK ROAD 7TH STREET IN DN 81, UNIT 18, ZONE 7",Own Sources,7,2016-17,2017-18 L/2016-17/4863,Electrical,Completed,L-Electrical,82,152500,"Proposed Laying of 340 Mtrs of 4 x 16 sq mm Cable with 3 phase Automatic Timer at Slaughter House in Ward 82, Zone VII",Own Sources,7,2016-17,2016-17 NG/2016-17/16956,Buildings,Completed,NG-AMBATTUR,82,58000,"REPAIR AND MAINTENANCE WORKS FOR STREET NAME BOARD DAMAGE AT PILLAIYAR ARCH STREET AND SOWKAR STREET DUE TO VARADHA CYCLONE IN DIV-82, UNIT-18, ZONE-VII.",Own Sources,7,2016-17,2017-18 NG/2016-17/4428,Storm Water Drain,Completed,NG-AMBATTUR,82,900000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-82,UNIT-18,ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/5600,Buildings,Completed,NG-AMBATTUR,82,1000000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM AT KARUKU MAIN ROAD,MADHAVI STREET IN DIV-82,UNIT-18,ZONE-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/6016,Buildings,Completed,NG-AMBATTUR,82,999000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM AT CHURCH ROAD PADI IN DIV-87,UNIT-19,ZONE-7.",Own Sources,7,2016-17,2016-17 BR/2016-17/17729,Roads,Completed,BR-Bus Route Roads,83,989000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Red Hills Road, East Avenue, MTH Road, Thirumangalam Avadi Road, Mogappair West 3rd Main Road and North Avenue & Other Bus route roads in Zone-7",Grants,7,2016-17,2017-18 BR/2016-17/9225,Roads,Completed,BR-Bus Route Roads,83,10787860,"Strengthening and Relaying road with DBM and CBC after cold milling by paver finisher by using plastic waste along with traffic improvement works @ Station road from the Jn of Central Avenue to the Jn of CTH Road in Dn-83, Zone-7",Grants,7,2016-17,2018-19 BR/2016-17/9325,Roads,Completed,BR-Bus Route Roads,83,4152000,"Strengthening and Relaying road with DBM and CBC after cold milling by paver finisher by using plastic waste along with traffic improvement works @ Mugapair Eri Scheme 4th Main Road (From the Jn of Eri Scheme 6th Main Road to the jn of Eri Scheme 1st Main Road) in Division-91, Zone-7",Grants,7,2016-17,2017-18 L/2016-17/13774,Electrical,Completed,L-Electrical,83,433200,"Replacement of 10 Nos of Damaged KIOSK Pillar with 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div 83,84,85 in Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2016-17,2017-18 L/2016-17/19294,Electrical,Completed,L-Electrical,83,674000,"Proposed Laying of 1067 Mtrs of 4 x 16 sq mm Cable at Vandikkaran Street From Srinivasapuram to Pattravakkam Bridge down in Dn 83, Zone VII, Ambattur",Own Sources,7,2016-17,2017-18 NG/2016-17/0401,Buildings,Completed,NG-AMBATTUR,83,795000,"Annual Maintenance to chennai Primary school and High school at agraharam in Dn - 83, Unit - 20, Zone - 7.",Own Sources,7,2016-17,2018-19 NG/2016-17/14026,Buildings,Completed,NG-AMBATTUR,83,430000,"Maintenance work for public convenience at (two location ) madhanakuppam Main road and TNHB 38th street in Div- 83,Unit-18, zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/15866,Buildings,Completed,NG-AMBATTUR,83,160000,"REPAIR AND MAINTENANCE WORKS FOR STREET NAME BOARDS AND SIGNAGE BOARD AT SUBULAKSHMI NAGAR 4th STREET, BALAJI NAGAR 3rd STREET, SUBULAKSHMI NAGAR 3rd STREET, TNHB 57th STREET, TNHB 61st STREET, NORTH AVENUE ROAD IN DIV-83, UNIT-18, ZONE-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/16030,Buildings,Completed,NG-AMBATTUR,83,36000,"REPAIR WORKS TO PARK AT TNHB 61ST STREET PARK IN DUE TO VARADHA CYCLONE IN DIV-83,UNIT-18,ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/16039,Buildings,Completed,NG-AMBATTUR,83,164000,"IMPROVEMENT WORK DUE TO VARADHA CYCLONE AT SUBULAKSHMI PARK IN DIV-83, UNIT-18,ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/16064,Buildings,Completed,NG-AMBATTUR,83,42000,"IMPROVEMENT WORK DUE TO VARADHA CYCLONE AT RANGA GARDEN PARK IN DIV-83, UNIT18, ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/16076,Parks,Completed,NG-AMBATTUR,83,50000,"IMPROVEMENT WORK DUE TO VARADHA CYCLONE AT SASATHA NAGAR PARK IN DIV-83,UNIT-18, ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/4485,Storm Water Drain,Completed,NG-AMBATTUR,83,995000,"Desilting and Repair Works to the Existing Road Side Drain And Storm Water Drain at various Streets in Srinivasapuram 1st Main road, 1st main road 2nd cross street,srinivasapuram Pillayar Koil Street, NRS road, Station Road, TNHB 26th,29th,30th,31st, 39th, 41st, 49th, North Avenue road and NAS Garden to Subulakshmi Nagar in dn-83, unit-20,Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/5653,Buildings,Completed,NG-AMBATTUR,83,995000,"Construction of Amma Unavagam at Rajiv Gandhi Nagar, (Thathankuppam) in Div - 83, Unit - 20, Zone - 7.",Own Sources,7,2016-17,2016-17 NG/2016-17/10835,Buildings,Completed,NG-AMBATTUR,84,830000,"PROVINDG ANNUAL MAINTENANCE FOR COC BUILDINGS, PARKS, ROADS AND STORM WATER DRAINS IN DIVISION :-84, UNIT-19,ZONE-07.",Own Sources,7,2016-17,2018-19 NG/2016-17/10900,Buildings,Completed,NG-AMBATTUR,84,998000,"Proposed Construction of Amma Unavagam at Ambattur Industrial Estate (North) 1st cross street pattaravakkam In Division-84, Unit-19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/13597,Buildings,Completed,NG-AMBATTUR,84,350000,"Supply and fixing of Bio- Gas plant to Amma Unavagam at East Avenue Road in Div-84,Unit-19, Zone-07.",Own Sources,7,2016-17,2018-19 NG/2016-17/14553,Buildings,Completed,NG-AMBATTUR,84,210000,"Repairs And Maintenance works to the Existing Public Conveniance At EB Road (Pattaravakkam), Gangai amman koil street and periyar nagar in Division - 84, Unit - 19, Zone - 7.",Own Sources,7,2016-17,2017-18 NG/2016-17/15888,Buildings,Completed,NG-AMBATTUR,84,284000,"Repairs to Pattaravakkam Amma unavagam and East Avenue Amma Unavagam in Div - 84, Unit - 19, Zone - 7",Own Sources,7,2016-17,2017-18 NG/2016-17/16007,Parks,Completed,NG-AMBATTUR,84,350000,"Repairs to Park at TNHB 4th Street in Division - 84, Unit-19, Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/17946,Buildings,Completed,NG-AMBATTUR,84,2630000,"Formation of New Tennis Courts (2Nos) at East Avenue road in Division -84, Unit - 19, Zone -7.",Own Sources,7,2016-17,2018-19 NG/2016-17/4489,Storm Water Drain,Completed,NG-AMBATTUR,84,998000,"Desilting and Repair Works to the Existing Road Side Drain And Storm Water Drain at various Streets in Vanji Nagar main street, 2nd street,3rd street, Kannagi Nagar main road, 3rd Street, 4th street, chavadi Cross Street, Mariammankoil street(Pattaravakkam), Kulakarai Street (Pattaravakkam), Bramin street Main road (Pattaravakkam), Bramanan 1st Street, 2nd Street, Bajanai koil street, Kanni amman koil street, Pattaravakkam Road, Bramin street (Kanniamman koil st), Yadaval Street, Kakkanji Street, Kammalar street, Station road Cross, Nagammal Street, TNHB 1 st Street, TNHB 4 th Street, 9 th Street,10 th Street, 12 th Street, 13TH STREET, 14TH STREET, 15TH STREET, 16th Street , Bharathy Nagar Main Road, 2nd Main Road, Kamaraj Nagar 5th Street in dn-84, unit-20,Zone-7",Own Sources,7,2016-17,2017-18 BR/2016-17/18785,Roads,Completed,BR-Bus Route Roads,85,176000,Providing and Laying of Disabled friendly Ramp for Stainless steel Bus shelters in various Bus route roads in Zone -7,Own Sources,7,2016-17,2017-18 NG/2016-17/13562,Buildings,Completed,NG-AMBATTUR,85,300000,"Repairs And Maintenance Of Public Convenience At Bajanai Kovil Street, Mangalapuram In Division 85, Unit 19, Zone 7.",Own Sources,7,2016-17,2017-18 NG/2016-17/13564,Buildings,Completed,NG-AMBATTUR,85,230000,"Repairs And Maintenance Of Existing (8+8 WC & 5+5 Bath )Public Convenience At Ambedkar Street, Kamarajapuram in Division 85, Unit 19, Zone 7.",Own Sources,7,2016-17,2016-17 NG/2016-17/13565,Buildings,Completed,NG-AMBATTUR,85,211000,"Repairs And Maintenance Of Existing (5+5 WC & 1+1 Bath )Public Convenience At Jeeva Street Kamarajapuram In Division 85, Unit 19, Zone 7.",Own Sources,7,2016-17,2016-17 NG/2016-17/16689,Buildings,Completed,NG-AMBATTUR,85,45000,"Repairs of existing car shed and drivers shed zone 7 campus at MTH road in div-85,unit-19, zone-07.",Own Sources,7,2016-17,2017-18 NG/2016-17/4833,Buildings,Completed,NG-AMBATTUR,85,992000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION- 85 UNIT-19 ZONE-7(AMBATTUR),Own Sources,7,2016-17,2017-18 L/2016-17/1538,Electrical,Completed,L-Electrical,86,2104200,"Proposed Erection of 29 nos of 6 Mtr hot dip zinc galvanising Lamp post Straight Brackets with 40 w to 50 watts LED fitting,16 nos of 6 Mtr hot dip zinc galvanising Lamp post arch Brackets with 90 w to 120 watts LED fitting at TNSCB, Athipat in Dn 86 Zone VII, Ambattur.",Deposit Works,7,2016-17,2017-18 L/2016-17/18929,Electrical,Completed,L-Electrical,86,198900,"Proposed laying of 402 mtrs of 3 1/2 x25 SQMM UG cable for bio gas plant at Athipet Dumping Yard to Vanagaram road in Dn 86 Zone VII, Ambattur.",Own Sources,7,2016-17,2017-18 NG/2016-17/13987,Buildings,Completed,NG-AMBATTUR,86,990000,"Repair Work to the existing toilets at K.K Nagar (T.G.Anna Nagar), Manickam Pillai Street, Padasalai Street, Udayar Palayam & Alamaram Street in division - 86, Unit -19, Zone - 7",Own Sources,7,2016-17,2016-17 NG/2016-17/14607,Buildings,Completed,NG-AMBATTUR,86,770000,"Repair Work to the existing Amma Unavagam Buildings at Athipet and Mannurpet in division - 86, Unit -19, Zone -7",Own Sources,7,2016-17,2018-19 NG/2016-17/15111,Buildings,Completed,NG-AMBATTUR,86,860000,"ANNUAL MAINTENANCE WORKS FOR PARKS, GCC BUILDINGS IN DIVISION 86, UNIT - 19, ZONE- 7 (AMBATTUR)",Own Sources,7,2016-17,2018-19 NG/2016-17/4782,Storm Water Drain,Completed,NG-AMBATTUR,86,990000,"Desilting And Repair Works To The Existing Road Side Drain And Storm Water Drain At Various Streets In Chinna Colony-Athipattu, Annai Sathya Nagar & Mannurpet In Division-86, Unit-19,Zone-7.",Own Sources,7,2016-17,2018-19 NG/2016-17/9339,Roads,Completed,NG-AMBATTUR,86,2340000,"Providing and Laying BT Road at Perumal Kovil Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9341,Roads,Completed,NG-AMBATTUR,86,2240000,"Providing and Laying BT Road at Athipet Industrial Estate Roads Reach 1 in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9342,Roads,Completed,NG-AMBATTUR,86,2340000,"Providing and Laying BT Road at Ganesh Street Reach 3 in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9343,Roads,Completed,NG-AMBATTUR,86,2340000,"Providing and Laying BT Road at Ganesh Street Reach 2 in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9344,Roads,Completed,NG-AMBATTUR,86,2340000,"Providing and Laying BT Road at Ganesh Street Reach 1 in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/9348,Roads,Completed,NG-AMBATTUR,86,1820000,"Providing and Laying BT Road at Reddy Street Main Road Reach 2 in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/9349,Roads,Completed,NG-AMBATTUR,86,1820000,"Providing and Laying BT Road at Reddy Main Road Reach 1 in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/9350,Roads,Completed,NG-AMBATTUR,86,1600000,"Providing and Laying BT Road at Kalyani Industrial Estate 4th Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9351,Roads,Completed,NG-AMBATTUR,86,1460000,"Providing and Laying BT Road at Kalyani Industrial Estate 3rd Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9352,Roads,Completed,NG-AMBATTUR,86,1580000,"Providing and Laying BT Road at Kalyani Industrial Estate 2nd Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9353,Roads,Completed,NG-AMBATTUR,86,1600000,"Providing and Laying BT Road at Kalyani Industrial Estate 1st Cross Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9354,Roads,Completed,NG-AMBATTUR,86,1780000,"Providing and Laying BT Road at Kalyani Industrial Estate in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9355,Roads,Completed,NG-AMBATTUR,86,3000000,"Providing and Laying BT Road at Kannadasan Cross Street, Elango Street & THiruvalluvar Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9356,Roads,Completed,NG-AMBATTUR,86,2700000,"Providing and Laying BT Road at NSK Street, Kannadasan Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9357,Roads,Completed,NG-AMBATTUR,86,2900000,"Providing and Laying BT Road at Pillayar Kovil Street, Pillayar Kovil Cross Street & Kalidasan Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9358,Roads,Completed,NG-AMBATTUR,86,2600000,"Providing and Laying BT Road at Amman Kovil Street & Annai Sathya Nagar Main Road in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9359,Roads,Completed,NG-AMBATTUR,86,3000000,"Providing and Laying BT Road at Kambar Street & Ambethkar Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9360,Roads,Completed,NG-AMBATTUR,86,3000000,"Providing and Laying BT Road at Zeon Street, Bajanai Kovil Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9361,Roads,Completed,NG-AMBATTUR,86,2800000,"Providing and Laying BT Road at Kamaraj Nagar 4th & 5th Streets, Theivethamman Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9362,Roads,Completed,NG-AMBATTUR,86,2720000,"Providing and Laying BT Road at Kamaraj Nagar 1st, 2nd & 3rd Streets in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9365,Roads,Completed,NG-AMBATTUR,86,2700000,"Providing and Laying BT Road at Link Street & Ram Poorna Nagar 4th Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9366,Roads,Completed,NG-AMBATTUR,86,3000000,"Providing and Laying BT Road at Alamaram Street & Amman Kovil Street (Chinna Colony) in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/9369,Roads,Completed,NG-AMBATTUR,86,2300000,"Providing and Laying BT Road at Padasalai Street & V.O.C 2nd Cross Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/9370,Roads,Completed,NG-AMBATTUR,86,2100000,"Providing and Laying BT Road at Kuppam & Ambethkar Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/9371,Roads,Completed,NG-AMBATTUR,86,2500000,"Providing and Laying BT Road at Reddy 2nd Street & Vanniyar Street in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/9372,Roads,Completed,NG-AMBATTUR,86,2800000,"Providing and Laying BT Road at South Reddy Main Road in DIvision 86, Unit - 19, Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/11497,Buildings,Completed,NG-AMBATTUR,87,840000,"Demolition and reconstruction of compound wall existing EOC building in div-87,Unit-19,Zone-7.",Own Sources,7,2016-17,2018-19 NG/2016-17/14504,Buildings,Completed,NG-AMBATTUR,87,360000,"Improvements works to the Amma unavagam At M.T.H Road and Church road in,Zone-VII,Unit-19, division-87,",Own Sources,7,2016-17,2018-19 NG/2016-17/18446,Buildings,Completed,NG-AMBATTUR,87,600000,"Providing major improvements to the existing EOC building @church road in Division-87,Unot-19,Zone-VII.",Own Sources,7,2016-17,2018-19 NG/2016-17/18612,Buildings,Completed,NG-AMBATTUR,87,580000,"New construction of Compost Yard at Mugappair road in Div-87, Unit-19, Zone-7.",Own Sources,7,2016-17,2018-19 NG/2016-17/19200,Buildings,Completed,NG-AMBATTUR,87,600000,"Demolition hospital old building at church road in Division-87,Unit-19,Zone-VII.",Own Sources,7,2016-17,2017-18 NG/2016-17/19346,Buildings,Completed,NG-AMBATTUR,87,520000,"Improvements to the GCC buildings in division-87,unit-19,zone-7.",Own Sources,7,2016-17,2018-19 NG/2016-17/4564,Storm Water Drain,Completed,NG-AMBATTUR,87,990000,"Desilting And Repair Works To The Existing Road Side Drain And Storm Water Drain At Various Streets InDivision-87, Unit-19,Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/5840,Buildings,Completed,NG-AMBATTUR,87,116000,"Improvement work to the Chennai middle school at DR.Moorthy nagar in div-87,unit-19,Zone-7",Own Sources,7,2016-17,2018-19 L/2016-17/18153,Electrical,Completed,L-Electrical,88,188000,Restoration of 8nos of 2X400W MH fitting in 30 mtr highmast at Padi service roadin DN 88,Own Sources,7,2016-17,2017-18 NG/2016-17/14500,Buildings,Completed,NG-AMBATTUR,88,127000,"Improvements works to the Amma unavagam at Kumaran Nagar in Zone-7, Unit-19, Division-88.",Own Sources,7,2016-17,2018-19 NG/2016-17/14507,Buildings,Completed,NG-AMBATTUR,88,24500,"Improvements works to the Amma unavagam at Pandurangapuram in Zone-7, Unit-19, Division-88.",Own Sources,7,2016-17,2018-19 NG/2016-17/16303,Parks,Completed,NG-AMBATTUR,88,1036000,"Repairs works to A.P Plot Park, C-Sector Park, B-Sector Park, Millienium Park Due to Damage Caused due to Cyclone Vardha in Dn-88, Unit-19, Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/18616,Buildings,Completed,NG-AMBATTUR,88,494000,"Improvements works to Compost Yard at Pandurangapuram Burial Ground in Div-88, Unit-19, Zone-7",Own Sources,7,2016-17,2018-19 NG/2016-17/4566,Storm Water Drain,Completed,NG-AMBATTUR,88,995000,"DE-SILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DIVISION-88, UNIT-19, ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/8786,Roads,Completed,NG-AMBATTUR,88,2500000,"Gold Milling and Re-Laying of Bituminous Concrete Road at Mahatma Gandhi Road in Division-88, Unit-19, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/8812,Roads,Completed,NG-AMBATTUR,88,521000,"Laying of Bituminous Concrete Road at Anna 3rd Street in Division-88, Unit-19, Zone-7.",Own Sources,7,2016-17,2017-18 L/2016-17/13414,Electrical,Completed,L-Electrical,89,411400,"Provision of 10 Nos of Kiosk Pillar with 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div 89,90,91,92 and 93 Zone-VII,Ambattur",Own Sources,7,2016-17,2017-18 NG/2016-17/0433,Buildings,Completed,NG-AMBATTUR,89,670000,"CONSTRUCTION OF AMMA KUDINEER STRUCTURE IN METRO WATER CAMPUS AT THIRUMANGALAM - ESTATE MAIN ROAD (OPP. TO DAV BOYS SCHOOL) IN DIVISION-89, UNIT-19, ZONE-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/15146,Buildings,Completed,NG-AMBATTUR,89,790000,"ANNUAL IMPROVEMENTS WORKS TO PARKS,COC BUILDINGS ETC IN DIVISION -89, UNIT-20, ZONE-VII .",Own Sources,7,2016-17,2018-19 NG/2016-17/15984,Roads,Completed,NG-AMBATTUR,89,490000,"Providing and fixing of Signage Street Name Boards at Various streets in Div-89,Unit-20,Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/16675,Parks,Completed,NG-AMBATTUR,89,768000,"Repairs and Improvement for TVS Colony Park, Akshaya Colony Park in Div-89, Unit-20, Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/4824,Storm Water Drain,Completed,NG-AMBATTUR,89,990000,"Desilting And Repair Works To The Existing Road Side Drain And Storm Water Drain At Various Streets In In Division-89, Unit-19,Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/8519,Parks,Completed,NG-AMBATTUR,89,2900000,"Construction of Compound Wall, Footpath, Providing Greeneries at R-53 Park in TVS Colony 46th Street in Div-89, Unit-19, Zone-7 (Ambattur)",Own Sources,7,2016-17,2017-18 NG/2016-17/11982,Buildings,Completed,NG-AMBATTUR,90,964000,"Construction of Tubler Framed Structure with Metal sheet roofing for Amma Unavaga Service Centre at Collector Nagar in Div-90,Unit-20,Zone-7",Own Sources,7,2016-17,2016-17 NG/2016-17/14089,Buildings,Completed,NG-AMBATTUR,90,183000,"Repair Work to the existing toilets at Thirumangalam main road in division - 90, Unit -20, Zone - 7",Own Sources,7,2016-17,2016-17 NG/2016-17/15982,Roads,Completed,NG-AMBATTUR,90,490000,"Providing and fixing of Signage Street Name Boards at Various streets in Div-90,Unit-20,Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/16632,Parks,Completed,NG-AMBATTUR,90,156000,"Repair and Improvement Work For Collector Nagar and Welcome Colony Block No 46, 47 Parks at Div-90,Unit-20,Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/18063,Buildings,Completed,NG-AMBATTUR,90,498000,"Formation of compost yard in division- 90,Unit- 20,Zone-7",Own Sources,7,2016-17,2018-19 NG/2016-17/4837,Storm Water Drain,Completed,NG-AMBATTUR,90,998000,"De-silting of Storm Water Drain & Side Drain in Div-90, Unit-20, Zone-7.",Own Sources,7,2016-17,2017-18 NG/2016-17/7103,Footpath,Completed,NG-AMBATTUR,90,890000,"IMPROVEMENT WORK AT WELCOME COLONY 49A PARK IN DIV 90, UNIT- 20, ZONE-7",Own Sources,7,2016-17,2017-18 P/2016-17/19679,Parks,Completed,P-Parks and Playfields,90,2464000,"Formation of New Park at Thirumanagalam Main Road, Mogappair in Dn-90, Unit-20, Zone-7",Grants,7,2016-17,2018-19 BR/2016-17/4312,Roads,Completed,BR-Bus Route Roads,91,690000,Supplying and fixing of Front facia & Back drop in the stainless steel Bus shelter at various bus route roads in zone - 7& 8,Own Sources,7,2016-17,2017-18 NG/2016-17/1264,Parks,Completed,NG-AMBATTUR,91,387500,PROVIDING GREENERIES TO EXISTING PARTK AT MOGAPPAIR ERI SCHEME 8TH STREET IN DIV-91 UNIT-20 ZONE-07(AMBATTUR),Own Sources,7,2016-17,2017-18 NG/2016-17/15260,Parks,Completed,NG-AMBATTUR,91,960000,IMPROVEMENT WORKS TO MOGAPPAIR ERI SCHEME 8th CROSS STREET PARK IN DIV-91 UNIT-20 ZONE-07(AMBATTUR),Own Sources,7,2016-17,2018-19 NG/2016-17/16232,Buildings,Completed,NG-AMBATTUR,91,830000,"REPAIRS AND IMPROVEMENTS WORKS (DUE TO VARDAH CYCLONE) TO EXISTING PARKS AT MOGAPPAIR WEST BUS STAND PARK, JESWANTH NAGAR PHASE 1&2 , MOGAPPAIR INDUSTRIAL ESTATE MAIN ROAD PARKS IN DIV-91 UNIT-20 ZONE-7 (AMBATTUR)",Own Sources,7,2016-17,2017-18 NG/2016-17/17505,Roads,Completed,NG-AMBATTUR,91,10200000,"RELAYING OF FLOOD DAMAGED ROAD AT MOGAPPAIR ERI SCHEME 2ND,3RD,5TH,7TH,9TH MAIN ROAD AND MOGAPPAIR ERI SCHEME 3RD,8TH STREET AND MOGAPPAIR ERI SCHEME 1ST MAIN ROAD EXTENSION IN DIV-91 UNIT-20 ZONE-07 (AMBATTUR)",Own Sources,7,2016-17,2017-18 NG/2016-17/18657,Roads,Completed,NG-AMBATTUR,91,333000,"PROVIDING SPEED BREAKER(AS PER IRC STANDARD) AT MOGAPPAIR ERI SCHEME 10TH STREET AND 7TH BLOCK CANAL ROAD IN DIVISION-91,UNIT-20,ZONE-7",Own Sources,7,2016-17,2019-20 NG/2016-17/19192,Buildings,Completed,NG-AMBATTUR,91,369000,REPAIR AND MAINTANANCE WORKS AT GCC BUILDINGS AND PARKS IN DIVISION-91 UNIT-20 ZONE-7 (AMBATTUR),Own Sources,7,2016-17,2018-19 NG/2016-17/2797,Buildings,Completed,NG-AMBATTUR,91,920000,"ANNUAL MAINTAINENCE TO CORPORATION BUILDINGS, PARKS, AMMA UNAVAGAM, UPHC IN DIV-91 UNIT-20 ZONE-7",Own Sources,7,2016-17,2016-17 NG/2016-17/3125,Buildings,Completed,NG-AMBATTUR,91,740000,"IMPROVEMENT WORKS TO THE EXISTING CHENNAI MIDDLE SCHOOL AT 7TH BLOCK AND ELECTRICAL WORKS TO 2ND,3RD BLOCK SCHOOLS IN DIV-91 UNIT-20 ZONE-7",Own Sources,7,2016-17,2018-19 NG/2016-17/4505,Storm Water Drain,Completed,NG-AMBATTUR,91,860000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-91 UNIT-20 ZONE-7(AMBATTUR),Own Sources,7,2016-17,2017-18 NG/2016-17/8719,Roads,Completed,NG-AMBATTUR,91,2400000,"FORMING AND LAYING BT ROADS AT MOGAPPAIR ERI SCHEME 19TH CROSS STREET, MOGAPPAIR WEST ESTATE 2ND,3RD,4TH & 5TH STREET IN DIV-91 UNIT-20 ZONE-7(AMBATTUR)",Own Sources,7,2016-17,2017-18 BR/2016-17/13209,Road Cut,Completed,BR-Bus Route Roads,92,960000,"Restoration of Roadcut made by TANGEDCO at Church Road (from Eri Scheme 1st Main Road to 6th Main Road) in Dn-92, Zone-7",Deposit Works,7,2016-17,2016-17 BR/2016-17/13211,Road Cut,Completed,BR-Bus Route Roads,92,963000,"Restoration of Roadcut made by CMWSSB at Church Road (from Eri Scheme 6th Main Road to Golden George Bridge) in Dn-92, Zone-7",Deposit Works,7,2016-17,2016-17 BR/2016-17/17292,Roads,Completed,BR-Bus Route Roads,92,2700000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at Pari Road, Mogappair Road and North avenue in Zone 7",Grants,7,2016-17,2017-18 BR/2016-17/19237,Road Cut,Completed,BR-Bus Route Roads,92,2305000,"Restoration of Road cut made by TANGEDCO in Church road from Mugapair Erikkarai scheme 6 th main road to Venugopal street in Div- 92,Zone-7 .",Deposit Works,7,2016-17,2017-18 BR/2016-17/19326,Road Cut,Completed,BR-Bus Route Roads,92,1655000,"Restoration of Road cut made by TANGEDCO in Church road from Golden George Rathinam street to Mugapair Erikarri scheme 6 th main road in Div- 92,Zone-7",Deposit Works,7,2016-17,2017-18 NG/2016-17/0159,Buildings,Completed,NG-AMBATTUR,92,650000,"CONSTRUCTION OF AMMA KUDINEER SHED AT SEETHAKADI SALAI DIV-92,UNIT-20,ZONE-VII",Own Sources,7,2016-17,2016-17 NG/2016-17/11083,Parks,Completed,P-Parks and Playfields,92,12895000,"IMPROVEMENTS TO THE MANGAL ERI PARK AT MOGAPPAIR WEST IN WARD-92,ZONE - VII.",Own Sources,7,2016-17,2018-19 NG/2016-17/14777,Buildings,Completed,NG-AMBATTUR,92,560000,IMPROVEMENTS TO THE EXISTING AMMA UNAVAGAM AT PATTINATHAR SALAI IN DIV 92,Own Sources,7,2016-17,2018-19 NG/2016-17/4425,Storm Water Drain,Completed,NG-AMBATTUR,92,950000,"Desilting and Improvements to the Existing Storm water Drain and Side Drain at Various Street in DIV-92,UNIT-20,ZONE-VII",Own Sources,7,2016-17,2017-18 P/2016-17/19680,Parks,Completed,P-Parks and Playfields,92,2914000,"FORMATION OF NEW PARK AT VENUGOPAL STREET JN. OF PANNER NAGAR, MOGAPPAIR IN DN- 92, ZONE - 7",Grants,7,2016-17,2018-19 P/2016-17/19681,Parks,Completed,P-Parks and Playfields,92,3371000,"Formation of New Park at VGP Nagar (Near Varun Appartment) , Mogappair in Dn-92, Unit-20, Zone-7",Grants,7,2016-17,2018-19 P/2016-17/19682,Parks,Completed,P-Parks and Playfields,92,4162000,"Formation of New Park at Veeramamunivar street (Opp to MGR Adharsh School) Mogappair in Division-92, Unit-20, Zone-7.",Grants,7,2016-17,2018-19 NG/2016-17/10326,Roads,Completed,NG-AMBATTUR,93,1050000,"Laying of Bituminous Concrete road at Indira Gandhi Street in Div-93,Unit-20,Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/13058,Roads,Completed,NG-AMBATTUR,93,1240000,"Providing and Laying of BT Road at Samson Saroja Street in Div-93,Unit-20,Zone-7.",Own Sources,7,2016-17,2016-17 NG/2016-17/15979,Roads,Completed,NG-AMBATTUR,93,490000,"Providing and fixing of Signage Street Name Boards at Various streets in Div-93,Unit-20,Zone-7",Own Sources,7,2016-17,2017-18 NG/2016-17/16613,Parks,Completed,NG-AMBATTUR,93,543000,"REPAIRS AND IMPROVEMENTS WORKS (DUE TO VARDAH CYCLONE) AT VEERAMAMUNIVAR PARK IN DIV-93,UNIT-20,ZONE-7",Own Sources,7,2016-17,2017-18 NG/2016-17/19157,Buildings,Completed,NG-AMBATTUR,93,565000,"CONSTRUCTION OF COMPOST YARD AT GANGAI AMMAN NAGAR MAIN ROAD IN DIV-93, UNIT-20, ZONE-7.",Own Sources,7,2016-17,2018-19 NG/2016-17/19865,Buildings,Completed,NG-AMBATTUR,93,795000,"ANNUAL MAINTENANCE TO CORPORATION BUILDING AND PARKS IN DN-93, U-20,Z7",Own Sources,7,2016-17,2018-19 NG/2016-17/4542,Storm Water Drain,Completed,NG-AMBATTUR,93,997000,Desilting of Side Drains at Various Places in Div-93,Own Sources,7,2016-17,2017-18 D/2016-17/5184,Storm Water Drain,Completed,D-Storm Water Drains,94,16474000,"Dismantling of existing storm water Drain of size 1500x1500mm and Reconstruction of storm water drain of size 1500x1500mm of along Villivakkam Sidco nagar 2nd main road and B sector street from Sidco nagar 2nd main road(near Mosque) to Burial ground compound wall in Dn.94,Zone-VIII.",Own Sources,8,2016-17,2016-17 L/2016-17/13405,Electrical,Completed,L-Electrical,94,750100,"Supply & Replacement of 17 nos of Kiosk Pillar box at Various places in Dn-94,95,103 & 104 at Zone-VIII Area.",Own Sources,8,2016-17,2017-18 L/2016-17/18020,Electrical,Completed,L-Electrical,94,188400,"WORK: Supply and Fixing of 2 Core SMC Fuse box 200 nos at various places in Division-94,95 & 99 Zone-8 area.",Own Sources,8,2016-17,2017-18 NH/2016-17/13623,Storm Water Drain,Completed,NH-ANNA NAGAR,94,396000,"PROVIDING WATER SUPPLY ARRANGEMENT FOR AMMA UNAVAGAM AT NORTH SIVAN KOIL STREET IN DN 94, UNIT-21, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/13808,Buildings,Completed,NH-ANNA NAGAR,94,80000,"IMPROVEMENTS TO DIVISION OFFICE 94 AT PAINTING AND ELECTRICAL WORK IN DN-94,UNIT-21,ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/13895,Roads,Completed,NH-ANNA NAGAR,94,148000,"REPAIRS AND MAINTENANCE OF PUBLIC CONVINCE AT SATHYA NAGAR IN DN 94, UNIT-21, ZONE-8",Own Sources,8,2016-17,2016-17 NH/2016-17/14370,Roads,Completed,NH-ANNA NAGAR,94,109000,"MAINTENANCE AND RECTIFYING ELECTRICAL ITEMS AND DAMPNESS IN FIRST FLOOR IN CMS AT NORTH SIVAN KOIL STREETIN DN 94, ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/15289,Buildings,Completed,NH-ANNA NAGAR,94,842000,"WATER SUPPLY , DRAINAGE,GREENARY AND ELECTRICAL ARRANGEMENTS TO AMMA KUDINEER PLANT ROOM AT SIDCO NAGAR 4TH MAIN ROAD IN DN 94,UNIT 21,ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/15522,Buildings,Completed,NH-ANNA NAGAR,94,255000,REPAIRS AND IMPROVEMENTS WORK IN AMMA UNAVAGAM NEAR DIVISION OFFICE IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/15523,Parks,Completed,NH-ANNA NAGAR,94,210000,REPAIRS AND IMPROVEMENTS WORK AT NORTH JEGANATHAN NAGAR 1ST STREET PARK INSIDE IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/15524,Roads,Completed,NH-ANNA NAGAR,94,96000,IMPROVEMENTS TO BIN PLATFORM AT VARIOUS STREETS IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/15525,Buildings,Completed,NH-ANNA NAGAR,94,198000,SUPPLY AND LAYING SERVICE CONNECTION CABLE TO VILLIVAKKAM SUBWAY AND SERVICE TO 3 NOS OF OIL MOTORS AT VARIOUS LOCATION IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/15527,Buildings,Completed,NH-ANNA NAGAR,94,215000,IMPROVEMENTS TO WATER SUPPLY ARRANGEMENTS IN DIVISION OFFICE CAMPUS IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/15728,Buildings,Completed,NH-ANNA NAGAR,94,320000,"REPAIR ELECTRICAL MOTOR, REPAIRED SUBMERGE MOTOR REPLACE IN TO EFFLUENT SUBMERGE MOTOR AND REPAIR DAMAGE SUBWAY ROAD IN VILLIVAKKAM SUBWAY IN DN-94, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/15831,Buildings,Completed,NH-ANNA NAGAR,94,253000,"REPAIR AND RESTORING DAMAGE COC BUILDING IN VARDHAH CYCLONE DIVSION 94 UNIT-21, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/18793,Roads,Completed,NH-ANNA NAGAR,94,248000,ANNUAL MAINTENANCES OF VILLIVAKKAM SUB WAY ENGAGING OF WATCH MAN AND ELECTRICIAN FOR FOUR MONTHS IN DIVISION-94. UNIT-21. ZONE-8.,Own Sources,8,2016-17,2018-19 NH/2016-17/18802,Storm Water Drain,Completed,NH-ANNA NAGAR,94,394000,"IMPROVEMENT TO SWD AT S.J.N 2ND MAIN ROAD (FROM DOOR NO 44/71 TO 101) IN DN-94, U-21,Z-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/18804,Storm Water Drain,Completed,NH-ANNA NAGAR,94,394000,"IMPROVEMENT TO SWD AT S.J.N 2ND MAIN ROAD (DOOR NO:101 TO JN OF S.J.N.4TH CROSS STREET) IN DN-94, U-21,Z-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/19146,Buildings,Completed,NH-ANNA NAGAR,94,397000,DISMANTLING DAMAGED RCC ROOF AND LAYING OF NEW RCC ROOF TO CREMATORIUM SHED AT ( VILLIVAKKAM BURIAL GROUND ) M.T.H ROAD IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2016-17 NH/2016-17/19147,Buildings,Completed,NH-ANNA NAGAR,94,395000,ADDITIONAL WORKS TO CREMATORIUM SHED AT ( VILLIVAKKAM BURIAL GROUND ) M.T.H ROAD IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2016-17 NH/2016-17/19148,Buildings,Completed,NH-ANNA NAGAR,94,370000,PROVIDING ELECTRICAL ARRANGEMENTS TO CREMATORIUM SHED AT (VILLIVAKKAM BURIAL GROUND ) M.T.H ROAD IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2016-17,2016-17 NH/2016-17/19149,Buildings,Completed,NH-ANNA NAGAR,94,345000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO TOILET ROOM AT VILLIVAKKAM BURIAL GROUND IN DN-94,UNIT-21,ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/19687,Buildings,Completed,NH-ANNA NAGAR,94,281000,"PROPOSED CONSTRUCTION OF CREACH AT SIDCO 42ND STREET IN DN-94,U-21,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/3065,Buildings,Completed,NH-ANNA NAGAR,94,970000,"PROVIDING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT VARIOUS STREETS IN DN-94,U-21,Z-8 (COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/4121,Electrical,Completed,NH-ANNA NAGAR,94,990000,"IMPROVEMENT WORK TO THE EXISTING GYM BUILDING WARD COUNCILLOR FUND 2016-17 IN DIVISION-94,UNIT-21 ,ZONE-8",Own Sources,8,2016-17,2016-17 NH/2016-17/5252,Storm Water Drain,Completed,NH-ANNA NAGAR,94,990000,Desilting of Storm Water Drain at Various Streets in division 94 unit 21 zone 08,Own Sources,8,2016-17,2016-17 NH/2016-17/5253,Storm Water Drain,Completed,NH-ANNA NAGAR,94,990000,Desilting of Storm Water Drain at Various Streets in division 94 unit 21 zone 08.,Own Sources,8,2016-17,2016-17 NH/2016-17/5254,Storm Water Drain,Completed,NH-ANNA NAGAR,94,990000,Desilting of Storm Water Drain at Various Streets in division 94 unit 21 zone 08,Own Sources,8,2016-17,2016-17 NH/2016-17/7390,Parks,Completed,NH-ANNA NAGAR,94,350000,"IMPROVEMENTS TO CHILDREN PLAY AREA AT SIDCO NAGAR 60TH STREET IN DN-94, UNIT-21, ZONE-08.(COUNCILLOR FUND 16-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/7391,Parks,Completed,NH-ANNA NAGAR,94,350000,"IMPROVEMENTS TO CHILDREN PLAY AREA AT SIDCO NAGAR 33RD STREET IN DN-94, UNIT-21, ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/7392,Parks,Completed,NH-ANNA NAGAR,94,300000,"IMPROVEMENTS TO CHILDREN PLAY AREA AT RAJAMAGALAM 2 MAIN ROAD IN DN-94, UNIT-21, ZONE-08.(COUNCILLOR FUND 16-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/8232,Storm Water Drain,Completed,NH-ANNA NAGAR,94,995000,"IMPROVEMENTS TO SWD (NORTHERN SIDE) IN THE BURIAL GROUND, REACH - 1 IN DN-94,UNIT-21,ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/8233,Storm Water Drain,Completed,NH-ANNA NAGAR,94,999000,"IMPROVEMENTS TO SWD (SOUTHERN SIDE) AT VILLIVAKAM BURIAL GROUND , REACH-2, IN DN-94,UNIT-21,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/9143,Storm Water Drain,Completed,NH-ANNA NAGAR,94,983000,"PROPOSED CONSTRUCTION OF AMMA KUDINEER PLANT ROOM AT SIDCO NAGAR 4TH MAIN ROAD IN DN 94,UNIT 21,ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/9839,Buildings,Completed,NH-ANNA NAGAR,94,998000,"IMPROVEMENT TO STORM WATER DRAIN AT SOUTH JAGANATHAN NAGAR 2ND MAIN ROAD IN DN-94, UNIT-21, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/9840,Buildings,Completed,NH-ANNA NAGAR,94,999000,"IMPROVEMENT TO STORM WATER DRAIN AT SOUTH JAGANATHAN NAGAR 2ND CROSS STREET IN DN-94, UNIT-21, ZONE-8",Own Sources,8,2016-17,2017-18 BR/2016-17/17726,Roads,Completed,BR-Bus Route Roads,95,783000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Millers Road, New Avadi Road, Halls Road, Sidco Nagar 4th Main Road and MTH Road in Zone-8",Grants,8,2016-17,2017-18 D/2016-17/5882,Storm Water Drain,Completed,D-Storm Water Drains,95,22896000,"Dismantling and Reconstruction of storm water Drain of size 3000X3000 mm along Kumaran Nagar from Burial Ground Compound wall to TVS Canal Dn-95,Zone-VIII.",Own Sources,8,2016-17,2017-18 L/2016-17/17953,Electrical,Completed,L-Electrical,95,171800,"Provision of of 4 nos 6 mtr lamp post with 1 mtr stright bracket and 4 nos 40-50 W led fitting at NRN compount in div -95,zone-VIII",Own Sources,8,2016-17,2017-18 NH/2016-17/1053,Buildings,Completed,NH-ANNA NAGAR,95,990000,"Additional improvement works to health post at venugopal street, dn.95, zone-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/11711,Storm Water Drain,Completed,NH-ANNA NAGAR,95,998000,"DESILTING OF TVS CANAL FROM AGARTHIYAR NAGR 14TH, 15TH, 16TH TO ANNA NAGAR RAILWAY STATION IN DN-95 UNIT-21, ZONE - 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/11713,Storm Water Drain,Completed,NH-ANNA NAGAR,95,998000,"DESILTING OF OTTERI NALLA ( FROM MULLAI NAGAR 11TH STREET TO MURUGAN TEMPLE) IN DN-95,U-21,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/11720,Storm Water Drain,Completed,NH-ANNA NAGAR,95,998000,"DESILTING OF TVS CANAL ( FROM SIVA SHAKTHI COLONY MAIN STREET SOUTH END TO AGATHIYAR NAGAR 14TH,15TH,16TH STREET JUNCTION) IN DN-95,U-21,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/12750,Roads,Completed,NH-ANNA NAGAR,95,1750000,"ATTENDING BT PATCH WORK ( FLOOD AFFECTED ROAD)BY PAVER AT THANTHONI AMMAN KOVIL STREET FROM MTH ROAD TO SOUTH MADA STREETIN DN-95,U-21,ZONE-8",Own Sources,8,2016-17,2016-17 NH/2016-17/12955,Roads,Completed,NH-ANNA NAGAR,95,250000,"REPAIR WORKS FOR CORPORTION BUILDING VARIOUS LOCATION IN DIVSION-95, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/12958,Buildings,Completed,NH-ANNA NAGAR,95,199000,"REPAIR AND IMPROVEMENT TO SLATTER WORKS AT NEW AAVADI ROAD & DIVISION OFFICE IN DN-95, U-21, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/12960,Buildings,Completed,NH-ANNA NAGAR,95,168000,"REPAIR AND IMPROVEMENT TO AMMA UNAVAGAM AND TREE CUTTING WORK AT VARIOUS STREETS IN DN-95, U-21, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/12961,Buildings,Completed,NH-ANNA NAGAR,95,252000,"REPAIR AND IMPROVEMENT TO CORPORATION BUILDINGS PLUMMING WORK AND HOSPITAL SHED WORK AT VARIOUS STREETS IN DN-95, U-21, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/12962,Buildings,Completed,NH-ANNA NAGAR,95,91000,"REPAIR AND IMPROVEMENT TO CORPORATION SCHOOLS RAMP WORK AT VARIOUS STREETS IN DN-95, U-21, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/12963,Buildings,Completed,NH-ANNA NAGAR,95,280000,"REPAIR AND IMPROVEMENT TO STORM WATER DRAIN WORK AT VARIOUS STREETS IN DN-95, U-21, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/12982,Storm Water Drain,Completed,NH-ANNA NAGAR,95,136000,"Desilting of storm water drain at kambar kudierupu,w-Block c-sector,Imayam colony and I Bock 10th street in division 95 unit 21 zone 08",Own Sources,8,2016-17,2017-18 NH/2016-17/13971,Road Cut,Completed,NH-ANNA NAGAR,95,565000,Restoration of road cut at Thiru nagar 11th street in division 95 unit 21 zone 08,Deposit Works,8,2016-17,2017-18 NH/2016-17/14093,Buildings,Completed,NH-ANNA NAGAR,95,50000,"REPAIR AND IMPROVEMENT WORK IN PUBLC CONVENIENCE AT SOUTH MADA STREET AND ICF ANNEX ROAD IN DN-95,,U-21,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/14095,Roads,Completed,NH-ANNA NAGAR,95,1700000,"FORMATION OF NEW ROAD AT SIVASAKTHI COLONY ALONG WITH TVS CANAL IN DN-95,U-21,,Z-08 (MLA FUND 2016-2017)",MLACDS,8,2016-17,2017-18 NH/2016-17/14621,Buildings,Completed,NH-ANNA NAGAR,95,999000,"MLA FUND 2016-17 CONSTRUCTION OF COMPOUND WALL AT WEST SIDE PUMP ROOM AND GRILL WORK IN KAMBAR COLONY PLY GROUND IN DIV-95, UNIT-21, ZONE-08",MLACDS,8,2016-17,2018-19 NH/2016-17/14651,Buildings,Completed,NH-ANNA NAGAR,95,680000,"MLA FUND 2016-17 RELAYING THE ROAD WITH PEVAR FINISHER AT THIRU NAGAR 11TH STREET IN DIVISION-95, UNIT-21, ZONE-08( MLA FUND 2016-17)",MLACDS,8,2016-17,2017-18 NH/2016-17/14927,Storm Water Drain,Completed,NH-ANNA NAGAR,95,575000,IMPROVEMENTS TO STORM WATER DRAIN AT THIRUMANGALAM ROAD IN DIVISION 95 UNIT21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/14929,Roads,Completed,NH-ANNA NAGAR,95,560000,RELAYING ROAD AT I BLOCK 1ST STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/14930,Roads,Completed,NH-ANNA NAGAR,95,140000,ATTENDING CEMENT CONCRETE PATCH WORK AT VARIOUS STREETS IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/14931,Buildings,Completed,NH-ANNA NAGAR,95,70000,IMPROVEMENTS TO TOILET ROOM AT SOUTH MADA STREET (NEAR VILLIVAKAM BUS DEPOT) IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/14932,Footpath,Completed,NH-ANNA NAGAR,95,198000,IMPROVEMENTS TO FOOTPATH AT JUNCTION OF 13TH MAIN ROAD AND JUNCTION OF 19TH MAIN ROAD IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/14961,Storm Water Drain,Completed,NH-ANNA NAGAR,95,995000,"CONSTRUCTION OF STORM WATER DRAIN IN RAJIV GANDHI NAGAR 2ND STREET ( FROM CHENNAI BATTAI ROAD TO DOOR NO:37)IN DN-95,U-21,Z-08",MLACDS,8,2016-17,2017-18 NH/2016-17/15569,Roads,Completed,NH-ANNA NAGAR,95,51000,REPAIRS AND SERVICE TO MOTORS AT VARIOUS LOCATION IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/15571,Roads,Completed,NH-ANNA NAGAR,95,51000,SUPPLY OF 1000LTR SINTEX TANK TO SLAUGHTER AT NEW AVADI ROAD AND SERVICE TO TREE CUTTING MACHINE IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2016-17,2017-18 NH/2016-17/16702,Parks,Completed,NH-ANNA NAGAR,95,787000,"REPAIR WORK OF PLAYGROUND AND PARK IN VARIOUS PLACES ( VASANTHAM COLONY 2ND STREET, VALLALAR KUDI IRUPU, W-BLOCK GANDHI PARK AND I-BLOCK 2ND STREET IN DN-95,U-21,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/18119,Buildings,Completed,NH-ANNA NAGAR,95,28500,SUPPLY AND FIXING OF NAME BOARD FOR HEALTH CENTER AT VENUGOPAL STREET AND MANNADI STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2016-17,2018-19 NH/2016-17/18480,Roads,Completed,NH-ANNA NAGAR,95,900000,Relaying the road with camber correction by mini hot mix plant at South Mada street 2nd lane in division 95 unit 21 zone 08 (MP Fund),MPLADS,8,2016-17,2018-19 NH/2016-17/18481,Roads,Completed,NH-ANNA NAGAR,95,600000,Relaying the road with camber correction by mini hot mix plant at T.V.K Main street from Ration shop to Narayana Maistri 1st street in division 95 unit 21 zone 08 (MP Fund ),MPLADS,8,2016-17,2018-19 NH/2016-17/2994,Roads,Completed,NH-ANNA NAGAR,95,798000,"RELAYING THE ROAD AT THANTHONRI AMMAN LANE EXTN,BAJANAI KOIL 3RD STREET, BAJANAI KOIL CROSS STREET AND RADHAKRISHNA CROSS STREET IN DN-95,U-21,Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/2995,Roads,Completed,NH-ANNA NAGAR,95,868000,"RELAYING THE ROAD AT SEEYALAM 2ND STREET, 3RD STREET AND EAST SEEYALAM 2ND STREET IN DN-95,U-21,Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/2996,Roads,Completed,NH-ANNA NAGAR,95,742000,"RELAYING THE ROAD AT THIRUVEETHIAMMAN KOIL 1ST LANE, 2ND LANE AND THIRU.VA 1ST LANE IN DN-95,U-21,Z-8 RELAYING OF THE",Own Sources,8,2016-17,2016-17 NH/2016-17/2997,Roads,Completed,NH-ANNA NAGAR,95,852000,"RELAYING THE ROAD AT LAKSHMIPURAM 3RD STREET AND THIRU VENKAT IYER 2ND STREET IN DN-95,U-21,Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/2998,Roads,Completed,NH-ANNA NAGAR,95,817000,"RELAYING THE ROAD AT NRN COLONY 1ST LANE, 2ND LANE, 3RD LANE AND 4TH LANE IN DN-95,U-21,Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/3062,Buildings,Completed,NH-ANNA NAGAR,95,990000,"PROVIDING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET AT VARIOUS STREETS IN DN-95,U-21,Z-8 (COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/4524,Storm Water Drain,Completed,NH-ANNA NAGAR,95,430000,Dismantling and Re-Construction of Storm Water Drain at N.R.N Colony From cross street in Division 95 Unit 21 Zone 08,Own Sources,8,2016-17,2016-17 NH/2016-17/4525,Storm Water Drain,Completed,NH-ANNA NAGAR,95,997000,Dismantling and Re-Construction of Storm Water Drain at N.R.N Colony From Thirumangalam Main Road in Division 95 Unit 21 Zone 08,Own Sources,8,2016-17,2017-18 NH/2016-17/4544,Storm Water Drain,Completed,NH-ANNA NAGAR,95,998000,Desilting of Storm Water Drain at Various Streets in division 95 unit 21 zone 08,Own Sources,8,2016-17,2017-18 NH/2016-17/4582,Parks,Completed,NH-ANNA NAGAR,95,995000,"PROVIDING YOGA STAGE TO PLAYGROUND AT ISHWARYA KUDI IRUPU IN DN-95,U-21,Z-08 (MLA IMPROVEMENT FUND 2015-16)",MLACDS,8,2016-17,2017-18 NH/2016-17/4585,Parks,Completed,NH-ANNA NAGAR,95,980000,"IMPROVEMENT TO PLAY GROUND AT AGATHIYAR NAGAR 3RD STREET IN DN-95,U-21,Z-08( WARD COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/6330,Buildings,Completed,NH-ANNA NAGAR,95,998000,"DESILTING OF OTTERI NALLA FROM ICF RCC WALL EAST SIDE TO MULLAI NAGAR 11STREET IN DN-95 UNIT-21, ZONE - 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/6331,Buildings,Completed,NH-ANNA NAGAR,95,998000,"DESILTING OF OTTERI NALLA FROM I BLOCK 38 STREET PARK EAST SIDE TO ICF RCC WALL EAST SIDE IN DN-95 UNIT-21, ZONE - 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/6332,Buildings,Completed,NH-ANNA NAGAR,95,998000,"DESILTING OF OTTERI NALLA FROM MURUGAN TEMPLE TO PADI FLYOVER IN DN-95 UNIT-21, ZONE - 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/6680,Roads,Completed,NH-ANNA NAGAR,95,393000,"RELAYING THE ROAD AT THIRU VI.KA 4th STREET IN DN-95,U-21,Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/7532,Parks,Completed,NH-ANNA NAGAR,95,990000,"PROVIDING GRILL FOR KAMBAR KUDI IRUPU PLAYGROUND , THIRUVALLUVAR KUDI IRUPU PLAYGROUND AND VALLAR KUDI IRUPU IN DN-95,U-21,Z-08 ( WARD COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/7958,Storm Water Drain,Completed,NH-ANNA NAGAR,95,985000,"DISMALTING TOP SLAB AND RE-CONSTRUCTION OF SWD AT MANADI OTHAVADA STREET ( FROM EAST MADA STREET TO MANADI OTHAVADA STREET TRANSFORMER ) IN DN-95,U-21,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/7963,Storm Water Drain,Completed,NH-ANNA NAGAR,95,996000,"CONSTRUCTION OF SWD AT AGATHIYAR NAGAR 16TH STREET (FROM TVS CANAL TO JUNCTION OF 15TH STREET) AND AGATHIYAR NAGAR 29TH STREET ( FROM THIRUMANGALAM ROAD TO EB POST NO:1845) IN DN-95,U-21,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/8511,Roads,Completed,NH-ANNA NAGAR,95,315000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT ADHI NAIDU STREET IN DIVISION 95 UNIT 21 ZONE 08,Deposit Works,8,2016-17,2017-18 BR/2016-17/13703,Roads,Completed,BR-Bus Route Roads,96,950000,"Repairs to the existing Footpath, Centre Median and Other Improvement works at various Bus Route roads in Zone-VIII",Own Sources,8,2016-17,2019-20 BR/2016-17/1679,Road Cut,Completed,BR-Bus Route Roads,96,2720000,"Restoration of road cut made by CMWSSB at Konnur high road from the jn of Konnur road lane to the jn of Pilnkington road in Dn - 96 , Zone 8 (Chellan NO :BR/2016-17/0001699 , dt;26.04.2016)",Deposit Works,8,2016-17,2016-17 BR/2016-17/17521,Footpath,Completed,BR-Bus Route Roads,96,2170000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at MTH Road, Konnur High Road, Raja Annamalai Road, Flowers Road, Barnaby Road and Balfour Road in Zone 8",Grants,8,2016-17,2017-18 BR/2016-17/9662,Roads,Completed,BR-Bus Route Roads,96,19700000,"Strengthening and relaying the road with DBM & CBC after cold milling by Paver finisher using plastic waste along with traffic improvement works at Konnur High Road from the jn Ayanavaram market to the jn of Medavakkam tank road in Dn - 96, Zone - 8",Grants,8,2016-17,2017-18 NH/2016-17/0515,Buildings,Completed,NH-ANNA NAGAR,96,194000,"REPAIR AND IMPROVEMENTS TO LEAKY TERRACE AT AMMA UNAVAGAM AND E.B OFFICE AT KONNUR HIGH ROAD IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/11123,Buildings,Completed,NH-ANNA NAGAR,96,998000,"IIMPROVEMENTS TO COMPOUND WALL AND OTHER REPAIRS IN K.K NAGAR 10TH STREET GROUND IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2016-17,2016-17 NH/2016-17/11124,Buildings,Completed,NH-ANNA NAGAR,96,65000,"REPAIR AND IMPROVEMENTS TO P.C AT I.C.F SIGNAL AND TAGORE NAGAR IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/11551,Road Cut,Completed,NH-ANNA NAGAR,96,252000,"Restoration of road cut made by CMWSSB at Duraiswamy street in Division-96,Unit -21,Zone-8",Deposit Works,8,2016-17,2016-17 NH/2016-17/11553,Road Cut,Completed,NH-ANNA NAGAR,96,291000,"Restoration of road cut made by CMWSSB at Soma sundaram 1 st. street in division-96,Unit-21, Zone-8.",Deposit Works,8,2016-17,2016-17 NH/2016-17/11729,Buildings,Completed,NH-ANNA NAGAR,96,130000,"Improvements to public convenience at Tagore nagar,K.k.nagar 5th street,Konnur high road in division-96,unit-21,Zone-8",Own Sources,8,2016-17,2016-17 NH/2016-17/13762,Parks,Completed,NH-ANNA NAGAR,96,58000,"MAINTENANCE OF OSR LAND PARK AT KONNUR HIGH ROAD FOR 6 MONTHS IN DN-96,U-21,Z-08",Own Sources,8,2016-17,2018-19 NH/2016-17/13763,Parks,Completed,NH-ANNA NAGAR,96,55000,"MAINTENANCE OF JEEVA PARK FOR 6 MONTHS IN DN-96,U-21,Z-08",Own Sources,8,2016-17,2018-19 NH/2016-17/13918,Storm Water Drain,Completed,NH-ANNA NAGAR,96,1800000,"STRENGTHENING AND RELAYING OF B.T. ROAD USING PAVER FINISHER AT APPADURAI 1ST STREET IN DIVISION - 96, UNIT - 21, ZONE - 8 ( UNDER M.L.A FUND)",MLACDS,8,2016-17,2017-18 NH/2016-17/14390,Buildings,Completed,NH-ANNA NAGAR,96,145000,"REPAIRS AND MAINTENANCE WORKS IN PUBLIC CONVENIENCES AT KK NAGAR 10TH STREET, KONNUR HIGH ROAD,NEW AVADI ROAD JN, GANDHI NAGAR IN WARD-96, UNIT-21, ZONE-VIII",Own Sources,8,2016-17,2016-17 NH/2016-17/18146,Buildings,Completed,NH-ANNA NAGAR,96,98000,"PROVIDING NAME BOARD AT CHC & UPHC HOSPITAL AT AYANAVARAM IN DIVISION-96, UNIT-21, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18147,Roads,Completed,NH-ANNA NAGAR,96,209000,"Repairs to Foot path at Various streets in United India nagar in Division-96,Unit. Zone-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18148,Roads,Completed,NH-ANNA NAGAR,96,159000,"IMPROVEMENT TO CHC 24-HOURS HOSPITAL AT UNITED INDIA NAGAR IN DIVISION-96, UNIT-21, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18149,Roads,Completed,NH-ANNA NAGAR,96,37000,"SUPPLYING OF WELL RINGS FOR SOURCE AGRICATION IN DIVISION-96, UNIT-21, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18150,Footpath,Completed,NH-ANNA NAGAR,96,227000,"IMPROVEMENT TO UPHC HOSPITAL AT OFFICERS COLONY ROAD IN DIVISION-96, UNIT-21, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/2402,Buildings,Completed,NH-ANNA NAGAR,96,990000,"DEMOLISHING AND RE-CONSTRUCTING OF THE STORM WATER DRAIN AT K.M.P STREET IN DIVISION - 96, UNIT- 21, ZONE - 8 ( WARD COUNCILOR DEVELOPMENT FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/2813,Buildings,Completed,NH-ANNA NAGAR,96,999000,"IMPROVEMENTS TO CHENNAI HIGHER SEC.SCHOOL PALAVAYAL IN DN-96,U-21,Z-08 (WARD COUNCILAR FUND -2016-2017)",Own Sources,8,2016-17,2016-17 NH/2016-17/3157,Storm Water Drain,Completed,NH-ANNA NAGAR,96,409000,"REPAIRS AND IMPROVEMENTS TO FOOTHPATH AND STORM WATER DRAIN AT N.M.K STREET(FROM DOOR NO 21/12 TO JUNCTION OF METTU STREET) IN DIVISION - 96, UNIT - 21, ZONE -8",Own Sources,8,2016-17,2016-17 NH/2016-17/3987,Roads,Completed,NH-ANNA NAGAR,96,87000,"PROVIDING PLATFORM FOR SOURCE SEGREGATION AT K.H ROAD IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/3998,Storm Water Drain,Completed,NH-ANNA NAGAR,96,990000,"DESILTING OF STORM WATER DRAIN AT KONNUR HIGH ROAD IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2016-17,2016-17 NH/2016-17/4565,Storm Water Drain,Completed,NH-ANNA NAGAR,96,990000,"DESILTING OF STORMWATER DRAINS AT VARIOUS STREETS IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2016-17,2016-17 NH/2016-17/6524,Roads,Completed,NH-ANNA NAGAR,96,998000,"LAYING OF CC ROAD AT BHOOSANAM STREET IN DN.96, UNIT-21, ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/6662,Buildings,Completed,NH-ANNA NAGAR,96,999000,"IMPROVEMENTS TO CHENNAI HIGHER SECONDARY SCHOOL PALAVAYAL IN DN-96, U-21, Z-8. (WARD COUNCILLOR FUND-2016-2017)",Own Sources,8,2016-17,2016-17 NH/2016-17/8278,Roads,Completed,NH-ANNA NAGAR,96,995000,"LAYING OF CC ROAD AT BHARATHAMADHA STREET IN DN.96, UNIT-21, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/8280,Roads,Completed,NH-ANNA NAGAR,96,998000,"LAYING OF CC ROAD AT NAGAIYAH THOTTAM - NMK LANE IN DN.96, UNIT-21, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/8281,Roads,Completed,NH-ANNA NAGAR,96,241000,"REPAIR AND IMPROVEMENTS TO C.I LABOUR SHED PORTIOUS ROAD IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/0557,Buildings,Completed,NH-ANNA NAGAR,97,83000,"Name of Work: REPAIRS, DESILTING, IMPROVEMENTS TO FOOTPATH AND STORM WARER DRAIN DOOR NO.15/12 TO 16/44 TEMPLE IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2016-17,2017-18 NH/2016-17/10335,Storm Water Drain,Completed,NH-ANNA NAGAR,97,898000,CONSTRUCTION OF SWD AT KULAKKARAI TO BATTACHARY MAIN STREET IN DN-97 UNIT-21 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/14099,Buildings,Completed,NH-ANNA NAGAR,97,50000,"REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE AT SOLAI 3RD STREET IN WARD 97, UNIT-21, ZONE-VIII",Own Sources,8,2016-17,2016-17 NH/2016-17/14384,Buildings,Completed,NH-ANNA NAGAR,97,39700,"REPAIRS AND MAINTENANCE WORKS IN CHENNAI PRIMARY SCHOOL, SOLAI STREET IN WARD-97, UNIT-21, ZONE-VIII",Own Sources,8,2016-17,2016-17 NH/2016-17/1495,Storm Water Drain,Completed,NH-ANNA NAGAR,97,960000,"IMPROVEMENTS TO SWD AT P.E.KOIL MAIN STREET, FROM PE KOIL TEMPLE TO NORTH MADA STREET IN DIVISION-97 UNIT-21 ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/1499,Storm Water Drain,Completed,NH-ANNA NAGAR,97,946000,IMPROVEMENTS TO SWD AT P.E.KOIL NORTH MADA STREET FROM DOOR NO:47 TO P.E. KOIL MAIN STREET IN DIVISION-97 UNIT-21 ZONE-08,Own Sources,8,2016-17,2017-18 NH/2016-17/1574,Buildings,Completed,NH-ANNA NAGAR,97,438979,REPAIRES AND IMPROVEMENTS TO FOOTPATH AND SWD AT PERIYAR SALAI D.NO NADAR SCHOOL TO NMK STREET IN DN 97 U 21 Z 8,Own Sources,8,2016-17,2017-18 NH/2016-17/1575,Buildings,Completed,NH-ANNA NAGAR,97,29000,"PROVIDING PVC PIPE LINE THROUGH EXISTING RAIN WATER HARVESTING AT VARIOUS LOCATIONS DN-97,U-21,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/1576,Buildings,Completed,NH-ANNA NAGAR,97,656000,"PROVIDING GYM EQUIPMENT AT VELLALA STREET GYM IN DN-97,U-21,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/1790,Storm Water Drain,Completed,NH-ANNA NAGAR,97,999000,"Improvements to SWD At PE Koil West Mada Street From 28/3 to North Mada Street In Division 97, Unit 21, Zone 08.",Own Sources,8,2016-17,2017-18 NH/2016-17/1805,Storm Water Drain,Completed,NH-ANNA NAGAR,97,745000,"Construction Of SWD From PE Koil Main Street Tank Bond To Patachariyar Street To Vinayagar koil In Division 97, Unit 21, Zone 8.",Own Sources,8,2016-17,2016-17 NH/2016-17/19383,Buildings,Completed,NH-ANNA NAGAR,97,210000,"REPARIING WORK AT CHENNAI PRIMARY SCHOOL VELLALAR STREET AND AMMA UNAVAGAM AT PERIYAR SALAI DN-97, UNIT-21, ZONR-8",Own Sources,8,2016-17,2017-18 NH/2016-17/3442,Storm Water Drain,Completed,NH-ANNA NAGAR,97,634000,"DISMANTLING RCC ROOF, REPAIR AND DESILTING TO STORM WATER DRAIN ALONG KUNJITHAM GURUSWAMY STREET FROM VELLALAR STREET TO NORTH SIDE DEAD END IN DN-97, U-21, Z-VIII",Own Sources,8,2016-17,2016-17 NH/2016-17/3873,Road Cut,Completed,NH-ANNA NAGAR,97,641000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT ELUMALAI STREET, KUPPUSWAMY NAGAR MAIN STREET AND KUPPUSWAMY NAGAR 2ND STREET IN DN-97, UNIT-21, ZONE-VIII",Deposit Works,8,2016-17,2016-17 NH/2016-17/4006,Buildings,Completed,NH-ANNA NAGAR,97,44300,"RE-CONSTRUCTION OF COMPOUND WALL AT DIVISION OFFICE IN DN-97, UNIT-21, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/4027,Buildings,Completed,NH-ANNA NAGAR,97,54000,"REPAIRS FLOORING WORKS IN CPS SCHOOL AT VELLALA STREET IN DN-97, UNIT-21, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/4376,Buildings,Completed,NH-ANNA NAGAR,97,257000,"Name of Work: REPAIRS, DESILTING AND IMPROVEMENTS TO STORM WARER DRAIN DOOR NO 19 (TEA STALL) TO VINAYAGAR TEMPLE IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2016-17,2017-18 NH/2016-17/4414,Storm Water Drain,Completed,NH-ANNA NAGAR,97,457000,REPAIRES AND IMPROVEMENTS TO FOOTPATH AND SWD AT PERIYAR SALAI LIC QUATERS TO NADAR SCHOOL IN DN-97 U-21 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/5173,Storm Water Drain,Completed,NH-ANNA NAGAR,97,999000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN WARD-97, UNIT-21, ZONE-VIII",Own Sources,8,2016-17,2017-18 NH/2016-17/5174,Buildings,Completed,NH-ANNA NAGAR,97,981000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM AT ADHI ANDHRA NAGAR IN WARD-97,UNIT-21,ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/5997,Road Cut,Completed,NH-ANNA NAGAR,97,998000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MUTHAMMAN KOIL STREET IN WARD-97, UNIT-21, ZONE-VIII",Deposit Works,8,2016-17,2017-18 NH/2016-17/8733,Buildings,Completed,NH-ANNA NAGAR,97,876000,"Improvements to Indoor Shuttle Badminton court ( Court-1) at Vellala street in Div-97, Unit-21, Zone-8 (Ward Councillor Fund 2016 - 17)",Own Sources,8,2016-17,2017-18 NH/2016-17/8739,Buildings,Completed,NH-ANNA NAGAR,97,846000,"Improvements to Indoor Shuttle Badminton court ( Court-2) at Vellala street in Div-97,Unit-21,Zone-8 (Ward Councillor Fund 2016 - 17)",Own Sources,8,2016-17,2017-18 NH/2016-17/8940,Buildings,Completed,NH-ANNA NAGAR,97,78000,"CLEANING OF TEMPLE TANK FOR REMOVAL OF DEAD FISHES AND ALGAE AT PARASURAMA ESWARAN KOIL STREET IN DN-97, UNIT-21, ZONE-VIII",Own Sources,8,2016-17,2017-18 NH/2016-17/9110,Buildings,Completed,NH-ANNA NAGAR,97,799000,"PROVIDING ELECTRICAL ARRANGEMENTS AND IMPROVEMENTS TO INDOOR SHUTTLE COCK COURT AT VELLALAR STREET IN DN-97, UNIT-21, ZONE-VIII (WARD COUNCILLOR FUND 2016 - 17)",Own Sources,8,2016-17,2017-18 NH/2016-17/0513,Buildings,Completed,NH-ANNA NAGAR,98,240000,"IMPROVEMENT TO FOOTPATH AT VENKATESAPURAM COLONY EXTENSION FROM AYANAVARAM SALAI TO PARTHASARATHI STREET ( SOUTH SIDE) IN DN-98,U-23,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/0635,Buildings,Completed,NH-ANNA NAGAR,98,720000,"SUPPLYING AND FIXING OF NAMMA TOILET WITH OUT SEWERAGE RGE.WOMEN -1, REG.MEN-1, URINAL 1 AT ASPIRAN GARDEN IN DIVISION-98,UNIT-23,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/13125,Buildings,Completed,NH-ANNA NAGAR,98,94000,"PROVIDING FENCING AT RAJU STREET DIVISION-98, UNIT-23, ZONE-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/13126,Roads,Completed,NH-ANNA NAGAR,98,99000,"PROVIDING WET MIX AT VARIOUS STREET IN DN-98,U-23,Z-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/15731,Buildings,Completed,NH-ANNA NAGAR,98,395000,"PROVIDING BASEMENT BORE FACILITIES WORK FOR NAMMA TOILET AT LOCKMA NAGER IN DIVISIONN - 98 , UNIT- 23, ZONE- 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/17992,Buildings,Completed,NH-ANNA NAGAR,98,10500,"PROVIDING NAME BOARDS UPHC CENTER AT RATNA SABAPATHY STREET IN DIVISION - 98, UNIT-23, ZONE-8",Own Sources,8,2016-17,2018-19 NH/2016-17/19638,Buildings,Completed,NH-ANNA NAGAR,98,325000,"PROVIDING SHED AT DIVISION OFFICE AND IMPROVEMENT AND MAINTENANCE WORK AT SAMIDASPURAM BRIDGE IN DN-98,U-23,Z-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/7075,Buildings,Completed,NH-ANNA NAGAR,98,46000,"IMPROVEMENT TO AMMA UNAVAGAM AT ASPIRAN GARDEN 1ST STREET IN DN-98,U-23,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/7076,Buildings,Completed,NH-ANNA NAGAR,98,95000,"REPAIR AND IMPROVEMENT TO PUBLIC CONVENIENCE AT SAMIDOSS PURAM IN DN-98,U-23,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/7077,Storm Water Drain,Completed,NH-ANNA NAGAR,98,245000,"ROAD CROSSING WITH D.I PIPE AT LOCKMA NAGAR (FROM ASHA NIVAS WOMEN'S HOSTEL TO CHILDREN'S PLAY GROUND ) IN DN-98,U-23,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/7078,Storm Water Drain,Completed,NH-ANNA NAGAR,98,200000,"ROAD CROSSING WITH D.I PIPE AT POLICE MANIKAM STREET ( FROM POLICE MANIKAM STREET TO AYANAVARAM ROAD) IN DN-98,U-23,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/7080,Storm Water Drain,Completed,NH-ANNA NAGAR,98,300000,"ROAD CROSSING WITH D.I PIPE AT V.P COLONY EXTENSION ( FROM V.P COLONY EXTENSION TO AYANAVARAM ROAD) IN DN-98,U-23,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/7082,Storm Water Drain,Completed,NH-ANNA NAGAR,98,710000,"REPAIR AND IMPROVEMENT TO SWD AT POLICE MANIKAM STREET( CHAINAGE FROM 0M TO 110M ) IN DN-98,U-22,Z-08 ( WARD COUNCILLOR FUND 2016-17 )",Own Sources,8,2016-17,2017-18 NH/2016-17/7496,Buildings,Completed,NH-ANNA NAGAR,98,997000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT PUDHU NAGAR CROSS STREET IN DN-98,U-23,Z-08 (WARD COUNCILOR FUND 2016-17 )",Own Sources,8,2016-17,2017-18 NH/2016-17/7558,Storm Water Drain,Completed,NH-ANNA NAGAR,98,710000,"REPAIR AND IMPROVEMENT TO SWD AT POLICE MANIKAM STREET(CHAINAGE FROM 110M TO 220M ) IN DN-98,U-22,Z-08 ( WARD COUNCILLOR FUND 2016-17 )",Own Sources,8,2016-17,2016-17 NH/2016-17/12917,Buildings,Completed,NH-ANNA NAGAR,99,87000,"SUPPLYING AND FIXING R O PLANT, TAINING TABLES, AND CHEARS FOR AMMA UNAVAGAM @ 2ND AVENUE IN DN 99 UNIT 22 ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/13395,Buildings,Completed,NH-ANNA NAGAR,99,51500,SUPPLYING AND FIXING NAME BOARD FOR O S R LAND IN DN 99 U 21 Z 8,Own Sources,8,2016-17,2017-18 NH/2016-17/18212,Storm Water Drain,Completed,NH-ANNA NAGAR,99,135000,REPAIR WORK TO SWD AT 6TH AVENUE IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2016-17,2016-17 NH/2016-17/18213,Buildings,Completed,NH-ANNA NAGAR,99,36000,SUPPLYING AND FIXING SREET NAME BOARD @ 21ST MAIN ROAD IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2016-17,2016-17 NH/2016-17/18214,Buildings,Completed,NH-ANNA NAGAR,99,30500,CONSTRUCTION OF WALL TO MULTIPURPOSE HALL @ NVN NAGAR 6TH STREET IN DN 99 UNIT 21 ZONE 8,Own Sources,8,2016-17,2016-17 NH/2016-17/19198,Buildings,Completed,NH-ANNA NAGAR,99,990000,"IMPROVEMENT TO FOOTPATH,ROAD,PARKS,SWD AT VARIOUS STREET IN DN-99,U-21,Z-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/19609,Parks,Completed,NH-ANNA NAGAR,99,349000,"ANNUAL MAINTENANCE OF PARK AT 15TH MAIN ROAD PARK (ONE YEAR) IN DIVISION 99,UNIT -21,ZONE-08.(BY EMPLOYED QUALIFIED HORTICULTURIST ONLY)",Own Sources,8,2016-17,2017-18 NH/2016-17/2043,Footpath,Completed,NH-ANNA NAGAR,99,43600,Painting for footpath @ j block 15th street 16th street 17th street 18th street and 19th street in dn 99 unit 22 zone 8,Own Sources,8,2016-17,2016-17 NH/2016-17/2044,Buildings,Completed,NH-ANNA NAGAR,99,122000,"Painting for footpath @ R.B.I park Anna nagar in division-99, Unit-21, Zone-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/2049,Buildings,Completed,NH-ANNA NAGAR,99,140000,"Providing Bin platform @ various street in division-99, Unit-21, Zone-8,",Own Sources,8,2016-17,2016-17 NH/2016-17/4119,Buildings,Completed,NH-ANNA NAGAR,99,50500,"Construction of Inlet chamber to connecting exsiting strom water drain at Ammankoil street ,Thirumular colony in division-99, Unit-21, Zone-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/4130,Storm Water Drain,Completed,NH-ANNA NAGAR,99,48000,"REPAIR WORKS TO SWD AT NVN NAGAR 14TH STREET IN DN - 99, UNIT-21, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/4777,Buildings,Completed,NH-ANNA NAGAR,99,999000,"PROVIDING SS NAME BOARD AT KATHIRAVAN COLONY PARK AND NNMP SHED AND RBI PARK IN DN-99,U-21, ZONE -08.(COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/4784,Buildings,Completed,NH-ANNA NAGAR,99,990000,"PROVIDING AND FIXING OF STREET NAME BOARDS AND SS STEEL LETTER BOARD AND RETRO REFLETIVE SHEETS IN DN - 99, UNIT 21, ZONE - 8. (WARD COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/5158,Buildings,Completed,NH-ANNA NAGAR,99,999000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM (NEHRU NAGAR SLUM) AT 2ND AVENUE THIRUMANGALAM DIVTION-99,UNIT-21,ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/5275,Storm Water Drain,Completed,NH-ANNA NAGAR,99,990000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREETS IN DN-99,UNIT-21,ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/6341,Buildings,Completed,NH-ANNA NAGAR,99,999000,"PROVIDING SS HAND RAIL WORK AT 15TH MAIN ROAD B.P.C PARK IN WARD COUNCILLOR FUND 2016-17 IN DN - 99, UNIT 21, ZONE - 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/6648,Road Cut,Completed,NH-ANNA NAGAR,99,990000,"RESTORATION OF ROAD CUT MADE BY TNEB AT (KATHIRAVAN COLONY AND 17TH MAIN ROAD) DIVISION-99, UNIT-21, ZONE-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/6653,Road Cut,Completed,NH-ANNA NAGAR,99,990000,"RESTORATION OF ROAD CUT MADE BY TNEB AT (14TH MAIN ROAD,PERIYAR STREET AND KAMARAJ STREET) DIVISION-99.",Deposit Works,8,2016-17,2016-17 NH/2016-17/6659,Road Cut,Completed,NH-ANNA NAGAR,99,990000,"RESTORATION OF ROAD CUT MADE BY TNEB AT (12TH MAIN ROAD, AF BLOCK 3RD AND 8TH STREET, Y-BLOCK 6TH STREET,13TH MAIN ROAD,Z-BLOCK 2ND STREET AND Y-BLOCK 3RD STREET) DIVITION-99.",Deposit Works,8,2016-17,2017-18 NH/2016-17/8905,Roads,Completed,NH-ANNA NAGAR,99,999000,"LAYING BITUMINOUS CONCRETE ROAD AT TRIVENI COLONY AROUND THE PARK IN DN-99, UNIT-21, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/9894,Storm Water Drain,Completed,NH-ANNA NAGAR,99,720000,"IMPROVEMENTS TO FOOTPATH,AND SWD AND GROUP BINS IN VARIOUS STREET IN DN-99,UNIT-21,ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/9896,Parks,Completed,NH-ANNA NAGAR,99,269000,"IMPROVEMENTS TO FOOTPATH AND PAINTING WORK TO 13TH MAIN ROAD,H BLOCK 4TH,AND 2ND AVENUE IN DN99,UNIT-21,ZONE-8.",Own Sources,8,2016-17,2016-17 BR/2016-17/13708,Roads,Completed,BR-Bus Route Roads,100,950000,"Repairs to the existing bus shelter,fixing studs & laying of thermoplastic painting and other Improvement works at various bus route roads in Zone - 8",Own Sources,8,2016-17,2019-20 BR/2016-17/17092,Roads,Completed,BR-Bus Route Roads,100,1060000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at Anna Nagar 4th Main Road, Anna Nagar 5th Avenue, Anna Nagar 2nd Avenue,Anna Nagar 4th AvenuE and Ayanavaram Road in Zone 8",Grants,8,2016-17,2017-18 BR/2016-17/17523,Footpath,Completed,BR-Bus Route Roads,100,2180000,Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Anna Nagar 2nd Avenue and Pulla Avenue and other Bus Route Roads in Zone 8,Grants,8,2016-17,2017-18 BR/2016-17/19176,Road Cut,Completed,BR-Bus Route Roads,100,1840000,"Restoration of Roadcut made by TANGEDCO at Nelson Manickam Road from the jn of Sky walk to the jn of Bharath Petrolieum Bunk in Dn-106, Zone-8",Deposit Works,8,2016-17,2017-18 L/2016-17/13406,Electrical,Completed,L-Electrical,100,761000,"Supply & Replacement of 17nos of Kiosk Pillar box at various places in Division-100,101,102,107,105 & 108 at Zone-VIII Area.",Own Sources,8,2016-17,2017-18 L/2016-17/18023,Electrical,Completed,L-Electrical,100,188400,WORK: Supply and Fixing of 2 Core SMC Fuse box 200 nos at various places in Division-100 & 101 Zone-8 area.,Own Sources,8,2016-17,2017-18 NH/2016-17/0615,Buildings,Completed,NH-ANNA NAGAR,100,343000,"PROVIDING PARTITION, BARRICADING, PANDAL, DEFACING OF WALLS,MARKING OF 100M AND 200M M FOR TAMILNADU GENERAL ELECTION 2016 AT D.G. VAISHNAVA COLLEGE, KOLA PERUMAL SCHOOL, KRISHNASAMY COLLEGE, JAIGOPAL GARODIA, CHENNAI PRIMARY SCHOOL (NATHAMUNI STREET & N.S.K NAGAR), JESSIE MOSES SCHOOL IN DN-100, UNIT,22,ZONE.8.(UNDER MAINTENANCE)",Own Sources,8,2016-17,2016-17 NH/2016-17/0617,Buildings,Completed,NH-ANNA NAGAR,100,60000,"IMPROVEMENTS OF TRANSFORMER AT 6th MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-08 (UNDER MAINTENANCE)",Own Sources,8,2016-17,2016-17 NH/2016-17/11352,Buildings,Completed,NH-ANNA NAGAR,100,995000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/1143,Road Cut,Completed,NH-ANNA NAGAR,100,108000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO @ 7th MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-08. (Length=80.00M)",Deposit Works,8,2016-17,2018-19 NH/2016-17/11675,Road Cut,Completed,NH-ANNA NAGAR,100,760000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AA BLOCK (2ND & 4TH) STREET ,AC BLOCK 2ND STREET, AG BLOCK 2ND STREET, Z BLOCK (8TH,9TH,11TH) STREET IN DIVISION-100,UNIT-22, ZONE-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/11679,Road Cut,Completed,NH-ANNA NAGAR,100,698000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AH BLOCK 3RD STREET AND INDHIRA NAGAR SLUM ROAD IN DIVISION-100,UNIT-22, ZONE-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/11682,Storm Water Drain,Completed,NH-ANNA NAGAR,100,997000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/1265,Road Cut,Completed,NH-ANNA NAGAR,100,118000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO @ TAS CHELLAIAH ROAD IN DIVISION-100, UNIT-22, ZONE-08.(Length=92.00M)",Deposit Works,8,2016-17,2018-19 NH/2016-17/1273,Roads,Completed,NH-ANNA NAGAR,100,247000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO @ AJ BLOCK 3rd STREET IN DIVISION-100, UNIT-22, ZONE-08.(Length=195.00M)",Deposit Works,8,2016-17,2018-19 NH/2016-17/1290,Roads,Completed,NH-ANNA NAGAR,100,150000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO @ AJ BLOCK 2nd STREET IN DIVISION-100, UNIT-22, ZONE-08. (Length=120.00M)",Deposit Works,8,2016-17,2018-19 NH/2016-17/1291,Roads,Completed,NH-ANNA NAGAR,100,68000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO @ 10th MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-08.(Length=50.00M)",Deposit Works,8,2016-17,2018-19 NH/2016-17/1293,Roads,Completed,NH-ANNA NAGAR,100,259000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO @ AH BLOCK 2nd STREET IN DIVISION-100, UNIT-22, ZONE-08. (Length=200.00M)",Deposit Works,8,2016-17,2018-19 NH/2016-17/1304,Buildings,Completed,NH-ANNA NAGAR,100,132000,"IMPROVEMENTS OF STROM WATER DRAIN AND ATTENDING CC PATCH WORK IN DIVISION-100, UNIT-22, ZONE-08.(UNDER MAINTENANCE).",Own Sources,8,2016-17,2016-17 NH/2016-17/13870,Buildings,Completed,NH-ANNA NAGAR,100,995000,"IMPROVEMENTS TO STORM WATER DRAIN AT 6TH AVENUE ROAD CROSSING IN DIVISION-100, UNIT-22, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/14216,Buildings,Completed,NH-ANNA NAGAR,100,109000,"REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCES AT 3RD AVENUE,7TH MAIN ROAD, ANNA NAGAR TOWER PARK IN DIVISION-100,UNIT-22, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/14404,Buildings,Completed,NH-ANNA NAGAR,100,350000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT NSK NAGAR IN DIVISION -100, UNIT-22, ZONE-22",Own Sources,8,2016-17,2017-18 NH/2016-17/15836,Parks,Completed,NH-ANNA NAGAR,100,70000,"MAINTENANCE OF DR. VISWESWARAYA TOWER PARK INSIDE ELECTRIC MOTOR AND WATER LINE (LANDSCAPE AREA,TOILET AREA,DRINKING WATER LINE),TOWER CLOCK SERVICES (SIX MONTHS) AT ANNA NAGAR IN DN-100, UNIT- 22, ZONE-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/15842,Parks,Completed,NH-ANNA NAGAR,100,977000,"MAINTENANCE FOR GREENERY AREA OF DR. VISWESWARAYA TOWER PARK (BY EMPLOYING QUALIFIED HORTICULTURIST) FOR A PERIOD OF SIX MONTHS IN DN-100, UNIT- 22, ZONE-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/1616,Electrical,Completed,NH-ANNA NAGAR,100,292000,Improvement and repairs work at GYM building 7th main road in division-100 unit-22 zone-8,Own Sources,8,2016-17,2017-18 NH/2016-17/1618,Buildings,Completed,NH-ANNA NAGAR,100,997000,"IMPROVEMENTS TO STORM WATER DRAIN AT 3RD MAIN ROAD(IN FRONT OF TOWER CLUB MAIN GATE TO CHAINAGE -50M ) IN DIVISION-100, UNIT-22, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/1619,Parks,Completed,NH-ANNA NAGAR,100,219000,"IMPROVEMENTS TO YOGA STAGE AT 14th MAIN ROAD PARK IN DIVISION- 100, UNIT-22, ZONE-08.(UNDER MAINTENANCE)",Own Sources,8,2016-17,2016-17 NH/2016-17/16388,Buildings,Completed,NH-ANNA NAGAR,100,297000,"PROVIDING STREET NAME BOARD AT VARIOUS STREET( AFFECTED BY THE VARDAH CYCLONE) IN DIVISION-100,UNIT-22, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/16407,Storm Water Drain,Completed,NH-ANNA NAGAR,100,860000,"IMPROVEMENTS TO STROM WATER DRAIN AT VARIOUS STREET ( AFFECTED BY THE VARDAH CYCLONE) IN DIVISION-100,UNIT-22,ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/16434,Buildings,Completed,NH-ANNA NAGAR,100,185000,"IMPROVEMENTS TO AMMA UNAVAGAM AT 3RDAVENUE NEAR ANNA HOSPITAL( AFFECTED BY THE VARDAH CYCLONE) IN DN-100,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/16850,Parks,Completed,NH-ANNA NAGAR,100,970000,"IMPROVEMENT TO AD BLOCK PARK COMPOUND WALL(AFFECTED BY THE VARDAH CYCLONE) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/16854,Parks,Completed,NH-ANNA NAGAR,100,2050000,"IMPROVEMENT TO DR. VISWESWARAYA TOWER PARK(AFFECTED BY THE VARDAH CYCLONE) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/16864,Parks,Completed,NH-ANNA NAGAR,100,759000,"IMPROVEMENT TO AL & AE BLOCK PARK AND PLAY GROUND (AFFECTED BY THE VARDAH CYCLONE) IN DIVISION-100, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/17048,Roads,Completed,NH-ANNA NAGAR,100,3670000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 5TH AVENUE(2ND AVENUE TO 5TH MAIN ROAD) IN DIVISION-100,UNIT-22,ZONE-8.( AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/17070,Roads,Completed,NH-ANNA NAGAR,100,952000,"RELAYING OF THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT 8TH MAIN ROAD ( AH-BLOCK 1ST STREET TO AH-BLOCK 3RD STREET) IN DIVISION-100,UNIT-22,ZONE-8.( AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/17733,Footpath,Completed,NH-ANNA NAGAR,100,730000,IMPROVEMENTS TO FOOTPATH AT VARIOUS STREET (AFFECTED BY THE VARDAH CYCLONE) IN DIVISION-100 UNIT-22 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/19607,Parks,Completed,NH-ANNA NAGAR,100,400000,"PROVIDING SECURITY GUARDS TO DR. VISWESWARAIAH TOWER PARK (ONE YEAR) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/19608,Parks,Completed,NH-ANNA NAGAR,100,376000,"PROVIDING SWEEPERS ARRANGEMENTS TO DR. VISWESWARAIAH TOWER PARK (SIX MONTHS) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/19720,Buildings,Completed,NH-ANNA NAGAR,100,284000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND REMOVAL OF DEBRIS AT VARIOUS STREET IN DIVISION -100, UNIT-22, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/4865,Storm Water Drain,Completed,NH-ANNA NAGAR,100,989000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/4871,Storm Water Drain,Completed,NH-ANNA NAGAR,100,155000,"PROVIDING HAND GYM AT TOWER PARK IN DIVISION-100, UNIT-22, ZONE-08.(UNDER MAINTENANCE)",Own Sources,8,2016-17,2016-17 NH/2016-17/4873,Buildings,Completed,NH-ANNA NAGAR,100,473000,"PAINTING FOOTPATH AT VARIOUS ROAD IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/4875,Buildings,Completed,NH-ANNA NAGAR,100,992000,"IMPROVEMENTS TO STORM WATER DRAIN AT 3RD MAIN ROAD (CHAINAGE FROM-50M TO CHAINAGE-100M) IN DIVISION-100,UNIT-22,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/4876,Buildings,Completed,NH-ANNA NAGAR,100,998000,"IMPROVEMENTS TO STORM WATER DRAIN AT 3RD MAIN ROAD (CHAINAGE FROM-100M TO CHAINAGE-150M ) IN DIVISION-100, UNIT-22, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/4877,Buildings,Completed,NH-ANNA NAGAR,100,994000,"IMPROVEMENTS TO STORM WATER DRAIN AT 3RD MAIN ROAD(CHAINAGE FROM-150M TO CHAINAGE-200M ) IN DIVISION-100, UNIT-22, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/4878,Footpath,Completed,NH-ANNA NAGAR,100,996000,"IMPROVEMENTS TO FOOTPATH AND STORM WATER DRAIN AT 3RD MAIN ROAD (CHAINAGE FROM -200M TO CHAINAGE-250M ) IN DIVISION-100, UNIT-22, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/6627,Road Cut,Completed,NH-ANNA NAGAR,100,410000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AJ BLOCK (1st, 2nd & 4th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/6628,Road Cut,Completed,NH-ANNA NAGAR,100,396000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AI BLOCK (1st & 5th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/6629,Road Cut,Completed,NH-ANNA NAGAR,100,472000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AL BLOCK (1st, 2nd, 3rd & 4th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2016-17 NH/2016-17/6630,Road Cut,Completed,NH-ANNA NAGAR,100,560000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AH BLOCK (1st, 2nd, 4th & 5th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/6631,Road Cut,Completed,NH-ANNA NAGAR,100,310000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AE BLOCK ( 2nd, 3rd & 5th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2016-17 NH/2016-17/6632,Road Cut,Completed,NH-ANNA NAGAR,100,298000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AD BLOCK ( 1st, 3rd, 4th & 5th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/6633,Road Cut,Completed,NH-ANNA NAGAR,100,185000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AB BLOCK ( 1st, 2nd, & 4th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2016-17 NH/2016-17/6634,Road Cut,Completed,NH-ANNA NAGAR,100,218000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT 7th MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/6635,Road Cut,Completed,NH-ANNA NAGAR,100,910000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT AD BLOCK (,3RD,4TH,5HT) ,AJ BLOCK (1ST,2ND,4TH) , AL BLOCK (1ST,2ND,3RD,4TH) STREET IN DIVISION-100,UNIT-22, ZONE-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/6636,Road Cut,Completed,NH-ANNA NAGAR,100,318000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT N.S.K NAGAR (13th, 14th, 15th & 16th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2016-17 NH/2016-17/6724,Road Cut,Completed,NH-ANNA NAGAR,100,994000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT N.S.K NAGAR (1st, 2nd, 3rd, 4th, 5th, 6th, 7th, 8th, 9th, 10th, 11th & 12th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2016-17 NH/2016-17/6729,Road Cut,Completed,NH-ANNA NAGAR,100,397000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT N.S.K NAGAR (19th, 20th, 21st, 22nd, 23rd & 24th ) STREET IN DIVISION-100, UNIT-22, ZONE-08.",Deposit Works,8,2016-17,2016-17 NH/2016-17/7900,Playfields,Completed,NH-ANNA NAGAR,100,948000,"IMPROVEMENT TO PARK AND COMPOND WALL AT AE BLOCK SHANTHI COLONY IN DN-100, U-22, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/8123,Playfields,Completed,NH-ANNA NAGAR,100,998000,"IMPROVEMENTS OF AL BLOCK PLAY GROUND IN DIVISION-100, UNIT-22, ZONE-08.(COUNCILOR FUND 2016-2017)",Own Sources,8,2016-17,2017-18 NH/2016-17/8124,Playfields,Completed,NH-ANNA NAGAR,100,994000,"IMPROVEMENTS OF AE BLOCK PLAY GROUND (WESTERN SIDE) IN DIVISION-100, UNIT-22, ZONE-08.(COUNCILOR FUND 2016-2017)",Own Sources,8,2016-17,2017-18 NH/2016-17/8412,Buildings,Completed,NH-ANNA NAGAR,100,997000,"IMPROVEMENTS OF AD BLOCK PARK IN DIVISION-100, UNIT-22, ZONE-08.(WARD COUNCILOR FUND 2016-2017)",Own Sources,8,2016-17,2016-17 NH/2016-17/8889,Buildings,Completed,NH-ANNA NAGAR,100,995000,"PROVIDING CONCRETE GARBAGE BIN PLATFORM AT VARIOUS STREET AND FENCING WORK AT 3RD AVENUE NEAR BREWERY ROAD IN DIVISION-100, UNIT-22,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/8927,Parks,Completed,NH-ANNA NAGAR,100,994000,"PROVIDING ACUPUNCTURE PATHWAY USING PEBBLE STONE AND HAND GYM IN SOUTH SIDE OF DR.VISWESVARAIYA TOWER PARK IN DN-100,U-22,Z-8",Own Sources,8,2016-17,2017-18 BR/2016-17/13648,Roads,Completed,BR-Bus Route Roads,101,2880000,"Proposed Construction of Granite kerb Centre Median and fixing of stainless steel grill at Anna Nagar 3rd avenue from the jn of annanagar 2nd avenue to the jn of Shanthi colony in Dn- 101, Zone- 8",Deposit Works,8,2016-17,2017-18 BR/2016-17/15116,Roads,Completed,BR-Bus Route Roads,101,2700000,"Proposed Construction of 4 Nos Traffic Island around Annanagar rountana at the jn of 3rd Avenue x 2nd Avenue in Dn - 101, Zone-8",Deposit Works,8,2016-17,2018-19 BR/2016-17/15504,Roads,Completed,BR-Bus Route Roads,101,2870000,"Proposed construction of Annanagar rountana at the jn of 3rd Avenue X 2nd Anenue in Dn 101, Zone -8",Deposit Works,8,2016-17,2018-19 NH/2016-17/0507,Buildings,Completed,NH-ANNA NAGAR,101,2670000,"LAYING OF CEMENT CONCRETE ROAD INSIDE VELANGADU BURIAL GROUND ( SOUTH SIDE) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/0512,Buildings,Completed,NH-ANNA NAGAR,101,2650000,"LAYING OF CEMENT CONCRETE ROAD INSIDE VELANGADU BURIAL GROUND (NORTH SIDE) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/10391,Roads,Completed,NH-ANNA NAGAR,101,500000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT F-BLOCK 5TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/10459,Roads,Completed,NH-ANNA NAGAR,101,384000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT CLUB ROAD WEST IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/10460,Roads,Completed,NH-ANNA NAGAR,101,1036700,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT K-BLOCK 16TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/10461,Roads,Completed,NH-ANNA NAGAR,101,1100000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT BREWERY ROAD IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/13598,Buildings,Completed,NH-ANNA NAGAR,101,996000,"CONSTRUCTION OF TOILET BLOCK AT CREASENT GROUND IN DN-101,U-22,Z-08(swachh bharat scheme)",Own Sources,8,2016-17,2017-18 NH/2016-17/14005,Buildings,Completed,NH-ANNA NAGAR,101,100000,"REPAIR AND IMPROVEMENT WORK IN PUBLC CONVENIENCE AT ANNA NAGAR 3RD AVENUE AND P.P GARDEN 6TH STREET IN DN-101,,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/1528,Roads,Completed,NH-ANNA NAGAR,101,980000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT P.P THOTTAM 2ND STREET IN DN-101,U-22,Z-08",Deposit Works,8,2016-17,2017-18 NH/2016-17/1530,Road Cut,Completed,NH-ANNA NAGAR,101,998000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT P.P THOTTAM 3RD STREET IN DN-101,U-22,Z-08",Deposit Works,8,2016-17,2017-18 NH/2016-17/1553,Roads,Completed,NH-ANNA NAGAR,101,448000,"ATTENDING PATCH WORK AT F-BLOCK 9TH STREET AND 5TH MAIN ROAD (FROM 3RD AVENUE TO 2ND MAIN ROAD) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/1556,Roads,Completed,NH-ANNA NAGAR,101,338000,"ATTENDING PATCH WORK AT J-BLOCK 7TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/16701,Storm Water Drain,Completed,NH-ANNA NAGAR,101,845000,"IMPROVEMENT TO SWD AT VARIOUS STREET IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/16704,Buildings,Completed,NH-ANNA NAGAR,101,810000,"IMPROVEMENT TO COMPOUND WALL AT CPS PRIMARY SCHOOL BHARATHIPURAM IN DN-101 U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/16852,Parks,Completed,NH-ANNA NAGAR,101,325000,"IMPROVEMENT TO INDOOR STADIUM AT SHENOY NAGAR 2ND MAIN ROAD IN DN-101,U-22,Z-08(AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/16860,Playfields,Completed,NH-ANNA NAGAR,101,1980000,"IMPROVEMENT TO CREASENT GROUND IN DN-101,U-22,Z-08(AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2018-19 NH/2016-17/16861,Buildings,Completed,NH-ANNA NAGAR,101,195000,"IMPROVEMENT TO AMMA ARANGAM IN DN-101,U-22,Z-08(AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/16862,Buildings,Completed,NH-ANNA NAGAR,101,225000,"IMPROVEMENT TO DISPENSARY AT BHARATHIPURAM 4TH STREET IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/16863,Parks,Completed,NH-ANNA NAGAR,101,967000,"IMPROVEMENT TO C-BLOCK PARK, BOGANVILLA PARK, SHENOY NAGAR 2ND MAIN ROAD PARK IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/17397,Roads,Completed,NH-ANNA NAGAR,101,700000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT K-BLOCK 14TH STREET IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/17405,Roads,Completed,NH-ANNA NAGAR,101,590000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT K-BLOCK 15TH STREET IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/17409,Roads,Completed,NH-ANNA NAGAR,101,200000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT N-BLOCK 19TH STREET IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/17412,Roads,Completed,NH-ANNA NAGAR,101,200000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT N-BLOCK 20TH STREET IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/17734,Footpath,Completed,NH-ANNA NAGAR,101,299000,"IMPROVEMENT TO FOOTPATH AT VARIOUS STREET IN DN-101,U-22,Z-08 (AFFECTED BY THE VARDAH CYCLONE)",Own Sources,8,2016-17,2017-18 NH/2016-17/18182,Roads,Completed,NH-ANNA NAGAR,101,400000,"REPAIR AND IMPROVEMENT TO FOOTPATH AT F-BLOCK 3RD,4TH,5TH,6TH,8TH AND 9TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2018-19 NH/2016-17/18202,Buildings,Completed,NH-ANNA NAGAR,101,315000,ADDITIONAL CONSTRUCTION OF REST ROOM AT DIVISION OFFICE IN DIVISION-101 UNIT-22 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/18203,Buildings,Completed,NH-ANNA NAGAR,101,190000,PAINTING WORKS TO DIVISION OFFICE IN DIVISION-101 UNIT-22 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/18205,Buildings,Completed,NH-ANNA NAGAR,101,123000,CONSTRUCTION OF PUMP ROOM AND REPAIRS WORKS TO AMMA ARRANGAM IN DIV-101 UNIT-22 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/18262,Storm Water Drain,Completed,NH-ANNA NAGAR,101,172000,"REPAIR AND IMPROVEMENT TO SWD AT E-BLOCK 1ST STREET & ANNAI SATHYA NAGAR IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/18263,Roads,Completed,NH-ANNA NAGAR,101,75000,"IMPROVEMENT WORK AT BOGANVILLA PARK IN DN-101-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/18264,Roads,Completed,NH-ANNA NAGAR,101,140000,"REPAIR AND IMPROVEMENT TO AMMA UNAVAGAM AT 2ND MAIN ROAD & KAMARAJAR STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/18624,Buildings,Completed,NH-ANNA NAGAR,101,10600,"PROVIDING NAME BOARD IN DISPENSARY AT BHARATHIPURAM IN DIV-101, UNIT-22, ZONE-8",Own Sources,8,2016-17,2018-19 NH/2016-17/1937,Storm Water Drain,Completed,NH-ANNA NAGAR,101,400000,"CONSTRUCTION OF SWD AT MM COLONY( REACH FROM 0M TO 25M) IN DN-101, U-22,Z-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/1941,Storm Water Drain,Completed,NH-ANNA NAGAR,101,400000,"CONSTRUCTION OF SWD AT MM COLONY( REACH FROM 25M TO 50M) IN DN-101, U-22,Z-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/2207,Storm Water Drain,Completed,NH-ANNA NAGAR,101,400000,"DESILTING AND IMPROVEMENT TO SWD AT M-BLOCK 8th , 9th & 10th STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/2223,Storm Water Drain,Completed,NH-ANNA NAGAR,101,255000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT P.P THOTTAM 5TH STREET IN DN-101,U-22,Z-08",Deposit Works,8,2016-17,2017-18 NH/2016-17/2224,Storm Water Drain,Completed,NH-ANNA NAGAR,101,990000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT P.P THOTTAM 6TH STREET IN DN-101,U-22,Z-08",Deposit Works,8,2016-17,2017-18 NH/2016-17/2227,Buildings,Completed,NH-ANNA NAGAR,101,998000,"DISMALTING AND RE-CONSTRUCTION OF SWD AT VELANGADU CREMANTORIUM ( NEAR BIO-METHANATION PLANT CHAINAGE 0M TO 35M) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/2315,Storm Water Drain,Completed,NH-ANNA NAGAR,101,400000,"CONSTRUCTION OF SWD AT BHARATHIPURAM MAIN ROAD IN DN-101, U-22,Z-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/2388,Storm Water Drain,Completed,NH-ANNA NAGAR,101,400000,"CONSTRUCTION OF SWD AT MM COLONY( REACH FROM 50M TO 75M) IN DN-101, U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/3315,Roads,Completed,NH-ANNA NAGAR,101,996000,"DISMALTING AND RE-CONSTRUCTION OF SWD AT VELANGADU CREMANTORIUM ( NEAR BIO-METHANATION PLANT CHAINAGE 35M TO 70M) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/3531,Roads,Completed,NH-ANNA NAGAR,101,930000,"RELAYING THE ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT O BLOCK 32ND,33RD AND 35TH STREET IN DN-101 , U-22 ,Z-08 ( WARD COUNCILLOR FUND 2016-17 )",Own Sources,8,2016-17,2017-18 NH/2016-17/3566,Roads,Completed,NH-ANNA NAGAR,101,600000,"RELAYING THE ROAD WITH CAMBER CORRECTION BY PAVER FINISHER AT O BLOCK 36TH STREET IN DN-101 , U-22 ,Z-08 ( WARD COUNCILAR FUND 2016-17 )",Own Sources,8,2016-17,2017-18 NH/2016-17/4648,Storm Water Drain,Completed,NH-ANNA NAGAR,101,998000,"DESILTING OF STORM WATER DRAIN AT ANNA NAGAR 3RD AVENUE, ANNA NAGAR 2ND AVENUE NORTH& SOUTH SIDE , ANNA NAGAR 6TH AVENUE, F-BLOCK 1ST STREET , F-BLOCK 4TH STREET, E-BLOCK 1A STREET AND VELANGADU BURIAL GROUND IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/4652,Storm Water Drain,Completed,NH-ANNA NAGAR,101,400000,"PROVIDING RAIN WATER HARVESTING WELL AT AMMA ARANGAM IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/5001,Roads,Completed,NH-ANNA NAGAR,101,500000,"ATTENDING PATCH WORK AT ANNA NAGAR 2ND MAIN ROAD IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/5006,Roads,Completed,NH-ANNA NAGAR,101,465000,"ATTENDING PATCH WORK AT ANNA NAGAR 2ND MAIN ROAD IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/5736,Roads,Completed,NH-ANNA NAGAR,101,454000,"ATTENDING PATCH WORK AT ANNA NAGAR 1ST MAIN ROADT IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/5737,Parks,Completed,NH-ANNA NAGAR,101,997000,"DISMALTING AND RE-CONSTRUCTION OF SWD AT VELANGADU CREMANTORIUM ( NEAR BIO-METHANATION PLANT CHAINAGE 70M TO 105M) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/5740,Parks,Completed,NH-ANNA NAGAR,101,996000,"DISMALTING AND RE-CONSTRUCTION OF SWD AT VELANGADU CREMANTORIUM ( NEAR BIO-METHANATION PLANT CHAINAGE 105M TO 140M) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/5744,Storm Water Drain,Completed,NH-ANNA NAGAR,101,449000,"ATTENDING PATCH WORK AT 5TH MAIN ROAD WEST SIDE ( FROM 3RD AVENUE TO 3RD MAIN ROAD) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/6862,Buildings,Completed,NH-ANNA NAGAR,101,400000,"CUTTING HEAVY JUNGLE AND SECTIONING THE ENCROUCHMENT SITE AND PROVIDING RCC POST WITH BARBED WIRE FENCHING AT REAR SIDE OF AMMA ARANGAM IN DN-101,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/8160,Storm Water Drain,Completed,NH-ANNA NAGAR,101,998000,"DISMALTING AND RE-CONSTRUCTION OF SWD FROM ANNA SATHYA NAGAR 10TH STREET TO VELANGADU BIO-METHANATION PLANT IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/8219,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"DISMALTING AND RE-CONSTRUCTION OF SWD FROM OTTER NALLA TO ANNA SATHYA NAGAR 10TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/8470,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"REPAIR AND IMPROVEMENT TO SWD AT ANNA NAGAR 6TH AVENUE & INTERCONNECTION AT C-BLOCK 7TH STREET N DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/8512,Storm Water Drain,Completed,NH-ANNA NAGAR,101,997000,"DESILTING OF OTTERI NALLA CANAL ( FROM N-BLOCK 23RD STREET TO ANNA NAGAR 1ST AVENUE ) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/8514,Storm Water Drain,Completed,NH-ANNA NAGAR,101,996000,"DESILTING OF OTTERI NALLA CANAL ( FROM P-BLOCK 21ST STREET TO N-BLOCK 23RD STREET ) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/8516,Buildings,Completed,NH-ANNA NAGAR,101,997000,"DESILTING OF OTTERI NALLA CANAL ( FROM GARDEN VIEW COLONY TO P-BLOCK 21ST STREET ) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9291,Roads,Completed,NH-ANNA NAGAR,101,500000,"RELAYING OF ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT J-BLOCK 7TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9292,Roads,Completed,NH-ANNA NAGAR,101,1246000,"RELAYING OF ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT N-BLOCK 22ND STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9293,Roads,Completed,NH-ANNA NAGAR,101,368000,"RELAYING OF ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT N-BLOCK 23RD STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9295,Roads,Completed,NH-ANNA NAGAR,101,310000,"RELAYING OF ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT N-BLOCK 18TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9296,Roads,Completed,NH-ANNA NAGAR,101,6920500,"RELAYING OF ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT ANNA NAGAR 2ND MAIN ROAD IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9299,Roads,Completed,NH-ANNA NAGAR,101,1093000,"RELAYING OF ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT SHENOY NAGAR 6TH CROSS STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9301,Buildings,Completed,NH-ANNA NAGAR,101,580000,"IMPROVEMENT WORK AT AMMA ARANGAM IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2018-19 NH/2016-17/9323,Storm Water Drain,Completed,NH-ANNA NAGAR,101,830000,"FORMING OF SWD AT ANNAI SATHYA NAGAR 3RD STREET IN DN-101,U-22,Z-08 ( WARD COUNCILOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/9329,Buildings,Completed,NH-ANNA NAGAR,101,670000,"REPAIR AND IMPROVEMENT WORK AT CHENNAI PRIMARY SCHOOL & KITCHEN SHED AT BHARATHIPURAM IN DN-101, U-22 , Z-08 (WARD COUNCILOR FUND 2016-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/9488,Roads,Completed,NH-ANNA NAGAR,101,727200,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT F-BLOCK 3RD STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9489,Roads,Completed,NH-ANNA NAGAR,101,763000,"RELAYING THE ROAD WITH LEVEL AND CAMBER CORRECTION BY PAVER FINISHER AT F-BLOCK 4TH STREET IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9671,Roads,Completed,NH-ANNA NAGAR,101,997000,"DISMALTING AND RE-CONSTRUCTION OF SWD AT VELANGADU CREMANTORIUM ( NEAR BIO-METHANATION PLANT CHAINAGE 140M TO 175M) IN DN-101,U-22,Z-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9892,Buildings,Completed,NH-ANNA NAGAR,101,970000,"CONSTRUCTION OF COMPOUND WALL AT VELANGADU CREMANTORIUM IN DN-101,U-22,Z-8",Own Sources,8,2016-17,2017-18 BR/2016-17/19253,Roads,Completed,BR-Bus Route Roads,102,163000,Providing and laying of Ramp for existing bus shelters at various Bus Route Roads in zone - 8,Own Sources,8,2016-17,2018-19 BR/2016-17/2056,Footpath,Completed,BR-Bus Route Roads,102,998000,"Improvements to Footpath at Kilpauk Garden Road from the jn of Pulla Avenue to Cemetry in Dn-102, Zone-8",Own Sources,8,2016-17,2016-17 BR/2016-17/2058,Footpath,Completed,BR-Bus Route Roads,102,997000,"Improvements to Footpath at Kilpauk Garden Road from the jn of Cemetry bus stop to the jn of New Avadi Road in Dn-102, Zone-8",Own Sources,8,2016-17,2016-17 BR/2016-17/4412,Roads,Completed,BR-Bus Route Roads,102,986000,Supplying and fixing of Front facia & Back drop in the stainless steel Bus shelter at various bus route roads in zone - 8,Own Sources,8,2016-17,2017-18 NH/2016-17/0612,Road Cut,Completed,NH-ANNA NAGAR,102,998000,"Restoration of Road cut made by TANGEDCO at East Park Road, First cross street(east) Ayyavoo 1st lane, Nathamuni Street, Gajapathy Street, 3rd Cross Street (east), Ayyavoo Street, Kanniamman Koil Street in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/10285,Roads,Completed,NH-ANNA NAGAR,102,3323000,"Strengthening and Relaying of the Road at First Main Road(east) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10295,Roads,Completed,NH-ANNA NAGAR,102,1080900,"Strengthening and Relaying of the Road at First Cross Street(east) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/10297,Roads,Completed,NH-ANNA NAGAR,102,788200,"Strengthening and Relaying of the Road at Second Cross Street (east) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/10300,Roads,Completed,NH-ANNA NAGAR,102,1067700,"Strengthening and Relaying of the Road at First Cross Street (west) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10303,Roads,Completed,NH-ANNA NAGAR,102,881700,"Strengthening and Relaying of the Road at Second Cross Street (west) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10306,Roads,Completed,NH-ANNA NAGAR,102,873200,"Strengthening and Relaying of the Road at X OWNER Plots 5th street(D block RV Nagar 2nd Street) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10307,Roads,Completed,NH-ANNA NAGAR,102,1407400,"Strengthening and Relaying of the Road at Mahatma Gandhi Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10309,Roads,Completed,NH-ANNA NAGAR,102,629400,"Strengthening and Relaying of the Road at VOC Colony Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10315,Roads,Completed,NH-ANNA NAGAR,102,2770200,"Strengthening and Relaying of the Road after cold miling and camber correction at RV Nagar Main Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10316,Roads,Completed,NH-ANNA NAGAR,102,643600,"Strengthening and Relaying of the Road at K.G.Colony 1st Cross Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10319,Roads,Completed,NH-ANNA NAGAR,102,1224800,"Strengthening and Relaying of the Road at New Mandapam Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10320,Roads,Completed,NH-ANNA NAGAR,102,555700,"Strengthening and Relaying of the Road at Mandapam Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10324,Roads,Completed,NH-ANNA NAGAR,102,450800,"Strengthening and Relaying of the Road at Gujji 1st lane in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10325,Roads,Completed,NH-ANNA NAGAR,102,792700,"Strengthening and Relaying of the Road at Gujji 2nd lane in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10328,Roads,Completed,NH-ANNA NAGAR,102,586900,"Strengthening and Relaying of the Road at Jothiammal Nagar Main Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10331,Roads,Completed,NH-ANNA NAGAR,102,4667500,"Strengthening and Relaying of the Road after cold milling and camber correction at TP Chathiram Main Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10333,Roads,Completed,NH-ANNA NAGAR,102,878900,"Strengthening and Relaying of the Road at Thiruveethiamman Koil Main Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10336,Roads,Completed,NH-ANNA NAGAR,102,235400,"Strengthening and Relaying of the Road at Playground 3rd Cross Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10338,Roads,Completed,NH-ANNA NAGAR,102,522700,"Strengthening and Relaying of the Road at Arumugam Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10342,Roads,Completed,NH-ANNA NAGAR,102,382800,"Strengthening and Relaying of the Road at Sengunthar Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10345,Roads,Completed,NH-ANNA NAGAR,102,889500,"Strengthening and Relaying of the Road at L Block 17th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10350,Roads,Completed,NH-ANNA NAGAR,102,2995800,"Strengthening and Relaying of the Road at Ayyavoo Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10354,Roads,Completed,NH-ANNA NAGAR,102,124800,"Strengthening and Relaying of the Road at Ayyavoo 2nd Lane in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10359,Roads,Completed,NH-ANNA NAGAR,102,396500,"Strengthening and Relaying of the Road at L Block 18th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10366,Roads,Completed,NH-ANNA NAGAR,102,365400,"Strengthening and Relaying of the Road at L Block 24th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10367,Roads,Completed,NH-ANNA NAGAR,102,396500,"Strengthening and Relaying of the Road at L Block 19th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10371,Roads,Completed,NH-ANNA NAGAR,102,281800,"Strengthening and Relaying of the Road at L Block 20th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10374,Roads,Completed,NH-ANNA NAGAR,102,83600,"Strengthening and Relaying of the Road at L Block 25th Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10383,Roads,Completed,NH-ANNA NAGAR,102,151300,"Strengthening and Relaying of the Road at D Block 8th Street(part) (From RV Nagar Main Road) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/10933,Storm Water Drain,Completed,NH-ANNA NAGAR,102,990000,"Desilting of Otteri Nullah Canal(from New Avadi Road to Pallliarasan Street) using float mounted machineries in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10936,Storm Water Drain,Completed,NH-ANNA NAGAR,102,995000,"Desilting of Otteri Nullah Canal(from Pallliarasan Street to R.V.Nagar 6th Street) using float mounted machineries in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10938,Storm Water Drain,Completed,NH-ANNA NAGAR,102,996000,"Desilting of Otteri Nullah Canal(from R.V.Nagar 6th Street to VOC Nagar Main Road) using float mounted machineries in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/10940,Storm Water Drain,Completed,NH-ANNA NAGAR,102,997000,"Desilting of Otteri Nullah Canal(from VOC Nagar Main Road to First Avenue Road) using float mounted machineries in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/11601,Buildings,Completed,NH-ANNA NAGAR,102,72000,"Repairs to damaged floor at Community hall at Gajalakshmi colony in Dn-102, Unit-23, Zone-08",Own Sources,8,2016-17,2017-18 NH/2016-17/11684,Buildings,Completed,NH-ANNA NAGAR,102,288000,"Improvements to CPS at Manjakollai Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/11685,Buildings,Completed,NH-ANNA NAGAR,102,348000,"Providing aluminium partition and Toilet Facilities for CAO / RDC at Zonal office 8 (second floor) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/11911,Storm Water Drain,Completed,NH-ANNA NAGAR,102,895000,"Repairs to SWD and Improvement to footpath at L Block 17th street, 21th street and 23rd street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/13114,Roads,Completed,NH-ANNA NAGAR,102,998000,"Restoration of Road cut made by TANGEDCO at TP Chathiram Main Road in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/13115,Road Cut,Completed,NH-ANNA NAGAR,102,980000,"Restoration of Road cut made by TANGEDCO at VOC Colony Road, Arumugam Street, D Block 5th Street, L block 18th Street in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/13116,Road Cut,Completed,NH-ANNA NAGAR,102,875000,"Restoration of Road cut made by TANGEDCO at VOC Nagar Main Road and VOC Nagar 4th Street in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/13117,Road Cut,Completed,NH-ANNA NAGAR,102,975000,"Restoration of Roadcut made by TANGEDCO at VOC New Colony and Nehru Street in Dn-102, Unit-23, Zone-08.",Deposit Works,8,2016-17,2017-18 NH/2016-17/13421,Parks,Completed,NH-ANNA NAGAR,102,266000,"Maintenance of Park at Skating Park, Pulla Avenue in Dn-102, Unit-23, Zone-08 for six months.",Own Sources,8,2016-17,2018-19 NH/2016-17/13852,Storm Water Drain,Completed,NH-ANNA NAGAR,102,993000,"Improvements to Storm water drain of size 1.20m x 1.50m at Kilpauk Garden Road (South side) from junction of Dharmaraja koil street Ch 80m to 160m) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/13854,Storm Water Drain,Completed,NH-ANNA NAGAR,102,995000,"Improvements to Storm water drain of size 1.20m x 1.50m at Kilpauk Garden Road (South side) from junction of Dharmaraja koil street Ch0m to 80m) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14170,Buildings,Completed,NH-ANNA NAGAR,102,87000,"Repairs to PC at Jothiammal Nagar, Gujji Street, Gandhi road and Thiruveethiammal Koil Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14555,Buildings,Completed,NH-ANNA NAGAR,102,128000,"Improvements to Chennai Primary School at Tamizhar Nagar in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14560,Buildings,Completed,NH-ANNA NAGAR,102,86500,"Improvements to Chennai Middle School, Aminijikarai at EVR Salai in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14573,Buildings,Completed,NH-ANNA NAGAR,102,263000,"Improvements to Chennai Girls Higher Secondary School at Pulla Avenue in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14774,Buildings,Completed,NH-ANNA NAGAR,102,398000,"Repairs and Improvement to the old dispensary at V.S.puram 1st Street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14775,Buildings,Completed,NH-ANNA NAGAR,102,299000,"Improvements to Compost yard at Cemetry Burial Ground in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14776,Buildings,Completed,NH-ANNA NAGAR,102,395000,"Improvements to Care taker Room at Cemetry Burial Ground in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/15471,Buildings,Completed,NH-ANNA NAGAR,102,60000,"REPAIRS TO CHENNAI PRIMARY SCHOOL AT MANJAKOLLAI STREET IN DN-102,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/15663,Buildings,Completed,NH-ANNA NAGAR,102,160000,"Repairs to wooden basket ball court in JJ indoor stadium at Playground street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/15665,Buildings,Completed,NH-ANNA NAGAR,102,90000,"Providing Name board at EOC shenoy nagar hospital at Pulla Avenue Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/16274,Buildings,Completed,NH-ANNA NAGAR,102,133000,"Repairs and Improvements to NNMP Shed at New Mandapam Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/16288,Buildings,Completed,NH-ANNA NAGAR,102,118000,"Repairs and Improvements to NNMP Shed at Telugu lane in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/16802,Roads,Completed,NH-ANNA NAGAR,102,335000,"Supplying and fixing Single Arrow Name board at various street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/16813,Parks,Completed,NH-ANNA NAGAR,102,1125000,"Repairs to damaged compound wall, handrail and play apparatus(due to varadha cyclone) at Skating park and g block park in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/16830,Parks,Completed,NH-ANNA NAGAR,102,230000,"Repairs to damaged compound wall and play apparatus(due to varadha cyclone) at L block Children playground in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/16834,Buildings,Completed,NH-ANNA NAGAR,102,280000,"Repairs to damaged compound wall and gate (due to varadha cyclone) in JJ Stadium at Big street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/16844,Buildings,Completed,NH-ANNA NAGAR,102,112000,"Repairs to damaged compound wall, sheet and Ro plant at Zonal office 8 building(due to varadha cyclone) at Pulla avenue road in Dn-102, Unit-23, Zone-08",Own Sources,8,2016-17,2018-19 NH/2016-17/18895,Playfields,Completed,NH-ANNA NAGAR,102,995000,"Supplying and fixing of Gym Apparatus to the existing Gym at First Cross Street(east)(under MP Central Development Fund) in Dn-102, Unit-23, Zone-08.",MPLADS,8,2016-17,2018-19 NH/2016-17/5251,Storm Water Drain,Completed,NH-ANNA NAGAR,102,990000,"Desilting of Storm Water Drain at Various street in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/6510,Footpath,Completed,NH-ANNA NAGAR,102,999500,"Improvements to the footpath at First Cross Street (west) and Second cross street(west) (under ward Councillor Development fund 2016-17) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/6517,Footpath,Completed,NH-ANNA NAGAR,102,999500,"Improvements to the footpath at Central Street(North side) (under ward Councillor Development fund 2016-17) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/6523,Footpath,Completed,NH-ANNA NAGAR,102,997000,"Improvements to the footpath at Central Street(South side) (under ward Councillor Development fund 2016-17) in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/7572,Buildings,Completed,NH-ANNA NAGAR,102,105000,"Supplying and fixing of E-seva Name Board at Zonal Office 8 and Division office 102 in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/9180,Roads,Completed,NH-ANNA NAGAR,102,2876600,"Strengthening and Relaying of the Road at East Club Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2016-17,2017-18 BR/2016-17/17086,Roads,Completed,BR-Bus Route Roads,103,1050000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at MTH Road, Mayor Ramanathan Salai and Kilpauk Garden Road in Zone 8",Grants,8,2016-17,2017-18 BR/2016-17/17522,Footpath,Completed,BR-Bus Route Roads,103,2440000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Harleys Road,Halls Road, Anna nagar 6th Avenue, New Avadi Road and Anna Nagar 1st Avenue in Zone 8",Grants,8,2016-17,2017-18 BR/2016-17/18787,Roads,Completed,BR-Bus Route Roads,103,198000,Providing and laying of ramp for existing bus shelters at various Bus Route Roads in zone - 8,Own Sources,8,2016-17,2018-19 BR/2016-17/9719,Roads,Completed,BR-Bus Route Roads,103,7000000,"Strengthening and relaying the road with DBM & CBC after cold milling by Paver finisher using plastic waste along with traffic improvement works at Millers Road in Dn - 103, Zone - 8",Grants,8,2016-17,2017-18 NH/2016-17/0620,Buildings,Completed,NH-ANNA NAGAR,103,424000,"PROVIDING PARTITION, BARRICADING, PANDAL, DEFACING OF WALLS, MARKING OF 100M AND 200M FOR TAMIL NADU GENERAL ELECTION 2016 AT ST.GEORGE SCHOOL, PACHIYAPPAN COLLEGE, RESERVE BANK QUARTER, T.E.L.C.SCHOOL,NIGHT SHELTER, C.H.S.SCHOOL,MARY IMMACULATE SCHOOL AND BAIN SCHOOL IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/0832,Buildings,Completed,NH-ANNA NAGAR,103,265000,"IMPROVEMENTS TO RAMP TO CPS AND CHS SCHOOL IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/0834,Buildings,Completed,NH-ANNA NAGAR,103,29000,"REPAIRS TO STORM WATER DRAIN AT EVR SALAI IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/0837,Buildings,Completed,NH-ANNA NAGAR,103,260000,"IMPROVEMENTS AND REPAIRS TO THE ELECTRICAL WORKS AND WATER SUPPLY ARRANGEMENTS AT DIVISION OFFICE, DISPENSARY, AMMA UNAVAGAM, LAKSHMI STREET P.C, T.P.CHATHIRAM 24TH CROSS STREET P.C AND GYM BUILDING IN DN-103.U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/10370,Roads,Completed,NH-ANNA NAGAR,103,383300,"RELAYING THE ROAD WITH BCCMP 30MM THICK BY PAVER FINISHER AT VENKATAPATHY STREET IN DN-103, U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/10375,Roads,Completed,NH-ANNA NAGAR,103,284200,"RELAYING THE ROAD WITH BCCMP 30MM THICK BY PAVER FINISHER AT KILPAUK GARDEN 2ND STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/10378,Roads,Completed,NH-ANNA NAGAR,103,340500,"RELAYING THE ROAD WITH BCCMP 30MM THICK BY PAVER FINISHER AT DAMODARAN STREET IN DN-103, U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/1058,Buildings,Completed,NH-ANNA NAGAR,103,362000,"IMPROVEMENTS TO TOILET BLOCK INSIDE CPS AT THIYAGAPPA STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/11782,Storm Water Drain,Completed,NH-ANNA NAGAR,103,296000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING SUMP AND PIPE LINES AT AMMA UNAVAGAM, HALLS ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/11851,Storm Water Drain,Completed,NH-ANNA NAGAR,103,373000,"CONSTRUCTION OF STORM WATER DRAIN AT PURASAIWALKAM HIGH ROAD (ROAD CROSS PORTION) FORM JN OF BRICKLINE ROAD TO CH.7.00m IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/11853,Buildings,Completed,NH-ANNA NAGAR,103,373000,"CONSTRUCTION OF STORM WATER DRAIN AT PURASAIWALKAM HIGH ROAD (ROAD CROSS PORTION) CH-7.01M TO CH-14.00M IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/11856,Storm Water Drain,Completed,NH-ANNA NAGAR,103,373000,"CONSTRUCTION OF STORM WATER DRAIN AT PURASAIWALKAM HIGH ROAD (ROAD CROSS PORTION) CH-14.01M TO CH-21.00M IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/11858,Storm Water Drain,Completed,NH-ANNA NAGAR,103,373000,"CONSTRUCTION OF STORM WATER DRAIN AT PURASAIWALKAM HIGH ROAD (ROAD CROSS PORTION) CH-21.01M TO CH-28.00M IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/11861,Storm Water Drain,Completed,NH-ANNA NAGAR,103,373000,"CONSTRUCTION OF STORM WATER DRAIN AT PURASAIWALKAM HIGH ROAD (ROAD CROSS PORTION) CH-28.01M TO JN OF MILLERS ROAD (OPP.BSNL OFFICE) IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/14214,Buildings,Completed,NH-ANNA NAGAR,103,351000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING PUBLIC CONVENIENCE AT ORMES ROAD,KUMMALAMMAN STREET, TP CHATHIRAM 24TH STREET, VALLIAMAL STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/14371,Buildings,Completed,NH-ANNA NAGAR,103,52000,"REPAIRS TO THE LEAKY ROOF AT CHENNAI MIDDLE SCHOOL AT THIYAGAPPA STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/15832,Storm Water Drain,Completed,NH-ANNA NAGAR,103,480000,"REPAIRS TO THE EXISTING SWD AT KELLYS ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/15833,Buildings,Completed,NH-ANNA NAGAR,103,164000,"REPAIRS TO THE ORNAMENTAL SHEET AND ROOFING AT AMMA UNAVAGAM HALLS ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/15986,Buildings,Completed,NH-ANNA NAGAR,103,39400,"IMPROVEMENTS AND REPAIR WORKS TO AMMA UNAVAGAM AT KMC HOSPITAL AND E.V.R.SALAI IN DN -103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/15987,Storm Water Drain,Completed,NH-ANNA NAGAR,103,52000,"PROVIDING AND FIXING FRC DOOR AT ORMES ROAD, KELLYS ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/15988,Buildings,Completed,NH-ANNA NAGAR,103,144000,"PROVIDING AND FIXING STAINLESS NAME BOARD TO HEALTH CENTRE AND DIVISION OFFICE AT TEMPLE STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/16075,Roads,Completed,NH-ANNA NAGAR,103,590000,"PROVIDING AND FIXING STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/17447,Roads,Completed,NH-ANNA NAGAR,103,660000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE BY PAVER FINISHER WITH CAMBER CORRECTION AT DHARMARAJA KOIL STREET AND LANE IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18370,Buildings,Completed,NH-ANNA NAGAR,103,352000,"REPAIRS AND IMPROVEMENTS TO THE PUBLIC CONVENIECS AND SEWER LINE AT KAMARAJAR NAGAR AND VALLIAMMAL STREET IN DN-103,U-23,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/18418,Footpath,Completed,NH-ANNA NAGAR,103,206000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING FOOT PATH AT APPA GARDEN STREET IN DN-03, UNIT-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18420,Footpath,Completed,NH-ANNA NAGAR,103,228000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING FOOT PATH AT VALLIAMMAL STREET AND BRANSON GARDEN STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18795,Buildings,Completed,NH-ANNA NAGAR,103,999000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING FOOT PATH AT KELLYS ROAD (FROM JN OF ORMES ROAD TO OPP TO RANGANATHAN AVENUE) IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/18810,Buildings,Completed,NH-ANNA NAGAR,103,168000,"REPAIRS TO THE EXISTING ROOF SHEET AT AMMA UNAVAGAM ( TAYLORS ROAD) IN DN-103,U-23,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/18811,Roads,Completed,NH-ANNA NAGAR,103,195000,"PROVIDING WATER TABLE AT ORMES ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/18812,Buildings,Completed,NH-ANNA NAGAR,103,183000,"REPAIRS TO THE EXISTING ROOF SHEET AT DIVISION OFFICE CAMPUS IN DN-103,U-23,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/18850,Buildings,Completed,NH-ANNA NAGAR,103,210000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING TOILET AND STORE ROOM UPHC CENTER AT TEMPLE STREET IN DN-103,U-23,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/18879,Buildings,Completed,NH-ANNA NAGAR,103,138000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHAPATHY CENTER AT HALLS LANE IN DN-103,U-23, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/19555,Buildings,Completed,NH-ANNA NAGAR,103,354000,"ROOFING WITH G.I SHEET IN FRONT OF E-SEVA CENTR AT DIVISION OFFICE CAMPUS IN DN-103,U-23,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/19697,Buildings,Completed,NH-ANNA NAGAR,103,289000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING FOOT PATH AT MANICKESWARI ROAD, BALFOUR ROAD AND TAYLORS ROAD(LANE) IN DN-103,U-23,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/2473,Roads,Completed,NH-ANNA NAGAR,103,399000,"LAYING CEMENT CONCRETE ROAD AT RANI ANNA NAGAR MAIN ROAD FROM HALLS ROAD (NORTH TO SOUTH) IN DN-103, UNIT-23, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/3958,Buildings,Completed,NH-ANNA NAGAR,103,185000,"REPAIRS AND IMPROVEMENT TO RATION SHOP AT KELLYS ROAD IN DN-103,UNIT -23,ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/5077,Storm Water Drain,Completed,NH-ANNA NAGAR,103,997000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-103,UNIT-23,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/7010,Storm Water Drain,Completed,NH-ANNA NAGAR,103,980000,"DESILTING OF OTTERI NALLAH RIVER FROM JN OF VENKATAPATHY STREET TO CH 295.00M (WESTERN SIDE) IN DN-103, U- 23, Z- 8.",Own Sources,8,2016-17,2016-17 NH/2016-17/7012,Storm Water Drain,Completed,NH-ANNA NAGAR,103,980000,DESILTING OF OTTERI NALLAH RIVER FROM JN OF VENKATAPATHY STREET TO CH 300.00M (EASTERN SIDE) IN DN 103 U 23 Z 8,Own Sources,8,2016-17,2016-17 NH/2016-17/7446,Buildings,Completed,NH-ANNA NAGAR,103,181000,"IMPROVEMENTS TO THE AMMA UNAVAGAM AT HALLS ROAD IN DN-103, U-23, Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/8158,Buildings,Completed,NH-ANNA NAGAR,103,412000,"IMPROVEMENTS TO THE TOILET BLOCK INSIDE CHS SCHOOL AT THIYAGAPPA STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/8159,Buildings,Completed,NH-ANNA NAGAR,103,294000,"IMPROVEMENTS TO WATER SUPPLY CHS SCHOOL AT THIYAGAPPA STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/8773,Buildings,Completed,NH-ANNA NAGAR,103,990000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT TAYLORS ROAD( OLD ZONAL OFFICE) IN DN-103, UNIT-23, ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9223,Roads,Completed,NH-ANNA NAGAR,103,516300,"RELAYING THE ROAD WITH BCCMP 30MM THICK BY PAVER FINISHER AT FLOWERS ROAD LANE IN DN-103, U-23,Z-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9271,Roads,Completed,NH-ANNA NAGAR,103,987000,"RELAYING THE ROAD WITH BCCMP 30MM THICK BY PAVER FINISHER AT MANONMANIAMMAL STREET IN DN-103,U-23,Z-8.",Own Sources,8,2016-17,2016-17 BR/2016-17/17727,Roads,Completed,BR-Bus Route Roads,104,860000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Konnur High Road, 100 Feet Road, Nelson Manickam Road, ICF Railway Road, Kilpauk Garden Road, Purasaiwalkam High Road, Raja Annamalai Road, Mayor Ramanathan Salai and Ormes Road in Zone-8",Grants,8,2016-17,2017-18 L/2016-17/18021,Electrical,Completed,L-Electrical,104,130000,WORK: Supply and Fixing of 2 Core SMC Fuse box 67 nos and 40 nos. cable raising with joint at various places in Division-103 & 104 Zone-8 area.,Own Sources,8,2016-17,2017-18 NH/2016-17/0371,Buildings,Completed,NH-ANNA NAGAR,104,211000,"PROVIDING RAMP & FLOORING FACILITIES AT VARIOUS PLACES IN DIVISION 104, UNIT - 23, ZONE - 8",Own Sources,8,2016-17,2016-17 NH/2016-17/0372,Buildings,Completed,NH-ANNA NAGAR,104,134000,"IMPROVEMENT WORKS TO P.C AT BRICKLINE ROAD, NEW BOOPATHINAGER, FLOWERS ROAD, PULLAPURAM, SASTRI NAGER IN DIVISION 104 , UNIT 23, ZONE - 8",Own Sources,8,2016-17,2016-17 NH/2016-17/0376,Buildings,Completed,NH-ANNA NAGAR,104,125000,"IMPROVEMENT AT GANGADESWARAR KOVIL STREET - HIGHER SECONDRY SCHOOL, C.S.I MIDDLE SCHOOL, LIBRARY IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/0613,Buildings,Completed,NH-ANNA NAGAR,104,390000,"PROVIDING PARTITION, BARRICADDING,DEFACING OF WALLS, MARKING OF 100 M AND 200 M FOR TAMILNADU GENERAL ELECTION 2016 AT TNSCB SCHOOL,CMS SUNDARAM SCHOOL, JUNIOR ENGINEER OFFICE (OLD DN- 61),CHENNAI LIBRARY AT SUNDARM LANE ,C.S.I MIDDLE SCHOOL,E.L.M SCHOOL,CHSS AT G.KOIL STREET,LADY MCT.M SCHOOL,KERALA VIDYALAYA SCHOOL,CMS AT PULLPURAM IN DN-104, UNIT-23, ZONE-VIII",Own Sources,8,2016-17,2016-17 NH/2016-17/11097,Buildings,Completed,NH-ANNA NAGAR,104,999500,"REPAIRS AND IMPROVEMENTS WORK AT TPF UNDER (SWACHH BHARAT SCHEME) IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/11099,Buildings,Completed,NH-ANNA NAGAR,104,820000,"PROPOSED CONSTRUCTION OF NAMMA TOILET AT NEW BOOPATHY NAGER DIVISION 104, UNIT 23, ZONE 8 (SWATCH BHARAT SCHEME)",Own Sources,8,2016-17,2016-17 NH/2016-17/11100,Storm Water Drain,Completed,NH-ANNA NAGAR,104,390000,"IMPROVEMENTS IN OTTERY BURIAL GROUND IN DIVISION 104, UNIT 23, ZONE - 8",Own Sources,8,2016-17,2016-17 NH/2016-17/11101,Buildings,Completed,NH-ANNA NAGAR,104,370000,"IMPROVEMENTS TO I.C.D.C CENTER AT PULLAPURAM C.M.S IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/11105,Buildings,Completed,NH-ANNA NAGAR,104,399900,"IMPROVEMENTS AND REPAIR WORKS AT OTTERY BURIAL GROUND AT DIVISION 104, UNIT - 23, ZONE - 8",Own Sources,8,2016-17,2016-17 NH/2016-17/11292,Buildings,Completed,NH-ANNA NAGAR,104,744000,"PROVIDING PLATFORMS FOR BIN LOCATION AND WATER TABLE, PAINTING FOOT PATHS AT VARIOUS PLACES IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/11329,Buildings,Completed,NH-ANNA NAGAR,104,395000,"PROVIDING BASEMENT BORE FACILITIES WORK FOR NAMMA TOILET AT LETTANGS ROAD( JUNCTION OF DR.ALAGAPPA ROAD ) IN DIVISION-104,UNIT-23,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/11330,Buildings,Completed,NH-ANNA NAGAR,104,720000,"SUPPLYING AND FIXING OF NAMMA TOILET WITH OUT SEWERAGE RGE.WOMEN -1, REG.MEN-1, URINAL 1 AT LETTANGS ROAD ( JUNCTION OF DR.ALAGAPPA ROAD ) IN DIVISION-104,UNIT-23,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/11331,Parks,Completed,NH-ANNA NAGAR,104,799000,"HOUSE KEEPING AND SECURITY FOR BANK MANICKAM PARK AND ROADSIDE PARK AROUND NAMMA TOILET IN DN 104, UNIT 23, ZONE-VIII",Own Sources,8,2016-17,2017-18 NH/2016-17/11334,Buildings,Completed,NH-ANNA NAGAR,104,310000,"REPAIRS AND IMPROVEMENTS TO I.C.D.C CENTER AT PULLAPURAM C.M.S IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/11335,Buildings,Completed,NH-ANNA NAGAR,104,419000,"PROVIDING PLUMPING WORKS FOR NAMMA TOILET AT LETTANGS ROAD( JUNCTION OF DR.ALAGAPPA ROAD ) IN DIVISION-104,UNIT-23,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/11336,Buildings,Completed,NH-ANNA NAGAR,104,750000,"CONSTRUCTION OF KITCHEN SHED , REPAIRS AND IMPROVEMENTS TO PULLAPURAM MIDDLE SCHOOL IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/14085,Buildings,Completed,NH-ANNA NAGAR,104,360000,"REPAIRS AND IMPROVEMENT WORKS IN PUBLIC CONVENIENCE AT LAWDERS GATE, BRICKLIN ROAD, SADHASIVAM STREET, PULLAPURAM IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/14373,Buildings,Completed,NH-ANNA NAGAR,104,560000,"CONSTRUCTION OF KITCHEN SHED AND TOILET, REPAIRS AND IMPROVEMENTS AT GANGADESWARAR HIGHER SECONDARY SCHOOL LOCATED AT DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/14383,Buildings,Completed,NH-ANNA NAGAR,104,112000,"CONSTRUCTION OF SUMP, REPAIRS AND IMPROVEMENTS AT SUNDARAM MIDDLE SCHOOL IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/14394,Buildings,Completed,NH-ANNA NAGAR,104,190000,"REPAIR AND MAINTAINANCE AT VELLALA MIDDLE SCHOOL IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/15989,Buildings,Completed,NH-ANNA NAGAR,104,580000,"URGENT REPAIR WORKS AT BANK MANICKAM PARK, HEALTH POST, NAMMA TOILET, BURRIAL GROUND, GANGADESWARAR HIGH SCHOOL IN DIVISION 104, UNIT 23, ZONE 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/16043,Storm Water Drain,Completed,NH-ANNA NAGAR,104,678000,"REPAIRS AND IMPROVEMENTS WORKS FOR STROM WATER DRAIN AT DR.ALAGAPPA ROAD NEAR ALAGAPPA SCHOOL IN DIVISION 104, UNIT - 23, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/17051,Buildings,Completed,NH-ANNA NAGAR,104,298000,"REPAIRS AND IMPROVEMENT WORK OF STORM WATER DRAIN AND FOOTPATH AT VARIOUS STREET IN DIVISION-104 , UNIT-23, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/17735,Footpath,Completed,NH-ANNA NAGAR,104,389000,"REPAIRS AND IMPROVEMENTS TO FOOT PATH AT LETHANGS ROAD ,DEWAN RAMA ROAD AND PROVIDING STREET NAME BOARD IN DIVISION 104, UNIT 23, ZONE -8",Own Sources,8,2016-17,2017-18 NH/2016-17/17977,Buildings,Completed,NH-ANNA NAGAR,104,10500,"PROVIDING NAME BOARDS UPHC CENTER AT RATNA SABAPATHY STREET IN DIVISION - 104, UNIT-23, ZONE-8",Own Sources,8,2016-17,2018-19 NH/2016-17/17997,Buildings,Completed,NH-ANNA NAGAR,104,369000,"REPAIRS AND MAINTAINANACE WORK OF PARK AND PLAY GROUND AT VARIOUS LOCATION IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/2233,Buildings,Completed,NH-ANNA NAGAR,104,990000,"CONSTRUCTION OF STROM WATER DRAIN FROM OSAN KULLAM TO NEW BOOPATHY NAGER IN DIVISON 104, UNIT 23, ZONE 8 (COUNCILLOR FUND 2016-2017)",Own Sources,8,2016-17,2016-17 NH/2016-17/2234,Buildings,Completed,NH-ANNA NAGAR,104,980000,"CONSTRUCTION OF NEW PUBLIC TOILET CONVENIANCE AT PULLAPURAM IN DIVISON 104, UNIT 23, ZONE 8 (COUNCILLOR FUND 2016-2017)",Own Sources,8,2016-17,2017-18 NH/2016-17/2641,Buildings,Completed,NH-ANNA NAGAR,104,417000,"PROVIDING BORE AT SALAIMANAGAR PC & SADASIVAM STREET PC IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/4723,Buildings,Completed,NH-ANNA NAGAR,104,950000,"CONSTRUCTION OF COMPOUND WALL AT OTTERI BURIAL GROUND ROAD -(0M TO 65M) IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/4730,Buildings,Completed,NH-ANNA NAGAR,104,945000,CONSTRUCTION OF COMPOUND WALL AT OTTERI BURIAL GROUND ROAD (65M TO 130M) IN DN-104 UNIT-23 ZONE-8,Own Sources,8,2016-17,2016-17 NH/2016-17/4759,Buildings,Completed,NH-ANNA NAGAR,104,310000,"IMPROVEMENT AND REPAIR WORK AT P.C AT BRICKLIN ROAD AND NEW BOOPATHY NAGAR IN DIVISION-104, UNIT-23, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/5239,Storm Water Drain,Completed,NH-ANNA NAGAR,104,990000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREETS IN DN - 104, UNIT - 23, ZONE -8",Own Sources,8,2016-17,2016-17 NH/2016-17/5870,Storm Water Drain,Completed,NH-ANNA NAGAR,104,990000,"REPAIRS & IMPROVEMENTS TO STROM WATER DRAIN AT SUNDARAM STREET (0 TO 100 m) IN DIVISION 104, UNIT 23, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/6061,Buildings,Completed,NH-ANNA NAGAR,104,298000,"IMPROVEMENT WORKS AT AMMA UNAVAGAM - PHASE 2 IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/6596,Storm Water Drain,Completed,NH-ANNA NAGAR,104,990000,"REPAIRS & IMPROVEMENTS TO STROM WATER DRAIN AT SUNDARAM STREET (100 TO 200 m) IN DIVISION 104, UNIT 23, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/6598,Roads,Completed,NH-ANNA NAGAR,104,340000,"REPAIRS AND IMPROVEMENTS TO ROAD PATCH AND FOOT PATH AT PONNAPPA STREET AND 3RD LANE IN DIVISION 104, UNIT 23, ZONE- 8",Own Sources,8,2016-17,2016-17 NH/2016-17/6599,Buildings,Completed,NH-ANNA NAGAR,104,316000,"PROVIDING FLOORING AND IMPROVEMENT WORKS AT GANGADESWARAR KOVIL STREET - CHENNAI HIGHER SECONDRY SCHOOL IN DIVISION 104, UNIT 23, ZONE 8.",Own Sources,8,2016-17,2016-17 NH/2016-17/7577,Buildings,Completed,NH-ANNA NAGAR,104,349000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT BRICKLIN ROAD (THIDEER NAGAR )IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/8367,Storm Water Drain,Completed,NH-ANNA NAGAR,104,994000,"CONSTRUCTION OF STROM WATER DRAIN AT NEW BOOPATHY NAGER IN DIVISION 104, UNIT 23, ZONE 8 (COUNCILLOR FUND 2016-2017)",Own Sources,8,2016-17,2017-18 L/2016-17/18025,Electrical,Completed,L-Electrical,105,94600,"WORK: Supply and Fixing of 2 Core SMC Fuse box 100 nos at various places in Division-105, 106 & 108 Zone-8 area.",Own Sources,8,2016-17,2017-18 L/2016-17/18537,Electrical,Completed,L-Electrical,105,1899800,REMOVAL & REFIXING OF 42 NOS OF 9.5 MTR M.S.STREET LAMP POST WITH SINGLE ARCH BRACKET AND 10 NOS OF 8 MTR M.S.LAMP POST WITH SINGLE ARCH BRACKET AT JAWARLAL NEHRU ROAD IN (100 FEET ROAD) IN JN OF LOCANATHAN 3 rd STREET TO JN OF PERIYAR PATHAI JN. EASTERN SIDE AND OPPOSITE SIDE JN OF WEST PERIYAR PATHAI TO SAF GAMES VILLEAGE IN DIV-105&108 IN ZONE-8 ( DEPOSIT WORK ),Deposit Works,8,2016-17,2017-18 NH/2016-17/0525,Buildings,Completed,NH-ANNA NAGAR,105,119000,"PROVIDING CONCRETE PLAT FORM FOR INDIVIDUAL BINS AT VARIOUS PLACES IN DN-105,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/0587,Roads,Completed,NH-ANNA NAGAR,105,807000,"Relaying the road at Bharathidhasan street in dn-105, unit-22, zone-8",Own Sources,8,2016-17,2017-18 NH/2016-17/10219,Roads,Completed,NH-ANNA NAGAR,105,351000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT VINAYAGAPURAM 3RD STREET EXTN., IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/10223,Roads,Completed,NH-ANNA NAGAR,105,351000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT NEHRU STREET IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/10922,Roads,Completed,NH-ANNA NAGAR,105,399000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT MMDA COLONY MAIN ROAD TOWARDS MMDA COLONY A-BLOCK IN DN-105,UNIT-22,ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/11281,Storm Water Drain,Completed,NH-ANNA NAGAR,105,333000,"DESILTING OF STORM WATER DRAIN THURAIPILLAI STREET,COMMUNITY HALL STREET, SREE VENGADESA PERUMAL NAGAR, THIRUKUMARAPURAM 1ST, 3RD & 4TH STREET, JANAGIRAMAN MAIN ROAD, ANNAI STREET, MMDA COLONY MAIN ROAD, RAZZAK GARDEN MAIN ROAD AND VINAYAGAPURAM MAIN ROAD IN DN-105,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/11294,Storm Water Drain,Completed,NH-ANNA NAGAR,105,476000,"IMPROVEMENTS TO THE EXISTING STROM WATER DRAIN AT KAMALA NEHRU NAGAR MAIN ROAD TAMILAR VEETHI 1ST STREET (FROM CHAINAGE 21.00-71.00M) IN DN-105, U-22, Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/11452,Roads,Completed,NH-ANNA NAGAR,105,656000,"Relaying the road at Pandiyan Street in Div -105, Unit -22, Zone -8.",Own Sources,8,2016-17,2017-18 NH/2016-17/11458,Buildings,Completed,NH-ANNA NAGAR,105,982000,"VARIOUS PLACE SS LETTER ACP PANEL BOARD AT PLAY GROUND, PARK, NNMP SHED AND HOSPITAL AT DN-106, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/11468,Roads,Completed,NH-ANNA NAGAR,105,633000,"Relaying the road at Muthumariamman Koil Street in Div -105, Unit -22, Zone -8.",Own Sources,8,2016-17,2017-18 NH/2016-17/11471,Buildings,Completed,NH-ANNA NAGAR,105,987000,"Improvements and water arrangmets to CMS at MMDA 'C' Block in dn 105, unit 22, zone 8",Own Sources,8,2016-17,2017-18 NH/2016-17/11584,Storm Water Drain,Completed,NH-ANNA NAGAR,105,990000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DN-105,U-22,Z-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/13339,Road Cut,Completed,NH-ANNA NAGAR,105,347000,"Restoration of Road Cut made by TNEB at police station street, SBI Staff colony 2nd street and Thiruveethi amman koil street in Division-105, Unit-22, Zone-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/13342,Road Cut,Completed,NH-ANNA NAGAR,105,347000,"Restoration of Road Cut made by TNEB at Janakiram colony main road and Jawahar street in Division-105, Unit-22, Zone-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/13343,Road Cut,Completed,NH-ANNA NAGAR,105,347000,"Restoration of Road Cut made by TNEB at Vinayapapuram 2nd street and Thirukumarapuram 1st street in Division-105, Unit-22, Zone-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/13346,Road Cut,Completed,NH-ANNA NAGAR,105,347000,"Restoration of Road Cut made by TNEB at Water tank road, valluvar road, Ganavinayagar koil street and Gandhi road in Division-105, Unit-22, Zone-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/13350,Roads,Completed,NH-ANNA NAGAR,105,347000,"Restoration of Road Cut made by TNEB at Razack garden avenue and Ashok street in Division-105, Unit-22, Zone-8",Deposit Works,8,2016-17,2017-18 NH/2016-17/14369,Buildings,Completed,NH-ANNA NAGAR,105,112000,"Repairs and Improvements to CMS at C-Block, MMDA Colony in Division-105, Unit-22, Zone-8",Own Sources,8,2016-17,2016-17 NH/2016-17/14745,Buildings,Completed,NH-ANNA NAGAR,105,313000,"REPAIRS AND MAINTENANCE WORKS FOR EXISITNG ANGANWADI CENTER 336030040106 AT ASHOKA STREET AND 04024 AT G BLOCK MMDA COLONY IN DN-105,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/17418,Buildings,Completed,NH-ANNA NAGAR,105,102700,"IMPROVEMENT TO SSS TOILET AT MMDA COLONY MAIN ROAD(ROAD SIDE)IN DIVISON-105,UNIT-22,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/18587,Buildings,Completed,NH-ANNA NAGAR,105,10500,"Providing Name Board At UPHC Pandayan Street, MMDA Colony D-Block In Division-105, Unit-22, Zone-8",Own Sources,8,2016-17,2018-19 NH/2016-17/4561,Buildings,Completed,NH-ANNA NAGAR,105,83000,"PROVIDING VINYL NAME BOARD FOR BUS STAND AT VARIOUS ROAD AND PAINTING FOOT PATH AT VARIOUS ROAD IN DN-105,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/4562,Storm Water Drain,Completed,NH-ANNA NAGAR,105,106000,"ATTENDING AND LOWERING MANHOLE DOOR AT VARIOUS STREET IN DN-105,U-22,Z-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/4563,Buildings,Completed,NH-ANNA NAGAR,105,123000,"PROVIDING RAIN WATER HARVESTING AT JANAKI RAMAN COLONY CROSS STREET IN DN-105,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/4717,Roads,Completed,NH-ANNA NAGAR,105,500000,"Providing Street name board at various streets in dn-105, unit-22, zone-8 (WARD COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/5176,Storm Water Drain,Completed,NH-ANNA NAGAR,105,600000,"Desilting of Storm Water Drain at Various street in Division-105, Unit-22, Zone-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/5177,Storm Water Drain,Completed,NH-ANNA NAGAR,105,910000,"Desilting of Storm Water Drain at ashok street, kannagi street, sbi staff colony and kalki nagar in Division-105, Unit-22, Zone-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/5242,Buildings,Completed,NH-ANNA NAGAR,105,58000,"WRITING NAME BOARD AT VARIOUS PLACES IN CORPORATION BUILDING IN DN-105,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/5243,Buildings,Completed,NH-ANNA NAGAR,105,211600,"PROVIDING OPEN WELL RING RAIN WATER HARVESTING AT RAZACK GARDEN ROAD IN DN-105,U-22,Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/5446,Roads,Completed,NH-ANNA NAGAR,105,500000,"Providing Street name board at various streets in dn-105, unit-22, zone-8 (WARD COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/5585,Buildings,Completed,NH-ANNA NAGAR,105,999000,"DESILTING OF VIRUGAMBAKKAM RIVER FROM THIRUKUMARAPURAM TO 1OO FEET METRO RAIL IN DN-105,UNIT-22,ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/6224,Buildings,Completed,NH-ANNA NAGAR,105,981000,"Improvements to CMS at MMDA 'C' Block in dn 105, unit 22, zone 8. (WARD COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/6225,Buildings,Completed,NH-ANNA NAGAR,105,997000,"IMPROVEMENTS TO ICDC AT VARIOUS PLACE IN DN-105, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/6312,Parks,Completed,NH-ANNA NAGAR,105,959000,"Construction of Compound wall at mariyaman koil street in division-105, unit-22, zone-8 (WARD COUNCILLOR FUND 2016-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/7398,Storm Water Drain,Completed,NH-ANNA NAGAR,105,399000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT MMDA COLONY MAIN ROAD TOWARDS NEW NATARAJAPURAM IN DN-105, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/7714,Storm Water Drain,Completed,NH-ANNA NAGAR,105,998000,"IMPROVEMENTS TO THE EXISTING STROM WATER DRAIN AT KAMALA NEHRU NAGAR 1ST STREET (CHAINAGE 0-165.00M) IN DN-105, UNIT-22, ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/7740,Storm Water Drain,Completed,NH-ANNA NAGAR,105,999000,"IMPROVEMENTS TO THE EXISTING STROM WATER DRAIN AT KAMALA NEHRU NAGAR 1ST STREET (CHAINAGE 165-257.00M) AND KAMALA NEHRU NAGAR MAIN ROAD TAMILAR VEETHI 1ST STREET IN DN-105, U-22, Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/8178,Roads,Completed,NH-ANNA NAGAR,105,752000,"Relaying The Road at P.P.Nagar 1st Street, 2nd Street and 3rd Street in DN-105, U-22, Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/8179,Roads,Completed,NH-ANNA NAGAR,105,983000,"Relaying The Road at P.P.Nagar 4th Street, 5th Street and P.P.Nagar Lane IN DN-105, U-22, Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/8591,Roads,Completed,NH-ANNA NAGAR,105,985000,"Relaying The Road at Cheran Street Lane's in Dn-105, Unit-22, Zone-8",Own Sources,8,2016-17,2017-18 NH/2016-17/8592,Roads,Completed,NH-ANNA NAGAR,105,994000,"Relaying The Road at Cheran Street in Dn-105, Unit-22, Zone-8",Own Sources,8,2016-17,2017-18 NH/2016-17/9102,Roads,Completed,NH-ANNA NAGAR,105,1153000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT BALAVINAYAGAR NAGAR MAIN ROAD IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9103,Roads,Completed,NH-ANNA NAGAR,105,907000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT PERUMAL KOIL GARDEN STREET IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9104,Roads,Completed,NH-ANNA NAGAR,105,527000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT THIRUMAGAL 1ST CROSS STREET IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9105,Roads,Completed,NH-ANNA NAGAR,105,343000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT THIRUMAGAL 2ND CROSS STREET IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9106,Roads,Completed,NH-ANNA NAGAR,105,351000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT KAMALA NEHRU NAGAR 2ND STREET (PART) IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9107,Roads,Completed,NH-ANNA NAGAR,105,1485000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT KAMALA NEHRU NAGAR 1ST STREET IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9108,Roads,Completed,NH-ANNA NAGAR,105,396000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT DURAI PILLAI STREET IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9111,Roads,Completed,NH-ANNA NAGAR,105,379000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT RAJIV GANDHI STREET (P.H ROAD) IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9112,Roads,Completed,NH-ANNA NAGAR,105,221000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT KANNAPPAN NAGAR IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9113,Roads,Completed,NH-ANNA NAGAR,105,697000,"RELAYING THE ROAD WITH DBM AND BC BY PAVER FINISHER AT VINAYAGAPURAM 1ST STREET IN DN-105, U-22, ZONE-8.",Own Sources,8,2016-17,2016-17 BR/2016-17/17888,Footpath,Completed,BR-Bus Route Roads,106,1010000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Anna Nagar 4th Avenue , Anna Nagar 3rd Avenue, Nelson Manickam Road and other Bus Route Roads in Zone 8",Own Sources,8,2016-17,2017-18 BR/2016-17/18747,Road Cut,Completed,BR-Bus Route Roads,106,1750000,"Restoration of road cut made by TANGEDCO at Nelson Manickam road from the jn of Railway Colony 2nd Street to the jn of Thiruvengadapuram 2nd Street in Dn - 106, zone - 8 (Chellan No; BR/2015-16/0018665)",Deposit Works,8,2016-17,2017-18 BR/2016-17/18748,Road Cut,Completed,BR-Bus Route Roads,106,1700000,"Restoration of road cut made by TANGEDCO at Nelson Manickam road from the jn of Railway colony 4th street to the jn of Railway Colony 2nd street in Dn - 106, zone - 8 (Chellan No; BR/2015-16/0018665)",Deposit Works,8,2016-17,2017-18 BR/2016-17/19174,Road Cut,Completed,BR-Bus Route Roads,106,1880000,"Restoration of Roadcut made by TANGEDCO at Nelson Manickam Road from the jn of Bharath Petrolieum Bunk to the jn of Railway Colony 4th Street in Dn-106, Zone-8",Deposit Works,8,2016-17,2017-18 L/2016-17/14706,Electrical,Completed,L-Electrical,106,1316000,"PROVISION OF NEW 1 NOS OF 20 MTR HIGHMAST WITH 7 NOS OF 210W TO 230W LED FITTINGS AT EVR SALAI NEAR ANNA ARCH BEHIND IN DIV-106,ZONE-8",Deposit Works,8,2016-17,2017-18 L/2016-17/17520,Electrical,Completed,L-Electrical,106,3370000,WORK: Removal and Refixing of 898 Nos of fallen lamp post due to vardha cyclone in division 94 to 108 - Zone-8 area.,Own Sources,8,2016-17,2016-17 L/2016-17/8531,Electrical,Completed,L-Electrical,106,4942900,provision of 31 nos 8mtr octogonal lamp post with single st.bracket lamp post at service road in evr salai and 3 rd avenue near anna ayurvedic hospital( Eastern &Western) side and 16 nos of 8 mtr octogonal double bracket lamp post in centre median post in div-101&106 in zone-8,Deposit Works,8,2016-17,2016-17 L/2016-17/8536,Electrical,Completed,L-Electrical,106,4144900,PROVISION OF 80 NOS OF 6 MTR G.I.LAMP POST WITH SINGLE ARCH BRACKET AT EVR SALAI OVER BRIDGE IN JN OF 3 RD AVENUE TO JN OF NELSONMANICKAM ROAD (EASTERN&WESTERN) SIDE IN DIV-101&106 IN ZONE-8,Deposit Works,8,2016-17,2016-17 NH/2016-17/10401,Roads,Completed,NH-ANNA NAGAR,106,213900,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT OFFICERS COLONY 3RD STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/10414,Roads,Completed,NH-ANNA NAGAR,106,283400,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT S.S.SAHIB STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/10418,Roads,Completed,NH-ANNA NAGAR,106,241600,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT WEST ARASAMARAM STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/10422,Roads,Completed,NH-ANNA NAGAR,106,75800,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT OTTERPALAYAM STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/12416,Storm Water Drain,Completed,NH-ANNA NAGAR,106,565000,"REPAIRS AND IMPROVEMENT TO THE STORM WATER DRAIN AT M.H COLONY 2ND CROSS STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/12716,Footpath,Completed,NH-ANNA NAGAR,106,65500,INTER CONNECTION OF STORM WATER DRAIN @ M H COLONY 3RD CROSS STREET IN DN 106 UNIT 22 ZONE 8,Own Sources,8,2016-17,2016-17 NH/2016-17/13419,Storm Water Drain,Completed,NH-ANNA NAGAR,106,72000,"REPAIRS AND IMPROVEMENT TO THE SIDE DRAIN AT KAKKAN NAGAR IN DN-106,UNIT-22,ZONE-8",Own Sources,8,2016-17,2016-17 NH/2016-17/14037,Buildings,Completed,NH-ANNA NAGAR,106,128000,"Repairs and improvements to the public convenience at perumal koil street, lime klin street, vellala street, amman koil street & MH Colony in Dn-106,Unit-22,Zone-8",Own Sources,8,2016-17,2018-19 NH/2016-17/14441,Storm Water Drain,Completed,NH-ANNA NAGAR,106,18000,SUPLLAYING AND FIXING 300MM PVC PIPE FOR STORM WATER DRAIN @ MATHA KOVIL STREET IN DN 106 UNIT 22 ZONE 8,Own Sources,8,2016-17,2016-17 NH/2016-17/14447,Footpath,Completed,NH-ANNA NAGAR,106,39000,REPAIR WORK TO FOOTPATH @ COLOCTER COLONY IN DN 106 UNIT 22 ZONE 8,Own Sources,8,2016-17,2016-17 NH/2016-17/15621,Buildings,Completed,NH-ANNA NAGAR,106,157000,"REPAIRS AND IMPROVEMENT TO THE FOOT PATH AT NARASIMMAN STREET GOVINDHAN STREET MUTHU KRISHNAN STREET IN DN-106,INIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/15677,Footpath,Completed,NH-ANNA NAGAR,106,35000,REPAIR WORK TO THE FOOT PATH AT METHA NAGAR MAIN ROAD IN DN-106 U 22 Z 8,Own Sources,8,2016-17,2016-17 NH/2016-17/15678,Buildings,Completed,NH-ANNA NAGAR,106,81000,"PROVIDING ILLUMINATION BOARDS AND LIGHTING ARRANGEMENTS FOR BUS SHELTER AT NELSON MANICKAM ROAD IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/16460,Parks,Completed,NH-ANNA NAGAR,106,80000,"IMPROVEMENTS TO COMPOUND WALL(for vardhah cyclone) METHA NAGAR PLAY GROUNDIN DN-106.UNIT-22,ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/16461,Parks,Completed,NH-ANNA NAGAR,106,62000,"IMPROVEMENTS TO COMPOUND WALL(for vardhah cyclone) AT M.H.COLONY NIGHT SHELTER IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2018-19 NH/2016-17/17942,Buildings,Completed,NH-ANNA NAGAR,106,19000,"SUPPLYING AND PASTING REFLECTIVE SHEET FOR STREET NAME BOARD @ LIME KILN STREET, KANNAIH STREET IN DN 106 UNIT 22 ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/18022,Buildings,Completed,NH-ANNA NAGAR,106,10500,"PROVIDING NAME BOARD AT UPHC, COLLECTRATE COLONY 6TH CROSS STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2018-19 NH/2016-17/19656,Buildings,Completed,NH-ANNA NAGAR,106,20500,"REPAIR WORK TO AMMA UNAVAGAM AT COLLECTER COLONY MAIN ROAD IN DN 106,UNIT 22,ZONE 8",Own Sources,8,2016-17,2017-18 NH/2016-17/19657,Buildings,Completed,NH-ANNA NAGAR,106,58000,SUPPLYING AND FIXING STREET NAME BOARD @ OFFICERS COLONY 3RD CROSS STREET AND SARANGAPANI STREET DN 106 UNIT 22 ZONE 8,Own Sources,8,2016-17,2017-18 NH/2016-17/19658,Buildings,Completed,NH-ANNA NAGAR,106,77000,"SUPPLYING AND FIXING GRATING AT VARIOUS STREET IN DN106,UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/19659,Buildings,Completed,NH-ANNA NAGAR,106,40500,"REPAIR WORK TO BORE WELL (E.B OFFICE) AT COLLECTERATE COLONY MAIN ROAD IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/19660,Buildings,Completed,NH-ANNA NAGAR,106,21000,"PROVIDING AND FIXING WALL TILE TO SUMP @ METAL FACTORY PARK IN DN 106,UNIT 22, ZONE 8.",Own Sources,8,2016-17,2017-18 NH/2016-17/3306,Footpath,Completed,NH-ANNA NAGAR,106,93000,"Painting for footpath at Nelson manickam road,division -106,unit-22,zone8",Own Sources,8,2016-17,2016-17 NH/2016-17/4150,Buildings,Completed,NH-ANNA NAGAR,106,980000,"REPAIRS AND IMPROVEMENTS WORKS TO GYM AT NAVANETHIYAMMAL STREET WARD COUNCILLOR FUND 2016-17 IN DN-106,U-22,Z-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/4470,Buildings,Completed,NH-ANNA NAGAR,106,970000,"REPAIR AND IMPROVEMENTS OF GYM AT M.H. COLONY 2ND MAIN ROAD WARD COUNCILLOR FUND 2016-17 IN DN-106, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/4513,Storm Water Drain,Completed,NH-ANNA NAGAR,106,990000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-106, UNIT-22,ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/4883,Buildings,Completed,NH-ANNA NAGAR,106,996000,"VARIOUS PLACE SS LETTER ACP PANEL BOARD AT DIVISION OFFICE, PLAY GROUND, PARK, NNMP SHED AND HOSPITAL IN WARD COUNCILLOR FUND 2016-17 AT DN-106, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/5009,Storm Water Drain,Completed,NH-ANNA NAGAR,106,979000,"DESILTING OF VIRUGAMPAKKAM RIVER FROM AZAD NAGAR 2ND STREET TO M.H COLONY (MATHA KOIL STREET) IN DN.106, UNIT.22 ZONE.8 USING FLOAT MOUNTED MACHINARIES",Own Sources,8,2016-17,2016-17 NH/2016-17/5011,Storm Water Drain,Completed,NH-ANNA NAGAR,106,980000,"DESILTING OF VIRUGAMBAKKAM RIVER FROM M.H.COLONY TO RAILWAY COLONY 3RD STREET IN DN.106, UNIT.22, ZONE.8 USING FLOAT MOUNTED MACHINARIES",Own Sources,8,2016-17,2016-17 NH/2016-17/5129,Storm Water Drain,Completed,NH-ANNA NAGAR,106,200000,"Desilting of storm water drain at nelson manickam road in Dn-106,Unit-22,Zone-08",Own Sources,8,2016-17,2017-18 NH/2016-17/6205,Buildings,Completed,NH-ANNA NAGAR,106,600000,"conversion of existing dispensary to amma unavagam face-2 at reddy avenue in dn-106,unit-22,zone-08",Own Sources,8,2016-17,2017-18 NH/2016-17/7367,Roads,Completed,NH-ANNA NAGAR,106,438000,"ROAD CUT RESTORATION MADE BY (CMWSSB) AT PETER RAJA STREET IN DN-106,UNIT-22,ZONE-08",Deposit Works,8,2016-17,2016-17 NH/2016-17/8087,Buildings,Completed,NH-ANNA NAGAR,106,101000,CONSTRUCTION OF PLATFORM FOR BIN @ VARIOUS STREET IN DN 106 U-22 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/9184,Roads,Completed,NH-ANNA NAGAR,106,213000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT SABAPATHI STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9186,Roads,Completed,NH-ANNA NAGAR,106,322000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT OFFICERS COLONY 1ST STREET IN DN -106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9208,Buildings,Completed,NH-ANNA NAGAR,106,31000,"SUPPLYING AND NAME BOARD FOR UPHC IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2017-18 NH/2016-17/9213,Roads,Completed,NH-ANNA NAGAR,106,653000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT EAST MADA STREET IN DN-106, UNIT-22.ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9215,Roads,Completed,NH-ANNA NAGAR,106,716000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT NORTH KASARATH THOTTAM,IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9218,Roads,Completed,NH-ANNA NAGAR,106,287000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT EAST ARASAMARAM STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9220,Roads,Completed,NH-ANNA NAGAR,106,533000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT LIME KILN STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9228,Roads,Completed,NH-ANNA NAGAR,106,1723000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT LAKSMIAMMAL STREET IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9232,Roads,Completed,NH-ANNA NAGAR,106,465000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT SOUTH KASARATH THOTTAM IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9303,Roads,Completed,NH-ANNA NAGAR,106,207000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT MANGALIAMMAN KOIL STREET IN DN-106 UNIT-22,ZONE-08",Own Sources,8,2016-17,2016-17 NH/2016-17/9889,Roads,Completed,NH-ANNA NAGAR,106,102000,"RELAYING OF C.C ROAD AT AMMAN KOIL STREET IN DN-106, UNIT - 22, ZONE - 8",Own Sources,8,2016-17,2017-18 NH/2016-17/9893,Buildings,Completed,NH-ANNA NAGAR,106,299000,"REPAIRS WORK TO NIGHT SHELTER BUILDING AT M.H.COLONY 1ST MAIN ROAD IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2016-17,2017-18 L/2016-17/18024,Electrical,Completed,L-Electrical,107,113000,WORK: Supply and Fixing of 2 Core SMC Fuse box 120 nos at various places in Division-102 & 107 Zone-8 area.,Own Sources,8,2016-17,2017-18 L/2016-17/19030,Electrical,Completed,BR-Bus Route Roads,107,530900,"Removal and Refixing of 24nos 9.5mtr OH Lamp post and Laying of 31/2 x 25 Sqmm Aluminium cable 838mtr for platform forming work by BRR Department at Mayor Ramanathan salai east in Dn-107,Zone-VIII area.",Own Sources,8,2016-17,2017-18 NH/2016-17/0110,Road Cut,Completed,NH-ANNA NAGAR,107,96000,"PROVIDING AND FIXING OF FRC DOOR AT VARIOUS LOCATION IN DIV-107,UN-23,Z-08",Own Sources,8,2016-17,2016-17 NH/2016-17/0207,Buildings,Completed,NH-ANNA NAGAR,107,140000,"IMPROVEMENTS TO C.M.S.M.S.NAGAR BOOTH NO;133,134,135,137 AT MAYOR SATHYAMOORTHY SALAI IN DIV-107 U-23 Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/0208,Buildings,Completed,NH-ANNA NAGAR,107,248000,"IMPROVEMENT TO COMMUNITY HALL BOOTH NO:131,132 AT SATHYAMOORTHY SALAI IN DIV-107 U-23 Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/0209,Buildings,Completed,NH-ANNA NAGAR,107,213000,"IMPROVEMENT TO C.M.S.SCHOOL BOOTH NO:138,139 AT NO:14, SCHOOL ROAD IN DIV-107 U-23 Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/0210,Buildings,Completed,NH-ANNA NAGAR,107,300000,"IMPROVEMENT TO C.M.S. SCHOOL BOOTH NO:140,141,142,143,144,AT NO:27, SCHOOL ROAD IN DIV-107 U-23 Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/0237,Buildings,Completed,NH-ANNA NAGAR,107,134000,EARASING ROMOVING POLITICAL ADS STRICKAR HARRINGHTON ROAD RAMANATHAN SALAI DR GURUSAMY ROAD IN DIV 107 U 23 Z08,Deposit Works,8,2016-17,2016-17 NH/2016-17/0238,Buildings,Completed,NH-ANNA NAGAR,107,87000,REPAIR AND FIXING F R C DOOR AT VARIOUS STREET IN DIV 107 U 23 Z 08,Own Sources,8,2016-17,2016-17 NH/2016-17/0676,Footpath,Completed,NH-ANNA NAGAR,107,155000,IMPROVEMENT TO FOOT BATH MAYOR RAMANATHAN SALAI( COOUVAM RIVER SIDE) IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2016-17 NH/2016-17/1146,Footpath,Completed,NH-ANNA NAGAR,107,340000,IMPROVEMENT TO FOOT BATH MAYOR RAMANATHAN SALAI(COOVER RIVER SIDE) IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2016-17 NH/2016-17/1156,Footpath,Completed,NH-ANNA NAGAR,107,490000,IMPROVEMENT TO FOOT BATH MAYOR RAMANATHAN SALAI IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2016-17 NH/2016-17/12761,Bridges,Completed,NH-ANNA NAGAR,107,2570000,"RELAYING THE BT ROAD AT PC HOSTEL ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/14023,Buildings,Completed,NH-ANNA NAGAR,107,197000,"REPAIRS AND IMPROVEMENTS TO PC DOHBIKHNA ,MANGALAPURAM MAIN ROAD, JAGANATHAN PURAM 1st STREET IN-107 U-23,Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/14374,Buildings,Completed,NH-ANNA NAGAR,107,394000,"IMPROVEMENT AND REPAIR WORKS AT CHENNAI HR SEC SCHOOL SUBBARAYAN STREET,CHENNAI HR SEC SCHOOL MC NICHOLS ROAD, CHENNAI MIDDLE SCHOOL JAGANATHAPURAM SCHOOL ROAD, CHENNAI MIDDLE SCHOOL MS NAGAR IN DIVISION 107 UNIT 23 ZONE-8,",Own Sources,8,2016-17,2017-18 NH/2016-17/1604,Roads,Completed,NH-ANNA NAGAR,107,304000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MC NICHOLS ROAD IN DIVISION - 107, UNIT - 23, ZONE - 8",Deposit Works,8,2016-17,2017-18 NH/2016-17/1605,Road Cut,Completed,NH-ANNA NAGAR,107,395000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT P.C.HOSTEL ROAD IN DIVISION DIV- 107, UNIT - 23, ZONE - 8 (REACH-1,MC NICHOLS ROAD TO DOOR NO:64)",Deposit Works,8,2016-17,2017-18 NH/2016-17/1606,Road Cut,Completed,NH-ANNA NAGAR,107,400000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT DOSSPURAM AND VARIOUS STREETS IN DIVISION - 107, UNIT - 23, ZONE - 8",Deposit Works,8,2016-17,2017-18 NH/2016-17/16744,Buildings,Completed,NH-ANNA NAGAR,107,387000,"REPAIRS AND MAINTENANCE WORK OF PARK AND PLAY GROUND AT VARIOUS LOCATION IN DIV -107,U-23, Z-8",Own Sources,8,2016-17,2017-18 NH/2016-17/16893,Buildings,Completed,NH-ANNA NAGAR,107,263000,"REPAIRS AND MAINTANANCE WORK OF MANAGALAPURAM AMMA UNAVAGAM VENKATCHALAPATHI STREET AMMAUNAVAGAM , JAGANATHAPURAM 2ND STREET HEALTH CENTRE AND DIVISION OFFICE BUILDING IN DN -107, UNIT -23, ZONE -8",Own Sources,8,2016-17,2017-18 NH/2016-17/16894,Buildings,Completed,NH-ANNA NAGAR,107,298000,"REPAIRS AND MAINTENANCE WORK OF MS NAGAR MIDDLE SCHOOL, MC NICHOLES ROAD SCHOOL AND JAGANATHA PURAM MIDDLE SCHOOL IN DIV -107, UNIT -23, ZONE -8",Own Sources,8,2016-17,2017-18 NH/2016-17/17009,Buildings,Completed,NH-ANNA NAGAR,107,966000,"CONSTRUCTION OF KITCHEN SHED AT SUBBRAYAN STREET C.H.S. SCHOOL IN DIV-107, U-23,Z-8. (MLA FUND)",MLACDS,8,2016-17,2018-19 NH/2016-17/17463,Buildings,Completed,NH-ANNA NAGAR,107,968000,"CONSTRUCTION OF KITCHEN SHED AT JAGANATHAN PURAM CHENNAI MIDDLE SCHOOL IN DIVISION 107, UNIT-23, ZONE-8 (MLA FUND)",MLACDS,8,2016-17,2018-19 NH/2016-17/17840,Buildings,Completed,NH-ANNA NAGAR,107,328000,IMPROVEMENT TO SUBURAYAN CHSS SCHOOL (AMMA UNDU URAVIDA PALLI) AND HOSTEL IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/17976,Buildings,Completed,NH-ANNA NAGAR,107,21000,"PROVIDING NAME BOARDS UPHC CENTER AT JAGANATHAPURAM AND MANGALAPURAM IN DIVISION - 107, UNIT-23, ZONE-8",Own Sources,8,2016-17,2018-19 NH/2016-17/1970,Road Cut,Completed,NH-ANNA NAGAR,107,472000,"Roadcut Restoration at MS Nagar1st, 2nd,3rd Street and Logambal Street in Dn-107, Unit-23, Zone-8",Deposit Works,8,2016-17,2016-17 NH/2016-17/3455,Roads,Completed,NH-ANNA NAGAR,107,319000,ATTENDING ROADCUT RESTORATION AT LOGAIYA STREET IN DN-104 UNIT -23 ZONE -8,Deposit Works,8,2016-17,2017-18 NH/2016-17/3456,Road Cut,Completed,NH-ANNA NAGAR,107,799000,"ATTENDING ROAD CUT RESTORATION AT JAGANATHAPURAM 1st, 2nd & SRINIVASAN STREET IN DN-107 UNIT -23 ZONE -8",Deposit Works,8,2016-17,2016-17 NH/2016-17/3458,Road Cut,Completed,NH-ANNA NAGAR,107,800000,"ATTENDING ROAD CUT RESTORATION AT V.R.R COLONY, MURUGESAN STREET, M.S NAGAR 3rd MAIN ROAD IN -DN-107 UNIT -23 ZONE -8",Deposit Works,8,2016-17,2016-17 NH/2016-17/3459,Road Cut,Completed,NH-ANNA NAGAR,107,799000,"ATTENDING ROAD CUT RESTORATION AT MANGALAPURAM 4th,12th,13th,&14th STREETIN DN-107 UNIT-23 ZONE -8",Deposit Works,8,2016-17,2016-17 NH/2016-17/3460,Road Cut,Completed,NH-ANNA NAGAR,107,517000,ATTENDING ROAD CUT RESTORATION AT RAJAMMAL STREET IN DN-107 UNIT-23 ZONE -8,Deposit Works,8,2016-17,2016-17 NH/2016-17/3729,Roads,Completed,NH-ANNA NAGAR,107,398000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT P.C.HOSTEL ROAD IN DIV - 107, UNIT - 23, ZONE - 8 (REACH-2 DOOR NO:64 TO DOOR NO:36 )",Deposit Works,8,2016-17,2017-18 NH/2016-17/3834,Road Cut,Completed,NH-ANNA NAGAR,107,199000,RESTORATION OF ROAD CUT MADE CMWSSB AT P.C.HOSTEL ROAD IN DIV-107 UNIT-23 ZONE-8 (REACH-3 DOOR NO:36 TO DOOR NO:24),Deposit Works,8,2016-17,2017-18 NH/2016-17/3838,Roads,Completed,NH-ANNA NAGAR,107,362000,PROVIDING OF SECURITY GUARDS FOR MAYOR SATHYA MURTHY PARK IN MAYOR SATHYA MURTHY SALAI IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/3839,Roads,Completed,NH-ANNA NAGAR,107,950000,Annual Maintenance of Mayor Sathyamurthy Park in Mayor Sathyamurthy salai and Mayor Ramanathan children park in mayor Ramanatha salai at Div-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/4210,Road Cut,Completed,NH-ANNA NAGAR,107,345000,ROAD CUT RESTORATION MANGALA PURAM 6TH STREET AND MANGALA PURAM 18TH STREET MANGALA PURAM 11TH STREET IN DIV-107 U-23 Z-8,Deposit Works,8,2016-17,2017-18 NH/2016-17/4211,Storm Water Drain,Completed,NH-ANNA NAGAR,107,320000,DESILTING HARRINGTON ROAD SUBWAY WELL REPAIR DIESEL MOTOR ELECTRICAL MOTOR SUB MERGABLE MOTOR IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2016-17 NH/2016-17/4213,Road Cut,Completed,NH-ANNA NAGAR,107,300000,ROAD CUT RESTORATION JAGANATHAN PURAM 5TH STREET AND JAGANATHAN PURAM 6THSTREET IN DIV-107 U-23 Z-8,Deposit Works,8,2016-17,2017-18 NH/2016-17/5248,Storm Water Drain,Completed,NH-ANNA NAGAR,107,990000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-107 UNIT-23 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/5306,Storm Water Drain,Completed,NH-ANNA NAGAR,107,995000,DESILTING OF STORM WATER DRAIN DHANAMMAL STREET AND VARIOUS STREETS IN DIV-107 UNIT-23 ZONE-8,Own Sources,8,2016-17,2017-18 NH/2016-17/6413,Buildings,Completed,NH-ANNA NAGAR,107,470000,IMPROVEMENT TO TOILET AND BATH ROOM CHS SCHOOL AT SCHOOL ROAD IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2016-17 NH/2016-17/6508,Buildings,Completed,NH-ANNA NAGAR,107,389000,"PROVIDING E TOILET AT CHARI STREET IN DN 107,UNIT 23,ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/6527,Buildings,Completed,NH-ANNA NAGAR,107,399000,"PROVIDING WATER SUPPLY,DRAINAGE,ELECTRICAL AND GREENARY WORK FOR E TOILET AT CHARI STREET IN DN 107,UNIT 23,ZONE 8",Own Sources,8,2016-17,2016-17 NH/2016-17/6537,Buildings,Completed,NH-ANNA NAGAR,107,244000,NEW CONSTRUCTION S W D R C C DRAIN AT MC NICHOLS SERVICE ROAD(SCHOOL SIDE) IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2016-17 NH/2016-17/9010,Buildings,Completed,NH-ANNA NAGAR,107,126000,PROVIDING WATER TABLE ARRANGMENT AT MCNICALS ROAD IN DIV 107 U 23 Z 8,Own Sources,8,2016-17,2016-17 NH/2016-17/9696,Roads,Completed,NH-ANNA NAGAR,107,730000,PROVIDING AND LAYING OF CEMENT CONCRETE ROAD AT M.S. NAGAR 1st MAIN STREET IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/9720,Roads,Completed,NH-ANNA NAGAR,107,880000,PROVIDING AND LAYING OF CEMENT CONCRETE ROAD AT M.S.NAGAR 2ND MAIN STREET IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/9737,Roads,Completed,NH-ANNA NAGAR,107,1190000,PROVIDING AND LAYING OF CEMENT CONCRETE ROAD MURUGESAN STREET IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/9742,Roads,Completed,NH-ANNA NAGAR,107,470000,PROVIDING AND LAYING OF CEMENT CONCRETE ROAD LOGAIYAH STREET IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/9745,Roads,Completed,NH-ANNA NAGAR,107,295000,PROVIDING AND LAYING OF CEMENT CONCRETE ROAD LOGAMMBAL STREET IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/9752,Roads,Completed,NH-ANNA NAGAR,107,560000,PROVIDING AND LAYING OF CEMENT CONCRETE ROAD AT SRINIVASAN STREET IN DIV-107 U-23 Z-8,Own Sources,8,2016-17,2017-18 NH/2016-17/0584,Buildings,Completed,NH-ANNA NAGAR,108,324000,"PROVIDING RAIN WATER HARVESTING AT GANDHI ROAD,SELVA VINAYAGAR KOIL STREET IN DN-108,U-22,Z-8",Own Sources,8,2016-17,2018-19 NH/2016-17/10762,Roads,Completed,NH-ANNA NAGAR,108,398000,"ATTENDING PATCH WORK AT INDIRAGANDHI 2ND STREET AND VIJESHWARI STREET APPROACH IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/10908,Storm Water Drain,Completed,NH-ANNA NAGAR,108,388000,"DISMANTLING AND RECONSTRUCTION OF STROM WATER DRAIN AT PASUMPON STREET R-BLOCK IN DIVISION-108,UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/10915,Storm Water Drain,Completed,NH-ANNA NAGAR,108,396000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT WATER TANK ROAD FROM NEW NATARAJA PURAM TO POSUMPON STREET R BLOCK IN DIVISION-108,UNIT-22, ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/10921,Storm Water Drain,Completed,NH-ANNA NAGAR,108,391000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT MARAIMALAIADIGAL STREET ( FROM PASUMPON STREET R-BLOCK TO J.T DURAIRAJ NAGAR 8TH STREET) IN DIVISION-108,UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/10923,Storm Water Drain,Completed,NH-ANNA NAGAR,108,383000,"DISMANTLING AND RECONSTRUCTION OF STROM WATER DRAIN AT J.T.DURAIRAJ NAGAR 8TH STREET FROM PASUMPON STREET Q-BLOCK TO J.T DURAIRAJ NAGAR 5TH STREET IN DIVISION-108,UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/11165,Buildings,Completed,NH-ANNA NAGAR,108,370000,"PROVIDING WATER SUPPLY AND DRAINAGE ARRANGEMENTS II PHASE AMMA UNAVAGAM AT SIDCO STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2016-17,2017-18 NH/2016-17/12532,Storm Water Drain,Completed,NH-ANNA NAGAR,108,290000,"LAYING OF CC ROAD AZHAD NAGAR CROSS STREET FROM AZHAD NAGAR 2ND STREET TO M.H COLONY IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/13127,Roads,Completed,NH-ANNA NAGAR,108,250000,"ATTENDING PATCH WORK AND PROVIDING MANHOLE DOORS AT VARIOUS STREET IN DN-108,U-22,Z-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/13128,Buildings,Completed,NH-ANNA NAGAR,108,135000,"IMPROVEMENT TO PUBLIC TOILET AT MMDA BUS TERMINALS IN DN-108,U-22,Z-8",Own Sources,8,2016-17,2018-19 NH/2016-17/13312,Buildings,Completed,NH-ANNA NAGAR,108,58000,"PROVIDING NAME BOARD TO E-SEVA CENTRE AT M.G.R 3RD STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/14456,Buildings,Completed,NH-ANNA NAGAR,108,179000,"PROVIDING FACE LIFTING FOR TRANSFORMERS AT VARIOUS STREETS IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/14457,Buildings,Completed,NH-ANNA NAGAR,108,234000,"IMPROVEMENTS TO THE TOILET BLOCK AT N-BLOCK CHS BHAGATH SINGH 2ND STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2018-19 NH/2016-17/14476,Buildings,Completed,NH-ANNA NAGAR,108,288000,"REPAIRS AND IMPROVEMENTS TO CHS N-BLOCK SCHOOL AT BHAGATH SINGH 2ND STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2016-17,2017-18 NH/2016-17/14485,Buildings,Completed,NH-ANNA NAGAR,108,278000,"REPAIRS AND IMPROVEMENTS TO O BLOCK SCHOOL AT BHAGATH SINGH STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2016-17,2016-17 NH/2016-17/1691,Buildings,Completed,NH-ANNA NAGAR,108,400000,"PROVIDING INLET CHAMBER WITH PIPE LINING FOR STROM WATER DRAIN AT SUBRAMANIAM STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/1692,Buildings,Completed,NH-ANNA NAGAR,108,400000,"PROVIDING INLET CHAMBER WITH PIPE LINING FOR STROM WATER DRAIN AT KANNIAPPAN STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/1694,Buildings,Completed,NH-ANNA NAGAR,108,400000,"PROVIDING INLET CHAMBER WITH PIPE LINING FOR STROM WATER DRAIN AT PERIYARPATHAI IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/1730,Buildings,Completed,NH-ANNA NAGAR,108,45000,IMPROVMENT TO TAX COLLOCTER ROOM @ M.G.R STREET IN DN 108 U 22 Z 8,Own Sources,8,2016-17,2016-17 NH/2016-17/17422,Buildings,Completed,NH-ANNA NAGAR,108,325000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREET IN DN-108,U-22,Z-8",Own Sources,8,2016-17,2018-19 NH/2016-17/17833,Buildings,Completed,NH-ANNA NAGAR,108,100000,"PROVIDING RETAINING WALL AT KAMARAJAR CROSS STREET IN DN-108,U-22,Z-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/18026,Roads,Completed,NH-ANNA NAGAR,108,115000,"REPAIR AND IMPROVEMENT TO R BLOCK PARK IN DN-108,UNIT-22,Z-8 .",Own Sources,8,2016-17,2018-19 NH/2016-17/18228,Roads,Completed,NH-ANNA NAGAR,108,400000,"LAYING OF CC ROAD AT AZHAD NAGAR CROSS STREET FROM COLLECTOR COLONY 6TH CROSS STREET TO AZHAD NAGAR IST STREET IN DN.108, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/18247,Roads,Completed,NH-ANNA NAGAR,108,383000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT WATER TANK ROAD ( FROM RAZAKGARDEN MAIN ROAD TO NEW NATARAJAPURAM) RIO R-BLOCK IN DIVISION-108,UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/3317,Storm Water Drain,Completed,NH-ANNA NAGAR,108,150000,"Repair work to storm water drain at Kamaraja nagar 4th street (Junction of N.G.O.clony 4th street) and Loganatha nagar 3rd street (Junction of 100feet road) in Division-108, Unit-22, Zone-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/3440,Buildings,Completed,NH-ANNA NAGAR,108,48000,REPAIR WORK TO TOILET @ MMDA COLONY IN DN 108 U 22 Z 8,Own Sources,8,2016-17,2016-17 NH/2016-17/4953,Buildings,Completed,NH-ANNA NAGAR,108,175000,"PROVIDING INLET CHAMBER WITH PIPE LINING FOR STROM WATER DRAIN AT SUBRAMANIAM STREET,IN DN-108,U-22,Z-8.",Own Sources,8,2016-17,2018-19 NH/2016-17/5002,Storm Water Drain,Completed,NH-ANNA NAGAR,108,980000,"DESELTING OF VIRUGAMBAKKAM RIVER FROM METRO RAIL TO THAMILAR VEEDHI IN DN.108, UNIT.22, ZONE.8 (USING FLOAT MACHINERIES MOUNTED)",Own Sources,8,2016-17,2016-17 NH/2016-17/5007,Storm Water Drain,Completed,NH-ANNA NAGAR,108,995000,"DESILTING OF VIRUGAMBAKKAM RIVER FROM THAMILAR VEEDGI TO VINOBAJI STREET IN DN.108, UNIT.22, ZONE.8 (USING FLOAT MOUNTED MACHINARIES)",Own Sources,8,2016-17,2016-17 NH/2016-17/5008,Storm Water Drain,Completed,NH-ANNA NAGAR,108,999000,"DESILTING OF VIRUGAMBAKKAM RIVER FROM VINOBAJI STREET TO AZAD NAGAR 2ND STREET IN DN.108, UNIT.22, ZONE.8 (USING FLOAT MOUNTED MACHINARIES)",Own Sources,8,2016-17,2016-17 NH/2016-17/5166,Storm Water Drain,Completed,NH-ANNA NAGAR,108,999000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN.108, UNIT.22 ZONE.8",Own Sources,8,2016-17,2017-18 NH/2016-17/5182,Storm Water Drain,Completed,NH-ANNA NAGAR,108,990000,"DESILTING OF STORM WATER DRAIN AT PERIYARPATHAI IN.108, UNIT.22, ZONE.8",Own Sources,8,2016-17,2017-18 NH/2016-17/6179,Buildings,Completed,NH-ANNA NAGAR,108,998000,"PROVIDING STREET NAME BOARD AT VARIOUS STREETS IN DIVISION-108, UNIT-22, ZONE-8. (COUNCILLOR FUND 16-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/6180,Electrical,Completed,NH-ANNA NAGAR,108,407000,"IMPROVEMENTS GYM & PLAY AREA TO PROVIDING GYM EQUIPMENTS AT R-BLOCK IN DIVISION-108, UNIT-22, ZONE-8 (UNDER COUNCILLOR FUND 16-17).",Own Sources,8,2016-17,2018-19 NH/2016-17/6181,Buildings,Completed,NH-ANNA NAGAR,108,995000,"LAYING CEMENT CONCRETE ROAD NEAR VIRUGAMBAKKAM CANAL @ TAMILARVEETHI & KO.SU. MANI STEET AND KO.SU.MANI STEET & INDIRA GANDHI STREETCONNECTED PASSAGES IN DN-108,UNIT-22, ZONE-8 (COUNCILLOR FUND 16-17)",Own Sources,8,2016-17,2017-18 NH/2016-17/6182,Buildings,Completed,NH-ANNA NAGAR,108,203000,"IMPROVEMENT TO GRANITE FOOT PATH AT SBI COLONY 1ST STREET,2ND STREET,VASUGI STREET,IN DN-105,UNIT-22,ZONE-8",Own Sources,8,2016-17,2017-18 NH/2016-17/6295,Roads,Completed,NH-ANNA NAGAR,108,600000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT KANNAGI STREET (PARTLY) IN DIVISION-108, UNIT-22, ZONE-8. (COUNCILOR FUND 2016-17)",Own Sources,8,2016-17,2016-17 NH/2016-17/7311,Roads,Completed,NH-ANNA NAGAR,108,700000,"LAYING OF CC ROAD AT AZHAD NAGAR LANE - MOSQUE STREET IN DN.108, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/7314,Roads,Completed,NH-ANNA NAGAR,108,990000,"LAYING OF CC ROAD AT AZHAD NAGAR 1ST STREET (CH. 0 TO 105 MTR) IN DN.108, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/7318,Roads,Completed,NH-ANNA NAGAR,108,950000,"LAYING OF CC ROAD AT AZHAD NAGAR 1ST STREET (CH. 105 TO 202 MTR.) IN DN.108, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/7325,Roads,Completed,NH-ANNA NAGAR,108,810000,"LAYING OF CC ROAD AT AZHAD NAGAR 1ST STREET (FROM COLLECTOR NAGAR 6TH CROSS STREET TO AZHAD NAGAR 1ST STREET) IN DN.108, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2017-18 NH/2016-17/7431,Roads,Completed,NH-ANNA NAGAR,108,915000,"LAYING OF CC ROAD AT PASUMPON P BLOCK STREET IN DN.108, UNIT-22, ZONE-08.",Own Sources,8,2016-17,2016-17 NH/2016-17/7573,Buildings,Completed,NH-ANNA NAGAR,108,390000,"PROVIDING ELECTRICAL ARRANGEMENTS II PHASE AMMA UNAVAGAM AT SIDCO STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2016-17,2017-18 NH/2016-17/7974,Buildings,Completed,NH-ANNA NAGAR,108,850000,"PROPOSED CONSTRUCTION OF II PHASE AMMA UNAVAGAM AT SIDCO STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2016-17,2017-18 NH/2016-17/7975,Storm Water Drain,Completed,NH-ANNA NAGAR,108,399000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT J.T.DURAIRAJ NAGAR 8TH STREET (FROM J.T DURAIRAJ NAGAR 5TH STREET TO CANAL) IN DIVISION-108,UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/9162,Roads,Completed,NH-ANNA NAGAR,108,245000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT ELANGO STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9164,Roads,Completed,NH-ANNA NAGAR,108,920000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT KANNAGI STREET (PART) IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9165,Roads,Completed,NH-ANNA NAGAR,108,980000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT VALLALAR STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9166,Roads,Completed,NH-ANNA NAGAR,108,980000,"RELAYING THE ROAD WITH BCCMP 30mm THICK BY PAVER FINISHER AT VINOBAJI STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2016-17 NH/2016-17/9673,Roads,Completed,NH-ANNA NAGAR,108,520000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT THIRU.VI.KA STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/9674,Roads,Completed,NH-ANNA NAGAR,108,382000,"LAYING CC ROAD IN AZHAD NAGAR CROSS STREET NEAR CANAL FROM IST STREET TO DEAD END IN DN-108,UNIT-22,Z-8",Own Sources,8,2016-17,2016-17 NH/2016-17/9675,Buildings,Completed,NH-ANNA NAGAR,108,399000,"PROVIDING WATER SUPPLY AND DRAINGE ARRANGEMENTS TO THIRD FLOOR TOILET BLOCK INSIDE THE N BLOCK SCHOOL AT BHGATH SINGH 2ND STREET IN DN.108, UNIT.22, ZONE.8",Own Sources,8,2016-17,2017-18 NH/2016-17/9679,Roads,Completed,NH-ANNA NAGAR,108,118000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT THIRU.VI.KA LANE IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/9680,Roads,Completed,NH-ANNA NAGAR,108,995000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT RAMASAMIRAJA STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/9709,Roads,Completed,NH-ANNA NAGAR,108,2100000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT AZAD NAGAR 2ND STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NH/2016-17/9715,Bridges,Completed,NH-ANNA NAGAR,108,400000,"LAYING CEMENT CONCRETE ROAD WITH RMC-30 AT VEERAPANDI NAGAR 4TH STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2016-17,2017-18 NJ/2016-17/10004,Roads,Completed,NJ-TEYNAMPET,109,170000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT NARAYANAPIRAM 1 ST STREET IN DIVISION -109,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/11009,Buildings,Completed,NJ-TEYNAMPET,109,950000,"PROPOSED CONSTRUCTION OF RATION SHOP BUILDING (UNDER M.L.A FUND) AT WEST NAMACHIVAYA PURAM IN DN 109,UNIT 24,ZONE 9",MLACDS,9,2016-17,2018-19 NJ/2016-17/13892,Buildings,Completed,NJ-TEYNAMPET,109,69000,"IMPROVEMENTS AND REPAIRS TO COMMUNITY TOILET AT WEST NAMACHIVAYA PURAM IN DIVISION-109,UNIT-24,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14219,Buildings,Completed,NJ-TEYNAMPET,109,55000,"IMPROVEMENTS AND REPAIRS TO CPS & CHS SCHOOL ,SANKARAPURAM/THIRUVALLUVARPURAM IN DIV 109,U 24,Z 9",Own Sources,9,2016-17,2019-20 NJ/2016-17/14325,Storm Water Drain,Completed,NJ-TEYNAMPET,109,910000,CONSTRUCTION OF RETAINING WALL AT THIRUVALLUVAR PURAM 1ST STREET AND THIRUVENKATAPURAM 2ND STREET CROSSING EAST SIDE OF TRUSTPURAM CANAL (UNDER M.L.A FUND) IN DN-109 UNIT-24 ZONE-09,MLACDS,9,2016-17,2018-19 NJ/2016-17/15739,Buildings,Completed,NJ-TEYNAMPET,109,534000,"DISMANTLING AND RE-CONSTRUCTION OF EXISTING COMPOUND WALL IN CHENNAI PRIMARY SCHOOL AT NAMACHIVAYAPURAM MAIN ROAD BY VARDA CYCLONE IN DIVISION - 109,UNIT-24,ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/16509,Buildings,Completed,NJ-TEYNAMPET,109,102000,"DISMANTLING AND RE-CONSTRUCTION OF DAMAGED COMPOUND WALL BY VARTHA CYCLONE AT SHANMUGANAR SALAI DIVISION-109 OFFICE IN DIVISION - 109,UNIT-24,ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/16540,Buildings,Completed,NJ-TEYNAMPET,109,250000,Repairs to Gill Nagar Park Affected by vartha cyclone in Dn-109 Unit-24 Zone-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16567,Buildings,Completed,NJ-TEYNAMPET,109,300000,REPAIR AND IMPROVEMENTS TO HOSPITAL BUILDING AFFECTED BY VARTHA CYCLONE AT SHERFUDHEEN STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16582,Storm Water Drain,Completed,NJ-TEYNAMPET,109,100000,REPAIRS TO STORM WATER DRAIN AFFECTED BY VARTHA CYCLONE IN ARTHAREYAPURAM MAIN ROAD AND VARIOUS STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/17874,Footpath,Completed,NJ-TEYNAMPET,109,310000,"REPAIRS AND IMPROVEMENTS TO FOOT PATH AFFECTED BY VARTHA CYCLONE AT GILL NAGAR IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/1829,Buildings,Completed,NJ-TEYNAMPET,109,846000,"IMPROVEMENTS TO GYM BUILDING AT EAST NAMACHIVAYAPURAM IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/1839,Storm Water Drain,Completed,NJ-TEYNAMPET,109,982000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT SHANMUGANAR SALAI ROAD CROSSING PORTION JUNCTION OF GILL NAGAR 1ST STREET AND SAKTHI NAGAR 2ND STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2095,Storm Water Drain,Completed,NJ-TEYNAMPET,109,348000,DE-SILTING OF STORM WATER DRAIN AT ABDULLAH STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2096,Storm Water Drain,Completed,NJ-TEYNAMPET,109,559000,DE-SILTING OF STORM WATER DRAIN AT NELSON MANICKAM ROAD (BOTH SIDE) IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2097,Storm Water Drain,Completed,NJ-TEYNAMPET,109,104000,DE-SILTING OF STORM WATER DRAIN AT VANNIAR 2ND STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2098,Storm Water Drain,Completed,NJ-TEYNAMPET,109,137000,DE-SILTING OF STORM WATER DRAIN AT ABITH NAGAR IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2099,Storm Water Drain,Completed,NJ-TEYNAMPET,109,119000,DE-SILTING OF STORM WATER DRAIN AT SANKARAPURAM MAIN ROAD IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2100,Storm Water Drain,Completed,NJ-TEYNAMPET,109,211000,DE-SILTING OF STORM WATER DRAIN AT THIRUVALLUVARPURAM 2ND STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2101,Storm Water Drain,Completed,NJ-TEYNAMPET,109,346000,DE-SILTING OF STORM WATER DRAIN AT GILL NAGAR 1ST STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2103,Storm Water Drain,Completed,NJ-TEYNAMPET,109,191800,DE-SILTING OF STORM WATER DRAIN AT THIRUVENGADAPURAM 1 ST STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2105,Storm Water Drain,Completed,NJ-TEYNAMPET,109,141000,DE-SILTING OF STORM WATER DRAIN AT NAMACHIVAYAPURAM IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2106,Storm Water Drain,Completed,NJ-TEYNAMPET,109,515000,"IMPROVEMENTS & REPAIRS TO GYM BUILDING IN GILL NAGAR PLAY GROUND AT GILL NAGAR CENTRAL SCHOOL ROAD IN DIVISION-109,UNIT-24,ZONE-IX.",Own Sources,9,2016-17,2018-19 NJ/2016-17/4923,Buildings,Completed,NJ-TEYNAMPET,109,994000,"Proposed fixing of Street Name Board using Stainless Steel Pipe and Retro Reflective Streets at Sankarapuram 3rd Street, Atherayapuram Main road, Radhakrishnapuram 1st Street,2nd Street,3rd Street,Arunachalam 1st Street,2nd Street, SBI Officers Colony ,Sakthi Nagar 3rd Street, Chella Vinayagar Street , Sree Ramapuram 1st Street 2nd Street, Vannier 1st lane, 2nd lane, Jothi Ramalingam Street, Bajanai Koil Street 1st Street , Bajanai Koil Street 1st lane ,Thiruvenkadapuram Main Road,, Thiruvalluvarpuram 1st Street,2nd Street,Bajanai Koil New Street , Raghavan Street, Kandappan Street,Bajanai Koil 4th Street, Bajanai Koil Street 5th Street, Bajanai Koil 6th Street ,Bajanai Koil 7th Street Thiru-vi-ka Colony 1st Street,2nd Street and 3rd Streets (Under Ward Councillor Scheme ) in Dn 109, unit-24 Zone- 09",Own Sources,9,2016-17,2019-20 NJ/2016-17/7533,Storm Water Drain,Completed,NJ-TEYNAMPET,109,223000,"DE-SILTING OF STORM WATER DRAIN AT THIRUVNGADAPURAM MAIN ROAD IN DIV 109,U-24,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/7539,Storm Water Drain,Completed,NJ-TEYNAMPET,109,136000,"DE-SILTING OF STORM WATER DRAIN VADA AGARAM IN DN -109,UNIT-24 ZONE -9",Own Sources,9,2016-17,2017-18 NJ/2016-17/7541,Storm Water Drain,Completed,NJ-TEYNAMPET,109,375000,"DE-SILTING OF STORM WATER DRAIN THIRUVALLUVAPURAM 1ST STREET IN DN -109,UNIT-24, Z -09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7547,Storm Water Drain,Completed,NJ-TEYNAMPET,109,104000,DE-SILTING OF STORM WATER DRAIN AT SANKARAPURAM 3RD STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/7548,Storm Water Drain,Completed,NJ-TEYNAMPET,109,63000,DE-SILTING OF STORM WATER DRAIN AT SANKARAPURAM 1ST STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/7550,Storm Water Drain,Completed,NJ-TEYNAMPET,109,45000,DE-SILTING OF STORM WATER DRAIN AT SANKARAPURAM 4TH STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/7552,Storm Water Drain,Completed,NJ-TEYNAMPET,109,35000,DE-SILTING OF STORM WATER DRAIN AT SAKTHI NAGAR 3RD STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/7557,Storm Water Drain,Completed,NJ-TEYNAMPET,109,74000,DE-SILTING OF STORM WATER DRAIN AT SAKTHI NAGAR 5TH STREET IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/7608,Storm Water Drain,Completed,NJ-TEYNAMPET,109,853000,DE-SILTING OF STORM WATER DRAIN AT ANNA NEDUM PATHAI IN DN-109 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/9965,Roads,Completed,NJ-TEYNAMPET,109,218000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT SRIRAMAPURAM 1ST STREET IN DIVISION-109 UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9967,Roads,Completed,NJ-TEYNAMPET,109,128000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT SRIRAMAPURAM 2 ND STREET IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9970,Roads,Completed,NJ-TEYNAMPET,109,102000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT SRI RAMAPURAM 1 ST LANE IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9972,Roads,Completed,NJ-TEYNAMPET,109,235000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT VENKATESHWARA LANE IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9996,Roads,Completed,NJ-TEYNAMPET,109,418000,"RELAYING OFV ROAD WITH BCCMP 30 MM THICK AT NARAYANAPURAM MAIN ROAD IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 BR/2016-17/17717,Roads,Completed,BR-Bus Route Roads,110,767000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Thiru Vi Ka High Road, Tank Bund Road, College Road, Uthamar Gandhi salai and Dr.M.G.R.Salai in Dn-114 & 116, Zone-9",Grants,9,2016-17,2017-18 BR/2016-17/18788,Roads,Completed,BR-Bus Route Roads,110,199000,Providing and laying of ramp for existing bus shelters at various Bus Route Roads in zone - 9,Own Sources,9,2016-17,2018-19 BR/2016-17/19013,Roads,Completed,BR-Bus Route Roads,110,199000,Providing and laying of ramp for existing bus shelters at various Bus Route Roads in zone - 9,Own Sources,9,2016-17,2018-19 BR/2016-17/19181,Road Cut,Completed,BR-Bus Route Roads,110,1693000,"Restoration of road cut made by TANGEDCO at Mahalingapuram Main road from Lyola College Sub Station to Tank Bund Road in Dn - 110, Zone - 9 (Chellan No; BR/2015-16/0018665)",Deposit Works,9,2016-17,2017-18 BR/2016-17/19184,Road Cut,Completed,BR-Bus Route Roads,110,1864000,"Restoration of road cut made by TANGEDCO at Nelson Manickam Road from the jn of Tank Bund Road to Lyola College Gate in Dn - 110, Zone - 9 (Chellan No; BR/2015-16/0018665)",Deposit Works,9,2016-17,2017-18 BR/2016-17/19185,Road Cut,Completed,BR-Bus Route Roads,110,1863000,"Restoration of road cut made by TANGEDCO at Nelson Manickam Road from the jn of Lyola College Gate to Subwayin Dn - 110, Zone - 9 (Chellan No; BR/2015-16/0018665)",Deposit Works,9,2016-17,2017-18 BR/2016-17/4418,Roads,Completed,BR-Bus Route Roads,110,890000,Supplying and fixing of Front facia & back drop in the 70 nos existing Modern stainless steel bus shelters in Zone -9,Own Sources,9,2016-17,2017-18 NJ/2016-17/10934,Buildings,Completed,NJ-TEYNAMPET,110,318000,DEMOLISHING OF OLD CLASS ROOM BUILDING (SOUTH WEST CORNER) AT CHENNAI MIDDLE SCHOOL JAYALAKSHMI PURAM MAIN ROAD IN DIVISION 110 UNIT 24 ZONE 09,Own Sources,9,2016-17,2018-19 NJ/2016-17/12013,Buildings,Completed,NJ-TEYNAMPET,110,998000,"Installation,Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at Valluvar Kottam High Road Junction of Tank Bund road in Dn 110,Unit-26, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13519,Roads,Completed,NJ-TEYNAMPET,110,735000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT MADHAVAN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/13521,Roads,Completed,NJ-TEYNAMPET,110,945000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT SIR MADHAVAN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/13809,Buildings,Completed,NJ-TEYNAMPET,110,45000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT APPASAMY STREET 6TH AVENUE IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13810,Buildings,Completed,NJ-TEYNAMPET,110,34000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT APPASAMY STREET 7TH AVENUE IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13811,Buildings,Completed,NJ-TEYNAMPET,110,66000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT APPASAMY STREET NEAR CMS IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13813,Buildings,Completed,NJ-TEYNAMPET,110,37000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT JAYALAKSHMI PURAM 4TH STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13814,Buildings,Completed,NJ-TEYNAMPET,110,50000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT JAYALAKSHMI PURAM 2ND STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13818,Buildings,Completed,NJ-TEYNAMPET,110,18000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT SEETHA NAGAR 2ND STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13819,Buildings,Completed,NJ-TEYNAMPET,110,38000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT VALLUVAKOTTAM HIGH ROAD REAR SIDE OF INDYPENDENCE DAY PARK IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13820,Buildings,Completed,NJ-TEYNAMPET,110,29000,"IMPROVEMENTS TO PUBLIC CONVINIANCE AT LAKE AREA 1ST MAIN ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14003,Buildings,Completed,NH-ANNA NAGAR,110,46000,"IMPROVEMENTS TO PUBLIC CONVENIANCE AT KAMARAJAPURAM MAIN ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14237,Buildings,Completed,NJ-TEYNAMPET,110,174000,"IMPROVEMENTS AND REPAIRS TO CHENNAI MIDDLE SCHOOL AT APPASAMY STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15856,Storm Water Drain,Completed,NJ-TEYNAMPET,110,51000,"REPAIRS TO STORM WATER DRAIN AT THIRUMOORTHI NAGAR MAIN ROAD NEAR G.G.HOSPITAL IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16031,Parks,Completed,NJ-TEYNAMPET,110,330000,"REPAIRS AND IMPROVEMENTS TO INDEPENDENCE DAY PARK AT VALLUVAR KOTTAM HIGH ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16160,Storm Water Drain,Completed,NJ-TEYNAMPET,110,857000,"REPAIR AND IMPROVEMENTS TO STORM WATER DRAIN AT MAHALINGAPURAM MAIN ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16162,Storm Water Drain,Completed,NJ-TEYNAMPET,110,348000,"REPAIR AND IMPROVEMENTS TO STORM WATER DRAIN AT KAMDAR NAGAR MAIN ROAD IN DN 110,UNIT24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16166,Buildings,Completed,NJ-TEYNAMPET,110,885000,"CONSTRUCTION OF COMPOUND WALL FOR THE DAMAGED PORTION FOR CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16167,Buildings,Completed,NJ-TEYNAMPET,110,355000,"CONSTRUCTION OF COMPOUND WALL FOR DAMAGED PORTION AT ROAD SIDE PARK VALLUVARKOTTAM HIGH ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16168,Storm Water Drain,Completed,NJ-TEYNAMPET,110,227000,"REPAIR AND IMPROVEMENTS TO STORM WATER DRAIN AT APPASAMY STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16486,Buildings,Completed,NJ-TEYNAMPET,110,97000,"CONSTRUCTION OF COMPOUND WALL FOR DAMAGED PORTION AT GYM BUILDING APPASAMY STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16493,Buildings,Completed,NJ-TEYNAMPET,110,140000,"CONSTRUCTION OF COMPOUND WALL FOR DAMAGED PORTION AT PUSPHA NAGAR HEALTH POST IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17891,Buildings,Completed,NJ-TEYNAMPET,110,815000,"REPAIRS TO FOOT PATH AT VARIOUS STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17894,Footpath,Completed,NJ-TEYNAMPET,110,170000,"REPAIRS TO FOOTPATH AT POES GARDEN IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17901,Buildings,Completed,NJ-TEYNAMPET,110,151000,"IMPROVEMENTS AND REPAIRS TO CHENNAI PRIMARY SCHOOL AT KAMDAR NAGAR IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17902,Buildings,Completed,NJ-TEYNAMPET,110,13000,"IMPROVEMENTS AND REPAIRS TO CHENNAI MIDDLE SCHOOL AT JAYALAKSHMI PURAM MAIN ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17903,Buildings,Completed,NJ-TEYNAMPET,110,67000,"IMPROVEMENTS AND REPAIRS TO CHENNAI GIRLS HR.SEC.SCHOOL AT SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17904,Buildings,Completed,NJ-TEYNAMPET,110,121000,"IMPROVEMENTS AND REPAIRS TO CHENNAI BOYS HR.SEC.SCHOOL AT SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/19642,Buildings,Completed,NJ-TEYNAMPET,110,960000,"SUPPLYING OF EACH ONE OPERATOR AND ASSISTANT AT NUGAMBAKKAM BURIAL GROUND ELECTRICAL CREMATORIUM (FOR 1 YEAR) IN DIV-110,U-24,Z-9",Own Sources,9,2016-17,2019-20 NJ/2016-17/2125,Storm Water Drain,Completed,NJ-TEYNAMPET,110,150000,"De silting of storm water drain at Kamarajapuram 4th cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2126,Storm Water Drain,Completed,NJ-TEYNAMPET,110,61000,"Desilting of storm water drain at Valluvar kottam 1st cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2127,Storm Water Drain,Completed,NJ-TEYNAMPET,110,91000,"Desilting of storm water drain at Harrington road 6th avenue in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2129,Storm Water Drain,Completed,NJ-TEYNAMPET,110,91000,"Desilting of storm water drain at Harrington road 1st avenue in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2130,Storm Water Drain,Completed,NJ-TEYNAMPET,110,65000,"Desilting of storm water drain at Seetha nagar main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2132,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Avenue road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2133,Storm Water Drain,Completed,NJ-TEYNAMPET,110,65000,"Desilting of storm water drain at Jayalakshmipuram main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2134,Storm Water Drain,Completed,NJ-TEYNAMPET,110,63000,"Desilting of storm water drain at Jayalakshmipuram 1st street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2138,Storm Water Drain,Completed,NJ-TEYNAMPET,110,65000,"Desilting of storm water drain at Jayalakshmipuram 3rd street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2139,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Ponnnangipuram main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2143,Storm Water Drain,Completed,NJ-TEYNAMPET,110,65000,"Desilting of storm water drain at Valluvar kottam high road from Mayor Shiva Shanmugam salai to Police Quarters in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2145,Storm Water Drain,Completed,NJ-TEYNAMPET,110,115000,"Desilting of storm water drain at Valluvar kottam high road from Uthamar Gandhi salai to Melpadi Muthu street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2146,Storm Water Drain,Completed,NJ-TEYNAMPET,110,53000,"Desilting of storm water drain at Harrington road 4th avenue in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2151,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Sterling road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2152,Storm Water Drain,Completed,NJ-TEYNAMPET,110,54000,"Desilting of storm water drain at Tank Bund road 2nd street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2154,Storm Water Drain,Completed,NJ-TEYNAMPET,110,52000,"Desilting of storm water drain at Tank Bund road 1st street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2155,Storm Water Drain,Completed,NJ-TEYNAMPET,110,65000,"Desilting of storm water drain at Sterling Avenue in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2156,Storm Water Drain,Completed,NJ-TEYNAMPET,110,151000,"Desilting of storm water drain at Tank Bund road from Mahalinga puram main road to Loyola college in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2157,Storm Water Drain,Completed,NJ-TEYNAMPET,110,60000,"Desilting of storm water drain at Kothari road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2158,Storm Water Drain,Completed,NJ-TEYNAMPET,110,119000,"Desilting of storm water drain at Kakkan colony 1st and 4th streett in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2160,Storm Water Drain,Completed,NJ-TEYNAMPET,110,82000,"Desilting of storm water drain at Pushpa nagar 2nd street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2161,Storm Water Drain,Completed,NJ-TEYNAMPET,110,55000,"Desilting of storm water drain at Pushpa nagar 1st street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2162,Storm Water Drain,Completed,NJ-TEYNAMPET,110,55000,"Desilting of storm water drain at Pushpa nagar main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2164,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Vaikundapuram 6th cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2165,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Vaikunadpuram 5th cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2167,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Vaikundapuram 4th cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2168,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Vaikungapuram 3rd cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2169,Storm Water Drain,Completed,NJ-TEYNAMPET,110,61000,"Desilting of storm water drain at Kamarajapuram 1st main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2170,Storm Water Drain,Completed,NJ-TEYNAMPET,110,55000,"Desilting of storm water drain at Vaikundapuram 1st cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2171,Storm Water Drain,Completed,NJ-TEYNAMPET,110,49000,"Desilting of storm water drain at Vaikundapuram 2nd street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2172,Storm Water Drain,Completed,NJ-TEYNAMPET,110,91000,"Desilting of storm water drain at Vaikundapuram 2nd street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2173,Storm Water Drain,Completed,NJ-TEYNAMPET,110,150000,"Desilting of storm water drain at Vaikundapuram 1st street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2175,Storm Water Drain,Completed,NJ-TEYNAMPET,110,129000,"Desilting of storm water drain at Kamarajapuram main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2176,Storm Water Drain,Completed,NJ-TEYNAMPET,110,61000,"Desilting of storm water drain at Lake area 6th cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2177,Storm Water Drain,Completed,NJ-TEYNAMPET,110,80000,"Desilting of storm water drain at Lake area 5th cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2178,Storm Water Drain,Completed,NJ-TEYNAMPET,110,55000,"Desilting of storm water drain at Lake area 4th cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2179,Storm Water Drain,Completed,NJ-TEYNAMPET,110,84000,"Desilting of storm water drain at Lake area 3rd cross street in Dn: 110, Unit: 24, Zone: 24",Own Sources,9,2016-17,2017-18 NJ/2016-17/2180,Storm Water Drain,Completed,NJ-TEYNAMPET,110,84000,"Desilting of storm water drain at Lake area 1 st cross street in Dn: 110, Unit: 24, Zone; 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2181,Storm Water Drain,Completed,NJ-TEYNAMPET,110,84000,"Desilting of storm water drain at Lake area 2nd cross street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2182,Storm Water Drain,Completed,NJ-TEYNAMPET,110,176000,"Desilting of storm water drain at Lake area 1st main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2184,Storm Water Drain,Completed,NJ-TEYNAMPET,110,116000,"Desilting od storm water drain at School road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2185,Storm Water Drain,Completed,NJ-TEYNAMPET,110,63000,"Desilting of storm water drain at School road 2nd street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2188,Storm Water Drain,Completed,NJ-TEYNAMPET,110,99000,"Desilting of storm water drain at 40' Scheme road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2189,Storm Water Drain,Completed,NJ-TEYNAMPET,110,84000,"Desilting of storm water drain at Kamdar nagar 3rd street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2191,Storm Water Drain,Completed,NJ-TEYNAMPET,110,87000,"Desilting of storm water drain at Kamdar nagar 1st street in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2192,Storm Water Drain,Completed,NJ-TEYNAMPET,110,86000,"Desilting of storm water drain at Kamdar Nagar main road in Dn: 110, Unit: 24, Zone 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2197,Storm Water Drain,Completed,NJ-TEYNAMPET,110,50000,"Desilting of storm water drain at 70' Scheme road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2198,Storm Water Drain,Completed,NJ-TEYNAMPET,110,297000,"Desilting of storm water drain at Tank Bund road from School road to Mahalinga puram main road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2199,Storm Water Drain,Completed,NJ-TEYNAMPET,110,85000,"Desilting of storm water drain at Valluvarkottam high road from Valluvar kottam East Gate to School road in Dn: 110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2200,Storm Water Drain,Completed,NJ-TEYNAMPET,110,102000,"Desilting of storm water drain at Kodambakkam high road service road-North in Dn:110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2201,Storm Water Drain,Completed,NJ-TEYNAMPET,110,50000,"Desilting of storm water drain at kodambakkam high road in Dn:110, Unit: 24, Zone: 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/3248,Parks,Completed,NJ-TEYNAMPET,110,150000,"IMPROVEMENTS TO PARK AT HARRINGTON ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3767,Storm Water Drain,Completed,NJ-TEYNAMPET,110,464000,"PROVIDING AND LAYING PIPE LINE FOR RAIN WATER DISPOSAL TO STORM WATER DRAIN AT VALLUVARKOTTAM HIGH ROAD( FROM APPU STREET TO POLICE QUARTRES) AND LAKE AREA 4TH CROSS STREET NEAR ZONAL OFFICE IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3992,Buildings,Completed,NJ-TEYNAMPET,110,619000,"IMROVEMENTS TO PUBLIC CONVENIANCE AT LAKE AREA 4TH CROSS STREET INSIDE PLAY GROUND IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/5727,Buildings,Completed,NJ-TEYNAMPET,110,765000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT KAMDAR NAGAR IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/5820,Buildings,Completed,NJ-TEYNAMPET,110,985000,"PROVIDING SHED FOR AMMA KUDINEER WATER PLANT AT SCHOOL ROAD JUNCTION OF VALLUVAR KOTTAM HIGH ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/6001,Parks,Completed,NJ-TEYNAMPET,110,334000,"IMPROVEMENTS TO INDEPENDENSE DAY PARK AT VALLUVAR KOTTAM HIGH ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/6440,Parks,Completed,NJ-TEYNAMPET,110,374000,"IMPROVEMENTS TO ANNA PARK AT KODAMBAKKAM HIGH ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/6644,Buildings,Completed,NJ-TEYNAMPET,110,268000,"IMPROVEMENTS TO TOILET BUILDING AND PROVIDING CONCRETE PLATE FORM FOR SURROUNDINGS OF NIGHT SHELTER AT KAMDAR NAGAR MAIN ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/8246,Buildings,Completed,NJ-TEYNAMPET,110,766000,"LAYING CEMENT CONCRETE PLATE FORM TO THE SURROUNDINGS OF AUDIDORIUM AT CHENNAI BOYS HIGHER SECONDARY SCHOOL,SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2019-20 NJ/2016-17/8264,Buildings,Completed,NJ-TEYNAMPET,110,370000,"CONSTRUCTION OF GALVANISHED IRON SHEET SHED FOR FOUR WHEELER PARKING AT ZONAL OFFICE 9 LAKE AREA 4TH CROSS STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/9944,Roads,Completed,NJ-TEYNAMPET,110,503000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT NACHIAPPAN STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9947,Roads,Completed,NJ-TEYNAMPET,110,769000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT APPASAMY STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9954,Roads,Completed,NJ-TEYNAMPET,110,555000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT RAMANATHAN STREET IN DIVISION-111,UNITY-24,ZONE-09",Own Sources,9,2016-17,2017-18 BR/2016-17/17347,Footpath,Completed,BR-Bus Route Roads,111,2274000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Whites Road, West Cott Road, Mahalingapuram Main Road, Tank Bund Road , Valluvarkottam High Road and 70 Feet Scheme Road in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/19222,Road Cut,Completed,BR-Bus Route Roads,111,1292000,"Restoration of Roadcut made by CMWSSB at Greams Road in Dn-113, Zone-9",Deposit Works,9,2016-17,2017-18 BR/2016-17/4420,Roads,Completed,BR-Bus Route Roads,111,840000,Supplying and fixing of Front facia & back drop in the 68 nos Existing Modern stainless steel bus shelters in Zone -9,Own Sources,9,2016-17,2017-18 BR/2016-17/7210,Roads,Completed,BR-Bus Route Roads,111,950000,"Attending repairs to existing centremedian, Footpath and other traffic improvements to various Bus Route Roads in Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/0112,Buildings,Completed,NJ-TEYNAMPET,111,810000,"PROVIDING ELECTION BOOTH BARRICADING WORKS,PAINTING WORKS,PLYWOOD PARTITION WORKS AND RAMPS FOR TAMILNADU ASSEMBLY GENERAL ELECTION 2016 IN DIVISION 111,118,119 AND 120 UNIT 24 ZONE 09",Own Sources,9,2016-17,2016-17 NJ/2016-17/14086,Buildings,Completed,NJ-TEYNAMPET,111,145000,REPAIRS AND MAINTENANCE OF ELLARI STREET COMMUNITY IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2016-17,2018-19 NJ/2016-17/14104,Buildings,Completed,NJ-TEYNAMPET,111,135000,REPAIRS AND MAINTENANCE OF RANGOON STREET PUBLIC CONVENIENCE IN DIVISION -111 UNIT-24 ZONE - 09,Own Sources,9,2016-17,2018-19 NJ/2016-17/14116,Buildings,Completed,NJ-TEYNAMPET,111,115000,"REPAIRS AND MAINTENANCE OF THIRU.VI.KA. STREET PUBLIC CONVENIENCE IN DIVI- 111, UNIT - 24, ZONE - 09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14117,Buildings,Completed,NJ-TEYNAMPET,111,128000,"REPAIRS AND MAINTENANCE OF 29 GREAMS ROAD PUBLIC CONVENIENCE IN DIVISION -111, UNIT-24 ZONE - 09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14120,Buildings,Completed,NJ-TEYNAMPET,111,160000,"REPAIRS AND MAINTENANCE OF BEGUM SAHIB STREET PUBLIC CONVENIENCE IN DIVISION -111, UNIT- 24 ZONE 09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14121,Buildings,Completed,NJ-TEYNAMPET,111,135000,REPAIRS AND MAINTENANCE OF RAMASAMY STREET (RIVER SIDE) PUBLIC CONVENIENCE IN DIVISION-111 UNIT-24 ZONE - 09,Own Sources,9,2016-17,2018-19 NJ/2016-17/14123,Buildings,Completed,NJ-TEYNAMPET,111,133000,"REPAIRS AND MAINTENANCE OF PUBLIC CONVENIENCE AT THIDEER NAGAR STREET IN DIVISION -111, UNIT -24, ZONE- 09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14125,Buildings,Completed,NJ-TEYNAMPET,111,185000,"REPAIRS AND MAINTENANCE OF RAMASAMY STREET PUBLIC CONVENIENCE IN DIVISION- 111, UNIT- 24 ZONE 09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14128,Buildings,Completed,NJ-TEYNAMPET,111,80000,"REPAIRS AND MAINTENANCE OF PUBLIC CONVENIENCE AT SUNDHANDRA NAGAR IN DIVISION -111, UNIT - 24, ZONE - 09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14234,Buildings,Completed,NJ-TEYNAMPET,111,198000,REPAIRS AND MAINTENANCE TO CHENNAI HIGH SCHOOL AT MODEL SCHOOL ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/1541,Buildings,Completed,NJ-TEYNAMPET,111,816000,"PROPOSED CONSTRUCTION OF COMPOUND WALL ,SUMP AND WATER SUPPLY ARRANGEMENTS AT AMMAUNAVAGAM WALLACE GARDEN 1ST STREET IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/1546,Buildings,Completed,NJ-TEYNAMPET,111,833000,"IMPROVEMENTS TO AMMA UNAVAGAM AT WALLACE GARDEN 1ST STREET IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/1564,Buildings,Completed,NJ-TEYNAMPET,111,616000,"PROVIDING AND LAYING INTERLOCKING PAVER BLOCKS FLOORING FOR AMMAUNAVAGAM CAMPUS AT WALLACE GARDEN 1ST STREET IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/15690,Storm Water Drain,Completed,NJ-TEYNAMPET,111,200000,"REPAIRS TO SUMP AT UPHSC AT ASSIZ MULLAK 2ND STREET (VARDHA CYCLONE) IN DIV-111, UNIT-24, ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16239,Buildings,Completed,NJ-TEYNAMPET,111,500000,Repairs to Chennai primary school at Model school road in division 111 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16240,Parks,Completed,NJ-TEYNAMPET,111,400000,Repairs to College Lane park at College road in division 111 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16241,Parks,Completed,NJ-TEYNAMPET,111,550000,Repairs to Haddows road park in division 111 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16242,Parks,Completed,NJ-TEYNAMPET,111,833000,Repairs to Spencer park in division 111 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/17870,Footpath,Completed,NJ-TEYNAMPET,111,525000,"REPAIRS TO FOOT PATH AT KHADERNAWASKHAN ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17871,Footpath,Completed,NJ-TEYNAMPET,111,125000,"REPAIRS TO FOOT PATH AT RUTLAND GATE 4 TH STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17872,Footpath,Completed,NJ-TEYNAMPET,111,390000,"REPAIRS TO FOOT PATH AT COLLEGE ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17873,Footpath,Completed,NJ-TEYNAMPET,111,630000,"REPAIRS TO FOOTPATH AT ANDERSON ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/18577,Road Cut,Completed,NJ-TEYNAMPET,111,1670000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KHADER NAWAS KHAN ROAD IN DIVISION-111,UNIT-24,ZONE-09",Deposit Works,9,2016-17,2017-18 NJ/2016-17/18722,Roads,Completed,NJ-TEYNAMPET,111,800000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SAFEE MOHAMOD ROAD IN DIVISION-111,UNIT-24, ZONE-09",Deposit Works,9,2016-17,2017-18 NJ/2016-17/2358,Storm Water Drain,Completed,NJ-TEYNAMPET,111,970000,IMPROVEMENTS AND STRENGTHENING TO SIDE DRAINS AT THIDEER NAGAR MAIN STREET IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2363,Storm Water Drain,Completed,NJ-TEYNAMPET,111,975000,IMPROVEMENTS AND STRENGTHENING TO SIDE DRAINS AT THIDEER NAGAR CROSS LANES IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3199,Storm Water Drain,Completed,NJ-TEYNAMPET,111,340000,Desilting of Storm Water Drain at College Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3201,Storm Water Drain,Completed,NJ-TEYNAMPET,111,200000,Desilting of Storm Water Drain at Haddows Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3203,Storm Water Drain,Completed,NJ-TEYNAMPET,111,252000,Desilting of Storm Water Drain at Kadharnawaskhan Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3204,Storm Water Drain,Completed,NJ-TEYNAMPET,111,274000,Desilting of Storm Water Drain at Model School Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3206,Storm Water Drain,Completed,NJ-TEYNAMPET,111,65000,Desilting of Storm Water Drain at College Lane in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3208,Storm Water Drain,Completed,NJ-TEYNAMPET,111,268000,Desilting of Storm Water Drain at Anderson Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3209,Storm Water Drain,Completed,NJ-TEYNAMPET,111,96000,Desilting of Storm Water Drain at Moors Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3210,Storm Water Drain,Completed,NJ-TEYNAMPET,111,56000,Desilting of Storm Water Drain at Pycrofts Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3213,Storm Water Drain,Completed,NJ-TEYNAMPET,111,168000,Desilting of Storm Water Drain at Pattulas Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3214,Storm Water Drain,Completed,NJ-TEYNAMPET,111,400000,Desilting of Storm Water Drain at Whites Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3215,Storm Water Drain,Completed,NJ-TEYNAMPET,111,168000,Desilting of Storm Water Drain at Conronsmith Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3216,Storm Water Drain,Completed,NJ-TEYNAMPET,111,137000,Desilting of Storm Water Drain at Woods Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3218,Storm Water Drain,Completed,NJ-TEYNAMPET,111,400000,Desilting of Storm Water Drain at Greems Road in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3219,Storm Water Drain,Completed,NJ-TEYNAMPET,111,49000,Desilting of Storm Water Drain at Thiru-Vi-Ka Salai in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3221,Storm Water Drain,Completed,NJ-TEYNAMPET,111,62000,Desilting of Storm Water Drain at Ganesh Street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3224,Storm Water Drain,Completed,NJ-TEYNAMPET,111,50000,Desilting of Storm Water Drain at West End Street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3225,Storm Water Drain,Completed,NJ-TEYNAMPET,111,137000,Desilting of Storm Water Drain at Gopalapuram 1st street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3227,Storm Water Drain,Completed,NJ-TEYNAMPET,111,68000,Desilting of Storm Water Drain at Gopalapuram 2nd street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3228,Storm Water Drain,Completed,NJ-TEYNAMPET,111,53000,Desilting of Storm Water Drain at Gopalapuram 3rd street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3230,Storm Water Drain,Completed,NJ-TEYNAMPET,111,53000,Desilting of Storm Water Drain at Gopalapuram 6th street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3232,Storm Water Drain,Completed,NJ-TEYNAMPET,111,53000,Desilting of Storm Water Drain at Gopalapuram 7th street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3233,Storm Water Drain,Completed,NJ-TEYNAMPET,111,61000,Desilting of Storm Water Drain at Gopalapuram 8th street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3234,Storm Water Drain,Completed,NJ-TEYNAMPET,111,350000,Desilting of Storm Water Drain at Avvai Shanmugam Salai in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3236,Storm Water Drain,Completed,NJ-TEYNAMPET,111,135000,Desilting of Storm Water Drain at Wallace Garden 2nd street in Division 111 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/4841,Buildings,Completed,NJ-TEYNAMPET,111,739000,"IMPROVEMENTS TO EXE.ENGINEER OFFICE ROOM FIRST FLOOR AT ZONAL OFFICE 9 LAKE AREA 4TH CROSS STREET IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/5621,Roads,Completed,NJ-TEYNAMPET,111,800000,"RELAYING OF RAOD WITH BCCMP 40MM THICK AT MURUGESAN NAICKER COMPLEX ROAD IN DIVISION-111,UNIT-24,ZONE-IX",Own Sources,9,2016-17,2016-17 NJ/2016-17/5631,Roads,Completed,NJ-TEYNAMPET,111,525000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT PETERS LANE IN DIVISION-111,UNIT-24,ZONE-IX",Own Sources,9,2016-17,2017-18 NJ/2016-17/5892,Footpath,Completed,NJ-TEYNAMPET,111,1580000,"NEW CONSTRUCTION OF STORM WATER DRAIN ALONG GOPALAPURAM 4TH STREET FROM GOPALAPURAM 2ND MAIN ROAD TO 1ST MAIN ROAD IN DIVISION-111,UNIT-24, ZONE-09(UNDER MLA FUND 2016-17)",MLACDS,9,2016-17,2017-18 NJ/2016-17/5893,Footpath,Completed,NJ-TEYNAMPET,111,2270000,"FORMING FOOTPATH AND PROVIDING STAINLESS STEEL HAND RAIL UNDER M.L.A. FUND 206-17 AT GOPALAPURAM 4TH STREET (SOUTH & NORTH SIDE) IN DIVISION-111,UNIT-24,ZONE-IX.",MLACDS,9,2016-17,2018-19 NJ/2016-17/6163,Buildings,Completed,NJ-TEYNAMPET,111,590000,"CONSTRUCTION OF COMPACTOR BIN PLATE FORM IN DIVISIONS-109,110,111,118 AND 119,UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/6407,Buildings,Completed,NJ-TEYNAMPET,111,330000,"CONSTRUCTION OF PLAT FORM AND WATER SUPPLY ARRANGEMENTS IN E- TOILET AT ANDERSON ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7448,Playfields,Completed,NJ-TEYNAMPET,111,188000,IMPROVEMENTS TO PLAY GROUND AT 29TH GREAMS ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/7640,Storm Water Drain,Completed,NJ-TEYNAMPET,111,195000,"DESILTING OF STORM WATER DRAIN AT HADDOWS ROAD 1 ST STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7641,Storm Water Drain,Completed,NJ-TEYNAMPET,111,186000,"DESILTING OF STORM WATER DRAIN AT HADDOWS ROAD 2 ND STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7642,Storm Water Drain,Completed,NJ-TEYNAMPET,111,107000,"DESILTING OF STORM WATER DRAIN AT GUALAM ABBAS ALIGHAN 10 TH STREET STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7643,Storm Water Drain,Completed,NJ-TEYNAMPET,111,185000,"DESILTING OF STORM WATER DRAIN AT AZIZ MULK 1 ST STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7644,Storm Water Drain,Completed,NJ-TEYNAMPET,111,120000,"DESILTING OF STORM WATER DRAIN AT AZIZ MULK 4 TH STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7645,Storm Water Drain,Completed,NJ-TEYNAMPET,111,197000,"DESILTING OF STORM WATER DRAIN AT SUBBA RAO 1 ST STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7647,Storm Water Drain,Completed,NJ-TEYNAMPET,111,132000,"DESILTING OF STORM WATER DRAIN AT GULAM ABBAS ALIGHAN BAHADUR STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7648,Storm Water Drain,Completed,NJ-TEYNAMPET,111,190000,"DESILTING OF STORM WATER DRAIN AT BINNY ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7649,Storm Water Drain,Completed,NJ-TEYNAMPET,111,198000,"DESILTING OF STORM WATER DRAIN AT PETERS ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7650,Storm Water Drain,Completed,NJ-TEYNAMPET,111,158000,"DESILTING OF STORM WATER DRAIN AT PETERS LANE IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7653,Storm Water Drain,Completed,NJ-TEYNAMPET,111,153000,"DESILTING OF STORM WATER DRAIN AT VASAN AVENUE IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7654,Storm Water Drain,Completed,NJ-TEYNAMPET,111,153000,"DESILTING OF STORM WATER DRAIN AT ELLARI STREET IN DIVISION-111,UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/7655,Storm Water Drain,Completed,NJ-TEYNAMPET,111,148000,"DESILTING OF STORM WATER DRAIN AT ANNA SALAI FLY OVER SERVICE ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7659,Storm Water Drain,Completed,NJ-TEYNAMPET,111,447000,"DESILTING OF STORM WATER DRAIN AT ANNA SALAI GEMINI FLY OVER END TO TOWARDS GREAMS ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/8460,Storm Water Drain,Completed,NJ-TEYNAMPET,111,961000,"IMPROVEMENTS TO STORM WATER DRAIN AT GANESH STREET IN DN 111,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/9899,Roads,Completed,NJ-TEYNAMPET,111,775000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT COLLEGE LANE IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9900,Roads,Completed,NJ-TEYNAMPET,111,317000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT KUSHKUMAR ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9901,Roads,Completed,NJ-TEYNAMPET,111,2590000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT ANDERSON ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9903,Roads,Completed,NJ-TEYNAMPET,111,424000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT RUTLAND GATE 5 TH STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/11508,Buildings,Completed,NJ-TEYNAMPET,112,998000,"Supply, Installation,Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at Choolai Medu High Road (Near Vanniar Street) in Dn 112,Unit-26,Zone -9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13975,Buildings,Completed,NJ-TEYNAMPET,112,72000,"Repair work to Public Convenience at Vannarapathai in Dn112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13976,Buildings,Completed,NJ-TEYNAMPET,112,55000,"Repair work to Public Convenience at Varatharajpet Main Road in Dn112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13977,Buildings,Completed,NJ-TEYNAMPET,112,52000,"Repair work to Public Convenience at Rajapuraniker Street in Dn112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13978,Buildings,Completed,NJ-TEYNAMPET,112,55000,"Repair work to Public Convenience at Dosspuram (Ladies) in Dn112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13979,Buildings,Completed,NJ-TEYNAMPET,112,62000,"Repair work to Public Convenience at Dosspuram (Gents) in Dn112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13980,Buildings,Completed,NJ-TEYNAMPET,112,35000,"Repair work to Public Convenience at Choolaimedu Railway Border in Dn112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13981,Buildings,Completed,NJ-TEYNAMPET,112,32000,"Repair work to Public Convenience at Puliyur 1st Main Road in Dn112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16291,Parks,Completed,NJ-TEYNAMPET,112,370000,"REPAIRS TO ANBAZHAGAN PARK AT TRUSTPURAM 6TH CROSS STREET IN DN 112,UNIT-26, ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16299,Buildings,Completed,NJ-TEYNAMPET,112,326000,"REPAIRS TO CHITRA PARK AT RAILWAY BORDER ROAD IN DN 112,UNIT-26, ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16309,Buildings,Completed,NJ-TEYNAMPET,112,100000,"REPAIR WORK AT AMMA UNAVAGAM AT CHOOLAIMEDU HIGH ROAD IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16317,Buildings,Completed,NJ-TEYNAMPET,112,49000,"REPAIR WORK AT AMMA UNAVAGAM AT PULIYUR MAIN ROAD IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16320,Storm Water Drain,Completed,NJ-TEYNAMPET,112,26000,"REPAIRS TO STORM WATER DRAIN AT PULIYUR 1ST LANE IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16321,Storm Water Drain,Completed,NJ-TEYNAMPET,112,22500,"REPAIRS TO STORM WATER DRAIN AT BHARATHEESWARAR COLONY 2ND STREET IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16323,Storm Water Drain,Completed,NJ-TEYNAMPET,112,23000,"REPAIRS TO STORM WATER DRAIN AT BHARATHEESWARAR COLONY 1ST STREET IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16326,Storm Water Drain,Completed,NJ-TEYNAMPET,112,24500,"REPAIRS TO STORM WATER DRAIN AT PULIYUR 1ST MAIN ROAD IN DN 112,UNIT-26, ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17944,Playfields,Completed,NJ-TEYNAMPET,112,576000,"REPAIR WORKS TO TRUSTPURAM PLAY GROUND AT PULIYUR 1ST MAIN ROAD IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17980,Roads,Completed,NJ-TEYNAMPET,112,385000,"ATTENDING PATCH WORK AT B.E.COLONY 1 T0 4 STREETS AND VARIOUS STREETS IN DN 112,UNIT-26,ZONE9",Own Sources,9,2016-17,2017-18 NJ/2016-17/19614,Buildings,Completed,NJ-TEYNAMPET,112,990000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT CHOOLAIMEDU HIGH ROAD (NEAR TO VANNIYAR STREET) IN DIV-112,U-26,Z-09",Own Sources,9,2016-17,2019-20 NJ/2016-17/2416,Roads,Completed,NJ-TEYNAMPET,112,105000,"Repairs and Desilting of Storm Water at Bharadeeswararan Colony 1st Street in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2418,Storm Water Drain,Completed,NJ-TEYNAMPET,112,170000,"Repairs and Desitling of Storm Water Drain at Bharatheeawarar Colony 2nd Street in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2419,Storm Water Drain,Completed,NJ-TEYNAMPET,112,20000,"Repairs and Desitling of Storm Water Drain at Bharadeeswarar Colony 4th Street in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2425,Storm Water Drain,Completed,NJ-TEYNAMPET,112,42000,"Repairs and Desilting of Storm Water at Ganga nagar 2nd main road in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2427,Storm Water Drain,Completed,NJ-TEYNAMPET,112,60000,"Repairs and Desilting of Storm Water at Ganga nagar 4th cross street in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2428,Storm Water Drain,Completed,NJ-TEYNAMPET,112,57000,"Repairs and Desilting of Storm Water at Muthumani Street in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2429,Storm Water Drain,Completed,NJ-TEYNAMPET,112,42000,"Repairs and Desilting of Storm Water at Nehru Street in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2431,Storm Water Drain,Completed,NJ-TEYNAMPET,112,98000,"Repairs and Desilting of Storm Water at Puliyur 1st lane in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2434,Storm Water Drain,Completed,NJ-TEYNAMPET,112,123000,"Repairs and Desilting of Storm Water at Puliyur Main Road in Dn 112,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2437,Storm Water Drain,Completed,NJ-TEYNAMPET,112,44000,"Repairs and Desilting of Storm water at Sivan kovil South Street in Dn 112, Unit- 26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2438,Storm Water Drain,Completed,NJ-TEYNAMPET,112,189000,"Repairs and Desilting of Storm water at Sivan kovil Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2439,Storm Water Drain,Completed,NJ-TEYNAMPET,112,73000,"Repairs and Desilting of Storm water at South Sivan kovil Street in Dn 112, Unit- 26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2440,Storm Water Drain,Completed,NJ-TEYNAMPET,112,65000,"Repairs and Desilting of Storm water at Sowrashtra nagar 10th Street in Dn 112, Unit- 26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2441,Storm Water Drain,Completed,NJ-TEYNAMPET,112,41000,"Repairs and Desilting of Storm water at Sowrashtra nagar 1St Street in Dn 112, Unit- 26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2443,Storm Water Drain,Completed,NJ-TEYNAMPET,112,42500,"Repairs and Desilting of Storm water at Sowrashtra nagar 7th Street in Dn 112, Unit- 26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2444,Storm Water Drain,Completed,NJ-TEYNAMPET,112,79000,"Repairs and Desilting of Storm water at Sowrashtra nagar 8th Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2445,Storm Water Drain,Completed,NJ-TEYNAMPET,112,83000,"Repairs and Desilting of Storm water at Sowrashtra nagar 9th Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2449,Storm Water Drain,Completed,NJ-TEYNAMPET,112,152000,"Repairs and Desilting of Storm water at Trustpuram 5th Cross Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2450,Storm Water Drain,Completed,NJ-TEYNAMPET,112,140000,"Repairs and Desilting of Storm water at Trustpuram 6th Cross Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2451,Storm Water Drain,Completed,NJ-TEYNAMPET,112,92000,"Repairs and Desilting of Storm water at Trustpuram 7th Cross Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2452,Storm Water Drain,Completed,NJ-TEYNAMPET,112,64000,"Repairs and Desilting of Storm water at Varatharajanpet Main Road in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2453,Storm Water Drain,Completed,NJ-TEYNAMPET,112,85000,"Repairs and Desilting of Storm water at Vellala street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2454,Storm Water Drain,Completed,NJ-TEYNAMPET,112,81000,"Repairs and Desilting of Storm water at Zakaria Colony 3rd Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2455,Storm Water Drain,Completed,NJ-TEYNAMPET,112,84000,"Repairs and Desilting of Storm water at Zakaria Colony 4th Street in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2456,Storm Water Drain,Completed,NJ-TEYNAMPET,112,129000,"Repairs and Desilting of Storm water at Zakaria Colony Main Road in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/4047,Buildings,Completed,NJ-TEYNAMPET,112,880000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT (PART-1) MUTHU THOTTAM 1ST STREET, MUTHU THOTTAM 2ND STREET, SOWRANBIKA STREET, SIVAN KOVIL SOUTH STREET, PULIYUR 1ST LANE, PULIYUR 2ND LANE,TRUST PURAM 5TH CROSS STREET,TRUST PURAM 6TH CROSS STREET,TRUST PURAM 8TH CROSS STREET, PULIYUR MAIN ROAD, TRUST PURAM9TH CROSS STREET, PONNUSAMY VADIYAR STREET, TRUST PURAM 10TH CROSS STREET, SIVAN KOVIL STREET, MINOR TRUST PURAM 2ND CROSS STREET,MINOR TRUST PURAM 3RD CROSS STREET, SOWRASTRA NAGAR 8TH STREET(Asset code:021/10476/64/2013-14) IN DN 112,UNIT-26,ZONE-9 (UNDER WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2016-17 NJ/2016-17/4051,Buildings,Completed,NJ-TEYNAMPET,112,880000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT (PART 2)SOUTH SIVAN KOIL STRET,VELLALA STREET 1ST LANE ,VELLALA STRET 2ND LANE, VELLLA STREET,VELLALA STREET UNIT OFFICE OPPOSITE,NW VELLALA STREET,,SIVAN KOIL CROSS STREET,VANNAR PATHAI,SIVAN KOIL SOUTH STREET,PULIYUR HOUSING BOARD ,ESWAR NAGAR 5TH STREET,ESWAR NAGAR 2ND STREET,SIVAN KOIL SOUTH STREET,ESWAR NAGAR 3RD STREET,GANDHI NAGAR,DAYALUH NAGAR MAIN ROAD,ESWAR NAGAR 4TH STREET,DAYALU NAGAR 3RD STREET,DAYALU NAGAR 2ND STREET(Asset code:155/10475/3648/2014-15) IN DN 112,UNIT-26,ZONE-9 (UNDER WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/4055,Parks,Completed,NJ-TEYNAMPET,112,588000,"Improvements to Anbazhagan Park under ward councilor fund in Trust puram 6th cross street(Asset code:013/10500/1121/2014-15 ) in Dn 112, Unit-26,Zone-9",Own Sources,9,2016-17,2019-20 NJ/2016-17/5310,Road Cut,Completed,NJ-TEYNAMPET,112,435000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BHARATHEESHWARER COLONY 1ST STREET(Asset code:155/16370/2942/2013-14) IN DN 112,UNIT-26,ZONE-9",Deposit Works,9,2016-17,2016-17 NJ/2016-17/5311,Road Cut,Completed,NJ-TEYNAMPET,112,261000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BHARATHEESHWARER COLONY 2ND STREET(Asset code:155/10462/3683/2014-15) IN DN 112,UNIT-26,ZONE-9",Deposit Works,9,2016-17,2016-17 NJ/2016-17/5312,Road Cut,Completed,NJ-TEYNAMPET,112,198000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BHARATHEESHWARER COLONY 3rd STREET (Asset code:155/16374/3771/2014-15)IN DN 112,UNIT-26,ZONE-9",Deposit Works,9,2016-17,2016-17 NJ/2016-17/5313,Road Cut,Completed,NJ-TEYNAMPET,112,389000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT NEW MARKET STREET (Asset code:155/8540/3749/2014-15)IN DN 112,UNIT-26,ZONE-9",Deposit Works,9,2016-17,2016-17 NJ/2016-17/5314,Road Cut,Completed,NJ-TEYNAMPET,112,350000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MUTHU THOTTAM 1ST STREET (Asset cde:155/10466/3717/2014-15)IN DN 112,UNIT-26,ZONE-9",Deposit Works,9,2016-17,2016-17 NJ/2016-17/5316,Road Cut,Completed,NJ-TEYNAMPET,112,356000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MUTHU THOTTAM 2nd STREET (Asset code:155/16371/3649/2014-15)IN DN 112,UNIT-26,ZONE-9",Deposit Works,9,2016-17,2016-17 NJ/2016-17/5609,Buildings,Completed,NJ-TEYNAMPET,112,428000,"IMPROVEMENT TO CHENNAI MIDDLE SCHOOL BUILDING IN PULLIYUR 2ND MAIN ROAD TRSUTPURAM IN DN 112,UNIT-26,ZONE-9 (Asset code: 156/16369/1345/2014-15) REF : (Z.O.IX.C.No.06795/2016)",Own Sources,9,2016-17,2018-19 NJ/2016-17/5697,Buildings,Completed,NJ-TEYNAMPET,112,266000,"IMPROVEMENTS TO PUBLIC CONVENIENCE( ASSET CODE NO 033/10563/707/2014-15) AT DHARMAPURAM 6TH STREET IN DN 113,UNIT-26, ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/6694,Buildings,Completed,NJ-TEYNAMPET,112,985000,"PROVIDING SHED FOR AMMA KUDINEER WATER PLANT AT CHOOLAIMEDU HIGH ROAD JUNCTION OF VANNIAR STREET IN DN 112,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 BR/2016-17/17367,Footpath,Completed,BR-Bus Route Roads,113,2390000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Uthamar Gandhi salai, Dr.M.G.R.salai, College Road and Sterling Avenue in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/17660,Roads,Completed,BR-Bus Route Roads,113,583000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Avvai Shanmugam Salai, Tank Bund Road and Uthamar Gandhi Salai in Zone-9",Grants,9,2016-17,2017-18 BR/2016-17/19219,Road Cut,Completed,BR-Bus Route Roads,113,1727000,"Restoration of Roadcut made by CMWSSB at Nungambakkam High Road (Uthamar gandhi Salai) (from the jn of Ponnangipuram main Road to Valluvar Kottam High Road) in Dn-113, Zone-9",Deposit Works,9,2016-17,2017-18 BR/2016-17/19230,Road Cut,Completed,BR-Bus Route Roads,113,1728000,"Restoration of Roadcut made by CMWSSB at Nungambakkam High Road (Uthamar gandhi Salai) (From the jn of Krishnamma Road to Ponnangi puram Main Road) in Dn-113, Zone-9",Deposit Works,9,2016-17,2017-18 NJ/2016-17/0032,Parks,Completed,NJ-TEYNAMPET,113,400000,"MAINTENANCE OF PRE FABRICATED URINAL UNITS AT VARIOUS LOCATIONS IN DIVISIONS-112,113,117 & 122 IN UNIT-26 ,ZONE-09 PERIOD (01.06.2016 TO 30.06.2016)4 MONTHS",Own Sources,9,2016-17,2019-20 NJ/2016-17/0736,Buildings,Completed,NJ-TEYNAMPET,113,400000,"IMPROVEMENTS TO DIVISION OFFICE BUILDING AT VALLUVAR KOTTAM HIGH ROAD IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/11069,Road Cut,Completed,NJ-TEYNAMPET,113,630000,"RESTORATION OF ROAD MADE BY TANGEDCO AT HABIBULLAH ROAD FROM NORTH USMAN ROAD TO MAMBALAM HIGH ROAD IN DIVISION 113 UNIT 26 ZONE 09 (Receipt No.07/2016-17/0307396. Challan No.NJ/2016-17/0005877. Deposit code.02/0149/2016-17)",Grants,9,2016-17,2017-18 NJ/2016-17/14138,Buildings,Completed,NJ-TEYNAMPET,113,40000,"Minor Repairs to Public Convenience at Kodambakkam High road (Near Merto water Filling Station) in Dn 113, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14140,Buildings,Completed,NJ-TEYNAMPET,113,72000,"Minor Repairs to Public Convenience at Kodambakkam high road (Badrikarai) in Dn 113, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14141,Buildings,Completed,NJ-TEYNAMPET,113,73000,"Minor Repairs to Public Convenience at Gangaikaraipuram in Dn 113, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14142,Buildings,Completed,NJ-TEYNAMPET,113,44000,"Minor Repairs to Public Convenience at G.N.(C) Road in Dn 113, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14143,Buildings,Completed,NJ-TEYNAMPET,113,28000,"Minor Repairs to Public Convenience at Pillaiyar koil street in Dn 113, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14144,Buildings,Completed,NJ-TEYNAMPET,113,56000,"Minor Repairs to Public Convenience at Seeranipuram in Dn 113, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14145,Buildings,Completed,NJ-TEYNAMPET,113,48000,"Minor Repairs to Public Convenience at Dharmapuram 6th street in Dn 113, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14319,Buildings,Completed,NJ-TEYNAMPET,113,390000,"IMPROVEMENTS AND REPAIRS TO CHENNAI MIDDLE SCHOOL AT DHARMAPURAM IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14320,Buildings,Completed,NJ-TEYNAMPET,113,217000,"IMPROVEMENTS AND REPAIRS TO CHENNAI MIDDLE SCHOOL AT RAMA STREET IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15854,Storm Water Drain,Completed,NJ-TEYNAMPET,113,473000,"REPAIRS TO STORM WATER DRAIN AT NUNGAMBAKKAM HIGH ROAD IN DN 113,UNIT 24,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15859,Storm Water Drain,Completed,NJ-TEYNAMPET,113,94000,"REPAIRS TO STORM WATER DRAIN AT VALLUVARKOTTAM HIGH ROAD OPP TO SRIBHAVAN HOTEL IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15860,Storm Water Drain,Completed,NJ-TEYNAMPET,113,81000,"REPAIRS TO STORM WATER DRAIN AT DURAISAMY STREET NEAR DOOR NO 3 IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15861,Storm Water Drain,Completed,NJ-TEYNAMPET,113,97000,"REPAIRS TO STORM WATER DRAIN AT KRISHNAMA ROAD IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15864,Storm Water Drain,Completed,NJ-TEYNAMPET,113,84000,"REPAIRS TO STORM WATER DRAIN AT THIRUMOORTHI NAGAR 3RD STREET JUNCTION OF 4TH CROSS STREET IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15958,Parks,Completed,NJ-TEYNAMPET,113,1144000,"REPAIRS TO PARK AT KODAMBAKKAM HIGH ROAD JUNCTION OF VALLUVARKOTTAM HIGH ROAD IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15959,Parks,Completed,NJ-TEYNAMPET,113,286000,"REPAIRS TO PERIYAR ROAD PARK AT KODAMBAKKAM HIGH ROAD IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17981,Roads,Completed,NJ-TEYNAMPET,113,385000,"ATTENDING PATCH WORK AT BALAMUTHUKRISHAN STREET AND OTHER VARIOUS STREETS IN DN 113,UNIT-26,ZONE9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2316,Storm Water Drain,Completed,NJ-TEYNAMPET,113,169000,"DESILTING OF STORM WATER DRAIN AT SHENOY ROAD IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2341,Storm Water Drain,Completed,NJ-TEYNAMPET,113,250000,"DESILTING OF STORM WATER DRAIN AT PILLAYAR KOIL STREET IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2351,Storm Water Drain,Completed,NJ-TEYNAMPET,113,135000,"DESILTING OF STORM WATER DRAIN AT THANGAVEL STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2353,Storm Water Drain,Completed,NJ-TEYNAMPET,113,340000,"DESILTING OF STORM WATER DRAIN AT BALAMUTHU KRISHNA STREET IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2393,Storm Water Drain,Completed,NJ-TEYNAMPET,113,219000,"DESILTING OF STORM WATER DRAIN AT DURAISAMY STREET IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2633,Storm Water Drain,Completed,NJ-TEYNAMPET,113,200000,"REPAIR AND IMPROVEMENTS TO STORM WATER DRAIN AT VALLUVARKOTTAM HIGH ROAD (OPP TO HOTEL SREE BHAVAN) IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2636,Storm Water Drain,Completed,NJ-TEYNAMPET,113,300000,"REPAIR AND IMPROVEMENTS TO STORM WATER DRAIN AT NUNGAMBAKKAM HIGH ROAD (JUNCTION OF KHADERNAWASKHAN ROAD) IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2769,Storm Water Drain,Completed,NJ-TEYNAMPET,113,495000,"DESILTING OF STORM WATER DRAIN AT G.N.CHETTY ROAD IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2817,Storm Water Drain,Completed,NJ-TEYNAMPET,113,61700,"DESILTING OF STORM WATER DRAIN AT JAMBULINGAM STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2821,Storm Water Drain,Completed,NJ-TEYNAMPET,113,498000,"DESILTING OF STORM WATER DRAIN AT PORUR SOMASUNDARAM STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2824,Storm Water Drain,Completed,NJ-TEYNAMPET,113,61700,"DESILTING OF STORM WATER DRAIN AT VIDYODAYA 2ND CROSS STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2829,Storm Water Drain,Completed,NJ-TEYNAMPET,113,61700,"DESILTING OF STORM WATER DRAIN AT SUBBARAYAN STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2855,Storm Water Drain,Completed,NJ-TEYNAMPET,113,89000,"DESILTING OF STORM WATER DRAIN AT KOLAMAMANIAMMAN KOIL STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2860,Storm Water Drain,Completed,NJ-TEYNAMPET,113,111000,"DESILTING OF STORM WATER DRAIN AT VAIDHYANATHAN STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2864,Storm Water Drain,Completed,NJ-TEYNAMPET,113,84000,"DESILTING OF STORM WATER DRAIN AT NOOR VEERASAMY STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2865,Storm Water Drain,Completed,NJ-TEYNAMPET,113,162000,"DESILTING OF STORM WATER DRAIN AT VEERABADHRAN STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2880,Storm Water Drain,Completed,NJ-TEYNAMPET,113,29100,"DESILTING OF STORM WATER DRAIN AT MOHAN KUMARAMANGAlAM STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2882,Storm Water Drain,Completed,NJ-TEYNAMPET,113,111000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM 2ND STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2884,Storm Water Drain,Completed,NJ-TEYNAMPET,113,111000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM 4TH STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2886,Storm Water Drain,Completed,NJ-TEYNAMPET,113,112000,"DESILTING OF STORM WATER DRAIN AT MELAPADI MUTHU STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2889,Storm Water Drain,Completed,NJ-TEYNAMPET,113,171000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM 6TH STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2893,Storm Water Drain,Completed,NJ-TEYNAMPET,113,182000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM 7TH STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2897,Storm Water Drain,Completed,NJ-TEYNAMPET,113,182000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM 5TH STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2898,Storm Water Drain,Completed,NJ-TEYNAMPET,113,79000,"DESILTING OF STORM WATER DRAIN AT KRISHNA STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2899,Storm Water Drain,Completed,NJ-TEYNAMPET,113,192000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM 10th STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2901,Storm Water Drain,Completed,NJ-TEYNAMPET,113,190000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM 11th STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2909,Storm Water Drain,Completed,NJ-TEYNAMPET,113,95000,"DESILTING OF STORM WATER DRAIN AT DHARMAPURAM MAIN ROAD IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2912,Storm Water Drain,Completed,NJ-TEYNAMPET,113,95000,"DESILTING OF STORM WATER DRAIN AT THIRUMOORTHY NAGAR MAIN ROAD IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2916,Storm Water Drain,Completed,NJ-TEYNAMPET,113,95000,"DESILTING OF STORM WATER DRAIN AT THIRUMOORTHY NAGAR 5th STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2962,Storm Water Drain,Completed,NJ-TEYNAMPET,113,117000,"DESILTING OF STORM WATER DRAIN AT JAGANATHAN ROAD IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2964,Storm Water Drain,Completed,NJ-TEYNAMPET,113,79000,"DESILTING OF STORM WATER DRAIN AT THIRUMOORTHY NAGAR 6th STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2966,Storm Water Drain,Completed,NJ-TEYNAMPET,113,114000,"DESILTING OF STORM WATER DRAIN AT KRISHNAMA ROAD IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2973,Storm Water Drain,Completed,NJ-TEYNAMPET,113,94000,"DESILTING OF STORM WATER DRAIN AT VIDVAN SUNDARAM STREET IN DN113,UNIT-26,ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2976,Storm Water Drain,Completed,NJ-TEYNAMPET,113,126000,"DESILTING OF STORM WATER DRAIN AT THIRUMALAI PILLAI ROAD IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2982,Storm Water Drain,Completed,NJ-TEYNAMPET,113,24600,"DESILTING OF STORM WATER DRAIN AT KUMARAPPA LANE IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2985,Storm Water Drain,Completed,NJ-TEYNAMPET,113,130000,"DESILTING OF STORM WATER DRAIN AT NAGESHWARA RAO ROAD IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3013,Storm Water Drain,Completed,NJ-TEYNAMPET,113,88000,"DESILTING OF STORM WATER DRAIN AT THIRUMOORTHY NAGAR 3RD STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3015,Storm Water Drain,Completed,NJ-TEYNAMPET,113,114000,"DESILTING OF STORM WATER DRAIN AT THIRUMOORTHY NAGAR 2ND STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3017,Storm Water Drain,Completed,NJ-TEYNAMPET,113,187000,"DESILTING OF STORM WATER DRAIN AT THIRUMOORTHY NAGAR 1ST STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3251,Buildings,Completed,NJ-TEYNAMPET,113,770000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR CI OFFICE BUILDING UNDER WARD COUNCILLOR FUND AT VALLUVARKOTTAM HIGH ROAD (JUNCTION OF TANK BUND ROAD) IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3422,Footpath,Completed,NJ-TEYNAMPET,113,998000,"PROVIDING AND LAYING INTERLOCKING PAVER BLOCKS TO THE ROAD EDGES AT JAGANNATHAN ROAD ON BOTH SIDES UNDER WARD COUNCILLOR FUND IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3476,Footpath,Completed,NJ-TEYNAMPET,113,999000,"PROVIDING AND LAYING INTER LOCKING PAVER BLOCKS TO THE ROAD EDGES AT KUMARAPPA STREET ON BOTH SIDE UNDER WARD COUNCILLOR FUND IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3727,Buildings,Completed,NJ-TEYNAMPET,113,958000,"Desilting of Mambalam Canal and removing the debris using machinery including Bio metric taken for encroachers along Mambalam canal (from Vidyodaya Main Road to G.N.Chetty Road) in Div 113,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3869,Storm Water Drain,Completed,NJ-TEYNAMPET,113,102000,"DESILTING OF STORM WATER DRAIN AT KRISHNABAI STREET IN DN113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3882,Storm Water Drain,Completed,NJ-TEYNAMPET,113,122000,"DESILTING OF STORM WATER DRAIN AT SIVASAILAM STREET IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3885,Storm Water Drain,Completed,NJ-TEYNAMPET,113,166000,"DESILTING OF STORM WATER DRAIN AT SARATHY STREET IN DN 113,UNIT-26,ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/3892,Storm Water Drain,Completed,NJ-TEYNAMPET,113,246000,"DESILTING OF STORM WATER DRAIN AT NORTH USMAN ROAD IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3894,Storm Water Drain,Completed,NJ-TEYNAMPET,113,98000,"DESILTING OF STORM WATER DRAIN AT PERIYAR ROAD IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3895,Storm Water Drain,Completed,NJ-TEYNAMPET,113,229000,"DESILTING OF STORM WATER DRAIN AT PRAKASAM STREET IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3897,Storm Water Drain,Completed,NJ-TEYNAMPET,113,110000,"DESILTING OF STORM WATER DRAIN AT VIDYODAYA MAIN ROAD IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3899,Storm Water Drain,Completed,NJ-TEYNAMPET,113,800000,"DESILTING OF STORM WATER DRAIN AT UTTHAMAR GANDHI SALAI IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3901,Storm Water Drain,Completed,NJ-TEYNAMPET,113,306000,"DESILTING OF STORM WATER DRAIN AT KODAMBAKKAM HIGH ROAD IN DN 113,UNIT-26,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3902,Storm Water Drain,Completed,NJ-TEYNAMPET,113,188000,"DESILTING OF STORM WATER DRAIN AT JOSIER STREET IN DN 113,UNIT-26,Z-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3903,Storm Water Drain,Completed,NJ-TEYNAMPET,113,235000,"DESILTING OF STORM WATER DRAIN AT CATHEDRAL GARDEN ROAD IN DN 113,UNIT-26,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3906,Storm Water Drain,Completed,NJ-TEYNAMPET,113,169000,"DESILTING OF STORM WATER DRAIN AT VALLUVAR KOTTAM HIGH ROAD IN DN 113,UNIT-26,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/4716,Footpath,Completed,NJ-TEYNAMPET,113,832000,"IMPROVEMENTS TO DAMAGED FOOTPATH AND PAINTING TO FOOTPATH KERBS AT NUNGAMBAKKAM HIGH ROAD IN DIVISION 113,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/5590,Buildings,Completed,NJ-TEYNAMPET,113,288000,"IMPROVEMENTS TO PUBLIC CONVINIENCE NEAR CORPORATION LANE (ASSET CODE NO 033/9847/702/2014-15) AT KODAMBAKKAM HIGH ROAD IN DN 113,UNIT-26, ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/5687,Buildings,Completed,NJ-TEYNAMPET,113,275000,"IMPROVEMENTS TO PUBLIC CONVENIENCE (ASSET CODE NO 033/10511/1096/2015-16) AT SEERANIPURAM IN DN 113,UNIT-26, ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/6427,Storm Water Drain,Completed,D-Storm Water Drains,113,19600000,"IMPROVEMENTS TO STORM WATER DRAIN AT HABIBULLAH ROAD IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/7658,Road Cut,Completed,NJ-TEYNAMPET,113,282000,"RESTORATION OF ROAD CUT MADE BY TNEB AT RAMANUJAM STREET IN DN 113,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 L/2016-17/13701,Electrical,Completed,L-Electrical,114,673400,"Replacement of 17 nos of Damaged Kiosk Pillar Boxes at Kamaraj Salai, Marina Beach Service Road and Various locations in Division 114, 115,116 and 120 Zone IX.",Own Sources,9,2016-17,2017-18 L/2016-17/15914,Electrical,Completed,L-Electrical,114,962600,"Estimate for Replacement of 14 Nos 400 W MH Fitting with 12 Nos of 240 - 300 watts LED Fitting and for Carrying out maintaince work for the High Mast of MGR Memorial back side, Marina beach service Road in Div-114 under Zone-IX.",Own Sources,9,2016-17,2017-18 L/2016-17/18957,Electrical,Completed,L-Electrical,114,197800,Removal & Refixing & Replacement of accessories and maintenance work for the High mast of Gandhi Statue (Back side ) Marina beach service Road (Sand area) in div-121 under Zone-IX.,Own Sources,9,2016-17,2017-18 L/2016-17/2370,Electrical,Completed,L-Electrical,114,198500,"Estimate for Replacement of accessories and maintaince work for the High Mast of Anna Square back side,Marina Beach Service Road,(sand area) in Div-114 under Zone-IX.",Own Sources,9,2016-17,2017-18 L/2016-17/8129,Electrical,Completed,L-Electrical,114,188700,"Painting of 603 Nos of 8/9.2 Mtr lamp post at Kamaraj Salai on Both sides from Napier Bridge to Light house and Radhakrishnan Salai, Avvai Shanmugam Salai DR. Besant Road , Santhome high road and Bharathy Salai in Div-114,116,120,121,125 Zone -IX.",Own Sources,9,2016-17,2016-17 NJ/2016-17/0475,Footpath,Completed,NJ-TEYNAMPET,114,178000,"Providing Black and White paint in Footpath and center median at kamarajar salai & sivananda salai in Dn-114,U-27,Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0725,Footpath,Completed,NJ-TEYNAMPET,114,994000,"REPAIRS AND IMPROVEMENTS TO FOOTPATH AT WALLAJAH ROAD AND KAMARAJAR SALAI IN DN-114,116,120 AND 121 ,UNIT-27,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/1039,Parks,Completed,NJ-TEYNAMPET,114,999000,"Repairs to damaged granite slab & Tiles in footpath and gallery area at marina beach(neppiar bridge to Gallery 8) in Dn-114 & 116 in U-27A,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14009,Buildings,Completed,NJ-TEYNAMPET,114,160000,"Improvements to public convenience at victoria hostel road and jony basha street in Div-114, U-27,Z-9.",Own Sources,9,2016-17,2018-19 NJ/2016-17/14246,Grade Separator,Completed,NJ-TEYNAMPET,114,334000,"Improvements to chennai middle school at Bangaru street in Div-114,U-27,Z-9.",Own Sources,9,2016-17,2018-19 NJ/2016-17/1434,Parks,Completed,NJ-TEYNAMPET,114,735000,"SUPPLYING AND PLANTATION OF NEW PLANTS TO LAWN NO 1 AT MARINA BEACH IN DIV-114, U-27A, Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/1435,Parks,Completed,NJ-TEYNAMPET,114,976000,"SUPPLYING AND PLANTATION OF NEW PLANTS TO LAWN NO 2 AT MARINA BEACH IN DIV-114, U-27A, Z-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/14392,Buildings,Completed,NJ-TEYNAMPET,114,189000,"Improvements to chennai middle school at Bells road and typhoon alikhan street in Div-114,U-27,Z-9.",Own Sources,9,2016-17,2018-19 NJ/2016-17/1488,Parks,Completed,NJ-TEYNAMPET,114,694000,SUPPLYING AND PLANTATION OF NEW PLANTS TO LAWN NO 3 (PART 2) AT MARINA BEACH IN DN-114 U-27A Z-9,Own Sources,9,2016-17,2016-17 NJ/2016-17/15886,Parks,Completed,NJ-TEYNAMPET,114,648000,"Improvements to marina lawn (1-4) due to VARDHA cyclone affected area in Div-114, U-27A, Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17984,Roads,Completed,NJ-TEYNAMPET,114,1730000,"ATTENDING PATCH WORK AT VALLABA AGRAHARAM STREET AND OTHER STREETS IN DN 114,115,116,120 & 121 IN UNIT-27,ZONE9",Own Sources,9,2016-17,2017-18 NJ/2016-17/18483,Buildings,Completed,NJ-TEYNAMPET,114,190000,"Improvements to chennai Urudu middle school at Vallaba agraharam street in Div-114,U-27,Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2653,Storm Water Drain,Completed,NJ-TEYNAMPET,114,125000,"Desilting and repairs to the storm water drain at Mosque Street IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2654,Storm Water Drain,Completed,NJ-TEYNAMPET,114,92000,"Desilting and repairs to the storm water drain at Habibulla street IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2655,Storm Water Drain,Completed,NJ-TEYNAMPET,114,200000,"Desilting and repairs to the strom water drain at Bangaru street IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2656,Storm Water Drain,Completed,NJ-TEYNAMPET,114,200000,"Desilting and repairs to the strom water drain at Pillaiyar Koil Street IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2657,Storm Water Drain,Completed,NJ-TEYNAMPET,114,108000,"Desilting and repairs to the storm water drain at Subathral Street IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2658,Storm Water Drain,Completed,NJ-TEYNAMPET,114,108000,"Desilting and repairs to the storm water drain at Sydoji Street IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2659,Storm Water Drain,Completed,NJ-TEYNAMPET,114,188000,"Desilting and repairs to the storm water drain at Bharathi Salai IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2661,Storm Water Drain,Completed,NJ-TEYNAMPET,114,388000,"Desilting and repairs to the storm water drain at Bells Road IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2662,Storm Water Drain,Completed,NJ-TEYNAMPET,114,440000,"Desilting and repairs to the strom water drain at Quiade -Millath salai IN DN-114, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2877,Roads,Completed,NJ-TEYNAMPET,114,600000,"PAINTING BLACK AND WHITE TO THE FOOTPATH KERB AT KAMARAJAR SALAI ( FROM NAPIER BRIDGE TO KANNAGI STATUE) AND VARIOUS ROADS IN DN-114& 125 UNIT-25 & 27, ZONE-09",Own Sources,9,2016-17,2016-17 NJ/2016-17/3570,Roads,Completed,NJ-TEYNAMPET,114,314000,"RELAYING CEMENT CONCRETE ROAD AT SANNATHI LANE IN DN-114,UNIT-27,ZONE-9 (FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/3571,Roads,Completed,NJ-TEYNAMPET,114,254000,"RELAYING OF CEMENT CONCRETE ROAD AT KRISHNAPPA LANE IN DN-114,UNIT-27,ZONE-9 (FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/3573,Roads,Completed,NJ-TEYNAMPET,114,193000,"RALAYING OF CEMENT CONCRETE ROAD AT O.V.M LANE IN DN-114,UNIT-27,ZONE-9( FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/3575,Roads,Completed,NJ-TEYNAMPET,114,393000,"RELAYING OF CEMENT CONCERTE ROAD AT PARTHASARTHY (N) LANE IN DN-114,UNIT-27,ZONE-9 (FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/3765,Playfields,Completed,NJ-TEYNAMPET,114,638000,"SUPPLYING AND FIXING GYM EQUIPMENTS TO GYM BUILDING AT ARUNCHALAM STREET IN DN-114,UNIT-27,ZONE-9 (FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/3769,Playfields,Completed,NJ-TEYNAMPET,114,700000,"SUPPLYING GYM EQUIPMENTS AND IMPROVEMENTS TO GYM BUILDING AT JANI BASHA STREET IN DN-114,UNIT-27,ZONE-9 ( FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/3774,Roads,Completed,NJ-TEYNAMPET,114,211000,"RELAYING CEMENT CONCRETE ROAD AT AKBAR 1ST LANE IN DN-114,UNIT-27,ZONE-9 ( FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/3776,Roads,Completed,NJ-TEYNAMPET,114,297000,"RELAYING CEMENT CONCRETE ROAD AT AKBAR 2ND LANE IN DN-114,UNIT-27,ZONE-9( FOR WARD COUNCILLOR FUND)",Own Sources,9,2016-17,2017-18 NJ/2016-17/7835,Buildings,Completed,NJ-TEYNAMPET,114,360000,"IMPROVEMENTS TO PC BEHIND MARINA SWIMMING POOL ,BEHIND LABOUR STATUE ,BEHIND MGR MEMORIAL AND ANNA SWIMMING POOL IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/8177,Footpath,Completed,P-Parks and Playfields,114,34665372,"PROPOSED NEW ANNA PARK LANDSCAPING , PLANTED GREENARY PLANTS AND FIXING PLAY APPARATUS AT KAMARAJAR SALAI ADJACENT TO ANNA SQUARE IN DN 114, UNIT-27A,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/9202,Roads,Completed,NJ-TEYNAMPET,114,423000,"RELAYING THE EXISTING B.T. ROAD WITH BCCMP1 BY PAVER AT MOSQUE STREET IN DIV-114, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/9211,Roads,Completed,NJ-TEYNAMPET,114,440000,"RELAYING THE EXISTING B.T. ROAD WITH BCCMP1 BY PAVER AT VENKATESAN STREET IN DIV-114, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 BR/2016-17/11346,Roads,Completed,BR-Bus Route Roads,115,883000,"Attending Patch works at approach roads of Peters Road in Dn-115, Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/0108,Buildings,Completed,NJ-TEYNAMPET,115,885000,"PROVIDING ELECTION BOOTH BARRICADING WORKS,PAINTING WORKS, PLYWOOD PARTITION WORKS AND RAMPS FOR TAMILNADU ASSEMBLY GENERAL ELECTION 2016 IN DIVISION 114,115,116 AND 121 UNIT 27 ZONE 09",Own Sources,9,2016-17,2016-17 NJ/2016-17/0289,Buildings,Completed,NJ-TEYNAMPET,115,24900,"Supplying and fixing of plumbing and electrical materials in community college at Mir Bakshi Ali street road in div-115,u-27,z-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/0290,Buildings,Completed,NJ-TEYNAMPET,115,24900,"Supplying and fixing of plumbing and electrical materials in cms at Soorappan street road in div-115,u-27,z-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/0292,Buildings,Completed,NJ-TEYNAMPET,115,24500,"Supplying and fixing of plumbing and electrical materials in NUHM at R.O.B street road in div-115,U-27,Z-09.",Own Sources,9,2016-17,2018-19 NJ/2016-17/0295,Buildings,Completed,NJ-TEYNAMPET,115,24900,"Supplying and fixing of over head tank, wash basin, pipe laying, tube light with patty and ceiling fan in S.I.office in westcot road in div-115,U-27,Z-09.",Own Sources,9,2016-17,2018-19 NJ/2016-17/14034,Buildings,Completed,NJ-TEYNAMPET,115,109000,"IMPROVEMENTS WORKS TO PC AT MANICKAM(N) STREET IN DIV 115,U-27,Z-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14274,Buildings,Completed,NJ-TEYNAMPET,115,258000,"IMPROVEMENTS WORK S OF CPS,CPUS & CMS SCHOOL AT BESANT ROAD,SOORAPPAN STREET IN DIV-115,U-27,Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15915,Buildings,Completed,NJ-TEYNAMPET,115,45000,"REPAIRS AND MAINTENANCE WORKS AT CORPORATION OFFICE AT WEST COTT ROAD AND COMMUNITY HALL AT MIR BAKSHI ALI STREET IN DN-115,UNIT27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2357,Buildings,Completed,NJ-TEYNAMPET,115,999000,"CONSTRUCTION OF GYM BUILDING IN FIRST FLOOR OF ICDS AT THIRUNAVUKARASU STREET IN DN-115,UNIT-27,ZONE-9 ( COUNCILLOR FUND )",Own Sources,9,2016-17,2016-17 NJ/2016-17/2365,Buildings,Completed,NJ-TEYNAMPET,115,683000,"PROVIDING DRAINAGE ,PLUMBING ARRANGEMENTS ANG SUPPLYING GYM EQUIPMENTS TO GYM BUILDING IN FIRST OF ICDS AT THIRUNAVUKARASU STREET IN DN-115,UNIT-27,ZONE-9 ( COUNCILLOR FUND )",Own Sources,9,2016-17,2016-17 NJ/2016-17/2369,Buildings,Completed,NJ-TEYNAMPET,115,352000,"CONSTRUCTION OF COMPOUND WALL AROUND TRANSFORMER OPP TO ROYAPETTAH GOVT HOSPITAL AT WEST COTT ROAD IN DN-115,UNIT-27,ZONE-9 ( COUNCILLOR FUND )",Own Sources,9,2016-17,2016-17 NJ/2016-17/2374,Storm Water Drain,Completed,NJ-TEYNAMPET,115,965000,"DISMANTLING AND RECONSTRUCTION THE STORM WATER DRAIN ( PART ) AT SHEIK DAWOOD STREET JN OF DR. BESANT ROAD AND MALLAN PONAPPAN STREET(PART) JN OF AGATHI MUTHAN STREET TO THIRUNAVUKARASU STREET IN DN-115,UNIT-27,ZONE-9 ( COUNCILLOR FUND )",Own Sources,9,2016-17,2016-17 NJ/2016-17/2827,Storm Water Drain,Completed,NJ-TEYNAMPET,115,120000,"DESILTING AND REPAIRS TO STORM WATER DRAIN AT SUBRAMANYA GARDEN STREET IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2828,Storm Water Drain,Completed,NJ-TEYNAMPET,115,175000,"DESILTING AND REPAIRS TO STORM WATER DRAIN AT DR.NIYAMATHULLAH STREET IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2832,Storm Water Drain,Completed,NJ-TEYNAMPET,115,155000,"DESILTING AND REPAIRS TO STORM WATER DRAIN AT MALLAN PONAPPAN STREET IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2839,Storm Water Drain,Completed,NJ-TEYNAMPET,115,960000,"DESILTING AND REPAIRS TO STORM WATER DRAIN AT DR. BESANT ROAD ( NORTH AND SOUTH SIDE ) IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2847,Buildings,Completed,NJ-TEYNAMPET,115,599000,"DESILTING AND REPAIRS TO STORM WATER DRAIN AT WEST COTT ROAD ( EAST AND WEST SIDE IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2863,Storm Water Drain,Completed,NJ-TEYNAMPET,115,146000,"DESILTING AND REPAIRS TO STORM WATER DRAIN AT MR.O.B MAIN STREET IN DN-115,UNIT-27",Own Sources,9,2016-17,2017-18 NJ/2016-17/8017,Buildings,Completed,NJ-TEYNAMPET,115,694000,"DESILTING AND REPAIRS TO STORM WATER DRAIN AT ROB 4TH STREET , ROB 5TH STREET, SHEIK DAWOOD STREET, THANGAVELU VAITHYAR STREET IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/8019,Storm Water Drain,Completed,NJ-TEYNAMPET,115,932000,"DESILTING AND REPAIRS TO STORM WATER DRAIN ATAMIR MAHAL ROAD,DEVARAJAN STREET,JOHNY JAHAN KHAN ROAD,PETERS ROAD IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/9248,Roads,Completed,NJ-TEYNAMPET,115,208000,"RELAYING THE EXISTING BT ROAD WITH BCCMP1 BY PAVER AT KAREEM SUBATHAR STREET INDIV-115,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 D/2016-17/6005,Storm Water Drain,Completed,D-Storm Water Drains,116,919000,"Dismantling slab & Invert Correction Existing storm water Drain of size 900x900mm along Dr.Besant Road from T.P.Street junction to T.P.Kovil 2nd street in Dn-116,Zone-IX.",Own Sources,9,2016-17,2016-17 L/2016-17/11864,Electrical,Completed,L-Electrical,116,371800,"Erection of 3 nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single Arch Bracket, 2 nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single straight Bracket and 4 nos 30w-60w Flood type LED fitting at Dr.Annibesent park, Kamaraj salai juncetion Dr.Besent road in Division-116,Zone-IX",Own Sources,9,2016-17,2018-19 L/2016-17/18955,Electrical,Completed,L-Electrical,116,194200,Removal & Refixing & Replacement of accessories and maintenance work for the 30 Mtr High mast of Partha sarathy Tempie (East Arch Entrance opp ) Marina beach service Road (Sand area) in div-116 under Zone-IX.,Own Sources,9,2016-17,2018-19 L/2016-17/7140,Electrical,Completed,L-Electrical,116,2026200,"Erection of 31 Nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single Arch Bracket with 31 Nos 90w-120w LED fitting, 7 Nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single straight Bracket with 7 Nos 40w-50w LED fitting at Ayodhiya Kuppam in Division-116,Zone-IX",Deposit Works,9,2016-17,2016-17 NJ/2016-17/0093,Buildings,Completed,NJ-TEYNAMPET,116,24900,"Supplying and fixing of Jet motor, taps,ball valve, pipe laying and motor repair in Amma unavagam building at venkatarangam street in DIV-116, UNIT-27, ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/0096,Buildings,Completed,NJ-TEYNAMPET,116,994000,"IMPROVEMENTS TO TRIPLECANE MLA OFFICE AT Dr.BESANT ROAD IN DN-116,U-27,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/0337,Buildings,Completed,NJ-TEYNAMPET,116,24900,"supplying and fixing plumbing and electrical items in cms at venkatrangam street in dn-116, U-27,Z-9.",Own Sources,9,2016-17,2018-19 NJ/2016-17/14013,Buildings,Completed,NJ-TEYNAMPET,116,40000,"Improvements to the Public convenience at Marina service road in div-116,unit-27,zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/14015,Buildings,Completed,NJ-TEYNAMPET,116,80000,"Improvements to the Public convenience at Bharathi salai(opp to V.R.Pillai street),Bharathi salai Near B canal and Palaniamman koil 6th street in div-116,unit-27,zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/14017,Buildings,Completed,NJ-TEYNAMPET,116,144000,"Improvements to the Public convenience at Dr.Besant road (Near metro water),Dr.Besant road B canal and Car street in div-116,unit-27,zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/14267,Buildings,Completed,NJ-TEYNAMPET,116,311000,"Improvements to CMS School at Triplicane High Road in Div-116,Unit-27,Zone-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/1456,Roads,Completed,NJ-TEYNAMPET,116,694000,"SUPPLYING AND PLANTATION OF NEW PLANTS TO LAWN NO 6 AT MARINA BEACH IN DIV 116,UNIT-27A,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/15825,Buildings,Completed,NJ-TEYNAMPET,116,679000,"IMPROVEMENTS TO THE UNIT-27 OFFICE AT Dr.BESANT ROAD (VARDHA )IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/15941,Buildings,Completed,NJ-TEYNAMPET,116,122000,"IMPROVEMENTS TO THE ANGANVADI AT SIVARAJAPURAM ( Vardah Cyclone )IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/15942,Buildings,Completed,NJ-TEYNAMPET,116,179000,"IMPROVEMENTS TO THE CMS SCHOOL AT VENKATRANGAM STREET (Vardah Cyclone)IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/15943,Parks,Completed,NJ-TEYNAMPET,116,537000,"IMPROVEMENTS TO THE FENCING & GREENARY FOR MARINA LAWN No.5 TO 8 AT MARINA SERVICE ROAD (Vardah Cyclone )IN DIV-116, UNIT-27A, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/15944,Buildings,Completed,NJ-TEYNAMPET,116,79000,"IMPROVEMENTS TO THE AMMA UNAVAGAM (PHASE-I) AT VENKATRANGAM STREET (VARDHA CYCLONE )IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/15946,Buildings,Completed,NJ-TEYNAMPET,116,53000,"IMPROVEMENTS TO THE AMMA UNAVAGAM (PHASE-II) AT VENKATRANGAM STREET (VARDHA CYCLONE ) IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2317,Roads,Completed,NJ-TEYNAMPET,116,492000,"PROVIDING BASE CONCRETE FOR GARBAGE BINS (20Nos) AT QUIDE MILATH ROAD,Dr.BESANT ROAD,,BHARATHI SALAI,VENKATRANGAM STREET,B.V NAICKEN STREET,CAR STREET,SINGACHARI STREET,SOUTH MADA STREET,T.P.KOIL STREET,CANAL STREET, ETC., DN-116, U-27,Z-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2546,Storm Water Drain,Completed,NJ-TEYNAMPET,116,995000,IMPROVEMENTS TO THE FOOTPATH INFRONT OF CMS AT QUIDE MILLATH ROAD IN DN-116 U-27 Z-9[COUNCILAR FUND 2016-17],Own Sources,9,2016-17,2016-17 NJ/2016-17/2575,Storm Water Drain,Completed,NJ-TEYNAMPET,116,990000,PROVIDING FLOORING ARRANGEMENTS FOR CLASS ROOMS AND IMPROVEMENTS TO THE BABY TOILETS IN CHENNAI MIDDLE SCHOOL AT QUIDE MILLATH ROAD IN DN-116 U-27 Z-9.[COUNCILAR WARD DEVELOPMENT FUND 2016-17],Own Sources,9,2016-17,2016-17 NJ/2016-17/2578,Playfields,Completed,NJ-TEYNAMPET,116,997000,PROVIDING ARRANGEMENTS FOR CHILDRENS PLAY FIELD AT CANAL STREET IN DN-116 U-27 Z-9[MP FUND],MPLADS,9,2016-17,2016-17 NJ/2016-17/2580,Playfields,Completed,NJ-TEYNAMPET,116,998000,PROVIDING ARRANGEMENTS FOR VOLLEYBALL GROUND AT CANAL STREET IN DN-116 U-27 Z-9 [MP FUND],MPLADS,9,2016-17,2016-17 NJ/2016-17/2621,Roads,Completed,NJ-TEYNAMPET,116,985000,"LAYING THE CEMENT CONCRETE ROAD AT PALANIAMMAN KOIL NORTH 2nd, 3rd STREET AND PALANIAMMAN KOIL SOUTH 4th STREET IN Dn-116,U-27,Z-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2624,Playfields,Completed,NJ-TEYNAMPET,116,673000,"PROVIDING THE FENCING ARRANGEMENTS TO THE VOLLEY BALL GROUND AT CANAL STREET IN Dn-116,U-27,Z-9 [MP FUND]",MPLADS,9,2016-17,2016-17 NJ/2016-17/2664,Storm Water Drain,Completed,NJ-TEYNAMPET,116,62000,"Desilting and repairs to the strom water drain at South mada street in DN-116, U-27, Z-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2665,Storm Water Drain,Completed,NJ-TEYNAMPET,116,22000,"Desilting and repairs to the strom water drain at T.P Koil 2nd lane in DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2668,Storm Water Drain,Completed,NJ-TEYNAMPET,116,8000,"Desilting and repairs to the strom water drain at Raja hanumantha lala street IN DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2669,Storm Water Drain,Completed,NJ-TEYNAMPET,116,45000,"Desilting and repairs to the strom water drain at Bandi venkatesan street in DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2670,Storm Water Drain,Completed,NJ-TEYNAMPET,116,265000,"Desilting and repairs to the strom water drain at Big street in DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2671,Storm Water Drain,Completed,NJ-TEYNAMPET,116,8000,"Desilting and repairs to the strom water drain at Raja hanumantha lala lane in DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2672,Storm Water Drain,Completed,NJ-TEYNAMPET,116,814000,"Desilting and repairs to the strom water drain at Quiade -Millath Road IN DN-116, U-27, Z-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2730,Storm Water Drain,Completed,NJ-TEYNAMPET,116,516000,"Desilting and repairs to the strom water drain at Dr,Besant road IN DN-116, U-27, Z-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2731,Storm Water Drain,Completed,NJ-TEYNAMPET,116,19300,"Desilting and repairs to the strom water drain at Venkatarangam street in DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2732,Storm Water Drain,Completed,NJ-TEYNAMPET,116,489000,"Desilting and repairs to the strom water drain at Bharathi salai in DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2733,Storm Water Drain,Completed,NJ-TEYNAMPET,116,108000,"Desilting and repairs to the strom water drain at car street in DN-116, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/4514,Roads,Completed,NJ-TEYNAMPET,116,269000,PROVIDING NAME BOARDS (5NOS) AND RECTIFICATION OF STREET NAME BOARDS (25NOS) IN DN-116 U-27 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/5851,Buildings,Completed,NJ-TEYNAMPET,116,695000,"IMPROVEMENT TO OLD RCC BUS SHELTER AT Dr.BESANT ROAD NEAR NKT SCHOOL(1NO), IN FRONT OF UNIT-27 OFFICE (2NOS), AND BHARATHI SALAI NEAR ARCH (1NO), NEAR ADYAR ANANDA BHAVAN (1NO) UNDER 2016-2017 COUNCILLOR WARD DEVELOPMENT SCHEME IN DN-116,U-27, Z-IX.",Own Sources,9,2016-17,2016-17 NJ/2016-17/8572,Roads,Completed,NJ-TEYNAMPET,116,933000,"Out sourcing Men and Material for cleaning of public convenience at Marina service road in dn-114,116 and 125 Unit-27A Zone-9.(6-Location-92 days)",Own Sources,9,2016-17,2019-20 B/2016-17/8144,Buildings,Completed,B-Buildings,117,997000,"ADDITIONAL WORKS IN EXISTING COMMUNITY CENTRE AT DR.GIRIAPPA ROAD IN DN-117, ZONE-9",Own Sources,9,2016-17,2017-18 BR/2016-17/18124,Footpath,Completed,BR-Bus Route Roads,117,1487000,Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at G.N.Chetty Road and North Usman Road in Zone 9,Grants,9,2016-17,2017-18 BR/2016-17/6480,Roads,Completed,BR-Bus Route Roads,117,922000,"Providing and Laying Mastic Asphalt at G.N.Chetty Road (Centre Median South Side jn of Narasimman Road) & College Road in Dn-111 & 117, Zone-9",Own Sources,9,2016-17,2016-17 BR/2016-17/9154,Roads,Completed,BR-Bus Route Roads,117,6860000,"Strengthening and relaying the road with DBM & CBC after cold milling by Paver finisher using plastic waste along with traffic improvement works at Gopathi Narayana (C) Road (Part) from the jn of Dr.Nair road to the jn of North Boag Road (Southern side) in Dn - 117 , Zone - 9",Grants,9,2016-17,2017-18 D/2016-17/3270,Storm Water Drain,Completed,D-Storm Water Drains,117,1479000,"Dismantling Slab and Desilting Re-construction of storm water drain of size 900x900mm North Usman road Storm water drain From Habibullah road junction to Buzullah Road junction.Div-117,Zone-IX.",Own Sources,9,2016-17,2016-17 J/2016-17/18770,Bridges,Completed,J-Bridges,117,1500000,"Repair and Re-Constructions of hand rail wall in Bridge across Mambalam canal at venkatnarayana road in Dn-117, Zone-IX.",Grants,9,2016-17,2017-18 NJ/2016-17/11501,Buildings,Completed,NJ-TEYNAMPET,117,998000,"Supply, Installation,Commissioning of High Quality Treated Drinking WaterPlant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at Vijayaraghava Road in Dn 117,Unit-26, Zone -9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13121,Roads,Completed,NJ-TEYNAMPET,117,900000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT NORTH CRESCENT STREET IN DIVISION 117 UNIT 26 ZONE 09,Deposit Works,9,2016-17,2017-18 NJ/2016-17/13122,Roads,Completed,NJ-TEYNAMPET,117,705000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT LAKSHMI COLONY IN DIVISION 117 UNIT 26 ZONE 09,Deposit Works,9,2016-17,2017-18 NJ/2016-17/13131,Roads,Completed,NJ-TEYNAMPET,117,423000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT GIRI ROAD IN DIVISION 117 UNIT 26 ZONE 09,Deposit Works,9,2016-17,2017-18 NJ/2016-17/13581,Roads,Completed,NJ-TEYNAMPET,117,998000,CONSTRUCTION OF AMMA DRINKING WATER SHED AT VIJAYARAGAVA ROAD IN DIVISION 117 UNIT 26 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/14147,Buildings,Completed,NJ-TEYNAMPET,117,63000,"Minor Repairs to Public Convenience at Theyagaraya Road in Dn 117, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14151,Buildings,Completed,NJ-TEYNAMPET,117,64000,"Minor Repairs to Public Convenience at Dr.Giriyappa Road (Drivers Colony) in Dn 117, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14152,Buildings,Completed,NJ-TEYNAMPET,117,38000,"Minor Repairs to Public Convenience at Dr.Giriyappa Road (North) in Dn 117, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14154,Buildings,Completed,NJ-TEYNAMPET,117,86000,"Minor Repairs to Public Convenience at M.K.Radha Nagar in Dn 117, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14158,Buildings,Completed,NJ-TEYNAMPET,117,38000,"Minor Repairs to Public Convenience at North Usman Road in Dn 117, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14159,Buildings,Completed,NJ-TEYNAMPET,117,70000,"Minor Repairs to Public Convenience at Mambalam High Road in Dn 117, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14160,Buildings,Completed,NJ-TEYNAMPET,117,97000,"Minor Repairs to Public Convenience at Sarangapani Street in Dn 117, Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14322,Buildings,Completed,NJ-TEYNAMPET,117,217000,"Improvements to Chennai Primary School at Giriappa Road in Dn 117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14323,Buildings,Completed,NJ-TEYNAMPET,117,290000,"Improvements to Chennai Middle School Erikarai in Dn 117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15857,Buildings,Completed,NJ-TEYNAMPET,117,220000,REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT THIRU-VI-KA KUDIYIRUPU IN DIVISION 117 UNIT 26 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16247,Footpath,Completed,NJ-TEYNAMPET,117,160000,"Repairs to Foot Path at Thyagaraya Road in Dn-117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16253,Footpath,Completed,NJ-TEYNAMPET,117,81000,"Repairs to Foot Path at Thanikachalam Road in Dn-117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16255,Footpath,Completed,NJ-TEYNAMPET,117,124000,"Repairs to Foot Path at North Boag Road in Dn-117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16263,Footpath,Completed,NJ-TEYNAMPET,117,153000,"Repairs to Foot Path at Vaidhiraman Street in Dn-117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16266,Storm Water Drain,Completed,NJ-TEYNAMPET,117,335000,"Repairs to Storm Water Drain at Sadasivam Street in Dn-117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16272,Storm Water Drain,Completed,NJ-TEYNAMPET,117,223000,"Repairs to Storm Water Drain at Mambalam High Road in Dn-117,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16374,Buildings,Completed,NJ-TEYNAMPET,117,324000,"REPAIRS TO DIVISION OFFICE BUILDING TA CHEVALI SIVAJI GANESAN ROAD IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16375,Buildings,Completed,NJ-TEYNAMPET,117,161000,"REPAIRS TO ICDS AT SOUTH BOAG ROAD TENAMENTS-( CENTRE NO- 33603080113) IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16376,Buildings,Completed,NJ-TEYNAMPET,117,114000,"REPAIRS TO ICDS AT GIRIYAPPA ROAD IN DIV 117, U 26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16377,Buildings,Completed,NJ-TEYNAMPET,117,249000,"REPAIRS TO ICDS AT GIRIYAPPA ROAD TENAMANTS IN DIV 117, U 26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16379,Buildings,Completed,NJ-TEYNAMPET,117,201000,"REPAIRS TO AMMA UNAVAGAM AT RAMAKAMATHUPURAM IN DIV 117, U26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16381,Buildings,Completed,NJ-TEYNAMPET,117,165000,"REPAIRS TO NUHM AT RAMAKAMATHUPRAM IN DIV 117, U-26,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16382,Buildings,Completed,NJ-TEYNAMPET,117,136000,"REPAIRS TO PUBLIC CONVENIENCE AT SS PURAM IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16383,Buildings,Completed,NJ-TEYNAMPET,117,133000,"REPAIRS TO PUBLIC CONVENIENCE AT SARANGAPANI STREET IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16384,Buildings,Completed,NJ-TEYNAMPET,117,138000,"REPAIRS TO PUBLIC CONVENIENCE AT M.K.RADHA NAGAR IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16385,Parks,Completed,NJ-TEYNAMPET,117,240000,"PLANTING TREES TO CHARI PARK AT RAMAKRISHNA STREET IN DIV 117, U-26,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17982,Roads,Completed,NJ-TEYNAMPET,117,520000,"ATTENDING PATCH WORK AT DR SADASIVAM STREET AND OTHER VARIOUS STREETS IN DN 117,UNIT-26,ZONE9",Own Sources,9,2016-17,2017-18 NJ/2016-17/19615,Buildings,Completed,NJ-TEYNAMPET,117,990000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT VIJAYARAGHAVA ROAD IN DIV-117,U-26,Z-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/19768,Buildings,Completed,NJ-TEYNAMPET,117,207000,"REPAIRS TO ICDS AT SOUTH BOAG ROAD TENAMENTS-( CENTRE NO- 33603080114) IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/19769,Buildings,Completed,NJ-TEYNAMPET,117,173000,"REPAIRS TO ICDS AT NAKKEERAN NAGAR IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/19770,Buildings,Completed,NJ-TEYNAMPET,117,237000,"REPAIRS TO COMMUNITY HALL AT GRIYAPPA ROAD IN DIV 117, U-26, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2060,Buildings,Completed,NJ-TEYNAMPET,117,700000,"PROVIDING PLATFORM AROUND E-TOILET AND WATER SUPPLY ARRANGEMENTS AT MAMBALAM HIGH ROAD IN DN 117,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2679,Storm Water Drain,Completed,NJ-TEYNAMPET,117,165000,"Repairs and Desilting of Storm water Drain at Thanikachalam Salai in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2696,Storm Water Drain,Completed,NJ-TEYNAMPET,117,188000,"Repairs and Desilting of Storm water Drain at Vijayaragava Salai in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2698,Storm Water Drain,Completed,NJ-TEYNAMPET,117,340000,"Repairs and Desilting of Storm water Drain at Dr.B.Narasimma Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2699,Storm Water Drain,Completed,NJ-TEYNAMPET,117,77000,"Repairs and Desilting of Storm water Drain at Dr.B.Narasimma Road 1st Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2701,Storm Water Drain,Completed,NJ-TEYNAMPET,117,73000,"Repairs and Desilting of Storm water Drain at Dr.B.Narasimman Road 2nd Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2704,Storm Water Drain,Completed,NJ-TEYNAMPET,117,85000,"Repairs and Desilting of Storm water Drain at Dr.Giriappa Road North in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2709,Storm Water Drain,Completed,NJ-TEYNAMPET,117,316000,"Repairs and Desilting of Storm water Drain at Chevaliar Sivaji Ganesan Road (South) in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2712,Storm Water Drain,Completed,NJ-TEYNAMPET,117,85000,"Repairs and Desilting of Storm water Drain at Melony Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2714,Storm Water Drain,Completed,NJ-TEYNAMPET,117,130000,"Repairs and Desilting of Storm water Drain at Saravana Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2727,Storm Water Drain,Completed,NJ-TEYNAMPET,117,187000,"Repairs and Desilting of Storm water Drain at Dr.Thomas Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2734,Storm Water Drain,Completed,NJ-TEYNAMPET,117,65000,"Repairs and Desilting of Storm water Drain at Chevaliar Sivaji Ganesan Road(TNSCB) in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2737,Storm Water Drain,Completed,NJ-TEYNAMPET,117,251000,"Repairs and Desilting of Storm water Drain at Thirumalai Pillai Nagar in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2742,Storm Water Drain,Completed,NJ-TEYNAMPET,117,255000,"Repairs and Desilting of Storm water Drain at Mambalam high Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2744,Storm Water Drain,Completed,NJ-TEYNAMPET,117,133000,"Repairs and Desilting of Storm water Drain at Ramakrishna Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2745,Storm Water Drain,Completed,NJ-TEYNAMPET,117,128000,"Repairs and Desilting of Storm water Drain at Dr.Sadasivam Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2746,Storm Water Drain,Completed,NJ-TEYNAMPET,117,203000,"Repairs and Desilting of Storm water Drain at Thirumoorthy Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2747,Storm Water Drain,Completed,NJ-TEYNAMPET,117,170000,"Repairs and Desilting of Storm water Drain at Bagirathiammal Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2748,Storm Water Drain,Completed,NJ-TEYNAMPET,117,65000,"Repairs and Desilting of Storm water Drain at Sarangapani Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2751,Storm Water Drain,Completed,NJ-TEYNAMPET,117,169000,"Repairs and Desilting of Storm water Drain at Arulambal Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2752,Storm Water Drain,Completed,NJ-TEYNAMPET,117,128000,"Repairs and Desilting of Storm water Drain at Sivasailam Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2753,Storm Water Drain,Completed,NJ-TEYNAMPET,117,313000,"Repairs and Desilting of Storm water Drain at Giri Road in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2756,Storm Water Drain,Completed,NJ-TEYNAMPET,117,125000,"Repairs and Desilting of Storm water Drain at Valmiki Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2757,Storm Water Drain,Completed,NJ-TEYNAMPET,117,124000,"Repairs and Desilting of Storm water Drain at Chinnaiah Pillai Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2760,Storm Water Drain,Completed,NJ-TEYNAMPET,117,150000,"Repairs and Desilting of Storm water Drain at Theyagaraya Bramani Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/3000,Buildings,Completed,NJ-TEYNAMPET,117,468000,"PROVIDING PLATFORM AROUND E-TOILET AND WATER SUPPLY ARRANGEMENTS AT M.K.RADHA NAGAR IN DN 117,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3060,Storm Water Drain,Completed,NJ-TEYNAMPET,117,39000,"Repairs and Desilting of Storm water Drain at Rajan Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/3066,Storm Water Drain,Completed,NJ-TEYNAMPET,117,37000,"Repairs and Desilting of Storm water Drain at Nagar 3rd Street Bharathi in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/3814,Buildings,Completed,NJ-TEYNAMPET,117,998000,"PROPOSED CONSTRUCTION OF ICDS CENTRE AT DR.THOMAS ROAD IN DN 117,UNIT-26,ZONE-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3859,Buildings,Completed,NJ-TEYNAMPET,117,970000,"Desilting of Mambalam Canal and removing the debris using machinery including Bio metric taken for encroachers along Mambalam canal from Vijaya Raghava Road to S.M. Nagar) in Div 117,Unit-26,Zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/8677,Buildings,Completed,NJ-TEYNAMPET,117,500000,"Providing Water supply arrangements and other improvements to Dr.Giriappa Road Public Conveyance in (Under Ward Councillor fund) in Div 117 , Unit-26, Zone-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/8678,Buildings,Completed,NJ-TEYNAMPET,117,498000,"Construction of Compound wall and other Improvements to M.K.Radha Nagar Public Conveyance -1 and M.K.Radha Nagar Public Conveyance -2 (Under Ward Councillor fund) in Div 117 , Unit-26, Zone-9",Own Sources,9,2016-17,2016-17 BR/2016-17/17340,Footpath,Completed,BR-Bus Route Roads,118,2588000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Dr.Radhakrishnan Salai, cathedral Road and TTK Road in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/17671,Roads,Completed,BR-Bus Route Roads,118,812000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Cathedral Road, Dr.Radhakrishnan Salai, Peters Road, West Cott Road, Kutchery Road, Devanathan Street, Luz Church Road,and Quide Millath Road, in Zone-9",Grants,9,2016-17,2017-18 BR/2016-17/18333,Roads,Completed,BR-Bus Route Roads,118,2448000,"Supplying and Fabricating of Stainless Steel Grill over the existing centre median at Cathedral Road (From the junction of Muthaiah Street to Anna Salai) in Dn-118, Zone-9",Own Sources,9,2016-17,2017-18 BR/2016-17/6664,Roads,Completed,BR-Bus Route Roads,118,2118600,"Providing and Fixing of SS Pipe Grill for Center Median at Cathedral Road from Hotel Chola to Binny Road in Division 118,Zone - 9.",Own Sources,9,2016-17,2017-18 BR/2016-17/6677,Roads,Completed,BR-Bus Route Roads,118,2117300,"Providing and Fixing of SS Pipe Grill for Center Median at Dr. Radha Krishnan Salai from Dr. Radha Krishnan Salai 4th street to P.S. Sivaswami Salai Junction in Division 121, zone - 9. Chainage 0 to 268.",Own Sources,9,2016-17,2016-17 L/2016-17/18614,Electrical,Completed,L-Electrical,118,855900,"Provision of new 20 Nos of 7mtr GI Single arch lamp post and 38 nos of additional arch bracket for service road side at Cathedral road over bridge in Division-118, Zone-IX",Own Sources,9,2016-17,2017-18 NJ/2016-17/13513,Roads,Completed,NJ-TEYNAMPET,118,425000,"Relaying of road with BC 30mm thick at Muthiah street in Division-118, Unit-24, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14235,Buildings,Completed,NJ-TEYNAMPET,118,110000,REPAIRS AND MAINTENANCE TO CHENNAI HIGH SCHOOL AT MUTHAIYA STREET IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2018-19 NJ/2016-17/16182,Storm Water Drain,Completed,NJ-TEYNAMPET,118,115000,Repairs to storm water drain at Mayor sunder rao road in division 118 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16186,Storm Water Drain,Completed,NJ-TEYNAMPET,118,105000,Repairs to storm water drain at Cathedral road in division 118 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16188,Storm Water Drain,Completed,NJ-TEYNAMPET,118,80000,Repairs to storm water drain at Kasturi rangan road in division 118 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16191,Parks,Completed,NJ-TEYNAMPET,118,555000,Repairs to Gopathy narayana park at Muthaiya street in division 118 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16195,Parks,Completed,NJ-TEYNAMPET,118,520000,Repairs to Thiru-Vi-Ka Park at Srinivasa Perumal Sannathi 1st Street in division 118 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16217,Buildings,Completed,NJ-TEYNAMPET,118,500000,Repairs to Community center at Srinivasa Perumal Sannathi 1st street in division 118 unit 24 zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/17893,Footpath,Completed,NJ-TEYNAMPET,118,96000,"REPAIRS TO FOOTPATH AT KASTHURI RANGAN ROAD IN DIVISION 118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17985,Roads,Completed,NJ-TEYNAMPET,118,1920000,"ATTENDING PATCH WORK AT STREET LAKE AREA AND OTHER STREETS IN DN 109,110,111,118 & 119 IN UNIT-24,ZONE9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3163,Storm Water Drain,Completed,NJ-TEYNAMPET,118,530000,Desilting of Storm Water Drain at Cathedral Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3164,Storm Water Drain,Completed,NJ-TEYNAMPET,118,95000,Desilting of Storm Water Drain at T.T.K Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3165,Storm Water Drain,Completed,NJ-TEYNAMPET,118,95000,Desilting of Storm Water Drain at Kasturi Estate 1st Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3166,Storm Water Drain,Completed,NJ-TEYNAMPET,118,87000,Desilting of Storm Water Drain at Kasturi Estate 2nd Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3167,Storm Water Drain,Completed,NJ-TEYNAMPET,118,65000,Desilting of Storm Water Drain at Kasturi Estate 3rd Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3168,Storm Water Drain,Completed,NJ-TEYNAMPET,118,245000,Desilting of Storm Water Drain at Kasturi Rangan Salai in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3169,Storm Water Drain,Completed,NJ-TEYNAMPET,118,120000,Desilting of Storm Water Drain at Poes Garden in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3170,Storm Water Drain,Completed,NJ-TEYNAMPET,118,134000,Desilting of Storm Water Drain at Sriman Srinivasa Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3171,Storm Water Drain,Completed,NJ-TEYNAMPET,118,64000,Desilting of Storm Water Drain at Partha Sarathy Garden in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3172,Storm Water Drain,Completed,NJ-TEYNAMPET,118,64000,Desilting of Storm Water Drain at Bashiyam Basheer Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3173,Storm Water Drain,Completed,NJ-TEYNAMPET,118,67000,Desilting of Storm Water Drain at Ambujammal Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3174,Storm Water Drain,Completed,NJ-TEYNAMPET,118,129000,Desilting of Storm Water Drain at Murrays Gate Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3175,Storm Water Drain,Completed,NJ-TEYNAMPET,118,92000,Desilting of Storm Water Drain at Raghavaveera Avenue in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3176,Storm Water Drain,Completed,NJ-TEYNAMPET,118,95000,Desilting of Storm Water Drain at Poes Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3177,Storm Water Drain,Completed,NJ-TEYNAMPET,118,58000,Desilting of Storm Water Drain at Venkatarathinam Salai in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3179,Storm Water Drain,Completed,NJ-TEYNAMPET,118,92000,Desilting of Storm Water Drain at Rajakrishnarao Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3180,Storm Water Drain,Completed,NJ-TEYNAMPET,118,138000,Desilting of Storm Water Drain at Varatharajapuram Main Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2016-17 NJ/2016-17/3181,Storm Water Drain,Completed,NJ-TEYNAMPET,118,98000,Desilting of Storm Water Drain at Ellaiamman Colony Main Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3182,Storm Water Drain,Completed,NJ-TEYNAMPET,118,150000,Desilting of Storm Water Drain at Chokkalingam Colony Main Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3183,Storm Water Drain,Completed,NJ-TEYNAMPET,118,92000,Desilting of Storm Water Drain at Besent Road in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3184,Storm Water Drain,Completed,NJ-TEYNAMPET,118,65000,Desilting of Storm Water Drain at Rathinam Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3185,Storm Water Drain,Completed,NJ-TEYNAMPET,118,245000,Desilting of Storm Water Drain at Avvai Shanmugam Salai in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3186,Storm Water Drain,Completed,NJ-TEYNAMPET,118,58000,Desilting of Storm Water Drain at Sadasivam Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3187,Storm Water Drain,Completed,NJ-TEYNAMPET,118,56000,Desilting of Storm Water Drain at Ramasamy Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3188,Storm Water Drain,Completed,NJ-TEYNAMPET,118,50000,Desilting of Storm Water Drain at Srinivasaperumal Sannathi 2nd Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3189,Storm Water Drain,Completed,NJ-TEYNAMPET,118,50000,Desilting of Storm Water Drain at Pudupet Garden Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/3190,Storm Water Drain,Completed,NJ-TEYNAMPET,118,65000,Desilting of Storm Water Drain at Ganapathy Colony 2nd Street in Division 118 Unit 24 Zone 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/4225,Parks,Completed,NJ-TEYNAMPET,118,300000,"Providing missing plants in Center median at Dr.Radhakrishnan Salai in Dn-118 and Dn 119, Unit-24, Zone-09.",Own Sources,9,2016-17,2018-19 NJ/2016-17/4634,Storm Water Drain,Completed,NJ-TEYNAMPET,118,880000,CONSTRUCTION OF STORM WATER DRAIN AT KASTURI ESTATE 2ND STREET IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/4731,Buildings,Completed,NJ-TEYNAMPET,118,475000,IMPROVEMENTS TO PC AT MARIYAPPAN STREET (UNDER WARD COUNCILOR FUND 2016-17) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/4733,Buildings,Completed,NJ-TEYNAMPET,118,450000,IMPROVEMENTS TO PC AT NALLAN STREET (UNDER WARD COUNCILOR FUND 2016-17) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/4734,Buildings,Completed,NJ-TEYNAMPET,118,470000,IMPROVEMENTS TO PC AT VARATHARAJAPURAM MAIN ROAD (UNDER WARD COUNCILOR FUND 2016-17) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/4735,Buildings,Completed,NJ-TEYNAMPET,118,455000,IMPROVEMENTS TO PC AT MAYOR SUNDER RAO ROAD (UNDER WARD COUNCILOR FUND 2016-17) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/4736,Buildings,Completed,NJ-TEYNAMPET,118,460000,IMPROVEMENTS TO PC AT AMMAIAPPAN LANE (UNDER WARD COUNCILOR FUND 2016-17) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/4738,Buildings,Completed,NJ-TEYNAMPET,118,520000,IMPROVEMENTS TO PC AT THOMAIYAPPAN STREET (UNDER WARD COUNCILOR FUND 2016-17) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/5074,Footpath,Completed,NJ-TEYNAMPET,118,170000,IMPROVEMENTS TO FOOTPATH AT SIVASANKARAN SALAI PART (UNDER COUNCILLOR FUND 2016-17) IN DIVISION 118 UNIT 24 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/6692,Footpath,Completed,NJ-TEYNAMPET,118,655000,"BLACK AND WHITE PAINTING TO THE FOOT PATH KERBS AT R.K SALAI,CATHEDRAL ROAD,T.T.K ROAD AND POES GARDEN IN VIEW OF INDEPENDENCE DAY CELEBRATION-2016, DIVISION 118 AND 119.UNIT 24,ZONE 09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7718,Storm Water Drain,Completed,NJ-TEYNAMPET,118,115000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT AMMAIAPPAN LANE IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7719,Storm Water Drain,Completed,NJ-TEYNAMPET,118,140000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT CHOCKKALINGAM COLONY IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7720,Storm Water Drain,Completed,NJ-TEYNAMPET,118,125000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT ELANGO SALAI IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7721,Storm Water Drain,Completed,NJ-TEYNAMPET,118,80000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT ELANGO SALAI CROSS STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7722,Storm Water Drain,Completed,NJ-TEYNAMPET,118,150000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT ELLAIAMMAN COLONY SCHEME ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7723,Storm Water Drain,Completed,NJ-TEYNAMPET,118,105000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT ELLAIAMMAN COLONY 1 ST CROSS STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7724,Storm Water Drain,Completed,NJ-TEYNAMPET,118,115000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT KASTHURI ESTATE ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7725,Storm Water Drain,Completed,NJ-TEYNAMPET,118,170000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT MUTHAIAH STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7726,Storm Water Drain,Completed,NJ-TEYNAMPET,118,75000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT NORTH GOPALAPURAM 1 ST STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7727,Storm Water Drain,Completed,NJ-TEYNAMPET,118,125000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT PRASANNA VINAYAGAR KOIL 2 ND STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7728,Storm Water Drain,Completed,NJ-TEYNAMPET,118,95000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT PRASANNA VINAYAGAR KOIL 1 ST STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7729,Storm Water Drain,Completed,NJ-TEYNAMPET,118,150000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT NALLAN STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7731,Storm Water Drain,Completed,NJ-TEYNAMPET,118,120000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT POES ROAD 1 ST STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7732,Storm Water Drain,Completed,NJ-TEYNAMPET,118,120000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT POES ROAD 2 ND STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7733,Storm Water Drain,Completed,NJ-TEYNAMPET,118,115000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT POES ROAD 3 RD STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7734,Storm Water Drain,Completed,NJ-TEYNAMPET,118,120000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT PONNUSAMY STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7738,Storm Water Drain,Completed,NJ-TEYNAMPET,118,145000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT VENUS COLONY 1 ST STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/7739,Storm Water Drain,Completed,NJ-TEYNAMPET,118,184000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT VENUS COLONY 2 ND STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/8036,Buildings,Completed,NJ-TEYNAMPET,118,485000,"CONVERTION OF MULTI PURPOSE HALL TO AMMAUNAVAGAM AT MARIYAPPAN STREET IN DIVISION-118,UNIT-24,ZONE-09.",Own Sources,9,2016-17,2018-19 NJ/2016-17/9904,Roads,Completed,NJ-TEYNAMPET,118,413000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT ELANGO SALAI IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9908,Roads,Completed,NJ-TEYNAMPET,118,480000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT MUTHAIAH STREET (PART) IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9910,Roads,Completed,NJ-TEYNAMPET,118,385000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT JJ SALAI IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9912,Roads,Completed,NJ-TEYNAMPET,118,350000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT KASTHURI ESTATE ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9913,Roads,Completed,NJ-TEYNAMPET,118,483000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT MAHARANI CHINNAMMAL SALAI IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9914,Roads,Completed,NJ-TEYNAMPET,118,1109000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT VENUS COLONY 2 ND STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9915,Roads,Completed,NJ-TEYNAMPET,118,600000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT AMMAIAPPAN LANE IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/9916,Roads,Completed,NJ-TEYNAMPET,118,262000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT GALLILAYAPURAM IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 L/2016-17/17549,Electrical,Completed,L-Electrical,119,2982500,"Replacement of damaged lamp post for 391 Nos of 6/7 Mtr Lamp Post and 234 Nos of OH/9.5/11 Lamp Post due to Vartha cyclone at Various Location in Division-109 to 126, Zone-IX.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0859,Roads,Completed,NJ-TEYNAMPET,119,655000,"RESTORATION OF ROAD CUT MADE BY TNEB AT MUTHAYA GARDEN STREET AND SAIVA MUTHAYA FIRST STREET AND 5TH STREET AND BALAJI NAGAR 4TH,RAMARAO GARDEN 2ND STREET IN DN-119 U-24 Z-9",Deposit Works,9,2016-17,2017-18 NJ/2016-17/1270,Buildings,Completed,NJ-TEYNAMPET,119,213000,RESTORATION OF ROADCUT MADE BY CMWSSB AT LEONARD STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1271,Roads,Completed,NJ-TEYNAMPET,119,638000,RESTORATION OF ROADCUT MADE BY CMWSSB AT KALINGA RAYAN STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1272,Road Cut,Completed,NJ-TEYNAMPET,119,370000,RESTORATION OF ROADCUT MADE BY CMWSSB AT IYYAMPERUMAL STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1274,Road Cut,Completed,NJ-TEYNAMPET,119,75000,RESTORATION OF ROADCUT MADE BY CMWSSB AT RAMARAO GARDEN 1 ST STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1275,Road Cut,Completed,NJ-TEYNAMPET,119,150000,RESTORATION OF ROADCUT MADE BY CMWSSB AT SUBBA RAO AVENUE IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1276,Footpath,Completed,NJ-TEYNAMPET,119,173000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT VATHIYAR CHINNAIYA PILLAI STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1277,Footpath,Completed,NJ-TEYNAMPET,119,213000,RESTORATION OF ROADCUT MADE BY CMWSSB AT ANTONY STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1278,Footpath,Completed,NJ-TEYNAMPET,119,213000,RESTORATION OF ROADCUT MADE BY CMWSSB AT NALLANNA MUDALI LANE IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/13970,Buildings,Completed,NJ-TEYNAMPET,119,38000,"REPAIR AND MAINTENANCE WORKS OF PUBLIC CONVENIENCE AT KATTUKOIL IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/13973,Buildings,Completed,NJ-TEYNAMPET,119,81000,"REPAIRS AND MAINTENANCE OF PUBLIC CONVENIENCE AT SAIVA MUTHAIAH 6 TH STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/1413,Roads,Completed,NJ-TEYNAMPET,119,185000,RESTORATION OF ROADCUT MADE BY CMWSSB AT MAYOR SIVARAJ STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1414,Roads,Completed,NJ-TEYNAMPET,119,140000,RESTORATION OF ROADCUT MADE BY CMWSSB AT RAMARAO GARDEN 2ND STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1415,Roads,Completed,NJ-TEYNAMPET,119,127000,RESTORATION OF ROADCUT MADE BY CMWSSB AT RAMARAO GARDEN 3RD STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1416,Roads,Completed,NJ-TEYNAMPET,119,69000,RESTORATION OF ROADCUT MADE BY CMWSSB AT BEGUM 1ST STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1417,Roads,Completed,NJ-TEYNAMPET,119,69000,RESTORATION OF ROADCUT MADE BY CMWSSB AT BEGUM SECOND STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1418,Roads,Completed,NJ-TEYNAMPET,119,140000,RESTORATION ROADCUT MADE BY CMWSSB AT BEGUM 4TH STREET IN DN-119 U-24 Z -9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1420,Roads,Completed,NJ-TEYNAMPET,119,97000,RESTORATION OF ROADCUT MADE BY CMWSSB AT KANDASAMY LANE IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1421,Roads,Completed,NJ-TEYNAMPET,119,218000,RESTORATION OF ROADCUT MADE BY CMWSSB AT PILOT LANE IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1422,Roads,Completed,NJ-TEYNAMPET,119,150000,RESTORATION ROADCUT MADE BY CMWSSB AT SAIVA MUTHAYA MUDALI 1ST STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1423,Roads,Completed,NJ-TEYNAMPET,119,150000,RESTORATION OF ROADCUT MADE BY CMWSSB AT MUTHIAH MUDALI 2ND STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/1424,Footpath,Completed,NJ-TEYNAMPET,119,125000,RESTORATION OF ROADCUT MADE BY CMWSSB AT SAIVA MUTHIAH 3RD STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/14353,Buildings,Completed,NJ-TEYNAMPET,119,370000,"REPAIRS AND MAINTENANCE WORKS OF CHENNAI MIDDLE SCHOOL AT BALAJI NAGAR 3 RD STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14359,Buildings,Completed,NJ-TEYNAMPET,119,250000,"REPAIR AND MAINTENANCE WORKS AT CHENNAI MIDDLE SCHOOL AT BEGUM STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14360,Buildings,Completed,NJ-TEYNAMPET,119,550000,"REPAIR AND MAINTENANCE OF CHENNAI URDU GIRLS SCHOOL AT PETERS ROAD IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16056,Buildings,Completed,NJ-TEYNAMPET,119,300000,REPAIRS AND IMPROVEMENTS TO THE CMS AT BEHUM STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/16057,Buildings,Completed,NJ-TEYNAMPET,119,120000,REPAIRS AND IMPROVEMENTS TO THE URUTHU SCHOOL AT PETERS ROAD IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/16058,Buildings,Completed,NJ-TEYNAMPET,119,230000,REPAIRS AND IMPROVEMENTS TO THE HEALTH POST AT BEHAM STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/16060,Buildings,Completed,NJ-TEYNAMPET,119,168000,REPAIRS AND IMPROVEMENTS TO THE STORM WATER TRAIN AT AVVAI SHANMUGAM SALAI IN DN-119 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/16061,Buildings,Completed,NJ-TEYNAMPET,119,190000,"REPAIRS AND RE-CONSTRUCTION OF FALLAN EXISING DAMAGED COMPOUND WALL IN CHENNAI MIDDLE SCHOOL AT SAIVAMUTHAIAHA 6TH STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17010,Bridges,Completed,NJ-TEYNAMPET,119,620000,"REPAIRS AND IMPROVEMENTS TO THE PARK AT CIT COLONY IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17875,Footpath,Completed,NJ-TEYNAMPET,119,190000,"REPAIRS FOOTPATH AT JEGATHAMBAL COLONY 1 ST AND 2 ND STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17876,Footpath,Completed,NJ-TEYNAMPET,119,410000,"REPAIRS AND IMPROVEMENTS TO THE FOOT PATH AT KALINGARAYAN STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17877,Footpath,Completed,NJ-TEYNAMPET,119,640000,"REPAIRS AND IMPROVEMENTS TO THE FOOTPATH AT JUDGE JAMBULINGAM STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17878,Footpath,Completed,NJ-TEYNAMPET,119,465000,"REPAIRS AND IMPROVEMENTS TO THE FOOT PATH AT AVVAISHANMUGAM SALAI IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/1966,Storm Water Drain,Completed,NJ-TEYNAMPET,119,220000,RESTORATION OF ROADCUT MADE BY CMWSSB AT SAIVA MUTHIAH MUDALI 5TH STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/2397,Buildings,Completed,NJ-TEYNAMPET,119,990000,IMPROVEMENTS TO THE COMMUNITY CENTRE AT BEHUM STREET IN DN-119 U-24 Z 9[COUNCILAR FUND],Own Sources,9,2016-17,2017-18 NJ/2016-17/2398,Buildings,Completed,NJ-TEYNAMPET,119,990000,PROVIDING FLOORING ARRANGEMENTS FOR COMMUNITY CENTRE [KITCHEN] AT BEHUM STREET IN DN-119 U-24 Z-9 [COUNCILAR FUND],Own Sources,9,2016-17,2017-18 NJ/2016-17/2520,Storm Water Drain,Completed,NJ-TEYNAMPET,119,460000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT PETTRS ROAD (SOUTH) IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2522,Storm Water Drain,Completed,NJ-TEYNAMPET,119,37000,"DESILTING OF STORM WATER DRAIN AT CIT COLONY 1st LINK STREET IN DIVISION-119,UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2523,Storm Water Drain,Completed,NJ-TEYNAMPET,119,318000,"DESILTING OF STORM WATER DRAIN AT PETTER'S ROAD IN DIVISION-119,UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2524,Buildings,Completed,NJ-TEYNAMPET,119,360000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT NALLANA STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2528,Buildings,Completed,NJ-TEYNAMPET,119,230000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT BALAJI NAGAR 1 ST STREET (EAST SIDE) IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2530,Buildings,Completed,NJ-TEYNAMPET,119,170000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT BALAJI NAGAR 1 ST STREET (WEST SIDE) IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2531,Storm Water Drain,Completed,NJ-TEYNAMPET,119,197000,"DESILTING OF STORM WATER DRAIN AT MUSURU SUBRAMANIA (OLIVER) ROAD IN DIVISION-119, UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2541,Buildings,Completed,NJ-TEYNAMPET,119,87000,RESTORATION OF ROADCUT MADE BY CMWSSB AT SAIVA MUTHIAH MUDALI 4TH STREET IN DN-119 U-24 Z-9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/2545,Buildings,Completed,NJ-TEYNAMPET,119,82000,DESILITING OF STORM WATER DRAIN AT PILOT LANE IN DIVISION -119 UNIT-24 ZONE-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/2547,Buildings,Completed,NJ-TEYNAMPET,119,90000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT AVVAI SHANMUGAM LANE IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2548,Buildings,Completed,NJ-TEYNAMPET,119,80000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT P.S.SIVASAMY SALAI IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2549,Storm Water Drain,Completed,NJ-TEYNAMPET,119,91000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT KALINGAROYAN STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2551,Storm Water Drain,Completed,NJ-TEYNAMPET,119,58000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT BISHOP WALLERS AVENUE (WEST) IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2553,Buildings,Completed,NJ-TEYNAMPET,119,58000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT BISHOP WALLERS AVENUE (EAST) IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2554,Buildings,Completed,NJ-TEYNAMPET,119,380000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT CIT COLONY 1 ST MAIN ROAD IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2555,Buildings,Completed,NJ-TEYNAMPET,119,130000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT SANDAVELI 2 ND STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2556,Buildings,Completed,NJ-TEYNAMPET,119,140000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT SANDAVELI 3 RD TREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2559,Buildings,Completed,NJ-TEYNAMPET,119,185000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT SAIVA MUTHAIAH 6 TH STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2561,Buildings,Completed,NJ-TEYNAMPET,119,295000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT SAIVA MUTHAIAH 5 TH STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2562,Buildings,Completed,NJ-TEYNAMPET,119,205000,DESILITING AND REPAIRS TO THE STORM WATER DRAIN AT SAIVA MUTHAIAH 2 ND STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/2564,Buildings,Completed,NJ-TEYNAMPET,119,180000,"DESILTING OF STORM WATER DRAIN ATPURAM PRAKASAM ROAD IN DIVISION - 119, UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2566,Buildings,Completed,NJ-TEYNAMPET,119,183000,"DESILTING OF STORM WATER DRAIN AT MUTHAIAH GARDEN STREET IN DIVISION - 119, UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2569,Buildings,Completed,NJ-TEYNAMPET,119,83000,"DESILTING OF STORM WATER DRAIN AT R.H.ROAD (SERVICE ROAD) IN DIVISION - 119, UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2571,Buildings,Completed,NJ-TEYNAMPET,119,229000,"DESILTING OF STORM WATER DRAIN AT MASILAMANI STREET IN DIVISION-119, UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2573,Storm Water Drain,Completed,NJ-TEYNAMPET,119,230000,"DESILTING OF STORM WATER DRAIN AT BALAJI NAGAR 2,3 & 4th STREET IN DIVISION-119, UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2574,Storm Water Drain,Completed,NJ-TEYNAMPET,119,205000,"DESILTING OF STORM WATER DRAIN AT RAMARAO GARDEN 1,2 &3 rd STREET IN DIVISION-119, UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2581,Storm Water Drain,Completed,NJ-TEYNAMPET,119,360000,"DESILTING OF STORM WATER DRAIN AT AVVAI SHANMUGAM SALAI IN DIVISION-119,UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2583,Storm Water Drain,Completed,NJ-TEYNAMPET,119,430000,"DESILTING OF STORM WATER DRAIN AT ROYAPETTAH HIGH ROAD IN DIVISION-119,UNIT-24,ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/5160,Roads,Completed,NJ-TEYNAMPET,119,510000,"Providing Speed Breakers as per IRC design [Clause 5, 6 of IRC: 99-1988] Bituminous Concrete (as per clause 509 of MORTH specification) to the required grade and alignment and rolled with vibratory roller etc., complete and as directed by Engineers as per the plan enclosed.at saiva Muthaiah 2,5 & 6th street,Muthaiah Garden street,Avvaishanmugam salai,Gowdia mutt Road and Sree puram 1st street in division-119,unit-24,zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/5320,Buildings,Completed,NJ-TEYNAMPET,119,467000,"DEMOLITION OF EXISTING HOSTEL AND KITCHEN SHED BUILDING( GROUND FLOOR AND FIRST FLOOR) IN CHENNAI URDU GIRLS MIDDLE SCHOOL CAMPUS AT PETERS ROAD IN DN-119, UNIT-24, ZONE-09",Own Sources,9,2016-17,2016-17 NJ/2016-17/6836,Roads,Completed,NJ-TEYNAMPET,119,85000,RESTORATION OF ROADCUT MADE BY TNEB AT CIT COLONY FIRST CROSS STREET IN DN-119 U-24 9,Deposit Works,9,2016-17,2017-18 NJ/2016-17/7730,Storm Water Drain,Completed,NJ-TEYNAMPET,119,120000,"DESILTING AND REPAIRS OF STORM WATER DRAIN AT POES ROAD NALLAN STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/8548,Footpath,Completed,NJ-TEYNAMPET,119,2430000,PROPOSED CONSTRUCTION OF NEW WASHING SHED IN DHOBIKANA CAMPUS AT MUTHAYA STREET IN DN-119 U-24 Z-9[MLA FUND],MLACDS,9,2016-17,2017-18 NJ/2016-17/8575,Buildings,Completed,NJ-TEYNAMPET,119,940000,REPAIRS AND IMPROVEMENTS TO THE IRONING HALL IN DHOBIKANA CAMPUS AT MUTHAYA GARDEN STREET IN DN-119 U-24 Z-9,Own Sources,9,2016-17,2017-18 NJ/2016-17/8577,Roads,Completed,NJ-TEYNAMPET,119,990000,PROVIDING AND FIXING STAINLESS STEEL STREET NAME BOARDS AT VARIOUS STREETS IN DN-119 U-24 Z-9 [COUNCILAR FUND],Own Sources,9,2016-17,2017-18 NJ/2016-17/9917,Roads,Completed,NJ-TEYNAMPET,119,950000,"RELAYING OF ROAD WITH BCCMP 30 MM THICK AT JUDGE JAMBULINGAM ROAD IN DIVISION-119,UNIT-24,ZON-09",Own Sources,9,2016-17,2016-17 L/2016-17/18956,Electrical,Completed,L-Electrical,120,194200,Removal & Refixing & Replacement of accessories and maintenance work for the 30 mtr High mast of Vivekanandha Illam ( opp ) Marina beach service Road (Sand area) in div-120 under Zone-IX.,Own Sources,9,2016-17,2018-19 L/2016-17/2373,Electrical,Completed,L-Electrical,120,198500,"WORK: Estimate for Replacement of accessories and maintaince work for the High Mast of Avvaiyar Statue back side,Marina Beach Service Road, in Div-121 under Zone-IX.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0033,Electrical,Completed,NJ-TEYNAMPET,120,24950,"Supply and fixing of overhead tank, taps, tube light with patty, ceiling fan in AMMA UNAVAGAM building at gajapathy street in DIV-120, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0034,Buildings,Completed,NJ-TEYNAMPET,120,23000,"Supplying and fixing of overhead tank, taps, tube light with patty and motor repair in 2nd Public convenience building at gajapathy street in DIV-120, UNIT-27, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0318,Buildings,Completed,NJ-TEYNAMPET,120,24000,"Supplying and fixing of plumbing and electrical materials in NUHM at MUTHAIYAH street road in div-120,U-27,Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0320,Buildings,Completed,NJ-TEYNAMPET,120,22000,"Supplying and fixing 1 HP Jet motor and M.S.Sheet Door at public convenience at Ramnagar in dn-120, U-27, Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0321,Buildings,Completed,NJ-TEYNAMPET,120,22000,"Supplying and fixing 1 HP Jet motor and M.S.Sheet Door at public convenience ( near temple)at in hanumanthapuram street dn-120, U-27, Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0322,Buildings,Completed,NJ-TEYNAMPET,120,22000,"Supplying and fixing 1 HP Jet motor and M.S.Sheet Door at public convenience (near community college) at in hanumanthapuram street dn-120, U-27, Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0323,Buildings,Completed,NJ-TEYNAMPET,120,22000,"supplying and fixing 1 HP Jet motor and M.S.Sheet Door at public convenience at in nadukuppam street dn-120, U-27, Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/0324,Buildings,Completed,NJ-TEYNAMPET,120,22000,"supplying and fixing 1 HP Jet motor and M.S.Sheet Door in public convenience in sunnambu kalvai street dn-120, U-27, Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/1040,Parks,Completed,NJ-TEYNAMPET,120,999000,"Repairs to damaged granite slab & Tiles in footpath and gallery area at marina beach(Gallery 9 to Gallery14 ) in Dn-120,121&125 in U-27A,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/13366,Electrical,Completed,NJ-TEYNAMPET,120,285000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT KRISHNAPET BURIAL GROUND IN DN 120, UNIT-27, ZONE -9. (COLLECTION OF GARBAGE FROM DIVISION 114, 115, 116, 120 and 121)",Own Sources,9,2016-17,2018-19 NJ/2016-17/14047,Buildings,Completed,NJ-TEYNAMPET,120,112000,"Improvements to the Public convenience at kandappan street,Gajapathy street (near amma unavagam) , Gajapathy street (near zym),Ramnagar main road (near ram nagar middle school) in div-120,unit-27,zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14078,Roads,Completed,NJ-TEYNAMPET,120,112000,"Improvements to the Public convenience at Sunnambu kalvai(back to burial ground) , Hanumanthapuram (south), Hanumanthapuram (north) ,Nadukuppam street in div-120,unit-27,zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14297,Buildings,Completed,NJ-TEYNAMPET,120,380000,"IMPROVEMENTS TO THE SCHOOL AT RAM NAGAR MIDDLE SCHOOL,IRUSAPPAN GIRLS HIGH SCHOOL IN DIV-120,UINIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15906,Bridges,Completed,NJ-TEYNAMPET,120,245000,"REPAIRS TO THE CHILDREN PLAY FIELD AT LLOYDS COLNY (VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15929,Bridges,Completed,NJ-TEYNAMPET,120,21000,"REPAIRS TO THE AMMA UNAVAGAM AT MUTHIAH ST(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15930,Bridges,Completed,NJ-TEYNAMPET,120,30000,"REPAIRS TO THE CMS AT BESANT SCHOOL ROAD(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15931,Parks,Completed,NJ-TEYNAMPET,120,152000,"REPAIRS TO THE ROAD SIDE PARK AT LLOYDS COLONY(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15932,Bridges,Completed,NJ-TEYNAMPET,120,112000,"REPAIRS TO THE ICDS AT LLOYDS COLONY(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15933,Bridges,Completed,NJ-TEYNAMPET,120,330000,"REPAIRS TO THE SWD AT LLOYDS COLONY (VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15934,Bridges,Completed,NJ-TEYNAMPET,120,721000,"REPAIRS TO THE DOG SHELTER AT LLOYDS COLONY(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15935,Bridges,Completed,NJ-TEYNAMPET,120,227000,"REPAIRS TO THE ITI AT LLOYDS COLONY(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15936,Bridges,Completed,NJ-TEYNAMPET,120,156000,"REPAIRS TO THE GIRLS HIGH SCHOOL AT IRUSAPPAN STREET(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15937,Bridges,Completed,NJ-TEYNAMPET,120,103000,"REPAIRS TO THE PLAY GROUND AT NADUKUPPAM 5TH STREET (VARTHA CYCLONE)IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/15951,Bridges,Completed,NJ-TEYNAMPET,120,202000,"REPAIRS TO THE ICDS AT NADUKUPPAM 5TH STREET ((VARTHA CYCLONE)IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16265,Bridges,Completed,NJ-TEYNAMPET,120,527000,"CONSTRUCTION OF COMPOUND WALL KRISHNAMPETTAIH BURIAL GROUND GAJAPATHY ST(VARTHA CYCLONE) IN DIV-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/1640,Storm Water Drain,Completed,NJ-TEYNAMPET,120,155000,DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT MUTHAIYA STREET IN DN-120 U-27 Z-9,Own Sources,9,2016-17,2016-17 NJ/2016-17/2122,Parks,Completed,NJ-TEYNAMPET,120,995000,CONSTRUCTION OF ROAD SIDE PARK ARROUND THE VINAYAGAR TEMPLE AT LLOUDS COLONY IN DN-120 U-27 Z-9 [COUNCILAR FUND],Own Sources,9,2016-17,2016-17 NJ/2016-17/2187,Parks,Completed,NJ-TEYNAMPET,120,495000,WATER SUPPLY AND GREENNARY ARRANGEMENTS FOR ROAD SIDE PARK ARROUND THE VINAYAGAR TEMPLE AT LLOYDS COLONY IN DN-120 U-27 Z-9 [COUNCILAR FUND],Own Sources,9,2016-17,2016-17 NJ/2016-17/2378,Storm Water Drain,Completed,NJ-TEYNAMPET,120,999000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT DR.NATESAN ROAD (PART) FROM JN OF DR. BESANT ROAD TO JN OF VAIKOL THOTTI STREET IN DN-120,UNIT-27,ZONE-9 [ FOR WARD COUNCILLOR FUND]",Own Sources,9,2016-17,2016-17 NJ/2016-17/2389,Storm Water Drain,Completed,NJ-TEYNAMPET,120,497000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN AT DR.NATESAN ROAD (PART) FROM JN OF VAIKOL THOTTI STREET TO JN OF ELEPHANT TANK 6TH STREET IN DN-120,UNIT-27,ZONE-9 [ FOR WARD COUNCILLOR FUND]",Own Sources,9,2016-17,2016-17 NJ/2016-17/2673,Storm Water Drain,Completed,NJ-TEYNAMPET,120,50000,"Desilting and repairs to the strom water drain at Irusappan 2nd LANE IN DN-120, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2674,Storm Water Drain,Completed,NJ-TEYNAMPET,120,200000,"Desilting and repairs to the strom water drain at LLOYDS COLONY IN DN-120, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2676,Storm Water Drain,Completed,NJ-TEYNAMPET,120,230000,"Desilting and repairs to the strom water drain at DR NATASAN ROAD IN DN-120, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2677,Storm Water Drain,Completed,NJ-TEYNAMPET,120,75000,"Desilting and repairs to the strom water drain at Irusappan Street IN DN-120, U-27, Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3276,Buildings,Completed,NJ-TEYNAMPET,120,195000,"IMPROVEMENTS TO THE AMMA UNAVAGAM AT GAJAPATHY STREET IN DIVISION-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/3277,Buildings,Completed,NJ-TEYNAMPET,120,196000,"IMPROVEMENTS TO THE AMMA UNAVAGAM AT MUTHIAHYA STREET IN DIVISION-120,UNIT-27,ZONE-09",Own Sources,9,2016-17,2017-18 BR/2016-17/18012,Roads,Completed,BR-Bus Route Roads,121,840000,"Providing and laying of hot thermoplastic paint at Kamarajar Salai in Dn -121, Zone -9",Own Sources,9,2016-17,2017-18 BR/2016-17/5966,Roads,Completed,BR-Bus Route Roads,121,790000,Providing Back drop accessories and repair works to the Bus shelters in various Bus route roads in Zone:9,Own Sources,9,2016-17,2018-19 BR/2016-17/6668,Roads,Completed,BR-Bus Route Roads,121,934600,Providing and Fixing of SS Pipe Grill for Center Median at Dr. Radha Krishnan Salai from P.S. Sivaswami Salai junction to TTK Flyover starting point in Division 119 Zone - 9.,Own Sources,9,2016-17,2017-18 BR/2016-17/6670,Roads,Completed,BR-Bus Route Roads,121,2117100,"Providing and Fixing of SS Pipe Grill for Center Median at Dr. Radha Krishnan Salai from Chennai Citi Center Junction to Dr. Radha Krishnan Salai 4th street in Division 121, Zone - 9. from Chainage 0 to 265.",Own Sources,9,2016-17,2016-17 BR/2016-17/6675,Roads,Completed,BR-Bus Route Roads,121,2117100,"Providing and Fixing of SS Pipe Grill for Center Median at Dr. Radha Krishnan Salai from Chennai Citi Center Junction to Dr. Radha Krishnan Salai 4th street in Division 121, Zone - 9. from Chainage 265 to 533.",Own Sources,9,2016-17,2016-17 BR/2016-17/6679,Roads,Completed,BR-Bus Route Roads,121,2117300,"Providing and Fixing of SS Pipe Grill for Center Median at Dr. Radha Krishnan Salai from Dr. Radha Krishnan Salai 4th street to P.S. Sivaswami Salai Junction in Division 121, zone - 9. Chainage 268 to 533.",Own Sources,9,2016-17,2016-17 NJ/2016-17/12388,Buildings,Completed,NJ-TEYNAMPET,121,998000,"Supply, Installation,Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at Avvai Shanmugam Salai (Near Amma Unavagam) in Dn 121,Unit-27, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/1280,Footpath,Completed,NJ-TEYNAMPET,121,852000,PROVIDING ARRANGEMENTS FOR WASHING AREA AND BATH ROOMS AT GANESHAPURAM IN DN-121 U-27 Z-9 [COUNCILLOR FUND],Own Sources,9,2016-17,2017-18 NJ/2016-17/1281,Footpath,Completed,NJ-TEYNAMPET,121,985000,PROVIDING ARRANGEMENTS FOR CHILDRENS PLAY FIELD AND LADIES GYM AT PM DHARGA 2 ND STREET IN DN-121 U-27 Z-9 [COUNCILAR FUND],Own Sources,9,2016-17,2017-18 NJ/2016-17/14057,Buildings,Completed,NJ-TEYNAMPET,121,374000,"IMPROVEMENT TO PC AT GANESAPURAM ( NORTH), GANESAPURAM (SOUTH), P.S.SIVASWAMY SALAI, THIRUVEETHIAMMAN KOIL STREET, ROTARY NAGAR (SOUTH ), ROTARY NAGAR (NORTH), AVVAI SHANMUGAM SALAI AND APPARSWAMY KOIL STREET(WEST) in Dn-121,U-27,Z-9.",Own Sources,9,2016-17,2018-19 NJ/2016-17/14269,Buildings,Completed,NJ-TEYNAMPET,121,319000,"IMPROVEMENT TO CHENNAI HIGH SCHOOL , CHENNAI PRIMARY SCHOOL AT V.P.KOIL STREET, CHENNAI PRIMARY SCHOOL AND CHENNAI HIGHER SECONDARY SCHOOL AT AVVAI SHANMUGAM SALAI IN DN - 121, UNIT - 27, ZONE - 9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/15877,Buildings,Completed,NJ-TEYNAMPET,121,322000,"DEMOLISHING AND CONSTRUCTION OF STORM WATER DRAIN IN DOOR NO 79/123 AT P.S SIVASAMY SALAI IN DN -121,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15891,Storm Water Drain,Completed,NJ-TEYNAMPET,121,31400,"REPAIRS OF STORM WATER DRAIN INFRONT OF CITYCENTER AT Dr.R.K.SALAI IN DIV-121,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15896,Buildings,Completed,NJ-TEYNAMPET,121,165000,"CONSTRUCTION OF COMPOUND WALL AT CHENNAI PRIMARY SCHOOL IN VEERAPERUMAL KOIL STREET IN DN 121, U 27, ZONE - 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/15899,Buildings,Completed,NJ-TEYNAMPET,121,126000,"CONSTRUCTION OF SIDEWALL AT PC IN GANASEPURAM(NORTH) IN DIV-121,U-27,Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17883,Buildings,Completed,NJ-TEYNAMPET,121,386000,"REPAIRS OF FOOTHPATH AT Dr.R.K.SALAI IN DIV-121,U-27,Z-9.",Own Sources,9,2016-17,2020-21 NJ/2016-17/17884,Buildings,Completed,NJ-TEYNAMPET,121,305000,"REPAIRS OF FOOTPATH AT V.M.STREET, P.S.SIVASWAMI SALAI AND BRINDAVANAM STREET IN DIV-121,U-27,Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/18760,Buildings,Completed,NJ-TEYNAMPET,121,698000,"DEMOLITION OF CHENNAI BOYS HIGHER SECONDARY SCHOOL (A BLOCK) GROUND FLOOR,FIRST FLOOR AND SECOND FLOOR AT AVVAI SHANMUGAM SALAI IN DN-121,U-27,Z-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/19616,Buildings,Completed,NJ-TEYNAMPET,121,990000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT AVVAI SHANMUGAM SALAI (LLYODS ROAD)IN DIV-121,U-27,Z-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/2218,Buildings,Completed,NJ-TEYNAMPET,121,892000,"IMPROVEMENTS TO MAIN BUILDING AND CONSTRUCTION OF RCC SUMP FOR CHENNAI HIGHER SECONDARY SCHOOL AT AVVAI SHANMUGAM SALAI, IN DN-121 U-27 Z-9 [COUNCILLOR FUND]",Own Sources,9,2016-17,2016-17 NJ/2016-17/2384,Parks,Completed,NJ-TEYNAMPET,121,463000,"PROVIDING MISSING PLANTS FOR CENTER MEDIAN AT DR.RADHAN KRISHNAN SALAI IN DN - 121, UNIT-27, ZONE -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2386,Roads,Completed,NJ-TEYNAMPET,121,887000,"IMPROVEMENTS TO DHOBIKANA AT VEERA PERUMAL KOIL STREET IN DN-121, UNIT-27, ZONE-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2391,Roads,Completed,NJ-TEYNAMPET,121,391000,"RELAYING THE EXISTING B.T. ROAD WITH BCCMP1 BY PAVER AT RANGAYA GARDEN IN DIVISION 121, UNIT - 27, ZONE -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2401,Buildings,Completed,NJ-TEYNAMPET,121,195000,IMPROVEMENTS TO THE AMMA UNAVAGAM AT LLOYDS ROAD IN DN-121 U-27 Z-9,Own Sources,9,2016-17,2016-17 NJ/2016-17/2941,Buildings,Completed,NJ-TEYNAMPET,121,100000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT THULLUKANAM THOTTAM IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2942,Buildings,Completed,NJ-TEYNAMPET,121,59000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT DWARAGA NAGAR COLONY IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2943,Buildings,Completed,NJ-TEYNAMPET,121,45000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT P.M. DURGA MAIN ROAD IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2944,Buildings,Completed,NJ-TEYNAMPET,121,31000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT SURESH MAKKAN 1st AND 2nd LANE IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2945,Buildings,Completed,NJ-TEYNAMPET,121,64000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT RAGHAVAN THOTTAM IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2946,Buildings,Completed,NJ-TEYNAMPET,121,106000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT MAYANDI COLONY IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2947,Buildings,Completed,NJ-TEYNAMPET,121,36000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT B.B.3rd STREET IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2948,Buildings,Completed,NJ-TEYNAMPET,121,26000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT CHANDRABAGU AVENUE 2nd STREET IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2949,Buildings,Completed,NJ-TEYNAMPET,121,39000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT V.M.STREET IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2950,Buildings,Completed,NJ-TEYNAMPET,121,75000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT MUNDAKANNIAMMAN KOIL STREET IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2951,Buildings,Completed,NJ-TEYNAMPET,121,23000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT BALAKRISHNA CROSS STREET IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2952,Buildings,Completed,NJ-TEYNAMPET,121,168000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT BALAKRISHNA STREET IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2954,Buildings,Completed,NJ-TEYNAMPET,121,37000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT DR,R.K.SALAI 5th STREET IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2955,Buildings,Completed,NJ-TEYNAMPET,121,510000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT DR,R.K.SALAI IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2958,Buildings,Completed,NJ-TEYNAMPET,121,136000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT P.S.SIVASWAMI SALAI IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/2959,Buildings,Completed,NJ-TEYNAMPET,121,174000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT THIRU-VI-KA HIGH ROAD IN DN-121,U-27,Z-9",Own Sources,9,2016-17,2016-17 NJ/2016-17/5642,Roads,Completed,NJ-TEYNAMPET,121,342000,"PROVIDING SPEED BREAKERS AT P.S.SIVASWAMI SALAI, APPARSWAMI KOIL STREET WEST, THIRU-VI-KA HIGH ROAD AND AVVAI SHANMUGAM SALAI IN DIV-121, U-27, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/6175,Buildings,Completed,NJ-TEYNAMPET,121,389000,"PROVIDING FOR BIN PLATFORM WORK AT VARIOUS LOCATION ( TOTAL - 54 NOS) IN DIVISION - 121, UNIT - 27, ZONE -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/6348,Buildings,Completed,NJ-TEYNAMPET,121,706000,"PROVIDING BLACK AND WHITE PAINTING FOR FOOTPATH KERB AT DR.RADHAKRISHNAN SALAI AND KAMARAJAR SALAI IN VIEW OF INDEPENDANCE DAY 2016 IN DIVISION - 114, 116, 120 AND 121,UNIT - 27, ZONE - 9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/6647,Storm Water Drain,Completed,NJ-TEYNAMPET,121,504000,"DEMOLISHING AND CONSTRUCTION OF STORM WATER DRAIN IN DOOR NO 69A AT P.S SIVASAMY SALAI IN DN-121,UNIT-27,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/6738,Buildings,Completed,NJ-TEYNAMPET,121,221000,"PROVIDING OF FOOTPATH ( TOTAL - 60 M) AT APPARSWAMY KOIL STREET WEST IN DN 121, UNIT - 27, ZONE - 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/8423,Buildings,Completed,NJ-TEYNAMPET,121,844000,"Construction of toilet Building for Chennai Primary School (CPS) at Avvai Shanmugam Salai in Div-121,Unit-27,Zone-9.(MLA FUND)",MLACDS,9,2016-17,2017-18 NJ/2016-17/8563,Buildings,Completed,NJ-TEYNAMPET,121,154000,PROVIDING PIPELINE ARRANGEMENTS FOR WATER STAGNATION POINTS AT PS SIVASAMY SALAI IN DN-121 U-27 Z-9.,Own Sources,9,2016-17,2017-18 NJ/2016-17/8564,Roads,Completed,NJ-TEYNAMPET,121,226000,"PROVIDING PIPE LINE ARRANGEMENTS FOR WATER STAGNATION POINTS AT THIRU VI KA 2 STREET,3 STREETS AND THIRU VEETHI AMMAN KOIL STREET IN DN-121 U-27 Z-9 .",Own Sources,9,2016-17,2017-18 NJ/2016-17/8565,Roads,Completed,NJ-TEYNAMPET,121,405000,PROVIDING PIPE LINE ARRANGEMENTS FOR WATER STAGNATION POINTS AT DR RATHAKRISHNAN SALAI IN DN-121 U-27 Z-9.,Own Sources,9,2016-17,2017-18 NJ/2016-17/8566,Buildings,Completed,NJ-TEYNAMPET,121,985000,"Providing Shed for Amma Kudineer Water Plant at Avvai Shanmugam Salai (Amma Canteen) in Dn - 121, Unit - 27, Zone -9.",Own Sources,9,2016-17,2016-17 BR/2016-17/17353,Footpath,Completed,BR-Bus Route Roads,122,2133000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at K.B.Dasan Road, Turn Bulls Road and Pasumpon Muthuramalinga Devar salai in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/17780,Roads,Completed,BR-Bus Route Roads,122,710000,Removing and refixing of 6 Numbers of Modern Statinless Steel Bus Shelter at various Bus Route Roads in Zone-9,Own Sources,9,2016-17,2018-19 BR/2016-17/18284,Roads,Completed,BR-Bus Route Roads,122,3458000,"Reparing and Restoration of road damaged by the flood during North East Monsoon 2015 approach road to Pasumpon Muthuramalinga Devar Road in Dn-122, Zone-IX",Own Sources,9,2016-17,2017-18 L/2016-17/18941,Electrical,Completed,L-Electrical,122,197200,Replacement of damaged Fuse Box due to Vartha Cyclone with 50 Nos of 2/core fuse box and 108 Nos of 4/core fuse box at Various Location in Division -117and122 Zone -IX,Own Sources,9,2016-17,2017-18 NJ/2016-17/14226,Buildings,Completed,NJ-TEYNAMPET,122,37000,"Repair works to Public convenience at Alayamman Koil Street in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14227,Buildings,Completed,NJ-TEYNAMPET,122,40000,"Repair works to Public convenience at KB Dasan Road in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14228,Buildings,Completed,NJ-TEYNAMPET,122,45000,"Repair works to Public convenience at Pughs Road Toilet -1 in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14229,Buildings,Completed,NJ-TEYNAMPET,122,36000,"Repair works to Public convenience at Pughs Road Toilet -2 in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14230,Buildings,Completed,NJ-TEYNAMPET,122,47000,"Repair works to Public convenience at Chamiers Lane in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14231,Buildings,Completed,NJ-TEYNAMPET,122,32000,"Repair works to Public convenience at Cenetoph Road in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/14232,Buildings,Completed,NJ-TEYNAMPET,122,53000,"Repair works to Public convenience at Ganesapuram 2nd Street in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16361,Buildings,Completed,NJ-TEYNAMPET,122,959000,"REPAIR WORK TO ROAD SIDE PARK AT CHAMIERS ROAD IN DN 122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16362,Parks,Completed,NJ-TEYNAMPET,122,392000,"REPAIR WORK TO PARK AT TURNBULLS ROAD IN DN 122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16363,Buildings,Completed,NJ-TEYNAMPET,122,116000,"REPAIRS TO AMMA UNAVAGAM AT KB DASAN ROAD IN DN 122,UNIT 26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16436,Footpath,Completed,NJ-TEYNAMPET,122,27000,"REPAIR WORKS TO FOOTPATH AT CENATOPH ROAD IN DN 122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16442,Footpath,Completed,NJ-TEYNAMPET,122,120000,"REPAIR WORKS TO FOOTPATH AT CHITTARANJAN ROAD IN DN 122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17928,Buildings,Completed,NJ-TEYNAMPET,122,1694000,PROPOSED CONSTRUCTION OF COMPOUND WALL AT TURN BULLS ROAD VACANT LAND NEAR KOTTORPURAM CANAL IN DIVISION 122 UNIT 26 ZONE 09,Own Sources,9,2016-17,2017-18 NJ/2016-17/17931,Playfields,Completed,NJ-TEYNAMPET,122,508000,"REPAIR WORK TO TURNBULLS PLAY GROUND IN DN 122,U-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17975,Playfields,Completed,NJ-TEYNAMPET,122,566000,"Repair works to Nandanam play ground in Div 122, U-26,Z-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17983,Roads,Completed,NJ-TEYNAMPET,122,578000,"ATTENDING PATCH WORK AT LOTUS COLONY AND OTHER VARIOUS STREETS IN DN 122,UNIT-26,ZONE9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2826,Storm Water Drain,Completed,NJ-TEYNAMPET,122,340000,"Repairs and Desilting of Storm water at Kaviager Bharathi Dasan Salai in Dn 122, Unit- 26,Zone-9",Own Sources,9,2016-17,2019-20 NJ/2016-17/2850,Storm Water Drain,Completed,NJ-TEYNAMPET,122,148900,"Repairs and Desilting of Storm water at Chithranjan Road in Dn 122, Unit-26,Zone-9",Own Sources,9,2016-17,2019-20 NJ/2016-17/2858,Storm Water Drain,Completed,NJ-TEYNAMPET,122,29900,"Repairs and Desilting of Storm water at T.T.K 1st cross Street in Dn 122, Unit-26,Zone-9",Own Sources,9,2016-17,2019-20 NJ/2016-17/2938,Storm Water Drain,Completed,NJ-TEYNAMPET,122,181900,"DESILTING OF STORM WATER DRAIN AT ARCH BISHOP MATHEWS AVENUE IN DIV 122,UNIT- 26,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2957,Storm Water Drain,Completed,NJ-TEYNAMPET,122,234000,"DESILTING OF STORM WATER DRAIN AT ADYAR CLUB GATE ROAD IN DIV 122,UNIT- 26,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2961,Storm Water Drain,Completed,NJ-TEYNAMPET,122,114900,"DESILTING OF STORM WATER DRAIN AT BOAD CLUB 1 AVENUE IN DIV 122,UNIT- 26,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2971,Storm Water Drain,Completed,NJ-TEYNAMPET,122,106400,"DESILTING OF STORM WATER DRAIN AT BOAD CLUB 3 RD AVENUE IN DIV 122,UNIT- 26,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2974,Storm Water Drain,Completed,NJ-TEYNAMPET,122,276600,"DESILTING OF STORM WATER DRAIN AT BOAD CLUB ROAD IN DIV 122,UNIT- 26,ZONE-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2980,Storm Water Drain,Completed,NJ-TEYNAMPET,122,53800,"DESILTING OF STORM WATER DRAIN AT TURNBULLS ROAD IN DIV 122,UNIT- 26,ZONE-9",Own Sources,9,2016-17,2019-20 NJ/2016-17/3007,Storm Water Drain,Completed,NJ-TEYNAMPET,122,342600,"DESILTING OF STORM WATER DRAIN AT NANDANAM EXTN 3RD STREET IN DN122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3011,Storm Water Drain,Completed,NJ-TEYNAMPET,122,76700,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT NANDANAM EXT.4TH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3022,Storm Water Drain,Completed,NJ-TEYNAMPET,122,46100,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT NANDANAM EXT.7TH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3025,Storm Water Drain,Completed,NJ-TEYNAMPET,122,55000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT NANDANAM EXT.9TH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3027,Storm Water Drain,Completed,NJ-TEYNAMPET,122,149000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT NANDANAM EXT.10TH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3028,Storm Water Drain,Completed,NJ-TEYNAMPET,122,63800,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT NANDANAM EXT.11 TH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3030,Storm Water Drain,Completed,NJ-TEYNAMPET,122,63800,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT NANDANAM EXT.12 TH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3031,Storm Water Drain,Completed,NJ-TEYNAMPET,122,12700,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT CHAIMERS 1ST LANE IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3037,Storm Water Drain,Completed,NJ-TEYNAMPET,122,149000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT CRECENT STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3038,Storm Water Drain,Completed,NJ-TEYNAMPET,122,212000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT RATNA NAGAR IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3039,Storm Water Drain,Completed,NJ-TEYNAMPET,122,206700,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT PUGHS ROAD(SUNDARAM SALAI) IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3041,Storm Water Drain,Completed,NJ-TEYNAMPET,122,63800,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT SATHIYAMOORTHY NAGAR ROAD IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3042,Storm Water Drain,Completed,NJ-TEYNAMPET,122,161900,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT CENOTAPH 2ND LANE IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3043,Storm Water Drain,Completed,NJ-TEYNAMPET,122,75600,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT PLAY GROUND VIEW STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3046,Storm Water Drain,Completed,NJ-TEYNAMPET,122,51500,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT TURNBULLS ROAD EXTN IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3047,Storm Water Drain,Completed,NJ-TEYNAMPET,122,127000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT SRIRAM NAGAR NORTH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3048,Storm Water Drain,Completed,NJ-TEYNAMPET,122,85100,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT SRIRAM NAGAR SOUTH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2019-20 NJ/2016-17/3049,Storm Water Drain,Completed,NJ-TEYNAMPET,122,51500,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT SRIRAM NAGAR WEST STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3052,Storm Water Drain,Completed,NJ-TEYNAMPET,122,58900,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT KAMAKSHI NAGAR IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3053,Storm Water Drain,Completed,NJ-TEYNAMPET,122,136000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT GANAPATHI COLONY IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3055,Storm Water Drain,Completed,NJ-TEYNAMPET,122,17500,"Repairs and Desilting of Storm water Drain at Arcot Street in Dn-117, Unit-26, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/3058,Storm Water Drain,Completed,NJ-TEYNAMPET,122,34000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT COOPERATIVE COLONY IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3059,Storm Water Drain,Completed,NJ-TEYNAMPET,122,153600,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT SATHYANARAYANA AVENUE IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3064,Storm Water Drain,Completed,NJ-TEYNAMPET,122,51000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT GANESAPURAM 2ND STREET( EAST) IN DN 122, UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3082,Storm Water Drain,Completed,NJ-TEYNAMPET,122,45600,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT GANESAPURAM 4TH STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3086,Storm Water Drain,Completed,NJ-TEYNAMPET,122,44700,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT CHAMIERS 3RD LANE IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3088,Storm Water Drain,Completed,NJ-TEYNAMPET,122,44700,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT CHAMIERS 4TH LANE IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2016-17 NJ/2016-17/3109,Buildings,Completed,NJ-TEYNAMPET,122,335000,"IMPROVEMENTS TO AMMA UNAVAGAM AT NANDANAM 10TH EXTN IN DN 122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3111,Buildings,Completed,NJ-TEYNAMPET,122,148000,"IMPROVEMENTS TO AMMA UNAVAGAM AT K.B.DASAN ROAD IN DN 122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3120,Storm Water Drain,Completed,NJ-TEYNAMPET,122,255000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT NANDANAM MAIN ROAD IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3127,Storm Water Drain,Completed,NJ-TEYNAMPET,122,144000,"REPAIRS AND DESILTING OF STROM WATER DRAIN AT KB DASAN SALAI IN DN 122,UNIT UNIT 26,ZONE 9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3326,Buildings,Completed,NJ-TEYNAMPET,122,468000,"PROVIDING PLATFORM AROUND E-TOILET AND WATER SUPPLY ARRANGEMENTS AT TANK BUND ROAD IN DN 122,UNIT-26,ZONE-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/4761,Footpath,Completed,NJ-TEYNAMPET,122,26700,"PAINTING FOOT PATH KERBS USING BLACK AND WHITE IN TURNBULLS ROAD IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/4763,Footpath,Completed,NJ-TEYNAMPET,122,44600,"PAINTING FOOT PATH KERBS USING BLACK AND WHITE IN TTK ROAD DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/4765,Footpath,Completed,NJ-TEYNAMPET,122,89000,"PAINTING FOOT PATH KERBS USING BLACK AND WHITE IN CHAMIERS ROAD DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/4919,Storm Water Drain,Completed,NJ-TEYNAMPET,122,974000,"Desilting and Removal of floating materials / Hyacinth garbages and Preventive measures for mosquito menance along Nandanam canal by using poclain vehicle from Alayamman koil to Adyar River in div-122,unit-26, zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/5344,Buildings,Completed,NJ-TEYNAMPET,122,198000,"URGENT MINOR REPAIRS TO PUBLIC CONVENIENCES IN CENOTAPH ROAD IN DN -122,UNIT -26 ,ZONE- 9 ASSET CODE(033/10181/1101/2015-16)",Own Sources,9,2016-17,2017-18 NJ/2016-17/5346,Buildings,Completed,NJ-TEYNAMPET,122,187000,"URGENT MINOR REPAIRS TO PUBLIC CONVENIENCES IN CHAMIERS 1ST LANE IN DIV -122,UNIT -26,ZONE -9,ASSET CODE(033/16719/866/2014-15)",Own Sources,9,2016-17,2017-18 NJ/2016-17/5517,Buildings,Completed,NJ-TEYNAMPET,122,223000,"URGENT MINOR REPAIRS TO DISPENSARY IN ALAYAMMANKOIL IN DN -122,UNIT -26,ZONE -9 ASSET CODE (041/16720/1526/2013-14)",Own Sources,9,2016-17,2017-18 NJ/2016-17/5741,Buildings,Completed,NJ-TEYNAMPET,122,960000,"IMPROVEMENTS TO FOOTHPATH AT NANDHANAM EXTN 9TH STREET IN DN-122,U-26,Z-9 (WARD COUNCILOR FUND 2016-2017)",Own Sources,9,2016-17,2017-18 NJ/2016-17/5743,Buildings,Completed,NJ-TEYNAMPET,122,965000,"IMPROVEMENTS TO ROAD WIEDENING PORTION AT NANDHANAM 1ST CROSS STREET (WARDCOUNSILER FUND)IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/5884,Buildings,Completed,NJ-TEYNAMPET,122,450000,"Improvements to Night Shelter by supply of water arrangements and other improvement works at Chamiers Road in Dn 122,Unit-26,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/7817,Storm Water Drain,Completed,NJ-TEYNAMPET,122,111000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT GANESAPURAM 3RD STREET( west ) IN DN 122, UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/7818,Storm Water Drain,Completed,NJ-TEYNAMPET,122,109000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT GANESAPURAM 3rd STREET IN DN 122, UNIT 26,ZONE9",Own Sources,9,2016-17,2017-18 NJ/2016-17/7820,Storm Water Drain,Completed,NJ-TEYNAMPET,122,183000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT K.B.DHADSAN SALAI IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/8010,Storm Water Drain,Completed,NJ-TEYNAMPET,122,119000,"REPAIRS AND DESILTING OF STORM WATER DRAIN AT Cenatoph 1ST LANE IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2016-17,2017-18 BR/2016-17/17391,Footpath,Completed,BR-Bus Route Roads,123,2250000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Avvai Shanmugam Salai , C.V.Raman Road, Babu Jagajeevanram Salai and C.P.Ramasamy Road in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/18125,Footpath,Completed,BR-Bus Route Roads,123,1344000,"Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Musuri Subramanyam Salai, Luz Church Road, R.A.Puram 2nd Main Road and Venkatakrishna Road in Zone 9",Grants,9,2016-17,2017-18 L/2016-17/2108,Electrical,Completed,L-Electrical,123,1788700,"Additional work for Provision of 12 Nos of 8mtr Octagonal street lamp post with double straight Bracket with 24 nos 150w-165w LED fitting and 4 nos of 8mtr Octagonal street lamp post with single straight Bracket with 4 nos 150w-165w LED fitting at Luz Church road in Div-123,Zone-IX",Own Sources,9,2016-17,2017-18 NJ/2016-17/10211,Roads,Completed,NJ-TEYNAMPET,123,149000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT ABIRAMAPURAM 1ST STREET IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/10212,Roads,Completed,NJ-TEYNAMPET,123,241000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT EAST ABIRAMAPURAM IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/10213,Roads,Completed,NJ-TEYNAMPET,123,811000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT LUZ AVENUE 5TH STREET IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/10214,Roads,Completed,NJ-TEYNAMPET,123,380000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT LUZ AVENUE 4TH STREET IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/10215,Roads,Completed,NJ-TEYNAMPET,123,458000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT BAKTHAVACHALAM STREET IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/10216,Roads,Completed,NJ-TEYNAMPET,123,545000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT C.P.RAMASAMY LANE IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10220,Roads,Completed,NJ-TEYNAMPET,123,655000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT KRISHNA AVENUE IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10226,Roads,Completed,NJ-TEYNAMPET,123,328000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT KRISHNASAMY STREET IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/1065,Road Cut,Completed,NJ-TEYNAMPET,123,1388000,"RESTORATION OF ROAD CUT AT JUSTIC SUNDARAM ROAD MADE BY METRO WATER SEWERAGE BOARD IN DN-123, UNIT-25, ZONE-9.",Deposit Works,9,2016-17,2016-17 NJ/2016-17/14452,Buildings,Completed,NJ-TEYNAMPET,123,45400,"REPAIRS TO CHENNAI PRIMARY SCHOOL AT APPADURAI STREET IN DN 123,UNIT.25,ZONE.09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14454,Buildings,Completed,NJ-TEYNAMPET,123,312800,"REPAIRS TO CHENNAI MIDDLE SCHOOL AT ST MARYS ROAD IN DN 123,UNIT.25,ZONE.09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14458,Buildings,Completed,NJ-TEYNAMPET,123,97800,"REPAIRS TO CHENNAI HIGH SCHOOL AT ST ELDAMS ROAD IN DN 123,UNIT.25,ZONE.09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14459,Buildings,Completed,NJ-TEYNAMPET,123,63900,"REPAIRS TO CHENNAI PRIMARY SCHOOL AT THIRUVALLUVAR SALAI IN DN 123,UNIT.25,ZONE.09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14460,Buildings,Completed,NJ-TEYNAMPET,123,180000,"REPAIRS TO PUBLIC TOILET AT VENKATARAMAN STREET AND KABALI THOTTAM (6NOS) IN DN 123,UNIT.25,ZONE.09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14541,Buildings,Completed,NJ-TEYNAMPET,123,225000,"REPAIRS TO CHENNAI HIGHER SECONDARY SCHOOL AT BEEMANNA GARDEN STREET IN DN.123,UNIT.25,ZONE.9",Own Sources,9,2016-17,2017-18 NJ/2016-17/16243,Buildings,Completed,NJ-TEYNAMPET,123,1360000,"REPAIRS THE EXISTING COMMUNITY CENTRE AT C.P.RAMASAMY ROAD IN DN.123,UNIT.25,ZONE.9 (VARADHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16399,Buildings,Completed,NJ-TEYNAMPET,123,850000,"REPAIRS THE EXISTING COMPOUND WALL AT NAGESHWARA PARK IN DN.123,UNIT.25,ZONE.9 (VARADHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16409,Parks,Completed,NJ-TEYNAMPET,123,205000,"REPAIRS THE EXISTING PARK AT DEMONDY COLONY IN DN.123,UNIT.25,ZONE.9 (VARADHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16446,Parks,Completed,NJ-TEYNAMPET,123,205000,"REPAIRS THE EXISTING PARK AT R.A.PURAM 7TH MAIN ROAD IN DN.123,UNIT.25,ZONE.9 (VARADHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16457,Buildings,Completed,NJ-TEYNAMPET,123,853000,"REPAIRS THE EXISTING COMMUNITY HALL AT LUZ AVENUE ROAD IN DN.123,UNIT.25,ZONE.9 (VARADHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16465,Buildings,Completed,NJ-TEYNAMPET,123,205000,"REPAIRS THE EXISTING AMMA UNAVAGAM AT R.A.PURAM 3RD CROSS STREET IN DN.123,UNIT.25,ZONE.9 (VARADHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16471,Buildings,Completed,NJ-TEYNAMPET,123,203000,"REPAIRS THE EXISTING AMMA UNAVAGAM AT C.P.RAMASAMY ROAD IN DN.123,UNIT.25,ZONE.9 (VARADHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16628,Parks,Completed,NJ-TEYNAMPET,123,186000,Greenarry Arrangements for Nageshwara Park Affected by Vartha Cyclone in Luz Church Road in Dn-123 Unit-25 Zone-09,Own Sources,9,2016-17,2017-18 NJ/2016-17/17938,Playfields,Completed,NJ-TEYNAMPET,123,1215000,"REPAIRS AND IMPROVEMENTS TO PLAY GROUND FOR VARADHA CYCLONE AT ST MARYS ROAD IN DN.123,UNIT.25,ZONE.9",Own Sources,9,2016-17,2017-18 NJ/2016-17/17986,Roads,Completed,NJ-TEYNAMPET,123,1543000,"ATTENDING PATCH WORK AT BHEEMANA GARDEN STREET AND OTHER STREETS IN DN 123,124,125 & 126 IN UNIT-25,ZONE 9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2478,Storm Water Drain,Completed,NJ-TEYNAMPET,123,170000,"DESILTING AND STORM WATER DRAIN AT DR.RANGA SALAI IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2479,Storm Water Drain,Completed,NJ-TEYNAMPET,123,100000,"DESILTING AND STORM WATER DRAIN AT DR.RANGA LANE IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2480,Storm Water Drain,Completed,NJ-TEYNAMPET,123,110000,"DESILTING AND STORM WATER DRAIN AT C.V. RAMAN SALAI IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2482,Storm Water Drain,Completed,NJ-TEYNAMPET,123,170000,"DESILTING AND STORM WATER DRAIN AT SEETHAMMAL MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2486,Storm Water Drain,Completed,NJ-TEYNAMPET,123,80000,"DESILTING AND STORM WATER DRAIN AT C.P.RAMASAMY SALAI IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2487,Storm Water Drain,Completed,NJ-TEYNAMPET,123,90000,"DESILTING AND STORM WATER DRAIN AT SEETHAMMAL 1ST STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2488,Storm Water Drain,Completed,NJ-TEYNAMPET,123,90000,"DESILTING AND STORM WATER DRAIN AT SEETHAMMAL 2ND STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2491,Storm Water Drain,Completed,NJ-TEYNAMPET,123,120000,"DESILTING AND STORM WATER DRAIN AT R.A.PURAM 1ST MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2492,Storm Water Drain,Completed,NJ-TEYNAMPET,123,80000,"DESILTING AND STORM WATER DRAIN AT R.A.PURAM 3RD CROSS STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2493,Storm Water Drain,Completed,NJ-TEYNAMPET,123,110000,"DESILTING AND STORM WATER DRAIN AT R.A.PURAM 3RD MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2496,Storm Water Drain,Completed,NJ-TEYNAMPET,123,75000,"DESILTING AND STORM WATER DRAIN AT NARASIMAPURAM IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2497,Storm Water Drain,Completed,NJ-TEYNAMPET,123,71000,"DESILTING AND STORM WATER DRAIN AT MARVADITHOTTAM IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2498,Storm Water Drain,Completed,NJ-TEYNAMPET,123,200000,"DESILTING AND STORM WATER DRAIN AT R.A.PURAM 2ND MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2500,Storm Water Drain,Completed,NJ-TEYNAMPET,123,150000,"DESILTING AND STORM WATER DRAIN AT R.A.PURAM 4TH MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/3023,Footpath,Completed,NJ-TEYNAMPET,123,440000,"BLACK AND WHITE WASHING FOR FOOTPATH AT ALL FOOTPATH ROADS AND STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2016-17,2017-18 NJ/2016-17/3122,Buildings,Completed,NJ-TEYNAMPET,123,80000,"Supplying and Fixing Venyl Name Board in Public Convenience Div 123, 124 and 125, Unit-25, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/4954,Roads,Completed,NJ-TEYNAMPET,123,999000,"IMPROVEMENTS AND RELAYING CEMENT CONCRETE ROAD AT VISHALATCHI THOTTAM 1ST LANE (WARD MEMBER DEVELOPMENT SCHEME 2016-17) IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/4956,Roads,Completed,NJ-TEYNAMPET,123,999000,"IMPROVEMENTS AND RELAYING CEMENT CONCRETE ROAD AT VISHALATCHI THOTTAM 2ND LANE (WARD MEMBER DEVELOPMENT SCHEME 2016-17) IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/5807,Buildings,Completed,NJ-TEYNAMPET,123,999000,"IMPROVEMENTS WORK IN BEEMANNA GARDEN HIGHER SECONDARY SCHOOL LAB IN DN-123, UNIT-25, ZONE-9. (WARD MEMBER DEVELOPMENT SCHEME -2016-17)",Own Sources,9,2016-17,2016-17 NJ/2016-17/8608,Buildings,Completed,NJ-TEYNAMPET,123,760000,"Demolition of Chennai Primary School at Beemanna Garden Street in Division -123,Unit-25, Zone-9.",Own Sources,9,2016-17,2018-19 L/2016-17/13241,Electrical,Completed,L-Electrical,124,587600,"Replacement of 20 nos of Damaged Kiosk Pillar Boxes at Anna Salai, Santhome high road and Various locations in Division 111, 121,119,124,125 and 126 Zone IX.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10267,Roads,Completed,NJ-TEYNAMPET,124,165000,"RELAYING OF THE ROAD WITH CBC30MM THICK BY PAVAR FINISH AT SOLAIYAPPAN STREET IN DN-123, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/14411,Buildings,Completed,NJ-TEYNAMPET,124,550000,"Improvement works to the Public Convenience at various Street in Div-124, Unit-25, Zone-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/14423,Buildings,Completed,NJ-TEYNAMPET,124,221900,"Improvement works to Chennai Middle School and Chennai Primary School at Mundakakanniyamman Koil and Slaterpuram Street in Div-124, Unit-25, Zone-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16757,Buildings,Completed,NJ-TEYNAMPET,124,202000,"REPAIRS THE EXISTING AMMA UNAVAGAM AT MANDAVELLI STREET IN DN-124, UNIT-25, ZONE-9. (VARDHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16769,Buildings,Completed,NJ-TEYNAMPET,124,203000,"REPAIRS THE EXISTING AMMA UNAVAGAM AT SARATHAPURAM MAIN ROAD IN DN-124, UNIT-25, ZONE-9. (VARDHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16790,Buildings,Completed,NJ-TEYNAMPET,124,506000,"REPAIRS THE EXISTING DISPENSARY AT MUNDAHAKANNI AMMAN KOIL STREET IN DN-124, UNIT-25, ZONE-9. (VARDHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/16797,Buildings,Completed,NJ-TEYNAMPET,124,506000,"REPAIRS THE EXISTING SCHOOL AT MUNDAHAKANNI AMMAN KOIL STREET IN DN-124, UNIT-25, ZONE-9. (VARDHA CYCLONE AFFECTED DURING 2016)",Own Sources,9,2016-17,2017-18 NJ/2016-17/2680,Storm Water Drain,Completed,NJ-TEYNAMPET,124,80000,"DESILTING AND STORM WATER DRAIN AT MOSQUE STREET IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2681,Storm Water Drain,Completed,NJ-TEYNAMPET,124,120000,"DESILTING AND STORM WATER DRAIN AT ABRAHAM STREET IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2683,Storm Water Drain,Completed,NJ-TEYNAMPET,124,110000,"DESILTING AND STORM WATER DRAIN AT SOLAIAPPAN STREET IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2685,Storm Water Drain,Completed,NJ-TEYNAMPET,124,70000,"DESILTING AND STORM WATER DRAIN AT KESAVA PERUMAL SANNATHI STREET IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2686,Storm Water Drain,Completed,NJ-TEYNAMPET,124,80000,"DESILTING AND STORM WATER DRAIN AT KESAVA PERUMAL EAST IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2687,Storm Water Drain,Completed,NJ-TEYNAMPET,124,70000,"DESILTING AND STORM WATER DRAIN AT KESAVA PERUMAL WEST IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2688,Storm Water Drain,Completed,NJ-TEYNAMPET,124,90000,"DESILTING AND STORM WATER DRAIN AT MANDAVELI LANE IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2689,Storm Water Drain,Completed,NJ-TEYNAMPET,124,170000,"DESILTING AND STORM WATER DRAIN AT R.K.MUTT SALAI IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2690,Storm Water Drain,Completed,NJ-TEYNAMPET,124,70000,"DESILTING AND STORM WATER DRAIN AT R.K.MUTT SALAI TO NORTH MADA SALAI IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2692,Storm Water Drain,Completed,NJ-TEYNAMPET,124,70000,"DESILTING AND STORM WATER DRAIN AT KUTCHERY SALAI IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2694,Storm Water Drain,Completed,NJ-TEYNAMPET,124,65000,"DESILTING AND STORM WATER DRAIN AT RAMAKRISHNAPURAM 1ST STREET IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2695,Storm Water Drain,Completed,NJ-TEYNAMPET,124,135000,"DESILTING AND STORM WATER DRAIN AT MUNDAKAKANNI AMMAN KOIL STREET IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2697,Storm Water Drain,Completed,NJ-TEYNAMPET,124,110000,"DESILTING AND STORM WATER DRAIN AT LOGANATHAN COLONY IN DN-124, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2792,Storm Water Drain,Completed,NJ-TEYNAMPET,124,65000,"DESILTING AND STORM WATER DRAIN AT RAMAKRISHNAPURAM 2ND STREET IN DN-124, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2793,Storm Water Drain,Completed,NJ-TEYNAMPET,124,80000,"DESILTING AND STORM WATER DRAIN AT RAMAKRISHNAPURAM 3RD STREET IN DN-124, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2800,Storm Water Drain,Completed,NJ-TEYNAMPET,124,66000,"DESILTING AND STORM WATER DRAIN AT RAMAKRISHNAPURAM 4TH STREET IN DN-124, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2807,Storm Water Drain,Completed,NJ-TEYNAMPET,124,85000,"DESILTING AND STORM WATER DRAIN AT RAMAKRISHNAPURAM 5TH STREET IN DN-124, UNIT-25, ZONE-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/5762,Road Cut,Completed,NJ-TEYNAMPET,124,1420000,"Restoration of road cut made by CMWSSB at V.C.Garden 1st Street in Div-124, U-25, Z-09",Deposit Works,9,2016-17,2017-18 BR/2016-17/17661,Roads,Completed,BR-Bus Route Roads,125,590000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Santhome High Road, Venkatakrishna Road, Pasumpon Muthuramalinga devar salai, Anna Salai, TTK Road and Eldams Road in Zone-9",Grants,9,2016-17,2017-18 L/2016-17/3144,Electrical,Completed,L-Electrical,125,1804200,"WORK Erection of 11 Nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single Arch Bracket with 11 Nos 90w-120w LED fitting, 27 Nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single straight Bracket with 27 Nos 40w-50w LED fitting at Nocchi Kuppam in Division-125 ,Zone-IX",Deposit Works,9,2016-17,2016-17 L/2016-17/3723,Electrical,Completed,SP-SPECIAL PROJECTS,125,3424200,"Provision of 46 Nos of 8mtr Octagonal street lamp post with single straight Bracket with 46 nos 90w-120w LED fitting at By Pass Road,Pattinapakkam ( Phase-I) in Div-125,Zone-IX",Own Sources,9,2016-17,2016-17 NJ/2016-17/10153,Roads,Completed,NJ-TEYNAMPET,125,245000,"Relaying of the Road with BC 30mm thick by Paver finish at Nainar Lane in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10158,Roads,Completed,NJ-TEYNAMPET,125,121000,"Relaying of the Road with BC 30mm thick by Paver finish at Kangeyapuram in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10162,Roads,Completed,NJ-TEYNAMPET,125,43000,"Relaying of the Road with BC 30mm thick by Paver finish at Powder mill 1st street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10165,Roads,Completed,NJ-TEYNAMPET,125,172000,"Relaying of the Road with BC 30mm thick by Paver finish at Powder Mill 2nd Street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10166,Roads,Completed,NJ-TEYNAMPET,125,60000,"Relaying of the Road with BC 30mm thick by Paver finish at Sonachalam street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10167,Roads,Completed,NJ-TEYNAMPET,125,280000,"Relaying of the Road with BC 30mm thick by Paver finish at Dooming lane in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10173,Roads,Completed,NJ-TEYNAMPET,125,102000,"Relaying of the Road with BC 30mm thick by Paver finish at Venkatesan street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/12180,Roads,Completed,NJ-TEYNAMPET,125,638000,"Disposal of Rain Water Using rain water pipe at Kamarajar Salai in Div-125, U-25, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14033,Buildings,Completed,NJ-TEYNAMPET,125,68200,"Improvement works to the Public Convenience at Karaneeswarar Pagoda Street in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14062,Buildings,Completed,NJ-TEYNAMPET,125,5200,"Improvement works to the Public Convenience at Mangollai East Mada Street in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14063,Buildings,Completed,NJ-TEYNAMPET,125,66000,"Damaged works to the Public Convenience at Demonte Street in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14064,Buildings,Completed,NJ-TEYNAMPET,125,31600,"Improvement works to the Public Convenience at Kamarajar Salai in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14065,Buildings,Completed,NJ-TEYNAMPET,125,75000,"Improvement works to the Public Convenience at Kailasapuram in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14067,Buildings,Completed,NJ-TEYNAMPET,125,18000,"Improvement works to the Public Convenience at Dr.Natesan Road in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14068,Buildings,Completed,NJ-TEYNAMPET,125,7300,"Improvement works to the Public Convenience at Batcha Garden in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14076,Buildings,Completed,NJ-TEYNAMPET,125,17000,"Improvement works to the Public Convenience at Service Road in Div-125, Unit-25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14372,Buildings,Completed,NJ-TEYNAMPET,125,457000,"Demolition of Chennai High School Old Building at Karaneeswarar Pagoda Street in Div-125, Unit-25, Zone-09.",Own Sources,9,2016-17,2018-19 NJ/2016-17/14402,Buildings,Completed,NJ-TEYNAMPET,125,106400,"Improvement works to Chennai Primary School at Kamarajar Salai in Div-125, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14403,Buildings,Completed,NJ-TEYNAMPET,125,26500,"Improvement works to Chennai Middle School at Prof.Sanjivi Street in Div-125, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/14436,Buildings,Completed,NJ-TEYNAMPET,125,17100,"Improvement works to the Public Convenience at (Nochinagar Slum Board) Loop Road in Div-125, Un-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/14437,Buildings,Completed,NJ-TEYNAMPET,125,42200,"Improvement works to Chennai High School at Karaneeswarar Pagoda Street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/16304,Buildings,Completed,NJ-TEYNAMPET,125,23000,"Improvement works to the Amma unavagam at Kamarajar Salai in Div-125, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16305,Buildings,Completed,NJ-TEYNAMPET,125,85000,"Improvements to the Compound Wall for the Community Center at Karaneeswarar Pagoda Street in Div-125, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16334,Buildings,Completed,NJ-TEYNAMPET,125,38000,"Improvement works to the Corporation Division Office at Sringeri Mutt Road in Div-126, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16357,Buildings,Completed,NJ-TEYNAMPET,125,16000,"Improvement works to the Chennai Middle School at Prof.Sanjivi Street in Div-125, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16359,Buildings,Completed,NJ-TEYNAMPET,125,58000,"Improvements works to the ICDS at Bazzar Road, Police Quarters, Prof.Sanjivi Street, Dooming Kuppam, Kuyil Thootam in Div-125, U-25,Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16360,Buildings,Completed,NJ-TEYNAMPET,125,410000,"Improvements works to the( City Center ) OSR park at Nainar Nadar Street in Div-125, U-25,Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16552,Storm Water Drain,Completed,NJ-TEYNAMPET,125,7000,"Improvement works to the Storm Water Drain at Sundareeswarar Swamy Street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17895,Footpath,Completed,NJ-TEYNAMPET,125,11900,"Improvements to the Footpath at Venkatasamy Street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17896,Footpath,Completed,NJ-TEYNAMPET,125,6720,"Improvements to the Footpath at Appu 1st Street in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17897,Footpath,Completed,NJ-TEYNAMPET,125,52600,"Improvements to the Footpath at kutchery road in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17898,Footpath,Completed,NJ-TEYNAMPET,125,36600,"Improvements to the Footpath at Rosary church Road in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17899,Footpath,Completed,NJ-TEYNAMPET,125,210550,"Improvements to the Footpath at Dr.radhakrishnan salai in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17900,Footpath,Completed,NJ-TEYNAMPET,125,168500,"Improvements to the Footpath at Santhome high road in Div-125, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/17973,Roads,Completed,NJ-TEYNAMPET,125,630000,"Relaying of the Road with BC 30mm thick by Paver finish at Karaneeswarar pagoda street in Div-125, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/1826,Storm Water Drain,Completed,NJ-TEYNAMPET,125,225000,"Desilting of Storm Water Drain at Karaneeswarar Pagoda Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2072,Buildings,Completed,NJ-TEYNAMPET,125,313000,"WATER SUPPLY AND DRAINGE ARANGEMENTS TO E-TOILET PROFESSOR SANJIV STREET IN DIV-125, UNIT-25, ZONE-9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2331,Parks,Completed,NJ-TEYNAMPET,125,160000,"Supplying and Planting of plants in Center median at Dr.Radhakrishnan Salai in Div-125, Unit-25, Zone-09.",Own Sources,9,2016-17,2016-17 NJ/2016-17/2383,Buildings,Completed,NJ-TEYNAMPET,125,172000,"Improvements work Amma unavagam at Kamarajar Salai in Div -125, Unit-25,Zone-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/2637,Storm Water Drain,Completed,NJ-TEYNAMPET,125,190000,"Improvements to Existing Foot path, Painting footpath kerbs and Center median at Dr.Radha Krishnan Salai for Independence Day 2016 in Dn-125, Unit-25, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2638,Storm Water Drain,Completed,NJ-TEYNAMPET,125,158000,"Desilting of Storm Water Drain at Dr.Natesan Road in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2643,Storm Water Drain,Completed,NJ-TEYNAMPET,125,120000,"Desilting of Storm Water Drain at P.V.Koil Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2644,Storm Water Drain,Completed,NJ-TEYNAMPET,125,125000,"Desilting of Storm Water Drain at Prof.Sanjivi Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2645,Storm Water Drain,Completed,NJ-TEYNAMPET,125,99000,"Desilting of Storm Water Drain at Rosary Church Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2646,Storm Water Drain,Completed,NJ-TEYNAMPET,125,131000,"Desilting of Storm Water Drain at East Mada Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2647,Storm Water Drain,Completed,NJ-TEYNAMPET,125,140000,"Desilting of Storm Water Drain at Sundareeswarar Swamy Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2648,Storm Water Drain,Completed,NJ-TEYNAMPET,125,114000,"Desilting of Storm Water Drain at Muthu Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2649,Storm Water Drain,Completed,NJ-TEYNAMPET,125,150000,"Desilting of Storm Water Drain at Venkatasamy Street in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2660,Storm Water Drain,Completed,NJ-TEYNAMPET,125,115000,"Desilting of Storm Water Drain at Santhome High Road in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/2663,Storm Water Drain,Completed,NJ-TEYNAMPET,125,100000,"Desilting of Storm Water Drain at Thandavarayan Street in Div -125 , Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/3148,Storm Water Drain,Completed,NJ-TEYNAMPET,125,199000,"Desilting of Storm Water Drain at St.Bedes Ground in Div -125, Unit -25, Zone -9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/3299,Storm Water Drain,Completed,NJ-TEYNAMPET,125,224000,"Desilting of Storm Water Drain at Dr.RadhaKrishnan salai in Div -125, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/4741,Roads,Completed,NJ-TEYNAMPET,125,200000,"Improvements to Existing Foot path, Painting footpath kerbs and Center median at Kamarajar Salai for Independence Day 2016 in Dn-125, Unit-25, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/4745,Roads,Completed,NJ-TEYNAMPET,125,240000,"Improvements to Existing Foot path, Painting footpath kerbs and Center median at Santhome High Rd (for Independence Day 2016) in Dn-125, Unit-25, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/5099,Buildings,Completed,NJ-TEYNAMPET,125,920000,"Proposed Amma Unavagam Dining Hall & Toilet at Prof.Sanjivi Street in Div-125, Unit-25, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/5709,Footpath,Completed,NJ-TEYNAMPET,125,721000,"Forming Footpath at Appu 2nd Street (Councillor Fund)In Div-125, Unit-25, Zone - 9.",Own Sources,9,2016-17,2019-20 NJ/2016-17/5710,Roads,Completed,NJ-TEYNAMPET,125,490000,"Widening the road with CC work at Chithirakulam North Street (Councillor Fund)In Div-125, Unit-25, Zone - 9.",Own Sources,9,2016-17,2019-20 NJ/2016-17/5711,Roads,Completed,NJ-TEYNAMPET,125,405000,"Widening the road with CC work at Kangayapuram (Councillor Fund)In Div-125, Unit-25, Zone - 9.",Own Sources,9,2016-17,2019-20 NJ/2016-17/5723,Buildings,Completed,NJ-TEYNAMPET,125,275000,"Improvement works to Public Convenience at Ekambaram Street in Div-125, U-25, Zone-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/8383,Storm Water Drain,Completed,NJ-TEYNAMPET,125,352000,"Disposal of Rain Water Using Hume pipe at Santhome High Road and Madha Church Road in Div-125 and 126, U-25, Zone-09",Own Sources,9,2016-17,2017-18 BR/2016-17/17062,Roads,Completed,BR-Bus Route Roads,126,3210000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at uthamar Gandhi salai, Haddows Road, Whites Road and Woods Road in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/17065,Roads,Completed,BR-Bus Route Roads,126,888000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at K.B.Dasan Road, Quiedh Millath Road, Bharathi salai and G.N.Chetty Road in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/17379,Footpath,Completed,BR-Bus Route Roads,126,1600000,Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at South Boag Road and North Boag Road in Zone 9,Grants,9,2016-17,2017-18 BR/2016-17/17658,Roads,Completed,BR-Bus Route Roads,126,838000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at kamarajar Salai in Dn-114 & 116, Zone-9",Grants,9,2016-17,2017-18 BR/2016-17/17728,Roads,Completed,BR-Bus Route Roads,126,995000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at EVR salai, Anna Nagar 6th Avenue,3rd Avenue, 4th Avenue and Anna Nagar 18th Main Road in Zone-8",Grants,9,2016-17,2017-18 BR/2016-17/17791,Roads,Completed,BR-Bus Route Roads,126,618000,"RECTIFICATION OF BUS SHELTER IN BAZZULA ROAD, MOSQUE ROAD, WEST JONES ROAD , KALLIAMMAN KOIL ST, DR.AMBEDKAR ROAD. ZONE-10.",Grants,9,2016-17,2017-18 BR/2016-17/17792,Roads,Completed,BR-Bus Route Roads,126,600000,"RECTIFICATION OF BUS SHELTER AT SADHAR PATEL ROAD,THALUK OFFICE ROAD, GANDHI MANDABAM ROAD, WEST AVENUE, ECR AT ZONE-13.",Grants,9,2016-17,2017-18 BR/2016-17/17793,Roads,Completed,BR-Bus Route Roads,126,930000,"RECTIFICATION OF BUS SHELTER IN MADIPAKKAM MAIN ROAD , VELACHERY MAIN ROAD, PALLAVARM RADIAL ROAD, PERUMBAKKAM MAIN ROAD IN ZONE-14.",Grants,9,2016-17,2017-18 BR/2016-17/17794,Roads,Completed,BR-Bus Route Roads,126,155000,"RECTIFICATION OF BUS SHELTER IN SECERTAT COLONY,KANAGAI NAGAR IN ZONE-15.",Grants,9,2016-17,2017-18 BR/2016-17/17795,Roads,Completed,BR-Bus Route Roads,126,458000,"RECTIFICATION OF BUS SHELTER IN KUNDRATHUR ROAD, MOUNT PONTHAMALI, POOTHAMALI ROAD IN ZONE-11.",Grants,9,2016-17,2017-18 BR/2016-17/17796,Roads,Completed,BR-Bus Route Roads,126,880000,"RECTIFICATION OF BUS SHELTER IN VELACHERY MAIN ROAD, 100 FEET BYPASS ROAD, FIVE FURLONG ROAD, TARAMANI 100 FEET ROAD. IN ZONE -13.",Grants,9,2016-17,2017-18 BR/2016-17/17797,Roads,Completed,BR-Bus Route Roads,126,710000,"RECTIFICATION OF BUS SHELTER AT DURGABAI DESHMUK ROAD, JAWAGARLAL NEHRU ROAD, ANNA SALAI IN ZONE-13.",Grants,9,2016-17,2017-18 BR/2016-17/17798,Roads,Completed,BR-Bus Route Roads,126,530000,"RECTIFICATION OF BUS SHELTER IN N.S.K SALAI, ANNA MAIN ROAD, RAGAVAN COLONY, KAMARAJ SALAI, P.T.RAJAN SALAI, G.N.CHEETY ST , PRAKASAM ROAD. IN ZONE-10.",Grants,9,2016-17,2017-18 BR/2016-17/17799,Roads,Completed,BR-Bus Route Roads,126,368000,"RECTIFICATION OF BUS SHELTER IN MANAPAKKAM GERUKABAKKAM MAIN ROAD, MOUNT POONTHAMALI,IN ZONE-12.",Grants,9,2016-17,2017-18 BR/2016-17/17882,Roads,Completed,BR-Bus Route Roads,126,2340000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at Dr.Besant Road, R.K.Mutt Road, South Canal Bank Road and Santhome High Road in Zone 9",Grants,9,2016-17,2017-18 BR/2016-17/17885,Footpath,Completed,BR-Bus Route Roads,126,2173000,Attending temporary repairs to damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Santhome High RoMad in Zone 9,Grants,9,2016-17,2017-18 BR/2016-17/7209,Roads,Completed,BR-Bus Route Roads,126,950000,"Attending Patchwork, repairs to existing Bus Shelter and providing thermoplastic paints, studs to various Bus Route Roads in Zone-9",Own Sources,9,2016-17,2017-18 L/2016-17/3809,Electrical,Completed,SP-SPECIAL PROJECTS,126,3048700,"Provision of 41 Nos of 8mtr Octagonal street lamp post with single straight Bracket with 41 nos 90w-120w LED fitting at By Pass Road, Pattinapakkam ( Phase-2) in Div-126,Zone-IX",Own Sources,9,2016-17,2016-17 L/2016-17/3810,Electrical,Completed,SP-SPECIAL PROJECTS,126,1215900,"Provision of 16 Nos of 8mtr Octagonal street lamp post with single straight Bracket with 16 nos 90w-120w LED fitting at By Loop Road in Div-126, Zone-IX",Own Sources,9,2016-17,2016-17 NJ/2016-17/10308,Roads,Completed,NJ-TEYNAMPET,126,150000,"Relaying of the Road with BC 30mm thick by Paver finish at Thiruvalluvar pet in Div-126, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10311,Roads,Completed,NJ-TEYNAMPET,126,997000,"Relaying of the Road with BC 30mm thick by Paver finish at 3rd Trust cross street in Div-126, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10313,Roads,Completed,NJ-TEYNAMPET,126,1615000,"Relaying of the Road with BC 30mm thick by Paver finish at west circular road in Div-126, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/10314,Roads,Completed,NJ-TEYNAMPET,126,1161000,"Relaying of the Road with BC 30mm thick by Paver finish at Norton main road in Div-126, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/12724,Roads,Completed,NJ-TEYNAMPET,126,555000,"Restoration of road cut in Thiruvengadam street in Div-126, Unit-25, Zone-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/13418,Buildings,Completed,NJ-TEYNAMPET,126,260000,"PROPOSED CONSTRUCTION OF COMPOSITE BIN AT SRINGERI MUTT ROAD IN DN-126,UNIT-25,ZONE-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/13779,Buildings,Completed,NJ-TEYNAMPET,126,537000,"Forming of compound Wall (Chennai Middle School)at 4th Trust Link Street in Div-126, Unit-25, Zone -9.",Own Sources,9,2016-17,2018-19 NJ/2016-17/14491,Buildings,Completed,NJ-TEYNAMPET,126,108610,"Improvement works to Chennai High School at Sringeri Mutt Road in Div-126, U-25, Z-09",Own Sources,9,2016-17,2018-19 NJ/2016-17/16324,Buildings,Completed,NJ-TEYNAMPET,126,49000,"Improvement works to the Amma unavagam at Santhome High Road in Div-126, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16336,Buildings,Completed,NJ-TEYNAMPET,126,16000,"Improvement works to the Chennai High School at Sringeri Mutt Road in Div-126, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16339,Buildings,Completed,NJ-TEYNAMPET,126,48000,"Improvement works to the NMPP Shelter at South Canal Bank Road in Div-126, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/16340,Buildings,Completed,NJ-TEYNAMPET,126,23000,"Improvement works to the Health center at R.K.Nagar 2nd Main Road in Div-126, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/17906,Footpath,Completed,NJ-TEYNAMPET,126,254800,"Improvements to the Footpath at Santhome High Road in Div-126, U-25, Z-09.",Own Sources,9,2016-17,2017-18 NJ/2016-17/18534,Parks,Completed,NJ-TEYNAMPET,126,122000,"Out Sourcing Maintenance of Park (9 MONTHS ) at Lazarus Church Park in Dn 126,Unit-25,Zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2460,Buildings,Completed,NJ-TEYNAMPET,126,142000,"Providing R.C.C slab and Desilting of Storm water drainage at Devanathan Street in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2462,Buildings,Completed,NJ-TEYNAMPET,126,144000,"Providing R.C.C slab and Desilting of Storm water drainage at R.K.Mutt Road in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2468,Buildings,Completed,NJ-TEYNAMPET,126,111000,"Providing R.C.C slab and Desilting of Storm water drainage at South Canal Bank Road in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2469,Buildings,Completed,NJ-TEYNAMPET,126,62000,"Providing R.C.C slab and Desilting of Storm water drainage at Jeth Nagar 1st Cross Street in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2470,Buildings,Completed,NJ-TEYNAMPET,126,73000,"Providing R.C.C slab and Desilting of Storm water drainage at Jeth Nagar 3rd Cross Street in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2477,Buildings,Completed,NJ-TEYNAMPET,126,89000,"Providing R.C.C slab and Desilting of Storm water drainage at 5th Trust Cross Street (part-1)in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2481,Buildings,Completed,NJ-TEYNAMPET,126,183000,"Providing R.C.C slab and Desilting of Storm water drainage at 2nd Trust Main Road in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2489,Buildings,Completed,NJ-TEYNAMPET,126,161000,"Providing R.C.C slab and Desilting of Storm water drainage at Thiruvengadam Street in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/2495,Buildings,Completed,NJ-TEYNAMPET,126,47000,"Providing R.C.C slab and Desilting of Storm water drainage at 10th Trust Cross Street in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2501,Buildings,Completed,NJ-TEYNAMPET,126,43000,"Providing R.C.C slab and Desilting of Storm water drainage at 4th Trust Link Street in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2503,Storm Water Drain,Completed,NJ-TEYNAMPET,126,143000,"Providing R.C.C slab and Desilting of Storm water drainage at Lazarus Church Road in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/2507,Buildings,Completed,NJ-TEYNAMPET,126,500000,"Providing R.C.C slab and Desilting of Storm water drainage at Santhome High Road in Div.126, Unit-25, Zone-9",Own Sources,9,2016-17,2018-19 NJ/2016-17/3771,Footpath,Completed,NJ-TEYNAMPET,126,1000000,"Improvements of Footpath Granite Slab from Madha Church Road to 3rd Trust Link Street in Div-126,Unit-25,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/3773,Buildings,Completed,NJ-TEYNAMPET,126,1000000,"Improvements Footpath from Madha Church Road to 3rd Trust Link Street in Division-126,Unit-25,Zone-9",Own Sources,9,2016-17,2017-18 NJ/2016-17/7220,Electrical,Completed,NJ-TEYNAMPET,126,2620000,"Construction of Modern Toilet at Inside The Chennai Primary and High School at sringeri mutt Road (Under MLA Constituency Development Scheme ) in Division-126,Unit-25,Zone-9",MLACDS,9,2016-17,2018-19 NJ/2016-17/7221,Buildings,Completed,NJ-TEYNAMPET,126,948000,"Proposed Construction of Toilet for Block for Chennai Middle School at 4th Trust Link Street (Under MLA Constituency Development Scheme ) in Division-126,Unit-25,Zone-9",MLACDS,9,2016-17,2018-19 NJ/2016-17/7907,Buildings,Completed,NJ-TEYNAMPET,126,130000,"Improvements to Compound Wall M.P.Office at Santhome High Road in Div-126, U-25, Z-09",Own Sources,9,2016-17,2017-18 NJ/2016-17/8214,Roads,Completed,NJ-TEYNAMPET,126,220000,"PROVIDING BLACK AND WHITE PAINTING FOR FOOTPATH KERB AND CENTER MEDIAN AT SANTHOME HIGH ROAD IN VIEW OF INDEPENDANCE DAY 2016 IN DIVISION - 126,UNIT - 25, ZONE - 9.",Own Sources,9,2016-17,2017-18 NJ/2016-17/8249,Buildings,Completed,NJ-TEYNAMPET,126,135000,"Improvements work to Public Convenience at Andimaniyam Thottam in Div-126, U-25, Z-09.",Own Sources,9,2016-17,2018-19 NJ/2016-17/9026,Roads,Completed,NJ-TEYNAMPET,126,980000,"ARRANGEMENTS TO SCAFFOLDING, CHAIR AND PANDHAL FOR IMMERSION OF VINAYAGAR STATUE AT LOOP ROAD BEACH IN DIV-126, UNIT-25, ZONE-9",Own Sources,9,2016-17,2018-19 BR/2016-17/14889,Roads,Completed,BR-Bus Route Roads,127,970000,"PROPOSED CONSTRUCTION OF CRASH BARRIER TYPE CENTRE MEDIAN AT KALLIAMMAN KOILSTREET( FROM AA ROAD TO NATESAN NAGAR ) IN DIV 127 , ZONE-10.",Own Sources,10,2016-17,2016-17 BR/2016-17/15370,Roads,Completed,BR-Bus Route Roads,127,2350000,"PROVIDING OF CRASH BARRIER TYPE CENTRE MEDIAN AT KALLIAMMAN KOIL ST FROM(CMWSSB GATE TO NATESAN NAGAR 3RD MAIN ROAD) IN DIV -127,ZONE-10.",Own Sources,10,2016-17,2017-18 BR/2016-17/17716,Roads,Completed,BR-Bus Route Roads,127,518000,"Attending temporary restoration of damaged footpath due to Vardha Cyclone in North East Monsoon 2016 at Arunachalam salai,kaliamman koil st, CIT Nagar 1st and 4th st in zone-10.",Grants,10,2016-17,2017-18 BR/2016-17/19386,Roads,Completed,BR-Bus Route Roads,127,1800000,"ROAD CUT RESTORATION WORK AT KALLIAMMAN KOIL STREET MADE BY TANTRANSCO IN DIV-127,ZONE-10",Deposit Works,10,2016-17,2017-18 D/2016-17/13423,Storm Water Drain,Completed,D-Storm Water Drains,127,945000,"Implementation of Campus Rain Water Harvesting at SAF games village complex at koyambedu in division 127,zone 10.",Own Sources,10,2016-17,2016-17 L/2016-17/12208,Electrical,Completed,L-Electrical,127,3463600,Errection of 21 nos 8 mtr lamp post and Removal and refixing of 27 nos 8 mtr lamp post and laying of 1630 mtrs 4 X 16 sqmm alu cable at Inner ring road (100 feet road)Div-127 Zone-10,Deposit Works,10,2016-17,2017-18 L/2016-17/1592,Electrical,Completed,L-Electrical,127,533100,Errection of 22 nos 6 mtr old lamp post and laying of 726 mtrs 2 X 16 sqmm alu cable at SAF Games village near X1 block and X2 block in Div-127 Zone-10,Own Sources,10,2016-17,2016-17 L/2016-17/18428,Electrical,Completed,L-Electrical,127,851000,"WORK: PROVISION OF 20 NOS OF OLD EL LAMP POST WITH 90W LED FITTING AT NERKUNDRUM VILLAGE IN DIVISION -127, ZONE-X",Own Sources,10,2016-17,2017-18 L/2016-17/18796,Electrical,Completed,L-Electrical,127,183100,"Erection of 10 Nos of old 7 mtr lamp post with 70w NV Fitting at Games village and New st in Div-127,zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/0432,Roads,Completed,NK-KODAMBAKKAM,127,2484000,"Installation of Water Treatment Plant, Maintenance and Operation of the plants at Avvai thiru Nagar in Ward No.127, Unit-29, Zone - 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/10407,Roads,Completed,NK-KODAMBAKKAM,127,260000,"Relaying of road using Bituminous concrete at Jai Nagar 1st main road in div-127, Unit-29, Zone-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10411,Roads,Completed,NK-KODAMBAKKAM,127,552000,"Relaying of road using Bituminous Concrete at New Colony Main road in div-127, Unit-29, Zone-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10419,Roads,Completed,NK-KODAMBAKKAM,127,731000,"Relaying of road using Bituminous Concrete at New Colony Cross Street in Div-127, Unit-29, Zone-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10425,Roads,Completed,NK-KODAMBAKKAM,127,1219000,"Relaying of Road using Bituminous Concrete at Burial ground Road in Div-127, Unit-29, Zone-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10454,Roads,Completed,NK-KODAMBAKKAM,127,873000,"Relaying of road using Bituminous Concrete at Sundaram street in Div-127, Unit-29, Zone-10",Own Sources,10,2016-17,2016-17 NK/2016-17/13392,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,995000,"CONSTRUCTION OF STORM WATER DRAIN AT KAALIAMMAN KOIL STREET (FROM CH:77M TO CH:154M) IN DN-127, UNIT-29,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/13393,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,998000,"CONSTRUCTION OF STORM WATER DRAIN AT KAALIAMMAN KOIL STREET (FROM SAI NAGAR ANNEX TO CH:77M) IN DN-127, UNIT-29,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/13402,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,993000,"CONSTRUCTION OF STORM WATER DRAIN AT KAALIAMMAN KOIL STREET (FROM CH:154M TO CH:231M) IN DN-127, UNIT-29,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/13410,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,992000,"CONSTRUCTION OF STORM WATER DRAIN AT KAALIAMMAN KOIL STREET (FROM CH:231M TO CH:308M) IN DN-127, UNIT-29,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/13411,Road Cut,Completed,NK-KODAMBAKKAM,127,798000,"RESTORATION OF ROAD CUT MADE BY TNEB AT SEMATHAMMAN NAGAR SECTOR 3 IN DIN 127, UNIT-29,ZONE 10",Deposit Works,10,2016-17,2018-19 NK/2016-17/13566,Electrical,Completed,NK-KODAMBAKKAM,127,992800,"REPLACEMENT OF 168 NOS OF 10 W to 20 W LED FITTING IN PLACE OF 1X18W CFL FITTING AT GAMES VILLAGE A-3 ,A-8,A-1,B-7,C-1,C-7,C-8,C-12,C-4,X-2 BLOCK PARKS IN DIVISION -127, ZONE-X",Own Sources,10,2016-17,2017-18 NK/2016-17/13909,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,780000,"Desilting of Virugambakkam Canal from Sai Nagar Annex 2nd Main Road to Sai Nagar 2nd Main Road including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13910,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,767000,"Desilting of Virugambakkam Canal from Sai Nagar Annex 2nd Main Road to Bharathiyar Street including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/14046,Buildings,Completed,NK-KODAMBAKKAM,127,135000,"IMPROVEMENTS AND REPAIRS TO PC AT SIVAN KOIL STREET AND A.K.R.ROAD IN DIV -127, UNIT-29, ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/15170,Parks,Completed,NK-KODAMBAKKAM,127,700000,"ANNUAL MAINTENANCE OF PARK AT JAI NAGAR PARK-2 IN DN-127, U-29, Z- 10.(Employed qualified horticulturist for only)",Own Sources,10,2016-17,2018-19 NK/2016-17/15171,Parks,Completed,NK-KODAMBAKKAM,127,640000,"ANNUAL MAINTENANCE OF PARK AT JAI NAGAR PARK-1 IN DN-127, U-29, Z- 10.(Employed qualified horticulturist for only)",Own Sources,10,2016-17,2018-19 NK/2016-17/15511,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,767000,"Desilting of Virugambakkam Canal from Sai Nagar 2nd Main Road to Nerkundrum Main Road (Part - I) including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/15513,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,767000,"Desilting of Virugambakkam Canal from Sai Nagar 2nd Main Road to Nerkundrum Main Road (Part) including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/15589,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,665000,"Desilting of Virugambakkam Canal from Nerkundrum Main Road to Chithirai Street (Part) including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/15590,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,665000,"Desilting of Virugambakkam Canal from Nerkundrum Main Road to Chithirai Street (Part - I) including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 127, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/16909,Footpath,Completed,NK-KODAMBAKKAM,127,1670000,"REPAIR AND IMPROVEMENTS TO SAF GAMES VILLAGE OSR 1 TO 12 PARKS DAMAGES DUE TO VARDHA CYCLONE IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16933,Parks,Completed,NK-KODAMBAKKAM,127,350000,"Repairs and Damages to Natesan nagar park due to VARDHA Cyclone In division -127,Unit -29, Zone -10",Own Sources,10,2016-17,2017-18 NK/2016-17/16937,Parks,Completed,NK-KODAMBAKKAM,127,295000,"REPAIR AND IMPROVEMENTS TO JAI NAGAR PARK 1 & 2 DAMAGES DUE TO VARDHA CYCLONE IN DIV-127,UNIT-29, ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16967,Buildings,Completed,NK-KODAMBAKKAM,127,488000,"Improvements to Chennai Middle School Arumbakkam in Div 127,Unit-29, Zone 10",Own Sources,10,2016-17,2018-19 NK/2016-17/18429,Roads,Completed,NK-KODAMBAKKAM,127,990000,Providing kitchen shed to Amma unavagam at Semathammn nagar 3rd sector in Dn-127 U-29 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/18430,Roads,Completed,NK-KODAMBAKKAM,127,420000,Providing Toilet and water supply electrical arrangement to amma unavagam Kitchen shed at Semathamman nagar 3rd sector in Dn-127 U-29 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/18434,Roads,Completed,NK-KODAMBAKKAM,127,950000,Providing chain link Fencing and wet mix macadam at Amma Unavagam Semathamman nagar 3rd street in Dn-127 U-29 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/18436,Roads,Completed,NK-KODAMBAKKAM,127,990000,Providing Internal work at Amma Unavagam Semathamman nagar 3rd sector in Dn-127 U-29 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/18437,Roads,Completed,NK-KODAMBAKKAM,127,440000,Providing Internal civil work and outer flooring at Amma Unavagam Semthamman nagar 3rd sector in DN-127 U-29 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/19075,Buildings,Completed,NK-KODAMBAKKAM,127,27900,"ENGAGING PRIVATE LABOURS FOR SCHOOL SECURITY GUARDS FOR C.H.S.S IN KOYEMBEDU, FOR 3 MONTHS IN DN- 127,UNIT- 29,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19077,Buildings,Completed,NK-KODAMBAKKAM,127,55000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR C.M.S IN ARUMBAKKAM, FOR 3 MONTHS IN DN- 127,UNIT- 29,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/19084,Parks,Completed,NK-KODAMBAKKAM,127,82000,"ENGAGING PRIVATE LABOURS FOR OUT SOURCING WORK FOR THE PERIOD OF 3 MONTHS OF SWEEPERS AND SECURITY GUARDS FOR 3 MONTHS) IN NATESAN NAGAR PARK, IN DN-127,UNIT-29,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19195,Buildings,Completed,NK-KODAMBAKKAM,127,28400,"Engaging Private Labours For House Keeping Work For The Period Of 3 Months At Urban Public Health Centre, Natesan nagar 5th main road, virugambakkam, In Dn-127,Unit-29,Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19266,Buildings,Completed,NK-KODAMBAKKAM,127,56000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR C.H.S.S IN KOYEMBEDU, FOR 3 MONTHS IN DN- 127,UNIT- 29,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19269,Buildings,Completed,NK-KODAMBAKKAM,127,56000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR C.P.S IN KOYAMBEDU, FOR 3 MONTHS IN DN- 127,UNIT- 29,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19271,Buildings,Completed,NK-KODAMBAKKAM,127,27900,"Engaging Private Labours For Security guard For The Period Of 3 Months At Urban Public Health Centre, Natesan nagar 5th main road, viriugambakkam, In Dn-127,Unit-29,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19401,Roads,Completed,NK-KODAMBAKKAM,127,630000,"Relaying of B.T roads with bituminous concrete 30mm thick by mechanical paver finisher at P.A Colony,Chithirai street&Bharathiyar street in Div-127,Unit-29,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/19403,Roads,Completed,NK-KODAMBAKKAM,127,822000,"Relaying of B.T roads with bituminous concrete 30mm thick by mechanical paver finisher at Natesan nagar 2nd main road & thiruvalluvar street in Div-127,Unit-29,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/4800,Parks,Completed,NK-KODAMBAKKAM,127,407000,"maintenance to Park at OSR 1 to 12 at SAF Games Village in Div-127,Unit-29,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5488,Footpath,Completed,NK-KODAMBAKKAM,127,994900,"IMPROVEMENTS TO JAINAGAR PARK 1&2 AT JAINAGAR 1ST MAIN ROAD IN DN-127, U-29, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5671,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,817000,"Desilting of existing SW Drain at Brindavan nagar samanthi st, Parijatham st, Roja st, Sri ayyappa nagar 1st cross st, 6th main road, 4th main road,2nd main road,2nd cross street, Velan nagar, TSD nagar 1st main road, TSD nagar school street, Kurungaleshwarar koil st, East mada street, South mada st, Venkateswara nagar ext 2nd st and Sayee nagar annex in div-127, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5672,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,914000,"Desilting of existing SW Drain at Jai nagar 13th st,15th st, Semmathamman nagar sector 3 1st and 2nd main road, Srinivasa nagar, Mettukulam, Sundaram street, Mahalingam street, Sayee Nagar 1st main road,8th st, 7th st , 2nd main road, Avvai thiru nagar 2nd main road, Avvai thiru nagar 3rd st, 5th st, Brindavan nagar Malligai st, in div-127, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5675,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,950000,"Desilting of existing SW Drain at Thiruvalluvar street,Sri ayyappa nagar 3rd main road,Brindavan Nagar kurunji st,bRathnapuri layout,Jai nagar 1st main road,2nd main road,21st st,8th st,7th st, 6th st,5th st,4th st,3rd st, 10th st Valluvar st in div-127, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5678,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,953000,"Desilting of existing SW Drain at Sivasankaran st, Natesan nagr 1st cross st,5th st,4th st,3rd st,2nd st,West natesan nagar,Masi st, Chittirai st, Aani st,Kumaran nagar 2nd main road,3rd main road,5th cross st,1st cross st,1st main road,4th cross st and Sri ayyappa nagar 1st main road in div-127, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5788,Roads,Completed,NK-KODAMBAKKAM,127,845000,"PROVIDING AND LAYING GSB AND WMM AT KOYEMBEDU BURIAL GROUND ROAD (CH-115.00-230.00M ) IN DN-127,U-29,ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/5789,Buildings,Completed,NK-KODAMBAKKAM,127,845000,"PROVIDING AND LAYING GSB AND WMM AT KOYEMBEDU BURIAL GROUND ROAD (CH0.00-115 M) IN DN-127,U-29,ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/7801,Roads,Completed,NK-KODAMBAKKAM,127,340000,"Restoration of Road Cut made by TNEB at Srinivasan 2nd Street in Dn - 127, Unit - 29, Zone - X.",Deposit Works,10,2016-17,2017-18 P/2016-17/19683,Parks,Completed,P-Parks and Playfields,127,22866000,"FORMATION OF NEW PARK AT TNHB QUARTERS, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN-127, ZONE - 10",Grants,10,2016-17,2019-20 BR/2016-17/16985,Roads,Completed,BR-Bus Route Roads,128,2000000,"PROVIDING OF CRASH BARRIER TYPE CENTRE MEDIAN AT KALLIAMMAN KOIL ST FROM(NATESAN NAGAR 3RD MAIN ROAD TO THANGAL ROAD) IN DIV -128,ZONE-10.",Own Sources,10,2016-17,2017-18 BR/2016-17/17069,Roads,Completed,BR-Bus Route Roads,128,4900000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at Postal Colony 3rd street ,,Kaliamman koil st, Reddy st,Arunachalam st, West Sivan koil st,Ramaswamy st,Mosque st and K.K.Road in Zone 10.",Grants,10,2016-17,2017-18 BR/2016-17/19662,Roads,Completed,BR-Bus Route Roads,128,811000,"PROVIDING OF CRASH BARRIER TYPE CENTRE MEDIAN AT Pantheon road bridge ST FROM(Greams Road Jn. to TO Co-optex Bridge st.pt) IN DIV -61,ZONE-5.",Own Sources,10,2016-17,2017-18 L/2016-17/18797,Electrical,Completed,L-Electrical,128,169400,Replacement of 103 nos of Damaged 2 core SMC fuse box at Natesns nagar div-127 and Raman street div-128 and 33 nos 4 core SMC fuse box at CIT nagar div-141 in Zone-10,Own Sources,10,2016-17,2017-18 NK/2016-17/10844,Roads,Completed,NK-KODAMBAKKAM,128,819000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Indira Nagar 1st Cross Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/10845,Roads,Completed,NK-KODAMBAKKAM,128,819000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Indira Nagar 2nd Cross Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/10847,Roads,Completed,NK-KODAMBAKKAM,128,819000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Indira Nagar 3rd Cross Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/10848,Roads,Completed,NK-KODAMBAKKAM,128,819000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Indira Nagar 4th Cross Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/10849,Roads,Completed,NK-KODAMBAKKAM,128,948000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Indira Nagar 5th Cross Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/10850,Roads,Completed,NK-KODAMBAKKAM,128,1241000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Shaik Abdulla Nagar 1st Main Road in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2018-19 NK/2016-17/10851,Roads,Completed,NK-KODAMBAKKAM,128,448000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Kaveri Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2018-19 NK/2016-17/10852,Roads,Completed,NK-KODAMBAKKAM,128,448000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Vaigai Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/10855,Roads,Completed,NK-KODAMBAKKAM,128,1379000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Kannadasan Street in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/10857,Roads,Completed,NK-KODAMBAKKAM,128,689000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Ottapillaiyar Koil Street (Part) in Dn. 128, Unit-29, Zone- X",Own Sources,10,2016-17,2018-19 NK/2016-17/10858,Roads,Completed,NK-KODAMBAKKAM,128,699000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Venkatesh Nagar Main Road Part in Dn. 128, Unit-29, zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10859,Roads,Completed,NK-KODAMBAKKAM,128,979000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Thangal Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10860,Roads,Completed,NK-KODAMBAKKAM,128,472000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at AVM Avenue 2nd Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10861,Roads,Completed,NK-KODAMBAKKAM,128,839000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Lamber Nagar 1st Main Road in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10862,Roads,Completed,NK-KODAMBAKKAM,128,279000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Elango Nagar South Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10863,Roads,Completed,NK-KODAMBAKKAM,128,685000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Rukmani / LOganadhan Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10864,Roads,Completed,NK-KODAMBAKKAM,128,706000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at West Vanniyar Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10865,Roads,Completed,NK-KODAMBAKKAM,128,439000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Thiruvalluvar 3rd Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10866,Roads,Completed,NK-KODAMBAKKAM,128,685000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Murugesan / Raji Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/10867,Roads,Completed,NK-KODAMBAKKAM,128,874000,"Relaying of Road by using BC 30 mm thick with Mechanical Paver Finisher at Vinayagam Street in Dn. 128, Unit-29, Zone - X",Own Sources,10,2016-17,2016-17 NK/2016-17/11441,Roads,Completed,NK-KODAMBAKKAM,128,870000,"Repair to footpath at Arcot road in Dn. 130, Unit 29, Zone X.",Own Sources,10,2016-17,2019-20 NK/2016-17/11493,Roads,Completed,NK-KODAMBAKKAM,128,999000,"Attending patch work by using WMM at Sai Baba Colony Main Road, Yadhaval Street, Thiruvalluvar 2nd Street and Patchaiyamma Koil Street in Dn -128, Unit -29, Zone - X.",Own Sources,10,2016-17,2017-18 NK/2016-17/11520,Roads,Completed,NK-KODAMBAKKAM,128,935000,"Attending patch work by using WMM at Alwarthiru Nagar Annex 1st Main Road and Errikarai Street in Dn -128, Unit -29, Zone - X.",Own Sources,10,2016-17,2017-18 NK/2016-17/14593,Buildings,Completed,NK-KODAMBAKKAM,128,509000,"Repair works to Toilet and other Improvements to CHSS at School Street in DN-128, U-29, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/14594,Buildings,Completed,NK-KODAMBAKKAM,128,315000,"Repair works to Toilet and other Improvements to CPS at Pillaiyar koil street, Nesapakkam in DN-128, U-29, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/15176,Parks,Completed,NK-KODAMBAKKAM,128,695000,"ANNUAL MAINTENANCE OF PARK AT ANNAJI NAGAR 2nd STREET VIRUGAMBAKKAM (2 YEARS) IN DIVISION 128,UNIT-29,ZONE-10.(Qualified horticulturist only)",Own Sources,10,2016-17,2018-19 NK/2016-17/15177,Parks,Completed,NK-KODAMBAKKAM,128,650000,"ANNUAL MAINTENANCE OF PARK AT LAMBERT NAGAR AT VIRUGAMBAKKAM (2 YEARS) IN DIVISION 128,UNIT-29,ZONE-10.(Qualified horticulturist only)",Own Sources,10,2016-17,2019-20 NK/2016-17/16924,Buildings,Completed,NK-KODAMBAKKAM,128,68000,"Repairs to Compound Wall affected due to the Vardha Cyclone Division 128 Office at Kamaraj Salai in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16926,Buildings,Completed,NK-KODAMBAKKAM,128,143000,"Repairs to NNMP Shed affected due to the Vardha Cyclone at Krishna Nagar in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16929,Playfields,Completed,NK-KODAMBAKKAM,128,100000,"Repairs to Compound Wall affected due to the Vardha Cyclone at Elango Nagar, Tharachand Nagar, Jai Ashkaiya Phase-I and II in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16934,Parks,Completed,NK-KODAMBAKKAM,128,135000,"Repairs to Compound Wall and Greenary affected due to the Vardha Cyclone at Lambert Nagar Park in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/19068,Buildings,Completed,NK-KODAMBAKKAM,128,28400,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK ( 3 MONTHS ) IN URBAN PUBLIC HEALTH CENTRE AT KAMARAJ SALAI, VIRUGAMBAKKAM, CHENNAI IN DN-128,UNIT-29,ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19086,Buildings,Completed,NK-KODAMBAKKAM,128,113000,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK ( 3 MONTHS ) IN C.P.S (VIRUGAMBAKKAM), C.P.S (NESAPAKKAM),C.P.S(NEW BUILDING NESAPAKKAM) IN DN-128,UNIT-29,ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19132,Buildings,Completed,NK-KODAMBAKKAM,128,85000,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK ( 3 MONTHS ) IN C.H.S.S ,VIRUGAMBAKKAM IN DN-128,UNIT-29,ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19261,Buildings,Completed,NK-KODAMBAKKAM,128,27900,"ENGAGING PRIVATE SECURITY GUARDS ( FOR 3 MONTHS) IN UPHC AT VIRUGAMBAKKAM IN DN-128,UNIT-29,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19442,Roads,Completed,NK-KODAMBAKKAM,128,588000,"Relaying of B.T roads with bituminous concrete 30mm thick by mechanical paver finisher at Marriyamman koil street Reach-1 in Div-128,Unit-29,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/19444,Roads,Completed,NK-KODAMBAKKAM,128,941000,"Relaying of B.T roads with bituminous concrete 30mm thick by mechanical paver finisher at East vanniyar street Reach-1 in Div-128,Unit-29,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/19445,Roads,Completed,NK-KODAMBAKKAM,128,889000,"Relaying of B.T roads with bituminous concrete 30mm thick by mechanical paver finisher at Bazzar street in Div-128,Unit-29,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3900,Buildings,Completed,NK-KODAMBAKKAM,128,995000,"SUPPLYING OF EACH ONE OPERATOR AND ASSISTANT AT VIRUGAMBAKKAM ELECTRICAL CREMATORIUM IN DIVISION-128,UNIT-29,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/4445,Roads,Completed,NK-KODAMBAKKAM,128,423000,"Restoration of road cut made by CMWSSB at West vanniyar 2nd cross street in division-128, Unit-29, Zone-10",Deposit Works,10,2016-17,2017-18 NK/2016-17/7487,Road Cut,Completed,NK-KODAMBAKKAM,128,990000,"Restoration of road cut made by CMWSSB at Thiruvalluvar street in division-128, Unit-29, Zone-10",Deposit Works,10,2016-17,2017-18 NK/2016-17/8237,Buildings,Completed,NK-KODAMBAKKAM,128,304000,"SERVICING OF EXISTING ELECTRICAL CREMATORIUM AT THANGAL ERIKARAI STREET,VIRUGAMBAKKAM BURIAL GROUND IN DIV-128,U-29,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8296,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,133000,"Desillting and other Improvements to SWD at Jeevanantham street and East Vanniyar Street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8297,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,138000,"Desillting and other Improvements to SWD at Marriamman koil street and Bazzar Street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8298,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,115000,"Desillting and other Improvements to SWD at Thiruvalluvar 3rd street and Elango nagar 1st street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8299,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,229000,"Desillting and other Improvements to SWD at Elango nagar south street and Ganpathraj nagar main road in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8300,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,108000,"Desillting and other Improvements to SWD at Tharachand nagar 1st and 2nd streets in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8312,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,194000,"Desillting and other Improvements to SWD at Venkatesh nagar main road and Saibaba colony in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8313,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,104000,"Desillting and other Improvements to SWD at Rukmani loganathan street and patchaiyappan street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8314,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,275000,"Desillting and other Improvements to SWD at Annai sathya nagar main road , 1st, 3rd 5th and 9th streets in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8316,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,193000,"Desillting and other Improvements to SWD at Alwarthiru Nagar Annexe1St Main Road, 2nd main road, New colony 2nd main road and Laxmi nagar 1st and 2nd street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8318,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,173000,"Desillting and other Improvements to SWD at Narayana samy street and Thangal street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8319,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,130000,"Desillting and other Improvements to SWD Shaik abthullah nagar 1st main road,Mosque Street and Kannadhasan Street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8320,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,168000,"Desillting and other Improvements to SWD Avm Avenue 1St Main Road,Avm Avenue 2St Main Road,Avm Avenue 2Nd Street and Avm Avenue 8Th Street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8321,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,147000,"Desillting and other Improvements to SWD Ganthi nagar main road in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8326,Roads,Completed,NK-KODAMBAKKAM,128,997000,"Re-Laying of road with using BC 40mm thick by Mechanical Paver Finisher at Thangal Errikkarai Street in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8327,Roads,Completed,NK-KODAMBAKKAM,128,900000,"Re-Laying of road with using BC 40mm thick by Mechanical Paver Finisher at Kaliamman koil Street(Market) in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8328,Roads,Completed,NK-KODAMBAKKAM,128,800000,"Re-Laying of road with using BC 40mm thick by Mechanical Paver Finisher at Patchaiamman Koil Street in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8329,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,245000,"Desillting and other Improvements to SWD at Thiruvegadam street and Reddy street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8333,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,950000,IMPROVEMENTS TO STROM WATER DRAIN AT VEMBULI AMMANKOIL 1 ST CROSS STREET( UDAYAM COLONY ) ( FROM VEMBULIAMMAN KOIL STREET ) IN DN 128 UNIT 29 ZONE 10,Own Sources,10,2016-17,2018-19 NK/2016-17/8334,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,494000,IMPROVEMENTS TO STROM WATER DRAIN AT VEMBULI AMMANKOIL 1 ST CROSS STREET( UDAYAM COLONY ) ( FROM SCHOOL STREET ) IN DN 128 UNIT 29 ZONE 10,Own Sources,10,2016-17,2018-19 NK/2016-17/8335,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,147000,"Desillting and other Improvements to SWD at Bangaru naidu colony in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8336,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,748000,"Desillting and other Improvements to SWD at School Street in Dn-128, Unit-29, Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8339,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,986000,CONSTRUCTION OF STROM WATER DRAIN AT LAMPART NAGAR ( FROM N.S.K SALAI ) IN DN 128 UNIT 29 ZONE 10,Own Sources,10,2016-17,2018-19 NK/2016-17/8340,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,998000,CONSTRUCTION OF STROM WATER DRAIN AT LAMPART NAGAR ( FROM SCHOOL ROAD ) IN DN 128 UNIT 29 ZONE 10,Own Sources,10,2016-17,2018-19 NK/2016-17/8341,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,993000,"Proposed construction of SWD at Kambar Street in Dn-128, U-29, Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8346,Roads,Completed,NK-KODAMBAKKAM,128,646000,"Relaying of B.T roads with bituminous concrete 30mm thick by mechanical paver finisher at Marriyamman koil street Reach-2 in Div-128,Unit-29,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/8347,Roads,Completed,NK-KODAMBAKKAM,128,464000,"Relaying of B.T roads with bituminous concrete 30mm thick by mechanical paver finisher at East vanniyar street Reach-2 in Div-128,Unit-29,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/8352,Road Cut,Completed,NK-KODAMBAKKAM,128,563000,"Restoration of Road cut made by TNEB at Kamarajar salai in Dn-128, U-29, Z-10",Deposit Works,10,2016-17,2017-18 NK/2016-17/8361,Roads,Completed,NK-KODAMBAKKAM,128,990000,"Re-laying the road with using DBM and BC by Mechanical Paver finisher at Alwarthirunagar Annex 1st main road in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8365,Roads,Completed,NK-KODAMBAKKAM,128,996000,"Re-laying the road with using DBM and BC by Mechanical Paver finisher at Vembuliamman koil street (Reach-2) in Dn-128, U-29, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/9313,Roads,Completed,NK-KODAMBAKKAM,128,998000,"SUPPLY, INSTALLATION, COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITRES / HOUR CAPACITY AT NEW BANGARU COLONY 2ND STREET IN DIV-128, U-29, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10463,Roads,Completed,NK-KODAMBAKKAM,129,882000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT AGASTHIYAR STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10531,Roads,Completed,NK-KODAMBAKKAM,129,354000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT PREM NAGAR IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10549,Roads,Completed,NK-KODAMBAKKAM,129,439000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT KAVERI STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10554,Roads,Completed,NK-KODAMBAKKAM,129,1048000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT DASARATHAN STREET,BASKAR COLONY IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10561,Roads,Completed,NK-KODAMBAKKAM,129,473000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT DEVARAJ NAGAR MAIN ROAD IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10568,Roads,Completed,NK-KODAMBAKKAM,129,836000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT KAMARAJAR SALAI (GANDHI NAGAR) IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10575,Roads,Completed,NK-KODAMBAKKAM,129,961000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT K.K.SALAI SALAI (GANDHI NAGAR) IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10580,Roads,Completed,NK-KODAMBAKKAM,129,762000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT PILLAYAR KOIL STREET (GANDHI NAGAR) IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10584,Roads,Completed,NK-KODAMBAKKAM,129,524000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT NEHRU NAGAR MAIN ROAD IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10589,Roads,Completed,NK-KODAMBAKKAM,129,873000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT SENTHIL AANDAVAR KOIL STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10592,Roads,Completed,NK-KODAMBAKKAM,129,292000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT NATARAJAN STREET GANDHI NAGAR IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10594,Roads,Completed,NK-KODAMBAKKAM,129,1224000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT SHANMUGA SUNDARAM STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10597,Roads,Completed,NK-KODAMBAKKAM,129,263000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT KULASEKARAN STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10600,Roads,Completed,NK-KODAMBAKKAM,129,609000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT SATHYAMOORTHY STREET (DEVARAJ NAGAR) IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10604,Roads,Completed,NK-KODAMBAKKAM,129,524000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT PONNIAMMAN KOIL STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10605,Roads,Completed,NK-KODAMBAKKAM,129,524000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT THIRUVENGADASAMY STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10607,Roads,Completed,NK-KODAMBAKKAM,129,524000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT KANNAMMAL STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10609,Roads,Completed,NK-KODAMBAKKAM,129,758000,"LAYING OF CEMENT CONCRETE ROAD USING M30 CONCRETE AT DASARADHAPURAM 6TH STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10614,Roads,Completed,NK-KODAMBAKKAM,129,775000,"LAYING OF CEMENT CONCRETE ROAD USING M30 CONCRETE AT DASARADHAPURAM 7th STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10615,Roads,Completed,NK-KODAMBAKKAM,129,775000,"LAYING OF CEMENT CONCRETE ROAD USING M30 CONCRETE AT DASARADHAPURAM 8th STREET IN DIV-129, UNIT-29, ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/11655,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,990000,Improvement to SWD at Abusali street (Annamalai Colony JN to Logaiha 4th street JN ) in Dn-129 U-29 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/11769,Playfields,Completed,NK-KODAMBAKKAM,129,990000,"Providing GYM Apparatus at Velayutham colony park & play field (under councilor fund) in div-129, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/11773,Playfields,Completed,NK-KODAMBAKKAM,129,650000,"Providing Bore well, Repair to Toilet and Compound wall painting in (under councilor fund) park at Velayutham colony Dn-129 U-29 Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/11786,Parks,Completed,NK-KODAMBAKKAM,129,990000,Providing SS Hand rail around walker path at Velayutham colony park (under councilor fund) in Dn-129 U-29 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/12075,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,830000,Improment of Storm water drain of size 1500x1500mm RCC Box type drain along Nehru Nagar Main Road from M.G.R. St in Dn 129 U-29 Zone 10.,Own Sources,10,2016-17,2018-19 NK/2016-17/13284,Roads,Completed,NK-KODAMBAKKAM,129,999000,"SUPPLY,INSTALLATION,COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITERS / HOUR CAPACITY AT THILLAIYADIVALLIAMMAI STREET IN DIV-129,U-29,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/13285,Roads,Completed,NK-KODAMBAKKAM,129,980000,Operation and Maintenance of High Quality Treated Drinking water Plant (RO/UV FILTRATION) OF 2000 Liter /hour Capacity for 1 year Period in Dn-129 U-29 Z-10,Own Sources,10,2016-17,2019-20 NK/2016-17/13656,Roads,Completed,NK-KODAMBAKKAM,129,444000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT KANNAIYA STREET IN DN-129,U-29,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/13657,Roads,Completed,NK-KODAMBAKKAM,129,888000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT MA.PO.C. STREET IN DN-129,U-29,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/13906,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,884000,"Desilting of Virugambakkam Canal from Mullai STreet to VOC Street including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13907,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,460000,"Desilting of Virugambakkam Canal from VOC Street to Mahalingam Street including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13908,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,972000,"Desilting of Virugambakkam Canal from Bharathiyar Street to Mullai street (Amma Unavagam) (Part) including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/15164,Parks,Completed,NK-KODAMBAKKAM,129,670000,"Annual Maintenance of Park at NSK Lane park and Muthukumarappa street Park in Saligramam DN.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for 2 years)",Own Sources,10,2016-17,2019-20 NK/2016-17/15166,Parks,Completed,NK-KODAMBAKKAM,129,620000,"Annual Maintenance of Park at Arcot road (Jain apartments) and Arcot road (Parameswaran vihar) in Saligramam DN.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for 2 years)",Own Sources,10,2016-17,2019-20 NK/2016-17/15167,Parks,Completed,NK-KODAMBAKKAM,129,750000,"Annual Maintenance of Park at Abusali road Park in Dn.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for Two year )",Own Sources,10,2016-17,2019-20 NK/2016-17/15168,Parks,Completed,NK-KODAMBAKKAM,129,665000,"Annual Maintenance of Park at Bhaskar Colony Park in Dn.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for 2 years )",Own Sources,10,2016-17,2019-20 NK/2016-17/15169,Parks,Completed,NK-KODAMBAKKAM,129,660000,"Annual Maintenance of Park at Pillayar koil street Park and Navallar main road Park in Dn.129,Unit-29,Zone-X.(Employed Qualified Diploma in Horticulture for Two year )",Own Sources,10,2016-17,2019-20 NK/2016-17/15512,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,972000,"Desilting of Virugambakkam Canal from Bharathiyar Street to Mullai street (Amma Unavagam) (Part - I) including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/16617,Roads,Completed,NK-KODAMBAKKAM,129,1270000,"IMPROVEMENT WORKS TO THE ARCOT ROAD PARK (APPASAMY BUILDERS), ABUSALI STREET PARK, BASKAR COLONY PARK, KAVERI RANGAN NAGAR PILLAYAR KOIL STREET PARK, NAVALAR HIGH ROAD PARK IN DN-129, U-29,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/18438,Playfields,Completed,NK-KODAMBAKKAM,129,700000,"Improvement to children play field at Thillaiyadi valliyamai street in div-129, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/18439,Buildings,Completed,NK-KODAMBAKKAM,129,920000,"Providing Amma Drinking water station at Thillaiyadivalliyammai street in div-129, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/18979,Roads,Completed,NK-KODAMBAKKAM,129,368000,"Relaying of B.T. Roads With Bituminous Concrete 30MM Thick by Mechanical Paver Finisher at vivekananthar street,Devaraj main road&Indra street in div-129, un-29,zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/19067,Buildings,Completed,NK-KODAMBAKKAM,129,28400,"Engaging Private Labours For House Keeping Work For The Period Of 3 Months At Urban Public Health Centre, Dhasatharapuram 8th Street, Saligramam, In Dn-129,Unit-29,Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19104,Roads,Completed,NK-KODAMBAKKAM,129,1580000,"Relaying bituminous concrete road at AVM street in divison -129, unit-29,zone-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19264,Buildings,Completed,NK-KODAMBAKKAM,129,27900,"Engaging Private Labours For Security Guards For The Period Of 3 Months At Urban Public Health Centre, Dhasatharapuram 8th Street, Saligramam, In Dn-129,Unit-29,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19374,Roads,Completed,NK-KODAMBAKKAM,129,565000,"Relaying of B.T. Roads With Bituminous Concrete 30MM Thick by Mechanical Paver Finisher at Venkateswara street and Harikrishna street (part) in div-129, un-29,zone-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19376,Roads,Completed,NK-KODAMBAKKAM,129,850000,"Relaying of B.T. Roads With Bituminous Concrete 30MM Thick by Mechanical Paver Finisher at L.v.prasad street in div-129, un-29,zone-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19377,Roads,Completed,NK-KODAMBAKKAM,129,765000,"Relaying of B.T. Roads With Bituminous Concrete 30MM Thick by Mechanical Paver Finisher at Kumaran Colony 2nd Street&Dr.Ambedhkar street in div-129, un-29,zone-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19378,Roads,Completed,NK-KODAMBAKKAM,129,912000,"Relaying of B.T. Roads With Bituminous Concrete 30MM Thick by Mechanical Paver Finisher at SSR pangajam Street in div-129, un-29,zone-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19379,Roads,Completed,NK-KODAMBAKKAM,129,708000,"Relaying of B.T. Roads With Bituminous Concrete 30MM Thick by Mechanical Paver Finisher at Balaji nagar 3rd street(part) , Sathyamoorthy street(part) in div-129, un-29,zone-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19821,Parks,Completed,NK-KODAMBAKKAM,129,980000,"Repairs to129 Division Office Building at Arunachalam Road in DN-129,Unit-29,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19822,Roads,Completed,NK-KODAMBAKKAM,129,950000,"Improvement work to 129 Division Office Building at Arunachalam Road in Dn-129,Unit-29,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19938,Footpath,Completed,NK-KODAMBAKKAM,129,840000,"Repair to footpath at Arunachalam road in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2019-20 NK/2016-17/4861,Roads,Completed,NK-KODAMBAKKAM,129,576000,"Construction of 'Pa' Shape for Compactor bin locations in Div-129, Unit-29, Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5591,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,940000,"Desilting of existing SW Drain at Arcot road,Arunachalam road, K.K.Road, Abusali road, SBI COlony 2nd st and SBI colony 3rd st in div-129, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5593,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,956000,"Desilting of existing Storm Water Drain at Kumaran colony 1st st, 2nd st,4th st, K.G.Nair st, Meenakshi st, Natarajan st,S.S.R Pankajam st, L.V.Prasad st, Kamarajar st(Ma Nagar), Kamarajar st (Gandhi nagar),Agasterior st, Anna street, Sathyamoorthy st(Gandhi nagar), Sathyamoorthy st ( Devaraj nagar), Prem nagar, Devaraj nagar main road,Sri ramalu st, Dasarathapuram 1st st and Logaiya colony 1st st in div-129, unit-29, zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/5594,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,953000,"Desilting of existing Storm Water Drain Logaiya colony 4th st, 5th st,2nd st, M.G.R st (K.R.Nagar), Durai arasan st, Kusaldoss st, Pillayar koil st, Indiragandhi st,Harikrishnan st, Bharathi st, Annamalai colony 2nd st, 3rd st,Thiruvengadasamy st, Vedavalli st, Muthukumarappa st, Rajesh avenue, M.P.avenue, Balaji nagar 1st street,3rd street, SBI Colony 1st st, Rajaji colony, Muthuramalingam street, Venkatesh nagar 1st st and Venkatesh nagar 2nd street in div-129, unit-29, zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/5595,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,590000,"Desilting of existing Storm Water Drain M.G.R salai, Nehru nagar main road, Thiruvalluvar street (Gandhi nagar), V.V.Koil st , vivekanandar street and Navaneethammal street in div-129, unit-29, zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/7795,Roads,Completed,NK-KODAMBAKKAM,129,990000,"Relaying of Road by using BC 30mm thick by Mechanical paver Finisher at Navaneedammal Street in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7797,Roads,Completed,NK-KODAMBAKKAM,129,960000,"Relaying of Road by using BC 30mm thick by Mechanical paver Finisher at MGR Street Part - II (From Pillaiyar Koil Street to Hari Krishnan Street) in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7800,Roads,Completed,NK-KODAMBAKKAM,129,950000,"Relaying of Road by using BC 30mm thick by Mechanical paver Finisher at MGR Street Part - I (From Abusali Street to Pillaiyar Koil Street) in Dn - 129, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/8508,Road Cut,Completed,NK-KODAMBAKKAM,129,964000,"Restoration of Road cut made by TNEB at MGR Street in Dn-129, U-29, Z-10",Deposit Works,10,2016-17,2016-17 NK/2016-17/8509,Road Cut,Completed,NK-KODAMBAKKAM,129,600000,"Restoration of Road cut made by TNEB at Bhaskar colony 2nd Street in Dn-129, U-29, Z-10",Deposit Works,10,2016-17,2017-18 NK/2016-17/8510,Road Cut,Completed,NK-KODAMBAKKAM,129,190000,"Restoration of Road cut made by TNEB at Abusali Street in Dn-129, U-29, Z-10",Deposit Works,10,2016-17,2017-18 L/2016-17/15516,Electrical,Completed,L-Electrical,130,745000,"Additional work of erection of 6 nos of 6 mtr GI Lamp post with LED Fitting at Jawaharlal Nehru salai junction of N.S.K.Salai, Vadapalani flyover, Vadapalani in Div-130, Zone-X.( By Deposit work MRL Vadapalani bridge)",Deposit Works,10,2016-17,2017-18 L/2016-17/15517,Electrical,Completed,L-Electrical,130,954000,"Supply, installation, aiming, testing and commissioning of 16 mtr high mast with LED fitting at Jawaharlal Nehru salai junction of N.S.K.Salai, Vadapalani flyover, Vadapalani in Div-130, Zone-X. ( By Deposit work MRL Vadapalani bridge)",Deposit Works,10,2016-17,2018-19 L/2016-17/5725,Electrical,Completed,L-Electrical,130,3500000,"Erection of 50 nos of 6 mtr GI Lamp post with LED Fitting at Jawaharlal Nehru salai junction of N.S.K.Salai, Vadapalani flyover, Vadapalani in Div-130, Zone-X.( By Deposit work MRL Vadapalani bridge)",Deposit Works,10,2016-17,2016-17 L/2016-17/8665,Electrical,Completed,L-Electrical,130,993000,"Provision of 55 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-130, 133, 134, 135, 136 &141, Zone-X.",Own Sources,10,2016-17,2016-17 NK/2016-17/10843,Roads,Completed,NK-KODAMBAKKAM,130,3364000,"Proposed Laying of Cement Concrete Road by using M30 Grade at Alagiri Nagar 4th Cross Street in Dn. 130, Unit-29, Zone- X",Own Sources,10,2016-17,2017-18 NK/2016-17/11179,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,628000,"IMPROVEMENTS TO STROM WATER DRAIN AT VARIOUS STREET(ANDAVAR NAGAR AND THIRU NAGAR) IN DIV-130,UNIT-29,ZONE-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/11210,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,628000,"IMPROVEMENTS TO STROM WATER DRAIN AT VARIOUS STREET IN DIV-130,UNIT-29,ZONE-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/11213,Buildings,Completed,NK-KODAMBAKKAM,130,238000,"Construction of Retaining Wall at Thiru Nagar 5th Steet in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/11215,Buildings,Completed,NK-KODAMBAKKAM,130,292000,"Supplying and Fixing of R.O Plant in Amma Unavagam at N.G.O Colony Main Road in Dn-130, Unit-29, Zone-X",Own Sources,10,2016-17,2018-19 NK/2016-17/11217,Buildings,Completed,NK-KODAMBAKKAM,130,905000,"Proposed Construction of Foundation to Amma Unavagam at N.G.O Colony Main Road in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/11324,Buildings,Completed,NK-KODAMBAKKAM,130,890000,"Providing Water Supply and Electrical arrangements at N.G.O Colony Main Road in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/1150,Roads,Completed,NK-KODAMBAKKAM,130,960000,"SUPPLY OF BOBCAT S 130 ( IMPORTED) FOR RENTAL BASIS IN DN 127,128,129 AND 130 , UNIT-29,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/11517,Buildings,Completed,NK-KODAMBAKKAM,130,453000,"Providing and Fixing of G.I Sheet Roofing for Amma Unavagam at N.G.O. Colony Main Road in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/12364,Buildings,Completed,NK-KODAMBAKKAM,130,319000,"Improvements to Amma Unavagam at N.G.O Colony Main Road in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/12376,Buildings,Completed,NK-KODAMBAKKAM,130,890000,"Providing and Fixing of Aluminium Composite Panel in Amma Unavagam at N.G.O Colony Main Road in Dn - 130, Unit - 29, ZOne - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13912,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,692000,"Desilting of Virugambakkam Canal from Mahalingam Street to Periyar pathai including removal of obstruction , hyacynth and other floating materials using poclain,special type of float platform in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/14073,Buildings,Completed,NK-KODAMBAKKAM,130,83000,"Repairs and Improvements Work to Public Convenience at Mosque Street in Dn - 130, Unit - 29, Zone - X",Own Sources,10,2016-17,2019-20 NK/2016-17/14236,Buildings,Completed,NK-KODAMBAKKAM,130,387000,"Improvements to Chennai Middle School at Amma Koil Street in Dn. 130, Unit - 29, Zone - X",Own Sources,10,2016-17,2019-20 NK/2016-17/16903,Buildings,Completed,NK-KODAMBAKKAM,130,56900,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK FOR THE PERIOD FROM 01.04.2017 TO 30.06.2017 AT CHENNAI MIDDLE SCHOOL, VADAPALANI, NO. 2, AMMAN KOIL STREET, VADAPALANI, CHENNAI IN DN-130,UNIT-29,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19062,Buildings,Completed,NK-KODAMBAKKAM,130,28400,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK FOR THE PERIOD FROM 01.04.2017 TO 30.06.2017 AT URBAN PUBLIC HEALTH CENTRE, NO. 1, RAJANGA MATHIYA VEETHI, VADAPALANI, CHENNAI IN DN-130,UNIT-29,ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19262,Buildings,Completed,NK-KODAMBAKKAM,130,27900,"ENGAGING SECURITY GUARDS (NIGHT SHIFT) FOR THE PERIOD FROM 01.04.2017 TO 30.06.2017 AT URBAN PUBLIC HEALTH CENTRE, NO. 1, RAJANGA MATHIYA VEETHI, VADAPALANI, CHENNAI IN DN-130,UNIT-29,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/4024,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,59500,"De-silting of Storm Water Drain at Nerkundram Pathai West in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4120,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,83000,"De-silting of Storm Water Drain at Thiru Nagar Main Road in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4279,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,40500,"De-silting of Storm Water Drain at Andavar Nagar 2nd Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4280,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,42000,"De-silting of Storm Water Drain at Andavar Nagar 3rd Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4281,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,42000,"De-silting of Storm Water Drain at Andavar Nagar 5th Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4287,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,41600,"De-silting of Storm Water Drain at Andavar Nagar 6th Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4289,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,58000,"De-silting of Storm Water Drain at Alagiri Nagar 3rd Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4292,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,41000,"De-Silting of Storm Water Drain at Amman Koil Street East in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4293,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,61800,"De-Silting of Storm Water Drain at Palani Andavar Koil Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4379,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,83000,"De-silting of Storm Water Drain at N.S.K Salai in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/4975,Roads,Completed,NK-KODAMBAKKAM,130,499000,"Restoration of Road Cut made by CMWSSB at Pillaiyar Koil Street (N.G.O Colony 1st Street) in Dn - 130, Unit - 29, Zone - X.",Deposit Works,10,2016-17,2017-18 NK/2016-17/4979,Roads,Completed,NK-KODAMBAKKAM,130,600000,"Restoration of Road Cut made by CMWSSB at N.G.O Colony Main Road in Dn - 130, Unit - 29, Zone - X.",Deposit Works,10,2016-17,2018-19 NK/2016-17/4983,Roads,Completed,NK-KODAMBAKKAM,130,607000,"Restoration of Road Cut made by CMWSSB at Dharansingh Colony 1st Street in Dn - 130, Unit - 29, Zone - X.",Deposit Works,10,2016-17,2017-18 NK/2016-17/5381,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,61300,"De-silting of Storm Water Drain at South Sivan Koil Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/5393,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,41900,"De-silting of Storm Water Drain at South Sivan Koil Street (West) (BRR) in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/5397,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,38300,"De-silting of Storm Water Drain at North Mada Street in Dn. 130, Unit-29, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/6787,Buildings,Completed,NK-KODAMBAKKAM,130,930000,"Removal of Debris at various streets and Roads and dumping the same at PDG/KDG in Dn127,128,129 and 130 Unit-31,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/7036,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,790000,"De- SIlting of Virugambakkam Canal using Excavator from Thiru Nagar Main Road to Pillaiyar Pathai in Dn - 130, Unit - 29, Zone - X",Own Sources,10,2016-17,2019-20 NK/2016-17/8604,Buildings,Completed,NK-KODAMBAKKAM,130,940000,"Proposed Construction of Retaining wall at Thiru Nagar Canal (From Thiru Nagar 5th Street to Thiru nagar 6th Street) in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/8731,Buildings,Completed,NK-KODAMBAKKAM,130,940000,"Proposed Construction of Retaining wall at Thiru Nagar Canal (From Thiru Nagar 6th Street to Virugambakkam Canal) in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/8888,Buildings,Completed,NK-KODAMBAKKAM,130,292000,"Supplying and Fixing of R.O Plant in Amma Unavagam at Nerkundrum Pathai in Dn-130, Unit-29, Zone-X",Own Sources,10,2016-17,2018-19 NK/2016-17/9081,Roads,Completed,NK-KODAMBAKKAM,130,950000,"Attending Patch Work by using RMC 40 at Various Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/9095,Roads,Completed,NK-KODAMBAKKAM,130,902000,"Proposed Laying of Cement Concrete Road by using RMC 40 Grade at Alagiri Nagar 1st Cross Street in Dn - 130, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/9465,Buildings,Completed,NK-KODAMBAKKAM,130,993000,"Removal of Debris at Important Roads and important streets and dumping the same in KDG from Div 127,128,129 and 130 in Unit -29, Zone10",Own Sources,10,2016-17,2019-20 L/2016-17/18132,Electrical,Completed,L-Electrical,131,1284900,"Estimate for street Lamp posts Various location in div 129,131,132,137,138,139 Damage due to Vardha Cyclone in Zone -10",Own Sources,10,2016-17,2017-18 L/2016-17/8793,Electrical,Completed,L-Electrical,131,993000,"Provision of 55 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-131, 138, 139, 140, & 142, Zone-X.",Own Sources,10,2016-17,2016-17 NK/2016-17/1033,Roads,Completed,NK-KODAMBAKKAM,131,882000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING PAVER FINISHER AT SATHYA GARDEN NEHRU STREET,AND VARIOUS STREET IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/10881,Roads,Completed,NK-KODAMBAKKAM,131,1242000,"LAYING CEMENT CONCRETE ROAD AT SIVALINGAPURAM NEW COLONY IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/11699,Roads,Completed,NK-KODAMBAKKAM,131,427000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING PAVER FINISHER AT SATHYA GARDEN KAKKANJI STREET,SATHYA GARDEN V.V.GIRI STREET, AND VARIOUS STREET IN DIV-131,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/11700,Roads,Completed,NK-KODAMBAKKAM,131,734000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING PAVER FINISHER AT SATHYA GARDEN KAMARAJAR STREET,AND VARIOUS STREET IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/11703,Roads,Completed,NK-KODAMBAKKAM,131,980000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT RANI ANNA NAGAR MAIN STREET (NEAR BLOCK NO :23) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/11704,Buildings,Completed,NK-KODAMBAKKAM,131,998000,"SUPPLY,INSTALLATION,COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITERS / HOUR CAPACITY AT RANI ANNA NAGAR MAIN STREET (NEAR BLOCK NO; 23) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/11705,Buildings,Completed,NK-KODAMBAKKAM,131,844000,PROPOSED CONSTRUCTION OF AMMA KUDINEER FLOORING WORK.AT RANI ANNA NAGAR MAIN STREET IN DIV 131 U 28 Z 10,Own Sources,10,2016-17,2018-19 NK/2016-17/11706,Buildings,Completed,NK-KODAMBAKKAM,131,990000,PROPOSED CONSTRUCTION OF AMMA KUDINEER SHED WORK AT RANI ANNA NAGAR MAIN STREET IN DIV 131 U 28 Z 10.,Own Sources,10,2016-17,2018-19 NK/2016-17/14055,Buildings,Completed,NK-KODAMBAKKAM,131,97000,"REPAIR AND IMPROVEMENTS WORKS FOR PUBLIC CONVEYANCE AT P.V.RAJAMANNAR SALAI IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/14577,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,331000,"CONSTRUCTION OF STROM WATER DRAIN ROAD CROSSING AT R.K.SHANMUGAM SALAI JUNCTION OF RAMASAMY SALAI (WITH HUME PIPE) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/15999,Parks,Completed,NK-KODAMBAKKAM,131,1130000,"REPAIR OF COMPOUND WALL AND OTHER IMPROVEMENT WORKS TO SIVAN PARK EFFECTED DUE TO VARDHA CYCLONE IN DIV-131,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16000,Playfields,Completed,NK-KODAMBAKKAM,131,53000,"REPAIR AND OTHER IMPROVEMENT WORKS TO 13th SECTOR PLAY FIELD EFFECTED DUE TO VARDHA CYCLONE IN DIV-131,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19304,Parks,Completed,NK-KODAMBAKKAM,131,290000,"MAINTENANCE OF SIVAN PARK AT P.T.RAJAN SALAI (3 MONTHS ONLY) IN DIV- 131,U-28,ZONE-X. (EMPLOYED QUALIFIED DIPLOMA HORTICULTURIST ONLY)",Own Sources,10,2016-17,2019-20 NK/2016-17/2741,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,995000,"DEMOLITION AND RECONSTRUCTION OF STORM WATER DRAIN AT R.K.SHANMUGAM SALAI,METRO WATER FILLING STATION 2nd GATE IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/3332,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,994000,"DEMOLITION AND RECONSTRUCTION OF STORM WATER DRAIN AT R.K.SHANMUGAM SALAI (FROM P.V.RAJAMANNAR SALAI) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/3333,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,993000,"DEMOLITION AND RECONSTRUCTION OF STORM WATER DRAIN AT R.K.SHANMUGAM SALAI (FROM RAMASAMY SALAI) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/3563,Roads,Completed,NK-KODAMBAKKAM,131,393000,"LAYING OF CEMENT CONCRETE ROAD AT SIVALINGAPURAM 1st STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/3740,Roads,Completed,NK-KODAMBAKKAM,131,882000,"ATTENDING PATCH WORK FOR FLOOD AFFECTED ROADS USING PAVER FINISHER AT SATHYA GARDEN GOBAL STREET,AND VARIOUS STREET IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/3841,Roads,Completed,NK-KODAMBAKKAM,131,624000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM M.G.R STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4843,Roads,Completed,NK-KODAMBAKKAM,131,996000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 3rd CROSS STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/4845,Roads,Completed,NK-KODAMBAKKAM,131,707000,"LAYING CEMENT CONCRETE ROAD AT VIJAYARAGAVAPURAM 4th CROSS STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4913,Roads,Completed,NK-KODAMBAKKAM,131,953000,"LAYING CEMENT CONCRETE ROAD AT KANNIGAPURAM 1st STREET (FROM P.V.RAJAMANNAR SALAI) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4914,Roads,Completed,NK-KODAMBAKKAM,131,953000,"LAYING CEMENT CONCRETE ROAD AT KANNIGAPURAM 1st STREET (FROM Dr: RAMASAMY SALAI) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/5010,Roads,Completed,NK-KODAMBAKKAM,131,517000,"LAYING CEMENT CONCRETE ROAD AT M.G.R NAGAR MOOVENDAR STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/5031,Roads,Completed,NK-KODAMBAKKAM,131,975000,"LAYING CEMENT CONCRETE ROAD AT M.G.R NAGAR ANBALAGAN STREET (PART FROM K.K.SALAI) IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/5033,Roads,Completed,NK-KODAMBAKKAM,131,786000,"LAYING CEMENT CONCRETE ROAD AT M.G.R NAGAR VALLALAR STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/5035,Roads,Completed,NK-KODAMBAKKAM,131,812000,"LAYING CEMENT CONCRETE ROAD AT M.G.R NAGAR BHARATHIDASAN STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/6019,Buildings,Completed,NK-KODAMBAKKAM,131,950000,"CONSTRUCTION OF ADDITIONAL AMMA UNAVAGAM DINNING HALL AT A.P.PATRO SALAI IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/6831,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,524000,"DESILTING OF EXISTING STORM WATER DRAIN AT ANNA MAIN ROAD, SATHYA GARDEN KAMARAJAR NAGAR 2nd STREET,SATHYA GARDEN KAMARAJAR NAGAR 3rd STREET, 2nd SECTOR 8th,9th,13th STREET,SOB SALAI,VIJAYARAGAVAPURAM 2nd STREET,BOBBILI RAJA SALAI,P.T.RAJAN SALAI, AND BHARANI COLONY, DR.BANUMATHI RAMAKRISHNAN STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/7291,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,996000,"DEMOLITION AND RECONSTRUCTION OF STORM WATER DRAIN AT R.K.SHANMUGAM SALAI,METRO WATER FILLING STATION 3rd GATE IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/7890,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,670000,"DESILTING OF EXISTING STORM WATER DRAIN AT LAKHSMANASAMY SALAI,5th SECTOR 22nd,25th,26th STREET AND VARIOUS STREET IN DIV- 131,U-28,Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/8658,Buildings,Completed,NK-KODAMBAKKAM,131,2498000,"CONSTRUCTION OF CAR PARKING FOR MULTIPURPOUS HALL AT 80 FEET ROAD IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/8746,Buildings,Completed,NK-KODAMBAKKAM,131,2465000,"PROPOSED CONSTRUCTION OF FIRST FLOOR FOR MULTIPURPOUS HALL AT 80 FEET ROAD IN DIV-131, U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/9179,Roads,Completed,NK-KODAMBAKKAM,131,2401000,"RELAYING THE BITUMINOUS CONCRETE ROAD AT A.P.PATRO SALAI IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/9183,Roads,Completed,NK-KODAMBAKKAM,131,5307000,"RELAYING THE BITUMINOUS CONCRETE ROAD AT R.K.SHANMUGAM SALAI SALAI IN DIV-131,U-28,Z-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/9315,Buildings,Completed,NK-KODAMBAKKAM,131,980000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT NEW BANGARU COLONY 2ND STREET IN DIV-131,U-28,Z-10",Own Sources,10,2016-17,2019-20 L/2016-17/13288,Electrical,Completed,L-Electrical,132,999600,"Replacement of 29 nos of KIOSK Pillar box Navalar Main Road, Arunachalam road and verieas places in div127,128,129,131,132,135,136,137,138,139,140 and 142 at zone 10 area",Own Sources,10,2016-17,2017-18 L/2016-17/8807,Electrical,Completed,L-Electrical,132,993000,"Supply and Fixing of 55nos of Automatic Timer unit in Div 127,128,129,132,137,Zone -X area",Own Sources,10,2016-17,2016-17 NK/2016-17/10327,Roads,Completed,NK-KODAMBAKKAM,132,5000000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 7TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/11170,Footpath,Completed,NK-KODAMBAKKAM,132,980000,"IMPROVEMENTS TO FOOTPATH AT 11TH AVENUE (FROM JUNCTION OF 1ST AVENUE TO JUNCTION OF 7TH AVENUE) IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/11171,Footpath,Completed,NK-KODAMBAKKAM,132,530000,"IMPROVEMENTS TO CENTRE MEDIAN AT (11TH AVENUE FROM JUNCTION OF 1ST AVENUE TO JUNCTION OF 7TH AVENUE) IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/12523,Roads,Completed,NK-KODAMBAKKAM,132,990000,"LAYING OF CEMENT CONCRETE ROAD AT PUDUR 9TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/12524,Roads,Completed,NK-KODAMBAKKAM,132,635000,"LAYING OF CEMENT CONCRETE ROAD AT ODDAGAPALAYAM 4TH & 5TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/13479,Buildings,Completed,NK-KODAMBAKKAM,132,980000,"PROPOSED CONSTRUCTION OF RATION SHOP AT 77TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/13484,Buildings,Completed,NK-KODAMBAKKAM,132,680000,"ELECTRICAL, WATER SUPPLY AND SANITARY ARRANGEMENTS FOR PROPOSED RATION SHOP AT 77TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/13487,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,980000,"IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS PLACES IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/13488,Buildings,Completed,NK-KODAMBAKKAM,132,660000,"ELECTRICAL ARRANGEMENTS AND OTHER IMPROVEMENTS AT AMMA UNAVAGAM AT 90TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/13790,Buildings,Completed,NK-KODAMBAKKAM,132,799000,"Proposed Construction of Foundation to Amma Kudineer at Ashok Nagar 90th Street, Kamarajar Salai in Dn - 132, Unit - 31, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13791,Buildings,Completed,NK-KODAMBAKKAM,132,332000,"Providing and Fixing of G.I Sheet Roofing for Amma Kudineer at Ashok Nagar 90th Street, Kamarajar Salai in Dn - 132, Unit - 31, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13792,Buildings,Completed,NK-KODAMBAKKAM,132,855000,"Providing and Fixing of Aluminium Composite Panel in Amma Kudineer at Ashok Nagar 90th Street, Kamarajar Salai in Dn - 132, Unit - 31, Zone - X",Own Sources,10,2016-17,2018-19 NK/2016-17/13797,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,825000,"Construction of Storm Water Drain at Vaigai Colony 1st Street in Dn. 132, Unit - 29, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13967,Buildings,Completed,NK-KODAMBAKKAM,132,440000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVINIENCE AT KAMARAJAR SALAI AND SAIDAPET ROAD IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/14813,Parks,Completed,NK-KODAMBAKKAM,132,785000,"ANNUAL MAINTAINANCE OF PARK AT 12TH AVENUE PARK IN DIV-132, U-31, Z-10 (Employed qualified Horticulturist for two years only)",Own Sources,10,2016-17,2019-20 NK/2016-17/15107,Parks,Completed,NK-KODAMBAKKAM,132,890000,"ANNUAL MAINTENANCE OF PARK AT 14TH SECTOR 102ND STREET PARK (FOR 2 YEAR) IN DIVISION-132,UNIT-31,ZONE-10(Employed qualified Horticulturist for two years only)",Own Sources,10,2016-17,2018-19 NK/2016-17/15460,Buildings,Completed,NK-KODAMBAKKAM,132,999000,"SUPPLY,INSTALLATION,COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITERS / HOUR CAPACITY AT ASHOK NAGAR 90TH STREET PLAYGROUND IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/15592,Buildings,Completed,NK-KODAMBAKKAM,132,980000,Operation and Maintenance of High Quality Treated Drinking water Plant (RO/UV FILTRATION) OF 2000 Liter /hour Capacity for 1 year Period in Dn-132 U-31 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/18568,Parks,Completed,NK-KODAMBAKKAM,132,980000,"ANNUAL MAINTENANCE OF 1ST AVENUE PARK AT ASHOK NAGAR IN DIV-132, U-31, Z-10 (QUALIFIED HORTICULTURIST ONLY)",Own Sources,10,2016-17,2019-20 NK/2016-17/19101,Buildings,Completed,NK-KODAMBAKKAM,132,28500,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK AT CORPORATION SCHOOLS & TOILETS (C.H.S. KANNIYAPPA NAGAR) IN DIV-132, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2016-17,2018-19 NK/2016-17/3595,Buildings,Completed,NK-KODAMBAKKAM,132,990000,"ADDITIONAL INCORPORATION OF LPG BURNER SYSTEM AND HUMAN BODY CHARGING TROLLEY IN THE GASIFIER CREMATORIUM AT AVM BURIAL GROUND IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/3597,Buildings,Completed,NK-KODAMBAKKAM,132,995000,"PROVIDING 100 FEET HEIGHT CHIMNEY, GAS CLEANING SYSTEM AND PIPE LINES FOR THE GASIFIER CREMATORIUM AT AVM BURIAL GROUND IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/3600,Buildings,Completed,NK-KODAMBAKKAM,132,995000,"CONSTRUCTION OF DOUBLE CHAMBER CREMATION CHAMBER FOR THE GASIFIER CREMATORIUM AT AVM BURIAL GROUND IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/3601,Buildings,Completed,NK-KODAMBAKKAM,132,950000,"PROVIDING GASIFIER UNIT, BURNER ASSEMBLY, WOOD CUTTING MACHINE, BLOWER, CONTROL PANEL AND PUMP FOR THE GASIFIER CREMATORIUM AT AVM BURIAL GROUND IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/3621,Buildings,Completed,NK-KODAMBAKKAM,132,660000,"PROVIDING DOOR WITH MOVING MECHANISMS, CAST IRON BODY RESISTING BRICKS AND WALL TILES FOR THE CREMATION CHAMBER FOR THE GASIFIER CREMATORIUM AT AVM BURIAL GROUND IN DIC-132, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/3818,Roads,Completed,NK-KODAMBAKKAM,132,990000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT 19TH AVENUE ( FROM CHAINAGE 0-120M) IN DN-132,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3819,Roads,Completed,NK-KODAMBAKKAM,132,990000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT 19TH AVENUE ( FROM CHAINAGE 120-240M) IN DN-132,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/4140,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,325000,"DESILTING OF SWD AT 4TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4339,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,153000,"DESILTING OF SWD AT 7TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4341,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,42000,"DESILTING OF SWD AT 10TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4343,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,260000,"DESILTING OF SWD AT KAMARAJ SALAI IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4346,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,77000,"DESILTING OF SWD AT P.T.RAJAN SALAI IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4349,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,77000,"DESILTING OF SWD AT 2ND AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4350,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,47500,"DESILTING OF SWD AT 8TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4351,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,42000,"DESILTING OF SWD AT 12TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4353,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,39000,"DESILTING OF SWD AT PUDUR 1ST STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4354,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,38500,"DESILTING OF SWD AT PUDUR 8TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4356,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,14500,"DESILTING OF SWD AT 46TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4360,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,13200,"DESILTING OF SWD AT SRI DEVI COLONY IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4361,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,13200,"DESILTING OF SWD AT SAMIYAR GARDEN STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4362,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,25500,"DESILTING OF SWD AT 54TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4363,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,10250,"DESILTING OF SWD AT 66TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4367,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,15500,"DESILTING OF SWD AT 67TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4416,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,123000,"DESILTING OF SWD AT 18TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4417,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,19000,"DESILTING OF SWD AT 65TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4591,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,148000,"DESILTING OF SWD AT 11TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4592,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,23000,"DESILTING OF SWD AT JS KANNAPPAR SALAI IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4597,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,7800,"DESILTING OF SWD AT 47TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4604,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,34000,"DESILTING OF SWD AT DR NATESAN SALAI IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4608,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,26000,"DESILTING OF SWD AT 41ST STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4615,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,60000,"DESILTING OF SWD AT 3RD AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4617,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,63500,"DESILTING OF SWD AT 6TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4621,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,35000,"DESILTING OF SWD AT 16TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4623,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,9000,"DESILTING OF SWD AT 42ND STREET IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4627,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,86500,"DESILTING OF SWD AT 9TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/9097,Roads,Completed,NK-KODAMBAKKAM,132,2100000,"RELAYING OF BT ROAD USING MECHANICAL PAVER AT 6TH AVENUE IN DIV-132, U-31, Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/11204,Buildings,Completed,NK-KODAMBAKKAM,133,750000,CONSTRUCTION OF KITCHEN SHED TO CPS AT MULLAI NAGAR IN DN 133 UNIT 31 ZONE 10 ( WARD COUNCILAR SCHEME ),Own Sources,10,2016-17,2016-17 NK/2016-17/11206,Buildings,Completed,NK-KODAMBAKKAM,133,464000,IMPROVEMENTS TO KITCHEN SHED IN CPS (PULIYUR ) AT N.S.K SALAI IN DN 133 UNIT 31 ZONE 10 (WARD COUNCILAR SCHEME ),Own Sources,10,2016-17,2016-17 NK/2016-17/13969,Buildings,Completed,NK-KODAMBAKKAM,133,305000,"REPAIR AND IMPROVEMENTS TO PUBLIC CONVINIENCE AT 61ST STREET, ASHOK NAGAR, PALAYAKKAARAN STREET AND N.S.K.SALAI IN DIV-133, U-31, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/14611,Buildings,Completed,NK-KODAMBAKKAM,133,83000,"REPAIRS AND MAINTAINANCE TO THE CPS MULLAI NAGAR SCHOOL AT 15TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/14612,Buildings,Completed,NK-KODAMBAKKAM,133,780000,"REPAIRS AND MAINTAINANCE TO THE CHSS PULIYUR SCHOOL AT N.S.K SALAI IN DIV-133, U-31, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16090,Footpath,Completed,NK-KODAMBAKKAM,133,375000,"FORMING FOOTPATH FOR REPAIRS AT FOOTPATH DURING VARDHA CYCLONE AT VARIOUS LOCATIONS IN DIV-133, U-31, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/1855,Roads,Completed,NK-KODAMBAKKAM,133,960000,"SUPPLY OF BOBCAT S 130 (IMPORTED) FOR RENTAL BASIS IN DN 132,133,134 AND 135 ,UNIT-31,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/19103,Buildings,Completed,NK-KODAMBAKKAM,133,28500,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK AT CORPORATION SCHOOLS & TOILETS (C.P.S. MULLAI NAGAR) IN DN-,133,U-31, Z-10. (FOR 3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/19152,Buildings,Completed,NK-KODAMBAKKAM,133,27500,"PROVIDING SECURITY ARRANGEMENTS FOR C.H.S..S. PULIYUR SCHOOL IN DIVISION-133,UNIT-31,ZONE-10.(3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/19160,Buildings,Completed,NK-KODAMBAKKAM,133,28500,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (C.H.S.S. PULIYUR) IN DN-,133,U-31, Z-10. (FOR 3 MONTHS)",Own Sources,10,2016-17,2018-19 NK/2016-17/3831,Roads,Completed,NK-KODAMBAKKAM,133,988000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT VOC 1ST CROSS, 2ND CROSS , 3RD CROSS STREET AND VOC 2ND MAIN ROAD IN DN-133,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3847,Roads,Completed,NK-KODAMBAKKAM,133,372000,"RESTORATION OF ROAD CUT MADE BY C. M. W. S. S. B., AT MUTHALAMMAN KOIL STREET IN DIVISION-133, UNIT-31, ZONE-10.",Deposit Works,10,2016-17,2016-17 NK/2016-17/4030,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47900,"Desilting of existing SW Drain at Brindavan Extn 1st cross street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/4041,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,52800,"Desilting of existing SW Drain at 21st avenue in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/4043,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,95700,"Desilting of existing SW Drain at Duraisamy road in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/4199,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,97000,"Desilting of existing SW Drain at NSK salai in Div-133, Unit-31, Zone-X",Own Sources,10,2016-17,2019-20 NK/2016-17/6012,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,878000,"REPAIR AND IMPROVEMENT WORKS TO THE EXISTING CHENNAI PRIMARY SCHOOL AND CHENNAI HIGH SCHOOL AT N.S.K.SALAI IN DN-133, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/6867,Roads,Completed,NK-KODAMBAKKAM,133,640000,"RELAYING OF B.T. ROADS WITH BITUMINOUS CONCRETE 30MM THICK BY MECHANICAL PAVER FINISHER AT PAPPATHI AMMAL STREET IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/6868,Roads,Completed,NK-KODAMBAKKAM,133,540000,"RELAYING OF B.T. ROADS WITH BITUMINOUS CONCRETE 30MM THICK BY MECHANICAL PAVER FINISHER AT RAJAGOPAL STREET IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/6869,Roads,Completed,NK-KODAMBAKKAM,133,565000,"RELAYING OF B.T. ROADS WITH BITUMINOUS CONCRETE 30MM THICK BY MECHANICAL PAVER FINISHER AT BHARATHI STREET IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/6870,Roads,Completed,NK-KODAMBAKKAM,133,350000,"RELAYING OF B.T. ROADS WITH BITUMINOUS CONCRETE 30MM THICK BY MECHANICAL PAVER FINISHER AT ASHOK NAGAR 26TH STREET IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/7847,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,91100,"Desilting of existing SW Drain at Brindavan Street Extn., in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7848,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,97800,"Desilting of existing SW Drain at Raju street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7850,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,53400,"Desilting of existing SW Drain at VOC Main road in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7851,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,49000,"Desilting of existing SW Drain at Suburayan Nagar 5th Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7852,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,51000,"Desilting of existing SW Drain at Suburayan Nagar 8th Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7853,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,52000,"Desilting of existing SW Drain at Karnan Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7855,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,46800,"Desilting of existing SW Drain at Kannadasan Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7856,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47900,"Desilting of existing SW Drain at Vathiyar Thottam Main Road in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7857,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,46800,"Desilting of existing SW Drain at Vathiyar Thottam 1st street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7858,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,46800,"Desilting of existing SW Drain at Vathiyar Thottam 2nd street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7862,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47100,"Desilting of existing SW Drain at Rajagopalan street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7864,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,42900,"Desilting of existing SW Drain at Bharathi street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7866,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,44500,"Desilting of existing SW Drain at Iyappan Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7867,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,91600,"Desilting of existing SW Drain at Subramani Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7868,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,89900,"Desilting of existing SW Drain at 5th Avenue in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7869,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47200,"Desilting of existing SW Drain at 2nd Avenue in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7870,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,46800,"Desilting of existing SW Drain at Ashok Nagar 57th Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7871,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,48000,"Desilting of existing SW Drain at Ashok Nagar 61st Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7872,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,43600,"Desilting of existing SW Drain at 10th Avenue in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7873,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47600,"Desilting of existing SW Drain at Postal Colony 3rd Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7874,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,51600,"Desilting of existing SW Drain at Postal Colony 2nd Street & Kamatchipuram 2nd Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7875,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,51600,"Desilting of existing SW Drain atPostal Colony 1st Street & Kamatchipuram 1st Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7876,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,52000,"Desilting of existing SW Drain at Rukmani Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2019-20 NK/2016-17/7877,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,52000,"Desilting of existing SW Drain at Mahadevan Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7878,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,51400,"Desilting of existing SW Drain at Moorthy Street Extn., in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7879,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,50300,"Desilting of existing SW Drain at Balakrishnan Street Extn., in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7880,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,45600,"Desilting of existing SW Drain at Postal Colony 4th Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7881,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,45600,"Desilting of existing SW Drain at 49th Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7882,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47500,"Desilting of existing SW Drain at Ashok Nagar 19th Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7883,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47200,"Desilting of existing SW Drain at Ashok Nagar 23rd Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7884,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,49000,"Desilting of existing SW Drain at Ashok Nagar 24th Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7885,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,46000,"Desilting of existing SW Drain at Nakeeran Street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7886,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,47200,"Desilting of existing SW Drain at 12TH Avenue in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7887,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,71500,"Desilting of existing SW Drain at 11TH Avenue in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/7888,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,49000,"Desilting of existing SW Drain at Andiappan street in Div-133, Unit-31, Zone-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/9222,Roads,Completed,NK-KODAMBAKKAM,133,1500000,"RELAYING OF B.T. ROADS WITH BITUMINOUS CONCRETE 30MM THICK BY MECHANICAL PAVER FINISHER AT SUBRAMANI STREET IN DIVISION-133, UNIT-31, ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/9922,Buildings,Completed,NK-KODAMBAKKAM,133,970000,"CONSTRUCTION OF SUMP AND IMPROVEMENTS TO CPS AT MULLAI NAGAR IN DN 133 UNIT 31 ZONE 10 (WARD COUNCILAR SCHEME )",Own Sources,10,2016-17,2017-18 NK/2016-17/9946,Buildings,Completed,NK-KODAMBAKKAM,133,900000,IMPROVEMENTS TO GYM AT ASHOK NAGAR 60 ST STREET AND 17 TH STREET IN DN 133 UNIT 31 ZONE 10 (WARD COUNCILAR SCHEME ),Own Sources,10,2016-17,2016-17 BR/2016-17/6577,Roads,Completed,BR-Bus Route Roads,134,990000,Supplying and fixing of Front facia & Back drop in the stainless steel Bus shelter at various bus route roads in zone -10,Own Sources,10,2016-17,2018-19 BR/2016-17/9625,Roads,Completed,BR-Bus Route Roads,134,9800000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improivement work at visvanathapuram main road & united colony 1st main road Road -Div 134,,Zone-10.",Grants,10,2016-17,2017-18 L/2016-17/18254,Electrical,Completed,L-Electrical,134,542400,"Erection of 9 nos of 6 mtr GI Lamp post at Cenral Avenue road, Kodambakkam and damaged cable replacement at kamarajar colony, Dharan Singh colony and others loc Div-130 & 134, Zone-X",Own Sources,10,2016-17,2017-18 NK/2016-17/0658,Buildings,Completed,NK-KODAMBAKKAM,134,879000,"IMPROVEMENT WORKS TO THE TOILET BLOCK IN CHENNAI PRIMARY SCHOOL AND CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD AND IMPROVEMENTS TO ADDITIONAL SHED AT ZONAL OFFICE-10 IN DN-134, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/10705,Roads,Completed,NK-KODAMBAKKAM,134,663000,"RELAYING THE ROAD WITH BC 30 MM THICK BY PAVER FINISHER AT JEYABARADAM ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10710,Roads,Completed,NK-KODAMBAKKAM,134,210000,"RELAYING THE ROAD WITH BC 30 MM THICK BY PAVER FINISHER AT JEYABARADAM LANE IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10712,Roads,Completed,NK-KODAMBAKKAM,134,2070000,"RELAYING THE ROAD WITH BC 30 MM THICK BY PAVER FINISHER AT CHAKRAPANI STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/11353,Buildings,Completed,NK-KODAMBAKKAM,134,985000,"PROVIDING AMMA KUDINEER AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/11612,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,960000,CONSTRUCTION OF STORM WATER DRAIN AT UNITED INDIA COLONY 2 ND CROSS STREET (FROM U.I COLONY MAIN ROAD ) IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2016-17,2018-19 NK/2016-17/11613,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,962000,CONSTRUCTION OF STORM WATER DRAIN AT UNITED INDIA COLONY 2 ND CROSS STREET (FROM CIRCULAR ROAD ) IN DN 134 UNIT 31 ZONE 10,Own Sources,10,2016-17,2018-19 NK/2016-17/13037,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,999000,"SUPPLY,INSTALLATION,COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITERS / HOUR CAPACITY AT CORPORATION COLONY ROAD IN DIV-134, U-31, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/13070,Roads,Completed,NK-KODAMBAKKAM,134,980000,"Operation and Maintenance of High Quality Treated Drinking water Plant (RO/UV FILTRATION) OF 2000 Liter /hour Capacity for 1 year Period for Amma Kudineer at Corporation Colony Road in Dn-134,u-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/13998,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,534000,"DE-SILTING OF CROSS CULVERT NO.43 & 44 FROM RAILWAY BORDER ROAD TO MAMBALAM HIGH ROAD AND PROVIDING RAIN WATER COLLECTION CHAMBER WITH PVC PIPE AT RATHINAMMAL STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/13999,Buildings,Completed,NK-KODAMBAKKAM,134,255000,"IMPROVEMENTS TO THE EXISTING PUBLIC CONVENIENCE AT DR.GOPALAMENON ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/14008,Buildings,Completed,NK-KODAMBAKKAM,134,465000,"IMPROVEMENTS TO THE EXISTING PUBLIC CONVENIENCE AT RANGARAJAPURAM MAIN ROAD (JN.OF CORPORATION COLONY ROAD, SHERKAN THOTTAM, KAMARAJAR COLONY) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/14012,Buildings,Completed,NK-KODAMBAKKAM,134,350000,"IMPROVEMENTS TO THE EXISTING PUBLIC CONVENIENCE AT AKBARABAD 2ND STREET (NORTH & SOUTHERN SIDE) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/14816,Buildings,Completed,NK-KODAMBAKKAM,134,544000,"PROVIDING FLOORING AND WATER SUPPLY ARRANGEMENTS TO THE AMMA KUDINEER AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/16668,Parks,Completed,NK-KODAMBAKKAM,134,170000,"PROVIDING COMPOUND WALL FOR DAMGED PORTION AT KALAINGA PARK AND ANNA PARK IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16672,Footpath,Completed,NK-KODAMBAKKAM,134,1700000,"PROVIDING FOOTPATH FOR DAMAGED PORTION AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16677,Roads,Completed,NK-KODAMBAKKAM,134,1200000,"ATTENDING PATCH WORK FOR DAMGED PORTION AT NAGARJUNA NAGAR 1ST STREET AND RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/16680,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,750000,"IMPROVEMETS TO THE EXISTING STORM WATER DRAIN DAMAGED PORTION AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/1716,Electrical,Completed,NK-KODAMBAKKAM,134,996000,"Supply,Erection of one no of 62.5KVA Three phase DG Set at Rangarajapuram Subway Division 134, Zone 10",Own Sources,10,2016-17,2018-19 NK/2016-17/19070,Buildings,Completed,NK-KODAMBAKKAM,134,27900,"ENGAGING SECURITY GUARDS (FOR 3 MONTHS) FOR MATERNITY HOSPITAL AT N.S.K.SALAI IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19076,Buildings,Completed,NK-KODAMBAKKAM,134,28500,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (FOR 3 MONTHS) FOR CHS AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19088,Buildings,Completed,NK-KODAMBAKKAM,134,28500,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR CPS AT ESWARAN KOIL STREET (FOR 3 MONTHS) IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19144,Buildings,Completed,NK-KODAMBAKKAM,134,28400,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR CMS AT KAMARAJAR COLONY (FOR 3 MONTHS) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19150,Buildings,Completed,NK-KODAMBAKKAM,134,56900,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR MATERNITY HOSPITAL AT N.S.K. SALAI (FOR 3 MONTHS) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19300,Buildings,Completed,NK-KODAMBAKKAM,134,57000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR PUBLIC CONVENIENCE (FOR 3 MONTHS) AT KAMRAJAR SALAI, SAIDAPET ROAD, N.S.K.SALAI, PALAYAKARAN STREET, RANGARAJAPURAM MAIN ROAD (KAMARAJAR COLONY 1ST STREET, JN.OF CORPORATION COLONY ROAD, NEAR SHERKAN THOTTAM & JN.OF CORPORATION COLONY 1ST MAIN ROAD (60 HUTS) IN DN-132, 133, 134, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19301,Buildings,Completed,NK-KODAMBAKKAM,134,57000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR PUBLIC CONVENIENCE (FOR 3 MONTHS) AT 61ST STREET, DR.GOPALAMENON ROAD, AKBARABAD 2ND STREET (NORTH & SOUTH), MADLEY SUBWAY & DURAISAMY SUBWAY IN DN- 133, 134, 135, U-31,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/3490,Roads,Completed,NK-KODAMBAKKAM,134,743000,"ATTENDING PATCH WORK USING BC 40MM BY PAVER FINISHER AT U.I.COLONY OUTER CIRCULAR ROAD (FROM JN OF U.I.COLONY 2ND MAIN ROAD TO 6TH CROSS STREET) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3825,Roads,Completed,NK-KODAMBAKKAM,134,592000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT VISWANATHAPURAM 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3826,Roads,Completed,NK-KODAMBAKKAM,134,726000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT NAGARJUNA NAGAR 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3827,Roads,Completed,NK-KODAMBAKKAM,134,990000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT SUBRAMANIAN NAGAR MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3828,Roads,Completed,NK-KODAMBAKKAM,134,247000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT JANAKIAMMAL STREET IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/4014,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,930000,"REPAIR AND IMPROVEMENT WORKS TO THE EXISTING STORM WATER DRAIN AND FOOTPATH AT NSK SALAI IN DN-134, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4015,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,877000,"REPAIR AND IMPROVEMENT WORKS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DN-134, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4016,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,875000,"REPAIR AND IMPROVEMENT WORKS TO THE CHENNAI PRIMARY SCHOOL AND CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4018,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,19000,"DESILTING OF STORM WATER DRAIN AT NAGARJUNA NAGAR 2ND STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/4021,Buildings,Completed,NK-KODAMBAKKAM,134,966000,"CONSTRUCTION OF ADDITIONAL AMMA UNAVAGAM AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/4023,Roads,Completed,NK-KODAMBAKKAM,134,969000,"IMPROVEMENTS TO THE ROAD BERMS AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/4025,Buildings,Completed,NK-KODAMBAKKAM,134,874000,"ENGAGING TECHNICAL ASSISTANT (GRADE-I) FOR DIVISION -132,133,134 & 135,UNIT-31,ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/4026,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,998000,"PROVIDING JOINERIES, PAINTING , GRANITE AND SS TABLE TOP FOR COUNTERS, ELECTRICAL, PLUMBING ARRANGEMENTS AT ADDITIONAL AMMA UNAVAGAM AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/4323,Buildings,Completed,NK-KODAMBAKKAM,134,510000,"SUPPLYING AND FIXING R.O.PLANT TO CHENNAI MIDDLE SCHOOL AT KAMARAJAR COLONY IN DN-134,U-31,Z-10 (UNDER MLA FUND 2015-16)",MLACDS,10,2016-17,2018-19 NK/2016-17/4326,Buildings,Completed,NK-KODAMBAKKAM,134,333000,"Construction of Under Ground Sump and Providing Drinking Water Facility at Chennai High School at Rangarajapuram in Dn-134,U-31,Z-10 (Under MLA Fund 2015-16)",MLACDS,10,2016-17,2018-19 NK/2016-17/4614,Electrical,Completed,NK-KODAMBAKKAM,134,794000,Electrification and Supply and Installation of 7 no?s of Split AC for the EOC Vadapalani in Division 134 Zone-X,Own Sources,10,2016-17,2018-19 NK/2016-17/6107,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,981000,"IMPROVEMENTS TO THE EXISTING TOILET FACILITIES,COMPOUND WALL AND CLASS ROOMS TO CHENNAI HIGH SCHOOL & CHENNAI PRIMARY SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/6108,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,53500,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY PARK VIEW ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6109,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,32600,"DESILTING OF STORM WATER DRAIN AT WEST AVENUE IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6110,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,33400,"DESILTING OF STORM WATER DRAIN AT CENTRAL AVENUE IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6111,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,36900,"DESILTING OF STORM WATER DRAIN AT STATION VIEW ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6113,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,32600,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 2ND MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6115,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,91700,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 4TH MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6116,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,30900,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 1ST CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6117,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,31800,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 2ND CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6119,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,28600,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 3RD CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6120,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,62600,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 4TH CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6121,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,31800,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 5TH CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6122,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,30600,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY 6TH CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6123,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,65700,"DESILTING OF STORM WATER DRAIN AT U.I.COLONY CIRCULAR ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6124,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,36900,"DESILTING OF STORM WATER DRAIN AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6125,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,28600,"DESILTING OF STORM WATER DRAIN AT BUDHA STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6129,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,35300,"DESILTING OF STORM WATER DRAIN AT ASHOKA AVENUE IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6130,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,65500,"DESILTING OF STORM WATER DRAIN AT RAJARAM FILM DIRECTORS COLONY IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6131,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,32200,"DESILTING OF STORM WATER DRAIN AT ANNA MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6132,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,32100,"DESILTING OF STORM WATER DRAIN AT JEYABARADAM ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6133,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,15300,"DESILTING OF STORM WATER DRAIN AT JEYABARADAM LANE IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6134,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,67400,"DESILTING OF STORM WATER DRAIN AT VISWANATHAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6135,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,29800,"DESILTING OF STORM WATER DRAIN AT VISWANATHAPURAM 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6140,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,33000,"DESILTING OF STORM WATER DRAIN AT NAGARJUNA NAGAR 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6148,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,19600,"DESILTING OF STORM WATER DRAIN AT GUGAN STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6150,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,18200,"DESILTING OF STORM WATER DRAIN AT RATHNASABATHY STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6151,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,34800,"DESILTING OF STORM WATER DRAIN AT PASUMARTHY STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6152,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,31300,"DESILTING OF STORM WATER DRAIN AT MINI STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6153,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,17000,"DESILTING OF STORM WATER DRAIN AT TANK STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6154,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,31300,"DESILTING OF STORM WATER DRAIN AT NEW STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6156,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,205000,"DESILTING OF STORM WATER DRAIN AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6157,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,37300,"DESILTING OF STORM WATER DRAIN AT CORPORATION COLONY MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6158,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,85200,"DESILTING OF STORM WATER DRAIN AT DR.AMBEDKAR ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6162,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,63400,"DESILTING OF STORM WATER DRAIN AT PARANGUSAPURAM IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6164,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,33800,"DESILTING OF STORM WATER DRAIN AT DR.GOPALAMENON ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6167,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,90200,"DESILTING OF STORM WATER DRAIN AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6776,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,17000,"DESILTING OF STORM WATER DRAIN AT RANGARAJAPURAM 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6780,Buildings,Completed,NK-KODAMBAKKAM,134,930000,"Removal of Debris at various streets and Roads and dumping the same at PDG/KDG in Dn132,133,134 and 135 Unit-31,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8030,Buildings,Completed,NK-KODAMBAKKAM,134,830000,"ANNUAL MAINTENANCE OF KALAINGAR PARK AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10(EMPLOYED QUALIFIED HORTICULTURIST FOR TWO YEARS ONLY)",Own Sources,10,2016-17,2018-19 NK/2016-17/8163,Buildings,Completed,NK-KODAMBAKKAM,134,840000,"Improvements and Maintenance of Anna Park in Dn.134,Unit-31,Zone-10.(Employed qualified Horticulturist for two years only)",Own Sources,10,2016-17,2018-19 NK/2016-17/8279,Buildings,Completed,NK-KODAMBAKKAM,134,940000,"IMPROVEMENTS AND REPAIR WORKS TO FOOTPATH AT RAILWAY BORDER ROAD (EASTERN SIDE FROM FLYOVER TO KODAMBAKKAM BRIDGE) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8585,Parks,Completed,NK-KODAMBAKKAM,134,217000,"REPAIRING PLAY APPARATUS, PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AND FILLING THE PLAY AREA WITH RIVER SAND FOR KALAINGAR PARK AT CORPORATION COLONY ROAD AND ANNA PARK AT U.I.COLONY IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/9045,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,745000,"IMPROVEMENS TO THE EXISTING STORM WATER DRAIN AT RANGARAJAPURAM MAIN ROAD ( FROM JN.OF VISWANATHAPURAM MAIN ROAD TO 85.00M) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/9048,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,735000,"IMPROVEMENS TO THE EXISTING STORM WATER DRAIN AT RANGARAJAPURAM MAIN ROAD ( FROM CHAINAGE 85 TO 170.00M ) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/9049,Footpath,Completed,NK-KODAMBAKKAM,134,860000,"PROVIDING FOOTPATH AT NTR STREET AND THIRUVALLUVAR STREET (NORTHERN SIDE) IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/9062,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,674000,"CONSTRUCTION OF INSPECTION CHAMBER FOR STORM WATER DRAIN AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/10019,Roads,Completed,NK-KODAMBAKKAM,135,708000,"RELAYING OF B.T. ROADS WITH BITUMINOUS CONCRETE 30MM THICK BY MECHANICAL PAVER FINISHER AT SERVICE ROAD (BOTH SIDE) MADLEY SUBWAY IN DIVISION-135, UNIT-31, ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/11500,Buildings,Completed,NK-KODAMBAKKAM,135,730000,"PROVIDING BASIC AMENITIES AND SAFETY MEASURES TO AMMA KUDINEER AT BAKTHAVATCHALAM STREET IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/12340,Buildings,Completed,NK-KODAMBAKKAM,135,2025000,"Proposed Construction of Indoor Shuttle Court (Under MLA Scheme)(Part - II) at West Mambalam, Bakthavatchalam street in Dn - 135, Unit - 31, Zone - X.",MLACDS,10,2016-17,2017-18 NK/2016-17/12343,Buildings,Completed,NK-KODAMBAKKAM,135,2425000,"Providing Lighting Arrangements for Indoor Shuttle Court (Under MLA Scheme) at West Mambalam, Bakthavatchalam Street in Div - 135, Unit - 31, Zone - X.",MLACDS,10,2016-17,2017-18 NK/2016-17/15461,Buildings,Completed,NK-KODAMBAKKAM,135,999000,"SUPPLY,INSTALLATION,COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITERS / HOUR CAPACITY AT BAKTHAVACHALAM STREET PLAYGROUND IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/15596,Buildings,Completed,NK-KODAMBAKKAM,135,980000,Operation and Maintenance of High Quality Treated Drinking water Plant (RO/UV FILTRATION) OF 2000 Liter /hour Capacity for 1 year Period in Dn-135 U-31 Z-10,Own Sources,10,2016-17,2018-19 NK/2016-17/16103,Footpath,Completed,NK-KODAMBAKKAM,135,490000,"FORMING FOOTPATH FOR REPAIRS AT FOOTPATH DURING VARDHA CYCLONE AT VARIOUS LOCATIONS IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/1977,Footpath,Completed,NK-KODAMBAKKAM,135,874000,"REPAIR AND IMPROVEMENT WORKS TO THE EXISTING STORM WATER DRAIN AND FOOTPATH AT NSK SALAI IN DN-133, U-31, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/3829,Roads,Completed,NK-KODAMBAKKAM,135,300000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT KAMAKOTTI STREET IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/3830,Roads,Completed,NK-KODAMBAKKAM,135,350000,"RELAYING THE ROAD WITH BC 30MM THICK BY PAVER FINISHER AT RAJAJI STREET IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/4317,Roads,Completed,NK-KODAMBAKKAM,135,886000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE 40MM THICK USING PAVER FINISHER AT BARODA STREET EXTN., (UNDER MLA SCHEME) IN DIV 135,U-31,Z-10",MLACDS,10,2016-17,2018-19 NK/2016-17/4370,Buildings,Completed,NK-KODAMBAKKAM,135,740000,"PROPOSED CONSTRUCTION OF TOILET BLOCK AT CHENNAI PRIMARY SCHOOL EASWARAN KOIL STREET UNDER MLA FUND IN DN 135,UNIT 31,ZONE 10",MLACDS,10,2016-17,2019-20 NK/2016-17/6034,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,997000,"REPAIRS AND CHANGING THE DAMAGED ROOF FOR CHENNAI PRIMARY SCHOOL (SOUTHERN SIDE BUILDING) AT ESWARAN KOIL STREET IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/6036,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,998000,"IMPROVEMENTS TO THE EXISTING SCHOOL BUILDING (SOUTHERN SIDE) FOR CHENNAI PRIMARY SCHOOL AT ESWARAN KOIL STREET IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/6037,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,83800,"DESILTING OF STORM WATER DRAIN AT JUBILEE ROAD IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6038,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,83900,"DESILTING OF STORM WATER DRAIN AT POSTAL COLONY 3RD STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6039,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,107100,"DESILTING OF STORM WATER DRAIN AT BRINDHAVAN STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6040,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,135200,"DESILTING OF STORM WATER DRAIN AT THAMBIAH ROAD IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6042,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,103000,"DESILTING OF STORM WATER DRAIN AT THAMBIAH ROAD EXTN., IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6043,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,79700,"DESILTING OF STORM WATER DRAIN AT NARASIMMAN STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6045,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,73700,"DESILTING OF STORM WATER DRAIN AT MANICKAM STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6046,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,75100,"DESILTING OF STORM WATER DRAIN AT RAJAJI STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6047,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,83200,"DESILTING OF STORM WATER DRAIN AT POSTAL COLONY 1ST STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6048,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,79500,"DESILTING OF STORM WATER DRAIN AT POSTAL COLONY 2ND STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6052,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,80700,"DESILTING OF STORM WATER DRAIN AT GIRI STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6054,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,80000,"DESILTING OF STORM WATER DRAIN AT GANAPATHY STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6055,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,99700,"DESILTING OF STORM WATER DRAIN AT BABU RAJENDRA PRASAD 1ST STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6056,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,72600,"DESILTING OF STORM WATER DRAIN AT STATION ROAD IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6057,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,44400,"DESILTING OF STORM WATER DRAIN AT SUBBA STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6058,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,51300,"DESILTING OF STORM WATER DRAIN AT LAKSHMI STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6059,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,53000,"DESILTING OF STORM WATER DRAIN AT RAMAKRISHNAPURAM 2ND STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6060,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,71500,"DESILTING OF STORM WATER DRAIN AT RAMAKRISHNAPURAM 3RD STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6062,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,53500,"DESILTING OF STORM WATER DRAIN AT JAISHANKAR STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6063,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,54000,"DESILTING OF STORM WATER DRAIN AT THIRUVENGADAM STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6064,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,71400,"DESILTING OF STORM WATER DRAIN AT BAKTHAVACHALAM STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6065,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,27100,"DESILTING OF STORM WATER DRAIN AT SRINIVASA (P) STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6066,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,26200,"DESILTING OF STORM WATER DRAIN AT GOKULAM COLONY IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6067,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,53400,"DESILTING OF STORM WATER DRAIN AT VELU STREET IN DIV-135, U-31, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6730,Buildings,Completed,NK-KODAMBAKKAM,135,2184000,"Providing and Fixing of Flooring for Indoor Shuttle Court (Under MLA Scheme) in Dn - 135, Unit - 31, Zone - X.",MLACDS,10,2016-17,2017-18 NK/2016-17/6743,Buildings,Completed,NK-KODAMBAKKAM,135,2450000,"Proposed Construction of Indoor Shuttle Court (Under MLA Scheme)(Part - I) in Dn - 135, Unit - 31, Zone - X.",MLACDS,10,2016-17,2017-18 NK/2016-17/6744,Buildings,Completed,NK-KODAMBAKKAM,135,2400000,"Providing and Fixing of G.I Sheet Roofing for Indoor Shuttle Court and Electrical Work (Under MLA Scheme) in Dn - 135, Unit - 31, Zone - X.",MLACDS,10,2016-17,2017-18 NK/2016-17/8444,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,999000,"IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT THAMBAIAH ROAD (FROM BRINDAVAN STREET) IN DN-135,U-31,Z-10",Own Sources,10,2016-17,2018-19 BR/2016-17/15900,Roads,Completed,BR-Bus Route Roads,136,571000,"Providing Thermoplastic Paint marking at Theayagaraya Road (Smart City Pedestrian Plaza) in Dn-136, Zone-10",Own Sources,10,2016-17,2018-19 BR/2016-17/9624,Roads,Completed,BR-Bus Route Roads,136,2900000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at usman Road (service road) -Div 136,Zone-10.",Grants,10,2016-17,2017-18 BR/2016-17/9628,Roads,Completed,BR-Bus Route Roads,136,11183000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Bazzula Road -Div 136,Zone-10.",Grants,10,2016-17,2017-18 D/2016-17/3278,Storm Water Drain,Completed,D-Storm Water Drains,136,3030000,New Construction of storm water Drain of size 600X750 mm along Bazullah Road(Western side) From Rangarajapuram Fly over Earthern Wall side to North usman Road Junction Div-136 in Zone-X.,Own Sources,10,2016-17,2016-17 J/2016-17/6642,Subway,Completed,J-Bridges,136,2229000,Improvements to the existing Duraisamy Subway in Dn-136.zone-X.,Own Sources,10,2016-17,2017-18 NK/2016-17/1000,Buildings,Completed,NK-KODAMBAKKAM,136,213000,"IMPROVEMENTS TO UNIT OFFICE AT MASILAMANI STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2016-17,2019-20 NK/2016-17/1019,Roads,Completed,NK-KODAMBAKKAM,136,454000,"MAINTANENCE OF STROM WATER DRAIN AT GOVINDU STREET, RANGANATHAN STREET AND VARIOUS STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2016-17,2017-18 NK/2016-17/1021,Roads,Completed,NK-KODAMBAKKAM,136,424000,"MAINTANENCE OF BIN PLATFORM AT Dr.NAIR ROAD, THIYAGARAYAR ROAD AND VARIOUS STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2016-17,2017-18 NK/2016-17/11412,Buildings,Completed,NK-KODAMBAKKAM,136,980000,"Forming footpath in front of Sir Pitty Theyagarayar Kalaiarangam at Gopathy Narayana Road in Dn 136,Unit-30,Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/11414,Footpath,Completed,NK-KODAMBAKKAM,136,985000,"Forming footpath at Srinivasan Street and Gopalakrishnan Street Near Kalai arangam in Dn 136,Unit-30,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/14006,Buildings,Completed,NK-KODAMBAKKAM,136,395000,"MAINTENANCE OF PUBLIC CONVENIENCE AT KANNADASAN STREET, VENKATNARAYANA ROAD, NAGESWARA ROAD, ANANDAN STREET, JAWAHARLAL NEHRU STREET AND RAILWAY BORDER STREET IN DIV - 136, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2017-18 NK/2016-17/15257,Parks,Completed,NK-KODAMBAKKAM,136,935000,"ANNUAL MAINTENANCE TO NATESAN PARK AT VENKATNARAYANA ROAD IN DIV 136,U 30,Z 10(Employed qualified 2 years diploma horticulture only)",Own Sources,10,2016-17,2019-20 NK/2016-17/15258,Parks,Completed,NK-KODAMBAKKAM,136,960000,"ANNUAL MAINTENANCE TO PANAGAL PARK AT BASHYAM ROAD IN DIV 136,U 30, Z 10(Employed qualified horticulturist only)",Own Sources,10,2016-17,2019-20 NK/2016-17/15259,Parks,Completed,NK-KODAMBAKKAM,136,570000,"ANNUAL MAINTENANCE TO JEEVA PARK AT G.N.CHEETY ROAD IN DIV 136,U 30, Z 10(Employed qualified horticulturist only)",Own Sources,10,2016-17,2018-19 NK/2016-17/16647,Parks,Completed,NK-KODAMBAKKAM,136,1310000,"RECTIFICATION WORK FOR COMPOUND WALL AT PANAGAL PARK, NATESAN PARK AND JEEVA PARK IN DIVISION - 136, UNIT - 30, ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16663,Parks,Completed,NK-KODAMBAKKAM,136,820000,"RECTIFICATION WORK FOR FOOTPATH AT PANAGAL PARK, NATESAN PARK AND JEEVA PARK IN DIVISION - 136, UNIT - 30, ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16665,Parks,Completed,NK-KODAMBAKKAM,136,280000,"RECTIFICATION WORK FOR WATER SUPPLY ARRANGEMENT AT PANAGAL PARK, NATESAN PARK AND JEEVA PARK IN DIVISION - 136, UNIT - 30, ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16963,Buildings,Completed,NK-KODAMBAKKAM,136,208000,"Providing barricading arrangement around the dilapidated building at MLA office in div ? 136, unit -30, zone -10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19110,Buildings,Completed,NK-KODAMBAKKAM,136,49000,"PROVIDING HOUSE KEEPING ARRANGEMENT TO PITTY THIYAGARAYA HALL G.N.CHETTY ROAD IN DIVISION -136, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19114,Buildings,Completed,NK-KODAMBAKKAM,136,69000,"PROVIDING ELECTRICIAN AND PLUMBER ARRANGEMENT TO CORPORATION SHOPPING COMPLEX AT SIR THIYAGARAYA ROAD IN DIVISION -136, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19180,Buildings,Completed,NK-KODAMBAKKAM,136,1053000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL(BLOCK-1) AT MAMBALAM HIGH ROAD ( JUNCTION OF BAZZULLA ROAD) IN DIV - 136, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2018-19 NK/2016-17/19183,Buildings,Completed,NK-KODAMBAKKAM,136,1015000,"CONSTRUCTION OF MULTIPURPOSE HALL - 2 AT MAMBALAM HIGH ROAD ( JN OF MAHARAJA SANTHANAM SALAI) IN DIV - 136, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2018-19 NK/2016-17/19297,Parks,Completed,P-Parks and Playfields,136,12607000,"IMPROVEMENTS TO VENKATNARAYANA ROAD PLAY GROUND AT T.NAGAR IN DIV - 136, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19916,Buildings,Completed,NK-KODAMBAKKAM,136,98000,"LEVELING OF PROPOSED MULTI LEVEL CAR PARKING SITE AREA ( CENTRE PORTION ) AT THIYAGARAYA ROAD ( JN OF THANIKACHALAM ROAD ) IN DIVISION - 136,U-30,Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19917,Buildings,Completed,NK-KODAMBAKKAM,136,96000,"LEVELING OF PROPOSED MULTI LEVEL CAR PARKING SITE AREA ( NORTH SIDE ) AT THIYAGARAYA ROAD ( JN OF THANIKACHALAM ROAD ) IN DIVISION - 136,U-30,Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19918,Buildings,Completed,NK-KODAMBAKKAM,136,99000,"LEVELING OF PROPOSED MULTI LEVEL CAR PARKING SITE AREA ( SOUTH SIDE ) AT THIYAGARAYA ROAD ( JN OF THANIKACHALAM ROAD ) IN DIVISION - 136,U-30,Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/4071,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,826000,"DESILTING OF STROM WATER DRAIN AT MOTHILAL STREET, MAHALAKSHMI STREET AND VARIOUS STREET IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2019-20 NK/2016-17/10269,Roads,Completed,NK-KODAMBAKKAM,137,703000,"RELAYING THE ROAD WITH PAVER FINISHER AT NAGATHAMMAN KOIL STREET DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10278,Roads,Completed,NK-KODAMBAKKAM,137,1469000,"RELAYING THE ROAD WITH PAVER FINISHED AT JAYABALAJI NAGAR 1ST,2ND,3RD STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10280,Roads,Completed,NK-KODAMBAKKAM,137,410000,"RELAYING THE ROAD WITH PAVER FINISHER AT PERIYAR STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10282,Roads,Completed,NK-KODAMBAKKAM,137,804000,"RELAYING THE ROAD WITH PAVER FINISHER AT DURGAIAMMAN KOIL STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10348,Roads,Completed,NK-KODAMBAKKAM,137,350000,"RELAYING THE ROAD WITH PAVER FINISHER AT 11TH SECTOR 70TH STREET DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10408,Roads,Completed,NK-KODAMBAKKAM,137,1035000,"LAYING THE CEMENT CONCRETE ROAD AT C.K.NAGAR IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10415,Roads,Completed,NK-KODAMBAKKAM,137,1104000,"LAYING THE CEMENT CONCRETE ROAD AT KANNAGI STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10440,Roads,Completed,NK-KODAMBAKKAM,137,690000,"LAYING THE CEMENT CONCRETE ROAD AT NAGATHAMAN KOIL CROSS STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10446,Roads,Completed,NK-KODAMBAKKAM,137,422000,"LAYING THE CEMENT CONCRETE ROAD AT INDRA STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10452,Roads,Completed,NK-KODAMBAKKAM,137,483000,"LAYING THE CEMENT CONCRETE ROAD AT AVADIAMAN STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10457,Roads,Completed,NK-KODAMBAKKAM,137,807000,"LAYING THE CEMENT CONCRETE ROAD AT KALAINGAR KARUNANITHIN STREET IN DIVISINON-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10458,Roads,Completed,NK-KODAMBAKKAM,137,207000,"LAYING THE CEMENT CONCRETE ROAD AT BUDDAR STREET IN DIVISION-137,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/11678,Roads,Completed,NK-KODAMBAKKAM,137,979000,"PROVIDING AND LAYING THERMOPLAST PAINT AND REFLECTOR STRUDS AT JAYABALAJI NAGAR MAIN ROAD, JAYABALAJI NAHGAR 2 nd CROSS STREET AND VARIOUS STREET IN DIVISION -137, UNIT - 28, ZONE -10.",Own Sources,10,2016-17,2016-17 NK/2016-17/12823,Buildings,Completed,NK-KODAMBAKKAM,137,322800,"IMPROVEMENT TO THE ANGANWADI CENTRE NOS(33603080424,80426,80427,80422,80420, 80415,80428, 80429)AT VARIOUS STREET IN DIVISION-137, UNIT-28,ZONE-10",Deposit Works,10,2016-17,2019-20 NK/2016-17/14020,Buildings,Completed,NK-KODAMBAKKAM,137,131000,"IMPROVEMENTS TO PUBLIC CONVENIANCE AT ERIKKARAI STREET, ANNA MAIN ROAD, ARCOT ROAD & RAJA MANNAR SALAI IN DN 137 UNIT 28 ZONE 10",Own Sources,10,2016-17,2019-20 NK/2016-17/14301,Buildings,Completed,NK-KODAMBAKKAM,137,296000,"IMPROVEMENT WORKS TO CHSS AT ERIKKARI STREET IN DIV-137, U-28, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/14304,Buildings,Completed,NK-KODAMBAKKAM,137,511000,"IMPROVEMENT WORKS TO CMS AT KAMARAJAR STREET IN DIV-137, U-28, Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/15178,Parks,Completed,NK-KODAMBAKKAM,137,950000,"ANNUAL MAINTENANCE OF PARK AT ERIKARAI STREET,NESAPAKKAM IN DIVISION 137,UNIT-28,ZONE-X.( By qualified horticulturist only)",Own Sources,10,2016-17,2018-19 NK/2016-17/15179,Parks,Completed,NK-KODAMBAKKAM,137,733000,"ANNUAL MAINTENANCE OF PARK AT 12 Sector (for two years)IN DIVISION 137,UNIT-28,ZONE-X.( By qualified horticulturist only)",Own Sources,10,2016-17,2018-19 NK/2016-17/16227,Parks,Completed,NK-KODAMBAKKAM,137,265000,"REPAIRS AND MAINTENANCE WORKS TO PARK AT ERIKARAI STREET,11TH SECTOR PARK, 12TH SECTOR PARK, 4TH SECTOR PARK IN DIVISION-137,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16916,Buildings,Completed,NK-KODAMBAKKAM,137,1330000,"Dismantling and Reconstruction of SWD at Munusamy Salai and Ponambalam Salai damaged due to Vardha Cyclone in Division-137, Unit-28, Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19040,Buildings,Completed,NK-KODAMBAKKAM,137,49000,"PROVIDING SECURITY ARRANGEMENTS CHSS AT ERIKKARAI STREET IN DIV-137,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/19041,Parks,Completed,NK-KODAMBAKKAM,137,83000,"Outsourcing Sweepers to CHSS at Erikkarai Street in DIV-137,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/19131,Parks,Completed,NK-KODAMBAKKAM,137,49000,"PROVIDING SECURITY ARRANGEMENT(DAY AND NIGHT) FOR CMS AT KAMARAJ STREET IN DIV-137,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/3980,Buildings,Completed,NK-KODAMBAKKAM,137,692000,"OUT SOURCING OF PRIVATE WORKERS FOR CLEANING SCHOOLS AT CMS KAMARAJAR SALAI MGR NAGAR AND CMS SANGARALINGANAR STREET IN DIV-137,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/5945,Buildings,Completed,NK-KODAMBAKKAM,137,488368,"PROPOSED FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEET IN VARIOUS STREET IN DN -137,UN-28, Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6196,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,632000,"DISILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN VANNIYAR STREET,MUNUSAMY STREET,ANNA MAIN ROAD,RAMASAMY SALAI,LAKSHMANASAMY SALAI,AND ARCOT ROAD IN DN 137 UNIT 28 ZONE 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/6197,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,651000,"DISILTING OF STORM WATER DRAIN AT 4TH SECTOR 14TH STREET,4TH SECTOR 20TH STREET,5TH SECTOR 21ST STREET,84TH SECTOR 42ND STREET,8TH SECTOR 43RD STREET,8TH SECTOR 44TH STREET,KHAN NAGAR MAIN ROAD ,KRISHNAN 1,2,AND 3RD STREET,SURENDER STREET,MYLAI SIVAMUTHU STREET,ANGALAPARAMESWARI MAIN ROAD AND ANGALAPARAMESWARI 1,2,3,AND 4TH STREET AND THAMARAI VINAYAGAR KOIL STREET IN DN 137 UNIT 28 ZONE 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/6198,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,651000,DISILTING OF STORM WATER DRAIN AT RAJAMANAR SALAI (SOUTH) IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2016-17,2018-19 NK/2016-17/6204,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,651000,DESILTING OF STORM DRAIN AT RAJAMANOR SALAI (NORTH) IN DN 137 UNIT 28 ZONE 10.,Own Sources,10,2016-17,2018-19 NK/2016-17/6584,Electrical,Completed,NK-KODAMBAKKAM,137,749600,"Supply and Erection of 9nos of 6mtr GI lamp post and 19nos of 2mtr GI Lamp post in the 8th sector park in Div 137,Zone -X area",Own Sources,10,2016-17,2018-19 NK/2016-17/6608,Buildings,Completed,NK-KODAMBAKKAM,137,595000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC TOILET CLEANING AT ARCOT STREET,RAJAMANNAR SALAI AND 11TH SECTOR IN DN 137,UNIT-28,ZONE10",Own Sources,10,2016-17,2018-19 NK/2016-17/6609,Buildings,Completed,NK-KODAMBAKKAM,137,417000,"OUT SOURCING OF PRIVATE WORKERS FOR PUBLIC TOILET CLEANING AT ANNA MAIN ROAD AND ERIKKARAI STREET IN DN 137,UNIT-28,ZONE10",Own Sources,10,2016-17,2018-19 NK/2016-17/6835,Buildings,Completed,NK-KODAMBAKKAM,137,930000,"Removal of Debris in various Roads and Streets dumping the same in PDG/KDG in Div 131 and 137,Unit-28, Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6944,Buildings,Completed,NK-KODAMBAKKAM,137,850000,"Forming Footpath at Moogambigai Street on North - From Door No.22 to Chainage 120mtr in Dn 137, unit-28, Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/6945,Footpath,Completed,NK-KODAMBAKKAM,137,843000,"Forming Footpath at Moogambigai Street on North - From Chainage 120mtr to Jn of Dr Kanu Nagar Main Road in Dn 137, unit-28, Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/6946,Footpath,Completed,NK-KODAMBAKKAM,137,837000,"Forming Footpath at Moogambigai Street on South from Door No 13/16 (towards East) to Chainage 118mtr in Dn 137, unit-28, Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/6947,Footpath,Completed,NK-KODAMBAKKAM,137,827000,"Forming Footpath at Moogambigai Street on South from Jn of Dr.Kanu Nagar Main Road to towards West in Dn 137, unit-28, Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/8115,Roads,Completed,NK-KODAMBAKKAM,137,560000,"RELAYING THE ROAD WITH PAVER FINISHER AT JAYALALITHA NAGAR 1 TO 5 STREET IN DN-137, U-28, Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/8356,Parks,Completed,NK-KODAMBAKKAM,137,888000,"ANNUAL MAINTENANCE OF PARK AT 11TH SECTOR (TWO YEARS), K.K.NAGAR IN DIV 137,UNIT-28,ZONE 10",Own Sources,10,2016-17,2019-20 NK/2016-17/8357,Parks,Completed,NK-KODAMBAKKAM,137,860000,"ANNUAL MAINTENANCE OF PARK AT 4TH SECTOR, K.K.NAGAR IN DIV 137,UNIT-28,ZONE 10",Own Sources,10,2016-17,2018-19 NK/2016-17/9817,Buildings,Completed,NK-KODAMBAKKAM,137,825000,"Laying Cement Concrete Road at Annai Indira Nagar in Dn 137,Unit-28,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/10416,Buildings,Completed,NK-KODAMBAKKAM,138,998000,"SUPPLY,INSTALLATION,TESTING AND COMMISSIONING OF 2000 LPH REVERSE OSMOSIS SYSTEM WITH RFID SMART CARD FOR WATER DISPENSING AT ANNA MAIN ROAD 60 FEET ROAD JUNCTION (AMMA KUDINEER) IN DIV-138,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/10427,Roads,Completed,NK-KODAMBAKKAM,138,980000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT RO/UV FILTERATION OF 2000 LPH FOR 1 YEAR AT ANNA MAIN ROAD 60 FEET ROAD JUNCTION (AMMA KUDINEER) IN DIV-138,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/10441,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,146000,"SUPPLYING AND FIXING OF MAN HOLE DOORS @ PILLAIYAR KOIL STREET,BHARATHIDSAN COLONY ,ANNA MAIN ROAD ,KK SALAI AND ASHOK PILLER ROAD IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/10444,Buildings,Completed,NK-KODAMBAKKAM,138,479000,"CONSTRUCTION OF BARRICADE BRICK WORK WITH GRILL IN ROAD SIDE TRANSFORM AREAS @ ANNA MAIN ROAD , 60 FEET ROAD , BHARATHIDASAN COLONY AND PILLAIYAR KOIL STREET IN DIVISION-138, UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/10445,Roads,Completed,NK-KODAMBAKKAM,138,851945,"LAYING OF BITUMINOUS CONCRETE ROAD USING PAVER FINISHER AT VASUDEVAN NAGAR RIVER SIDE ROAD IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/10447,Roads,Completed,NK-KODAMBAKKAM,138,586864,"LAYING OF BITUMINOUS CONCRETE ROAD USING PAVER FINISHER AT KASI ESTATE 2ND STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/10448,Roads,Completed,NK-KODAMBAKKAM,138,490471,"LAYING OF BITUMINOUS CONCRETE ROAD USING PAVER FINISHER AT KASI ESTATE 3RD STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/10451,Roads,Completed,NK-KODAMBAKKAM,138,864702,"LAYING OF BITUMINOUS CONCRETE ROAD USING PAVER FINISHER AT THIRU NAGAR RIVER SIDE ROAD IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/10928,Roads,Completed,NK-KODAMBAKKAM,138,1077929,"LAYING OF CEMENT CONCRETE ROAD AT SANJAI GANDHI STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/10929,Roads,Completed,NK-KODAMBAKKAM,138,391180,"LAYING OF CEMENT CONCRETE ROAD AT V.N.JANAKI STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10930,Roads,Completed,NK-KODAMBAKKAM,138,689692,"LAYING OF CEMENT CONCRETE ROAD AT PULITHEVAN STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10931,Roads,Completed,NK-KODAMBAKKAM,138,344592,"LAYING OF CEMENT CONCRETE ROAD AT PULITHEVAN 1ST CROSS STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10932,Roads,Completed,NK-KODAMBAKKAM,138,452473,"LAYING OF CEMENT CONCRETE ROAD AT PULITHEVAN 2ND CROSS STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10935,Roads,Completed,NK-KODAMBAKKAM,138,2803428,"LAYING OF CEMENT CONCRETE ROAD AT GOVINDASAMY STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2019-20 NK/2016-17/10937,Roads,Completed,NK-KODAMBAKKAM,138,426589,"LAYING OF CEMENT CONCRETE ROAD AT VN JANAKI 1ST STREET STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10939,Roads,Completed,NK-KODAMBAKKAM,138,289376,"LAYING OF CEMENT CONCRETE ROAD AT VN JANAKI 2ND STREET STREET,MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/12800,Buildings,Completed,NK-KODAMBAKKAM,138,1874000,"CONSTRUCTION OF COMMUNITY TOILET AT DR.AMBEDKHAR COLONY NEAR TAHSILDHAR OFFICE IN DIVISION-138, UNIT-28,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/14051,Buildings,Completed,NK-KODAMBAKKAM,138,272000,"IMPROVEMENTS AND REPAIRS OF PC AT PACHYAPPEN STREET,GOVINDASAMY STREET,60FEET ROAD AND ASHOK PILLER ROAD IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/14296,Buildings,Completed,NK-KODAMBAKKAM,138,84000,"IMPROVEMENT OF CHSS AT GOVINDASAMY STREET, MGR NAGAR IN DIV-138,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/14300,Buildings,Completed,NK-KODAMBAKKAM,138,61000,"IMPROVEMENT OF CPS AT GOVINDASAMY STREET, MGR NAGAR IN DIV-138,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/1571,Buildings,Completed,NK-KODAMBAKKAM,138,910000,"ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE TANGEDCO/TNEB AT AYYAVOO STREET AND VARIOUS STREETS IN DIVISION-138,UNIT-28,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/1572,Buildings,Completed,NK-KODAMBAKKAM,138,723000,"ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE TANGEDCO/TNEB AT THIRU NAGAR AND VARIOUS STREETS IN DIVISION-138,UNIT-28,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/1573,Buildings,Completed,NK-KODAMBAKKAM,138,387000,"ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE TANGEDCO/TNEB AT VASUDEVAN NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/16467,Buildings,Completed,NK-KODAMBAKKAM,138,150000,"CONSTRUCTION OF COMPOUND WALL AND OTHER IMPROVEMENT WORK FOR VARDHA CYCLONE AFFECTED PARK AT BHARATHIDASAN COLONY 5TH STREE IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16476,Buildings,Completed,NK-KODAMBAKKAM,138,240000,"CONSTRUCTION OF COMPOUND WALL AND OTHER IMPROVEMENT WORK AT NEHRU AVENUE PLAY GROUND IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16481,Buildings,Completed,NK-KODAMBAKKAM,138,27500,"CONSTRUCTION OF DAMAGED COMPOUND WALL AND OTHER IMPROVEMENT WORK AT GANAOLI STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19052,Parks,Completed,NK-KODAMBAKKAM,138,62000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CHSS GOVINDASAMY STREET , MGR NAGAR,(3 MONTHS PERIOD ONLY) IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19053,Parks,Completed,NK-KODAMBAKKAM,138,62000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CPS GOVINDASAMY STREET , MGR NAGAR, (3 MONTHS PERIODE ONLY) IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19056,Parks,Completed,NK-KODAMBAKKAM,138,25000,"PROVIDING PRIVATE WATCH MAN AT CHSS GOVINDASAMY STREET , MGR NAGAR, (3 MONTHS PERIOD ONLY) IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19058,Parks,Completed,NK-KODAMBAKKAM,138,25000,"PROVIDING WATCH MAN FOR FOOTBALL GROUND (NIGHT SHIFT ONLY) AT CHSS GOVINDASAMY STREET , MGR NAGAR, (3 MONTHS PERIOD ONLY) IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19059,Parks,Completed,NK-KODAMBAKKAM,138,50000,"PROVIDING PRIVATE SECURITY AT BHARATHIDASAN COLONY 6TH STREET PARK (3 MONTHS PERIOD ONLY) IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19065,Parks,Completed,NK-KODAMBAKKAM,138,249000,"PROVIDING PRIVATE LABOUR FOR PUBLIC TOILETS CLEANING WORK @ ASHOK PILLER ROAD, 60 FEET ROAD, GOVINDASAMY STREET, PACHAYAPPEN STREET AND NAMMA TOILET IN DIVSION-138. UNIT-28,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19324,Buildings,Completed,NK-KODAMBAKKAM,138,394000,"PROVIDING MS SHEET PARTITION (COMPOUND WALL) FOR BURIAL GROUND AT PACHAYAPPEN 1ST CROSS STREET, JAFFERKHANPET IN DIVSION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19456,Buildings,Completed,NK-KODAMBAKKAM,138,528000,"DEMOLISH THE EXISTING DAMAGED SUNSHADE AND PROVIDING NEW M.S SHEET SUN SHADE WITH FREAM WORK AT CPS GOVINDASAMY STREET, MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/4295,Buildings,Completed,NK-KODAMBAKKAM,138,323000,"CONSTRUCTION OF RAIN WATER HARVESTING STRUCTURE USING PRECAST WELL RING AT NETHAJI NAGAR , KASI ESTATE , PRAMAVATHI STREET , PAMMAL NALLATHAMBI STREET AND SM BLOCK ZAHIR HUSSAIN STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4781,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,445000,"DESILTING OF SWD AT PILLAIYAR KOVIL STREET ,KK SALAI,GOVINDASAMY STREET,MANGAI NAGAR MAIN ROAD,MANGAI NAGAR 2nd STREET,PARI NAGAR KARIKALAN STREET,PARI NAGAR CHOLAN STREET,PARI NAGAR COMMERCIAL COMPLEX ROAD,KASI ESTATE,ANJUGAM NAGAR 3rd STREET,ANJUGAM NAGAR 4th STREET IN DIV-138,U-28,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4783,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,444000,"DESILTING OF SWD AT BHATATHIDASAN COLONY MAIN ROAD,ANNA MAIN ROAD,ASHOK PILLAR SALAI,BHATATHIDASAN COLONY 4TH STREET IN DIV-138,U-28,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/4987,Buildings,Completed,NK-KODAMBAKKAM,138,930000,"Removal of Debris in various Roads and Streets dumping the same in PDG/KDG in Div 138 and 139,Unit-28, Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6013,Buildings,Completed,NK-KODAMBAKKAM,138,950000,"CONSTRUCTION OF ADDITIONAL AMMA UNAVAGAM DINNING HALL AT ASHOK PILLAR ROAD, K.K.NAGAR (IN FRONT OF ESI HOSPITAL) IN DIV-138,U-28,Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/6339,Buildings,Completed,NK-KODAMBAKKAM,138,935000,"ATTENDING DEPOSIT WORK RESTORATION OF ROAD CUT MADE CMWSSB AT GOVINDASAMY STREET, V.N.JANAKI STREET ,SANJAI GANDHI STREET, NAGGAPPAN STREET AND MANGAI NAGAR MAIN ROAD IN DIVISION-138,UNIT-28,ZONE-10.",Deposit Works,10,2016-17,2018-19 NK/2016-17/6463,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,790000,"DESILTING OF M.G.R CANAL USING OF POCLAIN FROM ANNA MAIN ROAD TO ADYAR RIVER,JAFFERKHANPET IN DN138, UNIT-28, ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8286,Buildings,Completed,NK-KODAMBAKKAM,138,965000,"CONSTRUCTION OF ROAD CROSSING SWD AT BHARATHIDASAN COLONY MAIN ROAD IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/8433,Parks,Completed,NK-KODAMBAKKAM,138,300000,"ANNUAL MAINTENANCE OF PARK AT BHARATHIDASEN COLONY 6THSTREET,KK NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/9769,Buildings,Completed,NK-KODAMBAKKAM,138,800000,"Construction for Amma Drinking Water in Amma Unavagam at Anna Main Road in Dn.138,Unit-28,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/9770,Buildings,Completed,NK-KODAMBAKKAM,138,950000,"Construction Kitchen shed for Amma Unavagam at Anna Main Road infront of ESI Hospital in Dn.138,Unit-28,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/0239,Buildings,Completed,NK-KODAMBAKKAM,139,230000,"OUT SOURCING OF PRIVATE WORKERS FOR CLEANING SCHOOLS AT CHS JAFFERKHANPET ,CPS JAFFERKHANPET AND CPS R.V.NAGAR IN DIV139, UNIT-28,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/0763,Roads,Completed,NK-KODAMBAKKAM,139,998000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT ANNAMALAI NAGAR 3RD ST AND PERIYAR RAMASAMY ST IN DIV-139,U-28,Z-10",Deposit Works,10,2016-17,2016-17 NK/2016-17/0767,Roads,Completed,NK-KODAMBAKKAM,139,992000,"RESTORATION OF ROADCUT MADE BY CMWSSB AT ANNAMALAI NAGAR 1ST STREET AND ANNAMALAI NAGAR 2ND STREET IN DIV-139,U-28,Z-10",Deposit Works,10,2016-17,2016-17 NK/2016-17/0843,Buildings,Completed,NK-KODAMBAKKAM,139,769000,"DE-SILTING OF JAFFERKHANPET CANAL INCLUDING REMOVAL OF FLOATING MATERIALS USING POCLAIN FROM R.V.NAGAR TO ADYAR RIVER IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/10738,Roads,Completed,NK-KODAMBAKKAM,139,527000,"RELAYING OF ROAD USING BT 30MM THICK WITH PAVER FINISHER AT VASUKI ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10741,Roads,Completed,NK-KODAMBAKKAM,139,321000,"RELAYING OF ROAD USING B.C. 30MM THICK WITH PAVER FINISHER AT KAMARAJ ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10744,Roads,Completed,NK-KODAMBAKKAM,139,340000,"RELAYING OF ROAD USING BY B.C. 30MM WITH PAVER FINISHER AT ANNA ST(ETHIRAJ NAGAR) IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2016-17 NK/2016-17/10745,Roads,Completed,NK-KODAMBAKKAM,139,775000,"RELAYING OF ROAD USING CEMENT CONCRETE AT VEETHI MARIYAMMAN KOIL MAIN ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/10747,Roads,Completed,NK-KODAMBAKKAM,139,1120000,"RELAYING OF ROAD USING CEMENT CONCRETE AT VEETHI MARIYAMMAN KOIL 1ST STREET IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10775,Roads,Completed,NK-KODAMBAKKAM,139,1120000,"RELAYING OF ROAD USING BY CEMENT CONCRETE AT VEETHIMARIYAMMAN KOIL 2ND ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10776,Roads,Completed,NK-KODAMBAKKAM,139,1034000,"RELAYING OF ROAD USING BY CEMENT CONCRETE AT MANI ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10778,Roads,Completed,NK-KODAMBAKKAM,139,859000,"RELAYING OF ROAD WORK USING BY CEMENT CONCRETE AT MUNUSAMY ST(SARATHI NAGAR) IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10814,Roads,Completed,NK-KODAMBAKKAM,139,1094000,"RELAYING OF ROAD USING CEMENT CONCRETE AT VADIVEL ST (KATTABOMMAN BLOCK) IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10816,Roads,Completed,NK-KODAMBAKKAM,139,258000,"RELAYING OF ROAD USING CEMENT CONCRETE AT M.P.BALAN ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10817,Roads,Completed,NK-KODAMBAKKAM,139,577000,"RELAYING OF ROAD USING CEMENT CONCRETE AT MURASOLIMARAN ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10821,Roads,Completed,NK-KODAMBAKKAM,139,1035000,"RELAYING OF ROAD USING CEMENT CONCRETE AT KRISHNAN ST & MAHADEVAN ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10823,Roads,Completed,NK-KODAMBAKKAM,139,517000,"RELAYING OF ROAD USING BY CEMENT CONCRETE AT ARUNACHALAM ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/10825,Roads,Completed,NK-KODAMBAKKAM,139,776000,"RELAYING OF ROAD USING BY CEMENT CONCRETE AT DEVARAJAN ST & BASKARAN ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10826,Roads,Completed,NK-KODAMBAKKAM,139,345000,"RELAYING OF ROAD USING BY CEMENT CONCRETE AT KANNIYAPPAN ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/10827,Roads,Completed,NK-KODAMBAKKAM,139,949000,"RELAYING OF ROAD USING BY CEMENT CONCRETE AT RAJABADAR ST & ARUMUGAM ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/12553,Buildings,Completed,NK-KODAMBAKKAM,139,910000,"IMPROVEMENTS TO COMMUNITY HALL AT VADIVEL MAIN ROAD JAFFERKHANPET IN DN-139,U-28,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/13925,Buildings,Completed,NK-KODAMBAKKAM,139,144000,"IMPROVEMENT TO THE PUBLIC CONVENIENCE AT JAFFERKHANPET MAIN ROAD AND VOC BLOCK IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/19049,Buildings,Completed,NK-KODAMBAKKAM,139,25000,"PROVIDING SECURITY ARRANGEMENTS FOR CHS JAFFERKHANPET IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19055,Buildings,Completed,NK-KODAMBAKKAM,139,99000,"OUTSOURCING OF PRIVATE WORKERS FOR PUBLIC CONVEYANCE CLEANING AT PILLAIYAR KOIL STREET P.C AND V.O.C BLOCK P.C IN DIV-139, UNIT -28, ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19134,Buildings,Completed,NK-KODAMBAKKAM,139,25000,"PROVIDING SECURITY ARRANGEMENT (NIGHT) FOR CPS AT SCHOOL STREET IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/2239,Road Cut,Completed,NK-KODAMBAKKAM,139,916000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT NEW COLONY MAIN ST,NEW COLONY 4TH ST,MUNUSAMY ST(BHARATHI BLOCK),MANI ST,MUNUSAMY ST(SARATHY NAGAR) AND SUNDARA MOORTHY ST IN DIV-139,U-28,Z-10",Deposit Works,10,2016-17,2017-18 NK/2016-17/2240,Road Cut,Completed,NK-KODAMBAKKAM,139,998000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT VEEDHIMAARIYAMMAN KOIL ST,ANNA ST,VASUKI ST AND KAMARAJ ST IN DIV-139,U-28,Z-10",Deposit Works,10,2016-17,2017-18 NK/2016-17/3981,Buildings,Completed,NK-KODAMBAKKAM,139,845000,"OUT SOURCING OF PRIVATE WORKERS FOR CLEANING SCHOOLS AT CHS JAFFERKHANPET ,CPS JAFFERKHANPET AND CPS R.V.NAGAR IN DIV139, UNIT-28,ZONE10",Own Sources,10,2016-17,2018-19 NK/2016-17/4159,Buildings,Completed,NK-KODAMBAKKAM,139,535000,"Providing Pa - Shape for Compact Bin at Various Location in Div-139,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/4632,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,943000,"OPERATION AND MAINTENANCE OF GASIFIER CREMATORIUM AT WEST JONES ROAD BURIAL GROUND IN DIVISION -139,UNIT - 28,ZONE- 10",Own Sources,10,2016-17,2019-20 NK/2016-17/4891,Roads,Completed,NK-KODAMBAKKAM,139,265000,"RELAYING OF ROAD USING CEMENT CONCRETE AT R.R.COLONY 4TH CROSS STREET IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6735,Buildings,Completed,NK-KODAMBAKKAM,139,750000,"ANNUAL MAINTENANCE OF COMPOSTING YARD AND BIO GAS PLANT AT WEST SAIDAPET BURIAL GROUND IN DIV - 139, U-28, Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/7329,Roads,Completed,NK-KODAMBAKKAM,139,728000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT PERIYAR RAMASAMY ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/7670,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,860000,"DESILTING OF THE SWD AT GANDHI ST,PERUMAL KOIL WEST MADA ST,WEST JONES ROAD,VALLUVAR ST,VENUGOBAL ST,R.V.NAGAR 67TH ST,R.V.NAGAR 69TH ST,E.K.RAGAVAN ST,LAKSHMI ST,ARUMUGAM ST,KANNAMMAL ST,R.R.COLONY 4TH ST AND R.R.COLONY 1ST CROSS ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/7674,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,945000,"DESILTING OF THE SWD AT MANIKKAM ST,VENKATACHALAM ST,GANESAN ST,S.V.CHIDAMBARAM SALAI,VADIVEL MAIN ST,R.R.COLONY 2ND CROSS ST, ANNAMALAI NAGAR 1ST STREET, ANNAMALAI NAGAR 2ND STREET, ANNAMALAI NAGAR 3RD STREET,PILLAIYAR KOIL ST,PERIYAR RAMASAMY ST,RAJAMBAL ST,DEIVANAMBI ST,SUSEELA ST,KUPPUSAMY ST,MAHADEVAN ST AND SUBRAMANIYAM ST IN DIV-139,U-28,Z-10",Own Sources,10,2016-17,2019-20 NK/2016-17/8552,Buildings,Completed,NK-KODAMBAKKAM,139,698000,"PROVIDING SECURITY ARRANGEMENTS AND SWEEPERS TO COMMUNITY HALL AT VADIVEL MAIN ST IN DIV-19,U-28,Z-10",Own Sources,10,2016-17,2018-19 NK/2016-17/8995,Buildings,Completed,NK-KODAMBAKKAM,139,982000,IMPROVEMENT AND REPAIR WORK ON COMMUNITY HALL IN VADIVEL MAIN STREET (UNDER WARD COUNCILLOR FUND) DIV 139 U 28 Z 10,Own Sources,10,2016-17,2018-19 L/2016-17/12842,Electrical,Completed,L-Electrical,140,133000,"WORK: Supply,intallation ,aiming,testing and commissioning of 1 no. of 8m GI Octogonal Mini high with 3 nos of LED flood light fitting at Govidhan Road (JN) Kodambakkam Road , Division 140, Zone-10 WORK: Supply,intallation ,aiming,testing and commissioning of 1 no. of 8m GI Octogonal Mini high with 3 nos of LED flood light fitting at Govidhan Road (JN) Kodambakkam Road , Division 140, Zone-10",Own Sources,10,2016-17,2017-18 L/2016-17/14004,Electrical,Completed,L-Electrical,140,59200,"Supply and fixing of existing mini high mast additional fitting 3 nos of LED flood light fitting at Govindan Road jun Kodambakkam Road ,Division 140, Zone- 10",Own Sources,10,2016-17,2017-18 NK/2016-17/10734,Roads,Completed,NK-KODAMBAKKAM,140,399000,RELAYING THE ROAD USING BITUMINOUS CONCRETE WITH PAVER FINISHER AT KARANI GARDEN 3RD STREET IN DIV 140 U 30 Z10,Own Sources,10,2016-17,2016-17 NK/2016-17/10735,Roads,Completed,NK-KODAMBAKKAM,140,581000,RELAYING THE ROAD USING BITUMINOUS CONCRETE WITH PAVER FINISHER AT VISAGATHOTTAM STREET IN DIV 140 U 30 Z10,Own Sources,10,2016-17,2016-17 NK/2016-17/11479,Buildings,Completed,NK-KODAMBAKKAM,140,868000,"IMPROVEMENT WORKS FOR ANGANWADI AT ADHIKESAVA PERUMAL KOIL STREET AND CHENNAI HIGHER SECONDARY SCHOOL AT K.R.KOIL STREET IN DIV-140, U-30,Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/11542,Buildings,Completed,NK-KODAMBAKKAM,140,995000,"Improvements and Repair works to the existing Main block in Boys CHSS(North side block with head room) at Kodambakkam road, Saidapet in Dn-140, U-30, Z-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/11543,Buildings,Completed,NK-KODAMBAKKAM,140,990000,"Improvements and Repair works to the existing Main block in Boys CHSS(South side block with head room) at Kodambakkam road, Saidapet in Dn-140, U-30, Z-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/11544,Buildings,Completed,NK-KODAMBAKKAM,140,875000,"Construction of Motor room, Hand wash area, Compound wall (for EB Transformer) and Main block toilet rooms in Boys CHSS at Kodambakkam road, Saidapet in Dn-140, U-30, Z-X.",Own Sources,10,2016-17,2018-19 NK/2016-17/13974,Buildings,Completed,NK-KODAMBAKKAM,140,141000,"REPAIRS AND IMPROVEMENTS WORK FOR PUBLIC CONVEYANCE AT KODAMBAKKAM ROAD, LIC COLONY MAIN STREET AND ADHIKESAVA PERUMAL KOIL STREET IN DIV-140, U-30,Z-10",Own Sources,10,2016-17,2017-18 NK/2016-17/19089,Buildings,Completed,NK-KODAMBAKKAM,140,24000,"PROVIDING SECURITY GUARDS TO CHENNAI BOYS HIGHER SECANDARY SCHOOL AT KODAMBAKKAM ROAD IN DIV-140,U-30,Z-10. ( 3 MONTHS)",Own Sources,10,2016-17,2018-19 NK/2016-17/19094,Buildings,Completed,NK-KODAMBAKKAM,140,39000,"MAINTENANCE OF PARK AT ELLAIAMMAN KOIL STREET IN DIV-140, U-30, Z-10 ( 3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/19096,Parks,Completed,NK-KODAMBAKKAM,140,24000,"PROVIDING SECURITY GURDS TO AMMA UNAVAGAM AT REDDYKUPPAM SALAI IN DIV-140, U-30, Z-10.(3 MONTHS)",Own Sources,10,2016-17,2018-19 NK/2016-17/19097,Parks,Completed,NK-KODAMBAKKAM,140,24000,"PROVIDING SECURITY GUARDS TO AMMA PARK AT KODAMBAKKAM ROAD IN DIVISION -140,UNIT -30, ZONE -10. ( 3 MONTHS)",Own Sources,10,2016-17,2018-19 NK/2016-17/19098,Buildings,Completed,NK-KODAMBAKKAM,140,249000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI BOYS HIGHER SECONDARY SCHOOL IN DIVISION -140, UNIT -30, ZONE -10. (3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/19100,Parks,Completed,NK-KODAMBAKKAM,140,25000,"ENGAGING PRIVATE LABOUR FOR HOUSE KEEPING WORK FOR UPHC AT GOVINDAN ROAD IN DIVISION-140,UNIT-30,ZONE-10. (3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/19102,Parks,Completed,NK-KODAMBAKKAM,140,24000,"PROVIDING SECURITY GUARDS TO PARK AT ELLAIAMMAN KOIL STREET IN DIVISION -140,UNIT -30, ZONE -10. ( 3 MONTHS)",Own Sources,10,2016-17,2018-19 NK/2016-17/19125,Buildings,Completed,NK-KODAMBAKKAM,140,24000,"PROVIDING SECURITY GUARDS TO AMMA UNAVAGAM AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/19126,Buildings,Completed,NK-KODAMBAKKAM,140,99000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI MIDDLE SCHOOL AT PERUMAL KOIL STREET IN DIV -140, UNIT -30, ZONE -10. (3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/19127,Buildings,Completed,NK-KODAMBAKKAM,140,74000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI MIDDLE SCHOOL AT VANDIKARAN STREET IN DIV -140, UNIT -30, ZONE -10. (3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/19128,Buildings,Completed,NK-KODAMBAKKAM,140,124000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI HIGHER SECONDARY SCHOOL AT K.R.KOIL STREET IN DIVISION -140, UNIT -30, ZONE -10. (3 MONTHS)",Own Sources,10,2016-17,2019-20 NK/2016-17/2618,Buildings,Completed,NK-KODAMBAKKAM,140,454000,"Providing Pa - Shape for Compact Bin at Various Location in Division - 140, Unit - 30, Zone - X.",Own Sources,10,2016-17,2018-19 NK/2016-17/3377,Buildings,Completed,NK-KODAMBAKKAM,140,877000,"IMPROVEMENT WORKS FOR AMMA PARK AT KODAMBAKKAM ROAD IN DIVISION-140, UNIT-30,ZONE-10",Own Sources,10,2016-17,2017-18 NK/2016-17/4196,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,931000,"DESILTING OF EXISTING STORM WATER DRAIN AT KODAMBAKKAM ROAD, GOVINDAN ROAD, K.R.KOIL STREET, REDDYKUPPAM SALAI(BRR),KODAMBAKKAM ROAD WEST, KASIKULAM, 11TH AVENUE, KRISHNAN STREET, RAGHAVAN STREET,NARATHINAMMAL COLONY iN DIV-140,U-30,Z-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4197,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,945000,"DESILTING OF EXISTING STORM WATER DRAIN AT PUSHPAVATHIAMMAL STREET, SRINIVASA IYENGAR MAIN STREET, JOTHIRAMALINGAM STREET, VADIVELPURAM , ELLAI AMMAN KOIL STREET, SAMBANGI STREET, ARANGAPPAN STREET, KUMARAN COLONY 1ST STREET, KUMARAN COLONY 2ND STREET,REDDY KUPPAM SALAI, KARUNANIDHI 1ST STREET, RAJAJI STREET, NETHAGI STREET, SARADHAMBAL STREET, VAZHAITHOPPU 6TH STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/4198,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,733000,"IMPROVEMENT WORK FOR FOOTPATH AND SPEED BREAKERS AT REDDYKUPPAM SALAI AND VARIOUS STREETS AND REPAIRS TO THE ANGANWADI AT KUMARAN COLONY 1ST STREET IN DN-140,UT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4250,Footpath,Completed,NK-KODAMBAKKAM,140,946000,"FORMATION OF NEW FOOTPATH NORTH AND WEST SIDE IN AMMA PARK (EXTENSION AREA) AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.(UNDER WARD COUNCILOR FUND 2016-17)",Own Sources,10,2016-17,2016-17 NK/2016-17/4251,Parks,Completed,NK-KODAMBAKKAM,140,953000,"FORMATION OF NEW FOOTPATH SOUTH AND WEST SIDE AND GYM AREA IN AMMA PARK (EXTENSION AREA) AT KODAMBAKKAM ROAD IN DIVISION-140,UNIT-30,ZONE-10.(UNDER WARD COUNCILOR FUND 2016-17)",Own Sources,10,2016-17,2016-17 NK/2016-17/4253,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,970000,"PROPOSED CONSTRUCTION WORK FOR ADDITIONAL AMMA UNAVAGAM AT REDDYKUPPAM SALAI (JUNCTION OF GOVINDAN ROAD) IN DIV-140, U-30 , Z-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/4255,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,702000,"OUTSOURCING OF PRIVATE WORK FOR PUBLIC TOILET AT KODAMBAKKAM ROAD,LIC COLONY AND ADHI KESAVA PERUMAL KOVIL ST IN DN-140,UT-30,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/4258,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,980000,"WATER SUPPLY ARRANGEMENTS AND ELECTRICAL WORK FOR ADDITIONAL AMMA UNAVAGAM AT REDDYKUPPAM SALAI (JUNCTION OF GOVINDAN ROAD) IN DIVISION-140, UNIT-30, ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/4277,Parks,Completed,NK-KODAMBAKKAM,140,984000,"PROVIDING PYRAMID FOR MEDITATION TO AMMA PARK AT KODAMBAKKAM ROAD(UNDER WARD COUNCILOR FUND 2016-17) IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2016-17 NK/2016-17/0503,Buildings,Completed,NK-KODAMBAKKAM,141,826000,"REPAIRS & IMPROVEMENTS TO THE HOSPITAL AT SOUTH USMAN ROAD AND AMMA DRINKING WATER SHED AT 4TH MAIN ROAD,CIT NAGAR IN DIVISION-141,UNIT,30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/11199,Buildings,Completed,NK-KODAMBAKKAM,141,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT NEW BOAG ROAD DIV -141,UNIT -30,ZONE -10.",Own Sources,10,2016-17,2018-19 NK/2016-17/11200,Buildings,Completed,NK-KODAMBAKKAM,141,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT NEW BOAG ROAD DIV -141,UNIT -30,ZONE -10.",Own Sources,10,2016-17,2018-19 NK/2016-17/11394,Roads,Completed,NK-KODAMBAKKAM,141,450000,"LAYING CEMENT CONCRETE ROAD AT MADLEY 2ND STREET LANE IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2019-20 NK/2016-17/11395,Roads,Completed,NK-KODAMBAKKAM,141,650000,"LAYING CEMENT CONCRETE ROAD AT C.I.T. NAGAR 3 rd CROSS STREET (PART) IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/11415,Buildings,Completed,NK-KODAMBAKKAM,141,542000,"Planting of new Trees at inside of Burial Ground at New Boag Road in Dn-141,Unit-30,Zone-10",Own Sources,10,2016-17,2019-20 NK/2016-17/13858,Buildings,Completed,NK-KODAMBAKKAM,141,753000,"REPAIR AND IMPROVEMENTS WORK FOR AMMA UNAVAGAM AT CIT NAGAR 4TH MAIN ROAD, LALITHAPURAM AND MAINTENANCE TO FOOTPATH AND COMPOSITING YARD C.I.T NAGAR IN DIVISION-141,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/14148,Buildings,Completed,NK-KODAMBAKKAM,141,301000,"IMPROVEMENT AND REPAIR TO PUBLIC CONVENIENCE AT POLICE QUATERERS ROAD, SOUTH WEST BOAG ROAD, MOOPPARAPPAN STREET AND CIT NAGAR 4TH CROSS ROAD IN DIVISION-141,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/16901,Parks,Completed,NK-KODAMBAKKAM,141,200000,"RECTIFICATION WORK FOR COMPOUND WALL AT CIT NAGAR 3 rd MAIN ROAD PARK IN DIVISION - 141, UNIT - 30, ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/19153,Buildings,Completed,NK-KODAMBAKKAM,141,299000,"Out Sourcing of Private Workers in Schools at CHS CIT Nagar , CPS CIT Nagar,CHS Kannamapettai and CPS Kannamapettai in Dn.141, Unit -30,Zone-10 (3 Months)",Own Sources,10,2016-17,2018-19 NK/2016-17/2632,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,890000,"DESILTING OF MAMBALAM CANAL INCLUDING REMOVAL OF FLOATING MATERIALS USING POCLAIN FROM VENKAT NARAYANA ROAD TO CIT NAGAR 4TH MAIN ROAD (REACH-1) IN DIVISION-141,UNIT-30 , ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/2634,Playfields,Completed,NK-KODAMBAKKAM,141,910000,"SUPPLYING AND FIXING MORDEN GYM EQUIPMENTS OF CIT NAGAR 3rd MAIN ROAD PARK INSIDE IN DIVISION - 141, UNIT -30, ZONE -10. (UNDER MAYOR FUND)",Own Sources,10,2016-17,2018-19 NK/2016-17/4510,Buildings,Completed,NK-KODAMBAKKAM,141,740000,"CONSTRUCATION OF TOILET AT CIT NAGAR 4th MAIN ROAD HIGH SEC SCHOOL (UNDER MLA FUND 2015-2016 ) IN DIVISION-141,UNIT-30,ZONE-10.",MLACDS,10,2016-17,2017-18 NK/2016-17/4862,Roads,Completed,NK-KODAMBAKKAM,141,800000,"ATTENDING CEMENT CONCRETE PATCH WORK AT CORPORATION COLONY 1,2 AND VARIOUS STREET IN DIVISION-141,UNIT-30,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/4868,Footpath,Completed,NK-KODAMBAKKAM,141,920000,"IMPROVEMENT TO FOOTPATH AT CIT NAGAR SOUTH WEST BOAG ROAD AND VARIOUS STREET IN DIVISION - 141,UNIT- 30, ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/5273,Buildings,Completed,NK-KODAMBAKKAM,141,998000,"SUPPLY, INSTALLATION,COMMISSIONING OF HIGH QUALITY TREATED DRINKING WATER PLANT ( RO/UV FILTRATION ) OF 2000 LITERS / HOUR CAPACITY(AMMA KUDINEER) IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2016-17,2017-18 NK/2016-17/5403,Buildings,Completed,NK-KODAMBAKKAM,141,151000,"ANNUAL MAINTENANCE OF BIO GAS PLANT AT CIT NAGAR AMMA UNAVAGAM IN DIVISION - 141, UNIT-30, ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/5465,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,772000,"DESILTING OF STROM WATER DRAIN AT BURKIT ROAD, SOUTH DHANDAPANI STREET AND VARIOUS STREET IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/5467,Buildings,Completed,NK-KODAMBAKKAM,141,835000,"DESILTING OF STROM WATER DRAIN AT CIT NAGAR 2nd CROSS STREET AND VARIOUS STREET IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/5471,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,800000,"DESILTING OF STROM WATER DRAIN AT MADLEY 2nd STREET AND VARIOUS STREET IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2016-17,2019-20 NK/2016-17/5520,Buildings,Completed,NK-KODAMBAKKAM,141,973000,"PROVIDING FENECING ARRANGEMENT AT KANNAMAPET BURIAL GROUND (SOUTH SIDE) OF NEW BOAG ROAD IN DIVISION - 141, UNIT - 30, ZONE -10.(UNDER MAYOR FUND 2016-17).",Own Sources,10,2016-17,2017-18 NK/2016-17/5530,Footpath,Completed,NK-KODAMBAKKAM,141,988000,"PROVIDING FENECING ARRANGEMENT AT KANNAMAPET BURIAL GROUND (NORTH SIDE) OF NEW BOAG ROAD IN DIVISION - 141, UNIT - 30, ZONE -10.(UNDER MAYOR FUND 2016-17).",Own Sources,10,2016-17,2017-18 NK/2016-17/5533,Parks,Completed,NK-KODAMBAKKAM,141,967000,"PROVIDING FENECING ARRANGEMENT AT KANNAMAPET BURIAL GROUND (EAST SIDE) OF NEW BOAG ROAD IN DIVISION - 141, UNIT - 30, ZONE -10.(UNDER MAYOR FUND 2016-17).",Own Sources,10,2016-17,2017-18 NK/2016-17/6398,Buildings,Completed,NK-KODAMBAKKAM,141,870000,"Improvements to Mangalore Tiled Roof Rest Room and Prayer Hall Buildings with flooring, walls,Roof,Painting Electrical Arrangements at Inside of Kannamapet at New Boag Road in Dn 141,Unit-30,Zone-10 (Under Mayor Fund 2016-17 )",Own Sources,10,2016-17,2017-18 NK/2016-17/6399,Buildings,Completed,NK-KODAMBAKKAM,141,998000,"Painting the Electrical Crematorium Buildings and Providing Benches, Fan ,Light and Electrical arrangements to Kannammapet Burial Ground at New Boag Road in Dn-141,Unit-30,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6414,Buildings,Completed,NK-KODAMBAKKAM,141,952000,"CONSTRUCTION OF WATER TREATMENT PLANT ROOM, AMMA DRINKING WATER AT KANNAMAPET NEW BOAG ROAD IN DIVISION -141, UNIT - 30, ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/6415,Buildings,Completed,NK-KODAMBAKKAM,141,980000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION ) OF 2000 LITERS / HOUR CAPACITY FOR 1 YEAR PERIOD (AMMA KUDINEER) IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/6788,Buildings,Completed,NK-KODAMBAKKAM,141,930000,"Removal of Debris in various Roads and Streets dumping the same in PDG/KDG in Div 136 and 141,Unit-30, Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6789,Buildings,Completed,NK-KODAMBAKKAM,141,660000,"Engaging 1 Private load Auto vehicle with Private labours 6 nos for Division work in Dn 141,UNit-30,Zone-10",Own Sources,10,2016-17,2018-19 NK/2016-17/6941,Buildings,Completed,NK-KODAMBAKKAM,141,890000,"Forming Gardens with shrubs and water pipeline arrangements at Kannammapet Burial Ground inside in Dn 141, Unit-30,Zone-10",Own Sources,10,2016-17,2017-18 NK/2016-17/7672,Parks,Completed,NK-KODAMBAKKAM,141,600000,"IMPROVEMENT TO TOILET ROOM, PARK FOOTPATH AND GRILL WORK AT CIT NAGAR 3RD MAIN ROAD PARK IN DIVISION - 141, UNIT-30, ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/7673,Playfields,Completed,NK-KODAMBAKKAM,141,690000,"FOOTPATH LAYING OF INTERLOCKING TILES AND FRP BENCH AT CIT NAGAR ROUNDNA AND SADHULLAH STREET IN DIVISION -141,UNIT-10, ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/7675,Roads,Completed,NK-KODAMBAKKAM,141,450000,"ATTENDING THE CC PATCH WORK AT CIT NAGR 4TH MAIN ROAD AND VARIOUS STREET IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2016-17,2018-19 NK/2016-17/7827,Buildings,Completed,NK-KODAMBAKKAM,141,785000,"OPERATION AND MAINTENANCE FOR ELECTRICAL CREMATORIUM AT KANNAMAPET BURIAL GROUND IN DIVISION - 141, UNIT - 30, ZONE - 10",Own Sources,10,2016-17,2018-19 NK/2016-17/8085,Roads,Completed,NK-KODAMBAKKAM,141,849000,"PROVDING COMPACTOR BIN PA SHAPE AT VARIOUS LOCATIONS AND IMPROVEMENT WORKS FOR FOOTPATH AT SOUTH DHANDAPANI STREET AND VARIOUS STREETS IN DIV-141, UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/8231,Buildings,Completed,NK-KODAMBAKKAM,141,306000,"SERVICING OF EXISTING ELECTRICAL CREMATORIUM AT KANNAMMAPET BURIAL GROUND IN DIV-141,UNIT-30,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/9750,Roads,Completed,NK-KODAMBAKKAM,141,927000,"STRENGTHENING AND RELAYING THE ROAD WITH CAMBER CORRECTION BY USING MECHANICAL PAVER FINISHER WITH BITUMINOUS CONCRETE AT NEW BOAG ROAD (PART) IN DIV-141, U-30, Z-10.",Own Sources,10,2016-17,2016-17 BR/2016-17/9269,Roads,Completed,BR-Bus Route Roads,142,9940000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improivement work at West jones Road -Div 142,Zone-10.",Grants,10,2016-17,2017-18 L/2016-17/18133,Electrical,Completed,L-Electrical,142,1883300,"Estimate for street lamp posts Various location in Division 127,128,130,133-136,140,141 & 142 Damaged due to Vardah Cylone, Zone 10",Own Sources,10,2016-17,2017-18 NK/2016-17/13972,Buildings,Completed,NK-KODAMBAKKAM,142,233000,"Improvements to the Public convenience at Kothavalchavadhi Street,Samiyar Thottam,Vegetable market,Jennis Road,Thideer Nagar, Abdul Razack Street,Godhamedhu and Dhobikana in Div 142,Unit -30,Zone -10",Own Sources,10,2016-17,2018-19 NK/2016-17/1853,Footpath,Completed,NK-KODAMBAKKAM,142,900000,"MAINTENANCE OF CPS SCHOOL SOUTH SIDE BLOCK AND NORTH SIDE BLOCK AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2016-17,2018-19 NK/2016-17/19074,Buildings,Completed,NK-KODAMBAKKAM,142,24500,"PROVIDING SECURITY GUARDS TO CGHS SCHOOL AT WEST JONES ROAD IN DIVISION -142, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2020-21 NK/2016-17/19090,Buildings,Completed,NK-KODAMBAKKAM,142,24900,"OUT SOURCING OF PRIVATE LABOUR FOR CONSERVANCY WORK AT UPHC HOSPITAL AT WEST JONES ROAD IN DIVISION -142, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19091,Buildings,Completed,NK-KODAMBAKKAM,142,74000,"OUT SOURCING OF PRIVATE LABOUR FOR CONSERVANCY WORK AT EOC HOSPITAL AT JEENIS ROAD IN DIVISION -142, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19122,Buildings,Completed,NK-KODAMBAKKAM,142,24900,"OUT SOURCING OF PRIVATE LABOUR FOR CONSERVANCY WORK AT CPS SCHOOL AT BAZAAR ROAD IN DIV 142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19124,Buildings,Completed,NK-KODAMBAKKAM,142,74000,"OUT SOURCING OF PRIVATE LABOUR FOR CONSERVANCY WORK AT CGHS SCHOOL AT WEST JONES ROAD IN DIV 142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19129,Buildings,Completed,NK-KODAMBAKKAM,142,24900,"OUT SOURCING OF PRIVATE LABOUR FOR CONSERVANCY WORK AT CPS SCHOOL AT WEST JONES ROAD IN DIV 142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19130,Buildings,Completed,NK-KODAMBAKKAM,142,24900,"OUT SOURCING OF PRIVATE LABOUR FOR CONSERVANCY WORK AT CMS SCHOOL AT THIDEER NAGAR IN DIV 142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19133,Buildings,Completed,NK-KODAMBAKKAM,142,24500,"PROVIDING SECURITY GUARDS TO AMMA UNAVAGAM AT JEENIS ROAD IN DIVISION -142, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2020-21 NK/2016-17/19283,Buildings,Completed,NK-KODAMBAKKAM,142,57000,"REPAIRS WORKS TO THE CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT WEST JONES ROAD IN DIV- 142 , U- 30, Z-10.",Own Sources,10,2016-17,2019-20 NK/2016-17/19284,Buildings,Completed,NK-KODAMBAKKAM,142,24500,"PROVIDING SECURITY GUARDS TO AMMA UNAVAGAM AT ABDHUL RAZACK STREET IN DIVISION -142, UNIT -30, ZONE -10.",Own Sources,10,2016-17,2020-21 NK/2016-17/3538,Road Cut,Completed,NK-KODAMBAKKAM,142,188000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT FLOWER STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3539,Road Cut,Completed,NK-KODAMBAKKAM,142,300000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT JEYARAM STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3543,Road Cut,Completed,NK-KODAMBAKKAM,142,511600,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KOOTHADUM PILLAIYAR KOIL STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3548,Road Cut,Completed,NK-KODAMBAKKAM,142,601000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KAARNEESHWARAR KOIL STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3549,Road Cut,Completed,NK-KODAMBAKKAM,142,511000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KAVARAI STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3550,Road Cut,Completed,NK-KODAMBAKKAM,142,586000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT PERUMAL KOIL STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3551,Road Cut,Completed,NK-KODAMBAKKAM,142,398000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SEMBADA STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3552,Road Cut,Completed,NK-KODAMBAKKAM,142,564000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SUBRAMANIASWAMY KOIL STREET IN DIVISION-142,UNIT-30,ZONE-10.",Deposit Works,10,2016-17,2017-18 NK/2016-17/3556,Buildings,Completed,NK-KODAMBAKKAM,142,175000,"IMPROVEMENTS TO THE AMMA UNAVAGAM AT JEENIS ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/3942,Roads,Completed,NK-KODAMBAKKAM,142,831000,"LAYING CEMENT CONCRETE ROAD AT KARANEESWARAR KOIL STREET FROM IOB BANK TO DOOR NO 25/1 IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/3943,Roads,Completed,NK-KODAMBAKKAM,142,920000,"LAYING CEMENT CONCRETE ROAD AT KARANEESWARAR KOIL STREET FROM ALANDUR SUBWAY TO IOB BANK IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/3945,Roads,Completed,NK-KODAMBAKKAM,142,920000,"LAYING CEMENT CONCRETE ROAD AT V.S.MUDHALI STREET FROM SUBRAMANIA MUDALI STREET TO KARANEESWARAR KOIL STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/3950,Roads,Completed,NK-KODAMBAKKAM,142,920000,"LAYING CEMENT CONCRETE ROAD AT K.P.KOIL STREET FROM DOOR NO 112/56 TO DOOR NO 75/50 IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/3952,Buildings,Completed,NK-KODAMBAKKAM,142,291000,"PROVIDING FLOORING FOR THE COMPACTOR BIN (PA SHAPE) AT VARIOUS PLACES IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/4212,Buildings,Completed,NK-KODAMBAKKAM,142,385000,"IMPROVEMENTS TO THE ANGANWADI AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4215,Buildings,Completed,NK-KODAMBAKKAM,142,315000,"IMPROVEMENTS TO THE CPS SCHOOL AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4282,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,994000,"DESILTING OF EXISTING STROM WATER DRAIN AT ALANDUR ROAD,KAVARAI STREET,BHARATHIYAR STREET,ABDUL RAZACK ROAD,BAZAAR ROAD,DIWAN BASHIYAM STREET,KOTHAVALCHAVADI STREET,PERUMAL KOIL STREET,JONES ROAD,TANK SQUARE STREET,THIRUVALLUVAR STREET,SESACHALA STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2017-18 NK/2016-17/4284,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,700000,"DESILTING OF EXISTING STROM WATER DRAIN AT EAST JONES ROAD,TANK SQUARE EAST STREET,SUBRAMANIA SALAI,JEENIS ROAD,RANGABASHIYAM STREET,OTHAVADAI STREET,MOSQUE STREET,WEST JONES ROAD,KUYAVAR STREET,DHARMARAJA KOIL STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2016-17,2018-19 NK/2016-17/7069,Buildings,Completed,NK-KODAMBAKKAM,142,874000,"REPAIRS AND IMPROVEMENTS WORK TO THE AMMA UNAVAGAM, EOC HOSPITAL, UPHC HOSPITAL, CHENNAI GIRLS HECONDARY SCHOOL, CHENNAI MIDDLE SCHOOL AND CHENNAI PRIMARY SCHOOLS IN DIVISION-142,UNIT-30,-10.",Own Sources,10,2016-17,2018-19 L/2016-17/13894,Electrical,Completed,L-Electrical,143,194500,"Laying of 460 Mtrs of 4x16 Sq.mm Alu Cable at UNION ROAD, DIVISION 143 in Zone-XI",Own Sources,11,2016-17,2017-18 L/2016-17/13896,Electrical,Completed,L-Electrical,143,199900,"Laying of 230 Mtrs of 2x16 Sq.mm Alu Cable & 265 Mtrs of 4x16 Sq.mm Alu Cable at Gurusami salai, Nolambur Division 143 in Zone-XI",Own Sources,11,2016-17,2017-18 L/2016-17/13897,Electrical,Completed,L-Electrical,143,198200,"Laying of 265 Mtrs of 2x16 Sq.mm Alu Cable & 230 Mtrs of 4x16 Sq.mm Alu Cable at 3rd Main road , Nolambur, Division 143 in Zone-XI",Own Sources,11,2016-17,2017-18 L/2016-17/13900,Electrical,Completed,L-Electrical,143,192300,"Laying of 230 Mtrs of 2x16 Sq.mm Alu Cable & 165 Mtrs of 4x16 Sq.mm Alu Cable at Union Road and phase 2, Nolambur, Divisions 143 in Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/0396,Roads,Completed,NL-VALASARAVAKKAM,143,998000,Relaying the B.T. Road at V.G.N 1st Cross Street & V.G.N. 4th Cross Street in Dn.143. U-32 Z-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/0397,Roads,Completed,NL-VALASARAVAKKAM,143,997000,"Relaying the B.T. Road at Guru Samy Road (Part) in Dn.143. U-32, Z-XI",Own Sources,11,2016-17,2016-17 NL/2016-17/0398,Roads,Completed,NL-VALASARAVAKKAM,143,900000,"Relaying the B.T. Road at Guru Samy Road (Part), V.O.C. Street and Gopi Street in Dn.143. U-32 Z-XI",Own Sources,11,2016-17,2016-17 NL/2016-17/0399,Roads,Completed,NL-VALASARAVAKKAM,143,820000,Relaying the B.T. Road at DABC Road and RR Street Extn in Dn.143. U-32 Z-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/0886,Roads,Completed,NL-VALASARAVAKKAM,143,998000,"PROVIDING BARRICADING FOR THE VACANT LANDS SITUATED IN DN143 &145, U 32 & 33, Z 11.",Own Sources,11,2016-17,2016-17 NL/2016-17/10243,Roads,Completed,NL-VALASARAVAKKAM,143,3000000,"Forming the BT road at Nolambur Phase-I, 1st main road and 5th main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10252,Roads,Completed,NL-VALASARAVAKKAM,143,4602000,"Forming the BT road at Nolambur Phase-I, 6th main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10256,Roads,Completed,NL-VALASARAVAKKAM,143,2951000,"Forming the BT road at Nolambur Phase-I, 7th main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10258,Roads,Completed,NL-VALASARAVAKKAM,143,3119000,"Forming the BT road at Nolambur Phase-I, 8th main road and 9th main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10259,Roads,Completed,NL-VALASARAVAKKAM,143,3118000,"Forming the BT road at Nolambur Phase-I, 10th main road and Nolambur Phase-I 10th, 11th, 14th and 15th cross street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10261,Roads,Completed,NL-VALASARAVAKKAM,143,3085000,"Forming the BT road at Nolambur Phase-I, 16th cross, 17th cross street and Phase -II 2nd main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10262,Roads,Completed,NL-VALASARAVAKKAM,143,3279000,"Forming the BT road at Nolambur Phase-II, 4th main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10263,Roads,Completed,NL-VALASARAVAKKAM,143,2853000,"Forming the BT road at Nolambur Phase-II, 2nd cross, 3rd cross, 4th cross and 5th cross street Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10358,Roads,Completed,NL-VALASARAVAKKAM,143,3229000,"Forming the BT road at Nolambur Phase-II,6th, 7th, 8th, 9th and 11th cross streets in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10360,Roads,Completed,NL-VALASARAVAKKAM,143,3181000,"Forming the BT road at Gajalakshmi nagar Road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10361,Roads,Completed,NL-VALASARAVAKKAM,143,2841000,"Forming the BT road at Nolambur Phase-II, 12th cross street, 13th cross street and Gajalakshmi nagar main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10363,Roads,Completed,NL-VALASARAVAKKAM,143,3151000,"Forming the BT road at Gajalakshmi nagar 2nd main road, Gajalakshmi nagar 1st, 2nd street and 2nd street (part) in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10364,Roads,Completed,NL-VALASARAVAKKAM,143,2943000,"Forming the BT road at Gajalakshmi nagar 3rd street, 3rd street (part), 4th street, 5th street and 1st street cross street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10379,Roads,Completed,NL-VALASARAVAKKAM,143,2841000,"Forming the BT road at Gajalakshmi nagar 5th street cross street, S&P garden 1st main road, S&P garden 1st cross street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10381,Roads,Completed,NL-VALASARAVAKKAM,143,3000000,"Forming the BT road at S&P garden 6th cross street, S&P garden 7th cross street and Gajalakshmi nagar cross street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10382,Roads,Completed,NL-VALASARAVAKKAM,143,4285000,"Forming the BT road at VGN nagar Gurusamy salai in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10384,Roads,Completed,NL-VALASARAVAKKAM,143,3011000,"Forming the BT road at VOC main road in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10385,Roads,Completed,NL-VALASARAVAKKAM,143,3427000,"Forming the BT road at S&P Garden 8th cross street, VOC Salai, Pachaiyappa nagr cross street and Vigneshwara nagar cross street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10386,Roads,Completed,NL-VALASARAVAKKAM,143,3318000,"Forming the BT road at Aishwarya Nagar, Sakthi nagar 4th Avenue and Tatia Nagar Phase-I in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10387,Roads,Completed,NL-VALASARAVAKKAM,143,2993000,"Forming the BT road at Tatia Nagar Phase-II and Tatia Nagar Phase-III in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10393,Roads,Completed,NL-VALASARAVAKKAM,143,4610000,"Forming the BT road at Bharathi Salai (Reach-1) in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10394,Roads,Completed,NL-VALASARAVAKKAM,143,4618000,"Forming the BT road at Bharathi Salai (Reach-2) in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10395,Roads,Completed,NL-VALASARAVAKKAM,143,4076000,"Forming the BT road at Phase-II Salai in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10396,Roads,Completed,NL-VALASARAVAKKAM,143,3245000,"Forming the BT road at College Road, College road 1st cross street and 2nd cross street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10397,Roads,Completed,NL-VALASARAVAKKAM,143,2990000,"Forming the BT road at Pachaiyappa Nagar, VGN Avenue road and Padma street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10398,Roads,Completed,NL-VALASARAVAKKAM,143,3347093,"Forming the BT road at Padma street 1st cross , 2nd cross street, Sriran nagar 1st street, Sriram nagar 1st cross, 2nd cross, 3rd cross streets , Devadoss street and Kannammal street in Dn-143, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/12279,Roads,Completed,NL-VALASARAVAKKAM,143,997000,"Relaying the BT Road at Nolambur phase-2 3rd Main road in Dn-143,U-32,Zone-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/12728,Buildings,Completed,NL-VALASARAVAKKAM,143,934000,Contruction Bin platform at Various street in Unit-32 in Zone-11.,Own Sources,11,2016-17,2017-18 NL/2016-17/14210,Buildings,Completed,NL-VALASARAVAKKAM,143,95000,"Improvements to Public Toilet at Vembuliamman koil street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/15885,Parks,Completed,NL-VALASARAVAKKAM,143,379000,"Improvements to Channel Road Park in Dn-143, Unit-32, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/15998,Parks,Completed,NL-VALASARAVAKKAM,143,125000,Urgent Repairs to Phase - I 3rd Main Road Park in Dn-143.,Own Sources,11,2016-17,2017-18 NL/2016-17/1681,Roads,Completed,NL-VALASARAVAKKAM,143,998000,Relaying the B.T. Road at S.R.R. 1st Main Road and 1st Cross Street in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1682,Roads,Completed,NL-VALASARAVAKKAM,143,950000,Relaying the B.T. Road at S.R.R. 2nd Main Road in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1683,Roads,Completed,NL-VALASARAVAKKAM,143,992000,Relaying the B.T. Road at Phase-II 4th Main Road (Part) in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1684,Roads,Completed,NL-VALASARAVAKKAM,143,915000,Relaying the B.T. Road at Phase-II 4th Main Road (Part) and S.R.R. Nagar 2nd and 3rd Cross Street in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1687,Roads,Completed,NL-VALASARAVAKKAM,143,998000,Relaying the B.T. Road at Church Road (4th Block) (Part) in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1688,Roads,Completed,NL-VALASARAVAKKAM,143,998000,Relaying the B.T. Road at Church Road (4th Block) (Part) in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1690,Roads,Completed,NL-VALASARAVAKKAM,143,993000,Relaying the B.T. Road at S & P Garden 5th Cross Street (Part) in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1693,Roads,Completed,NL-VALASARAVAKKAM,143,998000,Relaying the B.T. Road at S & P Garden 5th Cross Street (Part) in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1720,Roads,Completed,NL-VALASARAVAKKAM,143,996000,Relaying the B.T. Road at S & P Garden 2nd Cross Street (Part) in Dn.143 U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1721,Roads,Completed,NL-VALASARAVAKKAM,143,997000,Relaying the B.T. Road at S & P Garden 2nd Cross Street (Part) and 4th Cross Street in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1723,Roads,Completed,NL-VALASARAVAKKAM,143,910000,Relaying the B.T. Road at S & P Garden 3rd Cross Street in Dn.143. U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/1724,Roads,Completed,NL-VALASARAVAKKAM,143,855000,Relaying the B.T. Road at S & P Garden 2nd Main Road in Dn.143 U-32 Zone-XI,Own Sources,11,2016-17,2016-17 NL/2016-17/18353,Parks,Completed,NL-VALASARAVAKKAM,143,85000,"Annual Maintenance of Park at Nolambur Phase-I Third Main Road (Three months) in Dn.143,Unit-32,Zone-11(By employed qualified horticulturist 0niy)",Own Sources,11,2016-17,2017-18 NL/2016-17/18355,Parks,Completed,NL-VALASARAVAKKAM,143,42000,"Annual Maintenance of Park at Nolambur Phase-I,9th Main Road Park, Door no.225 new park (Three months) in Dn.143,Unit-32,Zone-11(By employed qualified horticulturist 0niy)",Own Sources,11,2016-17,2017-18 NL/2016-17/18385,Parks,Completed,NL-VALASARAVAKKAM,143,95000,"Annual Maintenance of Park at Nolambur Phase-II,7th cross Street park (Three months) in Dn.143,Unit-32,Zone-11(By employed qualified horticulturist 0niy)",Own Sources,11,2016-17,2017-18 NL/2016-17/18859,Buildings,Completed,NL-VALASARAVAKKAM,143,1868000,"Construction of Namma Toilet for Men 5 units with water supply, septic tank arrangements at Phase - II 2nd cross street in Dn - 143, U - 32, Z - XI",Grants,11,2016-17,2018-19 NL/2016-17/18861,Buildings,Completed,NL-VALASARAVAKKAM,143,1626000,"Construction of Namma Toilet for Women 5 units with water supply, septic tank arrangements at Phase - II 2nd cross street in Dn - 143, U - 32, Z - XI",Grants,11,2016-17,2018-19 NL/2016-17/4127,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,999000,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAINS AT VARIOUS STREETS IN DN - 143, ZONE -11.",Own Sources,11,2016-17,2018-19 NL/2016-17/4298,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,976000,"Desilting at Nolambur Canal Kavimani Salai to Mugappair West MainRoad Chainage 0 to 685m at Dn-143, Unit-32, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/4302,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,930000,"Desilting at Nolambur Canal Kavimani Salai to Mugappair West MainRoad Chainage 685 to 1330m at Dn-143, Unit-32, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/5629,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,999000,"Improvements of Side Drain at 4th Block 8th Street in Dn 143, Unit 32, Zone 11",Own Sources,11,2016-17,2018-19 NL/2016-17/5630,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,998000,"Improvements of Side Drain at 4th Block 15th Street in Dn 143, Unit 32, Zone 11",Own Sources,11,2016-17,2019-20 NL/2016-17/5657,Roads,Completed,NL-VALASARAVAKKAM,143,985000,Forming WMM work at Padasalai Street in Dn.143 U-32 Zone-XI,Own Sources,11,2016-17,2018-19 NL/2016-17/5828,Roads,Completed,NL-VALASARAVAKKAM,143,970000,Forming WMM work at Union Road in Dn.143 U-32 Zone-XI,Own Sources,11,2016-17,2018-19 NL/2016-17/5838,Roads,Completed,NL-VALASARAVAKKAM,143,940000,"Laying B.T. Road at Gangai amman koil street in Dn.143, U-32, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/5847,Roads,Completed,NL-VALASARAVAKKAM,143,850000,"Laying B.T. Road at S & B Garden 4th Cross Street in Dn.143, U-32, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/6739,Roads,Completed,NL-VALASARAVAKKAM,143,985000,"Relaying the BT Road AT Mugappair West Main Road (reach-1) In Dn-143,U-32,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/6746,Roads,Completed,NL-VALASARAVAKKAM,143,985000,"Relaying the BT Road AT Mugappair West Main Road (reach-2) In Dn-143,U-32,Z-11.",Own Sources,11,2016-17,2016-17 NL/2016-17/6747,Roads,Completed,NL-VALASARAVAKKAM,143,992000,"Relaying the BT Road AT Mugappair West Main Road (reach-3) In Dn-143,U-32,Z-11.",Own Sources,11,2016-17,2016-17 NL/2016-17/6750,Roads,Completed,NL-VALASARAVAKKAM,143,954000,"Relaying the BT Road AT Mugappair West Main Road (reach-4) In Dn-143,U-32,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/7581,Parks,Completed,NL-VALASARAVAKKAM,143,999000,"PROVIDING GREENERY AND OTHER IMPROVEMENTS TO PARK AT NOLAMBUR PHASE-1,6TH MAIN ROAD IN DN143,U32,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/7744,Parks,Completed,NL-VALASARAVAKKAM,143,998000,"PROVIDING ELECTRICAL ARRANGEMENTS TO THE PARK AT 7th CROSS STREET IN DN143,U32,Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/7745,Parks,Completed,NL-VALASARAVAKKAM,143,998000,"PROVIDING GAZEBO AT 7th CROSS STREET PARK IN DN143,U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/7780,Parks,Completed,NL-VALASARAVAKKAM,143,998000,"PROVIDING GREENERY AND OTHER IMPROVEMENTS TO THE PARK AT 7th CROSS STREET IN DN143,U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/8540,Parks,Completed,NL-VALASARAVAKKAM,143,998000,"PROVIDING ELECTRICAL.WATER SUPPLY AND DRAINAGE ARRANGEMENTS TO THE PARK AT 9th MAIN ROAD IN DN143, U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/8542,Parks,Completed,NL-VALASARAVAKKAM,143,858000,"PROVIDING GREENERY AND OTHER ARRANGEMENTS TO THE PARK AT 9th MAIN ROAD IN DN143,U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/8544,Parks,Completed,NL-VALASARAVAKKAM,143,998000,"SUPPLYING AND FIXING PLAY APPARATUS,WATER SUPPLY AND DRAINAGE ARRANGEMENTS TO THE PARK AT 7th CROSS STREET IN DN143,U32,Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/8581,Parks,Completed,NL-VALASARAVAKKAM,143,998000,"PROVIDING PEBBLE PATH WAY AND OTHER IMPROVEMENTS TO THE PARK AT 7th CROSS STREET IN DN143,U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/8582,Parks,Completed,NL-VALASARAVAKKAM,143,998000,"PROVIDING CLOCK TIMER AND OTHER IMPROVEMENTS TO THE PARK AT 7th CROSS STREET IN DN143,U32,Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/8709,Parks,Completed,NL-VALASARAVAKKAM,143,650000,"PROVIDING NAME BOARDS AND OTHER IMPROVEMENT WORKS TO THE PARK AT 7th CROSS STREET IN DN143,U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/0720,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,380000,"IMPROVEMENT WORK IN SIDE DRAIN AT KARTHIGAI STREET SELLI AMMAN NAGAR IN DIV-145,UNIT-32,ZONE-11",Own Sources,11,2016-17,2016-17 NL/2016-17/10232,Roads,Completed,NL-VALASARAVAKKAM,144,2793000,"Forming the BT road at Ayyavu Nagar 3rd main road Ayyavu nagar 1st Cross, 2nd Cross and 3rd cross streets in Dn-144, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/10890,Roads,Completed,NL-VALASARAVAKKAM,144,926000,Laying Thermo Plastic and RPM various street in division-144 in unit - 32 in Zone - XI,Own Sources,11,2016-17,2017-18 NL/2016-17/14815,Buildings,Completed,NL-VALASARAVAKKAM,144,196000,"REPAIR WORKS TO THE PUBLIC CONVENIENCE IN PILLAIYAR KOIL STREET, NAGATHAMMAN KOIL STREET AND OM SAKTHI NAGAR IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/14955,Buildings,Completed,NL-VALASARAVAKKAM,144,517000,"Repair work V.G.P Amutha Nager Park ,Laying CC slab at various side drain and improvements works at division office in div 144, unit32, zone11",Own Sources,11,2016-17,2018-19 NL/2016-17/16077,Parks,Completed,NL-VALASARAVAKKAM,144,406000,"Improvements to Footpath & Play apparatus in VGP Amudha Nagar Park, MMDA Colony 6th & 7th Block Playspace at Div-144,U-32,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17287,Roads,Completed,NL-VALASARAVAKKAM,144,1193000,"Attending CC Patch Works to Bharathiyar Street in Div-144, Unit-32, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/19358,Buildings,Completed,NL-VALASARAVAKKAM,144,2485000,"CONSTRUCTION OF ANGANWADI AT SANNATHI STREET IN DIV-144, UNIR-32, ZONE-XI",MLACDS,11,2016-17,2018-19 NL/2016-17/3730,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,999000,"Desilting Storm water drain & side drain at various street in Dv-144,Un-32,Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/4527,Roads,Completed,NL-VALASARAVAKKAM,144,666000,"SUPPLYING AND FIXING STREET NAME BOARD AT VARIOUS STREETS IN DN-144, ZONE-11. (WARD COUNCILLOR SCHEME FUND 2016-17).",Own Sources,11,2016-17,2018-19 NL/2016-17/4528,Roads,Completed,NL-VALASARAVAKKAM,144,516000,"LAYING CEMENT CONCRETE ROAD AT AYYAVOO NAGAR 1ST AND 2ND CROSS STREETS IN DN - 144, ZONE - 11.( WARD COUNCILLOR SCHEME FUND 2016-17).",Own Sources,11,2016-17,2018-19 NL/2016-17/4955,Buildings,Completed,NL-VALASARAVAKKAM,144,585000,Improvements and Annual maintenance works at various places at div 144 Unit 32 Zone 11,Own Sources,11,2016-17,2017-18 NL/2016-17/5189,Roads,Completed,NL-VALASARAVAKKAM,144,537000,"LAYING CEMENT CONCRETE ROAD AT NAGATHAMMAN KOIL FIRST STREET (NEAR POLICE STATION) FROM POONAMALLEE HIGH ROAD TO CHAINAGE 70M IN DN-144, ZONE-11. (WARD COUNCILLOR SCHEME FUND 2016-17).",Own Sources,11,2016-17,2018-19 NL/2016-17/5192,Roads,Completed,NL-VALASARAVAKKAM,144,660000,"LAYING CEMENT CONCRETE ROAD AT NAGATHAMMAN KOIL SECOND STREET (FROM POONAMALLE HIGH ROAD TO DEAD END) IN DN-144, ZONE-11. (WARD COUNCILLOR SCHEME FUND 2016-17).",Own Sources,11,2016-17,2018-19 NL/2016-17/5388,Roads,Completed,NL-VALASARAVAKKAM,144,621000,"LAYING CEMENT CONCRETE ROAD AT NAGATHAMMAN KOIL FIRST STREET (NEAR POLICE STATION) FROM POONAMALLEE HIGH ROAD CHAINAGE 70M TO DEAD END IN DN-144, ZONE-11. (WARD COUNCILLOR SCHEME FUND 2016-17).",Own Sources,11,2016-17,2018-19 NL/2016-17/9793,Roads,Completed,NL-VALASARAVAKKAM,144,3030000,"Forming the BT road at MMDA Colony Road and Kannan Nagar Cross Street in Dn-144, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/9795,Roads,Completed,NL-VALASARAVAKKAM,144,3177000,"Forming the BT road at Abirami Nagar Main Road in Dn-144, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/0566,Buildings,Completed,NL-VALASARAVAKKAM,145,895000,"IMPROVEMENT TO C.I OFFICE AND DRESSING ROOM AND TOILET ARRANGEMENTS @ KARUNAGAR STREET IN DIVISION-145, UNIT-33, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/0567,Buildings,Completed,NL-VALASARAVAKKAM,145,590000,"IMPROVEMENT TO AE, T.C ROOM ETC IN THE OLD BUILDING @ KARUNAGAR STREET IN DIVISION-145, UNIT-33, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/0580,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,999000,"Improvement and Desilting to side drain water at Sakthi nagar C Block 22nd street in Dn-145, Unit-33, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/0711,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,348000,"IMPROVEMENT TO SIDE DRAIN AT SENTHAMILNAGAR MAIN ROAD,IN DIV-145,UNIT-33,ZONE-11",Own Sources,11,2016-17,2017-18 NL/2016-17/0712,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,342000,"IMPROVEMENT TO SIDE DRAIN AT MAIN ROAD SENTHAMILNAGAR-2 IN DN-145, U-33,Z-XI",Own Sources,11,2016-17,2018-19 NL/2016-17/0714,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,360000,"IMPROVEMENT TO SIDE DRAIN AT AMMAIYAPPAN STREET(SALAI), SENTHAMIL NAGAR-1 IN DN-145,U-33,Z-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/0715,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,380000,"IMPROVEMENT TO SIDE DRAIN AMMAYAPPAN STREET(SALAI),SENTHAMIL NAGAR IN DIV-145,UNIT-33,ZONE11",Own Sources,11,2016-17,2017-18 NL/2016-17/0716,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,413000,"SIDEDRAIN at KUMUDHAVALLI AVENUE-SENTAMIL NAGAR IN DIV-145, UNIT-33, ZONE-11",Own Sources,11,2016-17,2017-18 NL/2016-17/0717,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,396000,"IMPROVEMENT TO SIDE DRAIN AT SENTAMIL NAGAR, AMMAIYAPPAN 1STSTREE,T IN DIV-145, UNIT-33, ZONE-11",Own Sources,11,2016-17,2018-19 NL/2016-17/0719,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,380000,"IMPROVEMENT TO SIDE DRAIN AT SELLI AMMAN NAGAR KARTHIGAI STREET IN DIV-145,UNIT-32,ZONE-11",Own Sources,11,2016-17,2018-19 NL/2016-17/0721,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,380000,"IMPROVEMENTSIDE DRAIN AT KARTHIGAI STREET,SELLIAMMAN NAGAR IN DIV-145,UNIT-33, ZONE-11",Own Sources,11,2016-17,2017-18 NL/2016-17/0722,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,437000,"IMPROVEMENT TO SIDE DRAIN AT 4TH STREET,KRISHNA NAGAR-1IN DIV-145,UNIT-32,ZONE 11",Own Sources,11,2016-17,2016-17 NL/2016-17/0723,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,436000,"IMPROVEMENT TO SIDE-DRAIN AT KRISHNA NAGAR 4TH STRREET-2(SRIDEVI SCHOOL) IN DIV-145, UNIT-33, ZONE-11,",Own Sources,11,2016-17,2018-19 NL/2016-17/0761,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,349000,"IMPROVEMENT TO SIDE DRAIN AT SENTHAMIL NAGAR MAIN ROAD,NERKUNDRAM IN DN-145,U-33,Z-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/0814,Buildings,Completed,NL-VALASARAVAKKAM,145,499900,"IMPROVEMENT AND RENOUATION WORK FOR DIVISION OFFICE 145,UNIT-33,ZONE-11",Own Sources,11,2016-17,2018-19 NL/2016-17/12729,Buildings,Completed,NL-VALASARAVAKKAM,145,934000,Contruction Bin platform at Various street in Unit-33 in Zone-11,Own Sources,11,2016-17,2017-18 NL/2016-17/17313,Roads,Completed,NL-VALASARAVAKKAM,145,2900000,"Attenting BT patch work at Madha koil street,Reddy Street,Dayasathan street,N.T.Patel Road,Moogmbagai nagar,Perumal koil main road, Sakthi nagar c block 23th street,Thiruvalluvar street,karunigar street damaged due to varadah cyclone in DIV-145,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/18525,Buildings,Completed,NL-VALASARAVAKKAM,145,2422000,"Construction of Compost Yard in Burial Ground at Valliammai Nagar in Dn - 145, U - 33, Z - XI",Grants,11,2016-17,2019-20 NL/2016-17/1906,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,499000,"IMPROVEMENT WORK IN SIDE DRAIN AT MANDAVELI 1ST STREET-1 ,IN DIV-145,UNIT-33,ZONE-11",Own Sources,11,2016-17,2017-18 NL/2016-17/1907,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,499900,"IMPROVEMENT IN SIDE DRAIN AT NERKUNDRAM -MANDHAVELI 1st STREET-2 IN DIV 145,UNIT-33,ZONE-11",Own Sources,11,2016-17,2018-19 NL/2016-17/2069,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,499000,"IMPROVEMENT WORK IN CULVERT AT NEW COLONY -PERUMAL KOVIL STREET,IN DIV145,UNIT-33,ZONE-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/2235,Roads,Completed,NL-VALASARAVAKKAM,145,499000,"IMPROVEMENT WORK ON CONCRETE ROAD AT NERKUNDRAM KUMUDAVALLI AVENUE & BALVADI 2ND,3RD AND 4 TH STREET PVC PIPE LAYING IN DIV-145,UNIT-33,ZONE-11",Own Sources,11,2016-17,2018-19 NL/2016-17/4033,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,503000,"Desilting Side drain at various street (Part-1) in DN-145,Un-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/4300,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,496000,"Desilting Side drain at various street (Part-2) in DN-145,Un-33,Z-11,",Own Sources,11,2016-17,2018-19 NL/2016-17/5431,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,995000,"Desilting of Virugambakkam Canal (Reach-1) in Dn 145, Unit-33, Zone -11",Own Sources,11,2016-17,2017-18 NL/2016-17/5463,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,998000,"Desilting of Virugambakkam Canal (Reach-2) in DN 145, Unit-33, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/8021,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,980000,"Improvement to Side Drain at Sakthi Nagar C Block 20th Street in Dn 145, Unit 33, Zone 11",Own Sources,11,2016-17,2018-19 L/2016-17/14671,Electrical,Completed,L-Electrical,146,199000,"1165 Nos Lamp Post Painting And 1268 Nos Lamp PostNumbering (6 mtr Lamp Post with 1mtr Stright bracket and 1064 Nos & 6 mtr Lamp Post with Single Arch bracket 38 Nos & 8 mtr Lamp Post with Double Arch bracket 47 Nos and 8 mtr Lamp Post with Trible Arch bracket 5 Nos ) at Various Places in Division 143,144,145,146,147,148,150,151,153 TO 155 in Zone XI",Own Sources,11,2016-17,2017-18 NL/2016-17/10222,Roads,Completed,NL-VALASARAVAKKAM,146,2638000,"Forming the BT Road at Ganapathy Nagar 2nd street in Dn-146, UNit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/1045,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,996000,"Improvements Flood Damage Side Drain at K.K. Salai Reach -1 Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1046,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,996000,"Improvements Flood Damage Side Drain at K.K. Salai Reach -2 Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1047,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,749000,"Improvements Flood Damage Side Drain at K.K. Salai Reach -3 Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1051,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,996000,"Improvements Flood Damage Side Drain at Ramadoss Street Reach -1 Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2018-19 NL/2016-17/1052,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,996000,"Improvements Flood Damage Side Drain at Ramadoss Street Reach -2 Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1054,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,335000,"Improvements Flood Damage Side Drain at Ramadoss Street Reach- 3 Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1068,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,967000,"Improvements Flood Damage Side Drain at Jeeva Street and Muthumariamman Koil Street Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1073,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,986000,"Improvements Flood Damage Side Drain at Kamaraj Street and Selva Vinayagar Koil 5th Street Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1076,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,871000,"Improvements Flood Damage Side Drain at Balaraman Street Reach -1 Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1082,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,942000,"Improvements Flood Damage Side Drain at Bharathidhasan 11th Street Dn-146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/10888,Roads,Completed,NL-VALASARAVAKKAM,146,998000,Laying Thermo Plastic and RPM various street in division-146 in unit - 32 in Zone - XI,Own Sources,11,2016-17,2017-18 NL/2016-17/1109,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,407000,"IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS STREETS IN DN-146, UNIT-32, ZONE-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/1111,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,121000,"ATTENDING PATCHWORK USING WET MIX MACADAM AT VARIOUS STREETS IN DN-146, UNIT-32, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/1235,Buildings,Completed,NL-VALASARAVAKKAM,146,986000,"CONSTRUCTION OF 16TH DAY CERMANY HALL AT DHANALAKSHMI NAGAR IN DN-146, U-32, ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/1236,Buildings,Completed,NL-VALASARAVAKKAM,146,976000,"CONSTRUCTION OF 16TH DAY CERMANY HALL AT BALARAMAN STREET IN DN-146, U-32, ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/1237,Buildings,Completed,NL-VALASARAVAKKAM,146,980000,"CONSTRUCTION OF 16TH DAY CERMANY HALL AT GANAPATHY NAGAR IN DN-146, U-32, ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/1449,Parks,Completed,NL-VALASARAVAKKAM,146,967000,"PLANTING OF TREES AT VARIOUS LOCATIONS IN DN146,U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/19280,Roads,Completed,NL-VALASARAVAKKAM,146,1357000,"Forming the BT road at Balaraman Street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/3035,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,995000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-146, UNIT-32, ZONE-XI",Own Sources,11,2016-17,2020-21 NL/2016-17/5156,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,964000,"Desilting of Canal at Vanagaram at Service Road (Reach -1) in Dn 146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/5157,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,991000,"Desilting of Canal at Vanagaram at Service Road (Reach -2) in Dn 146, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/9797,Roads,Completed,NL-VALASARAVAKKAM,146,2951000,"Forming the BT road at Metro Nagar 1st cross to 3rd Cross street, Metro Nagar 7th Avenue From Metro nagar 6th avenue to metro nagar 2nd cross street, Metro nagar 7th avenue from metro nagar 2nd cross street to metro nagar 3rd cross street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/9798,Roads,Completed,NL-VALASARAVAKKAM,146,1626000,"Forming the BT road at Dhanalakshmi nagar main road From Vanagaram union road to Dhanalakshmi nagar 8th street and Dhanalakshmi nagar main road from Dhanalakshmi nagar 8th street to 3rd street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9803,Roads,Completed,NL-VALASARAVAKKAM,146,4146000,"Forming the BT road at MGR Street (Bharathidasan nagar) and K.K. Salai in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/9804,Roads,Completed,NL-VALASARAVAKKAM,146,2046000,"Forming the BT road at MGR Street (Bhakiyalakshmi Nagar) and Gangaiamman nagar 10th street 1st to 3rd cross streets in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9805,Roads,Completed,NL-VALASARAVAKKAM,146,1901000,"Forming the BT road at Dhanalakshmi Nagar 8th street 1st to 3rd cross streets and Balamurugan Nagar Lane in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9807,Roads,Completed,NL-VALASARAVAKKAM,146,2956000,"Forming the BT road at Kamaraj Street, Anna Street, Annai Indira Gandhi street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9832,Roads,Completed,NL-VALASARAVAKKAM,146,2649000,"Forming the BT road at Balaraman Street and Ganapathy nagar 3rd street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9835,Roads,Completed,NL-VALASARAVAKKAM,146,2638000,"Forming the BT road at Ramadoss Street and Periyar Street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 L/2016-17/18123,Electrical,Completed,L-Electrical,147,1017000,"Restoration of Damaged posts in various locations in Dn-143 to 155 in Zone-XI,due to Vardha cyclone effect on 12-12-16 .",Own Sources,11,2016-17,2017-18 NL/2016-17/0727,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,997000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-147, U-32,Z-XI.",Own Sources,11,2016-17,2020-21 NL/2016-17/0869,Roads,Completed,NL-VALASARAVAKKAM,147,976000,"Laying the Cement Concrete Roads at Ganagaiamman koil street (from perumal koil street to ganagaiamman koil) in Division 147, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/0873,Roads,Completed,NL-VALASARAVAKKAM,147,976000,"Laying the Cement Concrete Roads at Ganagaiamman koil street (from ganagaiamman koil to near MLA office) in Division 147, Unit 32, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/0988,Buildings,Completed,NL-VALASARAVAKKAM,147,919000,"PROVIDING SHED AND OTHER IMPROVEMENTS TO AMMA KUDINEER STATION IN DN147,U32,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/10217,Roads,Completed,NL-VALASARAVAKKAM,147,2736000,"Forming the BT road at Janaki nagar 1st main road, Vetri Vinayagar street, Gandhi street and Pillaiyar koil street in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/13627,Buildings,Completed,NL-VALASARAVAKKAM,147,500000,"MAINTENANCE WORKS TO BE CARRIED OUT BY ATTENDING CC PATCHES AT VINAYAGAR KOIL STREET,PAINTING THE WALL AT AALAPAKKAM MAIN ROAD,DISMANTLING RCC SLAB AT SRI DEVI NAGAR,REPAIRS TO MOTORS AND SUPPLY OF FURNITURES IN DIVISION OFFICE,ATTENDING REPAIRS TO DEWATERING STATION AT SRI KRISHNA NAGAR AND PROVIDING NAME BOARDS AT GCC LIMITS IN DN.147, U32, Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/1608,Parks,Completed,NL-VALASARAVAKKAM,147,996000,"IMPROVEMENTS TO PARK AT PALLAVAN NAGAR IN DN - 147, UNIT - 32, ZONE - 11.",Own Sources,11,2016-17,2018-19 NL/2016-17/17995,Roads,Completed,NL-VALASARAVAKKAM,147,916000,"Forming the BT road at Seemathamman Nagar main road Reach-II in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/18526,Buildings,Completed,NL-VALASARAVAKKAM,147,2229000,"Proposed Compost Yard of 1.5 MTPD at Allapakkam main road Burial ground in Div-147, U-34, Z-11.",Grants,11,2016-17,2018-19 NL/2016-17/3726,Buildings,Completed,NL-VALASARAVAKKAM,147,500000,"REPAIRS AND IMPROVEMENTS TO PARKS,SCHOOLS AND STORM WATER DRAIN IN DN147,U32,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/4240,Culvert,Completed,NL-VALASARAVAKKAM,147,994000,"Dismantling and Reconstruction of side drain at Pump room pattai and Meenachi Street culvert in Dn-147, Unit-32, Zone-XI",Own Sources,11,2016-17,2018-19 NL/2016-17/4649,Buildings,Completed,NL-VALASARAVAKKAM,147,999000,"IMPROVEMENTS TO DIVISION OFFICE-147 AT GANGAI AMMAN KOIL STREET IN DN147,U32,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/4671,Buildings,Completed,NL-VALASARAVAKKAM,147,775000,"IMPROVEMENTS TO DRAINAGE, WATER SUPPLY AND OTHER FACILITIES TO DIVISION OFFICE-147 IN DN147,U32,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/4894,Buildings,Completed,NL-VALASARAVAKKAM,147,999000,"PROVIDING SHED,COLOUR WASHING AND OTHER IMPROVEMENTS TO DIVISION OFFICE-147 IN DN147,U32,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/9479,Roads,Completed,NL-VALASARAVAKKAM,147,724000,"Relaying of BT road at Pillaiyar Koil Street in Dn-147, Unit-32, Zone-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9838,Roads,Completed,NL-VALASARAVAKKAM,147,2974000,"Forming the BT road at Mettukuppam Gangaiamman koil street, Mulaimsingh Yadhav Street and Janaki nagar 5th street in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/9841,Roads,Completed,NL-VALASARAVAKKAM,147,2596000,"Forming the BT road at Chokkanathar 1st Street , Chokkanathar 2nd street and Thirumurugan Nagar Mullai Street in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9844,Roads,Completed,NL-VALASARAVAKKAM,147,2072000,"Forming the BT road at Thirumurugan Nagar 1st street, Seemathamman Nagar main road Reach-I in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2016-17 NL/2016-17/9848,Roads,Completed,NL-VALASARAVAKKAM,147,2533000,"Forming the BT road at Pallavan Nagar 6th Street, Pallavan Nagar 7th Street and Mettukuppam Main road Reach-I in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/9849,Roads,Completed,NL-VALASARAVAKKAM,147,3037000,"Forming the BT road at Mettukuppam Main Road Reach 2, D.K.Nagar Reach-2, Krishna Nagar 1st Street and Janaki Nagar 4th Street in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2016-17,2017-18 BR/2016-17/9632,Roads,Completed,BR-Bus Route Roads,148,3300000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improivement work at Jayram Nagar 1st Main road -Div 148,,Zone-10.",Grants,11,2016-17,2017-18 NL/2016-17/0803,Roads,Completed,NL-VALASARAVAKKAM,148,424000,"Forming the Road at Jayaram nagar 1st street in DIN-148,UN-33,Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/0874,Buildings,Completed,NL-VALASARAVAKKAM,148,995000,"CONSTRUCTION OF AMMA UNAVAGAM AT THANGAL KARAI MAIN ROAD IN DN -148 , U -33 , Z -11",Own Sources,11,2016-17,2018-19 NL/2016-17/0875,Buildings,Completed,NL-VALASARAVAKKAM,148,990000,"PROVIDING GALVANISED SHEET ROOFING ARRANGEMENTS AT AMMA UNAVAGAM AT THANGALKARAI MAIN ROAD IN DN-148, U- 33 , Z- 11 .",Own Sources,11,2016-17,2018-19 NL/2016-17/0876,Buildings,Completed,NL-VALASARAVAKKAM,148,975000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRENGEMENTS & OTHER IMPROVEMENT WORKS IN AMMA UNAVAGAM AT THANGALKARAI MAIN ROAD IN DIN-148,UN-33,Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/19432,Buildings,Completed,NL-VALASARAVAKKAM,148,389000,"Construction of toilet along with septic tank, water supply and drainage arrangements for anganvadi at Vanchinathan street in Div-148,U-33,Zn-11",Own Sources,11,2016-17,2017-18 NL/2016-17/2906,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,999000,"Desilting Side drain at Various street in DIN-148,UN-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/4589,Buildings,Completed,NL-VALASARAVAKKAM,148,999000,"Construction of New compound wall in school building (Councillor Fund )in DN-148,UN-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/5383,Roads,Completed,NL-VALASARAVAKKAM,148,999000,"Supplying and Fixing Street Name Board at Anbu Nagar, Balaji Nagar and various street (Councillor Fund) in DN-148,UN-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/5384,Roads,Completed,NL-VALASARAVAKKAM,148,999000,"Supplying and Fixing Street Name Board at Various street (Councillor Fund) in DN-148,UN-33,Z-11",Own Sources,11,2016-17,2017-18 L/2016-17/14672,Electrical,Completed,L-Electrical,149,199000,"1023 Nos Lamp Post Painting And Numbering (6 mtr Lamp Post with 1mtr Stright bracket and 448 Nos & 6 mtr Lamp Post with Single Arch bracket 459 Nos & 8 mtr Lamp Post with Single Arch bracket 17 Nos & 8 mtr Lamp Post with Double Arch bracket 71 Nos and 8 mtr Lamp Post with Trible Arch bracket 28 Nos ) at Various Places in Division 147,149,151 and 152 in Zone XI",Own Sources,11,2016-17,2017-18 NL/2016-17/10221,Roads,Completed,NL-VALASARAVAKKAM,149,886000,"Relaying the road at vanchinathan Street in Dn 149,U 3,Zn 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10224,Roads,Completed,NL-VALASARAVAKKAM,149,212000,"Relaying the BT road at Ramesh nagar 1st cross street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10235,Roads,Completed,NL-VALASARAVAKKAM,149,464000,"Relaying the BT road at Velan Nagar 7th street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10236,Roads,Completed,NL-VALASARAVAKKAM,149,309000,"Relaying the BT road at East kamakoti nagar 3rd cross street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10237,Roads,Completed,NL-VALASARAVAKKAM,149,174000,"Relaying the BT road at East Kamakoti Nagar 2nd street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10238,Roads,Completed,NL-VALASARAVAKKAM,149,290000,"Relaying the BT road at East Kamakoti Nagar 1st street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10239,Roads,Completed,NL-VALASARAVAKKAM,149,503000,"Relaying the BT road at East Kamakoti Nagar main road in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10242,Roads,Completed,NL-VALASARAVAKKAM,149,1817000,"Relaying the BT road at Lakshmi Nagar 3rd Main Road in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10245,Roads,Completed,NL-VALASARAVAKKAM,149,1308000,"Relaying the BT road at Radha nagar 2nd street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10246,Roads,Completed,NL-VALASARAVAKKAM,149,333000,"Relaying the BT road at Ramesh nagar 4th cross street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10247,Roads,Completed,NL-VALASARAVAKKAM,149,303000,"Relaying the BT road at Ramesh nagar 3rd cross street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10248,Roads,Completed,NL-VALASARAVAKKAM,149,363000,"Relaying the BT road at Ramesh nagar 2nd cross street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10249,Roads,Completed,NL-VALASARAVAKKAM,149,1396000,"Relaying the BT road at Thirumalai Nagar Main Road in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10250,Roads,Completed,NL-VALASARAVAKKAM,149,683000,"Relaying the BT road at Neithal Street in Div-149,U-33,Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/13376,Roads,Completed,NL-VALASARAVAKKAM,149,910000,"Attenting BT patch work at Ramakrishna Nagar damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/13377,Roads,Completed,NL-VALASARAVAKKAM,149,874000,"Attenting Cement Concrete patch work at various street due to Varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/13527,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,802000,"Improvement storm water drain at various streets damaged due to Varadah Cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/15203,Buildings,Completed,NL-VALASARAVAKKAM,149,998000,"Repairs to chimney,blower,furnace,trolley,burner set and gas pipe line arrangement in Brindavan Nagar Burial Ground in Dn-149, U-33, Z-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/15438,Buildings,Completed,NL-VALASARAVAKKAM,149,71400,"Repairs to Oiil Engine Motor Pump sets in Various HP,S to Utilized in North East Monsoon in Div-149,U-33,Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/15440,Buildings,Completed,NL-VALASARAVAKKAM,149,92000,"IMPROVEMENTS TO WATER SUPPLY AND OTHER IMPROVEMENTS TO BRINDHAVAN NAGAR BURIAL GROUND,RADHAKRISHNAN PARK,REPAIRS TO SWD AT THIRUVALLUVAR STREET IN DIV-149,UNIT-33,ZONE-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15441,Buildings,Completed,NL-VALASARAVAKKAM,149,345000,"IMPROVEMENTS TO AEE OFFICE IN FRIST FLOOR AT DIVISION OFFICE IN DIV-149,UNIT-33,ZONE-11",Own Sources,11,2016-17,2018-19 NL/2016-17/16034,Footpath,Completed,NL-VALASARAVAKKAM,149,920000,"Improvements Foot path at Various park in damaged due to varadha cycolone Div-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16044,Playfields,Completed,NL-VALASARAVAKKAM,149,550000,"Repairs to water supply arrangements and Repairs to Play appratus in Div-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16098,Buildings,Completed,NL-VALASARAVAKKAM,149,1330000,"Improvements to Compound Wall in Brinavan Nagar Burial Ground in damaged due to varadha cycolone DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16202,Footpath,Completed,NL-VALASARAVAKKAM,149,920000,"Improvement to Foot path Brindvan Nagar Burial ground damaged due to varadha cycolne in Div-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16580,Roads,Completed,NL-VALASARAVAKKAM,149,910000,"Attenting BT patch work at Alwarthirunagar Nagar damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16583,Roads,Completed,NL-VALASARAVAKKAM,149,910000,"Attenting BT patch work at Lakshmi Nagar damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16588,Roads,Completed,NL-VALASARAVAKKAM,149,910000,"Attenting BT patch work at Fathima Nagar(dr damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16590,Roads,Completed,NL-VALASARAVAKKAM,149,910000,"Attenting BT patch work at AKR Nagar damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17066,Roads,Completed,NL-VALASARAVAKKAM,149,510000,"Repairs and maintananace of street name board due to vardha cyclone in Rama Krishna Nagar,Alwarthirunagar in DN-149, UNIT-33 ,ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/17075,Roads,Completed,NL-VALASARAVAKKAM,149,510000,"Repairs and maintananace of street name board due to vardha cyclone in SBS Colony,Lakshmi Nagar,AKR Nagar,Thirupathi Nagar in DN-149, UNIT-33 ,ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/17236,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Kamakodi Nagar Main road damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17237,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Kamachi Nagar Main road damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17238,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at West Kamakodi Nagar damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17239,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Kanakathara Nagar Main road damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17240,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Thilagar street damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17241,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Viyasar street damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17242,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Radha Nagar Main road damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17243,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Radha Nagar 1st street damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17244,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at C.V.Raman Street damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17245,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at B.V.R Nagar Main road damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17246,Roads,Completed,NL-VALASARAVAKKAM,149,998000,"Attenting BT patch work at Vijaya Nagar damaged due to varadah cyclone in DIV-149,U-33,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/17472,Parks,Completed,NL-VALASARAVAKKAM,149,937000,"Providing Greenary to Brindhavan Nagar Park near Burial Ground damaged due to Varadah Cyclone in Dn - 149, U - 33, Z - XI",Own Sources,11,2016-17,2017-18 NL/2016-17/17624,Buildings,Completed,NL-VALASARAVAKKAM,149,259000,"Improvement to CI office in Ground Floor, Repairs to SWD and other Improvements works to in Div-149, Unit-33, Zone-11",Own Sources,11,2016-17,2018-19 NL/2016-17/19022,Buildings,Completed,NL-VALASARAVAKKAM,149,305000,"Construction of toiled and water arrangement at Gangai amman Koil street in Div-149,U-33,Zn-11",Own Sources,11,2016-17,2017-18 NL/2016-17/3365,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,967000,"Desilting of Storm Water Drain and Side Drain at various street in Division 149, Unit 33, Zone-11",Own Sources,11,2016-17,2017-18 NL/2016-17/3728,Buildings,Completed,NL-VALASARAVAKKAM,149,500000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAINS,UNIT OFFICE, PARKS AND SCHOOLS IN DN149,U33,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/6188,Buildings,Completed,NL-VALASARAVAKKAM,149,996000,"CONSTRUCTION OF AMMA UNAVAGAM AT SAMBANTHAM NAGAR MAIN ROAD IN DN 149, UNIT- 33, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/6192,Buildings,Completed,NL-VALASARAVAKKAM,149,932000,"CONSTRUCTION OF AMMA UNAVAGAM ROOFING AND FALSE CEILING WORK AT SAMBANTHAM NAGAR MAIN ROAD IN DN-149, UNIT- 33, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/6193,Buildings,Completed,NL-VALASARAVAKKAM,149,932000,"CONSTRUCTION OF AMMA UNAVAGAM ELECTRICAL AND PLUMBING WORK AT SAMBANTHAM NAGAR MAIN ROAD IN DN 149, UNIT- 33, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/6383,Buildings,Completed,NL-VALASARAVAKKAM,149,274000,"Demolition of shopping Complex at Chinthamani vinayagar koil street in Div-149, Unit -33, Zone-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/7017,Bridges,Completed,NL-VALASARAVAKKAM,149,739000,"CONSTRUCTION OF AMMA UNAVAGAM FLOORING AND PAINTING WORK AT SAMBANTHAM NAGAR MAIN ROAD IN DN 149, UNIT- 33, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/8197,Buildings,Completed,NL-VALASARAVAKKAM,149,356000,"Construction of compound wall of Division-149 Office at Chinthamani vinayagar koil street Div-149, Unit -33, Zone-XI",Own Sources,11,2016-17,2017-18 L/2016-17/13922,Electrical,Completed,L-Electrical,150,4277500,"PROVISION OF 44 NOS OF 6 MTR G.I HOT DIP ZINC GALVANISING LAMP POST WITH DOUBLE ARCH BRACKET WITH 120W - 150W LED FITTINGS AT PORUR OVER BRIDGE IN DIVISION 150,ZONE-XI.",Deposit Works,11,2016-17,2018-19 NL/2016-17/15904,Roads,Completed,NL-VALASARAVAKKAM,150,214000,"STRENGHING AND RELAYING OF BT ROAD AT DOSS 4TH STREET STREET IN DIV - 150, UNIT - 34, ZONE - 11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/15911,Roads,Completed,NL-VALASARAVAKKAM,150,319000,"STRENGHING AND RELAYING OF BT ROAD AT BUDHAR COLONY 1ST STREET STREET IN DIV - 150, UNIT - 34, ZONE - 11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/15913,Roads,Completed,NL-VALASARAVAKKAM,150,215000,"STRENGHING AND RELAYING OF BT ROAD AT MAHALAKSHMI 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/16010,Parks,Completed,NL-VALASARAVAKKAM,150,891000,"IMPROVEMENTS WORK AT PONNI NAGAR PONNI AMMAN KOIL PARK IN DIV-150,U-34,Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16011,Parks,Completed,NL-VALASARAVAKKAM,150,479000,"IMPROVEMENT WORK AT MARUTHI NAGAR PHASE - 3 1ST MAIN ROAD PARK AT DIV - 150, U - 34, Z - 11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16017,Parks,Completed,NL-VALASARAVAKKAM,150,584000,"IMPROVEMENTWORK AT MARUTHI NAGAR PHASE I, BHARATHIYAR STREET IN DN. 150, U 34, ZONE XI",Own Sources,11,2016-17,2017-18 NL/2016-17/16028,Parks,Completed,NL-VALASARAVAKKAM,150,599000,"IMPROVEMENTWORK AT PARASNATH NAGAR PARK IN DN. 150, U 34, ZONE XI",Own Sources,11,2016-17,2017-18 NL/2016-17/16046,Parks,Completed,NL-VALASARAVAKKAM,150,99400,"IMPROVEMENT WORK AT PARK AND PLAY GROUND AT RAJESWARI NAGAR 2ND STREET IN DN.150, U-34, Z-XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/17803,Buildings,Completed,NL-VALASARAVAKKAM,150,1379000,"PROPOSED COMPOST YARD AT GANDHI NAGAR BURIAL GROUND IN DIV - 150, U - 34, ZONE -11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/2304,Roads,Completed,NL-VALASARAVAKKAM,150,248000,"STRENGTHING AND RELAYING OF BT ROAD AT THUNDALAM ANNA NAGAR DESIGAN STREET IN DV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/2306,Roads,Completed,NL-VALASARAVAKKAM,150,340000,"STRENGTHING AND RELAYING OF BT ROAD AT THUNDALAM ANNA NAGAR AMBEDKAR STREET IN DV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/3075,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,990000,"Desilting of Strom water drain at Arunachalam Nagar, Ponni Nagar, Viswanathan Nagar, Samayapuram, Rajeshwari Nagar, Mothi Nagar, Moorthi Nagar and Chettiyaragaram all streets in Dn.150, U 34 Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/3296,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,989000,"DESILTING OF STORM WATER DRAIN AT BYPASS SERVICE ROAD (FROM MOUNT POONAMALLEE ROAD TO VANAGARAM POONAMALLEE HIGH ROAD) TWO SIDES AND ARCOT ROAD (FROM RAJESHWARI NAGAR TO A1 MUTTON STALL) IN DN 150, U - 34, Z XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/6748,Roads,Completed,NL-VALASARAVAKKAM,150,665000,"Strengthing and Realaying of BT Road at Sri Ram Nagar Main Road in Div - 150, Unit - 34, Zone - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6755,Roads,Completed,NL-VALASARAVAKKAM,150,359000,"Strengthing and Realaying of BT Road at Sri Ram Nagar 3rd Street in Div - 150, Unit - 34, Zone - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6761,Roads,Completed,NL-VALASARAVAKKAM,150,359000,"Strengthing and Realaying of BT Road at Sri Ram Nagar 2nd Street in Div - 150, Unit - 34, Zone - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6762,Roads,Completed,NL-VALASARAVAKKAM,150,306000,"Strengthing and Realaying of BT Road at Sivabootham Raja Naiker Street in Div - 150, Unit - 34, Zone - 11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/6794,Roads,Completed,NL-VALASARAVAKKAM,150,492000,"STRENGTHING AND RELAYING OF BT ROAD AT PONNI NAGAR KURINJI STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6796,Roads,Completed,NL-VALASARAVAKKAM,150,534000,"STRENGTHING AND RELAYING OF BT ROAD AT KARAMBAKKAM K.K.R STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6798,Roads,Completed,NL-VALASARAVAKKAM,150,356000,"STRENGTHING AND RELAYING OF BT ROAD AT SIVABOOTHAM MEDU PILLAIYAR KOIL 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6799,Roads,Completed,NL-VALASARAVAKKAM,150,820000,"STRENGTHING AND RELAYING OF BT ROAD AT SIVABOOTHAM MEDU LAKSHMI NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6800,Roads,Completed,NL-VALASARAVAKKAM,150,433000,"STRENGTHING AND RELAYING OF BT ROAD AT SIVABOOTHAM MEDU LAKSHMI NAGAR 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6801,Roads,Completed,NL-VALASARAVAKKAM,150,433000,"STRENGTHING AND RELAYING OF BT ROAD AT SIVABOOTHAM MEDU LAKSHMI NAGAR 2ND STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6803,Roads,Completed,NL-VALASARAVAKKAM,150,565000,"STRENGTHING AND RELAYING OF BT ROAD AT D PONNI NAGAR VIVEKANANTH STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6804,Roads,Completed,NL-VALASARAVAKKAM,150,213000,"STRENGTHING AND RELAYING OF BT ROAD AT PONNI NAGAR VALLALAR STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6805,Roads,Completed,NL-VALASARAVAKKAM,150,770000,"STRENGTHING AND RELAYING OF BT ROAD AT PONNI NAGAR VOC STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6806,Roads,Completed,NL-VALASARAVAKKAM,150,306000,"STRENGTHING AND RELAYING OF BT ROAD AT ELUPIDARAI KOIL STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/6807,Roads,Completed,NL-VALASARAVAKKAM,150,248000,"STRENGTHING AND RELAYING OF BT ROAD AT ELUPIDARAI KOIL CROSS STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6960,Roads,Completed,NL-VALASARAVAKKAM,150,514000,"STRENGTHING AND RELAYING OF BT ROAD AT Thundalam T.V.K. Nagar Perumal Koil Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/6961,Roads,Completed,NL-VALASARAVAKKAM,150,316000,"STRENGTHING AND RELAYING OF BT ROAD AT Thundalam T.V.K. Nagar Perumal Koil 3rd Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6962,Roads,Completed,NL-VALASARAVAKKAM,150,316000,"STRENGTHING AND RELAYING OF BT ROAD AT Thundalam T.V.K. Nagar Perumal Koil 2nd Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6963,Roads,Completed,NL-VALASARAVAKKAM,150,201000,"STRENGTHING AND RELAYING OF BT ROAD AT Thundalam T.V.K. Nagar Perumal Koil 1st Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6964,Roads,Completed,NL-VALASARAVAKKAM,150,731000,"STRENGTHING AND RELAYING OF BT ROAD AT S.S. Nagar Main Road IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6965,Roads,Completed,NL-VALASARAVAKKAM,150,334000,"STRENGTHING AND RELAYING OF BT ROAD AT S.S. Nagar 3rd Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6966,Roads,Completed,NL-VALASARAVAKKAM,150,97000,"STRENGTHING AND RELAYING OF BT ROAD AT S.S. Nagar 2nd Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6967,Roads,Completed,NL-VALASARAVAKKAM,150,93000,"STRENGTHING AND RELAYING OF BT ROAD AT S.S. Nagar 1st Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6968,Roads,Completed,NL-VALASARAVAKKAM,150,1048000,"STRENGTHING AND RELAYING OF BT ROAD AT Rajeshwarai Nagar Annex IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6969,Roads,Completed,NL-VALASARAVAKKAM,150,359000,"STRENGTHING AND RELAYING OF BT ROAD AT Ponni Nagar Senkuttuvan Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6974,Roads,Completed,NL-VALASARAVAKKAM,150,515000,"STRENGTHING AND RELAYING OF BT ROAD AT BUDHAR COLONY MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6975,Roads,Completed,NL-VALASARAVAKKAM,150,687000,"STRENGTHING AND RELAYING OF BT ROAD AT BUDHAR COLONY 3RD STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/6976,Roads,Completed,NL-VALASARAVAKKAM,150,278000,"STRENGTHING AND RELAYING OF BT ROAD AT BUDHAR COLONY 2ND STREETIN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6977,Roads,Completed,NL-VALASARAVAKKAM,150,514000,"STRENGTHING AND RELAYING OF BT ROAD AT THUNDALAM ANNA NAGAR ERIKARI Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6978,Roads,Completed,NL-VALASARAVAKKAM,150,514000,"STRENGTHING AND RELAYING OF BT ROAD ATTHUNDALAM ANNA NAGAR MAHATHMA GANDHI Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6979,Roads,Completed,NL-VALASARAVAKKAM,150,155000,"STRENGTHING AND RELAYING OF BT ROAD ATTHUNDALAM ANNA NAGAR NEHRU 2ND STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6980,Roads,Completed,NL-VALASARAVAKKAM,150,155000,"STRENGTHING AND RELAYING OF BT ROAD AT KTHUNDALAM ANNA NAGAR NEHRU 1ST Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6981,Roads,Completed,NL-VALASARAVAKKAM,150,480000,"STRENGTHING AND RELAYING OF BT ROAD ATTHUNDALAM ANNA NAGAR NEHRU STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6983,Roads,Completed,NL-VALASARAVAKKAM,150,158000,"STRENGTHING AND RELAYING OF BT ROAD AT THUNDALAM ANNA NAGAR SANNATHI CROSS STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/6984,Roads,Completed,NL-VALASARAVAKKAM,150,379000,"STRENGTHING AND RELAYING OF BT ROAD AT THUNDALAM ANNA NAGAR SENTHAMIZH STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/6986,Roads,Completed,NL-VALASARAVAKKAM,150,353000,"STRENGTHING AND RELAYING OF BT ROAD AT SIVABOOTHAM MEDU PILLIYAR KOIL STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/6987,Roads,Completed,NL-VALASARAVAKKAM,150,501000,"STRENGTHING AND RELAYING OF BT ROAD AT THUNDALAM ANNA NAGAR VIVEKANDAR STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7179,Roads,Completed,NL-VALASARAVAKKAM,150,204000,"STRENGTHING AND RELAYING OF BT ROAD AT Perumal Koil Ist Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7181,Roads,Completed,NL-VALASARAVAKKAM,150,204000,"STRENGTHING AND RELAYING OF BT ROAD AT Perumal Koil IInd Street STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7182,Roads,Completed,NL-VALASARAVAKKAM,150,223000,"STRENGTHING AND RELAYING OF BT ROAD AT Perumal Koil 3rd Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7184,Roads,Completed,NL-VALASARAVAKKAM,150,422000,"STRENGTHING AND RELAYING OF BT ROAD AT Samayapuram Nagar 6th Street PART IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7188,Roads,Completed,NL-VALASARAVAKKAM,150,204000,"STRENGTHING AND RELAYING OF BT ROAD AT Visvanathan 4th Cross Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7189,Roads,Completed,NL-VALASARAVAKKAM,150,246000,"STRENGTHING AND RELAYING OF BT ROAD AT Visvanathan 3rd Cross Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7191,Roads,Completed,NL-VALASARAVAKKAM,150,246000,"STRENGTHING AND RELAYING OF BT ROAD AT Visvanathan 1st Cross Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7217,Roads,Completed,NL-VALASARAVAKKAM,150,525000,"STRENGTHING AND RELAYING OF BT ROAD AT Thiruvenkadam 2nd Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7218,Roads,Completed,NL-VALASARAVAKKAM,150,418000,"STRENGTHING AND RELAYING OF BT ROAD AT Thiruvenkadam 1st Street IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7296,Roads,Completed,NL-VALASARAVAKKAM,150,657000,"STRENGTHING AND RELAYING OF BT ROAD AT Perumal Koil Main Road IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7316,Roads,Completed,NL-VALASARAVAKKAM,150,227000,"STRENGTHING AND RELAYING OF BT ROAD AT PONNAI NAGAR PARI STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7319,Roads,Completed,NL-VALASARAVAKKAM,150,220000,"STRENGTHING AND RELAYING OF BT ROAD AT PONNAI NAGAR NEITHAL STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7337,Roads,Completed,NL-VALASARAVAKKAM,150,1643000,"STRENGTHING AND RELAYING OF BT ROAD AT KOTHANDARAMAN NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7339,Roads,Completed,NL-VALASARAVAKKAM,150,551000,"STRENGTHING AND RELAYING OF BT ROAD AT KARAMBAKKAM MAHALAKSHMI NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7342,Roads,Completed,NL-VALASARAVAKKAM,150,719000,"STRENGTHING AND RELAYING OF BT ROAD AT KARAMBAKKAM BRAMIN STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7344,Roads,Completed,NL-VALASARAVAKKAM,150,1392000,"STRENGTHING AND RELAYING OF BT ROAD AT SIVABOOTHAM 1ST STREET EXTN IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7348,Roads,Completed,NL-VALASARAVAKKAM,150,348000,"STRENGTHING AND RELAYING OF BT ROAD AT PONNI NAGAR T.V.K STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7349,Roads,Completed,NL-VALASARAVAKKAM,150,306000,"STRENGTHING AND RELAYING OF BT ROAD AT PONNI NAGAR RAJARAJAN STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7355,Roads,Completed,NL-VALASARAVAKKAM,150,306000,"STRENGTHING AND RELAYING OF BT ROAD AT KAVERI NAGAR 3RD STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7356,Roads,Completed,NL-VALASARAVAKKAM,150,306000,"STRENGTHING AND RELAYING OF BT ROAD AT KAVERI NAGAR 2ND STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7357,Roads,Completed,NL-VALASARAVAKKAM,150,541000,"STRENGTHING AND RELAYING OF BT ROAD AT KANTHASAMI NAGAR KANTHA KANNAN STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7359,Roads,Completed,NL-VALASARAVAKKAM,150,817000,"STRENGTHING AND RELAYING OF BT ROAD AT KAMATCHI NAGAR BHARATHI SALAI IN DIV - 150, UNIT - 34, ZONE-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7361,Roads,Completed,NL-VALASARAVAKKAM,150,196000,"STRENGTHING AND RELAYING OF BT ROAD AT DEVI PARASAKTHI NAGAR 4TH STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7362,Roads,Completed,NL-VALASARAVAKKAM,150,207000,"STRENGTHING AND RELAYING OF BT ROAD AT DEVI NAGAR 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7384,Roads,Completed,NL-VALASARAVAKKAM,150,443000,"STRENGTHING AND RELAYING OF BT ROAD AT BDEVI PARASAKTHI NAGAR 3RD STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7385,Roads,Completed,NL-VALASARAVAKKAM,150,265000,"STRENGTHING AND RELAYING OF BT ROAD AT DEVI PARASAKTHI NAGAR 2ND STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7388,Roads,Completed,NL-VALASARAVAKKAM,150,920000,"STRENGTHING AND RELAYING OF BT ROAD AT DEVI NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/0937,Parks,Completed,NL-VALASARAVAKKAM,151,995000,"IMPROVEMENTS TO TCG PARK IN DN151,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/0993,Parks,Completed,NL-VALASARAVAKKAM,151,973000,"LAYING OF CEMENT CONCRETE TILES FOR PARKING AREA AT TCG PARK IN DN151,U34,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/0994,Parks,Completed,NL-VALASARAVAKKAM,151,479000,"LAYING GRANITE FLOORING FOR OPEN GYM AREA INSIDE TCG PARK IN DN151,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/10009,Roads,Completed,NL-VALASARAVAKKAM,151,359000,"Relaying Road with BMCM2 and BCCMP1 at Anna Salai & Chinna Porur Hospital Cross Street in Dn-151,U-34,Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10013,Roads,Completed,NL-VALASARAVAKKAM,151,948000,"Relaying Road with BMCM2 and BCCMP1 at Officers Colony Main Road & New Colony Main Road in Dn-151,U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10017,Roads,Completed,NL-VALASARAVAKKAM,151,839000,"Relaying Road with BMCM2 and BCCMP1 at St.John School Street & Pillaiyar Koil Street In Dn-151,U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/1145,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,851000,"IMPROVEMENT TO THE EXISTING SIDE DRAIN AT ELUMALAI STREET IN DN-151,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/11473,Buildings,Completed,NL-VALASARAVAKKAM,151,856000,"CONSTRUCTION OF AMMA RO PLANT AT HOSPITAL RAOD IN DIV-151, UNIT-34, ZONE-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/1154,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,729000,"IMPROVEMENT TO THE EXISTING SIDE DRAIN AT VELU STREET & VASUKI STREET IN DN-151,U-34,Z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/11552,Buildings,Completed,NL-VALASARAVAKKAM,151,996000,"Providing Plumbing and Roofing Arrangements in Amma RO Plant at Hospital Road In div-151, Unit-34, Zone-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/1259,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,697000,"IMPROVEMENT TO THE EXISTING SIDE DRAIN AT VAITHTHIYALINGAM STREET IN DN-151,U-34,Z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/12713,Buildings,Completed,NL-VALASARAVAKKAM,151,978600,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period at School Street in Dn - 151,Zone -11.",Own Sources,11,2016-17,2017-18 NL/2016-17/12717,Buildings,Completed,NL-VALASARAVAKKAM,151,998000,"Supply,Installation,Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at School Street in Dn-151,Zone-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/13291,Buildings,Completed,NL-VALASARAVAKKAM,151,733000,"Providing Electrical and Stainless Steel Arrangements in Amma RO Plant at Hospital Road In div-151, Unit-34, Zone-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/15928,Parks,Completed,NL-VALASARAVAKKAM,151,287000,"Repairs works to TCG Park at Mount Poonamallee Road in Dn-151,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/15938,Parks,Completed,NL-VALASARAVAKKAM,151,130000,"Repairs Work to Sabari Nagar Park at Sabari Nagar 5th Cross Street in Dn-151,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16214,Parks,Completed,NL-VALASARAVAKKAM,151,105000,"Repairs Work to Park at Lakshmi NagarExtn 5th Cross Street in Dn-151,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16591,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,1034000,"Restoration of Damaged SWD of Sabari ngr 1st & 4th , venkateswar avenue, Annai sathya ngr, Lakshmi ngr 5th Cross st, Anna salai and jawahar 3rd st during Varadha cyclone 2016 in Dn 151 U 34 Z 11",Own Sources,11,2016-17,2017-18 NL/2016-17/18152,Buildings,Completed,NL-VALASARAVAKKAM,151,2975000,"Proposed 2MTPD Compost Yard at School Road in Div-151, U-34, Z-11.",Grants,11,2016-17,2019-20 NL/2016-17/19023,Buildings,Completed,NL-VALASARAVAKKAM,151,1092000,"Construction of toiled and water arrangememt at Anjaneyar koil Street, School Street and bajanai Koil Street anganwadi in div-151,u-34,z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/19057,Buildings,Completed,NL-VALASARAVAKKAM,151,1436000,"Proposed to Compost Yard at Alappakkam Cross Street in Dn-151,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/3480,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,997000,"Desilting of Storm Water Drain & Side Drain at Various Streets In Dn-151,U-34,Z-11.",Own Sources,11,2016-17,2019-20 NL/2016-17/3721,Buildings,Completed,NL-VALASARAVAKKAM,151,500000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN, DIVISION OFFICE AND SCHOOL BUILDINGS IN DN151,U34,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/5024,Buildings,Completed,NL-VALASARAVAKKAM,151,999000,"IMPROVEMENTS TO THE COMPOST YARD SITUATED AT AALAPAKKAM MAIN ROAD IN DN151,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/7486,Roads,Completed,NL-VALASARAVAKKAM,151,1056000,"Relaying Road with BMCM2 and BCCMP1 at Anjaneyar Koil Street in Dn-151,U-34,Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/7825,Buildings,Completed,NL-VALASARAVAKKAM,151,483000,"Proposed demolition of dilapidated buildings of BHS quarters, ANM & CRI quarters, office building, siddha building, training centre, motor room and OHT inside the UPHC Campus at Hospital Road, Chinna Porur in Dn-151, U-34, Zone - XI.",Own Sources,11,2016-17,2019-20 NL/2016-17/8616,Buildings,Completed,NL-VALASARAVAKKAM,151,999000,"IMROVEMENTS TO ELECTRICAL CREMATORIUM SITUATED AT ARCOT ROAD IN DN151,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/8815,Buildings,Completed,NL-VALASARAVAKKAM,151,733000,"IMPROVEMENTS TO PRIMARY HEALTH CENTER SITUATED AT HOSPITAL ROAD IN DN151,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/9971,Roads,Completed,NL-VALASARAVAKKAM,151,859000,"Relaying Road with BMCM2 and BCCMP1 at Lakshmi Nagar Extn 1st Main Road & Anna Street in Dn-151,U-34,Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/0861,Electrical,Completed,NL-VALASARAVAKKAM,152,984000,"Providing pathway in front of Zonal Office-11 and forming zonal office drivers rest room at Arcot Road in Dn.152, U-33, Z-XI",Own Sources,11,2016-17,2016-17 NL/2016-17/0879,Buildings,Completed,NL-VALASARAVAKKAM,152,993000,"Construction of Lorry Water Washing Station at Arcot Road in Dn 152, Unit 33, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/0880,Buildings,Completed,NL-VALASARAVAKKAM,152,790000,"Formation of Zonal Officer Room (First Floor) in Zonal Office XI at Arcot Road in Dn 152, Unit 33, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/0881,Buildings,Completed,NL-VALASARAVAKKAM,152,514000,"Providing Electrical Arrangement Zonal Officer Room (First Floor) in Zonal Office XI at Arcot Road in Dn 152, Unit 33, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/0882,Buildings,Completed,NL-VALASARAVAKKAM,152,998000,"Improvement E selva and Public Relation Center at Arcot Road in Dn 152, Unit 33, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/0883,Buildings,Completed,NL-VALASARAVAKKAM,152,999000,"Providing Record Room (Second Floor) Zonal Office XI at Arcot Road in Dn 152, Unit 33, Zone 11",Own Sources,11,2016-17,2017-18 NL/2016-17/0938,Buildings,Completed,NL-VALASARAVAKKAM,152,997000,Providing Record room and other improvement works at Unit Audit Cell in zonal office 11 div 152 unit33 zone 11,Own Sources,11,2016-17,2017-18 NL/2016-17/0940,Buildings,Completed,NL-VALASARAVAKKAM,152,876000,"Providing Additional storage rack in record room and uac section at zonal office in div 152, unit33, zone XI",Own Sources,11,2016-17,2017-18 NL/2016-17/0995,Buildings,Completed,NL-VALASARAVAKKAM,152,375000,"PROVIDING RAIN WATER HARVESTING AT ZONAL OFFICE-XI IN DN152,U33,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/10208,Buildings,Completed,NL-VALASARAVAKKAM,152,324000,"Formation of AHO Room at Ground Floor in Arcot Road in Division - 152, Unit - 33 zone-11",Own Sources,11,2016-17,2017-18 NL/2016-17/1209,Buildings,Completed,NL-VALASARAVAKKAM,152,826000,"FACE LIFTING THE COMMON REST ROOM FOR MALE AT ZONAL OFFICE-11 IN DN152,U33,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/1210,Buildings,Completed,NL-VALASARAVAKKAM,152,577000,"FACE LIFTING THE COMMON REST ROOM FOR FEMALE AT ZONAL OFFICE-11 IN DN152,U33,Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/14439,Road Cut,Completed,NL-VALASARAVAKKAM,152,555000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BHARATHIYAR STREET IN DN152,U33,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/15442,Buildings,Completed,NL-VALASARAVAKKAM,152,95000,"IMPROVEMENTS AND PAINTING OF AEE S CABINS IN GROUND FLOOR ZONAL OFIICE IN DIV-152,U-33,Z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15443,Buildings,Completed,NL-VALASARAVAKKAM,152,87000,"IMPROVEMENTS TO WATER SUPPLY,DRAINAGE ARRANGEMENTS TO AMMA UNAVAGAM AND E- TOILET AT ZONAL OFFICE CAMPUS IN DIN152,U-33,Z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15444,Buildings,Completed,NL-VALASARAVAKKAM,152,94000,"IMPROVEMENTS TO DIVISION OFFICE AT CHOUTHRY NAGAR MAIN ROAD INSIDE THE PLAY GROUND N DIV-152,U-33,Z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15448,Buildings,Completed,NL-VALASARAVAKKAM,152,40300,"Repairs to Oiil Engine Motor Pump sets in Various HP,S to Utilized in North East Monsoon in Div-152 ,U-33,Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/15479,Roads,Completed,NL-VALASARAVAKKAM,152,3632000,"Relaying BT road at School Road,Kadmabadi Amman Kovil Main Road,Jai Nagar 6Th St,Jai Nagar 7Th St,Svs Nagar 2Nd St,Svs Nagar 3Rd St,Svs Nagar 4Th St,Azhagiri St,Madurai Meenakshi Nagar Main Road,VOC St in Dn-152, Unit - 33 in Zone - XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/15878,Parks,Completed,NL-VALASARAVAKKAM,152,106800,"Repair and maintenance of electrical items in playfield due to vardha cyclone at Bharathi Colony Play Ground in Division - 152, Unit - 33 in Zone - XI",Own Sources,11,2016-17,2017-18 NL/2016-17/16078,Parks,Completed,NL-VALASARAVAKKAM,152,106000,"Repair and maintenance of play apparatus due to vardha flood at Chowdry Nagar Play Ground in division - 152, unit -33 zone - XI",Own Sources,11,2016-17,2017-18 NL/2016-17/16079,Roads,Completed,NL-VALASARAVAKKAM,152,510000,"Repairs and maintananace of Zonal Office Board and street name board due to vardha cyclone in suresh nagar main road, om sakthi nagar, rajendran st, rajajai avenue, church st, kadambadi amman kovil st, chowdry nagar 9th st, chowdry nagar 10th st, chowdry nagar 6th st, chowdry nagar 11th st in DN-152, UNIT-33 ,ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/1620,Roads,Completed,NL-VALASARAVAKKAM,152,999000,"Supplying and fixing of street name board at Suresh Nagar Kanammal Nagar, Muthulakshmi St and Chowdry Nagar Other various Streets in DN-152, UNIT-33 ,ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/1621,Roads,Completed,NL-VALASARAVAKKAM,152,997000,"Supplying and fixing of street name board at OM Sakthi Nagar, Kariakal Ammaiyar St, Seyon St and Other Various Streets in DN-152, UNIT-33 ,ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/1623,Roads,Completed,NL-VALASARAVAKKAM,152,998000,"Supplying and fixing of street name board at Muthumariamman Koil Street, Kumaran Avenue, Bethiaya Nagar and Other various Streets in DN-152, UNIT-33 ,ZONE-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/17055,Buildings,Completed,NL-VALASARAVAKKAM,152,32000,Repairs and maintananace of Amma Unavagam due to vardha cyclone at arcot road div 152 unit 33 zone11,Own Sources,11,2016-17,2017-18 NL/2016-17/1878,Buildings,Completed,NL-VALASARAVAKKAM,152,349000,"IMPROVEMENTS TO WATER SUPPLY AND OTHER ARRANGEMENTS AT ZONAL OFFICE-XI IN DN-152, U-33, Z-11",Own Sources,11,2016-17,2016-17 NL/2016-17/3033,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,990000,"Desilting of Storm Water drain at various streets Anna St,Periyar St,Kalaingar St,P.N.Ramamurthy St,Dr.Ambedkar St,Kannamal St,Bethaniya Nagar,Majestic Colony 2nd Main Road,Chowdry Nagar Main Road,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 5th St,Chowdry Nagar 4th St,Chowdry Nagar 3rd St,Azhagiri St,Sarojini St,Singaravelan St,Kadambadi Amman Kovil St,Thiruvalluvar Salai,Thirvalluvar St,Alapakkam Main Road,Rajendran St,Krishnan Kovil St,Arumuga Nainar St,Chowdry Nagar 19th St,Thirumurugan St,Aringar Anna Avenue,Om Sakthi Nagar Main Road,Prakasam Salai,Rajaji avenue to sivan kovil temple in Dn-152, Unit - 33",Own Sources,11,2016-17,2017-18 NL/2016-17/4069,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,588000,"Improvement of strom water drain and Construction of Culvert at Alapakkam Main Road Reach - 1( 0mTO 60m) in Unit - 33, Division - 152, Zone - XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/6650,Buildings,Completed,NL-VALASARAVAKKAM,152,897000,Formation of Executive Engineer- II room in First Floor at zonal office div 152 unit 33 zone XI,Own Sources,11,2016-17,2017-18 NL/2016-17/6711,Buildings,Completed,NL-VALASARAVAKKAM,152,595000,Improvement of strom water drain at Alapakkam Road Reach - 2(60m to 133m) in unit - 33 dn - 152 in zone - 11,Own Sources,11,2016-17,2017-18 NL/2016-17/6712,Buildings,Completed,NL-VALASARAVAKKAM,152,558000,Providing Electrical arrangements to Executive Engineer - II at zonal office in div 152 unit 33 zoneXI,Own Sources,11,2016-17,2017-18 NL/2016-17/7453,Buildings,Completed,NL-VALASARAVAKKAM,152,599000,Improvement of strom water drain at Thiruvalluvar St Reach - 1 (0m to 74m) in unit - 33 dn - 152 in zone - 11,Own Sources,11,2016-17,2017-18 NL/2016-17/7454,Buildings,Completed,NL-VALASARAVAKKAM,152,586000,Improvement of strom water drain at Thiruvalluvar St Reach - 2 (74m to 146m) in unit - 33 dn - 152 in zone - 11,Own Sources,11,2016-17,2017-18 NL/2016-17/7918,Buildings,Completed,NL-VALASARAVAKKAM,152,849000,"Supplying and fixing of E-toilet 1nos Unit - 1 in Zonal Office Lorry Station in Unit - 33 Division - 152, in Zone - XI",Own Sources,11,2016-17,2017-18 NL/2016-17/0495,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,894000,"Providing Side Drain at Ramakrishna Nagar 6th Street in DN.153, U-34, Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/10037,Roads,Completed,NL-VALASARAVAKKAM,153,2980000,"Relaying Road with BMCM2 and BCCMP1 at Ramakrishna Nagar Main Road, Krishna Nagar Main Road, R.E.Nagar 5th Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10070,Roads,Completed,NL-VALASARAVAKKAM,153,3000000,"Relaying Road with BMCM2 and BCCMP1 at Wireless Station Road, Mangala Nagar 1st Main Road, Somasundaram 5th Avenue in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10073,Roads,Completed,NL-VALASARAVAKKAM,153,3000000,"Relaying Road with BMCM2 and BCCMP1 at Ramamoorthy Avenue Main Road, Mangala Nagar 7th Cross Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10074,Roads,Completed,NL-VALASARAVAKKAM,153,2830000,"Relaying Road with BMCM2 and BCCMP1 at Mangala Nagar 2nd Main Road, Mangala Nagar 6th Cross Street, Kamala Nagar Road, Ramakrishna Nagar 1st Avenue in Div153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10079,Roads,Completed,NL-VALASARAVAKKAM,153,2850000,"Relaying Road with BMCM2 and BCCMP1 at Ramakrishna Nagar 4th Street, Kurinchi Nagar Main Road, Kurinchi Nagar Rathi Street, Kaliyamman Koil 1st Street (West) in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10086,Roads,Completed,NL-VALASARAVAKKAM,153,2751000,"Relaying Road with BMCM2 and BCCMP1 at Eswaran Koil Main Road,Parvathi Avenue 1st Street, Parvathi Avenue 4th Street, Parvathi Avenue 5th Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10093,Roads,Completed,NL-VALASARAVAKKAM,153,2950000,"Relaying Road with BMCM2 and BCCMP1 at Mangala Nagar Road, Mangala Nagar 8th Cross Street, Mangala Nagar 9th Cross Street, Mangala Nagar 10th Cross Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10099,Roads,Completed,NL-VALASARAVAKKAM,153,3000000,"Relaying Road with BMCM2 and BCCMP1 at Sterling Avenue 2nd Street, Palayakara Street, Ambal Nagar Main Road, Sabari Nagar 5th Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10101,Roads,Completed,NL-VALASARAVAKKAM,153,3100000,"Relaying Road with BMCM2 and BCCMP1 at Subashree Nagar Main Road, R.E.Nagar Main Road, Sabari Nagar 1st Main Road in Div-153, u-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10105,Roads,Completed,NL-VALASARAVAKKAM,153,3400000,"Relaying Road with BMCM2 and BCCMP1 at Balamurugan Nagar 1st Street,Balamurugan Nagar 2nd Street, Santhosh Nagar Vaigai Street,Ramakrishna Nagar 3rd Street,krishna Nagar 1st Street,Suresh Nagar 4th Street in Div-153,U-34,Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10106,Roads,Completed,NL-VALASARAVAKKAM,153,3338000,"Relaying Road with BMCM2 and BCCMP1at M.S.Nagar Main Road,Eswaran Koil 1st Street,Kurunchi Nagar Malligai Street,Kaliyamman Koil 2nd Street(West), Krishna Nagar 2nd Street in Div-153,U-34,Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10109,Roads,Completed,NL-VALASARAVAKKAM,153,2890000,"Relaying Road with BMCM2 and BCCMP1 at Parvathi Avenue 6th Street, Udhaya Nagar 1st Street, Udhaya Nagar Extn Main Road, Ramasamy Nagar 1st Street, Ramasamy Nagar 2nd Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10111,Roads,Completed,NL-VALASARAVAKKAM,153,3000000,"Relaying Road with BMCM2 and BCCMP1 at Sabari Nagar 1st street, Ganesh Avenue 8th Street, Ganga Kaveri Street, Ganesh Avenue 9th Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10118,Roads,Completed,NL-VALASARAVAKKAM,153,3200000,"Relaying Road with BMCM2 and BCCMP1 Ramakrishna Nagar 6th Street, Ramasamy Nagar 3rd Street, Adhibagavan Nagar 2nd Street, Nakeeran Street, Vigneswara Nagar Cheran Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10120,Roads,Completed,NL-VALASARAVAKKAM,153,3100000,"Relaying Road with BMCM2 and BCCMP1 at Manikandan Street, Sterling Avenue Main Road, R.E.Nagar 9th Street, Ramasamy Nagar Main Road in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10125,Roads,Completed,NL-VALASARAVAKKAM,153,3000000,"Relaying Road with BMCM2 and BCCMP1 at Ekambaram Street, Suresh Nagar Main Road, Subasree Nagar 1st Main Road, Udaya Nagar 3rd Street in Div-153, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/16175,Parks,Completed,NL-VALASARAVAKKAM,153,155000,"Repairs Work to Kanniyappan Park at Kanniyappan Salai in Dn-153,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16176,Parks,Completed,NL-VALASARAVAKKAM,153,172000,"Repairs Work to Ramakrishna Park at Ramakrishna Nagar Main Road in Dn-153,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16177,Parks,Completed,NL-VALASARAVAKKAM,153,192000,"Repairs Work to Ramasamy Park at Ramasamy Nagar Main Road in Dn-153,U-34,Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16568,Roads,Completed,NL-VALASARAVAKKAM,153,2969000,"Restoration of Damaged roads of Mangala nagar 10th cross street 2nd lane, Ramakrishna Link road, Somasundaram 4th st, Ganesh Avenue 4th st, Rk nagar 3rd st 2nd lane, Chetty st, Subashree ngr 2nd main rd, sriram nagar 1st st during Varadha cyclone 2016 in Dn-153, U-34, Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16575,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,2549000,"Restoration of Damaged SWD of Mangala nagar 5th cross street, Ramakrishna Link road, Somasundaram 4th st, Jayabharathi ngr, Ganesh 5th avenue, Santhosh ngr Vaigai & Ganga st, Narayanan st, Suresh nagr 4th st, Sriram nagar 1st & 3rd st during Varadha cyclone 2016 in Dn-153, U-34, Z-11.",Own Sources,11,2016-17,2017-18 NL/2016-17/18538,Buildings,Completed,NL-VALASARAVAKKAM,153,495000,"Maintenance works carried out in Div -153 , Unit -34, Zone -11",Own Sources,11,2016-17,2018-19 NL/2016-17/2045,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,999000,"Desilting of Storm water drain at various streets (Ramakrishna Nagar, Melpallikuppam, Krishna Nagar, Balamurugan Nagar, Duraisamy Nagar, Jaya Bharathi Nagar, Vigneshwara Nagar, M.S.Nagar, Eswaran Koil Streets, Kaliamman Koil Streets, Balamurugan Koil Streets, Kungumam Nagar, Thiruveethi Amman Koil Streets, R.E..Nagar Streets) in Div-153, U-34, Z-11.",Own Sources,11,2016-17,2020-21 NL/2016-17/4409,Roads,Completed,NL-VALASARAVAKKAM,153,999000,"Providing, laying DBM 50 mm thick at Shakthi nagar main road in Dn-153, U-34, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/4410,Roads,Completed,NL-VALASARAVAKKAM,153,773000,"Providing, laying DBM 50 mm thick at Cholan street, Ganesh avenue 1st main road(Part) in Dn 153, U-34, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/5402,Buildings,Completed,NL-VALASARAVAKKAM,153,893000,"Construction of Amma Unavagam at Wireless Station Road in Dn-153, U-34, Zone- XI.",Own Sources,11,2016-17,2020-21 NL/2016-17/5406,Buildings,Completed,NL-VALASARAVAKKAM,153,714000,"Improvement to the Amma Unavagam at Wireless Station Road in Div-153, U-34, Z-11.",Own Sources,11,2016-17,2020-21 NL/2016-17/0421,Buildings,Completed,NL-VALASARAVAKKAM,154,650000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO 16TH DAY CEREMONY HALL AT KAMBAR STREET IN DN154,U34,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/0516,Road Cut,Completed,NL-VALASARAVAKKAM,154,997000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT STAR STREET,STAR 1ST AND 2ND CROSS STREETS IN DN154,U34,Z11.",Own Sources,11,2016-17,2016-17 NL/2016-17/10312,Roads,Completed,NL-VALASARAVAKKAM,154,2481000,"Relaying BT road at Anna Nagar Thangal Street in Dn-154, U-34, Z-11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10323,Roads,Completed,NL-VALASARAVAKKAM,154,2916000,"Relaying BT road at E.V.R 1st Periyar Street, Periyarst lane, Balambigai Nagar 5th Street, Periyar Street and Anandham nagar 2nd main road in Dn-154, U-34, Z-11",Loans And Grants,11,2016-17,2018-19 NL/2016-17/10330,Roads,Completed,NL-VALASARAVAKKAM,154,2100000,"Relaying BT road at Venugopal Street & Anandhamnagar 1st main road in Dn-154, U-34, Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10468,Roads,Completed,NL-VALASARAVAKKAM,154,2997000,"Relaying BT road at Kurinji nagar 1st main road Reach - II, Kurinji Nagar 9th Street & Shanthi Nagar Star Street in Dn-154, U-34, Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10486,Roads,Completed,NL-VALASARAVAKKAM,154,2959000,"Relaying BT road at Venkateswara nagar 10th street Reach II in Dn-154, U-34, Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/10491,Roads,Completed,NL-VALASARAVAKKAM,154,2761000,"Relaying BT road at Kurinji Nagar 1st Main Road Reach - I & Venkateswara nagar 10th street Reach III in Dn-154, U-34, Z-11",Loans And Grants,11,2016-17,2017-18 NL/2016-17/13451,Roads,Completed,NL-VALASARAVAKKAM,154,817500,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateshwara Nagar 7th street, G.S nagarnakkiran street & G.S Nagerkabilar street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13452,Roads,Completed,NL-VALASARAVAKKAM,154,659700,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at G.S Nagar manikavasagar street, Anandhamnagar 5th street & RB Sundharam street lane in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/13453,Roads,Completed,NL-VALASARAVAKKAM,154,869600,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at RB Sundharam street , N.S.K Street ,N.S.K Street 1st lane & N.S.K Street 2nd lane in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/13454,Roads,Completed,NL-VALASARAVAKKAM,154,952400,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kananammal Street ,Kananammal 1st cross street , Kananammal 1st cross street lane, Kananammal 2nd cross street lane, Kannadasan Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/13455,Roads,Completed,NL-VALASARAVAKKAM,154,999000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateshwara Nagar 3rd Main Road & Usainabath School Road in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13457,Roads,Completed,NL-VALASARAVAKKAM,154,864600,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateshwara Nagar 18th Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/13459,Roads,Completed,NL-VALASARAVAKKAM,154,877600,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at GovindhanSteet, Kattabomman Street & Umadhurai Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13463,Roads,Completed,NL-VALASARAVAKKAM,154,760500,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Gangai Amman Koil West Street, Gangai Amman Koil south Street lane & KalliappaUdayar Streetin division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13464,Roads,Completed,NL-VALASARAVAKKAM,154,936000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Naidu 1st cross sreet, Naidu Sreet 1st lane & Agathiyar Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13465,Roads,Completed,NL-VALASARAVAKKAM,154,864600,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Thiruvalluvar Street & Gangaiamman Koil 1st Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13467,Roads,Completed,NL-VALASARAVAKKAM,154,907000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Manathaveli Amman Koil 1st Street & Gangaiamman Koil 2nd Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13469,Roads,Completed,NL-VALASARAVAKKAM,154,982000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Gangaiamman Koil 3rd Street, Meenakshi Street & Mandavalli Amman Koil 2nd Street (venust) in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13470,Roads,Completed,NL-VALASARAVAKKAM,154,773600,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Balambigai Nagar 5th Street, Sannathi Street & Venkateswara Nagar 1st Main Road Lane in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13471,Roads,Completed,NL-VALASARAVAKKAM,154,993000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 19th Street, Venkateswara Nagar 19th cross Street lane & Venkateswara Nagar 14th 1st Cross Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/13473,Roads,Completed,NL-VALASARAVAKKAM,154,920000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 14th 2nd Cross Street & Shanthi Nagar Appadurai Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13474,Roads,Completed,NL-VALASARAVAKKAM,154,893800,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at pillayarkoil Street, Vivekanandha school street & New Bharathiyar street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13475,Roads,Completed,NL-VALASARAVAKKAM,154,993000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 1st Main Road Reach l in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/13476,Roads,Completed,NL-VALASARAVAKKAM,154,965600,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 1st Main Road Reach II n division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13478,Roads,Completed,NL-VALASARAVAKKAM,154,978500,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 1st Main Road extension & Venkateswara Nagar 2nd Main Road Rech I in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13480,Roads,Completed,NL-VALASARAVAKKAM,154,965300,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 2nd Main Road Reach II in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/13481,Roads,Completed,NL-VALASARAVAKKAM,154,936000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Anandhamnagar 1st main road in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/13483,Roads,Completed,NL-VALASARAVAKKAM,154,923000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 1st street, Venkateswara Nagar 23rd street, Kurinjinagar 10th street & Shanthi Nagar Chengalvarayan Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/14440,Road Cut,Completed,NL-VALASARAVAKKAM,154,991000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KURINJI NAGAR 1ST MAIN ROAD(part), KURINJI NAGAR 3RD CROSS STREET AND 5TH CROSS STREET IN DN154,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/14442,Road Cut,Completed,NL-VALASARAVAKKAM,154,990000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KURINJI NAGAR 2ND MAIN ROAD(part),KURINJI NAGAR 2ND CROSS STREET AND SHANTI NAGAR KANNAPPAN STREET(part) IN DN154,U34,Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/14453,Road Cut,Completed,NL-VALASARAVAKKAM,154,999000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KURINJI NAGAR 4TH,6TH,7TH,8TH & 9TH CROSS STREETS,VENKATESWARA NAGAR 4TH MAIN ROAD(part) AND BALAMBIGAI NAGAR 5TH STREET(part) IN DN154,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/14590,Road Cut,Completed,NL-VALASARAVAKKAM,154,999000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KALAIGNAR STREET,ANANDAM NAGAR 1 to 4 STREETS AND SHANTI NAGAR ANNA STREET IN DN154,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/14804,Road Cut,Completed,NL-VALASARAVAKKAM,154,999000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT VENKATESWARA NAGAR 4TH,14TH,20TH,21ST,22ND STREET(part),GANGAI AMMAN KOIL PERIYAR STREET ,LANE, SOUTH(part),EVR 1ST PERIYAR STREET(part) AND ANANDAM NAGAR 1ST AND 2ND MAIN ROAD(part) IN DN154,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/15445,Electrical,Completed,NL-VALASARAVAKKAM,154,73000,"Repairs and Improvements to Toilets at Gangaiamman koil street and Bharathi street in div-154,u-34,z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15446,Roads,Completed,NL-VALASARAVAKKAM,154,99300,"Supplying and Spreading of Wet mix Macadam at kakkan street and Kutty street in div-154,u-34,z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15447,Roads,Completed,NL-VALASARAVAKKAM,154,99000,"Repairs to SWD and Providing Wet Mix Macadam at Santhi Nagar Main Road in Div-154,U-34,Z-11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15872,Buildings,Completed,NL-VALASARAVAKKAM,154,137000,"REPAIRS TO AMMA UNAVAGAM IN DN-154, UNIT-34, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/16040,Parks,Completed,NL-VALASARAVAKKAM,154,79000,"Repairs to children play apparatus and water supply arrangements to kurinji nagar park in division-154, u-34, z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/1622,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,584000,"IMPROVEMENTS TO SIDE DRAIN AT BALAMBIGAI NAGAR 5TH STREET EXTN.IN DN154,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/16536,Buildings,Completed,NL-VALASARAVAKKAM,154,198000,"Repairs to Anganvadi in Gangai Amman Koil street in Dn-154, U-34, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/3034,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,999000,"Desilting of Side drain and Storm water drain at Venkateshwara Nagar, Kurinji Nagar, Anandham Nagar, Shanthi Nagar, Balambigai Nagar, Ambal Nagar, G.S Nagar, Gangaiamman Koil Street, Naidu Street, Bharathi Salai, in Dn-154, U-34, Z-XI",Own Sources,11,2016-17,2017-18 NL/2016-17/3308,Roads,Completed,NL-VALASARAVAKKAM,154,701000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kalaignar Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/3309,Roads,Completed,NL-VALASARAVAKKAM,154,739000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji Nagar 2nd Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/3310,Roads,Completed,NL-VALASARAVAKKAM,154,584000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji Nagar 3rd Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/3311,Roads,Completed,NL-VALASARAVAKKAM,154,727000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji Nagar 4th Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/3312,Roads,Completed,NL-VALASARAVAKKAM,154,727000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji Nagar 5th Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/3313,Roads,Completed,NL-VALASARAVAKKAM,154,727000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji Nagar 6th Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/3314,Roads,Completed,NL-VALASARAVAKKAM,154,780000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji Nagar 7th Street, Kurinji Nagar 8th Street & Kurinji Nagar 9th Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4473,Road Cut,Completed,NL-VALASARAVAKKAM,154,878000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 4th Street, Gangai amman koil periyar st lane and Shanthi Nagar Venugopal Street Lane in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4488,Road Cut,Completed,NL-VALASARAVAKKAM,154,936000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 20th Street and E.V.R 1st Periyar Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4492,Road Cut,Completed,NL-VALASARAVAKKAM,154,952000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara Nagar 14th Street and Venkateswara nagar 21st st in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4493,Road Cut,Completed,NL-VALASARAVAKKAM,154,835000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Shanthi Nagar Kannappan Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4494,Road Cut,Completed,NL-VALASARAVAKKAM,154,894000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Bharathiyar st in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4495,Road Cut,Completed,NL-VALASARAVAKKAM,154,878000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Gangai amman koil periyar st in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4496,Road Cut,Completed,NL-VALASARAVAKKAM,154,890000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Narasimma perumal koil street and Avvai Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4497,Road Cut,Completed,NL-VALASARAVAKKAM,154,963000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Anandham nagar 2nd main road and Gangai Amman Koil South Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4498,Road Cut,Completed,NL-VALASARAVAKKAM,154,892000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Perumal koil 2nd street, Venkateswara nagar 22nd st and Shanthi nagar Arignar anna street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4499,Road Cut,Completed,NL-VALASARAVAKKAM,154,936000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Venkateswara nagar 4th main road and Balambigai Nagar 5th Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4500,Road Cut,Completed,NL-VALASARAVAKKAM,154,848000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Anandham nagar 3rd street and Balambigai Nagar 3rd Street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4574,Road Cut,Completed,NL-VALASARAVAKKAM,154,979000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji nagar 2nd main road in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4647,Road Cut,Completed,NL-VALASARAVAKKAM,154,979000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji nagar 1st main road (From Bharathi salai to Kurinji nagar 6th street) in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4674,Road Cut,Completed,NL-VALASARAVAKKAM,154,979000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Anandham nagar 1st main road in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4676,Road Cut,Completed,NL-VALASARAVAKKAM,154,763000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kurinji nagar 1st main road (From Kurinji nagar 6th street to 7th street) and Venugopal street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4677,Road Cut,Completed,NL-VALASARAVAKKAM,154,736000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Anandham nagar 4th street and Anandham nagar 1st main road part in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4678,Road Cut,Completed,NL-VALASARAVAKKAM,154,539000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Anandham nagar 1st street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4679,Road Cut,Completed,NL-VALASARAVAKKAM,154,536000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Anandham nagar 2nd street in division 154, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/5097,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,486000,"Desilting of Mount poonamalle canal from Husainy bath school to Shanthi nagar main road In Dn-154,U-34,Z-XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/6495,Roads,Completed,NL-VALASARAVAKKAM,154,996000,"Laying the Cement Concrete road with RMC at Venugopal street lane, Natarajan street lane, Venkateswara nagar 13th street lane and Kakkan street in Division -154, Unit-34, Zone-11",Own Sources,11,2016-17,2017-18 NL/2016-17/6516,Buildings,Completed,NL-VALASARAVAKKAM,154,998000,"Improvements to Anganvadi at Venkateswara nagar 5th st, Gangai amman koil st and Kulakari south street in Dn-154, U-34, Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/6522,Buildings,Completed,NL-VALASARAVAKKAM,154,994000,"Suppling and Fixing Name Board at shanthi Nagar, kurinji Nagar, Ambal Nagar, Balambigai Nagar, Venkateswara nagar and various other street in Divison - 154, Unit - 34, Zone - 11",Own Sources,11,2016-17,2018-19 NL/2016-17/7049,Buildings,Completed,NL-VALASARAVAKKAM,154,335000,"Construction of compound wall for 16th day ceremony hall at kambar salai in Dn-154, U-34, Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/7124,Roads,Completed,NL-VALASARAVAKKAM,154,664000,"Construction of side drain at venugopal street lane in Dn-154, U-34, Z-11",Own Sources,11,2016-17,2018-19 NL/2016-17/7998,Buildings,Completed,NL-VALASARAVAKKAM,154,500000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM,DIVISION OFFICE,PUBLIC CONVENIENCE AND STORM WATER DRAIN IN DN154,U34,Z11.",Own Sources,11,2016-17,2017-18 BR/2016-17/9646,Roads,Completed,BR-Bus Route Roads,155,7040000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improivement work at kAMARAJ SALAI -Div1 55,Zone-11.",Grants,11,2016-17,2018-19 NL/2016-17/10010,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"CONSTRUCTION OF CREMATION PLACE INSIDE THE BURIAL GROUND LOCATED AT THIRUVALLUVAR SALAI IN DN155,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/1002,Roads,Completed,NL-VALASARAVAKKAM,155,984000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at G.R Nagar 1st Main Road & G.R Nagar 1st Street in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1003,Roads,Completed,NL-VALASARAVAKKAM,155,984000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Palaniappan Street & Chidhambaram Nagar Pillaiyar Koil Street in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1004,Roads,Completed,NL-VALASARAVAKKAM,155,634000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Arunachalam Street in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1005,Roads,Completed,NL-VALASARAVAKKAM,155,585000,"FForming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Vembuli Street in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1006,Roads,Completed,NL-VALASARAVAKKAM,155,585000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Maari Street in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1007,Roads,Completed,NL-VALASARAVAKKAM,155,580000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Krishnan Street in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1008,Roads,Completed,NL-VALASARAVAKKAM,155,936000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Annex Arunachalam 1st Street & Senthamizh Nagar Annex Arunachalam 2nd Street in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1009,Roads,Completed,NL-VALASARAVAKKAM,155,766000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Micheal garden hariharan street (Reach-1) in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1010,Roads,Completed,NL-VALASARAVAKKAM,155,766000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Micheal garden hariharan street (Reach-2) in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/1011,Roads,Completed,NL-VALASARAVAKKAM,155,703000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Micheal garden 2nd cross street, Micheal garden 3rd cross street & Micheal garden 3rd cross street lane in Dn-155, U-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/10146,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"IMPROVEMENTS TO BURIAL GROUND LOCATED AT THIRUVALLUVAR STREET IN DN155,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/10781,Roads,Completed,NL-VALASARAVAKKAM,155,921000,"Roadcut Restoration for Under ground Sewage System & Water Supply System at Kothari Nagar 6th Street in Dn-155, U-34, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/10785,Roads,Completed,NL-VALASARAVAKKAM,155,966000,"Roadcut Restoration for Under ground Sewage System & Water Supply System at Kothari Nagar 11th and 1st Cross Street in Dn-155, U-34, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/11046,Roads,Completed,NL-VALASARAVAKKAM,155,468000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Nehru Nagar Meenakshi Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11047,Roads,Completed,NL-VALASARAVAKKAM,155,979000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Giri nagar Annex, Natesan nagar 1st lane & 2nd lane in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/11048,Roads,Completed,NL-VALASARAVAKKAM,155,708000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Thamizh nagar 2nd main road in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11049,Roads,Completed,NL-VALASARAVAKKAM,155,999000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Vivekanandha Nagar Tichu Street Street & Hari Shankar Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11050,Roads,Completed,NL-VALASARAVAKKAM,155,999000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Vivekanandha Nagar Singaram Street, Singaram Street 1st lane, 2nd lane & Venkat Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11051,Roads,Completed,NL-VALASARAVAKKAM,155,963000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Vivekanandha Nagar Rajaram Street & Kumaran Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11052,Roads,Completed,NL-VALASARAVAKKAM,155,750000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Vivekanandha Nagar Srivatsa Street & Annaswamy Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/11053,Roads,Completed,NL-VALASARAVAKKAM,155,936000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Vivekanandha Nagar Main Road (Part - II) & Krishna Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11054,Roads,Completed,NL-VALASARAVAKKAM,155,936000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Vivekanandha Nagar Main Road (Part - I) & Sundharam Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/11055,Roads,Completed,NL-VALASARAVAKKAM,155,750000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Azhagapuri nagar 4th, 5th & 6th avenue in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11056,Roads,Completed,NL-VALASARAVAKKAM,155,665000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Azhagapuri nagar 1st, 2nd & 3rd avenue in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11057,Roads,Completed,NL-VALASARAVAKKAM,155,878000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Gandhi nagar 4th Street, Maha Lakshmi nagar main road & 1st Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11058,Roads,Completed,NL-VALASARAVAKKAM,155,710000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Gandhi nagar 3rd Street & 3rd Cross Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11059,Roads,Completed,NL-VALASARAVAKKAM,155,988000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Gandhi nagar 1st Street, 2nd Street & Maha Lakshmi nagar 2nd street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11060,Roads,Completed,NL-VALASARAVAKKAM,155,638000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at EVP Shanthosh nagar 4th, 5ht & 6th Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11062,Roads,Completed,NL-VALASARAVAKKAM,155,837000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at EVP Shanthosh nagar 3rd main road in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11063,Roads,Completed,NL-VALASARAVAKKAM,155,845000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at EVP Shanthosh nagar 2nd main road & 3rd Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11064,Roads,Completed,NL-VALASARAVAKKAM,155,923000,"Road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at EVP Shanthosh nagar 1st main road, 1st & 2nd Street in division 155, unit-34, Zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/11339,Roads,Completed,NL-VALASARAVAKKAM,155,2014000,"Relaying BT Road Bakthivendha 2nd Avenue, Thirumalai Nagar Thirumalai Street, Thirumalai Nagar Sanjay Ram Street and Rajeshwari Street in Dn-155, U-34, Z-XI",Loans And Grants,11,2016-17,2017-18 NL/2016-17/11992,Buildings,Completed,NL-VALASARAVAKKAM,155,998000,"Supply, Installation,Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at Bharathi Salai (Opp. Eswari Collage) in Dn - 155, U - 34, Zone - 11",Own Sources,11,2016-17,2017-18 NL/2016-17/12147,Buildings,Completed,NL-VALASARAVAKKAM,155,934000,Contruction Bin platform at Various street in Unit-34 in Zone-11.,Own Sources,11,2016-17,2018-19 NL/2016-17/12912,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"PROVIDING SHED AND OTHER IMPROVEMENTS TO AMMA KUDINEER STATION IN DN155,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/14581,Road Cut,Completed,NL-VALASARAVAKKAM,155,999000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SENTHAMIZH NAGAR VEMBULI STREET(part),ARUNACHALAM STREET(part),MAARI STREET(part), ANNEX ARUNACHALAM 1ST STREET(part) AND 2ND STREET(part) IN DN155,U34,Z11,",Own Sources,11,2016-17,2017-18 NL/2016-17/14586,Road Cut,Completed,NL-VALASARAVAKKAM,155,999000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT NETHAJI NAGAR MAIN ROAD(part),VENMANI STREET(part),SENTHAMIZH NAGAR KRISHNAN STREET(part),G R NAGAR 1ST STREET AND 2ND STREET IN DN155,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/14800,Road Cut,Completed,NL-VALASARAVAKKAM,155,999000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SENTHAMIZH NAGAR MAIN ROAD(part),CHIDAMBARAM NAGAR MAARI AMMAN STREET(part),SANNATHY STREET(part) AND ANDAL AMMAN STREET(part) IN DN155,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/14802,Road Cut,Completed,NL-VALASARAVAKKAM,155,999000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MICHAEL GARDEN HARIHARAN STREET(part),2ND & 3RD CROSS STREET(part), 3RD CROSS STREET LANE(part) AND NETHAJI NAGAR ANNA STREET(part) IN DN155,U34,Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/15000,Road Cut,Completed,NL-VALASARAVAKKAM,155,999000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at EVP Santhosh nagar 7th street, Manthi Naicker Thottam and Sriram nagar 4th street in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/15828,Parks,Completed,NL-VALASARAVAKKAM,155,86000,"Repairs works to Giri Nagar park at DN-155, Unit-34, Zone-11",Own Sources,11,2016-17,2017-18 NL/2016-17/15829,Parks,Completed,NL-VALASARAVAKKAM,155,150000,"Repairs works to Azhagapuri Nagar park and Eswaran Nagar park at DN-155, Unit-34, Zone-11",Own Sources,11,2016-17,2017-18 NL/2016-17/18964,Buildings,Completed,NL-VALASARAVAKKAM,155,800000,"Construction of compound wall at community center land (Survey no. 52 ramapuram revenue village) in rayala nagar 1st main road in Dn - 155, U - 34, Z - XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/18965,Buildings,Completed,NL-VALASARAVAKKAM,155,875000,"Construction of compound wall at Public Purpose land (Survey no. 51/2 ramapuram revenue village) in rayala nagar 1st cross street in Dn - 155, U - 34, Z - XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/18966,Buildings,Completed,NL-VALASARAVAKKAM,155,774000,"Construction of compound wall at children school land (Survey no. 56/1 ramapuram revenue village) in rayala nagar 3rd main road in Dn - 155, U - 34, Z - XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/19545,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,499000,"Improvement to SWD, Bore well, Fixing of Name Board and other improvements works in Div-155, Unit-134, Zone-11",Own Sources,11,2016-17,2018-19 NL/2016-17/2032,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,700000,"Desilting the Strom water Drains at Balakrishna Nagar Main Road, Senthamizh Nagar Main Road, Annai Sathya Nagar Main Road, Kannadasan Nagar Main Road, Barathi Nagar Main Road, G.R Nagar 1st Main Road, Rayala Nagar 1st Main Road, Kalasathamman Koil Street and Sriram Nagar 3rd Street in Division 155, Unit 34, Zone 11.",Own Sources,11,2016-17,2017-18 NL/2016-17/2034,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,996000,"Desilting the Side Drains at Senthamizh Nagar, Annai Sathya Nagar, Mullai Nagar, Rayala Nagar, Amman Nagar, Bakthivendha Avenue, Natesan Nagar, Tamil Nagar and Sriram Nagar in Division 155, Unit 34, Zone 11.",Own Sources,11,2016-17,2017-18 NL/2016-17/3493,Buildings,Completed,NL-VALASARAVAKKAM,155,553000,"Suppling and Fixing Name Board at Ragavendra Nagar, Moogambigai Nagar, Amman Nagar, Andal Garden, Jai balaji Nagar, A.K.R Garden, Periyar Street, Gangaiya Avenue, Sakthi Nagar and Balaji Avenue, in Divison - 155, Unit - 34, Zone - 11",Own Sources,11,2016-17,2018-19 NL/2016-17/3544,Buildings,Completed,NL-VALASARAVAKKAM,155,500000,"MAINTANANCE WORKS TO BE CARRIED OUT AT FREEZER BOX ROOM,BIO TOILET,PRIMARY HEALTH CENTER AND BURIAL GROUND IN DN155,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/3623,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,999000,"Desilting and removal of Hyacinth, Floating materials at Ramapuram lake (North) in Dn-155,U-34,Z-XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/3624,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,996000,"Desilting and removal of Hyacinth, Floating materials at Ramapuram lake (South) in Dn-155,U-34,Z-XI.",Own Sources,11,2016-17,2017-18 NL/2016-17/3682,Roads,Completed,NL-VALASARAVAKKAM,155,2260000,"Relaying BT Road at Egambaram Street, Periyar Salai, Balaji 1st Avenue and Balaji 2nd Avenue in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/3684,Roads,Completed,NL-VALASARAVAKKAM,155,2567000,"Relaying BT Road at Micheal garden hariharan street, Micheal garden 2nd cross street, Micheal garden 3rd cross street and Micheal garden 3rd cross street lane in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/3690,Roads,Completed,NL-VALASARAVAKKAM,155,2973000,"Relaying BT Road at Thirumalai Nagar Om Eswar Street, Thirumalai Nagar Maha Vishnu Street and Thirumalai Nagar Angel Street in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2016-17 NL/2016-17/3691,Roads,Completed,NL-VALASARAVAKKAM,155,2563000,"Relaying BT Road at Thirumalai Nagar Nehru Street, Thirumalai Nagar Nehru Street Lane, Thirumalai Nagar Padmavathy Street, Thirumalai Nagar Kathaie Amman Street, Thirumalai Nagar Angel Street Lane and Thirumalai Nagar Seven Hills Street in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/3692,Roads,Completed,NL-VALASARAVAKKAM,155,2576000,"Relaying BT Road at Amman Nagar 2nd Street, Amman Nagar 2nd Cross Street, Amman Nagar 3rd Street, Amman Nagar Circular Street, Bakthivedhandha Avenue and Bakthivedhandha 1st Avenue in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2016-17 NL/2016-17/3693,Roads,Completed,NL-VALASARAVAKKAM,155,2609000,"Relaying BT Road at Eswaran Nagar 1st Street, Eswaran Nagar 2nd Street, Eswaran Nagar 3rd Street, Eswaran Nagar 4th Street, Royala Nagar 2nd Cross Street and Royala Nagar 5th Cross Street in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2016-17 NL/2016-17/3696,Roads,Completed,NL-VALASARAVAKKAM,155,2808000,"Relaying BT Road at Kothari Nagar 8th Street, Kothari Nagar 9th Street, Kothari Nagar 10th Street, Kothari Nagar 11th Street and Kalyanaponnappan Street in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/3697,Roads,Completed,NL-VALASARAVAKKAM,155,2543000,"Relaying BT Road at Kothari Nagar 4th Street, Kothari Nagar 5th Street, Kothari Nagar 6th Street and Kothari Nagar 7th Street in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/3698,Roads,Completed,NL-VALASARAVAKKAM,155,2980000,"Relaying BT Road at Kothari Nagar 2nd Main Road, Kothari Nagar 1st Cross Street, Kothari Nagar 1st Street and Kothari Nagar2nd Street in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2018-19 NL/2016-17/3699,Roads,Completed,NL-VALASARAVAKKAM,155,2589000,"Relaying BT Road at Kothari Nagar 1St Main Road, Kothari Nagar EVR Street and Kothari Nagar 3rd Street in Dn-155, U-34, Z-11.",Loans And Grants,11,2016-17,2017-18 NL/2016-17/4371,Roads,Completed,NL-VALASARAVAKKAM,155,700000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Nethaji Nagar Main Road in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4372,Roads,Completed,NL-VALASARAVAKKAM,155,489000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Nethaji Nagar Venmani Street in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4373,Roads,Completed,NL-VALASARAVAKKAM,155,631000,"Forming road cut restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Nethaji Nagar Anna Street in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4590,Roads,Completed,NL-VALASARAVAKKAM,155,994000,"Providing Barricading for Ramapuram Lake Vacant Land (West Side) in Dn-155, U-34, Z-11",Own Sources,11,2016-17,2017-18 NL/2016-17/4949,Roads,Completed,NL-VALASARAVAKKAM,155,781000,"Roadcut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Main Road (Reach-I) in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4950,Roads,Completed,NL-VALASARAVAKKAM,155,781000,"Roadcut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Main Road (Reach-II) in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/4951,Roads,Completed,NL-VALASARAVAKKAM,155,781000,"Roadcut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Main Road (Reach-III) in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/5132,Footpath,Completed,NL-VALASARAVAKKAM,155,692000,"Forming bund at Ramapuram Lake in Division-155, Unit-34, Zone -11.",Own Sources,11,2016-17,2017-18 NL/2016-17/6272,Roads,Completed,NL-VALASARAVAKKAM,155,703000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Chidhambaram Nagar Sannathy Street & Andal Amman Street in division 155, Unit-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/6279,Roads,Completed,NL-VALASARAVAKKAM,155,537000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Chidhambaram Nagar Mari Amman Street (Part-1) in division 155, Unit-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/6282,Roads,Completed,NL-VALASARAVAKKAM,155,537000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Chidhambaram Nagar Mari Amman Street (Part-2) in division 155, Unit-34, Zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/8613,Roads,Completed,NL-VALASARAVAKKAM,155,920000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Senthamizh Nagar Sairam, Senthamizh Nagar Meenakshi Street & Senthamizh Nagar Shanmugam Street in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/8614,Roads,Completed,NL-VALASARAVAKKAM,155,750000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Karpagambal Nagar 1st Street in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/8615,Roads,Completed,NL-VALASARAVAKKAM,155,766000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Karpagambal Nagar 2nd Street & Karpagambal Nagar 2nd Cross Street in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2018-19 NL/2016-17/8617,Roads,Completed,NL-VALASARAVAKKAM,155,638000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Kaliappan Naicker Street in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/8618,Roads,Completed,NL-VALASARAVAKKAM,155,596000,"Road cut Restoration for Under ground sewage system and water Supply system using GSB, WMM, RMC-40 at Elumalai Avenue in division 155, unit-34, zone- 11",Own Sources,11,2016-17,2017-18 NL/2016-17/9923,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"PROVIDING WATER SUPPLY,ELECTRICAL AND OTHER ARRANGEMENTS TO NEW FAIR PRICE CANTEEN CALLED AMMA UNAVAGAM LOCATED AT BHARATHI SALAI IN DN155,U34,Z11.",Own Sources,11,2016-17,2017-18 NL/2016-17/9963,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"PROVIDING GLADING ARRANGEMENTS TO NEW FAIR PRICE CANTEEN CALLED AMMA UNAVAGAM LOCATED AT BHARATHI SALAI IN DN155,U34,Z11.",Own Sources,11,2016-17,2018-19 NL/2016-17/9969,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"PROVIDING SUBSIDY TIFFEN CENTRE CALLED AMMA UNAVAGAM IN DN155,U34,Z11.",Own Sources,11,2016-17,2018-19 BR/2016-17/17764,Roads,Completed,BR-Bus Route Roads,156,7600000,"Repair and Restoration of Relaying Road by Paver Finisher Work at MMTC Colony in Dn-164, Zone-12",Grants,12,2016-17,2017-18 BR/2016-17/17765,Roads,Completed,BR-Bus Route Roads,156,2200000,"Repair and Restoration of Relaying Road by Paver Finisher Work at Kannan Nagar Main Road in Dn-164, Zone-12",Grants,12,2016-17,2017-18 NM/2016-17/0235,Parks,Completed,NM-ALANDUR,156,290000,"IMPROVEMENTS TO PARK AT KUMUTHAM NAGAR PARK IN DN.156,UNIT-35,ZONE-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/0795,Storm Water Drain,Completed,NM-ALANDUR,156,195000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS STREETS IN DN.156, UNIT - 35, ZONE - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/0841,Buildings,Completed,NM-ALANDUR,156,132000,"PROVIDING RAMP AND HANDRAIL FOR DISABLED PERSONS AT VARIOUS SCHOOLS IN DN.156, U - 35, ZONE - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/0842,Buildings,Completed,NM-ALANDUR,156,98000,"CONSTRUCTION OF PLATFORMS FOR DUSTBINS AT VARIOUS STREETS IN DN.156, U - 35, ZONE - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/0992,Storm Water Drain,Completed,NM-ALANDUR,156,255000,"Repairs and Improvements to existing Storm Water Drain at Subhasree Nagar Extension 4 , in Dn.156, U - 35, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/11295,Buildings,Completed,NM-ALANDUR,156,125000,"PAINTING WORK OF AMMA UNAVAGAM AT MADHANANDHAPURAM MAIN ROAD IN DN-156, UNIT-35, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/11296,Buildings,Completed,NM-ALANDUR,156,168000,"ELECTRICAL ARRANGEMENTS OF E-TOILET AT PADASALAI STREET IN DN-156, UNIT-35, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/11948,Buildings,Completed,NM-ALANDUR,156,108000,"IMPROVEMENT WORK OF ALUMINUM PARTISION AT HOSPITAL BUILDING IN PADASALAI STREET IN DN-156,U-35,ZON-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1219,Parks,Completed,NM-ALANDUR,156,435000,"ANNUAL MAINTENANCE OF PARK AT AGS COLONY SABARI NAGAR 2ND MAIN ROAD PARK IN DN-156,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1220,Parks,Completed,NM-ALANDUR,156,480000,"ANNUAL MAINTENANCE OF PARK AT VND RAJESWARI AVENUE,SINDHU STREET PARK IN DN-156,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1221,Parks,Completed,NM-ALANDUR,156,658000,"ANNUAL MAINTENANCE OF PARK AT A.G.S COLONY PHASE 3 PARK IN DN-156,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1223,Parks,Completed,NM-ALANDUR,156,457000,"ANNUAL MAINTENANCE OF PARK AT MADHA NAGAR,2nd STREET PARK IN DN-156,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1225,Parks,Completed,NM-ALANDUR,156,432000,"ANNUAL MAINTENANCE OF PARK AT BLOOMING GARDEN MARRY GOLD PARK IN DN-156,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1258,Buildings,Completed,NM-ALANDUR,156,40000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CORPORATION PRIMARY AND MIDDLE SCHOOLS IN DN.156, UNIT - 35, ZONE - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13099,Buildings,Completed,NM-ALANDUR,156,134000,PROVIDING AND LAYING WMM AT KARPAKAMMBAL STREET IN DN -156 U-35 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/13100,Roads,Completed,NM-ALANDUR,156,156000,PROVIDING AND LAYING WMM AT KRISHNA NAGAR MAIN ROAD IN DN -156 U-35 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/13765,Buildings,Completed,NM-ALANDUR,156,93000,"Repairs and Improvements to Meidicinal store and Distribution room for Hospital building at Padasalai Street in DN.156, U - 35, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13766,Buildings,Completed,NM-ALANDUR,156,140000,"Providing Ramp and Steps for Entrance to Hospital at Padasalai Street in Dn.156, U - 35, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13815,Buildings,Completed,NM-ALANDUR,156,27000,"IMPROVEMENT WORK OF COMPOST YARD IN XL REAL PARK DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/13822,Buildings,Completed,NM-ALANDUR,156,41000,"IMPROVEMENT WORK OF CHENNAI MIDDLE SCHOOL AT MADHANANDHAPURAM MAIN ROAD IN DN-156, UNIT-35, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/13840,Roads,Completed,NM-ALANDUR,156,185000,PROVIDING AND LAYING WMM AT PANDIYAN STREET IN DN -156 U-35 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/13841,Buildings,Completed,NM-ALANDUR,156,24000,"DESEILTING OF MUGALIVAKKAM CULVERT AND SABARI NAGAR CULVERT IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1398,Roads,Completed,NM-ALANDUR,156,357000,"PROVIDING AND LAYING GSB & WMM AT VASUKI STREET IN DN. - 156, U - 35, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/1399,Roads,Completed,NM-ALANDUR,156,174000,"PROVIDING AND LAYING GSB AND WMM AT SUBHASHREE NAGAR EXTENSION 4 IN DN.156, U - 35, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/1458,Roads,Completed,NM-ALANDUR,156,87000,"PROVIDING AND LAYING GSB AND WMM AT SUBHASHREE NAGAR 3rd PHASE IN DN.156, U - 35, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/15824,Buildings,Completed,NM-ALANDUR,156,270000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) AT AGS COLONY PH-3 IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/15850,Parks,Completed,NM-ALANDUR,156,35000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) CHILDRENS PLAY PARK SABARINAGAR 1ST MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/15862,Buildings,Completed,NM-ALANDUR,156,245000,"REPAIRS WORK TO DAMAGED (VARDHA CYCLONE) AT PC AT MUGALIVAKKAM MANAPAKKAM MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/16021,Buildings,Completed,NM-ALANDUR,156,49000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) AT CHILDRENS PLAY PARK SUBASRI NAGAR EXTEN 5TH STREET IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/16022,Buildings,Completed,NM-ALANDUR,156,36000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) AT SSL GREEN PARK AT MADHANANTHAPURAM IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/16023,Buildings,Completed,NM-ALANDUR,156,212000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) AT MADHA NAGAR 2ND MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/16024,Buildings,Completed,NM-ALANDUR,156,39000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) AT DEVADHAS STREET IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/16025,Buildings,Completed,NM-ALANDUR,156,40000,"REPAIRS WORK TO DAMAGED AMMA UNAVAGAM (VARDHA CYCLONE) AT NANDHAGOPAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1737,Storm Water Drain,Completed,NM-ALANDUR,156,134000,"Desilting of Storm Water Drain at various street in dn-156, unit-35, zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17535,Parks,Completed,NM-ALANDUR,156,675000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) CRR PURAM L&T COLONY IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17556,Parks,Completed,NM-ALANDUR,156,98000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) KUMUTHAM NAGAR PARK IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17557,Parks,Completed,NM-ALANDUR,156,21000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE)SABARI NAGAR 2ND MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17558,Parks,Completed,NM-ALANDUR,156,84000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) MERYGOLD STREET PARK IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17560,Parks,Completed,NM-ALANDUR,156,300000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) VND AVENUE VAGAI STREET PARK IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17563,Parks,Completed,NM-ALANDUR,156,218000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) VND AVENUE RAJESWARINNAGAR SINDHUSALAI PARK IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17567,Parks,Completed,NM-ALANDUR,156,137000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) ANNAIVELANKANNI NAGAR PH-1,2ND STREET PARK IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17568,Parks,Completed,NM-ALANDUR,156,130000,"REPAIRS WORK TO DAMAGED PARK (VARDHA CYCLONE) ANNAIVELANKANNI NAGAR PH-1,5TH STREET PARK IN DN-156,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/19277,Buildings,Completed,NM-ALANDUR,156,292000,"Attending Patch Work with Cement Concrete at various Cement Concrete Roads and repairs to swd doors at various street in DN.156, U - 35, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/2153,Electrical,Completed,NM-ALANDUR,156,983400,ERECTION OF 38 NOS OF 2MTR POST WITH 15W LED FITTINGS AND 3 NOS OF 6MTR WITH 40W LED FITTINGS AT MADHA NAGAR PARK 2ND MAIN ROAD AT DN-156 ZONE XII,Own Sources,12,2016-17,2017-18 NM/2016-17/2166,Electrical,Completed,NM-ALANDUR,156,981600,ERECTION OF 38 NOS OF 2 MTR POST WITH 15W LED FITTINGS AND 3 NOS OF 6MTR WITH 40W LED FITTINGS AT KUMUTHAM NAGAR PARK AT DN-156 ZONE XII,Own Sources,12,2016-17,2017-18 NM/2016-17/2718,Parks,Completed,P-Parks and Playfields,156,4173000,"FORMATION OF NEW PARK AT KUNDRATHUR MAIN ROAD, MADHANANTHAPURAM (SIDDHARTH FOUNDATIONS) IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/2722,Parks,Completed,P-Parks and Playfields,156,8511000,"FORMATION OF NEW PARK AT GURUSAMY NAGAR, NANDAGOPAL STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/2723,Parks,Completed,P-Parks and Playfields,156,2477000,"FORMATION OF NEW PARK AT VGN LAKSHMI NAGAR VISHWANATHAN PALANI STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/2724,Parks,Completed,P-Parks and Playfields,156,9750000,"FORMATION OF NEW PARK AT V.G.N LAKSHMI NAGAR KALAIMAGAL STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/4851,Electrical,Completed,NM-ALANDUR,156,974000,ERECTION OF 38 NOS OF MTR POST WITH 15W LED FITTING AND 3NOS OF 6MTR WITH 40W LED FITTING AT CRR PURAM PARK AT DN-156 ZONE XII,Own Sources,12,2016-17,2016-17 NM/2016-17/5196,Buildings,Completed,NM-ALANDUR,156,982000,"Providing temporary amma unavagam shed at Mariamman Koil Street junction of Padasalai Street in Div-156, U-35, Zn-12",Own Sources,12,2016-17,2016-17 NM/2016-17/5967,Storm Water Drain,Completed,NM-ALANDUR,156,49000,"construction of bin at varies street in dn-156,u-35,zone-12",Own Sources,12,2016-17,2016-17 NM/2016-17/7399,Roads,Completed,NM-ALANDUR,156,504000,"PROVIDING AND LAYING GSB & WMM AT KUMUTHAM NAGAR 1ST STREET IN DN-156, U-35, Z-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/7480,Storm Water Drain,Completed,NM-ALANDUR,156,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT PADASALAI STREET NEAR DIVISION OFFICE IN DIV -156,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7758,Roads,Completed,NM-ALANDUR,156,420000,"PROVIDING AND LAYING GSB AND WMM AT AGS COLONY 3RD MAIN ROAD 3RD CROSS STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2018-19 NM/2016-17/7760,Roads,Completed,NM-ALANDUR,156,270000,"PROVIDING AND LAYING GSB AND WMM AT AGS COLONY 3RD MAIN ROAD 2ND CROSS STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2018-19 NM/2016-17/7761,Roads,Completed,NM-ALANDUR,156,270000,"PROVIDING AND LAYING GSB AND WMM AT AGS COLONY 3RD MAIN ROAD 1ST CROSS STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2018-19 NM/2016-17/7762,Roads,Completed,NM-ALANDUR,156,611000,"PROVIDING AND LAYING GSB AND WMM AT KRISHNAVENI NAGAR EXTN - II IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/7763,Roads,Completed,NM-ALANDUR,156,82000,"Providing Laying GSB and WMM Laying At Thiruvenkadam Street In Dn-156.U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/7764,Roads,Completed,NM-ALANDUR,156,173000,"Providing Laying GSB and WMM Laying At Thiruveni Street In Dn-156.U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/7967,Roads,Completed,NM-ALANDUR,156,170000,"PROVIDING AND LAYING GSB AND WMM AT ALVANCHERY PRUMAL KOIL STREET IN DN-156,U-35,ZONE-12",Own Sources,12,2016-17,2017-18 P/2016-17/19684,Parks,Completed,P-Parks and Playfields,156,5988303,"FORMATION OF NEW PARK AT ANNAI VELANKANNI NAGAR PHASE-2, MUGALIVAKKAM IN DN-156,U-35,ZONE-12",Grants,12,2016-17,2018-19 NM/2016-17/0691,Storm Water Drain,Completed,NM-ALANDUR,157,952000,IMPROVEMENTS WORKS OF SWD AT M.G.R NAGAR MAIN ROAD IN DN - 157 U-35 Z-12,Own Sources,12,2016-17,2016-17 NM/2016-17/0692,Roads,Completed,NM-ALANDUR,157,83000,"PROVIDING AND LAYING GSB & WMM AT SATHIYA NAGAR 6TH STREET IN DN-157, U-35, Z-12",Own Sources,12,2016-17,2016-17 NM/2016-17/0693,Roads,Completed,NM-ALANDUR,157,388000,"PROVIDING AND LAYING GSB & WMM AT PERIYA COLONY EAST STREET IN DN-157, U-35, Z-12",Own Sources,12,2016-17,2016-17 NM/2016-17/11230,Electrical,Completed,NM-ALANDUR,157,747700,ERECTION OF 25 NOS OF 2MTR POST WITH 15W LED FITTINGS AND 3 NOS OF 6 MTR WITH 40W LED FITTINGS AT BHELL NAGAR PARK (PART -I) DN-157 ZONE XII,Own Sources,12,2016-17,2017-18 NM/2016-17/1294,Parks,Completed,NM-ALANDUR,157,530000,"Annual Maintenance of Park at River view colony Phase-I Park in Dn.157,Unit- 35,Zone-12 (by Employed Qualified Horticulturist for one year)",Own Sources,12,2016-17,2017-18 NM/2016-17/1298,Parks,Completed,NM-ALANDUR,157,559000,"Annual Maintenance of Park at River view colony Phase-II Park in Dn.157,Unit- 35,Zone-12 (by Employed Qualified Horticulturist for one year only)",Own Sources,12,2016-17,2017-18 NM/2016-17/13144,Buildings,Completed,NM-ALANDUR,157,225000,"providing interlocking block at various street in dn-157,u-35,z-12",Own Sources,12,2016-17,2016-17 NM/2016-17/1734,Storm Water Drain,Completed,NM-ALANDUR,157,327000,"Desilting of Storm Water Drain at various street in dn-157, u-35, z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/18316,Buildings,Completed,NM-ALANDUR,157,132000,"REPAIRS TO DAMAGED COMPOUND WALL (VARDHA CYCLONE) AT MACRO MARVEL RIVER VIEW COUNTRY PARK DN-157,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1949,Parks,Completed,NM-ALANDUR,157,405000,"Annual Maintenance of Park at Kaviya garden Park in Dn.157,Unit-35,Zone-12 (by Employed Qualified Horticulturist only)",Own Sources,12,2016-17,2017-18 NM/2016-17/1950,Parks,Completed,NM-ALANDUR,157,410000,"Annual Maintenance of Park at Macro marval Park in Dn.157,Unit-35,Zone-12 (by Employed Qualified Horticulturist only)",Own Sources,12,2016-17,2017-18 NM/2016-17/1951,Parks,Completed,NM-ALANDUR,157,435000,"Maintenance of Park at Bel nagar Park in Dn.157,Unit-35,Zone-12(by Employed Qualified Horticulturist only)",Own Sources,12,2016-17,2017-18 NM/2016-17/2770,Parks,Completed,P-Parks and Playfields,157,5384000,"Formation of New Park at Arcot Road Near Naveen Flats in Dn-157, Unit-35, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/3002,Parks,Completed,P-Parks and Playfields,157,5472000,"Formation of New Park at River View Avenue Main Road Phase III in Dn-157, Unit-35, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/3346,Buildings,Completed,NM-ALANDUR,157,204000,"IMPROVEMENTS WORK S.I ROOM IN DN -157,UNIT-35,ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/3854,Buildings,Completed,NM-ALANDUR,157,463000,"CONSTRUCTION OF STORE ROOM AT COMMUNITY HALL IN DIV-157,UNIT-35,ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/4413,Buildings,Completed,NM-ALANDUR,157,289000,"CONSTRUCTION OF OPEN DRAIN AT NARMADHA STREET,ALONG KRISHANA STREET AND RIVER VIEW COLONY 4TH MAIN ROAD IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/5943,Buildings,Completed,NM-ALANDUR,157,961000,"Providing temporary shed of Amma Unavagam at Bell Nagar Main road in Div-157, U-35, Zn-12",Own Sources,12,2016-17,2017-18 NM/2016-17/6194,Storm Water Drain,Completed,NM-ALANDUR,157,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT M.G ROAD NEAR DHARMARAJPURAM IN DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2016-17 NM/2016-17/6442,Buildings,Completed,NM-ALANDUR,157,737000,"IMPROVEMENTS WORK OF SWD AT LAKSHMI NAGAR MAIN ROAD IN DN-157,UNIT-35, ZONE -12 (COUNCILLOR FUND)",Own Sources,12,2016-17,2017-18 NM/2016-17/6448,Buildings,Completed,NM-ALANDUR,157,356000,"IMPROVEMENTS WORK OF SWD AT LAKSHMI NAGAR 1ST CROSS STREET IN DN-157,UNIT-35, ZONE -12 (COUNCILLOR FUND)",Own Sources,12,2016-17,2017-18 NM/2016-17/6449,Buildings,Completed,NM-ALANDUR,157,454000,"IMPROVEMENTS WORK OF SWD AT PERIYAPALATHAMMAN KOIL 1ST CROSS STREET IN DN-157,UNIT-35, ZONE -12 (COUNCILLOR FUND)",Own Sources,12,2016-17,2017-18 NM/2016-17/6450,Buildings,Completed,NM-ALANDUR,157,440000,"IMPROVEMENTS WORK OF SWD AT PERIYAPALATHAMMAN KOIL 2ND CROSS STREET IN DN-157,UNIT-35, ZONE -12 (COUNCILLOR FUND)",Own Sources,12,2016-17,2017-18 NM/2016-17/6451,Buildings,Completed,NM-ALANDUR,157,460000,"IMPROVEMENTS WORK OF SWD AT METTU COLONY BAJANI KOIL STREET IN DN-157,UNIT-35, ZONE -12 (COUNCILAR FUND)",Own Sources,12,2016-17,2017-18 NM/2016-17/6458,Buildings,Completed,NM-ALANDUR,157,318000,"IMPROVEMENTS WORK OF SWD AT METTU COLONY BAJANI KOIL 2ND STREET IN DN-157,UNIT-35, ZONE -12 (COUNCILLOR FUND)",Own Sources,12,2016-17,2017-18 NM/2016-17/6461,Buildings,Completed,NM-ALANDUR,157,235000,"IMPROVEMENTS WORK OF SWD AT METTU COLONY KAMARAJAR SALAI IN DN-157,UNIT-35, ZONE -12 (COUNCILAR FUND)",Own Sources,12,2016-17,2017-18 NM/2016-17/6823,Roads,Completed,NM-ALANDUR,157,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT MOUNT POONAMALLEE HIGH ROAD NEAR REGENCY PARK IN DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7439,Buildings,Completed,NM-ALANDUR,157,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT MOUNT POONAMALLEE HIGH ROAD NEAR JUNCTION OF RAMAPURAM IN DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7442,Storm Water Drain,Completed,NM-ALANDUR,157,805000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT M.G ROAD DHARMARAJPURAM IN DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7445,Storm Water Drain,Completed,NM-ALANDUR,157,805000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT MOUNT POONAMALLEE HIGH ROAD NEAR REGENCY PARK IN DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7451,Storm Water Drain,Completed,NM-ALANDUR,157,805000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT MOUNT POONAMALLEE HIGH ROAD NEAR JUNCTION OF RAMAPURAM IN DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7484,Storm Water Drain,Completed,NM-ALANDUR,157,805000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT PADASALAI STREET NEAR DIVISION OFFICE IN DIV -156,UNIT -35,ZONE -12",Own Sources,12,2016-17,2016-17 NM/2016-17/8439,Electrical,Completed,NM-ALANDUR,157,961900,ERECTION OF 32 NOS OF 2MTR POST WITH 15W LED FITTINGS AND 4 NOS OF 6MTR WITH 40W LED FITTINGS AT MACRO MAREVEL PARK AT DN-157 ZONE XII,Own Sources,12,2016-17,2017-18 NM/2016-17/8804,Electrical,Completed,NM-ALANDUR,157,738100,ERECTION OF 26 NOS OF 2MTR POST WITH 15W LED FITTINGS AND 5 NOS OF 6 MTR WITH 40W LED FITTINGS AT BHELL NAGAR PARK (PART -II) KAVIYA GARDEN AT DN-157 ZONE XII,Own Sources,12,2016-17,2017-18 NM/2016-17/8848,Buildings,Completed,NM-ALANDUR,157,158000,"CONSTRUCTION OF COMPOUND WALL AT PERIYA COLONY GENTS & LADIES TOILET IN DN-157 ,U-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/8904,Buildings,Completed,NM-ALANDUR,157,135000,"IMPROVEMENT WORK OF PAINTING AT AMMAUNAVAGAM MG ROAD IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/8906,Buildings,Completed,NM-ALANDUR,157,160000,"IMPROVEMENT WORK OF PAINTING AT METRO WATER OFFICE MG ROAD IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/8909,Buildings,Completed,NM-ALANDUR,157,426000,"IMPROVEMENT WORK OF PAINTING AT CORPORATION MID SCHOOL IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9927,Roads,Completed,NM-ALANDUR,157,750000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT C.R.R. Puram - Right Cross Street IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9928,Roads,Completed,NM-ALANDUR,157,999000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT CRR PURAM 4TH MAIN ROAD IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9929,Roads,Completed,NM-ALANDUR,157,666000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT C.R.R. Puram - Link Road 2nd Right Cross Street IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9930,Roads,Completed,NM-ALANDUR,157,583000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Perumal Koil Street IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9931,Roads,Completed,NM-ALANDUR,157,1832000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT M.G.R NAGAR MAIN ROAD IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9932,Roads,Completed,NM-ALANDUR,157,902000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Mettu Colony, periyapalayathamman 2nd st IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9933,Roads,Completed,NM-ALANDUR,157,1080000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Mettu Colony, periyapalayathamman 1st st IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9934,Roads,Completed,NM-ALANDUR,157,433000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Parthasarathy Nagar IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9935,Roads,Completed,NM-ALANDUR,157,999000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Mottathamman Koil Street IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9936,Roads,Completed,NM-ALANDUR,157,916000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Pillayar Koil 1st Left Cross Street IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/9937,Roads,Completed,NM-ALANDUR,157,548000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT MAROMARVEL RIVER COUNYRT 6th RIGHT CROSS STREET IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9938,Roads,Completed,NM-ALANDUR,157,500000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT MAROMARVEL RIVER COUNYRT Y 4TH RIGHT CROSS STREET IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9939,Roads,Completed,NM-ALANDUR,157,582000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT MAROMARVEL RIVER COUNYRT 5TH RIGHT CROSS STREET IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9940,Roads,Completed,NM-ALANDUR,157,467000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT MAROMARVEL RIVER COUNYRT 1ST RIGHT CROSS STREET IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9941,Roads,Completed,NM-ALANDUR,157,2993000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Navarathna Garden IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9942,Roads,Completed,NM-ALANDUR,157,1791000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT Thiruvalluvar Nagar IN DN-157, UNIT-35, ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/9995,Roads,Completed,NM-ALANDUR,157,727000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT Dr.Ambedkar Nagar 3rd Main Road IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 BR/2016-17/18509,Footpath,Completed,BR-Bus Route Roads,158,185000,"PROVIDING OF RAMPS FOR STAINLESS STEEL BUS SHELTER AT VARIOUS BUS ROUTE ROADS IN , ZONE-12",Grants,12,2016-17,2017-18 NM/2016-17/10181,Roads,Completed,NM-ALANDUR,158,612000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT Wood Greek County 1St Main Road IN DN-158,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10182,Roads,Completed,NM-ALANDUR,158,1046000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT East Lake View Street IN DN-158,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10183,Roads,Completed,NM-ALANDUR,158,218000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT East Mada Street IN DN-158,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10184,Roads,Completed,NM-ALANDUR,158,1751000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT Bajanai Koil Street IN DN-158UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10185,Roads,Completed,NM-ALANDUR,158,1133000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT Ramar koil street IN DN-158,UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1412,Parks,Completed,NM-ALANDUR,158,249000,"Annual Maintenance of Park at Sunder nagar in Dn.158,Unit-36,Zone-12.(by qualified horticulturist for one year).",Own Sources,12,2016-17,2017-18 NM/2016-17/14933,Storm Water Drain,Completed,NM-ALANDUR,158,426000,"Improvement works to side drain at Nandambakkam Colony Street in Div-158, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/14935,Storm Water Drain,Completed,NM-ALANDUR,158,545000,"Improvement works to side drain at Easwaran Koil Street in Div-158, Unit-35, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/1736,Storm Water Drain,Completed,NM-ALANDUR,158,400000,"Desilting of Storm Water Drain at various street in dn-158, unit-35, zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/19298,Roads,Completed,NM-ALANDUR,158,935000,SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DIV.158 UNIT.35 ZONE.12.,Own Sources,12,2016-17,2018-19 NM/2016-17/19342,Electrical,Completed,NM-ALANDUR,158,369000,REMOVAL AND REFIXING OF 20 NOS OF 6 MTRS MS LAMP POSTS AND 2 NOS OF KIOSK PILLAR BOX LAYING OF 660MTRS 4X16 SQMM CABLE AT VARIOUS LOCATIONS DUE TO CONSTRUCTION OF STORM WATER DRAIN IN DIV 158 IN ZONE XII,Own Sources,12,2016-17,2018-19 NM/2016-17/19373,Buildings,Completed,NM-ALANDUR,158,390000,"Improvement works to corporation office buildings at Bajanai koil street in Div-158, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/19375,Buildings,Completed,NM-ALANDUR,158,270000,"Additional improvements work ro amma unavagam in div-158, unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/19380,Buildings,Completed,NM-ALANDUR,158,310000,"Improvement works to park at sundar nagar in Div-158, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/5183,Buildings,Completed,NM-ALANDUR,158,792000,"Providing temporary shed at IDPL inner side at Junction of Ganapathypuram Colony Main Road in Div-158, U-35, Zn-12",Own Sources,12,2016-17,2017-18 NM/2016-17/7441,Buildings,Completed,NM-ALANDUR,158,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) IN FRONT OF MIOT HOSPITAL DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2018-19 NM/2016-17/7452,Storm Water Drain,Completed,NM-ALANDUR,158,805000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) INFRONT OF MIOT HOSPITAL DIV -157,UNIT -35,ZONE -12",Own Sources,12,2016-17,2018-19 NM/2016-17/8438,Footpath,Completed,NM-ALANDUR,158,984000,"Providing and Laying Interlocking paver block at Vembuliamman koil in Div-158, U-35, Zn-12(Councillor Fund)",Own Sources,12,2016-17,2017-18 NM/2016-17/9054,Storm Water Drain,Completed,NM-ALANDUR,158,657000,"Improvements to existing Side Drain at Harikrishna Colony in Div-158, Unit-35, Zone-12.(Councillor Scheme)",Own Sources,12,2016-17,2017-18 NM/2016-17/9059,Roads,Completed,NM-ALANDUR,158,412000,"Providing Silt Catch Pit and Chute Pipe at Arcot Pet Street, North Mada street, West Lakeview Street, Gangai Amman Koil Street, Harikrishna Colony in Div-158, U-35, Zn-12(Councillor Fund)",Own Sources,12,2016-17,2017-18 L/2016-17/18129,Electrical,Completed,L-Electrical,159,447700,"Removal and refixing of 78 nos of 6mtr lamp post and 21 nos of 8 mtr lamp post at various places in Division-( 156 to 159, 161) , Zone-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/0448,Buildings,Completed,NM-ALANDUR,159,451000,"Additional Improvements works for old division office building at Kamaraj street in Division - 159, Unit - 35, Zone - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/14206,Buildings,Completed,NM-ALANDUR,159,34000,REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE AT V.O.C STREET AND ANNA STREET IN DN-159 U-35 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/15734,Electrical,Completed,NM-ALANDUR,159,992900,"Removal and refixing of 34 Nos 2 mtr lamp post in center median from Shanthi petrol bunk to V.I.P gate in Div 159, Zone XII",Own Sources,12,2016-17,2016-17 NM/2016-17/1739,Storm Water Drain,Completed,NM-ALANDUR,159,106000,"Desilting of Storm Water Drain at various street in dn-159, unit-35, zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/2117,Storm Water Drain,Completed,NM-ALANDUR,159,510000,"IMPROVEMENT WORKS TO SIDE DRAIN AT VOC STREET IN DN-159,U-35,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/6338,Buildings,Completed,NM-ALANDUR,159,996000,CONSTRUCTION OF AMMAUNAVAGAM PHASE-2 WITH WATER SUPPLY AND DRAINAGE AND ELECTRICAL ARRANGEMENTS AT GST ROAD IN DN159 U35 Z-XII,Own Sources,12,2016-17,2017-18 NM/2016-17/7589,Storm Water Drain,Completed,NM-ALANDUR,159,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT G.S.T. ROAD IN FRONT OF BURIAL GROUND IN DIV -159,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7590,Storm Water Drain,Completed,NM-ALANDUR,159,805000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT G.S.T ROAD IN FRONT OF BURIAL GROUND IN DIV -159,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/8901,Culvert,Completed,NM-ALANDUR,159,817000,"DEMOLITION AND RECONSTRUCTION OF CULVERT AT KAMARAJAR STREET, AVVAIYAR STREET (COUNCILLOR FUND 2016-2017) IN DN-159 U-35 Z-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/0285,Buildings,Completed,NM-ALANDUR,160,118000,"Improvement works to Division Office at New street in Dn-160, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/0286,Buildings,Completed,NM-ALANDUR,160,409000,"Improvement works to CI Office at New street park in Dn-160, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/0288,Buildings,Completed,NM-ALANDUR,160,270000,"Improvement works to Public Convenience at Margoes street in Dn-160, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/0294,Buildings,Completed,NM-ALANDUR,160,173000,"Improvement works to Amma Unavagam and Gandhi Hospital in Div-160, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/11133,Electrical,Completed,NM-ALANDUR,160,893900,"Erection of 10 Nos of G.I lamp post with 10 Nos of 90-120 W LED fittings at Lorryshed in Div 160, Zone XII(Sch of rate 2015-16)",Own Sources,12,2016-17,2016-17 NM/2016-17/11917,Roads,Completed,NM-ALANDUR,160,997000,ATTENDING PATCH WORK AT VARIOUS STREET IN DN160 UNIT 35 ZONE 12,Own Sources,12,2016-17,2017-18 NM/2016-17/12460,Buildings,Completed,NM-ALANDUR,160,980000,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV FILTRATION ) of 2000 Litters / Hour Capacity for 1 year period in Division-160, Unit-35, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/12462,Buildings,Completed,NM-ALANDUR,160,998000,"SUPPLY, INSTALLATION AND COMMISSIONING OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION ) OF 2000 LITTERS PER HOUR CAPACITY IN DIVISION-160, UNIT-35, ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/13834,Roads,Completed,NM-ALANDUR,160,960000,"Attending Patch Work At Various Street In DN-160,U-35,ZOne-12",Own Sources,12,2016-17,2017-18 NM/2016-17/14213,Buildings,Completed,NM-ALANDUR,160,37000,REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE AT MARGOES STREET IN DN-160 U-35 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/1452,Parks,Completed,NM-ALANDUR,160,408000,ANNUAL MAINTENANCE WORKS AT NEW STREET PARK IN DN 160 U 35 Z 12 ( by Employed Qualified Horticulturist for one year),Own Sources,12,2016-17,2017-18 NM/2016-17/15120,Buildings,Completed,NM-ALANDUR,160,728000,"Proposed construction of Amma Kudineer Shed at New street in Div-160, Unit-35, Zone-12",Own Sources,12,2016-17,2016-17 NM/2016-17/15124,Buildings,Completed,NM-ALANDUR,160,243000,"Proposed construction of Physically Challenged toilet at Gandhi Hospital in Div-160, Unit-35, Zone-12",Own Sources,12,2016-17,2016-17 NM/2016-17/15735,Electrical,Completed,NM-ALANDUR,160,996200,"Removal and refixing of 38 Nos of 2mtr lamp post in center median from Alandur cement road to shanthi petrol bunk in Div 160, Z XII",Own Sources,12,2016-17,2016-17 NM/2016-17/15882,Parks,Completed,NM-ALANDUR,160,138000,"REPAIRS TO COMPOUND WALL AND PLAY MATERIAL (VARDHA CYCLONE) AT NEW STREET PARK DN-160,UNIT-35,ZONE12",Own Sources,12,2016-17,2017-18 NM/2016-17/15974,Buildings,Completed,NM-ALANDUR,160,157000,"REPAIRS DAMAGED TO TRUSS SHEET (VARDHA CYCLONE)AT GANTHI HOSPITAL SOWRI STREET IN DN-160, UNIT -35, ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/15980,Buildings,Completed,NM-ALANDUR,160,46000,"REPAIRS DAMAGED TO COMPOUND WALL (VARDHA CYCLONE )AT NEW STREET RTO OFFICE IN DN-160, UNIT -35, ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/16332,Buildings,Completed,NM-ALANDUR,160,25000,"REPAIRS WORK TO DAMAGED SIDE DRAIN (VARDHA CYCLONE) AT NEW STREET IN DN -160, UNIT -35, ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/17493,Footpath,Completed,NM-ALANDUR,160,15000,REPAIRS WORK TO DAMAGED FOOT PATH (VARDHA CYCLONE) AT NEW STREET IN DN-160 UNIT -35 ZONE 12,Own Sources,12,2016-17,2017-18 NM/2016-17/1845,Storm Water Drain,Completed,NM-ALANDUR,160,512000,"DESILTING OF SWD AT VARIOUS STREET IN DN-160,U-35,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/5422,Road Cut,Completed,NM-ALANDUR,160,710000,"Attending Road cut Restoration at Sowri Street in Din-160, U-35, Z-12",Own Sources,12,2016-17,2018-19 NM/2016-17/6355,Electrical,Completed,NM-ALANDUR,160,751400,"Wiring in second floor in Zonal office and computer room in Jal street school, Div 160, Z-XII, Alandur",Own Sources,12,2016-17,2017-18 NM/2016-17/6453,Electrical,Completed,NM-ALANDUR,160,995600,"Replacement of damaged 4x25 sq mm Alu cables of 1180 mts with 4x16 sq.mm alu cable at gst road in div 160, Z-XII, Alandur and Removal and refixing of 30 nos of 8m Oct st lamp post with single arch bkt due to swd work in gst road(Sch of rate 2015-16)",Own Sources,12,2016-17,2017-18 NM/2016-17/7595,Storm Water Drain,Completed,NM-ALANDUR,160,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT NEW STREET(NEAR RDO OFFICE) IN DIV -160,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7596,Storm Water Drain,Completed,NM-ALANDUR,160,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT NEW STREET(NEAR RTO OFFICE) IN DIV -160,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7597,Storm Water Drain,Completed,NM-ALANDUR,160,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENERAL) AT NEW STREET(NEAR LORRY STATION) IN DIV -160,UNIT -35,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7836,Electrical,Completed,NM-ALANDUR,160,946800,"Erection of 8 nos of 8m lamp post with double bracket and 16 nos of 150-165W LED fittings near Alandur Metro Rail Station at GST Road in Div-160, Z-XII, Alandur",Own Sources,12,2016-17,2017-18 NM/2016-17/8034,Roads,Completed,NM-ALANDUR,160,476000,"ATTENDING PATCH WORK AT PACHAIAMMAN KOIL STREET (FROM RAILWAY GATE TO PARRYS APARTMENTS) IN DN160, UNIT35, ZONE12",Own Sources,12,2016-17,2016-17 NM/2016-17/8111,Roads,Completed,NM-ALANDUR,160,475000,"ATTENDING PATCH WORK AT PACHAIAMMAN KOIL STREET (FROM PARRYS APARTMENTS TO CITY LINK ROAD ) IN DN160, UNIT35, ZONE12",Own Sources,12,2016-17,2016-17 NM/2016-17/8376,Buildings,Completed,NM-ALANDUR,160,767000,"Improvement works to Existing corporation buildings at New Street In Div-160, U-35, Zn-12",Own Sources,12,2016-17,2017-18 NM/2016-17/8377,Buildings,Completed,NM-ALANDUR,160,203000,"Construction of Compound wall at MKN Road in Div-160, Unit-35, Zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/13089,Electrical,Completed,NM-ALANDUR,161,650000,"Wiring in chennai primary school, AR Line MKN Road in div 161, Z-XII, Alandur",Own Sources,12,2016-17,2017-18 NM/2016-17/1403,Parks,Completed,NM-ALANDUR,161,275000,ANNUAL MAINTENANCE WORKS AT JEEVAN NAGAR PARK IN DN 161 U 36 Z 12 ( by Employed Qualified Horticulturist for one year),Own Sources,12,2016-17,2017-18 NM/2016-17/1404,Parks,Completed,NM-ALANDUR,161,259000,ANNUAL MAINTENANCE WORKS AT MURUGAN NAGAR PARK IN DN 161 U 36 Z 12 ( by Employed Qualified Horticulturist for one year),Own Sources,12,2016-17,2017-18 NM/2016-17/1406,Parks,Completed,NM-ALANDUR,161,552000,ANNUAL MAINTENANCE WORKS AT OFFICERS COLONY PARK IN DN 161 U 36 Z 12 ( by Employed Qualified Horticulturist for one year),Own Sources,12,2016-17,2017-18 NM/2016-17/15538,Buildings,Completed,NM-ALANDUR,161,546000,"PROVIDING WATER SUPPLY ARRANGEMENTS, ELECTRICAL ARRANGEMENTS AND AND SEWAGE CONNECTION ARRANGEMENTS AT E-TOILET AT M.K.N ROAD IN DN-161,U-36,Z-XII",Own Sources,12,2016-17,2018-19 NM/2016-17/15539,Buildings,Completed,NM-ALANDUR,161,412000,"MAINTENANCE AND REPAIR WORKS TO VARIOUS COC BUILDINGS IN DN-161,U-36,Z-XII",Own Sources,12,2016-17,2018-19 NM/2016-17/15874,Parks,Completed,NM-ALANDUR,161,112000,"REPAIRS TO DAMAGED FOOTPATH (VARDHA CYCLONE) AT TNGO COLONY PARK DN-161,UNIT-36,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/15977,Storm Water Drain,Completed,NM-ALANDUR,161,58000,"REPAIRS WORKS TO SIDE DRAIN (VARDHA CYCLONE) AT JEEVAN NAGAR MAIN ROAD AND 2ND STREET DN-161,UNIT-36,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/15978,Buildings,Completed,NM-ALANDUR,161,73000,"REPAIRS WORKS TO AMMA UNAVAGAM (VARDHA CYCLONE) AT VELACHERY ROAD DN-161,UNIT-36,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17267,Roads,Completed,NM-ALANDUR,161,54000,"REPAIRS WORKS TO DAMAGED ROADS (VARDHA CYCLONE) AT JEEVAN NAGAR MAIN ROAD DN-161,UNIT-36,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1747,Storm Water Drain,Completed,NM-ALANDUR,161,585000,"DESILTING OF SWD AT VARIOUS STREET IN DN-161,U-36,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/5735,Buildings,Completed,NM-ALANDUR,161,996000,CONSTRUCTION OF AMMAUNAVAGAM PHASE-2 WITH WATER SUPPLY AND DRAINAGE AND ELECTRICAL ARRANGEMENTS AT VELACHERY ROAD IN DN161 U36 Z-XII,Own Sources,12,2016-17,2016-17 NM/2016-17/7845,Buildings,Completed,NM-ALANDUR,161,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT STATION ROAD INEAR HOOKO BIN N DIV -161,UNIT -36,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7846,Buildings,Completed,NM-ALANDUR,161,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT STATION ROAD NEAR HOOKO BIN N DIV -161,UNIT -36,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7937,Buildings,Completed,NM-ALANDUR,161,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT RAM NAGAR 8TH STREET IN DIV -165,UNIT -37,ZONE -12",Own Sources,12,2016-17,2016-17 NM/2016-17/7939,Buildings,Completed,NM-ALANDUR,161,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT RAM NAGAR 8TH STREET IN DIV -165,UNIT -37,ZONE -12",Own Sources,12,2016-17,2016-17 NM/2016-17/8107,Parks,Completed,NM-ALANDUR,161,84000,ANNUAL MAINTENANCE AND PLANTATION WORKS AT JEEVAN NAGAR PARK AND OFFICERS COLONY PARK IN DN 161 U 36 Z 12,Own Sources,12,2016-17,2017-18 NM/2016-17/8528,Roads,Completed,NM-ALANDUR,161,421000,"RELAYING AND STRENGTHENING BT ROAD USING PAVER FINISHING AT JEEVAN NAGAR 1ST STREET (COUNCILLOR FUND 2016-17) IN DN-161,U-36,Z-XII",Own Sources,12,2016-17,2016-17 NM/2016-17/8583,Storm Water Drain,Completed,NM-ALANDUR,161,948000,"IMPROVEMENT WORKS TO SIDE DRAIN AT OFFICERS COLONY 4TH STREET (SOUTH SIDE) (COUNCILLOR FUND 2016-17) IN DN-161,U-36,Z-XII",Own Sources,12,2016-17,2018-19 NM/2016-17/8584,Storm Water Drain,Completed,NM-ALANDUR,161,998000,"IMPROVEMENT WORKS TO SIDE DRAIN AT SIDCO NAGAR (EAST SIDE) (COUNCILLOR FUND 2016-17) IN DN-161,U-36,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/8589,Culvert,Completed,NM-ALANDUR,161,514000,"DEMOLITION AND RECONSTRUCTION OF CULVERT AT SANJAY GANDHI NAGAR 1ST MAIN ROAD, SOUTH RAJA STREET AND LOYDS AVENUE (COUNCILLOR FUND 2016-17) IN DN-161,U-36,Z-XII",Own Sources,12,2016-17,2016-17 L/2016-17/18127,Electrical,Completed,L-Electrical,162,447700,"Removal and refixing of 78 nos of 6mtr lamp post and 21 nos of 8 mtr lamp post at various places in Divisions (160, 162 to 167) , Zone-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/10005,Roads,Completed,NM-ALANDUR,162,2852000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT HUDCO COLONY IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/10876,Electrical,Completed,NM-ALANDUR,162,922700,"Erection of 15 nos of 6m GI Lamp post with 15 nos of 90-120W LED Fittings at Thillaiganga nagar 1st main road Burial ground in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2016-17 NM/2016-17/10878,Electrical,Completed,NM-ALANDUR,162,778500,"Erection of 6 nos of 6m GI Lamp post with 12 nos of 150-165W LED Fittings at Thillaiganga nagar 2nd main road Burial ground in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2016-17 NM/2016-17/10879,Electrical,Completed,NM-ALANDUR,162,976900,"Erection of 17 nos of 6m GI Lamp post with 17 nos of 90-120W LED Fittings at Kannan Colony Burial ground in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2016-17 NM/2016-17/11433,Buildings,Completed,NM-ALANDUR,162,800000,"ADDITIONAL IMPROVEMENT WORKS TO EXISTING CORPORATION BUILDINGS AT MKN ROAD IN DN-162,U-36,Z-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/11854,Roads,Completed,NM-ALANDUR,162,840000,"PROVIDING GSB AND WMM AT MORRISON 5TH STREET IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/12156,Buildings,Completed,NM-ALANDUR,162,980000,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV FILTRATION ) of 2000 Litters / Hour Capacity for 1 year period in Division-162, Unit-36, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/12464,Electrical,Completed,NM-ALANDUR,162,501900,"Laying of 120m of 2x16 sqmm PVC Alu cable and 228m of 4x16 Sq mm PVC Alu Cable and clamping of cable at bridge portion with 12 nos of 150-165W LED Fittings at Thillaiganga nagar subway in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2018-19 NM/2016-17/12465,Buildings,Completed,NM-ALANDUR,162,998000,"SUPPLY, INSTALLATION AND COMMISSIONING OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION ) OF 2000 LITTERS PER HOUR CAPACITY IN DIVISION-162, UNIT-36, ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/12731,Buildings,Completed,NM-ALANDUR,162,509000,"ADDITIONAL WORKS TO AMMA RO WATER PLANT AT THILLAIGANGA NAGAR 4TH MAIN ROAD IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/12887,Electrical,Completed,NM-ALANDUR,162,748900,"Erection of 64 nos of 6 mtr OCTOGANAL Street lamp pole with SINGLE BRACKET in Thillai ganga nagar subway and Palavanthangal Subway in Div - 162, Z-XII.",Own Sources,12,2016-17,2016-17 NM/2016-17/13229,Storm Water Drain,Completed,NM-ALANDUR,162,531000,"IMPROVEMENTS WORKS TO SIDE DRAIN AT THILLAIGANGA NAGAR 44TH STREET IN DN-162,U-36,Z-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13230,Buildings,Completed,NM-ALANDUR,162,153000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND EB SERVICE CONNECTION OF MULTI PURPOSE BUILDING AT THILLAI GANGA NAGAR 6TH MAINROAD IN DIVISION-162,U-36,Z-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13231,Buildings,Completed,NM-ALANDUR,162,96000,"PROVIDING OVER HEAD WATER TANK AT MKN ROAD E-TOILET IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13232,Buildings,Completed,NM-ALANDUR,162,190000,"REPAIR WORKS TO EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN-162,U-36,Z-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13432,Roads,Completed,NM-ALANDUR,162,971000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AND ATTENDING PATCH WORK AT VARIOUS STREET IN DIV-162,U-36,Z-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/13992,Electrical,Completed,NM-ALANDUR,162,584400,"Erection of 10 nos of 6m GI Lamp post with 10 nos of 90-120W LED Fittings at Thiruvalluvar nagar 3rd street park in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2017-18 NM/2016-17/14041,Roads,Completed,NM-ALANDUR,162,356000,"MAINTENANCE WORKS TO EXISTING PC TOILET AT KANNAN COLONY AND MORRISON STREET IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/14375,Electrical,Completed,NM-ALANDUR,162,387100,"Erection of 6 nos of 6m GI Lamp post with 6 nos of 90-120W LED Fittings at thillaiganga nagar 34th street park in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2017-18 NM/2016-17/14474,Electrical,Completed,NM-ALANDUR,162,483700,"Erection of 8 nos of 6m GI Lamp post with 8 nos of 90-120W LED Fittings at Thiruvalluvar nagar 1st street park in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2017-18 NM/2016-17/15945,Buildings,Completed,NM-ALANDUR,162,498000,"REPAIRS TO DAMAGED COMPOUND WALL (VARDHA CYCLONE) AT KANNAN COLONY BURIAL GROUND IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/16080,Storm Water Drain,Completed,NM-ALANDUR,162,200000,"REPAIRS TO DAMAGED STORM WATER DRAIN(VARDHA CYCLONE) AT THILLAI GANGA NAGAR 3RD MAIN ROAD AND THILLAI GANGA NAGAR 23RD STREET IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/16084,Parks,Completed,NM-ALANDUR,162,23000,"REPAIRS TO DAMAGED M.S GRILL (VARDHA CYCLONE) AT THILLAI GANGA NAGAR 34TH STREET PARK IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17248,Roads,Completed,NM-ALANDUR,162,20200,"REPAIR WORKS TO DAMAGED BT ROAD(VARDHA CYCLONE) AT THILLAI GANGA NAGAR 3RD MAIN ROAD, THILLAI GANGA NAGAR 23RD STREET AND THILLAI GANGA 1ST MAIN ROAD IN DN-162,UNIT-36,Z-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/1746,Storm Water Drain,Completed,NM-ALANDUR,162,585000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET (THILLAI GANGA NAGAR,THIRUVALLUR NAGAR,KANNAN COLONY,NOBLE STREETS AND MORRISON STREETS) IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17494,Buildings,Completed,NM-ALANDUR,162,304000,"CONSTRUCTION OF TOILET AND WATER ARRANGEMENTS AT MORRISON STREET ANGANWADI CENTRE IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17654,Buildings,Completed,NM-ALANDUR,162,159000,"IMPROVEMENTS WORKS TO AMMA KUDINEER PLANT AT THILLAI GANGA NAGAR 4TH MAIN ROAD IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17655,Storm Water Drain,Completed,NM-ALANDUR,162,620000,"IMPROVEMENTS WORKS TO EXISTING STORM WATER DRAIN AT THILLAIGANGA NAGAR 1ST MAIN ROAD IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17656,Buildings,Completed,NM-ALANDUR,162,40000,"IMPROVEMENTS WORKS TO NAMMA TOILET AT THILLAI GANGA NAGAR 4TH MAIN ROAD IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17657,Storm Water Drain,Completed,NM-ALANDUR,162,116000,"REPAIR WORKS TO EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/18514,Buildings,Completed,NM-ALANDUR,162,804000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET WITH BIO DIGESTER SEPTIC Tank AT THILLAIGANGA NAGAR 45TH STREET IN DIV -162,UNIT -36,ZONE -12",Own Sources,12,2016-17,2018-19 NM/2016-17/18515,Buildings,Completed,NM-ALANDUR,162,314000,"Providing Water supply , Drainage connection and Electrical supply. and other arrangements in E-Toilet at T.G nagar 45th street in Division-162, Unit-36, Zone-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/18553,Buildings,Completed,NM-ALANDUR,162,2050000,"Proposed Compost yard at Thillaiganga nagar 1st main road burial ground in division-162, unit-36,zone-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/19897,Electrical,Completed,NM-ALANDUR,162,410500,"Laying of 220m of 2x16 sqmm PVC Alu cable and 224m of 4x16 Sq mm PVC Alu Cable and clamping of cable at bridge portion with 6 nos of 150-165W LED Fittings at Palavanthangal subway in Division 162 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2018-19 NM/2016-17/2035,Culvert,Completed,NM-ALANDUR,162,400000,"Providing box culvert at Noble 1st street for kannan colony main road crossing purpose in division-162,unit-36,zone-12",Own Sources,12,2016-17,2017-18 NM/2016-17/5240,Electrical,Completed,NM-ALANDUR,162,224000,"Construction of Amma Unavagam Phase - II at MKN Road in Div-162, U-36, Zn-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/5447,Buildings,Completed,NM-ALANDUR,162,978000,"REPAIR AND SERVICE WORK TO GASIFIER CREMATORIUM AT KANNAN COLONY BURIAL GROUND IN DN -162, U-36 Z-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/5448,Buildings,Completed,NM-ALANDUR,162,998000,"CONSTRUCTION OF AMMAUNAVAGAM PHASE-II AT MKN Road IN DN162 ,U36, Z12",Own Sources,12,2016-17,2016-17 NM/2016-17/5521,Buildings,Completed,NM-ALANDUR,162,88000,"DEMOLITION OF PUBLIC CONVENIENCE AT MKN ROAD IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/5721,Buildings,Completed,NM-ALANDUR,162,893000,"CONSTRUCTION OF COMPOUND WALL,WATER SUPPLY AND DRAINAGE ARRANGEMENT IN EXISTING CORPORATION BUILDING AT MKN ROAD IN DN 162, U.36 Z.12",Own Sources,12,2016-17,2016-17 NM/2016-17/6281,Storm Water Drain,Completed,NM-ALANDUR,162,721000,"IMPROVEMENTS WORKS TO SIDE DRAIN AT THILLAI GANGA NAGAR 1ST MAIN ROAD(FROM JUNCTION OF DURAIRAJ STREET TO JUNCTION OF THILLAI GANGA NAGAR 5TH MAIN ROAD) IN DN-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/6437,Culvert,Completed,NM-ALANDUR,162,255000,"PROVIDING BOX CULVERT AT THILLAI GANGA NAGAR 10TH STREET FOR THILLAI GANGA NAGAR 1ST MAIN ROAD CROSSING PURPOSE IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/7908,Electrical,Completed,NM-ALANDUR,162,970000,"Wiring in Kannan Colony Burial Ground in Div - 162, Z-XII, Alandur",Own Sources,12,2016-17,2017-18 NM/2016-17/7940,Buildings,Completed,NM-ALANDUR,162,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT MKN ROAD IN DIV -162,UNIT -36,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/7942,Buildings,Completed,NM-ALANDUR,162,629000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT MKN ROAD IN DIV -162,UNIT -36,ZONE -12",Own Sources,12,2016-17,2017-18 NM/2016-17/9098,Storm Water Drain,Completed,NM-ALANDUR,162,997000,"IMPROVEMENTS WORKS TO EXISTING STORM WATER DRAIN AT THILLAIGANGA NAGAR 6TH MAIN ROAD TO THILLAIGANGA NAGAR 48TH STREET(COUNCILLOR FUND) IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9100,Storm Water Drain,Completed,NM-ALANDUR,162,716000,"IMPROVEMENTS WORKS TO EXISTING STORM WATER DRAIN AT THILLAIGANGA NAGAR 23RD STREET(COUNCILLOR FUND) IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9283,Buildings,Completed,NM-ALANDUR,162,126000,"Providing Water supply , Drainage connection and Electrical supply. and other arrangements in E-Toilet at MKN Road in Division-162, Unit-36, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9289,Buildings,Completed,NM-ALANDUR,162,410000,"Providing of under ground sump, Floor tiles, Compound wall and Grill gate at amma kudineer plant at Thillaiganga nagar 4th main road Division-162, Unit-36, Zone-12.",Own Sources,12,2016-17,2018-19 BR/2016-17/17547,Roads,Completed,BR-Bus Route Roads,163,1700000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at Palandiamman koil st,Thiruvalluvar st,New colony main road in Zone 12",Loans,12,2016-17,2017-18 NM/2016-17/1043,Storm Water Drain,Completed,NM-ALANDUR,163,175000,improvements and Repair works to side drain at Errikarii street (jn of parthasarthy nagar 5th st to jn of new Colony main road) in Dn163 u.36.z.12,Own Sources,12,2016-17,2016-17 NM/2016-17/1044,Storm Water Drain,Completed,NM-ALANDUR,163,135000,IMPROVEMENTS WORKS OF SIDE RAIN AT PARTHASARATAHY 2TH STREET(LANE) DN-163 Z-12,Own Sources,12,2016-17,2016-17 NM/2016-17/12185,Buildings,Completed,NM-ALANDUR,163,400000,"PROPOSED CONSTRUCTION OF GATE AND GATE PILLARS AND PROVIDING PATH WAY FOR KARYA MANDAPAM AT BALAKRISHNAPURAM BURIAL GROUND IN DN.163, U - 36, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/12189,Electrical,Completed,NM-ALANDUR,163,472500,"Laying of 248m of 4x16 Sq mm PVC Alu Cable and clamping of cable at bridge portion with 12 nos of 150-165W LED Fittings at St.Thomas Mount Subway in Division 163 ,Zone XII. (Sch of rate 2015-16)",Own Sources,12,2016-17,2018-19 NM/2016-17/12886,Electrical,Completed,NM-ALANDUR,163,666000,"Erection of 35 nos of 6 mtr OCTOGANAL Street lamp pole with SINGLE BRACKET and 15 nos of 8 mtr OCTOGANAL Street lamp pole with SINGLE BRACKETin Mount subway Div 163 and GST Road , Z-XII",Own Sources,12,2016-17,2016-17 NM/2016-17/12981,Buildings,Completed,NM-ALANDUR,163,443000,"IMPROVEMENT WORKS ,PROVIDING INTERLOCKING BLOCKS AND GRILL WORK FOR PARKING AREA IN FRONT OF AMMAUNAVAGAM PHASE - 2 AT MEDAVAKKAM HIGH ROAD ( OPP TO ERIKARAI ROAD ) IN DN.163, U - 36, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/13253,Storm Water Drain,Completed,NM-ALANDUR,163,137000,Improvements works to side drain at shanthi nagar 1st cross street in dn-163 u-36 z-12.,Own Sources,12,2016-17,2016-17 NM/2016-17/14595,Buildings,Completed,NM-ALANDUR,163,45400,REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE AT MANNADIYAMMAN KOIL STREET IN DN-163 U-36 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/15822,Storm Water Drain,Completed,NM-ALANDUR,163,9000,REPAIRS TO EXISTING SIDE DRAIN (VARDAH CYCLONE) AT PARTHASARATHY NAGAR 3RD STREET IN DN-163 U-36 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/16682,Roads,Completed,NM-ALANDUR,163,14000,SUPPLYING AND FIXING DAMAGED STREET NAME BOARD (VARDHA CYCLONE) AT BALAKRISHNAPURAM 1ST STREET IN DN-163 U-36 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/17283,Roads,Completed,NM-ALANDUR,163,25300,STRENTHNING AND LAYING DAMAGE ROAD (VARDAH CYCLONE) AT PARTHASARATHY NAGAR 3RD STREET AND EAST KARIKALAN 1ST STREET (LANE) IN DN-163 U-36 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/1788,Storm Water Drain,Completed,NM-ALANDUR,163,500000,"Desilting of Storm Water Drain at Various Streets in Dn-163,U-36,Z-12",Deposit-Asset,12,2016-17,2017-18 NM/2016-17/18524,Buildings,Completed,NM-ALANDUR,163,629000,SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT MEDAVAKKAM HIGH ROAD (JN OF JEEVAN NAGAR 5TH STREET) IN DN 163 U.36 Z.12,Own Sources,12,2016-17,2018-19 NM/2016-17/18549,Buildings,Completed,NM-ALANDUR,163,2050000,"Proposed Compost yard at Balakrishnapuram burial ground in division-163, unit-36,zone-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/18912,Roads,Completed,NM-ALANDUR,163,971000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN AT VARIOUS STREETS IN DIV 163,UNIT 36,ZONE 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/2115,Parks,Completed,NM-ALANDUR,163,266000,ANNUAL MAINTENANCE WORKS AT SHANTHI NAGAR 4TH STREET PARK AND PLAY FIELDS IN DN 163 U.36 Z.12{BY EMPLOYED QUALIFIED HORTICULTURIST FOR ONE YEAR},Own Sources,12,2016-17,2017-18 NM/2016-17/5317,Buildings,Completed,NM-ALANDUR,163,850000,"IMPROVEMENTS WORKS TO AMMAUNAVAGAM PHASE-2 AT MADAVAKKAM HIGH ROAD (OPP TO ERIKKARAI STREET) IN DN-163, U,36 Z,12.",Own Sources,12,2016-17,2016-17 NM/2016-17/5327,Buildings,Completed,NM-ALANDUR,163,990000,PROVIDING AMMAUNAVAGAM PHASE-2 AT MADAVAKKAM HIGH ROAD (ERIKKARAI STREET) IN DN163 U36 Z12,Own Sources,12,2016-17,2016-17 NM/2016-17/5343,Buildings,Completed,NM-ALANDUR,163,356000,"WATER SUPPLY,DRAINAGE AND ELECTRICAL WORKS TO AMMAUNAVAM PHASE-2 AT MADAVAKKAM HIGH ROAD (OPP TO ERRIKARI STREET ) IN DN 163 U.36 Z.12",Own Sources,12,2016-17,2016-17 NM/2016-17/5634,Buildings,Completed,NM-ALANDUR,163,155000,IMPROVEMENT WORK TO C.I OFFICE AT MANNADIYAMMAN KOIL STREET IN DN-163 U-36 Z-12,Own Sources,12,2016-17,2016-17 NM/2016-17/6405,Roads,Completed,NM-ALANDUR,163,570000,"WIDENING,LAYING PAVER BLOCK AT ERIKKARAI STREET(JN OF MADAVAKKAM HIGH ROAD TO PARTHASARATHY 1ST STREET)IN DN163,U-36,Z-12",Own Sources,12,2016-17,2016-17 NM/2016-17/6410,Buildings,Completed,NM-ALANDUR,163,41000,"REPAIR WORKS TO AMMUNAVAGAM AT BALAKRISHNAPURAM MAIN ROAD IN DN-163,U-36,Z-12",Own Sources,12,2016-17,2016-17 NM/2016-17/6411,Buildings,Completed,NM-ALANDUR,163,28000,"REPAIR WORKS TO BALAKRISHNAPURAM BURIAL GROUND AT BALAKRISHNAPURAM IN DN-163,U-36, Z-12",Own Sources,12,2016-17,2016-17 NM/2016-17/6425,Storm Water Drain,Completed,NM-ALANDUR,163,850000,"IMPROVEMENT WORKS TO SIDE DRAIN AT EAST KARIKALAN 2ND STREET N DN-163,U-36,Z-12",Own Sources,12,2016-17,2016-17 NM/2016-17/7956,Buildings,Completed,NM-ALANDUR,163,629000,SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (LADIES) AT NEAR CITY LINK ROAD BALAKRISHNAPURAM BURIAL GROUND IN DN 163 U.36 Z.12,Own Sources,12,2016-17,2017-18 NM/2016-17/7957,Buildings,Completed,NM-ALANDUR,163,629000,SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (GENTS) AT NEAR CITY LINK ROAD BALAKRISHNAPURAM BURIAL GROUND IN DN 163 U.36 Z.12,Own Sources,12,2016-17,2017-18 NM/2016-17/9006,Roads,Completed,NM-ALANDUR,163,495000,Relaying the road by paver finisher at BALAKRISHNAPURAM 1ST STREEET in dn-163 u-36 z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/9008,Roads,Completed,NM-ALANDUR,163,507000,Relaying the road by paver finisher at BALAKRISHNAPURAM 2ND STREET in dn-163 u-36 z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/9013,Roads,Completed,NM-ALANDUR,163,449000,Relaying the road by paver finisher at LABOUR WELL STREET in dn-163 u-36 z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/9016,Roads,Completed,NM-ALANDUR,163,330000,Relaying the road by paver finisher at MASTHAN GORI STREET in dn-163 u-36 z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/9017,Roads,Completed,NM-ALANDUR,163,613000,Relaying the road by paver finisher at PARAMESHWARI NAGAR MAIN ROAD STREET in dn-163 u-36 z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/9018,Roads,Completed,NM-ALANDUR,163,525000,Relaying the road by paver finisher at RAMAKRISHNAPURAM 1ST STREET in dn-163 u-36 z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/9023,Buildings,Completed,NM-ALANDUR,163,971000,SUPPLYING AND FIXING OF STREET NAME BOARD AT VARIOUS STREET IN DN-163 U-36 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/9898,Roads,Completed,NM-ALANDUR,163,1369000,PROPOSED LAYING M30 CEMENT CONCRETE ROAD AT SANNATHI STREET IN DN-163 U-36 Z-12,Own Sources,12,2016-17,2017-18 BR/2016-17/18164,Roads,Completed,BR-Bus Route Roads,164,6920000,"Repair and Restoration of Relaying Road by Paver Finisher Work at Manapaakam - Mugalivakkam Main Road in Dn-157,Zone-12",Own Sources,12,2016-17,2017-18 BR/2016-17/18508,Road Cut,Completed,BR-Bus Route Roads,164,1570000,Restoration of Road Cut Made by CMWSSB at MMTC Colony Main Road Div -164 Zone -12,Deposit Works,12,2016-17,2017-18 NM/2016-17/0781,Roads,Completed,NM-ALANDUR,164,970000,"Attend the Patch works (Bituminous concrete) at various street in division-164, unit-37, zone-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/0902,Buildings,Completed,NM-ALANDUR,164,900000,"Additional improvement works to Existing building of urban primary health centre at new colony 2nd cross street in division-164, unit-37, zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/15903,Parks,Completed,NM-ALANDUR,164,123000,"Repair works at Nanganallur 29th street children`s park (Due to varudha cyclone) in division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/16179,Storm Water Drain,Completed,NM-ALANDUR,164,99000,"Repair works for Storm water drain at Nanganallur 3rd main road (Due to varudha cyclone) in division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/16205,Buildings,Completed,NM-ALANDUR,164,85000,"Repair works for Amma unavagam at Nanganallur 4th MAIN ROAD (Due to varudha cyclone) in division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/16212,Buildings,Completed,NM-ALANDUR,164,12000,"Repair works for Community hall at New colony 1st street (Due to varudha cyclone) in division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17278,Roads,Completed,NM-ALANDUR,164,64000,"Repair works for Road at Nanganallur 3rd main road ( Due to varudha cyclone) in Dn-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/1741,Storm Water Drain,Completed,NM-ALANDUR,164,585000,"Desilting of strom water drains at Nanganallur And Nehru colony Area's in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17496,Footpath,Completed,NM-ALANDUR,164,23500,"Repair works for Foot path at Nanganallur 14th street (Due to varudha cyclone) in division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/18723,Buildings,Completed,NM-ALANDUR,164,250000,"Maintenance works to Anganvadi at ellaimuthamman koil street and Division office at Krishnasamy street in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/18725,Buildings,Completed,NM-ALANDUR,164,413000,"Maintenance works to Anganvadi and UPHC at New colony 2nd street in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/18726,Storm Water Drain,Completed,NM-ALANDUR,164,310000,"Maintenance works to Existing side drain at Nanganallur 29th street, Nanganallur 23rd street in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/19072,Roads,Completed,NM-ALANDUR,164,859000,"ATTENDING BT PATCH WORK AT VARIOUS STREETS IN DIV 164,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/2039,Storm Water Drain,Completed,NM-ALANDUR,164,420000,"Providing of under ground sump, Floor tiles, Compound wall and Grill gate at amma kudineer plant at Nanganallur 29th street and Road workers rest room at krishnasamy street in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/2484,Storm Water Drain,Completed,NM-ALANDUR,164,535000,"Maintenance works to Existing strom water drain at Nanganallur 21st street, Nanganallur 33rd street, Nangianallur 4th main road, college road and Nanganallur 1st main road in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/3301,Roads,Completed,NM-ALANDUR,164,200000,"Providing Compactor bin platform at various street in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/6485,Buildings,Completed,NM-ALANDUR,164,930000,"Improvements work in Anganwadi at New colony in Division-164,Unit-37,Zone-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/7799,Roads,Completed,NM-ALANDUR,164,953000,"Road cut restoration at various streets in Division-164, Unit-37, Zone-12.",Deposit Works,12,2016-17,2016-17 NM/2016-17/7802,Parks,Completed,NM-ALANDUR,164,629000,"Supplying and installation for Electronic toilet (Gents) at Nanganallur 48th street in Division-167, Unit-37, Zone-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/7803,Buildings,Completed,NM-ALANDUR,164,629000,"Supplying and installation for Electronic toilet (Ladies) at Nanganallur 48th street in Division-167, Unit-37, Zone-12",Own Sources,12,2016-17,2018-19 NM/2016-17/7804,Buildings,Completed,NM-ALANDUR,164,629000,"Supplying and installation for Electronic toilet (General) at Nanganallur 4th main road in Division-164, Unit-37, Zone-12.",Own Sources,12,2016-17,2018-19 NM/2016-17/8366,Buildings,Completed,NM-ALANDUR,164,600000,"Providing Water supply , Drainage connection and Electrical supply. and other arrangements in E-Toilet at Krishnasdamy street, Nanganallur 4th main road and Nanganallur 1st main road in Division-164, Unit-37, Zone.",Own Sources,12,2016-17,2017-18 NM/2016-17/8998,Roads,Completed,NM-ALANDUR,164,965000,"Strenthening and relaying of Cement concrete road at nanganallur 28th street in Division-164, Unit-37, Zone-12. (Councillor fund)",Own Sources,12,2016-17,2017-18 NM/2016-17/9061,Roads,Completed,NM-ALANDUR,164,890000,"Strengthening and relaying of cement concrete road at Krishnssamy street Extn,college cross street in Division-164, Unit-37, Zone-12. (Councillor fund)",Own Sources,12,2016-17,2017-18 NM/2016-17/9065,Roads,Completed,NM-ALANDUR,164,990000,"Strengthening and relaying of cement concrete road at Jayaraman street Extn in Division-164, Unit-37, Zone-12. (Councillor fund)",Own Sources,12,2016-17,2017-18 NM/2016-17/10218,Roads,Completed,NM-ALANDUR,165,145000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT BHARATHIDASAN NAGAR 2ND CROSS STREET IN DN-165,UNIT-37,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10227,Roads,Completed,NM-ALANDUR,165,404000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT BALAJI NAGAR 4TH STREET IN DN-165,UNIT-37,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10228,Roads,Completed,NM-ALANDUR,165,495000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT MUTHIYAL REDDY NAGAR 1ST STREET IN DN-165,UNIT-37,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10230,Roads,Completed,NM-ALANDUR,165,725000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT SUNDRAMOORTHY STREET SOUTH IN DN-165,UNIT-37,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/10231,Roads,Completed,NM-ALANDUR,165,589000,"RELAYING OF DAMAGED BT ROAD BY USING PAVER FINISING AT MUTHIYAL REDDY NAGAR MAIN ROAD IN DN-165,UNIT-37,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/12773,Storm Water Drain,Completed,NM-ALANDUR,165,736000,"DESILTING OF VEERANGAL ODAI (FROM JN OF INDRA NAGAR TO BHUVANESHVARI NAGAR 4TH STREET) IN DN-165, UNIT-37, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/13336,Roads,Completed,NM-ALANDUR,165,572000,ATTENDING THE BT PATCH WORK AT VARIOUS IN DIVISION 165 UNIT 37 ZONE 12.,Own Sources,12,2016-17,2017-18 NM/2016-17/13353,Roads,Completed,NM-ALANDUR,165,279000,PROVIDING AND LAYING OF WET MIX MECADAM AT ODAI STREET IN DIVISION 165 UNIT 37 ZONE 12.,Own Sources,12,2016-17,2017-18 NM/2016-17/13355,Roads,Completed,NM-ALANDUR,165,64000,PROVIDING AND LAYING INTER LOCKING BLOCKS AT NEW COLONY 8TH STREET IN DIVISION 165 UNIT 37 ZONE 12.,Own Sources,12,2016-17,2017-18 NM/2016-17/16402,Parks,Completed,NM-ALANDUR,165,129000,REPAIRS TO DAMAGED PARK ( vardha cyclone ) AT BHARATH NAGAR PARK IN DIV 165 UNIT 37 ZONE 12,Own Sources,12,2016-17,2017-18 NM/2016-17/16403,Parks,Completed,NM-ALANDUR,165,91000,REPAIRS TO DAMAGED PARK ( vardha cyclone ) AT SOUTH SECTOR PARK (KUNDRAKUDI NAGAR) IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2016-17,2017-18 NM/2016-17/16406,Storm Water Drain,Completed,NM-ALANDUR,165,34000,REPAIRS TO DAMAGED SIDE DRAIN ( vardha cyclone ) AT KESARI NAGAR MAIN ROAD IN DIV 165 UNIT 37 ZONE 12,Own Sources,12,2016-17,2017-18 NM/2016-17/16408,Storm Water Drain,Completed,NM-ALANDUR,165,678000,REPAIRS TO DAMAGED SIDE DRAIN ( vardha cyclone ) AT BALAJI NAGAR 17TH STREET IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2016-17,2017-18 NM/2016-17/16410,Buildings,Completed,NM-ALANDUR,165,1257000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET AT INDRA NAGAR 2ND STREET IN DIV -165,UNIT -37,ZONE -12",Own Sources,12,2016-17,2018-19 NM/2016-17/16413,Buildings,Completed,NM-ALANDUR,165,46000,"PROVIDING AND LAYING OF WET MIX MECADAM AT VARIOUS STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17269,Roads,Completed,NM-ALANDUR,165,218000,REPAIRS TO DAMAGED FOOTPATH ( vardha cyclone ) ATVARIOUS STREET IN DIV 165 UNIT 37 ZONE 12,Own Sources,12,2016-17,2017-18 NM/2016-17/17476,Buildings,Completed,NM-ALANDUR,165,390000,"Providing Water supply , Drainage connection and Electrical supply. and other arrangements in E-Toilet at Indra nagar 2nd street in Division-165, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17841,Buildings,Completed,NM-ALANDUR,165,96000,"Improvement works to Public Convenience at Nanganallur 11th street in Div-165, Unit-37, Zone-12",Own Sources,12,2016-17,2018-19 NM/2016-17/17843,Parks,Completed,NM-ALANDUR,165,201000,"PROVIDING SIT CATCH PIT,PIPE LAYING WORK AND OTHER REPAIR WORKS AT VARIOUS STREETS IN DIV-165, UNIT-37, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17844,Parks,Completed,NM-ALANDUR,165,265000,"IMPROVEMENTS WORKS TO SIDE DRAIN AT GOTHAVARI STREET IN DIV-165, UNIT-35,ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17988,Buildings,Completed,NM-ALANDUR,165,169000,"Improvement works to Chennai Primary School at Vanuvampet in Div 165,Unit 37,Zone 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/1816,Storm Water Drain,Completed,NM-ALANDUR,165,585000,"DESILTING OF STORM WATER DRAINS AT VARIOUS STREET ( NILAMANGAI NAGAR,BALAJI NAGAR,VEL NAGAR,SOUTH SECTOR,INCOM TAX COLONY,BHARATH NAGAR AREAS) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/19139,Culvert,Completed,NM-ALANDUR,165,221000,"CONSTRUCTION OF CULVERT GODHAVARI STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/19140,Culvert,Completed,NM-ALANDUR,165,245000,"IMPROVEMENT WORKS TO SIDE DRAIN AT SAKTHI NAGAR EXTN STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/19141,Culvert,Completed,NM-ALANDUR,165,265000,"IMPROVEMENT WORKS TO SIDE DRAIN AT THAMARAI STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/5088,Storm Water Drain,Completed,NM-ALANDUR,165,990000,"IMPROVEMENT WORKS TO STORM WATER DRAIN AT BALAJI NAGAR MAIN ROAD (FROM JN OF KURINJI STREET TO LAKSHMI NAGAR 1ST CROSS STREET) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/5090,Storm Water Drain,Completed,NM-ALANDUR,165,920000,"IMPROVEMENT WORKS TO SIDE DRAIN AT KESARI NAGAR 7TH STREET ( Counsillor fund 2016-17) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/5091,Storm Water Drain,Completed,NM-ALANDUR,165,941000,"IMPROVEMENT WORK TO STORM WATER DRAIN AT SENTHIL ANDAVAR STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/5193,Buildings,Completed,NM-ALANDUR,165,965000,"Proposed construction of Additional Amma unavagam at Balaji nagar Main Road in Div-165, U-37, Zn-12",Own Sources,12,2016-17,2018-19 NM/2016-17/5231,Buildings,Completed,NM-ALANDUR,165,999000,"PROVIDING WATER,DRAINAGE SUPPLY,ALUMINIUM PARTITION AND COMPOUNT WALL WORK TO THE ADDITIONAL AMMA UNVAGAM AT BALAJI NAGAR MAIN ROAD IN DIVISION 165 UNIT ZONE 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/6498,Storm Water Drain,Completed,NM-ALANDUR,165,614000,"IMPROVEMENT WORKS TO SIDE DRAIN AT AGASTHIYAR STREET IN DIV 165,UNIT 37,ZONE 12.(Counsillor fund 2016-17)",Own Sources,12,2016-17,2018-19 NM/2016-17/8192,Roads,Completed,NM-ALANDUR,165,259000,"Providing Compactor bin platform at various streets in Division-165, Unit-37, Zone-12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9157,Buildings,Completed,NM-ALANDUR,165,440000,PROVIDING PLATFORM FOR E-TOILET AT RAM NAGAR 8TH STREET (RAM NAGAR 2ND MAIN ROAD) IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2016-17,2017-18 NM/2016-17/9160,Buildings,Completed,NM-ALANDUR,165,523000,"PROVIDING SS PLAY APPARATUS BALAJI NAGAR PARK (Counsillor fund 2016-17) IN DIV-165,UNIT-37,ZONE-12",Own Sources,12,2016-17,2018-19 NM/2016-17/9950,Roads,Completed,NM-ALANDUR,165,725000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT SURENDRA NAGAR 11TH CROSS STREET IN DN-165, UNIT-37, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/9956,Roads,Completed,NM-ALANDUR,165,2209000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT RAIL WAY COLONY 5TH LAYOUT IN DN-165, UNIT-37, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/9957,Roads,Completed,NM-ALANDUR,165,1775000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT ANDAL NAGAR WEST 2ND STREETIN DN-165, UNIT-75, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/9959,Roads,Completed,NM-ALANDUR,165,1775000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT ANDAL NAGAR WEST 1ST STREETIN DN-165, UNIT-75, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/9960,Roads,Completed,NM-ALANDUR,165,808000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT SURENDRA NAGAR 6th EXTN CROSS STREETIN DN-165, UNIT-75, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/9961,Roads,Completed,NM-ALANDUR,165,1775000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT SUNDRAMOORTHY STREET NORTHIN DN-165, UNIT-75, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/9962,Roads,Completed,NM-ALANDUR,165,689000,"RELAYING OF DAMAGED CC ROAD BY USING RMC M30 AT THAMODARAN STREET IN DN-165, UNIT-75, ZONE-12",Own Sources,12,2016-17,2017-18 NM/2016-17/11676,Storm Water Drain,Completed,NM-ALANDUR,166,439000,"IMPROVEMENTS TO THE EXISTING SWD AT KAMARAJAR STREET (PART) IN DN-166, U-37,Z-12.",Own Sources,12,2016-17,2016-17 NM/2016-17/11834,Buildings,Completed,NM-ALANDUR,166,368000,"REPAIRS AND IMPROVEMENT WORKS TO THE CORPORATION INSTITUTIONS AND LAYING PIPE LINE AND CATCH PIT TO THE CC ROAD AT BURMA THAMIZHLAR COLONY 1ST STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/12175,Buildings,Completed,NM-ALANDUR,166,998000,"Supply, Installation, Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity in Dn - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/12176,Buildings,Completed,NM-ALANDUR,166,980000,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres /Hour Capacity for 1 Year Period in Dn - 166 , U - 37, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/12177,Culvert,Completed,NM-ALANDUR,166,247000,"DEMOLITION AND RECONSTRUCTION OF CULVERT AT BV NAGAR 7TH STREET IN DN-166,U-37,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/12755,Road Cut,Completed,NM-ALANDUR,166,983000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (NEMELI PROJECT) AT NEHRU NEDUNCHALAI IN DN - 166, U - 37, Z - 12.",Deposit Works,12,2016-17,2017-18 NM/2016-17/14043,Buildings,Completed,NM-ALANDUR,166,113000,"IMPROVEMENT TO THE PUBLIC CONVENIENCE AT BURMA THAMIZHER COLONY IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/16695,Parks,Completed,NM-ALANDUR,166,179000,REPAIR TO COMPOUND WALL PATH WAY & PLAY FIELD AREA (VARDHA CYCLONE) AT ANNA PARK IN DN-166 U-37 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/16696,Footpath,Completed,NM-ALANDUR,166,14000,REPAIR TO FOOT PATH (VARDHA CYCLONE) AT B.V NAGAR 3RD MAIN ROAD IN DN-166 U-37 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/17003,Buildings,Completed,NM-ALANDUR,166,340000,"providing water & electrical arrangement E-toilet at B.V Nagar 3rd main road and Nehru neduchalai In DN-166,U-37,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17004,Buildings,Completed,NM-ALANDUR,166,116000,"Providing ramp & Stainless steel at various Street In DN-166,U-37,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17005,Buildings,Completed,NM-ALANDUR,166,260000,"Providing Silt Catch Pit at various street in DN-166,U-37,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17020,Roads,Completed,NM-ALANDUR,166,246000,"SUPPLYING AND FIXING RETRO REFLECTIVE STAINLESS STEEL NAME BOARD AT VARIOUS STREET DN-166,U-35,Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/1797,Storm Water Drain,Completed,NM-ALANDUR,166,584000,"DESILTING OF STORM WATER DRAIN AT B.V.NAGAR, RAGHUPATHY NAGAR, TEACHERS COLONY, N.G.O COLONY, NEHRU COLONY , KAMARAJ STREET, KAMARAJ STREET EXTN AND NETHAJI STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/18402,Buildings,Completed,NM-ALANDUR,166,250000,"MAINTENANCE AND REPAIR WORKS TO VARIOUS COC BUILDINGS IN DN-166,U-37,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/18670,Buildings,Completed,NM-ALANDUR,166,350000,"IMPROVEMENT WORKS TO LIBARAY BUILDING AT TEACHERS COLONY 2ND CROSS STREET IN DN-166,U-37,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/18671,Buildings,Completed,NM-ALANDUR,166,115000,"REPAIR WORKS (ELECTRICAL WORK AND PLUMBING WORK )TO VARIOUS COC BUILDINGS IN DN-166,U-37,Z-XII",Own Sources,12,2016-17,2017-18 NM/2016-17/2144,Road Cut,Completed,NM-ALANDUR,166,981000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT B.V. NAGAR 3RD MAIN ROAD FROM B.V. NAGAR 1ST CROSS STREET TO N.G.O COLONY 4TH STREET (FOR THE WATER SUPPLY ARRANGEMENTS TO COASTAL GUARD MAIN BUILDING) IN DN - 166, U - 37, Z - 12.",Deposit Works,12,2016-17,2017-18 NM/2016-17/2150,Road Cut,Completed,NM-ALANDUR,166,824000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT B.V. NAGAR 1ST CROSS STREET(60 FEET ROAD) FROM NEHRU NEDUNCHALAI TO B.V. NAGAR 3RD MAIN ROAD (FOR THE WATER SUPPLY ARRANGEMENTS TO COASTAL GUARD MAIN BUILDING) IN DN - 166, U - 37, Z - 12.",Deposit Works,12,2016-17,2017-18 NM/2016-17/4394,Buildings,Completed,NM-ALANDUR,166,984000,"ALTERATION WORK TO EXISTING HEALTH CENTRE ( UNDER NUHM SCHEME) AT K.K. NAGAR MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/4769,Roads,Completed,NM-ALANDUR,166,162000,"PROVIDING GARBAGE COMPACTOR BINS AT VARIOUS STREETS IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/6433,Storm Water Drain,Completed,NM-ALANDUR,166,861000,"CONSTRUCTION OF SIDE DRAIN AT B.V. NAGAR 14TH STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/6475,Buildings,Completed,NM-ALANDUR,166,858000,"PROPOSED CONSTRUCTION OF ROAD SIDE GYM AT K.K. NAGAR MAIN ROAD (UNDER COUNCILLOR FUND) IN DN - 166, U - 37, Z- 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/7822,Buildings,Completed,NM-ALANDUR,166,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (MALE) AT B.V. NAGAR 3RD MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/7828,Buildings,Completed,NM-ALANDUR,166,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (FEMALE) AT B.V. NAGAR 3RD MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/7830,Buildings,Completed,NM-ALANDUR,166,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (FEMALE) AT NEHRU NEDUNCHALAI IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/7831,Buildings,Completed,NM-ALANDUR,166,628000,"SUPPLY AND INSTALLATION FOR ELECTRONIC TOILET (MALE) AT NEHRU NEDUNCHALAI IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8649,Storm Water Drain,Completed,NM-ALANDUR,166,970000,"CONSTRUCTION OF SWD AT B.V. NAGAR 2ND CROSS STREET (EAST SIDE) (FROM THE JN OF B.V NAGAR 13TH STREET TO B.V. NAGAR 10TH STREET) IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/8968,Roads,Completed,NM-ALANDUR,166,1144000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT B.V. NAGAR 11TH STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8974,Roads,Completed,NM-ALANDUR,166,354000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT NEHRU COLONY 3RD STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8976,Roads,Completed,NM-ALANDUR,166,207000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT NEHRU COLONY 3RD CROSS STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8985,Roads,Completed,NM-ALANDUR,166,307000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT NEHRU COLONY 4TH STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8986,Roads,Completed,NM-ALANDUR,166,436000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT NEHRU COLONY 5TH STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9197,Roads,Completed,NM-ALANDUR,166,750000,"FORMING AND LAYING M30 GRADE CONCRETE AT B.V. NAGAR 1ST CROSS LANE, B.V NAGAR 4TH STREET LANE (UNDER COUNCILLOR FUND) IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9311,Roads,Completed,NM-ALANDUR,166,237000,"FORMING AND LAYING M30 GRADE CONCRETE AT B.V. NAGAR 7TH STREET LANE, 10TH STREET LANE (UNDER COUNCILLOR FUND) IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9378,Buildings,Completed,NM-ALANDUR,166,938000,"PROVIDING AMMA KUDINEER WATER PLANT SHEED AT TEACHERS COLONY 1ST STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/12178,Buildings,Completed,NM-ALANDUR,167,998000,"Supply, Installation, Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity in Dn - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/12179,Buildings,Completed,NM-ALANDUR,167,980000,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres /Hour Capacity for 1 Year Period in Dn - 167, U - 37, Z- 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/12328,Buildings,Completed,NM-ALANDUR,167,971000,"REPAIRS AND MAINTENANCE WORK FOR BUILDINGS, PARK AND STORM WATER DRAIN IN VARIOUS STREETS AND VARIOUS BUILDINGS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/12756,Road Cut,Completed,NM-ALANDUR,167,683000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (NEMELI PROJECT) AT KANNAN NAGAR 3RD MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/16697,Storm Water Drain,Completed,NM-ALANDUR,167,208000,"REPAIR TO STORM WATER DRAIN (VARDHA CYCLONE) AT HINDHU COLONY 15TH CROSS STREET, NANGANALLUR 5TH MAIN ROAD,LAKSHMI NAGAR 1ST MAIN ROAD, VOLTAS COLONY 4TH STREET IN DN-167 U-36-Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/16698,Footpath,Completed,NM-ALANDUR,167,93000,"REPAIR TO FOOT PATH (VARDHA CYCLONE) AT VENUGOPALAPURAM MAIN ROAD, NANGANALLUR 5TH MAIN ROAD,SRIRAM COLONY IN DN-167 U-36-Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17257,Roads,Completed,NM-ALANDUR,167,122000,"ATTENDING DAMAGED ROAD PATCH WORK (VARDHA CYCLONE) AT NANGANALLUR 5TH MAIN ROAD, TNGO COLONY 7TH STREET, VOLTAS COLONY 50FT ROAD,VOLTAS COLONY 4TH STREET, LAKSHMI NAGAR 1ST MAIN ROAD, HINDU COLONY 15TH CROSS STREET IN DN-167 U-36 Z-12",Own Sources,12,2016-17,2017-18 NM/2016-17/17553,Parks,Completed,NM-ALANDUR,167,72000,"REPAIR TO COMPOUND WALL PATHWAY AND PLAY FIELD AREA (VARDHA CYCLONE) LAKSHMI NAGAR 7TH STREET PARK AT LAKSHMI NAGAR MAIN ROAD IN DN - 167, U - 36, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17554,Parks,Completed,NM-ALANDUR,167,458000,REPAIR TO COMPOUND WALL PATHWAY AND PLAY FIELD AREA (VARDHA CYCLONE) AT INDEPENDANCEDAY PARK IN DN-167 U-36 Z-12,Own Sources,12,2016-17,2017-18 NM/2016-17/17566,Parks,Completed,NM-ALANDUR,167,335000,"REPAIR TO COMPOUND WALL PATHWAY AND PLAY FIELD AREA (VARDHA CYCLONE) NANGANALLUR 100 FEET ROAD SIDE PARK AT NANGANALLUR 100 FEET ROAD IN DN - 167, U - 36, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17569,Parks,Completed,NM-ALANDUR,167,64000,"REPAIR TO COMPOUND WALL PATHWAY AND PLAY FIELD AREA (VARDHA CYCLONE) CIVIL AVIATION COLONY PARK AT SRI RAM COLONY IN DN - 167, U - 36, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17570,Parks,Completed,NM-ALANDUR,167,167000,"REPAIR TO COMPOUND WALL PATHWAY AND PLAY FIELD AREA (VARDHA CYCLONE) LAKSHMI NAGAR 4TH STAGE PARK AT VOLTAS COLONY 5TH STREET IN DN - 167, U - 36, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/17571,Parks,Completed,NM-ALANDUR,167,73000,"REPAIR TO COMPOUND WALL PATHWAY AND PLAY FIELD AREA (VARDHA CYCLONE) KANNAN NAGAR 1ST MAIN ROAD PARK AT KANNAN NAGAR 1ST MAIN ROAD IN DN - 167, U - 36, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/1815,Storm Water Drain,Completed,NM-ALANDUR,167,580000,"DESILTING OF STORM WATER DRAIN AT NANGANLLUR, HINDU COLONY, LAKSHMI NAGAR 3RD STAGE, LAKSHMI NAGAR 4TH STAGE, KANNAN NAGAR, BALAJI NAGAR, TNGO COLONY, VOLTAS COLONY, AGS COLONY, SIP COLONY AND SBI COLONY IN DN - 167, U - 37, Z- 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/18410,Buildings,Completed,NM-ALANDUR,167,327000,PROVIDING E - TOILET PLATFORM AND WATER SUPPLY DRAINAGE AND ELECTRICAL ARRANGEMENT AT NANGANALLUR 39TH STREET IN DN-167 U-36 Z-12,Own Sources,12,2016-17,2018-19 NM/2016-17/18479,Buildings,Completed,NM-ALANDUR,167,78000,PROVIDING BIN PLATFORM AT VARIOUS PLACES IN DN-167 U-36 Z-12,Own Sources,12,2016-17,2018-19 NM/2016-17/18494,Storm Water Drain,Completed,NM-ALANDUR,167,250000,"REPAIRS TO STORM WATER DRAIN AT VARIOUS STREET IN DN - 167, U - 36, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/18495,Storm Water Drain,Completed,NM-ALANDUR,167,188000,"PROVIDING SILT CATCH PIT AT LAKSHMI NAGAR, VISHWANATHAPURAM, STATE BANK COLONY 1ST STREET IN DN - 167, U - 36, Z- 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/18519,Footpath,Completed,NM-ALANDUR,167,92000,"IMPROVEMENT TO THE EXISTING FOOTPATH AT NANGANALLUR 45TH STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/2037,Parks,Completed,NM-ALANDUR,167,691000,"ADDITIONAL IMPROVEMENT TO THE EXISTING PARK AT KANNAN NAGAR 1ST CROSS STREET IN DN - 167, U - 37, Z - 12.( UNDER 167 WARD COUNCILOR FUND 2015 - 2016 )",Own Sources,12,2016-17,2016-17 NM/2016-17/2080,Parks,Completed,NM-ALANDUR,167,691000,"ADDITIONAL IMPROVEMENT TO THE EXISTING PARK AT LAKSHMI NAGAR 7TH STREET PARK AND LAKSHMI NAGAR MAIN ROAD IN DN - 167, U - 37, Z - 12. ( UNDER 167 WARD COUNCILOR FUND 2015 - 2016 )",Own Sources,12,2016-17,2016-17 NM/2016-17/2087,Parks,Completed,NM-ALANDUR,167,691000,"ADDITIONAL IMPROVEMENT TO THE EXISTING PARK AT VOLTAS COLONY 3RD STREET PARK IN DN - 167, U - 37, Z - 12.( UNDER 167 WARD COUNCILOR FUND 2015 - 2016 )",Own Sources,12,2016-17,2016-17 NM/2016-17/2093,Storm Water Drain,Completed,NM-ALANDUR,167,858000,"IMPROVEMENT TO THE EXISTING STORM WATER DRAIN AT LAKSHMI NAGAR 3RD STAGE MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2016-17 NM/2016-17/2094,Storm Water Drain,Completed,NM-ALANDUR,167,769000,"IMPROVEMENT TO THE EXISTING STORM WATER DRAIN AT HINDU COLONY 11TH CROSS STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/2112,Storm Water Drain,Completed,NM-ALANDUR,167,887000,"CONSTRUCTION OF SIDE DRAIN AT HINDU COLONY 1ST CROSS STREET (EAST SIDE) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/6189,Culvert,Completed,NM-ALANDUR,167,598000,CONSTRUCTION OF CULVERT AT MGR ROAD JN OF HINDU COLONY 8TH CROSS STREET IN DN-167 UNIT-37 Z-12,Own Sources,12,2016-17,2018-19 NM/2016-17/6326,Storm Water Drain,Completed,NM-ALANDUR,167,601000,"IMPROVEMENT TO THE EXISTING SWD AT LAKSHMI NAGAR 9TH STREET (3RD STAGE) (FROM VOLTAS COLONY 50 FEET ROAD TO A.G.S COLONY 1ST STREET) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/6639,Roads,Completed,NM-ALANDUR,167,970000,"RESTORATION TO ROAD CUTS AT VARIOUS STREETS IN DN 167, UNIT 37, ZONE 12.",Deposit Works,12,2016-17,2017-18 NM/2016-17/8195,Culvert,Completed,NM-ALANDUR,167,330000,"CONSTRUCTION OF CULVERT AT JAIN STAFF COLONY 2ND MAIN ROAD (JN OF RAJAJI STREET) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/8250,Parks,Completed,NM-ALANDUR,167,844000,"ADDITIONAL IMPROVEMENT TO THE EXISTING PARK AT LAKSHMI NAGAR EAST MAIN ROAD ( 4TH STAGE) (UNDER COUNCILLOR FUND) IN DN-167 , U-36 , ZONE-12",Own Sources,12,2016-17,2016-17 NM/2016-17/8381,Parks,Completed,NM-ALANDUR,167,32900,"IMPROVEMENT TO THE EXISTING PARK AT VOLTAS COLONY 1ST STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2018-19 NM/2016-17/8396,Buildings,Completed,NM-ALANDUR,167,994000,"CONSTRUCTION OF CONSERVANCY WORKERS DRESSING AND REST ROOM AT NANGANALLUR 100 FEET ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8990,Roads,Completed,NM-ALANDUR,167,196000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT DTE COLONY IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8991,Roads,Completed,NM-ALANDUR,167,245000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT KANNAN NAGAR 4TH MAIN ROAD IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8992,Roads,Completed,NM-ALANDUR,167,74000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT NANGANALLUR 46TH STREET 3RD CROSS STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8996,Roads,Completed,NM-ALANDUR,167,86000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT TNGO COLONY MAIN ROAD 1ST LANE IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/8997,Roads,Completed,NM-ALANDUR,167,183000,"RELAYING OF INTERIOR ROAD BY PAVER FINISHER AT VOLTAS COLONY 1ST STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9330,Parks,Completed,NM-ALANDUR,167,607000,"SUPPLYING AND FIXING OF TOWER CLOCK AT NANGANALLUR 100 FEET ROAD, LAKSHMI NAGAR 7TH STREET PARK (UNDER COUNCILLOR FUND) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9333,Parks,Completed,NM-ALANDUR,167,963000,"SUPPLYING AND FIXING OF TOWER CLOCK AT INDEPENDENCE DAY PARK, VOLTAS COLONY 50 FEET ROAD (UNDER COUNCILLOR FUND) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9375,Buildings,Completed,NM-ALANDUR,167,531000,"PROVIDING GULVANIZED IRON SHEED SHEET FOR VISITERS WAITING HALL AT SCATTING CENTER (UNDER COUNCILLER FUND) IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 NM/2016-17/9376,Buildings,Completed,NM-ALANDUR,167,938000,"PROVIDING AMMA KUDINEER WATER PLANT SHEED AT HINDU COLONY 15TH STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2016-17,2017-18 L/2016-17/13799,Electrical,Completed,L-Electrical,168,199100,"Shifting and raising of 39 nos Pillar boxes and painting of 125 nos of post and 39 pillars At Various Locations In Div-168 and 190, Zone-XIV",Own Sources,14,2016-17,2017-18 L/2016-17/13807,Electrical,Completed,L-Electrical,168,193300,Provision of 12 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-168 and 169. Zone-XIV,Own Sources,14,2016-17,2017-18 L/2016-17/18135,Electrical,Completed,L-Electrical,168,610400,"Removal and refixing of 82nos of 6mtr lamp post and 53nos of 7mtr lamp post in various locations in Dn-168,169,187,188 and 190 in Zone-XIV, due to Vardha cyclone effect on 12-12-16 .",Own Sources,14,2016-17,2017-18 NP/2016-17/0326,Storm Water Drain,Completed,NP-PERUNGUDI,168,435600,REPAIRS AND IMPROVEMENT TO SIDE DRAIN AT MG STREET FOR FLOOD WORK IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0327,Storm Water Drain,Completed,NP-PERUNGUDI,168,229800,REPAIRS AND IMPROVEMENT TO SIDE DRAIN AT THROPATHY AMMAN KOIL STREET FOR FLOOD WORK IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0328,Storm Water Drain,Completed,NP-PERUNGUDI,168,184700,IMPROVEMENT TO SIDE DRAIN AND LAYING INTERLOCKING BLOCKS AT MGR STREET FOR FLOOD WORK IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0329,Storm Water Drain,Completed,NP-PERUNGUDI,168,339000,REPAIRS AND IMPROVEMENT TO SIDE DRAIN AT CHITRARASU STREET FOR FLOOD WORK IN SIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0330,Storm Water Drain,Completed,NP-PERUNGUDI,168,271300,REPAIRS AND IMPROVEMENT TO SIDE DRAIN AT AMBEDKAR 2ND CROSS STREET FOR FLOOD WORK IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0331,Storm Water Drain,Completed,NP-PERUNGUDI,168,261000,REPAIRS AND IMPROVEMENTS TO SIDE DRAIN AT RAJARATHINAM STREET FOR FLOOD WORK IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0332,Culvert,Completed,NP-PERUNGUDI,168,116000,CONSTRUCTION OF ROAD CULVERT AT NANGANALLUR 23RD STREET FOR FLOOD WORK IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/1120,Roads,Completed,NP-PERUNGUDI,168,132000,ATTENDING PATCH WORK AT KUBERA MUNUSAMY STREET AND VARIOUS STREET FOR FLOOD WORK IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/1123,Storm Water Drain,Completed,NP-PERUNGUDI,168,434000,REPAIRS TO SIDE DRAIN AT LAKSHMI NAGAR 6TH STREET FLOOD WORK IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/13415,Storm Water Drain,Completed,NP-PERUNGUDI,168,440000,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN AT VIJAYAGANAPATHY NAGAR 3RD STREET IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/13875,Storm Water Drain,Completed,NP-PERUNGUDI,168,133000,ATTENDING FLOOD DAMAGED SIDE DRAIN AT VARIOUS STREET IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/13876,Buildings,Completed,NP-PERUNGUDI,168,197000,CONSTRUCTION OF DUST BINS AT VARIOUS STREET IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/13879,Buildings,Completed,NP-PERUNGUDI,168,158000,IMPROVEMENT TO DIVISION OFFICE IN DIVISION -168 AND IMPROVEMENT TO AMMA UNAVAGAM UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/15215,Storm Water Drain,Completed,NP-PERUNGUDI,168,833000,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN AT PARTHIBAN CROSS STREET AND MACMILLAN COLONY MAIN ROAD IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2017-18 NP/2016-17/15217,Storm Water Drain,Completed,NP-PERUNGUDI,168,840000,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN AT VENKATNARAYANA STREET IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/15218,Storm Water Drain,Completed,NP-PERUNGUDI,168,847000,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN ATSAMY NAGAR 1ST STREET IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/15219,Storm Water Drain,Completed,NP-PERUNGUDI,168,847000,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN AT SAMY NAGAR 2ND STREET IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/15220,Roads,Completed,NP-PERUNGUDI,168,453686,ATTENDING ROAD CUT PATCHES AT VARIOUS STREET IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/15221,Storm Water Drain,Completed,NP-PERUNGUDI,168,283000,FIXING HUME PIPE FOR ROAD CROSSING AT VARIOUS STREET IN FLOOD WORK DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/15686,Buildings,Completed,NP-PERUNGUDI,168,118000,FIXING ORNAMENTAL ROOFING SHED AT ROAD SIDE OF RATION SHOP IN DIVISION -168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/1670,Storm Water Drain,Completed,NP-PERUNGUDI,168,628000,"Desilting of side and storm water drain at ullagaram in dn-168,unit-42,zone-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/17301,Buildings,Completed,NP-PERUNGUDI,168,79500,"REPAIR WORKS TO AMMA UNAVAGAM BUILDINGS DUE TO VARDHA CYCLONE IN DN-168, UNIT-42, ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17429,Storm Water Drain,Completed,NP-PERUNGUDI,168,571001,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN AT GOPINATHAN STREET IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2017-18 NP/2016-17/17453,Storm Water Drain,Completed,NP-PERUNGUDI,168,366000,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN AT GOPINATHAN CROSS STREET WEST SIDE IN DIVISION- 168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2017-18 NP/2016-17/1945,Storm Water Drain,Completed,NP-PERUNGUDI,168,416000,"Desilting of Veerangal oodai at ullagaram in dn-168,unit-42,zone-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/2900,Buildings,Completed,NP-PERUNGUDI,168,379300,CONSTRUCTION OF TOILET AND OTHER IMPROVEMENT TO RATION SHOP AT LAKSHMI NAGAR 6TH STREET IN DIVISION-168 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/3429,Buildings,Completed,NP-PERUNGUDI,168,840000,"PROVIDING RESTORATION OF ROAD CUT AT BALAMMAL NAGAR MAIN ROAD FROM SAMY NAGAR MAIN ROAD TO NSC BOSE ROAD IN DN-168,UNIT-42,ZONE-14",Deposit Works,14,2016-17,2016-17 NP/2016-17/3463,Roads,Completed,NP-PERUNGUDI,168,840000,"PROVIDING RESTORATION OF ROAD CUT AT BALAMMAL NAGAR MAIN ROAD FROM MEDAVAKKAM MAIN ROAD TO SAMY NAGAR MAIN ROAD IN DN-168,UNIT-42,ZONE-14",Deposit Works,14,2016-17,2016-17 NP/2016-17/3871,Buildings,Completed,NP-PERUNGUDI,168,757000,CONSTRUCTION OF DRESS CHANGING ROOM AND TOILET BLOCK AT SHUTTLE CORK COURT IN KUPPUSAMY STREET IN DIVISION-168 UNIT-42 ZONE-14 (UNDER COUNCILLOR FUND 2016-17),Own Sources,14,2016-17,2017-18 NP/2016-17/3879,Buildings,Completed,NP-PERUNGUDI,168,591000,CONSTRUCTION OF SHUTTLE CORK COURT SHED WALLS AND ELECTRICAL ARRANGEMENT IN KUPPUSAMY STREET IN DIVISION-168 UNIT-42 ZONE-14 (UNDER COUNCILLOR FUND 2016-17),Own Sources,14,2016-17,2017-18 NP/2016-17/3883,Buildings,Completed,NP-PERUNGUDI,168,872000,PROVIDING ROOFING ARRANGEMENT TO SHUTTLE CORK COURT IN KUPPUSAMY STREET IN DIVISION-168 UNIT-42 ZONE-14 ( UNDER COUNCILLOR FUND 2016-17),Own Sources,14,2016-17,2017-18 NP/2016-17/3889,Footpath,Completed,NP-PERUNGUDI,168,770000,FORMING FOOTPATH TO SHUTTLE CORK COURT AND WOODEN FLOORING IN KUPPUSAMY STREET IN DIVISION-168 UNIT-42 ZONE-14 ( UNDER COUNCILLOR FUND 2016-17),Own Sources,14,2016-17,2017-18 L/2016-17/13798,Electrical,Completed,L-Electrical,169,198800,"Shifting and raising of 18 nos Pillar boxes and painting of 130 nos of post and 40 pillars At Various Locations In Div-169 and 187, Zone-XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/0121,Buildings,Completed,NP-PERUNGUDI,169,999000,CONSTRUCTION OF TOILET AND IMPROVEMENTS TO THE UPHC AT ERIKARAI STREET IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0165,Roads,Completed,NP-PERUNGUDI,169,994000,"LAYING WMM AND PROVIDING TILES, WATER SUPPLY ,ELECTRICAL ARRANGEMENTS AT OF UPHC IN DN-169 UNIT-42 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0386,Buildings,Completed,NP-PERUNGUDI,169,999000,"PROVIDING BARRICADING TABLES AND CHAIRS ARRANGEMENTS AND SHAMIYANA PANDAL BOOTHS AT VARIOUS LOCATION FOR ASSEMBLY ELECTION 2016 IN DN-169,UNIT-42,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0564,Playfields,Completed,NP-PERUNGUDI,169,812000,"IMPROVEMENT TO CHILDREN PLAY GROUND AND FORMING FOOTPATH, FIXING PLAY APPARATUS AT ANNAI THERASA NAGAR (ROAD SIDE ) IN DIVISION-169, UNIT-42, ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0668,Storm Water Drain,Completed,NP-PERUNGUDI,169,931000,CONSTRUCTION OF SIDE DRAIN AT MGR STREET FOR FLOOD WORK IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0948,Buildings,Completed,NP-PERUNGUDI,169,996000,"PROVIDING PAINTING,TILES TO THE SCHOOL TOILET AND IMPROVEMENTS TO THE ZONAL OFFICE IN DN169 UNIT-41 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0958,Buildings,Completed,NP-PERUNGUDI,169,455000,PROVING RAMP AND OTHER IMPROVEMENTS TO PC AND ANGANVADI AT ERIKARAI IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/0959,Buildings,Completed,NP-PERUNGUDI,169,269000,IMPROVEMENTS TO THE UPHC AT ERIKARAI IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/1241,Buildings,Completed,NP-PERUNGUDI,169,992000,"PROVIDING ILP,RMC AND OTHER IMPROVEMENTS TO THE ZONE IN DN-169 UNIT-42 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/12992,Parks,Completed,NP-PERUNGUDI,169,920000,IMPROVEMENT TO HINDU COLONY PARK AT 2ND STREET IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/17312,Buildings,Completed,NP-PERUNGUDI,169,102500,"REPAIR WORKS TO AMMA UNAVAGAM DAMAGES DUE TO VARDHA CYCLONE IN DN-169,UNIT-42,ZONE-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/17325,Buildings,Completed,NP-PERUNGUDI,169,74000,"REPAIRS WORKS (COMPOUND WALL) AT HINDU COLONY 2ND MAIN ROAD PARK AND DAVID GEORGE STREET DAMAGES DUE TO VARDAH CYCLONE IN DN-169, U-42, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/17338,Buildings,Completed,NP-PERUNGUDI,169,67600,"REPAIR WORKS TO SWAMY NAGAR BURIAL GROUND DAMAGES DUE TO VARDAH CYCLONE IN DN-169, UNIT-42, ZONE-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/17351,Buildings,Completed,NP-PERUNGUDI,169,83500,"REPAIR WORKS TO ZONA OFFICE STORE ROOM DUE TO VARDHA CYCLONE IN DN-169, UNIT-42,ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17374,Parks,Completed,NP-PERUNGUDI,169,194000,"REPAIR WORKS TO PARK (Balaji nagar park, AGS Colony park and EPR Nagar Park) DUE TO VARDHA CYCLONE IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17387,Roads,Completed,NP-PERUNGUDI,169,1733500,"REPAIR WORKS TO ROAD DAMAGES DUE TO VARDAH CYCLONE AT VARIOUS STREET IN DN-169, UNIT-42, ZONE-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/18162/C/C,Buildings,Completed,NP-PERUNGUDI,169,1086000,"CONSTRUCTION OF NAMMA TOILET FOR (2+1) AT PUZHUTHIVAKKAM BUS STAND IN DIV.169, U-42, Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/18185,Buildings,Completed,NP-PERUNGUDI,169,184000,"IMPROVEMENTS TO THE EXISTING PUBLIC CONVENIENCE AT PUZHUTHIVAKKAM BUS STAND IN DN-169,U-42,Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/19020,Storm Water Drain,Completed,NP-PERUNGUDI,169,598000,IMPROVEMENT TO FLOOD DAMAGED SIDE DRAIN AT GANESH NAGAR 5TH STREET IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/19021,Roads,Completed,NP-PERUNGUDI,169,108000,ATTENDING ROAD PATCHES AT VARIOUS STREET IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/1918,Storm Water Drain,Completed,NP-PERUNGUDI,169,476000,"DE SILTING OF SWD AND SIDE DRAIN AT VARIOUS STREET IN DIVISION-169, UNIT-42, ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/1920,Storm Water Drain,Completed,NP-PERUNGUDI,169,830000,"DE SILTING OF VEERANGAL OODAI (NORTH AND SOUTH SIDE) BY JCB AND LAYING HUME PIPE DIVISION-169, UNIT-42, ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3731,Storm Water Drain,Completed,NP-PERUNGUDI,169,998000,IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 AT MUTHU MOHAMED STREET FROM MEDAVAKKAM MAIN ROAD AND LINKING TO THE EXISTING SWD (COUNCILLOR FUND)IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/3735,Storm Water Drain,Completed,NP-PERUNGUDI,169,999000,IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 AT THIYAGI BAGATHSINGH STREET AND HINDU COLONY 4TH MAIN ROAD AND LINKING TO THE EXISTING SWD (COUNCILLOR FUND)IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/3893,Buildings,Completed,NP-PERUNGUDI,169,995000,"CONSTRUCTION OF COMPOUND WALL FLOOD DAMAGED FOR GANGAI AMMAN KULAM (EAST, WEST, SOUTH) IN DIVISION-169 UNIT-42 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/3896,Buildings,Completed,NP-PERUNGUDI,169,996000,CONSTRUCTION OF COMPOUND WALL AT NORTH SIDE OF FLOOD DAMAGED FOR GANGAI AMMAN KULAM AND OTHER IMPROVEMENT WORKS IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/4311,Storm Water Drain,Completed,NP-PERUNGUDI,169,997000,IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 AT THANGAVEL STREET AND LINKING TO THE EXISTING SWD (COUNCILLOR FUND)IN DN-169 UNIT-42 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/6753,Roads,Completed,NP-PERUNGUDI,169,2512000,"Restoration of Metro Water Road Cut at Murugappan Street in DN-169, Unit-42, Zone-14",Own Sources,14,2016-17,2016-17 NP/2016-17/6816,Roads,Completed,NP-PERUNGUDI,169,1767000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/6818,Roads,Completed,NP-PERUNGUDI,169,1741000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN-169, UNIT-42, ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/7249,Buildings,Completed,NP-PERUNGUDI,169,260000,"PAINTING TO ANGANVADI AND ZONAL OFFICE BUILDING IN DN-169, UNIT-42, ZONE-14.",Own Sources,14,2016-17,2016-17 L/2016-17/14082,Electrical,Completed,L-Electrical,170,178000,PROVISION OF REMOVAL AND REFIXING OF 20 NOS OF KIOSK PILLAR BOXES AT VARIOUS LOCATIONS IN DIVISIONS 170 TO 182 IN ZONE-XIII,Own Sources,13,2016-17,2017-18 L/2016-17/14136,Electrical,Completed,L-Electrical,170,999000,PROVISION OF SUPPLY AND ERECTION OF 23 NOS OF KIOSK PILLAR BOXES AT VARIOUS LOCATIONS IN DIVISIONS 170 TO 176 IN ZONE-XIII,Own Sources,13,2016-17,2016-17 L/2016-17/14174,Electrical,Completed,L-Electrical,170,557000,PROVISION OF SUPPLY AND FIXING OF 200 NOS 2C SMC FUSE BOX AND 100 NOS 4C SMC FUSE BOX AT VARIOUS LOCATIONS IN DIVISIONS 170 TO 176 IN ZONE-XIII,Own Sources,13,2016-17,2017-18 L/2016-17/18009,Electrical,Completed,L-Electrical,170,110000,"PROVISION OF REPLACEMENT OF ACCESSORIES AND MAINTENANCE WORK FOR THE 20 MTR HIGHMAST LIGHTING AT POONAMALLE ROAD IN DIV-170, ZONE-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/10410,Buildings,Completed,NN-ADYAR,170,880000,"IMPROVEMENTS OF AMMA UNAVAGAM AND CONSTRUCTION OF BIN PLATFORM (DN-170 ALL BINS) AT REDDY 2ND STREET IN DN-170,U-40A,Z-13",Own Sources,13,2016-17,2018-19 NN/2016-17/10874,Storm Water Drain,Completed,NN-ADYAR,170,930000,"DESILTING OF SWD AT GANDHI NAGAR EXTENSIONS , LABOUR COLONY ROADS ,ACHITHAN NAGAR 1ST STRRET,KATHIPARA ROAD, ALANDUR ROAD,CAR TRACK ROAD,GANAPATHY COLONY 1,2, CROSS STREET AND 2ND STREET IN DN-170,U-40A,Z-13",Own Sources,13,2016-17,2019-20 NN/2016-17/11013,Roads,Completed,NN-ADYAR,170,1096000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at Ambal Nagar Main Road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/11015,Roads,Completed,NN-ADYAR,170,3958000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at Poonamallee Road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/11017,Roads,Completed,NN-ADYAR,170,1360000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at Cart Track Road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/11018,Roads,Completed,NN-ADYAR,170,1135000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at Gandhi nagar main road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/11515,Buildings,Completed,NN-ADYAR,170,990000,"IMPROVEMENTS OF NNMP SHED AT NEERUPU MEDU,ALANDUR ROAD AND MADURAI MEENATCHI STREET IN DN-170,U-40A,Z-13",Own Sources,13,2016-17,2017-18 NN/2016-17/12468,Roads,Completed,NN-ADYAR,170,928000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement makers and signage boards at Various street in Div-170, Unit-40A, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/13190,Electrical,Completed,NN-ADYAR,170,247000,"PROVISION OF ELECTRICAL WIRING AT NEWLY CONSTRUCTED AMMA CANTEEN BUILDING AT KATHIPARA SALAI, GUINDY IN DIV-170, ZONE-XIII",Own Sources,13,2016-17,2019-20 NN/2016-17/14656,Electrical,Completed,NN-ADYAR,170,442000,"IMPROVEMENTS WORKS AND ELECTRICAL ARRANGEMENTS TO PUBLIC CONVENIENCE AT KATHIPARA ROAD,POONAMALEE ROAD ,ALANDHUR ROAD AND REDDY STREET IN DN - 170 UNIT - 40 A ZONE -13",Own Sources,13,2016-17,2017-18 NN/2016-17/1536,Buildings,Completed,NN-ADYAR,170,980000,"IMPROVEMENTS TO THE ELECTRICAL JE OFFICE AT ALANDUR ROAD IN DIVISION - 170, UNIT - 30, ZONE -13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1632,Roads,Completed,NN-ADYAR,170,998000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at labour colony masjid street in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/1633,Roads,Completed,NN-ADYAR,170,999000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at labour colony southern side of drainage road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/1634,Roads,Completed,NN-ADYAR,170,904000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at kalimagal nagar cross street&palayakaran street in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/1635,Roads,Completed,NN-ADYAR,170,999000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at kalaimagal nagar 2nd main road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/16848,Buildings,Completed,NN-ADYAR,170,2172000,"Construction of Damaged Compound Wall at Manjolai Burial Ground due to Vardah Cylone in Div 170, Zone - 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16891,Buildings,Completed,NN-ADYAR,170,594000,"Construction of Damaged Compound Wall at Customs Colony park due to Vardah Cylone in Div 170, Zone - 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/1696,Roads,Completed,NN-ADYAR,170,922000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at labour colony 10th,11th &labour colony 7thmain road 8th cross street street in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/1697,Roads,Completed,NN-ADYAR,170,973000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at labour colony car track road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/17484,Parks,Completed,NN-ADYAR,170,763000,"GREENERY IMPROVEMENT OF PARKS IN DIV-170,174 AND 177 ,UNIT-40-a,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/1787,Roads,Completed,NN-ADYAR,170,999000,"Restoration work for electric cable laying at labour colony masjid street,labour colony7th main road8th cross street in div-170,unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/19215,Roads,Completed,NN-ADYAR,170,787000,"CONSTRUCTION OF BIN PLATFORMS AT VARIOUS STREETS IN DIVISION - 170 & 177, ZONE - XIII (VARDAHCYCLONE WORKS)",Own Sources,13,2016-17,2017-18 NN/2016-17/4247,Storm Water Drain,Completed,NN-ADYAR,170,970000,"Improvements and Desilting of SWD at Balaji nagar main road, Thiruvasagam street, Ambal nagar main road, Poomagal main road, Arulayampet I,II & III street & Gandhi nagar main road in Div-170, Unit-40A, Zone-13.",Own Sources,13,2016-17,2020-21 NN/2016-17/4248,Storm Water Drain,Completed,NN-ADYAR,170,998000,"Improvements and Desilting of SWD at Pillayar koil I,II & III street, Poonamalle road, Danakodi raja street & Munusamy street in Div-170, Unit-40A, Zone-13.",Own Sources,13,2016-17,2020-21 NN/2016-17/4286,Roads,Completed,NN-ADYAR,170,990000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT HOSPITAL ROAD LANE IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/4294,Roads,Completed,NN-ADYAR,170,980000,"LAYING CEMENT CONCRETE ROAD WITH M30 GRADE AT ALANDUR SERVICE ROAD LANE IN DIVISION - 170, UNIT -40A, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/4432,Buildings,Completed,NN-ADYAR,170,998000,"DESILTING OF CANAL CLEANING @ GUINDY CANAL IN DN 170, UNIT 40(A), AT ZONE XIII",Own Sources,13,2016-17,2019-20 NN/2016-17/4438,Buildings,Completed,NN-ADYAR,170,474000,Outsourcing of Private Conservancy for CHSS (Maduvankarai )at Anna Salai and CPS ant Poonamallee School in Dn -170 unit -40A Zone -13,Own Sources,13,2016-17,2018-19 NN/2016-17/4440,Buildings,Completed,NN-ADYAR,170,998000,"DESILTING OF CANAL CLEANING @ REDDY GARDEN AND GUINDY ESTATE IN DN 170, UNIT 40(A), AT ZONE XIII",Own Sources,13,2016-17,2020-21 NN/2016-17/5706,Storm Water Drain,Completed,NN-ADYAR,170,410000,"REPAIRS AND DESILTING OF STORM WATER DRAIN @ REDDY 1ST STREET IN DN 170 ,UNIT-40(A), ZONEXIII",Own Sources,13,2016-17,2018-19 NN/2016-17/5707,Storm Water Drain,Completed,NN-ADYAR,170,516000,"REPAIRS AND DESILTING OF STORM WATER DRAIN @ REDDY 2ND STREET IN DN 170 ,UNIT-40(A), ZONEXIII",Own Sources,13,2016-17,2018-19 NN/2016-17/5708,Storm Water Drain,Completed,NN-ADYAR,170,300000,"REPAIRS AND DESILTING OF STORM WATER DRAIN @ REDDY 3RD STREET IN DN 170 ,UNIT-40(A), ZONEXIII",Own Sources,13,2016-17,2018-19 NN/2016-17/5861,Buildings,Completed,NN-ADYAR,170,757000,"PROVIDING GAS PIPE LINE CONNECTION AND WATER SUPPLY ARRANGEMENTS IN AMMA UNAVAGAM AT KATHIPARA ROAD IN DIV -170, U-40A,Z-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/5932,Buildings,Completed,NN-ADYAR,170,996000,"PROVIDING ROOFING ARRANGEMENT AND PAINTING WORKS IN AMMA UNAVAGAM AT KATHIPARA ROAD IN DN-170,U-40A,Z13.",Own Sources,13,2016-17,2018-19 NN/2016-17/5933,Buildings,Completed,NN-ADYAR,170,998000,"Proposed Construction of Amma Unavagam at Kathipara road in Div-170, Unit-40A, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/7193,Parks,Completed,NN-ADYAR,170,960000,REPAIRS AND IMPROVEMENTS TO THE PATHWAY AT CUSTOMS COLONY PARK IN DN -170 UNIT-40A ZONE-13(UNDER COUNCILLOR FUND),Own Sources,13,2016-17,2017-18 NN/2016-17/7227,Buildings,Completed,NN-ADYAR,170,995000,"PROVIDING PLAY MATERIAL TO THE CUSTOMS COLONY PARK AT DN-170,UT-40A,ZONE-13.(UNDER COUNCILLOR FUND)",Own Sources,13,2016-17,2017-18 NN/2016-17/7228,Buildings,Completed,NN-ADYAR,170,988000,"PROVIDING PLAY MATERIAL AND REPAIRS TO THE PARK AT CENTRAL EXCISE DUTY COLONY IN DN-170,UT-40A,ZONE-13.(UNDER COUNCILLOR FUND)",Own Sources,13,2016-17,2017-18 NN/2016-17/7293,Buildings,Completed,NN-ADYAR,170,932000,"Reparing and maintanance work at Transfer Station in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/7671,Buildings,Completed,NN-ADYAR,170,990000,"PROPOSED CONSTRUCTION OF SUMP AND ALUMINIUM WORK IN AMMA UNAVAGAM AT KATHIPARA ROAD IN DIV -170, U -40A ,Z -13",Own Sources,13,2016-17,2018-19 NN/2016-17/8139,Roads,Completed,NN-ADYAR,170,950000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at Parsn colony in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9380,Buildings,Completed,NN-ADYAR,170,630000,"IMPROVEMENTS OF CHENNAI PRIMARY SCHOOL AT POONTHAMALLE ROAD IN DN-170,U-40A,Z-13",Own Sources,13,2016-17,2018-19 BR/2016-17/18376,Roads,Completed,BR-Bus Route Roads,171,2490000,"Improvements to the Existing Centre median At Gandhi Mandabam Road From Anna GEM Park To Anna University Rear Entrance in DN-171 , Zone -13",Own Sources,13,2016-17,2017-18 BR/2016-17/18377,Roads,Completed,BR-Bus Route Roads,171,1760000,"Improvements to the Existing Centre median At Gandhi Mandabam Road From Anna University Rear Entrance to Anna University Campus Entrance in DN-171 , Zone-13",Own Sources,13,2016-17,2017-18 BR/2016-17/18379,Roads,Completed,BR-Bus Route Roads,171,2000000,"Improvements to the Existing Centre median At Gandhi Mandabam Road From Anna University Campus Entrance to Sardar patel Road in DN-171 , Zone -13",Own Sources,13,2016-17,2017-18 L/2016-17/16107,Electrical,Completed,L-Electrical,171,2186000,RESTORATION OF 577 NOS DAMAGED LAMP POSTS IN VARIOUS LOCATIONS IN DIV-171 TO 176 & 180 TO 182 IN ZONE-XIII DUE TO VARADHA CYCLONE EFFECT ON 12.12.2016,Own Sources,13,2016-17,2017-18 L/2016-17/18431,Electrical,Completed,L-Electrical,171,191000,"Provision of Removal of 46 Nos of 6/9 Mtr Lamp Post and Fixingof 41 Nos of LED Fittings at IIT Bridge, Sardar Patel Road in Div-171, Zone-XIII",Own Sources,13,2016-17,2017-18 L/2016-17/18674,Electrical,Completed,L-Electrical,171,605500,"Replacement of 12 Nos 400 W MH Fitting into 8Nos of 210 - 230 watts LED Fitting and for Carrying out maintaince work for the 20mtr High Mast at Saidapet Juntion of Little mount in Div-171, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/0747,Footpath,Completed,NN-ADYAR,171,877000,"Painting to Kerb, Centre Median and Repairs to the existing Footpath at Sardar Patel Road & Taluk office road in Dn-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/0896,Footpath,Completed,NN-ADYAR,171,182000,"Improvement to the existing Foot path at LDG road & North road West CIT nagar in Div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/0980,Roads,Completed,NN-ADYAR,171,225000,"TEMPORARY RESTORATION TO THE EXISTING DISPENSARY AT HOSPITAL ROAD IN DN-171,UT-40,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1049,Parks,Completed,NN-ADYAR,171,955940,"IMPROVEMENT GREENERY WORK OF ROAD SIDE PARK AT TALUK OFFICE ROAD, TRAFFIC ISLAND JN OF SARDAR PATEL ROAD WITH THALUK OFFICE ROAD AND CINNAMALAI JN IN DIV-171,UNIT-40,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/11021,Roads,Completed,NN-ADYAR,171,1593000,"Relaying the road with 40mm thick bituminous concrete using by paver finisher at West C.I.T.Nagar - North Road in div-171,Unit-40,Zone-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/11837,Storm Water Drain,Completed,NN-ADYAR,171,805000,"Improvements and Desilting of SWD at Srinagar Colony Temple Avenue, West mada street, Bharathidasan street and Srinagar colony cross Street in Div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2020-21 NN/2016-17/11838,Storm Water Drain,Completed,NN-ADYAR,171,897000,"Improvements and Desilting of SWD at Velachery Main Road, Link Road and Subbu Pillai Thottam in Div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2020-21 NN/2016-17/11839,Storm Water Drain,Completed,NN-ADYAR,171,773000,"Improvements and Desilting of SWD at 70 Road, Railway Border II Street Appavoo Nagar, Choodi Ammanpet and West Road West CIT Nagar in Div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11886,Buildings,Completed,NN-ADYAR,171,854000,"Defacing and painting of Rajbahavan compound wall for his excellency president of India visit at Sardar Patel Road in Dn-171,Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/12390,Roads,Completed,NN-ADYAR,171,738000,"Attending temporary restoration of damaged road at Feery Road due to flood in North East Mon soon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12391,Roads,Completed,NN-ADYAR,171,657000,"Attending temporary restoration of damaged road at Thomas Nagar 1st street due to flood in North East Mon soon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12392,Roads,Completed,NN-ADYAR,171,167000,"Attending temporary restoration of damaged road at Anjaneyar koil street, Bharathy street and Muthiayalu street due to flood in North East Mon soon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12525,Roads,Completed,NN-ADYAR,171,540000,"Attending temporary restoration of damaged road at Arokiyamada 1st & 2nd street, L.D.G. Road and Lane due to flood in North East Mon soon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12526,Roads,Completed,NN-ADYAR,171,513000,"Attending temporary restoration of damaged road at Gandhi street, Bharathy street, Indiraganthi street, Kasthuribai street and Hospital road due to flood in North East Mon soon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12527,Roads,Completed,NN-ADYAR,171,327000,"Attending temporary restoration of damaged road at Sastri main road, Soodiammanpet and School road due to flood in North East Mon soon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/13145,Roads,Completed,NN-ADYAR,171,920000,"Attending temporary restoration for damaged roads at Appavoo Nagar Railway Border Road 1st & 2nd street, Model Hutment Road and Selva Rangaraja Street due to flood in Monsoon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/13146,Roads,Completed,NN-ADYAR,171,920000,"Attending temporary restoration of damaged road at Panpet 2nd street and vetnery Hospital Road due to flood in North East Monsoon 2015 in Dn-171,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/13345,Buildings,Completed,NN-ADYAR,171,990000,"IMPROVEMENT WORKS TO ARANGANATHAN SUBWAY GENERATOR & CARE TAKER ROOM IN DIV-171, UNIT-40, ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/14542,Buildings,Completed,NN-ADYAR,171,555000,"Repairs and Improvemetns works to Public Convenience at Jothiyammal Nagar, Govt.Farm, LDG Road, Sathya Nagar, Gandhi Mandapam, Surya Nagar and Velachery Main road, Lorry station in Dn 171, Unit 40, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16754,Buildings,Completed,NN-ADYAR,171,528000,"Construction of compound wall ( Damaged in vartha cyclone) at Surya nagar burial ground in div171, unit-40, zone13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16881,Storm Water Drain,Completed,NN-ADYAR,171,568000,"Construction of Existing Dilapidated SWD at Mosque Garden ( Damaged in Vartha Cyclone) in div-171, unit-40, zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/18249,Buildings,Completed,NN-ADYAR,171,428000,"Repairs to Foot path (Damaged in Vartha Cyclone) at Srinagar Colony & Taluk office road road in div-171, unit-40, zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/18250,Buildings,Completed,NN-ADYAR,171,547000,"Repairs to Footpath (Damaged in Vartha Cyclone) at Ranjith road, Ferry road & Sardar patel road in div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/18251,Electrical,Completed,NN-ADYAR,171,249000,"Wiring of Newly Cotruction Amma Unavagam at Vengatapuram in div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/4265,Storm Water Drain,Completed,NN-ADYAR,171,999000,"Improvements and Desilting of SWD at Sardar patel road, Sasthri main road, Gandhi mandapam road and Birla planetarium in Div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2020-21 NN/2016-17/4267,Storm Water Drain,Completed,NN-ADYAR,171,999000,"Improvements and Desilting of SWD at Vengadapuram main road, Taluk office road, Sri nagar colony south avenue and Railway border 1st street in Div-171, Unit-40, Zone-13.",Own Sources,13,2016-17,2020-21 NN/2016-17/4439,Buildings,Completed,NN-ADYAR,171,189000,Outsourcing Scavenging Work for the CPS at Vengadapuram and in Dn-171 Unit-40 Zone - 13,Own Sources,13,2016-17,2018-19 NN/2016-17/5816,Buildings,Completed,NN-ADYAR,171,982000,"Defacing the Walls at Anna salai, Taluk office road and Sardar patel road in Dn 171, Unit 40, Zone 13 for the event of Honorable President of India visit to Chennai.",Own Sources,13,2016-17,2018-19 NN/2016-17/5876,Buildings,Completed,NN-ADYAR,171,600000,"SUPPLYING AND FIXING RETRO REFLECTIVE STAINLESS STEEL NAME BOARD AT VARIOUS STREET (VENKATAPURAM,JOTHIAMMAL NAGAR,SUBBU PILLAI THOTAM,AND GANDHI PURAM) IN DN-171,UT-40,ZONE-13 (UNDER COUNCILLOR FUND).",Own Sources,13,2016-17,2018-19 NN/2016-17/5919,Buildings,Completed,NN-ADYAR,171,780000,"PROPOSED CONSTRUCTION OF MULTI PURPOSE HALL AT HOSPITAL ROAD IN DN-171,UT-40,ZONE-13(UNDER COUNCILLOR FUND).",Own Sources,13,2016-17,2018-19 NN/2016-17/5920,Buildings,Completed,NN-ADYAR,171,970000,"PROPOSED CONSTRUCTION OF MULTI PURPOSE HALL AT RAILWAY BORDER 1ST STREET IN DN-171,UT-40,ZONE-13.( UNDER COUNCILLOR FUND)",Own Sources,13,2016-17,2017-18 NN/2016-17/6569,Buildings,Completed,NN-ADYAR,171,978000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM AT VENGADAPURAM (NEAR H-BLOCK) IN DN-171,UNIT-40,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/6586,Buildings,Completed,NN-ADYAR,171,950000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE AMMA UNAVAGAM AT VENGADAPURAM IN DN-171,UT-40,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/6597,Buildings,Completed,NN-ADYAR,171,634000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL (UNDER COUNCILLOR FUND) AT VENGADAPURAM (NEAR-H BLOCK) IN DN-171,UT-40,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/7207,Footpath,Completed,NN-ADYAR,171,792000,"PAINTING BLACK AND WHITE TO THE FOOTPATH KERB AND CENTER MEDIAN WALL IN VIEW OF INDEPENDENCE DAY'2016 AT SARDAR PATEL ROAD, GANDHIMANDAPAM ROAD AND TALUK OFFICE ROAD(VVIP ROUTE) IN DN-171,UNIT-40, ZONE-13",Own Sources,13,2016-17,2018-19 BR/2016-17/16069,Roads,Completed,BR-Bus Route Roads,172,275000,PROVIDING & LAYING RAMP WORK FOR BUS SHELTER AT VARIOUS ROAD IN ZONE 13 ADYAR,Own Sources,13,2016-17,2018-19 BR/2016-17/17002,Road Cut,Completed,BR-Bus Route Roads,172,113000,Restoration of road cut made by CMWSSB work at velachery Main Road in Zone -13 Adyar,Own Sources,13,2016-17,2017-18 BR/2016-17/18373,Roads,Completed,BR-Bus Route Roads,172,2300000,Improvements to the Existing Centre median At Gandhi Mandapam Road from River view road to Kottur link road in zone -13,Own Sources,13,2016-17,2018-19 BR/2016-17/18374,Roads,Completed,BR-Bus Route Roads,172,1670000,"Improvements to the Existing Centre median At Gandhi Mandabam Road Kottur Garden link road to Ranjith road in DN-172 , Zone -13",Own Sources,13,2016-17,2018-19 BR/2016-17/18375,Roads,Completed,BR-Bus Route Roads,172,1730000,"Improvements to the Existing Centre median At Gandhi Mandapam Road From Ranjith Road to Anna GEM Science Park in DN-171 , Zone -13",Own Sources,13,2016-17,2017-18 BR/2016-17/3589,Road Cut,Completed,BR-Bus Route Roads,172,3135000,Roat Cut Restoreation work at West Canal Bank Road by TNEB in Div 172 Zone 13,Deposit Works,13,2016-17,2016-17 NN/2016-17/0706,Footpath,Completed,NN-ADYAR,172,540000,"Painting Black and White washing for Footpath kerb, Centre Median and Repairs to Footpath at Gandhimandapam Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/0707,Footpath,Completed,NN-ADYAR,172,492000,"Repairs to Footpath and Painting Black and White washing for Footpath kerb, Centre Median at Sardar Patel Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/0708,Footpath,Completed,NN-ADYAR,172,242000,"Improvement to Flood Damaged Multipurpose Hall at Kotturpuram 3rd Main Road, Kotturpuram in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/11965,Roads,Completed,NN-ADYAR,172,1123000,"Attending temporary restoration of damaged road at Naidu Street due to floods in North East Monsoon 2015 in Division - 172, Unit - 40, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/11969,Roads,Completed,NN-ADYAR,172,212900,"Attending temporary restoration of damaged road at kalikuntram main road due to floods in North East Monsoon 2015 in Division - 172, Unit - 40, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/11970,Storm Water Drain,Completed,NN-ADYAR,172,1210000,"INSTALLATION OF WATER TREATMENT PLANT AT KOTTURPURAM 1ST MAIN ROAD IN DIVISION -172, UNIT - 40, ZONE - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/11975,Roads,Completed,NN-ADYAR,172,388000,"Attending temporary restoration of damaged road at Kandasamy street due to floods in North East Monsoon 2015 in Division - 172, Unit - 40, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/11980,Roads,Completed,NN-ADYAR,172,1995000,"Attending temporary restoration of damaged road at Lake view road(REACH-3) due to floods in North East Monsoon 2015 in Division - 172, Unit - 40, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/12084,Roads,Completed,NN-ADYAR,172,1461000,"Attending temporary restoration of damaged road at Lake view road (REACH-4)due to floods in North East Monsoon 2015 in Division - 172, Unit - 40, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/12342,Buildings,Completed,NN-ADYAR,172,1259000,"MAINTENANCE AND OPERATION OF THE WATER TREATMENT PLANT AT KOTTURPURAM 1ST MAIN ROAD IN DIVISION -172, UNIT - 40, ZONE - XIII",Own Sources,13,2016-17,2018-19 NN/2016-17/12657,Buildings,Completed,NN-ADYAR,172,789000,"Major repair and improvements to Gasifier crematorium Kotturpuram Burial Ground at Lake View Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/12916,Buildings,Completed,NN-ADYAR,172,697000,"Providing Inlet Chamber connection across the service Road (behind Bus Stop) near Madya Kailash at Sardar Patel Road in DN-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/13996,Storm Water Drain,Completed,NN-ADYAR,172,947000,"Raising the Manhole Doors & Supplying and Fixing FRC Manhole Door with frame at R.S.Sridar Salai (Pondichery Road) in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2019-20 NN/2016-17/14818,Buildings,Completed,NN-ADYAR,172,380000,"Improvement and Repair Works to CHS at New Street and CPS at Chitra Nagar in Dn-172,Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/15852,Buildings,Completed,NN-ADYAR,172,429000,"Repairs to Damaged G.I.Roof Sheet, Compound Wall, Bore due to Vardah Cyclone for Chennai High School at New Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/15889,Parks,Completed,NN-ADYAR,172,897000,"Construction of Damaged Compound Wall due to Vardah Cyclone for Park at River View Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/1637,Parks,Completed,NN-ADYAR,172,656000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT RIVER VIEW ROAD, KOTTURPURAM IN DN 172, UNIT 40, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1641,Parks,Completed,NN-ADYAR,172,65000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT KOTTUR GARDEN 4TH MAIN ROAD (SENIOR CITIZEN PARK) IN DN 172, UNIT 40, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1642,Parks,Completed,NN-ADYAR,172,123000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT CHITRA NAGAR, KOTTURPURAM IN DN 172, UNIT 40, ZONE 13",Own Sources,13,2016-17,2018-19 NN/2016-17/1645,Parks,Completed,NN-ADYAR,172,166000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT DHANDAYUTHAPANI NAGAR IN DN 172, UNIT 40, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1664,Parks,Completed,NN-ADYAR,172,70000,"OUTSOURCING MAINTENANCE OF PARK (6 MONTHS) AT GOVINDASAMY PARK, ERIKARAI STREET IN DN 172, UNIT 40, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/16884,Parks,Completed,NN-ADYAR,172,507000,"Construction of Damaged Compound Wall due to Vardah Cyclone for Park at Danadayuthapani Nagar Cross Street, Kotturgarden 4th Main Road, Kottur Garden 1st Cross Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/17488,Parks,Completed,NN-ADYAR,172,991000,"GREENERY IMPROVEMENT OF PARKS IN DIV-171,172 AND 173 ,UNIT-40,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/2904,Storm Water Drain,Completed,NN-ADYAR,172,618000,"Proposed construction of SWD and providing UPVC pipe at Bharathi Avenue 1st Street to B-Canal in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/3535,Buildings,Completed,NN-ADYAR,172,986000,"Proposed construction of TOILET BLOCK at Gypsy colony Kottur in Dn-172, Unit-40, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/3537,Buildings,Completed,NN-ADYAR,172,910000,"Proposed construction of AMMA DRINKING WATER at Kotturpuram in Dn-172, Unit-40, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/4435,Buildings,Completed,NN-ADYAR,172,474000,"Outsourcing Scavenging work for the CHS, CPS and KGS at New street and CPS at Kotturpuram in Dn -172 unit -40 Zone -13",Own Sources,13,2016-17,2018-19 NN/2016-17/5925,Buildings,Completed,NN-ADYAR,172,996000,"Providing Electrical, Water Supply & Drainage arrangement and Renovation for Amma Unavagam at Kotturpuram TNSCB Tenements in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/5935,Buildings,Completed,NN-ADYAR,172,993000,"Proposed additional construction and renovation of building for Amma Unavagam at Kotturpuram TNSCB Tenements in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/5939,Footpath,Completed,NN-ADYAR,172,987000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT KOTTURPURAM (Ward Councilor Fund) IN DN-172, UNIT- 40 ,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7107,Buildings,Completed,NN-ADYAR,172,660000,"Proposed construction of flooring, Water Supply & Electrical Work in AMMA DRINKING WATER at Kotturpuram in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/7166,Roads,Completed,NN-ADYAR,172,975000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREET (Ward Councilor Fund) IN DN-172, UNIT- 40 ,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7169,Storm Water Drain,Completed,NN-ADYAR,172,986000,"Improvement & Desilting of Storm Water Drain at Ellaiamman Koil street, East Ellaiamman Koil Street, Gandhi mandapam road, Kotturpuram Bridge Cross Drain to TNSCB, Kotturpuram 2nd Main Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/7213,Footpath,Completed,NN-ADYAR,172,826000,"PAINTING BLACK AND WHITE TO THE FOOTPATH KERB IN VIEW OF INDEPENDENCE DAY'2016 AT SARDAR PATEL ROAD, GANDHIMANDAPAM ROAD IN DN-172,UNIT-40, ZONE-13",Own Sources,13,2016-17,2018-19 NN/2016-17/8988,Buildings,Completed,NN-ADYAR,172,505000,"Proposed Construction of Compound Wall and Water Supply arrangement to Play ground at Kotturpuram 3rd Main Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/8989,Buildings,Completed,NN-ADYAR,172,989000,"Improvements to Gym Building and Providing GYM Materials at Kotturpuram 3rd Main Road in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9402,Storm Water Drain,Completed,NN-ADYAR,172,999000,"Improvement & Desilting of Storm Water Drain at Naidu Street, Mannappa Street, Bharathi Avenue Main Road, Bharathi Avenue 1st Cross Street, 2nd Cross Street, Ponniamman Koil Street, Lake View Road Jn of Ellaiamman Koil Street to Guruvappan Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9459,Buildings,Completed,NN-ADYAR,172,990000,"Improvements and Providing Play Apparatus to ABCD Park at Kotturgarden 1st Cross Street(Ward Councilor Fund) in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9477,Storm Water Drain,Completed,NN-ADYAR,172,979000,"Improvement & Desilting of Storm Water Drain at New Street,Yadaval Street, Dandayudhapani 1st Street, Dandayudhapani 2nd Street, Cross Street, River View Road Crossing, Thiruvalluvar 1st Street, 4th Street in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9495,Roads,Completed,NN-ADYAR,172,991000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Thandayuthapani street, Erikarrai Street, Kottur Puram, Kottur Garden and Kottur Garden 4th Main Road Extn in Dn-172, Unit-40, Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/9510,Buildings,Completed,NN-ADYAR,172,920000,"Improvement & Desilting of Storm Water Drain at Kotturpuram 1st Main Road (East side) in Dn-172, Unit-40, Zone-13.",Own Sources,13,2016-17,2019-20 L/2016-17/16257,Electrical,Completed,L-Electrical,173,406500,"RESTORATION OF DAMAGED POSTS AND LAYING OF 4CX16SQMM CABLE IN THIRU VI KA BRIDGE OVER ADYAR RIVER IN DIVISION-173,ZONE-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/18448,Electrical,Completed,L-Electrical,173,824000,"PROVIDING 30KVA DIESEL GENERATOR SET FOR DIVISION OFFICE CAMPUS AT KAMARAJ SALAI, RAJA ANNAMALAI PURAM IN DIVISION-173, ZONE-XIII.",Own Sources,13,2016-17,2018-19 NN/2016-17/0702,Footpath,Completed,NN-ADYAR,173,203000,"Repairs to footpath at Durgabai Deshmukh Road, DR.D G S Dinakaran Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/0744,Footpath,Completed,NN-ADYAR,173,993000,"Painting Footpath Kerbs, Trees and Centre Median at Durgabai Deshmukh Road, Dr. D.G.S Dinakaran Salai, R. K. Mutt Road, P.S. Kumarasamy Raja Road, Brodies Castle Road in Dn.173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/11476,Buildings,Completed,NN-ADYAR,173,998000,"Supply, Installation,Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at Kamarajar salai in Division - 173, Zone - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/11488,Buildings,Completed,NN-ADYAR,173,980000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period at Kamarajar salai in Dn -173, Zone - XIII",Own Sources,13,2016-17,2018-19 NN/2016-17/11670,Buildings,Completed,NN-ADYAR,173,591000,"Proposed Construction of Amma Kudineer plant and Repairs to Compound wall at Kamaraj Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/12357,Buildings,Completed,NN-ADYAR,173,2560000,"Improvements of building, water supply arrangements and repair works of compound wall to J.J.Kalyanamandapam at Kamarajar Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/13243,Buildings,Completed,NN-ADYAR,173,609000,"Providing Inlet Chambers to Collect Rain Water from junction of P.S.K.Salai to MGR Janaki College at Durgabai Deshmuk Road in Dn.173, Unit 40, Zone 13",Own Sources,13,2016-17,2018-19 NN/2016-17/13635,Roads,Completed,NN-ADYAR,173,589000,"Attending temporary restoration of damaged road at kesava perumal puram due to flood in North East Mon soon 2015 in Dn-173,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/13643,Roads,Completed,NN-ADYAR,173,998000,"Attending temporary restoration of damaged road at R.K Mutt 4th cross street due to flood in North East Mon soon 2015 in Dn-173,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/13710,Roads,Completed,NN-ADYAR,173,190000,"Attending temporary restoration of damaged road at Velayutha raja street&school view road due to flood in North East Monsoon 2015 in Dn-173,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/14678,Buildings,Completed,NN-ADYAR,173,162000,"Improvements to Public Convenience at Govindasamy Nagar East, Govindasamy Nagar West, P.S.K.Salai, R.K.Mutt Road, Kamarajar Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14824,Buildings,Completed,NN-ADYAR,173,348000,"Improvement and Repair Works to Chennai Middle School at NS Garden, Park View Road in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/15481,Roads,Completed,NN-ADYAR,173,981000,"Attending road cut work with bituminous concrete 40mm thick at thiruvengadam street in div-173,Unit-40,Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/16851,Storm Water Drain,Completed,NN-ADYAR,173,850000,"Repairs to SWD (Damaged in Vartha Cylone) at Various street in div173, Unit40, Zone13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16919,Roads,Completed,NN-ADYAR,173,296000,"Renovation and Construction of Centre Median at Rohini Garden in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16921,Buildings,Completed,NN-ADYAR,173,156000,"Renovation of Damaged Compound Wall due to Vardah Cyclone in Chennai Middle School at N.S.Garden, Park View Street in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/17019,Parks,Completed,NN-ADYAR,173,313000,"Renovation of damaged compound wall Krishnapuri Park and Kesavaperumal puram due to Vardah Cyclone at Krishnapuri main Road and Kesavaperumal Puram in Dn-173,Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/17021,Parks,Completed,NN-ADYAR,173,686000,"Improvements to Damaged Footpath and Compound Wall due to Varadah Cyclone in Sathyadev Avenue Park at MRC Nagar in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/19357,Electrical,Completed,NN-ADYAR,173,347000,"Providing Electricity connection and wiring arrangements for proposed Amma Unavagam at P.S.Kumarasamy Raja Salai, Raja Annamalaipuram ( Opp to Greenways Road MRTS station) in Division 173, Zone-XIII",Own Sources,13,2016-17,2019-20 NN/2016-17/2120,Parks,Completed,NN-ADYAR,173,835000,"Out Sourcing Maintenance of Parks (6 Months) at Kamarajar Salai, East Avenue, Central Avenue, Krishnapuri, MRC Nagar, Vasantha Avenue, Sathyadev Avenue and Guest House Park in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/4437,Buildings,Completed,NN-ADYAR,173,189000,Outsourcing of Private Conservancy in C.M.S at Park View street in Dn -173 unit -40 zone -13.,Own Sources,13,2016-17,2018-19 NN/2016-17/6007,Footpath,Completed,NN-ADYAR,173,947000,"PAINTING BLACK AND WHITE TO THE CENTER MEDIAN WALL IN VIEW OF INDEPENDENCE DAY'2016 AT P.S.KUMARASAMY RAJA SALAI, BRODIES CASTLE ROAD, R.K.MUTT ROAD, DURGA BAI DESHMUK SALAI AND D.G.S.DINAKARAN SALAI IN DN-173,UNIT-40, ZONE-13",Own Sources,13,2016-17,2018-19 NN/2016-17/6386,Footpath,Completed,NN-ADYAR,173,581000,"Repair and Improvements to Footpath from the Junction of Durgabhai Deshmuk Road to Junction of Greenways road at P.S.Kumarasamy raja Road in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/7165,Roads,Completed,NN-ADYAR,173,940000,"PAINTING BLACK AND YELLOW TO THE CENTER MEDIAN WALL IN VIEW OF INDEPENDENCE DAY'2016 AT P.S.KUMARASAMY RAJA SALAI, BRODIES CASTLE ROAD, R.K.MUTT ROAD, DURGA BAI DESHMUK SALAI AND D.G.S.DINAKARAN SALAI IN DN-173,UNIT-40, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7195,Buildings,Completed,NN-ADYAR,173,344000,"Repair & Improvements to Amma Unavagam at Kamaraj Salai in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/7222,Buildings,Completed,NN-ADYAR,173,386000,"Providing Ramp for Disabled Person at Various Corporation Building in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/9385,Buildings,Completed,NN-ADYAR,173,987000,"Proposed construction of 16th Day Ceremony Hall at South Kesavaperumal Puram Main Road in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/9387,Buildings,Completed,NN-ADYAR,173,500000,"Improvements to Multipurpose Hall at South Kesavaperumal Puram Main Road in Dn-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/9424,Buildings,Completed,NN-ADYAR,173,988000,"Proposed Construction of Amma Unavagam at PS Kumarasamy Raja Road Opp. to Railway station in Div-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9461,Roads,Completed,NN-ADYAR,173,990000,Providing Retro Reflection Stainless Steel Street Name Board Around R.K Nagar Area( Under Councilor Fund) at Various Street in Dn - 173 Unit -40 Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/9462,Roads,Completed,NN-ADYAR,173,990000,Providing Retro Reflection Stainless Steel Street Name Board Around Kesavaperumal Puram area ( Under Councilor Fund) at Various Street in Dn - 173 Unit -40 Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/9463,Roads,Completed,NN-ADYAR,173,990000,Providing Retro Reflection Stainless Steel Street Name Board Around Karpagam Avenue Area ( Under Councilor Fund) at Various Street in Dn - 173 Unit -40 Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/9472,Buildings,Completed,NN-ADYAR,173,992000,"Proposed construction of Sump and Water supply and Electrical arrangements to Amma Unavagam at PS Kumarasamy Raja Road Opp.to Railway station IN DN-173, U-40, Z13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9514,Buildings,Completed,NN-ADYAR,173,836000,"Repairs and Improvements to Vermi Composed Yard at M.R.C.Nagar- Janaki Avenue Extension in Div-173, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 BR/2016-17/17766,Roads,Completed,BR-Bus Route Roads,174,3550000,"Repair and Restroration of Relaying Road by Paver Finisher Work at Nethaji Road (Nehru Nagar) in Dn-174, Zone-13",Grants,13,2016-17,2017-18 BR/2016-17/18504,Roads,Completed,BR-Bus Route Roads,174,600000,Restoration of Road Cut Made by CMWSSB at Lake View Road in Div-177 Zone- 13,Deposit Works,13,2016-17,2017-18 BR/2016-17/18505,Road Cut,Completed,BR-Bus Route Roads,174,1900000,Restoration of Road Cut Made by CMWSSB at Brindhavan Nagar Main Road in Div-177 Zone- 13,Deposit Works,13,2016-17,2017-18 BR/2016-17/18506,Road Cut,Completed,BR-Bus Route Roads,174,750000,Restoration of Road Cut Made by CMWSSB at Mahalakshmi Nagar 1st Main Road in Div-177 Zone- 13,Deposit Works,13,2016-17,2017-18 BR/2016-17/18507,Roads,Completed,BR-Bus Route Roads,174,1580000,Restoration of Footpath Made by TANGEDCO UG Cable at Durga bai Deshmuk Road in Div- 175 & 176 Zone-13,Grants,13,2016-17,2018-19 BR/2016-17/7233,Buildings,Completed,BR-Bus Route Roads,174,972800,"Providing RCC Crash Barirer type Center Median at Velachery Main Road(From junction of Velachery 100ft road to Westin Hotel) and Road Cut restoration work done by service department in Division - 174 & 175, Zone -13",Own Sources,13,2016-17,2016-17 BR/2016-17/9511,Electrical,Completed,BR-Bus Route Roads,174,1400000,"Providing Electrical Arrangements and Display Board and footing for bus shelter at Race Course Road, Zone 13, Division 174.",Own Sources,13,2016-17,2017-18 BR/2016-17/9513,Buildings,Completed,BR-Bus Route Roads,174,2480000,"Proposed Construction of Bus Shelter with structure at Race Course Road, Zone 13, Division - 174.",Own Sources,13,2016-17,2017-18 NN/2016-17/11168,Storm Water Drain,Completed,NN-ADYAR,174,865000,"DESILTING THE RAJ BHAVAN CANAL AND REPAIRS TO THE SIDE DRAIN AT VELECHERY MAIN ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/11492,Storm Water Drain,Completed,NN-ADYAR,174,950000,"PROVIDING SILT CATCH PIT AT VELECHERY MAIN ROAD (FROM ANNA GARDEN TO FIVE FUR LONG JN) IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2016-17,2019-20 NN/2016-17/12028,Roads,Completed,NN-ADYAR,174,332000,"Wiring of Newly Construction of Amma Unavagam, Velachery main road in Maduvangarai div-174, in Zone-XIII.",Own Sources,13,2016-17,2019-20 NN/2016-17/1317,Roads,Completed,NN-ADYAR,174,868000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM II & III STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2017-18 NN/2016-17/1318,Roads,Completed,NN-ADYAR,174,913000,"PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM IV, V & VI STREET IN DN -174 U - 40A Z - 13",Own Sources,13,2016-17,2017-18 NN/2016-17/1321,Roads,Completed,NN-ADYAR,174,605054,"PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM VII, VIII & X STREET IN DN -174 U - 40A Z - 13",Own Sources,13,2016-17,2017-18 NN/2016-17/1330,Roads,Completed,NN-ADYAR,174,196000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM 9 STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/1345,Roads,Completed,NN-ADYAR,174,160000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM 19 STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/1353,Roads,Completed,NN-ADYAR,174,162000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM 14 STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/1361,Roads,Completed,NN-ADYAR,174,107000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT KANNIGAPURAM 31 STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/1365,Roads,Completed,NN-ADYAR,174,2544000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT GANGAI AMMAN KOIL STREET I STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2017-18 NN/2016-17/1367,Roads,Completed,NN-ADYAR,174,755000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT PRADAPA CHANDRAN STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/1368,Roads,Completed,NN-ADYAR,174,833000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT NEW KANNIGAPURAM 1 STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/1369,Roads,Completed,NN-ADYAR,174,957000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT NEW KANNIGAPURAM 2nd STREET & NEW KANNIGAPURAM 3rd STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2017-18 NN/2016-17/1371,Roads,Completed,NN-ADYAR,174,1212000,PROPOSED LAYING OF CEMENT CONCRETE ROAD AT MANTHOPPU 2 STREET IN DN -174 U - 40A Z - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/14543,Buildings,Completed,NN-ADYAR,174,177000,"IMPROVEMENTS TO THE TOILET AT CITY LINK ROAD (MALE & FEMALE), & RACE COURSE ROAD IN DN -174,UT-40A,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/15920,Buildings,Completed,NN-ADYAR,174,400000,"REPAIRS TO THE AMMA UNAVAGAM AT VELACHERY MAIN ROAD DUE TO THE VARDHA CYCLONE IN DN-174,UNIT-40A,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16345,Buildings,Completed,NN-ADYAR,174,513000,"CONSTRUCTION OF DAMAGED 16 TH DAY CEREMONY HALL DUE TO VARDHA CYCLONE AT VELACHERY MAIN ROAD IN DN-174,UNIT-40A,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/1646,Roads,Completed,NN-ADYAR,174,325000,"Providing Garbage Bin Platform at Velechery main road,Five Furlong Road,Race course Road,Cart track road and Link road in Dn - 174 U - 40A Z - 13",Own Sources,13,2016-17,2018-19 NN/2016-17/16858,Parks,Completed,NN-ADYAR,174,535000,"GREENERY IMPROVEMENT TREE SAPLING PLANTATION WORK AT VARIOUS PLACES IN DIV-170,174 AND-177, UNIT -40-A,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16902,Parks,Completed,NN-ADYAR,174,790000,"REPAIRS TO THE PARK AT SECERETRIAT COLONY,CITY LIMIT ROAD DUE TO VARDHA CYCLONE IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16957,Footpath,Completed,NN-ADYAR,174,570000,"REPAIRS TO THE DAMAGED FOOTPATH DUE TO THE VARDHA CYCLONE AT VELECHERY MAIN ROAD AND FIVE FUR LONG ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/1725,Parks,Completed,NN-ADYAR,174,194000,"Maintenance of Park for 6 months at Secretariat Colony, City Limit Road in Dn 174, Unit 40A, Zone 13",Own Sources,13,2016-17,2018-19 NN/2016-17/1811,Buildings,Completed,NN-ADYAR,174,200000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND IMPROVEMENTS TO THE P C AT VELECHERY MAIN ROAD (JN 0F FIVE FUR LONG ROAD) IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/4673,Buildings,Completed,NN-ADYAR,174,950000,"PROPOSED CONSTRUCTION OF STAGE AT CHS AT FIVE FUR LONG ROAD ,MADUVANKARAI IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/4703,Buildings,Completed,NN-ADYAR,174,569000,"Outsourcing scavenging work for the Chennai High School, Chennai Middle School and Chennai Primary School at Five Furlong Road in Dn -174 Unit -40A Zone -13",Own Sources,13,2016-17,2018-19 NN/2016-17/4909,Electrical,Completed,NN-ADYAR,174,996000,"Additional and rewiring of CHS SCHOOL in ' A ' Block and ' B ' Block at Maduvankarai div-174,Zone-XIII.",Own Sources,13,2016-17,2019-20 NN/2016-17/4911,Electrical,Completed,NN-ADYAR,174,798000,"Additional and rewiring of CH SCHOOL in 'C' Block and primary school in Maduvankarai div-174,Zone-XIII.",Own Sources,13,2016-17,2019-20 NN/2016-17/4912,Electrical,Completed,NN-ADYAR,174,999000,"Additional and rewiring of CPS SCHOOL in ' D ' Block and Extn Building in Maduvankarai div-174,Zone-XIII.",Own Sources,13,2016-17,2019-20 NN/2016-17/7143,Storm Water Drain,Completed,NN-ADYAR,174,980000,"DESILTING AND IMPROVEMENTS TO THE STROM WATER DRAIN AT VELECHERY MAIN ROAD AND THIRUMURUGAN STREET IN DN-174,UT-40A,ZONE-13",Own Sources,13,2016-17,2019-20 NN/2016-17/7144,Storm Water Drain,Completed,NN-ADYAR,174,980000,"DESILTING AND IMPROVEMENTS TO THE STROM WATER DRAIN AT RACE COURSE INTERIOR ROAD AND FIVE FURLONG ROAD IN DN-174,UT-40A,ZONE-13",Own Sources,13,2016-17,2018-19 NN/2016-17/7145,Storm Water Drain,Completed,NN-ADYAR,174,979000,"DESILTING AND IMPROVEMENTS TO THE STROM WATER DRAIN AT MOSQUE COLONY CANAL,NETHAJI ROAD,VIGNESWARA STREET,GOPALA KRISHNAN STREET AND SECRETARIAT COLONY ( CITY LIMIT ROAD) IN DN-174,UT-40A,ZONE-13",Own Sources,13,2016-17,2019-20 NN/2016-17/7146,Storm Water Drain,Completed,NN-ADYAR,174,981000,"DESILTING AND IMPROVEMENTS TO THE STROM WATER DRAIN AT CART TRACK ROAD AND GULMOHAR AVENUE IN DN-174,UT-40A,ZONE-13",Own Sources,13,2016-17,2019-20 NN/2016-17/7244,Roads,Completed,NN-ADYAR,174,581000,"Providing Garbage Bin Platform at Various street in DN-177, Unit-40(A), Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7618,Buildings,Completed,NN-ADYAR,174,990000,"Repair and Painting works at Chennai Corporation Higher Secondary School Ground floor and First floor 'C' Block at Five Furlong road, Maduvangarai (UNDER WARD COUNCILLOR FUND 2016-17) in Dn-174,U-40A, Z-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/7710,Buildings,Completed,NN-ADYAR,174,995000,"Proposed Construction of New Amma Unavagam at velachery main road opp, Kannigapuram in Dn-174 U-40A Z-13",Own Sources,13,2016-17,2018-19 NN/2016-17/8031,Buildings,Completed,NN-ADYAR,174,585000,"Providing Bore well Falseceling, Aluminium Partition and water Supply Arrangement of New Amma Unavagam ,velachery main road opp, Kannigapuram in Dn-174 U-40A Z-13",Own Sources,13,2016-17,2018-19 NN/2016-17/8738,Buildings,Completed,NN-ADYAR,174,999000,"PROVIDING PROJECTOR ROOM AT CORPORATION PRIMARY SCHOOL 1ST FLOOR ABOVE AT,FIVE FURLONG ROAD,MADUVINKARAI IN DN-174 U-40A Z-13",Own Sources,13,2016-17,2018-19 NN/2016-17/8971,Buildings,Completed,NN-ADYAR,174,589000,"PROVIDING FALSE CEILING,ALUMINUM PARTITION AND ELECTRICAL ARRANGEMENTS TO THE PROJECTOR ROOM AT CORPORATION PRIMARY SCHOOL,FIVE FURLONG ROAD,MADUVINKARAI IN DN-174 U-40A Z-13",Own Sources,13,2016-17,2018-19 BR/2016-17/17602,Roads,Completed,BR-Bus Route Roads,175,2890000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at Sardhar Patel Road,DGS Dhinkaran Salai, Broadies Castle Road,LB Road in Div-171,173,175 Zone -13",Grants,13,2016-17,2017-18 BR/2016-17/18789,Roads,Completed,BR-Bus Route Roads,175,492000,"ATTENDING PATCH WORK AT SARDARPATEL ROAD , DURGA BAI DESHMUK RAOD, BESENT AVENUE, TALUK OFFICE RAOD IN ZONE-13",Own Sources,13,2016-17,2017-18 L/2016-17/17614,Electrical,Completed,L-Electrical,175,994500,"PROVIDING 11Nos OF 8Mtr LONG G.I OCTOGANAL LAMP POSTS WITH 150W-165W LED FITTINGS AT FIRST AVENUE, REACH-1, INDIRA NAGAR ( from the junction of LB road to the junction of 2nd main road Indira Nagar) IN DIVISION -175, ZONE-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/17615,Electrical,Completed,L-Electrical,175,957000,"PROVIDING 11Nos OF 8Mtr G.I OCTOGANAL STREET LAMP POSTS WITH 150W-165W LED FITTINGS AT FIRST AVENUE, REACH-2 INDIRA NAGAR ( from the junction of 2nd main road to the junction of 6th crosss street Indira Nagar) IN DIVISION -175, ZONE-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/17616,Electrical,Completed,L-Electrical,175,632000,"PROVIDING 11Nos OF 8Mtr G.I OCTOGANAL LAMP POST WITH 150W-165W LED FITTINGS AT FIRST AVENUE, REACH-3 INDIRA NAGAR ( from the junction of 2nd main road to the junction of 6th crosss street Indira Nagar) IN DIVISION -175, ZONE-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/17617,Electrical,Completed,L-Electrical,175,827000,"PROVIDING 9Nos OF 8Mtr G.I OCTOGANAL LAMP POST WITH 150W-165W LED FITTINGS AT FIRST AVENUE, REACH-4 INDIRA NAGAR ( from the junction of 10th cross street to the junction of 2nd avenue road Indira Nagar) IN DIVISION -175, ZONE-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/0733,Footpath,Completed,NN-ADYAR,175,710000,"Painting Footpath Kerbs, Trees, Center Median and Under Flyover Bridge side wall at Sardar Patel Road, in Dn.175, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/0738,Buildings,Completed,NN-ADYAR,175,953000,"Repairs and Improvements to R.J.C south office and Zonal office building Rooms and Toilets at Dr. Muthulakshmi salai in Dn-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/12818,Roads,Completed,NN-ADYAR,175,2800000,"Attending temporary restoration for damaged roads at Bakthavatchalam 5th street, Kasthuri bai nagar 1st & 2nd cross streets and Balaraman road due to flood in North East Monsoon 2015 in Dn-175,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12819,Roads,Completed,NN-ADYAR,175,2760000,"Attending temporary restoration for damaged roads at Gandhi nagar 1st main road (From jn.of Canal Bank road to Gandhi nagar 2nd cross street) due to flood in North East Monsoon 2015 in Dn-175,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12820,Roads,Completed,NN-ADYAR,175,2890000,"Attending temporary restoration for damaged roads at Gandhi nagar 1st main road (From jn.of Gandhi nagar 2nd cross street), Bakthavatchalam 3rd, 4th & 5th main roads and Nehru nagar 4th main road due to flood in North East Monsoon 2015 in Dn-175,U-40,Z-13",Own Sources,13,2016-17,2016-17 NN/2016-17/14605,Buildings,Completed,NN-ADYAR,175,102000,"Repairs and Improvemet works to Public Convenience at Balaraman Street and Indira Nagar XIII th Cross Street in Dn 175, Unit 40, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14617,Buildings,Completed,NN-ADYAR,175,572000,"Repair and Improvements to Chennai High School ,Kamaraj Avenue and Chennai Primary School, Indira Nagar 29 th Cross Street in Div-175,Unit-40,Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/15074,Footpath,Completed,NN-ADYAR,175,962000,"Repairs to Footpath (Damaged in Vardha Cyclone) at Gandhi Nagar in Div-175, unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16781,Buildings,Completed,NN-ADYAR,175,103000,"Construction of School compound wall at Indira Nagar 29th Cross street Chennai Primary School and Flooring tiles and Plumbing work at Chennai High School, Kamaraj Avenue ( Damaged in vardha cyclone) in div175, unit-40, zone13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16783,Footpath,Completed,NN-ADYAR,175,646000,"Repairs to Foot path (damaged in Vartha Cyclone) at Kasthuribai Nagar,Krishnamachari Avenue,Kamaraj Avenue,Nehru Nagar,Srinivasamurthy Avenue,Venkatrathnam Nagar, in div175, Unit40, Zone13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16857,Parks,Completed,NN-ADYAR,175,751000,"GREENERY IMPROVEMENT TREE SAPLING PLANTATION WORK AT VARIOUS PLACES IN DIV-171,172,173 AND-175, UNIT -40,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16874,Buildings,Completed,NN-ADYAR,175,119000,"Supplying and fixing of damaged Stainless Steel Name board ( Damaged in Vartha Cyclone) at Various Streets in div-175,Unit-40, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16876,Roads,Completed,NN-ADYAR,175,530000,"Repairs to road damaged due to Vardha cyclone at Bhaktavatsalam nagar 2nd street,Nehru nagar 1st street,Kasturibai nagar 2nd cross street and Indira nagar 21st cross street in div 175,Unit-40,Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16885,Storm Water Drain,Completed,NN-ADYAR,175,580000,"Construction of Existing Dilapidated SWD at Indira Nagar 1st main road, Baktavachalam 1,2,3 & 5 streets, Nehru Nagar 1& 2 streets & Kasturibai Nagar 5th main road ( Damaged in Vartha Cyclone) in div-175, unit-40, zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16886,Storm Water Drain,Completed,NN-ADYAR,175,580000,"Construction of Existing Dilapidated SWD at Gandhi Nagar, Kamaraj Avenue 2nd street, Krishnamachary Avenue and Indira Nagar ( Damaged in Vartha Cyclone) in div-175, unit-40, zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/3482,Storm Water Drain,Completed,NN-ADYAR,175,793000,"Repairs and Improvements to Storm Water Drain at Kasthuribai Nagar 1st Cross Street Junction of Anna Avenue, Kasthuribai Nagar 2nd Cross Street Junction of Kasthuribai Nagar 3rd Main Road and Kasthuribai Nagar 3rd Cross Street Junction of Nehru Nagar 1st Main Road in Dn-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/3483,Storm Water Drain,Completed,NN-ADYAR,175,864000,"Repairs and Improvements to Storm Water Drain at Bakthavachalam Nagar 2nd street Junction of Kasthuribai Nagar 2nd Cross Street, Kasthuribai Nagar 2nd Main Road Junction of Aranganal Salai and Supplying and Fixing Hume Pipe at Kasthuribai Nagar 2nd Main Road Junction of Kasthuribai Nagar 3rd Cross Street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/4166,Buildings,Completed,NN-ADYAR,175,334000,"Repairs and Improvement to Amma Canteen at Thiruvengadam Street in Dn-175, Unit-40, Zone13.",Own Sources,13,2016-17,2017-18 NN/2016-17/4441,Buildings,Completed,NN-ADYAR,175,664000,Outsourcing Scavenging work for the CHS And CPS at Kamaraj Avenue and CPS at Indira Nagar 29th Cross Street in Dn -175 unit -40 zone -13,Own Sources,13,2016-17,2018-19 NN/2016-17/4978,Storm Water Drain,Completed,NN-ADYAR,175,577000,"Repairs and Improvements to Storm Water Drain at Nehru Nagar 2nd Street Near TNEB Office in Dn-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/5093,Buildings,Completed,NN-ADYAR,175,780000,"Improvements to Play Ground with Badminton Court and Providing Children's Play apparatus at Thiruvengadam street in Dn-175, Unit-40, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/5181,Storm Water Drain,Completed,NN-ADYAR,175,999000,"Improvements and Desilting of Storm Water Drain at Indira nagar 2nd Avenue, Kasthuribai nagar 3rd Cross Street and Anna Avenue in Dn-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/5954,Storm Water Drain,Completed,NN-ADYAR,175,615000,"Improvements and Desilting of Storm Water Drain at Dr. Muthulakshmi Salai in Dn-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/6023,Parks,Completed,NN-ADYAR,175,980000,"Repairs and Improvements to park Footpath at Indira Nagar 4th Cross Street in Dn-175, Unit-40, Zone-13. (Councillor Fund)",Own Sources,13,2016-17,2017-18 NN/2016-17/6024,Parks,Completed,NN-ADYAR,175,994000,"Repairs and Improvements to park Compound wall at Indira Nagar 4th Cross Street in Dn-175, Unit-40, Zone-13. (Councillor Fund)",Own Sources,13,2016-17,2017-18 NN/2016-17/6025,Parks,Completed,NN-ADYAR,175,995000,"Repairs and Improvements to park with Children's Play apparatus and Greenery arrangements at Indira Nagar 4th Cross Street in Dn-175, Unit-40, Zone-13. (Councillor Fund)",Own Sources,13,2016-17,2019-20 NN/2016-17/6219,Buildings,Completed,NN-ADYAR,175,490000,"Water supply and Drainage connection Arrangements to Smart Toilet at Indira nagar 14th cross street and Backthavachalam Nagar 5th street Jun of School Road in Dn-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/7274,Roads,Completed,NN-ADYAR,175,551000,"Painting Footpath Kerbs, Trees and Centre Median at Sardar Patel Road, Dr.Muthulakshmi Salai and KalkiKrishnamoorthy Salai in Dn.175, Unit-40, Zone-13 in the view of Independence Day Celebration 2016",Own Sources,13,2016-17,2017-18 NN/2016-17/7401,Buildings,Completed,NN-ADYAR,175,550000,"PROVIDING REVERSE OSMOSIS PLANT IN ZONAL OFFICE-13 BUILDING IN DIV-175, U-40,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9864,Roads,Completed,NN-ADYAR,175,274000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Gandhi Nagar Pumping Station Road in DN-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9868,Roads,Completed,NN-ADYAR,175,528000,"Relaying the road with BCCMP 30mm thick including camber correction using by Paver Finisher at Indira Nagar X Cross Street in DN-175, Unit-40, Zone-13.",Own Sources,13,2016-17,2017-18 BR/2016-17/17662,Footpath,Completed,BR-Bus Route Roads,176,1480000,"Attending temporary restoration of damaged Footpath due to Vardha Cyclone in North East Monsoon 2016 at Sardhar Patel Road,LB Road,DGS Dhinakaran Salai,Srinivasa Avenue,Besant Avenue,Gandhi Nagar 4th Main Road in Div-171,172,173,175,176, Zone -13",Grants,13,2016-17,2017-18 BR/2016-17/17665,Footpath,Completed,BR-Bus Route Roads,176,2000000,"Attending temporary restoration of damaged Footpath due to Vardha Cyclone in North East Monsoon 2016 at Velachery Main Road,Gandhi Road,Five Furlong Road,Brindhavan Nagar Main Road,LakeView Road,Taluk Offfice Road,AGS Colony 4th Main Road,Gandhi Mandapam Road,Mahalakshmi Nagar Main Road ,Cannal Bank Road in Div-174,179,177,171, Zone -13",Grants,13,2016-17,2017-18 L/2016-17/16104,Electrical,Completed,L-Electrical,176,180000,"REPLACEMENT OF DAMAGED GALVANIZED STEEL WIRE ROPE AND COPPER FLEXIBLE TRAILING CABLE FOR THE HIGH MAST AT BESANT NAGAR ELLIOT'S BEACH ( 6TH AVENUE ROAD JUNCTION OF 4TH MAIN ROAD ) IN DIVISION-176, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/0004,Roads,Completed,NN-ADYAR,176,740000,"Providing Thermoplastic Marking For Speed Breakers At Besant Avenue , Besant nagar 6th Avenue, Sasthiri nagar 1st avenue, D.D. Road, Besant nagar 1st Avenue, Dhamodrapuram Main road, Padmanabha nagar 5th St. and Besant nagar 5th Avenue In Dn-176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/0850,Roads,Completed,NN-ADYAR,176,999000,"PROVIDING STREET FURNITURES AT SHASTHRI NAGAR, THIRUVALLUVAR NAGAR AND VARIOUS STREET IN DIVISION - 176, UNIT - 38, ZONE - 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/11169,Buildings,Completed,NN-ADYAR,176,998000,"Repairs to Storm Water Drain at Sastri nagar, Karpagam Garden, Prameshwari nagar, Venkateshwara nagar and Padmanabha nagar in Dn- 176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/1139,Buildings,Completed,NN-ADYAR,176,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.P.S AT SASTHRI NAGAR 11 TH STREET IN DN-176, UNIT-38, ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1140,Buildings,Completed,NN-ADYAR,176,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.M.S AT DHAMODARAPURAM 4 TH STREET IN DN-176, UNIT-38, ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/12710,Storm Water Drain,Completed,NN-ADYAR,176,995000,"Repairs to Storm Water Drain at Ramaswamy Garden, Besant ave road, DD road, Vasantha Press road and venkaeshwara 3rd Street in Dn- 176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/14750,Buildings,Completed,NN-ADYAR,176,296000,"Improvements to Chennai Middle School at Dhamodrapuram and Sastri Nagar 11th Cross Street in Dn-176, Unit-38, Zone-13",Own Sources,13,2016-17,2018-19 NN/2016-17/15827,Buildings,Completed,NN-ADYAR,176,260000,"Improvements to Memorial Buildings and Providing Barricading arrangements at Elliats Beach for New year-2017 (First January) and Pongal festival-2017 in Dn-176, Unit-38, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16865,Buildings,Completed,NN-ADYAR,176,393000,"Vardha Cyclone Repirs works to Footpath at Besant ave road, Besant nagar, Sastri nagar, Karpagam Garden and Venkateshwara nagar in Dn-176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16866,Buildings,Completed,NN-ADYAR,176,155395,"Vardha Cyclone Repair works to Park at Padmanabha nagar 5th street, Besant nagar 4th main road, 4th Avenue, 21st Cross street and Sastri nagar 11th Cross street in Dn-176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/1712,Parks,Completed,NN-ADYAR,176,265000,"MAINTENANCE OF PARK FOR 6 MONTHS AT Dr. MUTHULAKSHMI PARK AT D.D. ROAD IN DN 176, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1715,Parks,Completed,NN-ADYAR,176,131000,"MAINTENANCE OF PARK FOR 6 MONTHS AT BESANT NAGAR 4TH AVENUE IN DN 176, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1722,Parks,Completed,NN-ADYAR,176,136000,"MAINTENANCE OF PARK FOR 6 MONTHS AT PADMANABHA NAGAR 5TH STREET IN DN 176, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/19217,Roads,Completed,NN-ADYAR,176,2548000,"CONSTRUCTION OF BIN PLATFORMS AT VARIOUS STREETS, RELAYING OF THIRUVALLUVAR NAGAR 2ND AVENUE AND LAYING PIPE LINE AT JOURNALISTS COLONY IN DIVISION - 176, 181 & 182, ZONE - XIII (VARDAH CYCLONE WORKS)",Own Sources,13,2016-17,2017-18 NN/2016-17/1939,Buildings,Completed,NN-ADYAR,176,920000,"EXISTING RAINWATER HARVESTING CLEANING AND PROPOSED RAIN WATER HARVESTING AT KARPAGAM GARDEN 1ST, 2ND, 3RD, 4TH, 5TH, 6TH, 7TH,8TH, 9TH STREETS, SASTHIRI NAGAR 15TH CROSS STREET, SASTHIRI NAGAR 9TH LANE AND BESANT NAGAR IN DIVISION-176, UNIT-38, ZONE-13",Own Sources,13,2016-17,2016-17 NN/2016-17/2939,Electrical,Completed,NN-ADYAR,176,83000,"Improvement to water supply arrangements to PC at Arunachala Puram, Kabali Thottam, Urur Kuppam, 6th Avenue Beach(BIO-TOILET) in Dn-176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/3074,Roads,Completed,NN-ADYAR,176,850000,"Laying The Bituminous Road With BCCMP 40mm thick by Paver Finisher at Besant nagar 17th cross Street in DN-176, Unit-38, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3094,Roads,Completed,NN-ADYAR,176,371000,"Laying The Bituminous Road With BCCMP 40mm thick by Paver Finisher at Beach Home Avenue 1st Street in Dn-176, Unit-38, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3095,Roads,Completed,NN-ADYAR,176,352000,"Laying The Bituminous Road With BCCMP 40mm thick by Paver Finisher at Beach Home Avenue 2nd Street in Dn-176, Unit-38, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3096,Roads,Completed,NN-ADYAR,176,470000,"Laying The Bituminous Road With BCCMP 40mm thick by Paver Finisher at Karpagam Garden 4th cross Street in Dn-176, Unit-38, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3097,Roads,Completed,NN-ADYAR,176,472000,"Laying The Bituminous Road With BCCMP 40mm thick by Paver Finisher at Karpagam Garden 5th cross Street in Dn-176, Unit-38, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3152,Roads,Completed,NN-ADYAR,176,203000,"Laying The Bituminous Road With BCCMP 40mm thick by Paver Finisher at Karpagam Garden 9th cross Street in Dn-176, Unit-38, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3747,Roads,Completed,NN-ADYAR,176,898000,"Attending Wet Mix patch work and Providing Interlocking ILP80mm at New Beach Road in Dn-182, Unit-38, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/5025,Storm Water Drain,Completed,NN-ADYAR,176,287000,"Repairs to Side drain at Besant nagar Elliot's Beach in Dn-176, Unit-38, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/6829,Roads,Completed,NN-ADYAR,176,856000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Besant avenue road,Besant nagar 6th avenue and Sasthri nagar 11th cross street in Dn-176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/6830,Playfields,Completed,NN-ADYAR,176,518000,"Providing Weathering Course and Improvements to NNMP Shed at Kakken colony in Dn- 176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/6859,Playfields,Completed,NN-ADYAR,176,212000,"Improvements to NNMP Shed and Gym at Venkateshwara nagar 4th cross street in Dn- 176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7105,Electrical,Completed,NN-ADYAR,176,260000,"Improvements to NNMP Shed and Gym at Urur Kuppam Besant nagar in Dn-176,Unit-38,Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7106,Buildings,Completed,NN-ADYAR,176,784000,"Laying Garbage Bin Platform At Besant Nagar, Sasthiri Nagar, Dhamodrapuram, Venkateshwara Nagar, Karpagam Garden, Padmanabha Nagar, Jeevarathinam Nagar, Parameshwari Nagar And Arunachalapuram In Division-176 Unit-38 Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7666,Storm Water Drain,Completed,NN-ADYAR,176,968000,"Providing Inspection chamber and Silt-catch pit arrangements at Sasthiri nagar, Karpagam Garden, Venkateshwara nagar, Parameshwari nagar, and Padmanabha nagar in Dn-176, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7668,Buildings,Completed,NN-ADYAR,176,972000,"ATTENDING CEMENT CONCRETE PATCH WORK AT DHAMODRAPURAM, NEW STREET, ELLAIAMMAN KOIL LANE, BESANT AVENUE SLUM AREA, PONNIYAMMAN KOIL STREET IN DN-176, UNIT-38, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7892,Roads,Completed,NN-ADYAR,176,585000,"Painting Footpath Kerbs, Trees and Centre Median at D.D. Road, Besant Avenue and Besant nagar 3rd Avenue in Dn-176, Unit-38, Zone-13. In the view of Independence Day Celebration 2016",Own Sources,13,2016-17,2017-18 BR/2016-17/17767,Roads,Completed,BR-Bus Route Roads,177,3155000,"Strengthening and Relaying Road by Paver Finisher Work at Ambedkar Nagar 1st Main Road in Dn-177, Zone-13",Grants,13,2016-17,2017-18 BR/2016-17/18502,Roads,Completed,BR-Bus Route Roads,177,2300000,Restoration of Road Cut Made by CMWSSB at Kakkan Nagar Main Road in Div-177 Zone- 13,Deposit Works,13,2016-17,2017-18 BR/2016-17/18503,Roads,Completed,BR-Bus Route Roads,177,950000,Restoration of Road Cut Made by CMWSSB at Sasthiri Nagar Main Road in Div-177 Zone- 13,Grants,13,2016-17,2017-18 L/2016-17/14139,Electrical,Completed,L-Electrical,177,999000,PROVISION OF SUPPLY AND ERECTION OF 23 NOS OF KIOSK PILLAR BOXES AT VARIOUS LOCATIONS IN DIVISIONS 177 TO 182 IN ZONE-XIII,Own Sources,13,2016-17,2016-17 L/2016-17/14176,Electrical,Completed,L-Electrical,177,557000,PROVISION OF SUPPLY AND FIXING OF 200 NOS 2C SMC FUSE BOX AND 100 NOS 4C SMC FUSE BOX AT VARIOUS LOCATIONS IN DIVISIONS 177 TO 182 IN ZONE-XIII,Own Sources,13,2016-17,2017-18 NN/2016-17/0213,Roads,Completed,NN-ADYAR,177,890000,"Attending temporary restoration of damaged road at GangaiNagar 2nd Cross Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0214,Roads,Completed,NN-ADYAR,177,610000,"Attending temporary restoration of damaged road at EB colony 4th Street - 1 & 2 street and Nethaji colony 1 & 3 Cross street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0215,Roads,Completed,NN-ADYAR,177,630000,"Attending temporary restoration of damaged road at Nethaji Colony 2nd Cross Street And Shawalace colony 2nd Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0216,Roads,Completed,NN-ADYAR,177,640000,"Attending temporary restoration of damaged road at GangaiNagar I Cross Street and Sakthi Vijiyalakshmi Nagar 3rd Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0217,Roads,Completed,NN-ADYAR,177,840000,"Attending temporary restoration of damaged road at Mahalakshmi Nagar 16th Cross Street and E.B Colony 5th Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0218,Roads,Completed,NN-ADYAR,177,690000,"Attending temporary restoration of damaged road at Astalakshmi Nagar 1st Street and Andal Nagar Extn street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0219,Roads,Completed,NN-ADYAR,177,960000,"Attending temporary restoration of damaged road at Astalakshmi Nagar 2 & 9th Street and Astalakshmi Nagar Nethaji Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0220,Roads,Completed,NN-ADYAR,177,570000,"Attending temporary restoration of damaged road at NNGO Colony 2 & 3rd Cross Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0221,Roads,Completed,NN-ADYAR,177,870000,"Attending temporary restoration of damaged road at Shawalace Colony 1st Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0222,Roads,Completed,NN-ADYAR,177,890000,"Attending temporary restoration of damaged road at Mahalakshmi Nagar 8th Cross Street and Vel Ngar 3rd Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0223,Roads,Completed,NN-ADYAR,177,590000,"Attending temporary restoration of damaged road at Shawalace Colony 3rd Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0224,Roads,Completed,NN-ADYAR,177,640000,"Attending temporary restoration of damaged road at GangaiNagar 4th Street due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0225,Roads,Completed,NN-ADYAR,177,870000,"Attending temporary restoration of damaged road at NNGO Colony 1st Main Road due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0226,Roads,Completed,NN-ADYAR,177,930000,"Attending temporary restoration of damaged road at Ramakrishna Nagar 3rd Main Road due to floods in North East Monsoon 2015 in Division - 177, Unit - 40 A, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/0227,Roads,Completed,NN-ADYAR,177,990000,"Desilting of Strom Water Drain MGR Nagar 3rd street,LH Nagar 1st Main Road,Bashyam Layout Indira Gandhi,Astalakshmi Nagar 9 & 10th Street,Nethaji Street,Vel Nagar Main Road & 2nd Street,Krishnaraja Nagar 1st Street & Extn 1st Street, Andal Nagar 2nd Main Road,New Secreriate Colony 6th Street and Raja Sethupathypuram 2nd Cross street in Dn - 177 Unit - 40A Zone - 13",Own Sources,13,2016-17,2017-18 NN/2016-17/0228,Roads,Completed,NN-ADYAR,177,991000,"Desilting of Strom Water Drain at Mahalakshmi Nagar 4th Main road,Telephone Colony 1st Street,Kakkan Nagar 2nd Cross Street,LH Nagar 2nd Main Road,Indira gandhi Nagar 3rd Street,Periyar Nagar 7,8 & 11th Cross Street, Andal Nagar 2 & 6th street,Radha Nagar Extn 3rd Street,Mohanapuri 2nd Street, L.H. Nagar 2nd Main Road, NNGO Colony 4th Main Road in Dn -177 Unit -40A Zone -13",Own Sources,13,2016-17,2017-18 NN/2016-17/11260,Electrical,Completed,NN-ADYAR,177,935000,"Additional and rewiring of Unit Office 40A at West Velacherry div-177,Zone-XIII.",Own Sources,13,2016-17,2019-20 NN/2016-17/1142,Roads,Completed,NN-ADYAR,177,2157000,"Proposed laying of Bituminous Concrete road at A.S.K Nagar Ist street, 2nd street, 3rd street & 4th street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/11489,Buildings,Completed,NN-ADYAR,177,980000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period AT Dr.Ambedkar III cross street in Dn - 177, Zone - XIII",Own Sources,13,2016-17,2018-19 NN/2016-17/11491,Buildings,Completed,NN-ADYAR,177,998000,"Supply, Installation,Commissioning of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity at Dr.Ambedkar nagar III cross street in Dn - 177, Zone - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/11986,Storm Water Drain,Completed,NN-ADYAR,177,635000,Desilting of Raj Bhavan Canal at ( From Kambar Street To Marudhupandi Salai ) in Dn 177 Unit 40A Zone 13,Own Sources,13,2016-17,2019-20 NN/2016-17/12181,Buildings,Completed,NN-ADYAR,177,770000,Improvements to Sasthiri Nagar Urban Primary Health Center at Sasthiri Nagar 4th Street in Dn 177 Unit 40A Zone 13,Own Sources,13,2016-17,2018-19 NN/2016-17/1255,Roads,Completed,NN-ADYAR,177,697000,"Proposed laying of Bituminous Concrete road at Ganesh Nagar 1st cross street (Telephone Colony) in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1256,Roads,Completed,NN-ADYAR,177,555000,"Proposed laying of Bituminous Concrete road at Ex Servicemen Colony II Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/1373,Roads,Completed,NN-ADYAR,177,623000,"Proposed laying of Bituminous Concrete road at TNHB Colony- VI Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1382,Roads,Completed,NN-ADYAR,177,623000,"Proposed laying of Bituminous Concrete road at TNHB Colony- VIII Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1388,Roads,Completed,NN-ADYAR,177,660000,"Proposed laying of Bituminous Concrete road at Brindavan Nagar Extn 1st Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1389,Roads,Completed,NN-ADYAR,177,708000,"Proposed laying of Bituminous Concrete road at Radha Nagar Extn 1st Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1390,Roads,Completed,NN-ADYAR,177,708000,"Proposed laying of Bituminous Concrete road at Radha Nagar Extn II Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1391,Roads,Completed,NN-ADYAR,177,935000,"Proposed laying of Bituminous Concrete road at Andal Nagar II Cross Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1392,Roads,Completed,NN-ADYAR,177,681000,"Proposed laying of Bituminous Concrete road at Ashtalakshmi Nagar III Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1393,Roads,Completed,NN-ADYAR,177,345000,"Proposed laying of Bituminous Concrete road at Ashtalakshmi Nagar V Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1394,Roads,Completed,NN-ADYAR,177,345000,"Proposed laying of Bituminous Concrete road at Ashtalakshmi Nagar VI Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1395,Roads,Completed,NN-ADYAR,177,259000,"Proposed laying of Bituminous Concrete road at Natesan Nagar Ist Street in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/1396,Roads,Completed,NN-ADYAR,177,345000,"Proposed laying of Bituminous Concrete road at Sakthi Vijayalakshmi Nagar Ist Street(part), in DN-177,UNIT-4O(A),Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/1397,Roads,Completed,NN-ADYAR,177,345000,"Proposed laying of Bituminous Concrete road at Sakthi Vijayalakshmi Nagar II 2nd Street(part), in DN-177,UNIT-4O(A),Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14580,Buildings,Completed,NN-ADYAR,177,76000,Improvements to Public Convenience at Marudhupandi Salai in Division -177 Unit -40 A Zone-13,Own Sources,13,2016-17,2017-18 NN/2016-17/14830,Buildings,Completed,NN-ADYAR,177,685000,Improvements Work & Water Supply Arrangement work for Chennai Primary School at TNHB Colony 3rd Avenue in Dn -177 Unit -40A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/14833,Buildings,Completed,NN-ADYAR,177,420000,Providing Dinning Hall for Chennai Primary School at TNHB Colony 3rd Avenue in Dn -177 Unit - 40 Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/16888,Buildings,Completed,NN-ADYAR,177,510000,"Suppling and fixing Street Name Board at Various Street in Division-177,Unit-40A, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16895,Playfields,Completed,NN-ADYAR,177,85000,"Supplying and Fixing Play Apparatus,Park at LH Nagar 4th Cross Street and Play Field at Shawalace Colony in DN -177 Unit -40A Zone -13",Own Sources,13,2016-17,2017-18 NN/2016-17/16898,Buildings,Completed,NN-ADYAR,177,90000,Supplying and Fixing of Water Tank at Division Office in Mahalakshmi Nagar Main Road and Supplying and Fixing GI Sheet of Chennai Corporation Dispensary at TNHB Colony 3rd Avenue in Dn -177 Unit - 40A Zone - 13,Own Sources,13,2016-17,2017-18 NN/2016-17/16900,Storm Water Drain,Completed,NN-ADYAR,177,210000,Improvement to Storm Water Drain at Periyar Nagar 3rd Cross Street and Dr. Ambekkar Nagar 1st Main Road in Div 177 zone 13,Own Sources,13,2016-17,2017-18 NN/2016-17/16968,Buildings,Completed,NN-ADYAR,177,36000,Repairs Work For UPHC at Sasthiri Nagar 4th Street and Amma Unavagam at Kakkan Nagar Main Road in Dn -177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/1727,Parks,Completed,NN-ADYAR,177,131000,"MAINTENANCE OF PARK FOR 6 MONTHS AT NNGO COLONY 2ND MAIN ROAD IN DN 177, UNIT 40A, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1728,Parks,Completed,NN-ADYAR,177,64000,"MAINTENANCE OF PARK FOR 6 MONTHS AT L.H. NAGAR 4TH CROSS STREET IN DN 177, UNIT 40A, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/19465,Playfields,Completed,NN-ADYAR,177,388000,Proposed Relaying of Bituminous Concrete road at Ragavendra Street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19466,Playfields,Completed,NN-ADYAR,177,667000,Proposed Relaying of Bituminous Concrete road at Balaji Colony Main Road in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19467,Playfields,Completed,NN-ADYAR,177,129000,Proposed Relaying of Bituminous Concrete road at Balaji Colony 2nd street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19468,Playfields,Completed,NN-ADYAR,177,408000,Proposed Relaying of Bituminous Concrete road at Nethaji Colony 4th Cross Street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19469,Playfields,Completed,NN-ADYAR,177,551000,Proposed Relaying of Bituminous Concrete road at EB Colony 1st Street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19470,Playfields,Completed,NN-ADYAR,177,405000,Proposed Relaying of Bituminous Concrete road at Rajiv Nagar Bharathi Street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19471,Playfields,Completed,NN-ADYAR,177,1263000,Proposed Relaying of Bituminous Concrete road at Ramakrishna Nagar 3rd Main Road in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19472,Playfields,Completed,NN-ADYAR,177,475000,Proposed Relaying of Bituminous Concrete road at Lakshmi Nagar 3rd Cross Street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19473,Playfields,Completed,NN-ADYAR,177,632000,Proposed Relaying of Bituminous Concrete road at Mahalakshmi Nagar 4th Cross Street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19474,Playfields,Completed,NN-ADYAR,177,939000,Proposed Relaying of Bituminous Concrete road at Mahalakshmi Nagar 6th Cross Street in Dn-177 Unit -40 A Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/19502,Buildings,Completed,NN-ADYAR,177,945000,"BUILDING MAINTENANCE WORK AT DIVISION OFFICE, HOSPITAL AND ANGANVADI IN DN-177,UNIT-40 (A), ZONE-13",Own Sources,13,2016-17,2018-19 NN/2016-17/19872,Electrical,Completed,NN-ADYAR,177,181000,"Proposed New Wiring of Amma Drinking Water Plant in 8th Cross Street Ambedkar Nagar at Adambakkam Div-177,Zone-XIII",Own Sources,13,2016-17,2019-20 NN/2016-17/19873,Electrical,Completed,NN-ADYAR,177,340000,"Wiring of Newly Construction of Amma Unavagam at Kakkan nagar main Road in Adambakkam Div-177, Zone-XIII.",Own Sources,13,2016-17,2018-19 NN/2016-17/3102,Roads,Completed,NN-ADYAR,177,5181000,"PROPOSED LAYING OF CEMENT CONCRETE ROAD AT A.L.MUDALI 1st STREET in DN-177,ZONE-13.",Own Sources,13,2016-17,2016-17 NN/2016-17/3107,Roads,Completed,NN-ADYAR,177,340000,"PROPOSED LAYING OF CEMENT CONCRETE ROAD AT A.G.S COLONY 7th CROSS STREET in DN-177,ZONE-13.",Own Sources,13,2016-17,2016-17 NN/2016-17/3108,Roads,Completed,NN-ADYAR,177,383000,"PROPOSED LAYING OF CEMENT CONCRETE ROAD AT ANDAL NAGAR II STREET I LANE in DN-177,ZONE-13.",Own Sources,13,2016-17,2016-17 NN/2016-17/3110,Roads,Completed,NN-ADYAR,177,298000,"ROPOSED LAYING OF CEMENT CONCRETE ROAD AT ANDAL NAGAR II LANE in DN-177,ZONE-13.",Own Sources,13,2016-17,2016-17 NN/2016-17/3112,Roads,Completed,NN-ADYAR,177,298000,"ROPOSED LAYING OF CEMENT CONCRETE ROAD AT ANDAL NAGAR III LANE in DN-177,ZONE-13.",Own Sources,13,2016-17,2016-17 NN/2016-17/4443,Buildings,Completed,NN-ADYAR,177,189000,"Outsourcing Scavenging work for the CPS at TNHB Colony 3 rd Avenue in Dn-177, Unit-40A zone - 13",Own Sources,13,2016-17,2018-19 NN/2016-17/4469,Buildings,Completed,NN-ADYAR,177,913000,Dismantling and Reconstruction of Compound Wall and improvements work at Chennai Primary School and Hospital at T.N.H.B Colony 3rd Avenue in DN-177 Unit-40( A ) Zone -13,Own Sources,13,2016-17,2018-19 NN/2016-17/4853,Buildings,Completed,NN-ADYAR,177,2493000,"CONSTRUCTION OF COMMUNITY HALL AT NEHRU NAGAR ANNA STREET, IN DN-177 UNIT:40(A) ZONE-13",MLACDS,13,2016-17,2017-18 NN/2016-17/4864,Culvert,Completed,NN-ADYAR,177,922000,"CONSTRUCTION OF CULVERTS AT A.L Mudhali 1st & 2nd street, Thiruvalluvar street, Karunanithi street and Gandhiyar Street IN DN-177 UNIT-40(A) ZONE-13",Own Sources,13,2016-17,2019-20 NN/2016-17/4926,Culvert,Completed,NN-ADYAR,177,958000,"Dismantling and Reconstruction of CULVERTS at Brindhavan Nagar 5th street,Brindhavan Nagar Ext 2nd & 3rd Street, T.N.H.B Nehru Nagar kamaraj street, L.H Nagar 4th cross street IN DN-177 UNIT-40(A) ZONE-13",Own Sources,13,2016-17,2019-20 NN/2016-17/6501,Storm Water Drain,Completed,NN-ADYAR,177,990000,"Desilting of Storm Water Drain at Rajiv nagar Radha main road, Netaji Colony IX Cross street, Brindhavan nagar main road & Mahalakshmi nagar I main road, Kakkan nagar I main road, Indra Gandhi III Street, Periyar nagar main road, Periyar nagar II cross street, Dr. Ambetkar nagar I main road And Nethaji Road in Dn-177, Unit-40(A), Zone-13",Own Sources,13,2016-17,2019-20 NN/2016-17/6513,Storm Water Drain,Completed,NN-ADYAR,177,990000,"Desilting of Storm Water Drain at T.N.H.B III Main road, EB colony main road, Nehru nagar- Kamaraj street, New secreteriate colony VI street, Rajiv nagar main road, Radha nagar ext, sri nagar colony main road, Nethaji colony II main road, Nethaji colony VI cross street, NNGO colony IV main road in Dn-177, Unit-40(A), Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7247,Buildings,Completed,NN-ADYAR,177,990000,"Desilting of Strom Water Drain at Joseph colony main road,Kakkan Nagar 1st cross Street,Andal Nagar 2nd Cross Street,LH Nagar 1st Street,Telephone colony 2nd main road,TNHB colony 2nd Main Road,ASK Nagar Main Road,Dr.Ambedkar Nagar 2nd Cross Street,New Secretariate colony 6th Cross Street and Raja Sethupathypuram 2nd Cross Street in Dn -177 Unit -40 A Zone -13",Own Sources,13,2016-17,2018-19 NN/2016-17/8164,Buildings,Completed,NN-ADYAR,177,500000,Proposed Construction Compound wall and Improvements to Amma Canteen work at Lake View Road in Dn -177 Unit -40a Zone -13,Own Sources,13,2016-17,2018-19 NN/2016-17/8390,Storm Water Drain,Completed,NN-ADYAR,177,800000,"CONSTRUCTION OF STORM WATER DRAIN (ROAD CROSSING) AT RADHA NAGAR EXTN AND LAKSHMI HAYAGREEVA NAGAR 2ND MAIN ROAD AND EB COLONY MAIN ROAD, VELACHERY IN DVN-177, UNIT-40A, ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/8463,Storm Water Drain,Completed,NN-ADYAR,177,985000,"Desilting of Strom Water Drain at A.G.S Colony II main road,A.G.S Colony IV main road,A.G.S Colony VI cross street,A.G.S Colony VII cross street,Brindavan Nagar Extn II street,Brindavan Nagar Extn III street,E.B Colony main road,E.B Colony VI street,Ganesh Nagar main road (M.L Nagar),Ganesh nagar III street,Ganesh nagar cross street,Mohanapuri V street in Dn - 177 Unit - 40A Zone - 13",Own Sources,13,2016-17,2019-20 NN/2016-17/8464,Storm Water Drain,Completed,NN-ADYAR,177,990000,"Desilting of Strom Water Drain at New Secretariat colony 5th street,L.H.Nagar 4th cross street,Rama Krishna nagar 1st main road,Ramakrishna nagar 2nd main road,Nethaji colony 4th cross street,Andal nagar ext Main Road,M.G.R Nagar 5th street,Andal nagar 1st cross street,Andal Nagar 3rd Cross street,Nethaji colony 2nd main road and Ramakrishna nagar II cross street, in Dn -177 Unit -40A Zone -13",Own Sources,13,2016-17,2017-18 NN/2016-17/8705,Buildings,Completed,NN-ADYAR,177,980000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM AT KAKKAN NAGAR MAIN ROAD IN DN-177,UT-40A,ZONE-13",Own Sources,13,2016-17,2018-19 NN/2016-17/8706,Buildings,Completed,NN-ADYAR,177,995000,"PROVIDING FALSE CEILING AND WATER SUPPLY ARRANGEMENTS TO THE AMMA UNAVAGAM AT KAKKAN NAGAR MAIN ROAD IN DN-177,UT40A,ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/8722,Roads,Completed,NN-ADYAR,177,999000,"proposed fixing of street name boards using stainless steel pipe and retro raflective sheet at various streets (Councilor Fund) in Dn 177 , Unit 40(A) , Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/8723,Roads,Completed,NN-ADYAR,177,999000,"proposed fixing of street name boards using stainless steel pipe and retro raflective sheet at various streets (Councilor Fund) in Dn 177 , Unit 40(A) , Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/8724,Roads,Completed,NN-ADYAR,177,999000,"Proposed fixing of street name boards using stainless steel pipe and retro raflective sheet at various streets (Councilor Fund) in Dn 177 , Unit 40(A) , Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9085,Buildings,Completed,NN-ADYAR,177,212000,Maintenance work in public Toilet at Marudhupandi Salai (Jn of Velachery 100 feet Bye Pass Road) in Dn - 177 U - 40A Z- 13,Own Sources,13,2016-17,2017-18 NN/2016-17/9284,Buildings,Completed,NN-ADYAR,177,830000,Providing Shed and other Improvements to Amma Kudineer Station at Dr.Ambedkar Nagar 3rd Cross Street in Dn-177 Unit - 40A Zone-13,Own Sources,13,2016-17,2016-17 NN/2016-17/9298,Storm Water Drain,Completed,NN-ADYAR,177,330000,Construction of Side Drain at MGR Nagar 4th Cross Street in Dn - 177 Unit -40A Zone - 13,Own Sources,13,2016-17,2018-19 NN/2016-17/9300,Roads,Completed,NN-ADYAR,177,325000,Attending Temporary Restoration of damaged interior roads due to floods in NEM 2015 At Lake VIew Road ( Part ) in Dn-177 Unit-40A Zone -13,Own Sources,13,2016-17,2016-17 NN/2016-17/9302,Buildings,Completed,NN-ADYAR,177,670000,Proposed Construction of Compound Wall at Amma Kudineer Station Dr.Ambedkar Nagar 3rd Cross Street in Dn -177 Unit - 40 A Zone -13,Own Sources,13,2016-17,2016-17 NN/2016-17/9544,Roads,Completed,NN-ADYAR,177,812000,"Proposed laying of Bituminous Concrete road at Venkateswara Nagar 6th Main Road ( 3rd Main Road Part ) in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9545,Roads,Completed,NN-ADYAR,177,504000,"Proposed laying of Bituminous Concrete road at Mahalakshmi Nagar 15th Cross Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9546,Roads,Completed,NN-ADYAR,177,318000,"Proposed laying of Bituminous Concrete road at NGO Colony 2nd Cross Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9547,Roads,Completed,NN-ADYAR,177,430000,"Proposed laying of Bituminous Concrete road at NGO Colony 2nd Main Road in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9548,Roads,Completed,NN-ADYAR,177,142000,"Proposed laying of Bituminous Concrete road at Rajiv Nagar Pandiyan Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9549,Roads,Completed,NN-ADYAR,177,370000,"Proposed laying of Bituminous Concrete road at Secretariate Colony 2nd Main Road in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9550,Roads,Completed,NN-ADYAR,177,370000,"Proposed laying of Bituminous Concrete road at Telephone Colony 2nd Main Road in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9551,Roads,Completed,NN-ADYAR,177,710000,"Proposed laying of Bituminous Concrete road at Venkateswara Nagar 6th Main Road in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9552,Roads,Completed,NN-ADYAR,177,556000,"Proposed laying of Bituminous Concrete road at Nethaji Colony 5th Cross Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9553,Roads,Completed,NN-ADYAR,177,260000,"Proposed laying of Bituminous Concrete road at Gangai Nagar 4th Cross Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9554,Roads,Completed,NN-ADYAR,177,203000,"Proposed laying of Bituminous Concrete road at Gangai Nagar 5th Main Road - 2nd Cross Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9555,Roads,Completed,NN-ADYAR,177,1441000,"Proposed laying of Bituminous Concrete road at Gangai Nagar 5th Main Road in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9556,Roads,Completed,NN-ADYAR,177,331000,"Proposed laying of Bituminous Concrete road at Lakshmi Nagar 2nd Cross Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9557,Roads,Completed,NN-ADYAR,177,257000,"Proposed laying of Bituminous Concrete road at Lakshmi Nagar 4th Cross Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/9558,Roads,Completed,NN-ADYAR,177,1420000,"Proposed laying of Bituminous Concrete road at Lakshmi Nagar 2nd Street in Dn-177,U-40(A),Z-XIII",Own Sources,13,2016-17,2017-18 L/2016-17/16095,Electrical,Completed,L-Electrical,178,743000,"Restoration of Damaged posts in various locations in Dn-170, 177 to 179 in Zone-XIII, due to Vardha cyclone effect on 12-12-16 .",Own Sources,13,2016-17,2017-18 L/2016-17/16762,Electrical,Completed,L-Electrical,178,839000,"Provision of 21nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at Anna Nagar 5th main road in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/11659,Storm Water Drain,Completed,NN-ADYAR,178,998000,"Desilting of S.W.D., Providing FRC Manhole Cover & Situ Catch Pit at Various Streets (Copy of List Enclosed) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11722,Storm Water Drain,Completed,NN-ADYAR,178,949000,"Dismantling and Providing top slab & Raising S.W.D. at Maheswari Nagar (L-130m) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11892,Roads,Completed,NN-ADYAR,178,839000,"Attending to Temporary Restoration of damaged Rajalakshmi Nagar 7th Cross street,Vijaya Nagar 2nd Cross Street,Ram Nagar 6th Street & Mettu Street due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13",Own Sources,13,2016-17,2016-17 NN/2016-17/11893,Roads,Completed,NN-ADYAR,178,840000,"Attending to Temporary Restoration of damaged Murugu Nagar 2nd Street, MGR Nagar 13th Main Road, Devi Karumariamman Main Road & Vagai Street due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13",Own Sources,13,2016-17,2016-17 NN/2016-17/11894,Roads,Completed,NN-ADYAR,178,880000,"Attending to Temporary Restoration of damaged Bhel Sakthi Nagar Main Road, Rennissuce Avenue & Alagapa Nagar Anna Street due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13",Own Sources,13,2016-17,2016-17 NN/2016-17/11896,Roads,Completed,NN-ADYAR,178,880000,"Attending to Temporary Restoration of damaged VOC Nagar 3rd Street,Unit Office & Vijaya Nagar 2nd Main Road due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13",Own Sources,13,2016-17,2016-17 NN/2016-17/11897,Roads,Completed,NN-ADYAR,178,999000,Attending to Temporary Restoration of damaged Orandiyamman Koil Street( Reach 1)due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/11898,Roads,Completed,NN-ADYAR,178,980000,Attending to Temporary Restoration of damaged Orandiyamman Koil Street( Reach 2)due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/11899,Roads,Completed,NN-ADYAR,178,995000,"Attending to Temporary Restoration of damaged Pillaiyar Koil Street,Srinivasa Nagar 1st Cross Street & MGR Nagar 12th Main Road due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13",Own Sources,13,2016-17,2016-17 NN/2016-17/11900,Roads,Completed,NN-ADYAR,178,450000,"Attending to Temporary Restoration of damaged MGR Nagar 10th Main Road & MGR Nagar 11th Main Road due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13",Own Sources,13,2016-17,2016-17 NN/2016-17/11901,Roads,Completed,NN-ADYAR,178,840000,Attending to Temporary Restoration of damaged AGS Colony 7th Cross Street & AGS Colony 7th Main Road due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/11903,Roads,Completed,NN-ADYAR,178,820000,Attending to Temporary Restoration of damaged Vijaya Nagar 1st Main Road( Reach 1) due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/11905,Roads,Completed,NN-ADYAR,178,820000,Attending to Temporary Restoration of damaged Vijaya Nagar 1st Main Road ( Reach 2) due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/11906,Roads,Completed,NN-ADYAR,178,470000,Attending to Temporary Restoration Wetmix Macadam of damaged Vijaya Nagar1st Main Road ( Reach 1)due to flood in North East Monsoon 2015 in Dn -178 Unit-39 Zone - 13,Own Sources,13,2016-17,2016-17 NN/2016-17/11961,Roads,Completed,NN-ADYAR,178,995000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Brahmin Street Part in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/11962,Roads,Completed,NN-ADYAR,178,411000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Pillaiyar Koil Street lane in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/14819,Buildings,Completed,NN-ADYAR,178,867000,"Improvements to Chennai Primary School at Rajalakshmi Nagar 2nd Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14820,Buildings,Completed,NN-ADYAR,178,893000,"Improvements to Chennai Higher Secondary School at Rajalakshmi Nagar 2nd Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14841,Buildings,Completed,NN-ADYAR,178,434000,"Provision of Water Supply & Drainage arrangements to C.P.S. & C.H.S.S. at Rajalakshmi Nagar 2nd Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/1656,Road Cut,Completed,NN-ADYAR,178,998000,"Restoration of Road Cut made by CMWSSB at Orandiamman Koil Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16940,Footpath,Completed,NN-ADYAR,178,38000,"Repairs to Play Ground at Ram Nagar 1st Street & Vijaya Nagar 1st main road (Damaged in Vartha Cyclone) In div-178, Unit-39, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16942,Buildings,Completed,NN-ADYAR,178,56000,"Construction of Park compound wall at AGS Colony 4th cross street (Damaged in Vartha cyclone) in div178, Unit-39, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16943,Roads,Completed,NN-ADYAR,178,76000,"Supplying and fixing Name Board at Various street (Damaged in Vartha Cyclone) in div-178, Unit-39, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16944,Storm Water Drain,Completed,NN-ADYAR,178,111000,"Repairs to SWD at Vijaya Nagar 3rd cross street (Damaged in Vartha Cyclone) in div-178, Unit-39, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/18015,Footpath,Completed,NN-ADYAR,178,66000,"REPAIRS TO FOOTPATH AT VIJAYANAGAR I MAIN ROAD AND JAGANATHAPURAM III MAIN ROAD (RAJALAKSHMI NAGAR) IN DIVISION - 178, ZONE - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/1807,Parks,Completed,NN-ADYAR,178,124000,"MAINTENANCE OF PARK FOR 6 MONTHS AT A.G.S. COLONY 4TH MAIN ROAD IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1814,Parks,Completed,NN-ADYAR,178,122000,"MAINTENANCE OF PARK FOR 6 MONTHS AT A.G.S. COLONY 4TH MAIN ROAD (JN. OF 4TH CROSS STREET) IN DN 178, UNIT 39, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/19223,Roads,Completed,NN-ADYAR,178,1124000,"CONSTRUCTION OF BIN PLATFORMS AT VARIOUS STREETS IN DIVISIONS 178, 179 & 180, ZONE - XIII (VARDAH CYCLONE WORKS)",Own Sources,13,2016-17,2017-18 NN/2016-17/2075,Buildings,Completed,NN-ADYAR,178,366000,"Out Sourcing Scavenging work for Toilet Cleaning the Chennai Higher Scondary School at Rajalakshmi Nagar in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/2076,Buildings,Completed,NN-ADYAR,178,183000,"Out Sourcing Scavenging work for Toilet Cleaning the Chennai Primary School at Rajalakshmi Nagar in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/3775,Roads,Completed,NN-ADYAR,178,740000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Sankar Nagar in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3790,Roads,Completed,NN-ADYAR,178,415000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Srinivasa Nagar Main Road in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3795,Roads,Completed,NN-ADYAR,178,834000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at M.G.R Nagar 12th Main Road in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3796,Roads,Completed,NN-ADYAR,178,793000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Bajanai koil Street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3797,Roads,Completed,NN-ADYAR,178,635000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Mettu Street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3798,Roads,Completed,NN-ADYAR,178,998000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Telugu Brahmin Street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3799,Roads,Completed,NN-ADYAR,178,755000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Nattar Street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3801,Roads,Completed,NN-ADYAR,178,415000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Muthuraja Street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3802,Roads,Completed,NN-ADYAR,178,760000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Rajalakshmi Nagar 7th Cross street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/3938,Roads,Completed,NN-ADYAR,178,811000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Rajalakshmi Nagar 1st main road in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/4896,Roads,Completed,NN-ADYAR,178,992000,"Laying cement concrete road at Lakshmipuram 3rd Cross Street From Lakshmipuram Main Road To Lakshmipuram 3rd Cross StreetLane in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/4897,Roads,Completed,NN-ADYAR,178,999000,"Laying cement concrete road at Lakshmipuram 3rd Cross Street Lane From Lakshmipuram 3rd cross street To Dead End in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/4898,Roads,Completed,NN-ADYAR,178,746000,"Proposed Laying of Bituminous Concrete road at AGS Colony 6th Main Road in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2017-18 NN/2016-17/6655,Roads,Completed,NN-ADYAR,178,720000,FORMING AND LAYING OF CC ROAD AT THROWPATHY AMMAN KOIL 2ND CROSS STREET IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2017-18 NN/2016-17/6656,Roads,Completed,NN-ADYAR,178,660000,FORMING AND LAYING OF CC ROAD AT JAGANATHAPURAM 1ST AND 5TH CROSS STREET IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2017-18 NN/2016-17/6657,Roads,Completed,NN-ADYAR,178,998000,FORMING AND LAYING OF CC ROAD AT THROWPATHY AMMAN KOIL 5TH CROSS STREET AND BRAHMIN STREET IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2017-18 NN/2016-17/6665,Roads,Completed,NN-ADYAR,178,890000,"FORMING AND LAYING OF CC ROAD AT THROWPATHY AMMAN KOIL 5TH CROSS STREET EXTN., IN DN-178 U-39 Z-13",Own Sources,13,2016-17,2017-18 NN/2016-17/6686,Roads,Completed,NN-ADYAR,178,880000,FORMING AND LAYING OF CC ROAD AT JAGANATHAPURAM 2ND CROSS STREET IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2017-18 NN/2016-17/6741,Storm Water Drain,Completed,NN-ADYAR,178,997000,"Desilting of S.W.D., Providing FRC Manhole Cover & Situ Catch Pit atA.G.S. Colony 5th Main Road, A.G.S. Colony Vinayakapuram Main Road, A.G.S. Colony 4th Cross Street, Kalki Nagar Main Road & A.G.S. Colony 5th Cross Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/6742,Storm Water Drain,Completed,NN-ADYAR,178,999000,"Desilting of S.W.D., Providing FRC Manhole Cover & Situ Catch Pit at Chockalingam Nagar (Part), Sterling Estate, Alagappa Nagar, V.O.C. Nagar Main Road, Padmavathy Nagar Main Road, Srinivasa Nagar 2nd Street, Kuberan Nagar, Sankar Nagar, Srinivasa Nagar 1st Street in Dn 178, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/6822,Roads,Completed,NN-ADYAR,178,900000,FORMING AND LAYING OF CC ROAD AT THROWPATHY AMMAN KOIL1ST CROSS STREET IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2017-18 NN/2016-17/8918,Buildings,Completed,NN-ADYAR,178,990000,Proposed Construction of GYM Building at Brhamin street (Councilor Fund) in Dn - 178 Unit - 39 Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/8921,Buildings,Completed,NN-ADYAR,178,990000,Construction of Compound wall and Supplying and fixing of GYM equipment at Bharamin Street (Councilor Fund) in Dn - 178 Unit -39 Zone 13,Own Sources,13,2016-17,2018-19 NN/2016-17/9140,Parks,Completed,NN-ADYAR,178,990000,Improvements to Children play field at AGS Colony 6th Street (Councilor Fund) in Dn -178 Unit -39 Zone -13,Own Sources,13,2016-17,2017-18 NN/2016-17/9481,Roads,Completed,NN-ADYAR,178,980000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Jaganadhapuram 1st main road From: Rajalakshmi Nagar 1st main road To Jaganadhapuram 1st cross street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/9483,Roads,Completed,NN-ADYAR,178,998000,LAYING OF CC ROAD AT LAKSHMI PURAM MAIN ROAD CH(90-160) AND LAKSHMI PURAM 2ND CROSS STREET IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2017-18 NN/2016-17/9484,Roads,Completed,NN-ADYAR,178,998000,LAYING OF CC ROAD AT LAKSHMI PURAM MAIN ROAD CH(0-90) IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2017-18 NN/2016-17/9487,Roads,Completed,NN-ADYAR,178,927000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Jaganadhapuram 1st main road From: Jaganadhapuram 1st cross street To Rajalakshmi Nagar 3rd main road in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2016-17 NN/2016-17/9520,Roads,Completed,NN-ADYAR,178,999000,LAYING OF CC ROAD AT ORANDI AMMAN KOIL 1ST AND 2ND LANE IN DN-178 U-39 Z-13,Own Sources,13,2016-17,2018-19 NN/2016-17/9614,Roads,Completed,NN-ADYAR,178,964000,"Laying The Bituminous Road With BCCMP 30mm thick by Paver Finisher at Jaganadhapuram 1st cross street in Dn-178, Unit-39, Zone- XIII.",Own Sources,13,2016-17,2017-18 BR/2016-17/17605,Roads,Completed,BR-Bus Route Roads,179,1710000,"Attending temporary restoration of damaged roads due to Vardha Cyclone in North East Monsoon 2016 at CSIR Road,Five Furlong Road,Taluk Office Road in Div-171,174,180 Zone -13",Grants,13,2016-17,2017-18 L/2016-17/16766,Electrical,Completed,L-Electrical,179,891000,"Provision of 21nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at Balakrishna Nagar in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/16774,Electrical,Completed,L-Electrical,179,839000,"Provision of 21nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at VGP Selva Nagar Extn. 2nd and 3rd main road and bethal avenue 3rd street in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/16777,Electrical,Completed,L-Electrical,179,891000,"Provision of 20nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at Bhuvaneswari Nagar 2nd main road and Karnan street in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/16784,Electrical,Completed,L-Electrical,179,929000,"Provision of 21nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at Bhuvaneswari Nagar 2nd, 3rd main Road and 3rd cross street in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/16806,Electrical,Completed,L-Electrical,179,962000,"Provision of 24nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at Bhuvaneswari Nagar 3rd main Road in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/16812,Electrical,Completed,L-Electrical,179,815000,"Provision of 20nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at kambar street extn., kamarajar street, Pilliar koil street and chellappa street in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/16825,Electrical,Completed,L-Electrical,179,876000,"Provision of 20nos of 6mtr G.I lamp post with single st. bracket with 40/50w LED fittings c.set at VGP Selva Nagar Extn. 1st and 3rd main road in Velachery Div-179, Zone-XIII.",Own Sources,13,2016-17,2017-18 L/2016-17/18054,Electrical,Completed,L-Electrical,179,191000,"REPLACEMENT OF ACCESSORIES AND MAINTENANCE WORK FOR THE 20 MTR HIGH MAST AT VIJAYA NAGARA HIGH MAST (Junction of Bus stand), VELACHERY IN DIVISION-179, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/11367,Buildings,Completed,NN-ADYAR,179,999000,"Construction of Modern Stainless Steel Bus Shelter at Velachery - Tambaram Main Road (Opp. to Vijaya Nagar Bus Terminus, Eastern Side) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2016-17 NN/2016-17/11369,Buildings,Completed,NN-ADYAR,179,999000,"Construction of Modern Stainless Steel Bus Shelter at Tansi Nagar (Southern Side) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/11370,Buildings,Completed,NN-ADYAR,179,999000,"Construction of Modern Stainless Steel Bus Shelter at Tansi Nagar (Northern Side) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/11439,Roads,Completed,NN-ADYAR,179,410000,Attending temporary restoration of damaged roads at Tansi Nagar 10th Street due to North East Monsoon 2015 in Division -179 Unit - 39 Zone -13,Own Sources,13,2016-17,2016-17 NN/2016-17/11440,Roads,Completed,NN-ADYAR,179,515000,Attending temporary restoration of damaged roads at Bhuvaneswari Nagar 1st Main Road due to North East Monsoon 2015 in Division -179 Unit - 39 Zone -13,Own Sources,13,2016-17,2016-17 NN/2016-17/16859,Parks,Completed,NN-ADYAR,179,556000,"GREENERY IMPROVEMENT TREE SAPLING PLANTATION WORK AT VARIOUS PLACES IN DIV-178,179 AND-180, UNIT -39,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16987,Buildings,Completed,NN-ADYAR,179,243000,"REPAIR WORKS TO DAMAGED AMMA UNAVAGAM DUE TO VARDAH CYCLONE AT NEW COLONY MAIN ROAD IN DIVISION - 179, ZONE - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/16989,Parks,Completed,NN-ADYAR,179,149000,"REPAIR WORKS TO DAMAGED THIRUVALLUVAR PARK DUE TO VARDAH CYCLONE AT GANDHI ROAD IN DIVISION - 179, ZONE - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/16995,Parks,Completed,NN-ADYAR,179,146000,"REPAIR WORKS TO DAMAGED BHARATHIAR PARK DUE TO VARDAH CYCLONE AT VELACHERY MAIN ROAD IN DIVISION - 179, ZONE - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/16997,Playfields,Completed,NN-ADYAR,179,97000,"REPAIR WORKS TO DAMAGED CHILDRENS PLAYGROUND DUE TO VARDAH CYCLONE AT SEETHAPATHY NAGAR III CROSS STREET IN DIVISION - 179, ZONE - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/16998,Playfields,Completed,NN-ADYAR,179,62000,"REPAIR WORKS TO DAMAGED CHILDRENS PLAYGROUND DUE TO VARDAH CYCLONE AT VELACHERY MAIN ROAD INFRONT OF SUTHERNLAND IN DIVISION - 179, ZONE - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/16999,Roads,Completed,NN-ADYAR,179,130000,"REPAIRS TO DAMAGED STREET NAME BOARDS DUE TO VARDAH CYCLONE AT VARIOUS STREETS IN DIVISION - 179, ZONE - XIII",Own Sources,13,2016-17,2017-18 NN/2016-17/17449,Buildings,Completed,NN-ADYAR,179,1126000,"Proposed Construction of Side Drain in size of 600 X 750 mm along Sastri Street (from Junction of PIllayar Koil Street to Mahatma Gandhi Street ) Velachery in Division -179, Unit-39, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/17490,Parks,Completed,NN-ADYAR,179,994000,"GREENERY IMPROVEMENT OF PARKS IN DIV-178,179 AND 180 ,UNIT-39,ZONE-13.",Loans,13,2016-17,2017-18 NN/2016-17/1876,Roads,Completed,NN-ADYAR,179,242000,"Raising of road with WMM (partly - Water Stagnation Area) at Ramagiri Nagar 1st & 2nd cross street and 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2016-17 NN/2016-17/1879,Roads,Completed,NN-ADYAR,179,158000,"Raising of road with WMM at Dhandeeswaram Nagar 7th Avenue West in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2016-17 NN/2016-17/1881,Parks,Completed,NN-ADYAR,179,240000,"Maintenance of Park for 6 months at V.G.P. Selva Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/19331,Footpath,Completed,NN-ADYAR,179,158000,"REPAIR WORKS TO DAMAGED FOOTPATH DUE TO VARDAH CYCLONE AT RANI STREET IN DIVISION-179, UNIT-39, ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/19333,Footpath,Completed,NN-ADYAR,179,117000,"REPAIR WORKS TO DAMAGED FOOTPATH DUE TO VARDAH CYCLONE AT VGP AVENUE IN DIVISION-179, UNIT-39, ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/19335,Footpath,Completed,NN-ADYAR,179,64000,"REPAIR WORKS TO DAMAGED FOOTPATH DUE TO VARDAH CYCLONE AT GANDHI ROAD IN DIVISION-179, UNIT-39, ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/19336,Footpath,Completed,NN-ADYAR,179,90000,"REPAIR WORKS TO DAMAGED FOOTPATH DUE TO VARDAH CYCLONE AT DHANDEESWARAM NAGAR 3RD MAIN ROAD IN DIVISION-179, UNIT-39, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/2077,Buildings,Completed,NN-ADYAR,179,275000,"Out Sourcing Scavenging work for Toilet Cleaning the Chennai Primary School at Udhayam Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/6855,Roads,Completed,NN-ADYAR,179,242000,"Raising of road with WMM at Karnan Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/6856,Roads,Completed,NN-ADYAR,179,290000,"Raising of road with WMM at V.G.P. Selva Nagar 2nd Main Road (Jn. of Bethel Avenue Main Road to Jn. of V.G.P. Selva Nagar 3rd Main Road) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/7018,Road Cut,Completed,NN-ADYAR,179,539000,"Restoration of Road Cut made by CMWSSB at V.G.P. Selva Naagr Extn., 1st Main Road in Dn 179, Unit 39, Zone 13.",Deposit Works,13,2016-17,2019-20 NN/2016-17/7019,Road Cut,Completed,NN-ADYAR,179,413000,"Restoration of Road Cut made by CMWSSB at V.G.P. Selva Naagr 4th Main Road in Dn 179, Unit 39, Zone 13.",Deposit Works,13,2016-17,2019-20 NN/2016-17/7020,Road Cut,Completed,NN-ADYAR,179,257000,"Restoration of Road Cut made by CMWSSB at Muthukrishnan Street in Dn 179, Unit 39, Zone 13.",Deposit Works,13,2016-17,2019-20 NN/2016-17/7024,Storm Water Drain,Completed,NN-ADYAR,179,165000,"Desilting of Kallukuttai lake at Bharani Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2020-21 NN/2016-17/7025,Storm Water Drain,Completed,NN-ADYAR,179,667000,"Desilting of 6 Vent Culvert (Disposal Point) in Velachery MRTS Railway Bridge, Vealchery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/7072,Roads,Completed,NN-ADYAR,179,998000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at various streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/7073,Storm Water Drain,Completed,NN-ADYAR,179,999000,"Desilting of S.W.D. at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2020-21 NN/2016-17/7074,Storm Water Drain,Completed,NN-ADYAR,179,998000,"Desilting of S.W.D. at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/8943,Buildings,Completed,NN-ADYAR,179,499000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT UDHAYAM NAGAR IN DN-179,UNIT-39,ZONE-13.",Own Sources,13,2016-17,2019-20 NN/2016-17/8945,Buildings,Completed,NN-ADYAR,179,790000,"Proposed Construction of Compound Wall And Gate and Gate pillar Of AMMA UNAVAGAM under the Velachery - Tambaram Flyover Bridge, Opp. to Velachery MRTS Railway Station at Velachery Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/8946,Buildings,Completed,NN-ADYAR,179,732000,"Additional Requirements to AMMA UNAVAGAM under the Velachery - Tambaram Flyover Bridge, Opp. to Velachery MRTS Railway Station at Velachery Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/9442,Roads,Completed,NN-ADYAR,179,772000,"Formation of road with B.T. Course by using Paver Finisher at Bhuvaneswari Nagar 2nd Main Road Extn., (From Jn. of Plot No.15 to IRR Road) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9447,Playfields,Completed,NN-ADYAR,179,998000,"Improvements to Children's Play Ground at Spic Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/9499,Storm Water Drain,Completed,NN-ADYAR,179,950000,"Desilting of Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2020-21 NN/2016-17/9506,Roads,Completed,NN-ADYAR,179,998000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Park Avenue 1st, 2nd, 3rd Street, Seshadripuram 1st Main Road, Vanchinathan Street, Udhayam Nagar1st, 2nd Main Road, V.O.C. Street, Sachidanandam Nagar, V.G.P. Selva Nagar Extn., 1st, 2nd, 3rd, 4th & 5th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9508,Roads,Completed,NN-ADYAR,179,988000,"Desilting of Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9512,Storm Water Drain,Completed,NN-ADYAR,179,973000,"Desilting of Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9537,Road Cut,Completed,NN-ADYAR,179,260000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT RAMAGIRI NAGAR IN DN-179,UNIT-39,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/9538,Road Cut,Completed,NN-ADYAR,179,374000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SESHADRIPURAM MAIN ROAD IN DN-179,UNIT-39,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9540,Road Cut,Completed,NN-ADYAR,179,120000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SESHADRIPURAM 1st CROSS STREETIN DN-179,UNIT-39,ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/9630,Playfields,Completed,NN-ADYAR,179,345000,"Providing and Fixing Play Apparatus to Children's Play Ground at Spic Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2016-17,2018-19 BR/2016-17/0160,Roads,Completed,BR-Bus Route Roads,180,1755000,"Restoration of Road Cut at West Avenue Road by TNEB in Div 180, Zone - 13",Deposit Works,13,2016-17,2017-18 BR/2016-17/6594,Road Cut,Completed,BR-Bus Route Roads,180,112000,Road Cut Restoration at Junction of West Avenue and L.B. Road by TNEB in Zone 13,Deposit Works,13,2016-17,2017-18 D/2016-17/13849,Storm Water Drain,Completed,D-Storm Water Drains,180,540000,"Removing of existing Drain and casting and erection of new drain of size 1200mm x 1200mm and laying 450mm Dia. hume pipe NP3 at the junction of CSIR road and vilaiyattu vinayagar koil street in Division 180,Zone 13.",Own Sources,13,2016-17,2017-18 L/2016-17/10987,Electrical,Completed,L-Electrical,180,958000,"PROVISION OF 14 NOS OF 6 MTR G.I LAMP POST WITH DOUBLE ARCH BRACKET WITH 90-120W LED FITTING AT AMMA VAARA SANTHAI (REACH-1) AT OMR, THIRUVANMIYUR IN DIV-180, ZONE-XIII",Own Sources,13,2016-17,2016-17 L/2016-17/11796,Electrical,Completed,L-Electrical,180,999000,"PROVISION OF 12 NOS OF 6 MTR G.I LAMP POST WITH SINGLE ARCH BRACKET WITH 90-120W LED FITTINGS AT AMMA VAARA SANTHAI (REACH-2) AT THIRUVANMIYUR IN DIV-180, ZONE-XIII",Own Sources,13,2016-17,2016-17 L/2016-17/11800,Electrical,Completed,L-Electrical,180,915000,"PROVISION OF 10 NOS OF 6 MTR G.I LAMP POST WITH SINGLE ARCH BRACKET AND 6 NOS 6 MTR LAMP POST WITH DOUBLE ARCH BRACKET WITH 90-120W LED FITTINGS AT AMMA VAARASANTHAI (REACH-3) AT THIRUVANMIYUR IN DIV-180, ZONE-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/10926,Roads,Completed,NN-ADYAR,180,963000,"Strengthening of Amma Vara Sandhai area with GSB from chainage 0-150 at Taramani Rajiv gandhi salai in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11034,Roads,Completed,NN-ADYAR,180,844000,"Relaying of road with B.T. Course by using Paver Finisher at Kanagam - Nehru Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/11035,Roads,Completed,NN-ADYAR,180,2616000,"Relaying of road with B.T. Course by using Paver Finisher at Kanagam - Nethaji Street, Ambekar Street, Gandhi Street, Lal Bagadur Sastri Street & Bajanai Koil Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/11526,Storm Water Drain,Completed,NN-ADYAR,180,996000,"Improvements and Repair works to S.W.D. at Peeliamman Koil Street (Ch 0-175m) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/11548,Roads,Completed,NN-ADYAR,180,963000,"Strengthening of Amma Vara Sandhai area with GSB from chainage 150 - 300 at Taramani Rajiv gandhi salai in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11549,Buildings,Completed,NN-ADYAR,180,2158000,"Providing Galvanized Metal Sheet for barricading AMMA VAARA SANTHAI at Rajiv Gandhi Salai in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11556,Storm Water Drain,Completed,NN-ADYAR,180,506000,"Raising and Providing Cover Slap for Side Drain at 12West Street & 4th West Street West Kamarajar Nagar (Part) in 180, Unit-39, Zone-13",Own Sources,13,2016-17,2019-20 NN/2016-17/11557,Storm Water Drain,Completed,NN-ADYAR,180,612000,"Raising and Providing Cover Slap for Side Drain at 10West Street West Kamarajar Nagar in 180, Unit-39, Zone-13",Own Sources,13,2016-17,2019-20 NN/2016-17/11558,Storm Water Drain,Completed,NN-ADYAR,180,779000,"Construction of New Side Drain at Kanagam Burrial Ground to Ramanujam I.T Park in Dn180, Unit-39, Zone13",Own Sources,13,2016-17,2019-20 NN/2016-17/11574,Storm Water Drain,Completed,NN-ADYAR,180,999000,"Improvements and Repair works to S.W.D. at Peeliamman Koil Street (Ch 175m-350m) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/11648,Buildings,Completed,NN-ADYAR,180,963000,"Strengthening of Amma Vara Sandhai area with GSB from chainage 300-450 at Taramani Rajiv gandhi salai in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11651,Storm Water Drain,Completed,NN-ADYAR,180,297000,"Dismantling and Re-Construction of Storm Water Drain road crossing at Kamarajar Nagar East 4th Main Road Jn. of L.B. Road, Thiruvanmiyur in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2020-21 NN/2016-17/11714,Storm Water Drain,Completed,NN-ADYAR,180,980000,"Providing FRC Doors and Silt Catch Pit at Thiruvalluvar Salai, Kanagam Periyar Nagar Main Road & Erikarai Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/11833,Road Cut,Completed,NN-ADYAR,180,883000,"Restoration of road cut made by TNEB at V.V. Koil Street (Ch 495m - 705m), Taramani in Dn 180, Unit 39, Zone 13.",Deposit Works,13,2016-17,2019-20 NN/2016-17/12207,Roads,Completed,NN-ADYAR,180,551000,"Attending temporary restoration of damaged road at X West Street due to flood in North East Monsoon 2015 in Division-180,Unit-39,Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12276,Roads,Completed,NN-ADYAR,180,695000,"Attending temporary restoration of damaged road at L.B.Road 3rd Street due to floods in North East Monsoon 2015 in Division-180,Unit-39,Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12277,Roads,Completed,NN-ADYAR,180,651000,"Attending temporary restoration of damaged road at XI West Street due to flood in North East Monsoon 2015 in Division-180,Unit-39,Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/14703,Buildings,Completed,NN-ADYAR,180,146000,"Repairs and Improvement works to Public Convenience at tharamani Bus Stand and Pammal Nallathampi Street at Tharamani in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14753,Buildings,Completed,NN-ADYAR,180,623000,"Improvements Water Supply & Drainage Arrangements to Chennai Primary School at Perumal Koil Street, Taramani in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14758,Buildings,Completed,NN-ADYAR,180,791000,"Improvements Water Supply & Drainage Arrangements to Chennai Higher Secondary School at Peeliamman Koil Street, Taramani in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16914,Buildings,Completed,NN-ADYAR,180,1073000,"Repair works to Kamarajar Nagar west 2nd street Park ( Damaged by Vardha Cyclone) in Div-180, Unit-39, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16923,Buildings,Completed,NN-ADYAR,180,366000,"Repair works to Kamarajar Nagar west 4th street Park ( Damaged by Vardha Cyclone) in Div-180, Unit-39, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16935,Buildings,Completed,NN-ADYAR,180,199000,"Repair works to Chennai Primary School at Perumal Koil street Tharamani ( Damaged by Vardha Cyclone) in Div-180, Unit-39, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/1818,Parks,Completed,NN-ADYAR,180,117000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 2ND WEST STREET, KAMARAJ NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1823,Parks,Completed,NN-ADYAR,180,57000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 13TH WEST STREET, KAMARAJ NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1825,Parks,Completed,NN-ADYAR,180,120000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 4TH WEST STREET, KAMARAJ NAGAR IN DN 180, UNIT 39, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/18256,Roads,Completed,NN-ADYAR,180,255000,"Poposed laying bt road at V.V.Koil stret, Pillaiyar koil street, Kamarajar Nagar II Main road in div-180, Unit-39, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/19016,Buildings,Completed,NN-ADYAR,180,900000,"Proposed construction of Compound wall, Gas Room & Motor room and other additional works to Amma Unavagam at Gothawari street in Div-180, Unit-39, Zone-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/2078,Buildings,Completed,NN-ADYAR,180,275000,"Out Sourcing Scavenging work for Toilet Cleaning the Chennai Primary School at Tharamani in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/2079,Buildings,Completed,NN-ADYAR,180,366000,"Out Sourcing Scavenging work for Toilet Cleaning the Chennai Higher Secondary School at Tharamani in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/5949,Storm Water Drain,Completed,NN-ADYAR,180,999000,"Desilting of S.W.D., and Providing FRC Manhole Cover at West Avenue, C.S.I.R Road & Taramani 100 feet road (Total Length-4560m) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/5952,Storm Water Drain,Completed,NN-ADYAR,180,998000,"Desilting of S.W.D., Providing FRC Manhole Cover & Siitu Catch Pit at Kalki Krishnamurthy Salai East & West, Kamaraj Nagar 5th Main Road, Ranganathapuram, V.V. Koil Street, Thiruvalluvar Salai, Arangannal Street, Erikarai Street, Taramani Bus Stand (Total Length-3560m) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2020-21 NN/2016-17/6053,Storm Water Drain,Completed,NN-ADYAR,180,997000,"Desilting of S.W.D., Providing FRC Manhole Cover & Situ Catch Pit at Kanagam Periyar Nagar Road, Peeliyamman Koil Street, Perunthalaivar Kamarajar Nagar Road, Kamarajar Nagar West 2nd Main Road, Kamarajar Nagar West 2 to 12 Street, Anna Street Taramani, M.G.R. Road & 100 fet road (Big Size) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/6185,Buildings,Completed,NN-ADYAR,180,990000,"Providing leveling and Filling for Amma Varasandhai at OMR (opp. Fashion Technology) in Div 180, Unit 39, at Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/7225,Buildings,Completed,NN-ADYAR,180,967000,"Providing Retro Reflection stainless steel street name board at Bharathi nagar and Anna nagar(ward councilor fund) in Dn-180, Unit- 39, Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/7226,Buildings,Completed,NN-ADYAR,180,980000,"Providing Retro Reflection stainless steel street name board at Periyar nagar(ward councilor fund) in Dn-180, Unit- 39, Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/9170,Storm Water Drain,Completed,NN-ADYAR,180,772000,"Raising and providing cover slab for side drain at 4th & 7th West Kamaraj Nagar in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9190,Storm Water Drain,Completed,NN-ADYAR,180,197000,"Providing FRC Square Door to side drain at Kamaraj Nagar West 2nd, 3rd, 5th, 6th & 8th to 12th Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2020-21 NN/2016-17/9196,Storm Water Drain,Completed,NN-ADYAR,180,983000,"Construction of New Side Drain at Judges Avenue (from L.B. Road to Ranganathapuram) Ch 0 - 50m in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9224,Storm Water Drain,Completed,NN-ADYAR,180,983000,"Construction of New Side Drain at Judges Avenue (from L.B. Road to Ranganathapuram) Ch 50m - 100m in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9252,Storm Water Drain,Completed,NN-ADYAR,180,983000,"Construction of New Side Drain at Judges Avenue (from L.B. Road to Ranganathapuram) Ch 100m - 150m in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2019-20 NN/2016-17/9637,Buildings,Completed,NN-ADYAR,180,943000,"Providing Garbage Bin Platform at Various Streets (Copy of road list enclosed) in Dn 180, Unit 39, Zone 13.",Own Sources,13,2016-17,2017-18 D/2016-17/8027,Storm Water Drain,Completed,D-Storm Water Drains,181,995000,Repairs and Fixing Manhole Door and Silt CatchPit at Dr. Radhakrishnan Nagar Main Road in Dn181 Zone13,Grants,13,2016-17,2016-17 L/2016-17/16157,Electrical,Completed,L-Electrical,181,191000,"PROVISION OF REPLACEMENT OF ACCESSORIES AND MAINTENANCE WORK FOR THE 20 MTR HIGH MAST AT ASTALAKSHMI KOIL, BESANT NAGAR IN DIVISION-181, ZONE-13",Own Sources,13,2016-17,2017-18 L/2016-17/16189,Electrical,Completed,L-Electrical,181,164000,"PROVISION OF REPLACEMENT OF ACCESSORIES AND MAINTENANCE WORK FOR THE 20 MTR HIGH MAST AT VEMBULIAMMAN KOIL STREET, THIRUVANMIYUR IN DIVISION-181, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/0203,Buildings,Completed,NN-ADYAR,181,720000,IMPROVEMENTS TO ELECTRONICS TOILETS AT THIRUVANMIYUR BUS TERMINUS IN DIVISION 181 UNIT 38 ZONE 13.,Own Sources,13,2016-17,2017-18 NN/2016-17/1136,Buildings,Completed,NN-ADYAR,181,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.P.S AT THIRUVANMIYUR KUPPAM BEACH ROAD IN DN-181, UNIT-38, ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1137,Buildings,Completed,NN-ADYAR,181,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.M.S AT (GANDHI GRAMAM) LAKSHMI PURAM IN DN-181, UNIT-38, ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1138,Buildings,Completed,NN-ADYAR,181,178000,"OUT SOURCING OF PRIVATE CONERVANCY IN C.P.S AT OODAIKUPPAM IN DN-181, UNIT-38, ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/11934,Buildings,Completed,NN-ADYAR,181,972000,"Providing retro reflection stainless steel street name board At Marudeesvarar nagar and Lakshmi puram (ward councilor fund) in dn-181, Unit - 38 ,zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/12048,Roads,Completed,NN-ADYAR,181,996000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Anna street, Karunanithi Road, Rukmani road, Beach Road, Tiger Varadhachari Salai and TM Maistry road in Dn-181, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/12058,Roads,Completed,NN-ADYAR,181,998000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Kalashekta Road, Kalashektra colony, Thiumurugan 2nd Street, Navabharath Colony 2nd Street and Sri Ram nagar in Dn-181, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/15679,Electrical,Completed,NN-ADYAR,181,132500,"PROVISION OF ADDITIONAL AND REWIRING AT PUBLIC CONVENIENCE AT ODAIKUPPAM, BESANT NAGAR IN DIV-181, ZONE-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/15834,Buildings,Completed,NN-ADYAR,181,157000,"Providing Barricading arrangements at Astalakshmi koil Beach and New Beach at Thiruvanmiyur for Pongal festival-2017 in Division-181 and 182 Unit-38, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16856,Parks,Completed,NN-ADYAR,181,554000,"GREENERY IMPROVEMENT TREE SAPLING PLANTATION WORK AT VARIOUS PLACES IN DIV-176,181 AND-182, UNIT 38,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/16912,Parks,Completed,NN-ADYAR,181,737000,"IMPROVEMENTS AND REPAIR WORKS TO PARKS AT CGE COLONY, YAMUNA ST, MGR ST, GANGAI ST, TIGER VARADHACHARI ST.AFFECTED BY VARTHA STORM IN DIVISION 181 UNIT 38",Own Sources,13,2016-17,2017-18 NN/2016-17/16918,Buildings,Completed,NN-ADYAR,181,769000,"URGENT REPAIR WORKS TO CORPORTION SCHOOLS AT ODDIKUPPAM PRIMARY SCHOOL, GANDHI GRAMAM SCHOOL AND THIRUVANMIYUR KUPPAM BEACH SCHOOL EFFECTED BY VARATHA STORM IN DIVISION 181 UNIT 38.",Own Sources,13,2016-17,2017-18 NN/2016-17/16920,Buildings,Completed,NN-ADYAR,181,738000,"IMPROVEMENTS & REPAIR WORKS TO FOOTPATHS AT MGR ROAD, RUKMANI STREET NEDUNCHELIAN STREET, BEACH ROAD & COASTAL ROAD AFFECTED BY VARTHA STROM IN DIVISION 181 UNIT38, ZONE 13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16925,Buildings,Completed,NN-ADYAR,181,523000,"REPAIR WORKS TO BURIAL GROUND AT RAJA SRINIVASAPURAM AFFECTED BY VARATHA STORM IN DIVISION 181 UNIT-38, ZONE-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/16928,Buildings,Completed,NN-ADYAR,181,720000,"REPAIR WORKS TO NNMP SHEDS AT ODDIKUPPAM, MARUDESWARAR NAGAR AND DR. MUTHULAKSHMI STREET IN DIV 181 UNIT 38 EFFECTED BY VARTHA STORM",Own Sources,13,2016-17,2017-18 NN/2016-17/16947,Roads,Completed,NN-ADYAR,181,814000,"REPAIR WORKS TOFOOTPATHS AT KAMARAJAR NAGAR 3RD , 4TH CROSS STREET, VALAMIKI NAGAR 1ST, 2ND 3 RD 4TH AND JOURNALIST COLONY EFFECTED VARATHA STORM IN DIVISION 182 UNIT 38",Own Sources,13,2016-17,2017-18 NN/2016-17/16949,Buildings,Completed,NN-ADYAR,181,560000,URGENT REPAIRS TO AMMA UNAVAGAM EFFECTED BY VARATHA STORM AT CGE C0L0NY AND VALMIKI STREET IN DIVISION 181 UNIT 38 ZONE 13,Own Sources,13,2016-17,2017-18 NN/2016-17/17489,Parks,Completed,NN-ADYAR,181,980000,"GREENERY IMPROVEMENT OF PARKS IN DIV-176,181 AND 182 ,UNIT-38,ZONE-13.",Loans,13,2016-17,2017-18 NN/2016-17/3191,Roads,Completed,NN-ADYAR,181,999000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at Balu street&kalakshetra avenue I street at Div-181,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3200,Roads,Completed,NN-ADYAR,181,850000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at Thirumurugan street Reach-1 at Div-181,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/4961,Buildings,Completed,NN-ADYAR,181,980000,"IMPROVEMENTS AND REPAIR WORKS TO PUBLIC CVONVENIENCE AT JAYARAMAN STREET, THIDEER NAGAR AND ODAIMA NAGAR IN DIVISION 181, UNIT 38.",Own Sources,13,2016-17,2018-19 NN/2016-17/4962,Roads,Completed,NN-ADYAR,181,805000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Anna street, Pillaiyar koil street,Valmigi street, Kalakshetra avenue 1st street, Coastal road, TM Mestiry street and Cholapuram in Dn-181, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/5719,Storm Water Drain,Completed,NN-ADYAR,181,980000,REPAIR WORKS TO STORM WATER DRAIN AT MARUDESWARAR NAGAR MAIN ROAD IN DIVISION 181 UNIT 38 ZONE 13.,Own Sources,13,2016-17,2018-19 NN/2016-17/5891,Roads,Completed,NN-ADYAR,181,993000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Kamaraj Salai, Jayaram Street, Vembuliamman Koil Street, Kuppam Beach Road, TM Mestiry Extn in Front of KGS Flats and RK Nagar 1st Cross Street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/6745,Roads,Completed,NN-ADYAR,181,953000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Rukmani road, Neduncheziyan street and MG Ramachandran road in Dn-181, Unit-38, Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/6879,Buildings,Completed,NN-ADYAR,181,984000,"Improvements to park at M.G.R. Road, Mahalakshmi Avenue(Ward Councilor Fund) in Dn-181, Unit-38, Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/7240,Buildings,Completed,NN-ADYAR,181,970000,IMPROVEMENTS AND REPAIR WORKS TO PUBLIC CONVENIENCE NEAR ASHTALAKSHMI TEMPLE AND LAKSHMIPURAM,Own Sources,13,2016-17,2018-19 NN/2016-17/7241,Storm Water Drain,Completed,NN-ADYAR,181,998000,"REAPIRS TO STORM WATER DRAINS AT MARUNDEESWARAR NAGAR MAIN ROAD, SIVAKAMIPURAM 1ST AND 2ND STREET, MALAVIYA AVENUE 1ST AND 2ND STREET, RADHAKRISHNA NAGAR 3RD CROSS STREET, SRIRAM NAGAR MAIN ROAD IN DIVISION 181, UNIT 38",Own Sources,13,2016-17,2018-19 NN/2016-17/7242,Buildings,Completed,NN-ADYAR,181,996000,"REPAIRS WORKS TO STORM WATER DRAIN AT KAMARAJ NAGAR 1ST 2ND AND 3RD STREET, SIVASUNDER AVENUE 1ST AND 2ND STREET, VALMIKI STREET, KAMARAJAR SALAI IN DIVISION 181 UNIT 38",Own Sources,13,2016-17,2018-19 NN/2016-17/7243,Roads,Completed,NN-ADYAR,181,1554000,IMPROVEMENT AND RELAING BT ROAD AT R.K NAGAR III CROSS STREET IN DIVISION 181 UNIT 38 ZONE 13.,Own Sources,13,2016-17,2017-18 NN/2016-17/7962,Roads,Completed,NN-ADYAR,181,990000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Kamaraj Salai(Dr.Ambedkar st.), T M Maistry Street, Cholapuram, Kuppam Beach road, Cholapuram and Balu Street in Dn-181, Unit-38, Zone-13",Own Sources,13,2016-17,2016-17 L/2016-17/16164,Electrical,Completed,L-Electrical,182,191000,"REPLACEMENT OF ACCESSORIES AND MAINTENANCE WORK FOR THE 20 MTR HIGH MAST AT NEW BEACH ROAD, THIRUVANMIYUR IN DIVISION-182, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/0562,Buildings,Completed,NN-ADYAR,182,365000,"Improvements to Election training center in CHSS at Bharathidasan street in Dn-182, Unit-48, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/11940,Storm Water Drain,Completed,NN-ADYAR,182,662000,"Providing Water and Drainage supply arrangements to Amma Unavagam at Thiruveedhiamman Koil Street in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/12202,Buildings,Completed,NN-ADYAR,182,999000,"Desilting Storm Water Drain at Kannappa nagar main road, 2nd street and Extension, South Avenue road, Kamaraj nagar 3rd,5th,6th streets in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/12203,Buildings,Completed,NN-ADYAR,182,999000,"Repairs to Storm Water Drain at Avvai nagar main road, Dharmambal street, Aibea nagar, Rajaji nagar Main road, 1st and 2nd streets, Pillaiyarkoil streets in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/12910,Electrical,Completed,NN-ADYAR,182,341000,"PROVISION OF ELECTRICAL WIRING AT NEWLY CONSTRUCTED AMMA CANTEEN BUILDING AT THIRUVEEDIAMMAN KOIL STREET, THIRUVANMIYUR IN DIV-182, ZONE-XIII",Own Sources,13,2016-17,2019-20 NN/2016-17/14873,Buildings,Completed,NN-ADYAR,182,987000,"Repair and Improvements to CHSS (A-Block and B-Block) at Bharathidasan Street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14880,Buildings,Completed,NN-ADYAR,182,327000,"Repair and Improvements to CHSS (C-Block and B-Block) at Bharathidasan Street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2016-17,2017-18 NN/2016-17/14939,Buildings,Completed,NN-ADYAR,182,317000,"Improvements to PC at ECR Bus stand Thiruvanmiyur in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/1669,Roads,Completed,NN-ADYAR,182,889000,"Relaying the road with bccmp 40mm thick using paver finisher at Avai nager main road REACH-1 in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/1672,Roads,Completed,NN-ADYAR,182,889000,"Relaying the road with bccmp 40mm thick using paver finisher at Avai nager main road REACH-2 in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/1673,Parks,Completed,NN-ADYAR,182,86000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 43RD CROSS STREET IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1674,Parks,Completed,NN-ADYAR,182,111000,"MAINTENANCE OF PARK FOR 6 MONTHS AT JOURNALIST COLONY IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1675,Parks,Completed,NN-ADYAR,182,140000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 1ST AVENUE IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1676,Roads,Completed,NN-ADYAR,182,889000,"Relaying the road with bccmp 40mm thick using paver finisher at Avai nager main road REACH-3 in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/1678,Roads,Completed,NN-ADYAR,182,889000,"Relaying the road with bccmp 40mm thick using paver finisher at Avai nager main road REACH-4 in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/16941,Buildings,Completed,NN-ADYAR,182,750000,"IMPROVEMENTS TO PARKS AND PLAYGROUND AT THIRUVALLUVAR NAGAR 1ST AVENUE, 2ND AVENUE, 43RD CROSS STREET, 11TH CROSS STREET, AIBEA NAGAR AFFECTED BY VARDHA STORM IN DIVISION 182 UNIT 38",Own Sources,13,2016-17,2017-18 NN/2016-17/16945,Buildings,Completed,NN-ADYAR,182,706000,URGENT REPAIR WORKS TO VARATHA STORM EFFECTED CORPORTION HIGHER SECONDARY SCHOOL AT PURATCHI KAVIZHAR BHARATHIDASAN STREET IN DIVISION 182 UNIT 38,Own Sources,13,2016-17,2017-18 NN/2016-17/16948,Buildings,Completed,NN-ADYAR,182,618000,URGENT REPAIR WORKS TO VARATHA STORM EFFECTED AMMA UNAVAGAN AT AVVAI NAGAR AND THIRUVEETHI AMMAN KOIL STREET IN DIVISION 182 UNIT 38,Own Sources,13,2016-17,2017-18 NN/2016-17/16988,Buildings,Completed,NN-ADYAR,182,549000,REPAIRS TO NNMP SHED AT AVVAI NAGAR AND INSIDE CORPORTION SCHOOL AT BHARATHIDASAN STREET IN DIVISION 182 UNIT 38,Own Sources,13,2016-17,2017-18 NN/2016-17/1701,Parks,Completed,NN-ADYAR,182,88000,"MAINTENANCE OF PARK FOR 6 MONTHS AT 69TH CROSS STREET, VALMIGI NAGAR IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1703,Parks,Completed,NN-ADYAR,182,128000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 2ND AVENUE IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1709,Parks,Completed,NN-ADYAR,182,102000,"MAINTENANCE OF PARK FOR 6 MONTHS AT THIRUVALLUVAR NAGAR 7TH CROSS STREET IN DN 182, UNIT 38, ZONE 13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1719,Parks,Completed,NN-ADYAR,182,51000,"MAINTENANCE OF PARK FOR 6 MONTHS AT AIBEA NAGAR IN 182, UNIT-38, ZONE-13.",Own Sources,13,2016-17,2018-19 NN/2016-17/1953,Buildings,Completed,NN-ADYAR,182,985000,"OUT SOURCING OF PRIVATE CONSERVANCY IN C.H..S.S AT BHARADHIDASAN STREET THIRUVANMIYUR IN DN-182,UNIT-38,ZONE-13",Own Sources,13,2016-17,2018-19 NN/2016-17/2067,Buildings,Completed,NN-ADYAR,182,393000,"Improvements to Amma Unavagam at Avvai Nagar in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/2853,Buildings,Completed,NN-ADYAR,182,980000,"Desilting of 'B' Canal Vegetation of hyacinth materials, floating materials removing work from S R P Tools to kottivakkam IN DIV 182, UNIT 38, AT ZONE XIII",Own Sources,13,2016-17,2018-19 NN/2016-17/3211,Roads,Completed,NN-ADYAR,182,999000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at Dharmambal street at Div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3223,Roads,Completed,NN-ADYAR,182,985000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at Anbea Nagar 3rd cross street&East kamaraj nagar VIII street at Div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3229,Roads,Completed,NN-ADYAR,182,813000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at East mada street Reach-1 at Div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3235,Roads,Completed,NN-ADYAR,182,813000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at East mada street Reach-2 at Div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3269,Roads,Completed,NN-ADYAR,182,999000,"Relaying the road with BC 40mm thick by using paver finisher at Thiruvalluvar nagar 58th Street in Div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3271,Roads,Completed,NN-ADYAR,182,889000,"Relaying the road with BC 40mm thick by using paver finisher at 1st Sea ward road reach-1 in Div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3272,Roads,Completed,NN-ADYAR,182,622000,"Relaying the road with BC 40mm thick by using paver finisher at 1st Sea ward road reach-2 in Div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3290,Roads,Completed,NN-ADYAR,182,934000,"Relaying the road with BC 40mm thick by using paver finisher at 4th sea ward REACH-1 road in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3291,Roads,Completed,NN-ADYAR,182,934000,"Relaying the road with BC 40mm thick by using paver finisher at 4th sea ward REACH-2 road in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3292,Roads,Completed,NN-ADYAR,182,664000,"Relaying the road with BC 40mm thick by using paver finisher at 4th sea ward REACH-3 road in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3294,Roads,Completed,NN-ADYAR,182,664000,"Relaying the road with BC 40mm thick by using paver finisher at bagathsingh salai reach-1 road in div-182,Unit-38,Zone-XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/3452,Storm Water Drain,Completed,NN-ADYAR,182,982000,"PROVIDING RAIN WATER HARVESTING AND CHUTE PIPE CONNECTION AT NEW BEACH ROAD FROM THIRUVALLUVAR NAGAR 2ND AVENUE TO DOOR NO:19/22 IN DN-182, UNIT-38, ZONE-13",Own Sources,13,2016-17,2016-17 NN/2016-17/3746,Storm Water Drain,Completed,NN-ADYAR,182,877800,"PROVIDING RAIN WATER HARVESTING AND CHUTE PIPE CONNECTION AT NEW BEACH ROAD FROM DOOR NO:19/22 TO JN OF SEA WORLD ROAD(POLICE BOOTH) IN DN-182, UNIT-38, ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/6605,Buildings,Completed,NN-ADYAR,182,133000,"Providing water supply arrangements to Bio-Toilet at Thiruvalluvar nagar beach and Avvai nagar in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/6826,Buildings,Completed,NN-ADYAR,182,418000,"Providing cupboard arrangements to CHSS at Bharathidasn street in Dn-182, Unit-38,Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7100,Buildings,Completed,NN-ADYAR,182,961000,"PROVIDING RETRO REFLECTION STAINLESS STEEL STREET NAME BOARD AT THIRUVALLUVAR NAGAR (Ward Councilor Fund) IN DN-182, UNIT- 38 ,ZONE-13",Own Sources,13,2016-17,2016-17 NN/2016-17/7101,Buildings,Completed,NN-ADYAR,182,936000,"Providing retro reflection stainless steel street name board at kamaraj nagar, Avvai nagar and Ibia nagar(ward councilor fund) in Dn-182, Unit- 38 ,Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/7104,Buildings,Completed,NN-ADYAR,182,153000,"Providing Drainage and Stair case Shed arrangement to Amma Unavagam at Valmigi Street in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7152,Roads,Completed,NN-ADYAR,182,908000,"Repairs to footpath at New Beach Road from Thiruvalluvar nagar 2nd Avenue to jn of Sea world road in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2016-17 NN/2016-17/7157,Roads,Completed,NN-ADYAR,182,157000,"Attending temporary restoration of damaged road at vasudev nagar extn lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7258,Roads,Completed,NN-ADYAR,182,360000,"Attending temporary restoration of damaged road at thiruvalluvar nagar beach road II lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7260,Roads,Completed,NN-ADYAR,182,360000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar beach road I lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7261,Roads,Completed,NN-ADYAR,182,1471000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar beach road due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7262,Roads,Completed,NN-ADYAR,182,278000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar I cross street road due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7264,Roads,Completed,NN-ADYAR,182,706000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar I main road road due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7265,Roads,Completed,NN-ADYAR,182,1079000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar III avenue road due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7267,Roads,Completed,NN-ADYAR,182,1308000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar I avenue due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7270,Roads,Completed,NN-ADYAR,182,1570000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar II avenue due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7273,Roads,Completed,NN-ADYAR,182,425000,"Attending temporary restoration of damaged road at Kannappa nagar TNHB road due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7275,Roads,Completed,NN-ADYAR,182,183000,"Attending temporary restoration of damaged road at Nethaji nagar north street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7278,Roads,Completed,NN-ADYAR,182,183000,"Attending temporary restoration of damaged road at Nethaji nagar south street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7280,Roads,Completed,NN-ADYAR,182,392000,"Attending temporary restoration of damaged road at Nethaji nagar Main road due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7282,Roads,Completed,NN-ADYAR,182,419000,"Attending temporary restoration of damaged road at Mettu street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7300,Roads,Completed,NN-ADYAR,182,340000,"Attending temporary restoration of damaged road at Lalitha garden due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7301,Roads,Completed,NN-ADYAR,182,327000,"Attending temporary restoration of damaged road at Rajagopalan street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7303,Roads,Completed,NN-ADYAR,182,288000,"Attending temporary restoration of damaged road at Thiruvalluvar nagar VII cross street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7305,Roads,Completed,NN-ADYAR,182,392000,"Attending temporary restoration of damaged road at Srinivasapuram East street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7306,Roads,Completed,NN-ADYAR,182,360000,"Attending temporary restoration of damaged road at Sannathi street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7307,Roads,Completed,NN-ADYAR,182,1177000,"Attending temporary restoration of damaged road at Chitrakulam street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7308,Roads,Completed,NN-ADYAR,182,366000,"Attending temporary restoration of damaged road at Devendra nagar I street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7317,Roads,Completed,NN-ADYAR,182,459000,"Attending temporary restoration of damaged road at Devendra nagar II street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7326,Roads,Completed,NN-ADYAR,182,405000,"Attending temporary restoration of damaged road at Devendra nagar III street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7327,Roads,Completed,NN-ADYAR,182,209000,"Attending temporary restoration of damaged road at Devendra nagar IV street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7328,Roads,Completed,NN-ADYAR,182,209000,"Attending temporary restoration of damaged road at Devendra nagar V street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7334,Roads,Completed,NN-ADYAR,182,157000,"Attending temporary restoration of damaged road at Devendra nagar VI street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7350,Roads,Completed,NN-ADYAR,182,314000,"Attending temporary restoration of damaged road at Devendra nagar VII street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7363,Roads,Completed,NN-ADYAR,182,262000,"Attending temporary restoration of damaged road at Devendra nagar VIII street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7365,Roads,Completed,NN-ADYAR,182,262000,"Attending temporary restoration of damaged road at Devendra nagar IX street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7366,Roads,Completed,NN-ADYAR,182,235000,"Attending temporary restoration of damaged road at Jourtrnalist colony I Street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7381,Buildings,Completed,NN-ADYAR,182,990000,IMPROVEMENTS AND REPAIR WORKS TO PUBLIC CONVEYENCE AT THIRUVEETHI AMMAN KOIL STREET IN DIVISION 182 UNIT 38 ZONE 13,Own Sources,13,2016-17,2018-19 NN/2016-17/7414,Roads,Completed,NN-ADYAR,182,471000,"Attending temporary restoration of damaged road at Jourtrnalist colony II Street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7415,Roads,Completed,NN-ADYAR,182,196000,"Attending temporary restoration of damaged road at Jourtrnalist colony III Street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7417,Roads,Completed,NN-ADYAR,182,262000,"Attending temporary restoration of damaged road at Jourtrnalist colony IV Street due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7418,Roads,Completed,NN-ADYAR,182,131000,"Attending temporary restoration of damaged road at Jourtrnalist colony I lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7419,Roads,Completed,NN-ADYAR,182,105000,"Attending temporary restoration of damaged road at Jourtrnalist colony II lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7420,Roads,Completed,NN-ADYAR,182,131000,"Attending temporary restoration of damaged road at Jourtrnalist colony III lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7421,Roads,Completed,NN-ADYAR,182,118000,"Attending temporary restoration of damaged road at Jourtrnalist colony IV lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7422,Roads,Completed,NN-ADYAR,182,131000,"Attending temporary restoration of damaged road at Jourtrnalist colony V lane due to floods in North East Monsoon 2015 in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2016-17,2016-17 NN/2016-17/7960,Roads,Completed,NN-ADYAR,182,989000,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Avvai nagar, Kannappa nagar, Kotivakkam Kuppam road and First Sea ward road in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/7961,Buildings,Completed,NN-ADYAR,182,980000,"Providing Retro Reflection Stainless Steel Street Name Board At Thiruvalluvar Nagar, Rathna Street, Gnanapathy Street and Bagath Singh Street (Ward Councilor Fund) IN DN-182, UNIT- 38 ,ZONE-13",Own Sources,13,2016-17,2017-18 NN/2016-17/8084,Buildings,Completed,NN-ADYAR,182,980000,"REPAIRS AND IMPROVEMENTS TO CORPORTION DISPANSARY AT THIRUVEETHI AMMAN KOIL STREET, THIRUVANMIYUR IN DIVISION 181 UNIT38",Own Sources,13,2016-17,2017-18 NN/2016-17/8247,Roads,Completed,NN-ADYAR,182,998200,"Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Journalist Colony, Ganapathy Street, Kamaraj nagar 3rd Main roadm and South avenue in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/9685,Storm Water Drain,Completed,NN-ADYAR,182,990000,"Providing Inspection chamber and Silt-catch pit arrangements at Kannapa nagar,Avvai nagar in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 NN/2016-17/9690,Storm Water Drain,Completed,NN-ADYAR,182,992000,"Providing Inspection chamber and Silt-catch pit arrangements at Kamaraj nagar, Vasudeva nagar and Rajaji nagar in Dn-182, Unit-38, Zone-13",Own Sources,13,2016-17,2017-18 D/2016-17/5965,Storm Water Drain,Completed,D-Storm Water Drains,183,4955000,"Construction of storm water Drain of size 1200x1200mm Along Kaveri Nagar Main road From Kavery nagar Beach 1st Street to Kavery NagarBeach 3rd street in div-183, Zone- XIV.",Own Sources,14,2016-17,2016-17 D/2016-17/6183,Storm Water Drain,Completed,D-Storm Water Drains,183,4955000,"Construction of Storm water Drain of size 1200 X 1200 mm Along Thiruvalluvar Nagar and Kaveri Nagar Main Road from Journalist colony to Kavery nagar Beach 1st Street in Div 183, Zone - XIV.",Own Sources,14,2016-17,2016-17 L/2016-17/13804,Electrical,Completed,L-Electrical,183,194700,"Shifting and raising of 37 nos Pillar boxes and painting of 78 pillars At Various Locations In Div-183,185 and 191, Zone-XIV",Own Sources,14,2016-17,2017-18 L/2016-17/13805,Electrical,Completed,L-Electrical,183,193300,"Provision of 12 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-183, Zone-XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/14512,Buildings,Completed,NP-PERUNGUDI,183,106000,"Repair and maintenance work of 2 nos public Convenience at Kottivakkam kuppam beach south side and north side in Div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/15158,Roads,Completed,NP-PERUNGUDI,183,926000,"ATTENDING PATCH WORK AT THULUKANATHAMMAN KOIL STREET, BAY WATCH BOULE VARD STREET AND CAUVERY BEACH ROAD 5TH CROSS STREET ( BHARATHY AVENUE ) IN DIVISION 183, UNIT 41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/15159,Buildings,Completed,NP-PERUNGUDI,183,711902,"REPAIRS TO TOILET BLOCK AND OTHER IMPROVEMENTS TO DIVISION 183 OFFICE AT ECR ROAD IN DIVISION 183, UNIT 41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/15160,Buildings,Completed,NP-PERUNGUDI,183,152000,"REPAIRS TO TOILET AND OTHER IMPROVEMENTS TO PRIMARY SCHOOL AT KUPPAM MAIN ROAD IN DIVISION 183, UNIT 41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/17297,Roads,Completed,NP-PERUNGUDI,183,465000,"RELAYING OF DAMAGED ROAD AT SWAMINATHAN NAGAR 10TH STREET IN DIVISION 183- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17316,Roads,Completed,NP-PERUNGUDI,183,714000,"RELAYING OF DAMAGED ROAD AT BAYWATCH ROAD IN DIVISION 183- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17320,Roads,Completed,NP-PERUNGUDI,183,933000,"RELAYING OF DAMAGED ROAD AT GANDHI STREET IN DIVISION 183- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17326,Roads,Completed,NP-PERUNGUDI,183,2012000,"RELAYING OF DAMAGED ROAD AT ELANGO NAGAR (NORTH) IN DIVISION 183- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17354,Roads,Completed,NP-PERUNGUDI,183,434000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 2ND CROSS STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17431,Storm Water Drain,Completed,NP-PERUNGUDI,183,191000,"Repair and improvements work for Side Drain at Swaminathan nagar 10th street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17433,Buildings,Completed,NP-PERUNGUDI,183,37000,"repairs and improvement work at amma unavagam at east cost road and tharamani in division-183,unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17434,Storm Water Drain,Completed,NP-PERUNGUDI,183,269000,"Repairs and improvement works for side drain at selvaraj avenue in division 183-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17437,Storm Water Drain,Completed,NP-PERUNGUDI,183,73400,"Repairs and improvement works for side drain at kuppam piullayar koil street in division 183-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17438,Buildings,Completed,NP-PERUNGUDI,183,479000,"Repairs and improvement works at Division office -183 and labour shed in division 183-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17440,Buildings,Completed,NP-PERUNGUDI,183,132000,"Repairs and improvement works at Kottivakkam Kuppam Panchayat Union primary school in Div -183 unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17442,Buildings,Completed,NP-PERUNGUDI,183,8600,"Repairs and improvement works at new colony anganvadi in division 183-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17443,Playfields,Completed,NP-PERUNGUDI,183,755000,"Repairs and improvement works at AGS colony play ground in division 183-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/1914,Storm Water Drain,Completed,NP-PERUNGUDI,183,581000,"DE SILTING OF SWD AND SIDE DRAIN AT VARIOUS STREET IN DIVISION-183,UNIT-41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/19220,Buildings,Completed,NP-PERUNGUDI,183,200000,PROVIDING ORNAMENTAL SHEETS ROOFING SHED TO RATION SHOP AT PURATCHI THALAVI NAGAR IN DIVISION-183 UNIT-41 ZONE-14,Own Sources,14,2016-17,2017-18 NP/2016-17/19292,Road Cut,Completed,NP-PERUNGUDI,183,2775000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT NEW COLONY STREET 1ST,NEW COLONY ROAD, VENKATESHWARA NAGAR, AGS COLONY MAIN ROAD, VENKATESHWARA NAGAR 21 STREET, VENKATESHWARA NAGAR 1ST STREET, NEW COLONY 3RD STREET, IN DIVISION 183,UNIT41-ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/3498,Storm Water Drain,Completed,NP-PERUNGUDI,183,835000,Construction of Linking Drain and Culvert at Swaminathan nagar 3 rd street in Dn 183 Unit 41 Zone XIV ( Under Ward Councillor Development Fund),Own Sources,14,2016-17,2017-18 NP/2016-17/3499,Culvert,Completed,NP-PERUNGUDI,183,492000,Construction of linking drain and culvert at Anna Street in Dn 183 Unit 41 Zone XIV( Under Ward Councillor Development Fund),Own Sources,14,2016-17,2017-18 NP/2016-17/3653,Culvert,Completed,NP-PERUNGUDI,183,960000,"Construction of Culverts at Kuppam Various Streets ( 9 Locations ) in Division 183, Unit 41, Zone 14.",Own Sources,14,2016-17,2018-19 NP/2016-17/3865,Road Cut,Completed,NP-PERUNGUDI,183,850000,"Restoration of Metro water (CMWSSB) road cut portion at Kalyani nagar 1st street (Karthick street, Lakshmana perumal nagar 2nd street, Kalyani nagar, Kalyani nagar 1st street, Kalyani nagar (nimalan street) Kalyani nagar (Pooja street), Kalyani nagar (Rani street) Raja Garden 1st street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3867,Road Cut,Completed,NP-PERUNGUDI,183,850000,"Restoration of Metro water (CMWSSB) road cut portion at Raja Garden, Nehru nagar 4th Link street, Nehru nagar 3rd main road in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3870,Road Cut,Completed,NP-PERUNGUDI,183,957000,"Restoration of Metro water (CMWSSB) road cut portion at Raja street, Karpagambal nagar 3rd street, Nehru nagar 5th link street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3876,Road Cut,Completed,NP-PERUNGUDI,183,855000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 2nd cross street, nehru nagar 1st link street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3881,Road Cut,Completed,NP-PERUNGUDI,183,850000,"Restoration of Metro water (CMWSSB)road cut portion at Nehru nagar 2nd link street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3884,Road Cut,Completed,NP-PERUNGUDI,183,852000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 1st main road 0 to 500 m in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3886,Road Cut,Completed,NP-PERUNGUDI,183,330000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 1st main road 500 to 670 m in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3888,Road Cut,Completed,NP-PERUNGUDI,183,833000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 10th link street, Nehru nagar 2nd main road in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3891,Road Cut,Completed,NP-PERUNGUDI,183,848000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 3rd cross street, Nehru nagar 3rd cross street Extn-1, Nehru nagar 10th cross street, Nehru nagar 6th link street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3907,Road Cut,Completed,NP-PERUNGUDI,183,848000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 3rd link street, Nehru nagar 13th street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3908,Road Cut,Completed,NP-PERUNGUDI,183,855000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 14th link street, Nehru nagar 11th street, Netco colony west street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3909,Road Cut,Completed,NP-PERUNGUDI,183,881000,"Restoration of Metro water (CMWSSB) road cut portion at Nehru nagar 12th street, Natco colony north street, Natco colony midil street, Vembuli amman koil street, Sri Ram avenue 2nd street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3911,Road Cut,Completed,NP-PERUNGUDI,183,850000,"Restoration of Metro water (CMWSSB) road cut Portion at Netco Colony west Extn street, Vembuli amman koil 1st street, Sri ram avenue 1st street, Sri Ram avenue 3rd street, Sri ram avenue 4th street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3913,Road Cut,Completed,NP-PERUNGUDI,183,854000,"Restoration of Metro water (CMWSSB) road cut Portion at Sri Ram avenue 5th street, Swaminathan nagar main road, Swaminathan nagar 2nd main road in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3914,Road Cut,Completed,NP-PERUNGUDI,183,850000,"Restoration of Metro water (CMWSSB) road cut Portion at Swaminathan nagar 2nd cross street, Vengateshwara nagar 5th street, Vengateshwara nagar 11th street, AGS Colony Beach 1st street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3915,Road Cut,Completed,NP-PERUNGUDI,183,818000,"Restoration of Metro water (CMWSSB) road cut Portion at Vengadeswara nagar 13th street, Vengadeshwara nagar 9th street, Vengadeshwara nagar 12th street, AGS Colony Beach 1st cross street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3917,Road Cut,Completed,NP-PERUNGUDI,183,815000,"Restoration of Metro water (CMWSSB) road cut Portion at Vengadeshwara nagar 18th street, A.G.S Colony Beach 2nd cross street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3918,Road Cut,Completed,NP-PERUNGUDI,183,851000,"Restoration of Metro water (CMWSSB) road cut Portion at AGS Colony Beach main road in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3919,Road Cut,Completed,NP-PERUNGUDI,183,956000,"Restoration of Metro water (CMWSSB) road cut Portion at Kottivakkam kuppam, Vengadeshwara nagar 17 th street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3920,Road Cut,Completed,NP-PERUNGUDI,183,855000,"Restoration of Metro water (CMWSSB) road cut Portion at Jaganathan street in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/4183,Roads,Completed,NP-PERUNGUDI,183,998000,"Laying Cement Concrete road at Bajanai Kovil cross st , Bajani koil 2nd cross and Bajanai koil 3rd cross street in Division-183, Unit-41,Zone-14",Own Sources,14,2016-17,2018-19 NP/2016-17/4249,Roads,Completed,NP-PERUNGUDI,183,998000,"Laying Cement Concrete road at Bajanai Kovil 6th cross st , Bajani koil 7th cross streetand purachi thalaivi street in Division-183, Unit-41,Zone-14",Own Sources,14,2016-17,2018-19 NP/2016-17/4257,Roads,Completed,NP-PERUNGUDI,183,998000,"Laying Cement Concrete road at Bajanai Kovil 8th cross st , Puratchi Thalaivi 13th street in Division-183, Unit-41,Zone-14",Own Sources,14,2016-17,2018-19 NP/2016-17/6763,Roads,Completed,NP-PERUNGUDI,183,2999000,"Restoration of metro water (CMWSSB) road cut VSI Estate 4th street, 5th street, 6th street, 7th street, 9th street, Nadesan colony, in Div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/6766,Roads,Completed,NP-PERUNGUDI,183,2997000,"Restoration of metro Water (CMWSSB) Raad cut portion at Ramalinga nagar, swaminathan nagar 9th street, Elango nagar, Vsi estate 11th street, 11th cross street, 10th street, 3rd street, in Div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/6767,Roads,Completed,NP-PERUNGUDI,183,2956000,"Restoration of Metro Water (CMWSSB) Road cut portion at Swaminathan 6th street, AGS Colony 3rd main road, 4th main road, 5th main road, ags colony 4th cross street, ags colony 4th cross street, Nehru nagar 9th link street,in Division-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/6768,Roads,Completed,NP-PERUNGUDI,183,2904000,"Restoration of Metro Water (CMWSSB) Road cut Portion at ags colony, ags Colony 2nd cross, 3rd cross, 1st street, a.g.s cross street, ags cross street, swaminathan nagar 4th main road, swaminathan nagar7th main road, swaminathan nagar7th main road, swaminathan street 4th street Div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/7683,Parks,Completed,NP-PERUNGUDI,183,686000,"Providing Pebble Walking pathway and other Improvement Works to A.G.S Colony Play Ground in Division 183, Unit 41, Zone 14. (Ward Councillor Improvement Fund 2015-2016)",Own Sources,14,2016-17,2017-18 NP/2016-17/9167,Roads,Completed,NP-PERUNGUDI,183,2011000,"Forming Strengthining and laying Bituminous Road at Ags Colony 2nd Main Road, in div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/9169,Roads,Completed,NP-PERUNGUDI,183,1969000,"Forming strengthening and laying Bituminous Road at DR.Vaidegi Road in div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/9173,Roads,Completed,NP-PERUNGUDI,183,1136000,"Forming strengthening and laying Bituminous Road at AGS Colony 1st cross street in div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/9175,Roads,Completed,NP-PERUNGUDI,183,1136000,"Forming strengthening and laying Bituminous Road at AGS Colony 2nd cross street in div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/9178,Roads,Completed,NP-PERUNGUDI,183,2186000,"Forming strengthening and laying Bituminous Road at Kaveri nagar 5th street in div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/9182,Roads,Completed,NP-PERUNGUDI,183,1573000,"Forming strengthening and laying Bituminous Road at AGS Colony 1st main road in div-183, Unit-41, Zone-14",Own Sources,14,2016-17,2017-18 L/2016-17/13801,Electrical,Completed,L-Electrical,184,199900,"Shifting and raising of 21 nos Pillar boxes and 336 pillars At Various Locations In Div-184,186 and 189, Zone-XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/0231,Storm Water Drain,Completed,NP-PERUNGUDI,184,215000,"REPAIRS TO SIDED DRAIN AT CBI COLONY AND VARIOUS STREET IN DIVISION-184, UNIT-41, ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0232,Roads,Completed,NP-PERUNGUDI,184,361000,"ATTENDING CEMENT CONCRETE AT VARIOUS STREET IN DIVISION-184,UNIT-41,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0233,Buildings,Completed,NP-PERUNGUDI,184,385000,"PROVIDING ORGAMENTAL SHEET ROOFING ARRANGEMENT AND FIXING S.S LETTERS TO MUITIPURPOSE HALL AND RATION SHOP ( NEAR AMMA UNAVAGAM ) IN DIVISION -184, UNIT-41, ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0675,Electrical,Completed,P-Parks and Playfields,184,993800,"Work: Provision of 7nos 6 Mtr lamp hot dip post with Single st Bracket with 40-50w LED Fitting ,18 nos of 2 Mtr lamp hot dip galvanising post with curved Bracket with 15w LED Fitting and 3 nos of 6 Mtr lamp hot dip post with 250w MHFitting at Annanedunchalai park in Division-184, Zone-XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/12725,Buildings,Completed,NP-PERUNGUDI,184,402000,"IMPROVEMENTS TO ENTRANCE GATE FOR BURIAL GROUND ,SCHOOL BUILDING AT SCHOOL ROAD AND IMPROVEMENT TO STORM WATER DRAIN AT ANNA NEDUNSALAI (KALIAMMAN KOIL)IN DIV 184,UNIT 41,ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/12726,Buildings,Completed,NP-PERUNGUDI,184,47600,"CONSTRUCTION OF DUSTBIN PLAT FORM AT VARIOUS STREET IN DIV 184, UNIT 41,ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/12727,Buildings,Completed,NP-PERUNGUDI,184,215000,"CONSTRUCTION OF LABOUR DRESSING ROOM INSIDE OF DIVISION OFFICE 184 AT SCHOOL ROAD IN DIV 184,UNIT 41,ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/13416,Roads,Completed,NP-PERUNGUDI,184,837000,"SUPPLYING 35 HP DIESEL MOTOR AND 1 HP SUB MERGE MOTOR AND PROVIDING AND RUNNING 35 HP DIESEL MOTOR FOR RENT IN DIV 184,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/13754,Buildings,Completed,NP-PERUNGUDI,184,200000,"CONSTRUCTION OF RAMP AND STEPS TO ANGANWADI AT ANNA NEDUNSALAI,PLUMBING WORKS TO KALLUKUTTAI METRO WATER LINE,ARRANGING AND ENGAGING 1HP,7.5HP MOTOR FOR VARIOUS LOCATION IN DIVISION 184 UNIT 41 ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/13755,Buildings,Completed,NP-PERUNGUDI,184,490000,"IMPROVEMENTS TO NAMMA TOILET AT MGR SALAI TARAMANI OPPOSITE TO ICDS AND REPAIRING DIESEL ENGINE AND WATER PURIFY IN DIV 184,UNIT 41,ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/14425,Roads,Completed,NP-PERUNGUDI,184,129000,"PROVIDING AND LAYING WETMIX MACADAM PATCH AT VEERA MAMUNIVAR STREET AND CLEANING BORE,REPAIRS OF MOTOR AT VARIOUS PLACES IN DIV 184, UNIT 41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/14430,Roads,Completed,NP-PERUNGUDI,184,253000,"ARRANGING AND ENGAGING JCB AND TIPPER LORRY FOR VARIOUS PLACES , PROVIDING AND FIXING SWD MHD2 AT VARIOUS PLACES AND DUSTBIN NAMES WRITING IN DIV 184, UNIT 14,ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/14510,Buildings,Completed,NP-PERUNGUDI,184,42000,REPAIRS AND IMPROVEMENTS OF 2 NOS PUBLIC CONVENIENCE AT ANNANEDUNSALAI {NEAR LAKE VIEW} IN DIVISION 184 UNIT 41 ZONE 14,Own Sources,14,2016-17,2017-18 NP/2016-17/1582,Electrical,Completed,NP-PERUNGUDI,184,678000,Work :Provision of 28 nos of 2mtr hot dip galvanising lamp post with1mtr curved bracket with 15W LED fittings at Telephone nagar park phase-II in Div 184 Zone XIV,Own Sources,14,2016-17,2016-17 NP/2016-17/16622,Buildings,Completed,NP-PERUNGUDI,184,328000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT ANNANEDUNSALAI,MGR SALAI IN DN 184 UT 41 ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/16634,Buildings,Completed,NP-PERUNGUDI,184,318000,"REPAIRS AND IMPROVEMENTS TO UNIT OFFICE41 DN 184 AND LABOUR SHED,PARKING SHED IN DN 184 UT 41 ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/16664,Buildings,Completed,NP-PERUNGUDI,184,370500,"PROVIIND REPAIRS AND IMPROVEMENTS TO TELEPHONENAGAR PARK,CBI COLONY PARK,ANDTHIRUVALLUVAR NAGAR OARK IN DN 184 UT 41 ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/16671,Buildings,Completed,NP-PERUNGUDI,184,245000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT ANNANEDUNSALAI 2NOS ,NAMMA TOILET MGR SALAI IN DN 184 UT 41 ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/1686,Electrical,Completed,NP-PERUNGUDI,184,985500,"Provision of 17 nos of 6mtr hot dip galvanising lamp post with Single Straight bracket with 40-50W LED fittings and 4 nos of 6mtr hot dip galvanising lamp post without bracket with 250w MH FL fitting,150w MH FL fitting at Telephone nagar park phase-I in Div 184 Zone XIV",Own Sources,14,2016-17,2016-17 NP/2016-17/17526,Roads,Completed,NP-PERUNGUDI,184,371000,"PROVIDING BT PATCH WORK AT TELAPHONE NAGAR 16TH STREET CR STREET, NETHAJINAGAR, PILLAYAR KOIL 1ST CROSS STREET, RAMAPPANAGAR,PILLAYAR KOIL 1ST CROSS STREET IN DN 184, U 41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/4774,Buildings,Completed,NP-PERUNGUDI,184,48800,PROVIDING WATER SUPPLY LINE TO WATER PURIFY IN DIVISION OFFICE IN DIV 184 UNIT 41 ZONE 14,Own Sources,14,2016-17,2016-17 NP/2016-17/4857,Roads,Completed,NP-PERUNGUDI,184,113000,"PROVIDING AND FIXING NAME STICKER FOR VARIOUS LOCATION IN DIV 184 ,AND REPAIRING AN ENGINE FOR TATA ACE (LOAD AUTO)IN DIV 184, UNIT 41,ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/4920,Roads,Completed,NP-PERUNGUDI,184,255600,"PROVIDING DE WATERING MOTOR FOR HIRE CHARGES INCLUDING FUEL CHARGES AND OPERATOR CHARGES IN DIV 184,UNIT 41 ,ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/4922,Buildings,Completed,NP-PERUNGUDI,184,160000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT KALLU KUTTAI IN DIV 184, UNIT 41,ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/4924,Buildings,Completed,NP-PERUNGUDI,184,178500,"ADDITIONAL IMPROVEMENTS AND PROVIDING ELECTRICAL ARRANGEMENTS TO GYM BUILDING AND RATION SHOP AT PILLAIYAR KOIL STREET IN DIV 184, UNIT 41, ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/4929,Roads,Completed,NP-PERUNGUDI,184,236000,"ATTENDING PATCH WORK WITH WET MIX MACADAM AT VARIOUS STREET IN DIV 184,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/4931,Buildings,Completed,NP-PERUNGUDI,184,774900,"PROVIDING SUPPLYING AND ARRANGEMENT TO ELECTION BOOTH ON POLLING DAY FOR TAMILNADU ASSEMBLY ELECTION AT VARIOUS ELECTION BOOTH IN DIV 184, UNIT 41, ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/4933,Buildings,Completed,NP-PERUNGUDI,184,117000,"IMPROVEMENTS TO PARK, PUBLIC CONVENIENCE ,STORM WATER DRAIN AT VARIOUS ROADS IN DIV 184,UNIT 41, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/4935,Buildings,Completed,NP-PERUNGUDI,184,279966,"ADDITIONAL IMPROVEMENTS TO GYM BUILDING AT RAMAPPA NAGAR MAIN ROAD (JUNCTION OF PILLAIYAR KOIL STREET)IN DIV 184,UNIT 41, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/4936,Buildings,Completed,NP-PERUNGUDI,184,187000,"IMPROVEMENTS TO COUNSELLOR OFFICE AND AMMA UNAVAGAM AT ANNANEDUNSALAI IN DIV 184,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/4937,Buildings,Completed,NP-PERUNGUDI,184,333036,"IMPROVEMENTS TO AMMA UNAVAGAM AT MGR SALAI (TARAMANI)IN DIV 184 ,UNIT 41, ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/5087,Buildings,Completed,NP-PERUNGUDI,184,990000,CONSTRUCTION OF MULTIPURPOSE HALL AT ANNA NEDUNSALAI JUNCTION OF SCHOOL ROAD IN DIVISION -184 UNIT-41 ZONE-14 (UNDER COUNCILLOR FUND 2016-2017),Own Sources,14,2016-17,2016-17 NP/2016-17/5170,Buildings,Completed,NP-PERUNGUDI,184,995000,"PROVIDING WATER SUPPLY, ELECTRICAL ARRANGEMENT AND ROOFING WORKS OF MULTIPURPOSE HAII AT ANNA NEDUNSALAI JUNCTION OF SCHOOL ROAD IN DIVISION -184 UNIT-41 ZONE-14 ( UNDER COUNCILLOR FUND 2016-2017)",Own Sources,14,2016-17,2016-17 NP/2016-17/5401,Buildings,Completed,NP-PERUNGUDI,184,984000,"CONSTRUCTION OF MULTIPURPOSE HALL AT ANNA NEDUNCHALAI (JUNCTION OF SCHOOL ROAD)IN DIV 184 ,UNIT 41,ZONE 14(COUNCILLOR FUND)",Own Sources,14,2016-17,2017-18 NP/2016-17/6849,Roads,Completed,NP-PERUNGUDI,184,2979000,"RESTORATION OF CMWSSB WATER LINE ROAD CUT AT ANNANEDUN SALAI AND SCHOOL ROAD IN DN-184, U-41, Z-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/6851,Roads,Completed,NP-PERUNGUDI,184,2979000,"RESTORATION OF CMWSSB WATER LINE ROAD CUT AT THIRUVENGADAM NAGAR 1ST , 2ND STREET, SANTHIAPPAN SALAI MAIN ROAD, 1ST, 2ND CROSS STREET, KARPAGAVINAYAGA KOIL STREET GOTHNDARAMAN NAGAR MAIN ROAD , CROSS STREET AND SAIAYUSH POOJA AVENUE IN DN-184, U-41, Z-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/7058,Roads,Completed,NP-PERUNGUDI,184,985000,LAYING OF CC ROAD AT THIRUVELLUVAR ST (FROM JUNCTION OF MGR SALAI ) DIVISION -184.UNIT-41 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/7669,Buildings,Completed,NP-PERUNGUDI,184,470000,PROVIDING CHAIR LINK FENCING FOR AMMA UNAVAGAM AT TNEB SALAI IN DIVISION-184 UNIT-41 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/7785,Buildings,Completed,NP-PERUNGUDI,184,990000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO AMMA UNAVAGAM AT MAHALAKSHMI NAGAR IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/8477,Buildings,Completed,NP-PERUNGUDI,184,43470,"ADDITIONAL IMPROVEMENTS TO DIVISION OFFICE ,COUNCILLOR OFFICE IN DIV 184,UNIT 41,ZONE 41",Own Sources,14,2016-17,2016-17 NP/2016-17/8934,Roads,Completed,NP-PERUNGUDI,184,293000,"PROVIDING STREET NAME BOARD AT VARIOUS STREET,E-SEVA NAME BOARD IN DIV 184,UNIT 41,ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/9015,Roads,Completed,NP-PERUNGUDI,184,182000,"DISMANTLING THE EXISTING RCC STRUCTURE WALL AND TOP SLAB OF SIZE 60CM*30CM INCLUDING DISMANTLING,MACHINERIES FOR CUTTER GENERATOR,TRACTOR AND LABOUR CHARGES INCLUDING SUPPLYING AND FIXING FRP GRATINGS ETC IN DIV 184 UNIT 41 ZONE 14",Own Sources,14,2016-17,2016-17 BR/2016-17/18636,Roads,Completed,BR-Bus Route Roads,185,173000,Providing of ramps for stainless steel bus shelter at various roads in zone-14.,Own Sources,14,2016-17,2018-19 L/2016-17/13796,Electrical,Completed,L-Electrical,185,193300,Provision of 12 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-185 and 191. Zone-XIV,Own Sources,14,2016-17,2017-18 L/2016-17/18122,Electrical,Completed,L-Electrical,185,699200,"Removal and refixing of 133nos of 6mtr lamp post and erection of 35Nos of 7mtr lamp post and 5Nos of 9.5 mtr lamp post at various locations in Dn-183 to 186 & 191 in Zone-XIV, due to Vardha cyclone effect on 12-12-16",Own Sources,14,2016-17,2017-18 NP/2016-17/0939,Buildings,Completed,NP-PERUNGUDI,185,300000,PAINTING FOR DIVISION AND TOILET AT ECR MAIN ROAD IN PALLAVAKKAM IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/1507,Buildings,Completed,NP-PERUNGUDI,185,998000,"PROVIDING BARRICADING TABLES AND CHAIRS ARRANGEMENTS AND SHAMIYANA PANDAL BOOTHS AT VARIOUS LOCATION FOR ASSEMBLY ELECTION 2016 IN DN-185,UNIT-41,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/17355,Buildings,Completed,NP-PERUNGUDI,185,1155000,"VARTHA CYCLONE DAMAGED AT BURIAL GROUND COMPOUND WALL REPAIR WORK IN DN 185, U-41,Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17370,Buildings,Completed,NP-PERUNGUDI,185,480000,"VARTHA CYCLONE DAMAGED AT DIVISION OFFICE IN DN-185, U-41, Z-14",Thanniraivu Thittam,14,2016-17,2017-18 NP/2016-17/17378,Storm Water Drain,Completed,NP-PERUNGUDI,185,745000,"VARTHA CYCLONE DAMAGED AT SIDE DRAIN GOVINDAN NAGAR AND ESTATE MAIN ROAD IN DN-185, U-41, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17384,Storm Water Drain,Completed,NP-PERUNGUDI,185,745000,"VARTHA CYCLONE DAMAGED AT SIDE DRAIN VEERAMANI SALAI 1ST, 2ND AND 4TH STREET IN DN-185, U-41, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17400,Roads,Completed,NP-PERUNGUDI,185,748000,"VARTHA CYCLONE DAMAGED PATCH WORK AT ESTATE 1ST MAIN ROAD , BARMA COLONY 4TH STREET, 5TH STREET, GOVINDAN NAGAR, GOVINDAN NAGAR MAIN ROAD, KARIM NAGAR, MANIYAMMAI STREET, KANDASWAMI NAGAR 7TH STREET IN DN-185, U-41, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17404,Buildings,Completed,NP-PERUNGUDI,185,64000,"VARTHA CYCLONE DAMAGED AT AMMA UNAVAGAM IN DN-185, U-41,Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/1916,Storm Water Drain,Completed,NP-PERUNGUDI,185,600000,"DE SILTING OF SWD AND SIDE DRAIN AT VARIOUS STREET IN DIVISION-185,UNIT-41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/2798,Storm Water Drain,Completed,NP-PERUNGUDI,185,960000,IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 FROM RADHA KRISHANAN STREET TO CANAL AND LINKING TO THE EXISTING SWD IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/2801,Storm Water Drain,Completed,NP-PERUNGUDI,185,978000,"IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 FROM ANBALAGAN STREET TO PACHAYAIPPAN STREET AND LINKING TO THE EXISTING SWD IN DN185 ,UNIT-41,ZONE-14",Own Sources,14,2016-17,2018-19 NP/2016-17/2803,Storm Water Drain,Completed,NP-PERUNGUDI,185,988000,IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 FROM PACHAYAIPPAN STREET TO M.K I. STALIN STREET AND LINKING TO THE EXISTING SWD IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/2804,Storm Water Drain,Completed,NP-PERUNGUDI,185,963000,IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 FROM M.K STALIN TO RADHAKRISHANAN STREET AND LINKING TO THE EXISTING SWD IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/2805,Storm Water Drain,Completed,NP-PERUNGUDI,185,984000,IMPROVEMENTS TO THE DAMAGED DRAIN DUE TO UNFORESEEN FLOOD 2015 FROM ECR MAIN ROAD TO ANBALAGAN STREET AND LINKING TO THE EXISTING SWD IN DN-185 UNIT-41 ZONE-14,Own Sources,14,2016-17,2018-19 NP/2016-17/2875,Storm Water Drain,Completed,NP-PERUNGUDI,185,973000,"LAYING HUME PIPE 0.30MM AT PAUL RAJ NAGAR IN DIVISION-185, UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/4655,Culvert,Completed,NP-PERUNGUDI,185,989000,REPAIRS AND IMPROVEMENTS TO EXISTING RCC CULVERT AT VARIOUS STREET (7NOS) IN DIV 185 UNIT 41 ZONE 14,Own Sources,14,2016-17,2018-19 NP/2016-17/4656,Culvert,Completed,NP-PERUNGUDI,185,993000,REPAIRS AND IMPROVEMENTS TO EXISTING RCC CULVERT AT VARIOUS STREET (8 NOS) IN DIV 185 UNIT 41 ZONE 14,Own Sources,14,2016-17,2018-19 NP/2016-17/5335,Roads,Completed,NP-PERUNGUDI,185,999000,"FORMING AND LAYING OF CC ROAD AT AMBEDKAR STREET, AND MAIN ROAD,RURAL SALI, 1ST STREET (COUNCILOR FUND)IN DN -185, UNIT 41,ZONE 14,",Own Sources,14,2016-17,2016-17 NP/2016-17/5345,Roads,Completed,NP-PERUNGUDI,185,998000,"FORMING AND LAYING OF CC ROAD AT POONGA NAGAR CROSS STREET,LAYING HUME PIPE,0.30MM AT, DIG COLENY, COUNCILOR FUND IN DN-185, UNIT-41, ZONE-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/5752,Buildings,Completed,NP-PERUNGUDI,185,990000,CONSTRUCTION OF AMMA UNAVAGAM AT BURMA COLONY STREET IN DIVISION-185 UNIT-41 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/5775,Buildings,Completed,NP-PERUNGUDI,185,997000,"CONSTRUCTION OF KITCHEN STORE ROOM, TOILET AND PROVIDING WATER SUPPLY ARRANGEMENT TO AMMA UNAVAGAM AT BURMA COLONY STREET IN DIVISION-185 UNIT-41 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/5806,Roads,Completed,NP-PERUNGUDI,185,998000,"FORMING AND LAYING OF CC ROAD AT KARUMARIAMMAN KOVIL STREET,AND CROSS STREET,RURAL SALI ,2ST,3ND STREETS. (COUNCILOR FUND) IN DN-185,UNIT-41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/6756,Roads,Completed,NP-PERUNGUDI,185,2999000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN-185,UNIT-41,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/6757,Roads,Completed,NP-PERUNGUDI,185,2892000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN-185,UNIT-41,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/6758,Roads,Completed,NP-PERUNGUDI,185,2933000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN-185,UNIT-41,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/6759,Roads,Completed,NP-PERUNGUDI,185,2854000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN-185,UNIT-41,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/6760,Roads,Completed,NP-PERUNGUDI,185,1575000,"RESTORATION OF METRO WATER ROAD CUT AT VARIOUS STREET IN DN-185,UNIT-41,ZONE-14",Own Sources,14,2016-17,2016-17 L/2016-17/13551,Electrical,Completed,L-Electrical,186,193300,Provision of 12 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-184 and 186. Zone-XIV,Own Sources,14,2016-17,2017-18 L/2016-17/13783,Electrical,Completed,L-Electrical,186,882300,"WORK: Replacement for cable laying of 500 mtr 3 1/2x25 sqmm cable,450mtr 3 x120 sqmm cable . Supply & erection of 2nos Busbar pillar and replacement of Galvanised steel wire rope of 30mtr Highmast & servicing , at perungudi dumping ground in div 186, Zone-XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/0997,Buildings,Completed,NP-PERUNGUDI,186,3618000,"PROPOSED CONSTRUCTION OF FIRST FLOOR 3 CLASS ROOM WITH STAIR CASE IN PANCHAYAT UNION PRIMARY SCHOOL AT SCHOOL ROAD IN DN-186, U-41, Z-14.",MPLADS,14,2016-17,2018-19 NP/2016-17/12718,Buildings,Completed,NP-PERUNGUDI,186,327999,"CONSTRUCTION OF LABOUR DRESSING ROOM INSIDE OF DIVISION OFFICE AT PANCHAYAT OFFICE MAIN ROAD IN DIV 186,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/12719,Roads,Completed,NP-PERUNGUDI,186,331980,"PROVIDING AND LAYING QUARRY RUBBISH AND WMM ROAD AT BETHAL NAGAR MAIN ROAD IN DIV 186, UNIT 41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/12720,Buildings,Completed,NP-PERUNGUDI,186,95500,"CONSTRUCTION OF DUST BIN PLAT FORM AT VARIOUS STREET IN DIV 186,UNIT 41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/12722,Buildings,Completed,NP-PERUNGUDI,186,176000,"PROVIDING AND LAYING 200MM DIA PVC PIPE AND CONSTRUCTION OF CHAMBER FOR DIVERT STORM WATER DRAIN AT CORPORATION ROAD IN DIV 186,UNIT 41, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/13189,Roads,Completed,NP-PERUNGUDI,186,85000,"PROVIDING WETMIX MACADAM PATCH AT NEAR 3RD CROSS STREET TO JUNCTION OF CORPORATION ROAD IN DIV 186,UNIT 41,ZONE -14",Own Sources,14,2016-17,2017-18 NP/2016-17/13192,Roads,Completed,NP-PERUNGUDI,186,322000,ARRANGING AND ENGAGING JCB AN LORRY FOR VARIOUS WORKS AND SUPPLYING PVC PIPE IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2016-17,2017-18 NP/2016-17/13193,Parks,Completed,NP-PERUNGUDI,186,519000,"IMPROVEMENTS TO THIRUMALAI NAGAR PARK GATE WORK, CONSTRUCTION OF SUMP WORK AND PROVIDING INNAGURATION CULVERT AT VARIOUS PLACES IN DIV 186 UNIT 41 ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/14083,Buildings,Completed,NP-PERUNGUDI,186,993000,"CONSTRUCTION OF STORE ROOM , TOILET AND PROVIDING PAINTING WORKS TO THE EXISTING AMMA UNAVAGAM AT CORPORATION ROAD IN DIVISION- 186, UNIT - 41, ZONE-15.",Own Sources,14,2016-17,2016-17 NP/2016-17/14406,Roads,Completed,NP-PERUNGUDI,186,571999,SUPPLYING DEDBRISH AND ENGAGING JCB FOR LEVELING THE DEBRISH AT MANI KODI SREENIVASA NAGAR MAIN ROAD IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2016-17,2017-18 NP/2016-17/14410,Roads,Completed,NP-PERUNGUDI,186,117000,ARRANGING AND ENGAGING JCB AND TIPPERS LORRY FOR VARIOUS WORKS AT SENTHIL NAGAR IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2016-17,2017-18 NP/2016-17/15122,Buildings,Completed,NP-PERUNGUDI,186,59000,"IMPROVEMENTS TO E- SEVA ,CLEANING BORES ,NAME WRITING FOR VEHICLES AND VARIOUS WORKS IN DIV 186,UNIT 41,ZONE 14",Own Sources,14,2016-17,2017-18 NP/2016-17/17335,Roads,Completed,NP-PERUNGUDI,186,279000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 5TH STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17341,Roads,Completed,NP-PERUNGUDI,186,465000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 4TH STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17345,Roads,Completed,NP-PERUNGUDI,186,527000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 1ST CROSS STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17360,Roads,Completed,NP-PERUNGUDI,186,558000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 8TH CROSS STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17365,Roads,Completed,NP-PERUNGUDI,186,248000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 7TH CROSS STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17399,Roads,Completed,NP-PERUNGUDI,186,279000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 6TH CROSS STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17407,Roads,Completed,NP-PERUNGUDI,186,186000,"RELAYING OF DAMAGED ROAD AT SENTHIL NAGAR 3RD CROSS STREET IN DIVISION 186- UNIT41,ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/17444,Buildings,Completed,NP-PERUNGUDI,186,17000,"Repairs and improvement works at AMMA UNAVAGAM in division 186-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17445,Parks,Completed,NP-PERUNGUDI,186,77000,"Repairs and improvement works at Vengateshvara nagar park division 186-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17446,Buildings,Completed,NP-PERUNGUDI,186,586000,"Repairs and improvement works at composed yard in verapandiya kattabomman street division 186-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17448,Buildings,Completed,NP-PERUNGUDI,186,109000,"Repairs and improvement works at Thirumalai nagar park division 186-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/17451,Buildings,Completed,NP-PERUNGUDI,186,184500,"REPAIR WORKS TO COMPOUND WALL AT CORPORATION ROAD KULAM IN DN-186, UNIT-42, ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17452,Parks,Completed,NP-PERUNGUDI,186,259000,"Repairs and improvement works at Rajive nagar park division 186-unit41,zone14",Own Sources,14,2016-17,2017-18 NP/2016-17/1857,Storm Water Drain,Completed,NP-PERUNGUDI,186,600000,"Desilting of side and storm water drain at various streets (87nos) in Dn-186,unit-41,zone-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/1862,Storm Water Drain,Completed,NP-PERUNGUDI,186,605000,"Desilting of side and storm water drain at various streets (67nos) in Dn-184,unit-41,zone-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/18930,Buildings,Completed,NP-PERUNGUDI,186,2229000,"PROPOSED COMPOST YARD AT INDUSTRIAL ESTATE 4TH MAIN ROAD (PERUNGUDI) IN DN-186, UNIT-41, ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/19276,Roads,Completed,NP-PERUNGUDI,186,3119000,"Forming and laying for C.C Road at Pillayar Koil 4th Cross street in division-186,unit-41,zone-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/19295,Roads,Completed,NP-PERUNGUDI,186,1936000,"RESTORATION OF METRO WATER(CMWSSB) ROAD CUTTING AT OOMADHURAI STREET, PANCHAYAT 2ND CROSS STREET, THIRUMALAI NAGAR 3RD CROSS STREET, PATHMAVATHI AVENUE, THIRUMALAI NAGAR ANNEX 2ND CROSS STREET, THIRUMALAI NAGAR ANNEX 4TH CROSS STREET, CORPORATION ROAD, IN DIVISION 186,UNIT41-ZONE14",Own Sources,14,2016-17,2017-18 NP/2016-17/3331,Buildings,Completed,NP-PERUNGUDI,186,999000,CONSTRUCTION OF MULTIPURPOSE HALL AT PANCHAYAT MAIN ROAD 3RD CROSS STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2016-17,2017-18 NP/2016-17/3481,Buildings,Completed,NP-PERUNGUDI,186,499900,CONSTRUCTION OF MULTIPURPOSE HALL AT CORPORATION ROAD NEAR DUMPING YARD IN DIV 186 UNIT 41 ZONE14,Own Sources,14,2016-17,2017-18 NP/2016-17/3500,Storm Water Drain,Completed,NP-PERUNGUDI,186,995000,"REPAIRS AND IMPROVEMENTS TO EXISTING RCC CULVERT AT PANCHAYAT MAIN ROAD ( JUNCTION OF OOMAI THURAI STREET,JN.OF 2ND CROSS STREET,JN. OF 3RD LINK ROAD,JN.OF SCHOOL ROAD,RAJIV NAGAR 1ST MAIN ROAD (JN.OF JANAKIRAMAN NAGAR MAIN ROAD IN DIVISION 186 UNIT 41 ZONE 14",Own Sources,14,2016-17,2018-19 NP/2016-17/4938,Buildings,Completed,NP-PERUNGUDI,186,45000,"IMPROVEMENTS TO CORPORATION ROAD DUMPING YARD IN DIV 186,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/4939,Buildings,Completed,NP-PERUNGUDI,186,245000,"ADDITIONAL IMPROVEMENTS TO RATION SHOP IN DIVISION OFFICE ENTRANCE AT PANCHAYAT MAIN ROAD IN DIV 186,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/4940,Buildings,Completed,NP-PERUNGUDI,186,130000,"WRITING LETTERS DUST BINS NAMES AT VARIOUS STREET AND SUPPLYING TABLE AND CHAIR TO LIABRARY BUILDING IN DIV 186, UNIT 41,ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/4941,Buildings,Completed,NP-PERUNGUDI,186,899000,"IMPROVEMENTS AND CLEANING THE POND AT PANCHAYAT MAIN ROAD JUNCTION OF PANCHYAT 3RD CROSS IN DIV 186,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/4942,Roads,Completed,NP-PERUNGUDI,186,117000,"ATTENDING PATCH WORK WITH WET MIX MACADAM AT PANCHAYAT OFFICE MAIN ROAD IN DIV 186,UNIT 41,ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/4943,Buildings,Completed,NP-PERUNGUDI,186,165000,"IMPROVEMENTS TO PARKS AND STORM WATER DRAIN, 'E' TOILET AT VARIOUS LOCATION IN DIV 186,UNIT 41,ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/4944,Buildings,Completed,NP-PERUNGUDI,186,212000,"PROVIDING AND FIXING STICKER FOR GREATER CHENNAI CORPORATION AT DIVISION OFFICE ,DUMPING YARD ,PARKS,BURIAL GROUNDS, SCHOOLS, LOAT AUTO ETC.. AND PROVIDING NAME BOARD ,PRICE BOARD AT E SEVA IN DIV 186,UNIT 41, ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/5950,Storm Water Drain,Completed,NP-PERUNGUDI,186,740000,CONSTRUCTIONS AND IMPROVEMENTS OF SIDE DRAIN AT RAJIV NAGAR 4TH CROSS STREET AND THIRUMALAI NAGAR ANNEX BHARATHI STREET IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2016-17,2017-18 NP/2016-17/6200,Buildings,Completed,NP-PERUNGUDI,186,186000,"IMPROVEMENTS TO FISH MARKET, ANGANWADI AND DUMPING YARD AND LABOUR,LOAD AUTO ENGAGED FOR CLEANING WORK AT VARIOUS LOCATION IN DIV 186 UNIT 41 ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/6201,Buildings,Completed,NP-PERUNGUDI,186,243000,"IMPROVEMENTS TO DIVISION OFFICE PANCHAYAT SCHOOL AMMA UNAVAGAM, ENTRANCE OF DIVISION OFFICE IN DIV 186 UNIT 41 ZONE 14",Own Sources,14,2016-17,2016-17 NP/2016-17/6202,Buildings,Completed,NP-PERUNGUDI,186,900000,PROVIDING SUPPLYING AND ARRANGEMENTS TO ELECTION BOOTH ON POLLING DAY FOR TAMILNADU ASSEMBLY ELECTION AT VARIOUS ELECTION BOOTH IN DIV 186 UNIT 41 ZONE 14,Own Sources,14,2016-17,2017-18 NP/2016-17/6343,Storm Water Drain,Completed,NP-PERUNGUDI,186,760000,"REPAIRS AND IMPROVEMENTS OF SIDE DRAIN AT VEMPULIAMMAN KOIL STREET , PANCHAYAT OFFICE ROAD, AND THIRUMALAI NAGAR 4TH CROSS STREET IN DIV 186, UNIT 41,ZONE 14.(COUNCILLOR FUND)",Own Sources,14,2016-17,2017-18 NP/2016-17/6844,Roads,Completed,NP-PERUNGUDI,186,2969000,"RESTORATION OF CMWSSB WATER LINE ROAD CUT AT THIRUMALAI NAGAR 1ST, 2ND, 4TH, 5TH, 6TH, 7TH AND 8TH CROSS STREET, PILLAYAR KOIL 2ND CROSS STREET AND ELLIM NAGAR 1ST MAIN ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/6846,Roads,Completed,NP-PERUNGUDI,186,2520000,"RESTORATION OF CMWSSB WATER LINE ROAD CUT AT ELLIM NAGAR MANTHOPPU 1ST MAIN ROAD, AND 1ST CROSS STREET, ELLIM NAGAR 1ST , 2ND MAIN ROAD AND 1ST , 2ND CROSS STREET, THIRUMALAI NAGAR 1ST MAIN ROAD (NORTH AND SOUTH SIDE) IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/7199,Buildings,Completed,NP-PERUNGUDI,186,892000,"SUPPLY AND INSTALLATION OF ELECTRONIC TOILET (GENERAL) AND ANNUAL MAINTENANCE FOR 1 YEARS AT VEEMBULIAMMAN KOIL STREET IN DIV - 186, UNIT - 41,ZONE-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/7201,Buildings,Completed,NP-PERUNGUDI,186,892000,"SUPPLY AND INSTALLATION OF ELECTRONIC TOILET (GENERAL) AND ANNUAL MAINTENANCE FOR 1 YEARS AT VEERAPANDIYAKATTABOMMAN STREET IN DIV - 186, UNIT - 41,ZONE-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/9168,Roads,Completed,NP-PERUNGUDI,186,966000,"FORMING AND LAYING BT ROAD AT SRINATH ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9172,Roads,Completed,NP-PERUNGUDI,186,5564000,"FORMING AND LAYING BT ROAD AT PANCHAYAT MAIN ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9174,Roads,Completed,NP-PERUNGUDI,186,3740000,"FORMING AND LAYING BT ROAD AT GREEN ACKAR ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9176,Roads,Completed,NP-PERUNGUDI,186,1066000,"FORMING AND LAYING BT ROAD AT RAJALAKSHMI AVENUE 4TH CROSS STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9177,Roads,Completed,NP-PERUNGUDI,186,1092000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 2ND MAIN ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9210,Roads,Completed,NP-PERUNGUDI,186,4918000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 4TH MAIN ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9212,Roads,Completed,NP-PERUNGUDI,186,696000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 1ST STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9217,Roads,Completed,NP-PERUNGUDI,186,2129000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 3RD STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9221,Roads,Completed,NP-PERUNGUDI,186,1413000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 4TH STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9227,Roads,Completed,NP-PERUNGUDI,186,3278000,"FORMING AND LAYING BT ROAD AT MANIKODISRINIVASAN NAGAR MAIN ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9231,Roads,Completed,NP-PERUNGUDI,186,594000,"FORMING AND LAYING BT ROAD AT MANIKODISRINIVASAN NAGAR 1ST STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9234,Roads,Completed,NP-PERUNGUDI,186,2226000,"FORMING AND LAYING BT ROAD AT MANIKODISRINIVASAN NAGAR 3RD STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9235,Roads,Completed,NP-PERUNGUDI,186,445000,"FORMING AND LAYING BT ROAD AT MANIKODISRINIVASAN NAGAR 5TH STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9241,Roads,Completed,NP-PERUNGUDI,186,2498000,"FORMING AND LAYING BT ROAD AT SEEVARAM 1ST STREET STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9243,Roads,Completed,NP-PERUNGUDI,186,2271000,"FORMING AND LAYING BT ROAD AT SEEVARAM 3RD STREET STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9244,Roads,Completed,NP-PERUNGUDI,186,1678000,"FORMING AND LAYING BT ROAD AT INDUSTRIAL ESTATE 1ST MAINROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9247,Roads,Completed,NP-PERUNGUDI,186,356000,"FORMING AND LAYING BT ROAD AT KUMARAN NAGAR CROSS STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9250,Roads,Completed,NP-PERUNGUDI,186,511000,"FORMING AND LAYING BT ROAD AT NAGAPILLAIAVENUE 1ST STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9253,Roads,Completed,NP-PERUNGUDI,186,370000,"FORMING AND LAYING BT ROAD AT SOWNTHRIYA NAGAR 1ST STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9254,Roads,Completed,NP-PERUNGUDI,186,455000,"FORMING AND LAYING BT ROAD AT SOWNTHRIYA NAGAR 2ND STREET IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/9255,Roads,Completed,NP-PERUNGUDI,186,2420000,"FORMING AND LAYING BT ROAD AT VEERAVANCHINATHAN MAIN ROAD IN DN-186, U-41, Z-14.",Own Sources,14,2016-17,2017-18 L/2016-17/17668,Electrical,Completed,L-Electrical,187,193400,"Provision of 9 nos of 7 Mtr Old lamp post with Single Straight Bracket in the Iyappa Nagar Lake View Main Road in Division-187, Zone-XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/0946,Buildings,Completed,NP-PERUNGUDI,187,780000,IMPROVEMENTS TO THE AMMA UNAVAGAM AND OTHER WORKS IN DN-187 UNIT-42 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/1299,Electrical,Completed,NP-PERUNGUDI,187,335100,"Provision of 5 nos of 6 Mtr lamp post with Single Straight Bracket 90w-120w LED Fitting with hot dip zinc galvanising at Park Square street park in Division-187, Zone-XIV",Own Sources,14,2016-17,2016-17 NP/2016-17/1300,Electrical,Completed,NP-PERUNGUDI,187,616100,"Provision of 12 nos of 6 Mtr lamp post with Single Straight Bracket 40w-50w LED Fitting and 1 nos of 6 Mtr lamp post with 250W MH Flood Light Fitting with hot dip zinc galvanising at Nehru street park in Division-187, Zone-XIV",Own Sources,14,2016-17,2016-17 NP/2016-17/1301,Electrical,Completed,NP-PERUNGUDI,187,789400,"Provision of 15 nos of 6 Mtr lamp post with Single Straight Bracket 40w-50w LED Fitting and 2 nos of 6 Mtr lamp post with 250W MH Flood Light Fitting with hot dip zinc galvanising at Karthikeyapuram 6th street park in Division-187, Zone-XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/13226,Storm Water Drain,Completed,NP-PERUNGUDI,187,489000,"DESILTING AND REMOVAL OF HYACINTH PLANT AT GANGAIAMMAN KULAM IN DIV-187, U-42, Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/13370,Buildings,Completed,NP-PERUNGUDI,187,990000,"CONSTRUCTION OF NAMMA TOILET FOR (2+1) AT KARTHIKEYAPURAM YERIKARAI ROAD SIDE, IN DIV.187, U-42, Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/1366,Buildings,Completed,NP-PERUNGUDI,187,656000,"PROVIDING BARRICADING TABLES AND CHAIRS ARRANGEMENTS AND SHAMIYANA PANDAL BOOTHS AT ANGANVADI FOR ASSEMBLY ELECTION 2016 IN DN-187,UNIT-42,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/1662,Storm Water Drain,Completed,NP-PERUNGUDI,187,380000,"DESILTING OF SIDE DRAIN, STROM WATER DRAIN AND CANAL (35 ) STREETS IN DN-187, U-42,Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/16910,Buildings,Completed,NP-PERUNGUDI,187,668000,"REPAIRS AND MAINTENANCE WORKS OF AMMA UNAVAGAM DAMAGES DUE TO VARDAH CYCLONE AT LAKE VIEW MAIN ROAD IN DN-187, U-42, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/1877,Storm Water Drain,Completed,NP-PERUNGUDI,187,980000,"IMPROVEMENTS TO SIDE DRAIN AT ESWARAN KOIL MAIN ROAD (FROM PONNIAMMAN KOIL STREET TO ESWARANKOIL TEMPLE) IN DN-187, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/1958,Storm Water Drain,Completed,NP-PERUNGUDI,187,970000,"IMPROVEMENTS TO SIDE DRAIN AT PONNIAMMAN KOIL STREET (FROM KARTHIKEYAPURAM 3RD STREET TO ESWARAN KOIL MAIN ROAD) IN DN-187, U-42,Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/1964,Storm Water Drain,Completed,NP-PERUNGUDI,187,990000,"IMPROVEMENTS TO SIDE DRAIN AT ESWARAN KOIL MAIN ROAD ( FROM BAJANAI KOIL STREET TO ESWARAN KOIL TEMPLE) IN DN-187,U-42,Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/9258,Roads,Completed,NP-PERUNGUDI,187,828000,Laying of the Bituminous road using mechanical paver finisher at sankaran street in Dn -187 U-42 Z-14,Own Sources,14,2016-17,2017-18 NP/2016-17/9260,Roads,Completed,NP-PERUNGUDI,187,1729000,Laying of the Bituminous road using mechanical paver finisher at gopal street in Dn -187 U-42 Z-14,Own Sources,14,2016-17,2017-18 NP/2016-17/9262,Roads,Completed,NP-PERUNGUDI,187,237000,Laying of the Bituminous road using mechanical paver finisher at kalaivani street in Dn -187 U-42 Z-14,Own Sources,14,2016-17,2017-18 NP/2016-17/9263,Roads,Completed,NP-PERUNGUDI,187,386000,Laying of the Bituminous road using mechanical paver finisher at New kubera nagar 3rd street in Dn -187 U-42 Z-14,Own Sources,14,2016-17,2017-18 NP/2016-17/9264,Roads,Completed,NP-PERUNGUDI,187,1036000,Laying of the Bituminous road using mechanical paver finisher at Karthikeya puram 11th street in Dn -187 U-42 Z-14,Own Sources,14,2016-17,2017-18 NP/2016-17/9265,Roads,Completed,NP-PERUNGUDI,187,550000,Laying of the Bituminous road using mechanical paver finisher at Deivanai nagar 1st street in Dn -187 U-42 Z-14,Own Sources,14,2016-17,2017-18 D/2016-17/11409,Storm Water Drain,Completed,D-Storm Water Drains,188,950000,"Providing and fixing of Fencing by using R C C Precast post and 3' X 3 PVC coated Chain link fencing at Mylai Balaji Canal at both side in Dn -188, Zone XIV.",Own Sources,14,2016-17,2016-17 L/2016-17/13768,Electrical,Completed,L-Electrical,188,975300,"Supply and fixing of 8nos of LED flood light fitting of 240 W to 300 W with 7 years replacement guarantee Fitting at Kaiveli Junction Div 188, Zone-14",Own Sources,14,2016-17,2018-19 L/2016-17/13795,Electrical,Completed,L-Electrical,188,193300,"Provision of 12 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-188, Zone-XIV",Own Sources,14,2016-17,2017-18 L/2016-17/13802,Electrical,Completed,L-Electrical,188,121000,"Shifting and raising of 16 nos Pillar boxes and painting of 300 nos of post and 16 pillars At Various Locations In Div-188, Zone-XIV",Own Sources,14,2016-17,2017-18 L/2016-17/7208,Electrical,Completed,L-Electrical,188,736100,"Erection of 5nos of 6 Mtr lamp post with Single Arch Bracket with 5 nos of 150w-165w LED Fitting, 3nos of 6 Mtr lamp post with Double Arch Bracket with 6 nos of 90w-120w LED Fitting, 2nos of 6 Mtr lamp post with Triple Arch Bracket with 6 nos of 90w-120w LED Fitting at Kaiveli to Bazzar Road in Division-188, Zone-XIV",Own Sources,14,2016-17,2016-17 L/2016-17/7215,Electrical,Completed,L-Electrical,188,898600,"Erection of 3nos of 6 Mtr lamp post with Single Arch Bracket with 1 nos of 150w-165w LEDand 2 nos of 90w-120w LED Fitting, Fitting, 6nos of 6 Mtr lamp post with Double Arch Bracket with 12 nos of 90w-120w LED Fitting, 1no of 6 Mtr lamp post with Triple Arch Bracket with 3 nos of 90w-120w LED Fitting at Madipakkam Bazzar Road in Division-188, Zone-XIV",Own Sources,14,2016-17,2016-17 NP/2016-17/14079,Buildings,Completed,NP-PERUNGUDI,188,18500,"REPAIRS AND IMPROVEMENTS WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 1ST BLOCK PC NO-1 IN DN-188 ,U-42, Z-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/14084,Buildings,Completed,NP-PERUNGUDI,188,18800,"REPAIRS AND IMPROVEMENT WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 1ST BLOCK PC NO-2 IN DN- 188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/14088,Buildings,Completed,NP-PERUNGUDI,188,19000,"REPAIRS AND IMPROVEMENTS WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 2ND BLOCK PC NO-1 IN DN-188, U-42, Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/14091,Buildings,Completed,NP-PERUNGUDI,188,18700,"REPAIRS AND IMPROVEMENTS WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 2ND BLOCK PC NO-2 IN DN -188,U-42,Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/14133,Buildings,Completed,NP-PERUNGUDI,188,80400,"REPAIRS AND IMPROVEMENTS WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 2ND BLOCK PC NO-3 IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/14156,Buildings,Completed,NP-PERUNGUDI,188,79000,"REPAIRS AND IMPROVEMENTS WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 2ND BLOCK PC NO-4 IN DN-188, U-42,Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/14162,Buildings,Completed,NP-PERUNGUDI,188,80200,"REPAIRS AND IMPROVEMENTS WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 3RD BLOCK PC NO-1 IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/14168,Buildings,Completed,NP-PERUNGUDI,188,77300,"REPAIRS AND IMPROVEMENT WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 3RD BLOCK PC NO-2 IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/14169,Buildings,Completed,NP-PERUNGUDI,188,25500,"REPAIRS AND IMPROVEMENT WORKS OF PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 4TH BLOCK PC NO-1 IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/14173,Buildings,Completed,NP-PERUNGUDI,188,35800,"REPAIRS AND IMPROVEMENT WORKS AT PUBLIC CONVENIENCE AT MYLLAI BALAJI NAGAR 4 TH BLOCK PC NO-2 IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/1448,Electrical,Completed,NP-PERUNGUDI,188,555500,"PROVISION OF 12 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKER WITH 40W - 50W LED FITTING WITH HOT DIP ZINC GALVANISHING AT DR. RAMAMOORTHI NAGAR PARK IN DN - 188, U - 42, Z - 14",Own Sources,14,2016-17,2016-17 NP/2016-17/15117,Roads,Completed,NP-PERUNGUDI,188,375000,"CONSTRUCTION OF TOILET AND APPROACH ROAD WITH INTERLOCKING BLOCKS TO DISPENSARY (UPHC) AT MADIPAKKAM BUS STAND IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/15118,Roads,Completed,NP-PERUNGUDI,188,490000,"PROVIDING DUSTBIN PLATFORM AT VARIOUS STREET IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/15127,Buildings,Completed,NP-PERUNGUDI,188,460000,"REPAIRS TO TOILET BLOCK AND OTHER IMPROVEMENT WORKS TO CMS SCHOOL AT MYLAI BALAJI NAGAR IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/15131,Buildings,Completed,NP-PERUNGUDI,188,930000,"REPAIRS TO TOILET BLOCK AND OTHER MAINTENANCE WORKS TO SCHOOL BUILDING AT KULAKARAI STREET IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/16267,Buildings,Completed,NP-PERUNGUDI,188,703000,"REPAIRS AND MAINTENANCE WORKS AT DR.RAMAMOORTHY NAGAR PARK IN DIV-188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/16412,Buildings,Completed,NP-PERUNGUDI,188,43000,"VARDHA CYCLONE DAMAGED WORK IN AMMA UNAVAGAM IN MADIPAKKAM BUS STAND IN DN-188,UNIT-42,ZONE-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/1665,Storm Water Drain,Completed,NP-PERUNGUDI,188,930000,"DESILTING OF CANAL IN BETWEEN MYLLAI BALAJI NAGAR 1ST BLOCK AND 2ND BLOCK, MYLLAI BALAJI NAGAR 3RD BLOCK AND 4TH BLOCK FOR FLOOD WORK IN DN-188, U-42,Z-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/16667,Roads,Completed,NP-PERUNGUDI,188,547000,"Construction of Storm Water Drain of size 600x750 mm at Mylai balaji nagar 2nd Block and Construction of Culvert at Dr.Ambedkar salai main road and mylai balaji nagar 2nd block in Dn-188,Unit -42, Zone -XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/1671,Storm Water Drain,Completed,NP-PERUNGUDI,188,215000,"DESILTING OF SIDE DRAIN AT VARIOUS STREET (39 NOS) IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17529,Roads,Completed,NP-PERUNGUDI,188,310000,"ATTENDING PATCHWORK AT DR.AMBEDKAR SALAI,KARPAGAMBAL NAGAR MAIN ROAD, SADHASHIVAM NAGAR 4TH CROSS STREET, PERIYAR NAGAR EXTN II 7TH STREET, RAMNAGAR 5TH CROSS STREET, LAKSHMI NAGAR MAIN ROAD,LIC NAGAR 4TH MAINROAD, ARUL MURUGAN NAGAR IN DN-188,UNIT-42,ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17826,Roads,Completed,NP-PERUNGUDI,188,2990000,"PROPOSED COMPOST YARD AT PALLIKARANAI OLD DUMPING GROUND IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/18079,Bridges,Completed,NP-PERUNGUDI,188,2970000,"PROPOSED COMPOST YARD ON WEST SIDE AT PALLIKARANAI OLD DUMPING GROUND IN DN-188,U-42,Z-14",Own Sources,14,2016-17,2018-19 NP/2016-17/1866,Storm Water Drain,Completed,NP-PERUNGUDI,188,683000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREETS (51 STREETS) IN DN-188,U-42,Z-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/18737,Buildings,Completed,NP-PERUNGUDI,188,100000,"REPAIRS AND MAINTENANCE IN MYLAI BALAJI NAGAR 2nd BLOCK P.C.No.04 IN DN-188,UNIT-42,ZONE-14",Own Sources,14,2016-17,2018-19 NP/2016-17/19232,Buildings,Completed,NP-PERUNGUDI,188,1490000,"CONSTRUCTION OF ANGANWADI AT MYLLAI BALAJI NAGAR 1ST BLOCK IN DN-188,U-42,Z-14",MLACDS,14,2016-17,2018-19 NP/2016-17/19366,Buildings,Completed,NP-PERUNGUDI,188,1490000,"CONSTRUCTION OF ANGANWADI AT MYLLAI BALAJI NAGAR 4TH BLOCK IN DN-188, U-42,Z-14",MLACDS,14,2016-17,2018-19 NP/2016-17/3132,Electrical,Completed,NP-PERUNGUDI,188,550200,"PROVISION OF 12 NOS OF 6 MTR LAMP POST WITH SINGLE STRAIGHT BRACKER WITH 40W - 50W LED FITTING WITH HOT DIP ZINC GALVANISHING AT RAJESH NAGAR PARK IN DN - 188, U - 42, Z - 14",Own Sources,14,2016-17,2017-18 NP/2016-17/4392,Roads,Completed,NP-PERUNGUDI,188,998000,"PROVIDING STREET NAME BOARD AT ANNA NAGAR 1ST STREET TO 11TH STREET, DR.RAMAMURTHY NAGAR AND SENTHIL NAGAR, MYLLAI KABALEESWARAR NAGAR AND VARIOUS OTHER STREETS IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/4396,Roads,Completed,NP-PERUNGUDI,188,998000,"PROVIDING STREET NAME BOARD AT SADHASIVAM NAGAR, THILAKAR AVENUE, KUBERAN NAGAR 1 ST STREET TO 4TH STREET AND VARIOUS OTHER STREETS IN DN-188, U-42, Z-14",Own Sources,14,2016-17,2017-18 NP/2016-17/4512,Road Cut,Completed,NP-PERUNGUDI,188,977000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT RAM NAGAR SOUTH FROM SADHASIVAM NAGAR 6TH MAIN ROAD IN DIVISION 188, UNIT 42, ZONE 14.",Deposit Works,14,2016-17,2017-18 NP/2016-17/4522,Road Cut,Completed,NP-PERUNGUDI,188,980000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT RAM NAGAR SOUTH FROM RAM NAGAR 8TH CROSS STREET ROAD IN DIVISION 188, UNIT 42, ZONE 14.",Deposit Works,14,2016-17,2017-18 NP/2016-17/4523,Road Cut,Completed,NP-PERUNGUDI,188,990000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT RAM NAGAR SOUTH FROM RAM NAGAR 6TH STREET ROAD IN DIVISION 188, UNIT 42, ZONE 14.",Deposit Works,14,2016-17,2017-18 NP/2016-17/4641,Storm Water Drain,Completed,NP-PERUNGUDI,188,980000,"IMPROVEMENTS TO R.C.C ROAD CROSSING CULVERTS AT PARTHASARATHY STREET (9 NOS) AND MUTHU MARIAMMAN KOIL STREET IN DN-188,U-42,Z-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/4643,Storm Water Drain,Completed,NP-PERUNGUDI,188,980000,"IMPROVEMENTS TO R.C.C ROAD CROSS CULVERT AT SADASIVAM NAGAR 3RD CROSS STREET,L.I.C NAGAR, SRI NAGAR 6TH STREET, RAJESH NAGAR 1STMAIN ROAD, ENFIELD AVENUE, TAI NAGAR AND GOVINDAN STREET IN DN-188,U-42,Z-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/5244,Buildings,Completed,NP-PERUNGUDI,188,990000,"CONSTRUCTION OF AMMA CANTEEN AT MYLLAI BALAJI NAGAR 3RD BLOCK IN DN-188, U-42, Z-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/5272,Buildings,Completed,NP-PERUNGUDI,188,990000,"CONSTRUCTION OF KITCHEN STORE ROOM, TOILET AND PROVIDING WATER SUPPLY ARRANGEMENT TO AMMA UNAVAGAM AT MYLLAI BALAJI NAGAR 3RD BLOCK IN DN-188, U-42, Z-14.",Own Sources,14,2016-17,2016-17 NP/2016-17/7778,Buildings,Completed,NP-PERUNGUDI,188,990000,"PROPOSED CONSTRUCTION OF AMMA UNAVAGAM AT MAHALAKSHMI NAGAR IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/7779,Buildings,Completed,NP-PERUNGUDI,188,995000,"CONSTRUCTION OF KITCHEN, STORE ROOM AND TOILET TO AMMA UNAVAGAM AT MAHALAKSHMI NAGAR IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/7781,Buildings,Completed,NP-PERUNGUDI,188,980000,"CONSTRUCTION OF SEPTIC TANK AND OTHER ARRANGEMENTS TO AMMA UNAVAGAM AT MAHALAKSHMI NAGAR IN DIVISION 188, UNIT 42, ZONE 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/8787,Roads,Completed,NP-PERUNGUDI,188,925000,"LAYING OF BT ROAD AT KUBERAN NAGAR EXTN 10TH STREET (FROM KUBERAN NAGAR MAIN ROAD TO PLOT NO-298 A) IN DN-188,U-42, Z-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/8822,Roads,Completed,NP-PERUNGUDI,188,925000,"LAYING OF BT ROAD AT KUBERAN NAGAR EXTN 10 STREET (FROM PLOT NO-298 TO PLOT NO- 294) IN DN-188, U-42, Z-14.",Own Sources,14,2016-17,2018-19 NP/2016-17/9728,Roads,Completed,NP-PERUNGUDI,188,995000,"Providing interlocking blocks flooring in approach road to C.M.S School at Myllai Balaji Nagar 2nd.block in Division 188, Unit 42, Zone 14.",Own Sources,14,2016-17,2017-18 L/2016-17/13800,Electrical,Completed,L-Electrical,189,193300,"Provision of 12 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-189, Zone-XIV",Own Sources,14,2016-17,2017-18 L/2016-17/18134,Electrical,Completed,L-Electrical,189,158800,"Restoration of Damaged posts in various locations in Dn-189 pallikaranai in Zone-XIV, due to Vardha cyclone effect on 12-12-16 .",Own Sources,14,2016-17,2020-21 NP/2016-17/15104,Buildings,Completed,NP-PERUNGUDI,189,485000,Construction of Multipurpose Hall at Thamarai Kulam in Dn 189 Unit 43 Zone XIV,Own Sources,14,2016-17,2016-17 NP/2016-17/15112,Buildings,Completed,NP-PERUNGUDI,189,415000,"PROVIDING INTER LOCKING TILES, RAIN WATER DISPOSAL ARRANGEMENTS AND ADDITIONAL IMPROVEMENTS TO BIO GAS PLANT IN AMMA UNAVAGAM AT MADA VEETHI STREET IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/15115,Buildings,Completed,NP-PERUNGUDI,189,470000,"REPAIRS TO TOILET BLOCK AND OTHER IMPROVEMENTS TO UNIT OFFICE 43 AT THULUKANATHAMMAN KOIL STREET IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/15162,Buildings,Completed,NP-PERUNGUDI,189,502000,"Providing deep borewell at VGP Shanthi nagar park , Kamakotti nagar 4 th street play ground ,Shopping complex at Thulukanathamman Koil street and providing Tiles for entrance to Nazza Kulam in Thulukanathamman Koil street IN DIVISION 189, UNIT 43, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/1626,Electrical,Completed,NP-PERUNGUDI,189,951500,Provision and erection of 16 nos 6 mtr hot dip galvanising lamp post with Single Straight bracket with 40-50W LED fittings and 4 nos of 6 mtr hot dip galvanising lamp post without bracket with 250w MH FL fitting at VGP Shanthi nagar park in Div 189 Zone XIV,Own Sources,14,2016-17,2016-17 NP/2016-17/1627,Electrical,Completed,NP-PERUNGUDI,189,752000,Provision and erection of 12 nos 6 mtr hot dip galvanising lamp post with Single Straight bracket with 40-50W LED fittings and 2 nos of 6 mtr hot dip galvanising lamp post without bracket with 250w MH FL fitting at VGP Shanthi nagar playground in Div 189 Zone XIV,Own Sources,14,2016-17,2016-17 NP/2016-17/16674,Roads,Completed,NP-PERUNGUDI,189,1123000,"Repairs to damaged footpath , play apparatus and chairs at VGP Shanthi nagar Park,Arumugam nagar Park,Kamakotti nagar park,IIT Colony Park,Kamakotti nagar Play Ground and Thamarai Kulam due to VARDAH CYCLONE in Dn 189, Unit-43, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/16685,Buildings,Completed,NP-PERUNGUDI,189,68000,"Repairs to Amma Unavagam at Mada Veethi and Thulukanathamman Koil street damaged due to VARDAH CYCLONE in Dn 189, Unit-43, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/16686,Buildings,Completed,NP-PERUNGUDI,189,100000,"Repairs to Unit Office Store room at 2 nd Floor at Thulukanathamman Koil street damaged due to VARDAH CYCLONE in Dn 189, Unit-43, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17416,Roads,Completed,NP-PERUNGUDI,189,950000,"ATTENDING CEMENT CONCRETE PATCH WORK AT MEENATCHIPURAM 2ND STREET,V.G.P SHANTHI NAGAR VALLALAR STREET,Dr.AMBEDKAR STREET,LABOUR COLONY MAIN ROAD ,MERU NAGAR 4TH CROSS STREET,MANOKAR NAGAR 1ST MAIN ROAD AND VARIOUS STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/18902,Buildings,Completed,NP-PERUNGUDI,189,2656000,"PROPOSED COMPOST YARD AT MALLIKESWARAN NAGAR BURIAL GROUND THULUKANATHAMMAN KOIL STREET IN DIVISION-189,UNIT-43,ZONE-14",Own Sources,14,2016-17,2018-19 NP/2016-17/1968,Storm Water Drain,Completed,NP-PERUNGUDI,189,315000,"Desilting of side and storm water drain at Pallikarani,dn-189,unit-43,zone-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/3056,Storm Water Drain,Completed,NP-PERUNGUDI,189,990000,"Proposed construction of RCC Road crossing Culverts at THULUKANATHAMMAN KOIL MAIN ROAD,ARUUMUGAM NAGAR 2ND STREET,MANOKAR NAGAR MAIN ROAD,V.G.P SHANTHI NAGAR-V.O.C STREET,MEENATCHIPURAM 1ST STREET, MEENATCHIPURAM 2ND STREET, PERIYAR NAGAR-RAMALINGA ADIKALAR STREET,PERUMAL KOIL STREET,I.I.T COLONY 4TH STREET in DN-189,UNIT-43,ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/3257,Buildings,Completed,NP-PERUNGUDI,189,930000,"Providing and Laying of Granular Sub Base (GSB), Quarry dust at Kalidasar Street, Meenatchi Puram 2nd cross street, Kamatchi Colony 3rd cross street, Rajalakshmi Nagar 2nd main road cross street and Attending Cement Concrete patchwork at various streets in Division 189, Unit 43, Zone 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/3858,Buildings,Completed,NP-PERUNGUDI,189,990000,"CONSTRUCTION OF AMMA CANTEEN AT THULUKANATHAMMAN KOIL MAIN ROAD IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/3926,Parks,Completed,NP-PERUNGUDI,189,700000,Providing water supply arrangements and fixing Play Apparatus to Astalakshmi Nagar Park in Dn 189 Unit 43 Zone XIV ( Under Ward Counciller Development Fund),Own Sources,14,2016-17,2017-18 NP/2016-17/3927,Parks,Completed,NP-PERUNGUDI,189,890000,Forming pathway to Astalakshmi Nagar Park in Dn 189 Unit 43 Zone XIV ( Under Ward Councillor Development Fund),Own Sources,14,2016-17,2017-18 NP/2016-17/5226,Buildings,Completed,NP-PERUNGUDI,189,990000,"CONSTRUCTION OF KITCHEN STORE ROOM, TOILET AND PROVIDING WATER SUPPLY ARRANGEMENT TO AMMA UNAVAGAM AT THULUKANATHAMMAN KOIL MAIN ROAD IN DIVISION-189 UNIT-43 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/7534,Buildings,Completed,NP-PERUNGUDI,189,990000,"Proposed Construction of Multipurpose Hall (Near) Amma Unavagam at Thulukanathamman koil Main Road in DN-189, UNIT-43, ZONE-14",Own Sources,14,2016-17,2016-17 L/2016-17/13806,Electrical,Completed,L-Electrical,190,193300,Provision of 12 Nos of 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units At Various Locations In Div-187 and 190. Zone-XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/13120,Buildings,Completed,NP-PERUNGUDI,190,920000,PROVIDING ALUMINUM PARTITION AND OTHER IMPROVEMENT WORK AT AMMA UNAVAGAM SUNABU KOLATHUR MAIN ROAD IN DIVISION-190 UNIT-43 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/13456,Buildings,Completed,NP-PERUNGUDI,190,920000,"CONSTRUCTION OF STORE ROOM INSIDE THE OFFICE NEAR AMMA UNAVAGAM IN DIVISION-190, UNIT-43, ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/14317,Buildings,Completed,NP-PERUNGUDI,190,424000,IMPROVEMENT TO CI ROOM AND GUDOWN NEAR AMMA UNAVAGAM IN DIVISION-190 UNIT-43 ZONE-14,Own Sources,14,2016-17,2017-18 NP/2016-17/14513,Buildings,Completed,NP-PERUNGUDI,190,25000,"REPAIRS AND IMPROVEMENTS OF 3 NOS. OF PUBLIC CONVENIENCES (KOVALAN NAGAR MAIN ROAD, KANNAPIRAN KOIL STREET AND KARMEL STREET) IN DN-190, ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/15157,Roads,Completed,NP-PERUNGUDI,190,926000,"Supplying and Fixing Street Furniture at Ganapathy nagar ( 4 nos), Sri Ambal nagar ( 24 nos),Devi Karumari Amman nagar ( 6 nos ) and various other streets 8 nos and City Limit boards 2 nos in Division 190, Unit 43, Zone 14.",Own Sources,14,2016-17,2016-17 NP/2016-17/15983,Buildings,Completed,NP-PERUNGUDI,190,357000,"PROVIDING PLATFORM, ELECTRICAL,WATER SUPPLY AND OTHER IMPROVEMENTS TO TOILET BLOCK NEAR AMMA UNAVAGAM, SUNAMBU KOLATHUR MAIN ROAD IN DIVISION-190 UNIT-43 ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17249,Buildings,Completed,NP-PERUNGUDI,190,46000,Repairs to Dn Office 190 at Velachery-Thambaram Main road due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17250,Roads,Completed,NP-PERUNGUDI,190,544000,"Attending Cement Concrete Patchwork at Vivekanandar Street, Chitti Babu Nagar Main Road Thiruvalluvar 2nd Street, Kannabiran Koil Street, Kannabiran Koil Street Extn, Perumal Koil Street, Sree Nagar Extn (3rd street), Ambal Nagar Main Road, Bhavani Amman Koil Street in Dn-190, Unit-43, Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/17256,Buildings,Completed,NP-PERUNGUDI,190,190000,Repairs to old and new Conservency Godown in 190 at Velachery-Thambaram Main road due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17263,Buildings,Completed,NP-PERUNGUDI,190,29000,Repairs to Amma Unavagam at Velachery-Thambaram Main road due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17268,Buildings,Completed,NP-PERUNGUDI,190,28000,Repairs to Amma Unavagam at S.Kolathur road due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17271,Buildings,Completed,NP-PERUNGUDI,190,16000,Repairs to Kovalan Nagar PC due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17273,Buildings,Completed,NP-PERUNGUDI,190,283100,Repairs to the PVC Coated Chain Link fencing at Thandukarai Kulam due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17311,Parks,Completed,NP-PERUNGUDI,190,363000,Construction of compound wall damaged at Dr.Ambedkar Park due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17323,Parks,Completed,NP-PERUNGUDI,190,530000,Construction of compound wall damaged at Chettinad Enclave Park-1 due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/17330,Parks,Completed,NP-PERUNGUDI,190,653000,construction of compound wall and Pathway damaged at Chettinad Enclave Park-2 due to VARADAH CYCLONE in 190 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/1947,Storm Water Drain,Completed,NP-PERUNGUDI,190,140000,"Desilting of side and storm water drain at Pallikarani,dn-190,unit-43,zone-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/3748,Buildings,Completed,NP-PERUNGUDI,190,990000,CONSTRUCTION OF AMMA CANTEEN AT SUNAMBU KOLATHUR MAIN ROAD IN DIVISION-190 UNIT-43 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/4917,Buildings,Completed,NP-PERUNGUDI,190,990000,"CONSTRUCTION OF KITCHEN STORE ROOM , TOILET AND PROVIDING WATER SUPPLY ARRANGEMENT TO AMMA UNAVAGAM AT SUNABU KOLATHUR MAIN ROAD IN DIVISION-190 UNIT-43 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/7108,Buildings,Completed,NP-PERUNGUDI,190,997000,CONSTRUCTION OF TOILET BLOCK NEAR AMMA UNAVAGAM AT SUNABU KOLATHUR ROAD IN DIVISION-190 UNIT-43 ZONE-14,Own Sources,14,2016-17,2016-17 NP/2016-17/7579,Footpath,Completed,NP-PERUNGUDI,190,990000,"PROVIDING FOOT PATH AND FRP BENCHES TO THUNDUKARAI KULAM EAST AND SOUTH SIDE OF WALKERS PATH IN DN-190,UNIT-43,ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/7582,Footpath,Completed,NP-PERUNGUDI,190,990000,PROVIDING FOOT PATH AND FRP BENCHES TO THUNDUKARAI KULAM WEST AND NORTH SIDE SIDE OF WALKERS PATH IN DN-190 U- 43 Z-14,Own Sources,14,2016-17,2017-18 NP/2016-17/7665,Roads,Completed,NP-PERUNGUDI,190,926000,"LAYING PAVER BLOCK AT KAKKAYI 1STREET, 2ND STREET AND 3RD STREET AND VARIOUS STREET IN DIVISION-190 UNIT-43 ZONE-14",Own Sources,14,2016-17,2016-17 NP/2016-17/0845,Electrical,Completed,NP-PERUNGUDI,191,490000,"Provision of 10nos of 6 mtr G.I lamp post with straight bracket with 40-50W LED street light fittings set at GREEN COURT in Div 191,Jalladanpettai Zone XIV",Deposit Works,14,2016-17,2016-17 NP/2016-17/10804,Roads,Completed,NP-PERUNGUDI,191,815000,"Providing and Laying for cement concrete Road at Lakshmi Nagar 1st street in DN-191,UNIT-43,ZONE-14 (Ward councilor fund 2016-17)",Own Sources,14,2016-17,2017-18 NP/2016-17/11715,Roads,Completed,NP-PERUNGUDI,191,225000,"Providing and laying for cement concrete Road at Pari Vallal street in DN-191,UNIT-43,ZONE-14 (Ward councilar fund 2016-17)",Own Sources,14,2016-17,2017-18 NP/2016-17/11718,Roads,Completed,NP-PERUNGUDI,191,270000,"Providing and laying for cement concrete Road at Periyar street in DN-191,UNIT-43,ZONE-14 (Ward councilar fund 2016-17)",Own Sources,14,2016-17,2017-18 NP/2016-17/15092,Buildings,Completed,NP-PERUNGUDI,191,112500,Providing grill to the existing compound wall at the GYM in Pillayar Koil street in Dn 191 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/15095,Roads,Completed,NP-PERUNGUDI,191,103000,"Repairs to Catch pit,painting the chute pipe locations at Pillayar Koil street ,Rice Mill road,Veerathamman Koil street and Anna Salai in Dn 191 Unit 43 Zone XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/16587,Parks,Completed,NP-PERUNGUDI,191,345000,"Repairs to Jayachandran Park damaged due to VARADAH CYCLONE in DN-191, Unit 43 ,Zone -14",Own Sources,14,2016-17,2017-18 NP/2016-17/16603,Buildings,Completed,NP-PERUNGUDI,191,112000,"Repairs to Division Office 191 damaged due to VARADAH CYCLONE in DN- 191 ,Unit 43, ������������������Zone-14",Own Sources,14,2016-17,2017-18 NP/2016-17/16609,Buildings,Completed,NP-PERUNGUDI,191,49000,"Repairs to Amma Unavagam at Rice Mill road, damaged due to VARADAH CYCLONE in 191 Unit 43 Zone XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/16615,Roads,Completed,NP-PERUNGUDI,191,340000,"Repairs to damaged road due to VARADAH CYCLONE in DN-191, Unit 43, Zone 14",Own Sources,14,2016-17,2017-18 NP/2016-17/17348,Buildings,Completed,NP-PERUNGUDI,191,780000,Construction of Damaged Compound wall at Madambakkam Leprasy Hospital due to VARADAH CYCLONE in 191 Unit 43 Zone XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/18922,Buildings,Completed,NP-PERUNGUDI,191,2656000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT PUTHU NAGAR BURIAL GROUND PUTHU NAGAR 5TH STREET IN DIVISION-191,UNIT-43,ZONE-14",Own Sources,14,2016-17,2017-18 NP/2016-17/1969,Storm Water Drain,Completed,NP-PERUNGUDI,191,215000,"Desilting of side and storm water drain at Jalladianpet,dn-191,unit-43,zone-14.",Own Sources,14,2016-17,2017-18 NP/2016-17/3592,Electrical,Completed,NP-PERUNGUDI,191,671500,Supply & Erection of 12Nos of 6mtr Lamp Post with 90-120W LED Fitting at Saiganesh Nagar Jalladampettai Burial Ground in Div 191 in Zone XIV.,Own Sources,14,2016-17,2016-17 NP/2016-17/3594,Electrical,Completed,NP-PERUNGUDI,191,998000,"Provision of 18Nos of 6mtr HOT DIP Lamp Post with 90-120W LED Fitting at JayaChandra Nagar Park 5th street,Jalladampettai in Div 191 in Zone XIV.",Own Sources,14,2016-17,2016-17 NP/2016-17/6783,Storm Water Drain,Completed,NP-PERUNGUDI,191,140000,Raising and covering the side drain at Veerthamman Koil street from Gandhi street to Veerathamman Koil West street on West side in Dn 191 Unit-43 Zone- XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/6785,Buildings,Completed,NP-PERUNGUDI,191,132000,"Repairs and Maintenance to Compound wall at Health Centre ,Thiruvaluuvar nagar in Dn 191 Unit-43 Zone- XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/6786,Buildings,Completed,NP-PERUNGUDI,191,96000,"Providing wall tiles, Interlocking slab etc to Anganwadi at Thiruvalluvar nagar and Jayanthi Natarajan street in Dn 191 Unit-43 Zone- XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/8239,Roads,Completed,NP-PERUNGUDI,191,330000,"Forming road at Mahaveer street Extn IN DIVISION 191, UNIT 43, ZONE 14.",Own Sources,14,2016-17,2017-18 NP/2016-17/8295,Roads,Completed,NP-PERUNGUDI,191,995000,"Providing and laying for cement concrete Road at Nesavallar Nagar -Kalaignar street in DN-191,UNIT-43,ZONE-14 (Ward councilar fund 2016-17)",Own Sources,14,2016-17,2017-18 NP/2016-17/8410,Roads,Completed,NP-PERUNGUDI,191,695000,"Providing and Laying for cement concrete Road at Vidya School Road in DN-191,UNIT-43,ZONE-14 (Ward councilor fund 2016-17)",Own Sources,14,2016-17,2017-18 NP/2016-17/9626,Buildings,Completed,NP-PERUNGUDI,191,304000,"Repairs and Improvements to CMS at Veerathamman Koil street ( Block-1,2 and Toilet ) in Dn 191 Unit-43 Zone- XIV",Own Sources,14,2016-17,2017-18 NP/2016-17/9633,Roads,Completed,NP-PERUNGUDI,191,382000,Providing and laying Paver Blocks at Rice Mill road and Pillayar Koil street in Dn 191 Unit-43 Zone- XIV,Own Sources,14,2016-17,2017-18 NP/2016-17/9634,Buildings,Completed,NP-PERUNGUDI,191,108000,Construction of platform for Dust Bins at Various streets in Dn 191 Unit-43 Zone- XIV,Own Sources,14,2016-17,2017-18 L/2016-17/13280,Electrical,Completed,L-Electrical,192,114500,The painting of 383 nos of 6 mtr single arch bracket street lamp post and numbering of 2246 street lamp post in various streets in Dn 192 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13281,Electrical,Completed,L-Electrical,192,170500,The painting of 1127 nos of 6 mtr single straight bracket street lamp post & 35 numbers of pillar box painting in various streets in Dn 192 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13575,Electrical,Completed,L-Electrical,192,193300,Supply and fixing of 12 No of Automatic street light on /off Timer complet set in Dn 192/193/194/195/196/199-variouse locations in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13576,Electrical,Completed,L-Electrical,192,199500,"Erection of 30 old 6 mtr street lamp posts and 100 nos of new plane cement concrete pedestal for street lamp post ,which haven been removed due to strom water work and aging in saraswaty nagar south ,Bharathiyar nagar, rajendra nagar ,Aringar anna nagar ,ramalinga nagar vgp layout and variouse street in Dn 192 /196/199 in Zone-XV.",Own Sources,15,2016-17,2017-18 L/2016-17/13898,Electrical,Completed,L-Electrical,192,186900,Replacement of 660mtr of 2X16 Sqmm Alu old cable in Saraswathy nagar south and Kumaraguru avenue due to strom water work and aging in Dn 192 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13899,Electrical,Completed,L-Electrical,192,198300,Replacement of 660mtr of 2X16 Sqmm Alu old cable in Kumaraguru avenue cross street due to strom water work and aging and erection of 2 no of street light post in ECR Dn 192/196 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/18128,Electrical,Completed,L-Electrical,192,1633800,Restoration of damaged post and kiosk pillar boxes in dn 192- 200due to vardha cyclon on 12.12.16,Own Sources,15,2016-17,2017-18 L/2016-17/18716,Electrical,Completed,L-Electrical,192,199000,Replacement of damaged 591mtr of 4X25 Sqmm Alu cable to 591mtr of 4X16 Sqmm Alu cable in pandian salai due to strom water work in NeelanKari Dn 192 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/18740,Electrical,Completed,L-Electrical,192,198500,The painting of 24 no of 8 Mtr street lamp post with 2.7 Mtr Arch triple bracket and 178 nos of 8 Mtr street lamp post with 2.7 Mtr Arch triple bracket in ECR Main road and Replacement of 155 nos of damaged 1 mtr arch bracket in to 155 nos of 1 mtr GI single Curved bracket in EL post of Sea Shore Service roads in DN 192/196/198/199 in zone -15,Own Sources,15,2016-17,2017-18 NQ/2016-17/0884,Buildings,Completed,NQ-SHOZHINGANALLUR,192,280000,"PROVIDING RAIN WATER HARVESTING AT E.C.R NEELANKARAI BUHARI HOTEL , RK INDUSTRIES, AND NARAYANASWAMI SCHOOL IN DIVISION 192 UNIT 44 ZONE 15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/0885,Buildings,Completed,NQ-SHOZHINGANALLUR,192,282000,"PROVIDING RAINWATER HARVESTING AT 192 DIVIISION OFFICE , INSIDE SCHOOL AND IN FRONT OF MAHARASTRA BANK",Own Sources,15,2016-17,2016-17 NQ/2016-17/0964,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,578000,Desilting of Strom water drain at various streets in Dn-192 U-44 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/11664,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,694000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT ELLAIAMMAN KOIL 5TH STREET IN DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/11667,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,694000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT ELLAIAMMAN KOIL 6TH STREET(KALATHUMETTU STREET) IN DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/11668,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,997000,"PROPOSED AND CONSTRUCTION OF SIDE DRAIN AT SURIYA GARDEN(PANDIAN SALAI LINK) IN DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/12201,Roads,Completed,NQ-SHOZHINGANALLUR,192,589000,"PROVIDING AND LAYING HUME PIPE AND IMPROVEMENT OF STORM WATER DRAIN AND CONSTRUCTION OF RAIN WATER HARVESTING AT ECR ROAD LINK SRI KAPALEESHWARAR NAGAR SOUTH 5TH CROSS STREET IN DIVISION 192,UNIT 44,ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/13915,Roads,Completed,NQ-SHOZHINGANALLUR,192,890000,"PROVIDING AND LAYING OF HUME PIPE AND CONSTRUCTION OF INSPECTION CHAMBER AT ECR TO SRI KAPALEESHWARAR NAGAR(SOUTH) 5TH CROSS STREET JUNCTION AND LAYING GSB,WMM AT ELLAIAMMAN KOIL STREET AND PROVIDING LAYING ROAD CROSS HUME PIPE AND RAMP AT CLRI NAGAR AND CONSTRUCTION OF CULVERT AT CHINNA NEELANGARAI IN DN-192,UNIT-45,ZONE-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16534,Roads,Completed,NQ-SHOZHINGANALLUR,192,183000,"REPAIR WORKS TO STREET FURNITURE AT VARIOUS STREETS IN DN 192, U45, Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16539,Parks,Completed,NQ-SHOZHINGANALLUR,192,189000,"Repair work to Workers Estate park due to Vardha Cyclone at Neelangarai in Dn.192, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/18936,Buildings,Completed,NQ-SHOZHINGANALLUR,192,946000,"CONSTRUCTION OF TOILET BLOCK (3+3) SEATER AT PERIYA NEELANGARAI KUPPAM ,NEELANGARAIIN DN-192,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/3596,Buildings,Completed,NQ-SHOZHINGANALLUR,192,141000,REPAIR WORKS TO AMMA CANTEEN AND DESILTING OF RAINWATER HARVESTING AT DIVISION 192 UNIT 44 ZONE15.,Own Sources,15,2016-17,2017-18 NQ/2016-17/3599,Buildings,Completed,NQ-SHOZHINGANALLUR,192,154000,REPAIR WORKS TO ROAD CROSSINGS FOR SIDE DRAINS AT CHINNA NEELANKARAI IN DIVISION 192 UNIT 44 ZONE 15.,Own Sources,15,2016-17,2017-18 NQ/2016-17/3738,Culvert,Completed,NQ-SHOZHINGANALLUR,192,510000,"CONSTRUCTION OF ROAD CROSSING BOX CULVERT AND HUME PIPE LAYING AT SINGARAVELLAN STREET AND CHINNA NEELANGARAI KUPPAM IN DN-192,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/4518,Buildings,Completed,NQ-SHOZHINGANALLUR,192,336000,"Repairs to Storm Water Drain at Various streets in Dn-192, Unit-44, Zone-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/5841,Parks,Completed,NQ-SHOZHINGANALLUR,192,250000,"OUT SOURCING MAINTENANCE OF PARK AT WORKERS ESTATE IN DN 192,UNIT44,ZONE-15 (FOR ONE YEAR)",Own Sources,15,2016-17,2017-18 NQ/2016-17/6209,Electrical,Completed,NQ-SHOZHINGANALLUR,192,998000,Construction of Amma Unavagam using Steel Structure and Corrugated Sheet Cladding at Neelangarai Division Office ECR in Dn-192 U-44 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/6238,Buildings,Completed,NQ-SHOZHINGANALLUR,192,129000,"DEMOLITION OF SHOPS INFRONNT OF DIVISION OFFICE, E C.R IN DIVISION 192 UNIT44 ZONE 15",Own Sources,15,2016-17,2016-17 NQ/2016-17/6610,Buildings,Completed,NQ-SHOZHINGANALLUR,192,114000,providing hume pipe for road crossing and attending patches with cement concrete at kabalieswarar nagar in division 192 unit 44 .,Own Sources,15,2016-17,2017-18 NQ/2016-17/6611,Buildings,Completed,NQ-SHOZHINGANALLUR,192,98000,"PROVIDING ZINC SHEET PARTITION TO FENCE DHOBIKHANA AT ECR IN NEELANGARAI, DN-192, U-44, Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7040,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,653000,"Providing Electrical And Water Supply Arrangements To Amma Unavagam At Neelankarai Division Office, ECR In Dn-192, Unit-44, Zone-15",Own Sources,15,2016-17,2017-18 RS/2016-17/0241,Parks,Completed,P-Parks and Playfields,192,3961100,PROPOSED CONSTRUCTION OF PARK AT RAJA NAGAR IN DIVISION-192 ZONE-XV,Own Sources,15,2016-17,2017-18 L/2016-17/13637,Electrical,Completed,L-Electrical,193,194800,"PAINTING OF 1282 NOS OF 6MTR SINGLE STRAIGHT BRACKET STREET LAMP POST ,10 NOS OF 8MTR LAMP POST WITH DOUBLE ARCH BRACKET AND 3NOS OF 8MTR LAMP POST WITH TRIPLE ARCH BRACKET AND 30 NOS OF PAINTING OF KIOSK PILLART BOX IN DN 193,ZONE 15",Own Sources,15,2016-17,2017-18 L/2016-17/13640,Electrical,Completed,L-Electrical,193,169400,"PROVISION OF 13 NOS OF 6MTR POST REMOVAL AND REFIXING AT VENKATESWARA NAGAR IN DN 193,ZONE 15",Own Sources,15,2016-17,2017-18 L/2016-17/13642,Electrical,Completed,L-Electrical,193,131300,"PAINTING OF 202 NOS OF 6MTR SINGLE ARCH B RTBRACKET STREET LAMP POST IN DN 193 AND N NNUMBERING OF 4312 NOS OF STREET LAMP POST IN DN193,194 AND 195",Own Sources,15,2016-17,2017-18 L/2016-17/13644,Electrical,Completed,L-Electrical,193,172700,"CONSTRUCTION OF NEW PLAIN CEMENT CONCRETE PEDESTAL FOR POSTS DAMAGED DUE TO RUSTING AND SOIL EROSION AT VARIOUS LOCATION IN DN 193,194 AND 195",Own Sources,15,2016-17,2017-18 L/2016-17/13646,Electrical,Completed,L-Electrical,193,186800,"Replacement of damaged cables due to fault at various location in dn 193 ,zone 15",Own Sources,15,2016-17,2017-18 L/2016-17/13649,Electrical,Completed,L-Electrical,193,182900,"REPLACEMENT OF DAMAGED CABLES DUE TO STORM WATER DRAIN AT KARPAGAVINAYAGAR NAGAR IN DN 193,ZONE 15",Own Sources,15,2016-17,2017-18 L/2016-17/18742,Electrical,Completed,L-Electrical,193,168200,Replacement of damaged 594 mtrs of 2Cx25 sq.mm PVC Alu.cable into 2Cx16 sq.mm cables due to storm water drain work at various locations in dn 193 zone 15,Own Sources,15,2016-17,2017-18 L/2016-17/18786,Electrical,Completed,L-Electrical,193,91400,"Removal and Carting of 36 nos of 8 Mtr Conventional type old damaged Cluster type posts at various location in Dn-193,194 & 195 in zone-XV area.",Own Sources,15,2016-17,2017-18 NQ/2016-17/0424,Buildings,Completed,NQ-SHOZHINGANALLUR,193,150000,"IMPROVEMENTS TO THE TOILET ( PROVIDING SYNTEX TANK, WATER LINE AND PAINTING THE WALL) GOVT HR SEC SCHOOL IN DN-193,Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/0425,Buildings,Completed,NQ-SHOZHINGANALLUR,193,460000,"PROVIDING RAMPS, FLOORING AND PAINTING WORKS AT ST THOMAS UNION PRIMARY SCHOOL IN DN-193,Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/0426,Buildings,Completed,NQ-SHOZHINGANALLUR,193,450000,"REPAIRS TO THE DOORS, WINDOWS AND PAINTING WORKS AT GOVT HR SEC SCHOOL IN DN-193,Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/0963,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,342000,Desilting of Strom Water Drain at Various Streets in Dn-193 U-44 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/0986,Buildings,Completed,NQ-SHOZHINGANALLUR,193,350000,"ATTENDING PATCHES WITH WMM AT VENKATESSHWARA NAGAR 1ST CROSS STREET, BETHAL NAGAR, SRI KARPAGA VINAYAGA NAGAR 6TH& 7TH MAIN ROAD, ELLAI AMMAN NAGAR AND SAI NAGAR 2ND MAIN ROAD IN DIV-193, U-45, Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/10644,Roads,Completed,NQ-SHOZHINGANALLUR,193,428000,Forming and Laying CC Road at Balamurugan Garden 1st cross street in Dn-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10646,Roads,Completed,NQ-SHOZHINGANALLUR,193,517000,Forming and Laying CC Road at Customs colony 1st cross street in Dn-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10647,Roads,Completed,NQ-SHOZHINGANALLUR,193,14652000,Forming and Laying CC Road at CL Metha road (Jain college road ) in Dn-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10648,Roads,Completed,NQ-SHOZHINGANALLUR,193,1851000,Forming and Laying CC Road at Kulakkarai street in Dn-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10649,Roads,Completed,NQ-SHOZHINGANALLUR,193,632000,Forming and Laying CC Road at Mettu street in DN-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10650,Roads,Completed,NQ-SHOZHINGANALLUR,193,12752000,Forming and Laying CC Road at Murugesan Nagar Main Road in DN-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10652,Roads,Completed,NQ-SHOZHINGANALLUR,193,632000,Forming and Laying CC Road at Raman nagar in DN-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10653,Roads,Completed,NQ-SHOZHINGANALLUR,193,472000,Forming and Laying CC Road at Sai Nagar 10th Street in DN-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10655,Roads,Completed,NQ-SHOZHINGANALLUR,193,479000,Forming and Laying CC Road at Sai Nagar 11th Street in DN-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10656,Roads,Completed,NQ-SHOZHINGANALLUR,193,479000,Forming and Laying CC Road at Sai Nagar 12th Street in DN-193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10657,Roads,Completed,NQ-SHOZHINGANALLUR,193,346000,Forming and Laying CC Road at Sakthi Nagar 1st Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10658,Roads,Completed,NQ-SHOZHINGANALLUR,193,517000,Forming and Laying CC Road at sakhti nagar 2nd cross street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10659,Roads,Completed,NQ-SHOZHINGANALLUR,193,428000,Forming and Laying CC Road at Sakthi Nagar 3rd Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10660,Roads,Completed,NQ-SHOZHINGANALLUR,193,346000,Forming and Laying CC Road at Sakthi Nagar 4th Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10661,Roads,Completed,NQ-SHOZHINGANALLUR,193,428000,Forming and Laying CC Road at Sakthi Nagar 5th Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10662,Roads,Completed,NQ-SHOZHINGANALLUR,193,346000,Forming and Laying CC Road at Sakthi Nagar 6th Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10664,Roads,Completed,NQ-SHOZHINGANALLUR,193,346000,Forming and Laying CC Road at Sakthi Nagar 7th Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10665,Roads,Completed,NQ-SHOZHINGANALLUR,193,346000,Forming and Laying CC Road at Sakthi Nagar 8th Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10666,Roads,Completed,NQ-SHOZHINGANALLUR,193,3579000,Forming and Laying CC Road at Sakthi Nagar Main Road in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/1090,Roads,Completed,NQ-SHOZHINGANALLUR,193,291000,"REPAIRS TO THE EXISTING ROAD AND PROVIDING CORRUGATED SHEET TO THE RATION SHOP AT POST OFFICE ROAD IN DIV-193, U-45, Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/10901,Roads,Completed,NQ-SHOZHINGANALLUR,193,475000,Forming and Laying CC Road at Selvakumar 1st Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10902,Roads,Completed,NQ-SHOZHINGANALLUR,193,337000,Forming and Laying CC Road at Selvakumar 2nd Cross Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10903,Roads,Completed,NQ-SHOZHINGANALLUR,193,394000,Forming and Laying CC Road at Sreepuram Street in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10905,Roads,Completed,NQ-SHOZHINGANALLUR,193,1458000,Forming and Laying CC Road at Arumugam Avenue in DN- 193 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/11074,Buildings,Completed,NQ-SHOZHINGANALLUR,193,293000,"PROVIDING CHAIN LINK FENCE TO THE EXISTING POND (KANAKKAR KULAM AND PALICHIYAM KULAM) AT PILLAIYAR KOVIL STREET AND KULLAKARAI STREET IN WARD-193, UNIT-45, ZONE-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/11226,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,989000,IMPROVEMENTS TO SIDE DRAIN AT MURUGESAN SALAI FROM (B) CANAL IN DN-193 U-45 Z-15.,Own Sources,15,2016-17,2017-18 NQ/2016-17/12106,Roads,Completed,NQ-SHOZHINGANALLUR,193,568000,"PROVIDING AND LAYING OF WET MIX MACADAM AT SRI KARPAGA VINAYAGAR NAGAR 10TH MAIN ROAD IN WARD-193, UNIT-45, ZONE-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/16488,Parks,Completed,NQ-SHOZHINGANALLUR,193,420000,"IMPROVEMENTS WORK TO PARK AT SAI NAGAR IN DN-193,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16546,Parks,Completed,NQ-SHOZHINGANALLUR,193,390000,"IMPROVEMENTS WORK TO PARK AT CUSTOMS COLONY IN DN-193,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/17061,Roads,Completed,NQ-SHOZHINGANALLUR,193,135000,ATTENDING PATCHES WITH GSB AND WMM AT BALAMURUGAN GARDEN 2ND CROSS STREET IN DN-193 U-44 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/17077,Roads,Completed,NQ-SHOZHINGANALLUR,193,290000,ATTENDING PATCHES WITH BITUMINOUS COURSE AT PILLAIYAR KOIL STREET IN DN-193 U-44 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/17079,Roads,Completed,NQ-SHOZHINGANALLUR,193,445000,ATTENDING PATCHES WITH BITUMINOUS COURSE AT SAI NAGAR 13TH CROSS STREET IN DN-193 U-44 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/17085,Roads,Completed,NQ-SHOZHINGANALLUR,193,210000,ATTENDING PATCHES WITH WMM AT KARPAGA VINAYAGAR NAGAR 32ND CROSS STREET IN DN-193 U-44 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/3560,Roads,Completed,NQ-SHOZHINGANALLUR,193,786000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MCN NAGAR 6TH STREET IN WARD-193, ZONE-15.",Deposit Works,15,2016-17,2016-17 NQ/2016-17/3579,Roads,Completed,NQ-SHOZHINGANALLUR,193,418000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MCN NAGAR 4TH STREET IN WARD -193, ZONE -15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/3580,Roads,Completed,NQ-SHOZHINGANALLUR,193,418000,"RESTORATION OF ROAD CUT MADE BY CMWSS AT MCN NAGAR 3RD STREET IN WARD -193,ZONE -15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/3582,Roads,Completed,NQ-SHOZHINGANALLUR,193,437000,"RESTORATION OF ROAD CUT MADE BY CMWSS AT MCN NAGAR 5TH STREET IN WARD -193, ZONE-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/4116,Buildings,Completed,NQ-SHOZHINGANALLUR,193,187000,"REPAIRS TO THE EXISTING HUME PIPE AT MCN NAGAR 10TH STREET IN DIV-193, U-45, Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/5050,Parks,Completed,NQ-SHOZHINGANALLUR,193,959000,"OUTSOURCING MAINTENANCE OF PARK AI CUSTOMS COLONY IN DIVISION-193,UNIT-45,ZONE-15 (Period for one year )",Own Sources,15,2016-17,2017-18 NQ/2016-17/5051,Parks,Completed,NQ-SHOZHINGANALLUR,193,629000,"OUTSOURCING MAINTENANCE OF PARK AT SAI NAGAR IN DIV-193,UNIT-44,ZONE-15 (Period for one year )",Own Sources,15,2016-17,2017-18 NQ/2016-17/5052,Parks,Completed,NQ-SHOZHINGANALLUR,193,440000,"OUTSOURCING MAINTENANCE OF PARK AT R.E NAGAR DIV-193,UNIT-44,ZONE-15 ( Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/6029,Culvert,Completed,NQ-SHOZHINGANALLUR,193,860000,"Providing Road Crossing Drain (Culvert) At Venkateswara Nagar in DN -193,u-45,Z-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6624,Buildings,Completed,NQ-SHOZHINGANALLUR,193,999000,"Construction of Compound Wall to the Amma Unavagam (Phase II) at Pandian Nagar in Dn:193, U:45, Z:XV",Own Sources,15,2016-17,2017-18 NQ/2016-17/7131,Roads,Completed,NQ-SHOZHINGANALLUR,193,348000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT CUSTOMS COLONY MAIN ROAD IN WARD-193, ZONE-15.",Deposit Works,15,2016-17,2020-21 NQ/2016-17/7137,Roads,Completed,NQ-SHOZHINGANALLUR,193,990000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BALAMURUGAN GARDERN 1ST TO 3RD MAIN ROAD AND 1ST TO 3RD CROSS STREET IN WARD-193, UNIT-45 ZONE-15.",Deposit Works,15,2016-17,2020-21 NQ/2016-17/7437,Roads,Completed,NQ-SHOZHINGANALLUR,193,425000,"ATTENDING PATCHES WITH WMM AT CUSTOMS COLONY MAIN ROAD, SAKTHI NAGAR 5TH ST, SAKTHI NAGAR MAIN ROAD IN DIV - 193 , U - 45, Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/7438,Buildings,Completed,NQ-SHOZHINGANALLUR,193,283000,"IMPROVEMENTS AND REPAIR WORKS TO THE DIVISION OFFICE AT WARD-193, UNIT-45, ZONE-15.",Own Sources,15,2016-17,2017-18 D/2016-17/11237,Storm Water Drain,Completed,D-Storm Water Drains,194,450000,"Providing and laying of 900 mm dia NP3 RCC Hume pipe, Earth work excavation for Earthen drain for free flow of water along 4 & 5 th Main road of Secretriate colony from 4th main road to south B'Canal and 3 rd Main road to South B'Canal at Thoraipakkam Dn-194, Zone XV",Own Sources,15,2016-17,2016-17 D/2016-17/13846,Storm Water Drain,Completed,D-Storm Water Drains,194,865000,"Desilting of canal and drain, laying of 600mm dia. RCC hume pipe (NP2) for free flow of water from Secretariate Colony to south B canal in Division 194,Zone 15.",Own Sources,15,2016-17,2016-17 L/2016-17/13638,Electrical,Completed,L-Electrical,194,159300,"PAINTING OF 636 NOS OF 6MTR Lamp post with ingle straight bracket ,357 nos of 6mtr single arch bracket and 28 nos of painting of kiosk pillar box in various dtreets in dn 194,zone 15",Own Sources,15,2016-17,2017-18 L/2016-17/13651,Electrical,Completed,L-Electrical,194,180700,"REPLACEMENT OF DAMAGED CABLES DUE TO FAULT AT VARIOUS LOCATION IN DN 194,ZONE XV",Own Sources,15,2016-17,2017-18 NQ/2016-17/0486,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,429000,"Restoration of Road cut ,Road cut made by CMWSSB at Chandrasekar avenue 1st main ,1st,2nd,3rd and 4th cross street in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0487,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,377000,"Restoration of Road cut, Road cut made by CMWSSB at Chandrasekar avenue 2nd main,1st,2nd,3rd,4th and 5th cross street in dn-194,Unit-45,Zone-15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0488,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,287000,"Restoration of Road cut,Road cut made by CMWSSB at Chandrasekar 2nd Avenue in dn-194,Unit-45,Zone-15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0489,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,279000,"Restoration of Road cut, Road cut made by CMWSSB, at Chandrasekar Avenue 3rd Main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0500,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,446000,"Restoration of road cut, Road cut made by CMWSSB at VPG Avenue Extn.Main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0501,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,457000,"Restoration of road cut,Road cut made by CMWSSB at VPG Avenue Extn.2nd,3rd,4th,5th and 6th Street in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0524,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,752000,"Restoration of Road cut,Road cut made by CMWSSB at PTC Qutrs 2nd main road,1st,2nd,3rd and 4th cross street in dn-194,U-45,zONE-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0526,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,284000,"Restoration of Road cut, Road cut made by CMWSSB at PTC Qtrs 3rd main road in dn-194,Unit-45,Zone-15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0527,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,490000,"Restoration of Road cut, Road cut made by CMWSSB at Kumaraguru avenue 1st,2nd,3rd,4th,5th and 7th street dn-194, Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0528,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,524000,"Restoration of Road cut,Road cut made by CMWSSB at Royal avenue 2nd,3rd,4th street,Ambal avenue 1st street and Srinivasa nagar in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0530,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,279000,"Restoration of Road cut,Road cut made by CMWSSB at Annai avenue 1st,2nd and 3rd street in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/0915,Roads,Completed,NQ-SHOZHINGANALLUR,194,157000,"Painting and writing letters to Dustbin at Various Streets in Dn-194, U-45, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0961,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,480000,"Repairs and Desilting of storm water drain at various street in dn194,Unit-45,Zone-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/11211,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,658000,"Proposed construction of side drain at VPG Avenue from OMR to Existing open side drain in dn-194,Unit-45,Zone-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/11212,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,786000,"Repairs and Raising the existing open side drain at VPG Avenue various streets in dn-194,Unit-45,Zone-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/11997,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,793000,"Restoration of Road cut Road cut made by CMWSSB at Secretariate colony 2nd main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/11999,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,476000,"Restoration of Road cut Road cut made by CMWSSB at secretariate colony 3rd main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12000,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,704000,"Restoration of Road cut,Road cut made by CMWSSB at Secretariate colony 4th main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12002,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,307000,"Restoration of Road cut,Road cut made by CMWSSB at Secretariate colony 5th main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12006,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,376000,"Restoration of Road cut ,Road cut made by CMWSSB at Secretariat colony 1st and 2nd cross street in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12007,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,793000,"Restoration of Road cut ,Road cut made by CMWSSB at Secretariate colony 3rd and 4th cross street in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12010,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,405000,"Restoration of Road cut,Road cut made by CMWSSB at Secretariate colony 5th cross street in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12011,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,700000,"Restoration of Road cut,Road cut made by CMWSSB at Secretariate colony 6th cross street,6th cr.extn.and 7th cross street in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12054,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,814000,"Restoration of Road cut,Road cut made by CMWSSB at Secretariate colony 1st and 2nd circle road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12061,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,634000,"Restoration of Road cut ,Road cut made by CMWSSB at Secretariate colony 3rd circle road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12069,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,576000,"Restoration of Road cut,Road cut made by CMWSSB at Secretariate colony West circle road and Joint road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12418,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,255000,"Restoration of Road cut,Road cut made by CMWSSB at PTC Quarters 1st main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/12803,Roads,Completed,NQ-SHOZHINGANALLUR,194,810000,Supply and Fixing of E-Toilet at Pillayar koil street (NEAR AMMA UNAVAGAM ) IN DN-194 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/17068,Roads,Completed,NQ-SHOZHINGANALLUR,194,970000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD AT NIK AVENUE IN DN-194,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/17503,Parks,Completed,NQ-SHOZHINGANALLUR,194,180000,Repair and Maintenance work for Chandra Sekaran park at Chandra Sekaran Avenue in Dn-194 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/18800,Buildings,Completed,NQ-SHOZHINGANALLUR,194,960000,"Construction of Anganwadi under MLA Fund at Kumaran Kudil 6th cross Street in Dn-194, U-45, Z-15.",MLACDS,15,2016-17,2019-20 NQ/2016-17/2808,Buildings,Completed,NQ-SHOZHINGANALLUR,194,237000,"Providing and Supplying SS Table, SS Wash Basin, Flooring in front of Amma Unavagam at Pillaiyar Koil Street in Dn-194, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/3280,Buildings,Completed,NQ-SHOZHINGANALLUR,194,220000,"Construction of Dust bin Platform at various streets in Dn-194, U-45, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/3281,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,190000,"FORMING WETMIX MACADAM AT EALIM STREET STREET IN DN-194, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/3282,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,589000,"FORMING AND LAYING CC ROAD AT MOUNTPATTEN 3RD CROSS STREET IN DN-194, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/4509,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,330000,"Additional Improvements to SWD at various streets in dn-194,Unit-45,Zone-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/5053,Parks,Completed,NQ-SHOZHINGANALLUR,194,920000,"OUT SOURCING MAINTENANCE OF PARKS AT SECRETARIAT COLONY IN DIV-194,UNIT-44,ZONE-15. (Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/5056,Parks,Completed,NQ-SHOZHINGANALLUR,194,572000,"OUTSOURCING MAINTENANCE OF PARKS AT CHANDRASEKARAN AVENUE IN DN-194, U-44, Z-15 (Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/5057,Parks,Completed,NQ-SHOZHINGANALLUR,194,583000,"OUT SOURCING MAINTENANCE OF PARKS IN P.T.C QUARTERS DIVISION-194, UNIT-44, ZONE-15 (Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/6031,Buildings,Completed,NQ-SHOZHINGANALLUR,194,905000,"Construction of Amma Unavagam using steel structure and corrugated sheet cladding at Pillaiyar koil street (west) near V.O.Office in Dn-194, Unit-45, Zone-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6585,Roads,Completed,NQ-SHOZHINGANALLUR,194,373000,"LAYING CEMENT CONCRETE AT ARIYATHAMMAN KOIL STREET, WATER TABLE AT ESWARAN KOIL STREET IN DN-194, U-45, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6591,Buildings,Completed,NQ-SHOZHINGANALLUR,194,427000,"Construction of storm water side drain at guindy engineering college road 3rd street in Dn-194, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6593,Buildings,Completed,NQ-SHOZHINGANALLUR,194,134000,"PROVIDING RAMP, HANDRAIL WRITING LETTERS AT VARIOUS STREETS IN DN-194, U-45, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6850,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,413000,"Restoration of Road cut Road made by TNEB at kogilambal nagar main road in dn 194,Unit-45,Zone-15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/6853,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,552000,"Restoration of Road cut Road cut made by TNEB at Azhagappa nagar 1st cross st and Balaji nagar 1st street in dn 194,Unit-45, Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/7271,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,405000,"Restoration of Road cut ,Road cut made by TNEB at Chandrasekar nagar in dn 194 Unit-45,Zone-15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/7276,Buildings,Completed,NQ-SHOZHINGANALLUR,194,364000,"PROVIDING CHAINLINK FENCING, GATE AND GATE PILLAR AT ESWARAN KOIL STREET PANJAVANKUTTAI(POND) IN DN-194, U-45, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7370,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,571000,"Restoration of Road cut,Road cut made by TNEB at Sulaimanagar main road and Bharathiyar nagar main road in dn-194,Unit-45,Zone-15.",Deposit Works,15,2016-17,2017-18 NQ/2016-17/7600,Buildings,Completed,NQ-SHOZHINGANALLUR,194,888000,"CONSTRUCTION OF CULVERTS AND SIDE DRAIN AT GUINDY COLLEGE ROAD , ALAGAPPA NAGAR MAIN ROAD IN DN-194, Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/8650,Buildings,Completed,NQ-SHOZHINGANALLUR,194,891000,"Providing corrugated sheet and Truss work for construction of New Amma Unavagam at Pillaiyar koil street(West) near VAO Office in dn-194,Unit-45,Zone-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/8826,Roads,Completed,NQ-SHOZHINGANALLUR,194,490000,"ATTENDING PATCH WORK WITH WMM AT ALAGAPPA NAGAR, BALAJI NAGAR, VPG AVENUE, FOUNDARY SALAI AND VARIOUS STREETS IN DN-194, U-45, Z-15",Own Sources,15,2016-17,2017-18 BR/2016-17/17768,Roads,Completed,BR-Bus Route Roads,195,3920000,"Repair and Restoration of Relaying Road by Paver Finisher Work at Kannagi Nagar 2nd Main road in Dn-195, Zone-15",Grants,15,2016-17,2017-18 BR/2016-17/17769,Roads,Completed,BR-Bus Route Roads,195,1485000,"Repair and Restoration of Relaying Road by Paver Finisher Work at Kannagi Nagar 8th Main Road in Dn-195, Zone-15",Grants,15,2016-17,2017-18 L/2016-17/13636,Electrical,Completed,L-Electrical,195,177000,"Painting of 706 nos of 6mtr single straight lamp post and 356 nos of single arch bracket ,36 nos of 8mtr single arch bracket and 25 nos of painting of kiosk pillar box in various streets in dn 195 ,zone 15",Own Sources,15,2016-17,2017-18 L/2016-17/13639,Electrical,Completed,L-Electrical,195,194800,"PROVISION OF 15 NOS OF POST REMOVAL AND REFIXING AT KANNAGI NAGAR,DN 195,ZONE 15",Own Sources,15,2016-17,2017-18 L/2016-17/13647,Electrical,Completed,L-Electrical,195,185200,"REPLACEMENT OF DAMAGED CABLES DUE TO FAULT AT VARIOUS LOCATION IN DN 195,ZONE 15",Own Sources,15,2016-17,2017-18 L/2016-17/13650,Electrical,Completed,L-Electrical,195,178000,"REPLACEMENT OF DAMAGED CABLES AND POST DUE TO STORM WATER DRAIN WORK AT ANNAI INDIRA NAGAR IN DN 195,ZONE XV",Own Sources,15,2016-17,2017-18 L/2016-17/18741,Electrical,Completed,L-Electrical,195,186900,Replacement of damaged 660 mtrs of 2Cx25 sq.mm PVC Alu.cable into 2Cx16 sq.mm cables due to storm water drain work at various locations in dn 195,Own Sources,15,2016-17,2017-18 NQ/2016-17/0359,Roads,Completed,NQ-SHOZHINGANALLUR,195,260000,PROVIDING AND LAYING GSB AT NETHAJI STREET AND SILT CATCH BIT KANNANGI NAGAR 11TH & 12TH MAIN ROAD IN DN 195 UNIT 45 ZONE 15,Own Sources,15,2016-17,2017-18 NQ/2016-17/0360,Buildings,Completed,NQ-SHOZHINGANALLUR,195,899000,"PROVIDING SPEED BREAKER WITH CAUTION BOARD THERMOPLASTIC PAINT AND STUDS AT MADHA KOIL STREET,PILLAYAR KOIL STREET ,IN DIVISION 195.UNIT45,ZONE15",Own Sources,15,2016-17,2017-18 NQ/2016-17/0361,Buildings,Completed,NQ-SHOZHINGANALLUR,195,710000,"IMPROVEMENTS TO PRIMARY AND HIGHER SECONDARY SCHOOL IN DN-195,UNIT-44,ZONE-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0362,Buildings,Completed,NQ-SHOZHINGANALLUR,195,180000,IMPROVEMENTS TO DUSTBIN PLATFORM AT BUSROUTE AT KANNAGI NAGAR IN DIVISION 195 UNIT 44,Own Sources,15,2016-17,2017-18 NQ/2016-17/0595,Buildings,Completed,NQ-SHOZHINGANALLUR,195,125000,"IMPROVEMENT TO POLICE OUT BOOTH INSTALLATION OF MOBILE TOILET AT BUS DEPOT IN DN-195,UN-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/0596,Buildings,Completed,NQ-SHOZHINGANALLUR,195,400000,"Patch work MRG Nagar Using WMM and Renovation of Compound wall in Playground at Kannagi Nagar 12th Main Road in DN-195,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/0597,Buildings,Completed,NQ-SHOZHINGANALLUR,195,298000,"CONSTRUCTION OF ROOFING FOR SHUTTING MACHINE IN COMPOST YARD AT 17th MAIN ROAD KANNAGI NAGAR IN DN- 195, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/0598,Buildings,Completed,NQ-SHOZHINGANALLUR,195,95120,"PROVIDING RAIN WATER HARVESTING INSIDE AMMA UNAVAGAM AT KANNAGI NAGAR IN DN- 195, U- 44, Z- 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/0599,Buildings,Completed,NQ-SHOZHINGANALLUR,195,880000,"CONSTRUCTION & IMPROVEMENT TO SIDE DRAIN AT SARASWATHI NAGAR V.O.C 1ST CROSS STREET IN DN-195, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/0968,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,378000,REPAIRS AND DESILTING of Strom Water Drain at Various Streets in Dn-195 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/13138,Buildings,Completed,NQ-SHOZHINGANALLUR,195,199000,"PROVIDING COLOUR WASHING AT VARIOUS PLACE IN DN-195, U-45, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/14691,Roads,Completed,NQ-SHOZHINGANALLUR,195,71000,"PROVIDING AND FIXING STREET NAME BOARD STICKERS AT KANNAGI NAGAR VARIOUS STREET IN DIV 195,UNIT44,ZONE15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16554,Buildings,Completed,NQ-SHOZHINGANALLUR,195,171000,"IMPROVEMENTS TO AMMA UNAVAGAM AT EZHIL NAGAR IN DN-195,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16564,Footpath,Completed,NQ-SHOZHINGANALLUR,195,353000,"Improvements to Footpath due to vardha cyclone at kannagi nagar 1st,2nd and 8th Main Road in Dn-195 U-45 Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16566,Buildings,Completed,NQ-SHOZHINGANALLUR,195,235000,"IMPROVEMENTS TO BURIAL GROUND COMPOUND WALL AT KANNAGI NAGAR IN DN-195,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16576,Buildings,Completed,NQ-SHOZHINGANALLUR,195,160000,"REPAIR WORKS TO STREET FURNITURE VARIOUS STREET IN DN-195,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/18939,Buildings,Completed,NQ-SHOZHINGANALLUR,195,810000,"CONSTRUCTION OF E-TOILET FOR (1+1) AT NEAR AMMA UNAVAGAM-OMR,IN DIV-195,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/18995,Buildings,Completed,B-Buildings,195,385000,"IMPROVEMENTS TO THE EXISTING UPHC LOCATED AT KANNAGI NAGAR 1ST MAIN ROAD IN DIV195,U45,Z15",Own Sources,15,2016-17,2018-19 NQ/2016-17/4529,Roads,Completed,NQ-SHOZHINGANALLUR,195,360000,"IMPROVEMENTS TO ROAD INFRONT OF KANNAGI NAGAR BUS DEPOT IN DIVISON 195,UNIT44,ZONE15",Own Sources,15,2016-17,2016-17 NQ/2016-17/4531,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,998000,"REPAIR WORK OF SWD INCLUDING REMOVING AND REFIXING OF CC SLAB AT VARIOUS STREET IN DN-195 U-45, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/5055,Parks,Completed,NQ-SHOZHINGANALLUR,195,348000,"OUTSOURCING MAINTENANCE OF PARKS AT SAKTHI SRINIVASAN NAGAR IN DN-194, U-45, Z-15 (Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/5058,Parks,Completed,NQ-SHOZHINGANALLUR,195,231000,"OUTSOURCING MAINTENANCE OF PARKS AT KANNAGI NAGAR 10th CROSS STREET IN DN-195, U-44, Z-15. ( Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/5059,Parks,Completed,NQ-SHOZHINGANALLUR,195,398000,"OUTSOURCING MAINTENANCE OF PARKS AT KANNAGI NAGAR 2ND MAIN ROAD IN DN-195,U-44,Z-15 ( Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/5060,Parks,Completed,NQ-SHOZHINGANALLUR,195,358000,"OUTSOURCING MAINTENANCE OF PARK AT KANNAGI NAGAR 7TH CROSS STREET IN DIV-195,UNIT-44,ZONE-15. (Period for One Year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/5062,Parks,Completed,NQ-SHOZHINGANALLUR,195,431000,"OUTSOURCING MAINTENANCE OF PARK AT ANNAI INDIRA NAGAR IN DIV-195,UNIT-44,ZONE-15. ( Period for One year)",Own Sources,15,2016-17,2017-18 NQ/2016-17/5063,Parks,Completed,NQ-SHOZHINGANALLUR,195,346000,"OUTSOURCING MAINTENANCE OF PARK AT KANNAGI NAGAR 9TH MAIN ROAD IN DIV-195,UNIT-44,ZONE-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/5877,Buildings,Completed,NQ-SHOZHINGANALLUR,195,900000,"CONSTRUCTION OF AMMA UNAVAGAM USING STEEL STRUCTURE AND CORRUGATED SHEET CLADDING AT NEAR RAJIV GANDHI SALAI (OKKIYAMPETTAI) IN DN-195,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6486,Buildings,Completed,NQ-SHOZHINGANALLUR,195,900000,"CONSTRUCTION OF AMMA UNAVAGAM USING STEEL STRUCTURE AND CORRUGATED SHEET CLADDING AT EZHIL NAGAR (ETRP APPROACH ROAD) IN DN-195,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7372,Road Cut,Completed,NQ-SHOZHINGANALLUR,195,998000,"Restoration of Road cut, Road cut made by CMWSSB at Thiruvalluvar street in dn 195,Unit-45,Zone-15",Deposit Works,15,2016-17,2016-17 NQ/2016-17/7493,Roads,Completed,NQ-SHOZHINGANALLUR,195,998000,"Restoration of road cut, road cut made by CMWSSB at Annai Indira Nagar, Nethaji Street and ford avenue in Dn.195, U-45, Z-15",Deposit Works,15,2016-17,2016-17 NQ/2016-17/8588,Buildings,Completed,NQ-SHOZHINGANALLUR,195,345000,IMPROVEMENTS TO COMPOSITE YARD AT KANNAGI NAGAR 17 TH MAIN ROAD,Own Sources,15,2016-17,2016-17 NQ/2016-17/8600,Buildings,Completed,NQ-SHOZHINGANALLUR,195,940000,"Improvement of Additional Amma unavagam in OMR(Okkayampet) DN 195 , U-45 , ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8601,Buildings,Completed,NQ-SHOZHINGANALLUR,195,990000,"Improvement to Additional Amma unavagam in Ezhil nagar DN 195 , U-45 , ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8602,Roads,Completed,NQ-SHOZHINGANALLUR,195,3540000,Forming and Laying CC Road at VOC Main road in Dn-195 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/8662,Roads,Completed,NQ-SHOZHINGANALLUR,195,3700000,Forming and Laying CC Road at Annai Indira nagar Main road in Dn-195 U-45 Z-15,Own Sources,15,2016-17,2017-18 RS/2016-17/5096,Parks,Completed,P-Parks and Playfields,195,3877800,PROVIDING PARK WITH COMPOUND WALL INSIDE OSR LAND GIVEN BY CTS IN DIVISION-195 ZONE-XV IN SOUDESWARI NAGAR CREAK STREET.,Own Sources,15,2016-17,2017-18 L/2016-17/13282,Electrical,Completed,L-Electrical,196,196000,The painting of 1083 nos of 6 mtr single straight bracket street lamp post & 35 numbers of pillar box painting and numbering of 1404 street lamp post in various streets in Dn 196/199 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/18958,Electrical,Completed,L-Electrical,196,955900,Provision of 22Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 22Nos of 40-50w watts LED fitting at Vimala gardens street Location in Dn.196 in Zone-XV,Own Sources,15,2016-17,2017-18 NQ/2016-17/0364,Buildings,Completed,NQ-SHOZHINGANALLUR,196,870000,"PROVIDING AND LAYING HUME PIPE AT KAMARAJAR STREET IN DIVSION 196,UNIT-44,ZONE15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0365,Buildings,Completed,NQ-SHOZHINGANALLUR,196,730000,"IMPROVEMENTS TO COMPACTER BIN LOCATIONS AT VARIOUS PLACES ON ROADSIDES IN DIVISION 196,UNIT44,ZONE15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0367,Buildings,Completed,NQ-SHOZHINGANALLUR,196,960000,"RAISING THE ROAD WITH GSBAND WMM AT SN NAGAR 1ST STREET,2ND STREET AND VARIOUS STREETS IN DIV 196 UNIT 44 ZONE 15",Own Sources,15,2016-17,2016-17 NQ/2016-17/16532,Parks,Completed,NQ-SHOZHINGANALLUR,196,165000,"REPAIRS TO PARK DUE TO VARDHA CYCLONE AT V.G.P. LAYOUT IN RAJARATHINAM AVENUE IN DIV.196, UNIT-44, ZONE-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/18036,Buildings,Completed,NQ-SHOZHINGANALLUR,196,946000,"CONSTRUCTION OF TOILET BLOCK (3+3) SEATER AT THIRUVALLUVAR SALAI, BETHEL NAGAR IN DIV-196, UNIT-44, ZONE-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/4576,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,196,552000,Desilting of Strom water drain at Bethel Nagar Main Road in Dn-196 U-44 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/5246,Buildings,Completed,NQ-SHOZHINGANALLUR,196,930000,"CONSTRUCTION OF AMMA UNAVAGAM USING STEEL STRUCTURE AND CORRUGATED SHEET CLADDING AT BETHEL NAGAR IN DN-196,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/5844,Parks,Completed,NQ-SHOZHINGANALLUR,196,475000,"OUT SOURCING MAINTENANCE OF VGP PARK AT INJAMBAKKAM IN DN 196,UNIT-44,ZONE-15 (FOR ONE YEAR)",Own Sources,15,2016-17,2017-18 NQ/2016-17/6211,Buildings,Completed,NQ-SHOZHINGANALLUR,196,240000,"IMPROVEMENTS TO PRIMARY HEALTH CENTRE AT KANNAGI NAGAR 1 ST MAIN ROAD ,IN DIVISION 195 ,UNIT 44 ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6213,Roads,Completed,NQ-SHOZHINGANALLUR,196,850000,"IMPROVEMENTS TO ROADS BY USING WMM AT CHOLAMANDALA DEVI NAGAR 1TO 6 STREETSIN DIVISION 196,UNIT 45,ZONE 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6374,Roads,Completed,NQ-SHOZHINGANALLUR,196,980000,"IMPROVEMENTS TO ROADS AT BETHEL NAGAR 2 ND MAIN ROAD (SOUTH) IN DIVISION 196,UNIT-44,ZONE15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8593,Roads,Completed,NQ-SHOZHINGANALLUR,196,980000,"PROVIDING SPEED BREAKER AT NANJUNDRAO SALAI ,AMEDKAR STREET,USING BT,AND RETRO REFLECTIVE BOARD , IN DN-196 U-44 Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8594,Roads,Completed,NQ-SHOZHINGANALLUR,196,965000,"PROVIDING SPEED BREAKER WITH CAUTION BOARD,THERMOPLASTIC PAINT AND STUDS AT HARICHANDRA MAIN ROAD ,INJABAKKAM VETTUVANKENI LINK ROAD ,IN DIVISION 196,UNIT 44,ZONE15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8595,Buildings,Completed,NQ-SHOZHINGANALLUR,196,980000,"PROVIDING SPEED BREAKER WITH CAUTION BOARD,THERMOPLASTIC PAINT AND STUDS AT THIRUVALLUAR SALAI,PONNIAMMAN KOIL STREET,BETHEL NAGAR NORTH 3RD STREET ,4TH,5THSTREETS IN DIVISION 196,UNIT 44,ZONE15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8596,Buildings,Completed,NQ-SHOZHINGANALLUR,196,870000,"IMPROVEMENT OF ADDITIONAL AMMA UNAVAGAM IN BETHEL NAGAR AT DN 196,UNIT 45,Z-15",Own Sources,15,2016-17,2017-18 L/2016-17/13715,Electrical,Completed,L-Electrical,197,176100,"Proposed Painting of 704 nos of 6 mtr with single straight bracket street lamp post,260 nos of 6 mtr with single Arch bracket street lamp post & 35 Nos of Kiosk Pillar boxes and Numbering of 964 nos of street lamp post at various location in Dn-197 in zone-15.",Own Sources,15,2016-17,2017-18 L/2016-17/13718,Electrical,Completed,L-Electrical,197,194500,"Proposed to Relocate 20 nos of 6 mtr street lamp post with single straight bracket,Erection of coventional type of 10 nos of 6mtr lamp post with single straight bracket and contruct 30 nos of new plane cement concrete pedestal for street lamp post due to aging and road widening at Elcot avenue road,Modern School road and various location in Dn 197 in Zone-XV.",Own Sources,15,2016-17,2017-18 L/2016-17/13877,Electrical,Completed,L-Electrical,197,195600,Replacement of 520 mtr of 4X16 Sqmm damaged cable in Elcot Avenue road and Modern School Road in Dn 197 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13881,Electrical,Completed,L-Electrical,197,157100,Replacement of 510 mtr 2X16 sqmm damaged cable in Kumarasamy nagar and various location inDn-197 in zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/16295,Electrical,Completed,L-Electrical,197,188100,Proposed to Replace the accessories and maintenance work of 30 mtr HighMast at Sholinganallur junction in Dn-197 Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/18712,Electrical,Completed,L-Electrical,197,128900,"Removal and Carting of 41 nos of 8/12 Mtr Conventional/foundation type old damaged Cluster type posts at various location in Dn-197,198 & 200 in zone-XV area.",Own Sources,15,2016-17,2017-18 L/2016-17/18713,Electrical,Completed,L-Electrical,197,198300,Proposed to Raising of 50 nos of Kiosk pillar boxes & 28 nos of Earthing work for Kiosk pillar boxes in various locations in Dn-192 to 200 in Zone-XV.,Own Sources,15,2016-17,2017-18 NQ/2016-17/0345,Buildings,Completed,NQ-SHOZHINGANALLUR,197,870000,Repair and Maintenance works to Govt Higher Secondary School at Sholinganallur in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/0357,Buildings,Completed,NQ-SHOZHINGANALLUR,197,690000,Repair and Maintenance works to Schools at Gajarajan Street Karapakkam and KK Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/0358,Buildings,Completed,NQ-SHOZHINGANALLUR,197,260000,Repair and Maintenance Works to Zonal Office Building at Rajiv Gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/0674,Roads,Completed,NQ-SHOZHINGANALLUR,197,990000,"Forming and Laying of BT Road with using Paver Finisher at Indira Gandhi Nagar Main Road Reach-1 in Dn-197, U-45, Z-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/0849,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,995000,Desilting of Strom Water Drain At Various Streets in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/0852,Buildings,Completed,NQ-SHOZHINGANALLUR,197,156000,Providing and Fixing Stainless Steel Office Name Board Inside of Division Office at Gangaiamman koil Street Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/0856,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,996000,"Providing Side Drain at Kajarajan Street Karapakkam in Dn- 197, U - 45, Z - 15",Own Sources,15,2016-17,2016-17 NQ/2016-17/10455,Roads,Completed,NQ-SHOZHINGANALLUR,197,440000,Forming and Laying CC Road at Arunachalam Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10456,Roads,Completed,NQ-SHOZHINGANALLUR,197,255000,Forming and Laying CC Road at Dr.Ambetkar Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10476,Roads,Completed,NQ-SHOZHINGANALLUR,197,1616000,Forming and Laying CC Road at Kanthasamy Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10489,Roads,Completed,NQ-SHOZHINGANALLUR,197,365000,Forming and Laying CC Road at M.A.Vaithiyalingam Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10492,Roads,Completed,NQ-SHOZHINGANALLUR,197,660000,Forming and Laying CC Road at Madurai Naickar street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10502,Roads,Completed,NQ-SHOZHINGANALLUR,197,425000,Forming and Laying CC Road at Mahathma Gandhi 2nd cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10505,Roads,Completed,NQ-SHOZHINGANALLUR,197,403000,Forming and Laying CC Road at Murugesa Naickar street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10508,Roads,Completed,NQ-SHOZHINGANALLUR,197,580000,Forming and Laying CC Road at Nadu street 1st cross east in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10509,Roads,Completed,NQ-SHOZHINGANALLUR,197,379000,Forming and Laying CC Road at Nadu street 1st cross west in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10511,Roads,Completed,NQ-SHOZHINGANALLUR,197,515000,Forming and Laying CC Road at Narayanasamy street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10513,Roads,Completed,NQ-SHOZHINGANALLUR,197,329000,Forming and Laying CC Road at Periya Palayathamman koil 1st cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10515,Roads,Completed,NQ-SHOZHINGANALLUR,197,470000,Forming and Laying CC Road at Periya Palayathamman koil street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10517,Roads,Completed,NQ-SHOZHINGANALLUR,197,411000,Forming and Laying CC Road at Periyar street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10520,Roads,Completed,NQ-SHOZHINGANALLUR,197,411000,Forming and Laying CC Road at Perumal naickar street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10523,Roads,Completed,NQ-SHOZHINGANALLUR,197,1088000,Forming and Laying CC Road at Rangasamy Naickar 1st street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10526,Roads,Completed,NQ-SHOZHINGANALLUR,197,1088000,Forming and Laying CC Road at Rangasamy Naickar 2nd street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10528,Roads,Completed,NQ-SHOZHINGANALLUR,197,2717000,Forming and Laying CC Road at Riverview residency 1st street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10532,Roads,Completed,NQ-SHOZHINGANALLUR,197,2890000,Forming and Laying CC Road at Riverview residency 2nd street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10534,Roads,Completed,NQ-SHOZHINGANALLUR,197,3002000,Forming and Laying CC Road at Riverview residency 3rd street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10537,Roads,Completed,NQ-SHOZHINGANALLUR,197,3002000,Forming and Laying CC Road at Riverview residency 4th street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10541,Roads,Completed,NQ-SHOZHINGANALLUR,197,10107000,Forming and Laying CC Road at Riverview residency main street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10544,Roads,Completed,NQ-SHOZHINGANALLUR,197,248000,Forming and Laying CC Road at Sadagopan naickar 1st street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10553,Roads,Completed,NQ-SHOZHINGANALLUR,197,896000,Forming and Laying CC Road at Sholinganallur link road (Duraisamy street) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10556,Roads,Completed,NQ-SHOZHINGANALLUR,197,360000,Forming and Laying CC Road at Velu Naickar street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10559,Roads,Completed,NQ-SHOZHINGANALLUR,197,828000,Forming and Laying CC Road at Vendrasi amman koil 1st cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10562,Roads,Completed,NQ-SHOZHINGANALLUR,197,20013000,Forming and Laying CC Road at Village High Road - Cross Street and School cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10566,Roads,Completed,NQ-SHOZHINGANALLUR,197,3100000,Forming and Laying CC Road at Village High Road - Cross Street and School cross street near lane church in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/10571,Roads,Completed,NQ-SHOZHINGANALLUR,197,185000,Forming and Laying CC Road at VOC street cross in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/1062,Roads,Completed,NQ-SHOZHINGANALLUR,197,995000,"Forming and Laying of BT Road with using Paver Finisher at Indira Gandhi Nagar Main Road Reach-2 in Dn-197, U-45, Z-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/11781,Roads,Completed,NQ-SHOZHINGANALLUR,197,990000,Providing and Laying GSB at New Kumaran Nagar Extn in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/12790,Roads,Completed,NQ-SHOZHINGANALLUR,197,447000,Supplying and providing chain link fencing at Eswaran Street of approach Road (Okkiyam Canal) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/13105,Buildings,Completed,NQ-SHOZHINGANALLUR,197,58000,Providing and Laying GSB for Low Laying area of infront of toilet for shopping complex at Neduncheliyan Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/15954,Buildings,Completed,NQ-SHOZHINGANALLUR,197,310000,Repair and Maintenance work for Amma Unavagam at Neduncheliyan Street and Kaliamman koil Main Road in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/15956,Parks,Completed,NQ-SHOZHINGANALLUR,197,653000,"Repair and Maintanence work for Devaraj Nagar park,Kumarasamy Nagar park,Elcot Avenue 1st Street Park and Techi Park at Rajiv Gandhi Salai in Dn-197 U-45 Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16526,Buildings,Completed,NQ-SHOZHINGANALLUR,197,265000,Repair and Maintanence work for Community hall at Kajarajan Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/16530,Buildings,Completed,NQ-SHOZHINGANALLUR,197,700000,Repair and Maintanence work for Zonal Office Building at Rajiv Gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/16565,Roads,Completed,NQ-SHOZHINGANALLUR,197,183000,"Repair works to street furniture at Various street in Dn.197, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/17697,Buildings,Completed,NQ-SHOZHINGANALLUR,197,2470000,Proposed Compost yard at Kuppusamy Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/18062,Roads,Completed,NQ-SHOZHINGANALLUR,197,28000,"Providing disabled water closet for toilet at periyapalayathamman koil street and neduncheliyan street in dn-197, U-45, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/3300,Parks,Completed,P-Parks and Playfields,197,7190000,"Formation of New Park at Kumarasamy Nagar Main Road, Sholinganallur in Dn-197 U-45 Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/3861,Roads,Completed,NQ-SHOZHINGANALLUR,197,990000,Supplying and placing of Ready Mix M30 Grade Concrete for Patch work at Wipro Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/6217,Parks,Completed,NQ-SHOZHINGANALLUR,197,851000,"Outsourcing Maintenance of parks at Rajiv Gandhi Salai ( TEECHI PARK) In Division 197,Unit-45, Zone-13.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6221,Parks,Completed,NQ-SHOZHINGANALLUR,197,239000,"Outsourcing Maintenance of parks at Elcot salai In Div-197, Unit-45, Zone-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6223,Parks,Completed,NQ-SHOZHINGANALLUR,197,383000,"Outsourcing Maintenance of Parks at Sholinganallur Devaraj Nagar Parks In Div-197, Unit-45. Zone-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6226,Parks,Completed,NQ-SHOZHINGANALLUR,197,886000,"Outsourcing Maintenance of Parks at New Kumarasamy Nagar In Division -197, Unit-45, Zone-13.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6228,Parks,Completed,NQ-SHOZHINGANALLUR,197,266000,"Outsourcing Maintenance of Parks at Central Avenue In Division-197, Unit-45, Zone-13.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6230,Parks,Completed,NQ-SHOZHINGANALLUR,197,238000,"Outsourcing maintenance of parks Locted at Nedungcheliyan street in Division -197, Unit-45, Zone-45.",Own Sources,15,2016-17,2017-18 NQ/2016-17/6275,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,980000,Raising the Existing Side Drain at Sadagoppan street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/6276,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,980000,"Raising the Existing Side Drain at Kalaingar street,MGR Street,Veerapandiya kattabomman street,Bharathiyar Street in Dn-197 U-45 Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6278,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,980000,Raising the Existing Side Drain at Mahatmagandhi Street in Dn-197 U-45 Z-15 (Councilor Fund 2016-17),Own Sources,15,2016-17,2017-18 NQ/2016-17/6283,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,416000,Raising the Existing Side Drain at Nehru Street VOC Street Avvaiyar Street Bharathidasan Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/6285,Buildings,Completed,NQ-SHOZHINGANALLUR,197,660000,Proposed gate and gate pillars and Raising of Existing Compound wall West Side Shopping Complex at Rajiv Gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6288,Buildings,Completed,NQ-SHOZHINGANALLUR,197,992000,Proposed gate and gate pillars and Raising of Existing Compound wall South Side Shopping Complex at Neduncheliyan Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6290,Buildings,Completed,NQ-SHOZHINGANALLUR,197,640000,Demolished and ReConstruction of Compound wall for Lorry Station (North west ) at Model School Road in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/6337,Roads,Completed,NQ-SHOZHINGANALLUR,197,163000,Supplying and Fixing Air Conditioner for Assistant Commissioner Room Auditor room and E-Seva Room at Rajiv Gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6345,Roads,Completed,NQ-SHOZHINGANALLUR,197,432000,Providing and Laying GSB & WMM at Vendrasiamman koil Street and Aringar anna Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6346,Roads,Completed,NQ-SHOZHINGANALLUR,197,161000,Improvements works to Town Planing Room at Rajiv Gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6349,Roads,Completed,NQ-SHOZHINGANALLUR,197,479000,Supplying and providing chain link fencing at Gangaiamman koil Pond and Vendrasiamman koil Pond in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/6525,Roads,Completed,NQ-SHOZHINGANALLUR,197,117000,Sectioning the site for Around Manthoppu Using JCB at Neduncheliyan Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6526,Buildings,Completed,NQ-SHOZHINGANALLUR,197,96000,Providing Rainwater Harvesting for Zonal Office Building at Rajiv gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6732,Buildings,Completed,NQ-SHOZHINGANALLUR,197,985000,"PROVIDING AND FIXING 300MM DIA RCC HUME PIPE AND ROAD WIEDLING AT BOOPATHYNAGAR,PALAYATHAMMAN ST & NEW KUMARAN NAGAR IN DN197 UNIT 45 ZONE15",Own Sources,15,2016-17,2016-17 NQ/2016-17/6773,Subway,Completed,NQ-SHOZHINGANALLUR,197,575000,"FORMING FOOTPATH IN KUMARASAMY NAGAR PARK ALL ROUND IN DN-197, U-45, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7292,Footpath,Completed,NQ-SHOZHINGANALLUR,197,118000,Providing SS Table for Amma Unavagam at Neduncheliyan Street in DN-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/7371,Buildings,Completed,NQ-SHOZHINGANALLUR,197,73000,Improvement works to GYM building at Aringar Anna street karapakkam in DN-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/7646,Buildings,Completed,NQ-SHOZHINGANALLUR,197,930000,Improvement Works to Gym Building and Construction of Compound wall at sadagoppan street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/7707,Buildings,Completed,NQ-SHOZHINGANALLUR,197,720000,Repair and Maintanence works to Toilet inside of Amma Unavagam at kaliamman koil Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/7717,Roads,Completed,NQ-SHOZHINGANALLUR,197,250000,Laying BT Course at Devaraj Nagar 3rd Cross Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/8202,Roads,Completed,NQ-SHOZHINGANALLUR,197,998000,"Providing water supply arrangement, Electrical work and supplying of Gym material for Gym building at Gandhi Street in Dn-197 U-45 Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8266,Buildings,Completed,NQ-SHOZHINGANALLUR,197,640000,Demolished and ReConstruction of Compound wall for Lorry Station (south west ) at Model School Road in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/8362,Buildings,Completed,NQ-SHOZHINGANALLUR,197,995000,Proposed Construction of Gym Building at Gandhi Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/8453,Buildings,Completed,NQ-SHOZHINGANALLUR,197,57000,Improvements works to Public Toilet for Shopping Complex atat Neduncheliyan Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/9142,Buildings,Completed,NQ-SHOZHINGANALLUR,197,411000,Improvements works to Zonal office Building and Division office building at Rajiv Gandhi Salai in DN-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9386,Roads,Completed,NQ-SHOZHINGANALLUR,197,2196000,Forming and Laying of BT Road using Paver Finisher at Elcot Avenue 1st Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9389,Roads,Completed,NQ-SHOZHINGANALLUR,197,3460000,Forming and Laying of BT Road using Paver Finisher at Elcot Avenue Main Street Extn (Main Road) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9390,Roads,Completed,NQ-SHOZHINGANALLUR,197,793000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar 6th Street (2nd Main Road) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9391,Roads,Completed,NQ-SHOZHINGANALLUR,197,1211000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar 3rd Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9408,Roads,Completed,NQ-SHOZHINGANALLUR,197,865000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar 7th Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9409,Roads,Completed,NQ-SHOZHINGANALLUR,197,283000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar 2nd Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9410,Roads,Completed,NQ-SHOZHINGANALLUR,197,1144000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar 1st Street (1st Main Road) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9411,Roads,Completed,NQ-SHOZHINGANALLUR,197,1946000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar 4th Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9412,Roads,Completed,NQ-SHOZHINGANALLUR,197,2018000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar Main Road in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9413,Roads,Completed,NQ-SHOZHINGANALLUR,197,505000,Forming and Laying of BT Road using Paver Finisher at Kumarasamy Nagar 5th Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9415,Roads,Completed,NQ-SHOZHINGANALLUR,197,2076000,Forming and Laying of BT Road using Paver Finisher at Bajanai koil Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9416,Roads,Completed,NQ-SHOZHINGANALLUR,197,913000,Forming and Laying of BT Road using Paver Finisher at Kalaingar Karunanithi Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9417,Roads,Completed,NQ-SHOZHINGANALLUR,197,615000,Forming and Laying of BT Road using Paver Finisher at Kaliamman koil water tank Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9419,Roads,Completed,NQ-SHOZHINGANALLUR,197,529000,Forming and Laying of BT Road using Paver Finisher at Nehru Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9420,Roads,Completed,NQ-SHOZHINGANALLUR,197,529000,Forming and Laying of BT Road using Paver Finisher at Gangappa Naicker Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9421,Roads,Completed,NQ-SHOZHINGANALLUR,197,817000,Forming and Laying of BT Road using Paver Finisher at Govindaraj Naicker Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9423,Roads,Completed,NQ-SHOZHINGANALLUR,197,529000,Forming and Laying of BT Road using Paver Finisher at Samy Naicker Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9426,Roads,Completed,NQ-SHOZHINGANALLUR,197,913000,Forming and Laying of BT Road using Paver Finisher at Veerapandiya Kattabomman Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9427,Roads,Completed,NQ-SHOZHINGANALLUR,197,721000,Forming and Laying of BT Road using Paver Finisher at VOC Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9428,Roads,Completed,NQ-SHOZHINGANALLUR,197,7973000,Forming and Laying of BT Road using Paver Finisher at Model School Road (Govt high School 1st street) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9431,Roads,Completed,NQ-SHOZHINGANALLUR,197,2307000,Forming and Laying of BT Road using Paver Finisher at Old Mahabalipuram cross road (Near OMR & KK Salai link road) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9432,Roads,Completed,NQ-SHOZHINGANALLUR,197,3075000,Forming and Laying of BT Road using Paver Finisher at Gangaiamman koil street Extn in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9433,Roads,Completed,NQ-SHOZHINGANALLUR,197,5190000,Forming and Laying of BT Road using Paver Finisher at Kuppusamy street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9435,Roads,Completed,NQ-SHOZHINGANALLUR,197,8613000,Forming and Laying of BT Road using Paver Finisher at Village High Road in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9436,Roads,Completed,NQ-SHOZHINGANALLUR,197,947000,Forming and Laying of BT Road using Paver Finisher at Thulukanathamman Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9437,Roads,Completed,NQ-SHOZHINGANALLUR,197,577000,Forming and Laying of BT Road using Paver Finisher at Vembuli Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9439,Roads,Completed,NQ-SHOZHINGANALLUR,197,3056000,Forming and Laying of BT Road using Paver Finisher at Anna Street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9440,Roads,Completed,NQ-SHOZHINGANALLUR,197,389000,Forming and Laying of BT Road using Paver Finisher at Anna Street 2nd cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9441,Roads,Completed,NQ-SHOZHINGANALLUR,197,481000,Forming and Laying of BT Road using Paver Finisher at Bajanai koil cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9444,Roads,Completed,NQ-SHOZHINGANALLUR,197,221000,Forming and Laying of BT Road using Paver Finisher at Gandhi 2nd street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9445,Roads,Completed,NQ-SHOZHINGANALLUR,197,2768000,Forming and Laying of BT Road using Paver Finisher at Gandhi 2nd street Extn in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9446,Roads,Completed,NQ-SHOZHINGANALLUR,197,4152000,Forming and Laying of BT Road using Paver Finisher at KCG College Salai in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9448,Roads,Completed,NQ-SHOZHINGANALLUR,197,1778000,Forming and Laying of BT Road using Paver Finisher at Gajarajan Street (MGR 2nd Cross Street) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9449,Roads,Completed,NQ-SHOZHINGANALLUR,197,1201000,Forming and Laying of BT Road using Paver Finisher at Avvaiyar Street (MGR 1st Cross Street Extn) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9450,Roads,Completed,NQ-SHOZHINGANALLUR,197,1653000,Forming and Laying of BT Road using Paver Finisher at Mahathmagandi Street (MGR 1st cross street) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9452,Roads,Completed,NQ-SHOZHINGANALLUR,197,1969000,Forming and Laying of BT Road using Paver Finisher at Lal Bhagathur Sastri street lane in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9453,Roads,Completed,NQ-SHOZHINGANALLUR,197,831000,Forming and Laying of BT Road using Paver Finisher at Lal Bhagathur Sastri street 3rd cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9455,Roads,Completed,NQ-SHOZHINGANALLUR,197,1874000,Forming and Laying of BT Road using Paver Finisher at Medavakkam road cross street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9464,Roads,Completed,NQ-SHOZHINGANALLUR,197,16795000,Forming and Laying of BT Road using Paver Finisher at Union School street (Anandha Nagar & Balaji Nagar) in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9466,Roads,Completed,NQ-SHOZHINGANALLUR,197,1403000,Forming and Laying of BT Road using Paver Finisher at Devaraj Avenue in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9467,Roads,Completed,NQ-SHOZHINGANALLUR,197,1076000,Forming and Laying of BT Road using Paver Finisher at Village High Road 1st street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9469,Roads,Completed,NQ-SHOZHINGANALLUR,197,677000,Forming and Laying of BT Road using Paver Finisher at Village High Road 2nd street in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9470,Roads,Completed,NQ-SHOZHINGANALLUR,197,8613000,Forming and Laying of BT Road using Paver Finisher at Vendrasi Amman koil street Extn in Dn-197 U-45 Z-15,Own Sources,15,2016-17,2017-18 P/2016-17/19686,Parks,Completed,P-Parks and Playfields,197,5433837,"FORMATION OF NEW PARK AT RAJIV GANDHI SALAI ( DOLLAR BUILDING), SHOLINGANALLUR IN DN-197, ZONE - 15",Grants,15,2016-17,2018-19 BR/2016-17/18637,Roads,Completed,BR-Bus Route Roads,198,185000,Providing of ramps for stainless steel bus shelter at various roads in zone=15,Own Sources,15,2016-17,2017-18 L/2016-17/13716,Electrical,Completed,L-Electrical,198,184600,"Proposed Painting of 953 nos of 6 mtr with single straight bracket street lamp post,34 nos of 6 mtr with single rch bracket street lamp post,28 nos of 8 mtr with Double Arch bracket street lamp post,3 nos of 8 mtr with Trible Arch bracket street lamp post,35 nos of Kiosk Pillar boxes and Numbering of 1018 nos of street lamp post at various location in Dn-198 in zone-15.",Own Sources,15,2016-17,2017-18 L/2016-17/13882,Electrical,Completed,L-Electrical,198,188200,"Replacement of 590 mtr of 2X16 Sqmm damaged cable in TVS Avenue,Shyamala Garden road and Various location in Dn 198 in Zone-XV.",Own Sources,15,2016-17,2017-18 L/2016-17/18771,Electrical,Completed,L-Electrical,198,3750000,Conversion of 128 nos of 400w MH fitting in to 150-165w LED fittings at E.C.R Main road from Akkarai junction to Sea Shore town 13 th avenue road junction in Dn-198 in Zone-15.,Deposit Works,15,2016-17,2017-18 NQ/2016-17/0342,Buildings,Completed,NQ-SHOZHINGANALLUR,198,650000,"IMPROVEMENTS TO KUDIMIYANDI THOPPU GOVT, HIGHER SECONDRY SCHOOL FOR ELECTION 2016 BY USING FLOORING ,PLUMBING, PAINTING WORKS ETC.,IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0350,Parks,Completed,NQ-SHOZHINGANALLUR,198,336000,"Outsourcing maintenance of Parks located at TNHB layout (OMR) and SEA CLIFF CONCLAVE (ECR) for the period of three months in Div-198, U-44, Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/0374,Buildings,Completed,NQ-SHOZHINGANALLUR,198,240000,"CONSTRUCTION OF NEW BIN PLATFORM IN VARIOUS STREET IN DN-198,U-45,Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0689,Buildings,Completed,NQ-SHOZHINGANALLUR,198,700000,"ATTENDING PATCH WORK AT MAYANA SALAI IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0690,Buildings,Completed,NQ-SHOZHINGANALLUR,198,293000,"DESILTING OPEN SIDE DRAIN IN TNHB AT B2,B4,B5,C3,C4 ROADS IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0700,Buildings,Completed,NQ-SHOZHINGANALLUR,198,999000,"IMPROVEMENTS TO EXISTING PARK AT E12 ROAD, TNHB IN DN-198, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10643,Roads,Completed,NQ-SHOZHINGANALLUR,198,1350000,"FORMING AND LAYING OF CC AT AKKARAI VILLAGE 2nd, 3rd STREET IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/10654,Roads,Completed,NQ-SHOZHINGANALLUR,198,4980000,"FORMING AND LAYING OF CC AT ANNAI INDIRA 2nd CROSS STREET, ANNAI INDIRA 1st CROSS STREET,CHRISTIAN MAYANA PATHAI EXTN, ELLA RAJAMANAIKAM ROAD, KAMARAJAR CROSS STREET, KAMARAJAR STREET IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10663,Roads,Completed,NQ-SHOZHINGANALLUR,198,4700000,"FORMING AND LAYING OF CC AT KUDIMIYANDI THOPPU M.G.R MAIN STREET EXTN , KUDIMIYANDI THOPPU M.G.R NAGAR 2nd STREET , KUDIMIYANDI THOPPU M.G.R NAGAR 2nd STREET EXTN IN DN-198,U-44,Z-15,",Own Sources,15,2016-17,2017-18 NQ/2016-17/10667,Roads,Completed,NQ-SHOZHINGANALLUR,198,4700000,"FORMING AND LAYING OF CC AT KUDIMIYANDI THOPPU M.G.R NAGAR 3rd,4th & 5th STREET IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10668,Roads,Completed,NQ-SHOZHINGANALLUR,198,4100000,"FORMING AND LAYING OF CC AT KUDIMIYANDI THOPPU M.G.R NAGAR 1st STREET, KUDIMIYANDI THOPPU M.G.R NAGAR MAIN ROAD IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10728,Roads,Completed,NQ-SHOZHINGANALLUR,198,4400000,"FORMING AND LAYING OF CC AT AKKARAI VILLAGE 1st & 4th STREET,KUDIMIYANDI THOPPU SCHOOL BUILDING 1st CROSS STREET SOUTH SIDE, KUDIMIYANDI THOPPU SCHOOL BUILDING 2nd CROSS STREET SOUTH SIDE, KUDIMIYANDI THOPPU SCHOOL BUILDING 4th CROSS STREET SOUTH SIDE, KUDIMIYANDI THOPPU SCHOOL PALLIVASAL CROSS STREET, KUDIMIYANDI THOPPU VELU NAICKER STREET, M.A VAITHYANATHAN STREET IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10839,Roads,Completed,NQ-SHOZHINGANALLUR,198,3800000,"FORMING AND LAYING OF CC AT M.G.R 12th STREET JAHIR HUSSAIN STREET LINK ROAD EXTN, PANAIYUR JAHIR HUSSIAN 1st,2nd,3rd,4th & 5th STREET IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10840,Roads,Completed,NQ-SHOZHINGANALLUR,198,4080000,"FORMING AND LAYING OF CC AT PANAIYUR KUPPAM M.G.R SEASHORE STREET TO JAHIR HUSSIAN 1st STREET LINK ROAD IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10869,Roads,Completed,NQ-SHOZHINGANALLUR,198,4800000,"FORMING AND LAYING OF CC AT PONNIAMMAN KOIL 2nd STREET 4th CROSS STREET, PONNIAMMAN KOIL 1st CROSS STREET EXTN, PONNIAMMAN KOIL 3rd STREET & VIGNESHWARA NAGAR 3rd STREET IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10870,Roads,Completed,NQ-SHOZHINGANALLUR,198,5500000,"FORMING AND LAYING OF CC AT RAJIV GANDHI NAGAR 1st & 2nd STREET ,RAJIV GANDHI NAGAR 1st EXTN, RAJIV GANDHI NAGAR 1st CROSS STREET LANE,,RAJIV GANDHI NAGAR 4th CROSS STREET EXTN IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10872,Roads,Completed,NQ-SHOZHINGANALLUR,198,8700000,"FORMING AND LAYING OF CC AT PANAIYUR KUPPAM M.G.R SALAI IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10873,Roads,Completed,NQ-SHOZHINGANALLUR,198,8700000,"FORMING AND LAYING OF CC AT PANAIYUR KUPPAM M.G.R SALAI (UPTO SEASHORE) IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/10945,Buildings,Completed,NQ-SHOZHINGANALLUR,198,220000,"PROVIDING CHAIN LINK FENCING AT TNHB D44 ROAD & B1 ROAD IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/11424,Roads,Completed,NQ-SHOZHINGANALLUR,198,4900000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT VGP MAIN STREET EXTN , VGP SOUTH ZONE 1st STREET , VGP SOUTH ZONE MAIN ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/11432,Roads,Completed,NQ-SHOZHINGANALLUR,198,999000,"PROVIDING IRC STANDARD SPEED BREAKERS WITH PROVISION OF SIGN BOARD ,THERMO REFLECTIVE PAINT AND STUDS IN MODERN LAYOUT 1st,3rd & 4th AVENUE IN DN-198,U-44,Z-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/11435,Buildings,Completed,NQ-SHOZHINGANALLUR,198,600000,"Improvements to Mandapam near Ponniamman koil by providing flooring & toilet block IN DN-198,U-44,Z-15.",Own Sources,15,2016-17,2016-17 NQ/2016-17/11436,Roads,Completed,NQ-SHOZHINGANALLUR,198,870000,"Improvements to the Existing ground for pathway at Mandapam by providing GSB near Ponniamman koil in DN-198,U-44,Z-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/11739,Buildings,Completed,NQ-SHOZHINGANALLUR,198,670000,"IMPROVEMENTS TO THE EXISTING MANDAPAM BUILDING BY PROVIDING PLASTERING IN DN-198,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/12771,Buildings,Completed,NQ-SHOZHINGANALLUR,198,960000,"CONSTRUCTION OF ANGANWADI UNDER MLA FUND AT KUDIMIYANDI THOPPU SCHOOL PANAIYUR IN DN-198,U-45,Z-15",MLACDS,15,2016-17,2018-19 NQ/2016-17/17736,Buildings,Completed,NQ-SHOZHINGANALLUR,198,2470000,Proposed Compost yard at Parameshwar nagar (Hindu mayanam) in Dn-198 U-45 Z-15,Own Sources,15,2016-17,2017-18 NQ/2016-17/3922,Buildings,Completed,NQ-SHOZHINGANALLUR,198,900000,"CONSTRUCTION OF AMMA UNAVAGAM USING STEEL STRUCTURE AND CORRUGATED SHEET CLADDING AT NEAR RAJIV GANDHI SALAI (OMR) IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/4521,Buildings,Completed,NQ-SHOZHINGANALLUR,198,483000,"IMPROVEMENTS TO THE EXISTING AMMA UNAVAGAM BY PROVIDING PAINTING,FALSE CEILING,WALL TILING WORK AT KUDIMIYANDI THOPPU IN Dn-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/5849,Parks,Completed,NQ-SHOZHINGANALLUR,198,470000,"OUT SOURCING MAINTENENCE OF PARKS LOCATED AT SEA CLIFF CONCLAVE (ECR) FOR ONE YEAR IN DN 198,UNIT-44,ZONE-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/5854,Parks,Completed,NQ-SHOZHINGANALLUR,198,995000,"OUT SOURCING MAINTENENCE OF PARKS LOCATED AT TNHB LAYOUT (OMR) FOR ONE YEAR IN DN198,UNIT-44,ZONE-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7250,Buildings,Completed,NQ-SHOZHINGANALLUR,198,960000,"Maintenance contract for Providing house keeping services for public conveniences at Neelangarai, Injamjbakkam ,Sholinganallur, Uthandi in U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7369,Roads,Completed,NQ-SHOZHINGANALLUR,198,766000,"RESTORATION OF ROAD CUT MADE BY CMWSSB IN AKKARAI VILLAGE MAIN ROAD, 2 ND STREET, 1 STREET, 4TH STREET IN DIV 198, U44,Z15.",Deposit Works,15,2016-17,2016-17 NQ/2016-17/7373,Roads,Completed,NQ-SHOZHINGANALLUR,198,995000,"RESTORATION OF ROAD CUT MADE BY CMWSSB IN RAJIV GANDHI NAGAR 1 ST STREET,1ST CROSS STREET LANE,1ST EXTENTION,2ND STREET,4TH STREET IN DIV 198, U44,Z15.",Deposit Works,15,2016-17,2016-17 NQ/2016-17/7375,Roads,Completed,NQ-SHOZHINGANALLUR,198,960000,"RESTORATION OF ROAD CUT MADE BY CMWSSB IN GANGAIAMMAN KOIL MAIN STREET,MAIN STREET EXTENTION, 1ST CROSS AND EXTENTION IN DIV 198, U44,Z15.",Deposit Works,15,2016-17,2016-17 NQ/2016-17/7376,Roads,Completed,NQ-SHOZHINGANALLUR,198,890000,"RESTORATION OF ROAD CUT MADE BY CMWSSB IN YADAVAL STREET,LR RAJA MANICKAM STREET, GANGAI AMMAN KOIL 2ND CROSS STREET, ZAHIR HUSSAIN 3rd and 5th street IN DIV 198, U44,Z15.",Deposit Works,15,2016-17,2016-17 NQ/2016-17/7434,Buildings,Completed,NQ-SHOZHINGANALLUR,198,850000,"PROVIDING CONSTRUCTION OF WATCHMAN ROOM AND CREEPER SHED AT E12 ROAD PARK IN DN-198,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7458,Buildings,Completed,NQ-SHOZHINGANALLUR,198,820000,"IMPROVEMENTS TO TOILET ,CONSTRUCTION TO DAMAGED COMPOUND WALL AT SATHIYAVANIMUTHU STREET IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7570,Buildings,Completed,NQ-SHOZHINGANALLUR,198,870000,"CONSTRUCTION OF NEW AMMA UNAVAGAM BY PROVIDING STRUSS WORK AT NEAR PONNIAMMANKOIL IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7578,Buildings,Completed,NQ-SHOZHINGANALLUR,198,670000,"IMPROVEMENTS TO THE WARD OFFICE BY PROVIDING INTERLOCK PAVEMENTS AND METAL CLADDING ROOFING IN DN-198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8378,Roads,Completed,NQ-SHOZHINGANALLUR,198,3090000,"FORMING AND LAYING CONCRETE ROAD AT PONNIYAMMAN KOIL 2ND STRREET 1ST,2ND & 3RD CROOSS STREET IN DN- 198,U-44,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/8385,Roads,Completed,NQ-SHOZHINGANALLUR,198,6900000,"FORMING AND LAYING OF BITUMINOUS CONCRETE ROAD WITH PAVER FINISHER AT VILLAGE HIGH ROAD (REACH-2) IN DN-198, U-44, Z-5",Own Sources,15,2016-17,2017-18 NQ/2016-17/9052,Buildings,Completed,NQ-SHOZHINGANALLUR,198,850000,IMPROVEMENT TO TOILET BLOCKS ( GENTS & LADIES )AT PANAYUR KUPPAAM INDN198 UNIT44 ZONE15,Own Sources,15,2016-17,2017-18 NQ/2016-17/9641,Roads,Completed,NQ-SHOZHINGANALLUR,198,3940000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT AKKARAI VILLAGE MAIN STREET , CHIDHAMBARAM NAGAR 1st CROSS STREET , IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9644,Roads,Completed,NQ-SHOZHINGANALLUR,198,4260000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT CHIDHAMBARAM NAGAR MAIN ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9647,Roads,Completed,NQ-SHOZHINGANALLUR,198,3670000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT GLORIYA AVENUE 3rd STREET,GOLDEN SHORE AVENUE IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9649,Roads,Completed,NQ-SHOZHINGANALLUR,198,4000000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT MODERN LAYOUT 2nd AVENUE IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9650,Roads,Completed,NQ-SHOZHINGANALLUR,198,3970000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT MODERN LAYOUT 9th AVENUE IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9654,Roads,Completed,NQ-SHOZHINGANALLUR,198,4000000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT MODERN LAYOUT 1st MAIN ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9655,Roads,Completed,NQ-SHOZHINGANALLUR,198,3970000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT MODERN LAYOUT 2nd MAIN ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9656,Roads,Completed,NQ-SHOZHINGANALLUR,198,3970000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT MODERN LAYOUT 3rd MAIN ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9657,Roads,Completed,NQ-SHOZHINGANALLUR,198,1990000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT MODERN LAYOUT 13th AVENUE & M.G.R 4th STREET IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9658,Roads,Completed,NQ-SHOZHINGANALLUR,198,6300000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT J NAGAR 1 to 4 CROSS STREET IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9661,Roads,Completed,NQ-SHOZHINGANALLUR,198,6300000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT J NAGAR 1 to 4 MAIN ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9666,Roads,Completed,NQ-SHOZHINGANALLUR,198,5000000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT HINDU MAYANA PATHAI EXTN, HINDU MAYANA SALAI , PARAMESHWARAN NAGAR MAYANA PATHAI EXTN,V.O.C STREET & YADAVAL STREET IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9831,Roads,Completed,NQ-SHOZHINGANALLUR,198,4600000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT VILLAGE HIGH ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9837,Roads,Completed,NQ-SHOZHINGANALLUR,198,5400000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT JAYARAM NAICKER STREET,GANGAIAMMAN KOIL MAIN ROAD ,KUMARAN NAGAR MAIN ROAD, TNHB D4 LINK ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9842,Roads,Completed,NQ-SHOZHINGANALLUR,198,4600000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT COPPER BEACH ROAD & BRINDAVAN STREET IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9845,Roads,Completed,NQ-SHOZHINGANALLUR,198,6600000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT SEA SHELL AVENUE AND SEA SHELL AVENUE EXTN,SPRING GARDEN 2nd STREET IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9847,Buildings,Completed,NQ-SHOZHINGANALLUR,198,350000,"PROVIDING CROSS PIPES AND RING WELLS FOR THE MANSOON WORKS AND WRITING LETTERS TO BINS & PC, BARIGATION WORKS , DESILTING OF SIDE DRAIN AT RAJIV GANDHI NAGAR IN DN,198,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9851,Roads,Completed,NQ-SHOZHINGANALLUR,198,3450000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT PANAIYUR KUPPAM MAIN ROAD IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9853,Roads,Completed,NQ-SHOZHINGANALLUR,198,3890000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT V.G.P SOUTH 2nd CROSS STREET AND RAJIV GANDHI NAGAR 4th STREET IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9857,Roads,Completed,NQ-SHOZHINGANALLUR,198,6400000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT VILLAGE HIGH ROAD CROSS STREETS (30 to 39 ) IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9860,Roads,Completed,NQ-SHOZHINGANALLUR,198,6900000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT PANDICHERRY SALAI IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9863,Roads,Completed,NQ-SHOZHINGANALLUR,198,3700000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT NRI LAYOUT (VGP SOUTH) IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2016-17 NQ/2016-17/9870,Roads,Completed,NQ-SHOZHINGANALLUR,198,5300000,"FORMING AND LAYING OF BITUMINOUS COURSE ROAD USING PAVER FINISHER AT SATHYAVANIMUTHU STREET & TNHB LINK ROAD (SATHYAVANIMUTHU STREET) IN DN-198, U-44, Z-15",Own Sources,15,2016-17,2017-18 L/2016-17/13283,Electrical,Completed,L-Electrical,199,190400,The painting of 359 nos of 6 mtr single arch bracket street lamp post& 734 nos of 6 mtr single straight bracket street lamp post & 20 numbers of pillar box painting and numbering of 913 street lamp post in various streets in Dn 196/199 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/18773,Electrical,Completed,L-Electrical,199,3450000,Conversion of 116 nos of 400w MH fitting in to 150-165w LED fittings at E.C.R Main road from Sea Shore town 13 th avenue road junction to Uthandi Toll Plaza in Dn-199 in Zone-15.,Deposit Works,15,2016-17,2017-18 NQ/2016-17/0864,Buildings,Completed,NQ-SHOZHINGANALLUR,199,160000,IMPROVEMENTS TO 16TH DAY CREMATION HALL BY PROVIDING PAVER BLOCK IN UTHANDI ZONE 15,Own Sources,15,2016-17,2016-17 NQ/2016-17/11921,Buildings,Completed,NQ-SHOZHINGANALLUR,199,46200,"IMPROVEMENT TO BIOTOILET BY PROVIDING SHUTTER , PAINTING ETC IN DN 199, U44,Z15",Own Sources,15,2016-17,2016-17 NQ/2016-17/15106,Buildings,Completed,NQ-SHOZHINGANALLUR,199,130000,"PROVIDING RAMP AND WATER SUPPLY ARRANGEMENT FOR BIO TOILET AT RAJA STREET ,MAYANA SALAI IN DN-199,U-45,Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/15246,Parks,Completed,NQ-SHOZHINGANALLUR,199,570000,Improvements works to park at Amirtha Street in Dn-199 U-45 Z-15,Own Sources,15,2016-17,2016-17 NQ/2016-17/16507,Buildings,Completed,NQ-SHOZHINGANALLUR,199,145000,"REPAIR WORKS FOR STREET FURNITURE AT VARIOUS STREETS IN DN 199, U44, Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/2846,Buildings,Completed,NQ-SHOZHINGANALLUR,199,620000,"PROVIDING HANDRAIL,PAVEMENT,PLUMBING AND ELECTRICALS ARRANGMENT TO HIGH SCHOOL IN DN199, UNIT44, ZONE15",Own Sources,15,2016-17,2016-17 NQ/2016-17/2896,Buildings,Completed,NQ-SHOZHINGANALLUR,199,550000,"CONSTRUCTION OF TOILET BLOCK (1+1) INCLUDING SOAK PIT & CONSTRUCTION OF PREFAB TOILET BLOCK (1+1) AT GANGAI AMMAN KOIL COLONY STREET IN DN 199, U44, Z15",Own Sources,15,2016-17,2016-17 NQ/2016-17/3576,Parks,Completed,NQ-SHOZHINGANALLUR,199,235000,"OUTSOURCING MAINTENANCE OF PARKS FOR 12 MONTHS AT AT AMURTHA STREET VGPLAYOUT PARK IN UTHANDI IN DN 199 ,U44, Z15",Own Sources,15,2016-17,2018-19 NQ/2016-17/6396,Buildings,Completed,NQ-SHOZHINGANALLUR,199,200000,"CONSTRUCTION OF CHAMPER , PRECASE SLAB AND STAINLESS STEEL NAME BOARD AT VARIOUS LOCATIONS IN DN 199, U 44,Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6494,Road Cut,Completed,NQ-SHOZHINGANALLUR,199,905000,"RESTORATION OF ROADCUT USING CC AND BT AT VVVS SALAI AND NEELA THIRAI SALAI IN DN 199, U44, Z15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/6563,Road Cut,Completed,NQ-SHOZHINGANALLUR,199,905000,"RESTORATION OF ROADCUT USING CC AND BT AT DR RAJAN SALAI , VOC STREET LENIN STREET IN DN 199, U44, Z15",Deposit Works,15,2016-17,2017-18 BR/2016-17/6177,Buildings,Completed,BR-Bus Route Roads,200,3551000,"ROAD CUT RESTORATION WORK AT NOOKAMPALAYAM MAIN ROAD DONE BY CMWSSB IN DIVISION 200, ZONE 15",Deposit Works,15,2016-17,2017-18 L/2016-17/13717,Electrical,Completed,L-Electrical,200,175300,"Proposed Painting of 914 nos of 6 mtr with single straight bracket street lamp post,90 nos of 6 mtr with single rch bracket street lamp post & 26 Nos of Kiosk Pillar boxes and Numbering of 1004 nos of street lamp post at various location in Dn-200 in zone-15.",Own Sources,15,2016-17,2017-18 L/2016-17/13719,Electrical,Completed,L-Electrical,200,157500,"Proposed to Relocate 15 nos of 6 mtr street lamp post with single straight bracket,Erection of coventional type of 10 nos of 6mtr lamp post with single straight bracket and contruct 30 nos of new plane cement concrete pedestal for street lamp post due to aging and road widening at Tsunami Nagar and Various location in Dn 200 in Zone-XV.",Own Sources,15,2016-17,2017-18 L/2016-17/13883,Electrical,Completed,L-Electrical,200,181800,Replacement of 570 mtr of 2X16 Sqmm damaged cable in Tsunami Kudiirruppu 9th avenue road and cross streets in Dn 200 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13884,Electrical,Completed,L-Electrical,200,188200,Replacement of 590 mtr of 2X16 Sqmm damaged cable in Tsunami Kudiirruppu 5th avenue road and cross streets in Dn 200 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13885,Electrical,Completed,L-Electrical,200,194900,Replacement of 610 mtr of 2X16 Sqmm damaged cable in Tsunami Kudiirruppu 3 rd avenue road and cross streets in Dn 200 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13886,Electrical,Completed,L-Electrical,200,195400,Replacement of 620 mtr of 2X16 Sqmm damaged cable in Tsunami Kudiirruppu 6th avenue road and cross streets in Dn 200 in Zone-XV.,Own Sources,15,2016-17,2017-18 L/2016-17/13887,Electrical,Completed,L-Electrical,200,198000,"Replacement of 220 mtr of 4X16 Sqmm,320 mtr of 2X16 damaged cable in Tsunami Kuddiirruppu 2nd main road and 8 th avenue road in Dn 200 in Zone-XV.",Own Sources,15,2016-17,2017-18 NQ/2016-17/0539,Buildings,Completed,NQ-SHOZHINGANALLUR,200,373000,"ADDITIONAL IMPROVEMENTS TO UPHC FOR PROVIDING FALSE CEILING AND ELECTRICAL WORKS AT TNSCB 1ST MAIN ROAD IN DN 200,U45,Z15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0570,Buildings,Completed,NQ-SHOZHINGANALLUR,200,239000,"IMPROVEMENTS TO TSUNAMI NAGAR PARK BY PROVIDING PLAY APPARATUS AT TNSCB 1ST MAIN ROAD,SEMMENCHERY IN DN 200, U45, Z15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0682,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,989000,"DESILTING OF SIDE DRAIN INCLUDING REMOVING AND REFIXING OF CC SLAB IN ALL CROSS STREETS OF TNSCB -SEMMENCHERRY AND REPAIR WORK SIDE DRAIN BAJANAI KOIL STREET IN DN200,U45,Z15",Own Sources,15,2016-17,2016-17 NQ/2016-17/0683,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,980000,"DESILTING OF SWD AND SIDE DRAIN INCLUDING DISMANTLING EXISTING SLAB AND RECASTING INCLUDING PROVISION OF HUMEPIPE INTER CONNECTION WORKS ETC.,TNSCB MAIN ROAD AND AVENUE STREETS IN DN 200, U45,Z15",Own Sources,15,2016-17,2016-17 NQ/2016-17/11926,Buildings,Completed,NQ-SHOZHINGANALLUR,200,230000,"IMPROVEMENTS TO PU MIDDLE SCHOOL AND PU PRIMARY SCHOOL AT SEMMENCHERRY FOR ULB ELECTION 2016 IN DN 200, U45, Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/11928,Buildings,Completed,NQ-SHOZHINGANALLUR,200,520000,IMPROVEMENT TO PARK AND REPAIRS TO PLAY APPRATUS IN 7TH CROSS ST &15THCROSS STREET ( TNSCB ) CHEMENCHERRY INDN200 UNIT45 ZONE15,Own Sources,15,2016-17,2017-18 NQ/2016-17/11929,Buildings,Completed,NQ-SHOZHINGANALLUR,200,520000,IMPROVEMENT TO PARK AND REPAIRS TO PLAY APPRATUS IN 52ND CROSS ST &25THCROSS STREET ( TNSCB ) CHEMENCHERRY INDN200 UNIT45 ZONE15,Own Sources,15,2016-17,2017-18 NQ/2016-17/11930,Buildings,Completed,NQ-SHOZHINGANALLUR,200,520000,IMPROVEMENT TO PARK AND REPAIRS TO PLAY APPRATUS IN 64TH CROSS ST &78TH STCROSS STREET ( TNSCB ) CHEMENCHERRY INDN200 UNIT45 ZONE15,Own Sources,15,2016-17,2017-18 NQ/2016-17/11931,Buildings,Completed,NQ-SHOZHINGANALLUR,200,520000,IMPROVEMENT TO PARK AND REPAIRS TO PLAY APPRATUS IN 85TH CROSS ST & 89TH STCROSS STREET ( TNSCB ) CHEMENCHERRY INDN200 UNIT45 ZONE15,Own Sources,15,2016-17,2017-18 NQ/2016-17/11932,Buildings,Completed,NQ-SHOZHINGANALLUR,200,997000,IMPROVEMENT TO PARK AND REPAIRS TO PLAY APPRATUS IN BHARATHI NAGAR AND ANNASTREET CHEMENCHERRY IN DN200 UNIT45 ZONE15,Own Sources,15,2016-17,2017-18 NQ/2016-17/16472,Buildings,Completed,NQ-SHOZHINGANALLUR,200,160000,"REPAIR WORKS TO STREET FURNITURE AT VARIOUS STREETS IN DN 200, U45, Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16473,Buildings,Completed,NQ-SHOZHINGANALLUR,200,360000,"IMPROVEMENTS TO UPHC DUE TO VARDHA CYCLONE AT TSUNAMI NAGAR 1ST MAIN ROAD IN DN 200, U45, Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/16474,Buildings,Completed,NQ-SHOZHINGANALLUR,200,420000,"REPAIR WORKS TO PARK DUE TO VARDHA CYCLONE AT TSUNAMI NAGAR 1ST MAIN ROAD IN DN 200 , U45, Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/18994,Buildings,Completed,B-Buildings,200,399500,"Additional improvement to compound wall, Aluminium partition and painting work at UPHC in Dn-200,U-45,Z-15.",Own Sources,15,2016-17,2017-18 NQ/2016-17/3546,Buildings,Completed,B-Buildings,200,235000,"ADDITIONAL IMPROVEMENTS TO UPHC BY PROVIDING PAINTING WORKS ETC., AT TNSCB 1ST MAIN ROAD IN DN 200, U45,Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/3572,Parks,Completed,NQ-SHOZHINGANALLUR,200,630000,"OUTSOURCING MAINTENANCE OF PARKS FOR 12 MONTHS AT TNSCB 1st MAIN ROAD PARK IN DN 200 ,U45, Z15",Own Sources,15,2016-17,2018-19 NQ/2016-17/3574,Parks,Completed,NQ-SHOZHINGANALLUR,200,215000,"OUTSOURCING MAINTENANCE OF PARKS FOR12 MONTHS AT TNSCB 33rd CROSS STREET PARK IN DN 200 ,U45 , Z15",Own Sources,15,2016-17,2018-19 NQ/2016-17/3976,Buildings,Completed,NQ-SHOZHINGANALLUR,200,997000,CONSTRUCTION OF 16th DAY CREMATION BUILDING AT (TNSCB) 2nd MAIN ROAD CHEMEN CHEERY IN DN 200 UNIT 45 ZONE 15,Own Sources,15,2016-17,2016-17 NQ/2016-17/6018,Buildings,Completed,NQ-SHOZHINGANALLUR,200,400000,"REFIXING OF STICKER IN STREET FURNITURE FOR VARIOUS STREETS IN DN 200, U45,Z15",Own Sources,15,2016-17,2017-18 NQ/2016-17/6397,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,730000,"FABRICATION OF PRECAST MOULD FOR SIDE DRAIN AT BAJANAI KOIL STREET IN DN 200, U45, Z15",Own Sources,15,2016-17,2016-17 NQ/2016-17/6566,Road Cut,Completed,NQ-SHOZHINGANALLUR,200,990000,"RESTORATION OF ROADCUT USING CC AND BT AT PAZHATHOTTA SALAI,TNSCB 8TH CROSS STREET AND BHARATHI NAGAR CROSSING IN DN 200, U44, Z15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/6567,Road Cut,Completed,NQ-SHOZHINGANALLUR,200,995000,"RESTORATION OF ROADCUT USING CC AND BT AT TNSCB 5TH AVENUE,6TH MAIN ROAD AND CROSS STREETS IN DN 200, U45, Z15",Deposit Works,15,2016-17,2017-18 NQ/2016-17/7523,Buildings,Completed,NQ-SHOZHINGANALLUR,200,256000,PROVIDING AND SUPPLYING FRC DOORS AT VARIOUS PLACE IN DN200 UNIT 45 ZONE15,Own Sources,15,2016-17,2017-18 NQ/2016-17/7787,Buildings,Completed,NQ-SHOZHINGANALLUR,200,998000,"Construction of toilet block (3+1 seater) FOR GENTS at TNSCB 7th Avenue (Near bus terminus) in Dn.200, U-45, zone 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7788,Buildings,Completed,NQ-SHOZHINGANALLUR,200,993000,"Improvement to toilet block at Pandhicherry pattai salai in Dn.200, U-45, zone 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7789,Buildings,Completed,NQ-SHOZHINGANALLUR,200,980000,"Improvement to toilet block at Veeravanchinathan Salai in Dn.200, Unit-45, zone 15",Own Sources,15,2016-17,2017-18 NQ/2016-17/7791,Buildings,Completed,NQ-SHOZHINGANALLUR,200,490000,"IMPROVEMENTS TO COMPOSITE YARD BY PROVIDING ELECTRICAL,PLUMBING AND PAINTING WORKS IN DN-200, U-45, Z-15",Own Sources,15,2016-17,2017-18 NQ/2016-17/9717,Buildings,Completed,NQ-SHOZHINGANALLUR,200,780000,"Renovation of shed into Amma unavagam 3 including dining table etc in Pazhathotta salai, Chemmencherry in Dn.200, Unit-45, zone 15",Own Sources,15,2016-17,2016-17 B/2016-17/13446,Buildings,Completed,B-Buildings,,122523472,"Construction of Community Health Centre at VOC Street, Injambakkam in Dn 196, Zone -15.",Own Sources,Greater Chennai Corporation,2016-17,2020-21 J/2016-17/0853,RUB,Completed,J-Bridges,,998000,"Improvement to the Riding surface and Foot path of existing Ganesapuram subway in Dr.Ambedkar college road, Div -45 & 70, Zone-IV &VI",Own Sources,Greater Chennai Corporation,2016-17,2016-17 J/2016-17/11321,RUB,Completed,J-Bridges,,900000,"ADDITIONAL IMPROVEMENTS TO THE RIDING SURFACE AND FOOT PATH OF EXISTING GANESHAPURAM SUBWAY IN Dr.AMBEDKAR COLLEGE ROAD IN DIVISION 45 AND 70, ZONE- IV & VI",Own Sources,Greater Chennai Corporation,2016-17,2016-17 J/2016-17/12808,Bridges,Completed,J-Bridges,,224000,"Painting to the existing steel foot over bridge at thaluka office road ,saidapet ,in Dn:171,Zone-XIII",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/12894,Bridges,Completed,J-Bridges,,167000,"Re-Construction of Enterance Pillar, Providing Anti crash barrier and Dr.Muthulakshmi salai junction of sardar patel road at Dn:175 and Wearing coat patch work at gandhi mandapam road junction of sardar patel road flyover Dn:171&172,Zone-13.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/13704,Bridges,Completed,J-Bridges,,17824000,"Construction of 4 vent Box Culvert across Kodungaiyur canal connecting T.H Road and Dumping ground in Division: 37, Zone -IV",Own Sources,Greater Chennai Corporation,2016-17,2018-19 J/2016-17/17848,RUB,Completed,J-Bridges,,3323000,"REPAIR AND RE LAYING OF WEARINGCOAT TO MADLEY ROAD SUBWAY IN DN-135&136, ZONE -X",Grants,Greater Chennai Corporation,2016-17,2018-19 J/2016-17/18342,Bridges,Completed,J-Bridges,,6875000,"Improvement to damaged revetment in Vaidyanathan Bridge Division-38, Zone-IV",Grants,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/18767,Bridges,Completed,J-Bridges,,516000,REPAIR AND RE-CONSTRUCTION OF HANDRAILWALL IN EXISTING BRIDGE ACROSS MAMBALAM CANAL AT VIJAYARAGHAVA ROAD IN DN- 117- ZONE -IX.,Grants,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/18813,Bridges,Completed,J-Bridges,,1010000,REPAIR AND RE-CONSTRUCTION OF HANDRAILWALL IN EXISTING BRIDGE ACROSS MAMBALAM CANAL AT G.N.CHETTY ROAD IN DN- 113- ZONE -IX.,Grants,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/19385,Bridges,Completed,J-Bridges,,561000,Construction of Anti crash barrier to the existing bridge at Aspiran garden 2nd st across Otteri nullah at Dn -98 Zone -VIII and Providing Anticarash barrier and traffic signage board in the existing flyover at C.P.Ramasamy road & junction of T.T.K.road in dn -118 and Zone -IX,Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4580,Subway,Completed,J-Bridges,,606000,"Providing Hump at the entrance of the subway, to avoid entry of surface water during rainfall at Aranganathan subway in Dn-171, Unit-40, Zone-XIII.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4581,Subway,Completed,J-Bridges,,348000,"Providing hump at the entrance of the subway to avoid entry od surface water during rainfall at Bazzar road subway in Dn-142, Zone-X.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4583,Subway,Completed,J-Bridges,,610000,"Providing hump at the entrance of the subway to avoid entry of surface water during rainfall at Duraisamy subway in Dn-136, Zone-X.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4586,Subway,Completed,J-Bridges,,355000,"Providing hump at the entrance of the subway to avoid entry of surface water during rainfall at Jones road subway in Dn-142, Zone-X.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4588,Subway,Completed,J-Bridges,,475000,"Providing hump at the entrance of the subway to avoid entry surface water during rainfall at madley road subway in Dn-135, Zone-X.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4594,Subway,Completed,J-Bridges,,604000,"Providing hump at the entrance of the subway to avoid entry of surface water during rainfall the Ganeshapuram subway in Dn-45 & 70,Zone-4 &6.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4600,Subway,Completed,J-Bridges,,559000,"Providing hump at the entrance of the subway to avoid entry of surface water during rainfall at M.C. road subway in Dn- 52, Zone-V.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4611,Subway,Completed,J-Bridges,,325000,"Providing hump at the entrance of the subway to avoid entry of surface water during rainfall at RBI subway in Dn-60, Zone-V.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/4618,Subway,Completed,J-Bridges,,1096000,"Providing hump at the entrance of the subway to avoid entry of surface water during rainfall at villivakkam LC2 subway in Dn-94, Zone-8.",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/6456,Bridges,Completed,J-Bridges,,866000,"Improvement to existing foot bridge across buckhingham canal at Palani amman koil Ist street connecting canal road and kamarajsalai in div 116, Zone-IX",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/6520,Bridges,Completed,J-Bridges,,912000,"Improvements to existing bridge across buckhingham canal at Triplicane connecting sunguvar street and Ayodhya nagar in div-116,zone- IX",Own Sources,Greater Chennai Corporation,2016-17,2017-18 J/2016-17/8728,Grade Separator,Completed,J-Bridges,,995000,"Dismantling the existng Barrier wall under the flyover and converting portion as a vehicle parking area at Northusman road and Mahalingapuram flyover Dn-110&113, Zone -9",Own Sources,Greater Chennai Corporation,2016-17,2017-18 BR/2016-17/17719,Roads,Completed,BR-Bus Route Roads,,1670000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters due to Vardha Cyclone in North east Monsoon 2016 at Thiruvottiyur Ponneri panchetti road, Ennore express way,Thiruvottiyur high road, Kathivakkam high road and Basin road Zone-1",Grants,1,2016-17,2017-18 NB/2016-17/16001,Parks,Completed,NB-MANALI,,840000,PLANTING OF TREE SAPLINGS DUE TO DAMAGES OCCURRED DURING VARDAH CYCLONE IN ZONE -2 (MANALI),Own Sources,2,2016-17,2017-18 B/2016-17/3561,Buildings,Completed,B-Buildings,,5400000,"CONSTRUCTION OF DIVISION OFFICE BUILDING 26 AT THANIGACHALAM NAGAR ,3RD STREET IN DIV 26 ZONE - III",Own Sources,3,2016-17,2017-18 B/2016-17/3874,Buildings,Completed,B-Buildings,,5400000,CONSTRUCTION OF DIVISION OFFICE BUILDING 25 IN RETTAIMALAI SRINIVASAN STREET IN DIV 25 ZONE - III,Own Sources,3,2016-17,2017-18 B/2016-17/13242,Buildings,Completed,B-Buildings,,7500000,"PROPOSED CONSTRUCTION OF NUHM HOSPITAL BUILDING AT ADHAM STREET IN DIVISION-60, ZONE-5.",Own Sources,5,2016-17,2018-19 D/2016-17/2823,Storm Water Drain,Completed,D-Storm Water Drains,,4855000,"Construction of RCC BOX Type Storm Water Drain of Size 1200x1200 along Varadharajan Street, Vetri Nagar Extn from Kumaran Nagar 3rd Street to 80 Feet Road, Thanichalam Nagar, PWD Canal in Dn-66,Zone-VI",Earmarked Fund,6,2016-17,2017-18 D/2016-17/3077,Storm Water Drain,Completed,D-Storm Water Drains,,2456000,"Construction of storm water Drain of size 900x900mm along Poombukar Nagar 4th Street from Poombukar Nagar II Cross Street to Poombukar Nagar II Main Road in Dn-64,Zone-VI",Own Sources,6,2016-17,2016-17 D/2016-17/3087,Storm Water Drain,Completed,D-Storm Water Drains,,4596000,"Construction of storm water Drain of size 900x900mm along Adhiamman Nagar&Rajiv Ganthi Street from Avvai Street to Valmigi Street in Dn-65,Zone-VI.",Own Sources,6,2016-17,2016-17 L/2016-17/19453,Electrical,Completed,L-Electrical,,149100,"Erection Materials for 5Nos of IP Bullet Camera to be fixed in Chennai Higher Secondary School, Subrayan street in Dn-107, Zone-VIII area.",Own Sources,8,2016-17,2019-20 L/2016-17/19455,Electrical,Completed,L-Electrical,,181400,"Provision of 5 nos. of IP Bullet Camera at Chennai Higher Secondary School, Subrayan Street in Division - 107, Zone - VIII area.",Own Sources,8,2016-17,2019-20 BR/2016-17/12183,Roads,Completed,BR-Bus Route Roads,,580000,"ATTENDING PATCH WORK FOR FOOTPATH PORTION AT TALUK OFFICE ROAD ,SARDAR PATEL ROAD , DURGA BAI DESH MUK ROAD , DR DINAKARAN SALAI,GANDHIMANDAPAM ROAD IN ZONE-13.",Own Sources,13,2016-17,2017-18 BR/2016-17/12184,Roads,Completed,BR-Bus Route Roads,,899000,"Attending Patch work to Damaged portions and Proposed speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Sardar Patel Road, Durgabai Deshmukh Road, R.K. Mutt Road and Dr. D.G.S. Dinakaran Salai in Dn-173, Zone-13.",Own Sources,13,2016-17,2016-17 BR/2016-17/6178,Footpath,Completed,BR-Bus Route Roads,,976600,"RESTORATION OF FOOTPATH AND ROAD AT SARDARPATEL ROAD CABLE LAYING WORK DONE BY SERVICE DEPARTMENT IN ZONE 13, DIVSION - 171 & 175.",Deposit Works,13,2016-17,2017-18 BR/2016-17/6507,Roads,Completed,BR-Bus Route Roads,,990000,Supplying and fixing of Front facia & Back drop in the stainless steel Bus shelter at various bus route roads in zone - 13,Own Sources,13,2016-17,2018-19 B/2017-18/8384,Buildings,Completed,B-Buildings,1,3544000,Construction of Conventional toilet in 3 locations with 17 seats in Zone 1 and Zone 2.,Own Sources,1,2017-18,2020-21 BR/2017-18/0321,Road Cut,Completed,BR-Bus Route Roads,1,129000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Division-14 Zone -1 For the challan no-B.R.R.C.NO.B4/0422/2016,Deposit Works,1,2017-18,2018-19 L/2017-18/12400,Electrical,Completed,L-Electrical,1,6975000,"Proposal for the provision of 150 nos. of 6 mtr posts with LED fittings as 85 nos. of 6mtr GI lamp post with single straight bracket (with Hot Dip Zinc Galvanise) with 40-50w LED fittings and 65 nos. of 6mtr GI lamp post with single arch bracket (with Hot Dip Zinc Galvanise) with 90-120w LED fittings at various location in Dn. 1, 2, 3, 4, 6, 11 and 14 in Zone-I.","Loans, Grants And Own Sources",1,2017-18,2018-19 L/2017-18/9619,Electrical,Completed,L-Electrical,1,266000,"Numbering of 11720 nos. of 6 and 8 mtr street lamp posts from divisions 1 to 14 in zone-I, Tiruvottriyur",Own Sources,1,2017-18,2018-19 L/2017-18/9621,Electrical,Completed,L-Electrical,1,277000,"Removal and Re-fixing of 168 nos. of damaged and rusted brackets with 1 meter long G.I single straight brackets in Bus Route Roads near sea shore areas in divisions 1, 2, 3, 9, 11 and 14 in Zone-I, Tiruvottiryur",Own Sources,1,2017-18,2018-19 NA/2017-18/0583,Buildings,Completed,NA-THIRUVOTTIYUR,1,270000,"Proposed Construction of Segregation Shed and Compost Yard in Division-1, Unit-1, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/10226,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,98000,"Providing of PVC drain with Inspection Chamber at Ennore Express Road from chainage 0.00 TO 100.00 (Thalankkupam ) in Division- 01,Unit -01 ,Zone -1",Own Sources,1,2017-18,2017-18 NA/2017-18/10232,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,99000,"Providing of PVC drain with Inspection Chamber at Ennore Express Road from chainage 100.00 to 180.00 (Thalankkupam) in Division- 01, Unit -01, Zone -01",Own Sources,1,2017-18,2017-18 NA/2017-18/6292,Road Cut,Completed,NA-THIRUVOTTIYUR,1,163000,"Improvements to the Interior B.T road at JJ Nagar 1st Block in Div -1, Unit-1, Zone-1",Own Sources,1,2017-18,2018-19 NA/2017-18/6294,Road Cut,Completed,NA-THIRUVOTTIYUR,1,157000,"Improvement to the Interior BT road at JJ Nagar 2nd Block in Div 1, Unit-1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6295,Road Cut,Completed,NA-THIRUVOTTIYUR,1,114000,"Improvement to the Interior BT road at JJ Nagar 3 Block in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6296,Road Cut,Completed,NA-THIRUVOTTIYUR,1,110000,"Improvement to the Interior B.T road at JJ Nagr 4th Block in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6297,Road Cut,Completed,NA-THIRUVOTTIYUR,1,99000,"Improvement to the Interior BT road at JJ Nagr 5th Block in Div 1, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6298,Road Cut,Completed,NA-THIRUVOTTIYUR,1,71000,"Improvement to the Interior B T road at JJ Nagar 8th Block in Div 1, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6299,Road Cut,Completed,NA-THIRUVOTTIYUR,1,88000,"Improvement to the Interior BT road at JJ Nagar 9th Block in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6300,Road Cut,Completed,NA-THIRUVOTTIYUR,1,133000,"Improvement to the Interior B T road at JJ Nagr 10th Block in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6301,Road Cut,Completed,NA-THIRUVOTTIYUR,1,127000,"Improvement to the Interior BT road at JJ Nagr 11th Block in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6302,Road Cut,Completed,NA-THIRUVOTTIYUR,1,91000,"Improvement to the Interior BT road at JJ Nagar 13th Block in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6303,Road Cut,Completed,NA-THIRUVOTTIYUR,1,110000,"Improvement to the Interior CC road at JJ Nagar 14th Block in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6308,Road Cut,Completed,NA-THIRUVOTTIYUR,1,926000,"Improvement to the Interior BT road at Kamaraj Nagar 8th Street in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6311,Roads,Completed,NA-THIRUVOTTIYUR,1,1763000,"Improvements to the Interior BT Road at Ulaganathapuram main Road in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6315,Road Cut,Completed,NA-THIRUVOTTIYUR,1,2261000,"Improvement to Interior C.C road at Donbosco school road 1st and 2nd street in Div 1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6317,Road Cut,Completed,NA-THIRUVOTTIYUR,1,159000,"Improvement to the Interior C.C road at JJ nagar 6th Block in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6325,Road Cut,Completed,NA-THIRUVOTTIYUR,1,88000,"Improvement to the Interior C.C road at JJ nagar 7th Block in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6328,Road Cut,Completed,NA-THIRUVOTTIYUR,1,159000,"Improvement to the Interior CC road at JJ nagar 12th Block in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6329,Road Cut,Completed,NA-THIRUVOTTIYUR,1,900000,"Improvement to the Interior CC road at Kamaraj nagar 1st street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6331,Road Cut,Completed,NA-THIRUVOTTIYUR,1,195000,"Improvements to the Interior at CC Roadcut made by CMWSSB at Kamaraj nagar 1st cross street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6332,Road Cut,Completed,NA-THIRUVOTTIYUR,1,1060000,"Improvement to the Interior CC road at Kamaraj nagar 2nd street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6333,Road Cut,Completed,NA-THIRUVOTTIYUR,1,1136000,"Improvement to the Interior CC road at Kamaraj nagar 3rd street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6334,Road Cut,Completed,NA-THIRUVOTTIYUR,1,956000,"Improvement to the Interior CC road at Kamaraj nagar 4th street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6335,Road Cut,Completed,NA-THIRUVOTTIYUR,1,742000,"Improvement to the Interior CC road at Kamaraj nagar 9th street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6336,Road Cut,Completed,NA-THIRUVOTTIYUR,1,180000,"Improvement to the Interior CC road at Kamaraj nagar 10th street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6348,Road Cut,Completed,NA-THIRUVOTTIYUR,1,847000,"Improvement to the Interior CC road at JJ nagar main road in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6349,Road Cut,Completed,NA-THIRUVOTTIYUR,1,532000,"Improvement to the Interior CC road at JJ nagar 1st cross street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6350,Road Cut,Completed,NA-THIRUVOTTIYUR,1,600000,"Improvement to the Interior CC road at JJ nagar main road to Kamaraj nagar 2nd street in Dn-1, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/8168,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,294000,"Desilting of Open Drain and SWD at Various Road (No of Road -72 ,Length -17071m) in Division -1 , Unit-1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/0584,Buildings,Completed,NA-THIRUVOTTIYUR,2,174000,"Construction and Additional works of segregation shed in Division-2, Unit-1, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/10379,Roads,Completed,NA-THIRUVOTTIYUR,2,91000,"Laying of PVC Pipe line for Amma Unavagam and Repair Work for School Building at KH Road in Division -02 ,Unit -01,Zone -01",Own Sources,1,2017-18,2018-19 NA/2017-18/2325,Roads,Completed,NA-THIRUVOTTIYUR,2,632000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SOUTH LOCK GATE ROAD IN DIVISION-02, UNIT-01, ZONE-01.",Own Sources,1,2017-18,2018-19 NA/2017-18/2363,Roads,Completed,NA-THIRUVOTTIYUR,2,1000000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ANNA NAGAR 1ST STREET IN DIVISION-2, UNIT-1, ZONE-1",Own Sources,1,2017-18,2018-19 NA/2017-18/6245,Road Cut,Completed,NA-THIRUVOTTIYUR,2,381000,"Improvement to the interior C.C road at Vinayagar koil Street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6249,Road Cut,Completed,NA-THIRUVOTTIYUR,2,512000,"Improvement to the interior C.C road at Sivan padai village road in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6252,Road Cut,Completed,NA-THIRUVOTTIYUR,2,868000,"Improvement to the interior C.C road at Sivan padai veethi in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6254,Road Cut,Completed,NA-THIRUVOTTIYUR,2,426000,"Improvement to the interior C.C road at Kattukuppam 5th street in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6256,Road Cut,Completed,NA-THIRUVOTTIYUR,2,423000,"Improvement to the interior C.C road at Kattukuppam 4th street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6259,Road Cut,Completed,NA-THIRUVOTTIYUR,2,409000,"Improvement to the interior C.C road at Kattukuppam 3rd street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6261,Road Cut,Completed,NA-THIRUVOTTIYUR,2,353000,"Improvement to the interior C.C road at Kattukuppam 2nd street in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6262,Road Cut,Completed,NA-THIRUVOTTIYUR,2,487000,"Improvement to the interior C.C road at Kattukuppam 1st street in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6263,Road Cut,Completed,NA-THIRUVOTTIYUR,2,300000,"Improvement to the interior C.C road at Kamaraj nagar 7th street in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6264,Road Cut,Completed,NA-THIRUVOTTIYUR,2,896000,"Improvement to the interior C.C road at Kamaraj nagar 6th street in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6265,Road Cut,Completed,NA-THIRUVOTTIYUR,2,952000,"Improvement to the Interior C.C road at Kamaraj nagar 5th street in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6266,Road Cut,Completed,NA-THIRUVOTTIYUR,2,317000,"Improvement to the Interior C.C road at Anna nagar 2nd street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6267,Road Cut,Completed,NA-THIRUVOTTIYUR,2,486000,"Improvement to the Interior C.C road at Manamakil mandram street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6268,Road Cut,Completed,NA-THIRUVOTTIYUR,2,527000,"Improvement to the Interior C.C road at Sasthiri nagar in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6269,Road Cut,Completed,NA-THIRUVOTTIYUR,2,183000,"Improvement to the interior C.C road at Manamakil mandram cross street in Div 2, Unit 1, Zone 1.",Own Sources,1,2017-18,2018-19 NA/2017-18/6316,Road Cut,Completed,NA-THIRUVOTTIYUR,2,1319000,"Improvement to Interior C.C road at Sweepers colony Railway station road in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6318,Road Cut,Completed,NA-THIRUVOTTIYUR,2,404000,"Improvement to the interior C.C road at Railway Station Road in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6319,Road Cut,Completed,NA-THIRUVOTTIYUR,2,830000,"Improvement to the Interior B.T road at Gandhi Nagar Main Road (Hospital Road) in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6320,Road Cut,Completed,NA-THIRUVOTTIYUR,2,564000,"Improvement to the Interior B.T road at EK Cross Street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6321,Road Cut,Completed,NA-THIRUVOTTIYUR,2,452000,"Improvement to the interior B.T road at Sasthiri nagar 1st Street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6322,Road Cut,Completed,NA-THIRUVOTTIYUR,2,400000,"Improvement to the interior B.T road at Nehru nagar 1st street in Div 2, Unit 1,Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6323,Road Cut,Completed,NA-THIRUVOTTIYUR,2,469000,"Improvement to the interior B.T road at Ulaganathan Park Street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6326,Road Cut,Completed,NA-THIRUVOTTIYUR,2,529000,"Improvement to the interior B.T road at Nehru nagar 3rd Street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6327,Road Cut,Completed,NA-THIRUVOTTIYUR,2,812000,"Improvement to the interior B.T road Ellaimman Koil Street in Div 2, Unit 1, Zone 1",Own Sources,1,2017-18,2018-19 NA/2017-18/6615,Buildings,Completed,NA-THIRUVOTTIYUR,2,376000,"REPAIRING AND IMPROVEMENT OF OPEN SIDE DRAIN AT VALLUVAR NAGAR ,INDIRA NAGR & THILAGAR NAGAR IN DIV-2,UNIT-1,ZONE-1",Own Sources,1,2017-18,2018-19 NA/2017-18/8179,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,225000,"Desilting of Open Drain at Various Road (94 Roads) and SWD at Kathivakkam High Road(Kothari Road to Anna Nagar) in Div 2, Unit 1 ,Zone -1",Own Sources,1,2017-18,2018-19 NA/2017-18/8455,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,336000,"Repairing Work for Open Drain at Various Road in Division -1, Unit -01, Zone -01",Own Sources,1,2017-18,2018-19 NA/2017-18/0579,Buildings,Completed,NA-THIRUVOTTIYUR,3,270000,"Proposed Construction of Segregation Shed and Composed Yard at Tsunami Quarters in Dn-3,Unit-1,Zone-1",Own Sources,1,2017-18,2018-19 NA/2017-18/10302,Buildings,Completed,NA-THIRUVOTTIYUR,3,95800,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT ANNAI SIVAGAMI NAGAR IN DN-3,UNIT-1,ZONE-1",Own Sources,1,2017-18,2018-19 NA/2017-18/7864,Roads,Completed,NA-THIRUVOTTIYUR,3,1118000,"IMPROVEMENT TO INTERIOR C.C ROAD AT NETAJI NAGAR EAST CROSS STREET IN DN-3, UNIT-1, ZONE-1 (L=209M X W=3.90M A=815 Sqm)",Own Sources,1,2017-18,2018-19 NA/2017-18/7865,Roads,Completed,NA-THIRUVOTTIYUR,3,1337000,"IMPROVEMENT TO INTERIOR C.C ROAD AT TKP NAGAR 1ST MAIN STREET, 2ND MAIN STREET, 1ST AND 2ND CROSS STREET IN DN-3,UNIT-1,ZONE-1(L=336M X Ws=3.00M A=1008Sqm)",Own Sources,1,2017-18,2018-19 NA/2017-18/0572,Buildings,Completed,NA-THIRUVOTTIYUR,4,255000,"Proposed Source Segregation shed and compost yard at Thiruveethiamman koil 5th st, Eranavoor in Division-4, Unit-1, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/13141,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,499000,"Providing the Top cover slab in open side drain at Thiruveethiamman koil 5th st, Ernavoor in Div-4, Unit-1, Zone-1.",Own Sources,1,2017-18,2019-20 NA/2017-18/1760,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,114000,"LAYING OF BUS STOP RAMPS AT VARIOUS LOCATION AND SUPPLY OF WELL RING FOR COMPOST IN DIV-4, UNIT-1, ZONE-1",Own Sources,1,2017-18,2017-18 NA/2017-18/7410,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,307000,"Desilting of SWD and side drain at various streets in Div-4, Unit-1, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/8310,Buildings,Completed,NA-THIRUVOTTIYUR,4,70000,"Repair and maintenance work to Amma unavagam PHASE 2 at K.H.road, Kamaraj & Chennai primary school at Eranavoor in Div-4, Unit-1, Zone-1",Own Sources,1,2017-18,2018-19 NA/2017-18/9020,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,224000,"Repair and improvement of Open Drain and Storm Water Drain in Division-04, Unit-01, Zone -01",Own Sources,1,2017-18,2018-19 BR/2017-18/11372,Roads,Completed,BR-Bus Route Roads,5,29700,Restoration of road cut made by CMWSSB at Thiruvottiyur High Road in Zone-5 against challan no. BR/2017-18/0003602,Deposit Works,1,2017-18,2018-19 L/2017-18/10023,Electrical,Completed,L-Electrical,5,49400,"Removal of 25 nos. of OH post at Tiruvottiyur High Road near Ajax Bus Stand to Wimco nagar in Dn-5, Zone-I",Deposit Works,1,2017-18,2018-19 NA/2017-18/0556,Buildings,Completed,NA-THIRUVOTTIYUR,5,277000,"Proposed Construction of Segregation Shed and Composed Yard at Ramakrishna nagar in Dn-5, Unit-2, Zone-1",Own Sources,1,2017-18,2018-19 NA/2017-18/0582,Buildings,Completed,NA-THIRUVOTTIYUR,5,280000,"Proposed Construction of Segregation Shed and Composed Yard at Bharath nagar near PC,Lift gate,Ernavoor in Dn-5,Unit-2,Zone-1",Own Sources,1,2017-18,2018-19 NA/2017-18/0258,Buildings,Completed,NA-THIRUVOTTIYUR,6,730000,"Improvements to division office at Jothi nagar 10th street in Div-6, Unit-2, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/0574,Buildings,Completed,NA-THIRUVOTTIYUR,6,255000,"PROPOSED SOURCE SEGREGATION SHED AND COMPOST YARD AT SATHIYAMOORTHY NAGAR B CANAL ROAD IN DIV -6 ,UNIT-2,ZONE-1.",Own Sources,1,2017-18,2018-19 B/2017-18/14550,Buildings,Completed,B-Buildings,7,26254547,"Additional works for the Lorry Operational Depot at Manali road, Thiruvottiyur in DN 7 Zone I",Own Sources,1,2017-18,2019-20 NA/2017-18/0704,Buildings,Completed,NA-THIRUVOTTIYUR,7,277000,"PROPOSED CONSTRUCTION OF SEGREGATION SHED AND COMPOSED YARD AT BALAKRISHNA NAGAR IN DIVISION-7, UNIT-2, ZONE-1",Own Sources,1,2017-18,2018-19 NA/2017-18/0707,Buildings,Completed,NA-THIRUVOTTIYUR,7,1828000,"CONSTRUCTION OF SEGREGATION SHED AND COMPOST YARD FOR DIVISIONS 10,11,12,13 AND 14 AT SATHANGADU DUMPING GROUND IN DIVISION 7",Own Sources,1,2017-18,2018-19 NA/2017-18/13281,Roads,Completed,NA-THIRUVOTTIYUR,7,3236000,"Improvement to the Interior B.T road at Glass factory road in Division-7, Unit-2, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/13349,Roads,Completed,NA-THIRUVOTTIYUR,7,969000,"Improvement to interior B.T road at Manickavel street in Division-7, Unit-2, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/13350,Roads,Completed,NA-THIRUVOTTIYUR,7,297000,"Improvement to interior B.T road at Manikavel cross street in Division-7, Unit-2, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/13351,Roads,Completed,NA-THIRUVOTTIYUR,7,320000,"Improvement to interior B.T road at Kargil nagar main road in Division-7, Unit-2, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/0521,Buildings,Completed,NA-THIRUVOTTIYUR,8,454000,"Improvements and Maintenance work at Anganvadi, Periyar nagar, Bharathinagar, Kakanji nagar, S.P.Koil street in Div-8, Unit-2, Zone-I.",Own Sources,1,2017-18,2018-19 NA/2017-18/10875,Roads,Completed,NA-THIRUVOTTIYUR,8,475000,"Improvement to the Interior B.T road at Kakanji nagar in Division-8, Unit-2, Zone-1 (TURIF PHASE 1)",Own Sources,1,2017-18,2018-19 NA/2017-18/10876,Roads,Completed,NA-THIRUVOTTIYUR,8,1100000,"Improvement to the Interior B.T road at Old well road in Division-8, Unit-2, Zone-1 (TURIF PHASE 1)",Own Sources,1,2017-18,2018-19 NA/2017-18/10877,Roads,Completed,NA-THIRUVOTTIYUR,8,817000,"Improvement to the Interior B.T road at Periyar nagar in Division-8, Unit-2, Zone-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10878,Roads,Completed,NA-THIRUVOTTIYUR,8,383000,"Improvement to the Interior B.T road at Gangai nagar in Division-8, Unit-2, Zone-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/13121,Buildings,Completed,NA-THIRUVOTTIYUR,8,108000,"Maintenance in Division office at Periyar nagar in Div-8, Unit-2, Zone-I.",Own Sources,1,2017-18,2019-20 L/2017-18/11232,Electrical,Completed,L-Electrical,9,27000,"REMOVAL OF 13 NOS. OF 8 MTR G.I LAMP POSTS WITH 150w LED FITTINGS AT THIRUVOTTRIYUR HIGH ROAD (CENTRE MEDIAN-CMRL WORK, IN DN-9, ZONE-I, THIRUVOTTRIYUR [SOR-2015-16]",Deposit Works,1,2017-18,2019-20 L/2017-18/11462,Electrical,Completed,L-Electrical,9,56000,"Provision of 3 phase electrical mains supply with other electrical installations and availing new service connection for R.O-Water Plant at TNSCB area in Dn. 9, Zone-I.",Deposit Works,1,2017-18,2019-20 NA/2017-18/0553,Buildings,Completed,NA-THIRUVOTTIYUR,9,1074000,"REPAIR AND SERVICE OF GASIFIER EQUIPMENTS & MACHINERIES IN GREATER CHENNAI CORPORATION THIRUVOTTIYUR CREMATORIUM in DIV-09, UNIT-2, Zone-I.",Own Sources,1,2017-18,2017-18 NA/2017-18/10879,Roads,Completed,NA-THIRUVOTTIYUR,9,2258000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT APPARSAMY KOIL STREET IN DIVISION-9, UNIT-2, ZONE-1 (TURIF PHASE 1)",Own Sources,1,2017-18,2018-19 NA/2017-18/10880,Roads,Completed,NA-THIRUVOTTIYUR,9,5401000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD E AT VILLAGE STREET IN DIVISION-9, UNIT-2, ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10881,Roads,Completed,NA-THIRUVOTTIYUR,10,951000,IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NATARAJAN GARDEN 1ST STREET IN DN-10 UNIT-3 ZONE-1,Own Sources,1,2017-18,2018-19 NA/2017-18/10882,Roads,Completed,NA-THIRUVOTTIYUR,10,965000,IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SOUTH PRAGARAM STREET IN DN-10 UNIT-3 ZONE-1,Own Sources,1,2017-18,2018-19 NA/2017-18/10883,Roads,Completed,NA-THIRUVOTTIYUR,10,442000,IMPROVEMENT TO THE INTERIOR B.T. ROAD AT WEST MADA STREET IN DN-10 UNIT-3 ZONE-1,Own Sources,1,2017-18,2018-19 B/2017-18/0357,Buildings,Completed,B-Buildings,11,15416466,"PROPOSED CONSTRUCTION OF UPHC AT THIRUVOTRIYUR IN DIVISION-11, ZONE-1",Own Sources,1,2017-18,2020-21 B/2017-18/12170,Buildings,Completed,B-Buildings,11,48600000,ADDITIONAL CONSTRUCTION OF SECOND AND THIRD FLOOR OF COMMUNITY HEALTH CENTER (100 BED) THIRUVOTTIYUR IN DIV-11 ZONE I,Own Sources,1,2017-18,2020-21 L/2017-18/11465,Electrical,Completed,L-Electrical,11,163000,"Provision of 3 phase electrical mains supply board with other electrical installations and availing service connections for 20 KVA Disel Genset Enabled Bio-Gas plant at Tiruvalluvar Arangam in Dn.11, Zone-I.",Deposit Works,1,2017-18,2019-20 L/2017-18/12095,Electrical,Completed,L-Electrical,11,100000,"REMOVAL OF 28 NOS. OF 8 MTR G.I LAMP POST WITH 250W SVL FITTINGS AT THIRUVOTTRIYUR HIGH ROAD (FROM ROHIT HOSPITAL TO ELLAIAMMAN KOIL STREET IN DN-11, ZONE-I, TIRUVOTTRIYUR",Deposit Works,1,2017-18,2019-20 NA/2017-18/10860,Roads,Completed,NA-THIRUVOTTIYUR,11,1145000,"Improvement to the Interior B.T road at Periyamettupalayam in Division-11, Unit-3, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/10861,Roads,Completed,NA-THIRUVOTTIYUR,11,506000,"Improvement to the Interior B.T road at Janakiammal Estate in Division- 11, Unit-3, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/10862,Roads,Completed,NA-THIRUVOTTIYUR,11,1825000,"Improvement to the Interior B.T road at Chinamettupalayam 2nd street in Division- 11, Unit-3, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/10863,Roads,Completed,NA-THIRUVOTTIYUR,11,1353000,"Improvement to the Interior B.T road at Radhakrishnan nagar 2nd street in Division- 11, Unit-3, Zone-1 (Turif Phase 1)",Own Sources,1,2017-18,2018-19 NA/2017-18/10864,Roads,Completed,NA-THIRUVOTTIYUR,11,804000,"Improvement to the Interior B.T road at Radhakrishnan nagar 3rd street in Division-11, Unit-3, Zone-1 (Turif Phase 1)",Own Sources,1,2017-18,2018-19 NA/2017-18/7641,Roads,Completed,NA-THIRUVOTTIYUR,11,583000,"RELAYING OF THE ROAD AT ELLAI AMMAN KOIL STREET IN DIVISION-11, UNIT-3, ZONE-1.",Own Sources,1,2017-18,2017-18 NA/2017-18/13282,Roads,Completed,NA-THIRUVOTTIYUR,12,519000,"Improvement to the Interior B.T road at Kavarai cross street in Division-12, Unit-3, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/13283,Roads,Completed,NA-THIRUVOTTIYUR,12,578000,"Improvement to the Interior B.T road at Thilagar nagar 1st street (Extension) in Division-12, Unit-3, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/13284,Roads,Completed,NA-THIRUVOTTIYUR,12,1308000,"Improvement to the Interior B.T road at Thilagar nagar 1st street in Division-12, Unit-3, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/13285,Roads,Completed,NA-THIRUVOTTIYUR,12,385000,"Improvement to the Interior B.T road at Veeragavan street in Division-12, Unit-3, Zone-1.",Own Sources,1,2017-18,2018-19 NA/2017-18/10868,Roads,Completed,NA-THIRUVOTTIYUR,13,2795000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VARADARAJAN STREET IN DIVISION-13, UNIT-3 ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10869,Roads,Completed,NA-THIRUVOTTIYUR,13,4970000,"RIMPROVEMENT TO THE INTERIOR B.T. ROAD AT SESHACHALA GRAMINI STREET IN DIVISION-13, UNIT-3 ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10870,Roads,Completed,NA-THIRUVOTTIYUR,13,4135000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT METTU STREET IN DIVISION-13, UNIT-3 ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10871,Roads,Completed,NA-THIRUVOTTIYUR,13,2012000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT GANDHI NAGAR MAIN ROAD IN DIVISION-13, UNIT-3 ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10872,Roads,Completed,NA-THIRUVOTTIYUR,13,780000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT GANDHI NAGAR LINK ROAD IN DIVISION-13, UNIT-3 ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10873,Roads,Completed,NA-THIRUVOTTIYUR,13,740000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT GIRIJA NAGAR STREET IN DIVISION-13, UNIT-3 ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10874,Roads,Completed,NA-THIRUVOTTIYUR,13,1861000,"Improvement to the Interior B.T road at othavadai street in Division-13, Unit-3, Zone-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 B/2017-18/0336,Buildings,Completed,B-Buildings,14,9176333,"PROPOSED CONSTRUCTION FOR NUHM HOSPITAL BUILDING AT MALLIGAPURAM IN DIV-14,ZONE-1",Own Sources,1,2017-18,2020-21 BR/2017-18/4103,Roads,Completed,BR-Bus Route Roads,14,141000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -1 For the challan no-B.R.R.C.NO.B4/4618/2016,Deposit Works,1,2017-18,2018-19 BR/2017-18/4129,Roads,Completed,BR-Bus Route Roads,14,73700,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -1 For the challan no-B.R.R.C.NO.B4/2464/2016,Deposit Works,1,2017-18,2018-19 L/2017-18/11233,Electrical,Completed,L-Electrical,14,34000,"REMOVAL OF 16 NOS. OF 8 MTR G.I LAMP POSTS WITH 150w LED FITTINGS AT THIRUVOTTRIYUR HIGH ROAD (GOWRI ASRAM STATION CMRL WORK, AT CH. 6151.453 to CH. 6313.291) IN DN-9, ZONE-I, THIRUVOTTRIYUR [SOR-2015-16]",Deposit Works,1,2017-18,2019-20 L/2017-18/6583,Electrical,Completed,L-Electrical,14,75000,"Removal of 35 Nos. of 8 Mtr G.I Lamp Post with 250W SVL Fittings at Thiruvottiyur High Road (From Toll gate to Rohit Hospital) in Dn: 14, Zone-I",Deposit Works,1,2017-18,2018-19 NA/2017-18/10884,Roads,Completed,NA-THIRUVOTTIYUR,14,756000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ONDIKUPPAM 1ST STREET IN DIVISION-14, UNIT-3, ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10885,Roads,Completed,NA-THIRUVOTTIYUR,14,756000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ONDIKUPPAM 2ND STREET IN DIVISION-14, UNIT-3, ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10886,Roads,Completed,NA-THIRUVOTTIYUR,14,584000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ONDIKUPPAM 3RD STREET IN DIVISION-14, UNIT-3, ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10887,Roads,Completed,NA-THIRUVOTTIYUR,14,729000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ONDIKUPPAM 4TH STREET IN DIVISION-14, UNIT-3, ZONE-1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/10888,Roads,Completed,NA-THIRUVOTTIYUR,14,1809000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PPD MAIN ROAD IN DIVISION-14, UNIT-3, ZONE?1 (TURIF PHASE 2)",Own Sources,1,2017-18,2018-19 NA/2017-18/15763,Buildings,Completed,NA-THIRUVOTTIYUR,14,95000,"Demolition of existing U.P.H.C Building at Malligapuram Main Road Thangal in Dn-14, Unit-3, Zone-1",Own Sources,1,2017-18,2018-19 BR/2017-18/11728,Roads,Completed,BR-Bus Route Roads,15,5998000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Manali New Town Road in Dn-15, Zone-II",Grants,2,2017-18,2018-19 BR/2017-18/4133,Roads,Completed,BR-Bus Route Roads,15,25900,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -2 For the challan no-B.R.R.C.NO.B4/4914/2016,Deposit Works,2,2017-18,2018-19 BR/2017-18/4134,Roads,Completed,BR-Bus Route Roads,15,51800,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -3 For the challan no-B.R.R.C.NO.B4/0422/2016,Deposit Works,2,2017-18,2018-19 BR/2017-18/4135,Roads,Completed,BR-Bus Route Roads,15,243000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -3 For the challan no-B.R.R.C.NO.B4/4618/2016,Deposit Works,2,2017-18,2018-19 BR/2017-18/4136,Roads,Completed,BR-Bus Route Roads,15,630000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -3 For the challan no-B.R.R.C.NO.B4/4914/2016,Deposit Works,2,2017-18,2018-19 BR/2017-18/4174,Roads,Completed,BR-Bus Route Roads,15,12900,Restoration of OFC road cut made by Idea Communication Ltd in Zone -2 For the challan no-B.R.R.C.NO.B4/0413/2016,Deposit Works,2,2017-18,2019-20 L/2017-18/12821,Electrical,Completed,L-Electrical,15,965000,Replacement of Damaged & Burnt out Cables,Own Sources,2,2017-18,2018-19 NB/2017-18/0405,Buildings,Completed,NB-MANALI,15,970000,"PROPOSED CONSTRUCTION OF COMPOSTING SHED AT MANALI NEW TOWN 150 FEET ROAD (HINDU BURIAL GROUND) IN DN- 15,U- 4,ZN-2",Own Sources,2,2017-18,2018-19 NB/2017-18/10038,Parks,Completed,NB-MANALI,15,178000,"MAINTENANCE OF PARK AT BLOCK NO 29 CPS - 9 IN DN-15, U-4, Z-2",Own Sources,2,2017-18,2018-19 NB/2017-18/10039,Parks,Completed,NB-MANALI,15,800000,"MAINTENANCE OF PARK AT BLOCK NO 26 CPS - 10 IN DN-15, U-4, Z-2",Own Sources,2,2017-18,2018-19 NB/2017-18/10040,Parks,Completed,NB-MANALI,15,177000,"MAINTENANCE OF PARK AT BLOCK NO 65 CPS - 8 IN DN-15, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/10056,Parks,Completed,NB-MANALI,15,201000,"Maintenance of Park at Block no 63 CPS- 7 in Dn - 15, U-4 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/14412,Road Cut,Completed,NB-MANALI,15,690000,"Improvements to the Interior BT Road At Thulasi Nagar Salai (TH road to End ) In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14425,Road Cut,Completed,NB-MANALI,15,138000,"Improvements to the Interior BT Road At Old Napalayam New colony Gangaiamman koil st In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14427,Road Cut,Completed,NB-MANALI,15,1597000,"Improvements to the Interior BT Road At Manali New Town 4th block 40feet road 6th Main road In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14428,Road Cut,Completed,NB-MANALI,15,897000,"Improvements to the Interior BT Road At Manali New Town 7th block 30feet road 9th Main road In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14429,Road Cut,Completed,NB-MANALI,15,1597000,"Improvements to the Interior BT Road At Manali New Town 16th block 30feet road 7th Main road In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14430,Road Cut,Completed,NB-MANALI,15,1335000,"Improvements to the Interior BT Road At Manali New Town 8th block 30feet road 8th Main road In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14431,Road Cut,Completed,NB-MANALI,15,1587000,"Improvements to the Interior BT Road At Manali New Town 5th block 40feet road 10th Main road In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14432,Road Cut,Completed,NB-MANALI,15,890000,"Improvements to the Interior BT Road At Manali New Town 23th block 40feet road 11th Main road In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14434,Road Cut,Completed,NB-MANALI,15,431000,"Improvements to the Interior BT Road At Manali New Town 10th block 30feet road 8th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14435,Road Cut,Completed,NB-MANALI,15,1415000,"Improvements to the Interior BT Road At Manali New Town 24th block 30feet road 12th Main road In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14436,Road Cut,Completed,NB-MANALI,15,876000,"Improvements to the Interior BT Road At Manali New Town 18th block 30feet road 11th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14438,Road Cut,Completed,NB-MANALI,15,438000,"Improvements to the Interior BT Road At Manali New Town 7th block 30feet road 14th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14440,Road Cut,Completed,NB-MANALI,15,545000,"Improvements to the Interior BT Road At Manali New Town 60th block 20feet road 38th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14441,Road Cut,Completed,NB-MANALI,15,545000,"Improvements to the Interior BT Road At Manali New Town 60th block 30feet road 39th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14442,Road Cut,Completed,NB-MANALI,15,590000,"Improvements to the Interior BT Road At Manali New Town 54th block 16feet road 43th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14443,Road Cut,Completed,NB-MANALI,15,345000,"Improvements to the Interior BT Road At Manali New Town 54th block 24feet road 44th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14482,Roads,Completed,NB-MANALI,15,374000,"Improvements to the of interior Cement Concrete road At Edayanchavadi 2nd street(Gangai amman koil street In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14483,Roads,Completed,NB-MANALI,15,287000,"Improvements to the of interior Cement Concrete road At Edayanchavadi 3rd street(Vinayakar koil street ) In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14484,Roads,Completed,NB-MANALI,15,202000,"Improvements to the Interior Cement Concrete Road At Edayanchavadi 1st street(sakthi amman koil street) In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14485,Roads,Completed,NB-MANALI,15,113000,"Improvements to the Interior Cement Concrete Road At New nappalayam 1st and 2nd street In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14486,Roads,Completed,NB-MANALI,15,1217000,"Improvements to the Interior BT Road At Edayanchavadi Main Road Part In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14488,Roads,Completed,NB-MANALI,15,927000,"Improvements to the Interior BT Road At Thulasi Nagar 2Nd Street In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14489,Roads,Completed,NB-MANALI,15,1500000,"Improvements to the Interior BT Road At Thulasi Nagar 3rd Street In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14526,Road Cut,Completed,NB-MANALI,15,458000,"Improvements to the Interior CC Road At Chinna eachanguzhi salai (TH road to End) IN DN-15, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14546,Buildings,Completed,NB-MANALI,15,1424000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR HINDU B.G (SOUTH SIDE) AT MANALI NEW TOWN 150FEET ROAD IN DN-15 U-4, ZONE-02",Own Sources,2,2017-18,2019-20 NB/2017-18/14626,Road Cut,Completed,NB-MANALI,15,987000,"Improvements to the Interior BT Road at Manali New Town 47th block 24feet road 33th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14627,Road Cut,Completed,NB-MANALI,15,545000,"Improvements to the Interior BT Road At Manali New Town 29th block 20feet road 29th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/14629,Road Cut,Completed,NB-MANALI,15,379000,"Improvements to the Interior BT Road At Manali New Town 54th block 24feet road 45th street In Dn-15, U-4, Zone-02.",Own Sources,2,2017-18,2018-19 NB/2017-18/8165,Buildings,Completed,NB-MANALI,15,494000,"DUE TO MONSOON FOR ATTENDING EMERGENCY WORKS AND PATCH WORKS (MAINTENANCE) DN-15,16&17, UNIT-4, ZONE-02.",Own Sources,2,2017-18,2018-19 D/2017-18/14691,Storm Water Drain,Completed,D-Storm Water Drains,16,11625000,"Restoration and other improvements to Kanniamman koil street pond,Kamarajapuram pond, Kosapur pond, Andarkuppam burial ground pond, Kulakkarai pond, Elanthanur pond, Burma nagar pond, vanian kulam (Sannathi street) pond and Thamarai kulam ponds for augmentation of water supply in Division -16,17,19,20 and 21, Zone - 2 (Package - II)",SMART CITY - SWD,2,2017-18,2020-21 L/2017-18/12820,Electrical,Completed,L-Electrical,16,991000,Replacement of Damaged & Burnt out Cables,Own Sources,2,2017-18,2018-19 NB/2017-18/0408,Buildings,Completed,NB-MANALI,16,970000,"PROPOSED CONSTRUCTION OF COMPOSTING SHED AT ANDARKUPPAM BURIAL GROUND IN DN- 16,U-4,ZN-2",Own Sources,2,2017-18,2018-19 NB/2017-18/10044,Parks,Completed,NB-MANALI,16,161000,"Maintenance of Park at Block no 52 CPS- 4������������������in Dn - 16, Unit-4������������������, Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10143,Parks,Completed,NB-MANALI,16,227000,"Maintenance of Park at Block no 134&135 CPS - 1 in Dn - 16, U-4 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10144,Parks,Completed,NB-MANALI,16,191000,"Maintenance of Park at Block no 90 CPS - 3 in Dn - 16, U-4 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10145,Parks,Completed,NB-MANALI,16,138000,"Maintenance of Park at Block no 78 CPS - 5 in Dn - 16, U-4 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10228,Buildings,Completed,NB-MANALI,16,383000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BURMA NAGAR 12TH STREET IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14400,Road Cut,Completed,NB-MANALI,16,448000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MRB NAGAR MAIN STREET IN DN-16, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14401,Road Cut,Completed,NB-MANALI,16,914000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MANALI NEW TOWN 78TH BLOCK 24FEET ROAD 77TH STREET IN DN-16, U-4,Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14402,Road Cut,Completed,NB-MANALI,16,1197000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MANALI NEW TOWN 99TH BLOCK 24FEET ROAD 79TH STREET IN DN-16, U-4,Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14404,Road Cut,Completed,NB-MANALI,16,1007000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MANALI NEW TOWN 102TH BLOCK 24FEET ROAD 81ST STREET IN DN-16, U-4,Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14405,Road Cut,Completed,NB-MANALI,16,1028000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MANALI NEW TOWN 100TH BLOCK 24FEET ROAD 80ST STREET IN DN-16, U-4,Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14407,Road Cut,Completed,NB-MANALI,16,155000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MANALI NEW TOWN 127TH BLOCK 24FEET ROAD 83RD STREET IN DN-16, U-4,Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14409,Road Cut,Completed,NB-MANALI,16,320000,"IMPROVEMENTS TO INTERIOR BT ROAD AT MANALI NEW TOWN 128TH BLOCK 24FEET ROAD 84TH STREET IN DN-16, U-4,Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14487,Roads,Completed,NB-MANALI,16,315000,"Improvements to the Interior BT Road At New Nappalayam Perumal Koil Street In Dn-15, U-4, Zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/14490,Buildings,Completed,NB-MANALI,16,348000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BURMA NAGAR 13TH STREET IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14491,Buildings,Completed,NB-MANALI,16,279000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BURMA NAGAR 15TH STREET IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14492,Buildings,Completed,NB-MANALI,16,279000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BURMA NAGAR 16TH STREET IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14493,Buildings,Completed,NB-MANALI,16,97000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT GANDHI NAGAR 1ST STREET IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14494,Buildings,Completed,NB-MANALI,16,150000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT GANDHI NAGAR 2ND STREET IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14495,Buildings,Completed,NB-MANALI,16,150000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT GANDHI NAGAR 3RD STREET IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14496,Buildings,Completed,NB-MANALI,16,97000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT GANDHI NAGAR 4TH STREET IN DIVISION-16, UNIT-4, ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14631,Road Cut,Completed,NB-MANALI,16,224000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MANALI NEW TOWN 129TH BLOCK 20FEET ROAD 85TH STREET IN DN-16, U-4,Z-2.",Own Sources,2,2017-18,2018-19 P/2017-18/13011,Parks,Completed,P-Parks and Playfields,16,7151100,"FORMATION OF NEW PARK AT MANALI NEW TOWN C.P.S.-6, BLOCK NO 54 IN DN - 15, ZONE - II",Grants,2,2017-18,2018-19 P/2017-18/13012,Parks,Completed,P-Parks and Playfields,16,5358100,"FORMATION OF NEW PARK AT CMDA, CPS-2, MANALI NEWTON IN DN-16, ZONE - II",Grants,2,2017-18,2018-19 P/2017-18/13014,Parks,Completed,P-Parks and Playfields,16,11148100,"FORMATION OF NEW PARK AT TNHB-MANALI PHASE-II, SADAYANKUPPAM IN DN -16, ZONE - II",Grants,2,2017-18,2019-20 L/2017-18/12818,Electrical,Completed,L-Electrical,17,573000,Replacement of Burnt out Cables,Own Sources,2,2017-18,2018-19 L/2017-18/12819,Electrical,Completed,L-Electrical,17,914000,Replacement of Damaged & Burnt out Cables,Own Sources,2,2017-18,2018-19 NB/2017-18/0409,Buildings,Completed,NB-MANALI,17,970000,"PROPOSED CONSTRUCTION OF COMPOSTING SHED AT SOWBHAKKIA NAGAR IN DN-17, U- 4, ZN-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/10049,Parks,Completed,NB-MANALI,17,114000,"Maintenance of Vadaperumpakkam park in Dn - 17, U-4 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10050,Parks,Completed,NB-MANALI,17,177000,"Maintenance of Thirupathy Devasthanam nagar park in Dn - 17, U-4 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13873,Road Cut,Completed,NB-MANALI,17,5005000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT GANDHI NAGAR AMBEDKAR NAGAR LINK ROAD IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13965,Roads,Completed,NB-MANALI,17,1163000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT THIYAGI VISWANATHADASS NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14504,Roads,Completed,NB-MANALI,17,473000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT THIYAGI VISWANATHADASS NAGAR PART IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14505,Roads,Completed,NB-MANALI,17,436000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT THANIGACHALAM NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14506,Roads,Completed,NB-MANALI,17,2215000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT VILAKKU V.S MANI NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14507,Roads,Completed,NB-MANALI,17,884000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT V.S MANI NAGAR 1ST CROSS STREET IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14508,Roads,Completed,NB-MANALI,17,1071000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT V.S MANI NAGAR 2ND CROSS IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14509,Roads,Completed,NB-MANALI,17,4434000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT OM KANNIAMMAN NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14511,Roads,Completed,NB-MANALI,17,2519000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT THANALAKSHMI NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14512,Roads,Completed,NB-MANALI,17,214000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT SAMUVEL BURIAL GROUND ROAD IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14513,Roads,Completed,NB-MANALI,17,399000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT YOUSUF COLONY IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/0414,Buildings,Completed,NB-MANALI,18,970000,"PROPOSED CONSTRUCTION OF COMPOSTING SHED AT BHARATHIYAR BURIAL GROUND IN DN-18, U- 5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/10051,Parks,Completed,NB-MANALI,18,122000,"Maintenance of Vimalapuram II street park in Dn - 18, U-5 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10052,Parks,Completed,NB-MANALI,18,118000,"Maintenance of CPCL IV street park in Dn - 18, U-5 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10053,Parks,Completed,NB-MANALI,18,399000,"Maintenance of Nedunchezhiyan street park in Dn - 18, U-5 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/11196,Storm Water Drain,Completed,NB-MANALI,18,2030000,"Improvement to existing Storm Water Drain at Nedunchezhian Street Extension in Dn-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/12395,Storm Water Drain,Completed,NB-MANALI,18,500000,"Repairs to Storm water drain for monsoon at various streets in Dn-18,U-05, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13830,Buildings,Completed,NB-MANALI,18,363000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 4TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13857,Road Cut,Completed,NB-MANALI,18,483000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 6TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13859,Road Cut,Completed,NB-MANALI,18,299000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 4TH CROSS STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13860,Road Cut,Completed,NB-MANALI,18,130000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 2ND CROSS STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13861,Road Cut,Completed,NB-MANALI,18,261000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 5TH CROSS STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13862,Road Cut,Completed,NB-MANALI,18,441000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 7TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13863,Road Cut,Completed,NB-MANALI,18,342000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 9TH CROSS STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13864,Buildings,Completed,NB-MANALI,18,416000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 10TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13865,Road Cut,Completed,NB-MANALI,18,508000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 12TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13866,Road Cut,Completed,NB-MANALI,18,335000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 9TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13867,Road Cut,Completed,NB-MANALI,18,543000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 13TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13868,Road Cut,Completed,NB-MANALI,18,575000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 13TH CROSS STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13869,Road Cut,Completed,NB-MANALI,18,702000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT CPCL LAYOUT 14TH CROSS STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13890,Road Cut,Completed,NB-MANALI,18,762000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT CPCL LAYOUT 8TH CROSS STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13892,Road Cut,Completed,NB-MANALI,18,576000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT CPCL LAYOUT 11TH CROSS STREET IN DN-18, U-5, Z-2",Own Sources,2,2017-18,2018-19 NB/2017-18/13896,Road Cut,Completed,NB-MANALI,18,607000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT CPCL LAYOUT 11TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/13950,Roads,Completed,NB-MANALI,18,78000,"IMPROVEMENTS TO INTERIOR CEMENT CONCRETE ROAD AT KALAINGAR NAGAR 2ND STREET IN DN - 18 , U - 5 , Z - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/14420,Roads,Completed,NB-MANALI,18,42000,"IMPROVEMENTS TO INTERIOR CEMENT CONCRETE ROAD AT KALAINGAR NAGAR 9TH STREET IN DN - 18 , U - 5 , Z - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/14421,Roads,Completed,NB-MANALI,18,84000,"IMPROVEMENTS TO INTERIOR CC ROAD AT KALAINGAR NAGAR 1ST STREET IN DN - 18 , U - 5 , Z - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/14515,Roads,Completed,NB-MANALI,18,242000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KALAINGAR NAGAR 8TH STREET IN DN-17, U-4, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14516,Roads,Completed,NB-MANALI,18,357000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KALAINGAR NAGAR 7TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14517,Roads,Completed,NB-MANALI,18,370000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KALAINGAR NAGAR 6TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14518,Roads,Completed,NB-MANALI,18,607000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KALAINGAR NAGAR 5TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14519,Roads,Completed,NB-MANALI,18,423000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KALAINGAR NAGAR 4TH STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/14520,Roads,Completed,NB-MANALI,18,346000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT KALAINGAR NAGAR 3RD STREET IN DN-18, U-5, Z-2.",Own Sources,2,2017-18,2018-19 L/2017-18/6153,Electrical,Completed,L-Electrical,19,814000,"Replacement of 1298 mtr 4x16 sqmm Alu UG Cable at Mathur MMDA 2nd Main Road in Div-19, Zone-2",Own Sources,2,2017-18,2017-18 L/2017-18/6159,Electrical,Completed,L-Electrical,19,809000,"Replacement of 1278 mtr 4x16 sqmm Alu UG Cable at Mathur MMDA 1st Main Road in Div-19, Zone-2",Own Sources,2,2017-18,2017-18 L/2017-18/6163,Electrical,Completed,L-Electrical,19,804000,"Replacement of 1241 mtr 4x16 sqmm Alu UG Cable at Mathur MMDA 3rd Main Road in Div-19, Zone-2",Own Sources,2,2017-18,2017-18 L/2017-18/6164,Electrical,Completed,L-Electrical,19,669000,"Replacement of 1410 mtr 4x16 sqmm Alu UG Cable at Chinna Mathur Salai Extension Road in Div-19, Zone-2",Own Sources,2,2017-18,2017-18 L/2017-18/9286,Electrical,Completed,L-Electrical,19,408000,"Replacement of 1155 mtr 2x16 sqmm Alu UG Cable at Mathur MMDA various places in Div-19, Zone-2",Own Sources,2,2017-18,2017-18 NB/2017-18/0394,Buildings,Completed,NB-MANALI,19,970000,"PROPOSED CONSTRUCTION OF COMPOSTING SHED AT MANJAMBAKKAM BURIAL GROUND (200FT ROAD) IN DN-19,U-05,ZN-2",Own Sources,2,2017-18,2018-19 NB/2017-18/10186,Parks,Completed,NB-MANALI,19,1152000,"Maintenance of MMDA II Main road park in Dn - 19, U-5 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10187,Parks,Completed,NB-MANALI,19,147000,"Maintenance of MMDA 34th street park in Dn - 19, U-5 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/10188,Parks,Completed,NB-MANALI,19,182000,"Maintenance of Lake view apartment park (Kamarajar Salai) in Dn - 19, U-5 , Zone - 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13409,Buildings,Completed,NB-MANALI,19,2092000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 2ND CROSS STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13410,Roads,Completed,NB-MANALI,19,993000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PONNI AMMAN KOIL STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13411,Roads,Completed,NB-MANALI,19,337000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 1ST STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13413,Roads,Completed,NB-MANALI,19,346000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 16TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13414,Roads,Completed,NB-MANALI,19,47000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 30TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13415,Roads,Completed,NB-MANALI,19,85000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 49TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13416,Roads,Completed,NB-MANALI,19,122000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 61ST STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13417,Roads,Completed,NB-MANALI,19,85000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MMDA 110TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13418,Roads,Completed,NB-MANALI,19,114000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 121ST STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13419,Roads,Completed,NB-MANALI,19,297000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 29TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13420,Roads,Completed,NB-MANALI,19,199000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 37TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13421,Roads,Completed,NB-MANALI,19,199000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 45TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13422,Roads,Completed,NB-MANALI,19,198000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PERUMAL KOIL STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13423,Roads,Completed,NB-MANALI,19,118000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TEACHERS COLONY 1ST CROSS STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13424,Roads,Completed,NB-MANALI,19,99000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TEACHERS COLONY 2ND CROSS STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13425,Roads,Completed,NB-MANALI,19,142000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT (MMDA 89TH STREET FROM MMDA 97TH STREET) IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13426,Roads,Completed,NB-MANALI,19,100000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ( MMDA 91ST STREET FROM MMDA 97TH STREET) IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13427,Roads,Completed,NB-MANALI,19,85000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT (MMDA 87TH STREET FROM MMDA 3RD MAIN ROAD) IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13428,Roads,Completed,NB-MANALI,19,478000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 69TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13429,Roads,Completed,NB-MANALI,19,182000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT( MMDA 47TH STREET FROM MMDA 56TH STREET) IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13430,Roads,Completed,NB-MANALI,19,174000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 56TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13431,Roads,Completed,NB-MANALI,19,199000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 48TH STREET FROM MMDA 1ST MAIN ROAD IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13432,Roads,Completed,NB-MANALI,19,375000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MMDA 23RD STREET FROM MMDA 15TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13433,Roads,Completed,NB-MANALI,19,81000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MMDA 9TH STREET FROM MMDA 1ST MAIN ROAD IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13434,Roads,Completed,NB-MANALI,19,121000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MMDA 104TH STREET FROM MMDA 97TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13435,Roads,Completed,NB-MANALI,19,489000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT BHARATHI NAGAR 1ST STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13436,Roads,Completed,NB-MANALI,19,502000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT BHARATHI NAGAR 2ND STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13437,Roads,Completed,NB-MANALI,19,491000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT BHARATHI NAGAR 3RD STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13440,Roads,Completed,NB-MANALI,19,1674000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT PONNIAMMAN KOIL STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13441,Roads,Completed,NB-MANALI,19,129000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT AMMAN NAGAR IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13442,Roads,Completed,NB-MANALI,19,195000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT TEACHERS COLONY 1ST STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13443,Roads,Completed,NB-MANALI,19,169000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT TEACHERS COLONY 2ND STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13445,Roads,Completed,NB-MANALI,19,115000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT TEACHERS COLONY CROSS STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13446,Roads,Completed,NB-MANALI,19,252000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT ELLAIYAMMAN KOIL STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13447,Roads,Completed,NB-MANALI,19,494000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MGR SALAI 1ST STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13448,Roads,Completed,NB-MANALI,19,266000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MMDA 119TH STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13452,Roads,Completed,NB-MANALI,19,795000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT KULAKARAI STREET 1ST CROSS STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13453,Roads,Completed,NB-MANALI,19,1824000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MMDA 1ST CROSS STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13465,Roads,Completed,NB-MANALI,19,447000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT BHARATHI NAGAR 4TH STREET 1ST CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13466,Roads,Completed,NB-MANALI,19,300000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT BHARATHI NAGAR 4TH STREET 2ND CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13467,Roads,Completed,NB-MANALI,19,563000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT BHARATHI NAGAR 4TH STREET 3RD CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13468,Roads,Completed,NB-MANALI,19,145000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT KARUMARAI AMMAN KOIL 3RD STREET 2ND CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13469,Roads,Completed,NB-MANALI,19,145000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT PERUMAL KOIL STREET 2ND CROSS T IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13470,Roads,Completed,NB-MANALI,19,426000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT NADIYA NAGAR IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13471,Roads,Completed,NB-MANALI,19,257000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT PONIAMMAN KOIL LANE IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13472,Roads,Completed,NB-MANALI,19,421000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT PADASALAI STREET IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13473,Roads,Completed,NB-MANALI,19,430000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT PERUMAL KOIL KIZANDA MADAVITHI CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13475,Roads,Completed,NB-MANALI,19,108000,"IMPROVEMENTS TO THE INTERIOR C.C. ROAD AT KAMARAJAR SALAI CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13476,Roads,Completed,NB-MANALI,19,255000,"IMPROVEMENT TO THE INTERIOR C.C. ROAD AT KAMARAJAR SALAI 2ND CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13478,Roads,Completed,NB-MANALI,19,406000,"IMPROVEMENT TO THE INTERIOR C.C. ROAD AT KAMARAJAR SALAI 3RD CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13479,Roads,Completed,NB-MANALI,19,300000,"IMPROVEMENT TO THE INTERIOR C.C. ROAD AT KAMARAJAR SALAI 4TH CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 NB/2017-18/13480,Roads,Completed,NB-MANALI,19,368000,"IMPROVEMENT TO THE INTERIOR C.C. ROAD AT KAMARAJAR SALAI 5TH CROSS IN DN-19,U-05,ZONE ? 2",Own Sources,2,2017-18,2018-19 BR/2017-18/4137,Roads,Completed,BR-Bus Route Roads,20,695000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/4914/2016,Deposit Works,2,2017-18,2018-19 NB/2017-18/0415,Buildings,Completed,NB-MANALI,20,970000,"PROPOSED CONSTRUCTION OF COMPOSTING SHED INSIDE BURIAL GROUND IN SRINIVASA PERUMAL KOIL STREET IN DN-20, U- 5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/0444,Buildings,Completed,NB-MANALI,20,985000,"PROVIDING AND LAYING INTERLOCKING PLATFORM FOR PETROL BUNK INSIDE LORRY DEPOT AT KAMARAJAR SALAI, IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2017-18 NB/2017-18/0622,Buildings,Completed,NB-MANALI,20,425000,"PROVIDING G.I SHEET ROOF AT PETROL BUNK INSIDE OF LORRY DEPOT AT KAMARAJAR SALAI,DN;20,UNIT;5,ZONE;2.",Own Sources,2,2017-18,2017-18 NB/2017-18/10190,Parks,Completed,NB-MANALI,20,145000,"MAINTENANCE OF JALAGANDAMARIAMMAN KOIL STREET PARK IN DN-21, U-05, ZONE-02",Own Sources,2,2017-18,2018-19 NB/2017-18/10191,Parks,Completed,NB-MANALI,20,175000,"MAINTENANCE OF LAKE VIEW PARK (CHINNA MATHUR SALAI) IN DN-20, U-05, ZONE-02",Own Sources,2,2017-18,2018-19 NB/2017-18/2584,Roads,Completed,NB-MANALI,20,458000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT SRINIVASA PERUMAL KOIL CROSS STREET IN DN20, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2018-19 NB/2017-18/2585,Roads,Completed,NB-MANALI,20,330000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT SRINIVASA PERUMAL KOIL MELANDAI CROSS LANE IN DN20, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2018-19 NB/2017-18/2586,Roads,Completed,NB-MANALI,20,336000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT SRINIVASA PERUMAL KOIL MELANDAI 4TH LANE IN DN20, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2018-19 NB/2017-18/2587,Roads,Completed,NB-MANALI,20,321000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT KALTHOTTAM MGR CROSS STREET IN DN20, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2018-19 NB/2017-18/2588,Roads,Completed,NB-MANALI,20,190000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT NEW MGR NAGAR IST STREET EXTN. 1ST LANE IN DN20, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2018-19 NB/2017-18/6674,Roads,Completed,NB-MANALI,20,490000,"Due to monsoon for attending emergency works and patch works in (Division-18 to 21 ) at unit -05,zone-02",Own Sources,2,2017-18,2018-19 NB/2017-18/6676,Storm Water Drain,Completed,NB-MANALI,20,609000,"DESILTING WORKS OF SWD AT VARIOUS STREETS IN DN18, 20 & 21, U-05, Z-02",Own Sources,2,2017-18,2018-19 NB/2017-18/6677,Storm Water Drain,Completed,NB-MANALI,20,580000,"REPAIR AND MAINTANENANCE WORKS OF SWD AT VARIOUS STREETS IN DN- 19 & 20, UNIT-5, ZONE-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/7267,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF LAKE BOUNDARY FLOOD RETAINING WALL AT NEW MGR NAGAR 1ST. STREET EXTENSION ( REACH; 5), IN DN;20, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2017-18 NB/2017-18/7729,Buildings,Completed,NB-MANALI,20,998000,"CONSTRUCTION OF LAKE BOUNDARY FLOOD RETAINING WALL AT NEW MGR 1st STREET EXTENSION (REACH;6) IN DN;20, UNIT;5, ZONE;2",Own Sources,2,2017-18,2017-18 NB/2017-18/0413,Buildings,Completed,NB-MANALI,21,970000,"PROPOSED CONSTRUCTION OF COMPOSTING SHED AT SABABATHY STREET IN DN-21, U- 5, Z-2.",Own Sources,2,2017-18,2018-19 NB/2017-18/6691,Road Cut,Completed,NB-MANALI,21,282000,"IMPROVEMENTS TO THE INTERIOR CC ROAD AT THAMARAIKULAM 3RD STREET IN DN;21, UNIT;5, ZONE;2.",Own Sources,2,2017-18,2019-20 NB/2017-18/6692,Storm Water Drain,Completed,NB-MANALI,21,447000,"REPAIR AND MAINTANENANCE WORKS OF SWD AT VARIOUS STREETS IN DN-21, UNIT-5, ZONE-2.",Own Sources,2,2017-18,2018-19 L/2017-18/10254,Electrical,Completed,L-Electrical,22,35970700,"Provision of 681 Nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 40 W to 50W LED fitting, 31 Nos of 8 Mtr Hot Dipped Zinc Galvanising Lamp post with Double Straight Brackets & 35 Nos of 8 Mtr Hot Dipped Zinc Galvanising Lamp post with Single Straight Brackets with 150 W to 165 W LED fitting at Siva Vishnu Nagar, Adhinath bhagavan Garden and Various Locations in Ward 22 to 25 in Zone III, Madhavaram.","Loans, Grants And Own Sources",3,2017-18,2018-19 NC/2017-18/0432,Buildings,Completed,NC-MADHAVARAM,22,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Kannadapalayam Burial Ground in div-22, Unit-6, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/0435,Buildings,Completed,NC-MADHAVARAM,22,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Kannappasamy Nagar Burial Ground in div-22, Unit-6, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/10281,Storm Water Drain,Completed,NC-MADHAVARAM,22,55000,"REPAIRS AND IMPROVEMENTS TO SWD AND SIDE AT VARIOUS STREET IN DN-22,U-6,Z-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/15280,Roads,Completed,NC-MADHAVARAM,22,421000,"PROVIDING SPEED BREAKER IN VARIOUS LOCATION AT GANDHI MAIN ROAD IN DN-22,U-6,Z-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/7798,Buildings,Completed,NC-MADHAVARAM,22,497000,"WATER AND ELECTRICIAL ARRANGEMENTS FOR AMMAKUDENEER(GANDHI MAIN STREET),,KANNAPASWAMY NAGAR AMMAUNAVAGAM AND KANNAPASAMY NAGAR BURIAL GROUND IN DN 22,U-6,Z-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/8101,Storm Water Drain,Completed,NC-MADHAVARAM,22,60000,"DE-SILTING OF SIDE DRAIN AND STORM WATER DRAIN AT GURUSHANTHI NAGAR MAIN ROAD,THIRU NEELA GANDAR NAGAR MAIN ROAD AND MAREAMMAL NAGAR MAIN ROAD IN DIVISION-22,UNIT-6,ZONE-3",Own Sources,3,2017-18,2017-18 L/2017-18/4095,Electrical,Completed,L-Electrical,23,198700,"Removing, Refixing and replacement of accessories of 20mtr High Mast Light at GNT Road (Puzhal camp signal rountana) Division-23 of zone-III (Madhavaram)(Sch of rate 2015-16)",Own Sources,3,2017-18,2018-19 NC/2017-18/10282,Storm Water Drain,Completed,NC-MADHAVARAM,23,23000,"REPAIRS AND IMPROVEMENTS TO SWD AND SIDE AT VARIOUS STREET IN DN-23,U-6,Z-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/15921,Buildings,Completed,NC-MADHAVARAM,23,1465000,"Proposed Construction of Resource recovery Centre Near Composed Yard at GNT service Road in Dn-23, Unit-6, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/15958,Buildings,Completed,NC-MADHAVARAM,23,1465000,"Proposed Construction of Resource recovery Centre Near Composed Yard at Lakshmi Amman Koil Street in Dn-23, Unit-6, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/8102,Storm Water Drain,Completed,NC-MADHAVARAM,23,7000,"DE-SILTING OF SIDE DRAIN AND STORM WATER DRAIN AT OTTAVADAI STREET IN DIVISION-23,UNIT-6,ZONE-3",Own Sources,3,2017-18,2017-18 BR/2017-18/11548,Roads,Completed,BR-Bus Route Roads,24,32400000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Surapet Main Road Road in Dn-24, Zone-III",Grants,3,2017-18,2018-19 BR/2017-18/11760,Roads,Completed,BR-Bus Route Roads,24,2400000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Senthil Nagar Main Road in Dn-24, Zone-III",Grants,3,2017-18,2018-19 D/2017-18/14711,Storm Water Drain,Completed,D-Storm Water Drains,24,16419000,"Restoration and other improvements to Chavadi Kulam pond, Teachers colony pond, Saamiyar kulam pond, Uthu kulam pond, Chella kulam pond, Mula kulam pond, Patcha kulam pond, Thamarai kulam pond, Idayan kulam pond and Basin Lake pond for augmentation of water supply in Division -24,25,26 and 32, Zone - 3 (Package - III)",SMART CITY - SWD,3,2017-18,2019-20 NC/2017-18/0431,Buildings,Completed,NC-MADHAVARAM,24,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Bharathidasan Nagar Burial Ground in div-24, Unit-6, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/10283,Storm Water Drain,Completed,NC-MADHAVARAM,24,55000,"REPAIRS AND IMPROVEMENTS TO SWD AND SIDE AT VARIOUS STREET IN DN-24,U-6,Z-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/15939,Buildings,Completed,NC-MADHAVARAM,24,1465000,"Proposed Construction of Resource recovery Centre at Cadapa Road Near Ammaunavagam in Dn-24, Unit-6, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4354,Road Cut,Completed,NC-MADHAVARAM,24,4012500,"IMPROVEMENTS TO INTERIOR BT ROAD AT SENTHI NAGAR MAIN ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4375,Road Cut,Completed,NC-MADHAVARAM,24,923800,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4376,Road Cut,Completed,NC-MADHAVARAM,24,728100,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4378,Road Cut,Completed,NC-MADHAVARAM,24,961000,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4384,Road Cut,Completed,NC-MADHAVARAM,24,777000,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR EXTN 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4385,Road Cut,Completed,NC-MADHAVARAM,24,841600,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR EXTN 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4386,Road Cut,Completed,NC-MADHAVARAM,24,1035900,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR EXTN 1ST CROSS STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4387,Road Cut,Completed,NC-MADHAVARAM,24,841600,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR EXTN 2ND CROSS STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4391,Road Cut,Completed,NC-MADHAVARAM,24,1424300,"IMPROVEMENTS TO INTERIOR BT ROAD AT JP NAGAR ANNEX IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4394,Road Cut,Completed,NC-MADHAVARAM,24,1729500,"IMPROVEMENTS TO INTERIOR BT ROAD AT SCHOOL STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4398,Road Cut,Completed,NC-MADHAVARAM,24,330300,"IMPROVEMENTS TO INTERIOR BT ROAD AT LAKSHMI AMMAN KOIL 1ST STREET STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4399,Road Cut,Completed,NC-MADHAVARAM,24,299800,"IMPROVEMENTS TO INTERIOR BT ROAD AT LAKSHMI AMMAN KOIL 2ND STREET STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4401,Road Cut,Completed,NC-MADHAVARAM,24,1977100,"IMPROVEMENTS TO INTERIOR BT ROAD AT PILLAYAR KOIL STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4404,Road Cut,Completed,NC-MADHAVARAM,24,388600,"IMPROVEMENTS TO INTERIOR BT ROAD AT PILLAYAR KOIL 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4407,Road Cut,Completed,NC-MADHAVARAM,24,294100,"IMPROVEMENTS TO INTERIOR BT ROAD AT PILLAYAR KOIL 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4411,Road Cut,Completed,NC-MADHAVARAM,24,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT THULUKANATHAMMAN KOIL 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4414,Road Cut,Completed,NC-MADHAVARAM,24,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT THULUKANATHAMMAN KOIL 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4416,Road Cut,Completed,NC-MADHAVARAM,24,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT THULUKANATHAMMAN KOIL 4TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4418,Road Cut,Completed,NC-MADHAVARAM,24,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT THULUKANATHAMMAN KOIL 5TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4422,Road Cut,Completed,NC-MADHAVARAM,24,2421300,"IMPROVEMENTS TO INTERIOR BT ROAD AT THULUKANATHAMMAN KOIL 6TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4429,Road Cut,Completed,NC-MADHAVARAM,24,3320700,"IMPROVEMENTS TO INTERIOR BT ROAD AT EZHIL NAGAR MAIN ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4431,Road Cut,Completed,NC-MADHAVARAM,24,1245300,"IMPROVEMENTS TO INTERIOR BT ROAD AT EZHIL NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4432,Road Cut,Completed,NC-MADHAVARAM,24,323700,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRI LAKSHMI NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4433,Road Cut,Completed,NC-MADHAVARAM,24,1937100,"IMPROVEMENTS TO INTERIOR BT ROAD AT EZHIL NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4435,Road Cut,Completed,NC-MADHAVARAM,24,180600,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRI LAKSHMI NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4436,Road Cut,Completed,NC-MADHAVARAM,24,2421300,"IMPROVEMENTS TO INTERIOR BT ROAD AT EZHIL NAGAR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4438,Road Cut,Completed,NC-MADHAVARAM,24,2490500,"IMPROVEMENTS TO INTERIOR BT ROAD AT EZHIL NAGAR 4TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4439,Road Cut,Completed,NC-MADHAVARAM,24,2905600,"IMPROVEMENTS TO INTERIOR BT ROAD AT EZHIL NAGAR 5TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4440,Road Cut,Completed,NC-MADHAVARAM,24,884000,"IMPROVEMENTS TO INTERIOR BT ROAD AT INDIRA NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4442,Road Cut,Completed,NC-MADHAVARAM,24,294100,"IMPROVEMENTS TO INTERIOR BT ROAD AT INDIRA NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4443,Road Cut,Completed,NC-MADHAVARAM,24,1798700,"IMPROVEMENTS TO INTERIOR BT ROAD AT EZHIL NAGAR 6TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4446,Road Cut,Completed,NC-MADHAVARAM,24,426900,"IMPROVEMENTS TO INTERIOR BT ROAD AT DG NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4448,Road Cut,Completed,NC-MADHAVARAM,24,378000,"IMPROVEMENTS TO INTERIOR BT ROAD AT DG NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4450,Road Cut,Completed,NC-MADHAVARAM,24,647400,"IMPROVEMENTS TO INTERIOR BT ROAD AT INDIRA NAGAR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4452,Road Cut,Completed,NC-MADHAVARAM,24,457000,"IMPROVEMENTS TO INTERIOR BT ROAD AT DG NAGAR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4456,Road Cut,Completed,NC-MADHAVARAM,24,633700,"IMPROVEMENTS TO INTERIOR BT ROAD AT INDIRA NAGAR 4TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4457,Road Cut,Completed,NC-MADHAVARAM,24,504900,"IMPROVEMENTS TO INTERIOR BT ROAD AT DG NAGAR 4TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4460,Road Cut,Completed,NC-MADHAVARAM,24,391900,"IMPROVEMENTS TO INTERIOR BT ROAD AT DG NAGAR 5TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4462,Road Cut,Completed,NC-MADHAVARAM,24,391900,"IMPROVEMENTS TO INTERIOR BT ROAD AT DG NAGAR 1ST CROSS STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4463,Road Cut,Completed,NC-MADHAVARAM,24,753500,"IMPROVEMENTS TO INTERIOR BT ROAD AT INDIRA NAGAR 5TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4505,Road Cut,Completed,NC-MADHAVARAM,24,784000,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4506,Road Cut,Completed,NC-MADHAVARAM,24,1799900,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4508,Road Cut,Completed,NC-MADHAVARAM,24,1698900,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4510,Road Cut,Completed,NC-MADHAVARAM,24,2941000,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 4TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4511,Road Cut,Completed,NC-MADHAVARAM,24,2286900,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 5TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4513,Road Cut,Completed,NC-MADHAVARAM,24,2353000,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 6TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4514,Road Cut,Completed,NC-MADHAVARAM,24,783900,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 6TH 1ST CROSS STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4515,Road Cut,Completed,NC-MADHAVARAM,24,1175900,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 2ND CROSS STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4516,Road Cut,Completed,NC-MADHAVARAM,24,1175900,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 6TH 2ND CROSS STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4517,Road Cut,Completed,NC-MADHAVARAM,24,914900,"IMPROVEMENTS TO INTERIOR BT ROAD AT METTUR 6TH 3RD CROSS STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4627,Road Cut,Completed,NC-MADHAVARAM,24,488200,"IMPROVEMENTS TO INTERIOR BT ROAD AT SUDHA NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4631,Road Cut,Completed,NC-MADHAVARAM,24,534000,"IMPROVEMENTS TO INTERIOR BT ROAD AT SUDHA NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4637,Road Cut,Completed,NC-MADHAVARAM,24,1177900,"IMPROVEMENTS TO INTERIOR BT ROAD AT REVATHI NAGAR MAIN ROAD IN DN-24,UNIT-6,ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4645,Road Cut,Completed,NC-MADHAVARAM,24,1798700,"IMPROVEMENTS TO INTERIOR BT ROAD AT SHANMUGAPURAM NETHAJI STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4648,Road Cut,Completed,NC-MADHAVARAM,24,4118900,"IMPROVEMENTS TO INTERIOR BT ROAD AT SHANMUGAPURAM MADHANAKUPPAM MAIN ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4691,Road Cut,Completed,NC-MADHAVARAM,24,2698100,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR MAIN ROAD (SOUTH) IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4694,Road Cut,Completed,NC-MADHAVARAM,24,1245300,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4697,Road Cut,Completed,NC-MADHAVARAM,24,1314500,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4700,Road Cut,Completed,NC-MADHAVARAM,24,622700,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4774,Road Cut,Completed,NC-MADHAVARAM,24,1282500,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 4TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4777,Road Cut,Completed,NC-MADHAVARAM,24,830200,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 5TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4780,Road Cut,Completed,NC-MADHAVARAM,24,1314500,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 6TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4784,Road Cut,Completed,NC-MADHAVARAM,24,1106900,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 7TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4785,Road Cut,Completed,NC-MADHAVARAM,24,1245300,"IMPROVEMENTS TO INTERIOR BT ROAD AT SIVAPRAKASAM NAGAR 8TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4815,Road Cut,Completed,NC-MADHAVARAM,24,1683200,"IMPROVEMENTS TO INTERIOR BT ROAD AT VIJAYALAKSHMI NAGAR MAIN ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4816,Road Cut,Completed,NC-MADHAVARAM,24,785500,"IMPROVEMENTS TO INTERIOR BT ROAD AT VIJAYALAKSHMI NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4817,Road Cut,Completed,NC-MADHAVARAM,24,226000,"IMPROVEMENTS TO INTERIOR BT ROAD AT VIJAYALAKSHMI NAGAR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4818,Road Cut,Completed,NC-MADHAVARAM,24,798900,"IMPROVEMENTS TO INTERIOR BT ROAD AT VIJAYALAKSHMI NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4819,Road Cut,Completed,NC-MADHAVARAM,24,1013500,"IMPROVEMENTS TO INTERIOR BT ROAD AT VELMURUGAN NAGAR MAIN ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4826,Road Cut,Completed,NC-MADHAVARAM,24,587900,"IMPROVEMENTS TO INTERIOR BT ROAD AT I N T U C NAGAR 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4828,Road Cut,Completed,NC-MADHAVARAM,24,587900,"IMPROVEMENTS TO INTERIOR BT ROAD AT I N T U C NAGAR 2ND STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4835,Road Cut,Completed,NC-MADHAVARAM,24,876700,"IMPROVEMENTS TO INTERIOR BT ROAD AT VELMURUGAN NAGAR 3RD STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4837,Road Cut,Completed,NC-MADHAVARAM,24,777000,"IMPROVEMENTS TO INTERIOR BT ROAD AT VELMURUGAN NAGAR 4TH AND 5TH STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4847,Road Cut,Completed,NC-MADHAVARAM,24,2019500,"IMPROVEMENTS TO INTERIOR BT ROAD AT PERUMAL KOIL MAIN ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4848,Road Cut,Completed,NC-MADHAVARAM,24,339800,"IMPROVEMENTS TO INTERIOR BT ROAD AT PERUMAL KOIL 1ST STREET IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/7781,Storm Water Drain,Completed,NC-MADHAVARAM,24,67000,"DE- SILTING OF STORM WATER DRAIN AT SANTHOSH NAGAR MAIN ROAD AND IYYAN THIRUVALLUVAR SALAIIN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2017-18,2017-18 BR/2017-18/11729,Roads,Completed,BR-Bus Route Roads,25,4245000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Srinivasa Nagar Main Road in Dn-25, Zone-III",Grants,3,2017-18,2018-19 BR/2017-18/11761,Roads,Completed,BR-Bus Route Roads,25,2066000,"Strengthening and Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement works at INTUC Nagar Main Road in Dn-24 & 25 , Zone-III",Grants,3,2017-18,2018-19 BR/2017-18/4138,Roads,Completed,BR-Bus Route Roads,25,123900,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/4914/2016,Deposit Works,3,2017-18,2018-19 BR/2017-18/4140,Roads,Completed,BR-Bus Route Roads,25,282000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/2464/2016,Deposit Works,3,2017-18,2018-19 BR/2017-18/4141,Roads,Completed,BR-Bus Route Roads,25,432000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/4915/2016,Deposit Works,3,2017-18,2018-19 BR/2017-18/4185,Roads,Completed,BR-Bus Route Roads,25,392000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 3 - For the challan no-B.R.R.C.NO.B4/0551/2017,Deposit Works,3,2017-18,2019-20 L/2017-18/4092,Electrical,Completed,L-Electrical,25,192700,Provision of removal and refixing of 12 nos of 6 mtr Octoganal lamp post collector Nagar in Division-25 of zone-III (Madhavaram)(Sch of rate 2015-16),Own Sources,3,2017-18,2018-19 NC/2017-18/0429,Buildings,Completed,NC-MADHAVARAM,25,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Bharathiyar street Burial Ground in div-25, Unit-6, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/10284,Storm Water Drain,Completed,NC-MADHAVARAM,25,55000,"REPAIRS AND IMPROVEMENTS TO SWD AND SIDE AT VARIOUS STREET IN DN-25,U-6,Z-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/15947,Buildings,Completed,NC-MADHAVARAM,25,650000,"Construction of Source Seggregation Shed at Padmavathy Nagar Burilal Ground in Div-25, Unit-6, Zone-3.",Own Sources,3,2017-18,2019-20 NC/2017-18/4892,Road Cut,Completed,NC-MADHAVARAM,25,980000,"IMPROVEMENTS TO INTERIOR BT ROAD AT AT DAVID JAYAVEL STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4901,Road Cut,Completed,NC-MADHAVARAM,25,1070900,"IMPROVEMENTS TO INTERIOR BT ROAD AT ANNA STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4902,Road Cut,Completed,NC-MADHAVARAM,25,964400,"IMPROVEMENTS TO INTERIOR BT ROAD AT ANNA CROSS STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4904,Road Cut,Completed,NC-MADHAVARAM,25,1111000,"IMPROVEMENTS TO INTERIOR BT ROAD AT INTUC NAGAR 1ST AND 2ND STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4905,Road Cut,Completed,NC-MADHAVARAM,25,1045000,"IMPROVEMENTS TO INTERIOR BT ROAD AT INTUC NAGAR 3RD AND 3RD CROSS STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4906,Road Cut,Completed,NC-MADHAVARAM,25,1372000,"IMPROVEMENTS TO INTERIOR BT ROAD AT INTUC NAGAR 4TH STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4908,Road Cut,Completed,NC-MADHAVARAM,25,980000,"IMPROVEMENTS TO INTERIOR BT ROAD AT INTUC NAGAR 5TH STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4909,Road Cut,Completed,NC-MADHAVARAM,25,980000,"IMPROVEMENTS TO INTERIOR BT ROAD AT INTUC NAGAR 6TH STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4911,Road Cut,Completed,NC-MADHAVARAM,25,1472900,"IMPROVEMENTS TO INTERIOR BT ROAD AT INTUC NAGAR MAIN ROAD IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5002,Road Cut,Completed,NC-MADHAVARAM,25,1135500,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR EXTN 5TH STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5003,Road Cut,Completed,NC-MADHAVARAM,25,777000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR EXTN 7TH STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5005,Road Cut,Completed,NC-MADHAVARAM,25,941500,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR EXTN 8TH AND 12TH STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5007,Road Cut,Completed,NC-MADHAVARAM,25,2848500,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR MAIN STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5008,Road Cut,Completed,NC-MADHAVARAM,25,1294700,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR 3RD AND 4TH STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5009,Road Cut,Completed,NC-MADHAVARAM,25,1294700,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR 1ST AND 2ND STREET IN DN-25,UNTI-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5010,Road Cut,Completed,NC-MADHAVARAM,25,1912500,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERARAGAVELU NAGAR 1ST MAIN ROAD IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5013,Road Cut,Completed,NC-MADHAVARAM,25,1294700,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERARAGAVELU NAGAR 2ND MAIN ROAD IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5014,Road Cut,Completed,NC-MADHAVARAM,25,1294700,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERARAGAVELU NAGAR 1ST AND 2ND STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5018,Road Cut,Completed,NC-MADHAVARAM,25,1135500,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERARAGAVELU NAGAR 3RD,4TH AND 5TH STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5026,Road Cut,Completed,NC-MADHAVARAM,25,876700,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERARAGAVELU NAGAR 6TH AND 7TH STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5027,Road Cut,Completed,NC-MADHAVARAM,25,1307000,"IMPROVEMENTS TO INTERIOR BT ROAD AT V.M.K NAGAR MAIN STREET STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5030,Road Cut,Completed,NC-MADHAVARAM,25,980000,"IMPROVEMENTS TO INTERIOR BT ROAD AT V.M.K NAGAR 3RD STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5031,Road Cut,Completed,NC-MADHAVARAM,25,777000,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERA RAGAVEU NAGAR 1ST EXTN STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5032,Road Cut,Completed,NC-MADHAVARAM,25,777000,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERA RAGAVEU NAGAR 2ND EXTN STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5033,Road Cut,Completed,NC-MADHAVARAM,25,647400,"IMPROVEMENTS TO INTERIOR BT ROAD AT VEERA RAGAVEU NAGAR 3RD EXTN STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5038,Road Cut,Completed,NC-MADHAVARAM,25,1294700,"IMPROVEMENTS TO INTERIOR BT ROAD AT LAKSHMI NAGAR MAIN ROAD IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5040,Road Cut,Completed,NC-MADHAVARAM,25,1035900,"IMPROVEMENTS TO INTERIOR BT ROAD AT LAKSHMI NAGAR 1ST AND 2ND STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5041,Road Cut,Completed,NC-MADHAVARAM,25,1294700,"IMPROVEMENTS TO INTERIOR BT ROAD AT LAKSHMI NAGAR 2ND CROSS STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5044,Road Cut,Completed,NC-MADHAVARAM,25,488200,"IMPROVEMENTS TO INTERIOR BT ROAD AT LAKSHMI NAGAR 3RD CROSS STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5229,Road Cut,Completed,NC-MADHAVARAM,25,1100700,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR 6TH STREET AND 6TH CROSS STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5232,Road Cut,Completed,NC-MADHAVARAM,25,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRINIVASA NAGAR MAIN ROAD IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5235,Road Cut,Completed,NC-MADHAVARAM,25,582800,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRINIVASA NAGAR 1ST STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5237,Road Cut,Completed,NC-MADHAVARAM,25,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRINIVASA NAGAR 2ND STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5239,Road Cut,Completed,NC-MADHAVARAM,25,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRINIVASA NAGAR 3RD STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5242,Road Cut,Completed,NC-MADHAVARAM,25,971100,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRINIVASA NAGAR 4TH STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5244,Road Cut,Completed,NC-MADHAVARAM,25,647400,"IMPROVEMENTS TO INTERIOR BT ROAD AT RANGA AVENQUE 1ST CROSS STREET STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5261,Road Cut,Completed,NC-MADHAVARAM,25,647400,"IMPROVEMENTS TO INTERIOR BT ROAD AT RANGA AVENQUE 2ND CROSS STREET STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5264,Road Cut,Completed,NC-MADHAVARAM,25,582800,"IMPROVEMENTS TO INTERIOR BT ROAD AT RANGA AVENUE 3RD CROSS STREET STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5267,Road Cut,Completed,NC-MADHAVARAM,25,2613900,"IMPROVEMENTS TO INTERIOR BT ROAD AT KVR NAGAR MAIN STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5270,Road Cut,Completed,NC-MADHAVARAM,25,653000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KVR NAGAR 2ND STREET IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5283,Road Cut,Completed,NC-MADHAVARAM,25,259100,"IMPROVEMENTS TO INTERIOR BT ROAD AT AMBAL NAGAR IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/5284,Road Cut,Completed,NC-MADHAVARAM,25,488200,"IMPROVEMENTS TO INTERIOR BT ROAD AT SRINIVASA NAGAR EXTN IN DN-25,UNT-6,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/7703,Roads,Completed,NC-MADHAVARAM,25,4990000,"IMPROVEMENTS TO INTERIOR BT ROAD at Collector Nagar and Birla Avenue joint Road in Dn-25, Unit-06, Zone-03.",Own Sources,3,2017-18,2018-19 NC/2017-18/8096,Storm Water Drain,Completed,NC-MADHAVARAM,25,62000,"DE- SILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-25, UNIT-6,ZONE-3.",Own Sources,3,2017-18,2017-18 BR/2017-18/10793,Roads,Completed,BR-Bus Route Roads,26,2423000,"Restoration of Roadcut made by CMWSSB at Surapet Main Road in Dn-26, Zone-3 (Chellan No.BR / 2015-16 / 011736",Deposit Works,3,2017-18,2018-19 BR/2017-18/10795,Roads,Completed,BR-Bus Route Roads,26,2417000,"Restoration of Roadcut made by CMWSSB at Surapet Main Road in Dn-26, Zone-3 (Chellan No.BR / 2015-16 / 011736)",Deposit Works,3,2017-18,2018-19 D/2017-18/13500,Storm Water Drain,Completed,D-Storm Water Drains,26,1894000,"Construction of storm water drain of size 900 x 900 mm along Siva Ganapathy street from junction of Siva nagar Appar street to junction of upto PWD drain along Retteri lake in Dn- 26,Zone - III.",Own Sources,3,2017-18,2018-19 D/2017-18/14826,Storm Water Drain,Completed,D-Storm Water Drains,26,2095000,"Construction of storm water drain of size 900 x 900 mm along Siva Ganapathy street from junction of Siva ganapathy nagar Main street junction of Siva nagar Appar street in Dn- 26,Zone - III.",Own Sources,3,2017-18,2019-20 D/2017-18/14877,Storm Water Drain,Completed,D-Storm Water Drains,26,2480000,"Construction of storm water drain of size 900 x 900 mm along Siva Ganapathy street from junction of Siva nagar Appar salai to junction of Siva nagar ASK street in Dn- 26,Zone - III.",Own Sources,3,2017-18,2018-19 D/2017-18/14878,Storm Water Drain,Completed,D-Storm Water Drains,26,2480000,"Construction of storm water drain of size 900 x 900 mm from junction of Siva nagar ASK street to junction of Siva nagar Kovalan street in Dn- 26,Zone - III.",Own Sources,3,2017-18,2018-19 L/2017-18/12379,Electrical,Completed,L-Electrical,26,11077400,"Provision of 209 Nos of 6mtr lamp post, single straight bracket with 40w LED Fitting and 21 nos of 8mtr lamp post, single straight bracket with 150w LED Fitting at Ganapathy Siva Nagar, Teachers Colony 7th Street & various streets in Div - 26 & 32 of Zone-III (Madhavaram) (Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2017-18,2019-20 L/2017-18/5230,Electrical,Completed,L-Electrical,26,197200,"Removing, Re-erection and Servicing of 20mtr High Mast Light at Inner Ring Road (MRH Road and Inner Ring Road Junction) Division-26 of zone-III (Madhavaram) (Sch of rate 2015-16)",Own Sources,3,2017-18,2018-19 NC/2017-18/0440,Buildings,Completed,NC-MADHAVARAM,26,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Truck Terminal Burial Ground in div-26, Unit-7, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/0445,Roads,Completed,NC-MADHAVARAM,26,1750100,"IMPROVEMENTS TO INTERIOR BT ROAD AT SEETHAPATHI STREET (TOWARDS TRUCK TERMINAL) IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/0519,Roads,Completed,NC-MADHAVARAM,26,1999000,"IMPROVEMENTS TO INTERIOR BT ROAD AT SEETHAPATHI STREET (FROM THATTANKULAM ROAD TO MRH ROAD) IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/0520,Roads,Completed,NC-MADHAVARAM,26,759000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THANIGACHALAM NAGAR 'F' BLOCK 7TH STREET IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/0525,Roads,Completed,NC-MADHAVARAM,26,380000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THANIGACHALAM NAGAR 'F' BLOCK 6TH STREET IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/10337,Storm Water Drain,Completed,NC-MADHAVARAM,26,121000,"REPAIRS OF DAMAGED SWD SLAB AT VARIOUS STREET IN DN-26, U-7, Z-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/10341,Storm Water Drain,Completed,NC-MADHAVARAM,26,159000,"Desilting of Side Drain at Various Street in Division -26, Unit-7, Zone-3",Own Sources,3,2017-18,2017-18 NC/2017-18/10903,Roads,Completed,NC-MADHAVARAM,26,93000,"Painting of Existing Speed Breakers at Various Street in Div-26, Unit-7, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/14605,Buildings,Completed,NC-MADHAVARAM,26,39900,"REPAIRS OF SWD AT 200 ' FEET ROAD GANAPATHY NAGAR IN DN-26, U-7, Z-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/15040,Parks,Completed,NC-MADHAVARAM,26,310000,"PROVIDING GREENARIES AT OMAKULAM POND IN DIV-26, UNIT-7,ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/15042,Buildings,Completed,NC-MADHAVARAM,26,589000,"CONSTRUCTION OF FLOOD DAMAGED COMPOUND WALL OMAKULAM POND IN DIV-26,UNIT-7,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4744,Road Cut,Completed,NC-MADHAVARAM,26,2081800,"IMPROVEMENTS TO INTERIOR BT ROAD AT Gandhi Street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4745,Road Cut,Completed,NC-MADHAVARAM,26,1478400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Anna Street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4746,Road Cut,Completed,NC-MADHAVARAM,26,1478400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Perumal Koil street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4747,Road Cut,Completed,NC-MADHAVARAM,26,904700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kamarajar street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4748,Road Cut,Completed,NC-MADHAVARAM,26,1507300,"IMPROVEMENTS TO INTERIOR BT ROAD AT Vinayar Koil street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4749,Road Cut,Completed,NC-MADHAVARAM,26,377200,"IMPROVEMENTS TO INTERIOR BT ROAD AT Sri Sai Ram Street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4750,Road Cut,Completed,NC-MADHAVARAM,26,904700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Sasthiri Nagar Anex IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4751,Road Cut,Completed,NC-MADHAVARAM,26,2412000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Natesan Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4754,Road Cut,Completed,NC-MADHAVARAM,26,664100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Thirumalai Nagar 3rd Cross street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4755,Road Cut,Completed,NC-MADHAVARAM,26,198600,"IMPROVEMENTS TO INTERIOR BT ROAD AT New Sasthiri Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4756,Road Cut,Completed,NC-MADHAVARAM,26,904700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Nataraj Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4757,Road Cut,Completed,NC-MADHAVARAM,26,752400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Seethapathy street (Part) IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4758,Road Cut,Completed,NC-MADHAVARAM,26,1507300,"IMPROVEMENTS TO INTERIOR BT ROAD AT Vinayagar Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4759,Road Cut,Completed,NC-MADHAVARAM,26,2185700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Secretriate Colony Main Road IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4760,Road Cut,Completed,NC-MADHAVARAM,26,678500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Secretriate Colony 1st cross street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4761,Road Cut,Completed,NC-MADHAVARAM,26,762900,"IMPROVEMENTS TO INTERIOR BT ROAD AT Secretriate Colony 1st street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4762,Road Cut,Completed,NC-MADHAVARAM,26,515100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Secretriate Colony 2nd street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4763,Road Cut,Completed,NC-MADHAVARAM,26,2007100,"IMPROVEMENTS TO INTERIOR BT ROAD AT SATHYAMOORTHY STREET IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4764,Road Cut,Completed,NC-MADHAVARAM,26,2561700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Pachaiappan Colony IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4765,Road Cut,Completed,NC-MADHAVARAM,26,2713300,"IMPROVEMENTS TO INTERIOR BT ROAD AT Ganesh Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4766,Road Cut,Completed,NC-MADHAVARAM,26,1478400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Subramaniam NagarIN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4767,Road Cut,Completed,NC-MADHAVARAM,26,515100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Umapathy Nagar extn IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4768,Road Cut,Completed,NC-MADHAVARAM,26,515100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kambar Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4769,Road Cut,Completed,NC-MADHAVARAM,26,1103200,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kanchi Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4770,Road Cut,Completed,NC-MADHAVARAM,26,1478400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kanchi Nagar Extn IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4771,Road Cut,Completed,NC-MADHAVARAM,26,1281900,"IMPROVEMENTS TO INTERIOR BT ROAD AT Iyappa Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4772,Road Cut,Completed,NC-MADHAVARAM,26,752400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Valarmathi Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4773,Road Cut,Completed,NC-MADHAVARAM,26,711700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Valarmathi Nagar extn IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4775,Road Cut,Completed,NC-MADHAVARAM,26,2185700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Burial Ground Road IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4778,Road Cut,Completed,NC-MADHAVARAM,26,1061600,"IMPROVEMENTS TO INTERIOR BT ROAD AT Umapathy Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4779,Road Cut,Completed,NC-MADHAVARAM,26,752400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Vignesh Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4781,Road Cut,Completed,NC-MADHAVARAM,26,279300,"IMPROVEMENTS TO INTERIOR BT ROAD AT Rajan Nagar 1st street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4782,Road Cut,Completed,NC-MADHAVARAM,26,423100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Rajan Nagar 2nd street IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4783,Road Cut,Completed,NC-MADHAVARAM,26,1568700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Akbar Nagar IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/5435,Road Cut,Completed,NC-MADHAVARAM,26,1809400,"IMPROVEMENTS TO INTERIOR BT ROAD AT PARIMALAM NAGAR IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/5442,Road Cut,Completed,NC-MADHAVARAM,26,664100,"IMPROVEMENTS TO INTERIOR BT ROAD AT LAKSHMI NARAYANA AVENUE IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/5449,Road Cut,Completed,NC-MADHAVARAM,26,272500,"IMPROVEMENTS TO INTERIOR BT ROAD AT SATHIRI NAGAR 1ST STREET IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6271,Road Cut,Completed,NC-MADHAVARAM,26,435900,"IMPROVEMENTS TO INTERIOR BT ROAD AT VASANTHA COLONY IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6272,Road Cut,Completed,NC-MADHAVARAM,26,407300,"IMPROVEMENTS TO INTERIOR BT ROAD AT IYAPPA NAGAR MAIN ROAD (PART) IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6273,Road Cut,Completed,NC-MADHAVARAM,26,273900,"IMPROVEMENTS TO INTERIOR BT ROAD AT IYAPPA NAGAR 5th CROSS STREET IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6274,Road Cut,Completed,NC-MADHAVARAM,26,539500,"IMPROVEMENTS TO INTERIOR BT ROAD AT ROJA NAGAR IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6275,Road Cut,Completed,NC-MADHAVARAM,26,181000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THULASI NAGAR IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6276,Road Cut,Completed,NC-MADHAVARAM,26,825000,"IMPROVEMENTS TO INTERIOR BT ROAD AT RAMACHANDARA NAGAR IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6277,Road Cut,Completed,NC-MADHAVARAM,26,693300,"IMPROVEMENTS TO INTERIOR BT ROAD AT THIRUMALAI NAGAR EXTN 3rd MAIN ROAD IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6278,Road Cut,Completed,NC-MADHAVARAM,26,228300,"IMPROVEMENTS TO INTERIOR BT ROAD AT THIRUMALAI NAGAR EXTN 4th MAIN ROAD (PART) IN DN-26, U-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6279,Road Cut,Completed,NC-MADHAVARAM,26,273900,"IMPROVEMENTS TO INTERIOR BT ROAD AT SUBASH NAGAR ROAD (PART) IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6280,Road Cut,Completed,NC-MADHAVARAM,26,1241000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THIRUMALAI NAGAR1st MAIN ROAD IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6281,Road Cut,Completed,NC-MADHAVARAM,26,407000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THIRUMALAI NAGAR RENGANATHAN AVENUE IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6283,Road Cut,Completed,NC-MADHAVARAM,26,578700,"IMPROVEMENTS TO INTERIOR BT ROAD AT DEVAKI NAGAR MAIN ROAD IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6284,Road Cut,Completed,NC-MADHAVARAM,26,445800,"IMPROVEMENTS TO INTERIOR BT ROAD AT DEVAKI NAGAR 1st CROSS STREET IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6285,Road Cut,Completed,NC-MADHAVARAM,26,180200,"IMPROVEMENTS TO INTERIOR BT ROAD AT DEVAKI NAGAR 3rd STREET(PART) IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6286,Road Cut,Completed,NC-MADHAVARAM,26,569300,"IMPROVEMENTS TO INTERIOR BT ROAD AT DEVAKI NAGAR 4th STREET IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6287,Road Cut,Completed,NC-MADHAVARAM,26,1591300,"IMPROVEMENTS TO INTERIOR BT ROAD AT MAJESTIC COLONY IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6288,Road Cut,Completed,NC-MADHAVARAM,26,1403000,"IMPROVEMENTS TO INTERIOR BT ROAD AT SASTHRI NAGAR 1st MAIN ROAD IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/6291,Road Cut,Completed,NC-MADHAVARAM,26,1013400,"IMPROVEMENTS TO INTERIOR BT ROAD AT GILBAN NAGAR IN DN-26, U-7, ZONE-3.",Own Sources,3,2017-18,2018-19 L/2017-18/12377,Electrical,Completed,L-Electrical,27,8786400,"Provision of 196 Nos of 6mtr lamp post, single straight bracket with 40w LED Fitting at AVM Nagar, Ring Road Housing Sector & various streets in Div-27 & 30 of Zone-III (Madhavaram) (Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2017-18,2018-19 NC/2017-18/0425,Buildings,Completed,NC-MADHAVARAM,27,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Telugu Colony Burial Ground in Division -27, Unit-7, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/0710,Buildings,Completed,NC-MADHAVARAM,27,999000,"Construction of Addtional Class Room and Dinning Hall at Madhavaram Milk Colony Chennai Middle School in Div-27, Unit-7, Zone-3",MLACDS,3,2017-18,2018-19 NC/2017-18/10355,Storm Water Drain,Completed,NC-MADHAVARAM,27,90000,"Desilting of Side Drain at Various Street in Division -27, Unit-7, Zone-3",Own Sources,3,2017-18,2017-18 NC/2017-18/10905,Roads,Completed,NC-MADHAVARAM,27,306000,"Painting of Existing Speed Breakers at Various Street in Div-27, Unit-7, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/11441,Storm Water Drain,Completed,NC-MADHAVARAM,27,67000,REPAIRS TO SIDE DRAIN AT PERUMAL KOIL STREET AND MANDAVELI STREET IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2017-18,2017-18 NC/2017-18/11442,Buildings,Completed,NC-MADHAVARAM,27,28000,REPAIRS TO WATER SUPPLY ARRANGEMENTS AT CHENNAI PRIMARY SCHOOL AT MADHAVARAM MILK COLONY IN DIVISION 27 UNIT 7 ZONE 3,Own Sources,3,2017-18,2017-18 NC/2017-18/13313,Buildings,Completed,NC-MADHAVARAM,27,356000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT ESWARAN KOIL STREET IN DN-27,UNIT-7,ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/13315,Buildings,Completed,NC-MADHAVARAM,27,432000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT MGR STREET IN DN-27,UNIT-7,ZONE-3",Own Sources,3,2017-18,2019-20 NC/2017-18/14603,Buildings,Completed,NC-MADHAVARAM,27,109000,REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT TELUGU COLONY AND EDAIMA NAGAR IN DN 27 UNIT7 ZONE -3,Own Sources,3,2017-18,2017-18 NC/2017-18/15036,Buildings,Completed,NC-MADHAVARAM,27,389000,"CONSTRUCTION OF COMPOUND WALL AT VENU NAGAR OSR LAND IN DIV-27,UNIT-7,ZONE-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/4725,Road Cut,Completed,NC-MADHAVARAM,27,387000,"IMPROVEMENTS TO INTERIOR BT ROAD AT MCG Avenue IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4726,Road Cut,Completed,NC-MADHAVARAM,27,1136000,"IMPROVEMENTS TO INTERIOR BT ROAD AT TELUGU COLONY (TO BURIAL GROUND) IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4733,Road Cut,Completed,NC-MADHAVARAM,27,331900,"IMPROVEMENTS TO INTERIOR BT ROAD AT ALEX NAGAR MAIN ROAD IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4734,Road Cut,Completed,NC-MADHAVARAM,27,465500,"IMPROVEMENTS TO INTERIOR BT ROAD AT ESWARAN KOIL STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4735,Road Cut,Completed,NC-MADHAVARAM,27,1592500,"IMPROVEMENTS TO INTERIOR BT ROAD AT ALEX NAGAR ������������������'COLONY BHARATHIDASAN STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4736,Road Cut,Completed,NC-MADHAVARAM,27,414200,"IMPROVEMENTS TO INTERIOR BT ROAD AT ALEX NAGAR ������������������'COLONY EXTN IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 BR/2017-18/17208,Roads,Completed,BR-Bus Route Roads,28,2440000,"Restoration of road cut made by TANGEDCO at Madhavaram milk colony road (Estate off to Mattur Jn.) Dn-28, Zone-III against Challan No. BR/2017-18/0021126.",Deposit Works,3,2017-18,2019-20 L/2017-18/12372,Electrical,Completed,L-Electrical,28,9161300,"Provision of 210 Nos of 6mtr lamp post, single straight bracket with 40w LED Fitting at Pachaiappa Garden, Chandran Street & various streets in Div-28 & 29 of Zone-III (Madhavaram) (Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2017-18,2018-19 NC/2017-18/0424,Buildings,Completed,NC-MADHAVARAM,28,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Sasthiri Nagar in Division -28, Unit-7, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/10356,Storm Water Drain,Completed,NC-MADHAVARAM,28,99000,"Desilting of Side Drain at Various Street in Division -28, Unit-7, Zone-3",Own Sources,3,2017-18,2017-18 NC/2017-18/10906,Roads,Completed,NC-MADHAVARAM,28,182000,"Painting of Existing Speed Breakers at Various Street in Div-28, Unit-7, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/13917,Parks,Completed,NC-MADHAVARAM,28,320268,"MAINTENANCE OF PARK AT PADMAGIRI PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF FEB 2018 TO APR 2018 IN DN-28, ZONE-III",Own Sources,3,2017-18,2018-19 NC/2017-18/13925,Parks,Completed,NC-MADHAVARAM,28,249261,"MAINTENANCE OF PARK AT KKR GARDEN PARK QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF FEB 2018 TO APR 2018 IN DN-31, ZONE-III",Own Sources,3,2017-18,2018-19 NC/2017-18/13975,Parks,Completed,NC-MADHAVARAM,28,263689,"MAINTENANCE OF PARK AT KKR NAGAR PARK & RC FLATS PARK MTH ROAD BY QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF FEB 2018 TO APR 2018 IN DN-31, ZONE-III",Own Sources,3,2017-18,2018-19 NC/2017-18/13981,Parks,Completed,NC-MADHAVARAM,28,278255,"MAINTENANCE OF PARK VOMAKULAM (MADHAVARAM )AT QUALIFIED HORTICULATURIST FOR MAINTENANCE WORK PERIOD OF FEB 2018 TO JULY 2018 IN DN-26 , UNIT-7, ZONE-III",Own Sources,3,2017-18,2018-19 NC/2017-18/14619,Buildings,Completed,NC-MADHAVARAM,28,27000,"Providing Speed Breakers at Various Street in Div-28, Unit-7, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/14621,Buildings,Completed,NC-MADHAVARAM,28,16500,PROVIDING WATER SUPPLY ARRANGEMENTS TO PLAY GROUND AT BANK COLONY 4TH STREET IN DN -28 UNIT7 ZONE -3,Own Sources,3,2017-18,2017-18 NC/2017-18/14622,Buildings,Completed,NC-MADHAVARAM,28,17000,REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT MADHAVARAM MILK COLONY (POTTUROOM) IN DN 28 UNIT7 ZONE -3,Own Sources,3,2017-18,2017-18 NC/2017-18/9334,Roads,Completed,NC-MADHAVARAM,28,1348000,"IMPROVEMENTS TO INTERIOR BT ROAD AT at pushbammbal street in division 28 , unit 6 , zone 3.",Own Sources,3,2017-18,2018-19 NC/2017-18/0478,Buildings,Completed,NC-MADHAVARAM,29,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Velu street in Div-29, Unit-7, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/0744,Buildings,Completed,NC-MADHAVARAM,29,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Karunanithi street in Div-29, Unit-7, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/10334,Storm Water Drain,Completed,NC-MADHAVARAM,29,121000,"REPAIRS OF DAMAGED SWD SLAB AT VARIOUS STREET IN DN-29, U-7, Z-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/10335,Storm Water Drain,Completed,NC-MADHAVARAM,29,181000,"PROVIDING BOX CULVERT AT E.V.R PERIYAR STREET IN DN-29,U-7,Z-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/10352,Storm Water Drain,Completed,NC-MADHAVARAM,29,248000,"Desilting of Side Drain at Various Street in Division -29, Unit-7, Zone-3",Own Sources,3,2017-18,2017-18 NC/2017-18/10354,Storm Water Drain,Completed,NC-MADHAVARAM,29,40000,"Desilting of Storm Water Drain at Various Street in Division -29, Unit-7, Zone-3",Own Sources,3,2017-18,2017-18 NC/2017-18/10907,Roads,Completed,NC-MADHAVARAM,29,200000,"Painting of Existing Speed Breakers at Various Street in Div-29, Unit-7, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/14632,Buildings,Completed,NC-MADHAVARAM,29,55000,REPAIRS TO PUBLIC CONVENIENCE AT KARUNANITHI STREET AND E.V.R. STREET IN DN 29 UNIT7 ZONE -3,Own Sources,3,2017-18,2017-18 NC/2017-18/14654,Buildings,Completed,NC-MADHAVARAM,29,139000,"PROVIDING AND LAYING RAIN WATER DISPOSAL PIPE INSIDE FUTURA LAYOUT IN DIV-29, UNIT-7,ZONE-3",Own Sources,3,2017-18,2017-18 NC/2017-18/14659,Buildings,Completed,NC-MADHAVARAM,29,15500,REPAIRS AND MAINTENANCE OF COMPOST YARD AT VELU STREET IN DN 29 UNIT7 ZONE -3,Own Sources,3,2017-18,2017-18 NC/2017-18/4952,Roads,Completed,NC-MADHAVARAM,29,288100,"IMPROVEMENTS TO THE INTERIOR BT AT KANNABIRAN STREET IN DIV-29, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4977,Roads,Completed,NC-MADHAVARAM,29,216000,"IMPROVEMENTS TO THE INTERIOR BT AT DEVARAJAN STREET IN DIV-29, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4981,Roads,Completed,NC-MADHAVARAM,29,279100,"IMPROVEMENTS TO THE INTERIOR BT AT PERUMAL KOIL 2ND STREET IN DIV-29, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/5199,Road Cut,Completed,NC-MADHAVARAM,29,282100,"IMPROVEMENTS TO THE INTERIOR BT AT PERUMAL KOIL 1ST STREET IN DIV-29, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/5201,Road Cut,Completed,NC-MADHAVARAM,29,385000,"IMPROVEMENTS TO THE INTERIOR BT AT PERUMAL KOIL EXTN IN DIV-29, UNIT-7, ZONE-3",Own Sources,3,2017-18,2018-19 BR/2017-18/17207,Roads,Completed,BR-Bus Route Roads,30,2430000,"Restoration of road cut made by TANGEDCO at Madhavaram milk colony road (Check post to Estate office) Dn-28, Zone-III against Challan No. BR/2017-18/0021126.",Deposit Works,3,2017-18,2018-19 D/2017-18/14718,Storm Water Drain,Completed,D-Storm Water Drains,30,17160000,"Restoration and other improvements to Aavin kulam pond, Perumal koil street pond, Panda kulam pond, Kumarappapuram pond, Athikulam pond, Vattamuni pond, Thamaraikulam pond (Kavankkarai), and Pura kulam pond for augmentation of water supply in Division -22,27,28 and 30, Zone - 3 (Package - IV)",SMART CITY - SWD,3,2017-18,2020-21 NC/2017-18/0422,Buildings,Completed,NC-MADHAVARAM,30,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Masilamani Nagar (Secreatriate officer colony Open Ground) in Division -30, Unit-8, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/10367,Storm Water Drain,Completed,NC-MADHAVARAM,30,218000,"Damaged SWD at Ring Road Housing Sector & Wherever necessary in Div-30, Unit-8, Zone-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/10368,Storm Water Drain,Completed,NC-MADHAVARAM,30,146000,"Desilting of Side drain at Various street in Div-30, Unit - 8, Zone - 3",Own Sources,3,2017-18,2017-18 NC/2017-18/10369,Storm Water Drain,Completed,NC-MADHAVARAM,30,173000,"Desilting of Strom Water Drain at Various street in Division - 30, Unit - 8, Zone - 3",Own Sources,3,2017-18,2017-18 NC/2017-18/10673,Roads,Completed,NC-MADHAVARAM,30,140000,"Painting of Existing Speed Breakers at Various Street in Div-30, Unit-8, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/11440,Buildings,Completed,NC-MADHAVARAM,30,79000,REPAIRS TO WATER SUPPLY ARRANGEMENTS AT PUBLIC TOILET AT BHARATHIAR STREET AND INSIDE MRH ROAD BUS STAND IN DIVISION 30 UNIT 8 ZONE 3,Own Sources,3,2017-18,2017-18 NC/2017-18/4669,Road Cut,Completed,NC-MADHAVARAM,30,293000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Ring Road Housing Sector IN DIV-30, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4670,Road Cut,Completed,NC-MADHAVARAM,30,123000,"IMPROVEMENTS TO INTERIOR BT ROAD AT V.S Mani Nagar 1st Main Road 2nd Cross street IN DIV-30, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 P/2017-18/13016,Parks,Completed,P-Parks and Playfields,30,5035529,"FORMATION OF NEW PARK AT V.S.MANI NAGAR, PHASE - I IN DN-30, ZONE - III",Grants,3,2017-18,2018-19 P/2017-18/13022,Parks,Completed,P-Parks and Playfields,30,4809287,"FORMATION OF NEW PARK AT V.S.MANI NAGAR PHASE- II IN DN-30, ZONE - III",Grants,3,2017-18,2018-19 BR/2017-18/17206,Roads,Completed,BR-Bus Route Roads,31,2410000,"Restoration of road cut made by TANGEDCO at Madhavaram milk colony road (Tapal petti jn to Check post) Dn-31, Zone-III against Challan No. BR/2017-18/0021126.",Deposit Works,3,2017-18,2018-19 L/2017-18/6470,Electrical,Completed,L-Electrical,31,100000,"Laying of 4x16sq.mm cable and Supply, Fixing and Termination of 8nos of 2core fuse box at pandian street and dhana singh mathiri street in division - 31, Zone III, Madhavaram",Own Sources,3,2017-18,2018-19 NC/2017-18/10370,Storm Water Drain,Completed,NC-MADHAVARAM,31,117000,"Desilting of Side Drain at Various Street in Division - 31, Unit - 8, Zone - 3",Own Sources,3,2017-18,2017-18 NC/2017-18/10371,Storm Water Drain,Completed,NC-MADHAVARAM,31,31000,"Desilting of Strom Water Drain at Various Street in Division - 31, Unit - 8, Zone - 3",Own Sources,3,2017-18,2017-18 NC/2017-18/10674,Roads,Completed,NC-MADHAVARAM,31,85000,"Painting of Existing Speed Breakers at Various Street in Div-31, Unit-8, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/11390,Buildings,Completed,NC-MADHAVARAM,31,97500,"REPAIRS TO WATER SUPPLY ARRANGEMENTS AT PUBLIC TOILET AT KANNABIRAN KOIL STREET, AMBEDKAR NAGAR, PANDIAN STREET AND MUTHUMARIAMMAN KOIL STREET IN DIVISION 31 UNIT 8 ZONE 3",Own Sources,3,2017-18,2017-18 NC/2017-18/11391,Storm Water Drain,Completed,NC-MADHAVARAM,31,87900,"REPAIRS TO SIDE DRAIN AT K.P. GARDEN, AMBEDKAR NAGAR JUNCTION OF GNT ROAD IN DIVISION 31 UNIT 8 ZONE 3",Own Sources,3,2017-18,2017-18 NC/2017-18/15584,Buildings,Completed,NC-MADHAVARAM,31,1445000,"Proposed Construction of Compound wall for Burial Ground at Kolkatta shop Main road in div-31, Unit-8, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/16311,Buildings,Completed,NC-MADHAVARAM,31,125000,"ANNUAL MAINTENANCE FOR BIO-GAS PLANT AT MUTHUMARIAMMAN KOVIL STREET IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2017-18,2019-20 NC/2017-18/7671,Buildings,Completed,NC-MADHAVARAM,31,115000,"PROVIDING WATER SUPPLY ARRANGEMENTS IN PUBLIC CONVENIENCE AT KANNABIRAN KOVIL STREET ( NEAR INDITAL COMPANY) IN DIV-31, UNIT-8, ZONE-31.",Own Sources,3,2017-18,2018-19 NC/2017-18/9797,Buildings,Completed,NC-MADHAVARAM,31,115000,"Providing Water Supply arrangements in Public Convenience at Pandian Street in div-31, Unit-8, Zone-3.",Own Sources,3,2017-18,2018-19 BR/2017-18/11546,Roads,Completed,BR-Bus Route Roads,32,17280000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Cudappa Road in Dn-32, Zone-III",Grants,3,2017-18,2018-19 BR/2017-18/11549,Roads,Completed,BR-Bus Route Roads,32,1500000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at K.K.Road (Patch) in Dn-129, Zone-X",Grants,3,2017-18,2018-19 BR/2017-18/11746,Roads,Completed,BR-Bus Route Roads,32,2169000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic waste along with traffic improvement work at Britania Road in Dn-24 & 25, Zone-III",Grants,3,2017-18,2018-19 NC/2017-18/10372,Storm Water Drain,Completed,NC-MADHAVARAM,32,438000,"Desilting of Side Drain at Various Street in Division - 32, Unit - 8, Zone - 3",Own Sources,3,2017-18,2017-18 NC/2017-18/10675,Roads,Completed,NC-MADHAVARAM,32,97000,"Painting of Existing Speed Breakers at Various Street in Div-32, Unit-8, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/11562,Storm Water Drain,Completed,NC-MADHAVARAM,32,28500,REPAIRS TO SIDE DRAIN & STORM WATER DRAIN AT TEACHERS COLONY 4TH CROSS STREET AND LAKSHMI NARAYANA PERUMAL KOIL STREET IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2017-18,2017-18 NC/2017-18/11563,Buildings,Completed,NC-MADHAVARAM,32,52000,REPAIRS TO SUMP AND WATER SUPPLY ARRANGEMENTS AT AMMA UNAVAGAM AT VILLIVAKKAM ROAD IN DIVISION 32 UNIT 8 ZONE 3,Own Sources,3,2017-18,2017-18 NC/2017-18/16561,Storm Water Drain,Completed,NC-MADHAVARAM,32,165000,"Improvements and Repairs side Drain at Ashoka st Dn-32, U-8, Z-3",Own Sources,3,2017-18,2018-19 NC/2017-18/16646,Storm Water Drain,Completed,NC-MADHAVARAM,32,420000,"Repair & Improvements Side drain at Amman koil street in Division - 32, Unit - 8, Zone - 3",Own Sources,3,2017-18,2018-19 NC/2017-18/16648,Storm Water Drain,Completed,NC-MADHAVARAM,32,43000,"Repair to Side drain at Kadappa Road (Damage Portion) in Division - 32, Unit - 8, Zone - 3",Own Sources,3,2017-18,2018-19 NC/2017-18/4444,Road Cut,Completed,NC-MADHAVARAM,32,1315100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Amman Koil street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4447,Road Cut,Completed,NC-MADHAVARAM,32,1315100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Asoka Street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4451,Road Cut,Completed,NC-MADHAVARAM,32,1327000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Bajanai koil street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4453,Road Cut,Completed,NC-MADHAVARAM,32,603400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kaveri Colony IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4455,Road Cut,Completed,NC-MADHAVARAM,32,1671500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Teacher's Colony 2nd Main Road IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4466,Road Cut,Completed,NC-MADHAVARAM,32,2412000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Teacher's Colony 4th Main Road IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4470,Road Cut,Completed,NC-MADHAVARAM,32,766800,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kalaimagal Nagar 1 & 2 IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4472,Road Cut,Completed,NC-MADHAVARAM,32,1418000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Raman Nagar & Sankar Nagar IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4473,Road Cut,Completed,NC-MADHAVARAM,32,1673000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Arul Nagar & Lalitha Nagar IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4475,Road Cut,Completed,NC-MADHAVARAM,32,802000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Moogambikai Nagar IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4486,Road Cut,Completed,NC-MADHAVARAM,32,1368000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Teacher's colony 3rd Cross street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4495,Road Cut,Completed,NC-MADHAVARAM,32,2724000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Bharathiyar street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4497,Road Cut,Completed,NC-MADHAVARAM,32,2406000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Lakshmi Narayana Perumal Koil street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4500,Road Cut,Completed,NC-MADHAVARAM,32,1383000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Teacher's Colony 1st cross street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6181,Road Cut,Completed,NC-MADHAVARAM,32,420000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Sankara lingam street & E.V.R street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6209,Road Cut,Completed,NC-MADHAVARAM,32,344800,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kannaiamman Koil street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6212,Road Cut,Completed,NC-MADHAVARAM,32,383400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Doulath B colony IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6215,Road Cut,Completed,NC-MADHAVARAM,32,919200,"IMPROVEMENTS TO INTERIOR BT ROAD AT Teachers colony 2nd cross street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6216,Road Cut,Completed,NC-MADHAVARAM,32,353400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Teachers colony 4th cross street IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6220,Road Cut,Completed,NC-MADHAVARAM,32,938300,"IMPROVEMENTS TO INTERIOR BT ROAD AT Teachers colony 5th main road IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/9215,Buildings,Completed,NC-MADHAVARAM,32,132000,PROVIDING WATER SUPPLY ARRANGEMENTS IN PUBLIC CONVENIENCE AT ASHOKA STREET IN DN 32 UNIT 8 ZONE -3,Own Sources,3,2017-18,2018-19 BR/2017-18/7625,Road Cut,Completed,BR-Bus Route Roads,33,2100000,"RESTORATION OF ROAD CUT MADE CMWSSB AT KADAPPA ROAD WEST IN DIVISION -32, ZONE - 3",Deposit Works,3,2017-18,2017-18 BR/2017-18/7626,Road Cut,Completed,BR-Bus Route Roads,33,1830000,"RESTORATION OF ROAD CUT MADE CMWSSB AT KADAPPA ROAD EAST IN DIVISION -32, ZONE - 3",Deposit Works,3,2017-18,2017-18 D/2017-18/8265,Storm Water Drain,Completed,D-Storm Water Drains,33,2476000,"Construction of Storm water drain of size 900x900mm along Sri Raman Nagar(South) from School Road to Thanigachalam B Block in Dn-33,Zone-III(Reach-II).",Own Sources,3,2017-18,2018-19 D/2017-18/8267,Storm Water Drain,Completed,D-Storm Water Drains,33,2385000,"Construction of storm water drain of size 900x900mm along Sri Raman Nagar (South) from PWD canal to chainage 150M in Dn-33,ZoneIII (Reach-I)",Own Sources,3,2017-18,2018-19 L/2017-18/12369,Electrical,Completed,L-Electrical,33,19023300,"Provision of 279 Nos of 6mtr lamp post, single straight bracket with 40w LED Fitting & 128 Nos of 6mtr lamp post with 90w LED Fitting at Ramalinga Colony 'C' blk, Annapoorni nagar & various streets in Div-33 of Zone-III (Madhavaram) (Sch of rate 2015-16)","Loans, Grants And Own Sources",3,2017-18,2018-19 NC/2017-18/0423,Buildings,Completed,NC-MADHAVARAM,33,2030000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Selvam Nagar (Open Ground) in Division -33, Unit-8, Zone-3",Own Sources,3,2017-18,2018-19 NC/2017-18/0841,Buildings,Completed,NC-MADHAVARAM,33,1300000,"Construction of ICDS Center at Periyar Nagar in Div-33,Unit-8,Zone-3",MLACDS,3,2017-18,2018-19 NC/2017-18/10366,Storm Water Drain,Completed,NC-MADHAVARAM,33,278000,"Repairs and Improvements work to SWD wherever necessary in Div-33 Unit-8, Zone-3.",Own Sources,3,2017-18,2017-18 NC/2017-18/10373,Storm Water Drain,Completed,NC-MADHAVARAM,33,190000,"Desilting of Side Drain at Various street in Division - 33, Unit - 8, Zone - 3",Own Sources,3,2017-18,2017-18 NC/2017-18/10374,Storm Water Drain,Completed,NC-MADHAVARAM,33,172000,"Desilting of Side Drain at Various Street in Division - 33, Unit - 8, Zone - 3",Own Sources,3,2017-18,2017-18 NC/2017-18/10904,Roads,Completed,NC-MADHAVARAM,33,110000,"Painting of Existing Speed Breakers at Various Street in Div-33, Unit-8, Zone-3.",Own Sources,3,2017-18,2018-19 NC/2017-18/11564,Storm Water Drain,Completed,NC-MADHAVARAM,33,109000,"PROVIDING AND LAYING HUME PIPES AT ROAD CROSSING AT VGP NAGAR, ELIZABETH NAGAR, RAGAVENDRA NAGAR, SRI KRISHNA NAGAR AND SUMATHI NAGAR IN DIVISION 33 UNIT 8 ZONE 3",Own Sources,3,2017-18,2017-18 NC/2017-18/11567,Buildings,Completed,NC-MADHAVARAM,33,62000,REPAIRS TO DRAINAGE ARRANGEMENTS TO CHENNAI PRIMARY SCHOOL AT NEHRU STREET IN DIVISION 33 UNIT 8 ZONE 3,Own Sources,3,2017-18,2017-18 NC/2017-18/12920,Roads,Completed,NC-MADHAVARAM,33,687000,"IMPROVEMENTS TO INTERIOR BT ROAD AT CHELLIAIAH NAGAR LINK ROAD IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4548,Road Cut,Completed,NC-MADHAVARAM,33,603400,"IMPROVEMENTS TO INTERIOR BT ROAD AT V.O.C Street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4595,Road Cut,Completed,NC-MADHAVARAM,33,306900,"IMPROVEMENTS TO INTERIOR BT ROAD AT Ambal Nagar IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4597,Road Cut,Completed,NC-MADHAVARAM,33,497000,"IMPROVEMENTS TO INTERIOR BT ROAD AT Brindhavan Garden 1st street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4600,Road Cut,Completed,NC-MADHAVARAM,33,715500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Brindhavan Garden 2nd street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4601,Road Cut,Completed,NC-MADHAVARAM,33,603400,"IMPROVEMENTS TO INTERIOR BT ROAD AT Brindhavan Garden 3rd street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4604,Road Cut,Completed,NC-MADHAVARAM,33,715500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kamaraj South IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4607,Road Cut,Completed,NC-MADHAVARAM,33,904700,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kamaraj West IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4646,Road Cut,Completed,NC-MADHAVARAM,33,331900,"IMPROVEMENTS TO INTERIOR BT ROAD AT Anna Salai 3rd cross street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4650,Road Cut,Completed,NC-MADHAVARAM,33,306900,"IMPROVEMENTS TO INTERIOR BT ROAD AT Vardharajan Nagar 1st street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4651,Road Cut,Completed,NC-MADHAVARAM,33,331200,"IMPROVEMENTS TO INTERIOR BT ROAD AT Vardharajan Nagar 2nd street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4657,Road Cut,Completed,NC-MADHAVARAM,33,689500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Thanigachalm Nagar 'C' Block 3rd cross street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4658,Road Cut,Completed,NC-MADHAVARAM,33,1240500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Thanigachalm Nagar 'c' block IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/4662,Road Cut,Completed,NC-MADHAVARAM,33,689500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Thanigachalm Nagar 'C' Block 1st cross street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6352,Road Cut,Completed,NC-MADHAVARAM,33,1008900,"IMPROVEMENTS TO INTERIOR BT ROAD AT Sarangapani street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6354,Road Cut,Completed,NC-MADHAVARAM,33,689500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Sundramorthy street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6355,Road Cut,Completed,NC-MADHAVARAM,33,1240500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Selvam nagar 6th street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6371,Road Cut,Completed,NC-MADHAVARAM,33,826100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kamarajar 1st street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6372,Road Cut,Completed,NC-MADHAVARAM,33,826100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kamarajar 2nd street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6373,Road Cut,Completed,NC-MADHAVARAM,33,826100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kamarajar 3rd street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6374,Road Cut,Completed,NC-MADHAVARAM,33,1559100,"IMPROVEMENTS TO INTERIOR BT ROAD AT Kamarajar school road IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6403,Road Cut,Completed,NC-MADHAVARAM,33,495500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Mahatma gandhi 1st street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/6404,Road Cut,Completed,NC-MADHAVARAM,33,495500,"IMPROVEMENTS TO INTERIOR BT ROAD AT Mahatma gandhi 2nd street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/9361,Road Cut,Completed,NC-MADHAVARAM,33,603400,"IMPROVEMENTS TO INTERIOR BT ROAD AT MADURAI MANAVALAN NAGAR IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/9367,Road Cut,Completed,NC-MADHAVARAM,33,331900,"IMPROVEMENTS TO INTERIOR BT ROAD AT ANNA SALAI 5TH CROSS STREET IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/9368,Road Cut,Completed,NC-MADHAVARAM,33,331900,"IMPROVEMENTS TO INTERIOR BT ROAD AT KARPAGAM NAGAR 1ST STREET IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 NC/2017-18/9369,Road Cut,Completed,NC-MADHAVARAM,33,689500,"IMPROVEMENTS TO INTERIOR BT ROAD AT BALAKRISHNA NAGAR MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2017-18,2018-19 P/2017-18/11311,Parks,Completed,P-Parks and Playfields,33,7200000,FORMATION OF NEW PARK AT V.S.MANI NAGAR PHASE III,Grants,3,2017-18,2019-20 B/2017-18/1778,Buildings,Completed,B-Buildings,34,10086119,"PROPOSED CONSTRUCTION OF UPHC HOSPITAL BUILDING AT VIVEKANANDA NAGAR IN DIV-34 , ZONE-4.",Own Sources,4,2017-18,2018-19 L/2017-18/14843,Electrical,Completed,L-Electrical,34,184300,"Replacement of 5 nos of old Kiosk Pillar box with 5 nos of new Kiosk Pillar Box in Chinadimadam, TH Road in div 35 and Association Road, Govindaswamy Nagar, Ponuswamy Nagar in div 34 Zone 4.",Own Sources,4,2017-18,2018-19 L/2017-18/14846,Electrical,Completed,L-Electrical,34,187000,"Supply, Fixing and Termination of 157 nos of 2core SMC fuse box in Thiruvallur salai, Seetharaman nagar, Narayana swamy garden, solaiamman kovil st and various location in div 34 Zone 4.",Own Sources,4,2017-18,2018-19 L/2017-18/8112,Electrical,Completed,L-Electrical,34,196400,"Replacement of Over Head wires with 535 mtrs of 2x16sqmm and 40mtrs of 3 1/2x25 sqmm ALU cable at School Road, Amutham Nagar and various loactions in Div 34 Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/8115,Electrical,Completed,L-Electrical,34,193600,"Replacement of Over Head wires with 575 mtrs of 2x16sqmm cable at SR Nagar, Kadumbadi Amman St, Venkateshwara Nagar and various loactions in Div 34 Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/0888,Buildings,Completed,ND-TONDIARPET,34,997000,Resource Recovery center at Thendral nagar 4th Street in div-34 Uni-9 Zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/0895,Buildings,Completed,ND-TONDIARPET,34,989000,Resource Recovery center at Manali salai burial ground in div-34 Uni-9 Zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/12832,Roads,Completed,ND-TONDIARPET,34,1352000,"IMPROVEMENT OF BT ROAD AT KADUMPADI AMMAN KOIL STREET IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12833,Roads,Completed,ND-TONDIARPET,34,229000,"IMPROVEMENT OF BT ROAD AT UNION CARBIDE COLONY 18TH STREET IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12834,Roads,Completed,ND-TONDIARPET,34,121000,"IMPROVEMENT OF BT ROAD AT UNION CARBIDE COLONY 3RD STREET IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12835,Roads,Completed,ND-TONDIARPET,34,134000,"IMPROVEMENT OF BT ROAD AT UNION CARBIDE COLONY 19TH STREET IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12836,Roads,Completed,ND-TONDIARPET,34,134000,"IMPROVEMENT OF BT ROAD AT ANNAI VELANKANNI NAGAR IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12838,Roads,Completed,ND-TONDIARPET,34,642000,"IMPROVEMENT OF BT ROAD AT MMC ROAD IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12840,Roads,Completed,ND-TONDIARPET,34,134000,"IMPROVEMENT OF BT ROAD AT RAGAVENDRA NAGAR IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12841,Roads,Completed,ND-TONDIARPET,34,838000,"IMPROVEMENT OF BT ROAD AT GOVINDASAMY NAGAR IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12842,Roads,Completed,ND-TONDIARPET,34,4949000,"IMPROVEMENT OF BT ROAD AT DURGAI AVENUE 13TH STREET IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12859,Roads,Completed,ND-TONDIARPET,34,170000,"IMPROVEMENT OF BT ROAD AT SRIVARI NAGAR IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12861,Roads,Completed,ND-TONDIARPET,34,201000,"IMPROVEMENT OF BT ROAD AT AMBIKA NAGAR 5TH STREET IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12865,Roads,Completed,ND-TONDIARPET,34,1559000,"IMPROVEMENT OF BT ROAD AT KALASATHAMMAN KOIL STREET IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/12871,Roads,Completed,ND-TONDIARPET,34,103000,"IMPROVEMENT OF BT ROAD AT BURMA MAHAL (OPP) ROAD IN DIVISION-34, UNIT-9, ZONE-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/1704,Buildings,Completed,ND-TONDIARPET,34,280000,"IMPROVEMENTS TO AMMAUNAGAM AT VENKATESHWARA COLONY IN DIV-34, UNIT-09, ZONE-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/8188,Storm Water Drain,Completed,ND-TONDIARPET,34,190000,"Desilting of SWD and Repairing of door at Milk colony road in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8189,Storm Water Drain,Completed,ND-TONDIARPET,34,120000,"Desilting of SWD and Repairing of door at Arul nagar main road in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8190,Storm Water Drain,Completed,ND-TONDIARPET,34,120000,"Desilting of SWD and Repairing of door at Seetharam nagar main road in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8191,Storm Water Drain,Completed,ND-TONDIARPET,34,240000,"Desilting of SWD and Repairing of door at Manali salai in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8202,Storm Water Drain,Completed,ND-TONDIARPET,34,90000,"Desilting of SWD and Repairing of door at School road in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8204,Storm Water Drain,Completed,ND-TONDIARPET,34,240000,"Desilting of SWD and Repairing of door at Vedhantha murugappa street in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8206,Storm Water Drain,Completed,ND-TONDIARPET,34,300000,"Desilting of SWD and Repairing of door at Kadumpadi amman koil street in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8207,Storm Water Drain,Completed,ND-TONDIARPET,34,150000,"Desilting of SWD and Repairing of door at Jambuli street in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8208,Storm Water Drain,Completed,ND-TONDIARPET,34,120000,"Desilting of SWD and Repairing of door at Venkateswara colony main road in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/8209,Storm Water Drain,Completed,ND-TONDIARPET,34,60000,"Desilting of SWD and Repairing of door at Ravi garden main road in Division-34, Unit-09, Zone-IV",Own Sources,4,2017-18,2017-18 ND/2017-18/9219,Storm Water Drain,Completed,ND-TONDIARPET,34,100000,"Minor Repair works of SWD at various location in DN-34, U-9, Z-IV.",Own Sources,4,2017-18,2017-18 B/2017-18/15567,Buildings,Completed,B-Buildings,35,843000,"Supplying and fixing of Two seater bench cum tables for propsed smart classes in CMS Chinnandimadam in DN 35 Zone 4, CMS Pudhumanaikuppam in DN 43 Zone 4, CUGMS Washermenpet in DN 53 Zone 5 and CUGMS Angappan street in DN 60 Zone 5",Own Sources,4,2017-18,2018-19 L/2017-18/0829,Electrical,Completed,L-Electrical,35,199300,Removal of 9 nos of old OH lamp post in TH road Moolakadi JN and reerection it in TH Road Kadumbadiamman road JN and Towards Solaiamman Kovil in div 35 Zone IV,Own Sources,4,2017-18,2017-18 L/2017-18/0832,Electrical,Completed,L-Electrical,35,189600,Removal of 10 nos of old OH lamp post in TH road and reerection it in Kadumbadiamman road opp to KKD Nagar Bus Depo in div 35 Zone IV,Own Sources,4,2017-18,2017-18 L/2017-18/14845,Electrical,Completed,L-Electrical,35,184300,"Replacement of 5 nos of old Kiosk Pillar box with 5 nos of new Kiosk Pillar Box in kavery salai, Gandhi Nagar 5th St, Kamaraj Salai near GNT Road, Kamaraj Salai near Gandhi Nagar, Sivasankaran ST in div 35 Zone 4.",Own Sources,4,2017-18,2018-19 L/2017-18/14848,Electrical,Completed,L-Electrical,35,189400,"Supply, Fixing and Termination of 159 nos of 2core SMC fuse box in Cauvery Salai, Techers Colony, Gandhi Nagar in div 35 , KKR Town, Venkateshwara nagar, and various location in div 34 Zone 4.",Own Sources,4,2017-18,2018-19 L/2017-18/6631,Electrical,Completed,L-Electrical,35,917400,Replacement of cable 2432 mtrs 2 X 16 sq mm cable at KKD Nagar block 1 & II in div 35 Zone IV.,Own Sources,4,2017-18,2018-19 L/2017-18/6786,Electrical,Completed,L-Electrical,35,989800,Replacement of cable 2706 mtrs 2 X 16 sq mm cable at KKD Nagar block II & III in div 35 Zone IV.,Own Sources,4,2017-18,2018-19 L/2017-18/6789,Electrical,Completed,L-Electrical,35,967000,Replacement of 2631 Mtrs of 2x16 Sqmm Cable at KKD Nagar block IV & V in div 35 Zone IV.,Own Sources,4,2017-18,2018-19 L/2017-18/6792,Electrical,Completed,L-Electrical,35,976400,"Replacement of over head wires with 2700 Mtrs of 2x16 Sqmm Cable at Muthamizh Nagar Block I, II & III in div 35 Zone IV.",Own Sources,4,2017-18,2018-19 L/2017-18/6795,Electrical,Completed,L-Electrical,35,959000,Replacement of over head wires with 2660 Mtrs of 2x16 Sqmm Cable at Muthamizh Nagar Block IV to VI in div 35 Zone IV.,Own Sources,4,2017-18,2018-19 L/2017-18/6797,Electrical,Completed,L-Electrical,35,847600,Replacement of over head wires with 2340 Mtrs of 2x16 Sqmm Cable at Muthamizh Nagar Block VII & VIII in div 35 Zone IV.,Own Sources,4,2017-18,2018-19 L/2017-18/8117,Electrical,Completed,L-Electrical,35,198400,"Replacement of Over Head wires with 540 mtrs of 2x16sqmm and 40mtrs of 3 1/2x25 sqmm ALU cable at Ponan Street, Anjugam Street , VOC Street and various loactions in Div 35 Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/8118,Electrical,Completed,L-Electrical,35,197300,"Replacement of Over Head wires with 585 mtrs of 2x16sqmm cable at Krishanan Street, Teachers Colony and various loactions in Div 35 Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/0836,Buildings,Completed,ND-TONDIARPET,35,540000,Construction of New Resource Recovery Center at 7th Block Muthamil Nagar in Div-35 Unit-9 Zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/0837,Buildings,Completed,ND-TONDIARPET,35,650000,Construction of new resource recovery centerat 6th main road 5th Block KKD nagar in Div-35 Unit-9 Zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/0838,Buildings,Completed,ND-TONDIARPET,35,817000,Construction of new resource recovery center at Anjugam nagar PC in div-35 unit-9 zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/10476,Buildings,Completed,B-Buildings,35,180000,Providing SMART Classroom at Chennai Middle School at Chinnandimadam TH Road in Div-35 Unit-9 Zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/11250,Buildings,Completed,ND-TONDIARPET,35,500000,"Repair Work to SWD at north avcenue road and muthamil nagar 2nd main road junction and KKD nagar 2,3,4th block pipeline crossing in div-35 unit-9 zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/12955,Roads,Completed,ND-TONDIARPET,35,761000,"IMPROVEMENT OF BT ROAD WORK AT Dr. ANNA SALAI KODUNGAIYUR IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12958,Roads,Completed,ND-TONDIARPET,35,553000,"IMPROVEMENT OF BT ROAD WORK AT SATHYAVANI MUTHU STREET ERUKKANCHERRY PART-1 IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12959,Roads,Completed,ND-TONDIARPET,35,2515000,"IMPROVEMENT OF BT ROAD WORK AT MUTHUTAMIL NAGAR WEST AVENUE ROAD IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12960,Roads,Completed,ND-TONDIARPET,35,2786000,"IMPROVEMENT OF BT ROAD WORK AT MUTHUTAMIL NAGAR EAST AVENUE ROAD IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12961,Roads,Completed,ND-TONDIARPET,35,267000,"IMPROVEMENT OF BT ROAD WORK AT MUTHUTAMIL NAGAR 103rd STREET IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12962,Roads,Completed,ND-TONDIARPET,35,267000,"iMPROVEMENT OF BT ROAD WORK AT MUTHUTAMIL NAGAR 105th STREET IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12963,Roads,Completed,ND-TONDIARPET,35,535000,"IMPROVEMENT OF BT ROAD WORK AT SATHYAVANI MUTHU STREET ERUKKANCHERRY PART-2 IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12964,Roads,Completed,ND-TONDIARPET,35,1905000,"IMPROVEMENT OF BT ROAD WORK AT MUTHUTAMIL NAGAR SOUTH AVENUE ROAD IN DIV-35, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/1516,Buildings,Completed,ND-TONDIARPET,35,275000,"Improvements to Amma unavagam Phase -1,6th main road ,2nd block,muthamil nagar div-35, unit-09,zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/1718,Buildings,Completed,ND-TONDIARPET,35,2500000,"ADDITIONAL CONSTRUCTION OF FIRST AND SECOND FLOOR CLASS ROOMS AT CHINNADIMADAM IN DIV-35,UNIT-09,ZONE-04",Own Sources,4,2017-18,2018-19 ND/2017-18/3176,Parks,Completed,ND-TONDIARPET,35,360000,"IMPROVEMENTS TO KRISHNAN PARK AT KRISHNAN STREET IN DIV-35,UNIT-09,ZONE-04.",Own Sources,4,2017-18,2020-21 ND/2017-18/4022,Buildings,Completed,ND-TONDIARPET,35,765000,"Improvements to Chennai High School at Anna salai,Erukkencherry in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/8498,Storm Water Drain,Completed,ND-TONDIARPET,35,116000,"Desilting of Storm Water Drain at KKD Nagar 5th Block 5th cross street in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8499,Storm Water Drain,Completed,ND-TONDIARPET,35,50000,"Desilting of Storm Water Drain at KKD Nagar Abirami Avenue 6th street in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8500,Storm Water Drain,Completed,ND-TONDIARPET,35,255000,"Desilting of Storm Water Drain at KKD NAGAR 6th Main road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8501,Storm Water Drain,Completed,ND-TONDIARPET,35,85000,"Desilting of Storm Water Drain at Ambedkar street (Erukkencherry) in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8502,Storm Water Drain,Completed,ND-TONDIARPET,35,146000,"Desilting of Storm Water Drain at Muthamil Nagar 5th Main Road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8503,Storm Water Drain,Completed,ND-TONDIARPET,35,81000,"Desilting of Storm Water Drain at Anna Salai Erukkencherry in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8504,Storm Water Drain,Completed,ND-TONDIARPET,35,191000,"Desilting of Storm Water Drain at T.H.Road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8505,Storm Water Drain,Completed,ND-TONDIARPET,35,121000,"Desilting of Storm Water Drain at Muthamil Nagar West Avenue Road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8506,Storm Water Drain,Completed,ND-TONDIARPET,35,114000,"Desilting of Storm Water Drain at Muthamil Nagar North Avenue Road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8509,Storm Water Drain,Completed,ND-TONDIARPET,35,170000,"Desilting of Storm Water Drain at Muthamil Nagar East Avenue Road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8513,Storm Water Drain,Completed,ND-TONDIARPET,35,125000,"Desilting of Storm Water Drain at Muthamil Nagar West Avenue Road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8518,Storm Water Drain,Completed,ND-TONDIARPET,35,122000,"Desilting of Storm Water Drain at Thiruvalluvar Salai in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8520,Storm Water Drain,Completed,ND-TONDIARPET,35,424000,"Desilting of Storm Water Drain at KKD Nagar Sidco 1st ,2nd,3rd s Main road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/8524,Storm Water Drain,Completed,ND-TONDIARPET,35,24000,"Desilting of Storm Water Drain at KKD Nagar 3rd Main road in Div-35, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/9218,Storm Water Drain,Completed,ND-TONDIARPET,35,446000,"Repairs and maintanece of Storm water drain at Muthamil Nagar, kamaraj salai, KKD Nagar and other location in division 35,unit-09, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/9911,Buildings,Completed,ND-TONDIARPET,35,155000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for 3 month at K.K.D Nagar Bus Depot in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9912,Buildings,Completed,ND-TONDIARPET,35,155000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for 3months at K.K.D Nagar Bus Depot in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9913,Buildings,Completed,ND-TONDIARPET,35,1245000,"Providing Portable Toilet 3 +3 Nos For men and Women with Water Tank 2000Lt on Rental Basis and Maintenance for one year at kannadasan nagar bus depot in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9914,Road Cut,Completed,ND-TONDIARPET,35,813000,"Providing Portable Toilets 4 Nos with Water Tank 2000 Lit on Rental Basis and Maintenance for one Year at Muthamil nagar 8th Block Market in div-35,unit-9, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/9915,Buildings,Completed,ND-TONDIARPET,35,1245000,"Providing Portable Toilet 3 +3 Nos Formen and Women with Water Tank 2000Lt on Rental Basis and Maintenance for one year at sathiyavani muthu street, Moolakadai Junction in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9916,Road Cut,Completed,ND-TONDIARPET,35,203000,"Providing Portable Toilets 4 Nos with Water Tank 2000 Lit on Rental Basis and Maintenance for 3 month at Muthamil nagar 8th Block Market in div-35,unit-9, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/9917,Buildings,Completed,ND-TONDIARPET,35,155000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for 3 Month at Sathiyavani Muthu Street Moolakadai in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9918,Buildings,Completed,ND-TONDIARPET,35,155000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for 3 monthr at sathiyavani muthu street Moolakadai Junction in Division - 35, Unit - 9, Zone - 4.",Own Sources,4,2017-18,2018-19 P/2017-18/13027,Parks,Completed,P-Parks and Playfields,35,7162834,"FORMATION OF NEW PARK AT (HANSA lAYOUT), E.H.ROAD IN DN-35, ZONE - IV.",Grants,4,2017-18,2018-19 B/2017-18/0353,Buildings,Completed,B-Buildings,36,10100000,"PROPOSED CONSTRUCTION OF UPHC HOSPITAL BUILDING AT SHARMA NAGAR IN DIV-36,ZONE-4",Own Sources,4,2017-18,2018-19 BR/2017-18/8205,Roads,Completed,BR-Bus Route Roads,36,136000,"refixing of 1 no of modern Bus shelter at Sharma Nagar - Erukkancheri High Road in Dn-37, Zone-4",Own Sources,4,2017-18,2018-19 L/2017-18/6816,Electrical,Completed,L-Electrical,36,982200,"Replacement of over head wires with 2736 Mtrs of 2x16 Sqmm Cable at Vivekanatha nagar, thiruvallur nagar, VV Giri street, Karunanathi Nagar, Indra Nagar and Various Locations in div 36 Zone IV.",Own Sources,4,2017-18,2019-20 L/2017-18/6819,Electrical,Completed,L-Electrical,36,976400,"Replacement of over head wires with 2700 Mtrs of 2x16 Sqmm Cable at West Avenue, Puthu Nagar, Sharma Nagar, Gandhi Nagar and SA Colony in div 36 Zone IV.",Own Sources,4,2017-18,2019-20 L/2017-18/8120,Electrical,Completed,L-Electrical,36,195800,"Replacement of Over Head wires with 580 mtrs of 2x16sqmm cable at Bharathi Nagar East, Karunanithi Nagar and various loactions in Div 36 Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/8121,Electrical,Completed,L-Electrical,36,194000,"Replacement of Over Head wires with 576 mtrs of 2x16sqmm cable at Gandhi Nagar, SA Colony and various loactions in Div 36 Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/0419,Parks,Completed,ND-TONDIARPET,36,325000,Maintanence of Park at M.K.B Nagar 14th West Cross Street Park and Sharmanagar 6th Street Park in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/0420,Parks,Completed,ND-TONDIARPET,36,189000,Maintanence of Park at Sharmanagar 1st main Road Park in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/0421,Parks,Completed,ND-TONDIARPET,36,430000,"Maintanence of Park at vasuki park,Bharathi park,M.R.nagar 5th cross park, in Dn-36 U-09 Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/0554,Parks,Completed,ND-TONDIARPET,36,2500000,"Construction of Compound wall, Sump and Improvements to Park at Sharma Nagar 1st main road in Div-36 Unit-9 Zone-4 (MLA fund)",MLACDS,4,2017-18,2018-19 ND/2017-18/0898,Buildings,Completed,ND-TONDIARPET,36,1467000,PROPOSED CONSTRUCTION RESOURCE RECOVERY CENTRES AT INDIRA NAGAR PARK EH ROAD IN DN-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/0900,Buildings,Completed,ND-TONDIARPET,36,900000,PROPOSED CONSTRUCTION RESOURCE RECOVERY CENTRES AT AMBEDKAR STREET SUZPUNALKARAI DN-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12868,Road Cut,Completed,ND-TONDIARPET,36,170000,Improvements work BT Road at T.V Nagar 15th Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12870,Road Cut,Completed,ND-TONDIARPET,36,219000,Improvements work BT Road at T.V Nagar 16th Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12872,Road Cut,Completed,ND-TONDIARPET,36,236000,Improvements work BT Road at T.V Nagar 17th Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12873,Road Cut,Completed,ND-TONDIARPET,36,170000,Improvements work BT Road at Kalasathaman koil street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12875,Road Cut,Completed,ND-TONDIARPET,36,746000,Improvements work BT Road at vasugi nagar 1st main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12881,Road Cut,Completed,ND-TONDIARPET,36,521000,Improvements work BT Road at vasugi nagar 2nd main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12884,Road Cut,Completed,ND-TONDIARPET,36,899000,Improvements work BT Road at V.V.Giri street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12885,Road Cut,Completed,ND-TONDIARPET,36,1330000,Improvements work BT Road at Thiruvalluvar nagar 1st main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/12886,Road Cut,Completed,ND-TONDIARPET,36,2075000,Improvements work BT Road at T.V.K.2nd link road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13050,Road Cut,Completed,ND-TONDIARPET,36,867000,Improvement to BT Road at M.R. 1st Main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13059,Road Cut,Completed,ND-TONDIARPET,36,1213000,Improvements work BT Road at M.R.Nagar 3rd Main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13195,Road Cut,Completed,ND-TONDIARPET,36,866000,Improvements work BT Road at Sanjay gandhi Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13196,Road Cut,Completed,ND-TONDIARPET,36,602000,Improvements work BT Road at Bharathidhasan Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13197,Road Cut,Completed,ND-TONDIARPET,36,647000,Improvements work BT Road at Viveakanandha 1st Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13198,Road Cut,Completed,ND-TONDIARPET,36,383000,Improvements work BT Road at Gandhi Street (V.V Nagar) in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13199,Road Cut,Completed,ND-TONDIARPET,36,623000,Improvements work BT Road at T.V.Nagar 7th Main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13200,Road Cut,Completed,ND-TONDIARPET,36,969000,Improvements work BT Road at T.V.Nagar 5th Main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13201,Road Cut,Completed,ND-TONDIARPET,36,1314000,Improvements work BT Road at T.V.Nagar 8th Main road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13202,Road Cut,Completed,ND-TONDIARPET,36,867000,Improvements work BT Road at Bharathiyar Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13203,Road Cut,Completed,ND-TONDIARPET,36,530000,Improvements work CC Road at Elango Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13204,Road Cut,Completed,ND-TONDIARPET,36,423000,Improvements work CC Road at Pudhu Nagar 7th Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13205,Road Cut,Completed,ND-TONDIARPET,36,706000,Improvements work CC Road at Pudhu Nagar 8th Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/13207,Road Cut,Completed,ND-TONDIARPET,36,1024000,Improvements to CC Road at Rajiv Gandhi Nagar Main Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/1369,Buildings,Completed,ND-TONDIARPET,36,280000,Repairs and Improvement Work Amma Unavagam at Suzhl Punal Karai & Sastri Nagar in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/15553,Buildings,Completed,ND-TONDIARPET,36,389000,"Repairs and Improvements Work GYM at Vasugi nagar 1st street in Dn-36,U-09, Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2497,Buildings,Completed,ND-TONDIARPET,36,130000,Improvement to Dispensary at Apper Street & SA Colony 8th Street in Dn-36,Own Sources,4,2017-18,2017-18 ND/2017-18/8271,Storm Water Drain,Completed,ND-TONDIARPET,36,300000,"SWD Repair Works At T.v.k 1st link road extn, T.v nagar 1st street junction of viveakanada 2nd street, T.v Nagar 12th Main Road, Ethiraj Samy Salai, Sharma nagar 1st main Main road ,T.v.k 2nd link Road and Rajiv Gandhi Nagar 19th West Cross Street in Dn-36 U-09 Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/8508,Storm Water Drain,Completed,ND-TONDIARPET,36,60000,Desilting of SWD at Sanjay Gandhi Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8510,Storm Water Drain,Completed,ND-TONDIARPET,36,240000,Desilting of SWD at Ethiraj Samy Salai in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8511,Storm Water Drain,Completed,ND-TONDIARPET,36,125000,Desilting of SWD at MR Nagar 3rd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8512,Storm Water Drain,Completed,ND-TONDIARPET,36,120000,Desilting of SWD at Nakeeren Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8514,Storm Water Drain,Completed,ND-TONDIARPET,36,240000,Desilting of SWD at Sidco Main Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8516,Storm Water Drain,Completed,ND-TONDIARPET,36,130000,Desilting of SWD at T.V Nagar 5th Main Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8517,Storm Water Drain,Completed,ND-TONDIARPET,36,140000,Desilting of SWD at Sharmanagar 2nd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8519,Storm Water Drain,Completed,ND-TONDIARPET,36,192000,Desilting of SWD at Sharmanagar 9th Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8522,Storm Water Drain,Completed,ND-TONDIARPET,36,340000,Desilting of SWD at T.v.k 2nd Link Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8523,Storm Water Drain,Completed,ND-TONDIARPET,36,182000,Desilting of SWD at Viveakanada Nagar 2nd Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8525,Storm Water Drain,Completed,ND-TONDIARPET,36,110000,Desilting of SWD at Kalamegam Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8527,Storm Water Drain,Completed,ND-TONDIARPET,36,190000,Desilting of SWD at T.V Nagar 1st Main Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8529,Storm Water Drain,Completed,ND-TONDIARPET,36,120000,Desilting of SWD at Anna Salai Sastri Nagar (E) in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8530,Storm Water Drain,Completed,ND-TONDIARPET,36,140000,Desilting of SWD at SA Colony 7th Street to 10th Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8531,Storm Water Drain,Completed,ND-TONDIARPET,36,170000,Desilting of SWD at Sharmanagr 1st main Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8533,Storm Water Drain,Completed,ND-TONDIARPET,36,310000,Desilting of SWD at West Avenue Road (E) in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8534,Storm Water Drain,Completed,ND-TONDIARPET,36,310000,Desilting of SWD at West Avenue Road (W) in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8535,Storm Water Drain,Completed,ND-TONDIARPET,36,200000,Desilting of SWD at West Avenue 2nd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/8536,Storm Water Drain,Completed,ND-TONDIARPET,36,140000,Desilting of SWD at Bharathiyar Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2017-18 ND/2017-18/9729,Roads,Completed,ND-TONDIARPET,36,1028000,Relaying CC Roads at SA Colony Karimedu 2nd Cross Street & Maraimalai Adigal Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/9731,Roads,Completed,ND-TONDIARPET,36,715000,Relaying CC Roads at SA Colony Karimedu 2nd Street 2nd Cross Lane & SA Colony 7th Street 3rd Cross lane in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/9732,Roads,Completed,ND-TONDIARPET,36,1037000,Relaying CC Roads at SA Colony Karimedu 1st Street & SA Colony Karimedu 1st Street 1st cross lane in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/9734,Roads,Completed,ND-TONDIARPET,36,1951000,Relaying CC Roads at SA Colony Karimedu 2nd Street & Papathiamman Koil Street in Dn-36 U-09 Z-04,Own Sources,4,2017-18,2018-19 ND/2017-18/9782,Buildings,Completed,ND-TONDIARPET,36,200000,"Providing Portable Toilets 4 Nos with Water Tank 2000lt on Rental basis and Maintenance for 3 Months at Sidco Nagar Main Road Opp to Vasuki Park, in Dn-36, Unit-9, Zone IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/9783,Buildings,Completed,ND-TONDIARPET,36,810000,"Providing Portable Toilets 4 Nos with Water Tank 2000lt on Rental basis and Maintenance for one year at Sidco Nagar Main Road Opp to Vasuki Park, in Dn-36, Unit-9, Zone IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/9996,Roads,Completed,ND-TONDIARPET,36,109000,Relaying of Bituminous Concrete Road by Paver finisher at Meenambal Service Road in Div-36 Unit-9 Zone-IV,Own Sources,4,2017-18,2017-18 ND/2017-18/0254,Buildings,Completed,ND-TONDIARPET,37,979000,Construction of New Resource recovery center at Mullai nagar burial ground in div-37 Uni-9 Zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/0255,Buildings,Completed,ND-TONDIARPET,37,996000,Construction of new Resource recovery center at North Avenue road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2018-19 ND/2017-18/0849,Buildings,Completed,ND-TONDIARPET,37,495000,"Construction of Well Type Compost Yard at 6th main road,7th block ,9th main road Muthamil nagar, GNT road in div-35 unit-9 Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/12973,Roads,Completed,ND-TONDIARPET,37,1126000,"IMPROVEMENTS WORK BT ROAD AT M.K.B NAGAR 7TH MAIN ROAD IN DIV-37, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12974,Roads,Completed,ND-TONDIARPET,37,623000,"IMPROVEMENTS WORK BT ROAD AT PALANI STREET IN DIV-37, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12976,Roads,Completed,ND-TONDIARPET,37,521000,"IMPROVEMENTS WORK BT ROAD AT GANAPATHY STREET IN DIV-37, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12977,Roads,Completed,ND-TONDIARPET,37,1245000,"IMPROVEMENTS WORK BT ROAD AT M.K.B NAGAR 2nd MAIN ROAD IN DIV-37, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12978,Roads,Completed,ND-TONDIARPET,37,1245000,"IMPROVEMENTS WORK BT ROAD AT M.K.B NAGAR 3rd MAIN ROAD IN DIV-37, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12979,Roads,Completed,ND-TONDIARPET,37,1245000,"IMPROVEMENTS WORK BT ROAD AT M.K.B NAGAR 4TH MAIN ROAD IN DIV-37, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12980,Roads,Completed,ND-TONDIARPET,37,692000,"IMPROVEMENTS WORK BT ROAD AT M.K.B NAGAR 5TH CROSS (UDAYA SURIYAN NAGAR) IN DIV-37, UNIT-09, ZONE-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/1751,Buildings,Completed,ND-TONDIARPET,37,59500,Repair works to Health Post at MKB nagar 14th East Cross street in div 37 Unit-9 Zone-IV,Own Sources,4,2017-18,2018-19 ND/2017-18/2456,Buildings,Completed,ND-TONDIARPET,37,789000,"Improvements to NNMP shed at JJ nagar Main Road, Udhayasuriyan Nagar,RR Nagar,MGR Nagar, KKD nagar 7th block & KKD nagar 8th block in Div-37 Unit-9 Zone-IV",Own Sources,4,2017-18,2018-19 ND/2017-18/7262,Parks,Completed,ND-TONDIARPET,37,346000,"OUTSOURCING MAINTENANCE OF PARK LOCATED AT MULLAI NAGAR BURIGAL GROUND IN DIVISION-37,UNIT-9, ZONE-4.(FOR ONE YEAR)",Own Sources,4,2017-18,2019-20 ND/2017-18/8616,Storm Water Drain,Completed,ND-TONDIARPET,37,45000,Desilting the Storm water drain at Abirami avenue 14th street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8617,Storm Water Drain,Completed,ND-TONDIARPET,37,153000,Desilting the Storm water drain at Manali salai in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8618,Storm Water Drain,Completed,ND-TONDIARPET,37,234000,Desilting the Storm water drain at MKB nagar 4th Cross street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8619,Storm Water Drain,Completed,ND-TONDIARPET,37,386000,Desilting the Storm water drain at JJ nagar Main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8620,Storm Water Drain,Completed,ND-TONDIARPET,37,145000,Desilting the Storm water drain at central avenue road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8621,Storm Water Drain,Completed,ND-TONDIARPET,37,21000,Desilting the Storm water drain at TH road 1st lane in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8622,Storm Water Drain,Completed,ND-TONDIARPET,37,304000,Desilting the Storm water drain at Meenambaal salai in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8623,Storm Water Drain,Completed,ND-TONDIARPET,37,166000,Desilting the Storm water drain at MKB nagar 1st main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8624,Storm Water Drain,Completed,ND-TONDIARPET,37,62000,Desilting the Storm water drain at MKB nagar 4th main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8625,Storm Water Drain,Completed,ND-TONDIARPET,37,81000,Desilting the Storm water drain at MKB nagar 3rd main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8626,Storm Water Drain,Completed,ND-TONDIARPET,37,209000,Desilting the Storm water drain at MKB nagar 2nd main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8627,Storm Water Drain,Completed,ND-TONDIARPET,37,90000,Desilting the Storm water drain at Bhavani amman koil street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8628,Storm Water Drain,Completed,ND-TONDIARPET,37,23000,Desilting the Storm water drain at Palani street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8629,Storm Water Drain,Completed,ND-TONDIARPET,37,143000,Desilting the Storm water drain at Srinivasan street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8630,Storm Water Drain,Completed,ND-TONDIARPET,37,163000,Desilting the Storm water drain at Ramakrishnan street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8631,Storm Water Drain,Completed,ND-TONDIARPET,37,143000,Desilting the Storm water drain at Pathmavathy street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8632,Storm Water Drain,Completed,ND-TONDIARPET,37,175000,Desilting the Storm water drain at Balakrishnan street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8633,Storm Water Drain,Completed,ND-TONDIARPET,37,73000,Desilting the Storm water drain at Good shed road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8634,Storm Water Drain,Completed,ND-TONDIARPET,37,680000,Desilting the Storm water drain at Damodhar 1st street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8635,Storm Water Drain,Completed,ND-TONDIARPET,37,17000,Desilting the Storm water drain at RR nagar 6th lane in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8636,Storm Water Drain,Completed,ND-TONDIARPET,37,17000,Desilting the Storm water drain at RR nagar 2nd main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8637,Storm Water Drain,Completed,ND-TONDIARPET,37,77000,Desilting the Storm water drain at RR nagar 4th main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8638,Storm Water Drain,Completed,ND-TONDIARPET,37,27000,Desilting the Storm water drain at RR nagar 3rd main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8639,Storm Water Drain,Completed,ND-TONDIARPET,37,182000,Desilting the Storm water drain at TVK 2nd link road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8640,Storm Water Drain,Completed,ND-TONDIARPET,37,20000,Desilting the Storm water drain at MKB Nagar Service Road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8641,Storm Water Drain,Completed,ND-TONDIARPET,37,68000,Desilting the Storm water drain at MKB nagar North Avenue Road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8642,Storm Water Drain,Completed,ND-TONDIARPET,37,148000,Desilting the Storm water drain at MKB Nagar 5th main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8643,Storm Water Drain,Completed,ND-TONDIARPET,37,108000,Desilting the Storm water drain at MKB nagar 5th cross street in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8644,Storm Water Drain,Completed,ND-TONDIARPET,37,260000,Desilting the Storm water drain at MKB nagar 6th main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/8645,Storm Water Drain,Completed,ND-TONDIARPET,37,658000,Desilting the Storm water drain at SM Nagar Main road in div-37 Unit-9 Zone-4,Own Sources,4,2017-18,2017-18 ND/2017-18/9735,Storm Water Drain,Completed,ND-TONDIARPET,37,203000,"Providing Portable Toilets 4 Nos with Water Tank 2000lt on Rental basis and maintenance for three months at Sathya Moorthy Nagar Main Road, Mullai Nagar Bus Depot, in Dn-37 Unit-9, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/9736,Storm Water Drain,Completed,ND-TONDIARPET,37,203000,"Providing Portable Toilets 4 Nos For Women with Water Tank 2000lt on Rental basis and maintenance for three months at Good Shed Road, Vyasarpadi, in Dn-37 Unit-09, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/9737,Storm Water Drain,Completed,ND-TONDIARPET,37,203000,"Providing Portable Toilets 4 Nos For Men with Water Tank 2000lt on Rental basis and maintenance for three months at Good Shed Road, Vyasarpadi, in Dn-37 Unit-9, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/9744,Buildings,Completed,ND-TONDIARPET,37,812000,"Providing Portable Toilets 4 Nos with Water Tank 2000lt on Rental basis and maintenance for one year at Sathya Moorthy Nagar Main Road, Mullai Nagar Bus Depot, in Dn-37 Unit-9, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/9746,Buildings,Completed,ND-TONDIARPET,37,1617000,"Providing Portable Toilets 4 Nos For Women and 4 Nos for Men with Water Tank 2000lt on Rental basis and maintenance for one year at Good Shed Road, Vyasarpadi, in Dn-37 Unit-09, Zone IV",Own Sources,4,2017-18,2018-19 Q/2017-18/13640,Buildings,Completed,Q-Solid Waste Management,37,4950000,"Proposed construction of Additional Weigh Bridge & Monitoring at Main entrance of Corporation road inside Kodungaiyur Dumping Ground in Dn-34, Z-4.",Own Sources,4,2017-18,2019-20 Q/2017-18/15527,Buildings,Completed,Q-Solid Waste Management,37,9840000,"CONSTRUCTION OF COMPOUND WALL AT EASTERN SIDE OF KODUNGAIYUR DUMPING GROUND AT DN-37, ZONE-4",Own Sources,4,2017-18,2019-20 Q/2017-18/15949,Buildings,Completed,Q-Solid Waste Management,37,9840000,"Construction of Compound wall at Northern side of Kodungaiyur Dumping Ground in Div 37, U-9, Z-4",Own Sources,4,2017-18,2020-21 Q/2017-18/16283,Buildings,Completed,Q-Solid Waste Management,37,4880000,"Construction of Compound wall across canal portion at Kodungaiyur Dumping Ground in Div 37, U-9, Z-4",Own Sources,4,2017-18,2020-21 Q/2017-18/16930,Buildings,Completed,Q-Solid Waste Management,37,208000,"Supplying and fixing street name boards using Stainless Steel pipes and Retro Reflective sheets at various locations inside Kodungaiyur dumping Ground in Dn-37, U-9, z-4",Own Sources,4,2017-18,2018-19 Q/2017-18/16932,Buildings,Completed,Q-Solid Waste Management,37,886000,"Supplying and fixing RCC Hume pipes across various roads inside Kodungaiyur Dumping ground in Dn-37, U-9, Z-4",Own Sources,4,2017-18,2018-19 Q/2017-18/9723,Buildings,Completed,Q-Solid Waste Management,37,9800000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT ATHIPATTU TRANSFER STATION AT DIV-86, Z-7",Own Sources,4,2017-18,2019-20 B/2017-18/15570,Buildings,Completed,B-Buildings,38,887000,"Supplying and fixing of Two seater bench cum tables for propsed smart classes in CHSS Patel nagar in DN 38 Zone 4, CHSS T.H road in DN 39 Zone 4, CHSS Buddha street in DN 42 Zone 4 and CHSS Kalyanapuram in DN 46 Zone 4",Own Sources,4,2017-18,2018-19 BR/2017-18/4193,Roads,Completed,BR-Bus Route Roads,38,681000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 4 - For the challan no-B.R.R.C.NO.B4/0422/2016,Deposit Works,4,2017-18,2018-19 BR/2017-18/4194,Roads,Completed,BR-Bus Route Roads,38,681000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 4 - For the challan no-B.R.R.C.NO.B4/0422/2016,Deposit Works,4,2017-18,2018-19 BR/2017-18/4195,Roads,Completed,BR-Bus Route Roads,38,657000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 4 - For the challan no-B.R.R.C.NO.B4/0551/2017,Deposit Works,4,2017-18,2018-19 BR/2017-18/4197,Roads,Completed,BR-Bus Route Roads,38,657000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 4 - For the challan no-B.R.R.C.NO.B4/0551/2017,Deposit Works,4,2017-18,2018-19 L/2017-18/9669,Electrical,Completed,L-Electrical,38,997900,"Provision of 8 Nos.of 8 Mtr Long Octagonal Mini Highmast Light with hexagonal lantern carriage with 3 Nos. of 70W-100W LED Flood Light Fitting at Various Locations in Dn:38,39,40 & 43, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/0928,Buildings,Completed,ND-TONDIARPET,38,236000,"Construction of Well Type Compost Yard at Sastri Nagar Main Road and Nehru Nagar 14th Street in Dn-38, Unit-9, Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10362,Buildings,Completed,ND-TONDIARPET,38,40000,"Repair Work to Toilet Block at CHSS, Patel Nagar 4th Street in Dn-38, Unit-9, Zone-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10444,Buildings,Completed,ND-TONDIARPET,38,300000,"Improvements to Gym Building inside Patel Nagar Park in Dn-38, Unit-9, Zone-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10482,Roads,Completed,ND-TONDIARPET,38,1522000,"Restoration of Roadcut at Nethaji Nagar 4th street(B.T.Road) in Dn-38,U-09,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10483,Roads,Completed,ND-TONDIARPET,38,1304000,"Restoration of Roadcut at Sanjay Gandhi Nagar Main Road(B.T.Road) in Dn-38,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10484,Roads,Completed,ND-TONDIARPET,38,1109000,"Relaying B.T.Road at Navalar Nagar A Street in Dn-38, Unit-9, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/10544,Buildings,Completed,ND-TONDIARPET,38,300000,"Improvements to Gym Building at Annai Sandhya Nagar Main Road in Dn-38, Unit-9, Zone-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10558,Parks,Completed,ND-TONDIARPET,38,25000,"Improvements to Park at Ellaya Street in Dn-38, Unit-09, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/10559,Parks,Completed,ND-TONDIARPET,38,15000,"Improvements to Park at Patel Nagar 4th Street in Dn-38, Unit-09, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/10560,Parks,Completed,ND-TONDIARPET,38,7000,"Improvements to Park at Nehru Nagar Main Road in Dn-38, Unit-09, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/15522,Buildings,Completed,ND-TONDIARPET,38,914000,"Construction of Secondary Source Segregation Centre And Additional Construction of Compost Unit inside Exisiting Compost Yard at Ennore High Road near ECI School in Dn-38, Unit-9, Zone-4.",Own Sources,4,2017-18,2019-20 ND/2017-18/4897,Buildings,Completed,ND-TONDIARPET,38,198000,"Maintenance of Amma Unavagam Phase-1 at New Vinobha Nagar in Dn-38, Unit-9, Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/5323,Playfields,Completed,ND-TONDIARPET,38,197000,"Maintenance of Play Field at Anna Street (Nedunchezhian Nagar) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/5336,Buildings,Completed,ND-TONDIARPET,38,159000,"Improvements to Anganwadi Center No :12112 at Nethaji Nagar 6th Street in Dn-38, Unit-9, Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8662,Storm Water Drain,Completed,ND-TONDIARPET,38,105000,"Desilting of Storm water Drain at Ellaya Street(From Vaidhyanathan bridge to Mannappan Street) in Dn.38, Unit-9, Zone - 4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8667,Storm Water Drain,Completed,ND-TONDIARPET,38,62000,"Desilting of Storm water Drain at Ennore High Road (From E.C.I School to Nehru Nagar Railway Track) in Dn.38, Unit-9, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8671,Storm Water Drain,Completed,ND-TONDIARPET,38,27000,"Desilting of Storm water Drain at Sundaram Nagar 5th Main Road in Dn.38, Unit-9, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8673,Storm Water Drain,Completed,ND-TONDIARPET,38,42000,"Desilting of Storm water Drain at Vaidhyanathan Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/9120,Storm Water Drain,Completed,ND-TONDIARPET,38,660000,"Desilting of Canal at Ennore High Road (From Jn of E.C.I School to Jn of Lube Plant Road & Near P.C) in Dn-38, Unit-9, Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/9126,Storm Water Drain,Completed,ND-TONDIARPET,38,170000,"Cost & Supply of FRC Manhole Doors to Various Roads in Dn-38, Unit-9, Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/9239,Buildings,Completed,B-Buildings,38,74000,"Painting and Other Improvement Works for Smart Class Room at CHSS (Northern Side) at Patel Nagar 4th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9658,Buildings,Completed,ND-TONDIARPET,38,1244000,"Providing Portable Toilets 6 Nos For Men and Women with Water Tank 2000lt on Rental basis and maintenance for one year at Vaidhyanathan Street end (Near Tondiarpet Railway Station) in Dn-38, Unit-9, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/9717,Buildings,Completed,ND-TONDIARPET,38,155000,"Providing Portable Toilets 3 Nos For Men with Water Tank 2000lt on Rental basis and maintenance for 3 months at Vaidhyanathan Street end (Near Tondiarpet Railway Station) in Dn-38, Unit-9, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/9719,Buildings,Completed,ND-TONDIARPET,38,155000,"Providing Portable Toilets 3 Nos For Women with Water Tank 2000lt on Rental basis and maintenance for 3 months at Vaidhyanathan Street end (Near Tondiarpet Railway Station) in Dn-38, Unit-9, Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/0706,Electrical,Completed,L-Electrical,39,299600,"Removal and Re-erection of 20 Mtr Highmast, Removal of 58 Nos. of 8 Mtr G.I Octagonal Lamp Post with 150W-165W LED Fittings at Thiruvottiyur High Road ( From Lakshimi Koil to Tolgate) in Dn:39, Zone IV",Deposit Works,4,2017-18,2019-20 L/2017-18/10255,Electrical,Completed,L-Electrical,39,475800,"Provision of 4 Nos of 8 Mtr Octagonal Mini Highmast Light with Hexagonal Lantern Carriage with 3 Nos. of 70W-100W LED Flood Light Fitting at Various Location in Dn:39, Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/10353,Electrical,Completed,L-Electrical,39,1314800,"Provision of Electrification at Smart Class Wiring Proposed for CMS School, Chinnnandhi Madam in Dn:35, CHSS School, Patel Nagar in Dn:38, CHSS School No.731, T.H Road in Dn:39, CHSS School, Buddha Street in Dn:42, CMS, Pudumanaikuppam in Dn:43, CHSS School, Kalyanapuram in Dn46 in Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/10637,Electrical,Completed,L-Electrical,39,198800,Erection of 14 Nos.Old lamp posts and laying of 2x16 sq.mm cable for the provision of temporary lightings at CMRL work site in Tiruvottriyur High Road ( From A.E Koil St to Vasar Varadappan St) Easrtern and Western side stretch in Dn. 39 Zone-IV.,Deposit Works,4,2017-18,2019-20 ND/2017-18/0941,Buildings,Completed,ND-TONDIARPET,39,236000,"Construction of Well Type Compost Yard at A.E Koil Street near Amma Kudineer in Dn-39, Unit-10, Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10019,Buildings,Completed,ND-TONDIARPET,39,148000,"Repairs and Maintainance at CHHSS, No:731 T.H.road in Dn-39,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10499,Roads,Completed,ND-TONDIARPET,39,1013000,"Relaying the road at Nammaiya maistry street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10501,Roads,Completed,ND-TONDIARPET,39,1757000,"Restoration of Roadcut made by CMWSSB,streanthing and relaying the road at Avoor muthaiya street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10502,Roads,Completed,ND-TONDIARPET,39,1857000,"Restoration of Roadcut made by CMWSSB,streanthing and relaying the road at Washer varadappa street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10503,Roads,Completed,ND-TONDIARPET,39,2437000,"Restoration of Roadcut made by CMWSSB,streanthing and relaying the road at Butchammal street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10504,Roads,Completed,ND-TONDIARPET,39,1657000,"Restoration of Roadcut made by CMWSSB,streanthing and relaying the road at Poondi thangammal street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10506,Roads,Completed,ND-TONDIARPET,39,414000,"Relaying the damaged road at Govindharaj street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10507,Roads,Completed,ND-TONDIARPET,39,2153000,"Relaying the damaged Road at Kannu street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10508,Roads,Completed,ND-TONDIARPET,39,693000,"Restoration of Roadcut made by CMWSSB,streanthing and relaying the road at Sudalai muthu street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10576,Buildings,Completed,ND-TONDIARPET,39,240000,"Improvements to Dhobikanna at Butchammal Street in Dn-39, Unit-10, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/10577,Buildings,Completed,ND-TONDIARPET,39,125000,"Improvements to Dhobikanna at Irusappa Street in Dn-39, Unit-10, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/10579,Buildings,Completed,ND-TONDIARPET,39,90000,"Improvements to Gym at Poondi Thangammal Street in Dn-39, Unit-10, Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10580,Buildings,Completed,ND-TONDIARPET,39,25000,"Improvements to P.C at S.N.Chetty Street in Dn-39, Unit-10, Zone-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10581,Buildings,Completed,ND-TONDIARPET,39,25000,"Improvements to P.C at A.E.Koil Street in Dn-39, Unit-10, Zone-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11453,Roads,Completed,ND-TONDIARPET,39,2421000,"Restoration of roadcut made by CMSSB,and relaying the road at Desiya nagar,Ashok nagar 4th street,cheriyan nagar 4th street in dn-39 un-10,z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/11459,Roads,Completed,ND-TONDIARPET,39,1384000,"Restoration of roadcut made by CMSSB,and relaying the road at Cheriyan nagar 2nd street in dn-39 un-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11460,Roads,Completed,ND-TONDIARPET,39,1384000,"Restoration of roadcut made by CMSSB,and relaying the road at Cheriyan nagar 3rd street in dn-39 unit-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11461,Roads,Completed,ND-TONDIARPET,39,692000,"Restoration of roadcut made by CMSSB,and relaying the road at Ashok nagar 2nd street in dn-39 unit-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11463,Roads,Completed,ND-TONDIARPET,39,692000,"Restoration of roadcut made by CMSSB,and relaying the road at Ashok nagar 3rd street in dn-39 unit-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11466,Roads,Completed,ND-TONDIARPET,39,346000,"Restoration of roadcut made by CMSSB,and relaying the road at Dhanapal nagar 1st street in dn-39 unit-10,z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11468,Roads,Completed,ND-TONDIARPET,39,346000,"Restoration of roadcut made by CMSSB,and relaying the road at Dhanapal nagar 2nd street in dn-39 unit-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11469,Roads,Completed,ND-TONDIARPET,39,346000,"Restoration of roadcut made by CMSSB,and relaying the road at Dhanapal nagar 3rd street in dn-39 unit-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11470,Roads,Completed,ND-TONDIARPET,39,865000,"Restoration of roadcut made by CMSSB,and relaying the road at Irusappa maistry street in dn-39 unit-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11471,Roads,Completed,ND-TONDIARPET,39,692000,"Restoration of roadcut made by CMSSB,and relaying the road at Irusappa maistry 2nd street in dn-39 unit-10,zn-4",Own Sources,4,2017-18,2018-19 ND/2017-18/11472,Roads,Completed,ND-TONDIARPET,39,346000,"Restoration of roadcut made by CMSSB,and relaying the road at Market form 1 to 7 street in dn-39 unit-10,z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/15548,Buildings,Completed,ND-TONDIARPET,39,276000,"Formation of Source Segregation Centre at S.N. Chetty Street near PC in Dn-39,Unit-10, Zone-4.",Own Sources,4,2017-18,2019-20 ND/2017-18/2617,Buildings,Completed,ND-TONDIARPET,39,97000,"Repairs and Maintenance to NNMP Shed (Centre No:101) at Dhanapal Nagar 3rd Street in Dn-39,U-10,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/6156,Buildings,Completed,ND-TONDIARPET,39,93000,"Improvement Work to Amma Unavagam at Kannu Street in Dn-39, U-10, Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/6160,Buildings,Completed,ND-TONDIARPET,39,82000,"Improvement Work to Amma Unavagam at Washer Varadappa Street in Dn-39, U-10, Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/6196,Buildings,Completed,ND-TONDIARPET,39,371000,"Improvements to Health Post at Cheriyan Nagar 4th Street in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/6479,Buildings,Completed,ND-TONDIARPET,39,72000,"Repair and Maintenance to ICDS at Cheriyan Nagar( Centre No:105,107,108,111) in Dn-39,U-10,Z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/6790,Buildings,Completed,ND-TONDIARPET,39,55000,"Repair and Maintenance to ICDS AE Koil Street and Chennai School West and East at in Dn-39,U-10,Z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/6793,Buildings,Completed,ND-TONDIARPET,39,72000,"Repair and Maintenance to ICDS Irusappan Maistry St,ButchammalSt,Poondithangammal St and Nagooran thottam at in Dn-39,U-10,Z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/6978,Buildings,Completed,ND-TONDIARPET,39,110000,"Improvements to CPS at 731 T.H.Road in Dn-39,U-10,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8648,Storm Water Drain,Completed,ND-TONDIARPET,39,51000,"Desilting of Storm water Drain at Arunachala Easwarar Koil Street in Dn.39, Unit-10, Zone - 4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8651,Storm Water Drain,Completed,ND-TONDIARPET,39,17000,"Desilting of Storm water Drain at Q.Q.Scheme Road (Alias) T.H Road 6th Lane in Dn.39, Unit-10, Zone - 4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8653,Storm Water Drain,Completed,ND-TONDIARPET,39,83000,"Desilting of Storm water Drain at Thiruyottiyur High Road (West) in Dn.39, Unit-10, Zone - 4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8658,Storm Water Drain,Completed,ND-TONDIARPET,39,96000,"Desilting of Storm water Drain at North Terminous Road in Dn.39, Unit-10, Zone - 4.",Own Sources,4,2017-18,2017-18 ND/2017-18/8669,Storm Water Drain,Completed,ND-TONDIARPET,39,27000,"Desilting of Storm water Drain at Sundaram Nagar 2nd Main Road in Dn.38, Unit-9, Zone-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/9246,Buildings,Completed,B-Buildings,39,126800,"Painting work for Smartclass room at CHSS(No:731 T.H.Road) in Dn-39, Unit-10, Zone-4.",Own Sources,4,2017-18,2018-19 L/2017-18/9665,Electrical,Completed,L-Electrical,40,338300,"Provision of 4 Nos of 6 Mtr G.I Lamp Post with 4 Way bracket with 40W LED Fittings at Thiruvalluvar Nagar Park in Dn:40, Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/9670,Electrical,Completed,L-Electrical,40,989300,"Provision of 8 Nos. of 8 Mtr Long Octagonal Lamp MIni Highmast Light with hexagonal lantern carriage with 3 Nos. of 70W-100w LED Flood Light Fitting at Various Locations in Dn:40 &43, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/0958,Buildings,Completed,ND-TONDIARPET,40,236000,"Construction of Well Type Compost Yard at Thiruvalluvar Quarters in Dn-40, Unit-10, Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10494,Roads,Completed,ND-TONDIARPET,40,2352000,"Relaying of B.T Road at Madha Koil Street and Karumaariamman koil Street in Dn-40,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10495,Roads,Completed,ND-TONDIARPET,40,2444000,"Relaying of B.T Road at VOC Nagar 1st Main Road in Dn-40,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10526,Roads,Completed,ND-TONDIARPET,40,1270000,"Restoration of roadcut at Ammaniammal thottam 3rd& 8th street (C.C Road) in Dn-40,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10552,Buildings,Completed,ND-TONDIARPET,40,25000,"Improvement works to P.C at Ammaniammal thottam (Seniamman Koil) in Division-40, Unit-10, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/10554,Buildings,Completed,ND-TONDIARPET,40,25000,"Improvement works to P.C at Jeeva Nagar in Division-40, Unit-10, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/10556,Buildings,Completed,ND-TONDIARPET,40,178000,"Improvements to NNMP Shed located at Seniamman koil 4th Street in Division-40, Unit-10, Zone-IV.",Own Sources,4,2017-18,2018-19 ND/2017-18/10561,Buildings,Completed,ND-TONDIARPET,40,70000,"Improvement works to NNMP Shed located at VOC nagar south street (Seniamman koil st) in Division-40, Unit-10, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/10565,Playfields,Completed,ND-TONDIARPET,40,200000,"Improvement works to Chelliamman Koil Street play area in Division-40, Unit-10, Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10570,Parks,Completed,ND-TONDIARPET,40,100000,"Improvement to Periyar Park at A.E Koil Street in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10571,Parks,Completed,ND-TONDIARPET,40,95000,"Improvement to Thiruvalluvar Park at Thiruvalluvar Quarters in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10572,Parks,Completed,ND-TONDIARPET,40,50000,"Improvement toElaya Park at Elaya Street in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/13611,Roads,Completed,ND-TONDIARPET,40,271000,"Attending patch work at kamaraj salai in Division-40, Unit-10, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/13612,Roads,Completed,ND-TONDIARPET,40,657000,"Attending patch work at Seniamman Koil Street in Division-40, Unit-10, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/16507,Buildings,Completed,ND-TONDIARPET,40,990000,"Improvements to various corporation buildings at various places in Div - 40, Unit - 10, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/16508,Buildings,Completed,ND-TONDIARPET,40,738000,"Improvements to the Periyar Park at AE Koil Street in Dn-40,Unit-10,Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/16510,Parks,Completed,ND-TONDIARPET,40,172000,"Improvements to the Thiruvalluvar Park at Thiruvalluvar Quarters in Dn-40,Unit-10,Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/16512,Parks,Completed,ND-TONDIARPET,40,210000,"Improvements to the Elaya Park at Elaya Street in Dn-40,Unit-10,Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/16513,Buildings,Completed,ND-TONDIARPET,40,390000,"Improvements to the Childrens Play Area at Thiruvalluvar Quarters in Dn-40,Unit-10,Zone-04",Own Sources,4,2017-18,2019-20 ND/2017-18/16723,Buildings,Completed,ND-TONDIARPET,40,604600,"Construction of Sump & pump Room at Thiruvalluvar Quarters play park in Dn-40,Unit-10,Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/1777,Buildings,Completed,ND-TONDIARPET,40,448000,"Improvements to Health Post at Chelliamman Koil Street in Dn-40,U-10,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/2489,Buildings,Completed,ND-TONDIARPET,40,178000,"Repairs and Maintenance to NNMP Shed (Center No-405) at Ammaniammal Thottam in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/2490,Buildings,Completed,ND-TONDIARPET,40,138000,"Repairs and Maintenanace work NNMP Shed (Center No-406) at Ammaniammal Thottam in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/2491,Buildings,Completed,ND-TONDIARPET,40,134000,"Repairs and Maintenanace work NNMP Shed (Center No-408) at Ammaniammal Thottam in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5546,Buildings,Completed,ND-TONDIARPET,40,321000,"Improvements to Kamarajar Press Quarters CMS at Kamarajar Salai in Dn-40,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/5674,Buildings,Completed,ND-TONDIARPET,40,78000,"Improvement to CPS at Thiruvalluvar Salai in Dn-40,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/5716,Buildings,Completed,ND-TONDIARPET,40,115000,"Improvements to the Division Office at AA Scheme Road in Dn-40,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5737,Buildings,Completed,ND-TONDIARPET,40,189000,"Improvements to the Amma Unavagam at Mangammal Thottam (Phase-1) in Dn-40,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/5761,Buildings,Completed,ND-TONDIARPET,40,327000,"Improvement to the Amma Unavagam (Phase -2) at Keerai Thottam in Dn-40,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/6122,Storm Water Drain,Completed,ND-TONDIARPET,40,76000,"Desilting and Other Improvement Works to Ext.SWD at TH Road in Dn-40,U-10, Z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/6125,Storm Water Drain,Completed,ND-TONDIARPET,40,46000,"Desilting and Other Improvement Works to Ext. SWD at VOC Nagar Main Road in Dn-40,U-10,Z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/6820,Buildings,Completed,ND-TONDIARPET,40,460000,"Improvement Works to NNMP Shed (No:403)at Press Quarters at Kamaraj Salai in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/6832,Buildings,Completed,ND-TONDIARPET,40,350000,"Improvement Works to NNMP Shed (No:403)at Press Quarters at Kamaraj Salai in Dn-40,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/7130,Storm Water Drain,Completed,ND-TONDIARPET,40,50000,"Desilting and Other Improvement Works to Ext.SWD At AE Koil Street in Dn-40,U-10,Z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/7135,Storm Water Drain,Completed,ND-TONDIARPET,40,203000,"Providing Portable Toilets 4 Nos For women with Water Tank 2000 ltr on Rental basis and maintenance for 3 month at Elaya Street in Dn-40, Unit-10, Zone -04",Own Sources,4,2017-18,2018-19 ND/2017-18/7136,Storm Water Drain,Completed,ND-TONDIARPET,40,203000,"Providing Portable Toilets 4 Nos For men with Water Tank 2000 ltr on Rental basis and maintenance for 3 month at Elaya Street in Dn-40, Unit-10, Zone -04",Own Sources,4,2017-18,2018-19 ND/2017-18/9939,Buildings,Completed,ND-TONDIARPET,40,1625500,"Providing Portable Toilets 4+4 Nos For men and Women with Water Tank 2000 ltr on Rental basis and maintenance for 1year Elaya Street in Dn-40, Unit-10, Zone -04",Own Sources,4,2017-18,2018-19 D/2017-18/9068,Storm Water Drain,Completed,D-Storm Water Drains,41,1140000,Demolition of parapet wall and replacing with M.S Grill gate for de-silting in canals using Robatic multi purpose excavator in various places in North region.,Own Sources,4,2017-18,2018-19 ND/2017-18/0970,Buildings,Completed,ND-TONDIARPET,41,157000,"Construction of well type compost yard at Lime Kiln Road (Thiruvalluvar Nagar ) in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/10445,Buildings,Completed,ND-TONDIARPET,41,120000,"Improvements to Chennai Corporation Primary School located at J.J Nagar 'B' Street in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/10469,Roads,Completed,ND-TONDIARPET,41,1529000,"Restoration of Roadcut at J.J Nagar A1 street (B.T Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10470,Roads,Completed,ND-TONDIARPET,41,1053000,"Restoration of Roadcut at J.J Nagar A2 street (B.T Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10471,Roads,Completed,ND-TONDIARPET,41,1212000,"Restoration of Roadcut at Old pumping station road (B.T Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10472,Roads,Completed,ND-TONDIARPET,41,2034000,"Restoration of Roadcut at Kamarajar salai (B.T Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10505,Roads,Completed,ND-TONDIARPET,41,780000,"Relaying the damaged road at Irusappa street(west) in Dn-39,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10513,Roads,Completed,ND-TONDIARPET,41,441000,"Restoration of Roadcut at Devi Karumariamman nagar 5th street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10514,Roads,Completed,ND-TONDIARPET,41,106000,"Restoration of Roadcut at Ezhil Nagar A Block 18th street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10515,Roads,Completed,ND-TONDIARPET,41,882000,"Restoration of Roadcut at Gopal Nagar 1,2,3,4,5&6th street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10516,Roads,Completed,ND-TONDIARPET,41,1270000,"Restoration of Roadcut at Kannagi nagar 1,2,3,4& 5th street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10517,Roads,Completed,ND-TONDIARPET,41,423000,"Restoration of Roadcut at J.J nagar I Street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10518,Roads,Completed,ND-TONDIARPET,41,388000,"Restoration of Roadcut at J.J nagar J Street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10519,Roads,Completed,ND-TONDIARPET,41,388000,"Restoration of Roadcut at J.J nagar K Street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10520,Roads,Completed,ND-TONDIARPET,41,370000,"Restoration of Roadcut at J.J nagar H Street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10541,Buildings,Completed,ND-TONDIARPET,41,80000,"Improvements to Chennai Corporation Primary School located at Anna Nagar (Periyar Salai) in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/10543,Buildings,Completed,ND-TONDIARPET,41,80000,"Improvements to Chennai Corporation Primary School located at M.G.R Nagar in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/10546,Buildings,Completed,ND-TONDIARPET,41,20000,"Improvement works to P.C at J.J Nagar in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/10548,Buildings,Completed,ND-TONDIARPET,41,20000,"Improvement works to P.C at Anna Nagar in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/10549,Buildings,Completed,ND-TONDIARPET,41,20000,"Improvement works to P.C at Sivaji Nagar in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/10582,Buildings,Completed,ND-TONDIARPET,41,50000,"Improvements to Amma unavagam located at J.J Nagar in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/11478,Road Cut,Completed,ND-TONDIARPET,41,1211000,"Restoration of Roadcut at Kalvai Salai (M.G.R Nagar) in Dn-41, Unit-10, Zone-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/2555,Buildings,Completed,ND-TONDIARPET,41,26500,"Improvement works to ICDS located at J.J Nagar centre number 90302 in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/2858,Buildings,Completed,ND-TONDIARPET,41,12300,"Improvement works to ICDS located at J.J Nagar centre number 90301 in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/2859,Buildings,Completed,ND-TONDIARPET,41,124400,"Improvement works to ICDS located at Anna Nagar centre number 90304 in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/2862,Buildings,Completed,ND-TONDIARPET,41,44750,"Improvement works to ICDS located at Chandira Sekar Nagar centre number 90426 in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/2865,Buildings,Completed,ND-TONDIARPET,41,99000,"Improvement works to ICDS located at Thoppai Vinayagar Koil Street in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/2868,Buildings,Completed,ND-TONDIARPET,41,108500,"Improvement works to ICDS located at Devi karumariamman nagar centre number 90421 in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/2871,Buildings,Completed,ND-TONDIARPET,41,92600,"Improvement works to ICDS located at Devi karumariamman nagar centre number 90422 in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/2876,Buildings,Completed,ND-TONDIARPET,41,44400,"Improvement works to ICDS located at Cornation nagar centre number 90307 in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/3205,Buildings,Completed,ND-TONDIARPET,41,146000,"REPAIRS TO AMMA UNAVAGAM AT ANNAI SATHYA NAGAR IN DIV-41,UNIT-10,ZONE-4",Own Sources,4,2017-18,2017-18 ND/2017-18/3936,Buildings,Completed,ND-TONDIARPET,41,299000,"Improvement works to ICDS located at Sivaji nagar centre number 90310 in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/3937,Buildings,Completed,ND-TONDIARPET,41,470000,"Improvement works to ICDS located at Kamaraj Salai centre number in Division-41, Unit-10, Zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/5340,Buildings,Completed,ND-TONDIARPET,41,366000,"Improvements and construction of new sump in Chennai Corporation Middle School located at parthasarathy Street in Division-41, Unit-10, Zone-IV.",Own Sources,4,2017-18,2017-18 ND/2017-18/7177,Storm Water Drain,Completed,ND-TONDIARPET,41,16000,"Desilting of Strom water drain at Sivaji Nagar Main Street in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 ND/2017-18/7178,Storm Water Drain,Completed,ND-TONDIARPET,41,72000,"Desilting of Strom water drain at Kumaran Nagar 1st Street in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 ND/2017-18/7179,Storm Water Drain,Completed,ND-TONDIARPET,41,40000,"Desilting of Strom water drain at Vaidhyanathan Service lane in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 ND/2017-18/7180,Storm Water Drain,Completed,ND-TONDIARPET,41,78000,"Desilting of Strom water drain at Manali Salai in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 ND/2017-18/7181,Storm Water Drain,Completed,ND-TONDIARPET,41,60000,"Desilting of Strom water drain at Ennore High Road in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 ND/2017-18/7183,Storm Water Drain,Completed,ND-TONDIARPET,41,8000,"Desilting of Strom water drain at Govindhasamy Nagar Bharathidasan Street in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 ND/2017-18/7186,Storm Water Drain,Completed,ND-TONDIARPET,41,318000,"Desilting of Strom water drain at Cornation Nagar 1-4th Street in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 ND/2017-18/7187,Storm Water Drain,Completed,ND-TONDIARPET,41,14000,"Desilting of Strom water drain at Kannagi Nagar 5th Street in Division-41, Unit-10, Zone -IV",Own Sources,4,2017-18,2017-18 B/2017-18/15354,Buildings,Completed,B-Buildings,42,9762074,"Additional works to zonal office IV building and construction of compound wall, parking shed and landscape works for Zonal office IV in Tondiarpet in Dn-42, Zone IV",Own Sources,4,2017-18,2020-21 B/2017-18/9056,Electrical,Completed,B-Buildings,42,4830900,"Providing Air conditioner Units, Generator set, PA System and Intercom and Projector for the newly constructed Zonal office 4 building in Div-42 Zone-4",Own Sources,4,2017-18,2019-20 L/2017-18/8542,Electrical,Completed,L-Electrical,42,111500,"Cost of removal of 59 No's Street Lamp Post at T H Road Western Side,Eastern Side and TH Road (From Vaidyanadhan Street to A.E Koil Street) due to Metro Rail , in Dn:42 and 40, Zone IV",Own Sources,4,2017-18,2017-18 ND/2017-18/10057,Buildings,Completed,ND-TONDIARPET,42,410000,"Providing Portable toilet 2 nos for Women with Water Tank 2000lt on Rental Basis and Maintenance for One Year at Kailasam Huts in Dn-42,Unit-10,Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10058,Buildings,Completed,ND-TONDIARPET,42,800000,"Providing Portable Toilet 4 Nos with Water Tank 2000Lt on Rental Basis and Maintenance for One Year at T.H Road (Opp: Post Office) in Division - 42, Unit - 10, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/10464,Roads,Completed,ND-TONDIARPET,42,697000,"Restoration of Roadcut at Thirunavukkarasu thottam 2nd st & T.H Service road (South) in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10467,Roads,Completed,ND-TONDIARPET,42,697000,"Restoration of Roadcut at M.C.M garden 1st lane & T.H road Service Road (North) in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10474,Roads,Completed,ND-TONDIARPET,42,346000,"East kg garden 1st street & T.H Road 2nd lane in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10477,Roads,Completed,ND-TONDIARPET,42,277000,"Restoration of Roadcut at East kg garden 2nd street & T.H.Road 3rd lane in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10479,Roads,Completed,ND-TONDIARPET,42,346000,"Restoration of Roadcut at East kg garden main street & selvavinayagar koil street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10481,Roads,Completed,ND-TONDIARPET,42,736000,"Restoration of Roadcut at West Krishnappa Garden 2nd Street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10486,Roads,Completed,ND-TONDIARPET,42,269000,"Relaying B.T.Road at Nethaji Nagar A Street in Dn-38, unit-9, zone-4",Own Sources,4,2017-18,2017-18 ND/2017-18/10488,Roads,Completed,ND-TONDIARPET,42,1038000,"Restoration of Roadcut at Veerakutty Street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10489,Roads,Completed,ND-TONDIARPET,42,208000,"Restoration of Roadcut at East KG garden 3rd Street ( B.T Road) in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10490,Roads,Completed,ND-TONDIARPET,42,588000,"Restoration of Roadcut at A.P Garden 4th Street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10492,Roads,Completed,ND-TONDIARPET,42,388000,"Restoration of Roadcut at Rathinasababathi lane (C.C Road) in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10496,Roads,Completed,ND-TONDIARPET,42,1048000,"Restoration of Roadcut at Appasamy thottam 2nd & 3rd Street (C.C Road) in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10497,Roads,Completed,ND-TONDIARPET,42,688000,"Restoration of Roadcut at Mayer Basudev 3rd lane (C.C Road) in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10498,Roads,Completed,ND-TONDIARPET,42,423000,"Restoration of Roadcut at West KG garden 2nd lane (C.C Road) in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10500,Roads,Completed,ND-TONDIARPET,42,226000,"Relaying the Damaged Road at Theyagi Perumal street in dn-39 un-10,zn-4",Own Sources,4,2017-18,2017-18 ND/2017-18/10512,Roads,Completed,ND-TONDIARPET,42,445000,"Restoration of Roadcut at Gopal Nagar 5th & 6th Street (C.C Road) in Dn-41,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10529,Buildings,Completed,ND-TONDIARPET,42,45000,"Improvements Works to 16th day Ceremony Hall at Rettaikuzhi Street in Dn-42,u-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10531,Parks,Completed,ND-TONDIARPET,42,20000,"Improvement Works to Thiyagaraya Park at T.H Road in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10532,Parks,Completed,ND-TONDIARPET,42,495000,"Improvements Work to Jeeva Park at T.H Road in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10569,Parks,Completed,ND-TONDIARPET,42,15000,"Improvements Works to Rettaikuzhi Street Park in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10573,Buildings,Completed,ND-TONDIARPET,42,18000,"Improvements Work to PC at Kailasam Street in Dn-42,u-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10574,Buildings,Completed,ND-TONDIARPET,42,16000,"Improvements Works to PC at Seniamman Koil Street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/11418,Roads,Completed,ND-TONDIARPET,42,567000,"Restoration of Roadcut at MCM garden 1st street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/11419,Roads,Completed,ND-TONDIARPET,42,553000,"Restoration of Roadcut at MCM garden 2nd street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/11420,Roads,Completed,ND-TONDIARPET,42,726000,"Restoration of Roadcut at MCM garden 3rd street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/11422,Roads,Completed,ND-TONDIARPET,42,581000,"Restoration of Roadcut at Thirunavukkarasu Thottam 2nd street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/11423,Roads,Completed,ND-TONDIARPET,42,484000,"Restoration of Roadcut at Thirunavukkarasu Thottam 3rd street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/11434,Roads,Completed,ND-TONDIARPET,42,519000,"Restoration of Roadcut at Kothandaraman Street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/12283,Buildings,Completed,ND-TONDIARPET,42,71000,"Repair Works in PC at Kailasam Street in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/15088,Buildings,Completed,ND-TONDIARPET,42,226600,"Repairs Works in PC at Seniamman Koil Street in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2019-20 ND/2017-18/15588,Buildings,Completed,ND-TONDIARPET,42,626000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Thilagar Nagar in Div-42, Unit-10, Zone-4.",Own Sources,4,2017-18,2019-20 ND/2017-18/1966,Buildings,Completed,ND-TONDIARPET,42,750000,"Improvements Work to 540 CGHSS at T.H Road in Dn-42,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/4875,Buildings,Completed,ND-TONDIARPET,42,153000,"Improvement ICDS Centre No.16 at Seniamman Koil Main Street in Dn-42,Unit-10,Zone-04",Own Sources,4,2017-18,2018-19 ND/2017-18/4890,Buildings,Completed,ND-TONDIARPET,42,197000,"Improvement Work Centre No.17 At Rettaikuzhi Street in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5187,Buildings,Completed,ND-TONDIARPET,42,400000,"Improvement Work at Amma Unavagam Seniamman Koil Street in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/5341,Buildings,Completed,ND-TONDIARPET,42,474000,"Improvement Work in UPHC at T.H Road in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/6239,Buildings,Completed,ND-TONDIARPET,42,79000,"Repairs Work at Dhobikana at Kothandaraman Street in Dn-42,Unit-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/6305,Buildings,Completed,ND-TONDIARPET,42,1673000,"Dismantling old Zonal office Building at T.H Road in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/6838,Buildings,Completed,ND-TONDIARPET,42,842000,"Providing and Laying GI Sheet at 540 T.H Road in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/8794,Storm Water Drain,Completed,ND-TONDIARPET,42,23800,"Desilting of SWD at Seniamman koil Street in Dn-42,unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8795,Storm Water Drain,Completed,ND-TONDIARPET,42,35300,"Desilting of SWD at Kailasam Street in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8797,Storm Water Drain,Completed,ND-TONDIARPET,42,148600,"Desilting of SWD at Rettaikuzhi Street in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8798,Storm Water Drain,Completed,ND-TONDIARPET,42,78100,"Desilting of SWD at T.H Road in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8800,Storm Water Drain,Completed,ND-TONDIARPET,42,25200,"Desilting of SWD at Kothandaraman Street in Dn-42.Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/9612,Buildings,Completed,ND-TONDIARPET,42,200000,"Providing Portable Toilet 4 Nos with Water Tank 2000Lt on Rental Basis and Maintenance for three Months at T.H Road (Opp: Post Office) in Division - 42, Unit - 10, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9720,Buildings,Completed,B-Buildings,42,110000,"Painting work and Improvement Work to Smart Class Room in 540 CGHSS in Dn-42,Unit-10,Zone-04.",Own Sources,4,2017-18,2018-19 L/2017-18/10055,Electrical,Completed,L-Electrical,43,59170,"Provision of 120sq.mm cable laying from Main panel to MDB in Administrative block at Communicable Disase hospital in Div.43, Z-4",Own Sources,4,2017-18,2017-18 ND/2017-18/0938,Buildings,Completed,ND-TONDIARPET,43,235000,"Construction of Well Type Compost Yard at Inside of Hindu Burial Ground in Dn-43Unit-10, Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10387,Buildings,Completed,ND-TONDIARPET,43,800000,"Improvement to the OP Ward at CDH Building in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10390,Buildings,Completed,ND-TONDIARPET,43,300000,"Improvement to the Filaria Ward at CDH in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10394,Buildings,Completed,ND-TONDIARPET,43,900000,"Repairs and Improvements to the Anbagam at CDH in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10395,Buildings,Completed,ND-TONDIARPET,43,500000,"Repairs and Improvements to the Kitchen Shed at CDH in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10396,Buildings,Completed,ND-TONDIARPET,43,800000,"Construction of Compound Wall Hostel at CDH in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10509,Roads,Completed,ND-TONDIARPET,43,101000,"RoadCut of Restoration at CG colony 8th Street in Dn-43,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10510,Roads,Completed,ND-TONDIARPET,43,761000,"Restoration of RoadCut at CG colony main Street in Dn-43,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10511,Roads,Completed,ND-TONDIARPET,43,346000,"Relaying B.T Road at Vinayagapuram main Street in Dn-43,U-10,Z-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/10522,Roads,Completed,ND-TONDIARPET,43,1804000,"Restoration of RoadCut at New Amaranjipuram and Kasimanagar in Dn-43,U-10,Z-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/10537,Buildings,Completed,ND-TONDIARPET,43,800000,"Repairs and Improvement to the Admin Block at CDH in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10538,Buildings,Completed,ND-TONDIARPET,43,600000,"Repairs and Improvement to the Quarters Block at CDH in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10539,Buildings,Completed,ND-TONDIARPET,43,450000,"Repairs and Improvement to the Compound wall at Christian Burial Ground in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10540,Buildings,Completed,ND-TONDIARPET,43,520000,"Construction of Toilet Block and Repairs & Improvements work at Muslim Burial Groung In Dn-43,U-10,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10542,Buildings,Completed,ND-TONDIARPET,43,100000,"Repairs and Improvement to the Amma Unavagam at M.G.R Nagar in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10545,Buildings,Completed,ND-TONDIARPET,43,150000,"Improvement to the amma Unavagam at Pudumanaikuppam Main Street in Dn-43,u-10,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10547,Buildings,Completed,ND-TONDIARPET,43,150000,"Improvement to the amma Unavagam at CDH (Campus Inside) in Dn-43,u-10,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10550,Buildings,Completed,ND-TONDIARPET,43,100000,"Repairs and Improvements to ICDS at Pudumanaikuppam Main Street in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10551,Buildings,Completed,ND-TONDIARPET,43,250000,"Flooring,Drainage Arregement to the ICDS at Kasipuram B B lock 10th Street in DN-43,u-10,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10553,Buildings,Completed,ND-TONDIARPET,43,50000,"Repairs and Improvement (Minor Repairs) to the ICDS at Pudumaikuppam CMS inside in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10555,Buildings,Completed,ND-TONDIARPET,43,100000,"Repairs and Improvement to the CMS at Vinayagapuram in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10562,Parks,Completed,ND-TONDIARPET,43,10000,"Repairs and Maintenance of Park at Hindu Burial Ground Park in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10563,Parks,Completed,ND-TONDIARPET,43,15000,"Repairs and Maintenance of Park at Suriyanarayanan Street in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10564,Parks,Completed,ND-TONDIARPET,43,20000,"Repairs and Maintenance of park at CDH in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10656,Road Cut,Completed,ND-TONDIARPET,43,191000,"Restoration of Roadcut at C.G Colony 2nd Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10659,Road Cut,Completed,ND-TONDIARPET,43,373000,"Restoration of Roadcut at C.G Colony 1st Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10660,Road Cut,Completed,ND-TONDIARPET,43,313000,"Restoration of Roadcut at C.G Colony 3rd Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10661,Road Cut,Completed,ND-TONDIARPET,43,279000,"Restoration of Roadcut at C.G Colony 4TH Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10662,Road Cut,Completed,ND-TONDIARPET,43,249921,"Restoration of Roadcut at C.G Colony 5th Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10663,Road Cut,Completed,ND-TONDIARPET,43,270000,"Restoration of Roadcut at C.G Colony 6th Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10680,Road Cut,Completed,ND-TONDIARPET,43,284000,"Restoration of Roadcut at C.G Colony 7th Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10681,Road Cut,Completed,ND-TONDIARPET,43,387000,"Restoration of Roadcut at Tondiar Nagar 1st Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10682,Road Cut,Completed,ND-TONDIARPET,43,367000,"Restoration of Roadcut at Tondiar Nagar 2nd Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10683,Road Cut,Completed,ND-TONDIARPET,43,367000,"Restoration of Roadcut at Tondiar Nagar 3rd Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10684,Road Cut,Completed,ND-TONDIARPET,43,117000,"Restoration of Roadcut at Tondiar Nagar 4th Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10685,Road Cut,Completed,ND-TONDIARPET,43,108000,"Restoration of Roadcut at Tondiar Nagar 5th Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10686,Road Cut,Completed,ND-TONDIARPET,43,128000,"Restoration of Roadcut at Tondiar Nagar 6th Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10687,Road Cut,Completed,ND-TONDIARPET,43,435000,"Restoration of Roadcut at Tondiar Nagar 7th Street (B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10688,Road Cut,Completed,ND-TONDIARPET,43,611000,"Restoration of Roadcut at Priyapalayathu Amman Koil Street(B.T Road) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/15539,Buildings,Completed,ND-TONDIARPET,43,1468000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Hindu Burial Ground in Div-43, Unit-10, Zone-4",Own Sources,4,2017-18,2019-20 ND/2017-18/16108,Buildings,Completed,ND-TONDIARPET,43,1468000,"Proposed Construction of Resource recovery Centre with Basice Machineries at Tsunami Quarters in Div-40, Unit-10, Zone-4",Own Sources,4,2017-18,2020-21 ND/2017-18/2633,Buildings,Completed,ND-TONDIARPET,43,118000,"Repairs and Maintainance at S.N Cheety ICDS Center (Minor Repairs) in Dn-43,Unit-10,Zone-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/2768,Buildings,Completed,ND-TONDIARPET,43,454000,"Construction of Compound wall and other improvement work at Pudumanaikuppam CMS in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/3923,Buildings,Completed,ND-TONDIARPET,43,295000,"Repairs and Improvement to UPHC CDH Building in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/3951,Buildings,Completed,ND-TONDIARPET,43,670000,"Dismandling and Construction of Compound wall at A.D Road (Division Office) in DN-43,U-10,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/4860,Buildings,Completed,ND-TONDIARPET,43,356000,"Construction of Compound Wall and Improvement to the UPHC at Kasimanagar 3rd Street in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/4887,Buildings,Completed,ND-TONDIARPET,43,731000,"Dismantling and Construction of Compound Wall(North Side) at Pudumanaikuppam CMS in DN-43,U-10,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/9535,Buildings,Completed,B-Buildings,43,576000,"Flooring,Painting and Other Improvement Works for Smart Class Room at CMS at Pudumanaikuppam (South Side Building) in Dn-43, Unit-10, Zone-4.",Own Sources,4,2017-18,2018-19 BR/2017-18/11389,Roads,Completed,BR-Bus Route Roads,44,49000,Restoration of road cut made by CMWSSB at Madhavaram High Road in Zone-4 against challan no. BR/2017-18/0001767,Deposit Works,4,2017-18,2018-19 BR/2017-18/11395,Roads,Completed,BR-Bus Route Roads,44,37000,Restoration of road cut made by CMWSSB at Melpatti ponnappan street in Zone-4 against challan no. BR/2017-18/0006597,Deposit Works,4,2017-18,2018-19 BR/2017-18/11397,Roads,Completed,BR-Bus Route Roads,44,44000,Restoration of road cut made by CMWSSB at Madhavaram High Road in Zone-4 against challan no. BR/2017-18/0005724,Deposit Works,4,2017-18,2018-19 BR/2017-18/12137,Roads,Completed,BR-Bus Route Roads,44,74000,"Restoration of Road cut made by CMWSSB in Melpatti ponnappan street street in Dn-44, Zone-IV against challan no. BR/2017-18/0019309",Deposit Works,4,2017-18,2018-19 BR/2017-18/12816,Roads,Completed,BR-Bus Route Roads,44,74000,"Restoration of Road cut made by CMWSSB in Madhavaram High Road in Dn-30, Zone-III against challan no. BR/2017-18/0020650",Deposit Works,4,2017-18,2018-19 L/2017-18/6812,Electrical,Completed,L-Electrical,44,971700,"Replacement of over head wires with 2700 Mtrs of 2x16 Sqmm Cable at Kakanji Colony, Alagar Sami Street, Sathiyabama Street, Anbalagan Street, Sathiyavani Muthunagar and Various locations in div 44 Zone IV.",Own Sources,4,2017-18,2019-20 L/2017-18/6814,Electrical,Completed,L-Electrical,44,988000,"Replacement of over head wires with Mtrs of 3 1/2 X 25 Sqmm Cable at Thulasingam Street, Thiru . VI .Ka street, MPM Road, Siddco Main Road, MKB Nagar Bridge, West Avenue Road and Various Locations in div 44 & 36 Zone IV.",Own Sources,4,2017-18,2019-20 L/2017-18/8122,Electrical,Completed,L-Electrical,44,198000,"Replacement of Over Head wires with 586 mtrs of 2x16sqmm cable at Kakanji colony, Periyar Nagar, and various loactions in Div 44 Zone IV",Own Sources,4,2017-18,2018-19 L/2017-18/8123,Electrical,Completed,L-Electrical,44,198200,"Replacement of Over Head wires with 504 mtrs of 4x16 sqmm ALU cable at Siddco Main Road, MKB Nagar Bridge, Thulasingam St, Manickkam Vinayagam St and various loactions in Div 36 & 44 Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/12849,Roads,Completed,ND-TONDIARPET,44,587000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT N.S.K STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/12850,Roads,Completed,ND-TONDIARPET,44,847000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT MA.PO.SI STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/12853,Roads,Completed,ND-TONDIARPET,44,282000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT MATHIYAZHAGAN STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/2518,Buildings,Completed,ND-TONDIARPET,44,94000,"Improvement and Repair work @ ICDS (AnganVadi Center)-No.(12043,12118) Azhagiri samy Street (Udhaya kumar Street) in DN-44, Unit -11,Zone -04.",Own Sources,4,2017-18,2018-19 ND/2017-18/2522,Buildings,Completed,ND-TONDIARPET,44,61000,"mprovement and Repair work @ ICDS (AnganVadi Center)-No.7201,7202 Nattal Garden II Street in DN-44, Unit -11,Zone -04.",Own Sources,4,2017-18,2018-19 ND/2017-18/2535,Buildings,Completed,ND-TONDIARPET,44,60000,"Improvement and Repair work @ ICDS (AnganVadi Center)-No7047,7049,7046 Anabazgan Street in DN-44, Unit -11,Zone -04.",Own Sources,4,2017-18,2018-19 ND/2017-18/2536,Buildings,Completed,ND-TONDIARPET,44,50000,"Improvement and Repair work @ ICDS (AnganVadi Center)-No.(70106,70107) Rani Ammaiyar Street in DN-44, Unit -11,Zone -04.",Own Sources,4,2017-18,2018-19 ND/2017-18/2537,Buildings,Completed,ND-TONDIARPET,44,54000,"Improvement and Repair work @ ICDS (AnganVadi Center)-No 12046,12041 at Gandhiji I Street in DN-44, Unit -11,Zone -04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5903,Roads,Completed,ND-TONDIARPET,44,1660000,"IMPROVEMENTS TO B.T ROAD at THULSINGAM STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5912,Roads,Completed,ND-TONDIARPET,44,86000,"IMPROVEMENTS TO B.T ROAD AT THULSINGAM 2ND STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5920,Roads,Completed,ND-TONDIARPET,44,484000,"IMPROVEMENTS TO B.T ROAD AT KAMARAJ NAGAR 2ND STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5925,Roads,Completed,ND-TONDIARPET,44,52000,"IMPROVEMENTS TO B.T ROAD AT K.V.K SAMY STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5931,Roads,Completed,ND-TONDIARPET,44,114000,"IMPROVEMENTS TO B.T ROAD AT THIRUVALLUR CROSS STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5936,Roads,Completed,ND-TONDIARPET,44,702000,"IMPROVEMENTS TO B.T ROAD AT PANNEER SELVAM STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/5941,Roads,Completed,ND-TONDIARPET,44,1537000,"IMPROVEMENTS TO BT ROAD AT NAGAVALLI AMMAN KOIL STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/8256,Storm Water Drain,Completed,ND-TONDIARPET,44,99000,"Supplying and fixing Storm Water Drain Manhole door at various street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/8649,Buildings,Completed,ND-TONDIARPET,44,28000,"DESILTING OF STROM WATER DRAIN AT MUNIYAPPAN STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8654,Buildings,Completed,ND-TONDIARPET,44,100000,"DESILTING OF STROM WATER DRAIN AT PALANI ANDAVAR KOVIL STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8656,Buildings,Completed,ND-TONDIARPET,44,35000,"DESILTING OF STROM WATER DRAIN AT KAMARAJ NAGAR 1ST STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8657,Buildings,Completed,ND-TONDIARPET,44,45000,"DESILTING OF STROM WATER DRAIN AT V.O.C STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8659,Buildings,Completed,ND-TONDIARPET,44,25000,"DESILTING OF STROM WATER DRAIN AT MATHIZAGAN STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8661,Buildings,Completed,ND-TONDIARPET,44,37000,"DESILTING OF STROM WATER DRAIN AT AMMAN KOVIL STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8665,Buildings,Completed,ND-TONDIARPET,44,121000,"DESILTING OF STROM WATER DRAIN AT MELPATTI PONNAPPAN STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8710,Buildings,Completed,ND-TONDIARPET,44,127000,"DESILTING OF STROM WATER DRAIN AT MA.PO.SI STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8711,Buildings,Completed,ND-TONDIARPET,44,47000,"DESILTING OF STROM WATER DRAIN AT THULSIGAM 2ND LANE IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8712,Buildings,Completed,ND-TONDIARPET,44,110000,"DESILTING OF STROM WATER DRAIN AT THIRUCHI CHINNASAMY STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2017-18 ND/2017-18/8713,Buildings,Completed,ND-TONDIARPET,44,120000,"DESILTING OF STROM WATER DRAIN AT SUBRAMANI NAGAR MAIN ROAD STREET IN DN-44, UNIT-11, ZONE-04.",Own Sources,4,2017-18,2018-19 BR/2017-18/11393,Roads,Completed,BR-Bus Route Roads,45,37800,Restoration of road cut made by CMWSSB at BB Road in Zone-4 against challan no. BR/2017-18/0005903,Deposit Works,4,2017-18,2018-19 ND/2017-18/1055,Storm Water Drain,Completed,ND-TONDIARPET,45,200000,"Desilting of SWD at B B road 1st, 2nd, 3rd street, Balamurugan street In Dn-45,U-11,Z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/1160,Buildings,Completed,ND-TONDIARPET,45,236000,"Construction of Well Type Compost Yard at MPM Street (Opposite to MLA Office at Road Side Park) in Dn-45, Unit11-, Zone-04.",Own Sources,4,2017-18,2018-19 ND/2017-18/13017,Electrical,Completed,ND-TONDIARPET,45,439400,"Electrification of Lorry Depot and Provision of LT Panel Board, Tube Light Fan, Plug Point at B B Road Lorry Depot in Division 45, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/16372,Storm Water Drain,Completed,ND-TONDIARPET,45,500000,"Desilting of SWD at B B road 1st, 2nd, 3rd street, Balamurugan street In Dn-39 to 43,U-10,Z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/16489,Roads,Completed,ND-TONDIARPET,45,238000,"ATTENDING ROAD DAMAGES CAUSED IN THE RECENT RAIN AT STEPHENSON LANE IN DN 45, UNIT 11,ZONE 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/16491,Roads,Completed,ND-TONDIARPET,45,186000,"ATTENDING ROAD DAMAGES CAUSED IN THE RECENT RAIN AT B V COLONY 1st STREET IN DN 45, UNIT 11,ZONE 4",Own Sources,4,2017-18,2018-19 ND/2017-18/16492,Roads,Completed,ND-TONDIARPET,45,88990,"ATTENDING ROAD DAMAGES CAUSED IN THE RECENT RAIN AT SUNDHARAM MAIN ROAD IN DN 45, UNIT 11,ZONE 4",Own Sources,4,2017-18,2018-19 ND/2017-18/16493,Roads,Completed,ND-TONDIARPET,45,177900,"ATTENDING ROAD DAMAGES CAUSED IN THE RECENT RAIN AT BB ROAD CROSS STREET JUNCTION IN DN 45, UNIT 11,ZONE 4",Own Sources,4,2017-18,2018-19 ND/2017-18/16494,Roads,Completed,ND-TONDIARPET,45,331000,"ATTENDING ROAD DAMAGES CAUSED IN THE RECENT RAIN AT B V COLONY 18th STREET IN DN 45, UNIT 11,ZONE 4",Own Sources,4,2017-18,2018-19 ND/2017-18/2401,Storm Water Drain,Completed,ND-TONDIARPET,45,200000,"Desilting of B V Colony 1st street, masuthi street, MPM street, sr iram nagar In Dn-45,U-11,Z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/2533,Storm Water Drain,Completed,ND-TONDIARPET,45,100000,"Desilting of work at clinic road In Dn-45,U-11,Z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/5864,Roads,Completed,ND-TONDIARPET,45,277000,"IMPROVEMENT BT ROAD WORK AT B V COLONY 4TH STREET IN DIVISION- 45, UNIT-11, ZONE-4",Own Sources,4,2017-18,2018-19 ND/2017-18/5867,Roads,Completed,ND-TONDIARPET,45,190000,"IMPROVEMENT BT ROAD WORK AT DESIGANATHAPURAM POWER LANE IN DIVISION- 45, UNIT-11, ZONE-4",Own Sources,4,2017-18,2018-19 ND/2017-18/5874,Roads,Completed,ND-TONDIARPET,45,1090000,"IMPROVEMENTS TO BT ROAD WORK DESIGANATHAPURAM 1ST STREET IN DIVISION- 45, UNIT-11, ZONE-4",Own Sources,4,2017-18,2018-19 ND/2017-18/5877,Roads,Completed,ND-TONDIARPET,45,726000,"IMPROVEMENTS TO BT ROAD WORK AT B V COLONY 1ST CROSS STREET IN DIVISION- 45, UNIT-11, ZONE-4",Own Sources,4,2017-18,2018-19 ND/2017-18/5880,Roads,Completed,ND-TONDIARPET,45,744000,"IMPROVEMENTS TO BT ROAD WORK AT DESIGANATHAPURAM 2ND STREET IN DIVISION- 45, UNIT-11, ZONE-4",Own Sources,4,2017-18,2018-19 ND/2017-18/8260,Storm Water Drain,Completed,ND-TONDIARPET,45,97000,"PROVIDING MANHOLE DOOR AT VARIOUS STREET IN DN-45,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/8650,Storm Water Drain,Completed,ND-TONDIARPET,45,139000,"Desilting of SWD at B V Colony 18th street In Division-45,Unit-11,Zone-04",Own Sources,4,2017-18,2017-18 ND/2017-18/8678,Storm Water Drain,Completed,ND-TONDIARPET,45,76000,"Desilting of SWD at Annai Sathya Nagar Main Road In Division-45,Unit-11,Zone-04",Own Sources,4,2017-18,2017-18 ND/2017-18/8680,Storm Water Drain,Completed,ND-TONDIARPET,45,125000,"Desilting of SWD at Kakkanji Colony 1st Street In Division-45,Unit-11,Zone-04",Own Sources,4,2017-18,2017-18 BR/2017-18/16590,Roads,Completed,BR-Bus Route Roads,46,2264000,"Restoration of road cut made by CMWSSB at Moorthinger street and Muthu mudali street in Dn-46, Zone-IV against Challan No. BR/2017-18/0022536.",Deposit Works,4,2017-18,2018-19 ND/2017-18/10363,Buildings,Completed,B-Buildings,46,400000,"Conversion of Class Room into Smart Class Room in CHSS Kalyana puram, in ward-46, Unit-11, Zone-4",Own Sources,4,2017-18,2019-20 ND/2017-18/1347,Storm Water Drain,Completed,ND-TONDIARPET,46,540000,"DESILTING THE S.W.D AT S.M NAGAR MAIN ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1383,Storm Water Drain,Completed,ND-TONDIARPET,46,43000,"DESILTING OF S.W.D AT MOORTHINGAR STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1387,Storm Water Drain,Completed,ND-TONDIARPET,46,36000,"DESILTING THE S.W.D AT MUTHU STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1389,Buildings,Completed,ND-TONDIARPET,46,110000,"Repairs and improvements to Public Convenience at John Kennady Nagar 1st street in Ward-46, Unit-11,Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/1390,Buildings,Completed,ND-TONDIARPET,46,185000,"Repairs and improvements to Public Convenience at Samanthipoo Colony (Good Shed road) in Ward-46, Unit-11, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/1392,Storm Water Drain,Completed,ND-TONDIARPET,46,100000,"DESILTING THE S.W.D AT MOSQUE STREET (BOTH SIDE) ,NEHRU NAGAR MAIN ST, 3RD AND 5TH STREETS, AND SM NAGAR 24TH BLOCK IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1394,Storm Water Drain,Completed,ND-TONDIARPET,46,97000,"DESILTING THE S.W.D AT PALLA 1ST, 2ND, 2ND CROSS, 3RD, AND 4TH STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1397,Buildings,Completed,ND-TONDIARPET,46,156000,"Repairs and improvements to Public Convenience at Moorthingar street in Ward-46, Unit-11,Zone-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1400,Storm Water Drain,Completed,ND-TONDIARPET,46,44000,"DESILTING THE S.W.D AT JOHN KENNEDY MAIN ROAD & CROSS STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1403,Storm Water Drain,Completed,ND-TONDIARPET,46,60000,"DESILTING THE S.W.D AT A.B KALYANAPURAM MAIN ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1408,Storm Water Drain,Completed,ND-TONDIARPET,46,40000,"DESILTING THE S.W.D AT C KALYANAPURAM MAIN ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1410,Storm Water Drain,Completed,ND-TONDIARPET,46,137000,"DESILTING THE S.W.D AT GOOD SHED ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1727,Buildings,Completed,ND-TONDIARPET,46,125000,"REPAIR AND IMPROVEMENT TO UPHC AT S.M NAGAR MAIN ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/2327,Storm Water Drain,Completed,ND-TONDIARPET,46,40000,"DESILTING THE S.W.D AT GANDHIPURAM IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/2331,Buildings,Completed,ND-TONDIARPET,46,135000,"Repairs and improvements to Public Convenience at Mallippoo Colony (Good Shed road) in Ward-46, Unit-11,Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/2412,Buildings,Completed,ND-TONDIARPET,46,119000,"IMPROVEMENT TO ANGANVADI CENTER NO.70117 AT S.M NAGAR 36TH BLOCK IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/2429,Buildings,Completed,ND-TONDIARPET,46,180000,"IMPROVEMENT TO ANGANVADI CENTER NO.70116 AT S.M NAGAR 31TH BLOCK IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/3132,Electrical,Completed,ND-TONDIARPET,46,195000,"Repairs and improvements to Public Convenience at S M Nagar Main road in Ward-46, Unit-11,Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/3133,Buildings,Completed,ND-TONDIARPET,46,145000,"Rerpairs and Improvements to Public Convenience at Moorthingar Street ( Junction of Muthu St) in Ward-46, Unit-11, Zone-4",Own Sources,4,2017-18,2018-19 ND/2017-18/3303,Parks,Completed,ND-TONDIARPET,46,160000,"MAINTENANCE OF PARK AT SM NAGAR MAIN ROAD IN WARD -46, UNIT -11, ZONE-04",Own Sources,4,2017-18,2018-19 ND/2017-18/8259,Storm Water Drain,Completed,ND-TONDIARPET,46,99000,"PROVIDING MANHOLE DOOR AT VARIOUS STREET IN DN-46,U-11,Z-04",Own Sources,4,2017-18,2018-19 L/2017-18/6629,Electrical,Completed,L-Electrical,47,168900,"Replacement of accessories and maintenance work for 20 mtr High Mast at K.H Road in Division 47, Zone IV",Own Sources,4,2017-18,2018-19 ND/2017-18/10461,Roads,Completed,ND-TONDIARPET,47,1920000,"Restoration of Roadcut and Relaying of Road at Harinarayanapuram Main Street ,kamaraja nagar 5,6,7,street ( C.C Road) in Dn-47,U-11,Z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10487,Roads,Completed,ND-TONDIARPET,47,1120000,"Restoration of Roadcut jawnmal sowcar street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/10491,Roads,Completed,ND-TONDIARPET,47,1590000,"Restoration of Roadcut at Kamarajar nagar 8,10,11,&12th street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10528,Buildings,Completed,ND-TONDIARPET,47,200000,"Improvements to Harinarayanapuram C.H.S At Old glass factory road in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10533,Buildings,Completed,ND-TONDIARPET,47,100000,"Improvements to Harinarayanapuram C.P.S At Old glass factory road in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10534,Buildings,Completed,ND-TONDIARPET,47,80000,"Repairs to C.M.S BUDHA School At Kannan Street in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10535,Parks,Completed,ND-TONDIARPET,47,25000,"Repairs To Bharathi nagar housing board park(TNSCB) in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/10536,Buildings,Completed,ND-TONDIARPET,47,20000,"Repairs to P.C.(Near pumping station) At C.B.Road in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/11288,Roads,Completed,ND-TONDIARPET,47,865000,"Restoration of Roadcut Egambaram street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11289,Roads,Completed,ND-TONDIARPET,47,346000,"Restoration of Roadcut Thyagappa street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/11290,Roads,Completed,ND-TONDIARPET,47,1557000,"Restoration of Roadcut RK.NAGAR,1,2,&Main street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/11291,Roads,Completed,ND-TONDIARPET,47,692000,"Restoration of Roadcut Pittymunusamy street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11296,Roads,Completed,ND-TONDIARPET,47,865000,"Restoration of Roadcut Egappan street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/11297,Roads,Completed,ND-TONDIARPET,47,865000,"Restoration of Roadcut Sathyamurthy street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/11298,Roads,Completed,ND-TONDIARPET,47,1136000,"Restoration of Roadcut Old.factory.road street (B.T Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/11301,Roads,Completed,ND-TONDIARPET,47,529000,"Restoration of Roadcut at Anandhanayagi nagar C.B.ROAD,2nd street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11302,Roads,Completed,ND-TONDIARPET,47,616000,"Restoration of Roadcut at Anandhanayagi nagar C.B.ROAD,3rd street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11303,Roads,Completed,ND-TONDIARPET,47,600000,"Restoration of Roadcut at Anandhanayagi nagar C.B.ROAD,4th street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11304,Roads,Completed,ND-TONDIARPET,47,600000,"Restoration of Roadcut at Anandhanayagi nagar C.B.ROAD,5th street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11305,Roads,Completed,ND-TONDIARPET,47,245000,"Restoration of Roadcut at Anandhanayagi nagar C.B.ROAD,1st street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11307,Roads,Completed,ND-TONDIARPET,47,227000,"Restoration of Roadcut at Anandhanayagi nagar C.B.ROAD,3rd.cross street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11308,Roads,Completed,ND-TONDIARPET,47,353000,"Restoration of Roadcut at Anandhanayagi nagar cross street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/11309,Roads,Completed,ND-TONDIARPET,47,352000,"Restoration of Roadcut at Madhurai muthu street (C.C Road) in dn-47,u-11,z-04",Own Sources,4,2017-18,2017-18 ND/2017-18/1143,Buildings,Completed,ND-TONDIARPET,47,1600000,"PROPOSED CONSTRUCTION OF WINDROWS COMPOSTED YARD AT CANAL ROAD IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/13719,Buildings,Completed,ND-TONDIARPET,47,95800,"DISMANTLING AND RECONSTRUCTION OF COMPOUND WALL AT(JJ NAGAR A1 STREET) DIVISION OFFICE 47 IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/15638,Buildings,Completed,ND-TONDIARPET,47,519000,"Supplying and Providing, Bio Shredding Machine, Sieving Machine and Wighing machine,Polythene Machine at Source Segregation Centre at C.B.road under fly over , in Division -47, Unit-11, Zone-04",Own Sources,4,2017-18,2019-20 ND/2017-18/15816,Buildings,Completed,ND-TONDIARPET,47,129000,MInor repairs and providing sunshade to C.P.S Meenambal nagar in ward.47 unit.11 zone.4,Own Sources,4,2017-18,2018-19 ND/2017-18/1750,Roads,Completed,ND-TONDIARPET,47,494000,"REPAIRS AND IMPROVEMENT TO HEALTH POST AT HARI NARAYANAPURAM IN DN-47,UNIT-11,ZONE-4",Own Sources,4,2017-18,2018-19 ND/2017-18/2454,Buildings,Completed,ND-TONDIARPET,47,51000,"MINOR REPAIR WORK TO ICDS (CMS INSIDE CENTER NO:33603090401) AT KANNAN STREET IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2455,Buildings,Completed,ND-TONDIARPET,47,123000,"MINOR REPAIR WORK TO RANGANATHAPURAM TNSCB SOUTH ICDS (CENTER NO:33603090403) AT RANGANATHAPURAM HOUSING BOARD IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2457,Buildings,Completed,ND-TONDIARPET,47,168000,"MINOR REPAIR WORK TO RANGANATHAPURAM TNSCB NORTH ICDS (CENTER NO:33603090404) AT RANGANATHAPURAM HOUSING BOARD IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2459,Buildings,Completed,ND-TONDIARPET,47,59000,"MINOR REPAIR WORK TO HARINARAYANAPURAM ICDS EAST (CENTER NO:33603090405) AT OLD GLASS FACTORY ROAD IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2460,Buildings,Completed,ND-TONDIARPET,47,54000,"MINOR REPAIR WORK TO HARINARAYANAPURAM ICDS SOUTH (CENTER NO:33603090407) AT OLD GLASS FACTORY ROAD IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2461,Buildings,Completed,ND-TONDIARPET,47,82000,"MINOR REPAIR WORK TO ICDS (CENTER NO:33603090409) AT BHARATHI NAGAR 6TH STREET IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2462,Buildings,Completed,ND-TONDIARPET,47,68000,"MINOR REPAIR WORK TO ICDS (CENTER NO:33603090410) AT MEENAMBAL NAGAR IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2464,Buildings,Completed,ND-TONDIARPET,47,44000,"MINOR REPAIR WORK TO ICDS (CENTER NO:33603090414) AT JEEVA NAGAR 16TH STREET IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2466,Buildings,Completed,ND-TONDIARPET,47,40000,"MINOR REPAIR WORK TO ICDS (CENTER NO:33603090415) AT JEEVA NAGAR 14TH STREET IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2467,Buildings,Completed,ND-TONDIARPET,47,139000,"MINOR REPAIR WORK TO ICDS (CENTER NO:33603090427) AT ANANDHANAYAGI NAGAR 2ND STREET IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/2495,Buildings,Completed,ND-TONDIARPET,47,66000,"MINOR REPAIR WORK TO ICDS (CENTER NO:33603090411) AT MEENAMBAL NAGAR IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/3746,Storm Water Drain,Completed,ND-TONDIARPET,47,177000,"DESILTING THE SWD AT K.H. ROAD.IN DN-47,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/3747,Storm Water Drain,Completed,ND-TONDIARPET,47,206000,"DESILTING THE SWD AT C.B.ROAD IN DN-47,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/3748,Storm Water Drain,Completed,ND-TONDIARPET,47,147000,"DESILTING THE SWD AT AMBETHKAR CANAL IN DN-47,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/3749,Storm Water Drain,Completed,ND-TONDIARPET,47,115000,"DESILTING THE SWD AT SIGGIRINTHAPALAYAM 4TH ST IN DN-47,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/3750,Storm Water Drain,Completed,ND-TONDIARPET,47,87000,"DESILTING THE SWD AT SIGGIRINTHAPALAYAM 11TH ST IN DN-47,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/3751,Storm Water Drain,Completed,ND-TONDIARPET,47,80000,"DESILTING THE SWD AT KAMARAJA NAGAR 12TH ST IN DN-47,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/3771,Parks,Completed,ND-TONDIARPET,47,170000,"Annual Maintenance of Park at Bharathi Nagar Housing Board in Dn-47,U-11,Z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/3943,Buildings,Completed,ND-TONDIARPET,47,171000,"ADDITIONAL IMPROVEMENT WORK TO AMMA UNAVAGAM AT SIGGIRINTHAPALAYAM 5TH STREET IN DN-47,U-11,Z-4",Own Sources,4,2017-18,2018-19 ND/2017-18/8258,Storm Water Drain,Completed,ND-TONDIARPET,47,99000,"Providing Manhole door at various street in dn-47,u-11,z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/9637,Buildings,Completed,ND-TONDIARPET,47,812000,"PROVIDING PORTABLE TOILETS 4 NOS WITH WATER TANK 2000lt ON RENTAL BASIS AND MAINTANANCE FOR ONE YEAR AT CB ROAD UNDER FLY OVER IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/9638,Buildings,Completed,ND-TONDIARPET,47,1244000,"Providing Portable Toilet 6 Nos with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Kamaraj Nagar 12th Street in Division - 47, Unit - 11, Zone",Own Sources,4,2017-18,2018-19 ND/2017-18/9639,Buildings,Completed,ND-TONDIARPET,47,155000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for 3months at Kamaraj Nagar 12th Street in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9641,Buildings,Completed,ND-TONDIARPET,47,1244000,"Providing Portable Toilet 6 Nos with Water Tank 2000Lt on Rental Basis and Maintenance for one year at Old Glass Factory in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9643,Buildings,Completed,ND-TONDIARPET,47,155000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for 3months at Old Glass Factory in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9651,Buildings,Completed,ND-TONDIARPET,47,155000,"Providing Portable Toilet 3 Nos For Men with Water Tank 2000Lt on Rental Basis and Maintenance for 3months at Old Glass Factory in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9652,Buildings,Completed,ND-TONDIARPET,47,155000,"Providing Portable Toilet 3 Nos For Women with Water Tank 2000Lt on Rental Basis and Maintenance for 3months at Kamaraj Nagar 12th Street in Division - 47, Unit - 11, Zone - 4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9653,Buildings,Completed,ND-TONDIARPET,47,203000,"PROVIDING PORTABLE TOILETS 4 NOS WITH WATER TANK 2000lt ON RENTAL BASIS AND MAINTANANCE FOR 3months AT CB ROAD UNDER FLY OVER IN DN-47,U-11,Z-04",Own Sources,4,2017-18,2018-19 ND/2017-18/0935,Buildings,Completed,ND-TONDIARPET,48,1585000,"CONSTRUCTION OF COMPOSED YARD -2 @ TPF BASIN BRIDGE ROAD IN DN- 48, U-11, Z-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/1112,Storm Water Drain,Completed,ND-TONDIARPET,48,75000,"DESILTING THE SWD AT ARANIGANGAN STREET IN DN-48,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/1114,Storm Water Drain,Completed,ND-TONDIARPET,48,220000,"DESILTING THE SWD AT RAMANUJAKOODAM STREET IN DN-48,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/1115,Storm Water Drain,Completed,ND-TONDIARPET,48,270000,"DESILTING THE SWD AT MINT SUBRAYAN STREET IN DN-48,UNIT-11,Z-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/1118,Storm Water Drain,Completed,ND-TONDIARPET,48,190000,"DESILTING S.W.D AT T.H ROAD IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2017-18 ND/2017-18/1119,Storm Water Drain,Completed,ND-TONDIARPET,48,310000,"DESILTING S.W.D AT NALLAPPA VATHIYAR STREET IN DN-48-UNIT-11,ZONE-4",Own Sources,4,2017-18,2017-18 ND/2017-18/1239,Buildings,Completed,ND-TONDIARPET,48,190000,"DESILTING S.W.D AT ANDIAPPAN STREET IN DN-48-UNIT-11,ZONE-4",Own Sources,4,2017-18,2017-18 ND/2017-18/2435,Buildings,Completed,ND-TONDIARPET,48,208000,"IMPROVEMENT TO THE UPHC @ T.H.ROAD (V.R.NAGAR} IN DN-48, U-11. Z-4.",Own Sources,4,2017-18,2019-20 ND/2017-18/5603,Road Cut,Completed,ND-TONDIARPET,48,104000,"IMPROVEMENTS TO BT ROAD AT PARTHA SARATHY STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/5605,Road Cut,Completed,ND-TONDIARPET,48,346000,"IMPROVEMENTS TO BT ROAD AT NATARAJA MUDALI STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/5606,Road Cut,Completed,ND-TONDIARPET,48,899000,"IMPROVEMENTS TO BT ROAD AT BASUVAIYAN STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/5607,Road Cut,Completed,ND-TONDIARPET,48,432000,"IMPROVEMENTS TO BT ROAD AT KANNI KOIL STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/5608,Road Cut,Completed,ND-TONDIARPET,48,642000,"IMPROVEMENTS TO BT ROAD AT SUBBARAYAN TREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/5610,Road Cut,Completed,ND-TONDIARPET,48,652000,"IMPROVEMENTS TO BT ROAD AT JAMAL SOWKAR STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/5611,Road Cut,Completed,ND-TONDIARPET,48,284000,"IMPROVEMENTS TO BT ROAD AT JAMAL SOWKAR LANE IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/5614,Road Cut,Completed,ND-TONDIARPET,48,318000,"IMPROVEMENTS TO BT ROAD AT SUNDARA VINAYAGAR KOIL STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/8250,Storm Water Drain,Completed,ND-TONDIARPET,48,97000,"PROVIDING MAN HOLE DOOR FOR SWD @ PARTHASARATHY ST, T.H.ROAD, MUTHIYA ST, MANNAPPAN ST, NAIMIYAPPAN ST, M.S.NAIDU ST,. RAMANUJA KUDAM ST, ARANI GANGAN ST, ULARRAMMAN ST, THULASIGAM ST,RAMANUJA IYAR ST, NALLAPPA VATHIYAR ST, SOLAIYAPPAN ST,ANDIYAPPAN ST, EAST CEMENTRY ROAD WEST CEMENTRY STREET IN DN-48, U-11, Z-4.",Own Sources,4,2017-18,2018-19 ND/2017-18/9553,Buildings,Completed,ND-TONDIARPET,48,2830000,"THE PROPOSED CONSTRUCTION OF ANGANVADI BUILDING(CENTER NO.33603010209) AT PARTHASARATHI NAGAR IN DN-48,UNIT-11,ZONE-4.",MLACDS,4,2017-18,2018-19 ND/2017-18/9664,Buildings,Completed,ND-TONDIARPET,48,2830000,"THE PROPOSED CONSTRUCTION OF ANGANVADI BUILDING(CENTER NO.33603010207) AT PARTHASARATHI NAGAR IN DN-48,UNIT-11,ZONE-4.",MLACDS,4,2017-18,2018-19 ND/2017-18/9706,Buildings,Completed,ND-TONDIARPET,48,2480000,"THE PROPOSED CONSTRUCTION OF MULTI PURPOSE HALL BUILDING AT PARTHASARATHI NAGAR IN DN-48,UNIT-11,ZONE-4.",MLACDS,4,2017-18,2018-19 B/2017-18/16581,Buildings,Completed,B-Buildings,49,16805400,"REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE IN UNIT-12,13,14, ZONE-5",Own Sources,5,2017-18,2020-21 B/2017-18/16585,Buildings,Completed,B-Buildings,49,9249000,REPAIRS AND IMPROVEMENTS TO CHENNAI SCHOOLS AT VARIOUS LOCATIONS IN ZONE-4,Own Sources,5,2017-18,2019-20 B/2017-18/16586,Buildings,Completed,B-Buildings,49,17336000,REPAIR AND MAINTENANCE WORKS TO CHENNAI SCHOOL BUILDINGS AT VARIOUS LOCATIONS IN ZONE-5,Own Sources,5,2017-18,2021-22 L/2017-18/6966,Electrical,Completed,L-Electrical,49,199900,Supply of 150 nos of 1 mtr Single Straight Bracket for fixing in Various Location in Div - 49 and 50 - Zone - 5.,Own Sources,5,2017-18,2019-20 NE/2017-18/12591,Buildings,Completed,NE-ROYAPURAM,49,155000,"Repairs to Community toilet at Soliappan Street in ward-49, Unit-12, Zone-5 Asst code- 156/2078/845/2009-10",Own Sources,5,2017-18,2018-19 NE/2017-18/12593,Buildings,Completed,NE-ROYAPURAM,49,235000,"Repairs to Community toilet at Appasamy Street In Ward-49,Unit-12, Zone-5 Asst code-044/2092/27312/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/12594,Buildings,Completed,NE-ROYAPURAM,49,229000,"Repairs to Urinal Drain in West Kalmanapam road in ward-49, Unit-12, Zone-5 Asst code: B/2124/1102/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/12645,Roads,Completed,NE-ROYAPURAM,49,188000,"Repairs and Maintance to Public Convenience Jaganathan Street in Ward-52, Unit-12, Zone-5 033/2274/526/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/2609,Storm Water Drain,Completed,NE-ROYAPURAM,49,18900,"Desilting of Storm water drain in Solaiappan Street in Div 49,Unit 12,Zone 5. 055/2078/5171/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2610,Storm Water Drain,Completed,NE-ROYAPURAM,49,13300,"Desilting of Storm Water Drain in Kothandaramar Street in Div 49,Unit 12,Zone 5. 055/2073/7362/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2611,Storm Water Drain,Completed,NE-ROYAPURAM,49,16700,"Desilting of Storm Water Drain in New Thandavarayan Street in Div 49,Unit 12,Zone 5. 055/15325/6598/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2612,Storm Water Drain,Completed,NE-ROYAPURAM,49,8600,"Desilting of Storm Water Drain in Balu Street in Div 49,Unit 12,Zone 5. 044/2088/24653/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2613,Storm Water Drain,Completed,NE-ROYAPURAM,49,28800,"Desilting of Storm Water Drain in Kappal Polu Street in Div 49,Unit 12,Zone 5.055/2067/6582/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2619,Storm Water Drain,Completed,NE-ROYAPURAM,49,19900,"Desilting of Storm Water Drain in Thandavarayan Street in Div 49,Unit 12,Zone 5. 040/2112/3748/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2620,Storm Water Drain,Completed,NE-ROYAPURAM,49,15400,"Desilting of Storm Water Drain in Bala Arunachalam Street in Div 49,Unit 12,Zone 5. 055/2091/6585/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2621,Storm Water Drain,Completed,NE-ROYAPURAM,49,34600,"Desilting of Storm Water Drain in Sanjeevarayan Koil Street in Div 49,Unit 12,Zone 5. 156/2081/2157/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/2622,Storm Water Drain,Completed,NE-ROYAPURAM,49,13300,"Desilting of Storm Water Drain in Venkatachalam Street in Div 49,Unit 12,Zone 5. 055/2084/6596/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2643,Storm Water Drain,Completed,NE-ROYAPURAM,49,20700,"Desilting of Storm Water Drain in Adam Street in Div 49,Unit 12,Zone 5. 055/2122/6599/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2645,Storm Water Drain,Completed,NE-ROYAPURAM,49,5100,"Desilting of Storm Water Drain in Bashyam Street in Div 49,Unit 12,Zone 5 044/2137/24269/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2647,Storm Water Drain,Completed,NE-ROYAPURAM,49,14000,"Desilting of Storm Water Drain in Grace Garden Main Road in Div 49,Unit 12,Zone 5. 055/2102/6586/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2650,Storm Water Drain,Completed,NE-ROYAPURAM,49,8100,"Desilting of Storm Water Drain in New kamarajar nagar 5th street in Div 49,Unit 12,Zone 5. 055/2104/6587/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2652,Storm Water Drain,Completed,NE-ROYAPURAM,49,14000,"Desilting of Storm Water Drain in Old Amaranjipuram in Div 49,Unit 12,Zone 5. 055/2103/6356/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2654,Storm Water Drain,Completed,NE-ROYAPURAM,49,10300,"Desilting of Storm Water Drain in PAN Rajarathinam Salai in Div 49,Unit 12,Zone 5. 055/15890/4782/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2655,Storm Water Drain,Completed,NE-ROYAPURAM,49,17600,"Desilting of Storm Water Drain in Rajagopal Street in Div 49,Unit 12,Zone 5. 055/2149/6600/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2657,Storm Water Drain,Completed,NE-ROYAPURAM,49,23600,"Desilting of Storm Water Drain in Rajavelu Street in Div 49,Unit 12,Zone 5. 055/2147/6601/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2659,Storm Water Drain,Completed,NE-ROYAPURAM,49,19000,"Desilting of Storm Water Drain in Singara garden 4th lane in Div 49,Unit 12,Zone 5. 055/2144/6602/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2663,Storm Water Drain,Completed,NE-ROYAPURAM,49,19500,"Desilting of Storm Water Drain in Singara garden 5th lane in Div 49,Unit 12,Zone 5. 044/2143/14633/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2664,Storm Water Drain,Completed,NE-ROYAPURAM,49,4800,"Desilting of Storm Water Drain in Somu 1st lane in Div 49,Unit 12,Zone 5. 055/2139/6589/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2665,Storm Water Drain,Completed,NE-ROYAPURAM,49,16100,"Desilting of Storm Water Drain in Somu 2nd lane in Div 49,Unit 12,Zone 5.",Own Sources,5,2017-18,2017-18 NE/2017-18/2667,Storm Water Drain,Completed,NE-ROYAPURAM,49,3400,"Desilting of Storm Water Drain in Somu 5th lane in Div 49,Unit 12,Zone 5. 055/2117/6588/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2668,Storm Water Drain,Completed,NE-ROYAPURAM,49,20300,"Desilting of Storm Water Drain in Thandavarayan Street in Dn-49, Unit-12, Zone-5 055/2075/6583/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2670,Storm Water Drain,Completed,NE-ROYAPURAM,49,13200,"Desilting of Storm Water Drain in West Kalmandapam Road in Dn-49, Unit-12, Zone-5 055/2124/6590/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/3202,Buildings,Completed,NE-ROYAPURAM,49,43600,"Repairs to Community Toilet at singara garden 4th street at Ward-49, Unit-12, Zone-5 Asst code - B/2144/876/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5414,Roads,Completed,NE-ROYAPURAM,49,553000,"Improvement to Road Work at Pandaliya Street in Ward-49, Unit-12, Zone-5 Asst code :044/2087/24655/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/5416,Roads,Completed,NE-ROYAPURAM,49,1400000,"Improvement to B.T road to Sri Rangammal Street in Ward-49, Unit-12, Zone-5 Asst code : 044/2076/14631/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5418,Roads,Completed,NE-ROYAPURAM,49,1418000,"Improvement to B.T road at Sanjeevaryan Koil Street in Ward-49, Unit-12, Zone-5 Asst code: 044/2081/14630/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5427,Roads,Completed,NE-ROYAPURAM,49,1420000,"Improvement to B.T road at Kappal polu street in Ward-49, Unit-12, Zone-5 044/2067/24656/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/5460,Roads,Completed,NE-ROYAPURAM,49,986000,"Improvement to B.T road at Balu (M) street in Ward-49, Unit-12, Zone-5 044/2088/24653/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/5467,Roads,Completed,NE-ROYAPURAM,49,380000,"Improvement to B.T road at Balu lane in Ward-49, Unit-12, Zone-5 044/15563/14632/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5488,Roads,Completed,NE-ROYAPURAM,49,1410000,"Improvement to C.C road at Old Amaranjipuarm to New Kamarajar 5th street in Ward-49, Unit-12, Zone-5 044/2104/24751/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/6927,Roads,Completed,NE-ROYAPURAM,49,32400,"Repairs and maintenance Existing of Speed breaker in Singara Garden 4th Street at Ward-49, Unit-12, Zone-5 044/2144/8667/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/6928,Roads,Completed,NE-ROYAPURAM,49,34000,"Repairs and maintenance Existing of Speed breaker in Singara Garden 8th Street at Ward-49, Unit-12, Zone-5 044/2140/8665/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/6929,Roads,Completed,NE-ROYAPURAM,49,35600,"Repairs and maintenance Existing of Speed breaker in M.C road at Ward-49, Unit-12, Zone-5 044/2099/15507/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/8888,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,Improvement and Minor Repairs of Existing of Storm Water Drain in Solaiappan Street 055/2078/5171/2013-14,Own Sources,5,2017-18,2017-18 NE/2017-18/8890,Storm Water Drain,Completed,NE-ROYAPURAM,49,5700,Improvement and Minor Repairs of Existing of Storm Water Drain in Bashyam Street 044/2137/24269/2014-15,Own Sources,5,2017-18,2017-18 NE/2017-18/8891,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,Improvement and Minor Repairs of Existing Storm Water Drain in Bala Arunachalam Street 055/2091/6585/2014-15,Own Sources,5,2017-18,2017-18 NE/2017-18/8892,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,Improvement and Minor Repairs of Existing of Storm Water Drain in Thandavarayan street 040/2112/3748/2013-14,Own Sources,5,2017-18,2017-18 NE/2017-18/8893,Storm Water Drain,Completed,NE-ROYAPURAM,49,17300,Improvement and Minor Repairs of Existing of Storm Water Drain in Adam Street 055/2122/6599/2014-15,Own Sources,5,2017-18,2017-18 NE/2017-18/8894,Storm Water Drain,Completed,NE-ROYAPURAM,49,11500,Improvement and Minor Repairs of Existing of Storm Water Drain in Venkatachalam street 055/2084/6596/2014-15,Own Sources,5,2017-18,2017-18 NE/2017-18/8895,Storm Water Drain,Completed,NE-ROYAPURAM,49,11500,Improvement and Minor Repairs of Existing of Storm Water Drain in Kothandaraman street 055/2073/7362/2014-15,Own Sources,5,2017-18,2017-18 NE/2017-18/8896,Storm Water Drain,Completed,NE-ROYAPURAM,49,28900,Improvement and Minor Repairs of Existing of Storm Water Drain in Sanjeevayaran koil street 156/2081/2157/2015-16,Own Sources,5,2017-18,2017-18 NE/2017-18/8897,Storm Water Drain,Completed,NE-ROYAPURAM,49,23100,"Improvement and Minor Repairs of Existing of Storm Water Drain in Kappal polu street Div-49, Unit-12, Zone-5 055/2067/6582/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8899,Storm Water Drain,Completed,NE-ROYAPURAM,49,11500,"Improvement and Minor Repairs of Existing of Storm Water Drain in Balu street Div-49, Unit-12, Zone-5 044/2088/24653/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8900,Storm Water Drain,Completed,NE-ROYAPURAM,49,17300,"Improvement and Minor Repairs of Existing of Storm Water Drain in New Thandavarayan street Div-49, Unit-12, Zone-5 055/15325/6598/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8901,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in West Kalmandapam Road Div-49, Unit-12, Zone-5 055/2124/6590/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8902,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Thandavarayan street Div-49, Unit-12, Zone-5 055/2075/6583/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8903,Storm Water Drain,Completed,NE-ROYAPURAM,49,2899,"Improvement and Minor Repairs of Existing of Storm Water Drain in Somu 5th lane Div-49, Unit-12, Zone-5 055/2117/6588/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8904,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Somu 2nd lane Div-49, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/8905,Storm Water Drain,Completed,NE-ROYAPURAM,49,2899,"Improvement and Minor Repairs of Existing of Storm Water Drain in Somu 1st lane Div-49, Unit-12, Zone-5 055/2139/6589/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8906,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Singara Garden 5th lane Div-49, Unit-12, Zone-5 044/2143/14633/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8908,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Singara Garden 4th lane Div-49, Unit-12, Zone-5 055/2144/6602/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8909,Storm Water Drain,Completed,NE-ROYAPURAM,49,17300,"Improvement and Minor Repairs of Existing of Storm Water Drain in Rajavelu street Div-49, Unit-12, Zone-5 055/2147/6601/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8910,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Rajagopal street Div-49, Unit-12, Zone-5 055/2149/6600/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8911,Storm Water Drain,Completed,NE-ROYAPURAM,49,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain in PAN Rajarathinam salai Div-49, Unit-12, Zone-5 055/15890/4782/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8912,Storm Water Drain,Completed,NE-ROYAPURAM,49,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Grace Garden Main Road Div-49, Unit-12, Zone-5 055/2102/6586/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8913,Storm Water Drain,Completed,NE-ROYAPURAM,49,11500,"Improvement and Minor Repairs of Existing of Storm Water Drain in Old Amaranjipuram Div-49, Unit-12, Zone-5 055/2103/6356/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8914,Storm Water Drain,Completed,NE-ROYAPURAM,49,5700,"Improvement and Minor Repairs of Existing of Storm Water Drain in New Kamarajar Nagar 5th street Div-49, Unit-12, Zone-5 055/2104/6587/2014-15",Own Sources,5,2017-18,2017-18 BR/2017-18/4175,Roads,Completed,BR-Bus Route Roads,50,103000,Restoration of OFC road cut made by Idea Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/0413/2016,Deposit Works,5,2017-18,2019-20 BR/2017-18/4176,Roads,Completed,BR-Bus Route Roads,50,194000,Restoration of OFC road cut made by Idea Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/4661/2016,Deposit Works,5,2017-18,2019-20 BR/2017-18/4177,Roads,Completed,BR-Bus Route Roads,50,240000,Restoration of OFC road cut made by Idea Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/3955/2016,Deposit Works,5,2017-18,2019-20 BR/2017-18/4178,Roads,Completed,BR-Bus Route Roads,50,160000,Restoration of OFC road cut made by Idea Communication Ltd in Zone -5 For the challan no-B.R.R.C.NO.B4/4202/2016,Deposit Works,5,2017-18,2019-20 BR/2017-18/4186,Roads,Completed,BR-Bus Route Roads,50,401000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 5 - For the challan no-B.R.R.C.NO.B4/0002/2016,Deposit Works,5,2017-18,2019-20 BR/2017-18/4189,Roads,Completed,BR-Bus Route Roads,50,210000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 5 - For the challan no-B.R.R.C.NO.B4/2453/2016,Deposit Works,5,2017-18,2019-20 BR/2017-18/4190,Roads,Completed,BR-Bus Route Roads,50,287000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 5 - For the challan no-B.R.R.C.NO.B4/3134/2016,Deposit Works,5,2017-18,2019-20 BR/2017-18/4198,Roads,Completed,BR-Bus Route Roads,50,164000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 5 - For the challan no-B.R.R.C.NO.B4/0393/2017,Deposit Works,5,2017-18,2018-19 NE/2017-18/10246,Roads,Completed,NE-ROYAPURAM,50,160000,Providing gully connection at various necessary places in ward.50 unit.12 zone.5,Own Sources,5,2017-18,2018-19 NE/2017-18/10247,Buildings,Completed,NE-ROYAPURAM,50,200000,Providing rain water harvesting at various nacessary places in ward.50 unit.12 zone.5,Own Sources,5,2017-18,2018-19 NE/2017-18/10248,Buildings,Completed,NE-ROYAPURAM,50,162000,Repairs to diesel motor and providing hose pipe and repairs to plastic streading machine in ward.50 unit.12 zone 5,Own Sources,5,2017-18,2018-19 NE/2017-18/10250,Buildings,Completed,NE-ROYAPURAM,50,200000,providing silt pit and other repairs storm water drain at various street in ward.50 unit.12 zone.5,Own Sources,5,2017-18,2018-19 NE/2017-18/11446,Roads,Completed,NE-ROYAPURAM,50,104000,ATTENDING THE URGENT REPAIR WORK AND FLOOD RELATED WORK AT VARIOUS STREET DN-50 U-12 Z-5,Own Sources,5,2017-18,2018-19 NE/2017-18/12681,Buildings,Completed,NE-ROYAPURAM,50,106000,"Repairs to Community Toilet at A.J Colony Main street in ward-50 unit-12 zone-5 033/15569/291/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/15673,Buildings,Completed,NE-ROYAPURAM,50,979000,"Construction of New Resource Recovery center at EAST MADHA CHRUCH STREET IN DIV-50, UNIT-12, ZONE-V",Own Sources,5,2017-18,2019-20 NE/2017-18/17053,Roads,Completed,NE-ROYAPURAM,50,130000,"Repairs and maintenance Existing of Speed breaker North Mada Chruch Street at Ward-50, Unit-12, Zone- 5 044/42623/24755/2014-15",Own Sources,5,2017-18,2019-20 NE/2017-18/2656,Storm Water Drain,Completed,NE-ROYAPURAM,50,39700,"DESILTING OF SWD SHEIK MAISTRY STREET IN DN-50,UNIT-12,ZONE-5. 055/2162/5008/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2662,Storm Water Drain,Completed,NE-ROYAPURAM,50,4700,"DESILTING OF SWD AT G.M.PETTAI(ON WESTERN SIDE) IN DN-50,UNIT-12,ZONE-5 055/2179/7389/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/2745,Storm Water Drain,Completed,NE-ROYAPURAM,50,53400,"Desilting storm water drain at S.N Street in ward.50 unit.12 zone.5 055/2159/3187/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2748,Storm Water Drain,Completed,NE-ROYAPURAM,50,48900,"Desilting storm water drain at M.S Kovil street in ward.50 unit.12 zone.5 055/2200/5014/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2749,Storm Water Drain,Completed,NE-ROYAPURAM,50,61500,"Desilting storm water drain at east madha street in ward.50 unit.12 zone.5 055/2202/5018/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2750,Storm Water Drain,Completed,NE-ROYAPURAM,50,73400,"Desilting storm water drain at north madha street ( north&south) in ward.50 unit 12 zone.5 055/2228/5017/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2752,Storm Water Drain,Completed,NE-ROYAPURAM,50,18900,"Desilting storm water drain at west madha street in ward.50 unit.12 zone.5 055/2230/5022/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2753,Storm Water Drain,Completed,NE-ROYAPURAM,50,24400,Desilting storm water drain at North Madha street in wad.50 unit.12 zone.5 055/2228/5017/2013-14,Own Sources,5,2017-18,2017-18 NE/2017-18/2755,Storm Water Drain,Completed,NE-ROYAPURAM,50,29300,"Desilting storm water drain at venkatesan street in ward.50 unit.12 zone.5 055/2235/5019/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/3946,Buildings,Completed,NE-ROYAPURAM,50,34100,"Repairs to Community Toilet at Thambu Street in ward-50 unit-12 zone-5 033/2158/399/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/3960,Buildings,Completed,NE-ROYAPURAM,50,193000,"Repairs to Community Toilet at G.M Petai in ward.50 unit.12 zone.5 033/2179/400/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5490,Roads,Completed,NE-ROYAPURAM,50,157000,"Improvement to B.T road at Tambu Lane in Ward-50, Unit-12, Zone-5 044/2158/1257/2006-07",Own Sources,5,2017-18,2018-19 NE/2017-18/5501,Roads,Completed,NE-ROYAPURAM,50,246000,"Improvement to C.C road at East Mada Main Road in Ward-50, Unit-12, Zone-5 043/2398/1084/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/5503,Roads,Completed,NE-ROYAPURAM,50,246000,"Improvement to C.C road at East Mada 1st street in Ward-50, Unit-12, Zone-5 039/2194/4/2001-02",Own Sources,5,2017-18,2018-19 NE/2017-18/5507,Roads,Completed,NE-ROYAPURAM,50,176000,"Improvement to C.C road at Mariamman Koil Street in Ward-50, Unit-12, Zone-5 044/2168/1263/2008-09",Own Sources,5,2017-18,2018-19 NE/2017-18/5508,Roads,Completed,NE-ROYAPURAM,50,105000,"Improvement to C.C road at Sathanar Koil street in Ward-50, Unit-12, Zone-5 044/15581/6065/2008-09",Own Sources,5,2017-18,2018-19 NE/2017-18/5511,Roads,Completed,NE-ROYAPURAM,50,317000,"Improvement to C.C road at Thulukanathamman Street in Ward-50, Unit-12, Zone-5 040/2157/6589/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5515,Roads,Completed,NE-ROYAPURAM,50,987000,"Improvement to C.C road at G.M.Pettai 2nd & 3rd Street in Ward-50, Unit-12, Zone-5 040/2212/252/2007-08",Own Sources,5,2017-18,2018-19 NE/2017-18/5518,Roads,Completed,NE-ROYAPURAM,50,176000,"Improvement to C.C road at Gurka lane in Ward-50, Unit-12, Zone-5 Asset code- 041/2181/2/2007-08",Own Sources,5,2017-18,2018-19 NE/2017-18/5523,Roads,Completed,NE-ROYAPURAM,50,811000,"Improvement to C.C road at Amman Koil Main Street,1st & 2nd Street in Ward-50, Unit-12, Zone-5 039/2214/16/2000-01",Own Sources,5,2017-18,2018-19 NE/2017-18/5527,Roads,Completed,NE-ROYAPURAM,50,423000,"Improvement to C.C road at Kumarappa Street in Ward-50, Unit-12, Zone-5 039/2201/8/1999-00",Own Sources,5,2017-18,2018-19 NE/2017-18/5530,Roads,Completed,NE-ROYAPURAM,50,635000,"Improvement to C.C road at East Madha Church Street 1 to 10 in Ward-50, Unit-12, Zone-5 039/2197/7/2001-02",Own Sources,5,2017-18,2018-19 NE/2017-18/5535,Roads,Completed,NE-ROYAPURAM,50,493000,"Improvement to C.C road at Thandavamurthy Street in Ward-50, Unit-12, Zone-5 043/2223/13/2004-05",Own Sources,5,2017-18,2018-19 NE/2017-18/5536,Roads,Completed,NE-ROYAPURAM,50,635000,"Improvement to C.C road at Muniappa Street & Lane in Ward-50, Unit-12, Zone-5 040/2198/6512/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5540,Roads,Completed,NE-ROYAPURAM,50,776000,"Improvement to C.C road at Market Lane in Ward-50, Unit-12, Zone-5 044/2167/1262/2008-09",Own Sources,5,2017-18,2018-19 NE/2017-18/5543,Roads,Completed,NE-ROYAPURAM,50,635000,"Improvement to C.C road at Sheik Maestry Street in Ward-50, Unit-12, Zone-5 044/2162/1260/2007-08",Own Sources,5,2017-18,2018-19 NE/2017-18/5544,Roads,Completed,NE-ROYAPURAM,50,670000,"Improvement to C.C road at St.Xavier Street in Ward-50, Unit-12, Zone-5 044/15585/6066/2007-08",Own Sources,5,2017-18,2018-19 NE/2017-18/6967,Roads,Completed,NE-ROYAPURAM,50,71000,"Repairs and maintenance Existing of Speed breaker Andiappan Street (For 3 location) at Ward-50, Unit-12, Zone5 044/2211/18651/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/6968,Roads,Completed,NE-ROYAPURAM,50,82000,"Repairs and maintenance Existing of Speed breaker Arthoon Road (For 4 location) at Ward-50, Unit-12, Zone5 039/2209/14/2008-09",Own Sources,5,2017-18,2019-20 NE/2017-18/6970,Roads,Completed,NE-ROYAPURAM,50,72000,"Repairs and maintenance Existing of Speed breaker Lotus Ramasamy Street (For 3 location) at Ward-50, Unit-12, Zone- 5 044/2169/1264/2006-07",Own Sources,5,2017-18,2019-20 NE/2017-18/6971,Roads,Completed,NE-ROYAPURAM,50,57700,"Repairs and maintenance Existing of Speed breaker Shaik Mastry Street (For 2 location) at Ward-50, Unit-12, Zone- 5 044/2162/1260/2007-08",Own Sources,5,2017-18,2019-20 NE/2017-18/6974,Roads,Completed,NE-ROYAPURAM,50,66000,"Repairs and maintenance Existing of Speed breaker South Mada Chruch Street (For 2 location) at Ward-50, Unit-12, Zone- 5 040/2411/307/2005-06",Own Sources,5,2017-18,2019-20 NE/2017-18/8915,Storm Water Drain,Completed,NE-ROYAPURAM,50,44700,"Improvement and Minor Repairs of Existing of Storm Water Drain in M.S.Kovil Street Div-50, Unit-12, Zone-5 055/2200/5014/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8917,Storm Water Drain,Completed,NE-ROYAPURAM,50,29800,"Improvement and Minor Repairs of Existing of Storm Water Drain in G.M.Pettai (on western side ) Div-50, Unit-12, Zone-5 055/2179/7389/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8918,Storm Water Drain,Completed,NE-ROYAPURAM,50,94000,"Improvement and Minor Repairs of Existing of Storm Water Drain in S.N. Street Div-50, Unit-12, Zone-5 055/2159/3187/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8919,Storm Water Drain,Completed,NE-ROYAPURAM,50,52000,"Improvement and Minor Repairs of Existing of Storm Water Drain in Sheik Maistry street Div-50, Unit-12, Zone-5 055/2162/5008/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8920,Storm Water Drain,Completed,NE-ROYAPURAM,50,29800,"Improvement and Minor Repairs of Existing of Storm Water Drain in West Madha Church Street Div-50, Unit-12, Zone-5 055/2230/5022/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8921,Storm Water Drain,Completed,NE-ROYAPURAM,50,14900,"Improvement and Minor Repairs of Existing of Storm Water Drain in Venkatesan street Div-50, Unit-12, Zone-5 055/2235/5019/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8922,Storm Water Drain,Completed,NE-ROYAPURAM,50,29800,"Improvement and Minor Repairs of Existing of Storm Water Drain in North Madha Church Street Div-50, Unit-12, Zone-5 055/2228/5017/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8923,Storm Water Drain,Completed,NE-ROYAPURAM,50,59600,"Improvement and Minor Repairs of Existing of Storm Water Drain in North Madha Street (North & South) Div-50, Unit-12, Zone-5 055/2228/5017/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8924,Storm Water Drain,Completed,NE-ROYAPURAM,50,59600,"Improvement and Minor Repairs of Existing of Storm Water Drain in East Madha Street Div-50, Unit-12, Zone-5 055/2202/5018/2013-14",Own Sources,5,2017-18,2017-18 BR/2017-18/8248,Road Cut,Completed,BR-Bus Route Roads,51,100000,"Restoration of Road cut made by CMWSSB at M.S Koil street in zone-5,against challan no:BR/2017-18/0010397",Deposit Works,5,2017-18,2019-20 NE/2017-18/0848,Buildings,Completed,NE-ROYAPURAM,51,890000,"CONSTRUCTION OF WELL RING COMPOST YARD AT VARIOUS STREETS IN UNIT-12 (DN-49 TO 53),Z-5",Own Sources,5,2017-18,2018-19 NE/2017-18/16674,Roads,Completed,NE-ROYAPURAM,51,105000,"Repairs and Maintainance of the Existing Speed Breaker in Kalingarayan Street in Div 51,Unit 12,Zone 5. 044/2314/17795/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/16675,Roads,Completed,NE-ROYAPURAM,51,107000,"Repairs and Maintainance of the Existing Speed Breaker in East Cemetry Road in Div 51,Unit 12,Zone 5. 044/2332/17816/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/16676,Roads,Completed,NE-ROYAPURAM,51,136000,"Repairs and Maintainance of the Existing Speed Breaker in Manikandan 4th Street in Div 51,Unit 12,Zone 5. 044/2310/17806/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/16677,Roads,Completed,NE-ROYAPURAM,51,90000,"Repairs and Maintainance of the Existing Speed Breaker in Srirangammal Street in Div 51,Unit 12,Zone 5. 044/2298/13250/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/1780,Storm Water Drain,Completed,NE-ROYAPURAM,51,19500,"Desilting of Storm water drain in Kalingarayan Street in Old washermenpet in Div 51,Unit 12,Zone 5. SD/2314/365/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/1787,Storm Water Drain,Completed,NE-ROYAPURAM,51,6300,"Desilting of Stormwater drain in Thulukkanam Street ,Old washermenpet in Div 51,Unit 12,Zone 5. 055/2316/7907/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/1789,Storm Water Drain,Completed,NE-ROYAPURAM,51,14100,"Desilting of Stormwater drain in East Cemetry Road ,Ola Washermenpet in Div 51,Unit 12,Zone 5. SD/2332/363/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/1790,Storm Water Drain,Completed,NE-ROYAPURAM,51,22300,"Desilting of Stormwater drain in West Cemetry Road,Old Washermenpet in Div 51,Unit 12,Zone 5. SD/2315/364/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/1791,Storm Water Drain,Completed,NE-ROYAPURAM,51,7700,"Desilting of Storm Water Drain in Manikandan 9th Street (alias) Vadivelu Street,Oldwashermenpet in Div 51,Unit 12,Zone 5. 055/2326/7905/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/1792,Storm Water Drain,Completed,NE-ROYAPURAM,51,23800,"Desilting of Stormwater drain in Narayanappan Street,Oldwashermenpet in Div 51,Unit 12,Zone 5. 055/2318/7906/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/1793,Storm Water Drain,Completed,NE-ROYAPURAM,51,4800,"Desilting of Stormwater drain in Ramanujam Street ,Oldwashermenpet in Div 51,Unit 12,Zone 5. SD/2289/359/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/1795,Storm Water Drain,Completed,NE-ROYAPURAM,51,15400,"Desilting of Stormwater drain in N.N.Garden 8th Street,Oldwashermenpet in Div 51,Unit 12,Zone 5. 055/2299/7904/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/1796,Storm Water Drain,Completed,NE-ROYAPURAM,51,6300,"Desilting of Stormwater drain in Narasier Street ,Old Washermenpet in Div 51,Unit 12,Zone 5. SD/2293/361/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/1797,Storm Water Drain,Completed,NE-ROYAPURAM,51,36300,"Desilting of Storm waterdrain in Cemetry Road,Old washermenpet,Div 51,Unit 12,Zone 5. 053/2334/1995/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2556,Storm Water Drain,Completed,NE-ROYAPURAM,51,11200,"Desilting of Storm Water Drain in Rope Godown Street in Div 52,Unit 12,Zone 5. 055/15595/4917/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/3918,Buildings,Completed,NE-ROYAPURAM,51,70000,"Repairs and maintainance to Community Toilet in NN Garden 8th Street in Div 51, Unit 12, Zone 5. Asset code : 033/2299/544/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5568,Roads,Completed,NE-ROYAPURAM,51,415000,"Improvement to B.T road at N.N.Garden 3rd Lane in Ward-51, Unit-12, Zone-5 044/2301/17787/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5574,Roads,Completed,NE-ROYAPURAM,51,449000,"Improvement to B.T road at N.N.Garden 4th Lane in Ward-51, Unit-12, Zone-5 044/2302/17788/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5577,Roads,Completed,NE-ROYAPURAM,51,415000,"Improvement to B.T road at N.N.Garden 5th Lane in Ward-51, Unit-12, Zone-5 044/2283/17789/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5579,Roads,Completed,NE-ROYAPURAM,51,449000,"Improvement to B.T road at N.N.Garden 6th Lane in Ward-51, Unit-12, Zone-5 044/2300/13266/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5583,Roads,Completed,NE-ROYAPURAM,51,415000,"Improvement to B.T road at N.N.Garden 10th Lane in Ward-51, Unit-12, Zone-5 044/2292/17792/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5587,Roads,Completed,NE-ROYAPURAM,51,449000,"Improvement to B.T road at N.N.Garden 6th Street in Ward-51, Unit-12, Zone-5 044/2300/13266/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5590,Roads,Completed,NE-ROYAPURAM,51,1100000,"Improvement to B.T road at Narasaiyar Street in Ward-51, Unit-12, Zone-5 044/2293/13249/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5593,Roads,Completed,NE-ROYAPURAM,51,1450000,"Improvement to B.T road at N.N.Garden 7th Street in Ward-51, Unit-12, Zone-5 044/2284/17791/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5596,Roads,Completed,NE-ROYAPURAM,51,1488000,"Improvement to B.T road at N.N.Garden 8th Street in Ward-51, Unit-12, Zone-5 044/2299/8489/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8940,Storm Water Drain,Completed,NE-ROYAPURAM,51,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Old Washermanpet, Narasier Street Div-51, Unit-12, Zone-5 SD/2293/361/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8941,Storm Water Drain,Completed,NE-ROYAPURAM,51,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Kalingarayan street in old washermanpet Div-51, Unit-12, Zone-5 SD/2314/365/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8942,Storm Water Drain,Completed,NE-ROYAPURAM,51,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain in Thulukkanam street, Old washermanpet Div-51, Unit-12, Zone-5 055/2316/7907/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/8943,Storm Water Drain,Completed,NE-ROYAPURAM,51,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain in Manikandan 9th street (alias) Vadivelu street, Old washermanpet Div-51, Unit-12, Zone-5 055/2326/7905/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/8944,Storm Water Drain,Completed,NE-ROYAPURAM,51,12900,"Improvement and Minor Repairs of Existing of Storm Water Drain in East Cemetry Road, Old Washermanpet Div-51, Unit-12, Zone-5 SD/2332/363/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8945,Storm Water Drain,Completed,NE-ROYAPURAM,51,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in West Cemetry Road, Old Washermanpet Div-51, Unit-12, Zone-5 SD/2315/364/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8946,Storm Water Drain,Completed,NE-ROYAPURAM,51,11500,"Improvement and Minor Repairs of Existing of Storm Water Drain in Narayanappan Street Div-51, Unit-12, Zone-5 055/2318/7906/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/8947,Storm Water Drain,Completed,NE-ROYAPURAM,51,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Ramanujam street, Old washermanpet Div-51, Unit-12, Zone-5 SD/2289/359/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8948,Storm Water Drain,Completed,NE-ROYAPURAM,51,23100,"Improvement and Minor Repairs of Existing of Storm Water Drain in N.N.Garden 8th street, Old washermanpet Div-51, Unit-12, Zone-5 055/2299/7904/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/8950,Storm Water Drain,Completed,NE-ROYAPURAM,51,42000,"Improvement and Minor Repairs of Existing of Storm Water Drain in Cemetry Road, Old Washerman pet Div-51, Unit-12, Zone-5 053/2334/1995/2013-14",Own Sources,5,2017-18,2017-18 BR/2017-18/13668,Roads,Completed,BR-Bus Route Roads,52,995000,Providing speed breakers at various bus route roads in Zone 4,Own Sources,5,2017-18,2018-19 BR/2017-18/14657,Roads,Completed,BR-Bus Route Roads,52,950000,"Attending patches / worn out portion at SN Chetty street, North terminal road ( near royapuram old bridge) in Dn-52, Zone-5",Own Sources,5,2017-18,2018-19 BR/2017-18/14661,Roads,Completed,BR-Bus Route Roads,52,2386000,Traffic Improvement Work at Various Bus Route Roads in Zone - V & VI,Own Sources,5,2017-18,2020-21 BR/2017-18/15158,Roads,Completed,BR-Bus Route Roads,52,920000,Attending patches / worn out portion at SN Chetty street (Royapuram old bridge) in Dn 52 in Zone 5,Deposit Works,5,2017-18,2018-19 BR/2017-18/15159,Roads,Completed,BR-Bus Route Roads,52,930000,Attending patches / worn out portion at SN Chetty street (Royapuram old bridge) and ibrahim street in Dn 52 and Dn-61 in Zone 5,Deposit Works,5,2017-18,2018-19 BR/2017-18/1759,Roads,Completed,BR-Bus Route Roads,52,136000,"Removing and refixing of 1 no of modern Bus shelter Bus shelter at Stanley medical college and Hospital ( Old Jail Road) in Dn-52, Zone-5",Own Sources,5,2017-18,2018-19 BR/2017-18/9692,Roads,Completed,BR-Bus Route Roads,52,2390000,Traffic diversion work due to NRT Bridge demolition in Royapuram (Dn-52 and Dn-60) Zone-5,Deposit Works,5,2017-18,2018-19 L/2017-18/0403,Electrical,Completed,L-Electrical,52,1035800,Proposed street light re-arrangement and cable laying for modification to road over bridge at Royapuram near NRT Road in Dn 52 & 60 Zone - 5 (Metropolitan Transport Project) (Railways )).,Deposit Works,5,2017-18,2018-19 L/2017-18/10173,Electrical,Completed,L-Electrical,52,144800,Repairing and replacing of steel rope and wire in 2 nos of 30 mtrs Highmasts at Secretariate Park and Parking area in Div - 60 in Zone - 5,Own Sources,5,2017-18,2019-20 L/2017-18/10176,Electrical,Completed,L-Electrical,52,822500,Removal of 30 mtrs Highmast from NRT Road Park and and Reerrection at Play ground in Div - 52 in Zone - 5,Own Sources,5,2017-18,2018-19 L/2017-18/9804,Electrical,Completed,L-Electrical,52,2001800,"Supply and erection of 45 nos 7 mtrs GI Lamp posts with single straight bracket with 90-120 watts LED fittings at NRT Bridge in Div-52, Zone - 5.",Deposit Works,5,2017-18,2018-19 NE/2017-18/12634,Buildings,Completed,NE-ROYAPURAM,52,30000,"Repairs and Maintance to Public Conveniences M.S koil Street in Ward-52, Unit-12, Zone-5 033/2341/529/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/12640,Buildings,Completed,NE-ROYAPURAM,52,176000,"Repairs and Maintance to Public Convenience M.C road Vanaga Valagam in Ward-52, Unit-12, Zone-5 B/2270/245/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/12652,Roads,Completed,NE-ROYAPURAM,52,142000,"Repairs and Maintance to Public Convenience Dhobikhana at Meenakashmi ammanpet in Ward-52, Unit-12, Zone-5 033/15327/554/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/12655,Buildings,Completed,NE-ROYAPURAM,52,315000,"Repairs and Maintance to Public Convenience O.S.H road in Ward-52, Unit-12, Zone-5 033/2380/535/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/12656,Roads,Completed,NE-ROYAPURAM,52,54200,"Repairs and Maintance to Public Convenience O.S.H road ( Jn of M.C road) in Ward-52, Unit-12, Zone-5 033/2380/536/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/12659,Buildings,Completed,NE-ROYAPURAM,52,215000,"Repairs and Maintance to Public Convenience Modal Lane 9th lane in Ward-52, Unit-12, Zone-5 033/2384/1026/2015-16",Own Sources,5,2017-18,2018-19 NE/2017-18/15526,Parks,Completed,P-Parks and Playfields,52,5273000,"TREES SAPLING PLANTING AND ONE YEAR MAINTENANCE AT VARIOUS STREET AND ROAD IN DIV-49 TO 63 UNIT-12,13,14 ZONE-5",Own Sources,5,2017-18,2020-21 NE/2017-18/16678,Roads,Completed,NE-ROYAPURAM,52,154000,"Repairs and maintenance Existing of Speed breaker M.C road (Near Stanly hospital E toilet) at Ward-52, Unit-12, Zone -5 044/2270/17680/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/16679,Buildings,Completed,NE-ROYAPURAM,52,83000,"Repairs and maintenance Existing of Speed breaker M.C road (Near Division Office-52) at Ward-52, Unit-12, Zone -5 044/2270/17680/2013-14",Own Sources,5,2017-18,2019-20 NE/2017-18/2033,Roads,Completed,NE-ROYAPURAM,52,522000,"ATTANDING CEMENT CONCRETE PATCH WORK AT MODEL LINE 1ST LANE,2ND LANE,3RDLANE,5TH LANE,9TH LANE AND 10TH LANE IN DN 52,ZONE 5",Own Sources,5,2017-18,2021-22 NE/2017-18/2534,Storm Water Drain,Completed,NE-ROYAPURAM,52,29300,"Desilting of Storm water drain in Cemetry Road in Div 52,Unit 12,Zone 5. 055/2250/4915/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2545/C,Storm Water Drain,Completed,NE-ROYAPURAM,52,6500,"Desilting of Storm water drain in Jaganathan Street in Div 52,Unit 12,Zone 5. 055/2274/4912/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2546,Storm Water Drain,Completed,NE-ROYAPURAM,52,7700,"Desilting of Storm water drain in Andiyappan Street in Div 52,Unit 12,Zone 5. 055/2280/4916/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2547,Storm Water Drain,Completed,NE-ROYAPURAM,52,12600,"Desilting of Storm water drain in Munusamy garden 3rd Street in Div 52,Unit 12,Zone 5. 055/2269/4918/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2549,Storm Water Drain,Completed,NE-ROYAPURAM,52,3390,"Desilting of Storm Water Drain in Velayutha Pandi Street in Div 52,Unit 12,Zone 5. 055/2275/4911/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2550,Storm Water Drain,Completed,NE-ROYAPURAM,52,10500,"Desilting of Storm Water Drain in Pitchandi Lane in Div 52,Unit 12,Zone 5. 055/2266/4913/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2551,Storm Water Drain,Completed,NE-ROYAPURAM,52,7700,"Desilting of Storm Water Drain in Cemetry Lane in Div 52,Unit 12,Zone 5. 055/2362/8017/2015-16",Own Sources,5,2017-18,2017-18 NE/2017-18/2552,Storm Water Drain,Completed,NE-ROYAPURAM,52,10400,"Desilting of Storm Water Drain in M.S.Koil Street in Div 52,Unit 12,Zone 5. 055/2341/4909/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2557,Storm Water Drain,Completed,NE-ROYAPURAM,52,8100,"Desilting of Storm Water Drain in Model Line 5th Street in Div 52,Unit 12,Zone 5. 055/2351/4907/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2558,Storm Water Drain,Completed,NE-ROYAPURAM,52,9700,"Desilting of Storm Water Drain in Model Line 9th Street in Div 52,Unit 12,Zone 5. 055/2384/4908/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/2559,Storm Water Drain,Completed,NE-ROYAPURAM,52,36300,"Desilting of Storm Water Drain in MC Road (Service Road ) in Div 52,Unit 12,Zone 5. 055/15327/4757/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/5680,Roads,Completed,NE-ROYAPURAM,52,102000,"Improvement to CC road at Thoppai Street in Ward-52, Unit-12, Zone-5 044/2399/17667/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/5688,Roads,Completed,NE-ROYAPURAM,52,968000,"Improvement to B.T road at Raman Street in Ward-52, Unit-12, Zone-5 044/2404/17669/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/7052,Buildings,Completed,NE-ROYAPURAM,52,30000,"RPOVIDING WATER SUPPLY ARRANGEMENTS TO E TOILET AT M.C.ROAD IN DN 52,UNIT 12,ZONE 5",Own Sources,5,2017-18,2021-22 NE/2017-18/7053,Buildings,Completed,NE-ROYAPURAM,52,369000,"REPAIRS AND IMPROVEMENTS TO ICDS & PUBLIC TOILET BUILDING AT VARIOUS STREETS IN DN 52,UNIT 12,ZONE 5",Own Sources,5,2017-18,2021-22 NE/2017-18/8925,Storm Water Drain,Completed,NE-ROYAPURAM,52,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Andiyappan Street Div-52, Unit-12, Zone-5 055/2280/4916/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8926,Storm Water Drain,Completed,NE-ROYAPURAM,52,5700,"Improvement and Minor Repairs of Existing of Storm Water Drain in Pitchandi lane Div-52, Unit-12, Zone-5 055/2266/4913/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8927,Storm Water Drain,Completed,NE-ROYAPURAM,52,20200,"Improvement and Minor Repairs of Existing of Storm Water Drain in Cemetry Road Div-52, Unit-12, Zone-5 055/2250/4915/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8928,Storm Water Drain,Completed,NE-ROYAPURAM,52,17300,"Improvement and Minor Repairs of Existing of Storm Water Drain in Jaganathan street Div-52, Unit-12, Zone-5 055/2274/4912/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8929,Storm Water Drain,Completed,NE-ROYAPURAM,52,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in O.S.H. Road Div-52, Unit-12, Zone-5 055/2380/4906/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8930,Storm Water Drain,Completed,NE-ROYAPURAM,52,5700,"Improvement and Minor Repairs of Existing of Storm Water Drain in M.S.Koil street Div-52, Unit-12, Zone-5 055/2341/4909/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8931,Storm Water Drain,Completed,NE-ROYAPURAM,52,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Cemetry Lane Div-52, Unit-12, Zone-5 055/2362/8017/2015-16",Own Sources,5,2017-18,2018-19 NE/2017-18/8932,Storm Water Drain,Completed,NE-ROYAPURAM,52,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in Model line 5th street Div-52, Unit-12, Zone-5 055/2351/4907/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8933,Storm Water Drain,Completed,NE-ROYAPURAM,52,5700,"Improvement and Minor Repairs of Existing of Storm Water Drain in Velayudha pandi street Div-52, Unit-12, Zone-5 055/2275/4911/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8935,Storm Water Drain,Completed,NE-ROYAPURAM,52,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain in Munusamy garden 3rd street Div-52, Unit-12, Zone-5 055/2269/4918/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8936,Storm Water Drain,Completed,NE-ROYAPURAM,52,11500,"Improvement and Minor Repairs of Existing of Storm Water Drain in Rope Godown street Div-52, Unit-12, Zone-5 055/15595/4917/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8937,Storm Water Drain,Completed,NE-ROYAPURAM,52,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain in MC Road (Service Road) Div-52, Unit-12, Zone-5 055/15327/4757/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8938,Storm Water Drain,Completed,NE-ROYAPURAM,52,14400,"Improvement and Minor Repairs of Existing of Storm water Drain in Model Line 9th street Div-52, Unit-12, Zone-5 055/2384/4908/2013-14",Own Sources,5,2017-18,2018-19 BR/2017-18/0060,Road Cut,Completed,BR-Bus Route Roads,53,2490000,Restoration of Road cut at Cochraine Basin Road made byTRANTRANSCO - From Anandanayak nagar 1 st street to Meenambal nagar 1 st street in Division -53 Zone - 5,Deposit Works,5,2017-18,2017-18 BR/2017-18/17209,Roads,Completed,BR-Bus Route Roads,53,990000,"Restoration of road cut made by CMWSSB at CB Road in Dn-53, Zone-V against Challan No. BR/2017-18/0029358..",Deposit Works,5,2017-18,2019-20 BR/2017-18/17213,Roads,Completed,BR-Bus Route Roads,53,2430000,"Restoration of road cut made by CMWSSB at Kannan street Dn-53, Zone-V against Challan No. BR/2017-18/0029358.",Deposit Works,5,2017-18,2019-20 L/2017-18/0399,Electrical,Completed,L-Electrical,53,810600,Supply and Erection of 22 nos of 7 mtrs GI Lamp posts with single straight bracket with 40 watts LED fittings at Woodwarf Road in Div 53 in Zone V,Own Sources,5,2017-18,2018-19 L/2017-18/10375,Electrical,Completed,L-Electrical,53,409100,"Provision of Electrification at Smart Class Wiring Proposed for Three classes at Div -53 CUGMS Lalakunda Street, Div - 58 CGHSS Roter Street and Div - 60 Angappa Naicken Street in Zone - 5.",Own Sources,5,2017-18,2018-19 L/2017-18/7069,Electrical,Completed,L-Electrical,53,1155700,SUPPLY AND LAYING OD DAMAGED 2508 MTRS OF 2 X 16 SQMM ALU CABLE AND 301 MTRS 4 X 16 SQMM ALU CABLE AT VARIOUS LOCATIONS IN DIV 53 IN ZONE V.,Own Sources,5,2017-18,2018-19 NE/2017-18/0910,Roads,Completed,NE-ROYAPURAM,53,595000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT SRINIVASAPURAM P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/0912,Roads,Completed,NE-ROYAPURAM,53,595000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT C B ROAD P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/0913,Roads,Completed,NE-ROYAPURAM,53,595000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT CANAL ROAD STANLEY NAGAR 5 TH STREET P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/0915,Roads,Completed,NE-ROYAPURAM,53,595000,"PROVIDING ANNUAL MAINTENANCE OF HOUSE KEEPING LABOURS AND SECURITY AT BOJARAJAN NAGAR P C IN DN-53, UNIT-12 ,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/10227,Buildings,Completed,NE-ROYAPURAM,53,142000,"REPAIRS AND ANNUAL MAINTENANCE OF BOILER AT RELIEF CENTRE IN BASIN BRIDGE, DIVISION-53, UNIT-13, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/1167,Roads,Completed,NE-ROYAPURAM,53,744000,"Procurement of Bio - shredding Machine, Sieving machine, Tri- cycle bullet tyre, Ordinary Tri- cycle, Electronic weighing machine,Various Street in Ward-53 Unit-12, Zone-5",Own Sources,5,2017-18,2018-19 NE/2017-18/14069,Buildings,Completed,NE-ROYAPURAM,53,665000,"PROVIDING GYM APPARATUS IN GYM AT PADAVATTAMMAN KOIL STREET IN DN-53, UNIT-12, ZONE-5",MLACDS,5,2017-18,2018-19 NE/2017-18/15351,Buildings,Completed,NE-ROYAPURAM,53,2445000,"Newly construction of GYM Building at Pattavatamman Koil Steet in Div-53, Unit-12, Zone-5",MLACDS,5,2017-18,2018-19 NE/2017-18/16684,Roads,Completed,NE-ROYAPURAM,53,163000,"Repairs and maintenance Existing of Speed breaker Kathpada Main road (For 7 location) at Ward-53, Unit-12, Zone- 5 044/2806/27569/2014-15",Own Sources,5,2017-18,2019-20 NE/2017-18/3482,Buildings,Completed,NE-ROYAPURAM,53,130000,"Improvement to Community Toilet at Pensioners 3rd Street in dn-53, Unit-12, Zone-05 044/19442/27568/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/3492,Buildings,Completed,NE-ROYAPURAM,53,108000,"Improvement to Community Toilet at Kannan street in Dn-53, Unit-12, Zone-5 153/1937/731/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/3496,Buildings,Completed,NE-ROYAPURAM,53,103600,"Improvement to Community Toilet at Kathbada Main Road(NEAR FISH MARKET) in Dn-53, Unit-12, Zone-5 156/2806/467/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/3500,Buildings,Completed,NE-ROYAPURAM,53,100000,"Improvement to Community Toilet at P.P. AMMAN KOIL 4th STREET in Dn-53, Unit-12, Zone-5 044/2795/27598/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/5415,Roads,Completed,NE-ROYAPURAM,53,830000,"Improvement to B.T road at New Pensioners 3rd & 4th Cross Street in Div-53, Unit-12, Zone-5 Asset Code- 040/2765/3774/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5420,Roads,Completed,NE-ROYAPURAM,53,830000,"Improvement to B.T road at New Pensioners 1st & 2nd Cross Street in Div-53, Unit-12, Zone-5 (Asset Code- 040/2765/3774/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5430,Roads,Completed,NE-ROYAPURAM,53,1591000,"Improvement to B.T road) in A M Ghouse Street, Div-53, Unit-12, Zone-5 (Asset Code- 044/1943/24234/2014-15)",Own Sources,5,2017-18,2019-20 NE/2017-18/5476,Roads,Completed,NE-ROYAPURAM,53,493000,"Improvement to C.C road in Chidambaram Nagar 5th Street in Div-53, Unit-12, Zone-5 (Asset- 044/2786/27579/2014-15)",Own Sources,5,2017-18,2018-19 NE/2017-18/5483,Roads,Completed,NE-ROYAPURAM,53,564000,"Improvement to C.C road in Chidambaram Nagar 5th Cross Street in Div-53, Unit-12, Zone-5(Asset code- 044/2786/27579/2014-15)",Own Sources,5,2017-18,2018-19 NE/2017-18/5489,Roads,Completed,NE-ROYAPURAM,53,493000,"Improvement to (C.C. Road) in Chidambaram Nagar 6th Street Div-53, Unit-12, Zone-5 (Asset code- 044/2785/27580/2014-15)",Own Sources,5,2017-18,2018-19 NE/2017-18/5505,Roads,Completed,NE-ROYAPURAM,53,3880000,"Improvement to B.T road in S M Chetty Street in Dn-53, Unit-12, Zone-5 (Asset Code- 040/1967/9700/2014-15)",Own Sources,5,2017-18,2019-20 NE/2017-18/6217,Storm Water Drain,Completed,NE-ROYAPURAM,53,20900,"Desiliting of Storm water drain in Parthasarathy Service Road in Ward-53, Unit-12, Zone-5 043/1938/1185/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6219,Storm Water Drain,Completed,NE-ROYAPURAM,53,20900,"Desilting of Storm water drain in Pensioners 3rd Street in Ward-53, Unit-12, Zone-5 044/19442/27568/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6224,Storm Water Drain,Completed,NE-ROYAPURAM,53,10300,"Desilting of Storm water drain in Pensioners 4th Street in Ward-53, Unit-12, Zone-5 044/19442/27568/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6225,Storm Water Drain,Completed,NE-ROYAPURAM,53,30900,"Desiliting of Storm water at Kathbada Main Road in Ward-53, Unit-12, Zone-5 055/2806/3188/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6226,Storm Water Drain,Completed,NE-ROYAPURAM,53,61900,"Desilting of Storm water drain at Basin Bridge Road in Ward-53, Unit-12, Zone-5 044/19443/22816/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6227,Storm Water Drain,Completed,NE-ROYAPURAM,53,24400,"Desilting of Storm water drain at C.B. Road in Ward-53, Unit-12, Zone-5 044/2791/26651/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6228,Storm Water Drain,Completed,NE-ROYAPURAM,53,4420,"Desilting of Storm water drain at Padavattamman Koil Street in Ward-53, Unit-12, Zone-5 043/2758/482/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6229,Storm Water Drain,Completed,NE-ROYAPURAM,53,17500,"Desilting of Storm water drain at Peddu (N) Street in Ward-53, Unit-12, Zone-5 055/2778/5866/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6230,Storm Water Drain,Completed,NE-ROYAPURAM,53,10600,"Desilting of Storm water drain at V.O.C. Salai in Ward-53, Unit-12, Zone-5 055/2775/3191/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6231,Storm Water Drain,Completed,NE-ROYAPURAM,53,27800,"Desilting of Storm water drain at North Wall Road in Ward-53, Unit-12, Zone-5 055/2760/4771/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6232,Storm Water Drain,Completed,NE-ROYAPURAM,53,11600,"Desilting of Storm water drain at Stanly Nagar 4th Street in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/6233,Storm Water Drain,Completed,NE-ROYAPURAM,53,5600,"Desilting of Storm water drain at Stanly Nagar 5th Street in Ward-53, Unit-12, Zone-5 055/2770/4780/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6234,Storm Water Drain,Completed,NE-ROYAPURAM,53,14000,"Desilting of Storm water drain at Stanly Nagar 6th Street in Ward-53, Unit-12, Zone-5 040/2769/9696/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6236,Storm Water Drain,Completed,NE-ROYAPURAM,53,20900,"Desilting of Storm water drain at Inside ITI ( Kadpada main road ) in Ward-53, Unit-12, Zone-5 055/2806/3188/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6238,Storm Water Drain,Completed,NE-ROYAPURAM,53,19600,"Desilting of Storm water drain at P.P. Amman Koil East Street in Ward-53, Unit-12, Zone-5 044/2780/27593/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6240,Storm Water Drain,Completed,NE-ROYAPURAM,53,18100,"Desilting of Storm water drain at P.P. Amman Koil 1st Lane in Ward-53, Unit-12, Zone-5 044/2798/27595/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6241,Storm Water Drain,Completed,NE-ROYAPURAM,53,31400,"Desilting of Storm water drain at NN Nagar in Ward-53, Unit-12, Zone-5 040/2740/9778/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6242,Storm Water Drain,Completed,NE-ROYAPURAM,53,18500,"Desilting of Storm water drain at KANNAN STREET(S.NO.1-12) in Ward-53, Unit-12, Zone-5 055/1928/7457/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6244,Storm Water Drain,Completed,NE-ROYAPURAM,53,23000,"Desilting of Storm water drain at SRINIVASAPURAM 1ST STREET in Ward-53, Unit-12, Zone-5 055/1928/7457/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6246,Storm Water Drain,Completed,NE-ROYAPURAM,53,44200,"Desilting of Storm water drain at DR. VIJAYARAGAVALU SALAI in Ward-53, Unit-12, Zone-5 055/1938/3190/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6248,Storm Water Drain,Completed,NE-ROYAPURAM,53,14700,"Desilting of Storm water drain at PARASURAM MUDALI STREET in Ward-53, Unit-12, Zone-5 055/1930/7203/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6250,Storm Water Drain,Completed,NE-ROYAPURAM,53,6900,"Desilting of Storm water drain at AZEEZ GOUSE MOHAMMED GOUS STREET in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/6251,Storm Water Drain,Completed,NE-ROYAPURAM,53,9700,"Desilting of Storm water drain at SAJA MUNUSAMY CHETTY STREET(S.NO.64-126) in Ward-53, Unit-12, Zone-5 055/1967/7202/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6253,Storm Water Drain,Completed,NE-ROYAPURAM,53,7600,"Desilting of Storm water drain at THIRUVETRIYUR HIGH ROAD ( DOOR NO..409-454 ) in Ward-53, Unit-12, Zone-5 153/2767/397/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6255,Storm Water Drain,Completed,NE-ROYAPURAM,53,21200,"Desilting of Storm water drain at BOJARAJA NAGAR MAIN STREET in Ward-53, Unit-12, Zone-5 055/1941/6442/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6257,Storm Water Drain,Completed,NE-ROYAPURAM,53,11000,"Desilting of Storm water drain at BOJARAJA NAGAR 1st STREET in Ward-53, Unit-12, Zone-5 040/1944/9766/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6258,Storm Water Drain,Completed,NE-ROYAPURAM,53,19600,"Desilting of Storm water drain at BOJARAJA NAGAR 2nd STREET in Ward-53, Unit-12, Zone-5 040/1942/9768/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6260,Storm Water Drain,Completed,NE-ROYAPURAM,53,8200,"Desilting of Storm water drain at BOJARAJA NAGAR SOUTH LANE in Ward-53, Unit-12, Zone-5 040/1986/9774/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9395,Storm Water Drain,Completed,NE-ROYAPURAM,53,17300,"Improvement and Minor Repairs of Existing of Storm Water Drain in Pensioner 3rd Street In ward-53, Unit-12, Zone-5 044/19442/27568/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9396,Storm Water Drain,Completed,NE-ROYAPURAM,53,17300,"Improvement and Minor Repairs of Existing of Storm Water Drain in Parthasarathy service road In ward-53, Unit-12, Zone-5 044/2759/27567/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9397,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain in P.P.Amman koil 1st lane In ward-53, Unit-12, Zone-5 044/2798/27595/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9398,Storm Water Drain,Completed,NE-ROYAPURAM,53,23100,"Improvement and Minor Repairs of Existing of Storm Water Drain in P.P.Amman koil East Street In ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9399,Storm Water Drain,Completed,NE-ROYAPURAM,53,11500,"Improvement and Minor Repairs of Existing of Storm Water Drain at N.N Nagar In ward-53, Unit-12, Zone-5 040/2740/9778/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9400,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain at Kannan Street In ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9404,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existingof Storm Water Drain at Srinivasapuram 1st street in Ward-53, Unit-12, Zone-5 040/1987/9775/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9405,Storm Water Drain,Completed,NE-ROYAPURAM,53,5700,"Improvement and Minor Repairs of Existingof Storm Water Drain at Dr.Vijayaragavalu salai in Ward-53, Unit-12, Zone-5 055/1938/3190/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/9406,Storm Water Drain,Completed,NE-ROYAPURAM,53,11500,"Improvement and Minor Repairs of Existingof Storm Water Drain at Parasuram Mudali street in Ward-53, Unit-12, Zone-5 055/1930/7203/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9407,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existingof Storm Water Drain at Azeez Gouse Mohammed Gous street in Ward-53, Unit-12, Zone-5 044/1943/24234/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9408,Storm Water Drain,Completed,NE-ROYAPURAM,53,5700,"Improvement and Minor Repairs of Existing of Storm Water Drain at Saja Munusamy street (S.No.64-126 in Ward-53, Unit-12, Zone-5 055/1967/7202/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9409,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain at Thiruvetriyur Road (Door No.409-454) in Ward-53, Unit-12, Zone-5 053/2767/1976/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/9410,Storm Water Drain,Completed,NE-ROYAPURAM,53,11500,"Improvement and Minor Repairs of Existing of Storm Water Drain at Bojaraja Nagar 1st street in Ward-53, Unit-12, Zone-5 040/1944/9766/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9411,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain at Bojaraja Nagar Main street in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9412,Storm Water Drain,Completed,NE-ROYAPURAM,53,11500,"Improvement and Minor Repairs of Existing of Storm Water Drain at Bojaraja Nagar 2nd street in Ward-53, Unit-12, Zone-5 040/1942/9768/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9413,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain at Bojaraja Nagar South Lane in Ward-53, Unit-12, Zone-5 040/1986/9774/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9414,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain at inside ITI (Kathbada main road) in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9415,Storm Water Drain,Completed,NE-ROYAPURAM,53,5700,"Improvement and Minor Repairs of Existing of Storm Water Drain at Stanley Nagar 6th street in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9416,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain at Stanley Nagar 5th street in Ward-53, Unit-12, Zone-5 055/2770/4780/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/9417,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain at Stanley Nagar 4th street in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9418,Storm Water Drain,Completed,NE-ROYAPURAM,53,34700,"Improvement and Minor Repairs of Existing of Storm Water Drain at North wall road in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9419,Storm Water Drain,Completed,NE-ROYAPURAM,53,17300,"Improvement and Minor Repairs of Existing of Storm Water Drain at VOC Salai in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9420,Storm Water Drain,Completed,NE-ROYAPURAM,53,17300,"Improvement and Minor Repairs of Existing of Storm Water Drain at Peddu (N) street in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9421,Storm Water Drain,Completed,NE-ROYAPURAM,53,8600,"Improvement and Minor Repairs of Existing of Storm Water Drain at Padavattamman koil street in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9422,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain at C.B Road in Ward-53, Unit-12, Zone-5 044/2791/26651/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/9424,Storm Water Drain,Completed,NE-ROYAPURAM,53,28900,"Improvement and Minor Repairs of Existing of Storm Water Drain at Basin Bridge Road in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9425,Storm Water Drain,Completed,NE-ROYAPURAM,53,23100,"Improvement and Minor Repairs of Existing of Storm Water Drain at Kathbada main road in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9426,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvement and Minor Repairs of Existing of Storm Water Drain at pensioners 4th street in Ward-53, Unit-12, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/9995,Roads,Completed,NE-ROYAPURAM,53,410000,ATTENDING THE URGENT REPAIR WORK AND FLOODRELATED WORK AT VARIOUS STREET IN DN-53 U-12 Z-5,Own Sources,5,2017-18,2018-19 D/2017-18/12424,Storm Water Drain,Completed,D-Storm Water Drains,54,2500000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Amman koil street from Chakkarai street to Lawyer Chinnathambi street in Dn- 54, Zone- V.",Own Sources,5,2017-18,2018-19 D/2017-18/12425,Storm Water Drain,Completed,D-Storm Water Drains,54,2393000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Amman koil street from Lawyer Chinnathambi street to Nammalwar street in Dn- 54, Zone- V.",Own Sources,5,2017-18,2019-20 D/2017-18/12436,Storm Water Drain,Completed,D-Storm Water Drains,54,2500000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Chakkarai street from junction of Amman koil street to Rivermill street in Dn- 54, Zone- V.",Own Sources,5,2017-18,2018-19 D/2017-18/12488,Storm Water Drain,Completed,D-Storm Water Drains,54,2306000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Amman koil street from Waltax road to junction of Chakkarai street in Dn 54, Zone 5.",Own Sources,5,2017-18,2018-19 D/2017-18/12492,Storm Water Drain,Completed,D-Storm Water Drains,54,2103000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Chakkarai street from junction of Rivermill street to Telegraph Abboy lane in Dn- 54, Zone- V.",Own Sources,5,2017-18,2018-19 D/2017-18/12493,Storm Water Drain,Completed,D-Storm Water Drains,54,2308000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Peddu street from junction of Waltax road to Padavattamman koil street junction in Dn-54, Zone- V.",Own Sources,5,2017-18,2018-19 D/2017-18/12494,Storm Water Drain,Completed,D-Storm Water Drains,54,1899000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Peddu street from junction of Padavattamman koil street to junction of Sabapathi street in Dn- 54, Zone- V.",Own Sources,5,2017-18,2018-19 D/2017-18/12495,Storm Water Drain,Completed,D-Storm Water Drains,54,2308000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Sabapathi street from Peddu street to Telegraph Abboy street Dn- 54, Zone- V.",Own Sources,5,2017-18,2018-19 D/2017-18/12497,Storm Water Drain,Completed,D-Storm Water Drains,54,2099000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Thirrupalli street from junction of Waltax road to Venkatesan street in Dn- 54, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/12498,Storm Water Drain,Completed,D-Storm Water Drains,54,2490000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Thirrupalli street from junction of Venkatesan street to Vadamalai street in Dn- 54, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/7005,Storm Water Drain,Completed,D-Storm Water Drains,54,990000,"Removal of Hyacinth and Floating Materials in North Buckingham canal from Railway track culvert to Elephant Gate road(100m) and from Elephant gate road to 150.00m chainage in Dn 54, Zone - 5",Own Sources,5,2017-18,2018-19 L/2017-18/7070,Electrical,Completed,L-Electrical,54,193700,SUPPLY AND LAYING OF DAMAGED 452 MTRS OF 4 X 16 SQMM ALU CABLE AT MINT STREET FROM THATHA MUTHIYAPPAN STREET TO AMMAN KOIL STREET IN DIV 54 IN ZONE V.,Own Sources,5,2017-18,2019-20 NE/2017-18/0601,Roads,Completed,NE-ROYAPURAM,54,2100000,"LAYING CC ROAD AT TEYNAMPET RAMASAMY STREET IN DN-54, U-13, Z-5. (MLA FUND)",MLACDS,5,2017-18,2018-19 NE/2017-18/0865,Buildings,Completed,NE-ROYAPURAM,54,890000,"CONSTRUCTION OF WELL RING COMPOST YARD AT VARIOUS STREET IN UNIT-13 (DN-54 TO 58&60), Z-5",Own Sources,5,2017-18,2018-19 NE/2017-18/11155,Buildings,Completed,NE-ROYAPURAM,54,630000,"DEMOLITION OF DANGEROUS BUILDINGS( CI AND SI OFFICE BUILDINGS) AT VADAMALAI MEISTRY STREET IN DN-54, UNIT-13, ZONE-05 (ASSET CODE-014/4001/104/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/12759,Buildings,Completed,NE-ROYAPURAM,54,2200000,"CONSTRUCTION OF PUBLIC CONVENIENCE AT PERUMAL KOIL GARDEN 3RD LANE IN DIVISION-54, UNIT-13, ZONE-05 ( ASSET CODE -033/4016/491/2013-14)",MPLADS,5,2017-18,2018-19 NE/2017-18/1457,Parks,Completed,NE-ROYAPURAM,54,2550000,"PROVIIDNG FOOTPATH FORMATION AT SIVAGNANAM PARK AT DN-54, UNIT-13, ZONE-05",MLACDS,5,2017-18,2018-19 NE/2017-18/1458,Parks,Completed,NE-ROYAPURAM,54,2600000,"PROVIDING SUMP WORKS, SKATING GROUND WORKS, AND PLAY APPARATUS AT SIVAGNANAM PARK IN DN-54, UNIT-13, ZONE-05",MLACDS,5,2017-18,2018-19 NE/2017-18/5961,Roads,Completed,NE-ROYAPURAM,54,529000,"Improvement to CC Road at Ayular Muhtiya street in Ward-54, Unit-13, Zone-5 (ASSET CODE- 044/2440/16289/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5989,Roads,Completed,NE-ROYAPURAM,54,212000,"Improvement to CC Road at Amman Koil 2nd street in Ward-54, Unit-13, Zone-5 (Asset Code- 040/3990/5639/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/5998,Roads,Completed,NE-ROYAPURAM,54,535000,"Improvement to CC Road at Nallanan Street in Ward-54, Unit-13, Zone-5 (Aseet Code- 040/4029/5678/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/6005,Roads,Completed,NE-ROYAPURAM,54,494000,"Restoration of Road cut made by CMWSSB at Subraya Pillai Street in Ward-54, Unit-13, Zone-5 (Asset Code- 044/2416/16284/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/6009,Roads,Completed,NE-ROYAPURAM,54,529000,"Improvement to CC Road at Arunachalam Street in Ward-54, Unit-13, Zone-5 (Asset code- 040/4006/5671/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/6010,Roads,Completed,NE-ROYAPURAM,54,494000,"Improvement to CC Road at Thandavarayan Street in Ward-54, Unit-13, Zone-5 (Asset Code- 040/4026/5695/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/6013,Roads,Completed,NE-ROYAPURAM,54,847000,"Improvement to CC Road at P.K.G. Main street in Ward-54, Unit-13, Zone-5 (Asset Code- 040/4027/5679/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/6014,Roads,Completed,NE-ROYAPURAM,54,265000,"Improvement to CC Road at Anna Pillai 2nd Street in Ward-54, Unit-13, Zone-5",Own Sources,5,2017-18,2018-19 NE/2017-18/6017,Roads,Completed,NE-ROYAPURAM,54,600000,"Improvement to CC Road at P.K.G 6th Lane in Ward-54, Unit-13, Zone-5 (Asset Code- 039/4013/247/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/6019,Roads,Completed,NE-ROYAPURAM,54,776000,"Improvement to CC Road at P.K.G 5th Lane in Ward-54, Unit-13, Zone-5 (Asset Code- 040/4015/5704/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/6022,Roads,Completed,NE-ROYAPURAM,54,564000,"Improvement to CC Road at P.K.G 4th Lane in Ward-54, Unit-13, Zone-5 Asset Code 040/4015/5704/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/6024,Roads,Completed,NE-ROYAPURAM,54,669000,"Improvement to CC Road at P.K.G 2nd Lane in Ward-54, Unit-13, Zone-5 (Asset Code- 040/4017/5702/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/6030,Roads,Completed,NE-ROYAPURAM,54,671000,"Improvement to CC Road at P.K.G 1st Lane in Ward-54, Unit-13, Zone-5 Asset Code-040/4017/5702/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/6038,Roads,Completed,NE-ROYAPURAM,54,811000,"Improvement to CC Road at Muniyappan street in Ward-54, Unit-13, Zone-5 (Asset code- 044/2427/16258/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/6113,Buildings,Completed,NE-ROYAPURAM,54,819000,"CONSTRUCTION OF AMMA KUDINEER PLANT CIVIL WORK AT VOC SALAI NEAR THIRUPALLI BUS STOP,SOWKARPETTAI IN DIV-54,U-13,Z-05",Own Sources,5,2017-18,2018-19 NE/2017-18/6436,Storm Water Drain,Completed,NE-ROYAPURAM,54,74100,"Improvements and Minor Repairs to Existing Strom Water Drain at Amman koil street in Dn-54, Unit-13, Zone-5 Asset Code: SD/3989/355/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6437,Storm Water Drain,Completed,NE-ROYAPURAM,54,75400,"Improvements and Minor Repairs to Existing Storm Water drain at Thirupalli Street in dn-54, Unit-13, Zone-5 Asset Code : SD/4024/358/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6438,Storm Water Drain,Completed,NE-ROYAPURAM,54,79800,"Improvements and Minor Repairs to Existing Storm Water Drain at Sundaram Street in Dn-54, Unit-13, Zone-5 Asset Code: SD/4000/357/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6439,Storm Water Drain,Completed,NE-ROYAPURAM,54,87600,"Improvements and Minor Repairs to Existing Storm Water Drain to Kancheepuram Sabapathy Street in Dn-54, Unit-13, Zone-5 Asset Code : SD/2442/354/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6440,Storm Water Drain,Completed,NE-ROYAPURAM,54,105000,"Improvements and Minor Repairs to Existing Storm Water Drain to Bhasyakaralu Street in Dn-54, Unit-13, Zone-5 Asset Code : SD/2441/353/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6441,Storm Water Drain,Completed,NE-ROYAPURAM,54,54600,"Improvements and Minor Repairs to Existing Storm Water Drain to Mint Street in Dn-54, Unit-13, Zone-5 Asset Code : SD/2430/351/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6442,Storm Water Drain,Completed,NE-ROYAPURAM,54,50400,"Improvements and Minor Repairs to Existing Storm Water Drain to Saravanan Street in Dn-54, Unit-13, Zone-5 Asset Code : SD/2418/352/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6443,Storm Water Drain,Completed,NE-ROYAPURAM,54,44500,"Improvements and Minor Repairs to Existing Storm Water Drain to Perumal Koil Garden 3rd and 4th Street in Dn-54, Unit-13, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/6444,Storm Water Drain,Completed,NE-ROYAPURAM,54,78600,"Improvements and Minor Repairs to Existing Storm Water Drain to VOC Salai in Dn-54, Unit-13, Zone-5",Own Sources,5,2017-18,2017-18 NE/2017-18/6936,Storm Water Drain,Completed,NE-ROYAPURAM,54,25600,"Improvements and Minor Repairs to Existing Storm Water Drain at Chakkarai Street in Div-54, Unit-13, Zone-5 Asset Code : SD/3988/356/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/7244,Roads,Completed,NE-ROYAPURAM,54,101000,"Repairs and Annual maintenance of Existing Speed breaker at Amman Koil Street in Ward-54, Unit-13, Zone-5 ( Asset Code-(R/3989/5953/2014-15)",Own Sources,5,2017-18,2019-20 NE/2017-18/7336,Roads,Completed,NE-ROYAPURAM,54,151000,"Repairs and Annual maintenance of Existing Speed Breaker at Peddu Street in Ward-54, Unit-13, Zone-5 (ASSET CODE- 044/2421/16103/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/7340,Roads,Completed,NE-ROYAPURAM,54,510000,"Attending cement concret road patches at various streets in Dn,54,55,56,57,60,Unit-13, Zone-5",Own Sources,5,2017-18,2019-20 NE/2017-18/8832,Storm Water Drain,Completed,NE-ROYAPURAM,54,87000,"Improvements and Minor repairs to Existing SWD at Chakkarai street. in Dn-54, Unit-13,Zone-5 (Asset Code- 044/3988/16297/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/8833,Storm Water Drain,Completed,NE-ROYAPURAM,54,76000,"Improvements and Minor repairs to Existing SWD at Mint Street in Dn-54, Unit-13,Zone-5, Asset Code- 044/3981/16059/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8834,Storm Water Drain,Completed,NE-ROYAPURAM,54,83000,"Improvements and Minor repairs to Existing SWD at Saravanan Street in Dn-54, Unit-13,Zone-5 (Asset Code- 044/2418/16107/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8835,Storm Water Drain,Completed,NE-ROYAPURAM,54,110000,"Improvements and Minor repairs to Existing SWD at Bhasyakaralu Street in Dn-54, Unit-13,Zone-5 Asset Code- 044/2441/16264/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8836,Storm Water Drain,Completed,NE-ROYAPURAM,54,127000,"Improvements and Minor repairs to Existing SWD at Kancheepuram sabapathy street in Dn-54, Unit-13,Zone-5 Asset Code- 055/2442/7075/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/8837,Storm Water Drain,Completed,NE-ROYAPURAM,54,116000,"Improvements and Minor repairs to Existing SWD at Amman koil street in Dn-54, Unit-13,Zone-5 Asset Code- 156/3989/1076/2014-15",Own Sources,5,2017-18,2018-19 NE/2017-18/8838,Storm Water Drain,Completed,NE-ROYAPURAM,54,134000,"Improvements and Minor repairs to Existing SWD at Thirupali street in Dn-54, Unit-13,Zone-5 Asset Code- 040/4024/5711/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8839,Storm Water Drain,Completed,NE-ROYAPURAM,54,72000,"Improvements and Minor repairs to Existing SWD at Perumal koil garden 3rd and 4th street in Dn-54, Unit-13,Zone-5 Asset Code- 040/4016/5703/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/8840,Storm Water Drain,Completed,NE-ROYAPURAM,54,120000,"Improvements and Minor repairs to Existing SWD at VOC salai in Dn-54, Unit-13,Zone-5 (Asset Code- 044/3973/16086/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/8841,Storm Water Drain,Completed,NE-ROYAPURAM,54,123000,"Improvements and Minor repairs to Existing SWD at Sundaram Street in Dn-54, Unit-13,Zone-5 ( Asset Code- 044/4000/16341/2013-14)",Own Sources,5,2017-18,2018-19 B/2017-18/7905,Buildings,Completed,B-Buildings,55,6151264,"CONSTRUCTION OF THREE CLASS ROOMS FOR CHENNAI MIDDLE SCHOOL AT PORTUGUESE CHRUCH STREET IN DN-55, ZONE 5.",MLACDS,5,2017-18,2019-20 BR/2017-18/11371,Roads,Completed,BR-Bus Route Roads,55,74000,Restoration of road cut made by CMWSSB at Prakasam salai in Zone-5 against challan no. BR/2017-18/0005726,Deposit Works,5,2017-18,2018-19 L/2017-18/7071,Electrical,Completed,L-Electrical,55,2018600,SUPPLY AND LAYING OD DAMAGED 4253 MTRS OF 2 X 16 SQMM ALU CABLE AND 691 MTRS 4 X 16 SQMM ALU CABLE AT VARIOUS LOCATIONS IN DIV 55 IN ZONE V.,Own Sources,5,2017-18,2019-20 NE/2017-18/0896,Roads,Completed,NE-ROYAPURAM,55,4700000,"LAYING CEMENT CONCRETE ROAD BY RMC 30 AT ACHARAPPAN STREET IN DN.55,UNIT - 13,ZONE-5 (BY MLA SCHEME 2017-18 FUND)",MLACDS,5,2017-18,2017-18 NE/2017-18/1176,Buildings,Completed,NE-ROYAPURAM,55,744000,"Procurement of Bio - shredding Machine,Sieving machine,Tri- cycle bullet tyre ,Ordinary Tri- cycle,Electronic weighing machine 500 KG capacity at Various Street in Unit-13, Zone-5",Own Sources,5,2017-18,2018-19 NE/2017-18/2717,Storm Water Drain,Completed,NE-ROYAPURAM,55,7400,"De-silting and Minor repairs to existing Storm Water Drain at St Xavier Street from jn of Seven Wells Street and Portuguese Church Street in Dn.55,Unit - 13,Zone - 5. ( Asset code- 055/2470/4701/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/2720,Storm Water Drain,Completed,NE-ROYAPURAM,55,14900,"De-silting and Minor repairs to Existing Storm Water Drain at Seven wells Street from Barracks Street to junc of Amman Koil Street in Dn.55, Unit-13, Zone-5. (Asset code-055/15615/4813/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/2726,Storm Water Drain,Completed,NE-ROYAPURAM,55,7400,"De-silting and Minor repairs to existing Existing Storm Water Drain at Aanaikara Konan Street from Seven Wells Street to junc of Poruguese Church Street in Dn.55, Unit-13, Zone-5. ( Asset Code-055/2456/4814/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/2727,Storm Water Drain,Completed,NE-ROYAPURAM,55,5900,"De-silting and Improvements to Existing Storm Water Drain at Giri Gory Street from jn of Barracks Street and Seven Wells Street in Dn.55,Unit - 13,Zone-5 .( Asset Code-055/2463/4815/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/2728,Storm Water Drain,Completed,NE-ROYAPURAM,55,10400,"De-silting and Improvement to Existing Storm Water Drain at Barracks Street from of Seven Wells Street to Junc. Barracks 1st Lane in Dn.55, Unit-13, Zone-5. (Asset Code-055/2453/4816/2013-14).",Own Sources,5,2017-18,2017-18 NE/2017-18/2730,Storm Water Drain,Completed,NE-ROYAPURAM,55,5900,"De-silting and Improvement to Existing Storm Water Drain at Barracks 1st Lane from of Barracks Street to Junc Portuguese Church Street in Dn.55, Unit-13, Zone-5. (Asset Code- 055/2455/4817/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/2731,Storm Water Drain,Completed,NE-ROYAPURAM,55,14900,"De-silting and Improvement to Existing Storm Water Drain at P.V.(I) Street (South) from of Govindappa Street to Jn.of Davidson Street in Dn.55,Unit-13,Zone-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/2732,Storm Water Drain,Completed,NE-ROYAPURAM,55,13400,"Improvements and Minor Repairs to Existing Storm Water Drain at at P.V.(I) Street (N) from jn Acharappan Street to jn of Davidson Street in Dn.55,Unit-13,Zone-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/5365,Roads,Completed,NE-ROYAPURAM,55,803000,"Improvement to B.T road at Buddi Sahib Street from P.V.(I) Street to Thathamuthaiappan Street in Dn.55,Unit-13,Zone-5. (Asset Code-044/2645/16730/2013-)",Own Sources,5,2017-18,2018-19 NE/2017-18/5512,Roads,Completed,NE-ROYAPURAM,55,540000,"Improvement to B.T road at 2nd Narayanan Street from Mint Street to Seven Wells Street in Dn.55,Unit-13,Zone-5. (Asset Code-044/2457/16712/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5524,Road Cut,Completed,NE-ROYAPURAM,55,282000,"Improvement to road work at Anaikarakonan Street in Dn.55,Unit-13,Zone-5. (asset Code-044/2456/16701/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5612,Roads,Completed,NE-ROYAPURAM,55,289000,"Improvement to Road Work at P.V.(I) Lane in Dn.55,Unit-13,Zone-5. (Asset Code- 040/2631/5705/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5667,Roads,Completed,NE-ROYAPURAM,55,353000,"Improvement to CC Road at Paramanada (M) Street in Dn.55,Unit-13,Zone-5. ( Asset Code-040/2450/5625/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5844,Roads,Completed,NE-ROYAPURAM,55,402000,"Improvement to CC Road at Shanmugam Street in Dn.55,Unit-13,Zone-5. (asset code-044/2471/16719/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/6424,Roads,Completed,NE-ROYAPURAM,55,18100,"De-Sliting the Existing Storm Water Drain at at Davidson Street from jn Amman Koil Street to jn of P.V.(I) Street in Dn.55,Unit-13,Zone-5. (Asset Code-055/2644/4820/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/6431,Storm Water Drain,Completed,NE-ROYAPURAM,55,14500,"De-sliting the Existing Storm Water Drain at Amman Koil Street from jn Mint Street to jn of Varadhamuthaiyappan Street in Dn.55,Unit-13,Zone-5. (ASSET CODE - 055/2676/4821/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/6432,Storm Water Drain,Completed,NE-ROYAPURAM,55,19300,"De-Sliting the Existing Storm Water Drain at Prakasam Salai (Broadway Road) in Dn.55,Unit-13,Zone-5. ( Asset code- 055/2652/4694/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/6433,Storm Water Drain,Completed,NE-ROYAPURAM,55,8134,"De-Sliting the Existing Storm Water Drain at Subramanian Street from jn Nattu Pillaiyar Koil Street to jn Amman Koil Street in Dn.55,Unit-13,Zone-5. (055/2669/4822/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/6434,Storm Water Drain,Completed,NE-ROYAPURAM,55,6900,"Improvements and Minor Repairs to Existing Storm Water Drain at Nattu Pillaiyar Koil Street from jn Subramanian Street to Thathamuthaiyappan Street in Dn.55,Unit-13,Zone-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/7055,Roads,Completed,NE-ROYAPURAM,55,149000,"Repairs and Annual maintenance Existing of Speed breaker at Portuguese Chruch Street in Ward-55, Unit-13, Zone-5 (Asset Code- 044/2447/16776/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/7056,Roads,Completed,NE-ROYAPURAM,55,151000,"Repairs and Annual maintenance of Existing Speed breaker at St.Xavier Street in Ward-55, Unit-13, Zone-5 ( Asset Code- 044/2470/16720/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/9431,Storm Water Drain,Completed,NE-ROYAPURAM,55,48000,"Improvements and Minor repairs to Existing SWD at P.V.(I) Street (N) from Acharappan street to jn.of Davidson Street in dn-55, unit-13, zone-v (ASSET CODE- 055/2679/4824/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9432,Storm Water Drain,Completed,NE-ROYAPURAM,55,49000,"Improvement and Minor Repairs of Existing at P.V.(I) Street (South) from Govindappa street to Jn. Of Davidson street in dn-55, Unit-13, Zone-5. (ASEET CODE- 055/2630/4700/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9494,Storm Water Drain,Completed,NE-ROYAPURAM,55,86000,"Improvement and Minor Repairs of Existing of SWD at Girigory Street.from Barracks street and Seven wells street in DN-55, U-13, ZONE-V. (Asset code- 055/2463/4815/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9495,Storm Water Drain,Completed,NE-ROYAPURAM,55,73000,"Improvement and Minor Repairs of Existing of swd at Barracks 1st lane from Barracks street to jn.of Portugese church street in Dn-55, Unit-13, Zone-V. (Asset Code- 055/2455/4817/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9497,Storm Water Drain,Completed,NE-ROYAPURAM,55,119000,"Improvement and Minor Repairs of Existing of SWD at St.Xavier Street from Sevenwells street & Portugese church street in Dn-55, Unit-13, zone-V. (Asset Code- 055/2470/4812/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9498,Storm Water Drain,Completed,NE-ROYAPURAM,55,159000,"Improvement and Minor Repairs of Existing of SWD at Sevenwells street from Barracks street to jn.of Amman koil street IN Dn-55, Unit-13, Zone-V (Asset Code-055/15615/4813/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9499,Storm Water Drain,Completed,NE-ROYAPURAM,55,89000,"Improvement and Minor Repairs of Existing of swd at Aanakarakonan street from Barracks street to jn.of Amman koil street in Dn-55, U-13, Zone-V (Asset Code- 055/2456/4814/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9503,Storm Water Drain,Completed,NE-ROYAPURAM,55,123000,"Improvements and Minor repairs to Existing SWD at Nattu pillaiyar koil street from jn.of Subramanian street to Thathamuthaiappan street in DN-55, Un-13, Zone-V Asset Code- 055/2680/4825/2013-14",Own Sources,5,2017-18,2018-19 NE/2017-18/9504,Storm Water Drain,Completed,NE-ROYAPURAM,55,129000,"Improvements and Minor repairs to Existing SWD at Amman koil street from jn.of Mint street to jn.of Varadhamuthaiyappan street in Dn-55, U-13, Zone-V. (Asset Code- 055/2676/4696/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/9505,Storm Water Drain,Completed,NE-ROYAPURAM,55,116000,"Improvements and Minor repairs to Existing SWD at Subramanian street from jn.of Nattu Pillaiyar koil street to jn.of Amman koil street in Dn-55, Unit-13, Zone-V Asset Code- 055/2669/4822/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/9507,Storm Water Drain,Completed,NE-ROYAPURAM,55,239000,"Improvements and Minor repairs to Existing SWD at Davidson street from jn.of Amman koil street to jn.of P.V.(I) Street in Dn-55, U-13, Zone-V (Asset Code- 055/2644/4820/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/9508,Storm Water Drain,Completed,NE-ROYAPURAM,55,159000,"Improvements and Minor repairs to Existing SWD at Prakasam salai ( Broadway road) in Dn-55, U-13, Zone-V (Asset Code-055/2652/4818/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/9509,Storm Water Drain,Completed,NE-ROYAPURAM,55,70000,"Improvement and Minor Repairs of Existing at Barracks street from Seven wells street to jn.of Barracks 1st lane . in Dn-55, U-13, Zone-V. (Asset code- 055/2453/4816/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/12289,Buildings,Completed,NE-ROYAPURAM,56,650000,"IMPROVEMENTS TO SHOPPING COMPLEX (CONVERTING NAMCO OFFICE) AT EBRAHIM SALAI IN DN-56,U-13,Z-5. (ASSET CODE- 030/2536/317/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/14979,Buildings,Completed,NE-ROYAPURAM,56,1115000,"Construction of Library Building at Salai Vinayagar Koil Street in Dn-56,Unit-13, Zone-5(MLA FUND) (Asset code- 019/2528/97/2013-14)",MLACDS,5,2017-18,2019-20 NE/2017-18/15330,Buildings,Completed,NE-ROYAPURAM,56,2566000,"Construction of Anganwadi Building at Venkata Iyer Street in Dn-56,Unit-13, Zone-5 (MLA Fund) (Asset code-019/2552/98/2013-14)",MLACDS,5,2017-18,2019-20 NE/2017-18/15930,Roads,Completed,NE-ROYAPURAM,56,1440000,"UNDER MLA SCHEME 2018-19 (HARBOUR CONSTITUENCY) LAYING CEMENT CONCRETE ROAD AT SALAI VINAYAGAR KOIL STREET(part) in Division-56, Unit-13, Zone-5.",MLACDS,5,2017-18,2018-19 NE/2017-18/5322,Storm Water Drain,Completed,NE-ROYAPURAM,56,5100,"DESILTING AND IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT SALAI VINAYAGAR KOIL STREET IN DN-56,U-13,Z-5. Asset Code :055/2528/4806/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/5332,Storm Water Drain,Completed,NE-ROYAPURAM,56,3900,"DESILTING AND IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT GEILLS STREET IN DN-56, U-13, Z-5. Asset Code : 055/2550/4807/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/5334,Storm Water Drain,Completed,NE-ROYAPURAM,56,14000,"DESILTING AND IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT ST.XAVIER STREET IN DN-56, UNIT-13, ZONE-5. Asset Code :055/2516/4803/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/5337,Storm Water Drain,Completed,NE-ROYAPURAM,56,4400,"DESILTING AND IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT AMMAN KOIL STREET IN DN-56, UNIT-13, ZONE-5. Asset Code : 055/2492/4804/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/5338,Storm Water Drain,Completed,NE-ROYAPURAM,56,6400,"DE SILTING AND IMPROVEMENTS TO THE EXISTING STORM WATER DRAIN AT MEERAN LABBAI STREET IN DN-56, UNIT-13, ZONE-5. Asset Code : 055/2496/4805/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/5852,Roads,Completed,NE-ROYAPURAM,56,1246000,"Improvement to B.T road at Naniyappan Street in Dn.56,Unit-13,Zone-5 (ASSET CODE-044/2522/16415/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5853,Roads,Completed,NE-ROYAPURAM,56,1246000,"Improvement to B.T road at Savarimuthu Street in Dn.56,Unit-13,Zone-5 (Asset Code-044/2556/16413/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/5854,Roads,Completed,NE-ROYAPURAM,56,1246000,"Improvement to B.T road at Malaiyappan Street in Dn.56,Unit-13,Zone-5 (Asset Code-044/2524/16411/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5855,Roads,Completed,NE-ROYAPURAM,56,1246000,"Improvement to B.T road at Nainiappan Street in Dn.56,Unit-13,Zone-5 (Asset Code-044/2522/16415/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5858,Roads,Completed,NE-ROYAPURAM,56,779000,"Improvement to B.T road at Geils Street in Dn.56,Unit-13,Zone-5 (Asset Code-044/2550/16409/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5859,Roads,Completed,NE-ROYAPURAM,56,706000,"Improvement to CC Road at Broadway 1st Lane in Dn.56,Unit-13,Zone-5 (Asset Code-040/2542/5744/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5898,Roads,Completed,NE-ROYAPURAM,56,831000,"Improvement to CC Road at Portuguese Church 1 to 9 Lanes in Dn.56,Unit-13, Zone-5 (Asset Code-039/2508/245/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5902,Roads,Completed,NE-ROYAPURAM,56,1411000,"Improvement to CC Road at Katchleeswarar Garden Street in Dn.56,Unit-13, Zone-5 (Asset Code-044/2549/16404/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5907,Roads,Completed,NE-ROYAPURAM,56,529000,"Improvement to CC Road Work at Maduravasal Lane in Dn.56,Unit-13, Zone-5 (Asset Code-044/2498/16373/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/6130,Roads,Completed,NE-ROYAPURAM,56,88000,"Repairs and Annul maintenance of existing Speed breaker at Krishnan Koil Street in ward-56, unit-13, zone-5. (Asset Code- 044/2545/16398/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/7059,Roads,Completed,NE-ROYAPURAM,56,88000,"Repairs and Annual maintenance of existing Speed breaker at Salai Vinayagar Koil Street in Ward-56, Unit-13, Zone-5 ( Asset Code- 044/2528/16401/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/7061,Roads,Completed,NE-ROYAPURAM,56,70000,"Repairs and Annual maintenance of existing Speed breaker in Ramasamy street at Ward-56, Unit-13, Zone-5 ( Asset Code - 044/2526/16407/2013-14 )",Own Sources,5,2017-18,2019-20 NE/2017-18/7087,Roads,Completed,NE-ROYAPURAM,56,76000,"Repairs and Annual maintenance of existing Speed breaker in St.Xavier Street at Ward-56, Unit-13, Zone-5 ( Asset Code- 044/2516/16370/2013-14 )",Own Sources,5,2017-18,2019-20 NE/2017-18/9187,Storm Water Drain,Completed,NE-ROYAPURAM,56,40000,"Improvement and Minor Repairs of Existing of swd at Salai Vinayagar koil Street IN DN-56, U-13, Z-5. (ASSET CODE- 055/2528/4806/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/9189,Storm Water Drain,Completed,NE-ROYAPURAM,56,195000,"Improvement and Minor Repairs of Existing of swd at St.Xavier Street IN Dn-56, U-13, Zone-V. (Asset code- 055/2516/4803/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/9427,Storm Water Drain,Completed,NE-ROYAPURAM,56,123000,"Improvement and Minor Repairs of Existing of SWD at Amman Koil Street in Dn-56, Unit-13, Zone-V. (ASSET CODE- 055/2492/4804/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/9429,Storm Water Drain,Completed,NE-ROYAPURAM,56,70000,"Improvement and Minor Repairs of Existing of SWD at Geills Street IN DN-56, UNIT-13, ZONE-V (ASSET CODE- 055/2550/4807/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/9430,Storm Water Drain,Completed,NE-ROYAPURAM,56,77000,"Improvement and Minor Repairs of Existing of swd at Meeran Labbai Street DN-56, UNIT-13, ZONE-V. (ASSET CODE- 055/2496/4805/2013-14)",Own Sources,5,2017-18,2018-19 D/2017-18/14648,Storm Water Drain,Completed,D-Storm Water Drains,57,2490000,"Construction of storm water drain of size 900 x 900 mm along Broadway road from junction of Thathamuthiyappan street to junction of Mookarnallamuthu street in Division 57 and 60, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/14847,Storm Water Drain,Completed,D-Storm Water Drains,57,2240000,"Construction of storm water drain of size 900 x 900 mm along Broadway road from junction of Mookarnallamuthu street to junction of Errabalu street in Division 57 and 60, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/14850,Storm Water Drain,Completed,D-Storm Water Drains,57,2400000,"Construction of storm water drain of size 900 x 900 mm along Broadway road from junction of Errabalu street to Junction of Goomes street in Division 57 and 60, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/14851,Storm Water Drain,Completed,D-Storm Water Drains,57,2335000,"Construction of storm water drain of size 900 x 900 mm along Broadway road from junction of Goomes street to Phillips street in Division 57 and 60, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/14856,Storm Water Drain,Completed,D-Storm Water Drains,57,2315000,"Construction of storm water drain of size 900 x 900 mm along Thathamuthiappan street from junction of Varadhamuthiappan street to junction of Ramakrishnan street in Division 57, Zone - V.",Own Sources,5,2017-18,2019-20 D/2017-18/14859,Storm Water Drain,Completed,D-Storm Water Drains,57,2410000,"Construction of storm water drain of size 900 x 900 mm along Thathamuthiappan street from junction of Ramakrishnan street junction of Nattupilliar street in Division 57, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/14861,Storm Water Drain,Completed,D-Storm Water Drains,57,2145000,"Construction of storm water drain of size 900 x 900 mm along Thathamuthiappan street from junction of Nattupilliar street to junction of Anna pillai street in Division 57, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/14869,Storm Water Drain,Completed,D-Storm Water Drains,57,1670000,"Laying of HDPE pipe and inspection chamber at regular interval, along Audiappanaicken street from junction of Waltax road to junction of Erullappan street in Division 57 and 60, Zone - V.",Own Sources,5,2017-18,2018-19 D/2017-18/16020,Storm Water Drain,Completed,D-Storm Water Drains,57,2240000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at Kalyanapuram 7 to 9 lanes in Division - 57, Zone - 5",Own Sources,5,2017-18,2019-20 L/2017-18/7072,Electrical,Completed,L-Electrical,57,1647500,SUPPLY AND LAYING OD DAMAGED 2129 MTRS OF 2 X 16 SQMM ALU CABLE AND 1705 MTRS 4 X 16 SQMM ALU CABLE AT VARIOUS LOCATIONS IN DIV 57 IN ZONE V.,Own Sources,5,2017-18,2018-19 NE/2017-18/13208,Roads,Completed,NE-ROYAPURAM,57,1900000,"Relaying of CC road at Acharappan Street in dn-57,unit-13,zone-v Asset code: 040/15616/5812/2013-14",MPLADS,5,2017-18,2018-19 NE/2017-18/1766,Storm Water Drain,Completed,NE-ROYAPURAM,57,69300,"DESILTING TO STORM WATER DRAIN AT ANNA PILLAI STREET IN DIV-57,UNIT-13,ZONE-5. (Asset Code- 055/2692/4687/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/1767,Storm Water Drain,Completed,NE-ROYAPURAM,57,27700,"DESILTING TO STORM WATER DRAIN AT PRAKASAM SALAI IN DIV-57,UNIT-13,ZONE-5. ( Asset Code- 055/2706/4774/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/1768,Storm Water Drain,Completed,NE-ROYAPURAM,57,22100,"DESILTING TO STORM WATER DRAIN AT SOUTH MARKET STREET AND THATTAMUTHIAPPAN STREET IN DIV-57,UNIT-13,ZONE-5. Asset code- 055/2708/4854/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/1822,Storm Water Drain,Completed,NE-ROYAPURAM,57,41600,"DESILTING TO STORM WATER DRAIN AT WATER BASIN STREET TO JUTKAPURAM AND VINAYAGAM STREET TO WALL TAX ROAD IN DIV-57,UNIT-13,ZONE-5. Asset code- 055/4198/4846/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/1823,Storm Water Drain,Completed,NE-ROYAPURAM,57,164000,"DESILTING TO THE ARCH DRAIN AT DAVIDSON STREET AND AMBERSON STREET IN DIV-57,UNIT-,ZONE-5. (Asset code- 044/2718/16452/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/6037,Roads,Completed,NE-ROYAPURAM,57,305000,"Improvement to B.T road AT THIRUVELIYAN BASIN STREET IN DIVISION-57,UNIT 13,ZONE-5 (Asset Code- 044/4200/16445/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/9510,Storm Water Drain,Completed,NE-ROYAPURAM,57,307000,"Improvement and Minor Repairs to the existing SWD at Anna Pillai street in Dn-57, U-13, Zn-5, (Asset Code- 055/2692/4687/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/9511,Storm Water Drain,Completed,NE-ROYAPURAM,57,301000,"Improvement and Minor Repairs of Existing of swd at Prakasam Salai in Dn-57, Unit-13, Zone-V, Asset Code- 055/2706/4774/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/9512,Storm Water Drain,Completed,NE-ROYAPURAM,57,317000,"Improvement and Minor Repairs of Existing of swd at South Market Street and Thathamuthaiappan street in Dn-57, Unit-13, Zone-V, (Asset Code-055/2708/4854/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/9513,Storm Water Drain,Completed,NE-ROYAPURAM,57,307000,"Improvement and Minor Repairs of Existing of swd at Water Basin street to Jutkapuram and vinayagam street to wall tax road in Dn-57, Unit-13, ZOne-V. (Asset Code- 055/4190/4847/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/9514,Storm Water Drain,Completed,NE-ROYAPURAM,57,191000,"Improvement and Minor Repairs of Existing of SWD to the Arch drain at Davidson street and Amberson street in DN-57, Unit-13, Zone-V. Asset Code- 044/2718/16452/2013-14)",Own Sources,5,2017-18,2017-18 B/2017-18/0335,Buildings,Completed,B-Buildings,58,2500000,REPAIR AND IMPROVEMENT WORKS TO RIPON BUILDING CAMPUS AND AMMA MALIGAI IN DN 58 ZONE 5,Own Sources,5,2017-18,2020-21 B/2017-18/12279,Buildings,Completed,B-Buildings,58,460000,Addition and Alteration work for conversion of HOD rooms to GIS Servor room in Amma Maligai First Floor 'A' wing in Ripon Building Campus in DN-58 Zone I,Own Sources,5,2017-18,2018-19 B/2017-18/13219,Buildings,Completed,B-Buildings,58,4950000,Construction of Underground Sump and Motor room and Water supply arrangements and other improvements works in Ripon Building Campus in DN58 Zone V,Own Sources,5,2017-18,2020-21 B/2017-18/15572,Buildings,Completed,B-Buildings,58,887000,"Supplying and fixing of Two seater bench cum tables for propsed smart classes in CGHSS Rotler Street in DN 58 Zone 5, CHSS Kolathur in DN 64 Zone 6, CGHSS Market street in DN 67 Zone 6 and CGHSS M.H road in DN 70 Zone 6",Own Sources,5,2017-18,2018-19 B/2017-18/1808,Buildings,Completed,B-Buildings,58,2300000,RECONSTRUCTION OF DAMAGED RIPON BUILDING COMPOUND WALL AND RELAYING OF BASEMENT PARKING AREA FLOORING IN AMMA MALIGAI BUILDING IN DN 58 ZONE 5,Own Sources,5,2017-18,2020-21 B/2017-18/6595,Buildings,Completed,B-Buildings,58,6800000,"SUPPLYING OF MATERIALS, INSTALLATION, REPAIRING AND RESTORATION OF STRUCTURAL CRACKS DEVELOPED IN RIPON BUILDING IN DN 58 ZONE 5",Own Sources,5,2017-18,2020-21 B/2017-18/9926,Buildings,Completed,B-Buildings,58,1200000,Alteration and Conversion of office space to Accommodate two Additional Court halls in the Second and Third floor of Allikulam Complex in Dn 58 Zone V.,Own Sources,5,2017-18,2021-22 BR/2017-18/11686,Roads,Completed,BR-Bus Route Roads,58,148000,"Restoration of road cut made by CMWSSB at sydenhams road in Dn-58, Zone-5 against challan no. BR/2017-18/0018434",Deposit Works,5,2017-18,2018-19 BR/2017-18/12036,Road Cut,Completed,BR-Bus Route Roads,58,142000,RESTORATION OF ROAD CUT MADE BY TANGEDCO AT EVK SAMPATH SALAI IN DIV-58 ZONE-V.,Deposit Works,5,2017-18,2018-19 BR/2017-18/14545,Roads,Completed,BR-Bus Route Roads,58,985000,Providing speed breakers at various bus route roads in Zone 5,Own Sources,5,2017-18,2018-19 L/2017-18/0901,Electrical,Completed,L-Electrical,58,936600,"Erection of 23 nos 7 mtr Lamp post with 1 mtr single Straight bracket, replacement of 952mtrs of 2C x16 Sq.mm PVC Alu cable and convertion of 23 nos 40w-50w LED fitting at Jothivenkatachalam Street in Division-58, under Zone- V.",Own Sources,5,2017-18,2018-19 L/2017-18/10819,Electrical,Completed,L-Electrical,58,240300,Supply and Installation of 4 nos of 2 ton 3 star Split Air Conditioner for the use of 3nos at Sub pay and Account Office 1st floor Revenue block and 1no at Chief Engineer Buildings chamber in Ripon building premises.,Own Sources,5,2017-18,2019-20 L/2017-18/1384,Electrical,Completed,L-Electrical,58,344700,"Erection of 8 nos 7 mtr Lamp post with 1 mtr single Straight bracket, replacement of 334mtrs of 2C x16 Sq.mm PVC Alu cable and convertion of 8 nos 40w-50w LED fitting at Parthapet Road in Division-58, under Zone- V.",Own Sources,5,2017-18,2018-19 L/2017-18/6986,Electrical,Completed,L-Electrical,58,1416600,"Supply and Erection of 36nos 7mtr lamp post with single straight bracket and replacement of 1348mtrs 2cX16sq.mm pvc alu cable with 37 nos 40-50w LED Fitting at Uthukottan Street, Periyanna Maistry Street and Veerasamy Street in Dn-58, Zone-05.",Own Sources,5,2017-18,2019-20 L/2017-18/7870,Electrical,Completed,L-Electrical,58,735600,"Electrification work in pay and accounts office department at Revenue building first floor western side in Ripon building Premises in DN-58,Zone-V",Own Sources,5,2017-18,2018-19 L/2017-18/9264,Electrical,Completed,L-Electrical,58,803900,"Supply and Erection of 1 no 8m GI Octoganal Minimast, 1 no 9.5mtr street lamp post, convertion of 4 nos 150-165w LED fitting and 7 nos of 200-210w LED fitting and replacement of 70mtr 4cX16 sq.mm cable, 129mtrs 2cX16sq.mm cable at Whannals road(Egmore Railway station junction), Nair Bridge(EVR Salai Junction) and Central Bridge junctions at EVR Salai in Dn-58 & 59, Zone-05.",Own Sources,5,2017-18,2018-19 NE/2017-18/0427,Roads,Completed,NE-ROYAPURAM,58,217000,"Providing Group Pin cement concrete Platform at various Roaad in DN 58,U 24,Z 5.",Own Sources,5,2017-18,2020-21 NE/2017-18/1177,Roads,Completed,NE-ROYAPURAM,58,744000,"Procurement of Bio - shredding Machine, Sieving machine, Tri- cycle bullet tyre, Ordinary Tri- cycle, Electronic weighing machine,at Various Street in Unit-14, Zone-5",Own Sources,5,2017-18,2018-19 NE/2017-18/13029,Roads,Completed,NE-ROYAPURAM,58,450000,"Attending repairs to damaged road portion at various streets in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/2074,Storm Water Drain,Completed,NE-ROYAPURAM,58,930000,"Desilting of SWD at Allikulam Link road, Baracks road, Jermiah Road, Jothy Venkatachalam Street, Naval Hospital Road, Nellu Jalladai street, New Moore Market Road, People park road, R.T. (M) Street, Rippon building campus, Stringers Street, Sydenhams Road in Ward-58, Uni5-14, Zone-V.",Own Sources,5,2017-18,2017-18 NE/2017-18/2076,Storm Water Drain,Completed,NE-ROYAPURAM,58,440000,"Repais and Improvements to SWD at Allikulam Link road, Baracks road, Jermiah Road, Jothy Venkatachalam Street, Naval Hospital Road, Nellu Jalladai street, New Moore Market Road, People park road, R.T. (M) Street, Rippon building campus, Stringers Street, Sydenhams Road in Ward-58, Uni5-14, Zone-V.",Own Sources,5,2017-18,2017-18 NE/2017-18/2078,Storm Water Drain,Completed,NE-ROYAPURAM,58,572000,"Desilting of SWD at Thiruvengadam Street, Veerasamy Street, Samiy (P) Street, Venkatachalam street, Vepery high road, A.P. Road, Balar Kalvi Nilayam salai, Dharmaraja koil street, Dr. Alagappa Road, E.V.K. Sampath salai, Kalathiyappa street, Ritherdon road, Rotler Street, Thirunarayanaguru salai, Vadamalai street, Valliammal road in Ward-58, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/2079,Storm Water Drain,Completed,NE-ROYAPURAM,58,570000,"Repairs and Improvements to SWD at Thiruvengadam Street, Veerasamy Street, Samiy (P) Street, Venkatachalam street, Vepery high road, A.P. Road, Balar Kalvi Nilayam salai, Dharmaraja koil street, Dr. Alagappa Road, E.V.K. Sampath salai, Kalathiyappa street, Ritherdon road, Rotler Street, Thirunarayanaguru salai, Vadamalai street, Valliammal road in Ward-58, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/2108,Storm Water Drain,Completed,NE-ROYAPURAM,58,632000,"Desilting of SWD at Bangaru Street, Broadway Bus Stand (inside), Ellis Road, Frazer Bridge Road, Kellys drain, Memorial Hall street, Mint Street, Mukthurinnsa begam 5th and 6th lane, Narayanappa road, NSC Bose Road, Nyniappa maistry street, Owlia (s) 4th and 6th lane, Pallavan Salai, Rattan bazaar road, S.M. Nagar, Thayar (S) Street, Tippu (S) street, Unnis Ali (S) street, Walajah road in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2017-18 NE/2017-18/5468,Roads,Completed,NE-ROYAPURAM,58,265000,"Improvements to CC Road at E.K. Guru Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5477,Roads,Completed,NE-ROYAPURAM,58,391000,"Improvement to B.T road at Salai Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5561,Roads,Completed,NE-ROYAPURAM,58,106000,"Improvements to CC Road at Nellu Jalladai Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5566,Roads,Completed,NE-ROYAPURAM,58,325000,"Improvement to B.T road at Kumarappa Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5569,Roads,Completed,NE-ROYAPURAM,58,467000,"Improvement to B.T road at Venkatachalam Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5578,Roads,Completed,NE-ROYAPURAM,58,606000,"Improvement to B.T road at Sydenhams Lane in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5581,Roads,Completed,NE-ROYAPURAM,58,865000,"Improvement to B.T road at Vaikkokaran street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5588,Roads,Completed,NE-ROYAPURAM,58,692000,"Improvements to BT Road at Sydenhams Lane in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5618,Roads,Completed,NE-ROYAPURAM,58,554000,"Improvements to BT Road at Kandappa Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5619,Roads,Completed,NE-ROYAPURAM,58,519000,"Improvements to BT Road at Venkatachalam Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5622,Roads,Completed,NE-ROYAPURAM,58,104000,"Improvements to BT Road at Aarani Muthu Street in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5641,Roads,Completed,NE-ROYAPURAM,58,657000,"Improvements to BT Road at Stringers road 1st and 2nd lane in Ward-58, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5698,Roads,Completed,NE-ROYAPURAM,58,346000,"Improvements to BT Road at Ekamabareshwarar Agraharam Street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5700,Roads,Completed,NE-ROYAPURAM,58,277000,"Improvements to BT Road at Ravanier Street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5707,Roads,Completed,NE-ROYAPURAM,58,1038000,"Improvements to BT Road at Unnis Ali (Sahib) Street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/7444,Parks,Completed,NE-ROYAPURAM,58,2150000,Annual Maintenance of MYLADIS PARK AT SYDAMS ROAD IN DIV-58 UNIT-14 ZONE-05 (Maintenance Period one year 365 days),Own Sources,5,2017-18,2018-19 BR/2017-18/9701,Roads,Completed,BR-Bus Route Roads,59,2254000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at South Mint Road in Dn-59, Zone-V",Grants,5,2017-18,2018-19 NE/2017-18/13033,Roads,Completed,NE-ROYAPURAM,59,62000,"Attending repairs to the damaged road portion at various streets in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/2109,Storm Water Drain,Completed,NE-ROYAPURAM,59,517000,"Repairs and Improvements to SWD at Bangaru Street, Broadway Bus Stand (inside), Ellis Road, Frazer Bridge Road, Kellys drain, Memorial Hall street, Mint Street, Mukthurinnsa begam 5th and 6th lane, Narayanappa road, NSC Bose Road, Nyniappa maistry street, Owlia (s) 4th and 6th lane, Pallavan Salai, Rattan bazaar road, S.M. Nagar, Thayar (S) Street, Tippu (S) street, Unnis Ali (S) street, Walajah road in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5694,Roads,Completed,NE-ROYAPURAM,59,381000,"Restoration of road cut made by CMWSSB at Muktharunisha Begum 6th Lane in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5703,Roads,Completed,NE-ROYAPURAM,59,346000,"Improvements to BT Road at V.O.C. Salai in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5713,Roads,Completed,NE-ROYAPURAM,59,391000,"Improvement to B.T road at Thayar (Sahib) 2nd Lane in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5717,Roads,Completed,NE-ROYAPURAM,59,260000,"Improvement to B.T road at Nalla Thambi Street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5720,Roads,Completed,NE-ROYAPURAM,59,692000,"Improvement to B.T road at Owlia (S) Street and Lane in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5723,Roads,Completed,NE-ROYAPURAM,59,391000,"Improvement to B.T road at Balamuthu Street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5725,Roads,Completed,NE-ROYAPURAM,59,606000,"Improvement to B.T road at Muktarunisha Begam street lane in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5729,Roads,Completed,NE-ROYAPURAM,59,606000,"Improvement to B.T road at Thayar (S) Street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5742,Roads,Completed,NE-ROYAPURAM,59,265000,"Improvements to CC Road at Thayar (Sahib) 1st Lane in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5745,Roads,Completed,NE-ROYAPURAM,59,399000,"Improvements to CC Road at Thirumalai Lane in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5751,Roads,Completed,NE-ROYAPURAM,59,268000,"Improvements to CC Road at Antony street in Ward-59, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/6678,Buildings,Completed,NE-ROYAPURAM,59,2225000,"MLA FUND 2017-18 CONSTRUCTION OF PUBLIC CONVENIENCE AT BROADWAY BUS STAND SOUTH SIDE IN DIV-59, UNIT-14, ZONE-05",MLACDS,5,2017-18,2019-20 B/2017-18/11848,Buildings,Completed,B-Buildings,60,2553112,"FABRICATION, CONSTRUCTION AND ERECTION OF GREATER CHENNAI CORPORATION PAVILION INCLUDING SUPPLYING OF NEW MODELS AND INTERIOR DESIGN, VIDEO DEVICES AND MAN POWER FOR MANAGING, HOUSE KEEPING AND SECURITY FOR 44th INDIA TOURIST AND INDUSTRIAL FAIR 2017 ISLAND GROUND IN DN 60 ZONE V",Own Sources,5,2017-18,2018-19 B/2017-18/7849,Buildings,Completed,B-Buildings,60,5630000,"MAINTAINANCE OF ELECTRONIC TOILET IN GCC 2,5,6,8,9,10,11,12,13, & 14 FOR A PERIOD OF 6 MONTHS",Own Sources,5,2017-18,2021-22 BR/2017-18/10784,Roads,Completed,BR-Bus Route Roads,60,885000,"Providing steel plate laying(16mm), and center median (0.4X0.25) at stanley subway for NRT bridge post diversion work in Dn-52, Zone-5",Deposit Works,5,2017-18,2018-19 BR/2017-18/17130,Roads,Completed,BR-Bus Route Roads,60,1915000,"Restoration of road cut made by CMWSSB at Rukmani lakshmipathy salai (sewer 1, Ethiraj salai Jn. to Rajarathinam stadium) Dn-61, Zone-V against Challan No. BR/2017-18/00030439.",Deposit Works,5,2017-18,2018-19 BR/2017-18/17137,Roads,Completed,BR-Bus Route Roads,60,315000,"Restoration of road cut made by TANGEDCO at Rajaji salai and Swami sivananda salai in Dn-60, Zone-V against Challan No. BR/2018-19/0002998.",Deposit Works,5,2017-18,2018-19 BR/2017-18/17142,Roads,Completed,BR-Bus Route Roads,60,1950000,"Restoration of road cut made by CMWSSB at Rukmani lakshmipathy salai (sewer 2 East, Rajarathinam stadium to Pantheon Jn. L=530m) Dn-61, Zone-V against Challan No. BR/2017-18/00030439.",Deposit Works,5,2017-18,2018-19 BR/2017-18/9677,Roads,Completed,BR-Bus Route Roads,60,2480000,"Modification and improvement work for traffic diversion in Royapuram MS Koil street, bharathi college round about, Anna park etc, due to NRT Bridge work",Deposit Works,5,2017-18,2018-19 BR/2017-18/9862,Roads,Completed,SP-SPECIAL PROJECTS,60,920000,"Traffic Improvement works for Bi-Cycle lanes at under Smart City initiative at Swamy Sivananda Salai, Flag Staff Road, Napier Bridge and Anna Salai in Dn-60, Zone-V",SMART CITY - BRR,5,2017-18,2018-19 D/2017-18/16488,Storm Water Drain,Completed,D-Storm Water Drains,60,2005000,"Construction of storm water drain of size 900 x 900 mm along Broadway road from junction of Phillips street to junction of NSC Bose road in Division 60, Zone - V.",Own Sources,5,2017-18,2018-19 L/2017-18/1134,Electrical,Completed,L-Electrical,60,932700,Supply and Erection of 7 nos of MINI HIGHMAST at Sathya Nagar in Div 60 in Zone - 5. (NORTH CHENNAI MPLADS ),MPLADS,5,2017-18,2018-19 L/2017-18/6513,Electrical,Completed,L-Electrical,60,86800,Replacement of accessories and maintenance of 30 mtrs Highamst at Flag Staff road in Div-60 in Zone - 5,Own Sources,5,2017-18,2018-19 NE/2017-18/10249,Buildings,Completed,NE-ROYAPURAM,60,190000,Providing water supply arrangement to toilet block inside division office and other improvements in ward50 unit.12 zone.5,Own Sources,5,2017-18,2018-19 NE/2017-18/11254,Buildings,Completed,NE-ROYAPURAM,60,2200000,"CONSTRUCTION OF PUBLIC CONVENIENCE AT KANDAPPA STREET(Jn. OF 4TH LANE BEACH ROAD ) IN DIVISION-60, UNIT-13, ZONE-5. [ASSET CODE. 033/2612/502/2013-14]",MPLADS,5,2017-18,2019-20 NE/2017-18/11255,Storm Water Drain,Completed,NE-ROYAPURAM,60,1520000,"PROVIDING RAIN WATER DRAINING ARRANGEMENTS e (Road side drain) AT RAJAJI SALAI (OPP.TO SECRETARIAT OFFICE ) NEAR BUS STOP IN DIVISION-60, UNIT-11, ZONE-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/12070,Buildings,Completed,NE-ROYAPURAM,60,466000,"Providing painting for kerb stone & center median at Kamaraj salai, Rajaji salai, Flag staff house road in ward-60, Unit-13, Zone-5 (Aseet Code- 043/2646/1098/2014-15)",Own Sources,5,2017-18,2018-19 NE/2017-18/12073,Roads,Completed,NE-ROYAPURAM,60,1723000,"Removal of Debris from vacant land (MLA car parking area) at Rajaji Salai opp. to Secretariat office in Division-60, Unit-13, Zone-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/12583,Buildings,Completed,NE-ROYAPURAM,60,155000,"PETTY REPAIR WORKS TO E-TOILET AT 4th LINE BEACH ROAD LANE (Jn. OF NARAYANA SARANG STREET) IN DIVISION-60, UNIT-13, ZONE-5 [ASSET CODE - 016/2601/8/2013-14 ]",Own Sources,5,2017-18,2018-19 NE/2017-18/12631,Footpath,Completed,NE-ROYAPURAM,60,615000,"PETTY REPAIR WORKS IN FOOTPATHS & CENTRE MEDIAN AT KAMARAJ SALAI, RAJAJI SALAI, FLAG STAFF HOUSE ROAD, NSC BOSE ROAD AND NORTH FORT SIDE ROAD IN DIVISION-60, UNIT-13, ZONE-5 [Asset Code 053/2646/1951/2013-14]",Own Sources,5,2017-18,2018-19 NE/2017-18/5929,Roads,Completed,NE-ROYAPURAM,60,1730000,"Improvement to B.T road at Mu.Ka. Nallamuthu Street in Ward-60, Unit-13, Zone-V. (Asset Code- 044/2587/16542/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5932,Roads,Completed,NE-ROYAPURAM,60,865000,"Improvement to B.T road at Marakaiyar Street in Ward-60, Unit-13, Zone-V. (Asset Code- 044/2590/1402/2007-08)",Own Sources,5,2017-18,2018-19 NE/2017-18/5933,Roads,Completed,NE-ROYAPURAM,60,1384000,"Improvement to B.T road at Jones Street in Ward-60, Unit-13, Zone-V. (Asset code- 044/2639/16582/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5934,Roads,Completed,NE-ROYAPURAM,60,1315000,"Improvement to B.T road at 3rd Lane Beach Road in Ward-60, Unit-13, Zone-V. (Asset- 044/2602/1407/2008-09)",Own Sources,5,2017-18,2018-19 NE/2017-18/5937,Roads,Completed,NE-ROYAPURAM,60,865000,"Improvement to B.T road at Katchaleeswarar Agaraharam in Ward-60, Unit-13, Zone-V. (Asset code-",Own Sources,5,2017-18,2018-19 NE/2017-18/5939,Roads,Completed,NE-ROYAPURAM,60,2595000,"Improvement to B.T road at Sembudoss Street in Ward-60, Unit-13, Zone-V. (Asset code- 044/2650/16683/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5960,Roads,Completed,NE-ROYAPURAM,60,706000,"Improvement to Cc Road work at Ibrahim 2nd lane in Ward-60, Unit-13, Zone-V. (Asset Code- 044/2582/16527/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/5963,Roads,Completed,NE-ROYAPURAM,60,1341000,"Improvement to CC Road work at 4th lane beach road in Ward-60, Unit-13, Zone-V. (Asset Code 044/2601/1406/2008-09)",Own Sources,5,2017-18,2018-19 NE/2017-18/6450,Buildings,Completed,NE-ROYAPURAM,60,69000,"Improvements and Minor Repairs to Existing Storm Water Drain Ibrahim Street in DIV-60, Unit-13, Zone-05. Asset Code: 055/2580/4826/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6451,Buildings,Completed,NE-ROYAPURAM,60,73400,"Improvements and Minor Repairs to Existing Storm Water Drain at Varadarasan Street in Div-60, Unit-13, Zone-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/6452,Buildings,Completed,NE-ROYAPURAM,60,75100,"Improvements and Minor Repairs to Existing Storm Water Drain at Jaffer Sarang Street in Div-60, Unit-13, Zone-05. Asset Code : 055/2578/4828/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6453,Buildings,Completed,NE-ROYAPURAM,60,15100,"Improvements and Minor Repairs to Existing Storm Water Drain at Moore Street in Div-60, Unit-13, Zone-05. Asset Code : 055/2599/4829/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6454,Buildings,Completed,NE-ROYAPURAM,60,34300,"Improvements and Minor Repairs to Existing Storm Water Drain at Jaffer Sarang Lane in Div-60, Unit-13, Zone-05. Asset Code : 055/2613/4830/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6455,Buildings,Completed,NE-ROYAPURAM,60,9700,"Improvements and Minor Repairs to Existing Storm Water Drain at Mooker Nallamuthu Lane in Div-60, Unit-13, Zone-05. Asset Code : 055/2587/4831/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6456,Buildings,Completed,NE-ROYAPURAM,60,59800,"Improvements and Minor Repairs to Existing Storm Water Drain at Post Office Street in Div-60, Unit-13, Zone-05. Asset Code : 055/2653/4832/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6457,Buildings,Completed,NE-ROYAPURAM,60,71600,"DESILTING OF STORM WATER DRAIN SULTAN STREET IN DIV-60, UNIT-13, ZONE-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/6458,Storm Water Drain,Completed,NE-ROYAPURAM,60,132600,"Improvements and Minor Repairs to Existing Storm Water Drain at Rajaji Salai (East) in Div-60, Unit-13, Zone-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/6459,Buildings,Completed,NE-ROYAPURAM,60,105800,"Improvements and Minor Repairs to Existing Storm Water Drain at Rajaji Salai (East -1) in Div-60, Unit-13, Zone-05 .",Own Sources,5,2017-18,2017-18 NE/2017-18/6787,Storm Water Drain,Completed,NE-ROYAPURAM,60,77400,"Improvements and Minor Repairs to Existing Storm Water Drain at Rajaji Salai (West) Street in Div-60, Unit-13, Zone-05. Asset Code : 055/2646/4836/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6841,Storm Water Drain,Completed,NE-ROYAPURAM,60,221400,"Improvements and Minor Repairs to Existing Storm Water Drain at Kamarajar Salai in Div-60, Unit-13, Zone-05. Asset Code : 055/2627/4837/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6842,Storm Water Drain,Completed,NE-ROYAPURAM,60,59200,"Improvements and Minor Repairs to Existing Storm Water Drain at Flag Staff House Road in Div-60, Unit-13, Zone-05. Asset Code : 055/2663/4838/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6843,Storm Water Drain,Completed,NE-ROYAPURAM,60,50400,"Improvements and Minor Repairs to Existing Storm Water Drain at North Fort Side Road in Div-60, Unit-13, Zone-05. Asset Code : 055/2664/4839/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6868,Storm Water Drain,Completed,NE-ROYAPURAM,60,202000,"Improvements and Minor Repairs to Existing Storm Water Drain at NSC Bose Road in Div-60, Unit-13, Zone-05. Asset Code : 055/2632/7533/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/6869,Storm Water Drain,Completed,NE-ROYAPURAM,60,19200,"Improvements and Minor Repairs to Existing Storm Water Drain at Sembudoss Street in Div-60, Unit-13, Zone-05. Asset Code : 055/2650/4919/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/6875,Storm Water Drain,Completed,NE-ROYAPURAM,60,17700,"Improvements and Minor Repairs to Existing Storm Water Drain at Jones Lane in Div-60, Unit-13, Zone-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/6923,Roads,Completed,NE-ROYAPURAM,60,488000,"Painting foot path Kerb wall at Kamarajar salai, Flag staff house road , Rajaji salai ,North fort side road,NSC Bose road Ward-60, Unit-13, Zone-5 (Asset Code- 153/2646/1062/2014-15)",Own Sources,5,2017-18,2018-19 NE/2017-18/6964,Footpath,Completed,NE-ROYAPURAM,60,300000,"Repairs and Improvement to Footpath at Kamaraj Salai Ward-60, Unit-13, Zone-5",Own Sources,5,2017-18,2018-19 NE/2017-18/6965,Roads,Completed,NE-ROYAPURAM,60,194000,"Supply of Bituminious Cold Mix for filling Pot Holes at Kamaraj Salai and Rajaji Salai, N.S.C.Boss Road, North Fort Road in Ward-60, Unit-13, Zone-5",Own Sources,5,2017-18,2018-19 NE/2017-18/6975,Roads,Completed,NE-ROYAPURAM,60,616000,"Removal of Debris at Rajaji Salai opp. to Secretariat in Watd-60, Unit-13, Zone-5",Own Sources,5,2017-18,2018-19 NE/2017-18/7247,Parks,Completed,NE-ROYAPURAM,60,403000,ANNUAL MAINTENANCE INSIDE PARK AT AVANAKAPPAGAM IN DIV-61 UNIT-14 ZONE-05,Own Sources,5,2017-18,2020-21 NE/2017-18/7343,Roads,Completed,NE-ROYAPURAM,60,117000,"Repairs and Annual maintenance of Existing Speed breaker at 2nd Lane Beach in Ward-60, Unit-13, Zone-5 (Asset Code:030/2603/12/2010-11)",Own Sources,5,2017-18,2019-20 NE/2017-18/7344,Roads,Completed,NE-ROYAPURAM,60,93000,"Repairs and Annual maintenance of Existing Speed breaker at Krishnan koil Street in Ward-60, Unit-13, Zone-5 (ASSET CODE- 044/2611/23554/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/7353,Roads,Completed,NE-ROYAPURAM,60,117000,"Repairs and Annual maintenance of Existing Speed breaker at Errabalu Street in Ward-60, Unit-13, Zone-5 (ASSET CODE- 044/2642/16530/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/7354,Roads,Completed,NE-ROYAPURAM,60,101000,"Repairs and Annual maintenance of Existing Speed breaker at Meclean Street in Ward-60, Unit-13, Zone-5. (Asset code- 044/2621/16594/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/7355,Roads,Completed,NE-ROYAPURAM,60,101000,"Repairs and Annual maintenance of Existing Speed breaker at Armenian Street in Ward-60, Unit-13, Zone-5 ( ASSET CODE- 044/2617/16578/2013-14)",Own Sources,5,2017-18,2019-20 NE/2017-18/8842,Storm Water Drain,Completed,NE-ROYAPURAM,60,53000,"Improvements and Minor repairs to Existing SWD at Sembudoss street in Dn-60, Unit-13,Zone-5 (Asset Code- 055/2650/4919/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/8843,Storm Water Drain,Completed,NE-ROYAPURAM,60,63000,"Improvements and Minor Repairs to Existing Storm water Drain at Moore street in Dn-60, Unit-13, Zone-5 (Asset Code- 055/2599/4829/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/8844,Storm Water Drain,Completed,NE-ROYAPURAM,60,108000,"Improvements and Minor Repairs to Existing Storm water Drain at Jaffer sarang street in Dn-60, Unit-13,Zone-5, ASSET CODE- 055/2578/4828/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/8845,Storm Water Drain,Completed,NE-ROYAPURAM,60,122000,"Improvements and Minor Repairs to Existing Storm water Drain at Varadarasan street in Dn-60, Unit-13,Zone-5 (ASSET CODE- 055/2615/4827/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/8846,Storm Water Drain,Completed,NE-ROYAPURAM,60,135000,"Improvements and Minor Repairs to Existing Storm water Drain at Ibrahim street in Dn-60, Unit-13,Zone-5 (ASSET CODE- 055/2580/4826/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/8847,Storm Water Drain,Completed,NE-ROYAPURAM,60,83000,"Improvements and Minor Repairs to Existing Storm water Drain at Jaffer Sarang Lane in Dn-60, Unit-13,Zone-5 (Asset Code- 055/2613/4830/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/8848,Storm Water Drain,Completed,NE-ROYAPURAM,60,52000,"Improvements and Minor Repairs to Existing Storm water Drain at Jones Lane in Dn-60, Unit-13,Zone-5 (Asset Code- 055/2640/4843/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/8849,Storm Water Drain,Completed,NE-ROYAPURAM,60,113000,"Improvements and Minor repairs to Existing SWD at NSC Bose Road in Dn-60, Unit-13,Zone-5 (Asset Code- 055/2632/4840/2013-14 )",Own Sources,5,2017-18,2018-19 NE/2017-18/8855,Storm Water Drain,Completed,NE-ROYAPURAM,60,75000,"Improvements and Minor repairs to Existing SWD at North Fort side road in Div-60, Unit-13, Zone-05 (Asset Code-055/2664/4839/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/8856,Storm Water Drain,Completed,NE-ROYAPURAM,60,90000,"Improvements and Minor repairs to Existing SWD at Flag staff house road in Div-60, Unit-13, Zone-05 (Asset Code- 055/2663/4838/2013-14)",Own Sources,5,2017-18,2018-19 NE/2017-18/8857,Storm Water Drain,Completed,NE-ROYAPURAM,60,139000,"Improvements and Minor repairs to Existing SWD at Kamarajar Salai Div-60, Unit-13, Zone-05. (Asset Code- 055/2627/4837/2013-14 )",Own Sources,5,2017-18,2017-18 NE/2017-18/8858,Storm Water Drain,Completed,NE-ROYAPURAM,60,136000,"Improvements and Minor repairs to Existing SWD at Rajaji Salai (West) Div-60, Unit-13, Zone-05. Asset Code- 055/2646/4836/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8859,Storm Water Drain,Completed,NE-ROYAPURAM,60,123000,"Improvements and Minor repairs to Existing SWD at Rajaji Salai (East-1) Street Div-60, Unit-13, Zone-05 Asset Code- 055/2646/4834/2013-14",Own Sources,5,2017-18,2017-18 NE/2017-18/8860,Storm Water Drain,Completed,NE-ROYAPURAM,60,149000,"Improvements and Minor Repairs to Existing Storm Water Drain at Rajaji Salai (East) Street Div-60, Unit-13, Zone-05. Asset Code- 055/2646/6853/2014-15",Own Sources,5,2017-18,2017-18 NE/2017-18/8861,Storm Water Drain,Completed,NE-ROYAPURAM,60,141000,"Improvements and Minor Repairs to Existing Storm Water Drain at Light House Road (West) Street Div-60, Unit-13, Zone-05. (Asset Code- 055/15609/4833/2013-14)",Own Sources,5,2017-18,2017-18 NE/2017-18/8862,Storm Water Drain,Completed,NE-ROYAPURAM,60,132000,"Improvements and Minor Repairs to Existing Storm Water Drain at Post Office Street in Div-60, Unit-13, Zone-05 (Asset Code- 055/2653/7534/2014-15 )",Own Sources,5,2017-18,2017-18 NE/2017-18/8863,Storm Water Drain,Completed,NE-ROYAPURAM,60,51000,"Improvements and Minor Repairs to Existing Storm Water Drain at Mooker Nallamuthu Streetin Div-60, Unit-13, Zone-05. (Asset Code- 055/2587/6856/2014-15 )",Own Sources,5,2017-18,2017-18 NE/2017-18/9528,Buildings,Completed,NE-ROYAPURAM,60,162000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENTS TO E-TOILET AT JAFFAR SARANG STREET IN DIV-60,UNIT-13,Z-05 (ASSET CODE- 033/2578/1064/2015-16 )",Own Sources,5,2017-18,2018-19 Q/2017-18/12111,Storm Water Drain,Completed,Q-Solid Waste Management,60,9990000,REMOVAL OF GARBAGE AND CONSTRUCTION DEBRIS ALONG THE COOVUM RIVER BANKS FROM THE BAY OF BENGAL MOUTH OF THE COOVUM RIVER TO THE MADURAVAYAL BYEPASS WITHIN THE CHENNAI CORP LIMIT - CRRT,Own Sources,5,2017-18,2018-19 Q/2017-18/1705,Storm Water Drain,Completed,Q-Solid Waste Management,60,9990000,REMOVAL OF GARBAGE AND CONSTRUCTION DEBRIS ALONG THE COOVUM RIVER BANKS FROM THE BAY OF BENGAL MOUTH OF THE COOVUM RIVER TO THE MADURAVAYAL BYEPASS WITHIN THE CHENNAI CORP LIMIT - CRRT,Grants,5,2017-18,2017-18 BR/2017-18/13674,Roads,Completed,BR-Bus Route Roads,61,949000,"Providing center median / Rectification, lane making, etc, at various bus roads in Zone-4",Own Sources,5,2017-18,2018-19 BR/2017-18/17135,Roads,Completed,BR-Bus Route Roads,61,1880000,"Restoration of road cut made by CMWSSB at Rukmani lakshmipathy salai (water line -1, West - Ethiraj salai Jn. to Rajarathinam stadium L=520m) in Dn-61, Zone-V against Challan No. BR/2017-18/0030439.",Deposit Works,5,2017-18,2018-19 BR/2017-18/17136,Roads,Completed,BR-Bus Route Roads,61,1920000,"Restoration of road cut made by CMWSSB at Rukmani lakshmipathy salai (water line 2 - Rajarathinam stadium to Pantheon Jn. L=530m) in Dn-61, Zone-V against Challan No. BR/2017-18/0030439.",Deposit Works,5,2017-18,2018-19 BR/2017-18/17216,Roads,Completed,BR-Bus Route Roads,61,1825000,"Restoration of road cut made by CMWSSB at Ethiraj salai (Ethiraj salai Jn. to DLF Building) Dn-61, Zone-V against Challan No. BR/2017-18/00030439.",Deposit Works,5,2017-18,2018-19 BR/2017-18/1723,Road Cut,Completed,BR-Bus Route Roads,61,119000,Restoration of Road cud made by TANGEDCO at Pantheon Road in Zone-5 against challan:BR/2017-18/0011965,Deposit Works,5,2017-18,2019-20 BR/2017-18/17280,Roads,Completed,BR-Bus Route Roads,61,775000,"Restoration of road cut made by CMWSSB at Rukmani lakshmipathy salai near Rajarathinam stadium in Dn-61, Zone-V against Challan No. BR/2017-18/00030439.",Deposit Works,5,2017-18,2019-20 D/2017-18/15466,Storm Water Drain,Completed,D-Storm Water Drains,61,2485000,"Construction of storm water drain of size 900 x 900 mm along Mayor Ramanathan Salai from junction of Gengureddy Subway southern end up to junction of East Ramanathan salai in Division 61, Zone - V.",Own Sources,5,2017-18,2018-19 NE/2017-18/1048,Buildings,Completed,NE-ROYAPURAM,61,2310000,"CONSTRUCTION OF BOYS TOILET AND PROVIDING OF CHILDREN PLAYING APPARATUS AT CHENNAI MIDDLE SCHOOL VEERASAMY STREET IN DIV-61, UNIT-14, ZONE-5 (MLA FUND)",MLACDS,5,2017-18,2018-19 NE/2017-18/15599,Buildings,Completed,NE-ROYAPURAM,61,3000000,"PROPOSED CONSTRUCTION RESOURCE RECOVERY CENTERS AT AYYA SAMY STREET (OLD DPF) IN DIV-61, UNIT-14, ZONE-V",Own Sources,5,2017-18,2019-20 NE/2017-18/1590,Buildings,Completed,NE-ROYAPURAM,61,136000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT EGMORE HIGH ROAD IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1592,Buildings,Completed,NE-ROYAPURAM,61,144000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT HALLS ROAD IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1599,Buildings,Completed,NE-ROYAPURAM,61,72000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT WHANELS ROAD IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1605,Buildings,Completed,NE-ROYAPURAM,61,64000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT SAMY STREET IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1606,Buildings,Completed,NE-ROYAPURAM,61,66000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT RANGACHARI STREET IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1607,Buildings,Completed,NE-ROYAPURAM,61,37000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT GOPALSAMY NAGAR (GENGU (R) ROAD IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1608,Buildings,Completed,NE-ROYAPURAM,61,22600,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT BOOPATHY NAGAR (GENGU (R) ROAD IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1609,Buildings,Completed,NE-ROYAPURAM,61,42000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT BOOPATHY NAGAR (GENGU (R) ROAD IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1610,Buildings,Completed,NE-ROYAPURAM,61,48800,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT BOOPATHY NAGAR IN DN-61, U-14, Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1623,Buildings,Completed,NE-ROYAPURAM,61,86000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT ETHIRAJ LANE IN DN-61, U-14,Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1625,Buildings,Completed,NE-ROYAPURAM,61,50900,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT MONTIETH LANE IN DN-61, U-14,Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1627,Buildings,Completed,NE-ROYAPURAM,61,76000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT DRIVER STREET IN DN-61, U-14,Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1628,Buildings,Completed,NE-ROYAPURAM,61,45000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT VELAYUTHAM STREET IN DN-61, U-14,Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1629,Buildings,Completed,NE-ROYAPURAM,61,63000,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT AYYASAMY ROAD (SLUM) IN DN-61, U-14,Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1631,Buildings,Completed,NE-ROYAPURAM,61,77000,"DESILTING AND IMPROVEMENT TO STORM WATER DRAIN AT SANTHOSH NAGAR IN DN-61, U-14,Z-5.",Own Sources,5,2017-18,2018-19 NE/2017-18/1632,Buildings,Completed,NE-ROYAPURAM,61,19400,"REPAIRS AND IMPROVEMENT TO STORM WATER DRAIN AT CHINNA KULANDAI STREET IN DN-61, U-14, Z-V",Own Sources,5,2017-18,2018-19 NE/2017-18/4047,Roads,Completed,NE-ROYAPURAM,61,430000,"RAISING OF MANHOLE DOORS AND CUTTING THE EXISTING CONCRETE SURFACE AT KENNET LANE IN DIV-61, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5718,Roads,Completed,NE-ROYAPURAM,61,311000,"IMPROVEMENTS TO BT ROAD AT VELAYUTHAM 3RD LINK TO TRANSPORT LANE IN DN-61,UNIT-14,,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5739,Roads,Completed,NE-ROYAPURAM,61,317000,"IMPROVEMENTS TO CC ROAD AT IYYASAMY STREET IN DN-61,UNIT-14,,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5755,Roads,Completed,NE-ROYAPURAM,61,311000,"Improvements to BT Road at Montieth Lane in division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5758,Roads,Completed,NE-ROYAPURAM,61,264000,"IMPROVEMENTS TO CC ROAD AT ABDUL HUSSAIN STREET IN DN-61,UNIT-14,,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5760,Roads,Completed,NE-ROYAPURAM,61,793000,"IMPROVEMENTS TO CC ROAD AT VELAYUTHAM 1ST,2ND AND 3RD LANE STREET IN DN-61,UNIT-14,,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5763,Roads,Completed,NE-ROYAPURAM,61,282000,"IMPROVEMENTS TO CC ROAD AT SAIT COLONY 2ND STREET IN DN-61,UNIT-14,,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5770,Roads,Completed,NE-ROYAPURAM,61,105000,"IMPROVEMENTS TO CC ROAD AT MUTHUKON STATUE IN DN-61,UNIT-14, ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/8488,Storm Water Drain,Completed,NE-ROYAPURAM,61,21900,"Desilting of Storm Water Drain at Boopathy Nagar in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8490,Storm Water Drain,Completed,NE-ROYAPURAM,61,49600,"Desilting of Storm Water Drain at Santhosh Nagar in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8491,Storm Water Drain,Completed,NE-ROYAPURAM,61,33000,"Desilting of Storm Water Drain at Ayyasamy Road (Slum) in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8492,Storm Water Drain,Completed,NE-ROYAPURAM,61,19700,"Desilting of Storm Water Drain at Velayutham Street in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8493,Storm Water Drain,Completed,NE-ROYAPURAM,61,61000,"Desilting of Storm Water Drain at Driver Street in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8494,Storm Water Drain,Completed,NE-ROYAPURAM,61,26400,"Desilting of Storm Water Drain at Montieth Lane in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8495,Storm Water Drain,Completed,NE-ROYAPURAM,61,44000,"Desilting of Storm Water Drain at Ethiraj Lane in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8549,Storm Water Drain,Completed,NE-ROYAPURAM,61,22600,"Desilting of Storm Water Drain at Boopathy Nagar (Gengu Reddy Road) in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8550,Storm Water Drain,Completed,NE-ROYAPURAM,61,11800,"Desilting of Storm Water Drain at Boopathy Nagar (Gengu Reddy Road) in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8584,Storm Water Drain,Completed,NE-ROYAPURAM,61,24000,"Desilting of Storm Water Drain at Gopalsamy Nagar (Gengu Reddy Road) in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8585,Storm Water Drain,Completed,NE-ROYAPURAM,61,33000,"Desilting of Storm Water Drain at Rangachari Street in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8587,Storm Water Drain,Completed,NE-ROYAPURAM,61,35000,"Desilting of Storm Water Drain at Samy Street in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8590,Storm Water Drain,Completed,NE-ROYAPURAM,61,53500,"Desilting of Storm Water Drain at Whanels Road in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8591,Storm Water Drain,Completed,NE-ROYAPURAM,61,110000,"Desilting of Storm Water Drain at Halls Road in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8593,Storm Water Drain,Completed,NE-ROYAPURAM,61,79000,"Desilting of Storm Water Drain at Egmore High Road in Division-61, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 B/2017-18/16181,Buildings,Completed,B-Buildings,62,7040699,"MLA FUND 2017-18, CONSTRUCTION OF MULTI PURPOSE HALL AT ADHIKESAVALU STREET IN DIV-62, UNIT-14, ZONE-05",MLACDS,5,2017-18,2019-20 BR/2017-18/11377,Roads,Completed,BR-Bus Route Roads,62,57000,Restoration of road cut made by CMWSSB at Arunachalam street in Zone-5 against challan no. BR/2017-18/0006439,Deposit Works,5,2017-18,2018-19 NE/2017-18/10225,Buildings,Completed,NE-ROYAPURAM,62,138000,"REPAIRS AND ANNUAL MAINTENANCE OF BOILER AT RELIEF CENTRE IN CHINTADRIPET, DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/1042,Storm Water Drain,Completed,NE-ROYAPURAM,62,1525000,"CONSTRUCTION OF STORM WATER DRAIN AT ARUNACHALAM STREET FROM ZION CHURCH TO JUNCTION OF LAFOND STREET IN DN-62,UNIT- 14,ZONE-5 (FOR MLA FUND)",Own Sources,5,2017-18,2017-18 NE/2017-18/1044,Buildings,Completed,NE-ROYAPURAM,62,490000,"PROPOSED CONSTRUCTION OF COMPOSITE YARD AT ADHIKESAVALU STREET IN DN-62,UNIT-14,ZONE-5 (FOR MLA FUND)",Own Sources,5,2017-18,2017-18 NE/2017-18/1045,Storm Water Drain,Completed,NE-ROYAPURAM,62,360000,"PROVIDING PIPELINE ARRANGEMENTS FOR DRAINING RAIN WATER CONNECTING FROM PADAVATTAMMAN KOIL STREET TO COOVAM RIVER AT WEST COOVAM ROAD IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2017-18,2017-18 NE/2017-18/10594,Buildings,Completed,NE-ROYAPURAM,62,282000,"MLA FUND 2017-18, LAYING OF CEMENT CONCRETE ROAD WITH M30 GRADE AT RAJA GOPAL LANE IN DIVISION-62, UNIT-14, ZONE-05",MLACDS,5,2017-18,2018-19 NE/2017-18/10595,Buildings,Completed,NE-ROYAPURAM,62,290000,"MLA FUND 2017-18, LAYING OF BITUMINUS CONCRETE ROAD AT AGRAHARAM STREET FROM KALAVAI (C) ST TO IYYA MUDHALI STREET, IN DIVISION-62, UNIT-14, ZONE-05.",MLACDS,5,2017-18,2018-19 NE/2017-18/10597,Buildings,Completed,NE-ROYAPURAM,62,438000,"MLA FUND 2017-18, LAYING OF CEMENT CONCRETE ROAD WITH M30 GRADE AT SAMY (N) LANE IN DIVISION-62, UNIT-14, ZONE-05",MLACDS,5,2017-18,2018-19 NE/2017-18/10599,Buildings,Completed,NE-ROYAPURAM,62,428000,"MLA FUND-2017-18, LAYING OF CEMENT CONCRETE ROAD WITH M30 GRADE AT EAST COOVAM ROAD IN DIVISION-62, UNIT-14, ZONE-05",MLACDS,5,2017-18,2018-19 NE/2017-18/10624,Buildings,Completed,NE-ROYAPURAM,62,1617000,"MLA FUND 2017-18, LAYING OF CEMENT CONCRETE ROAD AT AMMA NAGAR IN DIVISION-62, UNIT-14, ZONE-05",MLACDS,5,2017-18,2018-19 NE/2017-18/1263,Storm Water Drain,Completed,NE-ROYAPURAM,62,138000,"DESILTING OF STORM WATER DRAIN AT ARUNACHALAM ROAD AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1266,Storm Water Drain,Completed,NE-ROYAPURAM,62,8100,"DESILTING OF STORM WATER DRAIN AT REX STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1268,Storm Water Drain,Completed,NE-ROYAPURAM,62,34000,"DESILTING OF STORM WATER DRAIN BAZZAR STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1269,Storm Water Drain,Completed,NE-ROYAPURAM,62,67000,"DESILTING OF STORM WATER DRAIN SINGANNA (C) STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1272,Storm Water Drain,Completed,NE-ROYAPURAM,62,22000,"DESILTING OF STORM WATER DRAIN PUMPING STATION ROAD AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1274,Storm Water Drain,Completed,NE-ROYAPURAM,62,27600,"DESILTING OF STORM WATER DRAIN DY. MAYOR KABALA MOORTHY SALAI AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1276,Storm Water Drain,Completed,NE-ROYAPURAM,62,22000,"DESILTING OF STORM WATER DRAIN AT BALAKRISHNAN STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1277,Storm Water Drain,Completed,NE-ROYAPURAM,62,30900,"DESILTING OF STORM WATER DRAIN AT AYYA (M) STREET IN DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1278,Storm Water Drain,Completed,NE-ROYAPURAM,62,27300,"DESILTING OF STORM WATER DRAIN AT SOUTH PADAVATTAMMAN KOVIL STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1280,Storm Water Drain,Completed,NE-ROYAPURAM,62,17600,"DESILTING OF STORM WATER DRAIN AT ST. LAZAR CHURCH STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1282,Storm Water Drain,Completed,NE-ROYAPURAM,62,30000,"DESILTING OF STORM WATER DRAIN AT VENKATESAN STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1284,Storm Water Drain,Completed,NE-ROYAPURAM,62,60000,"DESILTING OF STORM WATER DRAIN AT WALLERS ROAD DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1289,Storm Water Drain,Completed,NE-ROYAPURAM,62,11000,"DESILTING OF STORM WATER DRAIN AT ATHIPATTAN STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1291,Storm Water Drain,Completed,NE-ROYAPURAM,62,33000,"DESILTING OF STORM WATER DRAIN AT RITCHIE STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1293,Storm Water Drain,Completed,NE-ROYAPURAM,62,13200,"DESILTING OF STORM WATER DRAIN AT ULAGAPPA STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1295,Storm Water Drain,Completed,NE-ROYAPURAM,62,5500,"DESILTING OF STORM WATER DRAIN AT GURUVAPPA ROAD AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1297,Buildings,Completed,NE-ROYAPURAM,62,27600,"DESILTING OF STORM WATER DRAIN AT SAMY PANDARAM STREET (KALAVAI ST) AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/1301,Buildings,Completed,NE-ROYAPURAM,62,27900,"DESILTING OF STORM WATER DRAIN AT LAFOND STREET AT DN-62, U-14, Z-5.",Own Sources,5,2017-18,2017-18 NE/2017-18/15529,Buildings,Completed,NE-ROYAPURAM,62,3710000,"PROPOSED CONSTRUCTION RESOURCE RECOVERY CENTER AT ADHIKESAVALU STREET IN DIVISION -62, UNIT-14, ZONE-5",Own Sources,5,2017-18,2019-20 NE/2017-18/16358,Buildings,Completed,NE-ROYAPURAM,62,225000,"Repairs and Improvements to Night Shelter at padavattamman koil street Div 62, Unit-14,Zone-5",Own Sources,5,2017-18,2019-20 NE/2017-18/17310,Roads,Completed,NE-ROYAPURAM,62,83000,"IMPROVEMENTS TO CC ROADS AT MUKKIYAMMAN KOIL STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2020-21 NE/2017-18/5454,Roads,Completed,NE-ROYAPURAM,62,432000,"IMPROVEMENTS TO BT ROAD AT SINGANNA (C) STREET IN WARD-62, UNIT-14, ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5478,Roads,Completed,NE-ROYAPURAM,62,432000,"IMPROVEMENTS TO BT ROAD AT KALAVAI STREET IN WARD-62,UNIT -14,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5485,Roads,Completed,NE-ROYAPURAM,62,865000,"IMPROVEMENTS TO BT ROAD AT WEST COOVAM RIVER ROAD (ARUNACHALAM ROAD TO SAMY(N) STREET IN WARD-62,UNIT-14,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5525,Roads,Completed,NE-ROYAPURAM,62,432000,"IMPROVEMENTS TO BT ROAD AT VENKATESAN STREET IN WARD-62,UNIT-14,ZONE-5",Own Sources,5,2017-18,2018-19 NE/2017-18/5541,Roads,Completed,NE-ROYAPURAM,62,692000,IMPROVEMENTS TO BT ROAD AT ATHIPATTAN STREET(USMANKHAN STREEET TO SINGANNA STREET),Own Sources,5,2017-18,2018-19 NE/2017-18/5557,Roads,Completed,NE-ROYAPURAM,62,796000,"IMPROVEMENTS TO BT ROAD AT PADAVATAMMAN KOIL STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5594,Roads,Completed,NE-ROYAPURAM,62,1280000,"IMPROVEMENTS TO BT ROAD AT IYYA (M) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5598,Roads,Completed,NE-ROYAPURAM,62,529000,"IMPROVEMENTS TO CC ROAD AT RAJAGOPAL STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5599,Roads,Completed,NE-ROYAPURAM,62,398000,"IMPROVEMENTS TO CC ROAD AT KRISHNAPPA (C) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5602,Roads,Completed,NE-ROYAPURAM,62,613000,"IMPROVEMENTS TO CC ROAD AT SAMY (N) LANE IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5604,Roads,Completed,NE-ROYAPURAM,62,244000,"IMPROVEMENTS TO CC ROAD AT SIVAPRAKASAM LANE IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5615,Roads,Completed,NE-ROYAPURAM,62,368000,"IMPROVEMENTS TO CC ROAD AT DAWOOD SAHIB STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5643,Roads,Completed,NE-ROYAPURAM,62,284000,"IMPROVEMENTS TO CC ROAD AT SOUTH PADAVATAMMAN KOIL STREET SOUTH IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5792,Roads,Completed,NE-ROYAPURAM,62,529000,"IMPROVEMENTS TO CC ROAD AT WEST PADAVATAMMAN KOIL STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5794,Roads,Completed,NE-ROYAPURAM,62,211000,"IMPROVEMENTS TO CC ROAD AT WALLERS LANE IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2017-18,2019-20 NE/2017-18/8261,Storm Water Drain,Completed,NE-ROYAPURAM,62,69000,"Repairs and Improvements to SWD at Rex Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8263,Storm Water Drain,Completed,NE-ROYAPURAM,62,186000,"Repairs and Improvements to SWD at Arunachalam Road in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8264,Storm Water Drain,Completed,NE-ROYAPURAM,62,56000,"Repairs and improvements to SWD at Singanna (C) Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8269,Storm Water Drain,Completed,NE-ROYAPURAM,62,58000,"Repairs and Improvements to SWD at Pumping Station Road in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8270,Storm Water Drain,Completed,NE-ROYAPURAM,62,31600,"Repairs and Improvements to SWD at Deputy Mayor Kabalamoorthy Salai in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8272,Storm Water Drain,Completed,NE-ROYAPURAM,62,28900,"Repairs and Improvements to SWD at South Padavatamman Koil Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8273,Storm Water Drain,Completed,NE-ROYAPURAM,62,23000,"Repairs and Improvements to SWD at St. Lazar Church Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8274,Storm Water Drain,Completed,NE-ROYAPURAM,62,28000,"Repairs and Improvements to SWD at Venkatesan Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8279,Storm Water Drain,Completed,NE-ROYAPURAM,62,56000,"Repairs and Improvements to SWD at Athipattan Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8366,Storm Water Drain,Completed,NE-ROYAPURAM,62,20800,"Desilting of Storm Water Drain at Chella Pillayar Koil Street in Division-63, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8431,Storm Water Drain,Completed,NE-ROYAPURAM,62,40700,"Repairs and Improvements to SWD at Ritchie Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8433,Storm Water Drain,Completed,NE-ROYAPURAM,62,5700,"Repairs and Improvements to SWD at Ulagappa Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8434,Storm Water Drain,Completed,NE-ROYAPURAM,62,14400,"Repairs and Improvements to SWD at Guruvappa Street in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/8436,Storm Water Drain,Completed,NE-ROYAPURAM,62,29900,"Repairs and Improvements to SWD at Samy (P) street ( Kalavai street )in Division-62, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 BR/2017-18/15197,Roads,Completed,BR-Bus Route Roads,63,705000,Painting on existing kerb and foot path repair in Walajah road and Thermoplastic paint on speed breaker at EVK Sampath salai in Zone 5,Own Sources,5,2017-18,2018-19 NE/2017-18/15536,Buildings,Completed,NE-ROYAPURAM,63,3000000,"PROPOSED CONSTRUCTION RESOURCE RECOVERY CENTERS AT VEERABATHIRAN STREET (D CATTLE DEPPO) IN DIV-63, UNIT-14, ZONE-V",Own Sources,5,2017-18,2019-20 NE/2017-18/1835,Buildings,Completed,NE-ROYAPURAM,63,999000,"Improvements to public convienience at various places in Dn.63,U-14,Z-05.",Own Sources,5,2017-18,2018-19 NE/2017-18/5516,Roads,Completed,NE-ROYAPURAM,63,391000,"Improvements to BT Road at Thayar Sahib market lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5521,Roads,Completed,NE-ROYAPURAM,63,311000,"Improvements to BT Road at Boobegam 2nd Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5526,Roads,Completed,NE-ROYAPURAM,63,778000,"Improvements to BT Road at Subedhar Hussain Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5529,Roads,Completed,NE-ROYAPURAM,63,467000,"Improvements to BT Road at Venkatesan 1st Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5533,Roads,Completed,NE-ROYAPURAM,63,657000,"Improvements to CC Road at Venkatesan 2nd Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5665,Roads,Completed,NE-ROYAPURAM,63,584000,"Improvements to BT Road at Boobegam 4th Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5666,Roads,Completed,NE-ROYAPURAM,63,484000,"Improvements to BT Road at Sami (C) Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5672,Roads,Completed,NE-ROYAPURAM,63,519000,"Improvements to BT Road at Abdhul Kadar Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5677,Roads,Completed,NE-ROYAPURAM,63,692000,"Improvements to BT Road at John Mohammed Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5681,Roads,Completed,NE-ROYAPURAM,63,1125000,"Improvements to CC Road at Burrah Sahib Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5682,Roads,Completed,NE-ROYAPURAM,63,865000,"Improvements to BT Road at Narayanan (N) Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5690,Roads,Completed,NE-ROYAPURAM,63,519000,"Improvements to CC Road at Lathuram Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5695,Roads,Completed,NE-ROYAPURAM,63,865000,"Improvements to BT Road at LGN Road, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5699,Roads,Completed,NE-ROYAPURAM,63,467000,"Improvements to BT Road at Hussain Mulk Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5702,Roads,Completed,NE-ROYAPURAM,63,830000,"Improvements to BT Road at Nainiayappa Maistry Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5704,Roads,Completed,NE-ROYAPURAM,63,622000,"Improvements to BT Road at Venkatesan 1st Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5706,Roads,Completed,NE-ROYAPURAM,63,709000,"Improvements to BT Road at Maroof sahib Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5712,Roads,Completed,NE-ROYAPURAM,63,346000,"Improvements to BT Road at Gopal Doss Road, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5868,Roads,Completed,NE-ROYAPURAM,63,744000,"Improvements to BT Road at Nagappa Mudali Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5871,Roads,Completed,NE-ROYAPURAM,63,519000,"Improvements to BT Road at Subbaraya Mudali Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5872,Roads,Completed,NE-ROYAPURAM,63,138000,"Improvements to BT Road at Maroof sahib Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5873,Roads,Completed,NE-ROYAPURAM,63,501000,"Improvements to BT Road at John Mohamed Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5875,Roads,Completed,NE-ROYAPURAM,63,692000,"Improvements to CC Road at Lathuram Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5876,Roads,Completed,NE-ROYAPURAM,63,674000,"Improvements to BT Road at Venkatachala Achari Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5879,Roads,Completed,NE-ROYAPURAM,63,2041000,"Improvements to CC Road at General Peters Road, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5885,Roads,Completed,NE-ROYAPURAM,63,726000,"Improvements to CC Road at V.N Doss Road, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5886,Roads,Completed,NE-ROYAPURAM,63,363000,"Improvements to CC Road at Sathu Chetty Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5887,Roads,Completed,NE-ROYAPURAM,63,865000,"Improvements to CC Road at Burrah Sahib Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5891,Roads,Completed,NE-ROYAPURAM,63,692000,"Improvements to BT Road at Venkatesan 2nd Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5892,Roads,Completed,NE-ROYAPURAM,63,830000,"Improvements to CC Road at Subedhar Hussain Street in ward-63, Unit-14, Zone-V.",Own Sources,5,2017-18,2018-19 NE/2017-18/5895,Roads,Completed,NE-ROYAPURAM,63,1762000,"Improvements to CC Road at Boobegum 2nd 3rd & 4th Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5899,Roads,Completed,NE-ROYAPURAM,63,207000,"Improvements to BT Road at Thayar Sahib Market lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5901,Roads,Completed,NE-ROYAPURAM,63,88000,"Improvements to CC Road at Venkatesan 1st lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5904,Roads,Completed,NE-ROYAPURAM,63,88000,"Improvements to CC Road at Venkatesan 2nd lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5905,Roads,Completed,NE-ROYAPURAM,63,211000,"Improvements to CC Road at Narayanan (N) 7th Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5906,Roads,Completed,NE-ROYAPURAM,63,134000,"Improvements to CC Road at Kalimanpuram 1st Lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5908,Roads,Completed,NE-ROYAPURAM,63,158000,"Improvements to CC Road at Kalimanpuram 2nd Lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5909,Roads,Completed,NE-ROYAPURAM,63,211000,"Improvements to CC Road at Narayanan (n) 6th Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5910,Roads,Completed,NE-ROYAPURAM,63,596000,"Improvements to CC Road at Narayanan (n) 8th Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5919,Roads,Completed,NE-ROYAPURAM,63,564000,"Improvements to BT Road at Raza Hyder Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5958,Roads,Completed,NE-ROYAPURAM,63,292000,"Improvements to BT Road at Syed Noor Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5964,Roads,Completed,NE-ROYAPURAM,63,705000,"Improvements to BT Road at Ramasamy Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5985,Roads,Completed,NE-ROYAPURAM,63,335000,"Improvements to BT Road at Kalimanpuram 1st 2nd Lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5986,Roads,Completed,NE-ROYAPURAM,63,511000,"Improvements to BT Road at Mohan Doss Road & Lane, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5988,Roads,Completed,NE-ROYAPURAM,63,670000,"Improvements to BT Road at Ramasamy Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5990,Roads,Completed,NE-ROYAPURAM,63,670000,"Improvements to BT Road at Jesan Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5992,Roads,Completed,NE-ROYAPURAM,63,1101000,"Improvements to BT Road at Narayana Naikken 1st to 9th and 11th main street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5994,Roads,Completed,NE-ROYAPURAM,63,599000,"Improvements to BT Road at Kalimanpuram Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5995,Roads,Completed,NE-ROYAPURAM,63,441000,"Improvements to BT Road at Perumal Mudali Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/5997,Roads,Completed,NE-ROYAPURAM,63,437000,"Improvements to BT Road at Raza Hyder Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/6000,Roads,Completed,NE-ROYAPURAM,63,370000,"Improvements to BT Road at Syed Noor Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/6001,Roads,Completed,NE-ROYAPURAM,63,370000,"Improvements to BT Road at Gulam Mohideen Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/6002,Roads,Completed,NE-ROYAPURAM,63,599000,"Improvements to BT Road at Ameernisa Begam Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/6004,Roads,Completed,NE-ROYAPURAM,63,140000,"Improvements to BT Road at Perumal Mudali 1st Street, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/6006,Roads,Completed,NE-ROYAPURAM,63,529000,"Improvements to CC Road at Veeranpuram, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2018-19 NE/2017-18/6008,Roads,Completed,NE-ROYAPURAM,63,635000,"Improvements to CC Road at Kalimanpuram, ward-63, Unit-14, Zone-V",Own Sources,5,2017-18,2019-20 NE/2017-18/6809,Storm Water Drain,Completed,NE-ROYAPURAM,63,320000,"Improvements to storm water drain at G.P.road in Dn-63,U-14,-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/6811,Storm Water Drain,Completed,NE-ROYAPURAM,63,690000,"Repairs and Improvements to storm water drain at Bharathi salai in Dn-63,U-14,Z-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/6822,Storm Water Drain,Completed,NE-ROYAPURAM,63,600000,"Repairs and Improvements to storm water drain at Chella Pillayar Koil Street in Dn-63,U-14,Z-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/6829,Storm Water Drain,Completed,NE-ROYAPURAM,63,579100,"Repairs and Improvements to storm water drain at L.G.N.road and Blackkers road in Dn-63,U-14,Z-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/8369,Storm Water Drain,Completed,NE-ROYAPURAM,63,33900,"Desilting of Storm Water Drain at L.G.N. Road and Blackers Road in Division-63, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 NE/2017-18/8373,Storm Water Drain,Completed,NE-ROYAPURAM,63,37000,"Desilting of storm water drain at Bharathi Salai in Dn-63,U-14,Z-05.",Own Sources,5,2017-18,2017-18 NE/2017-18/8594,Storm Water Drain,Completed,NE-ROYAPURAM,63,37000,"Desilting of Storm Water Drain at G.P. Road in Division-63, Unit-14, Zone-V",Own Sources,5,2017-18,2017-18 D/2017-18/12322,Storm Water Drain,Completed,D-Storm Water Drains,64,2373000,"Construction of storm water drain of size 900x900mm along Vasantham nagar 3rd street from Kalaimagal nagar to appasamy street in Dn- 64,Zone-VI.",Own Sources,6,2017-18,2018-19 D/2017-18/12323,Storm Water Drain,Completed,D-Storm Water Drains,64,2162000,"Construction of storm water drain of size 900x900mm along School road from School road chainage 0.0M to School road chainage 100.0M in Dn- 64, Zone-VI.",Own Sources,6,2017-18,2018-19 D/2017-18/12324,Storm Water Drain,Completed,D-Storm Water Drains,64,1953000,"Construction of storm water drain of size 900x900mm along School road from School road chainage 100.0M to School road chainage 190.0M in Dn- 64, Zone-VI.",Own Sources,6,2017-18,2018-19 D/2017-18/12391,Storm Water Drain,Completed,D-Storm Water Drains,64,1730000,"Construction of storm water drain of size 900x900mm along school road from School road chainage 190.0M to School road chainage 270.0M in Dn- 64, Zone-VI.",Own Sources,6,2017-18,2018-19 D/2017-18/12394,Storm Water Drain,Completed,D-Storm Water Drains,64,2464000,"Construction of storm water drain of size 900x900mm along Appasamy street from Appasamy street chainage 0.0M to Appasamy street chainage 125.0M in Dn- 64, Zone-VI.",Own Sources,6,2017-18,2018-19 D/2017-18/12396,Storm Water Drain,Completed,D-Storm Water Drains,64,2484000,"NAME OF WORK: Construction of storm water drain of size 900x900mm along Appasamy street from Appasamy street chainage 125.0M to Appasamy street chainage 240.0M in Dn- 64, Zone-VI.",Own Sources,6,2017-18,2018-19 L/2017-18/10300/C,Electrical,Completed,L-Electrical,64,588600,Electrification in smart classes in zone VI,Own Sources,6,2017-18,2018-19 L/2017-18/4277,Electrical,Completed,L-Electrical,64,782900,Supply and replacement of 1985Mtrs of damaged 2x16sqmm UG cables at chronicle faulty locations at Cement concrete road and Block topped road in div 64 zone VI (Phase 2),Own Sources,6,2017-18,2017-18 L/2017-18/4278,Electrical,Completed,L-Electrical,64,799300,Supply and replacement of 2060Mtrs of damaged 2x16sqmm UG cables at chronicle faulty locations at Cement concrete road and Block topped road in div 64 zone VI (Phase 1),Own Sources,6,2017-18,2017-18 L/2017-18/4434,Electrical,Completed,L-Electrical,64,458700,"Supply and replacement of 10nos of Damaged, Short in size and rusted lamp post at Chelliamman nagar in div 64 under kolathur section zone VI",Own Sources,6,2017-18,2017-18 L/2017-18/6449,Electrical,Completed,L-Electrical,64,907300,"Supply and replacement of 56nos of Damaged, Short in size and rusted lamp post at various places in div 64 under kolathur section zone VI Phase - 1",Own Sources,6,2017-18,2017-18 L/2017-18/6461,Electrical,Completed,L-Electrical,64,991600,"Supply and replacement of 62nos of Damaged, Short in size and rusted lamp post at various places in div 64 under kolathur section zone VI Phase - 2",Own Sources,6,2017-18,2017-18 L/2017-18/6462,Electrical,Completed,L-Electrical,64,875300,"Supply and replacement of 54nos of Damaged, Short in size and rusted lamp post at various places in div 65 under kolathur section zone VI Phase - 1",Own Sources,6,2017-18,2017-18 L/2017-18/6464,Electrical,Completed,L-Electrical,64,959600,"Supply and replacement of 60nos of Damaged, Short in size and rusted lamp post at various places in div 65 under kolathur section zone VI Phase - 2",Own Sources,6,2017-18,2017-18 L/2017-18/6468,Electrical,Completed,L-Electrical,64,1284100,"Supply and replacement of 29nos of Damaged, Short in size and rusted lamp post at Viveganandha nagar main road in div 65 under kolathur section zone VI",Own Sources,6,2017-18,2017-18 NF/2017-18/10378,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,4900000,"Formation of New park around Thamaraikulam at Haridoss nagar main road in Div-64,Unit-15,Zone-6",MLACDS,6,2017-18,2019-20 NF/2017-18/10604,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,98000,"Providing the basic infrastructure requirement for Samsung Smart Class Room in Chennai Higher Secondary School at School Road in DN-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/1067,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,570000,"Construction of Composting Yard Formers market at Sembium redhills road in Div-64,Unit-15,Zone-6.",Grants,6,2017-18,2017-18 NF/2017-18/11732,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,162000,"Laying CC Road at Sarojini Nagar 2nd Cross Street in dn-64,unit-15,zone-06",Own Sources,6,2017-18,2017-18 NF/2017-18/12456,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,85000,"Attending patch work @ various street in Monsoon period 2017 in dn-64,unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/12457,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,31400,"Barricading arrangements for the open canal side at 200 feet road for flood arrangements at various places in dn-64,unit-15,zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/12460,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,49000,"Supply of Flexible Hose for using dewatering of water stagination of flood afftected area in dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/12489,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,61000,"Construction of Inspection Chamber at Anjugam Nagar 1st Cross street,Sembium Redhills Road, M.N. Nagar, and other streets in DN-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/13214,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,76300,"Providing Thermoplastic for speedbreakers at Jayaram Nagar 3rd main road,Poompuhar Nagar 5th street,Poompuhar Nagar 7th Cross Street and Various Streets in Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/1398,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,800000,"Desilting Existing Storm water drain at various street in DN-64,U-16,Z-6.",Own Sources,6,2017-18,2017-18 NF/2017-18/14551,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,90000,Maintenance of park by private agency for the Period of Six Month at V.V.Nagar Park in Dn-64 U-15 Z-06,Own Sources,6,2017-18,2019-20 NF/2017-18/14553,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,125000,Maintenance of park by private agency for the Period of Six Month at Poompuhar Nagar Park in Dn-64 U-15 Z-06,Own Sources,6,2017-18,2019-20 NF/2017-18/14554,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,89000,Maintenance of park by private agency for the Period of Six Month at Anjugam Nagar Park in Dn-64 U-15 Z-06,Own Sources,6,2017-18,2019-20 NF/2017-18/14555,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,119000,Maintenance of park by private agency for the Period of Six Month at OSR Park and Thiruveethiamman Kovil Tank in Dn-64 U-15 Z-06,Own Sources,6,2017-18,2019-20 NF/2017-18/16114,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,563000,"Repairs and Improvements to CPS School Building At Thiruveethiamman Kovil Street In DN-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/16115,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,848000,"Repairs to Improvements to the Exisitng CHSS main building (A-Block) at school road in DN-64,Unit-15,Zone-06",Own Sources,6,2017-18,2018-19 NF/2017-18/16116,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,497000,"Repairs to Improvements to the CPS Building & Kitchen Shed at school road in DN-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/16185,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,383000,"Laying CC Road At Lakshmi Nagar 8th Street in Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/16186,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,787000,"Laying CC Road At Kambar Nagar Anna Street in Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/16188,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,300000,"Laying CC Road At Kambar Nagar Anna 1st Street in Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/4926,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,3119000,"Improvements to the Interior BT Road at Poompuhar Nagar 2nd Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/4937,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,658000,"Improvement To Interior B.T.Road at Poompuhar Nagar 13th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/4939,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,375000,"Improvement To Interior B.T.Road at Poompuhar Nagar 10th Cross street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/4943,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,722000,"Improvement To Interior B.T.Road at Poompuhar Nagar 25th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/4944,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,645000,"Improvement To Interior B.T.Road at Poompuhar Nagar 9th Cross Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/4949,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1540000,"Improvement To Interior B.T.Road at Poompuhar Nagar 23rd street & 26th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5228,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1310000,"Improvement To Interior B.T.Road at Thiru-vi-ka st,Then palani nagar,Jeeva st & Quidemillath St In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5369,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1210000,"Improvement To Interior B.T.Road at Vijaya Lakshmi Nagar and Chitti babu Nagar In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5371,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,298000,"Improvement To Interior B.T.Road at Verita Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5373,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1444000,"Improvement To Interior B.T.Road at Tirupathi Nagar 4th Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5377,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,3960000,"Improvements to the Interior Bt Road at Ambedkar Nagar 1st To 4th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5379,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1710000,"Improvement To Interior B.T.Road at Tirupathi Nagar 4th Cross Street & 3rd Main Road In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5381,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,427000,"Improvement To Interior B.T.Road at Sri Nagar Colony 1st street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5382,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,309000,"Improvement To Interior B.T.Road at Ragavendra Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5384,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,237000,"Improvement To Interior B.T.Road at Adinath Nagar 2nd Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5387,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,2080000,"Improvement To Interior B.T.Road at Alagari Street, Rajaji Street, Anna Street, AT Thenpalani Nagar In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5408,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1277000,"Improvement To Interior B.T.Road at Gandhi Street , Vallalar Street Annai Indra Street , Bharathi Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5410,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,268000,"Improvement To Interior B.T.Road at Kaveri 4th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/5417,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,3470000,"Improvements to the Interior CC Road at Kamarajar nagar,Vinayagar Kovil st, Ambedkar st,Odai In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5424,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,206000,"Improvement To Interior C.C.Road at Bagavathiammal 1st Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5429,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,138000,"Improvement To Interior C.C.Road at Bagavathiammal 2nd Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5431,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,138000,"Improvement To Interior C.C.Road at Bagavathiammal 3rd Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5434,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,138000,"Improvement to the interior C.C.Road at Bagavathiammal 4th Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5438,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,861000,"Improvement to the interior C.C.Road at Bagavathiammal 5th lane Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5450,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1235074,"Improvement to the interior C.C.Road at Bagavathiammal 1st lane In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5455,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1063091,"Improvement to the interior C.C.Road at SVM Padasalai Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5459,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,2750000,"Improvement to the interior C.C.Road at Bajanai Kovil Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5466,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,64,1031000,"Improvement to the interior C.C.Road at Kolathur Colony Thiruveethiamman Kovil Street In Dn-64,Unit-15,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/5470,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,903000,"Improvement To Interior B.T.Road with BC 30mm Thick at Kamaraj Street IN DIV-64, UNIT-15, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5472,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,4916000,"Improvements to the Interior BT Road at Poompuhar Nagar 2nd main Road IN DIV-64, UNIT-15, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/8677,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,190000,"Construction of SWD Link at Sri Velmurugan nagar Lane, supply and fixing of manhole doors in Div-64,Unit-15,Zone-6.",Own Sources,6,2017-18,2019-20 NF/2017-18/8679,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,154000,"Construction of SWD Link by using cement pipes at Tirupathi nagar 4th main road, Lakshmi nagar 6th str in Div-64,Unit-15,Zone-6.",Own Sources,6,2017-18,2019-20 NF/2017-18/8683,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,430000,"Construction of SWD Link at papermills road ( Near Gandhi Statue) in Div-68,Unit-15,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/9076,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,280000,"Desiting of Storm water drain at Poompugar nagar 7th cross street ,V.V Nagar 1st street,East Mada street and various streets in Div-64,Unit-15,Zone-6.",Own Sources,6,2017-18,2017-18 D/2017-18/12478,Storm Water Drain,Completed,D-Storm Water Drains,65,2162000,"Construction of storm water drain of size 900x900mm along Thillai nagar 1st cross street from junction of Selvi nagar main road to dead end in Dn- 65, Zone-VI",Own Sources,6,2017-18,2018-19 D/2017-18/2544,Storm Water Drain,Completed,D-Storm Water Drains,65,2444000,"Dismanlting of eexisting dilapidated storm water drain and Construction of storm water drain of size 600x750mm along Thillai nagar 5th stree from dead end of 5th cross street to Thillai nagar 1st main road in Dn- 65,Zone-VI.",Own Sources,6,2017-18,2017-18 L/2017-18/16592,Electrical,Completed,L-Electrical,65,197000,"PROVISION OF 5 NOS OF 7 MTR M.S. LAMP POST (N.V) WITH 70W SVL FITTINGS AT ANNAI INDIRA NAGAR EXTN IN DIV-65,ZONE-6",Own Sources,6,2017-18,2018-19 L/2017-18/4279,Electrical,Completed,L-Electrical,65,854200,Supply and replacement of 2095Mtrs of damaged 2x16sqmm UG cables at chronicle faulty locations at Cement concrete road and Block topped road in div 65 zone VI (Phase 1),Own Sources,6,2017-18,2017-18 L/2017-18/4280,Electrical,Completed,L-Electrical,65,933500,Supply and replacement of 2365Mtrs of damaged 2x16sqmm UG cables at chronicle faulty locations at Cement concrete road and Block topped road in div 65 zone VI(Phase 2),Own Sources,6,2017-18,2017-18 L/2017-18/6465,Electrical,Completed,L-Electrical,65,1423200,"Supply and replacement of 31nos of Damaged, Short in size and rusted lamp post at G K M Colony 2nd main road in div 65 under kolathur section zone VI",Own Sources,6,2017-18,2017-18 NF/2017-18/10148,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,82000,Construction of damaged swd & doors providing precast concrete slabs at senthil nagar 3rd main rd Dn-65 U-15 Z-06,Own Sources,6,2017-18,2019-20 NF/2017-18/10149,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,77000,"Connection of swd by using cement hume pipes at veenus nagar main road in dn-65,u-15,zn-6",Own Sources,6,2017-18,2019-20 NF/2017-18/1068,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,570000,"Construction of Composting Yard at Makkaram garden Burial ground in Div-65,Unit-15,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/1069,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,570000,"Construction of Composting Yard at GKM Colony Burial Ground in Div-65,Unit-15,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/11226,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,642000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN MALIGAI AVENUE 1ST STREET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/11251,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,810000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN JAYANTHI NAGAR 1ST,2ND AND 3RD CROSS STREET AND KADAPPA ROAD IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/11252,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1254000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN THILLI NAGAR 3RD STREET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/11327,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,490000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN RAJAJI NAGAR 9TH STREET DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/11333,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,403000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN VENUS NAGAR KAMARARAJAR STREET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/11730,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,95000,"Improvements and fixing Ornamental plants,grass and trees for Rohini Park at Rohini Street in Div-65,Unit-15,Zone-6.",Own Sources,6,2017-18,2017-18 NF/2017-18/12401,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1600000,"Laying of Cement Concrete Road @ Rajaji Nagar Extension Road IN Dn-65, Un-15, Z-6.",MPLADS,6,2017-18,2019-20 NF/2017-18/12402,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1600000,"Laying of Cement Concrete Road @ Vegavathi Street Extn In Rajaji Nagar Dn-65 U-15 Z-06,",MPLADS,6,2017-18,2019-20 NF/2017-18/12466,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,85000,"Attending patch work @various street in Monsoon period 2017 DN-65,Unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/13675,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,950000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN GKM COLONY 33RD STREET (REACH 2) DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13676,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,950000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN GKM COLONY 33RD STREET (REACH 1) DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13677,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,609000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN ATHIYAMAN NAGAR 2ND STRET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13678,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,603000,"IMPROVEMENTS TO THE INTERIOR BT ROAD IN DHANARAJAPURAM MAIN ROAD DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13682,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1538000,"IMPROVEMENTS TO NEW BT ROAD @ SENTHIL NAGAR 3RD MAIN ROAD (REACH 2) IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13683,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,355000,"IMPROVEMENTS TO NEW BT ROAD @ MO.POO.C STREET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13684,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,842000,"IMPROVEMENTS TO NEW BT ROAD @RAJAJI NAGAR VAIGAI STREET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13685,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,839000,"IMPROVEMENTS TO NEW BT @ IN VALMIKI STREET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13687,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,842000,"IMPROVEMENTS TO BT ROAD @ SELVI NAGAR EXTN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/13688,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,376000,"IMPROVEMENTS TO NEW BT @ SELVI NAGAR 3RD STREET IN DN-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/1407,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,505000,"Desiliting Storm Water Drain at Various Street in Dn-65,Unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/15291,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,109000,Maintenance of park by private agency for the Period of six month at park in senthil nagar 10th street in Dn-65 U-15 Z-06,Own Sources,6,2017-18,2018-19 NF/2017-18/15301,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,93000,Maintenance of park by private agency for the Period of six month at park in senthil nagar 13th street in Dn-65 U-15 Z-06,Own Sources,6,2017-18,2018-19 NF/2017-18/15308,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,116000,Maintenance of park by private agency for the Period of six month at park in janakiram reddy colony park in Dn-65 U-15 Z-06,Own Sources,6,2017-18,2018-19 NF/2017-18/15312,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,85900,Maintenance of park by private agency for the Period of six month at park in Mahaveer nagar park in Dn-65 U-15 Z-06,Own Sources,6,2017-18,2018-19 NF/2017-18/15317,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,116000,"Maintenance of park by private agency for the Period of six month at park in Rk syndicate Nagar park in Dn-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/16045,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,350000,"MAINTANANCE ESTIMATE FOR PARK @ SENTHIL NAGAR 13TH STREET (THANTHAI PERIYAR PARK in Dn-65 U-15 Z-06,",Own Sources,6,2017-18,2020-21 NF/2017-18/16048,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,343000,"MAINTANANCE ESTIMATE FOR PARK @ JANAKIRAM REDDY COLONY PARK in Dn-65 U-15 Z-06,",Own Sources,6,2017-18,2020-21 NF/2017-18/16065,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,304000,"Improvements to Cps School in Srinivasan Nagar 3rd Main Road in Dn-65 U-15 Z-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/16066,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,384000,"MAINTANANCE ESTIMATE FOR PARK @ SENTHIL NAGAR PARK in Dn-65 U-15 Z-06,",Own Sources,6,2017-18,2020-21 NF/2017-18/16503,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,345000,"MAINTANANCE ESTIMATE FOR PARK @ R.K SYNDICATE NAGAR PARK in Dn-65 U-15 Z-06,",Own Sources,6,2017-18,2020-21 NF/2017-18/16516,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,340000,"Attending patchwork for the damaged Roads at various Street in Rajaji Nagar in Dn-65,Unit-15,Zone-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/4974,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1180000,"Improvement to the road @ KAMBAR NAGAR AVVAI STREET Dn-65 Unit-15 Zone -06,",Own Sources,6,2017-18,2018-19 NF/2017-18/4990,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1340000,"Improvement to the Interior BT Road @ ADHIYAMAAN NAGAR 1,2,3, STREETS IN DN-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/4992,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1340000,"Improvement to the Interior BT Road @ VENKATRAMANANAN VEKAVATHY STREET K.K NAGAR IN DN-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/5057,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1186000,Improvement to the Interior BT Road @ GKM COLONY 35TH STREET DN-65 UNIT-15 ZONE-06,Own Sources,6,2017-18,2018-19 NF/2017-18/5099,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1180000,Improvement to the Interior BT Road @ SENTHIL NAGAR 3RD MAIN ROAD IN DN-65 UNIT-15 ZONE-06,Own Sources,6,2017-18,2018-19 NF/2017-18/5132,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,618000,"Improvement to the Interior BT Road @ SENTHIL NAGAR 12TH STREET IN DN-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/5133,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,851000,"Improvement to the Interior BT Road @ V.V NAGAR 6TH STREET IN DN-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/5134,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,610000,Improvements to the Interior BT Road @ SENTHIL NAGAR 13TH STREET INDN-65 UNIT-15 ZONE-06,Own Sources,6,2017-18,2018-19 NF/2017-18/5148,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,297000,"Improvement to the Interior BT Road @ Senthil Nagar 11th Cross Street DN-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/5169,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,412000,"IMPROVEMENTS TO THE INTERIOR CC ROAD @ Senthil Nagar 12th Cross Street In DIVISION-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/5172,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,770000,"Improvement to the Interior BT Road @ Senthil Nagar 13th Cross Street In DIVISION-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/5178,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1880000,"Improvement to the Interior BT Road @ Senthil Nagar 14th Cross Street In DIVISION-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/5180,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,4690000,"IMPROVEMENTS TO THE INTERIOR ROAD @ JANAKIRAM 2ND MAIN ROAD NETHAJINAGAR 1ST MAIN ROAD IN DIVISION-65 UNIT-15 ZONE-06,",Own Sources,6,2017-18,2018-19 NF/2017-18/7080,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,77819,"Maintenance of Park at Janakiram reddy colony in Div-65,Unit-15,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/7168,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,76000,"MAINTENANCE OF PARK BY PRIVATE AGENCY AT MAHAVEER PARK IN DIV -65 U-15 ZONE -06,",Own Sources,6,2017-18,2018-19 NF/2017-18/7170,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,75000,"MAINTENANCE OF PARK BY PRIVATE AGENCY AT RK SYNTICATE PARK IN DN-65,UNIT-15,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/7171,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,78000,"Maintenance of Thanthai Periyar Park at Senthil nagar 10th street in Div-65,Unit-15,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/7172,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,73000,"Maintenance of Thanthai Periyar Park at Senthil nagar 13th street in Dn.65,Unit-15,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/9925,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,119000,"Construction of inspection chamber with pvc pipe connection (2/2)in Rajaji Nagar various Streets in Dn-65 U-15 Z-06,",Own Sources,6,2017-18,2019-20 NF/2017-18/10653,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,47000,"Repairs to Sump at Unit-16 office at Jawahar nagar 3rd circular road 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/10705,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,3800000,"Providing Badminton court inside of Indoor stadium at Jawahar nagar 1st circular road in Div-66,Unit-16,Zone-6.",MLACDS,6,2017-18,2018-19 NF/2017-18/1071,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,570000,"Construction of Composting Yard at Jawahar nagar 1st circular road Playground Div-66,Unit-16,Zone-6.",Grants,6,2017-18,2017-18 NF/2017-18/13527,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,720000,"MAINTENANCE AND OPERATION OF WATER TREATMENT PLANT (AMMA KUDINEER) AT PERIYAR NAGAR PERIPHERAL HOSPITAL CAMPUS, KARTHIKEYAN SALAI IN DN-66,UNIT-16,ZONE-06",Own Sources,6,2017-18,2019-20 NF/2017-18/13777,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,1560000,"Improvements to the Interior BT Road at Jawahar nagar 5th main road in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13778,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,1770000,"Improvements to the Interior BT Road at Temple road in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13779,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,784000,"Improvements to the Interior BT Road at Jawahar nagar Temple 1st cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13780,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,1230000,"Improvements to the Interior BT Road at Jawahar nagar 5th circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13781,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,202000,"Improvements to the Interior BT Road at Jawahar nagar 5th circular 1st lane in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13782,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,155000,"Improvements to the Interior BT Road at Jawahar nagar 5th circular 2nd lane in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13783,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,155000,"Improvements to the Interior BT Road at Jawahar nagar 5th circular 3rd lane in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13784,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,224000,"Improvements to the Interior BT Road at Moorthy cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13785,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,1100000,"Improvements to the Interior BT Road BT Road at Kuppusamy street in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1393,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,690000,"Desilting Existing Storm water drain at Chandrasekaran salai,Krishnamoorthy street,Venugopal street,Karthick street,Manavalan street,Varatharajan street,Krishna nagar main road and various streets in Div-66,Unit-16,Zone-6.",Own Sources,6,2017-18,2017-18 NF/2017-18/14975,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,417000,"Maintenance of Jawahar nagar 5th main road park for the period of one year by private agency in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2020-21 NF/2017-18/14976,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,634000,"Maintenance of Periyar nagar 21st street park for the period of one year by private agency in Div-66,Unit-16,Zone-6 in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2020-21 NF/2017-18/14978,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,504000,"Maintenance of Jawahar nagar 2nd circular road park for the period of one year by private agency in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2020-21 NF/2017-18/15211,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,175000,Maintainance of park by private agency for the Period of Six Months at Jawahar Nagar 2nd Circular road Park in Dn66 U16 Z06,Own Sources,6,2017-18,2019-20 NF/2017-18/15213,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,186000,Maintainance of park by private agency for the Period of Six months at Jawahar Nagar 5th main road Park in Dn66 U16 Z06,Own Sources,6,2017-18,2018-19 NF/2017-18/15215,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,95000,Maintainance of park by private agency for the Period of Six months at Sakthivel nagar Park in Dn66 U16 Z06,Own Sources,6,2017-18,2018-19 NF/2017-18/15216,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,200000,Maintainance of park by private agency for the Period of Six months at Periyar nagar 20th street Park in Dn66 U16 Z06,Own Sources,6,2017-18,2019-20 NF/2017-18/16023,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,284000,"Maintenance of Sakthivel nagar 2nd cross street park for the period of one year by private agency in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2020-21 NF/2017-18/16102,Parks,Completed,P-Parks and Playfields,66,7800000,"Plantation and Maintenance of tree saplings for one year at Various locations in Unit-15,16 & 17,Zone-6",Own Sources,6,2017-18,2019-20 NF/2017-18/4966,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,747000,"Improvements to the Interior BT Road at Lakshman nagar west street in Div-66,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5016,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,489000,"Improvements to the Interior BT Road at Lakshman nagar East street in Div-66,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5017,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,412000,"Improvements to the Interior BT Road at Lakshman nagar 1st cross street in Din-66,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5019,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,438000,"Improvements to the Interior BT Road at Lakshman nagar 2nd cross street in Din-66,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5020,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,541000,"Improvements to the Interior BT Road at Jawahar nagar 2nd main road in Din-66,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5022,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,66,435000,"Improvements to the Interior BT Road at Krishnamoorthy street in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/5024,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,154000,"Maintanance of Park by Private agency for Seven month at Jawahar nagar 5th main road in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/5025,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,79000,"Maintanance of Park by Private agency for Seven month at Sakthivel nagar park in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8600,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,440000,"Construction of SWD Link at Chandrasekaran salai (From Periyar nagar 7th street to Venkatesan salai) in Div-66,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 D/2017-18/12398,Storm Water Drain,Completed,D-Storm Water Drains,67,2377000,"Construction of storm water drain of size 900x900mm along market street from market street chainage 0.0M to market street chainage 120.0M in Dn- 67, Zone-VI.",Own Sources,6,2017-18,2018-19 D/2017-18/12399,Storm Water Drain,Completed,D-Storm Water Drains,67,2373000,"Construction of storm water drain of size 900x900mm along market street from market street chainage 120.0M to market street chainage 230.0M in Dn- 67, Zone-VI.",Own Sources,6,2017-18,2018-19 NF/2017-18/0918,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT THANTHONDRI AMMAN KOVIL STREET IN DN.67 U-15,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/10605,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,52000,"Conversion of old class room into Samsung Smart Class Room, at Chennai Girls Higher Secondary School in Market Street in DN-67,Unit-15,Zone-06.",Own Sources,6,2017-18,2017-18 NF/2017-18/13662,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,2257000,"Relaying exisitng BT road with BC 30mm Thick at Muthukumarapp street Reach 3 IN DIV-67, UNIT-15, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/13663,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1756000,"Relaying exisitng BT road with BC 30mm Thick at Muthukumarappa street Reach 2 IN DIV-67, UNIT-15, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/13664,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,2006000,"Relaying exisitng BT road with BC 30mm Thick at Muthukumarappa Street Reach 1 IN DIV-67, UNIT-15, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/13666,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1747000,"Relaying exisitng BT road with BC 30mm Thick at Rangasayee Street IN DIV-67, UNIT-15, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/1388,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,295000,"Desilting Existing storm water drain at Rangasayee street,Market street,Jeganathan street,Locoworks road and various streets in Div-67,Unit-15,Zone-6.",Own Sources,6,2017-18,2017-18 NF/2017-18/14941,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,86000,Maintenance of Anandan park by agency for the period of 6 months at S.R.P Koil street in Dn 67 Unit 15 Z 06,Own Sources,6,2017-18,2018-19 NF/2017-18/16192,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,125000,"Repairs & Improvements to Existing Chennai Girls Higher Secondary School at Market Street in DN-67,Unit-15,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/17906,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,210000,Maintenance of Anandan park by agency for the period of 1 Year at S.R.P Koil street in Dn 67 Unit 15 Z 06,Own Sources,6,2017-18,2020-21 NF/2017-18/8157,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,144000,"MAINTENANCE OF ANANDAN PARK AT THANTHONRIAMMAN KOIL STREET (7 MONTHS) IN DIV-67, UNIT-15, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8647,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,393000,"Construction of SWD damaged top slab at GKM colony 21st street, various streets, supply and fixing of doors at various streets in Dn.67,U-15,z-6",Own Sources,6,2017-18,2019-20 B/2017-18/11901,Buildings,Completed,B-Buildings,68,10000000,"PROPOSED CONSTRUCTION OF COMMUNITY CENTRE FOR BASEMENT AND STILT FLOOR AT SRP KOVIL STREET THIRU.VI.KA.NAGAR. KOLATHUR IN DN-68,ZONE-6",MLACDS,6,2017-18,2018-19 B/2017-18/11902,Buildings,Completed,B-Buildings,68,9000000,"PROPOSED CONSTRUCTION OF COMMUNITY CENTRE FOR FIRST FLOOR AT SRP KOVIL STREET THIRU.VI.KA.NAGAR. KOLATHUR IN DN-68,ZONE-6.",MLACDS,6,2017-18,2019-20 B/2017-18/11927,Buildings,Completed,B-Buildings,68,6000000,"PROPOSED CONSTRUCTION OF COMMUNITY CENTRE FOR SECOND FLOOR AT SRP KOVIL STREET, THIRU.VI.KA.NAGAR .KOLATHUR IN DN-68, Z-6.",MPLADS,6,2017-18,2019-20 B/2017-18/11928,Buildings,Completed,B-Buildings,68,5000000,"PROPOSED COMMUNITY CENTRE PRVIDING WATER SUPPLY ,DRINAGE ARRANGEMENTS AND ELECTRICAL ARRANGEMENTS AND LIFT AT SRP KOVIL STREET, THIRU. VI. KA NAGAR KOLATHUR IN DN-68, Z-6.",MLACDS,6,2017-18,2020-21 B/2017-18/15569,Buildings,Completed,B-Buildings,68,843000,"Supplying and fixing of Two seater bench cum tables for propsed smart classes in CMS Gopalapuram in DN 68 Zone 6, CMS Aminjikarai in DN 102 Zone 8, CMS Triplicane high road in DN 116 Zone 9 and CMS Vadapalani in DN 130 Zone 10",Own Sources,6,2017-18,2018-19 BR/2017-18/1446,Road Cut,Completed,BR-Bus Route Roads,68,28000,Restoration of Road cut made by CMWSSB at Pallavan salai in(Div-68) Zone-6,Deposit Works,6,2017-18,2017-18 L/2017-18/7568,Electrical,Completed,L-Electrical,68,897500,"Supply and replacement of 2110Mtrs of damaged 2x16sqmm UG cables at chronicle faulty locations at Cement concrete road and Block topped road in Teeds garden, Lakshmi nagar and Various Location in div 68 zone-VI",Own Sources,6,2017-18,2019-20 NF/2017-18/10399,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,92000,"PROVIDING ALUMINIUM DOORS AND WINDOWS AND PAINTING WORK FOR SMART CLASS ROOM IN GOPLALAPURAM CPS (SAMSUNG SMART CLASSROOM) IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1072,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,570000,"Construction of Composting Yard at Thangal Burial ground ( North side) ,Pallavan salai in Div-68,Unit-16,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/1073,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,570000,"Construction of Composting Yard at Thangal Burial ground ( South side) ,Pallavan salai in Div-68,Unit-16,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/11268,Electrical,Completed,NF-THIRU-VI-KA NAGAR,68,212000,"DISMANTLING DELAPIDATED ROOF AND REPLACING WITH GI SHEET ROOFING WITH TRUSS AT AMMA UNAVAGAM AT PAPERMILLS ROAD IN DN-68, UNIT-16, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/12579,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1000000,CONSTRUCTION OF TOILET BLOCK AND ADDITIONAL IMPROVEMENT WORKS TO CUMMUNITY HALL AT JAIBEAM NAGAR IN DN 68 UNIT 16 ZONE 6 ( MPLAD FUND 2017-18),MPLADS,6,2017-18,2018-19 NF/2017-18/12733,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,16500,"REPAIRS TO SUMP MOTOR PIPE LINE, COVER, PAINTING AT CPS GOPALAPURAM AND PROVIDING GAS PIPE LINE CONNECTION AT AMMA UNAVAGAM IN DN -68, UNIT-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/13292,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,620000,"Demolition of Existing Old damaged Community Hall at SRP Koil Street in Dn-68, Un-16, Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13814,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,125000,"improvements to the interior BT Road at Thiruvalluvar cross street in Div-68,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13815,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,418000,"improvements to the Interior BT Road at Ayyavoo gramia lane ( 1st,2nd & 3rd lane) in Div-68,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13818,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,68,283000,"improvements to the Interior BT Road at Kennady square 3rd street ( North) in Din-68,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/13819,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,68,670000,"improvements to the Interior BT Road at Pandian street in Din-68,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/13820,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,68,573000,"improvements to the Interior BT Road at Teeds garden 7th street in Din-68,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/13821,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,68,954000,"improvements to the Interior BT Road at Watkin street in Din-68,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/1395,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,750000,"Desilting of Existing Storm water drain at Various streets in Dn-68,U-16,Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/14937,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,68,138000,"Improvements to the Interior CC Road at Teeds Garden Ist street in Div-68,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/16104,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,462000,"Improvement to CPS at Thiru.Vi.Ka Nagar Main Road in Dn-68, Un-16, Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/16117,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,250000,"Repair works(Kitchen flooring , Ceiling , wall) to Chennai Primary school at Mangalapuram in Div-71,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/16144,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,434000,"Maintenance For Park at KKR Avenue Park Pallavan Salai in Dn-68, Unit-16, Zone-06",Own Sources,6,2017-18,2020-21 NF/2017-18/16174,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,407000,"Maintanence of Park at George colony park at Gurusamy street in Div-68,Unit-16,Zone-6",Own Sources,6,2017-18,2020-21 NF/2017-18/16200,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,241000,"Relaying the lowlying CC Road at Madurai samy madam Adi andra street in Div-68,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/16202,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,264000,REPAIRS AND IMPROVEMENTS TO URUDHU PRIMARY SCHOOL IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2017-18,2018-19 NF/2017-18/16203,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,253000,"Relaying the lowlying CC Road at Thillainayagam 5th lane in Div-68,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/16204,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,317000,"Relaying the lowlying CC Road at Thillainayagam 3rd lane in Div-68,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/16205,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,180000,"Relaying the lowlying CC Road at Thillainayagam 3rd cross lane in Div-68,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/16511,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,247000,"Maintenance For Park at sarjid Hussain park at Papermills road in Dn-68, Unit-16, Zone-06",Own Sources,6,2017-18,2020-21 NF/2017-18/16990,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,192000,REPAIRS AND IMPROVEMENTS TO GEORGE COLONY PARK AT DN 68 UNIT 16 ZONE 6,Own Sources,6,2017-18,2018-19 NF/2017-18/8355,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,206000,"Maintanence of Park by Privatation Engaging Out Sourcing for seven month at Kennedy square park in Dn 68, Unit 16, Zone 6.",Own Sources,6,2017-18,2018-19 NF/2017-18/9922,Buildings,Completed,Q-Solid Waste Management,68,4475000,"CONSTRUCTION OF COMPOST YARD AT THANGAL BURIAL GROUND IN DN 68, UNIT 16, ZONE 6",Own Sources,6,2017-18,2018-19 L/2017-18/15519,Electrical,Completed,L-Electrical,69,197300,Replacement of Over Head wires with 561 mtrs of 2x16sqmm cable at Shanthi nagar & Cross street in Dn69 Zone-VI,Own Sources,6,2017-18,2018-19 L/2017-18/7566,Electrical,Completed,L-Electrical,69,962700,"Supply and replacement of 2230Mtrs of damaged 2x16sqmm UG cables at chronicle faulty at Cement concrete road and Block topped road in Shanbagavali street , Ponnuvelpuram and Various Location in div 69 zone-VI",Own Sources,6,2017-18,2019-20 L/2017-18/7567,Electrical,Completed,L-Electrical,69,863600,"Supply and replacement of 2027Mtrs of damaged 2x16sqmm UG cables at chronicle faulty locations at Cement concrete road and Block topped road in Janakiraman nagar, Maduraisami madam and Various Location in div 68 zone-VI",Own Sources,6,2017-18,2019-20 L/2017-18/7579,Electrical,Completed,L-Electrical,69,894500,Supply and replacement of 2145Mtrs of damaged 2x16sqmm UG cables at chronicle faulty at Cement concrete road and Block topped road in Shanthi colony stmarrys road and Various Location in div 69 zone-VI,Own Sources,6,2017-18,2019-20 NF/2017-18/10398,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,46000,"REPAIRS TO BOREWELL AND REPLACING COMPRESSOR MOTOR PUMP AND NEW PIPE LINES AT DIVISION OFFICE BUILDING IN DN 68, UNIT-16, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1059,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT GANDHI PARK ,TANKLINK ROAD IN DN.69 U-16,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/11321,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,37000,"REPAIRS TO ROOFING DAMAGED BY FALLEN TREE BRANCHES AT ENTRANCE OF ZONAL OFFICE BUILDING IN DN-69, UNIT-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/12141,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,1249000,"Relaying the Lowlying Damaged BT Road at Thikkakulam street in Div-69,Unit-16,Zone-6.",MPLADS,6,2017-18,2018-19 NF/2017-18/12771,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,35000,"REPAIRS TO TOILET FLUSH TANK, ALUMINIUM DOORS, DOOR GLASS, NAME BOARDS AND WATER SUPPLY AT ZONAL OFFICE BUILDING IN DN-69, UNIT-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/1399,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,800000,"Desilting of existing swd at Anderson road,Pilkington road and various street in DN-69,U-16,Z-6",Own Sources,6,2017-18,2017-18 NF/2017-18/14939,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,800000,"Repair works & Improvements to CMS at Kabilar street in Div-69,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/14945,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,2107000,"Relaying the damaged BT Road at Pilkington road in Div-66,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/14949,Parks,Completed,NF-THIRU-VI-KA NAGAR,69,75800,MAINTANANCE OF PARK BY PRIVATATION ENGAGING OUT SOURCING 6 MONTHS AT VENKATESWARA NAGAR 1ST STREET IN DN 69 UNIT 16 ZONE 6,Own Sources,6,2017-18,2018-19 NF/2017-18/14950,Parks,Completed,NF-THIRU-VI-KA NAGAR,69,77000,MAINTANANCE OF PARK BY PRIVATATION ENGAGING OUT SOURCING AT RAGAVAN STREET DN 69 UNIT 16 ZONE 6,Own Sources,6,2017-18,2018-19 NF/2017-18/6048,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,603000,"Improvement to the Interior BT road at Bunder garden 1st street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6051,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,603000,"Improvement to the road at Bunder garden 2nd street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6052,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,572000,"Improvement to the road at Bunder garden Main street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6055,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,469000,"Improvement to the road at Carpenter Street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6057,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,1006000,"Improvement to the road at SSV Kovil 1st street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6058,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,1670000,"Improvement to the road at Jamunabai Street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6059,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,1006000,"Improvement to the road at Shanthi Colony main street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6063,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,1350000,"IMPROVEMENTS TO THE INTERIOR CC ROAD at St Marys Road In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2019-20 NF/2017-18/6072,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,69,840000,"Improvement to the road at Sunder Vinayagar 2nd Street In Dn-69,Unit-16,Zone-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/8767,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,154000,"Constrution of SWD Link at Bangaru street to pilkington road IN dn-69,unit-16,zone-6",Own Sources,6,2017-18,2019-20 NF/2017-18/8799,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,154000,"Construction of SWD Link at Shanthi colony in Div-69,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/8801,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,190000,"Construction of SWD Link at Anderson road in Div-69,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/9119,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,110000,"Desilting of SWD at Shanthi colony,Gnambal garden 2nd street and Various streets in Div-69,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 B/2017-18/14549,Buildings,Completed,B-Buildings,70,8750000,"Improvements to CGHS ( Main Building ) at School road in Dn-70,Unit-16,Zone-6.",Own Sources,6,2017-18,2019-20 BR/2017-18/1453,Road Cut,Completed,BR-Bus Route Roads,70,20000,Restoration of Road cut made by CMWSSB at Perambur High Road (North) (Div-70) in Zone-6,Deposit Works,6,2017-18,2017-18 D/2017-18/8079,Storm Water Drain,Completed,D-Storm Water Drains,70,2430000,"Dismantling the existing dilapidated storm water drain and Re-construction of storm water drain of size 1200x1200mm along Dr.Ambedkar college road to Otteri-Nalla in Dn-70,Zone-VI.",Own Sources,6,2017-18,2018-19 D/2017-18/9069,Storm Water Drain,Completed,D-Storm Water Drains,70,2121000,"Improvement of storm water drain of size 1200x1200mm along Dr.Ambedkar college road to Otteri-Nalla in Dn-70,Zone-VI.",Own Sources,6,2017-18,2018-19 L/2017-18/15517,Electrical,Completed,L-Electrical,70,198400,Replacement of Over Head wires with 558mtrs of 2x16sqmm cable at NSK street and various location in dn.70 Zone-VI,Own Sources,6,2017-18,2018-19 L/2017-18/7569,Electrical,Completed,L-Electrical,70,998600,Supply and replacement of 2531Mtrs of damaged 2x16sqmm UG cables at chronicle faulty location at Cement concrete road and Block topped road in Mettupalayam arunthathi nagar and Various Location in div 70 zone-VI,Own Sources,6,2017-18,2019-20 NF/2017-18/10436,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,99100,"REPAIR WORKS FOR WINDOWS, DOORS, PROVIDING GRILL GATE, SCREEN AND PAINTING FOR SMART CLASSROOM AT CHS SCHOOL ROAD IN DN 70, UNIT-16, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/10437,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,30200,"Repairs to borewell and motor at Perambur lab in Dn 70, Unit-16, Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1075,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,570000,"Construction of Composting Yard at Tank Link road Div-70,Unit-16,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/1076,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,570000,"Construction of Composting Yard at Rajiv Gandhi park in Div-70,Unit-16,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/12504,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,30000,"REPAIRS TO BOREWELL, FLUSHING - 2 nos. SUBMERSIBLE MOTOR PUMP-1no. AND SUMP MOTOR PUMP AT GCC GIRLS HIGH SCHOOL AT SCHOOL ROAD IN DN-70, U-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/12507,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,10200,"REPAIRS TO NNMP SHED FLOORING AT TOILET, KITCHEN SHED AT STATE BANK COLONY IN DN 70, U-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/12509,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,127200,"PROVIDING ALUMINIUM PARTITION FOR SAFE ROOM, MS WELDMESH FOR WINDOWS, PAINTING OUTER WALLS AND GRILLS FOR SAMSUNG SMART CLASS ROOM AT SCHOOL ROAD IN DN-70, U-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/12518,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,14000,"REPAIRS TO OVERHEAD WATER TANK, WATER-PROOFING, AND PIPE LINES AT PERAMBUR PARK IN DN-70, U-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/13933,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1470000,"Strengthening and Relaying B.T.road at Paddy field road (from P.H. Road to Vadivelu 2nd cross street) in div-70,unit-16,zone-6.",MLACDS,6,2017-18,2018-19 NF/2017-18/14067,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,2109000,"Strengthening and Relaying B.T.road at Anandavelu street in div-70,unit-16,zone-6.",MLACDS,6,2017-18,2018-19 NF/2017-18/14101,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1646000,"Strengthening and Relaying B.T.road at Patel road (Bharathi main road to Patel road 1st street) n div-70,unit-16, zone-6.",MLACDS,6,2017-18,2018-19 NF/2017-18/1430,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,800000,"Desilting the Existing Storm water drain at Various streets in Div-70,Unit-16,Zone-6.",Own Sources,6,2017-18,2017-18 NF/2017-18/14620,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1262000,"Strengthening and Relaying B.T.road at Paddy field road (from Vadivelu 2nd cross street to vadivel street)in div-70,unit-16,zone-6.",MLACDS,6,2017-18,2018-19 NF/2017-18/15477,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,190000,"Maintenance of Rajiv Gandhi Park at PH Road in Dn-70,Un-16,Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/15478,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,412500,"Maintenance of Park Murasolimaran Park in Dn-70, Un-16, Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/15480,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,189000,"Maintenance of Vadivel(M) 2nd cross street park and kannabiran kovil street at Perambur in Dn-70, Un-16 , Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/16273,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,155000,"Relaying B.T.road at Bharathi cross street in div-70,unit-16,zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/16314,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,1329000,"Improvements to CGHS(Stadium Block & J-Block)) at School Road in Dn-70,Un-16,Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/17901,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,232000,"Maintenance of Rajiv Gandhi Park at PH Road in Dn-70,Un-16,Z-6 (per Year)",Own Sources,6,2017-18,2020-21 NF/2017-18/17903,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,265000,"Maintenance of Vadivel(M) 2nd cross street park (per Year) in Dn-70, Un-16 , Z-6",Own Sources,6,2017-18,2020-21 NF/2017-18/17904,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,1450000,"Maintenance of Park Murasolimaran Park (North) in Dn-70, Un-16, Z-6",Own Sources,6,2017-18,2020-21 NF/2017-18/17905,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,863000,"Maintenance of Park Murasolimaran Park (South) in Dn-71, Un-16, Z-6 (Per Year)",Own Sources,6,2017-18,2020-21 NF/2017-18/5400,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1341000,"Improvement to the road at Paddy filed road in div-70,uint-16,zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5402,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,825000,"Improvement to the road at Anandavelu street in div-70,uint-16,zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/5413,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,70,1857000,"Improvement to the road at Patel road in div-70,uint-16,zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/8360,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,96000,Maintenance of Vadivel(M)2nd cross street park and Kannabiran kovil street Park at Perambur in division 70 unit 16 zone 6 (By QualifiedHorticulturist For six month),Own Sources,6,2017-18,2018-19 NF/2017-18/8362,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,363000,"Maintenance of Park at Murasolimaran Park in Dn.70,Unit-16,Zone-6(By Qualified Horticulturist For seven month)",Own Sources,6,2017-18,2018-19 NF/2017-18/8370,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,106000,"MAINTANANCE OF RAGIV GANDHI PARK AT PH ROAD IN DN 70,UNIT 16,ZONE 6 (By QualifiedHorticulturist For six month)",Own Sources,6,2017-18,2018-19 NF/2017-18/8463,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,38900,"Improvements to existing Storm water drain at Nelvayal Road in Dn-70, Un-16 , Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8464,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,38900,"Improvement to existing Storm water drain at Vadivel Street in Dn-70, Un-16 , Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8465,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,71800,"Improvements to existing Storm water drain link at Nelvayal Road and P.H Road Junction in Dn-70, Un-16 , Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8601,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,124000,"Improvements to existing Storm water drain at Dr.Ambedkar college road near aatuthotti in Dn-70 , Un-16 , Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/9124,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,520000,"Desilting for SWD at State Bank Colony 1st Street ,State Bank Colony 2nd Street ,PH Road,Jamaliya Main Road and various streets in Div-70,Unit-16,Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/10596,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,920000,"REPAIR AND SPECIAL IMPROVEMENTS TO AE ROOM ,TOILETS AND SHED PARTITION TO ZONE-6 LORRY STATION LOCATED AT CHANDRAYOGI SAMATHI STREET IN DIVISION-71, UN-16,Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1077,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,570000,"Construction of Composting Yard at Old Lorry station, Perampur High road in Div-71,Unit-16,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/11708,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,2234000,"CONSTRUCTION OF MULTIPURPOSE HALL AT SASTHIRI NAGAR MAIN STREET UNDER MLA FUND (2017-18) IN DIVISION-71,UNIT-16,ZONE-6",MLACDS,6,2017-18,2018-19 NF/2017-18/12028,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,83000,"Drainage arrangements at Amma Unavagam (Jamaliya) in Div-71, Unit-16, Zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/12739,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,33000,"REPAIRS TO BOREWELL AND JET MOTOR PUMP AT CORPORATION PET HOSPITAL ( VETENARY HOSPITAL) IN DN-71, UNIT-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/12741,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,23500,"REPAIRS TO BOREWELL AT CPS EKANGIPURAM IN DN 71, U-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/12745,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,49300,"REPAIR WORKS TO BOREWELL AND TOILET AT NNMP SHED AT MANGALAPURAM HOUSING BOARD IN DN-71, UNIT-16, ZONE-VI",Own Sources,6,2017-18,2018-19 NF/2017-18/13701,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,71,687000,"Improvements to Interior CC Road at Bashiyam 1st street in Div-71,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13702,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,71,687000,"Improvement to Interior CC Road at Bhasyam 2nd street in Div-71,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13703,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,71,621000,"Improvement to Interior CC Road at New Tank bunk road in Div-71,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13704,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,71,894000,"Improvement to Interior CC Road at Nehru jothi nagar 2nd street in Div-71,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13709,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,387000,"Improvement to Interior BT Road at Subbarayan street in -71,U-16,ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13710,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1676000,"Improvement to Interior BT Road at Tank bund road in -71,U-16,ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13711,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,670000,"Improvement to Interior BT Road at Krisnadoss nagar 4th street in -71,U-16,ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13712,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,618000,"Improvement to Interior BT Road at Jamalia link road in -71,U-16,ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13714,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1080000,"Improvements to Interior BT Road at Bashyam 2nd street in Div-71,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/13715,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1120000,"Improvements to interior BT Road at Subbarayan street in Div-71,Unit-16,Zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1463,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,750000,DESILTING OF EXISTING SWD AT VARIOUS STREETS IN DN71 UNIT-16 ZONE-6,Own Sources,6,2017-18,2017-18 NF/2017-18/14864,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2250000,"STRENGTHENING AND RELAYING OF BT SURFACE AT TANK BUND ROAD ( FROM JUNCTION OF K.H.ROAD TO MALAYAPPAN STREET ) UNDER THIRU.VI.KA NAGAR MLA FUND ( 2017-2018 ) IN DIVISION 71,UNIT-16,ZONE-6",MLACDS,6,2017-18,2018-19 NF/2017-18/14951,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2250000,"STRENGTHENING AND RELAYING OF BT SURFACE AT TANK BUND ROAD ( FROM MALAYAPPAN STREET TO JUNCTION OF NEW VAZHAIMA NAGAR ) UNDER THIRU.VI.KA NAGAR MLA FUND ( 2017-2018 ) IN DIVISION 71,UNIT-16,ZONE-6",MLACDS,6,2017-18,2018-19 NF/2017-18/15454,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,435000,"Maintenance of Murasoli Maran park by private agensy for six months at Perambur high road in dn-71,unit-16,zone-6",Own Sources,6,2017-18,2018-19 NF/2017-18/17902,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,209000,"Maintenance for \park at Kannapiran Koil Street in dn-70,unit-16,zone-6 (Per Year)",Own Sources,6,2017-18,2020-21 NF/2017-18/8319,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,297000,"MAINTENANCE OF MURASOLI MARAN PARK AT PERAMBUR HIGH ROAD (SOUTH) IN Dn-71,UNIT-16,ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/10530,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,164000,"DESILTING OF SUMP 2 NOS AND IMPROVEMENT WORK AT SLAUGHTER HOUSE IN DN-72,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/13930,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,210000,"IMPROVEMENTS TO LABOURS DRESS CHANGING ROOM IN DIVISION OFFICE AT V.O.C NAGAR 1ST STREET IN DN-72, U-17, Z-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1444,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,378000,"Desilting of storm water drain at various streets in Dn 72, U17,Zone6",Own Sources,6,2017-18,2018-19 NF/2017-18/16416,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,400000,"Improvements to the existing to CPS at thiru ve ka nagar dn-72,unit-17,zone-06.",Own Sources,6,2017-18,2018-19 B/2017-18/13842,Buildings,Completed,B-Buildings,73,16679430,REPAIR AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE IN ZONE 6& 7,Own Sources,6,2017-18,2019-20 BR/2017-18/1434,Road Cut,Completed,BR-Bus Route Roads,73,80000,Restoration of Road cut made by CMWSSB at COOKS ROAD in(Div-73) Zone-6,Deposit Works,6,2017-18,2017-18 L/2017-18/7565,Electrical,Completed,L-Electrical,73,983300,Supply and replacement of 2478Mtrs of damaged 2x16sqmm UG cables at chronicle faulty at Cement concrete road and Block topped road in Otteri Stranhans road and dasamakan and Various Location in div 73 zone VI,Own Sources,6,2017-18,2019-20 NF/2017-18/1080,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,570000,"Construction of Composting Yard at New Ferrance road in Div-73,Unit-17,Zone-6.",Grants,6,2017-18,2018-19 NF/2017-18/11415,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,5330000,IMPROVEMENTS WORK TO THE INTERIOR BT ROAD AT NEW FERRANCE ROAD IN DIVISION 73 UNIT 17 ZONE-6,Own Sources,6,2017-18,2018-19 NF/2017-18/1474,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,800000,Desilting of existing swd at various streets in dn73 unit-17 zone6,Own Sources,6,2017-18,2017-18 NF/2017-18/15538,Playfields,Completed,NF-THIRU-VI-KA NAGAR,73,99000,"MAINTANANCE OF WADIA PARK AT NEW FERRANCE ROAD FOR SIX MONTH IN DN-73, UNIT-17, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8462,Parks,Completed,NF-THIRU-VI-KA NAGAR,73,80000,"MAINTENANCE OF WADIA PARK AT NEW FERRANCE ROAD FOR SEVEN MONTHS IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/9881,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,90000,"IMPROVEMENTS TO OLD ZONE-3 OFFICE AT AMBEDKAR COLLEGE ROAD IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 BR/2017-18/16569,Road Cut,Completed,BR-Bus Route Roads,74,2400000,"Restoration of road cut made by TANGEDCO at Medavakkam tank Road from the jn of Kellys signal to the jn of KM Hospital in Dn 74 , Zone - 6(Chellan No : BR/ 2017-18/0025484)",Deposit Works,6,2017-18,2019-20 BR/2017-18/17052,Road Cut,Completed,BR-Bus Route Roads,74,2420000,"Restoration of road cut made by TANGEDCO at Medavakkam tank Road from the jn of KM Hospital to the jn of Yamaha Show room in Dn 74 , Zone - 6(Chellan No : BR/ 2017-18/0025484)",Deposit Works,6,2017-18,2018-19 BR/2017-18/17055,Road Cut,Completed,BR-Bus Route Roads,74,2367000,"Restoration of road cut made by TANGEDCO at Medavakkam tank Road from the jn of Yamaha Show room to Konnur High Road in Dn 74 , Zone - 6(Chellan No : BR/ 2017-18/0025484)",Deposit Works,6,2017-18,2018-19 D/2017-18/14821,Storm Water Drain,Completed,D-Storm Water Drains,74,11830000,"Dismanlting of existing dilapidated Arch storm water drain and Construction of storm water Drain of size 1500x2500mm along Barakka road from A K samy nagar 9th street to Medavakkam tank road in Dn- 74, Zone-VI.",Own Sources,6,2017-18,2018-19 NF/2017-18/0142,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,362000,"PROVIDING SECURITY GUARDS PERIOD FOR ONE YEAR ( 3 SHIFTS -1NOS ) AT OTTERI DUMPING GROUND IN DN-74, U-17, Z-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/10475,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1170000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT NALLAIAH NAIDU STREET IN DN 74 UNIT-17, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/1081,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT PUMPING STATION ROAD IN DN.74 U-17,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/1082,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT OTTERI DUMPING GROUND IN DN.74 U-17,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/13747,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,602000,"Improvement To Interior B.T.Road with BC 30mm Thick at Balaji Nagar 2nd Main road IN DIV-64, UNIT-15, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/1412,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,530000,"Desilting of storm water drain at various street in dn 74, unit 17, zone 06",Own Sources,6,2017-18,2017-18 NF/2017-18/14151,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,134000,"IMPROVEMENT WORKS IN VARIOUS LOCATIONS AT DN 74 UNIT 17 , ZONE -6",Own Sources,6,2017-18,2018-19 NF/2017-18/1445,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,240000,"SUPPLYING AND FIXING BOX TYPE BACKLIGHT BOARD WITH ELECTRONIC CHOKES FOR EOC,UPHC ,NUHM IN VARIOUS DIVISIONS (DIVISIONS 64 TO 78) AT ZONE 06",Own Sources,6,2017-18,2017-18 NF/2017-18/1492,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,167000,"Demolishing old fish market and shopping complex at suburayan 1st street in division-74, unit-17, zone-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/15316,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,1100000,"MAINTANANCE WORK IN TROPICAL EVERGREEN FOREST (HERBAL PARK) SIX MONTH IN DN 74 , UNIT-17, ZONE -6",Own Sources,6,2017-18,2018-19 NF/2017-18/17907,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,3850000,"Maintenance of Otteri Tropical Dry Ever Green Forest park For One Year at otteri link road in Otteri Dn-74,Unit-17,Zone -06",Own Sources,6,2017-18,2020-21 NF/2017-18/4274,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,570000,"REPAIRS AND IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL SOUTH SIDE BUILDING AND EAST SIDE BUILDING AT SUBBARAYAN 1ST STREET IN DN-74, UNIT-17, ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/4276,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,330000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN BARACKKA ROAD AND MEDAVAKKAM TANK ROAD AT VARIOUS LOCATIONS IN DN-74, UNIT-17, ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/6183,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,74,540000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT NEW SECRETARIAT COLONY STREET IN DN-74, U-17, Z-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/6193,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,74,335000,"IMPROVEMENTS WORK TO THE INTERIOR BT ROAD AT BARACKKA ROAD 1ST STREET IN DN-74, U-17, Z-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/6199,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,74,516000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT VARADHAMMAL GARDEN 3RD STREET IN DN-74, U-17, Z-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/6201,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,74,258000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT DIVAN BHADUR SHANMUGAM STREET IN DN-74, U-17, Z-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/6203,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,74,516000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT SUBURAYAN 4TH STREET IN DN-74, U-17, Z-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/6206,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,74,516000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT OTHAVADAI STREET IN DN-74, U-17, Z-6.",Deposit Works,6,2017-18,2018-19 NF/2017-18/6207,Road Cut,Completed,NF-THIRU-VI-KA NAGAR,74,670000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SUBURAYAN MAIN I STREET IN DN-74, U-17, Z-6.",Deposit Works,6,2017-18,2018-19 NF/2017-18/6628,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,1140000,"MAINTENANCE TO TROPICAL DRY EVER GREEN FOREST ( HERBAL PARK ) AT OTTERI IN DN-74, U-17, Z-6. ( FOR EIGHT MONTHS )",Own Sources,6,2017-18,2018-19 NF/2017-18/8963,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,92000,"REPAIRS TO IMPROVEMENTS TO STORM WATER DRAIN AT BARRACKA ROAD TO CHENGALVARAYAN STREET AND A.K.SAMY NAGAR 9TH STREET AND SECRETARIAT COLONY 2ND STREET , & VARIOUS LOCATIONS IN DN-74, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 BR/2017-18/1443,Road Cut,Completed,BR-Bus Route Roads,75,55000,Restoration of Road cut made by CMWSSB at Strahans road in(Div-75) Zone-6,Deposit Works,6,2017-18,2017-18 BR/2017-18/1456,Road Cut,Completed,BR-Bus Route Roads,75,30000,Restoration of Road cut made by CMWSSB at Bricklin Road (Div-75) in Zone-6,Deposit Works,6,2017-18,2017-18 NF/2017-18/0987,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,450000,"DEMOLISHING OLD CHENNAI MIDDLE SCHOOL AT VENGATAMMAL SAMATHI STREET IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2017-18,2017-18 NF/2017-18/1083,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT PADAVETTAMAAN KOVIL STREET IN DN -75 U-17,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/11046,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,230000,"REPAIRS AND IMPROVEMENTS TO CPS AT CHELLAPA STREET IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/13856,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,47000,"IMPROVEMENTS AND ARRANGING WATER SUPPLY ARRANGEMENTS AT UPHC CHELLAPPA STREET IN DN-75 , UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/1415,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,270000,"Desilting of storm water drain at various street in dn 75 ,unit-17,zone-06",Own Sources,6,2017-18,2017-18 NF/2017-18/14875,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,98000,"MAINTENANCE OF PATEL PARK ( OUT SOURCING FOR 6 MONTHS ) AT CHELLAPA STREET IN DIV-75, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2019-20 NF/2017-18/16969,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,443000,"Maintenance of Patel Park For One Year at Chellapa Street in Otteri Dn-75,Unit-17,Zone -06",Own Sources,6,2017-18,2020-21 NF/2017-18/7800,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,88000,"MAINTENANCE OF PATEL PARK ( OUT SOURCING FOR 7 MONTHS ) AT CHELLAPA STREET IN DIV-75, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/1084,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT CONRONTZ SMITH NAGAR DOBIGHANA IN DN-76 U-17,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/11161,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,225000,"IMPROVEMENT WORK TO UPHC AT SACHIDANANDAM STREET IN DN 76,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/1417,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,440000,"Desilting of storm water drain at various street in dn-76,unit-17,zone-06",Own Sources,6,2017-18,2018-19 NF/2017-18/1435,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,272000,"Improvement works to the Sathya ammaiyar orphanage centre at sachidnandam street at dn-76,unit-17,zone-06",Own Sources,6,2017-18,2018-19 NF/2017-18/14871,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,170000,"MAINTENANCE OF SELVAPATHY PARK (OUT SOURCING FOR THE PERIOD OF 6 MONTHS ) AT STRAHANS ROAD IN DN 76, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/14872,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,78500,"MAINTENANCE OF BAKTHAVATCHALAM PARK (OUT SOURCING FOR THE PERIOD OF 6 MONTHS ) AT STRAHANS ROAD IN DN 76, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/14873,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,485000,"MAINTENANCE OF CONRONSMITH PARK (OUT SOURCING FOR THE PERIOD OF 6 MONTHS ) AT C.S.NAGAR IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/14874,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,77000,"MAINTENANCE OF KALAIGNAR KARUNANIDHI PARK (OUT SOURCING FOR 6 MONTHS) AT PERAMBUR BARRACKS ROAD IN DN 76,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/16249,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,1200000,"RELAYING OF BITUMINOUS ROAD IN DEVARAJ STREET AT DN-76,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/16309,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,360000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL (URUDHU) AT KANDHA SWAMY KOIL STREET IN DN-76, U-17, ZONE-06.",Own Sources,6,2017-18,2018-19 NF/2017-18/6143,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,254000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT NEW FERRANCE ROAD IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/6146,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,244000,"IMPROVEMENT TO THE STORM WATER DRAIN DAMAGED DUE TO FLOOD AT STRAHANS ROAD IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 NF/2017-18/7742,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,880000,"RELAYING OF THE BITUMINOUS ROAD AT GOODPET PALLAM 1 ST & 2ND STREETS DAMAGED DUE TO VARDHA CYCLONE IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2017-18 NF/2017-18/7796,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,360000,"MAINTENANCE OF C.S.PARK (OUT SOURCING FOR THE PERIOD OF 7 MONTHS ) AT C.S.NAGAR IN DIV 76, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/7797,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,140000,"MAINTENANCE OF SELVAPATHY PARK (OUT SOURCING FOR THE PERIOD OF 7 MONTHS ) AT STRAHANS ROAD IN DN 76, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/7799,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,61000,"MAINTENANCE OF PARK (OUT SOURCING FOR THE PERIOD OF 7 MONTHS ) BAKTHAVACHALAM PARK AT ANGALAMMAN KOIL STREET IN DIV-76, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/8375,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,184000,"DISMANTLING AND RECONSTRUCTION OF DAMAGED STORM WATER DRAIN AT SACHIDANANDAM STREET AND VARIOUS STREETS IN DN-76, UNIT-17, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8389,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,327000,"DISMANTLING AND RECONSTRUCTION STORM WATER DRAIN DAMAGED PORTION AT PERAMBUR BARRACKS ROAD JUN OF VENKATESABAKTHAN STREET AND JUN OF C.S. NAGAR 4TH STREET AND VARIOUS STREET IN DN-76, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/8400,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,108000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN DAMAGED PORTION AT STRAHANS ROAD AND VARIOUS STREETS IN DIV-76, UNIT-17, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8410,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,28000,"DISMANTLING AND RECONSTRUCTION OF STORM WATER DRAIN DAMAGED PORTION AT DEVARAJ STREET CROSS LANE AND VARIOUS STREETS IN DIV-76, UNIT-17, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8441,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,185000,"DISMANTLING AND RECONSTRUCTION STORM WATER DRAIN DAMAGED PORATION AT EDWARD PARK STREET AND VARIOUS STREETS IN DIV-75, UNIT-17, ZONE-6",Own Sources,6,2017-18,2018-19 NF/2017-18/8457,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,59000,"MAINTENANCE OF KARUNANIDHI PARK AT PERAMBUR BARRACKS ROAD IN DN 76,UNIT-17,ZONE-06",Own Sources,6,2017-18,2018-19 L/2017-18/0458,Electrical,Completed,L-Electrical,77,844300,"Provision of 6nos of 8mtr GI Octognal mini mast Hot Dip Zinc Galvanised post with LED flood light fitting at Junctions of Angalamman koil street and Strahans road, Satchidhanandham street and Ramanujam street Old Housing board road,K M Garden play ground, Bogi palayam puliyanthope highmast N S K Park,Basin elephant and Satta naicken street,K P Park(Dispensary adjustment play ground),Siva roa road and Demollows road in Div 76,77 and 78",Own Sources,6,2017-18,2020-21 NF/2017-18/12242,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,93000,Laying Cement Concrete Road at Corporation Lane (Urudu School opp) and Corporation Second Lane In Dn 77 U 17 Z 6,Own Sources,6,2017-18,2018-19 NF/2017-18/13652,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,208000,"MAINTENANCE OF AMMA PARK AT BASIN ELEPHANT GATE ROAD IN DN-77, U-17, Z-6.( FOR 6 MONTHS ONLY)",Own Sources,6,2017-18,2018-19 NF/2017-18/1436,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,505000,"Desilting at Various streets in Dn77, U 17, Z 6.",Own Sources,6,2017-18,2018-19 NF/2017-18/14967,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,110500,"Maintenance of TPF park at Basin elephant gate road, Dn 77, U 17, Zone 6 ( For the period of 6 months only)",Own Sources,6,2017-18,2018-19 NF/2017-18/1529,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,879000,"Construction of Compound Wall in 16th Ceremony Hall at Ayyavoo Street (MLA Fund) in Dn -77,U-17,Z-6.",MLACDS,6,2017-18,2017-18 NF/2017-18/8243,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,115000,"MAINTENANCE OF PARK (OUT SOURCING FOR THE PERIOD OF 7 MONTHS ) TPF PARK AT BASIN ELEPHANT GATE ROAD IN DIV-77, UNIT-17, ZONE-6.",Own Sources,6,2017-18,2018-19 NF/2017-18/8275,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,999000,"Demolishing and Reconstruction of Strom Water Drain at Choolai High Road,Junction of Elephant Gate Road & Junction of Demellows Road DN 77,Unit 17,Zone 6.",Own Sources,6,2017-18,2018-19 B/2017-18/11868,Buildings,Completed,B-Buildings,78,14900000,"PROPOSED CONSTRUCTION OF COMMUNITY CENTRE FOR GROUND FLOOR AND FIRST FLOOR FLOOR AT SACHITHANANDAM STREET KOSAPET IN DN - 78, UNIT - 17, ZONE - 6.",MLACDS,6,2017-18,2019-20 B/2017-18/11870,Buildings,Completed,B-Buildings,78,4100000,"PROPOSED CONSTRUCTION OF COMMUNITY CENTRE FOR PROVIDING WATER SUPPLY DRAINAGE ARRANGEMENTS AND ELECTRICAL ARRANGEMENTS AND LIFT AT SACHITHANANDAM STREET KOSAPET IN DN-78,UNIT-17,ZONE-6",MPLADS,6,2017-18,2020-21 BR/2017-18/1432,Road Cut,Completed,BR-Bus Route Roads,78,59000,Restoration of Road cut made by CMWSSB at CHOOLAI HIGH ROAD in(Div-78) Zone-78,Deposit Works,6,2017-18,2017-18 BR/2017-18/4143,Roads,Completed,BR-Bus Route Roads,78,749000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -6 For the challan no-B.R.R.C.NO.B4/0422/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4162,Roads,Completed,BR-Bus Route Roads,78,50000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -6 For the challan no-B.R.R.C.NO.B4/0422/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4165,Roads,Completed,BR-Bus Route Roads,78,75000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -6 For the challan no-B.R.R.C.NO.B4/4618/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4166,Roads,Completed,BR-Bus Route Roads,78,294000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -6 For the challan no-B.R.R.C.NO.B4/3946/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4167,Roads,Completed,BR-Bus Route Roads,78,29400,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -6 For the challan no-B.R.R.C.NO.B4/1074/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4168,Roads,Completed,BR-Bus Route Roads,78,582000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -6 For the challan no-B.R.R.C.NO.B4/1076/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4180,Roads,Completed,BR-Bus Route Roads,78,192000,Restoration of OFC road cut made by Idea Communication Ltd in Zone 6 - For the challan no-B.R.R.C.NO.B4/3954/2016,Deposit Works,6,2017-18,2019-20 BR/2017-18/4199,Roads,Completed,BR-Bus Route Roads,78,606000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 6- For the challan no-B.R.R.C.NO.B4/4803/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4203,Roads,Completed,BR-Bus Route Roads,78,606000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 6- For the challan no-B.R.R.C.NO.B4/4803/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4209,Roads,Completed,BR-Bus Route Roads,78,649000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 6- For the challan no-B.R.R.C.NO.B4/4803/2016,Deposit Works,6,2017-18,2018-19 BR/2017-18/4210,Roads,Completed,BR-Bus Route Roads,78,482000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 6- For the challan no-B.R.R.C.NO.B4/4803/2016,Deposit Works,6,2017-18,2018-19 NF/2017-18/1086,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT MANIKKAM STREET IN DN 78 U-17,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/1087,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,570000,"PROPOSED CONSTRUCTION OF COMPOSTING YARD AT ASTAPUJAM ROAD IN DN-78 U-17,ZONE-6",Grants,6,2017-18,2018-19 NF/2017-18/11782,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,401000,"ATTENDING CC PATCH WORK BY USING M30 GRADE CONCRETE AT ANGALAMMAN KOIL WEST MADA STREET IN DN.78, UNIT-17, ZONE - 6",Own Sources,6,2017-18,2018-19 NF/2017-18/12083,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,1316000,"DEMOLITION OF RESIDENTIAL / COMMERCIAL BUILDING AT OLD DOOR NO. 97,NEW NO 48 ASTAPUJAM ROAD, CHOOLAI, CHENNAI 600112 IN DN - 78, UNIT - 17, ZONE - 6. (AS PER THE DIRECTION OF HONURABLE HIGH COURT ORDER DATED: 29.11.2017 IN W.P.NO. 27882/2004)",Own Sources,6,2017-18,2018-19 NF/2017-18/14158,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,39000,"Improvements to Public Convenience at Sydenhams Road in Division - 78, Unit - 17, Zone - 6",Own Sources,6,2017-18,2018-19 NF/2017-18/1452,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,295000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-78,UNIT-17, ZONE - 6",Own Sources,6,2017-18,2018-19 NF/2017-18/14738,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,198000,"Demolition of Existing Health Post at Sachidhanandham 2nd Street, Kosapet, Chennai in Dn. 78, Unit-17, Zone-6",Own Sources,6,2017-18,2020-21 NF/2017-18/8288,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,196000,"Dismantling and Reconstruction of Storm water Drain at Choolai High road, Near Rountana and Desilting Work at Approaching SWD in Dn 78, Unit 17, Zone 6",Own Sources,6,2017-18,2018-19 B/2017-18/14708,Buildings,Completed,B-Buildings,79,14217090,REPAIRS AND IMPROVEMENT WORKS TO CHENNAI SCHOOLS AT VARIOUS LOCATIONS IN ZONE-9,Own Sources,7,2017-18,2019-20 L/2017-18/0128,Electrical,Completed,L-Electrical,79,164450,"Removal & Refixing of Existing 20 Mtr High Mast At Rakki Theatre Junction In Div 79 in Ramnagar Section, Zone-VII, Ambattur",Own Sources,7,2017-18,2018-19 L/2017-18/12325,Electrical,Completed,L-Electrical,79,56495500,"Provision of 1185 Nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 40 W to 50 W LED fitting, 135 nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post With Arch Bracket with 90 W to 120 W LED fitting at Various Locations in Ward 79 in Zone VII, Ambattur.","Loans, Grants And Own Sources",7,2017-18,2018-19 L/2017-18/7606,Electrical,Completed,L-Electrical,79,877000,Laying of 700 Mtrs of 2x16 Sq.mm Alu Cable & 1443 Mtrs of 4x16 Sq.mm Alu Cable at Various Locations in Divisions 79 (Phase - I) in Zone-VII,Own Sources,7,2017-18,2018-19 L/2017-18/7644,Electrical,Completed,L-Electrical,79,854800,Laying of 770 Mtrs of 2x16 Sq.mm Alu Cable & 1329 Mtrs of 4x16 Sq.mm Alu Cable at Various Locations in Divisions 79 (Phase II) in Zone-VII,Own Sources,7,2017-18,2018-19 NG/2017-18/11273,Buildings,Completed,NG-AMBATTUR,79,600000,"Construction of Bio Gas Plant at Ganthi Main Road Amma Unavagam in Div-79, Unit-18, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/1538,Storm Water Drain,Completed,NG-AMBATTUR,79,150000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN VARIOUS STREET IN DIVISION-79 ,UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2017-18,2017-18 NG/2017-18/8734,Roads,Completed,NG-AMBATTUR,79,150000,"Maintanance to Damaged surface to Various street in Dn-79, Unit -18, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9581,Buildings,Completed,NG-AMBATTUR,79,2030000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY CENTER WITH VEGETABLE SHREDDING MACHINE AT ORAGADAM BURIAL GROUND IN DN-79, UNIT -18, ZONE - 7",Own Sources,7,2017-18,2018-19 NG/2017-18/9593,Buildings,Completed,NG-AMBATTUR,79,2030000,"Proposed Construction of Restore Recovery Center (RRC) at MENAMBEDU BURIAL GROUND IN SOUTHERN PORTION in division-81, Unit-18, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/9596,Buildings,Completed,NG-AMBATTUR,79,570000,"PROPOSED CONSTRUCTION OF COMPOSIT YARD AT ORAGADAM BURIAL GROUND IN DIVISION-79,UNIT-18,ZONE-7",Own Sources,7,2017-18,2018-19 BR/2017-18/4169,Roads,Completed,BR-Bus Route Roads,80,200000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -7 For the challan no-B.R.R.C.NO.B4/0422/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4170,Roads,Completed,BR-Bus Route Roads,80,187000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -7 For the challan no-B.R.R.C.NO.B4/4618/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4171,Roads,Completed,BR-Bus Route Roads,80,373000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -7 For the challan no-B.R.R.C.NO.B4/4914/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4172,Roads,Completed,BR-Bus Route Roads,80,20000,Restoration of OFC road cut made by Relaince Jio Communication Ltd in Zone -7 For the challan no-B.R.R.C.NO.B4/4915/2016,Deposit-Asset,7,2017-18,2018-19 BR/2017-18/4182,Roads,Completed,BR-Bus Route Roads,80,187000,Restoration of OFC road cut made by Idea Communication Ltd in Zone 7 - For the challan no-B.R.R.C.NO.B4/0415/2016,Deposit Works,7,2017-18,2019-20 BR/2017-18/4183,Roads,Completed,BR-Bus Route Roads,80,108000,Restoration of OFC road cut made by Idea Communication Ltd in Zone 7 - For the challan no-B.R.R.C.NO.B4/0415/2016,Deposit Works,7,2017-18,2019-20 BR/2017-18/4211,Roads,Completed,BR-Bus Route Roads,80,293000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/1753/2017,Deposit Works,7,2017-18,2018-19 BR/2017-18/4213,Roads,Completed,BR-Bus Route Roads,80,52600,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/1753/2017,Deposit Works,7,2017-18,2018-19 BR/2017-18/4214,Roads,Completed,BR-Bus Route Roads,80,154000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/3169/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4215,Roads,Completed,BR-Bus Route Roads,80,746000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/5025/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4216,Roads,Completed,BR-Bus Route Roads,80,322000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/1707/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4217,Roads,Completed,BR-Bus Route Roads,80,148000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/3168/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4218,Roads,Completed,BR-Bus Route Roads,80,103000,Restoration of OFC road cut made by Airtel Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/3168/2016,Deposit Works,7,2017-18,2018-19 BR/2017-18/4219,Roads,Completed,BR-Bus Route Roads,80,168000,Restoration of OFC road cut made by Vodafone Communication Ltd in Zone 7- For the challan no-B.R.R.C.NO.B4/1073/2017,Deposit Works,7,2017-18,2018-19 L/2017-18/12345,Electrical,Completed,L-Electrical,80,35974800,"provision of 695 Nos of 6Mtr Hot DippedZinc Gulvanising Lamp post with straight brackets with 40 W to 50 W LED FITTING 84NOS of 6mtr Hot DippedZinc Gulvanising Lamp post with arch brackets with 90 W to 120 W LED FITTING 45NOS of 13mtr GI Octagional Lamp post with single straight bracket with 150 W to 165 W LED fITTING AT various location in Ward 80,90 &93 in Zone VII ,Ambattur","Loans, Grants And Own Sources",7,2017-18,2018-19 NG/2017-18/11278,Buildings,Completed,NG-AMBATTUR,80,600000,"Construction of Bio Gas Plant at MGR Street Amma Unavagam in Div-80, Unit-18, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/1531,Storm Water Drain,Completed,NG-AMBATTUR,80,450000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN VARIOUS STREET IN DIVISION-80 ,UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2017-18,2017-18 NG/2017-18/8736,Roads,Completed,NG-AMBATTUR,80,150000,"Maintanance to Damaged surface to Various street in Dn-80, Unit -18, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9591,Buildings,Completed,NG-AMBATTUR,80,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER AT THANGAL ERI PARK AND PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) in Dn-80, Unit-18, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9604,Buildings,Completed,NG-AMBATTUR,80,570000,"PROPOSED CONSTRUCTION OF COMPOSIT YARD AT THANGAL ERI PARK IN DIVISION-80,UNIT-18,ZONE-7",Own Sources,7,2017-18,2018-19 L/2017-18/12343,Electrical,Completed,L-Electrical,81,32694600,"Provision of 461 Nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 40 W to 50 W LED fitting, 123 nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post With Arch Bracket with 90 W to 120 W LED fitting, 45 Nos of 8 Mtr GI Octagonal Lamp post with Double Brackets with 150 W to 165 W LED fitting at Various Locations in Ward 81, 84 to 89, 91 & 92 in Zone VII, Ambattur.","Loans, Grants And Own Sources",7,2017-18,2018-19 L/2017-18/2608,Electrical,Completed,L-Electrical,81,134000,"Removal & Refixing of Existing 16 Mtr High Mast rope At KK road,Ambattur In Div 81 in Padi Section, Zone-VII, Ambattur",Own Sources,7,2017-18,2017-18 NG/2017-18/1478,Storm Water Drain,Completed,NG-AMBATTUR,81,570000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-81,UNIT-18,ZONE-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8732,Roads,Completed,NG-AMBATTUR,81,150000,"Maintanance to Damaged surface to Various street in Dn-81, Unit -18, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8809,Storm Water Drain,Completed,NG-AMBATTUR,81,980000,"Repairs works to Existing Storm water drain and side drains at Various Streets in Dn-79,80,81,82,83, Unit -18, Zone-7",Own Sources,7,2017-18,2019-20 NG/2017-18/9603,Buildings,Completed,NG-AMBATTUR,81,570000,"PROPOSED CONSTRUCTION OF COMPOSIT YARD MENAMBEDU BURIAL GROUND IN DIVISION-81,UNIT-18,ZONE-7",Own Sources,7,2017-18,2018-19 B/2017-18/14710,Buildings,Completed,B-Buildings,82,7695000,REPAIRS IMPROVEMENTS TO CHENNAI SCHOOLS AT VARIOUS LOCATIONS IN ZONE-6,Own Sources,7,2017-18,2019-20 L/2017-18/12329,Electrical,Completed,L-Electrical,82,55480200,"Provision of 1186 Nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 40 W to 50 W LED fitting, 113 nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post With Arch Bracket with 90 W to 120 W LED fitting at Various Locations in Ward 82 in Zone VII, Ambattur.","Loans, Grants And Own Sources",7,2017-18,2018-19 L/2017-18/12330,Electrical,Completed,L-Electrical,82,45109200,"Provision of 984 Nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 40 W to 50 W LED fitting, 87 nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post With Arch Bracket with 90 W to 120 W LED fitting at Various Locations in Ward 82 in Zone VII, Ambattur.","Loans, Grants And Own Sources",7,2017-18,2018-19 L/2017-18/7607,Electrical,Completed,L-Electrical,82,828500,Laying of 542 Mtrs of 2x16 Sq.mm Alu Cable & 1537 Mtrs of 4x16 Sq.mm Alu Cable at Various Locations in Divisions 82(Phase -I) in Zone-VII,Own Sources,7,2017-18,2018-19 L/2017-18/7645,Electrical,Completed,L-Electrical,82,869200,Laying of 407 Mtrs of 2x16 Sq.mm Alu Cable & 1690 Mtrs of 4x16 Sq.mm Alu Cable at Various Locations in Divisions 82(Phase II) in Zone-VII,Own Sources,7,2017-18,2018-19 NG/2017-18/14311,Roads,Completed,NG-AMBATTUR,82,929000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT RAJENDRA PRASAD 2ND STREET IN DIV-79,UNIT-18,ZONE-VII AMBATTUR",Own Sources,7,2017-18,2018-19 NG/2017-18/14334,Roads,Completed,NG-AMBATTUR,82,1412000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PILLAYAR KOIL ARCH STREET IN DIV-82, UNIT-18, ZONE-7 (AMBATTUR)",Own Sources,7,2017-18,2018-19 NG/2017-18/14395,Roads,Completed,NG-AMBATTUR,82,188000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT KARUKKU OLD STREET IN DIV-82, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14399,Roads,Completed,NG-AMBATTUR,82,2219000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PASUMPON NAGAR EXTN 4TH STREET IN DIV-82, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14413,Roads,Completed,NG-AMBATTUR,82,381000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VARADHAN STREET IN DIV-82, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14414,Roads,Completed,NG-AMBATTUR,82,968000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT KUPPUSAMY STREET IN DIV-82, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14595,Roads,Completed,NG-AMBATTUR,82,630000,Forming and stregnthening of B.T Course Road at Hindustan motor nagar in div -82 unit-18 zone-7,MLACDS,7,2017-18,2018-19 NG/2017-18/1876,Buildings,Completed,NG-AMBATTUR,82,1370000,"Annual Maintanence of ETP for 12 Months and repair works to Existing ETP of Sloter house at Madhanakuppam in Div-82, Unit-19, Zone-7",Own Sources,7,2017-18,2019-20 NG/2017-18/8487,Storm Water Drain,Completed,NG-AMBATTUR,82,850000,"Desilting of SIDE DRAINS & SWD at various streets in division-82,unit-18,zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8720,Roads,Completed,NG-AMBATTUR,82,150000,"Maintanance to Damaged surface to Various street in Dn-82, Unit -18, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9578,Buildings,Completed,NG-AMBATTUR,82,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER AT MENAMBEDU BURIAL GROUND AND PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) in Dn-82, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9632,Buildings,Completed,NG-AMBATTUR,82,570000,"PROPOSED CONSTRUCTION OF COMPOSIT YARD AT MENAMBEDU BURIAL GROUND IN DIVISION-82,UNIT-18,ZONE-7",Own Sources,7,2017-18,2018-19 BR/2017-18/11763,Roads,Completed,BR-Bus Route Roads,83,19594000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at North Station Road in Dn-83, Zone-VII",Grants,7,2017-18,2018-19 BR/2017-18/11972,Roads,Completed,BR-Bus Route Roads,83,2030000,"Forming Approach Road to existing bridge portion at Water Canal Road (Towards 100 feet Road) in Dn-83, Zone - 7",Own Sources,7,2017-18,2018-19 BR/2017-18/11973,Roads,Completed,BR-Bus Route Roads,83,1664000,"Forming and Strengthening the Approach Road to existing bridge portion at Water Canal Road (Towards 100 feet Road) in Dn-83, Zone - 7",Own Sources,7,2017-18,2018-19 BR/2017-18/11974,Roads,Completed,BR-Bus Route Roads,83,2415000,"Forming Approach Road to existing bridge portion at Water Canal Road (Towards madhanankuppam) Reach - 1 in Dn-83, Zone - 7",Own Sources,7,2017-18,2018-19 BR/2017-18/11975,Roads,Completed,BR-Bus Route Roads,83,2240000,"Forming Approach Road to existing bridge portion at Water Canal Road (Towards madhanankuppam) Reach - 2 in Dn-83, Zone - 7",Own Sources,7,2017-18,2018-19 BR/2017-18/11976,Roads,Completed,BR-Bus Route Roads,83,2047000,"Forming and Strengthening the Approach Road existing bridge portion at Water Canal Road ( towards madhanankuppam Road) Reach - 1 in Dn-83, Zone- 7",Own Sources,7,2017-18,2018-19 BR/2017-18/11977,Roads,Completed,BR-Bus Route Roads,83,1688000,"Forming and Strengthening the Approach Road to existing bridge portion at water Canal Road ( Towards madhanankuppam) Reach - 2 in Dn-83, Zone-7",Own Sources,7,2017-18,2018-19 BR/2017-18/12144,Roads,Completed,BR-Bus Route Roads,83,2349000,"Attending temporary patch work at Water Canal Road (From the jn of Jawaharlal Nehru Salai to Bridge) in Dn-83, Zone-7",Own Sources,7,2017-18,2018-19 L/2017-18/12326,Electrical,Completed,L-Electrical,83,52804400,"Provision of 909 Nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 40 W to 50 W LED fitting , 252 Nos of 6 Mtr Hot Dipped Zinc Galvanising Lamp post with Single Arch Brackets with 90 W to 120 W LED fitting and 50 Nos of 8 Mtr Hot Dipped Zinc Galvanising Lamp post with Straight Brackets with 150 W to 165 W LED fitting at Various Locations in Ward 83 in Zone VII, Ambattur.","Loans, Grants And Own Sources",7,2017-18,2018-19 L/2017-18/7608,Electrical,Completed,L-Electrical,83,772100,Laying of 1240 Mtrs of 2x16 Sq.mm Alu Cable & 754 Mtrs of 4x16 Sq.mm Alu Cable at Various Locations in Divisions 83 in Zone-VII,Own Sources,7,2017-18,2018-19 L/2017-18/7610,Electrical,Completed,L-Electrical,83,794900,Proposed Laying of 608 Mtrs of 4 x16 Sq.mm Alu Cable & 1395 Mtrs of 4x16 Sq.mm Alu Cable at Various Locations in Divisions 83 & 84 in Zone-VII,Own Sources,7,2017-18,2018-19 L/2017-18/9770,Electrical,Completed,L-Electrical,83,193400,"Shifting of Pillar Box and replacement of 316 mtrs of 4 x 16 sqmm Cable at 200 Ft Rd & North Railway Station road in Div 83, Zone VII, Ambattur",Own Sources,7,2017-18,2018-19 NG/2017-18/14366,Roads,Completed,NG-AMBATTUR,83,1527000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TNHB 70th ROAD AND STATION ROAD IN DIV-83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14368,Roads,Completed,NG-AMBATTUR,83,880000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT STATION ROAD IN DIV-83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14369,Roads,Completed,NG-AMBATTUR,83,4190000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TVS NAGAR EXTENSTION, KANDIGAI ROAD AND NRS ROAD IN DIV-83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14379,Roads,Completed,NG-AMBATTUR,83,1162000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VANASAKTHI NAGAR EXTN IN DIV-83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14384,Roads,Completed,NG-AMBATTUR,83,1982000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NETHAJI STREET IN DIV-83, UNIT-18,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14387,Roads,Completed,NG-AMBATTUR,83,1833000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THIRUMAL NAGAR RS NAGAR IN DIV-83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14389,Roads,Completed,NG-AMBATTUR,83,1936000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD TVS NAGAR 1st STREET EXTN IN DIV-83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/1700,Buildings,Completed,NG-AMBATTUR,83,380000,"DESILTING WORK AT VARIOUS STREET IN DIVISION-83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8737,Roads,Completed,NG-AMBATTUR,83,150000,"FLOOD WORK MAINTENANCE AT VARIOUS STREET IN DIVISION -83, UNIT-18, ZONE-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9594,Buildings,Completed,NG-AMBATTUR,83,2030000,"Proposed Construction of Restore Recovery Center (RRC) at TNHB 61ST PARK and procurement of Machineries ( shredding Machine , Weighing Machine, Sewing and Vegetable Cutter Machine) in division-83, Unit-18, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/9602,Buildings,Completed,NG-AMBATTUR,83,570000,"PROPOSED CONSTRUCTION OF COMPOSIT YARD AT TNHB 61st STREET IN DIVISION-83,UNIT-18,ZONE-7",Own Sources,7,2017-18,2018-19 L/2017-18/7609,Electrical,Completed,L-Electrical,84,786600,"Proposed Laying of 1504 Mtrs of 4x16 Sq.mm Alu Cable and 310 Mtrs of 2x16 Sq.mm aluminium cable at Various Locations in Divisions 83,84 in Zone-VII",Own Sources,7,2017-18,2018-19 L/2017-18/7646,Electrical,Completed,L-Electrical,84,821600,Proposed Laying of 1370 Mtrs of 4 x16 Sq.mm Alu Cable at Station road (From Britaniiya to central avenue Divisions 84 in Zone-VI,Own Sources,7,2017-18,2018-19 NG/2017-18/11241,Buildings,Completed,NG-AMBATTUR,84,69000,"Improvement and Maintenance of bio gas at East Avenue road in Division -84, Unit - 19, Zone -7",Own Sources,7,2017-18,2018-19 NG/2017-18/3675,Buildings,Completed,NG-AMBATTUR,84,1800000,"Construction of Store Room, Locker Room, Toilet and Water Supply Arrangement for Tennis Court at East Avenue road in Division -84, Unit - 19, Zone -7.",Own Sources,7,2017-18,2018-19 NG/2017-18/8458,Storm Water Drain,Completed,NG-AMBATTUR,84,360000,"Desilting To The Existing Road Side Drain And Storm Water Drain At Various Streets In Division-84, Unit-19,Zone-7.",Own Sources,7,2017-18,2017-18 NG/2017-18/8474,Storm Water Drain,Completed,NG-AMBATTUR,84,175000,"Repair Works To The Existing Road Side Drain And Storm Water Drain At Various Streets In Division-84, Unit-19,Zone-7.",Own Sources,7,2017-18,2017-18 NG/2017-18/8731,Roads,Completed,NG-AMBATTUR,84,150000,"PROVIDING NEW DE-WATERING MOTOR, POWER SAW, TELESCOPIC SAW AND REPAIR WORKS TO EXISTING DE-WATERING PUMP, POWER SAW AND TELESCOPIC SAW...ETC FOR ATTENDING FLOOD WORK IN DIVISION-84, UNIT-19, ZONE-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9350,Buildings,Completed,NG-AMBATTUR,84,29400,"Improvement and Maintenance of Public convenience at Gangai amman koil street in Division -84, Unit - 19, Zone -7",Own Sources,7,2017-18,2018-19 NG/2017-18/9607,Buildings,Completed,NG-AMBATTUR,84,2030000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY CENTRE AT KANNAGI NAGAR BURIAL GROUND AND PROCUREMENT OF MACHINERIES (SHERDDING MACHINE,WEIGHING MACHINE,SWEING MACHINE & VEGITABLE CUTTING MACHINE) IN DIVIOSION-84, UNIT-19, ZONE-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9623,Buildings,Completed,NG-AMBATTUR,84,570000,"CONSTRUCTION OF COMPOST YARD AT KANNAGI NAGAR BURIAL GROUND IN DIVISION-84,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 L/2017-18/12517,Electrical,Completed,L-Electrical,85,2355000,PROPOSED ERECTION OF 62 NOS 7 MTR LAMP POST STRAIGHT BRACKET WITH 40 WATTS LED FITTINGS AT INDIAN RAILWAYS WELFARE ORGANIZATION AMBATTUR ( TICYCLES BACK SIDE )VILLAGE IN DN 85 ZONE VII AMBATTUR,Deposit Works,7,2017-18,2018-19 L/2017-18/12764,Electrical,Completed,J-Bridges,85,998400,"PROPOSED ERECTION OF 8 NOS OF 8 MTR GI OCTAGANAL LAMP POST DOUBLE ST BRACKET WITH 150 T0 165 WATTS LED FITTINGS AT CANAL ROAD BRIDGE WESTERN SIDE(MADANAMKUPPAM ) IN DN 83 ,ZONE VII AMBATTUR",Own Sources,7,2017-18,2018-19 NG/2017-18/10030,Buildings,Completed,NG-AMBATTUR,85,160000,"Providing Bore well with Water supply arrangements for Zone-7 Lorry Station office in Div-85,Unit-19,Zone-7",Own Sources,7,2017-18,2019-20 NG/2017-18/14498,Roads,Completed,NG-AMBATTUR,85,223000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 2nd CANAL ROAD IN DIV-85, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14499,Roads,Completed,NG-AMBATTUR,85,343000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THIRUVALLUR STREET IN DIV-86, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14523,Roads,Completed,NG-AMBATTUR,85,374000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT KAMARAJAPURAM MAIN ROAD IN DIV-85, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/15552,Buildings,Completed,NG-AMBATTUR,85,345000,"Additional Maintenance for UPHC Building At Varadharajapuram in Zone-7 Div-85,Unit-19,Zone-7 .",Own Sources,7,2017-18,2019-20 NG/2017-18/16931,Buildings,Completed,NG-AMBATTUR,85,500000,"REPAIRS AND MAINTENANCE WORKS FOR ZONAL OFFICE BUILDING AT C.T.H ROAD IN DIVISION - 85, UNIT - 19, ZONE - 7.",Own Sources,7,2017-18,2019-20 NG/2017-18/1697,Buildings,Completed,NG-AMBATTUR,85,55000,"IMPROVEMENTS TO AE OFFICE ROOM WITH TOILET BLOCK PROVIDING WHITE WASHING, SLIDING WINDOW,REPAIR WORKS TO ALUMINIUM DOOR IN DIV-85,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2395,Buildings,Completed,NG-AMBATTUR,85,297000,"Providing Open Drain with Cover Slab and Flooring Arrangement Water supply, Electrical Fitting for Health Post at Varadharajapuram in Div-85,Unit-19,Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/2424,Buildings,Completed,NG-AMBATTUR,85,94000,"PROVIDING PAINTING AND REPAIR WORKS TO ALUMINIUM DOORS AND WINDOWS AT ZONAL OFFICE-7 IN DIV-85,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2426,Buildings,Completed,NG-AMBATTUR,85,89000,"PROVIDING ALUMINIUM DOORS AND WINDOWS FOR EE ROOM,AD ROOM,ADHAR CABIN, E SEVA CENTER AT ZONL OFFICE-7 IN DIV-85,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2427,Buildings,Completed,NG-AMBATTUR,85,59000,"PROVIDING STAINLESS STEEL HANDRAIL AND PARTITION FOR RAMP PORTION AND ADHAR SECTION AT ZONAL OFFICE -7 IN DIV-85 ,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2428,Buildings,Completed,NG-AMBATTUR,85,145000,"PROVIDING OVERHEAD TANK PROVISION WITH WATER TANK AND PIPE LINE ARRANGEMENTS AT ZONAL OFFICE -7 IN DIV-85,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2431,Buildings,Completed,NG-AMBATTUR,85,146000,"PROVIDING DRIVER SHED FOR ZONAL OFFICE IN DIV-85,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2432,Buildings,Completed,NG-AMBATTUR,85,120000,"PROVIDING RAMP ARRANGEMENTS FOR E SEVA CENTER,ATTENDING PLUMPING REPAIR WORKS AND PROVIDING ELECTRICAL FITTINGS FOR ZONAL OFFICE-7 IN DIV-85,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2433,Buildings,Completed,NG-AMBATTUR,85,62000,"PROVIDING MOTOR ARRANGEMENTS AND PIPE LINE REPAIR WORKS TO DIVISION-85 OFFICE,PUBLIC CONVENIENCE AT KAMARAJAPURAM,MANGALAPURAM IN DIV-85,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/2434,Buildings,Completed,NG-AMBATTUR,85,27800,"DISMANTLING EXISTING BUILDING FOR ZONE-7 LORRY STATION AND CLEARING THE SAME AT ZONE-7 IN DIV-85 ,UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/7100,Storm Water Drain,Completed,NG-AMBATTUR,85,350000,"Construction Of Side Drain with Providing Cover Slab at GNG road Near Ambattur Railway Station in Div- 85, Unit-19, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/7148,Storm Water Drain,Completed,NG-AMBATTUR,85,215000,"Providing Culvert For Side Drain of Across the Road at kullakarai Street in Dv-85, Unit-19, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/7225,Buildings,Completed,NG-AMBATTUR,85,367000,"Providing Barbed Fencing with Concrete post for OSR land at Sri Senthil Murugan nagar in Div -82, Unit-19, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8416,Roads,Completed,NG-AMBATTUR,85,866000,Desiliting of SWD,Own Sources,7,2017-18,2017-18 NG/2017-18/8451,Storm Water Drain,Completed,NG-AMBATTUR,85,1407000,"Improvement and Repair works to the Existing Side drain at various Street in Div-85, Unit-19, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8728,Buildings,Completed,NG-AMBATTUR,85,150000,"Supplying and Providing Motor, JCB, Power Saw, with Labour and Wet Mix Macadam for Flood Relief Work in Division - 85, Unit - 19, Zone - 7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9230,Buildings,Completed,NG-AMBATTUR,85,687000,"Repair works to Existing Compound Wall For Damaged Portion at Rear side of Zonal Office (Kannathamman koil Street) in Div - 85,Unit-19,Zone-7",Own Sources,7,2017-18,2019-20 B/2017-18/14862,Buildings,Completed,B-Buildings,86,10821380,REPAIRS AND MAINTENANCE WORKS TO CHENNAI SCHOOL BUILDINGS AT VARIOUS LOCATIONS IN ZONE-8,Own Sources,7,2017-18,2019-20 L/2017-18/7593,Electrical,Completed,L-Electrical,86,995800,"Proposed supply and laying of 1860mtrs of 4X16 Sqmm Al UG cable,527mtrs of 2X16 SQmm Al UG cable at Ayappakkam road,Vannier st and various streets in ward 86 and ward 87 Zone VII, Ambattur.",Own Sources,7,2017-18,2018-19 NG/2017-18/14524,Roads,Completed,NG-AMBATTUR,86,557000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VEKATESHWARA STREET IN DIV-86, UNIT19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14527,Roads,Completed,NG-AMBATTUR,86,2773000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PRIYA COLONY IN DIV-86, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14529,Roads,Completed,NG-AMBATTUR,86,669000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT LAKSHMI AMMAN KOIL STREET IN DIV-86, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14538,Roads,Completed,NG-AMBATTUR,86,334000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT UDAYAR PALAYAM CROSS STREET IN DIV-86, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14539,Roads,Completed,NG-AMBATTUR,86,1189000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MUNUSAMY 1st CROSS STREET IN DIV-86, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14540,Roads,Completed,NG-AMBATTUR,86,1783000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MUNUSAMY 2nd CROSS STREET IN DIV-86, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14587,Roads,Completed,NG-AMBATTUR,86,832000,"Laying 80mm Thick Cement Concrete Paver Block Road at 1)Kuyavar Street, 2)Lakshmi Amman Kovil Cross Street, 3)Malayathamman Kovil Street Lane, 4)Nehru Nagar 2nd Cross Street Lane, 5)New Pillayar Kovil 2nd Cross Street, 6)Pillayar Kovil 1st Cross Street in Division-86, Unit-19, Zone-7.",MLACDS,7,2017-18,2018-19 NG/2017-18/14588,Bridges,Completed,NG-AMBATTUR,86,668000,"Laying 80mm Thick Cement Concrete Paver Block Road at 1)Pillayar Kovil 2nd Cross Street, 2)Nehru Nagar 1st Cross Street Lane, 3)New Pillayar Kovil 1st Cross Street, 4)New Pillayar Kovil 4th Cross Street, 5)Kamaraj Nagar 2nd Cross Lane, 6)Bajanai Kovil Street Lane in Division-86, Unit-19, Zone-7.",MLACDS,7,2017-18,2018-19 NG/2017-18/4041,Roads,Completed,NG-AMBATTUR,86,1580000,"Providing and Laying BT Road at Kamaraj Nagar Street (School Street) in Division 86, Unit - 19, Zone-7.",Own Sources,7,2017-18,2017-18 NG/2017-18/7152,Roads,Completed,NG-AMBATTUR,86,410000,"Temporary Restoration to damages road at Chelliamman Kovil Extn Road in Division-86, Unit-19, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/7875,Roads,Completed,NG-AMBATTUR,86,870000,"Temporary Restoration to damages road at Nageshwara Rao Road in Division-86, Unit-19, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/7876,Roads,Completed,NG-AMBATTUR,86,340000,"Temporary Restoration to damages road at Nageshwara Rao Road 1st Cross Street, 2nd Cross Street and Nageshwara Rao Road Lane in Division-86, Unit-19, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/7877,Roads,Completed,NG-AMBATTUR,86,680000,"Temporary Restoration to damages road at Nageshwara Rao Road 3rd Cross Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/7878,Roads,Completed,NG-AMBATTUR,86,320000,"Temporary Restoration to damages road at Nageshwara Rao Road 4th & 5th Cross Streets in Division-86, Unit-19, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/8467,Storm Water Drain,Completed,NG-AMBATTUR,86,314000,"Improvement and Repair works to the Existing Side drain at various Street in Div-86, Unit-19, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8473,Storm Water Drain,Completed,NG-AMBATTUR,86,290000,"Desiliting of SWD at various Street in Div-86, Unit-19, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8726,Buildings,Completed,NG-AMBATTUR,86,150000,"Supplying and Providing Motor, JCB, Power Saw, with Labour and Wet Mix Macadam for Flood Relief Work in Division - 86, Unit - 19, Zone - 7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9095,Roads,Completed,NG-AMBATTUR,86,950000,"Temporary Restoration to damages road at Bharathidasan Nagar 1st Cross street, Bharathidasan Nagar 2nd Cross street,Bharathidasan Nagar 3rd Cross street,Anaganna Reddy Street, New Pillayar Kovil 1st Cross Street,New Pillayar Kovil 2nd Cross Street,New Pillayar Kovil 3rd Cross Street,Gandhi 1st Cross Street,Gandhi 2nd Cross Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9628,Buildings,Completed,NG-AMBATTUR,86,2030000,"Proposed Construction of Resource Recovery Centre at Athipet Dumping Yard and procurement of Machineries (Sherdding Machine, Weighing Machine, Sewing Machine and Vegetable Cutter Machine) in Division-86, Unit - 19, Zone -7.",Own Sources,7,2017-18,2018-19 P/2017-18/13030,Parks,Completed,P-Parks and Playfields,86,8276484,"FORMATION OF NEW PARK AT CTH ROAD, (OPP TO KOCHAR BUILDING) IN DN-86, ZONE - VII",Grants,7,2017-18,2019-20 P/2017-18/13043,Parks,Completed,P-Parks and Playfields,86,7827093,"FORMATION OF NEW PARK AT SIDCO ROAD NEAR ICICI BANK IN DN - 86, ZONE - VII",Grants,7,2017-18,2019-20 P/2017-18/13045,Parks,Completed,P-Parks and Playfields,86,12198100,"FORMATION OF NEW PARK AT 2ND CROSS STREET REAR SIDE OF INDIA LAND AMBATTUR INDUSTRIAL ESTATE IN DN-86, ZONE - VII.",Grants,7,2017-18,2019-20 P/2017-18/15956,Parks,Completed,P-Parks and Playfields,86,5800000,"Formation of new park at Agni estate pambai street & Kothavari street - ICF colony in division 86, Zone 7","Loans, Grants And Own Sources",7,2017-18,2019-20 P/2017-18/6213,Parks,Completed,P-Parks and Playfields,86,8074000,"FORMATION OF NEW PARK AT VGN SHANTHI NAGAR IN DN-86, ZONE - VII.",Grants,7,2017-18,2019-20 NG/2017-18/11260,Buildings,Completed,NG-AMBATTUR,87,408000,"Providing roof sheet and repairing work to Padi EOC building at church road in div-87,Unit-19,zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/14419,Roads,Completed,NG-AMBATTUR,87,3028000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SOUTH MADA STREET IN DIV-87, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14423,Roads,Completed,NG-AMBATTUR,87,1014000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THIRUNANASAMBATHAR STREET IN DIV-87, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/1589,Storm Water Drain,Completed,NG-AMBATTUR,87,550000,"Desilting of SWD at various street in division-87, unit-19, zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/8827,Roads,Completed,NG-AMBATTUR,87,150000,"Supplying wed mix macadam, GSB ,Stone dust,TATA Ace, Roller, Sand bag, Labour for flood relief work in division -87,Unot-19,Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/9610,Buildings,Completed,NG-AMBATTUR,87,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER AT ENANGO NAGAR BURIAL GROUND AND PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) in Dn-87, Unit-19, Zone-7",Own Sources,7,2017-18,2018-19 L/2017-18/7594,Electrical,Completed,L-Electrical,88,994700,"Proposed supply and laying of 1984mtrs of 4X16 Sqmm Al UG cable,372mtrs of 2X16 SQmm Al UG cable at Ap Plots,C sector,TI School road road and various streets in ward 81 and ward 88 Zone VII, Ambattur.",Own Sources,7,2017-18,2018-19 L/2017-18/7595,Electrical,Completed,L-Electrical,88,989700,"Proposed Supply and laying of 2149mtrs of 3 1/2X25 sqmm Al.UG cable for 12 nos of highmast at Padi National highways in ward88,Zone VII, Ambattur.",Own Sources,7,2017-18,2018-19 L/2017-18/7706,Electrical,Completed,L-Electrical,88,858700,"Proposed supply and laying of 1151 mtrs of 4X16 Sqmm Al UG cable,988 mtrs of 2X16 SQmm Al UG cable at Kumaren nagar,Thendral st,Cholapuram main road and various streets in ward 81 and ward 88 Zone VII, Ambattur.",Own Sources,7,2017-18,2018-19 NG/2017-18/12389,Buildings,Completed,NG-AMBATTUR,88,95000,"Improvement and Maintenance works to Bio-Gas Plant at Pandurangapuram in Div-88, Unit-19, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/13158,Buildings,Completed,NG-AMBATTUR,88,109000,"Improvement and Maintenance works to Compost pit at Pandurangapuram Burial Ground in Div-88, Unit-19, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14424,Roads,Completed,NG-AMBATTUR,88,1752000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SARTHAR PATEL STREET, TVS NAGAR 6th CROSS STREET, RAJA KRISHNAN STREET, KATTABOMMAN STREET, NSC BOSE STREET, THIRU.VI.KA STREET IN DIV-88, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14461,Roads,Completed,NG-AMBATTUR,88,2291000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SCHOOL ROAD & PARK ROAD IN DIV-88, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14469,Roads,Completed,NG-AMBATTUR,88,465000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT B-SECTOR 6th STREET IN DIV-88, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14471,Roads,Completed,NG-AMBATTUR,88,714000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NORTH MAIN ROAD & AP PLOT 10th STREET IN DIV-88, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14474,Roads,Completed,NG-AMBATTUR,88,365000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT B-SECTOR 1st AVENUE & PARK ROAD IN DIV-88, UNIT-19,ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14476,Roads,Completed,NG-AMBATTUR,88,564000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT WEST GATE ROAD IN DIV-88, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14480,Roads,Completed,NG-AMBATTUR,88,1149000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT KAVITHA STREET IN DIV-88, UNIT-19, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/14688,Roads,Completed,P-Parks and Playfields,88,5127000,TREE PLANTATION - ZONE-7,Own Sources,7,2017-18,2021-22 NG/2017-18/1509,Buildings,Completed,NG-AMBATTUR,88,63400,"Improvement works to Burial Ground at Pandurangapuarm in Div-88, Unit-19, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/8359,Roads,Completed,NG-AMBATTUR,88,328000,"Desilting the Existing Side drain & Storm water Drain at Various Street in Div-88, Unit-19, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8730,Roads,Completed,NG-AMBATTUR,88,150000,"Supplying Wet Mix Macadam & GSB, Stone Dust, TATA ACE, Roller, Sand bag, Labour for Flood Relief Work in Division - 88, Unit - 19, Zone - 7.",Own Sources,7,2017-18,2018-19 NG/2017-18/8796,Roads,Completed,NG-AMBATTUR,88,267000,"Repairs works to Existing Side Drain & Storm water Drain at Various Street in Division-88, Unit-19, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9601,Buildings,Completed,NG-AMBATTUR,88,2030000,"Proposed construction of Resources Recovery Centre at Kannagi nagar Burial ground in (div84) and procurement of macheneries (Shredding machine,Weighting machine,Sewing machineand Vegetable Cutter machine) at div-88,Unit-19,Zone-7",Own Sources,7,2017-18,2018-19 P/2017-18/13044,Parks,Completed,P-Parks and Playfields,88,5574100,"FORMATION OF NEW PARK AT CTH ROAD, NEAR SARAVANA STORES IN DN- 88, ZONE - VII",Grants,7,2017-18,2019-20 P/2017-18/13047,Parks,Completed,P-Parks and Playfields,88,16207866,"FORMATION OF NEW PARK AT (ONGC LAND) PARK ROAD, AMBATTUR IN DN-88, ZONE - VII",Grants,7,2017-18,2019-20 B/2017-18/15037,Buildings,Completed,B-Buildings,89,7966600,REPAIR AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE IN ZONE-8,Own Sources,7,2017-18,2019-20 D/2017-18/6901,Storm Water Drain,Completed,D-Storm Water Drains,89,72430000,"Construction of flood protection wall, canal lining & other improvements to Padikuppam canal (from chainage 0 to 925) in Padikuppam water shed of Cooum basin in the expanded areas of Greater Chennai Corporation. Padikuppam water shed in division 89,Zone - 7.",Loans And Grants,7,2017-18,2019-20 NG/2017-18/11573,Roads,Completed,NG-AMBATTUR,89,2870000,"PROVIDING BLACK TOPPING ROAD AT ASHAYA COLONY 2nd AVENUE Dn-89 AND 93, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/14686,Roads,Completed,NG-AMBATTUR,89,1000000,"LAYING OF CEMENT CONCRETE ROAD AT CROSS STREETS IN DN 89, UNIT - 20, ZONE - 7",MLACDS,7,2017-18,2018-19 NG/2017-18/3778,Parks,Completed,NG-AMBATTUR,89,200000,"Repairs to Pathway at Elango Play Ground(R57) in Dn 89, Unit 20, zone 7",Own Sources,7,2017-18,2018-19 NG/2017-18/8603,Storm Water Drain,Completed,NG-AMBATTUR,89,500000,"Desilting of Existing Strom water Drain at Various Street in Dn-89, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8604,Roads,Completed,NG-AMBATTUR,89,150000,"Maintanance to Damaged surface to Various street in Dn-89, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8804,Storm Water Drain,Completed,NG-AMBATTUR,89,650000,"Repairs to Existing SWD at Various Street in Dn-89 TO 93, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9580,Buildings,Completed,NG-AMBATTUR,89,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER AT ELANGO NAGAR BURIAL GROUND AND PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) in Dn-89, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 D/2017-18/6902,Storm Water Drain,Completed,D-Storm Water Drains,90,58240000,"Construction of flood protection wall, canal lining & other improvements to Padikuppam canal (from chainage 925 to 1225) in Padikuppam water shed of Cooum basin in the expanded areas of Greater Chennai Corporation. Padikuppam water shed in division 90,Zone - 7.",Loans And Grants,7,2017-18,2019-20 D/2017-18/6903,Storm Water Drain,Completed,D-Storm Water Drains,90,65560000,"Construction of flood protection wall, canal lining & other improvements to Padikuppam canal (from chainage 1225 to 1575) in Padikuppam water shed of Cooum basin in the expanded areas of Greater Chennai Corporation. Padikuppam water shed in division 90,Zone - 7.",Loans And Grants,7,2017-18,2019-20 D/2017-18/6904,Storm Water Drain,Completed,D-Storm Water Drains,90,52070000,"Construction of flood protection wall, canal lining & other improvements to Padikuppam canal (from chainage 1575 to 1853) in Padikuppam water shed of Cooum basin in the expanded areas of Greater Chennai Corporation. Padikuppam water shed in division 90,Zone - 7.",Loans And Grants,7,2017-18,2019-20 NG/2017-18/11616,Roads,Completed,NG-AMBATTUR,90,3056000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SOUNDARYA COLONY 6TH AVENUE IN Dn-90, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11617,Roads,Completed,NG-AMBATTUR,90,9439000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PADIPUDHU NAGAR MAIN ROAD IN Dn-90, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/1744,Parks,Completed,NG-AMBATTUR,90,59000,"Annual Maintenance and repair work at Golden Jubilee park in Div - 90, Unit-20, Zone-7.",Own Sources,7,2017-18,2019-20 NG/2017-18/8605,Storm Water Drain,Completed,NG-AMBATTUR,90,483000,"Desilting of Existing Strom water Drain at Various Street in Dn-90, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8606,Roads,Completed,NG-AMBATTUR,90,150000,"Maintanance to Damaged surface to Various street in Dn-90, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9582,Buildings,Completed,NG-AMBATTUR,90,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) AT PADIKUPPAM BURIAL GROUND ROAD in Dn-90, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 D/2017-18/6435,Storm Water Drain,Completed,D-Storm Water Drains,91,56906000,"Construction of flood protection wall, canal lining and other Improvements to Ambattur Sidco Canal from Ambattur Estate Road (Ch-0m) to Mogappair west 3rd Main Road (Ch - 670m) in Nolambur watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone - 7, Package No. 24A",Loans And Grants,7,2017-18,2019-20 D/2017-18/6466,Storm Water Drain,Completed,D-Storm Water Drains,91,71010000,"Construction of flood protection wall, canal lining and other Improvements to Ambattur Sidco Canal from Mogappair west 3rd Main Road (Ch- 670m) to Nolambur Canal (Ch - 1320m) in Nolambur watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone - 7, Pakage No.24B",Loans And Grants,7,2017-18,2019-20 D/2017-18/6469,Storm Water Drain,Completed,D-Storm Water Drains,91,55088000,"Construction of flood protection wall, canal lining and other Improvements to Nolambur Canal from V.C. Garden Road (Ch- 405m) to Bharathi Salai (Ch - 808m) in Nolambur watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone - 7, Package No. - 25B",Loans And Grants,7,2017-18,2019-20 D/2017-18/6473,Storm Water Drain,Completed,D-Storm Water Drains,91,69478000,"Construction of flood protection wall, canal lining and other Improvements to Nolambur Canal from Ambattur Sidco Canal confluence point (Ch.1275m) to Mogappair Eri Scheme 4th Main Road (Ch.1687m) in padikuppam watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone -7, Package No. 25D",Loans And Grants,7,2017-18,2019-20 D/2017-18/6474,Storm Water Drain,Completed,D-Storm Water Drains,91,63917000,"Construction of flood protection wall, canal lining and other Improvements to Nolambur Canal from Mogappair Eri Scheme 4th Main Roadconfluence point (Ch.1687m) to Mogappair Eri Scheme 3rd Main Road (Ch.2044m) in Nolambur watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone -7, Package No. 25E",Loans And Grants,7,2017-18,2019-20 D/2017-18/6480,Storm Water Drain,Completed,D-Storm Water Drains,91,55832000,"Construction of flood protection wall, canal lining and other Improvements to Nolambur Canal from Mogappair West 3rd Main Road (Ch.0m) V.G.N. Garden Road (Ch. 405m) in padikuppam watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone -7, Package No. 25A",Loans And Grants,7,2017-18,2019-20 D/2017-18/6481,Storm Water Drain,Completed,D-Storm Water Drains,91,74193000,"Construction of flood protection wall, canal lining and other Improvements to Nolambur Canal from Bharathi Salai (Ch.808m) to Ambattur Sidco Canal Confluence point (Ch.1275m) in padikuppam watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone -7, Package No. 25C",Loans And Grants,7,2017-18,2019-20 NG/2017-18/0221,Buildings,Completed,NG-AMBATTUR,91,2015000,PROPOSED CONSTRUCTION OF MULTI PURPOSE HALL AT 6TH BLOCK IN MOGAPPAIR WEST DIVISION-91 UNIT-20 ZONE-07 AMBATTUR,MLACDS,7,2017-18,2018-19 NG/2017-18/11577,Roads,Completed,NG-AMBATTUR,91,1843000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT JESWANTH NAGAR 1st MAIN ROAD Dn-91, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11579,Roads,Completed,NG-AMBATTUR,91,1033000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT JESWANTH NAGAR 3rd MAIN ROAD Dn-91, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11583,Roads,Completed,NG-AMBATTUR,91,1033000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT JESWANTH NAGAR 4TH MAIN ROAD Dn-91, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11589,Roads,Completed,NG-AMBATTUR,91,1033000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT JESWANTH NAGAR 5TH MAIN ROAD Dn-91, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11611,Roads,Completed,NG-AMBATTUR,91,1132000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT JESWANTH NAGAR 6TH MAIN ROAD Dn-91, Unit-20, Zone-7",Own Sources,7,2017-18,2018-19 NG/2017-18/11612,Roads,Completed,NG-AMBATTUR,91,817000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT JESWANTH NAGAR EXTN 1st STREET Dn-91, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11614,Roads,Completed,NG-AMBATTUR,91,1534000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TNHB 7TH BLOCK CANEL ROAD Dn-91, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/8607,Roads,Completed,NG-AMBATTUR,91,150000,"Maintanance to Damaged surface to Various street in Dn-91, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8714,Storm Water Drain,Completed,NG-AMBATTUR,91,465000,"Desilting of Existing Strom water Drain at Various Street in Dn-91, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9583,Buildings,Completed,NG-AMBATTUR,91,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER AT PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) AT MOGAPPAIR ERI SCHEME 7th CROSS STREET IN DN-91, UNIT-20, ZONE-7.",Own Sources,7,2017-18,2018-19 L/2017-18/6293,Electrical,Completed,L-Electrical,92,987900,"PROVISION FOR CABLE REPLACEMENT FOR 2340 MTRS OF 4X16 SQ.MM AL.UG CABLE FOR EXISTING 6M/SINGLE BRACKET POST AT MOGAPPAIR ROAD &VELLALAR STREET IN WARD 92, ZONE-7",Own Sources,7,2017-18,2018-19 NG/2017-18/11560,Roads,Completed,NG-AMBATTUR,92,4091000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BHARATHIDASAN NAGAR, SENTHAMIZH NAGAR, BHARATHI SALAI 10th BLOCK, Dr. J.J. NAGAR EAST 1St BLOCK 5th, 11th, 18th, 23rd Streets and SEETHAKATHI SALAI IN Dn-92 AND 93, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11734,Parks,Completed,NG-AMBATTUR,92,3722000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT MOGAPPAIR ROAD AND CHURCH ROAD IN DN 92, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14415,Parks,Completed,NG-AMBATTUR,92,2962000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT THIRUVALLUR ROAD IN DN 92, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14417,Parks,Completed,NG-AMBATTUR,92,2258000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT PANNER NAGAR MAIN ROAD IN DN 92, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14418,Parks,Completed,NG-AMBATTUR,92,1288000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT SPARTAN SCHOOL ROAD, BALU NAGAR AND BALU NAGAR MAIN ROAD IN DN 92, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/8716,Storm Water Drain,Completed,NG-AMBATTUR,92,472000,"Desilting of Existing Strom water Drain at Various Street in Dn-92, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8717,Roads,Completed,NG-AMBATTUR,92,150000,"Maintanance to Damaged surface to Various street in Dn-92, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9584,Buildings,Completed,NG-AMBATTUR,92,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER AT PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) at Mogappair Road in Dn-92, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 P/2017-18/6364,Parks,Completed,P-Parks and Playfields,92,3681000,"FORMATION OF NEW PARK AT CHURCH ROAD , MOGAPPIAR IN DN-92, ZONE - VII.",Grants,7,2017-18,2019-20 D/2017-18/6475,Storm Water Drain,Completed,D-Storm Water Drains,93,84691000,"Construction of flood protection wall, canal lining and other Improvements to Nolambur Canal from Mogappair Eri Scheme 3rd Main Road (Ch.2044m) to Cooum River (Ch.2390m) in Nolambur watershed of cooum basin in the expanded areas of Greater Chennai Corporation in Dn.91, Zone -7, Package No. 25F",Loans And Grants,7,2017-18,2019-20 D/2017-18/6905,Storm Water Drain,Completed,D-Storm Water Drains,93,44620000,"Construction of flood protection wall, canal lining & other improvements to Padikuppam canal (from chainage 1853 to 2085) in Padikuppam water shed of Cooum basin in the expanded areas of Greater Chennai Corporation. Padikuppam water shed in division 90,Zone - 7.",Loans And Grants,7,2017-18,2019-20 D/2017-18/6906,Storm Water Drain,Completed,D-Storm Water Drains,93,42870000,"Construction of flood protection wall, canal lining & other improvements to Padikuppam canal (from chainage 2085 to 2307) in Padikuppam water shed of Cooum basin in the expanded areas of Greater Chennai Corporation. Padikuppam water shed in division 93,Zone - 7.",Loans And Grants,7,2017-18,2019-20 L/2017-18/2409,Electrical,Completed,L-Electrical,93,138300,"Proposed new cable replacement of 4x16 sq.mm UG cable of 485 Mtrs for cable damages due to SWD work at Rathnavel Pandian Street, Ward 93, Zone 7",Deposit Works,7,2017-18,2017-18 L/2017-18/6304,Electrical,Completed,L-Electrical,93,889000,"PROVISION FOR CABLE REPLACEMENT FOR 1835 MTRS OF 2X16 SQ.MM AL.UG CABLE FOR EXISTING 54 NOS OF 6M/SINGLE BRACKET POST and 521 MTRS OF 4X16 SQ.MM AL.UG CABLE FOR 16 NOS. OF 6M/SINGLE POST AT GOLDEN GEORGE NAGAR & PADIKUPPAM ,WARD 93, ZONE 7",Own Sources,7,2017-18,2018-19 NG/2017-18/11036,Roads,Completed,NG-AMBATTUR,93,150000,"Temporary Restoration to rain damages roads at Vandiamman Koil Street in Division-93, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/11618,Roads,Completed,NG-AMBATTUR,93,5219000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SICILI PASHBOM STREET IN Dn-90, Unit-20, Zone-7.",Own Sources,7,2017-18,2018-19 NG/2017-18/14426,Parks,Completed,NG-AMBATTUR,93,2676000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT 1st BLOCK 9th STREET, 1st BLOCK 11th STREET TO 17th STREET, 2nd BLOCK 1st STREET AND 2nd BLOCK 26th TO 30th STREET IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14445,Parks,Completed,NG-AMBATTUR,93,166000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT 1st BLOCK 3rd STREET IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14454,Parks,Completed,NG-AMBATTUR,93,465000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT PARI SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14455,Parks,Completed,NG-AMBATTUR,93,664000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT SEETHALAKSHMI STREET IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14456,Parks,Completed,NG-AMBATTUR,93,33000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT VALAYAPATHI SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14457,Parks,Completed,NG-AMBATTUR,93,398000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT SRINIVAS KUMARAN STREET IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14458,Parks,Completed,NG-AMBATTUR,93,465000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT MARAIMALAI ADIKALAR STREET IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14459,Parks,Completed,NG-AMBATTUR,93,498000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT VEERAMA MUNIVAR SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14460,Parks,Completed,NG-AMBATTUR,93,830000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT SEETHAKATHI SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14462,Parks,Completed,NG-AMBATTUR,93,166000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT SEETHAKATHI SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14463,Parks,Completed,NG-AMBATTUR,93,100000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT SEETHAKATHI SALAI 2nd BLOCK APARTMENT IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14467,Parks,Completed,NG-AMBATTUR,93,199000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT PARI SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14468,Parks,Completed,NG-AMBATTUR,93,166000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT VALAYAPATHI SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/14470,Parks,Completed,NG-AMBATTUR,93,1478000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT MARAIMALA ADIKALAR SALAI, Dr. J.J NAGAR EAST 2nd BLOCK TO 4tH BLOCK, VALAYAPATHI SALAI AND PARI SALAI IN DN 93, UNIT 20, ZONE - VII",Own Sources,7,2017-18,2018-19 NG/2017-18/8608,Storm Water Drain,Completed,NG-AMBATTUR,93,480000,"Desilting of Existing Strom water Drain at Various Street in Dn-93, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/8609,Roads,Completed,NG-AMBATTUR,93,150000,"Maintanance to Damaged surface to Various street in Dn-92, Unit -20, Zone-7",Own Sources,7,2017-18,2017-18 NG/2017-18/9585,Buildings,Completed,NG-AMBATTUR,93,2030000,"PROPOSED CONSTRUCTION OF RESOURCES RECOVERY CENTER PROCUREMENT OF MACHINERIES (SHREDDING MACHINE, WEIGHTING MACHINE, SEWING MACHINE AND VEGETABLE CUTTER MACHINE) AT GANGAI AMMAN KOIL STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2017-18,2018-19 BR/2017-18/14249,Road Cut,Completed,BR-Bus Route Roads,94,2360000,"Restoration of Roadcut made by CMWSSB at MTH Road (from 501m Chainage to Villivakkam Police Station) in Dn-94 & 95, Zone-VIII (Challan No.BR/2017-18/0016530)",Deposit Works,8,2017-18,2018-19 D/2017-18/1738,Storm Water Drain,Completed,D-Storm Water Drains,94,988000,Dismantling existing dilapidated 1500x1500mm Storm water drain and Re-Construction of storm water Drain of size 1500x1500mm RCC Box type drain along Sidco nagar 2nd main road From KVP Transport to Kalyana mandapam Dn 94 Zone 8.,Own Sources,8,2017-18,2017-18 D/2017-18/1739,Storm Water Drain,Completed,D-Storm Water Drains,94,988000,Dismantling existing dilapidated 1500x1500mm Storm water drain and Re-Construction of storm water Drain of size 1500x1500mm RCC Box type drain along Sidco nagar 2nd main road From Kalyana Mandapam to Kamachi amman kovil junction Dn 94 Zone 8.,Own Sources,8,2017-18,2017-18 D/2017-18/2243,Storm Water Drain,Completed,D-Storm Water Drains,94,1970000,Demolition of Parapet Wall and Replacing with M.S Grill Gate for de-silting in canals using Robotic multipurpose excavator in various places in Centre Region,Own Sources,8,2017-18,2018-19 L/2017-18/1820,Electrical,Completed,L-Electrical,94,191700,"Replacement of Trailing cable ,Galvanizwd steet wire roap and maintenance work for the 20 , Mtr hight mast at MTH road High mast, Villiakkam in div -94, zone VIII",Own Sources,8,2017-18,2019-20 L/2017-18/1821,Electrical,Completed,L-Electrical,94,190000,"Replacement of Trailing cable ,Galvanizwd steet wire roap and maintenance work for the the 20 , Mtr hight mast at villivakkam burial ground High mast in div -94, zone VIII",Own Sources,8,2017-18,2019-20 NH/2017-18/11561,Roads,Completed,NH-ANNA NAGAR,94,280000,"PROVIDING RMC 30 PATCH AT VARIOUS STREET IN DN 94,U-21,Z-08.",Own Sources,8,2017-18,2019-20 NH/2017-18/1323,Buildings,Completed,Q-Solid Waste Management,94,2005000,"CONSTRUCTION OF COMPOST YARD AT VILLIVAKKAM SERVICE ROAD AND VILLIVAKKAM BURIAL GROUND IN DIV-94, UNIT-21 ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/14166,Roads,Completed,NH-ANNA NAGAR,94,280000,"IMPROVEMENT TO BT ROAD AT RAJAMAGALAM 1ST MAIN ROAD IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14167,Roads,Completed,NH-ANNA NAGAR,94,1838000,"IMPROVEMENT TO BT ROAD AT NORTH HIGH COURT COLONY IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14168,Roads,Completed,NH-ANNA NAGAR,94,1475000,"IMPROVEMENT TO BT ROAD AT BALLIAMMAN KOIL LANE IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14169,Roads,Completed,NH-ANNA NAGAR,94,1082000,"IMPROVEMENT TO BT ROAD AT SIDCO NAGAR 38TH STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14170,Roads,Completed,NH-ANNA NAGAR,94,2991000,"IMPROVEMENT TO BT ROAD AT REDHILLS 2ND STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14171,Roads,Completed,NH-ANNA NAGAR,94,1006000,"IMPROVEMENT TO BT ROAD AT SIVAN KOIL NORTH MADA STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14172,Roads,Completed,NH-ANNA NAGAR,94,374000,"IMPROVEMENT TO BT ROAD AT BALLAIAMMAN KOIL STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14173,Roads,Completed,NH-ANNA NAGAR,94,374000,"IMPROVEMENT TO BT ROAD AT NEHRU NAGAR IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14206,Roads,Completed,NH-ANNA NAGAR,94,440000,"IMPROVEMENT TO THE BT ROAD AT SIDCO NAGAR 91ST STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14208,Roads,Completed,NH-ANNA NAGAR,94,880000,"IMPROVEMENT TO THE BT ROAD AT SIDCO NAGAR 93ST STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14209,Roads,Completed,NH-ANNA NAGAR,94,880000,"IMPROVEMENT TO THE BT ROAD AT DEVAR STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14211,Roads,Completed,NH-ANNA NAGAR,94,468000,"IMPROVEMENT TO THE BT ROAD AT AMMAN KUTTAI 2ND STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14212,Roads,Completed,NH-ANNA NAGAR,94,468000,"IMPROVEMENT TO THE BT ROAD AT AMMAN KUTTAI 3RD STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14213,Roads,Completed,NH-ANNA NAGAR,94,468000,"IMPROVEMENT TO THE BT ROAD AT SOUTH JAGANTHAN NAGAR 2 CROSS STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14214,Roads,Completed,NH-ANNA NAGAR,94,468000,"IMPROVEMENT TO THE BT ROAD AT SOUTH JAGANTHAN NAGAR 4CROSS STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14215,Roads,Completed,NH-ANNA NAGAR,94,561000,"IMPROVEMENT TO THE BT ROAD AT SOUTH JAGANATHAN 5 CROSS STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14216,Roads,Completed,NH-ANNA NAGAR,94,425000,"IMPROVEMENT TO THE BT ROAD AT PADAMANBAN STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14251,Roads,Completed,NH-ANNA NAGAR,94,399000,"IMPROVEMENT TO THE CC ROAD AT SOUTH JAGANATHAN 1ST CROSS STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14253,Roads,Completed,NH-ANNA NAGAR,94,462000,"IMPROVEMENT TO THE CC ROAD AT RAJAMAGALAM 2ND STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14256,Roads,Completed,NH-ANNA NAGAR,94,378000,"IMPROVEMENT TO THE CC ROAD AT AGATHISWARAN KOIL LANE IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14257,Roads,Completed,NH-ANNA NAGAR,94,336000,"IMPROVEMENT TO THE CC ROAD AT SAMIYAR THOTTAM STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14258,Roads,Completed,NH-ANNA NAGAR,94,672000,"IMPROVEMENT TO THE CC ROAD AT SATHYA NAGAR IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14259,Roads,Completed,NH-ANNA NAGAR,94,616000,"IMPROVEMENT TO THE CC ROAD AT BALASUBRAMANIYAN STREET IN DN-94, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/15630,Buildings,Completed,NH-ANNA NAGAR,94,64800,"REPAIR TO BORE IN NNMP SHED SIDCO NAGAR 32ND STREET IN DN 94,U-21,Z-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/17040,Storm Water Drain,Completed,NH-ANNA NAGAR,94,573000,"RESTORATION OF DAMAGE STORM WATER DRAIN AT VARIOUS PLACES IN DIV 94,UNIT-21,ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/17041,Storm Water Drain,Completed,NH-ANNA NAGAR,94,460000,"RESTORATION OF DAMAGE SWD AT VARIOUS STREET IN DIV 94,UNIT-21,ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/17047,Buildings,Completed,NH-ANNA NAGAR,94,500000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DN 94,U-21,Z-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/17048,Buildings,Completed,NH-ANNA NAGAR,94,208000,"RESTORATION OF DAMAGE SCHOOLS AT VARIOUS PLACES IN DN-94, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2018-19 NH/2017-18/17049,Buildings,Completed,NH-ANNA NAGAR,94,306000,RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DIVISION 94 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/2250,Storm Water Drain,Completed,NH-ANNA NAGAR,94,884000,"Desilting swd at various street in dn-94,u-21,z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/2252,Storm Water Drain,Completed,NH-ANNA NAGAR,94,1516000,"Desilting swd at various street in dn-94,u-21,z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/2253,Storm Water Drain,Completed,NH-ANNA NAGAR,94,1450000,"Desilting swd at various street in dn-94,u-21,z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/7313,Roads,Completed,NH-ANNA NAGAR,94,59000,"PROVIDING THERMO PLAST AND STUD FOR SPEED BREAKERS VARIOUS STREET IN DIVITION-94,UNIT-21,ZONE-08",Own Sources,8,2017-18,2017-18 NH/2017-18/7807,Roads,Completed,NH-ANNA NAGAR,94,1990000,"PROVIDING TILE FOR WALKING TRACK, WATER SUPPLY ARRANGEMENT FOR PLANT IN VILLIVAKKAM BURIAL GROUND IN DN-94, U-21, ZONE-8.(MLA FUND)",MLACDS,8,2017-18,2018-19 NH/2017-18/7808,Roads,Completed,NH-ANNA NAGAR,94,1999000,"PROVIDING WALKING TRACK AND HEAVY JUNGLE AND BUSHES IN VILLIVAKKAM BURIAL GROUND IN DN-94, U-21, ZONE-8.(MLA FUND)",MLACDS,8,2017-18,2018-19 NH/2017-18/7817,Roads,Completed,NH-ANNA NAGAR,94,626000,"CONSTRUCTION OF CERMONY HALL IMPROVEMENT CARE TAKER ROOM AND TOILET PLANTING AND GREENERY ARRANGEMENT IN VILLIVAKKAM BURIAL GROUND IN DN-94, U-21, ZONE-8.(MLA FUND)",MLACDS,8,2017-18,2018-19 NH/2017-18/9260,Storm Water Drain,Completed,NH-ANNA NAGAR,94,736000,"MINOR REPAIRS WORK TO SWD AT VARIOUS STREET IN DN-94,U-21,ZONE-8",Own Sources,8,2017-18,2017-18 NH/2017-18/9261,Storm Water Drain,Completed,NH-ANNA NAGAR,94,664000,"MINOR REPAIRS WORK TO SWD AT VARIOUS STREET IN DN-94,U-21,ZONE-8",Own Sources,8,2017-18,2017-18 NH/2017-18/9711,Buildings,Completed,Q-Solid Waste Management,94,2022000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY CENTER WITH BASIC MACHINERIES AT VILLIVAKKAM BURIAL GROUND IN DN 94, UNIT, 21 ZONE 8.",Own Sources,8,2017-18,2018-19 BR/2017-18/13210,Road Cut,Completed,BR-Bus Route Roads,95,2400000,"Restoration of Roadcut made by CMWSSB at MTH Road (from the jn of ICF Signal to 500m Chainage) in Dn-95, Zone-VIII",Deposit Works,8,2017-18,2018-19 NH/2017-18/10865,Storm Water Drain,Completed,NH-ANNA NAGAR,95,106700,"PROVIDING MAN HOLE DOOR AT VARIOUS PLACE IN DN-95,U-21,Z-8",Own Sources,8,2017-18,2018-19 NH/2017-18/11101,Road Cut,Completed,NH-ANNA NAGAR,95,505000,IMPROVEMENT TO THE BT ROAD AT I BLOCK 38TH STREET REACH 2 IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/11104,Road Cut,Completed,NH-ANNA NAGAR,95,219000,IMPROVEMENT TO THE BT ROAD AT W BLOCK 6TH STREET REACH 2 IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/11123,Roads,Completed,NH-ANNA NAGAR,95,480000,IMPROVEMENT TO THE BT ROAD AT KAMBAR COLONY 27TH STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/11124,Roads,Completed,NH-ANNA NAGAR,95,552000,IMPROVEMENT TO THE BT ROAD AT IMAYAM COLONY 2ND STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/11125,Roads,Completed,NH-ANNA NAGAR,95,696000,IMPROVEMENT TO THE BT ROAD AT IMAYAM COLONY 1ST STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/11126,Roads,Completed,NH-ANNA NAGAR,95,512000,IMPROVEMENT TO THE BT ROAD AT I BLOCK 40TH STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/11127,Roads,Completed,NH-ANNA NAGAR,95,320000,IMPROVEMENT TO THE BT ROAD AT RAJIV GANDHI NAGAR 3RD STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/11128,Roads,Completed,NH-ANNA NAGAR,95,1656000,IMPROVEMENT TO THE BT ROAD AT I BLOCK 28TH STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/11129,Roads,Completed,NH-ANNA NAGAR,95,520000,IMPROVEMENT TO THE B T ROAD AT I BLOCK 30th STREET IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/11176,Parks,Completed,NH-ANNA NAGAR,95,183000,"ANNUAL MAINTENANCE WORK AT I BLOCK 38th STREET PARK IN DIVISION-95, UNIT-21, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/11177,Parks,Completed,NH-ANNA NAGAR,95,275000,"ANNUAL MAINTENANCE WORK AT I BLOCK 2nd STREET PARK IN DIVISION-95, UNIT-21, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/12900,Parks,Completed,NH-ANNA NAGAR,95,345000,IMPROVEMENTS TO GANDHI PARK at W BLOCK C SECTOR IN DIV -95. UNIT-21 ZONE-8,Own Sources,8,2017-18,2018-19 NH/2017-18/13190,Parks,Completed,NH-ANNA NAGAR,95,285000,"Annual maintenance of park at W Block C sector Gandhi park in Dn.95,Unit-21,Zone-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1329,Buildings,Completed,Q-Solid Waste Management,95,1330000,"CONSTRUCTION OF COMPOST YARD AT IMAYAM KUDIRUPPU IN DIV-95, UNIT-21, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/14879,Road Cut,Completed,NH-ANNA NAGAR,95,170000,IMPROVEMENT TO THE BT ROAD AT I BLOCK 35TH STREET IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/15496,Road Cut,Completed,NH-ANNA NAGAR,95,1309000,IMPROVEMENT TO BT ROAD AT THANTHONIAMMAN MAIN STREET IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/15497,Road Cut,Completed,NH-ANNA NAGAR,95,939000,IMPROVEMENT TO BT ROAD AT THANTHONIAMMAN 1ST STREET IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/15498,Road Cut,Completed,NH-ANNA NAGAR,95,513000,IMPROVEMENT TO BT ROAD AT ICF ANNEX IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/15499,Road Cut,Completed,NH-ANNA NAGAR,95,670000,IMPROVEMENT TO BT ROAD AT MANNADI OTHAVADI STREET IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/15500,Road Cut,Completed,NH-ANNA NAGAR,95,152000,IMPROVEMENT TO BT ROAD AT AGATHIYAR NAGAR 13TH STREET IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/16656,Buildings,Completed,NH-ANNA NAGAR,95,46800,RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN IN DIV - 95. UNIT - 21 ZONE - 8,Own Sources,8,2017-18,2018-19 NH/2017-18/16741,Storm Water Drain,Completed,NH-ANNA NAGAR,95,54000,RESTORATION OF DAMAGE SWD AT VARIOUS PLACES IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/16785,Buildings,Completed,NH-ANNA NAGAR,95,275000,RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2018-19 NH/2017-18/16790,Roads,Completed,NH-ANNA NAGAR,95,2986000,"LAYING CEMENT CONCRETE ROAD USING RMC AT LAXMI NAGAR EXTENTION 1ST , 2ND STREET AND 3RD STREET AND W BLOCK IN DIVISION 95 UNIT 21 ZONE 08 (MLA FUND)",MLACDS,8,2017-18,2018-19 NH/2017-18/16802,Buildings,Completed,NH-ANNA NAGAR,95,2212000,LAYING CEMENT CONCRETE ROAD AT WITH RMC 40 AT LAKSHMIPURAM 2ND STREET IN DIVISION 95 UNIT 21 ZONE 08,MLACDS,8,2017-18,2018-19 NH/2017-18/16807,Buildings,Completed,NH-ANNA NAGAR,95,234000,"LAYING CEMENT CONCRETE ROAD RMC 40 AT SIYALAM CANAL AND SIYALAM 2ND CROSS STREET , SIYALAM 3RD CROSS STREET IN DIVISION 95 UNIT 21 ZONE 08 (MLA FUND)",MLACDS,8,2017-18,2018-19 NH/2017-18/17100,Buildings,Completed,NH-ANNA NAGAR,95,165000,PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS TO THIRU NAGAR PARK IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2019-20 NH/2017-18/17695,Parks,Completed,NH-ANNA NAGAR,95,859000,"MAINTENANCE OF THIRU NAGAR PARK AT 13TH BLOCK, 11TH STREET FOR A PERIOD OF ONE YEAR IN DN-95,UNIT-21,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17696,Parks,Completed,NH-ANNA NAGAR,95,274000,"MAINTENANCE OF PARK AT I BLOCK 38TH STREET FOR A PERIOD OF ONE YEAR IN DN-95,UNIT-21,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17697,Parks,Completed,NH-ANNA NAGAR,95,555000,"MAINTENANCE OF PARK AT I BLOCK 2ND STREET FOR A PERIOD OF ONE YEAR IN DN-95,UNIT-21,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17698,Parks,Completed,NH-ANNA NAGAR,95,612000,"MAINTENANCE OF PARK AT W BLOCK C SECTOR 2ND STREET FOR A PERIOD OF ONE YEAR IN DN-95,UNIT-21,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/2054,Roads,Completed,NH-ANNA NAGAR,95,2951076,PROVIDING ALL ROUND FOOTPATH WITH STEPS AND ELECTRICAL ARRANGEMENT OF VALAIYAN KULAM (EAST SIDE) IN MANNADI OTHAVADAI STREET IN DIVISION 95 UNIT 21 ZONE 08 (MLA FUND 2017-18),MLACDS,8,2017-18,2018-19 NH/2017-18/2055,Parks,Completed,NH-ANNA NAGAR,95,1724000,PROVIDING FENCING WORK FOR GRACE AREA IN THIRU NAGAR PARK IN DIVISION 95 UNIT 21 ZONE 08 (MLA FUND 2017-18),MLACDS,8,2017-18,2018-19 NH/2017-18/2056,Road Cut,Completed,NH-ANNA NAGAR,95,505000,IMPROVEMENT TO THE BT ROAD AT I BLOCK 38TH STREET REACH 1 IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/2057,Road Cut,Completed,NH-ANNA NAGAR,95,237000,IMPROVEMENT TO THE BT ROAD AT I BLOCK 37TH STREET REACH 1 IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/2058,Road Cut,Completed,NH-ANNA NAGAR,95,335000,IMPROVEMENT TO THE BT ROAD AT VASANTHAM COLONY 2ND MAIN ROAD IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/2261,Storm Water Drain,Completed,NH-ANNA NAGAR,95,414000,"Desilting swd at various street in dn-95,u-21,z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/2262,Buildings,Completed,NH-ANNA NAGAR,95,175000,PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS TO MTH ANNEX ROAD PC IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2019-20 NH/2017-18/2263,Buildings,Completed,NH-ANNA NAGAR,95,200000,PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS TO DIVISION OFFICE CAMPUS IN DIVISION 95 UNIT 21 ZONE 08,Own Sources,8,2017-18,2019-20 NH/2017-18/2264,Road Cut,Completed,NH-ANNA NAGAR,95,103000,IMPROVEMENT TO THE BT ROAD AT 20TH MAIN ROAD IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/2420,Parks,Completed,NH-ANNA NAGAR,95,440000,"ANNUAL MAINTENANCE OF PARK AT THIRU NAGAR PARK (ONE YEAR) IN DN.95,UNIT-21,ZONE-8.(By Employed Qualified Horticulturist Only)..",Own Sources,8,2017-18,2018-19 NH/2017-18/2421,Buildings,Completed,NH-ANNA NAGAR,95,129000,"PROVIDING BARRICADING AT THIRUVENKADAYA STREET,NEW AVADI MAIN ROAD IN DIV 95 UNIT 21 ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/2673,Roads,Completed,NH-ANNA NAGAR,95,1137000,"PROVIDING COMPOUND WALL AND PLAY APPARATUS FOR AGITHIYAR NAGAR 12TH STREET AND 8TH STREET PLAY GROUND IN DN-95, UNIT-21, ZONE-08 (MLA FUND 2017-18)",MLACDS,8,2017-18,2017-18 NH/2017-18/7035,Roads,Completed,NH-ANNA NAGAR,95,2931076,PROVIDING ALL ROUND FOOTPATH WITH STEPS AND ELECTRICAL ARRANGEMENT OF VALAIYAN KULAM (SOUTH SIDE) IN MANNADI OTHAVADAI STREET IN DIVISION 95 UNIT 21 ZONE 08 (MLA FUND 2017-18),MLACDS,8,2017-18,2018-19 NH/2017-18/7036,Roads,Completed,NH-ANNA NAGAR,95,2976076,PROVIDING ALL ROUND FOOTPATH WITH STEPS AND ELECTRICAL ARRANGEMENT OF VALAIYAN KULAM (WEST SIDE) IN MANNADI OTHAVADAI STREET IN DIVISION 95 UNIT 21 ZONE 08 (MLA FUND 2017-18),MLACDS,8,2017-18,2018-19 NH/2017-18/7318,Roads,Completed,NH-ANNA NAGAR,95,159000,"PROVIDING THERMO PLAST AND STUDDS FOR SPEED BREAKERS VARIOUS STREET IN DIVISION-95, UNIT-21, ZONE-08",Own Sources,8,2017-18,2017-18 NH/2017-18/7735,Road Cut,Completed,NH-ANNA NAGAR,95,908000,IMPROVEMENT TO BT ROAD AT RAJIV GANDHI 1ST & 2ND STREET IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/8881,Storm Water Drain,Completed,NH-ANNA NAGAR,95,100000,"MINOR REPAIRS TO SWD AT VARIOUS STREET IN DIVISION-95, UNIT-21, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/9562,Road Cut,Completed,NH-ANNA NAGAR,95,237000,IMPROVEMENT TO THE BT ROAD AT I BLOCK 37TH STREET REACH 2 IN DIV 95 UNIT 21 ZONE 8,Own Sources,8,2017-18,2018-19 B/2017-18/11636,Buildings,Completed,B-Buildings,96,3739000,"REPAIRS AND IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT PALAVOYAL STREET ,AYANAVARAM IN DN-96, U-21.,ZONE - 8",Own Sources,8,2017-18,2019-20 B/2017-18/15575,Buildings,Completed,B-Buildings,96,887000,"Supplying and fixing of Two seater bench cum tables for propsed smart classes in CHSS Ayana varam in DN 96 Zone 8, CGHSS Pulla avenue in DN 102 Zone 8, CBHSS G.Koil street in DN 104 Zone 8and CHSS Subbu rayan street in DN 107 Zone 8",Own Sources,8,2017-18,2018-19 NH/2017-18/11132,Buildings,Completed,NH-ANNA NAGAR,96,2144000,"IMPROVEMENT WORKS TO THE MATERNITY AND CHILD HOSPITAL AT UNITED INDIA NAGAR, AYANVARAM, DIVISION-96, UNIT-21,, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/12110,Playfields,Completed,NH-ANNA NAGAR,96,90000,"PROVIDING AND FIXING FENCING FOR ROAD SIDE CORPORATION LAND AT NEW AVADI ROAD (SOUTHERN SIDE) FROM JN OF GANDHI NAGAR SINGAL IN DN-96, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2018-19 NH/2017-18/12814,Buildings,Completed,NH-ANNA NAGAR,96,330000,"MINOR REPAIR WORKS TO MARKET COMPLEX AT PALAVAYAL STREET, AYANAVARAM, IN WARD-96, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2018-19 NH/2017-18/13154,Buildings,Completed,NH-ANNA NAGAR,96,245000,"IMPROVEMENTS WORKS TO THE BLOOD STORAGE CENTRE AT 24 HOURS MATERNITY HOSPITAL, UNITED INDIA NAGAR , AYANAVARAM, DN-96, UINT-21, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/1316,Buildings,Completed,Q-Solid Waste Management,96,2680000,"CONSTRUCTION OF COMPOST YARD AT KONOOR HIGH ROAD NEAR AMMAUNAVAGAM ,SUNNYVEL AND V.P COLONY IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2017-18,2018-19 NH/2017-18/14177,Buildings,Completed,NH-ANNA NAGAR,96,290000,"MINOR REPAIR WORKS IN AMMA UNAVAGAM AND ELECTRICAL AE OFFICE (SAME BUILDING) AT KONNUR HIGH ROAD, AYANAVARAM, DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/14630,Buildings,Completed,NH-ANNA NAGAR,96,237000,"MINOR REPAIR WORKS TO PUBLIC CONVENIENCE AT ICF SIGNAL IN WARD-96, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2018-19 NH/2017-18/16705,Buildings,Completed,NH-ANNA NAGAR,96,576000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN WARD-96, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2018-19 NH/2017-18/16780,Storm Water Drain,Completed,NH-ANNA NAGAR,96,186000,"RESTORATION OF DAMAGE SWD AT VARIOUS PLACES IN DIVISION-96, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2018-19 NH/2017-18/17332,Buildings,Completed,NH-ANNA NAGAR,96,41000,"REPAIR AND IMPROVEMENT AT JEEVA PARK IN DN-96,U-21,Z-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/17688,Parks,Completed,NH-ANNA NAGAR,96,221000,"MAINTENANCE OF PARK AT KONNUR HIGH ROAD (OSR LAND PARK) FOR A PERIOD OF ONE YEAR IN DN-96,UNIT-21,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/17689,Parks,Completed,NH-ANNA NAGAR,96,216000,"MAINTENANCE OF PARK AT UNITED INDIA NAGAR (JEEVA PARK) FOR A PERIOD OF ONE YEAR IN DN-96,UNIT-21,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/2225,Buildings,Completed,NH-ANNA NAGAR,96,680000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/3587,Buildings,Completed,NH-ANNA NAGAR,96,176000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENT FOR GANDHI NAGAR PC IN DIVISION - 96, UNIT - 21, ZONE - 8.",Own Sources,8,2017-18,2019-20 NH/2017-18/3590,Buildings,Completed,NH-ANNA NAGAR,96,176000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENT FOR TAGORE NAGAR PC IN DIVISION-96,UNIT- 21, ZONE - 8",Own Sources,8,2017-18,2019-20 NH/2017-18/3593,Buildings,Completed,NH-ANNA NAGAR,96,215000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENT FOR KUNOOR HIGH ROAD PC (OPP AMMA UNAVAGAM) IN DIVISION-96,UNIT-21,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/4357,Buildings,Completed,NH-ANNA NAGAR,96,398000,"IMPROVEMENT WORKS TO THE CEMENT CONCRETE ROAD AT DURAISAMY STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4360,Road Cut,Completed,NH-ANNA NAGAR,96,469000,"IMPROVEMENT TO BT ROAD AT SSV KOIL 1ST STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4361,Road Cut,Completed,NH-ANNA NAGAR,96,516000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT KK NAGAR 5TH STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4362,Road Cut,Completed,NH-ANNA NAGAR,96,413000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT VP COLONY 1ST CROSS STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4363,Road Cut,Completed,NH-ANNA NAGAR,96,688000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT TAGORE NAGAR 3RD STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4365,Road Cut,Completed,NH-ANNA NAGAR,96,671000,"IMPROVEMENT TO BT ROAD AT APPADURAI 1ST STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4366,Road Cut,Completed,NH-ANNA NAGAR,96,671000,"IMPROVEMENT TO BT ROAD AT APPADURAI MAIN STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4368,Road Cut,Completed,NH-ANNA NAGAR,96,1006000,"IMPROVEMENT TO BT ROAD AT APPADURAI 2ND STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/4370,Road Cut,Completed,NH-ANNA NAGAR,96,506000,"IMPROVEMENT TO BT ROAD AT UNITED INDIA NAGAR 3RD STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7322,Roads,Completed,NH-ANNA NAGAR,96,136000,"PROVIDING THERMO PLAST AND STUD FOR SPEED BREAKERS VARIOUS STREET IN DIVITION-96,UNIT-21,ZONE-08",Own Sources,8,2017-18,2017-18 NH/2017-18/8878,Storm Water Drain,Completed,NH-ANNA NAGAR,96,200000,"REPAIR AND IMPROVEMENT TO STORM WATER DRAIN AT VARIOS STREET IN DN-96, U-21, Z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/9236,Buildings,Completed,NH-ANNA NAGAR,96,170000,"PROVIDING IMPROVEMENTS WORK IN SMART CLASS IN PALAVAYAL SCHOOL AT DIVISION 96, UNIT 21, ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/9598,Parks,Completed,NH-ANNA NAGAR,96,173000,"MAINTENANCE OF OSR LAND PARK AT KONNUR HIGH ROAD FOR ONE YEAR IN DN-96,U-21,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/9600,Parks,Completed,NH-ANNA NAGAR,96,168000,"MAINTENANCE OF JEEVA PARK FOR ONE YEAR IN DN-96,U-21,Z-08",Own Sources,8,2017-18,2018-19 L/2017-18/6987,Electrical,Completed,L-Electrical,97,198800,"WORK: Replacement of 510 Mtrs of 2 X 16 SQ.MM U.G .(ALUM)Cable at Thiru.Vi.Ka.Street , Kamarajar Street and Sivalingam Street in Division - 97 ,Zone-VIII areas..",Own Sources,8,2017-18,2018-19 NH/2017-18/0528,Buildings,Completed,NH-ANNA NAGAR,97,200000,"REPAIRS AND MAINTENANCE WORK IN AMMA UNNAVAGAM AT ATHI ANDRA NAGAR AND VELLALA STREET WARD-97,UNIT-21, ZONE-VIII.",Own Sources,8,2017-18,2017-18 NH/2017-18/0909,Buildings,Completed,NH-ANNA NAGAR,97,445000,"REPAIR AND IMPROVEMENT WORKS IN CPS VELLLA STREET DN-97, UNIT-21, ZONE-08",Own Sources,8,2017-18,2017-18 NH/2017-18/13249,Parks,Completed,NH-ANNA NAGAR,97,267000,"Annual Maintenance of park at Vallala Street Park (By employing qualified horticulturist for only) in Dn.97,Unit-21,Zone-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13251,Parks,Completed,NH-ANNA NAGAR,97,130000,"Annual Maintenance of park at pachaikal Veeraswamy Street (By employing qualified horticulturist for only) in Dn.97,Unit-21,Zone-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1332,Buildings,Completed,Q-Solid Waste Management,97,665000,"CONSTRUCTION OF COMPOST YARD AT THANTHI PERIYAR NAGAR IN DIV-97, UNIT-21 ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/14179,Roads,Completed,NH-ANNA NAGAR,97,401000,"IMPROVEMENT WORK BT ROAD AT P.E.KOIL NORTH MADA STREET (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14180,Roads,Completed,NH-ANNA NAGAR,97,187000,"IMPROVEMENT WORK BT ROAD AT P.A.KOIL STREET (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14181,Roads,Completed,NH-ANNA NAGAR,97,555000,"IMPROVEMENT WORK BT ROAD AT VELLALA STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14182,Roads,Completed,NH-ANNA NAGAR,97,999000,"IMPROVEMENT WORK BT ROAD AT SOLAI STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14183,Roads,Completed,NH-ANNA NAGAR,97,353000,"IMPROVEMENT WORK BT ROAD AT VEERASAMY 1ST STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14184,Roads,Completed,NH-ANNA NAGAR,97,158000,"IMPROVEMENT WORK BT ROAD AT PACHAIKKAL VEERASAMY STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14185,Roads,Completed,NH-ANNA NAGAR,97,747000,"IMPROVEMENT WORK BT ROAD AT P.A.KOIL STREET (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14186,Roads,Completed,NH-ANNA NAGAR,97,1036000,"IMPROVEMENT WORK BT ROAD AT P.E.KOIL NORTH MADA STREET (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14187,Roads,Completed,NH-ANNA NAGAR,97,655000,"IMPROVEMENT WORK BT ROAD AT P.E.KOIL WEST MADA STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14188,Roads,Completed,NH-ANNA NAGAR,97,226000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT BHATTACHARY STREET (R3) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14189,Roads,Completed,NH-ANNA NAGAR,97,240000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT CHELLIAMMAN KOIL 2ND LANE IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14190,Roads,Completed,NH-ANNA NAGAR,97,138000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT CHELLIAMMAN KOIL 1ST LANE IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14191,Roads,Completed,NH-ANNA NAGAR,97,260000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT VELLALA STREET LANE (R3) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14192,Roads,Completed,NH-ANNA NAGAR,97,137000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT ELUMALAI STREET LANE IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14193,Roads,Completed,NH-ANNA NAGAR,97,48000,"IMPROVEMENT WORK CC ROAD AT BHATTACHARY STREET (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14194,Roads,Completed,NH-ANNA NAGAR,97,192000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT DURAISAMY STREET LANE IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14195,Roads,Completed,NH-ANNA NAGAR,97,123000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT VELLALA STREET LANE (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14196,Roads,Completed,NH-ANNA NAGAR,97,152000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT SOLAI 3RD STREET LANE IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14197,Roads,Completed,NH-ANNA NAGAR,97,227000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT SEETHATHOPU STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14198,Roads,Completed,NH-ANNA NAGAR,97,171000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE AT P.A KOIL LANE (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14199,Roads,Completed,NH-ANNA NAGAR,97,310000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT PERIYAR SALAI HOUSING BOARD (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14200,Roads,Completed,NH-ANNA NAGAR,97,777000,"IMPROVEMENT WORK TO THE CEMENT CONCRETE ROAD AT SOLAI 3RD STREET (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16749,Buildings,Completed,NH-ANNA NAGAR,97,300000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16787,Storm Water Drain,Completed,NH-ANNA NAGAR,97,135000,"RESTORATION OF DAMAGE SWD AT VARIOUS PLACES IN DIV-97, UNIT-21, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/17690,Parks,Completed,NH-ANNA NAGAR,97,205000,"MAINTENANCE OF PARK AT PACHAIKAL VEERASWAMY STREET FOR A PERIOD OF ONE YEAR IN DN-97,UNIT-21,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/17691,Parks,Completed,NH-ANNA NAGAR,97,574000,"MAINTENANCE OF PARK AT VELLALA STREET FOR A PERIOD OF ONE YEAR IN DN-97,UNIT-21,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/3182,Buildings,Completed,NH-ANNA NAGAR,97,110000,"REPAIRS AND MAINTENANCE WORKS IN DIVISION OFFICE AT SOLAI STREET AND AMMA UNAVAGAM AT PERIYAR SALAI IN DN-97, UNIT-21, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/7327,Roads,Completed,NH-ANNA NAGAR,97,199000,"PROVIDING THERMOPLASTIC PAINT AND ROAD STUDS FOR SPEED BREAKERS AT VARIOUS STREETS IN WARD-97, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2017-18 NH/2017-18/7812,Roads,Completed,NH-ANNA NAGAR,97,74000,"IMPROVEMENT WORK BT ROAD AT VEERASAMY STREET IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7822,Roads,Completed,NH-ANNA NAGAR,97,275000,"IMPROVEMENT WORKS TO THE CC ROAD AT CHELLIAMMAN KOIL 1ST STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7823,Roads,Completed,NH-ANNA NAGAR,97,379000,"IMPROVEMENT WORKS TO THE CC ROAD AT CHETTY STREET LANE IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7824,Roads,Completed,NH-ANNA NAGAR,97,206000,"IMPROVEMENT WORKS TO THE CC ROAD AT NAGASWARA GURUSWAMY STREET (R2) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7825,Roads,Completed,NH-ANNA NAGAR,97,206000,"IMPROVEMENT WORKS TO THE CC ROAD AT VELLALAR STREET LANE (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7826,Roads,Completed,NH-ANNA NAGAR,97,206000,"IMPROVEMENT WORKS TO THE CC ROAD AT BHOOPATHY NAGAR CROSS STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7827,Roads,Completed,NH-ANNA NAGAR,97,241000,"IMPROVEMENT WORKS TO THE CC ROAD AT NAGESWARA GURUSWAMY STREET (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7828,Roads,Completed,NH-ANNA NAGAR,97,69000,"IMPROVEMENT WORKS TO THE CC ROAD AT CHELLIAMMAM KOIL STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7829,Roads,Completed,NH-ANNA NAGAR,97,54000,"IMPROVEMENT WORKS TO THE CC ROAD AT BHATTACHARY STREET (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7830,Roads,Completed,NH-ANNA NAGAR,97,929000,"IMPROVEMENT WORKS TO THE CC ROAD AT SOLAI 3RD STREET (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7831,Roads,Completed,NH-ANNA NAGAR,97,104000,"IMPROVEMENT WORKS TO THE CC ROAD AT P.E.KOIL 2ND STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7832,Roads,Completed,NH-ANNA NAGAR,97,104000,"IMPROVEMENT WORKS TO THE CC ROAD AT P.E.KOIL 1ST STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7833,Roads,Completed,NH-ANNA NAGAR,97,104000,"IMPROVEMENT WORKS TO THE CC ROAD AT P.A. KOIL LANE (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7834,Roads,Completed,NH-ANNA NAGAR,97,619000,"IMPROVEMENT WORKS TO THE CC ROAD AT THIRUPACHISWARAR STREET IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7835,Roads,Completed,NH-ANNA NAGAR,97,206000,"IMPROVEMENT WORKS TO THE CC ROAD AT PERIYAR SALAI HOUSING BOARD (R1) IN DIV - 97, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7836,Roads,Completed,NH-ANNA NAGAR,97,2040000,"IMPROVEMENT TO THE BT ROAD AT PERIYAR NAGAR IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7837,Roads,Completed,NH-ANNA NAGAR,97,461000,"IMPROVEMENT WORK TO THE CC ROAD AT P.E.KOIL NORTH MADA STREET LANE IN DIV - 97, UNIT - 21, ZONE -8",Own Sources,8,2017-18,2018-19 NH/2017-18/7838,Roads,Completed,NH-ANNA NAGAR,97,728000,"IMPROVEMENT TO THE BT ROAD AT GOPAL PILLAI NAGAR IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7839,Roads,Completed,NH-ANNA NAGAR,97,280000,"IMPROVEMENT TO THE BT ROAD AT MUTHAMMAN KOIL 1ST STREET IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7840,Roads,Completed,NH-ANNA NAGAR,97,1200000,"IMPROVEMENT TO THE BT ROAD AT P.E.KOIL MAIN STREET IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/8682,Storm Water Drain,Completed,NH-ANNA NAGAR,97,95000,"MINOR REPAIR WORK OF STORM WATER DRAIN AT VELLALA STREET IN WARD-97, UNIT-21, ZONE-VIII",Own Sources,8,2017-18,2017-18 NH/2017-18/0032,Electrical,Completed,NH-ANNA NAGAR,98,306000,"REPAIR AND MAINTENANCE WORK AT MULTI PURPOSE HALLS IN AMBEDKAR NAGAR 2ND STREET, PUTHU NAGAR 4TH STREET AND 4TH CROSS STREET AT DN-98, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/1341,Buildings,Completed,Q-Solid Waste Management,98,1995000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT SAMYDASPURAM,RAJIV STREET AND TNHB AYNAVARAM MAIN ROAD IN DIVISION-98,UNIT-23,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/14268,Roads,Completed,NH-ANNA NAGAR,98,480000,"IMPROVEMENT WORK BT ROAD AT RANGAYA STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14269,Roads,Completed,NH-ANNA NAGAR,98,134000,"IMPROVEMENT WORK BT ROAD AT NARAYANA STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14270,Roads,Completed,NH-ANNA NAGAR,98,279000,"IMPROVEMENT WORK BT ROAD AT PAPAMMAL STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14271,Roads,Completed,NH-ANNA NAGAR,98,413000,"IMPROVEMENT TO CC ROAD AT LOCK STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14272,Roads,Completed,NH-ANNA NAGAR,98,688000,"IMPROVEMENT TO CC ROAD AT C.K. STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14273,Roads,Completed,NH-ANNA NAGAR,98,467000,"IMPROVEMENT TO CC ROAD AT D.B.SHANMUGAM STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14274,Roads,Completed,NH-ANNA NAGAR,98,172000,"IMPROVEMENT TO CC ROAD AT DR.ABMIKAR NAGAR 3RD STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14275,Roads,Completed,NH-ANNA NAGAR,98,220000,"IMPROVEMENT TO CC ROAD AT KAMARAJ NAGAR IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14276,Roads,Completed,NH-ANNA NAGAR,98,413000,"IMPROVEMENT TO CC ROAD AT PALANIYAPPA 2ND STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14277,Roads,Completed,NH-ANNA NAGAR,98,69000,"IMPROVEMENT TO CC ROAD AT PUMPING STATION ROAD IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14278,Roads,Completed,NH-ANNA NAGAR,98,619000,"IMPROVEMENT TO CC ROAD AT DAVID PURAM IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16871,Buildings,Completed,NH-ANNA NAGAR,98,356000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIV-98, UNIT-23, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16894,Buildings,Completed,NH-ANNA NAGAR,98,260000,"RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DIV-98, UNIT-23, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16916,Storm Water Drain,Completed,NH-ANNA NAGAR,98,97500,"RESTORATION OF DAMAGE STORM WATER DRAIN AT VARIOUS PLACES IN DIV-98, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/17298,Buildings,Completed,Q-Solid Waste Management,98,600000,"CONSTRUCTION OF BIOGAS PLANT AT NEW AMMA UNAVAGAM (AYANAVARAM ROAD) IN DIV-98, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/7297,Roads,Completed,NH-ANNA NAGAR,98,275000,"IMPROVEMENT TO CEMENT CONCRETE ROAD AT NEELAKANDAN STREET IN DIV - 98, UNIT - 21, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7315,Roads,Completed,NH-ANNA NAGAR,98,356000,"PROVIDING THERMOPLASTIC COMPOUND AND REFLECTIVE PAVEMENT FOR SPEED BREAKERS AT VARIOUS STREET IN DIV - 98, U - 23, Z - 8",Own Sources,8,2017-18,2017-18 NH/2017-18/8546,Storm Water Drain,Completed,NH-ANNA NAGAR,98,750000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-98,U-23,Z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/9092,Storm Water Drain,Completed,NH-ANNA NAGAR,98,450000,"REPAIRS AND IMPROVEMENTS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DN-98,U-23,Z-8",Own Sources,8,2017-18,2017-18 BR/2017-18/8048,Road Cut,Completed,BR-Bus Route Roads,99,1130000,"Restoration of roadcut made by CMWSSB at Anna Nagar 4th Avenue from the jn of 100 ft road to the jn of 13th main road in Dn - 99, Zone - 8(Chellan No: BR/2017-18/0007229)",Deposit Works,8,2017-18,2018-19 L/2017-18/1089,Electrical,Completed,L-Electrical,99,675000,":Removal 4 nos oh post , 12 nos of 8 mtr octagonal post, supply of 4 nos of 8 mtr octagonal post Erection of 16 nos 8 mtr octagonal Lamp post and Laying of 3 1/2X25 Sqmm Aluminium cable 450 mtr for strom water work forming by high ways Department at Thirumangalam inner rink road in Dn-99,Zone-VIII area",Deposit Works,8,2017-18,2018-19 L/2017-18/11572,Electrical,Completed,L-Electrical,99,196200,"Replacement of 15 Nos. of Existing single Arch Bracket by 2 mtr GI Double Straight Bracket and 266 MTR 3 1/2 X 25 sq. mm. cable laying at Thirumangalam Inner Ring Road in Div. 99, zone - VIII.",Own Sources,8,2017-18,2018-19 L/2017-18/4132,Electrical,Completed,L-Electrical,99,985300,"Provision of 32 Nos 6 mtr lamp post with 1 mtr straight bracket and 1056 mtr 2 X 16 sq mm cable laying at Thirumoolar colony in div -99 , zone - 8",Own Sources,8,2017-18,2017-18 L/2017-18/8412,Electrical,Completed,L-Electrical,99,166500,"Replacement of 2 Nos of kiosk pillar box and Erection of 1 no kiosk pillar box at thirumangalam main road , 13 th main road and Thirumoolar colony in Annanagar west in Division - 99 Zone - 8",Own Sources,8,2017-18,2018-19 NH/2017-18/13227,Roads,Completed,NH-ANNA NAGAR,99,344000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NEHRU NAGAR 2ND STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13228,Roads,Completed,NH-ANNA NAGAR,99,344000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NEHRU NAGAR 3RD STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13229,Roads,Completed,NH-ANNA NAGAR,99,344000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NEHRU NAGAR 4TH STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13230,Roads,Completed,NH-ANNA NAGAR,99,344000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NEHRU NAGAR 5TH STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13231,Roads,Completed,NH-ANNA NAGAR,99,480000,"IMPROVEMENTS TO BT ROAD AT VALLALAR STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13232,Roads,Completed,NH-ANNA NAGAR,99,469000,"IMPROVEMENTS TO BT ROAD AT ADISANKARAR STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13233,Roads,Completed,NH-ANNA NAGAR,99,421000,"IMPROVEMENTS TO BT ROAD AT VIVEKANANDAR STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13234,Roads,Completed,NH-ANNA NAGAR,99,18100,"IMPROVEMENTS TO BT ROAD AT PONNI COLONY MAIN ROAD IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13235,Roads,Completed,NH-ANNA NAGAR,99,1207000,"IMPROVEMENTS TO BT ROAD AT 13TH MAIN ROAD IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13236,Roads,Completed,NH-ANNA NAGAR,99,1207000,"IMPROVEMENTS TO BT ROAD AT 14TH MAIN ROAD IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13237,Roads,Completed,NH-ANNA NAGAR,99,201000,"IMPROVEMENTS TO BT ROAD AT Y BLOCK 4TH STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13238,Roads,Completed,NH-ANNA NAGAR,99,1006000,"IMPROVEMENTS TO BT ROAD AT Y BLOCK 6TH STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13239,Roads,Completed,NH-ANNA NAGAR,99,1006000,"IMPROVEMENTS TO BT ROAD AT Y BLOCK 3RD STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13240,Roads,Completed,NH-ANNA NAGAR,99,201000,"IMPROVEMENTS TO BT ROAD AT Y BLOCK 5TH STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/16305,Roads,Completed,NH-ANNA NAGAR,99,1420000,"RESTORATION OF ROAD CUT MADE BY TNEB AT 13TH MAIN ROAD IN DIVISION 99,UNIT-21,ZONE-8",Deposit Works,8,2017-18,2018-19 NH/2017-18/16307,Roads,Completed,NH-ANNA NAGAR,99,1420000,"RESTORATION OF ROAD CUT MADE BY TNEB AT 14TH MAIN ROAD IN DIVISION 99,UNIT-21,ZONE-8",Deposit Works,8,2017-18,2018-19 NH/2017-18/16617,Buildings,Completed,NH-ANNA NAGAR,99,87600,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DN -99, UNIT -21, ZONE -08",Own Sources,8,2017-18,2018-19 NH/2017-18/17270,Buildings,Completed,NH-ANNA NAGAR,99,60000,"IMPROVEMENT TO THE ANGANWADI AT THIRUVALLUVAR STREET IN DIV-99 UNIT-21, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/17271,Storm Water Drain,Completed,NH-ANNA NAGAR,99,17500,"PROVIDING LAYING INTER CONNECTION PIPE FOR STORM WATER DRAIN AT H-BLOCK 24TH STREET IN DIV-99, UNIT-21, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/17272,Buildings,Completed,NH-ANNA NAGAR,99,166000,"PROVIDING FENCING AT J-BLOCK 16TH STREET IN DIV-99, UNIT-21, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/17273,Buildings,Completed,NH-ANNA NAGAR,99,75000,"PROVIDING FENCING AT 6TH AVENUE DE-COMPOST YARD IN DIV-99, UNIT-21, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/17699,Parks,Completed,NH-ANNA NAGAR,99,682000,"MAINTENANCE OF PARK AT 15TH MAIN ROAD (R.B.I) RANGANATHAN GARDEN FOR A PERIOD OF ONE YEAR IN DN-99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17700,Parks,Completed,NH-ANNA NAGAR,99,703000,"MAINTENANCE OF PARK AT 15TH MAIN ROAD (BPC) RANGANATHAN GARDEN FOR A PERIOD OF ONE YEAR IN DN-99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/2265,Storm Water Drain,Completed,NH-ANNA NAGAR,99,761000,"Desilting swd at various street in dn-99,u-21,z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/2844,Parks,Completed,NH-ANNA NAGAR,99,325000,"ANNUAL MAINTENANCE OF PARK AT 15TH MAIN ROAD PARK (ONE YEAR) IN DIVISION 99,UNIT -21,ZONE-08.(BY EMPLOYED QUALIFIED HORTICULTURIST ONLY)",Own Sources,8,2017-18,2018-19 NH/2017-18/2846,Parks,Completed,NH-ANNA NAGAR,99,395000,ANNUAL MAINTENANCE OF PARK AT ( O.S.R LAND ) R.B.I QRS PARK JN OF 15TH MAIN ROAD IN DN 99 UNIT 21 ZONE 8(BY QUALIFIED HORTICULTURIST FOR ONE YEAR),Own Sources,8,2017-18,2018-19 NH/2017-18/3113,Parks,Completed,NH-ANNA NAGAR,99,300000,"PROVIDING PLAY APPARATUS AT J BLOCK 14TH STREET PARK IN DN-99,UNIT-21,ZONE-8",MLACDS,8,2017-18,2018-19 NH/2017-18/7253,Roads,Completed,NH-ANNA NAGAR,99,179000,"PROVIDING THERMO PLAST AND STUD FOR SPEED BREAKERS VARIOUS STREET IN DIVITION-99,UNIT-21,ZONE-08",Own Sources,8,2017-18,2017-18 NH/2017-18/8268,Storm Water Drain,Completed,NH-ANNA NAGAR,99,450000,"minor repairs to swd at various street in dn-99,u-21,z-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/8708,Roads,Completed,NH-ANNA NAGAR,99,344000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NEHRU NAGAR 1ST STREET IN DIVISION 99,UNIT-21,ZONE-8",Own Sources,8,2017-18,2018-19 BR/2017-18/11762,Roads,Completed,BR-Bus Route Roads,100,4367000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Anna Nagar 5th Avenue in Dn-100, Zone-VIII",Grants,8,2017-18,2018-19 L/2017-18/0293,Electrical,Completed,L-Electrical,100,3871000,"Provision of 4 Nos. of 8m Lamp Post with Single Straight Bracket, 24 Nos. of 8m Lamp Post with Double Straight Bracket & 6 Nos. of of 8m Lamp Post with Triple Straight Bracket with70 Nos. of 150 -165W LED Fittings at 2nd Avenue from 6th Main Road to 12th Main Road in Division 100, Anna Nagar Substation, Zone VIII.",Own Sources,8,2017-18,2017-18 L/2017-18/0294,Electrical,Completed,L-Electrical,100,2778600,"Provision of 19 nos of 8 mtr lamp post with Double straight bracket and 4 nos of 8 mtr lamp post with Triple straight bracket with 50 nos of 150w LED Fitting at 2nd avenue from Roundana to 6th main road division 100, in Zone-8",Own Sources,8,2017-18,2017-18 L/2017-18/17019,Electrical,Completed,L-Electrical,100,1553500,Supply and replacement of LED Fittings in-place of worn out and damaged CFL Fittings at Anna tower park in div 100 Zone VIII,Own Sources,8,2017-18,2019-20 L/2017-18/7143,Electrical,Completed,L-Electrical,100,193000,Replacement of 545 mtrs of 2X16 sqmm PVC alu UG cable at AJ block 4th & 5th street in Division 100 under Zone-VIII area.,Own Sources,8,2017-18,2018-19 NH/2017-18/13191,Parks,Completed,NH-ANNA NAGAR,100,379000,"ANNUAL MAINTENANCE OF PARK AT AL BLOCK 3rd STREET IN DN.100,UNIT 22,ZONE 8.(Employed Qualified Horticulturist only)",Own Sources,8,2017-18,2018-19 NH/2017-18/13192,Parks,Completed,NH-ANNA NAGAR,100,380000,"Annual Maintenance of AD Block park 3rd street in DN.100,Unit-22,Zone-8.(qualified horticulturist only).",Own Sources,8,2017-18,2018-19 NH/2017-18/13193,Parks,Completed,NH-ANNA NAGAR,100,386000,"Annual Maintenance of park at AL Block 14th Main Road park (By employing qualified horticulturist for only) in Dn.100,Unit-22,Zone-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1331,Buildings,Completed,Q-Solid Waste Management,100,1995000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT 6th AVENUE AND ARUMBAKKAM BURIAL GROUND IN DN-100,UNIT-22,ZONE-08",Own Sources,8,2017-18,2019-20 NH/2017-18/14096,Parks,Completed,NH-ANNA NAGAR,100,472000,"Improvement of Tower Park in DN -100, Unit -22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/14410,Buildings,Completed,NH-ANNA NAGAR,100,152000,"REPAIR WORK TO ANNA TOWER PARK, ,ANGANVADI, SWD,@ DN 100 UNIT 22 ZONE 8",Own Sources,8,2017-18,2017-18 NH/2017-18/14548,Buildings,Completed,NH-ANNA NAGAR,100,486000,"Repairs work and Replacement of Electric Crematorium at Hindu Burial Ground Arumbakkam in DN-100,Unit-22,Zone - 08",Own Sources,8,2017-18,2018-19 NH/2017-18/14936,Roads,Completed,NH-ANNA NAGAR,100,1437000,"IMPROVEMENT TO THE BT ROAD AT 5TH AVENUE ( PART ) IN DN-100,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/16375,Roads,Completed,NH-ANNA NAGAR,100,2460000,"RESTORATION OF ROAD CUT MADE BY TNEB AT 7TH MAIN ROAD IN DIVISION -100, UNIT-22, ZONE -08",Deposit Works,8,2017-18,2018-19 NH/2017-18/16376,Roads,Completed,NH-ANNA NAGAR,100,2460000,"RESTORATION OF ROAD CUT MADE BY TNEB AT 14TH MAIN ROAD, 8TH MAIN ROAD AND AH BLOCK 5TH STREET IN DIVISION -100, UNIT-22, ZONE -08",Deposit Works,8,2017-18,2018-19 NH/2017-18/16381,Roads,Completed,NH-ANNA NAGAR,100,1560000,"RESTORATION OF ROAD CUT MADE BY TNEB AT AG BLOCK 3RD STREET IN DIVISION -100, UNIT-22, ZONE -08",Deposit Works,8,2017-18,2018-19 NH/2017-18/16455,Buildings,Completed,NH-ANNA NAGAR,100,200000,"RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DIV-100, UNIT-22, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/16461,Buildings,Completed,NH-ANNA NAGAR,100,197000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIV-100, UNIT-22, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/16638,Parks,Completed,NH-ANNA NAGAR,100,1566000,"MAINTENANCE OF DR.VISWESWARAYA TOWER PARK FOR SIX MONTHS IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/17692,Parks,Completed,NH-ANNA NAGAR,100,5424000,"MAINTENANCE OF DR.VISWESWARAYA TOWER PARK AT 3RD MAIN ROAD FOR A PERIOD OF ONE YEAR IN DN-100,UNIT-22,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/17693,Parks,Completed,NH-ANNA NAGAR,100,706000,"MAINTENANCE OF PARK AT AL - BLOCK PARK 14TH MAIN ROAD FOR A PERIOD OF ONE YEAR IN DN-100,UNIT-22,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/17694,Parks,Completed,NH-ANNA NAGAR,100,701000,"MAINTENANCE OF PARK AT AD - BLOCK PARK 3RD STREET FOR A PERIOD OF ONE YEAR IN DN-100,UNIT-22,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/7629,Roads,Completed,NH-ANNA NAGAR,100,212000,"PROVIDING SPEED BREAKER AT VARIOUS STREET IN DN-100, UNIT-22 ZONE-8",Own Sources,8,2017-18,2017-18 NH/2017-18/8528,Storm Water Drain,Completed,NH-ANNA NAGAR,100,989000,"Desilting of Storm Water Drain at Various Street in DN -100, Unit -22, Zone -08.",Own Sources,8,2017-18,2017-18 NH/2017-18/8854,Storm Water Drain,Completed,NH-ANNA NAGAR,100,680000,"Improvement to Storm Water Drain at Various Street in DN -100, Unit -22, Zone -08.",Own Sources,8,2017-18,2017-18 NH/2017-18/9337,Parks,Completed,NH-ANNA NAGAR,100,1422000,"MAINTENANCE OF DR.VISWESWARAYA TOWER PARK FOR SIX MONTHS IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/9356,Roads,Completed,NH-ANNA NAGAR,100,1756000,"IMPROVEMENT TO THE BT ROAD AT 7TH MAIN ROAD ( PART ) IN DN-100,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/9376,Roads,Completed,NH-ANNA NAGAR,100,1290000,"IMPROVEMENT TO THE B T ROAD AT THIRUVEETHI AMMAN KOIL STREET (WEST) IN DN-100,UNIT-22, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/9377,Roads,Completed,NH-ANNA NAGAR,100,375000,"IMPROVEMENT TO THE B T ROAD AT Y BLOCK 7th STREET IN DN-100,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/9378,Roads,Completed,NH-ANNA NAGAR,100,7838000,"IMPROVEMENT TO THE BT ROAD AT 7TH MAIN ROAD ( WEST) IN DN-100,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/9433,Roads,Completed,NH-ANNA NAGAR,100,147000,"Improvement to BT Road at AH Block 5th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9434,Roads,Completed,NH-ANNA NAGAR,100,573000,"Improvement to BT Road at AH Block 4th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9435,Roads,Completed,NH-ANNA NAGAR,100,261000,"Improvement to BT Road at AH Block 2nd St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9436,Roads,Completed,NH-ANNA NAGAR,100,549000,"Improvement to BT Road at AH Block 1 st St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9437,Roads,Completed,NH-ANNA NAGAR,100,549000,"Improvement to BT Road at Anna Nagar 3rd Main Road (Tnscb Quarters) in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9438,Roads,Completed,NH-ANNA NAGAR,100,152000,"Improvement to BT Road at Z Block 11th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9439,Roads,Completed,NH-ANNA NAGAR,100,166000,"Improvement to BT Road at Z Block 8th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9440,Roads,Completed,NH-ANNA NAGAR,100,145000,"Improvement to BT Road at Z Block 9th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9441,Roads,Completed,NH-ANNA NAGAR,100,817000,"Improvement to BT Road at U Block 9th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9442,Roads,Completed,NH-ANNA NAGAR,100,188000,"Improvement to BT Road at V Block 10th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9443,Roads,Completed,NH-ANNA NAGAR,100,482000,"Improvement to BT Road at V Block 14th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9444,Roads,Completed,NH-ANNA NAGAR,100,390000,"Improvement to BT Road at AE Block 2nd & Post Office St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9445,Roads,Completed,NH-ANNA NAGAR,100,85000,"Improvement to BT Road at AA Block 2nd street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9446,Roads,Completed,NH-ANNA NAGAR,100,328000,"Improvement to BT Road at AL Block 4th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9447,Roads,Completed,NH-ANNA NAGAR,100,354000,"Improvement to BT Road at AJ Block 2nd St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9448,Roads,Completed,NH-ANNA NAGAR,100,352000,"Improvement to BT Road at AJ Block 4th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9449,Roads,Completed,NH-ANNA NAGAR,100,559000,"Improvement to BT Road at AH Block 7th Main Road in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9450,Roads,Completed,NH-ANNA NAGAR,100,194000,"Improvement to BT Road at AA Block 4th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9451,Roads,Completed,NH-ANNA NAGAR,100,197000,"Improvement to BT Road at AB Block 2nd St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9452,Roads,Completed,NH-ANNA NAGAR,100,216000,"Improvement to BT Road at AB Block 1st St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9453,Roads,Completed,NH-ANNA NAGAR,100,244000,"Improvement to BT Road at AD Block 4th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9454,Roads,Completed,NH-ANNA NAGAR,100,219000,"Improvement to BT Road at AD Block 5th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9455,Roads,Completed,NH-ANNA NAGAR,100,1006000,"Improvement to BT Road at 7th Main Road (reach 1) in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9456,Roads,Completed,NH-ANNA NAGAR,100,939000,"Improvement to BT Road at 14th Main Road in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9457,Roads,Completed,NH-ANNA NAGAR,100,1006000,"Improvement to BT Road at Thiruveethi Amman Kovil St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9458,Roads,Completed,NH-ANNA NAGAR,100,2518000,"Improvement to BT Road at 7th main Road (reach 2) in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9459,Roads,Completed,NH-ANNA NAGAR,100,192000,"Improvement to the BT Road at AB Block 2nd Street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9460,Roads,Completed,NH-ANNA NAGAR,100,549000,"Improvement to the BT Road at Anna Nagar 3rd Main Road (Tnscb Quarters) in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9461,Roads,Completed,NH-ANNA NAGAR,100,201000,"Improvement to the BT Road at R Block 15th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9462,Roads,Completed,NH-ANNA NAGAR,100,237000,"Improvement to the BT Road at R Block 13th St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9463,Roads,Completed,NH-ANNA NAGAR,100,188000,"Improvement to the BT Road at 3rd Main Road in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9464,Roads,Completed,NH-ANNA NAGAR,100,811000,"Improvement to Cement Concrete Road at AI Block 4th & 5th street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9465,Roads,Completed,NH-ANNA NAGAR,100,260000,"Improvement to Cement Concrete Road at AG block 3rd street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9466,Roads,Completed,NH-ANNA NAGAR,100,152000,"Improvement to Cement Concrete Road at AE Block 3rd street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9467,Roads,Completed,NH-ANNA NAGAR,100,310000,"Improvement to Cement Concrete Road at Indra Nagar Slum Road in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9468,Roads,Completed,NH-ANNA NAGAR,100,226000,"Improvement to Cement Concrete Road at Pillaiyar Koil Street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9469,Roads,Completed,NH-ANNA NAGAR,100,261000,"Improvement to the Cement Concrete Road at Bajanai koil st in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9471,Roads,Completed,NH-ANNA NAGAR,100,536000,"Improvement to the Cement Concrete Road at New Colony in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9472,Roads,Completed,NH-ANNA NAGAR,100,43000,"Improvement to the BT Road at Anna Nagar 3rd Main Road in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9473,Roads,Completed,NH-ANNA NAGAR,100,201000,"Improvement to the BT Road at R block 15th street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9474,Roads,Completed,NH-ANNA NAGAR,100,237000,"Improvement to the BT Road at R block 13th street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9475,Roads,Completed,NH-ANNA NAGAR,100,335000,"Improvement to the BT Road at S - Block 16th street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9476,Roads,Completed,NH-ANNA NAGAR,100,167000,"Improvement to the BT Road at S - Block 21st street in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9477,Roads,Completed,NH-ANNA NAGAR,100,144000,"Improvement to the BT Road at 4th Main Road in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9483,Parks,Completed,NH-ANNA NAGAR,100,226000,"Improvement to the Cement Concrete road at Pillaiyar koil St in DN -100, Unit-22, Zone -08",Own Sources,8,2017-18,2018-19 NH/2017-18/9697,Buildings,Completed,Q-Solid Waste Management,100,600000,"Construction of Bio Gas Plant at (New Amma unavagam) 3rd Avenue in Div-100, Unit-22, Zone-8",Own Sources,8,2017-18,2018-19 B/2017-18/10635,Buildings,Completed,B-Buildings,101,5570000,"PROPOSED CONSTRUCTION OF KITCHEN SHED (STILT+F.F) IN AMMA KALAIARANGAM AT SHENOY NAGAR IN DN-101,Z-8",Own Sources,8,2017-18,2019-20 BR/2017-18/1794,Road Cut,Completed,BR-Bus Route Roads,101,103000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 1 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/1798,Road Cut,Completed,BR-Bus Route Roads,101,38800,Restoration of Roadcut made by Airtel at Various Interior Roads ( 2 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/1799,Road Cut,Completed,BR-Bus Route Roads,101,244000,Restoration of Roadcut made by IDEA at Various Interior Roads ( 1 Road) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/1800,Road Cut,Completed,BR-Bus Route Roads,101,615000,Restoration of Roadcut made by VODAFONE at Various Interior Roads ( 17 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/1852,Road Cut,Completed,BR-Bus Route Roads,101,245000,Restoration of Roadcut made by BSNL at Various Interior Roads ( 7 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/1962,Road Cut,Completed,BR-Bus Route Roads,101,688000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 7 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/2031,Roads,Completed,BR-Bus Route Roads,101,988000,"Providing and laying of Thermoplastic painting & studs at Purasaivakkam High road , New avadi road , MTH road, Reddy Street, Flowers Road, Razak garden Road, Water Tank road, Dr. Alagappa Road and Other Bus Route Roads in Zone - 8",Own Sources,8,2017-18,2017-18 BR/2017-18/2071,Road Cut,Completed,BR-Bus Route Roads,101,739000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 6 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/2075,Road Cut,Completed,BR-Bus Route Roads,101,501000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 5 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/2080,Road Cut,Completed,BR-Bus Route Roads,101,735000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 16 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/2105,Road Cut,Completed,BR-Bus Route Roads,101,851000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 6 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/2133,Road Cut,Completed,BR-Bus Route Roads,101,828000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads and Interior Roads ( 14 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/2134,Road Cut,Completed,BR-Bus Route Roads,101,590000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads and Interior Roads ( 11 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/2135,Road Cut,Completed,BR-Bus Route Roads,101,310000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads and Interior Roads ( 7 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/3008,Road Cut,Completed,BR-Bus Route Roads,101,515000,Restoration of Roadcut made by IDEA at Various Interior Roads ( 14 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3010,Road Cut,Completed,BR-Bus Route Roads,101,74000,Restoration of Roadcut made by VODAFONE at Various Bus Route Roads ( 1 Road) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3071,Road Cut,Completed,BR-Bus Route Roads,101,89600,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 1 Road) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3074,Road Cut,Completed,BR-Bus Route Roads,101,38800,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 1 Road) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3075,Road Cut,Completed,BR-Bus Route Roads,101,115000,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 2 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3078,Road Cut,Completed,BR-Bus Route Roads,101,128000,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 1 Road) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3079,Road Cut,Completed,BR-Bus Route Roads,101,51400,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 2 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3089,Road Cut,Completed,BR-Bus Route Roads,101,184000,Restoration of Roadcut made by AIRTEL at Various Bus Route Roads ( 1 Road) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/3092,Road Cut,Completed,BR-Bus Route Roads,101,333000,Restoration of Roadcut made by IDEA at Various Interior Roads ( 8 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/3098,Road Cut,Completed,BR-Bus Route Roads,101,180000,Restoration of Roadcut made by VODAFONE at VariousBus Route Roads ( 1 Road) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/3102,Road Cut,Completed,BR-Bus Route Roads,101,40800,Restoration of Roadcut made by AIRTEL at Various Bus Route Roads ( 1 Road) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/3104,Road Cut,Completed,BR-Bus Route Roads,101,143000,Restoration of Roadcut made by AIRTEL at Bus Route Roads ( 1 Road) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/3127,Road Cut,Completed,BR-Bus Route Roads,101,50600,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 2 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/3130,Road Cut,Completed,BR-Bus Route Roads,101,72000,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 3 Roads) in Zone -9,Deposit Works,8,2017-18,2018-19 BR/2017-18/6495,Road Cut,Completed,BR-Bus Route Roads,101,296000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads and Interior Roads ( 6 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/6714,Road Cut,Completed,BR-Bus Route Roads,101,52000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 2 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/6715,Road Cut,Completed,BR-Bus Route Roads,101,179000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 8 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 BR/2017-18/6716,Road Cut,Completed,BR-Bus Route Roads,101,51000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 1 Roads) in Zone -8,Deposit Works,8,2017-18,2018-19 L/2017-18/0296,Electrical,Completed,L-Electrical,101,1753500,"Provision of 4nos of 8mtr lamp post with single straight bracket,10 nos of 8 mtr lamp post with Double straight bracket and 2 nos of 8 mtr lamp post with Triple straight bracket with 30 nos of 150w LED Fitting at 2nd avenue from Rountana to Chinthamani Road Division 101 in Zone-8",Own Sources,8,2017-18,2017-18 L/2017-18/13483,Electrical,Completed,L-Electrical,101,149000,Supply and replacement of worn out and damaged cables,Own Sources,8,2017-18,2018-19 L/2017-18/14284,Electrical,Completed,L-Electrical,101,180200,Supply and replacement of worn out cables in div 101,Own Sources,8,2017-18,2018-19 L/2017-18/14585,Electrical,Completed,L-Electrical,101,188700,Supply and replacement of worn out Under ground cables in div 101,Own Sources,8,2017-18,2018-19 L/2017-18/17018,Electrical,Completed,L-Electrical,101,1710200,Replacement of old and damaged cables,Own Sources,8,2017-18,2019-20 NH/2017-18/0443,Roads,Completed,NH-ANNA NAGAR,101,488000,"PROVIDING AND LAYING SPEED BREAKERS AT VARIOUS STREET IN DN-101,U-22,Z-08",Own Sources,8,2017-18,2017-18 NH/2017-18/11239,Buildings,Completed,NH-ANNA NAGAR,101,836550,"Repair works to the Velangadu Gasifier Crematorium in Division-101, Unit-22, Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/11956,Parks,Completed,NH-ANNA NAGAR,101,140000,"MAINTENANCE FOR GREENERY AREA FOR ONE YEAR OF 2ND MAIN ROAD PARK IN DN-101,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/11957,Parks,Completed,NH-ANNA NAGAR,101,165000,"MAINTENANCE FOR GREENERY AREA FOR ONE YEAR OF C- BLOCK PARK IN DN-101,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/11958,Parks,Completed,NH-ANNA NAGAR,101,520000,"MAINTENANCE FOR GREENERY AREA FOR ONE YEAR OF BOGANVILLA PARK IN DN-101,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1322,Buildings,Completed,Q-Solid Waste Management,101,2005000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT VELANKADU AND NEAR BHAGAVATHY AMMAN TEMPLE IN DIV-101, UNIT-22, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/14034,Road Cut,Completed,NH-ANNA NAGAR,101,188000,"IMPROVEMENTS TO BT ROAD AT P BLOCK 19 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14043,Road Cut,Completed,NH-ANNA NAGAR,101,237000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 5 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14044,Road Cut,Completed,NH-ANNA NAGAR,101,304000,"IMPROVEMENTS TO BT ROAD AT P BLOCK 17 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14045,Road Cut,Completed,NH-ANNA NAGAR,101,908000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 1 ST STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14046,Road Cut,Completed,NH-ANNA NAGAR,101,622000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 2 ND STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14047,Road Cut,Completed,NH-ANNA NAGAR,101,439000,"IMPROVEMENTS TO BT ROAD AT P BLOCK 18 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14048,Road Cut,Completed,NH-ANNA NAGAR,101,237000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 3 RD STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14049,Road Cut,Completed,NH-ANNA NAGAR,101,640000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 4 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14050,Road Cut,Completed,NH-ANNA NAGAR,101,640000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 6 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14052,Road Cut,Completed,NH-ANNA NAGAR,101,653000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 7 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14053,Road Cut,Completed,NH-ANNA NAGAR,101,439000,"IMPROVEMENTS TO BT ROAD AT P BLOCK 21 ST STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14055,Road Cut,Completed,NH-ANNA NAGAR,101,256000,"IMPROVEMENTS TO BT ROAD AT W BLOCK 1 ST MAIN ROAD IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14056,Road Cut,Completed,NH-ANNA NAGAR,101,774000,"IMPROVEMENTS TO BT ROAD AT ANNA NAGAR 3 RD MAIN ROAD IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14057,Road Cut,Completed,NH-ANNA NAGAR,101,537000,"IMPROVEMENTS TO BT ROAD AT P BLOCK 20 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14059,Road Cut,Completed,NH-ANNA NAGAR,101,237000,"IMPROVEMENTS TO BT ROAD AT F BLOCK 3 RD STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14060,Road Cut,Completed,NH-ANNA NAGAR,101,1476000,"IMPROVEMENTS TO BT ROAD AT O BLOCK 29 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14061,Road Cut,Completed,NH-ANNA NAGAR,101,188000,"IMPROVEMENTS TO BT ROAD AT T BLOCK 12 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14062,Road Cut,Completed,NH-ANNA NAGAR,101,640000,"IMPROVEMENTS TO BT ROAD AT Q BLOCK 15 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14064,Road Cut,Completed,NH-ANNA NAGAR,101,268000,"IMPROVEMENTS TO BT ROAD AT Q BLOCK 13 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14065,Road Cut,Completed,NH-ANNA NAGAR,101,439000,"IMPROVEMENTS TO BT ROAD AT T BLOCK 1 ST STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14066,Road Cut,Completed,NH-ANNA NAGAR,101,268000,"IMPROVEMENTS TO BT ROAD AT T BLOCK 10 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14068,Road Cut,Completed,NH-ANNA NAGAR,101,268000,"IMPROVEMENTS TO BT ROAD AT Q BLOCK 14 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14071,Road Cut,Completed,NH-ANNA NAGAR,101,469000,"IMPROVEMENTS TO BT ROAD AT Q BLOCK 16 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14105,Road Cut,Completed,NH-ANNA NAGAR,101,604000,"IMPROVEMENTS TO BT ROAD AT Q BLOCK 17 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14107,Road Cut,Completed,NH-ANNA NAGAR,101,604000,"IMPROVEMENTS TO BT ROAD AT T BLOCK 8 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14108,Road Cut,Completed,NH-ANNA NAGAR,101,268000,"IMPROVEMENTS TO BT ROAD AT T BLOCK 9 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14116,Road Cut,Completed,NH-ANNA NAGAR,101,1445000,"IMPROVEMENTS TO BT ROAD AT 2 ND AVENUE F BLOCK IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14117,Road Cut,Completed,NH-ANNA NAGAR,101,1445000,"IMPROVEMENTS TO BT ROAD AT 2 ND AVENUE A,B,C BLOCK IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14119,Road Cut,Completed,NH-ANNA NAGAR,101,604000,"IMPROVEMENTS TO BT ROAD AT T BLOCK 11 TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/15817,Buildings,Completed,NH-ANNA NAGAR,101,61000,"REPAIR AND IMPROVEMENT TO AMMA ANRANGAM AND ICDS BULDINGS, AMMA UNAVAGAM IN DN 101 UNIT 22 ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/17682,Parks,Completed,NH-ANNA NAGAR,101,216000,"MAINTENANCE FOR PARK AT 2ND MAIN ROAD FOR A PERIOD OF ONE YEAR IN DN-101,UNIT-22,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17683,Parks,Completed,NH-ANNA NAGAR,101,202000,"MAINTENANCE FOR C BLOCK PARK FOR A PERIOD OF ONE YEAR IN DN-101,UNIT-22,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17684,Parks,Completed,NH-ANNA NAGAR,101,985000,"MAINTENANCE FOR BOGAN VILLA PARK FOR A PERIOD OF ONE YEAR IN DN-101,UNIT-22,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/2319,Storm Water Drain,Completed,NH-ANNA NAGAR,101,999000,"REPAIRS AND IMPROVEMENTS WORK TO STROM WATER DRIAN AT VARIOUS STREET IN DIVISION-101,UNIT-22,ZONE-8",Own Sources,8,2017-18,2017-18 NH/2017-18/8598,Storm Water Drain,Completed,NH-ANNA NAGAR,101,1398000,"Desilting of Storm Water Drain at Various Street in Division-101, Unit-22, Zone-8",Own Sources,8,2017-18,2017-18 NH/2017-18/9700,Buildings,Completed,Q-Solid Waste Management,101,2022000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY CENTER WITH BASIC MACHINERIES AT VELANKADU BURIAL GROUND IN DN 101, UNIT, 22 ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/9923,Buildings,Completed,NH-ANNA NAGAR,101,261000,"ENGAGEMENT OF OPERATORS IN BIOMETHANATION PLANT- (ANNUALLY) IN VELANGADU BURIAL GROUND IN DN-101, UNIT-22,ZONE-8",Own Sources,8,2017-18,2018-19 B/2017-18/13084,Buildings,Completed,B-Buildings,102,22590400,REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE IN ZONE-9,Own Sources,8,2017-18,2019-20 BR/2017-18/11789,Footpath,Completed,BR-Bus Route Roads,102,16880000,"Forming Footpath at Anna Nagar 1st Avenue in Dn-102, Zone-VIII",Grants,8,2017-18,2018-19 BR/2017-18/7885,Road Cut,Completed,BR-Bus Route Roads,102,910000,"Restoration of Roadcut made by TANGEDCO at New Avadi Road , Kilpauk Garden Road in Dn -102, Zone - 8 (Chellan No: BR/2015-16/0018663 & BR/2017-18/0012723)",Deposit Works,8,2017-18,2018-19 BR/2017-18/7951,Road Cut,Completed,BR-Bus Route Roads,102,1360000,"Restoration of Roadcut made by TANGEDCO at Pulla Avenue in Dn -102, Zone - 8 (Chellan No: BR/2015-16/0018663 & BR/2017-18/0012723)",Deposit Works,8,2017-18,2018-19 L/2017-18/6447,Electrical,Completed,L-Electrical,102,903800,"Replacement of 2x16Sqmm Aluminium UG Cable 2259mtr at V.O.C.Nagar 1st street to 5th street and New Colony in Division-102, Zone-VIII area.",Own Sources,8,2017-18,2017-18 L/2017-18/8155,Electrical,Completed,L-Electrical,102,795400,"Smart class wiring for CHS School Ayanavaram Div-96, CGHS School Pulla Avenue Div - 102,CMS Aminjikarai in Div-102,CBHS School G.E.Kovil street Div - 104 and CHS School Subrayan street Div - 107, in Zone-8 area.",Own Sources,8,2017-18,2018-19 NH/2017-18/10209,Buildings,Completed,NH-ANNA NAGAR,102,507000,"Repair works to terrace floor, OHT and ramp at Pulla avenue UPHC hospital in Division 102, Unit 23, Zone 8",Own Sources,8,2017-18,2018-19 NH/2017-18/11162,Buildings,Completed,NH-ANNA NAGAR,102,1200000,"Repair and improvements works to the hospital building at 1st Cross street west and Gajapathy street in Division 102, Unit 23, Zone 8",Own Sources,8,2017-18,2017-18 NH/2017-18/1333,Buildings,Completed,Q-Solid Waste Management,102,1350000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT BIG STREET AND GAJAPATHY STREET IN DIVISION-102,UNIT-23,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/13906,Road Cut,Completed,NH-ANNA NAGAR,102,275000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT VOC NAGAR 3 RD STREET IN DIV - 102, UNIT - 23, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13907,Road Cut,Completed,NH-ANNA NAGAR,102,379000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT VOC NAGAR 4 TH STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13908,Road Cut,Completed,NH-ANNA NAGAR,102,241000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT KUMARAN NAGAR 1 ST STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13910,Road Cut,Completed,NH-ANNA NAGAR,102,241000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT KUMARAN NAGAR 2 ND STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13911,Road Cut,Completed,NH-ANNA NAGAR,102,464000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT KVN PURAM 2 ND STREET IN DIV 102, UNIT 16, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13913,Road Cut,Completed,NH-ANNA NAGAR,102,310000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT JOTHIAMMAL NAGAR 2 ND STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13914,Road Cut,Completed,NH-ANNA NAGAR,102,241000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT JOTHIAMMAL NAGAR 3 RD STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13916,Road Cut,Completed,NH-ANNA NAGAR,102,206000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT JOTHIAMMAL NAGAR 4 TH STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13921,Road Cut,Completed,NH-ANNA NAGAR,102,241000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT JOTHIAMMAL NAGAR 6 TH STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13923,Road Cut,Completed,NH-ANNA NAGAR,102,138000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT JOTHIAMMAL NAGAR 8 TH STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13928,Road Cut,Completed,NH-ANNA NAGAR,102,137000,"IMPROVEMENT TO THE CEMENT CONCRETE ROAD AT JOTHIAMMAL NAGAR 10 TH STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13967,Roads,Completed,NH-ANNA NAGAR,102,1176000,"IMPROVEMENT TO THE BT ROAD AT CHELLAMAL STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13969,Roads,Completed,NH-ANNA NAGAR,102,800000,"IMPROVEMENT TO THE BT ROAD AT NADHAMUNI STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13970,Roads,Completed,NH-ANNA NAGAR,102,396000,"IMPROVEMENT TO THE BT ROAD AT TP CHATHIRAM 9 TH CROSS STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13971,Roads,Completed,NH-ANNA NAGAR,102,340000,"IMPROVEMENT TO THE BT ROAD AT TP CHATHIRAM 18 TH CROSS STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13972,Roads,Completed,NH-ANNA NAGAR,102,300000,"IMPROVEMENT TO THE BT ROAD AT TP CHATHIRAM 19 TH CROSS STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13974,Roads,Completed,NH-ANNA NAGAR,102,3080000,"IMPROVEMENT TO THE BT ROAD AT GUJJI MAIN ROAD IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14541,Roads,Completed,NH-ANNA NAGAR,102,900000,"IMPROVEMENTS TO THE BT ROAD AT MANDAPAM CROSS STREET IN DN 102, UNIT 23, ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/14542,Roads,Completed,NH-ANNA NAGAR,102,594000,"IMPROVEMENTS TO THE BT AT MANDAPAM 1 ST STREET IN DN 102, UNIT 23, ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/14543,Roads,Completed,NH-ANNA NAGAR,102,576000,"IMPROVEMENTS TO THE BT ROAD AT MANDAPAM 3 RD STREET IN DIV 102, UNIT 23, ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/15721,Buildings,Completed,NH-ANNA NAGAR,102,145000,"REPAIR WORK TO ZONE OFFICE, JJ STEADIYAM, SCHOOL, AMMA UNAVAGAM, IN DN 102 UNIT 23 ZONE 8",Own Sources,8,2017-18,2017-18 NH/2017-18/17685,Parks,Completed,NH-ANNA NAGAR,102,665000,"MAINTENANCE OF PARK AT G BLOCK FOR A PERIOD OF ONE YEAR IN DN-102,UNIT-23,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17701,Parks,Completed,NH-ANNA NAGAR,102,1170000,"MAINTENANCE OF PARK AT SCATTING PARK FOR A PERIOD OF ONE YEAR IN DN-102,UNIT-23,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/17716,Buildings,Completed,NH-ANNA NAGAR,102,629000,"Maintenance and Operation of the plant (AMMA KUDINEER) at Mandapam Road in Dn-102, Unit-23, Zone-08.",Own Sources,8,2017-18,2019-20 NH/2017-18/1888,Road Cut,Completed,NH-ANNA NAGAR,102,299000,"IMPROVEMENTS TO THE BT ROAD AT MANDAPAM ROAD 2 ND CROSS STREET IN DIV - 102, UNIT - 23, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1889,Road Cut,Completed,NH-ANNA NAGAR,102,1050000,"IMPROVEMENTS TO THE BT ROAD AT K.G COLONY PLAY GROUND STREET IN DIV - 102, UNIT - 23, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1890,Road Cut,Completed,NH-ANNA NAGAR,102,1186000,"IMPROVEMENTS TO THE BT ROAD AT K.G COLONY EAST STREET IN DIV - 102, UNIT - 23, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1892,Road Cut,Completed,NH-ANNA NAGAR,102,335000,"IMPROVEMENTS TO THE BT ROAD AT CHELLAMAL STREET IN DIV - 102, UNIT - 23, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1893,Road Cut,Completed,NH-ANNA NAGAR,102,638000,"IMPROVEMENTS TO THE BT ROAD AT K.G COLONY CANAL ROAD IN DIV - 102, UNIT - 23, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1894,Road Cut,Completed,NH-ANNA NAGAR,102,2103000,"IMPROVEMENTS TO THE BT ROAD AT K.G COLONY 1 ST STREET IN DIV - 102, UNIT - 23, ZONE -8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1895,Road Cut,Completed,NH-ANNA NAGAR,102,168000,IMPROVEMENTS TO THE BT ROAD AT KANNI AMMAN KOIL STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/1898,Road Cut,Completed,NH-ANNA NAGAR,102,149000,IMPROVEMENTS TO THE BT ROAD AT NEW MANDAPAM ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/1917,Road Cut,Completed,NH-ANNA NAGAR,102,1001000,IMPROVEMENTS TO THE BT ROAD AT TP CHATIRAM MAIN ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/1922,Road Cut,Completed,NH-ANNA NAGAR,102,604000,IMPROVEMENTS TO THE BT ROAD AT AYYAVOO STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/4846,Road Cut,Completed,NH-ANNA NAGAR,102,1006000,IMPROVEMENTS TO THE BT ROAD AT MAHATMA GANDHI ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/4921,Road Cut,Completed,NH-ANNA NAGAR,102,335000,IMPROVEMENTS TO THE BT ROAD AT LAKSHMI TALKIES ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6520,Road Cut,Completed,NH-ANNA NAGAR,102,671000,IMPROVEMENTS TO THE BT ROAD AT CEMENTRY ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6521,Road Cut,Completed,NH-ANNA NAGAR,102,1006000,IMPROVEMENTS TO THE BT ROAD AT EAST CLUB ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6522,Road Cut,Completed,NH-ANNA NAGAR,102,201000,IMPROVEMENTS TO THE BT ROAD AT G BLOCK 9TH STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6523,Road Cut,Completed,NH-ANNA NAGAR,102,1408000,IMPROVEMENTS TO THE BT ROAD AT 1ST MAIN ROAD EAST IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6545,Road Cut,Completed,NH-ANNA NAGAR,102,1981000,IMPROVEMENTS TO THE BT ROAD AT MANDAPAM ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6546,Road Cut,Completed,NH-ANNA NAGAR,102,671000,IMPROVEMENTS TO THE BT ROAD AT VENKATASAMY PURAM 1 ST STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6547,Storm Water Drain,Completed,NH-ANNA NAGAR,102,699999,REPAIRS AND IMPROVEMENTS SWD AT VARIOUS STREETS IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2017-18 NH/2017-18/6548,Road Cut,Completed,NH-ANNA NAGAR,102,707000,IMPROVEMENTS TO THE BT ROAD AT VENKATASAMY PURAM 2 ND STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6556,Road Cut,Completed,NH-ANNA NAGAR,102,537000,IMPROVEMENTS TO THE BT ROAD AT MOSQUE STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6560,Road Cut,Completed,NH-ANNA NAGAR,102,268000,IMPROVEMENTS TO THE BT ROAD AT CART TRACK ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6567,Road Cut,Completed,NH-ANNA NAGAR,102,304000,IMPROVEMENTS TO THE BT ROAD AT VOC NAGAR MAIN ROAD IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6573,Road Cut,Completed,NH-ANNA NAGAR,102,201000,IMPROVEMENTS TO THE BT ROAD AT RAJIV GANDHI STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6576,Road Cut,Completed,NH-ANNA NAGAR,102,201000,IMPROVEMENTS TO THE BT ROAD AT INDRA GANDHI STREET IN DIV 102 UNIT 23 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/6826,Buildings,Completed,NH-ANNA NAGAR,102,836000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR CORPORATION VACCANT LAND AT GAJAPATHY STREET JN OF 4 TH CROSS STREET IN DN - 102, UNIT - 23, ZONE - 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7320,Roads,Completed,NH-ANNA NAGAR,102,166000,"PROVIDING THERMOPLASTIC COMPOUND AND REFLECTIVE PAVEMENT FOR SPEED BREAKERS AT VARIOUS STREET IN DIVISION- 102, UNIT - 23, ZONE - 8",Own Sources,8,2017-18,2017-18 NH/2017-18/7802,Roads,Completed,NH-ANNA NAGAR,102,1926000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT KVN PURAM 1st STREET IN DIVISION-102, UNIT-23, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/8688,Storm Water Drain,Completed,NH-ANNA NAGAR,102,1200000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION -102, UNIT-23, ZONE-8",Own Sources,8,2017-18,2017-18 NH/2017-18/8907,Playfields,Completed,NH-ANNA NAGAR,102,450000,"MINOR REPAIR WORKS TO THE DAMAGED ASBESTOS SHEET AND WOODEN FLOORING AND BASKET BALL COURT OF THE J.J. BASKET BALL STADIUM AND SUPPLY OF TABLE TENNIS TABLE IN DIVISION 102, UNIT-23, ZONE -VIII.",Own Sources,8,2017-18,2018-19 NH/2017-18/9349,Buildings,Completed,NH-ANNA NAGAR,102,160000,"PROVIDING IMPROVEMENTS WORK IN SMART CLASS LOCATED IN PULLA AVENUE GIRLS HIGHER SECONDARY SCHOOL AT DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/9352,Buildings,Completed,NH-ANNA NAGAR,102,57000,"PROVIDING IMPROVEMENTS WORK IN SMART CLASS LOCATED IN PONDHAMALLI HIGH ROAD CMS SCHOOL AT DIVISION 102, UNIT 23, ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/9608,Parks,Completed,NH-ANNA NAGAR,102,639000,"ANNUAL MAINTENANCE OF SKKATTING PARK AT CEMENTRY ROAD IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/9609,Parks,Completed,NH-ANNA NAGAR,102,495000,"ANNUAL MAINTENANCE OF G BLOCK PARK IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 BR/2017-18/0216,Road Cut,Completed,BR-Bus Route Roads,103,970000,"Restoration of road cut Made by CMWSSB at New Avadi Road from the jn of Laksmi street to the jn of EVR salai in Dn -103, Zone - 8",Deposit Works,8,2017-18,2017-18 BR/2017-18/11791,Footpath,Completed,BR-Bus Route Roads,103,6278000,"Forming Footpath at Balfour Road from Kellys signal junction to the junction of Ormes road in Dn-103, Zone-VIII",Grants,8,2017-18,2019-20 BR/2017-18/11869,Footpath,Completed,BR-Bus Route Roads,103,4185000,"Forming Footpath at Harleys Road from the junction of Kilpauk garden road to junction of Balfour road in Dn-103, Zone-VIII",Grants,8,2017-18,2019-20 BR/2017-18/8437,Roads,Completed,BR-Bus Route Roads,103,298000,"Removing and Refixing of 2 Nos of Stainless Steel Bus Shelters at Poonamallee High Road near KMC Hospital and Fire Station in Dn-103, Zone-8",Own Sources,8,2017-18,2018-19 L/2017-18/1639,Electrical,Completed,L-Electrical,103,193700,"Replacement of Highmast Accessories and maintenance work in Ottery Buriyal ground at Bricklin road in Division-104, Zone - VIII area.",Own Sources,8,2017-18,2019-20 L/2017-18/1640,Electrical,Completed,L-Electrical,103,186500,"WORK: Proposal for Supply and fixing of 13 Nos of Timers at Tailors Road and Various places in Division-103 & 104, Zone - VIII.",Own Sources,8,2017-18,2017-18 L/2017-18/1641,Electrical,Completed,L-Electrical,103,188100,WORK: Painting of 976 Nos of lamp post in Purasaiwakkam high road and various places in division 103 Zone - VIII area.,Own Sources,8,2017-18,2017-18 L/2017-18/8062,Electrical,Completed,L-Electrical,103,4866300,"WORK: Proposal of 30 Nos of 8Mtr GI Lamp post with Double Arch Bracket and 8 Nos of 8Mtr GI Lamp post with Tripple Arch Bracket with 84 Nos of 150-165W LED Fitting in EVR Salai from Junction of Gengureddy Subway to Junction of Harrington road in Dn 102,103, Zone-VIII area.",Own Sources,8,2017-18,2018-19 NH/2017-18/0347,Footpath,Completed,NH-ANNA NAGAR,103,157000,"IMPROVEMENT TO THE CC ROAD AT SEMMENPATTAI 1ST STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/1321,Buildings,Completed,Q-Solid Waste Management,103,665000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT DIVISION OFFICE AND TEMPLE STREET IN DN-103,U-23,Z-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13217,Roads,Completed,NH-ANNA NAGAR,103,182000,"IMPROVEMENT TO THE BT ROAD AT VASU STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13218,Roads,Completed,NH-ANNA NAGAR,103,256000,"IMPROVEMENT TO THE BT ROAD AT T.P.CHATHIRAM 10TH CROSS STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13250,Roads,Completed,NH-ANNA NAGAR,103,268000,"IMPROVEMENT TO THE BT ROAD AT T.P.CHATHIRAM 5TH STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13256,Roads,Completed,NH-ANNA NAGAR,103,134000,"IMPROVEMENT TO THE BT ROAD AT KILPAUK GARDEN ROAD LANE IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13259,Roads,Completed,NH-ANNA NAGAR,103,67000,"IMPROVEMENT TO THE BT ROAD AT APPA GARDEN STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13267,Roads,Completed,NH-ANNA NAGAR,103,206000,"IMPROVEMENT TO THE CC ROAD AT SEMMENPETTAI 3RD STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13269,Roads,Completed,NH-ANNA NAGAR,103,123000,"IMPROVEMENT TO THE CC ROAD AT THIYAGAPPA STREET 3RD LANE IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13274,Roads,Completed,NH-ANNA NAGAR,103,124000,"IMPROVEMENT TO THE CC ROAD AT THIYAGAPPA STREET 2RD LANE IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/13276,Roads,Completed,NH-ANNA NAGAR,103,138000,"IMPROVEMENT TO THE CC ROAD AT THIYAGAPPA STREET 1ST LANE IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/14121,Buildings,Completed,NH-ANNA NAGAR,103,218000,"REPAIRS AND IMPROVEMENT TO THE P.C AT VALLIAMMAL STREET (JN OF TEMPLE LANE) IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/15735,Buildings,Completed,NH-ANNA NAGAR,103,71000,"REPAIR WORK TO AMMA UNAVAGAM, C.I OFFICE, NIGHT SHELTER, SWD AT VARIOUS PLACE IN DN-103, UNIT- 23, ZONE- 8.",Own Sources,8,2017-18,2017-18 NH/2017-18/16613,Buildings,Completed,NH-ANNA NAGAR,103,225000,"RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16615,Buildings,Completed,NH-ANNA NAGAR,103,176000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16767,Storm Water Drain,Completed,NH-ANNA NAGAR,103,200000,"RESTORATION OF DAMAGE STORM WATER DRAIN AT VARIOUS PLACES IN DN-103,UNIT-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/2203,Storm Water Drain,Completed,NH-ANNA NAGAR,103,1200000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/2221,Storm Water Drain,Completed,NH-ANNA NAGAR,103,700000,"REPAIRS AND IMPROVEMENTS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DN-103,U-23,Z-8",Own Sources,8,2017-18,2017-18 NH/2017-18/2488,Buildings,Completed,NH-ANNA NAGAR,103,428000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING NIGHT SHELTER AT SEMMENPETTAI IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/2903,Roads,Completed,NH-ANNA NAGAR,103,656000,"IMPROVEMENT TO THE B T ROAD AT T.P.CHATHIRAM 5TH CROSS STREET IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/2906,Roads,Completed,NH-ANNA NAGAR,103,224000,"IMPROVEMENT TO THE B T ROAD AT T.P.CHATHIRAM 3RD STREET IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/2917,Roads,Completed,NH-ANNA NAGAR,103,360000,"IMPROVEMENT TO THE BT ROAD AT T.P.CHATHIRAM 8TH CROSS STREET IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/2918,Roads,Completed,NH-ANNA NAGAR,103,1560000,"IMPROVEMENT TO THE BT ROAD AT DHAMODHARA MOORTHY STREET IN DN-103,UNIT-23,ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/3160,Buildings,Completed,NH-ANNA NAGAR,103,157000,"IMPROVEMENT TO THE CC ROAD AT SEMMENPATTAI 2ND STREET IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/3220,Buildings,Completed,NH-ANNA NAGAR,103,172000,"IMPROVEMENT TO THE CC ROAD AT SEMMENPATTAI MAIN ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7307,Roads,Completed,NH-ANNA NAGAR,103,534000,"PROVIDING THERMOPLASTIC COMPOUND AND REFLECTIVE PAVEMENT FOR SPEED BREAKERS AT VARIOUS STREET IN DIVISION-103, UNIT-23, ZONE-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/9699,Buildings,Completed,Q-Solid Waste Management,103,600000,"CONSTRUCTION OF BIO GAS PLANT AT AMMA UNAVAGAM ( TAYLORS ROAD ) IN DIVISION-103, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 BR/2017-18/11892,Road Cut,Completed,BR-Bus Route Roads,104,51000,"Restoration of Road cut made by CMWSSB at PURASAIWAKKAM HIGH ROAD in Dn-104, Zone-8.",Deposit Works,8,2017-18,2018-19 L/2017-18/1642,Electrical,Completed,L-Electrical,104,195000,WORK: Painting of 910 Nos and Numbering of lamp post in Dr.Alagappa road and various places in division 104 Zone - VIII area.,Own Sources,8,2017-18,2017-18 L/2017-18/1643,Electrical,Completed,L-Electrical,104,192000,"WORK: Laying of 533 Mtr of 2 X 16 Sqmm U.G.Cable at Parthasarathy street and Muthiyal street in Division-104, Zone - VIII area.",Own Sources,8,2017-18,2018-19 L/2017-18/1644,Electrical,Completed,L-Electrical,104,921300,"WORK: Replacement of 1799 Meters of 2 core X 16sqmm alu cable and 345 Meters of 4 core X 16sqmm alu cable at Sastri Nagar 1st to 11th street in division 104, under Zone-VIII area.",Own Sources,8,2017-18,2018-19 L/2017-18/1645,Electrical,Completed,L-Electrical,104,995800,"WORK: Replacement of 2347 Meters of 2 core X 16 sqmm alu cable in Pullapuram and EVR Lane in division 104, under Zone-VIII area",Own Sources,8,2017-18,2018-19 NH/2017-18/10158,Roads,Completed,NH-ANNA NAGAR,104,400000,"Improvements to the BT Road at Abirami Street in Division -104 ,unit-23,Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/10181,Roads,Completed,NH-ANNA NAGAR,104,454000,"Improvements to the BT Road at Menod Street in Division -104 ,unit-23,Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/10182,Roads,Completed,NH-ANNA NAGAR,104,1119000,"Improvements to BT Road at New Boopathy Nagar Main Road in Division -104 ,unit-23,Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/10183,Roads,Completed,NH-ANNA NAGAR,104,598000,"Improvements to BT Road at Potters Street in Division -104 ,unit-23,Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/10184,Roads,Completed,NH-ANNA NAGAR,104,1196000,"Improvements to BT Road at Sasthri Nagar Main road in Division -104 ,unit-23,Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/10185,Roads,Completed,NH-ANNA NAGAR,104,398000,"Improvements to BT Road at Gengu Reddy Subway Service Road (Western Side) in Division -104 ,unit-23,Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/1028,Road Cut,Completed,NH-ANNA NAGAR,104,643000,"IMPROVEMENTS TO B.T.ROAD AT MUTHIYAL (N) STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1029,Road Cut,Completed,NH-ANNA NAGAR,104,619000,"IMPROVEMENTS TO C.C.ROAD AT RATHINASAPABATHY STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1030,Road Cut,Completed,NH-ANNA NAGAR,104,413000,"IMPROVEMENTS TO C.C.ROAD AT PERUMAL STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1031,Roads,Completed,NH-ANNA NAGAR,104,240000,"IMPROVEMENTS TO C.C.ROAD AT VASUDEVAN STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1032,Roads,Completed,NH-ANNA NAGAR,104,310000,"IMPROVEMENTS TO C.C.ROAD AT PONNAPA 3RD LANE IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1149,Road Cut,Completed,NH-ANNA NAGAR,104,537000,"IMPROVEMENTS TO B.T.ROAD AT NANCY STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1150,Roads,Completed,NH-ANNA NAGAR,104,1135000,"IMPROVEMENTS TO C.C.ROAD AT SADASIVAM STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1151,Road Cut,Completed,NH-ANNA NAGAR,104,774000,"IMPROVEMENTS TO B.T.ROAD AT SUNDARAM LANE IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1152,Road Cut,Completed,NH-ANNA NAGAR,104,157000,"IMPROVEMENTS TO C.C.ROAD AT BAKATHAVATCHALAM LANE IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1153,Road Cut,Completed,NH-ANNA NAGAR,104,688000,"IMPROVEMENTS TO C.C.ROAD AT GRAMMA STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1154,Roads,Completed,NH-ANNA NAGAR,104,413000,"IMPROVEMENTS TO C.C.ROAD AT CHELLAPA STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1155,Road Cut,Completed,NH-ANNA NAGAR,104,841000,"IMPROVEMENTS TO B.T.ROAD AT OLD THANDAVARAYAN STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1156,Road Cut,Completed,NH-ANNA NAGAR,104,537000,"IMPROVEMENTS TO B.T.ROAD AT SOLAIAMMAN KOIL STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/1334,Buildings,Completed,Q-Solid Waste Management,104,1330000,"CONSTRUCTION OF COMPOST YARD AT OTTERI BURIAL GROUND IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/13456,Road Cut,Completed,NH-ANNA NAGAR,104,671000,"IMPROVEMENTS TO B.T.ROAD AT KRISHNAPPA STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14564,Roads,Completed,NH-ANNA NAGAR,104,364000,"IMPROVEMENTS TO C.C.ROAD AT PARTHASARATHY STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14565,Roads,Completed,NH-ANNA NAGAR,104,379000,"IMPROVEMENTS TO C.C.ROAD AT AUDIYAPPA LANE IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14566,Roads,Completed,NH-ANNA NAGAR,104,619000,"IMPROVEMENTS TO C.C.ROAD AT PULLAPURAM 3RD STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14572,Roads,Completed,NH-ANNA NAGAR,104,469000,"IMPROVEMENTS TO B.T .ROAD AT MUTHIYAL (C) STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/14573,Roads,Completed,NH-ANNA NAGAR,104,868000,"IMPROVEMENTS TO B.T .ROAD AT EVR 1ST LANE IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/14574,Roads,Completed,NH-ANNA NAGAR,104,971000,"IMPROVEMENTS TO B.T .ROAD AT SARAVANA PERUMAL STREET IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14575,Roads,Completed,NH-ANNA NAGAR,104,707000,"IMPROVEMENTS TO B.T .ROAD AT GANGADEESHWARAR LANE IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/14576,Roads,Completed,NH-ANNA NAGAR,104,712000,"IMPROVEMENTS TO B.T .ROAD AT SUBRAMANI STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/14577,Roads,Completed,NH-ANNA NAGAR,104,268000,"IMPROVEMENTS TO B.T .ROAD AT FLOWERS ROAD 4TH LANE IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/15720,Buildings,Completed,NH-ANNA NAGAR,104,166000,"REPAIR WORK TO DN OFFICE, AMMA UNAVAGAM, SWD AT VARIOUS PLACE IN DN -104, UNIT- 23, ZONE- 8.",Own Sources,8,2017-18,2017-18 NH/2017-18/16649,Buildings,Completed,NH-ANNA NAGAR,104,300000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIVISION-104,UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/16651,Buildings,Completed,NH-ANNA NAGAR,104,990000,"RESTORATION OF DAMAGE SCHOOLS (CMS) AT VARIOUS PLACES IN DIVISION-104,UNIT-23, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/16669,Storm Water Drain,Completed,NH-ANNA NAGAR,104,867000,"RESTORATION OF DAMAGE STORM WATER DRAIN AT VARIOUS PLACES IN DIVISION-104, UNIT-23,ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/2129,Roads,Completed,NH-ANNA NAGAR,104,350000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT VELLALA STREET 4TH LANE IN DN - 104, U-23, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/2130,Roads,Completed,NH-ANNA NAGAR,104,140000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT LAWDERS GATE 3RD LANE IN DN - 104, U -23 , Z - 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/3338,Buildings,Completed,NH-ANNA NAGAR,104,350000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT PONNAPA STREET 3RD LANE IN DN - 104, U-23, Z-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/3342,Buildings,Completed,NH-ANNA NAGAR,104,685000,"IMPROVEMENTS TO B.T .ROAD AT ARASAPPA STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/3460,Buildings,Completed,NH-ANNA NAGAR,104,665000,"IMPROVEMENTS TO B.T .ROAD AT PERUMAL 1ST STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/3607,Buildings,Completed,NH-ANNA NAGAR,104,192000,"IMPROVEMENTS TO B.T .ROAD AT PONNAN STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4069,Buildings,Completed,NH-ANNA NAGAR,104,1225000,REPAIRS AND IMPROVEMENT WORKS TO TPF ZONE -8 IN DN-104 UNIT-23 ZONE-8,Own Sources,8,2017-18,2018-19 NH/2017-18/6871,Roads,Completed,NH-ANNA NAGAR,104,665000,"IMPROVEMENTS TO B.T .ROAD AT PERUMAL 2ND STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/7304,Roads,Completed,NH-ANNA NAGAR,104,356000,"PROVIDING THERMOPLASTIC COMPOUND AND REFLECTIVE PAVEMENT FOR SPEED BREAKERS AT VARIOUS STREET IN DIVISION 104, UNIT - 23, ZONE 8",Own Sources,8,2017-18,2017-18 NH/2017-18/8684,Storm Water Drain,Completed,NH-ANNA NAGAR,104,1200000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREETS IN DN - 104, UNIT - 23, ZONE -8",Own Sources,8,2017-18,2017-18 NH/2017-18/8778,Storm Water Drain,Completed,NH-ANNA NAGAR,104,800000,"REPAIRS AND IMPROVEMENTS TO STROM WATER DRAIN AT VARIOUS STREETS IN DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2017-18,2017-18 NH/2017-18/8779,Buildings,Completed,NH-ANNA NAGAR,104,647000,"IMPROVEMENTS TO B.T .ROAD AT VEERASAMY STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/8781,Roads,Completed,NH-ANNA NAGAR,104,582000,"IMPROVEMENTS TO B.T .ROAD AT KANDAPPA STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/8782,Roads,Completed,NH-ANNA NAGAR,104,578000,"IMPROVEMENTS TO B.T .ROAD AT THANDAVAN STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/9231,Buildings,Completed,NH-ANNA NAGAR,104,117000,"PROVIDING IMPROVEMENTS WORK IN SMART CLASS LOCATED IN GANGADEESHWARAR HIGH SCHOOL AT DIVISION 104, UNIT 23, ZONE 8",Own Sources,8,2017-18,2018-19 NH/2017-18/9248,Roads,Completed,NH-ANNA NAGAR,104,371000,"IMPROVEMENTS TO B.T .ROAD AT THANDAVARAYAN STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/9702,Buildings,Completed,Q-Solid Waste Management,104,2022000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY CENTER WITH BASIC MACHINERIES IN OTTERI BURIAL GROUND DN 104, UNIT 23 , ZONE 8.",Own Sources,8,2017-18,2018-19 NH/2017-18/9740,Buildings,Completed,NH-ANNA NAGAR,104,1037000,"REPAIRS AND IMPROVEMENTS IN UPHC AT RATHINASAPABATHY STREET IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2017-18,2017-18 NH/2017-18/9928,Buildings,Completed,NH-ANNA NAGAR,104,261000,"ENGAGEMENT OF OPERATORS IN BIO METHANATION PLANT (ANNUALLY) IN OTTERY BURIAL GROUND IN DIVISION 104, UNIT 23, ZONE - 8.",Own Sources,8,2017-18,2018-19 B/2017-18/6840,Buildings,Completed,B-Buildings,105,999500,"ADDITIONAL ELECTRICAL WORKS TO THE EXISTING COMMUNITY CENTRE AT MMDA COLONY MAIN ROAD IN DN-105, ZONE-8",Own Sources,8,2017-18,2018-19 B/2017-18/7001,Buildings,Completed,B-Buildings,105,999900,ADDITIONAL WORKS TO THE EXISTING COMMUNITY CENTRE AT MMDA COLONY MAIN ROAD IN DN -105 ZONE - 8,Own Sources,8,2017-18,2019-20 BR/2017-18/11790,Footpath,Completed,BR-Bus Route Roads,105,4464000,"Forming Footpath at Vinayagapuram main Road in Dn-105, Zone-VIII",Grants,8,2017-18,2019-20 BR/2017-18/6938,Roads,Completed,BR-Bus Route Roads,105,930000,Repairs to the existing Modern stainless steel Bus Shelter at various bus route roads in Zone -4,Own Sources,8,2017-18,2018-19 BR/2017-18/6941,Roads,Completed,BR-Bus Route Roads,105,2300000,Proposed construction of Modern stainless steel Bus Shelter (2 Nos) at 100 ft road in Wheels India Bus Stop towards the direction Koyambedu to Redhills and Redhills to Koyambedu under the Padi flyover in Zone - 8 Under MP Scheme,MPLADS,8,2017-18,2019-20 BR/2017-18/6942,Roads,Completed,BR-Bus Route Roads,105,2097000,Proposed construction of 2 Nos Modern stainless steel Bus Shelter at Thirumangalam Bus Stop towards rountana and Rountana Bus Stop towards Thirumangalam in Zone - 8 Under MP Scheme,MPLADS,8,2017-18,2019-20 NH/2017-18/12831,Buildings,Completed,NH-ANNA NAGAR,105,152000,"REPAIR WORK TO MULTYPURPUS HALL, AMMA UNAVAGAM, DN OFFICE, SWD, SCHOOL IN DN 105 UNIT 22 ZONE 8",Own Sources,8,2017-18,2017-18 NH/2017-18/1320,Buildings,Completed,Q-Solid Waste Management,105,665000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT PERUMAL KOIL STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/16693,Buildings,Completed,NH-ANNA NAGAR,105,198000,"RESTORATION OF DAMAGE CMS AT VARIOUS PLACES IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/16695,Buildings,Completed,NH-ANNA NAGAR,105,197000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/16740,Storm Water Drain,Completed,NH-ANNA NAGAR,105,70000,"RESTORATION OF DAMAGE STORM WATER DRAIN AT VARIOUS PLACES IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/16744,Buildings,Completed,NH-ANNA NAGAR,105,200000,"RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/2215,Storm Water Drain,Completed,NH-ANNA NAGAR,105,999000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2017-18 NH/2017-18/2216,Storm Water Drain,Completed,NH-ANNA NAGAR,105,600000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2017-18 NH/2017-18/6184,Road Cut,Completed,NH-ANNA NAGAR,105,823000,"IMPROVEMENT TO THE BT ROAD AT DURAI PILLAI STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6185,Road Cut,Completed,NH-ANNA NAGAR,105,715000,"IMPROVEMENT TO THE BT ROAD AT MARIYAMMAN KOIL STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6186,Road Cut,Completed,NH-ANNA NAGAR,105,1610000,"IMPROVEMENT TO THE BT ROAD AT ASHOKA STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6187,Road Cut,Completed,NH-ANNA NAGAR,105,304000,"IMPROVEMENT TO THE BT ROAD AT SENTHIL NAGAR 4TH STREET (REACH 2) IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6188,Road Cut,Completed,NH-ANNA NAGAR,105,1677000,"IMPROVEMENT TO THE BT ROAD AT JAGANATHA NAGAR 1ST MAIN ROAD IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6189,Road Cut,Completed,NH-ANNA NAGAR,105,573000,"IMPROVEMENT TO THE BT ROAD AT SBI STAFF COLONY 1ST, 2ND, 4TH AND 6TH STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6190,Road Cut,Completed,NH-ANNA NAGAR,105,206000,"IMPROVEMENT TO THE CC ROAD AT THIRUKUMARAPURAM 4TH STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6191,Road Cut,Completed,NH-ANNA NAGAR,105,304000,"IMPROVEMENT TO THE BT ROAD AT SENTHIL NAGAR 4TH STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6192,Road Cut,Completed,NH-ANNA NAGAR,105,805000,"IMPROVEMENT TO THE BT ROAD AT PERIYAR PATHAI WEST IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6195,Road Cut,Completed,NH-ANNA NAGAR,105,172000,"IMPROVEMENT TO THE CC ROAD AT THIRUKUMARAPURAM 1ST STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6197,Road Cut,Completed,NH-ANNA NAGAR,105,206000,"IMPROVEMENT TO THE CC ROAD AT THIRUKUMARAPURAM 4TH STREET IN DN-105,U-22,Z-08",Own Sources,8,2017-18,2018-19 BR/2017-18/6943,Roads,Completed,BR-Bus Route Roads,106,920000,"Proposed construction of New modern stainless steel Bus Shelter of Size 6.0m x 2.5m at Garden Hotel Bus Stop at Purasawakkam High Road in Dn-104, Zone- 8 under MP Scheme",MPLADS,8,2017-18,2019-20 D/2017-18/4220,Storm Water Drain,Completed,D-Storm Water Drains,106,8756000,"Supplying,fixing and commissioning of booms to be laid at the 9 locations on the Coovam River in Chennai with suitable machinery for removing the accumulated garbage and other floating materials as directed by the Engineer - in - charge.",Own Sources,8,2017-18,2018-19 NH/2017-18/10099,Roads,Completed,NH-ANNA NAGAR,106,584000,"IMPROVEMENT TO THE BT ROAD AT AVVAIYAR STREET IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/10100,Roads,Completed,NH-ANNA NAGAR,106,480000,"IMPROVEMENT TO THE BT ROAD AT EAST MADA STREET IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/10101,Roads,Completed,NH-ANNA NAGAR,106,318000,"IMPROVEMENT TO THE BT ROAD AT YADHAVAL STREET IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/10102,Roads,Completed,NH-ANNA NAGAR,106,720000,"IMPROVEMENT TO THE BT ROAD AT SARANGAPANI STREET IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/10918,Buildings,Completed,NH-ANNA NAGAR,106,568000,"IMPROVEMENTS TO EXISTING AMMA UNAVAGAM (PHASE - 2) CONVERTED TO DISPANCERY AT REDDY AVENUE IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/10956,Buildings,Completed,NH-ANNA NAGAR,106,150000,"REPAIRS AND IMPROVEMENTS TO THE AMMA UNAVAGAM, ICDS BUILDINGS IN DN-106, UNIT-22, ZONE- 08",Own Sources,8,2017-18,2018-19 NH/2017-18/17686,Parks,Completed,NH-ANNA NAGAR,106,368000,"MAINTENANCE OF PARK AT METAL FACTORY ROAD FOR A PERIOD OF ONE YEAR IN DN-106, UNIT-22,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/2217,Storm Water Drain,Completed,NH-ANNA NAGAR,106,1180000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2017-18 NH/2017-18/2218,Storm Water Drain,Completed,NH-ANNA NAGAR,106,700000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2017-18 NH/2017-18/5972,Road Cut,Completed,NH-ANNA NAGAR,106,237000,"IMPROVEMENT TO THE BT ROAD AT RAILWAY COLONY 1ST STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/5973,Road Cut,Completed,NH-ANNA NAGAR,106,103000,"IMPROVEMENT TO THE BT ROAD AT RAILWAY COLONY 3RD STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/5975,Road Cut,Completed,NH-ANNA NAGAR,106,211000,"IMPROVEMENT TO THE BT ROAD AT GOVINDAN STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/5976,Road Cut,Completed,NH-ANNA NAGAR,106,528000,"IMPROVEMENT TO THE BT ROAD AT NAVANEETHAMMAL STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/5977,Road Cut,Completed,NH-ANNA NAGAR,106,335000,"IMPROVEMENT TO THE BT ROAD AT COLLECTORATE COLONY 4TH CROSS STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/5979,Road Cut,Completed,NH-ANNA NAGAR,106,644000,"IMPROVEMENT TO THE BT ROAD AT RAJARAM METHA NAGAR IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/5980,Road Cut,Completed,NH-ANNA NAGAR,106,329000,"IMPROVEMENT TO THE BT ROAD AT OFFICERS COLONY 4TH STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6109,Road Cut,Completed,NH-ANNA NAGAR,106,295000,"IMPROVEMENT TO THE CC ROAD AT M.H.COLONY 2ND MAIN ROAD IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6111,Road Cut,Completed,NH-ANNA NAGAR,106,220000,"IMPROVEMENT TO THE CC ROAD AT INDIRAGANDHI NAGAR 1ST STREET IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6112,Road Cut,Completed,NH-ANNA NAGAR,106,846000,"IMPROVEMENT TO THE CC ROAD AT M.H.COLONY 1ST MAIN ROAD IN DN-106,U-22,Z-08",Own Sources,8,2017-18,2018-19 NH/2017-18/6668,Roads,Completed,NH-ANNA NAGAR,106,316000,"PROVIDING AND LAYING SPEED BREAKERS AT VARIOUS STREET IN DN -106,U-22,Z-8.",Own Sources,8,2017-18,2017-18 NH/2017-18/9587,Parks,Completed,NH-ANNA NAGAR,106,168000,"MAINTENANCE FOR GREENERY AREA OF METAL FACTORY ROAD PARK (BY EMPLOYING QUALIFIED HORTICULTURIST) FOR A PERIOD OF ONE YEAR IN DN-106,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/9694,Buildings,Completed,Q-Solid Waste Management,106,600000,"Construction of Bio Gas Plant at Reddy avenue (AMMA UNAVAGAM) in Div-106, Unit-22, Zone-8",Own Sources,8,2017-18,2018-19 NH/2017-18/10114,Roads,Completed,NH-ANNA NAGAR,107,2923000,"IMPROVEMENTS TO THE BT ROAD AT PC HOSTEL ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/10115,Roads,Completed,NH-ANNA NAGAR,107,952000,"IMPROVEMENTS TO THE BT ROAD AT NATHAN STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/10117,Roads,Completed,NH-ANNA NAGAR,107,1352000,"IMPROVEMENTS TO THE BT ROAD AT SUBBARAYAN STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/10118,Roads,Completed,NH-ANNA NAGAR,107,748000,"IMPROVEMENTS TO THE BT ROAD AT KANDAN STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/10119,Roads,Completed,NH-ANNA NAGAR,107,396000,"IMPROVEMENTS TO THE BT ROAD AT MURUGASEN STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/10120,Roads,Completed,NH-ANNA NAGAR,107,1600000,"IMPROVEMENTS TO THE BT ROAD AT MC NICHOLAS ROAD (OLD ZONAL OFFICE) IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/11217,Buildings,Completed,NH-ANNA NAGAR,107,715000,"PROVIDING AMMA RESIDENTIAL SCHOOL INSIDE SUBBARAYAN SCHOOL CHS IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/13157,Roads,Completed,NH-ANNA NAGAR,107,150000,"REPAIR WORKS AT VARIOUS STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/1335,Buildings,Completed,Q-Solid Waste Management,107,665000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT VENKATCHALAPATHY STREET IN DIVISION-107,UNIT-23,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/14865,Roads,Completed,NH-ANNA NAGAR,107,542000,"IMPROVEMENTS TO THE BT ROAD AT MC NICHOLAS ROAD 2ND LANE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/16847,Buildings,Completed,NH-ANNA NAGAR,107,250000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/16901,Storm Water Drain,Completed,NH-ANNA NAGAR,107,275000,"RESTORATION OF DAMAGE STORM WATER DRAIN AT VARIOUS PLACES IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/16944,Buildings,Completed,NH-ANNA NAGAR,107,199000,"RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/16947,Buildings,Completed,NH-ANNA NAGAR,107,194000,"RESTORATION OF DAMAGE CHENNAI MIDDLE SCHOOL AT VARIOUS PLACES IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/16949,Buildings,Completed,NH-ANNA NAGAR,107,200000,"RESTORATION OF DAMAGE CHENNAI MIDDLE SCHOOL AT VARIOUS PLACES IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/17681,Parks,Completed,NH-ANNA NAGAR,107,609000,"MAINTENANCE OF PARK AT MAYOR RAMANATHAN SALAI FOR A PERIOD OF ONE YEAR IN DN-107,UNIT-23,ZONE-8",Own Sources,8,2017-18,2019-20 NH/2017-18/2194,Subway,Completed,NH-ANNA NAGAR,107,248000,"MAINTENANCE OF HARRINGTON ROAD SUBWAY ENGAGING OF WATCH MAN AND ELECTRICIAN FOR FOUR MONTHS IN DIVISION-107 UNIT-23, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/2232,Storm Water Drain,Completed,NH-ANNA NAGAR,107,500001,"REPAIRS AND IMPROVEMENTS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DN-107,U-23,Z-8",Own Sources,8,2017-18,2017-18 NH/2017-18/3013,Buildings,Completed,NH-ANNA NAGAR,107,538000,REPAIRS WORK TO NIGHT SHELTER AT SCHOOL ROAD IN DIVISION-107 UNIT-23 ZONE-08.,Own Sources,8,2017-18,2017-18 NH/2017-18/3032,Buildings,Completed,NH-ANNA NAGAR,107,325000,"REPAIRS WORK TO CAP IN DN-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/4796,Road Cut,Completed,NH-ANNA NAGAR,107,506000,"IMPROVEMENTS TO THE BT ROAD AT HARRINGTON ROAD 16th AVENUE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4797,Road Cut,Completed,NH-ANNA NAGAR,107,304000,"IMPROVEMENTS TO THE BT ROAD AT HARRINGTON ROAD 17th AVENUE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4798,Road Cut,Completed,NH-ANNA NAGAR,107,908000,"IMPROVEMENTS TO THE BT ROAD AT MUKTHA GARDEN IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4799,Road Cut,Completed,NH-ANNA NAGAR,107,506000,"IMPROVEMENTS TO THE BT ROAD AT LAMECH AVENUE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4800,Road Cut,Completed,NH-ANNA NAGAR,107,323000,"IMPROVEMENTS TO THE BT ROAD AT RAJAMMAL STREET (NORTH) IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4801,Road Cut,Completed,NH-ANNA NAGAR,107,196000,"IMPROVEMENTS TO THE BT ROAD AT KARUKATHAMMAN KOIL STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4802,Road Cut,Completed,NH-ANNA NAGAR,107,67000,"IMPROVEMENTS TO THE BT ROAD AT KARUKATHAMMAN KOIL STREET LANE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4803,Road Cut,Completed,NH-ANNA NAGAR,107,103000,"IMPROVEMENTS TO THE BT ROAD AT JAGANATHAPURAM 4th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4804,Road Cut,Completed,NH-ANNA NAGAR,107,516000,"IMPROVEMENTS TO THE CC ROAD AT M.S NAGAR 1st STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4805,Road Cut,Completed,NH-ANNA NAGAR,107,585000,"IMPROVEMENTS TO THE CC ROAD AT BRINDAVANAM NAGAR 3rd STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4806,Road Cut,Completed,NH-ANNA NAGAR,107,570000,"IMPROVEMENTS TO THE CC ROAD AT BRINDAVANAM NAGAR 4th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4807,Road Cut,Completed,NH-ANNA NAGAR,107,104000,"IMPROVEMENTS TO THE CC ROAD AT MANOHARAN LANE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4808,Road Cut,Completed,NH-ANNA NAGAR,107,447000,"IMPROVEMENTS TO THE CC ROAD AT V.R.R COLONY IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4809,Road Cut,Completed,NH-ANNA NAGAR,107,138000,"IMPROVEMENTS TO THE CC ROAD AT JAGANATHAPURAM 1st STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4810,Roads,Completed,NH-ANNA NAGAR,107,448000,"IMPROVEMENTS TO THE CC ROAD AT JAGANATHAPURAM 6th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4811,Roads,Completed,NH-ANNA NAGAR,107,448000,"IMPROVEMENTS TO THE CC ROAD AT JAGANATHAPURAM 5th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/4812,Roads,Completed,NH-ANNA NAGAR,107,840000,"IMPROVEMENTS TO THE CC ROAD AT DOSS PURAM IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/7319,Roads,Completed,NH-ANNA NAGAR,107,247000,"PROVIDING THERMOPLASTIC COMPOUND AND REFLECTIVE PAVEMENT FOR SPEED BREAKERS AT VARIOUS STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/7923,Storm Water Drain,Completed,NH-ANNA NAGAR,107,2400000,"CONSTRUCTION OF STORM WATER DRAIN AT MC NICHOLS ROAD 3rd LANE TO MC NICHOLS SERVICE ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/8140,Storm Water Drain,Completed,NH-ANNA NAGAR,107,1450000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2017-18 NH/2017-18/9193,Buildings,Completed,NH-ANNA NAGAR,107,112000,"PROVIDING IMPROVEMENTS WORK IN SMART CLASS LOCATED IN SUBBARAYAN SCHOOL (CHS) IN DIVISION-107, UNIT-23, ZONE-8",Own Sources,8,2017-18,2018-19 NH/2017-18/9606,Parks,Completed,NH-ANNA NAGAR,107,319000,"ANNUAL MAINTENANCE OF PARK AT MAYOR SATHYAMOORTHY SALAI IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/9681,Buildings,Completed,Q-Solid Waste Management,107,600000,"CONSTRUCTION OF BIO GAS PLANT AT MANGALAPURAM 16th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 NH/2017-18/9803,Buildings,Completed,NH-ANNA NAGAR,107,1200000,"PROPOSED URBAN PRIMARY HEALTH CENTER (SHIFTING FROM JAGANATHAPURAM 2nd STREET TO SCHOOL ROAD) IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2017-18,2018-19 BR/2017-18/11867,Footpath,Completed,BR-Bus Route Roads,108,3488000,"Forming Footpath at Ormes Road in Dn-103, Zone-VIII",Grants,8,2017-18,2019-20 NH/2017-18/10097,Roads,Completed,NH-ANNA NAGAR,108,2155000,"IMPROVEMENT TO THE BT ROAD AT ANDAVAR STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/11085,Storm Water Drain,Completed,NH-ANNA NAGAR,108,282500,"RESTORATION OF DAMAGE STORM WATER DRAIN AT VARIOUS PLACES IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/11089,Buildings,Completed,NH-ANNA NAGAR,108,315000,"RESTORATION OF DAMAGE CHENNAI HIGHER SECONDARY SCHOOL AT VARIOUS PLACES IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/11092,Buildings,Completed,NH-ANNA NAGAR,108,90000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/11093,Buildings,Completed,NH-ANNA NAGAR,108,41000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/11094,Buildings,Completed,NH-ANNA NAGAR,108,73000,REPAIR AND IMPROVEMENT TO O BLOCK AND N BLOCK SCHOOL AT BHAGATH SINGH STREET IN DN 108 UNIT 22 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/11095,Buildings,Completed,NH-ANNA NAGAR,108,47000,REPAIR AND IMPROVEMENT TO AMMA UNAVAGAM IN DN 108 UNIT 22 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/11096,Buildings,Completed,NH-ANNA NAGAR,108,29000,REPAIR AND IMPROVEMENT TO NNMP SHED IN DN 108 UNIT 22 ZONE 8,Own Sources,8,2017-18,2018-19 NH/2017-18/11945,Parks,Completed,NH-ANNA NAGAR,108,150000,"MAINTENANCE FOR GREENERY AREA FOR ONE YEAR OF MMDA COLONY R- BLOCK IN DN-108,UNIT-22,ZONE-08",Own Sources,8,2017-18,2018-19 NH/2017-18/17687,Parks,Completed,NH-ANNA NAGAR,108,377000,"MAINTENANCE OF PARK AT MMDA COLONY R BLOCK FOR A PERIOD OF ONE YEAR IN DN-108,UNIT-22,ZONE-8.",Own Sources,8,2017-18,2019-20 NH/2017-18/2205,Storm Water Drain,Completed,NH-ANNA NAGAR,108,1180000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-108,U-22,Z-08",Own Sources,8,2017-18,2017-18 NH/2017-18/2208,Storm Water Drain,Completed,NH-ANNA NAGAR,108,440000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT VARIOUS STREET IN DN-108,U-22,Z-08",Own Sources,8,2017-18,2017-18 NH/2017-18/5652,Road Cut,Completed,NH-ANNA NAGAR,108,268000,"IMPROVEMENT TO THE BT ROAD AT BRINDAVAN COLONY IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/5655,Road Cut,Completed,NH-ANNA NAGAR,108,506000,"IMPROVEMENT TO THE BT ROAD AT KASTURIBAI STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/5656,Road Cut,Completed,NH-ANNA NAGAR,108,511000,"IMPROVEMENT TO THE BT ROAD AT KAMARAJAR NAGAR 1ST STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/5657,Road Cut,Completed,NH-ANNA NAGAR,108,502000,"IMPROVEMENT TO THE BT ROAD AT KAMARAJAR NAGAR 2ND STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/5659,Road Cut,Completed,NH-ANNA NAGAR,108,289000,"IMPROVEMENT TO THE CC ROAD AT J.D. DURAIRAJ 1ST STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/5661,Road Cut,Completed,NH-ANNA NAGAR,108,2232000,"IMPROVEMENT TO THE BT ROAD AT GANDHI ROAD IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/5664,Road Cut,Completed,NH-ANNA NAGAR,108,138000,"IMPROVEMENT S TO THE CC ROAD AT (MMDA COLONY Q BLOCK) KANNADASEN STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2017-18,2018-19 NH/2017-18/7624,Roads,Completed,NH-ANNA NAGAR,108,324000,"PROVIDING AND LAYING SPEED BREAKERS AT VARIOUS STREET IN DN -108,U-22,Z-8.",Own Sources,8,2017-18,2018-19 BR/2017-18/15926,Roads,Completed,BR-Bus Route Roads,109,179000,"Repairs to damaged surface at Nungambakkam Subway in Dn - 109, Zone - XI",Own Sources,9,2017-18,2018-19 NJ/2017-18/1014,Road Cut,Completed,NJ-TEYNAMPET,109,300000,"IMPROVEMENTS TO INTERRIOR ROAD AT CANAL BUNK ROAD IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/1015,Roads,Completed,NJ-TEYNAMPET,109,543000,"IMPROMENTS TO INTERRIOR ROAD AT PERIYAR PATHAI IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/1023,Road Cut,Completed,NJ-TEYNAMPET,109,385000,"IMPROVEMENTS TO INTERRIOR ROAD AT THIRU.VI.KA.COLONY 1ST STREET IN DN-109,UNIT-24,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/1024,Road Cut,Completed,NJ-TEYNAMPET,109,387000,"IMPROVEMENTS TO INTERRIOR ROAD AT THIRU,VI.KA.COLONY 2ND STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/1025,Road Cut,Completed,NJ-TEYNAMPET,109,490000,"IMPROVEMENTS TO INTRRIOR ROAD AT THIRU,VI,KA,COLONY 3RD STREET IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/1026,Road Cut,Completed,NJ-TEYNAMPET,109,96000,"IMPROVEMENTS TO INTERRIOR ROAD AT VANIAR LANE IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/16011,Buildings,Completed,NJ-TEYNAMPET,109,235000,"REPAIRS AND IMPROVEMENTS WORKS TO CHENNAI PRIMARY SCHOOL AT NAMACHIVAYAPURAM IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/3909,Parks,Completed,NJ-TEYNAMPET,109,125000,"ANNUAL MAINTENECE OF GILL NAGAR PARK (6 MONTHS) AT GILL NAGAR CENTRAL SCHOOL ROAD IN DIVISION-109, UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5708,Road Cut,Completed,NJ-TEYNAMPET,109,1610000,"IMPROVEMENTS TO INTERRIOR ROAD AT THIRUVENGADAPURAM MAIN ROAD IN DIVISION-109, UNIT-24, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8368,Storm Water Drain,Completed,NJ-TEYNAMPET,109,96000,"Desilting for storm water drain at Nelson Manickam Road (Both Side) in division-109,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8372,Storm Water Drain,Completed,NJ-TEYNAMPET,109,32000,"Desilting for storm water drain at Thiruvenkatapuram Main road in division-109,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8383,Storm Water Drain,Completed,NJ-TEYNAMPET,109,61000,"Desilting for storm water drain at Abdullaha street in division-109,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8387,Storm Water Drain,Completed,NJ-TEYNAMPET,109,40000,"Desilting for storm water drain at Abith Nagar in division-109,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8392,Storm Water Drain,Completed,NJ-TEYNAMPET,109,71000,"Desilting for storm water drain at Shanmuganar Salai in division-109,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/9322,Storm Water Drain,Completed,NJ-TEYNAMPET,109,163000,"REPAIRS OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-109,UNIT-24, ZONE-09",Own Sources,9,2017-18,2017-18 B/2017-18/15576,Buildings,Completed,B-Buildings,110,887000,"Supplying and fixing of Two seater bench cum tables for propsed smart classes in CGHSS Nungampakkam in DN 110 Zone 9, CHSS Alwarpet in DN 123 Zone 9, CHSS Puliyur in DN 133 Zone 10 and CHSS M.G.R.nagar in DN 138 Zone 10",Own Sources,9,2017-18,2018-19 BR/2017-18/10920,Roads,Completed,BR-Bus Route Roads,110,990000,"ATTENDING REPAIR WORKS TO EXISTING CENTRE MEDIAN,FOOTPATH AND OTHER TRAFFIC IMPROVEMENT WORKS IN SANTHOME HIGH ROAD AND DGS DINAKARAN SALAI IN ZONE-09",Own Sources,9,2017-18,2018-19 BR/2017-18/2072,Road Cut,Completed,BR-Bus Route Roads,110,735000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 12 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 NJ/2017-18/10585,Buildings,Completed,B-Buildings,110,313000,"CONVERSION OF OLD CLASS ROOM INTO SMART CLASS ROOM AT CHENNAI GIRLS HIR.SEC. SCHOOL AT SCHOOL ROAD IN DN 110,UNIT 24.ZONE 9",SMART CITY - BUILDINGS,9,2017-18,2018-19 NJ/2017-18/11411,Buildings,Completed,NJ-TEYNAMPET,110,658000,"PROVIDING OF R.O.PLANT ROOM AND WATER SUPPLY ARRANGEMENTS AT CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT SCHOOL ROAD IN DIVISION 110,UNIT 24,ZONE 9",MLACDS,9,2017-18,2018-19 NJ/2017-18/1204,Buildings,Completed,NJ-TEYNAMPET,110,990000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT VALLUVAR KOTTAM MAIN ROAD (KUZHAKKARAI ROAD) IN DIV-110,U-24,Z-09",Own Sources,9,2017-18,2019-20 NJ/2017-18/14714,Roads,Completed,NJ-TEYNAMPET,110,524000,"Improvements to the Interier B.T. Road at Seethanagr 1st Street IN Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14715,Roads,Completed,NJ-TEYNAMPET,110,393000,"Improvements to the Interier B.T. Road at Seetha Nagar 2nd Street IN Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14739,Roads,Completed,NJ-TEYNAMPET,110,248000,"Improvements to the Interier B.T. Road at Ponnangipuram 1st Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14741,Roads,Completed,NJ-TEYNAMPET,110,188000,"Improvements to the Interier B.T. Road at Ponnangipuram 2nd Street IN Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14743,Roads,Completed,NJ-TEYNAMPET,110,784000,"Improvements to the Interier B.T. Road at Jayalakshmipuram 1st Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14744,Roads,Completed,NJ-TEYNAMPET,110,572000,"Improvements to the Interier B.T. Road at Lake Area 4th Cross Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14745,Roads,Completed,NJ-TEYNAMPET,110,671000,"Improvements to the Interier B.T. Road at Lake Area 5th Cross Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14746,Roads,Completed,NJ-TEYNAMPET,110,835000,"Improvements to the Interier B.T. Road at Avnue Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14747,Roads,Completed,NJ-TEYNAMPET,110,671000,"Improvements to the Interier B.T. Road at Lakshmanan Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14750,Roads,Completed,NJ-TEYNAMPET,110,604000,"Improvements to the Interier B.T. Road at Ramanathan Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14752,Roads,Completed,NJ-TEYNAMPET,110,771000,"Improvements to the Interier B.T. Road at Mayor Shiva Shanmugam Salai in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14753,Roads,Completed,NJ-TEYNAMPET,110,604000,"Improvements to the Interier B.T. Road at Jayalakshmipuram Main Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14754,Roads,Completed,NJ-TEYNAMPET,110,838000,"Improvements to the Interier B.T. Road at Lake Area Main Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14755,Roads,Completed,NJ-TEYNAMPET,110,671000,"Improvements to the Interier B.T. Road at Lake Area 4th Main Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14756,Roads,Completed,NJ-TEYNAMPET,110,402000,"Improvements to the Interier B.T. Road at Lake Area 6th Cross Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14757,Roads,Completed,NJ-TEYNAMPET,110,503000,"Improvements to the Interier B.T. Road at Lake Area 3rd Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14759,Roads,Completed,NJ-TEYNAMPET,110,503000,"Improvements to the Interier B.T. Road at Lake Area 2nd Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14760,Roads,Completed,NJ-TEYNAMPET,110,671000,"Improvements to the Interier B.T. Road at Lake Area 5th Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14761,Roads,Completed,NJ-TEYNAMPET,110,503000,"Improvements to the Interier B.T. Road at Lake Area 1st Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14762,Roads,Completed,NJ-TEYNAMPET,110,1174000,"Improvements to the Interier B.T. Road at Kamdha Nagar 1st Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14763,Roads,Completed,NJ-TEYNAMPET,110,1509000,"Improvements to the Interier B.T. Road at Madhavan Nair Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14764,Roads,Completed,NJ-TEYNAMPET,110,805000,"Improvements to the Interier B.T. Road at Sir Madhava Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14765,Roads,Completed,NJ-TEYNAMPET,110,1107000,"Improvements to the Interier B.T. Road at Kothari Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14766,Roads,Completed,NJ-TEYNAMPET,110,1442000,"Improvements to the Interier B.T. Road at Sterling 1st Cross Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14767,Roads,Completed,NJ-TEYNAMPET,110,402000,"Improvements to the Interier B.T. Road at Streling 2nd Cross Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14768,Roads,Completed,NJ-TEYNAMPET,110,1006000,"Improvements to the Interier B.T. Road at Streling 3rd Cross Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14769,Roads,Completed,NJ-TEYNAMPET,110,235000,"Improvements to the Interier B.T. Road at Streling 4th Cross Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14771,Roads,Completed,NJ-TEYNAMPET,110,1509000,"Improvements to the Interier B.T. Road at 70' Scheme Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14772,Roads,Completed,NJ-TEYNAMPET,110,905000,"Improvements to the Interier B.T. Road at Pushpa Nagar Main Road in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14774,Roads,Completed,NJ-TEYNAMPET,110,413000,"Improvements to the Interier C.C. Road at Rajaji 3rd Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14775,Roads,Completed,NJ-TEYNAMPET,110,1135000,"Improvements to the Interier C.C. Road at Kutty Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14776,Roads,Completed,NJ-TEYNAMPET,110,1479000,"Improvements to the Interier C.C. Road at Rajaji North Street in Div - 110 , Unit - 24 , Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/15968,Buildings,Completed,NJ-TEYNAMPET,110,917000,"CONSTRUCTION OF COMPOUND WALL EASTERN SIDE AT CHENNAI GIRLS HIGHER SEC SCHOOL AT SCHOOL ROAD(UNDER MLA FUND 2017-2018) IN DN 110,UNIT 24,ZONE 9",MLACDS,9,2017-18,2018-19 NJ/2017-18/15970,Buildings,Completed,NJ-TEYNAMPET,110,1083000,"CONSTRUCTION OF COMPOUND WALL NORTHERN SIDE AND PROVIDING NEW BORE WELL AT CHENNAI GIRLS HIGHER SEC. SCHOOL AT SCHOOL ROAD( UNDER MLA FUND 2017-2018) IN DN 110,UNIT 24,ZONE 9",MLACDS,9,2017-18,2018-19 NJ/2017-18/16587,Buildings,Completed,NJ-TEYNAMPET,110,595000,"Supply and Erection of 500 LPH RO Plant At Pushpa Nagar Health post in DN-110, U-24, Z-09.",MLACDS,9,2017-18,2018-19 NJ/2017-18/16588,Buildings,Completed,NJ-TEYNAMPET,110,595000,"Supply and Erection of 500 LPH RO Plant At Chennai Primary School (Kamdar Nagar) School Road, in DN-110, U-24, Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/16589,Buildings,Completed,NJ-TEYNAMPET,110,595000,"Supply and Erection of 500 LPH RO Plant At Chennai Middle School (Kutty Street), Jayalakshmipuram main road in DN-110, U-24, Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/16591,Buildings,Completed,NJ-TEYNAMPET,110,525000,"Supply and Erection of 250 LPH RO Plant At Dispansary Appa Swamy Street in DN-110, U-24, Z-9",MLACDS,9,2017-18,2018-19 NJ/2017-18/17335,Buildings,Completed,NJ-TEYNAMPET,110,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT VALLUVAR KOTTAM MAIN ROAD (KUZHAKKARAI ROAD) IN DIV-110,U-24,Z-09",Own Sources,9,2017-18,2019-20 NJ/2017-18/17974,Buildings,Completed,P-Parks and Playfields,110,1381000,TREE PLANTATION - ZONE -IX,Own Sources,9,2017-18,2019-20 NJ/2017-18/3966,Parks,Completed,NJ-TEYNAMPET,110,193000,"ANNUAL MAINTANANCE OF INDEPENDENCE DAY PARK AT SCHOOL ROAD FOR (6 MONTHS) IN DIVISION-110, UNIT-24, ZONE-IX.",Own Sources,9,2017-18,2018-19 NJ/2017-18/3968,Parks,Completed,NJ-TEYNAMPET,110,138000,"ANNUAL MAINTANANCE OF ANNA PARK AT VALLUVATR KOTTAM HIGH ROAD FOR (6 MONTHS) IN DIVISION-110, UNIT-24,ZONE-IX.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8507,Storm Water Drain,Completed,NJ-TEYNAMPET,110,45000,"DESILTING FOR STORM WATER DRAIN AT KAMDAR NAGAR 1st STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8537,Storm Water Drain,Completed,NJ-TEYNAMPET,110,108000,"DESILTING FOR STORM WATER DRAIN AT MAHALINGAPURAM MAIN ROAD IN DIVISION - 110, UNIT-24, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8538,Storm Water Drain,Completed,NJ-TEYNAMPET,110,96000,"DESILTING FOR STORM WATER DRAIN AT VALLUVAR KOTTAM HIGH ROAD IN DIVISION - 110,UNIT - 24, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8539,Storm Water Drain,Completed,NJ-TEYNAMPET,110,38000,"DESILTING FOR STORM WATER DRAIN AT SEETHA NAGAR MAIN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8540,Storm Water Drain,Completed,NJ-TEYNAMPET,110,99000,"DESILTING FOR STORM WATER DRAIN AT KAMARAJAPURAM MAIN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8541,Storm Water Drain,Completed,NJ-TEYNAMPET,110,45000,"DESILTING FOR STORM WATER DRAIN AT KAMARAJAPURAM 1st STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8544,Storm Water Drain,Completed,NJ-TEYNAMPET,110,38000,"DESILTING FOR STORM WATER DRAIN AT PONNAGIPURAM MAIN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8664,Storm Water Drain,Completed,NJ-TEYNAMPET,110,44000,"DESILTING FOR STORM WATER DRAIN AT SCHOOL ROAD 1st & 2nd STREETS IN DIVISION-110,UNIT-24, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8668,Storm Water Drain,Completed,NJ-TEYNAMPET,110,73000,"DESILTING FOR STORM WATER DRAIN AT SCHOOL ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8672,Storm Water Drain,Completed,NJ-TEYNAMPET,110,39000,"DESILTING FOR STORM WATER DRAIN AT VAIGUNDAPURAM 1st & 2nd STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8674,Storm Water Drain,Completed,NJ-TEYNAMPET,110,31000,"DESILTING FOR STORM WATER DRAIN AT JAYALAKSHMIPURAM 1st & 3rd STREET IN DIVISION-110,UNIT-24, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9327,Storm Water Drain,Completed,NJ-TEYNAMPET,110,228000,"REPAIRS OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-110,UNIT-24, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9786,Roads,Completed,NJ-TEYNAMPET,110,997000,RELAYING OF ROAD WITH BCCMP 40 MM THICK AT KAMDAR NAGAR 2 ND STREET (UNDER MLA FUND) IN DIVISION 110 UNIT 24 ZONE 09,MLACDS,9,2017-18,2018-19 NJ/2017-18/9787,Roads,Completed,NJ-TEYNAMPET,110,647000,RELAYING OF ROAD WITH BCCMP 40 MM THICK AT SEETA NAGAR 3RD STREET (UNDER MLA FUND) IN DIVISION 110 UNIT 24 ZONE 09,MLACDS,9,2017-18,2018-19 NJ/2017-18/9789,Roads,Completed,NJ-TEYNAMPET,110,682000,"RELAYING OF ROAD WITH BCCMP 40MM THICK AT KAMDARNAGAR MAIN ROAD (UNDER MLA FUND) IN DIVISION-110,UNIT-24,ZONE-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/9790,Roads,Completed,NJ-TEYNAMPET,110,684000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT KAMARAJAR PURAM MAIN ROAD (UNDER MLA FUND) IN DIVISION-110,UNIT-24,ZONE-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/9791,Roads,Completed,NJ-TEYNAMPET,110,1338000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT KAMARAJARPURAM 1 ST STREET IN DIVISION-110,UNIT-24,ZONE-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/9792,Roads,Completed,NJ-TEYNAMPET,110,1368000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT KAMDAR NAGAR 1 ST STREET (UNDER MLA FUND) IN DIVISION-110,UNIT-24,ZONE-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/9793,Roads,Completed,NJ-TEYNAMPET,110,1000000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT PONNANGIPURAM MAIN ROAD STREET (UNDER MLA FUND) IN DIVISION-110,UNIT-24,ZONE-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/9794,Roads,Completed,NJ-TEYNAMPET,110,1000000,"RELAYING OF ROAD WITH BCCMP 40 MM KAMARAJAR PURAM 2 ND SSTREET (UNDER MLA FUND) IN DIVISION-110,UNIT-24,ZONE-09",MLACDS,9,2017-18,2018-19 BR/2017-18/11872,Footpath,Completed,BR-Bus Route Roads,111,4185000,"Forming Footpath at Woods Road from G.P.Road to Bharathi salai junction in Dn-111, Zone-IX",Grants,9,2017-18,2019-20 BR/2017-18/11889,Road Cut,Completed,BR-Bus Route Roads,111,33500,"Restration of Road cut made by CMWSSB at CATHEDRAL ROAD in Dn-111, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/13614,Roads,Completed,BR-Bus Route Roads,111,705000,Restoration of Roadcut made by TANGEDCO at Greams Road in Dn-111 Zone-9 (Challan No.BR/2017-18/0019741),Deposit Works,9,2017-18,2019-20 BR/2017-18/17051,Road Cut,Completed,BR-Bus Route Roads,111,2225000,Restoration of road cut made by OFC company (Reliance JIO) at Bus Route Roads and Interior Roads in Zone - VIII,Deposit Works,9,2017-18,2018-19 NJ/2017-18/0245,Road Cut,Completed,NJ-TEYNAMPET,111,1490000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT MODEL SCHOOL ROAD IN DIVISION 111 UNIT 24 ZONE 09,Deposit Works,9,2017-18,2017-18 NJ/2017-18/11879,Roads,Completed,NJ-TEYNAMPET,111,1900000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT MODEL SCHOOL ROAD FROM JN OF ANNA SALAI TO GHULAM ABBAS ALI KHAN 10TH STREET IN DIVISION-111,UNIT-24, ZONE-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/11938,Parks,Completed,NJ-TEYNAMPET,111,810000,"PROVIDING AND FIXING OF WELD MESH GRILL WORK AROUND PILLARS UNDER PETERS ROAD FLY OVER BRIDGE IN DIVISION-111, UNIT-24, ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13212,Storm Water Drain,Completed,NJ-TEYNAMPET,111,1900000,"CONSTRUCTION OF STORM WATER DRAIN SIZE : 900 X 900mm [REACH-I] AT GOAPLAPURAM 2nd STREET (From Avvai shanmugam salai To Gopalapuram 3rd street) IN DIVISION-111,UNIT-24,ZONE-09.",MLACDS,9,2017-18,2018-19 NJ/2017-18/13216,Roads,Completed,NJ-TEYNAMPET,111,1940000,"RELAYING OF ROAD WITH BCCMP 40 MM THICK AT MODEL SCHOOL ROAD FROM JN OF GHULAM ABBAS ALI KHAN 10TH STREET UPTO SATHIK MOHAMED ROAD IN DIVISION-111,UNIT-24, ZONE-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/13223,Storm Water Drain,Completed,NJ-TEYNAMPET,111,1370000,"CONSTRUCTION OF STORM WATER DRAIN SIZE : 900 X 900mm [REACH-II] AT GOAPLAPURAM 2nd STREET (From Gopalapuram 3rd street To Gopalapuram 4th street ) IN DIVISION-111,UNIT-24,ZONE-09.",MLACDS,9,2017-18,2018-19 NJ/2017-18/14002,Roads,Completed,NJ-TEYNAMPET,111,988000,"Improvement to the Interior B.T. Road at Gopalapuram I street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14003,Roads,Completed,NJ-TEYNAMPET,111,297000,"Improvement to the Interior B.T. Road at Gopalapuram IV street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14004,Roads,Completed,NJ-TEYNAMPET,111,530000,"Improvement to the Interior B.T. Road at Begum sahib street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14005,Roads,Completed,NJ-TEYNAMPET,111,295000,"Improvement to the Interior B.T. Road Gulam Abbas Alikhan Bhagadur street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14006,Roads,Completed,NJ-TEYNAMPET,111,946000,"Improvement to the Interior B.T. Road Nungambakkam IV lane in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14007,Roads,Completed,NJ-TEYNAMPET,111,1228000,"Improvement to the Interior B.T. Road Wallace garden II street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14008,Roads,Completed,NJ-TEYNAMPET,111,423000,"Improvement to the Interior B.T. Road Gopalapuram VIII th street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14010,Roads,Completed,NJ-TEYNAMPET,111,671000,"Improvement to the Interior B.T. Road Smith Lane in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14011,Roads,Completed,NJ-TEYNAMPET,111,369000,"Improvement to the Interior B.T. Road Ganesh Street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14012,Roads,Completed,NJ-TEYNAMPET,111,738000,"Improvement to the Interior B.T. Road GAA khan 9th street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14013,Roads,Completed,NJ-TEYNAMPET,111,671000,"Improvement to the Interior B.T. Road GAA khan 10th street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14014,Roads,Completed,NJ-TEYNAMPET,111,838000,"Improvement to the Interior B.T. Road Subbarao avenue 1st street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14015,Roads,Completed,NJ-TEYNAMPET,111,268000,"Improvement to the Interior B.T. Road Subbarao avenue 2nd street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14016,Roads,Completed,NJ-TEYNAMPET,111,436000,"Improvement to the Interior B.T. Road Subbarao avenue 3rd street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14017,Roads,Completed,NJ-TEYNAMPET,111,1341000,"Improvement to the Interior B.T. Road Pycrafts garden in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14018,Roads,Completed,NJ-TEYNAMPET,111,402000,"Improvement to the Interior B.T. Road College lane in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14019,Roads,Completed,NJ-TEYNAMPET,111,1174000,"Improvement to the Interior B.T. Road Haddows 1st and 2nd road in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14020,Roads,Completed,NJ-TEYNAMPET,111,2012000,"Improvement to the Interior B.T. Road Rutland gate 5th and 4th street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14021,Roads,Completed,NJ-TEYNAMPET,111,1408000,"Improvement to the Interior B.T. Road Padmavathiyar road in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14023,Roads,Completed,NJ-TEYNAMPET,111,1107000,"Improvement to the Interior B.T. Road Aziz mulk 3rd street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14024,Roads,Completed,NJ-TEYNAMPET,111,402000,"Improvement to the Interior B.T. Road Aziz mulk 4TH street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14025,Roads,Completed,NJ-TEYNAMPET,111,1174000,"Improvement to the Interior B.T. Road Aziz mulk 1st street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14026,Roads,Completed,NJ-TEYNAMPET,111,604000,"Improvement to the Interior B.T. Road Rutland gate 6th street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14027,Roads,Completed,NJ-TEYNAMPET,111,2012000,"Improvement to the Interior B.T. Road Anderson road in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14029,Roads,Completed,NJ-TEYNAMPET,111,241000,"Improvement to the Interior C.C Road Aziz mulk 7TH street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14030,Roads,Completed,NJ-TEYNAMPET,111,344000,"Improvement to the Interior C.C Road GAA khan 2nd street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14031,Roads,Completed,NJ-TEYNAMPET,111,619000,"Improvement to the Interior C.C Road Aziz mulk 5TH street in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14032,Roads,Completed,NJ-TEYNAMPET,111,138000,"Improvement to the Interior C.C Road AAziz mulk 1st Lane in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14033,Roads,Completed,NJ-TEYNAMPET,111,3518000,"Improvement to the Interior C.C Road Suthanthira Nagar in Div-111,Unit-24,Zone ?9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14102,Storm Water Drain,Completed,NJ-TEYNAMPET,111,2210000,"CONSTRUCTION OF STORM WATER DRAIN OF SIZE 900MM X 900MM AT GOPALAPURAM 1ST STREET REACH 1 FROM AVVAISHUNMUGAM SALAI TO GOPALAPURAM 3RD STREET(UNDER MLA FUND 2017-2018) IN DN 111,UNIT 24,ZONE 9",MLACDS,9,2017-18,2018-19 NJ/2017-18/14106,Storm Water Drain,Completed,NJ-TEYNAMPET,111,2290000,"CONSTRUCTION OF STORM WATER DRAIN OF SIZE 900MMX900MM AT GOPALAPURAM 1ST STREET REACH 2 FROM GOPALAPURAM 3RD STREET TO GOPALAPURAM 5TH STREET(UNDER MLA FUND 2017-2018) IN DN 111,UNIT 24,ZONE 9",MLACDS,9,2017-18,2019-20 NJ/2017-18/16594,Buildings,Completed,NJ-TEYNAMPET,111,595000,"Supply and Erection of 500 LPH RO Plant At Dispensary Model School Road in DN-111, U-24, Z-9",MLACDS,9,2017-18,2018-19 NJ/2017-18/16609,Buildings,Completed,NJ-TEYNAMPET,111,595000,"Supply and Erection of 500 LPH RO Plant At Chennai High School Model School Road in DN-111, U-24, Z-9",MLACDS,9,2017-18,2018-19 NJ/2017-18/1944,Buildings,Completed,NJ-TEYNAMPET,111,410000,DISMANTLING OLD CLASS ROOM BUILDING IN CHENNAI HIGH SCHOOL AT MODEL SCHOOL ROAD IN DIVISION 111 UNIT 24 ZONE 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/3969,Parks,Completed,NJ-TEYNAMPET,111,131000,"ANNUAL MAINTANANCE OF HARRINGTON ROAD PARK AT HARRINGTON ROAD FOR (6 MONTHS) IN DIVISION-110, UNIT-24,ZONE-IX.",Own Sources,9,2017-18,2018-19 NJ/2017-18/3972,Parks,Completed,NJ-TEYNAMPET,111,238000,"ANNUAL MAINTENECE OF SPENCER PLAZA PARK AT BINNY SALAI SPENCER PLAZA (6 MONTHS) IN DIVISION-111, UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/3976,Parks,Completed,NJ-TEYNAMPET,111,215000,"ANNUAL MAINTENANCE OF PARK AT COLLAGE LANE PARK (6 MONTHS) IN DIVISION - 111, UNIT-24, ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8687,Storm Water Drain,Completed,NJ-TEYNAMPET,111,86000,"DESILTING FOR STORM WATER DRAIN GOPALAPURAM 1st STREET (East & West) AT IN DIVISION - 111, UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8689,Storm Water Drain,Completed,NJ-TEYNAMPET,111,30000,"DESILTING FOR STORM WATER DRAIN AT GOPALAPURAM 1st STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8690,Storm Water Drain,Completed,NJ-TEYNAMPET,111,58000,"DESILTING FOR STORM WATER DRAIN AT GOPALAPURAM 2nd &3rd STREET IN DIVISION-111,UNIT-24, ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8691,Storm Water Drain,Completed,NJ-TEYNAMPET,111,25000,"DESILTING FOR STORM WATER DRAIN AT AVVAI SHANMUGAM SALAI IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8692,Storm Water Drain,Completed,NJ-TEYNAMPET,111,35000,"DESILTING FOR STORM WATER DRAIN AT ELLARI STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8693,Storm Water Drain,Completed,NJ-TEYNAMPET,111,184000,"DESILTING FOR STORM WATER DRAIN AT ANNA SALAI IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8694,Storm Water Drain,Completed,NJ-TEYNAMPET,111,72000,"DESILTING FOR STORM WATER DRAIN AT PATTULAS ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8695,Storm Water Drain,Completed,NJ-TEYNAMPET,111,25000,"DESILTING FOR STORM WATER DRAIN AT CONRONSMITH ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8697,Storm Water Drain,Completed,NJ-TEYNAMPET,111,22000,"DESILTING FOR STORM WATER DRAIN AT WEST END STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8698,Storm Water Drain,Completed,NJ-TEYNAMPET,111,43000,"DESILTING FOR STORM WATER DRAIN AT MODEL SCHOOL ROAD (PART-I) IN DIVISION-111,UNIT - 24, ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8701,Storm Water Drain,Completed,NJ-TEYNAMPET,111,74000,"DESILTING FOR STORM WATER DRAIN AT COLLAGE ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8703,Storm Water Drain,Completed,NJ-TEYNAMPET,111,79000,"DESILTING FOR STORM WATER DRAIN AT GREEMS ROAD (East & West) IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8704,Storm Water Drain,Completed,NJ-TEYNAMPET,111,120000,"DESILTING FOR STORM WATER DRAIN AT WHITES ROAD (South & North) IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/9470,Storm Water Drain,Completed,NJ-TEYNAMPET,111,364000,"REPAIRS TO STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9785,Roads,Completed,NJ-TEYNAMPET,111,1660000,PROPOSED FORMING AND RELAYING OF BT ROAD AT ELLARI STREET (UNDER MLA FUND) IN DIVISION 111 UNIT 24 ZONE 09,MLACDS,9,2017-18,2018-19 BR/2017-18/1856,Road Cut,Completed,BR-Bus Route Roads,112,360000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 7 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/3090,Road Cut,Completed,BR-Bus Route Roads,112,349000,Restoration of Roadcut made by AIRTEL at Various Bus Route Roads ( 7 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/3193,Road Cut,Completed,BR-Bus Route Roads,112,25900,Restoration of Roadcut made by AIRTEL at Interior Road ( 1 Road) in Zone -9,Deposit Works,9,2017-18,2018-19 NJ/2017-18/14129,Roads,Completed,NJ-TEYNAMPET,112,860000,"IMPROVEMENTS TO INTERIOR CC ROAD AT TRUSTPURAM 4th CROSS STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14134,Roads,Completed,NJ-TEYNAMPET,112,625000,"IMPROVEMENTS TO INTERIOR ROAD AT SOWRASHTRA NAGAR CROS STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14135,Roads,Completed,NJ-TEYNAMPET,112,405000,"IMPROVEMENTS TO INTERIOR ROAD AT SOWRASHTRA NAGAR 7th STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14136,Roads,Completed,NJ-TEYNAMPET,112,450000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT SOWRASHTRA NAGAR 1ST STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14137,Roads,Completed,NJ-TEYNAMPET,112,516000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT NEHRU STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14138,Roads,Completed,NJ-TEYNAMPET,112,351000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT NEW MARKET STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14139,Roads,Completed,NJ-TEYNAMPET,112,499000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT CHOOLAIMEDU HIGH ROAD IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14140,Roads,Completed,NJ-TEYNAMPET,112,188000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT EASHWAR NAGAR 4tH STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14141,Roads,Completed,NJ-TEYNAMPET,112,337000,"IMPROVEMENTS TO INTERIOR B.T ROAD BHARATHEESWARAR COLONY 5tH STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14142,Roads,Completed,NJ-TEYNAMPET,112,849000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT BHARATHEESWARAR COLONY 4th STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14143,Roads,Completed,NJ-TEYNAMPET,112,949000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT BHARATHEESWARAR COLONY 3rd STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14144,Roads,Completed,NJ-TEYNAMPET,112,1111000,"IMPROVEMENTS TO INTERIOR B.T ROAD AT BHARATHEESWARAR COLONY 2ND STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/14145,Roads,Completed,NJ-TEYNAMPET,112,600000,"IMPROVEMENTS TO THE INTERIOR B.T ROAD AT BHARATHEESWARAR COLONY 1ST STREET IN DN 112, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/16012,Buildings,Completed,NJ-TEYNAMPET,112,400000,"REPAIRS AND IMPROVEMENTS TO CHENNAI BOYS HIGHER SECONDARY SCHOOL BUILDING AT CHOOLAIMEDU HIGH ROAD IN DIV -112, UNIT -26, ZONE -9",Own Sources,9,2017-18,2018-19 NJ/2017-18/16597,Buildings,Completed,NJ-TEYNAMPET,112,595000,"Supply and Erection of 500 LPH RO Plant At Health post Trustpuram 10th Cross Street in DN-112, U-26, Z-9",MLACDS,9,2017-18,2019-20 NJ/2017-18/16604,Buildings,Completed,NJ-TEYNAMPET,112,595000,"Supply and Erection of 500 LPH RO Plant At Chennai Boys Higher Sec School Choolaimedu High Road in DN-112, U-26, Z-9",MLACDS,9,2017-18,2019-20 NJ/2017-18/16608,Buildings,Completed,NJ-TEYNAMPET,112,595000,"Supply and Erection of 500 LPH RO Plant At Chennai Middle School Puliyur second Main Road in DN-112, U-26, Z-9",MLACDS,9,2017-18,2019-20 NJ/2017-18/17334,Buildings,Completed,NJ-TEYNAMPET,112,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT CHOOLAIMEDU HIGH ROAD (NEAR TO VANNIYAR STREET) IN DIV-112,U-26,Z-09",Own Sources,9,2017-18,2019-20 NJ/2017-18/17718,Parks,Completed,NJ-TEYNAMPET,112,194000,"ANNUAL MAINTENANCE OF CHITRA PARK AT RAILWAY BORDER ROAD IN DN-112,UNIT-26,ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/8440,Storm Water Drain,Completed,NJ-TEYNAMPET,112,46000,"DESLITING OF SWD AT BHARATHEESWARAR COLONY 1ST STREET IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8443,Storm Water Drain,Completed,NJ-TEYNAMPET,112,28800,"DESLITING OF SWD AT BHARATHEESWARAR COLONY 5TH STREET IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8444,Electrical,Completed,NJ-TEYNAMPET,112,39000,"DESLITING OF SWD AT SOUTH SIVAN KOIL STREET IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8445,Storm Water Drain,Completed,NJ-TEYNAMPET,112,52000,"DESLITING OF SWD AT DAYAL NAGAR MAIN ROAD IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8448,Storm Water Drain,Completed,NJ-TEYNAMPET,112,54000,"DESLITING OF SWD AT SIVAN KOIL STREET IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8449,Storm Water Drain,Completed,NJ-TEYNAMPET,112,36900,"DESLITING OF SWD AT PULIYUR 1ST LANE IN DN 112,UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8496,Storm Water Drain,Completed,NJ-TEYNAMPET,112,46900,"MINOR REPAIRS AND DESILTING OF STORM WATER DRAIN AT SOWRASHTRA NAGAR 8TH STREET IN DN. 112, UNIT -26, ZONE -9",Own Sources,9,2017-18,2017-18 NJ/2017-18/9118,Buildings,Completed,NJ-TEYNAMPET,112,200000,"Minor repairs to Storm water Drain at various streets (Trustpuram 4th Cross Street, Rajamanikar Street, Ponnusamy Vathiyar Street, Sowrastra Nagar 5th Street, Sowrastra Nagar 7th Street, Sowrastra Nagar 9th Street and Nehru Street) in Div-112,Unit-26,Zone-9",Own Sources,9,2017-18,2017-18 BR/2017-18/10919,Roads,Completed,BR-Bus Route Roads,113,755000,"ATTENDING REPAIR WORKS TO EXISTING CENTRE MEDIAN,FOOTPATH AND OTHER TRAFFIC IMPROVEMENT WORKS IN SANTHOME HIGH ROAD IN ZONE-09",Own Sources,9,2017-18,2018-19 BR/2017-18/11883,Road Cut,Completed,BR-Bus Route Roads,113,67000,"Restoration of Road cut made by CMWSSB at NUNGAMBAKKAM HIGH ROAD in Dn-113, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/11887,Road Cut,Completed,BR-Bus Route Roads,113,33500,"Restoration of Road cut made by CMWSSB at NUNGAMBAKKAM HIGH ROAD in Dn-113, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/13649,Road Cut,Completed,BR-Bus Route Roads,113,31800,"Restoration of Road cut made by CMWSSB at UTHAMAR GANDHI ROAD in Dn-113, Zone-9.",Deposit Works,9,2017-18,2018-19 D/2017-18/12950,Storm Water Drain,Completed,D-Storm Water Drains,113,29613000,"Construction of Strom Water Drain of size 900x900 mm at Kodambakkam High road, Periyar Road and Cathedral Garden Road in Dn-113, Zone- IX",SMART CITY - SWD,9,2017-18,2018-19 L/2017-18/13241,Electrical,Completed,L-Electrical,113,197800,"Painting and Numbering of 989 Nos of 6/7/8/9.2 Mtr lamp post at Kodambakkam High road , Abibullah road, Thirumalai pillai road and Various streets location in Thyagaraya Nagar Smart City ABD area , Greater Chennai corporation Division 113 Zone-9 .",Own Sources,9,2017-18,2020-21 NJ/2017-18/0588,Parks,Completed,NJ-TEYNAMPET,113,240000,"MAINTENECE WORK OUT SOURCING OF CORPORATION PARK (Near Diagnostic Lab ) AT KODAMBAKKAM HIGH ROAD FOR 6 MONTHS IN DIV 113,U 26,Z9 .(BY qualified Horticulturist only)",Own Sources,9,2017-18,2018-19 NJ/2017-18/11755,Roads,Completed,NJ-TEYNAMPET,113,695000,"REPAIRS TO DAMAGED PERIYAR ROAD DUE TO RECENT RAIN IN DN 113, UNIT 26, ZONE 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/11756,Roads,Completed,NJ-TEYNAMPET,113,827000,"REPAIRS TO DAMAGED BALA MUTHU KRISHNA STREET,AND HABIBULLAH ROAD DUE TO RECENT RAIN IN DN 113, UNIT 26, ZONE 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/11757,Roads,Completed,NJ-TEYNAMPET,113,714000,"REPAIRS TO DAMAGED SIVASAILAM STREET, DUE TO RECENT RAIN IN DN 113, UNIT 26, ZONE 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13738,Roads,Completed,NJ-TEYNAMPET,113,503000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT JUMBULINGAM STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13752,Roads,Completed,NJ-TEYNAMPET,113,469000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT SOUTH MADHA STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13753,Roads,Completed,NJ-TEYNAMPET,113,406000,"IIMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT EAST MADHA STREETT IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13754,Roads,Completed,NJ-TEYNAMPET,113,305000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT KUMARAPPA STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13756,Roads,Completed,NJ-TEYNAMPET,113,275000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT MOHAN KUMARAMANGALAM STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13759,Roads,Completed,NJ-TEYNAMPET,113,671000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT WEST MADA STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13760,Roads,Completed,NJ-TEYNAMPET,113,1140000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT PARTHASARATHYPURAM EXTN IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13761,Roads,Completed,NJ-TEYNAMPET,113,1006000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT PADMANABAN STREET IN DIVISION-113,UNIT-26, ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13762,Roads,Completed,NJ-TEYNAMPET,113,503000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT SARATHI STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13763,Roads,Completed,NJ-TEYNAMPET,113,503000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT KRISHNA STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13787,Roads,Completed,NJ-TEYNAMPET,113,908000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT BALA MUTHU KRISHNA STREET IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13788,Storm Water Drain,Completed,NJ-TEYNAMPET,113,599000,"IMPROVEMENT TO THE EXISTING INTERIOR B.T ROAD AT VIDYODAYA MAIN ROAD IN DIVISION-113,UNIT-26,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/16482,Buildings,Completed,NJ-TEYNAMPET,113,595000,"Supply and Erection of 500 LPH RO Plant At CMS, Rama Street In DN-113 U-26 Z-09.",MLACDS,9,2017-18,2019-20 NJ/2017-18/16484,Buildings,Completed,NJ-TEYNAMPET,113,430000,"Supply and Erection of 250 LPH RO Plant At CMS, Dharmapuram DN-113 U-26 Z-09.",MLACDS,9,2017-18,2019-20 NJ/2017-18/16487,Buildings,Completed,NJ-TEYNAMPET,113,595000,"Supply and Erection of 500 LPH RO Plant At Blood Testing And Dinagonastic Center, Kodambakkam High Road In DN-113 U-26 Z09.",MLACDS,9,2017-18,2019-20 NJ/2017-18/17720,Parks,Completed,NJ-TEYNAMPET,113,225000,"ANNUAL MAINTENANCE OF SHARMA ROAD PARK IN DN-113, UNIT-26, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/17721,Parks,Completed,NJ-TEYNAMPET,113,713000,"ANNUAL MAINTENANCE OF PERIYAR ROAD PARK IN DN-113, UNIT-26, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/17722,Parks,Completed,NJ-TEYNAMPET,113,357000,"ANNUAL MAINTENANCE OF KODAMBAKKAM HIGH ROAD PARK IN DN-113, UNIT-26, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/8220,Storm Water Drain,Completed,NJ-TEYNAMPET,113,68000,Desilting of storm water drain at Dhamapuram Main Road in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8223,Storm Water Drain,Completed,NJ-TEYNAMPET,113,48000,Desilting of storm water drain at Dhamapuram 4th street in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8224,Storm Water Drain,Completed,NJ-TEYNAMPET,113,25000,Desilting of storm water drain at Dhamapuram 5th street in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8226,Storm Water Drain,Completed,NJ-TEYNAMPET,113,62000,Desilting of storm water drain at Dhamapuram 6th street in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8227,Storm Water Drain,Completed,NJ-TEYNAMPET,113,41800,Desilting of storm water drain at Dharmapuram 7th street in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8228,Storm Water Drain,Completed,NJ-TEYNAMPET,113,39200,Desilting of storm water drain at krishnabai street in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8233,Storm Water Drain,Completed,NJ-TEYNAMPET,113,58000,Desilting of storm water drain at Kodambakkam high Road in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8234,Storm Water Drain,Completed,NJ-TEYNAMPET,113,41000,Desilting of storm water drain at Nungambakkam high Road in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8235,Storm Water Drain,Completed,NJ-TEYNAMPET,113,66500,Desilting of storm water drain at Balamuthu krishna street in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8236,Storm Water Drain,Completed,NJ-TEYNAMPET,113,90000,Desilting of storm water drain at G N Chetty Road in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8239,Storm Water Drain,Completed,NJ-TEYNAMPET,113,45200,Desilting of storm water drain at Thangavelu Street in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8240,Storm Water Drain,Completed,NJ-TEYNAMPET,113,59000,Desilting of storm water drain at Valluvar Kottam High Road in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8242,Storm Water Drain,Completed,NJ-TEYNAMPET,113,71000,Desilting of storm water drain at Prakasam Road in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8244,Storm Water Drain,Completed,NJ-TEYNAMPET,113,125000,Desilting of storm water drain at Cathedral Garden Road in div 113 unit 26 zone 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8865,Storm Water Drain,Completed,NJ-TEYNAMPET,113,2400000,"IMPROVEMENTS AND REPAIR TO STORM WATER DRAIN AT DR.MGR SALAI PART ( FROM PALM GROVE HOTEL TO UTHAMR GANDI SALAIIN FRONT OF PARK HOTEL ) IN DIVISION -113, UNIT-26, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8868,Storm Water Drain,Completed,NJ-TEYNAMPET,113,2400000,IMPROVEMENTS AND REPAIR TO STORM WATER DRAIN AT DR.MGR SALAI PART ( FROM CATHEDRAL GARDEN ROAD TO PALM GROVE HOTEL) IN DIVISION 113 UNIT 26 ZONE 09,Own Sources,9,2017-18,2018-19 NJ/2017-18/9102,Storm Water Drain,Completed,NJ-TEYNAMPET,113,150000,"Minor Repair work to storm water drain at various streets (Grama 1st Street, Pillayar Koil Street, Thirumoorthy Nagr 3rd & 6th Street.Kumarappa Street,Noor Veerasamy Street, Jaganathan Street,Krsihnama Road, Nageswara Road, Shenoy Road , Balamuthukrishna Street,Veerabadran Street,Balu Street, Parthasarathypuram , Sivasailam Street, Vidhyodaya Main Road in Div 113 Unit 26 Zone 09",Own Sources,9,2017-18,2017-18 P/2017-18/14337,Parks,Completed,P-Parks and Playfields,113,3393000,"Name of Work : Providing Packaged Sewage Treatment Plant Capacity of 10 KLD including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at Kodambakkam Park - 1 in Dn- 113, Zone - 9,",SMART CITY - PARKS,9,2017-18,2019-20 P/2017-18/2340,Parks,Completed,P-Parks and Playfields,113,6110000,"PROPOSED REDEVELOPMENT OF KODAMBAKKAM PARK-2 (PERIYAR SALAI) PARK IN THE AREA BASED DEVELOPMENT (ABD) OF T.NAGAR AS PART OF SMART CITY SCHEME IN DN-113, ZONE - IX",Grants,9,2017-18,2018-19 P/2017-18/2351,Parks,Completed,P-Parks and Playfields,113,12598764,PROPOSED REDEVELOPMENT OF KODAMBAKKAM CORPORATION (NEAR DHARMAPURAM LAB) PARK IN THE AREA BASED DEVELOPMENT(ABD) AREA OF T.NAGAR AS PART OF SMART CITY SCHEME IN DN 113/ZONE 9.,Grants,9,2017-18,2018-19 P/2017-18/2367,Parks,Completed,P-Parks and Playfields,113,6590000,PROPOSED REDEVELOPMENT OF SHARMA PARK IN THE AREA BASED DEVELOPMENT(ABD) AREA OF T.NAGAR AS PART OF SMART CITY SCHEME IN DN 113/ZONE 9.,Grants,9,2017-18,2019-20 B/2017-18/1500,Buildings,Completed,B-Buildings,114,5170000,"CONSTRUCTION OF NIGHT SHELTER AT KASTURBA GANDHI HOSPITAL FOR WOMEN AND CHILDREN AND GENERAL HOSPITAL (MEN) IN DN-114, Z-9",Own Sources,9,2017-18,2018-19 BR/2017-18/0608,Roads,Completed,BR-Bus Route Roads,114,1163000,"Provision of Simply Supported Over Head gantry Sign Boards at Swamy Sivananda Salai junction of Kamarajar Salai in Dn-114, Zone-9",Own Sources,9,2017-18,2019-20 BR/2017-18/3085,Footpath,Completed,BR-Bus Route Roads,114,22320000,"Forming of Footpath Quide Millath Road (From Wallaja Road to Peters Road) in Dn-114 & 116, Zone-IX",Grants,9,2017-18,2019-20 BR/2017-18/8791,Roads,Completed,BR-Bus Route Roads,114,10500000,"Proposed Construction of Tensile Roofing Bus Terminus at Anna Square Kamarajar Salai in Dn-114, Zone-9",Own Sources,9,2017-18,2018-19 L/2017-18/10417,Electrical,Completed,L-Electrical,114,186100,"Replacement of 6 nos of Distriburtion Pillar Box at Marina Beach Service Road ( Kamarajar Salai Labour statue to Kannagi statue. ) in Division - 114, Zone - IX area.",Own Sources,9,2017-18,2019-20 L/2017-18/12526,Electrical,Completed,L-Electrical,114,140300,"Painting of 407 Nos of 8 mtr Octagonal Street Lamp Post and 159 Nos 2/3 mtr Garden Post at Kamaraj Salai Both Side ( from Napier bridge to Light house ) and Service Road zone IX area in view of Repulic day (2018) to Division -114,116,120,121 and 125 in Zone - IX.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10634,Buildings,Completed,NJ-TEYNAMPET,114,602000,"Providing RO Purifier to Chennai middle school at Bangaru street in Div-114,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/10636,Buildings,Completed,NJ-TEYNAMPET,114,602000,"Providing RO Purifier to Chennai middle school at Bells Road in Div-114,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/10639,Buildings,Completed,NJ-TEYNAMPET,114,602000,"Providing RO Purifier to Chennai middle school at Typhoon alikhan street in Div-114,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/11037,Roads,Completed,NJ-TEYNAMPET,114,750000,"Attending patch work at various streets in Div-114,115, 116, 120 & 121, Unit-27, Zone-9.",Own Sources,9,2017-18,2019-20 NJ/2017-18/11735,Buildings,Completed,NJ-TEYNAMPET,114,690000,"Repairs to Public convenience at Marina Beach in Div-114,116 & 125, U-27A,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/17976,Parks,Completed,P-Parks and Playfields,114,531000,TREE PLANTATION - ZONE -IX,Own Sources,9,2017-18,2019-20 NJ/2017-18/4234,Parks,Completed,NJ-TEYNAMPET,114,648000,"OUTSOURCING FOR SECURITY AND MAINTAINANCE OF LAWN 1,2,3 AND 4 AT MARINA BEACH IN DN 114, UNIT - 27A, ZONE - 9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/5407,Roads,Completed,NJ-TEYNAMPET,114,372000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT ELLIS ROAD IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/5409,Roads,Completed,NJ-TEYNAMPET,114,374000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BIG STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/5411,Roads,Completed,NJ-TEYNAMPET,114,311000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT DERA VENKATASAMY STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/6973,Roads,Completed,NJ-TEYNAMPET,114,166000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT TAKUDHINKHAN STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/6976,Roads,Completed,NJ-TEYNAMPET,114,423000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT AZUDHINKHAN STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/6979,Roads,Completed,NJ-TEYNAMPET,114,203000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT TAZUDHINKHAN STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/7240,Roads,Completed,NJ-TEYNAMPET,114,405000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT VALLABA AGRAHARAM STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8386,Storm Water Drain,Completed,NJ-TEYNAMPET,114,218000,"DESILTING OF THE STORM WATER DRAIN AT QUIDE-MILLATH ROAD IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8388,Storm Water Drain,Completed,NJ-TEYNAMPET,114,129000,"DESILTING OF THE STORM WATER DRAIN AT BELLS ROAD IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8390,Roads,Completed,NJ-TEYNAMPET,114,146000,"IMPROVEMENTS TO INTERIOR CEMENT CONCRETE ROAD AT CNK LANE IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8394,Roads,Completed,NJ-TEYNAMPET,114,155000,"IMPROVEMENTS TO INTERIOR CEMENT CONCRETE SURFACE AT MURUGAPPA LANE IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8396,Roads,Completed,NJ-TEYNAMPET,114,153000,"IMPROVEMENTS TO INTERIOR CEMENT CONCRETE ROAD AT SUBRAMANI LANE IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8398,Roads,Completed,NJ-TEYNAMPET,114,976000,"IMPROVEMETS TO THE INTERIOR BT ROAD AT MAYOR CHITIBABU STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8399,Roads,Completed,NJ-TEYNAMPET,114,1164000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT KUPPU MUTHU STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8404,Roads,Completed,NJ-TEYNAMPET,114,412000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT TYPHOON ALIKHAN STREET IN DIV-114,U-27,Z-9.",Own Sources,9,2017-18,2018-19 P/2017-18/10654,Parks,Completed,P-Parks and Playfields,114,32814095,"ESTABLISHING CHILDREN TRAFFIC PARK AT KAMARAJAR SALAI NEAR NAPIER BRIDGE, IN DN-114, ZONE - IX",SMART CITY - PARKS,9,2017-18,2019-20 P/2017-18/12062,Parks,Completed,P-Parks and Playfields,114,88100000,Proposed Up gradation of existing infrastructure at Marina Beach - Coastal Tourism Circuit - Swadesh Darshan Scheme in Zone - IX,Grants,9,2017-18,2020-21 BR/2017-18/11873,Footpath,Completed,BR-Bus Route Roads,115,6278000,"Forming Footpath at West Cott Road from (Royapettah clock tower and Bharathi salai junction to peters road ) in Dn-115, Zone-IX",Grants,9,2017-18,2019-20 BR/2017-18/12015,Footpath,Completed,BR-Bus Route Roads,115,22390000,"Forming Footpath at Peters Road in Dn-115, Zone-IX",Grants,9,2017-18,2018-19 BR/2017-18/3195,Road Cut,Completed,BR-Bus Route Roads,115,77400,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 2 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/3196,Road Cut,Completed,BR-Bus Route Roads,115,103000,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 2 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/6011,Road Cut,Completed,BR-Bus Route Roads,115,112000,Restoration of Roadcut made by AIRTEL at Various Bus Route Roads ( 2 Road) in Zone -9,Deposit Works,9,2017-18,2018-19 NJ/2017-18/10648,Buildings,Completed,NJ-TEYNAMPET,115,602000,"Providing RO Purifier to Chennai middle school at soorappa street in Div-115,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/10649,Buildings,Completed,NJ-TEYNAMPET,115,602000,"Providing RO Purifier to Chennai middle school at Dr.Besant Road in Div-115,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/13629,Buildings,Completed,NJ-TEYNAMPET,115,250000,"Improvements to chennai primary school at Dr,Besant Road in Dn-115,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13634,Buildings,Completed,NJ-TEYNAMPET,115,375000,"Improvements to chennai Urudu Primary School at Dr,Besant Road in Dn-115,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13641,Buildings,Completed,NJ-TEYNAMPET,115,165000,"Improvements to ICDS at Thirunavukarasu street in Dn-115,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13844,Roads,Completed,NJ-TEYNAMPET,115,386000,"Improvements to the Existing B.T. Road at Manickam Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13845,Roads,Completed,NJ-TEYNAMPET,115,388000,"Improvements to the Existing B.T. General samy Street Road at in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13846,Roads,Completed,NJ-TEYNAMPET,115,1046000,"Improvements to the Existing B.T. Road at Mir Bakshi Ali Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13847,Roads,Completed,NJ-TEYNAMPET,115,791000,"Improvements to the Existing B.T.Road at Perumal Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13848,Roads,Completed,NJ-TEYNAMPET,115,447000,"Improvements to the Existing B.T.Road at Pallappan Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13849,Roads,Completed,NJ-TEYNAMPET,115,199000,"Improvements to the Existing B.T.Road at Jani Jan Khan Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13850,Roads,Completed,NJ-TEYNAMPET,115,282000,"Improvements to the Existing B.T. Road at Theetharappan Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13851,Roads,Completed,NJ-TEYNAMPET,115,306000,"Improvements to the Existing BT Road at Vannier Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13852,Roads,Completed,NJ-TEYNAMPET,115,269000,"Improvements to the Existing B.T. Road at Thalayari Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13853,Roads,Completed,NJ-TEYNAMPET,115,285000,"Improvements to the Existing B.T. Road at Agathimutham Street in Div - 115, Unit - 27, Zone - 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/16875,Roads,Completed,NJ-TEYNAMPET,115,315000,"IMPROVEMENTS TO THE BT ROAD AT HAKKIM MAQDOOM ASHRAF STREET IN DIVISION - 115, UNIT - 27, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/16876,Roads,Completed,NJ-TEYNAMPET,115,136000,"IMPROVEMENTS TO THE BT ROAD AT THAMBU STREET IN DIVISION - 115, UNIT - 27, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/16880,Roads,Completed,NJ-TEYNAMPET,115,360000,"IMPROVEMENTS TO THE BT ROAD AT THANAPPA STREET IN DIVISION - 115,UNIT - 27,ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/16881,Roads,Completed,NJ-TEYNAMPET,115,41000,"Improvements to the BT Road at Gaffoor 3rd Lane in Division - 115, Unit - 27, Zone-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/16882,Roads,Completed,NJ-TEYNAMPET,115,42000,IMPROVEMENTS TO THE BTROAD AT GAFOOR 2ND LANE IN DIVISION - 115 UNIT - 27 ZONE-9,Own Sources,9,2017-18,2019-20 NJ/2017-18/16884,Roads,Completed,NJ-TEYNAMPET,115,259000,"IMPROVEMENTS TO THE BT ROAD AT GAFOOR STREET IN DIVISION - 115, UNIT - 27, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/16961,Roads,Completed,NJ-TEYNAMPET,115,41000,"IMPROVEMENTS TO THE BT ROAD AT KOYA ARUNAGIRI 3RD STREET IN DIVISION - 115, UNIT - 27, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/16962,Roads,Completed,NJ-TEYNAMPET,115,187000,"IMPROVEMENTS TO THE B.TROAD AT KOYA ARUNAGIRI 2ND STREET IN DIVISION - 115, UNIT - 27, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/16963,Roads,Completed,NJ-TEYNAMPET,115,227000,"Attending Patch work of BT road with BC 40 mm at Ramasamy Garden Street in Division - 115, Unit - 27, Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/8415,Storm Water Drain,Completed,NJ-TEYNAMPET,115,188000,"DESILTING OF THE STORM WATER DRAIN AT Dr.BESANT ROAD IN DIV-115,U-27,Z-9.",Own Sources,9,2017-18,2017-18 BR/2017-18/11882,Road Cut,Completed,BR-Bus Route Roads,116,18000,"Restoration of Road cut made by CMWSSB at QUAID-E-MILLATH ROAD in Dn-116, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/11885,Road Cut,Completed,BR-Bus Route Roads,116,83000,"Restoration of Road cut made by CMWSSB at QUAID E MILLATH ROAD in Dn-116, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/13360,Roads,Completed,BR-Bus Route Roads,116,867000,"Providing Hot applied Thermo Plastic paint and other traffic improvement work at Kamarajar salai (from the jn of Santhome High Road to Dr.Radhakrishnan Salai ), Santhome High Road and Loop Road in the view of REpublic Day function in Dn- 121, 125 and 116, Zone-9",Own Sources,9,2017-18,2018-19 BR/2017-18/13362,Roads,Completed,BR-Bus Route Roads,116,933000,"Providing Hot applied Thermo Plastic paint and other traffic improvement work at Kamarajar salai in the view of Republic day function (from the jn of Dr.Radhakrishnan Salai to Vivekanandar Illam) in Dn-121 & 116, Zone-9",Own Sources,9,2017-18,2018-19 BR/2017-18/7166,Roads,Completed,BR-Bus Route Roads,116,422000,"Providing Speed Breaker and Sign Board at Vivekananda Illam Bus Bay (kamarajar Salai marina) in Dn.116, Zone 9",Own Sources,9,2017-18,2018-19 L/2017-18/10416,Electrical,Completed,L-Electrical,116,199300,"Replacement of 2 nos of Kiosk Pillar Box and 6 nos of Distriburtion Pillar Box at Marina Beach Service Road ( Kamarajar Salai Kannagi statue to Gandhi statue. ) in Division - 116 and 120, Zone - IX area.",Own Sources,9,2017-18,2019-20 L/2017-18/7714,Electrical,Completed,L-Electrical,116,1167100,"Provision of 6 nos of 8 mtr G I Octogonal Mini High Mast Hot Dip Zinc galvanising Post with 70 - 100 Watts LED Fitting at J J Khon Street jn of V M Street, Dr. Besent Road jn of V R Pillai Street, Dr. Besent road jn of Annaibesent park, Lloyds Colony E - Depo Junction, Lloyds Colony Jn of Greater Chennai Corparation I I T and Bharthi Salai Jn of V H Road in Division - 114, 115, 116 and 120, Zone-IX. .",MPLADS,9,2017-18,2020-21 NJ/2017-18/10587,Buildings,Completed,B-Buildings,116,215000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL FOR SMARTCLASS AT TRIPLICANE HIGHROAD IN DIV-116,U-27,Z-9.",SMART CITY - BUILDINGS,9,2017-18,2018-19 NJ/2017-18/10650,Buildings,Completed,NJ-TEYNAMPET,116,768000,"Providing RO Purifier to Chennai middle school at Triplicane High Road in Div-116,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/10651,Buildings,Completed,NJ-TEYNAMPET,116,602000,"Providing RO Purifier to Chennai middle school at V.R Pillai street in Div-116,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/13717,Buildings,Completed,NJ-TEYNAMPET,116,150000,"Improvements to ICDS at V.R Pillai street in Dn-116,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13718,Buildings,Completed,NJ-TEYNAMPET,116,150000,"Improvements to ICDS at Sivarajapuram in Dn-116,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13720,Buildings,Completed,NJ-TEYNAMPET,116,150000,"Improvements to Chennai Middle School at Triplicane High Road Road in Dn-116,U-27,Z-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/16889,Roads,Completed,NJ-TEYNAMPET,116,134000,"Attending Patch work of BT road with BC 40 mm at Narayana Krishnaraja Puram in Division - 116, Unit - 27, Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/4238,Parks,Completed,NJ-TEYNAMPET,116,648000,"OUTSOURCING FOR SECURITY AND MAINTAINANCE OF LAWN 5,6,7 AND 8 AT MARINA BEACH IN DN 116, UNIT - 27A, ZONE - 9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/7819,Roads,Completed,NJ-TEYNAMPET,116,860000,"IMPROVEMENT WORKS TO THE BT ROAD AT BIG STREET IN DIV-116,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/7820,Roads,Completed,NJ-TEYNAMPET,116,578000,"IMPROVEMENT WORK TO THE BT ROAD AT VASUDEVA PURAM IN DIV-116,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/7821,Roads,Completed,NJ-TEYNAMPET,116,346000,"IMPROVEMENT WORK TO THE BT ROAD AT BANDALA VENUGOPAL STREET IN DIV-116,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8347,Storm Water Drain,Completed,NJ-TEYNAMPET,116,196000,"DESILTING OF THE STORM WATER DRAIN AT DR. BESANT ROAD IN DIV-116,U-27,Z-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8351,Storm Water Drain,Completed,NJ-TEYNAMPET,116,246000,"DESILTING OF THE STORM WATER DRAIN AT QUIDE-MILATH ROAD IN DIV-116,U-27,Z-9.",Own Sources,9,2017-18,2017-18 BR/2017-18/11891,Road Cut,Completed,BR-Bus Route Roads,117,100000,"Restoration of Road cut made by CMWSSB at THANIKACHALAM ROAD in Dn-117, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/13213,Roads,Completed,BR-Bus Route Roads,117,2211000,"Restoration of Roadcut made by TANTRANSCO at Thanikachalam Road (from the junction of EB Sub Station to Melony Road) in Dn-117, Zone-IX (Challan No.BR/2017-18/0004220)",Deposit Works,9,2017-18,2018-19 BR/2017-18/13215,Roads,Completed,BR-Bus Route Roads,117,1673000,"Restoration of Roadcut made by TANTRANSCO at Thanikachalam Road (from the junction of Melony Road to Venkatanarayana Road ) (Challan No.BR/201-18/0004220) in Dn-117, Zone-IX",Deposit Works,9,2017-18,2018-19 BR/2017-18/1802,Road Cut,Completed,BR-Bus Route Roads,117,1360000,"Restoration of Road cut Made By CMWSSB at G.N. Chetty Road in Dn - 117, Zone -9",Deposit Works,9,2017-18,2018-19 BR/2017-18/5213,Road Cut,Completed,BR-Bus Route Roads,117,1432000,"Restoration of Roadcut made by CMWSSB at B.V.Narasimman Salai in Dn-117, Zone-9",Deposit Works,9,2017-18,2020-21 D/2017-18/12956,Storm Water Drain,Completed,D-Storm Water Drains,117,19829000,"Construction of Storm Water Drain of Size 900x900mm at Prakasam Road, South Boag Road, Mambalam Hiogh Road, Dr.Sadasivam Road and Dr.Narasimhan 2nd street in Dn-113 & 117 Zone-IX",SMART CITY - SWD,9,2017-18,2018-19 L/2017-18/13182,Electrical,Completed,L-Electrical,117,146700,"Painting of 132 no's of 8mtr lamp posts with straight single brt,79 no's of, 187 no's of 9.2mtr lamp posts with single straight brt and 38 no's of koisk pillar boxes with single cost Aluminium paints and 1448 no's of lamp posts numbering in various location in Thyagaraya Nagar Smart City ABD area,Greater Chennai corporation Division 117,Zone-IX",Own Sources,9,2017-18,2020-21 L/2017-18/13183,Electrical,Completed,L-Electrical,117,195000,"Painting of 1027no's of 6/7mtr lamp posts, 79 no's of 9.2mtr lamp posts with single arch single bkt, 24 no's of 8mtr lamp posts with arch double bkt, in various location in Thyagaraya Nagar Smart City ABD area, Greater Chennai corporation Division 117, Zone-IX",Own Sources,9,2017-18,2020-21 L/2017-18/2759,Electrical,Completed,L-Electrical,117,186500,"Proposal for supply and fixing of 13 nos of Timer at Thyagaraya road,G .N Chetty road and Various places in Division -117&122,Zone -IX",Own Sources,9,2017-18,2017-18 L/2017-18/7094,Electrical,Completed,L-Electrical,117,199100,"Replacement of 5 nos of Damaged Kiosk Pillar Boxes at Anna Salai, V C Road ,G. N .Chetty rd and Various locations in Division 117,122, Zone IX.",Own Sources,9,2017-18,2017-18 NJ/2017-18/0274,Buildings,Completed,NJ-TEYNAMPET,117,886000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENTS TO PLAY GROUND AT CHENNAI MIDDLE SCHOOL ERIKARAI IN DN 117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/13803,Roads,Completed,NJ-TEYNAMPET,117,939000,"IMPROVEMENTS TO THE EXISTING INTERIOR B.T.ROAD AT NORTH CRESCENT ROAD IN DIVISION -117,UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13804,Roads,Completed,NJ-TEYNAMPET,117,939000,"IMPROVEMENTS TO THE EXISTING INTERIOR B.T.ROAD AT GIRIAPPA ROAD (PART-2) IN DIVISION -117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13807,Roads,Completed,NJ-TEYNAMPET,117,1097000,"IMPROVEMENTS TO THE EXISTING INTERIOR B.T.ROAD AT NORTH CRESCENT ROAD IN DIVISION -117,UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13808,Roads,Completed,NJ-TEYNAMPET,117,707000,"IMPROVEMENTS TO THE EXISTING INTERIOR B.T.ROAD AT LAKSHMI COLONY IN DIVISION -117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/13810,Roads,Completed,NJ-TEYNAMPET,117,2268000,"IMPROVEMENTS TO THE EXISTING INTERIOR B.T.ROAD AT GIRI ROAD IN DIVISION -117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/17333,Buildings,Completed,NJ-TEYNAMPET,117,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT VIJAYARAGHAVA ROAD IN DIV-117,U-26,Z-09",Own Sources,9,2017-18,2019-20 NJ/2017-18/17723,Parks,Completed,NJ-TEYNAMPET,117,198000,"ANNUAL MAINTENANCE OF CHARI STREET PARK IN DN-117, UNIT-26, ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/7841,Buildings,Completed,NJ-TEYNAMPET,117,130000,"DISMANTLING AND CARTING OF DILAPILATED WILLIAMS BRIDGE INBETWEEN GIRIAPPA ROAD SND SSPURAM AND M.K.RADHA NAGAR IN DN 117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/8052,Storm Water Drain,Completed,NJ-TEYNAMPET,117,200000,"DESILTING OF SWD AT G.N.CHETTY ROAD BOTH SIDES IN DN 117,UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8053,Storm Water Drain,Completed,NJ-TEYNAMPET,117,79000,"DESILTING OF STORM WATER DRAIN AT CHEVALIAR SIVAJIGANESAN ROAD IN DN 117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8054,Storm Water Drain,Completed,NJ-TEYNAMPET,117,47000,"DESILTING OF STORM WATER DRAIN AT THANIKACHALAM ROAD IN DN 117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8057,Storm Water Drain,Completed,NJ-TEYNAMPET,117,42000,"DESILTING OF STORM WATER DRAIN AT B.NARASHIMHAN 2ND STREET IN DN 117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8405,Storm Water Drain,Completed,NJ-TEYNAMPET,117,43700,"DESILTING OF STORM WATER DRAIN AT LAKSHMI COLONY IN DN 117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8408,Storm Water Drain,Completed,NJ-TEYNAMPET,117,62000,"DESILTING OF STORM WATER DRAIN AT NORTH CRESENT ROAD IN DN 117, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/9088,Storm Water Drain,Completed,NJ-TEYNAMPET,117,150000,"Minor repairs to Storm water Drain at various streets (Arcot Road, New Giri Road, Arulambal Street, Sarathi Street and Street) in Div-117,Unit-26,Zone-9",Own Sources,9,2017-18,2017-18 P/2017-18/2370,Parks,Completed,P-Parks and Playfields,117,4080000,PROPOSED REDEVELOPMENT CHARI PARK IN THE AREA BASED DEVELOPMENT IN T. NAGAR AS PART OF SMART CITY SCHEME IN DN 117/ZONE 9,Grants,9,2017-18,2019-20 NJ/2017-18/10070,Roads,Completed,NJ-TEYNAMPET,118,144000,Improvements to the Existing BT Road AT MUTHU LANE IN DIV.118 UNIT.24 ZONE.9,Own Sources,9,2017-18,2018-19 NJ/2017-18/10217,Roads,Completed,NJ-TEYNAMPET,118,516000,"IMPROVEMENTS B.T. ROAD AT P.V.KOIL 1ST STREET IN DIV,118 UNIT.24 ZONE.9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10454,Roads,Completed,NJ-TEYNAMPET,118,525000,RELAYING B.T.ROAD AT J.J.ROAD (PART) IN DIV.118 UNIT.24 ZONE.9,Own Sources,9,2017-18,2018-19 NJ/2017-18/16598,Buildings,Completed,NJ-TEYNAMPET,118,595000,"Supply and Erection of 500 LPH RO Plant At Dispensary Royapettah in DN-118, U-24, Z-9",MLACDS,9,2017-18,2018-19 NJ/2017-18/16908,Storm Water Drain,Completed,NJ-TEYNAMPET,118,100000,"REPAIRS AND MAINTENANCE OF STORM WATER DRAIN AT SADASIVAM STREET IN DIVISION-118,UNIT-24,ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/16964,Storm Water Drain,Completed,NJ-TEYNAMPET,118,100000,"REPAIRS AND MAINTENANCE OF STORM WATER DRAIN AT ELANGO SALAI IN DIVISION-118,UNIT-24,ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/16965,Storm Water Drain,Completed,NJ-TEYNAMPET,118,100000,"REPAIRS AND MAINTENANCE OF STORM WATER DRAIN AT ELLAIAMMAN COLONY MAIN ROAD IN DIVISION-118,UNIT-24,ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/16966,Storm Water Drain,Completed,NJ-TEYNAMPET,118,100000,"REPAIRS AND MAINTENANCE OF STORM WATER DRAIN AT PUDUPET GARDEN LANE IN DIVISION-118,UNIT-24,ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/16967,Storm Water Drain,Completed,NJ-TEYNAMPET,118,100000,"REPAIRS AND MAINTENANCE OF STORM WATER DRAIN AT RATHINAM STREET IN DIVISION-118,UNIT-24,ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/3920,Parks,Completed,NJ-TEYNAMPET,118,160000,"ANNUAL MAINTENECE OF G.N.PARK (6 MONTHS) AT MUTHAIAH STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/3921,Parks,Completed,NJ-TEYNAMPET,118,113000,"ANNUAL MAINTENECE OF THI.VI.KA.PARK AT S.P.S 1st STREET IN DIVISION-118, UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5968,Road Cut,Completed,NJ-TEYNAMPET,118,838000,"Improvements to the Existing BT Road AT PUDUPET GARDEN STRET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5981,Road Cut,Completed,NJ-TEYNAMPET,118,469000,"Improvements to the Existing BT Road AT MARIAPPAN LANE IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5991,Road Cut,Completed,NJ-TEYNAMPET,118,335000,"Improvements to the Existing BT Road AT PARTHASARATHIPET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5993,Road Cut,Completed,NJ-TEYNAMPET,118,335000,"Improvements to the Existing BT Road RAMASAMY STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8557,Storm Water Drain,Completed,NJ-TEYNAMPET,118,31000,"DESILTING FOR STORM WATER DRAIN AT PUDUPET GARDEN STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8583,Storm Water Drain,Completed,NJ-TEYNAMPET,118,45000,"DESILTING FOR STORM WATER DRAIN AT PUDUPET GARDEN LANE IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8586,Storm Water Drain,Completed,NJ-TEYNAMPET,118,78000,"DESILTING FOR STORM WATER DRAIN AT KASTHURI ESTATE 2nd STREET IN DIVISION - 118, UNIT - 24, ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8588,Storm Water Drain,Completed,NJ-TEYNAMPET,118,30000,"DESILTING FOR STORM WATER DRAIN AT RAMASAMY STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8592,Storm Water Drain,Completed,NJ-TEYNAMPET,118,158000,"DESILTING FOR STORM WATER DRAIN AT CATHEDRAL (South) ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8610,Storm Water Drain,Completed,NJ-TEYNAMPET,118,158000,"DESILTING FOR STORM WATER DRAIN AT CATHEDRAL ROAD ( North) IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/9324,Storm Water Drain,Completed,NJ-TEYNAMPET,118,162000,"REPAIRS OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-118,UNIT-24, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9907,Roads,Completed,NJ-TEYNAMPET,118,475000,"RELAYING B.T.ROAD AT SADASIVAM STREET IN DIV.118 UNIT.24, ZONE.9",Own Sources,9,2017-18,2018-19 BR/2017-18/12986,Footpath,Completed,BR-Bus Route Roads,119,970000,Providing painting and repairs to the footpath kerb & the existing centre median at Dr.Radhakrishnan Salai in the view of Republic day function in Zone - 9,Own Sources,9,2017-18,2018-19 BR/2017-18/12987,Footpath,Completed,BR-Bus Route Roads,119,960000,Providing painting and repairs to the footpath kerb & the existing centre median at Cathedral road and TTK road in the view of Republic day function in Zone - 9,Own Sources,9,2017-18,2018-19 NJ/2017-18/10045,Roads,Completed,NJ-TEYNAMPET,119,362000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ANTHONY STREET IN DIVISION-119, UNIT-24, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10046,Roads,Completed,NJ-TEYNAMPET,119,289000,"Improvements to the Existing BT Road AT MAYOR SIVARAJ STREET IN DIVISION-119, UNIT-24, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10640,Buildings,Completed,NJ-TEYNAMPET,119,602000,"Providing RO Purifier to Chennai middle school at Begum sahib street in Div-119,U-24,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/10642,Buildings,Completed,NJ-TEYNAMPET,119,602000,"Providing RO Purifier to Chennai urudu girls middle School at Peters Road in Div-119,U-24,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/10643,Buildings,Completed,NJ-TEYNAMPET,119,602000,"Providing RO Purifier to Chennai middle school at Balaji nagar 3rd street in Div-119,U-24,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/12713,Roads,Completed,NJ-TEYNAMPET,119,750000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIV-109,110,111,118 & 119, UNIT-24, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13706,Roads,Completed,NJ-TEYNAMPET,119,451000,"IMPROVEMENTS TO THE B.T.ROAD AT CHANDA STREET IN DIVISION-119, UNIT-24, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/16634,Storm Water Drain,Completed,NJ-TEYNAMPET,119,150000,"REPAIRS TO THE DAMAGED STORM WATER DRAIN AT DEIVASIGAMANI STREET (JUNCTION OF T.T.K. SALAI) IN DIV-119, U-24, Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/3971,Parks,Completed,NJ-TEYNAMPET,119,136000,"ANNUVAL MAITENANCE OF C.I.T.COLONY PARK (6 MONTHS) AT C.I.T.COLONY 5TH CROSS STREET IN DIVISION-119, UNIT-24,ZONE-09.",Own Sources,9,2017-18,2018-19 NJ/2017-18/5999,Roads,Completed,NJ-TEYNAMPET,119,369000,"IMPROVEMENTS TO THE B.T.ROAD AT BEGAM 3rd STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/6071,Roads,Completed,NJ-TEYNAMPET,119,430000,"IMPROVEMENTS TO THE C.C.ROAD AT LOOP STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8420,Storm Water Drain,Completed,NJ-TEYNAMPET,119,28000,"Desilting for storm water drain at P.S.Sivasamy Salai in division-119,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8427,Storm Water Drain,Completed,NJ-TEYNAMPET,119,174000,"Desilting for storm water drain at Thiru.Vi.Ka.Salai in division-119,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8430,Storm Water Drain,Completed,NJ-TEYNAMPET,119,68000,"Desilting for storm water drain at Muthaiah Garden street in division-119,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8432,Storm Water Drain,Completed,NJ-TEYNAMPET,119,217000,"Desilting for storm water drain at Peters Road (South & North Side) in division-119,Unit-24,Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8435,Storm Water Drain,Completed,NJ-TEYNAMPET,119,142000,"Desilting for storm water drain at Avvai shanmugam salai (Part) and Jn of Avvai Shanmugam Salai & Appakannu Street in division-119,Unit-24,Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8450,Storm Water Drain,Completed,NJ-TEYNAMPET,119,26000,"Desilting for storm water drain at Avvai Shanmugam Salai 1st Lane in division-119,Unit-24,Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8705,Storm Water Drain,Completed,NJ-TEYNAMPET,119,92000,"DESILTING FOR STORM WATER DRAIN AT AVVAI SHANMUGAM SALAI IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9325,Storm Water Drain,Completed,NJ-TEYNAMPET,119,211000,"REPAIRS OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-119,UNIT-24, ZONE-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9947,Roads,Completed,NJ-TEYNAMPET,119,246000,"IMPROVEMENTS TO THE B.T.ROAD AT MYLAPOORAN STREET IN DIVISION-119, UNIT-24, ZONE-9.",Own Sources,9,2017-18,2018-19 B/2017-18/13458,Buildings,Completed,B-Buildings,120,7589014,"Additional works in Construction of Fish market at Nadukuppam in Dn.120, Zone-9",Grants,9,2017-18,2019-20 L/2017-18/6494,Electrical,Completed,L-Electrical,120,199200,"Electrification work for Damaged Wiring at CMS School, Ram Nagar in Division - 120, Zone-IX.",Own Sources,9,2017-18,2017-18 L/2017-18/7118,Electrical,Completed,L-Electrical,120,192200,"Replacement of 140 Mtr 3 1/2 X25 Sqmm U.G.Cable and 107 Mtr of 2 X 16 Sqmm U.G.Cable for Animal Birth Control Center at Lloyds colony, Ice House in Division-120, Zone - IX area.",Own Sources,9,2017-18,2017-18 L/2017-18/7119,Electrical,Completed,L-Electrical,120,193900,"Electrification work for Animal Birth Control Center at Lloyds Colony, Ice House in Division - 120, Zone-IX.",Own Sources,9,2017-18,2017-18 NJ/2017-18/10646,Buildings,Completed,NJ-TEYNAMPET,120,602000,"Providing RO Purifier to Chennai middle school at krishnampet in Div-120,U-27,Z-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/11328,Buildings,Completed,NJ-TEYNAMPET,120,631000,"IMPROVEMENT TO THE BIO-GASIFIER WORK IN KRISHNAMPETTAI BURIAL GROUND AT GAJAPATHY LALA STREET IN DIV-120,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/7413,Roads,Completed,NJ-TEYNAMPET,120,403000,"IMPROVEMENT TO THE INTEROR BT ROAD WORK AT E-DEPOT STREET AND LANE IN DIV-120,U-27,Z-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/7414,Roads,Completed,NJ-TEYNAMPET,120,132000,"IMPROVEMENT TO THE EXISTING BT ROAD WORK AT VENKASTASAMY LANE IN DIV-120,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8342,Storm Water Drain,Completed,NJ-TEYNAMPET,120,87000,"DESILTING OF THE STORM WATER DRAIN AT DR. NATESAN ROAD IN DIV-120,U-27,Z-9.",Own Sources,9,2017-18,2017-18 BR/2017-18/11886,Road Cut,Completed,BR-Bus Route Roads,121,117000,"Restoration of Road cut made by CMWSSB at DR. RADHAKRISHNAN SALAI in Dn-121, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/12985,Footpath,Completed,BR-Bus Route Roads,121,965000,Providing painting and repairs to the footpath kerb & the existing centre median at Kamarajar Salai in the view of Republic day function in Zone - 9,Own Sources,9,2017-18,2018-19 BR/2017-18/13364,Roads,Completed,BR-Bus Route Roads,121,810000,"Providing Hot applied Thermo Plastic paint and other traffic improvement work at Dr.Radhakrishnan salai (from the jn of Kamarajar Salai to City Centre) in the view of Republic day function in Dn-121 , Zone-9",Own Sources,9,2017-18,2018-19 BR/2017-18/14148,Roads,Completed,BR-Bus Route Roads,121,316000,"PROVIDING AND FIXING SOLAR STUD,VERTICAL DELINEATOR AND STUD AT KAMARAJAR SALAI IN DIV-121 ZONE-9",Own Sources,9,2017-18,2019-20 D/2017-18/6839,Storm Water Drain,Completed,D-Storm Water Drains,121,19600000,"Dismantling of existing dilapidated storm water drain and Re-construction of double vent storm water drain of size 1500x2000mm at P.S.Sivasamy salai from Vivekananda college to Indhirani Street in Dn - 121, Zone IX.",Own Sources,9,2017-18,2018-19 D/2017-18/7694,Storm Water Drain,Completed,D-Storm Water Drains,121,19600000,"Dismantling of existing dilapidated storm water drain and Re-construction of double vent storm water drain of size 1500x2000mm along P.S.Sivasamy salai from Indhirani Street to Royapettah High Road in Dn-121,Zone-IX.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13570,Buildings,Completed,NJ-TEYNAMPET,121,150000,"IMPROVEMENT TO THE ICDS AT AVVAI SHANMUGAM SALAI IN DIV-121,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13598,Buildings,Completed,NJ-TEYNAMPET,121,260000,"IMPROVEMENT TO THE CHENNAI PRIMARY SCHOOL AT VEERAPERUMAL KOIL STREET IN DIV-121,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13636,Buildings,Completed,NJ-TEYNAMPET,121,260000,"IMPROVEMENT TO CHENNAI PRIMARY SCHOOL & CHENNAI URDU PRIMARY SCHOOL AT AVVAI SHANMUGAM SALAI IN DIV-121,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/14475,Buildings,Completed,NJ-TEYNAMPET,121,2760000,"CONSTRUCTION OF NEW RATION SHOP AT AVVAI SHANMUGAM SALAI IN DIV-121,U-27,Z-9.(MLA FUND)",MLACDS,9,2017-18,2019-20 NJ/2017-18/16625,Buildings,Completed,NJ-TEYNAMPET,121,2980000,"CONSTRUCTION OF NEW ICDS(G+1) AT DWARAKA NAGAR IN DIV-121,U-27,Z-9.(MLA FUND)",MLACDS,9,2017-18,2019-20 NJ/2017-18/17724,Buildings,Completed,NJ-TEYNAMPET,121,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT AVVAI SHANMUGAM SALAI (LLYODS ROAD)IN DIV-121,U-27,Z-09",Own Sources,9,2017-18,2019-20 NJ/2017-18/5191,Storm Water Drain,Completed,NJ-TEYNAMPET,121,340000,"REPAIRS TO THE STORM WATER DRAIN AT P.S.SIVASWAMI SALAI IN DIV-121,U-27,Z-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/7415,Roads,Completed,NJ-TEYNAMPET,121,141000,"IMPROVEMENT TO THE EXISTING BT ROAD WORK AT VENKASTASAMY STREET IN DIV-120,U-27,Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/8304,Storm Water Drain,Completed,NJ-TEYNAMPET,121,52000,"DESILTING OF THE STORM WATER DRAIN AT THIRU-VI-KA HIGH ROAD IN DIV-121,U-27,Z-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8305,Storm Water Drain,Completed,NJ-TEYNAMPET,121,30000,"DESILTING OF STORM WATER DRAIN AT V.M.STREET IN DIV-121,U-27,Z-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8345,Storm Water Drain,Completed,NJ-TEYNAMPET,121,193000,"DESILTING OF THE STORM WATER DRAIN AT DR. RADHAKRISHNAN SALAI IN DIV-121,U-27,Z-9.",Own Sources,9,2017-18,2017-18 BR/2017-18/1880,Road Cut,Completed,BR-Bus Route Roads,122,903000,Restoration of Roadcut made by VODAFONE at Various Bus Route Roads ( 5 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2122,Road Cut,Completed,BR-Bus Route Roads,122,513000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 14 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2127,Road Cut,Completed,BR-Bus Route Roads,122,873000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 20 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/3199,Road Cut,Completed,BR-Bus Route Roads,122,50700,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 2 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/7929,Road Cut,Completed,BR-Bus Route Roads,122,2283000,"Restoration of Roadcut made by TANTRANSCO at Posumpon Muthuramalinga Devar Salai (From the jn of Boat Club Road to the jn of R.A.Puram 2ndc Main Road) in Dn-122, Zone-9 (L-400M Challan No.BR/2017-18/0004220)",Deposit Works,9,2017-18,2017-18 BR/2017-18/7931,Road Cut,Completed,BR-Bus Route Roads,122,2391000,"Restoration of Roadcut made by TANTRANSCO at Posumpon Muthuramalinga Devar Salai (From the jn of Taluk office to the jn of R.A.Puram 2ndc Main Road) in Dn-122, Zone-9 (L-410M Challan No.BR/2017-18/0004220)",Deposit Works,9,2017-18,2017-18 BR/2017-18/7932,Road Cut,Completed,BR-Bus Route Roads,122,380000,"Restoration of Roadcut made by TANTRANSCO at Turn Bulls Road in Dn-122, Zone-9 (L-71M Challan No.BR/2017-18/0004220)",Deposit Works,9,2017-18,2017-18 L/2017-18/15176,Electrical,Completed,L-Electrical,122,717800,"Provision of 5 no of GI Octoganal Mini Mast with Hot Dip zinc Galvanised with 70-100w LED flood light in sri ram nager south,north ,cenatop road 2 nd lane &T.T.K road dn 122/Z 9",Own Sources,9,2017-18,2018-19 NJ/2017-18/0593,Parks,Completed,NJ-TEYNAMPET,122,597000,"ANNUAL MAINTENANCE OF PARK FOR 9 MONTHS AT TURN BULLS ROAD (INCLUDING WATER SUPPLY BY PRIVATE LORRY) IN DN-122,UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/11163,Storm Water Drain,Completed,NJ-TEYNAMPET,122,414000,"REPAIR AND IMPROVEMENT SWD AT CHAMIER ROAD IN DN-122,U-26,Z-09.",Own Sources,9,2017-18,2019-20 NJ/2017-18/12704,Footpath,Completed,NJ-TEYNAMPET,122,820000,Repair and Improvement of Foothpath and Center Median Arch Bishop Mathive Avenue and Crasent Street in Dn 122 U-26 Z-09.,Own Sources,9,2017-18,2019-20 NJ/2017-18/17068,Buildings,Completed,NJ-TEYNAMPET,122,150000,IMPROVEMENT WORKS TO NNMP SHED AT CENATAPH STREET IN DIV 122 UNIT 26 ZONE 9,Own Sources,9,2017-18,2018-19 NJ/2017-18/17719,Parks,Completed,NJ-TEYNAMPET,122,1000000,"ANNUAL MAINTENANCE OF TURNBULLS ROAD PARK IN DN-122,UNIT-26,ZONE-9",Own Sources,9,2017-18,2019-20 NJ/2017-18/5971,Road Cut,Completed,NJ-TEYNAMPET,122,335000,"Improvement works to interior BT Roads at Seethammal Colony Extn 3rd Main Road in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/5982,Road Cut,Completed,NJ-TEYNAMPET,122,335000,"Improvement works to interior BT Roads at Seethammal Colony 3rd Cross Street in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6097,Road Cut,Completed,NJ-TEYNAMPET,122,1583000,"Improvement works to interior BT Roads at Alwarpet Street in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6099,Road Cut,Completed,NJ-TEYNAMPET,122,1563000,"Improvement works to interior BT Roads at Louts Colony 1st street in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6100,Roads,Completed,NJ-TEYNAMPET,122,969000,"Improvement works to interior BT Roads at Nandanam 1st Main Road in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6101,Road Cut,Completed,NJ-TEYNAMPET,122,386000,"Improvement works to interior BT Roads at Arch Bishop Mathew Avenue in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6102,Road Cut,Completed,NJ-TEYNAMPET,122,1764000,"Improvement works to interior BT Roads at Adayar Club Gate Road in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6103,Road Cut,Completed,NJ-TEYNAMPET,122,1304000,"Improvement works to interior BT Roads at Boat Club Avenue/Boat Club Road in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6104,Road Cut,Completed,NJ-TEYNAMPET,122,241000,"Improvement works to interior BT Road at Boat Club Road in Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/6139,Road Cut,Completed,NJ-TEYNAMPET,122,344000,"Improvement works to interior CC Roads at Ganeshapuram 3rd Streetin Dn 122 in Unit-26,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/7306,Roads,Completed,NJ-TEYNAMPET,122,191000,"Improvement works to interior BT Roads at Alwarpet 3rd Street in DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/7308,Roads,Completed,NJ-TEYNAMPET,122,146000,"Improvement works to interior BT Roads at Alwarpet 4th Street in DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/7309,Roads,Completed,NJ-TEYNAMPET,122,320000,"Improvement works to interior BT Roads at Alwarpet 5th street in DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/7310,Roads,Completed,NJ-TEYNAMPET,122,321000,"Improvement works to interior BT Roads at Seethammal Colony Extn 1st cross street in DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/8324,Storm Water Drain,Completed,NJ-TEYNAMPET,122,120000,"DESILTING OF STORM WATER DRAIN AT GANESAPURAM 2ND STREET IN DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8325,Storm Water Drain,Completed,NJ-TEYNAMPET,122,142000,"DESILTING OF STORM WATER DRAIN AT GANESAPURAM 3RD STREET IN DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8328,Storm Water Drain,Completed,NJ-TEYNAMPET,122,60000,"DESILTING OF STORM WATER DRAIN AT GANESAPURAM 4TH STREET IN DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8349,Storm Water Drain,Completed,NJ-TEYNAMPET,122,90000,"DESILTING OF STORM WATER DRAIN AT NANDANAM 1ST STREET IN DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8350,Storm Water Drain,Completed,NJ-TEYNAMPET,122,170000,"DESILTING OF STORM WATER DRAIN AT S.M.NAGAR IN DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/8352,Storm Water Drain,Completed,NJ-TEYNAMPET,122,51000,"DESILTING OF STORM WATER DRAIN AT CHAMIERS 1ST LANE IN DN 122, UNIT-26,ZONE-9",Own Sources,9,2017-18,2017-18 NJ/2017-18/9093,Storm Water Drain,Completed,NJ-TEYNAMPET,122,150000,"Minor repair works to Storm water Drain at various streets (Chamiers Road, Pughs Road, K.B.Dasan Road,Chittaranjan Road, Turnbulls Road, Nandanam 1st main Road, Nandanam 12th Street , Nandanam 10th Street , ABM Avenue Road, Cresent Street and Cenetoph Road ) in Div-122,Unit-26,Zone-9",Own Sources,9,2017-18,2017-18 B/2017-18/0540,Buildings,Completed,B-Buildings,123,3757000,"CONSTRUCTION OF ADDITIONAL CLAAS ROOMS IN FIRST FLOOR OVER THE EXISTING ANGANVADI BUILDING AT CHENNAI PRIMARY SCHOOL, APPADURAI STREET, IN DN-123, UNIT-25, ZONE-09 CHENNAI-18",MLACDS,9,2017-18,2018-19 BR/2017-18/11884,Road Cut,Completed,BR-Bus Route Roads,123,85000,"Restoration of Road cut made by CMWSSB at R.A.PURAM ABHIRAMAPURAM in Dn-123, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/1857,Road Cut,Completed,BR-Bus Route Roads,123,102000,Restoration of Roadcut made by Airtel at Bus Route Roads ( 1 Road) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/1873,Road Cut,Completed,BR-Bus Route Roads,123,395000,Restoration of Roadcut made by AIRTEL at Various Bus Route Roads ( 4 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/1875,Road Cut,Completed,BR-Bus Route Roads,123,348000,Restoration of Roadcut made by AIRTEL at Various Bus Route Roads ( 4 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/1877,Road Cut,Completed,BR-Bus Route Roads,123,219000,Restoration of Roadcut made by AIRTEL at Various Interior Roads ( 2 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/1878,Road Cut,Completed,BR-Bus Route Roads,123,287000,Restoration of Roadcut made by IDEA at Various Bus Route Roads ( 2 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/1879,Road Cut,Completed,BR-Bus Route Roads,123,771000,Restoration of Roadcut made by VODAFONE at Various Interior Roads ( 13 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/1959,Road Cut,Completed,BR-Bus Route Roads,123,296000,Restoration of Roadcut made by VODAFONE at Bus Route Roads ( 1 Road) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2081,Road Cut,Completed,BR-Bus Route Roads,123,674000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 16 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2106,Road Cut,Completed,BR-Bus Route Roads,123,868000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 6 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2118,Road Cut,Completed,BR-Bus Route Roads,123,962000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 7 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/7405,Road Cut,Completed,BR-Bus Route Roads,123,38000,"Restoration of road cut made by CMWSSB and TNEB at C.P.Ramasamy Road and St Marys Road( using cold milling,Earth work&Ready mix concrete work) in Dn-123, Zone-9",Deposit Works,9,2017-18,2018-19 BR/2017-18/7408,Road Cut,Completed,BR-Bus Route Roads,123,47000,"Restoration of road cut made by CMWSSB and TNEB at C.P.Ramasamy Road (Ready mix concrete work) in Dn-123, Zone-9",Deposit Works,9,2017-18,2018-19 BR/2017-18/7411,Road Cut,Completed,BR-Bus Route Roads,123,113000,"Restoration of road cut made by CMWSSB and TNEB at C.P.Ramasamy Road and St Marys Road(Ready mix concrete work,Prime coat) in Dn-123, Zone-9",Deposit Works,9,2017-18,2018-19 BR/2017-18/7416,Road Cut,Completed,BR-Bus Route Roads,123,104000,"Restoration of road cut made by CMWSSB and TNEB at C.P.Ramasamy Road using Bituminous concrete in Dn-123, Zone-9 (Challan No.BR/2016-17/0017324)",Deposit Works,9,2017-18,2018-19 L/2017-18/10299,Electrical,Completed,L-Electrical,123,441600,"Provision of CCTV Camera and Other Electrical works for Smart class ( Three rooms) at CHS School Beemanna Garden Div-123 , CGHS School Nungambakkam Div-110 and CH School Triplicane High road Div-116 in Zone 9.",Own Sources,9,2017-18,2018-19 L/2017-18/14578,Electrical,Completed,L-Electrical,123,987200,"Erection of 12 nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single Arch Bracket with 12 nos 90w-120w LED fitting,7 nos of 6 Mtr Hot dip Zinc Galvanising Lamp Post Single straight Bracket with 7nos 40w-50w LED fitting at Ananda Road, Ashoka street in Division-123,Zone-IX.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10241,Roads,Completed,NJ-TEYNAMPET,123,2679000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT ABIRAMAPURAM 4TH STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10242,Roads,Completed,NJ-TEYNAMPET,123,1233000,"IMPROVEMENTS TO INTERIOR B.T.ROAD AT DEMONTE COLONY IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10243,Roads,Completed,NJ-TEYNAMPET,123,561000,"IMPROVEMENTS TO INTERIOR B.T.ROAD AT JUSTICE SUNDARAM ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10244,Roads,Completed,NJ-TEYNAMPET,123,363000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT RAMACHANDRA ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/10575,Buildings,Completed,NJ-TEYNAMPET,123,190000,"IMPROVEMENTS TO SMART CLASS ROOM AT BEEMANNA GARDEN STREET (CHENNAI HIGHER SECONDARY SCHOOL) IN DIVISION.123,UNIT.25,ZONE.09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13739,Roads,Completed,NJ-TEYNAMPET,123,867000,"IMPROVEMENTS TO INTERIOR B.T.ROAD AT PALLAKUMANAGAR IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13740,Roads,Completed,NJ-TEYNAMPET,123,1784000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT KABALITHOTTAM IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13741,Roads,Completed,NJ-TEYNAMPET,123,549000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT BHARATHIYAR STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13742,Roads,Completed,NJ-TEYNAMPET,123,1004000,"IMPROVEMENTS TO THE BT ROAD AT R.A.PURAM 6TH MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13743,Roads,Completed,NJ-TEYNAMPET,123,688000,"IMPROVEMENTS TO BT ROAD AT R.A.PURAM 7TH MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13744,Roads,Completed,NJ-TEYNAMPET,123,503000,"IMPROVEMENTS TO THE BT ROAD AT SUBARAMANIYAM STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13745,Roads,Completed,NJ-TEYNAMPET,123,426000,"IMPROVEMENTS TO BITUMINOUS ROAD WITH BCCMP 40MM THICK USING PAVER FINISH AT SUNDERRAJAN STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13773,Buildings,Completed,NJ-TEYNAMPET,123,927000,"IMPROVEMENTS TO INTERIOR CEMENT CONCRETE ROAD WITH M30MM GRADE CONCRETE AT PERIYAR SALAI IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13774,Roads,Completed,NJ-TEYNAMPET,123,1016000,"IMPROVEMENTS TO INTERIOR B.T. ROAD AT SRIRAM COLONY IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/13775,Roads,Completed,NJ-TEYNAMPET,123,1006000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NYNAN STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/14246,Footpath,Completed,NJ-TEYNAMPET,123,1100000,"REPAIRS AND IMPROVEMENTS TO EXISTING GRANITE FOOTPATH AT ANANDHA ROAD (BOTH SIDE) IN DN.123, UNIT.25,ZONE.09",Own Sources,9,2017-18,2018-19 NJ/2017-18/16050,Footpath,Completed,NJ-TEYNAMPET,123,1000000,"SUPPLYING AND FIXING OF BOLLARDS AND STAINLESS STEEL HAND RAIL FOR FOOTPATH AT ANANDA ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2017-18,2018-19 NJ/2017-18/16080,Playfields,Completed,NJ-TEYNAMPET,123,425000,"SUPPLY AND ERECTION OF GYM EQUIPMENTS FOR GYM AT PALLAKKUMANIAM IN DN.123,UNIT.25,ZONE.09(MLA SCHEME 2017-18)",MLACDS,9,2017-18,2018-19 NJ/2017-18/8321,Storm Water Drain,Completed,NJ-TEYNAMPET,123,61000,"DESILTING OF STORM WATER DRAIN AT R.A.PURAM 2ND CROSS STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8323,Storm Water Drain,Completed,NJ-TEYNAMPET,123,54000,"DESILTING OF STORM WATER DRAIN AT R.A.PURAM 3RD CROSS STREET IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8327,Storm Water Drain,Completed,NJ-TEYNAMPET,123,145000,"DESILTING OF STORM WATER DRAIN AT R.A.PURAM 2ND MAIN ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8331,Storm Water Drain,Completed,NJ-TEYNAMPET,123,18000,"DESILTING OF STORM WATER DRAIN AT ANANDHA ROAD IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8333,Storm Water Drain,Completed,NJ-TEYNAMPET,123,95000,"DESILTING OF STORM WATER DRAIN AT THIRUVALLUVAR SALAI IN DN-123, UNIT-25, ZONE-9.",Own Sources,9,2017-18,2017-18 NJ/2017-18/9074,Storm Water Drain,Completed,NJ-TEYNAMPET,123,400000,"REPAIRS TO EXISTING DAMAGED STORM WATER DRAIN AT C.V.RAMAN SALAI,R.A.PURAM 3RD MAIN ROAD AND R.A.PURAM 3RD CROSS STREET IN DN. 123,UNIT.25,ZONE.09",Own Sources,9,2017-18,2017-18 BR/2017-18/1960,Road Cut,Completed,BR-Bus Route Roads,124,759000,Restoration of Roadcut made by VODAFONE at Various Bus Route Roads ( 4 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/1961,Road Cut,Completed,BR-Bus Route Roads,124,601000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 8 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2085,Road Cut,Completed,BR-Bus Route Roads,124,761000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various bus Route Roads ( 12 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2086,Road Cut,Completed,BR-Bus Route Roads,124,761000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various bus Route Roads ( 12 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2104,Road Cut,Completed,BR-Bus Route Roads,124,868000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 8 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2119,Road Cut,Completed,BR-Bus Route Roads,124,923000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 7 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 NJ/2017-18/10778,Roads,Completed,NJ-TEYNAMPET,124,410000,"Laying Wet mix Macadam Water Logging Area at V.C Garden 1st Street in Division- 124 Unit-25, Zone-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13770,Roads,Completed,NJ-TEYNAMPET,124,736000,"Improvements to the Existing B.T.Road at V.C Garden 1st street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13794,Roads,Completed,NJ-TEYNAMPET,124,837000,"Improvements to the Existing Cement Concrete Road at Ramakrishnapuram 5th Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13795,Roads,Completed,NJ-TEYNAMPET,124,837000,"Improvements to the Existing Cement Concrete Road at Ramakrishnapuram 6th Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13796,Roads,Completed,NJ-TEYNAMPET,124,846000,"Improvements to the Existing B.T. Road at Madhava Perumal Koil Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13797,Roads,Completed,NJ-TEYNAMPET,124,200000,"Improvements to the Existing B.T. Road at Mundagakanni Amman 4th Lane in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13799,Roads,Completed,NJ-TEYNAMPET,124,219000,"Improvements to the Existing B.T. Road at Kesavaperumal West Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13800,Roads,Completed,NJ-TEYNAMPET,124,204000,"Improvements to the Existing B.T. Road at Sengazhuneer Pillaiyar Koil Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13801,Roads,Completed,NJ-TEYNAMPET,124,190000,"Improvements to the Existing B.T. Road at Lala Thottam in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13802,Roads,Completed,NJ-TEYNAMPET,124,606000,"Improvements to the Existing B.T. Road at New Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13809,Roads,Completed,NJ-TEYNAMPET,124,1574000,"Improvements to the Existing B.T. Road at Alamelumangapuram in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13812,Roads,Completed,NJ-TEYNAMPET,124,716000,"Improvements to the Existing B.T. Road at DACH Arunachalam Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13813,Roads,Completed,NJ-TEYNAMPET,124,250000,"Improvements to the Existing B.T. Road at Nallappan Street in Dn - 124,Unit - 25,Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/16004,Buildings,Completed,NJ-TEYNAMPET,124,270000,Repairs and improvements to Existing Chennai Primary School Building at Ramakrishnapuram in Division - 124 Unit - 25 Zone -9,Own Sources,9,2017-18,2018-19 NJ/2017-18/16006,Buildings,Completed,NJ-TEYNAMPET,124,175000,Repairs and improvements to NNMP Shed Existing Building at Nattan Thottam A Block in Division - 124 Unit - 25 Zone -9,Own Sources,9,2017-18,2018-19 NJ/2017-18/16007,Buildings,Completed,NJ-TEYNAMPET,124,180000,Repairs and improvements to NNMP Shed Existing Building at Nattan Thottam B Block in Division - 124 Unit - 25 Zone -9,Own Sources,9,2017-18,2018-19 NJ/2017-18/16958,Storm Water Drain,Completed,NJ-TEYNAMPET,124,500000,Construction of Road Side Drain at Kutchery Road in Division - 124 Unit - 25 Zone - 9,Own Sources,9,2017-18,2018-19 NJ/2017-18/16959,Storm Water Drain,Completed,NJ-TEYNAMPET,124,800000,Construction of Road Side Drain at Nattan Thottam in Division - 124 Unit - 25 Zone - 9,Own Sources,9,2017-18,2018-19 NJ/2017-18/16960,Storm Water Drain,Completed,NJ-TEYNAMPET,124,1350000,Construction of Road Side Drain at Styn Marrys Road in Division - 124 Unit - 25 Zone - 9,Own Sources,9,2017-18,2018-19 NJ/2017-18/8374,Storm Water Drain,Completed,NJ-TEYNAMPET,124,110039,Desilting Strom water drain at Mosque street in Dn -124 Unit -25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8377,Storm Water Drain,Completed,NJ-TEYNAMPET,124,30000,Desilting Strom water drain at Saradhapuram Main Road in Dn -124 Unit -25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8378,Storm Water Drain,Completed,NJ-TEYNAMPET,124,78000,Desilting Strom water drain at Alamelumangapuram in Dn -124 Unit -25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8379,Storm Water Drain,Completed,NJ-TEYNAMPET,124,25000,Desilting Strom water drain at Saradhapuram 2nd Street in Dn -124 Unit -25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8380,Storm Water Drain,Completed,NJ-TEYNAMPET,124,33000,Desilting Strom water drain at Mandaveli Street and Lane in Dn -124 Unit -25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8381,Storm Water Drain,Completed,NJ-TEYNAMPET,124,132000,Desilting Strom water drain at Venkatesa Agrakaram Street in Dn -124 Unit -25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/8382,Storm Water Drain,Completed,NJ-TEYNAMPET,124,69000,Desilting Strom water drain at R K Mutt Road in Dn -124 Unit -25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/9079,Storm Water Drain,Completed,NJ-TEYNAMPET,124,40000,Minor repairs work SWD at Venkatesa Agraharam Street in Dn - 124 Unit - 25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/9080,Storm Water Drain,Completed,NJ-TEYNAMPET,124,36000,Minor repairs work SWD at St.Marys Road in Dn - 124 Unit - 25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/9081,Storm Water Drain,Completed,NJ-TEYNAMPET,124,124000,Minor repairs work SWD at Nattan Thottam (Pipe line) in Dn - 124 Unit - 25 Zone - 09,Own Sources,9,2017-18,2017-18 NJ/2017-18/9082,Storm Water Drain,Completed,NJ-TEYNAMPET,124,100000,Minor repairs work SWD at Ramakrishnapuram in Dn - 124 Unit - 25 Zone - 09,Own Sources,9,2017-18,2017-18 BR/2017-18/12984,Roads,Completed,BR-Bus Route Roads,125,950000,Providing painting and repairs to the footpath kerb & the existing centre median at Santhome High Road in the view of Republic day function in Zone - 9,Own Sources,9,2017-18,2018-19 BR/2017-18/13648,Road Cut,Completed,BR-Bus Route Roads,125,94000,"Restoration of Road cut made by CMWSSB at SANTHOME ROAD in Dn-125, Zone-9.",Deposit Works,9,2017-18,2018-19 BR/2017-18/2120,Road Cut,Completed,BR-Bus Route Roads,125,884000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Bus Route Roads ( 8 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2123,Road Cut,Completed,BR-Bus Route Roads,125,570000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 14 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2124,Road Cut,Completed,BR-Bus Route Roads,125,910000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 21 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/2128,Road Cut,Completed,BR-Bus Route Roads,125,690000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 18 Roads) in Zone -9,Deposit Works,9,2017-18,2018-19 BR/2017-18/6012,Road Cut,Completed,BR-Bus Route Roads,125,49800,Restoration of Roadcut made by AIRTEL at Various Bus Route Roads ( 1 Road) in Zone -9,Deposit Works,9,2017-18,2018-19 NJ/2017-18/0377,Buildings,Completed,NJ-TEYNAMPET,125,470000,"Improvement Works to Compound Wall and Playground at Ekambaram Street in Div-125, U-25, Zone-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/0508,Buildings,Completed,NJ-TEYNAMPET,125,760000,"New construction of Chimney at Mylapore Burial Ground in Division-125, Unit-25, Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/0870,Playfields,Completed,NJ-TEYNAMPET,125,925000,"Improvement works to the Play Ground at Loop Road in Dn-125, Unit-25, Zone-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/10166,Buildings,Completed,NJ-TEYNAMPET,125,600000,CONSTRUCTION OF ADDITIONAL ROOMS COMMUNITY CENTRE AT KARANEESWARER PAGODA STREET DIV-125 UNIT-25 ZONE-09,MPLADS,9,2017-18,2018-19 NJ/2017-18/13825,Roads,Completed,NJ-TEYNAMPET,125,540000,"Improvements works to the BT Road at Prof.Sanjivi Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13826,Roads,Completed,NJ-TEYNAMPET,125,337000,"Improvements works to the BT Road at Salai Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13827,Roads,Completed,NJ-TEYNAMPET,125,1215000,"Improvements works to the BT Road at Bazaar Road in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13828,Roads,Completed,NJ-TEYNAMPET,125,224000,"Improvements works to the BT Road at Nochikuppam Slum Road in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/13829,Roads,Completed,NJ-TEYNAMPET,125,709000,"Improvements works to the CC Road at Pidariyar Koil Street & Lane in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/14396,Roads,Completed,NJ-TEYNAMPET,125,850000,"Proposal of Cement Concrete Road at Mangollai (MLA FUND) in Div-125, U-25, Z-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/14397,Buildings,Completed,NJ-TEYNAMPET,125,423000,"Providing GYM Apparatus to GYM Building (MLA FUND ) at Kailasapuram in Dn-125, Unit-25, Zone-9.",MLACDS,9,2017-18,2018-19 NJ/2017-18/14398,Parks,Completed,NJ-TEYNAMPET,125,300000,"Proposal of New Park (MLA FUND) at Kuyil Thottam in Div-125, U-25, Z-09",MLACDS,9,2017-18,2018-19 NJ/2017-18/1487,Roads,Completed,NJ-TEYNAMPET,125,369000,"Improvements works to the BT Road at Lalitha Nagar 1st Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/1488,Roads,Completed,NJ-TEYNAMPET,125,336000,"Improvements works to the BT Road at Lalitha Nagar 2nd Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/1491,Roads,Completed,NJ-TEYNAMPET,125,470000,"Improvements works to the BT Road at Papanasam Sivan Salai in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/17038,Roads,Completed,NJ-TEYNAMPET,125,856000,"Attending Patch work of BT road with BC 40 mm Papanasam Sivan Salai at in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/17147,Roads,Completed,NJ-TEYNAMPET,125,340000,"Improvements to the Existing B.T.Road at Kuyil Thottam in Dn-125, Unit -25, Zone - 09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5329,Parks,Completed,NJ-TEYNAMPET,125,405000,"OUTSOURCING FOR SECURITY AND MAINTENANCE OF LAWN 13, 13-A AND 14 AT MARINA BEACH IN DIV-125, U-27A, Z-9.",Own Sources,9,2017-18,2018-19 NJ/2017-18/5624,Roads,Completed,NJ-TEYNAMPET,125,1007000,"Improvements works to the BT Road at Muthu Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5625,Roads,Completed,NJ-TEYNAMPET,125,1194000,"Improvements works to the BT Road at Karaneeswarar Koil Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5636,Roads,Completed,NJ-TEYNAMPET,125,329000,"Improvements works to the BT Road at Karaneeswarar Koil 1st Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5637,Roads,Completed,NJ-TEYNAMPET,125,379000,"Improvements works to the BT Road at Karaneeswarar Koil 2nd Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5640,Roads,Completed,NJ-TEYNAMPET,125,302000,"Improvements works to the BT Road at Valleswarar Koil Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5642,Roads,Completed,NJ-TEYNAMPET,125,1258000,"Improvements works to the BT Road at Rosary Church Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5644,Roads,Completed,NJ-TEYNAMPET,125,909000,"Improvements works to the BT Road at Sullivan Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5645,Roads,Completed,NJ-TEYNAMPET,125,470000,"Improvements works to the BT Road at Muthukrishnan Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5646,Roads,Completed,NJ-TEYNAMPET,125,234000,"Improvements works to the CC Road at Syed Nabimullah Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5647,Roads,Completed,NJ-TEYNAMPET,125,234000,"Improvements works to the CC Road at Syed Wahab Hussain Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5648,Roads,Completed,NJ-TEYNAMPET,125,234000,"Improvements works to the CC Road at Syed Ahamed Hussain Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5651,Roads,Completed,NJ-TEYNAMPET,125,774000,"Improvements works to the CC Road at Pidariyar Koil Street & Lane in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/6003,Roads,Completed,NJ-TEYNAMPET,125,453000,"Improvements works to the BT Road at Venkatasamy Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/6007,Roads,Completed,NJ-TEYNAMPET,125,805000,"Improvements works to the BT Road at G.N Street in Div-125, U-25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/8307,Storm Water Drain,Completed,NJ-TEYNAMPET,125,42000,"Desilting of Storm Water Drain at Dr.Radhakrishnan Salai in Div-125, Unit-25, Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8309,Storm Water Drain,Completed,NJ-TEYNAMPET,125,90000,"Desilting of Storm Water Drain at St.Bedes Ground in Div-125, Unit-25, Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8311,Storm Water Drain,Completed,NJ-TEYNAMPET,125,59000,"Desilting of Storm Water Drain at Dr.Natesan Road in Div-125, Unit-25, Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8312,Storm Water Drain,Completed,NJ-TEYNAMPET,125,19000,"Desilting of Storm Water Drain at Mylapore Burial Ground in Div-125, Unit-25, Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8314,Storm Water Drain,Completed,NJ-TEYNAMPET,125,157000,"Desilting of Storm Water Drain at Karaneeswarar Pagoda Street in Div-125, Unit-25, Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8316,Storm Water Drain,Completed,NJ-TEYNAMPET,125,11000,"Desilting of Storm Water Drain at Prof.Sanjivi Street in Div-125, Unit-25, Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/8317,Storm Water Drain,Completed,NJ-TEYNAMPET,125,12000,"Desilting of Storm Water Drain at P.V.Koil Street in Div-125, Unit-25, Zone-09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9096,Storm Water Drain,Completed,NJ-TEYNAMPET,125,50000,"Minor repairs work SWD at Karneeswarar Pakoda Street Street in Dn - 125, Unit - 25, Zone - 09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9098,Storm Water Drain,Completed,NJ-TEYNAMPET,125,25000,"Minor repairs work SWD at Sundareswarar Swamy Street in Dn -125, Unit - 25, Zone - 09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9099,Storm Water Drain,Completed,NJ-TEYNAMPET,125,25000,"Minor repairs work SWD at East Mada Street in Dn -125, Unit - 25, Zone - 09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9100,Storm Water Drain,Completed,NJ-TEYNAMPET,125,120000,"Minor repairs work SWD (PVC Pipe Line) at Kamarajar salai in Dn -125, Unit - 25, Zone - 09",Own Sources,9,2017-18,2017-18 NJ/2017-18/9103,Storm Water Drain,Completed,NJ-TEYNAMPET,125,80000,"Minor repairs work SWD at VenkataSwamy Street in Dn-125, Unit - 25, Zone - 09",Own Sources,9,2017-18,2017-18 BR/2017-18/12989,Footpath,Completed,BR-Bus Route Roads,126,970000,Providing painting and repairs to the footpath kerb & the existing centre median at Pasumpon Muthuramalinga devar salai and Turnbulls Road in the view of Republic day function in Zone - 9,Own Sources,9,2017-18,2018-19 BR/2017-18/4985,Roads,Completed,BR-Bus Route Roads,126,988000,"Providing and laying of Thermoplastic painting & studs at Peters Road, Babu jagajeevanram Salai,Quide Millath Road, South Canal Bank Road, Madha Church Road, Luz Church Road and other various Bus Route Roads in Zone - 9",Own Sources,9,2017-18,2017-18 BR/2017-18/5668,Roads,Completed,BR-Bus Route Roads,126,988000,"Providing and laying of Thermoplastic painting & studs at Vepry hgh road, purasawakkam high road, EVK Sampath salai, Rajaji salai, NSC Bose road, Egmore and other various Bus Route Roads in Zone - 5",Own Sources,9,2017-18,2018-19 NJ/2017-18/0683,Parks,Completed,NJ-TEYNAMPET,126,250000,"OUT SOURCING FOR PARK BY PRIVATE AGENCY AT LOOP ROAD (FOR 9 MONTHS ) IN DIV 126,UNIT-25,ZONE-9 (BY QUALIFIED HORTICULTURIST)",Own Sources,9,2017-18,2018-19 NJ/2017-18/0875,Buildings,Completed,NJ-TEYNAMPET,126,321000,"Improvement of Alphonsa Play Ground Compound Wall at South Canal Bank Road in DN-126, UNIT-25, ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/12165,Buildings,Completed,NJ-TEYNAMPET,126,1300000,REPAIR AND IMPROVEMENT TO ALFONSA GROUND IN BADMINTON COURT STADIUM AT SOUTH CANAL BANK ROAD IN DIV- 126 U -25 Z -9,Own Sources,9,2017-18,2019-20 NJ/2017-18/12166,Roads,Completed,NJ-TEYNAMPET,126,1317000,"IMPROVEMENT WORKS TO THE BT ROAD AT 2ND TRUST MAIN ROAD IN DIV-126, U -25, Z-09",Own Sources,9,2017-18,2018-19 NJ/2017-18/5787,Roads,Completed,NJ-TEYNAMPET,126,771000,"Improvements works to the BT Road at Srinivasan Street in Dn 126,Unit-25,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/5791,Roads,Completed,NJ-TEYNAMPET,126,603999,"Improvements works to the BT Road at Sivaraman Street in Dn 126,Unit-25,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/5800,Roads,Completed,NJ-TEYNAMPET,126,453000,"Improvements works to the BT Road at Mari Street in Dn 126,Unit-25,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/5813,Roads,Completed,NJ-TEYNAMPET,126,654000,"Improvements works to the BT Road at Adanjan Street in Dn 126,Unit-25,Zone-9",Own Sources,9,2017-18,2018-19 NJ/2017-18/8067,Roads,Completed,NJ-TEYNAMPET,126,870000,"ARRANGEMENTS TO SCAFFOLDING, CHAIR AND PANDHAL FOR IMMERSION OF VINAYAGAR STATUE AT LOOP ROAD BEACH IN DIV - 126, UNIT - 25, ZONE - 09",Own Sources,9,2017-18,2019-20 NJ/2017-18/8460,Storm Water Drain,Completed,NJ-TEYNAMPET,126,96950,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN AT JETH NAGAR 1ST CROSS STREET IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8466,Storm Water Drain,Completed,NJ-TEYNAMPET,126,74997,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN IN JETH NAGAR 3RD STREET IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8468,Storm Water Drain,Completed,NJ-TEYNAMPET,126,67912,"DE-SILTING AND MINOR REPAIRS OF STORM WATER DRAIN IN 4TH TRUST MAIN ROAD,DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8470,Storm Water Drain,Completed,NJ-TEYNAMPET,126,63975,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN AT 5TH TRUST CROSS STREET IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8475,Storm Water Drain,Completed,NJ-TEYNAMPET,126,95000,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN IN SANTHOME HIGH ROAD IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8477,Storm Water Drain,Completed,NJ-TEYNAMPET,126,130000,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN IN R.K.MUTT ROAD AT DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8479,Storm Water Drain,Completed,NJ-TEYNAMPET,126,218000,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN IN SOUTH CANAL BANK ROAD IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8481,Storm Water Drain,Completed,NJ-TEYNAMPET,126,125000,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN IN DEVANATHAN ROAD IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8484,Storm Water Drain,Completed,NJ-TEYNAMPET,126,125000,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN IN LAZURAS CHURCH ROAD IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/8485,Storm Water Drain,Completed,NJ-TEYNAMPET,126,123000,"DE-SILTING AND MINOR REPAIR OF STORM WATER DRAIN IN 2ND TRUST MAIN ROAD IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2017-18,2017-18 NJ/2017-18/9090,Storm Water Drain,Completed,NJ-TEYNAMPET,126,500000,"REPAIRS TO EXISTING DAMAGED STORM WATER DRAIN AT DAVANATHAN STREET, SOUTH CANAL BANK STREET, 10TH TRUSS LINK STREET, THIRUVENGADAM STREET, R.K.MUTT ROAD, SANTHOME HIGH ROAD, 4TH TRUST LINK STREET AND JETH NAGAR 3RD STREET IN DN. 126,UNIT.25,ZONE.09",Own Sources,9,2017-18,2017-18 P/2017-18/7889,Parks,Completed,P-Parks and Playfields,126,16077975,"CREATION OFA MODEL SENSORY PARK AND GARDEN FOR ALL ABILITIES IN THE EXISITING PLAY GROUND ABUTTING THE CHENNAI MIDDLE SCHOOL 4^th LINK TRUST ROAD,SANTHOME",Grants,9,2017-18,2019-20 B/2017-18/16558,Buildings,Completed,B-Buildings,127,6134672,REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE IN ZONE-10,Own Sources,10,2017-18,2019-20 BR/2017-18/14589,Buildings,Completed,BR-Bus Route Roads,127,1714000,"PROPOSED DEMOLITION AND RECONSTRUCTION OF CMDA COMPOUND WALL OF FLOWER MARKET AT KALIYAMMAN KOVIL STREET IN DIV-127, ZONE-10",Own Sources,10,2017-18,2018-19 BR/2017-18/15110,Roads,Completed,BR-Bus Route Roads,127,2481000,Repairs and Improvement works at Kaliamman koil Street by providing thermoplastic painting & restoration of road cut in Zone - 10,Own Sources,10,2017-18,2019-20 BR/2017-18/2125,Road Cut,Completed,BR-Bus Route Roads,127,896000,Restoration of Roadcut made by Reliance Jio Infocom Ltd at Various Interior Roads ( 15 Roads) in Zone -9,Deposit Works,10,2017-18,2018-19 L/2017-18/0361,Electrical,Completed,L-Electrical,127,1400100,"PROVISION OF 22NOS OF OLD EL LAMP POST WITH DOUBLE BRACKET WITH 90W AND 40W LED FITTING AT NERKUNDRUM VILLAGE IN DIVISION -127, ZONE-X",Own Sources,10,2017-18,2017-18 L/2017-18/1040,Electrical,Completed,L-Electrical,127,199200,Painting of 374 Numbers of street lamp posts and parks lamp post at games village in division 127 zone-x,Own Sources,10,2017-18,2017-18 L/2017-18/10602,Electrical,Completed,L-Electrical,127,508100,"Erection of 12 nos old lamp post and 91 nos of 4x16sqmm alu cable joint work and 35 nos 2x16sqmm aiu cable joint work at Games village in div-127,Zone-10",Own Sources,10,2017-18,2018-19 L/2017-18/13564,Electrical,Completed,L-Electrical,127,1494500,Provision of 8 nos of 6 mtr lamp post with Single arch bracket with 8 nos 90w LED Fitting and 7 nos of 8 mtr Lamp post with 150w LED Fitting and 10 nos of 6 mtr staright bracket with 40w LED Fitting at West Natesan nagar division 127 in Zone-10,Own Sources,10,2017-18,2018-19 L/2017-18/6448,Electrical,Completed,L-Electrical,127,559400,Errection of 3 nos old 8mtr lamp post and Replacement of 1040 mtrs 4 X 16 sqmm alu cable at Jai nagar 1st and 2nd main road in Div-127 zone-10,Own Sources,10,2017-18,2017-18 L/2017-18/6460,Electrical,Completed,L-Electrical,127,428400,Errection of 4 nos 7 mtr old lamp post and Replacement of 822 mtrs 2 X 16 sqmm alu cable at Rathinapuri in Div-127 Zone-10,Own Sources,10,2017-18,2017-18 L/2017-18/6467,Electrical,Completed,L-Electrical,127,665800,Painting and Numbering of 3925 nos of street lamp post in all streets and 105 nos of KYOSK type pillar box at Div-127 & 128 Zone-10,Own Sources,10,2017-18,2018-19 L/2017-18/6526,Electrical,Completed,L-Electrical,127,494500,REPLACEMENT OF1056 MTRS 2 X 16 SQMM ALU CABLE AT T.S.D.NAGAR IN DIV-127 ZONE-10,Own Sources,10,2017-18,2017-18 L/2017-18/6618,Electrical,Completed,L-Electrical,127,559100,Errection of 4 nos 9.5 mtrs old lamp post and Replacement of 1073 mtrs 4 X 16 sqmm alu cable at Valluvar salai in Div-127 Zone-10,Own Sources,10,2017-18,2017-18 NK/2017-18/1109,Roads,Completed,NK-KODAMBAKKAM,127,210000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT SAF GAMES VILLAGE 1ST CROSS STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/12192,Buildings,Completed,NK-KODAMBAKKAM,127,2360000,"Construction of Compound wall at West natesan nagar in div-127, unit-29, zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/12298,Footpath,Completed,NK-KODAMBAKKAM,127,2250000,"Forming road side park at West natesan nagar in div-127, unit-29, zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/12368,Roads,Completed,NK-KODAMBAKKAM,127,1220000,"Widening of the road using Bituminous Concrete and Providing Speed Breakers as per IRC Design at West natesan nagar ,Natesan nagar 2nd main road and 3rd main road in DN-127, U-29, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12570,Roads,Completed,NK-KODAMBAKKAM,127,640000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Chinmaya nagar Extn - 2 1st street , Reach - 1 ,in D-127, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12574,Roads,Completed,NK-KODAMBAKKAM,127,638000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Chinmaya nagar EXTN - 1st street , Reach - 2, in D-127, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12575,Roads,Completed,NK-KODAMBAKKAM,127,722000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Venkateswara nagar 1st main road reach - 1 in D-127, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12576,Roads,Completed,NK-KODAMBAKKAM,127,684000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Venkateswara nagar 1st main road reach - 2 in D-127, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12577,Roads,Completed,NK-KODAMBAKKAM,127,831000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Sai Nagar 5 th Street in D-127, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12578,Roads,Completed,NK-KODAMBAKKAM,127,752000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Chinmaya Nagar EXTN - 2 , 2nd street,DN-127, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/13335,Roads,Completed,NK-KODAMBAKKAM,127,168100,"IMPROVEMENTS TO ROAD AT AYYAPPA NAGAR CROSS STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13336,Roads,Completed,NK-KODAMBAKKAM,127,336200,"IMPROVEMENT TO ROAD AT JAI NAGAR 19TH STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13337,Roads,Completed,NK-KODAMBAKKAM,127,1227130,"IMPROVEMENTS TO ROAD AT SOUTH MADA STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13352,Roads,Completed,NK-KODAMBAKKAM,127,336200,"IMPROVEMENTS TO ROAD AT YAMUNA STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13353,Roads,Completed,NK-KODAMBAKKAM,127,941360,"IMPROVEMENT TO ROAD AT 1st CROSS STREET NATESAN NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13354,Roads,Completed,NK-KODAMBAKKAM,127,393350,"IMPROVEMENTS TO ROAD AT 3rd MAIN ROAD NATESAN NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13355,Roads,Completed,NK-KODAMBAKKAM,127,292500,"IMPROVEMENTS TO ROAD AT WEST MAIN ROAD NATESAN NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13356,Roads,Completed,NK-KODAMBAKKAM,127,759800,"IMPROVEMENTS TO ROAD AT CHITHIRAI STREET CHINMAYA NAGAR STAGE II IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13357,Roads,Completed,NK-KODAMBAKKAM,127,1344000,"IMPROVEMENTS TO ROAD AT NERKUNDRAM SALAI IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13358,Roads,Completed,NK-KODAMBAKKAM,127,2020000,"IMPROVEMENTS TO ROAD AT JAI NAGAR 1st MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13359,Roads,Completed,NK-KODAMBAKKAM,127,673000,"IMPROVEMENTS TO ROAD AT VALLUVAR STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13366,Roads,Completed,NK-KODAMBAKKAM,127,2102000,"PROPOSED ROAD WORK AT KUMARAN NAGAR 1st MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13367,Roads,Completed,NK-KODAMBAKKAM,127,1298000,"PROPOSED ROAD WORK AT KUMARAN NAGAR 3rd MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13368,Roads,Completed,NK-KODAMBAKKAM,127,360000,"PROPOSED ROAD WORK AT NATESAN NAGAR 2nd MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13371,Roads,Completed,NK-KODAMBAKKAM,127,336000,"PROPOSED ROAD WORK AT NATESAN NAGAR 3rd MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13372,Roads,Completed,NK-KODAMBAKKAM,127,312000,"PROPOSED ROAD WORK AT NATESAN NAGAR 5th MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13376,Roads,Completed,NK-KODAMBAKKAM,127,552000,"PROPOSED ROAD WORK AT KULASEKARAPURAM MANAVALAN STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13377,Roads,Completed,NK-KODAMBAKKAM,127,576000,"PROPOSED ROAD WORK AT KULASEKARAPURAM VEDHA STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13461,Footpath,Completed,NK-KODAMBAKKAM,127,750000,"Attending maintenance emergency work and patch work Extra work at various street in div-127, unit-29, zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/15747,Roads,Completed,NK-KODAMBAKKAM,127,687300,"PROPOSED ROAD WORK AT 3rd MAIN ROAD NATESAN NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/16265,Roads,Completed,NK-KODAMBAKKAM,127,120000,Improvement to CPS Buliding at Koyambedu school street in Dn-127 U29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16266,Roads,Completed,NK-KODAMBAKKAM,127,32000,Attending patch work using Bituminous concrete at Parijatham street in Dn127 U-29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16267,Roads,Completed,NK-KODAMBAKKAM,127,32000,Attending patch work using Bituminous concrete at Jai nagar 13th street in Dn127 U-29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16268,Roads,Completed,NK-KODAMBAKKAM,127,42000,Attending patch work using Bituminous Concrete at Valluvar street street in Dn-127 U-29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16269,Roads,Completed,NK-KODAMBAKKAM,127,27000,Attending patch work using Bituminous concrete at Avvai thirunagar in DN-127 U-29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16351,Roads,Completed,NK-KODAMBAKKAM,127,26000,Improvement to Anganvaadi at Vedha nagar in Dn-127 U29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16352,Roads,Completed,NK-KODAMBAKKAM,127,41000,Improvement to Anganvaadi at School street TSD Nagar in Dn-127 U29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16353,Roads,Completed,NK-KODAMBAKKAM,127,46000,Improvement to Anganvaadi at Thiruveedhi amman koil street in Dn-127 U29 Z-10,Own Sources,10,2017-18,2019-20 NK/2017-18/16355,Roads,Completed,NK-KODAMBAKKAM,127,154000,"Improvement to CHS at School street,Koyambedu in Dn-127 U29 Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/4925,Roads,Completed,NK-KODAMBAKKAM,127,2445000,"RELAYING OF ROAD USING BC 30MM THICK AT NATESAN NAGAR 1st CROSS STREET, NATESAN NAGAR 4TH MAIN ROAD, IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/4936,Roads,Completed,NK-KODAMBAKKAM,127,2463000,"RELAYING OF ROAD USING BC 30 mm THICK AT NATESAN NAGAR 5TH MAIN ROAD AND CHITTIRAI STREET IN DIV-127, UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5068,Roads,Completed,NK-KODAMBAKKAM,127,2493000,"RELAYING OF ROAD USING BC 30MM THICK AT NATESAN NAGAR 3rd MAIN ROAD, , NATESAN NAGAR 2ND MAIN ROAD, IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5072,Roads,Completed,NK-KODAMBAKKAM,127,1142000,"RELAYING OF ROAD USING BC 30MM THICK AT RAMALINGA NAGAR IN DIV-127, UNIT-29, ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/7467,Roads,Completed,NK-KODAMBAKKAM,127,975000,"Rectification of speed breaker at various streets in Div -127,Unit- 29,Zone- 10",Own Sources,10,2017-18,2018-19 NK/2017-18/7912,Parks,Completed,NK-KODAMBAKKAM,127,653000,"ANNUAL MAINTENANCE OF PARK AT JAI NAGAR PARK-2 IN DN-127, U-29, Z- 10.(Employed qualified horticulturist for only)",Own Sources,10,2017-18,2019-20 NK/2017-18/7913,Parks,Completed,NK-KODAMBAKKAM,127,474000,"ANNUAL MAINTENANCE OF PARK AT JAI NAGAR PARK-1 IN DN-127, U-29, Z- 10.(Employed qualified horticulturist for only)",Own Sources,10,2017-18,2019-20 NK/2017-18/7930,Buildings,Completed,NK-KODAMBAKKAM,127,241000,"ENGAGING PRIVATE LABOURS OUT SOURCING WORK AT NATESAN NAGAR UPHC, IN DIV-127, UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/7933,Parks,Completed,NK-KODAMBAKKAM,127,350000,"ENGAGING PRIVATE LABOURS AT OUT SOURCING WORK AND ENGAGING SECURITY GUARDS AT NATESAN NAGAR PARK , IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/7935,Buildings,Completed,NK-KODAMBAKKAM,127,140000,"ENGAGING PRIVATE LABOUR FOR OUT SOURCING WORK OF C.H.S.S KOYAMDEDU FOR 8 MONTHS IN DIV-127, UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/7941,Buildings,Completed,NK-KODAMBAKKAM,127,140000,"ENGAGING PRIVATE LABOUR FOR OUT SOURCING WORK OF C.P.S KOYAMDEDU FOR 8 MONTHS IN DIV-127, UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/7943,Buildings,Completed,NK-KODAMBAKKAM,127,140000,"ENGAGING PRIVATE LABOURS FOR OUTSOURCING AT C.M.S ARUMBAKKAM FOR 8 MONTHS IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/8391,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,600000,"Desilting of Storm Water Drain at Various streets in div 127, Unit-29,Zone-10",Own Sources,10,2017-18,2017-18 NK/2017-18/8406,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,434000,"Minor Repairs to Strorm water drain at Various streets in Div 127, Unit-29, Zone-10",Own Sources,10,2017-18,2017-18 NK/2017-18/8980,Parks,Completed,NK-KODAMBAKKAM,127,1925000,"ENGAGING PRIVATE LABOURS OUT SOURCING WORK AND SECURITY GUARD AT SAF GAMES VILLAGE PARK, IN DIV-127, UNIT-29,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9110,Buildings,Completed,NK-KODAMBAKKAM,127,109000,"ENGAGING SECURITY GUARD AT NATESAN NAGAR UPHC IN DIV-127,UNIT-29,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9501,Roads,Completed,NK-KODAMBAKKAM,127,2215000,"WIDENING OF ROAD IN CEMENT CONCRETE AT WEST NATESAN NAGAR MAIN ROAD IN DIV-127,U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9880,Roads,Completed,NK-KODAMBAKKAM,127,1950000,Improvements to SWD at Kaliyamman koil street ( from Indian oil petrol bunk to koyambedu market 'A' road JN ) in Dn-127 U-29 Z-10,Own Sources,10,2017-18,2018-19 P/2017-18/13698,Parks,Completed,P-Parks and Playfields,127,2378000,"PROPOSED CONSTRUCTION OF WATER FOUNTAIN AT THE OSR LAND AT TNHB QUARTERS PARK, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN -127, ZONE -10",Own Sources,10,2017-18,2019-20 P/2017-18/13699,Parks,Completed,P-Parks and Playfields,127,1459000,"Formation of Park at OSR land at TNHB Quarters Park, Nerkundram, West Natesan NAgar, Erikkarai Street in Division - 127, ZONE - X.",Own Sources,10,2017-18,2019-20 P/2017-18/14641,Parks,Completed,P-Parks and Playfields,127,2331000,"PROVIDING WOODEN FLOORING FOR THE BADMINTON COURT AT THE OSR LAND TNHB QUARTERS PARK, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN -127, ZONE - 10.",Own Sources,10,2017-18,2018-19 P/2017-18/14642,Parks,Completed,P-Parks and Playfields,127,1642000,"SUPPLYING AND FIXING OF OUTDOOR FITNESS GYM EQUIPMENTS AT THE OSR LAND TNHB QUARTERS PARK, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN -127, ZONE -- 10",Own Sources,10,2017-18,2018-19 P/2017-18/14643,Parks,Completed,P-Parks and Playfields,127,2030000,"PROVIDING TENSILE ROOF COVERING FOR OPEN GYM AREA AT THE OSR LAND TNHB QUARTERS PARK, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN -127, ZONE - 10.",Own Sources,10,2017-18,2018-19 P/2017-18/14645,Parks,Completed,P-Parks and Playfields,127,2189000,"CONSTRUCTION OF FRONT SIDE COMPOUND WALL AND AMENITIES FOR DRESS CHANGE ROOM AT THE OSR LALND TNHB QUARTERS PARKS, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN -127, ZONE - 10.",Own Sources,10,2017-18,2018-19 P/2017-18/14647,Parks,Completed,P-Parks and Playfields,127,2132000,"PROVIDING ORNAMENTAL GATE, BENCHES AND NAME BOARD AT THE OSR LAND TNHB QUARTERS PARK, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN -127, ZONE - 10",Own Sources,10,2017-18,2018-19 P/2017-18/14650,Parks,Completed,P-Parks and Playfields,127,1442000,"PROVIDING CHILDRENS PLAY APPARATUS AT THE OSR LAND TNHB QUARTERS PARK NERKUNDRAM WEST NATESAN NAGAR, ERIKKARAI STREET IN DN - 127 ZONE - 10",Own Sources,10,2017-18,2018-19 P/2017-18/14651,Parks,Completed,P-Parks and Playfields,127,2044000,"CONSTRUCTION OF SECURITY ROOM AT THE OSR LAND TNHB QUARTERS PARK NERKUNDRAM, WEST NATESAN NAGAR,ERIKKARAI STRRET IN DN - 127, ZONE - 10",Own Sources,10,2017-18,2018-19 P/2017-18/14652,Parks,Completed,P-Parks and Playfields,127,1874000,PROVIDING FOUNDATION FOR TENSILE ROOF COVERING FOR OPEN GYM AND PROVIDING VITRIFIED TILES FOR BADMINTON COURT,Own Sources,10,2017-18,2018-19 P/2017-18/14653,Parks,Completed,P-Parks and Playfields,127,1533000,"PROVIDING AND LAYING GREY GRANITE SLAB FOR THE PARK AT THE OSR LAND, TNHB QUARTERS PARK, NERKUNDRAM, WEST",Own Sources,10,2017-18,2018-19 P/2017-18/14681,Parks,Completed,P-Parks and Playfields,127,2301000,"CONSTRUCTION OF FILTRATION SUMP FOR FOUNTAIN AND IMPROVEMENTS TO OPEN GYM AREA AT THE OSR LAND TNHB QUARTERS PARK, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN - 127, ZONE - 10.",Own Sources,10,2017-18,2018-19 P/2017-18/14683,Parks,Completed,P-Parks and Playfields,127,2485000,"PROVIDING GAZEBO FOR THE PARK TNHB QUARTERS PARK, NERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN-127, ZONE - 10.",Own Sources,10,2017-18,2018-19 P/2017-18/17675,Parks,Completed,P-Parks and Playfields,127,1530000,"Additional work in IAS Quarters for Water supply arrangements for the park at OSR Land, TNHB Quarters, Nerkundram, West Natesan Nagar, Erikkarai Street in Dn-127, Zone - X.",Own Sources,10,2017-18,2020-21 BR/2017-18/1039,Road Cut,Completed,BR-Bus Route Roads,128,2146000,Restoration of Road cut made by TANGEDGO at Reddy Street in Zone-10,Deposit Works,10,2017-18,2017-18 L/2017-18/6446,Electrical,Completed,L-Electrical,128,900600,"REPLACEMENT OF 1831 MTRS 2 X 16 SQMM ALU CABLE AND 264 MTRS OF 4 x 16 SQ MM ALU CABLE AT RAJESWARICOLONY, THANGAL ST AND VARIOUS LOCATIONS IN DIV-128 ZONE-10",Own Sources,10,2017-18,2017-18 NK/2017-18/0699,Roads,Completed,NK-KODAMBAKKAM,128,605000,Restoration of Road Cut made by TNEB at Kamaraj Salai in Division -128 Unit-29 Zone-10,Deposit Works,10,2017-18,2017-18 NK/2017-18/0701,Roads,Completed,NK-KODAMBAKKAM,128,798000,Restoration of Road Cut made by TNEB at AVM Avenue Road in Division -128 Unit-29 Zone-10,Deposit Works,10,2017-18,2017-18 NK/2017-18/0702,Roads,Completed,NK-KODAMBAKKAM,128,866000,Restoration of Road Cut made by TNEB at Thangal Street in Division -128 Unit-29 Zone-10,Deposit Works,10,2017-18,2017-18 NK/2017-18/10212,Parks,Completed,NK-KODAMBAKKAM,128,1659000,"Proposed Construction Of Park At Thangal Ulvayil Street , Virugambakkam (UNDER MLA SCHEME 2017-18) in Dn - 128, Unit - 29, Zone - X .",MLACDS,10,2017-18,2019-20 NK/2017-18/11467,Buildings,Completed,NK-KODAMBAKKAM,128,977000,"Improvements to Electrical Crematorium and Proposed Sump at Burial Ground , Virugambakkam , Division - 128, Unit -29, Zone - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12562,Roads,Completed,NK-KODAMBAKKAM,128,916000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Pillayar Koil Street in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12563,Roads,Completed,NK-KODAMBAKKAM,128,759000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Raman cross Street and Yadava Street in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12564,Roads,Completed,NK-KODAMBAKKAM,128,998000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Perumal Koil 2nd Street and Vayuputhra Street in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12565,Roads,Completed,NK-KODAMBAKKAM,128,988000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Sornamibiga Nagar 1st Street in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12566,Roads,Completed,NK-KODAMBAKKAM,128,996000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Avenue 2nd Street in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12567,Roads,Completed,NK-KODAMBAKKAM,128,995000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at New Colony 1st Main Road in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12568,Roads,Completed,NK-KODAMBAKKAM,128,680000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Saibaba Colont Link Road in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12569,Roads,Completed,NK-KODAMBAKKAM,128,500000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Annai Sathya Nagar Main Road Road in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12571,Roads,Completed,NK-KODAMBAKKAM,128,930000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at EVR Street ,in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12572,Roads,Completed,NK-KODAMBAKKAM,128,980000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Saibaba Colony Main Road , Reach -1, in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/12573,Roads,Completed,NK-KODAMBAKKAM,128,990000,"Strengthening and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Saibaba Colony Main Road , Reach - 2 , in D-128, U-29, Z-10 ( Under Virugambakkam MLA Scheme)",MLACDS,10,2017-18,2018-19 NK/2017-18/13626,Buildings,Completed,NK-KODAMBAKKAM,128,1322000,"Proposed construction of Multi Purpose Hall at variyar street in Division - 128, Unit -29 , Zone - 10. ( M.L.A Scheme )",MLACDS,10,2017-18,2019-20 NK/2017-18/13656,Buildings,Completed,NK-KODAMBAKKAM,128,1322000,"Proposed construction of Multi Purpose Hall at Variyar street in Virugambakkam , div-128,unit-29,zone-10. ( Under virugambakkam MLA Scheme )",MLACDS,10,2017-18,2020-21 NK/2017-18/7303,Roads,Completed,NK-KODAMBAKKAM,128,435000,"Speed Breaker Rectification work at various street in division-128, unit-29, zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8423,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,770000,"Dismantling and reconstruction of storm water drain at Vanniar street crossing and Minor repair works at various street in Div-128, Unit-29, Zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8869,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,1918000,"Dismantling the existing RCC cover slab and Raising the Storm Water Drain at Arcot Road (from Vanniyar Street reach-1) in Div-128, U-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8875,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,2000000,"Dismantling the existing RCC cover slab and Raising the Storm Water Drain at Arcot Road (Reach-2) in Div-128, U-29, Zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9036,Buildings,Completed,NK-KODAMBAKKAM,128,109000,"ENGAGING PRIVATE SECURITY GUARDS ( FOR 1YEAR ) IN UPHC AT VIRUGAMPAKKAM IN DN-128,UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9040,Buildings,Completed,NK-KODAMBAKKAM,128,253000,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK (1 YEAR) IN URBAN PUBLIC HEALTH CENTRE AT KAMARAJ SALAI, VIRUGAMBAKKAM, CHENNAI IN DN-128,UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9044,Buildings,Completed,NK-KODAMBAKKAM,128,278000,"ENGAGING PRIVATE LABOURS FOR HOUSE KEEPING WORK (8 MONTHS) IN C.P.S AT NESAPPAKKAM AND VIRUGAMBAKKAM, CHENNAI IN DN-128,UNIT-29,ZONE-10",Own Sources,10,2017-18,2019-20 L/2017-18/0937,Electrical,Completed,L-Electrical,129,198900,"Proposed exixting lamp post short cables are raising and fuse box fixing work in div 129,137 and 134 in Zone 10 area",Own Sources,10,2017-18,2017-18 L/2017-18/14863,Electrical,Completed,L-Electrical,129,857100,"Proposed 20 nos of 6mtr GI street lamp post with 40w LED fitting at AV.Meiyappan road in div -129,zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/10694,Roads,Completed,NK-KODAMBAKKAM,129,270000,"Improvement to Bituminous Concrete at Anna street(Gandhi nagar) in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/10697,Roads,Completed,NK-KODAMBAKKAM,129,370000,"Improvement to Bituminous Concrete at Kumaran Colony 3rd street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/10698,Roads,Completed,NK-KODAMBAKKAM,129,337000,"Improvement to Bituminous Concrete at Gangappa street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/10699,Roads,Completed,NK-KODAMBAKKAM,129,236000,"Improvement to Bituminous Concrete at Ponniamman koil street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12679,Roads,Completed,NK-KODAMBAKKAM,129,77000,"Improvement to cement concrete at Dr.Ambedkar 1st street in div-129, Unit-29, Zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/12680,Roads,Completed,NK-KODAMBAKKAM,129,62000,"Improvement to cement concrete at Dr.Ambedkar 1st street in div-129, Unit-29, Zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/12695,Roads,Completed,NK-KODAMBAKKAM,129,111000,"Improvement to cement concrete at Dhasarathapuram 3rd street in div-129, Unit-29, Zone-10",Own Sources,10,2017-18,2018-19 NK/2017-18/12696,Roads,Completed,NK-KODAMBAKKAM,129,324000,"Relaying of Road with BCCMP by Using Mechanical Paver at Sri Ramulu Street in division-129,Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12697,Roads,Completed,NK-KODAMBAKKAM,129,1532000,"Relaying of Road with BCCMP by Using Mechanical Paver at K.K salai (M.A nagar) in division-129,Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12698,Roads,Completed,NK-KODAMBAKKAM,129,433000,"Relaying of Road with BCCMP by Using Mechanical Paver at Rajesh Avenu in division-129,Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12699,Roads,Completed,NK-KODAMBAKKAM,129,252000,"Relaying of Road with BCCMP by Using Mechanical Paver at Parthasarathy street in division-129,Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12700,Roads,Completed,NK-KODAMBAKKAM,129,108000,"Relaying of Road with BCCMP by Using Mechanical Paver at Parthasarathy 1st cross street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12701,Roads,Completed,NK-KODAMBAKKAM,129,108000,"Relaying of Road with BCCMP by Using Mechanical Paver at Parthasarathy 2nd cross street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12702,Roads,Completed,NK-KODAMBAKKAM,129,469000,"Relaying of Road with BCCMP by Using Mechanical Paver at Logaiah colony 1st cross street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12703,Roads,Completed,NK-KODAMBAKKAM,129,341000,"Relaying of Road with BCCMP by Using Mechanical Paver at Logaiah colony 2nd cross street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/15753,Roads,Completed,NK-KODAMBAKKAM,129,337000,"Improvement to Bituminous Concrete at Gangadharan street (Gandhi Nagar) in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3317,Buildings,Completed,NK-KODAMBAKKAM,129,72800,"Repair and Maintenance of NNMP shed at mullai street in division -129,unit-29,zone-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/3318,Buildings,Completed,NK-KODAMBAKKAM,129,76000,"Maintenance of NNMP shed at ponni amman koil street in division -129,unit-29,zone-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/3321,Buildings,Completed,NK-KODAMBAKKAM,129,30000,"Repair and Maintenance of NNMP shed at Dhasarathapuram 8th street in division -129,unit-29,zone-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/3323,Buildings,Completed,NK-KODAMBAKKAM,129,30000,"Repair and Maintenance of NHMP shed at Ambedkar nagar in division -129,unit-29,zone-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/7273,Roads,Completed,NK-KODAMBAKKAM,129,956000,"Speed Breaker rectification work of various street in division-129,unit-29,zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7611,Roads,Completed,NK-KODAMBAKKAM,129,114300,"Improvement to bituminous concrete at Ponniamman koil street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7612,Roads,Completed,NK-KODAMBAKKAM,129,336200,"Improvement to bituminous concrete at Velayutham colony 1st main road in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7614,Roads,Completed,NK-KODAMBAKKAM,129,336200,"Improvement to bituminous concrete at Velayutham colony 2nd main road in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7615,Roads,Completed,NK-KODAMBAKKAM,129,134480,"Improvement to bituminous concrete at Velayutham colony 2nd cross in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7616,Roads,Completed,NK-KODAMBAKKAM,129,1042220,"Improvement to bituminous concrete at Canara Bank Colony in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7617,Roads,Completed,NK-KODAMBAKKAM,129,302580,"Improvement to Bituminous Concrete at Kumaran Colony 5th street in division-129, Unit-29, Zone-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8403,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,600000,"Desilting of Storm Water Drain at various streets in Div-129, Unit-29,Zone-10",Own Sources,10,2017-18,2017-18 NK/2017-18/8428,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,530000,"Minor repair works for storm water drain at various street in Div-129,Unit-29,Zone-10",Own Sources,10,2017-18,2017-18 NK/2017-18/9030,Buildings,Completed,NK-KODAMBAKKAM,129,109000,"Engaging Private Labours For Security Guards For The Period Of 1 year At Urban Public Health Centre, Dhasatharapuram 8th Street, Saligramam, In Dn-129,Unit-29,Zone- 10",Own Sources,10,2017-18,2019-20 NK/2017-18/9033,Buildings,Completed,NK-KODAMBAKKAM,129,253800,"Engaging Private Labours For House Keeping Work For The Period Of 1 year At Urban Public Health Centre, Dhasatharapuram 8th Street, Saligramam, In Dn-129,Unit-29,Zone-10",Own Sources,10,2017-18,2019-20 P/2017-18/17315,Parks,Completed,P-Parks and Playfields,129,6900000,"FORMATION OF NEW PARK AT ARUNACHALAM SALAI kumaran nagar ) IN DN -129, ZONE-X","Loans, Grants And Own Sources",10,2017-18,2020-21 BR/2017-18/10657,Road Cut,Completed,BR-Bus Route Roads,130,928000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SOUTH SIVAN KOIL STREET IN DIV-130,ZONE-10 (FROM JUNCTION OF 100 FEET ROAD TO JUNCTION OF WEST SIVAN KOIL STREET)",Deposit Works,10,2017-18,2018-19 BR/2017-18/10658,Road Cut,Completed,BR-Bus Route Roads,130,1761000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT WEST SIVAN KOIL STREET IN DIV-130,ZONE-10 (FROM JUNCTION OF SOUTH SIVAN KOIL STREET TO JUNCTION OF NSK SALAI)",Deposit Works,10,2017-18,2018-19 BR/2017-18/14662,Road Cut,Completed,BR-Bus Route Roads,130,1830000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT N.S.K. SALAI IN DIV 130 ZONE-10(FROM VADAPAIANI POLICE STATION TO NEAR BUS DEPOT.),Deposit Works,10,2017-18,2018-19 NK/2017-18/12233,Roads,Completed,NK-KODAMBAKKAM,130,1141000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT N.G.O COLONY MAIN ROAD, VADAPALANI IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12234,Roads,Completed,NK-KODAMBAKKAM,130,265000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT VALLALLAR STREET, VADAPALANI IN DIV-130, U-29, Z-10(UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12235,Roads,Completed,NK-KODAMBAKKAM,130,531000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT ANDAVAR NAGAR 5th STREET, VADAPALANI IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12236,Roads,Completed,NK-KODAMBAKKAM,130,329000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT ANDAVAR NAGAR 6tH STREET, VADAPALANI IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12237,Roads,Completed,NK-KODAMBAKKAM,130,407000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT VANNIER STREET, VADAPALANI IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12238,Roads,Completed,NK-KODAMBAKKAM,130,493000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT MOSQUE STREET, VADAPALANI IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12239,Roads,Completed,NK-KODAMBAKKAM,130,81600,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT MOSQUE LANE, VADAPALANI IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12240,Roads,Completed,NK-KODAMBAKKAM,130,642000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT NERKUNDRAM PATHAI WEST, VADAPALANI IN DIV-130, U-29, Z-10(UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12241,Roads,Completed,NK-KODAMBAKKAM,130,631000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT ALAGIRI NAGAR 3rd STREET, VADAPALANI IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12314,Roads,Completed,NK-KODAMBAKKAM,130,199000,"ATTENDING PATCH WORK WITH BC 40mm N.G.O COLONY 1st STREET, VADAPALANI IN DIV-130, U-29, Z-10. (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12475,Buildings,Completed,B-Buildings,130,390800,"REPAIRS AND IMPROVEMENTS TO SMART CLASS ROOM IN CHENNAI MIDDLE SCHOOL AT DOOR NO:2, AMMAN KOIL STREET, VADAPALANI IN DIV-130, U-29, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/13734,Buildings,Completed,NK-KODAMBAKKAM,130,429000,"PROVIDING RESTROOM FOR WORKERS (LADIES) & IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT DOOR NO:2, AMMAN KOIL STREET, VADAPALANI IN DIV-130, U-29, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/5375,Roads,Completed,NK-KODAMBAKKAM,130,738800,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT NORTH MADA STREET IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5440,Roads,Completed,NK-KODAMBAKKAM,130,672400,"IMPROVEMENTS TO BITUMINOUS CONCRETE ROAD AT AMMAN KOIL STREET (WEST) IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5448,Roads,Completed,NK-KODAMBAKKAM,130,201720,"IMPROVEMENTS TO BITUMINOUS CONCRETE ROAD AT NERKUNDRAM LANE IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5452,Roads,Completed,NK-KODAMBAKKAM,130,369820,"IMPROVEMENTS TO BITUMINOUS CONCRETE ROAD AT ALAGIRI NAGAR 5TH STREET IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5456,Roads,Completed,NK-KODAMBAKKAM,130,184900,"IMPROVEMENTS TO BITUMINOUS CONCRETE ROAD AT ALAGIRI NAGAR 5TH CROSS STREET IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5457,Roads,Completed,NK-KODAMBAKKAM,130,504300,"IMPROVEMENTS TO BITUMINOUS CONCRETE ROAD AT KARUMARIAMMAN KOIL STREET IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/7438,Roads,Completed,NK-KODAMBAKKAM,130,640000,"IMPROVEMENTS TO SPEED BREAKER @ VARIOUS STREET IN DN-130,UNIT-29,ZONE-X.",Own Sources,10,2017-18,2019-20 NK/2017-18/8889,Buildings,Completed,NK-KODAMBAKKAM,130,700000,"PROPOSED CONSTRUCTION OF AMMA KUDINEER WITH G.I.SHEET ROOFING AT N.G.O COLONY MAIN ROAD IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8988,Buildings,Completed,NK-KODAMBAKKAM,130,140000,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI MIDDLE SCHOOL, (1 SWEEPERS & 1 SCAVENGERS) AT AMMAN KOVIL STREET FOR 8 MONTHS IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9037,Buildings,Completed,NK-KODAMBAKKAM,130,109000,"Engaging Private Labours For Security Guards For The Period Of 1 year At Urban Public Health Centre, Rajangam madhiya veedhi , In Dn-130,Unit-29,Zone-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9259,Buildings,Completed,B-Buildings,130,49500,"PREPARATION OF SMART CLASS ROOM AT CHENNAI MIDDLE SCHOOL, VADAPALANI AT AMMAN KOIL STREET (EAST) IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9869,Buildings,Completed,NK-KODAMBAKKAM,130,2360000,"Proposed Construction of First Floor over existing Multi - Purpose Hall at Alagiri Nagar 1st Street in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9874,Buildings,Completed,NK-KODAMBAKKAM,130,2340000,"Proposed Construction of Multi - Purpose Hall (First Floor) over existing Amma Unavagam Building at Nerkundrum Pathai in Dn - 130, Unit - 29, Zone - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9884,Buildings,Completed,NK-KODAMBAKKAM,130,999000,"SUPPLY, INSTALLATION, COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITRES / HOUR CAPACITY AT N.G.O COLONY MAIN ROAD IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9886,Buildings,Completed,NK-KODAMBAKKAM,130,990000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT N.G.O COLONY MAIN ROAD IN DIV-130, U-29, Z-10",Own Sources,10,2017-18,2019-20 L/2017-18/7065,Electrical,Completed,L-Electrical,131,808200,Replacement of 899 mtrs of 4x 16 sq mm cable at PT Rajan Salai salai Division 131 in Zone-X.,Own Sources,10,2017-18,2018-19 L/2017-18/7067,Electrical,Completed,L-Electrical,131,547500,Replacement of 813 mtrs of 4x 16 sq mm cable at Lakshmana Samy salai Division 131 in Zone-X.,Own Sources,10,2017-18,2018-19 NK/2017-18/11656,Roads,Completed,NK-KODAMBAKKAM,131,912000,"RELAYING OF CEMENT CONCRETE ROAD AT MGR NAGAR NAKEERAN STREET USING RMC 40 GRADE IN DIV-131,UNIT-28,ZONE-10.",Grants,10,2017-18,2018-19 NK/2017-18/11657,Roads,Completed,NK-KODAMBAKKAM,131,570000,"RELAYING OF CEMENT CONCRETE ROAD AT KANNIKAPURAM 2ND STREET USING RMC 40 GRADE IN DN 131, UNIT-28, ZONE 10",Grants,10,2017-18,2018-19 NK/2017-18/1248,Buildings,Completed,NK-KODAMBAKKAM,131,581000,"ATTENDING PATCH WORK ANNA MAIN ROAD AND VARIOUS STREET IN DIV-131,U-28,Z-10.",Own Sources,10,2017-18,2017-18 NK/2017-18/14692,Buildings,Completed,NK-KODAMBAKKAM,131,53000,"PLUMBING WORK FOR ANGANWADI,13TH SECTOR PLAY GROUND AND DIVISION OFFICE BUILDING IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/16856,Buildings,Completed,NK-KODAMBAKKAM,131,576000,"OPERATION AND MAINTENANCE FOR 3RD YEAR OPERATION OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) FOR 1 YEAR PERIOD (AMMA KUDINEER) AT SIVAN PARK CAMPUS, KK NAGAR, IN DN-131,U-28,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8018,Roads,Completed,NK-KODAMBAKKAM,131,950000,"LAYING OF CEMENT CONCRETE ROAD AT KALAIVANAR STREET (MGR NAGAR) IN DN 131, UNIT28, ZONE 10",Grants,10,2017-18,2018-19 NK/2017-18/8358,Buildings,Completed,NK-KODAMBAKKAM,131,290000,"Desilting of SWD at 80feet road and other streets in division -131, U-28, Z-10.",Own Sources,10,2017-18,2017-18 NK/2017-18/8807,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,195000,"Repairs to SWD at various street in division-131, U-28, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9156,Parks,Completed,NK-KODAMBAKKAM,131,902000,"Annual Maintenance Of Sivan Park At P.T.Rajan Salai In Div- 131,U-28,Zone-X. (Employed Qualified Diploma Horticulturist Only)",Own Sources,10,2017-18,2018-19 NK/2017-18/9161,Parks,Completed,NK-KODAMBAKKAM,131,230000,"ANNUAL MAINTENANCE OF PARK AT RANI ANNA NAGAR,KK NAGAR IN DIV- 131,U-28,ZONE-X. (EMPLOYED QUALIFIED DIPLOMA HORTICULTURIST ONLY)",Own Sources,10,2017-18,2018-19 NK/2017-18/9166,Roads,Completed,NK-KODAMBAKKAM,131,180000,"Providing and laying thermoplastic paint and fixing studs in speed breakers at Nadesan salai and various other street in Div-131,U-28,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9168,Roads,Completed,NK-KODAMBAKKAM,131,63000,"Providing and laying thermoplastic paint and fixing studs in speed breakers at Gangaiamman street and various other streets in Div-139, U-28, Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9179,Buildings,Completed,NK-KODAMBAKKAM,131,177000,"CONSTRUCTION OF DAMAGED BIO GAS PLANT WEST COMPOUND WALL AT GANGAIAMMAN KOIL STREET JAFFARKHANPET IN DIVISION-139,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 BR/2017-18/10773,Road Cut,Completed,BR-Bus Route Roads,132,1739000,RESTORATION OF ROAD CUT MADE BY TANTRANSCO AT ASHOK NAGAR 1ST AVENUE (FROM JUNCTION OF 10 TH AVENUE TO JUNCTION OF 11TH AVENUE) IN DIV 132 Z0NE-10.,Deposit Works,10,2017-18,2018-19 L/2017-18/0930,Electrical,Completed,L-Electrical,132,199100,Proposed exixting lamp post short cables are raising and fuse box fixing work in div 132 in Zone 10 area,Own Sources,10,2017-18,2017-18 NK/2017-18/10131,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,495000,"IMPROVEMENTS AND DESILTING OF STORM WATER DRAIN OF SIDE DRAIN AT OTTAGAPALAYAM CHURCH ROAD IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/10132,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,1048000,"IMPROVEMENTS AND DESILTING OF STORM WATER DRAIN AT P.T.RAJAN SALAI (NORTH SIDE) (FROM JN OF 100 FEET ROAD TO JN OF S.V.LINGAM SALAI) IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/10133,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,1048000,"IMPROVEMENTS AND DESILTING OF STORM WATER DRAIN AT P.T.RAJAN SALAI (SOUTH SIDE) (FROM JN OF 100 FEET ROAD TO JN OF KAMARAJAR SALAI) IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/12227,Roads,Completed,NK-KODAMBAKKAM,132,1512000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT 8TH AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12228,Roads,Completed,NK-KODAMBAKKAM,132,257000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT 46TH STREET (PART), ASHOK NAGAR IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12229,Roads,Completed,NK-KODAMBAKKAM,132,428000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT 67TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12230,Roads,Completed,NK-KODAMBAKKAM,132,1472000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT DR.NATESAN SALAI IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12231,Roads,Completed,NK-KODAMBAKKAM,132,503000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT J.O.KANNAPPAR SALAI IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12232,Roads,Completed,NK-KODAMBAKKAM,132,520000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT 28TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12297,Roads,Completed,NK-KODAMBAKKAM,132,1150000,"RELAYING OF BITUMINOUS CONCRETE ROAD BY PAVER FINISHER AT SAIDAPET ROAD IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/13318,Roads,Completed,NK-KODAMBAKKAM,132,293000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT 34TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13319,Roads,Completed,NK-KODAMBAKKAM,132,1811000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT 48TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13324,Roads,Completed,NK-KODAMBAKKAM,132,291000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT 54TH STREET LANE, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13326,Roads,Completed,NK-KODAMBAKKAM,132,572000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT 15TH SECTOR 98TH STREET IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13330,Roads,Completed,NK-KODAMBAKKAM,132,351000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT BAJANAI KOIL STREET IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/15755,Roads,Completed,NK-KODAMBAKKAM,132,1279000,"LAYING OF CEMENT CONCRETE ROAD WITH RMC40 AT 89TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/16029,Buildings,Completed,NK-KODAMBAKKAM,132,349000,"Repair and maintenance work in Chennai primary school, Kanniyappa Nagar at 83rd street, Ahsok Nagar in Div-132, Unit-31, Zone-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/3612,Buildings,Completed,NK-KODAMBAKKAM,132,278000,"OUTSOURCING PRIVATE LABOURS FOR GOVERNMENT GIRLS HR. SEC. SCHOOL (2 SWEEPERS & 2 SCAVENGERS) AT 9TH AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3617,Buildings,Completed,NK-KODAMBAKKAM,132,139000,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI HIGH SCHOOL, KANNIYAPPA NAGAR AT 83RD STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/3619,Buildings,Completed,NK-KODAMBAKKAM,132,208000,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI HR.SEC. SCHOOL, PULIYUR AT N.S.K. SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/6487,Roads,Completed,NK-KODAMBAKKAM,132,480000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT VENKATESAPURAM COLONY IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/6488,Roads,Completed,NK-KODAMBAKKAM,132,1120000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT PUDUR 1ST STREET IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6490,Roads,Completed,NK-KODAMBAKKAM,132,600000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 15TH SECTOR 94TH STREET IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/6492,Roads,Completed,NK-KODAMBAKKAM,132,460000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 15TH SECTOR 101ST STREET IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/6493,Roads,Completed,NK-KODAMBAKKAM,132,340000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 55TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/6496,Roads,Completed,NK-KODAMBAKKAM,132,360000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 56TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/6497,Roads,Completed,NK-KODAMBAKKAM,132,450000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT VAIGAI COLONY 2ND STREET IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/6498,Roads,Completed,NK-KODAMBAKKAM,132,690000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 81ST STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/6500,Roads,Completed,NK-KODAMBAKKAM,132,500000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT SOMA SUNDHARA BHARATHI NAGAR 5TH STREET IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2016-17)",MLACDS,10,2017-18,2017-18 NK/2017-18/8871,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,499000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-132,U- 31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9071,Buildings,Completed,NK-KODAMBAKKAM,132,69500,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL, KANNIYAPPA NAGAR AT 83RD STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/9141,Roads,Completed,NK-KODAMBAKKAM,132,1040000,"PROVIDING THERMOPLASTIC PAINT AND SUPPLYING & FIXING REFLECTIVE PAVEMENT STUD FOR SPEED BREAKERS AT VARIOUS STREETS IN DIV-132,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9142,Buildings,Completed,NK-KODAMBAKKAM,132,69500,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL, PULIYUR AT N.S.K. SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/9152,Buildings,Completed,NK-KODAMBAKKAM,132,60000,"PROVIDING SECURITY ARRANGEMENTS FOR GOVERNMENT HR. SEC. SCHOOL, PUDUR AT 3RD AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/9154,Buildings,Completed,NK-KODAMBAKKAM,132,60000,"PROVIDING SECURITY ARRANGEMENTS FOR GOVERNMENT GIRLS HR. SEC. SCHOOL AT 9TH AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/9180,Parks,Completed,NK-KODAMBAKKAM,132,624000,"ANNUAL MAINTENANCE OF 1ST AVENUE PARK AT ASHOK NAGAR IN DIV-132, U-31, Z-10 (QUALIFIED HORTICULTURIST ONLY) (FOR 1 YEAR)",Own Sources,10,2017-18,2019-20 BR/2017-18/10783,Road Cut,Completed,BR-Bus Route Roads,133,1244000,ROAD CUT RESTORATION MADE BY TANTRANSCO AT ASHOK NAGAR 11TH AVENUE (FROM JUNCTION OF 1ST AVENUE TO 100 FEET ROAD) IN DIV 133 ZONE-10.,Deposit Works,10,2017-18,2018-19 L/2017-18/7009,Electrical,Completed,L-Electrical,133,196300,"Additional wiring and damaged Tube light fitting, fan replacement at Chennai High Secondary School, Puliyur, Kodambakkam in Div-133 Zone - X",Own Sources,10,2017-18,2017-18 NK/2017-18/0106,Buildings,Completed,NK-KODAMBAKKAM,133,1270000,"CONSTRUCTION OF TOILET BLOCK AT CPS PULIYUR AT NSK SALAI, KODAMBAKKAM (UNDER MLA SCHEME 2017-18) IN DIV-133, U-31, Z-10",MLACDS,10,2017-18,2018-19 NK/2017-18/0534,Buildings,Completed,NK-KODAMBAKKAM,133,1270000,"CONSTRUCTION OF TOILET BLOCK AT CHSS PULIYUR AT NSK SALAI, KODAMBAKKAM (UNDER MLA SCHEME 2017-18) IN DIV-133, U-31, Z-10",MLACDS,10,2017-18,2018-19 NK/2017-18/0535,Buildings,Completed,NK-KODAMBAKKAM,133,2500000,"IMPROVEMENTS TO THE REPAIR AND MAINTAINANCE WORK AT CHSS PULIYUR SCHOOL AT NSK SALAI IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13340,Roads,Completed,NK-KODAMBAKKAM,133,697000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT DHANASEKARAN STREET IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13341,Roads,Completed,NK-KODAMBAKKAM,133,298000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT DHANASEKARAN STREET EXTENSION IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13343,Roads,Completed,NK-KODAMBAKKAM,133,455000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT 23RD STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13344,Roads,Completed,NK-KODAMBAKKAM,133,434000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT 24TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/13346,Roads,Completed,NK-KODAMBAKKAM,133,155000,"RELAYING OF ROAD WITH BITUMINOUS CONCRETE AT 64TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/16033,Buildings,Completed,NK-KODAMBAKKAM,133,600000,"Repair and maitenance work in chennai primary school, Puliyur at NSK salai, Kodambakkam in Div-133, Unit-31, Zone-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/3623,Buildings,Completed,NK-KODAMBAKKAM,133,69500,"OUTSOURCING PRIVATE LABOURS FOR MULLAI NAGAR CHENNAI PRIMARY SCHOOL, 15TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (FOR 8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/6501,Roads,Completed,NK-KODAMBAKKAM,133,819000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT V.O.C NAGAR 1ST MAIN ROAD IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6504,Roads,Completed,NK-KODAMBAKKAM,133,463000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT V.O.C NAGAR 2ND MAIN ROAD IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6505,Roads,Completed,NK-KODAMBAKKAM,133,208000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT V.O.C NAGAR 4TH CROSS STREET IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6506,Roads,Completed,NK-KODAMBAKKAM,133,154000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 52ND STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6508,Roads,Completed,NK-KODAMBAKKAM,133,375000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 57TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6509,Roads,Completed,NK-KODAMBAKKAM,133,625000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT KAVARAI STREET, WEST MAMBALAM IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6511,Roads,Completed,NK-KODAMBAKKAM,133,810000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT SHYAMALA VADHANA STREET IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6512,Roads,Completed,NK-KODAMBAKKAM,133,285000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT J.P. STREET IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6514,Roads,Completed,NK-KODAMBAKKAM,133,510000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT VARGHEESE AVENUE IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6516,Roads,Completed,NK-KODAMBAKKAM,133,347000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 50TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6517,Roads,Completed,NK-KODAMBAKKAM,133,185000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 51ST STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/6518,Roads,Completed,NK-KODAMBAKKAM,133,217000,"RELAYING OF ROAD WITH BCCMP BY USING MECHANICAL PAVER AT 63RD STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2017-18 NK/2017-18/7264,Roads,Completed,NK-KODAMBAKKAM,133,654000,"PROVIDING THERMOPLASTIC PAINT AND SUPPLYING & FIXING REFLECTIVE PAVEMENT STUD FOR SPEED BREAKERS AT VARIOUS STREETS IN DIV-133,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/8064,Buildings,Completed,NK-KODAMBAKKAM,133,290000,"IMPROVEMENTS TO THE GYM BUILDING AT 17TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8318,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,919000,"MINOR REPAIR AND MAINTAINANCE OF STORM WATER DRAIN AT VARIOUS STREETS IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2017-18 NK/2017-18/8339,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,688000,"MINOR REPAIR AND MAINTAINANCE OF STORM WATER DRAIN AT VARIOUS STREETS IN DIV-132, U-31, Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/8876,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,499000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-133,U- 31,Z-10",Own Sources,10,2017-18,2017-18 NK/2017-18/8885,Buildings,Completed,NK-KODAMBAKKAM,133,700000,"PROPOSED CONSTRUCTION OF AMMA KUDINEER WITH G.I.SHEET ROOFING AT 60TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8886,Buildings,Completed,NK-KODAMBAKKAM,133,700000,"PROPOSED CONSTRUCTION OF AMMA KUDINEER WITH G.I.SHEET ROOFING AT 17TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9241,Buildings,Completed,B-Buildings,133,45000,"PREPARATION OF SMART CLASS ROOM AT CHSS PULIYUR AT N.S.K SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9857,Buildings,Completed,NK-KODAMBAKKAM,133,222000,"ATTENDING REPAIR WORKS TO THE CHSS AND CPS AT NSK SALAI IN DN-133,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9860,Buildings,Completed,NK-KODAMBAKKAM,133,999000,"SUPPLY, INSTALLATION, COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITRES / HOUR CAPACITY AT 17TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9861,Buildings,Completed,NK-KODAMBAKKAM,133,999000,"SUPPLY, INSTALLATION, COMMISSIONING OF WATER TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITRES / HOUR CAPACITY AT 60TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9867,Buildings,Completed,NK-KODAMBAKKAM,133,990000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT 17TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9868,Buildings,Completed,NK-KODAMBAKKAM,133,990000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT 60TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2017-18,2019-20 BR/2017-18/0902,Footpath,Completed,BR-Bus Route Roads,134,7080000,"Street designing of existing road at Paramgusapuram Street in Dn-134, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2020-21 BR/2017-18/0917,Footpath,Completed,BR-Bus Route Roads,134,5641000,Street designing of existing road at Aziz Nagar 2nd Street in Dn-134 Zone-10 under Smart City,SMART CITY - BRR,10,2017-18,2020-21 BR/2017-18/11881,Road Cut,Completed,BR-Bus Route Roads,134,85000,"Restoration of Road cut made by CMWSSB at ARCOT ROAD in Dn-134, Zone-10.",Deposit Works,10,2017-18,2018-19 D/2017-18/13039,Storm Water Drain,Completed,D-Storm Water Drains,134,16223000,"Construction of Storm Water Drain of size 900x900mm at Rathinammal street, Gopal Menon street Jn.of Viswanathapuram Main Road, Ellayamman Koil Street Jn. of Sambangi Street, Reddykuppam Street Jn.of Vandikaran Street, Kodambakkam Road & Govindan Road Jn.of Kodambakkam Road in Dn-134 & 140, Zone-X.",SMART CITY - SWD,10,2017-18,2018-19 L/2017-18/11270,Electrical,Completed,L-Electrical,134,115000,"Additional wiring and replacement of Damaged fan and Tube light at Corporation primary Health Centre and Unit office 31, Corporation Colony, Kodambakkam, Division 134,Zone X",Own Sources,10,2017-18,2018-19 NK/2017-18/0136,Buildings,Completed,NK-KODAMBAKKAM,134,371000,"CONSTRUCTION OF GENERATOR ROOM FOR TWO WHEELER SUBWAY AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/11256,Roads,Completed,NK-KODAMBAKKAM,134,77700,"REPAIRS TO THE EXISTING ROOF AND CLADDING AT OTS IN MATERNITY HOSPITAL AT NSK SALAI, KODAMBAKKAM IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/12215,Roads,Completed,NK-KODAMBAKKAM,134,672000,"RELAYING THE ROAD WITH BC 40MM THICK AND DBM 50MM THICK FOR CAMBER CORRECTION BY USING PAVER FINISHER AT GUGAN STREET IN DN-134,U-31,Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12271,Roads,Completed,NK-KODAMBAKKAM,134,1152000,"RELAYING THE ROAD WITH BC 40MM THICK AND DBM 50MM THICK FOR CAMBER CORRECTION BY USING PAVER FINISHER AT RATHINAMMAL STREET IN DN-134,U-31,Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12272,Roads,Completed,NK-KODAMBAKKAM,134,1320000,"RELAYING THE ROAD WITH BC 40MM THICK AND DBM 50MM THICK FOR CAMBER CORRECTION BY USING PAVER FINISHER AT PASUMARTHY STREET IN DN-134,U-31,Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/14705,Buildings,Completed,NK-KODAMBAKKAM,134,325000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT PADIPPAGA CHEMMAL GANAPATHI HIGHER SECONDARY SCHOOL AT N.S.K.SALAI IN DIV-134, U-31, Z-10 (UNDER T.NAGAR CONSTIUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/15973,Buildings,Completed,NK-KODAMBAKKAM,134,795000,"REPAIR AND IMPROVEMENT WORKS TO THE CHENNAI PRIMARY SCHOOL BUILDING AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/15992,Buildings,Completed,NK-KODAMBAKKAM,134,820000,"REPAIR AND MAINTENANCE WORKS TO THE CHENNAI HIGH SCHOOL (EASTERN SIDE & WESTERN SIDE BUILDING) AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2792,Roads,Completed,NK-KODAMBAKKAM,134,2085000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2805,Roads,Completed,NK-KODAMBAKKAM,134,1086000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT STATION VIEW ROAD IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2807,Roads,Completed,NK-KODAMBAKKAM,134,1940000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT U.I.COLONY 4TH CROSS STREET IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2808,Roads,Completed,NK-KODAMBAKKAM,134,465000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT TAILOR ESTATE 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2809,Roads,Completed,NK-KODAMBAKKAM,134,1863000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT TAILOR ESTATE 2ND STREET IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5198,Roads,Completed,NK-KODAMBAKKAM,134,638800,"IMPROVEMENTS TO THE EXISTING BT ROAD SURFACE AT AKBARABAD 1ST STREET IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/7263,Roads,Completed,NK-KODAMBAKKAM,134,219000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT VALLIAMMAL GARDEN 2ND STREET IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/7628,Roads,Completed,NK-KODAMBAKKAM,134,677000,"PROVIDING THERMOPLASTIC COMPOUND AND REFLECTIVE PAVEMENT STUDS TO THE EXISTING SPEED BREAKERS AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/8521,Buildings,Completed,NK-KODAMBAKKAM,134,1612000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8983,Buildings,Completed,NK-KODAMBAKKAM,134,69500,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (FOR 8 MONTHS) FOR CHS AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/8985,Buildings,Completed,NK-KODAMBAKKAM,134,69500,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR CMS AT KAMARAJAR COLONY (FOR 8 MONTHS) IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8987,Buildings,Completed,NK-KODAMBAKKAM,134,104000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR MATERNITY HOSPITAL AT N.S.K. SALAI (FOR 1 YEAR) IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/8989,Buildings,Completed,NK-KODAMBAKKAM,134,90000,"ENGAGING SECURITY GUARDS ( FOR 1 YEAR) FOR MATERNITY HOSPITAL AT N.S.K.SALAI IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/8994,Buildings,Completed,NK-KODAMBAKKAM,134,72400,"SUPPLYING AND FIXING OF DEWATERING PUMP WITH ACCESSORIES, REPAIR & SERVICES TO THE EXISTING DIESEL OPERATING PUMPS AT RANGARAJAPURAM TWO WHEELOR SUBWAY IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9157,Buildings,Completed,NK-KODAMBAKKAM,134,60000,"ENGAGING SECURITY GUARDS ( FOR 8 MONTHS) FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9158,Buildings,Completed,NK-KODAMBAKKAM,134,139000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING ( FOR 8 MONTHS) FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9171,Roads,Completed,NK-KODAMBAKKAM,134,1490000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT CHAKRAPANI STREET EXTN., IN DN-134,U-31,Z-10",Own Sources,10,2017-18,2018-19 BR/2017-18/0919,Footpath,Completed,BR-Bus Route Roads,135,2818000,"Street designing of existing road at Jaishankar Street in Dn-135, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2020-21 D/2017-18/12968,Storm Water Drain,Completed,D-Storm Water Drains,135,16997000,"Construction of Storm Water Drain of size 900x900mm at Brindavan Road, Sathyapuri street, Lake View Road and Arya Dowda Raod Jn.of Postal Colony 1st street in Dn-135, Zone-10",SMART CITY - SWD,10,2017-18,2018-19 NK/2017-18/10170,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,285000,"REPAIR ANS RECONSTRUCTION OF SWD AT BRINDAVAN STREET & ARYA GOWDA ROAD IN DIV-135,U-31,Z-10",Own Sources,10,2017-18,2017-18 NK/2017-18/10704,Roads,Completed,NK-KODAMBAKKAM,135,1552000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE 30mm THICK AT ARYA GOWDA ROAD EXTENTION IN DIV-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/10706,Roads,Completed,NK-KODAMBAKKAM,135,1242000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE 30mm THICK AT BRINDAVAN STREET SUBWAY APPROACH ROAD IN DIV-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/11747,Buildings,Completed,NK-KODAMBAKKAM,135,580000,"REPAIR AND MAINTENANCE OF CPS AT ESWARANKOIL STREET IN DIV-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/11936,Subway,Completed,NK-KODAMBAKKAM,135,89000,"REPAIRING AND FIXING OF MOTOR TO MADLEY SUBWAY PUMP ROOM IN DIV-135,U-31,Z-10",Own Sources,10,2017-18,2017-18 NK/2017-18/12312,Roads,Completed,NK-KODAMBAKKAM,135,512000,"RELAYING THE EXISTING BT ROAD SURFACE WITH CAMBER AND PROFILE CORRECTION USING BC 40MM THICK BY PAVER FINISHER AT BABU RAJENDRA PRASAD 2ND STREET IN DN-135,U-31,Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/12313,Roads,Completed,NK-KODAMBAKKAM,135,240000,"RELAYING THE EXISTING BT ROAD SURFACE WITH CAMBER AND PROFILE CORRECTION USING BC 40MM THICK BY PAVER FINISHER AT HANUMAR KOIL STREET IN DN-135,U-31,Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2017-18)",MLACDS,10,2017-18,2018-19 NK/2017-18/5202,Roads,Completed,NK-KODAMBAKKAM,135,403500,"IMPROVEMENT WORK AT BARODA STREET IN DN-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5205,Roads,Completed,NK-KODAMBAKKAM,135,859000,"IMPROVEMENT WORK AT BABU RAJENDRA PRASAD 2ND STREET IN DN-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/7633,Roads,Completed,NK-KODAMBAKKAM,135,483000,"PROVIDING THERMOPLASTIC PAINT AND REFLECTIVE STUDS FOR THE EXISTING SPEED BREAKERS AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8337,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,216000,"ATTENDING MINOR REPAIRS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8853,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,498000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2017-18,2017-18 NK/2017-18/8999,Buildings,Completed,NK-KODAMBAKKAM,135,69500,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING FOR CPS AT ESWARAN KOIL STREET (FOR 8 MONTHS) IN DN-135,U-31,Z-10",Own Sources,10,2017-18,2018-19 BR/2017-18/0883,Footpath,Completed,BR-Bus Route Roads,136,3388000,"Street designing of existing road at Sarojini Street in Dn-136, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0891,Footpath,Completed,BR-Bus Route Roads,136,10005000,"Street designing of existing road at kannadasan salai in Dn-136, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0892,Footpath,Completed,BR-Bus Route Roads,136,3150000,"Street designing of existing road at Guild Street in Dn-136, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0911,Footpath,Completed,BR-Bus Route Roads,136,9244000,"Street designing of existing road at Dr.Gopala Menon Street in Dn-134, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2020-21 BR/2017-18/0921,Footpath,Completed,BR-Bus Route Roads,136,7194000,"Street designing of existing road at Maharaja Santhanam Street in Dn-136, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0964,Footpath,Completed,BR-Bus Route Roads,136,5425000,"Street designing of existing road at Pinchala Subramani Street in Dn-136, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0978,Footpath,Completed,BR-Bus Route Roads,136,3862000,"Street Designing of Existing Road at Kannadasan Street in Dn-136, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/1037,Road Cut,Completed,BR-Bus Route Roads,136,60000,Restoration of Road cut made by CMWSSB at Duraisamy road jn. of Lakshminarasimhan street in (Div 136)Zone-10,Deposit Works,10,2017-18,2018-19 BR/2017-18/1038,Road Cut,Completed,BR-Bus Route Roads,136,60000,Restoration of Road cut made by CMWSSB at Duraisamy road jn. of Lakshminarasimhan street in (Div 136)Zone-10,Deposit Works,10,2017-18,2018-19 D/2017-18/13049,Storm Water Drain,Completed,D-Storm Water Drains,136,11055005,"Construction of Storm Water Drain of size 1200x1200mm at Road Crossing in Kasturibai Road, Sivasailam Road, G.N.Chetty Road & North Usman Road Jn.of Habbibullah Road, in Dn-113 & 117, Zone-IX and North Usman Road Jn.of Coats Road, Duraisamy Road Jn.of Usman Road, Madley Road Jn.of Guild Street, Natesan Street Jn.of Guild Street, Venkatanarayana Road near Kannadasan Park, South West Boag Road Jn.of South Dhandapani Street & Burkit Road Jn.of Mooparappan street in Dn-136 & 141, Zone-X.",SMART CITY - SWD,10,2017-18,2018-19 D/2017-18/14726,Footpath,Completed,SP-SPECIAL PROJECTS,136,83500000,"Proposed construction of Pedestrian Plaza at Pondy Bazar, Thyeagaraya Road(Northern side ) in T.Nagar Reach-1 (from Jn. of Panagal park to Jn.of Thanigachalam Road) in Dn-136, Unit-30, Zone - X .",SMART CITY - SPECIAL PROJECTS,10,2017-18,2019-20 D/2017-18/14727,Footpath,Completed,SP-SPECIAL PROJECTS,136,85000000,"Proposed construction of Pedestrian Plaza at Pondy Bazar, Thyeagaraya Road(Southern side) in T.Nagar Reach-1 (from Jn. of Panagal park to Jn.of Thanigachalam Road) in Dn-136, Unit-30, Zone - X South",SMART CITY - SPECIAL PROJECTS,10,2017-18,2019-20 D/2017-18/14728,Footpath,Completed,SP-SPECIAL PROJECTS,136,99500000,"Proposed construction of Pedestrian Plaza at Pondy Bazar, Thyeagaraya Road in T.Nagar Reach-2 (from Jn. of Thanigachalam road to Jn. of North and South boag road) in Dn-136, Unit-30, Zone - X",SMART CITY - SPECIAL PROJECTS,10,2017-18,2019-20 NK/2017-18/13438,Buildings,Completed,NK-KODAMBAKKAM,136,54300,"PROVIDING FLOORING ARRANGEMENTS FOR VULCANIZING ROOM AT LORRY STATION IN DN-136,U-30,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/13486,Buildings,Completed,NK-KODAMBAKKAM,136,79600,"PROVIDING G.I.SHEET FOR VULCANIZING ROOM AT LORRY STATION IN DN-136,U-30,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/13487,Buildings,Completed,NK-KODAMBAKKAM,136,99500,"PROVIDING G.I.SHEET FOR WATCHMAN AND C.I. ROOM AT LORRY STATION IN DN-136,U-30,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/13871,Buildings,Completed,NK-KODAMBAKKAM,136,102000,"PAINTING AND COLOUR WASHING FOR OLD DIVISION OFFICE - 117 AT BAZULLA ROAD IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2017-18,2019-20 NK/2017-18/16955,Parks,Completed,NK-KODAMBAKKAM,136,901000,"REPAIR WORKS TO THE PANAGAL PARK AT BASHYAM ROAD IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2019-20 NK/2017-18/3322,Buildings,Completed,NK-KODAMBAKKAM,136,700000,"IMPROVEMENTS TO ROAD WORK AT SAMBASIVAM STREET AND DHANDAPANI STREET IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3328,Buildings,Completed,NK-KODAMBAKKAM,136,40400,"IMPROVEMENTS TO ROAD WORK AT RAGAVAIAH ROAD IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3331,Buildings,Completed,NK-KODAMBAKKAM,136,840500,"IMPROVEMENTS TO ROAD WORK AT SAMBASIVAM STREET IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/4967,Roads,Completed,NK-KODAMBAKKAM,136,857300,"ROAD MAINTANENCE WORK AT SOMASUNDARAM STREET IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7911,Parks,Completed,NK-KODAMBAKKAM,136,970000,"ANNUAL MAINTENANCE TO PANAGAL PARK AT BASHYAM ROAD IN DIV 136,U 30, Z 10(Employed qualified horticulturist only)",Own Sources,10,2017-18,2018-19 NK/2017-18/8237,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,650000,"DESILTING OF STROM WATER DRAIN AT USMAN ROAD, DURAISAMY ROAD,RANGANATHAN STREET AND VARIOUS STREET IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8247,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,149000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-141,U-30,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9021,Buildings,Completed,NK-KODAMBAKKAM,136,139000,"PROVIDING HOUSE KEEPING ARRANGEMENT TO CHENNAI MIDDLE SCHOOL AT PRAKASAM ROAD IN DIVISION - 136, UNIT - 30, ZONE - 10.FOR 8MONTHS",Own Sources,10,2017-18,2019-20 NK/2017-18/9045,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,956000,"REPAIR WORKS TO THE STROM WATER DRAIN AT COATS ROAD, PRAKASAM ROAD AND VARIOUS STREET IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9064,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,957000,"REPAIR WORKS TO THE STROM WATER DRAIN AT MOTHILAL STREET, GUILD STREET AND VARIOUS STREET IN DIVISION - 136, UNIT -30, ZONE -10.",Own Sources,10,2017-18,2018-19 P/2017-18/10855,Parks,Completed,P-Parks and Playfields,136,4680000,"Providing Packaged Sewage Treatment Plant Capacity of 40 KLD including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at Natesan Park, venkatanarayana Road (40 KLD) in Dn-136, Zone - X",Own Sources,10,2017-18,2019-20 P/2017-18/12747,Parks,Completed,P-Parks and Playfields,136,3393000,"Providing Packaged Sewage Treatment Plant Capacity of 10 KLD including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at jeeva Park in Dn-136, Zone - X",Own Sources,10,2017-18,2019-20 P/2017-18/2349,Parks,Completed,P-Parks and Playfields,136,16700000,PROPOSED REDEVELOPMENT JEEVA PARK IN THE AREA BASED DEVELOPMENT OF T. NAGAR AS PARK OF SMART CITY SCHEME IN DN 136/ZONE 10,Grants,10,2017-18,2018-19 P/2017-18/2366,Parks,Completed,P-Parks and Playfields,136,35400000,"PROPOSED REDEVELOPMENT NATESAN PARK IN THE AREA BASED DEVELOPMENT OF T.NAGAR AS PART OF SMART CITY SCHEME IN DN-136, ZONE - X.",Grants,10,2017-18,2019-20 P/2017-18/2368,Parks,Completed,P-Parks and Playfields,136,14900000,"PROPOSED REDEVELOPMENT CIT NAGAR PARK IN THE AREA BASED DEVELOPMENT OF T.AGAR AS PARK OF SMART CITY SCHEME IN DN-136, ZONE - X.",Grants,10,2017-18,2019-20 NK/2017-18/0952,Buildings,Completed,NK-KODAMBAKKAM,137,159000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS IN ANNA MAIN ROAD , PUBLIC CONVINIENCE UNIT-28,DIV-137 , ZONE -10.",Own Sources,10,2017-18,2019-20 NK/2017-18/10790,Buildings,Completed,NK-KODAMBAKKAM,137,296000,"Attending Emergency repair works to CMS at Kamarajar Street in Division -137, U-28, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12683,Roads,Completed,NK-KODAMBAKKAM,137,1270000,"Relaying of BT Road at 62nd street -10th sector in division137, Unit-28, Zone-10.",Grants,10,2017-18,2018-19 NK/2017-18/12685,Roads,Completed,NK-KODAMBAKKAM,137,1411000,"Relaying of BT Road at 63rd street -10th sector in division137, Unit-28, Zone-10.",Grants,10,2017-18,2018-19 NK/2017-18/12686,Roads,Completed,NK-KODAMBAKKAM,137,1112000,"Improvements to road at 59th street - 10th sector in Division -137, U-28, Z-10.",Grants,10,2017-18,2018-19 NK/2017-18/12688,Roads,Completed,NK-KODAMBAKKAM,137,708000,"Improvements to road at 65th street - 10th sector in Division -137, U-28, Z-10.",Grants,10,2017-18,2018-19 NK/2017-18/13009,Electrical,Completed,NK-KODAMBAKKAM,137,255000,"MAINTENANCE WORK OF GASIFIER AND CREMATORIUM AT ERIKARAI STREET IN DN 137, UNIT 28, ZONE -10",Own Sources,10,2017-18,2018-19 NK/2017-18/13068,Parks,Completed,NK-KODAMBAKKAM,137,282000,"MAINTENANCE OF BURIAL GROUND (FOR 3MONTHS) AT ERIKARAI STREET IN 137, UNIT28, ZONE10",Own Sources,10,2017-18,2018-19 NK/2017-18/1381,Roads,Completed,NK-KODAMBAKKAM,137,881000,"LAYING OF CEMENT CONCRETE ROAD AT NSC BOSE ROAD, MGR NAGAR, IN DIVISION-137, UNIT-28,ZONE-10.",Grants,10,2017-18,2019-20 NK/2017-18/1382,Roads,Completed,NK-KODAMBAKKAM,137,1540000,"LAYING OF CEMENT CONCRETE ROAD AT OMMADURAI STREET IN DIVIDION-137,UNIT-28,ZONE-10.",Grants,10,2017-18,2018-19 NK/2017-18/16363,Roads,Completed,NK-KODAMBAKKAM,137,350000,"Road patch work at Ponnambalam Salai in Div-137, U-28, Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/16706,Buildings,Completed,P-Parks and Playfields,137,2205000,TREE PLANTATION AT VARIOUS STREETS IN ZONE - 10.,Grants,10,2017-18,2019-20 NK/2017-18/1969,Roads,Completed,NK-KODAMBAKKAM,137,284000,"LAYING OF CEMENT CONCRETE ROAD AT OMMADUARI LANE AND JEEVANANDHAM STREET (LANE) IN DIVISION-137,UNIT-28,ZONE-10.",Grants,10,2017-18,2018-19 NK/2017-18/4003,Buildings,Completed,NK-KODAMBAKKAM,137,200000,"Repair works to CMS at Kamaraj Street, CHSS at Erikkarai Street, UPHC at Erikkarai Street, Amma Unavagam (at 61st street and Anna Main Road) in Div-137, U-28, Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/4972,Roads,Completed,NK-KODAMBAKKAM,137,168100,"IMPROVEMENTS TO ROAD AT NEHRU STREET IN DIVISION - 137, U-28, Z-10.",Grants,10,2017-18,2018-19 NK/2017-18/4976,Roads,Completed,NK-KODAMBAKKAM,137,244000,"IMPROVEMENTS TO ROAD AT GANDHI STREET IN DIVISION-137, U-28, Z-10.",Grants,10,2017-18,2018-19 NK/2017-18/5279,Roads,Completed,NK-KODAMBAKKAM,137,168100,"IMPROVEMENTS TO ROAD AT ANJUGAM NAGAR 1ST CROSS STREET IN DIVISION - 137, U-28, Z-10.",Grants,10,2017-18,2018-19 NK/2017-18/5293,Roads,Completed,NK-KODAMBAKKAM,137,326500,"IMPROVEMENTS TO ROAD AT KAMARAJAR STREET IN DIVISION - 137, U-28, Z-10.",Grants,10,2017-18,2018-19 NK/2017-18/5295,Roads,Completed,NK-KODAMBAKKAM,137,336800,"IMPROVEMENTS TO ROAD AT ANNAI INDIRA STREET IN DIVISION - 137, U-28, Z-10.",Grants,10,2017-18,2018-19 NK/2017-18/8338,Buildings,Completed,NK-KODAMBAKKAM,137,840000,"Desilting at Arcot Road and Various street in division-137, U-28, Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/8341,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,360000,"Repairs to SWD at Rajamannar salai and various streets in division-137, U-28, Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9149,Buildings,Completed,NK-KODAMBAKKAM,137,278000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CMS KAMARAJ STREET, (8 MONTHS PERIOD ONLY) IN DIV-137,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9150,Buildings,Completed,NK-KODAMBAKKAM,137,278000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CHSS ERIKKARAI STREET, (8 MONTHS PERIODE ONLY) IN DIV-137,UNIT-28,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9164,Parks,Completed,NK-KODAMBAKKAM,137,333000,"ANNUAL MAINTENANCE OF PARK AT 8TH SECTOR IN DIVISION 137,UNIT-28,ZONE-X",Own Sources,10,2017-18,2018-19 NK/2017-18/9167,Roads,Completed,NK-KODAMBAKKAM,137,302000,"Providing and laying thermoplastic paint and fixing studs in speed breakers at Alagirisamy salai and various other streets in Div-137, U-28, Z-10",Own Sources,10,2017-18,2019-20 BR/2017-18/11890,Road Cut,Completed,BR-Bus Route Roads,138,149000,"Restoration of Road cut made by CMWSSB at ANNA MAIN ROAD in Dn-138, Zone-10.",Deposit Works,10,2017-18,2018-19 BR/2017-18/12018,Footpath,Completed,BR-Bus Route Roads,138,10463000,"Forming Footpath at Bharathidasan Colony Main Road in Dn-138, Zone-X",Grants,10,2017-18,2018-19 BR/2017-18/12019,Footpath,Completed,BR-Bus Route Roads,138,4185000,"Forming Footpath at 60 Feet Road in Dn-138, Zone-X",Grants,10,2017-18,2018-19 L/2017-18/0184,Electrical,Completed,L-Electrical,138,172800,"Removal of 101 nos Street lamp post and 3 nos of Kiosk Pillar of at Anna Main Road & Ashok Pillar Ring Road in Divisions - 131,137,138 Zone-X.",Own Sources,10,2017-18,2017-18 L/2017-18/7068,Electrical,Completed,L-Electrical,138,814800,Replacement of 1733 mtr 4 x 16 sqmm cable at at Ashok Pillar Ring Road & Anna Main Road Division 131 & Division 138 in Zone-X.,Own Sources,10,2017-18,2018-19 L/2017-18/8145,Electrical,Completed,L-Electrical,138,734400,"Smart class ( Five Class rooms) wiring for CHS School Puliyur Div-130 ,CMS Vadapalani Div- 130 , CHS School MGR Nagar Div-138 ,CHS School West Mambalam Div-140 ,CGHS School Saidapet Div- 142 in Zone10.",Own Sources,10,2017-18,2018-19 L/2017-18/9014,Electrical,Completed,L-Electrical,138,194700,"Electrification work at Chennai High Secondary school at Govindasamy street ,MGR Nagar in div-138, Zone - X",Own Sources,10,2017-18,2017-18 L/2017-18/9016,Electrical,Completed,L-Electrical,138,183100,"Electrification of Chennai primary school, at Govindasamy street , MGR Nagar ,Zone -X .",Own Sources,10,2017-18,2017-18 L/2017-18/9018,Electrical,Completed,L-Electrical,138,172300,"Supply and Fixing of Tubelight , Fan and other Electrification work at of Chennai Higher Secondary school, at Govindasamy street , MGR Nagar Division -138 , Zone -X .",Own Sources,10,2017-18,2017-18 NK/2017-18/0102,Buildings,Completed,NK-KODAMBAKKAM,138,68000,"DISMANTLING THE DAMAGED SWD RCC COVER SLAB AND PROVIDING NEW RCC COVER SLAB AT NETHAJI NAGAR AND BHARATHIDASAN COLONY IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2017-18 NK/2017-18/1049,Buildings,Completed,NK-KODAMBAKKAM,138,146000,"SUPPLYING AND FIXING MS DOOR AND PUMPING WORK IN CHSS AT GOVINDASAMY STREET, MGR NAGAR IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2017-18 NK/2017-18/1050,Buildings,Completed,NK-KODAMBAKKAM,138,55000,"PROVIDING MS SHEET BARRICADE AT ANNA MAIN ROAD (NEAR EB OFFICE) IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2017-18 NK/2017-18/1212,Buildings,Completed,NK-KODAMBAKKAM,138,104000,"CONSTRUCTION OF COMPOUND WALL BURIAL GROUND AT PACHAIYAPPAN 1ST CROSS STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2017-18 NK/2017-18/12797,Buildings,Completed,NK-KODAMBAKKAM,138,1060000,"Operation and maintenance of high treated drinking water plant(RO/UV filtration) at 60 feet road junction, K.K.Nagar (For 12 months),Div-138,U-28,Z-10",Own Sources,10,2017-18,2019-20 NK/2017-18/15997,Buildings,Completed,NK-KODAMBAKKAM,138,79000,"REPAIRS WORK OF CPS AT GOVINDASAMY STREET IN DIVISION-138,UNIT-28,ZONE-10.",Grants,10,2017-18,2018-19 NK/2017-18/16013,Buildings,Completed,NK-KODAMBAKKAM,138,185000,"RENOVATION OF ANGANWADI AT ANNAI SATHYA NAGAR 3RD STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/17399,Buildings,Completed,NK-KODAMBAKKAM,138,203000,"IMPROVEMENT WORK AT AMMA UNAVAGAM ,DIVISION OFFICE,HOSPITAL,GOVINDASAMY SALAI PC,CHSS AT MGR NAGAR AND VARIOUS STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/1772,Roads,Completed,NK-KODAMBAKKAM,138,795000,"LAYING CEMENT CONCRETE ROAD AT KARIKALAN STREET, MGR NAGAR,IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/1805,Roads,Completed,NK-KODAMBAKKAM,138,532000,"LAYING CEMENT CONCRETE ROAD AT THIRUGNANASAMBANDAR STREET MGR NAGAR,IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/1811,Roads,Completed,NK-KODAMBAKKAM,138,532000,"LAYING CEMENT CONCRETE ROAD AT THIRUNAVUKKARASAR STREET MGR NAGAR,IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/1812,Roads,Completed,NK-KODAMBAKKAM,138,836000,"LAYING CEMENT CONCRETE ROAD AT BHUDDAR STREET MGR NAGAR,IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/1814,Roads,Completed,NK-KODAMBAKKAM,138,723000,"LAYING CEMENT CONCRETE ROAD AT SILAPATHIGARAM STREET MGR NAGAR,IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/1815,Roads,Completed,NK-KODAMBAKKAM,138,723000,"LAYING CEMENT CONCRETE ROAD AT VALAYAPATHY STREET MGR NAGAR,IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/1816,Roads,Completed,NK-KODAMBAKKAM,138,818000,"LAYING CEMENT CONCRETE ROAD AT KUNDALAKESI STREET MGR NAGAR,IN DIVISION-138,UNIT-28, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8346,Buildings,Completed,NK-KODAMBAKKAM,138,300000,"Desilting of SWD at Ashok pillar salai and various streets in Division-138, U-28, Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/8422,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,355000,"MINOR REPAIR OF STORM WATER DRAIN ASHOK PILLAR SALAI AND VARIOUS STREET IN DIV-138,U-28,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9104,Buildings,Completed,B-Buildings,138,143000,"PREPARATION OF SMART CLASS ROOM AT CHSS ,GOVINDASAMY STREET ,MGR NAGAR IN DIV-138,U-28,Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9106,Buildings,Completed,NK-KODAMBAKKAM,138,40000,"CONSTRUCTION OF DAMAGE COMPOUND WALL AT CPS GOVINDASAMY STREET MGR NAGAR IN DIVISION-138,UNITE-28,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9140,Buildings,Completed,NK-KODAMBAKKAM,138,429000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT GHSS ANNA MAIN ROAD , MGR NAGAR, (8 MONTHS PERIODE ONLY) IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9143,Buildings,Completed,NK-KODAMBAKKAM,138,208000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CPS GOVINDASAMY STREET , MGR NAGAR, (8 MONTHS PERIOD ONLY) IN DIV-138,UNIT-28,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9151,Buildings,Completed,NK-KODAMBAKKAM,138,278000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CHSS ANNA MAIN ROAD , MGR NAGAR, (8 MONTHS PERIODE ONLY) IN DIV-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9162,Parks,Completed,NK-KODAMBAKKAM,138,573000,"ANNUAL MAINTENANCE OF PARK AT BHARATHIDASEN COLONY 5TH & 6TH STREET, KK NAGAR IN DIVISION-138, UNIT-28, ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9170,Roads,Completed,NK-KODAMBAKKAM,138,394000,"Providing and laying thermoplastic paint and fixing studs in speed breakers at Pillaiyarkoil street and various other streets in Div-138, U-28, Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9338,Roads,Completed,NK-KODAMBAKKAM,138,2592000,"RELAYING THE BITUMINOUS CONCRETE ROAD AT MGR NAGAR THANTHAI PERIYAR STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9340,Roads,Completed,NK-KODAMBAKKAM,138,412400,"IMPROVEMENT CEMENT CONCRETE ROAD AT PULITHEVAN STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9341,Roads,Completed,NK-KODAMBAKKAM,138,795000,"LAYING CEMENT CONCRETE ROAD AT PALAI STREET AND THIRUNAVUKKARASAR STREET IN DIV-18,U-28,Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9342,Roads,Completed,NK-KODAMBAKKAM,138,509000,"LAYING CEMENT CONCRETE ROAD AT BUDHAR STREET AND BHARATHIYAR STREET PART IN DIV-18,U-28,Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9355,Road Cut,Completed,NK-KODAMBAKKAM,138,504300,"IMPROVEMENT BITUMINOUS CONCRETE ROAD AT GNANAOLI STREET IN DIVISION - 138, U-28, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9357,Road Cut,Completed,NK-KODAMBAKKAM,138,515500,"IMPROVEMENT CEMENT CONCRETE ROAD AT JAMBULINGAM STREET IN DIVISION - 138, U-28, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9359,Road Cut,Completed,NK-KODAMBAKKAM,138,343700,"IMPROVEMENT CEMENT CONCRETE ROAD AT NAGAPPAN STREET AND GNANAOLIVU STREET PART IN DIVISION - 138, U-28, Z-10.",Own Sources,10,2017-18,2018-19 B/2017-18/10957,Buildings,Completed,B-Buildings,139,39094197,"Construction of 142 seats of Conventionel toilet in 17 locations at various places in Zone-6,7,9 & 10",Own Sources,10,2017-18,2020-21 L/2017-18/0953,Electrical,Completed,L-Electrical,139,199900,"Supply and Fixing of 55 nos of 2C fuse Box and rising of cable at Various areas in division on-139, Zone-X.",Own Sources,10,2017-18,2017-18 L/2017-18/0957,Electrical,Completed,L-Electrical,139,198500,Supply and Fixing of 25 nos of 2C fuse Box and rising of cable at Various areas in division 138 & 139 Zone-X.,Own Sources,10,2017-18,2017-18 L/2017-18/0968,Electrical,Completed,L-Electrical,139,189300,"Raising of 2 Core & 4 core cable at Various areas in division in-131,139, Zone-X.",Own Sources,10,2017-18,2017-18 NK/2017-18/0843,Buildings,Completed,NK-KODAMBAKKAM,139,787000,"DISMANTLING OF THE EXISTING CHENNAI PRIMARY SCHOOL BUILDING AT CHS CAMPUS,JAFFERKHANPET MAIN ROAD IN DIV-139,U-28,Z-10",Own Sources,10,2017-18,2017-18 NK/2017-18/10068,Buildings,Completed,NK-KODAMBAKKAM,139,1000000,"CONSTRUCTION OF MULTIPURPOSE HALL (RATION SHOP) AT ERIKKARAI SALAI IN DIVISION-139,UNIT-28,ZONE-10.(2016-17 SAIDAPET MLA FUND)",MLACDS,10,2017-18,2018-19 NK/2017-18/11846,Buildings,Completed,NK-KODAMBAKKAM,139,560000,"Improvements Work in Burial Ground at West Saidapet, DN139, Unit-28, Zone -X",Own Sources,10,2017-18,2019-20 NK/2017-18/14693,Buildings,Completed,NK-KODAMBAKKAM,139,122000,"Improvement work at division office,burial ground and various street in division-139,unit-28,zone-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/16213,Buildings,Completed,NK-KODAMBAKKAM,139,800000,"IMPROVEMENT WORK AT CHENNAI HIGH SCHOOL AT JAFFERKANPET MAIN ROAD IN DN 139, UNIT-28, ZONE -X",Grants,10,2017-18,2018-19 NK/2017-18/16239,Buildings,Completed,NK-KODAMBAKKAM,139,261000,"REPAIR AND IMPROVEMENTS IN ANGANWADI (CODE NO. 10038) AT RR COLONY 3RD THIRD STREET IN DN 139, UNIT-28, ZONE - X",Grants,10,2017-18,2019-20 NK/2017-18/4077,Buildings,Completed,NK-KODAMBAKKAM,139,210700,"PROVIDING PARTITION FOR CLASS ROOMS AT CHENNAI MIDDLE SCHOOL, PILLAIYARKOIL STREET,JAFFERKHANPET IN DIV139,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/7077,Buildings,Completed,NK-KODAMBAKKAM,139,1500000,"CONSTRUCTION OF 16TH CEREMONY HALL AT ERIKARAI STREET SUNDARAMOORTHY STREET JUNCTION IN DIV-139,U-28,Z-10.( 2016-17 SAIDAPET MLA FUND)",MLACDS,10,2017-18,2020-21 NK/2017-18/8367,Buildings,Completed,NK-KODAMBAKKAM,139,170000,"Desilting of SWD at Arunachalam Street and other streets in Division-139, U-28, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8829,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,160000,"REPAIR TO SWD AT ARUNACHALAM STREET AND VARIOUS STREET IN DIVISION - 139,U-28,Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9145,Buildings,Completed,NK-KODAMBAKKAM,139,139000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CPS ERIKKARAI STREET, (8 MONTHS PERIODE ONLY) IN DIV-139,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9172,Buildings,Completed,NK-KODAMBAKKAM,139,278000,"PROVIDING PRIVATE LABOUR FOR SWEEPING AND TOILET CLEANING WORK AT CHSS ERIKKARAI STREET , (8 MONTHS PERIOD ONLY) IN DIV-139,UNIT-28,ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9178,Buildings,Completed,NK-KODAMBAKKAM,139,307000,"ANNUAL MAINTENANCE OF BIO GAS PLANT AT WEST SAIDAPET BURIAL GROUNT IN DIV-139,U-28,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9181,Buildings,Completed,NK-KODAMBAKKAM,139,67000,"PROVIDING AND FIXING OF FENCING AT WEST SAIDAPET BURIAL GROUND COMPOUND WALL IN DIV-139,U-28,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9921,Roads,Completed,NK-KODAMBAKKAM,139,806000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT KANNAMMAL STREET IN DN 139, UNIT-28, ZONE 10",Grants,10,2017-18,2018-19 B/2017-18/15578,Buildings,Completed,B-Buildings,140,887000,"Supplying and fixing of Two seater bench cum tables for propsed smart classes in CHSS West mambalam in DN 140 Zone 10, CGHSS Saidapet in DN 142 Zone 10, CHSS Maduvankarai in DN 174 Zone 13 and CHSS Thiruvanmiyur in DN 182 Zone 13",Own Sources,10,2017-18,2018-19 BR/2017-18/10388,Road Cut,Completed,BR-Bus Route Roads,140,1510000,"RESTORATION OF ROAD CUT MADE BY TANTRANSCO AT KODAMBAKKAM ROADT IN DIV-140, ZONE-10.(FROM JUNCTION OF WEST JONES ROAD TO KARUNANIDHI STREET.).",Deposit Works,10,2017-18,2018-19 BR/2017-18/13180,Road Cut,Completed,BR-Bus Route Roads,140,142000,"RESTORATION OF ROAD CUT MADE BY TAN TRANSCO AT REDDY KUPPAM ROAD (FROM JUNCTION OF KUMARAN COLONY 2ND STREET TO ARANGANATHAN SERVICE ROAD JUNCTION) IN DIV 140, ZONE-10.",Deposit Works,10,2017-18,2018-19 NK/2017-18/12510,Roads,Completed,NK-KODAMBAKKAM,140,650000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 30MM THICK BY PAVER FINISHER AT THALAYARI STREET IN DIV-140 UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12511,Roads,Completed,NK-KODAMBAKKAM,140,800000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 30MM THICK BY PAVER FINISHER AT SOUTH K.R.KOIL STREET IN DIV-140 UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12512,Roads,Completed,NK-KODAMBAKKAM,140,500000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 30MM THICK BY PAVER FINISHER AT KARANI GARDEN 1ST STREET IN DIV-140 UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12513,Roads,Completed,NK-KODAMBAKKAM,140,500000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 30MM THICK BY PAVER FINISHER AT KARANI GARDEN 2ND STREET IN DIV-140 UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12514,Roads,Completed,NK-KODAMBAKKAM,140,800000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 30MM THICK BY PAVER FINISHER AT VANDIKARAN STREET IN DIV-140 UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/12515,Roads,Completed,NK-KODAMBAKKAM,140,762000,"RELAYING OF BITUMINOUS CONCRETE AT KALAIGNAR KARUNANIDHI 1ST STREET AND PUSHPAVATHIAMMAL STREET IN DIV-140 UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/2009,Buildings,Completed,NK-KODAMBAKKAM,140,750000,"LAYING OF CEMENT CONCRETE ROAD AT SADAIYAPPAN LANE IN DIVISION -140, UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2010,Buildings,Completed,NK-KODAMBAKKAM,140,380000,"LAYING OF CEMENT CONCRETE ROAD AT CONSERVANCY LANE IN DIVISION -140, UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2011,Buildings,Completed,NK-KODAMBAKKAM,140,300000,"LAYING OF CEMENT CONCRETE ROAD AT VENKATRAMAN STREET IN DIVISION -140, UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2012,Buildings,Completed,NK-KODAMBAKKAM,140,350000,"LAYING OF CEMENT CONCRETE ROAD AT PADAVET TAMMAN KOIL 2ND STREET IN -140, UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/2013,Buildings,Completed,NK-KODAMBAKKAM,140,350000,"LAYING OF CEMENT CONCRETE ROAD AT SRINIVASA IYENGAR 1ST STREET IN DIV-140, UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/3056,Buildings,Completed,NK-KODAMBAKKAM,140,278000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI BOYS HIGHER SECONDARY SCHOOL AT KODAMBAKKAM ROAD IN DIVISION -140, UNIT -30, ZONE -10. (FOR 8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3059,Buildings,Completed,NK-KODAMBAKKAM,140,208000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI HIGHER SECONDARY SCHOOL AT K.R.KOIL STREET IN DIVISION -140, UNIT -30, ZONE -10. (8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3060,Buildings,Completed,NK-KODAMBAKKAM,140,208000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI MIDDLE SCHOOL AT PERUMAL KOIL STREET IN DIVISION -140, UNIT -30, ZONE -10. (FOR 8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3061,Buildings,Completed,NK-KODAMBAKKAM,140,139000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI MIDDLE SCHOOL AT VANDIKARAN STREET IN DIVISION -140, UNIT -30, ZONE -10. (FOR 8 MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3570,Buildings,Completed,NK-KODAMBAKKAM,140,169000,"REPAIRS TO THE ANGANWADI AT KODAMBAKKAM ROAD AND KUMARAN COLONY 1ST STREET IN DIVISION-140,UNIT-30, ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/4006,Buildings,Completed,NK-KODAMBAKKAM,140,377000,"LAYING OF CEMENT CONCRETE ROAD AT SRINIVASA IYENGAR 1ST STREET AND PUSHPAVATHIAMMAL 1ST STREET IN DIV-140, UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/5188,Roads,Completed,NK-KODAMBAKKAM,140,1680000,"IMPROVEMENTS TO THE ROAD AT KARUNANIDHI 1ST STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/5189,Roads,Completed,NK-KODAMBAKKAM,140,840000,"IMPROVEMENTS TO THE ROAD AT KAMARAN COLONY 1ST STREET IN DIV-140, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8245,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,199000,"DESILTING OF STORM WATER DRAIN AT KODAMBAKKAM ROAD,SAMBANGI STREET,PUSHPAVATHIAMMAL STREET,VAIVEL PURAM, JOTHIRAMALINGAM STREET,DEVANATHAN COLONY, NAGARATHINAMMAL COLONY, KARUNANITHI 1ST STREET,KUMARAN COLONY 1ST STREET, REDYKUPPAM SALAI, RAGHAVAN COLONY AND KRISHNAN STREET IN DIVISION - 140, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9060,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,617000,"REPAIR WORKS TO THE STORM WATER DRAIN AT REYKUPPAM SALAI, KODAMBAKKAM ROAD AND VARIOUS STREETS IN DIV-140,U-30,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9266,Buildings,Completed,B-Buildings,140,218000,"PREPARATION OF SMART CLASS IN CHS SCHOOL AT K.R.KOIL STREET IN DIV -140,U -30,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/9307,Buildings,Completed,NK-KODAMBAKKAM,140,184000,"REPAIRS WORKS TO THE CHENNAI BOYS HIGHER SECONDARY SCHOOL AT KODAMBAKKAM ROAD AND UPHC AT GOVINDAN ROAD IN DIV- 140 , U- 30, Z-10.",Own Sources,10,2017-18,2019-20 P/2017-18/2375,Parks,Completed,P-Parks and Playfields,140,4780000,"PROPOSED REDEVELOPMENT OF ELLAIAMMAN PARK IN THE AREA BASED DEVELOPMENT (ABD) AREA OF T.NAGAR AS PART OF SMART CITY SCHEME IN DN-140, ZONE - X.",Grants,10,2017-18,2018-19 BR/2017-18/0872,Footpath,Completed,BR-Bus Route Roads,141,7308000,"Street designing of existing cement concrete road at C.I.T.Nagar 5th Main Road in Dn-141, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0878,Footpath,Completed,BR-Bus Route Roads,141,15176000,"Street designing of existing road at Muthurangan salai in Dn-141, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0879,Footpath,Completed,BR-Bus Route Roads,141,8104000,"Street designing of existing road at Mooparappan street in Dn-141, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0893,Footpath,Completed,BR-Bus Route Roads,141,8184000,"Street designing of existing cement concrete road at C.I.T.Nagar Canal Bank Road in Dn-141, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/0894,Footpath,Completed,BR-Bus Route Roads,141,5184000,"Street designing of existing road at C.I.T.Nagar Model House Road in Dn-141, Zone-10 under Smart City",SMART CITY - BRR,10,2017-18,2019-20 BR/2017-18/10391,Road Cut,Completed,BR-Bus Route Roads,141,1584000,"RESTORATION OF ROAD CUT MADE BY TANTRANSCO AT NEW BOAG ROAD IN DIV-141, ZONE-10.(FROM JUNCTION OF 70 FEET ROAD TO SOUTH USMAN ROAD.).",Deposit Works,10,2017-18,2018-19 BR/2017-18/16017,Road Cut,Completed,BR-Bus Route Roads,141,430000,"RESTORATION OF ROAD CUT MADE BY TAN TRANSCO AT BURKIT ROAD IN DIV-141, ZONE-10. (FROM MOOPARAPPAN STREET JUNCTION TO VENKAT NARAYANA ROAD JUNCTION) LENGTH-90.00M.",Deposit Works,10,2017-18,2019-20 NK/2017-18/0240,Buildings,Completed,NK-KODAMBAKKAM,141,1265000,"PROPOSED CONSTRUCTION OF RCC ROOFED MULTI PURPOSE HALL - 1 AT MADURAIVEERAN KOIL STREET IN DIVISION - 141, UNIT -30, ZONE - 10",Own Sources,10,2017-18,2018-19 NK/2017-18/0241,Buildings,Completed,NK-KODAMBAKKAM,141,921000,"PROPOSED CONSTRUCTION OF RCC ROOFED MULTI PURPOSE HALL - 2 AT MADURAIVEERAN KOIL STREET IN DIVISION - 141, UNIT -30, ZONE - 10",Own Sources,10,2017-18,2018-19 NK/2017-18/10768,Roads,Completed,NK-KODAMBAKKAM,141,715000,"LAYING CEMENT CONCRETE ROAD AT NEW STREET IN DIV-141,UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/10769,Roads,Completed,NK-KODAMBAKKAM,141,420000,"LAYING CEMENT CONCRETE ROAD AT SRINIVASAPURAM STRET IN DIV-141,UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/10770,Roads,Completed,NK-KODAMBAKKAM,141,170000,"LAYING OF CEMENT CONCRETE AT MADELY 2ND STREET LANE IN DIV-141,UNIT-30,ZONE-10",Own Sources,10,2017-18,2018-19 NK/2017-18/11359,Buildings,Completed,NK-KODAMBAKKAM,141,440000,"IMPROVEMENT AND REPAIR WORKS TO CHENNAI PRIMARY SCHOOL AT CIT NAGAR 4 TH MAIN ROAD AND NEW BOAG ROAD IN DIV-141, UNIT-30, ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/11748,Buildings,Completed,NK-KODAMBAKKAM,141,300000,"IMPROVEMENT AND REPAIR WORKS TO THE LALITHA PURAM ANGANVADI IN DIV-141, UNIT-30, ZONE-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/1240,Buildings,Completed,NK-KODAMBAKKAM,141,140000,"IMPROVEMENT WORKS FOR CPS AT KANNAMAPET AND CHSS AT CIT NAGAR 4TH MAIN ROAD AND PROVIDING COMPOUNDWALL WORK FOR CANAL AT CIT NAGAR IN DIV-141, U-30,Z-10.",Own Sources,10,2017-18,2017-18 NK/2017-18/1616,Buildings,Completed,NK-KODAMBAKKAM,141,612000,"IMPROVEMENTS TO THE DOG SHELTER AT MUTHURANGAN SALAI KANNAMAPET IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3365,Buildings,Completed,NK-KODAMBAKKAM,141,178000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT MOOSA STREET LANE IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3366,Buildings,Completed,NK-KODAMBAKKAM,141,199000,"RELAYING ROAD WITH BT SURFACE USING PAVER FINISHER AT DHAMODARAN STREET IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3370,Buildings,Completed,NK-KODAMBAKKAM,141,1717000,"IMPROVEMENTS TO ROAD WORK FOR NEW BOAG ROAD IN DIVISION - 141, UNIT -30, ZONE -10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3372,Buildings,Completed,NK-KODAMBAKKAM,141,2329000,"IMPROVEMENTS TO ROAD WORK FOR SOUTH WEST BOAG ROAD IN DIVISION - 141, UNIT -30, ZONE -10.",Own Sources,10,2017-18,2018-19 NK/2017-18/9041,Buildings,Completed,NK-KODAMBAKKAM,141,139000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI HIGHER SECONDARY SCHOOL AT CIT NAGAR 4 th MAIN ROAD IN DIVISION -141, UNIT -30, ZONE -10. (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/9047,Buildings,Completed,NK-KODAMBAKKAM,141,139000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI HIGH SCHOOL AT KANNAMMAPET NEW BOAG ROAD IN DIVISION -141, UNIT -30, ZONE -10. (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/9048,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,850000,"REPAIR WORKS TO THE STROM WATER DRAIN AT CIT NAGAR 2 nd MAIN ROAD AND VARIOUS STREET IN DIVISION - 141, UNIT -30, ZONE -10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9049,Buildings,Completed,NK-KODAMBAKKAM,141,139000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI PRIMARY SCHOOL AT KANNAMMAPET NEW BOAG ROAD IN DIVISION -141, UNIT -30, ZONE -10. (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/9242,Buildings,Completed,NK-KODAMBAKKAM,141,139000,"OUT SOURCING OF PRIVATE WORKERS FOR CHENNAI PRIMARY SCHOOL AT CIT NAGAR 4TH MAIN ROAD IN DIVISION -141, UNIT -30, ZONE -10. (FOR 8 MONTHS)",Own Sources,10,2017-18,2018-19 NK/2017-18/9852,Buildings,Completed,NK-KODAMBAKKAM,141,1882000,"PROPOSED CONSTRUCTION OF SHOPPING COMPLEX AT FIRST FLOOR AS THE EXISTING SHOPPING COMPLEX BUILDING AT CIT NAGAR 4 TH MAIN ROAD JN. OF CANAL BANK ROAD IN DIVISION - 141, UNIT -30, ZONE -10.",Own Sources,10,2017-18,2018-19 P/2017-18/10797,Parks,Completed,P-Parks and Playfields,141,4095000,"Providing Packaged Sewage Treatment Plant Capacity of 20 KLD including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at C.I.T.Nagar 3rd Main road",Own Sources,10,2017-18,2019-20 BR/2017-18/10381,Road Cut,Completed,BR-Bus Route Roads,142,906000,"RESTORATION OF ROAD CUT MADE BY TANTRANSCO AT MOSQUE STREET IN DIV-142, ZONE-10.(FROM JUNCTION OF JAYARAM STREET TO ALANDUR ROAD).",Deposit Works,10,2017-18,2018-19 BR/2017-18/10386,Road Cut,Completed,BR-Bus Route Roads,142,906000,"RESTORATION OF ROAD CUT MADE BY TANTRANSCO AT JAYARAM STREET IN DIV-142, ZONE-10.(FROM JUNCTION OF WEST JONES ROAD TO MOSQUE STREET).",Deposit Works,10,2017-18,2018-19 NK/2017-18/11832,Buildings,Completed,NK-KODAMBAKKAM,142,164000,"REPAIRS AND IMPROVEMENTS WORK TO THE CHENNAI URUDU PRIMARY SCHOOL AT BAZAAR ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/11834,Buildings,Completed,NK-KODAMBAKKAM,142,282000,"REPAIRS AND IMPROVEMENTS WORK TO THE CHENNAI PRIMARY SCHOOL AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/2015,Buildings,Completed,NK-KODAMBAKKAM,142,750000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT JAYARAM STREET AND VGP LANE REACH-2 IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/2016,Buildings,Completed,NK-KODAMBAKKAM,142,650000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT SUBRAMANIA MUDALI LANE IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/2017,Roads,Completed,NK-KODAMBAKKAM,142,450000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT BAZAAR ROAD LANE IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/2018,Roads,Completed,NK-KODAMBAKKAM,142,360000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT DHARMARAJA KOIL LANE IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/2019,Buildings,Completed,NK-KODAMBAKKAM,142,460000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT JONES ROAD LANE (SOUTH) IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/2020,Buildings,Completed,NK-KODAMBAKKAM,142,880000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT KOOTHADUM PILLAYAR KOIL LANE IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3012,Buildings,Completed,NK-KODAMBAKKAM,142,500000,"SUPPLY AND ERECTION OF GYM EQUIPMENTS AT V.V.KOIL STREET IN DIV-142, UNIT-30,ZONE-10. ( M.L.A FUND )",MLACDS,10,2017-18,2018-19 NK/2017-18/3019,Buildings,Completed,NK-KODAMBAKKAM,142,500000,"SUPPLY AND ERECTION OF GYM EQUIPMENTS AT GODHAMEDU IN DIV-142, UNIT-30,ZONE-10. ( M.L.A FUND )",MLACDS,10,2017-18,2018-19 NK/2017-18/3044,Roads,Completed,NK-KODAMBAKKAM,142,680000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT JAYARAM STREET LANE AND VGP LANE REACH -1 IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3046,Roads,Completed,NK-KODAMBAKKAM,142,800000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT JAYARAM STREET IN DIV-142, U-30,Z-10",Own Sources,10,2017-18,2018-19 NK/2017-18/3049,Roads,Completed,NK-KODAMBAKKAM,142,600000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT MADHA CHURCH LANE IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/3050,Buildings,Completed,NK-KODAMBAKKAM,142,139000,"OUT SOURCING OF PRIVATE LABOR FOR CONSERVANCY WORK AT CHENNAI PRIMARY SCHOOL AT BAZAAR ROAD IN DIV 142,UNIT-30,ZONE-10.(FOR 8MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3051,Buildings,Completed,NK-KODAMBAKKAM,142,278000,"OUT SOURCING OF PRIVATE LABOR FOR CONSERVANCY WORK AT CGHS SCHOOL AT WEST JONES ROAD IN DIV 142,UNIT-30,ZONE-10.(FOR 8MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3053,Buildings,Completed,NK-KODAMBAKKAM,142,208000,"OUT SOURCING OF PRIVATE LABOUR FOR CONSERVANCY WORK AT CHENNAI PRIMARY SCHOOL AT WEST JONES ROAD IN DIV 142,UNIT-30,ZONE-10.(8MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/3054,Buildings,Completed,NK-KODAMBAKKAM,142,208000,"OUT SOURCING OF PRIVATE LABOR FOR CONSERVANCY WORK AT CHENNAI MIDDLE SCHOOL AT THIDEER NAGAR IN DIV 142,UNIT-30,ZONE-10.(FOR 8MONTHS)",Own Sources,10,2017-18,2019-20 NK/2017-18/8143,Roads,Completed,NK-KODAMBAKKAM,142,350000,"LAYING OF CEMENT CONCRETE ROAD (M40 GRADE) AT JEER NAIDU LANE IN DIV-142, U-30, Z-10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8253,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,498000,"DESILTING OF STORM WATER DRAIN AT TANK SQUARE STREET, TANK SQURE EAST STREET BAZAAR ROAD,JEENIS ROAD, SUBRAMANIA SALAI, WEST JONES ROAD AND KARUNANITHI STREET AND SUBWAY WELL AT ALANDUR ROAD AND WEST JONES ROAD IN DIVISION - 142, UNIT -30, ZONE - 10.",Own Sources,10,2017-18,2018-19 NK/2017-18/8255,Subway,Completed,NK-KODAMBAKKAM,142,146000,"REPAIR AND IMPROVEMENTS WORKS TO THE COMMUNITY HALL AT SAMIYAR THOTTAM IN DIVISION-142,UNIT-30,ZONE-10",Own Sources,10,2017-18,2019-20 NK/2017-18/9000,Roads,Completed,NK-KODAMBAKKAM,142,258000,"LAYING OF SPEED BREAKERS AT ABDUL RAZACK STREET IN DIV-142, U-30,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9001,Roads,Completed,NK-KODAMBAKKAM,142,124000,"LAYING OF SPEED BREAKERS AT PILLAIYAR KOIL STREET IN DIV-142, U-30,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9002,Roads,Completed,NK-KODAMBAKKAM,142,83000,"LAYING OF SPEED BREAKERS AT SESHACHALAM STREET IN DIV-142, U-30,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9003,Roads,Completed,NK-KODAMBAKKAM,142,51000,"LAYING OF SPEED BREAKERS AT SUBRAMANIYA SALAI IN DIV-142, U-30,Z-10.",Own Sources,10,2017-18,2019-20 NK/2017-18/9263,Buildings,Completed,B-Buildings,142,226000,"PREPARATION OF SMART CLASSING CGHS SCHOOL AT WEST JONES ROAD IN DIV-142, U-30,Z-10.",Own Sources,10,2017-18,2018-19 BR/2017-18/1904,Road Cut,Completed,BR-Bus Route Roads,143,474000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -11 (3838/2016),Deposit Works,11,2017-18,2018-19 L/2017-18/12352,Electrical,Completed,L-Electrical,143,21588000,"Provision of 274Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 182 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at SRR nagar, Matha koil street phase I ,Nolambur in 143 Zone XI","Loans, Grants And Own Sources",11,2017-18,2019-20 NL/2017-18/12063,Buildings,Completed,NL-VALASARAVAKKAM,143,104000,"IMPROVEMENT TO INTERIOR BT ROADS AT PADMA STREET 2ND CROSS STREET (PART) IN DN-143, UNIT-32, ZONE-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12067,Buildings,Completed,NL-VALASARAVAKKAM,143,834000,"IMPROVEMENT TO INTERIOR BT ROADS AT VELLALAR PRADHANA STREET (PART) IN DN-143, UNIT-32, ZONE-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12068,Buildings,Completed,NL-VALASARAVAKKAM,143,421000,"IMPROVEMENT TO INTERIOR BT ROADS AT PADMA STREET (PART) IN DN-143, UNIT-32, ZONE-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12069,Buildings,Completed,NL-VALASARAVAKKAM,143,104000,"IMPROVEMENT TO INTERIOR BT ROADS AT PADMA STREET 1ST CROSS STREET (PART) IN DN-143, UNIT-32, ZONE-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12854,Buildings,Completed,NL-VALASARAVAKKAM,143,1096000,"IMPROVEMENT TO INTERIOR BT ROADS AT DABC AISHWARYAM MAIN ROAD IN DN-143, UNIT-32, ZONE-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/13177,Footpath,Completed,NL-VALASARAVAKKAM,143,684000,"Construction of Roadside footpath at College Road in Div-143, Unit-32, Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/13838,Roads,Completed,NL-VALASARAVAKKAM,143,594000,"ROAD FORMATION WORK AT DABC MAIN ROAD & 9TH MAIN ROAD PHASE-I IN DN - 143 , U -32 , Z- XI",Own Sources,11,2017-18,2018-19 NL/2017-18/14149,Buildings,Completed,NL-VALASARAVAKKAM,143,274000,"Erection of Notice Board at vacant lands (169 nos.) to avoid dumping of garbage at vacant lands in Dn-143, 144, 146 &147, Unit - 32, Zone - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/14367,Buildings,Completed,NL-VALASARAVAKKAM,143,185000,"Improvement to Existing of Public convenience at 21st Cross Street, Nolambur in Dn.143 & Pillayar koil street and Nagathamman Koil Street in Dn.144, Unit-32, Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/14521,Parks,Completed,NL-VALASARAVAKKAM,143,375000,"Forming to the road side park at Phase-1 6th cross street park in Division -143, Unit -32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/14581,Parks,Completed,NL-VALASARAVAKKAM,143,48000,"Compost pit at Various parks in div- 143,144,146 & 147 U -32 , Z- XI",Own Sources,11,2017-18,2018-19 NL/2017-18/16665,Buildings,Completed,NL-VALASARAVAKKAM,143,1290000,"Construction of Compound Wall OSR Land at VGN Nagar V.O.C Street (Park) in Dn - 143, U - 32, Z - XI.",Own Sources,11,2017-18,2019-20 NL/2017-18/16680,Buildings,Completed,NL-VALASARAVAKKAM,143,1500000,"Construction of Compound Wall OSR Land at Mogappair West Phase - I (Park) in Dn - 143, U - 32, Z - XI.",Own Sources,11,2017-18,2020-21 NL/2017-18/16681,Buildings,Completed,NL-VALASARAVAKKAM,143,969000,"Construction of Compound Wall OSR Land at Sakthi Nagar (Park) in Dn - 143, U - 32, Z - XI.",Own Sources,11,2017-18,2019-20 NL/2017-18/1943,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,852600,"Desilting the storm water drain and side drain at various street in Division - 143, Unit - 32 , Zone -11",Own Sources,11,2017-18,2017-18 NL/2017-18/2211,Parks,Completed,NL-VALASARAVAKKAM,143,385000,"Annual Maintenance of Phase-1 9th main road park, Phase -I, 13th cross street park, Channel road park and Phase-1 6th main road park (One year) in DN-143, Unit-32, Zone-11",Own Sources,11,2017-18,2019-20 NL/2017-18/3213,Buildings,Completed,NL-VALASARAVAKKAM,143,591000,"Maintenance and Improvement work at Sri Ram Nagar Amma Unavagam & Phase-I 4th Main Road Amma Unavagam in Division-143, Unit-32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/3255,Roads,Completed,NL-VALASARAVAKKAM,143,736000,"Providing Speed Breaks as per IRC design at Phase-I, 4th, 5th and 8th main road, Phase -I 18th cross street , Perumal Koil Street and Union Road in DN-143, Unit-32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/4040,Parks,Completed,NL-VALASARAVAKKAM,143,541000,"Providing open gym Equipments including plat form at PH-1 3rd main road park in Div-143,unit-32 and zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/6081,Road Cut,Completed,NL-VALASARAVAKKAM,143,1139000,"IMPROVEMENT TO INTERIOR BT ROADS AT DABC main road in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/6082,Road Cut,Completed,NL-VALASARAVAKKAM,143,1122000,"IMPROVEMENT TO INTERIOR BT ROADS AT PHASE-1, 4th main road in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/6083,Road Cut,Completed,NL-VALASARAVAKKAM,143,870000,"IMPROVEMENT TO INTERIOR BT ROADS AT Vellalar Pradhana salai in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/6084,Road Cut,Completed,NL-VALASARAVAKKAM,143,259000,"IMPROVEMENT TO INTERIOR BT ROADS AT MCK layout 3rd main road in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/6085,Road Cut,Completed,NL-VALASARAVAKKAM,143,189000,"IMPROVEMENT TO INTERIOR BT ROADS AT MCK layout 2nd cross street in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/6086,Road Cut,Completed,NL-VALASARAVAKKAM,143,538000,"IMPROVEMENT TO INTERIOR BT ROADS AT Padma street in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/6087,Road Cut,Completed,NL-VALASARAVAKKAM,143,137000,"IMPROVEMENT TO INTERIOR BT ROADS AT Padma street 1st cross in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/6088,Road Cut,Completed,NL-VALASARAVAKKAM,143,137000,"IMPROVEMENT TO INTERIOR BT ROADS AT Padma street 2nd cross street in division 143, unit-32, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/7212,Roads,Completed,NL-VALASARAVAKKAM,143,740400,"Compactor Bin washing(inside & outside) using Mechanical sprayer twice a month for period of 6 months (617 nos) in Dn - 143 to 155, Unit - 32,33 & 34, Zone - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/7213,Roads,Completed,NL-VALASARAVAKKAM,143,894650,"Repair and Maintenance of Compactor Bins for 6 months (617 nos) in Dn - 143 to 155, Unit - 32,33 & 34, Zone - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/7584,Parks,Completed,NL-VALASARAVAKKAM,143,170000,"Annual Maintenance of Phase-I, 9th Main Road Park (One Year) in Dn-143, Unit-32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/7585,Parks,Completed,NL-VALASARAVAKKAM,143,342000,"Annual Maintenance of Phase-I, 3rd Main Road Park (One Year) in Dn-143, Unit-32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/7586,Parks,Completed,NL-VALASARAVAKKAM,143,380000,"Annual Maintenance of Phase-II, 7th Cross Street Park (One Year) in Dn-143, Unit-32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/7986,Roads,Completed,NL-VALASARAVAKKAM,143,978000,"Construction of Bin Platforms at various locations in Dn-143 to 148, U-32 & 33, Zone - 11",Own Sources,11,2017-18,2019-20 NL/2017-18/8076,Roads,Completed,NL-VALASARAVAKKAM,143,935700,"Supply of Conservancy Materials for daily use (for 6 months) in Dn - 143 to 155, U - 32, 33 & 34, Zone - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9206,Buildings,Completed,NL-VALASARAVAKKAM,143,429000,"Construction of Baby friendly Toilet at 4th block 4th street and Minor repair works at 4th block 4th & 8th street Anganwadi building in Dn-143, U-32, Zone-XI",Own Sources,11,2017-18,2019-20 NL/2017-18/9208,Buildings,Completed,NL-VALASARAVAKKAM,143,388000,"Construction of Baby friendly Toilet and Minor repair works at Perumal Koil Street Anganwadi building in Dn-143, U-32, Zone-XI",Own Sources,11,2017-18,2019-20 NL/2017-18/9209,Buildings,Completed,NL-VALASARAVAKKAM,143,388000,"Construction of Baby friendly Toilet and Minor repair works at Madha koil 2nd cross street Anganwadi building in Dn-143, U-32, Zone-XI",Own Sources,11,2017-18,2019-20 NL/2017-18/9752,Roads,Completed,NL-VALASARAVAKKAM,143,3044000,"Improvements to the interior CC Road in Nolambur Phase-I, 2nd Main Road in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9758,Roads,Completed,NL-VALASARAVAKKAM,143,3063000,"Improvements to the interior CC Road in Nolambur Phase-I, 3rd Main Road in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9759,Roads,Completed,NL-VALASARAVAKKAM,143,1076030,"Improvements to the interior CC Road in Nolambur Phase-I, 1st Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9760,Roads,Completed,NL-VALASARAVAKKAM,143,1823000,"Improvements to the interior CC Road in Nolambur Phase-I, 2nd Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9761,Roads,Completed,NL-VALASARAVAKKAM,143,652000,"Improvements to the interior CC Road in Nolambur Phase-I, 3rd Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9762,Roads,Completed,NL-VALASARAVAKKAM,143,530000,"Improvements to the interior CC Road in Nolambur Phase-I, 4th Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9763,Roads,Completed,NL-VALASARAVAKKAM,143,497000,"Improvement to the Interior CC Road in Nolambur Phase-I, 5th Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9764,Roads,Completed,NL-VALASARAVAKKAM,143,1274000,"Improvement to the Interior CC Road in Nolambur Phase-I, 6th Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9765,Roads,Completed,NL-VALASARAVAKKAM,143,486000,"Improvement to the Interior CC Road in Nolambur Phase-I, 12th Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9766,Roads,Completed,NL-VALASARAVAKKAM,143,1019000,"Improvement to the Interior CC Road in Nolambur Phase-I, 10th Main Road in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9767,Roads,Completed,NL-VALASARAVAKKAM,143,403000,"Improvement to the Interior CC Road in Nolambur Phase-I, 16th Cross Street in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9768,Roads,Completed,NL-VALASARAVAKKAM,143,1028000,"Improvement to the Interior CC Road in Nolambur Phase-I, 7th Main Road in Dn-143, Unit -32 , Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9781,Parks,Completed,NL-VALASARAVAKKAM,143,1200000,"Improvements work at Phase-I 9th main road park (old & new), Channel road park, Phase-I 3rd main road park,Phase-I 6th main road park,Phase-Il 7th cross street park and Phase-I 13th cross street park in Division -143, Unit -32, Zone-11",Own Sources,11,2017-18,2019-20 NL/2017-18/9890,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,526100,"Storm Water Drain and Side Drain Minor Repair work at Various Streets in Dn - 143, U - 32, Z - XI.",Own Sources,11,2017-18,2017-18 P/2017-18/13051,Parks,Completed,P-Parks and Playfields,143,6845388,"FORMATION OF NEW PARK AT MCK LAYOUT ROAD, NOLAMBUR VILLAGE IN DN-143, ZONE - XI.",Grants,11,2017-18,2018-19 NL/2017-18/12158,Buildings,Completed,NL-VALASARAVAKKAM,144,193000,"Improvements work at Pillaiyar Koil Street Anganwadi in Dn-144, Unit-32, Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/12183,Roads,Completed,NL-VALASARAVAKKAM,144,238000,"Forming the CC road at Kannan nagar annex 1st cross street in DN-144, Unit-32, Zone-11",Own Sources,11,2017-18,2019-20 NL/2017-18/12185,Roads,Completed,NL-VALASARAVAKKAM,144,339000,"Forming the CC road at Kannan nagar annex 3rd cross street in DN-144, Unit-32, Zone-11",Own Sources,11,2017-18,2019-20 NL/2017-18/12186,Roads,Completed,NL-VALASARAVAKKAM,144,832000,"Forming the CC road at Bharathiyar Cross Street in DN-144, Unit-32, Zone-11",Own Sources,11,2017-18,2019-20 NL/2017-18/12773,Parks,Completed,NL-VALASARAVAKKAM,144,311000,"Minor repair works and painting work to the Children play space at MMDA Colony 6th Block , 7th block and VGP Amutha nagar park in DN-144, Unit-32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/1967,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,453500,"DESILTING OF STORM WATER DRAINS AND SIDE DRAINS AT VARIOUS STREETS IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2017-18,2017-18 NL/2017-18/2279,Buildings,Completed,NL-VALASARAVAKKAM,144,2724000,"IMPROVEMENTS TO THE MADURAVOYAL URBAN PRIMARY HEALTH CENTRE AT POONAMALLEE HIGH ROAD IN DIV-144, U-32, Z-11",Own Sources,11,2017-18,2018-19 NL/2017-18/2280,Roads,Completed,NL-VALASARAVAKKAM,144,469000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT VGP AMUDHA NAGAR 3rd CROSS STREET IN DIV -144, U-32, Z-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/2281,Buildings,Completed,NL-VALASARAVAKKAM,144,703000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT MMDA COLONY 4TH BLOCK MAIN ROAD IN DIV-144, U-32, Z-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/2365,Roads,Completed,NL-VALASARAVAKKAM,144,812000,"PROVIDING SPEED BREAKERS AS PER IRC STANDARD (16 NOS) AT VARIOUS STREETS IN DIV - 144, UNIT - 32, ZONE- XI",Own Sources,11,2017-18,2018-19 NL/2017-18/3001,Buildings,Completed,NL-VALASARAVAKKAM,144,218000,"REPAIRS AND IMPROVEMENTS TO THE AMMA UNVAGAM IN METTUKUPPAM MAIN ROAD & NAGATHAMMAN KOIL STREET IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/3004,Roads,Completed,NL-VALASARAVAKKAM,144,161000,"Supplying and Laying of Thermoplast for 8 Nos of Speed Breakers at various Streets in Dn - 144, U - 32, Z - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/5015,Road Cut,Completed,NL-VALASARAVAKKAM,144,1604000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT MMDA COLONY I st MAIN ROAD IN DIV-144,UNIT-32,ZONEX1",Loans And Grants,11,2017-18,2018-19 NL/2017-18/8069,Buildings,Completed,NL-VALASARAVAKKAM,144,216000,"PROVIDING BOREWELL, SEPTIC TANK FACILITIES & WATER SUPPLY FACILITIES TO THE PUBLIC CONVENIENCE IN PILLAIYAR KOIL STREET & NAGATHAMMAN KOIL STREET IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9017,Buildings,Completed,NL-VALASARAVAKKAM,144,324000,"CONSTRUCTION OF BABY FRIENDLY TOILET AT PILLAIYAR KOIL STREET ANGANWADI IN DIV-144, UNIT-32, ZONE-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9893,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,502800,"Minor Repair Works to Existing Side Drain in Bharathiyar Street, Abirami Nagar 11th Street & Sathyamoorthy Nagar main Road in Div 144, Unit 32,Zone XI",Own Sources,11,2017-18,2017-18 B/2017-18/3665,Buildings,Completed,B-Buildings,145,11317135,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTRE AT PERUMAL KOIL STREET IN DIV-145, ZONE-11",Grants,11,2017-18,2020-21 L/2017-18/12350,Electrical,Completed,L-Electrical,145,10759000,"Provision of 261nos of 6mtr GI lamp post with single straight bracket Hot Dip Zinc Galvanised with 40 -50w LED fittings, at Krishna nagar main road & Various Location in Dn.145 in Zone-XI.","Loans, Grants And Own Sources",11,2017-18,2019-20 NL/2017-18/12795,Roads,Completed,NL-VALASARAVAKKAM,145,1037000,"Roadcut Restoration for Madha Koil Street in Dn - 145, U - 33, Z - XI.",Deposit Works,11,2017-18,2019-20 NL/2017-18/14150,Buildings,Completed,NL-VALASARAVAKKAM,145,230000,"Erection of Notice Board at vacant lands (142 nos.) to avoid dumping of garbage at vacant lands in Dn-145, 148, 149 &152, Unit - 33, Zone - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/14155,Roads,Completed,NL-VALASARAVAKKAM,145,516000,"Relaying BT patch work at Madha Koil Street in Dn - 145, U - 33, Z - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/14156,Roads,Completed,NL-VALASARAVAKKAM,145,1199000,"Laying CC Road at Sakthi Nagar 'C' Block 25th Street in Dn - 145, U - 33, Z - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/1971,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,166100,"Desilting of Storm Water Drain and Side drain at Various Streets in Dn-145, Unit-33, Zone-XI",Own Sources,11,2017-18,2017-18 NL/2017-18/3156,Buildings,Completed,NL-VALASARAVAKKAM,145,51000,"Maintenance of Amma Unavagam at Madha Koil Street in Dn - 145, U - 33, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/7952,Roads,Completed,NL-VALASARAVAKKAM,145,38000,"Providing and laying of hot applied thermoplastic at various street in Dn.145, Unit-33 Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/8217,Buildings,Completed,NL-VALASARAVAKKAM,145,135000,"Dismantling of NNMP Shed and UPHC building for proposed construction of UPHC in Dn - 145, U - 34, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/8959,Buildings,Completed,NL-VALASARAVAKKAM,145,7200,"Minor improvements to existing Anganwadi building at Mandaveli 2nd Street in Dn - 145, U - 33, Z - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9072,Buildings,Completed,NL-VALASARAVAKKAM,145,7100,"Minor improvements to existing Anganwadi building at Palvadi 1st Street in Dn - 145, U - 33, Z - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9073,Buildings,Completed,NL-VALASARAVAKKAM,145,203000,"Major improvements work to existing Anganwadi at Janaki raman colony ( Sakthi Nagar) in Dn - 145, U - 33, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/9486,Buildings,Completed,NL-VALASARAVAKKAM,145,319000,"Construction of Baby Friendly Toilet to existing Anganwadi at Janaki raman colony ( Sakthi Nagar) in Dn - 145, U - 33, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/9488,Buildings,Completed,NL-VALASARAVAKKAM,145,319000,"Construction of Baby Friendly Toilet to existing Anganwadi at Mandaveli 2nd Street in Dn - 145, U - 33, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/9489,Buildings,Completed,NL-VALASARAVAKKAM,145,319000,"Construction of Baby Friendly Toilet to existing Anganwadi at Palvadi 1st Street in Dn - 145, U - 33, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/9492,Buildings,Completed,NL-VALASARAVAKKAM,145,319000,"Construction of Baby Friendly Toilet to existing Anganwadi at Perumal Koil Street in Dn - 145, U - 33, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/12678,Parks,Completed,NL-VALASARAVAKKAM,146,160000,"Annual Maintenance of Metro Nagar Park (One Year) in Dn-146, Unit-32, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/9054,Buildings,Completed,NL-VALASARAVAKKAM,146,252000,"Construction of Baby Friendly Toilet at Dhanalakshmi nagar 7th street in Dn-146, Unit-32, Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9091,Buildings,Completed,NL-VALASARAVAKKAM,146,160000,"Major Repair work to Anganwadi at Dhanalakshmi Nagar 7th Street in Dn.146, Unit-32, Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9896,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,516500,"Desilting of SWD and side drain at Various Streets in Dn 146, Unit 32, Zone 11",Own Sources,11,2017-18,2017-18 NL/2017-18/9897,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,422800,"Improvement Minor repair to side drain at Kambar Nagar 1st, 2nd and 3rd Streets in Dn.146, U-32, Zone-XI",Own Sources,11,2017-18,2017-18 L/2017-18/10203,Electrical,Completed,L-Electrical,147,31355000,"Provision of 310Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 148 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Krishna Nagar various Places ,Bharathi Nagar Ohm Sakthi Nagar and Chakrabani Nagar in Division 147 Zone XI","Loans, Grants And Own Sources",11,2017-18,2019-20 NL/2017-18/0823,Buildings,Completed,NL-VALASARAVAKKAM,147,479000,"Construction of Anganwadi Toilet and water arrangements at Ganga Nagar in Dn-147, Unit-32, Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/11768,Parks,Completed,NL-VALASARAVAKKAM,147,640000,"IMPROVEMENT TO FOOTPATH AND COMPOUND WALL, ELECTRICAL WORKS AND GREENERY WORKS AT BHARATHI NAGAR PARK IN DN -147, UNIT -32, ZONE -11.",Own Sources,11,2017-18,2018-19 NL/2017-18/11795,Footpath,Completed,NL-VALASARAVAKKAM,147,598000,"IMPROVEMENTS TO FOOTPATH, COMPOUND WALL AND PLAY FIELD AT THANDAI PERIYAR THIDAL PARK, ALAPAKKAM MAIN ROAD IN DN -147, UNIT -32, ZONE -11.",Own Sources,11,2017-18,2018-19 NL/2017-18/12519,Parks,Completed,NL-VALASARAVAKKAM,147,468000,"Annual Maintenance of Bharathi Nagar Park, Pallavan Nagar Park and Arignar Anna Park (one year) in Dn- 147, Unit-32, Zone-11.",Own Sources,11,2017-18,2018-19 NL/2017-18/15012,Buildings,Completed,NL-VALASARAVAKKAM,147,1150000,"Construction of Bath Room, Toilet and Electrical fitting works at Burial Ground Alapakkam Main Road in Dn.147, U-32, Z-11",Own Sources,11,2017-18,2018-19 NL/2017-18/16073,Buildings,Completed,NL-VALASARAVAKKAM,147,284000,"Providing fencing at vacant land near ARS garden, Arcot road in Dn - 147, U - 32, Z - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/2326,Buildings,Completed,NL-VALASARAVAKKAM,147,231000,"Dismantling of Old Over head water tank at Ganga nagar middle school in division - 147, Unit - 32 in Zone - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/2519,Buildings,Completed,NL-VALASARAVAKKAM,147,1466000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT PALLAVAN NAGAR EAST MAIN ROAD IN DN-147, UNIT-32, ZONE-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/2825,Buildings,Completed,NL-VALASARAVAKKAM,147,130000,"Improvement to Amma Unavagam at Ganga Nagar in Dn - 147, Unit - 32, Zone - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/3807,Roads,Completed,NL-VALASARAVAKKAM,147,44000,"Supplying and laying of thermoplastic for 2 nos of speed breakers (Existing and New IRC Standard) at various in Dn - 147, U -32, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/4900,Roads,Completed,NL-VALASARAVAKKAM,147,790000,"Improvement to the interior BT road at Ganga Nagar East main road in Div-147, Unit-32, Zone-11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/7082,Buildings,Completed,NL-VALASARAVAKKAM,147,1741000,"Improvement to the interior BT road at Thideer Nagar DIV-147, UNIT-32, ZONE-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/8065,Buildings,Completed,NL-VALASARAVAKKAM,147,599000,"Forming open GYM in Periyar park at alapakkam main road in Dn-147,Unit-32,Zone-11.",Own Sources,11,2017-18,2018-19 NL/2017-18/8181,Buildings,Completed,NL-VALASARAVAKKAM,147,2653000,"Improvement to the interior BT road at Sri Krishna nagar 3rd main road (from car shed & Rajiv Gandhi salai to Seemathamman koil ) in Div-147 U-32, Z-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/8183,Buildings,Completed,NL-VALASARAVAKKAM,147,1556000,"Improvement to the interior BT road at Krishna nagar 3rd main road (pillaiyar koil road) in Div-147 U-32, Z-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/9401,Buildings,Completed,NL-VALASARAVAKKAM,147,37000,Minor repair work to anganvadi at seemathamman nagar main road in Dn-147 U-32 Z-11,Own Sources,11,2017-18,2018-19 NL/2017-18/9704,Buildings,Completed,NL-VALASARAVAKKAM,147,602000,"SUPPLYING AND FIXING MODERN GYM EQUIPMENTS AND ELECTRIFICATION, WIRING WORKS INSIDE GYM ROOM AND AROUND THE FOOTPATH AT THANTHAI PERIYAR THIEDAL ALAPAKKAM MAIN ROAD IN DN-147, UNIT-32, ZONE-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/9798,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,356000,"Desilting of SWD and Side drain at various streets in Dn-147, Unit-32, Zone-XI",Own Sources,11,2017-18,2017-18 NL/2017-18/9799,Buildings,Completed,NL-VALASARAVAKKAM,147,498000,IMPROVEMENT TO THE INTERIOR BT ROAD PALLAVAN NAGAR PTC OFFICER COLONY (FROM PALLAVAN PARK TO PUMPING STATION) IN DN :147 UNIT:32 ZONE:11,Loans And Grants,11,2017-18,2018-19 NL/2017-18/9891,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,48300,"Improvement Minor repair to Side Drain at Gandhi Street, Pillaiyar Koil Stret and Egambaram Estate in Dn - 147, U - 32, Z - XI.",Own Sources,11,2017-18,2017-18 L/2017-18/12373,Electrical,Completed,L-Electrical,148,11733500,"Provision of 188 nos of 6mtr GI lamp post with single straight bracket Hot Dip Zinc Galvanised with 40 -50w LED fittings, 40 nos of 6mtr GI lamp post with single Arch bracket Hot Dip Zinc Galvanised with 90 -120w LED fittings at Meenakshi amman nagar & Various Location in Dn.148 ,Kuapettai & various location in Div 151 in Zone-XI.","Loans, Grants And Own Sources",11,2017-18,2018-19 L/2017-18/15634,Electrical,Completed,P-Parks and Playfields,148,2483000,"Supply & Commissioning for Lawn Pathway, Open Gym Pathway of 20 Nos of 3 Mtr Decorative garden post with double arch bracket ,11 Nos of 3 Mtr Decorative garden post with single arch bracket & 51 Nos of 18w Decorative LED Fitting for the Nerkundrum Park in Div 148, Nerkundrum , zone11",Own Sources,11,2017-18,2018-19 L/2017-18/15636,Electrical,Completed,P-Parks and Playfields,148,2478000,"Supply & Commissioning for Tennis Court, Batmiton Court, Pathway of 4 Nos 8 Mtr Street lamp post with straight bracket hot Dip Galvansing with 12 nos of 240W to 300 W LED Flood Light for Tennis Court and 14 nos of 160 W to 200 W LED Flood Light Fitting for Badminton Court in Nerkundrum Park in Div 148, Nerkundrum in zone11",Own Sources,11,2017-18,2018-19 L/2017-18/16419,Electrical,Completed,P-Parks and Playfields,148,2423000,"Supply & Commissioning for Park Entrance and Pathway of 2 Nos of 3.5 Mtr Decorative garden post with double arch bracket with 4 Nos of 33w LED Fitting & 15 Nos of 3mtr Decorative garden post single Arch Bracket &15 Nos of 3mtr Decorative garden post Double Arch Bracket with 45 Numbers of 18w Decorative LED fitting for the Nerkundrum Park in Div 148,Nerkundrum , zone11",Own Sources,11,2017-18,2018-19 L/2017-18/16420,Electrical,Completed,P-Parks and Playfields,148,2360000,"Supply & Commissioning for Gaseba Pebble Pathway ,Tennis court Pathway of 38 Nos 1.2 Mtr Decorative garden post for Gaseba with 38 nos 18 W Decorative LED fitting and 10 Nos of 3mtr Decorative garden post single Arch Bracket & 8 Nos of 3mtr Decorative garden post Double Arch Bracket with 26 Numbers of 18w Decorative LED fitting at Nerkundrum Park in Nerkundrum , Div 148 in zone11",Own Sources,11,2017-18,2018-19 L/2017-18/16421,Electrical,Completed,P-Parks and Playfields,148,2232000,"Supply & Laying of 1400 mtrs of 2X16 sqmm Alu cable,420 Mtrs of 4X16 sqmm Alu cable, 300Mtrs of 2X 10 Sqmm Alu cable & 450 Mtrs of 3 1/2 25 Sqmm Aluminium cable for the graden Lamp post at the Nerkundrum Park in Div 148,Nerkundrum , zone11 .",Own Sources,11,2017-18,2018-19 NL/2017-18/15770,Roads,Completed,NL-VALASARAVAKKAM,148,1932000,Improvement to Interior B.T. Road at Jayaram Nagar 2nd Main Road in DN 148 U-33 ZONE-XI,Loans And Grants,11,2017-18,2018-19 NL/2017-18/15771,Roads,Completed,NL-VALASARAVAKKAM,148,1478000,"Improvement to Interior B.T. Road at Saraswathi Nagar Main Road in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15772,Roads,Completed,NL-VALASARAVAKKAM,148,3491000,"Improvement to Interior B.T. Road at Anbu Nagar Main Road in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15773,Roads,Completed,NL-VALASARAVAKKAM,148,844000,"Improvement to Interior B.T. Road at Anbu Nagar 5th Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15774,Roads,Completed,NL-VALASARAVAKKAM,148,1192000,"Improvement to Interior B.T. Road at Anbu Nagar 9th Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15775,Roads,Completed,NL-VALASARAVAKKAM,148,1300000,"Improvement to Interior B.T. Road at Balaji Nagar 1st Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15776,Roads,Completed,NL-VALASARAVAKKAM,148,273000,"Improvement to Interior B.T. Road at Balaji Nagar 8th Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15777,Roads,Completed,NL-VALASARAVAKKAM,148,1023000,"Improvement to Interior B.T. Road at Jayaram Nagar 3rd Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15778,Roads,Completed,NL-VALASARAVAKKAM,148,821000,"Improvement to Interior B.T. Road at Balavinayagar Nagar Main Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15779,Roads,Completed,NL-VALASARAVAKKAM,148,1181000,"Improvement to Interior B.T. Road at Balavinayagar Nagar Jeeva Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15780,Roads,Completed,NL-VALASARAVAKKAM,148,736000,"Improvement to Interior B.T. Road at Mettukuppam School Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15781,Roads,Completed,NL-VALASARAVAKKAM,148,490000,"Improvement to Interior B.T. Road at Anbu Nagar 2nd Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15782,Roads,Completed,NL-VALASARAVAKKAM,148,865000,"Improvement to Interior B.T. Road at Anbu Nagar 3rd Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15783,Roads,Completed,NL-VALASARAVAKKAM,148,351000,"Improvement to Interior B.T. Road at Anbu Nagar 4th Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15784,Roads,Completed,NL-VALASARAVAKKAM,148,568000,"Improvement to Interior B.T. Road at Anbu Nagar 11th Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15785,Roads,Completed,NL-VALASARAVAKKAM,148,875000,"Improvement to the interior B.T. road at Kamarajar High Road in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15786,Roads,Completed,NL-VALASARAVAKKAM,148,1152000,"Improvement to Interior B.T. Road at Balaji Nagar 2nd Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15787,Roads,Completed,NL-VALASARAVAKKAM,148,642000,"Improvement to Interior B.T. Road at Bhuvaneshwari Nagar 3rd Cross Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15788,Roads,Completed,NL-VALASARAVAKKAM,148,1733000,"Improvement to Interior B.T. Road at Bhuvaneshwari Nagar Amman Koil Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15789,Roads,Completed,NL-VALASARAVAKKAM,148,258000,"Improvement to the interior B.T. Road at Vadavenniyamman 2nd Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15790,Roads,Completed,NL-VALASARAVAKKAM,148,267000,"Improvement to the interior B.T. Road at Annai Sathiya Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15792,Roads,Completed,NL-VALASARAVAKKAM,148,236000,"Improvement to the interior B.T. Road at Kadambadi Nagar Iyyappan Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15793,Roads,Completed,NL-VALASARAVAKKAM,148,1281000,"Improvement to Interior B.T. Road at Lakshmi Nagar 1st Main Road in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15794,Roads,Completed,NL-VALASARAVAKKAM,148,266000,"Improvement to the interior B.T. Road at Goverdhan Nagar 8th Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15797,Roads,Completed,NL-VALASARAVAKKAM,148,483000,"Improvement to Interior B.T. Road at Meenatchi Amman Nagar Anna Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15798,Roads,Completed,NL-VALASARAVAKKAM,148,293000,"Improvement to the interior B.T. Road at Balaji Nagar 3rd Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15799,Roads,Completed,NL-VALASARAVAKKAM,148,893000,"Improvement to Interior B.T. Road at Meenatchi Amman Nagar Pillayar Koil Street in Dn.148, Unit-33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15800,Roads,Completed,NL-VALASARAVAKKAM,148,333000,"Improvement to the interior B.T. Road at Bhuveneshwari Nagar Periyar Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15801,Roads,Completed,NL-VALASARAVAKKAM,148,362000,"Improvement to the interior B.T. Road at Meenakchiamman Nagar Pilliyar Koil Cross Street in Dn 148, Unit 33, Zone XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15802,Roads,Completed,NL-VALASARAVAKKAM,148,258000,"Improvement to the interior B.T. Road at Bhuveneshwari Nagar Lakshanan Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15803,Roads,Completed,NL-VALASARAVAKKAM,148,329000,"Improvement to the interior B.T. Road at Dhanlakshmi Nagar Ganapathy Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15804,Roads,Completed,NL-VALASARAVAKKAM,148,293000,"Improvement to the interior B.T. Road at Saraswathi Nagar 5th Street in Dn 148 Unit 33, Zone XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15805,Roads,Completed,NL-VALASARAVAKKAM,148,385000,"Improvement to the interior B.T. Road at Dhanlakshmi Nagar Chokkalinga naicker Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15806,Roads,Completed,NL-VALASARAVAKKAM,148,341000,"Improvement to the interior B.T. Road at Lakshmi Nagar 2nd Main Road (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15807,Roads,Completed,NL-VALASARAVAKKAM,148,341000,"Improvement to the interior B.T. Road at Lakshmi Nagar 3rd Main Road (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15808,Roads,Completed,NL-VALASARAVAKKAM,148,323000,Improvement to Interior B.T. Road at Lakshmi 4th Street (part) in Dn 148 Unit-33 Zone XI,Loans And Grants,11,2017-18,2018-19 NL/2017-18/15809,Roads,Completed,NL-VALASARAVAKKAM,148,121000,"Improvement to the interior B.T. Road at Saraswathi Nagar 1st Cross Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15810,Roads,Completed,NL-VALASARAVAKKAM,148,355000,Improvement to Interior B.T. Road at Sriram Nagar (Kaviarasu kannadhasan Street (Part) in Dn 148 Unit-33 Zone -XI,Loans And Grants,11,2017-18,2018-19 NL/2017-18/15811,Roads,Completed,NL-VALASARAVAKKAM,148,58000,"Improvement to the interior B.T. Road at Lakshmi Nagar 1st Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/15813,Roads,Completed,NL-VALASARAVAKKAM,148,403000,"Improvement to the interior B.T. Road at Lakshmi Nagar 2nd Street (part) in Dn 148, Unit 33, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/16388,Parks,Completed,NL-VALASARAVAKKAM,148,165000,SUPPLY AND FIXING OF SFRC FRAME WITH JOLLY OF SIZE 930MM X930MMX65MM WITH 100MM THICK FRAME AI AIS HOUSING COMPLEX IN DN 148 UNIT 33 ZONE 11,Own Sources,11,2017-18,2019-20 NL/2017-18/17181,Roads,Completed,NL-VALASARAVAKKAM,148,96000,"REPAIRS TO EXISTING STREET NAME BOARDS AT VARIOUS STREETS in Dn - 148, U - 33, Z - XI.",Own Sources,11,2017-18,2019-20 NL/2017-18/9226,Buildings,Completed,NL-VALASARAVAKKAM,148,193000,Improvements to Amma Unavagam at Balavinayagar Nagar Kamarajar Salai Dn-148 Unit-33 Zone XI,Own Sources,11,2017-18,2018-19 NL/2017-18/9894,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,250000,Minor repairs to side drain at Avvai street and Gandhi street in Dn-148 U-33 Z-11,Own Sources,11,2017-18,2017-18 NL/2017-18/9895,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,244300,Desilting of SWD and Side Drain at various street in Dn-148 U-33 Z-11,Own Sources,11,2017-18,2017-18 BR/2017-18/11550,Roads,Completed,BR-Bus Route Roads,149,3000000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Sri Devi Kuppam Main Road (Patch) in Dn-149, Zone-XI",Grants,11,2017-18,2018-19 L/2017-18/10201,Electrical,Completed,L-Electrical,149,13622000,"Provision of 193 Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 95 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Thirumalai Nagar , Sastha Nagar & SBI Colony, BVR Nagar and AGS Colony ,Ramakrishna Nagar & , Nehru Street and Various Places in Division 149 Zone XI","Loans, Grants And Own Sources",11,2017-18,2018-19 NL/2017-18/10911,Roads,Completed,NL-VALASARAVAKKAM,149,1651000,"Forming Road in the Road Widening portion of Sri Devi kuppam Main Road (Encroachment Removal Portion ) in Div-149,U-33,Z-11.",Own Sources,11,2017-18,2017-18 NL/2017-18/12173,Roads,Completed,NL-VALASARAVAKKAM,149,427000,"Improvements to interior BT Road at Sastha Nagar 1st Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12174,Roads,Completed,NL-VALASARAVAKKAM,149,295000,"Improvements to interior BT Road at Sastha Nagar 2nd Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12202,Roads,Completed,NL-VALASARAVAKKAM,149,75000,"Improvements to interior BT Road at A.T.Annex 3rd Street (Part) in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12203,Roads,Completed,NL-VALASARAVAKKAM,149,100000,"Improvements to interior BT Road at A.T.Annex 2nd Street (Part) in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12204,Roads,Completed,NL-VALASARAVAKKAM,149,310000,"Improvements to interior BT Road at A.T.Annex Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12205,Roads,Completed,NL-VALASARAVAKKAM,149,466000,"Improvements to interior BT Road at A.T.Annex Ramanujam Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12207,Roads,Completed,NL-VALASARAVAKKAM,149,450000,"Improvements to interior BT Road at V.V. Giri Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12208,Roads,Completed,NL-VALASARAVAKKAM,149,289000,"Improvements to interior BT Road at Play Ground Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12209,Roads,Completed,NL-VALASARAVAKKAM,149,450000,"Improvements to interior BT Road at Bharathiyar Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12210,Roads,Completed,NL-VALASARAVAKKAM,149,579000,"Improvements to interior BT Road at Kambar Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12211,Roads,Completed,NL-VALASARAVAKKAM,149,694000,"Improvements to interior BT Road at A.G.S Colony Main Road in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12888,Playfields,Completed,NL-VALASARAVAKKAM,149,104000,"Improvements to Ramakrishna nagar playground in division - 149, unit - 33 in Zone - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/13188,Parks,Completed,NL-VALASARAVAKKAM,149,186000,"Annual Maintenance of corporation park for 1 years at Fathima Nagar(CEEBROS PARK)In Div-149,U-33,Z-11",Own Sources,11,2017-18,2018-19 NL/2017-18/13189,Parks,Completed,NL-VALASARAVAKKAM,149,161000,"Annual Maintenance of corporation park for 1 years at Arcot Road(Alsa Park)In Div-149,U-33,Z-11",Own Sources,11,2017-18,2018-19 NL/2017-18/13246,Parks,Completed,NL-VALASARAVAKKAM,149,600000,"Providing open GYM Equipments including platform at Palaniyappa Nagar Children Play Ground in Dn - 149, Unit - 33, Zone - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/13843,Footpath,Completed,NL-VALASARAVAKKAM,149,341000,"Construction foot path and improvements at Palaniyappa Nagar children play ground at Division-149,Unit-33,Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/14385,Parks,Completed,NL-VALASARAVAKKAM,149,397000,"Improvements to Brindhavan Nagar Varadha Park(Care Taker Room & Toilet) at Division-149,Unit-33,Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/15524,Roads,Completed,NL-VALASARAVAKKAM,149,1686000,"Road Cut Restoration work at Sannathi St, Sridevi Kuppam Main Road, Murali Krishna nagar main road, SBS Colony, IN DN-149, UNIT-33 ,ZONE-11.",Own Sources,11,2017-18,2019-20 NL/2017-18/15550,Road Cut,Completed,NL-VALASARAVAKKAM,149,1887000,"Road Cut Restoration work at Kamatchi Nagar Main Road, Kangathara Nagar Main Road, Ramakrishna Nagar Extension, Vanjinathan Street, Vysar Street, Indra Street , and Rajaji Street IN DN-149, UNIT-33 ,ZONE-11.",Own Sources,11,2017-18,2019-20 NL/2017-18/2353,Roads,Completed,NL-VALASARAVAKKAM,149,600000,"Providing Speed breaker as per (IRC) Standard 30 nos at various Streets in Dn - 149, U - 33, Z - XI",Own Sources,11,2017-18,2017-18 NL/2017-18/2672,Roads,Completed,NL-VALASARAVAKKAM,149,65000,"Supplying and laying of thermoplastic for speed breakers (IRC Standard) in Dn - 149, U -33, Z - XI.",Own Sources,11,2017-18,2017-18 NL/2017-18/2954,Buildings,Completed,NL-VALASARAVAKKAM,149,104000,"Maintenance to Amma Unavagam at Nakeeran Street in Div-149,U-33,Z-11",Own Sources,11,2017-18,2018-19 NL/2017-18/3825,Electrical,Completed,NL-VALASARAVAKKAM,149,522000,Provision of 13 Nos of 6 mtr Lamp Post with 13 Nos 40w LED Fitting at Brindhavanam Nagar Park in Division 149 Zone XI,Own Sources,11,2017-18,2017-18 NL/2017-18/7998,Roads,Completed,NL-VALASARAVAKKAM,149,495000,"Construction of Bin Platforms at various locations in Unit - 33 & 34, Zone - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/8152,Parks,Completed,NL-VALASARAVAKKAM,149,174000,"ANNUAL MAINTENANCE TO CORPORATION PARK AT Gandhi Road (Thiru-vi-ka Park) IN DN-149,UNIT-33,ZONE-11(one year).",Own Sources,11,2017-18,2018-19 NL/2017-18/8153,Parks,Completed,NL-VALASARAVAKKAM,149,205000,"ANNUAL MAINTENANCE TO CORPORATION PARK AT Dr.Radhakrishnan Salai (Thanthai Periyar park) IN DN-149,UNIT-33,ZONE-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/8154,Parks,Completed,NL-VALASARAVAKKAM,149,181000,"ANNUAL MAINTENANCE TO CORPORATION PARK AT Brindavan Nagar (Brindavan park& varadha park) IN DN-149,UNIT-33,ZONE-XI ( one year)",Own Sources,11,2017-18,2018-19 BR/2017-18/11554,Roads,Completed,BR-Bus Route Roads,150,6200000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Chettiyar Agaram Main Road (Patch) in Dn-150, Zone-XI",Grants,11,2017-18,2018-19 L/2017-18/12353,Electrical,Completed,L-Electrical,150,24852500,"Provision of 510 nos of 6mtr GI lamp post with single straight bracket Hot Dip Zinc Galvanised with 40 -50w LED fittings, 50 nos of 6mtr GI lamp post with single Arch bracket Hot Dip Zinc Galvanised with 90 -120w LED fittings at Ponni Nagar & Various Location in Dn.150 in Zone-XI.","Loans, Grants And Own Sources",11,2017-18,2019-20 NL/2017-18/12245,Roads,Completed,NL-VALASARAVAKKAM,150,928000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PONNI NAGAR C.V.K STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12246,Roads,Completed,NL-VALASARAVAKKAM,150,893000,"IMPROVEMENTS TO INTERIOR BT ROAD AT MOTHI NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12247,Roads,Completed,NL-VALASARAVAKKAM,150,354000,"IMPROVEMENTS TO INTERIOR BT ROAD AT ELUPEDARI AMMAN KOIL STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12248,Roads,Completed,NL-VALASARAVAKKAM,150,223000,"IMPROVEMENTS TO INTERIOR BT ROAD AT DOSS NAGAR 3RD STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12249,Roads,Completed,NL-VALASARAVAKKAM,150,333000,"IMPROVEMENTS TO INTERIOR BT ROAD AT BUDDHAR COLONY 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12250,Roads,Completed,NL-VALASARAVAKKAM,150,224000,"IMPROVEMENTS TO INTERIOR BT ROAD AT DOSS NAGAR 4TH STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12251,Roads,Completed,NL-VALASARAVAKKAM,150,790000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KAMARAJAR STREET (THUNDALAM ANNA NAGAR) IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12252,Roads,Completed,NL-VALASARAVAKKAM,150,224000,"IMPROVEMENTS TO INTERIOR BT ROAD AT MAHALAKSHMI NAGAR 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12253,Roads,Completed,NL-VALASARAVAKKAM,150,201000,"IMPROVEMENTS TO INTERIOR BT ROAD AT RAJIVGANDHI STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12254,Roads,Completed,NL-VALASARAVAKKAM,150,176000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PARASNATH NAGAR IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12255,Roads,Completed,NL-VALASARAVAKKAM,150,180000,"IMPROVEMENTS TO INTERIOR BT ROAD AT V.O.C STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12256,Roads,Completed,NL-VALASARAVAKKAM,150,194000,"IMPROVEMENTS TO INTERIOR BT ROAD AT SAMAYAPURAM 1ST STREET (PART) IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12257,Roads,Completed,NL-VALASARAVAKKAM,150,300000,"IMPROVEMENTS TO INTERIOR BT ROAD AT ADHIYAMAN STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12258,Roads,Completed,NL-VALASARAVAKKAM,150,292000,"IMPROVEMENTS TO INTERIOR BT ROAD AT TEACHER'S COLONY M.T.C 3RD STREET (PART) IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12259,Roads,Completed,NL-VALASARAVAKKAM,150,558000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KARUUYA NAGAR LUKE STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12260,Roads,Completed,NL-VALASARAVAKKAM,150,968000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KARUUYA NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12261,Roads,Completed,NL-VALASARAVAKKAM,150,1736000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12262,Roads,Completed,NL-VALASARAVAKKAM,150,766000,"IMPROVEMENTS TO INTERIOR BT ROAD AT SAMAYAPURAM 5TH STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12263,Roads,Completed,NL-VALASARAVAKKAM,150,567000,"IMPROVEMENTS TO INTERIOR BT ROAD AT ERIKARAI ROAD EXTN IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12264,Roads,Completed,NL-VALASARAVAKKAM,150,414000,"IMPROVEMENTS TO INTERIOR BT ROAD AT ALPHA COLLEGE CROSS STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12265,Roads,Completed,NL-VALASARAVAKKAM,150,1596000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KARAMBAKKAM 1ST MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12266,Roads,Completed,NL-VALASARAVAKKAM,150,366000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR 3RD CROSS STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12267,Roads,Completed,NL-VALASARAVAKKAM,150,343000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR 3RD STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12268,Roads,Completed,NL-VALASARAVAKKAM,150,328000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR 2ND STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12269,Roads,Completed,NL-VALASARAVAKKAM,150,266000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PADMAVATHY NAGAR 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12270,Roads,Completed,NL-VALASARAVAKKAM,150,1124000,"IMPROVEMENTS TO INTERIOR BT ROAD AT SAMAYAPURAM 4TH STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12273,Roads,Completed,NL-VALASARAVAKKAM,150,2785000,"IMPROVEMENTS TO INTERIOR BT ROAD AT SAMAYAPURAM MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12607,Parks,Completed,NL-VALASARAVAKKAM,150,781000,"ANNUAL MAINTENANCE OF PARK AT PONNI AMMAN KOIL STREET, MARUTHI NAGAR PHASE - 1&2 AND MARUTHI NAGAR PHASE - 3 FOR ONE YEAR (TOTAL PARK - 3 NOS) IN DN.150, U 34, Z 11.",Own Sources,11,2017-18,2018-19 NL/2017-18/12752,Buildings,Completed,NL-VALASARAVAKKAM,150,1480000,"IMPROVEMENT TO COMMUNITY HALL AT PONNI NAGAR MULLAI STREET KARAMBAKKAM IN DIV - 150, U -34, Z-11",Own Sources,11,2017-18,2018-19 NL/2017-18/14153,Buildings,Completed,NL-VALASARAVAKKAM,150,168000,"Erection of Notice Board at vacant lands (104 nos.) to avoid dumping of garbage at vacant lands in Dn-150, 151, 153, 154 & 155, Unit - 34, Zone - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/14591,Buildings,Completed,NL-VALASARAVAKKAM,150,238300,"Attending Patches, Improvements to Buildings, SWD, Parks, and Amma Unavagam in Dn - 150, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 NL/2017-18/16422,Parks,Completed,NL-VALASARAVAKKAM,150,1487000,"CONSTRUCTION OF COMPOUND WALL AT MAHARISHI TEACHER'S COLONY OSR LAND S. No. 66/ 1A1B (L - 145 M) IN DIV - 150, U - 34, ZONE - 11",Own Sources,11,2017-18,2019-20 NL/2017-18/16424,Parks,Completed,NL-VALASARAVAKKAM,150,820000,"CONSTRUCTION OF COMPOUND WALL AT SUBHAGIRI NAGAR OSR LAND (L - 85 M) IN DIV - 150, U -34, ZONE - 11",Own Sources,11,2017-18,2019-20 NL/2017-18/2096,Roads,Completed,NL-VALASARAVAKKAM,150,333000,PROVIDING SPEED BREAKERS AT VARIOUS STREETS AND VARIOUS LOCATION IN DN-150 UNIT-34 ZONE-11.,Own Sources,11,2017-18,2017-18 NL/2017-18/2689,Buildings,Completed,NL-VALASARAVAKKAM,150,265000,"REPAIR AND MAINTAINANCE WORK AT PONNI NAGAR MULLAI STREET AMMA UNAVAGAM IN DIV ? 150, U -34, Z - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/2690,Buildings,Completed,NL-VALASARAVAKKAM,150,210000,"REPAIR AND MAINTAINANCE WORK AT CHETTIYAR AGARAM MAIN ROAD AMMA UNAVAGAM IN DIV ? 150, U -34, Z - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/2746,Roads,Completed,NL-VALASARAVAKKAM,150,44000,"Supplying and laying Thermoplastic for Speed breakers at Chettiyar Agaram Main Road in Dn-150 U-34, Z-11.",Own Sources,11,2017-18,2017-18 NL/2017-18/3965,Parks,Completed,NL-VALASARAVAKKAM,150,585000,"providing open gym Equipments including plat form at maruthi nagar park ( Phase1&2 ) in dn-150,unit-34 and zone-11",Own Sources,11,2017-18,2017-18 NL/2017-18/9022,Buildings,Completed,NL-VALASARAVAKKAM,150,96000,"REPAIR WORK AT CHETTIYAR AGARAM AGANVADI AT SCHOOL STREET IN DIV - 150, U - 34, ZONE - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/9026,Buildings,Completed,NL-VALASARAVAKKAM,150,181000,"REPAIR WORK AT SIVABOOTHAM PERUMAL KOIL STREET AGANVADI IN DIV - 150, U - 34, ZONE - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/9031,Buildings,Completed,NL-VALASARAVAKKAM,150,273000,"PROVIDING BABY TOILET AND WATER SUPPLY ARRANGEMENT TO EXISTING ROOM AND REPAIR WORK AT POONI AMMAN KOIL STREET ANGANVADI IN DIV - 150, U - 34, ZONE - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/9741,Parks,Completed,NL-VALASARAVAKKAM,150,210000,"ANNUAL MAINTENANCE OF SRI PARASNATH NAGAR PARK AT SANTHOSH BAI STREET (KALAINGER KARUNANITHI PARK) IN DN.150, U 34, Z 11. (EMPLOYED QUALIFIED DIPLOMA IN HORTICULTURE FOR ONE YEAR PARK MAINTENANCE)",Own Sources,11,2017-18,2018-19 NL/2017-18/9844,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,397600,"DESILITING OF STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DIV - 150, UNIT - 34, ZONE - 11.",Own Sources,11,2017-18,2017-18 B/2017-18/9748,Buildings,Completed,B-Buildings,151,23060000,"ADDITIONAL CONSTRUCTION OF SECOND FLOOR IN URBAN COMMUNITY HEALTH CENTER (100BEDS HOSPITAL) AT HOSPITAL ROAD IN VALASARAVAKKAM, DN-151,ZN-11",Own Sources,11,2017-18,2019-20 D/2017-18/1991,Storm Water Drain,Completed,D-Storm Water Drains,151,1670000,Demolition of parapet wall and replacing with M.S Grill gate for de-silting in canals using Robatic multi purpose excavator in various places in South Region.,Own Sources,11,2017-18,2018-19 D/2017-18/6533,Storm Water Drain,Completed,D-Storm Water Drains,151,58139000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from Sabari nagar main road to AGS colony 3rd cross street In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,11,2017-18,2019-20 D/2017-18/6534,Storm Water Drain,Completed,D-Storm Water Drains,151,38321000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from Mugalivakkam main road to Sabari nagar main road In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,11,2017-18,2019-20 L/2017-18/12675,Electrical,Completed,L-Electrical,151,134000,"Supply and Laying of 31/2*25 Sq. mm. Al.UG Cable for power supply to the Park at Mount Poonamallee Road (Near Mugalivakkam signal and TCG Software Park) in Division-151,Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/10792,Parks,Completed,NL-VALASARAVAKKAM,151,151000,"ANNUAL MAINTENANCE OF SABARI NAGAR PARK FOR THE PERIOD OF ONE YEAR IN DN.151, U 34, ZONE 11.",Own Sources,11,2017-18,2018-19 NL/2017-18/12750,Buildings,Completed,NL-VALASARAVAKKAM,151,1060000,"Operation and Maintenance of high quality treated drinking water plant (RO/UV Filtration) at school road,(For 12 months), Div-151,U-34,Z-11",Own Sources,11,2017-18,2019-20 NL/2017-18/12894,Parks,Completed,NL-VALASARAVAKKAM,151,564000,"Annual Maintenance of TCG Park For the Period of One Year in Dn - 151, U - 34, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/13854,Buildings,Completed,NL-VALASARAVAKKAM,151,875000,"Improvements to the Corporation Building at MPH Road Jn of Ramakrishna Nagar Main Road Porur in Dn - 151, Unit - 34, Zone - XI",Own Sources,11,2017-18,2018-19 NL/2017-18/14594,Buildings,Completed,NL-VALASARAVAKKAM,151,129800,"Attending Patches, Improvements to Buildings, SWD, Parks, Bio - Toilets and Amma Unavagam in Dn - 151, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 NL/2017-18/1982,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,312100,"Desilting Storm Water Drain and Side Drain at various Streets in Dn - 151, U - 34, Z - 11.",Own Sources,11,2017-18,2017-18 NL/2017-18/2698,Buildings,Completed,NL-VALASARAVAKKAM,151,29600,"REPAIR AND IMPROVEMENT WORK AT HOSPITAL ROAD AMMA UNAVAGAM IN DIV - 151, U - 34, Z- 11",Own Sources,11,2017-18,2018-19 NL/2017-18/2709,Buildings,Completed,NL-VALASARAVAKKAM,151,356000,"REPAIR AND IMPROVEMENT WORK AT CHINNA PORUR HOSPITAL AT HOSPITAL ROAD IN DIV - 151, U - 34, Z- 11",Own Sources,11,2017-18,2017-18 NL/2017-18/2920,Buildings,Completed,NL-VALASARAVAKKAM,151,173000,"REPAIR AND MAINTAINANCE WORK AT ANJEYANAGAR KOIL STREET AMMA UNAVAGAM IN DIV ? 151, U -34, Z - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/3009,Buildings,Completed,NL-VALASARAVAKKAM,151,1158000,"Repair to Electrical Crematorium at Arcot Road in Dn.151, Unit-34, Zone - XI",Own Sources,11,2017-18,2019-20 NL/2017-18/3901,Roads,Completed,NL-VALASARAVAKKAM,151,100000,"PROVIDING SPEED BREAKER AS PER (IRC STANDARD) 5 NOS AT VARIOUS STREETS IN DIV - 151, U - 34, Z- 11.",Own Sources,11,2017-18,2017-18 NL/2017-18/7713,Electrical,Completed,NL-VALASARAVAKKAM,151,560500,"Supply & Erection of 30KVA DG set at Primary Health Centre (PHC),chinna porur, Division 151 Zone -XI",Own Sources,11,2017-18,2018-19 NL/2017-18/7715,Electrical,Completed,NL-VALASARAVAKKAM,151,498250,Repair and Replacement of Electrical accessories in Porur Electrical Crematorium in Div 151 Zone XI,Own Sources,11,2017-18,2018-19 L/2017-18/10202,Electrical,Completed,L-Electrical,152,11313000,"Provision of 111 Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 76 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Bethaniya Nagar Ambathgar Salai , Alapakkam Main Road ,Bhavaneshwari Nagar and Thiruvalluvar Salai Main Road in Division 152 Zone XI","Loans, Grants And Own Sources",11,2017-18,2018-19 NL/2017-18/10175,Electrical,Completed,NL-VALASARAVAKKAM,152,881000,"Supply and Fixing of 54 Nos of Ceiling Fan, 38 Nos of Exhaust Fan,13 nos of Water Heater, 23 No of Wall mounting Fan,12 No of UV Water Purifier 500 Litre per hour capacity ,4Nos of Weighing Machine ( up to 150 Kgm ) and 4 nos of freezer 200 litre, for Amma Unavagam in Dn-143 to 155 in Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/11558,Electrical,Completed,NL-VALASARAVAKKAM,152,37000,Supply of 20W Hand Grip Megaphone with built in Siren &Microphone DC 12V operation with volume control and press to talk swtich ISI marked with one year warrenty in Division 149 to 155 Sanitary Inspectors in Zone-11,Own Sources,11,2017-18,2018-19 NL/2017-18/12212,Roads,Completed,NL-VALASARAVAKKAM,152,1832000,"Improvements to interior BT Roads at Bethaniya Nagar Main Street, Thirunagar Annex and Arinjar Anna Avenue in Dn - 152, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12213,Roads,Completed,NL-VALASARAVAKKAM,152,1864000,"Improvements to interior BT Roads at Chowdry Nagar 5th Street, Majestic Colony Main Road and Jai Nagar 6th Street in Dn - 152, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12214,Roads,Completed,NL-VALASARAVAKKAM,152,1939000,"Improvements to interior BT Roads at Suresh Nagar Main Road (Part) and Chowdry Nagar Main Road (Part) in Dn - 152, U - 33, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/14001,Parks,Completed,NL-VALASARAVAKKAM,152,446000,"Providing Greenary at Thiru vi ka park, Ramakrishna nagar playground, Thanthai Periyar Park, Ceebros Park, Alsa Park, Palaniappa Nagar Childern's Playground, Brindhavan Nagar Park & Varadha in Division-149,Unit-33,Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/14154,Parks,Completed,NL-VALASARAVAKKAM,152,164000,Maintenance of various works in Division - 152 Unit - 33 in Zone - XI,Own Sources,11,2017-18,2018-19 NL/2017-18/14159,Buildings,Completed,NL-VALASARAVAKKAM,152,600000,"PROVIDING OPEN GYM EQUIPMENTS INCLUDING PLAT FORM AT BRINDHAVAN NAGAR VARDHA PARK IN DN-149, UNIT-33 ,ZONE-11.",Own Sources,11,2017-18,2018-19 NL/2017-18/14618,Buildings,Completed,NL-VALASARAVAKKAM,152,319000,Maintenance of various works in division 149 unit - 33 in zone - 11,Own Sources,11,2017-18,2018-19 NL/2017-18/1970,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,104000,"Desilting of Storm Water Drain and Side Drain at Various Streets in division - 152, Unit - 33 In Zone - XI",Own Sources,11,2017-18,2017-18 NL/2017-18/2477,Roads,Completed,NL-VALASARAVAKKAM,152,75000,"Supplying and laying Thermoplastic for Speed breaker (IRC Standard) at various Streets in Dn - 152, U - 33, Z - XI",Own Sources,11,2017-18,2017-18 NL/2017-18/2478,Roads,Completed,NL-VALASARAVAKKAM,152,83500,"Providing Speed breaker as per (IRC) Standard 4 nos at various Streets in Dn - 152, U - 33, Z - XI",Own Sources,11,2017-18,2017-18 NL/2017-18/2695,Buildings,Completed,NL-VALASARAVAKKAM,152,68000,"Repairs and maintanance of amma unavagam at Thiruvalluvar St, in Dn-152, Unit - 33, Zone - 11",Own Sources,11,2017-18,2018-19 NL/2017-18/8968,Buildings,Completed,NL-VALASARAVAKKAM,152,785000,Construction of baby toilet and compound wall for Anganwadi at Kaikankuppam VOC St Division - 152 Unit - 33 Zone - XI,Own Sources,11,2017-18,2018-19 NL/2017-18/8969,Buildings,Completed,NL-VALASARAVAKKAM,152,557000,Construction of baby toilet for Anganwadi at Bethaniya Nagar 3rd St in Division - 152 Unit - 33 Zone - XI,Own Sources,11,2017-18,2018-19 B/2017-18/3805,Buildings,Completed,B-Buildings,153,10776515,"Construction of Urban Primary Health Centre at Sakthi Nagar in Div-153, Zone ? 11.",Grants,11,2017-18,2019-20 L/2017-18/12354,Electrical,Completed,L-Electrical,153,44039000,"Provision of 863 nos of 6mtr GI lamp post with single straight bracket Hot Dip Zinc Galvanised with 40 -50w LED fittings, 133nos of 6mtr GI lamp post with single Arch bracket Hot Dip Zinc Galvanised with 90 -120w LED fittings at Subasree Nagar,suresh nagar & Various Location in Dn.153 & Bharthi sala & Various Locationi in Div 155 Zone-XI.","Loans, Grants And Own Sources",11,2017-18,2019-20 NL/2017-18/10002,Parks,Completed,NL-VALASARAVAKKAM,153,162000,"Annual Maintenance of Park at Kaniyapan salai and Ramakrishna Nagar in Dn.153,Unit-34,Zone-11.",Own Sources,11,2017-18,2018-19 NL/2017-18/12195,Roads,Completed,NL-VALASARAVAKKAM,153,2023000,"Improvements to interior BT Roads at Vigneshwara Nagar Pandian Street, Vigneshwara Nagar Vaigai Street, Vigneshwara Nagar Ganga Kaveri 1st Street and Vigneshwara Nagar Ganga Kaveri 2nd Cross Street, Nehru Street, Nehru Cross Street and Arivarasan Salai in Dn - 153, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12196,Roads,Completed,NL-VALASARAVAKKAM,153,2314000,"Improvements to interior BT Roads at Ramakrishna Nagar 7th Street, Ramakrishna Nagar Connecting Road, Udaya Nagar 2nd Street, Udaya Nagar Main Road and Suresh Nagar 1st Street in Dn - 153, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12197,Roads,Completed,NL-VALASARAVAKKAM,153,2135999,"Improvements to interior BT Roads at Suresh Nagar 2nd Street, Suresh Nagar 3rd Street, Suresh Nagar 4th Street, Subashree Nagar 3rd Main Road, Subashree Nagar 2nd Cross Street and Santhosh Nagar Vaigai Street in Dn - 153, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12198,Roads,Completed,NL-VALASARAVAKKAM,153,2506000,"Improvements to interior BT Roads at Ganesh Avenue 5th Street, Ganesh Avenue 6th Street, Ganesh Avenue 7th Street, Ganesh Avenue 2nd Main Road, Sterling Avenue 1st Street and Sterling Avenue 3rd Street in Dn - 153, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/14596,Buildings,Completed,NL-VALASARAVAKKAM,153,43800,"Attending Patches, Improvements to Buildings, SWD, Parks, Bio - Toilets and Amma Unavagam in Dn - 153, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 NL/2017-18/2026,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,541700,"Desilting Storm water drain and Side drain at various streets in Dn - 153, U - 34, Z - XI",Own Sources,11,2017-18,2017-18 NL/2017-18/2278,Buildings,Completed,NL-VALASARAVAKKAM,153,104000,"Dismantling of Annex U-34 office building for Proposed construction of UPHC in Div-153, U-34, Z-11",Own Sources,11,2017-18,2019-20 NL/2017-18/2739,Buildings,Completed,NL-VALASARAVAKKAM,153,90000,"Maintenance of Amma unavagam at Mount Poonamallee Road in Dn - 153, U - 34, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/2869,Buildings,Completed,NL-VALASARAVAKKAM,153,222000,"Maintenance to the existing UPHC and Unit office Building at Sakthi Nagar Main Road in Div-153, U-34, Z-11.",Own Sources,11,2017-18,2017-18 NL/2017-18/9347,Buildings,Completed,NL-VALASARAVAKKAM,153,1513000,"Construction of Baby friendly toilet and Minor repair works for Anganwadi at Palayakaran Street in Dn - 153, U - 34, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/9577,Buildings,Completed,NL-VALASARAVAKKAM,153,128000,"PROVIDING WATER SUPPLY ARRANGEMENT AT RAMAKRISHNA NAGAR PARK IN DIV - 153, U - 34, Z -11.",Own Sources,11,2017-18,2018-19 NL/2017-18/9842,Parks,Completed,NL-VALASARAVAKKAM,153,137000,"Annual Maintenance (2017-18) at Ramasamy Nagar Park in Ramasamy Nagar Main Road in Div - 153, U - 34, Z - 11.",Own Sources,11,2017-18,2018-19 L/2017-18/12356,Electrical,Completed,L-Electrical,154,8717000,"Provision of 90 Nos of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 89 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Perumal koil street,Kamber salai,Naidu street, Eswaran nagar main road and Thangal street Ramapuram Various plases in Division 154 Zone XI","Loans, Grants And Own Sources",11,2017-18,2019-20 NL/2017-18/12175,Roads,Completed,NL-VALASARAVAKKAM,154,2488000,"Improvements to interior BT Roads at Kannadasan Street, Kannammal Nagar 1st Cross Street Lane, Kannammal Nagar 2nd Cross Street Lane, Balambigai Nagar4th Street, R.P. Sundaram Street, R.P. Sundaram Street Lane and N.S.K Street in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12177,Roads,Completed,NL-VALASARAVAKKAM,154,2587000,"Improvements to interior BT Roads at Anandham Nagar 5th Cross Street, Burial Ground Street, Venkateshwara Nagar 14th Street and Venkateshwara Nagar 14th 1st Cross Street in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12178,Roads,Completed,NL-VALASARAVAKKAM,154,2408000,"Improvements to interior BT Roads at Venkateshwara Nagar 14th 2nd Cross Street, Shanthi Nagar Appadurai Street and G.S. Nagar Kabilar Street in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12179,Roads,Completed,NL-VALASARAVAKKAM,154,1715000,"Improvements to interior BT Roads at G.S. Nagar Manickavasagar Street, G.S. Nagar Nakkirar Street, Sannathi Street and Thiruvalluvar Street in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12199,Roads,Completed,NL-VALASARAVAKKAM,154,2661000,"Improvements to interior BT Roads at Naidu Street and Venkateshwara Nagar 19th Main Street in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12200,Roads,Completed,NL-VALASARAVAKKAM,154,1953000,"Improvements to interior BT Road at Venkateshwara nagar 1st Main Road (Reach - I) in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12201,Roads,Completed,NL-VALASARAVAKKAM,154,2340000,"Improvements to interior BT Roads at Venkateshwara nagar 1st Main Road (Reach - II) and Venkateshwara Nagar 23rd Street in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12775,Buildings,Completed,NL-VALASARAVAKKAM,154,828000,"Construction of compound wall at Shanthi Nagar Burial Ground in Dn - 154, U - 34, Z - XI.",Own Sources,11,2017-18,2019-20 NL/2017-18/14597,Buildings,Completed,NL-VALASARAVAKKAM,154,213700,"Attending Patches, Improvements to Buildings, SWD, Parks, Bio - Toilets and Amma Unavagam in Dn - 154, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 NL/2017-18/1942,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,238200,"Desilting Storm water drain and Side drain at various Streets in Dn - 154, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 NL/2017-18/9575,Buildings,Completed,NL-VALASARAVAKKAM,154,190000,"PROVIDING WATER SUPPLYING ARRANGEMENT AT( PC) GANGAI AMMAN KOIL STREET IN DIV - 154, U - 34, Z -11.",Own Sources,11,2017-18,2018-19 NL/2017-18/9576,Buildings,Completed,NL-VALASARAVAKKAM,154,190000,"PROVIDING WATER SUPPLYING ARRANGEMENT ( BIO TOILET) AT KAMBAR SALAI IN DIV - 154, U - 34, Z -11.",Own Sources,11,2017-18,2018-19 NL/2017-18/9655,Parks,Completed,NL-VALASARAVAKKAM,154,137000,"ANNUAL MAINTENANCE (2017 - 18) OF PARK AT KURINJI NAGAR PARK IN DN 154, U 34,ZONE XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/9877,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,360000,"Repair works for SWD and Side drain at Bharathiyar Street & Chinna Street in Dn - 154, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 B/2017-18/3994,Buildings,Completed,B-Buildings,155,11813699,"PROPOSED CONSTRUCTION OF DIVISION OFFICE IN 2nd FLOOR OVER THE PROPOSED UPHC BUILDING AT BANJANAI KOIL STREET, RAMAPURAM IN DIV- 155, ZONE- 11",Grants,11,2017-18,2019-20 BR/2017-18/2161,Road Cut,Completed,BR-Bus Route Roads,155,371000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -11 ( 4617/2016 ),Deposit Works,11,2017-18,2019-20 D/2017-18/6445,Storm Water Drain,Completed,D-Storm Water Drains,155,81133000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from MIOT hospital east side gate to Adyar river in Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,11,2017-18,2019-20 D/2017-18/6471,Storm Water Drain,Completed,D-Storm Water Drains,155,65089000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from MIOT hospital west side gate to MIOT hospital east side gate in Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,11,2017-18,2019-20 D/2017-18/6472,Storm Water Drain,Completed,D-Storm Water Drains,155,71921000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from Kalasathamman koil street to MIOT hospital west side gate in Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,11,2017-18,2019-20 D/2017-18/6476,Storm Water Drain,Completed,D-Storm Water Drains,155,78748000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from Valluvar salai to Kalasathamman koil street in Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,11,2017-18,2019-20 D/2017-18/6483,Storm Water Drain,Completed,D-Storm Water Drains,155,57599000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from MGR garden east side to Valluvar salai in Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,11,2017-18,2019-20 NL/2017-18/0226,Parks,Completed,NL-VALASARAVAKKAM,155,120000,"Providing water supply arrangements to Giri nagar park in dn-155, unit-34, zone-11.",Own Sources,11,2017-18,2017-18 NL/2017-18/12592,Road Cut,Completed,NL-VALASARAVAKKAM,155,2940000,"Improvements to Interior BT road at Sakthi Nagar 1st Street,Sakthi Nagar 2nd Street,Sakthi Nagar 3rd Street,Mullai Nagar 5th Street Lane,K.P. Nagar Main Road and Giri nagar 1st lane in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12595,Road Cut,Completed,NL-VALASARAVAKKAM,155,2659000,"Improvements to Interior BT road at Thamizh nagar 4th street, Thamizh nagar 5th street,Sriram nagar 3rd street,Mahalakshmi 1st cross street,Vanchinadhan Street and Senthamizh Nagar Kurinji Street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12596,Road Cut,Completed,NL-VALASARAVAKKAM,155,2933000,"Improvements to Interior BT road at Sriram Nagar Main Road and Sriram nagar 2nd street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/1260,Buildings,Completed,NL-VALASARAVAKKAM,155,747000,"Providing and Fixing GYM Equipments at Bajanai Koil Street in Dn - 155, U - 34, Z-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/12613,Road Cut,Completed,NL-VALASARAVAKKAM,155,2824000,"Improvements to Interior BT road at Thirupathi nagar, Chellamal nagar 1st main road, Chellamal nagar 2nd main road, Chellamal nagar 1st street and Chellamal nagar 2nd street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12618,Road Cut,Completed,NL-VALASARAVAKKAM,155,2782000,"Improvements to Interior BT road at Sriram nagar 1st street and Natesan nagar 1st main road in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12619,Road Cut,Completed,NL-VALASARAVAKKAM,155,2838000,"Improvements to Interior BT road at Kalasathamman koil street (UGSS) and Amman Nagar 1st street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2019-20 NL/2017-18/12620,Road Cut,Completed,NL-VALASARAVAKKAM,155,2263000,"Improvements to Interior BT road at Kalasathamman koil street(UGWSS) and Moogambigai nagar main street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12622,Road Cut,Completed,NL-VALASARAVAKKAM,155,2984000,"Improvements to Interior BT road at Nehru Nagar Sivanambal Street, Nehru Nagar Main road and Gangaiya Avenue 2nd Street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12623,Road Cut,Completed,NL-VALASARAVAKKAM,155,2819000,"Improvements to Interior BT road at Jai Balaji Nagar Annex I, Jai Balaji Nagar Annex II, Jai Balaji Nagar 1st Main Road, Royala Nagar 3rd Cross Street and Gangaiya Avenue 1st Street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12624,Road Cut,Completed,NL-VALASARAVAKKAM,155,2921000,"Improvements to Interior BT road at Mullai Nagar 1st Street, Mullai Nagar 2nd Street, Mullai Nagar 5th Street, Andaver Nagar Main Road, Andaver Nagar 1st Street, Andaver Nagar 2nd Street, Andaver Nagar 3rd street and Barathi Nagar 2nd Street in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12625,Road Cut,Completed,NL-VALASARAVAKKAM,155,2989000,"Improvements to Interior BT road at Natesan nagar 2nd main road, Natesan nagar 2nd main road (Pumping main cut), Azhagapuri nagar 1st main road, Azhagapuri nagar 2nd main road and AKR garden in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12626,Road Cut,Completed,NL-VALASARAVAKKAM,155,2003000,"Improvements to Interior BT road at Barathi Nagar Main Road, Barathi Nagar 1st Street and Gangaiya Avenue Main Road in division 155, unit-34, zone- 11",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12648,Road Cut,Completed,NL-VALASARAVAKKAM,155,2874000,"Improvements to Interior BT road at K.P. Nagar 1st Main Road, K.P. Nagar 2nd Main Road, K.P. Nagar 1st Street and K.P. Nagar 2nd Street in DN-155, Unit-34, Zone-XI",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12664,Roads,Completed,NL-VALASARAVAKKAM,155,2112000,"Improvements to Interior BT road at EVP Shanthosh Nagar 1st Main Road and EVP Shanthosh Nagar 2nd Main Road in Dn - 155, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12665,Roads,Completed,NL-VALASARAVAKKAM,155,2413000,"Improvements to Interior BT road at EVP Shanthosh Nagar 3rd Main Road, EVP Shanthosh Nagar 1st Street, EVP Shanthosh Nagar 2nd Street, EVP Shanthosh Nagar 3rd Street, EVP Shanthosh Nagar 4th Street, EVP Shanthosh Nagar 5th Street and EVP Shanthosh Nagar 6th Street in Dn - 155, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/12667,Roads,Completed,NL-VALASARAVAKKAM,155,2444000,"Improvements to Interior BT road at EVP Shanthosh Nagar 7th Street, Kalai Selvan Street, Ezhumalai Avenue, Azhagapuri Nagar 4th Avenue, Azhagapuri Nagar 5th Avenue, Azhagapuri Nagar 6th Avenue and Bakthivendha 3rd Avenue in Dn - 155, U - 34, Z - XI.",Loans And Grants,11,2017-18,2018-19 NL/2017-18/14203,Parks,Completed,NL-VALASARAVAKKAM,155,142000,"Maintenance of park at KP nagar and Jai balaji nagar in DN-155, Unit-34,Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/14304,Parks,Completed,NL-VALASARAVAKKAM,155,98000,"Improvements to park at Azhagapuri nagar in DN-155, Unit-34, Zone-XI",Own Sources,11,2017-18,2018-19 NL/2017-18/14600,Buildings,Completed,NL-VALASARAVAKKAM,155,373900,"Attending Patches, Improvements to Buildings, SWD, Parks, Bio - Toilets and Amma Unavagam in Dn - 155, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 NL/2017-18/16483,Buildings,Completed,NL-VALASARAVAKKAM,155,369000,"Construction of conservancy workers dress changing room and providing water supply arrangements to CI office (Library building) at Thamizh nagar 3rd street in dn-155, unit-34, zone-11.",Own Sources,11,2017-18,2018-19 NL/2017-18/2928,Buildings,Completed,NL-VALASARAVAKKAM,155,69000,"Demolishing UPHC Building and Division office annex buillding at Bajanai koil street in DN-155, unit-34, Zone-XI",Own Sources,11,2017-18,2019-20 NL/2017-18/3159,Buildings,Completed,NL-VALASARAVAKKAM,155,79000,"Maintenance of Amma Unavagam at Bajanai Koil Street in Dn - 155, U - 34, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/3190,Buildings,Completed,NL-VALASARAVAKKAM,155,27600,"Maintenance of Amma Unavagam at Thirumalai nagar VOC Street in Dn - 155, U - 34, Z - XI.",Own Sources,11,2017-18,2018-19 NL/2017-18/3885,Roads,Completed,NL-VALASARAVAKKAM,155,56000,"Supplying and laying of thermoplastic for 2 NOS of Speed breakersat Moogambigai street and Royala nagar 1st main road in DN-155, unit-34, zone-XI",Own Sources,11,2017-18,2017-18 NL/2017-18/3886,Roads,Completed,NL-VALASARAVAKKAM,155,66700,"Name of the work:Providing Speed breakers as per IRC design 2 NOS at Moogambigai street and Royala nagar 1st main road in DN-155, unit-34, zone-XI",Own Sources,11,2017-18,2017-18 NL/2017-18/8806,Buildings,Completed,NL-VALASARAVAKKAM,155,144000,"Providing water supply arrangements to Anganwadi at Amman nagar in dn-155, unit-34, zone-11.",Own Sources,11,2017-18,2018-19 NL/2017-18/8815,Buildings,Completed,NL-VALASARAVAKKAM,155,142000,"Maintainence and repairs work to Anganwadi at Bajanai koil st in dn-155, unit-34, zone-11.",Own Sources,11,2017-18,2018-19 NL/2017-18/8867,Buildings,Completed,NL-VALASARAVAKKAM,155,857000,"Construction of baby friendly toilet and improvements to Anganwadi at Thirumalai nagar VOC street in Div-155,U-34, Zone-11",Own Sources,11,2017-18,2018-19 NL/2017-18/9650,Parks,Completed,NL-VALASARAVAKKAM,155,164000,"Annual maintenance of park (one year) at Jai Balaji Nagar, Azhagapuri Nagar and KP Nagar in DN-155, U-34, Zone-Xi.",Own Sources,11,2017-18,2018-19 NL/2017-18/9780,Parks,Completed,NL-VALASARAVAKKAM,155,155000,"Annual maintenance of park (one year) at Giri nagar and Eswaran nagar in DN-155, U-34, Zone-Xi.",Own Sources,11,2017-18,2018-19 NL/2017-18/9879,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,166900,"Desilting of Storm Water Drain and Side Drain at Various Streets in Dn - 155, U - 34, Z - XI.",Own Sources,11,2017-18,2017-18 P/2017-18/16719,Parks,Completed,P-Parks and Playfields,155,4215035,"FORMATION OF NEW PARK AT ROYALA NAGAR 1ST MAIN ROAD IN DN-155, ZONE - XI",Own Sources,11,2017-18,2019-20 D/2017-18/6485,Storm Water Drain,Completed,D-Storm Water Drains,156,82669000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from Usha store room east side to Mount Poonamalle road In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,12,2017-18,2019-20 D/2017-18/6499,Storm Water Drain,Completed,D-Storm Water Drains,156,69479000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from Usha store room west side to Usha store room east side In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,12,2017-18,2019-20 D/2017-18/6503,Storm Water Drain,Completed,D-Storm Water Drains,156,72776000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from L & T East gate to Usha store room west side In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,12,2017-18,2019-20 D/2017-18/6529,Storm Water Drain,Completed,D-Storm Water Drains,156,72109000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from L & T west gate to L & T East gate In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,12,2017-18,2019-20 D/2017-18/6530,Storm Water Drain,Completed,D-Storm Water Drains,156,66170000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from DLF Entrance to L & T west gate In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,12,2017-18,2019-20 D/2017-18/6531,Storm Water Drain,Completed,D-Storm Water Drains,156,79360000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from T.V.Nagar to DLF Entrance In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,12,2017-18,2019-20 D/2017-18/6532,Storm Water Drain,Completed,D-Storm Water Drains,156,67831000,"Construction of flood protection wall, canal lining and other improvements to Nandambakkam canal from AGS colony 3rd cross street to T.V.Nagar In Adyar water shed Adyar basinin the expanded area of Greater Chennai Corporation.",Loans And Grants,12,2017-18,2019-20 NM/2017-18/0310,Parks,Completed,NM-ALANDUR,156,495000,"Annual Maintenance of Park at V.N.D Rajeswari Avenue Vaigai street in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/0314,Parks,Completed,NM-ALANDUR,156,185000,"Annual Maintenance of Park at Madha nagar 2nd street in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/0319,Parks,Completed,NM-ALANDUR,156,600000,"Annual Maintenance of Park at A.G.S Colony in Div-156,Unit-35,Zone-12(Period For one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/0498,Parks,Completed,NM-ALANDUR,156,390000,"Annual Maintenance of Thiruvalluvar Nager Park at Natha Muni street in Dn-156,unit-35,zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/0819,Buildings,Completed,NM-ALANDUR,156,1280000,"CONSTRUCTION OF TOILET BUILDING AT GUNDUMEDU IN DN.156 , U - 35 , Z - 12 .",Own Sources,12,2017-18,2017-18 NM/2017-18/0847,Buildings,Completed,NM-ALANDUR,156,730000,"CONSTRUCTION OF COMPOUND WALL IN BURIAL GROUND AT PONNIAMMAN KOIL MAIN ROAD DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/10426,Parks,Completed,NM-ALANDUR,156,590000,"PROPOSED OPEN GYM AT GURUSAMY NAGAR ,SANTHOSH NAGAR PARK IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/10630,Roads,Completed,NM-ALANDUR,156,1970000,"RESTORATION AND RELAYING OF BT ROAD USING PAVER FINISHER AT GOWRI NAGAR MAIN ROAD,GOWRI NAGAR 2ND STREET,GOWRI NAGAR 2ND(1ST CROSS STREET) IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12035,Parks,Completed,P-Parks and Playfields,156,2400000,"ADDITIONAL WORKS FOR NEW PARK AT GURUSAMY NANDHAGOPAL STREET IN DIV-156,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12131,Buildings,Completed,NM-ALANDUR,156,83000,"DISMANTLING OF DILAPIDATED UPHC BUILDING AT PADASALAI STREET IN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12458,Buildings,Completed,NM-ALANDUR,156,37000,"Improvement of Electrical work in community hall at selvalakshmi garden in dn-156,u-35,z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12459,Buildings,Completed,NM-ALANDUR,156,98000,"CONSTRUCTION OF SEPTIC TANK AT PC in MADHANANTHAPURAM MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12465,Buildings,Completed,NM-ALANDUR,156,313000,"IMPROVEMENT WORK OF ANGANVADI AT MADHANANDHAPURAM MAIN ROAD AND ALUVANCHERI AND PADASALAI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12484,Parks,Completed,NM-ALANDUR,156,879000,"IMPROVEMENT WORK OF PARK AND OPEN GYM AT VND RAJESWARI AVENUE SINDHU SALAI & MADHANGAR 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12490,Parks,Completed,NM-ALANDUR,156,216000,"IMPROVEMENT WORK OF PARK AT VND RAJESWARI AVENUE VAGAI STREET PARK & MERYGOLD STREET PARK IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12505,Parks,Completed,NM-ALANDUR,156,127000,"IMPROVEMENT WORK OF PARK AT ANNAIVELANKANNI NAGAR PH-1,2ND STREET& 5TH STREETIN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12506,Parks,Completed,NM-ALANDUR,156,35000,"IMPROVEMENT WORK OF PARK AT GURUSAMY NAGAR DEVADOSS STREET PARK ,SUBHASRI NAGAR 5TH STREET PARK AND IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12706,Parks,Completed,NM-ALANDUR,156,191000,"IMPROVEMENT WORK OF VGN LAKASHMI NAGAR PARK KALAIMAGAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12718,Parks,Completed,NM-ALANDUR,156,424000,"IMPROVEMENT WORK OPEN GYM AT PARK AT AGS COLONY PH-3 PARK IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12723,Parks,Completed,NM-ALANDUR,156,170000,"IMPROVEMENT WORK OF PARK AT CRR PURAM L& T COLONY PARK IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/12889,Storm Water Drain,Completed,NM-ALANDUR,156,102000,"DESILTING OF STORM WATER DRAIN (15 STREET ) IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/12890,Storm Water Drain,Completed,NM-ALANDUR,156,67000,"DESILTING OF STORM WATER DRAIN (22 STREET ) IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/13013,Parks,Completed,NM-ALANDUR,156,580000,"IMPROVEMENT AND OPEN GYM WORK OF SABARI NAGAR EXTN 5TH CROSS STREET PARK IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/13209,Roads,Completed,NM-ALANDUR,156,600000,"SUPPLYING AND FIXING OF GARBAGE FREE NOTICE BOARD FOR OSR LAND AND VACANT LANDS AT VARIOUS AREAS IN DIVISION 156,157,158,160,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13875,Roads,Completed,NM-ALANDUR,156,1368000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT BLOOMING GARDEN RAMAMORTHY AVENUE SAROJINI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13876,Roads,Completed,NM-ALANDUR,156,2536000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT BLOOMING GARDEN LAVANDER STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13877,Roads,Completed,NM-ALANDUR,156,1563000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT BLOOMING GARDEN MANI ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13878,Roads,Completed,NM-ALANDUR,156,2257000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT THIRUVALLUVAR NAGAR NATHAMUNI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13879,Roads,Completed,NM-ALANDUR,156,2224000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT THIRUVALLUVAR NAGAR MUTHAMMAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13880,Roads,Completed,NM-ALANDUR,156,2229000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT THIRUVALLUVAR NAGAR NATARAJ STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13881,Roads,Completed,NM-ALANDUR,156,1297000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT THIRUVALLUVAR NAGAR PAUNAMMAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13882,Roads,Completed,NM-ALANDUR,156,2300000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT VGN LAKSHMI NAGAR MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13884,Roads,Completed,NM-ALANDUR,156,2187000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT NANDHA GOPALRAJA STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13885,Roads,Completed,NM-ALANDUR,156,2064000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT SUBBHAIYA NAGAR MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13886,Roads,Completed,NM-ALANDUR,156,1059000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT SANTHOSH NAGAR RAMACHANDRA STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14035,Roads,Completed,NM-ALANDUR,156,1430000,"RELAYING OF BT ROAD USING PAVER FINISHER AT VND RAJESWARI AVENUE SINDHU SALAI IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14036,Roads,Completed,NM-ALANDUR,156,1038000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT KUMUTHAM NAGAR EAST MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14037,Roads,Completed,NM-ALANDUR,156,2147000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT LALITHAMBAL NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14038,Roads,Completed,NM-ALANDUR,156,949000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT SHANMUGA NAGAR BHARATHIDHASAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14039,Roads,Completed,NM-ALANDUR,156,784000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT SHANMUGA NAGAR BHARATHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14040,Roads,Completed,NM-ALANDUR,156,867000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT SHANMUGA NAGAR KAMBER STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14041,Roads,Completed,NM-ALANDUR,156,247000,"FORMING AND RELAYING OF BT ROAD USING PAVER FINISHER AT SHANMUGA NAGAR KANNADHASAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14074,Roads,Completed,NM-ALANDUR,156,670000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ARUMUGAM NAGAR 2ND STREET N DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14075,Roads,Completed,NM-ALANDUR,156,96000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ARUMUGAM NAGAR CROSS STREET N DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14076,Roads,Completed,NM-ALANDUR,156,143000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ANNAIVELANKANNI CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14077,Roads,Completed,NM-ALANDUR,156,734000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN JAHAVALLAR NEHRU STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14078,Roads,Completed,NM-ALANDUR,156,370000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN THIRUVALLUVAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14079,Roads,Completed,NM-ALANDUR,156,255000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN RAJA STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14080,Roads,Completed,NM-ALANDUR,156,478000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN KAMARAJAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14081,Roads,Completed,NM-ALANDUR,156,287000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN BHARATHIYAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14082,Roads,Completed,NM-ALANDUR,156,941000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN INDRAGANDHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14083,Roads,Completed,NM-ALANDUR,156,590000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN PATTAMMAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14084,Roads,Completed,NM-ALANDUR,156,143000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR EXTN MAHATMAGANDHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14085,Roads,Completed,NM-ALANDUR,156,734000,"IMPROVEMENT TO EXISTING OF BT ROAD AT SUNDRAVADIVEL NAGAR N DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14086,Roads,Completed,NM-ALANDUR,156,925000,"IMPROVEMENT TO EXISTING OF BT ROAD AT AGS COLONY KAUVERI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14087,Roads,Completed,NM-ALANDUR,156,207000,"IMPROVEMENT TO EXISTING OF BT ROAD AT AGS COLONY 2ND CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14088,Roads,Completed,NM-ALANDUR,156,287000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KAMALA NAGAR CROSS STREET DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14089,Roads,Completed,NM-ALANDUR,156,303000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KAMALA NAGAR 3RD STREET DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14090,Roads,Completed,NM-ALANDUR,156,383000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KAMALA NAGAR 4TH STREET DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14091,Roads,Completed,NM-ALANDUR,156,287000,"IMPROVEMENT TO EXISTING OF BT ROAD AT SUBHASRI NAGAR EXTN 5TH STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14092,Roads,Completed,NM-ALANDUR,156,223000,"IMPROVEMENT TO EXISTING OF BT ROAD ATANNAI THERASA STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14093,Roads,Completed,NM-ALANDUR,156,239000,"IMPROVEMENT TO EXISTING OF BT ROAD AT SABARI NAGAR 5TH CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14094,Roads,Completed,NM-ALANDUR,156,766000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ANNAIVELANKANNI NAGAR PHASE-2 MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14095,Roads,Completed,NM-ALANDUR,156,319000,"IMPROVEMENT TO EXISTING OF BT ROAD AT BRINDHAVANAM GARDEN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14312,Roads,Completed,NM-ALANDUR,156,813000,"IMPROVEMENT TO EXISTING OF BT ROAD AT BRINDHAVANAM GARDEN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14313,Roads,Completed,NM-ALANDUR,156,734000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KAVERY 1ST STREET DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14314,Roads,Completed,NM-ALANDUR,156,1691000,"IMPROVEMENT TO EXISTING OF BT ROAD AT BELL NAGAR REACH-1 IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14315,Roads,Completed,NM-ALANDUR,156,383000,"IMPROVEMENT TO EXISTING OF BT ROAD AT BELL NAGAR REACH-2 IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14316,Roads,Completed,NM-ALANDUR,156,399000,"IMPROVEMENT TO EXISTING OF BT ROAD AT BELL NAGAR REACH-3 IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14317,Roads,Completed,NM-ALANDUR,156,526000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR DEVADOSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14318,Roads,Completed,NM-ALANDUR,156,494000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR MANGAIYAKARASI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14319,Roads,Completed,NM-ALANDUR,156,558000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR NARASIMMAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14320,Roads,Completed,NM-ALANDUR,156,430000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR KANNAMAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14321,Roads,Completed,NM-ALANDUR,156,271000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR LAKSHMI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14322,Roads,Completed,NM-ALANDUR,156,782000,"IMPROVEMENT TO EXISTING OF BT ROAD AT RAMYA NAGAR ANNA SALAI IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14323,Roads,Completed,NM-ALANDUR,156,877000,"IMPROVEMENT TO EXISTING OF BT ROAD AT RAMYA NAGAR VOC NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14324,Roads,Completed,NM-ALANDUR,156,574000,"IMPROVEMENT TO EXISTING OF BT ROAD AT SANDHOSH NAGAR RAJESWARI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14325,Roads,Completed,NM-ALANDUR,156,1069000,"IMPROVEMENT TO EXISTING OF BT ROAD AT GURUSAMY NAGAR NEDHAJI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14326,Roads,Completed,NM-ALANDUR,156,383000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR RANGANATHAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14327,Roads,Completed,NM-ALANDUR,156,335000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR JAYACHANDRAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14328,Roads,Completed,NM-ALANDUR,156,159000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR MANI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14329,Roads,Completed,NM-ALANDUR,156,207000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR LAKSMI GARDEN IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14330,Roads,Completed,NM-ALANDUR,156,159000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR AMBIGA STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14342,Roads,Completed,NM-ALANDUR,156,111000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR JAYACHANDRAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14343,Roads,Completed,NM-ALANDUR,156,191000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR SETHU STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14344,Roads,Completed,NM-ALANDUR,156,143000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MUTHUMARIAMMAN NAGAR JAYALAKSHMI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14345,Roads,Completed,NM-ALANDUR,156,367000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR 10TH STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14346,Roads,Completed,NM-ALANDUR,156,383000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR 10TH CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14347,Roads,Completed,NM-ALANDUR,156,494000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR 3RD MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14348,Roads,Completed,NM-ALANDUR,156,574000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR 2ND MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14349,Roads,Completed,NM-ALANDUR,156,957000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14350,Roads,Completed,NM-ALANDUR,156,223000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR 13TH CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14351,Roads,Completed,NM-ALANDUR,156,287000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR 13TH STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14352,Roads,Completed,NM-ALANDUR,156,79000,"IMPROVEMENT TO EXISTING OF BT ROAD AT MADHA NAGAR 15 STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14353,Roads,Completed,NM-ALANDUR,156,1021000,"IMPROVEMENT TO EXISTING OF BT ROAD AT IMACHAL NAGAR (REACH 1)IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14354,Roads,Completed,NM-ALANDUR,156,351000,"IMPROVEMENT TO EXISTING OF BT ROAD AT IMACHAL NAGAR (REACH 2)IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14355,Roads,Completed,NM-ALANDUR,156,351000,"IMPROVEMENT TO EXISTING OF BT ROAD AT IMACHAL NAGAR (REACH 3)IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14356,Roads,Completed,NM-ALANDUR,156,893000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ANNAIVELANKANNI NAGAR PH-1 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14357,Roads,Completed,NM-ALANDUR,156,303000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ANNAIVELANKANNI NAGAR PH-1 9TH STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14358,Roads,Completed,NM-ALANDUR,156,175000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ANNAIVELANKANNI NAGAR PH-1 9TH CROSS IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14359,Roads,Completed,NM-ALANDUR,156,159000,"IMPROVEMENT TO EXISTING OF BT ROAD AT RAMACHANDRA NAGAR CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14360,Roads,Completed,NM-ALANDUR,156,574000,"IMPROVEMENT TO EXISTING OF BT ROAD AT RAMACHANDRA NAGAR MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14361,Roads,Completed,NM-ALANDUR,156,478000,"IMPROVEMENT TO EXISTING OF BT ROAD AT RAJARAJESWARI NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14362,Roads,Completed,NM-ALANDUR,156,383000,"IMPROVEMENT TO EXISTING OF BT ROAD AT LALITHA NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14363,Roads,Completed,NM-ALANDUR,156,399000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KARUMARIAMMAN NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14364,Roads,Completed,NM-ALANDUR,156,255000,"IMPROVEMENT TO EXISTING OF BT ROAD AT LALITHA NAGAR 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14446,Roads,Completed,NM-ALANDUR,156,446000,"IMPROVEMENT TO EXISTING OF BT ROAD AT LALITHA NAGAR MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14447,Roads,Completed,NM-ALANDUR,156,143000,"IMPROVEMENT TO EXISTING OF BT ROAD AT LAKSHMI NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14448,Roads,Completed,NM-ALANDUR,156,319000,"IMPROVEMENT TO EXISTING OF BT ROAD AT LAKSHMI NAGAR 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14449,Roads,Completed,NM-ALANDUR,156,478000,"IMPROVEMENT TO EXISTING OF BT ROAD AT LAKSHMI NAGAR MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14450,Roads,Completed,NM-ALANDUR,156,111000,"IMPROVEMENT TO EXISTING OF BT ROAD AT LAKSHMI NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14451,Roads,Completed,NM-ALANDUR,156,287000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KRISHNA NAGAR 3RD STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14452,Roads,Completed,NM-ALANDUR,156,383000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KRISHNA NAGAR 1ST MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14453,Roads,Completed,NM-ALANDUR,156,367000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KRISHNA NAGAR 2ND MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/15028,Roads,Completed,NM-ALANDUR,156,764000,"IMPROVEMENT TO EXISTING OF CC ROAD AT SABARI NAGAR 1ST MAIN N DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/15029,Roads,Completed,NM-ALANDUR,156,714000,"IMPROVEMENT TO EXISTING OF CC ROAD AT METTUKUPPAM PERUMAL KOIL STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/15030,Roads,Completed,NM-ALANDUR,156,398000,"IMPROVEMENT TO EXISTING OF CC ROAD AT SANTHOSH NAGAR PADMAVATHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/15031,Roads,Completed,NM-ALANDUR,156,631000,"IMPROVEMENT TO EXISTING OF CC ROAD AT PONNI NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/15032,Roads,Completed,NM-ALANDUR,156,116000,"IMPROVEMENT TO EXISTING OF CC ROAD AT SIVAJI NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/15033,Roads,Completed,NM-ALANDUR,156,481000,"IMPROVEMENT TO EXISTING OF CC ROAD AT SIVAJI NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/15034,Roads,Completed,NM-ALANDUR,156,232000,"IMPROVEMENT TO EXISTING OF CC ROAD AT RANIJI NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/15035,Roads,Completed,NM-ALANDUR,156,199000,"IMPROVEMENT TO EXISTING OF CC ROAD AT BHARATHIDHASAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/15138,Buildings,Completed,NM-ALANDUR,156,998000,"ATTENDING PATCH WORK WITH WMM AT VARIOUS STREETS IN DN-156,U-35, Z-12.",Own Sources,12,2017-18,2019-20 NM/2017-18/1556,Roads,Completed,NM-ALANDUR,156,223000,"IMPROVEMENT WORK TO THE EXISTING SPEED BREAKERS AT VARIOUS STREET IN DN-156, UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/15908,Parks,Completed,P-Parks and Playfields,156,3000000,PLANTATION OF MAINTENANCE OF TREES SAPLINGS FOR ONE YEAR AT VARIOUS PLACES IN ZONE 12 (1230 TREES),Own Sources,12,2017-18,2020-21 NM/2017-18/16635,Parks,Completed,NM-ALANDUR,156,1630000,"CONSTRUCTION OF COMPOUND WALL IN OSR LAND AT BLOOMING GARDEN IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/16639,Parks,Completed,NM-ALANDUR,156,335000,"CONSTRUCTION OF COMPOUND WALL IN OSR LAND AT SUBAIYA NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/16643,Electrical,Completed,NM-ALANDUR,156,612200,REPLACEMENT OF DAMAGED CFL FITTING INTO 40 NOS OF 20 WLED LED FITTINGS AND 6 NOS OF 40 W LED FITTING AT ANNAI VELANKANNI NAGAR PHASE-I 1ST STREET PARK IN DN-156 ZONE - XII,Own Sources,12,2017-18,2018-19 NM/2017-18/16645,Electrical,Completed,NM-ALANDUR,156,572500,REPLACEMENT OF 37 NOS OF DAMAGED CFL FITTING INTO 20W LED FITTINGS AT ANNAI VELANKANNI NAGAR PHASE-I 5 st STREET PARK IN DN-156 ZONE - XII,Own Sources,12,2017-18,2018-19 NM/2017-18/17143,Parks,Completed,NM-ALANDUR,156,270000,"REPAIR AND MAINTENANCE WORK AT BUILDINGS,PARKS,TOILET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/3185,Buildings,Completed,NM-ALANDUR,156,1900000,"CONSTRUCTION OF COMPOUND WALL FOR PANICHATHAMMAN KULAM AT PADASALAI STREET DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/5548,Roads,Completed,NM-ALANDUR,156,275000,"CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/6378,Parks,Completed,NM-ALANDUR,156,345000,"PROPOSED OPEN GYM AT THIRUVALLUVAR NAGAR NATHAMUNI STREET PARK IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/6379,Parks,Completed,NM-ALANDUR,156,590000,"PROPOSED OPEN GYM AT CRR PURAM L&T COLONY PARK IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/6802,Parks,Completed,NM-ALANDUR,156,486000,"Annual Maintenance of Park at CRR Puram L&T Colony in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/6804,Parks,Completed,NM-ALANDUR,156,500000,"Annual Maintenance of Park at Kumutham Nagar Park in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/6921,Roads,Completed,NM-ALANDUR,156,1130000,"PROVIDING AND SUPPLYING OF COMPOUND WALL GRILL AT VANNAN KULAM OTHAVADAI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7359,Buildings,Completed,NM-ALANDUR,156,257000,"REPAIR AND IMPROVEMENT WORK OF UPHC BUILDING AT PADASALAI STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8029,Parks,Completed,NM-ALANDUR,156,170000,"Annual Maintenance of Park at Mary Gold street in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8030,Parks,Completed,NM-ALANDUR,156,180000,"Annual Maintenance of Park at Gurusamy nagar Devadoss street in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8031,Parks,Completed,NM-ALANDUR,156,210000,"Annual Maintenance of Park at V.N.D Rajeswari avenue sindhu street in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8032,Parks,Completed,NM-ALANDUR,156,175000,"Annual Maintenance of Park at Sabari Nagar 2nd Main road and 1st main road in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8033,Parks,Completed,NM-ALANDUR,156,145000,"Annual Maintenance of Park at SSI green park Madhanandhapuram Main road in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8035,Parks,Completed,NM-ALANDUR,156,228000,"Annual Maintenance of Park at Annai Velankanni nagar phase-1 5th street and 2nd street in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8037,Parks,Completed,NM-ALANDUR,156,175000,"Annual Maintenance of Park at VGN lakshmi nagar viswanathan palani Park in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8039,Parks,Completed,NM-ALANDUR,156,188000,"Annual Maintenance of Park at kundrathur main road park in Dn.156,Unit-35,Zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8072,Parks,Completed,NM-ALANDUR,156,150000,"Annual Maintenance of sabari nagr 5th street in Dn-156,unit-35,zone-12(Period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/9282,Buildings,Completed,NM-ALANDUR,156,140000,"PROVIDING SEPTIC TANK AT PC IN OTHAVADAI STREET IN DN 156,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9388,Buildings,Completed,NM-ALANDUR,156,250000,"REPAIR AND MAINTENANCE OF AMMA UNAVAGAM AT NANDHAGOPAL RAJA STREET IN DN-156,U-35,Z-12",Own Sources,12,2017-18,2018-19 BR/2017-18/2175,Road Cut,Completed,BR-Bus Route Roads,157,424000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -12 ( 0779/2017),Deposit Works,12,2017-18,2018-19 L/2017-18/0051,Electrical,Completed,L-Electrical,157,3250800,Provision of 20 nos of 9mtr GI lamp post with double straight bracket Hot Dip Zinc Galvanised with 150 -165w LED fittings and removal and refixing 23 nos exsisting lamp post at widening of bridge at mount poonamallee road in Dn.157 in Zone-XII.,Deposit Works,12,2017-18,2019-20 L/2017-18/12385,Electrical,Completed,L-Electrical,157,5569600,PROVISION OF 130NOS OF 6MTR GI LAMP POST WITH SINGLE STRAIGHT BRACKET HOT DIP GALANISED WITH 40-50W LED FITTINGS AT VARIOUS LOCATION IN DN157 AND 158 ZONE12,"Loans, Grants And Own Sources",12,2017-18,2019-20 NM/2017-18/10428,Buildings,Completed,NM-ALANDUR,157,386000,"REPAIRS AND IMPROVEMENTS OF PARK AT BELL NAGAR PARK AND KAVIYA GARDEN PARK IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/10644,Electrical,Completed,NM-ALANDUR,157,234000,"REPAIRS AND IMPROVEMENTS OF PARK AT RIVER VIEW COLONY PHASE-2 IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/10645,Buildings,Completed,NM-ALANDUR,157,161000,"REPAIRS AND IMPROVEMENTS OF PARK AT MACRO MARVEL PARK IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2019-20 NM/2017-18/10647,Electrical,Completed,NM-ALANDUR,157,177000,"REPAIRS AND IMPROVEMENTS OF PARK AT RIVER VIEW COLONY PHASE-1 IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12715,Buildings,Completed,NM-ALANDUR,157,456000,"PROVIDING OPEN GYM AT MACRO MARVEL PARK IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/1304,Buildings,Completed,NM-ALANDUR,157,247000,"providing Water Supply Arrangement And Electrical Arrangement E-Toilet At Moit Hospital in Dn-157, U-35,z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/16724,Electrical,Completed,NM-ALANDUR,157,754600,"Replacement of 70nos 20w led fitting and 12 nos of 90w fitting and 4 nos of 150w led fitting at river view colony phase I & II Dn-157 ,ZoneXII",Own Sources,12,2017-18,2018-19 NM/2017-18/17258,Buildings,Completed,NM-ALANDUR,157,266000,"REPAIR AND MAINTENANCE AT PARK , PC , ROADS IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/1954,Buildings,Completed,NM-ALANDUR,157,215000,"providing Water Supply Arrangement And Electrical Arrangement E-Toilet At Meetu Colony in Dn-157, U-35,z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/1955,Buildings,Completed,NM-ALANDUR,157,266000,"providing Water Supply Arrangement And Electrical Arrangement E-Toilet At MGR Nagar in Dn-157, U-35,z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/1956,Buildings,Completed,NM-ALANDUR,157,249000,"providing Water Supply Arrangement And Electrical Arrangement E-Toilet At Dharmarajpuram in Dn-157, U-35,z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/2220,Roads,Completed,NM-ALANDUR,157,109000,"PAINTING OF EXISTING SPEED BREAKERS AT VARIOUS STREET IN DIVISION-157, UNIT-35,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/2448,Buildings,Completed,NM-ALANDUR,157,163000,"Repair and maintenance work At Amma Unavagam IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/2830,Storm Water Drain,Completed,NM-ALANDUR,157,106000,"DAMAGED PORTION OF SIDE DRAIN AT METTU COLONY KAMARAJAR SALAI IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2017-18 NM/2017-18/3975,Buildings,Completed,NM-ALANDUR,157,126000,"CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET DN-157,U-35,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/8021,Parks,Completed,NM-ALANDUR,157,545000,"Annual Maintenance of Park at Kaviya Garden, Bell Nagar & Macro Marvel park in Dn.157,Unit-35,Zone-12(period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8022,Parks,Completed,NM-ALANDUR,157,470000,"Annual Maintenance of Park at River Colony Phase -1 in Dn.157,Unit-35,Zone-12(period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8023,Parks,Completed,NM-ALANDUR,157,197000,"Annual Maintenance of Park at River Colony Phase -2 in Dn.157,Unit-35,Zone-12(period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8024,Parks,Completed,NM-ALANDUR,157,563000,"Annual Maintenance of Park at Naveen Flats & River View Colony Phase-3 in Dn.157,Unit-35,Zone-12(period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8230,Buildings,Completed,NM-ALANDUR,157,39000,"REPAIR AND MAINTENANCE OF PC AT PERIYA COLONY IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8231,Buildings,Completed,NM-ALANDUR,157,10000,"REPAIR AND MAINTENANCE OF PC AT GIRI GORI NAGAR IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8232,Buildings,Completed,NM-ALANDUR,157,128000,"REPAIR AND MAINTENANCE OF PC AT PURACHI THALAIVI NAGAR IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8819,Storm Water Drain,Completed,NM-ALANDUR,157,539000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-157,UNIT-35,ZONE-12",Own Sources,12,2017-18,2017-18 NM/2017-18/9625,Buildings,Completed,NM-ALANDUR,157,24000,"Repairs and Maintenance of Anganvadi at sub heath centre road (ICDS-1) in div -157, unit-35,zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9713,Buildings,Completed,NM-ALANDUR,157,268000,"REPAIR AND MAINTENANCE OF ANGANVADI AT DHARMARAJAPURAM IN DN-157,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9718,Buildings,Completed,NM-ALANDUR,157,470000,"RAISING AND FORMING THE ROAD AT RIVER VIEW COLONY GOTHAVARI STREET IN DN-157,UNIT-35, ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9801,Buildings,Completed,NM-ALANDUR,157,128000,"REPAIR AND MAINTENANCE OF ANGANVADI AT PERIYAR SALAI IN DN-157,U-35,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9802,Buildings,Completed,NM-ALANDUR,157,238000,"REPAIR AND MAINTENANCE OF ANGANVADI AT PERIYA COLONY IN DN-157,U-35 Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/10567,Buildings,Completed,NM-ALANDUR,158,1800000,"Improvement works to Compost plant at TPF and Burial ground inner side at M.G.R Nagar in Div-158, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/10601,Buildings,Completed,NM-ALANDUR,158,201000,"Improvement works to TPF at M.G.R Nagar in Div-158, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12453,Parks,Completed,NM-ALANDUR,158,442000,"Improvement works to Park at Sundar nagar in Div-158, U-35, Zn-12",Own Sources,12,2017-18,2019-20 NM/2017-18/12779,Buildings,Completed,NM-ALANDUR,158,834000,"IMPROVEMENT WORKS TO THE EXISTING PUBLIC CONVENIENCE AT RAMAR KOIL STREET IN DN 158, UNIT-35, ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12803,Storm Water Drain,Completed,NM-ALANDUR,158,122000,"Desilting of storm water drain at Ganapathypuram Colony, Defence Officers colony, Thulasingapuram, Woodgreek County (35-Streets) in Div-158, Unit-35, Zone-12",Own Sources,12,2017-18,2017-18 NM/2017-18/13070,Storm Water Drain,Completed,NM-ALANDUR,158,184000,"Desilting of Storm water drain at Sundar Nagar, Nandambakkam, Defence Officers Colony in Div-158, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14547,Buildings,Completed,NM-ALANDUR,158,134000,"Providing partition for conservancy workers room and Improvement works to Division office at Bajanai Koil Street in Div-158, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/1841,Roads,Completed,NM-ALANDUR,158,96000,"IMPROVEMENT WORKS TO EXISTING SPEED BREAKER AT VARIOUS STREET IN DIVISION-158, UNIT-35,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/3993,Buildings,Completed,NM-ALANDUR,158,89000,"CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET DN-158,U-35,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/8073,Storm Water Drain,Completed,NM-ALANDUR,158,110000,"Providing Rubber mat for floor and Gym equipments for corporation gym at East Lakeview street in Div-158, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8107,Parks,Completed,NM-ALANDUR,158,137000,"Annual Maintenance of Park at Sunder nagar in Dn.158,Unit-36,Zone-12.(one year).",Own Sources,12,2017-18,2018-19 NM/2017-18/8128,Buildings,Completed,NM-ALANDUR,158,34000,"Improvement works to Amma Unavagam at Bajanai Koil street & Burma Colony in Div-158, U-35, Zn-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9853,Buildings,Completed,NM-ALANDUR,158,70000,"Additional improvement works to Anganwadi at West Lakeview Street in Div-158, U-35, Zn-12",Own Sources,12,2017-18,2018-19 NM/2017-18/10628,Buildings,Completed,NM-ALANDUR,159,348000,CONSTRUCTION OF AMMA UNAVAGAM PHASE-2 KITCHEN AT GST ROAD IN DN 159 U36 Z-XII,Own Sources,12,2017-18,2018-19 NM/2017-18/12770,Buildings,Completed,NM-ALANDUR,159,3260000,PROPOSED CONSTRUCTION OF COMPOST YARD AT MEENAMBAKKAM BURIAL GROUND (CSR FUND) IN DIV -159 U-36 Z -12,Own Sources,12,2017-18,2018-19 NM/2017-18/12996,Buildings,Completed,NM-ALANDUR,159,77000,"REPAIR AND MAINTENANCE WORK TO E-TOILET AT MEENAMBAKKAM BURIAL GROUND IN DN-159,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12997,Buildings,Completed,NM-ALANDUR,159,37000,"REPAIR AND MAINTENANCE WORK TO PUBLIC TOILET AT V.O.C STREET IN DN-159,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12998,Buildings,Completed,NM-ALANDUR,159,43000,"REPAIR AND MAINTENANCE WORK TO PUBLIC TOILET AT ANNA STREET IN DN-159,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7862,Buildings,Completed,NM-ALANDUR,159,49000,PROPOSED RAISING OF COMPOUND WALL IN BURIAL GROUND MEENAMBAKKAM IN DN-159 U-35 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/9546,Buildings,Completed,NM-ALANDUR,159,187000,PROVIDING BORE WELL ARRANGEMENTS WORKS TO BIO TOILET AT PANDIAN STREET IN DN-159 U-35 ZONE-12,Own Sources,12,2017-18,2018-19 NM/2017-18/9640,Buildings,Completed,NM-ALANDUR,159,56000,MAINTANANCE WORK AT AMMA UNAVAGAM G S T ROAD IN MEENAMBAKKAM IN Dn-159 U-35 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/9649,Storm Water Drain,Completed,NM-ALANDUR,159,103000,DESILTING OF SWD& SIDE DRAIN AT VARIOUS STREET IN DN-159 U-35 Z-12,Own Sources,12,2017-18,2017-18 L/2017-18/0547,Electrical,Completed,L-Electrical,160,999000,"Conversion of 2000W MH Fitting ( for energy saving purpose) into 240W-300W LED fittings and replacement of damaged cables at Umbrella Highmast near AC Office, Div - 160, Z-XII",Own Sources,12,2017-18,2017-18 L/2017-18/0548,Electrical,Completed,L-Electrical,160,995000,"Conversion of 2000W MH Fitting ( for energy saving purpose) into 240W-300W LED fittings and replacement of damaged cables for Umbrella Highmast opposite to Le Royal Meridian at Kathipara, Div - 160, Z-XII",Own Sources,12,2017-18,2017-18 L/2017-18/0550,Electrical,Completed,L-Electrical,160,994600,"Conversion of 2000W MH Fitting ( for energy saving purpose) into 240W-300W LED fittings and replacement of damaged cables for Umbrella Highmast near right side of Porur Guindy Loop at Kathipara, Div - 160, Z-XII",Own Sources,12,2017-18,2017-18 L/2017-18/0551,Electrical,Completed,L-Electrical,160,933400,"Conversion of 2000W MH Fitting ( for energy saving purpose) into 240W-300W LED fittings and replacement of damaged cables for Umbrella Highmast in right side of Vadapalani Guindy service road at Kathipara junction, Div - 160, Z-XII",Own Sources,12,2017-18,2017-18 NM/2017-18/0040,Buildings,Completed,NM-ALANDUR,160,321000,"Providing Aluminium partition for Returning Officer room and Shed in Zonal office building at New Street in Div-160, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/0042,Buildings,Completed,NM-ALANDUR,160,327000,"Improvement works to Unit office 37 in Zonal office building at New street in Div-160, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/0307,Parks,Completed,NM-ALANDUR,160,153000,"Annual Maintenance of park at new street in Dn.160,Unit-35,Zone-12(period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/10344,Electrical,Completed,NM-ALANDUR,160,725000,"Proposed to Replace and Purchase of 26 Nos of Ceiling Fan, 14 Nos of Exhaust Fan, 1 No of Wall mounting Fan,13 nos of Water Heater,1 No of Pulvarizer, 2 nos of 200litre freezer, 3 Nos of Weighing Machine, 8 nos of commercial mixer in Dn-156 to 167 in Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/10671,Electrical,Completed,NM-ALANDUR,160,63000,Proposed to Purchase 12 Nos of Megaphone 20W at Amma Unavagam in Dn-156 to 167 in Zone-12,Own Sources,12,2017-18,2018-19 NM/2017-18/12999,Buildings,Completed,NM-ALANDUR,160,263000,DAMAGED DILAPIDATED PARK COMPOUND WALL AT NEW STREET IN DN-160 U-35 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/13902,Buildings,Completed,NM-ALANDUR,160,433000,"DEMOLITION OF GANDHI HOSPITAL OLD BUILDING AT SOWRI STREET IN DIV -160 , U -35, Z -12",Own Sources,12,2017-18,2019-20 NM/2017-18/2051,Roads,Completed,NM-ALANDUR,160,97000,"PAINTING OF THE EXISTING SPEED BREAKERS AT VARIOUS STREET IN DN-160, UNIT-35,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/2763,Buildings,Completed,NM-ALANDUR,160,1256000,IMPROVEMENT WORKS TO COMMERCIAL BUILDING (LIC OFFICE ) AT NEW STREET IN DIV -160 U-35 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/5327,Buildings,Completed,NM-ALANDUR,160,88000,"CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREETS IN DIV-160, UNIT-35, ZONE-12",Own Sources,12,2017-18,2017-18 NM/2017-18/6538,Electrical,Completed,NM-ALANDUR,160,460800,"Laying of 240 mtrs of 4x16 sq mm PVC Alu Cable and Clamping of cable at bridges portion with 12 nos of 150-165W LED Fittings at Kathipara Bridges in Div 160,Zone XII",Own Sources,12,2017-18,2017-18 NM/2017-18/6539,Electrical,Completed,NM-ALANDUR,160,975200,"Erection of 16 nos of 8 mtr street Lamp Posts with single bracket and 150-165W LED Watts LED Fittings at G.S.T Road near Alandhur metro station and opposite to Metro rail station in Div 160, Zone XII.",Own Sources,12,2017-18,2017-18 NM/2017-18/7202,Buildings,Completed,NM-ALANDUR,160,321000,"Improvement works to Amma Unavagam at M.K.N road in Div-160, Unit-35, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7888,Roads,Completed,NM-ALANDUR,160,320000,"ATTENDING ROAD CUT RESTORATION MADE BY TRANGEDCO AT SANYASI SUBEDHER STREET IN DIV-160, U-35, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7891,Roads,Completed,NM-ALANDUR,160,386000,"ATTENDING ROAD CUT RESTORATION MADE BY TRANGEDCO AT SOWRI STREET IN DIV-160, U-35, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7892,Roads,Completed,NM-ALANDUR,160,326000,"ATTENDING ROAD CUT RESTORATION MADE BY TRANGEDCO AT VEMBULI SUBEDHER STREET IN DIV-160, U-35, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7893,Roads,Completed,NM-ALANDUR,160,317000,"ATTENDING ROAD CUT RESTORATION MADE BY TRANGEDCO AT VEMBULI AMMAN KOIL STREET IN DIV-160, U-35, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7894,Roads,Completed,NM-ALANDUR,160,292000,"ATTENDING ROAD CUT RESTORATION MADE BY TRANGEDCO AT VENU STREET IN DIV-160, U-35, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8823,Buildings,Completed,NM-ALANDUR,160,358000,REPAIR AND IMPROVEMENT WORKS TO NIGHT SHELTER(RTO OFFICE) AT NEW STREET IN DIV 160 U-35 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/9023,Storm Water Drain,Completed,NM-ALANDUR,160,199000,DESILTING OF STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREET IN DN 160 U 35 Z 12.,Own Sources,12,2017-18,2017-18 NM/2017-18/9281,Buildings,Completed,NM-ALANDUR,160,26000,"Improvement works to Amma Unavagam at M.K.N Road in Div-160, U-35, Zn-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9647,Storm Water Drain,Completed,NM-ALANDUR,160,444000,"IMPROVEMENT WORKS TO SIDE DRAIN AT MKN ROAD ,CONSTRUCTION OF NEW CULVERT AT NEW STREET AND CONSTRUCRTION OF NEW DRAIN AT LAWYER JAGANATHAN STREET IN DIV -160 U -35 Z -12",Own Sources,12,2017-18,2018-19 NM/2017-18/9685,Electrical,Completed,NM-ALANDUR,160,563000,"AMC of 100KVA Generator functioning in Gandhi Hospital Div 160, (Zone-XII) , AMF panel for 100KVA Generator in Gandhi Hospital, 25KVA Generator in Gandhi Hospital and 25 KVA Generator in K.K.Nagar Hospital Div 166, (Z XII) for a period of one year",Own Sources,12,2017-18,2019-20 NM/2017-18/9687,Electrical,Completed,NM-ALANDUR,160,365000,"AMC of 100KVA Generator functioning in Zonal Office (Zone-XII) , AMF panel for 100KVA Generator in Zonal Office (Zone- XII) and 5 KVA mobile DG set in Zonal office (Z XII) for a period of one year",Own Sources,12,2017-18,2019-20 NM/2017-18/9837,Buildings,Completed,NM-ALANDUR,160,21400,ADDITIONAL IMPROVEMENT WORKS AT ANGANVAADI IN VEMBULIAMMAN KOVIL STREET IN DN-160 U-35 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/9838,Buildings,Completed,NM-ALANDUR,160,492000,ADDITIONAL IMPROVEMENT WORKS AT ANGANVAADI IN MUTHAMJI STREET IN DN-160 U-35 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/9892,Storm Water Drain,Completed,NM-ALANDUR,160,63000,REPAIR TO STROM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREET IN DIV-160 U -35 Z-12,Own Sources,12,2017-18,2017-18 NM/2017-18/0177,Buildings,Completed,NM-ALANDUR,161,12000,"Dismantling the dilaprated Ration Shop Building at South Raja Street in dn-161,u-36,z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/0206,Buildings,Completed,NM-ALANDUR,161,46000,"MAINTENANCE AND REPAIRS WORKS TO PC AT RAJA STREET IN DN-161,U-36,Z-XII",Own Sources,12,2017-18,2017-18 NM/2017-18/0207,Buildings,Completed,NM-ALANDUR,161,41000,"IMPROVEMENTS WORKS TO GYM BUILDING AT SOUTH RAJA STREET IN DN-161,U-36,Z-XII",Own Sources,12,2017-18,2017-18 NM/2017-18/0213,Parks,Completed,NM-ALANDUR,161,11000,"MAINTENANCE WORKS TO JEEVAN NAGAR PARK IN DN-161,U-36,Z-XII",Own Sources,12,2017-18,2018-19 NM/2017-18/11670,Roads,Completed,NM-ALANDUR,161,131000,"REPAIRS AND MAINTENANCE OF PARKS AND ATTENDING PATCH WORK IN DIVISION-161, UNIT-36,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/12670,Buildings,Completed,NM-ALANDUR,161,34000,"REPAIR AND MAINTANANCE WORK AT RAJA STREET PUBLIC CONVENIENCE IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12719,Buildings,Completed,NM-ALANDUR,161,273000,"PROPOSED OPEN GYM AT TNGO COLONY PARK IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12801,Buildings,Completed,NM-ALANDUR,161,114000,"REPAIR AND MAINTANANCE WORK AT OFFICER COLONY PARK IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12804,Buildings,Completed,NM-ALANDUR,161,25000,"REPAIR AND MAINTANANCE WORK AT TNGO COLONY PARK IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12808,Buildings,Completed,NM-ALANDUR,161,25000,"REPAIR AND MAINTANANCE WORK AT JEEVAN NAGAR PARK IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12810,Buildings,Completed,NM-ALANDUR,161,40000,"REPAIR AND MAINTANANCE WORK AT MURUGAN NAGAR PARK IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/15464,Buildings,Completed,NM-ALANDUR,161,382000,"CONSTRUCTION OF BABY FRIENDLY TOILET AND IMPROVEMENT WORKS IN ANGANVADI AT RAJA STREET NO:18 IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/15468,Buildings,Completed,NM-ALANDUR,161,382000,"CONSTRUCTION OF BABY FRIENDLY TOILET AND IMPROVEMENT WORKS IN ANGANVADI AT VOC NAGAR IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/16441,Buildings,Completed,NM-ALANDUR,161,209000,"REPAIR AND MAINTANANCE WORK IN ANGANVADI AT VELACHERY ROAD IN DN-161,U-36,Z-XII",Own Sources,12,2017-18,2018-19 NM/2017-18/16733,Electrical,Completed,NM-ALANDUR,161,894400,"Replacement of18 nos of 10- 20 w led fittings and 652 mtr of 2x16 sq mm cable at jeevan nagar park,murugan nagar park,officers colony park and TNGO Colony park DN 161 ZONE 12",Own Sources,12,2017-18,2018-19 NM/2017-18/1827,Roads,Completed,NM-ALANDUR,161,102000,"IMPROVEMENT WORKS TO EXISTING SPEED BREAKER AT VARIOUS STREET IN DIVISION-161, UNIT-36,ZONE-12.",Own Sources,12,2017-18,2017-18 NM/2017-18/2529,Buildings,Completed,NM-ALANDUR,161,33000,"REPAIRS WORKS TO AMMA UNAVAGAM AT RAJA STREET 1ST LANE IN DN-161,U-36,Z-XII",Own Sources,12,2017-18,2018-19 NM/2017-18/3967,Buildings,Completed,NM-ALANDUR,161,150000,"IMPROVEMENT WORKS TO GROUP BIN PLATFORM AT VARIOUS STREET IN DN-161,U-36,Z-XII",Own Sources,12,2017-18,2017-18 NM/2017-18/6796,Parks,Completed,NM-ALANDUR,161,155000,"ANNUAL MAINTENANCE OF PARK AT TNGO COLONY,MURUGAN NAGAR,JEEVAN PARKS IN DN-161,U-36,Z-XII(PERIOD FOR ONE YEAR)",Own Sources,12,2017-18,2018-19 NM/2017-18/6798,Parks,Completed,NM-ALANDUR,161,163000,"ANNUAL MAINTENANCE OF PARK AT OFFICER COLONYS PARK IN DN-161,U-36,Z-XII(PERIOD FOR ONE YEAR)",Own Sources,12,2017-18,2018-19 NM/2017-18/7637,Buildings,Completed,NM-ALANDUR,161,52566,"SUPPLYING AND FIXING OF WATER TANK AT VOC NAGAR PC ON DN-161,U-36,Z-XII",Own Sources,12,2017-18,2018-19 NM/2017-18/8526,Storm Water Drain,Completed,NM-ALANDUR,161,82000,"REPAIR AND MAINTANANCE WORK OF SWD IN DN-161,UN-36,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/8997/C,Storm Water Drain,Completed,NM-ALANDUR,161,150000,"DESILTING FOR VARIOUS STREET IN DN-161,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/0150,Buildings,Completed,NM-ALANDUR,162,160000,"CONSTRUCTION OF COMPOUND WALL AND IMPROVEMENT WORKS TO MULTI PURPOSE HALL AT THILLAI GANGA NAGAR 6TH MAIN ROAD IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/12418,Parks,Completed,NM-ALANDUR,162,42000,"REPAIRS WORKS TO THILLAIGANGA NAGAR 34TH STREET AND THIRUVALLUVAR NAGAR PARK IN DIVISION-162,UNIT-36,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12767,Buildings,Completed,NM-ALANDUR,162,22000,"IMPROVEMENT WORKS TO NAMMA TOILET AT THILLAIGANGA NAGAR 4TH MAIN ROAD IN DIVISION-162,UNIT-36,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13211,Buildings,Completed,NM-ALANDUR,162,460000,"SUPPLYING AND ERECTION OF NEW CHIMNEY AT KANNAN COLONY CREMATORIUM IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/14228,Roads,Completed,NM-ALANDUR,162,4145000,"STRENGTHENING AND LAYING BT ROAD AT MARRISON 5TH STREET, THIRUVALLUVAR MAIN ROAD,5TH STREET IN DN-162,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/2541,Buildings,Completed,NM-ALANDUR,162,49000,"REPAIR AND MAINTENANCE WORKS TO EXISTING AMMA UNAVAGAM AT THILLAIGANGA NAGAR 1ST MAIN ROAD AND MKN ROAD IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/2543,Parks,Completed,NM-ALANDUR,162,160000,"IMPROVEMENT WORKS TO UNDER GROUND SUMP AT THIRUVALLUR NAGAR PARK IN DIVISION-162,UNIT-36, ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/2548,Parks,Completed,NM-ALANDUR,162,160000,"IMPROVEMENT WORKS TO UNDER GROUND SUMP AT THILLAI GANGA NAGAR 34TH STREET PARK IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/2926,Buildings,Completed,NM-ALANDUR,162,291000,"ALTERATION AND IMPROVEMENT WORK IN EXISTING UNUSED P.C TOILET TO CONVERT LABOUR REST ROOM AND STORE ROOM AT NOBLE 1ST STREET IN DN-162,U-36,Z-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/3983,Roads,Completed,NM-ALANDUR,162,139000,"PROVIDING BIN PLATFORM AT VARIOUS STREET IN DN-162,U-36,Z-12.",Own Sources,12,2017-18,2017-18 NM/2017-18/7955,Buildings,Completed,NM-ALANDUR,162,18800,"SUPPLYING AND FIXING INSTRUCTION NAME BOARD AT KANNAN COLONY CREMATORIUM IN DN- 162, U- 36, Z- 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/8042,Parks,Completed,NM-ALANDUR,162,216000,"ANNUAL MAINTENANCE OF PARK AT THILLAI GANGA NAGAR 33RD STREET PARK AND THIRUVALLUVAR NAGAR 1ST STREET PARK IN DN-162,UNIT-36,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8080,Buildings,Completed,NM-ALANDUR,162,110000,"REPAIRS AND IMPROVEMENT TO GYM AT KANNAN COLONY AND MORRISION 1ST STREET IN DN DN-162, U-36, Z-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/8497,Storm Water Drain,Completed,NM-ALANDUR,162,171000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREES (25Streets) IN DIVISION 162,UNIT 36,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/9005,Storm Water Drain,Completed,NM-ALANDUR,162,32000,"REPAIRS WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION- 162, UNIT-36, ZONE-12.",Own Sources,12,2017-18,2017-18 NM/2017-18/9284,Buildings,Completed,NM-ALANDUR,162,338000,"CONSTRUCTION OF ANGANWADI BABY TOILET AT KANNAN COLONY IN DN 162 , U-36, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/9329,Buildings,Completed,NM-ALANDUR,162,180000,"IMPROVEMENTS ARRANGEMENT AND WATER SUPPLY IN ANGANVADI CENTER AT KANNAN COLONY IN DIVISION-162,UNIT-36,ZONE-12",Own Sources,12,2017-18,2018-19 BR/2017-18/3084,Road Cut,Completed,BR-Bus Route Roads,163,67000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT LAKE VIEW ROAD IN DIV - 163 , ZONE - 12",Deposit Works,12,2017-18,2018-19 NM/2017-18/0188,Buildings,Completed,NM-ALANDUR,163,50000,REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE AT BALAKRISHNAPURAM 1ST STREET IN DN-163 U-36 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/0242,Buildings,Completed,NM-ALANDUR,163,579000,"IMPROVEMENT OF ANGANVADI BUILDING AT PARTHASARATHY NAGAR 8TH EXT IN DN-163,U-36,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/10701,Roads,Completed,NM-ALANDUR,163,384217,"RELAYING ROAD BY USING PAVER FINISHER AT BALAKRISHNAPURAM 3RD STREET IN DIV - 163,UNIT - 37,ZONE - XII",Own Sources,12,2017-18,2018-19 NM/2017-18/10703,Roads,Completed,NM-ALANDUR,163,400811,"RELAYING THE ROAD BY USING PAVER FINISHER AT BALAKRISHNAPURAM 4TH STREET IN DIV - 163, UNIT - 37, ZONE - 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/12994,Buildings,Completed,NM-ALANDUR,163,87000,REPAIR WORKS AND PROVIDING MOTOR ROOM TO P.C. AT MANNADIAMMAN KOIL STREET IN DN 163 U.37 Z.12,Own Sources,12,2017-18,2018-19 NM/2017-18/12995,Storm Water Drain,Completed,NM-ALANDUR,163,160000,"PROVIDING INLET CHAMBER AT BALAKRISHNAPURAM MAINROAD(NEAR JN OF BALAKRISHNAPURAM 3TH STREET AND JN OF PARAMESWARAN NAGAR 3TH STREET,AND REPAIRS WORKS TO S.W.D AT VARIOUS STREET IN DN-163 U-37 Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14391,Buildings,Completed,NM-ALANDUR,163,126000,CONVERSANAL WORK OF TOILET TO COMPOSED YARD STORE ROOM AT BALAKRISHNAPURAM BURIAL GROUND IN DN 163 U.37 Z.12,Own Sources,12,2017-18,2018-19 NM/2017-18/14544,Buildings,Completed,NM-ALANDUR,163,789000,"SUPPLYING AND ERECTION OF NEW CHIMNEY WORK AT BALAKRISHNAPURAM GASIFIER CREMATORIUM IN DIV -163 , U-37, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/16060,Buildings,Completed,NM-ALANDUR,163,81000,REPAIR AND MAINTANANCE WORK OF SWD IN DIV-163 U-37 Z-12,Own Sources,12,2017-18,2017-18 NM/2017-18/1714,Roads,Completed,NM-ALANDUR,163,170000,PROVIDING THERMO PLASTIC PAINTING TO THE EXISTING SPEED BREAKER AT VARIOUS STREET IN DN-163 U-36 Z-12,Own Sources,12,2017-18,2017-18 NM/2017-18/2334,Parks,Completed,NM-ALANDUR,163,161000,CONSTRUCTION OF SUMP AND REPAIR WORKS TO PARK AND CHILDREN PLAY FIELD AT SHANTHI NAGAR 4TH STREET IN DN-163 U-36 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/2387,Roads,Completed,NM-ALANDUR,163,270000,Providing Plate Form for the Proposed E-Toilet at Medavakkam high road( jn of jeevan Nagar 5th street) in dn-163 u-36 z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/2790,Buildings,Completed,NM-ALANDUR,163,157000,"Construction of Sump and Repairs works at Medavakkam High Road Ammaunavagam in Dn-163,U-36.Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/2824,Buildings,Completed,NM-ALANDUR,163,31600,Repair and Maintenance works to Balakrishnapuram Ammaunavagam in Dn-163 U-36 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/2829,Buildings,Completed,NM-ALANDUR,163,133000,Repair Works to UPHC Building at mannadiyamman koil street in Dn-163 U-36 Z-2,Own Sources,12,2017-18,2018-19 NM/2017-18/3594,Buildings,Completed,NM-ALANDUR,163,79000,ADDITIONAL IMPROVEMENT TO ANGANVADI BUILDING AT MANNADIYAMMAN KOIL STREET IN DN 163 U 36 Z 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/3601,Buildings,Completed,NM-ALANDUR,163,140000,ADDITIONAL IMPROVEMENT TO ANGANVADI BUILDING AT PARAMESHVARAN NAGAR 3RD STREET IN DN163 U 36 Z12.,Own Sources,12,2017-18,2018-19 NM/2017-18/5192,Footpath,Completed,NM-ALANDUR,163,76000,PROVIDING BIN PLATFORM AT VARIOUS STREETS IN DN 163,Own Sources,12,2017-18,2017-18 NM/2017-18/7917,Buildings,Completed,NM-ALANDUR,163,18800,SUPPLYING AND FIXING INSTRUCTION NAME BOARD AT BALAKRISHNAPURAM BURIAL GROUND IN DN-163 U-36 Z-12.,Own Sources,12,2017-18,2018-19 NM/2017-18/8068,Parks,Completed,NM-ALANDUR,163,137000,ANNUAL MAINTENANCE OF PARK AT SHANTHI NAGAR 4TH STREET PARK IN DIV 163 UNIT 36 ZONE 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/9493,Buildings,Completed,NM-ALANDUR,163,30000,ADDITIONAL IMPROVEMENT TO ANGANVADI BUILDING AT PILLAYAR KOIL STREET IN DN-163 U-36 Z-12.,Own Sources,12,2017-18,2018-19 NM/2017-18/9858,Storm Water Drain,Completed,NM-ALANDUR,163,197000,Desilting of strom water Drain and side drain at various streets in Dn-163 U-36 Z-12,Own Sources,12,2017-18,2018-19 NM/2017-18/0249,Parks,Completed,NM-ALANDUR,164,246000,"Construction of compound wall at Nehru street park in Division -164, Unit-37, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/0267,Buildings,Completed,NM-ALANDUR,164,495000,"Additional improvement works to UPHC at New colony 2nd street in Division-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/12468,Parks,Completed,NM-ALANDUR,164,56000,"REPAIR AND MAINTENANCE WORKS TO CHILDRENS PARK AT NANGANALLUR 29TH STREET in DN-164,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13000,Buildings,Completed,NM-ALANDUR,164,63000,"MAINTENANCE WORKS TO DIVISION OFFICE BUILDING AT KRISHNA SWAMY STREET IN DN-164,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13063,Buildings,Completed,NM-ALANDUR,164,164000,"Repair works to school building (CPS) at Vembuliamman koil street in Divisionn-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/14219,Roads,Completed,NM-ALANDUR,164,1248000,"IMPROVEMENT TO EXISTING OF BT ROAD AT ELLAIMUTHAMMAN KOIL STREET IN DN-164,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14221,Roads,Completed,NM-ALANDUR,164,375000,"IMPROVEMENT TO EXISTING OF BT ROAD AT NANGANALLUR 14TH STREET IN DN-164,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14229,Roads,Completed,NM-ALANDUR,164,171000,"IMPROVEMENT TO EXISTING OF CC ROAD AT SATHANAR STREET IN DN-164,U-37,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/17125,Roads,Completed,NM-ALANDUR,164,399000,"HIRE CHARGES OF MOTORS (5HP AND 10HP) FOR DE WATERING THE RAIN WATER IN DN-161& 162,U-36,Z-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/17238,Roads,Completed,NM-ALANDUR,164,81000,"REPAIR AND MAINTENANCE WORKS OF SWD AT VARIOUS STREET IN DN-164, UNIT-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/17240,Roads,Completed,NM-ALANDUR,164,272000,"HIRE CHARGES OF MOTOR(5HP) FOR DEWATERING RAIN WATER IN DN-163,164,165,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/17244,Roads,Completed,NM-ALANDUR,164,120000,"REPAIRS AND MAINTENANCE OF PARKS, EXISTING CORPORATION BUILDINGS AND SWD IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/2405,Buildings,Completed,NM-ALANDUR,164,90000,"Improvemennt works to Amma unavagam at Krishnasamy street in Division-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/3262,Buildings,Completed,NM-ALANDUR,164,92000,"Improvement works to Amma unavagam at Nanganallur 4th main road in Division-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/3858,Buildings,Completed,NM-ALANDUR,164,112000,"Improvement works to Bin platform at various street in Division - 164, Unit -37, Zone-12.",Own Sources,12,2017-18,2017-18 NM/2017-18/4045,Buildings,Completed,NM-ALANDUR,164,90000,"Improvement works to 16th Day Ceremony Hall at Nanganallur 4th main road in Division-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/6861,Parks,Completed,NM-ALANDUR,164,29000,"Improvement works to Childrens park and repair works to play materials at Nanganallur 29th street park in division-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/8049,Parks,Completed,NM-ALANDUR,164,156000,"Annual maintenance works to Childrens park at Nehru street park and Nanganallur 29th street park Iin Dn-164, Unit-37, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8114,Parks,Completed,NM-ALANDUR,164,214000,"Improvement works to Childrens park and repair works to play materials at Nehru street park in division-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/8811,Storm Water Drain,Completed,NM-ALANDUR,164,170000,"Desilting of storm water drain at Naganallur Areas various street in dn-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2017-18 NM/2017-18/8874,Buildings,Completed,NM-ALANDUR,164,265000,"Construction of Baby friendly toilet in Angawadi at Ellaimuthamman koil street in Dn-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/9390,Storm Water Drain,Completed,NM-ALANDUR,164,355000,"Repair works to Storm water drain at various streets in Dn-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2017-18 NM/2017-18/9634,Buildings,Completed,NM-ALANDUR,164,125000,"Maintenance works for Annganwadi at Ellaimuthamman koil street and New colony 2nd street in Division-164, Unit-37, Zone-12.",Own Sources,12,2017-18,2018-19 BR/2017-18/1196,Road Cut,Completed,BR-Bus Route Roads,165,2300000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BALAJI NAGAR MAIN ROAD FROM RADIAL ROAD TO KURUNJI STREET IN DIV 165 , ZONE - 12",Deposit Works,12,2017-18,2017-18 BR/2017-18/1197,Road Cut,Completed,BR-Bus Route Roads,165,2300000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT BALAJI NAGAR MAIN ROAD FROM MAHALAKSHMI NAGAR MAIN ROAD TO KURUNJI STREET IN DIV 165 , ZONE - 12",Deposit Works,12,2017-18,2017-18 BR/2017-18/4298,Road Cut,Completed,BR-Bus Route Roads,165,534000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -11,Deposit Works,12,2017-18,2018-19 NM/2017-18/0152,Buildings,Completed,NM-ALANDUR,165,372000,"Improvement works to New colony burial ground in division-165,unit-37,zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/0292,Parks,Completed,NM-ALANDUR,165,163000,"Providing Bore well and other improvement works at Surendra nagar park in Din 165,Unit 37,Zone 12.",Own Sources,12,2017-18,2017-18 NM/2017-18/10404,Buildings,Completed,NM-ALANDUR,165,177400,Improvement works to Bharath nagar park in DIV 165 Unit 37 Zone 12,Own Sources,12,2017-18,2018-19 NM/2017-18/10414,Buildings,Completed,NM-ALANDUR,165,204900,Improvement works to Division office at Nanganallur 8th street in division 165 unit 37 zone 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/10616,Buildings,Completed,NM-ALANDUR,165,466000,"REPAIR AND MAINTENANCE OF PARKS, PUBLIC CONVENIENCE, GCC BUILDINGS AND OTHER IMPROVEMENT WORKS IN DIVISION 165,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/10617,Buildings,Completed,NM-ALANDUR,165,158900,"IMPROVEMENT WORKS TO PC AT NANGANALLUR 11TH STREET IN DIVISION 165,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/10619,Storm Water Drain,Completed,NM-ALANDUR,165,50000,"Desilting of Storm water drains and Culverts at Various streets in Div 165,Unit 37,Zone 12.",Own Sources,12,2017-18,2017-18 NM/2017-18/12443,Parks,Completed,NM-ALANDUR,165,89800,REPAIR AND MAINTENANCE OF PARK AT SURENDRA NAGAR 3RD STREET IN DIVISION 165 UNIT 37 ZONE 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/12444,Parks,Completed,NM-ALANDUR,165,68600,REPAIR AND MAINTENANCE OF PARK AT NETHAJI STREET IN DIVISION 165 UNIT 37 ZONE 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/12445,Parks,Completed,NM-ALANDUR,165,106100,REPAIR AND MAINTENANCE OF PARK AT BALAJI NAGAR 10TH STREET IN DIVISION 165 UNIT 37 ZONE 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/12446,Parks,Completed,NM-ALANDUR,165,25700,REPAIR AND MAINTENANCE OF PARK AT LAKSHMI NAGAR 1ST STREET IN DIVISION 165 UNIT 37 ZONE 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/12447,Parks,Completed,NM-ALANDUR,165,82400,"IMPROVEMENT WORKS TO ROAD SIDE PARK AT NANGANALLUR 11TH STREET IN DIVISION 165 UNIT 37, ZONE 12",Own Sources,12,2017-18,2018-19 NM/2017-18/13002,Buildings,Completed,NM-ALANDUR,165,536000,"LAYING CC ROAD USING RMC M30 GRADE AT SUNDRAMOORTHY STREET IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2017-18,2019-20 NM/2017-18/14478,Buildings,Completed,NM-ALANDUR,165,205000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 2ND CROSS STREET IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/14479,Buildings,Completed,NM-ALANDUR,165,98000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT KESARI NAGAR 2RD STREET IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/15096,Buildings,Completed,NM-ALANDUR,165,172000,Construction of Baby friendly toilet in Anganvadi at Vanuvampet in DIV 165 Unit 37 Zone 12,Own Sources,12,2017-18,2019-20 NM/2017-18/15102,Roads,Completed,NM-ALANDUR,165,525000,"PROVIDING AWARNESS BOARD FOR GARBAGE DUMPING AREA IN DIVISION 161 TO 167,UNIT 36 AND 37,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/16710,Electrical,Completed,NM-ALANDUR,165,259500,"Conversion of 4 nos of CFL into 40W-50W LED fittings at Surendar nagar park, Removal of 6 nos of damaged lamp posts in Balaji Nagar 10th street park ,Removal of 5 nos of damaged lamp posts in Lakshmi Nagar park, Conversion of 15 Nos of 11W CFL into 20W LED fittings and removal of damaged posts in Barath Nagar Park, Conversion of 9 Nos of 11W CFL into 10W-20W LED fittings and availing TNEB supply at Nethaji Street Park, Div - 165, Z-XII",Own Sources,12,2017-18,2018-19 NM/2017-18/2751,Buildings,Completed,NM-ALANDUR,165,165000,"IMPROVEMENT WORKS TO AMMA UNAVAGAM AT ( VANUVAMPET AND BALAJI NAGAR MAIN ROAD ) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/3939,Roads,Completed,NM-ALANDUR,165,66000,"Providing Compactor bin platform at various streets in Division-165, Unit-37, Zone-12.",Own Sources,12,2017-18,2017-18 NM/2017-18/4855,Roads,Completed,NM-ALANDUR,165,507000,"IMPROVEMENT WORKS TO SIDE DRAIN AT BHUVANESHWARI NAGAR 3RD STREET (Cover slab Precast slab at Size of 600 MM X 900 MM) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2017-18 NM/2017-18/5401,Roads,Completed,NM-ALANDUR,165,472000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT MUTHIYAL REDDY NAGAR MAIN ROAD (FOR THE SEWAGE FACILITIES ARRANGEMENTS TO INDIAN COASTAL GUARD MAIN BUILDING) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/5404,Roads,Completed,NM-ALANDUR,165,138000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT RAJA RAM STREET (FOR THE SEWAGE FACILITIES ARRANGEMENTS TO INDIAN COASTAL GUARD MAIN BUILDING) IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/6541,Electrical,Completed,NM-ALANDUR,165,455600,"Removal and refixing of 34 nos 6 mtr MS Lamp Posts and 2 nos 8 mtr MS Lamp Posts and 2 Nos KIOSK Pillar box at various locations due to construction of storm water drain in Div 164,165 & 167 in Zone XII.",Own Sources,12,2017-18,2017-18 NM/2017-18/6542,Electrical,Completed,NM-ALANDUR,165,510600,"Replacement of 285 mtrs of damaged 4x16 sq mm Alu cable and 810 mtrs of damaged 2x16 sq mm Alu cable and Removal and Refixing of 10 Nos of 6 mtr MS Street Lamp post at Elango st, Kesari Nagar 7th st and Various places in Div 165 , Zone XII",Own Sources,12,2017-18,2017-18 NM/2017-18/7871,Roads,Completed,NM-ALANDUR,165,125000,REPAIRS TO DAMAGED ROAD ( VARDHA CYCLONE ) AT BALAJI NAGAR 17TH STREET WEST IN DIVISION 165 UNIT 37 ZONE 12,Own Sources,12,2017-18,2017-18 NM/2017-18/7936,Parks,Completed,NM-ALANDUR,165,160000,"ANNUAL MAINTENANCE OF PARK AT BHARATH NAGAR AND NETHAJI STREET IN DN-165, UNIT-37,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7937,Parks,Completed,NM-ALANDUR,165,142000,"ANNUAL MAINTENANCE OF PARK AT SOUTH SECTOR AND SURENDRA NAGAR IN DN-165, UNIT-37,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/7938,Parks,Completed,NM-ALANDUR,165,152000,"ANNUAL MAINTENANCE OF PARK AT BALAJI NAGAR AND LAKSHMI NAGAR IN DN-165, UNIT-37,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8192,Buildings,Completed,NM-ALANDUR,165,263000,Construction of Baby friendly toilet in Anganvadi at Ram nagar in DIV 165 Unit 37 Zone 12,Own Sources,12,2017-18,2018-19 NM/2017-18/8197,Buildings,Completed,NM-ALANDUR,165,110000,IMPROVEMENT WORKS IN EXISTING ANGANVADI AT RAM NAGAR IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2017-18,2018-19 NM/2017-18/8393,Storm Water Drain,Completed,NM-ALANDUR,165,187900,"Desilting of storm water/Side darins at various streets ( Bharath nagar - 4 Streets,Nilamangai nagar- 8 streets,Kesari nagar 1st street,Income tax colony 1st street,Balaji nagar- 6 streets,Shakthi nagar - 3 streets,Vel nagar - 4 streets,Kundrakudi nagar - 4 streets,Sourth sector - 3 streets,New colony - 4 streets,Lakshmi nagar - 3 streets,Thiruvalluvar nagar - 3 streets,Surendra nagar - 2 streets) in Div 165,Unit 37,Zone 12.",Own Sources,12,2017-18,2017-18 NM/2017-18/8612,Storm Water Drain,Completed,NM-ALANDUR,165,17350,"REPAIR WORKS TO STORM WATER DRAIN AT VEL NAGAR EXTN MAIN ROAD AND INCOME TAX COLONY 1ST STREET IN DIVISION 165,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2017-18 NM/2017-18/10402,Buildings,Completed,NM-ALANDUR,166,22000,"REPAIR AND MAINTENANCE WORKS OF AMMA UNAVAGAM AT NEHRU NEDUNCHALAI IN DN-166, U-37, Z-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/10453,Buildings,Completed,NM-ALANDUR,166,30000,"REPAIR AND MAINTENANCE WORKS TO COMMUNITY HALL AT NEHRU COLONY MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/12038,Buildings,Completed,NM-ALANDUR,166,27100,"MAINTENANCE WORKS TO PC TOILET AT BURMATHAMIZAR COLONY IN DN-166,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12108,Buildings,Completed,NM-ALANDUR,166,869000,REPAIRS AND MAINTENANCE OF BIO METHONISATION PLANT IN EXISTING AMMA UNAVAGAM IN DN 166,Own Sources,12,2017-18,2018-19 NM/2017-18/12471,Parks,Completed,NM-ALANDUR,166,23800,"REPAIR AND MAINTENANCE WORK AT KK NAGAR MAIN ROAD PLAY FIELD IN DN-166,U-37,Z-12",Own Sources,12,2017-18,2019-20 NM/2017-18/12778,Buildings,Completed,NM-ALANDUR,166,40600,"IMPROVEMENT WORKS TO PUBLIC CONVINIENCE AT NEHRU HIGH ROAD IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/13005,Buildings,Completed,NM-ALANDUR,166,62800,"Improvements to Anganwadi at Nehru High Road in Div-166, Zone-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14338,Roads,Completed,NM-ALANDUR,166,1060000,"IMPROVEMENT TO EXISTING OF BT ROAD AT K K NAGAR MAIN ROAD IN DN-166,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14339,Roads,Completed,NM-ALANDUR,166,440000,"IMPROVEMENT TO EXISTING OF BT ROAD AT K K NAGAR 7TH STREET IN DN-166,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/17176,Road Cut,Completed,NM-ALANDUR,166,1241000,"RESTORATION OF BT ROAD CUT MADE BY CMWSSB AT NGO COLONY 4TH STREET, B.V. NAGAR 3RD MAIN ROAD, THIRU.VI.KA STREET, NEHRU NEDUNCHALAI (FOR THE SEWAGE FACILITIES ARRANGEMENTS TO INDIAN COASTAL GUARD MAIN BUILDING) IN DN - 166, U - 37, Z - 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/1731,Roads,Completed,NM-ALANDUR,166,108000,"PROVIDING THERMO PLASTIC COMPOUND OF EXISTING SPEED BREAKERS AT VARIOUS STREETS IN DIV 166,UNIT 37,ZONE 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/8070,Buildings,Completed,NM-ALANDUR,166,326000,"CONSTRUCTION OF BABY TOILET IN ANGANVADI AT K.K NAGAR MAIN ROAD IN DN-166,UNIT-37,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/8087,Parks,Completed,NM-ALANDUR,166,137000,"ANNUAL MAINTANANCE FOR PARK AT ANNA PARK IN DN-166,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8813,Storm Water Drain,Completed,NM-ALANDUR,166,111000,"DESILTING OF STORM WATER DRAIN AT RAGHUPATHY NAGAR 9TH STREET, B.V.NAGAR 7TH STREET, B.V.NAGAR 2ND STREET, B.V.NAGAR 1ST CROSS STREET, B.V.NAGAR 13TH STREET, GOVINDASAMY STREET, JOSEPH 2ND STREET, KAMARAJAR OODAI STREET, K.K.NAGAR MAIN ROAD, TEACHERS COLONY 1ST STREET, N.G.O COLONY 2ND STREET, NEHRU HIGH ROAD IN DN 166, UNIT 37, ZONE 12.",Own Sources,12,2017-18,2017-18 NM/2017-18/8816,Storm Water Drain,Completed,NM-ALANDUR,166,95000,"MINOR REPAIR WORK AT RAGHUPATHY NAGAR 9TH STREET, B.V.NAGAR 7TH STREET, B.V.NAGAR 2ND STREET, B.V.NAGAR 1ST CROSS STREET, B.V.NAGAR 13TH STREET, GOVINDASAMY STREET, JOSEPH 2ND STREET, KAMARAJAR OODAI STREET, K.K.NAGAR MAIN ROAD, TEACHERS COLONY 1ST STREET, N.G.O COLONY 2ND STREET, NEHRU HIGH ROAD IN DN 166, UNIT 37, ZONE 12.",Own Sources,12,2017-18,2017-18 BR/2017-18/11556,Roads,Completed,BR-Bus Route Roads,167,9520000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at M.G.R Road in Dn-167, Zone-XII",Grants,12,2017-18,2018-19 BR/2017-18/2160,Road Cut,Completed,BR-Bus Route Roads,167,437000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -12 ( 4617/2016 ),Deposit Works,12,2017-18,2019-20 D/2017-18/8015,Storm Water Drain,Completed,D-Storm Water Drains,167,746000,"Construction of storm water Drain culvert of size 900x900mm along Nanganallur 23rd Street,Nanganallur 46th Street,Lakshmi Nagar 56th Street,Lakshmi 6th Street in Dn-167 ,Zone-XII.",Own Sources,12,2017-18,2018-19 NM/2017-18/10376,Buildings,Completed,NM-ALANDUR,167,38000,"REPAIR AND MAINTENANCE WORKS OF AMMA UNAVAGAM AT B.V NAGAR 3RD MAIN ROAD IN DN-166, U-37, Z-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/11293,Storm Water Drain,Completed,NM-ALANDUR,167,860000,"CONSTRUCTION OF CROSS CULVERT IN M.G.R ROAD AT JN OF SOUTH B.V NAGAR 5TH STREET IN DN-167, U-36, Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/11475,Buildings,Completed,NM-ALANDUR,167,169000,"PROVINDING BORE WELL FOR E-TOILET AT NANGANALLUR 39th STREET IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12437,Parks,Completed,NM-ALANDUR,167,66000,"Repair and Maintenance work at Lakshmi nagar 7th street park at lakshmi nagar main road in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12439,Parks,Completed,NM-ALANDUR,167,9400,"Repair and Maintenance work at Vijay Avenue park in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12442,Parks,Completed,NM-ALANDUR,167,46000,"Repair and Maintenance work at kannan nagar 1st cross street park in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12448,Parks,Completed,NM-ALANDUR,167,44000,"Repair and Maintenance work at Voltas colony 3rd street park in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12449,Parks,Completed,NM-ALANDUR,167,26800,"Repair and Maintenance work at Kannan nagar 1st main road park in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12450,Parks,Completed,NM-ALANDUR,167,44000,"Repair and Maintenance work at kannika colony park at kannika colony 2nd street in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12451,Parks,Completed,NM-ALANDUR,167,124000,"Repair and Maintenance work at Indepandance day park at Nanganallur 5th main road in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12463,Parks,Completed,NM-ALANDUR,167,26800,"Repair and Maintenance work at Jain staff colony park in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/12464,Parks,Completed,NM-ALANDUR,167,72000,"Repair and Maintenance work at Civilaviation colony park at sriram colony in DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13732,Culvert,Completed,NM-ALANDUR,167,72000,"CONSTRUCTION OF MISSING LINK SWD AT KANNAN NAGAR 4TH CROSS STREET IN DIVISION-167,UNIT-36 ,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/13733,Culvert,Completed,NM-ALANDUR,167,72000,"CONSTRUCTION OF MISSING LINK SWD AT VOLTAS COLONY 6TH CROSS STREET IN DIVISION-167,UNIT-36 ,ZONE-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14152,Buildings,Completed,NM-ALANDUR,167,513000,"IMPROVEMENT TO THE EXISTING BUS TERMINUS AT HINDU COLONY 15TH STREET IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14222,Roads,Completed,NM-ALANDUR,167,163000,"IMPROVEMENT TO EXISTING OF BT ROAD AT KANNIGA COLONY 4TH STREET IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14223,Roads,Completed,NM-ALANDUR,167,1276000,"IMPROVEMENT TO EXISTING OF BT ROAD AT SARVAMANGALAM MAIN ROAD IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14224,Roads,Completed,NM-ALANDUR,167,340000,"IMPROVEMENT TO EXISTING OF BT ROAD AT BALAJI NAGAR 1ST STREET IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14225,Roads,Completed,NM-ALANDUR,167,936000,"IMPROVEMENT TO EXISTING OF BT ROAD AT NANGANALLUR 46TH CROSS STREET IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/14340,Roads,Completed,NM-ALANDUR,167,941000,"IMPROVEMENT TO EXISTING OF BT ROAD AT Ambedkar street (Nehru Colony) IN DN-166,U-37,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/16713,Electrical,Completed,NM-ALANDUR,167,993000,"Conversion of 14 nos of CFL fitting into 20 w LED fitting at 29th street Nanganallur Park in division-164,Supply and fixing of 8nos of tube light and 6nos of ceiling fan at KK nagar main road GYM in DIV-166,Erection of 12 nos of 3 mtrs GI lamp posts with single arch bracket with 20 watts LED fittings at Kk nagar main road play ground in division -166,Conversion of 10 nos of CFL fitting into 20 w LED fitting at 100 feet road GYM,nanganallur in division-167,Erection of 9 nos of 3 mtrs GI lamp posts with single arch bracket with 20 watts LED fittings at Vijaya avenue Park in division -167,Replacement of 212mtr 2cx16sqmm cable and 38mtr of 4cx16sqmm cable at Lakshmi nagar 7th street in DiV-167,Removal of 1no of 20 mtr Hymast in Independence park in DIV- 167IN Zone-XII.",Own Sources,12,2017-18,2018-19 NM/2017-18/17168,Road Cut,Completed,NM-ALANDUR,167,1973000,"RESTORATION OF BT ROAD CUT MADE BY CMWSSB AT HINDU COLONY 2ND MAIN ROAD,M.G.R ROAD CROSSING,AGS COLONY 1ST STREET, LAKSHMI NAGAR 9TH STREET(3RD STAGE), LAKSHMI NAGAR 10TH STREET,NANGANALLUR 100FT ROAD CROSSING LAKSHMI NAGAR 7TH STREET EXTN (FOR THE SEWAGE FACILITIES ARRANGEMENTS TO INDIAN COASTAL GUARD MAIN BUILDING) IN DN - 167, U - 36, Z - 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/17173,Roads,Completed,NM-ALANDUR,167,652000,"RESTORATION OF CC ROAD CUT MADE BY CMWSSB AT KANNIGA COLONY 1ST STREET, STATE BANK COLONY 1ST MAIN ROAD (FOR THE SEWAGE FACILITIES ARRANGEMENTS TO INDIAN COASTAL GUARD MAIN BUILDING) IN DN - 167, U - 36, Z - 12.",Own Sources,12,2017-18,2019-20 NM/2017-18/17243,Roads,Completed,NM-ALANDUR,167,293000,"REPAIRS AND MAINTENANCE OF PARKS, GCC BUILDING, SWD AND ATTENDING PATCH WORK IN DIVISION-167, UNIT-36,ZONE-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/2438,Roads,Completed,NM-ALANDUR,167,570000,"PROVIDING SPEED BREAKERS AT EAST MAIN ROAD, AYYAPPA NAGAR, VOLTAS COLONY 5TH STREET, TELEGRAPH COLONY IN DN - 167, U - 36, Z - 12.",Own Sources,12,2017-18,2018-19 NM/2017-18/2523,Buildings,Completed,NM-ALANDUR,167,138000,"REPAIR AND MAINTENANCE WORK AT AMMA UNNAVAGAM AT NANGANALLUR100FT ROAD IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/2528,Buildings,Completed,NM-ALANDUR,167,23000,"REPAIR AND MAINTENANCE WORK AT AMMA UNNAVAGAM AT KANNAN NAGAR 1ST MAIN ROAD IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/3737,Buildings,Completed,NM-ALANDUR,167,152000,"PROVIDING BIN PLATFORM AT VARIOUS STREET IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2017-18 NM/2017-18/3878,Buildings,Completed,NM-ALANDUR,167,51000,PROVIDING BIN PLATFORM AT VARIOUS STREETS IN DN-166 U-37 Z-12,Own Sources,12,2017-18,2017-18 NM/2017-18/6543,Electrical,Completed,NM-ALANDUR,167,346200,"Removal and refixing of 25 nos 6 mtr MS Lamp Posts and 2 Nos KIOSK Pillar box at various locations due to construction of storm water drain in Div 164,166 & 167 in Zone XII.",Own Sources,12,2017-18,2017-18 NM/2017-18/8036,Parks,Completed,NM-ALANDUR,167,452000,"ANNUAL MAINTANANCE FOR PARK AT INDEPENDENCE DAY PARK IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8041,Parks,Completed,NM-ALANDUR,167,148000,"ANNUAL MAINTANANCE FOR PARK AT VOLTAS COLONY3RD STREET,VOLTAS COLONY1ST STREET,KANNIKA COLONY PARK IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8043,Parks,Completed,NM-ALANDUR,167,139000,"ANNUAL MAINTANANCE FOR PARK AT KANNAN NAGAR 1ST CROSS STREET, KANNAN NAGAR 1ST MAIN ROAD PARK,IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8044,Parks,Completed,NM-ALANDUR,167,137000,"ANNUAL MAINTANANCE FOR PARK AT STATE BANK COLONY PARK,HINDU COLONY 26TH STREET,IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8045,Parks,Completed,NM-ALANDUR,167,137000,"ANNUAL MAINTANANCE FOR PARK AT NANGANALLUR 46TH STREET,SRIRAM CIVILAVIATION COLONY PARK, IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 NM/2017-18/8046,Buildings,Completed,NM-ALANDUR,167,137000,"Annual Maintenance of Park at LAKSHMI NAGAR 4TH STAGE & EAST MAIN ROAD in Dn.167,Unit-36,Zone-12(period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/8047,Parks,Completed,NM-ALANDUR,167,137000,"Annual Maintenance of Park at VIJAY AVENUE ,MMTC COLONY & JAIN STAFF COLONY in Dn.167,Unit-36,Zone-12(period for one year)",Own Sources,12,2017-18,2018-19 NM/2017-18/9011,Storm Water Drain,Completed,NM-ALANDUR,167,175000,"Desilting of storm water drain at Nanganallur Various street in Dn-167, Unit-36, Zone-12.",Own Sources,12,2017-18,2018-19 NM/2017-18/9383,Storm Water Drain,Completed,NM-ALANDUR,167,147000,"MINOR REPAIR WORKS TO STORM WATER DRAIN AT HINDU COLONY 6TH, 8TH, 15TH, 17TH AND 21ST CROSS STREET, TELEGRAPH COLONY, KANNAN NAGAR 3RD MAIN ROAD, VOLTAS COLONY 5TH STREET, VOLTAS COLONY MAIN ROAD, SBI COLONY 1ST MAIN ROAD, NANGANALLUR 46TH STREET IN DN - 167, U - 36, Z - 12.",Own Sources,12,2017-18,2017-18 NM/2017-18/9698,Roads,Completed,NM-ALANDUR,167,117000,"STRENGTHENING AND RELAYING BT ROAD AT KANNIKA COLONY 1ST STREET LANE AND KANNIKA COLONY 2ND STREET LANE IN DN-167,U-36,Z-12",Own Sources,12,2017-18,2018-19 BR/2017-18/2153,Road Cut,Completed,BR-Bus Route Roads,168,536000,"Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 ( 3760/2017,915/2016,3915/2016)",Deposit Works,14,2017-18,2018-19 BR/2017-18/2190,Road Cut,Completed,BR-Bus Route Roads,168,836000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 (4617/2016/1),Deposit Works,14,2017-18,2019-20 L/2017-18/12346,Electrical,Completed,L-Electrical,168,18629800,"Provision of 318 nos of 6 Mtr lamp post with Single Straight Bracket 40w-50w LED Fitting and 74 nos of 6 Mtr lamp post with Single Straight Bracket 90w-120w LED Fitting with hot dip zinc galvanising at various places in Division-168,169,183 and 187, Zone-XIV","Loans, Grants And Own Sources",14,2017-18,2018-19 NP/2017-18/12101,Buildings,Completed,NP-PERUNGUDI,168,254000,Repairs and Improvements to Usha nagar Burrial Ground in Dn 168 Unit 42 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12102,Buildings,Completed,NP-PERUNGUDI,168,71000,Repairs and Improvements to Amma Unavagam at Srinivasan nagar Dn 168 Unit 42 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12103,Buildings,Completed,NP-PERUNGUDI,168,71000,Repairs and Improvements to Amma Unavagam at Lakshmi nagar Dn 168 Unit 42 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12104,Buildings,Completed,NP-PERUNGUDI,168,485000,Repairs and Improvements to Anganwadi inside school at Nanganallure 6 th Main road Dn 168 Unit 42 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12866,Buildings,Completed,NP-PERUNGUDI,168,536500,"CONSTRUCTION OF 16TH DAY CEREMONY HALL AT THROWPATHY AMMAN KOVIL STREET IN DIV-168, UNIT-42, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/2936,Roads,Completed,NP-PERUNGUDI,168,168000,"PROVIDING THERMO PLASTIC COMPOUND MARKING AT PROPOSED SPEED BREAKERS AT VARIOUS STREET IN DN-168 U-42,Z-14",Own Sources,14,2017-18,2018-19 BR/2017-18/2191,Road Cut,Completed,BR-Bus Route Roads,169,772000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 (4617/2016/2),Deposit Works,14,2017-18,2019-20 L/2017-18/3741,Electrical,Completed,L-Electrical,169,399300,"Provision of 8 nos of 6 Mtr lamp post with Single Straight Bracket 40w-50w LED Fitting with hot dip zinc galvanising at Balaji nagar 33th street park in Division-169, Zone-XIV",Own Sources,14,2017-18,2018-19 L/2017-18/6574,Electrical,Completed,L-Electrical,169,710800,"Provision of 12 nos of 6mtr hot dip galvanized lamp post with 90 to 120 W LED fitting at Balaji nagar Burial ground, Division 169, Zone-14",Own Sources,14,2017-18,2018-19 L/2017-18/8136,Electrical,Completed,L-Electrical,169,521300,"Painting of 2160 nos of 6mtr lamp posts with single straight bracket, 301 nos of 6mtr lamp posts with single arch bracket, 59 nos of 9.2mtr lamp posts with Single arch bracket, 58 nos of 9.2mtr lamp posts withDouble Arch bracket, 129nos of 8mtr lamp posts with Single Straight bracket At Various Locations In division 168,169,187 and 190, Zone-XIV,",Own Sources,14,2017-18,2018-19 L/2017-18/9750,Electrical,Completed,L-Electrical,169,1170500,"Replacement of 1854 mtrs of 2 x 16 sqmm cable and 887 mtrs of 4 x 16 sqmm cable in various places in division 168,169,187 and 190, zone-14",Own Sources,14,2017-18,2017-18 NP/2017-18/0927,Buildings,Completed,NP-PERUNGUDI,169,300000,IMPROVEMENT TO CONTAINER ROOM AND RAISING COMPOUND WALL INSIDE THE ZONAL OFFICE IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/10036,Roads,Completed,NP-PERUNGUDI,169,832000,"SUPPLYING AND FIXING OF HUME PIPE AT SIVAPRAKASAM NAGAR 1st STREET, MULLAI STREET, SRINVASA NAGAR 3rd CROSS STREET and RAM NAGAR 9TH STREET, ANNAITHERASA NAGAR 11TH & 12TH STREET IN DN.169, U-42 , ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10216,Electrical,Completed,NP-PERUNGUDI,169,493500,"Proposed to Replace and Purchase of 22Nos of Ceiling Fan, 18Nos of Exhaust Fan, 5nos of Water Heater, 5Nos of UV/RO Plant, 1Nos of Pulvarizer, 4nos of Wall Mounting fan, 2Nos of Weighing Machine, 2Nos of freezer and 1Nos of mixer in Amma Unavagam in Dn-168,169,183 to 191 in Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10294,Parks,Completed,NP-PERUNGUDI,169,774000,"REPAIRS AND IMPROVEMENTS WORK AT EPR NAGAR IN DN-169,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10295,Parks,Completed,NP-PERUNGUDI,169,63000,"REPAIRS AND IMPROVEMENTS WORK AT ANNAI THERASA NAGAR PARK IN DN-169,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10296,Parks,Completed,NP-PERUNGUDI,169,521000,"REPAIRS AND IMPROVEMENTS WORK AT BALAJI NAGAR 19TH STREET IN DN-169,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10297,Parks,Completed,NP-PERUNGUDI,169,266000,"REPAIRS AND IMPROVEMENTS WORK AT AGS COLONY PARK IN DN-169,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10298,Parks,Completed,NP-PERUNGUDI,169,293000,"REPAIRS AND IMPROVEMENTS WORK AT HINDU COLONY IN DN-169,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10677,Electrical,Completed,NP-PERUNGUDI,169,57600,"PROVISION OF 11 NOS OF MEGAPHONE FOR DIVISION-168,169,183 TO 191, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10713,Roads,Completed,NP-PERUNGUDI,169,12838000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RAMALINGAM NAGAR MAIN ROAD IN ZONE-14,U-42,DN-169",Own Sources,14,2017-18,2019-20 NP/2017-18/10721,Roads,Completed,NP-PERUNGUDI,169,2201000,"FORMATION OF NEW BT ROAD AT GANGAI STREET IN DN-169, U-42,Z-14",Own Sources,14,2017-18,2019-20 NP/2017-18/10732,Roads,Completed,NP-PERUNGUDI,169,1837000,"FORMATION OF NEW CC ROAD AT ANNAI THERESA NAGAR 1ST STREET IN DN-169,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10735,Roads,Completed,NP-PERUNGUDI,169,1482000,"FORMATION OF NEW CC ROAD AT ANNAI THERESA NAGAR 2ND STREET IN DN-169,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10800,Roads,Completed,NP-PERUNGUDI,169,669000,"FORMATION OF NEW CC ROAD AT ANNAI THERESA NAGAR 4TH STREET IN DN-169, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/12105,Buildings,Completed,NP-PERUNGUDI,169,66000,Repairs and Improvements to Amma Unavagam at Kalaimagal street Dn 169 Unit 42 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12106,Buildings,Completed,NP-PERUNGUDI,169,137000,Repairs and Improvements to Amma Unavagam at Puzhuthivakkam Bus stop Dn 169 Unit 42 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12107,Buildings,Completed,NP-PERUNGUDI,169,188000,Repairs and Improvements to Burrial Ground at Ramalingam nagar Dn 169 Unit 42 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12467,Buildings,Completed,NP-PERUNGUDI,169,500000,"Construction of 16th day Cermony hall 6m x 5m of size at Gangai Amman Kulam in Dn-169, Unit-42, Zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/12501,Buildings,Completed,NP-PERUNGUDI,169,76500,"Maintance & Repair Work at Toilet, Water Arrangement & Improvement for Primary School at Ravanan Nagar in div 169, Unit-42, Zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/12965,Buildings,Completed,NP-PERUNGUDI,169,199000,"CONSTRUCTION OF BABY TOILET IN ANGANVADI AT RAVANAN NAGAR IN DN-169, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/13006,Electrical,Completed,NP-PERUNGUDI,169,615900,"Supply and Erection of 1 no of LT Panel Board with 5 nos of 3 phase distribution board in zonal office, division-169, zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/15284,Roads,Completed,NP-PERUNGUDI,169,461500,"Providing new speed breaker as per IRC standard with bituminous concrete and also fixing sign board and studs at various street in dn-169,un-42,zone-14",Own Sources,14,2017-18,2019-20 NP/2017-18/15294,Buildings,Completed,NP-PERUNGUDI,169,591000,"Construction of New Toilet,Mesh & Painting works in Library building at Sheela Nagar,Dn-169, Unit-42,.Zone14",Own Sources,14,2017-18,2019-20 NP/2017-18/15309,Buildings,Completed,NP-PERUNGUDI,169,1218000,"CONSTRUCTION OF NEW TOILET,SUMP (6.00mx4.00m) AT ZONAL OFFICE IN DN 169,U-42,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/16019,Buildings,Completed,NP-PERUNGUDI,169,120000,"REPAIRS AND IMPROVEMENTS TO UAC TOILET BLOCK AT ZONAL OFFICE BUILDING IN DN.169, UNIT-42, Z.14",Own Sources,14,2017-18,2018-19 NP/2017-18/16021,Buildings,Completed,NP-PERUNGUDI,169,365000,"CONSTRUCTION OF SHED AT REAR SIDE OF ZONAL OFFICE IN DN.169, U.42, Z.14.",Own Sources,14,2017-18,2018-19 NP/2017-18/16025,Buildings,Completed,NP-PERUNGUDI,169,178500,"IMPROVEMENTS AND REPAIRS CI AND ELECTRICAL ROOM AT ZONAL OFFICE DN 169, U 42, Z 14.",Own Sources,14,2017-18,2018-19 NP/2017-18/16411,Parks,Completed,NP-PERUNGUDI,169,918000,"PROPOSED CHILDREN PLAY FIELD AT BALAJI NAGAR PHASE III EXTN (NORTH) IN DN-169, U-42, Z-14",Own Sources,14,2017-18,2019-20 NP/2017-18/5309,Roads,Completed,NP-PERUNGUDI,169,1113000,"PROVIDING THERMOPLAST PAINTING WORK TO EXISTING SPEED BREAKER (140 LOCATIONS) IN DN-169, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/5351,Buildings,Completed,NP-PERUNGUDI,169,472000,"REPAIR AND MAINTENANCE WORK TO UPHC AT RAVANAN NAGAR MAIN ROAD PROVIDING SHED INFRONT OF THE BUILDING IN DN.169, U-42, Z-14",Own Sources,14,2017-18,2017-18 NP/2017-18/6397,Roads,Completed,NP-PERUNGUDI,169,1056000,"PROVIDING SPEED BREAKER AS PER IRC STANDARD WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGN BOARD AND STUDS AT VARIOUS STREETS (10 STREETS) IN DN-169, U-42, Z-14",Own Sources,14,2017-18,2017-18 NP/2017-18/6944,Buildings,Completed,NP-PERUNGUDI,169,718000,"OUTSOURCING FOR PUBLIC CONVENIENCES IN DIVISION -169/UNIT-42, DIVISION 190 & 191/UNIT-43, FOR A PERIOD OF 9 MONTHS IN ZONE-14",Own Sources,14,2017-18,2019-20 NP/2017-18/6947,Storm Water Drain,Completed,NP-PERUNGUDI,169,726000,"IMPROVEMENT TO SIDE DRAIN AT MURUGAPPA NAGAR 5TH STREET, 6TH STREET, MAHESWARI AVENUE AND SARTHY NAGAR 2ND STREET IN DIVISION-169 UNIT-42 ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/6948,Buildings,Completed,NP-PERUNGUDI,169,119900,REPAIRS AND IMPROVEMENT TO ZONAL OFFICE IN DIVISON-169 UNIT-42 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/6956,Buildings,Completed,NP-PERUNGUDI,169,109800,IMPROVEMENT TO PUZHUTHIVAKKAM BURIAL GROUND IN DIVISION-169 UNIT-42 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/6993,Buildings,Completed,NP-PERUNGUDI,169,841000,"MAINTENANCE OF GASIFIER CREMATORIUM AT PUZHUTHIVAKKAM BURIAL GROUND IN DN.169, U-42, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/7914,Buildings,Completed,NP-PERUNGUDI,169,2278000,"Outsourcing of scavenging and sweeping work for Primary School,Middile School,High School & Higher Secondary School for seven months for thirteen schools in DN-168,169,183,184,185,186,188,190 & 191 IN ZONE-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/8756,Storm Water Drain,Completed,NP-PERUNGUDI,169,971000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN IN (DN-168-126 Nos & DN-169 - 115 Nos) DN-168 & 169 , UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8758,Storm Water Drain,Completed,NP-PERUNGUDI,169,779100,"DESITING OF VEERANGAL OODAI CHAINAGE 0 M TO 1400 M IN DN- 169, UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8760,Storm Water Drain,Completed,NP-PERUNGUDI,169,779100,"DESITING OF VEERANGAL OODAI SOUTH SIDE CHAINAGE 1400 M TO 2100M AND NORTH SIDE PORTION CHAINAGE 0 M TO 700 M IN DN- 169, UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8814,Buildings,Completed,NP-PERUNGUDI,169,127000,"PROPOSED CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREETS IN DN-169, U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8828,Buildings,Completed,NP-PERUNGUDI,169,500000,"MINOR REPAIR WORKS TO STORM WATER DRAIN IN DN-168,169 & 187, U-42, Z-14",Own Sources,14,2017-18,2017-18 NP/2017-18/9288,Parks,Completed,NP-PERUNGUDI,169,313000,"Outsourceing maintenance of park at Balaji nagar 19 th street in div-169,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9289,Parks,Completed,NP-PERUNGUDI,169,165500,"Outsourceing maintenance of park at Annai theresa nagar 14 th street in div-169,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9291,Parks,Completed,NP-PERUNGUDI,169,157000,"Outsourceing maintenance of park at A G S Colony in div-169,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9293,Parks,Completed,NP-PERUNGUDI,169,162000,"Outsourceing maintenance of park at E P R nagar in div-169,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9299,Parks,Completed,NP-PERUNGUDI,169,161000,"Outsourceing maintenance of park at Balaji nagar extn ( south) in div-169,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9627,Electrical,Completed,NP-PERUNGUDI,169,855700,"Provision of 40 KVA Generator for Gasifier in Balaji Nagar Burial Ground in Division-169, Zone-XIV",Own Sources,14,2017-18,2019-20 BR/2017-18/13181,Road Cut,Completed,BR-Bus Route Roads,170,1617000,"RESTORATION OF ROAD CUT MADE BY TAN TRANSCO AT 70 FEET ROAD (FROM JUNCTION OF ARANGANATHAN SUB WAY SERVICE ROAD TO NEW BOAG ROAD JUNCTION) IN DIV 171, ZONE-13.",Deposit Works,13,2017-18,2018-19 BR/2017-18/2157,Road Cut,Completed,BR-Bus Route Roads,170,875000,"Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 3947/2016,4601/2016 )",Deposit Works,13,2017-18,2019-20 BR/2017-18/2165,Road Cut,Completed,BR-Bus Route Roads,170,345000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 0954/2017 ),Deposit Works,13,2017-18,2019-20 L/2017-18/12798,Electrical,Completed,L-Electrical,170,198500,"PROVISION OF PAINTING & NUMBERING OF 106 NOS 9.2 MTR LAMP POST & SUPPLY & FIXING OF 30 NOS 4C SMC FUSE BOX AT ANNA SALAI , GUINDY IN DIV-170, ZONE-XIII",Own Sources,13,2017-18,2018-19 NN/2017-18/0264,Buildings,Completed,NN-ADYAR,170,1500000,"Proposed construction of Anganwadi at ARULAYIAMMANPET in Div-170, Unit-40A, Zone-13 by MLA Fund.",MLACDS,13,2017-18,2018-19 NN/2017-18/10332,Buildings,Completed,NN-ADYAR,170,392000,"Improvement works to Slaughter House (Doctor Room) at Alandur Service Road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2017-18,2018-19 NN/2017-18/10336,Buildings,Completed,NN-ADYAR,170,2200963,"Improvement works to Slaughter House at Alandur Service Road in div-170,Unit-40(A),Zone-XIII",Own Sources,13,2017-18,2018-19 NN/2017-18/11623,Parks,Completed,NN-ADYAR,170,821000,"REPAIRS AND IMPROVEMENTS TO THE PARK AT LABOUR COLONY, CENTRAL EXCISE COLONY & CUSTOMS COLONY IN DN-170,UT-40A,ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/11701,Roads,Completed,NN-ADYAR,170,378000,"Improvement to BT Road at Arulayammanpet I street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11703,Roads,Completed,NN-ADYAR,170,86000,"Improvement to BT Road at Arulayammanpet II Cross street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11704,Roads,Completed,NN-ADYAR,170,217000,"Improvement to BT Road at Arulayammanpet II street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11705,Roads,Completed,NN-ADYAR,170,45000,"Improvement to BT Road at Kalaimagal I lane (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11979,Roads,Completed,NN-ADYAR,170,48000,"Improvement to BT Road at Kannagi street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11980,Roads,Completed,NN-ADYAR,170,149000,"Improvement to BT Road at Munisamy street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11981,Roads,Completed,NN-ADYAR,170,269000,"Improvement to BT Road at Reddy 1st street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11982,Roads,Completed,NN-ADYAR,170,99000,"Improvement to BT Road at Reddy 2nd street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11983,Roads,Completed,NN-ADYAR,170,79000,"Improvement to BT Road at Reddy 3rd street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11984,Roads,Completed,NN-ADYAR,170,32000,"Improvement to BT Road at Sornamigai 2nd street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11985,Roads,Completed,NN-ADYAR,170,53000,"Improvement to BT Road at Visalakchi Nagar 1sr Cross street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11986,Roads,Completed,NN-ADYAR,170,97000,"Improvement to BT Road at Visalakchi Nagar 1st street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11987,Roads,Completed,NN-ADYAR,170,74000,"Improvement to BT Road at Visalakchi Nagar Main Road (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11988,Roads,Completed,NN-ADYAR,170,89000,"Improvement to BT Road at Visalakchi Nagar 2nd street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11989,Roads,Completed,NN-ADYAR,170,59000,"Improvement to BT Road at Visalakchi Nagar 1st Cross street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11990,Roads,Completed,NN-ADYAR,170,25000,"Improvement to BT Road at Visalakchi Nagar 2nd Cross street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11991,Roads,Completed,NN-ADYAR,170,41000,"Improvement to BT Road at Balaji Nagar 1st Cross street (Part) in Division 170, Zone - 13.",Grants,13,2017-18,2018-19 NN/2017-18/11992,Roads,Completed,NN-ADYAR,170,864000,"Improvement to BT Road at Duraisamy Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11993,Roads,Completed,NN-ADYAR,170,542000,"Improvement to BT Road at Muthuramalingam Main Road in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11994,Roads,Completed,NN-ADYAR,170,663000,"Improvement to BT Road at Poomagal Main Road in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11995,Roads,Completed,NN-ADYAR,170,1690000,"Improvement to BT Road at Sathya Nagar 2nd Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11996,Roads,Completed,NN-ADYAR,170,1335000,"Improvement to BT Road at Sathya Nagar 1st Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11997,Roads,Completed,NN-ADYAR,170,511000,"Improvement to BT Road at Sathya Nagar Main Road in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11998,Roads,Completed,NN-ADYAR,170,371000,"Improvement to BT Road at Sornamigai 1st Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11999,Roads,Completed,NN-ADYAR,170,617000,"Improvement to BT Road at Sornamigai 2nd Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12000,Roads,Completed,NN-ADYAR,170,1095000,"Improvement to BT Road at Sornamigai 3rd Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12001,Roads,Completed,NN-ADYAR,170,1408000,"Improvement to BT Road at Sornamigai Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12002,Roads,Completed,NN-ADYAR,170,1026000,"Improvement to BT Road at Achudhan 1st Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12003,Roads,Completed,NN-ADYAR,170,818000,"Improvement to BT Road at Dhanakotti Raja Street in Division 170, Unit 40A, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12004,Roads,Completed,NN-ADYAR,170,668000,"Improvement to BT Road at Navarthinam Garadan 2nd Street in Division 170, Unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12005,Roads,Completed,NN-ADYAR,170,907000,"Improvements to BT Road at Navarthinam Garadan 2nd Cross Street in Division 170, Unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12006,Roads,Completed,NN-ADYAR,170,1359000,"Improvements to BT Road at Navarthinam Garadan 3rd Cross Street in Division 170, Unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12753,Roads,Completed,NN-ADYAR,170,206000,"Attending Patch work to Damaged BT Roads at Poondamalli road, Sanmugaraja street, Rajaji street, Gandhi nagar extn, Muthuramalingam street, Kalaimagal nagar 2nd main road and Defence colony 3rd main road in Dn-170, Unit-40A, Zone-13",Own Sources,13,2017-18,2017-18 NN/2017-18/14604,Buildings,Completed,NN-ADYAR,170,183000,"Repairs and Improvement works to P.C. at Poonamallee Road, Reddy 2nd Street, Alandur & Kathipara Road in Dn.170, Unit-40A, Zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/2742,Buildings,Completed,NN-ADYAR,170,592000,Name of the work: Outsourcing Scavenging Work for the CPS Poonamalle Ekkatuthangal chennai -32 and CHS Little Mount (for1YEAR) in Dn-170 Unit-40A Zone - 13,Own Sources,13,2017-18,2019-20 NN/2017-18/3073,Buildings,Completed,NN-ADYAR,170,174500,Repairs and Maintenance to UPHC centre at Reddy 2nd Street in Division 170 Zone 13,Own Sources,13,2017-18,2018-19 NN/2017-18/6067,Buildings,Completed,NN-ADYAR,170,1012000,"Outsourcing Scavenging Work for the Public Conveniences in Division 170, 174 and 177, Unit 40A, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8009,Parks,Completed,NN-ADYAR,170,168000,"Outsourcing maintenance of Labour colony park in div-170,unit-40-a,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8715,Storm Water Drain,Completed,NN-ADYAR,170,446000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 170, UNIT - 40A, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8939,Storm Water Drain,Completed,NN-ADYAR,170,300000,"Minor Repairs Works to Strom Water Drain at Various Streets in Dn.170, Unit-40(A), Zone-13",Own Sources,13,2017-18,2017-18 BR/2017-18/12022,Footpath,Completed,BR-Bus Route Roads,171,5580000,"Forming Footpath at 70 Feet Road in Dn-171, Zone-XIII",Grants,13,2017-18,2019-20 BR/2017-18/13123,Road Cut,Completed,BR-Bus Route Roads,171,740000,RESTORATION OF ROAD CUT MADE BY TANTRANSCO AT ALANDUR ROAD IN DIV 171 ZONE-13.(FROM JUNCTION OF MOSQUE STREET TO GUINDY ALANDUR BRIDGE),Deposit Works,13,2017-18,2018-19 BR/2017-18/15054,Road Cut,Completed,BR-Bus Route Roads,171,2325000,"RESTORATION OF ROAD CUT MADE BY TANTRANSCO AT KATHI PARA ROAD (FROM ARULALAMPET STREET JUNCTION TO GUINDY ESTATE ROAD JUNCTION) IN DIV 171, ZONE-13.(LENGTH-500M)",Deposit Works,13,2017-18,2019-20 BR/2017-18/17253,Roads,Completed,BR-Bus Route Roads,171,620000,MODERN STAINLESS STEEL BUS SHELTERS REPAIR WORK AT VARIOUS PLACES IN ZONES 13&14.,Own Sources,13,2017-18,2019-20 BR/2017-18/2039,Roads,Completed,BR-Bus Route Roads,171,990000,"PROVIDING AND LAYING OF THERMOPLASTIC PAINTING AND STUDD AT TALUK OFFICE ROAD , SARDAR PATEL ROAD, GANHI MANDAPAM ROAD, DGS DINAKARAN SALAI, DURGA BAI DESHMUK ROAD IN ZONE-13",Own Sources,13,2017-18,2017-18 BR/2017-18/6997,Roads,Completed,SP-SPECIAL PROJECTS,171,2680000,"Name of the Work :Traffic Improvement works for Bi-Cycle lanes at under Smart City initiative at Sardarpatel Road, Taluk Office road, Velachery Main road, Indra Nagar 1st Avenue, 2nd Avenue, 3rd Avenue, Kasturibai Nagar 3rd cr. Street, DGS Dinakaran Salai, Durgabai Deshmukh Road, Broadies castle road, Besant Avenue Road, Besant Nagar 3rd Avenue, MG Road in Division 171, 172, 173, 175, 176, at Zone - XIII",SMART CITY - BRR,13,2017-18,2018-19 BR/2017-18/9863,Roads,Completed,BR-Bus Route Roads,171,915000,PAINTING OF EXISTING FOOT PATH AND CENTER MEDIAN AT SARDAR PATEL ROAD (FROM GANDHI MANDAPAM ROAD TO ANNA SALAI ) IN DIV-171 ZONE-13.,Own Sources,13,2017-18,2018-19 L/2017-18/12904,Electrical,Completed,L-Electrical,171,155000,"PROVISION OF PAINTING & NUMBERING OF 297 NOS 9.2 & 6/7 MTR LAMP POST AT CIT NAGAR SORROUNDING AREAS , SAIDAPET IN DIV-171, ZONE-XIII",Own Sources,13,2017-18,2018-19 NN/2017-18/10612,Electrical,Completed,NN-ADYAR,171,832000,"Proposed to Replace and Purchase of 14 Nos of T/L Fitting, 6 Nos of Ceiling Fan, 8 Nos of Wall Mount Fan, 22 Nos of Exhaust Fan, 7 nos of UV/RO palnt, 13 Nos of Weighing Machine, 1 nos of 15 Ltr Pulvarizer, 1 No of 200 Ltr Freezer, 5 Nos of Water Heater and 1 Nos of Commercial Mixer in Amma Unavagam in Dn-170 to 176 in Zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/11839,Parks,Completed,NN-ADYAR,171,162000,"IMPROVEMENTS TO THE PARK AT VELACHERY MAIN ROAD IN DN 171, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/12300,Buildings,Completed,NN-ADYAR,171,608000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AND E-TOILET AT APPAVOO NAGAR(RAILWAY BORDER 1ST STREET),JOTHIYAMMAL NAGAR, LDG ROAD, GANDHI MANDAPAM INSIDE IN DN-171, UNIT-40, ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12732,Electrical,Completed,NN-ADYAR,171,300000,"PROVISION OF ADDITIONAL AND RE-WIRING FOR NIGHT SHELTER HOMLESS AT RAILWAY BORDER ROAD APPAVU NAGAR, SAIDAPET IN DIV 171, UNIT 40, ZONE 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/2514,Buildings,Completed,NN-ADYAR,171,1106000,"Improvements and repair works to Health Post Building and UPHC at Vengatapuram in div-171, unit-40, zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/2640,Buildings,Completed,NN-ADYAR,171,997780,"Improvements to Anganvaadi at Railway Border 1st street, Sasthri Nagar, Vengadapuram, Govt farm and Surya Nagar in div -171, Unit-40, zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/2641,Buildings,Completed,NN-ADYAR,171,322000,"IMPROVEMENTS TO NIGHT SHELTER AT RAILWAY BORDER 1ST STREET IN DN 171, UNIT-40, ZONE-13",Own Sources,13,2017-18,2017-18 NN/2017-18/2642,Buildings,Completed,NN-ADYAR,171,29000,"IMPROVEMENTS TO AMMA UNAVAGAM AT RAILWAYBORDER 1ST STREET IN DIV-171, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/6960,Electrical,Completed,NN-ADYAR,171,250000,"PROVIDING ELECTRICAL WIRING AT MULTIPURPOSE BUILDINGS AT HOSPITAL ROAD AND KAVERI NAGAR IN DIV-171, ZONE-XIII",Own Sources,13,2017-18,2017-18 NN/2017-18/7064,Buildings,Completed,B-Buildings,171,998000,"Construction of additional room in 1st floor at UPHC, Hospital road in div-171, unit-40, zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/7399,Buildings,Completed,NN-ADYAR,171,2500000,"PROPOSED CONSTRUCTION OF MULTI PURPOSE HALL AT GOVERNMENT FARM IN DN-171, UNIT-40, ZONE- 13",MLACDS,13,2017-18,2018-19 NN/2017-18/7553,Buildings,Completed,NN-ADYAR,171,500000,"IMPROVEMENTS TO GYM(UNDER MLA FUND) AT SUBBUPILLAI THOTTAM IN DN 171, UNIT-40, ZONE-13",MLACDS,13,2017-18,2018-19 NN/2017-18/7582,Buildings,Completed,NN-ADYAR,171,500000,IMPROVEMENTS TO ROAD SIDE PARK(UNDER MLA FUND) AT BHARATHIDASAN STREET IN DN 171 UNIT 40 ZONE 13,MLACDS,13,2017-18,2018-19 NN/2017-18/7619,Buildings,Completed,NN-ADYAR,171,1657000,"Outsourcing Scavenging work for Chennai Primary school at Vengatapuram & Govt Model Hr.Sec School at Saidapet and Govt Girls Hr.sec school at saidapet ( Jai gobal Garodia) for 1YEAR in div-171, unit-40, zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/7650,Buildings,Completed,NN-ADYAR,171,1053000,"Outsourcing Scavenging works of Public Conveyances at Division 171 and 172, Unit 40, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7704,Buildings,Completed,NN-ADYAR,171,500000,"IMPROVEMENTS TO GYM (UNDER MLA FUND) AT VENGATAPURAM IN DN 171, UNIT-40, ZONE-13",MLACDS,13,2017-18,2018-19 NN/2017-18/7965,Overbridges,Completed,NN-ADYAR,171,195000,"Outsourcing maintenance of park at Chinnamalai Hallda Jn in div-171.unit-40,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8160,Buildings,Completed,NN-ADYAR,171,454000,"IMPROVEMENTS TO AMMA UNAVAGAM AT VENGATAPUARAM IN DIV-171, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8725,Storm Water Drain,Completed,NN-ADYAR,171,398000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 171, UNIT - 40A, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8768,Storm Water Drain,Completed,NN-ADYAR,171,177000,"Repair works to Storm Water Drain at various street in Dn 171, Unit 40, Zone 13.",Own Sources,13,2017-18,2017-18 BR/2017-18/10922,Roads,Completed,BR-Bus Route Roads,172,956000,"PAINTING OF EXISTING FOOT PATH AND CENTER MEDIAN AT ,D.G.S.DINAKARAN SALAI R.K.MUTT ROAD AND DURGA BAI DESH MUKH ROAD IN DIV-173 ZONE-13.",Own Sources,13,2017-18,2018-19 BR/2017-18/10923,Roads,Completed,BR-Bus Route Roads,172,956000,"PAINTING OF EXISTING FOOT PATH AND CENTER MEDIAN AT GREEN WAYS ROAD,BROADIES CASTLE ROAD,D.G.S.DINAKARAN SALAI, IN DIV-173 ZONE-13.",Own Sources,13,2017-18,2018-19 BR/2017-18/14556,Roads,Completed,BR-Bus Route Roads,172,950000,"PAINTING OF EXISTING FOOT PATH AND CENTER MEDIAN AT GANDHI MANDAPAM ROAD AND SARDAR PATEL ROAD (FROM MADHYA KAILASH TO GANDHI MANDAPAM ROAD) IN DIV-172, ZONE-13.",Own Sources,13,2017-18,2018-19 BR/2017-18/2181,Road Cut,Completed,BR-Bus Route Roads,172,862000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 4617/2016/1),Deposit Works,13,2017-18,2019-20 BR/2017-18/2182,Road Cut,Completed,BR-Bus Route Roads,172,770000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 4617/2016/2),Deposit Works,13,2017-18,2019-20 NN/2017-18/11494,Roads,Completed,NN-ADYAR,172,499000,"Improvements to Bituminous road at Kalikundram main road in Divisions - 172, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/11495,Roads,Completed,NN-ADYAR,172,183000,"Improvements to Bituminous road at Karunanidhi Nagar 1st street in Divisions - 172, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/11496,Roads,Completed,NN-ADYAR,172,329000,"Improvements to Bituminous road at Karunanidhi Nagar 2nd street in Divisions - 172, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/11497,Roads,Completed,NN-ADYAR,172,344000,"Improvements to Bituminous road at Karunanidhi Nagar 3rd street in Divisions - 172, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/11498,Roads,Completed,NN-ADYAR,172,599000,"Improvements to Bituminous road at Pondichery road(part) in Divisions - 172, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/11840,Parks,Completed,NN-ADYAR,172,477000,Improvements to Govindasamy Park at Lake view road in Dn 172 Unit 40 Zone 13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12296,Buildings,Completed,NN-ADYAR,172,250000,"IMPROVEMENTS TO PUBLIC CONVENIENCE & SMART TOILET AT LAKE VIEW ROAD, GYPSY COLONY, PONNIYAMMAN KOIL STREET & WEST CANAL BANK ROAD IN DN-172, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/12316,Buildings,Completed,NN-ADYAR,172,347000,IMPROVEMENTS TO SENIOR CITIZEN PARK AT KOTTUR GARDEN 4TH MAIN ROAD IN DN 172 UNIT 40 ZONE 13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12370,Parks,Completed,NN-ADYAR,172,439000,"IMPROVEMENTS TO PARK AT CHITRA NAGAR & RIVER VIEW ROAD IN DN 172, UNIT 40 ZONE 13",Own Sources,13,2017-18,2018-19 NN/2017-18/17962,Roads,Completed,NN-ADYAR,172,415000,"Improvements to Cement Concrete Road at Raja garamani thottam 2nd street in Dn-173, unit-40, zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/2699,Buildings,Completed,NN-ADYAR,172,212000,"IMPROVEMENTS TO AMMA UNAVAGAM AT NEW STREET& KOTTURPURAM IN DN 172, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/2703,Buildings,Completed,NN-ADYAR,172,147000,"IMPROVEMENTS TO HEALTH POST BUILDING AT DHANDAUTHABANI 2ND STREET IN DN 172, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/2725,Buildings,Completed,NN-ADYAR,172,592000,"Outsourcing Scavenging work for the CHS, CPS and KGS at New street and CPS at Kotturpuram (For One Year)in Dn -172 unit -40 Zone -13",Own Sources,13,2017-18,2019-20 NN/2017-18/7554,Buildings,Completed,NN-ADYAR,172,500000,"CONSTRUCTION OF COMPOUND WALL FOR ROAD SIDE PARK (UNDER MLA FUND)AT SOUTH LOCK STREET IN DN-172, UNIT-40, ZONE-13.",MLACDS,13,2017-18,2018-19 NN/2017-18/7555,Buildings,Completed,NN-ADYAR,172,498000,"IMPROVEMENTS TO GYM AT PALLIPATTU MAIN ROAD IN DN 171, UNIT-40, ZONE-13",MLACDS,13,2017-18,2018-19 NN/2017-18/7966,Parks,Completed,NN-ADYAR,172,243000,"Outsourcing maintenance of park at Dhandayuthapani nagar in div-172.unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7969,Parks,Completed,NN-ADYAR,172,147000,"Outsourcing maintenance of Senior citizen park in div-172.unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7970,Parks,Completed,NN-ADYAR,172,142000,"Outsourcing maintenance of Govindasamy park in div-172,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7971,Parks,Completed,NN-ADYAR,172,1303000,"Outsourcing maintenance of River view park in div-172,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7972,Parks,Completed,NN-ADYAR,172,335000,"Outsourcing maintenance of Chitra nagar park in div-172,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8543,Buildings,Completed,NN-ADYAR,172,946000,"Conversion of Existing Gasifier Crematorium to manual LPG Burner system crematorium at Lake view road Burial ground in dn-172, unit-40, zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8718,Buildings,Completed,NN-ADYAR,172,193000,"IMPROVEMENTS TO ANGAN VAADI AT PALLIPATTU MAIN ROAD IN DN 172, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8719,Buildings,Completed,NN-ADYAR,172,166000,"IMPROVEMENTS TO ANGAN VAADI AT PELIYAMMAN KOIL STREET IN DN 172, UNIT-40, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8729,Storm Water Drain,Completed,NN-ADYAR,172,446000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 172, UNIT - 40, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8769,Storm Water Drain,Completed,NN-ADYAR,172,177000,"Repair works to Storm Water Drain at various street in Dn 172, Unit 40, Zone 13.",Own Sources,13,2017-18,2017-18 NN/2017-18/9633,Buildings,Completed,NN-ADYAR,172,1000000,"Proposed Construction of Anganwadi at West canal Bank road in Div- 172 , Unit-40 , Zone-13.",MLACDS,13,2017-18,2018-19 BR/2017-18/10178,Road Cut,Completed,BR-Bus Route Roads,173,1931000,RESTORATION OF ROAD CUT MADE BY TANGEDCO AT DURGA BAI DESH MUKH ROAD( REACH-1) IN DIV173 ZONE13.,Deposit Works,13,2017-18,2018-19 BR/2017-18/10194,Roads,Completed,BR-Bus Route Roads,173,1820000,RESTORATION OF ROAD CUT MADE BY TANGEDCO AT DURGA BAI DESHMUKH ROAD( REACH-2) IN DIV173 ZONE13.,Deposit Works,13,2017-18,2018-19 BR/2017-18/10198,Road Cut,Completed,BR-Bus Route Roads,173,4537000,RESTORATION OF ROAD CUT MADE BY TANGEDCO AT BESANT NAGAR 3RD AVENUE IN DIV173 ZONE13.,Deposit Works,13,2017-18,2018-19 BR/2017-18/10199,Road Cut,Completed,BR-Bus Route Roads,173,884000,RESTORATION OF ROAD CUT MADE BY TANGEDCO AT BESANT NAGAR 1ST AVENUE IN DIV173 ZONE13.,Deposit Works,13,2017-18,2019-20 BR/2017-18/10265,Road Cut,Completed,BR-Bus Route Roads,173,3500000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT BESANT AVENUE ROAD REACH -1 (FROM JUNCTION OF AAVIN MILK TO BESANT NAGAR 4TH LINK STREET.) IN DIV-173, ZONE-13.",Deposit Works,13,2017-18,2018-19 BR/2017-18/10266,Road Cut,Completed,BR-Bus Route Roads,173,3500000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT BESANT AVENUE ROAD REACH -2 (FROM JUNCTION OF BESANT NAGAR 4TH LINK STREET TO BESANT NAGAR 3RD AVENUE ) IN DIV-173, ZONE-13.",Deposit Works,13,2017-18,2018-19 BR/2017-18/10286,Road Cut,Completed,BR-Bus Route Roads,173,4674000,RESTORATION OF ROAD CUT MADE BY TANGEDCO AT GREEN WAYS ROAD (P.S. KUMARASAMY RAJA ROAD)IN DIV 173 ZONE-13.,Deposit Works,13,2017-18,2018-19 BR/2017-18/12023,Footpath,Completed,BR-Bus Route Roads,173,5859000,"Forming Footpath at Srinivasa Avenue in Dn-173, Zone-XIII",Grants,13,2017-18,2019-20 BR/2017-18/16989,Road Cut,Completed,BR-Bus Route Roads,173,1191000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SANTHOME HIGH ROAD (NEAR MRC MANDAPAM) IN DIV-173, ZONE-13. ( LENGTH 240.00M)",Deposit Works,13,2017-18,2018-19 BR/2017-18/7214,Roads,Completed,BR-Bus Route Roads,173,150000,"PROVIDING AND LAYING SPEED BREAKER AT DR. DINAKARAN SALAI NEAR DR. AMBEDKAR MEMORIAL HALL AND NEAR IYYAPPAN KOIL IN DIV - 173, ZONE-13",Grants,13,2017-18,2018-19 BR/2017-18/8961,Bridges,Completed,BR-Bus Route Roads,173,237000,REMOVING AND REFIXING OF 2NOS OF STAINLESS STEEL BUS SHELTER AT DURGABAI DESHMUKH ROAD NEAR SIVAJI GANESAN MEMORIAL HALL IN DIV 173 ZONE13,Own Sources,13,2017-18,2019-20 L/2017-18/6837,Electrical,Completed,L-Electrical,173,2539000,"Providing 2nos of 20mtr High Mast Lamp posts with 210w - 230w LED fittings for Chennai Corporation Play Ground at DGS Dinakaran Salai, Raja Annamalai puram in Div-173, Zone-XIII.",Own Sources,13,2017-18,2018-19 L/2017-18/7374,Electrical,Completed,L-Electrical,173,4465000,"Providing 67nos of 6mtr GI Lamp posts with 40w LED fittings and replacement of 2cx16sqmm cable for 29nos of lamp post with LED fittings at South Kesava perumal puram main road, 1st cross street, 2nd cross street, 3rd cross street, Annai Sathya nagar, Annai Therasa Nagar and Anna Nagar in Division-173, Zone-XIII.",Own Sources,13,2017-18,2018-19 NN/2017-18/10025,Roads,Completed,NN-ADYAR,173,364000,"Improvements to Bituminous road at Bagirathi Amman Street in Divisio - 173, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/10026,Roads,Completed,NN-ADYAR,173,986000,Improvements to Bituminous road at Srinivasapuram I Main Road (Part),Grants,13,2017-18,2018-19 NN/2017-18/10027,Roads,Completed,NN-ADYAR,173,87000,"Improvements to Bituminous road at Srinivasapuram I street in Division - 173, Unit - 40, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/10028,Roads,Completed,NN-ADYAR,173,672000,"Improvements to Bituminous road Srinivasapuram II Main Road IN DN-173, UNIT-40, ZONE-13.",Grants,13,2017-18,2018-19 NN/2017-18/10029,Roads,Completed,NN-ADYAR,173,66000,"Improvements to Bituminous road Srinivasapuram II Street IN DN-173, UNIT-40, ZONE-13.",Grants,13,2017-18,2018-19 NN/2017-18/10031,Roads,Completed,NN-ADYAR,173,79000,"Improvements to Bituminous road Srinivasapuram III street IN DN-173, UNIT-40, ZONE-13.",Grants,13,2017-18,2018-19 NN/2017-18/10032,Roads,Completed,NN-ADYAR,173,43000,"Improvements to Bituminous road at Srinivasapuram IV street IN DN-173, UNIT-40, ZONE-13.",Grants,13,2017-18,2018-19 NN/2017-18/10033,Roads,Completed,NN-ADYAR,173,2337000,"Improvements to Bituminous road at South Kesavaperumal main road IN DN-173, UNIT-40, ZONE-13.",Grants,13,2017-18,2018-19 NN/2017-18/10095,Roads,Completed,NN-ADYAR,173,490000,"Relaying of road at RK Nagar I Main Road in Division - 173, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/10096,Roads,Completed,NN-ADYAR,173,808000,"Relaying of road at Robertson Lane & Salaiyar street in Division - 173, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/11865,Buildings,Completed,NN-ADYAR,173,31000,"REPAIR AND MAINTAINENCE WORK OF AMMA UNAVAGAM (GREENWAYS ROAD),DIV-173, UNIT-40, ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11866,Buildings,Completed,NN-ADYAR,173,61000,"REPAIR AND MAINTAINENCE WORKS OF AMMA UNAVAGAM(KAMARAJ SALAI) DIV-173, UNIT-40, ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12190,Buildings,Completed,NN-ADYAR,173,189500,"REPAIR AND IMPROVEMENT OF PUBLIC CONVENIENCES AT GREENWAYS ROAD(2), KAMARAJ SALAI(1) GOVINDASAMY NAGAR AND R.K.MUTT ROAD IN DN-173, U-40, Z-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12191,Buildings,Completed,NN-ADYAR,173,222000,REPAIR AND MAINTENANCE OF DISPENSARY AT VELAYUDHA RAJA STREET IN DIV-173 UNIT-40 ZONE-13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12357,Parks,Completed,NN-ADYAR,173,238500,REPAIR AND IMPROVEMENTS OF CENTRAL AVENUE PARK AT KESAVAPERUMAL PURAM IN DIV-173 UNIT-40 ZONE-13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12358,Parks,Completed,NN-ADYAR,173,216000,REPAIR AND IMPROVEMENTS OF MAY FLOWER GARDEN AT SRINIVASA AVENUE AND GREENERIES AT MAY FLOWER GARDEN AND M.R.C NAGAR IN DIV-173 UNIT-40 ZONE-13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12360,Parks,Completed,NN-ADYAR,173,251600,REPAIR AND IMPROVEMENTS OF KRISHNAPURI PARK AT KRISHNAPURI MAIN ROAD IN DIV-173 UNIT-40 ZONE-13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12531,Parks,Completed,NN-ADYAR,173,125500,IMPROVEMENTS TO VASANTHA AVENUE PARK AT VASANTHA AVENUE IN DIV-173 UNIT-40 ZONE-13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12651,Buildings,Completed,NN-ADYAR,173,388000,IMPROVEMENTS TO ROADSIDE PARK AT D.G.S.DINAGARAN SALAI IN DIV-173 UNIT-40 ZONE-13.,Own Sources,13,2017-18,2018-19 NN/2017-18/12791,Buildings,Completed,NN-ADYAR,173,276000,"REPAIR AND IMPROVEMENT WORKS OF ANGANWADI AT KVB GARDEN (CENTRE NO-33603110221,33603110222,33603110223) SK PURAM ( CENTRE NO-33603110217,33603110218 & 33603110219) KAMARAJ SALAI (CENTRE NO - 33603110224,33603110225,33603110226 &33603110227) IN DIV-173, UNIT-40,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12812,Roads,Completed,NN-ADYAR,173,358000,"Attending Patch work at Damaged BT Roads Lock street, Ellaiamman koil Street, Ponniamman koil street in Dn-172 and Thiruvengadam street in Dn-173, Unit-40, Zone-13",Own Sources,13,2017-18,2017-18 NN/2017-18/16409,Buildings,Completed,NN-ADYAR,173,1300000,Improvement works to Karpagam Avenue Playfield in dn 173 Unit-40 Zone 13.,Own Sources,13,2017-18,2018-19 NN/2017-18/2741,Buildings,Completed,NN-ADYAR,173,237000,"Outsourcing Scavenging Work for the Chennai Middle School Park View Road R.A.Puram Chennai -28 (For 1Year) in DN173, Unit-40, Zone XIII","Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/7651,Buildings,Completed,NN-ADYAR,173,689000,"Outsourcing of Scavenging works for Public Conveyance at Division 173 and 175, Unit 40, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7974,Parks,Completed,NN-ADYAR,173,358000,"Outsourcing maintenance of Kamarajar salai(Dharmambabl) park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7975,Parks,Completed,NN-ADYAR,173,150000,"Outsourcing maintenance of Kesavaperumalpuram central avenue park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7976,Parks,Completed,NN-ADYAR,173,170000,"Outsourcing maintenance of Kesavaperumalpuram east avenue park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7977,Parks,Completed,NN-ADYAR,173,149000,"Outsourcing maintenance of Sathyadev avenue extn park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7979,Parks,Completed,NN-ADYAR,173,149000,"Outsourcing maintenance of Krishnapuri main road park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7980,Parks,Completed,NN-ADYAR,173,543000,"Outsourcing maintenance of M R C Nagar extn park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7981,Parks,Completed,NN-ADYAR,173,194000,"Outsourcing maintenance of M R C nagar Vasantha avenue park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8772,Storm Water Drain,Completed,NN-ADYAR,173,178000,"Repair works to Storm Water Drain at various street in Dn 173, Unit 40, Zone 13.",Own Sources,13,2017-18,2017-18 P/2017-18/13052,Parks,Completed,P-Parks and Playfields,173,7358100,"FORMATION OF NEW PARK AT THIRUVEETRIAMMAN ROAD (THIRUVENKADAM STREET) IN DN-173, ZONE - XIII.",Grants,13,2017-18,2019-20 BR/2017-18/0058,Road Cut,Completed,BR-Bus Route Roads,174,2850000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT CITY LINK ROAD FROM CHAKARAPANI ROAD TO VANDIKKARAN STREET IN DIV 174, ZONE- 13",Deposit Works,13,2017-18,2017-18 BR/2017-18/11557,Roads,Completed,BR-Bus Route Roads,174,27100000,"Strengthening and Relaying the Road with DBM and BC after cold milling by paver finish using plastic along with traffic improvement work at Velachery Main Road in Dn-174 & 179, Zone-XIII",Grants,13,2017-18,2018-19 BR/2017-18/12026,Footpath,Completed,BR-Bus Route Roads,174,6138000,"Forming Footpath at Five Furlong Road in Dn-174, Zone-XIII",Grants,13,2017-18,2019-20 D/2017-18/10159,Storm Water Drain,Completed,D-Storm Water Drains,174,2460000,"Construction of storm water drain of size 600x750mm along Ambedkar nagar main road from Periyar street to Nedunchezhian street in Dn- 174,Zone-XIII.",Own Sources,13,2017-18,2018-19 D/2017-18/10160,Storm Water Drain,Completed,D-Storm Water Drains,174,2480000,"Construction of storm water drain of size 900x900mm along Nedunchezhian street from Ambedkar main road to Rajbhavan canal in Dn- 174,Zone-XIII.",Own Sources,13,2017-18,2018-19 D/2017-18/10161,Storm Water Drain,Completed,D-Storm Water Drains,174,2330000,"Construction of storm water drain of size 900x900mm along City Link road from Chakarapani street to Railway culvert in Dn- 174,Zone-XIII.",Own Sources,13,2017-18,2018-19 D/2017-18/10162,Storm Water Drain,Completed,D-Storm Water Drains,174,2490000,"Construction of storm water drain along road crossing at City Link road near Railway culvert in Dn- 174,Zone-XIII.",Own Sources,13,2017-18,2018-19 NN/2017-18/10048,Buildings,Completed,NN-ADYAR,174,942000,"OPERATING ELECTRICAL CREMOTORIUM AT VELACHERY MAIN ROAD (OPP TO WESTERN HOTEL) IN DIVISION - 174, UNIT - 40A, ZONE - XIII",Own Sources,13,2017-18,2018-19 NN/2017-18/10629,Buildings,Completed,NN-ADYAR,174,268000,"PROVIDING SMART CLASS ROOM ARRANGEMENTS AT C BLOCK (1ST FLOOR) IN CORPORATION HIGHER SECONDARY SCHOOL , MADUVIVKARAI IN DN-174 ,UT40A,ZONE-13.",Grants,13,2017-18,2018-19 NN/2017-18/11133,Electrical,Completed,NN-ADYAR,174,496000,"SERVICING OF EXISTING ELECTRICAL CREMATORIUM AT VELACHERY BURIAL GROUND IN DN-174 ,UT -40 ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11850,Buildings,Completed,NN-ADYAR,174,449000,"REPAIR WORKS TO THE DAMAGED R.C.C. ROOF AT THE A BLOCK IN CHSS IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11851,Buildings,Completed,NN-ADYAR,174,164000,"REPAIR WORKS TO THE DAMAGED FLOOR PORTION IN FRONT OF H.M. ROOM AT CHSS IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11853,Buildings,Completed,NN-ADYAR,174,263000,"PROVIDING FLOORING FOR DINING IN FRONT OF C BLOCK AND REPAIR WORKS TO THE DAMAGED R.C.C. ROOF AT B BLOCK HEADROOM AT CHSS IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11854,Buildings,Completed,NN-ADYAR,174,218000,"REPAIR WORKS TO THE DAMAGED R.C.C. ROOF AND PASSAGE FLOORING AT S.S.I. BUILDING AT CPS IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11855,Buildings,Completed,NN-ADYAR,174,186000,"REPAIR WORKS TO THE LKG BLOCK AND TOILET BLOCK AT CPS IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12043,Parks,Completed,NN-ADYAR,174,169000,"PROVIDING WATCHMEN SHED AND RAISING THE LEVEL OF PLAY AREA AT SECRETARIAT COLONY PARK IN DN-174,UT-40A,ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/12045,Roads,Completed,NN-ADYAR,174,91000,"Improvements to Bituminous road at Sathanipet I street in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12046,Roads,Completed,NN-ADYAR,174,188000,"Improvements to Bituminous road at Sathanipet II street in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12047,Roads,Completed,NN-ADYAR,174,400000,"Improvements to Bituminous road at Sathanipet II street extn in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12048,Roads,Completed,NN-ADYAR,174,509000,"Improvements to Bituminous road at Anna Gardern I Street (Part) in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12049,Roads,Completed,NN-ADYAR,174,68000,"Improvements to Bituminous road at Anna Gardern II Street in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12050,Roads,Completed,NN-ADYAR,174,124000,"Improvements to Bituminous road at at Race Course Interior Road in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12051,Roads,Completed,NN-ADYAR,174,499000,"Improvements to Bituminous road at Cart Track Road in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12052,Roads,Completed,NN-ADYAR,174,499000,"Improvements to Bituminous road at Pilaiyar Koil Street (Maduvinkarai) in division 174, unit 40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12053,Roads,Completed,NN-ADYAR,174,319000,"Relaying the Road at K R Ramasamy Street in Division 174, Unit-40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12054,Roads,Completed,NN-ADYAR,174,876000,"Relaying the Road at Gandhi Street in Division 174, Unit-40A, Zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/12066,Electrical,Completed,NN-ADYAR,174,228000,"PROPOSED NEW WIRING OF CPS SCHOOL MAIN BUILDING (ABOVE 1ST FLOOR) PROJECTOR ROOM IN DIV-174, ZONE-XIII.",Own Sources,13,2017-18,2018-19 NN/2017-18/12407,Roads,Completed,NN-ADYAR,174,563000,"Attending Patch work at Damaged BT Roads Pillaiyar koil street, Blue Cross road and Vandikaran Street in Dn-174, Unit-40A, Zone-13",Own Sources,13,2017-18,2017-18 NN/2017-18/13149,Buildings,Completed,NN-ADYAR,174,413000,Providing Additional requirements for Smart Class Room at C Block First floor CHSS. in Division - 174 Unit - 40A Zone - 13,Own Sources,13,2017-18,2018-19 NN/2017-18/13156,Buildings,Completed,NN-ADYAR,174,510000,"IMPROVEMENTS TO THE PC AND CARETAKER ROOM BURIAL GROUND AT VELECHERY MAIN ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/14737,Buildings,Completed,NN-ADYAR,174,1050000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND FOOT PATH FOR PLAY FIELD AT JUNCTION OF NEDUNZIHAN STREET IN DN-174,UT-40A, ZONE-13.(UNDER SAIDAPET MLA FUND)",MLACDS,13,2017-18,2019-20 NN/2017-18/1553,Roads,Completed,NN-ADYAR,174,724000,"IMPROVEMENTS TO BT ROAD AT BLUE CROSS ROAD IN DN-174,UT-40A,ZONE-13.",Grants,13,2017-18,2018-19 NN/2017-18/17876,Buildings,Completed,NN-ADYAR,174,200000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 9 TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17877,Buildings,Completed,NN-ADYAR,174,759000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 10TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17878,Roads,Completed,NN-ADYAR,174,427000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 12TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17879,Buildings,Completed,NN-ADYAR,174,626000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 13TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17880,Roads,Completed,NN-ADYAR,174,499000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 14TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17881,Roads,Completed,NN-ADYAR,174,585000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 15TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17882,Roads,Completed,NN-ADYAR,174,427000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 16TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17883,Roads,Completed,NN-ADYAR,174,1697000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 6TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17884,Roads,Completed,NN-ADYAR,174,848000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 2ND ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17885,Roads,Completed,NN-ADYAR,174,875000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 3RD ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17886,Roads,Completed,NN-ADYAR,174,400000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 4TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17887,Roads,Completed,NN-ADYAR,174,999000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 5TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17888,Roads,Completed,NN-ADYAR,174,327000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 7TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17889,Roads,Completed,NN-ADYAR,174,200000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT MOSQUE COLONY 8TH ST IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17890,Roads,Completed,NN-ADYAR,174,693000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT TANK SQUARE ROAD (BHARATHI ST)IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17891,Roads,Completed,NN-ADYAR,174,960000,"PROVIDING AND LAYING OF M30 GRADE CEMENT CONCRETE ROAD AT KANNAGI ST ,KAMARAJAPURAM,IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/2944,Buildings,Completed,NN-ADYAR,174,173000,"IMPROVEMENTS AND REPAIRS TO THE AMMA UNAVAGAM AT FIVE FUR LONG ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/2947,Buildings,Completed,NN-ADYAR,174,995000,"IMPROVEMENTS AND REPAIRS TO THE COMMUNITY HALL AT CHAKARAPANI ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/3005,Buildings,Completed,NN-ADYAR,174,382000,"REPAIRS TO THE ANGANWADI AT FIVE FURLONG ROAD ,MGR ST RACE COURSE ROAD ,GANESH NAGAR NETHAJI RD AND VELECHERY 100 FT ROAD IN DN -174,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/6073,Buildings,Completed,NN-ADYAR,174,1538000,"Outsourcing of Scavenging work at CPS and CHS at five furlong road in DN174, unit 40A, zone XIII",Own Sources,13,2017-18,2019-20 NN/2017-18/7982,Parks,Completed,NN-ADYAR,174,444000,"Outsourcing maintenance of City limit road(Secretariat colony ) park in div-173,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8733,Storm Water Drain,Completed,NN-ADYAR,174,350000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 174, UNIT - 40A, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8949,Storm Water Drain,Completed,NN-ADYAR,174,250000,"Minor Repairs Works to Strom Water Drain at Various Streets in Dn.174, Unit-40(A), Zone-13",Own Sources,13,2017-18,2017-18 B/2017-18/14599,Buildings,Completed,B-Buildings,175,11325000,"CONSTRUCTION OF 3+3+1 CLASSROOMS (G+2F) FOR CPS AT KAMARAJ AVENUE IN ADYAR, DN-175, ZONE-13",MLACDS,13,2017-18,2020-21 BR/2017-18/10179,Roads,Completed,BR-Bus Route Roads,175,755000,"PAINTING OF EXISTING FOOT PATH AND CENTER MEDIAN AT ,SARDAR PATEL ROAD (FROM MADHYA KAILASH TO AAVIN JUNCTION) AND TALUK OFFICE ROAD, IN DIV-175 AND ZONE-13.",Own Sources,13,2017-18,2018-19 BR/2017-18/12031,Footpath,Completed,BR-Bus Route Roads,175,13950000,"Forming Footpath at Indra Nagar 1st Avenue in Dn-175, Zone-XIII",Grants,13,2017-18,2019-20 BR/2017-18/12032,Footpath,Completed,BR-Bus Route Roads,175,9068000,"Forming Footpath at Kasthuribai Nagar 3rd Cross Street in Dn-175, Zone-XIII",Grants,13,2017-18,2019-20 BR/2017-18/2184,Road Cut,Completed,BR-Bus Route Roads,175,862000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (4617/2016/1),Deposit Works,13,2017-18,2018-19 BR/2017-18/2185,Road Cut,Completed,BR-Bus Route Roads,175,770000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (4617/2016/2),Deposit Works,13,2017-18,2018-19 BR/2017-18/2186,Road Cut,Completed,BR-Bus Route Roads,175,643000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (4617/2016/3),Deposit Works,13,2017-18,2018-19 D/2017-18/11797,Storm Water Drain,Completed,D-Storm Water Drains,175,2022750,"Dismantling of existing dilapidated storm water drain and Re-Construction of storm water drain of size 900x900mm along Gandhi nagar 1st main road from Chainage 80.00M to Chainage 170M in Dn- 175,Zone-XIII.",Own Sources,13,2017-18,2018-19 D/2017-18/11799,Storm Water Drain,Completed,D-Storm Water Drains,175,1798000,"Dismantling of existing dilapidated storm water drain and Re-Construction of storm water drain of size 900x900mm along Gandhi nagar 1st main road from south B canal to Chainage 80.00M in Dn- 175,Zone-XIII.",Own Sources,13,2017-18,2018-19 L/2017-18/1826,Electrical,Completed,L-Electrical,175,604000,"Erection of 14Nos of 9mtr / 9.5mtr lamp post with replacement of cable of 4cx16sqmm at Sardar patel road Center median (from the Jn of KB Nagar 3rd cross to Jn of Adyar Fly over bridge) Adyar, in Div-175, Zone-XIII.",Own Sources,13,2017-18,2017-18 L/2017-18/1843,Electrical,Completed,L-Electrical,175,501000,"Replacement of 635mtrs of 4cx16sqmm Alu Cable at Latice Bridge Road (Kalki Krishna Moorthi salai and Dr.Muthulakshmi Salai) Centre median, Adyar in Division-175, Zone-XIII.",Own Sources,13,2017-18,2017-18 NN/2017-18/10088,Roads,Completed,NN-ADYAR,175,938000,"Relaying of road at LB road I street in Division - 175, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/10089,Roads,Completed,NN-ADYAR,175,1564000,Improvement to BT Road at Gandi nagar III canal cross street in Dn.175,Grants,13,2017-18,2018-19 NN/2017-18/10429,Buildings,Completed,NN-ADYAR,175,115000,"Repairs and Maintenance in Amma Unavagam at Thiruvengadam Street in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/10968,Electrical,Completed,NN-ADYAR,175,68000,PROPOSED TO PURCHASE OF 13 NOS 20 W HAND GRIP MEGAPHONE WITH BUILT SIREN & MICROPHONE DC 12V FOR THE USE OF DIV-170 TO 182 IN ZONE-XIII,Own Sources,13,2017-18,2018-19 NN/2017-18/11803,Buildings,Completed,NN-ADYAR,175,200000,"Demolition Building at Electrical Sub Station, Indira Nagar 1st Avenue in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12188,Roads,Completed,NN-ADYAR,175,675000,"Attanting Batch work to damaged BT roads at Gandhi nagar 2nd main road ,Gandhi nagar 3rd main road, Kasthuribai nagar 1st Cross street, and Kamaraj Avenue 2nd street And Repair works to Footpath at Gandhi nagar cresent avenue and Gandhi nagar 2nd cresent park street in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2017-18 NN/2017-18/16779,Buildings,Completed,NN-ADYAR,175,760000,"Proposed Construction of Compound wall for OSRland at Indira Nagar 26th Cross steert in Div-175,Unit-40,Zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/2719,Buildings,Completed,NN-ADYAR,175,711000,"Outsourcing Scavenging work for the CHS and CPS at kamaraj Avenue and CPS at Indira Nagar 29th Cross Street (for One Year) in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/2722,Buildings,Completed,NN-ADYAR,175,2095000,"Repairs and Improvement of UPHC Building Venkatrathnam Nagar, Adyar in Dn - 175, Unit - 40, Zone - 13",Own Sources,13,2017-18,2019-20 NN/2017-18/2724,Buildings,Completed,NN-ADYAR,175,220000,"Repairs and Improvement of Amma Unavagam 29th Cross Street,Indira Nagar, Adyar in Dn - 175, Unit - 40, Zone - 13",Own Sources,13,2017-18,2018-19 NN/2017-18/4068,Buildings,Completed,NN-ADYAR,175,2470000,"Repairs and Improvement of Shopping Complex at Indra nagar 3rd Avenue in Dn - 175, Unit - 40, Zone - 13",Own Sources,13,2017-18,2019-20 NN/2017-18/4355,Buildings,Completed,NN-ADYAR,175,2225000,"Repairs and Improvement of vegetable market Complex at Indra nagar 3rd Avenue in Dn - 175, Unit - 40, Zone - 13",Own Sources,13,2017-18,2018-19 NN/2017-18/8010,Parks,Completed,NN-ADYAR,175,878000,"Outsourcing maintenance of park at Indra nagar 4 th cross st park in div -175,unit-40,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8721,Buildings,Completed,NN-ADYAR,175,250000,"Repairs and Maintenance work of Anganwadi (ICDS) at Indira Nagar 11th Lane, Indira Nagar 18th Cross Street Thiruvengadam street, Malipoo Nagar in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8722,Buildings,Completed,NN-ADYAR,175,280000,"Repairs and Maintenance work of Anganwadi (ICDS) at Indira Nagar 29th Cross Street, in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8723,Buildings,Completed,NN-ADYAR,175,150000,"Repairs and Maintenance work of Anganwadi (ICDS) 33603110116 at School Road in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8724,Buildings,Completed,NN-ADYAR,175,195000,"Repairs and Maintenance work of Anganwadi (ICDS) 33603110113 at School Road, in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8735,Storm Water Drain,Completed,NN-ADYAR,175,638000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 175, UNIT - 40, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8770,Storm Water Drain,Completed,NN-ADYAR,175,178000,"Repair works to Storm Water Drain at various street in Dn 175, Unit 40, Zone 13.",Own Sources,13,2017-18,2017-18 NN/2017-18/9841,Buildings,Completed,NN-ADYAR,175,970000,"Demolition Building at Chennai Primary School, Kamaraj Avenue in Div-175, Unit-40, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/9975,Roads,Completed,NN-ADYAR,175,69000,"Improvements to Bituminous road at Indra nagar 8th cross street in Div - 175, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/9976,Roads,Completed,NN-ADYAR,175,2297000,"Improvements to Bituminous road at Indra nagar 26th cross street in Div - 175, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/9977,Roads,Completed,NN-ADYAR,175,196000,"Improvements to Bituminous road at Indra nagar 9th cross street in Div - 175, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/9978,Roads,Completed,NN-ADYAR,175,366000,"Improvements to Bituminous road at Gandhi nagar 1st canal cross street in Div - 175, unit-40, zone-13.",Grants,13,2017-18,2018-19 NN/2017-18/9979,Roads,Completed,NN-ADYAR,175,418000,"Improvements to Bituminous road at Bakthavachalam 3rd street in Div - 175, unit-40, zone-13.",Grants,13,2017-18,2018-19 B/2017-18/0876,Buildings,Completed,B-Buildings,176,9281000,"RENOVATION TO THE EXISTING WORKING WOMENS HOSTEL BUILDING AT SECOND CROSS STREET,SHASTRI NAGAR,ADYAR IN DN 176,ZONE 13",Own Sources,13,2017-18,2019-20 B/2017-18/14127,Buildings,Completed,B-Buildings,176,11846109,"CONSTRUCTION OF G+1F (12+12) REST ROOMS INSIDE THE SITE OF DHOBIKANA AT BESANT NAGAR IN DIV-176, ZONE-13",MLACDS,13,2017-18,2020-21 B/2017-18/14974,Buildings,Completed,B-Buildings,176,9487274,REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE IN ZONE-11 TO 15,Own Sources,13,2017-18,2020-21 BR/2017-18/12024,Footpath,Completed,BR-Bus Route Roads,176,6278000,"Forming Footpath at Besant Nagar 3rd Avenue in Dn-176, Zone-XIII",Grants,13,2017-18,2019-20 BR/2017-18/12140,Footpath,Completed,BR-Bus Route Roads,176,22669000,"Forming Footpath at Besant Avenue Road in Dn-176, Zone-XIII",Grants,13,2017-18,2019-20 BR/2017-18/2179,Road Cut,Completed,BR-Bus Route Roads,176,770000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (0023/2016/1),Deposit Works,13,2017-18,2018-19 BR/2017-18/2180,Road Cut,Completed,BR-Bus Route Roads,176,760000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (0023/2016/2),Deposit Works,13,2017-18,2018-19 BR/2017-18/2187,Road Cut,Completed,BR-Bus Route Roads,176,849000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (4617/2016/1),Deposit Works,13,2017-18,2018-19 NN/2017-18/10090,Roads,Completed,NN-ADYAR,176,361000,"Improvements to Bituminous road at Venkateswara nagar I street in Division - 176, Zone - XII",Grants,13,2017-18,2018-19 NN/2017-18/10091,Roads,Completed,NN-ADYAR,176,187000,"Improvements to Bituminous road at Besant nagar XXIII cross street in Division - 176, Zone - XII",Grants,13,2017-18,2018-19 NN/2017-18/10092,Roads,Completed,NN-ADYAR,176,308000,"Improvements to Bituminous road at Sastri nagar V cross street in Division - 176, Zone - XII",Grants,13,2017-18,2018-19 NN/2017-18/10093,Roads,Completed,NN-ADYAR,176,85000,"Improvements to Bituminous road at Damodarapuram V street in Division - 176, Zone - XII",Grants,13,2017-18,2018-19 NN/2017-18/10094,Roads,Completed,NN-ADYAR,176,100000,"Improvements to Bituminous road at Customs colony II cross street in Division - 176, Zone - XII",Grants,13,2017-18,2018-19 NN/2017-18/11031,Buildings,Completed,NN-ADYAR,176,2250000,IMPROVEMENT AND REPAIR WORKS FOR BURIAL GROUND (FURNACE 1) BESANT NAGAR IN DIVISION 176 UNIT 38.,Own Sources,13,2017-18,2018-19 NN/2017-18/11097,Electrical,Completed,NN-ADYAR,176,2250000,"PROVIDING PAINTING , RETRO WORKS, AND ELECTRICAL WORKS TO BESANT NAGAR BURIAL GROUND IN DIVISION 176 UNIT 38.",Own Sources,13,2017-18,2018-19 NN/2017-18/11134,Buildings,Completed,NN-ADYAR,176,329000,"Proposed Demolition Building at Chennai Middle School at Dhamodarapuram at Venkateshwara Nagar V th Street in Div- 176, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11259,Buildings,Completed,NN-ADYAR,176,2251000,"Design, Manufacture & Supply of Gasifier and alternate fuel LPG - Furnace II in division 176, unit 38, zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/11261,Buildings,Completed,NN-ADYAR,176,2063000,"Design, Manufacturing and supply of Gasifier & Fuel LPG fired furnace to Crematorium [Furnace 1] in division 176, unit 38, zone 13.",Loans And Grants,13,2017-18,2018-19 NN/2017-18/11262,Buildings,Completed,NN-ADYAR,176,1876000,"Design, Manufacture & Supply of ETP & Chimney with Scrubber & ID Fan in Division 176, Unit 38, Zone 13.",Loans And Grants,13,2017-18,2018-19 NN/2017-18/11263,Buildings,Completed,NN-ADYAR,176,932000,"Maintenance of cremation Ground & Man power services for Six months at Besant nagar burial ground in division 176, unit 38, zone 13.",Loans And Grants,13,2017-18,2018-19 NN/2017-18/11264,Buildings,Completed,NN-ADYAR,176,978000,"Cremation charges including cost of LPG in Besant nagar burial ground for Five months in division 176, unit 38, zone 13.",Loans And Grants,13,2017-18,2018-19 NN/2017-18/11792,Buildings,Completed,NN-ADYAR,176,446000,"Proposed Modern Designed Bins at Elliats Beach 6th avenue Besent Nagar in dn 176, unit-38, zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/11968,Buildings,Completed,NN-ADYAR,176,89000,"Providing Barricading arrangements at Elliots Beach for New year-2018 (First January) in Dn-176, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12282,Buildings,Completed,NN-ADYAR,176,37000,"Providing Barricading arrangements at Elliats Beach for Pongal Festival-2018 in division 176, Unit 38, Zone 13.","Loans, Grants And Own Sources",13,2017-18,2018-19 NN/2017-18/12782,Roads,Completed,NN-ADYAR,176,577000,"RELAYING OF ROAD AT SASTRI NAGAR 9TH CROSS STREET IN DIVISION 176, UNIT 38, ZONE 13.",Grants,13,2017-18,2018-19 NN/2017-18/12783,Roads,Completed,NN-ADYAR,176,1141000,"RELAYING OF ROAD AT SASTRI NAGAR 8TH CROSS STREET IN DIVISION 176, UNIT 38, ZONE 13",Grants,13,2017-18,2018-19 NN/2017-18/12784,Roads,Completed,NN-ADYAR,176,562000,"RELAYING OF ROAD AT RAMASAMY GARDEN IN DIVISION 176, UNIT 38, ZONE 13",Grants,13,2017-18,2018-19 NN/2017-18/13162,Electrical,Completed,NN-ADYAR,176,822700,"Providing Yard lighting, Erection of lamp posts and Electrical Accessories for Besant Nagar (Orur) Burial Ground (Campus) at Besant Nagar in Division-176, Zone-XIII.",Own Sources,13,2017-18,2019-20 NN/2017-18/2736,Buildings,Completed,NN-ADYAR,176,829000,Outsourcing Scavenging Work for the CMS SHASTRI NAGAR ADYAR CH -20 and CMS DHAMODHRAPURAM (for six month)and in Dn-176 Unit-38 Zone - 13,"Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/2924,Buildings,Completed,NN-ADYAR,176,1323998,"Improvement to care and protection center for children (Inside Thamodharapuram school campus) at Thamodharapuram 4th street and Venkateshwara nagar 5th street in Dn-176, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/2938,Buildings,Completed,NN-ADYAR,176,138000,"Improvements to Amma Unavagam at Besant nagar 1st Avenue and Besant Nagar 31st cross street in Dn-176,Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/3058,Buildings,Completed,NN-ADYAR,176,276000,"Improvements to Health Post at Besant Nagar 1st Avenue in Dn-176, Unit-38, Zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/3082,Buildings,Completed,NN-ADYAR,176,500000,"Improvements to PC at Allcot kuppam, Ramasamy Garden, Kabali Thottam, Besant nagar 6th Avenue, Besant Avenue, Kakkan Colony and Venkateshwara Nagar in Dn-176, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/3088,Electrical,Completed,NN-ADYAR,176,587000,"Improvements to Park at Dr.Muthulakshmi Salai ( Aavin Park) and Badmanaba Nagar 5th Street in Dn-176, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/3184,Parks,Completed,NN-ADYAR,176,453000,"Improvements to Road side Park at Besant Nagar 6th Avenue, Besant Nagar 4th main road, Besant Nagar 4th Avenue, Blue Cross StreetBesant nagar 1st avenue, Sastri nagar 1st avenue and D.D Road in Dn-176, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/3186,Buildings,Completed,NN-ADYAR,176,92000,"Improvements to Anganvadi at Besant Nagar 6th avenue, Kakkan Colony and Dhamotharapuram in Dn-176, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/6054,Buildings,Completed,NN-ADYAR,176,1250000,"Outsourcing Scavenging work for Public Conveniences in Division 176, Unit 38, Zone 13 for one year",Own Sources,13,2017-18,2018-19 NN/2017-18/7983,Parks,Completed,NN-ADYAR,176,153000,"Outsourcing maintenance of Padmanaba nagar park in div-176,unit-38,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/7984,Parks,Completed,NN-ADYAR,176,522000,"Outsourcing maintenance of Avin( Dr.Muthulakshmi ) park in div-176,unit-38,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8738,Storm Water Drain,Completed,NN-ADYAR,176,446000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 176, UNIT - 38, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8773,Storm Water Drain,Completed,NN-ADYAR,176,110000,"Repair works to Storm Water Drain at various street in Dn 176, Unit 38, Zone 13.",Own Sources,13,2017-18,2017-18 NN/2017-18/8789,Parks,Completed,NN-ADYAR,176,83250,"Repairs and Improvements to Road side park around the Karl Schmidt Memorial Building at Besant nagar 6th Avenue Elliot's Beach in Dn-176, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 BR/2017-18/0059,Road Cut,Completed,BR-Bus Route Roads,177,2830000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT CITY LINK ROAD FROM VANDIKKARAN STREET TO KAKKAN NAGAR MAIN ROAD IN DIV 177, ZONE- 13",Deposit Works,13,2017-18,2017-18 BR/2017-18/2158,Road Cut,Completed,BR-Bus Route Roads,177,707000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 4619/2016 / 1),Deposit Works,13,2017-18,2019-20 BR/2017-18/2159,Road Cut,Completed,BR-Bus Route Roads,177,733000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 4619/2016 / 2 ),Deposit Works,13,2017-18,2019-20 BR/2017-18/2168,Road Cut,Completed,BR-Bus Route Roads,177,347000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 1072/2017 ),Deposit Works,13,2017-18,2018-19 BR/2017-18/2169,Road Cut,Completed,BR-Bus Route Roads,177,740000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (1111/2017/ 1 ),Deposit Works,13,2017-18,2018-19 BR/2017-18/2170,Road Cut,Completed,BR-Bus Route Roads,177,380000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 1111/2017/ 2 ),Deposit Works,13,2017-18,2018-19 BR/2017-18/2171,Road Cut,Completed,BR-Bus Route Roads,177,672000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 0956/2017 /1),Deposit Works,13,2017-18,2018-19 BR/2017-18/2172,Road Cut,Completed,BR-Bus Route Roads,177,15971,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13,Deposit Works,13,2017-18,2018-19 BR/2017-18/2188,Road Cut,Completed,BR-Bus Route Roads,177,770000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (4617/2016/2),Deposit Works,13,2017-18,2018-19 BR/2017-18/6847,Road Cut,Completed,BR-Bus Route Roads,177,103000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (0131/17),Deposit Works,13,2017-18,2018-19 BR/2017-18/6850,Road Cut,Completed,BR-Bus Route Roads,177,309000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (3759/16),Deposit Works,13,2017-18,2018-19 BR/2017-18/6851,Road Cut,Completed,BR-Bus Route Roads,177,283000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (4600/2016),Deposit Works,13,2017-18,2018-19 NN/2017-18/11669,Roads,Completed,NN-ADYAR,177,278000,"Improvement to BT road at M.G.R Nagar 4th Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11772,Roads,Completed,NN-ADYAR,177,69000,"Improvement to BT road at M.G.R Nagar 8th Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11773,Roads,Completed,NN-ADYAR,177,85000,"Improvement to BT road at M.G.R Nagar 7th Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11774,Roads,Completed,NN-ADYAR,177,100000,"Improvement to BT road at M.G.R Nagar 5th Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11775,Roads,Completed,NN-ADYAR,177,397000,"Improvements to bituminous road at Gangai Nagar 1st Main Road in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11776,Roads,Completed,NN-ADYAR,177,157000,"Improvement to BT road at T.N.H.B.Colony 3rd Avenue ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11777,Roads,Completed,NN-ADYAR,177,32000,"Improvement to BT road at T.N.H.B. Colony 4th Avenue ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11778,Roads,Completed,NN-ADYAR,177,91000,"Improvement to BT road at Mahalakshmi Nagar 4th Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11779,Roads,Completed,NN-ADYAR,177,92000,"Improvement to BT road at Telephone Colony 1st Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11903,Roads,Completed,NN-ADYAR,177,157000,"Improvement to BT road at N.G.O.Colony 1st Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11904,Roads,Completed,NN-ADYAR,177,360000,"Improvement to BT road at Secretariat Colony 1st Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11905,Roads,Completed,NN-ADYAR,177,230000,"Improvement to BT road at Andal Nagar 2nd Main Road ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11906,Roads,Completed,NN-ADYAR,177,194000,"Improvement to BT road at M.G.R Nagar 3rd Cross Street( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11907,Roads,Completed,NN-ADYAR,177,49000,"Improvement to BT road at Ashtalakshmi Nagar 7th Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11908,Roads,Completed,NN-ADYAR,177,78000,"Improvement to BT road at Ashtalakshmi Nagar 8th Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11909,Roads,Completed,NN-ADYAR,177,49000,"Improvement to BT road at Ashtalakshmi Nagar XI Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11910,Roads,Completed,NN-ADYAR,177,140000,"Improvement to BT road at Ashtalakshmi Nagar 12th Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11911,Roads,Completed,NN-ADYAR,177,196000,"Improvement to BT road at Nethaji Colony 6th Cross Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11912,Roads,Completed,NN-ADYAR,177,84000,"Improvement to BT road at Nethaji Colony 9th Cross Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11913,Roads,Completed,NN-ADYAR,177,248000,"Improvement to BT road at Sri Nagar Colony( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11914,Roads,Completed,NN-ADYAR,177,170000,"Improvement to BT road at Andal Nagar Extn Main Road( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11915,Roads,Completed,NN-ADYAR,177,34000,"Improvement to BT road at Vengateshwara Nagar 3rd Main Road- 1st Cross Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11916,Roads,Completed,NN-ADYAR,177,273000,"Improvement to BT road at Vengateshwara Nagar 3rd Main Road- 2nd Cross Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11917,Roads,Completed,NN-ADYAR,177,206000,"Improvement to BT road at Secretariat Colony 1st Cross Street( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11918,Roads,Completed,NN-ADYAR,177,206000,"Attending patch work at Telephone Colony 1st Cross Street( part) & Periyar Nagar 1st Cross Street( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11919,Roads,Completed,NN-ADYAR,177,206000,"Improvement to BT road at Telephone Colony 2nd Street( part), Ex. Servicemen Main Road( part) & Nehru Nagar Bharathiyar Street (Part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11920,Roads,Completed,NN-ADYAR,177,130000,"Improvement to BT road at A.G.S Colony Chockalingam Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11944,Roads,Completed,NN-ADYAR,177,260000,"Attending patch work at Various Roads in Dn-177,U-40(A),Z-XIII",Own Sources,13,2017-18,2017-18 NN/2017-18/11946,Roads,Completed,NN-ADYAR,177,2256000,"Proposed Relaying of Bituminous Concrete road at M.G.R Nagar 2nd Cross Street in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2019-20 NN/2017-18/11947,Roads,Completed,NN-ADYAR,177,417000,"Proposed Relaying of Bituminous Concrete road at V.V.Colony 3rd Street in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2018-19 NN/2017-18/11948,Roads,Completed,NN-ADYAR,177,647000,"Proposed Relaying of Bituminous Concrete road at V.V.Colony 2nd Street in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2018-19 NN/2017-18/11949,Roads,Completed,NN-ADYAR,177,938000,"Proposed Relaying of Bituminous Concrete road at Mohanapuri 3rd Street ( part) in Dn-177,U-40(A),Z-XIII.",Own Sources,13,2017-18,2018-19 NN/2017-18/11950,Roads,Completed,NN-ADYAR,177,678000,"Proposed Relaying of Bituminous Concrete road at Lakshmi Nagar 4th Street ( part) in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2018-19 NN/2017-18/11951,Roads,Completed,NN-ADYAR,177,938000,"Proposed Relaying of Bituminous Concrete road at Lakshmi Nagar 3rd Street in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2018-19 NN/2017-18/11952,Roads,Completed,NN-ADYAR,177,417000,"Proposed Relaying of Bituminous Concrete road at Andal Nagar 1st Cross Street ( part) in Dn-177,U-40(A),Z-XIII",Grants,13,2017-18,2018-19 NN/2017-18/11953,Roads,Completed,NN-ADYAR,177,918000,"Proposed Relaying of Bituminous Concrete road at Andal Nagar 2nd Main Road in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2018-19 NN/2017-18/11954,Roads,Completed,NN-ADYAR,177,1497000,"Proposed Relaying of Bituminous Concrete road at M.G.R Nagar 1st Main Road,1st & 3rd Cross Street in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2018-19 NN/2017-18/11955,Roads,Completed,NN-ADYAR,177,751000,"Proposed Relaying of Bituminous Concrete road at A.G.S Colony 4th Main Road in Dn-177,U-40(A),Z-XIII.",Grants,13,2017-18,2018-19 NN/2017-18/12876,Buildings,Completed,NN-ADYAR,177,43000,IMPROVEMENT WORK OF PARK AT LH Nagar 4th CROSS STREET DN :177 UNIT:40 (A) ZONE:13,Own Sources,13,2017-18,2018-19 NN/2017-18/12878,Buildings,Completed,NN-ADYAR,177,568000,IMPROVEMENT WORK OF PARK AT NNGO Colony 2nd main road DN :177 UNIT:40 (A) ZONE:13,Own Sources,13,2017-18,2020-21 NN/2017-18/12879,Buildings,Completed,NN-ADYAR,177,1117000,IMPROVEMENT WORK OF CHILDREN PLAY FIELD AT LH Nagar 3rd CROSS STREET DN :177 UNIT:40 (A) ZONE:13,Own Sources,13,2017-18,2018-19 NN/2017-18/13109,Parks,Completed,NN-ADYAR,177,191000,"IMPROVEMENT WORK OF PARK AT Gangai Nagar 1st Main road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/15434,Buildings,Completed,NN-ADYAR,177,379000,"Construction of Toilet Building for Conservancy workers at Mahalakshmi Nagar 1st Cross Street in Dn-177, Unit-40A, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/15490,Buildings,Completed,NN-ADYAR,177,2105000,"PROVIDING COMPOUND WALL AND ADDITIONAL IMPROVEMENT WORKS TO COMMUNITY HALL AT NEHRU NAGAR, ANNA STREET IN DIVISION - 177,UNIT - 40A, ZONE - 13",Own Sources,13,2017-18,2019-20 NN/2017-18/17404,Roads,Completed,NN-ADYAR,177,320000,"Improvements to Cement Concrete Road at TNHB Colony 13 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17405,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at TNHB Colony 27 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17406,Roads,Completed,NN-ADYAR,177,220000,"Improvements to Cement Concrete Road at TNHB Colony 28 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17407,Roads,Completed,NN-ADYAR,177,127000,"Improvements to Cement Concrete Road at TNHB Colony 29 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17408,Roads,Completed,NN-ADYAR,177,126000,"Improvements to Cement Concrete Road at TNHB Colony 30Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17409,Roads,Completed,NN-ADYAR,177,112000,"Improvements to Cement Concrete Road at TNHB Colony 31 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17410,Roads,Completed,NN-ADYAR,177,178000,"Improvements to Cement Concrete Road at TNHB Colony 32 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17411,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 33 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17412,Roads,Completed,NN-ADYAR,177,178000,"Improvements to Cement Concrete Road at TNHB Colony 34 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17413,Roads,Completed,NN-ADYAR,177,918000,"Improvements to Cement Concrete Road at TNHB Colony 35 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17414,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 36 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17415,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 37 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17416,Roads,Completed,NN-ADYAR,177,408000,"Improvements to Cement Concrete Road at TNHB Colony 38 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17417,Roads,Completed,NN-ADYAR,177,554000,"Improvements to Cement Concrete Road at TNHB Colony 39 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17418,Roads,Completed,NN-ADYAR,177,289000,"Improvements to Cement Concrete Road at TNHB Colony 40 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17419,Roads,Completed,NN-ADYAR,177,281000,"Improvements to Cement Concrete Road at TNHB Colony 41 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17420,Roads,Completed,NN-ADYAR,177,281000,"Improvements to Cement Concrete Road at TNHB Colony 42 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17421,Roads,Completed,NN-ADYAR,177,230000,"Improvements to Cement Concrete Road at TNHB Colony 43 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17422,Roads,Completed,NN-ADYAR,177,186000,"Improvements to Cement Concrete Road at TNHB Colony 44 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17423,Roads,Completed,NN-ADYAR,177,201000,"Improvements to Cement Concrete Road at TNHB Colony 45 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17424,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at TNHB Colony 46 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17425,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at TNHB Colony 47 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17426,Roads,Completed,NN-ADYAR,177,358000,"Improvements to Cement Concrete Road at TNHB Colony 48 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17427,Roads,Completed,NN-ADYAR,177,454000,"Improvements to Cement Concrete Road at TNHB Colony 49 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17428,Roads,Completed,NN-ADYAR,177,289000,"Improvements to Cement Concrete Road at TNHB Colony 50 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17429,Roads,Completed,NN-ADYAR,177,584000,"Improvements to Cement Concrete Road at TNHB Colony 51 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17430,Roads,Completed,NN-ADYAR,177,753000,"Improvements to Cement Concrete Road at TNHB Colony 55 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17431,Roads,Completed,NN-ADYAR,177,295000,"Improvements to Cement Concrete Road at TNHB Colony 56 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17432,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 63 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17433,Roads,Completed,NN-ADYAR,177,281000,"Improvements to Cement Concrete Road at TNHB Colony 64 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17434,Roads,Completed,NN-ADYAR,177,281000,"Improvements to Cement Concrete Road at TNHB Colony 65 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17435,Roads,Completed,NN-ADYAR,177,569000,"Improvements to Cement Concrete Road at TNHB Colony 66 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17436,Roads,Completed,NN-ADYAR,177,422000,"Improvements to Cement Concrete Road at TNHB Colony 67 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17437,Roads,Completed,NN-ADYAR,177,189000,"Improvements to Cement Concrete Road at TNHB Colony 68 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17438,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 69 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17439,Roads,Completed,NN-ADYAR,177,470000,"Improvements to Cement Concrete Road at TNHB Colony 70 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17440,Roads,Completed,NN-ADYAR,177,311000,"Improvements to Cement Concrete Road at TNHB Colony 71 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17441,Roads,Completed,NN-ADYAR,177,181000,"Improvements to Cement Concrete Road at TNHB Colony 72 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17442,Roads,Completed,NN-ADYAR,177,181000,"Improvements to Cement Concrete Road at TNHB Colony 73 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17443,Roads,Completed,NN-ADYAR,177,320000,"Improvements to Cement Concrete Road at TNHB Colony 74 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17444,Roads,Completed,NN-ADYAR,177,178000,"Improvements to Cement Concrete Road at TNHB Colony 75 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17445,Roads,Completed,NN-ADYAR,177,189000,"Improvements to Cement Concrete Road at TNHB Colony 76 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17446,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 77 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17447,Roads,Completed,NN-ADYAR,177,345000,"Improvements to Cement Concrete Road at TNHB Colony 78 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17448,Roads,Completed,NN-ADYAR,177,345000,"Improvements to Cement Concrete Road at TNHB Colony 79 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17449,Roads,Completed,NN-ADYAR,177,178000,"Improvements to Cement Concrete Road at TNHB Colony 80 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17450,Roads,Completed,NN-ADYAR,177,178000,"Improvements to Cement Concrete Road at TNHB Colony 81 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17451,Roads,Completed,NN-ADYAR,177,397000,"Improvements to Cement Concrete Road at TNHB Colony 82 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17452,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 83 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17453,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 84 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17454,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 85 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17455,Roads,Completed,NN-ADYAR,177,358000,"Improvements to Cement Concrete Road at TNHB Colony 86 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17456,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 87 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17457,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at TNHB Colony 88 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17458,Roads,Completed,NN-ADYAR,177,281000,"Improvements to Cement Concrete Road at TNHB Colony 89 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17459,Roads,Completed,NN-ADYAR,177,569000,"Improvements to Cement Concrete Road at TNHB Colony 90 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17460,Roads,Completed,NN-ADYAR,177,259000,"Improvements to Cement Concrete Road at TNHB Colony 91 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17461,Roads,Completed,NN-ADYAR,177,189000,"Improvements to Cement Concrete Road at TNHB Colony 92 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17462,Roads,Completed,NN-ADYAR,177,189000,"Improvements to Cement Concrete Road at TNHB Colony 93 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17463,Roads,Completed,NN-ADYAR,177,204000,"Improvements to Cement Concrete Road at TNHB Colony 94 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17464,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at TNHB Colony 95 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17465,Roads,Completed,NN-ADYAR,177,189000,"Improvements to Cement Concrete Road at TNHB Colony 96 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17466,Roads,Completed,NN-ADYAR,177,189000,"Improvements to Cement Concrete Road at TNHB Colony 97 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17467,Roads,Completed,NN-ADYAR,177,189000,"Improvements to Cement Concrete Road at TNHB Colony 98 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17468,Roads,Completed,NN-ADYAR,177,798000,"Improvements to Cement Concrete Road at TNHB Colony 100 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17469,Roads,Completed,NN-ADYAR,177,250000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar II Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17470,Roads,Completed,NN-ADYAR,177,171000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 40th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17471,Roads,Completed,NN-ADYAR,177,60000,"Improvements to Cement Concrete Road at TDr. Ambedkar Nagar 74 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17472,Roads,Completed,NN-ADYAR,177,283000,"Improvements to Cement Concrete Road at TDr. Ambedkar Nagar 75 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17473,Roads,Completed,NN-ADYAR,177,238000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 76 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17474,Roads,Completed,NN-ADYAR,177,370000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 77 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17475,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 78 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17476,Roads,Completed,NN-ADYAR,177,194000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 79 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17477,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 80 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17478,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 81 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17479,Roads,Completed,NN-ADYAR,177,370000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 82 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17480,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 83 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17481,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 84 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17482,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 85 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17483,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 86 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17484,Roads,Completed,NN-ADYAR,177,392000,"Improvements to Cement Concrete Road at TDr. Ambedkar Nagar 87th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17485,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 88 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17486,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 89 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17487,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 90th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17488,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at TDr. Ambedkar Nagar 91th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17489,Roads,Completed,NN-ADYAR,177,461000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 92 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17490,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 93 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17491,Roads,Completed,NN-ADYAR,177,370000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 94 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17492,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 95 h Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17493,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 96 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17494,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 97 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17495,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 98 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17496,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 99 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17497,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 100th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17498,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 101 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17499,Roads,Completed,NN-ADYAR,177,321000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 102 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17500,Roads,Completed,NN-ADYAR,177,168000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 103 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17501,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 104 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17502,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 105 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17503,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 106 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17504,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road atDR.Ambedkar Nagar 107 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17505,Roads,Completed,NN-ADYAR,177,321000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 108th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17506,Roads,Completed,NN-ADYAR,177,252000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 109th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17507,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 110 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17508,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar111 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17509,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 112 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17510,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 113 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17511,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 114 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17512,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 115 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17513,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 116 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17514,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 117 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17515,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 118 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17516,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 119th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17517,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 120th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17518,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 121th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17519,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 122 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17520,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 123 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17521,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 124 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17522,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 125 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17523,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 126 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17524,Roads,Completed,NN-ADYAR,177,252000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 127th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17525,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 128 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17526,Roads,Completed,NN-ADYAR,177,194000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 129 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17527,Roads,Completed,NN-ADYAR,177,283000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 130 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17528,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 131 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17529,Roads,Completed,NN-ADYAR,177,304000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 132 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17530,Roads,Completed,NN-ADYAR,177,330000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 133 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17531,Roads,Completed,NN-ADYAR,177,321000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 134 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17532,Roads,Completed,NN-ADYAR,177,290000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 135 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17533,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 136 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17534,Roads,Completed,NN-ADYAR,177,392000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 137 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17535,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 138 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17536,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 139 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17537,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 140 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17538,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 141 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17539,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 142 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17540,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 143 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17541,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 144 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17542,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 145 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17543,Roads,Completed,NN-ADYAR,177,252000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 146 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17544,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 147 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17545,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 148 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17546,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 149 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17547,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 150 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17548,Roads,Completed,NN-ADYAR,177,330000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 151 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17549,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 152 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17550,Roads,Completed,NN-ADYAR,177,163000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 153 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17551,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 154 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17552,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 155 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17553,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 156th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17554,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 157th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17555,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 158th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17556,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 159th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17557,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 160th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17558,Roads,Completed,NN-ADYAR,177,252000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 161 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17559,Roads,Completed,NN-ADYAR,177,250000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 162 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17560,Roads,Completed,NN-ADYAR,177,218000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 163 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17561,Roads,Completed,NN-ADYAR,177,155000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 164 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17562,Roads,Completed,NN-ADYAR,177,155000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 165th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17563,Roads,Completed,NN-ADYAR,177,171000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 166th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17564,Roads,Completed,NN-ADYAR,177,155000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 167th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17565,Roads,Completed,NN-ADYAR,177,171000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 168th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17566,Roads,Completed,NN-ADYAR,177,193000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 169th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17567,Roads,Completed,NN-ADYAR,177,171000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 170th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17568,Roads,Completed,NN-ADYAR,177,171000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 171 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17569,Roads,Completed,NN-ADYAR,177,149000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 172 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17570,Roads,Completed,NN-ADYAR,177,149000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 173 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17571,Roads,Completed,NN-ADYAR,177,149000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 174 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17572,Roads,Completed,NN-ADYAR,177,149000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 175th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17573,Roads,Completed,NN-ADYAR,177,149000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 176th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17574,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 177th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17575,Roads,Completed,NN-ADYAR,177,183000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 178th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17576,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 179th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17577,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 180th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17578,Roads,Completed,NN-ADYAR,177,250000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 181 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17579,Roads,Completed,NN-ADYAR,177,194000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 182 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17580,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 183 Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17581,Roads,Completed,NN-ADYAR,177,128000,"Improvements to Cement Concrete Road at DR.Ambedkar Nagar 184 th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17582,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 185th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17583,Roads,Completed,NN-ADYAR,177,211000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 186th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17584,Roads,Completed,NN-ADYAR,177,231000,"Improvements to Cement Concrete Road at Dr. Ambedkar Nagar 187th Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17585,Roads,Completed,NN-ADYAR,177,783000,"Improvements to Cement Concrete Road at TMahlakshmi nagar IV Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17586,Roads,Completed,NN-ADYAR,177,733000,"Improvements to Cement Concrete Road at Lakshmi NagarV street in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17587,Roads,Completed,NN-ADYAR,177,490000,"Improvements to Cement Concrete Road at Venkateswara Nagar III Main Road I Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17588,Roads,Completed,NN-ADYAR,177,733000,"Improvements to Cement Concrete Road at Venkateswara Nagar III Main Road II Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17589,Roads,Completed,NN-ADYAR,177,733000,"Improvements to Cement Concrete Road at Venkateswara Nagar III Main Road III Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17590,Roads,Completed,NN-ADYAR,177,490000,"Improvements to Cement Concrete Road at Venkateswara Nagar III Main Road IV Lane in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17591,Roads,Completed,NN-ADYAR,177,730000,"Improvements to Cement Concrete Road at Venkateswara Nagar IV Main Road cross street in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17592,Roads,Completed,NN-ADYAR,177,124000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-I in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17593,Roads,Completed,NN-ADYAR,177,127000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-II in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17594,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-III in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17595,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-4 in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17596,Roads,Completed,NN-ADYAR,177,185000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-V in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17597,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-VI in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17598,Roads,Completed,NN-ADYAR,177,185000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-VII in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17599,Roads,Completed,NN-ADYAR,177,243000,"Improvements to Cement Concrete Road at Mazhialagan street-Lane-VIII in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17600,Roads,Completed,NN-ADYAR,177,393000,"Improvements to Cement Concrete Road at Nehru Nagar -Karunanidhi cross street in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17601,Roads,Completed,NN-ADYAR,177,318000,"Improvements to Cement Concrete Road at Nehru Nagar -Thiruvalluvar cross street in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17602,Roads,Completed,NN-ADYAR,177,1194000,"Improvements to Cement Concrete Road at A.L Mudalai 2nd street in Dn-177, Unit-40A, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17960,Roads,Completed,NN-ADYAR,177,1104000,"Improvements to Cement Concrete Road at NARAYANA SWAMY THOTTAM in Dn-173, unit-40, zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17961,Roads,Completed,NN-ADYAR,177,422000,"Improvements to Cement Concrete Road at Raja garamani thottam in Dn-173, unit-40, zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17963,Roads,Completed,NN-ADYAR,177,1994000,"Improvements to Cement Concrete Road at Raja garamani thottam 3rd street in Dn-173, unit-40, zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/2743,Buildings,Completed,NN-ADYAR,177,118000,Name of the work:Outsourcing Scavenging Work for the TNHB 3rd Avenue (CPS) in Dn-177 Unit-40A Zone - 13,Own Sources,13,2017-18,2019-20 NN/2017-18/3031,Buildings,Completed,NN-ADYAR,177,729000,"IMPROVEMENTS TO THE UPHC CENTRE AT SHASTRI NAGAR 4TH STREET AND TNHB COLONY 3 RD AVENUE IN DN-177,UT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/3544,Buildings,Completed,NN-ADYAR,177,1705000,DISMANTLING AND CONSTRUCTION OF PUBLIC TOILET AT Dr. AMBEDKAR NAGAR 3RD MAIN ROAD (65TH LANE) IN DN :177 UNIT:40 (A) ZONE:13,Own Sources,13,2017-18,2018-19 NN/2017-18/7985,Parks,Completed,NN-ADYAR,177,141000,"Outsourcing maintenance of L.H Nagar 4 th cross st park in div-177,unit-40-A,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/7987,Parks,Completed,NN-ADYAR,177,189000,"Outsourcing maintenance of N.N.G.O Colony park in div-177,unit-40-A,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8744,Storm Water Drain,Completed,NN-ADYAR,177,590000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 177, UNIT - 40A, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8775,Buildings,Completed,NN-ADYAR,177,356000,"REPAIRS TO THE ANGANWADI AT NGO COLONY 1st MAIN ROAD & NEW NGO COLONY 2nd MAIN ROAD IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2017-18,2020-21 NN/2017-18/8776,Buildings,Completed,NN-ADYAR,177,323000,"REPAIRS TO THE ANGANWADI AT Dr.AMBEDKAR NAGAR 21th CROSS STREET, Dr.AMBEDKAR NAGAR 18th CROSS STREET, Dr.AMBEDKAR NAGAR 3rd MAIN ROAD IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8916,Storm Water Drain,Completed,NN-ADYAR,177,450000,"Repairs Work to Strom Water Drain at Various Street in Div-177,Unit-40A,Zone-13",Loans And Grants,13,2017-18,2017-18 NN/2017-18/9220,Buildings,Completed,NN-ADYAR,177,198000,"REPAIRS TO THE ANGANWADI AT N.S.K NAGAR 2nd STREET, NEHRU NAGAR ANNA STREET IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2017-18,2020-21 NN/2017-18/9618,Buildings,Completed,NN-ADYAR,177,128000,"Repairs Work to Ammaunavagam at Kakkan Nagar 2nd Cross Street IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/9620,Buildings,Completed,NN-ADYAR,177,89000,"Repairs Work to Ammaunavagam at T.N.H.B.3rd AVENUE IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/9622,Buildings,Completed,NN-ADYAR,177,416000,"Repairs Work to Ammaunavagam at Lake View Road IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2017-18,2018-19 BR/2017-18/11650,Road Cut,Completed,BR-Bus Route Roads,178,151000,RESTORATION OF ROAD CUT AT VARIOUS LOCATIONS IN ZONE-13 (BUS ROUTES AND ROADS ),Deposit Works,13,2017-18,2018-19 BR/2017-18/2189,Road Cut,Completed,BR-Bus Route Roads,178,643000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 (4617/2016/3),Deposit Works,13,2017-18,2018-19 NN/2017-18/11857,Parks,Completed,NN-ADYAR,178,534000,"Improvements to Park at A.G.S. Colony 4th Main Road in Dn 178, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/12541,Roads,Completed,NN-ADYAR,178,1113000,"RELAYING OF ROAD AT SRINIVASA NAGAR EXTN IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12542,Roads,Completed,NN-ADYAR,178,619000,"RELAYING OF ROAD AT SRINIVASA NAGAR III CROSS STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12543,Roads,Completed,NN-ADYAR,178,499000,"RELAYING OF ROAD AT VIJAYANAGAR IV CROSS STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12544,Roads,Completed,NN-ADYAR,178,374000,"RELAYING OF ROAD AT GOMATHY NAGAR IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12545,Roads,Completed,NN-ADYAR,178,1718000,"RELAYING OF ROAD AT DEVI KARUMARIAMMAN MAIN ROAD IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12546,Roads,Completed,NN-ADYAR,178,300000,"RELAYING OF ROAD AT ORANDIAMMAN KOIL AVENUE IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12547,Roads,Completed,NN-ADYAR,178,140000,"IMPROVEMENTS TO BITUMINOUS ROAD AT NATTAR STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12548,Roads,Completed,NN-ADYAR,178,87000,"IMPROVEMENTS TO BITUMINOUS ROAD AT DEVI KARUMARIAMMAN KOIL III STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12550,Roads,Completed,NN-ADYAR,178,62000,"IMPROVEMENTS TO BITUMINOUS ROAD AT RAM NAGAR NORTH EXTN I STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12551,Roads,Completed,NN-ADYAR,178,208000,"IMPROVEMENTS TO BITUMINOUS ROAD AT RAM NAGAR 5TH STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12552,Roads,Completed,NN-ADYAR,178,217000,"IMPROVEMENTS TO BITUMINOUS ROAD AT AT MURUGU NAGAR V STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12554,Roads,Completed,NN-ADYAR,178,148000,"IMPROVEMENTS TO BITUMINOUS ROAD AT KUBERAN NAGAR IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12555,Roads,Completed,NN-ADYAR,178,297000,"IMPROVEMENTS TO BITUMINOUS ROAD AT AGS COLONY III STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12556,Roads,Completed,NN-ADYAR,178,50000,"IMPROVEMENTS TO BITUMINOUS ROAD AT V.O.C.NAGAR IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12557,Roads,Completed,NN-ADYAR,178,51000,"IMPROVEMENTS TO BITUMINOUS ROAD AT SRINIVASA NAGAR I CROSS STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12558,Roads,Completed,NN-ADYAR,178,60000,"IMPROVEMENTS TO BITUMINOUS ROAD AT AGS COLONY IV CROSS STREET EXTN IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12559,Roads,Completed,NN-ADYAR,178,52000,"IMPROVEMENTS TO BITUMINOUS ROAD AT DEVI KARUMARIAMMAN KOIL II STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12560,Roads,Completed,NN-ADYAR,178,475000,"IMPROVEMENTS TO BITUMINOUS ROAD AT VIJAYANAGAR III CROSS STREET IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12561,Roads,Completed,NN-ADYAR,178,947000,"IMPROVEMENTS TO BITUMINOUS ROAD AT RAM NAGAR NORTH EXTN MAIN ROAD IN DIVISION - 178, UNIT - 39, ZONE - XIII",Grants,13,2017-18,2018-19 NN/2017-18/2740,Buildings,Completed,NN-ADYAR,178,1539000,"Out sourcing scavenging work for Government Higher Secondary School in Division-178, Zone-XIII",Own Sources,13,2017-18,2019-20 NN/2017-18/7988,Parks,Completed,NN-ADYAR,178,163000,"Outsourcing maintenance of A G S Colony ( Alacrity ) park in div-178,unit-39,,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/7989,Parks,Completed,NN-ADYAR,178,178000,"Outsourcing maintenance of A G S Colony 4 th main road park in div-178,unit-39,,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8739,Storm Water Drain,Completed,NN-ADYAR,178,350000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 178, UNIT - 39, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8872,Storm Water Drain,Completed,NN-ADYAR,178,200000,"Minor Repairs and Maintenance work of Storm Water Drain at Various Street in Div-178, U-39, Z-13",Own Sources,13,2017-18,2018-19 P/2017-18/13053,Parks,Completed,P-Parks and Playfields,178,9104403,"FORMATION OF NEW PARK AT AGS COLONY IN DN-178, ZONE - XIII",Grants,13,2017-18,2018-19 BR/2017-18/0279,Road Cut,Completed,BR-Bus Route Roads,179,364000,Restoration of Footpath and Road Cut Made by TANGEDCO at Avvai Nagar & Lattice Bridge Road in Zone 13,Deposit Works,13,2017-18,2017-18 BR/2017-18/0280,Road Cut,Completed,BR-Bus Route Roads,179,87000,Restoration of Road Cut Made by CMWSSB at Velachery Main Road In Zone-13,Own Sources,13,2017-18,2018-19 BR/2017-18/0483,Road Cut,Completed,BR-Bus Route Roads,179,158000,Restoration of Road Cut Made by CMWSSB at Velachery Main Road ( K.R Ramasamy street ) In Zone-13,Own Sources,13,2017-18,2018-19 BR/2017-18/0484,Road Cut,Completed,BR-Bus Route Roads,179,71000,Restoration of Road Cut Made by CMWSSB at Velachery Main Road In Zone-13,Own Sources,13,2017-18,2018-19 BR/2017-18/0485,Road Cut,Completed,BR-Bus Route Roads,179,62000,Restoration of Road Cut Made by CMWSSB at Velachery Main Road In Zone-13,Own Sources,13,2017-18,2018-19 BR/2017-18/1135,Road Cut,Completed,BR-Bus Route Roads,179,2050000,Restoration of Road cut made by CMWSSB at Velachery Main Road in Dn-179 Zone -13,Deposit Works,13,2017-18,2017-18 BR/2017-18/1136,Road Cut,Completed,BR-Bus Route Roads,179,820000,Restoration of Road cut made by CMWSSB at LIC Colony Main Road in Dn-179 Zone -13,Deposit Works,13,2017-18,2018-19 BR/2017-18/1137,Road Cut,Completed,BR-Bus Route Roads,179,308000,Restoration of Road cut made by CMWSSB at LIC Colony 2 Street in Dn-179 Zone -13,Deposit Works,13,2017-18,2018-19 BR/2017-18/12094,Road Cut,Completed,BR-Bus Route Roads,179,901000,RESTORATION OF ROAD CUT AT VARIOUS LOCATIONS IN ZONE-11-15,Deposit Works,13,2017-18,2018-19 BR/2017-18/2167,Road Cut,Completed,BR-Bus Route Roads,179,347000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13 ( 1113/2017 ),Deposit Works,13,2017-18,2018-19 BR/2017-18/6995,Roads,Completed,BR-Bus Route Roads,179,1310000,RESTORATION ROAD CUT MADE BY CMWSSB AT VELACHERY MAIN ROAD IN DN 179 ZONE -13,Deposit Works,13,2017-18,2017-18 BR/2017-18/6996,Roads,Completed,BR-Bus Route Roads,179,100000,RESTORATION ROAD CUT MADE BY CMWSSB FOR DR. MUTHULAKSHMI SALAI IN DN 175 ZONE -13,Deposit Works,13,2017-18,2018-19 L/2017-18/10603,Electrical,Completed,L-Electrical,179,3724000,"Supply and Erection of 41nos 8mtr GI lamp post with single Straight Bracket and 1nos 8mtr GI post with Triple Straight bkt with 150/165w LED fittings c.set at Tharamani 100feet road, ( Expect Bridge) only service road ( vijaya nagar signal to Tansi Nagar Juntion) in Velachery Div-179, Zone-XIII.( Deposit work)",Deposit Works,13,2017-18,2018-19 L/2017-18/13275,Electrical,Completed,L-Electrical,179,85500,"Repair and MAINTENANCE WORK FOR THE 20 MTR HIGHMAST AT VIJAYA NAGARA HIGH MAST (Junction of Bus stand), VELACHERY IN DIVISION-179, ZONE-13",Own Sources,13,2017-18,2018-19 NN/2017-18/0094,Buildings,Completed,NN-ADYAR,179,119000,"Outsourcing scavenging work for CPS( for 1year) at Udayam Nagar in Division - 179, Zone-XIII",Own Sources,13,2017-18,2019-20 NN/2017-18/10586,Footpath,Completed,NN-ADYAR,179,694000,"Repair works and Proposed construction of gate and gate pillars in Childrens Play Ground at V.G.P. Selva Nagar 1st Main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/10589,Parks,Completed,NN-ADYAR,179,650000,"Repair works and Proposed construction of gate and gate pillars in Park and Play ground at V.G.P. Selva Nagar 2nd Main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/11940,Roads,Completed,NN-ADYAR,179,1000000,"Attending Patch work with Wet Mix Macadam in Unit-39 (Divisions-178, 179 & 180 list of roads enclosed) Velachery.",Own Sources,13,2017-18,2017-18 NN/2017-18/12084,Footpath,Completed,NN-ADYAR,179,164000,"Repairs works to footpath at Dhandeeswaram Nagar 7th main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12194,Buildings,Completed,NN-ADYAR,179,307000,"Dismantling and Re-Construction of Compound wall (Eastern Side) in UPHC at Seva Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12601,Roads,Completed,NN-ADYAR,179,138000,"Improvements to Bituminous road at Selvi Street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12602,Roads,Completed,NN-ADYAR,179,85000,"Improvements to Bituminous road at Rajambal Street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12603,Roads,Completed,NN-ADYAR,179,87000,"Improvements to Bituminous road at Tansi Nagar 16th Street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12604,Roads,Completed,NN-ADYAR,179,62000,"Improvements to Bituminous road at Kamatchiamman Street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12605,Roads,Completed,NN-ADYAR,179,207000,"Improvements to Bituminous road at Balakrishna Nagar (Tansi nagar XV street) in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12606,Roads,Completed,NN-ADYAR,179,297000,"Improvements to Bituminous road at Balamurugan Nagar III street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12608,Roads,Completed,NN-ADYAR,179,536000,"Improvements to bituminous road at VGP Selva nagar Extn I main road in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12609,Roads,Completed,NN-ADYAR,179,1122000,"Improvements to bituminous road at VGP Selva nagar IV main road in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12611,Roads,Completed,NN-ADYAR,179,677000,"Improvements to bituminous road at V.G.P. Selva Nagar V main road ( Dhandeeswaram V main road & Shanthi street) in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12617,Roads,Completed,NN-ADYAR,179,495048,"Improvements to bituminous road at Bhuvaneswari Nagar I main road in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12628,Roads,Completed,NN-ADYAR,179,66000,"Improvements to bituminous road at Bethel Avenue IV Street (Balamurugan II street) in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12629,Roads,Completed,NN-ADYAR,179,95000,"Improvements to bituminous road at Balamurugan Nagar I Cross Street in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12630,Roads,Completed,NN-ADYAR,179,551000,"Improvements to bituminous road at Tansi Nagar VII Street in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12632,Roads,Completed,NN-ADYAR,179,238000,"Improvements to bituminous road at New Colony III main road in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12633,Roads,Completed,NN-ADYAR,179,284000,"Improvements to bituminous road at Seshadripuram main road in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12635,Roads,Completed,NN-ADYAR,179,313000,"Improvements to bituminous road at V.G.P. Selva Nagar Extn., II main road (V.G.P Selva nagar main road) in Division - 179, Unit - 39, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/12637,Roads,Completed,NN-ADYAR,179,1252000,"Relaying of road at V.G.P. Selva Nagar Extn., II main road ( Baby nagar service road) in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12644,Roads,Completed,NN-ADYAR,179,365000,"Improvements to Bituminous road at L.B. Road 3rd Street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/13075,Buildings,Completed,NN-ADYAR,179,142000,"Repair work to Namma Toilet in Velachery MRTS Railway Station Campus at Velachery - Tambaram main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/13165,Playfields,Completed,NN-ADYAR,179,438000,"Improvements to Childrens Play field at Seshadripuram 1st main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/13168,Parks,Completed,NN-ADYAR,179,364000,"Improvements to Park at Ramagiri Nagar in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/13172,Playfields,Completed,NN-ADYAR,179,413000,"Improvements to Childrens Play field at V.G.P. Selva Nagar Extn., 3rd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/13176,Playfields,Completed,NN-ADYAR,179,191000,"Improvements to Childrens Play field at Shanthi 1st Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/13178,Playfields,Completed,NN-ADYAR,179,308000,"Improvements to Childrens Play field at Pillaiyar Koil Street (Annai Indira Nagar) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/16707,Buildings,Completed,NN-ADYAR,179,3174000,"Repair & Improvement work to Community Hall at Seva Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7655,Road Cut,Completed,NN-ADYAR,179,905000,"Improvements to bituminous road at Bhuvaneshwari Nagar I main road in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7656,Road Cut,Completed,NN-ADYAR,179,829000,"Improvements to bituminous road at V.G.P Selva nagar II main road in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7665,Road Cut,Completed,NN-ADYAR,179,533000,"Improvements to bituminous road at V.G.P Selva nagar III main road in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7666,Road Cut,Completed,NN-ADYAR,179,503000,"Improvements to bituminous road at V.G.P Selva nagar extn V street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7669,Road Cut,Completed,NN-ADYAR,179,503000,"Improvements to bituminous road at V.G.P Selva nagar extn IV street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7670,Road Cut,Completed,NN-ADYAR,179,503000,"Improvements to bituminous road at V.G.P Selva nagar extn III street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7673,Road Cut,Completed,NN-ADYAR,179,533000,"Improvements to bituminous road at V.G.P Selva nagar extn I street in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7674,Road Cut,Completed,NN-ADYAR,179,533000,"Improvements to bituminous road at V.G.P Selva nagar extn I main road in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7675,Road Cut,Completed,NN-ADYAR,179,836000,"Improvements to bituminous road at Bethel avenue in Dn 179, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/7676,Road Cut,Completed,NN-ADYAR,179,151000,"Improvements to Bituminous road in Bethal Avenue I street, Dn-179, Zone-13",Grants,13,2017-18,2018-19 NN/2017-18/7677,Road Cut,Completed,NN-ADYAR,179,151000,"Improvements to Bituminous road in Bethal Avenue II street, Dn-179, Zone-13",Grants,13,2017-18,2018-19 NN/2017-18/7678,Road Cut,Completed,NN-ADYAR,179,151000,"Improvements to Bituminous road in Bethal Avenue III street, Dn-179, Zone-13",Grants,13,2017-18,2018-19 NN/2017-18/7680,Road Cut,Completed,NN-ADYAR,179,118000,"Improvements to Bituminous road in Bethal Avenue IV street, Dn-179, Zone-13",Grants,13,2017-18,2018-19 NN/2017-18/7681,Road Cut,Completed,NN-ADYAR,179,296000,"Improvements to Bituminous road in V.G.P Selva Nagar, 3rd cross street, Dn-179, Zone-13",Grants,13,2017-18,2018-19 NN/2017-18/7682,Road Cut,Completed,NN-ADYAR,179,1089000,"Improvements to bituminous road at Bhuvaneswari nagar III main road in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7684,Road Cut,Completed,NN-ADYAR,179,151000,"Improvements to bituminous road at Railway Road in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7685,Road Cut,Completed,NN-ADYAR,179,328000,"Improvements to bituminous road at Karuna street in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7686,Road Cut,Completed,NN-ADYAR,179,592000,"Improvements to bituminous road at Anna Nagar, 6th main road in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7688,Road Cut,Completed,NN-ADYAR,179,592000,"Improvements to bituminous road at Balakrishna nagar in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7690,Road Cut,Completed,NN-ADYAR,179,296000,"Improvements to bituminous road at Mahavir street in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7691,Road Cut,Completed,NN-ADYAR,179,296000,"Improvements to bituminous road at Amirtham Avenue in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7692,Road Cut,Completed,NN-ADYAR,179,444000,"Improvements to bituminous road at Balamurugan Nagar, 3rd street, in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7695,Road Cut,Completed,NN-ADYAR,179,725000,"Improvements to bituminous road at Seshadripuram I main road in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7712,Roads,Completed,NN-ADYAR,179,1374000,"Improvements to bituminous road atBalakrishna Nagar in Division - 179, Zone - XIII",Grants,13,2017-18,2018-19 NN/2017-18/7990,Parks,Completed,NN-ADYAR,179,154000,"Outsourcing maintenance of Velachery main( Barathiyar park) road park in div-179,unit-39,,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/7991,Parks,Completed,NN-ADYAR,179,172000,"Outsourcing maintenance of Ramangiri nagar park in div-179,unit-39,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7992,Parks,Completed,NN-ADYAR,179,350000,"Outsourcing maintenance of V G P Selva nagar 2 nd main road park in div-179,unit-39,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7994,Parks,Completed,NN-ADYAR,179,186000,"Outsourcing maintenance of 4 th west st Kamarajar nagar park in div-180,unit-39,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8740,Storm Water Drain,Completed,NN-ADYAR,179,638000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 179, UNIT - 39, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8953,Storm Water Drain,Completed,NN-ADYAR,179,220000,"Minor Repairs and Maintenance work of Storm Water Drain at Various Streets in Div-179, U-39, Z-13",Own Sources,13,2017-18,2017-18 NN/2017-18/9267,Buildings,Completed,NN-ADYAR,179,652000,"Improvement works to UPHC (Urban Primary Health Centre) No.128 Seva nagar , Velachery, division-179, unit-39, zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/9279,Buildings,Completed,NN-ADYAR,179,81000,"Repair works to Anganwadi centre nos. 100750314 & 100750315 at New colony main road, Velachery, Dn-179, Unit-39, Zone-13.",Own Sources,13,2017-18,2018-19 BR/2017-18/12029,Footpath,Completed,BR-Bus Route Roads,180,18833000,"Forming Footpath at CSIR Road in Dn-180, Zone-XIII",Grants,13,2017-18,2018-19 D/2017-18/2553,Storm Water Drain,Completed,D-Storm Water Drains,180,494000,"Dismantling and Re- Construction of storm water drain of size 900x900mm crossing L.B.Road at Thiruvanmiyur signal and connecting the existing drain on both side in Dn- 180,Zone-XIII.",Own Sources,13,2017-18,2017-18 NN/2017-18/0197,Buildings,Completed,NN-ADYAR,180,1063000,"Outsourcing scavenging work for CPS, CHSS for 1year at Taramani in Division-180, UNIT 39, Zone-XIII",Own Sources,13,2017-18,2019-20 NN/2017-18/10610,Electrical,Completed,NN-ADYAR,180,714000,"Proposed to Replace and Purchase of 11 Nos of T/L Fitting, 12 Nos of Ceiling Fan, 9 Nos of Wall Mount Fan, 9 Nos of Exhaust Fan, 7 nos of UV/RO palnt, 10 Nos of Weighing Machine, 4 nos of 15 Ltr Pulvarizer, 6 Nos of Water Heater and 2 Nos of Commercial Mixer in Amma Unavagam in Dn-177 to 182 in Zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/12134,Buildings,Completed,NN-ADYAR,180,509000,"Demolition of Chennai Primary School (A-Block 1 & 2) at Perumal Koil Street, Tharamani in Dn 180, Unit 39, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12639,Roads,Completed,NN-ADYAR,180,453000,"Improvements to Bituminous road at Kamaraj Nagar West 2nd main road in Dn 180, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12641,Roads,Completed,NN-ADYAR,180,169000,"Improvements to Bituminous road at Kamaraj Nagar West 5th main road in Dn 180, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12642,Roads,Completed,NN-ADYAR,180,495000,"Improvements to Bituminous road at Tharamani Peeliamman Koil Street in Dn 180, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12643,Roads,Completed,NN-ADYAR,180,156000,"Improvements to Bituminous road at Kattabomman Street in Dn 180, Unit 39, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/12799,Parks,Completed,NN-ADYAR,180,845000,"Repair and Improvement work to Park at 2nd, 4th & 13th West Street, Kamaraj Nagar, in Dn 180, Unit 39, Zone 13.",Own Sources,13,2017-18,2019-20 NN/2017-18/14733,Electrical,Completed,NN-ADYAR,180,152000,"TOILET REPAIR FOR CONSERVANCY LABOUR AT THAMIRABARANI STREET AND MINOR REPAIR WORKS OF PUBLIC CONVINIENCES AT TARAMANI BUS STAND AND PAMMAL NALLATHAMBI STREET IN DIVISION 180, UNIT 39, ZONE 13.","Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/17647,Roads,Completed,NN-ADYAR,180,667000,"Improvements to Cement Concrete Road at Jayanthi Periyar Nagar - Anna Street in Dn-180, Unit-39, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17648,Roads,Completed,NN-ADYAR,180,340000,"Improvements to Cement Concrete Road at Jayanthi Periyar Nagar - Nehru Street in Dn-180, Unit-39, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17649,Roads,Completed,NN-ADYAR,180,177000,"Improvements to Cement Concrete Road at Jayanthi Periyar Nagar - VOC Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17650,Roads,Completed,NN-ADYAR,180,575000,"Improvements to Cement Concrete Road at Indra Nagar - XX Cross Lane in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17651,Roads,Completed,NN-ADYAR,180,340000,"Improvements to Cement Concrete Road at Southside Canal Road in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17652,Roads,Completed,NN-ADYAR,180,1337000,"Improvements to Cement Concrete Road at Gangaiamman Koil Lane in Dn-180, Unit-39, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17653,Roads,Completed,NN-ADYAR,180,209000,"Improvements to Cement Concrete Road at Thanthai Periyar Nagar - Kakkan Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17654,Roads,Completed,NN-ADYAR,180,177000,"Improvements to Cement Concrete Road at Taramani - Kattabomman Lane in Dn-180, Unit-39, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17655,Roads,Completed,NN-ADYAR,180,253000,"Improvements to Cement Concrete Road at Thanthai Periyar Nagar - Kamaraj Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17656,Roads,Completed,NN-ADYAR,180,177000,"Improvements to Cement Concrete Road at M.G. Nagar - Ramar Koil I Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17657,Roads,Completed,NN-ADYAR,180,164000,"Improvements to Cement Concrete Road at Anbazhagan Nagar - Kannagi Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17658,Roads,Completed,NN-ADYAR,180,370000,"Improvements to Cement Concrete Road at Anbazhagan Nagar - Devi Karumariamman Koil I Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17659,Roads,Completed,NN-ADYAR,180,202000,"Improvements to Cement Concrete Road at Anbazhagan Nagar - Devi Karumariamman Koil II Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17660,Roads,Completed,NN-ADYAR,180,63000,"Improvements to Cement Concrete Road at Anbazhagan Nagar - Putthukoil Street in Dn-180, Unit-39, Zone-13",Own Sources,13,2017-18,2019-20 NN/2017-18/17661,Roads,Completed,NN-ADYAR,180,126000,"Improvements to Cement Concrete Road at Anbazhagan Nagar - Sathya Street in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17662,Roads,Completed,NN-ADYAR,180,189000,"Improvements to Cement Concrete Road at Ganthi Cross Street (Taramani) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17663,Roads,Completed,NN-ADYAR,180,98000,"Improvements to Cement Concrete Road at Bajanai koil II Street (kanagam) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17666,Roads,Completed,NN-ADYAR,180,214000,"Improvements to Cement Concrete Road at M.G.R I Street - ( Anna Nagar) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17667,Roads,Completed,NN-ADYAR,180,99000,"Improvements to Cement Concrete Road at M.G.R II Street - ( Anna Nagar) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17668,Roads,Completed,NN-ADYAR,180,167000,"Improvements to Cement Concrete Road at JAYANTHI PERIYAR- BHARATHIYAR STREET in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17669,Roads,Completed,NN-ADYAR,180,279000,"Improvements to Cement Concrete Road at INDRA NAGAR-20TH CROSS STREET - 2 in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17670,Roads,Completed,NN-ADYAR,180,52000,"Improvements to Cement Concrete Road at THANTHAI PERIYAR NAGAR - M.G.R STREET LANE in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17671,Roads,Completed,NN-ADYAR,180,164000,"Improvements to Cement Concrete Road at TARAMANI - PEELIAMMAN KOIL STREET in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17673,Roads,Completed,NN-ADYAR,180,75000,"Improvements to Cement Concrete Road at M.G.NAGAR - N.S.K STREET in Dn-180, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/2932,Buildings,Completed,NN-ADYAR,180,57000,"Repairs and Maintenance work of Amma Unavagam at Taramani Bus stand in DN180, Unit 39, Zone XIII",Own Sources,13,2017-18,2018-19 NN/2017-18/3070,Buildings,Completed,NN-ADYAR,180,191000,"Repairs and Maintenance works of Anganwadi(ICDS) at Tharamani and Thiruvanmiyur in Dn-180, U-39,Z-13",Own Sources,13,2017-18,2018-19 NN/2017-18/6065,Buildings,Completed,NN-ADYAR,180,706000,"Outsourcing Scavenging work for the Public Conveniences in Divison 178, 179 and 180, Unit 39, Zone 13 for one year",Own Sources,13,2017-18,2018-19 NN/2017-18/7993,Parks,Completed,NN-ADYAR,180,158000,"Outsourcing maintenance of 2 nd west st Kamarajar nagar park in div-180,unit-39,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7995,Parks,Completed,NN-ADYAR,180,147000,"Outsourcing maintenance of 13 Th west st Kamarajar nagar park in div-180,unit-39,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8439,Buildings,Completed,NN-ADYAR,180,21000,"Dismantling the dilapidated public convenience at Jayanthi Periyar Nagar ,Thiruvanmiyur in DN180, Unit 39, Zone XIII",Own Sources,13,2017-18,2017-18 NN/2017-18/8741,Storm Water Drain,Completed,NN-ADYAR,180,446000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 180, UNIT - 39, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8820,Buildings,Completed,NN-ADYAR,180,200000,"Minor Repairs and Maintenance work of Storm Water Drain at Various Street in Div-180, U-39, Z-13",Own Sources,13,2017-18,2017-18 D/2017-18/15966,Storm Water Drain,Completed,D-Storm Water Drains,181,2235000,"Dismantling and Re-Construction of storm water drain of size 600x750mm along Malaviya Avenue main road from Malaviya 3rd street to the existing drain at M.G.Road in Dn- 181,Zone-XIII.",Own Sources,13,2017-18,2018-19 NN/2017-18/11444,Roads,Completed,NN-ADYAR,181,460000,"Improvements to Bituminous road at Sriram nagar I cross street (Dhobikana road) in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11445,Roads,Completed,NN-ADYAR,181,428000,"Improvements to Bituminous road at Sivagami puram 2nd cross street in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11447,Roads,Completed,NN-ADYAR,181,361000,"Improvements to Bituminous road at Ashtalakshmi Garden in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11517,Roads,Completed,NN-ADYAR,181,1811000,"Relaying of road at Sivakamipuram I Cross Street in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11518,Roads,Completed,NN-ADYAR,181,745000,"Relaying of road at East Coast Road Cross Street in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11519,Roads,Completed,NN-ADYAR,181,986000,"Relaying of road at Cholapuram in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11520,Roads,Completed,NN-ADYAR,181,1470000,"Relaying of road at T.M.Maistry Street in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11521,Roads,Completed,NN-ADYAR,181,1725000,"Relaying of road at Anna Colony in Division 181, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11523,Roads,Completed,NN-ADYAR,181,810000,"Relaying of BT Patches at Thiruvalluvar Nagar XXXIX Cross Street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11524,Roads,Completed,NN-ADYAR,181,2074000,"Relaying of BT Patches at South Mada Street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11971,Buildings,Completed,NN-ADYAR,181,77000,"Providing Barricading arrangements at Astalakshmi koil Beach and New Beach at Thiruvanmiyur for Pongal festival-2018 in Division-181 and 182 Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/12966,Electrical,Completed,NN-ADYAR,181,403000,"Repairs and Improvements to parks at Gangai street, yamuna street, MGR Street and CGE Colony in division 181, Unit 38, Zone 13.","Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/12972,Electrical,Completed,NN-ADYAR,181,309000,"IMPROVEMENTS AND REPAIR WORKS TO PUBLIC CONVINIENCES AT ASHTALAKSHMI KOIL STREET, THIDEER NAGAR, KAMARAJ SALAI, ODAIKUPPAM, JAYARAM STREET IN DIVISION 181, UNIT 38, ZONE 13.","Loans, Grants And Own Sources",13,2017-18,2018-19 NN/2017-18/14416,Buildings,Completed,NN-ADYAR,181,170000,"Repairs and Improvements to Amma Unavagam at Valmiki Street, CGE Colony in division 181 and Thiruveediamman koil street, Thiruvanmaiyur in division 182, Unit 38, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/17014,Buildings,Completed,NN-ADYAR,181,376000,"IMPROVEMENTS AND REPAIR WORKS TO CHENNAI CORPORATION PRIMARY SCHOOL AT ODAIKUPPAM AND THIRUVANMAIYUR KUPPAM BEACH ROAD, THIRUVANMAIYUR UNDER SDRF IN DIVISION 181, UNIT 38, ZONE 13.",Grants,13,2017-18,2018-19 NN/2017-18/17639,Roads,Completed,NN-ADYAR,181,2210000,"Improvements to Cement Concrete Road at Raja srinivasa Nagar Main Road in Dn-181, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17640,Roads,Completed,NN-ADYAR,181,2210000,"Improvements to Cement Concrete Road at Raja srinivasa Nagar 1st street in Dn-181, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17641,Roads,Completed,NN-ADYAR,181,2210000,"Improvements to Cement Concrete Road at Raja srinivasa Nagar 2nd street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17642,Roads,Completed,NN-ADYAR,181,2090000,"Improvements to Cement Concrete Road at Singaravelan Nagar in Dn-181, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17643,Roads,Completed,NN-ADYAR,181,515000,"Improvements to Cement Concrete Road at Gangaiamman koil street Lane in Dn-181, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/2738,Buildings,Completed,NN-ADYAR,181,592000,"Outsourcing Scavenging Work for the CPS THIRUVANMIYUR KUPPAM BEACH ROAD, CMS at GANDHIGRAMAM and CPS at ODAI KUPPAM (for 1YEAR)and in Dn-181 Unit-38 Zone - 13","Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/3124,Buildings,Completed,NN-ADYAR,181,480000,"Repairs and Improvements to Anganvadis at Dr.Muthulakshmi salai, Valmiki Street, Odaikkuppam , Kuppam Beach Road and Marundeeswarar Nagar in Dn-181, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/7996,Parks,Completed,NN-ADYAR,181,187000,"Outsourcing maintenance of M G R road park in div-181,unit-38,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/7997,Parks,Completed,NN-ADYAR,181,559000,"Outsourcing maintenance of Gangai street park in div-181,unit-38,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/7999,Parks,Completed,NN-ADYAR,181,152000,"Outsourcing maintenance of C G E Colony park in div-181,unit-38,zone-13",Own Sources,13,2017-18,2018-19 NN/2017-18/8742,Storm Water Drain,Completed,NN-ADYAR,181,398000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 181, UNIT - 38, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2018-19 NN/2017-18/8873,Storm Water Drain,Completed,NN-ADYAR,181,105000,MINOR REPAIR WORKS FOR THE STORM WATER DRAIN IN VARIOUS STREETS IN DN.181 UNIT-38 ZONE13.,Loans And Grants,13,2017-18,2017-18 NN/2017-18/9678,Buildings,Completed,NN-ADYAR,181,518000,PROVIDING ROOF TRUSS FOR DHOBIKHANA WASHING AREA AT KALAKSHETRA AVENUE IN DIVISION 181 UNIT 38,Own Sources,13,2017-18,2018-19 BR/2017-18/13328,Footpath,Completed,BR-Bus Route Roads,182,9068000,"Forming Footpath at South Avenue Road in Dn-182, Zone-XIII",Grants,13,2017-18,2019-20 BR/2017-18/13915,Roads,Completed,BR-Bus Route Roads,182,58000,PROVIDING AND LAYING THERMOPLAST PAINTING AND STUD AT KAMARAJ NAGAR 22ND STREET IN DIV-182 ZONE-13.,Own Sources,13,2017-18,2019-20 BR/2017-18/13929,Roads,Completed,BR-Bus Route Roads,182,95000,"PROVIDING AND LAYING THERMOPLAST PAINTING AND STUD AT PUTHIRA KANNIAMMAN KOIL, KAMARAJAR NAGARJ IN DIV-182 ZONE-13.",Own Sources,13,2017-18,2019-20 L/2017-18/10389,Electrical,Completed,L-Electrical,182,482000,"PROVISION OF ELECTRIFICATION AT SMART CLASS WIRING PROPOSED FOR CHSS MADUVANKARAI IN DIV-174 AND CHSS, BHARADIDASAN STREET, THIRUVANMIYUR IN DIV-182, ZONE-XIII",Own Sources,13,2017-18,2018-19 NN/2017-18/11464,Roads,Completed,NN-ADYAR,182,345000,"Improvements to Bituminous Road at Ganapathy nagar 2nd street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11476,Roads,Completed,NN-ADYAR,182,563000,"Improvements to Bituminous Road at Chitrakulam Street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11485,Roads,Completed,NN-ADYAR,182,277000,"Improvements to Bituminous Road at Pandiyan Street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11488,Roads,Completed,NN-ADYAR,182,130000,"Improvements to Bituminous Road at Kamaraj nagar XXII East street Extn. in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11499,Roads,Completed,NN-ADYAR,182,40000,"Improvements to Bituminous Road at PTC Colony I street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11501,Roads,Completed,NN-ADYAR,182,15000,"Improvements to Bituminous Road at PTC Colony II street (Avvai Nagar Main Road) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11504,Roads,Completed,NN-ADYAR,182,69000,"Improvements to Bituminous Road at Kannappa nagar TNHB (Avvai Nagar Main Road) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11508,Roads,Completed,NN-ADYAR,182,172000,"Improvements to Bituminous Road at Thiruvalluvar nagar VII cross street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11509,Roads,Completed,NN-ADYAR,182,277000,"Improvements to Bituminous Road at Pandiyan Street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11673,Roads,Completed,NN-ADYAR,182,511000,"Improvements to BT Road at Kurinji, Mullai, Marutham 1st street (Thiruvalluvar Nagar 7th Main Road from Junction of Thiruvalluvar Nagar 2nd Avenue to Childrens Playground) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11674,Roads,Completed,NN-ADYAR,182,347000,"Improvements to Bituminous Road at Kurinji, Mullai, Marutham 2nd street (Thiruvalluvar Nagar 7th Main Road from Childrens Playground to Junction of East Coast Road) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11675,Roads,Completed,NN-ADYAR,182,156000,"Improvements to Bituminous Road at Kurinji, Mullai, Marudam 3rd street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11676,Roads,Completed,NN-ADYAR,182,543000,"Relaying of BT Patches at Kurinji, Mullai, Marutham 4th street (North Mada Street and West Tank street) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11677,Roads,Completed,NN-ADYAR,182,44000,"Improvements to Bituminous Road at Kurinji, Mullai, Marudam 5th street (part) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11678,Roads,Completed,NN-ADYAR,182,177000,"Improvements to Bituminous Road at Kurinji, Mullai, Marutham 6th street (PTC Colony 1st street Approach road) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11679,Roads,Completed,NN-ADYAR,182,182000,"Improvements to Bituminous Road at Kurinji, Mullai, Marudam 7th street (Approach road) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11680,Roads,Completed,NN-ADYAR,182,45000,"Improvements to Bituminous Road at Kurinji, Mullai, Marutham 8th street (West tank street Approach road) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11681,Roads,Completed,NN-ADYAR,182,87000,"Improvements to Bituminous Road at Kurinji, Mullai, Marudam 9th street in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11682,Roads,Completed,NN-ADYAR,182,260000,"Improvements to Bituminous Road at Kurinji, Mullai, Marudam 10th street (Pillayar Koil Street) in Division 182, Unit 38, Zone 13.",Grants,13,2017-18,2018-19 NN/2017-18/11700,Roads,Completed,NN-ADYAR,182,693000,"Relaying of Road at Kurinji Mullai. marudam Street in Division 182, Unit -13.",Grants,13,2017-18,2018-19 NN/2017-18/11847,Roads,Completed,NN-ADYAR,182,994000,"Providing BT Patchs at Vnkateshwara nagar 4th street, Badmanaba nagar 4th and 5th street, Karpagam garden 2nd main road in dn 176 and Beach road, TM Mastery street in dn 181 and PTC colony 2nd and 4th street, kannappan nagar 3rd cross street, kannappan nagar TNHB road , Ganapathy nagar 1st, 2nd street in dn 182 Unit-38, Zone-13.","Loans, Grants And Own Sources",13,2017-18,2017-18 NN/2017-18/12290,Buildings,Completed,NN-ADYAR,182,139000,"Providing Barricading arrangements at Ashtalakshmi Koil Beach and New Beach at Thiruvanmaiyur for New Year-2018(1st January) in division 181 and 182, Unit 38, Zone 13.","Loans, Grants And Own Sources",13,2017-18,2018-19 NN/2017-18/12331,Buildings,Completed,NN-ADYAR,182,321000,"IMPROVEMENTS AND REPAIR WORKS TO PUBLIC CONVINIENCES AND SMART TOILET IN DIVISION 182, UNIT 38, ZONE 13.","Loans, Grants And Own Sources",13,2017-18,2018-19 NN/2017-18/13222,Playfields,Completed,NN-ADYAR,182,632000,"Repairs and Improvements to park at Thiruvalluvar Nagar 1st Avenue, Thiruvalluvar Nagar 43rd Cross Street and AIBEA Nagar in division 182, Unit 38, Zone 13.","Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/14335,Buildings,Completed,NN-ADYAR,182,169000,"REPAIRS AND IMPROVEMENTS TO E-TOILET AND SMART TOILET AT THIRUVANMIYUR BUS STAND, THIRUVANMAIYUR IN DIVISION 182, UNIT 38, ZONE 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/15000,Buildings,Completed,NN-ADYAR,182,39000,"Repair and Improvements to Conservancy Workers changing room and toilet at Division Office, Thiruvanmiyur in Division 182, Unit 38, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/16998,Buildings,Completed,NN-ADYAR,182,324000,"IMPROVEMENTS AND REPAIR WORKS TO CHENNAI CORPORATION PRIMARY SCHOOL AT BHARATHIDASAN STREET UNDER SDRF IN DIVISION 182, UNIT 38, ZONE 13.",Grants,13,2017-18,2018-19 NN/2017-18/17620,Roads,Completed,NN-ADYAR,182,170000,"Improvements to Cement Concrete Road at Thiruveethiamman Koil II Street in Dn-182, Unit-39, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17626,Roads,Completed,NN-ADYAR,182,210000,"Improvements to Cement Concrete Road at Thiruveethiamman koil II street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17627,Roads,Completed,NN-ADYAR,182,508000,"Improvements to Cement Concrete Road at Thiruveethiamman koil II street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17628,Roads,Completed,NN-ADYAR,182,580000,"Improvements to Cement Concrete Road at Thiruveethiamman koil III street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17630,Roads,Completed,NN-ADYAR,182,707000,"Improvements to Cement Concrete Road at Thiruveethiamman koil IV street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17631,Roads,Completed,NN-ADYAR,182,89000,"Improvements to Cement Concrete Road at I Seaward road in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17632,Roads,Completed,NN-ADYAR,182,407000,"Improvements to Cement Concrete Road at Kamaraj nagar XXVI East street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17633,Roads,Completed,NN-ADYAR,182,392000,"Improvements to Cement Concrete Road at Thirumudivinayagar koil street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17634,Roads,Completed,NN-ADYAR,182,634000,"Improvements to Cement Concrete Road at Puthirankanni amman koil street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17635,Roads,Completed,NN-ADYAR,182,624000,"Improvements to Cement Concrete Road at Mangala Eri main road in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17636,Roads,Completed,NN-ADYAR,182,322000,"Improvements to Cement Concrete Road at Mangala Eri I street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17637,Roads,Completed,NN-ADYAR,182,358000,"Improvements to Cement Concrete Road at Mangala Eri II street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17638,Roads,Completed,NN-ADYAR,182,212000,"Improvements to Cement Concrete Road at Mangala Eri III street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/17644,Roads,Completed,NN-ADYAR,182,46000,"Improvements to Cement Concrete Road at Thiruvalluvar Nagar 54th cross street in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2019-20 NN/2017-18/2734,Buildings,Completed,NN-ADYAR,182,1066000,Outsourcing Scavenging Work for the CHSS HR. SEC. SCHOOL at BARATHITHASAN STREET and CPS at BARATHITHASAN STREET (for 1year)and in Dn-182 Unit-38 Zone - 13,"Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/2942,Buildings,Completed,B-Buildings,182,985000,"IMPROVEMENTS AND REPAIR WORKS TO UPHC AT KAMARAJ NAGAR 8TH EAST STREET IN DIVISION 182, UNIT 38, ZONE 13.","Loans, Grants And Own Sources",13,2017-18,2019-20 NN/2017-18/3149,Buildings,Completed,NN-ADYAR,182,255000,"Repairs and Improvements to Anganvaadi - 33603100411,412,413,414, & 415 at Bharathidhasan street and Avvai nagar main road in Dn-182, Unit-38, Zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/3560,Roads,Completed,NN-ADYAR,182,165000,"PAINTING OF SPEED BREAKERS AT JOURNALISTS COLONY, THIRUVALLUVAR NAGAR 2ND AVENUE IN DIVISION 182, UNIT 38, ZONE 13.","Loans, Grants And Own Sources",13,2017-18,2018-19 NN/2017-18/4111,Parks,Completed,NN-ADYAR,182,339000,Repairs and maintenance works of Traffic island at Thiruvanmiyur in Dn 182 Unit 38 Zone 13,Own Sources,13,2017-18,2018-19 NN/2017-18/6061,Buildings,Completed,NN-ADYAR,182,1222000,"Outsourcing Scavenging work for the Public Convenience in Division 181 and 182, Unit 38, Zone 13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8001,Parks,Completed,NN-ADYAR,182,164000,"Outsourcing maintenance of Valmigi nagar 69 th cross st park in div-182,unit-38,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8002,Parks,Completed,NN-ADYAR,182,181000,"Outsourcing maintenance of Thiruvalluvar nagar 2 nd avenue park in div-182,unit-38,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8003,Parks,Completed,NN-ADYAR,182,175000,"Outsourcing maintenance of Thiruvalluvar nagar 43 rd cross street park in div-182,unit-38,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8005,Parks,Completed,NN-ADYAR,182,355000,"Outsourcing maintenance of Thiruvalluvar nagar 7 th cross street park in div-182,unit-38,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8006,Parks,Completed,NN-ADYAR,182,338000,"Outsourcing maintenance of Thiruvalluvar nagar 1 st avenue park in div-182,unit-38,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8008,Parks,Completed,NN-ADYAR,182,146000,"Outsourcing maintenance of journalist colony park in div-182,unit-38,zone-13.",Own Sources,13,2017-18,2018-19 NN/2017-18/8743,Storm Water Drain,Completed,NN-ADYAR,182,350000,"OUTSOURCING FOR DESILTING OF STORM WATER DRAINS, CLEANING OF CHUTE PIPES, SILT CATCH PITS ETC AT VARIOUS STREETS IN DIVISION - 182, UNIT - 38, ZONE - XIII FOR 60 DAYS",Own Sources,13,2017-18,2017-18 NN/2017-18/8826,Storm Water Drain,Completed,NN-ADYAR,182,315000,"Repairs and Maintanence of Storm Water Drain in DIV-182, U-40, Z-13",Own Sources,13,2017-18,2017-18 NN/2017-18/9283,Buildings,Completed,NN-ADYAR,182,389000,"Providing Smart Class Room in B Block at Chennai Higher Secondary School at Bharathidasan Street in division 182, Unit 38, Zone 13.",Own Sources,13,2017-18,2018-19 D/2017-18/9836,Storm Water Drain,Completed,D-Storm Water Drains,183,2275000,"CONSTRUCTION OF STORM WATER DRAIN OF SIZE 600 X 750MM ALONG RAJIV STREET,KOTTIVAKKAM, IN DN-183,ZONE-14.",Own Sources,14,2017-18,2018-19 L/2017-18/10021,Electrical,Completed,L-Electrical,183,354100,"Work : Supply and Erection of 11Nos of 7mtr hotdip galvanized lamp Post at Kavery Nagar Main road in Division 183,Zone 14",Own Sources,14,2017-18,2017-18 L/2017-18/8133,Electrical,Completed,L-Electrical,183,583500,"Painting of 1967 nos of 6mtr lamp posts with single straight bracket, 857 nos of 6mtr lamp posts with single arch bracket, 70 nos of 8mtr lamp posts with Double arch bracket, 78 nos of 8mtr lamp posts with Single Straight bracket, 10 nos of 8mtr lamp posts with Double Straight bracket and 3 nos of 8mtr lamp posts with Triple arch bracket At Various Locations In division 183,185 and 191, Zone-XIV",Own Sources,14,2017-18,2018-19 L/2017-18/9755,Electrical,Completed,L-Electrical,183,1417100,"Replacement of 2124mtrs of 2x16 sqmm Cable, 1289mtr of 4x16 sqmm Cable at various streets in Division-183,185 &191 Zone-XIV",Own Sources,14,2017-18,2017-18 NP/2017-18/10729,Roads,Completed,NP-PERUNGUDI,183,973000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Venkatesapuram Main Road in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10734,Roads,Completed,NP-PERUNGUDI,183,973000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Kuppam Main Road in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10738,Roads,Completed,NP-PERUNGUDI,183,967000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Anna Nagar, Kalathumedu Cross 3rd Steet to 5th Street in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10739,Roads,Completed,NP-PERUNGUDI,183,921000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Kalathumedu Cross 6th Street, Subramaniyan Street, Swaminathan 4th Street and Vengadessapuram Main Road in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10740,Roads,Completed,NP-PERUNGUDI,183,930000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Anna Street, Kuppam Beach Road in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10741,Roads,Completed,NP-PERUNGUDI,183,991000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Gandhi Street, Vivekanandha 2nd Cross Street in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10743,Roads,Completed,NP-PERUNGUDI,183,993000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Kalathumedu Main Road, Vivekanandha 3rd Street in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10748,Roads,Completed,NP-PERUNGUDI,183,939000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Selvaraj Street, Senthamarai Kannan Street, Vivekanandha 2nd Cross Street in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10752,Roads,Completed,NP-PERUNGUDI,183,954000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Vivekanandha Street , Vengadesapuram 2nd Street & 3rd Street and 7th Street in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10754,Roads,Completed,NP-PERUNGUDI,183,993000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Vengadesapuram 5th Street & 6th Street and 8th Street in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10755,Roads,Completed,NP-PERUNGUDI,183,915000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Vengadesapuram & Kottivakkam Main Road in Dn-183, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12843,Roads,Completed,NP-PERUNGUDI,183,140000,ATTENDING PATCH WORK AT VARIOUS STREET IN DN-183 DUE TO NORTH EAST MONSOON NATURAL CALAMITIES IN DIVISION-183 UNIT-41 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/12975,Buildings,Completed,NP-PERUNGUDI,183,617000,"Improvements to Amma Unavagam at Tharamani Main Road,ECR Main Road in DN-183,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/16037,Buildings,Completed,NP-PERUNGUDI,183,2685000,"Proposed Construction for kitchen room,dining hall and other improvements to existing community hall with electrical arrangements at Kuppam Beach in DN-183, UNIT-41,ZONE-14.",Own Sources,14,2017-18,2019-20 NP/2017-18/4054,Roads,Completed,NP-PERUNGUDI,183,220000,"Providing Thermo plastic compound at Jeganathan street,Raja street,karpagambal nagar,kuppam road and various streets in DN-183,UNIT-41,ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8747,Buildings,Completed,NP-PERUNGUDI,183,131000,"Proposed Construction of Bin platform at Various streets in DN-183,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 B/2017-18/2885,Buildings,Completed,B-Buildings,184,11706000,"CONSTRUCTION OF TERRACE FLOOR AND PROVIDING AMENITIES TO UCHC AT SCHOOL ROAD, PERUNGUDI IN DIVISION - 184, ZONE - 14",Grants,14,2017-18,2019-20 B/2017-18/7023,Buildings,Completed,B-Buildings,184,5560000,"Construction of Compound wall and Laying flooring with Paver block around the Building for UCHC at School road, Perungudi in Div-184, Zone-14",Own Sources,14,2017-18,2019-20 L/2017-18/8126,Electrical,Completed,L-Electrical,184,402200,"Painting of 1143nos of post 6/7mtr lamp post ,748 nos of post 6/7mtr lamp post 64 nos 8mtr lamp post with single arch bracket ,88 nos 8mtr lamp post with double arch bracket , 65nos of kioskpillars and 12nos of busbarpillars Various Locations In Div-184,186 and 189, Zone-XIV",Own Sources,14,2017-18,2018-19 L/2017-18/9308,Electrical,Completed,L-Electrical,184,1776900,"WORK: Proposed Supply & laying of damaged cable repacement of 2046mtrs of 4x16 sqmm Cable, 1587mtr of 2x16 sqmm Cable at various streets in Division-184,186 &189 Zone-XIV",Own Sources,14,2017-18,2017-18 NP/2017-18/10287,Buildings,Completed,NP-PERUNGUDI,184,600000,"Proposed Construction of public convenience at Anna Nedunchalai in DIV-184,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10307,Parks,Completed,NP-PERUNGUDI,184,276000,"REPAIR AND IMPROVEMENT WORKS AT C.B.I. COLONY PARK IN DIVISON -184 UNIT41, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10308,Parks,Completed,NP-PERUNGUDI,184,563500,"REPAIR AND IMPROVEMENT WORKS AT THIRUVALLUVAR NAGAR PARK IN DIVISON -184 UNIT41, ZONE-14",Own Sources,14,2017-18,2019-20 NP/2017-18/10358,Parks,Completed,NP-PERUNGUDI,184,367000,"Repair and Improvement at Ramappa nagar park in division-184, unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10756,Roads,Completed,NP-PERUNGUDI,184,922000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Erikarai Street, Erikarai Cross Street, Kothandaraman Main Road, Kothandaraman Nagar 1st Cross Street, Kodhandaraman Nagar 2nd Cross Street in Dn-184, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10758,Roads,Completed,NP-PERUNGUDI,184,945000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Kothandaraman 3rd Cross Street,, Kothandaraman Nagar 4th Cross Street, Govindhasamy Nagar 1st Street, Govindhasamy Nagar 3rd Street, Govindhasamy Nagar 6th Street in Dn-184, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10759,Roads,Completed,NP-PERUNGUDI,184,910000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Govindhasamy Nagar 2nd Street, Govindhasamy Nagar 4th Street, Govindhasamy Nagar 5th Street, Kulakarai Street in Dn-184, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10761,Roads,Completed,NP-PERUNGUDI,184,872000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Seran Senguttuvan Street, Santhiyappan 1st Cross Street, Sai Ayush Pooja 1st Street,2nd Street, 3rd Street and 4th Street in Dn-184, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10762,Roads,Completed,NP-PERUNGUDI,184,889000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Santhiyappan Salai Main Road, Thiruvalluvar Cross Street, Anna Nedunsalai Street in Dn-184, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10763,Roads,Completed,NP-PERUNGUDI,184,918000,"Restoration of Metro Water(CMWSSB) Road Cut Portion at Sai Ayush Pooja 5th Cross Street, Church Road, Ramappa Nagar Main Road, Telephone Nagar Main Road in Dn-184, Unit-41, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12306,Buildings,Completed,NP-PERUNGUDI,184,167000,"Improvements for MGR Salai NAMMA TOILET and Erikarai salai public convenience in dn-184,Unit-41,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12307,Buildings,Completed,NP-PERUNGUDI,184,267000,"Improvements for Anna Nedunchalai public convenience in dn-184,Unit-41,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12319,Buildings,Completed,NP-PERUNGUDI,184,379000,"Improvements for Amma Unavgam at Anna Nedunchalai,MGR Salai in dn-184,Unit-41,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12845,Roads,Completed,NP-PERUNGUDI,184,329000,ATTENDING PATCH WORK AT VARIOUS STREET IN DN-184 DUE TO NORTH EAST MONSOON NATURAL CALAMITIES IN DIVISION-184 UNIT-41 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/12864,Parks,Completed,NP-PERUNGUDI,184,402000,"Improvements to Ramappa Nagar Park at Vardha Cyclone in dn-184,Unit-41,Zone-14",Own Sources,14,2017-18,2017-18 NP/2017-18/13457,Parks,Completed,NP-PERUNGUDI,184,365000,"Repairs and Improvements to Telephone Nagar Park in Dn-184, Unit-41, Zone-XIV.",Own Sources,14,2017-18,2018-19 NP/2017-18/4055,Roads,Completed,NP-PERUNGUDI,184,220000,"Providing Thermo plastic compound at Anna Nedunchalai,Ramappa Nagar 1st street to 4th street and various streets in DN-184,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/4096,Roads,Completed,NP-PERUNGUDI,184,3353000,"Formation of new B.T Road at Telephone Nagar Main Road in division-184,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/6874,Buildings,Completed,NP-PERUNGUDI,184,429000,"Proposed Construction of Extension of Ground Floor Roof in Existing crematorium Building at School Road in DN-184,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8456,Buildings,Completed,NP-PERUNGUDI,184,841000,"Maintanance of Gasifier Crenatorium for Hindu Burial Ground at School Road in DN-184,Unit-41,Zone-14",Own Sources,14,2017-18,2019-20 NP/2017-18/8749,Buildings,Completed,NP-PERUNGUDI,184,134000,"Proposed Construction of Bin platform at Various streets in DN-184,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/9304,Parks,Completed,NP-PERUNGUDI,184,335000,"Outsourceing maintenance of park at Lakshmanan nagar ( CBI colony 2 nd main road ) in div-184,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9305,Parks,Completed,NP-PERUNGUDI,184,256000,"Outsourceing maintenance of park at Telephone nagar 2 nd cross street in div-184,unit - 41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9306,Parks,Completed,NP-PERUNGUDI,184,170000,"Outsourceing maintenance of park at Anna Nedunchalai Dn-184,unit - 41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9339,Parks,Completed,NP-PERUNGUDI,184,169000,"OUTSOURCEING MAINTENANCE OF PARK AT THIRUVALLUVAR STREET IN DIV-184,UNIT-41,ZONE-14.",Own Sources,14,2017-18,2018-19 BR/2017-18/2148,Road Cut,Completed,BR-Bus Route Roads,185,527000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 (1058/1),Deposit Works,14,2017-18,2018-19 BR/2017-18/2149,Road Cut,Completed,BR-Bus Route Roads,185,515000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 (1058/2),Deposit Works,14,2017-18,2018-19 BR/2017-18/2151,Road Cut,Completed,BR-Bus Route Roads,185,154000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -15 ( 2451/16),Deposit Works,14,2017-18,2018-19 BR/2017-18/2193,Road Cut,Completed,BR-Bus Route Roads,185,772000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 (4617/2016/2),Deposit Works,14,2017-18,2019-20 BR/2017-18/4285,Road Cut,Completed,BR-Bus Route Roads,185,141500,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14,Deposit Works,14,2017-18,2018-19 BR/2017-18/4286,Road Cut,Completed,BR-Bus Route Roads,185,25700,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14,Deposit Works,14,2017-18,2018-19 BR/2017-18/4296,Road Cut,Completed,BR-Bus Route Roads,185,167310,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -11,Deposit Works,14,2017-18,2018-19 BR/2017-18/4297,Road Cut,Completed,BR-Bus Route Roads,185,534000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -11,Deposit Works,14,2017-18,2018-19 BR/2017-18/4299,Road Cut,Completed,BR-Bus Route Roads,185,373000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13,Deposit Works,14,2017-18,2018-19 BR/2017-18/4300,Road Cut,Completed,BR-Bus Route Roads,185,772000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13,Deposit Works,14,2017-18,2018-19 BR/2017-18/4301,Road Cut,Completed,BR-Bus Route Roads,185,772000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -13,Deposit Works,14,2017-18,2018-19 NP/2017-18/0656,Roads,Completed,NP-PERUNGUDI,185,488000,"Forming and laying for C.C Road at kareem Nagar 1st cross street in division-185,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/0658,Roads,Completed,NP-PERUNGUDI,185,661000,"Forming and laying for C.C Road at kareem Nagar 3rd cross street in division-185,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/0664,Roads,Completed,NP-PERUNGUDI,185,743000,"Forming and laying for C.C Road at Subrayan street in division-185,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/0666,Roads,Completed,NP-PERUNGUDI,185,198000,"Forming and laying for C.C Road at Vaithiyar street in division-185,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/0669,Road Cut,Completed,NP-PERUNGUDI,185,466000,"Forming and laying for C.C Road at kareem Nagar 2nd cross street in division-185,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/0678,Roads,Completed,NP-PERUNGUDI,185,560000,"Forming and laying for C.C Road at Ma.Po.Si Street in division-185,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10067,Culvert,Completed,NP-PERUNGUDI,185,450000,"Improvements work for Road crossing Culvert and B Canal link SWD Drain at Govindan Nagar 1st Main Road,Govindan Nagar 6th street,Govindan Nagar 4th street,Govindan Nagar1st cross street,Govindan Nagar 2nd cross street,Govindan Nagar 3rd street,Maniyammai Street 'B'Canal link swd,Ambedkar salai in DN-185,UNIT-41,ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/10313,Parks,Completed,NP-PERUNGUDI,185,59000,"REPAIRS AND IMPROVEMENTS VGP LAYOUT PARK AT DIV 185,Unit-41, Zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10314,Parks,Completed,NP-PERUNGUDI,185,830000,"REPAIRS AND IMPROVEMENTS AT ECR MAIN ROAD PARK AT DIV 185,UNIT 41,ZONE 14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11274,Roads,Completed,NP-PERUNGUDI,185,541000,"Forming and laying for C.C Road at Veeravanchinadhan 3rd Cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/12320,Buildings,Completed,NP-PERUNGUDI,185,142500,"Improvements for Amma Unavgam at E.C.R Main Road,Burma colony in dn-185,Unit-41,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12848,Roads,Completed,NP-PERUNGUDI,185,227000,ATTENDING PATCH WORK AT VARIOUS STREET IN DN-185 DUE TO NORTH EAST MONSOON NATURAL CALAMITIES IN DIVISION-185 UNIT-41 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/12983,Roads,Completed,NP-PERUNGUDI,185,180000,"Supplying and Fixing for Precaste FRC Bench at Palavakkam Beach in DN-185,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/13069,Buildings,Completed,NP-PERUNGUDI,185,359000,"Improvements for Kandasamy Nagar 7th street Anganwadi centre & Aadhi dhiravidar school Toilets IN DN - 185, Unit - 41, Zone - 14",Own Sources,14,2017-18,2018-19 NP/2017-18/13073,Buildings,Completed,NP-PERUNGUDI,185,88000,"Improvements for Kuppam Beach Anganwadi Centre at Anna Salai in DN-185,UNIT-41,ZONE-14",Own Sources,14,2017-18,2019-20 NP/2017-18/2146,Roads,Completed,NP-PERUNGUDI,185,229000,"Forming and laying for C.C Road at A.M.Ali Street in division-185,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/4056,Roads,Completed,NP-PERUNGUDI,185,220000,"Providing Thermo plastic compound at M.G.R Salai,Anna salai,V.G.P Layout,Govind Nagar,Jayshankar Nagar and various streets in DN-185,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/5294,Parks,Completed,NP-PERUNGUDI,185,599000,"PROPOSED OPEN GYM AT VGP NAGAR LAYOUT 4th MAIN ROAD IN DN-185, UNIT-41, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8108,Buildings,Completed,NP-PERUNGUDI,185,510000,"Improvements to UPHC Building at East Coast Road in DN-185,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8750,Buildings,Completed,NP-PERUNGUDI,185,210000,"Proposed Construction of Bin platform at Various streets in DN-185,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8757,Storm Water Drain,Completed,NP-PERUNGUDI,185,992500,"MAINTENANCE AND MINOR REPAIRS TO VARIOUS STREETS IN SIDE DRAIN AND STORM WATER DRAIN IN Dn183,184,185 AND 186,UNIT41,ZONE 14.",Own Sources,14,2017-18,2017-18 NP/2017-18/8764,Storm Water Drain,Completed,NP-PERUNGUDI,185,864000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN IN DN-183, DN-185,DN-186 UNIT-41, ZONE-14.",Own Sources,14,2017-18,2017-18 NP/2017-18/9314,Parks,Completed,NP-PERUNGUDI,185,290000,"OUTSOURCEING MAINTENANCE OF PARK AT V.G.P LAYOUT IN DIV-185,UNIT-41,ZONE-14.",Own Sources,14,2017-18,2018-19 L/2017-18/13693,Electrical,Completed,L-Electrical,186,158600,"Replacement of 20nos Rusted & damaged lamp post with old lamp post at various location in Division-184 ,186&189 Perungudi, Zone-XIV",Own Sources,14,2017-18,2018-19 L/2017-18/3691,Electrical,Completed,L-Electrical,186,782700,"Replacement of damaged CCTV Cameras at Perungudi dumping ground(Due to vardha cyclone) in division 186, zone-14",Own Sources,14,2017-18,2018-19 L/2017-18/9482,Electrical,Completed,L-Electrical,186,769500,"WORK:Provision of Three phase supply for newly constructed UG Water tank at Perungudidumping ground (near zone14 dumping area) in division 186, zone-14",Own Sources,14,2017-18,2017-18 NP/2017-18/10311,Parks,Completed,NP-PERUNGUDI,186,213600,"REPAIR AND IMPROVEMENT WORKS AT OOMAITHURAI PARK IN DIVISON -186 UNIT41, ZONE-14",Own Sources,14,2017-18,2019-20 NP/2017-18/10315,Parks,Completed,NP-PERUNGUDI,186,310000,"REPAIR AND IMPROVEMENT WORKS AT RAJIV NAGAR PARK IN DIVISON -186 UNIT41, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10316,Parks,Completed,NP-PERUNGUDI,186,797000,"REPAIRS AND IMPROVEMENTS AT THIRUMALAI NAGAR PARK AT DIV 186,UNIT 41,ZONE 14.",Own Sources,14,2017-18,2019-20 NP/2017-18/10317,Parks,Completed,NP-PERUNGUDI,186,242000,"REPAIR AND IMPROVEMENT WORKS AT VENGATESWARA NAGAR PARK IN DIVISON -186 UNIT41, ZONE-14",Own Sources,14,2017-18,2019-20 NP/2017-18/11769,Buildings,Completed,NP-PERUNGUDI,186,834000,"Improvements to Damaged Roofing sheet in PDG Mechanical shed and Providing and Laying for hume pipe at variuos zone Garbage Dumping area (PDG) in dn-186,Unit-41,Zone-14",Own Sources,14,2017-18,2019-20 NP/2017-18/12305,Buildings,Completed,NP-PERUNGUDI,186,274000,"Improvements for Amma Unavgam at Corporation Road and Panchyat office road in dn-186,Unit-41,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12851,Roads,Completed,NP-PERUNGUDI,186,327000,ATTENDING PATCH WORK AT VARIOUS STREET IN DN-186 DUE TO NORTH EAST MONSOON NATURAL CALAMITIES IN DIVISION-186 UNIT-41 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/13380,Buildings,Completed,NP-PERUNGUDI,186,151000,"Supplying and Fixing of PVC Sintex Water Tank at Dumping Locations of Zones-11, 12, 13, 15 at Perungudi Dumping Ground (PDG) in Dn-186, Unit-41,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/2886,Roads,Completed,NP-PERUNGUDI,186,1794000,"Forming and laying for C.C Road at Vembuli street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/2887,Roads,Completed,NP-PERUNGUDI,186,2239000,"Forming and laying for C.C Road at Veeravanchinathan 1st street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/2888,Roads,Completed,NP-PERUNGUDI,186,1467000,"Forming and laying for C.C Road at Selavaganapathy Avenue 3rd Main road in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/2890,Roads,Completed,NP-PERUNGUDI,186,1035000,"Forming and laying for C.C Road at Veeravanchinadhan 1st Cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/2893,Roads,Completed,NP-PERUNGUDI,186,423000,"Forming and laying for C.C Road at Panchayat 1st cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/3180,Roads,Completed,NP-PERUNGUDI,186,1693000,"Forming and laying for C.C Road at Selavaganapathy Avenue 6th Cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/4057,Roads,Completed,NP-PERUNGUDI,186,220000,"Providing Thermo plastic compound at Corporation Road,Panchayat Main Road, Thirumalai Nagar,Veerasamy Nagar and various streets in DN-186,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/4062,Roads,Completed,NP-PERUNGUDI,186,789000,"Forming and laying for C.C Road at Veerapandia kattabomman 2nd cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/4099,Roads,Completed,NP-PERUNGUDI,186,602000,"Forming and laying for C.C Road at Veerapandia kattabomman 3rd cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/4705,Roads,Completed,NP-PERUNGUDI,186,526000,"Forming and laying for C.C Road at Elim nagar manthoppu 3rd Cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/4708,Roads,Completed,NP-PERUNGUDI,186,1128000,"Forming and laying for C.C Road at Saravana nagar kudisai paguthi in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/4711,Roads,Completed,NP-PERUNGUDI,186,263000,"Forming and laying for C.C Road at Kalaingar Nagar Seevaram in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/4713,Roads,Completed,NP-PERUNGUDI,186,3498000,"Forming and laying for C.C Road at Thirumalai nagar Anex 1st Lane in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/5247,Roads,Completed,NP-PERUNGUDI,186,541000,"Forming and laying for C.C Road at Veeravanchinathan 4th Cross street in division-186,unit-41,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/5296,Parks,Completed,NP-PERUNGUDI,186,599000,"PROPOSED GYM AT RAJIV NAGAR UIN DN-186, UNIT-41,ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8751,Buildings,Completed,NP-PERUNGUDI,186,140000,"Proposed Construction of Bin platform at Various streets in DN-186,UNIT-41,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8765,Roads,Completed,NP-PERUNGUDI,186,2837000,"Formation of new B.T Road at Veerapandiya kattabomman street in division-186,unit-41,zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/9315,Parks,Completed,NP-PERUNGUDI,186,155000,"OUTSOURCEING MAINTENANCE OF PARK AT OMADURAI STREET IN DIV-186,UNIT-41,ZONE-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9316,Parks,Completed,NP-PERUNGUDI,186,164000,"OUTSOURCING MAINTENANCE OF PARK AT VENKATESHVARA NAGAR FOR THE PERIOD ONE YEAR IN DIV-186,UNIT-41,ZONE-14.",Own Sources,14,2017-18,2018-19 BR/2017-18/2192,Road Cut,Completed,BR-Bus Route Roads,187,823000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 (4617/2016/1),Deposit Works,14,2017-18,2019-20 NP/2017-18/10290,Parks,Completed,NP-PERUNGUDI,187,164000,"REPAIRS AND IMPROVEMENTS WORK AT MAHATMA GANDHI PARK IN DN-187, U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10291,Parks,Completed,NP-PERUNGUDI,187,53000,"REPAIRS AND IMPROVEMENTS WORK OF PARK AT PARK SQUARE COLONY IN DN-187, U-42, Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10292,Parks,Completed,NP-PERUNGUDI,187,205000,"REPAIRS AND IMPROVEMENTS WORK OF PARK AT KARTHIKEYAPURAM 6TH STREET IN DN-187,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/15161,Roads,Completed,NP-PERUNGUDI,187,635500,"PROVIDING NEW SPEED BREAKER AS PER IRC STANDARD WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGN BOARD AND STUDS AT VARIOUS STREETS (IRR ROADS) IN DN-187, U-42, Z-14.",Own Sources,14,2017-18,2019-20 NP/2017-18/4222,Roads,Completed,NP-PERUNGUDI,187,254000,"IMPROVEMENTS TO EXISTING SPEED BREAKER BY PROVIDING THERMOPLAST PAINTING IN DN-187, U-42, Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8818,Buildings,Completed,NP-PERUNGUDI,187,105000,"PROPOSED CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREETS IN DN-187, U-42, Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/9300,Parks,Completed,NP-PERUNGUDI,187,162000,"Outsourceing maintenance of park at Nehru 3rd street ( Mahathma Gandhi park ) in div-187,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9302,Parks,Completed,NP-PERUNGUDI,187,153000,"Outsourceing maintenance of park at KARTHIKEYAPURAM 6 th street ) in div-187,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 BR/2017-18/12527,Roads,Completed,BR-Bus Route Roads,188,140000,REPLACEMENT OF POLYCARBONATE ROOF SHEET TO THE DAMAGED BUS SHELTER AT TAMBARAM TO VELACHERY MAIN ROAD DIV 188 AND MAHATHMA GANDHI NAGAR BUS STOP DIV 193 IN ZONE14 AND ZONE 15,Own Sources,14,2017-18,2018-19 L/2017-18/12348,Electrical,Completed,L-Electrical,188,84166800,"Provision of 1188 nos of 6 Mtr lamp post with Single Straight Bracket 40w-50w LED Fitting and 626 nos of 6 Mtr lamp post with Single Arch Bracket 90w-120w LED Fitting with hot dip zinc galvanising at various places in Division-188, Zone-XIV","Loans, Grants And Own Sources",14,2017-18,2018-19 L/2017-18/1563,Electrical,Completed,L-Electrical,188,771500,"Provision of supply and erection of 19 nos 8 Mtr old Street lamp post with Old 250w SVL Fitting at pallikarnai old dumping ground in Division-188, Zone-XIV",Own Sources,14,2017-18,2017-18 L/2017-18/8138,Electrical,Completed,L-Electrical,188,250600,"Painting of 671 nos of 6mtr lamp posts with single straight bracket, 449 nos of 6mtr lamp posts with single arch bracket, 100 nos of 8mtr lamp posts with Double arch bracket, 38 nos of 8mtr lamp posts with Single Straight bracket and 2 nos of 8mtr lamp posts with Triple arch bracket At Various Locations In division 188, Zone-XIV",Own Sources,14,2017-18,2018-19 L/2017-18/9751,Electrical,Completed,L-Electrical,188,636200,"Replacement of 561 mtrs of 2 x 16 sqmm cable and 881 mtrs of 4 x 16 sqmm cable in various places in division 188, zone-14",Own Sources,14,2017-18,2017-18 NP/2017-18/0231,Bridges,Completed,B-Buildings,188,200000,"PROVIDING FRONT SHED AND IMPROVEMENTS WORK AT MADIPAKKAM UPHC IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10276,Buildings,Completed,NP-PERUNGUDI,188,1289000,"REPAIRS AND IMPROVEMENTS WORK AT DR.RAMAMOORTHY NAGAR PARK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10277,Parks,Completed,NP-PERUNGUDI,188,400000,"REPAIRS AND IMPROVEMENTS WORK AT ANNA NAGAR PARK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10285,Parks,Completed,NP-PERUNGUDI,188,534000,"REPAIRS AND IMPROVEMENTS WORK AT RAJESH NAGAR PARK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10289,Parks,Completed,NP-PERUNGUDI,188,276000,"REPAIRS AND IMPROVEMENTS WORK AT RAJALAKSHMI NAGAR PARK IN DN-188, U-42, Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10799,Roads,Completed,NP-PERUNGUDI,188,226000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 1ST CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10801,Roads,Completed,NP-PERUNGUDI,188,198000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 1ST CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10802,Roads,Completed,NP-PERUNGUDI,188,187000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 1ST CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10803,Roads,Completed,NP-PERUNGUDI,188,192000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 1ST CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10804,Roads,Completed,NP-PERUNGUDI,188,198000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 1ST CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10805,Roads,Completed,NP-PERUNGUDI,188,214000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 1ST CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10806,Roads,Completed,NP-PERUNGUDI,188,204000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 1ST CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10807,Roads,Completed,NP-PERUNGUDI,188,211000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 2ND CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10808,Roads,Completed,NP-PERUNGUDI,188,226000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 4TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10809,Roads,Completed,NP-PERUNGUDI,188,209000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 4TH CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10810,Roads,Completed,NP-PERUNGUDI,188,204000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 4TH CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10811,Roads,Completed,NP-PERUNGUDI,188,221000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 4TH CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10812,Roads,Completed,NP-PERUNGUDI,188,218000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 4TH CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10814,Roads,Completed,NP-PERUNGUDI,188,199000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 4TH CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10815,Roads,Completed,NP-PERUNGUDI,188,377000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 5TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10816,Roads,Completed,NP-PERUNGUDI,188,223000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 5TH CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10817,Roads,Completed,NP-PERUNGUDI,188,181000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 5TH CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10824,Roads,Completed,NP-PERUNGUDI,188,199000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 5TH CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10825,Roads,Completed,NP-PERUNGUDI,188,217000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 5TH CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10827,Roads,Completed,NP-PERUNGUDI,188,235000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 1ST BLOCK 5TH CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10828,Roads,Completed,NP-PERUNGUDI,188,64000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 1ST CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10829,Roads,Completed,NP-PERUNGUDI,188,43000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 2ND CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10830,Roads,Completed,NP-PERUNGUDI,188,43000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 3RD CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10831,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 4TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10832,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 5TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10833,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 6TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10834,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 7TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10835,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 8TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10836,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 9TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10837,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 10TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10838,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 11TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10839,Roads,Completed,NP-PERUNGUDI,188,60000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 12TH CROSS STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10840,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10841,Roads,Completed,NP-PERUNGUDI,188,148000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10843,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10844,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10845,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10846,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10847,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 7TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10848,Roads,Completed,NP-PERUNGUDI,188,119000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 8TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10849,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 9TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10850,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 10TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10851,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 11TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10852,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10853,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10854,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10891,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10892,Roads,Completed,NP-PERUNGUDI,188,297000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10893,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10894,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 7TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10895,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 8TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10896,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 9TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10897,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 10TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10898,Roads,Completed,NP-PERUNGUDI,188,339000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 11TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10899,Roads,Completed,NP-PERUNGUDI,188,64000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 3RD CROSS 12TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10900,Roads,Completed,NP-PERUNGUDI,188,77000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 4TH CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10901,Roads,Completed,NP-PERUNGUDI,188,77000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 4TH CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10902,Roads,Completed,NP-PERUNGUDI,188,64000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 4TH CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10908,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 4TH CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10909,Roads,Completed,NP-PERUNGUDI,188,64000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 4TH CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10912,Roads,Completed,NP-PERUNGUDI,188,119000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 1ST CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10913,Roads,Completed,NP-PERUNGUDI,188,119000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 1ST CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10914,Roads,Completed,NP-PERUNGUDI,188,119000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 1ST CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10915,Roads,Completed,NP-PERUNGUDI,188,119000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 1ST CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10916,Roads,Completed,NP-PERUNGUDI,188,119000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 1ST CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10917,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10927,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10928,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10929,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10930,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10931,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10932,Roads,Completed,NP-PERUNGUDI,188,297000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 7TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10933,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 8TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10934,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 9TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10935,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 10TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10936,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 11TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10937,Roads,Completed,NP-PERUNGUDI,188,339000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 2ND CROSS 12TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10941,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 3RD CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10942,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 3RD CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10943,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 3RD CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10944,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 3RD CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10945,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 3RD CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10946,Roads,Completed,NP-PERUNGUDI,188,149000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 3RD CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10947,Roads,Completed,NP-PERUNGUDI,188,254000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 3RD CROSS 7TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10948,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10949,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10950,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10952,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10953,Roads,Completed,NP-PERUNGUDI,188,85000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10954,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10964,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 7TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10965,Roads,Completed,NP-PERUNGUDI,188,106000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 8TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10966,Roads,Completed,NP-PERUNGUDI,188,339000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 9TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10967,Roads,Completed,NP-PERUNGUDI,188,339000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 3RD MAIN ROAD 4TH CROSS 10TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10969,Roads,Completed,NP-PERUNGUDI,188,189000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 1ST CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10972,Roads,Completed,NP-PERUNGUDI,188,283000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 1ST CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10973,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 1ST CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10975,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 1ST CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10976,Roads,Completed,NP-PERUNGUDI,188,104000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 1ST CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10977,Roads,Completed,NP-PERUNGUDI,188,71000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 2ND CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10978,Roads,Completed,NP-PERUNGUDI,188,71000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 2ND CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10979,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 2ND CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10980,Roads,Completed,NP-PERUNGUDI,188,71000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 3RD CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10981,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 3RD CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10982,Roads,Completed,NP-PERUNGUDI,188,165000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 3RD CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11020,Roads,Completed,NP-PERUNGUDI,188,283000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 4TH CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11021,Roads,Completed,NP-PERUNGUDI,188,236000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 1ST MAIN ROAD 4TH CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11022,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 1ST CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11023,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 1ST CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11025,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 1ST CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11026,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 1ST CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11027,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 1ST CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11028,Roads,Completed,NP-PERUNGUDI,188,95000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11029,Roads,Completed,NP-PERUNGUDI,188,95000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11030,Roads,Completed,NP-PERUNGUDI,188,95000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11032,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11033,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11034,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11035,Roads,Completed,NP-PERUNGUDI,188,95000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 7TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11038,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 8TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11039,Roads,Completed,NP-PERUNGUDI,188,330000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 9TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11040,Roads,Completed,NP-PERUNGUDI,188,71000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 10TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11041,Roads,Completed,NP-PERUNGUDI,188,330000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 2ND CROSS 11TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11042,Roads,Completed,NP-PERUNGUDI,188,71000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 3RD CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11043,Roads,Completed,NP-PERUNGUDI,188,189000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 3RD CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11044,Roads,Completed,NP-PERUNGUDI,188,118000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK 2ND MAIN ROAD 3RD CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11051,Roads,Completed,NP-PERUNGUDI,188,249000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 1ST CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11059,Roads,Completed,NP-PERUNGUDI,188,165000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 1ST CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11063,Roads,Completed,NP-PERUNGUDI,188,149000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 1ST CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11064,Roads,Completed,NP-PERUNGUDI,188,238000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 2ND CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11065,Roads,Completed,NP-PERUNGUDI,188,276000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 2ND CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11067,Roads,Completed,NP-PERUNGUDI,188,204000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 2ND CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11068,Roads,Completed,NP-PERUNGUDI,188,165000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 2ND CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11069,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 2ND CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11070,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 1ST STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11071,Roads,Completed,NP-PERUNGUDI,188,127000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 2ND STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11073,Roads,Completed,NP-PERUNGUDI,188,198000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 3RD STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11074,Roads,Completed,NP-PERUNGUDI,188,184000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 4TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11075,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 5TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11077,Roads,Completed,NP-PERUNGUDI,188,123000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 6TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11078,Roads,Completed,NP-PERUNGUDI,188,137000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 7TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11079,Roads,Completed,NP-PERUNGUDI,188,142000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 8TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11080,Roads,Completed,NP-PERUNGUDI,188,149000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 1ST MAIN ROAD 3RD CROSS 9TH STREET IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11081,Roads,Completed,NP-PERUNGUDI,188,159000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 2ND MAIN ROAD 1ST CROSS IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11083,Roads,Completed,NP-PERUNGUDI,188,212000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 2ND MAIN ROAD 2ND CROSS IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11084,Roads,Completed,NP-PERUNGUDI,188,170000,"FORMATION OF NEW CC ROAD AT MYLLAI BALAJI NAGAR 4TH BLOCK 2ND MAIN ROAD 3RD CROSS IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/11168,Storm Water Drain,Completed,NP-PERUNGUDI,188,867000,"Providing Hume pipe Connections at Srinagar I st Main road, Ram nagar ,kuberan nagar etc IN DN-188,UNIT-42,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/11169,Storm Water Drain,Completed,NP-PERUNGUDI,188,723000,"Providing Hume pipe Connections at Ram nagar 12 th street,Sheela nagar,Ambedkar road,Lakshmi nagar Main road,Sri nagar 4 th street,LIC nagar 6 th street, Veeramamunivar street ,Vasu street ,Ram nagar, Balaji nagar and sai nagar etc IN DN-188,UNIT-42,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12161,Buildings,Completed,NP-PERUNGUDI,188,606000,"REPAIRS AND IMPROVEMENTS TO 16 TH DAY CEREMONY HALL AT AYYAN KULAKARAI STREET IN DIVISION 188, UNIT 42, ZONE 14",Own Sources,14,2017-18,2018-19 NP/2017-18/12162,Buildings,Completed,NP-PERUNGUDI,188,382000,"ADDITIONAL IMPROVEMENTS TO AMMA UNAVAGAM AT MYLLAI BALAJI NAGAR 3RDBLOCK AND MAHALAKSHMI NAGAR IN DN-188, U-42, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/12737,Roads,Completed,NP-PERUNGUDI,188,990000,"ATTENDING ROAD PATCH WORKS IN DN-169, 187 & 188, UNIT-42, ZONE-14.",Own Sources,14,2017-18,2017-18 NP/2017-18/12969,Buildings,Completed,NP-PERUNGUDI,188,1629000,"IMPROVEMENTS WORKS OF ANGANWADI AT MYLLAI BALAJI NAGAR 2ND BLOCK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12981,Buildings,Completed,NP-PERUNGUDI,188,166000,"CONSTRUCTION OF WATER TANK AT MYLLAI BALAJI NAGAR PUBLIC CONVENIENCES (10 NOS) AND NAMMA TOILET AT MADIPKKAM BUS TEMINUS IN DN-188, U-42, Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/14500,Buildings,Completed,NP-PERUNGUDI,188,764000,"CONSTRUCTION OF COMPOUND WALL AT MEENATCHI NAGAR PARK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/14501,Buildings,Completed,NP-PERUNGUDI,188,1115000,"CONSTRUCTION OF COMPOUND WALL AT SENTHIL NAGAR PARK IN DN-188, U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/14502,Buildings,Completed,NP-PERUNGUDI,188,1150000,"CONSTRUCTION OF COMPOUND WALL AT JV NAGAR PARK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/15109,Buildings,Completed,NP-PERUNGUDI,188,257000,"PROVIDING FRONT SHED FOR MULTIPUROPOSE HALL AT MYLLAI BALAJI NAGAR AND MAHALAKSHMI NAGAR IN DN-188,U-14,Z-14",Own Sources,14,2017-18,2019-20 NP/2017-18/15946,Roads,Completed,NP-PERUNGUDI,188,840000,"ANNUAL MAINTENANCE WORK AT ROAD IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/16475,Parks,Completed,P-Parks and Playfields,188,3362000,PLANTATION OF MAINTENANCE OF TREES SAPLINGS FOR ONE YEAR AT VARIOUS PLACES IN ZONE -14,Own Sources,14,2017-18,2019-20 NP/2017-18/4125,Roads,Completed,NP-PERUNGUDI,188,135000,"PROVIDING SPEED BREAKER THERMO PLASTIC PAINTING WORK AT DR.AMBEDKAR SALAI,RAM NAGAR SOUTH 9TH MAIN ROADAND MYLLAI BALAJI NAGAR 1ST BLOCK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2017-18 NP/2017-18/5268,Parks,Completed,NP-PERUNGUDI,188,599000,"PROPOSED OPEN GYM AT RAJALAKSHMAI NAGAR PARK IN DN-188, UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/6482,Roads,Completed,NP-PERUNGUDI,188,815000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGNAGE BOARD,PAVEMENT MARKER, ROAD STRUDS AT VARIOUS STREETS IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2017-18 NP/2017-18/6953,Buildings,Completed,NP-PERUNGUDI,188,821000,"OUTSOURCING FOR PUBLIC CONVENIENCES, NAMMA TOILET & E- TOILET IN DIVISION -183,184,185& 186/UNIT-41, DIVISION 188 /UNIT-42, FOR A PERIOD OF 9 MONTHS IN ZONE-14",Own Sources,14,2017-18,2019-20 NP/2017-18/7215,Buildings,Completed,NP-PERUNGUDI,188,1320000,"REPAIRS AND IMPROVEMENT WORKS OF COMMUNITY HALL AT MYLLAI BALAJI NAGAR 3RD BLOCK IN DN-188,U-42,Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8748,Storm Water Drain,Completed,NP-PERUNGUDI,188,870000,"DESILTING OF STORM WATER AND SIDE DRAIN WORK AT VARIOUS STREET (DN-187-35 Nos & DN-188 - 90Nos) IN DN-187 & DN-188, UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8753,Storm Water Drain,Completed,NP-PERUNGUDI,188,699000,"DESILTING OF CANAL IN (DN-187-IYAPPA NAGAR CANAL, PILLAYAR KOIL STREET CANAL AND , DN-188- MYLAI BALAJI NAGAR - 1st ,2nd,3rd AND 4th BLOCK CANAL) IN DN-187 & 188, UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8754,Storm Water Drain,Completed,NP-PERUNGUDI,188,853000,"DESILTING OF CANAL AT RADIAL ROAD CANAL AND VEERANGAL OODAI CANAL IN DN-188, UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8762,Storm Water Drain,Completed,NP-PERUNGUDI,188,799000,"MINOR REPAIR WORKSOF STORM WATER DRAIN AT 11 LOCATIONS RAMANAGR 6tH,8th,9th,10th MAIN ROAD, RAM NAGAR 7th STREET, RAM NAGAR 8th MAIN ROAD,MYLLAI BALAJI NAGAR 2ND BLOCK,RAJESH NAGAR 1ST MAIN ROAD,PERIYAR NAGAR EXTN 6TH STREET,KANJI KAMATCHI NAGAR MAIN ROAD AND BAJANAI KOIL STREET IN DN-188, UNIT-42, ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/8812,Buildings,Completed,NP-PERUNGUDI,188,102000,"PROPOSED CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREETS IN DN-188, U-42, Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/9303,Parks,Completed,NP-PERUNGUDI,188,160000,"Outsourceing maintenance of park at Rajalaksmi nagar 1 st main road in div-188,unit-42,zone-14.",Own Sources,14,2017-18,2018-19 L/2017-18/12349,Electrical,Completed,L-Electrical,189,39337300,"Provision of of 573nos of 6 mtr Hot dip galvanizing street lamp post with Single straight Bracket with 40-50W LEDfittings and 254 nos of 6 mtr Hot dip galvanizings street lamp post with straight bracket with 90-120W LED fittings set at various street in Div 189,Pallikaranai, Zone XIV","Loans, Grants And Own Sources",14,2017-18,2019-20 L/2017-18/9313,Electrical,Completed,L-Electrical,189,604100,"WORK: Proposed Supply & laying of damaged cable replacement of 662mtrs of 2x16 sqmm Cable, 693mtr of 4x16 sqmm Cable at IIT Colony ,Kamakottinagrar,VGP Shanthinagar and various streets in Division-189 Zone-XIV",Own Sources,14,2017-18,2017-18 NP/2017-18/10345,Buildings,Completed,NP-PERUNGUDI,189,205000,"Repairs and Improvements to Astalakshmi Nagar Park In Dn-189,Unit-43,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10347,Parks,Completed,NP-PERUNGUDI,189,942000,"Repairs and Improvements to IIT Colony Park In Dn-189,Unit-43,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10349,Parks,Completed,NP-PERUNGUDI,189,225000,"Repairs and maintenance to Kamakotti Nagar Park In Dn-189,Unit-43,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10350,Buildings,Completed,NP-PERUNGUDI,189,208000,"Repairs and Improvements to VGP Shanthi Nagar Park In Dn-189,Unit-43,Zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/10351,Electrical,Completed,NP-PERUNGUDI,189,550000,"Repairs and Improvements to Arumugam Nagar 3rd Main Road Park In Dn-189,Unit-43,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/11410,Buildings,Completed,NP-PERUNGUDI,189,266000,"Proposed constuction of public convenience and compound wall at Thulukanathamman koil street shopping complex in Dn 189 Unit-43,Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/11966,Roads,Completed,NP-PERUNGUDI,189,990000,"Attending patch work at Mehru nagar , VGP Shanthi nagar Vallalar st,Kamakotti nagar 1 st street and 3rd st ,IIT Colony 1 st Main road,Lakshmi nagar ,OM Sakthi nagar, Manohar nafar,Bharathi salai etc IN DN-189, Nehru street in Dn 190 and Pillayar Koil street,Jayachandran nagar 1 st Main road,Veerathamman Koil street,Rice Mill road ,Manickam st etc,in Dn 191UNIT-43,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12461,Buildings,Completed,NP-PERUNGUDI,189,755000,CONSTRUCTION OF NEW TOILET AT PARASURAMAN STREET ANGANWADI IN DN-189 UNIT-43 ZONE-14.,Own Sources,14,2017-18,2018-19 NP/2017-18/14226,Parks,Completed,NP-PERUNGUDI,189,37200,"PLAY MATERIALS REPAIR WORK AT THAMARAI KULAM PARK AND IIT COLONY PARK IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/2408,Buildings,Completed,NP-PERUNGUDI,189,180000,CONSTRUCTION OF SEPTIC TANK AT AMMA UNAVAGAM THULUKKANATHAMMAN KOIL STREET IN DN-189 U-43 Z-14,Own Sources,14,2017-18,2017-18 NP/2017-18/8134,Buildings,Completed,NP-PERUNGUDI,189,29000,"Providing Dustbin Platform at Kamakotti Nagar, Thulukkanathamman Koil Street and V.G.P Shanthi Nagar in Div-189, Unit-43, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8141,Buildings,Completed,NP-PERUNGUDI,189,3812000,"Proposed Construction of Dining hall, Kitchen room, Store room ,Toilet & Other improvements to I.I.T Colony Community Hall at I.I.T Colony 3rd main road in Div-189, Unit-43, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8755,Storm Water Drain,Completed,NP-PERUNGUDI,189,657000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN IN DN-184, DN-189, DN-190, DN-191.",Own Sources,14,2017-18,2017-18 NP/2017-18/8774,Storm Water Drain,Completed,NP-PERUNGUDI,189,310000,"MINOR REPAIRS TO STORM WATER DRAIN IN DN-189, DN-190, DN-191,UNIT-43 ZONE-14.",Own Sources,14,2017-18,2017-18 NP/2017-18/9318,Parks,Completed,NP-PERUNGUDI,189,349000,"OUTSOURCEING MAINTENANCE OF PARK AT TAMBARAM - VELACHERY MAIN ROAD (THAMARAI KULAM ) IN DIV-189,UNIT-43,ZONE-14.,",Own Sources,14,2017-18,2018-19 NP/2017-18/9319,Parks,Completed,NP-PERUNGUDI,189,239000,"OUTSOURCEING MAINTENANCE OF PARK AT TAMBARAM - VELACHERY MAIN ROAD (HERBAL ) IN DIV-189,UNIT-43,ZONE-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9320,Parks,Completed,NP-PERUNGUDI,189,289000,"OUTSOURCEING MAINTENANCE OF PARK AT I I T COLONY 3 RD MAIN ROAD IN DIV-189,UNIT-43,ZONE-14.",Own Sources,14,2017-18,2018-19 L/2017-18/12347,Electrical,Completed,L-Electrical,190,23732600,"Provision of 311 nos of 6 Mtr lamp post with Single Straight Bracket 40w-50w LED Fitting and 173 nos of 6 Mtr lamp post with Single Straight Bracket 90w-120w LED Fitting with hot dip zinc galvanising at various places in Division-190 and 191, Zone-XIV","Loans, Grants And Own Sources",14,2017-18,2018-19 NP/2017-18/10309,Buildings,Completed,NP-PERUNGUDI,190,301000,"REPAIRS AND IMPROVEMENTS TO DR.AMBEDKAR PARK AT KANNABIRAN KOIL STREET IN DN-190, UNIT-43, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10320,Parks,Completed,NP-PERUNGUDI,190,546000,"REPAIRS AND IMPROVEMENTS TO CHETTINAD ENCLAVE PARK-1 INCLUDING FORMATION OF SHUTTLE COCK COURT IN DN-190, UNIT-43, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/10325,Buildings,Completed,NP-PERUNGUDI,190,37500,"REPAIRS AND IMPROVEMENTS TO CHETTINAD ENCLAVE PARK-2 IN DN-190, UNIT-43, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12925,Buildings,Completed,NP-PERUNGUDI,190,246000,"Repairs and Improvements to GYM Building at Erikarai Street in Dn-190, Unit-43, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12953,Buildings,Completed,NP-PERUNGUDI,190,48500,"Repairs and Improvements to Public Conveniences at Kovalan Nagar, Kannbiran Koil Street, Karmel Street and Sunnambu Kolathur in Dn-190, Unit-43, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12990,Buildings,Completed,NP-PERUNGUDI,190,679000,"Constructuin of Baby toilet and other improvement works to Anganwadi at Dr.Ambedkar Nagar (near Devikarumariamman Koil) in Dn-190, Unit-43, Zone-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12991,Buildings,Completed,NP-PERUNGUDI,190,459000,"Construction of Compound Wall (Front & side) and other Improvement works to Anganwadi at Kannabiran Koil street in Dn-190, Unit-43, Zone-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/7174,Buildings,Completed,NP-PERUNGUDI,190,148000,"Construction of damaged Compound wall at Kovalan Nagar Burial Ground in DN-190,UNIT-43,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/8142,Buildings,Completed,NP-PERUNGUDI,190,22000,"NAME OF THE WORK : PROVIDING BIN PLATFORM AT SUNNAMBU KOLATHUR ROAD, AMBAL NAGAR 2ND MAIN ROAD, KANNABIRAN KOIL STREET, BHAVANI AMMAN KOIL STREET, VIVEKANANDAR NAGAR 2nd MAIN ROAD, GANAPATHYPURAM MAIN ROAD, ERIKARAI STREET IN DIVISION 190, UNIT 43, ZONE 14.",Own Sources,14,2017-18,2018-19 NP/2017-18/9500,Buildings,Completed,NP-PERUNGUDI,190,139000,"IMPROVEMENTS TO ANGANWADI AT KANNAPIRAN KOIL STREET IN DN-190, UNIT-43, ZONE-14",Own Sources,14,2017-18,2018-19 BR/2017-18/2162,Road Cut,Completed,BR-Bus Route Roads,191,77200,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -14 ( 2818/2016 ),Deposit Works,14,2017-18,2019-20 L/2017-18/15043,Electrical,Completed,L-Electrical,191,1368000,"Supply & Erection of 25nos of 6mtr Street Lamp post post with 2.7Mtr long Single Arch bracket with hot dip galvanizing with 90-120W LED street light fittings set at indiabulls in Div 191, Jalladanpettai. Zone XIV",Own Sources,14,2017-18,2018-19 NP/2017-18/0171,Buildings,Completed,NP-PERUNGUDI,191,224000,"IMPROVEMENTS TO THIRUVALLUVAR NAGAR HEALTH CENTRE IN DIVISION -191,UNIT-43,ZONE-14",Own Sources,14,2017-18,2017-18 NP/2017-18/10168,Buildings,Completed,NP-PERUNGUDI,191,989800,Proposed Construction of Dining hall at Near Community hall for Veerathamman koil street in Dn-191 Unit-43 Zone-14.,Own Sources,14,2017-18,2019-20 NP/2017-18/10301,Parks,Completed,NP-PERUNGUDI,191,145000,REPAIRS AND IMPROVEMENTS TO JAYACHANDIRAN NAGAR 5TH MAIN ROAD PARK IN DN-191 UNIT-43 ZONE-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12403,Buildings,Completed,NP-PERUNGUDI,191,511000,IMPROVEMENTS TO EX SERVICE MAN COLONY ANGANWADI IN DN-191 UNIT-43 ZONE-14.,Own Sources,14,2017-18,2018-19 NP/2017-18/12423,Buildings,Completed,NP-PERUNGUDI,191,179500,IMPROVEMENTS TO THIRUVALLUVAR NAGAR ANGANWADI IN DN-191 UNIT-43 ZONE-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12487,Buildings,Completed,NP-PERUNGUDI,191,102500,PAINTING AND OTHER IMPROVEMENTS WORK TO AMMA UNAVAGAM RICEMILL ROAD IN DN-191 UNIT-43 ZONE-14.,Own Sources,14,2017-18,2018-19 NP/2017-18/12500,Buildings,Completed,NP-PERUNGUDI,191,54000,Painting Work to Amma Unavagam at Ex Service Man Colony 2nd Street In Dn-191 Unit-43 Zone-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12502,Buildings,Completed,NP-PERUNGUDI,191,336700,IMPROVEMENTS TO PUBLIC CONVENIENCE AT KALAIKUTHU NAGAR IN DN-191 UNIT-43 ZONE-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12587,Buildings,Completed,NP-PERUNGUDI,191,174000,PAINTING AND ELECTRICAL WORK TO JAYANTHI NADARAJAN STREET IN DN-191 UNIT-43 ZONE-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12720,Buildings,Completed,NP-PERUNGUDI,191,95600,PAINTING AND ELECTRICAL WORK TO 16th CEREMONY SHED AT GANDHI STREET IN DN-191 UNIT-43 ZONE-14,Own Sources,14,2017-18,2018-19 NP/2017-18/12731,Buildings,Completed,NP-PERUNGUDI,191,38600,"PAINTING AND IMPROVEMENTS WORK TO PUBLIC CONVENENCEY AT GANDHI STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/12970,Buildings,Completed,NP-PERUNGUDI,191,70900,"Improvements to GYM Building at Pillaiyar Koil street in Dn-191, Unit-43, Zone- 14",Own Sources,14,2017-18,2018-19 NP/2017-18/13023,Playfields,Completed,NP-PERUNGUDI,191,148300,"IMPROVEMENTS TO PALLAVAN NAGAR PLAY GROUND 1ST AND 2ND STREET IN DN-191, UNIT-43, ZONE-14",Own Sources,14,2017-18,2018-19 NP/2017-18/16382,Roads,Completed,NP-PERUNGUDI,191,716500,"PROVIDING NEW SPEED BREAKER AS PER IRC STANDARD WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGN BOARD AT VARIOUS STREETS IN DN-191, U-43, Z-14.",Own Sources,14,2017-18,2018-19 NP/2017-18/16992,Buildings,Completed,NP-PERUNGUDI,191,757000,Improvements to Compost Yard at Pudhu Nagar Burial Ground In Dn-191 Unit-43 Zone-14,Own Sources,14,2017-18,2019-20 NP/2017-18/5251,Parks,Completed,NP-PERUNGUDI,191,491000,PROPOSED OPEN GYM AT JAYACHANDIRAN NAGAR 5TH MAIN ROAD PARK IN DN-191 UNIT-43 ZONE-14,Own Sources,14,2017-18,2017-18 NP/2017-18/5299,Roads,Completed,NP-PERUNGUDI,191,196300,"PROVIDING THERMOPLASTIC COMPOUND USING SPEED BREAKERS AT PILLAYAR KOIL STREET , ANNA SALAI, RICE MILL ROAD AND OTHER VARIOUS STREET IN DN-191, UNIT-43, ZONE-14.",Own Sources,14,2017-18,2017-18 NP/2017-18/8429,Buildings,Completed,NP-PERUNGUDI,191,29000,"PROVIDING DUST BIN PLATFORM AT VARIOUS STREET IN STREET IN DN-191,U-43, Z-14",Own Sources,14,2017-18,2018-19 NP/2017-18/9321,Parks,Completed,NP-PERUNGUDI,191,231000,"OUTSOURCEING MAINTENANCE OF PARK AT JAYACHANDRAN NAGAR 5 TH MAIN ROAD IN DIV-191,UNIT-43,ZONE-14.",Own Sources,14,2017-18,2018-19 L/2017-18/10667,Electrical,Completed,L-Electrical,192,188500,"Replacement of damaged 594 mtr of 2X25 Sqmm Alu old cable to new 594 mtrs of 2X16 Sqmm Alu cable in Gandhi kamaraj salai , Aringar Anna Nagar ,1 st Avenue, Thiruvalluar salai , bethal Nagar and variouse street in Dn 192/196 in Zone-XV.",Own Sources,15,2017-18,2018-19 L/2017-18/10669,Electrical,Completed,L-Electrical,192,199000,Replacement of damaged 627 mtr of 2X25 Sqmm Alu old cable to new 627 mtrs of 2X16 Sqmm Alu cable in Senganiamman koil all cross street due to strom water work in Neelangari Dn 192 in Zone-XV.,Own Sources,15,2017-18,2018-19 NQ/2017-18/0824,Buildings,Completed,NQ-SHOZHINGANALLUR,192,300000,"IMPROVEMENT WORK FOR PRIME TOILET AT PERIYA NEELANGARAI KUPPAM IN DN-192, U-44, Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/10771,Electrical,Completed,NQ-SHOZHINGANALLUR,192,47100,Proposed to Purchase of 9 Nos of Megaphone 20W in Dn-192 to 200 in Zone-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/10774,Electrical,Completed,NQ-SHOZHINGANALLUR,192,697900,"Proposed to Replace and Purchase of 19 Nos of Ceiling Fan, 14 Nos of Exhaust Fan,4 nos of Water Heater,4 Nos of UV/RO Plant,5 Nos of Pulvarizer, 4 nos of Wall Mounting fan and 5 Nos of Weighing Machine in Amma Unavagam in Dn-192 to 200 in Zone-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11487,Roads,Completed,NQ-SHOZHINGANALLUR,192,510000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT SARASWATHI NAGAR 1st CROSS STREET (SOUTH) IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11491,Roads,Completed,NQ-SHOZHINGANALLUR,192,747000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT SARASWATHI NAGAR 2nd CROSS STREET (SOUTH) IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11492,Roads,Completed,NQ-SHOZHINGANALLUR,192,827000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT SARASWATHI NAGAR 3RD CROSS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11500,Roads,Completed,NQ-SHOZHINGANALLUR,192,709000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT SARASWATHI NAGAR 4TH CROSS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11620,Roads,Completed,NQ-SHOZHINGANALLUR,192,3204000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT KAPALEESWARAR NAGAR 2nd MAIN ROAD SOUTH IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11660,Roads,Completed,NQ-SHOZHINGANALLUR,192,132000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT KAZURA GARDEN CROSS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11661,Roads,Completed,NQ-SHOZHINGANALLUR,192,264000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT KAZURA GARDEN 1ST CROSS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11662,Roads,Completed,NQ-SHOZHINGANALLUR,192,230000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT KAZURA GARDEN 2ND CROSS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11663,Roads,Completed,NQ-SHOZHINGANALLUR,192,291000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT KAZURA GARDEN 3RD CROSS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11664,Roads,Completed,NQ-SHOZHINGANALLUR,192,232000,LAYING OF BT ROAD USING PAVER FINISHER AT SUNRISE AVENUE 6th CROSS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11666,Roads,Completed,NQ-SHOZHINGANALLUR,192,199000,LAYING OF BT ROAD USING PAVER FINISHER AT PHILIPS STREET IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/15716,Roads,Completed,NQ-SHOZHINGANALLUR,192,730000,"FORMING AND LAYING OF CC ROAD USING PAVER FINISHER AT CLRI NAGAR 2nd MAIN ROAD (VANNAN KULAM), KALATHUMEDU STREET, M.A. VITHIYALINGAM SALAI, RAMP (M.A. VITHIYALINGAM SALAI TO CLRI NAGAR 1st MAIN ROAD ,BHARATHIYAR NAGAR to CLRI Ngar 1st Main Road RAMP AND CLRI NAGAR 1st MAIN ROAD TO CLRI NAGAR 2nd MAIN ROAD) IN DN-192 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/15978,Buildings,Completed,NQ-SHOZHINGANALLUR,192,2080000,IMPROVEMENTS TO PARK AT RAJA NAGAR NEELANGARAI IN DIV-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/1617,Buildings,Completed,NQ-SHOZHINGANALLUR,192,1160000,"Construction of Toilet Block (3+3) Seater for Gents& Ladies at Panchayat Office Main Road in Dn 200,U45, Z15",Own Sources,15,2017-18,2017-18 NQ/2017-18/2569,Buildings,Completed,NQ-SHOZHINGANALLUR,192,164000,Providing Zinc Roofing Sheet for Urban Primary Health Center at Kabaleeswarar beach main road Neelangarai in Dn-192 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/4231,Buildings,Completed,NQ-SHOZHINGANALLUR,192,390000,"CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET IN DN 192, U44, Z15",Own Sources,15,2017-18,2017-18 NQ/2017-18/4249,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,390000,DESILTING OF STORM WATER DRAINS AND SIDE DRAINS AT VARIOUS STREETS IN DN-192 U-44 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/5234,Buildings,Completed,NQ-SHOZHINGANALLUR,192,998000,"Improvement Works for Dhobikhana at vannan kulam in Neelangarai,DN-192,U44,Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/7392,Buildings,Completed,NQ-SHOZHINGANALLUR,192,960000,"Supplying Conservancy Materials and Disinfection for Conservancy Work in Dn-192 to 200 U-44 & 45, in Zone-15 (Period of 5 Months)",Own Sources,15,2017-18,2017-18 NQ/2017-18/7484,Buildings,Completed,NQ-SHOZHINGANALLUR,192,201000,IMPROVEMENT WORK FOR DIVISION OFFICE IN 192 AT NEELANGARAI,Own Sources,15,2017-18,2017-18 NQ/2017-18/7960,Buildings,Completed,NQ-SHOZHINGANALLUR,192,185000,"IMPROVEMENT WORK FOR PRIME TOILET AT CHINNA NEELANGARAI KUPPAM IN DN-192, U-44, Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/8078,Parks,Completed,NQ-SHOZHINGANALLUR,192,94000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT Workers Estate IN DN-192 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9217,Playfields,Completed,NQ-SHOZHINGANALLUR,192,55000,"Providing modular dust bin in beach at Kapaleeswarar Nagar Main Road Beach in Div.192, Unit-44, Zone-15.",Own Sources,15,2017-18,2017-18 NQ/2017-18/9516,Bridges,Completed,NQ-SHOZHINGANALLUR,192,36000,"Providing modular FRP BENCHES AT beach at Kapaleeswarar Nagar Main Road Beach in Div.192, Unit-44, Zone-15.",Own Sources,15,2017-18,2018-19 BR/2017-18/2163,Road Cut,Completed,BR-Bus Route Roads,193,360000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -15 ( 2818/2016 ),Deposit Works,15,2017-18,2019-20 BR/2017-18/2164,Road Cut,Completed,BR-Bus Route Roads,193,244000,Restoration of OFC road cut made by in all Bus Route Road and Interior Roads in Zone -15 (4617/2016),Deposit Works,15,2017-18,2019-20 D/2017-18/14510,Storm Water Drain,Completed,D-Storm Water Drains,193,4424000,"Construction of storm water drain of size 600x750mm along Murugesan nagar from south end to the existing drain at north end in Dn- 193,Zone-XV.",Own Sources,15,2017-18,2018-19 L/2017-18/4149,Electrical,Completed,L-Electrical,193,193300,"Replacement of 12 Nos of faulty timer unt in various locations of dn193,194 & 195 zone 15",Own Sources,15,2017-18,2018-19 NQ/2017-18/0714,Buildings,Completed,NQ-SHOZHINGANALLUR,193,540000,"IMPROVEMENTS OF THE URBAN PRIMARY HEALTH CENTRE AT THORAIPAKKAM-193, U-45,Z-15.",Own Sources,15,2017-18,2017-18 NQ/2017-18/10087,Roads,Completed,NQ-SHOZHINGANALLUR,193,2611000,"FORMING AND LAYING FOR BALAMURUGAN GARDEN 2ND &3RD CROSS STREET IN DN -193 ,U-45 ,Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11505,Buildings,Completed,NQ-SHOZHINGANALLUR,193,949000,"FORMING AND LAYING OF B.T ROAD AT ANANDHA NAGAR 9th STREET IN DN-193,U-45,Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11652,Roads,Completed,NQ-SHOZHINGANALLUR,193,475000,"IMPROVEMENTS TO BT ROAD at Vinayaga Nagar 4th,5th & 6th Cross Street in Dn-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11715,Buildings,Completed,NQ-SHOZHINGANALLUR,193,260000,IMPROVEMENT FOR UPHC AT RAJIV GANDHI SALAI IN DN-193 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12284,Parks,Completed,NQ-SHOZHINGANALLUR,193,780000,"Repair and Improvement works to park at Sai Nagar, RE Nagar and Custom colony Park in Dn-193 U-45 Z-15",Own Sources,15,2017-18,2019-20 NQ/2017-18/12342,Buildings,Completed,NQ-SHOZHINGANALLUR,193,390000,"Proposed Construction of open GYM at inside of Customs Colony Park in Div -193, U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/14392,Parks,Completed,NQ-SHOZHINGANALLUR,193,250000,Proposed Open gym and Improvements at Sai Nagar Park in Div -193 U-45 Zone -15,Own Sources,15,2017-18,2018-19 NQ/2017-18/2494,Buildings,Completed,NQ-SHOZHINGANALLUR,193,116000,Improvements works to Amma Unavagam at Mahathmagandhi Main Road & pandiyan nagar pallavan street in Dn-193 U-45 z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/4264,Buildings,Completed,NQ-SHOZHINGANALLUR,193,225000,CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET IN DN -193 U- 45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/7537,Roads,Completed,NQ-SHOZHINGANALLUR,193,4435000,FORMING AND LAYING OF BT ROAD AT KARPAGA VINAYAGAR NAGAR 10TH&11TH MAIN ROAD IN D-193 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7538,Roads,Completed,NQ-SHOZHINGANALLUR,193,1185000,FORMING BT ROAD AT RE NAGAR 1ST MAIN ROAD IN D-193 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7539,Roads,Completed,NQ-SHOZHINGANALLUR,193,3291000,FORMING AND LAYING BT ROAD AT CUSTOMS COLONY MAIN ROAD IN DN-193 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7571,Roads,Completed,NQ-SHOZHINGANALLUR,193,3100000,"IMPROVEMENTS TO BT ROAD at Anand Nagar 1st,2nd ,&R E Nagar 2nd main road in Dn-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7572,Roads,Completed,NQ-SHOZHINGANALLUR,193,1252000,"IMPROVEMENTS TO BT ROAD at V Vinayaga Nagar 1st,2nd Street & Pillayar koil Street in Dn-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7573,Road Cut,Completed,NQ-SHOZHINGANALLUR,193,2060000,"IMPROVEMENTS TO BT ROAD at MCN Nagar 4th,5th,6th & 10th street, MCN Nagar 1st 2nd & 3rd street MCN Nagar extn and MCN Nagar extn (ellaiamman) in Dn-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7576,Road Cut,Completed,NQ-SHOZHINGANALLUR,193,4680000,"IMPROVEMENTS TO BT ROAD at Sai Nagar 1 to 10 Cross Street & 12th ,13th cross street in Dn-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7750,Roads,Completed,NQ-SHOZHINGANALLUR,193,3540000,"IMPROVEMENTS TO BT ROAD AT SAI NAGAR 1st, 3rd MAIN ROAD IN DN-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7770,Roads,Completed,NQ-SHOZHINGANALLUR,193,1410000,IMPROVEMENTS TO BT ROAD AT SAI NAGAR 2ND MAIN ROAD IN DN-193 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/8099,Parks,Completed,NQ-SHOZHINGANALLUR,193,235000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT ,R.E NAGAR PARK IN DN 193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8110,Parks,Completed,NQ-SHOZHINGANALLUR,193,315000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT SAI NAGAR PARK IN DN 193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8476,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,92000,MINOR REPAIR WORKS AT STORM WATER DRAIN AND SIDE DRAIN @ MURUGESAN NAGAR MAIN ROAD & KARPAGA VINAYAGA NAGAR 9TH MAIN ROAD IN DN-193 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/8822,Roads,Completed,NQ-SHOZHINGANALLUR,193,500000,"Attending patch work with WMM at Thiruvalluvar nagar 1st street ,3rd street, Sainagar 2nd cross street,mahatmagandhi nagar 4th cross street ,customs colony main road,balamurugan garden 1st and 2nd main road,shanthi nikethen main road and post office street in DN-193 U-45 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/9200,Parks,Completed,NQ-SHOZHINGANALLUR,193,314000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT ANANDHA NAGAR PARK IN DN-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9201,Parks,Completed,NQ-SHOZHINGANALLUR,193,257000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT CUSTOMS COLONY PARK IN DN-193 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9769,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,500000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS DN-193 ,U-45 ,Z15",Own Sources,15,2017-18,2017-18 NQ/2017-18/9962,Roads,Completed,NQ-SHOZHINGANALLUR,193,3037000,"FORMING AND LAYING OF B.T ROAD AT MURUGESAN NAGAR 1st ,2nd CROSS STREET & PRABU NAGAR MAIN ROAD IN DN-193,U-45,Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9963,Roads,Completed,NQ-SHOZHINGANALLUR,193,6202000,"FORMING AND LAYING OF B.T ROAD AT PILLAIYAR KOIL STREET IN DN-193,U-45,Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9964,Roads,Completed,NQ-SHOZHINGANALLUR,193,2885000,"FORMING AND LAYING OF B.T ROAD AT BALAMUGAN GARDEN 1ST MAIN ROAD IN DN-193,U-45,Z-15",Own Sources,15,2017-18,2018-19 BR/2017-18/17991,Road Cut,Completed,BR-Bus Route Roads,194,500000,"Restroration of Roadcut made by OFC operators at Secretariat Colony in Dn-194,U-45,Zone - XV",Deposit Works,15,2017-18,2020-21 D/2017-18/7246,Storm Water Drain,Completed,D-Storm Water Drains,194,970000,"Providing and Laying 600mm Dia. NP3 hume pipe across the bund South B canal and Providing shutter for flood control at Secretariate colony in Dn-194,Zone-15.",Own Sources,15,2017-18,2017-18 L/2017-18/1813,Electrical,Completed,L-Electrical,194,140300,"Provision of 1 nos of Kiosk pillar box and Timer unit for Villivakkam MTH road 20 mtr high mast in Division-94,Zone-VIII area",Own Sources,15,2017-18,2017-18 NQ/2017-18/11565,Buildings,Completed,NQ-SHOZHINGANALLUR,194,635000,Construction of compound wall at Raju Nagar 6th street Mettukuppam Burial Ground in DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12280,Parks,Completed,NQ-SHOZHINGANALLUR,194,1130000,"Improvements to the existing park at Secretariat colony park,Sakthi srinivasa park, Chandrasekar Avenue park and PTC Quarters park in Dn-194 U-45 Z-15",Own Sources,15,2017-18,2019-20 NQ/2017-18/12288,Parks,Completed,NQ-SHOZHINGANALLUR,194,640000,Proposed of Open Gym at Secretariate colony park in Dn-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12694,Parks,Completed,NQ-SHOZHINGANALLUR,194,81000,Providing OSR Vacant land boards in Unit-44 & Unit-45 Zone 15,Own Sources,15,2017-18,2018-19 NQ/2017-18/4259,Parks,Completed,NQ-SHOZHINGANALLUR,194,320000,"IMPROVEMENTS TO PLAY APPARATUS AT KUMARAN KUDIL PARK, SECRETARIATE COLONY PARK,PTC QUARTERS PARK, TNHB E12 PARK IN DN-194 & 198 U-45 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/4267,Buildings,Completed,NQ-SHOZHINGANALLUR,194,225000,CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET IN DN -194 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/6959,Roads,Completed,NQ-SHOZHINGANALLUR,194,392000,RELAYING OF BT ROAD AT CHANDRASEKAR NAGAR 1ST CROSS STREET IN DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7200,Buildings,Completed,NQ-SHOZHINGANALLUR,194,410000,REPAIR AND MAINTENANCE OF TRICYCLE (208 NOS) IN DN-192 TO 200 FOR SIX MONTHS U-44 & U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7470,Roads,Completed,NQ-SHOZHINGANALLUR,194,870000,FORMING AND LAYING OF B.T ROAD AT KOKILAMBAL NAGAR MAIN ROAD DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7471,Roads,Completed,NQ-SHOZHINGANALLUR,194,300000,FORMING AND LAYING OF B.T ROAD AT KOKILAMBAL NAGAR 1st STREET DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7472,Roads,Completed,NQ-SHOZHINGANALLUR,194,197000,FORMING AND LAYING OF B.T ROAD AT KOKILAMBAL NAGAR 2nd STREET DN194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7473,Roads,Completed,NQ-SHOZHINGANALLUR,194,197000,FORMING AND LAYING OF B.T ROAD AT KOKILAMBAL NAGAR 3rd STREET DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7474,Roads,Completed,NQ-SHOZHINGANALLUR,194,296000,FOREMING AND LAYING OF B.T ROAD AT KOKILAMBAL NAGAR 4th STREET DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7475,Roads,Completed,NQ-SHOZHINGANALLUR,194,687000,FORMING AND LAYING OF B.T ROAD AT ALAGAPPA NAGAR MAIN ROAD DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7477,Roads,Completed,NQ-SHOZHINGANALLUR,194,888000,FORMING AND LAYING OF B.T ROAD AT ALAGAPPA NAGAR 1st STREET DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7478,Roads,Completed,NQ-SHOZHINGANALLUR,194,355000,FORMING AND LAYING OF B.T ROAD AT ALAGAPPA NAGAR 2nd STREET DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7479,Roads,Completed,NQ-SHOZHINGANALLUR,194,288000,FORMING AND LAYING OF B.T ROAD AT ALAGAPPA NAGAR 3rd STREET DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7481,Roads,Completed,NQ-SHOZHINGANALLUR,194,352000,FORMING AND LAYING OF B.T ROAD AT ALAGAPPA NAGAR 4th STREET DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7483,Roads,Completed,NQ-SHOZHINGANALLUR,194,1901000,"FORMING AND LAYING OF B.T ROAD AT VPG AVENUE EXTN 1ST,2ND DN-194 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8103,Parks,Completed,NQ-SHOZHINGANALLUR,194,590000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT SECRETARIAT COLONY 1ST MAIN ROAD IN DN 194 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8104,Parks,Completed,NQ-SHOZHINGANALLUR,194,83000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT PTC QUARTERS PARK IN DN 194 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8478,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,293000,"MINOR REPAIR WORKS TO STORM WATER DRAIN AND SIDE DRAIN AT KUMARANKUDIL ANEX MAIN ROAD, KUMARAN KUDIL ANEX 6TH CROSS STREET , SECRETARIATE COLONY MAIN ROAD & SAKTHI SRINIVASA ROAD IN DN-194 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8480,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,595000,"PROVIDING CULVERT OF SIZE (4X4) FEET AT VPG AVENUE MAIN ROAD, VPG AVENUE PILLAIYAR KOIL STREET AND VPG AVENUE EXTN IN DN-194 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8821,Roads,Completed,NQ-SHOZHINGANALLUR,194,500000,"Attending patch work with WMM at Devaraj avenue, Sulamanagar main road,Bharathiyar nagar main road, Eswaran koil street, sectraitcolony1st to 7th cross street,Aligandeswarar nagar main road,Foundary salai Kumaran kudil 4th cross street ,and Industrail estate road in DN-194 U-45 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/9203,Parks,Completed,NQ-SHOZHINGANALLUR,194,218000,"OUTSOURCING OF PARK MAITAINANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTANANCE FOR 6 MONTHS (180 DAYS) AT CHANDRASEKAR AVENUE PARK IN DN-194 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9204,Parks,Completed,NQ-SHOZHINGANALLUR,194,93000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT SAKTHI SRINIVASA NAGAR PARK IN DN 194 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9344,Roads,Completed,NQ-SHOZHINGANALLUR,194,1811000,RELAYING BT ROAD AT SECTRAITCOLONY 2ND CIRCLE STREET IN DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9346,Roads,Completed,NQ-SHOZHINGANALLUR,194,552000,FORMING AND LAYING BT ROAD AT SECTRAITCOLONY 4TH CROSS STREET IN DN194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9348,Roads,Completed,NQ-SHOZHINGANALLUR,194,575000,FORMING AND LAYING BT ROAD AT SECRETARIATE COLONY 2ND CROSSS STREET IN DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9351,Roads,Completed,NQ-SHOZHINGANALLUR,194,695000,FORMING AND LAYING BT ROAD AT SECRETARIATE COLONY 5TH CROSSS STREET IN DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9353,Roads,Completed,NQ-SHOZHINGANALLUR,194,637000,FORMING AND LAYING BT ROAD AT SECRETARIATE COLONY 7TH CROSSS STREET IN DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9354,Roads,Completed,NQ-SHOZHINGANALLUR,194,4598000,RELAYING BT ROAD AT RAJU NAGAR 1ST AND 2ND STREET IN DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9506,Parks,Completed,NQ-SHOZHINGANALLUR,194,749000,PROPOSED OPEN GYM AT CHANDRASEKAR AVENUE PARK IN DN-194 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9773,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,500000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DN-194 ,U-45 ,Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/9960,Roads,Completed,NQ-SHOZHINGANALLUR,194,3702000,"FORMING AND LAYING OF B.T ROAD AT BHARATHIYAR NAGAR MAIN ROAD IN DN-194,U-45,Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9961,Roads,Completed,NQ-SHOZHINGANALLUR,194,2879000,"FORMING AND LAYING OF B.T ROAD AT SULAIMA NAGAR MAIN ROAD IN DN-194,U-45,Z-15",Own Sources,15,2017-18,2018-19 B/2017-18/2503,Buildings,Completed,B-Buildings,195,8437000,"Construction of Compound wall and extra amenities in Primary school in Ezhil nagar Division-195, Zone-15",Own Sources,15,2017-18,2018-19 B/2017-18/7162,Buildings,Completed,B-Buildings,195,26500000,"Improvements in First floor, Construction of Second floor and Compound Wall in Urban Primary Health Center at 2nd main road, Kannagi nagar in Div-195, Zone-15",Grants,15,2017-18,2019-20 NQ/2017-18/10306,Buildings,Completed,NQ-SHOZHINGANALLUR,195,184000,REPAIR & MAINTAINANCE WORK IN ANGANWADI 17& 18 AT KANNAGI NAGAR IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/10312,Buildings,Completed,NQ-SHOZHINGANALLUR,195,85000,Repair & maitainance work in Anganwadi 9 at kannagi nagar 35th cross street in dn-195 u-45 z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/10588,Roads,Completed,NQ-SHOZHINGANALLUR,195,170000,"Attending Patch Work at MRG Nagar, Nethaji street in Dn-195 U-45 Z-15.",Own Sources,15,2017-18,2017-18 NQ/2017-18/11619,Roads,Completed,NQ-SHOZHINGANALLUR,195,900000,FORMING AND LAYING OF CC ROAD AT LAKSHMI AVENUE IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11696,Roads,Completed,NQ-SHOZHINGANALLUR,195,6897000,FORMING AND LAYING OF BT ROAD AT THIRUVALLUVAR STREET IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11697,Roads,Completed,NQ-SHOZHINGANALLUR,195,4389000,FORMING AND LAYING OF BT ROAD AT NETHAJI STREET IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11709,Roads,Completed,NQ-SHOZHINGANALLUR,195,2613000,FORMING AND LAYING OF BT ROAD AT MRG NAGAR IN DN -195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12508,Parks,Completed,NQ-SHOZHINGANALLUR,195,100000,IMPROVEMENTS TO KANNAGAI NAGAR 9TH MAIN ROAD PARK IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/3626,Roads,Completed,NQ-SHOZHINGANALLUR,195,870000,"Providing IRC Standard Speed Beaker(21 Nos) at Kannagi Nagar 8th to 12th Main road & various street in DN-195, U-45,Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/4042,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,435000,Desilting of Storm water drain & side drain at various street in DN-195 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/4246,Buildings,Completed,NQ-SHOZHINGANALLUR,195,390000,"CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET IN DN 195, U45, Z15",Own Sources,15,2017-18,2017-18 NQ/2017-18/5297,Buildings,Completed,NQ-SHOZHINGANALLUR,195,177000,Improvement work for Gym Equipment and Building at Kannagi Nagar 2nd Main Road in Dn-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7048,Parks,Completed,NQ-SHOZHINGANALLUR,195,3450000,IMPROVEMENTS TO PARK AT SOWDEESWARI NAGAR (CREEK STREET ) IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7199,Buildings,Completed,NQ-SHOZHINGANALLUR,195,640000,REPAIR AND MAINTENANCE OF HDPE (430 NOS) COMPACTOR BINS (VARIOUS TYPE OF WORKS) IN UNIT-45 ZONE-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/8106,Parks,Completed,NQ-SHOZHINGANALLUR,195,96000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT KANNAGI NAGAR 7TH CROSS ROAD IN DN 195 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8119,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,92000,Supplying Manhole cover at kannagi nagar 11th main road and Ezhil nagar main road IN DN -195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/8124,Roads,Completed,NQ-SHOZHINGANALLUR,195,298000,ATTENDING PATCH WORK AT THIRUVALLUVAR STREET IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/8438,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,170000,Repair work of strom water drain at kannagi nagar 11th main road and Ezhil nagar main road in Dn-195 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/9125,Parks,Completed,NQ-SHOZHINGANALLUR,195,170000,IMPROVEMENTS FOR PLAY APPARATUS IN ANNAI INDIRA NAGAR PARK & KANNAGI NAGAR PARK IN DN-195 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/9374,Parks,Completed,NQ-SHOZHINGANALLUR,195,188000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT ANNAI INDRA GANDHI ROAD PARK IN DN 195 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9392,Parks,Completed,NQ-SHOZHINGANALLUR,195,92000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT KANNAGI NAGAR 9TH MAIN ROAD IN DN 195 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9393,Parks,Completed,NQ-SHOZHINGANALLUR,195,83000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT KANNAGI NAGAR 10TH CROSS STREET (3 ADUKKU) PARK IN DN 195 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9394,Parks,Completed,NQ-SHOZHINGANALLUR,195,118000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT KANNAGI NAGAR 2ND CROSS STREET (3 ADUKKU) IN DN 195 U-45 Z-15",Own Sources,15,2017-18,2018-19 P/2017-18/16486,Parks,Completed,P-Parks and Playfields,195,8485735,"FORMATION OF NEW PARK AT SAKTHI GARDEN 4TH CROSS STREET IN DN -195, ZONE - XV.","Loans, Grants And Own Sources",15,2017-18,2018-19 P/2017-18/17314,Parks,Completed,P-Parks and Playfields,195,10910388,FORMATION OF NEW PARK AT SOWDEESWARI NAGAR MAIN ROAD IN DN 195 ZONE15,Grants,15,2017-18,2018-19 L/2017-18/4148,Electrical,Completed,L-Electrical,196,193300,Spply and Fixing of 12 nos of Automatic Street light ON/OFF Timer complete set in Dn-192-196 & 199 Various locations in Zone-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11712,Buildings,Completed,NQ-SHOZHINGANALLUR,196,85000,Improvement works to Unit Office at VOC Street in Dn-196 U-44 Z-15,Own Sources,15,2017-18,2019-20 NQ/2017-18/12292,Buildings,Completed,NQ-SHOZHINGANALLUR,196,500000,Improvement works to VGP Layout Park at Rajarathinam Avenue in Dn-196 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12693,Parks,Completed,NQ-SHOZHINGANALLUR,196,449000,Providing Awareness Boards at Unit-44 & 45 in Zone-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/2439,Roads,Completed,NQ-SHOZHINGANALLUR,196,695000,"Proposed Construction of compound wall for Night Shelter at Dr.Nanjundarao Salai Injambakkam Dn-196, U-44 ,Z -15",Own Sources,15,2017-18,2018-19 NQ/2017-18/2615,Buildings,Completed,NQ-SHOZHINGANALLUR,196,176000,"Improvements To The Existing Amma Unavagam at Bethel Nagar Dn-196, U-44 , Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/2616,Buildings,Completed,NQ-SHOZHINGANALLUR,196,80000,"Improvements Work To The Existing Amma Unavagam at VOC Street Dn-196, U-44 , Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/4224,Roads,Completed,NQ-SHOZHINGANALLUR,196,425000,"Providing IRC Standard Speed Breakers (10 NOS ) at VGP Layout & Sheshadri Avenue in Dn -196 , u-44 ,z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/4230,Buildings,Completed,NQ-SHOZHINGANALLUR,196,246000,"Name of Work : Construction of Bin Platform at Various Street DN-196, U-44, Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/4262,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,196,51000,"Desilting of Strom water drain at Thiruvalluvar Salai, Bethal Nagar 2nd Street in Dn-196 U-44 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/7223,Buildings,Completed,NQ-SHOZHINGANALLUR,196,810000,WASHING AT ABOVE 660 NOS COMPACTOR BINS INSIDE AND OUTSIDE (TWO TIMES ONCE IN A MONTH USING MECHANICAL SPRAYER) IN ZONE-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7456,Roads,Completed,NQ-SHOZHINGANALLUR,196,1977000,"Forming and Laying at BT Road 2nd Avenue 7th, 8th cross st (2 Roads) in Dn-196 , U-44, z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7457,Roads,Completed,NQ-SHOZHINGANALLUR,196,687000,"Forming and Laying at BT Road Chola Mandala Devi Nagar 2nd Street in Dn-196 , U-44, z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7462,Roads,Completed,NQ-SHOZHINGANALLUR,196,812000,"Forming and Laying at CC Road Cholan Nagar in Dn-196 , U-44, z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7491,Roads,Completed,NQ-SHOZHINGANALLUR,196,869000,"Forming and Laying at BT Road at Gopinath Avenue 5th Main Road & II Avenue 8th Cross Street in Dn-196, U-44, Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7492,Roads,Completed,NQ-SHOZHINGANALLUR,196,1223000,"Forming and Laying at BT Road at Brindavan Nagar in Dn-196, U-44, Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7493,Roads,Completed,NQ-SHOZHINGANALLUR,196,1058000,"Forming and Laying at BT Road in II Avenue 7th Cross Street in Dn-196, U-44, Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7551,Roads,Completed,NQ-SHOZHINGANALLUR,196,1034000,"Forming and Laying at BT Road in Gopinath Avenue 3rd Main Road & Gopinath Avenue 4th Main Road in Dn-196, U-44, Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/7552,Roads,Completed,NQ-SHOZHINGANALLUR,196,1034000,"Forming and Laying at BT Road in Gopinath Avenue 1 st Main Road & Gopinath Avenue 2nd Main Road Dn-196, U-44, Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8092,Parks,Completed,NQ-SHOZHINGANALLUR,196,109000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT (VGP LAYOUT 2ND STREET) IN DN 196 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8371,Electrical,Completed,NQ-SHOZHINGANALLUR,196,482700,"Supply, Erection, Commissioning and Testing of 1 no of 25 KVA Diesel Genset with AFM unit at Gasifier crematorium, Enjambakkam Dn 196 zone-15.",Own Sources,15,2017-18,2019-20 NQ/2017-18/8454,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,196,90000,Improvements to S.W Drain at Gowriamman Koil 1 st Street in Dn-196 U-44 Z-15,Own Sources,15,2017-18,2017-18 B/2017-18/3575,Buildings,Completed,B-Buildings,197,11518677,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTER AT SHOZHINGANALLUR IN DIV-197, ZONE-15",Grants,15,2017-18,2019-20 L/2017-18/0195,Electrical,Completed,L-Electrical,197,67300,Prposed to construction of 196 nos of new plain cement concrete pedestral at various location in dn-192 to 200 in z-15,Own Sources,15,2017-18,2017-18 L/2017-18/12338,Electrical,Completed,L-Electrical,197,18559500,Provision of 362 nos of 6mtr GI lamp post with single straight bracket Hot Dip Zinc Galvanised with 40 -50w LED fittings and 40 nos of 8mtr GI lamp post with single Arch bracket Hot Dip Zinc Galvanised with 150 -165w LED fittings at Various Location in Dn.192 to 200 in Zone-XV.,"Loans, Grants And Own Sources",15,2017-18,2018-19 L/2017-18/4146,Electrical,Completed,L-Electrical,197,193300,"Replacement of 12 Nos of faulty timer unt in various locations of dn197,198 & 200 zone 15",Own Sources,15,2017-18,2018-19 NQ/2017-18/10318,Culvert,Completed,NQ-SHOZHINGANALLUR,197,186000,Providing Culvert at Kajarajan Street Junction of Nehru Street and Sadagoppan Street Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/10319,Culvert,Completed,NQ-SHOZHINGANALLUR,197,156000,Providing Culvert at Aringar Anna Street Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/10321,Culvert,Completed,NQ-SHOZHINGANALLUR,197,427000,"Providing Culvert at MGR Street,Mahatma Gandhi Street,VOC Street,Vendrasiamman koil Street Karapakkam in Dn-197 U-45 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/10322,Culvert,Completed,NQ-SHOZHINGANALLUR,197,611000,"Providing Culvert at Kalaingar Karunanithi Street,Veerapandiya Kattabomman Street,Bharathiyar Street,Kajarajan Street Junction of Bharathiyar Street,Kambar Street Karapakkam in Dn-197 U-45 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/10323,Culvert,Completed,NQ-SHOZHINGANALLUR,197,128000,Providing Culvert at Lalbhagadur Sastri Street and New Kumaran Nagar 1st Main Road Karapakkam in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/11148,Roads,Completed,NQ-SHOZHINGANALLUR,197,236000,Attending Patch Work at Ciassic Farm Retreat Avenue 1st Street and inside of Shopping Complex in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/11540,Buildings,Completed,NQ-SHOZHINGANALLUR,197,170000,Improvement works to Community Center at Aringar Anna Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11649,Roads,Completed,NQ-SHOZHINGANALLUR,197,250000,"Repair and Improvement Works To Toilet at Nedunchelian street, Periyapalayathamman Koil Street, Kalliamman Koil Street, Model School road and Gangaiamman Koil Street in Dn-197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11699,Roads,Completed,NQ-SHOZHINGANALLUR,197,410000,Attending Patch Work at Eswaran Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/12148,Parks,Completed,NQ-SHOZHINGANALLUR,197,900000,Improvement works to Park at New Kumaran Nagar 2nd Main Road in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2019-20 NQ/2017-18/12149,Parks,Completed,NQ-SHOZHINGANALLUR,197,36000,Improvement works to Park at kumarasamy nagar 4th street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12150,Parks,Completed,NQ-SHOZHINGANALLUR,197,530000,Improvement works to Park at Rajiv Gandhi Salai (Techi Park) in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12151,Parks,Completed,NQ-SHOZHINGANALLUR,197,153000,Improvement works to Park at Central Park west Park in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12152,Parks,Completed,NQ-SHOZHINGANALLUR,197,230000,Improvement works to Park at Elcot avenue 1st Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12153,Parks,Completed,NQ-SHOZHINGANALLUR,197,84000,Improvement works to Park at Neduncheliyan Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12154,Parks,Completed,NQ-SHOZHINGANALLUR,197,215000,Improvement works to Park at Devaraj Nagar 2nd Main Road in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12337,Buildings,Completed,NQ-SHOZHINGANALLUR,197,654000,Repair and Maintenance work for Zonal Office Building at Rajiv Gandhi Salai Sholinganallur in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/13554,Roads,Completed,NQ-SHOZHINGANALLUR,197,160000,Improvement works to Anganwadi at School Road 1st Street and Kajarajan Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/2897,Buildings,Completed,NQ-SHOZHINGANALLUR,197,500000,"Providing Gym Equipments at Sadagoppan Street,Anna Street and Kaliamman koil Street in Dn-197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/3797,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,400000,Desilting of Strom Water Drain at Various Streets in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/4102,Parks,Completed,NQ-SHOZHINGANALLUR,197,640000,Proposed open GYM at Devaraj Nagar 2nd Main Road in Div -197 Zone -15,Own Sources,15,2017-18,2017-18 NQ/2017-18/4248,Roads,Completed,NQ-SHOZHINGANALLUR,197,350000,"CONSTRUCTION OF BIN PLATFORM AT VARIOUS STREET IN DN 197, U45, Z15",Own Sources,15,2017-18,2017-18 NQ/2017-18/7487,Roads,Completed,NQ-SHOZHINGANALLUR,197,8394000,Forming and Laying of BT Road using Paver Finisher at Eswaran koil Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7490,Roads,Completed,NQ-SHOZHINGANALLUR,197,2404000,Forming and Laying of BT Road using Paver Finisher at Gandhi 1st street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7507,Roads,Completed,NQ-SHOZHINGANALLUR,197,1329000,Forming and Laying of BT Road using paver Finishing at Manimegalai Nagar 1st street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7508,Roads,Completed,NQ-SHOZHINGANALLUR,197,905000,Forming and Laying of BT Road using paver Finishing at Manimegalai Nagar 2nd street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7517,Roads,Completed,NQ-SHOZHINGANALLUR,197,1204000,Laying of Cement Concrete Road at KTK Main Road in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7518,Roads,Completed,NQ-SHOZHINGANALLUR,197,547000,Laying of Cement Concrete Road at KTK Town 1st Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7519,Roads,Completed,NQ-SHOZHINGANALLUR,197,1891000,Laying of Cement Concrete Road at KTK Town 2nd Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7520,Roads,Completed,NQ-SHOZHINGANALLUR,197,198000,Laying of Cement Concrete Road at KTK Town 3rd Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/8011,Parks,Completed,NQ-SHOZHINGANALLUR,197,88000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT NEDUNCHELIYAN STREET PARK IN DN-197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8012,Parks,Completed,NQ-SHOZHINGANALLUR,197,175000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT DEVARAJ NAGAR 2ND MAIN ROAD PARK IN DN-197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9196,Parks,Completed,NQ-SHOZHINGANALLUR,197,234000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT KUMARASAMY NAGAR MAIN ROAD PARK (NORTH) IN DN-197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9363,Parks,Completed,NQ-SHOZHINGANALLUR,197,89000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT ELCOT AVENUE 1ST STREET IN DN 197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9364,Parks,Completed,NQ-SHOZHINGANALLUR,197,101000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT RAJIV GANDHI SALAI CENTRAL PARK WEST PARK IN DN 197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9365,Parks,Completed,NQ-SHOZHINGANALLUR,197,240000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT RAJIV GANDHI SALAI (TECHI PARK) IN DN 197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9366,Parks,Completed,NQ-SHOZHINGANALLUR,197,250000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT KUMARASAMY NAGAR 6TH STREET PARK IN DN 197 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9579,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1320000,Improvements works to Shopping Complex at Neduncheliyan Street and Anna Street in Dn-197 U-45 Z-15,Own Sources,15,2017-18,2018-19 P/2017-18/13054,Parks,Completed,P-Parks and Playfields,197,7738100,"FORMATION OF NEW PARK AT SADAGOPAN STREET, KARAPAKKAM IN DN-197, ZONE - XV.",Grants,15,2017-18,2019-20 NQ/2017-18/10346,Buildings,Completed,NQ-SHOZHINGANALLUR,198,40000,Demolition of Existing old building at Sea Cliff Park in Dn-198 U-45 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11483,Roads,Completed,NQ-SHOZHINGANALLUR,198,1004000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT PARAMESHWARAN NAGAR 3RD STREET IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11486,Roads,Completed,NQ-SHOZHINGANALLUR,198,975000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT PADVATTAMMAN KOIL 1ST STREET IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11490,Roads,Completed,NQ-SHOZHINGANALLUR,198,817000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT PADVATTAMMAN KOIL 2ND STREET IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11493,Roads,Completed,NQ-SHOZHINGANALLUR,198,589000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT PADVATTAMMAN KOIL 3RD STREET IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11502,Roads,Completed,NQ-SHOZHINGANALLUR,198,982000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT MGR NAGAR MAIN ROAD ( KK SALAI) IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11503,Roads,Completed,NQ-SHOZHINGANALLUR,198,575000,"FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT MGR NAGAR 1ST,2ND & 3RD CROSS STREET KK SALAI IN DN-198 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11510,Roads,Completed,NQ-SHOZHINGANALLUR,198,941000,FORMING AND LAYING OF CC ROAD AT L-JEY AVENUE ECR IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11534,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,990000,IMPROVEMENTS TO BT ROAD AT GANGAIAMMAN KOIL STREET IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11535,Roads,Completed,NQ-SHOZHINGANALLUR,198,600000,IMPROVEMENTS TO BT ROAD AT PONDICHERY SALAI IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11536,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,940000,IMPROVEMENTS TO BT ROAD AT ANNAI INDIRA STREET IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11538,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,2090000,IMPROVEMENTS TO BT ROAD AT VILLAGE HIGH ROAD IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11555,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,510000,IMPROVEMENTS TO BT ROAD AT PARAMESHWARAN NAGAR 1ST STREET IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11638,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,510000,"IMPROVEMENTS TO CC ROAD AT PANAIYUR KUPPAM SCHOOL 3RD CROSS STREET LANE , PANAIYUR KUPPAM SCHOOL 2ND CROSS STREET, PANAIYUR KUPPAM SCHOOL 2ND CROSS STREET LANE,PANAIYUR KUPPAM SCHOOL 2ND CROSS STREET 3RD LANE, PANAIYUR KUPPAM SCHOOL 2ND CROSS STREET 2ND LANE, PANAIYUR KUPPAM SCHOOL 2ND CROSS STREET 1ST LANE, PANAIYUR KUPPAM SCHOOL 2ND CROSS STREET 4TH LANE IN DN-198 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11639,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,736000,"IMPROVEMENTS TO CC ROAD AT PANAIYUR KUPPAM 1ST CROSS STREET, PANAIYUR KUPPAM 1ST CROSS STREET LINK ,PANAIYUR KUPPAM 1ST CROSS STREET LANE, PANAIYUR KUPPAM 4TH CROSS STREET LANE, PANAIYUR KUPPAM SCHOOL STREET IN DN-198, U-45, Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/11640,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,661000,"IMPROVEMENTS TO CC ROAD AT PANAIYUR MGR 2ND , 3RD & 5TH STREET TO 12TH STREETS IN DN-198 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/12168,Buildings,Completed,NQ-SHOZHINGANALLUR,198,74000,"REPAIR AND MAINTANENCE OF PUBLIC CONVENIENCE PANAIYUR KUPPAM NORTH , PANAIYUR KUPPAM (LADIES AND GENTS), KUDIMIYANDITHOPPU, RAJIV GANDHI NAGAR, SATHYAVANIMUTHU STREET, PARAMESHWARAN STREET IN DIV-198 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/12318,Buildings,Completed,NQ-SHOZHINGANALLUR,198,780000,MAINTANENCE CONTRACT FOR HOUSE KEEPING SERVICES TO PUBLIC CONVENIENCES AT 32 LOCATIONS FOR THE PERIOD OF 3 MONTHS (90 DAYS) IN UNIT-44 &45 :ZONE 15.,Own Sources,15,2017-18,2018-19 NQ/2017-18/12321,Buildings,Completed,NQ-SHOZHINGANALLUR,198,638000,PROPOSED CONSTRUCTION OF OPEN GYM AT E12 PARK AT TNHB E12 ROAD IN DIV-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12441,Parks,Completed,NQ-SHOZHINGANALLUR,198,47000,REPAIR AND MAINTANENCE OF TNHB E12 PARK AND SEACLIFF PARK IN DIV-198 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/3850,Buildings,Completed,NQ-SHOZHINGANALLUR,198,590000,"Providing Gym Equipments for Adult Gym at Sea Cliff Aveune, Akkarai in Dn-198 U-44 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/4142,Buildings,Completed,NQ-SHOZHINGANALLUR,198,1400000,MAINTANENCE CONTRACT FOR HOUSE KEEPING SERVICES TO PUBLIC CONVENIENCES AT 20 LOCATIONS FOR THE PERIOD OF (135 DAYS) IN UNIT-44 &45 :ZONE 15.,Own Sources,15,2017-18,2017-18 NQ/2017-18/4145,Buildings,Completed,NQ-SHOZHINGANALLUR,198,160000,Construction of Bin platform at TNHB layout & various street in Dn-198 U-44 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/7198,Buildings,Completed,NQ-SHOZHINGANALLUR,198,340000,REPAIR AND MAINTENANCE OF HDPE COMPACTOR BINS (VARIOUS TYPE OF WORKS) (230NOS) IN UNIT-44 ZONE-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/7794,Buildings,Completed,NQ-SHOZHINGANALLUR,198,200000,DESILTING OF SIDE DRAINS AT TNHB LAYOUT IN DN-198 U-44 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/8094,Parks,Completed,NQ-SHOZHINGANALLUR,198,119000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT SEA CLIFF PARK IN DN 198 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8830,Roads,Completed,NQ-SHOZHINGANALLUR,198,184000,"ATTENDING PATCH WORK AT M.G.R STREET, PONNIAMMAN KOIL 2ND STREET,PONDICHERRY PAATAI SALAI , TNHB C1,C2 & D1 ROADS IN DN-198 U-44 Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/9205,Parks,Completed,NQ-SHOZHINGANALLUR,198,256000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT TNHB E12 PARK IN DN-198 U-44 Z-15",Own Sources,15,2017-18,2018-19 P/2017-18/13055,Parks,Completed,P-Parks and Playfields,198,6905100,"FORMATION OF NEW PARK AT TNHB, OLD PONDICHERRY ROAD IN DN-198, ZONE - XV.",Grants,15,2017-18,2019-20 P/2017-18/13057,Parks,Completed,P-Parks and Playfields,198,8058100,"FORMATION OF NEW PARK AT TNHB, E17 AT SHOLINGANALLUR IN DN - 198, ZONE - XV.",Grants,15,2017-18,2019-20 NQ/2017-18/11552,Roads,Completed,NQ-SHOZHINGANALLUR,199,2149000,FORMING AND LAYING OF BT ROAD USING PAVER FINISHER AT VGP 2ND CROSS STREET IN DN-199 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/11644,Road Cut,Completed,NQ-SHOZHINGANALLUR,199,643000,IMPROVEMENTS TO BT ROAD AT MAZAHAVARAYAR STREET IN DN-199 U-44 Z-15,Own Sources,15,2017-18,2018-19 NQ/2017-18/12286,Buildings,Completed,NQ-SHOZHINGANALLUR,199,21500,"REPAIR AND MAINTANENCE OF PUBLIC CONVENIENCE UTHANDI VGP 2ND MAIN ROAD, NAINAR KUPPAM MAYANA SALAI IN DIV-199 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8097,Parks,Completed,NQ-SHOZHINGANALLUR,199,92000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT V.G.P 2ND MAIN ROAD PARKS IN DN 199 U-44 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9107,Buildings,Completed,NQ-SHOZHINGANALLUR,199,135000,PROVIDING MODERN DUSTBINS IN THE BEACH AT V.G.P 2ND MAIN ROAD IN DN-199 U-44 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/9676,Buildings,Completed,NQ-SHOZHINGANALLUR,199,63000,"Providing FRP BENCHES in beach at V.G.P 2nd Main Road in Div.199, Unit-44, Zone-15.",Own Sources,15,2017-18,2018-19 BR/2017-18/15635,Roads,Completed,BR-Bus Route Roads,200,413000,"PROPOSED SPEED BREAKER (6NOS)AT NOOKAM PALAYAM MAIN ROAD IN DIV-200,ZONE-15.",Own Sources,15,2017-18,2019-20 BR/2017-18/16919,Roads,Completed,BR-Bus Route Roads,200,2020000,"PROPOSED ROAD WIDENING, FOOTPATH AND CENTRE MEDIAN(CRASH BARRIER TYPE) AT NOOKAMPALAYAM MAIN ROAD IN DIV-200, ZONE-15. LENGTH (80.00M)",Own Sources,15,2017-18,2019-20 NQ/2017-18/0989,Buildings,Completed,NQ-SHOZHINGANALLUR,200,1160000,Construction of Toilet Block 3+3 Seater for gents and Ladies at Ezhilmuga Nagar in Dn-200 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/12171,Buildings,Completed,NQ-SHOZHINGANALLUR,200,50000,"Repair works to public convenience in Veeravanjinadhan salai , Pondicherri pattai salai , TNSCB 7th Avenue in Dn-200 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/13148,Parks,Completed,NQ-SHOZHINGANALLUR,200,100000,"Repair Works to Play Materials In Child Play Space at TNSCB 7th, 15th, 25th, 52nd, 87th cross street & 7th Main Road, Anna Salai. At Semmencherry in Dn- 200 U-45 Z-15.",Own Sources,15,2017-18,2018-19 NQ/2017-18/15191,Buildings,Completed,NQ-SHOZHINGANALLUR,200,1220000,"Construction of compound wall at Survey no. 408/1A1B OSR @ Nookampalayam link road in Dn-200, U-45, Z-15.",Own Sources,15,2017-18,2019-20 NQ/2017-18/2288,Buildings,Completed,NQ-SHOZHINGANALLUR,200,260000,"IMPROVEMENTS TO AMMA UNAVAGAM AT TNSCB 66th CROSS STREET & 19TH CROSS STREET in DN 200, U45, Z15",Own Sources,15,2017-18,2018-19 NQ/2017-18/2299,Buildings,Completed,NQ-SHOZHINGANALLUR,200,90000,"IMPROVEMENTS TO SIDE DRAIN AT TNSCB 25th CROSS STREET IN DN 200, U45, Z15",Own Sources,15,2017-18,2017-18 NQ/2017-18/3201,Roads,Completed,NQ-SHOZHINGANALLUR,200,76000,"providing thermoplast paint for speed breakers at TNSCB various streets in dn-200 ,U-45, Z-15",Own Sources,15,2017-18,2017-18 NQ/2017-18/4110,Buildings,Completed,NQ-SHOZHINGANALLUR,200,285000,"CONSTRUCTION OF BIN PLATFORM AT TNSCB VARIOUS STREET IN DN 200, U45, Z15",Own Sources,15,2017-18,2017-18 NQ/2017-18/4227,Parks,Completed,NQ-SHOZHINGANALLUR,200,169000,Improvements to play apparatus at TNSCB 2nd main road in Dn-200 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/7900,Parks,Completed,NQ-SHOZHINGANALLUR,200,79000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT TNSCB CHEMMENCHERY 33RD CROSS STREET PARK IN DN 200 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/8365,Electrical,Completed,NQ-SHOZHINGANALLUR,200,799600,"Supply, Erection, Commissioning and Testing of one no of 62.5 KVA Diesel Genset at Health Centre Chemmancherry in Dn-200 zone-15.",Own Sources,15,2017-18,2019-20 NQ/2017-18/8411,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,424000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-200 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/8413,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,710000,REPAIRS TO STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DN-200 U-45 Z-15,Own Sources,15,2017-18,2017-18 NQ/2017-18/9190,Parks,Completed,NQ-SHOZHINGANALLUR,200,206000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT TNSCB CHEMMENCHERY 1ST MAIN ROAD PARK IN DN 200 U-45 Z-15",Own Sources,15,2017-18,2018-19 NQ/2017-18/9671,Buildings,Completed,NQ-SHOZHINGANALLUR,200,400000,"Improvements to Anganwadi at Pondicherry Pattai Salai , TNSCB 4th cross street and TNSCB 8th Avenue(Dno:6105,6106) in DN 200, U45 Z15",Own Sources,15,2017-18,2018-19 BR/2017-18/17981,Roads,Completed,BR-Bus Route Roads,,1040000,Restoration of OFC Roadcut at various division in zone-10,Deposit Works,Central Region,2017-18,2020-21 BR/2017-18/17982,Roads,Completed,BR-Bus Route Roads,,982000,Restoration of OFC Roadcut at Various divisions in Zone -9.,Deposit Works,Central Region,2017-18,2020-21 B/2017-18/9544,Buildings,Completed,B-Buildings,,9900000,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTRE AT BANJANAI KOIL STREET, RAMAPURAM IN DIV -155 ,ZONE -11",Grants,Greater Chennai Corporation,2017-18,2019-20 J/2017-18/11335,Bridges,Completed,J-Bridges,,817000,DEMOLITION AND RE-CONSTRUCTION OF HANDRAIL WALL AT BRIDGE ACROSS OTTERI NALLAH AT DR.AMBEDHKAR COLLEGE ROAD IN DIV-71 ZONE -6,Own Sources,Greater Chennai Corporation,2017-18,2018-19 J/2017-18/11337,Bridges,Completed,J-Bridges,,999000,REPAIR OF HANDRAIL WALL AND PAINTING FOR RESERVE BANK SUBWAY IN DIV-60 ZONE-5,Own Sources,Greater Chennai Corporation,2017-18,2017-18 J/2017-18/11338,Bridges,Completed,J-Bridges,,547000,DISMANTLING THE EXISTING DAMAGED R.C.C ROPES ON THE TOP OF THE HANDRAIL WALL AT ROYAPURAM NRT BRIDGE IN DIV-60 ZONE-05,Own Sources,Greater Chennai Corporation,2017-18,2017-18 J/2017-18/11339,Bridges,Completed,J-Bridges,,54900,DISMANTLING THE EXISTING ELEVATION TILE AND BRICK WORK AT DR.NAIR BRIDGE IN DIV-61 ZONE-05,Own Sources,Greater Chennai Corporation,2017-18,2017-18 J/2017-18/11340,Bridges,Completed,J-Bridges,,160000,"REMOVING OF RANK VEGETATION AT VARIOUS BRIDGE AT NORTH REGION IN DIV-61,63 ZONE-05",Own Sources,Greater Chennai Corporation,2017-18,2017-18 J/2017-18/1396,Culvert,Completed,J-Bridges,,8030000,Demolition of the existing footbridge &Re-Construction of box culvert 5vent (4mx4m) at Andavar st in Dn -108 Zone 8,Own Sources,Greater Chennai Corporation,2017-18,2019-20 J/2017-18/14971,Bridges,Completed,J-Bridges,,964000,"PAINTING FOR THE NAPIER BRIDGE ACROSS COOVUM RIVER IN DN-60, ZONE-5",Own Sources,Greater Chennai Corporation,2017-18,2017-18 J/2017-18/14972,Bridges,Completed,J-Bridges,,270000,"REPAIR AND PAINTING FOR THE STANLEY VIA DUCT BRIDGE OPP TO CENTRAL RAILWAY STATION IN DN-59,ZONE-5",Own Sources,Greater Chennai Corporation,2017-18,2017-18 J/2017-18/1806,Bridges,Completed,J-Bridges,,990000,Improvement to Existing kakkan Bridge across Velachery eri at velachery in Dn-177& zone-13,Own Sources,Greater Chennai Corporation,2017-18,2018-19 J/2017-18/2350,Culvert,Completed,J-Bridges,,3782000,"Construction of 5 vent Box Culvert across Mambalam canal at Williams Bridge of size 3mx3m in Dn: 117, U-26, Zone -IX",MPLADS,Greater Chennai Corporation,2017-18,2018-19 BR/2017-18/4173,Roads,Completed,BR-Bus Route Roads,,219000,Restoration of OFC road cut made by Idea Communication Ltd in Zone -1 For the challan no-B.R.R.C.NO.B4/0413/2016,Deposit Works,1,2017-18,2019-20 L/2017-18/10214,Electrical,Completed,L-Electrical,,63842000,"Supply & erection of Street lamp post at various places in Div-15 to 20 Zone-II, Manali","Loans, Grants And Own Sources",2,2017-18,2018-19 BR/2017-18/11144,Roads,Completed,BR-Bus Route Roads,,19000,Restoration of road cut made by CMWSSB at EVK Sampath salai in Zone-5 against challan no. BR/2017-18/0003606,Deposit Works,5,2017-18,2018-19 BR/2017-18/11145,Roads,Completed,BR-Bus Route Roads,,7400,Restoration of road cut made by CMWSSB at EVK Sampath salai in Zone-5 against challan no. BR/2017-18/0006372,Deposit Works,5,2017-18,2018-19 BR/2017-18/11146,Roads,Completed,BR-Bus Route Roads,,119000,Restoration of road cut made by TANGEDCO at EVK Sampath salai in Zone-5 against challan no. BR/2017-18/0001150,Deposit Works,5,2017-18,2018-19 BR/2017-18/11147,Roads,Completed,BR-Bus Route Roads,,59000,Restoration of road cut made by CMWSSB at Arunachalam street in Zone-5 against challan no. BR/2017-18/0006598,Deposit Works,5,2017-18,2018-19 BR/2017-18/5216,Roads,Completed,BR-Bus Route Roads,,988000,"Providing and laying of Thermoplastic painting & studs at Duraisamy road , Anna main road, Kodambakkam road,Postal colony 3rd street,Ashok nagar 11th avenue, Ashok nagar 10th avenueand other various Bus Route Roads in Zone - 10",Own Sources,10,2017-18,2017-18 BR/2017-18/5245,Road Cut,Completed,BR-Bus Route Roads,,2405000,"Restoration of Roadcut made by CMWSSB at Ashok pillar road from 100feet road to PT Rajan salai Jn near in Div-138, Zone-10.",Deposit Works,10,2017-18,2017-18 BR/2017-18/5246,Road Cut,Completed,BR-Bus Route Roads,,2405000,"Restoration of Roadcut made by CMWSSB at Ashok pillar road from PT Rajan salai Jn to MGR Road Jn in Div-138, Zone-10.",Deposit Works,10,2017-18,2017-18 BR/2017-18/5278,Road Cut,Completed,BR-Bus Route Roads,,2424000,"Restoration of Road cut made by CMWSSB at Anna main road from Metro STP to Thiru Vika street Jn in Dn-137, Zone-10",Deposit Works,10,2017-18,2017-18 BR/2017-18/5280,Road Cut,Completed,BR-Bus Route Roads,,2424000,"Restoration of Road cut made by CMWSSB at Anna main road from Thiru Vika street Jn to MGR Road Jn in Dn-137, Zone-10",Deposit Works,10,2017-18,2017-18 BR/2017-18/6165,Road Cut,Completed,BR-Bus Route Roads,,185000,Restoration of Roadcut made by Airtel at Various Interior Roads ( 5 Roads/3342) in Zone -10,Deposit Works,10,2017-18,2018-19 BR/2017-18/6166,Road Cut,Completed,BR-Bus Route Roads,,66000,Restoration of Roadcut made by Airtel at Various Interior Roads ( 5 Roads/3945) in Zone -10,Deposit Works,10,2017-18,2018-19 BR/2017-18/6168,Road Cut,Completed,BR-Bus Route Roads,,172000,Restoration of Roadcut made by Airtel at Various Interior Roads ( 5 Roads/4600) in Zone -10,Deposit Works,10,2017-18,2018-19 BR/2017-18/6169,Road Cut,Completed,BR-Bus Route Roads,,583000,Restoration of Roadcut made by JIO at Various Interior Roads ( 13 Roads/4601) in Zone -10,Deposit Works,10,2017-18,2018-19 BR/2017-18/6174,Road Cut,Completed,BR-Bus Route Roads,,505000,Restoration of Roadcut made by VODAFONE at Various Interior Roads ( 5 Roads/0957) in Zone -10,Deposit Works,10,2017-18,2018-19 BR/2017-18/6175,Road Cut,Completed,BR-Bus Route Roads,,92000,Restoration of Roadcut made by IDEA at Various Interior Roads ( 4 Roads/0418) in Zone -10,Deposit Works,10,2017-18,2018-19 BR/2017-18/6176,Road Cut,Completed,BR-Bus Route Roads,,90000,Restoration of Roadcut made by BSNL at Various Interior Roads ( 4 Roads/0666) in Zone -10,Deposit Works,10,2017-18,2018-19 BR/2017-18/6177,Road Cut,Completed,BR-Bus Route Roads,,559000,Restoration of Roadcut made by JIO at Various Interior Roads ( 10 Roads/4617) in Zone -10,Deposit Works,10,2017-18,2019-20 BR/2017-18/6179,Road Cut,Completed,BR-Bus Route Roads,,487000,Restoration of Roadcut made by JIO at Various Interior Roads ( 11 Roads/4617) in Zone -10,Deposit Works,10,2017-18,2019-20 NK/2017-18/8397,Storm Water Drain,Completed,NK-KODAMBAKKAM,,600000,"Desilting of Storm Water Drain at Various streets in Div-128, Unit-29, Zone-10",Own Sources,10,2017-18,2018-19 P/2017-18/14684,Parks,Completed,P-Parks and Playfields,,2442000,"PROVIDING FENCING ALROUND TENNIS COURT AND FORMATION OF SYNTHETIC TURF AT THE OSR LAND, TNHB QUARTERS PARK, NWERKUNDRAM, WEST NATESAN NAGAR, ERIKKARAI STREET IN DN-127, ZONE - 10",Own Sources,10,2017-18,2018-19 D/2017-18/7232,Storm Water Drain,Completed,D-Storm Water Drains,,4979000,"Construction of Storm Water Drain of Size 600 X 750mm along Dr. Ambedkar Salai from Krishnaveni Ammal Nagar to L.I.C Nagar 4th Street in Dn - 188, Zone IVX",Own Sources,14,2017-18,2018-19 L/2018-19/10764,Electrical,Completed,L-Electrical,1,199250,"Proposal for Replace of new cable to damage cable in Manali express salai near Sathyamoorthy nagar Junction in Division -6, Zone-1",Own Sources,1,2018-19,2020-21 L/2018-19/11104,Electrical,Completed,L-Electrical,1,199970,"Proposal for Replace of new cable to damage cable in Manali express salai near BSB Company Junction in Division -6, Zone-1",Own Sources,1,2018-19,2020-21 L/2018-19/11105,Electrical,Completed,L-Electrical,1,135450,"Repairing and Refixing of steel rope and wire for 20MTR High Mast at the junction of Ajax Bus stand area in division-5, Zone-1 Tiruvottriyur",Own Sources,1,2018-19,2019-20 L/2018-19/12495,Electrical,Completed,L-Electrical,1,199200,"Proposal for removal of 509 nos. of old SVL fittings and fixing of 509 nos. of LED Fittings at ward-1 AND 2, Zone-1, Tiruvottriyur [SOR 2017-18]",Own Sources,1,2018-19,2019-20 L/2018-19/5172,Electrical,Completed,L-Electrical,1,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing in the building of Gymnasium at Teyagarayapuram Ist Street, Thangal in Dn-14 in Zone-1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5204,Electrical,Completed,L-Electrical,1,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Nettukuppam 2nd Street in Div-1 in Zone - 1 E.B.Account .no.023.017.625",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5206,Electrical,Completed,L-Electrical,1,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Mugathvarakuppam 5th Street in Div-1 in Zone - 1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5208,Electrical,Completed,L-Electrical,1,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Ulaganathpuram 2nd cross Street in Div-1 in Zone - 1 E.B.Account.No.023.015.588",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5209,Electrical,Completed,L-Electrical,1,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at JJ Nagar 1st cross Street in Div-1 in Zone - 1 E.B.Account.No.023.011.413",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5216,Electrical,Completed,L-Electrical,1,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at SVM nagar2nd main road (Community Hall ) in Div-1, Zone - I E.B Account Number : 023.016.558. .",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5217,Electrical,Completed,L-Electrical,1,312000,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Nettukuppam Main street (School) in Div-1, Zone - I . E.B Account Number : 023.017.390 .",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5218,Electrical,Completed,L-Electrical,1,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ennore kuppam &Mugathuvarakuppam main road School building in Div-1, Zone - I .B Account Number : 023.030.281.",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5219,Electrical,Completed,L-Electrical,1,162000,"upply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Mugathuvarakuppam 4th street School building in Div-1, Zone - I .B Account Number : 023.030.280.",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5220,Electrical,Completed,L-Electrical,1,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Thazankuppam market school building at Ennore high road in Div-1 in Zone - 1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5221,Electrical,Completed,L-Electrical,1,312000,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS SVM NAGAR 3rd Main Road (School) in Div-1, Zone - I . E.B Account Number : 023.016.560.",SMART CITY - ELECTRICAL,1,2018-19,2019-20 NA/2018-19/12558,Buildings,Completed,NA-THIRUVOTTIYUR,1,380000,"CONSTRUCTION OF NEW SIDE DRAIN AND ROAD CROSS CULVERT AT NETTUKUPPAM 4TH & 5TH STREET IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/12560,Buildings,Completed,NA-THIRUVOTTIYUR,1,200000,"IMPROVEMENT TO AMMA UNAVAGAM AT J.J.NAGAR IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2020-21 NA/2018-19/12561,Buildings,Completed,NA-THIRUVOTTIYUR,1,315000,"IMPROVEMENTS TO AMMA UNAVAGAM AT THALANGKUPPAM IN DIV-01,UNIT-01,ZONE-01",Own Sources,1,2018-19,2020-21 NA/2018-19/12562,Buildings,Completed,NA-THIRUVOTTIYUR,1,735000,"IMPROVEMENTS TO C.P.S AT S.V.M.NAGAR 3RD MAIN ROAD IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/12563,Buildings,Completed,NA-THIRUVOTTIYUR,1,670000,"IMPROVEMENTS TO C.P.S AT THALANGKUPPAM ENNORE EXPRESS ROAD IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/12564,Buildings,Completed,NA-THIRUVOTTIYUR,1,600000,"IMPROVEMENTS TO C.P.S.AT ENNORE KUPPAM IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2020-21 NA/2018-19/12565,Buildings,Completed,NA-THIRUVOTTIYUR,1,425000,"IMPROVEMENTS TO C.P.S AT MUGATHUVARA KUPPAM IN DIV-01, UNIT-01, ZONE-01.",Own Sources,1,2018-19,2019-20 NA/2018-19/12970,Buildings,Completed,NA-THIRUVOTTIYUR,1,300000,"IMPROVEMENTS TO C.M.S AT NETTUKUPPAM IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2020-21 NA/2018-19/12971,Buildings,Completed,NA-THIRUVOTTIYUR,1,270000,"IMPROVEMENTS TO C.P.S AT KAMARAJI NAGAR 3RD STREET IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/1512,Roads,Completed,NA-THIRUVOTTIYUR,1,748000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KAMARAJ NAGAR 2ND STREET IN DIVISION-1, UNIT-1, ZONE-1",Grants,1,2018-19,2019-20 NA/2018-19/1587,Roads,Completed,NA-THIRUVOTTIYUR,1,926000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KAMARAJ NAGAR 3RD STREET IN DIVISION-1, UNIT-1, ZONE-1",Grants,1,2018-19,2019-20 NA/2018-19/1588,Roads,Completed,NA-THIRUVOTTIYUR,1,781000,"IMPROVEMENTS TO INTERIOR BT ROAT AT KAMARAJ NAGAR 4TH STREET IN DIVISION-1, UNIT-1, ZONE-1",Grants,1,2018-19,2019-20 NA/2018-19/1590,Roads,Completed,NA-THIRUVOTTIYUR,1,570000,"IMPROVEMENTS TO INTERIOR BT ROAT AT KAMARAJ NAGAR 9TH STREET IN DIVISION-1, UNIT-1, ZONE-1",Grants,1,2018-19,2019-20 NA/2018-19/1594,Roads,Completed,NA-THIRUVOTTIYUR,1,132000,"IMPROVEMENTS TO INTERIOR BT ROAT AT KAMARAJ NAGAR 10TH STREET IN DIVISION-1, UNIT-1, ZONE-1",Grants,1,2018-19,2019-20 NA/2018-19/1595,Roads,Completed,NA-THIRUVOTTIYUR,1,762000,"IMPROVEMENTS TO INTERIOR BT ROAD AT ULAGANATHAPURAM MAIN ROAD (PART) IN DIVISION-1, UNIT-1, ZONE-1",Grants,1,2018-19,2019-20 NA/2018-19/17484,Parks,Completed,P-Parks and Playfields,1,1610009,"Plantation and Maintenance of Tree saplings for one year at various street in Division 1, Unit 1, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/8273,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,133000,"DESILTING OF OPEN SIDE DRAIN AT VARIOUS STREETS IN DIV-01, UNIT-01, ZONE-01",Own Sources,1,2018-19,2018-19 NA/2018-19/8561,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,175000,"REPAIR WORK IN OPEN SIDE DRAIN WORK AT VARIOUS STREETS IN DIV-1, UNIT-1, ZONE-1",Own Sources,1,2018-19,2018-19 BR/2018-19/1158,Roads,Completed,BR-Bus Route Roads,2,335000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 1 against the challan no 07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017 and Deposit code 57/0666/2017-18.",Deposit Works,1,2018-19,2019-20 L/2018-19/5210,Electrical,Completed,L-Electrical,2,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Valluvar nagar 6th street in Div-2 in Zone - 1 E.B.Account.No.023.009.233",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5211,Electrical,Completed,L-Electrical,2,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Chinnakuppam 1st street in Div-2 in Zone - 1 E.B.Account.No.023.020.142",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5212,Electrical,Completed,L-Electrical,2,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Periyakuppam Near Ennore express road in Div-2 in Zone - 1 E.B.Account.No.023.019.196",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5223,Electrical,Completed,L-Electrical,2,538000,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Nehru Nagar School Ellaiamman Kovil street in Div-2, Zone - I E.B Account Number : 023.004.340",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5224,Electrical,Completed,L-Electrical,2,613000,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing in CMS School at Kathivakkam school at Kathivakkam High Road in Div-2 in Zone - 1 E.B.Account.No. 023.003.594",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5225,Electrical,Completed,L-Electrical,2,312000,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS Periyakuppam Ennore High Road (School) in Div-2, Zone - I . E.B Account Number : 023.019.116",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5226,Electrical,Completed,L-Electrical,2,388000,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing in UPHC Hoispital at Kathivakkam high road in Div-2, Zone - I",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5227,Electrical,Completed,L-Electrical,2,538000,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit-1,Office building ,Katthivakkam High road in Div-2, Zone - I E.B Account Number : 023.003.582,583,597 .",SMART CITY - ELECTRICAL,1,2018-19,2019-20 NA/2018-19/12551,Buildings,Completed,NA-THIRUVOTTIYUR,2,200000,"IMPROVEMENTS TO AMMA UNAVAGAM AT K.H.ROAD IN DIV-02, UNIT-01, ZONE-01",Own Sources,1,2018-19,2020-21 NA/2018-19/12552,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,517000,"DISMANTLING AND RECONSTRUCTION OF SIDE DRAIN AT KATTU KUPPAM 1 & 2 STREETS, .BAJANAI KOIL STREET, PORKALIAMMAN KOIL STREET AND KATTUKUPPAM MAIN ROAD IN DIV-02, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/12553,Buildings,Completed,NA-THIRUVOTTIYUR,2,540000,"REPAIR WORKS OF SIDE DRAIN AT NEHRU NAGAR 1 & 3,STREET, BAJANAI KOIL STREET AND VINAYAKAR KOIL STREET IN DIV-02, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/12554,Buildings,Completed,NA-THIRUVOTTIYUR,2,445000,"IMPROVEMENT TO UNIT OFFICE BUILDING IN DIV-02, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/12701,Buildings,Completed,NA-THIRUVOTTIYUR,2,200000,"IMPROVEMENT TO AMMA UNAVAGAM AT VILLAGE STREET DIV-02,UNIT-01 ZONE-01",Own Sources,1,2018-19,2020-21 NA/2018-19/13223,Buildings,Completed,NA-THIRUVOTTIYUR,2,200000,"IMPROVEMENT TO ANGANWADI BUILDING CENTRE NO.12 AT SASTRI NAGAR IN DIV-02, UNIT-01, ZONE-01",Own Sources,1,2018-19,2020-21 NA/2018-19/14768,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,320000,"PROPOSED CONSTRUCTION OF NEW SIDE DRAIN AT SWEEPER COLONY IN DIV-02, UNIT-01, ZONE-01",Own Sources,1,2018-19,2019-20 NA/2018-19/1809,Roads,Completed,NA-THIRUVOTTIYUR,2,829000,"IMPROVEMENT TO INTERIOR B.T ROAD AT KAMARAJ NAGAR 5TH STREET IN DIVISION 2, UNIT 1, ZONE 1.",Grants,1,2018-19,2019-20 NA/2018-19/1810,Roads,Completed,NA-THIRUVOTTIYUR,2,443000,"IMPROVEMENT TO INTERIOR B.T ROAD AT KAMARAJ NAGAR 6TH STREET IN DIVISION 2, UNIT 1, ZONE 1.",Grants,1,2018-19,2019-20 NA/2018-19/1811,Roads,Completed,NA-THIRUVOTTIYUR,2,2390000,"IMPROVEMENT TO INTERIOR B.T ROAD AT KOTHARI MAIN ROAD IN DIVISION 2, UNIT 1, ZONE 1.",Grants,1,2018-19,2019-20 NA/2018-19/1812,Roads,Completed,NA-THIRUVOTTIYUR,2,506000,"IMPROVEMENT TO INTERIOR B.T ROAD AT ELLIAMMAN KOIL MAIN STREET (Giriappa thottam from K.H road to Indira nagar main road) IN DIVISION 2, UNIT 1, ZONE 1.",Grants,1,2018-19,2019-20 NA/2018-19/1813,Roads,Completed,NA-THIRUVOTTIYUR,2,1121000,"IMPROVEMENT TO INTERIOR B.T ROAD AT INDRA NAGAR MAIN ROAD FROM ELAIAMMAN KOIL ST (Giriapa thottam to B canal road) IN DIVISION 2, UNIT 1, ZONE 1.",Grants,1,2018-19,2019-20 NA/2018-19/1814,Road Cut,Completed,NA-THIRUVOTTIYUR,2,633000,"IMPROVEMENT TO INTERIOR B.T ROAD AT VILLAGE STREET IN DIVISION 2, UNIT 1, ZONE 1",Grants,1,2018-19,2019-20 NA/2018-19/1815,Roads,Completed,NA-THIRUVOTTIYUR,2,585000,"IMPROVEMENT TO INTERIOR B.T ROAD AT SIVAN PADAI VEEDHI STREET IN DIVISION 2, UNIT 1, ZONE 1",Grants,1,2018-19,2019-20 NA/2018-19/2777,Roads,Completed,NA-THIRUVOTTIYUR,2,198000,"IMPROVEMENT TO INTERIOR B.T ROAD AT VINAYAGAR KOIL STREET IN DIVISION 2, UNIT 1, ZONE 1",Grants,1,2018-19,2019-20 NA/2018-19/2778,Roads,Completed,NA-THIRUVOTTIYUR,2,408000,"IMPROVEMENT TO INTERIOR B.T ROAD AT NEHRU NAGAR LINK STREET IN DN 2, UNIT 1, ZONE 1",Grants,1,2018-19,2019-20 NA/2018-19/2779,Roads,Completed,NA-THIRUVOTTIYUR,2,807000,"IMPROVEMENT TO INTERIOR B.T ROAD AT PORKALIAMMAN KOIL STREET IN DIVISION 2, UNIT 1, ZONE 1",Grants,1,2018-19,2019-20 NA/2018-19/3500,Buildings,Completed,NA-THIRUVOTTIYUR,2,165000,"REPAIR & MAINTENANCE WORKS IN CHENNAI PRIMARY SCHOOL AT PREIYA KUPPAM ENNORE EXPRESS ROAD IN DIV-2, UNIT-1, ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/4141,Culvert,Completed,NA-THIRUVOTTIYUR,2,261000,"CONSTRUCTION OF ROAD CROSS CULVERT AT NEHRU NAGAR LINK STREET IN DIV-2, UNIT-1, ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/4259,Buildings,Completed,NA-THIRUVOTTIYUR,2,175000,"DESILTING OF OPEN SIDE DRAIN AT VARIOUS STREETS IN DIV-2, UNIT-1, ZONE-1",Own Sources,1,2018-19,2018-19 NA/2018-19/4261,Parks,Completed,P-Parks and Playfields,2,690025,"Plantation and Maintenance of Tree saplings for one year at various street in Division 2, Unit 1, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/8564,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,160000,"REPAIR WORK IN OPEN SIDE DRAIN WORK AT VARIOUS STREETS IN DIV-2, UNIT-1, ZONE-1",Own Sources,1,2018-19,2018-19 L/2018-19/5213,Electrical,Completed,L-Electrical,3,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Ernavoor Kuppam Main Road in Div-3 in Zone - 1 E.B.Account.No.023.021.122",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5228,Electrical,Completed,L-Electrical,3,312000,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS Annaisivagami nagar 10 th street near Ennore High Road (School) in Div-3, Zone - I . E.B Account Number : 023.022.320",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5229,Electrical,Completed,L-Electrical,3,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kasi kovil kuppam school building at Kasikovilkuppam main street in Div-3 in Zone - 1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/7256,Electrical,Completed,L-Electrical,3,880500,"Provision of 14 nos. of 6 mtr G.I lamp post with Single Straight Bracket and 4nos of 6mtr G.I.lamp post with Double Straight Bracket with 22Nos of 40w LED fittings at TNSCB-Reconstruction North division construction of 128 tenements (G+3) at Indira gandhi kuppam , in Division-3, Zone-I [SOR-2017-18]",Deposit Works,1,2018-19,2019-20 NA/2018-19/1217,Roads,Completed,NA-THIRUVOTTIYUR,3,1410000,"IMPROVEMENT TO INTERIOR BT ROAD AT TSUNAMI QUARTERS 1ST MAIN ROAD(PART) IN DN-3, UNIT-1, ZONE-1 (340m x 7.00m =2380sqm)",Grants,1,2018-19,2018-19 NA/2018-19/1218,Roads,Completed,NA-THIRUVOTTIYUR,3,186000,"IMPROVEMENTS TO THE BT ROAD AT TSUNAMI QUARTERS 7TH CROSS ROAD IN DN-3,UNIT-1,ZONE-1 (63m x 5.00m=315sqm)",Grants,1,2018-19,2019-20 NA/2018-19/1219,Roads,Completed,NA-THIRUVOTTIYUR,3,186000,"Improvement to Interior BT road at Tsunami quarters 20th cross road in Dn-3, Unit-1, Zone-1 (63m x 5.00m=315sqm)",Grants,1,2018-19,2019-20 NA/2018-19/1220,Roads,Completed,NA-THIRUVOTTIYUR,3,1451000,"Improvements to Interior BT road at Tsunami quarters 4th main road in Dn-3, Unit-1, Zone-1 (350M X 7.00M=2450 sqm)",Grants,1,2018-19,2018-19 NA/2018-19/13453,Buildings,Completed,NA-THIRUVOTTIYUR,3,382000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT ANNAI SIVAGAMI NAGAR IN DN-3, UNIT-1, ZONE-1",Own Sources,1,2018-19,2020-21 NA/2018-19/13461,Buildings,Completed,NA-THIRUVOTTIYUR,3,290000,"REPAIR & IMPROVEMENT WORKS TO URBAN PRIMARY HEALTH CENTRE(UPHC) AT TSUNAMI QUARTS IN DIV-03, UNIT-01, ZONE-01.",Own Sources,1,2018-19,2020-21 NA/2018-19/13462,Buildings,Completed,NA-THIRUVOTTIYUR,3,140000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT NETHAJI NAGAR IN DN-3 , UNIT-1,ZONE-1",Own Sources,1,2018-19,2020-21 NA/2018-19/1554,Roads,Completed,NA-THIRUVOTTIYUR,3,1433000,"IMPROVEMENT TO INTERIOR CEMENT CONCRETE ROAD AT ANNAI SIVAGAMI NAGAR BEACH ROAD IN DN-3, UNIT-1, ZONE-1 (L=275M W=3.00M A=825 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/1555,Roads,Completed,NA-THIRUVOTTIYUR,3,622000,"IMPROVEMENT TO INTERIOR CC ROAD AT ANNAI SIVAGAMI NAGAR 10TH STREET EXTN IN DN-3,UNIT-1,ZONE-1(L=120M W=3.00M A=360 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/17483,Parks,Completed,P-Parks and Playfields,3,253017,"Plantation and Maintenance of Tree saplings for one year at various street in Division 3, Unit 1, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/8868,Parks,Completed,NA-THIRUVOTTIYUR,3,248000,"ANNUAL MAINTENANCE PARK-4 AT Tsunami qrts (ALL INDIA RADIO NAGAR) IN DN-3, UNIT-1, ZONE-1",Own Sources,1,2018-19,2019-20 L/2018-19/5214,Electrical,Completed,L-Electrical,4,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Anganwadi building at Ramanathapuram 10 th street in Div-4 in Zone - 1 E.B.Account.No. 016.017.392",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5215,Electrical,Completed,L-Electrical,4,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Health post building at Earneeswaran nagar 1st street/school street in Div-4 in Zone - 1 E.B.Account.No.",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5230,Electrical,Completed,L-Electrical,4,388000,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing in UPHC Hoispital at Ramanathapuram main street,Near Wimco Railway station in Div-4, Zone - I",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5231,Electrical,Completed,L-Electrical,4,688000,"Supply, Installation, Testing & Commissioning of 9 Kwp Grid Tied Solar Rooftop including Civil works and earthing in CPS&CHS School at Earneeswaran nagar 1st street&Makakaliammankovil ,school street in Div-4 in Zone - 1 E.B.Account.No. 023.0031.327.",SMART CITY - ELECTRICAL,1,2018-19,2019-20 NA/2018-19/0270,Roads,Completed,NA-THIRUVOTTIYUR,4,472000,"Improvement to Interior CC Road at Mahalakshmi nagar 2nd st, Eranavoor in Div 4, Unit 1, Zone 1.",Grants,1,2018-19,2019-20 NA/2018-19/11077,Buildings,Completed,NA-THIRUVOTTIYUR,4,507000,"Providing the compound wall arrangement in Chennai Middle School building at Ramanathapuram school street in Div-4, Unit-1, Zone-1.",Own Sources,1,2018-19,2019-20 NA/2018-19/1222,Roads,Completed,NA-THIRUVOTTIYUR,4,850000,"Improvement to interior BT road at Kamaraj nagar 1st Main Road, Eranavoor in Div-4, Unit-1, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/12474,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,135000,"Maintenance work in Amma unavagam at Bajanai koil street Ernavoor in Div-4, Unit-1, Zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/1514,Roads,Completed,NA-THIRUVOTTIYUR,4,893000,"Improvement to interior B.T road at Eraneeshwaran Nagar 4th street in Div-4, Unit-1, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/17485,Parks,Completed,P-Parks and Playfields,4,650829,"Plantation and Maintenance of Tree saplings for one year at various street in Division 4, Unit 1, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/2385,Buildings,Completed,NA-THIRUVOTTIYUR,4,140000,"Demolishing the Dilapidated Chennai Middle School Building at Ramanathapuram school st in Div-4,Unit-1,Zone-1",Own Sources,1,2018-19,2018-19 NA/2018-19/3395,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,348000,"Providing the Top cover slab in open side drain at V.P.Nagar 5th st in Div-4, Unit-1, Zone-1",Own Sources,1,2018-19,2018-19 NA/2018-19/3477,Buildings,Completed,NA-THIRUVOTTIYUR,4,108791,"Repairs and maintenance work in Chennai Primary school at Mahalliamman school st, Ernavoor in Div-4, Unit-1, Zone-1.",Own Sources,1,2018-19,2019-20 NA/2018-19/3580,Buildings,Completed,NA-THIRUVOTTIYUR,4,193000,"Improvements and Mainteance work in chennai middle school at Ramanathapuram school st in Div-4, Unit-1, Zone-1",Own Sources,1,2018-19,2019-20 NA/2018-19/7933,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,146000,"DESILTING OF OPEN SIDE DRAIN AND STORM WATER DRAIN AT VARIOUS STREETS IN DIV-4, UNIT-1, ZONE-1.",Own Sources,1,2018-19,2018-19 NA/2018-19/8024,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,650000,"Providing the top cover slab in open side drain at Brindavan nagar extension 2 nd st ,Ernavoor in div-4,unit-1,Zone-1.",Own Sources,1,2018-19,2019-20 NA/2018-19/8563,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,4,160000,"Repair work in open side drain at various street in Div-4, Unit-1, Zone-1",Own Sources,1,2018-19,2018-19 L/2018-19/12496,Electrical,Completed,L-Electrical,5,199900,"Proposal for removal of 511 nos. of old SVL fittings and fixing of 511 nos. of LED Fittings at ward-5 and 6, Zone-1, Tiruvottriyur [SOR 2017-18]",Own Sources,1,2018-19,2019-20 L/2018-19/15812,Electrical,Completed,L-Electrical,5,3508000,"Proposal for commissioning of 46 nos. of 8 mtr Octagonal street lamp posts with G.I Double bracket at Ennore Express Way at Palagaithotti kuppam and KVK Kuppam area in ward-5, Zone-1",Own Sources,1,2018-19,2019-20 L/2018-19/15814,Electrical,Completed,L-Electrical,5,3396000,"Proposal for commissioning of 45 nos. of 8 mtr Octagonal street lamp posts with G.I Double bracket at Ennore Express Way at Ramakrishna nagar and KVK Kuppam area in ward-5, Zone-1 Tiruvottriyur",Own Sources,1,2018-19,2019-20 L/2018-19/16125,Electrical,Completed,L-Electrical,5,1645200,Proposal for removal of 8 nos. of 8 Mtr. G.I lamp posts with Single arch braket with LED fittings and Erecting of 8 nos. of 8 Mtr. G.I lamp posts and provision of 10 nos. of 8 Mtr. G.I lamp posts with 150w-165w LED fittings at Neithal Nagar in Division 5 in Zone-1 [SOR 2017-18],Deposit Works,1,2018-19,2019-20 NA/2018-19/0365,Roads,Completed,NA-THIRUVOTTIYUR,5,1088000,"IMPROVEMENTS TO INTERIOR CC ROAD AT CHINNA ERNAVOOR 2ND STREET IN DN-5,UNIT-2,ZONE-1 (L=150M W=4.00M A=600 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/0707,Roads,Completed,NA-THIRUVOTTIYUR,5,771000,"IMPROVEMENTS TO CEMENT CONCRETE ROAD AT CHINNA ERNAVOOR 3RD STREET IN DN-5, UNIT-2, ZONE-1 (L=150M W=2.80M A=420 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/0708,Roads,Completed,NA-THIRUVOTTIYUR,5,1088000,"IMPROVEMENTS TO INTERIOR CC ROAD AT CHINNA ERNAVOOR 4TH STREET IN DN-5,UNIT-2,ZONE-1 (L=150M W=4.00M A=600 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/0858,Roads,Completed,NA-THIRUVOTTIYUR,5,1662000,"IMPROVEMENTS TO INTERIOR BT ROAD AT MANICKAM NAGAR MAIN ROAD IN DN-5,UNIT-2,ZONE-1 (L=240M W=10M A=2400 SQM)",Grants,1,2018-19,2018-19 NA/2018-19/0860,Roads,Completed,NA-THIRUVOTTIYUR,5,928000,"IMPROVERMENTS TO INTERIOR B.T ROAD AT SAKTHIPURAM MAIN ROAD (PART) IN DN-5, UNIT-2, ZONE-1 (L=285M W=4.50M A=1282.50 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/1213,Roads,Completed,NA-THIRUVOTTIYUR,5,654000,"IMPROVEMENT TO INTERIOR BT ROAD A THIRU NAGAR 2ND STREET IN DN-5,UNIT-2,ZONE-1 (L=210M W=4.50M A=945 SQM)",Grants,1,2018-19,2018-19 NA/2018-19/1214,Roads,Completed,NA-THIRUVOTTIYUR,5,748000,"IMPROVEMENT TO INTERIOR BT ROAD AT ANJUGAM NAGAR 2ND STREET IN DN-5, UNIT-2, ZONE-1(L=240M W=4.50M A=1080 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/1215,Roads,Completed,NA-THIRUVOTTIYUR,5,946000,"IMPROVEMENT TO INTERIOR B.T ROAD AT SAKTHIPURAM 2ND STREET(PART) IN DN-5, UNIT-2, ZONE-1 (L=290 W=4.50 A=1305 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/1216,Roads,Completed,NA-THIRUVOTTIYUR,5,138000,"IMPROVEMENT TO INTERIOR B.T ROAD AT SAKTHIPURAM 3RD CROSS STREET IN DN-5,UNIT-2,ZONE-1(L=36M W=6.00M A=216 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/12345,Playfields,Completed,NA-THIRUVOTTIYUR,5,589000,"PROVIDING GYM EQUIPMENT AT EXISTING ROOM IN SIDE THE PARK AT SAKTHIPURAM (SRI RANGAM NEW TOWN) IN DN-5,UNIT-2,ZONE-1.",MLACDS,1,2018-19,2019-20 NA/2018-19/1291,Roads,Completed,NA-THIRUVOTTIYUR,5,368000,"IMPROVEMENT TO INTERIOR CC ROAD FOR SERVICE ROAD (NORTH SIDE) AT MANICKAM NAGAR SUBWAY IN DN-5,UNIT-2,ZONE-1(L=60M W=3.00M A=180 SQM)",Grants,1,2018-19,2019-20 NA/2018-19/13951,Roads,Completed,NA-THIRUVOTTIYUR,5,746000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND PROVIDING THERMO PLASTIC COMPOUND MARKING AND SIGNAGE BOARDS AT RAMAKRISHNA NAGAR 1ST,2ND,3RD AND 4TH MAIN ROAD IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/17486,Parks,Completed,P-Parks and Playfields,5,639416,"Plantation and Maintenance of Tree saplings for one year at various street in Division 5, Unit 2, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/3112,Roads,Completed,NA-THIRUVOTTIYUR,5,997000,"PROPOSED SPEED BREAKERS AS PER IRC DESIGN WITH BITUMINOUS CONCRETE AND PROVIDING THERMOPLASTIC COMPOUND MARKING AND SIGNAGE BOARDS AT BHARATHIYAR NAGAR 1ST,2ND,3RD,4TH,5TH,AND 6TH STREET IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2018-19,2019-20 NA/2018-19/3482,Buildings,Completed,NA-THIRUVOTTIYUR,5,122000,"REPAIR AND IMPROVEMENTS TO AMMA UNAVAGAM AT BHARATHIYAR NAGAR 2ND STREET IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/3634,Parks,Completed,NA-THIRUVOTTIYUR,5,222000,"IMPROVEMENTS TO GREENERY AREA AND OTHER IMPROVEMENT TO GCC PARK AT HANSA GARDEN OSR LAND , AJAX, THIRUVOTTIYUR IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2018-19 NA/2018-19/3829,Subway,Completed,NA-THIRUVOTTIYUR,5,186000,"REPAIRS AND IMPROVEMENT TO SUBWAY PUMP ROOM AT MANICKAM NAGAR IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/5088,Parks,Completed,NA-THIRUVOTTIYUR,5,665000,"ANNUAL MAINTENANCE FOR PARK AT SAKTHIPURAM IN DIV - 5 , UNIT - 2 , ZONE - 1. ( AREA = 3659 sq.m).",Own Sources,1,2018-19,2019-20 NA/2018-19/5089,Parks,Completed,NA-THIRUVOTTIYUR,5,261000,"ANNUAL MAINTENANCE FOR PARK AT HANSA GARDEN PARK , AJAX , THIRUVOTTIYUR IN DIV-5 , UNIT-2 , ZONE-1 (AREA=1411.50 sq.m).",Own Sources,1,2018-19,2019-20 NA/2018-19/5653,Roads,Completed,NA-THIRUVOTTIYUR,5,88000,"RE PAINTING OF SPEED BREAKER AT MRF ROAD,SAKTHIPURAM MAIN ROAD,RAMAKRISHNA NAGAR 4TH MAIN ROAD AND 3RD CROSS STREET ( Total No- 7) IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/5655,Buildings,Completed,NA-THIRUVOTTIYUR,5,58000,"PAINTING OF COMPACTOR BINS (SMALL AND BIG) SIZE AT VARIOUS LOCATION IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/6492,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,698000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREETS IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/6995,Roads,Completed,NA-THIRUVOTTIYUR,5,146000,"PROVIDING STAINLESS STEEL STREET NAME BOARD AND RAIN WATER HARVESTING AT SRI NAGAR AND THIRUMALAI NAGAR IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2020-21 NA/2018-19/6996,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,915000,"PROVIDING RCC LOOSE COVER SLAB FOR SIDE DRAIN AT SAKTHIPURAM MAIN ROAD IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2018-19,2019-20 NA/2018-19/8027,Buildings,Completed,NA-THIRUVOTTIYUR,5,171000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT MANICKAM NAGAR MAIN ROAD IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2020-21 NA/2018-19/8134,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,26000,"DESILTING OF STORM WATER DRAIN AT MRF ROAD IN DN-5, UNIT-2, ZONE-1",Own Sources,1,2018-19,2018-19 NA/2018-19/8635,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,174000,"MINOR REPAIRS TO STORM WATER DRAIN AT MRF ROAD IN DN-5,UNIT-2,ZONE-1",Own Sources,1,2018-19,2019-20 NA/2018-19/1729,Roads,Completed,NA-THIRUVOTTIYUR,6,3074000,"Improvement to Interior B.T road at Madura nagar Main road in Division-6, Unit-2, Zone-1",Grants,1,2018-19,2018-19 NA/2018-19/1733,Roads,Completed,NA-THIRUVOTTIYUR,6,1115000,"IMPROVEMENT TO INTERIOR BT ROAD AT SAKTHI GANAPATHI NAGAR 9TH STREET IN DN-6, UNIT-2, ZONE 1",Grants,1,2018-19,2018-19 NA/2018-19/1737,Roads,Completed,NA-THIRUVOTTIYUR,6,1163000,"IMPROVEMENT TO INTERIOR BT ROAD AT SAKTHI GANAPATHI NAGAR 2ND STREET IN DIVISION 6, UNIT 2, ZONE 1",Grants,1,2018-19,2018-19 NA/2018-19/1741,Roads,Completed,NA-THIRUVOTTIYUR,6,399000,IMPROVEMENT TO INTERIOR BT ROAD AT SUBRAMANIYAM NAGAR 3RD CROSS STREET IN DIVISION 6 UNIT 02,Grants,1,2018-19,2018-19 NA/2018-19/1742,Roads,Completed,NA-THIRUVOTTIYUR,6,2493000,IMPROVEMENT TO INTERIOR BT ROAD AT RAJASHANMUGAM NAGAR 4TH STREET IN DIVISION 6 UNIT 2 ZONE 1,Grants,1,2018-19,2018-19 NA/2018-19/1743,Roads,Completed,NA-THIRUVOTTIYUR,6,487000,"IMPROVEMENT TO INTERIOR BT ROAD AT AMBEDKAR NAGAR PILLAIYAR KOIL STREET IN DIVISION 6, UNIT 2, ZONE 1",Grants,1,2018-19,2018-19 NA/2018-19/6388,Storm Water Drain,Completed,P-Parks and Playfields,6,710726,"Plantation and Maintenance of Tree saplings for one year at various street in Division 6, Unit 2, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/8148,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,671000,"DESLITING OF STROM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREET IN DIV-6, UNIT-2, ZONE-1.",Own Sources,1,2018-19,2018-19 D/2018-19/9658,Storm Water Drain,Completed,D-Storm Water Drains,7,30350000,"Construction of Storm Water Drain of at Karkil Nagar in Dn-7, Zone - 1 in Package - 1",Grants,1,2018-19,2019-20 L/2018-19/10755,Electrical,Completed,L-Electrical,7,199450,"Proposal for Replacement of 284 Mtr. 31/2x 25 sq.mm cable laying of 9 nos. 8 mtr G.I straigh street lamp posts Near Balmer Laurie company Gate 1 at Manali salai Way near CPCL junction in division-7, Zone-1 Tiruvottriyur",Own Sources,1,2018-19,2020-21 L/2018-19/10763,Electrical,Completed,L-Electrical,7,976550,"Proposal for Removal and Refixing of 19 nos. of 8 mtr G.I straight street lamp posts with Double straight bracket and Replacement of 673 Mtr. 31/2x 25 sq.mm Alu. cable at Basin salai near Mattumandhai bridge in division-7, Zone-1 Tiruvottriyur",Own Sources,1,2018-19,2020-21 L/2018-19/12149,Electrical,Completed,L-Electrical,7,199950,"Proposal for Replacement of 381 Mtr. 31/2x 25 sq.mm cable laying of 12nos. 8 mtr G.I straigh street lamp posts Near Kotari Petrochemicals Limited Gate 1& 2 at Manali salai Way near CPCL junction in division-7, Zone-1 Tiruvottriyur",Own Sources,1,2018-19,2020-21 L/2018-19/12150,Electrical,Completed,L-Electrical,7,199700,"Proposal for Replacement of 352 Mtr. 31/2x 25 sq.mm cable laying of 10 nos. 8 mtr G.I straigh street lamp posts Near Balmer Laurie Gate-2 at Manali salai Way near CPCL junction in division-7, Zone-1 Tiruvottriyur",Own Sources,1,2018-19,2020-21 L/2018-19/5136,Electrical,Completed,L-Electrical,7,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office in Div-7at Bala krishna nagar main road, Zone - I . E.B Account Number : 016.055.264 .",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5137,Electrical,Completed,L-Electrical,7,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office in Div-6 at Jothi nagar 10 th street, Zone - I . E.B Account Number : 022.008.485 .",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5138,Electrical,Completed,L-Electrical,7,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office in Div-8 at Periyar nagar main road, Zone - I . E.B Account Number : 021.024.355 .",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5139,Electrical,Completed,L-Electrical,7,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office in Div-5 at Rama krishna nagar main road, Zone - I . E.B Account Number : 022.008.485 .",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5140,Electrical,Completed,L-Electrical,7,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Chennai Middle School at Thyagi Sathyamurthy Nagar in Div-6, Zone - I",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5141,Electrical,Completed,L-Electrical,7,688000,"Supply, Installation, Testing & Commissioning of 9 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Chennai Middle School at Thyagi Sathyamurthy Nagar in Div-6, Zone - I",Own Sources,1,2018-19,2019-20 NA/2018-19/13003,Buildings,Completed,NA-THIRUVOTTIYUR,7,275000,"Providing Compactor Bin Platform, Painting of Bins and Speed Brackers at various streets in Division-7, Unit-2, Zone-1.",Own Sources,1,2018-19,2020-21 NA/2018-19/8193,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,85000,"Desilting of Storm Water Drain at Various Streets in Division-7, Unit-2, Zone-1.",Own Sources,1,2018-19,2018-19 NA/2018-19/8197,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,148000,"Minor repair work in Storm Water Drain at various Streets in Division-7, Unit-3, Zone-1.",Own Sources,1,2018-19,2019-20 L/2018-19/15815,Electrical,Completed,L-Electrical,8,4341000,"Proposal for commissioning of 60 nos. of 8 mtr Octagonal street lamp posts with G.I Double bracket at Ennore Express Way at Masthan koil and Carborundum junction in ward-5 & 8, Zone-1 Tiruvottriyur",Own Sources,1,2018-19,2019-20 NA/2018-19/0048,Buildings,Completed,NA-THIRUVOTTIYUR,8,176000,"Maintenance and Repair work in Amma Unavagam at Ennore Exrpress Road (Phase-II) in Div-8, Unit-2, Zone-I.",Own Sources,1,2018-19,2020-21 NA/2018-19/13285,Buildings,Completed,NA-THIRUVOTTIYUR,8,196000,"Maintenance in Unit office at Ennore Express road in kakanji nagar in Div-8, Unit-2, Zone-I.",Own Sources,1,2018-19,2020-21 NA/2018-19/1354,Roads,Completed,NA-THIRUVOTTIYUR,8,327000,"Improvement to the Interior B.T road at Munusamy street in Division-8, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/13787,Buildings,Completed,NA-THIRUVOTTIYUR,8,657000,"Construction of room at first floor and raising ground floor in Dhobikana at Ekavalliamman koil street in Div-8, Unit-2, Zone-I.",Own Sources,1,2018-19,2019-20 NA/2018-19/1401,Roads,Completed,NA-THIRUVOTTIYUR,8,651000,"Improvement to the Interior B.T road at Ekavalli amman koil street in Division-8, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1410,Roads,Completed,NA-THIRUVOTTIYUR,8,637000,"Improvement to the Interior B.T road at Bharathiyar nagar in Division-8, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1413,Roads,Completed,NA-THIRUVOTTIYUR,8,406000,"Improvement to the Interior B.T road at T S R nagr 1st street in Division-8, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1433,Roads,Completed,NA-THIRUVOTTIYUR,8,143000,"Improvement to the Interior B.T road at T.S.R NAGAR 3rd street in Division-8, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1470,Roads,Completed,NA-THIRUVOTTIYUR,8,388000,"Improvement to the Interior B.T road at Anjugam Nagar main street in Division-8, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1475,Roads,Completed,NA-THIRUVOTTIYUR,8,1090000,"Improvement to the Interior B.T road at Othavadi street in Division-8, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/17487,Parks,Completed,P-Parks and Playfields,8,388719,"Plantation and Maintenance of Tree saplings for one year at various street in Division 8, Unit 2, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/6980,Buildings,Completed,NA-THIRUVOTTIYUR,8,175000,"Maintenance and Repair work in Amma unavagam at Periyar nagar (Phase-I) in Div-8, Unit-2, Zone-I.",Own Sources,1,2018-19,2019-20 L/2018-19/12497,Electrical,Completed,L-Electrical,9,194100,"Proposal for removal of 496 nos. of old SVL fittings and fixing of 496 nos. of LED Fittings at ward-9, 10 and 11 Zone-1, Tiruvottriyur [SOR 2017-18]",Own Sources,1,2018-19,2019-20 L/2018-19/3094,Electrical,Completed,L-Electrical,9,1757300,"Proposal for supply and erection of 14 nos. of 8 mtr G.I Octogonal mini mast hexagonal lantern carriage with 3 nos. of 70w to 100w flood light fittings at Ennore Express Road in Dn-5, 8, 9, 11 and 14 Zone-1 [SOR 2017-18]",Own Sources,1,2018-19,2019-20 NA/2018-19/1443,Roads,Completed,NA-THIRUVOTTIYUR,9,1592000,"Improvement to the Interior B.T road at Esanamoorthy koil street in Division-9, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1446,Roads,Completed,NA-THIRUVOTTIYUR,9,1050000,"Improvement to the Interior B.T road at Thulukanam street in Division-9, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1453,Roads,Completed,NA-THIRUVOTTIYUR,9,875000,"Improvement to the Interior B.T road at Nadabai Garden street in Division-9, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1462,Roads,Completed,NA-THIRUVOTTIYUR,9,367000,"Improvement to the Interior B.T road at MVN Nagar in Division-9, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1466,Roads,Completed,NA-THIRUVOTTIYUR,9,700000,"Improvement to the Interior B.T road at T.S.Gopal nagar in Division-9, Unit-2, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/17488,Parks,Completed,P-Parks and Playfields,9,296755,"Plantation and Maintenance of Tree saplings for one year at various street in Division 9, Unit 2, Zone 1",Own Sources,1,2018-19,2019-20 BR/2018-19/3065,Roads,Completed,BR-Bus Route Roads,10,129000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 1 against the challan no 07/2017-18/0377458,07/2017-18/0377463 DT: 21.07.2017 and Deposit code 57/0668/2017-18.",Deposit Works,1,2018-19,2019-20 L/2018-19/5167,Electrical,Completed,L-Electrical,10,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing in the building of Anganwadi at West mada street in Dn-10 in Zone-1 (TNEB A/c No.-021.008.790)",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5168,Electrical,Completed,L-Electrical,10,161400,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in the building of Anganwadi at West mada street in Dn-10 in Zone-1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5176,Electrical,Completed,L-Electrical,10,312000,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Roof top including Civil works and earthing in the building of Unit office-3 at West mada Street, in Dn-10 in Zone-1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5179,Electrical,Completed,L-Electrical,10,462500,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Roof top including Civil works and earthing in the building of Chennai Middle School at Tiruvottriyur Sannathy Street, in Dn-10 in Zone-1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 NA/2018-19/0311,Roads,Completed,NA-THIRUVOTTIYUR,10,786000,"Improvement to Interior BT Road at Nellikaran street in Division-10, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0312,Roads,Completed,NA-THIRUVOTTIYUR,10,412000,"Improvement to Interior BT Road at Amsa garden 2nd street in Division-10, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0313,Roads,Completed,NA-THIRUVOTTIYUR,10,307000,"Improvement to interior BT Road at Amsa garden 3rd street in Division-10, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0316,Roads,Completed,NA-THIRUVOTTIYUR,10,737000,"Improvement to Interior BT Road at Amsa garden 4th street in Division-10, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0317,Roads,Completed,NA-THIRUVOTTIYUR,10,943000,"Improvement to Interior BT Road at Rajeshwari nagar in Division-10, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0318,Roads,Completed,NA-THIRUVOTTIYUR,10,923000,"Improvement to Interior CC Road at West Tank Street in Division-10,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/12987,Buildings,Completed,NA-THIRUVOTTIYUR,10,330000,"REPAIR AND IMPROVEMENT WORKS OF UNIT OFFICE - 3 AT WEST MADA STREET IN DIVISION-10, UNIT-03, ZONE-01.",Own Sources,1,2018-19,2021-22 NA/2018-19/1316,Roads,Completed,NA-THIRUVOTTIYUR,10,2551000,"Improvement to Interior BT Road at North mada street in Division-10, Unit-3, Zone-1",Grants,1,2018-19,2018-19 NA/2018-19/1714,Roads,Completed,NA-THIRUVOTTIYUR,10,408000,"Improvement to Interior BT Road at Amsa Garden 1st Street in Division-10,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/2911,Roads,Completed,NA-THIRUVOTTIYUR,10,506000,"Improvement to Interior BT Road at West Mada Street (Nandhi Odai,Periyathottam) in Division-10, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/4454,Buildings,Completed,NA-THIRUVOTTIYUR,10,112000,REPAIRS AND IMPROVEMENTS TO CHENNAI CORPORATION MIDDLE SCHOOL AT SANNATHI STREET IN DN-10 UNIT-3 ZONE-1,Own Sources,1,2018-19,2020-21 NA/2018-19/4461,Buildings,Completed,NA-THIRUVOTTIYUR,10,99000,"REPAIRS AND IMPROVEMENT TO P.C AT EAST TANK ROAD IN DN-10, UNIT-3, ZONE-1",Own Sources,1,2018-19,2020-21 NA/2018-19/5041,Parks,Completed,P-Parks and Playfields,10,356344,"Plantation and Maintenance of Tree saplings for one year at various street in Division 10, Unit 3, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/7667,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,10,50000,"Minor repairs work in SWD at Sannadhi Street (Theradi) and North Mada Street in Division-10, Unit-3, Zone-1",Own Sources,1,2018-19,2019-20 NA/2018-19/7668,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,10,43000,"Desilting of Storm Water Drain at Sannadhi Street (Theradi) and North Mada street in Division-10, Unit-3, Zone-1",Own Sources,1,2018-19,2020-21 D/2018-19/2913,Storm Water Drain,Completed,D-Storm Water Drains,11,818000,"Rejuvenation and other improvements to the Temple Tank at Kalyana Varadaraja Perumal Koil, Kaladipet including construction of RWH well under Sustainable Water Security Mission in Dn-11,Zone-1",SMART CITY - SWD,1,2018-19,2019-20 L/2018-19/15776,Electrical,Completed,L-Electrical,11,4697000,"Proposal for commissioning of 64 nos. of 8 mtr Octagonal street lamp posts with G.I Double bracket at Ennore Express Way from SBI Colony to pattinathar koil jn in ward-9 and 11, Zone-1 Tiruvottriyur [SOR 2017-18]",Own Sources,1,2018-19,2019-20 L/2018-19/5182,Electrical,Completed,L-Electrical,11,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Roof top including Civil works and earthing in the building of Zonal Office block-2 at Tiruvottriyur High Road, in Dn-11 in Zone-1 (TNEB A/c. No. 024.005.84)",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5183,Electrical,Completed,L-Electrical,11,838700,"Supply, Installation, Testing & Commissioning of 11 Kwp Grid Tied Solar Roof top including Civil works and earthing in the building of Zonal Office main block at Tiruvottriyur High Road, in Dn-11 in Zone-1 (TNEB A/c. No.-024.005.85)",SMART CITY - ELECTRICAL,1,2018-19,2019-20 NA/2018-19/1727,Roads,Completed,NA-THIRUVOTTIYUR,11,1149000,"Improvement to Interior CC Road at Periyamettupalayam 1st street in Division-11,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1728,Roads,Completed,NA-THIRUVOTTIYUR,11,1299000,"Improvement to Interior CC Road at Periyamettupalayam 2nd street in Division-11,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/17490,Parks,Completed,P-Parks and Playfields,11,584239,"Plantation and Maintenance of Tree saplings for one year at various street in Division 11, Unit 3, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/1899,Roads,Completed,NA-THIRUVOTTIYUR,11,1213000,"Improvement to Interior BT road at Vedhachalam avenue (Main street and Cross streets) in Division-11, Unit-3, Zone-1",Grants,1,2018-19,2018-19 NA/2018-19/1902,Roads,Completed,NA-THIRUVOTTIYUR,11,379000,"Improvement to Interior BT Road at Chinnamettupalayam 3rd street in Division-11, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1904,Roads,Completed,NA-THIRUVOTTIYUR,11,1510000,"Improvement to Interior B.T Road in Market lane at Division-11, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/3578,Buildings,Completed,NA-THIRUVOTTIYUR,11,134000,"Repairs and Improvements to Executive Engineer I and II Offices and Ground Floor Passage of T.H.Road Inside Zonal Office Campus in Division-11, Unit-3, Zone-1.",Own Sources,1,2018-19,2020-21 NA/2018-19/3662,Buildings,Completed,NA-THIRUVOTTIYUR,11,86000,"Repairs and Improvements to Gents and Ladies toilet in Zonal office at T.H road in Division-11, Unit-3, Zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/4419,Buildings,Completed,NA-THIRUVOTTIYUR,11,79000,"Repairs and Improvements to Anganwadi Centre No.48 of Vedhachalam Avenue in Division-11, Unit-3, Zone-1",Own Sources,1,2018-19,2019-20 NA/2018-19/4420,Buildings,Completed,NA-THIRUVOTTIYUR,11,124000,"Repairs and Improvements to Amma Unavagam Phase - I at T.H Road in Division-11, Unit-3, Zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/4699,Buildings,Completed,NA-THIRUVOTTIYUR,11,60000,"Repairs and Improvements to Anganwadi Centre No.44 of Vedhachalam Avenue in Division-11, Unit-3, Zone-1",Own Sources,1,2018-19,2019-20 NA/2018-19/5048,Buildings,Completed,NA-THIRUVOTTIYUR,11,642000,"Maintenance Estimate For park at Shanmuganagar Park in Division-11, Unit-3, Zone-1,(per Year) Area = 2900Sq.m",Own Sources,1,2018-19,2020-21 NA/2018-19/6516,Buildings,Completed,NA-THIRUVOTTIYUR,11,95000,"Demolishing the existing Dilapidated Buildings (Conservancy store room and Street light Store room) in Zonal Office Campus at T.H.Road in Division-11, Unit-3, Zone-1.",Own Sources,1,2018-19,2018-19 NA/2018-19/7904,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,11,81000,"Desilting of Storm Water Drain at Sannathi Street, Market lane and Ellaiamman Koil Street in Division-11, Unit-3, Zone-1",Own Sources,1,2018-19,2019-20 NA/2018-19/8280,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,11,152000,"Repairs and Improvements to Storm Water Drain at T.H. Road (From Ellai amman koil street to Market Lane) Both Sides in Divison-11, Unit-3, Zone-1",Own Sources,1,2018-19,2019-20 BR/2018-19/5431,Roads,Completed,BR-Bus Route Roads,12,2673000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at West Mada Street in Dn-12, Zone - I",Grants,1,2018-19,2019-20 L/2018-19/5169,Electrical,Completed,L-Electrical,12,161400,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in the building of Anganwadi at Vanniyar Street in Dn-12 in Zone-1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5171,Electrical,Completed,L-Electrical,12,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing in the building of Division Office at B.K.N Colony 3rd Street, in Dn-12 in Zone-1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 L/2018-19/5175,Electrical,Completed,L-Electrical,12,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Roof top including Civil works and earthing in the building of UPHC at B.K.N Colony 2nd Street, in Dn-12 in Zone-1",SMART CITY - ELECTRICAL,1,2018-19,2019-20 NA/2018-19/0296,Roads,Completed,NA-THIRUVOTTIYUR,12,1384000,"Improvement to interior BT Road at North Mada street in Division-12, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0297,Roads,Completed,NA-THIRUVOTTIYUR,12,1520000,"Improvement to Interior BT Road at Jandraver Street in Division-12, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/10724,Buildings,Completed,NA-THIRUVOTTIYUR,12,36000,"Repairs and improvements to Chennai primary school at North Pragaram street in Division-12, Unit-3,zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/10894,Buildings,Completed,NA-THIRUVOTTIYUR,12,388000,"Repairs and Improvements at Anganwadi Center (Center No: 79) at Kavarai Street in DN-12, Unit - 03, Zone -01.",Own Sources,1,2018-19,2020-21 NA/2018-19/17491,Parks,Completed,P-Parks and Playfields,12,36800,"Plantation and Maintenance of Tree saplings for one year at various street in Division 12, Unit 3, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/5177,Buildings,Completed,NA-THIRUVOTTIYUR,12,32000,"Repairs and Improvements to NNMP Shed (CPS) at North Pragaram Street in Division-12, Unit-3, Zone-1",Own Sources,1,2018-19,2019-20 NA/2018-19/7626,Road Cut,Completed,NA-THIRUVOTTIYUR,12,678000,"Restoration of Road cut made by CMWSSB at Thilagar Nagar 1st Street in Division-12, Unit-3, Zone-1",Deposit Works,1,2018-19,2019-20 NA/2018-19/8471,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,12,201000,"Minor repair work in Storm Water Drain at Chetty street, North pragaram street in Division-12, Unit-3, Zone-1",Own Sources,1,2018-19,2019-20 NA/2018-19/9604,Buildings,Completed,NA-THIRUVOTTIYUR,12,97000,"Repairs and Improvements at Amma Unavagam at West Mada Street in Dv-12, Unit-3, Zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/9682,Buildings,Completed,NA-THIRUVOTTIYUR,12,132000,"Repairs and Improvements to UPHC at Bala Krishna Nagar 2nd Street in DN-12, Unit-03, Zone-01.",Own Sources,1,2018-19,2020-21 NA/2018-19/0299,Roads,Completed,NA-THIRUVOTTIYUR,13,842000,"Improvement to Interior BT Road at Udhayasuriyan 1st Street in Division-13,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0302,Roads,Completed,NA-THIRUVOTTIYUR,13,524000,"Improvement to Interior BT Road at Udhayasuriyan 2nd Street in Division-13,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0303,Roads,Completed,NA-THIRUVOTTIYUR,13,346000,"Improvement to Interior BT Road at Mettu Gandhi Street in Division-13, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0304,Roads,Completed,NA-THIRUVOTTIYUR,13,346000,"Improvement to Interior BT Road at Mettu Anna Street in Division-13, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0305,Roads,Completed,NA-THIRUVOTTIYUR,13,346000,"Improvement to Interior BT Road at Mettu Kamarajar Street in Division-13, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0306,Roads,Completed,NA-THIRUVOTTIYUR,13,1240000,"Improvement to Interior BT Road at Iyyapillai Garden 1st street, 1st cross street, 2nd cross street in Division-13, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0308,Roads,Completed,NA-THIRUVOTTIYUR,13,360000,"Improvement to Interior BT Road at Iyyapillai Garden 2nd street in Division-13,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/12999,Buildings,Completed,NA-THIRUVOTTIYUR,13,346000,"REPAIRS AND MAINTANANCE WORK IN AMMA UNAVAGAM AT MGR ROAD DIVISION-13, UNIT-03, ZONE-01.",Own Sources,1,2018-19,2020-21 NA/2018-19/17494,Parks,Completed,P-Parks and Playfields,13,115020,"Plantation and Maintenance of Tree saplings for one year at various street in Division 13, Unit 3, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/1835,Roads,Completed,NA-THIRUVOTTIYUR,13,433000,"Improvement to Interior BT Road at Vinobha colony in Division-13,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1838,Roads,Completed,NA-THIRUVOTTIYUR,13,265000,"Improvement to Interior BT Road at Jaganathapuram Gramani 1st street in Division-13, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1842,Roads,Completed,NA-THIRUVOTTIYUR,13,265000,"Improvement to Interior BT Road at Jaganathapuram Gramani 2nd street in Division-13, Unit-3, Zone-1",Grants,1,2018-19,2019-20 L/2018-19/15775,Electrical,Completed,L-Electrical,14,4086000,"Proposal for commissioning of 54 nos. of 8 mtr Octagonal street lamp posts with G.I Double bracket at Ennore Express Way from Tiruchinnakuppam road jn. to SBI colony in ward-14, Zone-1 Tiruvottriyur [SOR 2017-18]",Own Sources,1,2018-19,2019-20 L/2018-19/8789,Electrical,Completed,L-Electrical,14,464800,"Provision of 10 nos. of 6 mtr G.I lamp post with Single Bracket with 40w LED fittings at TNSCB-Re.con.North Construction of 128 Tenements at Dobikanna Scheme in Division-14, Zone-I [SOR 2017-18]",Deposit Works,1,2018-19,2019-20 NA/2018-19/0489,Roads,Completed,NA-THIRUVOTTIYUR,14,788000,"Improvement to Interior CC Road at P.P.D 3rd Street in Division-14,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0491,Roads,Completed,NA-THIRUVOTTIYUR,14,1422000,"Improvement to Interior CC Road at P.P.D 4th Street in Division-14, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0495,Roads,Completed,NA-THIRUVOTTIYUR,14,535000,"Improvement to Interior CC Road at P.P.D 3rd cross Street in Division-14,Unit-3,Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/0497,Roads,Completed,NA-THIRUVOTTIYUR,14,849000,"Improvement to Interior CC Road at P.P.D 5th cross Street in Division-14, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1716,Roads,Completed,NA-THIRUVOTTIYUR,14,555000,"Improvement to Interior BT Road at Thyagarayapuram 1st street in Division-14, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1717,Roads,Completed,NA-THIRUVOTTIYUR,14,255000,"Improvement to Interior BT Road at Thyagarayapuram 1st cross street in Division-14, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1718,Roads,Completed,NA-THIRUVOTTIYUR,14,412000,"Improvement to Interior BT Road at Thyagarayapuram 6th street in Division-14, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1723,Roads,Completed,NA-THIRUVOTTIYUR,14,234000,"Improvement to Interior BT Road at Thyagarayapuram 2nd cross street in Division-14, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/1725,Roads,Completed,NA-THIRUVOTTIYUR,14,426000,"Improvement to Interior BT Road at Ondikuppam 5th street in Division-14, Unit-3, Zone-1",Grants,1,2018-19,2019-20 NA/2018-19/17495,Parks,Completed,P-Parks and Playfields,14,453101,"Plantation and Maintenance of Tree saplings for one year at various street in Division 14, Unit 3, Zone 1",Own Sources,1,2018-19,2019-20 NA/2018-19/4423,Buildings,Completed,NA-THIRUVOTTIYUR,14,108000,REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE 14 AT A.SADANANDAPURAM IN DN-14 UNIT-3 ZONE-1,Own Sources,1,2018-19,2020-21 NA/2018-19/4426,Buildings,Completed,NA-THIRUVOTTIYUR,14,165000,REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT ONDIKUPPAM IN DN-14 UNIT-3 ZONE-1,Own Sources,1,2018-19,2020-21 NA/2018-19/4430,Buildings,Completed,NA-THIRUVOTTIYUR,14,236000,REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM IN T.H. ROAD AT DN-14 UNIT-3 ZONE-1,Own Sources,1,2018-19,2020-21 NA/2018-19/4435,Buildings,Completed,NA-THIRUVOTTIYUR,14,161000,"Writing Street Name board at Various streets in Division-14, Unit-3, Zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/4437,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,14,194000,"Maintenance to Existing Storm Water Drain at P.P.D Main road & Thyagarayapuram 2nd street in Division-14, Unit-3, Zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/4530,Buildings,Completed,NA-THIRUVOTTIYUR,14,170000,"Repairs and Improvements to Anganwadi Centre No.87 at Thiruchinankuppam in Division-14, Unit-3, Zone-1",Own Sources,1,2018-19,2020-21 NA/2018-19/7503,Road Cut,Completed,NA-THIRUVOTTIYUR,14,678000,"Restoration of Road cut made by CMWSSB at Thiruchinankuppam Main road in Division-14, Unit-3, Zone-1",Deposit Works,1,2018-19,2019-20 L/2018-19/16341,Electrical,Completed,L-Electrical,15,311900,Installation of Grid tied Solar Roof top PV system,SMART CITY - ELECTRICAL,2,2018-19,2019-20 NB/2018-19/11740,Buildings,Completed,NB-MANALI,15,44000,"Repair and Maintenance work for Anganvadi at Chinna echan kuzhi in Dn-15, U-4, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/11759,Buildings,Completed,NB-MANALI,15,47000,"Repair and Maintenance work for Anganvadi at Old nappalayam in Dn-15, U-4, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/12853,Parks,Completed,NB-MANALI,15,1327000,"MAINTENANCE OF PARK AT BLOCK NO 26 CPS - 10 IN DN-15, U-4, Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/12856,Parks,Completed,NB-MANALI,15,247000,"MAINTENANCE OF PARK AT BLOCK NO 29 CPS - 9 IN DN-15, U-4, Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/12857,Parks,Completed,NB-MANALI,15,219000,"MAINTENANCE OF PARK AT BLOCK NO 65 CPS - 8 IN DN-15, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/12859,Parks,Completed,NB-MANALI,15,214000,"Maintenance of Park at Block no 63 CPS- 7 in Dn - 15, U-4 , Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/14062,Parks,Completed,NB-MANALI,15,280000,"MAINTENANCE WORK FOR CPS-6TH PARK AT MANALI NEW TOWN 54TH BLOCK 44TH STREET IN DN-15, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3186,Buildings,Completed,B-Buildings,15,765000,"Repair and Maintenance work for primary health centre at Manali new town 58th block 15th Main road in Dn-15, U-4, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/3192,Buildings,Completed,B-Buildings,15,1630000,"Proposed construction of first floor over the existing Building in Health centre at Manali new town 58th block 15th Main road in Dn-15, U-4, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/3936,Roads,Completed,NB-MANALI,15,611000,"Forming Cement conctret Road at Service link road 1 (New nappalayam) IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3947,Roads,Completed,NB-MANALI,15,1220000,"Forming Cement conctret Road at Service link road 2 (New nappalayam) IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3948,Roads,Completed,NB-MANALI,15,1490000,"Forming Cement conctret Road at Service link road 3 (New nappalayam) IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3950,Roads,Completed,NB-MANALI,15,1009000,"Forming Cement conctret Road at Perumal koil 1st cross street (New nappalayam) IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3952,Roads,Completed,NB-MANALI,15,1190000,"Forming Cement conctret Road at Perumal koil 2nd cross street (New nappalayam) IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3954,Roads,Completed,NB-MANALI,15,1330000,"Forming and Re laying Cement conctret Road at Thulasi nagar 1st street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3961,Roads,Completed,NB-MANALI,15,5820000,"Re laying Cement conctret Road at New nappalayam Gangai amman koil street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3962,Roads,Completed,NB-MANALI,15,3160000,"Relaying Cement conctret Road at Kanni koil main street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3963,Roads,Completed,NB-MANALI,15,2930000,"Relaying Cement conctret Road at Periya Eachanguzhi street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3964,Roads,Completed,NB-MANALI,15,451000,"Forming and laying BT Road at lakshmi nagar 3rd street Part IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3968,Roads,Completed,NB-MANALI,15,1800000,"Forming and laying BT Road at Edayanchavadi 1st cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3969,Roads,Completed,NB-MANALI,15,2230000,"Forming and laying BT Road at Edayanchavadi 2nd cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3970,Roads,Completed,NB-MANALI,15,2230000,"Forming and laying BT Road at Manali new Town 8th Block (Near vinayakar koil) IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3971,Roads,Completed,NB-MANALI,15,435000,"Forming and laying BT Road at Lakshmi nagar 3rd street 1st cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3972,Roads,Completed,NB-MANALI,15,580000,"Forming and laying BT Road at lakshmi nagar 1st street 1st cross street Part IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3973,Roads,Completed,NB-MANALI,15,199000,"Re Laying BT Road at New colony 1st street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/3974,Roads,Completed,NB-MANALI,15,199000,"Re Laying BT Road at New colony 2nd street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/3975,Roads,Completed,NB-MANALI,15,199000,"Re Laying BT Road at New colony 3rd street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3976,Roads,Completed,NB-MANALI,15,359000,"Re Laying BT Road at New colony cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/3977,Roads,Completed,NB-MANALI,15,426000,"Re Laying BT Road at Pooniamman Nagar 1st street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3978,Roads,Completed,NB-MANALI,15,600000,"Re Laying BT Road at Pooniamman Nagar 2nd street IN DN-15,U-4",Own Sources,2,2018-19,2019-20 NB/2018-19/3979,Roads,Completed,NB-MANALI,15,415000,"Re Laying BT Road at Pooniamman Nagar 3rd cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3980,Roads,Completed,NB-MANALI,15,415000,"Re Laying BT Road at Pooniamman Nagar 4th cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3981,Roads,Completed,NB-MANALI,15,539000,"Re Laying BT Road at New nappalayam Gangai amman koil cross stret IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/3982,Roads,Completed,NB-MANALI,15,2820000,"Re Laying BT Road at Laksminagar nagar 1st street and cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/3983,Roads,Completed,NB-MANALI,15,1260000,"Re Laying BT Road at Laksminagar nagar 2nd street and cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/3984,Roads,Completed,NB-MANALI,15,1680000,"Re Laying BT Road at Laksminagar nagar 3rd street and cross street IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/4015,Roads,Completed,NB-MANALI,15,474000,"Re Laying of BT Road at Chinna eachanguzhi salai IN DN-15,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/5591,Buildings,Completed,NB-MANALI,15,102000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT MANALI NEW TOWN IN DN-15,U-4,Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/5593,Buildings,Completed,NB-MANALI,15,96000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM FOR EDAIYANCHAVADI MAIN ROAD IN DN-15,U-4,Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/8746,Buildings,Completed,NB-MANALI,15,520000,"PROVIDING ADDITIONAL IMPROVEMENTS TO COMPOSTING SHED AT MANALI NEW TOWN 150 ROAD (HINDU BURIAL GROUND) IN DN-15, U- 4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/9331,Storm Water Drain,Completed,NB-MANALI,15,69000,"DESILTING OF STORM WATER DRAIN IN VARIOUS STREETS IN DN-15, U-4, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/9332,Storm Water Drain,Completed,NB-MANALI,15,54000,"MINOR REPAIRS TO STORM WATER DRAIN AT VARIOUS STREETS IN DN - 15, U-4, Z-2.",Own Sources,2,2018-19,2018-19 BR/2018-19/5634,Roads,Completed,BR-Bus Route Roads,16,63400,"Road cut restoration (road cut made by BHARTI AIRTEL) at various division in Zone 2 against the challan noBR/2017-18/0011998, BR/2017-18/0012001-dt.28.07.2017 Deposit code 57/0697/2017-18.",Deposit Works,2,2018-19,2019-20 L/2018-19/16342,Electrical,Completed,L-Electrical,16,311900,Installation of Grid tied Solar roof top PV system,SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/16346,Electrical,Completed,L-Electrical,16,462400,Installation of Grid tied Solar roof top PV system,SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/16347,Electrical,Completed,L-Electrical,16,462400,Installation of Grid tied solar roof top PV system,SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/16348,Electrical,Completed,L-Electrical,16,462400,Installation of Grid tied Solar roof top PV system,SMART CITY - ELECTRICAL,2,2018-19,2019-20 NB/2018-19/10838,Buildings,Completed,NB-MANALI,16,33000,"REPAIRS AND MAINTENANCE TO KANNIAMMANPET BURIAL GROUND IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11553,Buildings,Completed,NB-MANALI,16,38000,"REPAIRS AND MAINTENANCE TO ANGANVADI CENTRE FOR KAMARAJAPURAM IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11557,Buildings,Completed,NB-MANALI,16,45000,"REPAIRS AND MAINTENANCE TO ANGANVADI CENTRE FOR ELANTHANOOR OFFICE STREET IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11957,Buildings,Completed,NB-MANALI,16,42000,"REPAIRS AND MAINTENANCE TO UNIT OFFICE FOR ANDARKUPPAM REDHILLS ROAD IN DN-16,U-4,Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/12860,Parks,Completed,NB-MANALI,16,202000,"Maintenance of Park at Block no 90 CPS - 3 in Dn - 16, U-4 , Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/12861,Parks,Completed,NB-MANALI,16,225000,"Maintenance of Park at Block no 134&135 CPS - 1 in Dn - 16, U-4 , Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/12862,Parks,Completed,NB-MANALI,16,196000,"Maintenance of Park at Block no 78 CPS - 5 in Dn - 16, U-4 , Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/12863,Parks,Completed,NB-MANALI,16,240000,"Maintenance of Park at Block no 52 CPS- 4 in Dn - 16, Unit-4 , Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/14027,Parks,Completed,NB-MANALI,16,127000,"Maintenance of Park at Block100&101 CPS- 2 in Dn - 16,Unit-4 ,Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/16511,Buildings,Completed,NB-MANALI,16,184000,"MAINTENANCE OF NEW PARK AT TNHB PHASE-2 BLOCK 3 PARK IN DN-16, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1783,Roads,Completed,NB-MANALI,16,372000,"Forming Cement concrete Road at Andarkuppam perumal koil cross street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1784,Roads,Completed,NB-MANALI,16,2216000,"Relaying Cement concrete Road at Elanthanoor mayeliamman koil street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1785,Roads,Completed,NB-MANALI,16,424000,"Relaying Cement concrete Road at Elanthanoor office street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1786,Roads,Completed,NB-MANALI,16,649000,"Forming of BT Road at MRB Nagar 1st street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1787,Roads,Completed,NB-MANALI,16,649000,"Forming of BT Road at MRB Nagar 2nd street IN DN-16,U-4,Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/1788,Roads,Completed,NB-MANALI,16,428000,"Relaying of BT Road at Irular colony (sadayankuppam) IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1789,Roads,Completed,NB-MANALI,16,230000,"Relaying BT Road at Burma nagar 5th street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1790,Roads,Completed,NB-MANALI,16,191000,"Relaying BT Road at Burma nagar 6th street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1791,Roads,Completed,NB-MANALI,16,153000,"Relaying BT Road at Burma nagar 8th street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1792,Roads,Completed,NB-MANALI,16,513000,"Relaying BT Road at Burma nagar 2nd cross street IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5583,Buildings,Completed,NB-MANALI,16,90000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM FOR ANDARKUPPAM REDHILLS ROAD (NEAR BY CMS )IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5586,Buildings,Completed,NB-MANALI,16,106000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM FOR ANDARKUPPAM REDHILLS ROAD (NEAR BY UNIT OFFICE -4 )IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5587,Buildings,Completed,NB-MANALI,16,110000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM FOR BURMA NAGAR IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/6507,Buildings,Completed,NB-MANALI,16,537000,"MACHINERIES REQUIRED FOR THE COMPOSTING SHEDS AT MRB NAGAR IN DN-16,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7287,Buildings,Completed,NB-MANALI,16,525000,"PROVIDING ADDITIONAL IMPROVEMENTS TO COMPOSTING SHED AT MRB NAGAR IN DN-16, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7752,Storm Water Drain,Completed,NB-MANALI,16,118000,"MINOR REPAIRS TO STORM WATER DRAIN AT VARIOUS STREETS IN DN - 16, U-4, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/9340,Storm Water Drain,Completed,NB-MANALI,16,245000,"Desilting of Storm water drain in various streets in dn-16, u-4, z-2.",Own Sources,2,2018-19,2018-19 L/2018-19/16344,Electrical,Completed,L-Electrical,17,311900,Installation of Grid tied Solar roof top PV system,SMART CITY - ELECTRICAL,2,2018-19,2019-20 NB/2018-19/11441,Buildings,Completed,NB-MANALI,17,16000,"REPAIRS AND MAINTENANCE WORKS TO BURIAL GROUND AT SAMUVEL NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11554,Buildings,Completed,NB-MANALI,17,16000,"REPAIRS AND MAINTENANCE WORKS TO BURIAL GROUND AT VINAYAGAPURAM IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11574,Buildings,Completed,NB-MANALI,17,7900,"REPAIRS AND MAINTENANCE WORKS TO NNMP SHED AT VENUGOPALSAMY STREET IN KOSAPPUR IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11576,Buildings,Completed,NB-MANALI,17,17500,"REPAIRS AND MAINTENANCE WORKS TO DIVISION OFFICE AT VCN SALAI IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11577,Buildings,Completed,NB-MANALI,17,18500,"REPAIRS AND MAINTENANCE WORKS TO COMMUNITY HALL AT MADHAVARAM REDHILLS HIGH ROAD IN VADAPERUMBAKKAM IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11974,Buildings,Completed,NB-MANALI,17,8000,"REPAIRS AND MAINTENANCE WORKS TO NNMP SHED AT CHETTIMEDU AND THEEYAMBAKKAM IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/12864,Parks,Completed,NB-MANALI,17,195000,"Maintenance of Vadaperumpakkam park in Dn - 17, U-4 , Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/12868,Parks,Completed,NB-MANALI,17,267000,"Maintenance of Thirupathy Devasthanam nagar park in Dn - 17, U-4 , Zone - 2",Own Sources,2,2018-19,2019-20 NB/2018-19/16299,Buildings,Completed,NB-MANALI,17,166000,"Improvement works to Corporation Gym at perumal koil street in kosappur in Dn-17, U-4, Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/16454,Buildings,Completed,NB-MANALI,17,119000,"Repair works to composting shed at samuvel nagar and division office in Dn-17, U-4, Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/16549,Buildings,Completed,NB-MANALI,17,105000,"Repair works to gym equiptments and attending plumbing repairs to Corporation Gym at perumal koil street in kosappur in Dn-17, U-4, Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/1762,Roads,Completed,NB-MANALI,17,1467000,"Forming and laying BT Road at Vadaperumbakkam Perumal Nagar in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1763,Roads,Completed,NB-MANALI,17,6771000,"Forming and Laying BT Road at co-operative society and anbu valarmathi nagar in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1765,Roads,Completed,NB-MANALI,17,1692000,"Forming and Laying BT Road at mumtaj nagar in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1766,Roads,Completed,NB-MANALI,17,1241000,"Forming and Laying BT Road at industrial garden in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1767,Roads,Completed,NB-MANALI,17,3949000,"Forming and Laying BT Road at sumangali nagar in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1768,Roads,Completed,NB-MANALI,17,3861000,"Forming and Laying BT Road at annai avenue in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1769,Roads,Completed,NB-MANALI,17,5642000,"Forming and Laying BT Road at parvathipuram in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1770,Roads,Completed,NB-MANALI,17,3949000,"Forming and Laying BT Road at rose nagar in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1771,Roads,Completed,NB-MANALI,17,902000,"Forming and Laying BT Road at Pon Nagar IN DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1772,Roads,Completed,NB-MANALI,17,4514000,"Forming and Laying BT Road at Ariyaloor Road IN DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1773,Roads,Completed,NB-MANALI,17,1128000,"Forming and Laying BT Road at sowbhakia nagar 1st cross street in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1774,Roads,Completed,NB-MANALI,17,1287000,"Forming and Laying BT Road at VS Mani nagar 1st cross street in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1775,Roads,Completed,NB-MANALI,17,2574000,"Forming and Laying BT Road at VS Mani nagar 2nd main road in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1776,Roads,Completed,NB-MANALI,17,3217000,"Forming and Laying BT Road at VS Mani nagar 3rd main road in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1777,Roads,Completed,NB-MANALI,17,1128000,"Forming and Laying BT Road at TG Samy nagar in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/1778,Roads,Completed,NB-MANALI,17,2369000,"Forming and Laying BT Road at thanigachalam nagar 1st cross street in Dn-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1779,Roads,Completed,NB-MANALI,17,291000,"Relaying of BT Road at VS Mani nagar 1st main road in Dn-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1780,Roads,Completed,NB-MANALI,17,1455000,"Relaying of BT Road at gandhi nagar ambedkar nagar link road in Dn-17,U-4,Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/1781,Roads,Completed,NB-MANALI,17,608000,"Relaying of BT Road at TG Samy 2nd and 3rd street in Dn-17,U-4,Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/1782,Roads,Completed,NB-MANALI,17,608000,"Relaying of CC Road at Vinayagapuram in DN-17,U-4,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5594,Buildings,Completed,NB-MANALI,17,99000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT VADAPERUMBAKKAM IN DN-17, U-4, Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/5595,Buildings,Completed,NB-MANALI,17,91000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT KOSAPPUR IN DN-17, U-4, Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/6513,Buildings,Completed,NB-MANALI,17,537000,"Machineries required for Resource Recovery Centre at Sowbhakkia Nagar in div-17, Unit-4, Zone-2",Own Sources,2,2018-19,2019-20 NB/2018-19/6515,Buildings,Completed,NB-MANALI,17,537000,"Providing Machineries required for Resource Recovery Centre at Manali New Town 150 feet Road (Hindu Burial Ground) in div-15, Unit-4, Zone-2",Own Sources,2,2018-19,2019-20 NB/2018-19/7288,Buildings,Completed,NB-MANALI,17,525000,"PROVIDING ADDITIONAL IMPROVEMENTS TO COMPOSTING SHED AT SOWBHAKIA NAGAR (KATHAKUZHI) IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/9329,Storm Water Drain,Completed,NB-MANALI,17,36000,"DESILTING OF STORM WATER DRAIN IN VARIOUS STREETS IN DN-17, U-4, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/9330,Storm Water Drain,Completed,NB-MANALI,17,206000,"Minor Repairs To Storm Water Drain At Various Streets In Dn - 17, U-4, Z-2.",Own Sources,2,2018-19,2018-19 L/2018-19/16313,Electrical,Completed,L-Electrical,18,4754200,"Replacement of 227 Nos of 7 Mtrs Street Lamp Post with Single Straight Bracket, 30 Nos of 7 Mtrs Street Lamp Post with Single Arch Bracket and 3Nos of 9.5 Mtr. Street Lamp Post with 2.7 MTR arch Single Bracket , In Neduchezhiyan st,Thiruvengadam st,Bharathyar st and Various Streets in Ward 18,20 &21 (SOR 2017-18)",Own Sources,2,2018-19,2019-20 L/2018-19/4737,Electrical,Completed,L-Electrical,18,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division - 18 Office at Nedunchezhian Street (Unique Code- 002MLI016) in Div-18, Zone- II(Manali) E.B Account Number : 015.026.75",Loans And Grants,2,2018-19,2019-20 L/2018-19/4742,Electrical,Completed,L-Electrical,18,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP shed at Harikrishnapuram Perumal Koil Street(Unique Code002MLI017) in Div-18, Zone- II (Manali),T.N. E.B Account Number : 015.001.1277 .",Loans And Grants,2,2018-19,2019-20 L/2018-19/4745,Electrical,Completed,L-Electrical,18,86200,"Supply, Installation, Testing & Commissioning of 1Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed at Thiruvalluvar Street 1st Lane (Unique Code002MLI016) in Div-18, Zone- II(Manali), T.N.E.B Account Number : 015.020.727",Loans And Grants,2,2018-19,2019-20 L/2018-19/4747,Electrical,Completed,L-Electrical,18,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed at Thiruvalluvar St, Salaima Nagar(Unique Code 002MLI018) in Div-18, Zone- II(Manali) E.B Account Number :015.019.383",Loans And Grants,2,2018-19,2019-20 L/2018-19/4748,Electrical,Completed,L-Electrical,18,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed at CPCL Layout Amullaivayal (Unique Code 002MLI019)in Div-18, Zone- II(Manali)T.N.E.B Account Number : 015.002.1336 .",Loans And Grants,2,2018-19,2019-20 NB/2018-19/0015,Roads,Completed,NB-MANALI,18,6930000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT AAMULLAIVOYAL VAIKADU LINK ROAD FROM CULVERT TO ANDARKUPPAM REDHILLS LINK ROAD IN DN-18, U-5, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/13243,Parks,Completed,NB-MANALI,18,578000,maintenance for park at neduncheziyan street in div 18 unit 5 zone 2,Own Sources,2,2018-19,2019-20 NB/2018-19/13244,Parks,Completed,NB-MANALI,18,201000,maintenace for park at vimalapuram 2nd street in div 18 unit 5 zone 2,Own Sources,2,2018-19,2019-20 NB/2018-19/13853,Storm Water Drain,Completed,NB-MANALI,18,88000,Repair to existing storm water drain at anbalagan street in div 18 u 5 zone 2,Own Sources,2,2018-19,2019-20 NB/2018-19/15300,Parks,Completed,P-Parks and Playfields,18,1855125,"Plantation of maintenance of tree saplings for one year at various street in dn-18,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/15318,Parks,Completed,P-Parks and Playfields,18,790309,"Plantation of maintenance of tree saplings for one year at various street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/16001,Parks,Completed,NB-MANALI,18,191000,Maintenance park at cpcl 4th street in div 18 unit 5 zone 2,Own Sources,2,2018-19,2019-20 NB/2018-19/16367,Parks,Completed,NB-MANALI,18,550000,"MAINTENANCE PARK ( 6 MONTHS ) FOR CPCL IV MAIN ROAD IN DIVISION 18, UNIT 05 & ZONE 02.",Own Sources,2,2018-19,2019-20 NB/2018-19/1745,Roads,Completed,NB-MANALI,18,399000,"Forming and Laying the Interior road by paver finisher vimalapuram 1st street in dn-18,u-05,zn-02",Own Sources,2,2018-19,2018-19 NB/2018-19/1746,Roads,Completed,NB-MANALI,18,417000,"Forming and Laying the Interior road by paver finisher vimalapuram 2nd street in dn-18,u-05,zn-02",Own Sources,2,2018-19,2018-19 NB/2018-19/1747,Roads,Completed,NB-MANALI,18,576000,"Forming and Laying the Interior road by paver finisher vimalapuram 3rd street in dn-18,u-05,zn-02",Own Sources,2,2018-19,2018-19 NB/2018-19/1748,Roads,Completed,NB-MANALI,18,393000,"Forming and Laying the Interior road by paver finisher kuttiappan street in dn-18,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/1749,Roads,Completed,NB-MANALI,18,460000,"Forming and Laying the Interior road by paver finisher Thiruvengadam street in dn-18,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/5588,Buildings,Completed,NB-MANALI,18,96000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM FOR CPCL LAYOUT 3RD MAIN ROAD IN DN-18,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5589,Buildings,Completed,NB-MANALI,18,90000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM FOR HARIKRISHNAPURAM ANNA MAIN ROAD IN DN-18,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/6510,Buildings,Completed,NB-MANALI,18,537000,"MACHINERIES REQUIRED FOR THE COMPOSTING SHEDS AT CPCL CREMATORIUM IN DN-18,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/8755,Buildings,Completed,NB-MANALI,18,520000,"ADDITIONAL WORK FOR THE CONSTRUCTION OF COMPOSTING SHED INSIDE BURIAL GROUND AT CPCL POLYTECHNICAL BACK SIDE IN DN-18, U- 5, Z-2.",Deposit Works,2,2018-19,2019-20 NB/2018-19/9384,Buildings,Completed,NB-MANALI,18,591000,"Desilting of Storm Water Drain At Various Streets In Dn - 18, U-5, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/9434,Storm Water Drain,Completed,NB-MANALI,18,343000,"Minor repair works for various street of SWD in dn.18,U-5,Z-II",Own Sources,2,2018-19,2018-19 L/2018-19/4804,Electrical,Completed,L-Electrical,19,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 2nd Main road (16th Ceremoney Hall ) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4805,Electrical,Completed,L-Electrical,19,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MMDA 29th street (Anganvadi centre ) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4806,Electrical,Completed,L-Electrical,19,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MMDA 97th street (Anganvadi centre ) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4807,Electrical,Completed,L-Electrical,19,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MMDA 119th street (Anganvadi centre ) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4808,Electrical,Completed,L-Electrical,19,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Arulanandam Nagar Cross street (Anganvadi centre ) in Div-19, Zone - II .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4809,Electrical,Completed,L-Electrical,19,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Athikulam street (Anganvadi centre ) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4810,Electrical,Completed,L-Electrical,19,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ponni amman koil street (Anganvadi centre ) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4811,Electrical,Completed,L-Electrical,19,162000,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ponni amman koil street (Multi Purpose Hall ) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4812,Electrical,Completed,L-Electrical,19,312000,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Kamarajar Salai, Manjambakkam (School) in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4813,Electrical,Completed,L-Electrical,19,463000,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MMDA 4th Cross street , Mathur (AMMA Unavagam) in Div-19, Zone - II .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4814,Electrical,Completed,L-Electrical,19,237000,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MMDA 2nd Cross street , Mathur (Division Office ) in Div-19, Zone - II .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 L/2018-19/4815,Electrical,Completed,L-Electrical,19,463000,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Primary Sschool in MMDA 59th street in Div-19, Zone - II . .",SMART CITY - ELECTRICAL,2,2018-19,2019-20 NB/2018-19/11725,Buildings,Completed,NB-MANALI,19,24000,"Repair works in anganwadi at MMDA 46th street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/11726,Buildings,Completed,NB-MANALI,19,17700,"Repair works in anganwadi at Arulanandam Nagar Cross Street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/11727,Buildings,Completed,NB-MANALI,19,130000,"Repair works in anganwadi at poinniamman koil street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/11728,Buildings,Completed,NB-MANALI,19,23600,"Repair works in anganwadi at mmda 119th street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/11729,Buildings,Completed,NB-MANALI,19,8000,"Repair works in anganwadi at mmda 97th street street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/11730,Buildings,Completed,NB-MANALI,19,12200,"Repair works in anganwadi at MMDA 15TH street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/11731,Buildings,Completed,NB-MANALI,19,37700,"Repair works in CPS school at MMDA 59th street n dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/11732,Buildings,Completed,NB-MANALI,19,11600,"Repair works in CMS school at Manjambakkam in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/13068,Parks,Completed,NB-MANALI,19,1646000,"MAINTENANCE ESTIMATE FOR PARK AT MMDA 2ND MAIN ROAD IN DN-19,U-05,ZN-02",Own Sources,2,2018-19,2019-20 NB/2018-19/13167,Parks,Completed,NB-MANALI,19,230000,"Maintenance estimate for park at Lake view Apartment (kamaraj salai) in Dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/13170,Parks,Completed,NB-MANALI,19,196000,"Maintenance estimate for park at MMDA 34TH Street in Dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/16504,Buildings,Completed,NB-MANALI,19,208000,"Repair and improvements works at Arulanandham Nagar composed yard IN DN-19, UN-5, ZONE-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/5271,Roads,Completed,NB-MANALI,19,2798649,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT MMDA 2ND MAIN ROAD FROM ( KAMARAJAR SALAI TO MMDA 2ND AMIN ROAD TNEB SUB STATION) IN DN-19,U-05,ZN-02 (MANALI)",Deposit Works,2,2018-19,2018-19 NB/2018-19/5614,Buildings,Completed,NB-MANALI,19,58700,"Repair works in amma uanavagam at mmda 4th cross street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/5617,Buildings,Completed,NB-MANALI,19,68000,"Repair works in amma uanavagam at Manjambakkam in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/5736,Roads,Completed,NB-MANALI,19,1050000,"Providind and laying of speed breaker,hot thermos plastic copmound ,reflective pavement marker and signage board Omakulam street,sakthi nagar,MMDA 59th street,MMDA 76TH STREET,MMDA 85TH STREET ,MMDA 1ST MAIN ROAD ,MMDA 2ND MAIN ROAD IN DN-19,U-05,ZN-02",Own Sources,2,2018-19,2020-21 NB/2018-19/6509,Buildings,Completed,NB-MANALI,19,537000,"Providing Machineries required for Resource recovery Centre at Manjambakkam Burial Ground (200 feet road) in div-19, Unit-5, Zone-2",Own Sources,2,2018-19,2019-20 NB/2018-19/7002,Roads,Completed,NB-MANALI,19,983000,"Providind and laying hot thermos plastic copmound ,reflective pavement marker and signage board at MMDA 1st Main Road ,MMDA 2nd Main Road ,MMDA 3rd Main Road ,and MMDA 1st Cross Street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7401,Roads,Completed,NB-MANALI,19,471000,"Work: Laying C.C. Road KARUMARI AMMAN KOIL LANE @ div -19 ,UNIT -5, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/7403,Roads,Completed,NB-MANALI,19,1410000,"Forming and Laying the Interior road by paver finisher at kanakamabal nagar in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7407,Roads,Completed,NB-MANALI,19,793000,"Forming and Laying the Interior road by paver finisher at kanaka ambal nagar 1st cross street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7408,Roads,Completed,NB-MANALI,19,811000,"Forming and Laying the Interior road by paver finisher at Perumal koil street 1st cross in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7409,Roads,Completed,NB-MANALI,19,500000,"Forming and Laying the Interior road by paver finisher at pazhani street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7410,Roads,Completed,NB-MANALI,19,636000,"Forming and Laying the Interior road by paver finisher at Bakthachalu nagar 3rd street cross in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7411,Roads,Completed,NB-MANALI,19,2000000,"Forming and Laying the Interior road by paver finisher at CPCL link road cross street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7412,Roads,Completed,NB-MANALI,19,780000,"Forming and Laying the Interior road by paver finisher at Nehruji nagar cross street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7413,Roads,Completed,NB-MANALI,19,1675000,"Forming and Laying the Interior road by paver finisher at Yegambharam garden in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7414,Roads,Completed,NB-MANALI,19,880000,"Forming and Laying the Interior road by paver finisher at Telecom Nagar 1st Cross Street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7415,Roads,Completed,NB-MANALI,19,1610000,"Forming and Laying the Interior road by paver finisher at Telecom Nagar 2nd Cross Street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2019-20 NB/2018-19/7416,Roads,Completed,NB-MANALI,19,2690000,"Forming and Laying the Interior road by paver finisher at MMDA 3RD CROSS STREET in dn-19,u-05,zn-02",Own Sources,2,2018-19,2018-19 NB/2018-19/7417,Roads,Completed,NB-MANALI,19,1860000,"Forming and Laying the Interior road by paver finisher at MMDA 4th cross street in dn-19,u-05,zn-02",Own Sources,2,2018-19,2018-19 NB/2018-19/7419,Roads,Completed,NB-MANALI,19,343000,"Work: Laying C.C. Road KARUMARI AMMAN KOIL 3RD LANE @ div -19 ,UNIT -5, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/7420,Roads,Completed,NB-MANALI,19,323000,"Work: Laying C.C. Road Perumal koil 1st lane @ div -19 ,UNIT -5, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/7421,Roads,Completed,NB-MANALI,19,628000,"Work: Laying C.C. Road Appollo Armstrong Nagar 2nd Street 1st Lane @ div -19 ,UNIT -5, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/7422,Roads,Completed,NB-MANALI,19,467000,"Work: Laying C.C. Road Appollo Armstrong Nagar 2nd Street @ div -19 ,UNIT -5, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/7423,Roads,Completed,NB-MANALI,19,314000,"Work: Laying C.C. Road Appollo Armstrong Nagar 2nd Street 2nd Lane @ div -19 ,UNIT -5, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/7424,Roads,Completed,NB-MANALI,19,84000,"Laying C.C. Road Nadhiya nagar lane @ div -19 ,UNIT -5, Z-02.",Own Sources,2,2018-19,2019-20 NB/2018-19/8545,Buildings,Completed,NB-MANALI,19,160000,"Repairs works to Night shelter at MMDA 86th street in Dn-19,u-05,zn-02(manali)",Own Sources,2,2018-19,2019-20 NB/2018-19/8718,Buildings,Completed,NB-MANALI,19,576000,"ADDITIONAL WORKS OF RESOURCE RECOVERY CENTRE AT MANJAMBAKKAM IN DN-19,U-05,ZN-2",Own Sources,2,2018-19,2019-20 NB/2018-19/9272,Storm Water Drain,Completed,NB-MANALI,19,941000,"DESILTING OF STORM WATER DRAIN IN VARIOUS STREETS IN DN-19, U-5, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/9274,Storm Water Drain,Completed,NB-MANALI,19,584000,"MINOR REPAIRS TO STORM WATER DRAIN IN VARIOUS STREETS IN DN-19, U-5, Z-2.",Own Sources,2,2018-19,2018-19 B/2018-19/11074,Buildings,Completed,B-Buildings,20,4670000,"Provision of Additional wiring and Electrification work in New Zonal office Building, at Kamarajar salai in Dn-20 Zone-II",Own Sources,2,2018-19,2019-20 B/2018-19/3224,Buildings,Completed,B-Buildings,20,4990000,"Additional works to Zonal office II building at Kamarajar salai, Manali in Dn-20, Zone II",Own Sources,2,2018-19,2020-21 B/2018-19/7858,Buildings,Completed,B-Buildings,20,1540000,Provision of 125 KVA Generator set in New Zonal office Building at Kamarajar salai in Dn-20 Zone-II,Own Sources,2,2018-19,2020-21 D/2018-19/9298,Storm Water Drain,Completed,D-Storm Water Drains,20,72715000,Construction of Storm Water Drain of various roads in Zone - 2 in Package - 2,Grants,2,2018-19,2019-20 L/2018-19/4753,Electrical,Completed,L-Electrical,20,5879600,"Supply, Installation, Testing & Commissioning of 78 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Zonal Office at Kamarajar Salai(Unique Code 002MLI080) in Div-20, Zone- II(Manali) T.N.E.B Account Number : Nil . .",Loans And Grants,2,2018-19,2019-20 L/2018-19/4755,Electrical,Completed,L-Electrical,20,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed at Kalthottam MGR Street(Unique Code 002MLI046) in Div-20, Zone- II(Manali) T.N.E.B Account Number :015.003.955,.",Loans And Grants,2,2018-19,2019-20 L/2018-19/4757,Electrical,Completed,L-Electrical,20,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed at Srinivasa Perumal Koil Street(Unique Code 002MLI043) in Div-20, Zone- II(Manali) T.N.E.B Account Number :015.004.550,",Loans And Grants,2,2018-19,2019-20 L/2018-19/4759,Electrical,Completed,L-Electrical,20,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed at New MGR Nagar Ist Street (Unique Code 002MLI044) in Div-20, Zone- II(Manali)",Loans And Grants,2,2018-19,2019-20 L/2018-19/4761,Electrical,Completed,L-Electrical,20,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office - 20 at New MGR Nagar Ist Street(Unique Code 002MLI042) in Div-20, Zone- II(Manali) .",Loans And Grants,2,2018-19,2019-20 L/2018-19/4762,Electrical,Completed,L-Electrical,20,537600,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Lorry Station at Kamarajar Salai (Unique Code 002MLI048) in Div-20, Zone- II(Manali) .",Loans And Grants,2,2018-19,2019-20 L/2018-19/4764,Electrical,Completed,L-Electrical,20,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Building in Lake View Park MGR Nagar (Unique Code 002MLI047) in Div-20, Zone- II(Manali) ,TNEB Acc No;015-003-1296 .",Loans And Grants,2,2018-19,2019-20 L/2018-19/4765,Electrical,Completed,L-Electrical,20,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed at Chokkammalkulam Street (Unique Code 002MLI045) in Div-20, Zone- II(Manali) TNEB Account Number ;015-003-1397. .",Loans And Grants,2,2018-19,2019-20 NB/2018-19/11629,Buildings,Completed,NB-MANALI,20,46000,"REPAIR & MAINTENANCE WORKS TO LORRY DEPOT AT KAMARAJAR SALAI IN DN20, UNIT;5, ZONE;2.",Own Sources,2,2018-19,2019-20 NB/2018-19/11640,Buildings,Completed,NB-MANALI,20,27800,REPAIR AND MAINTENANCE WORKS TO DIVISION-20 OFFICE BUILDING AT NEW MGR NAGAR 1ST STREET IN DN-20; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/11792,Buildings,Completed,NB-MANALI,20,12300,REPAIR AND MAINTENANCE WORKS TO ANGANWADI AT NEW MGR NAGAR 1ST STREET EXTN. IN DN-20; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/11799,Buildings,Completed,NB-MANALI,20,32000,"REPAIR AND MAINTENANCE WORKS TO ANGANWADI AT SRINIVASA PERUMAL KOIL STREET, CHOCKAMMAL KULAM STREET AND KALTHOTTAM MGR STREET IN DN-20; U-5; Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/11804,Buildings,Completed,NB-MANALI,20,14000,REPAIR AND MAINTENANCE WORKS IN BURIAL GROUND AT KAMARAJAR SALAI AND SRINIVASA PERUMAL KOIL STREET IN DN-20; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/12617,Electrical,Completed,NB-MANALI,20,819403,"Supply and installation of 1no.of 30 KVA DG set for Lorry Depot Zone -1&2at Kamarajar salai ,Manali in Division 20,Zone-2(Manali)",Own Sources,2,2018-19,2019-20 NB/2018-19/13217,Parks,Completed,NB-MANALI,20,257000,"Maintenance Estimate for Park at Lake View (Chinna Mathur Salai) in Dn-20, Unit-05, Zone-2 (Per year)",Own Sources,2,2018-19,2019-20 NB/2018-19/5443,Buildings,Completed,NB-MANALI,20,714000,CONSTRUCTION OF LORRY SERVICE ROOM INSIDE LORRY DEPOT AT KAMARAJAR SALAI IN DN-20; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/5603,Buildings,Completed,NB-MANALI,20,144000,"REPAIR & MAINTENANCE WORKS TO AMMA UNAVAGAM AT KAMARAJAR SALAI NEAR FIRE SERVICE STATION IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5608,Buildings,Completed,NB-MANALI,20,225000,"REPAIR & MAINTENANCE WORKS TO AMMA UNAVAGAM AT KAMARAJAR SALAI NEAR NEW MGR NAGAR 1ST ST. IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/6514,Buildings,Completed,NB-MANALI,20,537000,"Machineries required for Resource Recovery Centre at Burial Ground in Srinivasa Perumal Koil Street in Dn-20, Unit-5, Zone-2",Own Sources,2,2018-19,2019-20 NB/2018-19/7289,Buildings,Completed,NB-MANALI,20,405000,"ADDITIONAL WORK FOR THE CONSTRUCTION OF COMPOSTING SHED INSIDE BURIAL GROUND AT SRINIVASA PERUMAL KOIL STREET IN DN-20, U- 5, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7431,Roads,Completed,NB-MANALI,20,577000,"Relaying BT Road at Chinna Kannu Street IN DN-20,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7432,Roads,Completed,NB-MANALI,20,799000,"Relaying BT Road at New MGR Nagar 1st street IN DN-20,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7433,Roads,Completed,NB-MANALI,20,627000,"Relaying BT Road at New MGR Nagar 1st street Extn IN DN-20,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7448,Roads,Completed,NB-MANALI,20,572000,"Relaying BT Road at Gandhi Street IN DN-21,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7449,Roads,Completed,NB-MANALI,20,638000,"Relaying BT Road at P.Varadharajan Street IN DN-21,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7450,Roads,Completed,NB-MANALI,20,1307000,"Relaying BT Road at Ettiyappan Street (from Anbazhagan Street to EVR Periyar Street) IN DN-21,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/7451,Roads,Completed,NB-MANALI,20,892000,"Relaying BT Road at Dr.Radha Krishnan Street (from VAO Office to EVR Periyar Street) IN DN-21,U-5,Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/9360,Storm Water Drain,Completed,NB-MANALI,20,453000,"Desilting of Storm Water Drains at Various Streets In Dn - 20, U-5, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/9362,Storm Water Drain,Completed,NB-MANALI,20,397000,"Minor Repair works to of Storm Water Drains at Various Streets In Dn - 20, U-5, Z-2.",Own Sources,2,2018-19,2018-19 L/2018-19/4749,Electrical,Completed,L-Electrical,21,838600,"Supply, Installation, Testing & Commissioning of 11 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit Office - 5, at Padasalai Street 1st Lane(Unique Code 002MLI051) in Div-21, Zone- II(Manali) ,T.NE.B Account Number : 015.019.854",Loans And Grants,2,2018-19,2019-20 L/2018-19/4750,Electrical,Completed,L-Electrical,21,1139600,"Supply, Installation, Testing & Commissioning of 15 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Primary Health Centre at Nedunchezhiyan Street (Unique Code 002MLI050) in Div-21, Zone- II(Manali)T.N.E.B Account Number : 015.019.356 .",Loans And Grants,2,2018-19,2019-20 L/2018-19/4751,Electrical,Completed,L-Electrical,21,989100,"Supply, Installation, Testing & Commissioning of 13 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, School at Padasalai Street (Unique Code002MLI049) in Div-21, Zone- II(Manali) T.N.E.B Account Number : 014-035-38",Loans And Grants,2,2018-19,2019-20 L/2018-19/5201,Electrical,Completed,L-Electrical,21,276900,"Provision of Tube lights, Ceiling fan, Exhaust Fan and accessories for CPS & C M S School at Padasalai Street Nedunchezhiyan Street,Kamarajar Salai, Manjambakkam ,and 59th st MMDA Mathur in division-18,19 & 21, Zone-2(Manali)",Own Sources,2,2018-19,2019-20 NB/2018-19/11809,Buildings,Completed,NB-MANALI,21,87000,REPAIR AND MAINTENANCE WORKS TO ZONE-2 OFFICE BUILDING AT PADASALAI STREET IN DN-21; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/11810,Buildings,Completed,NB-MANALI,21,22000,"REPAIR AND MAINTENANCE WORKS TO ANGANWADI AT SANNATHY STREET, THIRUVENGADAM STREET-3A AND 5A IN DN-21; U-5; Z-2",Own Sources,2,2018-19,2019-20 NB/2018-19/11813,Buildings,Completed,NB-MANALI,21,31500,REPAIR AND MAINTENANCE WORKS TO ANGANWADI AT NSK STREET AND DR.AMBEDKAR STREET IN DN-21; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/11815,Buildings,Completed,NB-MANALI,21,12000,REPAIR AND MAINTENANCE WORKS TO URBAN PRIMARY HEALTH CENTER AT NEDUNCHEZHIYAN STREET IN DN-21; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/12142,Buildings,Completed,NB-MANALI,21,23700,REPAIR AND MAINTENANCE WORKS TO CHENNAI PRIMARY SCHOOL AT PADASALAI STREET IN DN-21; U-5; Z-2,Own Sources,2,2018-19,2019-20 NB/2018-19/13218,Parks,Completed,NB-MANALI,21,205000,"Maintenance Estimate for Park at Jalagandamariamman Koil Street in Dn-21, Unit-05, Zone-2 (Per year)",Own Sources,2,2018-19,2019-20 NB/2018-19/15325,Parks,Completed,P-Parks and Playfields,21,114540,"Plantation of Maintenance of Tree Saplings for One year at Various Streets in Dn-21, U-05, Z-02",Own Sources,2,2018-19,2019-20 NB/2018-19/5609,Buildings,Completed,NB-MANALI,21,193000,"REPAIR & MAINTENANCE WORKS TO AMMA UNAVAGAM AT PADASALAI STREET IN DN-21, UNIT-5, ZONE-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5610,Buildings,Completed,NB-MANALI,21,240000,"REPAIR & MAINTENANCE WORKS TO AMMA UNAVAGAM AT JALAGANDAMARIAMMAN KOIL STREET IN DN-21, UNIT-5, ZONE-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/5613,Buildings,Completed,NB-MANALI,21,41000,"REPAIR & MAINTENANCE WORKS TO AMMA UNAVAGAM INSIDE MANALI BUS TERMINUS IN DN-21, UNIT-5, ZONE-2",Own Sources,2,2018-19,2019-20 NB/2018-19/6505,Buildings,Completed,NB-MANALI,21,537000,"Machineries required for Resource Recovery Centre at Sababathy Street in Dn-21, Unit-5, Zone-2",Own Sources,2,2018-19,2019-20 NB/2018-19/7290,Buildings,Completed,NB-MANALI,21,645000,"ADDITIONAL WORK FOR THE CONSTRUCTION OF COMPOSTING SHED AT SABAPATHY STREET IN DN-21, U- 5, Z-2.",Own Sources,2,2018-19,2019-20 NB/2018-19/9401,Storm Water Drain,Completed,NB-MANALI,21,98000,"Minor Repair works to of Storm Water Drains at Various Streets In Dn - 21, U-5, Z-2.",Own Sources,2,2018-19,2018-19 NB/2018-19/9406,Storm Water Drain,Completed,NB-MANALI,21,417000,"Desilting of Storm Water Drains at Various Streets In Dn - 21, U-5, Z-2.",Own Sources,2,2018-19,2018-19 L/2018-19/4594,Electrical,Completed,L-Electrical,22,172400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dn. office, Gandhi 1st street, in Div-22, Zone- III. EB.Account Number: 454-002-2651",Loans And Grants,3,2018-19,2019-20 NC/2018-19/1019,Buildings,Completed,NC-MADHAVARAM,22,459575,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI MIDDLE SCHOOL AT KANNAPPASAMY NAGAR 6TH STREET AND GANDHI MAIN STREET IN DIVISION-22, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10242,Road Cut,Completed,NC-MADHAVARAM,22,1390000,"Improvements to Existing BT Road at Sakthivel Nagar 2nd main road In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10243,Road Cut,Completed,NC-MADHAVARAM,22,1083000,"Improvements to Existing BT Road at Thiruneela Gandar nagar main road In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10244,Road Cut,Completed,NC-MADHAVARAM,22,258000,"Improvements to Existing BT Road at Subash chandira boss 2nd cross street In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10245,Road Cut,Completed,NC-MADHAVARAM,22,622000,"Improvements to Existing BT Road at Subash chandira boss 2nd street In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10246,Road Cut,Completed,NC-MADHAVARAM,22,810000,"Improvements to Existing BT Road at Subash chandira boss 1st main street In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10247,Road Cut,Completed,NC-MADHAVARAM,22,2450000,"Improvements to Existing BT Road at Sakthivel Nagar 1st main road In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10248,Road Cut,Completed,NC-MADHAVARAM,22,2428000,"Improvements to Existing BT Road at Sakthivel Nagar main road In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10249,Road Cut,Completed,NC-MADHAVARAM,22,1015000,"Improvements to Existing BT Road at Mahaveer Garden 2nd main road In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10250,Road Cut,Completed,NC-MADHAVARAM,22,840000,"Improvements to Existing BT Road at Sangaralinganaar 2nd street In Div- 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10251,Road Cut,Completed,NC-MADHAVARAM,22,264000,"Improvements to Existing BT Road at Sangaralinganaar street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10252,Road Cut,Completed,NC-MADHAVARAM,22,1375000,"Improvements to Existing BT Road at Thiru.Vi.Ka street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10253,Road Cut,Completed,NC-MADHAVARAM,22,424000,"Improvements to Existing BT Road at K.S Nagar 27th street Sangeetha Avenue In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10254,Road Cut,Completed,NC-MADHAVARAM,22,890000,"Improvements to Existing BT Road at K.O.C Main street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10255,Road Cut,Completed,NC-MADHAVARAM,22,487000,"Improvements to Existing BT Road at Church street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10256,Road Cut,Completed,NC-MADHAVARAM,22,1425000,"Improvements to Existing BT Road at KS Nagar 27th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10257,Road Cut,Completed,NC-MADHAVARAM,22,900000,"Improvements to Existing BT Road at KS Nagar 26th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10258,Road Cut,Completed,NC-MADHAVARAM,22,530000,"Improvements to Existing BT Road at KS Nagar 25th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10259,Road Cut,Completed,NC-MADHAVARAM,22,2160000,"Improvements to Existing BT Road at KS Nagar 24th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10260,Road Cut,Completed,NC-MADHAVARAM,22,353000,"Improvements to Existing BT Road at KS Nagar 23rd street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10261,Road Cut,Completed,NC-MADHAVARAM,22,938000,"Improvements to Existing BT Road at KS Nagar 22th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10262,Road Cut,Completed,NC-MADHAVARAM,22,468000,"Improvements to Existing BT Road at KS Nagar 21th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10263,Road Cut,Completed,NC-MADHAVARAM,22,2025000,"Improvements to Existing BT Road at KS Nagar 19th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10264,Road Cut,Completed,NC-MADHAVARAM,22,272000,"Improvements to Existing BT Road at KS Nagar 17th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/10265,Road Cut,Completed,NC-MADHAVARAM,22,899000,"Improvements to Existing BT Road at KS Nagar 16th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10266,Road Cut,Completed,NC-MADHAVARAM,22,1269000,"Improvements to Existing BT Road at KS Nagar 15th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/10267,Road Cut,Completed,NC-MADHAVARAM,22,990000,"Improvements to Existing BT Road at KS Nagar 14th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10268,Road Cut,Completed,NC-MADHAVARAM,22,735000,"Improvements to Existing BT Road at KS Nagar 13th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/10269,Road Cut,Completed,NC-MADHAVARAM,22,698000,"Improvements to Existing BT Road at KS Nagar 12th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/10270,Road Cut,Completed,NC-MADHAVARAM,22,675000,"Improvements to Existing BT Road at KS Nagar 11th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10271,Road Cut,Completed,NC-MADHAVARAM,22,686000,"Improvements to Existing BT Road at KS Nagar 10th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10272,Road Cut,Completed,NC-MADHAVARAM,22,899000,"Improvements to Existing BT Road at KS Nagar 9th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10273,Road Cut,Completed,NC-MADHAVARAM,22,850000,"Improvements to Existing BT Road at KS Nagar 8th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10274,Road Cut,Completed,NC-MADHAVARAM,22,750000,"Improvements to Existing BT Road at KS Nagar 7th street In Div- 22,Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10275,Road Cut,Completed,NC-MADHAVARAM,22,510000,"Improvements to Existing BT Road at KS Nagar 6th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10276,Road Cut,Completed,NC-MADHAVARAM,22,540000,"Improvements to Existing BT Road at KS Nagar 5th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10277,Road Cut,Completed,NC-MADHAVARAM,22,872000,"Improvements to Existing BT Road at KS Nagar 4thstreet In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10278,Road Cut,Completed,NC-MADHAVARAM,22,607000,"Improvements to Existing BT Road at KS Nagar 3rd street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10279,Road Cut,Completed,NC-MADHAVARAM,22,1024000,"Improvements to Existing BT Road at KS Nagar Cross 1 In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10280,Road Cut,Completed,NC-MADHAVARAM,22,173000,"Improvements to Existing BT Road at KS Nagar Cross Street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10281,Road Cut,Completed,NC-MADHAVARAM,22,817000,"Improvements to Existing BT Road at KS Nagar 28th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10282,Road Cut,Completed,NC-MADHAVARAM,22,569168,"Improvements to Existing BT Road at KS Nagar 18th street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/10283,Road Cut,Completed,NC-MADHAVARAM,22,2579031,"Improvements to Existing BT Road at Mahaveer Garden main road In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10284,Road Cut,Completed,NC-MADHAVARAM,22,1015000,"Improvements to Existing BT Road at KS nagar cyloan colony road Valluvar street In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10285,Road Cut,Completed,NC-MADHAVARAM,22,1230000,"Improvements to Existing BT Road at K.S Nagar cyloan colony road In Dn 22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/12852,Buildings,Completed,NC-MADHAVARAM,22,318000,"REPAIRS AND IMPROVEMENTS TO NNMP SHED AT KANNAPPASWAMI NAGAR 6TH STREET IN DN-22,U-6,Z-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/12885,Parks,Completed,NC-MADHAVARAM,22,398000,"Maintanance for park at Micro marvel 1st cross street in dn-22,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/12886,Parks,Completed,NC-MADHAVARAM,22,216000,"Maintanance for park macro marvel 2nd cross street in Dn-22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/12887,Parks,Completed,NC-MADHAVARAM,22,205000,"Maintanance for park Gurusanthi nagar in Dn-22, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13406,Buildings,Completed,NC-MADHAVARAM,22,330000,"REPAIRS AND IMPROVEMENTS TO BURIAL GROUND COMPOUND WALL AT KANNADAPALAYAM IN DIV-22, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13621,Buildings,Completed,NC-MADHAVARAM,22,278000,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM AT PERUMAL KOIL STREET IN DIVISION-22, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13622,Buildings,Completed,NC-MADHAVARAM,22,220000,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM AT GNT SERVICE ROAD IN DIVISION-22, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/16297,Buildings,Completed,NC-MADHAVARAM,22,1075000,"Operation and Maintenance of High Quality Treated Drinking Water Plant ( RO/UV Filtration of 2000 litres / Hours Capacity For 1 Year Period at Gandhi Main Road in Division-22, Unit-6, Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/5262,Buildings,Completed,NC-MADHAVARAM,22,1000000,"Operation and Maitenance of High Quality Treated Drinking Water Plant (RO/UV Filtration of 2000 litres / Hours Capacity For 1 year Period at Gandhi Main street in div-22, Unit-6, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/6349,Parks,Completed,NC-MADHAVARAM,22,326000,"PROVIDING BARBED WIRE FENCING WITH GATE AND GATE PILLERS OF OSR PARK LAND-4 AT V.S MANI NAGAR 3rd STREET (WEST SIDE) IN DIVISION-23, UNIT-6,ZONE-3. (LENGTH = 236 M)",Own Sources,3,2018-19,2019-20 NC/2018-19/8504,Storm Water Drain,Completed,NC-MADHAVARAM,22,558040,"Desilting of Storm Water Drain at Various Streets (Grushanthi Nagar Main,1st&2nd Street, Valluvar Street, Mariyammal Nagar Main Street,Thiruneelagandar Nagar Main Street,Sakthivel Nagar Main Road, Sakthivel Nagar 13th to Thiruneelagandar Nagar 6th Street, Thiruneelagandar Nagar 1st,2nd&3rd Street,Mahaveer Gardan 1st & 2nd & Main Road) in Div-22, Unit-6, Zone-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/8509,Storm Water Drain,Completed,NC-MADHAVARAM,22,46490,"Providing Manhole Doors at Grushanthi Nagar Main Street, Mariyammal Nagar Main Street,Thiruneelagandar Nagar Main Street,Sakthivel Nagar Main Road,Mahaveer Gardan 1st & 2nd & Main Road in Div-22, Unit-6, Zone-3.",Own Sources,3,2018-19,2018-19 B/2018-19/12468,Buildings,Completed,B-Buildings,23,4980000,"ADDITIONAL CIVIL WORKS TO THE 65 BEDDED HOSPITAL AT PUZHAL, DN-23, ZONE-3",Own Sources,3,2018-19,2019-20 B/2018-19/12494,Buildings,Completed,B-Buildings,23,5598892,"ADDITIONAL ELECTRICAL WORKS TO THE 65 BEDDED HOSPITAL AT PUZHAL, DN-23, ZONE-3",Own Sources,3,2018-19,2019-20 B/2018-19/12498,Buildings,Completed,B-Buildings,23,3740000,"ADDITIONAL CIVIL WORKS TO THE 65 BEDDED HOSPITAL AT PUZHAL, DN-23, ZONE-3",Own Sources,3,2018-19,2019-20 B/2018-19/4886,Buildings,Completed,B-Buildings,23,3626000,"SUPPLY, INSTALLATION,TESTING & COMMISSIONING OF CENTRALISED MEDICAL GAS SYSTEMS IN URBAN COMMUNITY HEALTH CENTRE AT PUZHAL IN DN-23,ZONE-3.",Own Sources,3,2018-19,2020-21 B/2018-19/4902,Buildings,Completed,B-Buildings,23,5411724,"FIRE PROTECTION SYSTEM AND ONE YEAR MAINTANANCE IN URBAN COMMUNITY HEALTH CENTRE IN DN-23,ZONE-3 PUZHAL.",Own Sources,3,2018-19,2019-20 L/2018-19/4597,Electrical,Completed,L-Electrical,23,172400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dn. office, GNT Road, in Div-23, Zone- III. EB.Account Number: 051-004-2899",Loans And Grants,3,2018-19,2019-20 NC/2018-19/1018,Buildings,Completed,NC-MADHAVARAM,23,367660,"OUTSOURCING PRIVATE LABOURS FOR BOPPILI RAJA Hr.Sec. SCHOOL AT PUZHAL CAMP IN DIVISION-23, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10228,Road Cut,Completed,NC-MADHAVARAM,23,165000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUVALLUVAR CROSS STREET IN DIV? 23,UNIT- 6, ZONE -3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10231,Road Cut,Completed,NC-MADHAVARAM,23,748000,"IMPROVEMENTS TO EXISTING B.T ROAD AT MANNAN STREET IN D.N ? 23, UNIT ? 6, ZONE -3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10286,Road Cut,Completed,NC-MADHAVARAM,23,690000,"IMPROVEMENTS TO EXISTING B.T ROAD AT GANGADARAN PARK STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10288,Road Cut,Completed,NC-MADHAVARAM,23,612000,"IMPROVEMENTS TO EXISTING B.T ROAD AT KALI CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10289,Road Cut,Completed,NC-MADHAVARAM,23,287000,"IMPROVEMENTS TO EXISTING B.T ROAD AT BAJANAI KOIL CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10290,Road Cut,Completed,NC-MADHAVARAM,23,2513000,"IMPROVEMENTS TO EXISTING B.T ROAD AT METTU STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10291,Road Cut,Completed,NC-MADHAVARAM,23,1234000,"IMPROVEMENTS TO EXISTING B.T ROAD AT KALI STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10292,Road Cut,Completed,NC-MADHAVARAM,23,1622000,"IMPROVEMENTS TO EXISTING B.T ROAD AT STEEFEN THIRUMARAN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10293,Road Cut,Completed,NC-MADHAVARAM,23,1050000,"IMPROVEMENTS TO EXISTING B.T ROAD AT KALYAN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10294,Road Cut,Completed,NC-MADHAVARAM,23,568000,"IMPROVEMENTS TO EXISTING B.T ROAD AT VINAYAGAR KOIL STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10295,Road Cut,Completed,NC-MADHAVARAM,23,1485000,"IMPROVEMENTS TO EXISTING B.T ROAD AT M.M. PALLI STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10297,Road Cut,Completed,NC-MADHAVARAM,23,758000,"IMPROVEMENTS TO EXISTING B.T ROAD AT ANNA NAGAR 6TH STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10298,Road Cut,Completed,NC-MADHAVARAM,23,590000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUVALLUVAR 1ST STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10299,Road Cut,Completed,NC-MADHAVARAM,23,469000,"IMPROVEMENTS TO EXISTING B.T ROAD AT PUNITHA ANTHONIYAR 4TH BRANCH STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10300,Road Cut,Completed,NC-MADHAVARAM,23,1227000,"IMPROVEMENTS TO EXISTING B.T ROAD AT NEEDHIDASAN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10301,Road Cut,Completed,NC-MADHAVARAM,23,375000,"IMPROVEMENTS TO EXISTING B.T ROAD AT GANGADARAN 6TH STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10302,Road Cut,Completed,NC-MADHAVARAM,23,722186,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUPUR KUMARAN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10303,Road Cut,Completed,NC-MADHAVARAM,23,265000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUPUR KUMARAN 6TH STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10304,Road Cut,Completed,NC-MADHAVARAM,23,295000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUPUR KUMARAN 5TH CROSS ST. ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10305,Road Cut,Completed,NC-MADHAVARAM,23,307000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUPUR KUMARAN 4TH CROSS ST. ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10306,Road Cut,Completed,NC-MADHAVARAM,23,334000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUPUR KUMARAN 3RD CROSS ST. ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10307,Road Cut,Completed,NC-MADHAVARAM,23,308000,"IMPROVEMENTS TO EXISTING B.T ROAD AT PUNITHA ANTHONIYAR 1ST MAIN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10308,Road Cut,Completed,NC-MADHAVARAM,23,1510000,"IMPROVEMENTS TO EXISTING B.T ROAD AT PUNITHA ANTHONIYAR MAIN ST ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10309,Road Cut,Completed,NC-MADHAVARAM,23,311000,"IMPROVEMENTS TO EXISTING B.T ROAD AT OTRAVADAI MAIN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10310,Road Cut,Completed,NC-MADHAVARAM,23,270000,"IMPROVEMENTS TO EXISTING B.T ROAD AT LAKSHMIAMMAN KOIL MAIN 2ND CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10311,Road Cut,Completed,NC-MADHAVARAM,23,633000,"IMPROVEMENTS TO EXISTING B.T ROAD AT LAKSHMIAMMAN KOIL 1ST STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10312,Road Cut,Completed,NC-MADHAVARAM,23,307000,"IMPROVEMENTS TO EXISTING B.T ROAD AT GANGADARAN 4TH CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10313,Road Cut,Completed,NC-MADHAVARAM,23,2019000,"IMPROVEMENTS TO EXISTING B.T ROAD AT GANGADARAN MAIN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10314,Road Cut,Completed,NC-MADHAVARAM,23,1513000,"IMPROVEMENTS TO EXISTING B.T ROAD AT PUNITHA ANTHONIYAR 3ST BRANCH STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10315,Road Cut,Completed,NC-MADHAVARAM,23,611000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUVALLUVAR 2ND CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10316,Road Cut,Completed,NC-MADHAVARAM,23,373000,"IMPROVEMENTS TO EXISTING B.T ROAD AT METTU STREET 3RD BRANCH ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10317,Road Cut,Completed,NC-MADHAVARAM,23,2181000,"IMPROVEMENTS TO EXISTING B.T ROAD AT ANNA NINAIVU NAGAR EB SALAI ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10318,Road Cut,Completed,NC-MADHAVARAM,23,1296000,"IMPROVEMENTS TO EXISTING B.T ROAD AT ANNA NAGAR 4TH STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10319,Road Cut,Completed,NC-MADHAVARAM,23,545000,"IMPROVEMENTS TO EXISTING B.T ROAD AT GANGADARAN 2ND STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10320,Road Cut,Completed,NC-MADHAVARAM,23,510900,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIURVALLUVAR 2ND MAIN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10321,Road Cut,Completed,NC-MADHAVARAM,23,535000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUVEEDIYAMMAN KOIL STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10322,Road Cut,Completed,NC-MADHAVARAM,23,465800,"IMPROVEMENTS TO EXISTING B.T ROAD AT ST. ANTHONIYAR MAIN 3RD 1ST CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10323,Road Cut,Completed,NC-MADHAVARAM,23,226600,"IMPROVEMENTS TO EXISTING B.T ROAD AT ST. ANTHONIYAR MAIN 3RD 2ND CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10324,Road Cut,Completed,NC-MADHAVARAM,23,820000,"IMPROVEMENTS TO EXISTING B.T ROAD AT LAKSHMIAMMAN KOIL STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10325,Road Cut,Completed,NC-MADHAVARAM,23,420000,"IMPROVEMENTS TO EXISTING B.T ROAD AT LAKSHMIAMMAN KOIL MAIN 5ST CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10326,Road Cut,Completed,NC-MADHAVARAM,23,817000,"IMPROVEMENTS TO EXISTING B.T ROAD AT LAKSHMIAMMAN KOIL MAIN 2ND CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10327,Road Cut,Completed,NC-MADHAVARAM,23,585000,"IMPROVEMENTS TO EXISTING B.T ROAD AT GANGADARAN 3RD STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10328,Road Cut,Completed,NC-MADHAVARAM,23,819000,"IMPROVEMENTS TO EXISTING B.T ROAD AT GANGADARAN 1ST CROSS STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10329,Road Cut,Completed,NC-MADHAVARAM,23,1409000,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIURVALLUVAR MAIN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10330,Road Cut,Completed,NC-MADHAVARAM,23,1099900,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIYAGI CHINNASAMY STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10332,Road Cut,Completed,NC-MADHAVARAM,23,1253900,"IMPROVEMENTS TO EXISTING B.T ROAD AT THALAMUTHU NATARAJAN STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10333,Road Cut,Completed,NC-MADHAVARAM,23,1871000,"IMPROVEMENTS TO EXISTING B.T ROAD AT N.S.K. STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10334,Road Cut,Completed,NC-MADHAVARAM,23,989600,"IMPROVEMENTS TO EXISTING B.T ROAD AT THIRUVALLUVAR STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10377,Road Cut,Completed,NC-MADHAVARAM,23,866000,"IMPROVEMENTS TO EXISTING B.T ROAD AT PUNITHA ANTHONIYAR 2ST CROSS 2RD BRANCH STREET ROAD IN ,DIV- 23,UNIT ? 6, ZONE ? 3.",Own Sources,3,2018-19,2019-20 NC/2018-19/12888,Parks,Completed,NC-MADHAVARAM,23,670000,"Maintanance for park Ambattur Redhills in Dn-23, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/12893,Buildings,Completed,NC-MADHAVARAM,23,238000,"REPAIR AND IMPROVEMENT TO OFFICE BUILDING AND BIO-TOILET AT G.N.T ROAD IN DIV-23, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13623,Buildings,Completed,NC-MADHAVARAM,23,279000,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM AT THIRUVEETHI AMMAN KOIL STREET IN DIVISION-23, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13624,Buildings,Completed,NC-MADHAVARAM,23,22800,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM AT ERATTAIMALAI SRINIVASAN STREET IN DIVISION-23, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/6345,Parks,Completed,NC-MADHAVARAM,23,202000,"PROVIDING BARBED WIRE FENCING WITH GATE AND GATE PILLERS OF OSR PARK LAND-1 AT V.S MANI NAGAR 1st STREET (NORTH SIDE) IN DIVISION-23, UNIT-6,ZONE-3. (LENGTH = 126M)",Own Sources,3,2018-19,2019-20 NC/2018-19/6346,Parks,Completed,NC-MADHAVARAM,23,167000,"PROVIDING BARBED WIRE FENCING WITH GATE AND GATE PILLERS OF OSR PARK LAND-2 AT V.S MANI NAGAR 1st STREET (SOUTH SIDE) IN DIVISION-23, UNIT-6,ZONE-3. (LENGTH = 95 M))",Own Sources,3,2018-19,2019-20 NC/2018-19/6347,Parks,Completed,NC-MADHAVARAM,23,169000,"PROVIDING BARBED WIRE FENCING WITH GATE AND GATE PILLERS OF OSR PARK LAND-3 AT V.S MANI NAGAR 3rd STREET (NORTH SIDE) IN DIVISION-23, UNIT-6,ZONE-3. (LENGTH = 97M)",Own Sources,3,2018-19,2019-20 NC/2018-19/8231,Storm Water Drain,Completed,NC-MADHAVARAM,23,708670,"DESILTING OF STORM WATER DRAINS AT VARIOUS STREETS (STEPHEN THIRUMARAN STREET, STEPHEN THIRUMARAN 1st STREET, THALAMUTHU NATARAJAN STREET, ST.ANTONYIN KOIL MAIN STREET,(SWD), ST.ANTONY KOIL 3rd STREET, GANGADHARAN 1st STREET, ST.ANTONY KOIL MAIN STREET (SIDE DRAIN) IN DN 23, UNIT 6, ZONE 3.",Own Sources,3,2018-19,2018-19 NC/2018-19/8240,Storm Water Drain,Completed,NC-MADHAVARAM,23,46490,"PROVIDING MANHOLE DOORS AT STEPHEN THIRUMARAN STREET, STEPHEN THIRUMARAN 1st STREET, THALAMUTHU NATARAJAN STREET, ST.ANTONYIN KOIL MAIN STREET,(SWD), ST.ANTONY KOIL 3rd STREET, GANGADHARAN 1st STREET, ST.ANTONY KOIL MAIN STREET (SIDE DRAIN) DN 23, UNIT 6, ZONE 3",Own Sources,3,2018-19,2018-19 D/2018-19/9905,Storm Water Drain,Completed,D-Storm Water Drains,24,81590000,"Construction of Storm Water Drai at Iyyan Thiruvalluvar salaiin Zone - 3, Package - 3",Grants,3,2018-19,2020-21 NC/2018-19/10000,Road Cut,Completed,NC-MADHAVARAM,24,620000,"Improvements to Existing BT Road at Bharathidhasan nagar 21th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10001,Road Cut,Completed,NC-MADHAVARAM,24,680000,"Improvements to Existing BT Road at Bharathidhasan nagar 22th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10002,Road Cut,Completed,NC-MADHAVARAM,24,210000,"Improvements to Existing BT Road at Bharathidhasan nagar 23rd cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10003,Road Cut,Completed,NC-MADHAVARAM,24,1070000,"Improvements to Existing BT Road at Bharathidhasan nagar 24th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10004,Road Cut,Completed,NC-MADHAVARAM,24,1230000,"Improvements to Existing BT Road at Bharathidhasan nagar 25th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10005,Road Cut,Completed,NC-MADHAVARAM,24,340000,"Improvements to Existing BT Road at Bharathidhasan nagar 27th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10006,Road Cut,Completed,NC-MADHAVARAM,24,399000,"Improvements to Existing BT Road at Annai indhira nagar periyar street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10007,Road Cut,Completed,NC-MADHAVARAM,24,1800000,"Improvements to Existing BT Road at Annai indhira nagar Kalaignar street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10008,Road Cut,Completed,NC-MADHAVARAM,24,570000,"Improvements to Existing BT Road at Annai indhira nagar pillayar koil street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10009,Road Cut,Completed,NC-MADHAVARAM,24,2980000,"Improvements to Existing BT Road at Annai indhira nagar Nagathamman koil street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10010,Road Cut,Completed,NC-MADHAVARAM,24,370000,"Improvements to Existing BT Road at Annai indhira nagar Nagatheviamman koil street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10011,Road Cut,Completed,NC-MADHAVARAM,24,1290000,"Improvements to Existing BT Road at Annai indhira nagar kamarajar street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10012,Road Cut,Completed,NC-MADHAVARAM,24,650000,"Improvements to Existing BT Road at Annai indhira nagar rajiv gandhi street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10013,Road Cut,Completed,NC-MADHAVARAM,24,2480000,"Improvements to Existing BT Road at Annai indhira nagar bharathiyar street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10014,Road Cut,Completed,NC-MADHAVARAM,24,810000,"Improvements to Existing BT Road at Annai indhira nagar Thiruvalluvar street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10015,Road Cut,Completed,NC-MADHAVARAM,24,930000,"Improvements to Existing BT Road at Annai indhira nagar Nethaji street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10016,Road Cut,Completed,NC-MADHAVARAM,24,2250000,"Improvements to Existing BT Road at Annai indhira nagar Nehru street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10017,Road Cut,Completed,NC-MADHAVARAM,24,1050000,"Improvements to Existing BT Road at Annai indhira nagar Mahathma gandhi street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10018,Road Cut,Completed,NC-MADHAVARAM,24,700000,"Improvements to Existing BT Road at Annai indhira nagar Kambar street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10019,Road Cut,Completed,NC-MADHAVARAM,24,470000,"Improvements to Existing BT Road at Annai indhira nagar Bharathan 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10020,Road Cut,Completed,NC-MADHAVARAM,24,310000,"Improvements to exting BT road at Annai indhira nagar bharathan 2nd Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10021,Road Cut,Completed,NC-MADHAVARAM,24,280000,"Improvements to exting BT road at Annai indhira nagar bharathan 3rd Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10022,Road Cut,Completed,NC-MADHAVARAM,24,710000,"Improvements to exting BT road at Annai indhira nagar bharathan 4th Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10023,Road Cut,Completed,NC-MADHAVARAM,24,420000,"Improvements to exting BT road at Annai indhira nagar bharathan 5th Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10024,Road Cut,Completed,NC-MADHAVARAM,24,340000,"Improvements to exting BT road at Annai indhira nagar Anna street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10025,Road Cut,Completed,NC-MADHAVARAM,24,450000,"Improvements to exting BT road at Annai indhira nagar VOC street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10026,Road Cut,Completed,NC-MADHAVARAM,24,900000,"Improvements to exting BT road at Annai indhira nagar Ambedkar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10027,Road Cut,Completed,NC-MADHAVARAM,24,520000,"Improvements to exting BT road at Annai indhira nagar Ambedkar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10028,Road Cut,Completed,NC-MADHAVARAM,24,1880000,"Improvements to exting BT road at Annai indhira nagar Ratchagan street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10030,Road Cut,Completed,NC-MADHAVARAM,24,860000,"Improvements to exting BT road at Annai indhira nagar 1st main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10031,Road Cut,Completed,NC-MADHAVARAM,24,1170000,"Improvements to exting BT road at Annai indhira nagar Korrai road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10032,Road Cut,Completed,NC-MADHAVARAM,24,3370000,"Improvements to exting BT road at Annai indhira nagar Quarry road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10033,Road Cut,Completed,NC-MADHAVARAM,24,1520000,"Improvements to exting BT road at Annai indhira nagar Venkateshwara street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10034,Road Cut,Completed,NC-MADHAVARAM,24,490000,"Improvements to exting BT road at Annai indhira nagar Quarry road pallam In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10035,Road Cut,Completed,NC-MADHAVARAM,24,1390000,"Improvements to exting BT road at Shanmugapuram perumal koil street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10036,Road Cut,Completed,NC-MADHAVARAM,24,1220000,"Improvements to exting BT road at Shanmugapuram Mariamman koil street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10037,Road Cut,Completed,NC-MADHAVARAM,24,2710000,"Improvements to exting BT road at Jasmine nagar main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10038,Road Cut,Completed,NC-MADHAVARAM,24,780000,"Improvements to exting BT road at Annai nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10039,Road Cut,Completed,NC-MADHAVARAM,24,680000,"Improvements to exting BT road at Annai nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10040,Road Cut,Completed,NC-MADHAVARAM,24,900000,"Improvements to exting BT road at Annai nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10041,Road Cut,Completed,NC-MADHAVARAM,24,602580,"Improvements to exting BT road at Annai nagar 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10042,Road Cut,Completed,NC-MADHAVARAM,24,530000,"Improvements to exting BT road at Annai nagar 5th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10043,Road Cut,Completed,NC-MADHAVARAM,24,1120000,"Improvements to exting BT road at Arul nagar 1st main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10044,Road Cut,Completed,NC-MADHAVARAM,24,1270000,"Improvements to exting BT road at Arul nagar 2nd main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10045,Road Cut,Completed,NC-MADHAVARAM,24,2160000,"Improvements to exting BT road at Arul nagar 1st and 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10047,Road Cut,Completed,NC-MADHAVARAM,24,1560000,"Improvements to exting BT road at Arul nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10048,Road Cut,Completed,NC-MADHAVARAM,24,1200000,"Improvements to exting BT road at Poonga street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10049,Road Cut,Completed,NC-MADHAVARAM,24,4010000,"Improvements to exting BT road at Sivaprakasam nagar kalyana mandapam street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10050,Road Cut,Completed,NC-MADHAVARAM,24,1550000,"Improvements to exting BT road at Sivaprakasam nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10051,Road Cut,Completed,NC-MADHAVARAM,24,510000,"Improvements to exting BT road at Sivaprakasam nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10052,Road Cut,Completed,NC-MADHAVARAM,24,1430000,"Improvements to exting BT road at Sivaprakasam nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10053,Road Cut,Completed,NC-MADHAVARAM,24,670000,"Improvements to exting BT road at Sathyamoorthy nagar main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10054,Road Cut,Completed,NC-MADHAVARAM,24,1540000,"Improvements to exting BT road at Brindhavan tamarai street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10055,Road Cut,Completed,NC-MADHAVARAM,24,2370000,"Improvements to exting BT road at Brindhavan Malli street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10056,Road Cut,Completed,NC-MADHAVARAM,24,1470000,"Improvements to exting BT road at Brindhavan Mullai street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10057,Road Cut,Completed,NC-MADHAVARAM,24,500000,"Improvements to exting BT road at Brindhavan Sevanthi street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10058,Road Cut,Completed,NC-MADHAVARAM,24,317000,"Improvements to exting BT road at Brindhavan Sembaruthi street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10059,Road Cut,Completed,NC-MADHAVARAM,24,1330000,"Improvements to exting BT road at Brindhavan Roja street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10060,Road Cut,Completed,NC-MADHAVARAM,24,1280000,"Improvements to exting BT road at Brindhavan Parijatham street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10061,Road Cut,Completed,NC-MADHAVARAM,24,1650000,"Improvements to exting BT road at Brittania nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10062,Road Cut,Completed,NC-MADHAVARAM,24,1670000,"Improvements to exting BT road at Brittania nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10063,Road Cut,Completed,NC-MADHAVARAM,24,1310000,"Improvements to exting BT road at Brittania nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10064,Road Cut,Completed,NC-MADHAVARAM,24,1690000,"Improvements to exting BT road at Brittania nagar 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10065,Road Cut,Completed,NC-MADHAVARAM,24,2390000,"Improvements to exting BT road at Brittania nagar 5th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10066,Road Cut,Completed,NC-MADHAVARAM,24,2830000,"Improvements to exting BT road at Jeyalakshmi nagar 1st,2nd,3rd and 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10067,Road Cut,Completed,NC-MADHAVARAM,24,3030000,"Improvements to exting BT road at Sakthi nagar 1st,2nd,3rd and 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10068,Road Cut,Completed,NC-MADHAVARAM,24,1770000,"Improvements to exting BT road at Kalaivani nagar In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10069,Road Cut,Completed,NC-MADHAVARAM,24,2740000,"Improvements to exting BT road at Sakthi nagar 5th,6th,7th and 8th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10070,Road Cut,Completed,NC-MADHAVARAM,24,2220000,"Improvements to exting BT road at Vigneshwara gandhi main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10071,Road Cut,Completed,NC-MADHAVARAM,24,289000,"Improvements to exting BT road at Thirupathi nagar In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10072,Road Cut,Completed,NC-MADHAVARAM,24,360000,"Improvements to exting BT road at Purusothamman nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10073,Road Cut,Completed,NC-MADHAVARAM,24,1430000,"Improvements to exting BT road at Purusothamman nagar 2nd,3rd,4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10074,Road Cut,Completed,NC-MADHAVARAM,24,750000,"Improvements to exting BT road at Purusothamman nagar 5th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10075,Road Cut,Completed,NC-MADHAVARAM,24,329000,"Improvements to exting BT road at Purusothamman nagar 6th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10076,Road Cut,Completed,NC-MADHAVARAM,24,1140000,"Improvements to exting BT road at Purusothamman nagar 7th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10077,Road Cut,Completed,NC-MADHAVARAM,24,710000,"Improvements to exting BT road at Ganapathy nagar main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10078,Road Cut,Completed,NC-MADHAVARAM,24,490000,"Improvements to exting BT road at Ganapathy nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10079,Road Cut,Completed,NC-MADHAVARAM,24,520000,"Improvements to exting BT road at Ganapathy nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10080,Road Cut,Completed,NC-MADHAVARAM,24,570000,"Improvements to exting BT road at Ganapathy nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10081,Road Cut,Completed,NC-MADHAVARAM,24,410000,"Improvements to exting BT road at Indhira nagar Extn 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10082,Road Cut,Completed,NC-MADHAVARAM,24,267000,"Improvements to exting BT road at Indhira nagar Extn 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10083,Road Cut,Completed,NC-MADHAVARAM,24,490000,"Improvements to exting BT road at Indhira nagar Extn 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10084,Road Cut,Completed,NC-MADHAVARAM,24,267000,"Improvements to exting BT road at Indhira nagar Extn 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10085,Road Cut,Completed,NC-MADHAVARAM,24,670000,"Improvements to exting BT road at Indhira nagar Extn 5th street(Srinivasa nagar) In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10086,Road Cut,Completed,NC-MADHAVARAM,24,900000,"Improvements to exting BT road at Ramalinga nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10087,Road Cut,Completed,NC-MADHAVARAM,24,600000,"Improvements to exting BT road at Ramalinga nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10088,Road Cut,Completed,NC-MADHAVARAM,24,540000,"Improvements to exting BT road at Ramalingam nagar Extn In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10089,Road Cut,Completed,NC-MADHAVARAM,24,226000,"Improvements to exting BT road at Padma nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10090,Road Cut,Completed,NC-MADHAVARAM,24,450000,"Improvements to exting BT road at Padma nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10091,Road Cut,Completed,NC-MADHAVARAM,24,370000,"Improvements to exting BT road at Padma nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10092,Road Cut,Completed,NC-MADHAVARAM,24,670000,"Improvements to exting BT road at Padma nagar 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10093,Road Cut,Completed,NC-MADHAVARAM,24,640000,"Improvements to exting BT road at Padma nagar 5th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10094,Road Cut,Completed,NC-MADHAVARAM,24,267000,"Improvements to exting BT road at Padma nagar 6th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10095,Road Cut,Completed,NC-MADHAVARAM,24,240000,"Improvements to exting BT road at Padma nagar 7th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10096,Road Cut,Completed,NC-MADHAVARAM,24,319000,"Improvements to exting BT road at Vanavan nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10097,Road Cut,Completed,NC-MADHAVARAM,24,1680000,"Improvements to exting BT road at Vanavan nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10098,Road Cut,Completed,NC-MADHAVARAM,24,339000,"Improvements to exting BT road at Vanavan nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10099,Road Cut,Completed,NC-MADHAVARAM,24,670000,"Improvements to exting BT road at Revathi nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10100,Road Cut,Completed,NC-MADHAVARAM,24,490000,"Improvements to exting BT road at Revathi nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10101,Road Cut,Completed,NC-MADHAVARAM,24,520000,"Improvements to exting BT road at Revathi nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10102,Road Cut,Completed,NC-MADHAVARAM,24,369000,"Improvements to exting BT road at Revathi nagar 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10103,Road Cut,Completed,NC-MADHAVARAM,24,670000,"Improvements to exting BT road at Revathi nagar 5th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10104,Road Cut,Completed,NC-MADHAVARAM,24,1050000,"Improvements to exting BT road at Lakshmi nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10105,Road Cut,Completed,NC-MADHAVARAM,24,640000,"Improvements to exting BT road at Lakshmi nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10106,Road Cut,Completed,NC-MADHAVARAM,24,670000,"Improvements to exting BT road at Lakshmi nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10107,Road Cut,Completed,NC-MADHAVARAM,24,640000,"Improvements to exting BT road at Lakshmanan nagar In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10108,Road Cut,Completed,NC-MADHAVARAM,24,1020000,"Improvements to exting BT road at SBOA Teacers nagar 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10109,Road Cut,Completed,NC-MADHAVARAM,24,1060000,"Improvements to exting BT road at SBOA Teacers nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10110,Road Cut,Completed,NC-MADHAVARAM,24,1410000,"Improvements to exting BT road at SBOA Teacers nagar 3rd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/10111,Road Cut,Completed,NC-MADHAVARAM,24,1460000,"Improvements to exting BT road at Singaravelan nagar main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10112,Road Cut,Completed,NC-MADHAVARAM,24,2010000,"Improvements to exting BT road at Annai therasa street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/1016,Buildings,Completed,NC-MADHAVARAM,24,551489,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI MIDDLE SCHOOL (BALAVINAYAKAR KOIL STREET, MARIAMMAN KOIL STREET,MURUGAMBEDU, BHARATHIDASAN NAGAR 1ST CROSS STREET, BHARATHIDASAN NAGAR 6TH STREET, SCHOOL ROAD AND JP NAGAR) IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/11235,Buildings,Completed,NC-MADHAVARAM,24,102000,"REPAIR AND IMPROVEMENTS OF COMMUNITY HALL AT COMMUNITY HALL STREET IN DIVISION-24, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/11302,Buildings,Completed,NC-MADHAVARAM,24,167000,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM KADAPPA ROAD IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/11304,Buildings,Completed,NC-MADHAVARAM,24,211000,"REPAIRS AND MAINTANANCE OF AMMA UNAVAGAM METTUR LINK ROAD IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13789,Buildings,Completed,NC-MADHAVARAM,24,286000,"SUPPLYING AND LAYING OF INTERLOCKING SLAB AT SCHOOL BUILDINGS (CMS) SURAPET IN DN-24.U-6,Z-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/15178,Parks,Completed,NC-MADHAVARAM,24,226000,"Annual Maintenance for Park at DG Nagar in div-24., Unit-6, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/15379,Buildings,Completed,NC-MADHAVARAM,24,88000,"Providing Grill Gate for Burial Ground at Vijayalakshmi nagar in DN-24,Unit-6,Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/15556,Parks,Completed,NC-MADHAVARAM,24,110000,"FORMATION OF FENCING AROUND THE OSR LAND AT SOORAPATTU (NEAR JASMINE NAGAR) IN DIVISION-24, UNIT-6,ZONE-3. (length = 100 m)",Own Sources,3,2018-19,2019-20 NC/2018-19/2287,Parks,Completed,P-Parks and Playfields,24,6500000,"Plantation and maintenance of tree saplings for one year at various street in Division 22 to 31 & 33, Unit-6,7 & 8.Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2289,Storm Water Drain,Completed,NC-MADHAVARAM,24,55790,"iMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN 24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/7080,Storm Water Drain,Completed,NC-MADHAVARAM,24,177000,"REPAIR AND IMPROVEMENTS OF EXISTING SIDE DRAIN AT THULUKANATHAMMAN KOIL 5TH STREET IN DIVISION - 24, UNIT- 6, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/7148,Parks,Completed,NC-MADHAVARAM,24,420000,"CONSTRUCTION OF COMPOUND WALL AT DG NAGAR PARK IN DN-24, UNIT-6, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/7620,Parks,Completed,NC-MADHAVARAM,24,227000,"FORMATION OF FENCING AROUND THE OSR LAND AT SOORAPATTU IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/7656,Parks,Completed,NC-MADHAVARAM,24,106000,"FORMATION OF FENCING AROUND THE OSR LAND AT PUTHAGARAM IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/7677,Storm Water Drain,Completed,NC-MADHAVARAM,24,203290,"DE- SILTING OF EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DN-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/7717,Storm Water Drain,Completed,NC-MADHAVARAM,24,164000,"REPAIR AND IMPROVEMENTS OF EXISTING SIDE DRAIN AT THULUKANATHAMMAN KOIL STREET (SCHOOL STREET) IN DIVISION - 24, UNIT- 6, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/8594,Buildings,Completed,NC-MADHAVARAM,24,179000,"CONSTRUCTION OF BABY TOILET AND IMPROVEMENTS OF NNMP SHED AT BRINDHAVAN NAGAR IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/9600,Buildings,Completed,NC-MADHAVARAM,24,2010000,"DEMOLITION AND CONSTRUCTION OF OF NNMP SHED AT PERUMAL KOIL STREET IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/9720,Buildings,Completed,NC-MADHAVARAM,24,2010000,"DEMOLITION AND CONSTRUCTION OF OF NNMP SHED AT SHANMUGAPURAM IN DIVISION-24, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/9952,Road Cut,Completed,NC-MADHAVARAM,24,1050000,"Improvements to interior BT road at Bharathidasan Nagar 26th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9957,Road Cut,Completed,NC-MADHAVARAM,24,1310000,"Improvements to Existing BT Road at Senthil nagar 3rd street in Dn-24,Unit-6, Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/9958,Road Cut,Completed,NC-MADHAVARAM,24,1390000,"Improvements to Existing BT Road at Senthil nagar 4th street in Dn-24,Unit-6, Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/9959,Road Cut,Completed,NC-MADHAVARAM,24,1520000,"Improvements to Existing BT Road at Senthil nagar 5th street in Dn-24,Unit-6, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/9960,Road Cut,Completed,NC-MADHAVARAM,24,6890000,"Improvements to Existing BT Road at Vellammal Nagar in Dn-24, Unit-6,Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/9961,Road Cut,Completed,NC-MADHAVARAM,24,291000,"Improvements to Existing BT Road at JP Nagar 1st Cross Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9962,Road Cut,Completed,NC-MADHAVARAM,24,369000,"Improvements to Existing BT Road at JP Nagar 2nd Cross Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9963,Road Cut,Completed,NC-MADHAVARAM,24,600000,"Improvements to Existing BT Road at JP Nagar 3rd Cross Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9965,Road Cut,Completed,NC-MADHAVARAM,24,209000,"Improvements to Existing BT Road at JP Nagar 5th Cross Street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9966,Road Cut,Completed,NC-MADHAVARAM,24,1500000,"Improvements to Existing BT Road at Vijayalakshmi nagar 5th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9967,Road Cut,Completed,NC-MADHAVARAM,24,920000,"Improvements to Existing BT Road at Velmurugan 1st street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9968,Road Cut,Completed,NC-MADHAVARAM,24,930000,"Improvements to Existing BT Road at Vijayalakshmi nagar 4th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9969,Road Cut,Completed,NC-MADHAVARAM,24,1090000,"Improvements to Existing BT Road at Velmurugan nagar 2nd street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9970,Road Cut,Completed,NC-MADHAVARAM,24,1310000,"Improvements to Existing BT Road at Venkata sai nagar 13th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9971,Road Cut,Completed,NC-MADHAVARAM,24,440000,"Improvements to Existing BT Road at Vijayalakshmi nagar 6th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9972,Road Cut,Completed,NC-MADHAVARAM,24,510000,"Improvements to Existing BT Road at Vijayalakshmi nagar 7th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9973,Road Cut,Completed,NC-MADHAVARAM,24,720000,"Improvements to Existing BT Road at Sarathy nagar Extn 11th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9974,Road Cut,Completed,NC-MADHAVARAM,24,890000,"Improvements to Existing BT Road at Sarathy nagar Extn 12th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9975,Road Cut,Completed,NC-MADHAVARAM,24,2080000,"Improvements to Existing BT Road at Sarathy nagar Extn 13th street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9976,Road Cut,Completed,NC-MADHAVARAM,24,1270000,"Improvements to Existing BT Road at Saraswathi nagar 1st main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9977,Road Cut,Completed,NC-MADHAVARAM,24,1120000,"Improvements to Existing BT Road at Saraswathi nagar 2nd main road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9978,Road Cut,Completed,NC-MADHAVARAM,24,2620000,"Improvements to Existing BT Road at Mettur Nagathamman koil street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9979,Road Cut,Completed,NC-MADHAVARAM,24,540000,"Improvements to Existing BT Road at Bharathidhasan nagar 1st circle road In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9980,Road Cut,Completed,NC-MADHAVARAM,24,980000,"Improvements to Existing BT Road at Bharathidhasan nagar 1st cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9981,Road Cut,Completed,NC-MADHAVARAM,24,1330000,"Improvements to Existing BT Road at Bharathidhasan nagar 2nd cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9982,Road Cut,Completed,NC-MADHAVARAM,24,970000,"Improvements to Existing BT Road at Bharathidhasan nagar 3rd cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9983,Road Cut,Completed,NC-MADHAVARAM,24,1870000,"Improvements to Existing BT Road at Bharathidhasan nagar 4th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9984,Road Cut,Completed,NC-MADHAVARAM,24,489110,"Improvements to Existing BT Road at Bharathidhasan nagar 5th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9985,Road Cut,Completed,NC-MADHAVARAM,24,1090000,"Improvements to Existing BT Road at Bharathidhasan nagar 6th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9986,Road Cut,Completed,NC-MADHAVARAM,24,750000,"Improvements to Existing BT Road at Bharathidhasan nagar 7th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9987,Road Cut,Completed,NC-MADHAVARAM,24,1310000,"Improvements to Existing BT Road at Bharathidhasan nagar 8th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9988,Road Cut,Completed,NC-MADHAVARAM,24,1120000,"Improvements to Existing BT Road at Bharathidhasan nagar 9th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9989,Road Cut,Completed,NC-MADHAVARAM,24,470000,"Improvements to Existing BT Road at Bharathidhasan nagar 10th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9990,Road Cut,Completed,NC-MADHAVARAM,24,440000,"Improvements to Existing BT Road at Bharathidhasan nagar 11th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9991,Road Cut,Completed,NC-MADHAVARAM,24,1090000,"Improvements to Existing BT Road at Bharathidhasan nagar 12th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9992,Road Cut,Completed,NC-MADHAVARAM,24,1870000,"Improvements to Existing BT Road at Bharathidhasan nagar 13th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9993,Road Cut,Completed,NC-MADHAVARAM,24,670000,"Improvements to Existing BT Road at Bharathidhasan nagar 14th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9994,Road Cut,Completed,NC-MADHAVARAM,24,560000,"Improvements to Existing BT Road at Bharathidhasan nagar 15th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 NC/2018-19/9995,Road Cut,Completed,NC-MADHAVARAM,24,3910000,"Improvements to Existing BT Road at Bharathidhasan nagar 16th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9996,Road Cut,Completed,NC-MADHAVARAM,24,1010000,"Improvements to Existing BT Road at Bharathidhasan nagar 17th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9997,Road Cut,Completed,NC-MADHAVARAM,24,440000,"Improvements to Existing BT Road at Bharathidhasan nagar 18th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9998,Road Cut,Completed,NC-MADHAVARAM,24,1090000,"Improvements to Existing BT Road at Bharathidhasan nagar 19th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/9999,Road Cut,Completed,NC-MADHAVARAM,24,780000,"Improvements to Existing BT Road at Bharathidhasan nagar 20th cross street In Dn 24, Unit-6,Zone-3",Own Sources,3,2018-19,2020-21 BR/2018-19/18204,Road Cut,Completed,BR-Bus Route Roads,25,600000,RESTORATION OF OFC ROAD CUT MADE BY M/S BHARATHI AIRTEL AT VARIOUS STREET IN DIV-25 UNIT-6 ZONE-3 (DEPOSIT CODE: 57/0096/2018-19),Deposit Works,3,2018-19,2019-20 BR/2018-19/18205,Road Cut,Completed,BR-Bus Route Roads,25,600000,RESTORATION OF OFC ROAD CUT MADE BY M/S BHARATHI AIRTEL AT VARIOUS STREET IN DIV-25 UNIT-6 ZONE-3 (DEPOSIT CODE: 57/0096/2018-19),Deposit Works,3,2018-19,2019-20 D/2018-19/9906,Storm Water Drain,Completed,D-Storm Water Drains,25,57965000,"Construction of Storm Water Drain at Veeraragavalu1 st, 2 nd and 2 other streetsin Zone - 3, Package - 4",Grants,3,2018-19,2019-20 L/2018-19/4599,Electrical,Completed,L-Electrical,25,172400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dn. office, EMS Street, in Div-25, Zone- III. EB.Account Number: 051-002-3545",Loans And Grants,3,2018-19,2019-20 L/2018-19/7651,Electrical,Completed,L-Electrical,25,514800,Removal and refixing of 68 nos of 8mtr lamp post at both the sides of service road (SWD Construction work location North side and South side) in dn.25 of zone.3,Own Sources,3,2018-19,2019-20 NC/2018-19/10153,Road Cut,Completed,NC-MADHAVARAM,25,3420000,"Improvements to exting BT road at Bajanai koil street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10154,Road Cut,Completed,NC-MADHAVARAM,25,1130000,"Improvements to exting BT road at Gangai amman koil street and Gangai amman koil cross street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10155,Road Cut,Completed,NC-MADHAVARAM,25,313000,"Improvements to exting BT road at Bajanai koil cross street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10157,Road Cut,Completed,NC-MADHAVARAM,25,1720000,"Improvements to exting BT road at Kannagi Street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10158,Road Cut,Completed,NC-MADHAVARAM,25,1520000,"Improvements to exting BT road at Gandhi Street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10159,Road Cut,Completed,NC-MADHAVARAM,25,3410000,"Improvements to exting BT road at Dr.Ambedkar Street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10160,Road Cut,Completed,NC-MADHAVARAM,25,940000,"Improvements to exting BT road at Brittania nagar In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10161,Road Cut,Completed,NC-MADHAVARAM,25,1750000,"Improvements to exting BT road at Sathyamoorthy nagar 1st,2nd,3rd street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10162,Road Cut,Completed,NC-MADHAVARAM,25,2940000,"Improvements to exting BT road at Sathyamoorthy nagar 4th and 5th street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10163,Road Cut,Completed,NC-MADHAVARAM,25,1910000,"Improvements to exting BT road at Birla avenue main and 1st street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10164,Road Cut,Completed,NC-MADHAVARAM,25,550000,"Improvements to exting BT road at Birla avenue 1st street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10165,Road Cut,Completed,NC-MADHAVARAM,25,850000,"Improvements to exting BT road at VMK nagar 1st street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10166,Road Cut,Completed,NC-MADHAVARAM,25,1670000,"Improvements to exting BT road at VMK nagar 2nd street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10167,Road Cut,Completed,NC-MADHAVARAM,25,2240000,"Improvements to exting BT road at VMK nagar 3rd and 3rd cross street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10168,Road Cut,Completed,NC-MADHAVARAM,25,1660000,"Improvements to exting BT road at Thiru vi ka street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10169,Road Cut,Completed,NC-MADHAVARAM,25,1320000,"Improvements to exting BT road at Thirumalai Srinivasa nagar main street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/1017,Buildings,Completed,NC-MADHAVARAM,25,275745,"OUTSOURCING PRIVATE LABOURS FOR GOVT HIGH SCHOOL AT KATHIRVEDU IN DIVISION -25, UNIT-6, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10170,Road Cut,Completed,NC-MADHAVARAM,25,990000,"Improvements to exting BT road at Thirumalai Srinivasa nagar 1st,2nd,3rd street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10171,Road Cut,Completed,NC-MADHAVARAM,25,2060000,"Improvements to exting BT road at KVR nagar main 1st street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10172,Road Cut,Completed,NC-MADHAVARAM,25,1710000,"Improvements to exting BT road at Kattida thozhilalar nagar In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10173,Road Cut,Completed,NC-MADHAVARAM,25,1750000,"Improvements to exting BT road at Murthy nagar main street In Dn 25, Unit-6,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/10174,Road Cut,Completed,NC-MADHAVARAM,25,1500000,"Improvements to extisting BT road at Murthy nagar 1st and 2nd street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10175,Road Cut,Completed,NC-MADHAVARAM,25,1250000,"Improvements to extisting BT road at Murthy nagar 3rd street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10176,Road Cut,Completed,NC-MADHAVARAM,25,1680000,"Improvements to extisting BT road at Mahalakshmi nagar 3rd and 4th street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10177,Road Cut,Completed,NC-MADHAVARAM,25,880000,"Improvements to extisting BT road at Parimalam nagar in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10178,Road Cut,Completed,NC-MADHAVARAM,25,910000,"Improvements to extisting BT road at Rajiv gandhi street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10179,Road Cut,Completed,NC-MADHAVARAM,25,840000,"Improvements to extisting BT road at Balaji nagar 1st street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10180,Road Cut,Completed,NC-MADHAVARAM,25,610000,"Improvements to extisting BT road at Balaji nagar 2nd street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10181,Road Cut,Completed,NC-MADHAVARAM,25,3790000,"Improvements to extisting BT road at Balaji nagar 3rd and 4th street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10182,Road Cut,Completed,NC-MADHAVARAM,25,1840000,"Improvements to extisting BT road at Jai maruthi nagar main road in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10183,Road Cut,Completed,NC-MADHAVARAM,25,1440000,"Improvements to extisting BT road at Jai maruthi nagar 1st and 3rd street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10184,Road Cut,Completed,NC-MADHAVARAM,25,1190000,"Improvements to extisting BT road at Jai maruthi nagar 2nd street in Dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10407,Storm Water Drain,Completed,NC-MADHAVARAM,25,92980,"IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VARIUOS STREET IN DN-25, UNIT-6,ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/12599,Storm Water Drain,Completed,NC-MADHAVARAM,25,1741000,"Construction of storm water drain of size 600x750mm at Collector Nagar 2nd cross street in Dn-25 , Unit-6, Zone-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/12816,Buildings,Completed,NC-MADHAVARAM,25,214000,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM AT EMS STREET IN DN-25,UNIT-6,ZONE-3",Own Sources,3,2018-19,2020-21 NC/2018-19/12840,Parks,Completed,NC-MADHAVARAM,25,194000,"REPAIR AND MAINTANANCE AT PADMAVATHY NAGAR 5TH STREET PARK IN DN-25,UNIT-6, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/12846,Buildings,Completed,NC-MADHAVARAM,25,472000,"REPAIRS AND IMPROVEMENTS OF NNMP SHED AT ANNA STREET(C.NO:33603140212) IN DIVISION-25, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/12883,Parks,Completed,NC-MADHAVARAM,25,215000,"Maintanance for park at Collector nagar main road in dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/12884,Parks,Completed,NC-MADHAVARAM,25,224000,"Maintanance for park at Padmavathy nagar in dn-25,unit-6,zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13278,Parks,Completed,NC-MADHAVARAM,25,559000,"Maintenance for Park at Srinivasa Nagar Main road park in div-25., Unit-6, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13515,Buildings,Completed,NC-MADHAVARAM,25,38000,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM AT PADMAVATHY NAGAR IN DIVISION-25, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13517,Buildings,Completed,NC-MADHAVARAM,25,25600,"REPAIRS AND IMPROVEMENTS OF AMMA UNAVAGAM AT MGR NAGAR IN DIVISION-25, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13860,Buildings,Completed,NC-MADHAVARAM,25,86000,"REPAIR AND MAINTANANCE TO BURIAL GROUND AT BHARATHIYAR STREET IN DN-25, UNIT-6,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1973,Parks,Completed,NC-MADHAVARAM,25,4000000,"Improvements of park at Collector Nagar Main Road in Dn-25, Unit-6, Zone-03",Own Sources,3,2018-19,2018-19 NC/2018-19/7146,Storm Water Drain,Completed,NC-MADHAVARAM,25,219060,"DESILTING TO EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DIVISION - 25, UNIT- 6, ZONE-3.",Own Sources,3,2018-19,2018-19 L/2018-19/4589,Electrical,Completed,L-Electrical,26,172400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dn. office, Thanikasalam nagar F Block, in 26 Div, Zone- III. EB.Account Number: 073.010.1926",Loans And Grants,3,2018-19,2019-20 L/2018-19/7038,Electrical,Completed,L-Electrical,26,784300,Erection of 26 nos of 7mtr old Lamp post with 1m long single straight bracket at PRH Road in Div-26 of Zone-III (Madhavaram),Own Sources,3,2018-19,2018-19 NC/2018-19/10409,Roads,Completed,NC-MADHAVARAM,26,780440,"DESILTING OF SIDE DRAIN AT VARIOUS STREET IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/11476,Roads,Completed,NC-MADHAVARAM,26,1404000,"Attending patchwork with WMM at CMDA Truck Terminal Main Road in Division-26, Unit-7, Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/11480,Roads,Completed,NC-MADHAVARAM,26,999000,"IMPROVEMENT WORKS TO SIDE DRAIN AT CMDA TRUCK TERMINAL IN DIVISION-26, UNIT-7, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/13065,Buildings,Completed,NC-MADHAVARAM,26,1163000,"REPAIRS AND IMPROVEMENT WORKS TO EXISTING OLD OFFICE BUILDING IN ZONAL OFFICE CAMPUS IN DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13277,Parks,Completed,NC-MADHAVARAM,26,352000,"Annual Maintenance for Park at Secretariate colony park in div-26., Unit-7, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13557,Buildings,Completed,NC-MADHAVARAM,26,1759000,"CONSTRUCTION OF RRC COMPOUND WALL AT CMDA TRUCK TERMINAL COMPLEX IN DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13563,Buildings,Completed,NC-MADHAVARAM,26,680000,"CONSTRUCTION OF TOILET AND PROVIDING WATER SUPPLY ARRANGEMENTS AT CMDA TRUCK TERMINAL COMPLEX IN DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13974,Buildings,Completed,NC-MADHAVARAM,26,91000,"Repairs and Maintenance of Amma Unavagam At Thanigachalam Nagar F Block In Division-26,u-7,z-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13977,Buildings,Completed,NC-MADHAVARAM,26,104000,"Repairs and Maintenance of Amma Unavagam At Vinayagapuram in Division-26,U-7,Z-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13981,Buildings,Completed,NC-MADHAVARAM,26,164000,"Repairs and Maintenance of Amma Unavagam At CMDA Truck Terminal in Division-26,U-7,Z-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/15533,Buildings,Completed,NC-MADHAVARAM,26,4984000,"PROVIDING FOOTPATH AND OTHER IMPROVEMENT WORKS TO OMAKULAM POND IN DIVISION-26 UNIT-7, ZONE-3",Own Sources,3,2018-19,2020-21 NC/2018-19/16777,Storm Water Drain,Completed,NC-MADHAVARAM,26,91000,"PROVIDING RAIN WATER DISPOSAL PIPE AT VARIOUS STREET IN DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/16778,Buildings,Completed,NC-MADHAVARAM,26,106000,"REPAIRS AND IMPROVEMENT WORKS AT ZONAL OFFICE-III IN DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/16780,Buildings,Completed,NC-MADHAVARAM,26,187000,"REPAIRS TO SIDE DRAIN AT CMDA TRUCK TERMINAL ( DAMAGED PORTION) IN DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/17121,Buildings,Completed,NC-MADHAVARAM,26,93000,"REPAIRS AND IMPROVEMENT WORKS AT DIVISION OFFICE IN DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/3044,Roads,Completed,NC-MADHAVARAM,26,694000,"Improvements of BT Road at Ponnusamy Nagar in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3045,Roads,Completed,NC-MADHAVARAM,26,345000,"Relaying of BT Road at Devaki nagar 3rd Street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3047,Roads,Completed,NC-MADHAVARAM,26,172000,"Improvements of BT Road at Thirumalai Nagar Extn.3rd cross street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3048,Roads,Completed,NC-MADHAVARAM,26,172000,"Improvements of BT Road at Thirumalai Nagar Extn.6th cross street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3051,Roads,Completed,NC-MADHAVARAM,26,126000,"Improvements of BT Road at Thirumalai Nagar Extn.4th cross street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3054,Roads,Completed,NC-MADHAVARAM,26,661000,"Improvements of BT Road at Simmam Avenue in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3055,Roads,Completed,NC-MADHAVARAM,26,303660,"Improvements of BT Road at Vajravel Nagar main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3058,Roads,Completed,NC-MADHAVARAM,26,211000,"Improvements of BT Road at Thirumalai Nagar Extn 2nd cross street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3059,Roads,Completed,NC-MADHAVARAM,26,1204000,"Improvements of BT Road at Thirumalai Nagar Extn 1st main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3061,Roads,Completed,NC-MADHAVARAM,26,291000,"Improvements of BT Road at Thirumalai Nagar 1st cross street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3064,Roads,Completed,NC-MADHAVARAM,26,626000,"Improvements of BT Road at Thirumalai Nagar west main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3066,Roads,Completed,NC-MADHAVARAM,26,736000,"Improvements of BT Road at Thirumalai Nagar 4th main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3068,Roads,Completed,NC-MADHAVARAM,26,611000,"Improvements of BT Road at Vajiravel 2nd street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3069,Roads,Completed,NC-MADHAVARAM,26,608000,"Improvements of BT Road at Vajiravel 3rd street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3071,Roads,Completed,NC-MADHAVARAM,26,1151000,"Improvements of BT Road at Gilban nagar part in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3072,Roads,Completed,NC-MADHAVARAM,26,1060000,"Improvements of BT Road at Sasthri nagar 2nd main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3074,Roads,Completed,NC-MADHAVARAM,26,1149000,"Improvements of BT Road at Sasthri nagar anex 2 in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3075,Roads,Completed,NC-MADHAVARAM,26,476000,"improvements of BT Road at Thanikachalam nagar west F block 6th street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3078,Roads,Completed,NC-MADHAVARAM,26,301000,"improvements of BT Road at Thanikachalam nagar west F block 7th street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3079,Roads,Completed,NC-MADHAVARAM,26,661000,"Improvements of BT Road at Lakshmi Nagar 2nd Street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3080,Roads,Completed,NC-MADHAVARAM,26,316000,"Improvements of BT Road at Shanmuga Sundaram nagar 3rd Street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3081,Roads,Completed,NC-MADHAVARAM,26,408000,"Improvements of BT Road at Subash Nagar Main Road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3082,Roads,Completed,NC-MADHAVARAM,26,240000,"Improvements of BT Road at Kamachi Nagar in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3083,Roads,Completed,NC-MADHAVARAM,26,1291000,"Improvements of BT Road at Thirumalai Nagar Extn 2nd main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3084,Roads,Completed,NC-MADHAVARAM,26,210000,"Improvements of BT Road at Thirumalai Nagar East main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3085,Roads,Completed,NC-MADHAVARAM,26,1015000,"Improvements of BT Road at Thirumalai Nagar 2nd main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3086,Roads,Completed,NC-MADHAVARAM,26,995000,"Improvements of BT Road at Thirumalai Nagar 3rd main road in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3087,Roads,Completed,NC-MADHAVARAM,26,631000,"Improvements to BT Road at Vajiravel 4th street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3088,Roads,Completed,NC-MADHAVARAM,26,579000,", New formation of BT Road at RDS Avenue in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3091,Roads,Completed,NC-MADHAVARAM,26,466000,"Relaying of BT Road at Kanchi Nagar lake view street in division-26,Unit-7,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/5394,Buildings,Completed,NC-MADHAVARAM,26,1243000,"MINOR REPAIRS AND IMPROVEMENT WORKS TO UPHC AT SWAMY NAGAR IN DN-26, UNIT-7, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/5400,Buildings,Completed,NC-MADHAVARAM,26,1491000,"CONSTRUCTON OF ADDITIONAL STORE ROOM AT 2ND FLOOR OF ZONAL OFFICE-3 BUILDING AND MINOR REPAIR WORKS TO ZONAL OFFICE AT THATTANKULAM ROAD IN DIVISION-26,UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/6430,Buildings,Completed,NC-MADHAVARAM,26,692000,"PROVIDING RAINWATER DISPOSAL PIPELINE AT OMAKULAM POND IN DIVISION-26,UNIT-7,ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/7281,Roads,Completed,NC-MADHAVARAM,26,736000,"PROVIDING OPEN SIDE DRAIN AT THATTANKULAM ROAD IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/8597,Buildings,Completed,NC-MADHAVARAM,26,886000,"Reconstruction of Dismantling existing damaged Compound wall at Vinayagapuram Burial Ground Road in DN-26, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/8848,Electrical,Completed,NC-MADHAVARAM,26,756300,"Supply and Erection of 1 no of LT Panel Board with 7 nos of 3 phase distribution board in zonal office, division-26, zone-III",Own Sources,3,2018-19,2019-20 NC/2018-19/9936,Buildings,Completed,NC-MADHAVARAM,26,79000,"Dismantling existing damaged condition of community toilet at CMDA Truck Terminal in Div-26, Unit-7, Zone-3",Own Sources,3,2018-19,2020-21 Q/2018-19/10952,Buildings,Completed,Q-Solid Waste Management,26,8400000,"Construction of Domestic Hazardous waste collection centres for package 1 as per DFR in Zone-1,2,3 &7",Grants,3,2018-19,2021-22 BR/2018-19/18246,Road Cut,Completed,BR-Bus Route Roads,27,426000,Restoration of OFC road cut made by M/s Bharathi Airtel at various interior roads in Div-27 Unit- 7 Zone-3(Deposit code-57/0167/2018-19),Deposit Works,3,2018-19,2019-20 BR/2018-19/5303,Roads,Completed,BR-Bus Route Roads,27,499000,Providing speed breakers at kumarappa puram main road (various location) in Zone 3.,Own Sources,3,2018-19,2019-20 L/2018-19/4593,Electrical,Completed,L-Electrical,27,172400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dn. office, Perumalkoil street in Div. 27, Zone- III. EB Account Number: 074.001.358",Loans And Grants,3,2018-19,2019-20 NC/2018-19/10443,Storm Water Drain,Completed,NC-MADHAVARAM,27,159780,DESILTING OF SIDE DRAIN AT VARIOUS STREET IN DIV 27 UNIT -7 ZONE -3,Own Sources,3,2018-19,2018-19 NC/2018-19/13222,Buildings,Completed,NC-MADHAVARAM,27,763000,"REPAIRS AND MAINTENANCE OF EXISTING GASIFIER CREMATORIUM AT MANDAVELI (TELUGU COLONY)BURIAL GROUND UN DIVISION 27 UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13383,Buildings,Completed,NC-MADHAVARAM,27,302000,"REPAIRS AND MAINTENANCE OF AMMA UNAVAGAM AT PERUMAL KOIL STREET IN DIVISION-27,UNIT-7,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/16776,Roads,Completed,NC-MADHAVARAM,27,96000,"IMPROVEMENTS TO SIDE DRAIN AT MANDAVELI STREET AND EDAIMA NAGAR PERUMAL KOIL STREET IN DN-27, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2987,Roads,Completed,NC-MADHAVARAM,27,950000,"IMPROVEMENTS TO EXTING BT ROAD AT SRINIVASA PERUMAL KOIL STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2989,Roads,Completed,NC-MADHAVARAM,27,274000,"IMPROVEMENTS TO EXTING BT ROAD AT PERUMAL KOIL STREET( EAST) IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2991,Roads,Completed,NC-MADHAVARAM,27,242000,"IMPROVEMENTS TO EXTING BT ROAD AT MGR STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2992,Roads,Completed,NC-MADHAVARAM,27,1017000,"IMPROVEMENTS TO EXTING BT ROAD AT KANNADASAN STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2994,Roads,Completed,NC-MADHAVARAM,27,2634000,"IMPROVEMENTS TO EXTING BT ROAD AT ASSISI NAGAR LINK ROAD IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2995,Roads,Completed,NC-MADHAVARAM,27,475000,"IMPROVEMENTS TO EXTING BT ROAD AT RAMACHANDRA NAGAR DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2996,Roads,Completed,NC-MADHAVARAM,27,1151000,"IMPROVEMENTS TO EXTING BT ROAD AT SUNDARAM NAGARIN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2997,Roads,Completed,NC-MADHAVARAM,27,398000,"IMPROVEMENTS TO EXTING BT ROAD AT VASANTHAM AVENUE IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2998,Roads,Completed,NC-MADHAVARAM,27,173000,"IMPROVEMENTS TO EXTING BT ROAD AT GANESH NAGAR EXTN IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2999,Roads,Completed,NC-MADHAVARAM,27,538000,"IMPROVEMENTS TO EXTING BT ROAD AT TELEPHONE COLONY SOUTH 2ND STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3000,Roads,Completed,NC-MADHAVARAM,27,235000,"IMPROVEMENTS TO EXTING BT ROAD AT PERUMAL KOIL CROSS STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3001,Roads,Completed,NC-MADHAVARAM,27,333000,"IMPROVEMENTS TO EXTING BT ROAD AT PERUMAL KOIL 7TH STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3002,Roads,Completed,NC-MADHAVARAM,27,862000,"IMPROVEMENTS TO EXTING BT ROAD AT KAMBAN NAGAR MAIN ROAD IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3003,Roads,Completed,NC-MADHAVARAM,27,785000,"IMPROVEMENTS TO EXTING BT ROAD AT S.S.V. KOIL STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3004,Roads,Completed,NC-MADHAVARAM,27,776000,"IMPROVEMENTS TO EXTING BT ROAD AT KAMBAN KAVI NAGAR IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3005,Roads,Completed,NC-MADHAVARAM,27,327000,"IMPROVEMENTS TO EXTING BT ROAD AT ESRA SARGUNAM 1ST STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3006,Roads,Completed,NC-MADHAVARAM,27,633000,"IMPROVEMENTS TO EXTING BT ROAD AT SUBRAMANIYAM STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3008,Roads,Completed,NC-MADHAVARAM,27,616000,"IMPROVEMENTS TO EXTING BT ROAD AT DEVI NAGAR IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3009,Roads,Completed,NC-MADHAVARAM,27,158000,"IMPROVEMENTS TO EXTING BT ROAD AT DEVI NAGAR 1ST CROSS STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3010,Roads,Completed,NC-MADHAVARAM,27,173000,"IMPROVEMENTS TO EXTING BT ROAD AT DEVI NAGAR 2ND CROSS STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3011,Roads,Completed,NC-MADHAVARAM,27,130000,"IMPROVEMENTS TO EXTING BT ROAD AT V.P.CHITTAN STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3012,Roads,Completed,NC-MADHAVARAM,27,353000,"IMPROVEMENTS TO EXTING BT ROAD AT BHAVANI AMMAN KOIL STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3013,Roads,Completed,NC-MADHAVARAM,27,105000,"IMPROVEMENTS TO EXTING BT ROAD AT KURINJI STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3014,Roads,Completed,NC-MADHAVARAM,27,202000,"IMPROVEMENTS TO EXTING BT ROAD AT ESWARAN KOIL 2ND LANE IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3015,Roads,Completed,NC-MADHAVARAM,27,520000,"IMPROVEMENTS TO EXTING BT ROAD AT ESWARAN KOIL 1ST LANE IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3016,Roads,Completed,NC-MADHAVARAM,27,1502000,"IMPROVEMENTS TO EXTING BT ROAD AT MANDAVELI MAIN ROAD IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3017,Roads,Completed,NC-MADHAVARAM,27,125000,"IMPROVEMENTS TO EXTING BT ROAD AT NEHRU 1ST CROSS STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3018,Roads,Completed,NC-MADHAVARAM,27,163000,"IMPROVEMENTS TO EXTING BT ROAD AT NEHRU 2ND CROSS STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3019,Roads,Completed,NC-MADHAVARAM,27,195000,"IMPROVEMENTS TO EXTING BT ROAD AT NEHRU 3RD CROSS STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3020,Roads,Completed,NC-MADHAVARAM,27,965000,"RESTORATION OF ROAD CUT MADE BY CMWSS BOARD AT PERUMAL KOIL 1ST CROSS STREET IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/5657,Buildings,Completed,NC-MADHAVARAM,27,1460000,"IMPROVEMENT WORKS TO MANDAVELI (TELUGU COLONY) BURIAL GROUND IN DN-27, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/5660,Buildings,Completed,NC-MADHAVARAM,27,1260000,"CONSTRUCTION OF COMPOUND WALL TO RRC & SOURCE SEGREGATION SHED AT MANDAVELI (TELUGU COLONY) BURIAL GROUND IN DN-27, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/8771,Buildings,Completed,NC-MADHAVARAM,27,432000,"IMPROVEMENTS TO SIDE DRAIN AT PERUMAL KOIL STREET (EAST) IN DIV-27,UNIT-7,ZONE-3",Own Sources,3,2018-19,2018-19 B/2018-19/9000,Buildings,Completed,B-Buildings,28,8208326,Proposed Construction of Special shelters Near Aavin milk farm kulam Greater Chennai corporations road side vacant land in dn-28 zone-3,Own Sources,3,2018-19,2021-22 BR/2018-19/18245,Road Cut,Completed,BR-Bus Route Roads,28,769000,Restoration of OFC road cut made by M/s Bharathi Airtel at various interior roads in Div-28 Unit- 7 Zone-3(Deposit code-57/0167/2018-19),Deposit Works,3,2018-19,2019-20 L/2018-19/4582,Electrical,Completed,L-Electrical,28,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office-28, Arul Nagar, Madhavaram, Div-28, Zone-III",Loans And Grants,3,2018-19,2019-20 NC/2018-19/0695,Parks,Completed,NC-MADHAVARAM,28,243918,"MAINTENANCE OF PADMAGIRI NAGAR PARK BY QUALIFIED HORTICULTURIST FROM MAY 2018 TO JULY 2018 DV-28, UNIT-7, ZONE-III",Own Sources,3,2018-19,2018-19 NC/2018-19/10444,Buildings,Completed,NC-MADHAVARAM,28,176150,"DESILTING OF SIDE DRAIN AT M.M.C MAIN ROAD TO ERIKARAI IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/13275,Parks,Completed,NC-MADHAVARAM,28,332000,"Annual Maintenance for Park at Krishna Nagar & Childrens play field in div-28., Unit-7, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13276,Parks,Completed,NC-MADHAVARAM,28,928000,"Annual Maintenance for Park at Padmagiri Nagar in div-28., Unit-7, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13944,Buildings,Completed,NC-MADHAVARAM,28,97000,"NAME OF WORK: REPAIRS AND MAINTENANCE OF AMMA UNAVAGAM AT K.K.THAZHI MAIN ROAD (PADAVATTAMMAN KOIL OPPOSITE) IN DIVISION-28,UNIT-7,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13945,Buildings,Completed,NC-MADHAVARAM,28,270000,"NAME OF WORK: REPAIRS AND MAINTENANCE OF AMMA UNAVAGAM AT ARUL NAGAR MAIN ROAD IN DIVISION-28,UNIT-7,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/3031,Road Cut,Completed,NC-MADHAVARAM,28,500000,"FORMING OF INTERIOR BT ROAD AT KUPPU STREET IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3032,Road Cut,Completed,NC-MADHAVARAM,28,643000,"FORMING OF INTERIOR BT ROAD AT PADMAGIRI NAGAR EXTENSION IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3033,Road Cut,Completed,NC-MADHAVARAM,28,800000,"FORMING OF INTERIOR BT ROAD AT AVM AVENUE 1ST MAIN STREET IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3034,Road Cut,Completed,NC-MADHAVARAM,28,864000,"FORMING OF INTERIOR BT ROAD AT AVM AVENUE 2ND MAIN STREET IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3035,Road Cut,Completed,NC-MADHAVARAM,28,158000,"FORMING OF INTERIOR BT ROAD AT AVM AVENUE 1st STREET IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3036,Road Cut,Completed,NC-MADHAVARAM,28,325000,"FORMING OF INTERIOR BT ROAD AT AVM AVENUE 2ND STREET IN DIVISION-28, UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3037,Road Cut,Completed,NC-MADHAVARAM,28,313000,"FORMING OF INTERIOR BT ROAD AT AVM AVENUE 3RD STREET IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3038,Road Cut,Completed,NC-MADHAVARAM,28,226000,"FORMING OF INTERIOR BT ROAD AT AVM AVENUE 4TH STREET IN DIVISION-28,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 D/2018-19/9908,Storm Water Drain,Completed,D-Storm Water Drains,29,25825000,Construction of Storm Water Drain at Ediama Nagar and 5 other streets in Zone - 3 & 4 in Package - 5,Grants,3,2018-19,2020-21 NC/2018-19/10414,Storm Water Drain,Completed,NC-MADHAVARAM,29,300850,"Desilting of Side Drain at Various street in Division -29, Unit-7, Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/10417,Storm Water Drain,Completed,NC-MADHAVARAM,29,223170,"Providing a new manhole doors at various streets in Division -29, Unit-7, Zone-3",Own Sources,3,2018-19,2018-19 NC/2018-19/13450,Buildings,Completed,NC-MADHAVARAM,29,136000,"IMPROVEMENTS TO AMMA UNAVAGAM AT DEVARAJAN STREET IN DIVISION-29, UNIT-7,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13534,Buildings,Completed,NC-MADHAVARAM,29,145000,"IMPROVEMENTS TO AMMA UNAVAGAM AT BALJIPALAYAM IN DIVISION-29, UNIT-7,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13632,Buildings,Completed,NC-MADHAVARAM,29,1350000,"SUPPLYING AND PROVIDING GALVANIZED IRON SHEET FOR COCONUT HUSK AND SUGAR CANE HUSK AT VELU STREET COMPOST YARD IN DN-29, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1942,Road Cut,Completed,NC-MADHAVARAM,29,366000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT ANANDAN STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/1944,Road Cut,Completed,NC-MADHAVARAM,29,258000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT CHANDRAN STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/1997,Road Cut,Completed,NC-MADHAVARAM,29,344000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT KANNAIYARAM CROSS STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2008,Road Cut,Completed,NC-MADHAVARAM,29,344000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT KRISHNAN STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2013,Road Cut,Completed,NC-MADHAVARAM,29,559000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT KUMARIANANDAN STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2071,Road Cut,Completed,NC-MADHAVARAM,29,266000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT MANICKAM STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2072,Road Cut,Completed,NC-MADHAVARAM,29,473000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT MUNUSAMY 2ND CROSS STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2073,Road Cut,Completed,NC-MADHAVARAM,29,365000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT MUNUSAMY 1ST CROSS STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2074,Road Cut,Completed,NC-MADHAVARAM,29,85000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT MUNUSAMY 3RD CROSS 1ST LANE STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2075,Road Cut,Completed,NC-MADHAVARAM,29,65000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT MUNUSAMY 3RD CROSS 2ND LANE STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2077,Road Cut,Completed,NC-MADHAVARAM,29,495000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT MUNUSAMY 3RD CROSS STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2078,Road Cut,Completed,NC-MADHAVARAM,29,473000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT P.GOVINDASAMY STREET IN DIV-29,UNIT- ,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2079,Road Cut,Completed,NC-MADHAVARAM,29,151000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT PARTHASARATHY 5TH CROSS STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2082,Road Cut,Completed,NC-MADHAVARAM,29,790000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT PERUMAL KOIL 2ND CROSS STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2083,Road Cut,Completed,NC-MADHAVARAM,29,301000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT PERUMAL KOIL 4TH CROSS STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2084,Road Cut,Completed,NC-MADHAVARAM,29,237000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT PONNUSAMY STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2085,Road Cut,Completed,NC-MADHAVARAM,29,322000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT SIGAMANI STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2086,Road Cut,Completed,NC-MADHAVARAM,29,215000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT KUMARIANANDAN CROSS STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2087,Road Cut,Completed,NC-MADHAVARAM,29,215000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT SWAMY DOSS STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2088,Road Cut,Completed,NC-MADHAVARAM,29,365000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT T.V.K STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2089,Road Cut,Completed,NC-MADHAVARAM,29,494000,"PROVIDING AND LAYING CEMENT CONCRETE ROAD AT V.O.C STREET IN DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/3642,Buildings,Completed,NC-MADHAVARAM,29,997000,"CONSTRUCTION OF PARTITION WALL IN NORTH WESTERN SIDE OF COMPOST YARD SOURCE SEGREGATION PURPOSE AT VELU STREET IN DN-29, UNIT-7, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/5232,Buildings,Completed,NC-MADHAVARAM,29,160000,"IMPROVEMENT WORKS TO DIVISIONAL OFFICE AT DEVARAJAN STREET IN DN-29, UNIT-7, ZONE-3",Own Sources,3,2018-19,2019-20 NC/2018-19/5630,Buildings,Completed,NC-MADHAVARAM,29,791000,"IMPROVEMENTS TO SIDE DRAIN AT T.V.K STREET,MANICKAM STREET,CHANDRAN STREET AT DIV-29,UNIT-7,ZONE-3",Own Sources,3,2018-19,2018-19 BR/2018-19/18208,Road Cut,Completed,BR-Bus Route Roads,30,818000,Restoration of OFC road cut made by M/s Bharathi airtel at various interior roads in Unit-8 Zone-3(Deposit code-57/0167/2018-19),Deposit Works,3,2018-19,2019-20 L/2018-19/4596,Electrical,Completed,L-Electrical,30,172400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit office 8, MRH Road (near Madhavaram Bus Stand) in Dn.30, Zone- III. EB Account Number: 066.001.819",Loans And Grants,3,2018-19,2019-20 NC/2018-19/10357,Road Cut,Completed,NC-MADHAVARAM,30,1160000,"IMPROVEMENTS TO INTERIOR ROAD AT VRD NAGAR 1ST & 2ND MAIN ROAD IN DIVISION - 30, UNIT-8, ZONE -3",Own Sources,3,2018-19,2019-20 NC/2018-19/10358,Road Cut,Completed,NC-MADHAVARAM,30,92000,"IMPROVEMENTS TO INTERIOR ROAD AT Anna street IN DIVISION - 30, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/10360,Road Cut,Completed,NC-MADHAVARAM,30,324000,"IMPROVEMENTS TO INTERIOR ROAD AT Victroy Field IN DIVISION - 30, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/10363,Road Cut,Completed,NC-MADHAVARAM,30,195000,"Providing and laying of Cement Concrete Interior Roads at PUKRAJ NAGAR 6TH MAIN ROAD 1ST CROSS STREET IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/10366,Road Cut,Completed,NC-MADHAVARAM,30,87000,"Providing and laying of Cement Concrete Interior Roads at Padmavathy Nagar 5th cross street IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10367,Road Cut,Completed,NC-MADHAVARAM,30,195000,"Providing and laying of Cement Concrete Interior Roads at Padmavathy Nagar 4th cross street IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10368,Road Cut,Completed,NC-MADHAVARAM,30,195000,"Providing and laying of Cement Concrete Interior Roads at Padmavathy Nagar 3rd cross street IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10369,Road Cut,Completed,NC-MADHAVARAM,30,195000,"Providing and laying of Cement Concrete Interior Roads at Padmavathy Nagar 2nd cross street IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1044,Buildings,Completed,NC-MADHAVARAM,30,183830,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL(RAJAJI STREET) IN DIVISION-30, UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/10495,Storm Water Drain,Completed,NC-MADHAVARAM,30,414940,"DESILTING OF SIDE DRAIN AT VARIOUS STREET IN DIVISION - 30, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2018-19 NC/2018-19/10505,Storm Water Drain,Completed,NC-MADHAVARAM,30,37190,"PROVIDING MAN HOLE AT VARIOUS STREET IN DIVISION - 30, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2018-19 NC/2018-19/10636,Roads,Completed,NC-MADHAVARAM,30,1144000,"FORMING AND ROAD WIDENING OF BT ROAD IN V.S.MANI NAGAR IN DIVISION-30, UNIT-8, ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/13100,Parks,Completed,NC-MADHAVARAM,30,200000,"Annual Maintenance for Park at RC flat Arul Nagar in Division - 30, Unit - 8, Zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/13103,Parks,Completed,NC-MADHAVARAM,30,803000,"Annual Maintenance for park at VRD nagar in Division - 30, Unit - 8, Zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/13184,Parks,Completed,NC-MADHAVARAM,30,478000,"Annual Maintenance Park at Ring Road Housing Sector in Div-30, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13194,Parks,Completed,NC-MADHAVARAM,30,228000,"Annual Maintenance Park at Sivasakthi Nagar 2nd Main road in Div-30, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13358,Buildings,Completed,NC-MADHAVARAM,30,347000,"IMPROVEMENT AND MAINTAINENCE WORK FOR AMMA UNAVAGAM AT SIVA SAKTHI NAGAR IN DN-30, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13845,Buildings,Completed,NC-MADHAVARAM,30,170000,"IMPROVEMENT AND MAINTENANCE WORK FOR DIVISION OFFICE IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2098,Road Cut,Completed,NC-MADHAVARAM,30,902000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT BAGWAT SINGH NAGAR IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2126,Road Cut,Completed,NC-MADHAVARAM,30,187000,"IMPROVEMENTS TO INTERIOR OF ROAD AT BAGWAT SINGH 1ST STREET IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2129,Road Cut,Completed,NC-MADHAVARAM,30,187000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT BAGWAT SINGH 2ND STREET IN DIVISION-30,UN IT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2133,Road Cut,Completed,NC-MADHAVARAM,30,187000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT BAGWAT SINGH ROAD 3RD STREET IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2137,Road Cut,Completed,NC-MADHAVARAM,30,187000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT PUKRAJ NAGAR 6TH MAIN ROAD 2ND CROSS STREET IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2140,Road Cut,Completed,NC-MADHAVARAM,30,187000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT PUKRAJ 6TH MAIN ROAD 3RD CROSS STREET IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2143,Road Cut,Completed,NC-MADHAVARAM,30,1040000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT BHARATHIYAR STREET IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2163,Road Cut,Completed,NC-MADHAVARAM,30,412000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT PUKRAJ NAGAR TO BHARATHIYAR STREET CONNECTION IN DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2166,Road Cut,Completed,NC-MADHAVARAM,30,696000,"IMPROVEMENTS TO INTERIOR OF ROAD CUT AT PADMAVATHY NAGAR 1ST STREET DIVISION-30,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/7011,Buildings,Completed,NC-MADHAVARAM,30,490000,"CONSTRUCTION OF COMPOUND WALL AT RING ROAD HOUSING SECTOR IN DIVISION-30, UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/0691,Parks,Completed,NC-MADHAVARAM,31,190654,"MAINTENANCE OF KKR GARDEN PARK AT QUALIFIED HORTICULTURIST FOR MAINTENANCE WORK PERIOD OF MAY 2018 TO JULY 2018 IN DN-31 , UNIT-8, ZONE-III",Own Sources,3,2018-19,2018-19 NC/2018-19/0693,Parks,Completed,NC-MADHAVARAM,31,218285,"MAINTENANCE OF KKR NAGAR AND RC FLATS PARK BY QUALIFIED HORTICULTURIST FROM MAY 2018 TO JULY 2018 DV-31, UNIT-8, ZONE-III",Own Sources,3,2018-19,2018-19 NC/2018-19/10496,Storm Water Drain,Completed,NC-MADHAVARAM,31,705060,"DESILTING OF SIDE DRAIN AT VARIOUS STREET IN DIVISION - 31, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2018-19 NC/2018-19/10504,Storm Water Drain,Completed,NC-MADHAVARAM,31,27890,"PROVIDING MAN HOLE AT VARIOUS STREET IN DIVISION - 31, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/1152,Buildings,Completed,NC-MADHAVARAM,31,367660,"OUTSOURCING PRIVATE LABOURS FOR ADI DRAVIDA WELFARE SCHOOL PANDIAN STREET & PNSS SCHOOL KANNABIRAN KOIL STREET IN DIVISION-31, UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13224,Parks,Completed,NC-MADHAVARAM,31,197000,"Annual Maintenance Park, at RC Flats, MRH road, in div-31, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13225,Parks,Completed,NC-MADHAVARAM,31,855000,"Annual Maintenance Park, at KKR Nagar 1st Main road in div-31, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13226,Parks,Completed,NC-MADHAVARAM,31,887000,"Annual Maintenance park at KKR garden 2nd Main road in div-31, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13467,Buildings,Completed,NC-MADHAVARAM,31,290000,"Repair and Improvement Amma Unavagam at Muthumariamman Kovil Street in Div-31,Unit-8,Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13760,Buildings,Completed,NC-MADHAVARAM,31,190000,"Improvement to Amma Unavagam at Kannabiran Kovil Street in Div-31,Unit-8,Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13888,Buildings,Completed,NC-MADHAVARAM,31,1330000,"IMPROVEMENT AND RAISING OF SIDE DRAIN AT V.O.C STREET IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2018-19,2020-21 NC/2018-19/1948,Buildings,Completed,NC-MADHAVARAM,31,51000,"Repairs and improvement to park at kkr nagar Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2090,Road Cut,Completed,NC-MADHAVARAM,31,2347000,"IMPROVEMENTS TO INTERIOR ROAD at Jangiri Shop in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2092,Road Cut,Completed,NC-MADHAVARAM,31,621000,"IMPROVEMENTS TO INTERIOR ROAD at T.V.K. 5th St. in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2094,Road Cut,Completed,NC-MADHAVARAM,31,788000,"IMPROVEMENTS TO INTERIOR ROAD at Thiruvalluvar Cross St. 1st. in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2096,Road Cut,Completed,NC-MADHAVARAM,31,209000,"IMPROVEMENTS TO INTERIOR ROAD at K.K.R. Garden 4th Cross St in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2099,Road Cut,Completed,NC-MADHAVARAM,31,209000,"IMPROVEMENTS TO INTERIOR ROAD at K.K.R. Garden 5th Cross St in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2102,Road Cut,Completed,NC-MADHAVARAM,31,209000,"IMPROVEMENTS TO INTERIOR ROAD at K.K.R. Garden 6th Cross St in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2103,Road Cut,Completed,NC-MADHAVARAM,31,209000,"IMPROVEMENTS TO INTERIOR ROAD at K.K.R. Garden 8th Cross St in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2108,Road Cut,Completed,NC-MADHAVARAM,31,523000,"IMPROVEMENTS TO INTERIOR ROAD at Kannan Nagar 1st St in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2112,Road Cut,Completed,NC-MADHAVARAM,31,478000,"IMPROVEMENTS TO INTERIOR ROAD at Kannan Nagar 2nd St in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2113,Road Cut,Completed,NC-MADHAVARAM,31,990000,"IMPROVEMENTS TO INTERIOR ROAD at Burma Colony Lane in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2120,Road Cut,Completed,NC-MADHAVARAM,31,863000,"IMPROVEMENTS TO INTERIOR ROAD at Anna nagar 2nd street in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2125,Road Cut,Completed,NC-MADHAVARAM,31,294000,"IMPROVEMENTS TO INTERIOR ROAD at K.K.R Garden 3rd cross street in Div-31,Unit-8,Z",Own Sources,3,2018-19,2019-20 NC/2018-19/2131,Road Cut,Completed,NC-MADHAVARAM,31,490000,"IMPROVEMENTS TO INTERIOR ROAD at K.K.R Garden 9th cross street in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2135,Road Cut,Completed,NC-MADHAVARAM,31,361000,"IMPROVEMENTS TO INTERIOR ROAD at Sathyaraj Nagar 1st street in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2142,Road Cut,Completed,NC-MADHAVARAM,31,621000,"IMPROVEMENTS TO INTERIOR ROAD at Sathyaraj Nagar 2nd street in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2145,Road Cut,Completed,NC-MADHAVARAM,31,412000,"IMPROVEMENTS TO INTERIOR Road at Sathyaraj Nagar 3rd street in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2148,Road Cut,Completed,NC-MADHAVARAM,31,600000,"IMPROVEMENTS TO INTERIOR ROAD at Sathyaraj Nagar Main Road in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2158,Roads,Completed,NC-MADHAVARAM,31,851000,"IMPROVEMENTS TO INTERIOR road at AMBEDHKAR NAGAR MAIN ROAD in div-31,unit-8,zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2164,Roads,Completed,NC-MADHAVARAM,31,1734000,"Providing and laying of Cement Concrete Interior Roads at K.P Garden in div-31,unit-8,zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/2202,Roads,Completed,NC-MADHAVARAM,31,1331000,"Providing and laying of Cement Concrete Interior Roads at at V.O.C St in Div-31,Unit-8,Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/5383,Buildings,Completed,NC-MADHAVARAM,31,140000,"Providing drainage Arrangement for PC at Kannabiran Kovil Street (Backside of Dental Hospital) Div-31, Unit-8,Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/6975,Roads,Completed,NC-MADHAVARAM,31,1150000,"WIDENING OF ROAD AT KKR NAGAR 1ST MAIN ROAD IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/8634,Buildings,Completed,NC-MADHAVARAM,31,253000,Improvement to ICDS at Muthumariamman kovil street in Dn-31 Unit-8 Zone-3.,Own Sources,3,2018-19,2019-20 NC/2018-19/8637,Buildings,Completed,NC-MADHAVARAM,31,61000,Improvement to ICDS at Kannabiran kovil street in Dn-31 Unit-8 Zone-3.,Own Sources,3,2018-19,2019-20 NC/2018-19/9827,Buildings,Completed,NC-MADHAVARAM,31,440000,"Repairs and Improvements to the Health Post at Kannabiran Kovil Street in Division 31, Unit 8, Zone 3.",Own Sources,3,2018-19,2020-21 BR/2018-19/1164,Roads,Completed,BR-Bus Route Roads,32,292000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 3 against the challan no07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017 and Deposit code 57/0666/2017-18.",Deposit Works,3,2018-19,2019-20 NC/2018-19/10497,Storm Water Drain,Completed,NC-MADHAVARAM,32,291860,"DESILTING OF SIDE DRAIN AT VARIOUS STREET IN DIVISION - 32, UN IT - 8, ZONE - 3",Own Sources,3,2018-19,2018-19 NC/2018-19/10503,Storm Water Drain,Completed,NC-MADHAVARAM,32,27890,"PROVIDING MAN HOLE AT VARIOUS STREET IN DIVISION - 32, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/1154,Buildings,Completed,NC-MADHAVARAM,32,459575,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL (LAKSHIMI NARAYANAN PERUMAL KOIL STREET) & CHENNAI HIGHER SEC SCHOOL (BARATHIYAR STREET) IN DIVISION-32, UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13227,Parks,Completed,NC-MADHAVARAM,32,353000,"Abstract for Maintenance Estimate for Park, at Teachers colony 6th main road in div-32, Zone-3(per year)",Own Sources,3,2018-19,2019-20 NC/2018-19/13229,Parks,Completed,NC-MADHAVARAM,32,766000,"Abstract for Maintenance Estimate for Park, at Teachers colony 4th cross street in div-32, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13476,Buildings,Completed,NC-MADHAVARAM,32,177000,"NAME OF WORK: Improvement to Amma Unavagam at Gangaiamman Kovil Street in Div-32,Unit-8,Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13483,Buildings,Completed,NC-MADHAVARAM,32,172000,"NAME OF WORK: Improvement to Amma Unavagam at Villivakam road in Div-32,Unit-8,Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13695,Buildings,Completed,NC-MADHAVARAM,32,459000,"REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE AT KADAPAH ROAD IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13866,Storm Water Drain,Completed,NC-MADHAVARAM,32,780000,"CONSTRUCTION OF NEW SIDE DRAIN PARTLY AND REIMPROVEMENT AND REPAIR TO THE EXISTING SIDE DRAIN (SIZE 0.45 CM x 0.60 CM) AT BAJANAI KOIL STREET PART AND VOC STREET PART IN DN-32,UNIT-8, ZONE-3.(LENGTH :75.00 M)",Own Sources,3,2018-19,2020-21 NC/2018-19/16114,Buildings,Completed,NC-MADHAVARAM,32,500000,"SUPPLYING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS FOR CPS AT LAKSHMINARAYANA PERUMAL KOIL STREET IN DIVISION-32, UNIT-8, ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/2182,Road Cut,Completed,NC-MADHAVARAM,32,4617000,"Improvements of interior BT road at Gangaiamman koil street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2183,Road Cut,Completed,NC-MADHAVARAM,32,2254000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Teacher's Colony 6th Main Road in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2184,Road Cut,Completed,NC-MADHAVARAM,32,2294000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Vivekanadha street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2185,Road Cut,Completed,NC-MADHAVARAM,32,2196000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Nethaji Street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2186,Road Cut,Completed,NC-MADHAVARAM,32,2107000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at V.O.C street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2188,Road Cut,Completed,NC-MADHAVARAM,32,1895000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Teacher's Colony 7th Main Road & 7th cross street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2190,Road Cut,Completed,NC-MADHAVARAM,32,1199000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Rajaji street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2191,Road Cut,Completed,NC-MADHAVARAM,32,907000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Thiruvalluvar Street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2192,Road Cut,Completed,NC-MADHAVARAM,32,589000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Vinus Nagar in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2193,Road Cut,Completed,NC-MADHAVARAM,32,1457000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Bharathiyar street Extn in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2194,Road Cut,Completed,NC-MADHAVARAM,32,869000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Kamaraj street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2197,Road Cut,Completed,NC-MADHAVARAM,32,1162000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Kalainger street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2199,Road Cut,Completed,NC-MADHAVARAM,32,1470000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Ramani Nagar in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2200,Road Cut,Completed,NC-MADHAVARAM,32,1468000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Bhavani Nagar in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2206,Road Cut,Completed,NC-MADHAVARAM,32,1709000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Thilagar street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2207,Road Cut,Completed,NC-MADHAVARAM,32,1242000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Ramadass street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2215,Road Cut,Completed,NC-MADHAVARAM,32,1468000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Teacher's Colony 3rd Main Road in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2217,Road Cut,Completed,NC-MADHAVARAM,32,2128000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Selvam Nagar in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2226,Road Cut,Completed,NC-MADHAVARAM,32,742000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Teacher's colony 5th cross street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2236,Road Cut,Completed,NC-MADHAVARAM,32,541000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Teacher's Colony 6th cross street in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2237,Road Cut,Completed,NC-MADHAVARAM,32,880000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at V.V Nagar 1, 2 & 3 in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2239,Road Cut,Completed,NC-MADHAVARAM,32,612000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Rajaji street Extn in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2241,Road Cut,Completed,NC-MADHAVARAM,32,293000,"IMPROVEMENTS TO INTERIOR ROAD Cut Work made by CMWSSB at Madhavan Nagar in Div - 32, unit - 8, zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/2247,Road Cut,Completed,NC-MADHAVARAM,32,1532000,"Providing and laying of Cement Concrete Interior Roads at PALLAVAN STREET in Div - 32, unit - 8, Zone - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/5202,Roads,Completed,NC-MADHAVARAM,32,572000,"PROVIDIND & FIXING STREET NAME BOARD AT VARIOUS STREET IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/5234,Storm Water Drain,Completed,NC-MADHAVARAM,32,1056000,"DEMOLITION AND RECONSTRUCTION SIDE DRAIN AT BHARATHIYAR STREET(PART) IN DIV-32, UNIT-8, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/7081,Parks,Completed,NC-MADHAVARAM,32,138000,"Improvements to Parks at Teacher's Colony 4th cross street & 6th Main road in div-32, Unit-8, Zone-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/7687,Buildings,Completed,NC-MADHAVARAM,32,710000,"Providing shed in front of Health Center (NHUM) at Gangaiamman kovil st in div-32, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 BR/2018-19/18206,Road Cut,Completed,BR-Bus Route Roads,33,602000,Restoration of OFC road cut made by M/s Bharathi airtel at various interior roads in Unit-8 Zone-3(Deposit code-57/0167/2018-19),Deposit Works,3,2018-19,2019-20 BR/2018-19/18207,Road Cut,Completed,BR-Bus Route Roads,33,602000,Restoration of OFC road cut made by M/s Bharathi airtel at various interior roads in Unit-8 Zone-3(Deposit code-57/0167/2018-19),Deposit Works,3,2018-19,2019-20 BR/2018-19/3404,Roads,Completed,BR-Bus Route Roads,33,357000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 3 against the challan no 07/2017-18/0377458,07/2017-18/0377463 DT: 21.07.2017 and Deposit code 57/0668/2017-18.",Deposit Works,3,2018-19,2019-20 NC/2018-19/10498,Storm Water Drain,Completed,NC-MADHAVARAM,33,473180,"DESILTING OF SIDE DRAIN AT VARIOUS STREET IN DIVISION - 33, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2018-19 NC/2018-19/10499,Storm Water Drain,Completed,NC-MADHAVARAM,33,130150,"PROVIDING MAN HOLE AT VARIOUS STREET IN DIVISION - 33, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2018-19 NC/2018-19/10634,Roads,Completed,NC-MADHAVARAM,33,1915000,"FORMING AND RAISING BT ROAD AT ANNAPOORNA NAGAR 1ST MAIN ROAD IN DIVISION-33,UNIT-8, ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/10653,Roads,Completed,NC-MADHAVARAM,33,1445000,"FORMING AND RAISING OF BT ROAD AT RAGHAVENDRA NAGAR MAIN ROAD IN DIVISION-33, UNIT-8, ZONE -3.",MLACDS,3,2018-19,2019-20 NC/2018-19/1155,Buildings,Completed,NC-MADHAVARAM,33,183830,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI MIDDLE SCHOOL(PERIYAR SALAI) IN DIVISION-33, UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1227,Road Cut,Completed,NC-MADHAVARAM,33,564000,"IMPROVEMENTS TO INTERIOR ROAD AT KARPAGAM NAGAR 2ND STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1228,Road Cut,Completed,NC-MADHAVARAM,33,519000,"IMPROVEMENTS TO INTERIOR ROAD AT KARPAGAM NAGAR 3RD STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1229,Road Cut,Completed,NC-MADHAVARAM,33,703000,"IMPROVEMENTS TO INTERIOR ROAD AT MUTHUMARIAMMAN KIOL STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1230,Road Cut,Completed,NC-MADHAVARAM,33,482000,"IMPROVEMENTS TO INTERIOR ROAD AT BHARATHIYAR STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/1231,Road Cut,Completed,NC-MADHAVARAM,33,450000,"IMPROVEMENTS TO INTERIOR ROAD AT KAMBAR STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/1232,Road Cut,Completed,NC-MADHAVARAM,33,746000,"IMPROVEMENTS TO INTERIOR ROAD AT PRAKASH NAGAR 3RD MAINROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1233,Road Cut,Completed,NC-MADHAVARAM,33,561000,"IMPROVEMENTS TO INTERIOR ROAD AT PRAKASH NAGAR 9TH STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1234,Road Cut,Completed,NC-MADHAVARAM,33,752000,"IMPROVEMENTS TO INTERIOR ROAD AT V.P.C NAGAR MAINROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/1235,Road Cut,Completed,NC-MADHAVARAM,33,1134000,"IMPROVEMENTS TO INTERIOR ROAD AT MUNUSAMY NAGAR MAINROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/1236,Road Cut,Completed,NC-MADHAVARAM,33,466000,"IMPROVEMENTS TO INTERIOR ROAD AT CHANDRA PRABHU COLONY 1ST STREET IN DIV-33, UNIT-8, ZONE-3..",Own Sources,3,2018-19,2019-20 NC/2018-19/1237,Road Cut,Completed,NC-MADHAVARAM,33,216000,"IMPROVEMENTS TO INTERIOR ROAD AT SELVAM NAGAR 2ND STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/1238,Road Cut,Completed,NC-MADHAVARAM,33,201000,"RESTORATION OF ROAD CUT AT CHANDRA PRABHU COLONY 4TH STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13231,Parks,Completed,NC-MADHAVARAM,33,349000,"Annual Maintenance Estimate for Park, at Selvam Nagar in div-33, Zone-3",Own Sources,3,2018-19,2019-20 NC/2018-19/13237,Parks,Completed,NC-MADHAVARAM,33,405000,"Annual Maintenance Park, at Thanikachalam Nagar B block 5/2 cross street in div-33, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13238,Parks,Completed,NC-MADHAVARAM,33,354000,"Annual Maintenance Park at at VGP Nagar in div-33, Unit-8, Zone-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13474,Electrical,Completed,NC-MADHAVARAM,33,193000,"IMPROVEMENTS AND MAINTENANCE WORK FOR AMMA UNAVAGAM AT PERIYA SALAI IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13477,Electrical,Completed,NC-MADHAVARAM,33,129000,"IMPROVEMENTS AND MAINTANACE WORK FOR AMMA UNAVAGAM AT PERIYAR NAGAR IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/13512,Buildings,Completed,NC-MADHAVARAM,33,1308000,"DEMOLITION AND RECONSTRUCTIONS CULVERT AND PLACING PRE-CAST COVER SLAB OVER EXISTING SIDE DRAIN AT ANNA STREET IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13513,Buildings,Completed,NC-MADHAVARAM,33,516000,"IMPROVEMENT AND RAISING OF SIDE DRAIN AT BRINDHAVAN GARDEN MANROAD IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13782,Buildings,Completed,NC-MADHAVARAM,33,134000,"IMPROVEMENTS TO DIVISION OFFICE AT THANIKACHALAM NAGAR B BLOCK 5/2 CROSSS STREET IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/13791,Buildings,Completed,NC-MADHAVARAM,33,1412000,"IMPROVEMENTS AND CONSTRUCTION OF TOILET BLOCK AND LAYING CC ROAD TO BURIAL GROUND AT VALLIAMMAI NAGAR IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/14067,Roads,Completed,NC-MADHAVARAM,33,209000,"ATTENDING PATCHWORK AT VASUDEVAN THOTTAM IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/14068,Roads,Completed,NC-MADHAVARAM,33,707000,"ATTENDING PATCHWORK AT 80 FEET ROAD IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/14413,Buildings,Completed,NC-MADHAVARAM,33,98000,"IMPROVEMENTS TO CPS SCHOOL AT NEHRU STREET IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/14898,Buildings,Completed,NC-MADHAVARAM,33,98000,"MANUFACTURING, SUPPLYING AND ERECTION OF TRASH BOOM AND WITH FABRICATED STRUCTURE TO COLLECT FLOATING DEBRIES AT RAMALINGA COLONY A BLOCK JN.OF DIVISION-26 IN DIVISION- 33, UNIT - 8, ZONE - 3",Own Sources,3,2018-19,2019-20 NC/2018-19/14957,Buildings,Completed,NC-MADHAVARAM,33,38000,"MAINTENANCE TO SIDE DRAIN AT VPC NAGAR AND VGP NAGAR IN DIV-3,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/16067,Buildings,Completed,NC-MADHAVARAM,33,113000,"IMPROVEMENTS TO ICDS AT PERIYA SALAI IN DIV-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/16105,Buildings,Completed,NC-MADHAVARAM,33,500000,"SUPPLYING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS FOR CPS AT NEHRU STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/2115,Road Cut,Completed,NC-MADHAVARAM,33,431000,"IMPROVEMENTS TO INTERIOR ROAD AT Thanikachalam Nagar 'b' Block 5th main Road IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/2118,Road Cut,Completed,NC-MADHAVARAM,33,540000,"IMPROVEMENTS TO INTERIOR ROAD AT THANIKACHALAM NAGAR B BLOCK 5/2 CROSS STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/2119,Road Cut,Completed,NC-MADHAVARAM,33,345000,"IMPROVEMENTS TO INTERIOR ROAD AT KRISHNA NAGAR 1ST STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2122,Road Cut,Completed,NC-MADHAVARAM,33,409000,"IMPROVEMENTS TO INTERIOR ROAD AT MADURAI MANAVALAN NAGAR 1ST STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/2124,Road Cut,Completed,NC-MADHAVARAM,33,663000,"IMPROVEMENTS TO INTERIOR ROAD AT NETHAJI STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2127,Road Cut,Completed,NC-MADHAVARAM,33,374000,"IMPROVEMENTS TO INTERIOR ROAD AT ANNAPOORNI 1ST STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2130,Road Cut,Completed,NC-MADHAVARAM,33,231000,"IMPROVEMENTS TO INTERIOR ROAD AT SELVAM NAGAR 3RD MAIN ROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2134,Road Cut,Completed,NC-MADHAVARAM,33,561000,"IMPROVEMENTS TO INTERIOR ROAD AT VASU NAGAR 1ST STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2136,Road Cut,Completed,NC-MADHAVARAM,33,570000,"IMPROVEMENTS TO INTERIOR ROAD AT RANGASWAMY ROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2018-19 NC/2018-19/2139,Road Cut,Completed,NC-MADHAVARAM,33,807000,"IMPROVEMENTS TO INTERIOR ROAD AT V.O.C 2ND STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2144,Road Cut,Completed,NC-MADHAVARAM,33,605000,"IMPROVEMENTS TO INTERIOR ROAD AT BRINDAVAN GARDEN 4TH STREET IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2147,Road Cut,Completed,NC-MADHAVARAM,33,540000,"IMPROVEMENTS TO INTERIOR ROAD AT CHANDRA PRABHU COLONY MAIN ROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2150,Road Cut,Completed,NC-MADHAVARAM,33,329000,"IMPROVEMENTS TO INTERIOR ROAD AT KASIAMMAL NAGAR MAIN ROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2153,Road Cut,Completed,NC-MADHAVARAM,33,124000,"IMPROVEMENTS TO INTERIOR ROAD AT 80 FEET ROAD NEAR RAJUS FLATS IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2155,Road Cut,Completed,NC-MADHAVARAM,33,450000,"Providing and laying of Cement Concrete Interior Roads at GOWRI NAGAR 1ST STREET ,DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2157,Road Cut,Completed,NC-MADHAVARAM,33,360000,"Providing and laying of Cement Concrete Interior Roads at GOWRI NAGAR 2ND STREET ,DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2167,Road Cut,Completed,NC-MADHAVARAM,33,585000,"Providing and laying of Cement Concrete Interior Roads at VASU NAGAR 2ND STREET ,DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2168,Road Cut,Completed,NC-MADHAVARAM,33,579000,"Providing and laying of Cement Concrete Interior Roads at VASU NAGAR 3RD STREET ,DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2169,Road Cut,Completed,NC-MADHAVARAM,33,379000,"Providing and laying of Cement Concrete Interior Roads at VASU NAGAR 4TH STREET ,DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/2170,Road Cut,Completed,NC-MADHAVARAM,33,241000,"Providing and laying of Cement Concrete Interior Roads at PATEL STREET ,DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2020-21 NC/2018-19/2255,Road Cut,Completed,NC-MADHAVARAM,33,464000,"IMPROVEMENTS TO INTERIOR ROAD AT VINOBAJI STREET IN DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2262,Road Cut,Completed,NC-MADHAVARAM,33,309000,"IMPROVEMENTS TO INTERIOR ROAD AT PRAKASH NAGAR 10TH STREET IN DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2264,Road Cut,Completed,NC-MADHAVARAM,33,638000,"IMPROVEMENTS TO INTERIOR ROAD AT NATESAN NAGAR MAINROAD IN DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2406,Roads,Completed,NC-MADHAVARAM,33,1307000,"IMPROVEMENTS TO INTERIOR ROAD AT RAJAJI SALAI IN DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2407,Road Cut,Completed,NC-MADHAVARAM,33,496000,"IMPROVEMENTS TO INTERIOR ROAD AT ChandraPrabhu Colony 2nd Main Road IN DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/2408,Roads,Completed,NC-MADHAVARAM,33,1645000,"IMPROVEMENTS TO INTERIOR ROAD AT Thanikachalam Nagar 80 feet road IN DIVISION-33,UNIT-8,ZONE-3.",Own Sources,3,2018-19,2019-20 NC/2018-19/6136,Buildings,Completed,NC-MADHAVARAM,33,357000,"IMPROVEMENT AND RAISING OF SIDE DRAIN AT VASU DEVAN THOTTAM IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2018-19,2018-19 NC/2018-19/7304,Roads,Completed,NC-MADHAVARAM,33,368000,"FORMATION OF BT ROAD AT CHANDRA PRABHU COLONY 3RD STREET IN DIV-33,UNIT-8,ZONE-3",MLACDS,3,2018-19,2019-20 NC/2018-19/7308,Roads,Completed,NC-MADHAVARAM,33,285000,"FORMATION OF BT ROAD AT ANNAPOORNA NAGAR 1ST CROSS STREETIN DIV-33,UNIT-8,ZONE -3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7309,Roads,Completed,NC-MADHAVARAM,33,285000,"FORMATION OF BT ROAD AT ANNAPOORNA NAGAR 2ND CROSS STREET IN DIV-33,UNIT-8,ZONE-3",MLACDS,3,2018-19,2019-20 NC/2018-19/7467,Roads,Completed,NC-MADHAVARAM,33,293000,"FORMATION OF BT ROAD AT SWAMY RAMALINGA COLONY C BLOCK 1ST CROSS STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7469,Roads,Completed,NC-MADHAVARAM,33,365000,"FORMATION OF BT ROAD AT MAHATAMA GANDHI 1ST CROSS STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7472,Roads,Completed,NC-MADHAVARAM,33,142000,"RELAYING OF BT ROAD AT SWAMY RAMALINGA COLONY C BLOCK 2ND CROSS STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7477,Roads,Completed,NC-MADHAVARAM,33,926000,"RELAYING OF BT ROAD AT SWAMY RAMALINGA COLONY C BLOCK 2ND MAINROAD IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7478,Roads,Completed,NC-MADHAVARAM,33,206000,"RELAYING BT ROAD AT SWAMY RAMALINGA COLONY C BLOCK 3RD CROSS STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7480,Roads,Completed,NC-MADHAVARAM,33,668000,"RELAYING OF BT ROAD AT SWAMY RAMALINGA COLONY B BLOCK 3RD CROSS STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7481,Roads,Completed,NC-MADHAVARAM,33,300000,"RELAYING OF BT ROAD AT SWAMY RAMALINGA COLONY B BLOCK 2ND CROSS STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7484,Roads,Completed,NC-MADHAVARAM,33,476000,"RELAYING OF BT ROAD AT SAWMY RAMALIMGA COLONY MAINROAD IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7485,Roads,Completed,NC-MADHAVARAM,33,143000,"RELAYING OF BT ROAD AT MADURAI MANAVALAN NAGAR 3RD STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7486,Roads,Completed,NC-MADHAVARAM,33,332000,"RELAYING OF BT ROAD AT MADURAI MANAVALAN NAGAR 2ND STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 NC/2018-19/7487,Roads,Completed,NC-MADHAVARAM,33,236000,"RELAYING OF BT ROAD AT MADURAI MANAVALAN NAGAR 4TH STREET IN DIV-33,UNIT-8,ZONE-3.",MLACDS,3,2018-19,2019-20 B/2018-19/12144,Buildings,Completed,B-Buildings,34,1900000,"Additional works to Urban Primary Health Center building at Vivekananda Nagar in DN - 34, Zone - 4.",Own Sources,4,2018-19,2019-20 L/2018-19/5022,Electrical,Completed,L-Electrical,34,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chinna Kodungaiyur CPS in Div 34, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/10779,Storm Water Drain,Completed,ND-TONDIARPET,34,289000,"Desilting of Storm Water Drain and Minor Repairs in Various Location in Dn-34, U-9, Z-IV.",Own Sources,4,2018-19,2018-19 ND/2018-19/13924,Buildings,Completed,ND-TONDIARPET,34,500000,"Improvement works in Amma Unavagam IN DN-34, U-09, Z-IV",Own Sources,4,2018-19,2019-20 ND/2018-19/14016,Parks,Completed,ND-TONDIARPET,34,996000,"Maintenance of park at Binny Nagar Main Road, Venkateshwara colony v street, Union carbide colony 14th street, Kaveri Nagar in division-34, Unit-9, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/15565,Parks,Completed,ND-TONDIARPET,34,311000,"Maintenance of park at Carbite colony 9th street in division-34, Unit-09, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/3623,Buildings,Completed,ND-TONDIARPET,34,800000,"IMPROVEMENTS TO BURIAL GROUND AT SEETHARAM NAGAR BURIAL GROUND IN DN-34,U-9,Z-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/3788,Parks,Completed,ND-TONDIARPET,34,182000,"MAINTENANCE TO BURIAL GROUND GREENERY ARRANGEMENTS FOR 6 MONTHS AT SEETHARAM NAGAR BURIAL GROUND IN DN-34,U-9,Z-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/4150,Parks,Completed,ND-TONDIARPET,34,113000,"MAINTENANCE TO PARKS (2018) FOR 6 MONTHS AT UNION CARBIDE COLONY 9th STREET IN DN-34,U-9,Z-4",Own Sources,4,2018-19,2018-19 ND/2018-19/5895,Storm Water Drain,Completed,ND-TONDIARPET,34,600000,"Strom Water Drain Desilting Work at Various Places in Div-34, U-09, Z-IV.",Own Sources,4,2018-19,2018-19 ND/2018-19/6497,Playfields,Completed,ND-TONDIARPET,34,162000,"REPAIR WORK IN S.R. NAGAR PLAYFIELD IN DN-34, U-09, Z-IV.",Own Sources,4,2018-19,2018-19 ND/2018-19/6579,Roads,Completed,ND-TONDIARPET,34,92000,Relaying of B.T Road by Paver finisher at Anna Garden in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6580,Roads,Completed,ND-TONDIARPET,34,595000,Forming & Strengthening of B.T Road by Paver finisher at Bharathidhasan street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6582,Roads,Completed,ND-TONDIARPET,34,760000,Forming & Strengthening of B.T Road by Paver finisher at Ganesh Nagar 1st Cross Street n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6584,Roads,Completed,ND-TONDIARPET,34,259000,Forming & Strengthening of B.T Road by Paver finisher at Ganesh Nagar 1st Cross Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6585,Roads,Completed,ND-TONDIARPET,34,749000,Forming & Strengthening of B.T Road by Paver finisher at Ganesh Nagar 2nd Cross Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6586,Roads,Completed,ND-TONDIARPET,34,476000,Forming & Strengthening of B.T Road by Paver finisher at Ganesh Nagar 3rdCross Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6587,Roads,Completed,ND-TONDIARPET,34,906000,Forming & Strengthening of B.T Road by Paver finisher at Ganesh Nagar Main Road n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6588,Roads,Completed,ND-TONDIARPET,34,3740000,Forming & Strengthening of B.T Road by Paver finisher at Kattabomman street extension n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6607,Roads,Completed,ND-TONDIARPET,34,1054000,Forming & Strengthening of B.T Road by Paver finisher at Kramiya Garden Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6609,Roads,Completed,ND-TONDIARPET,34,232000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar 2nd Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6610,Roads,Completed,ND-TONDIARPET,34,264000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar 3rd Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6611,Roads,Completed,ND-TONDIARPET,34,231000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar 4th Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6612,Roads,Completed,ND-TONDIARPET,34,232000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar 5th Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6613,Roads,Completed,ND-TONDIARPET,34,232000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar 6th Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6615,Roads,Completed,ND-TONDIARPET,34,232000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar 7th Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6616,Roads,Completed,ND-TONDIARPET,34,1488000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar Main Road in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6618,Roads,Completed,ND-TONDIARPET,34,264000,Forming & Strengthening of B.T Road by Paver finisher at Nachiammai Nagar 1st Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6619,Roads,Completed,ND-TONDIARPET,34,794000,Forming & Strengthening of B.T Road by Paver finisher at Palpannai Cross Street n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6620,Roads,Completed,ND-TONDIARPET,34,463000,Forming & Strengthening of B.T Road by Paver finisher at Periyapalayathamman Street (Bharma mahal opp) n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6621,Roads,Completed,ND-TONDIARPET,34,247000,Relaying of B.T Road by Paver finisher at R.V. Nagar 5th street extension in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6622,Roads,Completed,ND-TONDIARPET,34,773000,Forming & Strengthening of B.T Road by Paver finisher at Sakthi Nagar n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6626,Roads,Completed,ND-TONDIARPET,34,328000,Relaying of B.T Road by Paver finisher at Sankaralingam nagar in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6629,Roads,Completed,ND-TONDIARPET,34,483000,Forming & Strengthening of B.T Road by Paver finisher at Thiru thangal Nagar 1st street n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6633,Roads,Completed,ND-TONDIARPET,34,811000,Forming & Strengthening of B.T Road by Paver finisher at Thiru thangal Nagar 2nd street n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6635,Roads,Completed,ND-TONDIARPET,34,429000,Forming & Strengthening of B.T Road by Paver finisher at Thiru thangal Nagar 3rd street n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6637,Roads,Completed,ND-TONDIARPET,34,330000,Forming & Strengthening of B.T Road by Paver finisher at Thiru thangal Nagar 4th street n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6639,Roads,Completed,ND-TONDIARPET,34,1154000,Forming & Strengthening of B.T Road by Paver finisher at Thiru thangal Nagar Main Road n Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6641,Roads,Completed,ND-TONDIARPET,34,849000,Relaying of B.T Road by Paver finisher at Vadhathamurugappan Main Road in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 ND/2018-19/6652,Roads,Completed,ND-TONDIARPET,34,1662000,Relaying of B.T Road by Paver finisher at Vadhathamurugappan Street in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2020-21 ND/2018-19/6653,Roads,Completed,ND-TONDIARPET,34,238000,Forming & Strengthening of B.T Road by Paver finisher at Vijya Nagar in Div-34 Unit-9 Zone-IV,Own Sources,4,2018-19,2019-20 BR/2018-19/12647,Road Cut,Completed,BR-Bus Route Roads,35,1970000,"Restoration of road cut at Thiruvalluvar salai in Dn-35, Zone-4, against challan No.BR/2016-17/0014860 and BR/2018-19/0021733. (Road cut made by CMWSSB)",Deposit Works,4,2018-19,2019-20 BR/2018-19/12653,Road Cut,Completed,BR-Bus Route Roads,35,1035000,"Restoration of road cut at Kamaraj salai in Dn-35, Zone-4, against challan No.BR/2016-17/0014860 and BR/2018-19/0021733. (Road cut made by CMWSSB)",Deposit Works,4,2018-19,2020-21 BR/2018-19/5635,Roads,Completed,BR-Bus Route Roads,35,72900,Road cut restoration (road cut made by BHARTI AIRTEL) at various division in Zone 4 against the challan no BR/2017-18/0011868 BR/2017-18/0011872 dt:28.07.2017 and Deposit code 57/0699/2017-18.,Deposit Works,4,2018-19,2019-20 BR/2018-19/7353,Roads,Completed,BR-Bus Route Roads,35,83500,Restoration of road cut made by CMWSSB at Tondiarpet High Road in zone-4 against challan No. BR/2017-18/0032115,Deposit Works,4,2018-19,2019-20 D/2018-19/9907,Storm Water Drain,Completed,D-Storm Water Drains,35,75680000,"Construction of Storm Water Drain at Muthamizh Nagar North, East, West, South, Muthamizh nagar 5 th main road and Muthamizh nagar 2 nd main road in Zone - 4, Package - 6",Grants,4,2018-19,2020-21 L/2018-19/5005,Electrical,Completed,L-Electrical,35,3058900,"Electrification of School Building and Provision of Tube Light,Fan,Plug point,etc at various loction in Division 35,36,37,45 and 46 under Kodungaiyur, E H Road and M K B Nagar Section in Zone IV.",Own Sources,4,2018-19,2019-20 L/2018-19/5024,Electrical,Completed,L-Electrical,35,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anna Salai CHS in Div 35, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5025,Electrical,Completed,L-Electrical,35,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Kamarajar Nagar, Block 2, CPS in Div 44, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5027,Electrical,Completed,L-Electrical,35,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kamaraj Salai CHS in Div 35, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5029,Electrical,Completed,L-Electrical,35,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chinnandimadam (T.H Road) CHS in Div 35, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5032,Electrical,Completed,L-Electrical,35,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Krishnamoorthy Salai, Unit Office in Div 35, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5034,Electrical,Completed,L-Electrical,35,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anna Salai, Health Post in Div 35, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/0529,Buildings,Completed,ND-TONDIARPET,35,490000,"IMPROVEMENTS WORK TO GYM AT 4TH BLOCK,4TH MAIN ROAD,MUTHAMIL NAGAR IN DIVISION-35, UNIT-9, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14119,Buildings,Completed,ND-TONDIARPET,35,550000,"Improvements to Amma Unavagam phase 2 at EH Road (G.N.T Road) in Div 35,Unit 9,Zone 04.",Own Sources,4,2018-19,2019-20 ND/2018-19/14127,Buildings,Completed,ND-TONDIARPET,35,175000,"Improvements to Amma Unavagam phase 1 Muthamil Nagar 2nd block 6TH Main Road in Div-35, Unit -09, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/15376,Footpath,Completed,ND-TONDIARPET,35,112000,"Improvements and Repair Center Mediam at TH Road in Div-35,Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/15568,Parks,Completed,ND-TONDIARPET,35,295000,"Maintenance of GNT road (Erukanchery) park in division-35, Unit-09, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/1947,Roads,Completed,ND-TONDIARPET,35,200000,"PATCH WORK AT MUTHAMIL NAGAR 97TH STREET IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/1950,Roads,Completed,ND-TONDIARPET,35,90000,"PATCH WORK AT KKD NAGAR 1ST MAIN ROAD IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/1951,Roads,Completed,ND-TONDIARPET,35,180000,"PATCH WORK AT KKD NAGAR 2ND MAIN ROAD IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/1952,Roads,Completed,ND-TONDIARPET,35,225000,"PATCH WORK AT KKD NAGAR 3RD MAIN ROAD IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/1953,Roads,Completed,ND-TONDIARPET,35,120000,"PATCH WORK AT EVR SALAI,ERUKKENCHERRY IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/3510,Storm Water Drain,Completed,ND-TONDIARPET,35,145000,"REPAIRS AND FIXING STORM WATER DRAINS DOOR AT VARIOUS STREETS IN DIV-35, UNIT-09,ZONE-04.",Own Sources,4,2018-19,2018-19 ND/2018-19/6358,Playfields,Completed,ND-TONDIARPET,35,1430000,"Proving yoga hall and meditation Centre at inside Chennai Primary School in Anna Salai,Erukkencherry Div-35, Unit-9, Zone-4",Own Sources,4,2018-19,2018-19 ND/2018-19/6697,Roads,Completed,ND-TONDIARPET,35,540000,"Relaying of BT Road at Tiruvalluvar Salai (Part) in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6698,Roads,Completed,ND-TONDIARPET,35,580000,"Relaying of BT Road at Muthamil Nagar 91 th street i in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6699,Roads,Completed,ND-TONDIARPET,35,556000,"Relaying of BT Road at KKD Nagar 6TH Main road in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6700,Roads,Completed,ND-TONDIARPET,35,278000,"Relaying of BT Road at EVR Salai in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6701,Roads,Completed,ND-TONDIARPET,35,612000,"Relaying of BT Road at ParthasarathI Reddy Street in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6702,Roads,Completed,ND-TONDIARPET,35,232000,"Relaying of BT Road at Union Salai in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6703,Roads,Completed,ND-TONDIARPET,35,579000,"Relaying of BT Road at Kandha Samy Kovil Street in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6704,Roads,Completed,ND-TONDIARPET,35,348000,"Relaying of BT Road at Kannabiran Kovil Street in Div-35, Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/6863,Roads,Completed,ND-TONDIARPET,35,309000,"Relaying of Cement Concrete Road Srinivasan Perumal Koil Streetin Div-35, Unit-9, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/6864,Roads,Completed,ND-TONDIARPET,35,291000,"Relaying of Cement Concrete Road at Sengaiya Mesthri Street in Div-35, Unit-9, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/6865,Roads,Completed,ND-TONDIARPET,35,436500,"Relaying of Cement Concrete Road at Thirupur Kumaran Street in Div-35, Unit-9, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/7935,Buildings,Completed,ND-TONDIARPET,35,780000,"Repair ILB Work and Construction of Under Level Sump for Amma Unavagam Phase-2 , GNT Road (E.H Road) in Div-35, Unit-09 Zone-04.",Own Sources,4,2018-19,2018-19 ND/2018-19/9740,Storm Water Drain,Completed,ND-TONDIARPET,35,1318000,"Improvements to Storm Water Drain at Anna Salai Main Street , Indhra Nagar West, KKD Nagar 6th Main Road ,Kannabiran Kovil Street , Srinivasa perumal Kovil Street , Kandhasamy Kovil Street, Kumaran Street ,T.H Road ,EVR Salai,MK Ponnan Street,Ambedkar Street(Erukkanchery) ,Anna Salai Cross Street in Div -35, Unit-09,Zone-04.",Own Sources,4,2018-19,2018-19 ND/2018-19/9746,Storm Water Drain,Completed,ND-TONDIARPET,35,1319000,"Improvements and Repair SWD Vadiudaiyamman Koil St.,Teachers Colony 7th St.,Teachers Colony Main Road.,Abirami Avenue 6th St., KKD Nagar 5th Block 5th St., KKD Nagar 3rd St., Muthamil Nagar 5th Main Road.,Thiruvalluvar Salai,Cavery Salai,Union Salai,Sidco Nagar 1st,2nd,3rd Main Roads and Kamaraj Salai in Dn.35, unit-09,Zone-04.",Own Sources,4,2018-19,2018-19 BR/2018-19/1165,Roads,Completed,BR-Bus Route Roads,36,758000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 4 against the challan no 07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017 , DT: 21.07.2017 and Deposit code 57/0666/2017-18.",Deposit Works,4,2018-19,2019-20 BR/2018-19/1170,Roads,Completed,BR-Bus Route Roads,36,746000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 4 against the challan no 07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017 and Deposit code 57/0666/2017-18.",Deposit Works,4,2018-19,2019-20 BR/2018-19/13082,Roads,Completed,BR-Bus Route Roads,36,65600,"Restoration of roadcut restoration by CMWSSB at Ethiraj samy salai in Zone-4,against challan no:BR/2018-19/0014816.",Deposit Works,4,2018-19,2019-20 D/2018-19/14908,Storm Water Drain,Completed,D-Storm Water Drains,36,36600000,"Demolition and Re-Construction of Storm Water Drain of size 0.90x0.90m at (from E.H. Road to MKB nagar 13th Cross Street) on north side from Indian Petrol Pump to Sri Vijaya Laxmi Bakery(Left and Right Side) in Dn.-36,Zone-4,Package - 1.",SMART CITY - SWD,4,2018-19,2020-21 D/2018-19/9913,Storm Water Drain,Completed,D-Storm Water Drains,36,33504000,"Construction of Storm Water Drain at Thiruvalluvar nagar 3 rd main road on South side and 6 other roads in Zone - 4, Package - 11",Grants,4,2018-19,2020-21 ND/2018-19/12318,Playfields,Completed,ND-TONDIARPET,36,375000,Improvement to Play Field at SA Colony 3rd Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2020-21 ND/2018-19/14053,Parks,Completed,ND-TONDIARPET,36,739000,"Maintenance of park at Bharathi nagar V street, Vasugi nagar, M.R nagar park in division-36, Unit-09, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14054,Parks,Completed,ND-TONDIARPET,36,236000,"Maintenance of park at Indira Nagar, E.H road in division-36, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14060,Parks,Completed,ND-TONDIARPET,36,375000,"Maintenance of park at Sharma Nagar 1st main road, 14th west cross (MKB nagar ) street in division-36, Unit-09, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14061,Parks,Completed,ND-TONDIARPET,36,214000,"Maintenance of park at Sharma nagar 3rd main road in division-36, Unit-9, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14217,Buildings,Completed,ND-TONDIARPET,36,273000,Improvement work Amma Unavagam at Sastri Nagar in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/14218,Buildings,Completed,ND-TONDIARPET,36,205000,Improvement work Amma Unavagam at Suzhlpunal Karai in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2343,Roads,Completed,ND-TONDIARPET,36,4500,ATTENDING PATCH WORK BT ROAD AT TVK 2ND LINK ROAD IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2344,Roads,Completed,ND-TONDIARPET,36,4500,ATTENDING PATCH WORK BT ROAD AT MR NAGAR 3RD MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2346,Roads,Completed,ND-TONDIARPET,36,2350,ATTENDING PATCH WORK BT ROAD AT MR NAGAR 2ND CROSS STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2347,Roads,Completed,ND-TONDIARPET,36,3800,ATTENDING PATCH WORK BT ROAD AT VASUGI NAGAR 1ST STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2348,Roads,Completed,ND-TONDIARPET,36,1100,ATTENDING PATCH WORK BT ROAD AT MR NAGAR 1ST CROSS STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2349,Roads,Completed,ND-TONDIARPET,36,3000,ATTENDING PATCH WORK BT ROAD AT VASUGI NAGAR 1ST MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2350,Roads,Completed,ND-TONDIARPET,36,13600,ATTENDING PATCH WORK BT ROAD AT VV GIRI STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2352,Roads,Completed,ND-TONDIARPET,36,6200,ATTENDING PATCH WORK BT ROAD AT GANDHI STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2353,Roads,Completed,ND-TONDIARPET,36,10200,ATTENDING PATCH WORK BT ROAD AT APPER STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2354,Roads,Completed,ND-TONDIARPET,36,9100,ATTENDING PATCH WORK BT ROAD AT BHARATHIYAR STREET EXTENSION IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2355,Roads,Completed,ND-TONDIARPET,36,2500,ATTENDING PATCH WORK BT ROAD AT BHARATHIYAR STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2356,Roads,Completed,ND-TONDIARPET,36,4700,ATTENDING PATCH WORK BT ROAD AT TVK 1ST LINK ROAD IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2357,Roads,Completed,ND-TONDIARPET,36,8000,ATTENDING PATCH WORK BT ROAD AT TV NAGAR 9TH MAIN ROAD IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2358,Roads,Completed,ND-TONDIARPET,36,4500,ATTENDING PATCH WORK BT ROAD AT TV NAGAR 17TH CROSS STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2359,Roads,Completed,ND-TONDIARPET,36,12700,ATTENDING PATCH WORK BT ROAD AT PARK STREET IN DN-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/2360,Roads,Completed,ND-TONDIARPET,36,923000,Relaying BT Road at Rajiv Gandhi Nagar Main Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2361,Roads,Completed,ND-TONDIARPET,36,694000,Relaying BT Road at Tholkapier Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2362,Roads,Completed,ND-TONDIARPET,36,1779000,Relaying BT Road at Viveakananda Nagar 2nd Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2363,Roads,Completed,ND-TONDIARPET,36,369000,Relaying BT Road at Sastri Nagar Quide Millat Road in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2364,Roads,Completed,ND-TONDIARPET,36,2168000,Relaying BT Road at Sharmanagar 3rd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2365,Roads,Completed,ND-TONDIARPET,36,400000,Relaying BT Road at TV Nagar 9th Main Road in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2366,Roads,Completed,ND-TONDIARPET,36,230000,Relaying BT Road at Sastri Nagar Anna Salai in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2367,Roads,Completed,ND-TONDIARPET,36,444000,Relaying BT Road at T.V Nagar 8th Main Road Lane in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2368,Roads,Completed,ND-TONDIARPET,36,3337000,Relaying BT Road at T.V.K 2nd Link Road in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2369,Roads,Completed,ND-TONDIARPET,36,724000,Relaying BT Road at Vasugi Nagar 1st Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2370,Roads,Completed,ND-TONDIARPET,36,579000,Relaying BT Road at Vasugi Nagar 2nd Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2371,Roads,Completed,ND-TONDIARPET,36,579000,Relaying BT Road at Vasugi Nagar 3rd Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2372,Roads,Completed,ND-TONDIARPET,36,610000,Relaying BT Road at Vasugi Nagar 4th Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2373,Roads,Completed,ND-TONDIARPET,36,420000,Relaying BT Road at Vasugi Nagar 5th Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2374,Roads,Completed,ND-TONDIARPET,36,556000,Relaying BT Road at Vasugi Nagar 6th Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2375,Roads,Completed,ND-TONDIARPET,36,556000,Relaying BT Road at Vasugi Nagar 7th Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2376,Roads,Completed,ND-TONDIARPET,36,2224000,Relaying BT Road at MR Nagar 2nd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2377,Roads,Completed,ND-TONDIARPET,36,466000,Relaying BT Road at Nakeeren Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2378,Roads,Completed,ND-TONDIARPET,36,1300000,Relaying BT Road at Bharathiyar Street Extension in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2379,Roads,Completed,ND-TONDIARPET,36,417000,Relaying BT Road at T.V Nagar 8th Main Road Cross Lane in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/2531,Buildings,Completed,ND-TONDIARPET,36,159000,Demolition for Existing UPHC Building at SA Colony 8th Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/3097,Buildings,Completed,ND-TONDIARPET,36,305000,Improvement work For Multipurpose Hall at Bharathi Nagar East Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/5386,Storm Water Drain,Completed,ND-TONDIARPET,36,270000,Improvement Storm Water Drain (Damaged Manhole Covers Replacing) at Various Location in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 ND/2018-19/5893,Storm Water Drain,Completed,ND-TONDIARPET,36,975000,"Repairing of Damaged Storm Water Drain at Ponnusamy nagar and Rizwan salai junction in Div-34, U-09, Z-IV.",Own Sources,4,2018-19,2018-19 ND/2018-19/6870,Roads,Completed,ND-TONDIARPET,36,2904000,Relaying Cement Concrete Road at Apper Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6871,Roads,Completed,ND-TONDIARPET,36,2128000,Relaying Cement Concrete Road at Thirugnana Sambandar Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6874,Roads,Completed,ND-TONDIARPET,36,715000,Relaying Cement Concrete Road at Jeevanandam Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6875,Roads,Completed,ND-TONDIARPET,36,1932000,Relaying Cement Concrete Road at Bharathi Nagar East Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6878,Roads,Completed,ND-TONDIARPET,36,557000,Relaying Cement Concrete Road at T.v.k 3rd Link Road in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6879,Roads,Completed,ND-TONDIARPET,36,3600000,Relaying Cement Concrete Road at SA Colony 1st Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6882,Roads,Completed,ND-TONDIARPET,36,3420000,Relaying Cement Concrete Road at SA Colony 5th Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6885,Roads,Completed,ND-TONDIARPET,36,790000,Relaying Cement Concrete Road at T.V Nagar 10th Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/6890,Roads,Completed,ND-TONDIARPET,36,960000,Relaying Cement Concrete Road at Kalidhasan Street in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2019-20 ND/2018-19/7213,Storm Water Drain,Completed,ND-TONDIARPET,36,785000,Desilting and Minor Repair Work of SWD at Various Location in Dn-36 U-09 Z-04,Own Sources,4,2018-19,2018-19 B/2018-19/3812,Buildings,Completed,B-Buildings,37,7912997,"PROPOSED CONSTRUCTION OF NIGHT SHELTER AT KODUNGAIYUR (OPPOSITE TO DUMPING YARD KODUNGAIYUR HIGHWAY) IN DN-37, Z-4",Own Sources,4,2018-19,2020-21 BR/2018-19/16270,Road Cut,Completed,BR-Bus Route Roads,37,390000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT CENTRAL AVENUE ROAD IN DIV-37 ZONE-4 against Challan No : BR/2018-19/0020376,Deposit Works,4,2018-19,2019-20 BR/2018-19/17464,Roads,Completed,BR-Bus Route Roads,37,303000,Attending Patch Work to Various Bus Route Roads in Zone-4,Own Sources,4,2018-19,2019-20 BR/2018-19/2926,Roads,Completed,BR-Bus Route Roads,37,2400000,"Traffic Improvement Works at Various Bus Route Roads in Zone - IV, V & VI",Own Sources,4,2018-19,2020-21 BR/2018-19/3141,Roads,Completed,BR-Bus Route Roads,37,580000,"Replacing the roof damaged damaged Modern Stainless Steel Bus shelter sheets in New secretariate bus shelter (1 no), Sharma nagar bus shelters(2 nos), Thalankuppam (1 no) bus shelter, fixing sign board at Ethiraj salai Gantry, Name board at Gandhi - Irwin Road, Prakasam salai roof top replacing and refixing and rectification of Chairs at Tondiarpet post office in various zones in North Region.",Own Sources,4,2018-19,2019-20 BR/2018-19/9753,Roads,Completed,BR-Bus Route Roads,37,1150000,"Attending OFC patches at MH Road,Tondiarpet High Road Nedunchezian St, Moorthingar St, Meenambal Salai in Dn- in ZoneI to V",Own Sources,4,2018-19,2019-20 D/2018-19/14909,Storm Water Drain,Completed,D-Storm Water Drains,37,27590000,"Demolition and Re-Construction of Storm Water Drain of size 900 x 900 mm along Ramakrishnan Street and MKB nagar 4th street in Dn.-37,Zone-4,Package - 2.",SMART CITY - SWD,4,2018-19,2020-21 D/2018-19/9910,Storm Water Drain,Completed,D-Storm Water Drains,37,57421000,"Construction of Storm Water Drain at Sathyamoorthy nagar main road in Zone - 4, Package - 8",Grants,4,2018-19,2020-21 D/2018-19/9914,Storm Water Drain,Completed,D-Storm Water Drains,37,29876000,"Construction of Storm Water Drain at Lube plant road on West side and 5 other roads in Zone - 4, Package -12",Grants,4,2018-19,2019-20 D/2018-19/9916,Storm Water Drain,Completed,D-Storm Water Drains,37,43595000,"Construction of Storm Water Drain at Satyamurty Nagar main road on North side and 5 other roads in Zone - 4, Package14",Grants,4,2018-19,2020-21 L/2018-19/0072,Electrical,Completed,L-Electrical,37,14973700,"Supply, Installation, Aiming, Testing and Commissioning of 5 Nos of 30 mtr high mast with 15 Nos of 240 to 300w LED fitting at Kodungaiyur Dumping Yard (Gate 1and 2) in Division 37,Zone IV",Own Sources,4,2018-19,2019-20 L/2018-19/4827,Electrical,Completed,L-Electrical,37,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at S M Nagar Main Road Health Post in Div 37, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4831,Electrical,Completed,L-Electrical,37,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 4th Cross Street M K B Nagar CPS in Div 37, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4835,Electrical,Completed,L-Electrical,37,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at K K D Nagar 10th main road CPS in Div 37, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4840,Electrical,Completed,L-Electrical,37,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at R R Nagar 3rd main road CPS in Div 37, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4845,Electrical,Completed,L-Electrical,37,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 4th Cross Street M K B Nagar Anganwadi in Div 37, Zone- IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4848,Electrical,Completed,L-Electrical,37,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 7th Block K K D Nagar Anganwadi in Div 37, Zone- IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4851,Electrical,Completed,L-Electrical,37,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at S M Nagar main road Community Centre in Div 37, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4859,Electrical,Completed,L-Electrical,37,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 14th Central Cross Street M K B Nagar Dispensary in Div 37, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4861,Electrical,Completed,L-Electrical,37,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 4th Cross Street M K B Nagar Ward Office in Div 37, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/10940,Playfields,Completed,ND-TONDIARPET,37,403000,"Improvement at Playground and gym building at srinivasan street in DN-37,Unit-09, Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/12944,Storm Water Drain,Completed,ND-TONDIARPET,37,676000,"DESILTING OF STORM WATER DRAIN PACAGE NO.2 IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/12946,Storm Water Drain,Completed,ND-TONDIARPET,37,675000,"DESILTING OF STORM WATER DRAIN PACAGE NO.3 IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/14063,Parks,Completed,ND-TONDIARPET,37,1265000,"Maintenance of park at Mullai Nagar in division-37, Unit-09, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14102,Playfields,Completed,ND-TONDIARPET,37,3387000,"Improvement work of Mullai Nagar Football ground at S.M.Nagar Main road in Div-37,Unit-09,Zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/14107,Buildings,Completed,ND-TONDIARPET,37,1247000,"CONSTRUCTION OF NEW COMPOUND WALL IN NORTH AVENUE VACANT LAND IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2020-21 ND/2018-19/14111,Parks,Completed,ND-TONDIARPET,37,205000,"Maintenance of park at Kannadasan Nagar 7th block in division-37, Unit-9, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14135,Buildings,Completed,ND-TONDIARPET,37,800000,"Improvements to amma unavagam at KKD Nagar 7th Block in DN-37,U-09,Z-04",Own Sources,4,2018-19,2020-21 ND/2018-19/14162,Buildings,Completed,ND-TONDIARPET,37,275000,"IMPROVEMENTS TO AMMA UNAVAGAM AT MKB NAGAR 3RD MAIN ROAD IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2020-21 ND/2018-19/18293,Buildings,Completed,ND-TONDIARPET,37,194000,"INSTALLATION OF NAME BOARD AT KODUNGAIYUR DUMPING GROUND IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2021-22 ND/2018-19/1962,Roads,Completed,ND-TONDIARPET,37,15000,"ATTENDING PATCH WORK AT EASWARAN STREET IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/1964,Roads,Completed,ND-TONDIARPET,37,15000,"ATTENDING PATCH WORK AT RAMAKRISHNA STREET IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/1988,Roads,Completed,ND-TONDIARPET,37,13000,ATTENDING PATCH WORK AT MKB NAGAR 10TH STREET,Own Sources,4,2018-19,2018-19 ND/2018-19/1991,Roads,Completed,ND-TONDIARPET,37,45000,"ATTENDING PATCH WORK AT MKB NAGAR 3RD MAIN ROAD IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/1996,Roads,Completed,ND-TONDIARPET,37,19000,"ATTENDING PATCH WORK AT MKB NAGAR 4TH CROSS STREET IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/2002,Roads,Completed,ND-TONDIARPET,37,23000,ATTENDING PATCH WORK AT MKB NAGAR 4TH MAIN ROAD,Own Sources,4,2018-19,2018-19 ND/2018-19/2004,Roads,Completed,ND-TONDIARPET,37,13000,"ATTENDING PATCH WORK AT MANALI SALAI IN DN 37 , UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/2025,Roads,Completed,ND-TONDIARPET,37,4717000,"Relaying of BT roads at JJ Nagar main road in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2027,Roads,Completed,ND-TONDIARPET,37,1539000,"Forming and laying of BT road at MKB Nagar 4th link road in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2031,Roads,Completed,ND-TONDIARPET,37,198400,"Relaying of BT roads at MKB Nagar 1st Link Road in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2039,Roads,Completed,ND-TONDIARPET,37,3427000,"Relaying of CC roads at RR Nagar 5th Street E Block in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2041,Roads,Completed,ND-TONDIARPET,37,4575000,"Relaying of CC roads at RR Nagar 4Th Street in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2043,Roads,Completed,ND-TONDIARPET,37,1414000,"Relaying of CC roads at Balaji Street in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2044,Roads,Completed,ND-TONDIARPET,37,865000,"Relaying of CC roads at Annai sandhya nagar in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2049,Roads,Completed,ND-TONDIARPET,37,3598000,"Relaying of CC roads at Damodaran nagar 1st main road in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2051,Roads,Completed,ND-TONDIARPET,37,377000,"Relaying of CC roads at KSS Madam 4th Street in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2052,Roads,Completed,ND-TONDIARPET,37,2556000,"Relaying of CC roads at KKD Nagar 7th Block 1st Cross st in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2486,Buildings,Completed,ND-TONDIARPET,37,650000,"IMPROVEMENTS TO MULLAI NAGAR FOOTBALL GROUND AT SM NAGAR MAIN ROAD IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/3712,Parks,Completed,ND-TONDIARPET,37,458000,"Improvement work at Lingesan street park in Dn-37,U-09,Z-04",Own Sources,4,2018-19,2020-21 ND/2018-19/4075,Buildings,Completed,ND-TONDIARPET,37,430000,"Repairs and Improvements work at 18th central cross GYM in DN-37,UNIT-09,ZONE-04",Own Sources,4,2018-19,2018-19 ND/2018-19/4110,Buildings,Completed,ND-TONDIARPET,37,1995000,"Repairs and Improvement work at TH Road in Kodungaiyur Dumping ground in DN-37,UNIT-09,ZONE-04",Own Sources,4,2018-19,2018-19 ND/2018-19/5366,Storm Water Drain,Completed,ND-TONDIARPET,37,291000,"ATTENDING MINOR REPAIR WORKS FOR STORM WATER DRAIN AT VARIOUS STREETS IN DN 37, UNIT 9 AND ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/5481,Buildings,Completed,ND-TONDIARPET,37,341000,"CONSTRUCTION OF NEW TOILET AT DIVISION OFFICE AT MKB NAGAR 4TH CROSS STREET IN DN 37, UNIT 9 AND ZONE 4",Own Sources,4,2018-19,2018-19 ND/2018-19/6689,Roads,Completed,ND-TONDIARPET,37,2125000,"Relaying of CC roads at JJ nagar 1st Street in dn-37,unit-09,zone-04",Own Sources,4,2018-19,2019-20 ND/2018-19/7030,Buildings,Completed,ND-TONDIARPET,37,327000,"IMPROVEMENT WORKS TO 16TH CEREMONY HALL AT NORTH AVENUE IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2019-20 ND/2018-19/8345,Storm Water Drain,Completed,ND-TONDIARPET,37,675000,"DESILTING OF STORM WATER DRAIN PACAGE NO.1 IN DN 37, UNIT 9, ZONE 4",Own Sources,4,2018-19,2018-19 Q/2018-19/0823,Roads,Completed,Q-Solid Waste Management,37,4950000,"Proposed Construction of Additional Weigh Bridge & Monitoring at Main entrance of Corproation road outside Kodungaiyur Dumping ground in Dn-34, Zone-4",Own Sources,4,2018-19,2019-20 BR/2018-19/15126,Roads,Completed,BR-Bus Route Roads,38,730000,Attending patch work at various roads and providing speed breaker in Manali salai in Zone 4,Own Sources,4,2018-19,2020-21 BR/2018-19/5414,Roads,Completed,BR-Bus Route Roads,38,14584432,"Strengthening and relaying of the existing road along B Canal in Dn-38, Zone 4 (Ezhil Nagar Bridge to IOC Gate) L=1200m",Own Sources,4,2018-19,2020-21 D/2018-19/14910,Storm Water Drain,Completed,D-Storm Water Drains,38,31625000,"Demolition and Re-Construction of Storm Water Drain at Nethaji nagar 2nd street and Nethaji nagar 5th street in Dn.-38,Zone-4,Package - 3.",SMART CITY - SWD,4,2018-19,2020-21 D/2018-19/14911,Storm Water Drain,Completed,D-Storm Water Drains,38,29475000,"Demolition and Re-Construction of Storm Water Drain at Nethaji nagar 3nd street and Nethaji nagar 4th street in Dn.-38,Zone-4,Package - 4.",SMART CITY - SWD,4,2018-19,2019-20 D/2018-19/9911,Storm Water Drain,Completed,D-Storm Water Drains,38,25845000,"Construction of Storm Water Drain at Netaji nagar 1 st street and Kummalamman koil street in Zone - 4, Package - 9",Grants,4,2018-19,2019-20 D/2018-19/9915,Storm Water Drain,Completed,D-Storm Water Drains,38,23361000,"Construction of Storm Water Drain at Nehru Nagar main road 9 th street on South East and Navalar Nagar A street on West sidein Zone - 4, Package - 13",Grants,4,2018-19,2019-20 L/2018-19/13993,Electrical,Completed,L-Electrical,38,196500,"Replacement of 492 Mtrs of 2 x16Sqmm PVC Alu.Cable at Vinobha Nagar 2nd St and 3rd St in Dn:38, Zone IV",Own Sources,4,2018-19,2019-20 L/2018-19/16146,Electrical,Completed,L-Electrical,38,183000,"Replacement of 5 Nos. of Old Damaged Pillar Box by New Pillar Box at Various Location in Dn:38 &43, Zone IV",Own Sources,4,2018-19,2019-20 L/2018-19/4896,Electrical,Completed,L-Electrical,38,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Patel Nagar 4th Street CPS in Div 38, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4898,Electrical,Completed,L-Electrical,38,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Annai Sandhiya Nagar 1st Street Dispensary in Div 38, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4899,Electrical,Completed,L-Electrical,38,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Navalar Nagar A Street Anganwadi in Div 38, Zone- IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4900,Electrical,Completed,L-Electrical,38,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nethaji Nagar 6th Street Anganwadi in Div 38, Zone- IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4903,Electrical,Completed,L-Electrical,38,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at J.E Division Office and C.I Office building at Durgha Devi Nagar 6th Cross St in Dn:38, Zone IV",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/0751,Roads,Completed,ND-TONDIARPET,38,1629000,"Relaying of B.T. Road using Paver Finisher at Nethaji Nagar 6th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/0752,Roads,Completed,ND-TONDIARPET,38,1036000,"Relaying of B.T. Road using Paver Finisher at Nehru Nagar Main Road in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/0754,Roads,Completed,ND-TONDIARPET,38,852000,"Relaying of B.T. Road using Paver Finisher at Nehru Nagar 13th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/0758,Roads,Completed,ND-TONDIARPET,38,201000,"Relaying of B.T. Road using Paver Finisher at Nedunchezhian Nagar Main Road in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/12229,Buildings,Completed,ND-TONDIARPET,38,250000,"Repair Works to Amma Unavagam at Nehru Nagar Main Street in DN-38,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12230,Buildings,Completed,ND-TONDIARPET,38,230000,"Repair Works to Amma Unavagam at New Vinobha Nagar 3rd Street in DN-38,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/13072,Roads,Completed,ND-TONDIARPET,38,998000,"Improvements of road at Ellaya street in Division 38, Unit 10, Zone 4.",Own Sources,4,2018-19,2019-20 ND/2018-19/13870,Parks,Completed,ND-TONDIARPET,38,842000,"Maintenance of park at Patel Nagar in division-38, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13872,Parks,Completed,ND-TONDIARPET,38,648000,"Maintenance of park at Elaya Street OSR (Prince) in division-38, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13876,Parks,Completed,ND-TONDIARPET,38,680000,"Maintenance of park at Nehru Nagar in division-38, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/15860,Parks,Completed,ND-TONDIARPET,38,495000,"Maintenance of park at (Prince phase-II) in division-38,Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/18109,Electrical,Completed,ND-TONDIARPET,38,501860,"Relaying the BT Road using paver finisher at Nethaji Nagar main road in Dn-38,Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/18110,Electrical,Completed,ND-TONDIARPET,38,200415,"Relaying the BT Road using paver finisher at Nehru Nagar 14th Street Extn in Dn-38,Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/18111,Electrical,Completed,ND-TONDIARPET,38,240810,"Relaying the BT Road using paver finisher at Sastiri Nagar main road in Dn-38,Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/18112,Electrical,Completed,ND-TONDIARPET,38,212596,"Relaying the BT Road using paver finisher at Tamilar Nagar main road in Dn-38,Unit-09,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/18113,Roads,Completed,ND-TONDIARPET,38,2251344,"Relaying of B.T. Road using Paver Finisher at Nethaji Nagar 5th Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/18114,Roads,Completed,ND-TONDIARPET,38,531211,"Relaying of B.T. Road using Paver Finisher at Nethaji Nagar 4th Street (PART) in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/18115,Roads,Completed,ND-TONDIARPET,38,538994,"Relaying of B.T. Road using Paver Finisher at Nethaji Nagar3rd (PART) Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/18116,Roads,Completed,ND-TONDIARPET,38,2657058,"Relaying of B.T. Road using Paver Finisher at Nethaji Nagar 2nd Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/18117,Roads,Completed,ND-TONDIARPET,38,2778485,"Relaying of B.T. Road using Paver Finisher at Nethaji Nagar 1ST Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/6487,Playfields,Completed,ND-TONDIARPET,38,58000,"Repairs to Compound wall and Improvements to Playfield at Navalar Nagar A Street in Dn-38, Unit-9, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/7803,Parks,Completed,ND-TONDIARPET,38,78000,"Providing Entrance Gate, Name Board and Repairs to Compound wall for Park at Prince Village-2 (OSR Land) in Dn-38, Unit-10, Zone-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/9602,Storm Water Drain,Completed,ND-TONDIARPET,38,585000,"Desilting and Minor Repairs to Storm Water Drains at Ellaya Street, Ennore High Road, Sundaram Nagar 1st, 3rd, 5th Main road, Vaidhyanathan Street, Nehru Nagar Main Road, Nethaji Nagar 2nd, 3rd, 4th, 5th, Navalar Nagar A Street & Sastri Nagar Main Road in Dn-38, Unit-10, Zone-4.",Own Sources,4,2018-19,2018-19 P/2018-19/4156,Parks,Completed,P-Parks and Playfields,38,3393000,"Providing Packaged Sewage Treatment Plant Capacity of 10 KLD including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at Nehru Nagar Park in Dn-38, Zone - 4",Own Sources,4,2018-19,2020-21 P/2018-19/4157,Parks,Completed,P-Parks and Playfields,38,3393000,"Providing Packaged Sewage Treatment Plant Capacity of 10 KLD including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at Patel Nagar Park in Dn-38, Zone - 4",Own Sources,4,2018-19,2020-21 L/2018-19/13999,Electrical,Completed,L-Electrical,39,193100,"Replacement of 4 Nos.of Old damaged Pillar box by New Pillar box at Various locations in Dn39 & 40, Zone IV",Own Sources,4,2018-19,2019-20 L/2018-19/15837,Electrical,Completed,L-Electrical,39,2694000,"Proposal for Commissioning of 36 Nos.of 8 Mtr Octagonal Street Lamp Post with G.I Double Bracket at Ennore Express Highway at Surya Narayana Street in Ward-39, Zone IV.",Own Sources,4,2018-19,2019-20 L/2018-19/16235,Electrical,Completed,L-Electrical,39,192400,"Replacement of Old Cable by 594 Mtrs of New 2 x16 Sqmm PVC Alu.Cable at Kannupillai Street, Cherian Nagar Main St and Deisya Nagar 4th St in Dn:39, Zone IV",Own Sources,4,2018-19,2019-20 L/2018-19/4906,Electrical,Completed,L-Electrical,39,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Cheriyan Nagar CHS in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4907,Electrical,Completed,L-Electrical,39,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ponnusamy Street CPS in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4909,Electrical,Completed,L-Electrical,39,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at No.731, T.H Road CPS in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5037,Electrical,Completed,L-Electrical,39,2947200,"Re-Electrification of 4 School Buildings and Provision of Tube Light,Fan,Plug point,etc in Greater Chennai Primary School, Chennai Middle School,Chennai High School ,Chennai Higher Secondary Schools in Divisions 38,39,43 , Zone IV.",Own Sources,4,2018-19,2019-20 L/2018-19/5065,Electrical,Completed,L-Electrical,39,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Irrusappa Street CPS in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5066,Electrical,Completed,L-Electrical,39,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Cheriyan Nagar Main Road Ward Office in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5067,Electrical,Completed,L-Electrical,39,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Cheriyan Nagar 4th Street Health Post in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5068,Electrical,Completed,L-Electrical,39,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at A E Koil Street 16th Day Ceremony Hall in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5074,Electrical,Completed,L-Electrical,39,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Cheriyan Nagar CPS in Div 39, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/11826,Buildings,Completed,ND-TONDIARPET,39,2999000,"Construction of shed For Dhobikhana at Putchammal Street in DN-39,U-10,Z-04",MLACDS,4,2018-19,2019-20 ND/2018-19/12234,Buildings,Completed,ND-TONDIARPET,39,509000,"Repair Work to Amma Unavagam at Vasar Varathappa Street in DN-39,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12235,Buildings,Completed,ND-TONDIARPET,39,134000,"Repair Work to Amma Unavagam at Kannu Street in DN-39,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12649,Buildings,Completed,ND-TONDIARPET,39,243000,"Construction of baby toilet for Anganwadi at Cheriyan Nagar ICDS IN DN-43,U-10,Z-04",MLACDS,4,2018-19,2018-19 ND/2018-19/12650,Buildings,Completed,ND-TONDIARPET,39,247000,"Construction of baby toilet for Anganwadi at Dhanapal Nagar ICDS IN DN-39,U-10,Z-04",MLACDS,4,2018-19,2018-19 ND/2018-19/12651,Buildings,Completed,ND-TONDIARPET,39,275000,"Construction of baby toilet for Anganwadi at Irusappa Street ICDS IN DN-43,U-10,Z-04",MLACDS,4,2018-19,2018-19 ND/2018-19/12652,Buildings,Completed,ND-TONDIARPET,39,475000,"Construction of RCC Sump and Water Supply Arrangement to ICDS at 731,T.H Road in DN-39,U-10,Z-04",MLACDS,4,2018-19,2018-19 ND/2018-19/13429,Road Cut,Completed,ND-TONDIARPET,39,238000,"Restoration of Roadcut at Veeragavan Street in DN-39,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/15686,Buildings,Completed,ND-TONDIARPET,39,908000,"Repair and Improvement to CHSS(Main Building) at 731,T.H Road in DN-39,U-10,-04",Own Sources,4,2018-19,2019-20 ND/2018-19/4659,Buildings,Completed,ND-TONDIARPET,39,998000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period at A.E.Koil Street Dn 39, UNIT-10- Zone -4.",Own Sources,4,2018-19,2019-20 ND/2018-19/9733,Storm Water Drain,Completed,ND-TONDIARPET,39,281000,"DEsilting and Minor Repairs Work at Cheriyan Nagar Main Street,Kannu Street,Veeraraghavan Street,AE Koil Street,TH Road,Avoor Muthaiyah Street and Market Form 4th Lane,Market Form 8th Lane IN DN-39,U-10,Z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/9736,Storm Water Drain,Completed,ND-TONDIARPET,39,559800,"Desilting and Minor Repairs to SWD at Rathinasabapathy Street,Seniamman Koil Street,Kailasam Street,Rettaikuzhi Street,TH Road,Kothandaraman Street,Arani Rangan Street,Veerakutty Street,MCM Garden 1st Street,MCM Garden 2nd Street,MCM Garden 3rd Street in DN-42,U-10,Z-04",Own Sources,4,2018-19,2018-19 D/2018-19/14912,Storm Water Drain,Completed,D-Storm Water Drains,40,30490000,"Demolition and Re-Construction of Storm Water Drain of size 900x1200mm along VOC nagar senniamman koil street and Kailasam street in Dn.-40,Zone-4,Package - 5.",SMART CITY - SWD,4,2018-19,2020-21 D/2018-19/9909,Storm Water Drain,Completed,D-Storm Water Drains,40,68498000,"Construction of Storm Water Drain at Thiruvalluvar Nagar main road, Senniamman koil street and 2 other roads in Zone - 4, Package - 7",Grants,4,2018-19,2019-20 L/2018-19/5069,Electrical,Completed,L-Electrical,40,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kamaraj Salai G P N Colony CMS in Div 40, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5070,Electrical,Completed,L-Electrical,40,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Thiruvalluvar Nagar CPS in Div 40, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5071,Electrical,Completed,L-Electrical,40,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at A A Garden, Division Office in Div 40, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5073,Electrical,Completed,L-Electrical,40,462400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chelliamman Koil Street, Health Post in Div 40, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/12143,Storm Water Drain,Completed,ND-TONDIARPET,40,348000,"Repairs and improvements work to swd located at various street in division-40,unit-10,zone-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/12213,Buildings,Completed,ND-TONDIARPET,40,258000,"Repairs and improvement works to amma unavagam located at Mangammal thottam in Division-40, Unit-10, Zone-4.",Own Sources,4,2018-19,2021-22 ND/2018-19/12214,Buildings,Completed,ND-TONDIARPET,40,258000,"Repairs and improvement works to amma unavagam located at Keerai thottam in Division-40, Unit-10, Zone-4.",Own Sources,4,2018-19,2021-22 ND/2018-19/12894,Buildings,Completed,ND-TONDIARPET,40,2200000,"Construction of PC Periyar Park at A,E Koil Street in DN-40,U-10,Z-04",MLACDS,4,2018-19,2019-20 ND/2018-19/13564,Parks,Completed,ND-TONDIARPET,40,264000,"Maintenance of Thanthai periyar park in division-40, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13568,Parks,Completed,ND-TONDIARPET,40,812000,"Maintenance of park at cross road osr (Brindavan) in division-40, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13611,Parks,Completed,ND-TONDIARPET,40,873000,"Maintenance of Elaya street OSR (Emmar) Park in division-40, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13612,Parks,Completed,ND-TONDIARPET,40,386000,"Maintenance of Thiruvalluvar Nagar park in division-40, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/15570,Parks,Completed,ND-TONDIARPET,40,407205,"Maintenance of park at Tsunami Quarters (B Block & M Block) in division-40, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/2836,Parks,Completed,ND-TONDIARPET,40,245500,"Maintenance Of Thiruvalluvar Park at Thiruvalluvar Nagar in Dn-40,Unit-10,Zone-04.(For 6 Month)",Own Sources,4,2018-19,2018-19 ND/2018-19/2837,Parks,Completed,ND-TONDIARPET,40,389500,"Maintenance Of Elaya Park at Elaya Street in Dn-40,Unit-10,Zone-04.(For 6 Month)",Own Sources,4,2018-19,2018-19 ND/2018-19/3253,Parks,Completed,ND-TONDIARPET,40,144000,"MAINTENANCE OF THE TSUNAMI QUARTERS (BLOCK-B&M) PARK IN DN-40, U-10,Z-4.(For 6 Month)",Own Sources,4,2018-19,2018-19 BR/2018-19/12876,Roads,Completed,BR-Bus Route Roads,41,540000,"Attending patch work at Moorthinger street, TH Road Stephenson road in various division in Zone 4",Own Sources,4,2018-19,2019-20 BR/2018-19/17465,Roads,Completed,BR-Bus Route Roads,41,364000,Repairs to Bus Shulter in various Bus Route Road in Zone-4,Own Sources,4,2018-19,2019-20 L/2018-19/3303,Electrical,Completed,L-Electrical,41,185000,"Supply and fixing of 100 nos of 4C SMC Fuse Box , 9 Nos of loop Pillar box and 26 nos of breaking of existing pedestal and new construction of pedestal at Various Location in Division 41, Zone IV",Own Sources,4,2018-19,2019-20 L/2018-19/5038,Electrical,Completed,L-Electrical,41,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Sivaji Nagar Amman Koil Street Health Post in Div 41, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5040,Electrical,Completed,L-Electrical,41,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at J J Nagar (K.N.S) Depot J.E Office Building in Div 41, Zone- IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/0762,Roads,Completed,ND-TONDIARPET,41,300000,"Attending Patch work using BC at Thoppai Vinayagar Koil Street in Dn-41, Unit-10, Zone-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0764,Roads,Completed,ND-TONDIARPET,41,432000,"Attending Patch work using BC at Devi Karumari Amman Nagar 1st Main Road in Dn-41, Unit-10, Zone-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0772,Roads,Completed,ND-TONDIARPET,41,504000,"Attending Patch work using BC at Devi Karumari Amman Nagar 2nd Main Road in Dn-41, Unit-10, Zone-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/12892,Buildings,Completed,ND-TONDIARPET,41,2395000,"Construction of Dining hall at chennai corporation primary school at J.J.Nagar B street in division-41,u-10,z-04",MLACDS,4,2018-19,2018-19 ND/2018-19/13555,Parks,Completed,ND-TONDIARPET,41,237000,"Maintenance of park at M.G.R Nagar in division-41, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14018,Parks,Completed,ND-TONDIARPET,41,495000,"Maintenance of park at Krishnan street OSR (RC Appt), Muthamizh Nagar 9th street in division-35, Unit-09, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/4661,Buildings,Completed,ND-TONDIARPET,41,998000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period at JJ Nagar A1 Street in Div - 41, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/5428,Roads,Completed,ND-TONDIARPET,41,2283000,"Relaying of CC Road at Gopal Nagar 1 to 6 Streets in Dn-41, Unit-10, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/9734,Storm Water Drain,Completed,ND-TONDIARPET,41,181900,"Desilting and Minor Repair to SWD at Sivaji nagar main road,kumaran nagar 1st street,Amman koil street,T.V. Nagar 4th street, Kannagi nagar 5th street, Thiruvalluvar salai,Govindasamy nagar 1st street,Vaidhiyanathan service road,Cornation nagar ,Manali salai,E.H. ROAD in DN-41,U-10,Z-04",Own Sources,4,2018-19,2018-19 L/2018-19/3306,Electrical,Completed,L-Electrical,42,176500,"Supply and fixing of 69 nos 4C SMC Fuse Box at various location in division 42 and 23 nos 4C SMC Fuse Box at various location in division 41 and 10 Nos of Loop pillar Box and 40 nos of breaking of existing pedestal and new construction of pedestal at Various Location in Division 42, Zone IV",Own Sources,4,2018-19,2019-20 L/2018-19/5042,Electrical,Completed,L-Electrical,42,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at T H Road (Near Jeeva Park), AD Electrical in Div 42, Zone- IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5044,Electrical,Completed,L-Electrical,42,1666200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 22 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Zonal Office Building in Div 42, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/1020,Buildings,Completed,ND-TONDIARPET,42,2606000,"Relaying of CC Road at Kailasam Street in Dn-42, Unit-10, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/13878,Parks,Completed,ND-TONDIARPET,42,244000,"Maintenance of park at Rettaikuzhi Street in division-42, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13879,Parks,Completed,ND-TONDIARPET,42,897000,"Maintenance of Thiyagaraya park in division-42, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14180,Buildings,Completed,ND-TONDIARPET,42,200000,"IMPROVEMENTS TO AMMA UNAVAGAM AT SENIAMMAN KOIL STREET IN DN-42,U-10,Z-4.",Own Sources,4,2018-19,2020-21 ND/2018-19/1479,Roads,Completed,ND-TONDIARPET,42,461000,"Relaying the CC Road at Perumal Koil Garden lane in Dn-42,Unit-10,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/1487,Roads,Completed,ND-TONDIARPET,42,398500,"Relaying the CC Road at Mayar Basudev 3rd lane in Dn-42,Unit-10,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/17902,Buildings,Completed,ND-TONDIARPET,42,566000,"PROVIDING COMPOUND WALL AND OTHER IMPROVEMENT WORKS TO EXISTING AMMA UNAVAGAM AT THILAGAR NAGAR IN DN-42,U-10,Z-4.",Own Sources,4,2018-19,2020-21 ND/2018-19/18102,Electrical,Completed,ND-TONDIARPET,42,1905000,"Relaying the BT Road at Mayor Basudev Street in Dn-42,Unit-10,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/18103,Electrical,Completed,ND-TONDIARPET,42,874000,"Relaying the BT Road at Rettai kuzhi lane in Dn-42,Unit-10,Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/3617,Buildings,Completed,ND-TONDIARPET,42,797000,"Maintenance of Zonal Office at T.H Road in Dn-42,unit-10,Zone-04.",Own Sources,4,2018-19,2018-19 ND/2018-19/4660,Buildings,Completed,ND-TONDIARPET,42,998000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period at Ellaya Street, Thilagar Nagar in Div - 42, Unit - 10, Zone -4",Own Sources,4,2018-19,2019-20 ND/2018-19/8686,Buildings,Completed,ND-TONDIARPET,42,270000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHSS AT 540,T.H ROAD IN DN-42,U-10,Z-4.",Own Sources,4,2018-19,2018-19 B/2018-19/8748,Buildings,Completed,B-Buildings,43,7240000,"PROPOSED CONSTRUCTION OF NIGHT SHELTER AT C.D HOSPITAL CAMPUS IN, DIV- 43, ZONE -4.",Grants,4,2018-19,2020-21 D/2018-19/9912,Storm Water Drain,Completed,D-Storm Water Drains,43,35945000,"Construction of Storm Water Drain at Kamaraj Salai and S.N Chetty street in Zone - 4, Package - 10.",Grants,4,2018-19,2019-20 L/2018-19/4894,Electrical,Completed,L-Electrical,43,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Adhi Dravidar Salai (Near IDH Hospital Compound)Kasima Nagar 2nd Street Ward Office in Div 43, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5063,Electrical,Completed,L-Electrical,43,7534900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 100 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 187,T H Road, CDH in Div 43, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/6180,Electrical,Completed,L-Electrical,43,143500,"Name of Work:- Smart class ( Six Class rooms) .Additional electrification work for CMS School Chinnandi Madam Div-35 ,CHSS, Patel Nagar, Div- 38 , CHSS School ,No.731, T.H Road, Div-39 ,CHSS School Buddha Street Div-42 , CMS Pudumanai Kuppam Div- 43, CHSS School, Kalyanapuram Div-46 in Zone IV.",Own Sources,4,2018-19,2019-20 ND/2018-19/0902,Buildings,Completed,ND-TONDIARPET,43,666000,"Construction of Store Room and Toilet Block inside Park at CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/12211,Buildings,Completed,ND-TONDIARPET,43,232000,"Repairs Work to Amma Unavagam at Inside CDH Campus in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12217,Buildings,Completed,ND-TONDIARPET,43,160000,"Repairs Work to Amma Unavagam at Pudumanaikuppam Main Street in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12241,Buildings,Completed,ND-TONDIARPET,43,176000,"Repairs Work to Amma Unavagam at M.G.R Nagar in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12331,Buildings,Completed,ND-TONDIARPET,43,993000,"Alteration Work for Medical lab at CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12340,Buildings,Completed,ND-TONDIARPET,43,962000,"Aluminium Window,Flooring,Plumbing and Electrical work for Medical Lab(GF & FF at CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2020-21 ND/2018-19/12371,Buildings,Completed,ND-TONDIARPET,43,471000,"Dhobikhana Convert to Class Room at CDH Main Building in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/12589,Buildings,Completed,ND-TONDIARPET,43,500000,"Providing and Fixing RO plant at CMS Pudumanaikuppam in Div-43, Ut-10, Zn-4",MLACDS,4,2018-19,2018-19 ND/2018-19/12590,Buildings,Completed,ND-TONDIARPET,43,500000,"Providing and Fixing RO plant at CMS Kummalamman Koil Street in Div-43, Ut-10, Zn-4",MLACDS,4,2018-19,2018-19 ND/2018-19/12591,Buildings,Completed,ND-TONDIARPET,43,500000,"Providing and Fixing RO plant at CMS Vinayagapuram in Div-43, Ut-10, Zn-4",MLACDS,4,2018-19,2018-19 ND/2018-19/12644,Buildings,Completed,ND-TONDIARPET,43,488000,"Construction of RCC Sump and Water Supply Arrangement to ICDS at Suriyanarayan Street in DN-43,U-10,Z-04",MLACDS,4,2018-19,2018-19 ND/2018-19/12648,Buildings,Completed,ND-TONDIARPET,43,243000,"Construction of baby toilet for Anganwadi at Pudumanaikuppam ICDS IN DN-43,U-10,Z-04",MLACDS,4,2018-19,2018-19 ND/2018-19/13687,Buildings,Completed,ND-TONDIARPET,43,300000,"Installation of Bio Shredding Machine (Vegetable Cutter) for Bio Gas Plant at Communicable Disease Hospital in Division - 43, Unit - 10, Zone IV",Own Sources,4,2018-19,2019-20 ND/2018-19/13881,Parks,Completed,ND-TONDIARPET,43,1120000,"Maintenance of park at C D HOSPITAL & Opp Main Building park in division-43, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13885,Parks,Completed,ND-TONDIARPET,43,309000,"Maintenance of park at Kasimedu burial ground in division-43, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13886,Parks,Completed,ND-TONDIARPET,43,220000,"Maintenance of park at s.n chetty street in division-43, Unit-10, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13889,Roads,Completed,ND-TONDIARPET,43,585000,"laying the BT Road at Burial Ground Road in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/13891,Roads,Completed,ND-TONDIARPET,43,488000,"laying the BT Road at CDH inside in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/14165,Buildings,Completed,ND-TONDIARPET,43,687000,"Operation and maintenance of RO Plant ( 3rd Year 2018-19) at T.H Road inside the CDH Compus inDN-43,U-10,Z-04",Own Sources,4,2018-19,2020-21 ND/2018-19/14368,Buildings,Completed,ND-TONDIARPET,43,892000,"Alteration work For Old Ward :4 at CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2020-21 ND/2018-19/14377,Buildings,Completed,ND-TONDIARPET,43,614000,"Electrical , Plumbing Work and Addition Toilet Block,Partition, at Old ward:4 inside CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2020-21 ND/2018-19/14562,Buildings,Completed,ND-TONDIARPET,43,671000,"Improvement to the Staff Quarters at CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/18187,Buildings,Completed,ND-TONDIARPET,43,500000,"Providing and Fixing RO plant at Annai Santhiya Nagar UPHC in Div-38, Ut-09, Zn-4",MLACDS,4,2018-19,2019-20 ND/2018-19/2472,Parks,Completed,ND-TONDIARPET,43,250000,"Greenary Arrangement at CDH Main Building and Park in DN-43,U-10,Z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/2562,Buildings,Completed,ND-TONDIARPET,43,212000,"Improvement to the PC at Singaravelan Nagar in DN-43,U-10,Z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/3874,Buildings,Completed,ND-TONDIARPET,43,734000,"Dismantling and Reconstruction of Compound wall at CDH (South side) in DN-43,U-10,Z-04(Lenth-25m)",Own Sources,4,2018-19,2018-19 ND/2018-19/3879,Roads,Completed,ND-TONDIARPET,43,979000,"Relaying of BT Road using Paver Finisher Street at Kanakkar Street in Dn-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/3896,Roads,Completed,ND-TONDIARPET,43,1193000,"Name of Work: Relaying of B.T.Road using Paver finisher at Pillaiyar Koil Street in Dn-43, Unit-10, Zone-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/4438,Buildings,Completed,ND-TONDIARPET,43,565000,"Improvement to the old E.B Room at CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/5313,Parks,Completed,ND-TONDIARPET,43,121000,"Repairs to Compound wall For Park at S.N.Chetty Street in Dn-43, Unit-10, Zone-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/6140,Buildings,Completed,ND-TONDIARPET,43,456000,"Construction of Toilet Block For Anbagam Block at CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/6142,Buildings,Completed,ND-TONDIARPET,43,337000,"Water Arrangement to the CDH in DN-43,U-10,Z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/9660,Storm Water Drain,Completed,ND-TONDIARPET,43,232000,"Desilting of SWD at Suriyanarayan Street East,West Side , Jeevarathinam Salai,New Amarajipuram, in DN-43,U-10,Z-04",Own Sources,4,2018-19,2018-19 BR/2018-19/3405,Roads,Completed,BR-Bus Route Roads,44,37000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 4 against the challan no 07/2017-18/0377458,07/2017-18/0377463 DT: 21.07.2017 and Deposit code 57/0668/2017-18.",Deposit Works,4,2018-19,2019-20 BR/2018-19/7355,Roads,Completed,BR-Bus Route Roads,44,54000,Roadcut restoration made by CMWSSB at Melpatti Ponnappan street in zone-4 against challan no BR/2017-18/0028747,Deposit Works,4,2018-19,2019-20 L/2018-19/4819,Electrical,Completed,L-Electrical,44,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nattal Garden 2nd Street Ward Office in Div 44, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4820,Electrical,Completed,L-Electrical,44,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Kamaraj Nagar CMS in Div 44, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/0228,Buildings,Completed,ND-TONDIARPET,44,317000,"Improvement to Health Post at Kamaraj Nagar 2nd Street in Dn-44, Unit-11, Zone-04.",Own Sources,4,2018-19,2019-20 ND/2018-19/0792,Roads,Completed,ND-TONDIARPET,44,105000,"INTERIOR ROAD PATCH WORK AT AMBEDKAR STREET IN DIVISION-44,UNIT-11, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/0815,Roads,Completed,ND-TONDIARPET,44,72900,"INTERIOR ROAD PATCH WORK AT VEERAPANDI STREET IN DIVISION -44, UNIT-11, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/0820,Roads,Completed,ND-TONDIARPET,44,131000,"INTERIOR ROAD PATCH WORK AT NETHAJI STREET IN DIVISION -44, UNIT-11, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/0834,Roads,Completed,ND-TONDIARPET,44,75000,"INTERIOR ROAD PATCH WORK AT SUBRAMANI MAIN STREET IN DIVISION -44, UNIT-11, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/0835,Roads,Completed,ND-TONDIARPET,44,75000,"INTERIOR ROAD PATCH WORK AT SATHYA BAMA STREET IN DIVISION -44, UNIT-11, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/12697,Buildings,Completed,ND-TONDIARPET,44,150000,"REPAIRS AND IMPROVEMENT WORK TO AMMA UNAVAGAM AT AMMAN KOIL STREET IN DIVISION -44, UNIT-11, ZONE-4.",Own Sources,4,2018-19,2020-21 ND/2018-19/14113,Parks,Completed,ND-TONDIARPET,44,345000,"Maintenance of park at Sathiyavani muthu nagar in division-44, Unit-11, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/3884,Roads,Completed,ND-TONDIARPET,44,1094000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT KANDAN STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3888,Roads,Completed,ND-TONDIARPET,44,2412000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT MANIKKA VINAYAGAR KOIL STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3889,Roads,Completed,ND-TONDIARPET,44,1525000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT MUNIAPPAN STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3890,Roads,Completed,ND-TONDIARPET,44,2412000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT THIRU.VI.KA STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3891,Roads,Completed,ND-TONDIARPET,44,1481000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT PALANI ANDAVAR STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3893,Roads,Completed,ND-TONDIARPET,44,822000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT VOC STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3894,Roads,Completed,ND-TONDIARPET,44,1232000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT SUBRAMANI STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3897,Roads,Completed,ND-TONDIARPET,44,1339000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT THIRUPUR KUMARAN STREET STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3899,Roads,Completed,ND-TONDIARPET,44,340000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT BHARATHA MADHA 1ST STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/3900,Roads,Completed,ND-TONDIARPET,44,575000,"REPAIR AND IMPROVEMENT TO B.T ROAD AT AZAD STREET IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/5425,Buildings,Completed,ND-TONDIARPET,44,216000,"REPAIRS AND IMPROVEMENT WORK TO CERMONY HALL AT PALANI ANDAVAR KOIL STREET IN DIVISION -44, UNIT-11, ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/7055,Buildings,Completed,ND-TONDIARPET,44,195000,"REPAIRS AND IMPROVEMENT WORK TO AMMA UNAVAGAM AT M.P.M STREET IN DIVISION -44, UNIT-11, ZONE-4.",Own Sources,4,2018-19,2020-21 ND/2018-19/8617,Storm Water Drain,Completed,ND-TONDIARPET,44,851000,"DESILTING AND MINOR REPAIRS TO THE STORM WATER DRAIN AT VERIOUS STREET(ANNA STREET,KAMARAJ STREET,AMMAN KOIL STREET,RAJAJI STREET,KASTHURIBAI STREET,V.O.C STREET,MANIKKA VINAYAGAR KOIL STREET,ALAGIRYSWAMY 3RD STREET,KATTABOMMAN STREET,MUNIAPPAN STREET,GOPAL STREET,VEERAPANDIAN STREET) IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8623,Storm Water Drain,Completed,ND-TONDIARPET,44,849000,"DESILTING AND MINOR REPAIR WORKS AT VARIOUS STREET(M.P.M STREET,MUTHTAMIZH STREET,PALANIANDAVAR KOIL STREET,MANIMEGALAI STREET,NAGAMMAIYAR STREET,THULASINGAM STREET,THIRUPOUR KUMARAN STREET,THIRU.VI.KA. STREET,MA.PO.SI. STREET,MATHIAZHAGAN STREET,THIRUCHI CHINNA SWAMY STREET,JAWAHAR STREET) IN DN 44,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 BR/2018-19/2853,Footpath,Completed,BR-Bus Route Roads,45,191000,"Footpath Repair works at Dr. Ambedkar college road in Dn-45, Zone-4",Grants,4,2018-19,2018-19 BR/2018-19/7540,Roads,Completed,BR-Bus Route Roads,45,39000,RESTORATION OF ROAD CUT AT AA ROAD MADE BY CMWSSB against challan no:BR/2017-18/0029170 IN ZONE-4.,Deposit Works,4,2018-19,2019-20 BR/2018-19/7541,Roads,Completed,BR-Bus Route Roads,45,38000,RESTORATION OF ROAD CUT RESTORTION AT AMBEDKAR COLLEGE ROAD MADE BY CMWSSB IN ZONE-4 against challan no:BR/2017-18/0029340.,Deposit Works,4,2018-19,2019-20 L/2018-19/4863,Electrical,Completed,L-Electrical,45,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Mayor Krishnamoorthy Nagar Office Building in Div 45, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4889,Electrical,Completed,L-Electrical,45,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dr.Ambedkar College Road, CHS in Div 45, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4891,Electrical,Completed,L-Electrical,45,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ganeshapuram Mayor Krishnamoorthy Nagar Main Road CPS in Div 45, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/4893,Electrical,Completed,L-Electrical,45,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ganeshapuram Main Road, CHS in Div 45, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/0230,Roads,Completed,ND-TONDIARPET,45,185000,"RELAYING B T ROAD WORK AT SRI RAM NAGAR 1ST STREET IN DN-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0263,Roads,Completed,ND-TONDIARPET,45,427000,"RELAYING B T ROAD WORK AT SRI RAM NAGAR 2ND STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0268,Roads,Completed,ND-TONDIARPET,45,599000,"RELAYING B T ROAD WORK AT SRI RAM NAGAR MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0271,Roads,Completed,ND-TONDIARPET,45,369000,"RELAYING BT ROAD WORK AT RATHINAM MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0273,Roads,Completed,ND-TONDIARPET,45,1027000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 1ST STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0274,Roads,Completed,ND-TONDIARPET,45,1224000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 8TH STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0276,Roads,Completed,ND-TONDIARPET,45,743000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 21ST STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0277,Roads,Completed,ND-TONDIARPET,45,664000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 25TH STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0278,Roads,Completed,ND-TONDIARPET,45,493000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 27TH STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0279,Roads,Completed,ND-TONDIARPET,45,440000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 17TH STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0280,Roads,Completed,ND-TONDIARPET,45,2097000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 18TH STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0285,Roads,Completed,ND-TONDIARPET,45,548000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 28TH STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/0287,Roads,Completed,ND-TONDIARPET,45,445000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 31ST STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/16129,Buildings,Completed,ND-TONDIARPET,45,553000,"DEMOLISED BUILDING AT CHENNAI HIGH SCHOOL GANESAPURAM MAIN ROAD IN DIVISION-45, UNIT-11,ZONE-04",Own Sources,4,2018-19,2020-21 ND/2018-19/2878,Parks,Completed,ND-TONDIARPET,45,250000,"Maintainance for Desikanandapuram Park,Vyasar Nagar Park, Kasthuri Bai Gandhi Park (SIX month) In Div-45,Unit-11,Zone-04",Own Sources,4,2018-19,2018-19 ND/2018-19/3043,Buildings,Completed,ND-TONDIARPET,45,771000,"REPAIR AND IMPROVEMENT WORK TO THE LORRY STATION MECHAINC SHET AT B B ROAD IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/3050,Buildings,Completed,ND-TONDIARPET,45,253000,"REPAIR AND IMPROVEMENT WORK AT LORRY DEPO ( GENERETOR ROOM ) AT B B ROAD MAIN ROAD IN DINVISION -45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/3114,Roads,Completed,ND-TONDIARPET,45,822000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 29TH STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/3115,Roads,Completed,ND-TONDIARPET,45,803000,"RELAYING BT ROAD WORK AT BHAKTHAVACHALAM COLONY 23RD STREET IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/3398,Buildings,Completed,ND-TONDIARPET,45,949000,"REPAIR AND IMPROVEMENT WORK CPS AT MAYOR KRISHNA MURTHI NAGAR MAIN ROAD IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/3710,Buildings,Completed,ND-TONDIARPET,45,298000,"REPAIR AND IMPROVEMENT WORK TO THE LORRY DEPO STORE ROOM IN DIVISION -45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/4107,Buildings,Completed,ND-TONDIARPET,45,393000,"REPAIR AND IMPROVEMENT WORK AT MAYOR KRISHNA MURTHY NAGAR MAIN ROAD AMMA UNAVAGAM IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/4109,Buildings,Completed,ND-TONDIARPET,45,172000,"REPAIR AND IMPROVEMENT WORK AT SANJAY NAGAR AMMA UNAVAGAM IN DIVISION-45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/4274,Buildings,Completed,ND-TONDIARPET,45,998000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period in Dr. Ambedkar college road Dn 45, UNIT-11- Zone -4.",Own Sources,4,2018-19,2019-20 ND/2018-19/8217,Storm Water Drain,Completed,ND-TONDIARPET,45,18000,"Desilting of storm water drain at Bakthvatchalam Colony 8th Street in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8218,Storm Water Drain,Completed,ND-TONDIARPET,45,12400,"Desilting of storm water drain at Bakthvatchalam Colony 1st Street in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8219,Storm Water Drain,Completed,ND-TONDIARPET,45,236300,"Minor repairs of storm water drain at Balamurugan Street in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8220,Storm Water Drain,Completed,ND-TONDIARPET,45,45000,"Desilting of storm water drain at BB Road Main road , 1st, 2rd and 3rd Street in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8221,Storm Water Drain,Completed,ND-TONDIARPET,45,26800,"Desilting of storm water drain at Dr. Ambedkar College Road in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8222,Storm Water Drain,Completed,ND-TONDIARPET,45,12200,"Desilting of storm water drain at Ganesapuram Main Road in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8227,Storm Water Drain,Completed,ND-TONDIARPET,45,14500,"Desilting of storm water drain at Grama Ayyavu Street in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8228,Storm Water Drain,Completed,ND-TONDIARPET,45,12400,"Desilting of storm water drain at Kakkanji Colony Main Road in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8229,Storm Water Drain,Completed,ND-TONDIARPET,45,51000,"Desilting of storm water drain at Melapatti Ponappan Street in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8230,Storm Water Drain,Completed,ND-TONDIARPET,45,14500,"Desilting of storm water drain at Murthingar Road in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8232,Storm Water Drain,Completed,ND-TONDIARPET,45,9000,"Desilting of storm water drain at Ratinam Main Road in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8234,Storm Water Drain,Completed,ND-TONDIARPET,45,21000,"Desilting of storm water drain at Shanthi Nagar Main Road in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8235,Storm Water Drain,Completed,ND-TONDIARPET,45,26500,"Desilting of storm water drain at Stephenson Lane in Dn:45,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8237,Storm Water Drain,Completed,ND-TONDIARPET,45,19000,"Desilting of storm water drain at Stephenson Road in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8269,Storm Water Drain,Completed,ND-TONDIARPET,45,18000,"Desilting of storm water drain at Sundaram 3rd Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8270,Storm Water Drain,Completed,ND-TONDIARPET,45,14500,"Desilting of storm water drain at Sundaram Main Road in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8271,Storm Water Drain,Completed,ND-TONDIARPET,45,12500,"Desilting of storm water drain at Vyasar Nagar 1st Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8272,Storm Water Drain,Completed,ND-TONDIARPET,45,4500,"Desilting of storm water drain at Vyasar Nagar 2nd Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8346,Storm Water Drain,Completed,ND-TONDIARPET,45,4500,"Desilting of storm water drain at Vyasar Nagar 3rd Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8348,Storm Water Drain,Completed,ND-TONDIARPET,45,5600,"Desilting of storm water drain at Vyasar Nagar 5th Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8349,Storm Water Drain,Completed,ND-TONDIARPET,45,10000,"Desilting of storm water drain at Vyasar Nagar 6th Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8350,Storm Water Drain,Completed,ND-TONDIARPET,45,10000,"Desilting of storm water drain at Vyasar Nagar 7th Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8351,Storm Water Drain,Completed,ND-TONDIARPET,45,10000,"Desilting of storm water drain at Vyasar Nagar 8th Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8352,Storm Water Drain,Completed,ND-TONDIARPET,45,11200,"Desilting of storm water drain at Vyasar Nagar 1st Cross Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8544,Storm Water Drain,Completed,ND-TONDIARPET,45,476000,"Minor repairs of storm water drain at A A road (behind Stephenson Road ) in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8598,Storm Water Drain,Completed,ND-TONDIARPET,45,106300,"Minor repairs of storm water drain at Annai Sathya nagar Main Road in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8599,Storm Water Drain,Completed,ND-TONDIARPET,45,243000,"Minor repairs of storm water drain at Bakthavatchalam Colony 18th Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8601,Storm Water Drain,Completed,ND-TONDIARPET,45,119000,"Minor repairs of storm water drain at BV Colony Mosque Street in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8604,Storm Water Drain,Completed,ND-TONDIARPET,45,105000,"Minor repairs of storm water drain at Clinic Road in Dn:45,Unit:11,Zone:4",Own Sources,4,2018-19,2018-19 ND/2018-19/8738,Roads,Completed,ND-TONDIARPET,45,1052000,"Restoration Road cut made by CMWSSB at B V colony 23rd street In Division-45,Unit-11,Zone-4",Deposit Works,4,2018-19,2019-20 ND/2018-19/8812,Roads,Completed,ND-TONDIARPET,45,256000,"Restoration Road cut made by CMWSSB at B V colony 8th street In Division-45,Unit-11,Zone-4",Deposit Works,4,2018-19,2019-20 ND/2018-19/8814,Roads,Completed,ND-TONDIARPET,45,1160000,"Restoration of Road cut made by CMWSSB at Mosque street (B V colony 31 th street) In Dn-45,U-11,Z-4",Deposit Works,4,2018-19,2019-20 ND/2018-19/8815,Roads,Completed,ND-TONDIARPET,45,303000,"Restoration of Road cut made by CMWSSB at clinic road ( B V Colony 8th street) In Dn-45,U-11,Z-4",Deposit Works,4,2018-19,2019-20 ND/2018-19/8942,Buildings,Completed,ND-TONDIARPET,45,384000,"REPAIRS AND IMPROVEMENT WORK TO DIVISION OFFICE AT MAY0R KRISHNA MURTHY NAGAR MAIN ROAD IN DIVISION -45, UNIT-11, ZONE-4",Own Sources,4,2018-19,2020-21 BR/2018-19/12875,Roads,Completed,BR-Bus Route Roads,46,944000,"Attending patch work at Kummallamman koil street,Manali High Road, TH Road etc in Dn-41,38 Zone-5",Own Sources,4,2018-19,2019-20 D/2018-19/14913,Storm Water Drain,Completed,D-Storm Water Drains,46,62190000,"Construction of Missing Link Storm Water Drain at Good Shed Road of size 1.20 x 1.30 m in Dn.-46,Zone - 4, Package - 6.",SMART CITY - SWD,4,2018-19,2020-21 ND/2018-19/12136,Buildings,Completed,ND-TONDIARPET,46,242000,"REPAIRS AND IMPROVEMENTS TO ANGANWADI C.NO.33603070121 AT SUNDARA GANDHI PURAM IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2020-21 ND/2018-19/12219,Storm Water Drain,Completed,ND-TONDIARPET,46,130000,"IMPROVEMENTS TO STORM WATER DRAIN GOODS SHED ROAD NEAR GOODS SHED POND IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/12220,Buildings,Completed,ND-TONDIARPET,46,228000,"REPAIRS TO SEPTIC TANK AT GANDHIPURAM PUBLIC CONVENIENCE IN DIVISION 46,UNIT.11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/12370,Buildings,Completed,ND-TONDIARPET,46,45000,"REPAIRS AND IMPROVEMENTS TO GYM BUILDING AT SAMANTHIPOOCOLONY FOOT BALL GROUND IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2020-21 ND/2018-19/12708,Buildings,Completed,ND-TONDIARPET,46,245000,"REPAIRS AND IMPROVEMENTS TO AMMAKUDINEER BUILDING AT 24TH BLOCK IN DIVISION 46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/12792,Buildings,Completed,ND-TONDIARPET,46,1377000,"REPAIRS TO PUBLIC CONVENIENCE AT SAMANTHIPOO COLONY IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2020-21 ND/2018-19/12793,Buildings,Completed,ND-TONDIARPET,46,17500,"REPAIRS TO PUBLIC CONVENIENCE AT KENNEDY NAGAR IN DIVISION 46,UNIT 11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/12795,Buildings,Completed,ND-TONDIARPET,46,21500,"REPAIRS TO PUBLIC CONVENIENCE AT MALLIPOO COLONY IN DIVISION 46,UNIT 11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/12796,Buildings,Completed,ND-TONDIARPET,46,89000,"REPAIRS TO PUBLIC CONVENIENCE AT MOORTHINGAR STREET JN. OF MUTHU STREET IN DIVISION 46,UNIT 11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/12797,Buildings,Completed,ND-TONDIARPET,46,60600,"REPAIRS TO PUBLIC CONVENIENCE AT MOORTHINGAR STREET NEAR WATER FILLING STN. IN DIVISION 46,UNIT 11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/13560,Buildings,Completed,ND-TONDIARPET,46,583000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM BUILDING AT 24 TH,BLOCK,S.M.NAGAR IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14124,Parks,Completed,ND-TONDIARPET,46,231000,"Maintenance of park at Sathyamurthy Nagar in division-46, Unit-11, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14194,Buildings,Completed,ND-TONDIARPET,46,200000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM AT C.KALYANAPURAM,S.M.NAGAR MAIN ROAD IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/14842,Buildings,Completed,ND-TONDIARPET,46,142000,"DISMANTLING THE DAMAGED TOILET BUILDING AT C.KALYANAPURAM ,S.M.NAGAR MAIN ROAD IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/18297,Buildings,Completed,ND-TONDIARPET,46,1988000,"CONSTRUCTION OF P.C. AT C.KALYANAPURAM S.M.NAGAR MAIN ROAD IN DIVISION 46,UNIT 11,ZONE-4",Own Sources,4,2018-19,2020-21 ND/2018-19/2160,Roads,Completed,ND-TONDIARPET,46,217000,"PATCH WORK THE CC ROAD AT A.B KALYANAPURAM MAIN ROAD IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/2162,Roads,Completed,ND-TONDIARPET,46,209000,"PATCH WORK THE B.T ROAD AT JOHN KENNEDY NAGAR IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/2171,Roads,Completed,ND-TONDIARPET,46,71000,"PATCH WORK THE B.T ROAD AT PALLA 2ND STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/2172,Roads,Completed,ND-TONDIARPET,46,71000,"PATCH WORK THE B.T ROAD AT PALLA 3RD STREET IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/2180,Roads,Completed,ND-TONDIARPET,46,61000,"PATCH WORK THE B.T ROAD AT MOORTHINGER STREET IN DN-46,UNIT-11,ZONE-4",Own Sources,4,2018-19,2018-19 ND/2018-19/2424,Roads,Completed,ND-TONDIARPET,46,124000,"RELAYING THE B.T ROAD AT JOHN KENNEDY NAGAR CROSS STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/4270,Buildings,Completed,ND-TONDIARPET,46,96000,"URGENT REPAIR WORK FOR CHENNAI HR SEC SCHOOL AT C KALYANAPURAM IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/4271,Buildings,Completed,ND-TONDIARPET,46,998000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period in S M Nagar 24th block Dn 46, UNIT-11- Zone -4.",Own Sources,4,2018-19,2019-20 ND/2018-19/4272,Buildings,Completed,ND-TONDIARPET,46,47000,"URGENT REPAIR WORK FOR CHENNAI MIDDLE SCHOOL AT MOORTHINGAR STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8661,Storm Water Drain,Completed,ND-TONDIARPET,46,789000,"Desilting of storm water drain at 1,S.M.Nagar main road,2,Moorthingar road,3.Muthu street,4.Palla2 ndstreet,5.Palla 3rd street,6.Palla 4th street,7.John kennedy cross street,8.John kennedy Main road,9.A.B.Kalyanapuram main road,10.C.Kalyanapuram main road,11.Old Goods shed road,12.Mosque road,13.New Goods shed road,14.Gandhipuram,15.Nehru nagar 3rd street,16. Nehru nagar5th street,17.Nehru nagar Main road,18.24 th. block, in Dn:46,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 ND/2018-19/8670,Storm Water Drain,Completed,ND-TONDIARPET,46,477000,"Minor Repairs of storm water drain at various streets in Dn:46,Unit:11,Zone:4.",Own Sources,4,2018-19,2018-19 BR/2018-19/0627,Roads,Completed,BR-Bus Route Roads,47,400000,"Attending patches and pot holes at KH Road korukkupet jn. in Dn-47, Zone 4 (SDRF Fund)",Grants,4,2018-19,2018-19 BR/2018-19/16417,Road Cut,Completed,BR-Bus Route Roads,47,1490000,"ROADCUT RESTORATION AT C.B ROAD IN DN. 47, ZONE - 4 against Challan No : BR/2018-19/0005778",Deposit Works,4,2018-19,2019-20 L/2018-19/5008,Electrical,Completed,L-Electrical,47,3707900,"Electrification of School Building and Provision of Tube Light,Fan,Plug point,etc at various locaion in Division 42,47 & 48 under Washermenpet section in Zone IV.",Own Sources,4,2018-19,2019-20 L/2018-19/5045,Electrical,Completed,L-Electrical,47,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Harinarayanapuram CHSS in Div 47, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5047,Electrical,Completed,L-Electrical,47,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kannan Street CMS in Div 47, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5049,Electrical,Completed,L-Electrical,47,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kannan Street (Rengarajapuram) CMS in Div 47, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5050,Electrical,Completed,L-Electrical,47,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Meenambal Nagar CPS in Div 47, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5051,Electrical,Completed,L-Electrical,47,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Harinarayanapuram CPS in Div 47, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5058,Electrical,Completed,L-Electrical,47,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Meenambal Nagar, OLK Area, Cochrane Basin Rd, Ambedkar Nagar, Govt Maternity Hospital & AYUSH Medical in Div 47, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/10740,Buildings,Completed,ND-TONDIARPET,47,230000,Providing entrance flooring and aluminium partision in CWC at meenambal nagar in ward.47 unit.11 zone.4,Own Sources,4,2018-19,2018-19 ND/2018-19/11442,Buildings,Completed,ND-TONDIARPET,47,2400000,Construction of GYM BUILDING at Meenambal nagar 3rd street in ward.47 unit.11 zone.4 ( Under MLA Scheame ),MLACDS,4,2018-19,2018-19 ND/2018-19/12351,Buildings,Completed,ND-TONDIARPET,47,180000,"Repairs to Amma Unavagam at Meenambal nagar 3rd street in dn-47,u-11,z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/13594,Buildings,Completed,ND-TONDIARPET,47,200000,"Minor repair work to Amma unavagam at siggirinthapalayam 5th street in dn-47,u-11,z-04",Own Sources,4,2018-19,2019-20 ND/2018-19/13887,Parks,Completed,ND-TONDIARPET,47,216000,"Maintenance of park at Bharathi Nagar Housing board in division-47, Unit-11, Zone-4",Own Sources,4,2018-19,2019-20 ND/2018-19/4656,Buildings,Completed,ND-TONDIARPET,47,2495000,Construction of Dining hall in corporation high school at Harinarayana puram in ward.47 unit.11 zone.4 (under MLA Scheame),MLACDS,4,2018-19,2018-19 ND/2018-19/5535,Buildings,Completed,ND-TONDIARPET,47,118000,"Additional improvement to Meenambal UPHC at k.h.road in dn-47,u-11,z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/5545,Buildings,Completed,ND-TONDIARPET,47,223000,"Raising compound wall to harinarayanapuram health post at old glass factory road in dn-47,u-11,z-04",Own Sources,4,2018-19,2018-19 ND/2018-19/9603,Storm Water Drain,Completed,ND-TONDIARPET,47,937000,"Desiltind and minor repair work to storm water drain at Egambaram st,Thyagappa st,Kannan st,Jawanmoul sowcar st,pittymunusamy st,Egappan street,Mannappan street,Kamaraja nagar 12th street,Siggirinthapalayam 11th street,Siggirinthapalayam 4th street,Ambedkar canal,K.H.Road,C.B.Road,Meenambal nagar cross st,Old glass factory road ,",Own Sources,4,2018-19,2018-19 P/2018-19/4158,Parks,Completed,P-Parks and Playfields,47,3393000,"Providing Packaged Sewage Treatment Plant Capacity of 10 KLD including Supply, Installation, Testing and Commissioning of the Sewage Water Treatment Plant (MBBR Technology) and Operation and Maintenance of the same for a Period of One Year at Eco Park in Dn-47, Zone - 4",Own Sources,4,2018-19,2020-21 B/2018-19/8810,Buildings,Completed,B-Buildings,48,13013502,"Proposed construction of Urban Primary Health Centre Ground Floor in V.R.Nagar at Tondiarpet in Dn - 48, Zone - 4",MLACDS,4,2018-19,2020-21 B/2018-19/8813,Buildings,Completed,B-Buildings,48,10290000,"Proposed construction of Urban Primary Health Centre First Floor,Compound wall and Sump in V.R.Nagar at Tondiarpet in Dn - 48, Zone - 4",Own Sources,4,2018-19,2020-21 L/2018-19/5052,Electrical,Completed,L-Electrical,48,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary at T.H Road in Dn:48, Zone IV",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5054,Electrical,Completed,L-Electrical,48,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post, T.H Road in Dn:48, Zone IV",SMART CITY - ELECTRICAL,4,2018-19,2019-20 L/2018-19/5057,Electrical,Completed,L-Electrical,48,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Mottai Thottam Health Post in Div 48, Zone-IV.",SMART CITY - ELECTRICAL,4,2018-19,2019-20 ND/2018-19/0011,Roads,Completed,ND-TONDIARPET,48,1922000,"IMPROVEMENT THE B.T ROAD AT NALLAPPAVATHIYAR STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0090,Road Cut,Completed,ND-TONDIARPET,48,385000,"IMPROVEMENT THE B.T ROAD AT MUTHUMARIYAMMAN STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0091,Roads,Completed,ND-TONDIARPET,48,450000,"IMPROVEMENT THE B.T ROAD AT BHUDHA STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0094,Roads,Completed,ND-TONDIARPET,48,400000,"IMPROVEMENT THE B.T ROAD AT BOMMI SIVARAMULU STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0097,Roads,Completed,ND-TONDIARPET,48,315000,"RELAYING THE B.T ROAD AT ULLARAMMAN KOIL STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0120,Roads,Completed,ND-TONDIARPET,48,75000,"IMPROVEMENT THE B.T ROAD AT ANDIAPPAN STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/0122,Roads,Completed,ND-TONDIARPET,48,677000,"RELAYING B.T ROAD AT ARANIKANGAN STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/0124,Roads,Completed,ND-TONDIARPET,48,1294000,"RELAYING B.T ROAD AT RAMANUJAM STREET IN DN-46,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/0125,Roads,Completed,ND-TONDIARPET,48,812000,"RELAYING B.T ROAD AT AVATHARA RAMASAMY STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/0715,Roads,Completed,ND-TONDIARPET,48,400000,"IMPROVEMENT THE B.T ROAD AT WEST CEMENTRY ROAD IN DN-48, UNIT-11,ZONE-4.",Own Sources,4,2018-19,2018-19 ND/2018-19/13158,Buildings,Completed,ND-TONDIARPET,48,600000,"Dismantling existing UPHC(VR NAGAR) Building at TH ROAD in DN-48,unit-11, Zone-4",Own Sources,4,2018-19,2018-19 ND/2018-19/14199,Buildings,Completed,ND-TONDIARPET,48,213000,"REPAIRS FOR DAMAGE ROOF, WATER SUPPLY,DRAINAGE ARRANGEMENT IN AMMA CANTEEN @ KANNI KOVIL ST IN DN 48, UNIT- 11, ZN-04",Own Sources,4,2018-19,2019-20 ND/2018-19/2058,Roads,Completed,ND-TONDIARPET,48,1300000,"RELAYING THE B.T ROAD AT RAMANUJAKODAM STREET IN DN-48,UNIT-11,ZONE-4.",Own Sources,4,2018-19,2019-20 ND/2018-19/4276,Buildings,Completed,ND-TONDIARPET,48,998000,"Operation and Maintenance of of High Quality Treated Drinking Water Plant (RO/UV FILTRATION) of 2000 Litres / Hour Capacity for 1 Year Period in Parthasarathi street Dn 48, UNIT-11- Zone -4.",Own Sources,4,2018-19,2019-20 ND/2018-19/5039,Buildings,Completed,ND-TONDIARPET,48,400000,"IMPROVEMENT TO HEALTH POST AT MOTTAI GARDAN IN DN-48, ZONE-4",Own Sources,4,2018-19,2019-20 ND/2018-19/6717,Buildings,Completed,ND-TONDIARPET,48,345000,"Dismandling Dental Hospital Building at TH ROAD in DN-48, Zone-4",Own Sources,4,2018-19,2020-21 ND/2018-19/7035,Buildings,Completed,ND-TONDIARPET,48,590000,"Shifting and Erecting Amma Kudineer at Parthasarathy Street in DN-48, Zone-4",Own Sources,4,2018-19,2018-19 ND/2018-19/7658,Buildings,Completed,ND-TONDIARPET,48,225000,"REPAIRS FOR DAMAGED ROOF, WATER SUPPLY, DRAINAGE ARRANGEMENTS IN AMMA CANTEEN @ BOMMI SIVARAMULU STREET IN DN-48, U-11, Z-4",Own Sources,4,2018-19,2019-20 ND/2018-19/9754,Storm Water Drain,Completed,ND-TONDIARPET,48,506000,"Desilting and Minor Reapir Work at SWD PARTHASARTHY STREET,PARTHASARTHY 2ND STREET,PARTHASARTHY 1ST STREET,DBK STREET,MUTHAIAH STREET,ULLARAMMA KOIL STREET,THULASINGAM STREET,NAINIYAPPAN STREET,MANNAPPAN STREET,T H ROAD,ANDIYAPPAN STREET IN dn-48,u-11,z-04",Own Sources,4,2018-19,2018-19 BR/2018-19/5649,Roads,Completed,BR-Bus Route Roads,49,27500,Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan no BR/2017-18/0006002 BR/2017-18/0006003 dt:03.06.2017 and Deposit code 57/0434/2017-18.,Deposit Works,5,2018-19,2019-20 D/2018-19/2902,Storm Water Drain,Completed,D-Storm Water Drains,49,1907000,"Restoration to the temple tank at Angala Parameswari Koil,Royapuram & Kasi Viswanathasamy Koil ,Ayanavaaram under Sustainable Water Secruity Mission in Dn - 49 & 96,Zone - 5 & 8.",SMART CITY - SWD,5,2018-19,2020-21 L/2018-19/4710,Electrical,Completed,L-Electrical,49,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHHS School building at Appasamy Street in Div-49 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4711,Electrical,Completed,L-Electrical,49,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post building at Solaiappan Street in Div-49 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4712,Electrical,Completed,L-Electrical,49,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post building at Solaiappan Street in Div-49 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4821,Electrical,Completed,L-Electrical,49,2821200,"Electrification work at Greater Corporation of Chennai Schools in Division-49,50,51,52,53,57, 58,59,62 & 63 in Zone - 5.",Own Sources,5,2018-19,2019-20 NE/2018-19/0207,Buildings,Completed,NE-ROYAPURAM,49,2770000,"Providing School Housekeeping Cleaning class room and Toilet in CPS,CMS,CHS AND CHSS SCHOOL at Kappal Polu Street, Appasamy Street, Durai Street, Arthoon Road, S.N Street, Cementry Road, East Cementry Road(Manikandan 6th Street), Sanjeevaryan Koil Street, Manikandan 8th Street, O.S.H Road, Anjaneya Nagar, Kathpada Main Street, C.B Road, Padavattamman Koil Street, Bojaraja Nagar, in",Own Sources,5,2018-19,2019-20 NE/2018-19/0589,Roads,Completed,NE-ROYAPURAM,49,522000,"Relaying B.T road with Paver Finisher in B-Pumping Station Road in Ward-49, Unit-12, Zone-5 044/2098/24662/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/0634,Roads,Completed,NE-ROYAPURAM,49,182000,"Relaying B.T road with Paver Finisher at Srinivasalu Street in Ward-49, Unit-12, Zone-5 044/2114/27311/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0635,Roads,Completed,NE-ROYAPURAM,49,324000,"Attending B.T patches with Paver Finisher at Bala Arunchalam Street in Ward-49, Unit-12, Zone-5 044/2091/24658/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/0888,Roads,Completed,NE-ROYAPURAM,49,51000,"Improvements of Relaying C.C road at Old Amaranji Puram By Lane Div-49,unit-12,zone-5",Own Sources,5,2018-19,2020-21 NE/2018-19/0890,Roads,Completed,NE-ROYAPURAM,49,23000,Improvements of Relaying C.C road at Namasivayam Street (asset no:,Own Sources,5,2018-19,2020-21 NE/2018-19/0892,Roads,Completed,NE-ROYAPURAM,49,13000,"Improvements of Relaying C.C road at New Kamaraja Nagar 5th Lane Div-49,Unit-12,zone-5",Own Sources,5,2018-19,2020-21 NE/2018-19/0893,Roads,Completed,NE-ROYAPURAM,49,15000,"Improvements of Relaying C.C road at New Kamaraja Nagar 4th Lane Div-49,Unit-12,zone-5",Own Sources,5,2018-19,2020-21 NE/2018-19/0895,Roads,Completed,NE-ROYAPURAM,49,17000,"Improvements of Relaying C.C road at New Kamaraja Nagar 1st Lane Div-49,Unit-12,zone-5",Own Sources,5,2018-19,2020-21 NE/2018-19/0896,Roads,Completed,NE-ROYAPURAM,49,128000,"Improvements of Relaying C.C road at Solaiappan lane Dn-49,unit-13,zn-5.",Own Sources,5,2018-19,2020-21 NE/2018-19/10370,Storm Water Drain,Completed,NE-ROYAPURAM,49,7200,"Improvement and Minor Repairs to Existing SWD at West Kalmandapam Road in Ward-49, Unit-12, Zone-5",Own Sources,5,2018-19,2018-19 NE/2018-19/11483,Roads,Completed,NE-ROYAPURAM,49,247000,Improvements of Relaying B.T road at Solaiappan street(asset no:044/2078/22772/2013-14),Own Sources,5,2018-19,2019-20 NE/2018-19/11494,Roads,Completed,NE-ROYAPURAM,49,442000,Improvement of relaying B.T Road at New solaiappan street (Asset code:044/2068/24652/2014-15),Own Sources,5,2018-19,2019-20 NE/2018-19/11495,Roads,Completed,NE-ROYAPURAM,49,288000,Improvement of relaying B.T Road at Thanikachalam street (Asset code:044/2086/24657/2014-15),Own Sources,5,2018-19,2019-20 NE/2018-19/11497,Roads,Completed,NE-ROYAPURAM,49,709000,Improvement of relaying B.T at M.C Road street (Asset code:044/2099/15507/2013-14),Own Sources,5,2018-19,2019-20 NE/2018-19/11502,Roads,Completed,NE-ROYAPURAM,49,702000,Improvement of relaying B.T Road at Singara Garden 1st lane (Asset code:044/2146/24268/2014-15),Own Sources,5,2018-19,2019-20 NE/2018-19/11507,Roads,Completed,NE-ROYAPURAM,49,691000,Improvements of Relaying B.T road at Singara Garden 5th Lane asset no:044/2143/14633/2013-14),Own Sources,5,2018-19,2019-20 NE/2018-19/11508,Roads,Completed,NE-ROYAPURAM,49,679000,Improvements of Relaying B.T road at Singara Garden 6th Lane (asset no:044/2142/14634/2013-14),Own Sources,5,2018-19,2019-20 NE/2018-19/15367,Roads,Completed,NE-ROYAPURAM,49,458000,"Relaying of BT road with paver finisher at kappal polu street division -49,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15421,Roads,Completed,NE-ROYAPURAM,49,624000,"Relaying Of B.T Road with Paver finisher at Adam street in Division-49,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15423,Roads,Completed,NE-ROYAPURAM,49,75000,"Relaying of BT Road with Paver finisher at Venkadapathy street in Division-49,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15424,Roads,Completed,NE-ROYAPURAM,49,59000,"Relaying of B.T Road with Paver finisher at Rajavelu lane in Division-49,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15425,Roads,Completed,NE-ROYAPURAM,49,729000,"Relaying Of B.T Road with Paver finisher at Balu Street in Dn-49, Unit-12, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15426,Roads,Completed,NE-ROYAPURAM,49,439000,"Relaying Of B.T Road with Paver finisher at Justice Pandalai Street in Dn-49, Unit-12, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15435,Roads,Completed,NE-ROYAPURAM,49,335000,"Relaying Of B.T Road with Paver finisher at Singara Garden 4th Lane in Dn-49, Unit-12, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15437,Roads,Completed,NE-ROYAPURAM,49,310000,"Relaying Of B.T Road with Paver finisher at Singara Garden 8th Lane in Dn-53, unit-12, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/8941,Roads,Completed,NE-ROYAPURAM,49,1075000,"Attending various B.T Patches at M.C Road & Solaiyappan Street in Division-49, Unit-12, Zone-5. 044/2078/22772/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9145,Storm Water Drain,Completed,NE-ROYAPURAM,49,15500,"Improvements and Desilting to Existing SWD at Solaiappan Street in Dn-49, U-12, Zone-V ASSET CODE:055/2078/6597/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9147,Storm Water Drain,Completed,NE-ROYAPURAM,49,8900,"Improvements and Desilting to Existing SWD at Rajavelu Street in Dn-49, U-12, Zone-V ASSET CODE: 055/2147/6601/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9148,Storm Water Drain,Completed,NE-ROYAPURAM,49,6600,"Improvements and Desilting to Existing SWD at Singara Garden 4th Lane in Dn-49, U-12, Zone-V ASSET CODE: 055/2144/6602/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9149,Storm Water Drain,Completed,NE-ROYAPURAM,49,7000,"Improvements and Desilting to Existing SWD at Raja Gopal Street in Dn-49, U-12, Zone-V ASSET CODE: 055/2149/6600/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9150,Storm Water Drain,Completed,NE-ROYAPURAM,49,5800,"Improvements and Desilting to Existing SWD at PAN Rajarathinam Salai in Dn-49, U-12, Zone-V ASSET CODE:044/15890/15487/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9151,Storm Water Drain,Completed,NE-ROYAPURAM,49,8200,"Improvements and Desilting to Existing SWD at Singara Garden 5th Lane in Dn-49, U-12, Zone-V ASSET CODE: 044/2143/14633/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9152,Storm Water Drain,Completed,NE-ROYAPURAM,49,9100,"Improvements and Desilting to Existing SWD at Bala Arunachalam Street in Dn-49, U-12, Zone-V ASSET CODE: 055/2091/6585/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9153,Storm Water Drain,Completed,NE-ROYAPURAM,49,8200,"Improvements and Desilting to Existing SWD at Balu Street in Dn-49, U-12, Zone-V ASSET CODE: 044/2088/24653/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9154,Storm Water Drain,Completed,NE-ROYAPURAM,49,22800,"Improvements and Desilting to Existing SWD at Kappal Street in Dn-49, U-12, Zone- V ASSET CODE: 055/2067/6582/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9155,Storm Water Drain,Completed,NE-ROYAPURAM,49,11200,"Improvements and Desilting to Existing SWD at Thandavarayan Street in Dn-49, U-12, Zone-V asset code- 055/2075/6583/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9156,Storm Water Drain,Completed,NE-ROYAPURAM,49,27700,"Improvements and Desilting to Existing SWD at Sanjeevirayan Street in Dn-49, U-12, Zone-V asset code- 156/2081/2157/2015-16",Own Sources,5,2018-19,2018-19 NE/2018-19/9157,Storm Water Drain,Completed,NE-ROYAPURAM,49,7500,"Improvements and Desilting to Existing SWD at Adam Street in Dn-49, U-12, Zone-V Asset code- 055/2122/6599/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9158,Storm Water Drain,Completed,NE-ROYAPURAM,49,12200,"Improvements and Desilting to Existing SWD at Thandavarayan Street in Dn-49, U-12, Zone-V asset code- 055/2075/6583/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9159,Storm Water Drain,Completed,NE-ROYAPURAM,49,5300,"Improvements and Desilting to Existing SWD at Grace Garden Main Road in Dn-49, U-12, Zone-V Asset code- 055/2102/6586/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9160,Storm Water Drain,Completed,NE-ROYAPURAM,49,3000,"Improvements and Desilting to Existing SWD at New Kamaraj Nagar Sreet in Dn-49, U-12, Zone-V asset code- 055/2104/6587/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9161,Storm Water Drain,Completed,NE-ROYAPURAM,49,7900,"Improvements and Desilting to Existing SWD at Venkatachalam Street in Dn-49, U-12, Zone-V Asset code- 055/2084/6357/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9162,Storm Water Drain,Completed,NE-ROYAPURAM,49,11000,"Improvements at Desilting to Existing SWD at Kothandaramar Street in Dn-49, U-12, Zone-V Asset- 044/2073/24266/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9163,Storm Water Drain,Completed,NE-ROYAPURAM,49,10500,"Improvements and Desilting to Existing SWD at New Thandavarayan in Dn-49, U-12,Zone-V Asset code- 055/15325/6598/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9164,Storm Water Drain,Completed,NE-ROYAPURAM,49,11000,"Improvements and Desilting to Existing SWD at Old Amaranji Puram in Dn-49, U-12, Zone-V asset code- 055/2103/6356/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9165,Buildings,Completed,NE-ROYAPURAM,49,39000,"Improvements and Minor repairs to Existing SWD at Solaiappan Street in Dn-49, U-12, Zone-V (Asset Code- 055/2078/6597/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9166,Buildings,Completed,NE-ROYAPURAM,49,39000,"Improvements and Minor repairs to Existing SWD at Kothandaramar Street in Dn-49, U-12, Zone-V (Asset Code- 044/2073/24266/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9182,Storm Water Drain,Completed,NE-ROYAPURAM,49,15900,"Improvements and Desilting to Existing SWD at West Kalmadapam Road in Dn-49, U-12, Zone-V ASSET CODE: 055/2124/6590/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9183,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Thandavarayan Street in Dn-49, U-12, Zone-V (Asset Code- 055/2075/6583/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9184,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Raja Gopal Street Dn-49, U-12, Zone-V (Asset Code- 055/2149/6600/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9185,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Singara Garden 5th in Dn-49, U-12, Zone-V (Asset Code- 044/2143/14633/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9186,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at New Thandavarayan Street in Dn-49, U-12, Zone-V (Asset Code- 055/15325/6598/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9187,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at PAN Rajarathinam Salai in Dn-49, U-12, Zone-V (Asset Code- 044/15890/15487/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9188,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Venkatachalam in Dn-49, U-12, Zone-V (Asset Code- 055/2084/6596/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9189,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Sanjeevirayan in Dn-49, U-12, Zone-V (Asset Code- 156/2081/2157/2015-16",Own Sources,5,2018-19,2018-19 NE/2018-19/9190,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Old Amaranji Puram in Dn-49, U-12, Zone-V (Asset Code- 055/2103/6356/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9191,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Adam Street in Dn-49, U-12, Zone-V (Asset Code- 055/2122/6599/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9192,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Grace Garden Main Road in Dn-49, U-12, Zone-V (Asset Code- 055/2102/6586/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9194,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Singara Garden 4th Lane in Dn-49, U-12, Zone-V (Asset Code- 055/2144/6602/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9195,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Bala Arunachalam Street in Dn-49, U-12, Zone-V (Asset Code- 055/2091/6585/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9196,Buildings,Completed,NE-ROYAPURAM,49,10900,"Improvements and Minor repairs to Existing SWD at Kappal polu Street in Dn-49, U-12, Zone-V (Asset Code- 055/2067/6582/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9197,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at New Kamaraj Nagar 5th Street in Dn-49, U-12, Zone-V (Asset Code-055/2104/6587/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9198,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Raja Velu Street in Dn-49, U-12, Zone-V (Asset Code- 055/2147/6601/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9199,Buildings,Completed,NE-ROYAPURAM,49,7200,"Improvements and Minor repairs to Existing SWD at Thandavarayan Street in Dn-49, U-12, Zone-V (Asset Code- 130/714/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9200,Buildings,Completed,NE-ROYAPURAM,49,7100,"Improvements and Minor repairs to Existing SWD at Balu Street in Dn-49, U-12, Zone-V (Asset Code- 044/2088/24653/2014-15",Own Sources,5,2018-19,2018-19 BR/2018-19/18200,Roads,Completed,BR-Bus Route Roads,50,530000,PROVIDING CENTRE MEDIAN AND LAYING THERMOPLASTIC & STUD AT WEST MADA STREET IN ZONE-5 DIV-50.,Own Sources,5,2018-19,2019-20 L/2018-19/4714,Electrical,Completed,L-Electrical,50,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS School building (Amma Unavagam) at S.N Chetty Street in Div-50 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4715,Electrical,Completed,L-Electrical,50,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS School building at Durai Street in Div-50 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4716,Electrical,Completed,L-Electrical,50,161500,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHHS School building at S.N Chetty Street in Div-50 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4718,Electrical,Completed,L-Electrical,50,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post building at S.N Chetty Street in Div-50 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4719,Electrical,Completed,L-Electrical,50,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Centre building at Shiek Maistry Street in Div-50 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 NE/2018-19/0636,Roads,Completed,NE-ROYAPURAM,50,465000,"Attending B.T patches with Paver Finisher at Andiyappan Street in Ward-50, Unit-12, Zone-5 044/2211/18651/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0639,Roads,Completed,NE-ROYAPURAM,50,1062000,"Attending B.T patches with Paver Finisher at North Madha Church Street. in Ward-50, Unit-12, Zone-5 044/42623/24755/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/0737,Roads,Completed,NE-ROYAPURAM,50,818000,"Attending B.T patches with Paver Finisher at A.J COLONY MAIN ROAD. in Ward-50, Unit-12, Zone-5 Asset code: 044/15569/6063/2006-07",Own Sources,5,2018-19,2019-20 NE/2018-19/0740,Roads,Completed,NE-ROYAPURAM,50,227000,"Attending B.T patches with Paver Finisher at A.J COLONY 1st lane in Ward-50, Unit-12, Zone-5 Asset code:044/2190/18645/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0742,Roads,Completed,NE-ROYAPURAM,50,268000,"Attending B.T patches with Paver Finisher at A.J COLONY 2ND lane in Ward-50, Unit-12, Zone-5 Asset code:044/2189/18646/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0745,Roads,Completed,NE-ROYAPURAM,50,314000,"Attending B.T patches with Paver Finisher at A.J COLONY 3RD lane in Ward-50, Unit-12, Zone-5 Asset code:044/2188/18647/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0781,Roads,Completed,NE-ROYAPURAM,50,638000,"Attending B.T patches with Paver Finisher at hussain maistry street in Ward-50, Unit-12, Zone-5 Asset code:044/2156/1256/2009-10",Own Sources,5,2018-19,2019-20 NE/2018-19/0784,Roads,Completed,NE-ROYAPURAM,50,257000,"Attending B.T patches with Paver Finisher at P.V kovil 1st street street in Ward-50, Unit-12, Zone-5 Asset code:039/2191/1/2009-10",Own Sources,5,2018-19,2019-20 NE/2018-19/0824,Roads,Completed,NE-ROYAPURAM,50,63000,"Attending B.T patches in N.R.T service road in Ward-50, Unit-12, Zone-5 asset code:044/42624/18789/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0826,Roads,Completed,NE-ROYAPURAM,50,49000,"Attending B.T patches in Thandavamurthy street(tank street) in Ward-50, Unit-12, Zone-5 asset code:040/15596/2795/2007-08",Own Sources,5,2018-19,2019-20 NE/2018-19/0827,Roads,Completed,NE-ROYAPURAM,50,231000,"Attending B.T patches in south madha kovil street in Ward-50, Unit-12, Zone-5 asset code:040/2411/307/2005-06",Own Sources,5,2018-19,2019-20 NE/2018-19/0829,Roads,Completed,NE-ROYAPURAM,50,62000,"Attending B.T patches in P.V kovil street in Ward-50, Unit-12, Zone-5 asset code:039/2195/5/2009-10",Own Sources,5,2018-19,2019-20 NE/2018-19/0830,Roads,Completed,NE-ROYAPURAM,50,188000,"Attending B.T patches with Paver Finisher in P.V kovil 8th lane in Ward-50, Unit-12, Zone-5 asset code:039/2216/17/2007-08",Own Sources,5,2018-19,2019-20 NE/2018-19/0831,Roads,Completed,NE-ROYAPURAM,50,310000,"Attending B.T patches with Paver Finisher in LOTUS RAMASAMY STREET in Ward-50, Unit-12, Zone-5 asset code:044/2169/1264/2006-07",Own Sources,5,2018-19,2019-20 NE/2018-19/0832,Roads,Completed,NE-ROYAPURAM,50,630000,"Attending B.T patches with Paver Finisher in G.M pettah Road in Ward-50, Unit-12, Zone-5 asset code:040/2212/252/2007-08",Own Sources,5,2018-19,2019-20 NE/2018-19/0833,Roads,Completed,NE-ROYAPURAM,50,560000,"Attending B.T patches with Paver Finisher in East madha kovil Street in Ward-50, Unit-12, Zone-5 asset code:040/2357/292/2005-06",Own Sources,5,2018-19,2019-20 NE/2018-19/0909,Roads,Completed,NE-ROYAPURAM,50,247000,"Attending Cement Concrete patches at periyathambi 2nd street ward-50, Unit-12, Zone-5 Asset code:040/2163/6522/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/0911,Roads,Completed,NE-ROYAPURAM,50,445000,"Attending Cement Concrete patches at periyathambi 1st street ward-50, Unit-12, Zone-5 Asset code:040/2164/6521/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/0912,Roads,Completed,NE-ROYAPURAM,50,51000,"Attending Cement Concrete patches at North madha square lane ward-50, Unit-12, Zone-5 Asset code:040/2229/6513/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/0913,Roads,Completed,NE-ROYAPURAM,50,138000,"Attending Cement Concrete patches at Durai street lane in ward-50, Unit-12, Zone-5 Asset code:041/2185/3/2009-10",Own Sources,5,2018-19,2020-21 NE/2018-19/0915,Roads,Completed,NE-ROYAPURAM,50,187000,"Attending Cement Concrete patches at corporation colony 1st street lane in ward-50, Unit-12, Zone-5 Asset code:040/2227/257/2008-09",Own Sources,5,2018-19,2020-21 NE/2018-19/0916,Roads,Completed,NE-ROYAPURAM,50,80000,"Attending Cement Concrete patches at bentleman garden 2nd lane in ward-50, Unit-12, Zone-5 Asset code:040/2186/6506/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/0917,Roads,Completed,NE-ROYAPURAM,50,79000,"Attending Cement Concrete patches at bentleman garden 1st lane in ward-50, Unit-12, Zone-5 Asset code:044/15571/6064/2007-08",Own Sources,5,2018-19,2020-21 NE/2018-19/15375,Roads,Completed,NE-ROYAPURAM,50,349000,"Relaying of BT road with paver finisher at Andiappan street division -50 unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/16742,Parks,Completed,NE-ROYAPURAM,50,344000,Annual Maintenance for Kamarajar Park at Suriyanarayana Salai in Div-50 Unit-12 Zone,Own Sources,5,2018-19,2020-21 NE/2018-19/16767,Parks,Completed,NE-ROYAPURAM,50,1363000,Annual Maintenance for NRT Bridge Under Park at N R T Service Road in Div-50 Unit-12 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/2159,Buildings,Completed,NE-ROYAPURAM,50,141000,"Repairs and annual maintenance in anganwadi at G.M pettah road at ward-50, unit-12, zone-5 asset code:020/2159/32/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/2311,Buildings,Completed,NE-ROYAPURAM,50,113000,"Repairs and Annual Maintance to Anganvadi Center at East kalmandapam Road in Dn-50, Unit-12, Zone-V asset code:023/2174/237/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/5954,Buildings,Completed,NE-ROYAPURAM,50,1700000,"CONSTRUCTION OF ANGANWADI BUILDING 1 AT SHEIK MAISTRY STREET IN DIVISION-50, UNIT-13, ZONE-5",MLACDS,5,2018-19,2019-20 NE/2018-19/5955,Buildings,Completed,NE-ROYAPURAM,50,1700000,"CONSTRUCTION OF ANGANWADI BUILDING 2 AT SHEIK MAISTRY STREET IN DIVISION-50, UNIT-13, ZONE-5",MLACDS,5,2018-19,2019-20 NE/2018-19/9441,Storm Water Drain,Completed,NE-ROYAPURAM,50,12300,"Improvements and Desilting Existing SWD at Thiruvenkadam Street (From East Madha Koil Street to Venkatesan Street) in Dn-50, U-12, Zone- V Asset code:",Own Sources,5,2018-19,2018-19 NE/2018-19/9443,Storm Water Drain,Completed,NE-ROYAPURAM,50,8500,"Improvements and Desilting Existing SWD at South Madha church Road( North) in Dn-50, U-12, Zone- V Asset code: 055/42625/5024/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9445,Storm Water Drain,Completed,NE-ROYAPURAM,50,16600,"Improvements and Desilting Existing SWD at Mannar samy koil street in Dn-50, U-12, Zone- V Asset code:055/2200/5014/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9446,Storm Water Drain,Completed,NE-ROYAPURAM,50,9300,"Improvements and Desilting Existing SWD at North Railway Terminus Road in Dn-50, U-12, Zone- V Asset code: 055/42624/5023/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9447,Storm Water Drain,Completed,NE-ROYAPURAM,50,10900,"Improvements and Desilting Existing SWD at Bazaar street in Dn-50, U-12, Zone- V Asset code: 055/2168/5012/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9448,Storm Water Drain,Completed,NE-ROYAPURAM,50,19400,"Improvements and Desilting Existing SWD at East Mada church street in Dn-50, U-12, Zone- V Asset code: 055/2202/5018/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9449,Storm Water Drain,Completed,NE-ROYAPURAM,50,1900,"Improvements and Desilting Existing SWD atVenkatesan 1st Street (Corporation Colony Lane to Venkatesan Street) in Dn-50, U-12, Zone- V Asset code: 055/2234/5021/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9450,Storm Water Drain,Completed,NE-ROYAPURAM,50,20300,"Improvements and Desilting Existing SWD at Venkatesan Street (From East Kalmandapam Road to North Madha Square Lane) in Dn-50, U-12, Zone- V Asset code:055/2235/5019/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9451,Storm Water Drain,Completed,NE-ROYAPURAM,50,29000,"Improvements and Desilting Existing SWD at East Madha Koil Street (From East Madha Koil 1st Lane to Thiruvenkadam Street) (And East Madha Koil 10th Lane to North Madha Koil Street) in Dn-50, U-12, Zone- V Asset code:055/2202/5018/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9452,Storm Water Drain,Completed,NE-ROYAPURAM,50,14600,"Improvements and Desilting Existing SWD at North Madha Koil Street (From West Madha Koil Street to East Madha Koil Streetin Dn-50, U-12, Zone- V Asset code: 055/2228/5017/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9454,Storm Water Drain,Completed,NE-ROYAPURAM,50,20700,"Improvements and Desilting Existing SWD at Andiappan (From Mannarsamy Koil Street to West Madha koil Street)in Dn-50, U-12, Zone- V Asset code:055/2200/5015/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9455,Storm Water Drain,Completed,NE-ROYAPURAM,50,20700,"Improvements and Desilting Existing SWD at Mannarsamy Koil Street (From East Kalmandapam Road to West side) in Dn-50, U-12, Zone- V Asset code:055/2200/5015/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9456,Storm Water Drain,Completed,NE-ROYAPURAM,50,34800,"Improvements and Desilting Existing SWD at S N ������������������ Street (East Side) in Dn-50, U-12, Zone- V Asset code: 055/2159/5003/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9457,Storm Water Drain,Completed,NE-ROYAPURAM,50,16000,"Improvements and Desilting Existing SWD at S N ������������������ Street (West Side) in Dn-50, U-12, Zone- V Asset code: 055/2159/3187/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9458,Storm Water Drain,Completed,NE-ROYAPURAM,50,3300,"Improvements and Desilting Existing SWD at Thulukanathamman Koil Street in Dn-50, U-12, Zone- V Asset code: 055/2157/5013/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9463,Storm Water Drain,Completed,NE-ROYAPURAM,50,26700,"Improvements and Desilting Existing SWD at Lotus Ramasamy Street in Dn-50, U-12, Zone- V Asset code: 055/2169/5010/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9464,Storm Water Drain,Completed,NE-ROYAPURAM,50,3600,"Improvements and Desilting Existing SWD at Sheike Mastry 1st Lane in Dn-50, U-12, Zone- V Asset code: 055/2160/5009/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9465,Storm Water Drain,Completed,NE-ROYAPURAM,50,22700,"Improvements and Desilting Existing SWD at Sheike Mastry Street in Dn-50, U-12, Zone- V Asset code: 055/2162/5008/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9466,Storm Water Drain,Completed,NE-ROYAPURAM,50,14600,"Improvements and Desilting Existing SWD at St Xavier Street in Dn-50, U-12, Zone- V Asset code: 055/15585/5007/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9467,Storm Water Drain,Completed,NE-ROYAPURAM,50,7000,"Improvements and Desilting Existing SWD at G M Pettai Road (On Western Side) in Dn-50, U-12, Zone- V Asset code:055/2179/5005/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9468,Storm Water Drain,Completed,NE-ROYAPURAM,50,60000,"Improvements and Desilting Existing SWD at G M Pettai Road (On Eastern Side)(Arch Drain) in Dn-50, U-12, Zone- V Asset code:055/2179/5006/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9484,Buildings,Completed,NE-ROYAPURAM,50,3600,"Improvements and Minor repairs to Existing SWD at South Madha church Road( North) in Dn-50, U-12, Zone-V (Asset Code-055/42625/5024/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9486,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Mannar samy koil street in Dn-50, U-12, Zone-V (Asset Code-055/2200/7330/2014-15)",Own Sources,5,2018-19,2018-19 NE/2018-19/9487,Buildings,Completed,NE-ROYAPURAM,50,3600,"Improvements and Minor repairs to Existing SWD at North Railway Terminus Road in Dn-50, U-12, Zone-V (Asset Code-055/42624/5023/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9488,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Bazaar street in Dn-50, U-12, Zone-V Asset code:055/2202/5018/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9489,Buildings,Completed,NE-ROYAPURAM,50,60200,"Improvements and Minor repairs to Existing SWD at East Mada church street in Dn-50, U-12, Zone-V (Asset Code-055/2202/5018/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9490,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Venkatesan 1st Street (Corporation Colony Lane to Venkatesan Street) in Dn-50, U-12, Zone-V (Asset Code-055/2202/5018/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9491,Buildings,Completed,NE-ROYAPURAM,50,3600,"Improvements and Minor repairs to Existing SWD at Thiruvenkadam Street (From East Madha Koil Street to Venkatesan Street) in Dn-50, U-12, Zone-V (Asset Code-055/2222/5020/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9492,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Venkatesan Street (From East Kalmandapam Road to North Madha Square Lane) in Dn-50, U-12, Zone-V Asset Code- 055/2235/5019/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9493,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at East Madha Koil Street (From East Madha Koil 1st Lane to Thiruvenkadam Street) (And East Madha Koil 10th Lane to North Madha Koil Street) in Dn-50, U-12, Zone-V Asset Code- 055/2202/5018/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9494,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at North Madha Koil Street (From West Madha Koil Street to East Madha Koil Street in Dn-50, U-12, Zone-V Asset Code- 055/2228/5017/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9495,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Andiappan (From Mannarsamy Koil Street to West Madha koil Street) in Dn-50, U-12, Zone-V Asset Code- 055/2211/5016/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9496,Buildings,Completed,NE-ROYAPURAM,50,126000,"Improvements and Minor repairs to Existing SWD at Mannarsamy Koil Street (From East Kalmandapam Road to West side) in Dn-50, U-12, Zone-V Asset Code- 055/2200/5015/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9497,Buildings,Completed,NE-ROYAPURAM,50,118000,"Improvements and Minor repairs to Existing SWD at S N ������������������ Street (East Side) in Dn-50, U-12, Zone-V Asset Code- 055/2159/5003/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9498,Buildings,Completed,NE-ROYAPURAM,50,10800,"Improvements and Minor repairs to Existing SWD at S N ������������������ Street (West Side) in Dn-50, U-12, Zone-V Asset Code- 055/2159/3187/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9499,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Thulukanathamman Koil Street in Dn-50, U-12, Zone-V Asset Code- 055/2157/5013/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9500,Buildings,Completed,NE-ROYAPURAM,50,3600,"Improvements and Minor repairs to Existing SWD at Lotus Ramasamy Street in Dn-50, U-12, Zone-V Asset Code- 055/2169/5010/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9501,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Sheike Mastry 1st Lane in Dn-50, U-12, Zone-V Asset Code- 055/2160/5009/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9502,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at Sheike Mastry Street in Dn-50, U-12, Zone-V Asset Code- 055/2162/5008/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9503,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at St Xavier Street in Dn-50, U-12, Zone-V Asset Code- 055/15585/5007/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9504,Buildings,Completed,NE-ROYAPURAM,50,10800,"Improvements and Minor repairs to Existing SWD at G M Pettai Road (On Western Side) in Dn-50, U-12, Zone-V Asset Code- 055/2179/5005/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9505,Buildings,Completed,NE-ROYAPURAM,50,7200,"Improvements and Minor repairs to Existing SWD at G M Pettai Road (On Eastern Side)(Arch Drain) in Dn-50, U-12, Zone-V Asset Code- 055/2179/5006/2013-14",Own Sources,5,2018-19,2018-19 BR/2018-19/5952,Roads,Completed,BR-Bus Route Roads,51,692000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 5 against the challan no 07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017 and Deposit code 57/0666/2017-18.",Deposit Works,5,2018-19,2018-19 BR/2018-19/6576,Roads,Completed,BR-Bus Route Roads,51,7886349,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Cemetry Road in Dn-51 & 52, Zone-V",Grants,5,2018-19,2019-20 NE/2018-19/0646,Roads,Completed,NE-ROYAPURAM,51,364000,"Attending B.T patches with Paver Finisher at Perambalu Street (Part) in Ward-51, Unit-12, Zone-5 044/2290/13263/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0648,Roads,Completed,NE-ROYAPURAM,51,182000,"Attending B.T patches with Paver Finisher at Selvavinayagar Koil Street (Part) in Ward-51, Unit-12, Zone-5 044/2286/15277/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0649,Roads,Completed,NE-ROYAPURAM,51,145000,"Attending B.T patches with Paver Finisher at Narayanappan Street (Part) (From Kalilngarayan Street to M.C Road) in Ward-51, Unit-12, Zone-5 044/2318/14629/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0650,Roads,Completed,NE-ROYAPURAM,51,286000,"Attending B.T patches with Paver Finisher at East Muthaya Street in Ward-52, Unit-12, Zone-5",Own Sources,5,2018-19,2018-19 NE/2018-19/0651,Roads,Completed,NE-ROYAPURAM,51,519000,"Attending B.T patches with Paver Finisher at Dhakshiana Moorthy Kovil Street. in Ward-52, Unit-12, Zone-5 (ASSET CODE- 044/15592/17712/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/0652,Roads,Completed,NE-ROYAPURAM,51,393000,"Attending B.T patches with Paver Finisher at Raman Street. (Old Ward No-19 Except Road cut CMWSSB Andiappan Street to Veerasamy Street) in Ward-52, Unit-12, Zone-5 ( 044/2280/17683/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/0653,Roads,Completed,NE-ROYAPURAM,51,519000,"Attending B.T patches with Paver Finisher at M.C Road (Partly) in Ward-52, Unit-12, Zone-5 044/15327/14954/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0654,Roads,Completed,NE-ROYAPURAM,51,1351000,"Attending B.T patches with Paver Finisher at Andiappan Street in Ward-52, Unit-12, Zone-5 ( 044/2280/17683/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/0655,Roads,Completed,NE-ROYAPURAM,51,561000,"Attending B.T patches with Paver Finisher at Mosque Street in Ward-52, Unit-12, Zone-5 044/2342/17701/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0656,Roads,Completed,NE-ROYAPURAM,51,415000,"Attending B.T patches with Paver Finisher at Bajanai Kovil Street. in Ward-52, Unit-12, Zone-5 044/2367/17702/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0660,Roads,Completed,NE-ROYAPURAM,51,1081000,"Attending B.T patches with Paver Finisher at Canal Street in Ward-53, Unit-12, Zone-5 044/2743/27581/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/0662,Roads,Completed,NE-ROYAPURAM,51,1152000,"Attending B.T patches with Paver Finisher at Kathbada Main Street in Ward-53, Unit-12, Zone-5 044/2806/27569/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/0663,Roads,Completed,NE-ROYAPURAM,51,435000,"Attending B.T patches with Paver Finisher at Pensioner Lane 1st Street in Ward-53, Unit-12, Zone-5 040/2738/3775/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0727,Roads,Completed,NE-ROYAPURAM,51,410000,"Improvements of BT Road in Narayanappan 9th Street in Div-51, Unit-12, Zone-5 asset code: 044/2308/8519/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0729,Roads,Completed,NE-ROYAPURAM,51,329000,"Improvements of BT Road in Manikandan 8th Street in Div-51, Unit-12, Zone-5 asset code: 044/2306/8520/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0919,Roads,Completed,NE-ROYAPURAM,51,215000,"Improvements of BT Road in Manikandan 7th Street in Div-51, Unit-12, Zone-5 asset code: 044/2307/17813/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0923,Roads,Completed,NE-ROYAPURAM,51,1183000,"Improvements of BT Road in Manikandan 6th Street in Div-51, Unit-12, Zone-5 asset code: 044/2308/17810/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0926,Roads,Completed,NE-ROYAPURAM,51,708000,"Improvements of BT Road in Manikandan 5th Street in Div-51, Unit-12, Zone-5 asset code: 044/2309/15274/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0928,Roads,Completed,NE-ROYAPURAM,51,480000,"Improvements of BT Road in Manikandan 4th Street in Div-51, Unit-12, Zone-5 asset code: 044/2310/17806/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0929,Roads,Completed,NE-ROYAPURAM,51,396000,"Improvements of BT Road in Manikandan 3rd Street in Div-51, Unit-12, Zone-5 asset code: 044/2311/17804/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0931,Roads,Completed,NE-ROYAPURAM,51,374000,"Improvements of BT Road in Manikandan 2nd Street in Div-51, Unit-12, Zone-5 asset code: 044/2312/17803/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0933,Roads,Completed,NE-ROYAPURAM,51,105000,"Improvements of BT Road in Kalingarayan Street in Div-51, Unit-12, Zone-5 asset code: 044/2314/17795/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0935,Roads,Completed,NE-ROYAPURAM,51,105000,"Improvements of BT Road in Srirangammal Street in Div-51, Unit-12, Zone-5 asset code: 044/2298/13250/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/0955,Roads,Completed,NE-ROYAPURAM,51,276500,"Providing and Laying Cement Concrete Interior Road in Nainiappa Garden 1st Lane in Div -51,Unit -12,Zone -5. asset code: 040/2325/6149/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/0962,Roads,Completed,NE-ROYAPURAM,51,253000,"Providing and Laying Cement Concrete Interior Road in Nainiappa Garden 2nd Lane in Div -51,Unit -12,Zone -5. asset code: 040/2324/6151/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/1304,Roads,Completed,NE-ROYAPURAM,51,311000,"Providing and Laying Cement Concrete Interior Road in Nainiappa Garden 3rd Lane in Div -51,Unit -12,Zone -5. asset code: 040/2323/6152/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/1308,Roads,Completed,NE-ROYAPURAM,51,145500,"Providing and Laying Cement Concrete Interior Road in Nainiappa Garden 5th Lane in Div -51,Unit -12,Zone -5. asset code: 040/2321/6156/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/1309,Roads,Completed,NE-ROYAPURAM,51,259000,"Providing and Laying Cement Concrete Interior Road in Gengan Street (North - South) in Div -51,Unit -12,Zone -5. asset code: 044/2305/17825/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/15380,Roads,Completed,NE-ROYAPURAM,51,271000,"Relaying of BT road with paver finisher at manikandan1st street division-51,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15427,Roads,Completed,NE-ROYAPURAM,51,295000,"Relaying of BT road with paver finisher in Sanjeevarayan koil street division-51,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15430,Roads,Completed,NE-ROYAPURAM,51,454000,"Relaying Of B.T Road with Paver finisher at East Cementry Road in Dn-51, Unit-12, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/3118,Buildings,Completed,NE-ROYAPURAM,51,196000,"Improvements to Anganvadi Centers (218,219,220) in Srirangammal Street in Div 51,Unit 12,Zone 5.Asset code-023/2298/222/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/3120,Buildings,Completed,NE-ROYAPURAM,51,143000,"Repairs and Annual maintainance to Anganvadi Centers in Pandian Park in Cemetry Road in Div 51,Unit 12,Zone 5.Asset code - 023/2334/229/2013-14.",Own Sources,5,2018-19,2019-20 NE/2018-19/3122,Buildings,Completed,NE-ROYAPURAM,51,526500,"Improvements to Anganvadi Centers (106,107,108,109) in Manikandan 6th Street in Div 51,Unit 12,Zone 5.Assert Code -023/2308/228/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/3155,Buildings,Completed,NE-ROYAPURAM,51,89000,"Repairs and Maintainance to Anganvadi centers in TNSCB Slum Tenements in East Cemetry Road in Div 51,Unit 12,Zone 5.Asset code - 023/2332/223/2013-14.",Own Sources,5,2018-19,2019-20 NE/2018-19/5992,Buildings,Completed,NE-ROYAPURAM,51,382000,"Improvements to Dispensary in East Cemetry Road in Div 51,Unit 12,Zone 5.Asset Code - 014/2332/84/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/5997,Buildings,Completed,NE-ROYAPURAM,51,293000,"Improvements to Unit office,Siddha dispensary and E-Seva center in Perambalu Street in Div-51,Unit-12,Zone-5.(Asset Code- 026/2290/21/2013-14).",Own Sources,5,2018-19,2019-20 NE/2018-19/6511,Buildings,Completed,NE-ROYAPURAM,51,979000,"Construction of New Resource Recovery center at NN Garden 8th lane in DIV-51, Unit-12, Zone-5",Own Sources,5,2018-19,2020-21 NE/2018-19/8944,Roads,Completed,NE-ROYAPURAM,51,798000,"Attending various B.T Patches at Singara garden 4th street, guruvappa street & J.P Koil street in Division-49 & 51, Unit-12, Zone-5.",Own Sources,5,2018-19,2018-19 NE/2018-19/9345,Storm Water Drain,Completed,NE-ROYAPURAM,51,14200,"Desilting to Existing SWD at N.N. Garden 8th Lane in Dn-51, U-12, Zone- V asset code: 055/2299/7904/2015-16",Own Sources,5,2018-19,2018-19 NE/2018-19/9346,Storm Water Drain,Completed,NE-ROYAPURAM,51,13700,"Desilting to Existing SWD at Narasier Street in Dn-51, U-12, Zone-V.(Asset Code - SD/2293/361/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9347,Storm Water Drain,Completed,NE-ROYAPURAM,51,2400,"Desilting to Existing SWD at Ramanujam Street in Dn-51, U-12, Zone-V (Aseet Code - SD/2289/359/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9349,Storm Water Drain,Completed,NE-ROYAPURAM,51,2600,"Desilting to Existing SWD at Manikandan 6th Street in Dn-51, U-12, Zone-V Asset Code -SD/2308/362/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9350,Storm Water Drain,Completed,NE-ROYAPURAM,51,4800,"Desilting to Existing SWD at Vadivelu Street(Manikandan 9th Street) in Dn-51, U-12, Zone-V (Asset Code - 055/2326/7905/2015-16)",Own Sources,5,2018-19,2018-19 NE/2018-19/9351,Storm Water Drain,Completed,NE-ROYAPURAM,51,12100,"Desilting to Existing SWD at Narayanappan Street in Dn-51, U-12, Zone-V (Asset Code -055/2318/7906/2015-16)",Own Sources,5,2018-19,2018-19 NE/2018-19/9352,Storm Water Drain,Completed,NE-ROYAPURAM,51,12600,"Desilting to Existing SWD at East Cemetry Road in Dn-51, U-12, Zone-V (Asset Code - SD/2332/363/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9354,Storm Water Drain,Completed,NE-ROYAPURAM,51,12300,"Desilting to Existing SWD at Cemetry Road in Dn-51, U-12, Zone-V (Asset Code -SD/2334/366/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9355,Storm Water Drain,Completed,NE-ROYAPURAM,51,12600,"Desilting to Existing SWD at West Cemetry Road in Dn-51, U-12, Zone-V (Asset Code -SD/2315/364/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9356,Storm Water Drain,Completed,NE-ROYAPURAM,51,4800,"Desilting to Existing SWD at Thulukkanam Street in Dn-51, U-12, Zone-V (Asset Code - 055/2316/7907/2015-16)",Own Sources,5,2018-19,2018-19 NE/2018-19/9357,Storm Water Drain,Completed,NE-ROYAPURAM,51,10900,"Desilting to Existing SWD at Kalingarayan Street in Dn-51, U-12, Zone-V (Asset Code - SD/2314/365/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9716,Storm Water Drain,Completed,NE-ROYAPURAM,51,42400,"Improvements and minor repair works to existing SWD at N.N. Garden 8th Lane in Dn-51, U-12, Zone-V Asset code: 055/2299/7904/2015-16",Own Sources,5,2018-19,2018-19 NE/2018-19/9717,Storm Water Drain,Completed,NE-ROYAPURAM,51,10800,"Improvements and minor repair works to existing SWD at Narasier Street in Dn-51, U-12, Zone-V Asset code: SD/2293/361/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9719,Storm Water Drain,Completed,NE-ROYAPURAM,51,7200,"Improvements and minor repair works to existing SWD at Ramanujam Street in Dn-51, U-12, Zone-V Asset code: SD/2289/359/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9721,Storm Water Drain,Completed,NE-ROYAPURAM,51,7200,"Improvements and minor repair works to existing SWD at Jandara Pillaiyar Koil Street in Dn-51, U-12, Zone-V Asset code SD/2296/360/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9722,Storm Water Drain,Completed,NE-ROYAPURAM,51,3600,"Improvements and minor repair works to existing SWD at Manikandan 6th Street in Dn-51, U-12, Zone-V Asset code SD/2308/362/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9723,Storm Water Drain,Completed,NE-ROYAPURAM,51,10800,"Improvements and minor repair works to existing SWD at Vadivelu Street alias Manikandan 9th Street in Dn-51, U-12, Zone-V Asset code 055/2326/7905/2015-16",Own Sources,5,2018-19,2018-19 NE/2018-19/9725,Storm Water Drain,Completed,NE-ROYAPURAM,51,25200,"Improvements and minor repair works to existing SWD at Narayanappan Street in Dn-51, U-12, Zone-V Asset code 055/2318/7906/2015-16",Own Sources,5,2018-19,2018-19 NE/2018-19/9726,Storm Water Drain,Completed,NE-ROYAPURAM,51,7200,"Improvements and minor repair works to existing SWD at East Cemetry Road in Dn-51, U-12, Zone-V Asset code SD/2332/363/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9727,Storm Water Drain,Completed,NE-ROYAPURAM,51,18000,"Improvements and minor repair works to existing SWD at Cemetry Road in Dn-51, U-12, Zone-V Asset code SD/2334/366/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9728,Storm Water Drain,Completed,NE-ROYAPURAM,51,18000,"Improvements and minor repair works to existing SWD at West Cemetry Road in Dn-51, U-12, Zone-V Asset code SD/2315/364/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9731,Storm Water Drain,Completed,NE-ROYAPURAM,51,7200,"Improvements and minor repair works to existing SWD at Thulukkanam Street in Dn-51, U-12, Zone-V Asset code 055/2316/7907/2015-16",Own Sources,5,2018-19,2018-19 NE/2018-19/9732,Storm Water Drain,Completed,NE-ROYAPURAM,51,14400,"Improvements and minor repair works to existing SWD at Kalingarayan Street in Dn-51, U-12, Zone-V .Asset Code SD/2314/365/2013-14",Own Sources,5,2018-19,2018-19 BR/2018-19/5637,Roads,Completed,BR-Bus Route Roads,52,164000,"Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan no BR/2017-18/0005975, BR/2017-18/0005974-dt.03.06.2017 and Deposit code 57/0419/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5652,Roads,Completed,BR-Bus Route Roads,52,27500,"Road cut restoration (road cut made by reliance jio) at various division in Zone 1 against the challan noBR/2017-18/0011876, BR/2017-18/011877, dt:27.07.2017 and Deposit code 57/0689/2017-18.",Deposit Works,5,2018-19,2019-20 L/2018-19/4720,Electrical,Completed,L-Electrical,52,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHHS School building at OSH Road in Div-52 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4721,Electrical,Completed,L-Electrical,52,161500,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at M.C Road Office Building in Div - 52 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 NE/2018-19/0841,Roads,Completed,NE-ROYAPURAM,52,445000,Improvement of relaying C.C road at Anjaneya Nagar 10th Lane ( asset code: 041/2348/1373/2013-14 ),Own Sources,5,2018-19,2020-21 NE/2018-19/0843,Roads,Completed,NE-ROYAPURAM,52,420000,Improvement of relaying C.C road at Anjaneya Nagar 9th Lane ( asset code : 041/2349/1372/2013-14 ),Own Sources,5,2018-19,2020-21 NE/2018-19/0851,Roads,Completed,NE-ROYAPURAM,52,118000,Improvement of relaying C.C road at Munusamy Gardern 4th Lane ( asset code : 040/2268/6067/2013-14 ),Own Sources,5,2018-19,2020-21 NE/2018-19/0857,Roads,Completed,NE-ROYAPURAM,52,63000,Improvement of relaying C.C road at Model Lane 5th Lane (asset code : 041/2351/1410/2013-14 ),Own Sources,5,2018-19,2020-21 NE/2018-19/0859,Roads,Completed,NE-ROYAPURAM,52,63000,Improvement of relaying C.C road at Model Lane 9th Lane (asset code : 041/2384/1414/2013-14),Own Sources,5,2018-19,2020-21 NE/2018-19/0956,Buildings,Completed,NE-ROYAPURAM,52,217000,"Annual maintenance and minor repairs for greater corporation of Chennai asset of Division office -52 at cemetery road in ward-52,unit-12,zone-5. B/2250/710/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/11484,Roads,Completed,NE-ROYAPURAM,52,69000,"Improvement of relaying B.T road at B.C press Road (Asset code:044/15591/8668/2013-14) Div-52,Unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11486,Roads,Completed,NE-ROYAPURAM,52,69000,"Improvement of relaying. B.T road at Nagatha koil street (Asset code:044/2382/17709/2013-14) Div-52,Unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11487,Roads,Completed,NE-ROYAPURAM,52,103000,"Improvement of relaying B.T road at Nagatha koil lane (Asset code:044/2381/17710/2013-14) Div-52,Unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/1321,Roads,Completed,NE-ROYAPURAM,52,33000,Improvement of relaying C.C road at Model Lane(Huts)(Asset code:041/2377/1457/2013-14),Own Sources,5,2018-19,2020-21 NE/2018-19/15369,Roads,Completed,NE-ROYAPURAM,52,293000,"Relaying of BT road with paver finisher at Bajanai koil street division -52,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15370,Roads,Completed,NE-ROYAPURAM,52,294000,"Relaying of BT road with paver finisher at Dhakishina moorthy koil street division -52 unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15428,Roads,Completed,NE-ROYAPURAM,52,139000,"Relaying of BT road with paver finisher in Periannan street division-52,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15429,Roads,Completed,NE-ROYAPURAM,52,129000,"Relaying of BT road with paver finisher in Durai street division-52,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/16768,Parks,Completed,NE-ROYAPURAM,52,2169000,Annual Maintenance for Anna Park at Cementry Road in Div-52 Unit-12 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/18132,Parks,Completed,NE-ROYAPURAM,52,482000,"Improvement of relaying B.T road at Jagannahan Steet ( asset code:044/2274/17675/2013-14 ) Div-52,Unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/9256,Storm Water Drain,Completed,NE-ROYAPURAM,52,9900,"Improvements and Desilting to Existing SWD at Rope godown street (,Asset code:055/15595/4917/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9361,Storm Water Drain,Completed,NE-ROYAPURAM,52,12300,"Desilting to Existing SWD at Old slaughter road in Dn-52, U-12, Zone-V(ASSET CODE:(055/2380/4906/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9364,Storm Water Drain,Completed,NE-ROYAPURAM,52,15600,"Desilting to Existing SWD at MODEL LINE 5TH Street in Dn-52, U-12, Zone-v ASSET CODE:055/2351/4907/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9368,Storm Water Drain,Completed,NE-ROYAPURAM,52,9500,"Desilting to Existing SWD at MODEL LINE 9TH Street in Dn-52, U-12, Zone-v (ASSET CODE: 055/2384/4908/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9370,Storm Water Drain,Completed,NE-ROYAPURAM,52,3000,"Desilting to Existing SWD at Velayudha pandi Street in Dn-52, U-12, Zone-v( ASSET COD;055/2275/4911/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9371,Storm Water Drain,Completed,NE-ROYAPURAM,52,6500,"Desilting to Existing SWD at Jaganathan Street in Dn-52, U-12, Zone-vASSET CODE:055/2274/4912/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9372,Storm Water Drain,Completed,NE-ROYAPURAM,52,16000,"Desilting to Existing SWD at Pichandi lane in Dn-52, U-12, Zone-v (Asset code: 055/2266/4913/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9373,Storm Water Drain,Completed,NE-ROYAPURAM,52,6500,"Desilting to Existing SWD at East rope gowdown Street in Dn-52, U-12, Zone-v asset code: 055/15595/4917/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9375,Storm Water Drain,Completed,NE-ROYAPURAM,52,18600,"Desilting to Existing SWD at CEMENTRY ROAD Street in Dn-52, U-12, Zone-v (asset code:055/2250/4915/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9376,Storm Water Drain,Completed,NE-ROYAPURAM,52,12000,"Desilting to Existing SWD at Andiappan Street in Dn-52, U-12, Zone-v ASSET CODE: 055/2280/4916/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9662,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at ANNDIAPPAN street in Dn-52, U-12, Zone-V (Asset Code- 055/2280/4916/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9663,Storm Water Drain,Completed,NE-ROYAPURAM,52,92000,"Improvements and Minor repairs to Existing SWD at CEMENTRY ROAD in Dn-52, U-12, Zone-V (Asset Code- 055/2250/4915/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9664,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at ROPE GOWDOWN STREET in Dn-52, U-12, Zone-V (Asset Code-( 055/15595/4917/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9665,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at pichandi lane in Dn-52, U-12, Zone-V (Asset Code- 055/2266/4913/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9666,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at jagnnathan street in Dn-52, U-12, Zone-V (Asset Code- 055/2274/4912/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9668,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at velayudha pandi street in Dn-52, U-12 Zone-V (Asset Code- 055/2275/4911/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9669,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at model lane 9th street in Dn-52, U-12, Zone-V (Asset Code- 055/2384/4908/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9670,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at model lane 5th street in Dn-52, U-12, Zone-V (Asset Code- 055/2351/4907/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9671,Storm Water Drain,Completed,NE-ROYAPURAM,52,38000,"Improvements and Minor repairs to Existing SWD at Old slaughter house road in Dn-52, U-12, Zone-V (Asset Code- 055/2380/4906/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9689,Buildings,Completed,NE-ROYAPURAM,52,10800,"Improvements and Minor repairs to Existing SWD at East Rope godown street in Dn-52, U-12, Zone-V (Asset Code-055/15595/4914/2013-14",Own Sources,5,2018-19,2018-19 BR/2018-19/12878,Roads,Completed,BR-Bus Route Roads,53,990000,"Attending patch work at Sydenhams road, Parthasarathy road, LG Road, EVK Sampath, Old Jail Road, Basin Bridge road etc in Dn-58,61 and 53 Zone-5",Own Sources,5,2018-19,2018-19 BR/2018-19/16720,Roads,Completed,BR-Bus Route Roads,53,780000,Attending patches - road cut portion at padavettamman koil street and concrete patches at stanley subway in DN-52 AND 53 Zone-5,Own Sources,5,2018-19,2019-20 BR/2018-19/6572,Roads,Completed,BR-Bus Route Roads,53,3028000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at North Wall Road in Dn-53, Zone-V",Grants,5,2018-19,2020-21 BR/2018-19/6573,Roads,Completed,BR-Bus Route Roads,53,1582000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Padavattamman Koil Street in Dn-53, Zone-V",Grants,5,2018-19,2020-21 D/2018-19/7095,Storm Water Drain,Completed,D-Storm Water Drains,53,2335000,"Construction of storm water drain of size 1200x1800mm along Kannan rountana upto junction of Bojarajan nagar main road Ch 0 m to 60 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7096,Storm Water Drain,Completed,D-Storm Water Drains,53,2335000,"Construction of storm water drain of size 1200x1800mm along Kannan rountana upto junction of Bojarajan nagar main road Ch 60 m to 120 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7097,Storm Water Drain,Completed,D-Storm Water Drains,53,2125000,"Construction of storm water drain of size 1200x1800mm along Kannan rountana upto junction of Bojarajan nagar main road Ch 120 m to 175 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7098,Storm Water Drain,Completed,D-Storm Water Drains,53,2335000,"Construction of storm water drain of size 1200x1800mm along Kannan rountana upto junction of Bojarajan nagar main road Ch 175 m to 235 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7100,Storm Water Drain,Completed,D-Storm Water Drains,53,2430000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch-0 to Ch 75 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2019-20 D/2018-19/7103,Storm Water Drain,Completed,D-Storm Water Drains,53,2240000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch- 75 m to Ch 145 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2019-20 D/2018-19/7104,Storm Water Drain,Completed,D-Storm Water Drains,53,2430000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch- 145 m to Ch 220 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7105,Storm Water Drain,Completed,D-Storm Water Drains,53,2430000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch- 220 m to Ch 295 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7106,Storm Water Drain,Completed,D-Storm Water Drains,53,2240000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch- 295 m to Ch 365 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7107,Storm Water Drain,Completed,D-Storm Water Drains,53,2430000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch- 365 m to Ch 440 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7108,Storm Water Drain,Completed,D-Storm Water Drains,53,2240000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch- 440 m to Ch 510 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7109,Storm Water Drain,Completed,D-Storm Water Drains,53,2430000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Vijayaragavalu street from Ch- 510 m to Ch 585 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7110,Storm Water Drain,Completed,D-Storm Water Drains,53,2065000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Parasuraman main road from junction of Kannan Rountana to junction of DBK street in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7111,Storm Water Drain,Completed,D-Storm Water Drains,53,2490000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Parasuraman main road from junction of DBK street to junction of Parthasarathy nagar main road in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7112,Storm Water Drain,Completed,D-Storm Water Drains,53,2315000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Parasuraman main road from junction of Parthasarathy nagar main to junction of Muniappan street in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7115,Storm Water Drain,Completed,D-Storm Water Drains,53,1940000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Parasuraman main road from junction of Egappan street to junction of Kannan street Railway culvert in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7116,Storm Water Drain,Completed,D-Storm Water Drains,53,1940000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Aziz Mohammed Ghose street from junction of Kannan Rountana to junction Jayaraman street junction in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7117,Storm Water Drain,Completed,D-Storm Water Drains,53,1985000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Aziz Mohammed Ghose street from junction of Jayaraman street junction to junction of DBK street in Dn- 53,Zone-V.",Own Sources,5,2018-19,2019-20 D/2018-19/7118,Storm Water Drain,Completed,D-Storm Water Drains,53,2485000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Sajja Munusamy street from junction of Kannan Rountana to junction Aziz Mohammed Ghose street (Ch 0 to Ch 105m) in Dn- 53,Zone-V.",Own Sources,5,2018-19,2019-20 D/2018-19/7119,Storm Water Drain,Completed,D-Storm Water Drains,53,1935000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Sajja Munusamy street from junction of Aziz Mohammed Ghose street to Ch-185m (Ch-105m to Ch-185m) in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7121,Storm Water Drain,Completed,D-Storm Water Drains,53,1970000,"Demolition and Reconstruction of storm water drain of size 900x900mm along Sajja Munusamy street from Ch-185m to junction of Muthiah Lane (Ch-185m to Ch-270 m) in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 D/2018-19/7471,Storm Water Drain,Completed,D-Storm Water Drains,53,2490000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Srinivasapuram 1 st main road from Ch-0 to Ch 80 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2019-20 D/2018-19/7473,Storm Water Drain,Completed,D-Storm Water Drains,53,2355000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Srinivasapuram 1 st main road from Ch-80 to Ch155m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2019-20 D/2018-19/7474,Storm Water Drain,Completed,D-Storm Water Drains,53,2355000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Srinivasapuram 1 st main road from Ch-155 to Ch230 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2019-20 D/2018-19/7476,Storm Water Drain,Completed,D-Storm Water Drains,53,2490000,"Demolition and Reconstruction of storm water drain of size 1200x1200mm along Srinivasapuram 1 st main road from Ch-300 to Ch 380 m in Dn- 53,Zone-V.",Own Sources,5,2018-19,2018-19 L/2018-19/15179,Electrical,Completed,L-Electrical,53,4972700,"Supply and replacing of 268 nos of damaged 6 / 7 Mtrs MS Lamp posts into 7 mtrs GI lamp posts with Single Straight bracket at various locations in Div - 49,50,51,52 & 53 in Zone - 5.",Own Sources,5,2018-19,2019-20 L/2018-19/16557,Electrical,Completed,L-Electrical,53,176900,Erection of 8 nos of 6/7 mtrs lamp posts and 2 nos 9.5 /11 mtrs old lamp posts and laying of 220 mtrs of 4 x 16 sqmm Alu cable at Bojaraja Nagar - Hutting Ground in Div - 53 in Zone -5.,Own Sources,5,2018-19,2019-20 L/2018-19/4705,Electrical,Completed,L-Electrical,53,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Zonal office - 5 building at Basin Bridge Road in Div-53 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4706,Electrical,Completed,L-Electrical,53,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Padavettamman Koil Street CMS in Basin Bridge Road in Div - 53 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4708,Electrical,Completed,L-Electrical,53,387200,"Supply, Installation, Testing and Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Zone - 5 office building at Basin Bridge Road in Div-53 in Zone - 5 - Phase -II",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4709,Electrical,Completed,L-Electrical,53,537600,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Lorry Depot - 5 building at Basin Bridge Road in Div-53 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 NE/2018-19/0659,Roads,Completed,NE-ROYAPURAM,53,1042000,"Attending B.T patches with Paver Finisher at Kathivakkam High Road. in Ward-53, Unit-12, Zone-5 044/19444/23544/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/0869,Roads,Completed,NE-ROYAPURAM,53,89000,"Attending B.T. Patches with Paver Finisher at Kathbada 1st and 2nd Street at Div-53,Unit-12,Zone-05. asset code: 044/2751/27570/2014-15",Own Sources,5,2018-19,2019-20 NE/2018-19/0886,Roads,Completed,NE-ROYAPURAM,53,591000,"Attending B.T. Full Road Damages Patches with Paver Finisher at Sajja Munusamy Street at Div-53,Unit-12,Zone-05. asset code: 044/1969/24432/2014-15",Own Sources,5,2018-19,2019-20 NE/2018-19/0937,Roads,Completed,NE-ROYAPURAM,53,526000,"Attending B.T. Patches with Paver Finisher at BalaSubramaniya Street at Div-53,Unit-12,Zone-05. asset code: 044/1945/27584/2014-15",Own Sources,5,2018-19,2019-20 NE/2018-19/0938,Roads,Completed,NE-ROYAPURAM,53,278000,"Attending Cement Concrete patches at New Labour Lane East in ward-53, Unit-12, Zone-5 ASSET CODE: 044/19431/27574/2014-15",Own Sources,5,2018-19,2020-21 NE/2018-19/0940,Roads,Completed,NE-ROYAPURAM,53,227000,"ATTENDING FULL ROAD DAMAGED WITH RMC M-40 CONCREATE AT NEW LABOUR LANE (west) IN DN-53,UNIT-12, ZONE-V. ASST CODE:044/19430/27573/2014-15",Own Sources,5,2018-19,2020-21 NE/2018-19/0941,Roads,Completed,NE-ROYAPURAM,53,35000,"ATTENDING FULL ROAD DAMAGED WITH RMC M-40 CONCREATE AT NEW LABOUR LANE (SOUTH) IN DN-53,UNIT-12, ZONE-V. ASST CODE: 040/2808/7952/2013-14",Own Sources,5,2018-19,2020-21 NE/2018-19/0942,Roads,Completed,NE-ROYAPURAM,53,1203000,"ATTENDING FULL ROAD DAMAGED WITH RMC M-40 CONCREATE AT P P AMMAN KOIL STREET (EAST) IN DN-53,UNIT-12, ZONE-V. ASST CODE:044/2780/27593/2014-15",Own Sources,5,2018-19,2020-21 NE/2018-19/0944,Roads,Completed,NE-ROYAPURAM,53,395000,"ATTENDING FULL ROAD DAMAGED WITH RMC M-40 CONCREATE AT P P AMMAN KOIL 4TH STREET IN DN-53,UNIT-12, ZONE-V. ASST CODE: 044/2795/27598/2014-15",Own Sources,5,2018-19,2020-21 NE/2018-19/1489,Buildings,Completed,NE-ROYAPURAM,53,405000,"Repair and Improvements to the existing Lorry station B Depot at Basin bridge road in Ward 53, Unit 12, Zone V. Asset Code :B/19443/1091/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/15372,Roads,Completed,NE-ROYAPURAM,53,314000,"Relaying of BT road with paver finisher at Parasuram main street division -53 ,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15373,Roads,Completed,NE-ROYAPURAM,53,268000,"Relaying of BT road with paver finisher at Pensioners 4th lane street division -53,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15432,Roads,Completed,NE-ROYAPURAM,53,466000,"Relaying Of B.T Road with Paver finisher at Pensioners Lane 2nd Street in Dn-53, unit-12, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15433,Roads,Completed,NE-ROYAPURAM,53,225000,"Relaying of BT road with paver finisher in Ajees mohammed gouse street division-53,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15436,Roads,Completed,NE-ROYAPURAM,53,182000,"Relaying of BT road with paver finisher in Kuppammal street division-53,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15440,Roads,Completed,NE-ROYAPURAM,53,244000,"Relaying of B.T road and Paver Finisher in Pensioner 3rd street division-53,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15441,Roads,Completed,NE-ROYAPURAM,53,255000,"Relaying of B.T road and Paver Finisher in Pensioner 2nd cross street division-53,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/15442,Roads,Completed,NE-ROYAPURAM,53,255000,"Relaying of B.T road and Paver Finisher in Pensioner 3rdCROSS street division-53,unit-12,zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/16369,Parks,Completed,NE-ROYAPURAM,53,123000,"Improvement of centre median in BRR Road at Parthasarthy Road Division -53,Unit-12,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/16371,Parks,Completed,NE-ROYAPURAM,53,336000,"Improvement of centre median in BRR Road at Dr.Vijaraghavalu Road Division -53,Unit-12,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/16372,Parks,Completed,NE-ROYAPURAM,53,280000,"Improvement of centre median in BRR Road at Basin Bridge Road Division -53,Unit-12,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/16770,Parks,Completed,NE-ROYAPURAM,53,757000,Annual Maintenance for Mint Model City Park at Model City in Div-53 Unit-12 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/16771,Parks,Completed,NE-ROYAPURAM,53,860000,Annual Maintenance for Old Andhra Bus Stand Park at wALTAX Road in Div-53 Unit-12 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/7749,Electrical,Completed,NE-ROYAPURAM,53,1541200,"Provision of 125 KVA Generator Set in Zonal Office Building, at Basin bridge Road in Division -53 /Zone -5 [SOR 2017 - 2018]",Own Sources,5,2018-19,2020-21 NE/2018-19/7750,Electrical,Completed,NE-ROYAPURAM,53,1394700,"Supply , fixing and installation of 16 HP Air conditioner in Conference Hall in Regional Office Zone - 5 at Basin Bridge Road in Div- 53 in Zone - 5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9092,Buildings,Completed,NE-ROYAPURAM,53,893000,"Dismantling of Existing Building in Kondithope UPHC at Basin Bridge Road in Dn-53, Unit-12, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/9379,Storm Water Drain,Completed,NE-ROYAPURAM,53,18600,"DESILITING OF EXISTING STORM WATER DRAIN AT PENSIONERS 3RD STREET IN DIV-53, UNIT-12, ZONE-V (asset code:044/19442/27568/2014-15)",Own Sources,5,2018-19,2018-19 NE/2018-19/9381,Storm Water Drain,Completed,NE-ROYAPURAM,53,3650,"DESITING OF EXISTING STORM WATER DRAIN AT PENSIONERS 3RD CROSS STREET IN DIV-53, UNIT-12, ZONE-V (asset code:044/19442/27568/2014-15)",Own Sources,5,2018-19,2018-19 NE/2018-19/9383,Storm Water Drain,Completed,NE-ROYAPURAM,53,9700,"DESITING OF EXISTING STORM WATER DRAIN AT KATHBADA MAIN ROAD (SOUTH SIDE) IN DIV-53, UNIT-12, ZONE-V (asset code:055/2806/3188/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9385,Storm Water Drain,Completed,NE-ROYAPURAM,53,8100,"DESITING OF EXISTING STORM WATER DRAIN AT KATHBADA MAIN ROAD (EAST SIDE) IN DIV-53, UNIT-12, ZONE-V (asset code:055/2806/3188/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9386,Storm Water Drain,Completed,NE-ROYAPURAM,53,56300,"DESITING OF EXISTING STORM WATER DRAIN AT BASIN BRIDGE ROAD (NORTH SIDE) IN DIV-53, UNIT-12, ZONE-V (asset code:R/19443/2754/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9388,Storm Water Drain,Completed,NE-ROYAPURAM,53,18600,"DESITING OF EXISTING STORM WATER DRAIN AT BASIN BRIDGE ROAD (WEST SIDE) IN DIV-53, UNIT-12, ZONE-V (asset code:R/19443/2754/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9389,Storm Water Drain,Completed,NE-ROYAPURAM,53,24300,"DESITING OF EXISTING STORM WATER DRAIN AT C.B ROAD IN DIV-53, UNIT-12, ZONE-V (asset code: 044/2791/26651/2014-15)",Own Sources,5,2018-19,2018-19 NE/2018-19/9393,Storm Water Drain,Completed,NE-ROYAPURAM,53,3300,"DESITING OF EXISTING STORM WATER DRAIN AT PADAVATTAMMAN KOIL STREET IN DIV-53, UNIT-12, ZONE-V Asset code:055/19443/4772/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9399,Storm Water Drain,Completed,NE-ROYAPURAM,53,27600,"DESITING OF EXISTING STORM WATER DRAIN AT NORTH WALL ROAD IN DIV-53, UNIT-12, ZONE-V asset code:055/2760/4771/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9411,Storm Water Drain,Completed,NE-ROYAPURAM,53,8100,"DESITING OF EXISTING STORM WATER DRAIN AT STANLY NAGAR 6TH STREET IN DIV-53, UNIT-12, ZONE-V asset code:040/2769/9696/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9413,Storm Water Drain,Completed,NE-ROYAPURAM,53,12300,"DESITING OF EXISTING STORM WATER DRAIN AT INSIDE ITI (KATHBADA MAIN ROAD) IN DIV-53, UNIT-12, ZONE-V asset code:055/2806/3188/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9414,Storm Water Drain,Completed,NE-ROYAPURAM,53,8200,"DESITING OF EXISTING STORM WATER DRAIN AT TPF ROAD (B.B ROAD) IN DIV-53, UNIT-12, ZONE-V asset code :R/19443/2754/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9415,Storm Water Drain,Completed,NE-ROYAPURAM,53,19500,"DESITING OF EXISTING STORM WATER DRAIN AT P.P AMMAN KOIL EAST STREET IN DIV-53, UNIT-12, ZONE-V asset code:055/19443/4772/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9416,Storm Water Drain,Completed,NE-ROYAPURAM,53,18000,"DESITING OF EXISTING STORM WATER DRAIN AT P.P AMMAN KOIL 1ST LANE IN DIV-53, UNIT-12, ZONE-V asset code:044/2798/27595/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9417,Storm Water Drain,Completed,NE-ROYAPURAM,53,25000,"DESITING OF EXISTING STORM WATER DRAIN AT N.N NAGAR IN DIV-53, UNIT-12, ZONE-V asset code:055/2802/6883/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9419,Storm Water Drain,Completed,NE-ROYAPURAM,53,16700,"DESITING OF EXISTING STORM WATER DRAIN AT BOJARAJA NAGAR MAIN STREET IN DIV-53, UNIT-12, ZONE-V asset code:055/1941/6442/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9420,Storm Water Drain,Completed,NE-ROYAPURAM,53,6600,"DESITING OF EXISTING STORM WATER DRAIN AT BOJARAJA NAGAR 1ST STREET IN DIV-53, UNIT-12, ZONE-V asset code:040/1944/9766/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9421,Storm Water Drain,Completed,NE-ROYAPURAM,53,11400,"DESITING OF EXISTING STORM WATER DRAIN AT BOJARAJA NAGAR 2ND STREET IN DIV-53, UNIT-12, ZONE-V asset code:040/1942/9768/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9422,Storm Water Drain,Completed,NE-ROYAPURAM,53,4800,"DESITING OF EXISTING STORM WATER DRAIN AT BOJARAJA NAGAR SOUTH LANE IN DIV-53, UNIT-12, ZONE-V asset code:040/1986/9774/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9630,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements and Minor Repair Work to Existing SWD at Bojaraja Nagar South Lane in Dn-53, Unit-12, Zone-5 (asset code:055/1940/3186/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9631,Storm Water Drain,Completed,NE-ROYAPURAM,53,62600,"Improvements Minor Repair Works to Existing SWD at Inside ITI (Kathbada Main Road) in Dn-53, Unit-12, Zone-5 (asset code: 055/2806/3188/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9633,Storm Water Drain,Completed,NE-ROYAPURAM,53,10800,"Improvements Minor Repair Work to Existing SWD at Pensioners Lane 3rd Street in Dn-53, Unit-12, Zone-5 asset code:044/19442/27568/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9634,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at Pensioners Lane 3rd Cross Street in in Dn-53, Unit-12, Zone-5 asset code: 044/19442/27568/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9636,Storm Water Drain,Completed,NE-ROYAPURAM,53,3600,"Improvements Minor Repair Work to Existing SWD at Kathbada Main Road in Dn-53, Unit-12, Zone-5 asset code: 055/2806/3188/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9637,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at Kathbada Main Road in Dn-53, Unit-12, Zone-5 (asset code: 055/2806/3188/2013-14 )",Own Sources,5,2018-19,2018-19 NE/2018-19/9638,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvements Minor Repair Work to Existing SWD at Basin Bridge Road in Dn-53, Unit-12, Zone-5 (ASSET CODE: R/19443/2754/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9639,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvements Minor Repair Work to Existing SWD at Basin Bridge Road in Dn-53, Unit-12, Zone-5 (asset code:R/19443/2754/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9640,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvements Minor Repair Work to Existing SWD at C.B. Road in Dn-53, Unit-12, Zone-5 Asset code: 044/2791/26651/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9641,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at Padavattamman Koil Street in Dn-53, Unit-12, Zone-5 (asset code:043/2758/482/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9643,Storm Water Drain,Completed,NE-ROYAPURAM,53,10800,"Improvements Minor Repair Work to Existing SWD at North Wall Road in Dn-53, Unit-12, Zone-5 (asset code: 055/2760/4779/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9646,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at Stanly Nagar 6th Street in Dn-53, Unit-12, Zone-5 (asset code:055/2770/4780/2013-14 )",Own Sources,5,2018-19,2018-19 NE/2018-19/9647,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at TPF Road (BB Road) in Dn-53, Unit-12, Zone-5 (asset code:R/19443/2754/2013-14 )",Own Sources,5,2018-19,2018-19 NE/2018-19/9648,Storm Water Drain,Completed,NE-ROYAPURAM,53,14400,"Improvements Minor Repair Work to Existing SWD at P.P. Amman Koil East Street in Dn-53, Unit-12, Zone-5 (asset code:055/19443/4772/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9649,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at P.P. Amman Koil 1st Lane in Dn-53, Unit-12, Zone-5 (asset code:055/19443/4772/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9650,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at NN Nagar in Dn-53, Unit-12, Zone-5 Asset code: 040/2740/9778/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/9652,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements Minor Repair Work to Existing SWD at Bojaraja Nagar 1st Street in Dn-53, Unit-12, Zone-5 (asset code: 055/1940/3186/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9653,Storm Water Drain,Completed,NE-ROYAPURAM,53,7200,"Improvements and Minor Repair Work to Existing SWD at Bojaraja Nagar 2nd Street in Dn-53, Unit-12, Zone-5 asset code: 055/1941/6442/2014-15",Own Sources,5,2018-19,2018-19 B/2018-19/12070,Buildings,Completed,B-Buildings,54,5500000,"Construction of Multipurpose hall at Vadamalai Maistry street in Dn-54, Zone -5",MLACDS,5,2018-19,2019-20 D/2018-19/2884,Storm Water Drain,Completed,D-Storm Water Drains,54,1752000,"Providing RWH well to the temple tank at Biragi Madam Venkatesaperumal Koil,General Muthiya street & Kasi Viswanathar Koil,Krishnappa tank street under Sustainable Water Secruity Mission in Dn - 54 & 57,Zone - 5.",SMART CITY - SWD,5,2018-19,2019-20 L/2018-19/4728,Electrical,Completed,L-Electrical,54,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post at Wall Tax Road in Div-54 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/6869,Electrical,Completed,L-Electrical,54,976100,"Replacement of 2178mtrs 0f 2cX16sq.mm pvc alu cable at Vadamalai Street, Tirupathi Street, PKG Gardern and Various Street, division-58, Zone-5",Own Sources,5,2018-19,2018-19 NE/2018-19/0644,Buildings,Completed,NE-ROYAPURAM,54,316000,"Repairs Work and Annual Maintenance of Existing to Amma Unavagam(OLD) at 428, Mint Street DN-54,U-13,Z-5. ( Asset Code- B/2430/1838/2014-15)",Own Sources,5,2018-19,2019-20 NE/2018-19/0645,Buildings,Completed,NE-ROYAPURAM,54,164000,"Repairs and Annual Maintenance of Existing to Amma Unavagam(NEW) at 508,Mint Street DN-54,U-13,Z-5. ( Asset Code-B/2430/1159/2014-15)",Own Sources,5,2018-19,2019-20 NE/2018-19/11580,Roads,Completed,NE-ROYAPURAM,54,1328000,"Improvement of Relaying CC Road at Reliance Rice Mill Street in Div-54, Unit-13, Zone-5 (Asset Code -044/3977/16332/2013-14)",Own Sources,5,2018-19,2020-21 NE/2018-19/11581,Roads,Completed,NE-ROYAPURAM,54,2386000,"Improvement of Relaying CC Road in Chakkarai Street at Div-54, Unit-13, Zone-5 (Asset Code - 044/3988/16297/2013-14)",Own Sources,5,2018-19,2020-21 NE/2018-19/11582,Roads,Completed,NE-ROYAPURAM,54,1810000,"Improvement of Relaying CC Road at Zinda Street in Div-54, Unit-13, Zone-5 (Asset Code -044/3985/16349/2013-14)",Own Sources,5,2018-19,2020-21 NE/2018-19/11583,Roads,Completed,NE-ROYAPURAM,54,1905000,"Improvement of Relaying CC Road at Ibrahim Street in Div-54, Unit-13, Zone-5 (Asset Code -044/3987/16301/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11589,Roads,Completed,NE-ROYAPURAM,54,2210000,"Improvement of Relaying CC Road at Vadamalai Street in Div-54, Unit-13, Zone-5 (Asset Code - 044/4001/16345/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11590,Roads,Completed,NE-ROYAPURAM,54,4470000,"Improvement of Relaying CC Road at Thirupalli Street in Div-54, Unit-13, Zone-5 (Asset Code - 040/4024/5711/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11592,Roads,Completed,NE-ROYAPURAM,54,1022000,"Improvement of Relaying BT Road at Saravanan Street in Div-54, Unit-13, Zone-5 (Asset Code-044/2418/16107/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/16779,Parks,Completed,NE-ROYAPURAM,54,768000,Annual Maintenance for Sivananam Park at Peddu Street in Div-54 Unit-13Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/2490,Buildings,Completed,NE-ROYAPURAM,54,241000,"Repairs work and Annual Maintenance to Existing Division office at 337, Wall Tax Road in Dn-54, Unit-13, Zone-V. (Asset Code-B/3973/591/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/3101,Buildings,Completed,NE-ROYAPURAM,54,999900,"Operation and Maintenance of High Quality treated Drinking Water Plant (RO/UV Filtration) Thirupalli Bus Stand,Sowkarpettai,(For 12 Months) Div-54,Unit-12,Zone-05 087/3973/61/2013-14",Own Sources,5,2018-19,2019-20 NE/2018-19/7156,Roads,Completed,NE-ROYAPURAM,54,72000,"PROVIDING BIN FLATFORM AT VARIOUS PLACES IN DN-54 U-13, Z-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/8830,Footpath,Completed,NE-ROYAPURAM,54,439000,"Providing Footpath AT V.O.C.Salai in Front of Public Toilet in Div-54 , Unit-13 , Zone-5 (Asset Code-053/3973/1954/2013-14)",MLACDS,5,2018-19,2019-20 NE/2018-19/9131,Storm Water Drain,Completed,NE-ROYAPURAM,54,16100,"Improvements and Desilting to Existing SWD at Saravanan Street in Dn-54, U-13, Zone-V(Asset Code:SD/2418/352/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9132,Storm Water Drain,Completed,NE-ROYAPURAM,54,24500,"Improvements and Desilting to Existing SWD at Bashyakaralu Street in Dn-54, U-13, Zone-V(Asset Code:SD/2441/353/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9133,Storm Water Drain,Completed,NE-ROYAPURAM,54,7400,"Improvements and Desilting to Existing SWD at Sundaram Street in Dn-54, U-13, Zone-V(Asset Code-SD/4000/357/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9134,Storm Water Drain,Completed,NE-ROYAPURAM,54,17700,"Improvements and Desilting repairs to Existing SWD at V.O.C Salai in Dn-54, U-13, Zone-V(Asset Code-053/3973/1953/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9135,Storm Water Drain,Completed,NE-ROYAPURAM,54,13700,"Improvements and Desilting to Existing SWD at Perumal koil Garden 3rd Lane in Dn-54, U-13, Zone-V(Asset Code-040/4016/5703/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9136,Storm Water Drain,Completed,NE-ROYAPURAM,54,10200,"Improvements and Desilting to Existing SWD at Perumal koil Garden 4th Lane in Dn-54, U-13, Zone-V(Asset Code-053/4015/1961/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9137,Storm Water Drain,Completed,NE-ROYAPURAM,54,8000,"Improvements and Desilting to Existing SWD at Mint street in Dn-54, U-13, Zone-V(Asset Code-055/3981/8079/2015-16)",Own Sources,5,2018-19,2018-19 NE/2018-19/9138,Buildings,Completed,NE-ROYAPURAM,54,119800,"Improvements and Minor repairs to Existing SWD at Mint Street in Dn-54, U-13, Zone-V(Asset Code-055/3981/8079/2015-16)",Own Sources,5,2018-19,2018-19 NE/2018-19/9139,Buildings,Completed,NE-ROYAPURAM,54,124800,"Improvements and Minor repairs to Existing SWD at Saravanan in Dn-54, U-13, Zone-V(Asset Code-SD/2418/352/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9140,Buildings,Completed,NE-ROYAPURAM,54,113900,"Improvements and Minor repairs to Existing SWD at Bashyakaralu Street in Dn-54, U-13, Zone-V(Asset Code-SD/2441/353/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9141,Buildings,Completed,NE-ROYAPURAM,54,106900,"Improvements and Minor repairs to Existing SWD at Sundaram in Dn-54, U-13, Zone-V(Asset Code-SD/4000/357/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9142,Buildings,Completed,NE-ROYAPURAM,54,147700,"Improvements and Minor repairs to Existing SWD at V.O.C Salai in Dn-54, U-13, Zone-V(Asset Code-053/3973/1953/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9143,Buildings,Completed,NE-ROYAPURAM,54,148000,"Improvements and Minor repairs to Existing SWD at Perumal koil Garden 3rd Lane in Dn-54, U-13, Zone-V(Asset Code-040/4016/5703/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9144,Buildings,Completed,NE-ROYAPURAM,54,91900,"Improvements and Minor repairs to Existing SWD at Perumal koil Garden 4th Lane in Dn-54, U-13, Zone-V(Asset Code-053/4015/1961/2013-14)",Own Sources,5,2018-19,2018-19 BR/2018-19/5650,Roads,Completed,BR-Bus Route Roads,55,64000,Road cut restoration (road cut made by reliance jio) at various division in Zone 1 against the challan no BR/2017-18/0011847 BR/2017-18/0011849 dt:26.07.2017 and Deposit code 57/0686/2017-18.,Deposit Works,5,2018-19,2019-20 BR/2018-19/5935,Roads,Completed,BR-Bus Route Roads,55,55000,Road cut restoration (road cut made by bharti airtel) at various division in Zone 1 against the challan no BR/2017-18/0011908 BR/2017-18/0011911 dt:27.07.2017 and Deposit code 57/0692/2017-18.,Deposit Works,5,2018-19,2019-20 L/2018-19/4702,Electrical,Completed,L-Electrical,55,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post building at Amman Koil Street in Div-55 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4703,Electrical,Completed,L-Electrical,55,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Portuguese Church Street CMS in Div - 55 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4704,Electrical,Completed,L-Electrical,55,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit office -13 building at Shanmugam Street in Div-55 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4722,Electrical,Completed,L-Electrical,55,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post building at Appu Street in Div-55 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 NE/2018-19/0640,Buildings,Completed,NE-ROYAPURAM,55,118000,"Repairs Work and Annual Maintenance of Existing to Amma Unavagam at Nattu Pillaiyar koil street DN-55, U-13, Z-5. ( Asset Code- 019/2680/101/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/0641,Buildings,Completed,NE-ROYAPURAM,55,111000,"Repairs and Annual Maintenance of Existing to Amma Unavagam at St.Xavier Street DN-55,U-13,Z-5. ( Asset Code- 019/2448/164/2014-15 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11518,Roads,Completed,NE-ROYAPURAM,55,960000,"Improvements to Cement Concrete Road at Meeran Labbai Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11519,Roads,Completed,NE-ROYAPURAM,55,104000,"Improvements to Cement Concrete Road at Muthu (N) Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11520,Roads,Completed,NE-ROYAPURAM,55,220000,"Improvements to Cement Concrete Road at Mofukhan Garden Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11521,Roads,Completed,NE-ROYAPURAM,55,1024000,"Improvements to Cement Concrete Road at MeilaiPeriya Thambi Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11522,Roads,Completed,NE-ROYAPURAM,55,356000,"Improvements to Cement Concrete Road at Ramalingam Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11523,Roads,Completed,NE-ROYAPURAM,55,164000,"Improvements to Cement Concrete Road at Periyannan Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11524,Roads,Completed,NE-ROYAPURAM,55,78000,"Improvements to Cement Concrete Road at Buddi Sahib Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11525,Roads,Completed,NE-ROYAPURAM,55,221000,"Improvements to Cement Concrete Road at Mari Muthu Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11526,Roads,Completed,NE-ROYAPURAM,55,645000,"Improvements to Cement Concrete Road at Mangammal Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11527,Roads,Completed,NE-ROYAPURAM,55,507000,"Improvements to Cement Concrete Road at Thandava Moorthy Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11528,Roads,Completed,NE-ROYAPURAM,55,510000,"Improvements to Cement Concrete Road at Davidson Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11529,Roads,Completed,NE-ROYAPURAM,55,577000,"Improvements to Cement Concrete Road at Sadaiyappa Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11530,Roads,Completed,NE-ROYAPURAM,55,286000,"Improvements to Cement Concrete Road at Varadier Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11534,Roads,Completed,NE-ROYAPURAM,55,173000,"Improvements to Cement Concrete Road at Pattu Rasapa Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11536,Roads,Completed,NE-ROYAPURAM,55,98000,"Improvements to Cement Concrete Road at Appa Samy Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11537,Roads,Completed,NE-ROYAPURAM,55,213000,"Improvements to Cement Concrete Road at Kumarappa Street in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11539,Roads,Completed,NE-ROYAPURAM,55,196000,"Improvements to Cement Concrete Road at Amman Kovil Pokada Lane in DIv-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11544,Roads,Completed,NE-ROYAPURAM,55,844000,"Improvements to B.T Road at Portugese Chruch Street (Part) in Div-55,Unit-13,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/14103,Buildings,Completed,NE-ROYAPURAM,55,1100000,"Constuction of Auditorium building over the first floor to CMS at Portchuguese Chruch Street in Division-55,Unit-13,Zone-5 (Under Harbour A/C MLA Scheme 2018-2019)",MLACDS,5,2018-19,2019-20 NE/2018-19/15521,Buildings,Completed,NE-ROYAPURAM,55,1000000,"Providing Bore well and fixing India Mark II Pump at Barract street ,Portugueze street , Nattu Pillayar Koil street and Subramani street in Ward -55 ,Unit-13 ,Zone-5",MLACDS,5,2018-19,2019-20 NE/2018-19/2876,Buildings,Completed,NE-ROYAPURAM,55,435000,"Repairs and Annual Maintenance to Health post at Amman koil Street in Dn-55, Unit-13, Zone-V. Asset code- 017/2676/34/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/2877,Buildings,Completed,NE-ROYAPURAM,55,317000,"Repairs and Annual Maintenance to Health post at Appu Maistry Street in Dn-55, Unit-13, Zone-V. (Asset code- 017/2661/33/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/3150,Buildings,Completed,NE-ROYAPURAM,55,157000,"Repairs and Annual Maintenance to SI Office (Old Dispensary) at St.Xavier Street in Dn-55, Unit-13, Zone-V",Own Sources,5,2018-19,2018-19 NE/2018-19/3154,Buildings,Completed,NE-ROYAPURAM,55,307000,"Repairs and Annual Maintenance to Unit-13 office and A.E Office Dn-55 at Shanmugam Street in Dn-55, Unit-13, Zone-V",Own Sources,5,2018-19,2020-21 NE/2018-19/6168,Buildings,Completed,NE-ROYAPURAM,55,3590000,"Construction of Additional Room in Barracks Play Ground Gym at Portuguese Street in Dn-55,Unit-13,Zone-5(MLA Fund) ( Asset Code- 019/2447/100/2013-14",MLACDS,5,2018-19,2018-19 NE/2018-19/7155,Roads,Completed,NE-ROYAPURAM,55,72000,"PROVIDING BIN FLATFORM AT VARIOUS PLACES IN DN-55 U-13, Z-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9167,Storm Water Drain,Completed,NE-ROYAPURAM,55,53900,"Improvements and Desilting to Existing SWD at Amman Koil Street in Dn-55, U-13, Zone-V(Asset Code: 055/2676/4699/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9168,Storm Water Drain,Completed,NE-ROYAPURAM,55,13700,"Improvements and Desilting to Existing SWD at Anaikara konan Street in Dn-55, U-13, Zone-V(Asset Code-055/2456/4814/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9169,Storm Water Drain,Completed,NE-ROYAPURAM,55,13700,"Improvements and Desilting to Existing SWD at Barracks 1st Lane in Dn-55, U-13, Zone-V(Asset Code:055/2455/4817/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9170,Storm Water Drain,Completed,NE-ROYAPURAM,55,43800,"Improvements and Desilting to Existing SWD at Barracks Street in Dn-55, U-13, Zone-V(Asset Code-055/2453/4816/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9171,Storm Water Drain,Completed,NE-ROYAPURAM,55,40900,"Improvements and Desilting to Existing SWD at Davidson Street in Dn-55, U-13, Zone-V(Asset Code:055/2644/4820/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9172,Storm Water Drain,Completed,NE-ROYAPURAM,55,18200,"Improvements and Desilting SWD at Girigory Street in Dn-55, U-13, Zone-V(Asset Code:055/2463/4815/2013-14 )",Own Sources,5,2018-19,2018-19 NE/2018-19/9173,Storm Water Drain,Completed,NE-ROYAPURAM,55,15400,"Improvements and Desilting to Existing SWD at Nattu Pillaiyar Koil Street in Dn-55, U-13, Zone-V(Asset Code:055/2680/4697/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9174,Storm Water Drain,Completed,NE-ROYAPURAM,55,102000,"Improvements and Desilting to Existing SWD at P.V.Iyer Street in Dn-55, U-13, Zone-V(Asset Code: 055/2630/4700/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9175,Storm Water Drain,Completed,NE-ROYAPURAM,55,77000,"Improvements and Desilting to Existing SWD at Prakasam Salai in Dn-55, U-13, Zone-V(AssetCode:055/2652/4694/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9176,Storm Water Drain,Completed,NE-ROYAPURAM,55,71000,"Improvements and Desilting to Existing SWD at Sevenwells Street in Dn-55, U-13, Zone-V(Assetcode:055/15615/4690/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9177,Storm Water Drain,Completed,NE-ROYAPURAM,55,26200,"Improvements and Desilting to Existing SWD at St Xavier Street in Dn-55, U-13, Zone-V(Asset Code:055/2470/4701/2013-14 )",Own Sources,5,2018-19,2018-19 NE/2018-19/9178,Storm Water Drain,Completed,NE-ROYAPURAM,55,38100,"Improvements and Desilting to Existing SWD at Subramani Street in Dn-55, U-13, Zone-V (Asset Code:055/2669/4698/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9179,Storm Water Drain,Completed,NE-ROYAPURAM,55,31100,"Improvements and Desilting to Existing SWD at Old Jail Road in Dn-55, U-13, Zone-V(Asset Code:053/2444/1939/2013-14 )",Own Sources,5,2018-19,2018-19 NE/2018-19/9201,Buildings,Completed,NE-ROYAPURAM,55,140300,"Improvements and Minor repairs to Existing SWD at Subramani Street in Dn-55, U-13, Zone-V (Asset Code- 055/2669/4698/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9202,Buildings,Completed,NE-ROYAPURAM,55,129500,"Improvements and Minor repairs to Existing SWD at Prakasam salai in Dn-55, U-13, Zone-V (Asset Code- 055/2652/4694/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9203,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at Amman Koil Street in Dn-55, U-13, Zone-V (Asset Code- 055/2676/4696/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9204,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at Anaikara konar Street in Dn-55, U-13, Zone-V (Asset Code- 055/2456/4814/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9205,Buildings,Completed,NE-ROYAPURAM,55,7200,"Improvements and Minor repairs to Existing SWD at Barracks 1st Lane in Dn-55, U-13, Zone-V (Asset Code- 055/2455/4817/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9206,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at Barracks Street in Dn-56, U-13, Zone-V (Asset Code- 055/2453/4816/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9207,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at Davidson Street in Dn-55, U-13, Zone-V (Asset Code- 055/2644/4820/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9208,Buildings,Completed,NE-ROYAPURAM,55,28800,"Improvements and Minor repairs to Existing SWD at Girigory Street in Dn-55, U-13, Zone-V (Asset Code- 055/2463/4815/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9209,Buildings,Completed,NE-ROYAPURAM,55,7200,"Improvements and Minor repairs to Existing SWD at Nattu Pillaiar Koil Street in Dn-55, U-13, Zone-V (Asset Code- 055/2680/4697/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9210,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at P.V.Iyer Street in Dn-55, U-13, Zone-V (Asset Code- 055/2630/4700/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9211,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at St Xavier Street in Dn-55, U-13, Zone-V (Asset Code- 055/2470/4701/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9212,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at Sevenwells Street in Dn-55, U-13, Zone-V (Asset Code- 055/15615/4690/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9213,Buildings,Completed,NE-ROYAPURAM,55,18000,"Improvements and Minor repairs to Existing SWD at Old Jail Road in Dn-55, U-13, Zone-V (Asset Code- 053/2444/1939/2013-14)",Own Sources,5,2018-19,2018-19 BR/2018-19/1172,Roads,Completed,BR-Bus Route Roads,56,692000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 5 against the challan 07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017n and Deposit code 57/0666/2017-18.",Deposit Works,5,2018-19,2018-19 BR/2018-19/5938,Roads,Completed,BR-Bus Route Roads,56,209000,Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan noBR/2017-18/0006416 BR/2017-18/0006420 dt:08.06.2017 and Deposit code 57/0431/2017-18.,Deposit Works,5,2018-19,2019-20 D/2018-19/2914,Storm Water Drain,Completed,D-Storm Water Drains,56,1102000,"Rejuvenation and other improvements to the temple tank at Mallikeswarar Koil, Lingi chetty Street including construction of RWH well under Sustainable Water Secruity Mission in Dn - 56,Zone - 5.",SMART CITY - SWD,5,2018-19,2020-21 NE/2018-19/0637,Buildings,Completed,NE-ROYAPURAM,56,215000,"Repair Works and Annual Maintenance of Amma Unavagam at BRN Garden DN-56,U-13,Z-5. ( Asset Code- 019/2501/93/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/0638,Buildings,Completed,NE-ROYAPURAM,56,173000,"Repair Works and Annual Maintenance of Amma Unavagam at Coral Merchant Street DN-56,U-13,Z-5. (018/2538/72/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11743,Roads,Completed,NE-ROYAPURAM,56,619000,"IMPROVEMENTS TO CC ROAD AT THAIYAPPAN LANE IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE- 044/2515/16368/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11744,Roads,Completed,NE-ROYAPURAM,56,255000,"IMPROVEMENTS CC ROAD AT SAVAIMUTHIYA 1st LANE IN DIVISION-56,UNIT-13,ZONE-5(ASSED CODE - 041/2535/1223/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11745,Roads,Completed,NE-ROYAPURAM,56,226000,"IMPROVEMENTS TO CC ROAD AT SAIVAMUTHIYA 2nd LANE IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE - 041/2534/1224/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11746,Roads,Completed,NE-ROYAPURAM,56,71000,"IMPROVEMENTS TO CC ROAD AT SAIVAMUTHIYA 3rd LANE IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE - 041/2533/1225/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11747,Roads,Completed,NE-ROYAPURAM,56,75000,"IMPROVEMENTS TO CC ROAD AT SAIVAMUTHIYA 4th LANE IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE - 041/2532/1226/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11748,Roads,Completed,NE-ROYAPURAM,56,261000,"IMPROVEMENTS TO CC ROAD AT SAIVAMUTHIYA 5th LANE IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE - 041/2531/1227/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11749,Roads,Completed,NE-ROYAPURAM,56,190000,"IMPROVEMENTS TO CC ROAD AT PEDARIYAR KOIL 1st LANE IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE - 040/2484/5662/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11751,Roads,Completed,NE-ROYAPURAM,56,210000,"IMPROVEMENTS TO CC ROAD AT DEVARAJ LANE IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE - 040/2537/5690/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11752,Roads,Completed,NE-ROYAPURAM,56,481000,"IMPROVEMENTS TO CC ROAD AT SAVARIMUTHU LANE IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE - 040/2557/5691/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11753,Roads,Completed,NE-ROYAPURAM,56,720000,"IMPROVEMENTS TO CC ROAD AT AMMAN KOIL, STREET IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE - 044/2492/16375/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11754,Roads,Completed,NE-ROYAPURAM,56,132000,"IMPROVEMENTS TO CC ROAD AT FRANCISTURIN STREET IN DIVISION-56,UNIT-13,ZONE-5.(ASSET CODE -044/2500/16374/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11755,Roads,Completed,NE-ROYAPURAM,56,185000,"IMPROVEMENTS TO CC ROAD AT VENKATESAN STREET IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE - 044/2513/16376/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11756,Roads,Completed,NE-ROYAPURAM,56,70000,"IMPROVEMENTS TO CC ROAD AT VENKATESAN LANE IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE - 044/2513/16377/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11758,Roads,Completed,NE-ROYAPURAM,56,1702000,"IMPROVEMENTS TO BT ROAD AT LINGU CHETTY STREET IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE -044/2520/16384/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11819,Roads,Completed,NE-ROYAPURAM,56,810000,"IMPROVEMENTS TO BT ROAD AT KRISHNAN KOIL STREET IN DIVISION-56,UNIT-13,ZONE-5(ASSET CODE -044/2545/16398/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11820,Roads,Completed,NE-ROYAPURAM,56,2902000,"IMPROVEMENTS TO BT ROAD AT CORAL MERCHANT STREET IN DIVISION-56,UNTI-13,ZONE-5(ASSET CODE -044/2538/16394/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11821,Roads,Completed,NE-ROYAPURAM,56,1439000,"IMPROVEMENTS TO BT ROAD AT SALAI VINAYAGAR KOIL STREET IN DIVISION-56,UNTI-13,ZONE-5(ASSET CODE -044/2528/16401/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11822,Roads,Completed,NE-ROYAPURAM,56,348000,"IMPROVEMENTS TO BT ROAD AT CHELLA MUTHU LANE IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE - 044/2540/16418/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11823,Roads,Completed,NE-ROYAPURAM,56,3953000,"IMPROVEMENTS TO BT ROAD AT PEDARIYAR KOVIL STREET IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE-044/2481/16362/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11824,Roads,Completed,NE-ROYAPURAM,56,1406000,"IMPROVEMENTS TO BT ROAD AT NEW STREET IN DIVISION-56,UNIT-13,ZONE-5,(ASSET CODE - 044/2539/16538/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/15534,Buildings,Completed,NE-ROYAPURAM,56,1000000,"Providing Bore well and Fixing Mark II Pump at Salai Vinayakar Street ,Pedariayan koil Streer ,St Xavier Street , Geills Street , Thambuchetty Street and Madurai vasal Street in Division -56 , Unit-13 , Zone-5",MLACDS,5,2018-19,2019-20 NE/2018-19/16783,Parks,Completed,NE-ROYAPURAM,56,1262000,Annual Maintenance for Terrace Garden Park at Ibrahim Salai in Div-56 Unit-13 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/2879,Buildings,Completed,NE-ROYAPURAM,56,920000,"Repairs and Annual Maintenance to UPHC at BRN Gardent in Dn-56, Unit-13, Zone-V, (Asset code- 016/2501/7/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/3161,Buildings,Completed,NE-ROYAPURAM,56,300000,"Repairs and Annual Maintenance to A.E Office, at Ibrahim Salai in Dn-56, Unit-13, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/3165,Buildings,Completed,NE-ROYAPURAM,56,300000,"Repairs and Annual Maintenance to SI Office, CI Office at Geills street in Dn-56, Unit-13, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/7150,Roads,Completed,NE-ROYAPURAM,56,91000,"PROVIDING BIN FLATFORM AT VARIOUS PLACES IN DN-56, U-13, Z-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/8954,Roads,Completed,NE-ROYAPURAM,56,1077000,"Attending various B.T Patches at Nainiyappan street in Division- 56, Unit- 13, Zone-5.",Own Sources,5,2018-19,2018-19 NE/2018-19/8957,Roads,Completed,NE-ROYAPURAM,56,265000,"Attending various B.T Patches at Salai vinayagar koil street in Division- 56 Unit-13, Zone-5.",Own Sources,5,2018-19,2018-19 NE/2018-19/9214,Storm Water Drain,Completed,NE-ROYAPURAM,56,109000,"Improvements and Desilting to Existing SWD at Prakasam salai ( Broadway road) in Dn-56, U-13, Zone-V (ASSET CODE-055/2504/4802/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9215,Storm Water Drain,Completed,NE-ROYAPURAM,56,40700,"Improvements and Desilting to Existing SWD at St. Xavier Street in Dn-56, U-13, Zone-V (ASSET CODE- 055/2516/4803/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9216,Storm Water Drain,Completed,NE-ROYAPURAM,56,43500,"Improvements and Desilting to Existing SWD at Amman Koil Street in Dn-56, U-13, Zone-V (ASSET CODE- 055/2492/4804/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9217,Storm Water Drain,Completed,NE-ROYAPURAM,56,62000,"Improvements and Desilting to Existing SWD at Meera Labbai Street in Dn-56, U-13, Zone-V (ASSET CODE- 055/2496/4805/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9218,Storm Water Drain,Completed,NE-ROYAPURAM,56,15000,"Improvements and Desilting to Existing SWD at Salai Vinayagar Koil Street in Dn-56, U-13, Zone-V (ASSET CODE- 055/2528/4806/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9219,Storm Water Drain,Completed,NE-ROYAPURAM,56,14200,"Improvements and Desilting to Existing SWD at Geils Street in Dn-56, U-13, Zone-V (ASSET CODE- 055/2550/4807/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9220,Storm Water Drain,Completed,NE-ROYAPURAM,56,8500,"Improvements and Desilting to Existing SWD at Savarimuthu Lane in Dn-56, U-13, Zone-V (ASSET CODE- 055/2557/4808/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9221,Storm Water Drain,Completed,NE-ROYAPURAM,56,51000,"Improvements andr Desilting to Existing SWD at Ebrahim Salai (BRR) in Dn-56, U-13, Zone-V (ASSET CODE- 055/2536/4809/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9222,Storm Water Drain,Completed,NE-ROYAPURAM,56,5400,"Improvements and Desilting to Existing SWD at Ebrahim Salai (BRR) in Dn-56, U-13, Zone-V (ASSET CODE- 055/2536/4810/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9223,Storm Water Drain,Completed,NE-ROYAPURAM,56,28500,"Improvements and Desilting to Existing SWD at Old Jail Road in Dn-56, U-13, Zone-V (ASSET CODE- 043/2494/834/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9224,Buildings,Completed,NE-ROYAPURAM,56,168000,"Improvements and Minor repairs to Existing SWD at Amman Koil Street in Dn-56, U-13, Zone-V (Asset Code- 055/2492/4804/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9225,Buildings,Completed,NE-ROYAPURAM,56,170000,"Improvements and Minor repairs to Existing SWD at St. Xavier Street in Dn-56, U-13, Zone-V (Asset Code- 055/2516/4803/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9226,Buildings,Completed,NE-ROYAPURAM,56,92000,"Improvements and Minor repairs to Existing SWD at Savarimuthu Lane in Dn-56, U-13, Zone-V (Asset Code- 055/2557/4808/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9227,Buildings,Completed,NE-ROYAPURAM,56,18000,"Improvements and Minor repairs to Existing SWD at Meera Labbai Street in Dn-56, U-13, Zone-V (Asset Code- 055/2496/4805/2013-14 )",Own Sources,5,2018-19,2018-19 NE/2018-19/9228,Buildings,Completed,NE-ROYAPURAM,56,18000,"Improvements and Minor repairs to Existing SWD at Prakasam salai in Dn-56, U-13, Zone-V (Asset Code- 055/2504/4802/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9229,Buildings,Completed,NE-ROYAPURAM,56,21600,"Improvements and Minor repairs to Existing SWD at Salai Vinayagar Koil Street in Dn-56, U-13, Zone-V (Asset Code- 055/2528/4806/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9230,Buildings,Completed,NE-ROYAPURAM,56,21600,"Improvements and Minor repairs to Existing SWD at Geils Street in Dn-56, U-13, Zone-V (Asset Code- 055/2550/4807/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9231,Buildings,Completed,NE-ROYAPURAM,56,42000,"Improvements and Minor repairs to Existing SWD at Old Jail Road in Dn-56, U-13, Zone-V (Asset Code- 043/2494/834/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9232,Buildings,Completed,NE-ROYAPURAM,56,28800,"Improvements and Minor repairs to Existing SWD at Ebrahim Salai (BRR) in Dn-56, U-13, Zone-V (Asset Code-055/2536/4809/2013-14)",Own Sources,5,2018-19,2018-19 BR/2018-19/5640,Roads,Completed,BR-Bus Route Roads,57,72900,"Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan noBR/2017-18/0222839, BR/2017-18/0222825 dt:03.06.2017 and Deposit code 57/0425/2017-18.",Deposit Works,5,2018-19,2019-20 D/2018-19/14914,Storm Water Drain,Completed,D-Storm Water Drains,57,25800000,"Demolition and Re-Construction of Storm Water Drain of Size 900x900mm along Annapillai street from junction of Waltax road to junction of Prakasam salai in Dn.-57,Zone - 5,Package - 7.",SMART CITY - SWD,5,2018-19,2020-21 D/2018-19/2883,Storm Water Drain,Completed,D-Storm Water Drains,57,1974000,"Restoration to the temple tank at Biragi Madam Venkatesaperumal Koil,General Muthiya Mudali street & Kasi Viswnathar Koil,Krisnappa tank street under Sustainable Water Secruity Mission in Dn - 57 & 54 ,Zone - 5.",SMART CITY - SWD,5,2018-19,2019-20 D/2018-19/6167,Storm Water Drain,Completed,D-Storm Water Drains,57,2045000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at Kalyanapuram 4 to 6 lanes in Division - 57, Zone - 5",Own Sources,5,2018-19,2019-20 D/2018-19/6521,Storm Water Drain,Completed,D-Storm Water Drains,57,2430000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at Kalyanapuram 1 to 3 lanes in Division - 57, Zone - 5",Own Sources,5,2018-19,2019-20 L/2018-19/11069,Electrical,Completed,L-Electrical,57,925500,"Over head wire and faulty cable Replacement of 2178 mtrs of 2C x 16 Sq.mm PVC Alu cable at Athiappan street,water basin street,General Muthiya street street and various street in Division-57, Zone-V.",Own Sources,5,2018-19,2019-20 L/2018-19/11964,Electrical,Completed,L-Electrical,57,197600,Supply and replacement of 3 nos of damaged 9.5 mtrs MS lamp post with 3 nos of 9.5 MTRS GI Lamp Post with single arch bracket at Prakasam Salai in div 57 in Zone - 5,Own Sources,5,2018-19,2019-20 L/2018-19/12843,Electrical,Completed,L-Electrical,57,97900,"Replacement of the damaged of 96 nos 2core fuse box at various street In div 54,57,58, in Zone - 5",Own Sources,5,2018-19,2019-20 L/2018-19/13983,Electrical,Completed,L-Electrical,57,123600,Replacement of 259 mtr of 2*16 sqmm cable for play ground at water basin street DIV 57 zone 5,Own Sources,5,2018-19,2019-20 L/2018-19/4726,Electrical,Completed,L-Electrical,57,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Printing Press at Wall Tax Road in Div-57 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4727,Electrical,Completed,L-Electrical,57,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Corporation higher Secondary School at V.O.C Salai in Div-57 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/6660,Electrical,Completed,L-Electrical,57,888400,"Electrification work with 8 Nos of Air Conditioner, 91 Nos of tube lights , 38 Nos of fan and 220m 3 1/2*x 25 sqmm of Aluminum Cable at Printing Press, Greater Corporation of Chennai in Division- 57 Zone - 5",Own Sources,5,2018-19,2019-20 NE/2018-19/0475,Roads,Completed,NE-ROYAPURAM,57,2065000,"Relaying of Cement concrete road at South Market Street in Division-57, Zone-5 ( Asset code:040/2708/5806/2013-14)",MLACDS,5,2018-19,2019-20 NE/2018-19/0487,Buildings,Completed,NE-ROYAPURAM,57,190000,"Repair Works and Annual Maintenance of Amma Unavagam at Anna (P) Street in division-57,Unit-13,Zone-5 Asset code:156/2692/734/2010-11",Own Sources,5,2018-19,2019-20 NE/2018-19/11636,Roads,Completed,NE-ROYAPURAM,57,2687000,"Improvements to CC Road at Audiappa Naicken Street in Division-57,Unit-13, Zone-5 (Asset Code:044/2735/16441/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11637,Roads,Completed,NE-ROYAPURAM,57,1642000,"Improvements to CC Road at South Market Street in Division-57,Unit-13, Zone-5 (Asset Code:040/2708/5806/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11641,Roads,Completed,NE-ROYAPURAM,57,1884000,"Improvements to CC Road at Badrian Street in Division-57,Unit-13, Zone-5 (Asset Code:040/2723/5808/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11642,Roads,Completed,NE-ROYAPURAM,57,2654000,"Improvements to CC Road at Bundar Street in Division-57,Unit-13, Zone-5 (Asset Code:040/2721/5807/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11643,Roads,Completed,NE-ROYAPURAM,57,846000,"Improvements to CC Road at Chandrappa Street in Division-57,Unit-13, Zone-5 (Asset Code:040/4171/5722/2013-14 )",Own Sources,5,2018-19,2019-20 NE/2018-19/11644,Roads,Completed,NE-ROYAPURAM,57,585000,"Improvements to CC Road at Hussain Street in Division-57,Unit-13, Zone-5 (Asset Code:040/4193/5801/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11646,Roads,Completed,NE-ROYAPURAM,57,845000,"Improvements to CC Road at Irulappan Street in Division-57,Unit-13, Zone-5 (Asset Code:040/4192/5725/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11649,Roads,Completed,NE-ROYAPURAM,57,1144000,"Improvements to CC Road at Periya Uthandi Street in Division-57,Unit-13, Zone-5 (Asset Code: 044/2717/16459/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11653,Roads,Completed,NE-ROYAPURAM,57,1068000,"Improvements to CC Road at Reddy Raman Street in Division-57,Unit-13, Zone-5 (Asset Code:040/2704/5382/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11674,Roads,Completed,NE-ROYAPURAM,57,439000,"Improvements to CC Road at Somasundaram Street in Division-57,Unit-13, Zone-5 (Asset Code:040/2702/5813/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11675,Roads,Completed,NE-ROYAPURAM,57,324000,"Improvements to CC Road at Thambu Naicken Street in Division-57,Unit-13, Zone-5 (Asset Code:040/2728/5826/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11676,Roads,Completed,NE-ROYAPURAM,57,287000,"Improvements to CC Road at Venkatasamy Lane in Division-57,Unit-13, Zone-5 (Asset Code:040/4165/5799/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11678,Roads,Completed,NE-ROYAPURAM,57,180000,"Improvements to CC Road at Theradi Lane in Division-57,Unit-13, Zone-5 (Asset Code:040/2730/5824/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11680,Roads,Completed,NE-ROYAPURAM,57,3628000,"Improvements to CC Road at Davidson Street in Division-57,Unit-13, Zone-5 (Asset Code:044/2718/1477/2005-06)",Own Sources,5,2018-19,2019-20 NE/2018-19/11681,Roads,Completed,NE-ROYAPURAM,57,7497000,"Improvements to CC Road at Mint Street in Division-57,Unit-13, Zone-5 (Asset Code:040/2696/5408/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/14193,Buildings,Completed,NE-ROYAPURAM,57,273000,"Repairs and improvements to the P.C at Kalayanapuram Street in Division-57,Unit-13, Zone-5 (Asset Code:033/15489/512/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/7154,Roads,Completed,NE-ROYAPURAM,57,91000,"PROVIDING BIN PLATFORM AT VARIOUS PLACES IN DN-57, U-13, Z-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9233,Storm Water Drain,Completed,NE-ROYAPURAM,57,133000,"Improvements and Desilting to Existing SWD at Anna (P) Street in Dn-57, U-13, Zone-V (Asset code-055/2692/4687/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9234,Storm Water Drain,Completed,NE-ROYAPURAM,57,3700,"Improvements and Desilting to Existing SWD at South Market Street in Dn-57, U-13, Zone-V Asset Code- 055/2708/4854/2013-14",Own Sources,5,2018-19,2018-19 NE/2018-19/9237,Storm Water Drain,Completed,NE-ROYAPURAM,57,36500,"Improvements and Desilting to Existing SWD at Ramanan Road (N) in Dn-57, U-13, Zone-V (Asset Code:055/4185/4848/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9238,Storm Water Drain,Completed,NE-ROYAPURAM,57,8500,"Improvements and Desilting to Existing SWD at Ramanan Road (S) in Dn-57, U-13, Zone-V (Asset Code:055/4185/4849/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9239,Buildings,Completed,NE-ROYAPURAM,57,22100,"Improvements and Minor Repair to Existing SWD at Kalyanapuram cross Street in Dn-57, U-13, Zone-V (Asset Code-",Own Sources,5,2018-19,2018-19 NE/2018-19/9240,Buildings,Completed,NE-ROYAPURAM,57,62600,"Improvements and Minor repairs to Existing SWD at Ramanan Road (N) in Dn-57, U-13, Zone-V (Asset Code-055/4185/4848/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9241,Buildings,Completed,NE-ROYAPURAM,57,7200,"Improvements and Minor repairs to Existing SWD at Jatkapuram slum in Dn-57, U-13, Zone-V (Asset Code-055/4190/4847/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9242,Buildings,Completed,NE-ROYAPURAM,57,85800,"Improvements and Minor repairs to Existing SWD at South Market Lane in Dn-57, U-13, Zone-V (Asset Code-055/2708/4854/2013-14)",Own Sources,5,2018-19,2018-19 NE/2018-19/9243,Buildings,Completed,NE-ROYAPURAM,57,183500,"Improvements and Minor repairs to Existing SWD at Anna (P) Street in Dn-57, U-13, Zone-V (Asset Code-055/2692/4687/2013-14)",Own Sources,5,2018-19,2018-19 B/2018-19/11292,Buildings,Completed,B-Buildings,58,1148366,"Additional works for Night shelter at Rajiv Ganthi Hospital at E.V.R Salai in DN-58, Zone-5",Own Sources,5,2018-19,2019-20 B/2018-19/11444,Buildings,Completed,B-Buildings,58,8736354,"Proposed construction of Night shelter at Driver street, Egmore in Dn-61,Unit-14,Zone-V",Own Sources,5,2018-19,2020-21 B/2018-19/13614,Buildings,Completed,B-Buildings,58,2360000,"Supplying and Fixing Furnitures at Urban Community Health Centre in Perungudi in Dn - 184, Zone - 14.",Own Sources,5,2018-19,2019-20 B/2018-19/13616,Buildings,Completed,B-Buildings,58,2370000,"Supplying and Fixing Furnitures at Urban Community Health Centre in Valasaravakkam in Dn - 151, Zone - 11",Own Sources,5,2018-19,2019-20 B/2018-19/13617,Buildings,Completed,B-Buildings,58,326000,"Supplying and Fixing of Fire Rsisting filing cabinet in the Chambers of Commiossionerm, Deputy Commissioner (Works) and Principal Chief Engineer office in Ripon Building Campus in DN 58 Zone V",Own Sources,5,2018-19,2019-20 B/2018-19/13697,Buildings,Completed,B-Buildings,58,830000,Supplying and Fixing of Furnitures for Departments in Amma Maligai and Ripon Building in Dn 58 Zone V,Own Sources,5,2018-19,2019-20 B/2018-19/15016,Buildings,Completed,B-Buildings,58,147000,Supplying of HDU Storage Units for Public Health Department in Amma Maligai in Ripon Building campus in Dn 58 Zone V,Own Sources,5,2018-19,2019-20 B/2018-19/16719,Buildings,Completed,B-Buildings,58,2500000,Repair and improvement works to Ripon building campus and Amma Maligai in DN 58 Zone 5,Own Sources,5,2018-19,2021-22 B/2018-19/2890,Buildings,Completed,B-Buildings,58,1030000,Supplying and Fixing of MS structure for car shed in Ripon Building Campus in Dn 58 Zone V,Own Sources,5,2018-19,2018-19 B/2018-19/2893,Buildings,Completed,B-Buildings,58,15098700,"Repair and improvements to the existing Convetional public Conveniences in Zone 1,2,3&4",Own Sources,5,2018-19,2019-20 B/2018-19/2956,Buildings,Completed,B-Buildings,58,3130000,Supplying and Providing furnitures and storage units for various Departments in Amma Maligai and Ripon Building in Dn 58 Zone V,Own Sources,5,2018-19,2018-19 B/2018-19/4480,Buildings,Completed,B-Buildings,58,2500000,REPAIR AND IMPROVEMENT WORK TO RIPON BUILDING CAMPUS AND AMMA MAALIGAI IN DN 58 ZONE 5.,Own Sources,5,2018-19,2020-21 B/2018-19/4852,Buildings,Completed,B-Buildings,58,9779000,SUPPLY INSTALLATION AND MAINTENANCE AND HOUSE KEEPING OF 80 SEATS OF VARIOUS TYPE OF RENTAL TOILET FOR A PERIOD OF ONE YEAR IN VARIOUS PLACES AT ZONE4 & ZONE5.,Own Sources,5,2018-19,2019-20 BR/2018-19/0667,Roads,Completed,BR-Bus Route Roads,58,300000,"Attending patches and pot holes at EVK Sampah salai in Dn-58, Zone 5 (SDRF Fund)",Grants,5,2018-19,2018-19 BR/2018-19/15125,Roads,Completed,BR-Bus Route Roads,58,440000,"Attending patch work in old jail road, kannan round about, Mint parthasarathy road and TH Road, vijayaragavalu street in Dn-53 in Zone - 5",Own Sources,5,2018-19,2019-20 BR/2018-19/15361,Roads,Completed,BR-Bus Route Roads,58,960000,"Attending repair / Maintenance work at Sydenhams center median, and parrys corner traffic island and Bus shelter repair works at Arunachalam street, Dy Mayor kabalamoorthy salai, Walajah salai and GP road in various division in Zone-5",Own Sources,5,2018-19,2019-20 BR/2018-19/5931,Roads,Completed,BR-Bus Route Roads,58,18500,Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan no BR/2017-18/0011880 BR/2017-18/001184 dt:01.08.2017 and Deposit code 57/0690/2017-18.,Deposit Works,5,2018-19,2019-20 BR/2018-19/7347,Roads,Completed,BR-Bus Route Roads,58,109000,"Restoration of road cut made by CMWSSB at Hunters Road in Zone 5, against challan No BR/2017-18/0027093",Deposit Works,5,2018-19,2019-20 BR/2018-19/7348,Roads,Completed,BR-Bus Route Roads,58,92000,"Restoration of road cut made by CMWSSB at Perambur barracks road in Zone-5, against challan no BR/2017-18/0029166",Deposit Works,5,2018-19,2019-20 BR/2018-19/7351,Roads,Completed,BR-Bus Route Roads,58,61000,Restoration of road cut made by CMWSSB at East coovum river road in zone-5 against challan no BR/2017-18/0030498,Deposit Works,5,2018-19,2019-20 L/2018-19/11241,Electrical,Completed,L-Electrical,58,178200,Supply and errection of 3 nos of 9.5 MTR Lamp Post with double arch bracket and 140 mtrs of 3 1/2 * 25 SQMM Alumininum Cable in Sydems Road (CMRL) 58 in Zone - 5,Own Sources,5,2018-19,2019-20 L/2018-19/12842,Electrical,Completed,L-Electrical,58,177300,Replacement of damage post 2 nos of 9.5 MTR Lamp Post with double arch bracket and 1 nos of 9.5 MTR Lamp Post with double arch bracket 140 mtrs of 3 1/2 * 25 SQMM Alumininum Cable in Sydems Road 58 in Zone - 5,Own Sources,5,2018-19,2019-20 L/2018-19/13075,Electrical,Completed,L-Electrical,58,1256300,"Supply and erection of 33 nos 7mtr GI street lamp post with single arch bracket and replacement of 1222mtrs 3 1/2 X25sq.mm Alu cable at Ritherton Road in Division-58, Zone-5",Own Sources,5,2018-19,2019-20 L/2018-19/13975,Electrical,Completed,L-Electrical,58,1290000,"Proposal for 16 nos of 9.5 Mtr Gi lamp post with Double Arch Bracket , 2 nos 9.5 Mtr Gi lamp post with Triple Arch Bracket and 4 nos 9.5 Mtr Gi lamp post with Single Arch Bracket with 875 mtr of 3 1/2 * 25 sqmm at E.V.R SALAI (CMRL ) In Divison 58 zone 5",Deposit Works,5,2018-19,2019-20 L/2018-19/14378,Electrical,Completed,L-Electrical,58,928800,"Over head wire and faulty cable Replacement of 2244mtrs of 2C x 16 Sq.mm PVC Alu cable VV koil street,Ek guru street,lala kutty street and various street in Division-58, Zone-V.",Own Sources,5,2018-19,2019-20 L/2018-19/14379,Electrical,Completed,L-Electrical,58,118300,"Supply and erection of 4 nos 9mtr no value post with 1mtr MS straight bracket and replacement of 120mtrs of 4cX16sq.mm pvc alu cable at N.H.Road Play Ground in Division-58, Zone-5.",Own Sources,5,2018-19,2019-20 L/2018-19/1856,Electrical,Completed,L-Electrical,58,35400,"Erection 2 nos 7mtr post and replacement of 79 mtrs of 2C x 16 Sq.mm PVC Alu cable in old Depot for vehicle parking uses at A.P.Road, in Division-58, under Zone- V.",Own Sources,5,2018-19,2018-19 L/2018-19/3943,Electrical,Completed,L-Electrical,58,441500,"To provide Electrification work in Birth and Death department at Ripon building Northern side in Ripon building Premises in Dn-58,Zone-V",Own Sources,5,2018-19,2019-20 L/2018-19/4724,Electrical,Completed,L-Electrical,58,3998700,"Supply, Installation, Testing & Commissioning of 53 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma maligai at Sydenhams Rd,Kannappar Thidal,Periyamet in Div-58 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2020-21 L/2018-19/4725,Electrical,Completed,L-Electrical,58,5879600,"Supply, Installation, Testing & Commissioning of 78 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Revenue Department Building Ripon Building at Sydenhams Rd,Kannappar Thidal,Periyamet in Div-58 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2020-21 L/2018-19/4729,Electrical,Completed,L-Electrical,58,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at School building at Vathiyar Kanda Pillai Street in Div-58 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4730,Electrical,Completed,L-Electrical,58,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Greater Corporation of Chennai Middle School at A.P.Road in Div-58 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4731,Electrical,Completed,L-Electrical,58,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Greater Corporation of Chennai Middle School at Vaikokaran Street in Div-58, Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4732,Electrical,Completed,L-Electrical,58,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Dispensary at Kadappa Rangaiah Street in Div-58 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4734,Electrical,Completed,L-Electrical,58,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Center at Kannappar Thidal in Div-58 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4834,Electrical,Completed,L-Electrical,58,2642000,"Electrification work at Greater Corporation of Chennai Girls Schools in Division- 58 & Ramasamy Street School in division-56, Zone - 5.",Own Sources,5,2018-19,2018-19 L/2018-19/6170,Electrical,Completed,L-Electrical,58,94800,"Electrification work at Greater Corporation of Chennai Schools in Division-53,58 & 60, Zone - 5.",Own Sources,5,2018-19,2019-20 L/2018-19/6366,Electrical,Completed,L-Electrical,58,593000,"Supply and erection of 2 nos 9mtr lamp post with double arch bracket and replacement of 805mtrs of 3 1/2X25sq.mm pvc alu cable at EVR Salai from Rippon Buildings Signal to Gandhi Irvine Bridge in Division-58, Zone-5.",Own Sources,5,2018-19,2019-20 L/2018-19/6868,Electrical,Completed,L-Electrical,58,231000,"Replacement of 550mtrs 0f 2cX16sq.mm pvc alu cable at Ragavendra Park, division-58, Zone-5",Own Sources,5,2018-19,2018-19 L/2018-19/9681,Electrical,Completed,L-Electrical,58,12314100,"Provision of Electrification, PAC, UPS, DG Set & Fire Suppression System along with Civil Work for the Proposed GIS Server Room located at 1st Floor Amma Maaligai, Ripon Building Div-58, Zone-5",Own Sources,5,2018-19,2020-21 NE/2018-19/0209,Buildings,Completed,NE-ROYAPURAM,58,2577000,"Providing Housekeeping Cleaning class room and Toilet for V.K Pillai Street, A.P Road, Vykakaran Street, Rotler Street, Mint Street, Ellis Puram, S.M Nagar, Veerasamy Street, Varadharaja Puram (Pandianth Road), Langs Garden Road, Narasingapuram, West Coovam Road, Goyathope in CPS,CMS,CHS AND CHSS SCHOOL in Div-58,59,61,62&63,Unit-14,zONE-5",Own Sources,5,2018-19,2019-20 NE/2018-19/11658,Roads,Completed,NE-ROYAPURAM,58,357000,"IMPROVEMENTS TO BT ROAD AT KARIAPPA STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11660,Roads,Completed,NE-ROYAPURAM,58,1302000,"IMPROVEMENTS TO BT ROAD PERIYANNA (M) STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11661,Buildings,Completed,NE-ROYAPURAM,58,1034000,"IMPROVEMENTS TO BT ROAD AT KARPURA (M) STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11663,Buildings,Completed,NE-ROYAPURAM,58,378000,"IMPROVEMENTS TO BT ROAD AT KOVALAM MUTHU STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11664,Roads,Completed,NE-ROYAPURAM,58,168000,"IMPROVEMENTS TO BT ROAD AT LALA KUTTY STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11665,Buildings,Completed,NE-ROYAPURAM,58,1078000,"IMPROVEMENTS TO BT ROAD ROTTI KIDANGU THIRUVENGADAM STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11666,Roads,Completed,NE-ROYAPURAM,58,644000,"IMPROVEMENTS TO BT ROAD AT DR. ALAGAPPA STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11667,Roads,Completed,NE-ROYAPURAM,58,379000,"IMPROVEMENTS TO BT ROAD AT THOPPAI STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11668,Buildings,Completed,NE-ROYAPURAM,58,610000,"IMPROVEMENTS TO BT ROAD AT PRATHAPET ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11906,Buildings,Completed,NE-ROYAPURAM,58,2840000,"REPAIR AND IMPROVEMENTS TO EXISTING TPF AT BASIN ELEPHANT BRIDGE ROAD IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/12245,Buildings,Completed,NE-ROYAPURAM,58,483800,"SERVICING AND REPAIRING OF WEIGH BRIDGE (SOUTH) AT TPF AT BASIN ELEPHANT GATE BRIDGE ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/13322,Buildings,Completed,NE-ROYAPURAM,58,469000,"IMPROVEMENTS TO OFFICE OF THE MEMBER OF PARLIAMENT (CENTRAL CHENNAI) AT POONAMALLEE HIGH ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/13325,Buildings,Completed,NE-ROYAPURAM,58,106000,"IMPROVEMENTS TO ALLIKULAM SHOPPING COMPLEX IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/13389,Buildings,Completed,NE-ROYAPURAM,58,2700000,"Construction of Stage and additional room and a Staff toilet at Chennai girls higher Secondary School at Rolters Street Choolai in Ward-58, Unit-14, Zone-5",MLACDS,5,2018-19,2020-21 NE/2018-19/13435,Buildings,Completed,NE-ROYAPURAM,58,39800,"Demolition of Night Center at Stringer Street in Dn-58,U-14,Z-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/13519,Buildings,Completed,NE-ROYAPURAM,58,488000,"DEMOLITION OF EXISTING CHENNAI MIDDLE SCHOOL AT ROTLER STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/14394,Buildings,Completed,B-Buildings,58,223000,IMPROVEMENTS TO SMART CLASS ROOM IN CHENNAI HIGH SCHOOL IN ROTLER STREET IN DIV-58 UNIT- 14 ZONE-05,Own Sources,5,2018-19,2019-20 NE/2018-19/15167,Parks,Completed,NE-ROYAPURAM,58,973000,"Supply and Erection of Green Outdoor Gym at My Ladies Park in Dn-58, Unit-14, Zone-5 ( MPLADS FUND 2018-19)",MPLADS,5,2018-19,2020-21 NE/2018-19/16784,Parks,Completed,NE-ROYAPURAM,58,3706000,Annual Maintenance for Myladis Park at Sydams Road in Div-58 Unit-14 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/16785,Parks,Completed,NE-ROYAPURAM,58,84000,Annual Maintenance for Jermaiah Park at Dovton in Div-52 Unit-12 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/16786,Parks,Completed,NE-ROYAPURAM,58,223000,Annual Maintenance for Dovton Tower Clock Park at Doveton junction in Div-58 Unit-14 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/16787,Parks,Completed,NE-ROYAPURAM,58,1102000,Annual Maintenance for Ragevandra Park at A.P. Road in Div-58 Unit-14 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/2282,Roads,Completed,NE-ROYAPURAM,58,2338000,"IMPROVEMENTS TO BT ROAD AT KALATHIYAPPA STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/8652,Parks,Completed,NE-ROYAPURAM,58,2900000,"Providing childrens play material and formation of tennis court in Ragavendra park at Avadhanam pappier road in Div-58,U-14,Z-5..",MLACDS,5,2018-19,2019-20 NE/2018-19/9576,Storm Water Drain,Completed,NE-ROYAPURAM,58,43000,"DESILTING OF EXISITING STORM WATER DRAIN AT SYDENHAMS ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9578,Storm Water Drain,Completed,NE-ROYAPURAM,58,63700,"DESILTING OF EXISITING STORM WATER DRAIN AT VEPERY HIGH ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9579,Storm Water Drain,Completed,NE-ROYAPURAM,58,43700,"DESILTING OF EXISITING STORM WATER DRAIN AT ALLIKULAM LINK ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9580,Storm Water Drain,Completed,NE-ROYAPURAM,58,70000,"DESILTING OF EXISITING STORM WATER DRAIN AT VENKATACHALAM STREET IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9582,Storm Water Drain,Completed,NE-ROYAPURAM,58,26500,"DESILTING OF EXISITING STORM WATER DRAIN AT SAMY (P) STREET IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9583,Storm Water Drain,Completed,NE-ROYAPURAM,58,3890,"DESILTING OF EXISITING STORM WATER DRAIN AT PEOPLE PARKS ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9584,Storm Water Drain,Completed,NE-ROYAPURAM,58,12000,"DESILTING OF EXISITING STORM WATER DRAIN AT THIRUVENGADAM STREET IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9585,Storm Water Drain,Completed,NE-ROYAPURAM,58,6500,"DESILTING OF EXISITING STORM WATER DRAIN AT VADAMALAI STREET IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9586,Storm Water Drain,Completed,NE-ROYAPURAM,58,57800,"DESILTING OF EXISITING STORM WATER DRAIN AT KALATHIYAPPA ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9587,Storm Water Drain,Completed,NE-ROYAPURAM,58,11300,"DESILTING OF EXISITING STORM WATER DRAIN AT R.T. (M) STREET IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9588,Storm Water Drain,Completed,NE-ROYAPURAM,58,107000,"DESILTING OF EXISITING STORM WATER DRAIN AT E.V.K. SAMPATH SALAI IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9589,Storm Water Drain,Completed,NE-ROYAPURAM,58,11800,"DESILTING OF EXISITING STORM WATER DRAIN AT KANNAPPAR THIDAL CANAL IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9590,Storm Water Drain,Completed,NE-ROYAPURAM,58,46500,"DESILTING OF EXISITING STORM WATER DRAIN AT JOTHI VENKATACHALAM ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9591,Storm Water Drain,Completed,NE-ROYAPURAM,58,19600,"DESILTING OF EXISITING STORM WATER DRAIN AT STRINGERS ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9592,Storm Water Drain,Completed,NE-ROYAPURAM,58,23500,"DESILTING OF EXISITING STORM WATER DRAIN AT NAVAL HOSPITAL ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9593,Storm Water Drain,Completed,NE-ROYAPURAM,58,57300,"DESILTING OF EXISITING STORM WATER DRAIN AT AVADHANA PAPPIER ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9594,Storm Water Drain,Completed,NE-ROYAPURAM,58,7000,"DESILTING OF EXISITING STORM WATER DRAIN AT ROTLER STREET IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9595,Storm Water Drain,Completed,NE-ROYAPURAM,58,20700,"DESILTING OF EXISITING STORM WATER DRAIN AT DR. ALAGAPPA ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9596,Storm Water Drain,Completed,NE-ROYAPURAM,58,37500,"DESILTING OF EXISITING STORM WATER DRAIN AT HUNTERS ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9597,Storm Water Drain,Completed,NE-ROYAPURAM,58,16400,"DESILTING OF EXISITING STORM WATER DRAIN AT VALLIAMMAL ROAD IN DIVISION-58, UNIT-14, Z0NE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9797,Buildings,Completed,NE-ROYAPURAM,58,382000,"Improvements to Doveton tower clock at Jarmiah Road in Div-58,Unit-14,Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9878,Storm Water Drain,Completed,NE-ROYAPURAM,58,36000,"Improvements to Existing Storm Water Drain at Sydenham Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9879,Storm Water Drain,Completed,NE-ROYAPURAM,58,18000,"Improvements to Existing Storm Water Drain at Vepery High Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9880,Storm Water Drain,Completed,NE-ROYAPURAM,58,14400,"Improvements to Existing Storm Water Drain at Allikulam Link Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9881,Storm Water Drain,Completed,NE-ROYAPURAM,58,7200,"Improvements to Existing Storm Water Drain at Vengatachalam Street in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9882,Storm Water Drain,Completed,NE-ROYAPURAM,58,18000,"Improvements to Existing Storm Water Drain at People Park Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9883,Storm Water Drain,Completed,NE-ROYAPURAM,58,10800,"Improvements to Existing Storm Water Drain at Vadamalai Street in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9884,Storm Water Drain,Completed,NE-ROYAPURAM,58,14400,"Improvements to Existing Storm Water Drain at Kalathiappa Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9885,Storm Water Drain,Completed,NE-ROYAPURAM,58,10800,"Improvements to Existing Storm Water Drain at RT Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9886,Storm Water Drain,Completed,NE-ROYAPURAM,58,18000,"Improvements to Existing Storm Water Drain at Jothi Venkatachalam Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9887,Storm Water Drain,Completed,NE-ROYAPURAM,58,28800,"Improvements to Existing Storm Water Drain at Stringers Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9888,Storm Water Drain,Completed,NE-ROYAPURAM,58,18000,"Improvements to Existing Storm Water Drain at Naval Hospital Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9889,Storm Water Drain,Completed,NE-ROYAPURAM,58,10800,"Improvements to Existing Storm Water Drain at Avadhana Papier Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9890,Storm Water Drain,Completed,NE-ROYAPURAM,58,10800,"Improvements to Existing Storm Water Drain at Rotler Street in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9891,Storm Water Drain,Completed,NE-ROYAPURAM,58,7200,"Improvements to Existing Storm Water Drain at Alagappa Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9892,Storm Water Drain,Completed,NE-ROYAPURAM,58,10800,"Improvements to Existing Storm Water Drain at Valliammal Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9893,Storm Water Drain,Completed,NE-ROYAPURAM,58,14400,"Improvements to Existing Storm Water Drain at Hunters Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9894,Storm Water Drain,Completed,NE-ROYAPURAM,58,18000,"Improvements to Existing Storm Water Drain at Ritherdon Road in Division-58, Unit-14, Z0ne-V",Own Sources,5,2018-19,2018-19 B/2018-19/11491,Buildings,Completed,B-Buildings,59,8736354,"Proposed construction of Night shelter at N.S.C Bose road in Dn-59,Unit-14,Zone-V",Own Sources,5,2018-19,2019-20 BR/2018-19/11457,Roads,Completed,BR-Bus Route Roads,59,485000,"Marking Thermoplastic on Cycle Track (Swami sivananda salai, Kamaraj salai, Flag staff Road etc in Dn-59, Zone-4",Own Sources,5,2018-19,2019-20 BR/2018-19/15034,Roads,Completed,BR-Bus Route Roads,59,935000,"Attending patch work at Swami sivananda salai (in front of CMWSSB pumping station) in Dn-59, Zone - 5.",Own Sources,5,2018-19,2019-20 BR/2018-19/18209,Roads,Completed,BR-Bus Route Roads,59,1735000,ATTENDING PATCH WORK AT PAPER MILLS ROAD AND VARIOUS BUS ROUTE ROAD IN ZONE-6,Own Sources,5,2018-19,2019-20 BR/2018-19/3407,Roads,Completed,BR-Bus Route Roads,59,18300,"Road cut restoration (road cut made by reliance jio) at various division in Zone 5 against the challan no 07/2017-18/0377458,07/2017-18/0377463 DT: 21.07.2017 and Deposit code 57/0668/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5651,Roads,Completed,BR-Bus Route Roads,59,63500,"Road cut restoration (road cut made by reliance jio) at various division in Zone 1 against the challan no BR/2017-18/0011936 , BR/2017-18/0011937 dt:27.07.2017 and Deposit code 57/0696/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5945,Roads,Completed,BR-Bus Route Roads,59,281000,"Road cut restoration (road cut made by bharti airtel) at 63rd division in Zone 5 against the challan no 06/2017-18/0244518,06/2017-18/12.06.2017 and Deposit code 57/0465/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/6605,Roads,Completed,BR-Bus Route Roads,59,499000,"Providing speed breakers at Frazer bridge road, Kannan street and Arunachalam street (various location) in Zone 5.",Own Sources,5,2018-19,2019-20 BR/2018-19/6746,Footpath,Completed,BR-Bus Route Roads,59,1074000,"Footpath Repair Works at Muthusamay Salai in Dn-59, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6767,Footpath,Completed,BR-Bus Route Roads,59,1192000,"Footpath Repair Works at Pallavan Salai in Dn-59, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6769,Footpath,Completed,BR-Bus Route Roads,59,548000,"Footpath Repair Works at Wallajah Road in Dn-59, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6772,Footpath,Completed,BR-Bus Route Roads,59,887000,"Footpath Repair Works at Evening Bazaar Road in Dn-59, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6773,Footpath,Completed,BR-Bus Route Roads,59,1060000,"Footpath Repair Works at Rattan Bazaar Road in Dn-59, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6774,Footpath,Completed,BR-Bus Route Roads,59,1060000,"Footpath Repair Works at Basin Bridge Road in Dn-53, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6776,Footpath,Completed,BR-Bus Route Roads,59,1312000,"Footpath Repair Works at Vepery High Road in Dn-58, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6777,Footpath,Completed,BR-Bus Route Roads,59,810000,"Footpath Repair Works at Ripon Building Annexure Road in Dn-58, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6778,Footpath,Completed,BR-Bus Route Roads,59,1969000,"Footpath Repair Works at E.V.K. Sampath Road in Dn-58, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/6779,Footpath,Completed,BR-Bus Route Roads,59,290000,"Footpath Repair Works at Whannels Road in Dn-61, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/8251,Roads,Completed,BR-Bus Route Roads,59,685000,"Strengthening of existing MLA Hostel service road in Dn-59, Zone-5",Own Sources,5,2018-19,2019-20 D/2018-19/14915,Storm Water Drain,Completed,D-Storm Water Drains,59,25095000,"Demolition and Re-Construction of Storm Water Drain of size 1500x1500mm along Muthusamy Salai and Esplanade road from junction of North Fort Road to Railway culvert in Muthusamy salai in Dn.-59,Zone-5,Package - 8.",SMART CITY - SWD,5,2018-19,2020-21 D/2018-19/2899,Storm Water Drain,Completed,D-Storm Water Drains,59,722000,"Rejuvenation and other improvements to the temple tank at Chenna Malleswarar Chenna Kesavaperumal Koil,Devaraja Mudali street including construction of RWH well under Sustainable Water Secruity Mission in Dn - 59,Zone - 5.",SMART CITY - SWD,5,2018-19,2019-20 D/2018-19/2912,Storm Water Drain,Completed,D-Storm Water Drains,59,1283000,"Rejuvenation and other improvements to the temple tank at Ekambareswarar Koil,Thangasalai including construction of RWH well under Sustainable Water Secruity Mission in Dn - 59,Zone - 5.",SMART CITY - SWD,5,2018-19,2019-20 L/2018-19/10883,Electrical,Completed,L-Electrical,59,1818100,"PROPOSAL OF 16NOS.OF 9.5MTR GI LAMPPOST WITH DOUBLE ARCH BRACKET AND 32NOS.OF 150-165W LED FITTINGS AT PRRSONS CENTER MEDIAN DIV59,ZONE-5.",Own Sources,5,2018-19,2020-21 L/2018-19/17116,Electrical,Completed,L-Electrical,59,962500,"Removal and Refixing 23 nos of 9.5 Mtr OH lamp post with Double Arch Bracket , with 1335 mtr of 3 1/2 * 25 sqmm at E.V.R Salai and Wall tax div 59 Zone 5",Own Sources,5,2018-19,2019-20 L/2018-19/17117,Electrical,Completed,L-Electrical,59,356300,Removal and Re-Erection of 20 mtrs Highmast at Muthu swami Road junction of Espalande Road in Div 59 Zone - 5.,Own Sources,5,2018-19,2019-20 L/2018-19/4736,Electrical,Completed,L-Electrical,59,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Dispensary at Balamuthu street Street in Div-59 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/7294,Electrical,Completed,L-Electrical,59,985700,Supply and errection of 15 nos of 9.5 MTRS GI Lamp Post with double arch bracket and 3 nos of 9.5 mtrs GI Lamp post with trible arch bracket in Esplanade road and NSC Bose road in div 59 in Zone - 5,Own Sources,5,2018-19,2019-20 L/2018-19/7506,Electrical,Completed,L-Electrical,59,197700,Removal and Re erection of 20 mtr highmast at NSC Road Junction of Espalande road in Division 59 Zone 5,Own Sources,5,2018-19,2019-20 NE/2018-19/0786,Roads,Completed,NE-ROYAPURAM,59,643000,"Relaying Of Cement Concrete Road At Antony Street In Dn-59, Un-14, Z-05.",Own Sources,5,2018-19,2019-20 NE/2018-19/0787,Roads,Completed,NE-ROYAPURAM,59,339000,"Relaying Of Cement Concrete Road At Thanjai Murugappa Street (Part) In Dn-59, Un-14, Z-05.",Own Sources,5,2018-19,2019-20 NE/2018-19/0788,Roads,Completed,NE-ROYAPURAM,59,423000,"Relaying Of Cement Concrete Road At Singannan Street In Dn-59, Un-14, Z-05.",Own Sources,5,2018-19,2019-20 NE/2018-19/0789,Roads,Completed,NE-ROYAPURAM,59,140000,"Relaying Of Cement Concrete Road At Narayanappa Lane In Dn-59, Un-14, Z-05.",Own Sources,5,2018-19,2019-20 NE/2018-19/0790,Roads,Completed,NE-ROYAPURAM,59,1532000,"Relaying Of BT Road At NSC Boes Road (From Rattan Bazaar Road To Mint Street) In Dn-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/12969,Buildings,Completed,NE-ROYAPURAM,59,149000,"Demolition of Existing Electrical Substation at NSC Bose Road in DN-59, U-14, Z-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/16453,Parks,Completed,NE-ROYAPURAM,59,560000,"Repairs and Improvements to Center Median at Pallavan Salai in Dn - 59, Unit - 14, Zone - 5.",Own Sources,5,2018-19,2019-20 NE/2018-19/16503,Parks,Completed,NE-ROYAPURAM,59,336000,"Repairs and Improvements to Center Median at Wallajah Road in Dn - 59, Unit - 14, Zone - 5.",Own Sources,5,2018-19,2019-20 NE/2018-19/2057,Buildings,Completed,NE-ROYAPURAM,59,500000,"Providing R.O Purifier to Chennai Primary School at S.M Nagar in Div-59,U-14,Z-5.",MLACDS,5,2018-19,2019-20 NE/2018-19/2059,Buildings,Completed,NE-ROYAPURAM,59,500000,"Providing R.O Purifier to Chennai middle School at Ellispuram, Ellis Road in Div-59,U-14,Z-5.",MLACDS,5,2018-19,2019-20 NE/2018-19/2060,Buildings,Completed,NE-ROYAPURAM,59,500000,"Providing R.O Purifier to Chennai middle School at Mint street, Poonga nagar in Div-59,U-14,Z-5.",MLACDS,5,2018-19,2019-20 NE/2018-19/6104,Buildings,Completed,NE-ROYAPURAM,59,1490000,"MLA FUND 2017-18 CONSTRUCTUION OF PUBILC CONVENIENCE AT SATHYA VANI MUTHU NAGAR IN DIV-59, UNIT-14, ZONE-05",MLACDS,5,2018-19,2019-20 NE/2018-19/6526,Buildings,Completed,NE-ROYAPURAM,59,2036000,"FORMING KERB FOR FOOTPATH AT EAST MADHA CHRUCH STREET IN DIV-50, UNIT-12, ZONE-05",Own Sources,5,2018-19,2019-20 NE/2018-19/9800,Storm Water Drain,Completed,NE-ROYAPURAM,59,43100,"Desilting of Existing Storm Water Drain at Broadway Bus Stand (inside) in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9801,Storm Water Drain,Completed,NE-ROYAPURAM,59,63700,"Desilting of Existing Storm Water Drain at Evening Bazaar Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9802,Storm Water Drain,Completed,NE-ROYAPURAM,59,43700,"Desilting of Exisiting Storm Water Drain at Frazer Bridge Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9805,Storm Water Drain,Completed,NE-ROYAPURAM,59,16100,"Desilting of Existing Storm Water Drain at Narayanappa Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9806,Storm Water Drain,Completed,NE-ROYAPURAM,59,64900,"Desilting of Existing Storm Water Drain at NSC Bose Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9807,Storm Water Drain,Completed,NE-ROYAPURAM,59,17800,"Desilting of Existing Storm Water Drain at NSC Bose Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9808,Storm Water Drain,Completed,NE-ROYAPURAM,59,19200,"Desilting of Existing Storm Water Drain at Nyniappa (N) Street in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9809,Storm Water Drain,Completed,NE-ROYAPURAM,59,30000,"Desilting of Existing Storm Water Drain at Rattan Bazzar Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9810,Storm Water Drain,Completed,NE-ROYAPURAM,59,53900,"Desilting of Existing Storm Water Drain at Kellys drain in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9811,Storm Water Drain,Completed,NE-ROYAPURAM,59,7400,"Desilting of Existing Storm Water Drain at Bangaru (N) Street in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9812,Storm Water Drain,Completed,NE-ROYAPURAM,59,31600,"Desilting of Existing Storm Water Drain at Ellis Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9813,Storm Water Drain,Completed,NE-ROYAPURAM,59,11800,"Desilting of Existing Storm Water Drain at Mukthurinnsa Begam 5th Lane in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9814,Storm Water Drain,Completed,NE-ROYAPURAM,59,8300,"Desilting of Existing Storm Water Drain at Mukthurinnsa Begam 6th Lane in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9815,Storm Water Drain,Completed,NE-ROYAPURAM,59,2480,"Desilting of Existing Storm Water Drain at Owlia (S) 4th Lane in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9816,Storm Water Drain,Completed,NE-ROYAPURAM,59,5300,"Desilting of Existing Storm Water Drain at Owlia (S) 6th Lane in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9817,Storm Water Drain,Completed,NE-ROYAPURAM,59,241000,"Desilting of Existing Storm Water Drain at Pallavan Kudiyiruppu in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9818,Storm Water Drain,Completed,NE-ROYAPURAM,59,71300,"Desilting of Existing Storm Water Drain at Pallavan Salai in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9821,Storm Water Drain,Completed,NE-ROYAPURAM,59,32500,"Desilting of Existing Storm Water Drain at Unnis Ali (S) Street in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9822,Storm Water Drain,Completed,NE-ROYAPURAM,59,53900,"Desilting of Existing Storm Water Drain at Wallajah Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9823,Storm Water Drain,Completed,NE-ROYAPURAM,59,225000,"Desilting of Existing Storm Water Drain at Sathyavani Muthu Nagar in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9824,Storm Water Drain,Completed,NE-ROYAPURAM,59,129000,"Desilting of Existing Storm Water Drain at Sathyavani Muthu Nagar in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9857,Storm Water Drain,Completed,NE-ROYAPURAM,59,7200,"Improvements to Existing Storm Water Drain at Evening Bazaar Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9859,Storm Water Drain,Completed,NE-ROYAPURAM,59,10800,"Improvements to Existing Storm Water Drain at NSC Bose Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9860,Storm Water Drain,Completed,NE-ROYAPURAM,59,21600,"Improvements to Existing Storm Water Drain at Nyniappa (N) Street in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9861,Storm Water Drain,Completed,NE-ROYAPURAM,59,3600,"Improvements to Existing Storm Water Drain at Rattan Bazzar Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9862,Storm Water Drain,Completed,NE-ROYAPURAM,59,7200,"Improvements to Existing Storm Water Drain at Ellis Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9863,Storm Water Drain,Completed,NE-ROYAPURAM,59,7200,"Improvements to Existing Storm Water Drain at Mukthurinnsa Begam 5th Lane in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9864,Storm Water Drain,Completed,NE-ROYAPURAM,59,7200,"Improvements to Existing Storm Water Drain at Thayar (S) Street in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9865,Storm Water Drain,Completed,NE-ROYAPURAM,59,7200,"Improvements to Existing Storm Water Drain at Unnis Ali (S) Street in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9866,Storm Water Drain,Completed,NE-ROYAPURAM,59,10800,"Improvements to Existing Storm Water Drain at Wallajah Road in Division-59, Unit-14, Z0ne-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9867,Storm Water Drain,Completed,NE-ROYAPURAM,59,18000,"Improvements to Existing Storm Water Drain at Sathyavani Muthu Nagar in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9870,Storm Water Drain,Completed,NE-ROYAPURAM,59,133000,"Improvements to Existing Storm Water Drain at Frazer Bridge Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9871,Storm Water Drain,Completed,NE-ROYAPURAM,59,96500,"Improvements to Existing Storm Water Drain at NSC Bose Road in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9872,Storm Water Drain,Completed,NE-ROYAPURAM,59,89300,"Improvements to Existing Storm Water Drain at Kellys drain in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9873,Storm Water Drain,Completed,NE-ROYAPURAM,59,94100,"Improvements to Existing Storm Water Drain at Pallavan Kudiyiruppu in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/9874,Storm Water Drain,Completed,NE-ROYAPURAM,59,223000,"Improvements to Existing Storm Water Drain at Sathyavani Muthu Nagar in Division-59, Unit-14, Zone-5.",Own Sources,5,2018-19,2019-20 B/2018-19/12882,Buildings,Completed,B-Buildings,60,2810000,"Fabrication, construction, and erection of Greater Chennai Corporation pavilion including supplying of new models and interior design, video devices and manpower for managing, housekeeping and security for 45th India Tourist and Industrial Fair 2019 Island ground in Dn-60, Zone ? V",Own Sources,5,2018-19,2019-20 BR/2018-19/13292,Footpath,Completed,BR-Bus Route Roads,60,20500000,"Improvements / Providing and paving with Granite footpath along with railing of SS pipe and Granite pedestal stones to the existing footpath in Kamaraj salai (Dn-60, Zone-5) Reach Napier Bridge to War Memorial",Grants,5,2018-19,2019-20 BR/2018-19/14723,Roads,Completed,BR-Bus Route Roads,60,1740000,"Strengthening and Relaying of existing road in Island ground at TTDC campus (Railway track to kalai arangam) in Dn-60, Zone-5. Against challan No BR/2018-19/0031460",Deposit Works,5,2018-19,2019-20 BR/2018-19/14725,Roads,Completed,BR-Bus Route Roads,60,2389000,"Strengthening and Relaying of existing road in Island ground at TTDC campus (Flag staff road entrance gate to Plaza Round) in Dn-60, Zone-5 Against challan No BR/2018-19/0031460",Deposit Works,5,2018-19,2019-20 BR/2018-19/14726,Roads,Completed,BR-Bus Route Roads,60,957000,"Strengthening and Relaying of existing road in Island ground at TTDC campus (Carriage road + Between railway track and Plaza Round area) in Dn-60, Zone-5. Against challan No BR/2018-19/0031460",Deposit Works,5,2018-19,2019-20 BR/2018-19/2852,Footpath,Completed,BR-Bus Route Roads,60,239000,"Footpath Repair works at NSC Bose road in Dn-60, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/3635,Roads,Completed,BR-Bus Route Roads,60,140000,Painting on footpath kerb at Kamaraj Salai in Zone 5,Own Sources,5,2018-19,2018-19 BR/2018-19/3637,Roads,Completed,BR-Bus Route Roads,60,151000,Painting on footpath kerb at Wallajah Salai in Zone 5,Own Sources,5,2018-19,2018-19 BR/2018-19/5636,Roads,Completed,BR-Bus Route Roads,60,45600,"Road cut restoration (road cut made by BHARTI AIRTEL) at various division in Zone 5 against the challan noBR/2017-18/0012026, BR/2017-18/0012030-dt.28.07.2017 and Deposit code 57/0701/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5950,Roads,Completed,BR-Bus Route Roads,60,957000,"Road cut restoration (road cut made by indian navy) at various division in Zone 5 against the challan no 01/2017-18/0938800,01/2017-18/0938817 dt:19.01.2018 and Deposit code 57/1064/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5953,Roads,Completed,BR-Bus Route Roads,60,698000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 5 against the challan no 07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017 and Deposit code 57/0666/2017-18.",Deposit Works,5,2018-19,2018-19 BR/2018-19/7026,Footpath,Completed,BR-Bus Route Roads,60,980000,"Repair and rectification work of Existing footpath at Rajaji salai (near secretariate) in Dn-60, Zone V",Own Sources,5,2018-19,2019-20 BR/2018-19/7268,Roads,Completed,BR-Bus Route Roads,60,950000,"Repair of existing footpath at Rajaji salai (in front of war memorial) in Dn-60, Zone 5",Own Sources,5,2018-19,2019-20 D/2018-19/14916,Storm Water Drain,Completed,D-Storm Water Drains,60,38700000,"Demolition and Re-Construction of Storm Water Drain of size 1500x1500mm along Rajaji Salai from Reserve Bank subway to junction of War Memorial in Dn.-60,Zone-5,Package - 9.",SMART CITY - SWD,5,2018-19,2019-20 D/2018-19/2916,Storm Water Drain,Completed,D-Storm Water Drains,60,726000,"Rejuvenation and other improvements to the temple tank at Sengazhuneer Pillaiyar Koil ,Sengazhuneer Pillaiyar Koil Street including construction of RWH well under Sustainable Water Secruity Mission in Dn - 60,Zone - 5.",SMART CITY - SWD,5,2018-19,2020-21 D/2018-19/2918,Storm Water Drain,Completed,D-Storm Water Drains,60,1846000,"Rejuvenation and other improvements to the temple tank at Katchaleeshwarar Koil ,Aranmanaikaran street including construction of RWH well under Sustainable Water Secruity Mission in Dn - 60,Zone - 5.",SMART CITY - SWD,5,2018-19,2019-20 D/2018-19/9918,Storm Water Drain,Completed,D-Storm Water Drains,60,52490000,"Construction of Storm Water Drain at Rajaji salai and Pallavan salai in Zone - 5, Package - 16",Grants,5,2018-19,2019-20 L/2018-19/10456,Electrical,Completed,L-Electrical,60,918400,"Supply and Erection 8 nos of 8m GI Octogonal Mini mast at Sathya Nagar, dn-60 and SM Nagar, dn-59, Zone-5",MPLADS,5,2018-19,2019-20 L/2018-19/10916,Electrical,Completed,L-Electrical,60,737400,"PROPOSAL OF 14 NOS.OF 9.5MTR GI LAMPPOST WITH SINGLE ARCH BRACKET AT PRAKASHAM SALAI,DIV-60 ZONE-5..",Own Sources,5,2018-19,2019-20 L/2018-19/15941,Electrical,Completed,L-Electrical,60,176900,"Supply and replacing of 2 nos of damaged Kiosk Pillar Box, 90mtrs 3 1/2X25sq.mm PVC Alu cable and Painting and Numbering of 95 nos of 2/3 mtrs lamp posts at Secretariat Park in dn-60, Zone-5.",Own Sources,5,2018-19,2019-20 L/2018-19/4723,Electrical,Completed,L-Electrical,60,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Centre building at 2 nd Lane Beach Street in Div-60 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 NE/2018-19/10941,Buildings,Completed,NE-ROYAPURAM,60,2000000,"CONSTRUCTION OF ANGANWADI CENTRE AT ANNAI SATHYA NAGAR IN DIVISION-60, UNIT-13, ZONE -5",MLACDS,5,2018-19,2019-20 NE/2018-19/11068,Roads,Completed,NE-ROYAPURAM,60,800000,"LAYING OF CEMENT CONCRETE ROAD AT ANGANWADI CENTRE AT ANNAI SATHYA NAGAR IN DIVISION -60, UNIT-13, ZONE-5,",MLACDS,5,2018-19,2019-20 NE/2018-19/11671,Roads,Completed,NE-ROYAPURAM,60,112000,"Improvement of Relaying CC Road at Ibrahim 1 st Lane in DN.60, U-13, Z-05(Asset Code-040/2581/353/2004-05))",Own Sources,5,2018-19,2020-21 NE/2018-19/11672,Roads,Completed,NE-ROYAPURAM,60,574000,"Improvement of Relaying CC Road at Mannady Street in DN.60, U-13, Z-05 (Asset Code- 044/2591/16540/2013-14 )",Own Sources,5,2018-19,2020-21 NE/2018-19/11677,Roads,Completed,NE-ROYAPURAM,60,165000,"Improvement of Relaying BT Road at Jaffer Sarang Street in DN.60, U-13, Z-05 (Asset Code-044/2578/1395/2007-08)",Own Sources,5,2018-19,2019-20 NE/2018-19/11679,Roads,Completed,NE-ROYAPURAM,60,219000,"Improvement of Relaying BT Road at Vanniyar Street in Dn.60, U-13, Z-05 (Asset Code-044/2657/16690/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11683,Roads,Completed,NE-ROYAPURAM,60,165000,"Improvement of Relaying BT Road At Singanna Street in Dn.60, U-13, Z-05 (Asset Code-044/2649/16685/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11684,Roads,Completed,NE-ROYAPURAM,60,68000,"Improvement of Relaying BT Road at periyanna (M) Street in Dn.60, U-13, Z-05 (Asset Code-044/2629/16596/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11689,Roads,Completed,NE-ROYAPURAM,60,159000,"Improvement of Relaying BT Road at Mclean Street in Dn.60, U-13, Z-05 (Asset Code-044/2621/16594/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11690,Roads,Completed,NE-ROYAPURAM,60,239000,"Improvement of Relaying BT Road at Krishna koil street in Dn.60, U-13, Z-05 (Asset Code-044/2611/23554/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11691,Roads,Completed,NE-ROYAPURAM,60,432000,"Improvement of Relaying BT Road at Armenina Street in Dn.60, U-13, Z-05 (Asset Code-044/2617/16578/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11693,Roads,Completed,NE-ROYAPURAM,60,46000,"Improvement of Relaying BT Road at Post office street in Dn.60, U-13, Z-05 (Asset Code-044/2653/16559/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11697,Roads,Completed,NE-ROYAPURAM,60,79000,"Improvement of Relaying BT Road at Mookar Nallamuthu Street in Dn.60, U-13, Z-05 (Asset Code-044/2587/16542/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11699,Roads,Completed,NE-ROYAPURAM,60,27000,"Improvement of Relaying BT Road at Gopal (C) Street in Dn.60, U-13, Z-05 (Asset Code-044/2584/16531/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/11703,Roads,Completed,NE-ROYAPURAM,60,269000,"Improvement of Relaying BT Road at Moore Street in Dn.60, U-13, Z-05 (Asset Code-044/2599/1405/2006-07)",Own Sources,5,2018-19,2019-20 NE/2018-19/11706,Roads,Completed,NE-ROYAPURAM,60,205000,"Improvement of Relaying BT Road at venkata (M) street in Dn.60, U-13,Z-05 (Asset code-044/2655/16688/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/12827,Roads,Completed,NE-ROYAPURAM,60,779000,"Improvements of Foot Path Kerp at Kamaraj Salai,Flag staff house road, Rajaji salai, North Ford Side Road, NSC Bose Road, and Ibrahim Salaiin Division 60,unit-13,Zone-5.( Asset code - 053/2646/1833/2013-14, 053/2664/1949/2013-14, 153/2627/1061/2014-15,053/2663/1952/2013-14, 053/2632/1950/2013-14,053/2580/1947/2013-14 )",Own Sources,5,2018-19,2020-21 NE/2018-19/14380,Roads,Completed,NE-ROYAPURAM,60,698000,"Painting foot path Kerb wall at Kamaraj salai, Flag staff house road, Rajaji salai ,North fort side road,NSC Bose road and Ibrahim street in (Independence Day celebration) Ward-60, Unit-13, Zone-5 (Asset Code- 053/2664/1949/2013-14, 053/2646/1951/2013-14, 053/2580/1947/2013-14, 053/2580/1947/2013-14, 53/2646/1062/2014-15)",Own Sources,5,2018-19,2019-20 NE/2018-19/14383,Footpath,Completed,NE-ROYAPURAM,60,554000,"IMPROVEMENTS WORKS IN FOOTPATHS & CENTRE MEDIAN AT KAMARAJ SALAI, RAJAJI SALAI, FLAG STAFF HOUSE ROAD, NSC BOSE ROAD AND NORTH FORT SIDE ROAD IN (INDEPENDENCE DAY CELEBRATION) IN DIVISION-60, UNIT-13, ZONE-5 [Asset Code 053/2646/1951/2013-14]",Own Sources,5,2018-19,2019-20 NE/2018-19/14402,Buildings,Completed,B-Buildings,60,203000,"PETTY REPAIR AND MAINTENANCE WORK FOR SMART CLASS ROOM AT URDU SCHOOL AT ANGAPPA (N) STREET IN DIVISION-60, UNIT-13, ZONE-5 (Asset Code-019/2568/103/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/15532,Buildings,Completed,NE-ROYAPURAM,60,1000000,"Providing and Sinking 4 feet dia well ring at Annai Sathya Nagar in Division-60 ,Unit-13 ,Zone-5",MLACDS,5,2018-19,2019-20 NE/2018-19/16421,Parks,Completed,NE-ROYAPURAM,60,168000,"Repair and Maintenance Work in Center Median Park & Civil Work in kamaraj Salai at Dn.60, U-13, Z-05 (043/2627/849/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/16422,Parks,Completed,NE-ROYAPURAM,60,280000,"Repair and Maintenance Work in Center Median Parks & Civil Works in Rajaji Salai at Dn.60, U-13, Z-05 (043/2646/1098/2014-15)",Own Sources,5,2018-19,2019-20 NE/2018-19/16424,Parks,Completed,NE-ROYAPURAM,60,448000,"Repair And Maintenance Work at Center Median Parks & Civil Works in North Ford Side Road at Dn.60, U-13, Z-05",Own Sources,5,2018-19,2019-20 NE/2018-19/16788,Parks,Completed,NE-ROYAPURAM,60,8695000,Annual Maintenance for Secretariat Park at Rajaji Salai in Div-60 Unit-13 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/1984,Buildings,Completed,NE-ROYAPURAM,60,3360000,"CONSTRUCTION OF ADDITIONAL CLASS ROOMS TO URDU SCHOOL (CUGMS) AT ANGAPPAN (N) STREET IN DN.60 UNIT-13, ZONE-5. (ASSET CODE- 019/2568/103/2013-14 )",MLACDS,5,2018-19,2018-19 NE/2018-19/7084,Buildings,Completed,NE-ROYAPURAM,60,2100000,"CONSTRUCTION OF ANGANWADI CENTRE BUILDING AT 4TH LINE BEACH ROAD IN DIVISION-60, UNIT-13, ZONE-5.",MLACDS,5,2018-19,2019-20 NE/2018-19/7130,Storm Water Drain,Completed,NE-ROYAPURAM,60,575000,"PROVIDING RAIN WATER HARVESTING STRUCTURE AT RAJAJI SALAI (NEAR CHENNAI PORT TRUST GATE NO.10, ANNAI SATHYA NAGAR BUS SHELTER, COLEECTOR OFFICE, PARRYS CORNER AND CHENNAI BEACH RAILWAY STATION) IN DIVISION-60, UNIT-13, ZONE-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/7133,Storm Water Drain,Completed,NE-ROYAPURAM,60,647000,"PROVIDING RAIN WATER HARVESTING STRUCTURE AT Thambu (C) street, Angappa (N) street, Kachleesuwarar Pagoda Lane (Jn of Thambu C st.), Muthumari (C) Street, Clive Battery Bus stop, Periyanna maistry street, Sembudoss street in Division-60, Unit-13, Zone-5. (ASSET CODE : 055/2650/4842/2013-14, 055/2580/4826/2013-14)",Own Sources,5,2018-19,2019-20 NE/2018-19/7158,Roads,Completed,NE-ROYAPURAM,60,126000,"PROVIDING BIN FLATFORM AT VARIOUS PLACES IN DN-60 U-13, Z-5.",Own Sources,5,2018-19,2019-20 NE/2018-19/7216,Storm Water Drain,Completed,NE-ROYAPURAM,60,54800,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT KAMARAJ SALAI IN DIVISION-60, UNIT-13, ZONE-5.[055/2627/4837/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7217,Storm Water Drain,Completed,NE-ROYAPURAM,60,35800,"IMPROVEMENTS AND DISILTING TO STORM WATER DRAIN AT RAJAJI SALAI IN DIVISION-60,UNIT-13,ZONE-5. [ASSET CODE:- 053/2646/1951/2013-14 ,055/2646/4834/2013-14,055/2646/4835/2013-14,055/2646/4836/2013-14,055/2646/6853/2014-15 ]",Own Sources,5,2018-19,2018-19 NE/2018-19/7218,Storm Water Drain,Completed,NE-ROYAPURAM,60,21500,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT N.S.C.BOSE ROAD IN DIVISION-60,UNIT-13,ZONE-5. [ASSET CODE; 055/4207/4996/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7219,Storm Water Drain,Completed,NE-ROYAPURAM,60,6600,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT NORTH FORT SIDE ROAD IN DIVISION-60,UNIT-13,ZONE-5. [ASSET CODE: 055/2664/4839/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7220,Storm Water Drain,Completed,NE-ROYAPURAM,60,20700,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT FLAG STAFF HOUSE ROAD IN DIVISION-60,UNIT-13,ZONE-5. [ASSET CODE:055/2663/4838/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7221,Storm Water Drain,Completed,NE-ROYAPURAM,60,31300,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT IBRAHIM SAHIB STREET IN DIVISION-60,UNIT-13,ZONE-5. [ASSET CODE; 055/2580/4826/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7222,Storm Water Drain,Completed,NE-ROYAPURAM,60,65800,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT SEMBUDOSS STREET IN DIVISION-60,UNIT-13,ZONE-5. [055/2650/4842/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7223,Storm Water Drain,Completed,NE-ROYAPURAM,60,64900,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT MOOKER NALLAMUTHU STREET IN DIVISION-60,UNIT-13, ZONE-5. [ASSET CODE- 055/2587/4831/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7224,Storm Water Drain,Completed,NE-ROYAPURAM,60,19500,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT ANGAPPA (N) STREET IN DIVISION-60, UNIT-13, ZONE-5.[ASSET CODE :055/2568/4935/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7226,Storm Water Drain,Completed,NE-ROYAPURAM,60,37400,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT MANNADY STREET IN DIVISION-60, UNIT-13, ZONE-5 [ASSET CODE-044/2568/16511/2013-14 ]",Own Sources,5,2018-19,2018-19 NE/2018-19/7227,Storm Water Drain,Completed,NE-ROYAPURAM,60,20700,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT ARBUTNOT LANE IN DIVISION-60, UNIT-13,ZONE-5. [ASSET CODE- 044/15607/16516/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7228,Storm Water Drain,Completed,NE-ROYAPURAM,60,11500,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT MOORE STREET IN DIVISION-60, UNIT-13, ZONE-5. [ASSET CODE:055/2599/4829/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7229,Storm Water Drain,Completed,NE-ROYAPURAM,60,39800,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT VARADARAJAN (M) STREET IN DIVISION-60, UNIT-13,ZONE-5. [ASSET CODE-055/2615/4827/2013-14 ]",Own Sources,5,2018-19,2018-19 NE/2018-19/7230,Storm Water Drain,Completed,NE-ROYAPURAM,60,19000,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT MOORTHIGAL LANE IN DIVISION-60, UNIT-13,ZONE-5. [ASSET CODE- 044/2608/16544/2013-14 ]",Own Sources,5,2018-19,2018-19 NE/2018-19/7231,Storm Water Drain,Completed,NE-ROYAPURAM,60,4500,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT JONES LANE IN DIVISION-60, UNIT-13, ZONE-5. [ASSET CODE- 055/2640/4843/2013-14 ]",Own Sources,5,2018-19,2018-19 NE/2018-19/7232,Storm Water Drain,Completed,NE-ROYAPURAM,60,5400,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT JAFFER SARANG STREET IN DIVISION-60, UNIT-13, ZONE-5. [ASSET CODE- 055/2578/4828/2013-14]",Own Sources,5,2018-19,2018-19 NE/2018-19/7234,Storm Water Drain,Completed,NE-ROYAPURAM,60,4500,"IMPROVEMENTS AND DESILTING TO STORM WATER DRAIN AT POST OFFICE STREET IN DIVISION-60, UNIT-13, ZONE-5. [ASSET CODE- 055/2653/4832/2013-14 ]",Own Sources,5,2018-19,2018-19 NE/2018-19/9251,Storm Water Drain,Completed,NE-ROYAPURAM,60,306000,"IMPROVEMENTS AND MINOR REPAIRS TO KAMARAJ SAALAI RAJAJI SAALAI NSC BOSE ROAD NORTH FORT SIDE ROAD FLAG STAFF HOUSE ROAD IBRAHIM SAHIB STREET SEMBUDOSS STREET MOOKAR NALLAMUTHU STREET ANGAPPA (N) STREET MANNADY STREET ARBUTNOT LANE MOORE STREET VARADARAJAN STREET MOORTHIGAL LANE JONES LANE POST OFFICE STREET JAFFER SARANG STREET IN DIVISION 60, UNIT-13, ZONE 5,",Own Sources,5,2018-19,2018-19 P/2018-19/12309,Parks,Completed,P-Parks and Playfields,60,710000,"IMPROVEMENTS TO PARK-2 (NORTH SIDE) AT ANNAI SATHYA NAGAR IN DN -60, ZONE - 5",Own Sources,5,2018-19,2019-20 P/2018-19/17442,Parks,Completed,P-Parks and Playfields,60,397000,"IMPROVEMENTS TO PARK-1 (SOUTH SIDE) AT ANNAI SATHYA NAGAR IN DN -60, ZONE - 5",Own Sources,5,2018-19,2019-20 Q/2018-19/16521,Buildings,Completed,Q-Solid Waste Management,60,9990000,REMOVAL OF GARBAGE AND CONSTRUCTION DEBRIS ALONG THE COOVUM RIVER BANKS FROM THE BAY OF BENGAL MOUTH OF THE COOVUM RIVER TO THE MADURAVAYAL BYEPASS WITHIN THE CHENNAI CORP LIMIT - CRRT,Own Sources,5,2018-19,2019-20 BR/2018-19/10753,Road Cut,Completed,BR-Bus Route Roads,61,1440000,Restoration of road cut (open trench made by CMWSSB) in Adhitnar salai in Dn-61 against challan no.BR/2017-18/0030439.,Deposit Works,5,2018-19,2019-20 BR/2018-19/1171,Roads,Completed,BR-Bus Route Roads,61,692000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 5 against the challan no07/2017-18/0377453,07/2017-18/0377472, DT: 21.07.2017 and Deposit code 57/0666/2017-18.",Deposit Works,5,2018-19,2018-19 BR/2018-19/12155,Roads,Completed,BR-Bus Route Roads,61,325000,"Restoration of road cut (open trench made by CMWSSB) in Ethiraj salai (DLF Building- Ethiraj lane)in Dn-61, Zone-5 against challan no.BR/2017-18/0030439.",Deposit Works,5,2018-19,2019-20 BR/2018-19/12877,Roads,Completed,BR-Bus Route Roads,61,980000,"Attending patch work in Egmore PCO Road,Tamizh Salai, East Ramanathan Salai, GP Road, Dams Road,Pantheon road etc in Dn-61 and Dn-62 in Zone - 5",Own Sources,5,2018-19,2018-19 BR/2018-19/2526,Footpath,Completed,BR-Bus Route Roads,61,224000,"Footpath Repair Works at Pantheon Road in Division-61, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/2532,Footpath,Completed,BR-Bus Route Roads,61,1012000,"Footpath Repair work at PCO road in Dn-61, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/2536,Footpath,Completed,BR-Bus Route Roads,61,107000,"Footpath Repair works at Gandhi irwin road footpath in Dn-61, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/2537,Footpath,Completed,BR-Bus Route Roads,61,213000,"Footpath Repair works at S.N chetty street in Dn-52, Zone-5",Grants,5,2018-19,2018-19 BR/2018-19/2539,Footpath,Completed,BR-Bus Route Roads,61,213000,"Footpath Repair works at M.S.Koil Street in Dn-43, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/2551,Footpath,Completed,BR-Bus Route Roads,61,723000,"Footpath Repair works at Ethiraj salai in Dn-61, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/2553,Footpath,Completed,BR-Bus Route Roads,61,1096000,"Footpath Repair works at Casa major road in Dn-61, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/2854,Footpath,Completed,BR-Bus Route Roads,61,308000,"Footpath Repair works at Cementry Road in Dn-52, Zone-5",Grants,5,2018-19,2018-19 BR/2018-19/2855,Footpath,Completed,BR-Bus Route Roads,61,946000,"Footpath Repair works at Halls Road Tamil salai in Dn-61, Zone-5",Grants,5,2018-19,2019-20 BR/2018-19/5646,Roads,Completed,BR-Bus Route Roads,61,82000,"Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan no BR/2017-18/0005976, BR/2017-18/0005977 dt:03.06.2017 and Deposit code 57/0420/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5647,Roads,Completed,BR-Bus Route Roads,61,27500,"Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan no BR/2017-18/0005956, BR/2017-18/0005957 dt:03.06.2017 and Deposit code 57/0438/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/7352,Roads,Completed,BR-Bus Route Roads,61,99000,Restoration of road cut made by CMWSSB at PCO Road in zone-5 challan No.BR/2017-18/0000581,Deposit Works,5,2018-19,2019-20 BR/2018-19/7356,Roads,Completed,BR-Bus Route Roads,61,35000,Roadcut restoration at Rukmani lakshmipathy salai made by CMWSSB in zone-5 against challan no BR/2017-18/0029336,Deposit Works,5,2018-19,2019-20 BR/2018-19/7542,Roads,Completed,BR-Bus Route Roads,61,19500,RESTORATION OF ROAD CUT MADE AT PANTHEON ROAD BY CMWSSB IN ZONE-5 AGAINST CHALLAN NO:BR/2017-18/0000580,Deposit Works,5,2018-19,2019-20 D/2018-19/9917,Storm Water Drain,Completed,D-Storm Water Drains,61,39590000,"Construction of Storm Water Drain at Stanley nagar 1, 2 & 5 street and 2 other roads in Zone - 5, in Package - 15",Grants,5,2018-19,2019-20 D/2018-19/9919,Storm Water Drain,Completed,D-Storm Water Drains,61,37485000,"Construction of Storm Water Drain at Sydenhams road and Gandhi Irwin road in Zone - 5, Package - 17.",Grants,5,2018-19,2019-20 D/2018-19/9920,Storm Water Drain,Completed,D-Storm Water Drains,61,29935000,"Construction of Storm Water Drain at Sathyamoorthy salai in Zone - 5, Package- 18.",Grants,5,2018-19,2019-20 L/2018-19/11079,Electrical,Completed,L-Electrical,61,153700,"Painting and Numberings are 280 nos 9/9.5mtr posts at Gandhi Irvine Bridge, Gandhi Irvine Road, Rukumani Lakshmipathy Salai, L.G.Road and EVR Salai in Division-58 & 61 in Zone-5.",Own Sources,5,2018-19,2019-20 L/2018-19/14671,Electrical,Completed,L-Electrical,61,81400,"Electrical Improvements in Amma Unavagam at Pantheon Road, divsion-61, Zone-5.",Own Sources,5,2018-19,2019-20 L/2018-19/14876,Electrical,Completed,L-Electrical,61,198200,"Erection of 5 nos 9mtr No value street lamp post with single arch bracket and replacement of 222mtrs 3 1/2 X25sq.mm Alu cable at Poniamma Koil Street in Division-61, Zone-5",Own Sources,5,2018-19,2019-20 L/2018-19/14888,Electrical,Completed,L-Electrical,61,155100,"Replacement of 135mtrs 3 1/2X120sq.mm pvc ALU cable from TNEB Pillar to Street Light Kiosk Pillar Box at Gandhi Irvine Bridge in Division-61, Zone-5",Own Sources,5,2018-19,2019-20 L/2018-19/16050,Electrical,Completed,L-Electrical,61,102600,"Supply of 1mtr Long Straight MS single Brackets70 nos for replacing existing bracket at Iyyappa Playground in dn-58 and Sundarao Park, Vengu Pillai Playground, Rangachari Playground in dn-61, Zone-5",Own Sources,5,2018-19,2019-20 L/2018-19/16345,Electrical,Completed,L-Electrical,61,999900,"Supply and erection of 25 nos 6 mtr Street Lamp Post with 2.7mtr Single Arch Bracket and replacement of 821mtrs 3 1/2 X25sq.mm Alu cable at Victoria Crescent Road in Division-61, Zone-5",Own Sources,5,2018-19,2019-20 L/2018-19/1836,Electrical,Completed,L-Electrical,61,82900,"Replacement of 198 mtrs of 2C x 16 Sq.mm PVC Alu cable at Pantheon lane in Division-61, Zone-V.",Own Sources,5,2018-19,2018-19 L/2018-19/1840,Electrical,Completed,L-Electrical,61,178200,"Replacement of 418 mtrs of 2C x 16 Sq.mm PVC Alu cable at Montieth lane in Division-61, Zone-V.",Own Sources,5,2018-19,2018-19 L/2018-19/4733,Electrical,Completed,L-Electrical,61,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Greater Corporation of Chennai Middle School at Junction of Pantheon Road in Div-61, Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/7681,Electrical,Completed,L-Electrical,61,459100,"Supply and erection of 7 nos kiosk pillar box and timer unit at Kennet lane and 6 other location in dn-58 & 61, zone-5.",Own Sources,5,2018-19,2018-19 L/2018-19/8203,Electrical,Completed,L-Electrical,61,184300,"Replacement of 3 1/2X25sq.mm 220mtrs in the place of Fault Road Cross cable and over head wire in various location at Rukumanilakshmipathy Salai dn-61, Zone-5.",Own Sources,5,2018-19,2018-19 NE/2018-19/10119,Storm Water Drain,Completed,NE-ROYAPURAM,61,80000,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT GANDHI IRWIN ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10120,Storm Water Drain,Completed,NE-ROYAPURAM,61,36000,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT CASA MAJOR ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10121,Storm Water Drain,Completed,NE-ROYAPURAM,61,16800,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT GENGU (R) ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10122,Storm Water Drain,Completed,NE-ROYAPURAM,61,93900,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT EGMORE HIGH ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10123,Storm Water Drain,Completed,NE-ROYAPURAM,61,60700,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT HALLS ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10125,Storm Water Drain,Completed,NE-ROYAPURAM,61,34400,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT RUKMANI LAKSHMIPATHY SALAI IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10126,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT DRIVER STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10127,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VELAYUTHAM STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10128,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT AYYASAMY ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10129,Storm Water Drain,Completed,NE-ROYAPURAM,61,22000,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT ADHITHANAR SALAI IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10130,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT GOPAL SAMY NAGAR (GENGU (R) SUBWAY SERVICE ROAD) IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10131,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT BOOPATHY NAGAR (GENGU (R) SUBWAY SERVICE ROAD) IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10132,Storm Water Drain,Completed,NE-ROYAPURAM,61,3600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT BOOPATHY NAGAR (GENGU (R) SUBWAY SERIVCE ROAD) IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10133,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT BOOPATHY NAGAR IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10134,Storm Water Drain,Completed,NE-ROYAPURAM,61,3600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT MOTHIBABA LANE IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10135,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT ARAVAMUTHU GARDEN IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10136,Storm Water Drain,Completed,NE-ROYAPURAM,61,3600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT PONNIAMMAN KOIL STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10137,Storm Water Drain,Completed,NE-ROYAPURAM,61,57100,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT ETHIRAJ SALAI IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10138,Storm Water Drain,Completed,NE-ROYAPURAM,61,14800,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT ETHIRAJ LANE IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10139,Storm Water Drain,Completed,NE-ROYAPURAM,61,38700,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT MONTIETH ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10140,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT MONTIETH LANE IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10141,Storm Water Drain,Completed,NE-ROYAPURAM,61,49200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT POLICE COMMISSIONER OFFICE ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10142,Storm Water Drain,Completed,NE-ROYAPURAM,61,27500,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT SAIT COLONY 1ST STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10143,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT SAIT COLONY 2ND STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10144,Storm Water Drain,Completed,NE-ROYAPURAM,61,51200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT PANTHEON ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10145,Storm Water Drain,Completed,NE-ROYAPURAM,61,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VARADHARAJULU STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10146,Storm Water Drain,Completed,NE-ROYAPURAM,61,20100,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT RANGACHARI STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10147,Storm Water Drain,Completed,NE-ROYAPURAM,61,3600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VEERASAMY STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10148,Storm Water Drain,Completed,NE-ROYAPURAM,61,23700,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT CASA MAJOR ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10149,Storm Water Drain,Completed,NE-ROYAPURAM,61,3600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT GENGU (R) ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10150,Storm Water Drain,Completed,NE-ROYAPURAM,61,177000,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT EGMORE HIGH ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10151,Storm Water Drain,Completed,NE-ROYAPURAM,61,29400,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT HALLS ROAD (TAMIZH SALAI) IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/11417,Roads,Completed,NE-ROYAPURAM,61,1421000,"Improvements to BT Road at Dr.P.V.Cherian Cresent Road in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11418,Roads,Completed,NE-ROYAPURAM,61,980000,"Improvements to BT Road at Sait Colony 1st Street in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11419,Roads,Completed,NE-ROYAPURAM,61,490000,"Improvements to BT Road at Sait Colony 2nd Street in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11420,Roads,Completed,NE-ROYAPURAM,61,483000,"Improvements to BT Road at Driver Street in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11422,Roads,Completed,NE-ROYAPURAM,61,865000,"Improvement to BT Road at PCO Road (NBRR) in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11423,Roads,Completed,NE-ROYAPURAM,61,245000,"Improvements to BT Road at Monteth Road in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/12085,Buildings,Completed,NE-ROYAPURAM,61,750000,"Providing RO Purifier and Borewell to Presidency Girls Higher Secondary school at Gengureddy road in Div-61,U-14,Z-5",MLACDS,5,2018-19,2019-20 NE/2018-19/16531,Parks,Completed,NE-ROYAPURAM,61,168000,"Repair and Improvements to Center Median at Halls Road in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/16532,Parks,Completed,NE-ROYAPURAM,61,224000,"Repair and Improvements to Center Median at P.C.O. Road in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/16533,Parks,Completed,NE-ROYAPURAM,61,84000,"Repair and Improvements to Center Median at Adhithanar Salai in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/16534,Parks,Completed,NE-ROYAPURAM,61,280000,"Repair and Improvements to Center Median at Montieth Road in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/16535,Parks,Completed,NE-ROYAPURAM,61,605000,"Repair and Improvements to Center Median at Gandhi Irwin Road in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/16536,Parks,Completed,NE-ROYAPURAM,61,392000,"Repair and Improvements to Center Median at Pantheon Road in Division-61, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/16789,Parks,Completed,NE-ROYAPURAM,61,337000,Annual Maintenance for Ethiraj lane Park at Ethiraj lane in Div-61 Unit-14 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/18128,Parks,Completed,NE-ROYAPURAM,61,1220000,"IMPROVEMENTS TO BT ROADS AT VEDHAGIRI STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/18131,Parks,Completed,NE-ROYAPURAM,61,798000,"IMPROVEMENTS TO BT ROADS AT Dams Road IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/9826,Storm Water Drain,Completed,NE-ROYAPURAM,61,120500,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT RUKMANI LAKSHMIPATHY SALAI IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9828,Storm Water Drain,Completed,NE-ROYAPURAM,61,14600,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT DRIVER STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9829,Storm Water Drain,Completed,NE-ROYAPURAM,61,9900,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VELAYUTHAM STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9830,Storm Water Drain,Completed,NE-ROYAPURAM,61,14300,"DESILTING AND IMPROVEMENTS TO EXISTING DESILTING OF EXISTING STORM WATER DRAIN AT AYYASAMY ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9833,Storm Water Drain,Completed,NE-ROYAPURAM,61,10400,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT GOPALSAMY NAGAR IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9834,Storm Water Drain,Completed,NE-ROYAPURAM,61,5100,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT BOOPATHY NAGAR (GENGU (R) SERVICE ROAD) IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9835,Storm Water Drain,Completed,NE-ROYAPURAM,61,12900,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT BOOPATHY NAGAR IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9836,Storm Water Drain,Completed,NE-ROYAPURAM,61,11100,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT BOOPATHY NAGAR IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9837,Storm Water Drain,Completed,NE-ROYAPURAM,61,12000,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT MOTHIBABA LANE IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9838,Storm Water Drain,Completed,NE-ROYAPURAM,61,21400,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT ARAVAMUDHAN GARDEN IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9842,Storm Water Drain,Completed,NE-ROYAPURAM,61,65700,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT ETHIRAJ SALAI IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9843,Storm Water Drain,Completed,NE-ROYAPURAM,61,25600,"DESILTING OF EXISTING STORM WATER DRAIN AT ETHIRAJ LANE IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9844,Storm Water Drain,Completed,NE-ROYAPURAM,61,22400,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT MONTIETH ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9845,Storm Water Drain,Completed,NE-ROYAPURAM,61,11400,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT MONTIETH LANE IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9846,Storm Water Drain,Completed,NE-ROYAPURAM,61,41000,"DESILTING OF EXISTING STORM WATER DRAIN AT POLICE COMMISSIONER OFFICE ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9847,Storm Water Drain,Completed,NE-ROYAPURAM,61,16800,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SAIT COLONY 1ST STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9848,Storm Water Drain,Completed,NE-ROYAPURAM,61,16800,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SAIT COLONY 2ND STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9849,Storm Water Drain,Completed,NE-ROYAPURAM,61,80300,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT PANTHEON ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9851,Storm Water Drain,Completed,NE-ROYAPURAM,61,11800,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VARADHARAJALU STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9853,Storm Water Drain,Completed,NE-ROYAPURAM,61,15300,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SAMY (R) STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9854,Storm Water Drain,Completed,NE-ROYAPURAM,61,14300,"DESILTING OF EXISTING STORM WATER DRAIN AT RANGACHARI STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9856,Storm Water Drain,Completed,NE-ROYAPURAM,61,29000,"DESILTING OF EXISTING STORM WATER DRAIN AT WHANNELS ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 B/2018-19/3300,Buildings,Completed,B-Buildings,62,7912997,"PROPOSED CONSTRUCTION OF SPECIAL SHELTER AT STRINGER STREET DIVISION-56,ZONE-5",Own Sources,5,2018-19,2020-21 BR/2018-19/16018,Roads,Completed,BR-Bus Route Roads,62,166000,Restoration of OFC road cut made by ACT at various Bus Route Roads in zone VI Deposit code:57/0206/2018-19,Deposit Works,5,2018-19,2019-20 BR/2018-19/5648,Roads,Completed,BR-Bus Route Roads,62,55000,"Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan no BR/2017-18/0005996, BR/2017-18/0005997 dt:03.06.2017 and Deposit code 57/0430/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/6781,Footpath,Completed,BR-Bus Route Roads,62,1058000,"Footpath Repair Works at Deputy Mayor Kabalamoorthy Salai in Dn-62, Zone-V",Grants,5,2018-19,2019-20 BR/2018-19/7346,Roads,Completed,BR-Bus Route Roads,62,129000,Roadcut restoration made by CMWSSB at Arunachalam street in zone-5 against Challan No BR/2017-18/0023202,Deposit Works,5,2018-19,2019-20 L/2018-19/4738,Electrical,Completed,L-Electrical,62,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Greater Corporation of Chennai Higher secondary School at west coovam road in Div-62 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4740,Electrical,Completed,L-Electrical,62,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing in office building at Adikesavalu Street in Div-62 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4741,Electrical,Completed,L-Electrical,62,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Greater Corporation of Chennai dispensary at Arunachala naicken street in Div-62 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4743,Electrical,Completed,L-Electrical,62,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Greater Corporation of Chennai Community hall at singanna chetty street in Div-62 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 L/2018-19/4746,Electrical,Completed,L-Electrical,62,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing in building at Ritchie Street in Div-62 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 NE/2018-19/0870,Buildings,Completed,NE-ROYAPURAM,62,400000,"Repairs and Improvements to Dispensary at padavattamman koil street Div 62, Unit-14,Zone-5",Own Sources,5,2018-19,2018-19 NE/2018-19/0875,Buildings,Completed,NE-ROYAPURAM,62,240000,"Repairs and maintenance to Dispensary at Singanna ( C ) street in Div 62, Unit-14,Zone-5",Own Sources,5,2018-19,2018-19 NE/2018-19/10204,Storm Water Drain,Completed,NE-ROYAPURAM,62,15900,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SAMY (P) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10205,Storm Water Drain,Completed,NE-ROYAPURAM,62,36100,"DESILTING OF EXISTING STORM WATER DRAIN AT LAFOND STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10206,Storm Water Drain,Completed,NE-ROYAPURAM,62,13200,"DESILTING OF EXISTING STORM WATER DRAIN AT KOVOOR VAITHIYANATHAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10207,Storm Water Drain,Completed,NE-ROYAPURAM,62,7500,"DESILTING OF EXISTING STORM WATER DRAIN AT NEW BALAKRISHNAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10208,Storm Water Drain,Completed,NE-ROYAPURAM,62,17500,"DESILTING OF EXISTING STORM WATER DRAIN AT VENKATESAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10209,Storm Water Drain,Completed,NE-ROYAPURAM,62,32400,"DESILTING OF EXISTING STORM WATER DRAIN AT WALLERS ROAD IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10210,Storm Water Drain,Completed,NE-ROYAPURAM,62,23900,"DESILTING OF EXISTING STORM WATER DRAIN AT SAMY (N) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10211,Storm Water Drain,Completed,NE-ROYAPURAM,62,7500,"DESILTING OF TO EXISTING STORM WATER DRAIN AT ULAGAPPA (M) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10212,Storm Water Drain,Completed,NE-ROYAPURAM,62,2100,"DESILTING OF EXISTING STORM WATER DRAIN AT GURUVAPPA (C) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10213,Storm Water Drain,Completed,NE-ROYAPURAM,62,36000,"DESILTING OF TO EXISTING STORM WATER DRAIN AT DEPUTY MAYOR KABALAMOORTHY SALAI IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10214,Storm Water Drain,Completed,NE-ROYAPURAM,62,6300,"DESILTING OF TO EXISTING STORM WATER DRAIN AT BALAKRISHNAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10215,Storm Water Drain,Completed,NE-ROYAPURAM,62,8800,"DESILTING OF EXISTING STORM WATER DRAIN AT IYYA (M) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10216,Storm Water Drain,Completed,NE-ROYAPURAM,62,15900,"DESILTING OF EXISTING STORM WATER DRAIN AT SOUTH PADAVATTAMMAN KOIL STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10217,Storm Water Drain,Completed,NE-ROYAPURAM,62,7400,"DESILTING OF EXISTING STORM WATER DRAIN AT ST. LAZAR CHURCH STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10218,Storm Water Drain,Completed,NE-ROYAPURAM,62,6300,"DESILTING OF EXISTING STORM WATER DRAIN AT PUMPING STATION ROAD IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10219,Storm Water Drain,Completed,NE-ROYAPURAM,62,94600,"DESILTING OF TO EXISTING STORM WATER DRAIN AT SINGANNA (C) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10220,Storm Water Drain,Completed,NE-ROYAPURAM,62,20700,"DESILTING OF TO EXISTING STORM WATER DRAIN AT BAZAAR STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10221,Storm Water Drain,Completed,NE-ROYAPURAM,62,3500,"DESILTING OF TO EXISTING STORM WATER DRAIN AT REX STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10222,Storm Water Drain,Completed,NE-ROYAPURAM,62,65700,"DESILTING OF TO EXISTING STORM WATER DRAIN AT ARUNACHALAM ROAD IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10337,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SAMY (P) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10338,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT LAFOND STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10339,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT KOVOOR VAITHIYANATHAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10340,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT NEW BALAKRISHNAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10341,Storm Water Drain,Completed,NE-ROYAPURAM,62,10800,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VENKATESAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10342,Storm Water Drain,Completed,NE-ROYAPURAM,62,10800,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT WALLERS ROAD IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10343,Storm Water Drain,Completed,NE-ROYAPURAM,62,10800,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SAMY (N) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10344,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT ULAGAPPA (M) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10345,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT GURUVAPPA STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10346,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT DEPUTY MAYOR KABALAMOORTHY SALAI IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10347,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT BALAKRISHNAN STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10348,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT IYYA (M) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10349,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SOUTH PADAVATAMMAN KOIL STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10350,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT ST. LAZAR CHURCH STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10351,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT PUMPING STATION ROAD IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10352,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT SINGANNA (C) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10353,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT BAZAAR STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10354,Storm Water Drain,Completed,NE-ROYAPURAM,62,7200,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT REX STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10355,Storm Water Drain,Completed,NE-ROYAPURAM,62,32900,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT ARUNACHALAM ROAD IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/16790,Parks,Completed,NE-ROYAPURAM,62,1283000,Annual Maintenance for May Day Park at Mayor Kabalamoorthy Salai in Div-62 Unit-14 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/1764,Buildings,Completed,NE-ROYAPURAM,62,880000,"Proposed construction of Childrens Toilet at Ritchi street in Division -62, Unit-14, Zone-V Asset Code:033/8559/853/2014-15",Own Sources,5,2018-19,2018-19 NE/2018-19/18129,Parks,Completed,NE-ROYAPURAM,62,1568000,"IMPROVEMENTS TO BT ROADS AT SAMY (N) STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/18130,Parks,Completed,NE-ROYAPURAM,62,588000,"IMPROVEMENTS TO BT ROADS AT Iyya (M) Street (From Guruvappa Street to Iyya (M) Lane IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/8673,Buildings,Completed,NE-ROYAPURAM,62,1500000,"Providing Drinking water RO Plant Station and Borewell at Ulagappa street, chintadripet in Div-62,U-14,Z-5",MLACDS,5,2018-19,2020-21 Q/2018-19/6683,Buildings,Completed,Q-Solid Waste Management,62,9990000,REMOVAL OF GARBAGE AND CONSTRUCTION DEBRIS ALONG THE COOVUM RIVER BANKS FROM THE BAY OF BENGAL MOUTH OF THE COOVUM RIVER TO THE MADURAVAYAL BYEPASS WITHIN THE CHENNAI CORPORATION LIMIT - CRRT,Own Sources,5,2018-19,2018-19 BR/2018-19/13080,Roads,Completed,BR-Bus Route Roads,63,73500,Roadcut restoration at Thiru-vi-ka Salai(G.P road) against challlan no:BR/2018-19/0016878.,Deposit Works,5,2018-19,2019-20 BR/2018-19/16017,Roads,Completed,BR-Bus Route Roads,63,376800,Restoration of OFC road cut made by Reliance Jio Infocom Ltd at various Bus Route Roads in zone VI Deposit code:57/0055/2018-19,Deposit Works,5,2018-19,2019-20 BR/2018-19/5645,Roads,Completed,BR-Bus Route Roads,63,92000,"Road cut restoration (road cut made by bharti airtel) at various division in Zone 5 against the challan no BR/2017-18/0005958, BR/2017-18/0005959 dt:03.06.2017 and Deposit code 57/0437/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5943,Roads,Completed,BR-Bus Route Roads,63,191000,Road cut restoration (road cut made by BHARTI AIRTEL) at various division in Zone 5 against the challan no BR/2017-18/0005994 BR/2017-18/0005995 dt:03.06.2017 and Deposit code 57/0666/2017-18.,Deposit Works,5,2018-19,2019-20 BR/2018-19/5946,Roads,Completed,BR-Bus Route Roads,63,136000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 5 against the challan no 08/2017-18/0410704,08/2017-18/0410711,DT: 01.08.2017 and Deposit code 57/0683/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/5951,Roads,Completed,BR-Bus Route Roads,63,964000,"Road cut restoration (road cut made by indian navy) at various division in Zone 5 against the challan no 01/2017-18/0938800,01/2017-18/0938817 dt:19.01.2018 and Deposit code 57/1064/2017-18.",Deposit Works,5,2018-19,2019-20 BR/2018-19/6560,Footpath,Completed,BR-Bus Route Roads,63,8417000,"Forming Footpath at Thir Vi Ka High Road (G.P.Road) in Dn-63, Zone-V",Grants,5,2018-19,2020-21 BR/2018-19/7354,Roads,Completed,BR-Bus Route Roads,63,91500,Restoration of road cut made by CMWSSB at Bharathi salai in zone-5 against challan no BR/2018-19/0005236,Deposit Works,5,2018-19,2019-20 D/2018-19/9921,Storm Water Drain,Completed,D-Storm Water Drains,63,33530000,"Construction of Storm Water Drain in GP road in Zone - 5, Package - 19.",Grants,5,2018-19,2019-20 L/2018-19/10640,Electrical,Completed,L-Electrical,63,265700,"ELECTRIFICATION WORK AT D DEPO,ZONE-5",Own Sources,5,2018-19,2019-20 L/2018-19/10882,Electrical,Completed,L-Electrical,63,1837600,PROPOSAL OF 30NOS.OF 9.5MTR GI LAMPPOST WITH DOBLE ARCH BRACKET AT LIC CENTER MEDIAN DIV63 ZONE-5,Own Sources,5,2018-19,2020-21 L/2018-19/15523,Electrical,Completed,L-Electrical,63,4135000,"PROPOSAL OF 50NOS.OF 9.5MTR GI LAMPPOST WITH SINGLE ARCH BRACKET AND 50NOS.OF 150-165W LED FITTINGS AND 1715MTRS OF 31/2*25 SQ.MM PVC ALU CABLE AT LIC CENTER MEDIAN SIDE AND ADDISION SIDE,DIV-63 ZONE-5",Own Sources,5,2018-19,2019-20 L/2018-19/3680,Electrical,Completed,L-Electrical,63,87900,"ELECTRIFICATION WORK FOR D DEPO PUDUPET .DIV63,ZONE-5.",Own Sources,5,2018-19,2018-19 L/2018-19/4744,Electrical,Completed,L-Electrical,63,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing in Community hall at Veerabadran street Street in Div-63 in Zone - 5",SMART CITY - ELECTRICAL,5,2018-19,2019-20 NE/2018-19/10185,Storm Water Drain,Completed,NE-ROYAPURAM,63,18000,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT NARAYANA (N) STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10186,Storm Water Drain,Completed,NE-ROYAPURAM,63,34400,"REPAIR AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT LG ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10187,Storm Water Drain,Completed,NE-ROYAPURAM,63,51600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT ANNA SALAI(DARGHA) IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10188,Storm Water Drain,Completed,NE-ROYAPURAM,63,19000,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT KANCHEEPURAM PACHAYAPPAN STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10189,Storm Water Drain,Completed,NE-ROYAPURAM,63,44400,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT KOYYA POTHTHU IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10190,Storm Water Drain,Completed,NE-ROYAPURAM,63,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VEERABATHIRAN STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10191,Storm Water Drain,Completed,NE-ROYAPURAM,63,24500,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT ATHITHANAR SALAI IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10192,Storm Water Drain,Completed,NE-ROYAPURAM,63,29300,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT BHARATHI SALAI IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10193,Storm Water Drain,Completed,NE-ROYAPURAM,63,3600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT PYCRAFT 1ST STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10194,Storm Water Drain,Completed,NE-ROYAPURAM,63,43300,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VN DOSS ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10195,Storm Water Drain,Completed,NE-ROYAPURAM,63,36100,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VEERANPURAM IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10196,Storm Water Drain,Completed,NE-ROYAPURAM,63,80100,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT THIRU.VI.SALAI (GP ROAD) IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10197,Storm Water Drain,Completed,NE-ROYAPURAM,63,41500,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT CHELLA PILLAYAR KOVIL STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10198,Storm Water Drain,Completed,NE-ROYAPURAM,63,3600,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VENKADACHALA (N) STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10199,Storm Water Drain,Completed,NE-ROYAPURAM,63,7200,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT VELAYUTHA (A) STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/10200,Storm Water Drain,Completed,NE-ROYAPURAM,63,10800,"REPAIR AND IMPROVEMENTS TO EXISITING STORM WATER DRAIN AT LGN ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/11410,Roads,Completed,NE-ROYAPURAM,63,920000,"Improvements to BT Road at Mir Ashak Hussain Street in Division-63, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11411,Roads,Completed,NE-ROYAPURAM,63,515000,"Improvement to BT Road at Venkatachala (Achari) Street in Division-63, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11412,Roads,Completed,NE-ROYAPURAM,63,718000,"Improvements to BT Road at Venkatachala(N) Street in Division-63, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11413,Roads,Completed,NE-ROYAPURAM,63,905000,"Improvements to BT Road at Oil Monger Street and Lane in Division-63, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11414,Roads,Completed,NE-ROYAPURAM,63,980000,"Improvements to BT Road at Dams Road in Division-63, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11415,Roads,Completed,NE-ROYAPURAM,63,924000,"Improvements to BT Road at Narasingapuram Street in Division-63, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/11416,Roads,Completed,NE-ROYAPURAM,63,385000,"Improvements to BT Road at Chanrabanu Street in Division-63, Unit-14, Zone-V",Own Sources,5,2018-19,2019-20 NE/2018-19/12682,ROB,Completed,NE-ROYAPURAM,63,224000,"PROVIDING OF STEEL STRUCTURES TO AVOID HEAVY DUTY TRANSPORTS VEHICLES MOVEMENTS RESTRICTION AT SOUTH COOVAM RIVER ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2019-20 NE/2018-19/16791,Parks,Completed,NE-ROYAPURAM,63,549000,Annual Maintenance for Raheja Complex OSR Land Park at GP Road in Div-63 Unit-14 Zone-5,Own Sources,5,2018-19,2020-21 NE/2018-19/2928,Buildings,Completed,NE-ROYAPURAM,63,159000,"Repairs and Improvements to Amma unavagam At Veerabadhran Street Div 63, Unit-14,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/2929,Buildings,Completed,NE-ROYAPURAM,63,154000,"Repairs and Improvements to Amma unavagam at Bharathi salai Div 63, Unit-14,Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/3138,Buildings,Completed,NE-ROYAPURAM,63,754000,"Repaire and Maintanance to Hospital at Kanchi Pachaiyappan Street in Div-63, unit-14, zone-5 014/8734/19/1959-60",Own Sources,5,2018-19,2018-19 NE/2018-19/5505,Buildings,Completed,NE-ROYAPURAM,63,979000,"Construction of New Resource recovery center at South Koovam River Road in Div-63, Unit-14, Zone-5",Own Sources,5,2018-19,2019-20 NE/2018-19/9606,Storm Water Drain,Completed,NE-ROYAPURAM,63,57800,"DESILTING TO EXISITING STORM WATER DRAIN AT NARAYANA (N) STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9607,Storm Water Drain,Completed,NE-ROYAPURAM,63,6300,"DESILTING TO EXISITING STORM WATER DRAIN AT LONGS GARDEN ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9608,Storm Water Drain,Completed,NE-ROYAPURAM,63,38500,"DESILTING TO EXISITING STORM WATER DRAIN AT ANNA SALAI (DARGHA) IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9609,Storm Water Drain,Completed,NE-ROYAPURAM,63,16800,"DESILTING TO EXISITING STORM WATER DRAIN AT KANJIPURAM PACHAYAPPAN STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9610,Storm Water Drain,Completed,NE-ROYAPURAM,63,2100,"DESILTING TO EXISITING STORM WATER DRAIN AT GOYYATHOPE IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9611,Storm Water Drain,Completed,NE-ROYAPURAM,63,20000,"DESILTING TO EXISITING STORM WATER DRAIN AT VEERABATHIRAN STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9612,Storm Water Drain,Completed,NE-ROYAPURAM,63,19200,"DESILTING TO EXISITING STORM WATER DRAIN AT ATHITHANAR SALAI IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9613,Storm Water Drain,Completed,NE-ROYAPURAM,63,35000,"DESILTING TO EXISTING STORM WATER DRAIN AT BHARATHI SALAI IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9614,Storm Water Drain,Completed,NE-ROYAPURAM,63,11800,"DESILTING TO EXISTING STORM WATER DRAIN AT PYCRAFT 1ST STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9615,Storm Water Drain,Completed,NE-ROYAPURAM,63,43100,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT VN DOSS ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9616,Storm Water Drain,Completed,NE-ROYAPURAM,63,5600,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT NAINIYAPPA STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9617,Storm Water Drain,Completed,NE-ROYAPURAM,63,6800,"DESILTING TO EXISITING STORM WATER DRAIN AT VEERANPURAM STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9619,Storm Water Drain,Completed,NE-ROYAPURAM,63,5400,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT CHANDRABANU STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9620,Storm Water Drain,Completed,NE-ROYAPURAM,63,93200,"DESILTING TO EXISTING STORM WATER DRAIN AT THIRU.VI.KA.SALAI IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9621,Storm Water Drain,Completed,NE-ROYAPURAM,63,41700,"DESILTING TO EXISTING STORM WATER DRAIN AT CHELLA PILLAYAR KOVIL STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9622,Storm Water Drain,Completed,NE-ROYAPURAM,63,7000,"DESILTING AND IMPROVEMENTS TO EXISTING STORM WATER DRAIN AT BEGAM SAIB STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9623,Storm Water Drain,Completed,NE-ROYAPURAM,63,11800,"DESILTING TO EXISTING STORM WATER DRAIN AT VENKADACHALA (N) STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9624,Storm Water Drain,Completed,NE-ROYAPURAM,63,14300,"DESILTING TO EXISTING STORM WATER DRAIN AT VELAYUTHA (A) STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 NE/2018-19/9626,Storm Water Drain,Completed,NE-ROYAPURAM,63,22600,"DESILTING TO EXISTING STORM WATER DRAIN AT LORD GOVINDASS NAGAR ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2018-19,2018-19 BR/2018-19/5964,Roads,Completed,BR-Bus Route Roads,64,820000,Restoration of Road cut made by reliance jio at various roads in Zone 6 ( Challan No : BR/2017-18/0012037 Deposit code 57/0683/2017-18.),Deposit Works,6,2018-19,2018-19 D/2018-19/6484,Storm Water Drain,Completed,D-Storm Water Drains,64,2470000,"Construction of storm water drain of size 900x9000mm along Sivasakthi nagar main road Extension from sivasakthi nagar 3 rd street to inner ring road chainage 0m to 130m in Dn - 64 ,Zone-VI.",Own Sources,6,2018-19,2019-20 D/2018-19/6485,Storm Water Drain,Completed,D-Storm Water Drains,64,2470000,"Construction of storm water drain of size 900x9000mm along Sivasakthi nagar Extension main road from sivasakthi nagar 3 rd street to inner ring road chainage 130m to 260m in Dn - 64 ,Zone-VI.",Own Sources,6,2018-19,2019-20 D/2018-19/6486,Storm Water Drain,Completed,D-Storm Water Drains,64,1510000,"Construction of storm water drain of size 900x9000mm along Sivasakthi nagar Extension main road from sivasakthi nagar 3 rd street to inner ring road chainage 260m to 340m in Dn - 64 ,Zone-VI.",Own Sources,6,2018-19,2019-20 L/2018-19/4916,Electrical,Completed,L-Electrical,64,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS,Thiruveethi Amman koil street in Div64, Zone- 6",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4918,Electrical,Completed,L-Electrical,64,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHSS Padasalai street in Div64, Zone- 6.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4920,Electrical,Completed,L-Electrical,64,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS School road in Div64, Zone- 6.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4922,Electrical,Completed,L-Electrical,64,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS GKM colony 27th street in Div64, Zone- 6.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/11137,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,489000,"Improvements to BT Road at Ashoka Avenue 2nd main road in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11138,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,471000,"Improvements to BT Road at Ashoka Avenue 4th Cross Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11139,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,502000,"Improvements to BT Road atAshoka Avenue 5th Cross Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11143,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,247000,"Improvements to BT Road at Vasan St ,Vasatham Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11144,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,292000,"Improvements to BT Road at Vasatham Nagar 1st street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11145,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,310000,"Improvements to BT Road at Vasatham Nagar 2nd Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11146,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,301000,"Improvements to BT Road at Vasatham Nagar 3rd Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11147,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1188000,"Improvements to BT Road at Kambar nagar 5th street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11148,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,570000,"Improvements to BT Road at Appasamy Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11149,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,757000,"Improvements to BT Road at Poompuhar Nagar 29th Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11150,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,552000,"Improvements to BT Road at Anjugam Nagar 15th Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11169,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,836000,"Improvements to BT Road at Velmurugan Nagar 1st Avenue and 2nd main road in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11170,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,547000,"Improvements to BT Road at Poompuhar Nagar 11 th cross street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11177,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,276000,"Improvements to BT Road at Ramdoss Nagar in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11179,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,467000,"Improvements to BT Road at TNHB-MIG road in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11180,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,320000,"Improvements to BT Road at Samudhuriya colony 5th street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11181,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,607000,"Improvements to BT Barath Avenue 1st,2nd & 3rd Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11182,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,186000,"Improvements to BT Road at Pongavanam Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11184,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,257000,"Improvements to BT Road at Venkat nagar in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11185,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,398000,"Improvements to BT Road at Haridoss nagar main road in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11188,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,809000,"Improvements to BT Road at K.S.Nagar (Part) in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11189,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,374000,"Improvements to BT Road at Selliamman Kovil Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11191,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,234000,"Improvements to BT Road at Shanthi nagar 1st cross st in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11192,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,396000,"Improvements to BT Road at Shanthi Nagar main road in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11193,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,402000,"Improvements to BT Road at Balakumaran nagar B part 2nd main road in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11194,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,298000,"Improvements to BT Road at Balaji naagr 1st cross street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11710,Culvert,Completed,NF-THIRU-VI-KA NAGAR,64,3300000,"PROVIDING DRY REVETMENT MASANRY WORK AT ALL SIDE REVETMENT AT HARIDOSS POND IN DN-64,UNIT-15,ZONE-6",MLACDS,6,2018-19,2019-20 NF/2018-19/15892,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,250000,"Providing Borewell and Water supply arragements at Haridass street Lotus Park in Div-64, Unit-15, Zone -6.",MLACDS,6,2018-19,2019-20 NF/2018-19/15956,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,657000,"MAINTENANCE FOR V.V.NAGAR PARK IN DN-64 , Z-6 (PER YEAR)",Own Sources,6,2018-19,2020-21 NF/2018-19/15960,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,406000,"MAINTENANCE FOR POOMBUGHAR NAGAR PARK IN DN-64 , Z-6 (PER YEAR)",Own Sources,6,2018-19,2020-21 NF/2018-19/15967,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,318000,"MAINTENANCE FOR ANJUGAM NAGAR PARK IN DN-64 , Z-6 (PER YEAR)",Own Sources,6,2018-19,2020-21 NF/2018-19/6909,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,233000,"Improvements to exisitng UPHC building at Anjugam Nagar 4th Cross Street in Dn-64,Unit-15,Zone-06.",Own Sources,6,2018-19,2018-19 NF/2018-19/9294,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,521000,"Minor Repairs to the exisitng SWD at Ashoka Avenue 1st main road jn of Jaganathan Salai , Nermai Nagar,Thirupathi Nagar ,United Colony And Various streets in Dn-64,Unit-15,Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/9295,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,275000,"Minor Repairs to the exisitng SWD at Poompuhar Nagar 10th cross street, Poompuhar Nagar,Venkateswara Nagar,Thenpalani Nagar,Sembium Redhills road,Velavan Nagar ,Velmurugan Nagar ,Balaji Nagar And Various streets in Dn-64,Unit-15,Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/9365,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,878000,"Desilting Work to the exisitng SWD at Poompuhar Nagar 10th cross street, Poompuhar Nagar,Venkateswara Nagar,Thenpalani Nagar,Sembium Redhills road,Velavan Nagar ,Velmurugan Nagar ,Balaji Nagar And Various streets in Dn-64,Unit-15,Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/9367,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,624000,"Desilting Work to the exisitng SWD at Ashoka Avenue 1st main road jn of Jaganathan Salai , Nermai Nagar,Thirupathi Nagar ,United Colony And Various streets in Dn-64,Unit-15,Zone-06.",Own Sources,6,2018-19,2019-20 B/2018-19/7573,Buildings,Completed,B-Buildings,65,13391093,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTRE AT 36TH STREET, JAMBULINGAM MAIN ROAD, G.K.M. COLONY IN DIV-65,ZONE-06.",Own Sources,6,2018-19,2020-21 BR/2018-19/10768,Road Cut,Completed,BR-Bus Route Roads,65,2160000,"Restoration of road cut made by CMWSSB at Thillai Nagar 1st Main Road in Dn - 65, Zone -6",Deposit Works,6,2018-19,2019-20 BR/2018-19/16015,Roads,Completed,BR-Bus Route Roads,65,904000,Restoration of OFC road cut made by M/s Bharathi Airtel at various Bus Route roads in zone VI Deposit code 57/0233/2018-19,Deposit Works,6,2018-19,2019-20 BR/2018-19/6002,Roads,Completed,BR-Bus Route Roads,65,1900000,"Restoration of Road cut made by CMWSSB at Kolathur main road from the jn of Jambulingam main road to the jn of Burial Ground in Div-65, Zone -06",Deposit Works,6,2018-19,2019-20 BR/2018-19/6534,Roads,Completed,BR-Bus Route Roads,65,102000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DN.65, ZONE-06. Deposite code :57/0694/2017-18",Deposit Works,6,2018-19,2018-19 BR/2018-19/6536,Roads,Completed,BR-Bus Route Roads,65,160000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DN.65, ZONE-06. (57/0439/2017-18) PACKAGE-11.",Deposit Works,6,2018-19,2018-19 BR/2018-19/9562,Road Cut,Completed,BR-Bus Route Roads,65,2061000,"Restoration of Roadcut made by CMWSSB at Jambulingam main Road (from the jn of GKM Colony 28th Street to GKM Colony 21st Street) in Dn-65, Zone - 6",Deposit Works,6,2018-19,2019-20 BR/2018-19/9564,Road Cut,Completed,BR-Bus Route Roads,65,1800000,"Restoration of Roadcut made by CMWSSB at Jambulingam main Road (from the jn of Kolathur main Road to GKM Colony 28th Street) in Dn-65, Zone - 6",Deposit Works,6,2018-19,2019-20 D/2018-19/9922,Storm Water Drain,Completed,D-Storm Water Drains,65,33246000,"Construction of Storm Water Drain at Pumpuhar Nagar 9 th street and 4 other roads in Zone - 6, Package - 20.",Grants,6,2018-19,2020-21 L/2018-19/0258,Electrical,Completed,L-Electrical,65,139300,"PROVISION OF 7 NOS OF 7MTR STREET LAMP POST WITH STRAIGHT BRACKET (NO-VALUE) WITH 7 NOS OF 70W SVL FITTINGS C.SET (N.V) AT MA-PO-SI- EXTN IN JAYANTHI NAGAR IN DIV-65,ZONE-Vl",Own Sources,6,2018-19,2018-19 L/2018-19/4925,Electrical,Completed,L-Electrical,65,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health post srinivasa nagar in Div65, Zone- 6.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4926,Electrical,Completed,L-Electrical,65,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, Padasalai in DN 65, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4932,Electrical,Completed,L-Electrical,65,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at AE office at Anjugam nagar 4th main road in 65, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4935,Electrical,Completed,L-Electrical,65,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi srinivasan nagar 3rd main road in Dn65 Zone-6",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4937,Electrical,Completed,L-Electrical,65,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi,GKM Colony 29th street in 65, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4979,Electrical,Completed,L-Electrical,65,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS Srinivasa nagar 3rd main road in Dn65, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/6474,Electrical,Completed,L-Electrical,65,2345900,"Electrification work for CHSS at Ammaiyammal street,CGHS at mannarasami street,CHS at padasalai street,CMS at Narasimhnagar ,Decastor road and Tana street in divisions 65,73 and 78 of Zone6.",Own Sources,6,2018-19,2019-20 NF/2018-19/0193,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,2000000,"Construction of Additional class rooms at CPS,Srinivasa nagar 3rd main road in Div-65,Unit-15,Zone-6",MLACDS,6,2018-19,2018-19 NF/2018-19/11056,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,990000,"Construction of additional class rooms at CPS,Srinivasa nagar 3rd main road in Div-65,Unit-15,Zone-6",MLACDS,6,2018-19,2019-20 NF/2018-19/1173,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,719000,"Improvements and Relaying BT Road at JAYANTHI NAGAR 2ND MAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1174,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1208000,"Improvements and Relaying BT Road at JAYANTHI NAGAR 1ST MAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1175,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,162000,"Improvements and Relaying BT Road at RAJAJI NAGAR 7TH STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1176,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1080000,"Improvements and Relaying BT Road at RAJAJI NAGAR 2ND STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1177,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,173000,"Improvements and Relaying BT Road at THIRUMALAI NAGAR in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1178,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1182000,"Improvements and Relaying BT Road RAJAJIVE GANDHI NAGAR in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1179,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1647000,"Improvements and Relaying BT Road NETHAJI NAGAR MAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1180,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,147000,"Improvements and Relaying BT Road NETHAJI NAGAR 3RD STRET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1181,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,820000,"Improvements and Relaying BT Road SENTHIL NAGAR 4TH CROSS STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1182,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,600000,"Improvements and Relaying BT Road SENTHIL NAGAR 3RD CROSS STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1183,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,520000,"Improvements and Relaying BT Road SENTHIL NAGAR 8TH CROSS STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2020-21 NF/2018-19/1184,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,569000,"Improvements and Relaying BT Road SENTHIL NAGAR 5TH CROSS STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2020-21 NF/2018-19/1185,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,909000,"Improvements and Relaying BT Road P.U SHANMUGAM NAGAR in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2020-21 NF/2018-19/1186,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,806000,"Improvements and Relaying BT Road R.K SYNDICATE NAGAR in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2020-21 NF/2018-19/1187,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,2549000,"Improvements and Relaying BT Road VIVEKANANDA MAIN ROAD MAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1190,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,2887000,"Improvements and Relaying BT Road THILLI NAGAR MAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2020-21 NF/2018-19/1191,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,929000,"Improvements and Relaying BT Road SRI GANESH NAGAR MAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1192,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,450000,"Improvements and Relaying BT Road RAJAJI NAGAR 8TH STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1193,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1113000,"Improvements and Relaying BT Road VENUS NAGAR MAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1194,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,549000,"Improvements and Relaying BT Road SRI GANEH NAGAR DHANABAKIYAM STREETin Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1195,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,306000,"Improvements and Relaying BT Road SRI GANESH NAGAR PERIYAR STREET Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1196,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,305000,"Improvements and Relaying BT Road SRI GANESH NAGAR NSK STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1198,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,2138000,"Improvements and Relaying BT ROAD IN JAMBULINGAMMAIN ROAD in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1203,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,324000,"Improvements and Relaying CC Road at GKM COLONY 25TH STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1204,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,856000,"Improvements and Relaying CC Road at GKM COLONY 36TH STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1205,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,444000,"Improvements and Relaying CC Road at THIRUVALLUR NAGAR in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1206,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,247000,"Improvements and Relaying CC Road at JAYANTHI NAGAR KAMARAJAR STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1207,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,198000,"Improvements and Relaying CC Road at RAJAJI NAGAR VAIGAI CROSS STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1208,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,151000,"Improvements and Relaying CC Road at RAJAJI NAGAR PETER CROSS STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1209,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,339000,"Improvements and Relaying CC Road at SILANTHI KUTTAI KAMARAJAR STREET in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1210,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,806000,"Improvements and Relaying CC Road at K.R COLONY in Dn 65, Unit 15, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/15894,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,250000,"Providing Borewell & Water Supply Arragements at Janagiram reddy Colony Park in Div-65, Unit -15, Zone -6.",MLACDS,6,2018-19,2019-20 NF/2018-19/2898,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,4000000,"Construction of Care taker room ,Store room And other works @ Burial Ground In Gkm Colony Jambulingam Main Road In Dn-65 U-15 Z-06,",MLACDS,6,2018-19,2019-20 NF/2018-19/3664,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,166000,"IMPROVEMENTS TO THEY MOHAMMED USSAN COLONY AMMA UNAVAGAM IN DN-65 U-15 Z-06,",Own Sources,6,2018-19,2018-19 NF/2018-19/3667,Electrical,Completed,NF-THIRU-VI-KA NAGAR,65,65000,"IMPROVEMENTS TO THEY MOTOR REPAIR AND BORE FLUSH IN ROHINI PARK ,GKM COLONY JAMBULINGAM MAIN ROAD PC AND JANAKIRAM REDDY COLONY PARK IN DN-65 U-15 Z-06,",Own Sources,6,2018-19,2018-19 NF/2018-19/7362,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,254000,"Storm Water Drain in MINOR REPAIR WORK IN VARIOUS STREET IN DN-65U-15 Z-06,",Own Sources,6,2018-19,2019-20 NF/2018-19/8851,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,38000,"Repair work to Water tank @ gkm Colony Burial ground in Dn-65 U-15 Z-06,",Own Sources,6,2018-19,2018-19 NF/2018-19/8892,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,816000,"Desilting Work to the exisitng SWD in Vivekanandha main Road Rajaji nagar ,Venus nagar Senthil Nagar,Thilli nagar Various streets IN Dn-65,Unit-15,Zone-06.",Own Sources,6,2018-19,2019-20 BR/2018-19/16016,Roads,Completed,BR-Bus Route Roads,66,994000,Restoration of OFC road cut made by M/s Bharathi Airtel at various Bus Route Roads in zone VI Deposit code:57/0233/2018-19,Deposit Works,6,2018-19,2019-20 BR/2018-19/16711,Road Cut,Completed,BR-Bus Route Roads,66,857000,"Restoration of Roadcut made by ACT at Kumaran nagar 1st Main Road, ayyalu Street, Nagammal Street, Nagammal Street, Varatharajan Street, Krishna Nagar and various streets in Dn-66, Zone-6 (Chellan No.06/2018-19 /0226859 & 06/2018-19/0226866 Dt.01.06.2018)",Deposit Works,6,2018-19,2019-20 BR/2018-19/16947,Road Cut,Completed,BR-Bus Route Roads,66,839000,"Restoration of Roadcut made by ACT at Jaganathan Salai , Karthikeyan Salai, Papermills Road, Lakshman Nagar, Ragavendra Link Road and various streets in Dn-66,Zone-6 (Chellan No.06/2018-19/0226859 & 06/2018-19/0226866 Dt.01.06.2018)",Deposit Works,6,2018-19,2019-20 BR/2018-19/5592,Road Cut,Completed,BR-Bus Route Roads,66,2480000,Restoration of roadcut made by CMWSSB at karthikeyan salai from the jn of 70 feet Road in Dn -66 Zone - 6(Chellan code 57/0841/2017-18),Deposit Works,6,2018-19,2018-19 BR/2018-19/5598,Road Cut,Completed,BR-Bus Route Roads,66,2290000,Restoration of Roadcut made by CMWSSB at karthikeyan salai from the jn of Balasubramanian street in Dn -66 Zone - 6(Chellan code 57/0841/2017-18),Deposit Works,6,2018-19,2019-20 BR/2018-19/5965,Roads,Completed,BR-Bus Route Roads,66,812000,Restoration of Road cut made by reliance jio at various roads in Zone 6 ( Challan No : BR/2017-18/0012037 Deposit code 57/0683/2017-18.),Deposit Works,6,2018-19,2018-19 L/2018-19/4938,Electrical,Completed,L-Electrical,66,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Jawahar road circular salai in dn 65, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4939,Electrical,Completed,L-Electrical,66,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office jawahar nagar 3rd street in dn-66, Zone- VI.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/0247,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,320000,"Improvements to BT Road at Siva elango salai West in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2018-19 NF/2018-19/1009,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,2500000,"Providing Modern GYM Apparatus at Jawahar nagar 1st circular road Playground in Div-66,Unit-16,Zone-6",MLACDS,6,2018-19,2018-19 NF/2018-19/1010,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1772000,"Improvements to BT Road at Jawahar nagar 4th main road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11171,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,691000,"Improvements to BT Road at Murugan Nagar 7th Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11172,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,652000,"Improvements to BT Road at Poompuhar Nagar west 1st & 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11173,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,287000,"Improvements to BT Road at NVM Nagar in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11174,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,587000,"Improvements to BT Road at Poompuhar Nagar 8th Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11175,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,411000,"Improvements to BT Road at Rajarajeshwari 4th street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11176,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,691000,"Improvements to BT Road a Murugan Nagar 5th Street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11178,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,550000,"Improvements to BT Road at Ashoka Avenue 1st main road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11183,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,219000,"Improvements to BT Road at Venkateswaranagar ambedkar st in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11186,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,247000,"Improvements to BT Road at Balakumaran nagar c part in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11190,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,331000,"Improvements to BT Road at Rajan Nagar Main Road in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11195,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,592000,"Improvements to BT Road at Balaji naagr 8th cross street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11196,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,542000,"Improvements to BT Road at Nermai nagar 1st street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11197,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,606000,"Improvements to BT Road at Velavan nagar 1st & 2nd street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11198,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,291000,"Improvements to BT Road at Lakshmi nagar 7th street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11199,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,6370000,"Improvements to BT Road at MGR Nagar Gangaiyamman kovil street in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11200,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2251000,"Improvements to BT Road at Sivasakthinagar 3rd st Extn in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11201,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1714000,"Improvements to CC ROAD MURUGAN NAGAR 2ND MAIN ROAD in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11202,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1905000,"Improvements to CC Road at UNITED COLONY1ST MAIN ROAD in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11203,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1457000,"Improvements to CC Road at SIVASAKTHI NAGAR 3RD STREET in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11204,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,458000,"Improvements to CC Road at SIVASAKTHI NAGAR EXTN 5TH STREET in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11205,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1870000,"Improvements to CC Road at KAMBAR STREET & SUBRAMANIAN STREET in Div-64,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11224,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,97000,"Improvements to BT Road at Janagiram nagar 4th lane in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11231,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1206000,"Improvements to BT Road at ayyavoo gramaniya lane 1 st, 2 nd, 3rd in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11233,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,812000,"Improvements to BT Road at Voc 1 st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11248,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,714000,"Improvements to BT Road at GKM Colony 18th Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11793,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,644000,"Minor Repairs work for Existing storm water drain at Venugopal street,Govindasamy street and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11794,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,596000,"De-silting of Existing Storm water drain at Venugopal street,Govindasamy street,Sivalingam street,Kumppusamy street and various streets in Div-66,Unit-16,Zone-6.",Own Sources,6,2018-19,2019-20 NF/2018-19/11795,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,584000,"Minor Repairs work for Existing storm water drain at Jawhar nagar 3rd circular road,2nd cross street,Periyar nagar 14th street , Siva elango salai and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11796,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,617000,"De-silting of existing storm water drain at Periyar nagar 14th street,Jeganathan salai,Karthikeyan salai,Jawahar nagar and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11797,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,693000,"Minor Repairs work for Existing storm water drain at SRP Colony,Ramamoorthy colony,Balaraman street and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11798,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,584000,"De-silting of Existing storm water drain at SRP Colony,Ramamoorthy colony ,Balaraman street and various streets in Div-66,Unit-16,Zone-6.",Own Sources,6,2018-19,2019-20 NF/2018-19/1248,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1041000,"Improvements to BT Road at Jawahar nagar 3rd main road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1249,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,871000,"Improvements to BT Road at Jawahar nagar 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1250,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,569000,"Improvements to BT Road at Jawahar nagar 3rd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1251,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1441000,"Improvements to BT Road at Jawahar nagar 2nd circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1252,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,2211000,"Improvements to BT Road at Jawahar nagar 3rd circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1253,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,663000,"Improvements to BT Road at Jawahar nagar 3rd circular 1st cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1254,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1804000,"Improvements to BT Road at Jawahar nagar 4th circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1255,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,700000,"Improvements to BT Road at Jawahar nagar 4th circular cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1256,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,566000,"Improvements to BT Road at Periyar nagar 5th street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1257,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1182000,"Improvements to BT Road at Periyar nagar 4th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1258,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,580000,"Improvements to BT Road at Chelliamman koil 1st street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1259,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,586000,"Improvements to BT Road at Chelliamman koil 2nd street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1260,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,684000,"Improvements to BT Road at Sivaprakasam street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1261,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,659000,"Improvements to BT Road at Bashyam street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1262,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,1504000,"Improvements to the BT Road at Ayyalu street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1263,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,461000,"Improvements to the BT Road at Paul varghese street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1264,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,425000,"Improvements to the BT Road at Andal avenue 2nd street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1265,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,3350000,"Improvements to the BT Road at Siva Elango salai street (west) in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1266,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,3900000,"Improvements to the BT Road at Siva elango salai street ( East) in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1267,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,809000,"Improvements to the BT Road at Kumaran nagar 1st main road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1268,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,420000,"Improvements to the BT Road at Kumaran nagar 1st cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1269,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,263000,"Improvements to the BT Road at Kumaran nagar 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1270,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,920000,"Improvements to the BT Road at Kumaran nagar 3rd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1271,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,331000,"Improvements to the BT Road at Kumaran nagar 4th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1272,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,440000,"Improvements to the BT Road at Sakthivel nagar 1st cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1273,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,552000,"Improvements to the BT Road at Sakthivel nagar 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1274,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,552000,"Improvements to the BT Road at Sakthivel nagar 3rd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1275,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,289000,"Improvements to the BT Road at Sakthivel nagar 4th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1276,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,132000,"Improvements to the BT Road at Sakthivel nagar 5th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1277,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,289000,"Improvements to the BT Road at Sakthivel nagar 6th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1278,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,587000,"Improvements to the BT Road at Sakthivel nagar 7th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1279,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,580000,"Improvements to the BT Road at Sakthivel nagar school road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1280,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,202000,"Improvements to the BT Road at Chelliamman colony main road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1281,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,212000,"Improvements to the BT Road at Chelliamman colony 1st street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1282,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,431000,"Improvements to the BT Road at Chelliamman colony 2nd street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1283,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,215000,"Improvements to the BT Road at Dhanraj main street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1284,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,313000,"Improvements to the BT Road at Dhanraj 1st street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1285,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,286000,"Improvements to the BT Road at Dhanraj 2nd street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1286,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,316000,"Improvements to the CC Road at Markandeyan street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1287,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,446000,"Improvements to the CC Road at Markandeyan lane in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/1288,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,524000,"Improvements to the CC Road at Ram nagar 3rd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14384,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,250000,"Providing Borewell & water supply arrangements at Jawahar nagar 2nd circular road park in Div-66,Unit-16,Zone-6",MLACDS,6,2018-19,2019-20 NF/2018-19/14873,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,250000,"Providing Borewell & water supply arrangements at Jawahar nagar 5th main road park in Div-66,Unit-16,Zone-6",MLACDS,6,2018-19,2019-20 NF/2018-19/15364,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,250000,"Providing Borewell & water supply arrangements at Periyar nagar 20th street park in Div-66,Unit-16,Zone-6",MLACDS,6,2018-19,2019-20 NF/2018-19/17498,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,765000,"MAINTENANCE AND OPERATION OF WATER TREATMENT PLANT (AMMA KUDINEER) AT PERIYAR NAGAR PERIPHERAL HOSPITAL CAMPUS, KARTHIKEYAN SALAI IN DN-66,UNIT-16,ZONE-06",Own Sources,6,2018-19,2020-21 NF/2018-19/2091,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,274000,"Improvements to the CC Road at Thiruvenkadam street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/2107,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,265000,"Improvements to the CC Road at Ramani bai colony in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/4817,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,2000000,"Construction of Sewing training center in Scout office at Jawahar nagar 1st circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2018-19 NF/2018-19/5521,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,45000,"Improvements to Periyar nagar 20th street park in Div-66,Unit-16,Zone-6.",Own Sources,6,2018-19,2018-19 NF/2018-19/6370,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,828000,"Improvements to the CC Road at Lakshman nagar in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/6406,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,888000,"Improvements to the CC Road at Ragavendra link road in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/6407,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,418000,"Improvements to the CC Road at Annal gandhi street in Div-66,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/8768,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,98000,"Repair and Improvements to Bio-Gas Plant at Jawahar Nagar 1st Circular Road in Dn-66 , Un-16 , ZN-6",Own Sources,6,2018-19,2018-19 BR/2018-19/5430,Road Cut,Completed,BR-Bus Route Roads,67,1140000,"Restoration of Roadcut made by CMWSSB at GKM Colony 17th Street in Dn-67, Zone-VI (Chellan code :57/0841/2017-18)",Deposit Works,6,2018-19,2019-20 BR/2018-19/5966,Roads,Completed,BR-Bus Route Roads,67,755000,"Road cut restoration (road cut made by reliance jio) at various division in Zone 6 against the challan no 08/2017-18/0410704,08/2017-18/0410711,DT: 01.08.2017 and Deposit code 57/0683/2017-18.",Deposit Works,6,2018-19,2018-19 BR/2018-19/9537,Road Cut,Completed,BR-Bus Route Roads,67,2435000,"Restoration of roadcut Made by CMWSSB at Jumbulingam main road (from the jn of GKM Colony 21st Street to GKM Colony 14th Street) in Dn-65, Zone -6",Deposit Works,6,2018-19,2019-20 D/2018-19/9925,Storm Water Drain,Completed,D-Storm Water Drains,67,19375000,"Construction of Storm Water Drain at Paper Mills road(Jn of SRP colony 8th street to Anna statue) and 3 other roads in Zone - 6, Package - 23",Grants,6,2018-19,2020-21 L/2018-19/1151,Electrical,Completed,L-Electrical,67,2057000,Supply and replacement of 7 mtr lamp post inplace of rusted and damaged lamp post being inside the railway compound wall at Muthukumarappa salai in div 67 of zone VI,Own Sources,6,2018-19,2018-19 L/2018-19/4940,Electrical,Completed,L-Electrical,67,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHSS , Market street in Div67 Zone- 6",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4942,Electrical,Completed,L-Electrical,67,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital, Somaiya street in Div67 Zone- 6",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4943,Electrical,Completed,L-Electrical,67,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi,G.K.M.Colony 1-9th street in Div67, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4958,Electrical,Completed,L-Electrical,67,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi GKM colony 14th street in Div67, Zone- VI.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4978,Electrical,Completed,L-Electrical,67,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS GKM Colony 12th street in Dn67, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/6475,Electrical,Completed,L-Electrical,67,2677200,"Electrification work in CHSS at strahans road,CGHS at market street ,CHS at somaiya raja street,CMS at Rangasayee street and CPS at GKM Colony Pappammal street in division 67 and 76 of Zone6.",Own Sources,6,2018-19,2019-20 NF/2018-19/11243,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,2071000,"Improvements to BT Road at Loco scheme 1st street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11244,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,364000,"Improvements to BT Road at Moorthy raja street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11245,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,736000,"Improvements to BT Road at GKM Colony 21st street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11246,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,690000,"Improvements to BT Road at GKM Colony 19th street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11247,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,761000,"Improvements to BT Road at GKM Colony 20th Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11249,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,497000,"Improvements to BT Road at GKM Colony 17th Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11250,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,718000,"Improvements to BT Road GKM Colony 15th Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11251,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,379000,"Improvements to BT Road at GKM Colony 12th Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11252,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,317000,"Improvements to BT Road at Somiya Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/11253,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,298000,"Improvements to BT Road at Somasundaram Main Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11258,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,404000,Minor Repairs work at Muthukumarppa salai in Dn 67 Unit 15 Zone 6,Own Sources,6,2018-19,2019-20 NF/2018-19/11274,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,598000,"Desilting at Rangasayee street , GKM Colony Main Road , Sai Nagar, Loco scheme 1 street and Various Street in dn -67,unit-15,zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11288,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1675000,"Improvements to BT Road at Jambulingam main road in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11289,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,1541000,"Improvements to CC Road GKM Colony 16th street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11290,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,313000,"Improvements to CC Road at Somaramasamy 1st Street in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12102,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,750000,Erection of 250 LPH Plant with Pre Filtration at Chennai Girls Higher Secondary School at Market Street in Dn 67 Unit 15 Zone 6 (MLA FUND),MLACDS,6,2018-19,2019-20 NF/2018-19/12104,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,750000,Erection of 250 LPH Plant with Pre Filtration at Chennai Middle School at Rangasayee Street in Dn 67 Unit 15 Zone 6 (MLA FUND),MLACDS,6,2018-19,2019-20 NF/2018-19/12108,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,500000,Providing Borewell arrangements & Sump at Chennai High School at Somiya Street in Dn 67 Unit 15 Zone 6 (MLA FUND),MLACDS,6,2018-19,2020-21 NF/2018-19/12467,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,198000,"Repairs & Improvements to Amma unavagam at Loco works road in Div-67,Unit-15,Zone-6",Own Sources,6,2018-19,2019-20 BR/2018-19/16955,Road Cut,Completed,BR-Bus Route Roads,68,452000,"Restoration of Roadcut made by ACT at Anbhazagan Salai , Kennady Square Cross Street, Cheran Street and Various Street in Dn-68, Zone-6 ( Chellan No.06/2018-19/0226859 & 06/2018-19/0226866, DT.01.06.2018)",Deposit Works,6,2018-19,2019-20 BR/2018-19/3548,Roads,Completed,BR-Bus Route Roads,68,650000,"Proposed laying of Speed Breakers at Pallavan Salai , Madavaram High road, Perambur high road (South) and the jn of AA road under Road safety fund in Zone - 6",Own Sources,6,2018-19,2018-19 BR/2018-19/6846,Footpath,Completed,BR-Bus Route Roads,68,1206000,"Footpath Repair Works at Pallavan Salai in Dn-68, Zone-VI",Grants,6,2018-19,2019-20 BR/2018-19/6847,Footpath,Completed,BR-Bus Route Roads,68,1148000,"Footpath Repair Works at SRP Koil Street North in Dn-68, Zone-VI",Grants,6,2018-19,2019-20 BR/2018-19/7521,Roads,Completed,BR-Bus Route Roads,68,31000,Restoration of road cut made by CMWSSB at SRP Koil street in zone-6 against challan no:BR/2018-19/0006752,Deposit Works,6,2018-19,2019-20 D/2018-19/9927,Storm Water Drain,Completed,D-Storm Water Drains,68,53210000,"Construction of Storm Water Drain at Paper Mills road on South - East side and 3 other roads in Zone - 6 and Baba Nagar 1 st main road on North side and 5 other roads in Zone - 8, Package - 25.",Grants,6,2018-19,2020-21 L/2018-19/4951,Electrical,Completed,L-Electrical,68,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Jamaliya-7030, in Div68, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4952,Electrical,Completed,L-Electrical,68,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Jaibeem nagar-1120, in Div68, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4953,Electrical,Completed,L-Electrical,68,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Jaibeem nagar-1121, in Div68, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4954,Electrical,Completed,L-Electrical,68,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Thiru.vi.ka.nagar-7036, in Div68, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4955,Electrical,Completed,L-Electrical,68,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Thiru.vi.ka.nagar-7034, in Div68, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4956,Electrical,Completed,L-Electrical,68,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Paper mills road-7040, in Div68, Zone- VI.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4957,Electrical,Completed,L-Electrical,68,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Paper mills road-7038, in Div68, Zone- VI.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4977,Electrical,Completed,L-Electrical,68,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office in dn68, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4985,Electrical,Completed,L-Electrical,68,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Gopalapuram in Dn68 Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4988,Electrical,Completed,L-Electrical,68,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary Paper Mills road in Dn68 Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4989,Electrical,Completed,L-Electrical,68,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS Thiruvika nagar in Dn68 Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/5451,Electrical,Completed,L-Electrical,68,192600,"Electrification of Additional wiring for Smart class at Various School in division 64, 67, 68 & 70 in Zone VI",Own Sources,6,2018-19,2019-20 L/2018-19/6464,Electrical,Completed,L-Electrical,68,4822700,"Electrification work of CPS at Thiruvikanagar, Cookes road, Vasantha garden & Suburayan 1st street , CMS at Gopalapuram, Maduma nagar & Mangalapuram, CHS at Bunder garden, Padavattamman koil street & Chinnababu street in various div 68, 69, 70, 71, 73, 74 & 75 in zone VI.",Own Sources,6,2018-19,2019-20 NF/2018-19/11212,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,682000,"Improvements to BT Road at gurusamy st ( george colony) in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11213,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,261000,"Improvements to BT Road at teeds garden 3 rd cross st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11219,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,769000,"Improvements to BT Road at mohamadiyan st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11220,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1001000,"Improvements to BT Road at Thillai nayagam 6 th st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11221,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,910000,"Improvements to BT Road at sababathy st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11222,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,948000,"Improvements to BT Road at tvk nagar 22 nd st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11223,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,850000,"Improvements to BT Road at Janagiram nagar 2 nd main road in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11225,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,538000,"Improvements to BT Road at ragavan st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11226,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1083000,"Improvements to BT Road at anbazagan 4 th st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11227,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1074000,"Improvements to BT Road at prakasam st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11229,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,437000,"Improvements to BT Road at lakshmi nagar main road in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11230,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,347000,"Improvements to BT Road at lakshmi nagar 4th st in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11232,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,823000,"Improvements to BT Road at thillai nayagam main road in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11783,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,438000,"DE-SILTING OF EXISTING STORM WATER DRAIN AT VARIOUS STREETS AT DIV-68,UNIT-16,ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12005,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,598000,"Improvements to the CC Road at Gurusamy(Jai beam Nagar) in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12008,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,171000,"Improvements to the CC Road at Vasudevan 2nd lane in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12009,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,306000,"Improvements to the CC Road at Subramani Thottam 1st Street in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12011,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,387000,"Improvements to the CC Road at Subramani Thottam 2nd Street in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12012,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,661000,"Improvements to the CC Road at Kalyana Sundaram Main street in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12013,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,171000,"Improvements to the CC Road at Kalyana Sundaram Cross Lane in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12015,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1471000,"Improvements to the CC Road at Othavadai street in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12016,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1013000,"Improvements to the CC Road at Gopalapuram 1st Street in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12018,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,968000,"Improvements to the CC Road at teeds garden 1st street in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12059,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1976000,"Improvements to the CC Road at Kennedy Square 1st North in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12060,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1440000,"Improvements to the CC Road at MSM (Vasantham Apartment in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12111,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1500000,"Providing Borewell and water supply arrangement and Infrastructure facility at Chennai Middle School at Gopalapuram in DN68,UN16,Z6(MLA FUND)",MLACDS,6,2018-19,2019-20 NF/2018-19/12135,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,300000,PROVIDING BOREWELL AND WATER SUPPLY ARRANGEMENT TO VETERINARY HOSPITAL AT PALLAVAN SALAI IN DN 68 UNIT 16 ZONE 6(MLA FUND),MLACDS,6,2018-19,2019-20 NF/2018-19/12137,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,99000,"Demolition of Old dilabilated ICDS Centre at Teeds garden 1st street in div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12148,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,2000000,"Construction of ICDS (Centre No.3360307217) at Teeds Garden 1st Street in Dn-68 , Un-16 , Z-6",MLACDS,6,2018-19,2019-20 NF/2018-19/13950,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,2500000,"Construction of Care Taker Room , Compound Wall and Infrastructure Facility and Construction of Chimney shrubber unit,furnace front frame and manual door at Thangal Burial Ground at pallavan salai in Dn-68 , Un-16 , Z-6",MLACDS,6,2018-19,2019-20 NF/2018-19/15889,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,250000,"Providing Borewell & water supply arrangements at Guru sami street George Park in Div-68, Unit -16, Zone -6.",MLACDS,6,2018-19,2019-20 NF/2018-19/2524,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,62000,"Providing Chain link fencing at Thiru. Vi. Ka nagar , 22nd st (OSR Land - Opp. to Fish Market ) in Dn-68 , Un-16 , Z-6",Own Sources,6,2018-19,2018-19 NF/2018-19/3457,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,32700,"WATER SUPPLY AND ELECTRICAL ARRANGEMENT FOR ELECTRONIC TOILET (GENERAL) AT PALLAVAN SALAI (NEAR BURIYAL GROUND) JUNCTION IN DIV - 68 ,UNIT-16 ,ZONE-6",Own Sources,6,2018-19,2018-19 NF/2018-19/5249,Playfields,Completed,NF-THIRU-VI-KA NAGAR,68,4500000,"Providing of Batminton court , Volley Ball Court , Football Pitch, Footpath and High mast Lightening Arrangement in the playground at Maduraisamy madam in Dn - 68 ,Un -16 , Z - 6 (MLA Fund)",MLACDS,6,2018-19,2019-20 NF/2018-19/8883,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,299000,"Repairs & Improvements to Night shelter at Jai beem nagar 1st street in Div-68,Unit-16,Zone-6",Own Sources,6,2018-19,2018-19 NF/2018-19/9618,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,605000,MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2018-19,2019-20 BR/2018-19/16959,Road Cut,Completed,BR-Bus Route Roads,69,452000,"Restoration of Roadcut made by ACT at Chinnakulanthai 1st Street, 2nd Street, Kabilar Street and various streets in Dn-69, Zone-6 (Chellan No.06/2018-19/0226859, 06/2018-19/0226866 Dt.0106.2018)",Deposit Works,6,2018-19,2019-20 BR/2018-19/6848,Footpath,Completed,BR-Bus Route Roads,69,818000,"Footpath Repair Works at Madhavaram High Road in Dn-69, Zone - VI",Grants,6,2018-19,2019-20 BR/2018-19/7514,Roads,Completed,BR-Bus Route Roads,69,73500,Restoration of road cut made by CMWSSB at Paper mills road in zone-6 against challan no:BR/2018-19/0007002.,Deposit Works,6,2018-19,2019-20 BR/2018-19/7525,Roads,Completed,BR-Bus Route Roads,69,78000,Restoration of road cut made by CMWSSB at Paper mills road in zone-6 against challan no:BR/2017-18/28210.,Deposit Works,6,2018-19,2019-20 D/2018-19/9924,Storm Water Drain,Completed,D-Storm Water Drains,69,29632000,"Construction of Storm Water Drain at Bunder Garden main street and Madhavaram High road in Dn - 69, Zone - 6, Package - 22.",Grants,6,2018-19,2019-20 L/2018-19/4948,Electrical,Completed,L-Electrical,69,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Mylappa cross street in Div69, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4949,Electrical,Completed,L-Electrical,69,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,Madurai street in Div69, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4950,Electrical,Completed,L-Electrical,69,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP, Thikkakulam in Div69, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4974,Electrical,Completed,L-Electrical,69,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Siruvallur Health post Kabilar street in dn69, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4975,Electrical,Completed,L-Electrical,69,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health post Vasantha garden in dn69, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4976,Electrical,Completed,L-Electrical,69,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary Thiruvika nagar in dn68, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4986,Electrical,Completed,L-Electrical,69,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Vasantha garden in Dn69 Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4987,Electrical,Completed,L-Electrical,69,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Maduma Nagar in Dn69 Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/0689,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,146000,"Improvements to Amma Unavagam Phase - II at M.H Road in Div-69, Un-16 , Z-6",Own Sources,6,2018-19,2018-19 NF/2018-19/11784,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,366000,"Minor repair works for existing storm water drain at Anderson road,kabilar street and various streets in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11786,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,864000,"De-silting of Existing storm water drain at Anderson road,kabilar street and various streets in Div-69,Unit-16,Zone-6.",Own Sources,6,2018-19,2019-20 NF/2018-19/11925,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,131000,"Improvements to BT Road at Jawahar nagar Venkateshwara nagar main road in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11926,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,355000,"Improvements to BT Road at Venkateshwara nagar 2nd street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11927,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,407000,"Improvements to BT Road at Venkateshwara nagar 1st street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11928,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,110000,"Improvements to BT Road at venkateshwara nagar cross street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11929,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,1292000,"Improvements to BT Road at Jawahar street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11930,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,479000,"Improvements to BT Road at Chinnakulanthai street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11931,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,308000,"Improvements to BT Road at Bangaru street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11932,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,2138000,"Improvements to BT Road at Raghavan street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11933,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,297000,"Improvements to BT Road at Beer shop lane in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11934,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,461000,"Improvements to BT Road at Gnammal garden 1st street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11935,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,431000,"Improvements to BT Road at Gnammal garden 2nd street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11936,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,269000,"Improvements to BT Road at Aartisiyan shunmugam street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11937,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,803000,"Improvements to the CC Road at Madurai street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11938,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,2542000,"Improvements to the CC Road at Foxen street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11940,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,427000,"Improvements to the CC Road at Thanikachalam street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11942,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,534000,"Improvements to the CC Road at MES(EB) Street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11943,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,145000,"Improvements to the CC Road at Venkateshwara nagar 2nd street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11944,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,163000,"Improvements to the CC Road at Vsantha garden 4th steet in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11945,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,327000,"Improvements to the CC Road at Chokkalingam street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11946,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,2334000,"Improvements to the CC Road at SSV Koil 2nd street in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11947,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,469000,"Improvements to the CC Road at SSV Koil 2nd lane in Div-69,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/13011,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,975000,"Repair works & Improvements to Zonal office at Anderson road in Div-69,Unit-16,Zone-6.",Own Sources,6,2018-19,2020-21 NF/2018-19/15885,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,250000,"Providing Borewell & Water supply arrangements at Vengatesvara nagar Park in Div-69, Unit -16, Zone -6",MLACDS,6,2018-19,2019-20 NF/2018-19/15887,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,250000,"Providing Borewell & Water supply arrangements at Ragavanan street Park in Div-69, Unit -16, Zone -6",MLACDS,6,2018-19,2019-20 NF/2018-19/2494,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,555000,"Modernization for English Lab at CHSS, Bunder garden main street in Div-69,Unit-16,Zone-6.",MLACDS,6,2018-19,2018-19 NF/2018-19/8677,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,310000,"REPAIRS TO LEAKAGE OF RCC ROOF, AC SHEET ROOFING AND REPAIRS TO GYPSUM FALSE CEILING AT SECOND FLOOR MEETING HALL, STAIRCASE HEAD ROOM, TOILET DAMAGED BY TREE FALL DURING MONSOON HEAVY RAINS AT ZONAL OFFICE BUILDING IN DN-69, UNIT-16, ZONE-VI",Own Sources,6,2018-19,2018-19 NF/2018-19/8886,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,467000,"Demolition of Corporation Higher Secondary School (Block-1) in Bunder Garden Street in Div-69 , Un-16 , Z-6",Own Sources,6,2018-19,2019-20 BR/2018-19/10831,Road Cut,Completed,BR-Bus Route Roads,70,2480000,"Restoration of roadcut made by CMWSSB at Perambur High Road (South) from the jn of Jamalia School to the jn of Flyover in Dn -70 , Zone - 6",Deposit Works,6,2018-19,2019-20 BR/2018-19/17433,Road Cut,Completed,BR-Bus Route Roads,70,2190000,Restoration of Roadcut made by OFC Operators at various Bus Route Roads and Interior Roads in Zone - 6,Deposit Works,6,2018-19,2019-20 BR/2018-19/3093,Road Cut,Completed,BR-Bus Route Roads,70,1670000,Restoration of roadcut made by TANGEDCO at Konnur High Road from the jn of Medavakkam tank road to the jn Mariamman temple in Zone - 6 (Chellan No: BR/2017-18/0025484),Deposit Works,6,2018-19,2018-19 BR/2018-19/3142,Road Cut,Completed,BR-Bus Route Roads,70,1660000,Restoration of roadcut made by TANGEDCO at Konnur High Road from the jn of Mariamman temple to the jn of Tank bund road in Zone - 6 (Chellan No: BR/2017-18/0025484),Deposit Works,6,2018-19,2018-19 BR/2018-19/5130,Road Cut,Completed,BR-Bus Route Roads,70,2490000,"Restoration of Roadcut made by CMWSSB at Perambur High Road (South) from the jn of Cooks Road to the jn of Haji Abdul Rahim Street in Dn-70, Zone-6 (Chellan No.BR/2017-18/0029358)",Deposit Works,6,2018-19,2018-19 BR/2018-19/6578,Roads,Completed,BR-Bus Route Roads,70,44615000,"Widening the road with DBM and BC by paver finisher using plastic waste along with traffic improvement work at Konnur High Road (From jn of Medavakkam Tank Road to jn of Cooks Road) in Dn-70, Zone - VI",Grants,6,2018-19,2020-21 BR/2018-19/6862,Footpath,Completed,BR-Bus Route Roads,70,45000,"Footpath Repair Works at Anna Nagar 21st Main Road in Dn-95, Zone-VIII",Grants,6,2018-19,2019-20 BR/2018-19/7434,Footpath,Completed,BR-Bus Route Roads,70,662000,"Footpath Repair Works at Royapettah High Road in Dn-119, Zone-IX",Grants,6,2018-19,2019-20 BR/2018-19/7437,Footpath,Completed,BR-Bus Route Roads,70,204000,"Footpath Repair Works at Luz Church Road in Dn-123, Zone-IX",Grants,6,2018-19,2019-20 BR/2018-19/7439,Footpath,Completed,BR-Bus Route Roads,70,640000,"Footpath Repair Works at TTK Road in Dn-118 & 123, Zone - IX",Grants,6,2018-19,2020-21 BR/2018-19/7440,Footpath,Completed,BR-Bus Route Roads,70,707000,"Footpath Repair Works at Dr.radhakrishnan Salai in Dn-119 & 121, Zone-IX",Grants,6,2018-19,2019-20 BR/2018-19/7441,Footpath,Completed,BR-Bus Route Roads,70,998000,"Footpath Repair Works at Cathedral Road in Dn-118, Zone-IX",Grants,6,2018-19,2020-21 BR/2018-19/7442,Footpath,Completed,BR-Bus Route Roads,70,1129000,"Footpath Repair Works at Avvai Shanmugam Salai in Dn-119, Zone-IX",Grants,6,2018-19,2020-21 BR/2018-19/7443,Footpath,Completed,BR-Bus Route Roads,70,1170000,"Footpath Repair Works at Dr.Natesan Salai in Dn-116, Zone-IX",Grants,6,2018-19,2020-21 BR/2018-19/7444,Footpath,Completed,BR-Bus Route Roads,70,1003000,"Footpath Repair Works at North Boag Road in Dn-117, Zone-IX",Grants,6,2018-19,2019-20 BR/2018-19/7445,Footpath,Completed,BR-Bus Route Roads,70,1180000,"Footpath Repair Works at South Boag Road in Dn-117, Zone-IX",Grants,6,2018-19,2019-20 BR/2018-19/7447,Footpath,Completed,BR-Bus Route Roads,70,736000,"Footpath Repair Works at Thirumalai Pillai Road in Dn-117, Zone-IX",Grants,6,2018-19,2019-20 BR/2018-19/7454,Footpath,Completed,BR-Bus Route Roads,70,2869000,"Footpath Repair Works at Ashok Nagar 2nd Avenue in Dn-132, Zone-X",Grants,6,2018-19,2018-19 BR/2018-19/7455,Footpath,Completed,BR-Bus Route Roads,70,1590000,"Footpath Repair Works at Ashok Nagar 4th Avenue in Dn-132 & 133, Zone-X",Grants,6,2018-19,2019-20 BR/2018-19/7456,Footpath,Completed,BR-Bus Route Roads,70,929000,"Footpath Repair Works at Ashok Nagar 7th Avenue in Dn-132, Zone-X",Grants,6,2018-19,2018-19 BR/2018-19/7457,Footpath,Completed,BR-Bus Route Roads,70,1640000,"Footpath Repair Works at Kamarajar Salai in Dn-132, Zone-X",Grants,6,2018-19,2020-21 BR/2018-19/7458,Footpath,Completed,BR-Bus Route Roads,70,1082000,"Footpath Repair Works at Duraisamy Road in Dn-133, Zone-X",Grants,6,2018-19,2018-19 BR/2018-19/7459,Footpath,Completed,BR-Bus Route Roads,70,246000,"Footpath Repair Works at Dr.Ambedkar Road in Dn-134, Zone-X",Grants,6,2018-19,2018-19 BR/2018-19/7460,Footpath,Completed,BR-Bus Route Roads,70,1440000,"Footpath Repair Works at Brindavan Street in Dn-135, Zone-X",Grants,6,2018-19,2019-20 BR/2018-19/7461,Footpath,Completed,BR-Bus Route Roads,70,1710000,"Footpath Repair Works at Ashok Pillar Road in Dn-138, Zone-X",Grants,6,2018-19,2019-20 BR/2018-19/7462,Footpath,Completed,BR-Bus Route Roads,70,2281000,"Footpath Repair Works at Sardar Patel Road in Dn-171 & 174, Zone - XIII",Grants,6,2018-19,2019-20 BR/2018-19/7515,Roads,Completed,BR-Bus Route Roads,70,36500,Restoration of road cut made by CMWSSB at Madhavaram high road in Zone-6 against challan no:BR/2018-19/0011103,Deposit Works,6,2018-19,2019-20 BR/2018-19/7517,Roads,Completed,BR-Bus Route Roads,70,81500,Restoration of road cut made by CMWSSB at Madhavaram High road in zone-6 against challan no:BR/2018-19/0006281.,Deposit Works,6,2018-19,2019-20 BR/2018-19/9955,Road Cut,Completed,BR-Bus Route Roads,70,789000,"Restoration of roadcut made by CMWSSB at Permbur High Road (south) from the jn of !st Main Road to the jn of Jamalia school in Dn -70, Zone -6",Deposit Works,6,2018-19,2019-20 D/2018-19/14931,Storm Water Drain,Completed,D-Storm Water Drains,70,23830000,"Construction of Double Vent Drain of size 2500x2500mm along Dr. Ambedkar college road from junction of Vyaasarpadi Subway to Otteri Nullah in Dn-70,Zone -VI,package -11.",SMART CITY - SWD,6,2018-19,2020-21 D/2018-19/14932,Storm Water Drain,Completed,D-Storm Water Drains,70,53030000,"Construction of Storm Water Drain of size 2000x2000mm along Dr. Ambedkar college road from the junction of Strahans road to Otteri Nullah in Dn-70 & 73,Zone -VI,Package - 12.",SMART CITY - SWD,6,2018-19,2020-21 D/2018-19/9923,Storm Water Drain,Completed,D-Storm Water Drains,70,32882000,"Construction of Storm Water Drain at Anderson road and 3 other roads in Zone - 6, Package - 21.",Grants,6,2018-19,2019-20 L/2018-19/4971,Electrical,Completed,L-Electrical,70,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Gokulam school cheiyur Parathasarathy street in dn70, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4972,Electrical,Completed,L-Electrical,70,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS school road street in dn70, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4973,Electrical,Completed,L-Electrical,70,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS school Arunthathi nagar in dn70, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4983,Electrical,Completed,L-Electrical,70,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS MH Road in Dn70 Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4984,Electrical,Completed,L-Electrical,70,537600,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS MH Road in Dn70 Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/11264,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,482000,"Improvements to BT Road at NSK Scheme Road in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11265,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,722000,"Improvements to BT Road at Bharathi 2nd Street in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11266,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,793000,"Improvements to BT Road at Kumaraswamy Street in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11267,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,718000,"Improvements to BT Road at Perambur High Road 2nd Street in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11269,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,270000,"Improvements to BT Road at Anna Swamy Street in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11270,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,491000,"Improvements to BT Road at Srinivasan Cross Street in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11271,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,825000,"Improvements to BT Road at Srinivasan Street in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11273,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,447000,"Improvements to BT Road at Rajabhadar Street road in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12215,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,877000,"Improvements to CC Road at Kandhan street road in Div-70,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12216,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,458000,"Improvements to CC Road at State Bank Colony 1st Street in Div-70, unit-16, Zone-6.",Own Sources,6,2018-19,2019-20 NF/2018-19/12974,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,346500,"Desilting Work to the exisitng Storm Water Drain at Various streets in Dn-70, Unit-16, Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/12975,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,249500,"Desilting Work to the exisitng Storm Water Drain at Various streets in Dn-70, Unit-16, Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/12976,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,727000,"Minor Repairs to the exisitng Storm Water Drain at Various streets in Dn-70, Unit-16, Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/12977,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,438000,"Minor Repairs to the exisitng Storm Water Drain at Various streets in Dn-70, Unit-16, Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/3476,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,336000,"IMPROVEMENT OF GYM BUILDING AT TANK LINK ROAD IN DIV-70,UINT-16,ZONE-6.",Own Sources,6,2018-19,2019-20 NF/2018-19/3561,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,167000,"WATER SUPPLY AND ELECTRICAL ARRANGEMENT FOR LAB AT P.H.ROAD NEAR GANDHI PARK IN DIV - 70 ,UNIT-16 ,ZONE-6",Own Sources,6,2018-19,2018-19 NF/2018-19/3708,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,96000,"WATER SUPPLY AND ELECTRICAL ARRANGEMENT FOR P.C. AT CHENGAN STREET IN DIV - 70 ,UNIT-16 ,ZONE-6",Own Sources,6,2018-19,2018-19 D/2018-19/8704,Storm Water Drain,Completed,D-Storm Water Drains,71,20740000,"Construction of Egangipuram canal of size 3000x3000mm from Perambur High road to Egangipuram main street with fencing arrangements in wall in Dn- 71, Zone-VI.",Grants,6,2018-19,2019-20 D/2018-19/9926,Storm Water Drain,Completed,D-Storm Water Drains,71,17382000,"Construction of Storm Water Drain at Janakiram Reddy Colony 4 th street in Dn - 65and Melpatti Ponnappan street in Dn - 70, Zone - 6, Package - 24.",Grants,6,2018-19,2020-21 L/2018-19/0845,Electrical,Completed,L-Electrical,71,975900,"Supply and replacement of 1935 mtrs of damaged 2x25 sq.mm UG Cable at chronicle faulty locations at cement concrete road and Block tapped road in Semathamman colony,Nehru jothi nagar,Hyder garden and Various locations in div 71 zone-VI.",Own Sources,6,2018-19,2018-19 L/2018-19/4970,Electrical,Completed,L-Electrical,71,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Ekangipuram in dn71, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/0037,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,2200000,"PROPOSED CONSTRUCTION OF MODERN GYM AT CHANDRAYOGI SAMADHI ROAD TNSCB TENAMENTS MAIN STREET (UNDER WARD MLA FUND) IN DN-71,UNIT-16,ZONE-6",MLACDS,6,2018-19,2018-19 NF/2018-19/12188,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,445000,"Improvements to BT Road at Bowden Street in Dn-71, Unit-15, Zone 6",Own Sources,6,2018-19,2019-20 NF/2018-19/12192,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2947000,"Improvements to BT Road at Krishnadoss Main Road in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12193,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,503000,"Improvements to BT Road at Krishnadoss 1st Street in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12194,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,2770000,"Improvements to BT Road at Chandrayogi Samathi Street in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12379,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,497242,"Improvements to CC Road at Sasthri Nagar Main street in Div-71, Unit-16, Zone-6.",Own Sources,6,2018-19,2019-20 NF/2018-19/12972,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,740000,"Minor Repairs to the exisitng Storm Water Drain at Various streets in Dn-71, Unit-16, Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/12973,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,347000,"Desilting Work to the exisitng Storm Water Drain at Various streets in Dn-71, Unit-16, Zone-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/14805,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1170000,"Improvements to the CC Road at SEMATHAMMAN COLONY 3RD STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14806,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,631000,"Improvements to the CC Road at ADISESHA NAGAR 4TH STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14807,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,631000,"Improvements to the CC Road at ADISESHA NAGAR 3RD STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14808,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,632000,"Improvements to the CC Road at KRISHNA DOSS 5TH STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14809,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,133000,"Improvements to the CC Road at BRISLEY NAGAR 6TH LANE in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14810,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1167000,"Improvements to the CC Road at SEMATHAMMAN COLONY 1ST STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14811,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,1114000,"Improvements to the CC Road at SEMATHAMMAN COLONY 2ND STREETin Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14813,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,372000,"Improvements to the CC Road at RAJIV GANDHI NAGAR 1ST STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14814,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,298000,"Improvements to the CC Road at RAJIV GANDHI NAGAR 2ST STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14815,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,262000,"Improvements to the CC Road at RAJIV GANDHI NAGAR 3RD STREET in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/14847,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,196000,"Reair & improvements to ICDS Centre (Centre No. 33603070314) at Managalapuram in Div-71,Unit-16,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/14851,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,196000,"Repair & improvements to ICDS cntre (Centre No 33603070315) at Chandrayogi samathi street in Div-71,Unit-6,Zone-6",Own Sources,6,2018-19,2020-21 NF/2018-19/7908,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,248000,"REPAIR WORK AND CONSTRUCTION OF NEW GATE AT G CATTLE DEPOT AT CHANDRAYOGI SAMADHI STREET IN DN-71,UNIT-16,ZONE-6",Own Sources,6,2018-19,2018-19 D/2018-19/14930,Storm Water Drain,Completed,D-Storm Water Drains,72,32935000,"Construction of Storm Water Drain of size 1500 x 1500 mm along Decastor road and Narasiman nagar main road from junction of Dr.Ambedkaar college road to Otteri Nullah in Dn. - 72,Zone - VI,Package - 10.",SMART CITY - SWD,6,2018-19,2020-21 L/2018-19/4285,Electrical,Completed,L-Electrical,72,1907400,"Supply and provision of 19 nos of 40w solar photo voltaic LED fitting with Pole at JJ nasgar 11nos, Ponnappan street 2nos, Grey nagar 2nos, amma Tiffen centre 2nos, EOC Hospital 2nos and Surrounding area in dn 72 & 73 zone 6",MLACDS,6,2018-19,2020-21 L/2018-19/4287,Electrical,Completed,L-Electrical,72,1706600,"Supply and provision of 17 nos of 40w solar photo voltaic LED fitting with Pole at Nagathamman koil st 6nos, Thiruvika nagar Pallam 6nos, VOC nagar 4nos, Thiruvikanagar school 1no, Decastor road school and surrounding areas in dn 72 Zone-6",MLACDS,6,2018-19,2020-21 L/2018-19/4968,Electrical,Completed,L-Electrical,72,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS Thiruvika nagar 3rd street in dn72, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/11013,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1245000,"RELAYING OF ROAD BY USING BC40 MM THICK AT DESIGANADHA SALAI IN DN-72, UNIT-72, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11014,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1080000,"RELAYING OF ROAD BY USING BC 40MM THICK AT DR.AMBEDKAR NAGAR MAIN ROAD IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11015,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,640000,"RELAYING OF ROAD BY USING BC 40MM THICK AT VEERACHETTY STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11016,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,2800000,"RELAYING OF ROAD BY USING BC 40MM THICK AT POWDER MILLS ROAD IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11333,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1035000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT VASUKI NAGAR IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11334,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1089000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT NAGATHAMMAN KOIL STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11335,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,827000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT JOSEPH STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11336,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,546000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KANNIGAPURAM MAIN ROAD IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11337,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,548000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT AMBEDKAR NAGAR 1ST CROSS STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11338,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,503000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT AMBEDKAR NAGAR 2ND CROSS STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11339,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,466000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KANNIYAMMAN KOIL STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11340,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,945000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY A BLOCK MAIN ROAD IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11341,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,364000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY A BLOCK 1 ST STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11342,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,434000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY A BLOCK 1 ST CROSS STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11343,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,620000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY A BLOCK 2 ND STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11344,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,757000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY B BLOCK 2 ND STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11345,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,996000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY B BLOCK 3RD STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11346,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,996000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY B BLOCK 4TH STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11347,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,986000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIBAI COLONY B BLOCK 5 TH STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11349,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,446000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K ANNIGAPURAM 1ST STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11350,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,425000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K ANNIGAPURAM 2ND STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11351,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,261000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT DECASTER ROAD 1 ST STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11352,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,261000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT DECASTER ROAD 2 ND STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11353,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1486000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT THIRU VI KA NAGAR 1 ST STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11354,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,2022000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT THIRU VI KA NAGAR 2 ND STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11355,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,2784000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT THIRU VI KA NAGAR 3RD STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11356,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1144000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT THIRU VI KA NAGAR 2ND EXTENSION STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11357,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1516000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SATHIYA VANI MUTHU NAGAR MAIN ROAD IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11358,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1210000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT THIRU VI KA NAGAR MAIN ROAD IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11360,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1486000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT DOSS NAGAR MAIN ROAD IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11361,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,225000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT NEW THIRU VI KA NAGAR 1ST STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11362,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,225000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT NEW THIRU VI KA NAGAR 2 ND STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11363,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,188000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT NEW THIRU VI KA NAGAR 3RD STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11367,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,335000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE ATM.S.MUTHU NAGAR 1 ST STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11368,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,668000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE ATM.S.MUTHU NAGAR 2ND STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11369,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,485000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT M.S.MUTHU NAGAR 3RD STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11370,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,610000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KASTHURIIBAI COLONY B BLOCK 1 ST STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11371,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1002000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT M.S MUTHU NAGAR 1ST CROSS STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11372,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,535000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT M.S MUTHU NAGAR 2ND CROSS STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11373,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,2175000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT NEW THIRU VI KA NAGAR MAIN STREET IN DN-72, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/9522,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,187400,"DE-SILTING OF STORM WATER DRAIN AT V.O.C. NAGAR, SAMY DESIGANANDHASALAI, DECOSTER ROAD, HARNESS SADAL FACTORY ROAD, AND VARIOUS STREETS IN DN-72, UNIT-17, ZONE-06",Own Sources,6,2018-19,2019-20 NF/2018-19/9524,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,1440400,"REPAIR WORKS TO STORM WATER DRAIN AT SAMY DASIGANANDHASALAI, SASTHIRINAGAR, KANNIGAPURAM AND VARIOUS STREETS IN DN.72, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/9706,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,3154000,"LAYING CEMENT CONCRETE ROAD M30 AT Decaster Road IN DN-72, U-17, Z-6.",MLACDS,6,2018-19,2019-20 NF/2018-19/9707,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,1689000,"LAYING CEMENT CONCRETE ROAD M30 AT Powder Mills Road 1st Street IN DN-72, U-17, Z-6.",MLACDS,6,2018-19,2020-21 NF/2018-19/9708,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,799000,"LAYING CEMENT CONCRETE ROAD M30 AT Powder Mills Road 2nd Street IN DN-72, U-17, Z-6.",MLACDS,6,2018-19,2019-20 Q/2018-19/7189,Buildings,Completed,Q-Solid Waste Management,72,996000,"Proposed construction of Compound wall at Southern side of Bio-methanation plant inside Pullianthope Slaughter house in Dn-72, Z-6",Own Sources,6,2018-19,2018-19 Q/2018-19/7262,Buildings,Completed,Q-Solid Waste Management,72,997000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT WESTERN SIDE OF PULIANTHOPE BIO-DEGRADABLE PLANT IN DN-72,Z-6",Own Sources,6,2018-19,2018-19 Q/2018-19/7311,Buildings,Completed,Q-Solid Waste Management,72,884000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT NORTHERN SIDE OF PULIANTHOPE BIO-DEGRADABLE PLANT IN DN-72,Z-6",Own Sources,6,2018-19,2019-20 Q/2018-19/7313,Buildings,Completed,Q-Solid Waste Management,72,748000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT EASTERN SIDE OF PULIANTHOPE BIO-DEGRADABLE PLANT IN DN-72,Z-6",Own Sources,6,2018-19,2019-20 B/2018-19/3229,Electrical,Completed,B-Buildings,73,3960000,"IMPROVEMENT WORKS (COMPOUND WALL, TOILET AND WATER SUPPLY ARRANGEMENTS) TO THE EXISTING UCHC BUILDING AT THIRUVENKADASAMY STREET, PULIANTHOPE IN DN - 73,Z-6",Own Sources,6,2018-19,2020-21 BR/2018-19/16082,Roads,Completed,BR-Bus Route Roads,73,1020000,Attending patch work at strahans road approach near tower clock in Zone-6,Own Sources,6,2018-19,2018-19 BR/2018-19/6849,Footpath,Completed,BR-Bus Route Roads,73,1350000,"Footpath Repair Works at Dr.Ambedkar College Roadin Dn-73, Zone-VI",Grants,6,2018-19,2019-20 BR/2018-19/6850,Footpath,Completed,BR-Bus Route Roads,73,1290000,"Footpath Repair Works at Cooks Road in Dn-73, Zone-VI",Grants,6,2018-19,2019-20 D/2018-19/14933,Storm Water Drain,Completed,D-Storm Water Drains,73,69950000,"Construction of Storm Water Drain of size 2500x2500mm along Cooks road from the junction of Stephension road to junction of Konnur high road disposal at OtteriNullah in Dn-73,Zone -VI,Package - 13.",SMART CITY - SWD,6,2018-19,2020-21 L/2018-19/4284,Electrical,Completed,L-Electrical,73,2409400,Supply and provision of 24 nos of 40w solar photo voltaic LED Lamps with lamp post at periyar nagar housing board and sourrounding areas in dn 73 zone 6,MLACDS,6,2018-19,2020-21 L/2018-19/4944,Electrical,Completed,L-Electrical,73,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS,New farrance road in 73, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4945,Electrical,Completed,L-Electrical,73,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS,Strahans Road in 76, Zone- VI.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4947,Electrical,Completed,L-Electrical,73,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP,New farrance road in Div73, Zone- VI.",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4966,Electrical,Completed,L-Electrical,73,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community hall New ferrance road in dn73, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4967,Electrical,Completed,L-Electrical,73,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health post cookes road in dn73, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4982,Electrical,Completed,L-Electrical,73,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS Cookes road in Dn73, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/11017,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1130000,"RELAYING OF ROAD BY USING BC 40MM THICK AT MANNERSAMY STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11019,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,863000,"RELAYING OF ROAD BY USING BC 40MM THICK AT KUTTY THAMBURAN STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11020,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,820000,"RELAYING OF ROAD BY USING BC 40MM THICK AT BOLU (NAIKEN ) STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11021,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,740000,"RELAYING OF ROAD BY USING BC 40MM THICK AT GOVINDA SINGH STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11022,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1500000,"RELAYING OF ROAD BY USING BC 40MM THICK PARTHASARATHY STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11026,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,920000,"RELAYING OF ROAD BY USING BC 40MM THICK AT THIRU VI KA STREET IN DN-75, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11308,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,254000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT GOVINDHA SINGH LANE IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11311,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,526000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PADISOPURAM LANE IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11314,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,373000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SHEIK MOHIDEEN SUBEDHAR LANE IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11315,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,282000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KANAGAMMAL LANE IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11316,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,427000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT ALEXANDER LANE IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11317,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,318000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT ALEXANDER CROSS STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11318,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,454000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT VALLI HUSSAIN STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11319,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1270000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT NACHARMMAL STREET IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11320,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,570000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PENSIONERS MAIN LANE IN DN-73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/12297,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,274000,"Re-Construction of Exisiting Damaged Compound wall in Chennai Primary School at New Ferrance road in Dn-73, Unit-17, Zone -06",Own Sources,6,2018-19,2019-20 NF/2018-19/13115,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,2460000,"Repairs and Improvements to the Existing EOC hospital in Thiruvenkdasamy street at Dn-73.Unit-17,Zone-06",Own Sources,6,2018-19,2019-20 NF/2018-19/13234,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,2000000,"NEW CONSTRUCTION OF ICDS AT OLD VALAIMA NAGAR IN DN-73, UNIT-17, ZONE-06.",MLACDS,6,2018-19,2019-20 NF/2018-19/16466,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,470000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT GANDHI NAGAR IN DN.73, UNIT-17, ZONE- 6",Own Sources,6,2018-19,2019-20 NF/2018-19/1884,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,267000,"IMPROVEMENTS TO THE EXISTING CHENNAI PRIMARY SCHOOL AT THIRUVENGADASAMY STREET IN DIVISION-73,UNIT-17,ZONE-6",Own Sources,6,2018-19,2018-19 NF/2018-19/1892,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,1870000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL TOILET BLOCK AT AMMAIAMMAL STREET IN DIVISION-73,UNIT-17,ZONE-6",Own Sources,6,2018-19,2018-19 NF/2018-19/1979,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,414000,"Maintenance of Wardiya Park For One Year at New Ferrance Road in Pattalam Dn-73,Unit-17,Zone -06",Own Sources,6,2018-19,2020-21 NF/2018-19/3798,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,80000,"Repairs to BIO GAS Plant at New ferrance road in Division-73,Unit-17,Zone-6",Own Sources,6,2018-19,2019-20 NF/2018-19/8885,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,35000,"Supplying and Fixing of Name Board to Urban Primary Health Center Located at Wadia Health Post at cooks road and Diagnostic Laboratory at Perambur high road (North) in Dn-70,73 of Un-16 and 17 , Zn-6",Own Sources,6,2018-19,2018-19 NF/2018-19/9523,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,789400,"DE-SILTING OF STORM WATER DRAIN AT AMMAYAMMAL STREET, NARAYANASAMY STREET, MANNAR SAMY STREET, PARTHASARATHY STREET AND VARIOUS STREETS IN DIVISION-73, UNIT-17, ZONE-06",Own Sources,6,2018-19,2019-20 NF/2018-19/9527,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,1103400,"REPAIR WORKS TO STORM WATER DRAIN AT AMMAYAMMAL STREET, LAL SINGH STREET, NARAYANA MESTHIRI STREET, AND VARIOUS STREETS IN DIVISION -73, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 BR/2018-19/0964,Roads,Completed,BR-Bus Route Roads,74,2461000,"Traffic Improvement Works at Various Bus Route Roads in Zone - III, VIII, IX & X",Own Sources,6,2018-19,2019-20 BR/2018-19/6527,Footpath,Completed,BR-Bus Route Roads,74,19478000,"Forming Footpath at Medavakkam Tank Road in Dn-74, Zone-VI",Grants,6,2018-19,2019-20 BR/2018-19/6542,Footpath,Completed,BR-Bus Route Roads,74,12556000,"Forming Footpath at P.S.Sivasamy Salai (From the jn of Musri Subramani Salai to Royapettah High Road) in Dn-123, Zone-IX",Grants,6,2018-19,2020-21 BR/2018-19/7345,Roads,Completed,BR-Bus Route Roads,74,39000,Roadcut restoration made by CMWSSB at Medavakkam tank road in zone-6 against challan no:BR/2018-19/0011889.,Deposit Works,6,2018-19,2019-20 BR/2018-19/7519,Roads,Completed,BR-Bus Route Roads,74,19700,Restoration of road cut made by CMWSSB at Medavakkam Tank Road in zone-6 against challan no:BR/2017-18/0033918,Deposit Works,6,2018-19,2019-20 D/2018-19/8717,Storm Water Drain,Completed,D-Storm Water Drains,74,32220000,"Construction of Storm Water Drain of size 900 X 900 mm along Tank bund road, Subbrayan 4 th street and Sandiyappan street in Dn - 74, Zone - VI",Grants,6,2018-19,2020-21 D/2018-19/8722,Storm Water Drain,Completed,D-Storm Water Drains,74,26450000,"Construction of Storm Water Drain of size 900 X 900 mm size along Chanadrayogi Samadhi street and Krishnadoss street in Dn 74, Zone- VI",Grants,6,2018-19,2020-21 D/2018-19/8723,Storm Water Drain,Completed,D-Storm Water Drains,74,42020000,"Dismanlting of existing Dilapiated storm water drain and Construction of storm water Twin Drain of size 3000x2500mm along Konnur High Road from Junction of Anderson road to Otteri Nullah in Dn- 74, Zone-VI.(Chainage 0 M to Chainage 300 M)",Grants,6,2018-19,2020-21 D/2018-19/8725,Storm Water Drain,Completed,D-Storm Water Drains,74,42020000,"Dismanlting of existing Dilapiated storm water drain and Construction of storm water Twin Drain of size 3000x2500mm along Konnur High Road from Junction of Anderson road to Otteri Nullah in Dn- 74, Zone-VI.(Chainage 300 M to Chainage 600 M)",Grants,6,2018-19,2020-21 D/2018-19/8726,Storm Water Drain,Completed,D-Storm Water Drains,74,42020000,"Dismanlting of existing Dilapiated storm water drain and Construction of storm water Twin Drain of size 3000x2500mm along Konnur High Road from Junction of Anderson road to Otteri Nullah in Dn- 74, Zone-VI.(Chainage 600 M to Chainage 900 M)",Grants,6,2018-19,2019-20 D/2018-19/8729,Storm Water Drain,Completed,D-Storm Water Drains,74,42020000,"Dismanlting of existing Dilapiated storm water drain and Construction of storm water Twin Drain of size 3000x2500mm along Konnur High Road from Junction of Anderson road to Otteri Nullah in Dn- 74, Zone-VI.(Chainage 900 M to Chainage 1200M)",Grants,6,2018-19,2020-21 L/2018-19/0842,Electrical,Completed,L-Electrical,74,922600,"Supply and replacement of 1886 mtrs of damaged 2x25 sq.mm UG Cable at chronicle faulty locations at cement concrete rod and Block tapped road in Sandiappan street,Subbarayan Street,Medavakkam 2nd street and Various locations in div 75 zone-VI.",Own Sources,6,2018-19,2018-19 L/2018-19/3420,Electrical,Completed,L-Electrical,74,177800,"Supply and Provision of 4nos of 6mtrs lamp post having 1mtr single straight bracket with 4nos of 40-50w LED Fitting and laying of 137mtrs of 2x16sq.mm UG Cable at SVM Nagar playfield area in div.74,Z-VI.",Own Sources,6,2018-19,2018-19 L/2018-19/4963,Electrical,Completed,L-Electrical,74,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Chinnababu street in dn74 , Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4964,Electrical,Completed,L-Electrical,74,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary suburayan 2nd street in dn74, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4965,Electrical,Completed,L-Electrical,74,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS suburayan 1st street in dn74, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4981,Electrical,Completed,L-Electrical,74,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS Chinnababu street in Dn74, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/10725,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,570000,"CONSTRUCTION OF TOILET IN CHENNAI PRIMARY SCHOOL AT SUBURAYAN FIRST STREET IN DIVISION-74, UNIT-17, ZONE-6.",MLACDS,6,2018-19,2019-20 NF/2018-19/10997,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1460000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SECRETARIAT COLONY 1ST STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/10998,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,350000,"RELAYING OF ROAD BY USING BC 40MM THICK AT REDDY COLON STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/10999,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,960000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SANKARA BAKTHAN STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11000,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,280000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SAMY BAKTHAN LANE IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11001,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,940000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SAMY BAKTHAN STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11002,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,290000,"RELAYING OF ROAD BY USING BC 40MM THICK AT CHENGALVARAYAN (PART) STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11003,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,920000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SUBURAYAN 1ST STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11004,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,450000,"RELAYING OF ROAD BY USING BC 40MM THICK AT BARRACKA 2ND STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11005,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,750000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SUBURAYAN 2ND STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11006,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1060000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SANDHIYAPPAN MAIN STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11007,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,1350000,"RELAYING OF ROAD BY USING BC 40MM THICK AT BARRACKA ROAD IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11008,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,140000,"RELAYING OF ROAD BY USING BC 40MM THICK AT BARRACKA ROAD 1 ST STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11009,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,207000,"RELAYING OF ROAD BY USING BC 40MM THICK AT VARATHAMMAL GARDEN 3RD STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11010,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,411000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SUBURAYAN MAIN STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11012,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,210000,"RELAYING OF ROAD BY USING BC 40MM THICK AT OTTHAVADAI STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11065,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,91000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SANDHIYAPPAN 4TH STREET ( PART ) IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/12298,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,89000,"Repairs and Improvements to NNMP shed in Chennai Primary School Campus at Thiruvenkadasamy street Dn -73, Unit-17, Zone-06",Own Sources,6,2018-19,2020-21 NF/2018-19/9507,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,465400,"REPAIR WORKS TO STORM WATER DRAIN AT MEDAVAKKAM TANK ROAD, NALLAIYAH STREET, A.K SAMY NAGAR 9TH STREET, SECRETARIAT COLONY 4TH STRRT AND VARIOUS STREETS IN DN.74, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/9511,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,530400,"DE-SILTING OF STORM WATER DRAIN AT SECRETARIAT COLONY 1,2,3,4,6,7,9 STREETS , A.K.SAMY NAGAR 1& 9 STREETS, SUBURAYAN 1,2,3,4,5, STREETS, AND VARIOUS STREETS IN DN.74, UNIT-17, ZONE - 6",Own Sources,6,2018-19,2019-20 BR/2018-19/7350,Roads,Completed,BR-Bus Route Roads,75,15000,Restoration of road cut made by CMWSSB at Bricklin Road in zone-6 against challan No. BR/2017-18/0033523.,Deposit Works,6,2018-19,2019-20 BR/2018-19/7516,Roads,Completed,BR-Bus Route Roads,75,19000,Restoration of road cut made by CMWSSB at Bricklin road in zone-6 against challan no:BR/2017-18/0030963.,Deposit Works,6,2018-19,2019-20 BR/2018-19/7523,Roads,Completed,BR-Bus Route Roads,75,36500,Restoration of road cut made by CMWSSB at Bricklin road in zone-6.,Deposit Works,6,2018-19,2019-20 L/2018-19/0816,Electrical,Completed,L-Electrical,75,896000,"Supply and replacement of 1836 mtrs of damaged 2x25 sq.mm UG Cable at chronicle faulty locations at cement concrete rod and Block tapped road in S.S.Puram A Block,S.S.Puram B Block,Vengadathiri street and Various locations in div 75 zone-VI.",Own Sources,6,2018-19,2018-19 L/2018-19/4961,Electrical,Completed,L-Electrical,75,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Vengadammal samathi street in dn75 , Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4962,Electrical,Completed,L-Electrical,75,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS Chellappa street in dn75 , Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 L/2018-19/4980,Electrical,Completed,L-Electrical,75,386190,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS Padavattamman koil street in Dn75, Zone- VI",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/11024,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,380000,"RELAYING OF ROAD BY USING BC 40MM THICK AT S.S.PURAM B BLOCK 5TH STREET IN DN-75, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11025,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,4750000,"RELAYING OF ROAD BY USING BC 40MM THICK AT CHELLAPPA STREET IN DN-75, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11027,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,840000,"RELAYING OF ROAD BY USING BC 40MM THICK ATS.S.PURAM A BLOCK 1ST STREET IN DN-75, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11321,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,635000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT NARAYANA MAISTRY STREET IN DN.75, UNIT-17,ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11322,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,233000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT HANUMATHARAYAN KOIL STREET IN DN.75, UNIT-17,ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/8682,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,2150000,"ADDITIONAL CONSTRUCTION IN FIRST FLOOR AT MULTI PURPOSE HALL (Under M.P.Fund) AT S.S.PURAM B BLOCK MAIN STREET IN DN-76,UNIT-17,ZONE-06",MPLADS,6,2018-19,2020-21 NF/2018-19/8972,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,325000,"CONSTRUCTION OF SUMP AT CHENNAI MIDDLE SCHOOL IN VENKATTAMMAL SAMATHI STREET ( UNDER MLA FUND)DN-76,UNIT-17,ZONE-06",MLACDS,6,2018-19,2019-20 NF/2018-19/9283,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,357000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2018-19,2019-20 NF/2018-19/9284,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,541000,"MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT VENKATTAMAL SAMATHI ST, THIR-VI-KA STREET ,vALLUVAN STREET AND VARIOUS STREETS IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2018-19,2019-20 BR/2018-19/0511,Roads,Completed,BR-Bus Route Roads,76,2120000,Restoration of Road cut at Choolai High Road made by TANGEDCO - )From AA Road to Sydams road) in Division -76 Zone - 6,Deposit Works,6,2018-19,2018-19 BR/2018-19/0585,Roads,Completed,BR-Bus Route Roads,76,2426000,"Traffic Improvement Works at Various Bus Route Roads in Zone - I ,II , V & IX",Own Sources,6,2018-19,2020-21 BR/2018-19/6851,Footpath,Completed,BR-Bus Route Roads,76,1199000,"Footpath Repair Works at Strahans Road in Dn-76, Zone-VI",Grants,6,2018-19,2019-20 BR/2018-19/7518,Roads,Completed,BR-Bus Route Roads,76,23500,Restoration of road cut made by CMWSSB at Perambur Barracks road in zone-6 against challan no:BR/2018-19/0006742,Deposit Works,6,2018-19,2019-20 L/2018-19/0846,Electrical,Completed,L-Electrical,76,893500,"Supply and replacement of 1821 mtrs of damaged 2x25 sq.mm UG Cable at chronicle faulty locations at cement concrete road and Block tapped road in K.M.Garden,Govindapuram,Old Housing Board and Various locations in div 76 zone-VI.",Own Sources,6,2018-19,2018-19 L/2018-19/4960,Electrical,Completed,L-Electrical,76,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary Satchithanatham street in 76, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/11028,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,570000,"RELAYING OF ROAD BY USING BC 40MM THICK AT C.S.NAGAR PARK STREET IN DN-76, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11029,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,1360000,"RELAYING OF ROAD BY USING BC 40MM THICK AT KANDHASWAMY KOIL STREET IN DN-76, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11030,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,890000,"RELAYING OF ROAD BY USING BC 40MM THICK AT VENKATESAN ( NAIKEN ) STREET IN DN-76, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11323,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,235004,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT BABU STREET IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11324,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,101000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT BABU LANE IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11325,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,804000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT APPASAMY STREET IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11327,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,218000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT SACHIDANANDAM LANE IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11328,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,180000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT DEVARAJ LANE IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11329,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,313000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT CHINNATHAMBI STREET IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11330,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,638000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT PARASURAMAN STREET IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/12505,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,300000,"PROVIDING WATER SUPPLY ARRANGEMENT TO THE DOBICANA AT SACHIDANANDAM STREET IN DN-76,UNIT-17,ZONE-06",MLACDS,6,2018-19,2019-20 NF/2018-19/1450,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,1299000,"Maintenance of C.S. park for One Year at C.S.Nager Park street Pattalam Dn-76,UNit-17,zone-06",Own Sources,6,2018-19,2020-21 NF/2018-19/1451,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,200000,"Maintenance of Kalaignar Karunanidhi park for One Year Dr.Amedkar College road in Pattlam Dn-76,Unit-17,Zone-06",Own Sources,6,2018-19,2020-21 NF/2018-19/1452,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,563000,"Maintenance of Selvapathy.Park For One Year at Strahans road in Pattalam Dn-76,Unit-17,Zone -06",Own Sources,6,2018-19,2020-21 NF/2018-19/1454,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,327000,"Maintenance of Bakthavatchalam.Park For One Year at Strahans road in Pattalam Dn-76,Unit-17,Zone -06",Own Sources,6,2018-19,2020-21 NF/2018-19/5308,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,2330000,"LAYING OF CEMENT CONCRETE ROAD RMC M30 AT K.M.GARDEN FIRST STREET PART, CORPORATION TENEMENTS STREETS (UNDER MLA FUND ) IN DN-76,UNIT-17,ZONE-06",MLACDS,6,2018-19,2019-20 NF/2018-19/5310,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,2840000,"LAYING OF CEMENT CONCRETE ROAD RMC M30 AT K.M.GARDEN FIRST STREET (PART),2ND,3RD,4TH AND 5TH STREET (UNDER MLA FUND ) IN DN-76,UNIT-17,ZONE-06",MLACDS,6,2018-19,2019-20 NF/2018-19/5323,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,2850000,"LAYING OF CEMENT CONCRETE ROAD RMC M30 AT K.M.GARDEN 6TH STREET AND 8 TH STREET(UNDER MLA FUND ) IN DN-76,UNIT-17,ZONE-06",MLACDS,6,2018-19,2019-20 NF/2018-19/5324,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,1770000,"LAYING OF CEMENT CONCRETE ROAD RMC M30 AT K.M.GARDEN 7TH ,9TH,11TH,13TH STREET AND 14TH STREET (UNDER MLA FUND ) IN DN-76,UNIT-17,ZONE-06",MLACDS,6,2018-19,2019-20 NF/2018-19/8571,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,392000,"MAINTENANCE AND OPERATION OF WATER TREATMENT PLANT (AMMA KUDINEER) AT CHENNAI HIGH SCHOOL AT STRAHANS ROAD IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2018-19,2020-21 NF/2018-19/8986,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,325000,"CONSTRUCTION OF SUMP IN CHENNAI HIGH SCHOOL AT STRAHANS ROAD IN DN-76,UNIT-17,ZONE-06",MLACDS,6,2018-19,2019-20 NF/2018-19/8987,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,590000,"Erection of 250 LPH Ro Plant with Pre - Filteration in Chennai ( Urudhu) Middle School (UNDER MLA FUND) at Kandha samy koil street in Dn-76,unit-17,Zone-06",MLACDS,6,2018-19,2019-20 NF/2018-19/9277,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,361000,"DE-SILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2018-19,2019-20 NF/2018-19/9279,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,833000,"MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT PERAMBUR BARRACKS ROAD,STRAHANS ROAD AND VARIOUS STREET DN-76,UNIT-17,ZONE-06",Own Sources,6,2018-19,2019-20 B/2018-19/5157,Buildings,Completed,B-Buildings,77,15655498,"Proposed Construction of UPHC Building at Kesava Pillai Park, Pulianthope in Div-77, Zone-6",Grants,6,2018-19,2020-21 BR/2018-19/7544,Roads,Completed,BR-Bus Route Roads,77,19500,RESTORATION OF ROAD CUT RESTORTION MADE BY CMWSSB IN ZONE-6 AGAINST CHALLAN NO:BR/2017-18/0028440,Deposit Works,6,2018-19,2019-20 NF/2018-19/0543,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,918000,"Maintenance of Amma .Park For One Year at Elephant gate road in Pulianthope Dn-77,Unit-17,Zone -06",Own Sources,6,2018-19,2020-21 NF/2018-19/0678,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,311000,"Maintenance of New TPF.Park For One Year at Elephant gate road in Pulianthope Dn-77,Unit-17,Zone -06",Own Sources,6,2018-19,2020-21 NF/2018-19/10656,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,1893000,"MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT BOGIPALAYAM MAIN ROAD, SUNDARAPURAM MAIN ROAD, BASIN ELEPHANT GATE ROAD, OIL MILL STREET AND AT VARIOUS STREET DN-77,UNIT-17,ZONE-06",Own Sources,6,2018-19,2019-20 NF/2018-19/11031,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,767000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SUNDHARAPURAM 1 ST MAIN ROAD IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11032,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,832000,"RELAYING OF ROAD BY USING BC 40MM THICK AT THULASI ( NAIKEN ) STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11033,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,520000,"RELAYING OF ROAD BY USING BC 40MM THICK AT SANDHIYAPPA STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11376,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,168000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P PARK 7TH & 8TH BLOCK BACK SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11377,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,93000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT RAJA THOTTAM 3RD STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11378,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,304000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 4 TH CROSS STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11379,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,326000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT GURU SAMY NAGAR MAIN STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11381,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,132000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KNM CORPORATION 3RD LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11382,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,212000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P.PARK. 9 TH BLOCK FRONT SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11383,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,79000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT RAJA THOTTAM CROSS STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11384,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,118000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KNM 2ND LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11385,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,178000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT CORPORATION SMALL LANE (THATANGULAM) IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11386,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,681000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 2 ND STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11387,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,216000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 5TH STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11388,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,136000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PAYALA PACHAYAPPA STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11389,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,182000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT URUDHU SCHOOL OPPOSITE (BOGIPALAYAM CORPORATION LANE) STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11390,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,937000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 3RD STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11391,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,335000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P.PARK. 14 TH BLOCK FRONT SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11392,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,93000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT RAJA THOTTAM 2 ND STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11393,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,281000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 2ND CROSS STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11394,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,876000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 1ST STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11395,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,118000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KNM 1ST LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11396,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,346000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT P.K.COLONY 5TH BLOCK IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11397,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,354000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 5 TH CROSS STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11398,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,109000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KNM CORPORATION 2ND LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11399,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,259000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT RAJA THOTTAM CROSS STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11400,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,597000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT GOVINDARAJ STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11402,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,320000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT RAJA THOTTAM 1 ST STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11403,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,411000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT P.K.COLONY 19TH BLOCK IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11405,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,449000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT PULIANTHOPE 3RD CROSS STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11406,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,82000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KNM 3RD LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11434,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,320000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P PARK 9TH & 10TH BLOCK BACK SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11435,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,284000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P PARK 10TH & 11TH BLOCK FRONT SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11436,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,334000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P PARK 11TH & 12 TH BLOCK BACK SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11449,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,195000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P PARK 13 TH BLOCK FRONT SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11450,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,309000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P PARK 13 TH & 14 TH BLOCK BACK SIDE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11451,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1056000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT K.P PARK 1ST & 12TH BLOCK PASSAGE ROAD IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11452,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,213000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KANAGARAYA THOTTAM IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11453,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,212000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KANAGARAYA THOTTAM 1ST LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11454,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,343000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KANAGARAYA THOTTAM 2 ND LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11455,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,271000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT KANAGARAYA THOTTAM 3RD LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11456,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,822000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT COMMON STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11458,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,704000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SUNDHARAPURAM 2 ND STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11459,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,652000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SUNDHARAPURAM 3 RD STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11460,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,120000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SUNDHARAPURAM 4TH STREET IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11461,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,436000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SUNDHARAPURAM 1ST LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11462,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,468000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SUNDHARAPURAM 2 ND LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2020-21 NF/2018-19/11463,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,235000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT SUNDHARAPURAM 3 RD LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11464,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,224000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT CORPORATION SMALL LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11465,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,454000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT CORPORATION SMALL 1 ST LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11466,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,508000,"RELAYING CEMENT CONCRETE ROAD M40 GRADE CONCRETE AT CORPORATION SMALL 2ND LANE IN DN-77, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/13705,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,1512000,"Improvements to Dog Shelter (Animal Birth Control centre) at Basin Elephant Gate road, Dn 77, U-17, Zone 6.",Own Sources,6,2018-19,2019-20 NF/2018-19/14797,Electrical,Completed,NF-THIRU-VI-KA NAGAR,77,355000,ELECTRIFICATION WORK AT LETHAL CHAMBER IN DN 77 BASINELEPHANTGATE ROAD ZONE6,Own Sources,6,2018-19,2019-20 NF/2018-19/16406,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,56000,"REPAIRS AND GAP FILLING TO CENTER MEDIAN AT DEMELLOUS ROAD IN DN-77, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/16407,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,112000,"REPAIRS AND IMPROVEMENTS TO CENTER MEDIAN AT DEMELLOUS ROAD IN DN-77, U-17, Z-06",Own Sources,6,2018-19,2019-20 NF/2018-19/16411,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,45000,"REPAIRS AND IMPROVEMENTS TO CENTER MEDIAN AT ELEPHANT GATE ROAD IN DN-77, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/16435,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,34000,"REPAIRS AND GAP FILLING TO CENTER MEDIAN AT ELEPHANT GATE ROAD IN DN-77, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/2586,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,860000,"Construction of Multi Purpose Hall-Additional Room at Old Slaughter House Road ( MLA FUND-2017-18) in Division 77, Unit 17, Zone 6.",MLACDS,6,2018-19,2018-19 NF/2018-19/6999,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,1603000,"Construction of Multi Purpose Hall at Mothila Street in Division 77, Unit 17, Zone 6.",MLACDS,6,2018-19,2018-19 NF/2018-19/8114,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,657000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREET IN DN-77,UNIT-17,ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/9339,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,768000,"MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT MOTHILAL STREET , ANSARI STREET AND AT VARIOUS STREET DN-77,UNIT-17,ZONE-06",Own Sources,6,2018-19,2019-20 BR/2018-19/6535,Roads,Completed,BR-Bus Route Roads,78,87000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DN.78, ZONE-06. (57/0741/2017-18) PACKAGE-11.",Deposit Works,6,2018-19,2018-19 BR/2018-19/7522,Roads,Completed,BR-Bus Route Roads,78,48500,Restoration of road cut made by CMWSSB Choolai high road in zone-6 against challan no:BR/2017-18/0033470.,Deposit Works,6,2018-19,2019-20 D/2018-19/2897,Storm Water Drain,Completed,D-Storm Water Drains,78,1140000,"Rejuvenation and other improvements to the temple tank at Kandasamy and Aathimottaiamman Koil,Kuyapettai including construction of RWH well under Sustainable Water Secruity Mission in Dn - 78,Zone - 6.",SMART CITY - SWD,6,2018-19,2019-20 L/2018-19/4959,Electrical,Completed,L-Electrical,78,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dn office Manickam street in dn78, Zone- VI .",SMART CITY - ELECTRICAL,6,2018-19,2019-20 NF/2018-19/11034,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,540000,"RELAYING OF ROAD BY USING BC 40MM THICK AT CHINNA THAMMBI ( NAIKEN ) STREET IN DN-78, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11035,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1300000,"RELAYING OF ROAD BY USING BC 40MM THICK AT RAGHAVA STREET IN DN-78, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11036,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,330000,"RELAYING OF ROAD BY USING BC 40MM THICK AT KURAVAN KULAM MAIN STREET 1 IN DN-78, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11037,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,414000,"RELAYING OF ROAD BY USING BC 40MM THICK AT KURAVAN KULAM MAIN STREET 2 IN DN-78, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11038,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,380000,"RELAYING OF ROAD BY USING BC 40MM THICK AT VENKATESAN STREET IN DN-78, UNIT-17, ZONE-06.",Own Sources,6,2018-19,2019-20 NF/2018-19/11307,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,955000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT KANDASWAMY STREET (PART) IN DN.78, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11309,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1291000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT NEW MANICKAM STREET IN DN.78, UNIT-17, ZONE - 6",Own Sources,6,2018-19,2019-20 NF/2018-19/11310,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,369000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT V V KOIL STREET IN DN.78, UNIT-17,ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11312,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,532000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT YEMI STREET IN DN.78, UNIT-17,ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/11313,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1008000,"PROPOSED RELAYING OF CEMENT CONCRETE ROAD AT ANGALAMMAN KOIL STREET IN DN.78, UNIT-17,ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/16267,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,34000,"REPAIRS AND GAP FILLING TO CENTER MEDIAN AT TANA STREET IN DN-78, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/16269,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,84000,"Plantation of Plants to Centre Median at Sydenhams Road in Dn-78, Unit-17, Zone-06",Own Sources,6,2018-19,2019-20 NF/2018-19/16271,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,56000,"Improvements and Repairs to Centre Median at Sydenhams Road in Dn-78, Unit-17, Zone-06",Own Sources,6,2018-19,2019-20 NF/2018-19/9285,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,505400,"REPAIR WORKS TO STORM WATER DRAIN AT SYDENHAMS ROAD AND ANGALAMMAN KOIL STREET AND VARIOUS STREETS IN DN.78, UNIT-17, ZONE-6",Own Sources,6,2018-19,2019-20 NF/2018-19/9288,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,388400,"DE-SILTING OF STORM WATER DRAIN AT PERAMBUR BARRACKS ROAD, TANA STREET, SYDENHAMS ROAD, V V KOIL STREET, ASTAPUJAM ROAD, VADAMALAI STREET, RANGAIAH STREET, ANGALAMMAN KOIL STREET, MOOKU STREET AND NEW MANICKAM STREET AND VARIOUS STREETS IN DN.78, UNIT-17, ZONE - 6",Own Sources,6,2018-19,2019-20 BR/2018-19/15697,Road Cut,Completed,BR-Bus Route Roads,79,1000000,Restoration of OFC road cut made by Reliance at various IRR roads in Division-79 Unit-18 Zone-7 (Deposit Code-57/0053/2018-19),Deposit Works,7,2018-19,2019-20 L/2018-19/10938,Electrical,Completed,L-Electrical,79,199500,"Proposal for Fixing of 510 Nos of LED Fittings & Removal of 510 nos Sodium fittings At Various Locations In Div 79, 82 & 84 in Ramnagar & Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/10956,Electrical,Completed,L-Electrical,79,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ICDS, Othravadai St, Kattabomman St in Ward 79 Zone - VII . E.B Account Number : 433.002.1610",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6040,Electrical,Completed,L-Electrical,79,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ICDS, Kallikuppamm in Ward 82 Zone - VII . E.B Account Number : 441.004.3097",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6042,Electrical,Completed,L-Electrical,79,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma unavagam , Kattabomman street , Oragadam in Ward 79 Zone - VII . E.B Account Number : 433.002.1546",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6043,Electrical,Completed,L-Electrical,79,989100,"ESTIMATE for Supply, Installation, Testing & Commissioning of 13 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Hall, Gopalsamy Street in Ward 79 Zone - VII . E.B Account Number : 433.014.259",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6054,Electrical,Completed,L-Electrical,79,462400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post Oragadam in Ward 79 Zone - VII . E.B Account Number : 433.002.774",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6055,Electrical,Completed,L-Electrical,79,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ICDS, Kakkanji Street, Oragadam in Ward 79 Zone - VII . E.B Account Number : 433.005.778",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6056,Electrical,Completed,L-Electrical,79,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit Office, Bank Street in Ward 79 Zone - VII . E.B Account Number : 433.014.1026",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/9123,Electrical,Completed,L-Electrical,79,190600,"Proposal for raising of 20 nos of Kiosk Pillar Boxes from the Ground Level at various location in Division 79,82 in Zone VII",Own Sources,7,2018-19,2019-20 NG/2018-19/0379,Roads,Completed,NG-AMBATTUR,79,2030000,"FORMING AND LAYING OF BT SURFACE AT THIRUMURTHY STREET, IN DIVISION-79, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0380,Roads,Completed,NG-AMBATTUR,79,828000,"FORMING AND LAYING OF BT SURFACE AT VALARMATHI NAGAR CROSS STREET, IN DIVISION-79, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0381,Roads,Completed,NG-AMBATTUR,79,1450000,"FORMING AND LAYING OF BT SURFACE AT ANNA MAIN ROAD IN DIVISION-79, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0382,Roads,Completed,NG-AMBATTUR,79,1358000,"FORMING AND LAYING OF BT SURFACE AT DURAI SAMMY STREET IN DIVISION-79, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2020-21 NG/2018-19/0383,Roads,Completed,NG-AMBATTUR,79,4793000,"FORMING AND LAYING OF BT SURFACE AT MANALODAI MAIN ROAD IN DIVISION-79, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0391,Roads,Completed,NG-AMBATTUR,79,340000,"FORMING AND LAYING OF BT SURFACE AT ORAGADAM ROAD 1ST CROSS STREET IN DIVISION-81, UNIT-18, ZONE-VII (AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0395,Roads,Completed,NG-AMBATTUR,79,262000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SATHIYA STREET IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0396,Roads,Completed,NG-AMBATTUR,79,1150000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SEETHARAMAN STREET IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0398,Roads,Completed,NG-AMBATTUR,79,5380000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT ERIKARI SALAI IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2020-21 NG/2018-19/0400,Roads,Completed,NG-AMBATTUR,79,950000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT OM SAKTHI STREET IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/15632,Parks,Completed,NG-AMBATTUR,79,263000,"MAINTANANCE ESTIMATE FOR THE PARK AT CHILDRENS PARK IN PARK STREET IN LAKSHMIAMMAN NAGAR IN DIVISION-79, UNIT-18, ZONE-7",Own Sources,7,2018-19,2020-21 NG/2018-19/15633,Parks,Completed,NG-AMBATTUR,79,199000,"MAINTENANCE ESTIMATE FOR THE PARK LENIN NAGAR PARK IN DIVISION-79, UNIT-18, ZONE-VII.",Own Sources,7,2018-19,2020-21 NG/2018-19/15634,Parks,Completed,NG-AMBATTUR,79,205000,"Maintenance Estimate for the Park At Ram Nagar Park In Division-79, Unit-18, Zone-VII ( Ambattur )",Own Sources,7,2018-19,2020-21 NG/2018-19/15635,Parks,Completed,NG-AMBATTUR,79,210000,"Maintenance Estimate for the Park At Gandhi Nagar Park In Division-79, Unit-18, Zone-VII ( Ambattur )",Own Sources,7,2018-19,2020-21 NG/2018-19/15816,Roads,Completed,NG-AMBATTUR,79,210000,"Laying 80mm Thick Cement Concrete Paver Block Road at Anna Main Road 1st Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15817,Roads,Completed,NG-AMBATTUR,79,332000,"Laying 80mm Thick Cement Concrete Paver Block Road at Anna Main Road 2nd Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15818,Roads,Completed,NG-AMBATTUR,79,129000,"Laying 80mm Thick Cement Concrete Paver Block Road at Valarmathi Nagar Om Sakthi 1st Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15822,Roads,Completed,NG-AMBATTUR,79,151000,"Laying 80mm Thick Cement Concrete Paver Block Road at Valarmathi Nagar Om Sakthi 2nd Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15825,Roads,Completed,NG-AMBATTUR,79,765000,"Laying 80mm Thick Cement Concrete Paver Block Road at Valarmathi Nagar Abirami 5th Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15828,Roads,Completed,NG-AMBATTUR,79,198000,"Laying 80mm Thick Cement Concrete Paver Block Road at Annai Therasa Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15830,Roads,Completed,NG-AMBATTUR,79,192000,"Laying 80mm Thick Cement Concrete Paver Block Road at Venkateswara Nagar Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15831,Roads,Completed,NG-AMBATTUR,79,320000,"Laying 80mm Thick Cement Concrete Paver Block Road at Kalaivanar Cross Street in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15834,Roads,Completed,NG-AMBATTUR,79,139000,"Laying 80mm Thick Cement Concrete Paver Block Road at AKA Nagar Main Road Lane in Division-79, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/4798,Roads,Completed,NG-AMBATTUR,79,530000,"FORMING AND STRENGTHENING OF BT ROAD AT RAGAVENDRA 1ST STREET IN DN-79, U-18, ZONE-7",MLACDS,7,2018-19,2020-21 NG/2018-19/6714,Buildings,Completed,NG-AMBATTUR,79,270000,"IMPROVEMENT AND MAINTENANCE WORKS AT KATTABOMMAN STREET AMMA UNAVAGAM AND GANDHI MAIN ROAD AMMA UNAVAGAM IN DIV-79, UNIT-18, ZONE-VII.",Own Sources,7,2018-19,2020-21 NG/2018-19/7846,Storm Water Drain,Completed,NG-AMBATTUR,79,82000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-79, UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/7847,Storm Water Drain,Completed,NG-AMBATTUR,79,984000,"REPAIR AND MAINTENANCE OF SWD AND SIDE DRAINS AT PADMAVATHI SRINIVASA NAGAR MAIN ROAD DRAIN AND 10TH MAIN ROAD IN DIVISION-79,UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 BR/2018-19/15698,Road Cut,Completed,BR-Bus Route Roads,80,482000,Restoration of OFC road cut made by Reliance at various IRR roads in Division-80 Unit-18 Zone-7 (Deposit Code-57/0053/2018-19),Deposit Works,7,2018-19,2019-20 L/2018-19/10372,Electrical,Completed,L-Electrical,80,73300,"Proposal for raising of 7 nos of Kiosk Pillar Boxes from the Ground Level at various location in Division 80,91 in Zone VII",Own Sources,7,2018-19,2019-20 L/2018-19/10951,Electrical,Completed,L-Electrical,80,199500,"Fixing of 510 Nos of LED Fittings & Removal of 510 nos of Sodium fittings At Various Locations In Div 80, 91 and 88in Banu nagar Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/11128,Electrical,Completed,L-Electrical,80,395500,"Replacement of 20 Nos. of Completely damaged 63 AMP/3 phase Analogue single dial Automatic Street Lighting ON /OFF Controlling TIMER UNITS At Various Locations In Div. 80,81,86&91 in Banu nagar Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/13069,Electrical,Completed,L-Electrical,80,117000,"Proposal for fixing of 299 Nos of LED Fittings & Removal of 299 nos Sodium fittings At Various Locations In Div 80,81,86,89,90,91,&92 in Banu nagar Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/6045,Electrical,Completed,L-Electrical,80,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma unavazam,wast Banu nagar . Div -80 , Zone -VII / EB NO:433-006-1828",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6048,Electrical,Completed,L-Electrical,80,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital ,Chittu Oragadam Health Post KVK Swami Street . Div - 80, Zone -7 EB NO:041.003.891",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6052,Electrical,Completed,L-Electrical,80,311900,"Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office-80, pudur main road ambattur in Div. 80 Zone-VII. E.B No: 434.007.3492",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/0385,Roads,Completed,NG-AMBATTUR,80,525000,"FORMING AND LAYING OF BT SURFACE AT BANU NAGAR 16TH AVENUE IN DIVISION-80, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0386,Roads,Completed,NG-AMBATTUR,80,790000,"FORMING AND LAYING OF BT SURFACE AT BANU NAGAR 30TH EXTN IN DIVISION-80, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0387,Roads,Completed,NG-AMBATTUR,80,730000,"FORMING AND LAYING OF BT SURFACE AT BANU NAGAR 31ST EXTN IN DIVISION-80, UNIT-18, ZONE-VII(AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0390,Roads,Completed,NG-AMBATTUR,80,900000,"FORMING AND LAYING OF BT SURFACE AT THIRUTHANIGAI NAGAR 4TH CROSS STREET IN DIVISION-80, UNIT-18, ZONE-VII (AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0402,Roads,Completed,NG-AMBATTUR,80,930000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT 3RD MAIN ROAD BANU NAGAR IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0403,Roads,Completed,NG-AMBATTUR,80,358000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT GOVINDAN STREET WEST BANU NAGAR IN DIVISION -80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0404,Roads,Completed,NG-AMBATTUR,80,1590000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PATEL STREET IN DIVISION-80, UNIT-18, ZONE-7 (AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0405,Roads,Completed,NG-AMBATTUR,80,449000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT RAJASEKARAN STREET IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0406,Roads,Completed,NG-AMBATTUR,80,4100000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT ANNA SALAI IN DIVISION-80, UNIT-18, ZONE-7 (AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0407,Roads,Completed,NG-AMBATTUR,80,8500000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PUDHUR MAIN ROAD IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0408,Roads,Completed,NG-AMBATTUR,80,1980000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT ABIRAMIPURAM MAIN ROAD IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0409,Roads,Completed,NG-AMBATTUR,80,2400000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT THIRUMALAI PRIYA NAGAR MAIN ROAD IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0410,Roads,Completed,NG-AMBATTUR,80,890000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SABARI STREET IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/15162,Storm Water Drain,Completed,NG-AMBATTUR,80,1040000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT THANGAL ERI PARK IN DN 80, UNIT 18, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15163,Storm Water Drain,Completed,NG-AMBATTUR,80,189000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT BHARATHI NAGAR IN DN 80, UNIT 18, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15821,Roads,Completed,NG-AMBATTUR,80,166000,"Laying Paver Block Road at cpc 6th street, in Division-80, Unit-18, Zone-7.",MLACDS,7,2018-19,2019-20 NG/2018-19/16220,Buildings,Completed,NG-AMBATTUR,80,400000,"CONSTRUCTION OF TOILET BLOCK AT PANDIAN STREET IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",MLACDS,7,2018-19,2019-20 NG/2018-19/16221,Buildings,Completed,NG-AMBATTUR,80,600000,"CONSTRUCTION OF TOILET BLOCK AT THANGAL ERI PARK IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",MLACDS,7,2018-19,2020-21 NG/2018-19/16310,Culvert,Completed,NG-AMBATTUR,80,700000,"Construction of Culvert of size 900 X900 MM at kalanjar street, mgr street and prakasam street In Division 80 , Zone: 7",MLACDS,7,2018-19,2019-20 NG/2018-19/16365,Roads,Completed,NG-AMBATTUR,80,530000,"Laying Cement Concrete Paver Block Road at Vairakulam cross, Thirumalai priya nagar , Perumal I cross, Perumal 2nd cross, Perumal 3rd cross & Perumal 4th cross in Division-80, Unit-18, Zone-7",MLACDS,7,2018-19,2019-20 NG/2018-19/16370,Roads,Completed,NG-AMBATTUR,80,1640000,"LAYING OF CEMENT CONCRETE ROAD AT ANNAI THERESA STREET, NAGATHAMMAN KOIL 2ND STREET AND THIRUMALA PRIYA NAGAR 8TH STREET& Kamaraj street IN DIVISION:80, UNIT-18, ZONE-VII.",MLACDS,7,2018-19,2020-21 NG/2018-19/4887,Playfields,Completed,NG-AMBATTUR,80,325000,"IMPROVEMENT WORKS TO PLAY FIELD AT PANDIAN STREET IN DIVISION-80,UNIT-18,ZONE-7.",Own Sources,7,2018-19,2018-19 NG/2018-19/6877,Buildings,Completed,NG-AMBATTUR,80,295000,"IMPROVEMENT AND MAINTENANCE WORKS AT M.G.R STREET AMMA UNAVAGAM AND PUDHUR MAIN ROAD AMMA UNAVAGAM IN DIV-80, UNIT-18, ZONE-VII.",Own Sources,7,2018-19,2019-20 NG/2018-19/7907,Storm Water Drain,Completed,NG-AMBATTUR,80,259000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-80,UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/8448,Storm Water Drain,Completed,NG-AMBATTUR,80,1280000,"Repair work of SWD and Side Drains at Thangal eri, Parkasam karu Street, Rajasekaran Street, Subramaniyan Street and in Division-80, Unit-18, Zone-VII",Own Sources,7,2018-19,2019-20 BR/2018-19/16638,Roads,Completed,BR-Bus Route Roads,81,389000,Traffic Improvement works at various bus route roads in Zone-VII & IX,Own Sources,7,2018-19,2019-20 L/2018-19/6050,Electrical,Completed,L-Electrical,81,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital. South Park Street in Div. 81, Zone-VII. EB NO:031.010.1908",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6051,Electrical,Completed,L-Electrical,81,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division 81 office, South Parck Street in Div. 81 Zone-VII. EB NO:031.010.1208",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/0392,Roads,Completed,NG-AMBATTUR,81,495000,"FORMING AND LAYING OF BT SURFACE AT ORAGADAM ROAD 2ND CROSS STREET IN DIVISION-81, UNIT-18, ZONE-VII (AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0412,Roads,Completed,NG-AMBATTUR,81,2023000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT ORAGADAM MAIN ROAD IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0413,Roads,Completed,NG-AMBATTUR,81,1340000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT MOUNASAMY MADAM STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0414,Roads,Completed,NG-AMBATTUR,81,168800,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT MOUNASAMY MADAM CROSS STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0415,Roads,Completed,NG-AMBATTUR,81,1760000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT MURUGAPPA REDDY STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0422,Roads,Completed,NG-AMBATTUR,81,550000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT BAJANAI KOIL 1ST STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0423,Roads,Completed,NG-AMBATTUR,81,303000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT BAJANAI KOIL 2ND STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0424,Roads,Completed,NG-AMBATTUR,81,448000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT MAYA STREET IN DIVISION-81, UNIT-18, ZONE-7 (AMBATTUR)",Own Sources,7,2018-19,2019-20 NG/2018-19/0425,Roads,Completed,NG-AMBATTUR,81,1160000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT CRESANT ROAD IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0426,Roads,Completed,NG-AMBATTUR,81,1716000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT NAINIAMMAL STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0427,Roads,Completed,NG-AMBATTUR,81,709000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT RAMDOSS STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0428,Roads,Completed,NG-AMBATTUR,81,786000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PATTAMMAL STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0429,Roads,Completed,NG-AMBATTUR,81,1588000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT RUKUMANI AMMAL STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0432,Roads,Completed,NG-AMBATTUR,81,231000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT ORAGADAM ROAD CROSS STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0433,Roads,Completed,NG-AMBATTUR,81,936000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT VASUKI STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0434,Roads,Completed,NG-AMBATTUR,81,2000000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SCHOOL ROAD IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/0435,Roads,Completed,NG-AMBATTUR,81,923000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT MUGUNTHAN STREET IN DIVISION-81, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2018-19,2019-20 NG/2018-19/15629,Parks,Completed,NG-AMBATTUR,81,624000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR THIRUVENKADAM NAGAR PARK IN DN-81, UNIT-18, ZONE-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/15630,Parks,Completed,NG-AMBATTUR,81,578000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT SECRETRIAT COLONY PARK IN DIVISION-81, UNIT-18, ZONE-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/15631,Parks,Completed,NG-AMBATTUR,81,569000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT KRISHNAPURAM PARK IN DIVISION-81, UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/15835,Roads,Completed,NG-AMBATTUR,81,93000,"Laying 80mm Thick Cement Concrete Paver Block Road at Nehru Nagar Cross Street in Division-81, Unit-18, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/15836,Storm Water Drain,Completed,NG-AMBATTUR,81,1060000,"Construction of side drain at vivek nagar main road and cross streets in division-81, unit-18, zone-7.",MLACDS,7,2018-19,2019-20 NG/2018-19/6855,Buildings,Completed,NG-AMBATTUR,81,270000,"IMPROVEMENT AND MAINTENANCE WORKS AT SOUTH PARK STREET AND O.T BUS STAND AMMA UNAVAGAM IN DIV-81, UNIT-18, ZONE-VII.",Own Sources,7,2018-19,2020-21 NG/2018-19/7868,Storm Water Drain,Completed,NG-AMBATTUR,81,360000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-81, UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/8447,Storm Water Drain,Completed,NG-AMBATTUR,81,122000,"REPAIR OF SWD AND SIDE DRAINS AT NEHRU NAGAR 2ND STREET AND SATHIYAPURAM 2ND STREET IN DIVISION-81,UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 BR/2018-19/3145,Road Cut,Completed,BR-Bus Route Roads,82,2400000,"Restoration of roadcut made by TANGEDCO at Karukku Main Road (Chainage from 0m to 500m) in Division- 82, Zone -7(Chellan No: BR/2018-19/0001088)",Deposit Works,7,2018-19,2018-19 BR/2018-19/3156,Road Cut,Completed,BR-Bus Route Roads,82,2430000,"Restoration of roadcut made by TANGEDCO at Karukku Main Road (Chainage from 501m to 1000m) in Division- 82, Zone -7(Chellan No: BR/2018-19/0001088)",Deposit Works,7,2018-19,2018-19 BR/2018-19/3158,Road Cut,Completed,BR-Bus Route Roads,82,2080000,"Restoration of roadcut made by TANGEDCO at Karukku Main Road (Chainage from 1001m to 1396m) in Division- 82, Zone -7(Chellan No: BR/2018-19/0001088)",Deposit Works,7,2018-19,2018-19 L/2018-19/11136,Electrical,Completed,L-Electrical,82,197800,"Replacement of 10 Nos. of Completely damaged 63 AMP/3 phase Analogue single dial Automatic Street Lighting ON /OFF Controlling TIMER UNITS At Various Locations In Div. 79 & 82 in Ramnagar Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/11211,Electrical,Completed,L-Electrical,82,997100,"Replacement of 2034 Mtrs of 4 x 16 Sqmm Aluminium UG Cable At Murugambedu Rd, Perumal koil St & Station Road & Lal Bahadur St In Div. 82 & 79 in Ramnagar Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/12277,Electrical,Completed,L-Electrical,82,537600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Slaughter House, Madanakuppam Main Road, Kallikuppam in Ward 82 Zone - VII . E.B Account Number : 441.006.1964",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6053,Electrical,Completed,L-Electrical,82,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma unavagam , Mariamman Koil St, Menambedu in Ward 82 Zone - VII . E.B Account Number : 041.003.3710",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/9788,Electrical,Completed,L-Electrical,82,421600,"Replacement of 6 Nos of Damaged KIOSK Pillar with 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units & Removal of Old Pillar At Various Locations In Div 79 82 in Ramnagar Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 NG/2018-19/0517,Roads,Completed,NG-AMBATTUR,82,390000,"Relaying of BT surface road at Periyar street in Div-82,Unit-18, Zone",Own Sources,7,2018-19,2019-20 NG/2018-19/0518,Roads,Completed,NG-AMBATTUR,82,172000,"Forming and strenthening the road at Thiruvallur nagar 2nd cross street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0519,Roads,Completed,NG-AMBATTUR,82,172000,"Forming and strenthening the road at Thiruvallur nagar 1st cross street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0521,Roads,Completed,NG-AMBATTUR,82,1300000,"Forming and strenthening the road at Thiruvallur nagar MAIN ROAD in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0523,Roads,Completed,NG-AMBATTUR,82,915000,"Forming and strenthening the road at Sakthi nagar 2nd Street Street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0524,Roads,Completed,NG-AMBATTUR,82,965000,"Forming and strenthening the road at Thirunavukarasu Street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0525,Roads,Completed,NG-AMBATTUR,82,1045000,"Forming and strenthening the road at Sakthi nagar 3rd Street Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0526,Roads,Completed,NG-AMBATTUR,82,2210000,"Relaying of BT surface road at Indian bank 3rd main road in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0527,Roads,Completed,NG-AMBATTUR,82,985000,"Relaying of BT surface road at Anna street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0694,Roads,Completed,NG-AMBATTUR,82,1655000,"Relaying of BT surface road at Valliyammal in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0696,Roads,Completed,NG-AMBATTUR,82,800000,"Relaying of BT surface road at Sowkar street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0697,Roads,Completed,NG-AMBATTUR,82,1180000,"Relaying of BT surface road at Gandhi street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0698,Roads,Completed,NG-AMBATTUR,82,1970000,"Relaying of BT surface road at Munusamy koil street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0699,Roads,Completed,NG-AMBATTUR,82,510000,"Relaying of BT surface road at DTP Colony 4TH street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0700,Roads,Completed,NG-AMBATTUR,82,585000,"Relaying of BT surface road at DTP Colony 3rD street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0701,Roads,Completed,NG-AMBATTUR,82,500000,"Relaying of BT surface road at DTP Colony 2nd street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0796,Roads,Completed,NG-AMBATTUR,82,450000,"Relaying of BT surface road at DTP Colony 1st street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0800,Roads,Completed,NG-AMBATTUR,82,840000,"Relaying of BT surface road at Sastri street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0802,Roads,Completed,NG-AMBATTUR,82,840000,"Relaying of BT surface road at Rajamanikkam street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0806,Roads,Completed,NG-AMBATTUR,82,575000,"Relaying of BT surface road at Banu street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0809,Roads,Completed,NG-AMBATTUR,82,765000,"Relaying of BT surface road at Vittal street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0810,Roads,Completed,NG-AMBATTUR,82,850000,"Relaying of BT surface road at Devasi street in Div-82,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/16609,Parks,Completed,NG-AMBATTUR,82,544000,"Maintenance Estimate for Park at Hindustan Colony park in Dn-82, Zone-7",Own Sources,7,2018-19,2020-21 NG/2018-19/6723,Buildings,Completed,NG-AMBATTUR,82,130000,"MAINTENANCE AND REPAIR WORK TO AMMA UNAVAGAM AT MADHAVI STREET KARUKKU IN DIVISION-82, UNIT-18, ZONE-7",Own Sources,7,2018-19,2020-21 NG/2018-19/8159,Storm Water Drain,Completed,NG-AMBATTUR,82,424000,"Desilting of SWD at various streets in division-82,unit-18,zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/8180,Storm Water Drain,Completed,NG-AMBATTUR,82,120000,"Repair Works to SWD prithvipakkam main road, karukku main road, lower canal road, Chittibabu street, prithvipakkam 2nd avenue In Divsion-82,unit-18, Zone-7.",Own Sources,7,2018-19,2019-20 BR/2018-19/15701,Road Cut,Completed,BR-Bus Route Roads,83,297000,Restoration of OFC work made by Reliance in various IRR roads in Division- 83 Unit-18 Zone-7(Deposit code-57/0053/2018-19),Deposit Works,7,2018-19,2019-20 BR/2018-19/5436,Roads,Completed,BR-Bus Route Roads,83,28277000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Madhanakuppam Road in Dn-83, Zone - VII",Grants,7,2018-19,2019-20 BR/2018-19/5493,Road Cut,Completed,BR-Bus Route Roads,83,2495000,"Restoration of roadcut made by CMWSSB at Madhanakuppam Main Road in Dn-83, Zone-7(Chellan code :57/0841/2017-18)",Deposit Works,7,2018-19,2018-19 BR/2018-19/7056,Roads,Completed,BR-Bus Route Roads,83,7490000,"Proposed Centre Median at Water Canal Road (From the jn of bridge to Madhanakuppam Road) and Construction of Barricade Work (Crash Barrier type) at Water Canal Road (Southern Side and Northern side) from Bridge towards Madhanakuppam Road in Dn-83, Zone-7",Grants,7,2018-19,2019-20 D/2018-19/16002,Storm Water Drain,Completed,D-Storm Water Drains,83,46000000,"Construction of Flood Protection Wall with bed lining for North Avenue Canal (from Railway Chainage 11/900 to 11/500) parallel to Southern side of Railway Track in Dn. 83, Zone - 7",SMART CITY - SWD,7,2018-19,2019-20 D/2018-19/16003,Storm Water Drain,Completed,D-Storm Water Drains,83,45840000,"Construction of Flood Protection Wall with bed lining for North Avenue Canal (from Railway Chainage 11/500 to 11/100) parallel to Southern side of Railway Track in Dn. 83, Zone - 7",SMART CITY - SWD,7,2018-19,2019-20 D/2018-19/16004,Storm Water Drain,Completed,D-Storm Water Drains,83,46160000,"Construction of Flood Protection Wall with bed lining for North Avenue Canal (from Railway Chainage 11/100 to 10/700) parallel to Southern side of Railway Track in Dn. 83, Zone - 7",SMART CITY - SWD,7,2018-19,2019-20 L/2018-19/10939,Electrical,Completed,L-Electrical,83,199500,"Proposal for fixing of 510 Nos of LED Fittings & Removal of 510 nos Sodium fittings At Various Locations In Div 83, 84, 85 & 87 in Ramnagar & Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/11424,Electrical,Completed,L-Electrical,83,257100,"Replacement of 13 Nos. of Completely damaged 63 AMP/3 phase Analogue single dial Automatic Street Lighting ON /OFF Controlling TIMER UNITS At Various Locations In Div. 84, 85 & 87 in Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/11427,Electrical,Completed,L-Electrical,83,197800,"Replacement of 10 Nos. of Completely damaged 63 AMP/3 phase Analogue single dial Automatic Street Lighting ON /OFF Controlling TIMER UNITS At Various Locations In Div. 83.84, 85 & 87 in Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/12931,Electrical,Completed,L-Electrical,83,178800,"Proposal for fixing of 457 Nos of LED Fittings & Removal of 457 nos Sodium fittings At Various Locations In Div 83 , 84, 85 & 87 in Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/14747,Electrical,Completed,L-Electrical,83,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office ,Venketramannagar Dn 83 Zone - VII . E.B Account Number : 038.002.5581",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/14748,Electrical,Completed,L-Electrical,83,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC @ TNHB 32 nd street Ward 83 Zone - VII . E.B Account Number : 038.002.2657",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/14751,Electrical,Completed,L-Electrical,83,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ICDS, Thathankuppam in Ward 83 Zone - VII . E.B Account Number : 072.077.829",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/9130,Electrical,Completed,L-Electrical,83,192700,"Estimate for raising of 24 nos of Kiosk Pillar Boxes from the Ground Level at various location in Division 83,84,85,87, in Zone VII",Own Sources,7,2018-19,2019-20 NG/2018-19/0073,Roads,Completed,NG-AMBATTUR,83,2280000,"Relaying the Bituminous ConCrete Road at Avs Nagar Main Road in Div-83,Unit-19, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0086,Roads,Completed,NG-AMBATTUR,83,225000,"Relaying the Bituminous ConCrete Road at Rajiv Nagar in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0088,Roads,Completed,NG-AMBATTUR,83,579000,"Relaying the Bituminous ConCrete Road at Metro Water Link Road in Div-83,Unit-19, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0098,Roads,Completed,NG-AMBATTUR,83,1390000,"forming and laying the BT road at Gopala Krishnan Nagar Main Road in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0259,Roads,Completed,NG-AMBATTUR,83,698000,"Relaying of BT surface road at SRINIVASAPURAM 2ND MAIN ROAD in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2020-21 NG/2018-19/0266,Roads,Completed,NG-AMBATTUR,83,1655000,"Relaying of BT surface road at THATHANKUPPAM MAIN ROAD in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0267,Roads,Completed,NG-AMBATTUR,83,617000,"Relaying of BT surface road at ANNAI NAGAR 5TH STREET in Div-83,Unit-18,Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0275,Roads,Completed,NG-AMBATTUR,83,577000,"FORMING AND LAYING THE BT ROADS AT ANNAI NAGAR 1ST STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0286,Roads,Completed,NG-AMBATTUR,83,625000,"Relaying of BT surface road at ELLAIYAMMAN NAGAR 3RD STREET in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0288,Roads,Completed,NG-AMBATTUR,83,710000,"Relaying of BT surface road at KUMARAN NAGAR in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0290,Roads,Completed,NG-AMBATTUR,83,870000,"RELAYING THE BT ROADS AT ELLAIYAMMAN NAGAR 4TH STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0294,Roads,Completed,NG-AMBATTUR,83,1120000,"RELAYING THE BT ROADS AT SUBULAKSHMI NAGAR 1ST STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0300,Roads,Completed,NG-AMBATTUR,83,475000,"Relaying of BT surface road at ELLAIYAMMAN NAGAR 5TH STREET in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0309,Roads,Completed,NG-AMBATTUR,83,1010000,"Relaying of BT surface road at KAVIYA NAGAR in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0319,Roads,Completed,NG-AMBATTUR,83,1965000,"Relaying of BT surface road at TVS NAGAR EXTENSION in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0321,Roads,Completed,NG-AMBATTUR,83,1100000,"FORMING AND LAYING THE BT ROADS AT COLLECTOR NAGAR 1ST STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0322,Roads,Completed,NG-AMBATTUR,83,925000,"FORMING AND LAYING THE BT ROADS AT COLLECTOR NAGAR 2ND STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0323,Roads,Completed,NG-AMBATTUR,83,925000,"FORMING AND LAYING THE BT ROADS AT COLLECTOR NAGAR 3RD STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0328,Roads,Completed,NG-AMBATTUR,83,925000,"FORMING AND LAYING THE BT ROADS AT COLLECTOR NAGAR 4TH STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0343,Roads,Completed,NG-AMBATTUR,83,825000,"Relaying of BT surface road at TNHB 49TH STREET in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0345,Roads,Completed,NG-AMBATTUR,83,640000,"Relaying of BT surface road at TNHB 32ND STREET in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0346,Roads,Completed,NG-AMBATTUR,83,870000,"Relaying of BT surface road at TNHB 37TH STREET in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0349,Roads,Completed,NG-AMBATTUR,83,1120000,"Relaying of BT surface road at STATION ROAD in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/0352,Roads,Completed,NG-AMBATTUR,83,1720000,"FORMING AND LAYING THE BT ROADS AT PERUMAL KOIL STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0354,Roads,Completed,NG-AMBATTUR,83,840000,"Relaying of BT surface road at TNHB 41ST STREET in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2020-21 NG/2018-19/15636,Parks,Completed,NG-AMBATTUR,83,204000,"Maintenance Estimate for the Park At Sastha Nagar Park In Division-83, Unit-18, Zone-VII ( Ambattur )",Own Sources,7,2018-19,2020-21 NG/2018-19/15637,Parks,Completed,NG-AMBATTUR,83,831000,"Maintenance Estimate for the Park At TNHB 61st Street Park In Division-83, Unit-18, Zone-VII ( Ambattur )",Own Sources,7,2018-19,2020-21 NG/2018-19/15638,Parks,Completed,NG-AMBATTUR,83,263000,"Maintenance Estimate for the Park At Subulakshmi Nagar Park In Division-83, Unit-18, Zone-VII ( Ambattur )",Own Sources,7,2018-19,2020-21 NG/2018-19/15639,Parks,Completed,NG-AMBATTUR,83,222000,"Maintenance Estimate for the Park At Sri Ranga Garden Park In Division-83, Unit-18, Zone-VII ( Ambattur )",Own Sources,7,2018-19,2020-21 NG/2018-19/1923,Roads,Completed,NG-AMBATTUR,83,925000,"FORMING AND LAYING THE BT ROADS AT COLLECTOR NAGAR 5TH STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1924,Roads,Completed,NG-AMBATTUR,83,1200000,"FORMING AND LAYING THE BT ROADS AT COLLECTOR NAGAR 6TH STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1925,Roads,Completed,NG-AMBATTUR,83,1200000,"Relaying of BT surface road at COLLECTOR NAGAR 7TH STREET MADHANKUPPAM in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/1926,Roads,Completed,NG-AMBATTUR,83,1090000,"Relaying of BT surface road at TNHB 25TH STREET in Div-83,Unit-18, Zone 7",Own Sources,7,2018-19,2019-20 NG/2018-19/1928,Roads,Completed,NG-AMBATTUR,83,1369000,"FORMING AND LAYING THE BT ROADS AT AVS NAGAR MAIN ROAD EXTENSION IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1929,Roads,Completed,NG-AMBATTUR,83,1975000,"FORMING AND LAYING THE BT ROADS AT GANESH NAGAR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1930,Roads,Completed,NG-AMBATTUR,83,775000,"FORMING AND LAYING THE BT ROADS AT VENKATESHWARA THYAGARAYA NAGAR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1931,Roads,Completed,NG-AMBATTUR,83,550000,"FORMING AND LAYING THE BT ROADS AT ANNAI NAGAR 6TH STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1932,Roads,Completed,NG-AMBATTUR,83,265000,"FORMING AND LAYING THE B .T ROADS AT MADHAVA NAGAR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1933,Roads,Completed,NG-AMBATTUR,83,3275000,"FORMING AND LAYING THE BT ROADS AT SENAI THALAIVAR NAGAR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1935,Roads,Completed,NG-AMBATTUR,83,2730000,"FORMING AND LAYING THE BT ROADS AT SANTHOSH NAGAR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1936,Roads,Completed,NG-AMBATTUR,83,995000,"FORMING AND LAYING THE BT ROADS AT ARB NAGAR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1937,Roads,Completed,NG-AMBATTUR,83,1230000,"FORMING AND LAYING THE BT ROADS AT VAAGAI NAGAR 2ND STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/1939,Roads,Completed,NG-AMBATTUR,83,960000,"FORMING AND LAYING THE BT ROADS AT MAHATMA GHANDHI STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4327,Roads,Completed,NG-AMBATTUR,83,996000,"Attending Patches and Providing Thermoplastic and molded studd to the existing BT surface road at NAS garden in Div-83, unit-18, Zone-7",Own Sources,7,2018-19,2021-22 NG/2018-19/6899,Buildings,Completed,NG-AMBATTUR,83,270000,"Improvement And Maintenance Works At North Avenue Amma Unavagam And Rajiv Gandhi Nagar Amma Unavagam In Div-83, Unit-18, Zone-VII.",Own Sources,7,2018-19,2019-20 NG/2018-19/7910,Storm Water Drain,Completed,NG-AMBATTUR,83,228000,"DE-SILTING AND IMPROVEMENT OF EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-83,UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/8167,Storm Water Drain,Completed,NG-AMBATTUR,83,13000,"REPLACEMENT OF DAMAGED MANHOLE COVERS IN DIVISION-83, UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/8320,Roads,Completed,NG-AMBATTUR,83,775000,"RELAYING THE BT ROADS AT SAKTHI NAGAR IN DIVISION-83, UNIT-18, ZONE-7",Own Sources,7,2018-19,2019-20 BR/2018-19/0200,Road Cut,Completed,BR-Bus Route Roads,84,950000,"Restoration of Roadcut made by TANGEDCO at Station Road in Dn-84, Zone-7",Deposit Works,7,2018-19,2018-19 BR/2018-19/15713,Road Cut,Completed,BR-Bus Route Roads,84,843000,Restoration of OFC road cut made by AIRTEL in various IRR roads in Division-84 Unit-19 Zone-VII (Chellan No:BR/2018-19/0004910),Deposit Works,7,2018-19,2019-20 BR/2018-19/17107,Road Cut,Completed,BR-Bus Route Roads,84,973000,REstoration of Roadcut made by OFC Operators at Various Bus Route Roads in Zone-VII,Deposit Works,7,2018-19,2019-20 BR/2018-19/17122,Road Cut,Completed,BR-Bus Route Roads,84,974000,REstoration of Roadcut made by OFC Operators at Various Bus Route Roads in Zone-VII,Deposit Works,7,2018-19,2019-20 BR/2018-19/5559,Roads,Completed,BR-Bus Route Roads,84,16677000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Central Avenue Road in Dn-84, Zone - VII",Grants,7,2018-19,2019-20 BR/2018-19/6852,Footpath,Completed,BR-Bus Route Roads,84,2196000,"Footpath Repair Works at East Avenue Road in Dn-84, Zone-VII",Grants,7,2018-19,2019-20 BR/2018-19/6853,Footpath,Completed,BR-Bus Route Roads,84,1681000,"Footpath Repair Works at Central Avenue Road in Dn-84, Zone-VII",Grants,7,2018-19,2019-20 D/2018-19/8370,Storm Water Drain,Completed,D-Storm Water Drains,84,1238000,"Restoration and other improvements to JJ NAGAR (Jambukeshwarar pond) POND for augmentation of water supply in Dn.84, Zone 7.",SMART CITY - SWD,7,2018-19,2019-20 L/2018-19/12542,Electrical,Completed,L-Electrical,84,954300,"Replacement of 184 Mtrs 4 x 16 Sqmm Aluminium UG Cable At Elango Nagar, Vallalar Street & , 1601 Mtrs of 2 x 16 sqmm Aluminium UG Cable at TNHB Colony & Thillai Nagar In Div. 84 in Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2020-21 L/2018-19/14752,Electrical,Completed,L-Electrical,84,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office , 11th St, TNHB Colony in Ward 84 Zone - VII . E.B Account Number : 038.003.3591",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/14753,Electrical,Completed,L-Electrical,84,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma unavagam , pattravakkam Ward 84 Zone - VII . E.B Account Number : 430.002.1265",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/0168,Buildings,Completed,NG-AMBATTUR,84,403000,"Forming a new Cement Concrete road at Vinayagar Koil Cross street in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0289,Buildings,Completed,NG-AMBATTUR,84,1393000,"Relaying a BT road at Bramin street (Korattur) in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0378,Buildings,Completed,NG-AMBATTUR,84,2000000,"Improvements to ICDS at Kulakkarai Street ( Pattravakkam ) in Div - 84, Unit - 19, Zone - 7.",Own Sources,7,2018-19,2018-19 NG/2018-19/0464,Buildings,Completed,NG-AMBATTUR,84,2000000,"Improvements to ICDS at Bajanai koil Street ( Pattravakkam ) in Div - 84, Unit - 19, Zone - 7.",Own Sources,7,2018-19,2018-19 NG/2018-19/0465,Buildings,Completed,NG-AMBATTUR,84,2000000,"Improvements to ICDS at EB Road Pattravakkam (Inside of School Campus) in Div - 84, Unit - 19, Zone - 7.",Own Sources,7,2018-19,2018-19 NG/2018-19/0508,Buildings,Completed,NG-AMBATTUR,84,500000,"IMPROVEMENT WORKS CHS AT CHAVADI STREET KORATTUR IN DIVISION :-84, UNIT-19,ZONE-07.",Own Sources,7,2018-19,2018-19 NG/2018-19/0586,Buildings,Completed,NG-AMBATTUR,84,200000,"IMPROVEMENT WORKS CMS AT EB ROAD (PATTARAVAKKAM) IN DIVISION - 84, UNIT - 19, ZONE - 7",Own Sources,7,2018-19,2018-19 NG/2018-19/0657,Buildings,Completed,NG-AMBATTUR,84,810000,"Relaying a BT road at DEVADOSS STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0658,Buildings,Completed,NG-AMBATTUR,84,2366000,"Relaying a BT road at JAMBUKESHWARAR MAIN ROAD in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0661,Buildings,Completed,NG-AMBATTUR,84,458000,"Relaying a BT road at KAMARAJ NAGAR 10TH STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/0666,Buildings,Completed,NG-AMBATTUR,84,742000,"Relaying a BT road at KAMARAJ NAGAR 6TH STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/11857,Road Cut,Completed,NG-AMBATTUR,84,579000,"Restoration of Road Cut Made by CMWSSB AT Kamaraj nagar 9th street and Bajanai koil street in Division -84, Unit-19, Zone-7",Deposit Works,7,2018-19,2019-20 NG/2018-19/12250,Buildings,Completed,NG-AMBATTUR,84,135000,"Improvement and maintenance of Amma unavagam at Kannan koil street(Pattaravakkam) in Division -84, Unit - 19, Zone -7.",Own Sources,7,2018-19,2019-20 NG/2018-19/13030,Buildings,Completed,NG-AMBATTUR,84,473000,"Forming a new Cement Concrete road at PERIYAR NAGAR MGR CROSS STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13031,Buildings,Completed,NG-AMBATTUR,84,310000,"Forming a new Cement Concrete road at AMBEDKAR 4TH CROSS STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13032,Buildings,Completed,NG-AMBATTUR,84,593000,"Forming a new Cement Concrete road at BAJANAI KOIL PATTARAVAKKAM in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13044,Buildings,Completed,NG-AMBATTUR,84,458000,"Relaying a BT road at KAMARAJ NAGAR 9TH STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13047,Buildings,Completed,NG-AMBATTUR,84,1095000,"Relaying a BT road at SHANTHI NAGAR in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13048,Buildings,Completed,NG-AMBATTUR,84,1095000,"Relaying a BT road at SIVASAKTHI NAGAR 1ST STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13049,Buildings,Completed,NG-AMBATTUR,84,281000,"Relaying a BT road at SIVASAKTHI NAGAR 2ND STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13050,Buildings,Completed,NG-AMBATTUR,84,1450000,"Relaying a BT road at TAMIL STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13051,Buildings,Completed,NG-AMBATTUR,84,564000,"Relaying a BT road at THILLAI NAGAR 1ST STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13052,Buildings,Completed,NG-AMBATTUR,84,245000,"Relaying a BT road at THILLAI NAGAR 2ND STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13053,Buildings,Completed,NG-AMBATTUR,84,2650000,"Relaying a BT road at THIRUMULLAIVOIL ROAD STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13054,Buildings,Completed,NG-AMBATTUR,84,1290000,"Relaying a BT road at TNHB 11 TH STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13055,Buildings,Completed,NG-AMBATTUR,84,2860000,"Relaying a BT road at TNHB 2 ND STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13056,Buildings,Completed,NG-AMBATTUR,84,1190000,"Relaying a BT road at TNHB 4 TH STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13057,Buildings,Completed,NG-AMBATTUR,84,1190000,"Relaying a BT road at VANNIAR 2ND STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13058,Buildings,Completed,NG-AMBATTUR,84,995000,"Relaying a BT road at Vanniar 1st Street in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13059,Buildings,Completed,NG-AMBATTUR,84,2010000,"Relaying a BT road at TNHB 18th street in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13060,Buildings,Completed,NG-AMBATTUR,84,660000,"Relaying a BT road at Kuppu reddy street in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13061,Buildings,Completed,NG-AMBATTUR,84,264000,"Relaying a BT road at Lakshmana reddy street in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13062,Buildings,Completed,NG-AMBATTUR,84,839000,"Relaying a BT road at Nagammal street in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13301,Road Cut,Completed,NG-AMBATTUR,84,846000,"Restoration of Road Cut Made by CMWSSB at Kanniamman koil street in Division -84, Unit-19, Zone-7",Deposit Works,7,2018-19,2020-21 NG/2018-19/13303,Road Cut,Completed,NG-AMBATTUR,84,714000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SASTHIRI SQUARE STREET IN DIVISION -84, UNIT-19, ZONE-7",Deposit Works,7,2018-19,2020-21 NG/2018-19/16094,Buildings,Completed,NG-AMBATTUR,84,1410000,"Relaying a Cement Concrete road at KAKKANJI STREET in Div-84, Unit-19, Zone-7",MLACDS,7,2018-19,2019-20 NG/2018-19/16095,Buildings,Completed,NG-AMBATTUR,84,3056000,"Relaying a Cement Concrete road at PERIAR NAGAR MGR STREET in Div-84, Unit-19, Zone-7",MLACDS,7,2018-19,2019-20 NG/2018-19/16559,Parks,Completed,NG-AMBATTUR,84,215000,"ABSTRACT FOR MAINTENANCE ESTIMATE FOR PARK AT KR NAGAR PARK IN DN-84, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16560,Parks,Completed,NG-AMBATTUR,84,220000,"ABSTRACT FOR MAINTENANCE ESTIMATE FOR PARK AT TNHB 4TH STREET PARK IN DIV-84, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4190,Buildings,Completed,NG-AMBATTUR,84,458000,"Relaying a BT road at KAMARAJ NAGAR 7TH STREET in Div-84, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/6872,Buildings,Completed,NG-AMBATTUR,84,135000,"Improvement and maintenance of Amma unavagam at Bajanai Koil street(Pattaravakkam) in Division -84, Unit - 19, Zone -7.",Own Sources,7,2018-19,2019-20 NG/2018-19/6884,Buildings,Completed,NG-AMBATTUR,84,135000,"Improvement and maintenance of Ammaunavagam at East Avenue road in Division -84, Unit - 19, Zone -7.",Own Sources,7,2018-19,2019-20 NG/2018-19/8740,Buildings,Completed,NG-AMBATTUR,84,321000,"Desilting To The Existing Road Side Drain And Storm Water Drain At Various Streets In Division-84, Unit-19,Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/8741,Buildings,Completed,NG-AMBATTUR,84,160000,"Repair Works To The Existing Road Side Drain And Storm Water Drain At Various Streets In Division-84, Unit-19,Zone-7.",Own Sources,7,2018-19,2019-20 BR/2018-19/6539,Roads,Completed,BR-Bus Route Roads,85,58000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DN.85, ZONE-07. (57/0740/2017-18) PACKAGE-11.",Deposit Works,7,2018-19,2018-19 L/2018-19/14754,Electrical,Completed,L-Electrical,85,4525300,"ESTIMATE for Supply, Installation, Testing & Commissioning of 60 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Zonal Office, CTH Road in Ward 85 Zone - VII . E.B Account Number : 435.232.110",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/14756,Electrical,Completed,L-Electrical,85,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC, Vardharajapuram in Ward 85 Zone - VII . E.B Account Number : 435.114.7 .",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/14757,Electrical,Completed,L-Electrical,85,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office ,MTH road Dn 85 Zone - VII . E.B Account Number : 435.232.139",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/0238,Buildings,Completed,NG-AMBATTUR,85,300000,"Repair and Maintenance for CMS at Nehru Street, Teachers Colony in Divsion-85, Unit-19, Zone-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0251,Buildings,Completed,NG-AMBATTUR,85,100000,"Repair and Maintenance for CMS at Padasalai Street, Mangalapuram in Divsion-85, Unit-19, Zone-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0252,Buildings,Completed,NG-AMBATTUR,85,300000,"Repair and Maintanance for CHS at Jeeva Street, Kamarajapuram in Divsion-85, Unit-19, Zone-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0269,Buildings,Completed,NG-AMBATTUR,85,321000,"Repair and Maintenance for NNMP Shed At Bajanai koil Street, Mangalapuram in Divsion-85, Unit-19, Zone-7",Own Sources,7,2018-19,2018-19 NG/2018-19/12251,Buildings,Completed,NG-AMBATTUR,85,135000,"Repairs and Maintanance works to Amma unavagam at CTH Road in Div-85, Unit-19, Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/12252,Buildings,Completed,NG-AMBATTUR,85,135000,"Repairs and Maintanance works to Amma unavagam at Sivanandha 1st Street in Div-85, Unit-19, Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/13602,Roads,Completed,NG-AMBATTUR,85,2270000,"RELAYING OF BT ROAD IN BAZZER STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13688,Roads,Completed,NG-AMBATTUR,85,881000,"RELAYING OF BT ROAD IN DR.MOORTHY NAGAR MAIN ROAD IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13700,Roads,Completed,NG-AMBATTUR,85,2130000,"RELAYING OF BT ROAD IN AGASHIAR STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13702,Roads,Completed,NG-AMBATTUR,85,1400000,"RELAYING OF BT ROAD IN OLD ESI ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13703,Roads,Completed,NG-AMBATTUR,85,2575000,"RELAYING OF BT ROAD IN PATTARAVAKKAM ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13704,Roads,Completed,NG-AMBATTUR,85,1400000,"RELAYING OF BT ROAD IN O.V ASHAGESAN ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13706,Roads,Completed,NG-AMBATTUR,85,793000,"RELAYING OF BT ROAD IN SAMDHARIYA 3RD STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13707,Roads,Completed,NG-AMBATTUR,85,859000,"RELAYING OF BT ROAD IN SAMDHARIYA 4TH STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13708,Roads,Completed,NG-AMBATTUR,85,387000,"RELAYING OF BT ROAD IN SAMDHARIYA CROSS STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13709,Roads,Completed,NG-AMBATTUR,85,874000,"RELAYING OF BT ROAD IN KUMARAN STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13710,Roads,Completed,NG-AMBATTUR,85,1166000,"RELAYING OF BT ROAD IN BADMANABAN STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13711,Roads,Completed,NG-AMBATTUR,85,652000,"RELAYING OF BT ROAD IN KAMBER STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13712,Roads,Completed,NG-AMBATTUR,85,930000,"RELAYING OF BT ROAD IN BHARATHI STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13713,Roads,Completed,NG-AMBATTUR,85,775000,"RELAYING OF BT ROAD IN RAMAN STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13714,Roads,Completed,NG-AMBATTUR,85,767000,"RELAYING OF BT ROAD IN KALYANI AMMAL STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13715,Roads,Completed,NG-AMBATTUR,85,1970000,"RELAYING OF BT ROAD IN GNG ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13716,Roads,Completed,NG-AMBATTUR,85,402000,"RELAYING OF BT ROAD IN GNG 1ST STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13717,Roads,Completed,NG-AMBATTUR,85,448000,"RELAYING OF BT ROAD IN GNG 2ND STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13718,Roads,Completed,NG-AMBATTUR,85,979000,"RELAYING OF BT ROAD IN GNG 3RD STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13719,Roads,Completed,NG-AMBATTUR,85,631000,"RELAYING OF BT ROAD IN CRM STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13720,Roads,Completed,NG-AMBATTUR,85,516000,"RELAYING OF BT ROAD IN SUBBAN STREET STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13721,Roads,Completed,NG-AMBATTUR,85,393000,"RELAYING OF BT ROAD IN SHANMUGAM STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13722,Roads,Completed,NG-AMBATTUR,85,612000,"RELAYING OF BT ROAD IN RAJA MUDALI STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13723,Roads,Completed,NG-AMBATTUR,85,489000,"RELAYING OF BT ROAD IN KUMARASAMY STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13724,Roads,Completed,NG-AMBATTUR,85,326000,"RELAYING OF BT ROAD IN PARTHASARATHY STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13725,Roads,Completed,NG-AMBATTUR,85,1290000,"RELAYING OF BT ROAD IN NADESAN STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13726,Roads,Completed,NG-AMBATTUR,85,353000,"RELAYING OF BT ROAD IN STATION STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13727,Roads,Completed,NG-AMBATTUR,85,914000,"RELAYING OF BT ROAD IN TIC ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13728,Roads,Completed,NG-AMBATTUR,85,1576000,"RELAYING OF BT ROAD IN NEHRU STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13729,Roads,Completed,NG-AMBATTUR,85,426000,"RELAYING OF BT ROAD IN NEW STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13730,Roads,Completed,NG-AMBATTUR,85,980000,"RELAYING OF BT ROAD IN TEACHERS COLONY 1ST MAIN ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13731,Roads,Completed,NG-AMBATTUR,85,760000,"RELAYING OF BT ROAD IN TEACHERS COLONY 2ND MAIN ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13732,Roads,Completed,NG-AMBATTUR,85,740000,"RELAYING OF BT ROAD IN STALIN STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13734,Roads,Completed,NG-AMBATTUR,85,1260000,"RELAYING OF BT ROAD IN AMBEDKAR STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13735,Roads,Completed,NG-AMBATTUR,85,1160000,"RELAYING OF BT ROAD IN CANAL STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13736,Roads,Completed,NG-AMBATTUR,85,810000,"RELAYING OF BT ROAD IN RAMAR KOIL STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13737,Roads,Completed,NG-AMBATTUR,85,890000,"RELAYING OF BT ROAD IN SIVANANDHA 1ST MAIN ROAD IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13738,Roads,Completed,NG-AMBATTUR,85,1880000,"RELAYING OF BT ROAD IN KULLAKARAI STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13739,Roads,Completed,NG-AMBATTUR,85,1340000,"RELAYING OF BT ROAD IN JEEVA STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13740,Roads,Completed,NG-AMBATTUR,85,920000,"RELAYING OF BT ROAD IN KANNATHAMMAN KOIL STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13741,Roads,Completed,NG-AMBATTUR,85,1150000,"RELAYING OF BT ROAD IN PERIYAR STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13742,Roads,Completed,NG-AMBATTUR,85,1300000,"RELAYING OF BT ROAD IN TVK STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13743,Roads,Completed,NG-AMBATTUR,85,890000,"RELAYING OF BT ROAD IN VOC STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13744,Roads,Completed,NG-AMBATTUR,85,314000,"RELAYING OF BT ROAD IN TOWNSHIP QUARTUS 1ST STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13745,Roads,Completed,NG-AMBATTUR,85,270000,"RELAYING OF BT ROAD IN TOWNSHIP QUARTUS 2ND STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13747,Roads,Completed,NG-AMBATTUR,85,280000,"RELAYING OF BT ROAD IN TOWNSHIP QUARTUS 3RD STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13749,Roads,Completed,NG-AMBATTUR,85,1120000,"RELAYING OF BT ROAD IN PADASALAI STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13750,Roads,Completed,NG-AMBATTUR,85,1120000,"RELAYING OF BT ROAD IN NALLAKINARU STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13751,Roads,Completed,NG-AMBATTUR,85,629000,"RELAYING OF BT ROAD IN KULLAN STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13752,Roads,Completed,NG-AMBATTUR,85,1140000,"RELAYING OF BT ROAD IN BAJANAI KOIL STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13756,Roads,Completed,NG-AMBATTUR,85,1610000,"RELAYING OF CC ROAD IN HARI KRISHNA NAIDU STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13758,Roads,Completed,NG-AMBATTUR,85,212000,"RELAYING OF CC ROAD IN MANIKKA VINAYAGAR STREET IN DN 85, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/16038,Roads,Completed,NG-AMBATTUR,85,276000,"Laying of Cement Concrete Road at Harichandran koil Cross street in Division-85, Unit-19, Zone-7.",MLACDS,7,2018-19,2019-20 NG/2018-19/16043,Roads,Completed,NG-AMBATTUR,85,322700,"Laying of Cement Concrete Road At Anna Street in Division-85, Unit-19, Zone-7.",MLACDS,7,2018-19,2020-21 NG/2018-19/16045,Roads,Completed,NG-AMBATTUR,85,208400,"Laying 80mm Thick cement Concrete Paver Block Road at Siva Sankaran Koil 1st cross st & 2nd Cross St in Div-85,Unit-19,Zone-7",MLACDS,7,2018-19,2019-20 NG/2018-19/7367,Storm Water Drain,Completed,NG-AMBATTUR,85,743000,"Desiliting of SWD at various Street in Div-85, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 P/2018-19/11982,Parks,Completed,P-Parks and Playfields,85,17416661,"FORMATION OF NEW PARK AT RAILWAY QUARTRES (Near T.I. CYCLE ) CTH ROAD (OSR-1) IN DN-85, ZONE - VII.",Grants,7,2018-19,2019-20 BR/2018-19/5531,Road Cut,Completed,BR-Bus Route Roads,86,2000000,"Restoration of Roadcut made by CMWSSB at ICF Colony Ayampakkam Main Road in Dn-86, Zone-7(Chellan code :57/0841/2017-18)",Deposit Works,7,2018-19,2019-20 BR/2018-19/8997,Road Cut,Completed,BR-Bus Route Roads,86,960000,"Restoration of roadcut made by CMWSSB at ICF colony Ayanambakkam Road from the jn of Thirupathi kodai road to the jn of Cauvery Road in Dn - 86, Zone - 7.(chellan no: BR/2018-19/0001633)",Deposit Works,7,2018-19,2019-20 D/2018-19/8445,Storm Water Drain,Completed,D-Storm Water Drains,86,2440000,"Restoration and other improvements to Udayarpalayam Pond for augmentation of water supply in Dn.86, Zone 7.",SMART CITY - SWD,7,2018-19,2020-21 L/2018-19/6046,Electrical,Completed,L-Electrical,86,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital ,Chinna colony Health Post Athipet . Div - 86, Zone -7 EB NO:440.124.790",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/0439,Buildings,Completed,NG-AMBATTUR,86,352000,"Annual Maintenance and Repair Works to Anganvadi Centre at Vanagaram main road athipet in division - 86, unit-19,zone -7",Own Sources,7,2018-19,2018-19 NG/2018-19/0440,Buildings,Completed,NG-AMBATTUR,86,331000,"Annual Maintenance and Repair Works to Anganvadi Centre at Pillayar Kovil Street, Mannurpet in division - 86, unit-19,zone -7",Own Sources,7,2018-19,2018-19 NG/2018-19/0442,Buildings,Completed,NG-AMBATTUR,86,642000,"Annual Maintenance and Repair Works to Chennai High School at Vanagarm Main road, Athipet in division - 86, unit-19,zone -7",Own Sources,7,2018-19,2018-19 NG/2018-19/11994,Buildings,Completed,NG-AMBATTUR,86,135000,"Attending repair work and improvement to Amma Unavagam at Vanagaram Main road, Athipet in Division -86, Unit- 19, Zone - VII",Own Sources,7,2018-19,2019-20 NG/2018-19/12003,Buildings,Completed,NG-AMBATTUR,86,245000,"Attending repair works and improvements to Amma Unavagam at Nehru Nagar, Mannurpet in Division - 86, Unit- 19, Zone - 7.",Own Sources,7,2018-19,2019-20 NG/2018-19/15311,Roads,Completed,NG-AMBATTUR,86,1040000,"Forming and Laying Bituminous concrete road at TT Mathew Cross Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15312,Roads,Completed,NG-AMBATTUR,86,5500000,"Relaying the existing Bituminous concrete road at Manickam Pillai Street,Nehru Nagar Main road,Pillayar Kovil Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15313,Roads,Completed,NG-AMBATTUR,86,4400000,"Relaying the existing Bituminous concrete road at PK Mohammed Road,Kavarai Street,Vellalar Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15314,Roads,Completed,NG-AMBATTUR,86,6900000,"Relaying the existing Bituminous concrete road at Ram Poornam Nagar 1st Main Road,Ram Poornam Nagar 2nd Main Road,Ram Poornam Nagar Extn Road,Ram Poornam Nagar 1st Cross Street,Ram Poornam Nagar 2nd Cross Street,Ram Poornam Nagar 3rd Cross Street,Bharathi Street,Kalidasan Street, Bharathidasan Street, Bharathidasan Cross Street,Pugazenthi Street,Kambar Street in Division-86,Unit-19, Zone-7.",Own Sources,7,2018-19,2018-19 NG/2018-19/15315,Roads,Completed,NG-AMBATTUR,86,8900000,"Relaying the existing Bituminous concrete road at MWP 3rd cross street, Gothavari Street, Thamirabarani Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15316,Roads,Completed,NG-AMBATTUR,86,7400000,"Forming and Laying Bituminous concrete road at Athipet main Road (From Perumal kovil to vanagaram main road) in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15317,Roads,Completed,NG-AMBATTUR,86,5200000,"Forming and Laying Bituminous concrete road at Township Colony in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15321,Roads,Completed,NG-AMBATTUR,86,13741000,"Forming and Laying Bituminous concrete road at Chelliamman kovil main road (from ayanambakkam main road to Mettu street) in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15322,Roads,Completed,NG-AMBATTUR,86,8500000,"Forming and Laying Bituminous concrete road Chelliamman kovil Extn road,Ambethkar Street (Chelliammman kovil nagar) at in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15323,Roads,Completed,NG-AMBATTUR,86,7800000,"Forming and Laying Bituminous concrete road at Ambethkar Street (Udayar Palayam),Ceon Street,Kulam Street,Thirukumaran Street,Mettu 9th Street,Anganna Reddy Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15324,Roads,Completed,NG-AMBATTUR,86,13159000,"Forming and Laying Bituminous concrete road at Natesan Nagar Main Road ( L shape road & Lanes) in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15326,Roads,Completed,NG-AMBATTUR,86,3880000,"Forming and Laying Bituminous concrete road at Natesan Nagar 1st, 2nd, 3rd Cross Streets in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/15327,Roads,Completed,NG-AMBATTUR,86,5650000,"Forming and Laying Bituminous concrete road at Nageshwara Rao Main Road in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15328,Roads,Completed,NG-AMBATTUR,86,8300000,"Forming and Laying Bituminous concrete road at Nageshwara Rao 1st Cross Street,Nageshwara Rao 2nd Cross Street,Nageshwara Rao 3rd Cross Street,Nageshwara Rao 4th Cross Street,Nageshwara Rao 5th Cross Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15329,Roads,Completed,NG-AMBATTUR,86,6530000,"Forming and Laying Bituminous concrete road at Vivekananda Street (Manthope Junction),Mother therasa Street,Udayar Palayam 1St Cross Street(Jawaharlal Nehru Street),Udayar Palayam 2nd Cross Street (Ganesh Street), Udayar Palayam 3rd Cross Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15330,Roads,Completed,NG-AMBATTUR,86,6700000,"Forming and Laying Bituminous concrete road at Manickam Pillai Cross Street, Dunlop Quarters Road,Krishna 2nd Cross Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/15339,Roads,Completed,NG-AMBATTUR,86,4900000,"Forming and Laying Cement concrete road with M30 Grade at Bharathidasan Nagar 1st Cross Street,Bharathidasan Nagar 2nd Cross Street,Bharathidasan Nagar 3rd Cross Street,Kalaivanar Nagar Cross Street,New Pillayar kovil 1st Cross Street,New Pillayar kovil 2nd Cross Street,Kuyavar Street,Lakshmi Amman Cross Street,Mettu Cross Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/15904,Roads,Completed,NG-AMBATTUR,86,2460000,"Laying 80mm Thick Cement Concrete Paver Block Road at School Street (Brindavan Strret),Bajani Kovil 1st Cross Street, Bajani Kovil 2nd Cross Street, Bajani Kovil 3rd Cross Street, Bajanai Kovil 4th Cross Street, Bajanai Kovil 5th Cross Street, Bajanai Kovil 6th Cross Street,Mettu Street Lane, Kannan Kovil Street (Kuppam), Kamarajar Street, Bharathiyar Street in Division-86, Unit-19, Zone-7.",MLACDS,7,2018-19,2019-20 NG/2018-19/16692,Parks,Completed,NG-AMBATTUR,86,874000,"Maintenance Estimate for Park at chelliamman Koil Pond Park (Including pond) in Dn-86, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16696,Parks,Completed,NG-AMBATTUR,86,198000,"Maintenance Estimate for Park at Gopal Swamy Nagar Park in Dn-86, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16699,Parks,Completed,NG-AMBATTUR,86,253000,"Maintenance Estimate for Park at sindhu Nathi Park in Dn-86, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16701,Parks,Completed,NG-AMBATTUR,86,243000,"Maintenance Estimate for Park at Children Park at the Junction of Bharathi Street(Kalidasan Street) in Dn-86, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16703,Parks,Completed,NG-AMBATTUR,86,411000,"Maintenance Estimate for Park at VGN Cosmo Polis Park in Dn-86, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16706,Parks,Completed,NG-AMBATTUR,86,556000,"Maintenance Estimate for Park at B- Sector Park in Dn-88, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/7979,Buildings,Completed,NG-AMBATTUR,86,712000,"Desilting of Side Drains at various streets in Division-86, Unit-19,Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/7981,Buildings,Completed,NG-AMBATTUR,86,2400000,"Repair Works to side drain side walls at chinna colony Various Streets in Division-86, Unit-19,Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/8891,Road Cut,Completed,NG-AMBATTUR,86,2230000,"Restoration of road cut made by TNSCB at Thirupathi Kodai Road in Division-86, Unit-19, Zone-7.",Deposit Works,7,2018-19,2019-20 Q/2018-19/17894,Roads,Completed,Q-Solid Waste Management,86,970000,"Formation of GSB Road Quarry dust finish from Vanagaram Main Road to Weigh Bridge at Athipet Transfer Station in Division 86, Unit 19, Zone 7.",Own Sources,7,2018-19,2019-20 Q/2018-19/17895,Roads,Completed,Q-Solid Waste Management,86,890000,"Formation of GSB Road Quarry dust finish from weigh Bridge to North east Corner at Athipet Transfer Station in Division 86, Unit 19, Zone 7.",Own Sources,7,2018-19,2019-20 BR/2018-19/6538,Roads,Completed,BR-Bus Route Roads,87,79000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DN.87, ZONE-07. (57/0693/2017-18) PACKAGE-11.",Deposit Works,7,2018-19,2018-19 L/2018-19/10202,Electrical,Completed,L-Electrical,87,295700,"Replacement of 4 Nos of Damaged KIOSK Pillar with 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units & Removal of Old Pillar At Various Locations In Div 87 in Ambattur Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/14759,Electrical,Completed,L-Electrical,87,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ICDS, Padasalai, Dr. Moorthy Nagar in Ward 87 Zone - VII . E.B Account Number : 04.009.1823",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6035,Electrical,Completed,L-Electrical,87,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office ,Church road TNP nagar Dn 87 Zone - VII . E.B Account Number : 039.001.6191",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6038,Electrical,Completed,L-Electrical,87,1515800,"ESTIMATE for Supply, Installation, Testing & Commissioning of 20 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Padi EOC Hospital Ward 87 Zone - VII . E.B Account Number : 039.001.6192",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/0336,Buildings,Completed,NG-AMBATTUR,87,79000,"Improvements to new motor and bore flushing chennai middle school at Dr.Moorthy nagar in div-87,unit-19,zone-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0537,Buildings,Completed,NG-AMBATTUR,87,102000,"PROVIDING ADDITINOAL STORE ROOM ICDS AT DR.MOORTHY NAGAR SCHOOL IN DIVISION-87,UNIT-19,ZONE-VII.",Own Sources,7,2018-19,2018-19 NG/2018-19/11556,Buildings,Completed,NG-AMBATTUR,87,134000,"IMPROVEMENTS TO THE AMMA UNAVAGAM AT M.TH. ROAD IN DIVISION-87,UNIT-19,ZONE-7.",Own Sources,7,2018-19,2020-21 NG/2018-19/11594,Buildings,Completed,NG-AMBATTUR,87,135000,"IMPROVEMENTS TO THE AMMA UNAVAGAM AT CHURCH ROAD IN DIVISION-87,UNIT-19,ZONE-7",Own Sources,7,2018-19,2020-21 NG/2018-19/13604,Roads,Completed,NG-AMBATTUR,87,237000,"RELAYING OF BT ROAD IN SATHYAVATHI NAGER 3RD STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13605,Roads,Completed,NG-AMBATTUR,87,407000,"RELAYING OF BT ROAD IN RATHINAM CROSS STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13606,Roads,Completed,NG-AMBATTUR,87,498000,"RELAYING OF BT ROAD IN SATHYAVATHI NAGAR 3RD STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13608,Roads,Completed,NG-AMBATTUR,87,358000,"RELAYING OF BT ROAD IN ASAITHAMBI STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13629,Roads,Completed,NG-AMBATTUR,87,542000,"RELAYING OF BT ROAD IN ARUNAGIRINATHAR STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13630,Roads,Completed,NG-AMBATTUR,87,423000,"RELAYING OF BT ROAD IN FLOWER STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13631,Roads,Completed,NG-AMBATTUR,87,313000,"RELAYING OF BT ROAD IN MARIYAMMAN KOIL STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13633,Roads,Completed,NG-AMBATTUR,87,203000,"RELAYING OF BT ROAD IN BAJANAI KOIL LANE STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13634,Roads,Completed,NG-AMBATTUR,87,464000,"RELAYING OF BT ROAD IN JUPITER STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13635,Roads,Completed,NG-AMBATTUR,87,408000,"RELAYING OF BT ROAD IN VENUS STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13636,Roads,Completed,NG-AMBATTUR,87,288000,"RELAYING OF BT ROAD IN RATHINAM STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13637,Roads,Completed,NG-AMBATTUR,87,936000,"RELAYING OF BT ROAD IN APPER STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13638,Roads,Completed,NG-AMBATTUR,87,508000,"RELAYING OF BT ROAD IN NEHRU STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13639,Roads,Completed,NG-AMBATTUR,87,1220000,"RELAYING OF BT ROAD IN VIVEKANANDAR STREET (SAKTHI NAGAR) IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13640,Roads,Completed,NG-AMBATTUR,87,1253000,"RELAYING OF BT ROAD IN AVVAI STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13641,Roads,Completed,NG-AMBATTUR,87,162000,"RELAYING OF BT ROAD IN YADHAVAL 1ST STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13642,Roads,Completed,NG-AMBATTUR,87,819000,"RELAYING OF BT ROAD IN BHARATHIYAR STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13644,Roads,Completed,NG-AMBATTUR,87,1160000,"RELAYING OF BT ROAD IN THIRUVALLUVAR STREET EXTN IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13645,Roads,Completed,NG-AMBATTUR,87,314000,"RELAYING OF BT ROAD IN SATHYAVATHI NAGAR 1ST STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13646,Roads,Completed,NG-AMBATTUR,87,1554000,"RELAYING OF BT ROAD IN VANNIYAR STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13647,Roads,Completed,NG-AMBATTUR,87,2420000,"RELAYING OF BT ROAD IN GUBERAGANAPATHY STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13650,Roads,Completed,NG-AMBATTUR,87,1370000,"RELAYING OF BT ROAD IN RAJA STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13651,Roads,Completed,NG-AMBATTUR,87,312000,"RELAYING OF BT ROAD IN POST OFFICE STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13653,Roads,Completed,NG-AMBATTUR,87,247000,"RELAYING OF BT ROAD IN VANNIAR 2ND STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13656,Roads,Completed,NG-AMBATTUR,87,6340000,"RELAYING OF BT ROAD IN CHURCH ROAD IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13657,Roads,Completed,NG-AMBATTUR,87,265000,"RELAYING OF BT ROAD IN MASUDHI STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13659,Roads,Completed,NG-AMBATTUR,87,239000,"RELAYING OF BT ROAD IN APPADURAI STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13660,Roads,Completed,NG-AMBATTUR,87,696000,"RELAYING OF BT ROAD IN EASWARAN KOIL THERU IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13662,Roads,Completed,NG-AMBATTUR,87,985000,"RELAYING OF BT ROAD IN KAMBER STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13663,Roads,Completed,NG-AMBATTUR,87,455000,"RELAYING OF BT ROAD IN MANIKAVASAKAR STREET JAGATHAMBIGAI NAGAR IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13665,Roads,Completed,NG-AMBATTUR,87,329000,"RELAYING OF BT ROAD IN THANIKASALAM STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13667,Roads,Completed,NG-AMBATTUR,87,1875000,"RELAYING OF BT ROAD IN YADHAVAL STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13670,Roads,Completed,NG-AMBATTUR,87,2500000,"RELAYING OF BT ROAD IN ELANGO NAGAR MAIN ROAD IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13671,Roads,Completed,NG-AMBATTUR,87,284000,"RELAYING OF BT ROAD IN BHARADHIDASAN STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13673,Roads,Completed,NG-AMBATTUR,87,300000,"RELAYING OF BT ROAD IN ELANGO NAGAR 2ND MAIN ROAD IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13676,Roads,Completed,NG-AMBATTUR,87,339000,"RELAYING OF BT ROAD IN SIRALAN STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/13677,Roads,Completed,NG-AMBATTUR,87,1017000,"RELAYING OF BT ROAD IN THIRUVALLUVAR STREET IN DN 87, UNIT19, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/15761,Buildings,Completed,NG-AMBATTUR,87,577000,"Laying of Cement Concrete Road at vanniyar cross street in Division-87, Unit-19, Zone-7,Under Ambattur MLA Constituency Fund.",MLACDS,7,2018-19,2019-20 NG/2018-19/15762,Buildings,Completed,NG-AMBATTUR,87,432000,"Laying of Cement Concrete Road at Bajanai koil 10th cross street in Division-87, Unit-19, Zone-7.Under Ambattur MLA Constituency Fund.",MLACDS,7,2018-19,2019-20 NG/2018-19/15763,Buildings,Completed,NG-AMBATTUR,87,526000,"Laying of Cement Concrete Road at Bajanai koil 11th cross street in Division-87, Unit-19, Zone-7. Under Ambattur MLA Constituency Fund.",MLACDS,7,2018-19,2020-21 NG/2018-19/7844,Storm Water Drain,Completed,NG-AMBATTUR,87,434000,"De-silting of SWD at various street in division-87, unit-19, zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/8452,Buildings,Completed,NG-AMBATTUR,87,1051000,"Repairing minor works to the existing side drain at various street in Div-87,Unit-19,Zone-7.",Own Sources,7,2018-19,2019-20 BR/2018-19/15723,Road Cut,Completed,BR-Bus Route Roads,88,942000,Restoration of OFC road cut made by Reliance Jio at various IRR roads in DIvision- 88 Unit-19 Zone-7 (Deposit code-57/0683/2017-18),Deposit Works,7,2018-19,2019-20 BR/2018-19/5939,Roads,Completed,BR-Bus Route Roads,88,1033000,"Attending Repairs to existing roads at Anna Nagar West (Ext) C Sector 9th Street in Dn-88, Zone-7",Grants,7,2018-19,2018-19 BR/2018-19/5942,Roads,Completed,BR-Bus Route Roads,88,1137000,"Attending Repairs to existing roads at Anna Nagar West (Ext) C Sector 6th Street in Dn-88, Zone-7",Grants,7,2018-19,2018-19 L/2018-19/11127,Electrical,Completed,L-Electrical,88,395500,"Replacement of 20 Nos. of Completely damaged 63 AMP/3 phase Analogue single dial Automatic Street Lighting ON /OFF Controlling TIMER UNITS At Various Locations In Div. 88,89&90 in Mogappair Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/12992,Electrical,Completed,L-Electrical,88,194500,"Proposal for fixing of 497 Nos of LED Fittings & Removal of 497 nos Sodium fittings At Various Locations In Div 88 in Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 NG/2018-19/0461,Buildings,Completed,NG-AMBATTUR,88,12540,Improvement work to ICDS at Kalaivanar Nagar,Own Sources,7,2018-19,2018-19 NG/2018-19/0462,Buildings,Completed,NG-AMBATTUR,88,12540,"IMPROVEMENT WORKS TO THE EXISTING ICDS CENTER AT MAHATMA GANDHI ROAD IN DN-88,UNIT-19,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/11692,Roads,Completed,NG-AMBATTUR,88,2272000,"Restoration of road cut made by CMWSSB at Park Road in Division-88, Unit-19, Zone-7.",Deposit Works,7,2018-19,2019-20 NG/2018-19/11694,Roads,Completed,NG-AMBATTUR,88,821000,"Road Cut Made by CMWSSB at Padavattamman Koil Street in Div-88, Unit-19, Zone-7",Deposit Works,7,2018-19,2019-20 NG/2018-19/11695,Roads,Completed,NG-AMBATTUR,88,579000,"Restoration of road cut made by TNEB at Park Road in Division-88, Unit-19, Zone-7.",Deposit Works,7,2018-19,2019-20 NG/2018-19/13306,Roads,Completed,NG-AMBATTUR,88,689000,"Relaying the BT Road at C-Sector 7th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13309,Roads,Completed,NG-AMBATTUR,88,699000,"Relaying the BT Road at C-Sector 8th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13310,Buildings,Completed,NG-AMBATTUR,88,3792000,"Relaying the BT Road at Park Road in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13312,Roads,Completed,NG-AMBATTUR,88,380000,"Relaying the BT Road at Kalaivanar Nagar Main road in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13313,Roads,Completed,NG-AMBATTUR,88,283000,"Relaying the BT Road at Thirumurugan Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13314,Roads,Completed,NG-AMBATTUR,88,971000,"Relaying the BT Road at Kamarajar Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13315,Roads,Completed,NG-AMBATTUR,88,737000,"Relaying the BT Road at TVS Nagar Main road in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13317,Roads,Completed,NG-AMBATTUR,88,140000,"Relaying the BT Road at TVS Nagar 1st Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13318,Roads,Completed,NG-AMBATTUR,88,332000,"Relaying the BT Road at TVS Nagar 3rd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13319,Roads,Completed,NG-AMBATTUR,88,484000,"Relaying the BT Road at TVS Nagar 5th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13356,Roads,Completed,NG-AMBATTUR,88,334000,"Relaying the BT Road at TVS Nagar 6th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13362,Roads,Completed,NG-AMBATTUR,88,278000,"Relaying the BT Road at TVS Nagar 7th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13363,Roads,Completed,NG-AMBATTUR,88,285000,"Relaying the BT Road at TVS Nagar 8th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13365,Roads,Completed,NG-AMBATTUR,88,205000,"Relaying the BT Road at TVS Nagar 9th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13375,Roads,Completed,NG-AMBATTUR,88,261000,"Relaying the BT Road at TVS Nagar 10th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13376,Roads,Completed,NG-AMBATTUR,88,755000,"Relaying the BT Road at North Mada Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13377,Roads,Completed,NG-AMBATTUR,88,1663000,"Relaying the BT Road at Relaying the BT Road at Padavattamman Koil Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13378,Buildings,Completed,NG-AMBATTUR,88,148000,"Relaying the BT Road at Anna 2nd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13379,Buildings,Completed,NG-AMBATTUR,88,228000,"Relaying the BT Road at UR Nagar Extn Main Road in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13380,Buildings,Completed,NG-AMBATTUR,88,92000,"Relaying the BT Road at UR Nagar Extn 1st Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13381,Roads,Completed,NG-AMBATTUR,88,235000,"Relaying the BT Road at UR Nagar Extn 2nd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13382,Roads,Completed,NG-AMBATTUR,88,339000,"Relaying the BT Road at UR Nagar Main Road in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13384,Roads,Completed,NG-AMBATTUR,88,152000,"Relaying the BT Road at UR Nagar 1st Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13400,Roads,Completed,NG-AMBATTUR,88,61000,"Relaying the BT Road at UR Nagar 2nd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13401,Roads,Completed,NG-AMBATTUR,88,99000,"Relaying the BT Road at UR Nagar 3rd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13407,Roads,Completed,NG-AMBATTUR,88,538000,"Relaying the BT Road at Balaji Nagar 1st Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13408,Roads,Completed,NG-AMBATTUR,88,527000,"Relaying the BT Road at Balaji Nagar 2nd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13409,Roads,Completed,NG-AMBATTUR,88,326000,"Relaying the BT Road at Balaji Nagar 3rd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13410,Roads,Completed,NG-AMBATTUR,88,759000,"Relaying the BT Road at Pandurangapuram Main Road in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13411,Roads,Completed,NG-AMBATTUR,88,465000,"Relaying the BT Road at Jawaharlal Nehru Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13412,Roads,Completed,NG-AMBATTUR,88,310000,"Relaying the BT Road at Lokmanya Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13415,Roads,Completed,NG-AMBATTUR,88,196000,"Relaying the BT Road at Kambar Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13417,Roads,Completed,NG-AMBATTUR,88,591000,"Relaying the BT Road at Thiruvika Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13418,Roads,Completed,NG-AMBATTUR,88,579000,"Relaying the BT Road at Rajendra Prasad Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13420,Roads,Completed,NG-AMBATTUR,88,553000,"Relaying the BT Road at Rajarajacholan Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13421,Roads,Completed,NG-AMBATTUR,88,277000,"Relaying the BT Road at Nethaji Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13496,Roads,Completed,NG-AMBATTUR,88,243000,"Relaying the BT Road at Bharathiyar Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13497,Roads,Completed,NG-AMBATTUR,88,252000,"Relaying the BT Road at Jawahar Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13498,Roads,Completed,NG-AMBATTUR,88,174000,"Relaying the BT Road at Gandhi Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13499,Roads,Completed,NG-AMBATTUR,88,334000,"Relaying the BT Road at Thiruvalleswarar Colony Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13500,Roads,Completed,NG-AMBATTUR,88,237000,"Relaying the BT Road at VOC Street Devar Nagar in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13501,Roads,Completed,NG-AMBATTUR,88,129000,"Relaying the BT Road at Vasantham Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13508,Roads,Completed,NG-AMBATTUR,88,933000,"Relaying the BT Road at THENDRAL STREET in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13509,Roads,Completed,NG-AMBATTUR,88,238000,"Relaying the BT Road at KURUNJI STREET in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13510,Roads,Completed,NG-AMBATTUR,88,543000,"Relaying the BT Road at Pillayar Koil Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13572,Roads,Completed,NG-AMBATTUR,88,306000,"Relaying the BT Road at Rukmani Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13573,Roads,Completed,NG-AMBATTUR,88,369000,"Relaying the BT Road at Mullai Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13574,Roads,Completed,NG-AMBATTUR,88,131000,"Relaying the BT Road at AP Plot 1st Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13577,Roads,Completed,NG-AMBATTUR,88,282000,"Relaying the BT Road at AP Plot 2nd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13578,Buildings,Completed,NG-AMBATTUR,88,287000,"Relaying the BT Road at AP Plot 6th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13581,Roads,Completed,NG-AMBATTUR,88,391000,"Relaying the BT Road at B-Sector 1st Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13584,Roads,Completed,NG-AMBATTUR,88,188000,"Relaying the BT Road at B-Sector 2nd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13585,Roads,Completed,NG-AMBATTUR,88,235000,"Relaying the BT Road at B-Sector 3rd Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13586,Roads,Completed,NG-AMBATTUR,88,477000,"Relaying the BT Road at B-Sector 4th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13587,Roads,Completed,NG-AMBATTUR,88,998000,"Relaying the BT Road at B-Sector 5th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13590,Roads,Completed,NG-AMBATTUR,88,123000,"Relaying the BT Road at B-Sector 7th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13592,Roads,Completed,NG-AMBATTUR,88,1242000,"Relaying the BT Road at B-Sector 8th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13593,Roads,Completed,NG-AMBATTUR,88,1203000,"Relaying the BT Road at B-Sector 2nd Avenue in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13595,Roads,Completed,NG-AMBATTUR,88,339000,"Relaying the BT Road at 1st Avenue in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13598,Roads,Completed,NG-AMBATTUR,88,980000,"Relaying the BT Road at AP Plot 7th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13599,Buildings,Completed,NG-AMBATTUR,88,812000,"Relaying the BT Road at AP Plot 9th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13648,Roads,Completed,NG-AMBATTUR,88,829000,"Relaying the BT Road at C-Sector 10th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13652,Roads,Completed,NG-AMBATTUR,88,834000,"Relaying the BT Road at C-Sector 11th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13654,Roads,Completed,NG-AMBATTUR,88,211000,"Relaying the BT Road at C-Sector 12th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13658,Roads,Completed,NG-AMBATTUR,88,387000,"Relaying the BT Road at C-Sector 13th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13661,Roads,Completed,NG-AMBATTUR,88,469000,"Relaying the BT Road at C-Sector 14th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13664,Roads,Completed,NG-AMBATTUR,88,758000,"Relaying the BT Road at C-Sector 15th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13669,Buildings,Completed,NG-AMBATTUR,88,1240000,"Relaying the BT Road at 3rd Avenue in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13674,Roads,Completed,NG-AMBATTUR,88,318000,"Relaying the BT Road at D-Sector 5th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13678,Buildings,Completed,NG-AMBATTUR,88,231000,"Relaying the BT Road at D-Sector 6th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13679,Roads,Completed,NG-AMBATTUR,88,252000,"Relaying the BT Road at D-Sector 7th Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13681,Roads,Completed,NG-AMBATTUR,88,372000,"Relaying the BT Road at D-Sector 8th Street,in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13682,Roads,Completed,NG-AMBATTUR,88,261000,"Relaying the BT Road at Thiruvalluvar Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13683,Roads,Completed,NG-AMBATTUR,88,652000,"Relaying the BT Road at School Road in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13784,Roads,Completed,NG-AMBATTUR,88,751000,"Formation & laying of CC Road at Krishnan Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13785,Roads,Completed,NG-AMBATTUR,88,471000,"Relaying the CC Road at Madurai veeran Cross Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/13786,Roads,Completed,NG-AMBATTUR,88,170000,"Relaying the CC Road at TVS Nagar 4th Cross Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16705,Parks,Completed,NG-AMBATTUR,88,204000,"Maintenance Estimate for Park at A.P.flats Children's Park in Dn-88, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16707,Parks,Completed,NG-AMBATTUR,88,605000,"Maintenance Estimate for Park at C- Sector Park in Dn-88, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/16708,Parks,Completed,NG-AMBATTUR,88,985000,"Maintenance Estimate for Park at Millienium Park in Dn-88, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/7549,Roads,Completed,NG-AMBATTUR,88,276000,"Desilting side Drain at Various Street in Dn-88, Unit-19, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/7551,Roads,Completed,NG-AMBATTUR,88,506000,"Repair works to Culvert At North mada 5th Street, North mada Street 3rd Street,North mada Street 3rd Street, Karumariyamman koil street In Division-88, Unit-19,Zone-7.",Own Sources,7,2018-19,2019-20 BR/2018-19/15727,Road Cut,Completed,BR-Bus Route Roads,89,591000,Restoration of OFC road cut made by Reliance Jio at various IRR roads in Division-89 Unit-20 Zone-7 (Deposit code-57/0683/2017-18),Deposit Works,7,2018-19,2019-20 L/2018-19/10942,Electrical,Completed,L-Electrical,89,199500,"Fixing of 510 Nos of LED Fittings & Removal of 510 nos of Sodium fittings At Various Locations In Div 89, 90 ,92 and 93 in Mogappair Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/11042,Electrical,Completed,L-Electrical,89,197800,"Replacement of 10 Nos. of Completely damaged 63 AMP/3 phase Analogue single dial Automatic Street Lighting ON /OFF Controlling TIMER UNITS At Various Locations In Div. 89 ,90,92&93 in Mogappair Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/12300,Electrical,Completed,L-Electrical,89,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office -89, elango nagar in Div-89, Zone-VII",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/12926,Electrical,Completed,L-Electrical,89,81100,"Provision for New Cable Replacement of 4X16 SQ.MM UG.Aluminium Cable of 55 MTRS at 120 Feet Road,Golden colony Junction in Division 89, Mogappair section , Zone 7",Own Sources,7,2018-19,2019-20 L/2018-19/5979,Electrical,Completed,L-Electrical,89,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Primary Health Centre, TVS Colony in Div-89, Zone-VII .(E.B.Account no. - 432.011.617 ).",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/11549,Buildings,Completed,NG-AMBATTUR,89,210000,ADDITIONAL IMPROVEMENT WORKS TO THE EXISTING AMMA UNAVAGAM IN DIVISION-89 UNIT-20 ZONE-7(AMBATTUR).,Own Sources,7,2018-19,2019-20 NG/2018-19/13627,Roads,Completed,NG-AMBATTUR,89,451000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT AKSHAYA COLONY 4th AVENUE IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/13628,Roads,Completed,NG-AMBATTUR,89,847000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SRINIVASA NAGAR BHARATHIYAR STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15078,Storm Water Drain,Completed,NG-AMBATTUR,89,781000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT GOLDEN COLONY IN DN 89, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15088,Storm Water Drain,Completed,NG-AMBATTUR,89,352000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT TVS COLONY IN DN 89, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15090,Storm Water Drain,Completed,NG-AMBATTUR,89,279000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT OFFICERS COLONY IN DN 89, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15093,Storm Water Drain,Completed,NG-AMBATTUR,89,264000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT AKSHAYA COLONY IN DN 89, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15094,Storm Water Drain,Completed,NG-AMBATTUR,89,566000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT T.V.S AVENUE MAIN ROAD IN DN 89, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15098,Storm Water Drain,Completed,NG-AMBATTUR,89,552000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT ASIAD COLONY IN DN 90, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15099,Storm Water Drain,Completed,NG-AMBATTUR,89,549000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT GOLDEN JUBLEE IN DN 90, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15102,Storm Water Drain,Completed,NG-AMBATTUR,89,210000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT WELCOME COLONY BLOCK NO 49-A AND PARK ROAD IN DN 89, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15132,Storm Water Drain,Completed,NG-AMBATTUR,89,227000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT Veeramamunivar Park IN DN 93, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2665,Roads,Completed,NG-AMBATTUR,89,564000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT OLYPIC COLONY 2ND MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2666,Roads,Completed,NG-AMBATTUR,89,395000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BAKIATHAMMAN NAGAR 3RD CROSS STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2668,Roads,Completed,NG-AMBATTUR,89,395000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BAKIATHAMMAN NAGAR 5TH CROSS STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2669,Roads,Completed,NG-AMBATTUR,89,1127000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SATHYA NAGAR 1ST MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2670,Roads,Completed,NG-AMBATTUR,89,1127000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SATYA NAGAR 2ND MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2671,Roads,Completed,NG-AMBATTUR,89,459000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SATHYA NAGAR 3RD CROSS STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2672,Roads,Completed,NG-AMBATTUR,89,1503000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SATHYA NAGAR CHURCH STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2673,Roads,Completed,NG-AMBATTUR,89,1052000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SRINIVASA NAGAR NEHRU STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2678,Roads,Completed,NG-AMBATTUR,89,1774000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SRINIVASA NAGAR PERIYAR MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2679,Roads,Completed,NG-AMBATTUR,89,385000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SRINIVASA NAGAR KAMARAJAR 1ST CROSS STREET PERIYAR MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2680,Roads,Completed,NG-AMBATTUR,89,161000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SRINIVASA NAGAR KAMARAJAR 3RD CROSS STREET PERIYAR MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2681,Roads,Completed,NG-AMBATTUR,89,154000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SRINIVASA NAGAR KAMARAJAR 4TH CROSS STREET PERIYAR MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2683,Roads,Completed,NG-AMBATTUR,89,1688000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT GOLDEN COLONY 1ST MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2684,Roads,Completed,NG-AMBATTUR,89,2143000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT T.S. KRISHNA NAGAR MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2685,Roads,Completed,NG-AMBATTUR,89,3572000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT T.V.S AVENUE MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2686,Roads,Completed,NG-AMBATTUR,89,533000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT T.V.S AVENUE 39TH STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2687,Roads,Completed,NG-AMBATTUR,89,1242000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT T.V.S COLONY 1ST MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2688,Roads,Completed,NG-AMBATTUR,89,533000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT T.V.S COLONY 52ND STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2689,Roads,Completed,NG-AMBATTUR,89,733000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT THIRUVALLUVAR NAGAR 1ST STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2691,Roads,Completed,NG-AMBATTUR,89,658000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT THIRUVALLUVAR NAGAR 2ND STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2692,Roads,Completed,NG-AMBATTUR,89,1196000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT KANIAPPAN STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2693,Roads,Completed,NG-AMBATTUR,89,666000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT WEST END COLONY 19TH STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2694,Roads,Completed,NG-AMBATTUR,89,1194000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT TVS COLONY 57TH STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2695,Roads,Completed,NG-AMBATTUR,89,2143000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BHAKIYATHAMMAL NAGAR MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2696,Roads,Completed,NG-AMBATTUR,89,1637000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT T.V.S COLONY 2ND MAIN ROAD IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4029,Roads,Completed,NG-AMBATTUR,89,982000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT T.V.S COLONY 58TH STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4030,Roads,Completed,NG-AMBATTUR,89,948000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT S.M. NARAYANA NAGAR IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4031,Roads,Completed,NG-AMBATTUR,89,989000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT T.V.S COLONY 45TH STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4032,Roads,Completed,NG-AMBATTUR,89,491000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT SRINIVASA NAGAR PERIYAR 4TH CROSS STREET IN DN 89, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/5536,Parks,Completed,NG-AMBATTUR,89,495000,"IMPROVEMENTS TO PLAY GROUND AT ELANGO NAGAR IN DIVISION-89, UNIT-20, ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/8213,Storm Water Drain,Completed,NG-AMBATTUR,89,406000,REPAIRS WORKS TO THE EXISTING ROAD SIDE DRAIN AND STORM WATER DRAIN AT VARIOUS STREET IN DIVISION- 89 UNIT-20 ZONE-7(AMBATTUR),Own Sources,7,2018-19,2019-20 NG/2018-19/9246,Storm Water Drain,Completed,NG-AMBATTUR,89,390000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION- 89 UNIT-20 ZONE-7(AMBATTUR),Own Sources,7,2018-19,2019-20 BR/2018-19/15705,Roads,Completed,BR-Bus Route Roads,90,681000,Restoration of OFC road cut made by Reliance at various IRR roads in Division-90 Unit-20 Zone-7 (Deposit Code-57/0053/2018-19),Deposit Works,7,2018-19,2019-20 BR/2018-19/5437,Roads,Completed,BR-Bus Route Roads,90,15017000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Padikuppam Main Road in Dn-90 & 93, Zone - VII",Grants,7,2018-19,2019-20 L/2018-19/12870,Electrical,Completed,L-Electrical,90,199500,"Fixing of 510 Nos. of LED Fittings & Removal of 510 nos. of Sodium fittings At Various Locations In Div 89, 90 and 93 in Mogappair Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 L/2018-19/5982,Electrical,Completed,L-Electrical,90,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office -90, padipudhu nagar in Div-90, Zone-VII(E.B.Account no-432.017.2730 )",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/9953,Electrical,Completed,L-Electrical,90,496300,"Replacement of 8 Nos of Damaged KIOSK Pillar with 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units & Removal of Old Pillar At Various Locations In Div. 88,89 & 90 in Mogappair Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 NG/2018-19/11532,Buildings,Completed,NG-AMBATTUR,90,270000,"Additional Improvements Work to Amma Unavagam At Padiputhu Nagar 3rd Street & Collector Nagar in Div-90, Unit-20, Zone-7.",Own Sources,7,2018-19,2019-20 NG/2018-19/15101,Storm Water Drain,Completed,NG-AMBATTUR,90,532000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT COLLECTOR NAGAR IN DN 89, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2880,Roads,Completed,NG-AMBATTUR,90,2293000,"Forming of New BT Road at Thamaraikudiyiruppu in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2889,Roads,Completed,NG-AMBATTUR,90,2987000,"Relaying of BT Road at D Sector 9th Street in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2892,Roads,Completed,NG-AMBATTUR,90,4513000,"Relaying of BT Road at D-Sector 10th st and B.T road laying after restoration at Anbu Street, Bharathi Street, Valluvar Street, Nethaji Street, Kannadasan Street, V.O.C Street, Kambar Street, Vivekanandhar Street and Padiputhu Nagar Koil street in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2895,Roads,Completed,NG-AMBATTUR,90,1122000,"Relaying of BT Road at D Sector 11th Street in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2900,Roads,Completed,NG-AMBATTUR,90,3563000,"Relaying of BT Road at 5th Avenue in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2901,Roads,Completed,NG-AMBATTUR,90,511000,"Relaying of BT Road at Balaji Nagar 1st Street in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2904,Roads,Completed,NG-AMBATTUR,90,1122000,"Relaying of BT Road at Balaji Nagar 2nd Street in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2906,Roads,Completed,NG-AMBATTUR,90,307000,"Relaying of BT Road at Balaji Nagar 3rd Street in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2907,Roads,Completed,NG-AMBATTUR,90,111000,"Relaying of BT Road at Balaji Nagar 3rd Cross Street in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2910,Roads,Completed,NG-AMBATTUR,90,3925000,"Relaying of BT Road at East Main Road in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2917,Roads,Completed,NG-AMBATTUR,90,4835000,"Relaying of BT Road at Park Road in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/2953,Roads,Completed,NG-AMBATTUR,90,1339000,"Relaying of BT Road at Periyar Nagar in Div-90, Unit-20, Zone-7",Own Sources,7,2018-19,2019-20 NG/2018-19/7329,Storm Water Drain,Completed,NG-AMBATTUR,90,517000,"DESILTING TO THE EXISTING ROAD SIDE DRAIN AND STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION 90, UNIT - 20, ZONE-7",Own Sources,7,2018-19,2019-20 P/2018-19/11985,Parks,Completed,P-Parks and Playfields,90,5779824,"FORMATION OF NEW PARK AT TNHB, PADIKUPPAM ROAD (S.NO.2381 PT) IN DN-90 , ZONE -7",Grants,7,2018-19,2020-21 BR/2018-19/10662,Road Cut,Completed,BR-Bus Route Roads,91,1110000,"Restoration of roadcut made by CMWSSB at wavin road , Mogapair west main and Bharathi Salai in Dn -91, Zone -7",Deposit Works,7,2018-19,2018-19 BR/2018-19/10669,Road Cut,Completed,BR-Bus Route Roads,91,990000,"Restoration of roadcut made by CMWSSB at Mogapair west 3rd main in Dn -91, Zone -7",Deposit Works,7,2018-19,2018-19 BR/2018-19/10670,Road Cut,Completed,BR-Bus Route Roads,91,880000,"Restoration of roadcut made by CMWSSB at Venugopal street (from the jn of shravan street to the jn of Corporation school) in Dn -92, Zone -7",Deposit Works,7,2018-19,2019-20 BR/2018-19/10672,Road Cut,Completed,BR-Bus Route Roads,91,970000,"Restoration of roadcut made by CMWSSB at Church street in Dn -92, Zone -7",Deposit Works,7,2018-19,2019-20 BR/2018-19/6537,Roads,Completed,BR-Bus Route Roads,91,160000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DN.91, ZONE-07. (57/0667/2017-18) PACKAGE-11.",Deposit Works,7,2018-19,2018-19 L/2018-19/13761,Electrical,Completed,L-Electrical,91,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at mogapair west community hall . Div - 91, Zone -7 EB NO:043.008.2",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6047,Electrical,Completed,L-Electrical,91,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital kalamegam salai ,mogapair west Health Post . Div - 91, Zone -/ EB NO:043.001.136",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/6049,Electrical,Completed,L-Electrical,91,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division 91 office, 1st Main Road Eri Scheme Mogappair in Div. 91 Zone-VII. EB.NO:431-012-4186",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/8924,Electrical,Completed,L-Electrical,91,653200,Supply and replacement of 1041trs of 4x16sqmm UG Cables at Chronically fault occuring locations at Service Road in div 91 zone VII area.,Own Sources,7,2018-19,2018-19 L/2018-19/9930,Electrical,Completed,L-Electrical,91,253800,"Replacement of 4Nos of Damaged KIOSK Pillar with 63 Amp / 3phase Analogue Single Dial Automatic Street Lighting On / Off Controlling Timer Units & Removal of Old Pillar At Various Locations In Div. 81,86 & 91 in Banu nagar Section, Zone-VII, Ambattur",Own Sources,7,2018-19,2019-20 NG/2018-19/10996,Buildings,Completed,NG-AMBATTUR,91,412000,"MINOR REPAIR WORKS TO THE EXISTING SWD AND MANHOLE DOORS AT VARIOUS STREETS IN DN 91, UNIT 20, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/11023,Buildings,Completed,NG-AMBATTUR,91,346000,IMPROVEMENT WORKS TO THE EXISTING NNMP SHED AT 1ST BLOCK IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2018-19,2018-19 NG/2018-19/11039,Buildings,Completed,NG-AMBATTUR,91,845380,IMPROVEMENT WORKS TO THE EXISTING CHENNAI MIDDLE SCHOOL AT 7TH BLOCK IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2018-19,2018-19 NG/2018-19/11547,Buildings,Completed,NG-AMBATTUR,91,270000,ADDITIONAL IMPROVEMENT WORKS TO THE EXISTING AMMA UNAVAGAM(6TH BLOCK AND REDDIPALAYAM ) IN DIVISION-91 UNIT-20 ZONE-7(AMBATTUR).,Own Sources,7,2018-19,2019-20 NG/2018-19/15106,Storm Water Drain,Completed,NG-AMBATTUR,91,237000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT JESWANTH NAGAR PHASE I IN DN 91, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15109,Storm Water Drain,Completed,NG-AMBATTUR,91,567000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT MOGAPPAIR ERI SCHEME 8TH STREET IN DN 91, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15110,Storm Water Drain,Completed,NG-AMBATTUR,91,592000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT MOGAPPAIR WEST BUS STAND IN DN 91, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15112,Storm Water Drain,Completed,NG-AMBATTUR,91,205000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT TRI STAR PARK IN DN 91, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15113,Storm Water Drain,Completed,NG-AMBATTUR,91,241000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT JASWANTH NAGAR PHASE - II IN DN 91, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15128,Storm Water Drain,Completed,NG-AMBATTUR,91,242000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT AIBEA NAGAR IN DN 91, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15129,Storm Water Drain,Completed,NG-AMBATTUR,91,231000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR ATMOGAPPAIR ERI SCHEME 1st STREET IN DN 91, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2198,Buildings,Completed,NG-AMBATTUR,91,346000,IMPROVEMENT WORKS TO THE EXISTING NNMP SHED AT 3RD BLOCK IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2018-19,2018-19 NG/2018-19/2697,Roads,Completed,NG-AMBATTUR,91,1158000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT jems park 1st main road IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2698,Roads,Completed,NG-AMBATTUR,91,452000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 5TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2699,Roads,Completed,NG-AMBATTUR,91,187000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 6TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2700,Roads,Completed,NG-AMBATTUR,91,886000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 7TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2701,Roads,Completed,NG-AMBATTUR,91,661000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 8TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2702,Roads,Completed,NG-AMBATTUR,91,900000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 10TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2703,Roads,Completed,NG-AMBATTUR,91,452000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 1ST CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2704,Roads,Completed,NG-AMBATTUR,91,452000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 2ND CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2705,Roads,Completed,NG-AMBATTUR,91,402000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 3RD CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2706,Roads,Completed,NG-AMBATTUR,91,433000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 4TH CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2707,Roads,Completed,NG-AMBATTUR,91,452000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 5TH CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2708,Roads,Completed,NG-AMBATTUR,91,683000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT TNHB 3RD BLOCK SEEVAGA CHINTHAMANI STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2709,Roads,Completed,NG-AMBATTUR,91,415000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT TNHB 3RD BLOCK 6TH STREET ( BALA MURUGAN KOIL STREET) IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2710,Roads,Completed,NG-AMBATTUR,91,464000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT TNHB 6TH BLOCK GANGAI AMMAN KOIL STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2711,Roads,Completed,NG-AMBATTUR,91,505000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT TNHB 7TH BLOCK KARUMARIAMMAN KOIL STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2712,Roads,Completed,NG-AMBATTUR,91,1175000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT TNHB 7TH BLOCK SCHOOL ROAD IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2713,Roads,Completed,NG-AMBATTUR,91,1339000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT VGN AVENUE PADMA STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2716,Roads,Completed,NG-AMBATTUR,91,413000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT VGN AVENUE PRADISH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2717,Roads,Completed,NG-AMBATTUR,91,141000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME LIG 15TH CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2718,Roads,Completed,NG-AMBATTUR,91,255000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME LIG 16TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2719,Roads,Completed,NG-AMBATTUR,91,332000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME LIG 17TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2720,Roads,Completed,NG-AMBATTUR,91,438000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME LIG 18TH STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2721,Roads,Completed,NG-AMBATTUR,91,939000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 8TH CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2722,Roads,Completed,NG-AMBATTUR,91,1090000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT AIBEA NAGAR MAIN ROAD IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2723,Roads,Completed,NG-AMBATTUR,91,676000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT JESWANTH NAGAR 1ST STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2724,Roads,Completed,NG-AMBATTUR,91,273000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT JESWANTH NAGAR 2ND STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2725,Roads,Completed,NG-AMBATTUR,91,262000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT JESWANTH NAGAR 3RD STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4027,Roads,Completed,NG-AMBATTUR,91,949000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 13TH CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4028,Roads,Completed,NG-AMBATTUR,91,615000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT MOGAPPAIR ERI SCHEME 14TH CROSS STREET IN DN 91, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/9244,Storm Water Drain,Completed,NG-AMBATTUR,91,374000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION- 91 UNIT-20 ZONE-7(AMBATTUR),Own Sources,7,2018-19,2019-20 BR/2018-19/15706,Road Cut,Completed,BR-Bus Route Roads,92,1111000,Restoration of OFC road cut made by Reliance at various IRR roads in Division-92 Unit-20 Zone-7 (Deposit Code-57/0053/2018-19),Deposit Works,7,2018-19,2019-20 BR/2018-19/1976,Road Cut,Completed,BR-Bus Route Roads,92,1440000,"Restoration of roadcut Made by CMWSSB at Vellalar Street in Dn - 92, Zone - 7(Chellan No; BR/2017-18/0007977)",Deposit Works,7,2018-19,2018-19 BR/2018-19/5546,Road Cut,Completed,BR-Bus Route Roads,92,2358000,Restoration of Roadcut made by OFC Operators at various Bus Route Roads and Interior Roads in Zone - 7,Deposit Works,7,2018-19,2019-20 BR/2018-19/5558,Roads,Completed,BR-Bus Route Roads,92,10163000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Church Road in Dn-92, Zone - VII",Grants,7,2018-19,2019-20 D/2018-19/9929,Storm Water Drain,Completed,D-Storm Water Drains,92,22727000,"Construction of Storm Water Drain at Par Salai and Pattinathar Salai in Dn. - 92,Zone - 7 in Package - 26",Grants,7,2018-19,2019-20 L/2018-19/11043,Electrical,Completed,L-Electrical,92,199000,"Provision for Erection of 6NOS. of New 6M Lamp post with one Mtr Single Straight Bracket, with Hot DIP ZINC Galvanising with Supply of 6NOS of Departmental Fitting at TNHB-Goverment Employees Quarters Road, WARD 92, ZONE -7",Own Sources,7,2018-19,2019-20 NG/2018-19/0002,Roads,Completed,NG-AMBATTUR,92,150000,IMPROVEMENT WORKS TO THE EXISTING ICDS CENTER AT BHARATHIDASAN SALAI IN DIV 92 UNIT 20 ZONE 07,Own Sources,7,2018-19,2018-19 NG/2018-19/0540,Buildings,Completed,NG-AMBATTUR,92,150000,IMPROVEMENT WORKS TO THE EXISTING ICDS CENTER AT ELANGO SALAI 10TH BLOCK IN DIV 92 UNIT 20 ZONE 7 AMBATTUR,Own Sources,7,2018-19,2018-19 NG/2018-19/11018,Buildings,Completed,NG-AMBATTUR,92,410000,"MINOR REPAIR WORKS TO THE EXISTING SWD AND MAN HOLE DOORS AT VARIOUS STREETS IN DN 92, UNIT 20, ZONE 7",Own Sources,7,2018-19,2019-20 NG/2018-19/11548,Buildings,Completed,NG-AMBATTUR,92,270000,ADDITIONAL IMPROVEMENT WORKS TO THE EXISTING AMMA UNAVAGAM(PATTINATHAR SALAI AND KANNADASAN SALAI) IN DIVISION-92 UNIT-20 ZONE-7(AMBATTUR).,Own Sources,7,2018-19,2019-20 NG/2018-19/15130,Storm Water Drain,Completed,NG-AMBATTUR,92,298000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT EB ROAD IN DN 92, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/15131,Storm Water Drain,Completed,NG-AMBATTUR,92,2047000,"ANNUAL MAINTENANCE OF GCC PARKS FOR ONE YEAR AT ANNA PARK (MANGAL ERI) IN DN 92, UNIT 20, ZONE VII",Own Sources,7,2018-19,2019-20 NG/2018-19/1941,Buildings,Completed,NG-AMBATTUR,92,276000,IMPROVEMENT WORKS TO THE EXISTING NNMP SHED AT PATTINATHAR SALAI IN DIVISION-92 UNIT-20 ZONE-07,Own Sources,7,2018-19,2018-19 NG/2018-19/2260,Buildings,Completed,NG-AMBATTUR,92,150000,IMPROVEMENT WORKS TO THE EXISTING ICDS CENTER AT BAJANAI KOIL STREET IN DIV 92 UNIT 20 ZONE 7 AMBATTUR,Own Sources,7,2018-19,2018-19 NG/2018-19/2263,Buildings,Completed,NG-AMBATTUR,92,150000,IMPROVEMENT WORKS TO THE EXISTING ICDS CENTER AT VALLALAR STREET IN DIV 92 UNIT 20 ZONE 7 AMBATTUR,Own Sources,7,2018-19,2018-19 NG/2018-19/2265,Buildings,Completed,NG-AMBATTUR,92,150000,IMPROVEMENT WORKS TO THE EXISTING ICDS CENTER AT KANNADASSAN SALAI 11TH BLOCK IN DIV 92 UNIT 20 ZONE 7 AMBATTUR,Own Sources,7,2018-19,2018-19 NG/2018-19/2726,Roads,Completed,NG-AMBATTUR,92,1000000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BARATHIDASAN SALAI MAIN ROAD IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2727,Roads,Completed,NG-AMBATTUR,92,2568000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT VEERAMAMUNIVAR SALAI IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2728,Roads,Completed,NG-AMBATTUR,92,300000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BHARATHIDASAN 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2730,Roads,Completed,NG-AMBATTUR,92,1152000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT KARNAN 1ST STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2731,Roads,Completed,NG-AMBATTUR,92,491000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOHANRAM NAGAR 1ST STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2732,Roads,Completed,NG-AMBATTUR,92,332000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOHANRAM NAGAR 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2733,Roads,Completed,NG-AMBATTUR,92,673000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOHANRAM NAGAR 3RD STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2734,Roads,Completed,NG-AMBATTUR,92,3280000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MUGAPPAIR ROAD IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2735,Roads,Completed,NG-AMBATTUR,92,327000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SPARTAN NAGAR 1ST STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2736,Roads,Completed,NG-AMBATTUR,92,2548000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT EB SALAI IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2737,Roads,Completed,NG-AMBATTUR,92,639000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT ORI SALAI IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2738,Roads,Completed,NG-AMBATTUR,92,532000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT 10TH BLOCK ELANGO SALAI MAIN ROAD IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/2739,Roads,Completed,NG-AMBATTUR,92,1044000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT KANNADASAN SALAI MAIN ROAD IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2740,Roads,Completed,NG-AMBATTUR,92,1759000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SEETHAKATHI SALAI MAIN ROAD IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2741,Roads,Completed,NG-AMBATTUR,92,3653000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SEETHAKATHI SALAI 1ST STREET, KAMADHENU STREET, 1ST & 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2742,Roads,Completed,NG-AMBATTUR,92,221000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SEETHAKATHI SALAI 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2743,Roads,Completed,NG-AMBATTUR,92,319000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SEETHAKATHI SALAI 3RD STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2744,Roads,Completed,NG-AMBATTUR,92,867000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SPARTAN NAGAR 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2745,Roads,Completed,NG-AMBATTUR,92,262000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SPARTAN NAGAR 4TH STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2751,Roads,Completed,NG-AMBATTUR,92,539000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BALU NAGAR 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2752,Roads,Completed,NG-AMBATTUR,92,714000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BALU NAGAR 3RD STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2753,Roads,Completed,NG-AMBATTUR,92,199000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT BALU NAGAR 4TH STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2755,Roads,Completed,NG-AMBATTUR,92,430000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT MOHANRAM NAGAR 5TH STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2756,Roads,Completed,NG-AMBATTUR,92,486000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT V.G.P NAGAR1ST STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2759,Roads,Completed,NG-AMBATTUR,92,381000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT VGP NAGAR 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2760,Roads,Completed,NG-AMBATTUR,92,318000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT VGP NAGAR 3RD STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2762,Roads,Completed,NG-AMBATTUR,92,1271000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT VGP NAGAR 4TH STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2763,Roads,Completed,NG-AMBATTUR,92,674000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT JUSTICE KRISHNAN 1ST STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2765,Roads,Completed,NG-AMBATTUR,92,265000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT JUSTICE KRISHNAN 2ND STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2766,Roads,Completed,NG-AMBATTUR,92,265000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT JUSTICE KRISHNAN 3RD STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/2768,Roads,Completed,NG-AMBATTUR,92,972000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT EVK SAMPATH SALAI CROSS STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4016,Roads,Completed,NG-AMBATTUR,92,4284000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT PANEER NAGAR MAIN ROAD IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4017,Roads,Completed,NG-AMBATTUR,92,671000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT MOHAN RAM 4TH STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4018,Roads,Completed,NG-AMBATTUR,92,2852000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT PARI SALAI IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4019,Roads,Completed,NG-AMBATTUR,92,480000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT PANNEER NAGAR GURUNATH STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4020,Roads,Completed,NG-AMBATTUR,92,309000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT SPARTAN NAGAR 6TH STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2019-20 NG/2018-19/4021,Roads,Completed,NG-AMBATTUR,92,1760000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT 11TH BLOCK BHARATHIDASAN SALAI IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4022,Roads,Completed,NG-AMBATTUR,92,676000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT THIRUVALLUVAR CROSS STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4023,Roads,Completed,NG-AMBATTUR,92,2847000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT EVK SAMPATH SALAI IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4024,Roads,Completed,NG-AMBATTUR,92,676000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT VALALAR CROSS STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4025,Roads,Completed,NG-AMBATTUR,92,1866000,"RELAYING THE EXISTING BLOCK TOPPED ROAD AT SENTAMIZH NAGAR 2ND STREETD IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/4026,Roads,Completed,NG-AMBATTUR,92,563000,"RELAYING THE EXISTING BLACK TOPPED ROAD AT BHARATHIDASAN NAGAR 1ST STREET IN DN 92, UNIT 20, ZONE -VII",Own Sources,7,2018-19,2020-21 NG/2018-19/9245,Storm Water Drain,Completed,NG-AMBATTUR,92,170000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION- 92 UNIT-20 ZONE-7(AMBATTUR),Own Sources,7,2018-19,2019-20 BR/2018-19/6005,Road Cut,Completed,BR-Bus Route Roads,93,1370000,Restoration of Road cut work made by CMWSSB at Parisalai road in Div-93.Zone -07,Deposit Works,7,2018-19,2019-20 L/2018-19/5978,Electrical,Completed,L-Electrical,93,838600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 11 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Primary Health Centre, Veeramamunivar salai in Div-93, Zone-VII .(E.B.Account no. - 042.004.1280 ).",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/5980,Electrical,Completed,L-Electrical,93,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office -93, Pillayar koil street, Padikuppam in Div-93 ,Zone-VII (EB.A/C.NO.042-019-4810)",SMART CITY - ELECTRICAL,7,2018-19,2019-20 L/2018-19/5981,Electrical,Completed,L-Electrical,93,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Unavagam, Burnor salai, 6th block in Div-93, Zone-VII (042-006-899)",SMART CITY - ELECTRICAL,7,2018-19,2019-20 NG/2018-19/0481,Buildings,Completed,NG-AMBATTUR,93,175000,"IMPROVEMENT WORKS TO THE EXCISTING ICDS CENTER AT NAKKEERAN SALAI IN DIV-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0565,Roads,Completed,NG-AMBATTUR,93,150000,"IMPROVEMENT TO THE EXCISTING ICDS CENTER AT 2ND BLOCK 18TH STREET IN DIV-93,U-20,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0566,Buildings,Completed,NG-AMBATTUR,93,175000,"IMPROVEMENT WORK TO THE EXCISTING ICDS CENTER AT PUGAZHENTHI SALAI 3RD BLOCK IN DIV 93, UNIT-20, ZONE 7",Own Sources,7,2018-19,2018-19 NG/2018-19/0567,Roads,Completed,NG-AMBATTUR,93,175000,"IMPROVEMENT TO THE EXCISTING ICDS CENTER AT PUGAZHENTHI SALAI IN DIV-93, UNIT-20,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0568,Roads,Completed,NG-AMBATTUR,93,150000,"IMPROVEMENT WORKS TO THE EXSISTING ICDS CENTER AT 5TH BLOCK BURNER SALAI IN DIV-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0569,Buildings,Completed,NG-AMBATTUR,93,175000,"IMPROVEMENTS WORK TO THE EXISTING ICDS CENTER AT 6TH BLOCK IN DIV 93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0570,Roads,Completed,NG-AMBATTUR,93,175000,"IMPROVEMENT WORK TO THE EXISTING ICDS CENTER AT 1ST BLOCK IN DIV93, UNIT-20,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0571,Buildings,Completed,NG-AMBATTUR,93,175000,"IMPROVEMENT WORK TO THE EXISTING ICDS CENTER AT NAKKEERAN SALAI IN DIV 93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/0572,Buildings,Completed,NG-AMBATTUR,93,215000,"IMPROVEMENT WORK TO THE EXISTING CHENNAI MIDDLE SCHOOL AT PUGAZHENTHI SALAI SEC II SCHOOL IN DIV-93, UNIT-20,ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/10401,Roads,Completed,NG-AMBATTUR,93,1000000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIV 91, 92 & 93 UNIT-20, ZONE-7",Own Sources,7,2018-19,2018-19 NG/2018-19/16353,Parks,Completed,NG-AMBATTUR,93,2955000,"Proposed Construction Of Compound Wall And Foot Path At Rail Nagar OSR Park In Division 93, Unit 20, Zone 7.",MLACDS,7,2018-19,2019-20 NG/2018-19/4034,Roads,Completed,NG-AMBATTUR,93,620000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 2ND BLOCK NAKKEERAN ROAD 31ST STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4035,Roads,Completed,NG-AMBATTUR,93,510000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 6TH BLOCK BURNER ROAD 8TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4036,Roads,Completed,NG-AMBATTUR,93,490000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 6TH BLOCK BURNER ROAD 13TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4037,Roads,Completed,NG-AMBATTUR,93,285000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 2ND BLOCK NAKKEERAN ROAD 2ND STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4038,Roads,Completed,NG-AMBATTUR,93,350000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 2ND BLOCK NAKKEERAN ROAD 3RD STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4039,Roads,Completed,NG-AMBATTUR,93,493000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 6TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4040,Roads,Completed,NG-AMBATTUR,93,249000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 7TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4041,Roads,Completed,NG-AMBATTUR,93,618000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 8TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4042,Roads,Completed,NG-AMBATTUR,93,618000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 9TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4043,Roads,Completed,NG-AMBATTUR,93,650000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 10TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4044,Roads,Completed,NG-AMBATTUR,93,598000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 4TH BLOCK NAKKEERAN ROAD 13TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4045,Roads,Completed,NG-AMBATTUR,93,860000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 4TH BLOCK NAKKEERAN ROAD 14TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4046,Roads,Completed,NG-AMBATTUR,93,373000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 4TH BLOCK NAKKEERAN ROAD 15TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4047,Roads,Completed,NG-AMBATTUR,93,373000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 4TH BLOCK NAKKEERAN ROAD 16TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4048,Roads,Completed,NG-AMBATTUR,93,211000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 4TH BLOCK NAKKEERAN ROAD 17TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4049,Roads,Completed,NG-AMBATTUR,93,356000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 4TH BLOCK NAKKEERAN ROAD 19TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4050,Roads,Completed,NG-AMBATTUR,93,325000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 20TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4051,Roads,Completed,NG-AMBATTUR,93,598000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 21ST STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4052,Roads,Completed,NG-AMBATTUR,93,459000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 22ND STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4053,Roads,Completed,NG-AMBATTUR,93,211000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 23RD STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4054,Roads,Completed,NG-AMBATTUR,93,598000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 24TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4055,Roads,Completed,NG-AMBATTUR,93,598000,"RELAYING THE EXSISTING CEMENT CONCRETE ROAD AT DR.JJ NAGAR EAST 3RD BLOCK NAKKEERAN ROAD 25TH STREET IN DN-93,UNIT-20,ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4056,Roads,Completed,NG-AMBATTUR,93,2035000,"RELAYING THE EXSISTING B.T ROAD AT ORI SALAI STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4057,Roads,Completed,NG-AMBATTUR,93,1550000,"RELAYING THE EXSISTING B.T ROAD AT 1ST BLOCK 1 TO 4 AND 6 TO 8 STREETS IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4058,Roads,Completed,NG-AMBATTUR,93,2710000,"RELAYING THE EXSISTING B.T ROAD AT 2ND BLOCK TO 4TH BLOCK PUGAZHENTHI ROAD AND 2ND, 4TH, 5TH AND 14TH STREETS IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4059,Roads,Completed,NG-AMBATTUR,93,4060000,"RELAYING THE EXSISTING B.T ROAD AT 2ND BLOCK AGATHIYAR ROAD, 1 TO 4 STREETS AND 5TH BLOCK AGATHIYAR ROAD, 1 TO 3 STREETS IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4060,Roads,Completed,NG-AMBATTUR,93,1870000,"RELAYING THE EXSISTING B.T ROAD AT 5TH BLOCK AGATHIYAR ROAD 4 TO 10 STREETS IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4061,Roads,Completed,NG-AMBATTUR,93,2340000,"RELAYING THE EXSISTING B.T ROAD AT PERIYAR 2ND CROSS STREET, RAIL NAGAR MAIN ROAD IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4062,Roads,Completed,NG-AMBATTUR,93,4324000,"RELAYING THE EXSISTING B.T ROAD AT 5TH BLOCK BURNER ROAD, PACHAIYAPPAR SALAI IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4064,Roads,Completed,NG-AMBATTUR,93,4638000,"RELAYING THE EXSISTING B.T ROAD AT MARAIMALAI MALAI ADIKALAR SALAI, ANNAI THERASA STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4065,Roads,Completed,NG-AMBATTUR,93,5500000,"RELAYING THE EXSISTING B.T ROAD AT EDEN AVENUE, JUSTICE RATHINAVEL PANDIAN ROAD IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4066,Roads,Completed,NG-AMBATTUR,93,3585000,"RELAYING THE EXSISTING B.T ROAD AT AMBIKA STREET, VASANTHA STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4067,Roads,Completed,NG-AMBATTUR,93,3980000,"RELAYING THE EXSISTING B.T ROAD AT PILLAYAR KOIL STREET, SELVI JAYAKUMAR STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4068,Roads,Completed,NG-AMBATTUR,93,3212000,"RELAYING THE EXSISTING B.T ROAD AT ARANI SUBRAMANIAM STREET, BACKIYAM STREET, PAGADALA RANGASAMY STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4069,Roads,Completed,NG-AMBATTUR,93,2233000,"RELAYING THE EXSISTING B.T ROAD AT SAVITHRI NATARAJAN STREET, NANDHINI LAKSHMAN STREET AND SRINIVASA KUMAR STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4070,Roads,Completed,NG-AMBATTUR,93,1593000,"RELAYING THE EXSISTING B.T ROAD AT ALEX LEO STREET, GOVINDASAMY STREET IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/4071,Roads,Completed,NG-AMBATTUR,93,3035000,"RELAYING THE EXSISTING B.T ROAD AT 5TH BLOCK BURNER ROAD 1ST TO 6TH STREET AND 18 TO 23 STREETS IN DN-93, UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/7324,Storm Water Drain,Completed,NG-AMBATTUR,93,763000,"DESILTING TO THE EXISTING ROAD SIDE DRAIN AND STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION 93 UNIT - 20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/7696,Roads,Completed,NG-AMBATTUR,93,2888000,"ROAD CUT RESTORATION BITUMINOUS MACADAM ROAD AT VARIOUS STREETS IN DIV 93,UNIT-20, ZONE-7",Own Sources,7,2018-19,2019-20 NG/2018-19/8037,Buildings,Completed,NG-AMBATTUR,93,270000,"Improvements & Repair work to Amma Unavagam at 6th Block Burner salai & Padikuppam Main Road in div-93,unit-20,zone-7",Own Sources,7,2018-19,2019-20 BR/2018-19/7342,Roads,Completed,BR-Bus Route Roads,94,21200,Roadcut restoration made by CMWSSB at North Redhills road in zone-8 against challan no:BR/2018-19/0010074.,Deposit Works,8,2018-19,2019-20 D/2018-19/6023,Storm Water Drain,Completed,D-Storm Water Drains,94,2465000,"Demolition and Reconstruction of storm water drain of size 1500x1500mm inside Villivakkam Burial ground from the diposal point of Villivakkam tank upto main drain at Chennai Thiruvallur main road in Dn - 94,Zone-VIII.",Own Sources,8,2018-19,2018-19 D/2018-19/6041,Storm Water Drain,Completed,D-Storm Water Drains,94,1825000,"Demolition and Reconstruction of storm water drain of size 1500x1500mm along Chennai Thiruvallur high road from the entrance of Villivakkam Burial ground up to the cross drain connecting to Kumarasamy canal in Dn - 94,Zone-VIII.",Own Sources,8,2018-19,2018-19 D/2018-19/9390,Storm Water Drain,Completed,D-Storm Water Drains,94,50726000,"Construction of Storm Water Drain at Baba Nagar,Bharathi Salai,Ambedkar Road ( KH Road,Gandhi Nagar TNSCB and Thiru Nagar in Zone - 8 - Package - 27.",Grants,8,2018-19,2019-20 D/2018-19/9407,Storm Water Drain,Completed,D-Storm Water Drains,94,19274000,Construction of Storm Water Drain at Baba Nagar 15th Street on East Side in Zone - 8 and Puliyur 2nd Land on North Side in Zone - 9 - Package - 37.,Grants,8,2018-19,2019-20 L/2018-19/14069,Electrical,Completed,L-Electrical,94,194900,"Proposal for fixing of 498nos of LED Fittings and removal of 498 nos of Sodium vapour lamp fitting at various places in Villivakkam and Anna nagar west in div 94,95,&99 Zone VIII",Own Sources,8,2018-19,2019-20 L/2018-19/16241,Electrical,Completed,L-Electrical,94,507600,"Provision of 10 nos of 7 mtr GI Lamp post with 1 mtr straight bracket With 40-50 W LED Fitting and laying of 437 mtrs. of 2 X 25 sqmm alu. UG. Cable at Baba Nagar 12 th street, in Dn - 94, Zone - 8",Own Sources,8,2018-19,2020-21 L/2018-19/5692,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 2 nd main road, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5693,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 2 nd main road, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5695,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 10th Street, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5696,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 51 th Street, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5698,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 3rd main road, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5699,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 42 nd Street, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5700,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 33 rd Street, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5701,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 50th Street, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5702,Electrical,Completed,L-Electrical,94,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, Sidco nagar 56th Street, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5703,Electrical,Completed,L-Electrical,94,838600,"Supply, Installation, Testing & Commissioning of 11 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS ,Sivan koil north mada street, villivakkam, DIV-94 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/7692,Electrical,Completed,L-Electrical,94,2294800,"Replacement of 4126 mtrs of 2 X 25 sq mm and 387 mtrs of 3 1/2 X 25 sq mm ALU. UG. Cable at SIDCO Nagr 5 th Street to 45 th Street in division-94, Zone-VIII area.",Own Sources,8,2018-19,2019-20 NH/2018-19/12221,Buildings,Completed,NH-ANNA NAGAR,94,620000,"Repairs and Improvement to Villivakkam Subway room in Dn-94, Unit-21, Zone-8",Own Sources,8,2018-19,2019-20 NH/2018-19/12428,Buildings,Completed,NH-ANNA NAGAR,94,247000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT SIVAN KOIL NORTH MADA STREET IN DIV-94, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/12429,Buildings,Completed,NH-ANNA NAGAR,94,53000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT RAJAMANGALAM 1ST MAIN ROAD IN DIV-94, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14627,Roads,Completed,NH-ANNA NAGAR,94,1627300,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT SIVAN KOIL WEST MADA STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14628,Roads,Completed,NH-ANNA NAGAR,94,3282600,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MTH SERVICE ROAD IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14631,Roads,Completed,NH-ANNA NAGAR,94,369700,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT SIDCO INDUSTRIAL AREA A - PART IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14632,Roads,Completed,NH-ANNA NAGAR,94,536400,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT SIDCO INDUSTRIAL AREA B-PART IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14633,Roads,Completed,NH-ANNA NAGAR,94,236900,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT SIDCO INDUSTRIAL AREA C-PART IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14634,Roads,Completed,NH-ANNA NAGAR,94,375900,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT REDHILLS ROAD 4TH STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14635,Roads,Completed,NH-ANNA NAGAR,94,474600,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT REDHILLS ROAD 3RD STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14636,Roads,Completed,NH-ANNA NAGAR,94,530400,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT REDHILLS ROAD 5TH STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14637,Roads,Completed,NH-ANNA NAGAR,94,146500,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT DAMODARA PERUMAL COLONY 1ST LANE IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14638,Roads,Completed,NH-ANNA NAGAR,94,146500,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT DAMODARA PERUMAL COLONY 2ND LANE IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14639,Roads,Completed,NH-ANNA NAGAR,94,107000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT DAMODARA PERUMAL COLONY 3RD LANE IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14643,Roads,Completed,NH-ANNA NAGAR,94,813000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SIDCO NAGAR 59TH STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/15547,Buildings,Completed,NH-ANNA NAGAR,94,980000,"MAINTENANCE AND OPERATION OF THE PLANT (AMMA KUDINEER) AT SIDCO NAGAR 4TH MAIN ROAD IN DN-94, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/5132,Footpath,Completed,NH-ANNA NAGAR,94,737000,"REPAIR OF FOOT PATHWAY AND REPLACING DAMAGE PLAY APPARATUS AT CHILDREN PLAY FILED IN 32ND STREET AND STREET LIGHT OFFICE SIDCO NAGAR IN DN.94,Z.8.",Own Sources,8,2018-19,2019-20 NH/2018-19/7997,Storm Water Drain,Completed,NH-ANNA NAGAR,94,156700,"PROVIDING WATER SUPPLY IN CMS AT NORTH SIVAN KOIL STREET DIVISION -94, UNIT-21, ZONE-08",Own Sources,8,2018-19,2018-19 NH/2018-19/7998,Storm Water Drain,Completed,NH-ANNA NAGAR,94,156700,"PROVIDING WATER SUPPLY IN STREET LIGHT OFFICE SIDCO NAGAR 33RD STREET DIVISION -94, UNIT-21, ZONE-08",Own Sources,8,2018-19,2018-19 NH/2018-19/8254,Storm Water Drain,Completed,NH-ANNA NAGAR,94,321000,MAINTENANCE OF VILLIVAKKAM SUBWAY ENGAGING OF WATCH MAN AND ELECTRICIAN FOR FOUR MONTHS IN DIVISION-94 UNIT-21 ZONE-8,Own Sources,8,2018-19,2018-19 NH/2018-19/8721,Storm Water Drain,Completed,NH-ANNA NAGAR,94,373000,"REPAIR MOTORS AND DESILITING SUBWAY WELL IN VILLIVAKKAM SUBWAY DIVISION -94, UNIT-21, ZONE-08",Own Sources,8,2018-19,2018-19 NH/2018-19/8949,Roads,Completed,NH-ANNA NAGAR,94,250000,"ATTENDING PATCHES AND PROVIDING GSB & WMM AT FLOOD AFFECTED AREA IN DN 94,UNIT-21,ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/9015,Storm Water Drain,Completed,NH-ANNA NAGAR,94,985000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 94, UNIT 21, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/9016,Storm Water Drain,Completed,NH-ANNA NAGAR,94,970000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 94, UNIT 21, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/9018,Storm Water Drain,Completed,NH-ANNA NAGAR,94,995000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 94, UNIT 21, ZONE 8.",Own Sources,8,2018-19,2018-19 L/2018-19/12996,Electrical,Completed,L-Electrical,95,199200,"Proposal for fixing of 509nos of LED Fittings and removal of 509nos of Sodium vapour lamp fitting at various places in Anna nagar west in div 95, Zone VIII",Own Sources,8,2018-19,2019-20 L/2018-19/5704,Electrical,Completed,L-Electrical,95,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office -95 , I-Block, Annanagar West, DIV-95 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5706,Electrical,Completed,L-Electrical,95,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Fittness Centre, Thirunagar, Annanagar West, DIV-95 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5707,Electrical,Completed,L-Electrical,95,537600,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Centre, Venugopal street, Annanagar West, DIV-95 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5711,Electrical,Completed,L-Electrical,95,311900,"Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary ,Officers Colony ,Ayanavaram in Div. 96 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/12078,Buildings,Completed,NH-ANNA NAGAR,95,470000,"IMPROVEMENTS TO AMMA UNAVAGAM THANTHONNI AMMAN KOIL STREET IN DIVISION - 95, UNIT - 21, ZONE - 08.",Own Sources,8,2018-19,2019-20 NH/2018-19/12105,Buildings,Completed,NH-ANNA NAGAR,95,251000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT THIRU NAGAR GYM IN DIVISION - 95 , UNIT - 21 , ZONE - 08.",Own Sources,8,2018-19,2019-20 NH/2018-19/12364,Buildings,Completed,NH-ANNA NAGAR,95,250000,"IMPROVEMENTS TO AMMA UNAVAGAM VENUGOPAL STREET IN DIVISION - 95, UNIT - 21, ZONE - 08.",Own Sources,8,2018-19,2018-19 NH/2018-19/12614,Roads,Completed,NH-ANNA NAGAR,95,2687000,"Laying cement concrete road at Thiruvenkadaya 1st and 2nd street in division 95,unit 21,zone 08 (MLA FUND)",MLACDS,8,2018-19,2019-20 NH/2018-19/12686,Roads,Completed,NH-ANNA NAGAR,95,1842000,LAYING CEMENT CONCRETE ROAD AT SEEYALAM 2ND STREET EXTENSION AND SEEYALAM 1ST AND 2ND CROSS STREET IN DIVISION 95 UNIT 21 ZONE 08 .(MLA FUND),MLACDS,8,2018-19,2019-20 NH/2018-19/12688,Roads,Completed,NH-ANNA NAGAR,95,1737000,LAYING CEMENT CONCRETE ROAD AT SIYALAM CANAL 2ND STREET IN DIVISION 95 UNIT 21 ZONE 08 (MLA FUND),MLACDS,8,2018-19,2019-20 NH/2018-19/14023,Roads,Completed,NH-ANNA NAGAR,95,1468600,PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIRU NAGAR 12TH & 13TH STREET IN DIVISION 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14025,Roads,Completed,NH-ANNA NAGAR,95,277100,IMPROVEMENTS TO THE INTERIOR BT ROAD AT MANNADI OTHAVADAI STREET IN DIVISION 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2020-21 NH/2018-19/14029,Roads,Completed,NH-ANNA NAGAR,95,159700,IMPROVEMENTS TO THE INTERIOR BT ROAD AT THIRUVALLUVAR STREET IN DIVISION 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2020-21 NH/2018-19/14030,Roads,Completed,NH-ANNA NAGAR,95,1368300,IMPROVEMENTS TO THE INTERIOR BT ROAD AT THIRUVEETHI AMMAN KOIL 1ST STREET IN DIVISION 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14031,Roads,Completed,NH-ANNA NAGAR,95,798300,IMPROVEMENTS TO THE INTERIOR BT ROAD AT SIYALAM 1ST STREET IN DIVISION 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14032,Roads,Completed,NH-ANNA NAGAR,95,643700,IMPROVEMENTS TO THE INTERIOR BT ROAD AT THIRUVEETHI AMMAN KOIL STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14033,Roads,Completed,NH-ANNA NAGAR,95,540700,IMPROVEMENTS TO THE INTERIOR BT ROAD AT DR. AMBDEKAR STREET IN DIVISION - 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14034,Roads,Completed,NH-ANNA NAGAR,95,187400,IMPROVEMENTS TO THE INTERIOR BT ROAD AT NARAYANA MAISTRY 1ST STREET IN DIVISION- 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14035,Roads,Completed,NH-ANNA NAGAR,95,374900,IMPROVEMENTS TO THE INTERIOR BT ROAD AT BAJANAI KOIL 2ND STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14036,Roads,Completed,NH-ANNA NAGAR,95,347400,IMPROVEMENTS TO THE INTERIOR BT ROAD AT BAJANAI KOIL 1ST STREET IN DIVISION -95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14037,Roads,Completed,NH-ANNA NAGAR,95,395500,IMPROVEMENTS TO THE INTERIOR BT ROAD AT BAJANAI KOIL MAIN STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14038,Roads,Completed,NH-ANNA NAGAR,95,326800,IMPROVEMENTS TO THE INTERIOR BT ROAD AT THIRU.VI.KA NAGAR (PART) IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2020-21 NH/2018-19/14039,Roads,Completed,NH-ANNA NAGAR,95,232200,IMPROVEMENTS TO THE INTERIOR BT ROAD AT RAJIV GANDHI NAGAR CROSS STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14041,Roads,Completed,NH-ANNA NAGAR,95,141200,IMPROVEMENTS TO THE INTERIOR BT ROAD AT MULLAI NAGAR 11TH STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2020-21 NH/2018-19/14042,Roads,Completed,NH-ANNA NAGAR,95,407000,IMPROVEMENTS TO THE INTERIOR BT ROAD AT VIJAYALAKSHMIPURAM 4TH STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2020-21 NH/2018-19/14043,Roads,Completed,NH-ANNA NAGAR,95,486500,IMPROVEMENTS TO THE INTERIOR BT ROAD AT KUMARASWAMY NAGAR 2ND MAIN ROAD IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14044,Roads,Completed,NH-ANNA NAGAR,95,643700,IMPROVEMENTS TO THE INTERIOR BT ROAD AT AGATHIYAR NAGAR 31ST STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14045,Roads,Completed,NH-ANNA NAGAR,95,792100,IMPROVEMENTS TO THE INTERIOR BT ROAD AT I-BLOCK 38TH STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14046,Roads,Completed,NH-ANNA NAGAR,95,227800,IMPROVEMENTS TO THE INTERIOR BT ROAD AT I-BLOCK 39TH STREET IN DIVISION- 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14047,Roads,Completed,NH-ANNA NAGAR,95,218000,IMPROVEMENTS TO THE INTERIOR BT ROAD AT I - BLOCK 42ND STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14048,Roads,Completed,NH-ANNA NAGAR,95,903700,IMPROVEMENTS TO THE INTERIOR BT ROAD AT IMAYAM COLONY 3RD STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14049,Roads,Completed,NH-ANNA NAGAR,95,342200,IMPROVEMENTS TO THE INTERIOR BT ROAD AT THIRU NAGAR 17TH STREET IN DIVISION 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14050,Roads,Completed,NH-ANNA NAGAR,95,996600,IMPROVEMENTS TO THE INTERIOR BT ROAD AT 13TH MAIN ROAD NORTH SIDE IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2020-21 NH/2018-19/14051,Roads,Completed,NH-ANNA NAGAR,95,1331300,IMPROVEMENTS TO THE INTERIOR BT ROAD AT CHENNAI BATTAI ROAD IN DIVISION- 95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/14052,Roads,Completed,NH-ANNA NAGAR,95,180300,IMPROVEMENTS TO THE INTERIOR BT ROAD AT NAVALAR NAGAR MUTHUMARI AMMAN KOIL STREET IN DIVISION-95 UNIT- 21 ZONE 08,Own Sources,8,2018-19,2019-20 NH/2018-19/5418,Roads,Completed,NH-ANNA NAGAR,95,300000,"ATTENDING PATCH WORK AT EAST MAIN ROAD, NORTHERN MAIN ROAD AND AGATHIYAR NAGAR IN DIV-95, UNIT-21, ZONE-8",Own Sources,8,2018-19,2018-19 NH/2018-19/7773,Buildings,Completed,NH-ANNA NAGAR,95,129000,"PROVIDING WATER SUPPLY ARRANGEMENTS IN CONSERVANCY OFFICE ,THIRU NAGAR IN DIV-95, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/9023,Storm Water Drain,Completed,NH-ANNA NAGAR,95,611000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 95, UNIT 21, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/9024,Storm Water Drain,Completed,NH-ANNA NAGAR,95,990000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 95, UNIT 21, ZONE 8.",Own Sources,8,2018-19,2018-19 BR/2018-19/0675,Road Cut,Completed,BR-Bus Route Roads,96,1470000,"Restoration of roadcut made by CMWSSB at Konnur High Road from the jn of Mettu Street to the jn of Murugan stores in Dn - 96, Zone - 8 ( Chellan No: BR/2017 - 18/0016530 & Deposit code :57/0841/2017 - 18)",Deposit Works,8,2018-19,2018-19 BR/2018-19/0688,Road Cut,Completed,BR-Bus Route Roads,96,2470000,"Restoration of roadcut made by CMWSSB at Konnur High Road from the jn of Murugan stores to the jn of Tagore nagar in Dn - 96, Zone - 8 ( Chellan No: BR/2017 - 18/0016530 & Deposit code :57/0841/2017 - 18)",Deposit Works,8,2018-19,2018-19 BR/2018-19/6531,Footpath,Completed,BR-Bus Route Roads,96,44657000,"Forming Footpath at Konnur High Road in Dn-70 & 96, Zone-VI & VIII",Grants,8,2018-19,2020-21 BR/2018-19/7339,Roads,Completed,BR-Bus Route Roads,96,52500,Roadcut restoration made by CMWSSB at Konnur High road in zone-8 against challan no:BR/2018-19/0008776.,Deposit Works,8,2018-19,2019-20 D/2018-19/2920,Storm Water Drain,Completed,D-Storm Water Drains,96,2282000,"Providing RWH well to the Temple Tank at AngalaParameshwari Koil,Royapuram & Kasiviswanathasamy koil, Ayanavaram under Sustainable Water Security Mission in Dn - 49 & 96,Zone 5 & 8",SMART CITY - SWD,8,2018-19,2020-21 L/2018-19/15466,Electrical,Completed,L-Electrical,96,156400,"Provision of 1No of 8Mtr GI Octogonal Mini High mast with hot galvanised hexagonal lantern carriage with 3 Nos of 70-100w LED Flood light fitting with Laying of 38 Mtr 31/2 x 25 SQ,MM U.G.(ALUM)Cable at Ayanavaram New Avadi Road (jn) ICF Gandhi Nagar Link Road Signal in div 96 zone VIII area.",Own Sources,8,2018-19,2020-21 L/2018-19/4201,Electrical,Completed,L-Electrical,96,2890700,"WORK: Supply and Erection of 10 Nos of 8 Mtr Street lamp post with 2 mtr Straight Single Bracket, Hot Dip zinc Galvanised with 10 Nos 150-165w LED Fittings with Laying of 400 Mtr 31/2 x 25 SQ,MM U.G.(ALUM)Cable and Replacement of 3421 Mtrs of 31/2 X 25 SQ.MM U.G .(ALUM)Cable at Konnur High Road (I.C.F. Signal - to - Railway quarters ICF- joint office( jn.) in Division - 96 ,Zone-VIII areas..",Own Sources,8,2018-19,2018-19 L/2018-19/4205,Electrical,Completed,L-Electrical,96,2931600,"WORK: Replacement of 1065 Mtrs of 31/2 X 25 SQ.MM U.G .(ALUM)Cable and 4570 Mtrs of 2 X 25 SQ.MM U.G .(ALUM)Cable at Gandhi Nagar,(H/B.Part-1),K.H.Road (Jn)Bhoosnan Street, New Street,Porteous Road,Munuswamy street,Appadurai main street, A.V.Koil 1st to 3rd Street in Division - 96 ,Zone-VIII areas..",Own Sources,8,2018-19,2019-20 L/2018-19/5479,Electrical,Completed,L-Electrical,96,142600,"Provision of 1No of 8Mtr GI Octogonal Mini High mast with hot galvanised hexagonal lantern carriage with 3 Nos of 70-100w LED Flood light fitting with Laying of 45 Mtr 31/2 x 25 SQ,MM U.G.(ALUM)Cable at Konnur High Road (jn) ICF Signal in div 96 zone VIII area.",Own Sources,8,2018-19,2020-21 L/2018-19/5708,Electrical,Completed,L-Electrical,96,161400,"Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dr.MGR Sathunavu Koodam, Palavayol Road ,Ayanavaram in Div. 96 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5709,Electrical,Completed,L-Electrical,96,161400,"Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dr.MGR Sathunavu Koodam,Mayyam no-440, Palavayol Road ,Ayanavaram in Div. 96 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5712,Electrical,Completed,L-Electrical,96,1516400,"Supply, Installation, Testing & Commissioning of 20 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Child Welfare Centre,( EOC )United India Colony ,Ayanavaram in Div. 96 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5713,Electrical,Completed,L-Electrical,96,236700,"Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Off-96 ,Officers Colony ,Ayanavaram in Div. 96 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5715,Electrical,Completed,L-Electrical,96,462400,"Supply, Installation, Testing & Commissioning of 6Kwp Grid Tied Solar Rooftop including Civil works and earthing at Market Complex,Palavayal Road ,Ayanavaram in Div. 96 Zone-VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5716,Electrical,Completed,L-Electrical,96,387200,"Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at C H S,Market Street,Ayanavaram in Div. 96, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5718,Electrical,Completed,L-Electrical,96,387200,"Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS,Market Street,Ayanavaram in Div. 96, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5719,Electrical,Completed,L-Electrical,96,387200,"Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma unavagam ,K.H.Road ,Ayanavaram in Div. 96, Zone-VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5720,Electrical,Completed,L-Electrical,96,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Sathunavu Koodam,Gandhi Nagar -H / B,,Ayanavaram in Div. 96 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5721,Electrical,Completed,L-Electrical,96,311900,"Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at K,H,Road -S/S ,K.H.Road ,Ayanavaram in Div. 96, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5722,Electrical,Completed,L-Electrical,96,688100,"Supply, Installation, Testing & Commissioning of 9Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.H.S.School,Palavayal Road ,Ayanavaram in Div. 96 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/0020,Buildings,Completed,NH-ANNA NAGAR,96,279000,"MINOR REPAIR WORKS IN AMMA UNAVAGAM AT K.K.NAGAR 5TH STREET IN AYANAVARAM IN WARD-96, UNIT-21, ZONE-VIII",Own Sources,8,2018-19,2018-19 NH/2018-19/12445,Buildings,Completed,NH-ANNA NAGAR,96,497000,"MINOR REPAIR WORKS TO AMMA UNAVAGAM AT KONNUR HIGH ROAD IN DN-96, UINT-21, ZONE-VIII",Own Sources,8,2018-19,2018-19 NH/2018-19/12448,Buildings,Completed,NH-ANNA NAGAR,96,432000,"MINOR REPAIR WORKS TO AMMA UNAVAGAM AT K.K.NAGAR 5TH STREET IN DN-96, UINT-21, ZONE-VIII",Own Sources,8,2018-19,2018-19 NH/2018-19/14259,Roads,Completed,NH-ANNA NAGAR,96,280500,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT N.M.K. STREET 1ST LANE IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14261,Roads,Completed,NH-ANNA NAGAR,96,174000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT N.M.K 2ND LANE IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14708,Roads,Completed,NH-ANNA NAGAR,96,619000,"IMPROVEMENT TO THE INTERIOR B T ROAD AT S.S.DEVAR 1ST STREET IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14709,Roads,Completed,NH-ANNA NAGAR,96,619000,"IMPROVEMENT TO THE INTERIOR B T ROAD AT S.S.DEVAR 2ND STREET IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14710,Roads,Completed,NH-ANNA NAGAR,96,632000,"IMPROVEMENT TO THE INTERIOR B T ROAD AT S.S.DEVAR 4TH STREET IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14711,Roads,Completed,NH-ANNA NAGAR,96,632000,"IMPROVEMENT TO THE INTERIOR B T ROAD AT S.S.DEVAR 5TH STREET IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14712,Roads,Completed,NH-ANNA NAGAR,96,154000,"IMPROVEMENT TO THE INTERIOR B T ROAD ROAD AT THIRUMALAI RAJA 2ND STREET IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14713,Roads,Completed,NH-ANNA NAGAR,96,1338000,"IMPROVEMENT TO THE INTERIOR B T ROAD AT PORTEOUS ROAD IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14715,Roads,Completed,NH-ANNA NAGAR,96,1390000,"IMPROVEMENT TO THE INTERIOR B T ROAD AT APPADURAI MAIN STREET IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/3550,Roads,Completed,NH-ANNA NAGAR,96,785900,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT PALAVAYAL ROAD IN DIV-96, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/7946,Buildings,Completed,NH-ANNA NAGAR,96,125000,"PROVIDING WATER SUPPLY ARRANGEMENTS IN PUBLIC CONVENIENCE AT ICF SIGNAL IN AYANAVARAM, DIVISION-96, UNIT-21, ZONE-VIII",Own Sources,8,2018-19,2018-19 NH/2018-19/9026,Storm Water Drain,Completed,NH-ANNA NAGAR,96,992000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 96, UNIT 21, ZONE 8",Own Sources,8,2018-19,2018-19 D/2018-19/9398,Storm Water Drain,Completed,D-Storm Water Drains,97,46229000,"Construction of Storm Water Drain along Ambethkar Road From Seemalamman 2nd Street to Konnu High Road on South -West Side from Vinayagar Koil to UCO Bank ICF Colony in Dn - 97,Zone - 8 - Package - 33.",Grants,8,2018-19,2019-20 D/2018-19/9400,Storm Water Drain,Completed,D-Storm Water Drains,97,38459000,Construction of Storm Water Drain at Police Manickam Road and 6 Other Roads in Zone - 8 - Package - 34.,Grants,8,2018-19,2019-20 L/2018-19/5723,Electrical,Completed,L-Electrical,97,236700,"Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Off-97 ,Solai Street ,Ayanavaram in Div. 97 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5724,Electrical,Completed,L-Electrical,97,236700,"Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.P.S ,Solai Street ,Ayanavaram in Div. 97 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5726,Electrical,Completed,L-Electrical,97,86200,"Supply, Installation, Testing & Commissioning of 1Kwp Grid Tied Solar Rooftop including Civil works and earthing at Noon Meal Cenre ,P.V.Street -H/B,Ayanavaram in Div. 97 Zone-VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5727,Electrical,Completed,L-Electrical,97,86200,"Supply, Installation, Testing & Commissioning of 1Kwp Grid Tied Solar Rooftop including Civil works and earthing at Noon Meal Cenre ,D.56,P.V.Street ,Ayanavaram in Div. 97 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5728,Electrical,Completed,L-Electrical,97,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Gymnasium Building,Pachaikal Veera samy Street in Div. 97, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5729,Electrical,Completed,L-Electrical,97,311900,"Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.P.S,Vellalah Street,Ayanavaram in Div. 97, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/12407,Buildings,Completed,NH-ANNA NAGAR,97,119000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT VELLALA STREET IN DIV-97, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/12424,Buildings,Completed,NH-ANNA NAGAR,97,173000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT PERIYAR SALAI IN DIV-97, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14433,Roads,Completed,NH-ANNA NAGAR,97,1202400,IMPROVEMENT OF BT ROAD AT BATTACHARI STREET IN DIV - 97 UNIT-21 ZONE -8.,Own Sources,8,2018-19,2019-20 NH/2018-19/14434,Roads,Completed,NH-ANNA NAGAR,97,326800,IMPROVEMENT OF BT ROAD AT THANTAI PERIYAR NAGAR 1ST CROSS STREET IN DIV - 97 UNIT-21 ZONE -8.,Own Sources,8,2018-19,2020-21 NH/2018-19/14435,Roads,Completed,NH-ANNA NAGAR,97,319800,IMPROVEMENT OF BT ROAD AT THANTAI PERIYAR NAGAR 1ST STREET IN DIV - 97 UNIT-21 ZONE -8.,Own Sources,8,2018-19,2019-20 NH/2018-19/14436,Roads,Completed,NH-ANNA NAGAR,97,113200,IMPROVEMENT OF BT ROAD AT THANTAI PERIYAR NAGAR 5TH STREET IN DIV - 97 UNIT-21 ZONE -8.,Own Sources,8,2018-19,2020-21 NH/2018-19/14437,Roads,Completed,NH-ANNA NAGAR,97,149800,IMPROVEMENT OF BT ROAD AT SOLAI 4TH STREET IN DIV - 97 UNIT-21 ZONE -8.,Own Sources,8,2018-19,2019-20 NH/2018-19/14440,Roads,Completed,NH-ANNA NAGAR,97,1245400,IMPROVEMENT OF BT ROAD AT ELUMALAI STREET IN DIV - 97 UNIT-21 ZONE -8.,Own Sources,8,2018-19,2019-20 NH/2018-19/14445,Roads,Completed,NH-ANNA NAGAR,97,568600,IMPROVEMENT OF BT ROAD AT PACHAIKAL VEERASWAMY STREET IN DIV - 97 UNIT-21 ZONE -8.,Own Sources,8,2018-19,2019-20 NH/2018-19/4289,Roads,Completed,NH-ANNA NAGAR,97,1459900,IMPROVEMENT OF BT ROAD AT VEERASWAMY STREET IN DIV - 97 UNIT-21 ZONE -8,Own Sources,8,2018-19,2019-20 NH/2018-19/8287,Roads,Completed,NH-ANNA NAGAR,97,2900000,"LAYING OF CC ROAD AT PERIYAR SALAI HOUSING BOARD IN DIV-97, UNIT-21, ZONE-08.(MLA FUND)",MLACDS,8,2018-19,2019-20 NH/2018-19/8947,Roads,Completed,NH-ANNA NAGAR,97,600000,"ATTENDING PATCHES AND PROVIDING GSB & WMM AT FLOOD AFFECTED AREA IN DN 97,UNIT-21,ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/9374,Storm Water Drain,Completed,NH-ANNA NAGAR,97,722000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV-97, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2018-19 L/2018-19/5730,Electrical,Completed,L-Electrical,98,161400,"Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganwadi ,Aspirian Garden in Div. 98 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5731,Electrical,Completed,L-Electrical,98,236700,"Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganwadi,Aspirian Garden,kilpauk in Div. 98, Zone-VIII. .",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5733,Electrical,Completed,L-Electrical,98,387200,"Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary ,Aspirian Garden,kilpauk in Div. 98, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5734,Electrical,Completed,L-Electrical,98,387200,"Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Off-98 Water Works avenue Road ,kilpauk in Div. 98, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5735,Electrical,Completed,L-Electrical,98,161400,"Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed ,Dr.Ambedkar Nagar in Div. 98 Zone-VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5737,Electrical,Completed,L-Electrical,98,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed,Madha koil Street in Div. 98 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5739,Electrical,Completed,L-Electrical,98,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed,Solaiamman koil Street in Div. 98 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/12426,Buildings,Completed,NH-ANNA NAGAR,98,184000,"REPAIRS TO THE EXISTING AMMA UNAVAGAM AT AYANAVARAM ROAD IN DN-98,U-23, Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/12427,Buildings,Completed,NH-ANNA NAGAR,98,110000,"REPAIRS TO THE EXISTING AMMA UNAVAGAM AT ASPIRAN GARDEN 1ST STREET IN DN-98, U -23 ,Z -8.",Own Sources,8,2018-19,2018-19 NH/2018-19/14385,Roads,Completed,NH-ANNA NAGAR,98,347400,"IMPROVEMENT TO THE INTERIOR BT ROAD AT KUTTYAPPAN 1ST STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14389,Roads,Completed,NH-ANNA NAGAR,98,3904300,"IMPROVEMENT TO THE INTERIOR BT ROAD AT ASPIRAN GARDEN 2ND STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14392,Roads,Completed,NH-ANNA NAGAR,98,1758000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT ASPIRAN GARDEN 1ST CROSS STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14395,Roads,Completed,NH-ANNA NAGAR,98,196000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT ASPIRAN GARDEN 2ND CROSS STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14396,Roads,Completed,NH-ANNA NAGAR,98,479600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT ASPIRAN GARDEN WATER WORKS AVENUE ROAD IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14397,Roads,Completed,NH-ANNA NAGAR,98,446700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SOMASUNDARAM 6TH STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14398,Roads,Completed,NH-ANNA NAGAR,98,1144600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RANGAIAH STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14399,Roads,Completed,NH-ANNA NAGAR,98,788500,"IMPROVEMENT TO THE INTERIOR BT ROAD AT PALANIAPPA STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2020-21 NH/2018-19/14403,Roads,Completed,NH-ANNA NAGAR,98,568600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT ASPIRAN GARDEN 1ST STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14432,Roads,Completed,NH-ANNA NAGAR,98,895800,"IMPROVEMENT TO THE INTERIOR BT ROAD AT KUTTYAPPAN 2ND STREET IN DN-98 , UNIT-23, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/6312,Roads,Completed,NH-ANNA NAGAR,98,37064,"IMPROVEMENT TO PC IN DIVISION-98, UNIT-23, ZONE-8",Own Sources,8,2018-19,2018-19 NH/2018-19/6313,Buildings,Completed,NH-ANNA NAGAR,98,214581,"IMPROVEMENT TO DIVISION OFFICE AND AMMA UNAVAGAM AT ASPER GARDEN DN -98,U-23,Z-08",Own Sources,8,2018-19,2018-19 NH/2018-19/9377,Storm Water Drain,Completed,NH-ANNA NAGAR,98,936000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV-98, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 BR/2018-19/0954,Road Cut,Completed,BR-Bus Route Roads,99,760000,"Restoration of road cut made by TANGEDCO at Annanagar 4th Avenue from the jn of 13th Main Road to the jn of 100 ft Road in DN - 99, Zone -8 (BR/2016-17/0001109)",Deposit Works,8,2018-19,2018-19 BR/2018-19/6859,Footpath,Completed,BR-Bus Route Roads,99,861000,"Footpath Repair Works at Anna Nagar 4th Avenue in Dn - 99 &100, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/6861,Footpath,Completed,BR-Bus Route Roads,99,2102000,"Footpath Repair Works at Anna Nagar 6th Avenue in Dn-99,100 & 101, Zone-VIII",Grants,8,2018-19,2019-20 D/2018-19/9391,Storm Water Drain,Completed,D-Storm Water Drains,99,59004000,Construction of Storm Water Drain at Anna Nagar 21st Main Road and School Road in Zone - 8 - Package - 28.,Grants,8,2018-19,2020-21 D/2018-19/9395,Storm Water Drain,Completed,D-Storm Water Drains,99,16485000,"Construction of Storm Water Drain at Amman Koil Road,Vaigai Kudiyuruppu and Others in Zone - 8 - Package - 31.",Grants,8,2018-19,2019-20 D/2018-19/9397,Storm Water Drain,Completed,D-Storm Water Drains,99,45924000,Construction of Storm Water Drain at New Avadi Road and Kilpauk Garden Road in Zone - 8 - Package - 32.,Grants,8,2018-19,2019-20 L/2018-19/5740,Electrical,Completed,L-Electrical,99,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi, T.V Nagar, Annanagar West, DIV-99 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5746,Electrical,Completed,L-Electrical,99,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, T.V Nagar, Pillair Koil Street ,Annanagar West, DIV-99 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/0197,Roads,Completed,P-Parks and Playfields,99,1110000,"PROVIDING TREE PLANTATION AT VARIOUS ROADS IN DIVISION-95, 96, 99, 100 AND 101, UNIT-21 & 22 ZONE-08.",Own Sources,8,2018-19,2021-22 NH/2018-19/0982,Parks,Completed,NH-ANNA NAGAR,99,455000,"Improvements of J block 10th street park in dn99, U-21, Zone-8",Own Sources,8,2018-19,2019-20 NH/2018-19/12437,Buildings,Completed,NH-ANNA NAGAR,99,387000,"PROPOSED CONSTRUCTION OF KITCHEN SHED IN AMMA UNAVAGAM AT 2ND AVENUE IN DIV-99, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/13008,Buildings,Completed,NH-ANNA NAGAR,99,200000,"PROVIDING FENCING AT 100 FEET ROAD NEAR COOVUM RIVER BRIDGE EASTERN SIDE IN DN 99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14491,Roads,Completed,NH-ANNA NAGAR,99,3767400,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT BELLY AREA ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14493,Roads,Completed,NH-ANNA NAGAR,99,278100,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT G - BLOCK 14TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14494,Roads,Completed,NH-ANNA NAGAR,99,746800,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT G - BLOCK 15TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14495,Roads,Completed,NH-ANNA NAGAR,99,287200,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT G - BLOCK 17TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14496,Roads,Completed,NH-ANNA NAGAR,99,314700,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT G - BLOCK 18TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14497,Roads,Completed,NH-ANNA NAGAR,99,325200,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT 21ST MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14498,Roads,Completed,NH-ANNA NAGAR,99,333700,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT ADHAVAN COLONY IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14500,Roads,Completed,NH-ANNA NAGAR,99,278100,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT 12TH MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14501,Roads,Completed,NH-ANNA NAGAR,99,1151900,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT 13TH MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14502,Roads,Completed,NH-ANNA NAGAR,99,1080900,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT 14TH MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14503,Roads,Completed,NH-ANNA NAGAR,99,739300,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 2ND STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14505,Roads,Completed,NH-ANNA NAGAR,99,236900,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 3RD STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14506,Roads,Completed,NH-ANNA NAGAR,99,349200,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 4TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14507,Roads,Completed,NH-ANNA NAGAR,99,643700,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 15TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14509,Roads,Completed,NH-ANNA NAGAR,99,236900,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 16TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14510,Roads,Completed,NH-ANNA NAGAR,99,195600,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 17TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14512,Roads,Completed,NH-ANNA NAGAR,99,349200,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 18TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14513,Roads,Completed,NH-ANNA NAGAR,99,373600,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT J - BLOCK 19TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14515,Roads,Completed,NH-ANNA NAGAR,99,1613100,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT EAST MAIN ROAD (SOUTH) IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14516,Roads,Completed,NH-ANNA NAGAR,99,695200,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT EAST GATE ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14518,Roads,Completed,NH-ANNA NAGAR,99,592200,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT W - BLOCK 1ST STREET (D-SECTOR) IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14519,Roads,Completed,NH-ANNA NAGAR,99,325200,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT W - BLOCK 2ND STREET (D-SECTOR) IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/17701,Roads,Completed,NH-ANNA NAGAR,99,3837000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT PILLAYAR KOIL STREET NEAR METRO ZONE IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/7574,Storm Water Drain,Completed,NH-ANNA NAGAR,99,910000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 99, UNIT 21, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7576,Storm Water Drain,Completed,NH-ANNA NAGAR,99,522000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 99, UNIT 21, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7771,Buildings,Completed,NH-ANNA NAGAR,99,129000,"PROVIDING WATER SUPPLY ARRANGEMENTS IN 16TH MAIN ROAD IN DIV-99, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/8443,Buildings,Completed,NH-ANNA NAGAR,99,129000,"PROVIDING WATER SUPPLY ARRANGEMENTS IN EAST MAIN ROAD IN DIV-99, UNIT-21, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/8478,Roads,Completed,NH-ANNA NAGAR,99,2498000,FORMING THE ROAD AT 6TH AVENUE THANGAM COLONY (CH-0 M TO CH-135M) IN DIV-99 UNIT-21 ZONE-8,Own Sources,8,2018-19,2019-20 NH/2018-19/8479,Roads,Completed,NH-ANNA NAGAR,99,2499000,FORMATION OF NEW ROAD AT 6TH AVENUE THANGAM COLONY (CH-136M TO CH-270M) IN DIV-99 UNIT-21 ZONE-8,Own Sources,8,2018-19,2019-20 NH/2018-19/9571,Roads,Completed,NH-ANNA NAGAR,99,150000,"ATTENDING PATCH WORK AT PILLAIYAR KOIL STREET NEAR SREE SATHYA SAI NAGAR IN DN 99,UNIT-21,ZONE-08.",Own Sources,8,2018-19,2018-19 BR/2018-19/15643,Road Cut,Completed,BR-Bus Route Roads,100,594000,Restoration of OFC road cut made by Reliance Jio at Various Bus Route roads in Zone-VIII(Deposit Code-57/0027/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/17195,Footpath,Completed,BR-Bus Route Roads,100,29634000,"Forming Footpath at Anna Nagar 3rd Avenue (From Anna Arch to New Avadi Road) in Dn-100 & 101, Zone-VIII",Grants,8,2018-19,2020-21 BR/2018-19/18254,Roads,Completed,BR-Bus Route Roads,100,2637000,ROAD CUT RESTORATION AND ATTENDING PATCH WORK AT VARIOUS BUS ROUTE ROADS IN ZONE-8.,Own Sources,8,2018-19,2019-20 BR/2018-19/18308,Roads,Completed,BR-Bus Route Roads,100,2500000,"ATTENDING PATCH WORK AT NELSON MANIKAM ROAD, NEW AVADI ROAD, AND VARIOUS BUS ROUTE ROADS IN ZONE-8",Own Sources,8,2018-19,2020-21 BR/2018-19/4689,Road Cut,Completed,BR-Bus Route Roads,100,980000,"Restoration of road cut made by CMWSSB at Anna Nagar 3rd Avenue in Dn-100, Zone - 8 (Chellan No: BR/17-18/0029358)",Deposit Works,8,2018-19,2018-19 BR/2018-19/6860,Footpath,Completed,BR-Bus Route Roads,100,461000,"Footpath Repair Works at Anna Nagar 5th Avenue in Dn - 100, Zone-VIII",Grants,8,2018-19,2019-20 L/2018-19/10783,Electrical,Completed,L-Electrical,100,427800,Supply and replacement of 504mtrs of 4 x 25sqmm damaged and chronically fault occurance locations in EVR Periyar salai into 3 1/2x25sqmm in div 100 zone VIII,Own Sources,8,2018-19,2019-20 L/2018-19/12991,Electrical,Completed,L-Electrical,100,199200,"Proposal for fixing of 509nos of LED Fittings and removal of 509nos of Sodium vapour lamp fitting at various places in div 100,101 in zone VIII",Own Sources,8,2018-19,2019-20 L/2018-19/5747,Electrical,Completed,L-Electrical,100,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Pillayar koil street health centre div 101 zone VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5749,Electrical,Completed,L-Electrical,100,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS Nadhamuni street in div 101 zone VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5783,Electrical,Completed,L-Electrical,100,558600,Supply and laying of cable at MGR Colony,Own Sources,8,2018-19,2019-20 L/2018-19/6411,Electrical,Completed,L-Electrical,100,3560100,"Electrification of Chennai schools in div 94,96,97,100,102,104,107 and 108 zone VIII",Own Sources,8,2018-19,2019-20 NH/2018-19/0221,Roads,Completed,NH-ANNA NAGAR,100,314700,"IMPROVEMENT TO THE BT ROAD AT AH BLOCK 2nd STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/12410,Buildings,Completed,NH-ANNA NAGAR,100,76000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT 3RD AVENUE IN DIV-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/12411,Buildings,Completed,NH-ANNA NAGAR,100,189000,"REPAIRS AND IMPROVEMENT TO AMMA UNAVAGAM AT 7TH MAIN ROAD IN DIV-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14877,Roads,Completed,NH-ANNA NAGAR,100,355300,"IMPROVEMENT TO THE BT ROAD AT AI BLOCK 1st STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14878,Roads,Completed,NH-ANNA NAGAR,100,1251100,"IMPROVEMENT TO THE BT ROAD AT AL BLOCK 1st STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14879,Roads,Completed,NH-ANNA NAGAR,100,1251100,"IMPROVEMENT TO THE BT ROAD AT AL BLOCK 2nd STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14880,Roads,Completed,NH-ANNA NAGAR,100,1251100,"IMPROVEMENT TO THE BT ROAD AT AL BLOCK 3rd STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14881,Roads,Completed,NH-ANNA NAGAR,100,1251100,"IMPROVEMENT TO THE BT ROAD AT AL BLOCK 4th STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14882,Roads,Completed,NH-ANNA NAGAR,100,38400,"IMPROVEMENT TO THE BT ROAD AT AD BLOCK 1st STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14883,Roads,Completed,NH-ANNA NAGAR,100,335300,"IMPROVEMENT TO THE BT ROAD AT AD BLOCK 2nd STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14884,Roads,Completed,NH-ANNA NAGAR,100,314700,"IMPROVEMENT TO THE BT ROAD AT AD BLOCK 3rd STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14885,Roads,Completed,NH-ANNA NAGAR,100,277100,"IMPROVEMENT TO THE BT ROAD AT AD BLOCK 4th STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14886,Roads,Completed,NH-ANNA NAGAR,100,632400,"IMPROVEMENT TO THE BT ROAD AT R- BLOCK 13th STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14887,Roads,Completed,NH-ANNA NAGAR,100,473800,"IMPROVEMENT TO THE BT ROAD AT R- BLOCK 14th STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14889,Roads,Completed,NH-ANNA NAGAR,100,270500,"IMPROVEMENT TO THE BT ROAD AT R- BLOCK 15th STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/15190,Road Cut,Completed,NH-ANNA NAGAR,100,3035000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT 5TH AVENUE FROM CHRUCH TO 6TH AVENUE IN DIVISION 100 UNIT 21 ZONE 08,Deposit Works,8,2018-19,2019-20 NH/2018-19/6998,Roads,Completed,NH-ANNA NAGAR,100,162000,IMPROVEMENTS TO CENTER MEDIANS FROM ANNA NAGAR ROUNDANA TO 100 FEET ROAD IN DIVISION 100 UNIT 22 ZONE 8,Own Sources,8,2018-19,2018-19 NH/2018-19/7700,Storm Water Drain,Completed,NH-ANNA NAGAR,100,650000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 100, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7702,Storm Water Drain,Completed,NH-ANNA NAGAR,100,750000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 100, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/7726,Buildings,Completed,NH-ANNA NAGAR,100,565000,"IMPROVEMENT TO THE PARK AT 14TH MAIN ROAD IN DIV-100, UNIT-22, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/9125,Storm Water Drain,Completed,NH-ANNA NAGAR,100,407000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 100, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2018-19 B/2018-19/14719,Buildings,Completed,B-Buildings,101,6425000,ADDITIONAL CONSTRUCTION OF SECOND FLOOR WITH CONNECTING CORRIDAR AND LIFT ROOM FOR KITCHEN CUM STORE BUILDING FOR AMMA ARANGAM AT SHENOY NAGAR IN DN-101 ZONE-8,Own Sources,8,2018-19,2019-20 BR/2018-19/10331,Road Cut,Completed,BR-Bus Route Roads,101,1300000,"Restoration of roadcut made by CMWSSB at Anna Nagar 2nd avenue from the jn of 2nd main road to the jn of 1st avenue in Dn-101, Zone -8",Deposit Works,8,2018-19,2019-20 BR/2018-19/10405,Road Cut,Completed,BR-Bus Route Roads,101,1800000,"Restoration of roadcut made by CMWSSb at Anna Nagar 3rd Avenue from the jn of Kandasamy college to the jn of 3rd street in Dn -101, Zone - 8",Deposit Works,8,2018-19,2018-19 BR/2018-19/10423,Road Cut,Completed,BR-Bus Route Roads,101,2000000,"Restoration of roadcut made by CMWSSB at Anna Nagar 3rd Avenue from the jn of 3rd street to the jn of 6th avenue Dn -101, Zone - 8",Deposit Works,8,2018-19,2019-20 BR/2018-19/15644,Road Cut,Completed,BR-Bus Route Roads,101,1023000,Restoration of OFC road cut made by Reliance at Various Bus Route Roads in zone-VIII(Deposit Code-57/0055/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/15657,Road Cut,Completed,BR-Bus Route Roads,101,251000,Restoration of OFC road cut made by Airtel at various Bus Route Roads in Zone-VIII (Deposit Code-57/0233/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/18279,Road Cut,Completed,BR-Bus Route Roads,101,678000,"Restoration of roadcut attending patchwork at various street in Dn -101, Unit-22, Zone -8",Deposit Works,8,2018-19,2020-21 BR/2018-19/4384,Roads,Completed,BR-Bus Route Roads,101,134000,"Removing and refixing of One No of Bus Shelter(Opp To Skywalk) at EVR SALAI in Dn - 101, Zone - 8",Own Sources,8,2018-19,2019-20 BR/2018-19/6389,Road Cut,Completed,BR-Bus Route Roads,101,996000,"Restoration of Roadcut Made by CMWSSB at Annanagar 2nd avenue from the jn of A Block 12th Street to the jn of A Block 2nd main Road in Dn - 101, Zone - 8 (Chellan No: BR/2017-18/0016530)",Deposit Works,8,2018-19,2018-19 L/2018-19/10780,Electrical,Completed,L-Electrical,101,197800,"Supply and replacement of worn out timer unit in div 100,101 zone VIII",Own Sources,8,2018-19,2019-20 L/2018-19/1211,Electrical,Completed,L-Electrical,101,160600,Provision of additional illuminaries at the Bougain villea park,Own Sources,8,2018-19,2020-21 L/2018-19/1212,Electrical,Completed,L-Electrical,101,153700,Provision of additional lamp post at Bougain Villea park,Own Sources,8,2018-19,2020-21 L/2018-19/13099,Electrical,Completed,L-Electrical,101,195300,"Proposal for fixing of 499 nos. of LED Fittings and removal of 499 nos. of Sodium vapour lamp fitting at various places in div 94, 105, 100 and 101 in zone VIII",Own Sources,8,2018-19,2019-20 L/2018-19/13967,Electrical,Completed,L-Electrical,101,199200,"Proposal for fixing of 509nos of LED Fittings and removal of 509nos of Sodium vapour lamp fitting at various places in div 100,101 in zone VIII",Own Sources,8,2018-19,2019-20 L/2018-19/16236,Electrical,Completed,L-Electrical,101,2291900,Supply and erection of 12Nos of 9 mtr Height GI lamp post with 42nos of 120 TO 130w Flood light LED Fittings and laying of 340mtrs of 31/2x35 sqmm UG Cable at K Block Tennis Stadium in div 101 zone VIII,Own Sources,8,2018-19,2019-20 L/2018-19/5750,Electrical,Completed,L-Electrical,101,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Corporation primary school Brewary road in div 101 zone VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5751,Electrical,Completed,L-Electrical,101,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Bharathi puram 3rd street dispensary div 101 zone VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5753,Electrical,Completed,L-Electrical,101,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ICDS 3rd Avenue 101 div 101 zone VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5985,Electrical,Completed,L-Electrical,101,1810200,Supply and erection of LED Lamp post at Anna nagar 3rd Avenue div 101 Zone VIII.,Own Sources,8,2018-19,2019-20 NH/2018-19/0684,Buildings,Completed,NH-ANNA NAGAR,101,135000,"RESTORATION OF DAMAGE UPHC AT VARIOUS PLACES IN DIV 101, UNIT - 22, ZONE -8.",Own Sources,8,2018-19,2018-19 NH/2018-19/0685,Buildings,Completed,NH-ANNA NAGAR,101,87600,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIV 101, UNIT - 22, ZONE -8.",Own Sources,8,2018-19,2018-19 NH/2018-19/12415,Buildings,Completed,NH-ANNA NAGAR,101,309000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM AT UNIT OFFICE IN DIVISION-101, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/13430,Roads,Completed,NH-ANNA NAGAR,101,314000,"RESTORATION OF BT ROAD CUT MADE BY CMWSSB AT W BLOCK SERVICE ROAD IN DN-101,UNIT-22,ZONE-VIII",Deposit Works,8,2018-19,2019-20 NH/2018-19/13431,Roads,Completed,NH-ANNA NAGAR,101,696000,"RESTORATION OF BT ROAD CUT MADE BY CMWSSB AT ANNA NAGAR 2ND MAIN ROAD IN DN-101,UNIT-22,ZONE-VIII",Deposit Works,8,2018-19,2019-20 NH/2018-19/13433,Roads,Completed,NH-ANNA NAGAR,101,676000,"RESTORATION OF BT ROAD CUT MADE BY CMWSSB AT ANNAI SATHYA NAGAR 12TH STREET IN DN-101,UNIT-22,ZONE-VIII",Deposit Works,8,2018-19,2019-20 NH/2018-19/14172,Buildings,Completed,NH-ANNA NAGAR,101,487000,"REPAIRS AND IMPROVEMENT WORKS AT CRESENT PLAYGROUND GYM IN DIVISION-102, UNIT-22, ZONE-VIII.",Own Sources,8,2018-19,2019-20 NH/2018-19/14557,Roads,Completed,NH-ANNA NAGAR,101,719700,"IMPROVEMENT TO THE BT ROAD AT F BLOCK 1ST STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2020-21 NH/2018-19/14559,Roads,Completed,NH-ANNA NAGAR,101,498600,"IMPROVEMENT TO THE ROAD AT F BLOCK 6TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14563,Roads,Completed,NH-ANNA NAGAR,101,395500,"IMPROVEMENT TO THE BT ROAD AT F BLOCK 8TH STREET IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14567,Roads,Completed,NH-ANNA NAGAR,101,962300,"IMPROVEMENT TO THE BT ROAD AT CRESENT ROAD IN DIV 101, UNIT 23, ZONE 8",Own Sources,8,2018-19,2019-20 NH/2018-19/14570,Roads,Completed,NH-ANNA NAGAR,101,1063300,IMPROVEMENT TO THE ROAD AT ANNA NAGAR 5TH MAIN ROAD IN DIV 101 UNIT 22 ZONE 8.,Own Sources,8,2018-19,2019-20 NH/2018-19/16366,Parks,Completed,NH-ANNA NAGAR,101,594000,"REPAIRS AND IMPROVEMENTS TO THE CENTER MEDIAN AT VARIOUS LOCATION IN DIV- 94 TO 108, UNIT-21, 22 & 23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/7654,Storm Water Drain,Completed,NH-ANNA NAGAR,101,910000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/8821,Buildings,Completed,NH-ANNA NAGAR,101,655000,"REPAIRS & IMPROVEMENTS TO THE LORRY STATION IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/8995,Storm Water Drain,Completed,NH-ANNA NAGAR,101,930000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2018-19,2018-19 BR/2018-19/18006,Roads,Completed,BR-Bus Route Roads,102,603000,"Providing Centre Median at Anna Nagar 1st Avenue (From the jn of New Avadi Road to jn of 6th Avenue) in Dn-102, Zone-VIII",Own Sources,8,2018-19,2019-20 BR/2018-19/6854,Footpath,Completed,BR-Bus Route Roads,102,1065000,"Footpath Repair Works at Kilpauk Garden Road in Dn-102 & 103, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/6955,Roads,Completed,BR-Bus Route Roads,102,320000,"Improvements to existing Centre Median at Pulla Avenue (from the jn of Th.Vi.Ka. Park to the jn of EVR salai )in Dn -102, Zone - 8",Own Sources,8,2018-19,2018-19 BR/2018-19/7543,Roads,Completed,BR-Bus Route Roads,102,20000,RESTORATION OF ROAD CUT RESTORTION MADE BY CMWSSB ZONE-8 AGAINST CHALLAN NO:BR/2018-19/0014678.,Deposit Works,8,2018-19,2019-20 L/2018-19/13101,Electrical,Completed,L-Electrical,102,196400,"Proposal for fixing of 502 nos of LED Fittings and removal of 502 nos of Sodium vapour lamp fitting at various places in div 97,102 & 103 in zone VIII.",Own Sources,8,2018-19,2019-20 L/2018-19/3570,Electrical,Completed,L-Electrical,102,2868300,"Supply and erection of 73 Nos of 6 Mtr Hot dip zinc galvanising Lamp post with Single straight bracket with laying of 2506 Mtr 2x16 sqmm Pvc Alu.UG Cable with 120 Mtr 4x16sqmm Alu.UG Cable at L-Block in Dn-102,Zone-VIII Area.",Own Sources,8,2018-19,2018-19 L/2018-19/5537,Electrical,Completed,L-Electrical,102,163000,"Smart class Additional wiring for CHS School Ayanavaram Dn-96, CGHS School Pulla Avenue Div- 102, CM School Aminjikarai dn-102, CBHS School G.E.Koil street Div-104 and CHS School Subrayan street Div-107, in Zone-8 area.",Own Sources,8,2018-19,2019-20 L/2018-19/5742,Electrical,Completed,L-Electrical,102,2268200,"Supply, Installation, Testing & Commissioning of 30Kwp Grid Tied Solar Rooftop including Civil works and earthing at Zonal office - 8 Aminjikarai in Div. 102 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5754,Electrical,Completed,L-Electrical,102,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Middle school,Guji street in div 102 zone VIII Area.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5791,Electrical,Completed,L-Electrical,102,763400,"Estimate for Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Girls Higher secondary School Annexure building, T.V.Amman street,Manjakollai, in div 102, Zone VIII Area.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/6413,Electrical,Completed,L-Electrical,102,2771800,"Electrification of Chennai Schools at div 101,102,103,104,105,106,107 and 108 in zone VIII",Own Sources,8,2018-19,2019-20 NH/2018-19/0680,Buildings,Completed,NH-ANNA NAGAR,102,198000,"RESTORATION OF DAMAGE CMS AT VARIOUS PLACES IN DN - 102, UNIT - 23, ZONE -8.",Own Sources,8,2018-19,2018-19 NH/2018-19/0681,Buildings,Completed,NH-ANNA NAGAR,102,194000,"RESTORATION OF DAMAGE CMS AT VARIOUS PLACES IN DN - 102, UNIT - 23, ZONE -8.",Own Sources,8,2018-19,2018-19 NH/2018-19/0682,Buildings,Completed,NH-ANNA NAGAR,102,194000,"RESTORATION OF DAMAGE CMS AT VARIOUS PLACES IN DN - 102, UNIT - 23, ZONE -8.",Own Sources,8,2018-19,2018-19 NH/2018-19/0683,Buildings,Completed,NH-ANNA NAGAR,102,350000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIV 102, UNIT - 23, ZONE -8.",Own Sources,8,2018-19,2018-19 NH/2018-19/11407,Buildings,Completed,NH-ANNA NAGAR,102,1747000,"REPAIR AND IMPROVEMENTS TO JJ BASKETBALL INDOOR STADIUM IN DIVISION-102, UNIT-23, ZONE-VIII.",Own Sources,8,2018-19,2019-20 NH/2018-19/12413,Buildings,Completed,NH-ANNA NAGAR,102,255000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM AT TAMILAR NAGAR IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/12414,Buildings,Completed,NH-ANNA NAGAR,102,379000,"REPAIRS AND IMPROVEMENTS TO AMMAUNAVAGAM AT VS PURAM IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/12811,Parks,Completed,NH-ANNA NAGAR,102,1990000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND WATER SUPPLY ARRANGEMENTS AT ROAD SIDE PARK IN CEMETRY ROAD IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/12923,Parks,Completed,NH-ANNA NAGAR,102,1430000,"PROPOSED GREENERY AND ELECTRICAL ARRANGEMETS AT ROAD SIDE PARK IN CEMETRY ROAD IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/13424,Roads,Completed,NH-ANNA NAGAR,102,554000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT SENGUNTHAR STREET IN DN-102,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/13425,Roads,Completed,NH-ANNA NAGAR,102,507000,"RESTORATION OF BT ROAD CUT MADE BY CMWSSB AT 2ND AVENUE EXTENSION IN DN-102,UNIT-23,ZONE-VIII",Deposit Works,8,2018-19,2019-20 NH/2018-19/13426,Roads,Completed,NH-ANNA NAGAR,102,461000,"RESTORATION OF CC ROAD CUT MADE BY CMWSSB AT V.O.C.NAGAR MAIN ROAD IN DN-102,UNIT-23,ZONE-VIII",Deposit Works,8,2018-19,2019-20 NH/2018-19/14164,Buildings,Completed,NH-ANNA NAGAR,102,740000,"REPAIR AND IMPROVEMENT WORKS TO CANAL ROAD GYM IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14482,Roads,Completed,NH-ANNA NAGAR,102,636000,"IMPROVEMENT TO THE BT ROAD AT AYYAVOO STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14549,Roads,Completed,NH-ANNA NAGAR,102,1964300,"IMPROVEMENT TO THE BT ROAD AT GUJJI 1ST STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14551,Roads,Completed,NH-ANNA NAGAR,102,898400,"IMPROVEMENT TO THE BT ROAD AT GUJJI 2ND STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14553,Roads,Completed,NH-ANNA NAGAR,102,374900,"IMPROVEMENT TO THE BT ROAD AT GUJJI 1ST LANE IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2020-21 NH/2018-19/14556,Roads,Completed,NH-ANNA NAGAR,102,507100,"IMPROVEMENT TO THE BT ROAD AT AYYAVOO 2ND LANE IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2020-21 NH/2018-19/14573,Roads,Completed,NH-ANNA NAGAR,102,541000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT VOC NAGAR 5TH STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2020-21 NH/2018-19/14576,Roads,Completed,NH-ANNA NAGAR,102,517600,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT T.P CHATHIRAM 25TH CROSS STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14579,Roads,Completed,NH-ANNA NAGAR,102,535000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT KATHIRAVAN COLONY 1ST STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14581,Roads,Completed,NH-ANNA NAGAR,102,494700,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT KATHIRAVAN COLONY 2ND STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14582,Roads,Completed,NH-ANNA NAGAR,102,215000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT KATHIRAVAN COLONY 3RD STREET IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14583,Roads,Completed,NH-ANNA NAGAR,102,664000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIRUVEETHI AMMAN KOIL 1ST LANE IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2020-21 NH/2018-19/14584,Roads,Completed,NH-ANNA NAGAR,102,373000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIRUVEETHI AMMAN KOIL 2ND LANE IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2020-21 NH/2018-19/14698,Buildings,Completed,NH-ANNA NAGAR,102,367000,"REPAIR AND IMPROVEMENT WORKS AT ZONAL OFFICE IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/15756,Parks,Completed,NH-ANNA NAGAR,102,1000000,"PROVIDING HAND GYM EQUIPMENTS AND PLATFORM AT SKATING PARK IN DIVISION-102, UNIT-23, ZONE-08(MP FUND 2017-18)",MPLADS,8,2018-19,2020-21 NH/2018-19/17907,Buildings,Completed,NH-ANNA NAGAR,102,2450000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT MANDAPAM ROAD OPPOSITE TO KILPAUK WATER WORKS IN DIVISION -102, UNIT -23, ZONE-08. (MLA FUND).",MLACDS,8,2018-19,2019-20 NH/2018-19/18324,Buildings,Completed,NH-ANNA NAGAR,102,1192000,"Maintenance and Operation of the plant (AMMA KUDINEER) at Mandapam Road in Dn-102, Unit-23, Zone-08. (Period 01.01.2019 to 31.12.2019)",Own Sources,8,2018-19,2021-22 NH/2018-19/7089,Buildings,Completed,NH-ANNA NAGAR,102,809000,"REPAIRS & IMPROVEMENTS WORK TO CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT PULLA AVENUE IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7090,Buildings,Completed,NH-ANNA NAGAR,102,264000,"REPAIRS & IMPROVEMENTS WORK TO CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT MANJAKOLLAI IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7653,Storm Water Drain,Completed,NH-ANNA NAGAR,102,825000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 NH/2018-19/8258,Buildings,Completed,NH-ANNA NAGAR,102,525000,"REPAIRS & IMPROVEMENTS TO THE UPHC AT PULLA AVENUE IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/8763,Buildings,Completed,NH-ANNA NAGAR,102,2277990,"CONSTRUCTION OF ICDS CENTRE AT TELUGU LANE IN DIV -102, UNIT - 23, ZONE - 8. (MLA FUND 2017-18)",MLACDS,8,2018-19,2019-20 NH/2018-19/8780,Parks,Completed,NH-ANNA NAGAR,102,1270000,"PROPOSED CONSTRUCTION OF YOGA PLATFORM AT SKATING PARK IN DIVISION 102,UNIT 23, ZONE 8 (MLA FUND 2017-18)",MLACDS,8,2018-19,2019-20 NH/2018-19/8782,Buildings,Completed,NH-ANNA NAGAR,102,1280000,"Repair and improvements work to RDCC Office and Zonal Office in Division 102, Unit-23, Zone-8",Own Sources,8,2018-19,2018-19 NH/2018-19/8992,Storm Water Drain,Completed,NH-ANNA NAGAR,102,825000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2018-19 BR/2018-19/15645,Road Cut,Completed,BR-Bus Route Roads,103,149600,Restoration of OFC road cut made by AIrtel at Various bus route roads in Zone-VIII (Deposit Code-57/0088/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/15646,Road Cut,Completed,BR-Bus Route Roads,103,44600,Restoration of OFC road cut by Airtel at various Bus Route Roads in Zone-VIII (Deposit Code-57/0162/2018-19,Deposit Works,8,2018-19,2019-20 BR/2018-19/15648,Road Cut,Completed,BR-Bus Route Roads,103,933000,Restoration of OFC road cut made by ACT at various Bus Route Roads in Zone -VIII (Deposit Code-57/0199/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/15651,Road Cut,Completed,BR-Bus Route Roads,103,874000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in zone-VIII (Deposit no-57/0233/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/15656,Road Cut,Completed,BR-Bus Route Roads,103,904000,Restoration of OFC road cut made by Airtel at various Bus Route Roads in Zone-VIII (Deposit Code-57/0286/2018-2019),Deposit Works,8,2018-19,2019-20 BR/2018-19/15688,Road Cut,Completed,BR-Bus Route Roads,103,598000,Restoration of OFC road cut made by Airtel at various Bus Route Roads in Zone-VIII (Deposit Code-57/0233/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/17192,Footpath,Completed,BR-Bus Route Roads,103,3764000,"Forming Footpath at Flowers Road in Dn-104, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/17197,Footpath,Completed,BR-Bus Route Roads,103,3825000,"Forming Footpath at Halls Road in Dn-103, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/18281,Road Cut,Completed,BR-Bus Route Roads,103,798000,"Restoration of roadcut attending patchwork at various street in Dn -103, Unit-23, Zone -8",Deposit Works,8,2018-19,2020-21 BR/2018-19/3174,Roads,Completed,BR-Bus Route Roads,103,2565000,"PROPOSED LAYING OF SPEED BREAKER, CENTRE MEDIAN AND PEDESTRAIN CROSSING UNDER ROAD SAFETY FUND AT KILPAUK GARDEN ROAD, KONNUR HIGH ROAD, NEW AVADI ROAD AND ANNA NAGAR 18TH MAIN ROAD, IN ZONE -8`",Own Sources,8,2018-19,2018-19 BR/2018-19/4382,Roads,Completed,BR-Bus Route Roads,103,135000,"Removing and refixing of One No of Bus Shelter at New Avadi Road in Dn - 103, Zone - 8",Own Sources,8,2018-19,2019-20 BR/2018-19/5800,Roads,Completed,BR-Bus Route Roads,103,168000,REMOVING AND REFIXING OF MODERN STAINLESS STEEL BUS SHELTER (1NO) AT KALIAMMAN KOIL STREET(JUNCTION OF AYYAPPA NAGAR BUS STOP) IN DIV-127 ZONE-10.,Own Sources,8,2018-19,2020-21 BR/2018-19/6530,Footpath,Completed,BR-Bus Route Roads,103,12683000,"Forming Footpath at Purasaiwakkam High Road (From the jn of Kellys Signal to jn of Gangadeeshwarar Koil) in Dn-103, Zone-VIII",Grants,8,2018-19,2020-21 BR/2018-19/6856,Footpath,Completed,BR-Bus Route Roads,103,878000,"Footpath Repair Works at Barnaby Road in Dn-103, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/6857,Footpath,Completed,BR-Bus Route Roads,103,356000,"Footpath Repair Works at Millers Road in Dn-103, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/7335,Roads,Completed,BR-Bus Route Roads,103,12500,Roadcut restoration made by CMWSSB at Millers road in zone-8 against challan no:BR/2018-19/0016302.,Deposit Works,8,2018-19,2019-20 BR/2018-19/7338,Roads,Completed,BR-Bus Route Roads,103,12500,Roadcut restoration made by CMWSSB at Harleys road in zone-8 against challan no:BR/2017-18/0033198.,Deposit Works,8,2018-19,2019-20 BR/2018-19/7340,Roads,Completed,BR-Bus Route Roads,103,68500,Roadcut restoration made by CMWSSB at Millers road in zone-8 against challan no:BR/2017-18/0033194.,Deposit Works,8,2018-19,2019-20 BR/2018-19/7343,Roads,Completed,BR-Bus Route Roads,103,12500,Roadcut restoration made by CMWSSB at Kilpauk Garden road in zone-8 against challan no:BR/2018-19/0008289.,Deposit Works,8,2018-19,2019-20 D/2018-19/9394,Storm Water Drain,Completed,D-Storm Water Drains,103,48294000,Construction of Storm Water Drain at Purasaivakkam High Road and SBI Staff Colony in Zone - 8 - Package - 30.,Grants,8,2018-19,2020-21 D/2018-19/9402,Storm Water Drain,Completed,D-Storm Water Drains,103,43831000,Construction of Storm Water Drain at Balfour Road on North-East Side and 10 Other Roads in Zone - 8 - Package - 35.,Grants,8,2018-19,2020-21 L/2018-19/5471,Electrical,Completed,L-Electrical,103,198900,"Replacement of 509 Mtrs 2 X 16sqmm UG Alu Cable at Semmenpet Main street, 1st street and 2nd Street in div 103 zone VIII area",Own Sources,8,2018-19,2018-19 L/2018-19/5472,Electrical,Completed,L-Electrical,103,2882800,"Replacement of 355 Mtrs 3 1/2 X 25sqmm UG Cable and 5588 Mtrs of 2 x 25 sqmm UG Cable at T.P.Chattiram 1st to 31th Street, Parameswaran nagar and Dharmaraja koil street in div 103 Zone VIII area.",Own Sources,8,2018-19,2019-20 L/2018-19/5755,Electrical,Completed,L-Electrical,103,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai High School, Thiyagappa Street in Div. 103, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5756,Electrical,Completed,L-Electrical,103,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Temple Lane Old Councellor office in Div. 103 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5757,Electrical,Completed,L-Electrical,103,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kelleys Road, Kilpauk Sub-Station in Div. 103 Zone-VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5758,Electrical,Completed,L-Electrical,103,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Temple Street Dispensary in Div. 103, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5762,Electrical,Completed,L-Electrical,103,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Middle School Thiyagappa street in Div. 103 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5763,Electrical,Completed,L-Electrical,103,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Semman pettai Old Age Homeless Centre in Div. 103 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5766,Electrical,Completed,L-Electrical,103,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Temple Street Anganvadi Centre in Div. 103 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/10362,Roads,Completed,NH-ANNA NAGAR,103,700000,"ATTENDING PATCH WORKS USING GSB & WET MIX MACADAM AT T.P.CHATHIRAM 1ST TO 12TH STREETS IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/11922,Buildings,Completed,NH-ANNA NAGAR,103,1838000,"IMPROVEMENTS TO THE EXISTING OLD ZONAL OFFICE BUILDING AT E.V.R SALAI IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2018-19,2018-19 NH/2018-19/12417,Buildings,Completed,NH-ANNA NAGAR,103,122000,"REPAIRS TO THE EXISTING AMMA UNAVAGAM AT HALLS ROAD IN DN-103, U -23, Z -8.",Own Sources,8,2018-19,2019-20 NH/2018-19/12418,Buildings,Completed,NH-ANNA NAGAR,103,87000,"REPAIRS TO THE EXISTING CHAPPATHI CENTRE AT HALLS ROAD LANE IN DN-103 , U-23, Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/12419,Buildings,Completed,NH-ANNA NAGAR,103,88000,"REPAIRS TO THE EXISTING AMMA UNAVAGAM AT E.V.R.SALAI (OLD ZONAL OFFICE ) IN DN-103,U-23, Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/12421,Buildings,Completed,NH-ANNA NAGAR,103,168000,"REPAIRS TO THE EXISTING AMMA UNAVAGAM AT KMC HOSPITAL CAMPUS IN DN-103, U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/12524,Roads,Completed,NH-ANNA NAGAR,103,814000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 1ST CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12525,Roads,Completed,NH-ANNA NAGAR,103,282000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (CC ROAD) AT PARAMESWARAN NAGAR 5TH STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12526,Roads,Completed,NH-ANNA NAGAR,103,216000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (CC ROAD) AT T.P.CHATHIRAM 16TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12527,Roads,Completed,NH-ANNA NAGAR,103,249000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (CC ROAD) AT T.P.CHATHIRAM 20TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12528,Roads,Completed,NH-ANNA NAGAR,103,141000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 5TH STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12529,Roads,Completed,NH-ANNA NAGAR,103,487000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 2ND STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12530,Roads,Completed,NH-ANNA NAGAR,103,603000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 12TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12531,Roads,Completed,NH-ANNA NAGAR,103,279000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 8TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12532,Roads,Completed,NH-ANNA NAGAR,103,263000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 7TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12533,Roads,Completed,NH-ANNA NAGAR,103,244000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 3RD STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12534,Roads,Completed,NH-ANNA NAGAR,103,470000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 5TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12535,Roads,Completed,NH-ANNA NAGAR,103,73000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 14TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12536,Roads,Completed,NH-ANNA NAGAR,103,226000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD) AT T.P.CHATHIRAM 10TH CROSS STREET IN DN-103,UNIT-23,ZONE-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12978,Buildings,Completed,NH-ANNA NAGAR,103,2550396,"ADDITIONAL IMPROVEMENTS TO OLD ZONAL OFFICE BUILDING AT E.V.R.SALAI IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/14269,Roads,Completed,NH-ANNA NAGAR,103,382000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIYAGAPPA STREET 1ST LANE IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14273,Roads,Completed,NH-ANNA NAGAR,103,348000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIYAGAPPA STREET 2ND LANE IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14290,Roads,Completed,NH-ANNA NAGAR,103,328000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIYAGAPPA STREET 3RD LANE IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14370,Roads,Completed,NH-ANNA NAGAR,103,2711600,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT RAJARATHINAM ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14371,Roads,Completed,NH-ANNA NAGAR,103,699700,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT T.P.CHATHIRAM 14TH CROSS STREET IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14372,Roads,Completed,NH-ANNA NAGAR,103,1474000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT PROF.SUBRAMANIYAM STREET IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14373,Roads,Completed,NH-ANNA NAGAR,103,638700,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT RAMANATHAN STREET IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14374,Roads,Completed,NH-ANNA NAGAR,103,962300,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT LAKSHMI STREET IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14375,Roads,Completed,NH-ANNA NAGAR,103,4026700,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT APPA GARDEN STREET AND SIVA SANKARAN STREET IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14376,Roads,Completed,NH-ANNA NAGAR,103,4256900,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT LANDONS ROAD IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/4345,Buildings,Completed,NH-ANNA NAGAR,103,140000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENTS TO AMMA UNAVAGAM AT TAYLORS ROAD IN DIVISION-103, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/5994,Buildings,Completed,NH-ANNA NAGAR,103,417000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING AMMA UNAVAGAM AT KMC HOSPITAL CAMPUS IN DIV-103,U-23,Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7361,Storm Water Drain,Completed,NH-ANNA NAGAR,103,804000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7869,Storm Water Drain,Completed,NH-ANNA NAGAR,103,804000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DN-103,U-23,Z-8.",Own Sources,8,2018-19,2018-19 BR/2018-19/15649,Road Cut,Completed,BR-Bus Route Roads,104,903000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-VIII (Deposit Code-57/0233/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/15655,Road Cut,Completed,BR-Bus Route Roads,104,44500,Restoration of OFC Road cut by ACT at various Bus Route Roads in Zone-VIII (Deposit Code-57/0202/2018-19,Deposit Works,8,2018-19,2019-20 BR/2018-19/15658,Road Cut,Completed,BR-Bus Route Roads,104,844000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-VIII (Deposit code-57/0363/2018-2019),Deposit Works,8,2018-19,2019-20 BR/2018-19/6532,Footpath,Completed,BR-Bus Route Roads,104,3678000,"Forming Footpath at Raja Annamalai Road (From the jn of EVR Salai to Jn of Dr.Alagappa Road) in Dn-104, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/6533,Footpath,Completed,BR-Bus Route Roads,104,7299000,"Forming Footpath at Dr.Alagappa Road in Dn-104, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/6858,Footpath,Completed,BR-Bus Route Roads,104,476000,"Footpath Repair Works at Gangadeeshwarar Koil Street in Dn-104, Zone-VIII",Grants,8,2018-19,2019-20 BR/2018-19/7344,Roads,Completed,BR-Bus Route Roads,104,45000,"Restoration of roadcut made by CMWSSB at Dr.Alagappa road in zone-8, against challan no:BR/2018-19/0009206.",Deposit Works,8,2018-19,2019-20 D/2018-19/2874,Storm Water Drain,Completed,D-Storm Water Drains,104,2423000,"Restoraton to the temple tank at Gangadeeswarar Koil,Purasaiwalkam and Virupaacheeswarar Koil,Mylapore under Sustainable Water Secruity Mission in Dn - 104 & 125,Zone - 8 &9.",SMART CITY - SWD,8,2018-19,2019-20 L/2018-19/5478,Electrical,Completed,L-Electrical,104,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Corporation School, C- Block, School Road, MMDA Colony in Div. 105 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5764,Electrical,Completed,L-Electrical,104,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Boys Higher Sec. School, Gangadeswarar Road in Div. 104, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5767,Electrical,Completed,L-Electrical,104,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Middle School, Pullapuram in Div. 104, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5768,Electrical,Completed,L-Electrical,104,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Middle School, Sundaram Street in Div. 104, Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5770,Electrical,Completed,L-Electrical,104,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Old Division office Sundaram Street in Div. 104 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5771,Electrical,Completed,L-Electrical,104,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi Centre Sastri Nagar in Div. 104 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5774,Electrical,Completed,L-Electrical,104,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganvadi Centre Ozone Kulam Pullapuram in Div. 104 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5775,Electrical,Completed,L-Electrical,104,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office Lettangs Road in Div. 104 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5776,Electrical,Completed,L-Electrical,104,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Rathina Sabapathi Street Dispensary in Div. 104 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5777,Electrical,Completed,L-Electrical,104,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at EVR Salai Diagnostic centre in Div. 104, Zone-VIII",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/12355,Buildings,Completed,NH-ANNA NAGAR,104,390000,"REPAIR AND IMPROVEMENTS AT AMMA UNAVAGAM 2 (lettangs road) IN DIVISION 104 , UNIT 23, ZONE 8",Own Sources,8,2018-19,2019-20 NH/2018-19/12363,Buildings,Completed,NH-ANNA NAGAR,104,489000,"REPAIR AND IMPROVEMENTS AT AMMA UNAVAGAM 1 (sundaram lane) IN DIVISION 104 , UNIT 23, ZONE 8",Own Sources,8,2018-19,2019-20 NH/2018-19/12704,Roads,Completed,NH-ANNA NAGAR,104,738000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (CC ROAD) AT PARTHASARATHY STREET IN DN-104, U-23,Z-8",Deposit Works,8,2018-19,2019-20 NH/2018-19/12705,Roads,Completed,NH-ANNA NAGAR,104,420000,"RESTORATION OF ROAD CUT MADE BY CMWSSB (BT ROAD ) AT GANGATHISWARAR KOIL STREET IN DN-104, U-23, Z-8.",Deposit Works,8,2018-19,2019-20 NH/2018-19/14268,Roads,Completed,NH-ANNA NAGAR,104,195600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SARAVANA PERUMAL STREET IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14279,Roads,Completed,NH-ANNA NAGAR,104,195600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT LADDERS GATE MAIN ROAD IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14289,Roads,Completed,NH-ANNA NAGAR,104,308800,"IMPROVEMENT TO THE INTERIOR BT ROAD AT FLOWERS 1ST LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14291,Roads,Completed,NH-ANNA NAGAR,104,271900,"IMPROVEMENT TO THE INTERIOR BT ROAD AT FLOWERS 2ND LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14292,Roads,Completed,NH-ANNA NAGAR,104,278100,"IMPROVEMENT TO THE INTERIOR BT ROAD AT FLOWERS 3RD LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14296,Roads,Completed,NH-ANNA NAGAR,104,308800,"IMPROVEMENT TO THE INTERIOR BT ROAD AT FLOWERS 4TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14297,Roads,Completed,NH-ANNA NAGAR,104,827900,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SUBRAMANI STREET IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14298,Roads,Completed,NH-ANNA NAGAR,104,625700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT NANCY STREET IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14299,Roads,Completed,NH-ANNA NAGAR,104,195600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SARAVANA PERUMAL 3RD LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14300,Roads,Completed,NH-ANNA NAGAR,104,903700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT DIVAN RAMA ROAD IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14301,Roads,Completed,NH-ANNA NAGAR,104,58200,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 1ST LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14302,Roads,Completed,NH-ANNA NAGAR,104,72200,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 2ND LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14303,Roads,Completed,NH-ANNA NAGAR,104,1475000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT PULLAPURAM 2ND STREET IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14305,Roads,Completed,NH-ANNA NAGAR,104,531000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 1ST STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14308,Roads,Completed,NH-ANNA NAGAR,104,422700,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 3RD STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14309,Roads,Completed,NH-ANNA NAGAR,104,192600,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 4TH STREET (ENTRANCE FACING LEFT SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14310,Roads,Completed,NH-ANNA NAGAR,104,449800,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 5TH STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14312,Roads,Completed,NH-ANNA NAGAR,104,436000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 6TH STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14315,Roads,Completed,NH-ANNA NAGAR,104,531000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 7TH STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14321,Roads,Completed,NH-ANNA NAGAR,104,415600,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 8TH STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14329,Roads,Completed,NH-ANNA NAGAR,104,418500,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 9TH STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14336,Roads,Completed,NH-ANNA NAGAR,104,402100,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SASTRI NAGAR 10TH STREET (BOTH SIDE) IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/14338,Roads,Completed,NH-ANNA NAGAR,104,44000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 3RD LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14340,Roads,Completed,NH-ANNA NAGAR,104,57800,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 4TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14341,Roads,Completed,NH-ANNA NAGAR,104,57800,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 5TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14342,Roads,Completed,NH-ANNA NAGAR,104,58000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 6TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14343,Roads,Completed,NH-ANNA NAGAR,104,58000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 7TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14344,Roads,Completed,NH-ANNA NAGAR,104,57000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 8TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14345,Roads,Completed,NH-ANNA NAGAR,104,72000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 9TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14346,Roads,Completed,NH-ANNA NAGAR,104,58000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 10TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14349,Roads,Completed,NH-ANNA NAGAR,104,71800,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 11TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14355,Roads,Completed,NH-ANNA NAGAR,104,59000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 12TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14356,Roads,Completed,NH-ANNA NAGAR,104,58000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 13TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14357,Roads,Completed,NH-ANNA NAGAR,104,100000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 14TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14358,Roads,Completed,NH-ANNA NAGAR,104,58700,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NEW BHOOPATHY NAGAR 15TH LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14360,Roads,Completed,NH-ANNA NAGAR,104,180800,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT LADERS GATE 1ST LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2019-20 NH/2018-19/14361,Roads,Completed,NH-ANNA NAGAR,104,242000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT LADERS GATE 2ND LANE IN DIV-104, UNIT-23, ZONE-8",Own Sources,8,2018-19,2020-21 NH/2018-19/4390,Buildings,Completed,NH-ANNA NAGAR,104,295000,"REPAIRS & IMPROVEMENTS TO MULTIPURPOSE HALL AT PULLAPURAM IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/4391,Buildings,Completed,NH-ANNA NAGAR,104,153000,"PROVIDING BORE AND WATER SUPPLY ARRANGEMENTS TO DIVISION OFFICE AT LETTANGS ROAD IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/5098,Playfields,Completed,NH-ANNA NAGAR,104,300000,"PROVIDING AND FIXING GYM APPARATUS AT NEHRU PARK IN DIVISION 104, UNIT 23, ZONE 8. (MLA FUND 2018-19)",MLACDS,8,2018-19,2019-20 NH/2018-19/5101,Playfields,Completed,NH-ANNA NAGAR,104,500000,"PROVIDING AND FIXING GYM APPARATUS AT SASTRI NAGAR IN DIVISION 104, UNIT 23, ZONE 8. (MLA FUND)",MLACDS,8,2018-19,2019-20 NH/2018-19/9005,Buildings,Completed,NH-ANNA NAGAR,104,939000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION 104, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2018-19 NH/2018-19/9008,Roads,Completed,NH-ANNA NAGAR,104,930000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION 104, UNIT 23, ZONE 8.",Own Sources,8,2018-19,2019-20 BR/2018-19/15642,Roads,Completed,BR-Bus Route Roads,105,148600,Restoration of OFC road cut made by AIrtel at various bus route road in zone-VIII( Deposit code- 57/0087/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/15647,Road Cut,Completed,BR-Bus Route Roads,105,658000,Restoration of OFc road cut made by airtel at various Bus Route Roads in Zone-VIII (Deposit Code 57/0281/2018-19),Deposit Works,8,2018-19,2019-20 BR/2018-19/15650,Road Cut,Completed,BR-Bus Route Roads,105,859000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-VIII (Deposit Code-57/0233/2018-2019),Deposit Works,8,2018-19,2019-20 D/2018-19/9405,Storm Water Drain,Completed,D-Storm Water Drains,105,48243000,Construction of Storm Water Drain at Perumal Koil Street on East Side and 10 Other Roads in Zone - 8 - Package - 36.,Grants,8,2018-19,2020-21 L/2018-19/13995,Electrical,Completed,L-Electrical,105,197600,"Proposal for fixing of 505 nos. of LED Fittings and removal of 505 Nos. of Sodium vapour lamp fitting at various places in div 105, 106 and 108 in zone VIII",Own Sources,8,2018-19,2019-20 L/2018-19/5784,Electrical,Completed,L-Electrical,105,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Corporation Hospital, C- Block, Pandian Street, MMDA Colony in Div. 105 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/0616,Roads,Completed,NH-ANNA NAGAR,105,500000,"Attending Patch work at Seethammal Avenue in Division-105, Unit-22, Zone-8",Own Sources,8,2018-19,2018-19 NH/2018-19/12360,Buildings,Completed,NH-ANNA NAGAR,105,409000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT MUTHUMARI AMMAN KOIL STREET IN DN-105,U-22,ZONE-08",Own Sources,8,2018-19,2019-20 NH/2018-19/12368,Buildings,Completed,NH-ANNA NAGAR,105,110000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT SBI STAFF COLONY 6TH STREET,kALKI NAGAR IN DN-105,U-22,ZONE-08",Own Sources,8,2018-19,2019-20 NH/2018-19/14439,Roads,Completed,NH-ANNA NAGAR,105,361600,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT PALLAVAN STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14442,Roads,Completed,NH-ANNA NAGAR,105,610000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT SIVASUBRAMANIYAN NAGAR IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14451,Roads,Completed,NH-ANNA NAGAR,105,1181800,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT ANNAI SATHYA NAGAR 2ND STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14467,Roads,Completed,NH-ANNA NAGAR,105,140000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIRUPOORKUMARAN 1ST LANE IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14468,Roads,Completed,NH-ANNA NAGAR,105,188000,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT THIRUPOORKUMARAN CROSS STREET LANE IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14469,Roads,Completed,NH-ANNA NAGAR,105,223500,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT NAVALAR STREET (RANI ANNA NAGAR) IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14470,Roads,Completed,NH-ANNA NAGAR,105,223500,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT POOMBUKAR STREET (RANI ANNA NAGAR) IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14476,Roads,Completed,NH-ANNA NAGAR,105,341700,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT BHARATHIDASAN 2ND CROSS STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14481,Roads,Completed,NH-ANNA NAGAR,105,157400,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SRI VENKATESHA PERUMAL NAGAR IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14591,Roads,Completed,NH-ANNA NAGAR,105,234400,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SENTHIL NAGAR 4TH STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14594,Roads,Completed,NH-ANNA NAGAR,105,1529200,"IMPROVEMENT TO THE INTERIOR BT ROAD AT JANAKIRAM COLONY MAIN ROAD IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14595,Roads,Completed,NH-ANNA NAGAR,105,179100,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RAJIV GANDHI STREET (P H ROAD) IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14596,Roads,Completed,NH-ANNA NAGAR,105,532800,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RAMAKRISHNA STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14597,Roads,Completed,NH-ANNA NAGAR,105,131600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT AMBEDKAR STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14598,Roads,Completed,NH-ANNA NAGAR,105,395500,"IMPROVEMENT TO THE INTERIOR BT ROAD AT JAGANATHA NAGAR 2ND MAIN ROAD IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14599,Roads,Completed,NH-ANNA NAGAR,105,292400,"IMPROVEMENT TO THE INTERIOR BT ROAD AT PERUMAL KOIL GARDEN STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14600,Roads,Completed,NH-ANNA NAGAR,105,262500,"IMPROVEMENT TO THE INTERIOR BT ROAD AT JEEVARATHINAM STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14601,Roads,Completed,NH-ANNA NAGAR,105,64100,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SAKTHI NAGAR EAST STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14602,Roads,Completed,NH-ANNA NAGAR,105,648000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT MURUGESHAN STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14603,Roads,Completed,NH-ANNA NAGAR,105,553200,"IMPROVEMENT TO THE INTERIOR BT ROAD AT SAKTHI NAGAR MAIN ROAD IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14604,Roads,Completed,NH-ANNA NAGAR,105,454900,"IMPROVEMENT TO THE INTERIOR BT ROAD AT VATHALAKUNDU ARUMUGAM MAIN ROAD IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14619,Roads,Completed,NH-ANNA NAGAR,105,293500,"IMPROVEMENT TO THE INTERIOR BT ROAD AT KANNAGI STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14620,Roads,Completed,NH-ANNA NAGAR,105,695300,"IMPROVEMENT TO THE INTERIOR BT ROAD AT WATER TANK ROAD (M M D A COLONY) IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14621,Roads,Completed,NH-ANNA NAGAR,105,669400,"IMPROVEMENT TO THE INTERIOR BT ROAD AT MAHATMA GANDHI STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14622,Roads,Completed,NH-ANNA NAGAR,105,651000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT GNANA VINAYAGAR KOIL STREET ( M M D A ) IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14623,Roads,Completed,NH-ANNA NAGAR,105,928300,"IMPROVEMENT TO THE INTERIOR BT ROAD AT AMBEDKAR STREET IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/4340,Buildings,Completed,NH-ANNA NAGAR,105,160000,"Providing Bore and Water Supply Arrangement at CMS C-Block, School street, in Dn-105, U-22, Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/5144,Buildings,Completed,NH-ANNA NAGAR,105,230000,"REPAIR AND IMPROVEMENT TO COMMUNITY HALL AT MMDA COLONY MAIN ROAD ARUMBAKKAM IN DN-105, U-22, Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7326,Storm Water Drain,Completed,NH-ANNA NAGAR,105,800000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7327,Storm Water Drain,Completed,NH-ANNA NAGAR,105,317000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2018-19,2018-19 BR/2018-19/15660,Road Cut,Completed,BR-Bus Route Roads,106,89000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in zone-IX (Deposit Code-57/0235/2018-19,Deposit Works,8,2018-19,2019-20 BR/2018-19/6540,Roads,Completed,BR-Bus Route Roads,106,61000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DN.106, ZONE-08. (57/0426/2017-18) PACKAGE-11.",Deposit Works,8,2018-19,2018-19 BR/2018-19/7337,Roads,Completed,BR-Bus Route Roads,106,94000,Roadcut restoration made by CMWSSB at Nelson Manickam Road in zone-8 against challan no:BR/2017-18/0022113.,Deposit Works,8,2018-19,2019-20 BR/2018-19/7341,Roads,Completed,BR-Bus Route Roads,106,19500,Roadcut restoration made by CMWSSB at Nelson Manickam Road in zone-8 against challan no:BR/2017-18/0031892.,Deposit Works,8,2018-19,2019-20 D/2018-19/9392,Storm Water Drain,Completed,D-Storm Water Drains,106,50825000,Construction of Storm Water Drain at Nelson Manickam Road and Police Manickam Road in Zone - 8 - Package - 29.,Grants,8,2018-19,2020-21 L/2018-19/3451,Electrical,Completed,L-Electrical,106,198000,Electrification work at care and protection centre for children at Muthirulandi colony in div 106 zone VIII Area.,Own Sources,8,2018-19,2018-19 L/2018-19/5786,Electrical,Completed,L-Electrical,106,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Corporation Hospital, 6th street Collector Colony, Aasath Nagar, in Div. 106 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/0676,Buildings,Completed,NH-ANNA NAGAR,106,442000,"RESTORATION OF DAMAGE ANGANWADI AT VARIOUS PLACES IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/12366,Electrical,Completed,NH-ANNA NAGAR,106,414000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT COLLECTORATE COLONY MAIN ROAD IN DN-106,U-22,ZONE-08",Own Sources,8,2018-19,2019-20 NH/2018-19/12367,Buildings,Completed,NH-ANNA NAGAR,106,100000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM PHASE-2 AT COLLOECTRATE COLONY 6TH CROSS STREET IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2018-19,2019-20 NH/2018-19/14270,Roads,Completed,NH-ANNA NAGAR,106,361200,"IMPROVEMENT TO THE INTERIOR BT AT ROAD RANGANAYAGI STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14271,Roads,Completed,NH-ANNA NAGAR,106,645500,"IMPROVEMENT TO THE INTERIOR BT AT ROAD THIRUVALLUVAR STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14272,Roads,Completed,NH-ANNA NAGAR,106,469300,"IMPROVEMENT TO THE INTERIOR BT ROAD AT VANILAI ARASU STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14274,Roads,Completed,NH-ANNA NAGAR,106,489000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RAILWAY COLONY 2ND STREET EXTENSION IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14275,Roads,Completed,NH-ANNA NAGAR,106,710200,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RAILWAY COLONY 2ND STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14276,Roads,Completed,NH-ANNA NAGAR,106,514000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RAILWAY COLONY 1ST STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14277,Roads,Completed,NH-ANNA NAGAR,106,1019500,"IMPROVEMENT TO THE INTERIOR BT ROAD AT METAL FACTORY ROAD IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14278,Roads,Completed,NH-ANNA NAGAR,106,833600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT BARATHIYAR STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14280,Roads,Completed,NH-ANNA NAGAR,106,486700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT V O C COLONY 3RD STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14281,Roads,Completed,NH-ANNA NAGAR,106,540700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT V O C COLONY 2ND STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14282,Roads,Completed,NH-ANNA NAGAR,106,828700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT V O C COLONY 1ST STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14283,Roads,Completed,NH-ANNA NAGAR,106,179100,"IMPROVEMENT TO THE INTERIOR BT ROAD AT COLLECTORATE COLONY 2ND CROSS STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14284,Roads,Completed,NH-ANNA NAGAR,106,71000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT KANNAPPAN STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14285,Roads,Completed,NH-ANNA NAGAR,106,233700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT DURAISAMY STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14286,Roads,Completed,NH-ANNA NAGAR,106,233700,"IMPROVEMENT TO THE INTERIOR BT ROAD AT INDIRA GANDHI NAGAR 8TH STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14287,Roads,Completed,NH-ANNA NAGAR,106,192600,"IMPROVEMENT TO THE INTERIOR BT ROAD AT COLLECTORATE COLONY 4TH CROSS STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14288,Roads,Completed,NH-ANNA NAGAR,106,350100,"IMPROVEMENT TO THE INTERIOR BT ROAD AT PERUMAL KOIL STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14293,Roads,Completed,NH-ANNA NAGAR,106,798000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT KANNAIAH STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14294,Roads,Completed,NH-ANNA NAGAR,106,901400,"IMPROVEMENT TO THE INTERIOR BT ROAD AT RAJA RAM METHA NAGAR MAIN ROAD IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14354,Roads,Completed,NH-ANNA NAGAR,106,250500,"PROVIDING AND LAYING OF INTERIOR CEMENT CONCRETE ROAD AT V O C COLONY LANE IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/8226,Storm Water Drain,Completed,NH-ANNA NAGAR,106,630000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DN-106,U-22, Z-08",Own Sources,8,2018-19,2018-19 NH/2018-19/8233,Storm Water Drain,Completed,NH-ANNA NAGAR,106,505000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DN-106, U-22, Z-08",Own Sources,8,2018-19,2018-19 BR/2018-19/10596,Road Cut,Completed,BR-Bus Route Roads,107,17662,Restoration of OFC road cut made by JIO Communication Ltd in Mayor Ranganathan street (gangu Reddy Bridge) and other roads in Zone 8,Deposit Works,8,2018-19,2019-20 BR/2018-19/10597,Road Cut,Completed,BR-Bus Route Roads,107,88311,"Restoration of OFC road cut made by JIO Communication LtdMC Nicholas Road,mayor Ramanathan, Ranganathapuram 3rd steert and other roads in Zone 8",Deposit Works,8,2018-19,2019-20 BR/2018-19/10598,Road Cut,Completed,BR-Bus Route Roads,107,35324,Restoration of OFC road cut made by JIO Communication Ltd 4th Main Road in Zone 8,Deposit Works,8,2018-19,2019-20 BR/2018-19/10601,Road Cut,Completed,BR-Bus Route Roads,107,70649,"Restoration of OFC road cut made by JIO Communication Ltd Dr.Natesan Road,Haddows Road and other roads . in Zone 9",Deposit Works,8,2018-19,2019-20 BR/2018-19/10602,Road Cut,Completed,BR-Bus Route Roads,107,88311,"Restoration of OFC road cut made by JIO Communication Ltd Jayammal street,poes road,poes 2nd street. and other roads in Zone 9",Deposit Works,8,2018-19,2019-20 BR/2018-19/10603,Road Cut,Completed,BR-Bus Route Roads,107,35324,Restoration of OFC road cut made by JIO Communication Ltd Pathari Street and other street in Zone 9,Deposit Works,8,2018-19,2019-20 BR/2018-19/10604,Road Cut,Completed,BR-Bus Route Roads,107,97142,"Restoration of OFC road cut made by JIO Communication Ltd Sterling 3rd Cross Street,North usman road and other roads in Zone 9",Deposit Works,8,2018-19,2019-20 BR/2018-19/10605,Road Cut,Completed,BR-Bus Route Roads,107,114805,"Restoration of OFC road cut made by JIO Communication Ltd Cathrdral road,TTK Road and other roads in Zone 9",Deposit Works,8,2018-19,2019-20 BR/2018-19/10606,Road Cut,Completed,BR-Bus Route Roads,107,44155,Restoration of OFC road cut made by JIO Communication Ltd Anderson Road and other roads in Zone 9,Deposit Works,8,2018-19,2019-20 BR/2018-19/10607,Road Cut,Completed,BR-Bus Route Roads,107,70649,Restoration of OFC road cut made by JIO Communication Ltd Peter's Road and other roads in Zone 9,Deposit Works,8,2018-19,2019-20 BR/2018-19/10608,Road Cut,Completed,BR-Bus Route Roads,107,105973,"Restoration of OFC road cut made by JIO Communication Ltd Oliver Road ,32nd cross street and other roads in Zone 9",Deposit Works,8,2018-19,2019-20 BR/2018-19/10609,Road Cut,Completed,BR-Bus Route Roads,107,105973,"Restoration of OFC road cut made by JIO Communication Ltd Sydenhams road,choolai road,Elephant Gate road and other roads in Zone 9",Deposit Works,8,2018-19,2019-20 BR/2018-19/10610,Road Cut,Completed,BR-Bus Route Roads,107,52986,Restoration of OFC road cut made by JIO Communication Ltd Uthamar Gandhi Salai and other roads in Zone 9,Deposit Works,8,2018-19,2019-20 BR/2018-19/10611,Road Cut,Completed,BR-Bus Route Roads,107,1254024,"Restoration of OFC road cut made by JIO Communication Ltd Kamarajar salai,santhome high road, south canal bank road,vekantakrishan higer road and other roads in Zone 9",Deposit Works,8,2018-19,2019-20 BR/2018-19/10614,Road Cut,Completed,BR-Bus Route Roads,107,35324,"Restoration of OFC road cut made by JIO Communication Ltd 1st Main Road Extension,Arcot road and other roads in Zone 10",Deposit Works,8,2018-19,2019-20 BR/2018-19/10615,Road Cut,Completed,BR-Bus Route Roads,107,17030,Restoration of OFC road cut made by JIO Communication Ltd Vembuli Subedhar street and other roads in Zone 12,Deposit Works,8,2018-19,2019-20 BR/2018-19/10616,Road Cut,Completed,BR-Bus Route Roads,107,110698,Restoration of OFC road cut made by JIO Communication Ltd Velacherry Main road and other roads in Zone 13,Deposit Works,8,2018-19,2019-20 BR/2018-19/18280,Road Cut,Completed,BR-Bus Route Roads,107,602000,"Restoration of roadcut attending patchwork at various street in Dn -107, Unit-23, Zone -8",Deposit Works,8,2018-19,2020-21 BR/2018-19/5489,Road Cut,Completed,BR-Bus Route Roads,107,1269000,"Restoration of roadcut made by CMWSSB at Mc Nichols Road from the jn of Spurtank road in Dn-107, Zone-8(Chellan code :57/0841/2017-18)",Deposit Works,8,2018-19,2019-20 D/2018-19/9409,Storm Water Drain,Completed,D-Storm Water Drains,107,36066000,"Construction of Storm Water Drain at Nathan Street and 3 other Roads in Zone - 8,Sivan Koil 5th Street and 2 Other Roads in Zone - 9 and Kumaran Colony 2nd Street and 7 Other Roads in Zone - 10 - Package - 38",Grants,8,2018-19,2019-20 NH/2018-19/0024,Roads,Completed,NH-ANNA NAGAR,107,244400,"IMPROVEMENT TO THE BT ROAD AT MANGALAPURAM 8th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/11061,Buildings,Completed,NH-ANNA NAGAR,107,2777680,"PROPOSED CONSTRUCTION OF GYM BUILDING AT VENKATACHALAPATHY STREET IN DIVISION-107, UNIT-23, ZONE-08. (MLA FUND 2018-19)",MLACDS,8,2018-19,2019-20 NH/2018-19/11134,Buildings,Completed,NH-ANNA NAGAR,107,950000,"PROVIDING GYM EQUIPMENTS AT MAYOR RAMANATHAN SALAI (SPUR TANK ROAD ) IN DIVISION-107, UNIT-23, ZONE-08. (MLA FUND)",MLACDS,8,2018-19,2019-20 NH/2018-19/11808,Buildings,Completed,NH-ANNA NAGAR,107,2450000,"IMPROVEMENTS WORKS TO COMMUNITY HALL AT MAYOR SATHYAMOORTHY SALAI IN DIVISION-107,UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/12315,Buildings,Completed,NH-ANNA NAGAR,107,324000,"REPAIRS AND IMPROVEMENTS WORKS AT AMMAUNAVAGAM AT MANGALAPURAM 16th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/12350,Buildings,Completed,NH-ANNA NAGAR,107,131000,"REPAIRS AND IMPROVEMENTS WORKS AT AMMAUNAVAGAM AT VENKATACHALAPATHY STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/13290,Buildings,Completed,NH-ANNA NAGAR,107,2231847,"PROPOSED CONSTRUCTION OF KITCHEN SHED AT MS NAGAR MIDDLE SCHOOL IN DIVISION-107,UNIT-23, ZONE-08.(MLA FUND)",MLACDS,8,2018-19,2019-20 NH/2018-19/17301,Buildings,Completed,NH-ANNA NAGAR,107,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE UPHC HOSPITAL AT SCHOOL ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/17476,Roads,Completed,NH-ANNA NAGAR,107,175000,"IMPROVEMENT TO THE BT ROAD AT MANGALAPURAM 10th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/17477,Roads,Completed,NH-ANNA NAGAR,107,189000,"IMPROVEMENT TO THE BT ROAD AT MANGALAPURAM 11th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/17478,Roads,Completed,NH-ANNA NAGAR,107,651000,"IMPROVEMENT TO THE BT ROAD AT JAGANATHAPURAM 4th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/17888,Buildings,Completed,NH-ANNA NAGAR,107,999000,"PROVIDING GYM EQUIPMENTS FOR GYM BUILDING AT NEW BHOOPATHI NAGAR MAIN ROAD IN DIVISION-104, UNIT-23, ZONE-08. (MP FUND)",MPLADS,8,2018-19,2020-21 NH/2018-19/2337,Roads,Completed,NH-ANNA NAGAR,107,244400,"IMPROVEMENT TO THE BT ROAD AT MANGALAPURAM 7th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/2341,Roads,Completed,NH-ANNA NAGAR,107,190600,"IMPROVEMENT TO THE BT ROAD AT MANGALAPURAM 6th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/3917,Roads,Completed,NH-ANNA NAGAR,107,464200,"IMPROVEMENT TO THE BT ROAD AT NOWROJI ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/4288,Roads,Completed,NH-ANNA NAGAR,107,945300,"IMPROVEMENT TO THE BT ROAD AT CHARI ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/4291,Roads,Completed,NH-ANNA NAGAR,107,721100,"IMPROVEMENT TO THE BT ROAD AT VAITHIYANATHAN LANE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/4293,Roads,Completed,NH-ANNA NAGAR,107,710200,"IMPROVEMENT TO THE BT ROAD AT MUTHIAPPAN STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/4294,Roads,Completed,NH-ANNA NAGAR,107,788500,"IMPROVEMENT TO THE BT ROAD AT ARUNACHALAM STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/4300,Roads,Completed,NH-ANNA NAGAR,107,912600,"IMPROVEMENT TO THE BT ROAD AT MANGALAPURAM 5th STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/7012,Subway,Completed,NH-ANNA NAGAR,107,275000,"MAINTENANCE OF HARRINGTON ROAD SUBWAY ENGAGING OF WATCH MAN AND ELECTRICIAN FOR FOUR MONTHS IN DIVISION-107 UNIT-23, ZONE-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7629,Storm Water Drain,Completed,NH-ANNA NAGAR,107,655000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DN-107,U-23,Z-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/8925,Playfields,Completed,NH-ANNA NAGAR,107,2100000,"CONSTRUCTION OF GALLERY AND IMPROVEMENTS TO FOOTBALL PLAY GROUND AT MAYOR SATHYAMOORTHY SALAI DR.AMBEDKAR PLAY GROUND IN DIVISION-107, UNIT-23, ZONE-08.(MLA FUND)",MLACDS,8,2018-19,2019-20 NH/2018-19/8927,Buildings,Completed,NH-ANNA NAGAR,107,2100000,"PROPOSED CONSTRUCTION OF GYM AT DR.AMBEDKAR PLAY GROUND AT MAYOR SATHYAMOORTHY SALAI IN DIVISION-107, UNIT-23, ZONE-08. (MLA FUND)",MLACDS,8,2018-19,2019-20 NH/2018-19/9027,Storm Water Drain,Completed,NH-ANNA NAGAR,107,655000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DN-107,U-23,Z-8.",Own Sources,8,2018-19,2018-19 L/2018-19/13098,Electrical,Completed,L-Electrical,108,194900,Proposal for fixing of 498 nos. of LED Fittings and removal of 498 nos. of Sodium vapour lamp fitting at various places in div 108 in zone VIII,Own Sources,8,2018-19,2019-20 L/2018-19/5789,Electrical,Completed,L-Electrical,108,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Corporation High School, Bhagat Singh Street, MMDA Colony in Div. 108 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 L/2018-19/5790,Electrical,Completed,L-Electrical,108,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Corporation School, O- Block, NSK Street, MMDA Colony in Div. 108 Zone-VIII.",SMART CITY - ELECTRICAL,8,2018-19,2019-20 NH/2018-19/12365,Buildings,Completed,NH-ANNA NAGAR,108,390000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT M.G.R 3RD STREET P-BLOCK IN DN-108,U-22,ZONE-08",Own Sources,8,2018-19,2019-20 NH/2018-19/12369,Buildings,Completed,NH-ANNA NAGAR,108,135000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM MMDA BUS TERMINUS IN DN-108,U-22,ZONE-08",Own Sources,8,2018-19,2019-20 NH/2018-19/14317,Roads,Completed,NH-ANNA NAGAR,108,1092000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT LOGANATHAN NAGAR 1ST STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14318,Roads,Completed,NH-ANNA NAGAR,108,693000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT LOGANATHAN NAGAR 3RD STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14320,Roads,Completed,NH-ANNA NAGAR,108,888000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT LOGANATHAN NAGAR 2ND STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14322,Roads,Completed,NH-ANNA NAGAR,108,1875800,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT VEERAPANDI NAGAR 1ST STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14323,Roads,Completed,NH-ANNA NAGAR,108,772100,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BHARATHI STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14324,Roads,Completed,NH-ANNA NAGAR,108,324400,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT SUBRAMANI STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14325,Roads,Completed,NH-ANNA NAGAR,108,1515000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT KANIYAPPAN STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14326,Roads,Completed,NH-ANNA NAGAR,108,592200,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT SUBBARAYAN STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14327,Roads,Completed,NH-ANNA NAGAR,108,216300,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT KRISHNAVENIAMMAL STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14328,Roads,Completed,NH-ANNA NAGAR,108,56396,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT SRIDARAN STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14330,Roads,Completed,NH-ANNA NAGAR,108,179100,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT PARI 1ST CROSS STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2020-21 NH/2018-19/14331,Roads,Completed,NH-ANNA NAGAR,108,1934800,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT PARI STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14332,Roads,Completed,NH-ANNA NAGAR,108,665800,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT KALAIMAGAL STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14333,Roads,Completed,NH-ANNA NAGAR,108,856200,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT RAJESHWARI STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14334,Roads,Completed,NH-ANNA NAGAR,108,1193900,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT KAMARAJAR NAGAR 3RD STREET EXTENSION IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14335,Roads,Completed,NH-ANNA NAGAR,108,1908800,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT KAMARAJAR NAGAR 3RD STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/14441,Roads,Completed,NH-ANNA NAGAR,108,343800,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MULLAI STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14443,Roads,Completed,NH-ANNA NAGAR,108,789000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT VEERAPANDI NAGAR 2ND STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/14444,Roads,Completed,NH-ANNA NAGAR,108,473800,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT ANNAL KAMARAJAR STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2018-19 NH/2018-19/16558,Parks,Completed,NH-ANNA NAGAR,108,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE R-BLOCK PARK AT ELANGO STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2018-19,2019-20 NH/2018-19/7634,Storm Water Drain,Completed,NH-ANNA NAGAR,108,990000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2018-19,2018-19 NH/2018-19/7635,Storm Water Drain,Completed,NH-ANNA NAGAR,108,990000,"DESILTING AND REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2018-19,2018-19 BR/2018-19/15661,Road Cut,Completed,BR-Bus Route Roads,109,89000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX (Deposit code-57/0276/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/15666,Road Cut,Completed,BR-Bus Route Roads,109,956000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX (Deposit Code-57/0365/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/3178,Roads,Completed,BR-Bus Route Roads,109,1350000,PROPOSED LAYING OF CENTRE MEDIAN AT TANK BUNK ROAD FROM THE JN OF STERLING AVENUE TO THE JN OF MAHALINGA PURAM MAIN ROAD IN ZONE -9,Own Sources,9,2018-19,2019-20 L/2018-19/5804,Electrical,Completed,L-Electrical,109,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS Thiruvalluvarpuram,Sankarapuram main road, Choolaimedu, Ch-92, in Div-109, Zone-IX .(E.B.Account no-236.025.328)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5806,Electrical,Completed,L-Electrical,109,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, Sankarapuram, Choolaimedu, Ch-92, in Div-109, Zone-IX .(E.B.Account no-236.025.88)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0358,Storm Water Drain,Completed,NJ-TEYNAMPET,109,275000,"REPAIRS TO STORM WATER DRAIN AT NELSON MANICKAM ROAD (SOUTH SIDE) IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0360,Storm Water Drain,Completed,NJ-TEYNAMPET,109,100000,"REPAIRS TO STORM WATER DRAIN AT BAJANAI KOIL STREET (EAST) IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/11559,Storm Water Drain,Completed,NJ-TEYNAMPET,109,542000,"Desilting the storm water drain at various Streets in Dn-109,Unit- 24, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11560,Storm Water Drain,Completed,NJ-TEYNAMPET,109,937000,"Minor repair to the existing storm water drain at various Streets in Dn-109,Unit- 24,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1225,Roads,Completed,NJ-TEYNAMPET,109,2417000,"IMPROVEMENTS TO THE BT ROAD AT BASHA STREET IN DIVISION-109, UNIT-24, ZONE-IX",Own Sources,9,2018-19,2019-20 NJ/2018-19/1239,Roads,Completed,NJ-TEYNAMPET,109,5110000,"IMPROVEMENTS TO THE BT ROAD AT ANNANEDUMPATHAI IN DIVISION-109, UNIT-24, ZONE-IX",Own Sources,9,2018-19,2019-20 NJ/2018-19/1240,Roads,Completed,NJ-TEYNAMPET,109,1550000,"IMPROVEMENTS TO THE BT ROAD AT GILL NAGAR 2nd STREET IN DIVISION-109, UNIT-24, ZONE-IX",Own Sources,9,2018-19,2019-20 NJ/2018-19/1243,Roads,Completed,NJ-TEYNAMPET,109,1597000,"CONSTRUCTION OF DAMAGED STORM WATER DRAIN UNDER M.L.A. SCHEME AT PERIYAR PATHAI & SIVAN KOIL STREET (From Annanedumpathai Junction To Vanniar Street Junction) IN DIVISION-109, UNIT-24, ZONE-09.",MLACDS,9,2018-19,2018-19 NJ/2018-19/1437,Roads,Completed,NJ-TEYNAMPET,109,1376976,"IMPROVEMENTS TO THE BT ROAD AT KANTHAPPAN COLONY IN DIVISION-109, UNIT-24, ZONE-IX.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16024,Parks,Completed,NJ-TEYNAMPET,109,675000,"ANNUAL MAINTENANCE OF GREATER CHENNAI PARK AT GILL NAGAR PARK IN DIVISION-109,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/16476,Roads,Completed,NJ-TEYNAMPET,109,300000,"REPAIRS TO EXISTING CENTRE MEDIAN AT NELSONMANICKKAM ROAD IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17228,Roads,Completed,NJ-TEYNAMPET,109,422000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Vannier 2nd Lane IN DIVISION-109, UNIT-24, ZONE-IX.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17229,Roads,Completed,NJ-TEYNAMPET,109,429000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Bajanai Koil Cross street (West) IN DIVISION-109, UNIT-24, ZONE-IX.",Own Sources,9,2018-19,2019-20 NJ/2018-19/2960,Parks,Completed,NJ-TEYNAMPET,109,159000,"ANNUAL MAINTENECE OF GILL NAGAR PARK (6 MONTHS) AT GILL NAGAR CENTRAL SCHOOL ROAD IN DIVISION-109, UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/8847,Buildings,Completed,NJ-TEYNAMPET,109,1500000,"PROVIDING 1000 LITRE LPH RO PLANT STATION and BORE WELL UNDER M.L.A.SCEME 2018-19 AT WEST NAMACHIVAYAPURAM PARK (NEAR AMMA UNAVAGAM) IN DIVISION-109,UNIT-24,ZONE-09.",MLACDS,9,2018-19,2020-21 NJ/2018-19/9129,Subway,Completed,NJ-TEYNAMPET,109,98000,"REPAIRS TO SUB WAY PUMP ROOM & REPAIRS TO 5HP DESALE MOTOR AT SUB WAY PUMP ROOM IN SERVICE ROAD IN DIVISION-109, UNIT-24, ZONE-09.",Own Sources,9,2018-19,2019-20 BR/2018-19/15286,Roads,Completed,BR-Bus Route Roads,110,194000,"RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS 109,110,111,118 AND 119 IN UNIT 24 ZONE 09",Deposit Works,9,2018-19,2019-20 BR/2018-19/15659,Road Cut,Completed,BR-Bus Route Roads,110,74000,Restoration of OFC road cut made by Reliance at various Bus Route Roads in Zone-IX (Deposit Code-57/0055/2018-2019),Deposit Works,9,2018-19,2019-20 BR/2018-19/2573,Footpath,Completed,BR-Bus Route Roads,110,336000,"Footpath Repair Works at Sterling Road in Dn-110, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/2574,Footpath,Completed,BR-Bus Route Roads,110,189000,"Footpath Repair works at Sterling Avenue in Dn-110, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/2576,Footpath,Completed,BR-Bus Route Roads,110,329000,"Footpath Repair works at Tank Bund Road in Dn-110, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/2577,Footpath,Completed,BR-Bus Route Roads,110,301000,"Footpath Repair Works at Mahalingapuram Main Road in Dn-110, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/2579,Footpath,Completed,BR-Bus Route Roads,110,308000,"Footpath Repair works at 70 Feet Scheme Road in Dn-110, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/6547,Footpath,Completed,BR-Bus Route Roads,110,19775000,"Forming Footpath at Valluvar Kottam High Road in Dn-110 & 113, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/8192,Road Cut,Completed,BR-Bus Route Roads,110,1140000,"Restoration of roadcut made by CMWSSB at Mahalingapuram Main road(from the jn of Flyover to the jn of loyala institute) in Dn -110, Zone -9",Deposit Works,9,2018-19,2018-19 BR/2018-19/9020,Road Cut,Completed,BR-Bus Route Roads,110,2170000,"Restoration of road cut Made by CMWSSB at Wheat Craft Road , Siva Ganga Road And The jn of Sterling Road in Dn -110, Zone - 9",Deposit Works,9,2018-19,2019-20 D/2018-19/9424,Storm Water Drain,Completed,D-Storm Water Drains,110,29915000,Construction of Storm Water Drain at Sterling Road and 2 other Roads in Zone - 9 - Package - 42.,Grants,9,2018-19,2020-21 L/2018-19/15170,Electrical,Completed,L-Electrical,110,189200,"Replacement of KIOSK pilla box at various loactions in div 110,Independence day park, Pushpa Nagar main Road, Kamarajapuram main road, Neelakandan Street, Kamdar nagar 2nd street and School Road",Own Sources,9,2018-19,2019-20 L/2018-19/5669,Electrical,Completed,L-Electrical,110,1892000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 25 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 4th Cross Street, Lake Area, Nungambakkam, Zonal office-9 in Div-110, Zone-IX .(E.B.Account no-171.049.302)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5675,Electrical,Completed,L-Electrical,110,462500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Girls Higher Sec. School , School Road in Div-110, Zone-IX .(E.B.Account no-171.078.3)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5676,Electrical,Completed,L-Electrical,110,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Boys Higher Sec. School , School Road in Div-110, Zone-IX .(E.B.Account no-171.078.8 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5678,Electrical,Completed,L-Electrical,110,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Pushpa nagar Health Post in Div-110, Zone-IX . (E.B.Account no-171.035.100)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5679,Electrical,Completed,L-Electrical,110,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Junior Engineer Officer- 110, No.22, Kutty Street,Nungambakkam, Ch-34, in Div-110, Zone-IX .(E.B.Account no-171.011.103)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5685,Electrical,Completed,L-Electrical,110,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Boys Higher Sec. School at School Road in Div-110, Zone-IX .(E.B.Account no-171.006.97)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5687,Electrical,Completed,L-Electrical,110,86300,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1Kwp Grid Tied Solar Rooftop including Civil works and earthing at Jayalakshmipuram Main Road CMS in Div-110, Zone-IX .(E.B.Account no-171.064.721)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5689,Electrical,Completed,L-Electrical,110,86300,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kamdar Nagar Main road ( Junction of 1st St., ) Night Shelter in Div-110, Zone-IX .(E.B.Account no- 171.003.322)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5987,Electrical,Completed,L-Electrical,110,183900,"Electrification Work at Div-113 CI office, Amma unavagam, Nungambakkam Burial Ground in Division-110 & 113 Zone-IX",Own Sources,9,2018-19,2018-19 L/2018-19/9629,Electrical,Completed,L-Electrical,110,198400,"Replacement of underground cables with HDPE pipe and overhead wires at Nungambakkam Subway service road and Tank bund 1st cross street in div 110, zone - 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/0344,Storm Water Drain,Completed,NJ-TEYNAMPET,110,100000,"REPAIRS TO STORM WATER DRAIN AT VALLUVAR KOTAM HIGH ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0348,Storm Water Drain,Completed,NJ-TEYNAMPET,110,250000,"REPAIRS TO STORM WATER DRAIN AT SCHOOL ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0350,Storm Water Drain,Completed,NJ-TEYNAMPET,110,100000,"REPAIRS TO STORM WATER DRAIN AT STERLING AVENUE IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0351,Storm Water Drain,Completed,NJ-TEYNAMPET,110,100000,"REPAIRS TO STORM WATER DRAIN AT STERLING ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0353,Storm Water Drain,Completed,NJ-TEYNAMPET,110,130000,"REPAIRS TO STORM WATER DRAIN AT KAMDHAR NAGAR MAIN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0355,Storm Water Drain,Completed,NJ-TEYNAMPET,110,100000,"REPAIRS TO STORM WATER DRAIN AT JAYALAKSHMIPURAM MAIN ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0357,Storm Water Drain,Completed,NJ-TEYNAMPET,110,200000,"REPAIRS TO STORM WATER DRAIN AT TANK BUND ROAD IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0361,Roads,Completed,NJ-TEYNAMPET,110,768000,"ATTENDING PATCH WORKS AT LAKE AREA 6th CROSS STREET IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0530,Buildings,Completed,NJ-TEYNAMPET,110,200000,"REPAIRS AND IMPROVEMENTS TO GCGH SCHOOL AT SCHOOL ROAD IN DIVISION-110,UNIT-24,ZONE-IX",Own Sources,9,2018-19,2018-19 NJ/2018-19/10648,Storm Water Drain,Completed,NJ-TEYNAMPET,110,830000,"Desilting the storm water drain at various Streets in Dn-110,Unit- 27, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10660,Storm Water Drain,Completed,NJ-TEYNAMPET,110,545000,"Minor repair to the existing storm water drain at various Streets in Dn-110, Unit- 24, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10879,Buildings,Completed,NJ-TEYNAMPET,110,997000,"REPAIRS AND IMPROVEMENT TO CONFERENCE HALL, VERANDAH, PROPERTY TAX COMPUTER ROOM AND AHO ROOM AT ZONAL OFFICE 9, LAKE AREA 4 TH CROSS STREET IN DIN 110,UNIT 24, ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/12247,Buildings,Completed,NJ-TEYNAMPET,110,4900000,"PROPOSED RENOVATION WORK AND INSTALLATION OF MODULAR WORK STATION IN GROUND FLOOR ZONAL OFFICE-09, GREATER CHENNAI CORPORATION AT NUNGAMBAKKAM IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2020-21 NJ/2018-19/12311,Buildings,Completed,NJ-TEYNAMPET,110,746000,"IMPROVEMENT WORKS TO ZONAL OFFICER ROOM, ZONE-09 OFFICE IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/1461,Roads,Completed,NJ-TEYNAMPET,110,3938000,"IMPROVEMENTS TO THE BT ROAD AT SCHOOL ROAD & JAYALAKSHMIPURAM 4TH STREET IN DIVISION-110, UNIT-24, ZONE-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16027,Parks,Completed,NJ-TEYNAMPET,110,197000,"ANNUAL MAINTENANCE OF GREATER CHENNAI PARK ON ANNA PARK AT VALLUVAR KOTTAM IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/16030,Parks,Completed,NJ-TEYNAMPET,110,671000,"ANNUAL MAINTENANCE OF GREATER CHENNAI PARK AT INDEPENDENCE DAY PARK IN VALLUVAR KOTTAM HIGH ROAD IN DIVISION-110,UNIT-24,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16475,Roads,Completed,NJ-TEYNAMPET,110,305000,"REPAIRS TO EXISTING CENTRE MEDIAN AT HARRINGTON ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17135,Parks,Completed,NJ-TEYNAMPET,110,230000,"MAINTENANCE OF GREATER CHENNAI PARK AT HARRINGTON ROAD PARK IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17269,Roads,Completed,NJ-TEYNAMPET,110,2406000,"IMPROVEMENTS TO THE CC ROAD AT KAMARAJAPURAM MAIN ROAD IN DIVISION-110, UNIT-24, ZONE-IX.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17270,Roads,Completed,NJ-TEYNAMPET,110,1205000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT KAMARAJAPURAM 1st STREET IN DIV 110,UNIT -24, ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17997,Buildings,Completed,NJ-TEYNAMPET,110,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT VALLUVAR KOTTAM MAIN ROAD (KUZHAKKARAI ROAD) IN DIV-110,U-24,Z-09",Own Sources,9,2018-19,2020-21 NJ/2018-19/2977,Parks,Completed,NJ-TEYNAMPET,110,280000,"ANNUAL MAINTANANCE OF INDEPENDENCE DAY PARK AT SCHOOL ROAD FOR (6 MONTHS) IN DIVISION-110,UNIT-24, ZONE-IX.",Own Sources,9,2018-19,2018-19 NJ/2018-19/2978,Parks,Completed,NJ-TEYNAMPET,110,460000,"ANNUAL MAINTENANCE OF ANNA PARK (6 MONTHS) AT VALLUVAR KOTTAM HIGH ROAD IN DIVISION-110,UNIT-24, ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/3151,Footpath,Completed,NJ-TEYNAMPET,110,1257000,"FORMING FOOT PATH AT RAJAJI 2ND STREET ON BOTH SIDES(UNDER MLA FUND 2018-2019) IN DN 110,UNIT 24,ZONE 9",MLACDS,9,2018-19,2018-19 NJ/2018-19/6139,Buildings,Completed,NJ-TEYNAMPET,110,125000,"IMPROVEMENT TO AMMA UNAVAGAM AT KUTTY STREET, DIN 110,UNIT 24,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/6985,Buildings,Completed,NJ-TEYNAMPET,110,1216000,"PROVIDING WATER SUPPLY ARRANGEMENT AND CONSTRUCTION OF SUMP AT CHENNAI GIRLS HIGH SECONDARY SCHOOL, SCHOOL ROAD(UNDER MLA FUND 2018-2019) IN DIN 110,UNIT-24,ZONE 9,",MLACDS,9,2018-19,2019-20 NJ/2018-19/7024,Buildings,Completed,NJ-TEYNAMPET,110,2000000,"PROVIDING NEW BORE WELL AND WATER SUPPLY ARRANGEMENT FOR ANGANWADI CENTRES AT APPASAMY STREET(33603020201,33603020202,33603020203,33603020204), JAYALAKSHMIPURAM MAIN ROAD(33603020205,33603020206), KAKKAN COLONY(33603020215),PUSHPA NAGAR 2ND STREET(33603020209,33603020210), LAKE AREA 4TH CROSS STREET(33603020212,33603020213) AND TANK BUND ROAD(33603020207,33603020208 (UNDER MLA FUND 2018-2019)IN DN 110, UNIT 24,ZONE9",MLACDS,9,2018-19,2020-21 NJ/2018-19/8035,Buildings,Completed,NJ-TEYNAMPET,110,210000,"IMPROVEMENTS TO AMMAUNAVAGAM AT SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2018-19,2019-20 BR/2018-19/15665,Road Cut,Completed,BR-Bus Route Roads,111,274000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX(Deposit Code-57/0290/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/15989,Road Cut,Completed,BR-Bus Route Roads,111,2490000,"Restoration of roadcut made by CMWSSB at Whites Road from the jn of Anna Salai to the jn of Smith Road in Dn-111, Zone - 9",Deposit Works,9,2018-19,2020-21 BR/2018-19/2567,Footpath,Completed,BR-Bus Route Roads,111,319000,"Footpath Repair works at Conronsmith Road in Dn-111, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/2571,Footpath,Completed,BR-Bus Route Roads,111,320000,"Footpath Repair works at Whites Road in Dn-111, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/2591,Footpath,Completed,BR-Bus Route Roads,111,736000,"Footpath Repair works at Greams Road in Dn-111, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/5135,Road Cut,Completed,BR-Bus Route Roads,111,860000,"Restoration of roadcut made by TANGEDCO at Greams Road in DN -111, Zone - 9",Deposit Works,9,2018-19,2018-19 BR/2018-19/6546,Footpath,Completed,BR-Bus Route Roads,111,15576000,"Forming Footpath at College Road in Dn-111, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/6548,Footpath,Completed,BR-Bus Route Roads,111,10712000,"Forming Footpath at Haddows Road in Dn-111, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/7435,Footpath,Completed,BR-Bus Route Roads,111,140000,"Footpath Repair Works at Binny Road in Dn-111, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/7436,Footpath,Completed,BR-Bus Route Roads,111,141000,"Footpath Repair Works at Pattulas Road in Dn-111, Zone-IX",Grants,9,2018-19,2019-20 D/2018-19/3188,Storm Water Drain,Completed,D-Storm Water Drains,111,9149000,"Construction of storm water drain of size 1200x1200mm along Pattullas road Southern side from Whites road junction to Annasalai in Dn- 111,Zone-IX.",Own Sources,9,2018-19,2019-20 D/2018-19/4239,Storm Water Drain,Completed,D-Storm Water Drains,111,6688000,"Construction of Storm water drain of size 900x900mm along Whites road Southern side from Smith road junction to Pattullas road junction in Dn-111,Zone-IX.",Own Sources,9,2018-19,2019-20 D/2018-19/4860,Storm Water Drain,Completed,D-Storm Water Drains,111,6688000,"Construction of Storm water drain of size 900x900mm along Whites road northern side from woods road junction to Pattullas road junction in Dn-111,Zone-IX.",Own Sources,9,2018-19,2020-21 L/2018-19/11166,Electrical,Completed,L-Electrical,111,171000,"Supply & Fixing of 10 Nos of Digital Timer Unit at Various Location in Gopalapuram Section ,div-111,119,121,zone-IX",Own Sources,9,2018-19,2019-20 L/2018-19/11167,Electrical,Completed,L-Electrical,111,188000,"Supply & Fixing of 11 Nos of Digital Timer Unit at Various Location in Gopalapuram Section ,div-111,119,121,zone-IX",Own Sources,9,2018-19,2019-20 L/2018-19/11168,Electrical,Completed,L-Electrical,111,131900,"Replacement of cable from pillar box to whites Rd Highmast in at R.H Road in Gopalapuram section, Div-111, Zone-IX",Own Sources,9,2018-19,2020-21 L/2018-19/13455,Electrical,Completed,L-Electrical,111,3073800,"PROVISION OF 8 NOS OF 8 MTR LAMP POST WITH SINGLE ARCH BKT, 24 NOS OF 8MTR LAMP POST WITH DOUBLE ARCH BKT ,2 NOS OF 8MTR LAMP POST WITH TRIPLE ARCH BKT AT ANNA SALAI FROM WHITES RD JN TO BINNY RD JN in Div 111,Zone-IX.(DUE TO CMRL WORK COMPLETED).",Deposit Works,9,2018-19,2020-21 L/2018-19/13456,Electrical,Completed,L-Electrical,111,1868900,"PROVISION OF 4 NOS OF 6 MTR LAMP POST WITH ST-BKT, 6 NOS OF 6MTR LAMP POST WITH SINGLE ARCH BKT , 26 NOS OF 8MTR WITH SINGLE ARCH BKT AT ANNA SALAI FROM WHITES RD JN TO BINNY RD JN in Div 111,Zone-IX",Deposit Works,9,2018-19,2019-20 L/2018-19/14088,Electrical,Completed,L-Electrical,111,195300,"WORK. Replacement of 270 Mtrs of 4 x 16 Sq.mm PVC Alu cable at Gopalapuram 2nd st and Various Places in Dn.111, Zone - IX",Own Sources,9,2018-19,2019-20 L/2018-19/14089,Electrical,Completed,L-Electrical,111,199100,"WORK. Replacement of 235 Mtrs of 4 x 16 Sq.mm PVC Alu cable at Gopalapuram 2nd street and various Places in Dn.111, Zone - IX",Own Sources,9,2018-19,2019-20 L/2018-19/14090,Electrical,Completed,L-Electrical,111,199600,"WORK. Replacement of 272 Mtrs of 4 x 16 Sq.mm PVC Alu cable at Pattulas Rd from jn Mount Rd to Post No 534 in Dn.111, Zone - IX",Own Sources,9,2018-19,2019-20 L/2018-19/14091,Electrical,Completed,L-Electrical,111,199700,"WORK. Replacement of 362 Mtrs of 4 x 16 Sq.mm of PVC Alu cable at Pattulas Rd from jn Mount Rd to Post No 534 to Post No 474 in Dn.111, Zone - IX",Own Sources,9,2018-19,2019-20 L/2018-19/14092,Electrical,Completed,L-Electrical,111,199700,"WORK. Replacement of 323 Mtrs of 3 1/2 x 25 Sq.mm PVC Alu cable at Whited Rd from jn of Pattullas Rd to Jn of RH Rd in Dn.111, Zone - IX(Express Avenue Side)",Own Sources,9,2018-19,2020-21 L/2018-19/14093,Electrical,Completed,L-Electrical,111,199900,"WORK. Replacement of 377 Mtrs of 4 x 16 Sq.mm PVC Alu cable at whites Rd from Chruch of South Indian secretariat to Post No 439 in Dn.111, Zone - IX",Own Sources,9,2018-19,2020-21 L/2018-19/4871,Electrical,Completed,L-Electrical,111,880000,"Electrification work for proposed Rewiring of Urban Primary Health centre(Waiting Hall,Paediatrician Room,Medical Officer Room,Counselling Room,Pharmacy Room,Laboratory Room,Stores Room,ccc Room,Recovery Room,Paediatric ward,Toilet, Maternity unit) at Aziz Mulk 2nd St,Division - 111 , Zone - IX.",Own Sources,9,2018-19,2020-21 L/2018-19/5865,Electrical,Completed,L-Electrical,111,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS, Modal school road in Div-111, Zone-IX .(E.B.Account no-131.005.120)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5866/C,Electrical,Completed,L-Electrical,111,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS,Modal school road in Div-111, Zone-IX .(E.B.Account no-131.005.141)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5867,Electrical,Completed,L-Electrical,111,387200,"Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital, Model school road in Div-111, Zone-IX .(E.B.Account no-131.007.186)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5868,Electrical,Completed,L-Electrical,111,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at COMMUNITY HALL, Model School Rd, in Div-111, Zone-IX .(E.B.Account no-131.005.154)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6472,Electrical,Completed,L-Electrical,111,4564500,"Work: Electrification work for CHS School Sringeri mutt Road, CMS Pf. Sanjivi Street, CKGS Nochi Kuppam., CHS Karneepagoda street School and CPS 4 th Trust Link Street , CMS Bells Rd, cms Arunchala St,Urudu School Valaba Agragaram and Cms Bangaru st ,CHS Model School Rd,CPS LLoyds Rd,CHS Veeraperumal Koil st in Division-111,114,119,121,125,126, Zone-IX.",Own Sources,9,2018-19,2019-20 NJ/2018-19/0335,Roads,Completed,NJ-TEYNAMPET,111,194000,"ATTENDING PATCH WORKS AT GOPALAPURAM 6th STREET IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0338,Storm Water Drain,Completed,NJ-TEYNAMPET,111,400000,"REPAIRS TO STORM WATER DRAIN AT CLUB HOUSE ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0340,Storm Water Drain,Completed,NJ-TEYNAMPET,111,100000,"REPAIRS TO STORM WATER DRAIN AT COLLAGE LANE IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0341,Storm Water Drain,Completed,NJ-TEYNAMPET,111,150000,"REPAIRS TO STORM WATER DRAIN AT ANDERSON ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0342,Storm Water Drain,Completed,NJ-TEYNAMPET,111,300000,"REPAIRS TO STORM WATER DRAIN AT kHADHAR NAWAS KHAN ROAD IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/10649,Storm Water Drain,Completed,NJ-TEYNAMPET,111,1288000,"Desilting the storm water drain at various Streets in Dn-111,Unit- 24, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10661,Storm Water Drain,Completed,NJ-TEYNAMPET,111,910000,"Minor repair to the existing storm water drain at various Streets in Dn-111,Unit- 27,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16382,Buildings,Completed,NJ-TEYNAMPET,111,504000,"REPAIRS AND MAINTENANCE TO THE CENTRE MEDIAN AT COLLEGE ROAD IN DIVISION-111, UNIT-24, ZONE-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16465,Buildings,Completed,NJ-TEYNAMPET,111,616000,"IMPROVEMENT TO CENTER MEDIAN AT GREAMS ROAD DIV - 111, UNIT 24, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17131,Parks,Completed,NJ-TEYNAMPET,111,713000,"MAINTENANCE OF GREATER CHENNAI PARK AT BINNY ROAD-SPENCER PLAZA PARK IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17132,Parks,Completed,NJ-TEYNAMPET,111,719000,"MAINTENACE OF GREATER CHENNAI PARK AT COLLEGE LANE PARK IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17133,Parks,Completed,NJ-TEYNAMPET,111,700000,"MAINTENANCE OF GREATER CHENNAI PARK AT WHITES ROAD PARK (SATYAM) INDIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17134,Parks,Completed,NJ-TEYNAMPET,111,197000,"MAINTENANCE OF GREATER CHENNAI PARK AT KO.SU.MANI PARK IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17176,Parks,Completed,NJ-TEYNAMPET,111,700000,"MAINTENANCE OF GREATER CHENNAI PARK AT NUNGAMBAKKAM 4TH LANE PARK IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17452,Roads,Completed,NJ-TEYNAMPET,111,2405000,"IMPROVEMENTS TO THE EXISTING BT ROAD AT Wallace Garden 3rd Street IN DIV-111, U-24, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17453,Roads,Completed,NJ-TEYNAMPET,111,1430000,"IMPROVEMENTS TO THE EXISTING BT ROAD AT West End Street & Gopalapuram 6th Street IN DIV-111, U-24, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17454,Roads,Completed,NJ-TEYNAMPET,111,2861000,"IMPROVEMENTS TO THE EXISTING BT ROAD AT Greams Lane & Modal School Road IN DIV-111, U-24, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/2979,Parks,Completed,NJ-TEYNAMPET,111,195000,"ANNUAL MAINTANANCE OF HARRINGTON ROAD PARK AT HARRINGTON ROAD FOR (6 MONTHS) IN DIVISION-110, UNIT-24,ZONE-IX.",Own Sources,9,2018-19,2018-19 NJ/2018-19/3117,Footpath,Completed,NJ-TEYNAMPET,111,2113000,"FORMING FOOT PATH AT PADMAVATHIAR ROAD FROM PETERS ROAD TO AVVAISHANMUGAM SALAI EASTERN SIDE(UNDER MLA FUND 2017-2018) IN DN 111,UNIT 24,ZONE 9",MLACDS,9,2018-19,2019-20 NJ/2018-19/3349,Parks,Completed,NJ-TEYNAMPET,111,384000,"ANNUAL MAINTENANCE OF SPENCER PLAZA PARK (6 MONTHS) AT BINNY ROAD IN DIVISION-111,UNIT-24, ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/3377,Parks,Completed,NJ-TEYNAMPET,111,300000,"ANNUAL MAINTENANCE OF PARK AT COLLAGE LANE PARK (6 MONTHS) IN DIVISION-111,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/3645,Buildings,Completed,NJ-TEYNAMPET,111,998000,"PROPOSED CONSTRUCTION OF COMPOUND WALL (UNDER M.L.A.FUND 2018-2019) AT GOPALAPURAM PLAY GROUND IN DN-111,UNIT-24, ZONE - 9",MLACDS,9,2018-19,2019-20 BR/2018-19/15662,Road Cut,Completed,BR-Bus Route Roads,112,75600,restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone IX (Deposit Code-57/0276/2018-19),Deposit Works,9,2018-19,2019-20 L/2018-19/5799,Electrical,Completed,L-Electrical,112,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHSS, Choolaimedu, Choolaimedu main road, Ch-92, in Div-112, Zone-IX .(E.B.Account no-236.001.38)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5802,Electrical,Completed,L-Electrical,112,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS, Puliyur 2nd main road, Kodambakkam, Ch-24, in Div-112, Zone-IX .(E.B.Account no-225.013.387)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/10400,Buildings,Completed,NJ-TEYNAMPET,112,750000,"PROVIDING 300 LITER LPH RO PLANT STATION and BORE WELL UNDER M.L.A.SCEME 2018-19 AT VARATHARAJAN PETTAI CHENNAI PRIMARY SCHOOL IN DIVISION-112, UNIT-26, ZONE-09.",MLACDS,9,2018-19,2019-20 NJ/2018-19/10577,Storm Water Drain,Completed,NJ-TEYNAMPET,112,458000,"Desilting the storm water drain at various Streets in Dn-112, Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10579,Storm Water Drain,Completed,NJ-TEYNAMPET,112,1242000,"Minor repair to the existing storm water drain at various Streets in Dn-112,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/12195,Roads,Completed,NJ-TEYNAMPET,112,1000000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT PULIYUR MAIN ROAD IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12196,Roads,Completed,NJ-TEYNAMPET,112,440000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT SOWRASTRA NAGAR 2ND STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12197,Roads,Completed,NJ-TEYNAMPET,112,410000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT SOWRASTRA NAGAR 5TH STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12198,Roads,Completed,NJ-TEYNAMPET,112,1179000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT PULIYUR 1ST MAIN ROAD IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12199,Roads,Completed,NJ-TEYNAMPET,112,785000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT PULIYUR 2ND MAIN ROAD IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12200,Roads,Completed,NJ-TEYNAMPET,112,174000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT MINOR TRUSTPURAM IIND CROSS STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12201,Roads,Completed,NJ-TEYNAMPET,112,753000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT SOUTH SIVAN KOIL STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12202,Roads,Completed,NJ-TEYNAMPET,112,570000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT VELLALA STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12203,Roads,Completed,NJ-TEYNAMPET,112,774000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT TRUSTPURAM II CROSS STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12204,Roads,Completed,NJ-TEYNAMPET,112,870000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT TRUSTPURAM 1ST CROSS STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12205,Roads,Completed,NJ-TEYNAMPET,112,900000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT TRUSTPURAM VI CROSS STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/12206,Roads,Completed,NJ-TEYNAMPET,112,1124000,"IMPROVEMENTS TO THE EXISTING B.T ROAD AT SIVAN KOIL STREET IN DIV -112, UNIT -26, ZONE -9. (MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/17455,Roads,Completed,NJ-TEYNAMPET,112,294000,"IMPROVEMENTS TO THE BT ROAD AT Moopan Maisthri 1st Street IN DIVISION-112, UNIT-26, ZONE-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17456,Roads,Completed,NJ-TEYNAMPET,112,951000,"IMPROVEMENTS TO THE BT ROAD AT Dayal Nagar Main Road IN DIVISION-112, UNIT-26, ZONE-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17457,Roads,Completed,NJ-TEYNAMPET,112,726000,"IMPROVEMENTS TO THE BT ROAD AT Sowrastra Nagar 6th Street IN DIVISION-112, UNIT-26, ZONE-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17458,Roads,Completed,NJ-TEYNAMPET,112,580000,"IMPROVEMENTS TO THE BT ROAD AT Minor Trustpuram 3rd Street (PART) IN DIVISION-112, UNIT-26, ZONE-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17460,Roads,Completed,NJ-TEYNAMPET,112,449000,"IMPROVEMENTS TO THE BT ROAD AT New Vellala Street IN DIVISION-112, UNIT-24, ZONE-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17461,Roads,Completed,NJ-TEYNAMPET,112,691000,"IMPROVEMENTS TO THE BT ROAD AT Sivan Koil South Street IN DIVISION-112, UNIT-26, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17996,Buildings,Completed,NJ-TEYNAMPET,112,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT CHOOLAIMEDU HIGH ROAD (NEAR TO VANNIYAR STREET) IN DIV-112,U-26,Z-09",Own Sources,9,2018-19,2020-21 NJ/2018-19/2152,Roads,Completed,NJ-TEYNAMPET,112,2073000,"IMPROVEMENTS TO THE INTERIOR B.T ROAD AT CHOOLAIMEDU HIGH ROAD (PART) IN DIV -112,UNIT-26, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2271,Roads,Completed,NJ-TEYNAMPET,112,293000,"Improvements To The B.T Road At Sowrastra Nagar 8th Street In Div -112, Unit-26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/8772,Buildings,Completed,NJ-TEYNAMPET,112,346000,"REPAIRS AND IMPROVEMENTS TO THE AMMA UNAVAGAM BUILDING AT PULIYUR MAIN ROAD IN DIV - 112, UNIT -26, ZONE -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/8774,Buildings,Completed,NJ-TEYNAMPET,112,298000,"REPAIRS AND IMPROVEMENTS TO THE AMMA UNAVAGAM BUILDING AT CHOOLAIMEDU HIGH ROAD IN DIV -112, UNIT -26, ZONE -9.",Own Sources,9,2018-19,2019-20 B/2018-19/3951,Buildings,Completed,B-Buildings,113,10464100,REPAIRS AND IMPROVEMENTS TO CHENNAI SCHOOLS AT VARIOUS LOCATIONS IN ZONE-10,Own Sources,9,2018-19,2020-21 BR/2018-19/14681,Roads,Completed,BR-Bus Route Roads,113,2000000,REPAIRS TO THE EXISTING GCC STAINLESS STEEL BUS SHELTERS AT VARIOUS ZONES 6 TO 10 (GIM) FOR THE YEAR 2018-19,Own Sources,9,2018-19,2019-20 BR/2018-19/15288,Roads,Completed,BR-Bus Route Roads,113,516000,"RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS 112,113,117 AND 122 IN UNIT 26 ZONE 09",Deposit Works,9,2018-19,2019-20 BR/2018-19/15664,Road Cut,Completed,BR-Bus Route Roads,113,135000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX (Deposit Code-57/0281/2018-19,Deposit Works,9,2018-19,2019-20 BR/2018-19/17892,Roads,Completed,BR-Bus Route Roads,113,2500000,"REPAIRS AND IMPROVEMENTS TO EXISTING GANTRY GIRDER, STREET NAME BOARDS AND SIGN BOARDS AT VARIOUS BUS ROUTE ROADS IN ZONE-5, 9,10, 12 AND 13",Own Sources,9,2018-19,2019-20 BR/2018-19/6545,Footpath,Completed,BR-Bus Route Roads,113,21071000,"Forming Footpath at Dr.M.G.R.Salai (From the jn of Uthamar gandhi Salai to 70 Feet Scheme Road) in Dn-113, Zone-IX",Grants,9,2018-19,2020-21 BR/2018-19/6549,Footpath,Completed,BR-Bus Route Roads,113,19863000,"Forming Footpath at Uthamar Gandhi Salai in Dn-113, Zone-IX",Grants,9,2018-19,2020-21 BR/2018-19/6667,Roads,Completed,BR-Bus Route Roads,113,5026000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at G.N.Chetty Road (From the jn of North boag road to Anna Fly over) in Dn-113 & 136, Zone - IX",Grants,9,2018-19,2019-20 L/2018-19/10871,Electrical,Completed,L-Electrical,113,200000,"Replacement of underground cables with HDPE pipe and overhead wires at Nungambakkam Lane, Nungambakkam 1st Lane and Prakasam Street in div 113, zone - 9",Own Sources,9,2018-19,2019-20 L/2018-19/5671,Electrical,Completed,L-Electrical,113,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nungambakkam Diognastic centre, Kodambakkam High Road in Div-113, Zone-IX .(E.B.Account no-129.022.179)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/8824,Electrical,Completed,L-Electrical,113,1413100,"Electrification Work at CMS Jayalakshmipuram, CMS Appa samy street, CMS Rama street, CBHS School Nungambakkam, in Division-110 , 113 Zone-IX.",Own Sources,9,2018-19,2019-20 NJ/2018-19/0332,Buildings,Completed,NJ-TEYNAMPET,113,80000,"IMPROVEMENTS TO THE EXISTING NNMP SHEED AT SARATHI STREET IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/11124,Buildings,Completed,NJ-TEYNAMPET,113,1266000,"MINOR REPAIRS TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-113, UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11125,Buildings,Completed,NJ-TEYNAMPET,113,1019000,"DESILTING TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DIV-113, UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/12439,Buildings,Completed,NJ-TEYNAMPET,113,606000,"IMPROVEMENTS TO THE EXISTING SSA BUILDING AT VALLUVAR KOTTAM HIGH ROAD IN DIVISION -113, UNIT -26,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/12441,Buildings,Completed,NJ-TEYNAMPET,113,459000,"IMPROVEMENTS TO THE EXISTING DIAGNOSTIC LAB AT KODAMBAKKAM HIGH ROAD NEAR PARK IN DIVISION -113, UNIT -26,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/1298,Roads,Completed,NJ-TEYNAMPET,113,1797000,"IMPROVEMENTS TO THE BT ROAD AT NOOR VEERASAMY STREET IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1307,Roads,Completed,NJ-TEYNAMPET,113,2903000,"IMPROVEMENTS TO THE BT ROAD AT MANGADUSWAMY STREET & RAMA STREET IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16390,Roads,Completed,NJ-TEYNAMPET,113,1221000,"REPAIRS AND MAINTENANCE TO EXISTING CENTRE MEDIAN AT NUNGAMBAKKAM HIGH ROAD IN DN-113 ,UNIT-26, ZONE-9",Own Sources,9,2018-19,2020-21 NJ/2018-19/16468,Roads,Completed,NJ-TEYNAMPET,113,448000,"REPAIRS AND MAINTENANCE TO EXISTING CENTRE MEDIAN AT THIRUMALAI PILLAI ROAD IN DN-113 ,UNIT-26, ZONE-9",Own Sources,9,2018-19,2020-21 NJ/2018-19/16722,Roads,Completed,NJ-TEYNAMPET,113,2902000,"IMPROVEMENTS TO THE BT RAOD Nageshwara rao Road & Kumarappa Street STREET IN DIV 113,UNIT 26,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16723,Roads,Completed,NJ-TEYNAMPET,113,1617000,"IMPROVEMENTS TO THE BT ROAD AT Thirumoorthi Main Road IN DIV 113,UNIT 26,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1990,Roads,Completed,NJ-TEYNAMPET,113,1078000,"IMPROVEMENTS TO THE BT ROAD AT VIDHYODAYA 1ST CROSS STREET IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2001,Roads,Completed,NJ-TEYNAMPET,113,373000,"IMPROVEMENTS TO THE B.T.ROAD AT NOOR VEERASAMY LANE IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2011,Roads,Completed,NJ-TEYNAMPET,113,2709000,"IMPROVEMENTS TO THE B.T.ROAD AT KRISHNAMBAL STREET IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2016,Roads,Completed,NJ-TEYNAMPET,113,2709000,"IMPROVEMENTS TO THE B.T.ROAD AT CATHEDRAL GARDEN ROAD IN DIVISION-113, UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2021,Roads,Completed,NJ-TEYNAMPET,113,1099000,"IMPROVEMENTS TO THE B.T.ROAD AT JAGANATHAN ROAD IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/3783,Roads,Completed,NJ-TEYNAMPET,113,750000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 112,113,117&122 IN UNIT 26 ZONE 09",Own Sources,9,2018-19,2019-20 NJ/2018-19/5351,Storm Water Drain,Completed,NJ-TEYNAMPET,113,903000,"IMPROVEMENTS TO THE EXISTING SWD AT G.N.CHETTY ROAD (FROM LIITTLE FLOWER CONVENT TO DOOR NO 14) IN DIVISION-113,UNIT-26,ZONE-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/8036,Buildings,Completed,NJ-TEYNAMPET,113,279000,Improvements to the Existing Amma Unavagam at Sarathi Street in dn113 unit 26 zone 09,Own Sources,9,2018-19,2019-20 B/2018-19/8312,Buildings,Completed,B-Buildings,114,673115,"PROVIDING PARTITION, CUPBOARD DOORS AND ELECTRICAL ARRANGEMENTS AT NIGHT SHELTER 1 ,KASTURIBAI GHANDHI HOSPITAL IN DN -114, Z-9",Grants,9,2018-19,2018-19 B/2018-19/8961,Buildings,Completed,B-Buildings,114,673115,"PROVIDING PARTITION, CUPBOARD DOORS AND ELECTRICAL ARRANGEMENTS AT NIGHT SHELTER 2 ,KASTURIBAI GHANDHI HOSPITAL IN DN -114, Z-9",Grants,9,2018-19,2018-19 BR/2018-19/10737,Road Cut,Completed,BR-Bus Route Roads,114,1280000,"Restoration of road cut made by TANGEDCO @ Dr. Natesan road and Besant road in Dn-114, Zone-09.",Deposit Works,9,2018-19,2019-20 BR/2018-19/15289,Roads,Completed,BR-Bus Route Roads,114,226000,"RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS 114,115,116,120 AND 121 IN UNIT 27 ZONE 09",Deposit Works,9,2018-19,2019-20 BR/2018-19/15663,Road Cut,Completed,BR-Bus Route Roads,114,1022000,Restoration of OFC road cut made by ACT at various Bus Route Roads in zone-IX (Deposit Code-57/0198/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/15667,Road Cut,Completed,BR-Bus Route Roads,114,29600,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX(Deposit Code-57/0580/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/15893,Roads,Completed,BR-Bus Route Roads,114,782000,"Providing Thermo Plastic Paint for Kerb at Kamarajar Salai ( jn of Light House to the jn of labour statue) in Dn-114,116 & 121, Zone-IX",Own Sources,9,2018-19,2019-20 BR/2018-19/18004,Roads,Completed,BR-Bus Route Roads,114,689000,"Providing Centre Median at Jn of Bharathi Salai X Quide Millath Road in Dn-114, Zone-IX",Own Sources,9,2018-19,2019-20 BR/2018-19/6550,Footpath,Completed,BR-Bus Route Roads,114,5790000,"Forming Footpath at Babu Jagajeevanram salai (Bells Road) in Dn-114, Zone-IX",Grants,9,2018-19,2020-21 BR/2018-19/7836,Footpath,Completed,BR-Bus Route Roads,114,990000,"Repair and improvement of existing footpath at Kamaraj salai (Eastern side0 in Dn -114, Zone - 9",Own Sources,9,2018-19,2018-19 D/2018-19/2915,Storm Water Drain,Completed,D-Storm Water Drains,114,1606000,"Rejuvenation and other improvements to the temple tank at Thiruvetteswarar Koil & Thiruvettewaran Pettai including construction of RWH well under Sustainable Water Secruity Mission in Dn - 114,Zone - 9.",SMART CITY - SWD,9,2018-19,2020-21 L/2018-19/15546,Electrical,Completed,L-Electrical,114,179100,"Supply of 149 nos of 1mtr curved G.I. SINGLE BRACKET for the use of 2mtr and 3mtr Post top lantern Posts at Anna Park ( Near left side of Anna Square ) Kamaraja Salai, Gill Nagar Park, Chitra Park and Anbazigan Park in division-114,109 and 112, Zone-IX.",Own Sources,9,2018-19,2019-20 L/2018-19/15984,Electrical,Completed,L-Electrical,114,188000,"Provision of 11 nos of 63 AMP / 3Phase Microprocessor based digital AUTOMATIC STREET LIGHTING ON / OFF CONTROLLING TIMER UNITS at Marina Beach Service Road in Division - 114, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/17294,Electrical,Completed,L-Electrical,114,184000,"Providing of 15 Nos 4 feet of 20 W Tube Light LED Fitting at Labour Statue Pedestrian SubWay and Erection of 3 Nos 6 Mtr Lamp Post with Straight Bkt at Kanagi Statue Pedestrian SubWay in Kamarajar salai in Division- 114 and 116, Zone-IX.",Own Sources,9,2018-19,2020-21 L/2018-19/4132,Electrical,Completed,L-Electrical,114,4282500,"Electrification work for CMS V R Pillai Street, CGHS Irusappa Street, CMS Besent Road, CMS Surappa Street, CMS T H Road, CMS Namachivayapuram, CHS Choolaimedu, CHS Tiruvalluvarpuram and CPS Sankarapuram in Division - 109, 112, 115, 116 & 120, Zone-IX.",Own Sources,9,2018-19,2019-20 L/2018-19/4136,Electrical,Completed,L-Electrical,114,195800,"Replacement of 498 Mtrs 2 X 16 sqmm UG Alu Cable at Buchi Babau Street Yusuf Street and Lane in Division - 114, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/5881,Electrical,Completed,L-Electrical,114,161500,"Estimate for Supply, Installation, Testing & Commissioning of 2Kwp Grid-Tied Solar Rooftop including Civil works and earthing at CMS, Bells Road, Division - 114, Zone - 9. (E.B.Account no- 103.076.336 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5888,Electrical,Completed,L-Electrical,114,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at URDU SCHOOL in Vallaba Agraharam St, Division - 114, ZONE-9 .(E.B.Account no- 192.021.30 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5891,Electrical,Completed,L-Electrical,114,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS School in Typoon Ali Khan Street, Division - 114, ZONE-9 .(E.B.Account no- 103.050.100 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5892,Electrical,Completed,L-Electrical,114,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Gym in Arunachalam Street, Division - 114, ZONE-9 .(E.B.Account no- 103.053.255 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5896,Electrical,Completed,L-Electrical,114,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office - 114 in Arunachalam Street, Division - 114, ZONE-9 .(E.B.Account no- 103.053.54 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5912,Electrical,Completed,L-Electrical,114,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS School, in Bangaru Street, Division - 114, Zone -9 .(E.B.Account no- 193.003.143 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0339,Storm Water Drain,Completed,NJ-TEYNAMPET,114,350000,"Improvements to storm water drain at C.N.K Road in Div-114,U-27,Z-9.",Own Sources,9,2018-19,2018-19 NJ/2018-19/14799,Buildings,Completed,NJ-TEYNAMPET,114,1380000,"Providing Rain water harvesting structure and Improvement works to Marina Beach in Div-114, U-27A,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/14896,Storm Water Drain,Completed,NJ-TEYNAMPET,114,2856000,"CONSTRUCTION OF STORM WATER DRAIN AT BANGARU STREET IN DIVISION-114,U-27, Z-9.",MLACDS,9,2018-19,2019-20 NJ/2018-19/15505,Subway,Completed,NJ-TEYNAMPET,114,514000,"IMPROVEMENTS TO LABOUR STATUE SUBWAY AT KAMARAJAR SALAI IN DIV -114, UNIT-27A, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/15564,Buildings,Completed,NJ-TEYNAMPET,114,889000,"Improvement works to Night shelter at Lock nagar in Div-114, U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16328,Roads,Completed,NJ-TEYNAMPET,114,556000,"Repairs and improvements to Center median at Wallaja salai in Div-114,Unit-27,Zone-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16335,Roads,Completed,NJ-TEYNAMPET,114,112000,"Repairs and improvements to Center median at sivananda salai in Div-114,Unit-27,Zone-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16343,Roads,Completed,NJ-TEYNAMPET,114,504000,"Repairs and improvements to Center median at kamarajar salai in Div-114,Unit-27,Zone-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1642,Roads,Completed,NJ-TEYNAMPET,114,1225000,"IMPROVEMENTS TO THE BT ROAD AT C.N.K Road IN DIV-114, UNIT-27, ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/1648,Roads,Completed,NJ-TEYNAMPET,114,333000,"IMPROVEMENTS TO THE BT ROAD AT SYDOJI STREET AND LANE IN DIV-114, UNIT-27, ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/1651,Roads,Completed,NJ-TEYNAMPET,114,265000,"IMPROVEMENTS TO THE BT ROAD AT CHELLAPILLAIYAR KOIL STREET IN DIVISION-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1655,Roads,Completed,NJ-TEYNAMPET,114,738000,"IMPROVEMENTS TO THE BT ROAD AT Bangaru Street IN DIVISION-114,U-27,Z-9.i",Own Sources,9,2018-19,2019-20 NJ/2018-19/1659,Roads,Completed,NJ-TEYNAMPET,114,442000,"IMPROVEMENTS TO THE BT ROAD AT Arunachalam Street IN DIVISION-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1661,Roads,Completed,NJ-TEYNAMPET,114,762000,"IMPROVEMENTS TO THE BT ROAD AT chinna thambi street IN DIVISION-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1662,Roads,Completed,NJ-TEYNAMPET,114,2031000,"IMPROVEMENTS TO THE BT ROAD AT VICTORIA HOSTEL ROAD IN DIVISION - 114, U -27, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1665,Roads,Completed,NJ-TEYNAMPET,114,2389000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD at Lock Nagar in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1667,Roads,Completed,NJ-TEYNAMPET,114,362000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD at Pillaiyar Koil 1st and 2nd Street in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1669,Roads,Completed,NJ-TEYNAMPET,114,376000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD Azudhinkhan 1st and 2nd Lane in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1670,Roads,Completed,NJ-TEYNAMPET,114,283000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Tazudhinkhan 1st and 2nd Lane in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1674,Roads,Completed,NJ-TEYNAMPET,114,375000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT John Mohammed Street in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1675,Roads,Completed,NJ-TEYNAMPET,114,375000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Raja Hyder Ali Street in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1677,Roads,Completed,NJ-TEYNAMPET,114,891000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Fakir Sahib 1st and 2nd Street in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1678,Roads,Completed,NJ-TEYNAMPET,114,453000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Lathuram Street in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1682,Roads,Completed,NJ-TEYNAMPET,114,1680000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Subathral Street in Dn-114,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17173,Parks,Completed,NJ-TEYNAMPET,114,929000,"MAINTENANCE OF GREATER CHENNAI PARK AT ANNA MEMORIAL PARK IN DIVISION-114,UNIT-27,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17174,Parks,Completed,NJ-TEYNAMPET,114,2050000,"MAINTENANCE OF GREATER CHENNAI PARK AT MARINA BEACH IN DIVISION-114,UNIT-27,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/7788,Storm Water Drain,Completed,NJ-TEYNAMPET,114,1117000,"MINOR REPAIRS TO SWD AT VARIOUS STREETS IN DIV-114, U-27, Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/7867,Storm Water Drain,Completed,NJ-TEYNAMPET,114,751000,"DESILTING OF SWD AT VARIOUS STREETS IN DIV-114,U-27,Z-9.",Own Sources,9,2018-19,2018-19 NJ/2018-19/8562,Buildings,Completed,NJ-TEYNAMPET,114,750000,"Providing RO Purifier to Chennai middle school at Vallaba Agraharam street in Div-114,U-27,Z-9.",MLACDS,9,2018-19,2019-20 NJ/2018-19/8578,Buildings,Completed,NJ-TEYNAMPET,114,250000,"Providing Bore well to RO Purifier in Chennai Middle School at Bangaru street in Div-114,U-27,Z-9.",MLACDS,9,2018-19,2019-20 NJ/2018-19/8582,Buildings,Completed,NJ-TEYNAMPET,114,750000,"Providing RO Purifier and Borewell to ICDS(33603030426 & 33603030427) at Arunachalam street in Div-114,U-27,Z-9.",MLACDS,9,2018-19,2019-20 NJ/2018-19/8583,Buildings,Completed,NJ-TEYNAMPET,114,700000,"Providing RO Purifier and Borewell to ICDS(33603030422 & 33603030423) at Lock Nagar in Div-114,U-27,Z-9.",MLACDS,9,2018-19,2019-20 P/2018-19/16049,Parks,Completed,P-Parks and Playfields,114,2470000,Proposed improvement to damaged RR Masonry wall and improvement to greenery at Marina beach From Labour statue to light House at unit- 27A Zone-9.,Own Sources,9,2018-19,2020-21 P/2018-19/16065,Parks,Completed,P-Parks and Playfields,114,2460000,"Proposed Improvement to Damaged Footpath, Planter box Granite at Marina Beach from Labour Statue to Light house at Unit-27 A, Zone-9",Own Sources,9,2018-19,2020-21 P/2018-19/16080,Parks,Completed,P-Parks and Playfields,114,2496000,"Replacing of Damaged SS Handrails at Marina Beach From Labour Statue to Light House at Unit - 27A, Zone - 5.",Own Sources,9,2018-19,2020-21 D/2018-19/9412,Storm Water Drain,Completed,D-Storm Water Drains,115,28743000,Construction of Storm Water Drain at Dr. Besant Road in Zone - 9 - Package - 40.,Grants,9,2018-19,2020-21 L/2018-19/15985,Electrical,Completed,L-Electrical,115,188000,"Provision of 11 nos of 63 AMP / 3Phase Microprocessor based digital AUTOMATIC STREET LIGHTING ON / OFF CONTROLLING TIMER UNITS at J J Khan Road, Faroz Khan Street, West Cott Rd, Devaraj Street, Sheikh Dawood Street, Peters Road, R O B Street 5th street and Sardar Jung Garden in Division - 115, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/4137,Electrical,Completed,L-Electrical,115,196900,"Replacement of 509 Mtrs 2 X 16 sqmm UG Alu Cable at R.O .B Main Street , R.O.B Main 1st stree 8 th and Perumal Mudali Street in Division - 115, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/5898,Electrical,Completed,L-Electrical,115,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Urdu School in Dr. Besent Road, Division - 115, ZONE-9 .(E.B.Account no- 123.079.234 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5900,Electrical,Completed,L-Electrical,115,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS School in Surappa street, Division - 115, ZONE-9 .(E.B.Account no- 123.068.1 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5903,Electrical,Completed,L-Electrical,115,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS School in Dr. Besent Road, Division - 115, ZONE-9 .(E.B.Account no- 123.079.602 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5904,Electrical,Completed,L-Electrical,115,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Canteen in West Cott Road, Division - 115, ZONE-9 .(E.B.Account no- 123.042.323 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5913,Electrical,Completed,L-Electrical,115,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dispensary in Mirza Hider Ali Khan Street, Division - 115, Zone -9 .(E.B.Account no- 123.014.678 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/14139,Parks,Completed,NJ-TEYNAMPET,115,420000,"REPAIRS AND IMPROVEMENTS TO CENTER MEDIAN AT WEST COTT ROAD IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/18000,Roads,Completed,NJ-TEYNAMPET,115,113000,"IMPROVEMENTS TO THE B.T.ROAD KOYA ARUNAGIRI 4TH STREET IN DN-115, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/18001,Roads,Completed,NJ-TEYNAMPET,115,87000,"IMPROVEMENTS TO THE B.T.ROAD KOYA ARUNAGIRI 5th STREET IN DN-115, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/18002,Roads,Completed,NJ-TEYNAMPET,115,49000,"IMPROVEMENTS TO THE B.T.ROAD GAFFOOR 1ST LANE IN DN-115, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2196,Roads,Completed,NJ-TEYNAMPET,115,408000,"IMPROVEMENTS TO THE B.T.ROAD ANGAMUTHU STREET IN DN.115, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2203,Roads,Completed,NJ-TEYNAMPET,115,82000,"IMPROVEMENTS TO THE B.T.ROAD SHERFUDDIN GARDEN 1ST STREET IN DN.115, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2212,Roads,Completed,NJ-TEYNAMPET,115,187000,"IMPROVEMENTS TO THE B.T.ROAD SHERFUDIN GARDEN 2ND STREET IN DN.115, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2221,Roads,Completed,NJ-TEYNAMPET,115,204000,"Improvements to the B.T.Road Haji Shaik Hussain Street in Dn.115, Unit-27, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2244,Roads,Completed,NJ-TEYNAMPET,115,82000,"Improvements to the B.T.Road Haji Shaik Hussain 1st Lane in Dn.115, Unit-27, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2249,Roads,Completed,NJ-TEYNAMPET,115,102000,"Improvements to the B.T.Road Haji Shaik Hussain 2nd Lane in Dn.115, Unit-27, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2257,Roads,Completed,NJ-TEYNAMPET,115,180000,"IMPROVEMENTS TO THE B.T.ROAD KOYA ARUNAGIRI 1ST STREET IN DN-115, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/3551,Buildings,Completed,NJ-TEYNAMPET,115,1781545,"CONSTRUCTION OF GYM BUILDING AT MIRSHA HIDER ALIKAN STREET IN DIV-115, U-27, Z-9. ( MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/3553,Playfields,Completed,NJ-TEYNAMPET,115,1789113,"PROVIDING ARRANGEMENTS FOR CHILDRENS PLAY FIELD AT MIRSHA HIDER ALIKAN STREET IN DIV-115, U-27, Z-9. ( MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/7880,Storm Water Drain,Completed,NJ-TEYNAMPET,115,594000,"desilting the storm water drain at various streets in dn-115,unit-27, zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/7906,Storm Water Drain,Completed,NJ-TEYNAMPET,115,165000,"minor repair works to storm water drain at various streets in dn-115,unit-27, zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/8146,Buildings,Completed,NJ-TEYNAMPET,115,756000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT WEST COTT ROAD IN DN-115,U-27, Z-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/8149,Buildings,Completed,NJ-TEYNAMPET,115,645000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT SOORAPAN STREET IN DN-115,U-27, Z-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/8584,Buildings,Completed,NJ-TEYNAMPET,115,750000,"Providing RO Purifier and Borewell to Chennai Urudu Primary school at Dr.Besant Road in Div-115,U-27,Z-9",MLACDS,9,2018-19,2020-21 NJ/2018-19/8596,Buildings,Completed,NJ-TEYNAMPET,115,1500000,"Providing 2000 LPH RO Plant Station and Borewell Near Eseva Center at westcot Road in Div-115,U-27,Z-9.",MLACDS,9,2018-19,2020-21 BR/2018-19/15671,Road Cut,Completed,BR-Bus Route Roads,116,192000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX (Deposit code-57/0364/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/16178,Roads,Completed,BR-Bus Route Roads,116,895000,Attending patch work and laying of speed breaker at Various Bus Route Roads in Zone-9,Own Sources,9,2018-19,2019-20 BR/2018-19/17162,Roads,Completed,BR-Bus Route Roads,116,901000,Providing theromoplastic and stud at various BRR roads in zone-9,Own Sources,9,2018-19,2019-20 BR/2018-19/17165,Roads,Completed,BR-Bus Route Roads,116,930000,Attending Patch work at various roads in Zone-9,Own Sources,9,2018-19,2019-20 BR/2018-19/18273,Roads,Completed,BR-Bus Route Roads,116,2729000,Traffic improvement works at various Bus route roads in zone-9,Own Sources,9,2018-19,2019-20 BR/2018-19/3517,Roads,Completed,BR-Bus Route Roads,116,377000,"PROVIDING PAINTING TO THE EXISTING CENTRE MEDIAN ANJD FOOTPATH KERB AT KAMARAJ SALAI IN DN-116,121 ZONE 09",Own Sources,9,2018-19,2018-19 BR/2018-19/4373,Roads,Completed,BR-Bus Route Roads,116,165000,"Painting of existing footpath kerb at Kamaraj Salai from the Jn of TNSB Office to the Jn of Kannagi statue in Div 116 , Zone 9.",Own Sources,9,2018-19,2019-20 BR/2018-19/4376,Roads,Completed,BR-Bus Route Roads,116,157000,"Painting of existing footpath kerb at Kamaraj Salai from the Jn of Kannagi statue to the Jn of labour statue in Div 116 , Zone 9.",Own Sources,9,2018-19,2019-20 BR/2018-19/6551,Footpath,Completed,BR-Bus Route Roads,116,10167000,"Forming Footpath at Dr.Besant Road in Dn-116, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/6663,Roads,Completed,BR-Bus Route Roads,116,12124000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Dr.Besant Road (from the jn of Quide Millath Road to Kamarajar Salai) in Dn-116, Zone - IX",Grants,9,2018-19,2019-20 L/2018-19/15986,Electrical,Completed,L-Electrical,116,188000,"Provision of 11 nos of 63 AMP / 3Phase Microprocessor based digital AUTOMATIC STREET LIGHTING ON / OFF CONTROLLING TIMER UNITS at Kamarajar Salai, Marina Beach Service Road and in Division - 116 and 121 Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/17296,Electrical,Completed,L-Electrical,116,184300,"Providing of 15 Nos of 20 Watts FL LED Fitting at Kannagi statue Pedestrian SubWay at Kamarajar salai in Division- 116, Zone-IX.",Own Sources,9,2018-19,2020-21 L/2018-19/4138,Electrical,Completed,L-Electrical,116,197400,"Replacement of 510 Mtrs 2 X 16 sqmm UG Alu Cable at Eswara Doss lala Street, Raja Hunumantha Lala Street, and Neeli Veera Samy Street in Division - 116, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/5908,Electrical,Completed,L-Electrical,116,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office - 116, in Chengalvarayan Street, Division - 116, ZONE-9 .(E.B.Account no- 121.013.138 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5911,Electrical,Completed,L-Electrical,116,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit - 27 Office in Dr. Besent Road, Division - 116, ZONE-9 .(E.B.Account no- 121.020.206 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5914,Electrical,Completed,L-Electrical,116,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS School in Triplicane Road, Division - 116, Zone -9 .(E.B.Account no- 121.072.238 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5919,Electrical,Completed,L-Electrical,116,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at MLA Offfice, Triplican in Besant Road, Ice Housse, Division - 120, Zone -9 .(E.B.Account no- 121.020.480 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/10643,Storm Water Drain,Completed,NJ-TEYNAMPET,116,513000,"Desilting the storm water drain at various Streets in Dn-116,Unit- 27, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10947,Buildings,Completed,NJ-TEYNAMPET,116,772000,"REPAIRS TO THE ELECTRICAL SUB STATION AT Dr.BESANT ROAD IN DN-116,UNIT-27, ZONE-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/15052,Roads,Completed,NJ-TEYNAMPET,116,2498000,"LAYING CEMENT CONCRETE ROAD AT AYOTHIYA KUPPAM MAIN ROAD ( FROM Dr,BESANT ROAD JN To BLOCK - I ) IN DIV-116, U-27,Z-9. (UNDER MLA`S SCHEME)",MLACDS,9,2018-19,2019-20 NJ/2018-19/15332,Subway,Completed,NJ-TEYNAMPET,116,710000,"IMPROVEMENTS TO KANNAGI STATUE SUBWAY AT KAMARAJAR SALAI IN DIV -116, UNIT-27, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17291,Buildings,Completed,NJ-TEYNAMPET,116,78000,"PROVIDING DRAINAGE CONNECTION FOR PUBLIC CONVENIENCE AT Dr.BESANT ROAD (NEAR B-CANAL) IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17292,Buildings,Completed,NJ-TEYNAMPET,116,72000,"PROVIDING DRAINAGE CONNECTION FOR PUBLIC CONVENIENCE AT BHARATHI SALAI (OPPOSITE TO AMMA KUDINEER) IN DIV-116,UNIT-27,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17468,Roads,Completed,NJ-TEYNAMPET,116,204000,"IMPROVEMENTS TO THE BT ROAD WORK AT Old Firewood Street IN DN 116, UNIT - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17471,Roads,Completed,NJ-TEYNAMPET,116,272000,"IMPROVEMENTS TO THE BT ROAD WORK AT Muthukalathy Street IN DN 116, UNIT - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17472,Roads,Completed,NJ-TEYNAMPET,116,204000,"IMPROVEMENTS TO THE BT ROAD WORK AT Singaperumal Street IN DN 116, UNIT - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17473,Roads,Completed,NJ-TEYNAMPET,116,197000,"IMPROVEMENTS TO THE BT ROAD WORK AT T.P. Koil 2nd Lane IN DN 116, UNIT - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/7911,Storm Water Drain,Completed,NJ-TEYNAMPET,116,797000,"Minor repair works to storm water drain at various street in dn-116,unit-27,zone-9",Own Sources,9,2018-19,2019-20 BR/2018-19/0952,Road Cut,Completed,BR-Bus Route Roads,117,52000,"Restration of Road cut made by CMWSSB at VIJAYARAGHAVA ROAD in Dn-117, Zone-9.",Own Sources,9,2018-19,2018-19 BR/2018-19/15993,Roads,Completed,BR-Bus Route Roads,117,540000,Restoration of OFC road cot made by ACT in various Bus Route Roads in Zone-IX (Deposit code-57/0198/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/5543,Roads,Completed,BR-Bus Route Roads,117,194000,"Providing Speed Breaker at Dr. B.V.Narasimman Road and Sterling Road in Dn-110 & 117, Zone-9",Own Sources,9,2018-19,2019-20 L/2018-19/13029,Electrical,Completed,L-Electrical,117,450200,"Removal &refixing lamp post at Anna salai teynampet sigal to V R C road Reconstruction strom water drain in Div-117 of Zone-IX,",Deposit-Asset,9,2018-19,2019-20 L/2018-19/15586,Electrical,Completed,L-Electrical,117,3089700,"Provision of 34nos of 8mtr lamp post with single Arch bracket ,17 nos 8mtr post with double arch bracket and 2nos of 8mtr with triple arch bracket and along the Cmrl Metro stations Project Annasalai on either side roads and centre median from DMS Teynampet to Teynampet signal in Division 117, Zone IX",Deposit Works,9,2018-19,2019-20 L/2018-19/3967,Electrical,Completed,L-Electrical,117,926400,"Electrification Work at CMS South boag road,CPS Girippa road, in Division-117, Zone-IX",Own Sources,9,2018-19,2019-20 L/2018-19/5823,Electrical,Completed,L-Electrical,117,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ramakamathpuram Main Road (HEALTH POST) in Div-117, Zone-IX .(E.B.Account no-221-096-406)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6059,Electrical,Completed,L-Electrical,117,1892000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 25Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dr.Giriappa road ,COMMUNITY CENTRE in Div-117, Zone-IX .(E.B.Account no-235-039-701)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6061,Electrical,Completed,L-Electrical,117,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chevaliar Sivaji Ganesan Road CHENNAI MIDDLE SCHOOL Teynampet in Div-117, Zone-IX .(E.B.Account no-222-012-850)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6066,Electrical,Completed,L-Electrical,117,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Dr.Giriappa road CHENNAI PRIMARY SCHOOL Teynampet in Div-117, Zone-IX .(E.B.Account no-235-039-32)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6069,Electrical,Completed,L-Electrical,117,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chevaliar Sivaji Ganesan Road OFFICE BUILDING DIV-117 Zone-IX .(E.B.Account no-222-012-633)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6071,Electrical,Completed,L-Electrical,117,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHENNAI CORPORATION STREET LIGHT OFFICE (TEYNAMPET S/S ) THEYAGARAYA ROAD in Div-117, Zone-IX .(E.B.Account no-235-024-807)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0293,Roads,Completed,NJ-TEYNAMPET,117,265000,"Attending Patch work to the existing interior B.T road at Dr.Sadasivam Road in Div-117,Unit-26,Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/0457,Storm Water Drain,Completed,NJ-TEYNAMPET,117,274000,"Improvements to the existing Storm Water Drain at G.N.Chetty Road in Division-117,Unit-26,Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/0463,Storm Water Drain,Completed,NJ-TEYNAMPET,117,175000,"Improvements to the Existing Storm Water Drain at Sarangapani Street in Division-117,Unit-26,Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/10424,Buildings,Completed,NJ-TEYNAMPET,117,1520000,"Providing Barricading Sheets along the Mambalam Canal from Theyagaraya road to Vijayaragava Road (Thiru-Vi-Ka Kudiyiruppu) in Div-117,Unit-26,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10589,Buildings,Completed,NJ-TEYNAMPET,117,625000,"Providing RO Plant Station 500 LPH and Bore Well Under M.L.A. Scheme 2018-19 at South Boag Road Chennai Middle School In Division-117, Unit-26, Zone-09.",MLACDS,9,2018-19,2020-21 NJ/2018-19/10914,Buildings,Completed,NJ-TEYNAMPET,117,252000,"Repair and Improvements to Amma Unavagam at Thiru.Vi.Ka Kudiyiruppu in Div-117, Unit-26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11101,Storm Water Drain,Completed,NJ-TEYNAMPET,117,874000,"DESILTING TO THE EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DIV-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11102,Buildings,Completed,NJ-TEYNAMPET,117,576000,"MINOR REPAIRS TO THE EXISTING STORM WATER DRAIN IN DIVISION-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1312,Roads,Completed,NJ-TEYNAMPET,117,830000,"IMPROVEMENTS TO THE INTERIOR B.T.ROAD AT JAYAMMAL STREET IN DIVISION-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1319,Roads,Completed,NJ-TEYNAMPET,117,1524000,"IMPROVEMENTS TO THE B.T.ROAD AT VIJAYARAGAVA ROAD Ist STREET & Dr.Narasimman Road IN DIVISION-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1325,Roads,Completed,NJ-TEYNAMPET,117,1263000,"IMPROVEMENTS TO THE B.T.ROAD AT VAITHYARAMAN STREET IN DIVISION-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1331,Roads,Completed,NJ-TEYNAMPET,117,1451000,"IMPROVEMENTS TO THE B.T.ROAD AT Sadasivam road IN DIVISION-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1337,Roads,Completed,NJ-TEYNAMPET,117,671000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT NAKKERAN NAGAR IN DIVISION-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1357,Roads,Completed,NJ-TEYNAMPET,117,1156000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT M.K.RADHA NAGAR IN DIVISION-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16315,Roads,Completed,NJ-TEYNAMPET,117,722000,"REPAIRS & MAINTENANCE TO THE EXISTING CENTRE MEDIAN AT THIYAGARAYA ROAD IN DIV 117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16385,Parks,Completed,NJ-TEYNAMPET,117,633000,"REPAIRS AND MAINTENANCE TO EXISTING CENTRE MEDIAN AT G.N.CHETTY ROAD IN DIV-117,UNIT-26,ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16387,Roads,Completed,NJ-TEYNAMPET,117,560000,"REPAIRS AND MAINTENANCE TO EXISTING CENTRE MEDIAN AT VENKATANARAYAN ROAD IN DIV-117,UNIT-26, ZONE-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16724,Roads,Completed,NJ-TEYNAMPET,117,2073000,"IMPROVEMENTS TO THE BT ROAD AT Arulambal Street IN DIV -117, UNIT -26, ZONE -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16725,Roads,Completed,NJ-TEYNAMPET,117,2104000,"IMPROVEMENTS TO THE BT ROAD AT Thirumoorthi street IN DIV -117, UNIT -26, ZONE -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16726,Roads,Completed,NJ-TEYNAMPET,117,1451000,"IMPROVEMENTS TO THE BT ROAD AT THILAK STREET IN DIV -117, UNIT -26, ZONE -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16727,Roads,Completed,NJ-TEYNAMPET,117,2591000,"IMPROVEMENTS TO THE BT ROAD AT Sarangabani street IN DIV -117, UNIT -26, ZONE -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16728,Roads,Completed,NJ-TEYNAMPET,117,968000,"IMPROVEMENTS TO THE BT ROAD AT Ramakamadhapuram Main road IN DIV -117, UNIT -26, ZONE -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17994,Buildings,Completed,NJ-TEYNAMPET,117,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT VIJAYARAGHAVA ROAD IN DIV-117,U-26,Z-09",Own Sources,9,2018-19,2020-21 NJ/2018-19/4299,Buildings,Completed,NJ-TEYNAMPET,117,307400,"Repairs to the Existing Gym building at Nakkeran Nagar in Div-117,Unit-26,Zone-9",Own Sources,9,2018-19,2018-19 BR/2018-19/10583,Road Cut,Completed,BR-Bus Route Roads,118,2491000,"Restoration of Roadcut made by CMWSSB at Cathedral Road (From the jn of American embassy to Damodaran Street (Northern Side) in Dn-118, Zone-9 L-500m",Deposit Works,9,2018-19,2019-20 BR/2018-19/15360,Roads,Completed,BR-Bus Route Roads,118,526531,"Providing Thermo Plastic Paint for Centre Median and and Kerb at Cathedral Road (Jn of TTK Road to Gemini Flyover) in Dn-118, Zone-IX",Own Sources,9,2018-19,2019-20 BR/2018-19/16484,Road Cut,Completed,BR-Bus Route Roads,118,2400000,"Restoration of Roadcut made by CMWSSB at Cathedral Road ( Northern Side) (From the jn of Muthaiya Street to the jn of TTK Road) in Dn-118, Zone-IX L - 500m",Deposit Works,9,2018-19,2019-20 L/2018-19/13076,Electrical,Completed,L-Electrical,118,361000,"Provision of 5nos of 160-200W LED FL fittings and 7 nos of 70-100W LED FL fittings down below the Cathedral road bridge in division-118,Zone-IX.",Own Sources,9,2018-19,2020-21 L/2018-19/5710,Electrical,Completed,L-Electrical,118,913900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 12 Kwp Grid Tied Solar Rooftop including Civil works and earthing at No-68, Muthiahstreet,Teynampet, Chennai-18 COMMUNITY CENTER in Div-118, Zone-IX .(E.B.Account no-208.051.136)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5717,Electrical,Completed,L-Electrical,118,688200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 9 Kwp Grid Tied Solar Rooftop including Civil works and earthing at No-75/12, Srinivasaperumal sannathi 2nd street, Gopalapuram Relief centre and Amma unavagam in Div-118, Zone-IX .(E.B.Account no-133.031.254)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5725,Electrical,Completed,L-Electrical,118,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Muthaiah street, (Division office Building) Teynampet in Div-118, Zone-IX .(E.B.Account no-208.046.230)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5732,Electrical,Completed,L-Electrical,118,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at No-72, Muthiah street, (Amma Unavagam) Teynampet in Div-118, Zone-IX .(E.B.Account no-208.046.899)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6073,Electrical,Completed,L-Electrical,118,172500,"Additional Electrification Work at Srinivasa Perumal Sannathi 2nd street Amma unavagam, C.P.Ramasamy road Amma unavagm and Replacement of existing Irrepairable 17 nos of Exhaust fans in Various Amma unavagam (5 Location) at Division-118 & 123 Zone-IX.",Own Sources,9,2018-19,2018-19 NJ/2018-19/0152,Roads,Completed,NJ-TEYNAMPET,118,1780000,"ATTENDING THE TEMPORARY RESTORATION OF INTERIROR ROADS IN VARIOUS STREETS IN DIVISION - 109,110,111 AND 118 IN UNIT-24 ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/10650,Storm Water Drain,Completed,NJ-TEYNAMPET,118,744000,"Desilting the storm water drain at various Streets in Dn-118,Unit- 24, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10665,Storm Water Drain,Completed,NJ-TEYNAMPET,118,1024000,"Minor repair to the existing storm water drain at various Streets in Dn-118,Unit- 24,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11447,Buildings,Completed,NJ-TEYNAMPET,118,360000,"CONSTRUCTIONOF PLATFORM AND WATER SUPPLY ARRANGEMENTS IN E-TOILET AT SCHEME ROAD IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2018-19,2020-21 NJ/2018-19/16541,Roads,Completed,NJ-TEYNAMPET,118,435000,"REPAIRS TO EXISTING CENTRE MEDIAN AT T.T.K ROAD IN DN 118,UNIT 24,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16542,Roads,Completed,NJ-TEYNAMPET,118,347000,"REPAIRS TO EXISTING CENTRE MEDIAN AT CATHEDRAL ROAD IN DN 118,UNIT 24,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16900,Parks,Completed,NJ-TEYNAMPET,118,243000,"MAINTENANCE OF PARK AT THIRU.VI.KA PARK AT DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/16913,Parks,Completed,NJ-TEYNAMPET,118,566000,"MAINTENACE OF GREATER CHENNAI PARK AT G.N.MUTHIAH STREET PARK AT DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/1744,Roads,Completed,NJ-TEYNAMPET,118,415000,"IMPROVEMENT TO B.T .ROAD AT GANAPATHY STREET IN DIV -118,UNIT - 24, ZONE - 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1793,Roads,Completed,NJ-TEYNAMPET,118,780000,"IMPROVEMENT TO B.T .ROAD AT NATTUMUTHU STREET IN DIV -118,unit - 24,zone -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/3385,Parks,Completed,NJ-TEYNAMPET,118,151000,"ANNUAL MAINTENECE OF THI.VI.KA.PARK AT S.P.S 1st STREET(6 MONTHS) IN DIVISION-118,UNIT-24, ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/3386,Parks,Completed,NJ-TEYNAMPET,118,369000,"ANNUAL MAINTENECE OF G.N.PARK (6 MONTHS) AT MUTHAIAH STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/7746,Buildings,Completed,NJ-TEYNAMPET,118,860000,"RAISING OF FLOOR LEVEL AND MAINTENANCE OF FLOOD RELIEF CENTRE AT SRINIVASA PERUMAL SANNATHY STREET IN DIVISION-118,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 B/2018-19/13619,Buildings,Completed,B-Buildings,119,6700000,"ADDITIONAL CONSTRUCTION OF FIRST FLOOR AT UCHC AT MEERSAHIBPET , TRIPLICANE IN DN-119,Z-9",Own Sources,9,2018-19,2020-21 B/2018-19/4117,Buildings,Completed,B-Buildings,119,7940406,"PROPOSED CONSTRUCTION OF NIGHT SHELTER AT T.T.K.ROAD IN DN-119,Z-9",Own Sources,9,2018-19,2020-21 BR/2018-19/15670,Road Cut,Completed,BR-Bus Route Roads,119,896000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in zone-IX (Deposit Code-57/0362/2018-19,Deposit Works,9,2018-19,2019-20 BR/2018-19/15824,Roads,Completed,BR-Bus Route Roads,119,668000,"Providing Thermo Plastic Paint for Centre Median and Kerb at Radhakrishnan Salai (Jn of TTK Road to Kamaraj Salai) in Dn-119 & 121, Zone-IX",Own Sources,9,2018-19,2019-20 BR/2018-19/18272,Roads,Completed,BR-Bus Route Roads,119,2660000,Traffic improvement works at various Bus route roads in zone-9,Own Sources,9,2018-19,2019-20 BR/2018-19/3089,Roads,Completed,BR-Bus Route Roads,119,990000,"PROVIDING AND FIXING GANTRY GIRDER NAME BOARD AT UTHAMAR GANDHI SALAI,BOAT CLUB ROAD,WHITES ROAD,DR.RADHAKRISHNAN SALAI, LUZ CORNER ROAD AND REPAIRS TO STREET NAME BOARD AT VARIOUS BUS ROUTE ROADS IN ZONE-09",Own Sources,9,2018-19,2019-20 BR/2018-19/3182,Roads,Completed,BR-Bus Route Roads,119,2487000,"PROPOSED LAYING OF HOT APPLIED THERMOPLASTICS PAINTING M.G.R.SALAI, LUZ CHURCH ROAD ,MUSURI SUBRAMI SALAI , ROYAPETTHA HIGH ROAD , VENKATESA AGHRAARAM STREET IN ZONE -9",Own Sources,9,2018-19,2018-19 BR/2018-19/4125,Roads,Completed,BR-Bus Route Roads,119,1987000,"PROPOSED LAYING OF HOT APPLIED THERMOPLASTICS PAINTING SOUTH CANAL BANK ROAD QUIDEMILLAATH ROAD , PETERS ROAD , DR, NATESAN SALAI IN ZONE -9",Own Sources,9,2018-19,2018-19 D/2018-19/9410,Storm Water Drain,Completed,D-Storm Water Drains,119,41230000,Construction of Storm Water Drain at Nungambakkam High Road and 2 Other Roads in Zone - 9 - Package - 39.,Grants,9,2018-19,2020-21 L/2018-19/17303,Electrical,Completed,L-Electrical,119,688200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 9Kwp Grid-Tied Solar Rooftop including Civil works and earthing at Hospital, Begum Main Rd in Div-119, Zone-IX .(E.B.Account no-122.008.234)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/4872,Electrical,Completed,L-Electrical,119,2921500,"Electrification work for proposed Rewiring of EOC hospital(Waiting Hall,Paediatrician Room,Medical Officer Room,Counselling Room,Pharmacy Room,Laboratory Room,Stores Room,ccc Room,MCHO Room,Urban Health Room,Recovery Room,Paediatric ward,Bllod storage Room,Autoclave Room,Operation Theatre,Duty Nurses Room,Toilet,Cervical Screening Room,Scan Room,Edd Room,Breast Feeding,Labour Room,New Born Stabilisation Unit,Nurses Station,Dressing Room,Maternity unit) at Division - 119 , Zone - IX",Own Sources,9,2018-19,2019-20 L/2018-19/5869,Electrical,Completed,L-Electrical,119,688200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 9Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital,Begum Main Rd,Meersapet market in Div-119, Zone-IX .(E.B.Account no-122.008.53)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5871/C,Electrical,Completed,L-Electrical,119,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS,Begam 5th street in Div-119, Zone-IX .(E.B.Account no-122.008.212)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5872,Electrical,Completed,L-Electrical,119,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Hall,Begam 5th street in Div-119, Zone-IX .(E.B.Account no-122.008.52)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/10624,Storm Water Drain,Completed,NJ-TEYNAMPET,119,850000,"Desilting the storm water drain at various Streets in Dn-119,Unit- 24, Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/10666,Storm Water Drain,Completed,NJ-TEYNAMPET,119,1078000,"Minor repair to the existing storm water drain at various Streets in Dn-119,Unit- 24,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10668,Storm Water Drain,Completed,NJ-TEYNAMPET,119,1106000,"Minor repair to the existing storm water drain at various Streets in Dn-119,Unit- 27,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/16312,Parks,Completed,NJ-TEYNAMPET,119,83000,"REPAIRS AND MAINTENANCE TO THE CENTRE MEDIAN AT ROYAPETTAH HIGH ROAD IN DIVISION-119, UNIT-24, ZONE-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16921,Parks,Completed,NJ-TEYNAMPET,119,713000,"MAINTENANCE OF GREATER CHENNAI PARK AT AT C.I.T COLONY 5 TH CROSS STREET PARK IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/16929,Parks,Completed,NJ-TEYNAMPET,119,190000,"MAINTENACE OF GREATER CHENNAI PARK AT PARTHASARATHY PARK IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/3341,Parks,Completed,NJ-TEYNAMPET,119,190000,"ANNUVAL MAINTENANCE OF C.I.T.COLONY PARK (6 MONTHS) AT C.I.T.COLONY 5th CROSS STREET IN DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/6020,Storm Water Drain,Completed,NJ-TEYNAMPET,119,2500000,"CONSTRUCTION OF STORM WATER DRAIN OF SIZE 6OOX750MM AT AVVAISHANMUGAM SALAI IN DN 119,UNIT 24,ZONE 9(UNDER MLA SCHEME)",MLACDS,9,2018-19,2018-19 NJ/2018-19/6031,Storm Water Drain,Completed,NJ-TEYNAMPET,119,2490000,"CONSTRUCTION OF STORM WATER DRAIN OF SIZE 600X750MM AT BISHOP WALLERS AVENUE(EAST) AND CIT COLONY 1ST MAIN ROAD IN DN 119,UNIT 24,ZONE 9(UNDER MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/7805,Buildings,Completed,NJ-TEYNAMPET,119,965000,"REPAIR AND IMPROVEMENTS TO THE CHENNAI CORPORATION MATERNITY CENTRE AT BEGUM MAIN STREET DIVISION-119,UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/9521,Buildings,Completed,NJ-TEYNAMPET,119,455000,"DEMOLITION OF CHILD WEALTH CENTER (G+1) AT T.T.K SALAI IN DIV-119,UNIT-24, ZONE-9.",Own Sources,9,2018-19,2018-19 L/2018-19/15987,Electrical,Completed,L-Electrical,120,188000,"Provision of 11 nos of 63 AMP / 3Phase Microprocessor based digital AUTOMATIC STREET LIGHTING ON / OFF CONTROLLING TIMER UNITS at Dr. Besant Road, Singara Chari Street, T. Koil Street and M. M Garden in Division - 116 and 120, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/4139,Electrical,Completed,L-Electrical,120,193400,"Replacement of 497 Mtrs 2 X 16 sqmm UG Alu Cable at Nadu Kuppam, Neelam Bhasha Durga and Anumandhapuram in Division - 120, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/5916,Electrical,Completed,L-Electrical,120,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at CGHS School in Irusappa Street, Division - 120, Zone -9 .(E.B.Account no- 122.033.24 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5917,Electrical,Completed,L-Electrical,120,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS School in Ram Nagar, Division - 120, Zone -9 .(E.B.Account no- 122.070.365 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5918,Electrical,Completed,L-Electrical,120,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at GCC ITI in E- Depo Street, Lloyds Colony, Division - 120, Zone -9 .(E.B.Account no- 137.049.751 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0326,Storm Water Drain,Completed,NJ-TEYNAMPET,120,100000,"REPAIRS TO STORM WATER DRAIN AT MUTHAIYA STREET IN DIV-120,U-27,Z-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/10644,Storm Water Drain,Completed,NJ-TEYNAMPET,120,320000,"Desilting the storm water drain at various Streets in Dn-120,Unit- 27, Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/10705,Storm Water Drain,Completed,NJ-TEYNAMPET,120,101000,"Minor repair to the existing storm water drain at various Streets in Dn-120,Unit- 27,Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/13852,Buildings,Completed,NJ-TEYNAMPET,120,488000,"IMPROVEMENTS TO DOG SHELTER (ABC CENTER ) AT LLOYDS COLONY IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1422,Roads,Completed,NJ-TEYNAMPET,120,1924000,"IMPROVEMENTS TO THE BT ROAD AT IRUSAPPAN STREET IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1427,Roads,Completed,NJ-TEYNAMPET,120,143000,"IMPROVEMENTS TO THE EXISTING BT ROAD WORK AT IRUSAPPAN 1st STREET IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1436,Roads,Completed,NJ-TEYNAMPET,120,137000,"IMPROVEMENTS TO THE BT ROAD AT IRUSAPPAN 2nd LANE IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1438,Storm Water Drain,Completed,NJ-TEYNAMPET,120,1442000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT HANUMANTHAPURAM MAIN STREET IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1439,Storm Water Drain,Completed,NJ-TEYNAMPET,120,606000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT HANUMANTHAPURAM SLUM IN DIV-120,U-27,Z-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1441,Storm Water Drain,Completed,NJ-TEYNAMPET,120,504000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT GAJAPATHY 2nd LANE IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1444,Storm Water Drain,Completed,NJ-TEYNAMPET,120,588000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT RAJAJI NAGAR IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1445,Storm Water Drain,Completed,NJ-TEYNAMPET,120,890000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT MUNUSWAMI NAGAR IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/8064,Buildings,Completed,NJ-TEYNAMPET,120,319000,"IMPROVEMENT TO AMMA UNAVAGAM IN MUTHAIYA STREET IN DIV 120, U - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/8605,Buildings,Completed,NJ-TEYNAMPET,120,750000,"Providing RO Purifier and Borewell to Chennai girls High School at Irusappan Street in Div-120,U-27,Z-9.",MLACDS,9,2018-19,2020-21 NJ/2018-19/8643,Buildings,Completed,NJ-TEYNAMPET,120,550000,"Providing RO Purifier and Borewell to ICDS(33603030316 & 33603030317 at Irusappan Street in Div-120,U-27,Z-9.",MLACDS,9,2018-19,2020-21 BR/2018-19/0950,Road Cut,Completed,BR-Bus Route Roads,121,16000,"Restration of Road cut made by CMWSSB at DR.RADHAKRISHNAN SALAI ROAD in Dn-121, Zone-9.",Deposit Works,9,2018-19,2018-19 BR/2018-19/3959,Roads,Completed,BR-Bus Route Roads,121,500000,"DEMOLITION AND RECONSTRUCTION OF WATER SUMP IN CMWSSB STP AT KALIAMMAN KOIL STREET IN DIV-127, ZONE -10",Own Sources,9,2018-19,2018-19 BR/2018-19/6628,Road Cut,Completed,BR-Bus Route Roads,121,1680000,"Restoration of Roadcut made by CMWSSB (I & A Scheme) at P.S.Sivasamy Salai (From the jn of Dr.Radhakrishnan Salai to Vivekananda College) in Dn-121, Zone-9",Deposit Works,9,2018-19,2018-19 D/2018-19/9423,Storm Water Drain,Completed,D-Storm Water Drains,121,23558000,Construction of Storm Water Drain at School Road and 2 Other Roads in Zone - 9 - Package - 41.,Grants,9,2018-19,2020-21 L/2018-19/13867,Electrical,Completed,L-Electrical,121,191000,"Painting of 524 nos 8 mtr Octagonal street lamp post at Kamaraj salai Both side, Service Road, (from Napier bridge to Light House ) Wallaja Salai, and Swamy Sivanandha Salai of Zone IX.area in view of Repulic day(2019) to Division-114,116,120,121 &125. in Zone-IX.",Own Sources,9,2018-19,2019-20 L/2018-19/5873,Electrical,Completed,L-Electrical,121,688200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 9Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS,Veeraperumal street in Div-121, Zone-IX .(E.B.Account no-125.008.107)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5874,Electrical,Completed,L-Electrical,121,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital, Dwaraka nagar in Div-121, Zone-IX .(E.B.Account no-125.066.1043",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5875,Electrical,Completed,L-Electrical,121,537700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS, Lloyds road,Division-121,Zone-IX.(E.B.Account no-137.048.1)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5876/C,Electrical,Completed,L-Electrical,121,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS,Lloyds road in Div-121, Zone-IX .(E.B.Account no-137.048.3)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5877,Electrical,Completed,L-Electrical,121,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS,Lloyds road in Div-121, Zone-IX .(E.B.Account no-137.048.525)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5878,Electrical,Completed,L-Electrical,121,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing atCPS, Bankaramman VP Koil street in Div-121, Zone-IX .(E.B.Account no-125.009.77)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0298,Roads,Completed,NJ-TEYNAMPET,121,106000,"ATTENDING PATCHWORK AT AVVAI SHANMUGAM SALAI IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2018-19 NJ/2018-19/0315,Roads,Completed,NJ-TEYNAMPET,121,141000,"ATTENDING PATCH WORK AT MUTHAIYA STREET IN DIV-120,U-27,Z-9.",Own Sources,9,2018-19,2018-19 NJ/2018-19/10655,Storm Water Drain,Completed,NJ-TEYNAMPET,121,557000,"Desilting the storm water drain at various Streets in Dn-121,Unit- 27, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10706,Storm Water Drain,Completed,NJ-TEYNAMPET,121,371000,"Minor repair to the existing storm water drain at various Streets in Dn-121,Unit- 27,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11816,Buildings,Completed,NJ-TEYNAMPET,121,957000,"IMPROVEMENTS TO CHENNAI CORPORATION AIDS PREVENTION AND CONTROL SOCIETY AT ROYAPETTAH HIGH ROAD IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1330,Roads,Completed,NJ-TEYNAMPET,121,698000,"IMPROVEMENTS TO THE BT ROAD AT BRINDHAVAN STREET IN DN 121, UNIT - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1339,Roads,Completed,NJ-TEYNAMPET,121,1555000,"IMPROVEMENTS TO THE BT ROAD AT MUNDAKANNIAMMAN KOIL STREET IN DN 121, UNIT - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1346,Roads,Completed,NJ-TEYNAMPET,121,721000,"IMPROVEMENTS TO THE BT ROAD AT DR.R.K.SALAI 5TH STREET IN DIVISION-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1351,Roads,Completed,NJ-TEYNAMPET,121,181000,"IMPROVEMENTS TO THE BT ROAD WORK AT DR.R.K.SALAI 4TH STREET, IN DN 121, UNIT - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1380,Roads,Completed,NJ-TEYNAMPET,121,306000,"IMPROVEMENTS TO THE BT ROAD WORK AT ISMAIL GROUND STREET IN DN 121, UNIT -27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1383,Roads,Completed,NJ-TEYNAMPET,121,120000,"IMPROVEMENTS TO THE BT ROAD WORK AT NEW STREET IN DN 121, UNIT 27, ZONE -9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1387,Roads,Completed,NJ-TEYNAMPET,121,289000,"IMPROVEMENTS TO THE BT ROAD WORK AT BB ROAD 2ND STREET IN DN 121, UNIT - 27, ZONE - 9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1390,Roads,Completed,NJ-TEYNAMPET,121,204000,"IMPROVEMENTS TO THE BT ROAD WORK AT BB ROAD 4TH STREET IN DN 121, UNIT - 27, ZONE - 9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1404,Roads,Completed,NJ-TEYNAMPET,121,1141000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA MAIN ROAD IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1408,Roads,Completed,NJ-TEYNAMPET,121,252000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA 1st STREET IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1409,Roads,Completed,NJ-TEYNAMPET,121,195000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA 2nd STREET IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1411,Roads,Completed,NJ-TEYNAMPET,121,538000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA 3rd STREET IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1412,Storm Water Drain,Completed,NJ-TEYNAMPET,121,100000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA 4th LANE IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1414,Storm Water Drain,Completed,NJ-TEYNAMPET,121,103000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA 5th LANE IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1416,Storm Water Drain,Completed,NJ-TEYNAMPET,121,108000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA 6th LANE IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1418,Roads,Completed,NJ-TEYNAMPET,121,216000,"PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT P.M.DURGA 1st,2nd AND 3rd LANE IN DIV-121,U-27,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16151,Buildings,Completed,NJ-TEYNAMPET,121,750000,"PROVIDING RO PURIFIER TO CHENNAI PRIMARY SCHOOL AND CHENNAI URUDU PRIMARY SCHOOL AT LIOYDS ROAD IN DIV - 121, UNIT - 27, ZONE - 9.",MLACDS,9,2018-19,2020-21 NJ/2018-19/16373,Roads,Completed,NJ-TEYNAMPET,121,1008000,"IMPROVEMENT TO CENTER MEDIAN AT DR. RADHA KRISHNAN SALAI IN DN 119, 121 AND 125, UNIT 24,25, AND 27, ZONE -9.",Own Sources,9,2018-19,2020-21 NJ/2018-19/16721,Roads,Completed,NJ-TEYNAMPET,121,387000,"IMPROVEMENTS TO THE BT AT Josier Street IN DIV -113,UNIT-26,ZONE -9",Own Sources,9,2018-19,2019-20 NJ/2018-19/17995,Buildings,Completed,NJ-TEYNAMPET,121,618000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTER) OF 2000 Liters/ Hours CAPACITY FOR 1 YEAR PERIOD AT AVVAI SHANMUGAM SALAI (LLYODS ROAD)IN DIV-121,U-27,Z-09",Own Sources,9,2018-19,2020-21 NJ/2018-19/8044,Electrical,Completed,NJ-TEYNAMPET,121,242000,"IMPROVEMENT TO AMMA UNAVAGAM IN AVVAI SHANMUGAM SALAI IN DIV - 121, U - 27, ZONE -9.",Own Sources,9,2018-19,2019-20 B/2018-19/4121,Buildings,Completed,B-Buildings,122,8910813,"PROPOSED CONSTRUCTION OF NIGHT SHELTER AT K.P. DASAN ROAD IN DN-122,Z-9",Own Sources,9,2018-19,2020-21 BR/2018-19/2594,Footpath,Completed,BR-Bus Route Roads,122,366000,"Footpath Repair works at K.B.Dasan Road in Dn-122, Zone-IX",Grants,9,2018-19,2019-20 L/2018-19/6075,Electrical,Completed,L-Electrical,122,236700,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHAMIERS ROAD NIGHT SHELTER,Nandanam in Div-122, Zone-IX .(E.B.Account no-215-009-374)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6077,Electrical,Completed,L-Electrical,122,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at COMMUNITY HALL SM NAGAR in Div-122, Zone-IX .(E.B.Account no-182-027-968)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6078,Electrical,Completed,L-Electrical,122,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at K.B.DASAN ROAD HOSPITAL in Div-122, Zone-IX .(E.B.Account no-208-019-97)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6081,Electrical,Completed,L-Electrical,122,387200,"Supply, Installation, Testing and Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at following locations 2 Kwp at Div 122 OFFICE K.B.DASAN ROAD(Division Div-122, Zone-IX. (E.B.Account no-215-019-395). 2 Kwp at CHENNAI CORPORATION STREET LIGHT OFFICE (TEYNAMPET S/S ) THEYAGARAYA ROAD in Div-117, Zone-IX .(E.B.Account no-235-024-807). 1 Kwp at ALAIAMMAN KOIL STREET UNIT OFFICE (26)BUILDING DIV-122 Zone-IX Building as a EPC contrect includimg applicable Taxes.",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6099,Electrical,Completed,L-Electrical,122,1139600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 15 Kwp Grid Tied Solar Rooftop including Civil works and earthing at COMMUNITY CENTRE K.B.DASAN ROADin Div-122, Zone-IX .(E.B.Account no-215-019-352)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6103,Electrical,Completed,L-Electrical,122,236700,"Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at ALAIAMMAN KOIL STREET UNIT OFFICE (26)BUILDING DIV-122 Zone-IX Building as a EPC contrect includimg applicable Taxes.",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6106,Electrical,Completed,L-Electrical,122,236700,"Supply, Installation, Testing & Commissioning of 3Kwp Grid Tied Solar Rooftop including Civil works and earthing at BUGHS ROAD DHOBIKANADIV-122 Zone-IXBuilding as a EPC contrect includimg applicable Taxes.",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/10576,Storm Water Drain,Completed,NJ-TEYNAMPET,122,811000,"Desilting the storm water drain at various Streets in Dn-122,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10582,Storm Water Drain,Completed,NJ-TEYNAMPET,122,1211000,"Minor repair to the existing storm water drain at various Streets in Dn-122,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10584,Storm Water Drain,Completed,NJ-TEYNAMPET,122,1023000,"Minor repair to the existing storm water drain at various Streets in Dn-122,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10585,Storm Water Drain,Completed,NJ-TEYNAMPET,122,993000,"Minor repair to the existing storm water drain at various Streets in Dn-122,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10586,Storm Water Drain,Completed,NJ-TEYNAMPET,122,962000,"Minor repair to the existing storm water drain at various Streets in Dn-122,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10587,Storm Water Drain,Completed,NJ-TEYNAMPET,122,1165000,"Minor repair to the existing storm water drain at various Streets in Dn-122,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10590,Storm Water Drain,Completed,NJ-TEYNAMPET,122,1119000,"Minor repair to the existing storm water drain at various Streets in Dn-122,Unit- 26, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10630,Playfields,Completed,NJ-TEYNAMPET,122,95000,"SUPPLYING AND FIXING OF PLAY APPARATUS TO TURNBULLS ROAD PARK IN DN-122, UNIT-26, ZONE - 9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1311,Roads,Completed,NJ-TEYNAMPET,122,141000,ATTENDING PATCH WORK AT SEETHAMMAL COLONY 3RD CROSS STREET IN DIV122 UNIT 26 ZONE 9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1314,Roads,Completed,NJ-TEYNAMPET,122,106000,ATTENDING PATCH WORK AT SEETHAMMAL COLONY 4TH CROSS STREET IN DIV122 UNIT 26 ZONE 9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1317,Storm Water Drain,Completed,NJ-TEYNAMPET,122,100000,IMPROVEMENT WORKS TO SWD AT CHAMIERS ROAD IN DIV 122 UNIT 26 ZONE 9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1320,Storm Water Drain,Completed,NJ-TEYNAMPET,122,120000,IMPROVEMENT WORKS TO SWD AT TURNBULLS ROAD IN DIV 122 UNIT 26 ZONE9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1610,Roads,Completed,NJ-TEYNAMPET,122,1378000,IMPROVEMENT TO THE BT ROAD AT BOAT CLUB 2ND AVENUE AND 1ST AVENUE IN DIV 122 UNIT 26 ZONE9,Own Sources,9,2018-19,2019-20 NJ/2018-19/1614,Roads,Completed,NJ-TEYNAMPET,122,4450000,IMPROVEMENT TO THE BT ROAD AT CHITTHRARANJAN ROAD AND T.T.K 1ST & 2ND AVENUE IN DIV 122 UNIT 26 ZONE9,Own Sources,9,2018-19,2019-20 NJ/2018-19/1615,Roads,Completed,NJ-TEYNAMPET,122,267000,IMPROVEMENT TO THE BT ROAD AT CRESENT STREET (NEAR KB DASAN SALAI) IN DIV 122 UNIT 26 ZONE9,Own Sources,9,2018-19,2019-20 NJ/2018-19/1616,Roads,Completed,NJ-TEYNAMPET,122,663000,IMPROVEMENT TO THE BT ROAD AT KAMATCHI NAGAR IN DIV 122 UNIT 26 ZONE9,Own Sources,9,2018-19,2019-20 NJ/2018-19/1619,Roads,Completed,NJ-TEYNAMPET,122,1225000,IMPROVEMENT TO THE BT ROAD AT ABM AVENUE LANE 1 TO 7 AND CRESENT STREET IN DIV 122 UNIT 26 ZONE9,Own Sources,9,2018-19,2019-20 NJ/2018-19/16425,Roads,Completed,NJ-TEYNAMPET,122,392000,"IMPROVEMENT WORKS TO CENTRE MEDIAN AT CHAMIERS ROAD IN DIVISION 122, UNIT 26,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/2552,Storm Water Drain,Completed,NJ-TEYNAMPET,122,276000,"IMPROVEMENT WORKS TO EXISTING STORM WATER DRAIN AT BOAT CLUB ROAD IN DIV 122,UNIT 26, ZONE 9",Own Sources,9,2018-19,2018-19 NJ/2018-19/8131,Buildings,Completed,NJ-TEYNAMPET,122,366000,"IMPROVEMENTS TO AMMAUNAVAGAM AT NANDANAM 10TH ST EXTN IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/8411,Buildings,Completed,NJ-TEYNAMPET,122,169000,"DEMOLITION OF OLD DAMAGED DIVISION OFFICE BUILDING(G+1) AT K.B.DASAN SALAI IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2018-19,2019-20 B/2018-19/4122,Buildings,Completed,B-Buildings,123,7940406,"PROPOSED CONSTRUCTION OF NIGHT SHELTER AT GURUPURAM IN DN-123,Z-9",Own Sources,9,2018-19,2020-21 BR/2018-19/0951,Road Cut,Completed,BR-Bus Route Roads,123,32000,"Restoration of Road cut made by CMWSSB at TTK ROAD in Dn-123, Zone-9.",Deposit Works,9,2018-19,2018-19 BR/2018-19/10600,Road Cut,Completed,BR-Bus Route Roads,123,105973,Restoration of OFC road cut made by JIO Communication Ltd Triplicane High road and other roads in Zone 9,Deposit Works,9,2018-19,2019-20 BR/2018-19/15668,Road Cut,Completed,BR-Bus Route Roads,123,44500,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX (deposit code-57/0323/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/3076,Roads,Completed,BR-Bus Route Roads,123,950000,"PROVIDING AND FIXING GANTRY GIRDER NAME BOARD AT R.A.PURAM 2ND MAIN ROAD, 3RD MAIN ROAD , VALLUVAR KOTTAM HIGH ROAD, COLLEGE ROAD and Millers Road IN ZONE-08 & 09",Own Sources,9,2018-19,2019-20 BR/2018-19/6544,Footpath,Completed,BR-Bus Route Roads,123,9165000,"Forming Footpath at R.A.Puram 2nd Main Road (From the jn of Venkatakrishna Road to Posumpon Muthuramalinga Devar Salai) in Dn-123, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/7429,Footpath,Completed,BR-Bus Route Roads,123,545000,"Footpath Repair works at St Marys Road in Dn-123, Zone-IX",Grants,9,2018-19,2019-20 L/2018-19/15297,Electrical,Completed,L-Electrical,123,192300,"Supply of 160 nos of 1mtr curved G.I. SINGLE BRACKET for the use of 2mtr and 3mtr Post top lantern Posts at Nageshwara rao Park,Demandy colony Park, R.A.Puram 7th main road Park, Haddow's road Park, College Lane Park,Spensor Plaza Park and V.M.Street Park in division-123, 111 and 119, Zone-IX.",Own Sources,9,2018-19,2019-20 L/2018-19/3994,Electrical,Completed,L-Electrical,123,1317000,"Electrification Work at CHSS Beemanna garden, CPS Thiruvalluvar salai, CMS St.Marys road in Division-123, Zone-IX",Own Sources,9,2018-19,2019-20 L/2018-19/5738,Electrical,Completed,L-Electrical,123,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at R.A.Puram 3rd Cross Street, (S.I.Office and Judge office) R.A.Puram in Div-123, Zone-IX .(E.B.Account no-209.023.241)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5745,Electrical,Completed,L-Electrical,123,688200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 9 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.P.Ramasamy road (Multy speciality) in Div-123, Zone-IX .(E.B.Account no-132.013.827)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5752,Electrical,Completed,L-Electrical,123,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at Appadurai street CPS,Teynampet in Div-123, Zone-IX .(E.B.Account no-208.024.170)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5759,Electrical,Completed,L-Electrical,123,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Thiruvalluvar street CMS,Teynampet in Div-123, Zone-IX .(E.B.Account no-208.021.328)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5765,Electrical,Completed,L-Electrical,123,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at St.Marys road CMS in Div-123, Zone-IX .(E.B.Account no-215.029.35)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5773,Electrical,Completed,L-Electrical,123,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Thiruvalluvar salai CHS,Teynampet in Div-123, Zone-IX .(E.B.Account no-208.021.289)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5778,Electrical,Completed,L-Electrical,123,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Beemana garden (CPS), Alwarpet in Div-123, Zone-IX .(E.B.Account no-132.009.755)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5782,Electrical,Completed,L-Electrical,123,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at 29 LUZ AVENUE (Community Hall Sishuvihar),Luz in Div-123, Zone-IX .(E.B.Account no-128.002.232)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5792,Electrical,Completed,L-Electrical,123,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at No-29, C.P.Ramasamy road (Division Office),Beemannapet in Div-123, Zone-IX .(E.B.Account no-132.013.340)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5795,Electrical,Completed,L-Electrical,123,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 30 C.P.Ramasamy road, (Community hall),Alwarpet in Div-123, Zone-IX .(E.B.Account no-132.013.388)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/6319,Electrical,Completed,L-Electrical,123,122700,"Additional Work for Provision of 165W two zone amplifier with USB and Other Electrical works for Smart class ( Three rooms) at CHS School Beemanna Garden Div-123 , CGHS School Nungambakkam Div-110 and CH School Triplicane High road Div-116 in Zone 9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/0334,Storm Water Drain,Completed,NJ-TEYNAMPET,123,200000,"REPAIRS TO THE STORM WATER DRAIN AT R.A.PURAM 2ND MAIN ROAD AND R.W.H. AT SRILATHIF COLONY IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2018-19,2018-19 NJ/2018-19/0337,Storm Water Drain,Completed,NJ-TEYNAMPET,123,200000,"REPAIRS TO THE STORM WATER DRAIN AT R.A.PURAM 1ST MAIN ROAD IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2018-19,2018-19 NJ/2018-19/11100,Storm Water Drain,Completed,NJ-TEYNAMPET,123,909000,"Desilting the storm water drain at various Streets in Dn-123,Unit- 25, Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/11558,Storm Water Drain,Completed,NJ-TEYNAMPET,123,1032000,"Minor repair to the existing storm water drain at various Streets in Dn-123,Unit- 25,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11834,Storm Water Drain,Completed,NJ-TEYNAMPET,123,1217000,"Minor repair to the existing storm water drain at various Streets in Dn-123,Unit- 25,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/13109,Buildings,Completed,NJ-TEYNAMPET,123,432000,"DEMOLITION OF NATIONAL URBAN HEALTH MISSION BUILDING (NUHM) AT C.P.RAMASAMY SALAI IN DIVISION.123,UNIT.25,ZONE.09",Own Sources,9,2018-19,2019-20 NJ/2018-19/13267,Buildings,Completed,NJ-TEYNAMPET,123,770000,"REPAIRS TO EXISTING SHOPPING COMPLEX AT C.P.RAMASAMY SALAI IN DIVISION.123,UNIT.25,ZONE.09",Own Sources,9,2018-19,2019-20 NJ/2018-19/13813,Storm Water Drain,Completed,NJ-TEYNAMPET,123,495000,"PROVIDING RAIN WATER HARVESTING WELL AT VARIOUS LOCATION IN UNIT ? 25, ZONE -9 ( MLA FUND )",MLACDS,9,2018-19,2019-20 NJ/2018-19/13926,Buildings,Completed,NJ-TEYNAMPET,123,2000000,"PROPOSED CONSTRUCTION OF AUDITORIUM AND ADDITIONAL CLASS ROOM FOR CHENNAI MIDDLE SCHOOL AT ST MARYS ROAD(UNDER MLA FUND 2018-19) IN DIVISION. 123,UNIT 25,ZONE 9",MLACDS,9,2018-19,2019-20 NJ/2018-19/16379,Parks,Completed,NJ-TEYNAMPET,123,448000,"IMPROVEMENTS TO EXISTING CENTRE MEDIAN AT LUZ CHURCH ROAD FROM T.T.K.ROAD TO MUSIRI SUBARAMANI SALAI IN DN.123 UNIT.25,ZONE.09",Own Sources,9,2018-19,2019-20 NJ/2018-19/16942,Parks,Completed,NJ-TEYNAMPET,123,227000,"MAINTENACE OF GREATER CHENNAI PARK AT DEMONTE COLONY PARK IN DIVISION-123 UNIT-24,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/16946,Parks,Completed,NJ-TEYNAMPET,123,352000,"MAINTENANCE OF GREATER CHENNAI CORPORATION PARK AT R.A.PURAM 7TH MAIN ROAD PARK IN DIVISION-123,UNIT-25,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/2023,Roads,Completed,NJ-TEYNAMPET,123,234000,"IMPROVEMENTS TO BITUMINOUS ROAD AT MADHANAGOPAL STREET IN DN.123,UNIT.25.ZONE.09",Own Sources,9,2018-19,2019-20 NJ/2018-19/2036,Roads,Completed,NJ-TEYNAMPET,123,339000,"IMPROVEMENTS TO BITUMINOUS ROAD AT DR,RANGA LANE IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2018-19,2019-20 NJ/2018-19/2040,Roads,Completed,NJ-TEYNAMPET,123,876000,"IMPROVEMENTS TO BITUMINOUS ROAD AT EAST ABIRAMAPURAM 1ST STREET IN DN.123,UNIT.25,ZONE.09",Own Sources,9,2018-19,2019-20 NJ/2018-19/2566,Roads,Completed,NJ-TEYNAMPET,123,248000,"Attending patch work to the existing B.T.road at Prithivi Avenue in dn.123,unit.25,zone.09",Own Sources,9,2018-19,2018-19 NJ/2018-19/8132,Buildings,Completed,NJ-TEYNAMPET,123,103040,"DEMOLITION OF PUBLIC CONVENIANCY AT THIRUVALLUVAR SALAI IN DIVISION.123,UNIT.25,ZONE.9",Own Sources,9,2018-19,2019-20 NJ/2018-19/8531,Road Cut,Completed,NJ-TEYNAMPET,123,1100000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT LUZ AVENUE 1ST STREET IN DN.123,UNIT.25,ZONE.09",Deposit Works,9,2018-19,2019-20 BR/2018-19/15287,Roads,Completed,BR-Bus Route Roads,124,464000,"RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS 123,124,125 AND 126 IN UNIT 25 ZONE 09",Deposit Works,9,2018-19,2019-20 BR/2018-19/15669,Road Cut,Completed,BR-Bus Route Roads,124,844000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-IX (Deposit Code-57/0362/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/18003,Roads,Completed,BR-Bus Route Roads,124,689000,"Providing Centre Median at R.K.Mutt Road in Dn-124, Zone-IX",Own Sources,9,2018-19,2019-20 BR/2018-19/18005,Roads,Completed,BR-Bus Route Roads,124,517000,"Providing Centre Median at Tank Bund Road (From the jn of Sterling Avenue to Mahalingapuram main Road) in Dn-110, Zone-IX",Own Sources,9,2018-19,2019-20 BR/2018-19/6541,Footpath,Completed,BR-Bus Route Roads,124,3750000,"Forming Footpath at R.K.Mutt Road (Part) (From the jn of St Marys Road to Venkatakrishna Road) in Dn-124, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/7438,Footpath,Completed,BR-Bus Route Roads,124,500000,"Footpath Repair Works at Venkatesa Agraharam Road in Dn-124, Zone-IX",Grants,9,2018-19,2019-20 BR/2018-19/9001,Roads,Completed,BR-Bus Route Roads,124,2311000,"Thermoplastic Painting (Pedestrian Crossing) at kamarajar Salai (Marina), Kutchery Road, Luz Church Road, Royapettah High Road, Radhakrishnan Salai and Cathedral Road in Zone-IX",Own Sources,9,2018-19,2018-19 L/2018-19/5741,Electrical,Completed,L-Electrical,124,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at Balakrishna road (Slatterpuram) CMS (SundargramaniThottam) in Div-124, Zone-IX .(E.B.Account no-124.020.619)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5885,Electrical,Completed,L-Electrical,124,161500,"Estimate for Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ramakrishnapuram CPS Division - 124, Zone - 9 .(E.B.Account no- 124.023.740 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5924,Electrical,Completed,L-Electrical,124,161500,"Estimate for Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at Homiopathy clinic, MANDAVELI STREET, MANDAVELI, DIVISION - 124, ZONE -9. (E.B.Account no-127/002/633)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5929,Electrical,Completed,L-Electrical,124,86300,"Estimate for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Building, 124 Division office, KUCHRRY ROAD, MYLAPORE, DIVISION-124, ZONE-9 (E.B.Account no-128/001/722)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0629,Roads,Completed,NJ-TEYNAMPET,124,176000,Attending Patch Work to the Existing Bituminous Road at Solaippan Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/0630,Roads,Completed,NJ-TEYNAMPET,124,318000,Attending Patch Work to the Existing Bituminous Road at Nattu Subraiyan Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/0631,Roads,Completed,NJ-TEYNAMPET,124,247000,Attending Patch Work to the Existing Bituminous Road at North Mada Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/0632,Roads,Completed,NJ-TEYNAMPET,124,282000,Attending Patch Work to the Existing Bituminous Road at South Mada Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/0633,Roads,Completed,NJ-TEYNAMPET,124,339000,Attending Patch Work to the Existing Bituminous Road at Thiyagarapuram in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/10651,Storm Water Drain,Completed,NJ-TEYNAMPET,124,406000,"Desilting the storm water drain at various Streets in Dn-124,Unit- 25, Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/10691,Storm Water Drain,Completed,NJ-TEYNAMPET,124,1418000,"Minor repair to the existing storm water drain at various Streets in Dn-124,Unit- 25,Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/10910,Buildings,Completed,NJ-TEYNAMPET,124,297000,"IMPROVEMENTS TO AMMA UNAVAGAM AT MANDAVELI STREET IN DIV 124, UNIT - 25, ZONE - 9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/10911,Buildings,Completed,NJ-TEYNAMPET,124,298000,"IMPROVEMENTS TO AMMA UNAVAGAM AT ALAMELUMANGAPURAM IN DIV 124, UNIT - 25, ZONE - 9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/11375,Buildings,Completed,NJ-TEYNAMPET,124,1500000,"PROPOSED CONSTRUCTION OF GYM BUILDING AT PILLAIYAR KOIL THOTTAM IN DN 124, UNIT 25, ZONE 9. (UNDER MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/1501,Roads,Completed,NJ-TEYNAMPET,124,141000,Attending Patch Work to the Existing Bituminous Road at T S V Koil Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1502,Roads,Completed,NJ-TEYNAMPET,124,63000,Attending Patch Work to the Existing Bituminous Road at Mosque Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1503,Roads,Completed,NJ-TEYNAMPET,124,88000,Attending Patch Work to the Existing Bituminous Road at Rakkiyappa Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1504,Roads,Completed,NJ-TEYNAMPET,124,70000,Attending Patch Work to the Existing Bituminous Road at Mandaiveli Lane in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1505,Roads,Completed,NJ-TEYNAMPET,124,212000,Attending Patch Work to the Existing Bituminous Road at Kesavaperumal East Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/1506,Roads,Completed,NJ-TEYNAMPET,124,176000,Attending Patch Work to the Existing Bituminous Road at Adam street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2018-19 NJ/2018-19/16388,Roads,Completed,NJ-TEYNAMPET,124,452000,REPAIRS & MAINTENANCE TO THE EXISTING CENTER MEDIAN AT RAMAKRISHNA MUTT ROAD IN DIVISION -124 UNIT - 25 ZONE-9.,Own Sources,9,2018-19,2019-20 NJ/2018-19/2220,Roads,Completed,NJ-TEYNAMPET,124,84000,Improvements to the Bituminous Road at Rakkiappa 2nd Lane in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2222,Roads,Completed,NJ-TEYNAMPET,124,196000,Improvements to the Bituminous Road at Vaithiyar Annamalai Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2224,Roads,Completed,NJ-TEYNAMPET,124,129000,Improvements to the Bituminous Road at Singari Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2225,Roads,Completed,NJ-TEYNAMPET,124,57000,Improvements to the Bituminous Road at Ganapathy Colony in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2227,Roads,Completed,NJ-TEYNAMPET,124,114000,Improvements to the Bituminous Road at vadugar idaiyar Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2228,Roads,Completed,NJ-TEYNAMPET,124,450000,Improvements to the Bituminous Road at Puthu Palli Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2229,Roads,Completed,NJ-TEYNAMPET,124,691000,Improvements to the Bituminous Road at Abraham Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2231,Roads,Completed,NJ-TEYNAMPET,124,3317000,Improvements to the Bituminous Road at Mandaiveli Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2232,Roads,Completed,NJ-TEYNAMPET,124,691000,Improvements to the Bituminous Road at Slatterpuram in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 NJ/2018-19/2233,Roads,Completed,NJ-TEYNAMPET,124,2114000,PROVIDNG AND LAYING CEMENT CONCRETE INTERIOR ROAD AT Shanmugam Pillai Street in Division - 124 Unit - 25 Zone-9,Own Sources,9,2018-19,2019-20 B/2018-19/11439,Buildings,Completed,B-Buildings,125,3700000,"PROPOSED CONSTRUCTION OF COMMUNITY HALL AT GROUND FLOOR AT DUMMING KUPPAM IN DN -125 ,Z-9",MLACDS,9,2018-19,2019-20 BR/2018-19/11054,Road Cut,Completed,BR-Bus Route Roads,125,1590000,RESTORATION ROAD CUT WORK MADE BY OFC COMPANIES AT VARIOUS ROADS IN ZONE-9 & 10.,Deposit-Asset,9,2018-19,2018-19 BR/2018-19/12634,Roads,Completed,BR-Bus Route Roads,125,2000000,Proposed Construction of Cattle Trap at Kamarajar Salai Approaches Marina Beach Service Road in Zone -9,Own Sources,9,2018-19,2019-20 BR/2018-19/15826,Roads,Completed,BR-Bus Route Roads,125,320000,"Providing Thermo Plastic Paint for Centre Median and Kerb at Santhome High Road (Jn of South canal Bank Road to the jn of Light House) in Dn-125 & 126, Zone-IX",Own Sources,9,2018-19,2019-20 D/2018-19/2881,Storm Water Drain,Completed,D-Storm Water Drains,125,2490000,"Providing RWH well to the temple tank at Gangadeeswarar Koil,Purasaiwakkam & Virupaacheeswarar Koil,Mylapore under Sustainable Water Secruity Mission in Dn - 104 &125,Zone - 8 & 9 .",SMART CITY - SWD,9,2018-19,2019-20 L/2018-19/16042,Electrical,Completed,L-Electrical,125,188000,"Provision of 11 nos of 63 AMP / 3Phase Microprocessor based digital AUTOMATIC STREET LIGHTING ON / OFF CONTROLLING TIMER UNITS at Kamaraja Salai, Beach Service Road in Division - 125, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/5921,Electrical,Completed,L-Electrical,125,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Building, Community hall Karaneeswarar Pagoda Street, Mylapore, DIVISION-125, ZONE-9 (E.B.Account no-124/042/514)",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5925,Electrical,Completed,L-Electrical,125,161500,"Estimate for Supply, Installation, Testing & Commissioning of 2Kwp Grid Tied Solar Rooftop including Civil works and earthing at Building, 125 Division office, KUCHRRY ROAD, MYLAPORE, DIVISION-125, ZONE-9 .(E.B.Account no-126/002/361 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5940,Electrical,Completed,L-Electrical,125,86300,"Estimate for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at,Hospital, Health Post,Sanjivi street, Mylapore, DIVISION-125, ZONE-9 . (E.B.Account no-124/045/224 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0272,Roads,Completed,NJ-TEYNAMPET,125,364000,"Attending Patch work of BT road with BC 40 mm at East Mada Street in Div-125, U-25, Z-09",Own Sources,9,2018-19,2018-19 NJ/2018-19/10402,Roads,Completed,NJ-TEYNAMPET,125,291000,"Providing Colour Metal Sheet Fencing at Kailasapuram 5th Street (Near B-Canal) in Div-125, U-25, Z-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/10652,Storm Water Drain,Completed,NJ-TEYNAMPET,125,243000,"Desilting the storm water drain at various Streets in Dn-125,Unit- 25, Zone-9",Own Sources,9,2018-19,2018-19 NJ/2018-19/10692,Storm Water Drain,Completed,NJ-TEYNAMPET,125,710000,"Minor repair to the existing storm water drain at various Streets in Dn-125,Unit- 25,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/11448,Buildings,Completed,NJ-TEYNAMPET,125,584000,"Improvement works to the Community Center at Karaneeswarar Pagoda Street in Div-125, U-25, Z-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/16935,Parks,Completed,NJ-TEYNAMPET,125,229000,"MAINTENANCE OF GREATER CHENNAI PARK AT CITY CENTRE PARK (OSR) IN DIVISION-125,UNIT-25,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/2477,Roads,Completed,NJ-TEYNAMPET,125,242000,"IMPROVEMENTS TO THE BT ROAD AT SUNDARESWARAR SWAMY LANE (PART) IN DIVISION-125,U-25,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/7581,Buildings,Completed,NJ-TEYNAMPET,125,117000,"Demolition of PC at Karaneeswarar Pagoda Street in Div-125, Unit-25, Zone-09.",Own Sources,9,2018-19,2019-20 BR/2018-19/15995,Roads,Completed,BR-Bus Route Roads,126,692000,Restoration of OFC road cut made by AIrtel in various Bus Route Roads in Zone-IX (Deposit Code-57/0365/2018-19),Deposit Works,9,2018-19,2019-20 BR/2018-19/3519,Footpath,Completed,BR-Bus Route Roads,126,353000,PROVIDING PAINTING OF THE EXISTING CENTRE MEDIAN AND FOOTPATH KERB AT SANTHOME HIGH ROAD IN DN 125 &126 IN ZONE 09,Own Sources,9,2018-19,2018-19 BR/2018-19/6562,Footpath,Completed,BR-Bus Route Roads,126,11485000,"Forming Footpath at South Canal Bank Road in Dn-126, Zone-IX",Grants,9,2018-19,2019-20 L/2018-19/16047,Electrical,Completed,L-Electrical,126,188000,"Provision of 11 nos of 63 AMP / 3Phase Microprocessor based digital AUTOMATIC STREET LIGHTING ON / OFF CONTROLLING TIMER UNITS at Shanmugam Street ,M K A Street , South Mada Street , North Mada Street , V S V Koil Street, Kutchari Road and Various Street in Division - 124 & 126, Zone - IX area.",Own Sources,9,2018-19,2019-20 L/2018-19/5158,Electrical,Completed,L-Electrical,126,992000,"Erection and commissioning of 1 No of 20 Mtr High Mast with 7 nos of 210 to 230w LED FL fitting at Alphonsa Ground ,South canal Bank road in Division-126,Zone-IX.",MPLADS,9,2018-19,2020-21 L/2018-19/5920,Electrical,Completed,L-Electrical,126,387200,"Estimate for Supply, Installation, Testing & Commissioning of 5Kwp Grid Tied Solar Rooftop including Civil works and earthing at SCHOOL ,CMS,Santhome high road,4th trust link street, Santhome, DIVISION - 126, ZONE -9 .(E.B.Account no-135/013/11 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5922,Electrical,Completed,L-Electrical,126,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital, Hospital, Health Post, VANNIYAM PATHI, R A PURAM, DIVISION-126, ZONE-9 .(E.B.Account no-209/050/7 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5923,Electrical,Completed,L-Electrical,126,312000,"Estimate for Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital, Hospital, Health Post, VANNIYAM PATHI, R A PURAM, DIVISION-126, ZONE-9 .(E.B.Account no-209/050/6 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5928,Electrical,Completed,L-Electrical,126,86300,"Estimate for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Building, 126 Division office, SIRUGARI MADAM ROAD, MANDAVELI, DIVISION-126, ZONE-9 (E.B.Account no-209/050/59 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 L/2018-19/5934,Electrical,Completed,L-Electrical,126,86300,"Estimate for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Building, Amma unavagam, Santhome high road, DIVISION-126, ZONE-9 .(E.B.Account no-135/024/417 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 NJ/2018-19/0154,Roads,Completed,NJ-TEYNAMPET,126,390000,ATTENDING THE TEMPORARY RESTORATION OF INTERIOR ROADS IN VARIOUS STREETS IN DIVISION - 123 TO 126 IN UNIT-25 ZONE-09,Own Sources,9,2018-19,2019-20 NJ/2018-19/10654,Storm Water Drain,Completed,NJ-TEYNAMPET,126,517000,"Desilting the storm water drain at various Streets in Dn-126,Unit- 25, Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10693,Storm Water Drain,Completed,NJ-TEYNAMPET,126,433000,"Minor repair to the existing storm water drain at various Streets in Dn-126,Unit- 25,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/10694,Storm Water Drain,Completed,NJ-TEYNAMPET,126,1500000,"Minor repair to the existing storm water drain at various Streets in Dn-126,Unit- 25,Zone-9",Own Sources,9,2018-19,2019-20 NJ/2018-19/13157,Buildings,Completed,NJ-TEYNAMPET,126,1400000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AND PROVIDING PLAY APPARATUS (UNDER MLA SCHEME) AT CHENNAI PRIMARY SCHOOL SRINGERI MUTT ROAD R.A.PURAM IN DN 126,UNIT 25,ZONE 9",MLACDS,9,2018-19,2019-20 NJ/2018-19/1333,Roads,Completed,NJ-TEYNAMPET,126,1736000,"IMPROVEMENTS TO THE BT ROAD AT 5TH TRUST CROSS STREET IN DIVISION-126,U-25,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1341,Roads,Completed,NJ-TEYNAMPET,126,738000,"IMPROVEMENTS TO THE BT ROAD AT 7TH TRUST CROSS STREET IN DIVISION-126,U-25,Z-9.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16300,Buildings,Completed,NJ-TEYNAMPET,126,722000,"Providing RO Purifier to Chennai primary school and chennai high school at canal bank road in Div-126,U-25,Z-9.(MLA FUND)",MLACDS,9,2018-19,2019-20 NJ/2018-19/1635,Roads,Completed,NJ-TEYNAMPET,126,427000,"IMPROVEMENTS TO THE BT ROAD AT 9TH TRUST CROSS STREET IN DIV-126, U-25, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1639,Roads,Completed,NJ-TEYNAMPET,126,1709000,"IMPROVEMENTS TO THE BT ROAD AT PERIYAPALLI STREET IN DIV-126, U-25, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1644,Roads,Completed,NJ-TEYNAMPET,126,1022000,"IMPROVEMENTS TO THE BT ROAD AT KANAGARA MALIYAPPAN STREET IN DIV-126, U-25, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/16508,Buildings,Completed,NJ-TEYNAMPET,126,731000,"REPAIRS AND IMPROVEMENTS TO EXISTING AMMAUNAVAGAM AT SANTHOME HIGH ROAD IN DN 126,UNIT 25,ZONE 9",Own Sources,9,2018-19,2019-20 NJ/2018-19/1657,Roads,Completed,NJ-TEYNAMPET,126,984000,"IMPROVEMENTS TO THE BT ROAD AT 1ST TRUST LINK STREET IN DIV-126, U-25, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/1664,Roads,Completed,NJ-TEYNAMPET,126,109000,"IMPROVEMENTS TO THE EXISTING BT ROAD AT JOHANAN STREET IN DIV-126, U-25, Z-09.",Own Sources,9,2018-19,2019-20 NJ/2018-19/17129,Parks,Completed,NJ-TEYNAMPET,126,237000,"MAINTENANCWE OF GREATER CHENNAI PARK AT LAZARAS CHURCH ROAD PARK IN DIVISION-126 UNIT-25,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/17130,Parks,Completed,NJ-TEYNAMPET,126,819000,"MAINTENANCE OF GREATER CHENNAI PARK AT PATTINAMPAKKAM NURSURY PARK IN DIVISION-126 UNIT-25,ZONE-09",Own Sources,9,2018-19,2019-20 NJ/2018-19/8079,Buildings,Completed,NJ-TEYNAMPET,126,3000000,"PROPOSED CONSTRUCTION OF GYM AT SANTHOM HIGH ROAD IN DN.126,UNIT.25,ZONE.09 (MLA SCHEME)",MLACDS,9,2018-19,2019-20 NJ/2018-19/9715,Roads,Completed,NJ-TEYNAMPET,126,430000,"ARRANGEMENTS TO SCAFFOLDING AND BARRICADES FOR IMMERSION OF VINAYAGAR STATUE AT LOOP ROAD BEACH IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2018-19,2019-20 P/2018-19/12310,Parks,Completed,P-Parks and Playfields,126,498000,"PROVIDING OF FOOTPATH , SOLAR CHARGING UNIT AND SIGNAGE BOARDS AT SENSORY PARK AT DIV-126, UNIT -25,ZONE-9.",Own Sources,9,2018-19,2019-20 BR/2018-19/0134,Buildings,Completed,BR-Bus Route Roads,127,2338000,"PROPOSED DEMOLITION AND RECONSTRUCTION OF CMWSSB (STP) COMPOUND WALL AT KALIAMMAN KOIL STREET FROM CHAINAGE 0 TO 180.00M IN DIV-127, ZONE-10",Own Sources,10,2018-19,2018-19 BR/2018-19/10592,Roads,Completed,BR-Bus Route Roads,127,1656000,"RELAYING THE EXISTING ROAD WITH PAVER FINISHER AT NATESAN NAGAR 2nd MAIN ROAD (FROM KALIAMMAN KOIL STREET TO IAS QUARTERS) IN DN-127, ZONE - X",Own Sources,10,2018-19,2019-20 BR/2018-19/15114,Roads,Completed,BR-Bus Route Roads,127,1450000,"SUPPLYING AND FIXING DIGITAL BANNERIN THE STANLESS STEEL BUSSHELTERS AT VARIOUS BUS ROUTE ROADS IN ZONE - 8,10,13.",Own Sources,10,2018-19,2019-20 BR/2018-19/15118,Footpath,Completed,BR-Bus Route Roads,127,1398000,"IMPROVEMENT TO EXISTING FOOTPATHAT AT KALIAMMAN KOIL STREET AND PT RAJAN SALAI TRAFFIC ISLAND IN DN-127,130, Z-10.",Own Sources,10,2018-19,2019-20 BR/2018-19/15122,Road Cut,Completed,BR-Bus Route Roads,127,1200000,"RESTORATION OF ROAD CUT MADE BY TNEB AT NATESAN NAGAR 2ND MAIN ROAD (SOUTHERN SIDE) IN DIV-127 ,ZONE-10.",Deposit Works,10,2018-19,2019-20 BR/2018-19/15465,Roads,Completed,BR-Bus Route Roads,127,984000,"Providing and Laying of Centre Median at Kaliamman Koil Street From the jn of A Road to STP Gate in Dn-127, Zone -10",Own Sources,10,2018-19,2019-20 BR/2018-19/15468,Roads,Completed,BR-Bus Route Roads,127,998000,"Providing and Laying of Centre Median at Kaliamman Koil Street From the jn of E Road to STP Gate in Dn-127, Zone -10",Own Sources,10,2018-19,2019-20 BR/2018-19/16793,Road Cut,Completed,BR-Bus Route Roads,127,2500000,Restoration of Roadcut made by OFC Operators at Various Bus Route Roads in Zone-X,Deposit Works,10,2018-19,2019-20 BR/2018-19/17208,Road Cut,Completed,BR-Bus Route Roads,127,695000,Restoration of Roadcut made by OFC Operators at Various Bus Route Roads in Zone-X,Deposit Works,10,2018-19,2019-20 BR/2018-19/17761,Road Cut,Completed,BR-Bus Route Roads,127,1145000,Restoration of Roadcut made by OFC Operators at Various Interior Route Roads in Zone-X,Deposit Works,10,2018-19,2019-20 BR/2018-19/18247,Roads,Completed,BR-Bus Route Roads,127,168000,REMOVING AND REFIXING OF MODERN STAINLESS STEEL BUS SHELTER (1NO) AT KALIAMMAN KOIL STREET(JUNCTION OF CMWSSBSTP BUS STOP) IN DIV-127 ZONE-10.,Own Sources,10,2018-19,2020-21 BR/2018-19/1986,Roads,Completed,BR-Bus Route Roads,127,2200000,"PROPOSED DEMOLITION AND RECONSTRUCTION OF CMWSSB (STP) COMPOUND WALL AT KALIAMMAN KOIL STREET FROM CHAINAGE 180.00 M TO 350.00M IN DIV-127, ZONE-10",Own Sources,10,2018-19,2018-19 BR/2018-19/1992,Roads,Completed,BR-Bus Route Roads,127,1600000,"PROPOSED NEW COMPOUND WALL AT KALIAMMAN KOIL STREET (CMWSSB STAFF QUARTERS) IN DIV-127, ZONE-10",Own Sources,10,2018-19,2018-19 BR/2018-19/2342,Roads,Completed,BR-Bus Route Roads,127,2699000,"PROPOSED ROAD WIDENING CMDA MARKET AT KALIAMMAN KOIL STREET IN DIV-127, ZONE-10",Own Sources,10,2018-19,2019-20 BR/2018-19/2381,Roads,Completed,BR-Bus Route Roads,127,1720000,"PROPOSED ROAD WIDENING CMWSSB (STP) AT KALIAMMAN KOIL STREET REACH - I IN DIV-127, ZONE-10",Own Sources,10,2018-19,2018-19 BR/2018-19/2382,Roads,Completed,BR-Bus Route Roads,127,2990000,"PROPOSED ROAD WIDENING CMDA GIFTED LAND AT KALIAMMAN KOIL STREET REACH- I IN DIV-127, ZONE-10",Own Sources,10,2018-19,2019-20 BR/2018-19/2383,Roads,Completed,BR-Bus Route Roads,127,1478000,"PROPOSED ROAD WIDENING CMWSSB STAFF QUARTERS AT KALIAMMAN KOIL STREET IN DIV-127, ZONE-10",Own Sources,10,2018-19,2019-20 BR/2018-19/2387,Roads,Completed,BR-Bus Route Roads,127,151000,"PAINTING WORK FOR CENTRE MEDIAN AND FOOT PATH AT DGS DINAKARAN SALAI (FROM JUNCTION OF PATINAM PAKKAM SIGNAL TO IYYAPPAN KOIL) IN DIV-173, ZONE-13.",Own Sources,10,2018-19,2020-21 BR/2018-19/2547,Roads,Completed,BR-Bus Route Roads,127,2250000,"PROPOSED ROAD WIDENING CMDA GIFTED LAND AT KALIAMMAN KOIL STREET REACH- 2 IN DIV-127, ZONE-10",Own Sources,10,2018-19,2019-20 BR/2018-19/2548,Roads,Completed,BR-Bus Route Roads,127,2250000,"PROPOSED ROAD WIDENING CMDA GIFTED LAND AT KALIAMMAN KOIL STREET REACH- 3 IN DIV-127, ZONE-10",Own Sources,10,2018-19,2019-20 BR/2018-19/2549,Roads,Completed,BR-Bus Route Roads,127,1720000,"PROPOSED ROAD WIDENING CMWSSB (STP) AT KALIAMMAN KOIL STREET REACH - 2 IN DIV-127, ZONE-10",Own Sources,10,2018-19,2018-19 BR/2018-19/3399,Roads,Completed,BR-Bus Route Roads,127,926000,"DISMANTLING AND RECONSTRUCTION OF CMWSSB STP COMPOUND WALL MAIN ENTRANCE GATE WITH GRANITE FIXING AT KALIAMMAN KOIL STREET IN DIV-127, ZONE -10",Own Sources,10,2018-19,2018-19 BR/2018-19/3800,Buildings,Completed,BR-Bus Route Roads,127,155000,DEMOLISHION AND RE- CONSTRUCTION OF SECURITY SHED CMWSSB STP AT KALIAMMAN KOIL STREET IN DIV - 127. ZONE - 10,Own Sources,10,2018-19,2019-20 BR/2018-19/6082,Roads,Completed,BR-Bus Route Roads,127,12561664,"Widening and Relaying of Kaliamman koil street from the jn of Ayappa nagar 1st main road to Virugambakkam canal in Div - 127, Zone - 10",Own Sources,10,2018-19,2019-20 BR/2018-19/6101,Roads,Completed,BR-Bus Route Roads,127,3866000,"Providing Concrete Duct at Kaliamman koil street from the jn of Ayappa nagar 1st main road to Virugambakkam canal in Div - 127, Zone - 10",Own Sources,10,2018-19,2019-20 BR/2018-19/6194,Footpath,Completed,BR-Bus Route Roads,127,2025000,"Footpath Repair Works at Dr.D.G.S.Dinakaran Salai in Dn-173, Zone-XIII",Grants,10,2018-19,2019-20 BR/2018-19/6314,Road Cut,Completed,BR-Bus Route Roads,127,805000,"Restoration of Roadcut made by TANGEDCO at Kaliamman Koil Street (From Iyyappa Nagar 1ST Main Road to Virugambakkam canal) in Dn-127, Zone-10",Deposit Works,10,2018-19,2018-19 BR/2018-19/6476,Roads,Completed,BR-Bus Route Roads,127,1045000,"PROPOSED CENTRE MEDIAN (CRASH BARRIER TYPE) AT KALIAMMAN KOIL STREET (FROM A-ROAD TO SEMATHAMMAN NAGAR 1ST MAIN ROAD) IN DIV-127,ZONE-10.",Own Sources,10,2018-19,2019-20 BR/2018-19/6902,Roads,Completed,BR-Bus Route Roads,127,8783000,"Proposed Road Laying with BC 40MM Thick by using Paver Finisher at Kaliamman Koil Street and Providing Concrete Duct at Kaliamman koil street from the jn of A- Road to Ayyappa nagar 1st main road (Eastern side and Western side) in Div - 127, Zone - 10",Grants,10,2018-19,2019-20 BR/2018-19/7123,Road Cut,Completed,BR-Bus Route Roads,127,1326000,RESTORATION OF ROAD CUT MADE BY TANGEDCO AT KALIAMMAN KOIL STREET (VIRUGAM BAKKAM CANAL TO NATESAN NAGAR 2ND MAIN ROAD) IN DIV-127 ZONE-10.,Deposit Works,10,2018-19,2018-19 BR/2018-19/7126,Roads,Completed,BR-Bus Route Roads,127,1062000,"PROPOSED CENTRE MEDIAN (CRASH BARRIER TYPE) AT KALIAMMAN KOIL STREET (FROM THE JUNCTION OF SEMATHAMMAN NAGAR MAIN ROAD TO AYYAPPA NAGAR 1ST MAIN ROAD) IN DIV-127,ZONE-10.",Own Sources,10,2018-19,2019-20 BR/2018-19/7129,Roads,Completed,BR-Bus Route Roads,127,2340000,"PROPOSED CONSTRUCTION OF COMPOUND WALL WORK FOR CMDA FLOWER MARKET AT KALIAMMAN KOIL STREET IN DIV-127, ZONE-10.",Own Sources,10,2018-19,2019-20 BR/2018-19/7995,Road Cut,Completed,BR-Bus Route Roads,127,1011000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT NATESAN 2ND MAIN ROAD (WEST NATESAN NAGAR TO NATESAN NAGAR 2ND CROSS STREET ) IN DIV-127,ZONE-10.",Deposit Works,10,2018-19,2019-20 BR/2018-19/9628,Roads,Completed,BR-Bus Route Roads,127,1650000,"DISMANTLING OF EXISTING CENTRE MEDIAN WORK, REMOVING AND REFIXING OF MS GRIILL FOR FLOWER MARKET AT KALIAMMAN KOIL STREET IN DIV-127, ZONE-10.",Own Sources,10,2018-19,2020-21 BR/2018-19/9796,Road Cut,Completed,BR-Bus Route Roads,127,2249000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT NATESAN NAGAR 2ND MAIN ROAD (FROM KALIAMMAN KOIL STREET TO NATESAN 1ST CROSS STREET) IN DIV-127, ZONE-10.",Deposit Works,10,2018-19,2019-20 D/2018-19/6193,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 0 M to Chainage 90 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6195,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 90 M to Chainage 180 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6196,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 180 M to Chainage 270 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6197,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 270 M to Chainage 360 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6198,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 360 M to Chainage 450 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6199,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 450 M to Chainage 540 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6200,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 540 M to Chainage 630 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6201,Storm Water Drain,Completed,D-Storm Water Drains,127,2351000,"Construction of storm water drain of size 1200x1200mm along Western side of Kaliamman koil street from Koyambedu market A road to 100 feet road in Dn- 127,Zone-X-Reach I ( From Chainage 630 M to Chainage 720 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6203,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to V.V.KOIL STREET in Dn- 127,Zone-X-Reach II ( From Chainage 0 M to Chainage 80 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6204,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to V.V.KOIL STREET in Dn- 127,Zone-X-Reach II ( From Chainage 80 M to Chainage 160 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6205,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to V.V.KOIL STREET in Dn- 127,Zone-X-Reach II ( From Chainage 160 M to Chainage 240 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6206,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to V.V.KOIL STREET in Dn- 127,Zone-X-Reach II ( From Chainage 240 M to Chainage 320 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6207,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to V.V.KOIL STREET in Dn- 127,Zone-X-Reach II ( From Chainage 320 M to Chainage 400 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6208,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to Iyappan nagar 1st main road in Dn- 127,Zone-X-Reach III ( From Chainage 0 M to Chainage 80 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6209,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to Iyappan nagar 1st main road in Dn- 127,Zone-X-Reach III ( From Chainage 80 M to Chainage 160 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6210,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to Iyappan nagar 1st main road in Dn- 127,Zone-X-Reach III ( From Chainage 160 M to Chainage 240 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6211,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm Kaliamman koil street from Koyambedu market A road to Iyappan nagar 1st main road in Dn- 127,Zone-X-Reach III ( From Chainage 240 M to Chainage 320 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6212,Storm Water Drain,Completed,D-Storm Water Drains,127,2074000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to Iyappan nagar 1st main road in Dn- 127,Zone-X-Reach III ( From Chainage 320 M to Chainage 400 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6213,Storm Water Drain,Completed,D-Storm Water Drains,127,2090000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to junction of CMBT mofusil bus stand entrance in Dn- 127,Zone-X.-Reach IV ( From Chainage 0 M to Chainage 80 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6214,Storm Water Drain,Completed,D-Storm Water Drains,127,2090000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to junction of CMBT mofusil bus stand entrance in Dn- 127,Zone-X.-Reach IV ( From Chainage 80 M to Chainage 160 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6215,Storm Water Drain,Completed,D-Storm Water Drains,127,2090000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to junction of CMBT mofusil bus stand entrance in Dn- 127,Zone-X.-Reach IV ( From Chainage 160 M to Chainage 240 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6216,Storm Water Drain,Completed,D-Storm Water Drains,127,2090000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to junction of CMBT mofusil bus stand entrance in Dn- 127,Zone-X.-Reach IV ( From Chainage 240 M to Chainage 320 M)",Own Sources,10,2018-19,2018-19 D/2018-19/6217,Storm Water Drain,Completed,D-Storm Water Drains,127,2090000,"Construction of storm water drain of size 1200x1200mm along Kaliamman koil street from Koyambedu market A road to junction of CMBT mofusil bus stand entrance in Dn- 127,Zone-X.-Reach IV ( From Chainage 320 M to Chainage 400 M)",Own Sources,10,2018-19,2018-19 D/2018-19/9459,Storm Water Drain,Completed,D-Storm Water Drains,127,2498000,"Construction of Storm Water Drain of Size 1200 x1200mm along Kaliamman Koil Street from Koyambedu Market E Road Junction to Macro Canal in Dn. - 127,Zone - X.",Own Sources,10,2018-19,2019-20 L/2018-19/11474,Electrical,Completed,L-Electrical,127,458500,Provision of 30 nos 3mtr lamp post with 1mtr arch bracket and laying of 366 mtrs 2 x 10 sqmm alu cable and 198 mtrs 2 X 25 sqmm alu cable at Natesan nagar park in div-127 zone-10,Own Sources,10,2018-19,2019-20 L/2018-19/2457,Electrical,Completed,L-Electrical,127,3607200,Provision of 26 nos of 8 mtr lamp post with Double Arch bracket and 4 nos of 8 mtr lamp post with Triple Arch bracket with 64 nos of 150w LED Fitting at Kalliyamman koil street from Koyambedu market police station to kaliammam koil st Junction sri Ayyappa nagar division 127 in Zone-10,Own Sources,10,2018-19,2019-20 L/2018-19/3610,Electrical,Completed,L-Electrical,127,2986000,"Removal and refixing of 19 nos old 7mtr lamp post and replacement of 6219 mtrs of 2 X 16 sqmm alu cable at Natesan nagar 1st and 5th main roads ,M G Swamy street in Div-127 Zone-10",Own Sources,10,2018-19,2018-19 L/2018-19/5623,Electrical,Completed,L-Electrical,127,4780200,"Provision of 147 nos of 7 mtr lamp post with 1mtr staright bracket at semathamman nagar sector-1 and sector-2 and Raja street Bharathiyar st ,Koyambedu school street ,south mada street, north mada street,Division 127 in Zone-10",Own Sources,10,2018-19,2018-19 L/2018-19/5882,Electrical,Completed,L-Electrical,127,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.H.S koyambedu, School street in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5884,Electrical,Completed,L-Electrical,127,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.H.S Virugambakkam, School street in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5886,Electrical,Completed,L-Electrical,127,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.M.S.Koyambedu, T.S.D.nagar , School street in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5887,Electrical,Completed,L-Electrical,127,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.P.S koyambedu, School street in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5890,Electrical,Completed,L-Electrical,127,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Jai nagar 2 nd main road in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5905,Electrical,Completed,L-Electrical,127,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Natesan nagar 1st street in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5906,Electrical,Completed,L-Electrical,127,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Natesan nagar 5 th main road in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5907,Electrical,Completed,L-Electrical,127,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Thiruveedhi Amman Koil Street in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5909,Electrical,Completed,L-Electrical,127,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at T.S.D. Nagar School Street in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5910,Electrical,Completed,L-Electrical,127,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Vedha nagar in Div 127, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/10391,Roads,Completed,NK-KODAMBAKKAM,127,986000,"Forming the road by Bituminous concrete with using Mechanical Paver Finisher , at west natesan nagar ( End of the canal ) , in Dn-127, Uniit-29, Zone-10.",Own Sources,10,2018-19,2018-19 NK/2018-19/11429,Buildings,Completed,NK-KODAMBAKKAM,127,500000,"Improvements to Amma unavagam at Seemathamman sector 3 and Ayyappa nagar 1st main road in Div-127, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/11723,Roads,Completed,NK-KODAMBAKKAM,127,599000,"Relaying the Jogging track at 2nd main road SAF games Village , Koyambedu in Dn-127, Unit-29 , Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/11735,Roads,Completed,NK-KODAMBAKKAM,127,779000,"Relaying the Jogging Track at 1st main road SAF Games Village , Koyambedu in Dn-127, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/16316,Footpath,Completed,NK-KODAMBAKKAM,127,376000,"Repair and improvement of footpath at massi street , natesan nagar 1s cross street and sayee nagar 1st main road in div-127, unit-29. zone10.",Own Sources,10,2018-19,2019-20 NK/2018-19/16326,Footpath,Completed,NK-KODAMBAKKAM,127,496000,"Repair and improvement of footpath at chithirai street in div-127, unit-29, zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/16423,Footpath,Completed,NK-KODAMBAKKAM,127,256000,"Repair and improvement of footpath at sayee nagar 1st cross street , sayee nagar 6th street, and sayee nagar 7th street in div-127, unit-29, zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/17136,Parks,Completed,NK-KODAMBAKKAM,127,1330000,"MAINTENANCE ESTIMATE FOR PARK AT JAI NAGAR 1& 2 AT JAWAHARLAL NEHRU SALAI PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17137,Parks,Completed,NK-KODAMBAKKAM,127,228000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 4 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17138,Parks,Completed,NK-KODAMBAKKAM,127,207000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 5 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17139,Parks,Completed,NK-KODAMBAKKAM,127,295000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 6 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17140,Parks,Completed,NK-KODAMBAKKAM,127,218000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 7 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17141,Parks,Completed,NK-KODAMBAKKAM,127,291000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 8 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17142,Parks,Completed,NK-KODAMBAKKAM,127,211000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 9 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17143,Parks,Completed,NK-KODAMBAKKAM,127,331000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 10 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17144,Parks,Completed,NK-KODAMBAKKAM,127,237000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 11 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17145,Parks,Completed,NK-KODAMBAKKAM,127,203000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 12 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17146,Parks,Completed,NK-KODAMBAKKAM,127,995000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 2 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17147,Parks,Completed,NK-KODAMBAKKAM,127,239000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 3 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17148,Parks,Completed,NK-KODAMBAKKAM,127,237000,"MAINTENANCE ESTIMATE FOR PARK AT SAF GAMES VILLAGE OSR 1 PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17149,Parks,Completed,NK-KODAMBAKKAM,127,755000,"MAINTENANCE ESTIMATE FOR PARK AT NATESAN NAGAR PARK IN DN-127, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/17293,Roads,Completed,NK-KODAMBAKKAM,127,1250000,Attending patch work using RMC40 at various street in DN-127 U-29 Z-10,Own Sources,10,2018-19,2019-20 NK/2018-19/17479,Roads,Completed,NK-KODAMBAKKAM,127,470000,"Improvement to footpath at natasan nagar 1st maiin road in Dn. 127, Unit-29, Zone-X",Own Sources,10,2018-19,2019-20 NK/2018-19/1898,Roads,Completed,NK-KODAMBAKKAM,127,1171000,"PROPOSED ROAD WORK AT SRI AYYAPPA NAGAR 4TH STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1903,Roads,Completed,NK-KODAMBAKKAM,127,290000,"PROPOSED ROAD WORK AT SRINIVASA NAGAR 2ND STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1906,Roads,Completed,NK-KODAMBAKKAM,127,616000,"PROPOSED ROAD WORK AT SRINIVASA NAGAR 1ST MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1909,Roads,Completed,NK-KODAMBAKKAM,127,300000,"PROPOSED ROAD WORK AT SRINIVASA NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1981,Roads,Completed,NK-KODAMBAKKAM,127,502000,"PROPOSED ROAD WORK AT VEDHA NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1983,Roads,Completed,NK-KODAMBAKKAM,127,462000,"PROPOSED ROAD WORK AT GANDHI STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1985,Roads,Completed,NK-KODAMBAKKAM,127,370000,"PROPOSED ROAD WORK AT SCHOOL STREET AND BAKTHAVATCHALAM STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1989,Roads,Completed,NK-KODAMBAKKAM,127,1016000,"PROPOSED ROAD WORK AT PILLAYAR KOIL STREET KOYAMBEDU IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1994,Roads,Completed,NK-KODAMBAKKAM,127,800000,"PROPOSED ROAD WORK AT VALLUVAR STREET PART IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2000,Roads,Completed,NK-KODAMBAKKAM,127,801000,"PROPOSED ROAD WORK AT KOYAMBEDU SIVAN KOIL STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2005,Roads,Completed,NK-KODAMBAKKAM,127,355000,"PROPOSED ROAD WORK AT SAYEE NAGAR 2ND STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2010,Roads,Completed,NK-KODAMBAKKAM,127,442000,"PROPOSED ROAD WORK AT SAYEE NAGAR 1ST STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2015,Roads,Completed,NK-KODAMBAKKAM,127,305000,"PROPOSED ROAD WORK AT SAYEE NAGAR 4TH STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2033,Roads,Completed,NK-KODAMBAKKAM,127,186000,"PROPOSED ROAD WORK AT SAYEE NAGAR 6TH CROSS STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2035,Roads,Completed,NK-KODAMBAKKAM,127,565000,"PROPOSED ROAD WORK AT BHARATHIYAR NAGAR ANNA STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2042,Roads,Completed,NK-KODAMBAKKAM,127,691000,"IMPROVEMENTS TO ROAD AT WEST NATESAN NAGAR IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2046,Roads,Completed,NK-KODAMBAKKAM,127,1284000,"IMPROVEMENTS TO ROAD AT VALLUVAR SALAI IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2048,Roads,Completed,NK-KODAMBAKKAM,127,494000,"IMPROVEMENTS TO ROAD AT JAI NAGAR 13TH STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2020-21 NK/2018-19/2050,Roads,Completed,NK-KODAMBAKKAM,127,230000,"IMPROVEMENTS TO ROAD AT JAI NAGAR 23RD STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2020-21 NK/2018-19/2053,Roads,Completed,NK-KODAMBAKKAM,127,558000,"IMPROVEMENTS TO ROAD AT THIRUVEEDHI AMMAN KOIL STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2020-21 NK/2018-19/2054,Roads,Completed,NK-KODAMBAKKAM,127,478000,"IMPROVEMENTS TO ROAD AT JAI NAGAR 7TH STREET IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/2056,Roads,Completed,NK-KODAMBAKKAM,127,2639000,"PROVIDING CEMENT CONCRETE ROAD AT THIRUVEEDHI AMMAN KOIL CROSS STREETS IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2020-21 NK/2018-19/3704,Parks,Completed,NK-KODAMBAKKAM,127,589000,"CUTTING AND REMOVAL OF TREES INCLUDING ROOTS AT KALI AMMAN KOIL STREET REACH (BOTH SIDES) FROM K10 POLICE STATION TO SRI AYYAPPA NAGAR 4TH MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/3714,Parks,Completed,NK-KODAMBAKKAM,127,194500,"TRANSPLANTATION OF PALM AND OTHER TREES AT KALI AMMAN KOIL STREET REACH IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5125,Buildings,Completed,NK-KODAMBAKKAM,127,29500,"ENGAGING PRIVATE LABOUR FOR OUT SOURCING WORK OF C.H.S.S KOYAMDEDU FOR 3 MONTHS IN DIV-127, UNIT-29,ZONE-10",Own Sources,10,2018-19,2018-19 NK/2018-19/5128,Buildings,Completed,NK-KODAMBAKKAM,127,29500,"ENGAGING PRIVATE LABOUR FOR OUT SOURCING WORK OF C.P.S KOYAMDEDU FOR 3 MONTHS IN DIV-127, UNIT-29,ZONE-10",Own Sources,10,2018-19,2018-19 NK/2018-19/5129,Buildings,Completed,NK-KODAMBAKKAM,127,273000,"Engaging private labours for Security guards ( 1 year ) at Health post ( UPHC ) at Natesan Nagar 5th main Road, Virugambakkam in Division -127, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/5131,Buildings,Completed,NK-KODAMBAKKAM,127,235000,"Engaging private labours for House keeping work ( 1Year ) in Health post ( UPHC ) Natesan Nagar 5th main Road at Virugambakkam in Division - 127, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/5133,Buildings,Completed,NK-KODAMBAKKAM,127,59000,"ENGAGING PRIVATE LABOURS FOR OUTSOURCING AT C.M.S ARUMBAKKAM FOR 3 MONTHS IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2018-19 NK/2018-19/6274,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,1750000,"IMPROVEMENTS TO SWD AT NATESAN NAGAR 3RD MAIN ROAD IN DIV-127,UNIT-29,ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/7001,Roads,Completed,NK-KODAMBAKKAM,127,950000,Forming to Center median at West Natesan Nagar main road in Dn127 U-29 z-10,Own Sources,10,2018-19,2018-19 NK/2018-19/7005,Roads,Completed,NK-KODAMBAKKAM,127,1320000,Widening of the road RMC 40 at West Natesan Nagar Main Road in Dn-127 U29 Z-10,Own Sources,10,2018-19,2019-20 NK/2018-19/7007,Roads,Completed,NK-KODAMBAKKAM,127,38000,"Improvement to Transformer D wart wall at Natesan nagar 3rd main road IN DN 127,U-29 Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/7674,Buildings,Completed,NK-KODAMBAKKAM,127,1850000,"Forming to Road side park and compound wall at West natesan nagar main road in div-127, unit-29, zone-10",Own Sources,10,2018-19,2018-19 NK/2018-19/7686,Roads,Completed,NK-KODAMBAKKAM,127,1700000,Providing and laying Thermo plastic and Fixing solar stud at west natesan nagar main road and Natesan nagar 3rd main road in Dn-127 U-29 Z-10,Own Sources,10,2018-19,2018-19 NK/2018-19/7689,Roads,Completed,NK-KODAMBAKKAM,127,550000,Widening of the road using cement concrete at natesan nagar 3rd main road in Dn-127 U-29 Z-10,Own Sources,10,2018-19,2018-19 NK/2018-19/7691,Roads,Completed,NK-KODAMBAKKAM,127,1360000,Improvement to SWD at west natesan nagar main road in Dn-127 U-29 Z-10,Own Sources,10,2018-19,2018-19 NK/2018-19/7698,Roads,Completed,NK-KODAMBAKKAM,127,240000,Attending patch work using RMC at west natesan nagar main road in Dn-127 U-29 z-10,Own Sources,10,2018-19,2018-19 NK/2018-19/8982,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,992000,"Desilting of Storm Water Drain at various streets in Division-127, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8983,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,67000,"Minor repairs of storm water Drain with manhole door at various street in DN- 127, Unit-29, Zone-10.",Own Sources,10,2018-19,2018-19 NK/2018-19/9286,Buildings,Completed,NK-KODAMBAKKAM,127,133000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School , School street , at Koyambedu ( 7Months )in Dn-127, Unit-29, Zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/9287,Buildings,Completed,NK-KODAMBAKKAM,127,200000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Hr.Sec.School , School street , at Koyambedu ( 7Months )in Dn-127, Unit-29, Zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/9289,Buildings,Completed,NK-KODAMBAKKAM,127,133000,"Providing Private Labourers for Sweeping and Toilet cleaning work at CMS ,TSD Nagar ,Arumbakkam ( 7Months )in Dn-127, Unit-29, Zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 BR/2018-19/1442,Roads,Completed,BR-Bus Route Roads,128,140000,"PAINTING WORK FOR CENTRE MEDIAN AND FOOT PATH AT DGS DINAKARAN SALAI (FROM JUNCTION OF IYYAPPAN KOIL TO GREEN WAYS ROAD SIGNAL) IN DIV-173, ZONE-13.",Own Sources,10,2018-19,2019-20 BR/2018-19/6553,Footpath,Completed,BR-Bus Route Roads,128,7863000,"Forming Footpath at P.V. Rajamannar Salai in Dn-128 & 137, Zone-X",Grants,10,2018-19,2020-21 BR/2018-19/6556,Footpath,Completed,BR-Bus Route Roads,128,55590000,"Forming Footpath at NSK Salai (From Kodambakkam Bridge to Vadapalani Bus Depot) in Dn-128,129, 134, 130 & 133, Zone-X",Grants,10,2018-19,2019-20 L/2018-19/5889,Electrical,Completed,L-Electrical,128,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.P.S Virugambakkam, School street in Div 128, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/0988,Electrical,Completed,NK-KODAMBAKKAM,128,500000,"Providing and fixing lamp post in park at Thangal ulvayil street in Virugambakkam , Division - 128,Unit - 29, Zone - X .(under Virugambakkam MLA Scheme )",MLACDS,10,2018-19,2019-20 NK/2018-19/11428,Buildings,Completed,NK-KODAMBAKKAM,128,308000,"Improvements to Amma unavagam at kamarajar salai and Elango nagar in Div-128, Unit-29, Zone-10.",Own Sources,10,2018-19,2018-19 NK/2018-19/17150,Parks,Completed,NK-KODAMBAKKAM,128,277000,"ANNUAL MAINTENANCE OF PARK AT ANNAJI NAGAR 2ND MAIN ROAD PARK IN DN-128, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/2509,Roads,Completed,NK-KODAMBAKKAM,128,493000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 1st street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2510,Roads,Completed,NK-KODAMBAKKAM,128,558000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 2nd street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2511,Roads,Completed,NK-KODAMBAKKAM,128,460000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 3rd street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2512,Roads,Completed,NK-KODAMBAKKAM,128,378000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 4th street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2513,Roads,Completed,NK-KODAMBAKKAM,128,528000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 5th street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2514,Roads,Completed,NK-KODAMBAKKAM,128,1045000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 6th street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2518,Roads,Completed,NK-KODAMBAKKAM,128,245000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 1st cross street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2520,Roads,Completed,NK-KODAMBAKKAM,128,271000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 2nd cross street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2522,Roads,Completed,NK-KODAMBAKKAM,128,271000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 3rd cross street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2523,Roads,Completed,NK-KODAMBAKKAM,128,295000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 4th cross street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2525,Roads,Completed,NK-KODAMBAKKAM,128,210000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Colony 5th cross street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2527,Roads,Completed,NK-KODAMBAKKAM,128,1036000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Jawahar street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2528,Roads,Completed,NK-KODAMBAKKAM,128,630000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Kambar street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2529,Roads,Completed,NK-KODAMBAKKAM,128,7825000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Kamarajar salai , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2533,Roads,Completed,NK-KODAMBAKKAM,128,2327000,"Road cut restoration and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at AVM Avenue 1st main road , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2534,Roads,Completed,NK-KODAMBAKKAM,128,4910000,"Road cut restoration and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Thangal Erikkarai street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2535,Roads,Completed,NK-KODAMBAKKAM,128,896000,"Road cut restoration and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Thirukkai avenue , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2761,Roads,Completed,NK-KODAMBAKKAM,128,1377000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Ratna Nagar , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2798,Roads,Completed,NK-KODAMBAKKAM,128,691000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Periyar nagar , Raman street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2934,Buildings,Completed,NK-KODAMBAKKAM,128,260000,"Improvements for Electrical Crematorium at Virugambakkam Burial ground in Division - 128 , Unit - 29, Zone - 10.",Own Sources,10,2018-19,2018-19 NK/2018-19/2936,Roads,Completed,NK-KODAMBAKKAM,128,594000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Tharachand nagar 3rd street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2937,Roads,Completed,NK-KODAMBAKKAM,128,306000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Kasturi street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2938,Roads,Completed,NK-KODAMBAKKAM,128,1742000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Venkatesh nagar main road part , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2942,Roads,Completed,NK-KODAMBAKKAM,128,632000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Thiruvalluvar 3rd street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2945,Roads,Completed,NK-KODAMBAKKAM,128,166000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Periyar nagar Kamarajar street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2946,Roads,Completed,NK-KODAMBAKKAM,128,344000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Periyar nagar Sabari street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2948,Roads,Completed,NK-KODAMBAKKAM,128,127000,"Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Periyar nagar Kannamal street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2949,Roads,Completed,NK-KODAMBAKKAM,128,895000,"Laying Cement Concrete Road at Virugambakkam school 1st street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2950,Roads,Completed,NK-KODAMBAKKAM,128,550000,"Laying Cement Concrete Road using at Virugambakkam school 2nd street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2951,Roads,Completed,NK-KODAMBAKKAM,128,268000,"Laying Cement Concrete Road at Virugambakkam school 3rd street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2952,Roads,Completed,NK-KODAMBAKKAM,128,506000,"Laying Cement Concrete Road using at Virugambakkam school 1st cross street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2959,Roads,Completed,NK-KODAMBAKKAM,128,595000,"Laying Cement Concrete Road at Virugambakkam school 2nd cross street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2961,Roads,Completed,NK-KODAMBAKKAM,128,1177000,"Laying Cement Concrete Road at school street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2962,Roads,Completed,NK-KODAMBAKKAM,128,1066000,"Laying Cement Concrete Road using at Thangal Uluvai street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2965,Roads,Completed,NK-KODAMBAKKAM,128,774000,"Laying Cement Concrete Road using at Subramanian street , Virugambakkam in DN-128, U-29, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3199,Roads,Completed,NK-KODAMBAKKAM,128,4760000,"Laying of BT road by using mechanical paver finisher at Vembuliamman koil street , at virugambakkam , Dn-128, Unit-29, Zone -10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3200,Roads,Completed,NK-KODAMBAKKAM,128,1295000,"Laying of BT road by using mechanical paver finisher at Gangaiamman koil street , at virugambakkam , Dn-128, Unit-29, Zone -10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3393,Buildings,Completed,NK-KODAMBAKKAM,128,548000,Operation and Maintenance for 2nd year opearation High Quality Treated Drinking water Plant (RO/UV FILTRATION) OF 500 Liter /hour Capacity for 1 year Period at old bangaru naidu colony west k.k nagar in Dn-128 U-29 Z-10,Own Sources,10,2018-19,2019-20 NK/2018-19/3485,Roads,Completed,NK-KODAMBAKKAM,128,999000,"Stengthaning and Laying BT Road using BC 40mm thick by using Mechanical Paver Finishing at Elango Nagar (South) Street in DN-128, U-29, Z-10.( Virugambakkam MLA fund )",MLACDS,10,2018-19,2018-19 NK/2018-19/4354,Buildings,Completed,NK-KODAMBAKKAM,128,600000,"Operation and Maintenance for Electrical Crematorium at Virugambakkam Burial Ground for the Year 2018 in Division - 128, Unit - 29, Zone - 10. (For 6 Months)",Own Sources,10,2018-19,2019-20 NK/2018-19/4520,Buildings,Completed,NK-KODAMBAKKAM,128,174000,"Engaging private labours for House keeping work ( 3 Months) in Jayagopal karodiya girls higher secondary school at Virugambakkam in Division - 128, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2018-19 NK/2018-19/4521,Buildings,Completed,NK-KODAMBAKKAM,128,116000,"Engaging private labours for House keeping work ( 3 Months) in CHSS at Virugambakkam in Division - 128, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2018-19 NK/2018-19/4524,Buildings,Completed,NK-KODAMBAKKAM,128,58000,"Engaging private labours for House keeping work ( 3 Months ) in CPS at Virugambakkam in Division - 128, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2018-19 NK/2018-19/4526,Buildings,Completed,NK-KODAMBAKKAM,128,116000,"Engaging private labours for House keeping work (3 Months ) in Pillaiyar Koil Street CPS at Nesapakkam in Division - 128, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2018-19 NK/2018-19/4529,Buildings,Completed,NK-KODAMBAKKAM,128,88000,"Engaging private labours for House keeping work ( 3 Months ) in Adi-Dravidar High school at Virugambakkam in Division - 128, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2018-19 NK/2018-19/4681,Buildings,Completed,NK-KODAMBAKKAM,128,235000,"Engaging private labours for House keeping work ( 1Year ) in Health post ( UPHC ) kamarajar salai at Virugambakkam in Division - 128, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/4688,Buildings,Completed,NK-KODAMBAKKAM,128,273000,"Engaging private labours for Security guards ( 1 year ) at Health post ( UPHC ) at kamarajar salai, Virugambakkam in Division - 128, Unit - 29, Zone - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8289,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,711000,"Minor repairs of storm water Drain with manhole door at various street in DN- 128, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8293,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,999000,"Minor repairs of storm water Drain with manhole door at various street in DN- 128, Unit-29, Zone-10.",Own Sources,10,2018-19,2018-19 NK/2018-19/8300,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,987000,"Minor repairs of storm water Drain with manhole door at various street in DN- 128, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8325,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,795000,"Minor repairs of storm water Drain with manhole door at various street in DN- 128, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8577,Roads,Completed,NK-KODAMBAKKAM,128,168000,"Attending patch work by using Bituminous concrete at Jeevanatham street , Vembuliamman koil street , Lakshmi nagar main road and Co-operative society colony in Dn-128, Unit-29, Zone -10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8977,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,899000,"Desilting Storm Water Drain at Various streets in DN- 128, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/9276,Buildings,Completed,NK-KODAMBAKKAM,128,267000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Hr.Sec.School , School street , at Virugambakkam ( 7Months )in Dn-128, Unit-29, Zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/9278,Buildings,Completed,NK-KODAMBAKKAM,128,400000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Jayagopal karodiya Girls .Hr.Sec.School at Virugambakkam ( 7Months )in Dn-128, Unit-29, Zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/9280,Buildings,Completed,NK-KODAMBAKKAM,128,200000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Adhi Dhiravidar Govt High School, Kaliamman Koil Street, Virugambakkam ( 7 Months ) in Dn-128, unit-29,zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/9281,Buildings,Completed,NK-KODAMBAKKAM,128,133000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School , School street , at Virugambakkam ( 7Months )in Dn-128, Unit-29, Zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/9282,Buildings,Completed,NK-KODAMBAKKAM,128,267000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary school , Nesapakkam ( 7Months )in Dn-128, Unit-29, Zone-10. ( From 10.10.2018 to 30.04.2019 )",Own Sources,10,2018-19,2019-20 BR/2018-19/12232,Road Cut,Completed,BR-Bus Route Roads,129,1998000,Restoration of Roadcut made by TANTRANSCO at SBI Colony 2nd Street and Abusai Road l in Zone-10,Deposit Works,10,2018-19,2019-20 BR/2018-19/18270,Roads,Completed,BR-Bus Route Roads,129,2662000,Traffic improvement works at various Bus route roads in zone-10,Own Sources,10,2018-19,2019-20 L/2018-19/5808,Electrical,Completed,L-Electrical,129,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at AMBEDKAR NAGAR - GIM ,SALIGRAMAM, in Div 129, Zone-10 TNEB ACC NO : 278-005-145",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5897,Electrical,Completed,L-Electrical,129,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at DASARATHAPURAM 8TH STREET ICDS ,SALIGRAMAM, in Div 129, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5899,Electrical,Completed,L-Electrical,129,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at PONNIYAMMAN KOIL STREET ICDS ( E.SEVA ),SALIGRAMAM in Div 129, Zone-10",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/8611,Electrical,Completed,L-Electrical,129,3223800,Provision of 95 nos of 7 mtr lamp post at Dasarathapuram & Mathiyazagan Nagar and Removel of damage solar old post in Division 129 in Zone-10,Own Sources,10,2018-19,2019-20 NK/2018-19/11468,Buildings,Completed,NK-KODAMBAKKAM,129,258000,"Repair and Maintenance of Amma Unavagam at Mullai street in Division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1542,Roads,Completed,NK-KODAMBAKKAM,129,740000,"Relaying of Road with BCCMP by Using Mechanical Paver at Dhasarathapuram 1st street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1543,Roads,Completed,NK-KODAMBAKKAM,129,377000,"Relaying of Road with BCCMP by Using Mechanical Paver at Anatha ramakrishnan street (devaraj nagar ) in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2020-21 NK/2018-19/1544,Roads,Completed,NK-KODAMBAKKAM,129,1256000,"Relaying of Road with BCCMP by Using Mechanical Paver at Bharathiyar street(part) and pillayar koil street (part) kaveri rangan nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1545,Roads,Completed,NK-KODAMBAKKAM,129,1781000,"Relaying of Road with BCCMP by Using Mechanical Paver at Indira gandhi street kaveri rangan nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1547,Roads,Completed,NK-KODAMBAKKAM,129,1050000,"Relaying of Road with BCCMP by Using Mechanical Paver at Hari krishna street part in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1548,Roads,Completed,NK-KODAMBAKKAM,129,493000,"Relaying of Road with BCCMP by Using Mechanical Paver at devar street mathialagan nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2020-21 NK/2018-19/1549,Roads,Completed,NK-KODAMBAKKAM,129,605000,"Relaying of Road with BCCMP by Using Mechanical Paver at Navalar Street Devaraj nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1550,Roads,Completed,NK-KODAMBAKKAM,129,897000,"Relaying of Road with BCCMP by Using Mechanical Paver at Pammal nallathambi street (M.A Nagar) in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1551,Roads,Completed,NK-KODAMBAKKAM,129,757000,"Relaying of Road with BCCMP by Using Mechanical Paver at Thiruvalluvar street M.A Nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1552,Roads,Completed,NK-KODAMBAKKAM,129,1892000,"Relaying of Road with BCCMP by Using Mechanical Paver at MGR salai nehru nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1557,Roads,Completed,NK-KODAMBAKKAM,129,1040000,"Relaying of Road with BCCMP by Using Mechanical Paver at Thillaiadi valliammai street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1558,Roads,Completed,NK-KODAMBAKKAM,129,2019000,"Relaying of Road with BCCMP by Using Mechanical Paver at Rajaji colony main road in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1559,Roads,Completed,NK-KODAMBAKKAM,129,1144000,"Relaying of Road with BCCMP by Using Mechanical Paver at Venkateswara nagar main Road in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1560,Roads,Completed,NK-KODAMBAKKAM,129,650000,"Relaying of Road with BCCMP by Using Mechanical Paver at AVM street venkesh nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2020-21 NK/2018-19/1561,Roads,Completed,NK-KODAMBAKKAM,129,656000,"Relaying of Road with BCCMP by Using Mechanical Paver at Sarathammal street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2020-21 NK/2018-19/1562,Roads,Completed,NK-KODAMBAKKAM,129,1923000,"Relaying of Road with BCCMP by Using Mechanical Paver at Muthukumarappa street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1563,Roads,Completed,NK-KODAMBAKKAM,129,2423000,"Relaying of Road with BCCMP by Using Mechanical Paver at Bharathi street gandhi nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1564,Roads,Completed,NK-KODAMBAKKAM,129,616000,"Relaying of Road with BCCMP by Using Mechanical Paver at Dr.Ambedkar street (part) in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1565,Roads,Completed,NK-KODAMBAKKAM,129,987000,"Relaying of Road with BCCMP by Using Mechanical Paver at Bharathidasan street baskar colony in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1566,Roads,Completed,NK-KODAMBAKKAM,129,1144000,"Relaying of Road with BCCMP by Using Mechanical Paver at Balaji nagar 1st street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1567,Roads,Completed,NK-KODAMBAKKAM,129,1144000,"Relaying of Road with BCCMP by Using Mechanical Paver at Balaji nagar 2nd street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1568,Roads,Completed,NK-KODAMBAKKAM,129,449000,"Relaying of Road with BCCMP by Using Mechanical Paver at Balaji nagar 3rd street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1569,Roads,Completed,NK-KODAMBAKKAM,129,357000,"Relaying of Road with BCCMP by Using Mechanical Paver at Balaji nagar 1st cross street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1570,Roads,Completed,NK-KODAMBAKKAM,129,493000,"Relaying of Road with BCCMP by Using Mechanical Paver at Balaji nagar 2nd cross street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1571,Roads,Completed,NK-KODAMBAKKAM,129,740000,"Relaying of Road with BCCMP by Using Mechanical Paver at Logaiah colony 2nd main road in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1572,Roads,Completed,NK-KODAMBAKKAM,129,802000,"Relaying of Road with BCCMP by Using Mechanical Paver at Logaiah colony 5th cross street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1574,Roads,Completed,NK-KODAMBAKKAM,129,757000,"Relaying of Road with BCCMP by Using Mechanical Paver at at Thilagar street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1575,Roads,Completed,NK-KODAMBAKKAM,129,403000,"Relaying of Road with BCCMP by Using Mechanical Paver at Nehru nagar main road ( Part) in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1576,Roads,Completed,NK-KODAMBAKKAM,129,336000,"Relaying of Road with BCCMP by Using Mechanical Paver at Annamalai colony 1st street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1577,Roads,Completed,NK-KODAMBAKKAM,129,1076000,"Relaying of Road with BCCMP by Using Mechanical Paver at Annamalai colony 2nd street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1578,Roads,Completed,NK-KODAMBAKKAM,129,403000,"Relaying of Road with BCCMP by Using Mechanical Paver at Annamalai colony 3rd street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1579,Roads,Completed,NK-KODAMBAKKAM,129,1009000,"Relaying of Road with BCCMP by Using Mechanical Paver at Navalar high road (part) division-129,Unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1581,Roads,Completed,NK-KODAMBAKKAM,129,1838000,"Improvement to bituminous concrete at Sambhu prasad avenue in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1589,Roads,Completed,NK-KODAMBAKKAM,129,890000,"Laying of cement concrete using M30 at Mosque Garden 1st street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1591,Roads,Completed,NK-KODAMBAKKAM,129,677000,"Laying of cement concrete using by M30 road at Mosque garden 2nd street in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1592,Roads,Completed,NK-KODAMBAKKAM,129,1079000,"Laying of cement concrete using by M30 at Dhasarathapuram 3rd sstreet in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1593,Roads,Completed,NK-KODAMBAKKAM,129,1378000,"Relaying of cement concrete road at Dr.Ambedkar nagar in division-129, unit-29, Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16625,Parks,Completed,NK-KODAMBAKKAM,129,362000,"MAINTENANCE ESTIMATE FOR PARK AT NAVALAR STREET IN DN-129, U-29, ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16626,Parks,Completed,NK-KODAMBAKKAM,129,759000,"MAINTENANCE ESTIMATE FOR PARK AT ARCOT ROAD(APPASWANY PARK ) IN DN-129, U-29, ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16627,Parks,Completed,NK-KODAMBAKKAM,129,235000,"MAINTENANCE ESTIMATE FOR PARK AT PILLAYR KOIL STREET, K.R.NAGAR PARK IN DN-129, U-29, ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16628,Parks,Completed,NK-KODAMBAKKAM,129,223000,"MAINTENANCE ESTIMATE FOR PARK AT NSK LANE IN DN-129, U-29, ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16629,Parks,Completed,NK-KODAMBAKKAM,129,787000,"MAINTENANCE ESTIMATE FOR PARK AT ABUSALI ROAD PARK IN DN129, U-29, ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16630,Parks,Completed,NK-KODAMBAKKAM,129,604000,"MAINTENANCE ESTIMATE FOR PARK AT BHASKAR COLONY PARK IN DN-129, U-29, ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16688,Buildings,Completed,NK-KODAMBAKKAM,129,183000,"Abstract for Maintenance Estimate for Park at Kumaran Colony - 4th Street in Dn-129, Unit-29, Zone-10, ( from 1st Apr 2019 to 31st Aug 2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/2389,Roads,Completed,NK-KODAMBAKKAM,129,539000,"Improvement to bituminous concrete at S.S.R Pangajam cross street in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2390,Roads,Completed,NK-KODAMBAKKAM,129,1414000,"Improvement to bituminous concrete at Nehru nagar main road in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/2391,Roads,Completed,NK-KODAMBAKKAM,129,477000,"Improvement to bituminous concrete at Sasthiri street in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2392,Roads,Completed,NK-KODAMBAKKAM,129,303000,"Improvement to bituminous concrete at thiyagi sangaralingam street in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2393,Roads,Completed,NK-KODAMBAKKAM,129,131000,"Improvement to bituminous concrete at Kesavalu street in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2394,Roads,Completed,NK-KODAMBAKKAM,129,980000,"Improvement to bituminous concrete at Pillayar koil street (gandhi nagar) in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2396,Roads,Completed,NK-KODAMBAKKAM,129,510000,"Improvement to bituminous concrete at anna street ( door no.25 to 20/2) in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2398,Roads,Completed,NK-KODAMBAKKAM,129,186000,"Improvement to bituminous concrete at anna cross street (gandhi nagar) in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2399,Roads,Completed,NK-KODAMBAKKAM,129,114000,"Improvement to bituminous concrete at Thiruvallvar street in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/2400,Roads,Completed,NK-KODAMBAKKAM,129,208000,"Improvement to bituminous concrete at Gangappa street in division-129, Unit-29, Zone-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/5288,Buildings,Completed,NK-KODAMBAKKAM,129,235000,"Engaging Private Labours for House Keeping Work and Scavengers For the Period Of 1 Year At UPHC, Dhsarathapuram 8th street, Saligramam, in div-129, Unit-29 , Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5289,Buildings,Completed,NK-KODAMBAKKAM,129,136000,"Engaging Private Labours for Security Guards For the Period Of 1 Year At UPHC, Dhsarathapuram 8th street, Saligramam, in div-129, Unit-29 , Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/6157,Roads,Completed,NK-KODAMBAKKAM,129,96000,"ATTENDING PATCH WORK USING BC 40MM THICK BY PAVER FINISHER AT ABUSALI STREET IN DN-129,U-29,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/6161,Roads,Completed,NK-KODAMBAKKAM,129,32000,"ATTENDING PATCH WORK USING BC 40MM THICK BY PAVER FINISHER AT DEVARAJ NAGAR MAIN ROAD IN DN-129,U-29,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/7125,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,340000,"Improvements and repairs to SWD at Arunachalam Road in div-129, unit-29, zone-10",Own Sources,10,2018-19,2018-19 NK/2018-19/7733,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,807000,"Desilting of storm water Drain at Various street in division-129, unit-29, Zone-10.",Own Sources,10,2018-19,2018-19 NK/2018-19/8200,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,495000,"Minor repairs of Storm Water Drain with Manhole door at Various street in Div-129, Unit-29,Zone-10",Own Sources,10,2018-19,2020-21 NK/2018-19/8993,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,621000,"Minor repairs of Storm Water Drain with Manhole door at Various street in Div-129, Unit-29,Zone-10",Own Sources,10,2018-19,2018-19 BR/2018-19/15672,Road Cut,Completed,BR-Bus Route Roads,130,283000,Restoration of OFC road cut made by Reliance at various Bus Route Roads in Zone-X (Deposit Code-57/0054/2018-19),Deposit Works,10,2018-19,2019-20 BR/2018-19/5956,Road Cut,Completed,BR-Bus Route Roads,130,2400000,"Restoration of roadcut made by CMWSSB at NSK Salai from the jn of Vadapalani bus stand to the jn of 100 ft road in Dn - 130, Zone -10 (Chellan No BR/2017-18/0002850)",Deposit Works,10,2018-19,2018-19 BR/2018-19/6461,Road Cut,Completed,BR-Bus Route Roads,130,620000,"Restoration of roadcut made by TANGEDCO at PT Rajan Salai in Dn 130, Zone - 10 (Chellan No: BR/2017-18/0017041)",Deposit Works,10,2018-19,2019-20 BR/2018-19/6671,Roads,Completed,BR-Bus Route Roads,130,2805000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at West Sivan Koil Street in Dn-130, Zone - X",Grants,10,2018-19,2019-20 BR/2018-19/6672,Roads,Completed,BR-Bus Route Roads,130,1660000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at South Sivan Koil Street in Dn-130, Zone - X",Grants,10,2018-19,2019-20 L/2018-19/0261,Electrical,Completed,L-Electrical,130,3420000,"Provision of 86 nos of 7 mtr lamp post with 40w LED Fitting at Rajangamandir Veethi, Bajanaikoil st, Meigai Vinayagar koil st, Desigar st,Pillaiyar koil st and other streets Division 130 in Zone-10",Own Sources,10,2018-19,2018-19 L/2018-19/5681,Electrical,Completed,L-Electrical,130,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at School , Amman Koil Street, Vadapalani in Div 130, Zone-10",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5690,Electrical,Completed,L-Electrical,130,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Proposal Ward Nerkundram Pathai , Vadapalani in Div 130, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5697,Electrical,Completed,L-Electrical,130,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Multi Purpose Hall Rajangam Mathiya Veethi, Vadapalani in Div 130, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5705,Electrical,Completed,L-Electrical,130,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Multi-purpose Hall Rajangam Mathiya Veethi east side Vadapalani in Div 130, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5743,Electrical,Completed,L-Electrical,130,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC Rajangam Mathiya Veethi, Vadapalani in Div 130, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/1600,Roads,Completed,NK-KODAMBAKKAM,130,511000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT PARAMESWARA COLONY IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1608,Roads,Completed,NK-KODAMBAKKAM,130,602000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT NORTH MADA STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1611,Roads,Completed,NK-KODAMBAKKAM,130,1554000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT ALAGIRI NAGAR MAIN ROAD IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1613,Roads,Completed,NK-KODAMBAKKAM,130,702000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT ALAGIRI NAGAR 3RD STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1625,Roads,Completed,NK-KODAMBAKKAM,130,699000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT ALAGIRI NAGAR EAST STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1626,Roads,Completed,NK-KODAMBAKKAM,130,113000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT KAMATHCHIAMMAN COLONY 1ST STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1630,Roads,Completed,NK-KODAMBAKKAM,130,223000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT GANESH AVENUE IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1631,Roads,Completed,NK-KODAMBAKKAM,130,506000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT KANNIYAPPAN STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1633,Roads,Completed,NK-KODAMBAKKAM,130,866000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT MANNAR 2ND STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1636,Roads,Completed,NK-KODAMBAKKAM,130,456000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT DESIGAR STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1637,Roads,Completed,NK-KODAMBAKKAM,130,465000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT GANGAIAMMAN KOVIL 1ST STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1638,Roads,Completed,NK-KODAMBAKKAM,130,462000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT GANGAIAMMAN KOVIL 2ND STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2020-21 NK/2018-19/1640,Roads,Completed,NK-KODAMBAKKAM,130,3086000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT GANGAIAMMAN KOVIL STREET (VADAPALANI) IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1645,Roads,Completed,NK-KODAMBAKKAM,130,447000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT RAGHAVAN COLONY IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1646,Roads,Completed,NK-KODAMBAKKAM,130,331000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT ANDAVAR NAGAR 1ST STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1647,Roads,Completed,NK-KODAMBAKKAM,130,251000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT JEEVA STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5290,Buildings,Completed,NK-KODAMBAKKAM,130,117800,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI MIDDLE SCHOOL (2 SWEEPERS & 2 SCAVENGERS) AT AMMAN KOVIL STREET EAST ,VADAPALANI IN DIV-130, U-29, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2018-19 NK/2018-19/5295,Buildings,Completed,NK-KODAMBAKKAM,130,234000,"OUTSOURCING PRIVATE LABOURS FOR U.P.H.C, (2 SWEEPERS & 2 SCAVENGERS) AT RAJANGA MADHIYA VEETHI,VADAPALANI IN DIV-130, U-29, Z-10 (FOR 11 MONTHS)",Own Sources,10,2018-19,2019-20 NK/2018-19/5300,Buildings,Completed,NK-KODAMBAKKAM,130,136000,"Engaging Private Labours for Security Guards For the Period Of 1 Year At UPHC, Rajanga Madhiya Veedhi, Vadapalani in Div-130, Unit-29 , Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5813,Roads,Completed,NK-KODAMBAKKAM,130,80000,"ATTENDING PATCH WORK IN SOUTH PERUMAL KOVIL STREET ,VADAPALANI IN DIVISION-130,UNIT-29,ZONE-X.",Own Sources,10,2018-19,2019-20 NK/2018-19/5814,Roads,Completed,NK-KODAMBAKKAM,130,110000,"ATTENDING PATCH WORK IN NEW VELLALAL STREET ,VADAPALANI IN DIVISION-130,UNIT-29,ZONE-X.",Own Sources,10,2018-19,2019-20 NK/2018-19/9022,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,310000,"REPAIR & MAINTENANCE WORKS TO THE DAMAGED PORTIONS OF STORM WATER DRAIN AT ARCOT ROAD (SALIGRAMAM & VADAPALANI), NGO COLONY MAIN ROAD, AMMAN KOIL STREET (EAST), NERKUNDRAM PATHAI (WEST), DHARAN SINGH COLONY 1ST STREET, THIRUNAGAR MAIN ROAD, HOSTEL ROAD, ALAGIRI NAGAR 2ND & 3RD STREET, ANDAVAR NAGAR 2ND, 3RD, 5TH & 6TH STREET, GANAGAIAMMAN KOIL STREET (VADAPALANI), KUMARAN COLONY MAIN ROAD & ALAGIRI NAGAR MAIN ROAD AND VARIOUS STREETS IN DN-130,U-29,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9090,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,274000,"DESILTING OF STORM WATER DRIAN AT ARCOT ROAD (SALIGRAMAM & VADAPALANI), NGO COLONY MAIN ROAD, AMMAN KOIL STREET (EAST), NERKUNDRAM PATHAI (WEST), DHARAN SINGH COLONY 1ST STREET, THIRUNAGAR MAIN ROAD, HOSTEL ROAD, ALAGIRI NAGAR 2ND & 3RD STREET, ANDAVAR NAGAR 2ND, 3RD, 5TH & 6TH STREET, GANAGAIAMMAN KOIL STREET (VADAPALANI), KUMARAN COLONY MAIN ROAD & ALAGIRI NAGAR MAIN ROAD IN DN-130,U-29,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9408,Buildings,Completed,NK-KODAMBAKKAM,130,267000,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI MIDDLE SCHOOL (2 SWEEPERS & 2 SCAVENGERS) AT AMMAN KOVIL STREET EAST ,VADAPALANI IN DIV-130, U-29, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 BR/2018-19/2909,Road Cut,Completed,BR-Bus Route Roads,131,840000,"Restoration of Road cut made by CMWSSB at P.T.Rajan salai in Division - 131,Zone-X.",Deposit Works,10,2018-19,2019-20 L/2018-19/5748,Electrical,Completed,L-Electrical,131,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Unavagam, PV Rajamannar salai in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5761,Electrical,Completed,L-Electrical,131,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at FAMILY WELFAIR KANNIGAPURAM 1ST STREET in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5793,Electrical,Completed,L-Electrical,131,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ANGAWADI BOBBILIRAJA SALAI in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5796,Electrical,Completed,L-Electrical,131,311900,"Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC vijayaragavapuram 3rd st in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5797,Electrical,Completed,L-Electrical,131,311900,"Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC vijayaragavapuram 1st cross in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5801,Electrical,Completed,L-Electrical,131,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at GYM 1ST SECTOR PLAY FIELD in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5803,Electrical,Completed,L-Electrical,131,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at GYM 2ND SECTOR PLAY FIELD in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5810,Electrical,Completed,L-Electrical,131,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Multi Purpose Hall-Sivalingapuram(Puthiya Kudiirupu) in Div 131, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/15969,Parks,Completed,NK-KODAMBAKKAM,131,1263000,MAINTANANCE OF SIVAN PARK AT P.T.RAJAN SALAI KK NAGAR IN DIVISION-131.,Own Sources,10,2018-19,2019-20 NK/2018-19/1601,Roads,Completed,NK-KODAMBAKKAM,131,928000,"LAYING OF CEMENT CONCRETE ROAD AT SIVALINGAPURAM 13TH SECTOR 85TH STREET IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1605,Roads,Completed,NK-KODAMBAKKAM,131,435000,"LAYING OF CEMENT CONCRETE ROAD AT MARUTHAPADIAN STREET,MGR NAGAR IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1606,Roads,Completed,NK-KODAMBAKKAM,131,351000,"LAYING OF CEMENT CONCRETE ROAD AT ANJUGAM STREET,MGR NAGAR IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1609,Roads,Completed,NK-KODAMBAKKAM,131,452000,"LAYING OF CEMENT CONCRETE ROAD AT KAMARAJAR STREET VIJAYARAGAVAPURAM IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1612,Roads,Completed,NK-KODAMBAKKAM,131,1024000,"RELAYING BITUMINOUS CONCRETE ROAD AT DR.NATESAN ROAD KK NAGAR IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/16545,Buildings,Completed,NK-KODAMBAKKAM,131,200000,"MAINTANANCE OF RANI ANNA NAGAR PARK AT KK NAGAR IN DIV-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3362,Roads,Completed,NK-KODAMBAKKAM,131,200000,"ATTENDING PATCH WORK AT BHARANI COLONY AND VARIOUS PLACES IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/7776,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,863000,"DESILTING OF STORMWATER DRAIN AT P.T.RAJAN SALAI AND VARIOUS STREET IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/7777,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,154000,"REPAIRS OF STORMWATER DRAIN AND REPLACE OF DAMAGED MANHOLE COVER AT R.K.SHANMUGAM SALAI AND VARIOUS STREET IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 BR/2018-19/5599,Roads,Completed,BR-Bus Route Roads,132,795000,Providing and Laying Mastic Asphalt of 25mm thick at PT Rajan Salai and Other Bus Roue Roads in Zone-10,Own Sources,10,2018-19,2020-21 BR/2018-19/6555,Footpath,Completed,BR-Bus Route Roads,132,11596000,"Forming Footpath at Kamarajar Salai in Dn-132, Zone-X",Grants,10,2018-19,2020-21 L/2018-19/5894,Electrical,Completed,L-Electrical,132,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 35th str health post, in Div 132, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/0081,Roads,Completed,NK-KODAMBAKKAM,132,2799000,"LAYING OF CEMENT CONCRETE ROAD AT PUDUR 2ND STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/0082,Roads,Completed,NK-KODAMBAKKAM,132,776000,"LAYING OF CEMENT CONCRETE ROAD AT PUDUR 4TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/0084,Roads,Completed,NK-KODAMBAKKAM,132,826000,"LAYING OF CEMENT CONCRETE ROAD AT PUDUR 5TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/0085,Roads,Completed,NK-KODAMBAKKAM,132,665000,"LAYING OF CEMENT CONCRETE ROAD AT PUDUR 7TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/11479,Buildings,Completed,NK-KODAMBAKKAM,132,332500,"REPAIR AND MAINTAINANCE OF AMMA UNAVAGAM AT 6TH AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1449,Roads,Completed,NK-KODAMBAKKAM,132,569000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT BANK OF INDIA COLONY IN DIV-132, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1500,Roads,Completed,NK-KODAMBAKKAM,132,317000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT 35TH STREET(PART), ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/15951,Parks,Completed,NK-KODAMBAKKAM,132,844000,"ANNUAL MAINTENANCE OF 1ST AVENUE PARK AT ASHOK NAGAR IN DIV-132, U-31, Z-10 (QUALIFIED HORTICULTURIST ONLY) (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/15952,Parks,Completed,NK-KODAMBAKKAM,132,525000,"ANNUAL MAINTENANCE OF PARK AT 14TH SECTOR 102ND STREET PARK (FOR 1 YEAR) IN DIVISION-132,UNIT-31,ZONE-10 (EMPLOYED QUALIFIED HORTICULTURIST FOR ONE YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/15953,Parks,Completed,NK-KODAMBAKKAM,132,414000,"ANNUAL MAINTENANCE OF PARK AT 12TH AVENUE, ASHOK NAGAR IN DIVISION-132, UNIT-31, ZONE -10.. (Employed qualified Horticulturist for one year only)",Own Sources,10,2018-19,2019-20 NK/2018-19/1652,Roads,Completed,NK-KODAMBAKKAM,132,481000,"LAYING OF CEMENT CONCRETE ROAD AT THANGAVEL COLONY, VADAPALANI IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1654,Roads,Completed,NK-KODAMBAKKAM,132,385000,"LAYING OF CEMENT CONCRETE ROAD AT N.G.O COLONY 2ND STREET, VADAPALANI IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5148,Buildings,Completed,NK-KODAMBAKKAM,132,29400,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL, KANNIYAPPA NAGAR AT 83RD STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2019-20 NK/2018-19/5149,Buildings,Completed,NK-KODAMBAKKAM,132,117800,"OUTSOURCING PRIVATE LABOURS FOR GOVERNMENT HR. SEC. SCHOOL, PUDUR (2 SWEEPERS & 2 SCAVENGERS) AT 3RD AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2018-19 NK/2018-19/5151,Buildings,Completed,NK-KODAMBAKKAM,132,58900,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI HIGH SCHOOL, KANNIYAPPA NAGAR AT 83RD STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2019-20 NK/2018-19/5153,Buildings,Completed,NK-KODAMBAKKAM,132,117800,"OUTSOURCING PRIVATE LABOURS FOR GOVERNMENT GIRLS HR. SEC. SCHOOL (2 SWEEPERS & 2 SCAVENGERS) AT 9TH AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2018-19 NK/2018-19/5154,Buildings,Completed,NK-KODAMBAKKAM,132,29400,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL, PULIYUR AT N.S.K. SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2019-20 NK/2018-19/5155,Buildings,Completed,NK-KODAMBAKKAM,132,88400,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI HR.SEC. SCHOOL, PULIYUR AT N.S.K. SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2018-19 NK/2018-19/5296,Buildings,Completed,NK-KODAMBAKKAM,132,273000,"PROVIDING SECURITY ARRANGEMENTS FOR UPHC AT 5TH AVENUE, ASHOK NAGAR IN DIV-133, U-31, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/5301,Buildings,Completed,NK-KODAMBAKKAM,132,235700,"OUTSOURCING PRIVATE LABOURS FOR UPHC AT 35TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2020-21 NK/2018-19/5302,Buildings,Completed,NK-KODAMBAKKAM,132,273000,"PROVIDING SECURITY ARRANGEMENTS FOR UPHC AT 35TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2020-21 NK/2018-19/8979,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,291000,"DESILTING OF STORM WATER DRAIN AT 4TH & 7TH AVENUE ASHOK NAGAR, PUDUR 1ST STREET, KAMARAJAR SALAI (WESTERN SIDE), 86TH STREET, 18TH AVENUE (EASTERN SIDE), 2ND AVENUE ASHOK NAGAR, 41ST STREET AND 3RD AVENUE IN DN-132,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9012,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,530000,"REPAIR & MAINTENANCE WORKS TO THE DAMAGED PORTIONS OF STORM WATER DRAIN AT 4TH & 7TH AVENUE ASHOK NAGAR, PUDUR 1ST STREET, 86TH STREET, 18TH AVENUE (EASTERN SIDE), 2ND AVENUE ASHOK NAGAR, 41ST STREET, 3RD AVENUE AND VARIOUS STREETS IN DN-132,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9334,Buildings,Completed,NK-KODAMBAKKAM,132,266000,"OUTSOURCING PRIVATE LABOURS FOR GOVERNMENT GIRLS HR. SEC. SCHOOL (2 SWEEPERS & 2 SCAVENGERS) AT 9TH AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9335,Buildings,Completed,NK-KODAMBAKKAM,132,133000,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI HIGH SCHOOL, KANNIYAPPA NAGAR AT 83RD STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9336,Buildings,Completed,NK-KODAMBAKKAM,132,266000,"OUTSOURCING PRIVATE LABOURS FOR GOVERNMENT HR. SEC. SCHOOL, PUDUR (2 SWEEPERS & 2 SCAVENGERS) AT 3RD AVENUE, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9337,Buildings,Completed,NK-KODAMBAKKAM,132,66000,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL, KANNIYAPPA NAGAR AT 83RD STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9342,Buildings,Completed,NK-KODAMBAKKAM,132,200000,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI HR.SEC. SCHOOL, PULIYUR AT N.S.K. SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9343,Buildings,Completed,NK-KODAMBAKKAM,132,66700,"OUTSOURCING PRIVATE LABOURS FOR CHENNAI PRIMARY SCHOOL, PULIYUR AT N.S.K. SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9792,Buildings,Completed,NK-KODAMBAKKAM,132,1156000,"OPERATION AND MAINTENANCE OF GAS (LPG) CREMATORIUM AT AVM BURIAL GROUND IN DIVISION -132,UNIT - 31,ZONE- 10 (FOR 1 YEAR ONLY)",Own Sources,10,2018-19,2020-21 BR/2018-19/12233,Road Cut,Completed,BR-Bus Route Roads,133,198000,"Restoration of Roadcut made by CMWSSB at Ashok Nagar 4th Avenue (Dr.Ambedkar Road) in Dn-133, Zone-10",Deposit Works,10,2018-19,2019-20 BR/2018-19/6668,Roads,Completed,BR-Bus Route Roads,133,7981000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Kodambakkam Road in Dn-133 & 140, Zone - X",Grants,10,2018-19,2019-20 D/2018-19/9426,Storm Water Drain,Completed,D-Storm Water Drains,133,45529000,Construction of Storm Water Drain at Seventh Sector 34th & 38th Street and 3 Other Roads in Zone - 10 - Package - 43.,Grants,10,2018-19,2020-21 D/2018-19/9428,Storm Water Drain,Completed,D-Storm Water Drains,133,36379000,Construction of Storm Water Drain at Abusali Street on North Side and Kalaignar karunanidhi Road on East Side in Zone - 10 - Package - 45,Grants,10,2018-19,2019-20 L/2018-19/5861,Electrical,Completed,L-Electrical,133,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, 15th street, Mullai Nagar,,Ashok Nagar in Div 133, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/1507,Roads,Completed,NK-KODAMBAKKAM,133,495000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT PALAYAKKARAN STREET IN DIV-133, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1508,Roads,Completed,NK-KODAMBAKKAM,133,148000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT PALANIYAPPA STREET IN DIV-133, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1509,Roads,Completed,NK-KODAMBAKKAM,133,730000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT SATHYANARAYANA STREET IN DIV-133, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1510,Roads,Completed,NK-KODAMBAKKAM,133,845000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT SUBBURAYAN NAGAR 6TH STREET IN DIV-133, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1511,Roads,Completed,NK-KODAMBAKKAM,133,434000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT SUBBURAYAN NAGAR MAIN ROAD IN DIV-133, U-31, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1602,Roads,Completed,NK-KODAMBAKKAM,133,304000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT NEW VELLALAL (PART) STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1627,Roads,Completed,NK-KODAMBAKKAM,133,173000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT KAMATCHIAMMAN COLONY 2ND STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1628,Roads,Completed,NK-KODAMBAKKAM,133,166000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT N.G.O COLONY 3RD STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1629,Roads,Completed,NK-KODAMBAKKAM,133,203000,"RELAYING OF BITUMINOUS CONCRETE ROAD AT N.G.O COLONY 3RD CROSS STREET IN DIV-130, U-29, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5156,Buildings,Completed,NK-KODAMBAKKAM,133,29400,"OUTSOURCING PRIVATE LABOURS FOR MULLAI NAGAR CHENNAI PRIMARY SCHOOL, 15TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (FOR 3 MONTHS)",Own Sources,10,2018-19,2019-20 NK/2018-19/5293,Buildings,Completed,NK-KODAMBAKKAM,133,235700,"OUTSOURCING PRIVATE LABOURS FOR UPHC AT 5TH AVENUE, ASHOK NAGAR IN DIV-133, U-31, Z-10 (FOR 1 YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/6493,Buildings,Completed,NK-KODAMBAKKAM,133,1700000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT KASIKULAM, WEST MAMBALAM IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2018-19)",MLACDS,10,2018-19,2019-20 NK/2018-19/8787,Roads,Completed,NK-KODAMBAKKAM,133,317000,"PROVIDING INTERLOCKING BLOCKS AT PALAYAKKARAN STREET IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2018-19)",MLACDS,10,2018-19,2019-20 NK/2018-19/8817,Roads,Completed,NK-KODAMBAKKAM,133,945000,"PROPOSED LAYING OF CEMENT CONCRETE ROAD AT PALAYAKKARAN 1ST STREET IN DIV-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2018-19)",MLACDS,10,2018-19,2018-19 NK/2018-19/9086,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,323000,"REPAIR & MAINTENANCE WORKS TO THE DAMAGED PORTIONS OF STORM WATER DRAIN AT 10TH AVENUE, POSTAL COLONY 3RD STREET, DURAISMAY ROAD, PALAYAKARAN STREET, V.O.C. NAGAR 1ST MAIN ROAD, SUBBURAYAN NAGAR 8TH STREET, R.N.NAMBIAR STREET, 23RD & 24TH STREET ASHOK NAGAR AND VARIOUS STREETS IN DN-133,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9341,Buildings,Completed,NK-KODAMBAKKAM,133,66000,"OUTSOURCING PRIVATE LABOURS FOR MULLAI NAGAR CHENNAI PRIMARY SCHOOL, 15TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10 (FROM 10.10.2018 TO 30.04.2019)",Own Sources,10,2018-19,2019-20 B/2018-19/10227,Buildings,Completed,B-Buildings,134,6225418,"PROPOSED CONSTRUCTION OF GYM BUILDING IN GROUND FLOOR AT KAMARAJAR COLONY ,KODAMBAKKAM IN DN-134,Z-10",MPLADS,10,2018-19,2020-21 B/2018-19/11092,Buildings,Completed,B-Buildings,134,10570000,"PROPOSED CONSTRUCTION OF BOXING HALL IN FIRST FLOOR AND INDOOR GAMES IN SECOND FLOOR OVER THE EXISTING GYM BUILDING AT KAMARAJAR COLONY ,KODAMBAKKAM IN DN-134,Z-10",Own Sources,10,2018-19,2020-21 L/2018-19/5683,Electrical,Completed,L-Electrical,134,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Malaria Hospital Corporation Colony,Kodambakkam in Div 134, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5686,Electrical,Completed,L-Electrical,134,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Electrical substation, Kodambakkam in Div 134, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/8039,Electrical,Completed,L-Electrical,134,195600,"Electrification of Ambedkar Salai Community Center , Ranagarajapuram PCs in Division 134 in Zone-10",Own Sources,10,2018-19,2019-20 L/2018-19/8052,Electrical,Completed,L-Electrical,134,199200,"Erection of 2 nos of Split Ac Unit Blood Bank room , Zonal medical officer room at EOC Vadapalani in Division 134 in Zone-10",Own Sources,10,2018-19,2019-20 NK/2018-19/11503,Buildings,Completed,NK-KODAMBAKKAM,134,571000,"REPAIR AND IMPROVEMENT WORKS TO THE EXISTING AMMA UNAVAGAM AT KAMARAJAR COLONY 1ST STREET (OLD AMMA UNAVAGAM) IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/16302,Parks,Completed,NK-KODAMBAKKAM,134,407000,"MAINTENANCE WORKS TO THE ANNA PARK AT U.I.COLONY IN DN-134, U-31, Z-10 (FOR ONE YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/16304,Parks,Completed,NK-KODAMBAKKAM,134,628000,"MAINTENANCE WORKS TO THE KALAINGAR PARK AT CORPORATION COLONY ROAD IN DN-134, U-31, Z-10 (FOR ONE YEAR)",Own Sources,10,2018-19,2019-20 NK/2018-19/1687,Roads,Completed,NK-KODAMBAKKAM,134,786000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT ANNA MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1695,Roads,Completed,NK-KODAMBAKKAM,134,1711000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT U.I.COLONY 4TH MAIN ROAD AND WEST AVENUE IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1713,Roads,Completed,NK-KODAMBAKKAM,134,559000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT U.I.COLONY 3RD MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1852,Roads,Completed,NK-KODAMBAKKAM,134,385000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KAMARAJAR COLONY 4TH STREET IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1855,Roads,Completed,NK-KODAMBAKKAM,134,341000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KAMARAJAR COLONY 6TH STREET IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1858,Roads,Completed,NK-KODAMBAKKAM,134,522000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KAMARAJAR COLONY 9TH STREET IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/4516,Buildings,Completed,NK-KODAMBAKKAM,134,427000,"PROVIDING TOILET AND WATER SUPPLY ARRANGEMENTS TO MULTIPURPOSE HALL AT RAILWAY BORDER ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/5159,Roads,Completed,NK-KODAMBAKKAM,134,166000,"ATTENDING PATCH WORK USING BC 40MM THICK BY PAVER FINISHER AT VARIOUS STREET IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5240,Buildings,Completed,NK-KODAMBAKKAM,134,58900,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (3 MONTHS) FOR CHENNAI PRIMARY SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5241,Buildings,Completed,NK-KODAMBAKKAM,134,58900,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (3 MONTHS) FOR CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5242,Buildings,Completed,NK-KODAMBAKKAM,134,58900,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (3 MONTHS) FOR CHENNAI MIDDLE SCHOOL AT KAMARAJAR COLONY IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5243,Buildings,Completed,NK-KODAMBAKKAM,134,58900,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (3 MONTHS) FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/5245,Buildings,Completed,NK-KODAMBAKKAM,134,846000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING AND ENGAGING SECURITY GUARDS (ONE YEAR) FOR COMMUNITY WELFARE CENTER VADAPALANI (24 HOURS MATERNITY HOSPITAL & EMERGENCY OPERATIVE CARE) AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5246,Buildings,Completed,NK-KODAMBAKKAM,134,560000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING AND ENGAGING SECURITY GUARDS(ONE YEAR) FOR UPHC AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5492,Buildings,Completed,NK-KODAMBAKKAM,134,241000,"ARRANGEMENTS FOR BLOOD STORAGE UNIT IN COMMUNITY WELFARE CENTER (24 HOURS MATERNITY HOSPITAL) AT N.S.K.SALAI IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/8705,Buildings,Completed,NK-KODAMBAKKAM,134,110000,"DEMOLITION OF EXISTING DAMAGED PUBLIC CONVENIENCE AT RANGARAJAPURAM MAIN ROAD (JN.OF KAMARAJAR COLONY 1ST STREET) IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/8707,Buildings,Completed,NK-KODAMBAKKAM,134,191600,"DEMOLITION OF EXISTING DAMAGED ADDITIONAL SCHOOL BUILDING AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/8827,Parks,Completed,NK-KODAMBAKKAM,134,1438000,"PROVIDING OUTDOOR GYM EQUIPMENT AND PLAY APPARATUS FOR ANNA PARK AT U.I.COLONY IN DN-134,U-31,Z-10 (UNDER T.NAGAR MLA FUND 2018-19)",MLACDS,10,2018-19,2019-20 NK/2018-19/8976,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,1267000,"DESILTING OF STORM WATER DRAIN AT N.S.K.SALAI, RANGARAJAPURAM MAIN ROAD, CORPORATION COLONY MAIN ROAD, PASUMARTHY LANE, U.I.COLONY PARK VIEW ROAD, CENTRAL AVENUE, RAILWAY BORDER ROAD, STATION VIEW ROAD, U.I.COLONY 1ST, 2ND, 3RD & 4TH MAIN ROAD, U.I.COLONY 1ST, 2ND, 3RD, 4TH, 5TH & 6TH CROSS STREET, U.I.COLONY CIRCULAR ROAD AND VARIOUS STREETS IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/8978,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,148000,"DESILTING OF STORM WATER DRAIN AT 10TH AVENUE, POSTAL COLONY 3RD STREET, DURAISAMY ROAD, PALAYAKARAN STREET, V.O.C.NAGAR 1ST MAIN ROAD, SUBRAYAN NAGAR 8TH STREET, R.N.NAMBIYAR STREET, 19TH, 23RD & 24TH STREET AND 61ST STREET, ASHOK NAGAR IN DN-133,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/8984,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,872000,"REPAIR & IMPROVEMENT WORKS TO THE DAMAGED PORTION OF STORM WATER DRAIN AT N.S.K.SALAI, RANGARAJAPURAM MAIN ROAD, CORPORATION COLONY ROAD, PASUMARTHY LANE, CENTRAL AVENUE,RAILWAY BORDER ROAD, STATION VIEW ROAD, U.I.COLONY 1ST, 2ND & 3RD MAIN ROAD, U.I.COLONY 1ST, 2ND, 3RD, 4TH & 5TH CROSS STREET, U.I.COLONY CIRCULAR ROAD AND VARIOUS STREETS IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/9325,Buildings,Completed,NK-KODAMBAKKAM,134,133000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (FROM 10.10.2018 TO 30.04.2019) FOR CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9326,Buildings,Completed,NK-KODAMBAKKAM,134,133000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (FROM 10.10.2018 TO 30.04.2019) FOR CHENNAI MIDDLE SCHOOL AT KAMARAJAR COLONY IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9327,Buildings,Completed,NK-KODAMBAKKAM,134,133000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (FROM 10.10.2018 TO 30.04.2019) FOR CHENNAI PRIMARY SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/9328,Buildings,Completed,NK-KODAMBAKKAM,134,285000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (FROM 10.10.2018 TO 30.04.2019) FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2018-19,2019-20 B/2018-19/16111,Buildings,Completed,B-Buildings,135,4849000,"PROPOSED CONSTRUCTION OFCHILDRENS PLAY AREA IN SECOND FLOOR OVER THE EXISTING GYM BUILDING AT BHAKTAVACHALAM STREET, WEST MAMBALAM, IN DN-135, Z-10",Own Sources,10,2018-19,2020-21 B/2018-19/5959,Buildings,Completed,B-Buildings,135,14429422,"Proposed Construction of Gym Building and Yoga Traning Centre at Bhaktavachalam Street ,West Mambalam in Dn-135, Z-10",MPLADS,10,2018-19,2020-21 L/2018-19/5863,Electrical,Completed,L-Electrical,135,161500,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post ,5th Avenue,Ashok Nagar in Div 135, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5864,Electrical,Completed,L-Electrical,135,161500,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai School ,Eswarankoil st , West Mambalam in Div 135, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/0151,Roads,Completed,NK-KODAMBAKKAM,135,892000,"RELAYING OF ROAD USING BC 40MM THICK AT MOORTHI ST IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/0160,Roads,Completed,NK-KODAMBAKKAM,135,3010000,"PROPOSED RELAYING ROAD USING CC AT STATION ROAD (PART) IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2020-21 NK/2018-19/0458,Roads,Completed,NK-KODAMBAKKAM,135,847000,"RELAYING OF ROAD USING BC 40MM THICK AT MAHADEVAN STREET IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/0459,Roads,Completed,NK-KODAMBAKKAM,135,993000,"RELAYING OF ROAD USING BC 40MM THICK AT RAMAKRISHANAPURAM 3RD STREET IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/11122,Buildings,Completed,NK-KODAMBAKKAM,135,980000,"CONSTRUCTION OF MULTIPURPOSE HALL-1 (UNDER MLA FUND) AT BRINDAVAN STREET IN DIV-135,U-31,Z-10",MLACDS,10,2018-19,2019-20 NK/2018-19/11126,Buildings,Completed,NK-KODAMBAKKAM,135,1020000,"CONSTRUCTION OF MULTIPURPOSE HALL-2 AT BRINDAVAN STREET (UNDER MLA FUND) IN DIV-135, U-31, Z-10",MLACDS,10,2018-19,2019-20 NK/2018-19/11380,Buildings,Completed,NK-KODAMBAKKAM,135,700000,"CONSTRUCTION OF MULTIPURPOSE HALL (UNDER MLA FUND) AT ESWARANKOVIL STREET IN DIV-135, U-31, Z-10.",MLACDS,10,2018-19,2019-20 NK/2018-19/11473,Buildings,Completed,NK-KODAMBAKKAM,135,296000,"REPAIR AND MAINTENANCE WORK TO THE EXISTING AMMA UNAVAGAM AT THAMBAIAH ROAD (DIVISION 135 OFFICE BACK SIDE) IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/14262,Subway,Completed,NK-KODAMBAKKAM,135,512000,"IMPROVEMENT WORKS TO MADLEY SUBWAY PUMP ROOM (MARKET SIDE) AT MADLEY SUBWAY SERVICE ROAD IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2020-21 NK/2018-19/3135,Roads,Completed,NK-KODAMBAKKAM,135,907000,"RELAYING OF ROAD USING CC AT KASIVISHWANATHAN KOIL ST IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2020-21 NK/2018-19/5174,Roads,Completed,NK-KODAMBAKKAM,135,166000,"ATTENDING PATCH WORK USING BC 40MM THICK BY PAVER FINISHER AT VARIOUS STREET IN DN-135,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/5178,Buildings,Completed,NK-KODAMBAKKAM,135,88400,"OUT SOURCING OF PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK AT CHENNAI PRIMARY SCHOOL AT ESWARANKOIL STREET IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/8030,Buildings,Completed,NK-KODAMBAKKAM,135,103000,"DISMANTLING AND DEMOLISHING OF EXISTING GYM BUILDING AT BAKTHAVACHALAM ST PLAY GROUND IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/8031,Buildings,Completed,NK-KODAMBAKKAM,135,136000,"DISMANTLING AND DEMOLISHING OF EXISTING LIBRARY BUILDING AT BAKTHAVACHALAM ST PLAY GROUND IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/9073,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,839000,"DESILT OF STORM WATER DRAIN AT LAKSHMI STREET AND VARIOUS STREETS IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/9095,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,552000,"MINOR REPAIR WORK OF STORM WATER DRAIN AT ARYA GOWDA ROAD AND VARIOUS STREETS IN DIV-135, U-31,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/9324,Buildings,Completed,NK-KODAMBAKKAM,135,200400,"OUT SOURCING OF PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK (10.10.2018 TO 30.04.2019) AT CHENNAI PRIMARY SCHOOL AT ESWARANKOIL STREET IN DIV-135,U-31,Z-10",Own Sources,10,2018-19,2019-20 BR/2018-19/15513,Road Cut,Completed,BR-Bus Route Roads,136,261000,RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS - 136 UNIT - 30 ZONE-10,Deposit Works,10,2018-19,2019-20 BR/2018-19/18318,Roads,Completed,BR-Bus Route Roads,136,2500000,ATTENDING PATCH WORK AT VARIOUS BUS ROUTE ROAD IN ZONE-10,Own Sources,10,2018-19,2020-21 BR/2018-19/6673,Roads,Completed,BR-Bus Route Roads,136,3302000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at North Usman Service Road in Dn-136, Zone - X",Grants,10,2018-19,2019-20 L/2018-19/11563,Electrical,Completed,SP-SPECIAL PROJECTS,136,2880400,"Provision of Cables, HDPE Ducts, Erection of New Street Lights, Pedestrian Lights and other Lighting Arrangments in Pedestrian Plaza, Theyadaraya Road in Reach 1(Northern Side)",SMART CITY - SPECIAL PROJECTS,10,2018-19,2019-20 L/2018-19/11564,Electrical,Completed,SP-SPECIAL PROJECTS,136,2881800,"Provision of Cables, HDPE Ducts, Erection of New Street Lights, Pedestrian Lights and other Lighting Arrangments in Pedestrian Plaza, Theyadaraya Road in Reach 1(Southern Side)",SMART CITY - SPECIAL PROJECTS,10,2018-19,2019-20 L/2018-19/11565,Electrical,Completed,SP-SPECIAL PROJECTS,136,1822700,"Provision of Shifting Existing Street Light,Cables, HDPE Ducts Other Lighting Arrangements in All Reach and Supply of LED Strip for Seating in Reach 1 (Southern Side & Northern Side)in Pedestrian Plaza, Theyagaraya Road",SMART CITY - SPECIAL PROJECTS,10,2018-19,2019-20 L/2018-19/11566,Electrical,Completed,SP-SPECIAL PROJECTS,136,2787500,"Provision of Cables, HDPE Ducts, Erection of New Street Lights, Pedestrian Lights and other Lighting Arrangments in Pedestrian Plaza, Theyadaraya Road in Reach 2",SMART CITY - SPECIAL PROJECTS,10,2018-19,2019-20 L/2018-19/11567,Electrical,Completed,SP-SPECIAL PROJECTS,136,2094860,"Provision of Cables, HDPE Ducts, Erection of New Street Lights, Pedestrian Lights and other Lighting Arrangments in Pedestrian Plaza, Theyadaraya Road in Reach 3",SMART CITY - SPECIAL PROJECTS,10,2018-19,2020-21 L/2018-19/5788,Electrical,Completed,L-Electrical,136,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 136, Masilamani Street in Div 136, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5819,Electrical,Completed,L-Electrical,136,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ofc no. 119, Bazulla Road in Div 136, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5822,Electrical,Completed,L-Electrical,136,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Prakasam Road in Div 136, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/10897,Buildings,Completed,NK-KODAMBAKKAM,136,133600,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai Higher Secondary School and Chennai Middle School at Pragasam Road (Kannamapet) (7 months ) in Div -136, U-30, Z-10. (From 10.10.2018 to 30.04.2019).",Own Sources,10,2018-19,2020-21 NK/2018-19/12086,Buildings,Completed,NK-KODAMBAKKAM,136,925000,"CONSTRUCTION OF CAR PARKING SHED FOR UNIT OFFICE CAMPUS AT USMAN ROAD IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/13282,Buildings,Completed,NK-KODAMBAKKAM,136,455000,"DISMANTLING OF THE EXISTING OLD HEALTH BUILDING AT SIVAGNANAM STREET IN DIVISION -136, UNIT-30,ZONE-10.",Own Sources,10,2018-19,2018-19 NK/2018-19/16953,Parks,Completed,NK-KODAMBAKKAM,136,824000,"ANNUAL MAINTENANCE WORKS TO THE JEEVA PARK AT G.N.CHETTY ROAD IN DIVISION-136,UNIT-30,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/17012,Parks,Completed,NK-KODAMBAKKAM,136,1640000,"ANNUAL MAINTENANCE WORKS TO THE NATESAN PARK AT VENKATNARAYANA ROAD IN DIVISION-136,UNIT-30,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/17013,Parks,Completed,NK-KODAMBAKKAM,136,1304000,"ANNUAL MAINTENANCE WORKS TO THE PANAGAL PARK AT BASHYAM ROAD IN DIVISION-136,UNIT-30,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3239,Buildings,Completed,NK-KODAMBAKKAM,136,605000,"IMPROVEMENT WORKS TO THE SIR PITTY THIYAGARAYA HALL AT G.N.CHETTY ROAD IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3249,Buildings,Completed,NK-KODAMBAKKAM,136,810000,"IMPROVEMENT WORKS TO THE UNIT OFFICE BUILDING AT USMAN ROAD IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3924,Roads,Completed,NK-KODAMBAKKAM,136,1424000,"RELAYING THE ROAD WITH BM 50MM THICK AND BC 40 MM THICK BY USING PAVER FINISHER AT MANGESH STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3925,Roads,Completed,NK-KODAMBAKKAM,136,3212000,"RELAYING THE ROAD WITH BM 50MM THICK AND BC 40 MM THICK BY USING PAVER FINISHER AT DHANDAPANI STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3927,Roads,Completed,NK-KODAMBAKKAM,136,2735000,"RELAYING THE ROAD WITH BM 50MM THICK AND BC 40 MM THICK BY USING PAVER FINISHER AT MADLEY ROAD IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3928,Roads,Completed,NK-KODAMBAKKAM,136,1670000,"RELAYING THE ROAD WITH BM 50MM THICK AND BC 40 MM THICK BY USING PAVER FINISHER AT SOUNDARAJAN STREET IN DIVISION - 136, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3931,Roads,Completed,NK-KODAMBAKKAM,136,3006000,"RELAYING THE ROAD WITH BM 50MM THICK AND BC 40 MM THICK BY USING PAVER FINISHER AT CIT NAGAR 4th MAIN ROAD IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3932,Roads,Completed,NK-KODAMBAKKAM,136,473000,"RELAYING THE ROAD WITH BM 50MM THICK AND BC 40 MM THICK BY USING PAVER FINISHER ATCIT NAGAR 3rd MAIN ROAD 1st EXT IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3935,Roads,Completed,NK-KODAMBAKKAM,136,2085000,"LAYING CEMENT CONCRETE ROAD AT LAKSHMIKANTHAN STREET IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3937,Roads,Completed,NK-KODAMBAKKAM,136,1404000,"LAYING CEMENT CONCRETE ROAD AT THUKKARAM 1st STREET IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3938,Roads,Completed,NK-KODAMBAKKAM,136,1404000,"LAYING CEMENT CONCRETE ROAD AT THUKKARAM 2nd STREET IN DIVISION - 136, UNIT -30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3939,Roads,Completed,NK-KODAMBAKKAM,136,1404000,"LAYING CEMENT CONCRETE ROAD AT THUKKARAM 3rd STREET IN DIVISION - 136, UNIT -30, ZONE - 10",Own Sources,10,2018-19,2019-20 NK/2018-19/4164,Buildings,Completed,NK-KODAMBAKKAM,136,526000,"DISMANTLING OF EXISTING DILAPIDATED CORPORATION ELECTRICAL STORE ROOM AND JUNIOR ENGINEER OFFICE AT THIYAGARAYA ROAD ( JN OF THANIKASALAM ROAD ) IN DIVISION - 136, UNIT - 30, ZONE -10.",Own Sources,10,2018-19,2019-20 NK/2018-19/4769,Buildings,Completed,NK-KODAMBAKKAM,136,116000,"Providing Private Labours for Sweeping and Toilet cleaning work (3 month) at Chennai Middle School at Prakasam Road in Division - 136, Unit - 30, Zone - X.",Own Sources,10,2018-19,2018-19 NK/2018-19/6425,Buildings,Completed,NK-KODAMBAKKAM,136,430000,"Providing Private Labours for Security, Sweeping and Toilet cleaning work (1 year) at Health Post ( Radhakrishna Street ) in Division - 136, Unit - 30, Zone - X.",Own Sources,10,2018-19,2020-21 NK/2018-19/9119,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,1094000,"DESILTING OF STORM WATER DRAIN AT NORTH USMAN ROAD, BUZULLAH ROAD AND VARIOUS STREETS IN DIV-136, U-30, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/9120,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,1141000,"MINOR REPAIRS WORK TO STORM WATER DRAIN AT G.N.CHETTY ROAD, DURAISAMY ROAD AND VARIOUS STREETS IN DIVISION-136, UNIT- 30, ZONE-10.",Own Sources,10,2018-19,2019-20 SP/2018-19/14761,Footpath,Completed,SP-SPECIAL PROJECTS,136,111000000,"REDEVELOPMENT IN GOPATHI NARAYANASAMY ROAD REACH 1 ( FROM BASHYAM ROAD TO NEW CRESCENT ROAD) IN DN . NO 117 ZONE -09 & DN NO. 136, ZONE -10.",SMART CITY - SPECIAL PROJECTS,10,2018-19,2020-21 SP/2018-19/14785,Roads,Completed,SP-SPECIAL PROJECTS,136,13800000,"IMPROVEMENTS TO THE EXISTING BITUMONOUS ROAD WITH CAMBER CORRECTION IN PEDESTRIAN PLAZA REACH - I AT THEYARAYA SALAI IN DIVISION - 136 ,ZONE -X",SMART CITY - SPECIAL PROJECTS,10,2018-19,2019-20 SP/2018-19/15124,Footpath,Completed,SP-SPECIAL PROJECTS,136,113000000,"REDEVELOPMENT IN VENKATNARAYANA ROAD ( FROM BASHYAM ROAD TO MOUNT ROAD) IN DN . NO 117 & 122, ZONE -09 & DN NO. 136, ZONE -10.",SMART CITY - SPECIAL PROJECTS,10,2018-19,2020-21 SP/2018-19/7497,Buildings,Completed,SP-SPECIAL PROJECTS,136,41986600,Shoring and dewatering for Construction of Multi level car parking at Junction of Thiyagaraya Road and Thanikachalam Road Pondy bazaar in Dn-136. Zone-10,SMART CITY - SPECIAL PROJECTS,10,2018-19,2019-20 BR/2018-19/8017,Road Cut,Completed,BR-Bus Route Roads,137,1800000,"Restoration of roadcut made by TANTRANSCO at Pillaiyar Koil Street(from the jn of Thiruvalluvar salai to the jn of Erikarai street) in Dn 137, Zone - 10 (chellan no: BR/2018-19/0009648)",Deposit Works,10,2018-19,2018-19 BR/2018-19/8018,Road Cut,Completed,BR-Bus Route Roads,137,2400000,"Restoration of roadcut made by TANTRANSCO at Erikarai Street(from the jn of Pillaiyar kiol street to the jn of Burial ground) in Dn 137, Zone - 10 (chellan no: BR/2018-19/0002452)",Deposit Works,10,2018-19,2018-19 BR/2018-19/8019,Road Cut,Completed,BR-Bus Route Roads,137,2050000,"Restoration of roadcut made by TANTRANSCO at Erikarai Street(from the jn of burial ground to the jn of Kamaraj salai) in Dn 137, Zone - 10 (chellan no: BR/2018-19/0002452)",Deposit Works,10,2018-19,2018-19 BR/2018-19/8825,Road Cut,Completed,BR-Bus Route Roads,137,2480000,"Restoration of road cut Made by TANTRANSCO at Anna main Road from the jn of Munusamy Salai to the jn of Ponmana Chemmal Street in Dn - 137, Zone -10 (Chellan No BR/18-19/0009648)",Deposit Works,10,2018-19,2019-20 BR/2018-19/9004,Road Cut,Completed,BR-Bus Route Roads,137,2495000,"Restoration of roadcut made by TANTRANSCO at Munusamy Salai in Dn - 137, Zone -10",Deposit Works,10,2018-19,2019-20 BR/2018-19/9007,Road Cut,Completed,BR-Bus Route Roads,137,2470000,"Restoration of roadcut made by TANTRANSCO at Anna Main Road from the jn of Ponmana Chemmal street to the jn of MGR road in dn -137, Zone -10",Deposit Works,10,2018-19,2019-20 BR/2018-19/9014,Road Cut,Completed,BR-Bus Route Roads,137,1240000,"Restoration of roadcut made by TANTRANSCO at Anna Main Road from the jn of MGR road to the jn of TNEB office in dn -137, Zone -10",Deposit Works,10,2018-19,2019-20 D/2018-19/14938,Storm Water Drain,Completed,D-Storm Water Drains,137,27291000,"Demolition and Re-Construction of Storm Water Drain of size 1200 x 1000 mm at Rajamannar Salai(right) on west side from thisathya matriculation school to metro shop in Dn. - 137,Zone - 10, Package - 16.",SMART CITY - SWD,10,2018-19,2020-21 L/2018-19/8610,Electrical,Completed,L-Electrical,137,4216500,Provision of 139 nos of 7 mtr lamp post at Khanu nagar and Removel of damage solr old post in Division 137 in Zone-10,Own Sources,10,2018-19,2020-21 NK/2018-19/11493,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,1240000,"Dismantling and Reconstruction of SWD at Rajamannar Salai in division-137, Unit-28, Zone-10",Own Sources,10,2018-19,2018-19 NK/2018-19/15955,Parks,Completed,NK-KODAMBAKKAM,137,896000,"Maintenance of Park at 11th Sector , K.K Nagar in Div-137, U-28, Z-10 (per year).",Own Sources,10,2018-19,2019-20 NK/2018-19/16031,Parks,Completed,NK-KODAMBAKKAM,137,300000,"Maintenance of Park at 12h Sector , K.K Nagar in Div-137, U-28, Z-10 (per year).",Own Sources,10,2018-19,2019-20 NK/2018-19/16044,Parks,Completed,NK-KODAMBAKKAM,137,935000,"Maintenance of Park at Erikkarai Street in Div-137, U-28, Z-10 (per year).",Own Sources,10,2018-19,2019-20 NK/2018-19/16693,Buildings,Completed,NK-KODAMBAKKAM,137,172000,"Maintenance Estimate for Park Cum Play Ground at Erikkarai Street, Nesapakkam in Dn-137, Zone-10, ( from 1st Apr 2019 to 31st Aug 2019 )",Own Sources,10,2018-19,2019-20 NK/2018-19/1715,Roads,Completed,NK-KODAMBAKKAM,137,456000,"Relaying of BT Road at Kataboman Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/1875,Roads,Completed,NK-KODAMBAKKAM,137,832000,"Relaying of BT Road at 9th Sector 51st Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2204,Roads,Completed,NK-KODAMBAKKAM,137,2751000,"Relaying of BT Road at Ponnambalam Salai in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2209,Roads,Completed,NK-KODAMBAKKAM,137,3161000,"Relaying of BT Road at Alagirisamy Salai in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2211,Roads,Completed,NK-KODAMBAKKAM,137,475000,"Relaying of BT Road at Ponnamal Nagar Main Road in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2213,Roads,Completed,NK-KODAMBAKKAM,137,139000,"Relaying of BT Road at Ponnamal Nagar 1st Cross Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2219,Roads,Completed,NK-KODAMBAKKAM,137,81000,"Relaying of BT Road at Ponnamal Nagar 2nd Cross Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2230,Roads,Completed,NK-KODAMBAKKAM,137,1164000,"Relaying of BT Road at Sivagnammal Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2235,Roads,Completed,NK-KODAMBAKKAM,137,1411000,"Relaying of BT Road at Radhakrishnan Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2240,Roads,Completed,NK-KODAMBAKKAM,137,223000,"Relaying of BT Road at Kanagasabai Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2243,Roads,Completed,NK-KODAMBAKKAM,137,2773000,"Relaying of BT Road at Venkatraman Salai in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2246,Roads,Completed,NK-KODAMBAKKAM,137,1432000,"Relaying of Cement Concrete Road at Bharathiyar 2nd Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2250,Roads,Completed,NK-KODAMBAKKAM,137,191000,"Relaying of Cement Concrete Road at Veerapandian Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2252,Roads,Completed,NK-KODAMBAKKAM,137,261000,"Relaying of Cement Concrete Road at Agasthiyar Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2254,Roads,Completed,NK-KODAMBAKKAM,137,572000,"Relaying of Cement Concrete Road at Ayyavupuram Main Road in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2256,Roads,Completed,NK-KODAMBAKKAM,137,451000,"Relaying of Cement Concrete Road at Kanagasabai Cross Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2020-21 NK/2018-19/2258,Roads,Completed,NK-KODAMBAKKAM,137,511000,"Relaying of Cement Concrete Road at Vikramathithan Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/2315,Roads,Completed,NK-KODAMBAKKAM,137,1136000,"Relaying of BT Road at 21st street - 5th sector in Div-137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/3320,Roads,Completed,NK-KODAMBAKKAM,137,93000,"Relaying of Cement Concrete Road at Rajiv Gandhi Cross Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/3322,Roads,Completed,NK-KODAMBAKKAM,137,249000,"Relaying of Cement Concrete Road at Jayalalitha Street in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/3324,Roads,Completed,NK-KODAMBAKKAM,137,739000,"Relaying of Cement Concrete Road at 56th Street - 10th Sector in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/3325,Roads,Completed,NK-KODAMBAKKAM,137,488000,"Relaying of Cement Concrete Road at 57th Street - 10th Sector in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/3326,Roads,Completed,NK-KODAMBAKKAM,137,488000,"Relaying of Cement Concrete Road at 58th Street - 10th Sector in Division -137, U-28, Z-10.",Grants,10,2018-19,2019-20 NK/2018-19/3449,Buildings,Completed,NK-KODAMBAKKAM,137,117900,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School and Annexure building near play ground at Erikkarai Street (3 Months) in Division - 137, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/3450,Buildings,Completed,NK-KODAMBAKKAM,137,147500,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Kamaraj Street and Annexure building at Sankaralinganar Steet (3 Months) in Division - 137, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/3458,Buildings,Completed,NK-KODAMBAKKAM,137,888000,"Operation and Maintenance of LPG Crematorium at Erikkarai Street, Nesapakkam in Division -137, Unit-28, Zone-10 (For 10 months Only)",Own Sources,10,2018-19,2019-20 NK/2018-19/3459,Buildings,Completed,NK-KODAMBAKKAM,137,506000,"OUTSOURCING OF PRIVATE LABOUR FOR THE MAINTENANCE OF BURIAL GROUND AT ERIKARAI STREET, NESAPAKKAM IN DN137, UNIT-28, ZONE-10 ( FOR 10 MONTHS ONLY)",Own Sources,10,2018-19,2019-20 NK/2018-19/3462,Roads,Completed,NK-KODAMBAKKAM,137,526000,"Relaying of BT Road at TK Pani 3rd Street in Div - 137, U -28, Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/7725,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,711000,"Desilting of SWD at Rajamannar Salai and various streets in Div-137, U-28, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/7732,Buildings,Completed,NK-KODAMBAKKAM,137,623700,"Repairs to SWD at Rajamannar salai and various streets in division-137, U-28, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/7808,Buildings,Completed,NK-KODAMBAKKAM,137,796000,"Construction of Yoga shed inside 4th Sector Park (MLA Fund) in Div- 137, U-28, Z-10",MLACDS,10,2018-19,2019-20 NK/2018-19/8956,Buildings,Completed,NK-KODAMBAKKAM,137,334000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School and Annexure building near play ground at Erikkarai Street (7 Months) in Division - 137, Unit - 28, Zone - X (from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/8958,Buildings,Completed,NK-KODAMBAKKAM,137,334000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Kamaraj Street and Annexure building at Sankaralinganar Steet (7 Months) in Division - 137, Unit - 28, Zone - X (from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9686,Buildings,Completed,NK-KODAMBAKKAM,137,1144000,"Repair works to Amma Unavagam at 61st Street - 10th Sector in division-137, Unit-28, Zone-10",Own Sources,10,2018-19,2019-20 D/2018-19/9427,Storm Water Drain,Completed,D-Storm Water Drains,138,26219000,Construction of Storm Water Drain at Ashoka Avenue on East Side and 4 Other Roads Zone - 10 - Package - 44,Grants,10,2018-19,2020-21 L/2018-19/5389,Electrical,Completed,L-Electrical,138,125000,"ADDITIONAL SCHOOL ESTIMATE DIV-130,138,140,142 IN ZONE-10.",Own Sources,10,2018-19,2019-20 L/2018-19/5772,Electrical,Completed,L-Electrical,138,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at DIVISION OFFICE , 1,AYYAVOO STREEET , JAFFERKHANPET in Div 138, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5779,Electrical,Completed,L-Electrical,138,311900,"Supply, Installation, Testing & Commissioning of 4Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS GOVINDASAMY STREET in Div 138, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5781,Electrical,Completed,L-Electrical,138,462400,"Supply, Installation, Testing & Commissioning of 6Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHSS GOVINDASAMY STREET in Div 138, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5787,Electrical,Completed,L-Electrical,138,462400,"Supply, Installation, Testing & Commissioning of 6Kwp Grid Tied Solar Rooftop including Civil works and earthing at AYYAVOO STREET 4TH STREET in Div 138, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/1039,Roads,Completed,NK-KODAMBAKKAM,138,5165500,"RELAYING THE BITUMINOUS CONCRETE ROAD AT PACHAIYAPPAN STREET IN DIVISION-138,UNIT-28,ZONE-10",Loans And Grants,10,2018-19,2020-21 NK/2018-19/1040,Roads,Completed,NK-KODAMBAKKAM,138,2180000,"RELAYING THE BITUMINOUS CONCRETE ROAD AT PUGAZHENTHI STREET IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2018-19,2020-21 NK/2018-19/1365,Roads,Completed,NK-KODAMBAKKAM,138,718420,"RELAYING THE BITUMINOUS CONCRETE ROAD AT PARI NAGAR,KARIKALAN STREET IN DIVISION-138,UNIT-28,ZONE-10",Own Sources,10,2018-19,2020-21 NK/2018-19/1377,Roads,Completed,NK-KODAMBAKKAM,138,914170,"RELAYING THE BITUMINOUS CONCRETE ROAD AT PARI NAGAR,GANDHI STREET IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/16032,Parks,Completed,NK-KODAMBAKKAM,138,221610,"ANNUAL MAINTENANCE AT BHARATHIDASAN COLONY 5TH STREET PARK IN DIV-138,U-28,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/16033,Parks,Completed,NK-KODAMBAKKAM,138,660820,"ANNUAL MAINTENANCE AT BHARATHIDASAN COLONY 6TH STREET PARK IN DIV-138,U-28,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1641,Buildings,Completed,NK-KODAMBAKKAM,138,146000,"PROVIDING AND FIXING FENCING AT KASI BRIDGE SERVICE ROAD ( ADJACENT TO ADAYAR RIVER) AT DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3435,Buildings,Completed,NK-KODAMBAKKAM,138,88400,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Govindaswamy Street (3 Months) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/3437,Buildings,Completed,NK-KODAMBAKKAM,138,117900,"Providing Private Labourers for Sweeping and Toilet cleaning work at Govt. Higher secondary School at Anna main road MGR Nagar (3 Months) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/3439,Buildings,Completed,NK-KODAMBAKKAM,138,117900,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher secondary School at Govindasamy Street,MGR Nagar (3 Months) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/4206,Buildings,Completed,NK-KODAMBAKKAM,138,216000,"Providing Private Labourers for Scavenger in Public Convenience at Dr.Ambedhkar Colony, Jafferkanpet (11 Months) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2018-19,2019-20 NK/2018-19/5809,Buildings,Completed,NK-KODAMBAKKAM,138,44900,"Providing Private Labourers for Watch man at Govt. Higher Secondary School at Anna main road MGR Nagar (2 Months) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/7305,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,262000,"DESILTING OF STORM WATER DRAIN AT ASHOK PILLAR SALAI, ANNA MAIN ROAD AND VARIOUS STREET IN DIV-138,U-28,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/7728,Buildings,Completed,NK-KODAMBAKKAM,138,326000,"Minor Repair works to SWD at Govindasamy street and various streets in Div-138, U-28, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8952,Buildings,Completed,NK-KODAMBAKKAM,138,200400,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Govindaswamy Street (7 Months) in Division - 138, Unit - 28, Zone - X (from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/8953,Buildings,Completed,NK-KODAMBAKKAM,138,419200,"Providing Private Labourers for Sweeping and Toilet cleaning work at Govt. Higher Secondary School at Anna main road, MGR Nagar (7 Months) in Division - 138, Unit - 28, Zone - X (from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/8955,Buildings,Completed,NK-KODAMBAKKAM,138,267200,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at Govindasamy street, MGR Nagar (7 Months) in Division - 138, Unit - 28, Zone - X (from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 B/2018-19/3757,Buildings,Completed,B-Buildings,139,8667229,"PROPOSED CONSTRUCTION OF 4 CLASS ROOMS WITH TOILET AND STAIRCASE FOR GROUND FLOOR IN CHENNAI PRIMARY SCHOOL AT JAFFERKHANPET IN DN-139,ZONE-10.",MPLADS,10,2018-19,2020-21 L/2018-19/5824,Electrical,Completed,L-Electrical,139,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at A Block, Kodambakkam Road in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/6452,Electrical,Completed,L-Electrical,139,2704900,"Electrification of Chennai Primary School, Chennai Middle School ,Chennai High School, Chennai Higher Secondary School at Various Places in Div 127,128,130,132,133,134,135,136,137,139,141 Zone - X",Own Sources,10,2018-19,2019-20 NK/2018-19/10574,Buildings,Completed,NK-KODAMBAKKAM,139,199000,"Dismantling of the Existing Health Building at Periyar Ramaswamy Street in Division 139, Unit-28, Zone 10",Own Sources,10,2018-19,2019-20 NK/2018-19/10886,Buildings,Completed,NK-KODAMBAKKAM,139,349700,"Annual Maintenance of Bio Gas Plant for Amma Unavagam at Gangaiamman Kovil Street in Division - 139, Unit - 28, Zone - X",Own Sources,10,2018-19,2020-21 NK/2018-19/10905,Buildings,Completed,NK-KODAMBAKKAM,139,518000,"Operation and Maintenance For 3rd Year Operation of High Quality Treated Drinking Water Plant (RO/UV Filtration) For 1 Year Period (Amma Kudineer) at RR Colony Third Street, RRcolony, in Dn-139, Unit-28, Zone-10",Own Sources,10,2018-19,2018-19 NK/2018-19/16128,Buildings,Completed,NK-KODAMBAKKAM,139,228200,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT PUBLIC CONVENIENCE, VOC BLOCK, JAFERKANPET IN DIV-139, U-28, Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/3441,Buildings,Completed,NK-KODAMBAKKAM,139,117800,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai High School at Jafferkanpet (3 Months) in Division - 139, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/3443,Buildings,Completed,NK-KODAMBAKKAM,139,58950,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Jafferkanpet (3 Months) in Division - 139, Unit - 28, Zone - X",Own Sources,10,2018-19,2019-20 NK/2018-19/3444,Buildings,Completed,NK-KODAMBAKKAM,139,58950,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School Street (3 Months) in Division - 139, Unit - 28, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/3919,Roads,Completed,NK-KODAMBAKKAM,139,4790000,"RELAYING THE BITUMINIOUS CONCRETE ROAD AT GANGAIAMMAN KOVIL STREET IN DIVISION-139, UNIT-28, ZONE -10",Loans And Grants,10,2018-19,2019-20 NK/2018-19/3934,Roads,Completed,NK-KODAMBAKKAM,139,672000,"RELAYING THE BITUMINIOUS CONCRETE ROAD AT MN MURUGESAN STREET IN DIVISION-139, UNIT-28, ZONE -10",Loans And Grants,10,2018-19,2019-20 NK/2018-19/3940,Roads,Completed,NK-KODAMBAKKAM,139,1385000,"RELAYING THE BITUMINIOUS CONCRETE ROAD AT SANGUTHALA STREET IN DIVISION-139, UNIT-28, ZONE -10",Loans And Grants,10,2018-19,2019-20 NK/2018-19/3953,Roads,Completed,NK-KODAMBAKKAM,139,482000,"RELAYING THE BITUMINIOUS CONCRETE ROAD AT THIRU-VI-KA STREET IN DIVISION-139, UNIT-28, ZONE -10",Loans And Grants,10,2018-19,2019-20 NK/2018-19/3955,Roads,Completed,NK-KODAMBAKKAM,139,931000,"RELAYING THE BITUMINIOUS CONCRETE ROAD AT V.O.C.STREET AND JAYARAMAN STREET IN DIVISION-139, UNIT-28, ZONE -10",Loans And Grants,10,2018-19,2019-20 NK/2018-19/3957,Roads,Completed,NK-KODAMBAKKAM,139,4950000,"RELAYING OF CEMENT CONCRETE AT RV NAGAR 69TH STREET IN DN139, UNIT-28, ZONE -X",Loans And Grants,10,2018-19,2020-21 NK/2018-19/3958,Roads,Completed,NK-KODAMBAKKAM,139,1508000,"RELAYING OF CEMENT CONCRETE AT RV NAGAR 69A STREET IN DN139, UNIT-28, ZONE -X",Loans And Grants,10,2018-19,2020-21 NK/2018-19/3960,Roads,Completed,NK-KODAMBAKKAM,139,1336000,"RELAYING OF CEMENT CONCRETE ROAD AT RV NAGAR 73RD STREET IN DIVISION 139, UNIT-28, ZONE-X",Loans And Grants,10,2018-19,2020-21 NK/2018-19/7739,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,674000,"REPAIRS OF STORM WATER DRAIN AND REPLACEMENT OF DAMAGED MANHOLE COVER AT APPADURAI STREET AND VARIOUS STREET IN DIV139, UNIT-28, ZONE - X",Own Sources,10,2018-19,2019-20 NK/2018-19/7826,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,352000,"DE-SILTING OF STORM WATER DRAIN AT RR COLONY, VENUGOPAL STREET AND VARIOUS STREET IN DIVISION 139, UNIT-28, ZONE 10",Own Sources,10,2018-19,2019-20 NK/2018-19/8948,Buildings,Completed,NK-KODAMBAKKAM,139,267200,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai High School at Jafferkanpet (7 Months) in Division - 139, Unit - 28, Zone - X (from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/8950,Buildings,Completed,NK-KODAMBAKKAM,139,133600,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Jafferkanpet (7 Months) in Division - 139, Unit - 28, Zone - X(from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/8951,Buildings,Completed,NK-KODAMBAKKAM,139,133600,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School Street (7 Months) in Division - 139, Unit - 28, Zone - X (from 10.10.2018 to 30.04.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/8959,Buildings,Completed,NK-KODAMBAKKAM,139,644100,"OPERATION AND MAINTENANCE OF LPG CREMATORIUM AT WEST JONES ROAD IN DIVISION -139,UNIT - 28, ZONE- 10 (FOR 6 MONTHS ONLY) (24.09.2018 to 31.03.2019)",Own Sources,10,2018-19,2019-20 NK/2018-19/9366,Buildings,Completed,NK-KODAMBAKKAM,139,218000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT WEST SAIDAPET BURIAL GROUND IN DIV-139, U-28, Z-10",Own Sources,10,2018-19,2018-19 BR/2018-19/15080,Roads,Completed,BR-Bus Route Roads,140,104000,RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS - 140 UNIT - 30 ZONE-10,Deposit Works,10,2018-19,2019-20 BR/2018-19/15850,Road Cut,Completed,BR-Bus Route Roads,140,381000,RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS - 141 UNIT - 30 ZONE-10,Deposit Works,10,2018-19,2019-20 BR/2018-19/6557,Footpath,Completed,BR-Bus Route Roads,140,8852000,"Forming Footpath at Govindan Road in Dn-140, Zone - X",Grants,10,2018-19,2019-20 L/2018-19/0847,Electrical,Completed,L-Electrical,140,2676800,"Electrification of Chennai Boys Hr. Sec. School,CMS,Mettupalayam,CMS, New Street,CHSS, K.R.Koil street ,Chennai Girls Her Sec School, Jones Road ,CMS, Jones Road,CPS,Jones Roa,CUG, Primery School, Bazzar Road,CMS, Gothamedu,Division,140, 142, Zone- X.",Own Sources,10,2018-19,2019-20 L/2018-19/0854,Electrical,Completed,L-Electrical,140,614000,"Supply Erection 14 nos of 6mtr lamp post with 40w LED Fitting at Pushpavathiamman Koil Lane, Din-140,-X .",Own Sources,10,2018-19,2018-19 L/2018-19/5811,Electrical,Completed,L-Electrical,140,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at D Block, West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5821,Electrical,Completed,L-Electrical,140,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at A Block K.R.Koil st in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5828,Electrical,Completed,L-Electrical,140,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at A Block, West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5831,Electrical,Completed,L-Electrical,140,537700,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Auditorium Kodambakkam Road in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5833,Electrical,Completed,L-Electrical,140,161500,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Multi Purpose Hall Palmore St in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5834,Electrical,Completed,L-Electrical,140,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at B Block, Kodambakkam Road in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5835,Electrical,Completed,L-Electrical,140,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Main Block, Kodambakkam Road in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5837,Electrical,Completed,L-Electrical,140,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Lab K.R.Koil Street in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5838,Electrical,Completed,L-Electrical,140,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at B. Block, K.R.Koil Street in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5840,Electrical,Completed,L-Electrical,140,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kitchen Shed, Kodambakkam Road in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5841,Electrical,Completed,L-Electrical,140,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at K.R.Koil st in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5843,Electrical,Completed,L-Electrical,140,161500,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C Block Kodambakkam Road in Div 140,Zone-10.",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5846,Electrical,Completed,L-Electrical,140,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Health Post Govindan St in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5848,Electrical,Completed,L-Electrical,140,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at H Block, West Jones Road in Div 142. Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5854,Electrical,Completed,L-Electrical,140,537700,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS New Street in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5856,Electrical,Completed,L-Electrical,140,537700,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Perumal Koil St in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5857,Electrical,Completed,L-Electrical,140,537700,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS Perumal Koil St in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/11514,Buildings,Completed,NK-KODAMBAKKAM,140,400000,"REPAIR AND IMPROVEMENTS WORKS FOR AMMA UNAVAGAM AT REDDYKUPPAM SALAI AND KODAMBAKKAM ROAD IN DIV-140, U-30, Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/12624,Buildings,Completed,NK-KODAMBAKKAM,140,518000,"Operation and Maintenance For 3rd Year Operation of High Quality Treated Drinking Water Plant (RO/UV Filtration) For 1 Year Period (Amma Kudineer) at Kodambakkam Road, in Dn-140, Unit-30, Zone-10",Own Sources,10,2018-19,2018-19 NK/2018-19/14121,Buildings,Completed,NK-KODAMBAKKAM,140,560000,"IMPROVEMENT WORK IN ANGANWADI (CENTRE NO.33603100109 and 33603100110.) AT NEW STREET IN DIVISION-140, UNIT-30, ZONE-10",Own Sources,10,2018-19,2019-20 NK/2018-19/16037,Parks,Completed,NK-KODAMBAKKAM,140,195400,"ANNUAL MAINTENANCE WORK AT ELLAIAMMAN KOVIL STREET IN DN 140, UNIT-30, ZONE 10",Own Sources,10,2018-19,2019-20 NK/2018-19/16040,Parks,Completed,NK-KODAMBAKKAM,140,667500,"ANNUAL MAINTENANCE WORK AT AMMA PARK , KODAMBAKKAM ROAD IN DN 140, UNIT-28, ZONE -10",Own Sources,10,2018-19,2019-20 NK/2018-19/1690,Roads,Completed,NK-KODAMBAKKAM,140,377000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT LAKE VIEW ROAD EXTN IN DIV-140 U-30,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1692,Roads,Completed,NK-KODAMBAKKAM,140,799000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT KRISHNAPPA STREET IN DIV-140 U-30,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1696,Roads,Completed,NK-KODAMBAKKAM,140,413000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT SRINIVASA IYENGAR 2ND STREET IN DIV-140 U-30,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1699,Roads,Completed,NK-KODAMBAKKAM,140,425000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT THIRUVEETHIAMMAN KOIL STREET IN DIV-140 U-30,Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/1701,Roads,Completed,NK-KODAMBAKKAM,140,557000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT PADAVETTAMMAN KOIL MAIN STREET IN DIV-140 U-30,Z-10.",Own Sources,10,2018-19,2020-21 NK/2018-19/1703,Roads,Completed,NK-KODAMBAKKAM,140,903000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT PALMORE STREET IN DIV-140 U-30,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1706,Roads,Completed,NK-KODAMBAKKAM,140,471000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT NAGATHAMMAN KOIL STREET IN DIV-140 U-30,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1710,Roads,Completed,NK-KODAMBAKKAM,140,667000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT SCHOOL ROAD IN DIV-140 U-30,Z-10",Own Sources,10,2018-19,2019-20 NK/2018-19/1711,Roads,Completed,NK-KODAMBAKKAM,140,662000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK BY PAVER FINISHER AT NAGARATHINAMMAL COLONY IN DIV-140 U-30,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/1712,Roads,Completed,NK-KODAMBAKKAM,140,1015000,"IMPROVEMENTS TO THE ROAD AT OLD MAMBALAM ROAD IN DIV-140 ,U-30,Z-10",Own Sources,10,2018-19,2020-21 NK/2018-19/4823,Buildings,Completed,NK-KODAMBAKKAM,140,147000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Boy's Higher Secondary School at Kodambakkam Road (3 Months) in Division - 140, Unit - 30, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/4824,Buildings,Completed,NK-KODAMBAKKAM,140,117900,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Perumal Kovil Street (3 Months) in Division - 140 Unit - 30, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/4825,Buildings,Completed,NK-KODAMBAKKAM,140,59000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Vandikaran Street (3 Months) in Division - 140, Unit - 30, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/4826,Buildings,Completed,NK-KODAMBAKKAM,140,88500,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at KR Koil Street (3 Months) in Division - 140, Unit - 30, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/6451,Buildings,Completed,NK-KODAMBAKKAM,140,560000,"Providing Security Arrangements and Engaging private labourers for UPHC at Govindan Road (12 Months) in Division - 140, Unit - 30, Zone - X",Own Sources,10,2018-19,2019-20 NK/2018-19/8994,Buildings,Completed,NK-KODAMBAKKAM,140,420000,"DESILTING OF STORM WATER DRAIN AT KODAMBAKKAM ROAD, REDDYKUPPAM SALAI AND VARIOUS STREETS IN DIVISION- 140, UNIT -30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8998,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,277000,"MINOR REPAIRS WORK TO STORM WATER DRAIN AT KODAMBAKKAM ROAD AND VARIOUS STREETS IN DIV-140, UNIT-30,ZONE -10.",Own Sources,10,2018-19,2019-20 NK/2018-19/9554,Buildings,Completed,NK-KODAMBAKKAM,140,267000,"PROVIDING PRIVATE LABOURS SWEEPING AND TOILET CLEANING WORK AT CHENNAI BOYS HIGER SECONDARY SCHOOL AT KODAMBAKKAM ROAD IN DIV-140,U-30,Z-10",Own Sources,10,2018-19,2020-21 NK/2018-19/9555,Buildings,Completed,NK-KODAMBAKKAM,140,200000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher secondary School at K.R.Koil Street (7 Months) in Division - 140, Unit - 30, Zone - X. (From 10.10.2018 to 30.04.2018)",Own Sources,10,2018-19,2020-21 NK/2018-19/9556,Buildings,Completed,NK-KODAMBAKKAM,140,200000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Perumal Koil Street (7 Months) in Division - 140, Unit - 30, Zone - X.",Own Sources,10,2018-19,2020-21 NK/2018-19/9557,Buildings,Completed,NK-KODAMBAKKAM,140,133000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Vandikaran Street (7 Months) in Division - 140, Unit - 30, Zone ? X",Own Sources,10,2018-19,2020-21 L/2018-19/5794,Electrical,Completed,L-Electrical,141,161500,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Multi Complex, C.I.T.Nagar 3rd Main Road in Div 141, Zone-10",Own Sources,10,2018-19,2019-20 L/2018-19/5798,Electrical,Completed,L-Electrical,141,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at HEALTH BUILDING C.I.T Nagar 4th Main Road in Div 141, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5805,Electrical,Completed,L-Electrical,141,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at I Block, C.I.T Nagar 4th Main Road in Div 141, Zone-10",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5807,Electrical,Completed,L-Electrical,141,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at I Block, New Boag Road in Div 141, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5812,Electrical,Completed,L-Electrical,141,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at II Block, C.I.T Nagar 4th Main Road in Div 141, Zone-10",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5815,Electrical,Completed,L-Electrical,141,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at II Block, New Boag Road in Div 141, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5816,Electrical,Completed,L-Electrical,141,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MIDDLE SCHOOL C.I.T Nagar 4th Main Road in Div 141, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5818,Electrical,Completed,L-Electrical,141,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Boag Road in Div 141, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/10892,Buildings,Completed,NK-KODAMBAKKAM,141,200000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai High School and Chennai Primary School at New Boag Road (Kannamapet) (7 months ) in Div -141, U-30, Z-10. (From 10.10.2018 to 30.04.2019).",Own Sources,10,2018-19,2019-20 NK/2018-19/10893,Buildings,Completed,NK-KODAMBAKKAM,141,334000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai Higher Secondary School and Chennai Primary School at C.I.T Nagar 4th Main Road (Kannamapet) (7 months ) in Div -141, U-30, Z-10. (From 10.10.2018 to 30.04.2019).",Own Sources,10,2018-19,2019-20 NK/2018-19/11545,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,1016000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) MUTHURANGANSALAI,KANNAMMAPETTAI(FOR 12 MONTHS),DIV-141,U-30,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/11709,Buildings,Completed,NK-KODAMBAKKAM,141,1082000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 1600 LITERS / HOUR CAPACITY FOR 3 RD YEAR PERIOD (AMMA KUDINEER) CIT NAGART 4TH MAIN ROAD ,DIV-141,U-30,Z-10",Own Sources,10,2018-19,2018-19 NK/2018-19/16025,Buildings,Completed,NK-KODAMBAKKAM,141,413000,"REPAIR AND MAINTENANCE OF CIVIL WORKS IN BIO GAS PLANT IN CIT NAGAR 4TH CROSS ROAD AT IN DIVISION - 141, UNIT -30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/17015,Parks,Completed,NK-KODAMBAKKAM,141,922000,"ANNUAL MAINTENANCE WORKS TO THE CIT NAGAR PARK AT CIT NAGAR 3RD MAIN ROAD IN DIVISION-141,UNIT-30,ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/3933,Roads,Completed,NK-KODAMBAKKAM,141,1451000,"RELAYING THE ROAD WITH BM 50MM THICK AND BC 40 MM THICK BY USING PAVER FINISHER AT DHAMODARAN STREET IN DIVISION - 141, UNIT - 30, ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/4770,Buildings,Completed,NK-KODAMBAKKAM,141,116000,"Providing Private Labours for Sweeping and Toilet cleaning work ( 3month) at Chennai high.sec. School and Chennai Primary School at CIT Nagar 4th Main Road in Division - 141, Unit - 30, Zone - X.",Own Sources,10,2018-19,2019-20 NK/2018-19/4773,Buildings,Completed,NK-KODAMBAKKAM,141,116000,"Providing Private Labours for Sweeping and Toilet cleaning work ( 3 month) at Chennai high School and Chennai Primary School at New Boag Road ( Kannamapet) in Division - 141, Unit - 30, Zone - X.",Own Sources,10,2018-19,2019-20 NK/2018-19/6432,Buildings,Completed,NK-KODAMBAKKAM,141,560000,"Providing security arrangements and engaging private labours for UPHC at South Usman Road (12 months) in Division - 141, Unit - 30, Zone ? X.",Own Sources,10,2018-19,2020-21 NK/2018-19/6436,Buildings,Completed,NK-KODAMBAKKAM,141,423500,"Providing security arrangements and engaging private labours for UPHC at CIT Nagar 4th Main Road (12 months) in Division - 141, Unit - 30, Zone ? X.",Own Sources,10,2018-19,2020-21 NK/2018-19/9116,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,876000,"DESILTING OF STORM WATER DRAIN AT SOUTH DHANDAPANI STREET, C.I.T NAGAR 4TH MAIN ROAD AND VARIOUS STREETS IN DIV-141, U-30,Z-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/9117,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,241000,"MINOR REPAIRS WORK TO STORM WATER DRAIN AT C.I.T NAGAR 1ST LINK STREET AND VARIOUS STREETS IN DIV-141, U-30, Z-10.",Own Sources,10,2018-19,2019-20 SP/2018-19/8581,Buildings,Completed,SP-SPECIAL PROJECTS,141,21700000,Modifying and Construct the existing crematorium at Kannammapet with conversion existing electrical crematorium in to LPG based Crematorium unit -02 Nos in Division-141 Zone -10,SMART CITY - SPECIAL PROJECTS,10,2018-19,2020-21 BR/2018-19/15853,Road Cut,Completed,BR-Bus Route Roads,142,250000,RESTORATION OF OFC CUTS AT VARIOUS INTERIOR ROADS IN DIVISIONS - 142 UNIT - 30 ZONE-10,Deposit Works,10,2018-19,2019-20 BR/2018-19/6669,Roads,Completed,BR-Bus Route Roads,142,2634000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Jayaram Street in Dn-142, Zone - X",Grants,10,2018-19,2019-20 BR/2018-19/6670,Roads,Completed,BR-Bus Route Roads,142,2810000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Mosque Street in Dn-142, Zone - X",Grants,10,2018-19,2019-20 L/2018-19/0849,Electrical,Completed,L-Electrical,142,1384500,"Provision of 31 nos of 6mtr lamp post with 40w-90w LED Fitting at Narayanan Samy main road,Narayanan 1st,street,Narayanan 2nd street,division -142, in Zone-10.",Own Sources,10,2018-19,2018-19 L/2018-19/5825,Electrical,Completed,L-Electrical,142,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5827,Electrical,Completed,L-Electrical,142,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5829,Electrical,Completed,L-Electrical,142,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5830,Electrical,Completed,L-Electrical,142,537700,"Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Thideer Nagar in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5836,Electrical,Completed,L-Electrical,142,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at B Block, West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5842,Electrical,Completed,L-Electrical,142,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Bazaar Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5844,Electrical,Completed,L-Electrical,142,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ICDS, West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5847,Electrical,Completed,L-Electrical,142,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C Block, West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5849,Electrical,Completed,L-Electrical,142,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at G Block, West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5850,Electrical,Completed,L-Electrical,142,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at chennai Urdu Girls Bazaar Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5851,Electrical,Completed,L-Electrical,142,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS New St in Div 140, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5852,Electrical,Completed,L-Electrical,142,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at EOC Hospital,jennis road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 L/2018-19/5853,Electrical,Completed,L-Electrical,142,612900,"Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at E Block, West Jones Road in Div 142, Zone-10 .",SMART CITY - ELECTRICAL,10,2018-19,2019-20 NK/2018-19/11477,Buildings,Completed,NK-KODAMBAKKAM,142,686000,"REPAIR AND IMPROVEMENTS WORK FOR AMMA UNAVAGAM AT JEENIS ROAD IN DIV-142, UNIT-30, ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/4693,Buildings,Completed,NK-KODAMBAKKAM,142,117000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Girls Higher Secondary School at west Jones Road (3 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/4694,Buildings,Completed,NK-KODAMBAKKAM,142,88000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at west Jones Road (3 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2019-20 NK/2018-19/4695,Buildings,Completed,NK-KODAMBAKKAM,142,58000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Bazaar Road (3 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2019-20 NK/2018-19/4696,Buildings,Completed,NK-KODAMBAKKAM,142,88000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Thideer Nagar (11 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2018-19 NK/2018-19/8931,Buildings,Completed,NK-KODAMBAKKAM,142,267000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Girls Higher Secondary School at west Jones Road (7 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2020-21 NK/2018-19/8933,Buildings,Completed,NK-KODAMBAKKAM,142,200000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Thideer Nagar (7 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2020-21 NK/2018-19/8935,Buildings,Completed,NK-KODAMBAKKAM,142,133000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Bazaar Road (7 Months) in Division - 142, Unit - 30, Zone - X ( FROM 10-08-2018 TO 30-04-2019)",Own Sources,10,2018-19,2020-21 NK/2018-19/8936,Buildings,Completed,NK-KODAMBAKKAM,142,200000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at West Jones Road (7 Months) in Division - 142, Unit - 30, Zone - X. ( FROM 10.10.2014 TO 30-04-2019)",Own Sources,10,2018-19,2020-21 NK/2018-19/8973,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,467000,"DE-SILTING OF STORM WATER DRAIN AT WEST JONES ROAD, TANK SQUARE STREET AND VARIOUS STREETS IN DIVISION- 142 , UNIT- 30 , ZONE - 10.",Own Sources,10,2018-19,2019-20 NK/2018-19/8974,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,181000,"MINOR REPAIRS WORK OF STORM WATER DRAIN AT KOTHAVALCHAVADI STREET AND VARIOUS STREETS IN DIVISION-142, UNIT-30, ZONE-10.",Own Sources,10,2018-19,2019-20 NK/2018-19/9654,Buildings,Completed,NK-KODAMBAKKAM,142,846000,"Providing Security Arrangements and Engaging private labourers for Emergency Obstetric Care Center Hospital at Jennis Road, Saidapet (12 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2019-20 NK/2018-19/9655,Buildings,Completed,NK-KODAMBAKKAM,142,560000,"Providing Security Arrangements and Engaging private labourers for UPHC at West Jones Road, Saidapet (12 Months) in Division - 142, Unit - 30, Zone - X",Own Sources,10,2018-19,2019-20 BR/2018-19/17276,Road Cut,Completed,BR-Bus Route Roads,143,93200,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-143, Zone-XI",Deposit Works,11,2018-19,2019-20 BR/2018-19/5957,Road Cut,Completed,BR-Bus Route Roads,143,85000,RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VOC MAIN ROAD AND SOUTH MADA STREET IN DIV-143 &156 ZONE-11.(57/0510/2017-18) PACKAGE-11.,Deposit Works,11,2018-19,2019-20 BR/2018-19/5958,Road Cut,Completed,BR-Bus Route Roads,143,283000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DIV-143,145,150&155 ZONE-11.(57/0667/2017-18) PACKAGE-11.",Deposit Works,11,2018-19,2019-20 L/2018-19/5694,Electrical,Completed,L-Electrical,143,1641000,"Painting of 7458 Nos of street lamp post,259 Nos of Pillar Box and Numbering of 8527 nos of above lamp post at various location in Division 143 to 155 in Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/10945,Buildings,Completed,NL-VALASARAVAKKAM,143,420000,"Supplying Two Coloured Modern Designed Bins at Commercial Areas in Dn - 143 to 155, U - 32 to 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/11818,Parks,Completed,NL-VALASARAVAKKAM,143,650000,"Additional Improvement at Nolambur Phase-2,13th cross street park in Div-143,Unit-32,Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/13193,Parks,Completed,NL-VALASARAVAKKAM,143,131000,"Maintenance for Park at Nolambur Phase-I 13th Cross Street (area=1163) (7 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13195,Parks,Completed,NL-VALASARAVAKKAM,143,118000,"Maintenance for Park at Nolambur Phase-I 9th Main Road (New) (Area=1095 sqm) (7 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13196,Parks,Completed,NL-VALASARAVAKKAM,143,133000,"Maintenance for Park at Nolambur Channal Road (Area-1694 sqm) (7months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13197,Parks,Completed,NL-VALASARAVAKKAM,143,118000,"Maintenance for Park at Nolambur Phase-II, 7th Cross Street (Area=1650 sqm) (7 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13198,Parks,Completed,NL-VALASARAVAKKAM,143,116000,"Maintenance for Park at Nolambur Phase-I 7th Main Road( Area=978 sqm) (7months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13199,Parks,Completed,NL-VALASARAVAKKAM,143,527000,"Maintenance for Park at Nolambur Phase-I 3rd Main Road ( Area =4975 m2) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13360,Buildings,Completed,NL-VALASARAVAKKAM,143,364000,"Improvement to Division office at Sri Ram Nagar in Div-143, Un-32, Z-XI",Own Sources,11,2018-19,2020-21 NL/2018-19/13692,Parks,Completed,NL-VALASARAVAKKAM,143,204000,"Maintenance for Park at Nolambur Phase-1,9th main road (old) (area=1456 sqm) in Dn-143, U - 33, Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/13699,Parks,Completed,NL-VALASARAVAKKAM,143,138000,"Maintenance for Park at Nolambur Phase-II ,3rd Cross Street (7 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13960,Buildings,Completed,NL-VALASARAVAKKAM,143,1134000,"Construction of Compound Wall at Nolambur Phase-1,5th main Road (OSR LAND)in Div-143,un-32,z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/13962,Buildings,Completed,NL-VALASARAVAKKAM,143,844000,"Construction of Compound Wall at Tataiya Nagar OSR Land in Div-143,un-32,z-11",Own Sources,11,2018-19,2020-21 NL/2018-19/13986,Buildings,Completed,NL-VALASARAVAKKAM,143,138000,"Providing Electricity and Water Facility to the E-Toilet at Mogappair West Main Road in Div-143,Unit-32,Zone-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/14252,Roads,Completed,NL-VALASARAVAKKAM,143,110000,"Attenting Patch Work at Nolambur Phase-1, 21th cross street in Div-143,Unit-32,Zone-11",Own Sources,11,2018-19,2020-21 NL/2018-19/14258,Roads,Completed,NL-VALASARAVAKKAM,143,54000,"Repairs to street name board at various street in division - 143 , unit - 32 in Zone - XI",Own Sources,11,2018-19,2020-21 NL/2018-19/1490,Roads,Completed,NL-VALASARAVAKKAM,143,1114000,"Relaying the B.T. Road at Sakthi Nagar 4th Avenue in Dn.143, Unit-32, Zone-XI",Grants,11,2018-19,2019-20 NL/2018-19/1492,Roads,Completed,NL-VALASARAVAKKAM,143,423000,"Relaying the B.T. Road at Phase -2 3rd Main Road Extn in Dn.143, Unit-32, Zone-XI",Grants,11,2018-19,2019-20 NL/2018-19/1493,Roads,Completed,NL-VALASARAVAKKAM,143,356000,"Relaying the B.T. Road at V.G.N. Road in Dn.143, Unit-32, Zone-XI",Grants,11,2018-19,2019-20 NL/2018-19/15156,Parks,Completed,NL-VALASARAVAKKAM,143,257000,"Maintenance of corporation park at Nolambur Phase-2 ,13th cross street In Div-143,U-32,Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/15157,Parks,Completed,NL-VALASARAVAKKAM,143,212000,"Maintenance of corporation park at Nolambur MCK Layout Park In Div-143,U-32,Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/15599,Electrical,Completed,NL-VALASARAVAKKAM,143,1548000,"Replacement of Damaged Lamp post and Conversion of Fittings in Various parks in Division 143,144 & 146 in Zone-XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/16035,Buildings,Completed,NL-VALASARAVAKKAM,143,96000,"Demolition of old Anganwadi building and Tv Room at 4th block 4th street,5th Block Sivan Koil street and Madha Koil 2nd street in Div-143, Unit-32, Zone - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/1704,Roads,Completed,NL-VALASARAVAKKAM,143,142000,"Relaying the B.T. Road at V.G.N.Channel Road in Dn.143, Unit-32, Zone-XI",Grants,11,2018-19,2019-20 NL/2018-19/1705,Roads,Completed,NL-VALASARAVAKKAM,143,295000,"Relaying the B.T. Road at V.G.N. Phase-3 2nd Cross Street in Dn.143, Unit-32, Zone-XI",Grants,11,2018-19,2019-20 NL/2018-19/17508,Roads,Completed,NL-VALASARAVAKKAM,143,1541000,"Forming of Cement Concrete Road at Selvavinayagar Street in Dn-143, Unit-32, Zone-11.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/17509,Roads,Completed,NL-VALASARAVAKKAM,143,787000,"Forming of Cement Concrete Road at Selvavinayagar 1st Street in Dn-143, Unit-32, Zone-11.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/17510,Roads,Completed,NL-VALASARAVAKKAM,143,646000,"Forming of Cement Concrete Road at Selvavinayagar 2nd Street in Dn-143, Unit-32, Zone-11.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/17511,Roads,Completed,NL-VALASARAVAKKAM,143,625000,"Forming of Cement Concrete Road at Selvavinayagar 3rd Street in Dn-143, Unit-32, Zone-11.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/17512,Roads,Completed,NL-VALASARAVAKKAM,143,626000,"Forming of Cement Concrete Road at Selvavinayagar 4th Street in Dn-143, Unit-32, Zone-11.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/17513,Roads,Completed,NL-VALASARAVAKKAM,143,835000,"Forming of Cement Concrete Road at Selvavinayagar 5th Street in Dn-143, Unit-32, Zone-11.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1808,Roads,Completed,NL-VALASARAVAKKAM,143,257000,"Patch work at Various Street in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2018-19 NL/2018-19/2455,Parks,Completed,NL-VALASARAVAKKAM,143,289000,Supply and errection of 6 numbers of 6 mtr lamp post with 40w LED fitting at GCC park at phase 1 st Main road Nolambur div 143 zone11,Own Sources,11,2018-19,2019-20 NL/2018-19/2843,Roads,Completed,NL-VALASARAVAKKAM,143,1123000,"Relaying the B.T. Road at V.G.N. Gurusamy Salai in Dn.143, Unit-32, Zone-XI",Grants,11,2018-19,2019-20 NL/2018-19/2844,Roads,Completed,NL-VALASARAVAKKAM,143,3146000,"Relaying the B.T. Road at V.O.C main road in Dn.143, Unit-32, Zone-XI",Grants,11,2018-19,2019-20 NL/2018-19/3440/C,Parks,Completed,NL-VALASARAVAKKAM,143,455000,"THE PROPOSED SENIOR GYM LOCATION AT VGN NAGAR CHANNAL ROAD PART IN DN-143, UNIT-32 ,ZONE-11.",Own Sources,11,2018-19,2018-19 NL/2018-19/3809,Buildings,Completed,NL-VALASARAVAKKAM,143,1246000,"Construction of Compound Wall at Nolambur Union Road Burial Ground in Dn - 143, U - 32, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/4816,Parks,Completed,NL-VALASARAVAKKAM,143,570000,"PROPOSED OPEN GYM EQUIPMENT AND PEBBLE PATHWAY FOR PHASE-2, 3RD CROSS STREET AND PHASE-1, 3RD MAIN ROAD AT NOLAMBUR IN DN-143, UNIT-32 ,ZONE-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/6169,Roads,Completed,NL-VALASARAVAKKAM,143,64000,"Road Cut (made by CMWSSB) Restoration for Ramalingam street, Nolambur in DN-143, UNIT-32, ZONE-XI",Deposit Works,11,2018-19,2019-20 NL/2018-19/7823,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,553000,"Desilting of SWD and Side Drain at various streets in Div - 143, U-32, Z-XI",Own Sources,11,2018-19,2018-19 NL/2018-19/7835,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,59000,"Minor Repair to Storm Water Drain at Various Street in Dn.143, Unit-32, Zone-XI",Own Sources,11,2018-19,2018-19 NL/2018-19/8084,Roads,Completed,NL-VALASARAVAKKAM,143,613000,"Attending B.T. Patch work at Various Street in DN-143, UNIT-32, ZONE-11",Own Sources,11,2018-19,2019-20 NL/2018-19/8679,Buildings,Completed,NL-VALASARAVAKKAM,143,338000,Improvement & Construction of baby toilet for Anganwadi at 4th Block 15th St(Center No.7) in Division - 143 Unit - 32 Zone - XI,Own Sources,11,2018-19,2021-22 NL/2018-19/8680,Buildings,Completed,NL-VALASARAVAKKAM,143,298000,"Improvement & Construction of Baby Friendly Toilet to existing Anganwadi at Padasalai Street in Dn - 143, U - 32, Z - XI.",Own Sources,11,2018-19,2019-20 L/2018-19/13493,Electrical,Completed,L-Electrical,144,2865000,"Replacement of Damaged 4159 Meters of 2x16 Sq.mm Alu cable at 2236 Meters of 4x16 Sq.mm Alu cable Phase 1, VGN Nagar,7th Block,Metro nagar & varoius location in Maduravoyal, Nolambur Division 143,144 & 146 in Zone-XI as per list enclosed.",Own Sources,11,2018-19,2021-22 NL/2018-19/10888,Buildings,Completed,NL-VALASARAVAKKAM,144,130000,"IMPROVEMENT WORK AT AMMAUNAVAGAM METTUKUPPAM MAIN ROAD AND NAGATHAMMAN KOIL STREET MADURAVOYAL IN DIN-144,UNIT-32,ZONE-11",Own Sources,11,2018-19,2019-20 NL/2018-19/11965,Buildings,Completed,NL-VALASARAVAKKAM,144,272000,"Forming the Cement Concrete Road at Kannan Nagar Annex 2nd Cross Street in Div-144,Unit-32,Zone-11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/13204,Parks,Completed,NL-VALASARAVAKKAM,144,183000,"Maintenance for Park at VGP Amutha Nagar Nolambur in Dn.144, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/14695,Roads,Completed,NL-VALASARAVAKKAM,144,108000,"Repair to Street Name board at various streets in DN-144, Unit-32. Zone-XI",Own Sources,11,2018-19,2020-21 NL/2018-19/6074,Roads,Completed,NL-VALASARAVAKKAM,144,66000,"Repair to Street Name board at Various streets in Division-144, Unit-32, Zone-11.",Own Sources,11,2018-19,2020-21 NL/2018-19/6247,Buildings,Completed,NL-VALASARAVAKKAM,144,170000,"Improvements work in Anganwadi at MMDA Colony 6th Block 33rd Street and Sannathi Street, Maduravoyal in Dn.144, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/7820,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,1790000,"Relaying the BT Road At Mettukuppam Main Road in Div-144,Unit-32,Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/7838,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,435000,"Relaying the BT Road At MMDA Colony 7th Block Main Road in Div-144,Unit-32,Zone-11",Grants,11,2018-19,2019-20 NL/2018-19/8034,Roads,Completed,NL-VALASARAVAKKAM,144,306000,"Attending B.T. Patch work at Various Streets in DN-144, UNIT-32, ZONE-11",Own Sources,11,2018-19,2019-20 NL/2018-19/8775,Roads,Completed,NL-VALASARAVAKKAM,144,460000,"Relaying the BT Road at Om Sakthi Nagar Main Road in Div-144, Unit-32, Zone-11",Grants,11,2018-19,2019-20 NL/2018-19/9127,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,1979000,"Desilting and Minor Repair works to the damaged existing drains at various streets in 144 U-32, Z-11.",Own Sources,11,2018-19,2019-20 BR/2018-19/17280,Road Cut,Completed,BR-Bus Route Roads,145,17400,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-145, Zone-XI",Deposit Works,11,2018-19,2019-20 D/2018-19/9429,Storm Water Drain,Completed,D-Storm Water Drains,145,23683000,Construction of Storm Water Drain at Pachaiappan Street and 2 Other Roads in Zone - 10 - Package - 46.,Grants,11,2018-19,2020-21 D/2018-19/9690,Storm Water Drain,Completed,D-Storm Water Drains,145,13811000,"Construction of Storm Water Drain at Mookambigai Nagar 2nd Main Road and 3 Other Roads in Dn. - 145, Zone -11 - Package - 47.",Grants,11,2018-19,2019-20 L/2018-19/12924,Electrical,Completed,L-Electrical,145,1812000,"Replacement of Damaged 951 meters of 2*16 Sqmm Aluminium cable & 3518 meters of 4*16Sqmm Aluminium cable at Elumbu company road,Muniyappa Nagar & various location in Division 145 ,zone XI as per list enclosed",Own Sources,11,2018-19,2020-21 NL/2018-19/10751,Buildings,Completed,NL-VALASARAVAKKAM,145,81000,"Improvement Work to PH Road Amma Unavagam in DN-145, UNIT-33, Z-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/13287,Buildings,Completed,NL-VALASARAVAKKAM,145,274000,"Providing Improvement works to Valliyammai nagar Burial ground in Dn-145, U-33, Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/14264,Roads,Completed,NL-VALASARAVAKKAM,145,376000,"Attending patch work at Reddy Street, Madha koil Street, N.T. Patel Road and Saraswathi Colony in dn-145, U-33 in Z - XI",Own Sources,11,2018-19,2020-21 NL/2018-19/14415,Roads,Completed,NL-VALASARAVAKKAM,145,87000,"Repair to Street Name board at Various streets in Division-145, Unit-33, Zone-11",Own Sources,11,2018-19,2020-21 NL/2018-19/6009,Roads,Completed,NL-VALASARAVAKKAM,145,102000,"Repair to Street Name board at Various streets in Division-145, Unit-33, Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/8065,Roads,Completed,NL-VALASARAVAKKAM,145,132000,"Attending patch work at Various street in division - 145, unit - 33 in Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/9321,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,345000,"Desilting of SWD and Side Drain at various streets in Div - 145, U-33, Z-XI",Own Sources,11,2018-19,2018-19 NL/2018-19/9322,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,346000,"Minor Repair works to the damaged existing drains at various streets in Div-145, U-33, Z-11.",Own Sources,11,2018-19,2018-19 NL/2018-19/9901,Buildings,Completed,NL-VALASARAVAKKAM,145,562000,"Improvement of Anganwadi at Palvadi St, Perumal Koil St,Mandhaiveli 2nd St,Janagiraman Colony in DN-145, UNIT-33, ZONE-11.",Own Sources,11,2018-19,2021-22 NL/2018-19/9902,Buildings,Completed,NL-VALASARAVAKKAM,145,292000,"Improvement works at Madha Koil Street Amma Unavagam in DN-145, UNIT-33, ZONE-11.",Own Sources,11,2018-19,2019-20 BR/2018-19/17281,Road Cut,Completed,BR-Bus Route Roads,146,56000,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-146, Zone-XI",Deposit Works,11,2018-19,2019-20 L/2018-19/10981,Electrical,Completed,L-Electrical,146,170000,"Erection of (shiftig) 12 Nos 6Mtrs existing Lamp post and fixing of 12 Nos 2 Mtrs straight bracket at Various street Junction in Maduravoyal , Division 146 , Zone XI",Own Sources,11,2018-19,2019-20 L/2018-19/10982,Electrical,Completed,L-Electrical,146,146000,"Erection of (shiftig) 10 Nos 6Mtrs existing Lamp post and fixing of 10 Nos 2 Mtrs straight bracket at Various street Junction in Maduravoyal , Division 146 , Zone XI",Own Sources,11,2018-19,2019-20 L/2018-19/10983,Electrical,Completed,L-Electrical,146,162000,"Erection of (shiftig) 11 Nos 6Mtrs existing Lamp post and fixing of 11 Nos 2 Mtrs straight bracket at Various street Junction in Maduravoyal , Division 146 , Zone XI",Own Sources,11,2018-19,2019-20 NL/2018-19/10756,Buildings,Completed,NL-VALASARAVAKKAM,146,127000,"Improvements Work For Amma Unavagam at P.H.Road and Ganapathy Nagar in DN-146, UNIT-32, ZONE-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/11094,Roads,Completed,NL-VALASARAVAKKAM,146,307000,"Relaying the BT Road at Iyappa nagar 7th street in Div- 146, Unit- 32, Zone -XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/13205,Parks,Completed,NL-VALASARAVAKKAM,146,134000,"Maintenance for Park at Metro Nagar (7months) in Dn.146, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/14187,Roads,Completed,NL-VALASARAVAKKAM,146,184000,"Relaying the BT Road at Dhanalakshmi nagar 3rd street in Div- 146, Unit- 32, Zone -XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/14703,Roads,Completed,NL-VALASARAVAKKAM,146,380000,"Relaying the BT Road at Gangaiamman koil 10th 3rd street in Div- 146, Unit- 32, Zone -XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1535,Roads,Completed,NL-VALASARAVAKKAM,146,483000,"Relaying the B.T. Road at Bharathidasan Nagar 1st Cross Street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1536,Roads,Completed,NL-VALASARAVAKKAM,146,319000,"Relaying B.T. Road at Sri lakshmi Nagar 2nd Avenue in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1537,Roads,Completed,NL-VALASARAVAKKAM,146,466000,"Relaying the B.T. Road at Iyappa Nagar 6th street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1538,Roads,Completed,NL-VALASARAVAKKAM,146,368000,"Relaying the B.T. Road at New Subramaniam Nagar Main Road in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1539,Roads,Completed,NL-VALASARAVAKKAM,146,487000,"Relaying the B.T. Road at Gangaiamman koil 8th Street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/18026,Roads,Completed,NL-VALASARAVAKKAM,146,384000,"Relaying the BT Road at Metro Nagar 2nd Avenue in Dn 146, Unit 32, Zone XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/18027,Roads,Completed,NL-VALASARAVAKKAM,146,241000,"Relaying the BT road at Dhanalakshmi nagar 6th street in Dn-146, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/3387,Roads,Completed,NL-VALASARAVAKKAM,146,255000,"Relaying the BT Road at Iyappa nagar 8th street in Div- 146, Unit- 32, Zone -XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/3744,Roads,Completed,NL-VALASARAVAKKAM,146,271000,"Relaying the BT road at Dhanalakshmi nagar 7th street in DN-146, UNIT - 32, ZONE - XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/5423,Roads,Completed,NL-VALASARAVAKKAM,146,90000,"Repair to street name board at various streets in DN-146, UN-32, ZONE-XI",Own Sources,11,2018-19,2020-21 NL/2018-19/7828,Roads,Completed,NL-VALASARAVAKKAM,146,484000,"Relaying of BT road at Metro Nagar 3rd Avenue in Div-146, Unit-32, Zone-11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/7839,Roads,Completed,NL-VALASARAVAKKAM,146,805000,"Relaying of BT road at Metro Nagar 1st Avenue in Div-146, Unit-32, Zone-11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/8020,Roads,Completed,NL-VALASARAVAKKAM,146,240000,"Attending BT Patch work at Various Streets in Dn -146, U-32, Z-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/8108,Roads,Completed,NL-VALASARAVAKKAM,146,524000,"Relaying of BT road at Selvavinayagar street in Div-146, Unit-32, Zone-11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/8466,Roads,Completed,NL-VALASARAVAKKAM,146,1666000,"Forming the BT Road at Sri lakshmi nagar main road in Div- 146, Unit- 32, Zone -XI",Loans And Grants,11,2018-19,2020-21 BR/2018-19/17282,Road Cut,Completed,BR-Bus Route Roads,147,33000,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-147, Zone-XI",Deposit Works,11,2018-19,2019-20 L/2018-19/12263,Electrical,Completed,L-Electrical,147,2587000,Replacement of 3564 Mtr 2x16 Sqmm UG Cable and 1584 Mtr 4x16 Sqmm UG Cable at Various Location in Division 147in Zone 11,Own Sources,11,2018-19,2019-20 L/2018-19/3597,Electrical,Completed,L-Electrical,147,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office:147 Building , Gangai Amman Koil Street , Maduravoyal , in Division-147, Zone-XI (E.B.Account no-402.005.696 )",SMART CITY - ELECTRICAL,11,2018-19,2019-20 NL/2018-19/0028,Roads,Completed,NL-VALASARAVAKKAM,147,925000,"Relaying Cement Concrete Road at Mulayansingh yadav street in Div-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/0029,Roads,Completed,NL-VALASARAVAKKAM,147,816000,"Relaying Cement Concrete Road at Arangalanathan Street in Div-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2020-21 NL/2018-19/10575,Parks,Completed,NL-VALASARAVAKKAM,147,462000,"Forming of Open Gym at Bharathi Park at Bharathi Nagar 3rd Street in Div-147, U-32, Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/10659,Buildings,Completed,NL-VALASARAVAKKAM,147,456000,"Supplying and Installation of Bio Shredding Pulverizer Machine, Manure Siever Machine and Weighing Machine including Civil and Electrical Work at the Existing Compost Yard at Gangaiamman Koil Street in Div-147, Unit-32, Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/10696,Parks,Completed,NL-VALASARAVAKKAM,147,177000,"Improvement work to Bharathi Park at Bharathi Nagar 3rd Street in Div-147, U-32, Z-11",Own Sources,11,2018-19,2020-21 NL/2018-19/10798,Buildings,Completed,NL-VALASARAVAKKAM,147,61000,"Repairs and Improvements to the Amma Unavagam at Ganga Nagar and Gangaiamman koil street in Div-147, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/10799,Roads,Completed,NL-VALASARAVAKKAM,147,433000,"Conversion to existing Speed breaker as per (IRC) Standard 8 Numbers at various Streets in Dn -147, U - 32, Z - XI",Own Sources,11,2018-19,2020-21 NL/2018-19/13151,Roads,Completed,NL-VALASARAVAKKAM,147,448000,"Attending Patch Work at Perumal Koil Street and Ganga Nagar Gandhi Street in Dn - 147, U - 32, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/13206,Parks,Completed,NL-VALASARAVAKKAM,147,123000,"Maintenance for Park at Pallavan Nagar(7months) in Dn.147, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13207,Parks,Completed,NL-VALASARAVAKKAM,147,157000,"Maintenance for Park at Gangai amman koil Street Arignar Anna Park( 7 months) in Dn.147, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13208,Parks,Completed,NL-VALASARAVAKKAM,147,152000,"Maintenance for Park at Bharathiyar Nagar (7 months ) in Dn.147, Unit-32, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13228,Buildings,Completed,NL-VALASARAVAKKAM,147,563000,"Providing Shed for Motor room and other Improvements to Division office & Shredding machine unit located inside the Division office Building at Gangaiamman Koil Street in Div-147, Unit-32, Zone-XI",Own Sources,11,2018-19,2020-21 NL/2018-19/1328,Buildings,Completed,NL-VALASARAVAKKAM,147,1430000,"Relaying B.T. Road at Sri devi nagar main road in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/13316,Buildings,Completed,NL-VALASARAVAKKAM,147,283000,"Providing Electricity and Water facility to the existing E-toilet at Alapakkam main road and Arcot road in Div-147, Unit-32, Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/13930,Roads,Completed,NL-VALASARAVAKKAM,147,370000,"Attending BT and CC Patches at Various Streets in Din -147, U-32, Z-XI",Own Sources,11,2018-19,2020-21 NL/2018-19/14260,Roads,Completed,NL-VALASARAVAKKAM,147,74000,"Repair to the existing street name board at various street in Div-147,U-32, Z-11",Own Sources,11,2018-19,2020-21 NL/2018-19/15032,Parks,Completed,NL-VALASARAVAKKAM,147,190000,"Maintenance of Thanthai periyar Thiedal (one year) in Div-147, Unit-32, Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/1515,Roads,Completed,NL-VALASARAVAKKAM,147,654000,"Forming B.T. Road at Astalakshmi 19th Street in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/1517,Roads,Completed,NL-VALASARAVAKKAM,147,259000,"Relaying B.T. Road at Seemathamman Nagar Main Road in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/1519,Roads,Completed,NL-VALASARAVAKKAM,147,351000,"Relaying B.T. Road at Mettukuppam Main Road in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/1520,Roads,Completed,NL-VALASARAVAKKAM,147,271000,"Relaying B.T. Road at Astalakshmi 27th Street in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/1522,Roads,Completed,NL-VALASARAVAKKAM,147,620000,"Relaying B.T. Road at Krishna Nagar 2nd Main Road in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/1523,Roads,Completed,NL-VALASARAVAKKAM,147,703000,"Relaying B.T. Road at Krishnamachari Nagar 2nd Main Road in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/1524,Roads,Completed,NL-VALASARAVAKKAM,147,291000,"Relaying B.T. Road at MG Chakkarabani Main Road in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/1525,Roads,Completed,NL-VALASARAVAKKAM,147,609000,"Forming of BT Road at Astalakshmi nagar 4th street in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/15494,Parks,Completed,NL-VALASARAVAKKAM,147,150000,"Forming Badminton Court and other improvement works to Arignar Anna Park & Pallavan Nagar Park in Div-147, U-32, Z-11",Own Sources,11,2018-19,2020-21 NL/2018-19/15977,Buildings,Completed,NL-VALASARAVAKKAM,147,57000,"Dismantling of old Anganwadi building at Ganga nagar 3rd main road in Div-147, Unit-32, Zone - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/1632,Roads,Completed,NL-VALASARAVAKKAM,147,819000,"Relaying B.T. Road at Astalakshmi nagar 3rd Main road in Dn-147, Unit-32, Zone-XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/5392,Parks,Completed,NL-VALASARAVAKKAM,147,422000,"Improvement work and painting work to the Arignar anna park at Gangai amman koil Street in div-147, U-32, Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/5547,Roads,Completed,NL-VALASARAVAKKAM,147,573000,"Providing Speed breaker as per (IRC) Standard 16 nos at various Streets in Dn - 147, U - 32, Z - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/8010,Buildings,Completed,NL-VALASARAVAKKAM,147,495000,"Improvement work to Anganwadi at Ganga nagar and perumal koil street in div-147,unit -32,zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/8015,Roads,Completed,NL-VALASARAVAKKAM,147,900000,"Attending patch work at various streets in Dn -147, U-32, Z-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/8081,Roads,Completed,NL-VALASARAVAKKAM,147,1533000,"Attending road cut restoration at Astalakshmi nagar 1st,2nd & 5th main road and 3rd street in Div-147,Unit-32, Zone-11",Deposit Works,11,2018-19,2019-20 NL/2018-19/9128,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,2428000,"Desilting and Minor Repair works to the damaged existing drains at various streets in Div-146 and 147 U-32, Z-11.",Own Sources,11,2018-19,2019-20 L/2018-19/12925,Electrical,Completed,L-Electrical,148,2200000,"Replacement of Damaged 2047 meters of 2*16 Sqmm Aluminium cable & 3776 meters of 4*16Sqmm Aluminium cable at CDN Main road Balavinyaga nagar & various location in Division 148 ,zone XI as per list enclosed",Own Sources,11,2018-19,2020-21 L/2018-19/16148,Electrical,Completed,L-Electrical,148,86300,"supply, Installation,Testing & Commissioning of 1Kwp grid solar Rooftop inclunding civil works and earthing at balavinyagar nagar Nerkundrum ,Div-148 .Zone-XI",Grants,11,2018-19,2019-20 L/2018-19/6105,Electrical,Completed,L-Electrical,148,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC , Mettukupam main road ,Nerkundrum, Div-148, Zone-XI",SMART CITY - ELECTRICAL,11,2018-19,2019-20 NL/2018-19/10431,Buildings,Completed,NL-VALASARAVAKKAM,148,269000,"Improvement works to Anganwadi at Bhuvaneswari Nagar sheela Mohan Street and Govardhan Nagar Vanchinathan Street in Dn-148, U-33, Zone-XI",Own Sources,11,2018-19,2021-22 NL/2018-19/13353,Electrical,Completed,NL-VALASARAVAKKAM,148,225700,"IMPROVEMENTS OF AMMA UNAVAGAM AT KAMARAJAR HIGH ROAD IN DN -148 , U -33 , Z -11",Own Sources,11,2018-19,2019-20 NL/2018-19/16515,Parks,Completed,NL-VALASARAVAKKAM,148,170000,"Provision of 4 Number of 160w-200w LED Flood lights at badminton court & cable laying for 5KVA Diesel generator for newly formed AIS Quarters in Dn-148, Unit - 33, Zone - XI.",Own Sources,11,2018-19,2020-21 NL/2018-19/16516,Parks,Completed,NL-VALASARAVAKKAM,148,332000,"Provision of 1nos 5KVA Diesel generator for newly formed AIS Quarters in Dn-148, Unit - 33, Zone - XI.",Own Sources,11,2018-19,2020-21 NL/2018-19/17741,Parks,Completed,NL-VALASARAVAKKAM,148,1135000,"IMPROVEMENT WORKS IN TAISHA PARK AT AIS HOUSING COMPLEX, NERKUNDRAM IN DN- 148,UNIT-33, ZONE-XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/2966,Parks,Completed,NL-VALASARAVAKKAM,148,1575000,"ANNUAL MAINTENANCE FOR TAISHA PARK AT AIS HOUSING COMPLEX, NERKUNDRAM IN DN- 148,UNIT-33, ZONE-XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/6065,Buildings,Completed,NL-VALASARAVAKKAM,148,292000,"IMPROVEMENT WORKS TO UPHC AT KAMARAJAR HIGH ROAD IN DN-148, UNIT- 33, ZONE - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/6070,Roads,Completed,NL-VALASARAVAKKAM,148,321000,"PROPOSED PATCH WORK AT VARIOUS STREETS IN DN-148, UNIT-33, ZONE - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/7085,Buildings,Completed,NL-VALASARAVAKKAM,148,2963000,"Proposed construction of 2 nos. of classrooms (GF) for Villivakkam Panchayat Middle School at School Street, Mettukuppam, Nerkundram Village in Dn-148, Unit - 33, Zone - XI.",MLACDS,11,2018-19,2020-21 NL/2018-19/7479,Roads,Completed,NL-VALASARAVAKKAM,148,728000,"Providing Speed Breakers as per IRC Standards at various streets in Dn-148, Unit- 33, Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/7774,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,546000,"Desilting of side drains at various streets in Dn-148, Unit-33, Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/7807,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,1483000,"Minor repairs to the existing side drains in Dn-148, Unit - 33, Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/8835,Parks,Completed,NL-VALASARAVAKKAM,148,1355000,"REPAIRS AND IMPROVEMENTS TO PARKS,SWD ETC.,IN DN148,UNIT33,ZONE11.",Own Sources,11,2018-19,2018-19 BR/2018-19/17283,Road Cut,Completed,BR-Bus Route Roads,149,104000,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-149, Zone-XI",Deposit Works,11,2018-19,2019-20 BR/2018-19/17762,Roads,Completed,BR-Bus Route Roads,149,706000,Restoration of road cut made by OFC at Bus Route Roads and Interior Roads in Zone - 11,Deposit Works,11,2018-19,2019-20 L/2018-19/12264,Electrical,Completed,L-Electrical,149,1377000,Replacement of 1386 Mtr 2x16 Sqmm UG Cable and 1195 Mtr 4x16 Sqmm UG Cable at Various Location in Division 149in Zone 11,Own Sources,11,2018-19,2019-20 L/2018-19/3599,Electrical,Completed,L-Electrical,149,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit-33 and Division Office:149 Building ,Chinthamani Vinayagar Koil Street ,Alwar Thiru Nagar , in Division-149, Zone-XI (E.B.Account no-227.061.367 )",SMART CITY - ELECTRICAL,11,2018-19,2019-20 NL/2018-19/10570,Parks,Completed,NL-VALASARAVAKKAM,149,130000,"Additional Improvement works to Brindhavan Nagar Varadha Park in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/10573,Parks,Completed,NL-VALASARAVAKKAM,149,103000,"Additional Improvement works to Brindhavan Nagar Park in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/10818,Buildings,Completed,NL-VALASARAVAKKAM,149,18000,"Improvement work to amma unavagam at Samantham Nagar 1st Street at Division - 149, Unit - 33 in Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13149,Roads,Completed,NL-VALASARAVAKKAM,149,448000,"Attending Patch Work at Sridevikuppam Main Road and Kamakodi Nagar in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/13159,Parks,Completed,NL-VALASARAVAKKAM,149,323000,"Maintenance for Thiru.Vi.Ka Park at Gandhi Road (Total Area - 2415 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13161,Parks,Completed,NL-VALASARAVAKKAM,149,115000,"Maintenance for Park at Brindavan nagar (Total Area - 510 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13162,Parks,Completed,NL-VALASARAVAKKAM,149,404000,"Maintenance for Park at Fathima Nagar (Total Area - 2730 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13163,Parks,Completed,NL-VALASARAVAKKAM,149,215000,"Maintenance for Park at CEEBROS OSR land (Total Area - 1630 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13164,Parks,Completed,NL-VALASARAVAKKAM,149,205000,"Maintenance for Park at OSR land Near Alsa Tower (Total Area - 1512 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13165,Parks,Completed,NL-VALASARAVAKKAM,149,227000,"Maintenance for Varadha Park at Brindhavan Nagar (Total Area - 2498.27 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13388,Roads,Completed,NL-VALASARAVAKKAM,149,786000,"Attending BT Patch Work at Various at Division - 149, Unit - 33, Zone - XI",Own Sources,11,2018-19,2020-21 NL/2018-19/13398,Buildings,Completed,NL-VALASARAVAKKAM,149,894000,Improvements to Thiru vi ka park in Division - 149 Unit - 33 in Zone - XI,Own Sources,11,2018-19,2020-21 NL/2018-19/13465,Parks,Completed,NL-VALASARAVAKKAM,149,1242000,"Improvements to the Existing Periyar Park at Fathima Nagar in Dn - 149, U - 33, Z - XI.",Own Sources,11,2018-19,2020-21 NL/2018-19/13529,Parks,Completed,NL-VALASARAVAKKAM,149,513000,"Improvements to vardha park at Brinthavan nagar 5th street in DN-149, Unit-33, Zone-XI",Own Sources,11,2018-19,2020-21 NL/2018-19/13971,Playfields,Completed,NL-VALASARAVAKKAM,149,521000,"Improvements to the Existing Ramakrishna Nagar Play Ground at Tagore Street in Dn-149,U-33, Z-11",Own Sources,11,2018-19,2020-21 NL/2018-19/15056,Buildings,Completed,NL-VALASARAVAKKAM,149,298000,"Attending roof leakage and floor damage at Brindhavan nagar burial ground at Division - 149, unit - 33 in Zone - XI",Own Sources,11,2018-19,2020-21 NL/2018-19/3266,Buildings,Completed,NL-VALASARAVAKKAM,149,454000,"PROVIDING OPEN GYM EQUIPMENTS INCLUDING PLAT FORM AT Ramakrishna Nagar Playground IN DN-149, UNIT-33 ,ZONE-",Own Sources,11,2018-19,2018-19 NL/2018-19/3267,Buildings,Completed,NL-VALASARAVAKKAM,149,454000,"PROVIDING OPEN GYM EQUIPMENTS INCLUDING PLAT FORM AT Thiru Vi Ka Park IN DN-149, UNIT-33 ,ZONE-",Own Sources,11,2018-19,2018-19 NL/2018-19/3296,Buildings,Completed,NL-VALASARAVAKKAM,149,103000,"Demolition of Existing Building & Construction of Compound wall at Thiru Vi Ka Park DN-149, UNIT-33 ,ZONE-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/4857,Electrical,Completed,NL-VALASARAVAKKAM,149,93500,Replacement of Damaged U.G.cable and Permanent wiring for unit-33 office 15KVA Diesel Generator set at Chindamani Vinayagar koil street in Division 149 in Zone-11,Own Sources,11,2018-19,2018-19 NL/2018-19/5970,Roads,Completed,NL-VALASARAVAKKAM,149,57000,"Repair to Street Name board at Various streets in Division-149, Unit-33, Zone-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/6021,Playfields,Completed,NL-VALASARAVAKKAM,149,47000,"Improvements at Arunagiri Street Play Field in Div-149,U-33,Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/8068,Roads,Completed,NL-VALASARAVAKKAM,149,20700,"Attending patch work at Muralikrishna nagar main road & Velan Nagar Main Road in Division - 149, Unit - 33 in Zone - XI",Own Sources,11,2018-19,2019-20 BR/2018-19/15673,Road Cut,Completed,BR-Bus Route Roads,150,44500,Restoration of OFC road cut by Reliance at various Bus Route Roads in Zone-IX(Deposit Code-57/0082/2018-19),Deposit Works,11,2018-19,2019-20 BR/2018-19/17284,Road Cut,Completed,BR-Bus Route Roads,150,460000,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-150, Zone-XI",Deposit Works,11,2018-19,2019-20 BR/2018-19/18173,Roads,Completed,BR-Bus Route Roads,150,1200000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER (1 NO) AT MOUNT POONAMALLEE ROAD ( TOWARDS GUINDY) IN DIV-150, ZONE-11. (UNDER M.P FUND) SIZE:( 9.00MX2.50M)",MPLADS,11,2018-19,2019-20 BR/2018-19/4237,Roads,Completed,BR-Bus Route Roads,150,1200000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER (1 NO) AT PORUR, (JUNCTION OF LAKSHMI NAGAR TOWARDS GUINDY) IN DIV-150, ZONE-11. (UNDER M.P FUND) SIZE:( 9.00MX2.50M)",MPLADS,11,2018-19,2019-20 D/2018-19/8446,Storm Water Drain,Completed,D-Storm Water Drains,150,2214000,"Restoration and other improvements to Abbadurai pillai street pond in Dn-150,Zone-11.",SMART CITY - SWD,11,2018-19,2020-21 L/2018-19/13341,Electrical,Completed,L-Electrical,150,1483000,"Replacement of Damaged 2331 Meters of 2X16 Sq.mm alu.Cable and 1307 Meters of 4X16 Sq.mm Alu Cable at Erikkarai street,Mandaveli street & Various places in Division 150,Zone-XI.",Own Sources,11,2018-19,2020-21 L/2018-19/5962,Electrical,Completed,L-Electrical,150,161400,"supply, Installation,Testing & Commissioning of 2Kwp grid Tiedsolar Rooftop inclunding civil works and earthing at Kitchen centre, Theruveethi amman koil street, thundalam,Karambakkam, Porur,Div-150.Zone-XI",SMART CITY - ELECTRICAL,11,2018-19,2019-20 L/2018-19/9900,Electrical,Completed,L-Electrical,150,178000,"Erection of 2 nos of 8mtr lamp post with Double Arch bracket with 4 nos of 150w LED fittings at mount poonamallee road in Div 150,Zone -XI",Own Sources,11,2018-19,2019-20 NL/2018-19/10671,Buildings,Completed,NL-VALASARAVAKKAM,150,472000,"Supplying and Installation of Vegetable Pulvariser and Mechanical Siever Machine at the Existing Compost Yard at Gandhi Nagar Main Road in Dn - 150, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/10805,Roads,Completed,NL-VALASARAVAKKAM,150,3039000,"IMPROVEMENTS TO INTERIOR BT ROAD AT AGNI FAIRY LAND STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2019-20 NL/2018-19/10806,Roads,Completed,NL-VALASARAVAKKAM,150,528000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THUNDALAM PERUMAL KOIL 1ST STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2019-20 NL/2018-19/10807,Roads,Completed,NL-VALASARAVAKKAM,150,200000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THUNDALAM PERUMAL KOIL 1ST CROSS STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2019-20 NL/2018-19/10808,Roads,Completed,NL-VALASARAVAKKAM,150,427000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THUNDALAM PERUMAL KOIL 2ND CROSS STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2019-20 NL/2018-19/10809,Roads,Completed,NL-VALASARAVAKKAM,150,935000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PONNI NAGAR KAMBAR STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/10811,Roads,Completed,NL-VALASARAVAKKAM,150,1174000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PONNI NAGAR PONNI AMMAN KOIL STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/10812,Roads,Completed,NL-VALASARAVAKKAM,150,1343000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THUNDALAM ERIKARI STREET FROM THUNDALAM BURIAL GROUND TO MGR STATUE IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2019-20 NL/2018-19/10814,Roads,Completed,NL-VALASARAVAKKAM,150,622000,"IMPROVEMENTS TO INTERIOR BT ROAD AT THUNDALAM ANNA NAGAR PHASE - 2 MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2019-20 NL/2018-19/10815,Roads,Completed,NL-VALASARAVAKKAM,150,574000,"IMPROVEMENTS TO INTERIOR BT ROAD AT ARUNACHALAM NAGAR 3RD STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/10816,Roads,Completed,NL-VALASARAVAKKAM,150,256000,"IMPROVEMENTS TO INTERIOR BT ROAD AT PONNI NAGAR JAIN KOIL STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/13169,Parks,Completed,NL-VALASARAVAKKAM,150,522000,"Maintenance for Park at Parasnath Nagar Sayarbhai Street (Total Area - 6347 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13172,Parks,Completed,NL-VALASARAVAKKAM,150,406000,"Maintenance for Park at Phase - I Maruthi nagar OSR Land (Total Area - 2676 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13173,Parks,Completed,NL-VALASARAVAKKAM,150,208000,"Maintenance for Park at Phase -III Maruthi nagar OSR Land (Total Area - 1338 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13174,Parks,Completed,NL-VALASARAVAKKAM,150,209000,"Maintenance for Park at Ponniamman Nagar (Total Area - 1000 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/14416,Roads,Completed,NL-VALASARAVAKKAM,150,28000,"REPAIRS TO EXISTING STREET NAME BOARD AT VARIOUS STREET IN DIV - 150, U - 34, Z- 11",Own Sources,11,2018-19,2019-20 NL/2018-19/15597,Electrical,Completed,NL-VALASARAVAKKAM,150,1908000,"Removal of damaged lamp post and Replacement of cable and conversion Fittings for Various parks and Playgrounds in Division 150,151 & 153 in Zone -XI.",Own Sources,11,2018-19,2020-21 NL/2018-19/1831,Roads,Completed,NL-VALASARAVAKKAM,150,456000,"IMPROVEMENTS TO INTERIOR BT ROAD AT KARAMBAKKAM PILLAIYAR KOIL STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1846,Roads,Completed,NL-VALASARAVAKKAM,150,398000,"FORMING OF CC ROAD AT KARAMBAKKAM K.K.R. GARDEN IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1850,Roads,Completed,NL-VALASARAVAKKAM,150,932000,"FORMING OF CC ROAD AT THUNDALAM ANNA NAGAR PANJALI STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/1851,Roads,Completed,NL-VALASARAVAKKAM,150,506000,"FORMING OF CC ROAD AT THUNDALAM ANNA NAGAR PANJALI CROSS STREET IN DIV - 150, UNIT - 34, ZONE - 11",Loans And Grants,11,2018-19,2020-21 NL/2018-19/3531,Parks,Completed,NL-VALASARAVAKKAM,150,455000,"PROVIDING OPEN GYM EQUIPMENTS INCLUDING PLATFORM AT PARASNATH NAGAR PARK IN DIV - 150, UNIT - 34, ZONE - 11",Own Sources,11,2018-19,2018-19 NL/2018-19/7042,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,346000,"Desilting of SWD and Side Drain at Various Streets in Dn - 150, U - 34, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/7260,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,1222000,"Desilting of SWD at Bypass Service Road in Dn - 150, U - 34, Z - XI.",Own Sources,11,2018-19,2018-19 B/2018-19/4874,Buildings,Completed,B-Buildings,151,5440000,"SUPPLY, INSTALLATION,TESTING , COMMISSIONING AND MAINTENANCE FOR ONE YEAR OF CENTRALISED MEDICAL MEDICAL GAS SYSTEM IN URBAN COMMUNITY HEALTH CENTER VALASARAWAKKAM IN DN-151 ZONE-11",Grants,11,2018-19,2020-21 BR/2018-19/17285,Road Cut,Completed,BR-Bus Route Roads,151,94000,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-151, Zone-XI",Deposit Works,11,2018-19,2019-20 L/2018-19/10915,Electrical,Completed,L-Electrical,151,1800000,"Replacement of 2918 Meters of Damaged 4*25 Sq.mm.Cable , Painting of 174 Nos of 8 Mtr Lamp, post at Mount Poonamallee Road and Kundrathur Roads in Division 150,151,153 and 154,Porur and Ramapuram,Zone-XI (Global Invester Meet-2018.(G.I.M.2018)",Own Sources,11,2018-19,2019-20 L/2018-19/13342,Electrical,Completed,L-Electrical,151,1545000,"Replacement of Damaged 3655 Meters of 2X16 Sq.mm alu.Cable and 399 Meters of 4X16 Sq.mm Alu Cable at Lakshmi nagar & Various places in Division 151,Zone-XI.",Own Sources,11,2018-19,2020-21 L/2018-19/5969,Electrical,Completed,L-Electrical,151,86200,"supply, Installation,Testing & Commissioning of 1Kwp grid Tiedsolar Rooftop inclunding civil works and earthing at Lakshmi Nagar, Porur,Div-151.Zone-XI",SMART CITY - ELECTRICAL,11,2018-19,2019-20 L/2018-19/5972,Electrical,Completed,L-Electrical,151,236700,"supply, Installation,Testing & Commissioning of 3Kwp grid Tiedsolar Rooftop inclunding civil works and earthing at Electrical Crematorium,Arcot Road,Porur,Div-151.Zone-XI",SMART CITY - ELECTRICAL,11,2018-19,2019-20 NL/2018-19/10545,Buildings,Completed,NL-VALASARAVAKKAM,151,455000,"Supplying and Installation of Vegetable Pulvariser and Mechanical Siever Machine at the Existing Compost Yard at Alapakkam Cross Street in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/10667,Buildings,Completed,NL-VALASARAVAKKAM,151,497000,"Supplying and Installation of Vegetable Pulvariser and Mechanical Siever Machine at the Existing Compost Yard at School Street in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/10738,Buildings,Completed,NL-VALASARAVAKKAM,151,163000,"Repair works to Anganwadi at Bajanai Koil Street Chinna Porur in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2020-21 NL/2018-19/10784,Roads,Completed,NL-VALASARAVAKKAM,151,355000,"Improvements to interior BT road at Sethuraman Street in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/11593,Culvert,Completed,NL-VALASARAVAKKAM,151,660000,"Proposed Construction of SWD culvert in Poothabedu salai - 4 nos & Anna salai - 1no in dn 151, U-34, Z XI",Own Sources,11,2018-19,2019-20 NL/2018-19/12812,Buildings,Completed,NL-VALASARAVAKKAM,151,1034000,"Proposed Compound Wall for Compost Yard at Alapakkam Main Road (Southern Side & Northern Side) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13176,Parks,Completed,NL-VALASARAVAKKAM,151,122000,"Maintenance for Park at Sabari Nagar 5th street (Total Area - 927.50 Sq.m) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13177,Parks,Completed,NL-VALASARAVAKKAM,151,183000,"Maintenance for Park at T.C.G park (Total Area - 995 Sq.m) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13213,Playfields,Completed,NL-VALASARAVAKKAM,151,168000,"Annual Maintenance for Playground at Lakshmi Nagar Extn. 4th Main Road (Total - 1961.17 Sq.m) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13214,Playfields,Completed,NL-VALASARAVAKKAM,151,169000,"Annual Maintenance for Playground at Lakshmi Nagar 5th Cross Street (Total - 480.03 Sq.m) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13863,Roads,Completed,NL-VALASARAVAKKAM,151,1222000,"Attending BT Patches for Various Streets in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13898,Buildings,Completed,NL-VALASARAVAKKAM,151,60000,"Providing Basic Amenities to the Proposed E-Toilet Location (Elect. Crematorium) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13899,Buildings,Completed,NL-VALASARAVAKKAM,151,57000,"Providing Basic Amenities to the Proposed E-Toilet Location (Hospital Road) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/15159,Road Cut,Completed,NL-VALASARAVAKKAM,151,132000,"Roadcut Restoration work at Lakshmi Nagar Extn. 7th Main Road in Dn - 151, U - 34, Z - XI.",Deposit Works,11,2018-19,2019-20 NL/2018-19/15512,Buildings,Completed,NL-VALASARAVAKKAM,151,1188000,"Operation and Maintenance of high quality treated drinking water plant (RO/UV Filtration) at school road,(For 12 months), Div-151,U-34,Z-11",Own Sources,11,2018-19,2020-21 NL/2018-19/15514,Buildings,Completed,NL-VALASARAVAKKAM,151,2252000,"Operation and Maintenance of Electrical Burial Ground for 12 months at Arcot Road in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2021-22 NL/2018-19/2110,Parks,Completed,NL-VALASARAVAKKAM,151,288000,"REPAIR AND MAINTENANCE WORK AT LASKHMI NAGAR EXTN 4TH MAIN ROAD PLAY GROUND, PORUR PARK AND LAKSHMI NAGAR 5TH CROSS STREEET PLAY GROUND IN DN.151, U 34, Z 11.",Own Sources,11,2018-19,2019-20 NL/2018-19/7040,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,152000,"Desilting of SWD and Side Drain at Various Streets in Dn - 151, U - 34, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/8990,Buildings,Completed,NL-VALASARAVAKKAM,151,527000,"ADDITIONAL IMPROVEMENT WORK TO ELECTRICAL CREMATORIUM AT ARCOT ROAD IN DIV - 151, U -34, Z-11.",Own Sources,11,2018-19,2018-19 NL/2018-19/9674,Electrical,Completed,NL-VALASARAVAKKAM,151,461000,"Electrification work in Electrical Crematorium Building at Arcot Road,Porur,Zone-XI",Own Sources,11,2018-19,2019-20 BR/2018-19/15678,Road Cut,Completed,BR-Bus Route Roads,152,253000,Restoration of OFC road cut made by AIrtel at various Bus Route roads in Zone-X (deposit code-57/0280/2018-19),Deposit Works,11,2018-19,2019-20 BR/2018-19/17286,Road Cut,Completed,BR-Bus Route Roads,152,125000,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-152, Zone-XI",Deposit Works,11,2018-19,2019-20 L/2018-19/12265,Electrical,Completed,L-Electrical,152,979000,Replacement of 1176 Mtr 2x16 Sqmm UG Cable and 662 Mtr 4x16 Sqmm UG Cable at Various Location in Division 152in Zone 11,Own Sources,11,2018-19,2019-20 L/2018-19/3601,Electrical,Completed,L-Electrical,152,764000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Zonal Office Building , Arcot Road , Valasaravakkam ,in Division-152, Zone-XI (E.B.Account no-.240.002.413 )",Own Sources,11,2018-19,2019-20 NL/2018-19/10788,Roads,Completed,NL-VALASARAVAKKAM,152,2793000,"Improvements to interior BT Roads at Chowdry nagar 2nd street, Chowdry nagar 3rd street Chowdry nagar 4th street,Durairaj street,Janaki nagar Extn 1st Street,Janaki nagar Extn 2nd Street,Janaki nagar Extn 3rd Street,Kalainzar Cross street ,Kalainzar street ,Nagarathinammal street,Nedumaran street,N.N. Lakshmi street,Periyar street and Rukmani devi street in Division - 152, Unit - 33 in Zone - XI.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/10790,Roads,Completed,NL-VALASARAVAKKAM,152,2957000,"Improvements to interior BT Roads at Anna street,Annai Thresa Street,Bethaniya nagar 5th street,Chellammal Street,Chowdry nagar 11th street,Chowdry nagar 15th street,Chowdry nagar 16th street,Chowdry nagar 17th street,Chowdry nagar 18th street,Chowdry nagar 19th street and Chowdry nagar 1st street in Division - 152, Unit - 33, Zone - XI",Loans And Grants,11,2018-19,2019-20 NL/2018-19/10820,Buildings,Completed,NL-VALASARAVAKKAM,152,24000,"Improvement to amma unavagam at Thiruvalluvar salai and Thiruvalluvar St at Division - 152, Unit - 33, in Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/12208,Electrical,Completed,NL-VALASARAVAKKAM,152,1792700,"Supply and Fixing of 17 Nos of UV Water Purifier 500 Litre per hour capacity , 11 Nos of Weighing Machine ( up to 150 Kgm ), 8 Nos of Pulverizer of 15 Ltrs and 10 Nos of 300 Litre Cooler for various Amma Unavagam in Dn-143 to 155 in Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/13180,Parks,Completed,NL-VALASARAVAKKAM,152,109000,"Maintenance for Park at Zonal Office park (Total Area - 253 Sq.m) in Dn - 152, U - 33, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13414,Buildings,Completed,NL-VALASARAVAKKAM,152,218000,"Providing water supplying arrangements, drainage and compound wall to the E-Toilet in Zonal office campus at Division - 152 Unit - 33 in Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/15298,Electrical,Completed,NL-VALASARAVAKKAM,152,471000,"Supply and Fixing of TL Fittings, Ceiling Fan, Exhaust Fan, Wall mounting Fan, Water Heater and 5A /15A Switches for various Amma Unavagam in Dn-143 to 155 in Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/15550,Buildings,Completed,NL-VALASARAVAKKAM,152,1119000,"Providing GYM Equipments and Improvement to the Play Field at Chowdry Nagar Play Ground, Bharathi Colony Play Field, Veerapa Nagar Play field,Sai Ram Avenue Play Field at Division - 152, Unit - 33 in Zone - XI",Own Sources,11,2018-19,2020-21 NL/2018-19/15566,Buildings,Completed,NL-VALASARAVAKKAM,152,20000,"Improvements to the Amma Unavgam at Thiruvalluvar Street and Thiruvalluvar Salai, at Division - 152 Unit - 33 in Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/15596,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,117000,"Improvement to SWD at Alapakkam Main Road at Division - 152, Unit - 33 in Zone - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/4842,Electrical,Completed,NL-VALASARAVAKKAM,152,1873000,"Removal of Demaged Lamp Post and Replacement of Cable for Various Park's/PlayGround's in Division 147 ,149 & 152 in Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/5975,Roads,Completed,NL-VALASARAVAKKAM,152,31500,"Repair to Street Name board at Various streets in Division-152, Unit-33, Zone-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/6044,Playfields,Completed,NL-VALASARAVAKKAM,152,213000,"Improvement to the Childrens Play Field at Veerpa Nagar,Bharthi colony,Chowdry Nagar and Sai Ram Avenue in Div-152.U-33,Z-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/6574,Electrical,Completed,NL-VALASARAVAKKAM,152,193000,Supply and fixing of 16nos 18? sweep size heavy duty industrial type exhaust fan for the use of Electrical crematorium at Porur Division-150 and Gasifier Burial Ground at Brindhavanam nagar Division-149 in Zone-XI,Own Sources,11,2018-19,2018-19 NL/2018-19/7025,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,61000,"Desilting of SWD and Side Drain at Various Streets in Dn - 152, U - 33, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/7238,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,84000,"Repairs to SWD and Side Drain at Om Sakthi Nagar , P.N. Ramamurthy Street, Kadambadiamman Nagar Main Road, Alapakkam Main Road and Bharathidasan Street in Dn - 152, U - 33, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/8067,Roads,Completed,NL-VALASARAVAKKAM,152,171000,"Attending patch work at Chowdry nagar 9th st, SVS nagar main road, Lamech st in Division - 152, Unit - 33 in Zone - XI",Own Sources,11,2018-19,2019-20 BR/2018-19/15677,Road Cut,Completed,BR-Bus Route Roads,153,481000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-X (Deposit Code-57/0283/2018-19),Deposit Works,11,2018-19,2019-20 BR/2018-19/17287,Road Cut,Completed,BR-Bus Route Roads,153,126000,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-153, Zone-XI",Deposit Works,11,2018-19,2019-20 BR/2018-19/3057,Roads,Completed,BR-Bus Route Roads,153,952000,"PROPOSED MODERN NEW STAINLESS STEEL BUS SHELTER AT VIGNESHWARA NAGAR KUNDRATHUR ROAD IN DIV-153, ZONE-11 (UNDER MADURAVAYOL MLA SCHEME)",MLACDS,11,2018-19,2019-20 L/2018-19/13343,Electrical,Completed,L-Electrical,153,1771800,"Replacement of Damaged 2653 Meters of 2X16 Sq.mm alu.Cable and 1812 Meters of 4X16 Sq.mm Alu Cable at Mangala nagar & Various places in Division 153,Zone-XI.",Own Sources,11,2018-19,2020-21 L/2018-19/5960,Electrical,Completed,L-Electrical,153,236700,"supply, Installation,Testing & Commissioning of 3Kwp grid Tiedsolar Rooftop inclunding civil works and earthing at Community hall, Arivarasan salai, Ramakrishna Nagar, Porur,Div-153.Zone-XI",SMART CITY - ELECTRICAL,11,2018-19,2019-20 NL/2018-19/10388,Roads,Completed,NL-VALASARAVAKKAM,153,2467000,"Improvements to interior BT Roads at Subashree Nagar 1st Cross Street, Mangala Nagar 12Th Cross Street 1st Lane (Chekhilar Street) and Ramakrishna Nagar 2nd Street in Dn - 153,U - 34, Z - XI.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/10389,Roads,Completed,NL-VALASARAVAKKAM,153,2684000,"Improvements to interior BT Roads at Kamala Nagar Road 2nd Street, Santhosh Nagar Ganga Street, Mangala Nagar Main Road and Mangala Nagar 4th Cross Street in Dn - 153,U - 34, Z - XI.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/13181,Parks,Completed,NL-VALASARAVAKKAM,153,109000,"Maintenance for Park at Kanniyappan salai (Total Area - 796.70 Sq.m) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13182,Parks,Completed,NL-VALASARAVAKKAM,153,190000,"Maintenance for Park at Ramakrishna nagar (Total Area - 753.47 Sq.m) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13183,Parks,Completed,NL-VALASARAVAKKAM,153,130000,"Maintenance for Park at Ramaswamy nagar (Total Area - 1033.26 Sq.m) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13844,Roads,Completed,NL-VALASARAVAKKAM,153,1205000,"Attending BT Patches for Various Streets in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13895,Buildings,Completed,NL-VALASARAVAKKAM,153,61000,"Providing Basic Amenities to the Proposed E-Toilet Location (Wireless Station Road) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/14929,Buildings,Completed,NL-VALASARAVAKKAM,153,341000,"Proposed Construction of Compound Wall at Sterling Avenue OSR Vacant Land in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/15160,Road Cut,Completed,NL-VALASARAVAKKAM,153,84000,"Roadcut Restoration work at Mangala Nagar 5th Cross Street in Dn - 153, U - 34, Z - XI.",Deposit Works,11,2018-19,2019-20 NL/2018-19/15524,Buildings,Completed,NL-VALASARAVAKKAM,153,238000,"Improvements to Amma Unavagam at Wireless Station Road and Mount Poonamallee Road in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/4310,Road Cut,Completed,NL-VALASARAVAKKAM,153,89000,"Road cut restoration work at Chetty Street in Div-153, U-34, Z-11.",Deposit Works,11,2018-19,2019-20 NL/2018-19/5624,Roads,Completed,NL-VALASARAVAKKAM,153,596000,"Attending Patch Work at Various Streets in Dn - 153, U - 34, Z - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/6417,Buildings,Completed,NL-VALASARAVAKKAM,153,304000,"Proposed Construction of Toilet Block in Ramakrishna Nagar Park in Dn - 153,U - 34, Z - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/6418,Buildings,Completed,NL-VALASARAVAKKAM,153,304000,"Proposed Construction of Toilet Block in Kanniappan Salai Park in Dn - 153,U - 34, Z - XI",Own Sources,11,2018-19,2019-20 NL/2018-19/6577,Buildings,Completed,NL-VALASARAVAKKAM,153,331000,"Proposed Repair & Maintenance work at Shopping Complex in Sakthi Nagar Main Road in Dn - 153,U - 34, Z - XI",Own Sources,11,2018-19,2020-21 NL/2018-19/7033,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,331000,"Desilting of SWD and Side Drain at Various Streets in Dn - 153, U - 34, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/7655,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,712000,"Repair works to the damaged existing drains at various streets in Div - 153, U - 34, Z - 11.",Loans And Grants,11,2018-19,2018-19 P/2018-19/12002,Parks,Completed,P-Parks and Playfields,153,3500000,"Formation of New park at Udhaya Nagar main road in DN - 153, Zone - 11",Grants,11,2018-19,2020-21 BR/2018-19/15675,Road Cut,Completed,BR-Bus Route Roads,154,348000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-X (Deposit Code-57/0234/2018-19),Deposit Works,11,2018-19,2019-20 BR/2018-19/15676,Road Cut,Completed,BR-Bus Route Roads,154,105000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-X (Deposit Code3-57/0235/2018-19),Deposit Works,11,2018-19,2019-20 BR/2018-19/17899,Road Cut,Completed,BR-Bus Route Roads,154,90000,Restoration of OFC road cut by AIrtel at various Bus Route Roads in zone-X (Deposit Code-57/0089/2018-19),Deposit Works,11,2018-19,2019-20 D/2018-19/8414,Storm Water Drain,Completed,D-Storm Water Drains,154,1697000,"Restoration and other improvements to Aalangulam ramapuram for augmentation of water supply in Dn. - 154, Zone 11",SMART CITY - SWD,11,2018-19,2019-20 L/2018-19/16149,Electrical,Completed,L-Electrical,154,161500,"supply, Installation,Testing & Commissioning of 2Kwp grid solar Rooftop inclunding civil works and earthing at kambar salai kulakarai , Ramapuram ,Div-154.Zone-XI",SMART CITY - ELECTRICAL,11,2018-19,2019-20 NL/2018-19/0301,Parks,Completed,NL-VALASARAVAKKAM,154,72900,"Improvements and Maintainence of park at Kurinji nagar in DN-154, Unit-34, Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/10754,Buildings,Completed,NL-VALASARAVAKKAM,154,74000,"Repairs and Improvement and Color washing to the Existing Amma unavagam at Kambar salai in Dn-154,Unit 34, Zone11.",Own Sources,11,2018-19,2020-21 NL/2018-19/10789,Roads,Completed,NL-VALASARAVAKKAM,154,971000,"Improvements to interior BT roads at Venkateswara nagar 5th street and Venkateswara nagar 17th street in Dn - 154, U - 34, Z - XI.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/13185,Parks,Completed,NL-VALASARAVAKKAM,154,113000,"Maintenance for Park at Kurinji Nagar 3rd cross street (Total Area - 979.58 Sq.m) in Dn - 154, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13963,Roads,Completed,NL-VALASARAVAKKAM,154,249000,"Attending BT Patches at Various Streets in Dn - 154, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/14014,Buildings,Completed,NL-VALASARAVAKKAM,154,400000,"Construction of water sump and painting, Colour washing to the existing Division office at DN-154, Unit-34, Zone-11.",Own Sources,11,2018-19,2019-20 NL/2018-19/5566,Buildings,Completed,NL-VALASARAVAKKAM,154,285000,"Repair and Improvement at Gangai amman Koil Public Convenience in Dn-154, Unit-34, Zone-11",Own Sources,11,2018-19,2019-20 NL/2018-19/6135,Buildings,Completed,NL-VALASARAVAKKAM,154,99000,"Conversion and improvement in Kambar Salai Existing UPHC lab Room in Dn-154, Unit-34, Zone-11.",Own Sources,11,2018-19,2018-19 NL/2018-19/7057,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,364000,"Desilting of Side drain and Storm water drain at Various streets in DN-154, Unit-34, Zone-XI",Own Sources,11,2018-19,2018-19 NL/2018-19/7722,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,155000,"Repair and improvement Side drain and Strom water Drain at various street in Dn-154, Unit-34, Zone-11.",Own Sources,11,2018-19,2018-19 BR/2018-19/17288,Road Cut,Completed,BR-Bus Route Roads,155,93200,"Restoration of Roadcut made by OFC Providers at Various Interior Roads in Dn-155, Zone-XI",Deposit Works,11,2018-19,2019-20 BR/2018-19/4230,Roads,Completed,BR-Bus Route Roads,155,1200000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER (1 NO) AT RAMAVARAM (THIRUVALLUVAR SALAI MAIN ROAD TOWARDS NANDAMBAKKAM) IN DIV-155, ZONE-11. (UNDER M.P FUND) SIZE:( 9.00MX2.50M)",MPLADS,11,2018-19,2019-20 D/2018-19/8431,Storm Water Drain,Completed,D-Storm Water Drains,155,8761000,"Restoration and other improvement to Ramapuram Eri for augmentation of water supply in Dn-155,Zone -11.",SMART CITY - SWD,11,2018-19,2020-21 NL/2018-19/0019,Buildings,Completed,NL-VALASARAVAKKAM,155,976000,"Operation and Maintenance of high quality treated drinking water plant (RO/UV Filtration) at Bharathi Salai,(For 12 months), Div-155,U-34,Z-11",Own Sources,11,2018-19,2019-20 NL/2018-19/0237,Parks,Completed,NL-VALASARAVAKKAM,155,222000,"Providing water supply arrangements to KP nagar park and Jai Balaji nagar park in dn-155, unit-34, zone-11.",Own Sources,11,2018-19,2018-19 NL/2018-19/0451,Buildings,Completed,NL-VALASARAVAKKAM,155,556000,"Construction of compound wall at K.P Nagar Main road in Dn - 155, U - 34, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/0713,Parks,Completed,NL-VALASARAVAKKAM,155,188000,"Repairs and Improvements to park at Giri nagar in DN-155, Unit-34, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/10785,Roads,Completed,NL-VALASARAVAKKAM,155,1863000,"Improvements to interior BT roads at Karpagambal nagar 1st street, Karpagambal nagar 2nd street, Thamizh nagar 2nd main road, Vivekanandha nagar Harishankar street, Sriram nagar 4th street and Alagapuri Nagar 3rd Avenue in Dn - 155, U - 34, Z - XI.",Loans And Grants,11,2018-19,2020-21 NL/2018-19/12889,Playfields,Completed,NL-VALASARAVAKKAM,155,787000,"Providing Play apparatus and Electrical arrangements at Amman nagar OSR land (Survey no:68B) in DN-155, Unit-34, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13186,Parks,Completed,NL-VALASARAVAKKAM,155,114000,"Maintenance for Park at Eswaran Nagar (Total Area - 611.16 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13187,Parks,Completed,NL-VALASARAVAKKAM,155,115000,"Maintenance for Park at Giri Nagar (Total Area - 688.24 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13188,Parks,Completed,NL-VALASARAVAKKAM,155,109000,"Maintenance for Park at Jai Balaji Nagar (Total Area - 405.92 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13189,Parks,Completed,NL-VALASARAVAKKAM,155,206000,"Maintenance for Park at Azhagapuri Nagar (Total Area - 1052.64 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13190,Parks,Completed,NL-VALASARAVAKKAM,155,186000,"Maintenance for Park at K.P.Nagar (Total Area - 768.60 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/13559,Buildings,Completed,NL-VALASARAVAKKAM,155,93000,"Providing Ramp, Electrical and water supply arrangement proposed E-Toilet at Bharathi salai and Thiruvalluvar salai in DN-155, U-34, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/13874,Roads,Completed,NL-VALASARAVAKKAM,155,546000,"Attending BT Patches at Various Streets in Dn - 155, U-34, Z - XI.",Own Sources,11,2018-19,2019-20 NL/2018-19/15188,Playfields,Completed,NL-VALASARAVAKKAM,155,896000,"Providing Volley ball Court and Badminton court at KP Nagar Vacant land in DN-155, Unit-34, Zone-XI",Own Sources,11,2018-19,2020-21 NL/2018-19/15598,Electrical,Completed,NL-VALASARAVAKKAM,155,432700,"Removal of damaged lamp post, Conversation of Fitting and Connected works for various parks and play grounds in Division 154,155 in Zone XI",Own Sources,11,2018-19,2020-21 NL/2018-19/1834,Buildings,Completed,NL-VALASARAVAKKAM,155,282000,"Improvements to Anganwadi at Amman Nagar 1st Main Road in Dn - 155, U - 34, Z - XI.",Own Sources,11,2018-19,2018-19 NL/2018-19/5627,Roads,Completed,NL-VALASARAVAKKAM,155,73000,"Name board Repair works at Various streets in DN-155, Unit-34, Zone-XI",Own Sources,11,2018-19,2019-20 NL/2018-19/7023,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,186000,"Desilting of Storm water drain and Side drain at Various streets in DN-155, Unit-34, Zone-11",Own Sources,11,2018-19,2018-19 NL/2018-19/7060,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,261000,"Repairs to Storm water drains and Side drains at Various street in DN-155, Unit-34, Zone-XI",Own Sources,11,2018-19,2018-19 BR/2018-19/12867,Roads,Completed,BR-Bus Route Roads,156,2276000,"Roadcut Restoration made by CMWSSB at Mugalivakkam Main Road to Arasamaram in Dn-156, Zone-12 (From jn of manapakkam Main Road to Lalithambal nagar) L-500m",Deposit Works,12,2018-19,2019-20 BR/2018-19/14177,Roads,Completed,BR-Bus Route Roads,156,485000,REPAIRS AND REFIXING OF DAMAGED MODERN STAINLESS STEEL BUS SHELTER AT KUNDRATHUR MAIN ROAD MADANANTHAPURAM BUS STOP IN DIV-156 ZONE-12,Own Sources,12,2018-19,2019-20 BR/2018-19/15290,Roads,Completed,BR-Bus Route Roads,156,1246000,Roadcut Restoration made by OFC Providers at Various Bus Route Roads in Zone 12.,Deposit Works,12,2018-19,2020-21 D/2018-19/9756,Storm Water Drain,Completed,D-Storm Water Drains,156,18096000,Construction of Storm Water Drain at Blue Bell Street and 3 Other Roads in Zone - 12 - Package - 49,Grants,12,2018-19,2019-20 L/2018-19/11956,Electrical,Completed,L-Electrical,156,199500,"Proposal for fixing of 510 nos of LED Fittings & Removal of 510 nos of Sodium Fittings at various locations in Div 156, 157, Z-XII, Alandur",Own Sources,12,2018-19,2020-21 L/2018-19/16159,Electrical,Completed,L-Electrical,156,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Madanathapuram, Amma Unavagam in Div- 156, Zone- XII. (320-008-314)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16161,Electrical,Completed,L-Electrical,156,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Madananthapuram, ICDS Centre in Div- 156, Zone- XII. (320-008-381)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16164,Electrical,Completed,L-Electrical,156,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Padasalai Street, Public Health Centre in Div- 156, Zone- XII. (301-014-812)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16195,Electrical,Completed,L-Electrical,156,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Padasalai Street, Municipality School in Div- 156, Zone- XII. (301-009-1579)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/8938,Electrical,Completed,L-Electrical,156,960500,SHIFTING OF STREET LIGHT CABLE FOR SWD WORK AND RELAYING 2640MTR OF 2X16SQMM CABLE AT VARIOUS STREET IN DN156 ZONE 12,Deposit Works,12,2018-19,2019-20 NM/2018-19/10731,Buildings,Completed,NM-ALANDUR,156,217000,"IMPROVEMENT WORK AT AMMA UNAVAGAM AT NANDHAGOBAL RAJA STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/10734,Buildings,Completed,NM-ALANDUR,156,265000,"IMPROVEMENT WORK AT PC IN MUGALIVAKKAM MANAPAKKAM MAIN ROAD AND MADHANANDHAPURAM MAIN ROAD STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/11517,Roads,Completed,NM-ALANDUR,156,1140000,"ATTENDING PATCH WORK USING GSB,WMM AT VARIOUS STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/11962,Roads,Completed,NM-ALANDUR,156,287000,"ATTENDING CC PATCH WORK AT MICRO MARVELL 1ST CROSS STREET IN DN-157,U-35,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/12890,Buildings,Completed,NM-ALANDUR,156,215000,"IMPROVEMENT WORK TO DIVISION OFFICE BUILDING AT PADASALAI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/12988,Storm Water Drain,Completed,NM-ALANDUR,156,1030000,"IMPROVEMENT WORK TO SWD AT MANGAIYARKARASI STREET,SRIRAMULU STREET,NANDHAGOBALRAJA STREET,MARIAMMAN KOIL STREET,PADASALAI STREET,MUTHUMARIAMMAN NAGAR LAKSHMI GARDEN ,MANI STREET AND SEKAR AVENUE IN DN -156.U-35.Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/14606,Roads,Completed,NM-ALANDUR,156,37000,"REPAIRS AND MAINTENANCE OF STREET NAME BOARDS AT VARIOUS STREETS IN DN-156,U-35,ZN-12","Loans, Grants And Own Sources",12,2018-19,2020-21 NM/2018-19/14741,Buildings,Completed,NM-ALANDUR,156,204000,"IMPROVEMENT WORKS TO UPHC AT PADASALAI STREET IN DN-156 U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15446,Parks,Completed,NM-ALANDUR,156,218000,"ANNUAL MAINTENANCE OF PARK AT MARY GOLD STREET PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15447,Parks,Completed,NM-ALANDUR,156,195400,"ANNUAL MAINTENANCE OF PARK AT AGS COLONY SABARI NAGAR 2ND MAIN ROAD PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15448,Parks,Completed,NM-ALANDUR,156,265000,"ANNUAL MAINTENANCE OF PARK AT VND RAJESWARI AVENUE VAIGAI STREET PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15449,Parks,Completed,NM-ALANDUR,156,184000,"ANNUAL MAINTENANCE OF PARK AT SSL GREEN PARK MADHANANDHAPURAM MAIN ROAD PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15450,Parks,Completed,NM-ALANDUR,156,222000,"ANNUAL MAINTENANCE OF PARK AT ANNAIVELANKANNI NAGAE PH-1 1ST STREET PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15451,Parks,Completed,NM-ALANDUR,156,247000,"ANNUAL MAINTENANCE OF PARK AT ANNAIVELANKANNI NAGAE PH-1 5TH STREET PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15452,Parks,Completed,NM-ALANDUR,156,399000,"ANNUAL MAINTENANCE OF PARK AT MADHA NAGAR 2ND MAIN ROAD PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15453,Parks,Completed,NM-ALANDUR,156,218000,"ANNUAL MAINTENANCE OF PARK AT GURUSAMY NAGAR DEVADAS STREET PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15454,Parks,Completed,NM-ALANDUR,156,244000,"ANNUAL MAINTENANCE OF PARK AT VND RAJESWARI AVENUE SINDHU SALAI PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15456,Parks,Completed,NM-ALANDUR,156,450000,"ANNUAL MAINTENANCE OF PARK AT CRR PURAM L&T COLONY PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15457,Parks,Completed,NM-ALANDUR,156,499900,"ANNUAL MAINTENANCE OF PARK AT AGS COLONY PH-III PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15458,Parks,Completed,NM-ALANDUR,156,398000,"ANNUAL MAINTENANCE OF PARK AT THIRUVALLUVAR NAGAR NATHAMUNI STREET PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15460,Parks,Completed,NM-ALANDUR,156,105000,"ANNUAL MAINTENANCE OF PARK AT KUNDRATHUR MAIN ROAD PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15461,Parks,Completed,NM-ALANDUR,156,105000,"ANNUAL MAINTENANCE OF PARK AT VGN LAKSHMI NAGAR VISWANATHAN PALANI PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15462,Parks,Completed,NM-ALANDUR,156,122000,"ANNUAL MAINTENANCE OF PARK AT SABARI NAGAR 1ST MAIN ROAD PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17434,Parks,Completed,NM-ALANDUR,156,385000,"ANNUAL MAINTENANCE OF PARK AT KUMUTHAM NAGAR PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17435,Parks,Completed,NM-ALANDUR,156,342000,"ANNUAL MAINTENANCE OF PARK AT VGN LAKSHMI NAGAR KALAIMAGAL PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17436,Parks,Completed,NM-ALANDUR,156,79000,"ANNUAL MAINTENANCE OF PARK AT SABRI NAGAR 5TH STREET PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17530,Roads,Completed,NM-ALANDUR,156,1244000,"FORMATION AND STRENGTHENING BT ROAD ATRAMYA NGAR AMBEDKAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17531,Roads,Completed,NM-ALANDUR,156,1285000,"FORMATION AND STRENGTHENING BT ROAD AT SANTHOASH NAGAR RUKUMANI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17532,Roads,Completed,NM-ALANDUR,156,1173000,"FORMATION AND STRENGTHENING BT ROAD AT VINAYAGAPURAM IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17533,Roads,Completed,NM-ALANDUR,156,454000,"FORMATION AND STRENGTHENING BT ROAD AT SS KOIL EXTN IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17534,Roads,Completed,NM-ALANDUR,156,2163000,"FORMATION AND STRENGTHENING BT ROAD AT SS KOIL STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17535,Roads,Completed,NM-ALANDUR,156,478000,"FORMATION AND STRENGTHENING BT ROAD ATSRI LAKSHMI NAGAR 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17536,Roads,Completed,NM-ALANDUR,156,479000,"FORMATION AND STRENGTHENING BT ROAD ATSRI LAKSHMI NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17537,Roads,Completed,NM-ALANDUR,156,845000,"FORMATION AND STRENGTHENING BT ROAD ATSRI LAKSHMI NAGAR MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17538,Roads,Completed,NM-ALANDUR,156,2210000,"FORMATION AND STRENGTHENING BT ROAD AT SUBHASRI NAGAR EXTN 4 IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17539,Roads,Completed,NM-ALANDUR,156,991000,"RELAYING BT ROAD AT ANANDHA NAGAR IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17540,Roads,Completed,NM-ALANDUR,156,352000,"FORMATION AND STRENGTHENING BT ROAD AT PADMAVATHI CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17541,Roads,Completed,NM-ALANDUR,156,2620000,"FORMATION AND STRENGTHENING BT ROAD AT PADMAVATHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17542,Roads,Completed,NM-ALANDUR,156,4218000,"FORMATION AND STRENGTHENING BT ROAD AT BANGALATHOBHU BAJANAI KOIL STREET (9ROADS) IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17543,Roads,Completed,NM-ALANDUR,156,1133000,"FORMATION AND STRENGTHENING BT ROAD AT BANGALATHOBHU BAJANAI KOIL STREET MAIN ROAD IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17544,Roads,Completed,NM-ALANDUR,156,457000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN NEHRU STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17545,Roads,Completed,NM-ALANDUR,156,348000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN VIVEKANDHA STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17546,Roads,Completed,NM-ALANDUR,156,540000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN VOC STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17547,Roads,Completed,NM-ALANDUR,156,674000,"FORMATION AND STRENGTHENING BT ROAD AT PAGAVATHI AVENUE IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17548,Roads,Completed,NM-ALANDUR,156,881000,"FORMATION AND STRENGTHENING BT ROAD AT RAMAMOORTHY AVENUE EXTN IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17549,Roads,Completed,NM-ALANDUR,156,861000,"FORMATION AND STRENGTHENING BT ROAD AT SAROJINI STREET 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17550,Roads,Completed,NM-ALANDUR,156,539000,"FORMATION AND STRENGTHENING BT ROAD AT SAROJINI STREET 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17551,Roads,Completed,NM-ALANDUR,156,920000,"FORMATION AND STRENGTHENING BT ROAD AT VGNLAKSHMI NAGAR RAGUPATHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17552,Roads,Completed,NM-ALANDUR,156,3435000,"FORMATION AND STRENGTHENING BT ROAD AT VGNLAKSHMI NAGAR KALAIMAGAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17553,Roads,Completed,NM-ALANDUR,156,1162000,"FORMATION AND STRENGTHENING BT ROAD AT MUTHU NAGAR 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17554,Roads,Completed,NM-ALANDUR,156,630000,"FORMATION AND STRENGTHENING BT ROAD AT MUTHU NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17555,Roads,Completed,NM-ALANDUR,156,740000,"FORMATION AND STRENGTHENING BT ROAD AT RAJESWARI AVENUE YAMUNA STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17556,Roads,Completed,NM-ALANDUR,156,1177000,"FORMATION AND STRENGTHENING BT ROAD AT RAJESWARI AVENUE KOTHAVARI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17557,Roads,Completed,NM-ALANDUR,156,629000,"FORMATION AND STRENGTHENING BT ROAD AT RAJESWARI AVENUE PONNI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17558,Roads,Completed,NM-ALANDUR,156,1081000,"FORMATION AND STRENGTHENING BT ROAD AT RAJESWARI AVENUE NARMATHA STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17559,Roads,Completed,NM-ALANDUR,156,1385000,"FORMATION AND STRENGTHENING BT ROAD AT KUMUTHAM NAGAR 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17560,Roads,Completed,NM-ALANDUR,156,835000,"FORMATION AND STRENGTHENING BT ROAD AT LALITHAMBAL NAGAR LALITH AVENUE IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17561,Roads,Completed,NM-ALANDUR,156,543000,"FORMATION AND STRENGTHENING BT ROAD AT GOWRI NAGAR 4TH STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17562,Roads,Completed,NM-ALANDUR,156,1187000,"FORMATION AND STRENGTHENING BT ROAD AT GOWRI NAGAR 3RD STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17563,Roads,Completed,NM-ALANDUR,156,1488000,"FORMATION AND STRENGTHENING BT ROAD AT GOWRI NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17564,Roads,Completed,NM-ALANDUR,156,794000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR AMMA BAKIYAM STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17565,Roads,Completed,NM-ALANDUR,156,1216000,"FORMATION AND STRENGTHENING BT ROAD AT KUMUTHAM NAGAR 4TH STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17566,Roads,Completed,NM-ALANDUR,156,1092000,"FORMATION AND STRENGTHENING BT ROAD AT KUMUTHAM NAGAR 3RD STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17567,Roads,Completed,NM-ALANDUR,156,564000,"FORMATION AND STRENGTHENING BT ROAD AT RAMAMOORTHY AVENUE SUBHULAKSHMI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17568,Roads,Completed,NM-ALANDUR,156,313000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR MANIKKAM STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17569,Roads,Completed,NM-ALANDUR,156,383000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR KULASEKARAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17570,Roads,Completed,NM-ALANDUR,156,801009,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN SUNFLOWER STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17571,Roads,Completed,NM-ALANDUR,156,1637000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN ORCHIT STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17572,Roads,Completed,NM-ALANDUR,156,515000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN MARYGOLD STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17573,Roads,Completed,NM-ALANDUR,156,419000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN LOTUS STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17574,Roads,Completed,NM-ALANDUR,156,995000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN JASMIN STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17575,Roads,Completed,NM-ALANDUR,156,617000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN DHULIP STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17576,Roads,Completed,NM-ALANDUR,156,496009,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN DAFODIL STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17577,Roads,Completed,NM-ALANDUR,156,539000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN BLUEBELL STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17578,Roads,Completed,NM-ALANDUR,156,3403000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN BLACKBERRY STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17579,Roads,Completed,NM-ALANDUR,156,746000,"FORMATION AND STRENGTHENING BT ROAD AT BLOOMING GARDEN ASTROS STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17580,Roads,Completed,NM-ALANDUR,156,819000,"FORMATION AND STRENGTHENING BT ROAD ATGURUSAMY NAGAR EXTN KAMARAJAR SALAI IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17581,Roads,Completed,NM-ALANDUR,156,2215000,"FORMATION AND STRENGTHENING BT ROAD ATGURUSAMY NAGAR EXTN INDRAGANDHI SALAI IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17582,Roads,Completed,NM-ALANDUR,156,452000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN GANDHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17583,Roads,Completed,NM-ALANDUR,156,580000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN KAMARAJAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17584,Roads,Completed,NM-ALANDUR,156,722000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN BHARATHIYAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17585,Roads,Completed,NM-ALANDUR,156,352000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN KALKI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17586,Roads,Completed,NM-ALANDUR,156,452000,"FORMATION AND STRENGTHENING BT ROAD AT SELVALAKSHMI GARDEN NETHAJI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17587,Roads,Completed,NM-ALANDUR,156,2286000,"FORMATION AND STRENGTHENING BT ROAD AT VGN LAKSHMI NAGAR SARSWATHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17588,Roads,Completed,NM-ALANDUR,156,2008000,"FORMATION AND STRENGTHENING BT ROAD AT VGN LAKSHMI NAGAR VISWANATHAN PALANI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17589,Roads,Completed,NM-ALANDUR,156,771000,"FORMATION AND STRENGTHENING BT ROAD AT VGN LAKSHMI NAGAR SUBARAMANI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17590,Roads,Completed,NM-ALANDUR,156,1006000,"FORMATION AND STRENGTHENING BT ROAD AT VGN LAKSHMI NAGAR ARUNAGIRI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17591,Roads,Completed,NM-ALANDUR,156,1301000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR NAVANEETHAM STREET STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17592,Roads,Completed,NM-ALANDUR,156,485000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR GNANA PRAGASAM STREET STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17593,Roads,Completed,NM-ALANDUR,156,651000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR BALAKRISHNA STREET STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17594,Roads,Completed,NM-ALANDUR,156,502000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR THIRUPATHI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17595,Roads,Completed,NM-ALANDUR,156,242000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR MARAGATHAM STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17596,Roads,Completed,NM-ALANDUR,156,1511000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR MURUGESANAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17597,Roads,Completed,NM-ALANDUR,156,597000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR SUBARAMANI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17598,Roads,Completed,NM-ALANDUR,156,352000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR GOVINDHARAJ STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17599,Roads,Completed,NM-ALANDUR,156,574000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR PAPATHIAMMAL STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17600,Roads,Completed,NM-ALANDUR,156,422000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR PACHIAPPAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17601,Roads,Completed,NM-ALANDUR,156,704000,"FORMATION AND STRENGTHENING BT ROAD AT THIRUVALLUVAR NAGAR ARUNAGIRI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17602,Roads,Completed,NM-ALANDUR,156,810000,"FORMATION AND STRENGTHENING BT ROAD AT KUMUTHAM NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/17950,Roads,Completed,NM-ALANDUR,156,690000,"ROAD CUT RESTORATION OF ANNAIVELANKANNI NAGAR PH-2 1T STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17951,Roads,Completed,NM-ALANDUR,156,856000,"ROAD CUT RESTORATION OF ANNAIVELANKANNI NAGAR PH-2 2ND STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17952,Roads,Completed,NM-ALANDUR,156,552000,"ROAD CUT RESTORATION OF ANNAIVELANKANNI NAGAR PH-2 3RD STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17953,Roads,Completed,NM-ALANDUR,156,323000,"ROAD CUT RESTORATION OF ANNAIVELANKANNI NAGAR PH-2 4TH STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17954,Roads,Completed,NM-ALANDUR,156,296000,"ROAD CUT RESTORATION OF ANNAIVELANKANNI NAGAR PH-2 5TH STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17955,Roads,Completed,NM-ALANDUR,156,237000,"ROAD CUT RESTORATION OF ANNAIVELANKANNI NAGAR PH-2 6TH STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17956,Roads,Completed,NM-ALANDUR,156,351000,"ROAD CUT RESTORATION OF GURUSAMY NAGAR SAMPATH STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17957,Roads,Completed,NM-ALANDUR,156,1049000,"ROAD CUT RESTORATION OF KARTHICK BALAJI NAGAR IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17958,Roads,Completed,NM-ALANDUR,156,710000,"ROAD CUT RESTORATION OF KUMUTHAM NAGAR 5TH STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17959,Roads,Completed,NM-ALANDUR,156,868000,"ROAD CUT RESTORATION OF KUMUTHAM NAGAR EXTN IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17960,Roads,Completed,NM-ALANDUR,156,385000,"ROAD CUT RESTORATION OF KUMUTHAM NAGAR PASUPATHI STREET IN DN 156,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/2414,Roads,Completed,NM-ALANDUR,156,1800000,"SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DN-156,U-35,ZN-12",Own Sources,12,2018-19,2019-20 NM/2018-19/2442,Roads,Completed,NM-ALANDUR,156,2170000,"PROVIDING SPEED BREAKERS AT VARIOUS STREETS IN DIV 156, U 35, ZN 12",Own Sources,12,2018-19,2019-20 NM/2018-19/4184,Electrical,Completed,NM-ALANDUR,156,651000,"Rewiring in chennai corporation primary healthcenter in padasalai street muglivakkam dn-156, Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/6231,Parks,Completed,NM-ALANDUR,156,259000,"Improvement work of santhosh nagar ramchandran street park in Dn-156,U-35,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/6449,Electrical,Completed,NM-ALANDUR,156,648400,LAYING OF 1048MTR OF 2X16SQMM CABLE AND ERECTION OF 8NOS OF 6MTR POST ST BRACKET WITH 40-50W LED FITTINGS AT THIRUVALLUVAR NAGAR NATHAMUNISTREET PARK IN DN-156 ZONE XII,Own Sources,12,2018-19,2018-19 NM/2018-19/7077,Buildings,Completed,NM-ALANDUR,156,199000,"CONSTRUCTION OF BABY TOILET IN ANGANVADI AT PADASALAI STREET IN DN-156,UNIT-35,ZONE-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/8633,Buildings,Completed,NM-ALANDUR,156,1375000,"CONSTRUCTION OF COMPOUND WALL OSR LAND AT RAMAMOORTHY AVENUE EXTN SAROJINI STREET IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9260,Buildings,Completed,NM-ALANDUR,156,2917000,"CONSTRUCTION OF COMPOST YARD INCLUDING WATER FACILITY ,SUPPLYING AND ERECTION OF BIO-SHREDDING PULVERIZED MACHINE,MANURE SEIVER MACHINE AND WEIGHING MACHINE AT OTHAVADAI STREET BURIAL GROUND IN DN-156,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9782,Road Cut,Completed,NM-ALANDUR,156,713000,"Desilting and Repair work to Storm water drain and side drain at various street a in Din-156,Unit-35, Zone-12",Own Sources,12,2018-19,2018-19 BR/2018-19/15679,Road Cut,Completed,BR-Bus Route Roads,157,1007000,Restoration of OFC road cut made by AIrtel at various Bus Route Roads in Zone-x (Deposit Code-57/0288/2018-19),Deposit Works,12,2018-19,2019-20 BR/2018-19/15681,Road Cut,Completed,BR-Bus Route Roads,157,370000,Restoration of OFC road cut made by Reliance at various Bus Route Roads in Zone-X (Deposit Code-57/0338/2018-19),Deposit Works,12,2018-19,2019-20 BR/2018-19/17893,Road Cut,Completed,BR-Bus Route Roads,157,286000,"RESTORATION OF OFC ROAD CUT MADE BY RELAINCE IN VARIOUS IRR ROADS IN DIV- 157,UNIT-35, ZONE-12 (DEPOSIT CODE-57/0026/2018-19)",Deposit Works,12,2018-19,2019-20 L/2018-19/10796,Electrical,Completed,L-Electrical,157,1583000,"Supply and Erection of 8 Nos of 8mtr Octogonal StreetLamp post with 150-165W LED Fittings and Replacement of 956 Mtrof damaged 4x16sq mm cable at Paul Wills Road and Mount Poonamallee Road in Div -158, and Painting of 334 Nos of Old 9.2 mtr Street lamp posts at Paul wills road, Butt road, Mount Poonamallee road, Manapakkam main road, M.G.Salai and Anna nagar main road at Div-157 and 158, Z-XII .GIM Work (Sch of rate 2017-18)",Own Sources,12,2018-19,2019-20 L/2018-19/11958,Electrical,Completed,L-Electrical,157,199500,"Proposal for fixing of 510 nos of LED Fittings & Removal of 510 nos of Sodium Fittings at various locations in Div 157,158 Z-XII, Alandur",Own Sources,12,2018-19,2020-21 L/2018-19/16226,Electrical,Completed,L-Electrical,157,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office, Manapakkam in Div 157, Zone-12 .service no -322.001.1300",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16228,Electrical,Completed,L-Electrical,157,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Library at manabakkam in Div 157, Zone-12 .service no 322.001.1021.",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16229,Electrical,Completed,L-Electrical,157,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at mettu street in Div 157, Zone-12 .service no -322.001.503",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16230,Electrical,Completed,L-Electrical,157,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at pp Board back side, Manapakkam in Div 157, Zone-12 .service no -322.001.942",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16231,Electrical,Completed,L-Electrical,157,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at div office mettu street, manapakkam, .service no 322.001.940",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16233,Electrical,Completed,L-Electrical,157,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at amma unavagam, mg salai, bell nagar, Manapakkam in Div 157, Zone-12 .service no 261.033.739",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16234,Electrical,Completed,L-Electrical,157,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at V.A.O Office, Manapakkam in Div 157, Zone-12 .service no -322.001.938",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/10937,Buildings,Completed,NM-ALANDUR,157,215000,"IMPROVEMENT WORKS TO EXISTING SHOPPING COMPLEX AT MG SALAI IN DN-157,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/11070,Buildings,Completed,NM-ALANDUR,157,44000,"REPAIR AND MAINTENANCE AMMAUNAVAGAM AT VALLESWARAN KOIL STREET IN DN-157,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/15786,Parks,Completed,NM-ALANDUR,157,252000,ANNUAL MAINTENANCE OF PARK AT RIVER VIEW COLONY PHASE 2 (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN 157,Own Sources,12,2018-19,2019-20 NM/2018-19/15788,Parks,Completed,NM-ALANDUR,157,265000,ANNUAL MAINTENANCE OF PARK AT RIVER VIEW COLONY PHASE 1 (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN 157,Own Sources,12,2018-19,2019-20 NM/2018-19/15789,Parks,Completed,NM-ALANDUR,157,234000,ANNUAL MAINTENANCE OF PARK AT BHEL NAGAR (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN 157,Own Sources,12,2018-19,2019-20 NM/2018-19/16107,Parks,Completed,NM-ALANDUR,157,159000,ANNUAL MAINTENANCE OF PARK AT KAVYA GARDEN (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN 157(1500SQ.M),Own Sources,12,2018-19,2019-20 NM/2018-19/16108,Parks,Completed,NM-ALANDUR,157,118000,ANNUAL MAINTENANCE ESTIMATE FOR PARK AT MANAPAKKAM ARCOT SALAI PARK (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN 157 (1431SQM),Own Sources,12,2018-19,2019-20 NM/2018-19/16109,Parks,Completed,NM-ALANDUR,157,255000,ANNUAL MAINTENANCE OF PARK AT MACRO MARVEL RIVER VIEW COUNTY (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN 157 AREA 2064 SQM,Own Sources,12,2018-19,2019-20 NM/2018-19/16110,Parks,Completed,NM-ALANDUR,157,118000,ANNUAL MAINTENANCE OF PARK AT RIVER VIEW COLONY (PERIOD OF 7 MONTHS FROM 01.09.2018 TO 31.03.2019) IN DN 157 AREA 1710 SQM.,Own Sources,12,2018-19,2019-20 NM/2018-19/2151,Buildings,Completed,NM-ALANDUR,157,1080000,"SUPPLYING AND FIXING OF STREET NAME BOARDS USING STAINLESS STEEL PIPE AND RETRO REFLECTIVE SHEETS AT VARIOUS STREETS IN DN-157,U-35,ZN-12",Own Sources,12,2018-19,2019-20 NM/2018-19/2862,Buildings,Completed,NM-ALANDUR,157,696000,"Providing Speed Breakers as per IRC design at CRR Puram and Bell Nagar in Div-157, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/4772,Roads,Completed,NM-ALANDUR,157,267000,"FORMING AND RELAYING THE EXISTING BT ROAD AT RIVER VIEW COLONY VAIGAI STREET IN DN -157, UNIT-35,ZONE-12",Own Sources,12,2018-19,2018-19 NM/2018-19/5235,Roads,Completed,NM-ALANDUR,157,154000,"Repair and improvements of Anganvadi at sub heath centre road (ICDS-1) in div -157, unit-35,zone-12",Own Sources,12,2018-19,2018-19 NM/2018-19/9783,Storm Water Drain,Completed,NM-ALANDUR,157,260000,"Desilting and Repair work to Storm water drain and side drain at various street a in Din-157,Unit-35, Zone-12",Own Sources,12,2018-19,2018-19 NM/2018-19/9949,Buildings,Completed,NM-ALANDUR,157,38700,PROVIDING BARRIGADING WORK AT ADYAR RIVER IN DIVISION -157 UNIT-35 ZONE-12,Own Sources,12,2018-19,2018-19 L/2018-19/16223,Electrical,Completed,L-Electrical,158,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Unavagam, Nandampakkam in Div 158, Zone-12.(EB Account No: 242.052.938)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16225,Electrical,Completed,L-Electrical,158,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Gym East lake view street, Nandampakkam in Div 158, Zone-12 ((EB Account No: 242.052.938).",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/11044,Buildings,Completed,NM-ALANDUR,158,60000,"Improvement works to Amma Unavagam at Bajanai koil street in Div-158, U-35, Zn-12",Own Sources,12,2018-19,2020-21 NM/2018-19/12821,Storm Water Drain,Completed,BR-Bus Route Roads,158,1500000,"Supplying and Fixing RCC Circular pipe for drain at IDPL Parking area in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/12822,Parks,Completed,BR-Bus Route Roads,158,1200000,"Renovationn work of auditorium and Traffic Islands in IDPL in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13763,Roads,Completed,BR-Bus Route Roads,158,22000,"Cutting and clearing heavy jungle at Vinayagar temple near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13764,Roads,Completed,BR-Bus Route Roads,158,67500,"Cutting and clearing heavy jungle at Auditorium near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13765,Roads,Completed,BR-Bus Route Roads,158,16100,"Cutting and clearing heavy jungle at Behind police station near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13766,Roads,Completed,BR-Bus Route Roads,158,10900,"Cutting and clearing heavy jungle at At Ration shop near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13767,Roads,Completed,BR-Bus Route Roads,158,136300,"Cutting and clearing heavy jungle at IDPL School Adjacent near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13769,Roads,Completed,BR-Bus Route Roads,158,41100,"Cutting and clearing heavy jungle at Registration Counter near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13770,Roads,Completed,BR-Bus Route Roads,158,146900,"Cutting and clearing heavy jungle at At IDPL Filling point near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13771,Roads,Completed,BR-Bus Route Roads,158,344600,"Cutting and clearing heavy jungle at At Tele-Matrix near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13772,Roads,Completed,BR-Bus Route Roads,158,141000,"Cutting and clearing heavy jungle at Behind Vembuliamman Koil near Chennai Trade Centre in Dn- 158, U-35,Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13774,Roads,Completed,BR-Bus Route Roads,158,2776000,"Laying and spreading wet mix macadam for parking area at At Vinayaga temple in Dn-158, U-35, Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13775,Roads,Completed,BR-Bus Route Roads,158,3572000,"Laying and spreading wet mix macadam for parking area at Auditorium in Dn-158, U-35, Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13776,Roads,Completed,BR-Bus Route Roads,158,852000,"Laying and spreading wet mix macadam for parking area Behind police station in Dn-158, U-35, Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13777,Roads,Completed,BR-Bus Route Roads,158,575000,"Laying and spreading wet mix macadam for parking area at Ration shop in Dn-158, U-35, Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13778,Roads,Completed,BR-Bus Route Roads,158,5182000,"Laying and spreading wet mix macadam for parking area at Registration counter in Dn-158, U-35, Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13779,Roads,Completed,BR-Bus Route Roads,158,22638000,"Laying and spreading wet mix macadam for parking area at At IDPL Pump house in Dn-158, U-35, Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13780,Roads,Completed,BR-Bus Route Roads,158,21732000,"Laying and spreading wet mix macadam for parking area Behind Vembuliamman Koil in Dn-158, U-35, Zn-12",Own Sources,12,2018-19,2019-20 NM/2018-19/14081,Roads,Completed,BR-Bus Route Roads,158,978000,"Relaying and strengthening of BT road by using paver finisher at IDPL 2nd Avenue in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/14082,Roads,Completed,BR-Bus Route Roads,158,1051000,"Relaying and strengthening of BT road by using paver finisher at IDPL 3rd Avenue in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/14084,Roads,Completed,BR-Bus Route Roads,158,1773000,"Relaying and strengthening of BT road by using paver finisher at IDPL School road in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/14085,Roads,Completed,BR-Bus Route Roads,158,394000,"Relaying and strengthening of BT road by using paver finisher at CTC Entry gate-1 to IDPL 2nd main road in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/14086,Roads,Completed,BR-Bus Route Roads,158,394000,"Relaying and strengthening of BT road by using paver finisher at CTC Entry gate-2 to IDPL 2nd main road in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/14087,Roads,Completed,BR-Bus Route Roads,158,641000,"Relaying and strengthening of BT road by using paver finisher at IDPL Pump house road in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15479,Roads,Completed,BR-Bus Route Roads,158,914000,"Relaying and strengthening of BT road by using paver finisher at IDPL 1st Avenue in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/16170,Parks,Completed,NM-ALANDUR,158,105000,ANNUAL MAINTENANCE OF PARK AT SUNDAR NAGAR IN DN 158(01.09.2018 TO 31.03.2019 =7MONTHS),Own Sources,12,2018-19,2019-20 NM/2018-19/16206,Electrical,Completed,BR-Bus Route Roads,158,1325600,"Provision of temporary lighting and other necessary works including PA system for car park area at IDPL grounds for global investors meet at Chennai Trade Centre, Div-158, Z-XII in the month of January 2019.",Own Sources,12,2018-19,2019-20 NM/2018-19/17646,Roads,Completed,NM-ALANDUR,158,690000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 2ND MAIN ROAD IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17647,Roads,Completed,NM-ALANDUR,158,71000,"RELAYING THE EXISTING OF BT ROAD AT WOOD CREEK COUNTY 1ST CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17652,Roads,Completed,NM-ALANDUR,158,142000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 6TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17653,Roads,Completed,NM-ALANDUR,158,156000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 7TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17654,Roads,Completed,NM-ALANDUR,158,142000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 8TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17655,Roads,Completed,NM-ALANDUR,158,243000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 9TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17656,Roads,Completed,NM-ALANDUR,158,94000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 10TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17657,Roads,Completed,NM-ALANDUR,158,82000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 11TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17658,Roads,Completed,NM-ALANDUR,158,77000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 12TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17659,Roads,Completed,NM-ALANDUR,158,72000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 13TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17660,Roads,Completed,NM-ALANDUR,158,75000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 14TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17661,Roads,Completed,NM-ALANDUR,158,227000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 15TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17662,Roads,Completed,NM-ALANDUR,158,1710000,"FORMATION OF GRANULAR SUB BASE AND WET MIOX MACADAM AT THULASINGAPURAM BURIAL GROUND ROAD IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/8963,Buildings,Completed,NM-ALANDUR,158,90000,"Improvement works to Shopping Complex at east lakeview street in Dn-158, Unit-35, Zone-12",Own Sources,12,2018-19,2018-19 NM/2018-19/8968,Road Cut,Completed,NM-ALANDUR,158,263000,ROAD CUT RESTORATION SUNDAR NAGAR 7TH CROSS STREET(LEFT SIDE) IN DIVISION 158 UNIT-35 ZONE 12,Deposit Works,12,2018-19,2019-20 NM/2018-19/9019,Roads,Completed,NM-ALANDUR,158,263000,ROAD CUT RESTORATION SUNDAR NAGAR 7TH CROSS STREET(RIGHT SIDE) IN DIVISION 158 UNIT-35 ZONE 12,Deposit Works,12,2018-19,2019-20 NM/2018-19/9625,Buildings,Completed,NM-ALANDUR,158,448500,"SUPPLYING AND ERECTION OF BIO-SHREDDING PULVERIZER MACHINE, MANURE SEIVER MACHINE AND WEIGHING MACHINE INCLUDING CIVIL AND ELECTRICAL WORK AT MGR NAGAR COMPOSED YARD IN DN 158 U.35 Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9786,Storm Water Drain,Completed,NM-ALANDUR,158,232000,"DESILTING AT VARIOUS STREET IN DN-158, UNIT-35, ZONE-12",Own Sources,12,2018-19,2018-19 L/2018-19/10707,Electrical,Completed,L-Electrical,159,2496000,PROVISION OF 16 NOS OF 8 MTR.OCT STREET LAMP POST WITH SINGLE BRACKET WITH Hot dip zinc galvanising AND 6 NOS 6 MTR LAMP POST WITH Hot dip zinc galvanising AND 22 NOS OF LED street light fitting of 150W-165W wi...for automated group street light monitoring system AND 748 MTR OF 4X16 SQ MM CABLE AT GST ROAD NEAR POLICE STATION SIGNAL TO AMMA VUNAVAGAM MEENAMBAKKAM SIDE IN DN 159 ZONE 12,Own Sources,12,2018-19,2019-20 L/2018-19/10709,Electrical,Completed,L-Electrical,159,2451800,"PROVISION OF 20 NOS OF 8 MTR Oct STREET LAMP POST WITH SINGLE BRACKET WITH Hot dip zinc galvanising ,AND 20 NOS OF LED street light fitting of 150W-165W wi...for automated group street light monitoring system AND 557 MTR OF 4X16 SQ MM CABLE AT GST ROAD NEAR ASHARKHANA TO OTA SIDE(PAET 2) IN DN 159 ZONE 12(GIM 2019 work)Schedule of Rate 2017-18",Own Sources,12,2018-19,2019-20 L/2018-19/10710,Electrical,Completed,L-Electrical,159,1125400,REPLACEMENT OF 1834 MTR OF 4X16 SQ MM CABLE AND 30 NOS OF 2 MTR LONG G.I. SINGLE STRAIGHT BRACKET WITH EPOXY PRIMER AT GST ROAD NEAR ASHARKHANA SIDE AND TRISULAM SIDE IN DN 159 ZONE 12(GIM2019 WORK)SCHEDULE OF RATE 2017-18,Own Sources,12,2018-19,2019-20 L/2018-19/10906,Electrical,Completed,L-Electrical,159,1474000,PAINTING OF 193 NOS LAMP POST AND PROVISION OF 3 NOS OF 9.5 MTR STREET LAMP POST WITH 2.5 MTR ARCH SINGLE BRACKET WITH HOT DIP ZINC GALVANISING AND 3 NOS OF LED STREET LIGHT FITTING OF 150W-165W wi..for automated light monitoring system and REPLACEMENT OF 904 MTR OF 4X16 SQ MM CABLE AT GST ROAD VARIOUS LOCATIONS IN DN 159 ZONE 12,Own Sources,12,2018-19,2019-20 L/2018-19/11954,Electrical,Completed,L-Electrical,159,199500,"Proposal for fixing of 510 nos of LED Fittings & Removal of 510 nos of Sodium Fittings at various locations in Div 159, 161, 162, Z-XII, Alandur",Own Sources,12,2018-19,2020-21 L/2018-19/12323,Electrical,Completed,L-Electrical,159,2448200,"PROVISION OF 15 NOS OF 8 MTR Oct STREET LAMP POST WITH SINGLE BRACKET WITH Hot dip zinc galvanising ,AND 8 NOS OF 6MTR LAMP POST WITH SINGLE ARCH BRACKET AND 23 NOS OF LED street light fitting of 150W-165W wi...for automated group street light monitoring system AND 661 MTR OF 4X16 SQ MM CABLE AT GST ROAD NEAR ASHARKHANA TO OTA SIDE(PART 1) IN DN 159 ZONE 12(GIM 2019 work)Schedule of Rate 2017-18",Own Sources,12,2018-19,2019-20 L/2018-19/12329,Electrical,Completed,L-Electrical,159,2486000,PROVISION OF 20 NOS OF 8 MTR.OCT STREET LAMP POST WITH SINGLE BRACKET WITH Hot dip zinc galvanising AND 20 NOS OF LED street light fitting of 150W-165W wi...for automated group street light monitoring system AND 557 MTR OF 4X16 SQ MM CABLE AT GST ROAD NEAR AMMA VUNAVAGAM TO AIRPORT MEENAMBAKKAM SIDE IN DN 159 ZONE 12,Own Sources,12,2018-19,2019-20 L/2018-19/15472,Electrical,Completed,L-Electrical,159,189000,"Supply and Fixing of GATE LIGHT FITTING with 12W LED lamp with 5 mtrs of 2.5 Sq.mm copper wire for fixing in the existing short posts in GST Road from OTA to VIP Gate, Div 159, Z-XII.",Own Sources,12,2018-19,2019-20 L/2018-19/16181,Electrical,Completed,L-Electrical,159,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kamaraj street Gym in Division 159, Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16182,Electrical,Completed,L-Electrical,159,311900,"Supply, Installation, Testing & Commissioning of 1 No of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Panchayat Office, Meenambakkam Amma Vunavagam DN 159, ZONE 12 EB 241.038.1093",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/4126,Electrical,Completed,L-Electrical,159,442600,Replacemen of Dameged 729 mtr of 4x16 sqmm cable and painting of 72 nos of lamp post and clamping at Centre mdian posts at GST Road opp VVIP GATE and near kathipara bridge in dn 159 and 160 zone 12,Own Sources,12,2018-19,2019-20 NM/2018-19/10715,Buildings,Completed,NM-ALANDUR,159,358000,"PROPOSED TOILET AND CYCLINDER ROOM IN AMMA UNAVAGAM AT G.S.T ROAD IN DN-159,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/5283,Buildings,Completed,NM-ALANDUR,159,48000,"IMPROVEMENT WORKS TO COMPOUND WALL PAINTING AT MEENAMBAKKAM BURIAL GROUND IN DN-159,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/7500,Culvert,Completed,NM-ALANDUR,159,437000,"DEMOLITION AND RECONSTRUCTION OF CULVERT AT KAMARAJ STREET,ANNA STREET AND THIRUVALLUVAR STREET IN DIV-159,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/8904,Buildings,Completed,NM-ALANDUR,159,136000,"REPAIRS AND MAINTENANCE WORKS TO CI OFFICE BUILDING AT KAMARAJ STREET IN DN-159,U-35A,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9785,Storm Water Drain,Completed,NM-ALANDUR,159,153000,"Desilting and Repair work to Storm water drain and side drain at various street a in Din-159,Unit-35A, Zone-12",Own Sources,12,2018-19,2018-19 L/2018-19/10800,Electrical,Completed,L-Electrical,160,369000,"Painting of Lamp posts in Kathipara bridge and GST Road near Alandur metro rail station, replacement of damaged cable in Porur Vadapalani service road , Vadapalani Guindy Service Road and Le royal meridian to Asarkana service road in Div 160, Z-XII (Sch of rate 2017-18) GIM Work.",Own Sources,12,2018-19,2019-20 L/2018-19/11955,Electrical,Completed,L-Electrical,160,199500,"Proposal for fixing of 510 nos of LED Fittings & Removal of 510 nos of Sodium Fittings at various locations in Div 160, 163, 165, Z-XII, Alandur",Own Sources,12,2018-19,2020-21 L/2018-19/13405,Electrical,Completed,L-Electrical,160,630000,"Replacement of 1047 mtrs of damaged 4 x 16 sqmm PVC Alu cables and Shifting of 1 no of 8m MS street lamp post at Mkn Road and Chakrapani Bridge, Div 160, Zone XII (Sch of Rate 2017-18)",Own Sources,12,2018-19,2020-21 L/2018-19/16201,Electrical,Completed,L-Electrical,160,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Appavu Mudaly Street, Hospital in Div- 160, Zone- XII. (E.B Account Number : 241.020.759)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16203,Electrical,Completed,L-Electrical,160,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Jal Street, School in Div- 160, Zone- XII. (E.B Account Number : 241.001.540)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16204,Electrical,Completed,L-Electrical,160,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Street, Zonal Office-Ground Floor in Div- 160, Zone- XII. (E.B Account Number :241.001.269)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16205,Electrical,Completed,L-Electrical,160,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Jal Street, Municipality Elementary School in Div- 160, Zone- XII. (E.B Account Number : 241.001.391)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16207,Electrical,Completed,L-Electrical,160,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Sowri Street, Gandhi Hospital in Div- 160, Zone- XII. (E.B Account Number :241.001.328)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16208,Electrical,Completed,L-Electrical,160,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Street, Alandur Building in Div- 160, Zone- XII. (E.B Account Number : 241.001.534)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16209,Electrical,Completed,L-Electrical,160,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Margoes street, GYM in Div- 160, Zone- XII. (241.016.1386)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/10712,Buildings,Completed,NM-ALANDUR,160,47000,"REPAIR AND MAINTENANCE WORK IN AMMA UNAVAGAM AT NEW STREET IN DIV- 160, U- 35,Z- 12 .",Own Sources,12,2018-19,2020-21 NM/2018-19/10714,Buildings,Completed,NM-ALANDUR,160,64000,"REPAIR AND IMPROVEMENT WORKS AT AMMAKUDINEER AT NEW STREET IN DIV -160,U-35,Z-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/10943,Buildings,Completed,NM-ALANDUR,160,194000,"PROVIDING NEW SUMP AND MOTOR ARRANGEMENTS FOR AMMA UNAVAGM AT MKN ROAD IN DIV -160, U-35, Z-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/12869,Roads,Completed,NM-ALANDUR,160,130000,"ATTENDING CONCRETE PATCH WORK AT VARIOUS STREET IN DN-160, U-35, Z-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/15764,Electrical,Completed,NM-ALANDUR,160,341000,"Supply and Fixing of 2 Nos of Weighing Machine ( up to 150 Kgm ), 5 nos of commercial mixer(3 jar ISI marked) and 2 Nos of 300 Litre Cooler for various Amma Unavagam in Dn-156 to 167 in Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15767,Electrical,Completed,NM-ALANDUR,160,118000,"Supply and Fixing of 37 nos of TL Fittings, 30 nos of Ceiling Fan, 11 nos of Exhaust Fan, 2 nos of Wall mounting Fan, 1 no of Water Heater and 5A /15A Switches for various Amma Unavagam in Dn-156 to 167 in Zone-12",Own Sources,12,2018-19,2019-20 NM/2018-19/16112,Parks,Completed,NM-ALANDUR,160,210000,ANNUAL MAINTENANCE OF PARK AT NEW STREET IN DN 160 AREA 1363SQM(01.09.2018 to 31.03.2019),Own Sources,12,2018-19,2019-20 NM/2018-19/17648,Roads,Completed,NM-ALANDUR,160,180000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 2ND CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17649,Roads,Completed,NM-ALANDUR,160,163000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 3RD CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17650,Roads,Completed,NM-ALANDUR,160,150000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 4TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/17651,Roads,Completed,NM-ALANDUR,160,142000,"RELAYING THE EXISTING OF BT ROAD AT WOODCREEK COUNTY 5TH CROSS STREET IN DIV -158,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3250,Buildings,Completed,NM-ALANDUR,160,257000,"IMPROVEMENTS WORKS TO GYM BUILDING AT NEW STREET IN DIV-160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3901,Roads,Completed,NM-ALANDUR,160,338000,"STRENGTHENING AND RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT SANYASI SUBEDHAR STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3902,Roads,Completed,NM-ALANDUR,160,1085000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT SOWRI STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3903,Roads,Completed,NM-ALANDUR,160,1292000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT NEW STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3904,Roads,Completed,NM-ALANDUR,160,824000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT EKAMBARADABADHER STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3905,Roads,Completed,NM-ALANDUR,160,453000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT DHARAMARAJA KOVIL STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3906,Roads,Completed,NM-ALANDUR,160,468000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT KARPAGAVINAYAKAR KOVIL STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3907,Roads,Completed,NM-ALANDUR,160,590000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT APPAVU STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3908,Roads,Completed,NM-ALANDUR,160,472000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT JILLANI STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3909,Roads,Completed,NM-ALANDUR,160,757000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT MARGOUS STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3911,Roads,Completed,NM-ALANDUR,160,290000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT VEMBULIAMMAN KOVIL STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3912,Roads,Completed,NM-ALANDUR,160,232000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT NATHAT SUBEDHAR STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3913,Roads,Completed,NM-ALANDUR,160,417000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT MUTHAMJI STREET IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/3914,Roads,Completed,NM-ALANDUR,160,481000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT ESWARAN KOVIL LANE IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3915,Roads,Completed,NM-ALANDUR,160,234000,"RELAYING THE EXISTING OF BT ROAD BY USING PAVER FINISHER AT RAMASAMY BANDULA LANE IN DIV -160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/4692,Buildings,Completed,NM-ALANDUR,160,200000,"IMPROVEMENT WORKS TO ANGANVADI CENTER NO 115 AT RAMASAMY BANDULA LANE IN DIV 160 ,U -35, Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/7466,Buildings,Completed,NM-ALANDUR,160,200000,"CONSTRUCTION OF BABY FRIENTLY TOILET IN ANGANVADI AT JAL STREET IN DN-160,UNIT-35,ZONE-12",Own Sources,12,2018-19,2018-19 NM/2018-19/8043,Buildings,Completed,NM-ALANDUR,160,821000,"IMPROVEMENT WORKS TO SHOPING COMPLEX ( RTO OFFICE ,IOB BANK, WATER BOARD OFFICE ),AT NEW STREET IN DIV -160 U-35, Z-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/8069,Buildings,Completed,NM-ALANDUR,160,1080000,"IMPROVEMENT WORKS TO ZONE OFFICE BUILDING AT NEW STREET IN DIV-160 ,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/8862,Buildings,Completed,NM-ALANDUR,160,138000,"REPAIR AND MAINTENANCE WORK TO GYM BUILDING AT MARKOSH STREET IN DN-160,U-35,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9781,Storm Water Drain,Completed,NM-ALANDUR,160,701000,"Desilting and Repair work to Storm water drain and side drain at various street a in Din-160,Unit-35, Zone-12",Own Sources,12,2018-19,2018-19 L/2018-19/16183,Electrical,Completed,L-Electrical,161,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Raja street NMC 1 in Division 161,Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16184,Electrical,Completed,L-Electrical,161,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Raja street NMC 2 in Division 161,Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16185,Electrical,Completed,L-Electrical,161,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at VOC Nagar NMC in Division 161,Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/4127,Electrical,Completed,L-Electrical,161,743900,Provision of 1 no 12 mtr new highmast with 10 nos of 70-100w lLED FL fitting and 50 mtr of 31/2x120 and 120 mtr of 4x16 sq mm cable at Near PONNIAMMAN KOIL STREET Junction in DN 161 Zone 12,MPLADS,12,2018-19,2019-20 NM/2018-19/0053,Roads,Completed,NM-ALANDUR,161,218000,"RELAYING CC ROAD AT SOUTH RAJA STREET 1ST LANE IN DIV-161, UNIT-36, ZONE-12",Own Sources,12,2018-19,2019-20 NM/2018-19/0054,Roads,Completed,NM-ALANDUR,161,272000,"RELAYING CC ROAD AT RAJA STREET 2ND LANE IN DIV-161, UNIT-36, ZONE-12",Own Sources,12,2018-19,2019-20 NM/2018-19/0061,Roads,Completed,NM-ALANDUR,161,2539000,"RELAYING OF BT ROAD AT PUDUPET STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/0067,Roads,Completed,NM-ALANDUR,161,549000,"RELAYING OF BT ROAD AT THIRUVALLUVAR 3RD STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/0068,Roads,Completed,NM-ALANDUR,161,531000,"RELAYING OF BT ROAD AT LYODS AVENUE STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/1035,Roads,Completed,NM-ALANDUR,161,259000,"RELAYING OF BT ROAD AT VALLALAR STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/10873,Buildings,Completed,NM-ALANDUR,161,166000,"Repair and maintanance work of Amma Unnavagam at Raja street in Dn-161,U-35A,Z-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/14003,Storm Water Drain,Completed,NM-ALANDUR,161,303000,"Repair and Maintanance work of Storm Water Drain at Mandi Street in DN-161,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/1419,Roads,Completed,NM-ALANDUR,161,659000,"RELAYING CC ROAD AT MASTHAN GORI STREET IN DIV-161, UNIT-36, ZONE-12",Own Sources,12,2018-19,2019-20 NM/2018-19/1477,Roads,Completed,NM-ALANDUR,161,445000,"RELAYING CC ROAD AT MKN ROAD LANE IN DIV-161, UNIT-36, ZONE-12",Own Sources,12,2018-19,2019-20 NM/2018-19/16136,Parks,Completed,NM-ALANDUR,161,206000,ANNUAL MAINTENANCE OF PARK AT TNGO COLONY IN DN 161 (FROM 01.09.2018 TO 31.03.2019 7 MONTHS 1100SQM),Own Sources,12,2018-19,2019-20 NM/2018-19/16137,Parks,Completed,NM-ALANDUR,161,108000,ANNUAL MAINTENANCE OF PARK AT MURUGAN NAGAR IN DN 161 (450SQM) 01.09.2018 TO 31.03.2019 7MONTHS,Own Sources,12,2018-19,2019-20 NM/2018-19/17437,Parks,Completed,NM-ALANDUR,161,85000,ANNUAL MAINTENANCE OF PARK AT JEEVAN NAGAR IN DN 161 (01.09.2018 TO 31.03.2019 7 MONTHS (400SQM),Own Sources,12,2018-19,2019-20 NM/2018-19/17438,Parks,Completed,NM-ALANDUR,161,172000,ANNUAL MAINTENANCE OF PARK AT OFFICERS COLONY IN DN 161 (01.09.2018 TO 31.03.2019) 7MONTHS (1038SQM),Own Sources,12,2018-19,2019-20 NM/2018-19/17878,Roads,Completed,NM-ALANDUR,161,1134000,"RELAYING OF BT ROAD AT PONNIAMMAN KOVIL STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/2963,Storm Water Drain,Completed,NM-ALANDUR,161,452000,"SUPPLYING AND FIXING STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3073,Buildings,Completed,NM-ALANDUR,161,20000,"REPAIR AND MAINTANANCE WORK OF SS NAME BOARD AT VARIOUS STREETS IN DN-161,UNIT-36,ZONE-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3374,Roads,Completed,NM-ALANDUR,161,858000,"RELAYING OF BT ROAD AT TNGO COLONY 2ND STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/7418,Roads,Completed,NM-ALANDUR,161,303000,"ATTENDING BT ROAD CUT AND PATCH WORK AT VARIOUS STREET IN DN-161,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9531,Storm Water Drain,Completed,NM-ALANDUR,161,554000,"DESILTING AND MINOR REPAIR WORKS OF SWD AT VARIOUS STREETS IN DN-161,U-35A,Z-12",Own Sources,12,2018-19,2018-19 BR/2018-19/18193,Road Cut,Completed,BR-Bus Route Roads,162,721000,Restoration of OFC road cut made by M/s Bharathi Airtel at various interior roads in Div-162 Unit- 36 Zone-12(Deposit code-57/0086/2018-19),Deposit Works,12,2018-19,2019-20 BR/2018-19/18194,Road Cut,Completed,BR-Bus Route Roads,162,736000,Restoration of OFC road cut made by M/s Bharathi Airtel at various interior roads in Div-162 Unit- 36 Zone-12(Deposit code-57/0086/2018-19),Deposit Works,12,2018-19,2019-20 BR/2018-19/18195,Road Cut,Completed,BR-Bus Route Roads,162,779000,Restoration of OFC road cut made by M/s Bharathi Airtel at various interior roads in Div-162 Unit- 36 Zone-12(Deposit code-57/0086/2018-19),Deposit Works,12,2018-19,2019-20 BR/2018-19/18196,Road Cut,Completed,BR-Bus Route Roads,162,476000,Restoration of OFC road cut made by Reliance Jio at various interior roads in Div-162 Unit- 36 Zone-12(Deposit code-57/0319/2018-19),Deposit Works,12,2018-19,2019-20 BR/2018-19/18274,Roads,Completed,BR-Bus Route Roads,162,2606000,Traffic Improvement Works at Various Bus Route Roads in Zone -XII,Own Sources,12,2018-19,2019-20 D/2018-19/9743,Storm Water Drain,Completed,D-Storm Water Drains,162,53719000,Construction of Storm Water Drain at North Raja Street and 4 Other Roads in Zone - 12 - Package 48,Grants,12,2018-19,2019-20 L/2018-19/16188,Electrical,Completed,L-Electrical,162,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kannan colony Gym in Division 162, Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16189,Electrical,Completed,L-Electrical,162,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kannan Colony NMC in Division 162, Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16190,Electrical,Completed,L-Electrical,162,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Hall, kannan Colony in Division 162, Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16191,Electrical,Completed,L-Electrical,162,86200,"Supply, Installation, Testing & Commissioning of 1 No of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nobel street,Kannan colony in Division 162, Zone 12",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16192,Electrical,Completed,L-Electrical,162,311900,"Supply, Installation, Testing & Commissioning of 1 No of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division Office,Thillai Ganga Nagar in DN 162 , ZONE 12 EB 268.011.548",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/11801,Storm Water Drain,Completed,NM-ALANDUR,162,111000,"IMPROVEMENT WORKS TO EXISTING DRAIN AT VARIOUS STREET IN DN-164,UNIT-37,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/12839,Parks,Completed,NM-ALANDUR,162,156000,"ANNUAL MAINTENANCE FOR PARK AT THIRUVALLUVAR NAGAR IN DN 162, ZONE 12.(AREA 1718 SQ.M) FOR 7MONTHS FROM 01.09.2018 TO 31.03.2019",Own Sources,12,2018-19,2019-20 NM/2018-19/13160,Buildings,Completed,NM-ALANDUR,162,231000,"IMPROVEMENT WORKS TO DIVISION OFFICE BUILDING AT THILLAIGANGA NAGAR 1ST MAIN ROAD IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/13335,Road Cut,Completed,NM-ALANDUR,162,69000,"ATTENDING CEMENT CONCRETE PATCH WORK AT VARIOUS STREETS IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/14718,Buildings,Completed,NM-ALANDUR,162,175000,"REPAIR WORKS TO EXISTING INDOOR GAME SHED AT NOBLE 1ST STREET IN DN-162,U-36,Z-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/15278,Parks,Completed,NM-ALANDUR,162,105000,ANNUAL MAINTENANCE OF PARK AT T.G.NAGAR 34TH STREET IN DN 162 (AREA 446 SQ.M IN ZONE 12 FOR 7MONTHS 01.09.2018 TO 31.03.2019.,Own Sources,12,2018-19,2019-20 NM/2018-19/18315,Roads,Completed,NM-ALANDUR,162,9770500,"FORMING AND STRENGTHENING OF EXISTING BT ROAD( FROM RAILWAY FOOT OVER BRIDGE TO GST ROAD ) AT NOBLE 1ST STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/18316,Roads,Completed,NM-ALANDUR,162,800000,"FORMING AND STRENGTHENING OF EXISTING BT ROAD(FROM PALAVANTHANGAL SUB WAY SERVICE ROAD TO RAILWAY FOOT OVER BRIDGE) AT NOBLE 1ST STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/2303,Roads,Completed,NM-ALANDUR,162,689000,"SUPPLYING AND FIXING STAINLESS STEEL STREET NAME BOARD AT VARIOUS STREET IN DIVISION-162, UNIT-36, ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/2619,Roads,Completed,NM-ALANDUR,162,130000,"IMPROVEMENT WORKS TO EXISTING SPEED BREAKER AS PER IRC DESIGN AT THILLAI GANGA NAGAR 22ND STREET AND HUDCO COLONY IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/2861,Roads,Completed,NM-ALANDUR,162,357000,"IMPROVEMENTS TO EXISTING CC ROAD AT THILLAIGANGA NAGAR 1ST STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/2967,Roads,Completed,NM-ALANDUR,162,261000,"IMPROVEMENTS TO EXISTING CC ROAD AT THIRUVALLUVAR NAGAR 4TH STREET IN DIVISION-162, UNIT-36., ZONE-12",Own Sources,12,2018-19,2020-21 NM/2018-19/2974,Roads,Completed,NM-ALANDUR,162,385400,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAI GANGA NAGAR 19TH STREET IN DIVISION-162, UNIT-36., ZONE-12",Own Sources,12,2018-19,2019-20 NM/2018-19/2981,Roads,Completed,NM-ALANDUR,162,405300,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 15TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3021,Roads,Completed,NM-ALANDUR,162,543500,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 17TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3022,Roads,Completed,NM-ALANDUR,162,159600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 18TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3023,Roads,Completed,NM-ALANDUR,162,431500,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 20TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3024,Roads,Completed,NM-ALANDUR,162,303000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 21TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3025,Roads,Completed,NM-ALANDUR,162,927600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 25TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3026,Roads,Completed,NM-ALANDUR,162,337900,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 30TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/3027,Roads,Completed,NM-ALANDUR,162,143300,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 33RD STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/3028,Roads,Completed,NM-ALANDUR,162,341600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THIRUVALLUVAR NAGAR 4TH STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/3029,Roads,Completed,NM-ALANDUR,162,445800,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 22ND STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/3049,Buildings,Completed,NM-ALANDUR,162,9000,"PROVIDING AWARNESS BOARD FOR BURIAL GROUND IN DIVISION 162,UNIT 36,ZONE 12",Own Sources,12,2018-19,2018-19 NM/2018-19/5111,Roads,Completed,NM-ALANDUR,162,173000,"THERMOPLASTIC PAINTING WORKS TO EXISTING SPEED BREAKER AT VARIOUS STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/6320,Buildings,Completed,NM-ALANDUR,162,328000,"IMPROVEMENT WORKS TO KANNAN COLONY BURIAL GROUND IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/6397,Electrical,Completed,NM-ALANDUR,162,29000,"IMPROVEMENT WORKS TO ANGANVADI CENTRE AT MORRISON 2ND STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/6398,Buildings,Completed,NM-ALANDUR,162,40000,"IMPROVEMENT WORKS TO MULTI PURPOSE HALL AT KANNAN COLONY IN DIVISION-162, UNIT-36, ZONE-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/6566,Buildings,Completed,NM-ALANDUR,162,179000,"CONSTRUCTION OF SUMP AT AMMA KUDINEER AT THILLAI GANGA NAGAR 4TH MAIN ROAD IN DN-162,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/7330,Roads,Completed,NM-ALANDUR,162,335000,"ATTENDING BT PATCH WORK AT VARIOUS STREET IN DN-162,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/8638,Playfields,Completed,NM-ALANDUR,162,1160000,"CONSTRUCTION OF COMPOUND WALL, FOOT PATH,AND PROVIDING PLAY APPARATUS, ELECTRICAL ARRANGEMENTS OF THE EXISTING PLAY FIELD IN KANNAN COLONY 3RD STREET IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/9247,Buildings,Completed,NM-ALANDUR,162,448500,"SUPPLYING AND ERECTION OF BIO-SHREDDING PULVERIZER MACHINE, MANURE SEIVER MACHINE AND WEIGHING MACHINE INCLUDING CIVIL AND ELECTRICAL WORK AT KANNAN COLONY COMPOSED YARD IN DN 162 U.36 Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9248,Road Cut,Completed,NM-ALANDUR,162,82000,"ROAD CUT RESTORATION AT THILLAIGANGA NAGAR 45TH STREET IN DIVISION-162,UNIT-36,ZONE-12.",Deposit Works,12,2018-19,2019-20 NM/2018-19/9529,Storm Water Drain,Completed,NM-ALANDUR,162,720000,"DESILTING THE RAILWAY CULVERT AT KANNAN COLONY AND MINOR REPAIR WORKS AT THILLAIGANGA NAGAR 4TH MAIN ROAD IN DN-162,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9530,Storm Water Drain,Completed,NM-ALANDUR,162,714000,"DESILTING WORKS AND MINOR REPAIR WORKS OF SWD AT VARIOUS STREET IN DN-162,U-36,Z-12",Own Sources,12,2018-19,2018-19 BR/2018-19/5560,Roads,Completed,BR-Bus Route Roads,163,1181000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Palandiamman Koil Street in Dn-163, Zone - XII",Grants,12,2018-19,2019-20 BR/2018-19/5561,Roads,Completed,BR-Bus Route Roads,163,956000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at East Karikalan Street in Dn-163, Zone - XII",Grants,12,2018-19,2019-20 BR/2018-19/5562,Roads,Completed,BR-Bus Route Roads,163,1247000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Erikkarai Street (Part) in Dn-163, Zone - XII",Grants,12,2018-19,2019-20 L/2018-19/16210,Electrical,Completed,L-Electrical,163,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Karunigar Street, Municipality School, in Div- 163, Zone- XII. (E.B Account Number : 243.122.641)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/16211,Electrical,Completed,L-Electrical,163,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Parthasarathy 8th (Extn), NMC in Div- 163, Zone- XII. (E.B Account Number : 243.124.634)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/13434,Roads,Completed,NM-ALANDUR,163,200000,ATTENDING CONCRETE PATCH WORK AT VARIOUS STREETS IN DN 163 U.37 Z.12,Own Sources,12,2018-19,2019-20 NM/2018-19/15303,Parks,Completed,NM-ALANDUR,163,105000,"ANNUAL MAINTENANCE OF PARK AT SHANTHI NAGAR 4TH STREET IN DN 163, ZONE 12 (515 SQM) FOR 7MONTHS 01.09.2018 TO 31.03.2019",Own Sources,12,2018-19,2019-20 NM/2018-19/1668,Buildings,Completed,NM-ALANDUR,163,498000,"1. Color Washing and providing platform at Balakrishnapuram Gasifier 2. Color washing, rising and art work front side of Balakrishnapuram Burial ground compound wall 3. Forming environmental Greenery inside of Balakrishnapuram Burial ground and laying flooring and wall tiles and compound wall Shattering work at compost yard. in Dn-163, Unit- 37, Zone-12",Own Sources,12,2018-19,2018-19 NM/2018-19/2275,Roads,Completed,NM-ALANDUR,163,253000,"PROPOSED SPEED BREAKER AS PER IRC DESIGN AT BALAKRISHNAPURAM 1ST,2ND,3RD AND 4TH STREETT IN DN-163 U-37 Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/2443,Roads,Completed,NM-ALANDUR,163,69000,THERMOPLASTIC PAINTING TO THE EXISTING SPEED BREAKER AT VARIOUS STREET IN DN-163 U-37 Z-12,Own Sources,12,2018-19,2018-19 NM/2018-19/2660,Roads,Completed,NM-ALANDUR,163,124000,RELAYING THE ROAD BY PAVER FINISHER AT BALAKRISHNAPURAM 5 STREET IN DN-163 U-37 Z-12,Own Sources,12,2018-19,2019-20 NM/2018-19/2662,Roads,Completed,NM-ALANDUR,163,408800,STRENGTHING AND RELAYING ROAD BY PAVER FINISHER AT KARNEEGAR STREET(PART)IN DN-163 U-37 Z-12,Own Sources,12,2018-19,2019-20 NM/2018-19/2919,Buildings,Completed,NM-ALANDUR,163,38000,REPAIRS WORK TO SS NAME BOARD VARIOUS STREET IN DN-163 U-37 Z-12,Own Sources,12,2018-19,2019-20 NM/2018-19/3681,Buildings,Completed,NM-ALANDUR,163,300000,IMPROVEMENT WORKS AND INSULATION OF A.C IN DOCTOR ROOM AND LAB ROOM AT U.P.H.C MANNADIYMMAN KOVIL STREET DIV-163 U-37 Z-12,Own Sources,12,2018-19,2019-20 NM/2018-19/4161,Roads,Completed,NM-ALANDUR,163,401200,RELAYING THE ROAD OF MILLING BY PAVER FINISHER AT RAMAKRISHNA STREET IN DN-163 U-37 Z-12,Own Sources,12,2018-19,2019-20 NM/2018-19/4162,Roads,Completed,NM-ALANDUR,163,190000,RELAYING THE ROAD OF MILLING BY PAVER FINISHER AT BALAKRISHNAPURAM 6 STREET IN DN-163 U-37 Z-12,Own Sources,12,2018-19,2020-21 NM/2018-19/4518,Electrical,Completed,NM-ALANDUR,163,198000,IMPROVEMENT WORKS TO ANGANWADI BUILDING AT PILLIYAR KOIL STREET(THIRUVALLUVAR NAGAR) IN DN-163 U-37 Z-12,Own Sources,12,2018-19,2019-20 NM/2018-19/6977,Roads,Completed,NM-ALANDUR,163,203000,"ATTENDING BT PATCH WORK AT VARIOUS STREETS IN DN 163,U.37.Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/8946,Roads,Completed,NM-ALANDUR,163,144000,RESTORATION OF ROAD CUT AT PARTHASARTHY NAGAR 1ST AND 2ND STREET IN DN 163 U.36 Z.12,Deposit Works,12,2018-19,2019-20 NM/2018-19/9009,Buildings,Completed,NM-ALANDUR,163,448500,"SUPPLYING AND ERECTION OF BIO-SHREDDING PULVERIZER MACHINE, MANURE SEIVER MACHINE AND WEIGHING MACHINE INCLUDING CIVIL AND ELECTRICAL WORK AT BALAKRISHNAPURAM COMPOSED YARD IN DN 163 U.36 Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9539,Storm Water Drain,Completed,NM-ALANDUR,163,531000,"DESILTING,MINOR REPAIR WORK AND REPLACING MANHOLE AT VARIOUS STREET IN DN 163 U.36 Z-12",Own Sources,12,2018-19,2019-20 D/2018-19/9780,Storm Water Drain,Completed,D-Storm Water Drains,164,26318000,Construction of Storm Water Drain at Naganallur 19th Street and 2 Other Roads in Zone - 12 - Package - 50.,Grants,12,2018-19,2020-21 L/2018-19/16196,Electrical,Completed,L-Electrical,164,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganwadi, Ellaimuthamman Kovil Street in Div-164, Zone-Xll .( TNEB AC NO.244.183.705 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6121,Electrical,Completed,L-Electrical,164,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Chennai Primary School, Vembuliamman koil st, Palavanthangal in Div-164, Zone-Xll. ( 244.181.656 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6122,Electrical,Completed,L-Electrical,164,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Palavanthangal Health Post in Div-164, Zone-Xll . ( 268.029.15 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6131,Electrical,Completed,L-Electrical,164,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Colony Anganwadi in Div-164, Zone-Xll .( 268.029.710,268.029.711 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6132,Electrical,Completed,L-Electrical,164,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Colony, GYM in Div-164, Zone-Xll .( 268.029.16 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6133,Electrical,Completed,L-Electrical,164,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at New Colony Kalyana Mandapam, Palavanthangal in Div-164, Zone-Xll.",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/10874,Buildings,Completed,NM-ALANDUR,164,16500,"REPAIR AND MAINTENANCE WORKS TO AMMA UNAVAGAM AT NANGANALLUR 4TH MAIN ROAD IN DN-164,U-37,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/11708,Storm Water Drain,Completed,NM-ALANDUR,164,700000,"Construction of new drain at Thillai ganga Nagar 5th Main road in Division 164,Unit 37,Zone 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/11802,Storm Water Drain,Completed,NM-ALANDUR,164,369000,"CONSTRUCTION OF STORM WATER DRAIN AT NANGANALLUR 3RD MAIN ROAD IN DN-164,UNIT-37,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/13320,Parks,Completed,NM-ALANDUR,164,163000,"ANNUAL MAINTENANCE OF PARK AT NANGANALLUR 29TH STREET IN DN 164, ZONE 12(446 SQM) for 7months (01.09.2018 to 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/13441,Roads,Completed,NM-ALANDUR,164,535000,"ATTENDING CEMENT CONCRETE PATCH WORK AT VARIOUS STREETS IN DIVISION-164,UNIT-37,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/14198,Buildings,Completed,NM-ALANDUR,164,62000,"REPAIR WORKS TO AMMA KUDINEER AT NANGANALLUR 29TH STREET IN DIVISION-164,UNIT-37,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/14306,Buildings,Completed,NM-ALANDUR,164,397000,PROVIDING IEC ACTIVITIES AWARENESS BOARD AT VARIOUS LOCATION IN ZONE-12.,Own Sources,12,2018-19,2020-21 NM/2018-19/14865,Parks,Completed,NM-ALANDUR,164,456000,"PROVIDING OPEN GYM MATERIALS AND PEBBLE WALK AT NEHRU STREET PARK IN DN-164,U-37,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/15301,Parks,Completed,NM-ALANDUR,164,172000,ANNUAL MAINTENANCE OF PARK AT NEHRU STREET IN DN 164 ZONE 12(475SQM) 7MONTHS (01.09.2018 TO 31.03.2019),Own Sources,12,2018-19,2019-20 NM/2018-19/17603,Roads,Completed,NM-ALANDUR,164,350000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANALLUR 32ND STREET IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17604,Roads,Completed,NM-ALANDUR,164,419100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANALLUR 37TH STREET EXTN IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17605,Roads,Completed,NM-ALANDUR,164,568100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT JAIHIND STREET IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/1863,Culvert,Completed,NM-ALANDUR,164,272000,"CONSTRUCTION OF CROSSING CULVERT AT NANGANALLUR 2ND MAIN ROAD SWD CROSSING PURPOSE IN DN-164, UNIT-37, ZONE-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/2411,Roads,Completed,NM-ALANDUR,164,572000,"Providing SS name board at Various streets in Division 164,Unit 36,Zone 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/2433,Buildings,Completed,NM-ALANDUR,164,118000,"IMPROVEMENT WORKS TO ANGANVADI BUILDING AT VEMBULIAMMAN KOIL STREET IN DN-164,U-37,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/2983,Roads,Completed,NM-ALANDUR,164,98000,"PAINTING OF SPEED BREAKARS AS PER IRC STANDARDS AT VEERARAGAVAN STREET, NANGANALLUR 33RD STREET, NANGANALLUR 29TH STREET, NANGANALLUR 3RD MAIN ROAD, NANGANALLUR 13TH STREET, NANGANALLUR 37TH STREET EXTN, THILLAIGANGANAGAR 5TH MAIN ROAD AND JOHN DESIKAN STREET IN DIVISION-164,U-37,Z-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/3833,Roads,Completed,NM-ALANDUR,164,346500,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANALLUR 33RD STREET IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3834,Roads,Completed,NM-ALANDUR,164,436000,"RELAYING OF EXISTING CC ROAD AT NANGANALLUR 31 ST STREET IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3836,Roads,Completed,NM-ALANDUR,164,229000,"STRENGTHENING AND LAYING OF CC ROAD AT ELLAIMUTHAMMAN KOIL STREET LANE IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3877,Roads,Completed,NM-ALANDUR,164,173000,"PROVIDING SPEED BREAKERS AS PER IRC STANDARD AT NERHU COLONY MAIN ROAD IN DN-164,U-37,Z-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/4112,Buildings,Completed,NM-ALANDUR,164,224000,Construction of Baby friendly toilet in Anganvadi at Vembuli amman koil street in DIV 164 Unit 37 Zone 12,Own Sources,12,2018-19,2019-20 NM/2018-19/4151,Buildings,Completed,NM-ALANDUR,164,46000,"REPAIR WORKS TO 16TH CEREMONY HALL AT NANGANALLUR 4TH MAIN ROAD IN DN-164,U-37,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/4418,Buildings,Completed,NM-ALANDUR,164,887000,"IMPROVEMENTS WORKS TO COMMUNITY HALL BUILDING AT NEWCOLONY 1ST STREET IN DN-164,U-37,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/4775,Buildings,Completed,NM-ALANDUR,164,217000,"PROVIDING REST ROOM AND STORE ROOM FOR MALERIA AND SANITARY WORKERS IN DN-164,U-37,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/4778,Roads,Completed,NM-ALANDUR,164,153000,"PROVIDING THERMO PLASTIC PAINTING AT KRISHNASAMY STREET AND NANGANALLUR 2ND MAOIN ROAD IN DN-164,U-37,Z-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/5503,Buildings,Completed,NM-ALANDUR,164,175000,"PROVIDING UNDER GROUND SUMP AT UPHC BUILDING AT NEW COLONY 2ND STREET IN DN-164,U-37,Z-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/7261,Roads,Completed,NM-ALANDUR,164,435000,ATTENDING BT PATCH WORK AT VARIOUS STREETS IN DN 164.U.37.Z-12,Own Sources,12,2018-19,2019-20 NM/2018-19/9787,Storm Water Drain,Completed,NM-ALANDUR,164,342000,"DESILTING AND PROVIDING MANHOLE DOORS AT VARIOUS STREET IN DN-164,U-37,Z-12",Own Sources,12,2018-19,2018-19 L/2018-19/16212,Electrical,Completed,L-Electrical,165,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ram Nagar 8th Street, School in Div- 165, Zone- XII. (E.B Account Number : 268.014.514)",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/3090,Electrical,Completed,L-Electrical,165,1865000,"Removal of 20 nos of 9m lamp post ,Supply and Erection of 27 nos of 8m GI Lamp post with single straight bracket and 7 nos of 150-165W LED Fittings at Inner Ring Road North and South in Division 165 ,Zone XII. (Sch of rate 2017-18) MRTS Deposit work.",Deposit Works,12,2018-19,2019-20 NM/2018-19/11608,Culvert,Completed,NM-ALANDUR,165,167000,"Demolition and Reconstruction of existing damaged culvert at New colony 1st street in Division-165, Unit-37,Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/13990,Electrical,Completed,NM-ALANDUR,165,106000,"Rewiring of 16th Day Ceremony Hall with necessary lights, fans and switches in , Pazhandiamman Street, Vanuvampet, Div 165, Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/14186,Electrical,Completed,NM-ALANDUR,165,320000,"Supply and Erection of 11 nos of 2 mtr Lamp post with 20W LED Fittings and conversion of 2 nos of CFL into 20W Led fittings at Nanganallur 11th st park , DIV 165, ZONE - XII (Schedule of Rates 2017-18)",Own Sources,12,2018-19,2020-21 NM/2018-19/14247,Buildings,Completed,NM-ALANDUR,165,75000,"Improvement works to Burial ground at Vanuvampet in DN-165,U-37,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/15304,Parks,Completed,NM-ALANDUR,165,185000,ANNUAL MAINTENANCE OF PARK AT SOUTH SECTOR 2ND STREET IN DN 165 ZONE 12(799SQM) 7months 01.09.2018 to 31.03.2019.,Own Sources,12,2018-19,2019-20 NM/2018-19/15336,Parks,Completed,NM-ALANDUR,165,119000,"ANNUAL MAINTENANCE OF PARK AT BALAJI NAGAR IN DN 165, ZONE 12(740SQM) 7months 01.09.2018 to 31.03.2019",Own Sources,12,2018-19,2019-20 NM/2018-19/15346,Parks,Completed,NM-ALANDUR,165,106000,"ANNUAL MAINTENANCE OF PARK AT LAKSHMI NAGAR IN DN 165, ZONE 12(240SQM) for 7months (01.09.2019 to 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/15349,Parks,Completed,NM-ALANDUR,165,211000,"ANNUAL MAINTENANCE OF PARK AT BHARATH NAGAR IN DN 165, ZONE 12 (1142SQM) 7months (01.09.2018 to 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/15351,Parks,Completed,NM-ALANDUR,165,106000,"ANNUAL MAINTENANCE ESTIMATE FOR PARK AT SURENDRA NAGAR IN DN 165, ZONE 12 (424SQM) 7months (01.09.2018 to 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/15354,Parks,Completed,NM-ALANDUR,165,105000,ANNUAL MAINTENANCE OF PARK AT NETHAJI STREET IN DN 165 ZONE 12(294SQM) 7months (01.09.2018 to 31.03.2019),Own Sources,12,2018-19,2019-20 NM/2018-19/17606,Roads,Completed,NM-ALANDUR,165,273900,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Co-Operative nagar Gandhi street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17607,Roads,Completed,NM-ALANDUR,165,81400,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Bharathi street North IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17608,Roads,Completed,NM-ALANDUR,165,106000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Thirumalai street North IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17609,Roads,Completed,NM-ALANDUR,165,283100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD ATMuthiyal reddy nagar 3rd street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17610,Roads,Completed,NM-ALANDUR,165,283850,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Gas Godown street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17611,Roads,Completed,NM-ALANDUR,165,92550,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Co Oprative nagar 3rd cross street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17612,Roads,Completed,NM-ALANDUR,165,193600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Manivasagam street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17613,Roads,Completed,NM-ALANDUR,165,200700,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT North new street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17614,Roads,Completed,NM-ALANDUR,165,136800,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Co Oprative nagar Srinivasan street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17615,Roads,Completed,NM-ALANDUR,165,318200,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT South new street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17616,Roads,Completed,NM-ALANDUR,165,513100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Balaji nagar 17th street East IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17617,Roads,Completed,NM-ALANDUR,165,157800,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Thiruvalluvar Nagar Gopalakrishnan street IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17618,Roads,Completed,NM-ALANDUR,165,142000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THENPANNAI STREET IN DIVISION 165, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17619,Roads,Completed,NM-ALANDUR,165,308900,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT B.V. Nagar 2nd street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17620,Roads,Completed,NM-ALANDUR,165,240600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Raghupathy Nagar 4th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17621,Roads,Completed,NM-ALANDUR,165,429200,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Raghupathy Nagar 5th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17622,Roads,Completed,NM-ALANDUR,165,300500,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Raghupathy Nagar 6th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17623,Roads,Completed,NM-ALANDUR,165,811300,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Raghupathy Nagar 9th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17624,Roads,Completed,NM-ALANDUR,165,173600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Gandhi Nagar (Nehru Street) IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17625,Roads,Completed,NM-ALANDUR,165,123100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT Gandhi Nagar (Thiruvalluvar Street) IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17626,Roads,Completed,NM-ALANDUR,165,78200,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT B.V. Nagar 5th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17627,Roads,Completed,NM-ALANDUR,165,1329000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT B.V. Nagar 10th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17628,Roads,Completed,NM-ALANDUR,165,119500,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT K.K Nagar 5th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/17629,Roads,Completed,NM-ALANDUR,165,112800,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT K.K. Nagar 6th street IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/2540,Roads,Completed,NM-ALANDUR,165,927000,"Providing SS name board at Various streets in Division 165,Unit 37,Zone 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/2955,Buildings,Completed,NM-ALANDUR,165,31500,"Improvement works to Burial ground at Muthiyal reddy nagar main road in Division-165,Unit 37,Zone-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/2957,Buildings,Completed,NM-ALANDUR,165,9000,"PROVIDING AWARNESS BOARD FOR BURIAL GROUND (NEW COLONY AND MUTHIYAL REDDY NAGAR ) IN DIVISION 165,UNIT 37,ZONE 12.",Own Sources,12,2018-19,2018-19 NM/2018-19/2985,Roads,Completed,NM-ALANDUR,165,264000,"Providing and laying of thermoplastic paint to the existing speed breaker at various streets in Division 165,Unit 37,Zone 12.",Own Sources,12,2018-19,2018-19 NM/2018-19/3157,Buildings,Completed,NM-ALANDUR,165,74000,"Repair work to the existing stainless steel name board at Various streets in Division 165,Unit 37,Zone 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/4305,Buildings,Completed,NM-ALANDUR,165,128000,"Improvement works to Anganwadi at Ram nagar in Division-165,Unit-37,Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/4417,Buildings,Completed,NM-ALANDUR,165,222000,"IMPROVEMENT WORKS TO KARIYA MANDABAM AT PALANDIAMMAN KOIL STREET IN DIV 165,UNIT 37,ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/7257,Roads,Completed,NM-ALANDUR,165,727000,"ATTENDING BT PATCH WORK AT VARIOUS STREETS IN DN-165,U-37,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/7986,Parks,Completed,NM-ALANDUR,165,436000,"PROVIDING SUMP AND TOILET FACILITIES TO BALAJI NAGAR PARK IN DIVISION 165,UNIT 37,ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/8473,Roads,Completed,NM-ALANDUR,165,350000,"RESTORATION OF ROAD CUT MADE BY CMWSSB AT PALANDIAMMAN KOIL STREET IN DIVISION 165,UNIT 37,ZONE 12.",Deposit Works,12,2018-19,2019-20 NM/2018-19/9558,Buildings,Completed,NM-ALANDUR,165,2533000,"CONSTRUCTION OF COMPOST YARD INCLUDING WATER FACILITY ,SUPPLYING AND ERECTION OF BIO-SHREDDING PULVERIZED MACHINE,MANURE SEIVER MACHINE AND WEIGHING MACHINE AT VANUVAMPET BURIAL GROUND IN DIV-165, UNIT-37, ZONE-12",Own Sources,12,2018-19,2019-20 NM/2018-19/9657,Buildings,Completed,NM-ALANDUR,165,107000,"Improvement works to Anganwadi at Vanuvampet in Division-165,Unit-37,Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/9793,Storm Water Drain,Completed,NM-ALANDUR,165,1017500,"DESILTING AND MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DN-165,U-37,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/9794,Storm Water Drain,Completed,NM-ALANDUR,165,1017500,"DESILTING AND MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DN-165,U-37,Z-12",Own Sources,12,2018-19,2018-19 NM/2018-19/9795,Storm Water Drain,Completed,NM-ALANDUR,165,1017500,"DESILTING AND MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DN-165,U-37,Z-12",Own Sources,12,2018-19,2018-19 Q/2018-19/10991,Buildings,Completed,Q-Solid Waste Management,165,7200000,"Construction of Domestic Hazardous waste collection centres for package 2 as per DFR in Zone-11,12,14 & 15",Grants,12,2018-19,2020-21 L/2018-19/6112,Electrical,Completed,L-Electrical,166,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at B.V. Nagar 3rd Main Road (GYM Building) in Div-166, Zone-Xll. ( 264.666.1114 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6113,Electrical,Completed,L-Electrical,166,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at B.V. Nagar 3rd Main Road, Amma Unavagam in Div-166, Zone-Xll. ( 264.666.1165 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6120,Electrical,Completed,L-Electrical,166,462400,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nehru colony main road Community Hall, Nanganallur in Div-166, Zone-Xll. ( 244.160.1227 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6123,Electrical,Completed,L-Electrical,166,688100,"Supply, Installation, Testing & Commissioning of 9 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital K.K. Nagar in Div-166, Zone-Xll. ( 244.192.216 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6125,Electrical,Completed,L-Electrical,166,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at K.K. Nagar (NNMP Shed)-2 Centre in Div-166, Zone-Xll . 9 244.192.313 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6126,Electrical,Completed,L-Electrical,166,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at K.K. Nagar School in Div-166, Zone-Xll. ( 244.192.313 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6128,Electrical,Completed,L-Electrical,166,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nehru Nedunchalai (NNMP Shed Opp To B.V. Nagar 10th Street) in Div-166, Zone-Xll . ( 244.190.1496 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6129,Electrical,Completed,L-Electrical,166,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nehru Nedunchalai (NNMP Shed opp To B.V. Nagar 7th Street) in Div-166, Zone-Xll. ( 244.189.990 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6130,Electrical,Completed,L-Electrical,166,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nehru Nedunchalai (Street Light Maintenance AE/JE Office) in Div-166, Zone-Xll. ( 244.190.970 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/10118,Parks,Completed,NM-ALANDUR,166,645000,"CONSTRUCTION OF COMPOUND WALL ROAD SIDE PARK AT NERHU HIGH ROAD ROAD IN DN-166,U-37,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/10993,Buildings,Completed,NM-ALANDUR,166,48000,"IMPROVEMENTS WORKS TO AMMA UNAVAGAM AT B.V. NAGAR 3RD MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/10994,Roads,Completed,NM-ALANDUR,166,223000,"PROVIDING THERMO PLASTIC COMPOUND OF EXISTING SPEED BREAKERS AT VARIOUS STREETS IN DIV 166,UNIT 37,ZONE 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/11828,Culvert,Completed,NM-ALANDUR,166,218000,"CONSTRUCTION OF MISSING LINK TO STORM WATER DRAIN AT JOSEPH 2ND STREET IN DN - 166, Z-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/13351,Buildings,Completed,NM-ALANDUR,166,127000,"REPAIR AND MAINTENANCE WORKS TO AMMA KUDINEER AT TEACHERS COLONY 1ST STREET IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/13352,Buildings,Completed,NM-ALANDUR,166,113000,"REPAIR AND MAINTENANCE WORKS TO COMMUNITY HALL AT NEHRU COLONY MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/13452,Roads,Completed,NM-ALANDUR,166,16000,"ATTENDING CONCRETE PATCH WORK AT KUMARAN STREET (GANDHI NAGAR) IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/14138,Electrical,Completed,NM-ALANDUR,166,507300,Erection of 21 nos of 3 mtrs GI lamp posts with single arch bracket with 20 watts LED fittings and 2 nos of 6 mtrs lamp posts with 150W LED fitting at Anna street Park in division 166 in zone -XII.,Own Sources,12,2018-19,2020-21 NM/2018-19/14188,Parks,Completed,NM-ALANDUR,166,193000,"IMPROVEMENTS WORKS TO ANNA PARK AT ANNA STREET SUMP,COMPOUND WALL COLOUR WASHING GRENEERY IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/16213,Parks,Completed,NM-ALANDUR,166,105000,ANNUAL MAINTENANCE OF ANNA PARK IN DN 166 (7MONTHS) 01.09.2018 TO 31.03.2019,Own Sources,12,2018-19,2019-20 NM/2018-19/3077,Roads,Completed,NM-ALANDUR,166,11000,REPAIR WORKS TO STREET NAME BOARD AT VARIOUS STREETS IN DIVISION -166 UNIT-37 ZONE-12,Own Sources,12,2018-19,2019-20 NM/2018-19/5000,Buildings,Completed,NM-ALANDUR,166,175000,"Improvements to Anganvadi at K. K. Nagar main road(213 & 214) in Dn-166, Unit-37,Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/5002,Buildings,Completed,NM-ALANDUR,166,186000,"Improvements to Anganvadi at K. K. Nagar main road(211) in Dn-166, Unit-37,Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/5017,Buildings,Completed,NM-ALANDUR,166,109000,"Improvements to Anganvadi atK. K. Nagar main road(212) in Dn-166,Unit-37, Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/5021,Buildings,Completed,NM-ALANDUR,166,133000,"Improvements to Anganvadi at k.k.nagar main road(210) in Dn-166,Unit-37,Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/6174,Buildings,Completed,NM-ALANDUR,166,59000,"Improvements to Anganvadi at Nehru street (215) in Dn-166,Unit-37,Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/6229,Buildings,Completed,NM-ALANDUR,166,69000,"Improvements to Anganvadi at Nehru High Road (202) in Dn-166,Unit-37, Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/7018,Buildings,Completed,NM-ALANDUR,166,97000,"REPAIR WORKS TO GYM AT B.V. NAGAR 3RD MAIN ROAD IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/7465,Roads,Completed,NM-ALANDUR,166,595000,"ATTENDING THE PATCH WORKS AT VARIOUS STREETS IN DN-166,U-37,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/7734,Storm Water Drain,Completed,NM-ALANDUR,166,424000,"DESILTING AND MANHOLE DOOR REPAIR WORKS AT VARIOUS STREETS IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2018-19 NM/2018-19/9369,Buildings,Completed,NM-ALANDUR,166,106000,"IMPROVEMENTS TO AMMA UNAVAGAM AT NEHRU NEDUNCHALAI IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2019-20 NM/2018-19/9566,Buildings,Completed,NM-ALANDUR,166,240000,"IMPROVEMENTS WORKS TO UPHC BUILDING AT K.K. NAGAR MAIN ROAD IN DN - 166, U - 37, Z -12.",Own Sources,12,2018-19,2019-20 NM/2018-19/9568,Buildings,Completed,NM-ALANDUR,166,24000,"IMPROVEMENTS WORKS TO VETERINARY HOSPITAL AT NEHRU NEDUNCHALAI IN DN - 166, U - 37, Z - 12.",Own Sources,12,2018-19,2019-20 L/2018-19/11961,Electrical,Completed,L-Electrical,167,199500,"Proposal for fixing of 510 nos of LED Fittings & Removal of 510 nos of Sodium Fittings at various locations in Div 164, 166, 167, Z-XII, Alandur",Own Sources,12,2018-19,2020-21 L/2018-19/6115,Electrical,Completed,L-Electrical,167,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 100 Feet Road CI Office in Div-167, Zone-Xll. ( 244.187.847 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6124,Electrical,Completed,L-Electrical,167,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kannan Nagar 1st Main Road (Amma Unavagam Phase-2) in Div-167, Zone-Xll ( 264.654.1433 ).",SMART CITY - ELECTRICAL,12,2018-19,2019-20 L/2018-19/6127,Electrical,Completed,L-Electrical,167,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Nanganallur 100 Feet Road (JE Office) in Div-167, Zone-Xll. 9 244.188.1663 )",SMART CITY - ELECTRICAL,12,2018-19,2019-20 NM/2018-19/10201,Buildings,Completed,NM-ALANDUR,167,998000,"CONSTRUCTION OF COMPOUND WALL FOR ROAD SIDE VACANT LAND AT NANGANALLUR 100 FEET ROAD IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/10223,Parks,Completed,NM-ALANDUR,167,178000,"REPAIR WORKS TO OPEN GYM AT NANGANALLUR 1OO FEET ROAD IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/10862,Buildings,Completed,NM-ALANDUR,167,56800,"MAINTENANCE WORKS TO AMMA UNAVAGAM AT NANGANALLUR 1OO FEET ROAD IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/10865,Buildings,Completed,NM-ALANDUR,167,31000,"MAINTENANCE WORKS TO AMMA UNAVAGAM AT KANNAN NAGAR 1ST MAIN ROAD IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/13327,Buildings,Completed,NM-ALANDUR,167,177000,"Providing Water supply, Drainage connection and Electrical supply in E-Toilet at M.G.R ROAD in Division-167, Unit-36, Zone-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/14136,Electrical,Completed,NM-ALANDUR,167,209400,"Conversion of 24 nos of CFL fitting into 40-50 w LED fitting at 100 feet road SKATING CENTRE,nanganallur in division-167 in zone- XII.",Own Sources,12,2018-19,2020-21 NM/2018-19/14137,Electrical,Completed,NM-ALANDUR,167,390000,Erection of 14 nos of 3 mtrs GI lamp posts with single arch bracket with 20 watts LED fittings and 2 nos of 6 mtrs lamp posts with 150W LED fitting at Eswaran colony street Park in divisions -167 in zone- XII.,Own Sources,12,2018-19,2020-21 NM/2018-19/14836,Parks,Completed,NM-ALANDUR,167,488000,"ANNUAL MAINTENANCE OF INDEPENDENCE DAY PARK IN DN 167, ZONE 12 7months 01.09.2018 to 31.03.2019",Own Sources,12,2018-19,2019-20 NM/2018-19/14837,Parks,Completed,NM-ALANDUR,167,177000,"ANNUAL MAINTENANCE OF NANGANALLUR 46TH STREET PARK IN DN 167, ZONE 12 7months(01.09.2018 to 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/14838,Parks,Completed,NM-ALANDUR,167,177000,"ANNUAL MAINTENANCE OF LAKSHMI NAGAR 7TH STREET PARK IN DN 167, ZONE 12 7MONTHS (01.09.2018 TO 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/14839,Parks,Completed,NM-ALANDUR,167,105000,"ANNUAL MAINTENANCE OF VIJAY AVENUE PARK IN DN 167, ZONE 12 7MONTHS (01.09.2018 TO 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/14840,Parks,Completed,NM-ALANDUR,167,291000,"ANNUAL MAINTENANCE OF HINDU COLONY PARK IN DN 167, ZONE 12 7MONTHS(01.09.2018 TO 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/15768,Parks,Completed,NM-ALANDUR,167,848000,"PROVIDING OPEN GYM MATERIALS AT STATE BANK COLONY PARK IN DIVISION-167,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/15777,Parks,Completed,NM-ALANDUR,167,457000,"PROVIDING OPEN GYM MATERIALS AT VOLTAS COLONY 1ST STREET PARK IN DIVISION-167,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/15778,Parks,Completed,NM-ALANDUR,167,848000,"PROVIDING OPEN GYM MATERIALS AT HINDU COLONY 26TH STREET PARK IN DIVISION-167,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2019-20 NM/2018-19/15779,Parks,Completed,NM-ALANDUR,167,457000,"PROVIDING OPEN GYM MATERIALS AT NANGANALLUR 46TH STREET PARK IN DIVISION-167,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/15781,Parks,Completed,NM-ALANDUR,167,440500,"PROVIDING OPEN GYM MATERIALS AT LAKSHMI NAGAR 4TH STAGE PARK IN DIVISION-167,UNIT-36,ZONE-12.",Own Sources,12,2018-19,2020-21 NM/2018-19/16250,Parks,Completed,NM-ALANDUR,167,105000,ANNUAL MAINTENANCE OF PARK AT JAIN STAFF COLONY IN DN 167 (7MONTHS 01.09.2018 TO 31.03.2019),Own Sources,12,2018-19,2019-20 NM/2018-19/16291,Parks,Completed,NM-ALANDUR,167,105000,"ANNUAL MAINTENANCE OF PARK AT MMTC COLONY, ESWARAN STREET IN DN 167 (7MONTHS - 01.09.2018 TO 31.03.2019)",Own Sources,12,2018-19,2019-20 NM/2018-19/16292,Parks,Completed,NM-ALANDUR,167,110000,ANNUAL MAINTENANCE OF PARK AT KANNIGA COLONY IN DN 167 FOR 7MONTHS 01.09.2018 TO 31.03.2019,Own Sources,12,2018-19,2019-20 NM/2018-19/16293,Parks,Completed,NM-ALANDUR,167,124000,ANNUAL MAINTENANCE OF PARK AT VOLTAS COLONY 1ST STREET IN DN 167 7MONTHS 01.09.2018 TO 31.03.2019,Own Sources,12,2018-19,2019-20 NM/2018-19/16294,Parks,Completed,NM-ALANDUR,167,104000,ANNUAL MAINTENANCE OF PARK AT VOLTAS COLONY 3ST STREET IN DN 167 7MONTHS 01.09.2018 TO 31.03.2019,Own Sources,12,2018-19,2019-20 NM/2018-19/16295,Parks,Completed,NM-ALANDUR,167,188000,ANNUAL MAINTENANCE OF PARK AT LAKSHMI NAGAR 4TH STREET IN DN 167 FOR 7MONTHS 01.09.2018 TO 31.03.2019,Own Sources,12,2018-19,2019-20 NM/2018-19/16537,Parks,Completed,NM-ALANDUR,167,105000,ANNUAL MAINTENANCE OF PARK AT KANNAN NAGAR 1ST CROSS STREET IN DN 167 FOR 7MONTHS (01.09.2018 TO 31.03.2019),Own Sources,12,2018-19,2019-20 NM/2018-19/16538,Parks,Completed,NM-ALANDUR,167,291000,ANNUAL MAINTENANCE OF PARK AT SBI COLONY MAIN ROAD IN DN 167 7MONTHS FROM 01.09.2018 TO 31.03.2019,Own Sources,12,2018-19,2019-20 NM/2018-19/16539,Parks,Completed,NM-ALANDUR,167,181000,ANNUAL MAINTENANCE OF PARK KANNAN NAGAR 1ST MAIN ROAD IN DN 167 7MONTHS (01.09.2018 TO 31.03.2019),Own Sources,12,2018-19,2019-20 NM/2018-19/16550,Parks,Completed,NM-ALANDUR,167,177000,ANNUAL MAINTENANCE OF PARK AT CIVIL AVIATION COLONY IN DN 167 FOR 7MONTHS (01.09.2018 TO 31.03.2019)),Own Sources,12,2018-19,2019-20 NM/2018-19/17630,Roads,Completed,NM-ALANDUR,167,228850,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 26TH STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17631,Roads,Completed,NM-ALANDUR,167,90400,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 26TH STREET 1ST CROSS IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17632,Roads,Completed,NM-ALANDUR,167,99600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 1ST CROSS STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17633,Roads,Completed,NM-ALANDUR,167,137100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 1ST STREET 2ND CROSS IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17634,Roads,Completed,NM-ALANDUR,167,253400,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 25TH STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17635,Roads,Completed,NM-ALANDUR,167,1078600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANALLUR 46TH STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17636,Roads,Completed,NM-ALANDUR,167,114600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT SOUTH B.V NAGAR 1ST STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17637,Roads,Completed,NM-ALANDUR,167,539600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANLLUR 6TH MAIN ROAD IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17638,Roads,Completed,NM-ALANDUR,167,358100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 11TH STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17639,Roads,Completed,NM-ALANDUR,167,852500,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT VENUGOPALAPURAM MAIN ROAD IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17640,Roads,Completed,NM-ALANDUR,167,852500,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT VISHWANATHAPURAM MAIN ROAD IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17641,Roads,Completed,NM-ALANDUR,167,162100,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 3RD STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17642,Roads,Completed,NM-ALANDUR,167,1480400,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT TNGO COLONY MAIN ROAD IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/17643,Roads,Completed,NM-ALANDUR,167,725400,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 1ST STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/3821,Parks,Completed,NM-ALANDUR,167,118000,"IMPROVEMENT WORKS TO THE EXISTING PARK VOLTAS COLONY 1ST STREET PARK AT VOLTAS COLONY 1ST STREET IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/3851,Roads,Completed,NM-ALANDUR,167,604600,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 5th STREET IN DIVISION 167, UNIT 36, ZONE 12.",Own Sources,12,2018-19,2020-21 NM/2018-19/4153,Parks,Completed,NM-ALANDUR,167,233000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENT,REPAIR WORKS TO THE GYM MATERIAL AT EAST MAIN ROAD PARK IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/5305,Roads,Completed,NM-ALANDUR,167,292000,"THERMOPLASTIC PAINTING WORKS TO EXISTING SPEED BREAKER AT VARIOUS STREET IN DIV 167,UNIT 36,ZONE 12.",Own Sources,12,2018-19,2018-19 NM/2018-19/7328,Roads,Completed,NM-ALANDUR,167,972000,"ATTENDING BT PATCH WORK AT VARIOUS STREET IN DN-167,U-37,Z-12",Own Sources,12,2018-19,2019-20 NM/2018-19/8214,Buildings,Completed,NM-ALANDUR,167,1147000,"MAINTENANCE AND REPAIR WORKS TO SHOPPING COMPLEX BUILDING AT NANGANALLUR 39TH STREET IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2020-21 NM/2018-19/8900,Parks,Completed,NM-ALANDUR,167,72000,"REPAIR AND MAINTENANCE WORKS TO INDEPENDENCE PARK AT NANGANALLUR 5TH MAIN ROAD IN DN-167,U-36,Z-12.",Own Sources,12,2018-19,2018-19 NM/2018-19/9789,Storm Water Drain,Completed,NM-ALANDUR,167,396000,"DESILTING AND MANHOLE DOOR REPAIR WORKS FOR VARIOUS STREET IN DN-167,U-36,Z-12",Own Sources,12,2018-19,2019-20 L/2018-19/16319,Electrical,Completed,L-Electrical,168,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at M.G Nagar, Division Office, Div-168, Zone-XIV (E.B.Account no-302-110-1986)",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/11831,Roads,Completed,NP-PERUNGUDI,168,136000,"Formation of Inter Locking Blocks Road at Vembuliamman Koil Street in Dn-168, U-42, Z-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15840,Roads,Completed,NP-PERUNGUDI,168,453000,"ATTENDING B.T ROAD PATCH WORK IN VARIOUS STREETS IN DN-168,UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15924,Parks,Completed,NP-PERUNGUDI,168,219000,"MAINTENANCE ESTIMATE FOR PARK AT LAKSHMI NAGAR 10TH STREET DIV-168, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/2796,Roads,Completed,NP-PERUNGUDI,168,3442000,"RELAYING OF INTERIOR B.T.ROAD AT BALAMMAL NAGAR MAIN ROAD IN DIV-168, U-42, Z-14.",Grants,14,2018-19,2018-19 NP/2018-19/5257,Roads,Completed,NP-PERUNGUDI,168,234000,"Providing thermoplast compound marking to existing IRC standard speed breakers at Various street in DN-168, U-42, Z-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/7665,Roads,Completed,NP-PERUNGUDI,168,592000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIV-168, UNIT-42, ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/7925,Electrical,Completed,NP-PERUNGUDI,168,515800,"Supply and erection of 8 nos of 6mtr Hot Dip Lamp Post with 40w LED fitting in Usha Nagar Burial Ground, division-169, Zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/8903,Roads,Completed,NP-PERUNGUDI,168,1740000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT MATHIAZHAGAN STREET,USHA NAGAR 3RD STREET, VIDHYA NAGAR 2ND & 3RD STREET, NSC BOSE ROAD, SABAPATHY STREET AND NAVALUR STREET IN DN-168, U-42, Z-14.",Deposit Works,14,2018-19,2019-20 NP/2018-19/9348,Storm Water Drain,Completed,NP-PERUNGUDI,168,1803000,"DESILTING OF STORM WATER DRAIN, SIDE DRAIN AND VEERANGAL OODAI IN DN-168 & DN-169 , UNIT-42, ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/9515,Storm Water Drain,Completed,NP-PERUNGUDI,168,789000,"MINOR REPAIR WORKS IN DN-168,169,186,189,190, AND 191 UNIT-41,UNIT-42 AND UNIT-43, ZONE-14",Own Sources,14,2018-19,2018-19 D/2018-19/15007,Storm Water Drain,Completed,D-Storm Water Drains,169,29470000,"Construction of Storm Water Drain of size 1200 x 1200mm along Ramalingam nagar main road from Bazaar road to Veerangal odai Dn.-169,Zone - XIV,Package - 21.",SMART CITY - SWD,14,2018-19,2020-21 D/2018-19/8533,Storm Water Drain,Completed,D-Storm Water Drains,169,24138000,"Restoration and other improvements to pulithivakkam lake for augmentation of water supply in Dn - 169, Zone -14.",SMART CITY - SWD,14,2018-19,2020-21 L/2018-19/16320,Electrical,Completed,L-Electrical,169,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Office Building, Puzhuthivakkam, Div-169, Zone-XIV (E.B.Account no-302-102-217)",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/16321,Electrical,Completed,L-Electrical,169,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC, Puzhuthivakkam, Div-169, Zone-XIV (E.B.Account no-302-106-1470)",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/11046,Buildings,Completed,NP-PERUNGUDI,169,745000,"MAINTENANCE OF GASIFIER CREMATORIUM AT PUZHUTHIVAKKAM BURIAL GROUND IN DN.169, U-42, ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/11048,Parks,Completed,NP-PERUNGUDI,169,2141000,"Construction of Compound wall in OSR land at Balaji Nagar 24th Street, at div -169, Unit-42, Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/11240,Electrical,Completed,NP-PERUNGUDI,169,1437900,"Maintenance work in various parks in division-169,183,184,185,186,189 and 191, Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/11546,Roads,Completed,NP-PERUNGUDI,169,1116100,"ROAD CUT RESTORATION WORK IN SENKANIAMMAN KOIL STREET, MANDAVELI STREET, HINDUCOLONY 2ND MAIN ROAD, GANESH NAGAR 7TH STREET, ANNAI THERASA NAGAR 12TH STREET, PUZHUTHIVAKKM MAIN ROAD IN DIV 169, UNIT-42, ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/11833,Buildings,Completed,NP-PERUNGUDI,169,1003000,"CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT ANDAVAR STREET, AT DIV-169, U-42, Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/12132,Buildings,Completed,NP-PERUNGUDI,169,1476000,"Outsourcing of Sweeping/Scavenging work for Primary schools, Middle Schools, High Schools, Higher Secondary School for a period of Five months, Thirteen Schools, Dn- 168,169,183,184,185,186,188,190,191 in Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/12134,Buildings,Completed,NP-PERUNGUDI,169,128000,"Supplying and Fixing of hume pipe at balaji nagar main road (puzhuthivakkam bus stand), Sundarajan salai, Gangai street, Ramalingam street in Dn.169, U.42, Z.14",Own Sources,14,2018-19,2019-20 NP/2018-19/15810,Electrical,Completed,NP-PERUNGUDI,169,1489100,"Proposed to Replace and Purchase of 31 Nos of Ceiling Fan, 14Nos of Exhaust Fan, 9nos of Water Heater, 4Nos of UV/RO Plant, 9nos of Wall Mounting fan, 5Nos of Weighing Machine, 7No of freezer and 11Nos of mixer in Amma Unavagam in Dn-168,169,183 to 191 in Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15811,Roads,Completed,NP-PERUNGUDI,169,1648000,"ATTENDING THE BT PATCH WORK AT VARIOUS STREETS IN DIV-169, U-42, Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15903,Parks,Completed,NP-PERUNGUDI,169,227000,"MAINTENANCE ESTIMATE FOR PARK AT HINDU COLONY IN DIV-169, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15906,Parks,Completed,NP-PERUNGUDI,169,868000,"MAINTENANCE ESTIMATE FOR PARK AT BALAJI NAGAR 19TH STREET IN DIV-169, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15908,Parks,Completed,NP-PERUNGUDI,169,257000,"MAINTENANCE ESTIMATE FOR PARK AT BALAJI NAGAR EXTN SOUTH IN DIV-169, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15909,Parks,Completed,NP-PERUNGUDI,169,590000,"MAINTENANCE ESTIMATE FOR PARK AT AGS COLONY IN DIV-169, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15912,Parks,Completed,NP-PERUNGUDI,169,582000,"MAINTENANCE ESTIMATE FOR PARK AT ANNAI THERASA 14TH STREET IN DIV-169, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15914,Parks,Completed,NP-PERUNGUDI,169,585000,"MAINTENANCE ESTIMATE EPR NAGAR AT IN DIV-169, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15943,Parks,Completed,NP-PERUNGUDI,169,234000,"MAINTENANCE ESTIMATE FOR PARK AT AYYAN THIRUVALLUVAR PARK IN DIV-169, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15973,Electrical,Completed,NP-PERUNGUDI,169,751600,"Maintenance work in various parks in division-168,169,187, Unit-42, Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/2784,Roads,Completed,NP-PERUNGUDI,169,4538000,"RELAYING OF INTERIOR B.T.ROAD AT MURUGAPPA SALAI IN DN-169, U-42, Z-14",Grants,14,2018-19,2018-19 NP/2018-19/2908,Roads,Completed,NP-PERUNGUDI,169,1729000,"FORMING OF CC ROAD AT ANNAI THERASA NAGAR 5TH STREET IN DIV - 169, UNIT - 42, ZONE - 14",Grants,14,2018-19,2019-20 NP/2018-19/3046,Buildings,Completed,NP-PERUNGUDI,169,32500,GASIFIER AWARNESS BOARD 3 Ft X 2 Ft AT VARIOUS LOCATIONS AT ZONE-14,Own Sources,14,2018-19,2018-19 NP/2018-19/3104,Roads,Completed,NP-PERUNGUDI,169,1745000,"FORMING OF CC ROAD AT ANNAI THERASA NAGAR 6TH STREET IN DIV - 169, UNIT - 42, ZONE -14",Grants,14,2018-19,2019-20 NP/2018-19/3252,Parks,Completed,NP-PERUNGUDI,169,2326000,"IMPROVEMENTS TO IYYAN THIRUVALLUVAR PARK IN DN-169, U-42, ZONE-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/3455,Roads,Completed,NP-PERUNGUDI,169,966000,"Relaying of B.T. Road at Ramalingam Nagar 1st Street Extension in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3467,Roads,Completed,NP-PERUNGUDI,169,105000,"Relaying of B.T. Road at Vaigai Street(Part) in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3469,Roads,Completed,NP-PERUNGUDI,169,149000,"Relaying of B.T. Road at Vallal Kuman Street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3472,Roads,Completed,NP-PERUNGUDI,169,582000,"Relaying of B.T. Road at Sivasubramaniyum Street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3479,Roads,Completed,NP-PERUNGUDI,169,482000,"Relaying of B.T. Road at Bharathi Street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3480,Roads,Completed,NP-PERUNGUDI,169,264000,"Relaying of B.T. Road at Jaya Nagar 1st street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3484,Roads,Completed,NP-PERUNGUDI,169,187000,"Relaying of B.T. Road at Dharabarathi Street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3487,Roads,Completed,NP-PERUNGUDI,169,105000,"Relaying of B.T. Road at Balaji Nagar 9th Street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3595,Roads,Completed,NP-PERUNGUDI,169,89000,"Relaying of B.T. Road at Hindu Colony 1st Cross Street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3598,Roads,Completed,NP-PERUNGUDI,169,1730000,"Relaying of B.T. Road at Balaji Nagar Main road in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3602,Roads,Completed,NP-PERUNGUDI,169,636000,"Relaying of B.T. Road at Sivaprakasam Nagar 1st street in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3603,Roads,Completed,NP-PERUNGUDI,169,835000,"Relaying of B.T. Road at Sivaprakasam Nagar 2ndstreet in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3605,Roads,Completed,NP-PERUNGUDI,169,804000,"Relaying of B.T. Road at Sivaprakasam Nagar 2nd Main road in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/3606,Roads,Completed,NP-PERUNGUDI,169,523000,"Relaying of B.T. Road at N.S.C Boss Road in DN-169, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/7321,Buildings,Completed,NP-PERUNGUDI,169,894000,"Outsourcing of Sweeping/Scavenging work for Primary schools, Middle Schools, High Schools, Higher Secondary School for a period of Three months, Thirteen Schools, Dn- 168,169,183,184,185,186,188,190,191 in Z-14",Own Sources,14,2018-19,2018-19 NP/2018-19/7657,Roads,Completed,NP-PERUNGUDI,169,3000000,"CONSTRUCTION OF BUS SHELTER, CC FLOORING, & PASSENGERS SEATING AT PUZHUTHIVAKKAM BUS STAND IN DIV.169, U-42, Z-14",MLACDS,14,2018-19,2020-21 NP/2018-19/7723,Roads,Completed,NP-PERUNGUDI,169,941500,"REPAIRS AND IMPROVEMENT OF PATCH WORK IN VARIOUS STREET IN DN-169, U-42, Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/9897,Electrical,Completed,NP-PERUNGUDI,169,302600,"Procuring 5 nos of Office tables, 4 nos of Computer tables, 5 nos of S Type chairs, 4 nos of Beros and 1 no of Executive Chair for Electrical Department Division ? 183,184, Unit ? 41, Division-169,187, Unit-42 and Division-190, Unit ? 43, Zone-14.",Own Sources,14,2018-19,2018-19 B/2018-19/2921,Buildings,Completed,B-Buildings,170,25450589,Repairs and improvements to chennai school at various Locations in Zone-13,Own Sources,13,2018-19,2019-20 B/2018-19/3658,Buildings,Completed,B-Buildings,170,9914000,"PROPOSED CONSTRUCTION FOR UPHC BUILDING AT ADAMBAKKAM IN DIV-177,ZONE-13.",Grants,13,2018-19,2020-21 BR/2018-19/5961,Road Cut,Completed,BR-Bus Route Roads,170,70000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT POOMAGAL MAIN ROAD &33 FEET ROAD IN DIV-170, ZONE-13(57/0667/2017-18) PACKAGE-11.",Deposit Works,13,2018-19,2019-20 L/2018-19/12290,Electrical,Completed,L-Electrical,170,188000,"Replacement of 11 Nos. of Completely damaged 63 AMP/3 phase Analogue single dial Automatic Street Lighting ON /OFF Controlling TIMER UNITS At Various Locations In Div-170, Guindy Section ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/15044,Electrical,Completed,L-Electrical,170,199600,"PROVISION OF PAINTING AND NUMBERING OF 464 NOS 6/7 MTR AND 8/9 MTR STREET LIGHTS POLE 76 NOS OF KOISK PILLAR BOXES WITH SINGLE COST ALUMINIUM PAINT AT KATHIPARA TO CHELLAMMAL COLLEGE ANNA SALAI BOTH SIDE AND CENTRE MEDIAN AND NEHRU SALAI TO KASI THEATER BRIDGE,VELACHERY 100FT ROAD,KAKKAN NGR MAIN ROAD IN DIV-170,177,ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/16591,Electrical,Completed,L-Electrical,170,198900,"PROVISION OF PA SYSTEM AT CHSS,MUDUVANKARAI,GUINDY IN DIVISIN-170,ZONE-13",MLACDS,13,2018-19,2019-20 L/2018-19/2519,Electrical,Completed,L-Electrical,170,737000,"Provision of 18nos of 6mtr GI lamp post Single Straight Bracket With Laying of cable 681Mtrs at Narayanansamy 3rd Street and Vinayagapuram Surrounding Street Div-170,Zone-13",Own Sources,13,2018-19,2018-19 L/2018-19/6232,Electrical,Completed,L-Electrical,170,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Maduvankarai , chinnamalai High School in Div -170, Zone-XIII.(E.B ACCOUNT NO 211.030.326)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6234,Electrical,Completed,L-Electrical,170,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ekkattuthangal Primary School in Div-170, Zone-XIII (E.B.Account no211.030.326)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6236,Electrical,Completed,L-Electrical,170,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Neurppumedu Guindy Noon meal centrei in Div-170, Zone-XIII",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6240,Electrical,Completed,L-Electrical,170,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Alandur, Opp to Olympia Tower E-Seva Maiyam in Div-170, Zone-XIII",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/10767,Roads,Completed,NN-ADYAR,170,332000,Supply of garbage dust bins in two different colours of capacity 100litres (Robo moulds) (17Nos) in commercial areas at various streets in Zone - XIII,Own Sources,13,2018-19,2019-20 NN/2018-19/11073,Footpath,Completed,NN-ADYAR,170,781000,"Improvements to the Bus Shelter at Jawarhalal Nehru Salai (Ambal Nagar) 2nos and Kathipara Road 2nos in division 170, Unit 40(A), Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/11075,Buildings,Completed,NN-ADYAR,170,459000,"Providing Bio-Shredding Pulverizer Machine, Manure Seiver Machine and Weighing Machine including Civil and Electrical work in Division 170, Unit 40(A), Zone-13. (As per circular No.R.O/South/A.E.E/Spl/2018, Date:13.09.2017)",Own Sources,13,2018-19,2019-20 NN/2018-19/13203,Buildings,Completed,NN-ADYAR,170,73000,PROVIDING BARRIGADING WORK AT ADYAR RIVER IN DIVISION -170 UNIT-40(A) ZONE-13,Own Sources,13,2018-19,2018-19 NN/2018-19/13903,Buildings,Completed,NN-ADYAR,170,1300000,"Proposed Construction of Multipurpose building at Poonamallee Road in Division 170, Unit 40(A), Zone 13 using MLA (Saidapet) Fund for the year 2018-19.",MLACDS,13,2018-19,2020-21 NN/2018-19/14010,Buildings,Completed,NN-ADYAR,170,116000,"Repairs and Improvements to the Amma Unavagam at Reddy street and Kathipara Road in Division 170, Unit 40(A), Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/14651,Buildings,Completed,NN-ADYAR,170,800000,"PROVIDING RO PURIFIER 1000 LPH AT CHENNAI HIGHER SECONDARY SCHOOL IN DIVISION - 170, UNIT-40A, ZONE-13.",MLACDS,13,2018-19,2019-20 NN/2018-19/14664,Buildings,Completed,NN-ADYAR,170,831000,"Repairs to damaged roof in Public Convenience at Reddy 2nd street in Division - 170, Unit - 40(A), Zone - 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14801,Buildings,Completed,NN-ADYAR,170,1267000,"Repairs and improvement to the Division 170 Office Building in Division - 170, Unit - 40(A), Zone - 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/15013,Buildings,Completed,NN-ADYAR,170,312000,"PROVIDING DIGITAL NAME BOARDS FOR AWARENESS AT THE BUS SHELTER AT JAWAHARLAL NEHRU SALAI (AMBAL NAGAR) West and East Side IN DIVISION 170,UNIT 40(A),ZONE -13.",Own Sources,13,2018-19,2019-20 NN/2018-19/18013,Parks,Completed,NN-ADYAR,170,188000,"Annual Park Maintenance For Park At Centrale\ Exeise Coiony in Dn-170, U-40A, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18031,Parks,Completed,NN-ADYAR,170,130000,"ANNUAL MAINTENANCE FOR PARK AT LABOUR COLONY IN DN-170, ZONE-13,(6 MONTHS) AREA = 1330 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/2038,Roads,Completed,NN-ADYAR,170,693000,"Providing Single (58Nos) & Double (59Nos)Compactor bin platforms at various streets in Divisions - 170, 174 & 177, Unit - 40A, Zone - XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/2625,Buildings,Completed,NN-ADYAR,170,2524000,Conversion of Gasifier to LPG of Burial Ground at Arulayammanpet 2nd Street in Division 170 unit 40A zone 13,Own Sources,13,2018-19,2019-20 NN/2018-19/2661,Roads,Completed,NN-ADYAR,170,593000,"Conversion of Existing Spreed breaker to IRC standards in various Street in division 170, Unit 40A, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2896,Footpath,Completed,NN-ADYAR,170,705000,"Improvements to the foothpath at Pumping Station road & Labour Colony Main Road in dn-170,Unit-40A,Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/3544,Footpath,Completed,NN-ADYAR,170,24000,"Repairs to the Damaged Street Name boards at various Location in Division 170, Unit 40A, Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/6326,Roads,Completed,NN-ADYAR,170,437000,"Attending B.T. Road Patch Work In Various Street in Div-170, Unit - 40(A), Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7970,Storm Water Drain,Completed,NN-ADYAR,170,1914000,"Minor Repair works to Storm Water Drains at Various Location in Division 170, Unit 40(A), Zone 13",Own Sources,13,2018-19,2018-19 NN/2018-19/7971,Storm Water Drain,Completed,NN-ADYAR,170,1828000,"De-Silting of Storm Water Drain at Various Location in Division 170, Unit 40(A), Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/8033,Parks,Completed,NN-ADYAR,170,63000,"Repairs and Improvements to the Road Side Park at Reddy 2nd Street in Division 170, Unit 40(A), Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8800,Buildings,Completed,NN-ADYAR,170,307000,"Repairs and Improvements to the 16th Day Ceremony Hall at Manjolai 1st Main Road in Division 170, Unit 40(A), Zone 13.",Own Sources,13,2018-19,2018-19 BR/2018-19/0703,Roads,Completed,BR-Bus Route Roads,171,553000,"PAINTING WORK FOR CENTRE MEDIAN AND FOOT PATH AT SARDAR PATEL ROAD (FROM THE JUNCTION OF MADHYA KAILASH TO ANNA SALAI ) IN DIV-171, ZONE-13.",Own Sources,13,2018-19,2019-20 BR/2018-19/1399,Roads,Completed,BR-Bus Route Roads,171,345000,"PAINTING WORK FOR CENTRE MEDIAN AND FOOT PATH AT SARDAR PATEL ROAD (FROM THE JUNCTION OF ADYAR SIGNAL TO MADHYA KAILASH ) IN DIV-171, ZONE-13.",Own Sources,13,2018-19,2019-20 BR/2018-19/17492,Roads,Completed,BR-Bus Route Roads,171,2015000,"PROVIDING AND LAYING OF HOT APPLIED THERMOPLASTIC PAINTING WORK AT SARDAR PATEL ROAD(FROM THE JUNCTION OF GANDHI MANDAPAM ROAD TO ADYAR SIGNAL), DURGABAI DESHMUKH ROAD, R.K MUTT ROAD(PART), BRADDIES CASTLE ROAD, GREENWAYS ROAD, DGS DINAKARAN SALAI (PART) IN VIEW OF GLOBAL INVESTOR MEET AND REPUBLIC DAY 2019 IN ZONE-13",Own Sources,13,2018-19,2019-20 BR/2018-19/17771,Roads,Completed,BR-Bus Route Roads,171,2500000,"PROVIDING AND LAYING OF HOT APPLIED THERMOPLASTIC PAINTING,STUD, AND DELINEATOR AT VARIOUS BUS ROUTE ROADS IN ZONE- V , IX, X ,XII, XIII",Own Sources,13,2018-19,2019-20 BR/2018-19/18023,Roads,Completed,BR-Bus Route Roads,171,1020000,REPAIRS TO THE EXISTING GCC STAINLESS STEEL BUS SHELTERS AT VARIOUS ZONES 13 & 15 (GIM) FOR THE YEAR 2018-19,Own Sources,13,2018-19,2019-20 BR/2018-19/18024,Roads,Completed,BR-Bus Route Roads,171,980000,REPAIRS TO THE EXISTING GCC STAINLESS STEEL BUS SHELTERS AT VARIOUS ZONES 13 (GIM) FOR THE YEAR 2018-19,Own Sources,13,2018-19,2019-20 BR/2018-19/6171,Roads,Completed,BR-Bus Route Roads,171,1068000,"Footpath Repair works at Gandhi Mandapam Road in Dn-171, Zone - XIII",Grants,13,2018-19,2019-20 BR/2018-19/7983,Road Cut,Completed,BR-Bus Route Roads,171,355000,"RESTORATION OF ROAD CUT MADE BY TANGEDCO AT LINK ROAD IN DIV-171,ZONE-13.",Deposit Works,13,2018-19,2018-19 D/2018-19/14960,Storm Water Drain,Completed,D-Storm Water Drains,171,30250000,"Construction of Storm Water Drain at Gandhi Mandapam Road West Left Side on East side from Cancer Institute to Anna Gem Science Park School in Dn.-171,Zone-13,Package - 18.",SMART CITY - SWD,13,2018-19,2020-21 D/2018-19/14961,Storm Water Drain,Completed,D-Storm Water Drains,171,30396000,"Construction of Storm Water Drain at Gandhi Mandapam Road West Right Side on East side from Cancer Institute to Anna Gem Science Park School in Dn.-171,Zone-13,Package - 19.",SMART CITY - SWD,13,2018-19,2020-21 L/2018-19/11164,Electrical,Completed,L-Electrical,171,198500,ADDITIONAL AND REWIRING OF ARANAGANATHAN SUBWAY IN SAIDAPET DV-171 Z-XIII,Own Sources,13,2018-19,2019-20 L/2018-19/12537,Electrical,Completed,L-Electrical,171,1893000,PROVISION OF SUPPLY AND ERECTION OF 9 MTR LAMP POST 14 NOS AND 6MTR LAMP POST 2 NOS WITH LAYING OF 4X16 SQ MM ALL CABLE 729 MTRS AT SAIDAPET ANNA SALAI IN DIV-171 ZONE-XIII,Own Sources,13,2018-19,2019-20 L/2018-19/13516,Electrical,Completed,L-Electrical,171,178000,REPLACEMENT OF DAMAGED AND RUSTED 3 NOS KIOSK PILLAR BOXES AT SARDAR PATEL ROAD IN DV-171 IN ZONE -XIII,Own Sources,13,2018-19,2020-21 L/2018-19/14875,Electrical,Completed,L-Electrical,171,193500,"PROVISION OF PAINTING AND NUMBERING OF 527 NOS 9.2 Mtrs AND 8Mtrs AND 6/7 Mtrs LAMP POST ANNA SALAI AND SARDAR PATEL ROAD AND GANDHIMANDAPAM ROAD AND SAIDAPET,IIT,KOTTURPURAM BRIDGES IN DV-171 &172 IN ZONE -XIII",Own Sources,13,2018-19,2019-20 L/2018-19/5315,Electrical,Completed,L-Electrical,171,903000,"PROVISION OF ADDITIONAL & RE-WIRING AT CPS SCHOOL AT SAIDAPET VENGATAPURAM&CHITRA NAGAR, KTTURPURAM IN DIV-171,172, ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/6144,Electrical,Completed,L-Electrical,171,1515800,"ESTIMATE for Supply, Installation, Testing & Commissioning of 20 Kwp Grid Tied Solar Rooftop including Civil works and earthing for RICHARDS PARK AE/171 OFFICE IN DIV 171, ZONE-XIII (A/C.NO 207.041.313).",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6147,Electrical,Completed,L-Electrical,171,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for NNMP SHEAD , KAVERI NAGAR, DIV-171, Zone - XIII. ( E.B Account Number : 271.034.355)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6148,Electrical,Completed,L-Electrical,171,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for NIGHT SHELTER, KAVERI NAGAR, DIV-171, Zone - XIII. ( E.B Account Number : 271.030.114)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6149,Electrical,Completed,L-Electrical,171,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for NNMP SHED Venkatapuram, in Div-171, Zone - XIII. (E.B Account Number : 262.010.1140)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6153,Electrical,Completed,L-Electrical,171,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing for VENKATAPURAM SCHOOL , SAIDAPET, DIV 171, ZONE.XIII (Account no:262.010.951)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6154,Electrical,Completed,L-Electrical,171,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing for KANNAMAPET HOSPITAL, HOSPITAL ROAD IN DIV-171, ZONE-XIII (E.B.Account no: 271.026.101)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/0777,Buildings,Completed,NN-ADYAR,171,44000,Demolishing the dilateded building at electrical street light building at richards pak campus in div-171 unit-40 zone-13,Own Sources,13,2018-19,2018-19 NN/2018-19/10698,Roads,Completed,NN-ADYAR,171,55000,"PROVIDING PATCH WORK FOR DAMAGED BITUMINOUS ROAD AT NORTH ROAD WEST CIT NAGAR, MODEL HUTMENT ROAD, SCHOOL ROAD, SRI NAGAR COLONY SOUTH AVENUE, SOUTH MADA STREET, BHARATHI DASAN STREET, TEMPLE AVENUE, PONNIAMMAN KOIL STREET IN DN 171, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/10766,Road Cut,Completed,NN-ADYAR,171,1273000,"Restoration of roadcut made by CMWSSB at Government Farm Main road,1st and 2nd street in Dn.171,Unit-40,Zone-13.",Deposit Works,13,2018-19,2018-19 NN/2018-19/11237,Buildings,Completed,NN-ADYAR,171,3233000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT RICHARDS PARK ,ANNA SALAI IN DN.171,UNIT-40,ZONE-13.",Grants,13,2018-19,2019-20 NN/2018-19/14128,Buildings,Completed,NN-ADYAR,171,123000,"IMPROVEMENTS TO AMMA UNAVAGAM AT RAILWAY BORDER Ist STREET IN DN.171,UNIT-40,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14175,Roads,Completed,NN-ADYAR,171,520000,"ATTENDING CEMENT CONCRETE PATCHES AT VARIOUS STREETS IN DN-171, UNIT-40,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/15152,Buildings,Completed,NN-ADYAR,171,202000,Providing galvanized zinc sheet partition( to deface the hut dwellers of venkatapuram )at Taluk office road and defacind the walls of political letter writtings at taluk office road and sardar patel road in Dn:171 Unit:40 Zone:13,Own Sources,13,2018-19,2019-20 NN/2018-19/15193,Electrical,Completed,NN-ADYAR,171,1191000,"Proposed Supply and Fixing of 6 nos 15 Ltr Pulvarizer , 2 Nos 10 Litres Grinder , 7 Nos 300 Litres Cooler, and 9 Nos Three Jar Commercial Mixer at Various Location Amma Unavagams in Dn-170 to 182 in Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/15244,Electrical,Completed,NN-ADYAR,171,123500,"Proposed Supply and Fixing of 13 Nos of T/L Fitting, 19 Nos of Ceiling Fan, 9 Nos of Wall Mount Fan, 11 Nos of Exhaust Fan, 3 Nos Water Heater at Various Location Amma Unavagams in Dn-170 to 182 in Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/16152,Parks,Completed,NN-ADYAR,171,156000,"ANNUAL MAINTENANCE FOR PARK AT CHINNAMALAI PARK (HALDA) IN DN-171, ZONE-13(PER SIX MONTHS) AREA = 1300 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/17889,Roads,Completed,NN-ADYAR,171,457000,"Relaying of Bitumen Concrete Road at Govt farm main road in DN-171, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17890,Roads,Completed,NN-ADYAR,171,755000,"Relaying of Bitumen Concrete Road at Ranjith road & Ferri road in DN-171, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17891,Roads,Completed,NN-ADYAR,171,971000,"Relaying of Cement Concrete Road at Chinnaiya thottam & Soodiammanpet road in DN-171, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17897,Roads,Completed,NN-ADYAR,171,820000,"Relaying of Bitumen Concrete Road at Govt farm 1 road in DN-171, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17898,Roads,Completed,NN-ADYAR,171,820000,"Relaying of Bitumen Concrete Road at Govt farm 2 road in DN-171, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/18085,Parks,Completed,NN-ADYAR,171,148700,"ANNUAL MAINTENANCE FOR PARK AT CHINNAMALAI PARK (HALDA) IN DN-171, ZONE-13(PER SIX MONTHS) AREA = 1300 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/2029,Roads,Completed,NN-ADYAR,171,1703000,"Providing Single ( 294Nos) & Double (51Nos) Compactor bin platforms at various streets in Divisions - 171, 172, 173 & 175, Unit - 40, Zone - XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/2149,Playfields,Completed,NN-ADYAR,171,872000,"Improvements to gym buding at surya nagar and subbupillai thottam in Div-171,Unit-40,Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2178,Roads,Completed,NN-ADYAR,171,466000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at north road, east road, south road, west road and 1&3 cross streets in west C.I.T nagar in Div-171, Unt-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2986,Buildings,Completed,NN-ADYAR,171,351000,"Improvements to play field at subbupillia thottam in DN171, U-40, Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/6134,Buildings,Completed,NN-ADYAR,171,1354000,"ADDITION CONSTRUCTION OF HEAD ROOM,STAIRECASE PORTION,DRESSING ROOMS AND TOILET OF MULTIPURPOSE HALL AT GOVERNMENT FARM IN DN 171,UNIT 40,ZONE 13(UNDER MLA FUND)",MLACDS,13,2018-19,2019-20 NN/2018-19/6394,Buildings,Completed,NN-ADYAR,171,75000,"Additional Improvement works to night shelter at railway border 1st street in DN171, U-40, Z-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7406,Parks,Completed,NN-ADYAR,171,64000,"Providing Greenery to the Traffic Island at Taluk-office road ( Rajiv Gandhi statue ) and Center Median at 70 feet road in DN 171, Unti-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7853,Storm Water Drain,Completed,NN-ADYAR,171,421000,"Desilting of Storm water drain(0.9 X.0.9 )at various streets in Dn 171, unit-40, zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7871,Storm Water Drain,Completed,NN-ADYAR,171,2373000,"Repairs to storm water drain ( 0.9 X 0.9 ) at various streets in Dn 171, unit-40, Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7903,Storm Water Drain,Completed,NN-ADYAR,171,14000,"Desilting of SWD (0.6 X.0.6m) at various streets in Dn171, Unit-40, Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7909,Storm Water Drain,Completed,NN-ADYAR,171,253000,"Repairs to SWD (0.6X0.6m) at various streets in Dn 171, Unit-40, Zone-13",Own Sources,13,2018-19,2018-19 NN/2018-19/7912,Storm Water Drain,Completed,NN-ADYAR,171,115000,"Desilting of SWD ( 1.2 X 1.2m ) at Gandhimandapam Road ( Birla planterium to lake view road canal ) in Dn 171, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7988,Storm Water Drain,Completed,NN-ADYAR,171,1257000,"Providing High density polyethylene pipe 315mm dia for the disposal of rain water stagnation at Gandhi mandapam road (in front of madras university campus and Anna centenary library, Chronicle point) in Dn171, Unit-40, Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7989,Storm Water Drain,Completed,NN-ADYAR,171,1250000,"Providing High density polyethylene pipe 315mm dia for the disposal of rain water stagnation at Sardar patel road ( in front of Ashok leyland), Taluk office Road ( in front of All india Radio), Velachery main road ( opp to A2B ) in Dn171, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8150,Footpath,Completed,NN-ADYAR,171,500000,"Improvements to the existing user friendly pavement for physically challenged children school at Ranjith road in Dn 171, Unit-40, Zone-13.",Own Sources,13,2018-19,2018-19 P/2018-19/11630,Parks,Completed,P-Parks and Playfields,171,386000,"IMPROVEMENTS TO CENTRE MEDIAN AT GANDHI MANADAPAM ROAD (FROM PATTINAPAKKAM SIGNAL TO GREENWAYS ROAD JUNCTION AND JN OF SARDHAR PATEL ROAD TO KOTTURPURAM BRIDGE) IN DN-171 AND 172, ZONE -13 (540 Mts)",Own Sources,13,2018-19,2019-20 BR/2018-19/18199,Roads,Completed,BR-Bus Route Roads,172,1249000,"PROVIDING CENTRE MEDIAN AT SARDAR PATEL ROAD [FROM THE JN OF KPN SIGNAL TO MADYA KAILASH] IN ZONE -13, DIV- 172",Own Sources,13,2018-19,2019-20 BR/2018-19/18275,Roads,Completed,BR-Bus Route Roads,172,2740000,Traffic Improvement Works at Various Bus Route Roads in Zone -XIII,Own Sources,13,2018-19,2019-20 L/2018-19/1405,Electrical,Completed,L-Electrical,172,941000,"PROVISION OF REMOVAL OF 19 NOS 9 MTR LAMP POST AND 13 NOS 6 MTR LAMP POST AND ERECTION OF 10 NOS 9MTR LAMP POST WITH 150-165 W LED FITTING AT SARDAR ROAD, GUINDY IN DIV-172 ZONE-XIII",Own Sources,13,2018-19,2018-19 L/2018-19/6156,Electrical,Completed,L-Electrical,172,1892000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 25 Kwp Grid Tied Solar Rooftop including Civil works and earthing for NEW STREET SCHOOL KOTTUR IN DIV 172, ZONE-XIII (A/C.NO 220.012.89).",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6159,Electrical,Completed,L-Electrical,172,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing for CHITRA NAGAR SCHOOL KOTTURPURAM DIV-172, Zone-XIII (E.B.Account no: 262.014.910)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6162,Electrical,Completed,L-Electrical,172,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing for KOTTURPURAM HOSPITAL DHANDAPANI STREET, DIV-172, ZONE-XIII (E.B.Account no: 262.004.172)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6163,Electrical,Completed,L-Electrical,172,161400,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for NNMP SHED KALIKUNDRAM in Div-172, Zone - XIII. ( E.B Account Number : 220.015.600)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6165,Electrical,Completed,L-Electrical,172,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing for CHITRA NAGAR AMMA CANTEEN IN DIV-172, ZONE-XIII (E.B.Account no: 262.014.1450)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/10900,Buildings,Completed,NN-ADYAR,172,398000,"IMPROVEMENT WORKS TO MULTIPURPOSE HALL AT PONDICHERY ROAD (R.S.SRIDHAR SALAI) IN DN 172, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/11622,Buildings,Completed,NN-ADYAR,172,429000,"OPERATING AND MAINTENANCE OF LPG GAS IN BURIAL GROUND AT LAKE VIEW ROAD , KOTTURPURAM IN DIVISION - 172, ZONE - XIII (FOR ONE YEAR)",Own Sources,13,2018-19,2020-21 NN/2018-19/13357,Electrical,Completed,NN-ADYAR,172,1222000,"SUPPLY AND ERECTION OF 23 NOS OF 8/9.2 MTR OLD LAMP POST AND 23 NOS OF150-165W LED FITTING AT KOTTURPURAM 1ST CROSS AND AMBADI PLAY GROUND IN DIV-172, ZONE-XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/13672,Buildings,Completed,NN-ADYAR,172,438000,"Proposed Open Gym at River view park at River view road in Division 172, Unit 40, Zone-13",Own Sources,13,2018-19,2020-21 NN/2018-19/13685,Playfields,Completed,NN-ADYAR,172,1028000,"IMPROVEMENTS TO PLAY GROUND AT LAKE VIEW ROAD IN DN.172, UNIT-40,ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/14626,Buildings,Completed,NN-ADYAR,172,191000,"IMPROVEMENTS TO AMMA UNAVAGAM AT NEW STREET AND KOTTURPURAM IN DN.172, UNIT-40 ,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/15173,Buildings,Completed,NN-ADYAR,172,33000,"Improvement works to smart Toilet at West Canal bank road in Dn.172,Unit-40,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/15443,Parks,Completed,NN-ADYAR,172,174000,"ANNUAL MAINTAINANCE FOR PARKS AT DHANDAPANI PARK IN DN 172, ZONE 13 ( Per Six Months ) AREA 2000 SQ M",Own Sources,13,2018-19,2019-20 NN/2018-19/15535,Storm Water Drain,Completed,NN-ADYAR,172,312000,"Providing Rain Water harvesting at Ranjith road, Murugappa street, Arunachalam street,Ambadi road and Vellaiyan street in Dn.172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16130,Parks,Completed,NN-ADYAR,172,115000,"ANNUAL MAINTENANCE FOR PARK AT SENIOR CITIZEN PARK IN Dn-172, ZONE -13, ( Per Six Months ) Area=837Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16132,Parks,Completed,NN-ADYAR,172,113000,"ANNUAL MAINTENANCE FOR PARK AT GOVINDASWAMY PARK IN DN-172, ZONE-13, ( Per Six Months ) Area = 800 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16133,Parks,Completed,NN-ADYAR,172,343000,"ANNUAL MAINTENANCE FOR PARK AT CHITRA NAGAR PARK IN DN-172, ZONE-13, ( Per Six Months ) Area = 2750 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/17977,Buildings,Completed,NN-ADYAR,172,480000,"ERECTION OF BOREWELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CHENNAI PRIMARY SCHOOL KOTTUR,CHENNAI PRIMARY SCHOOL KOTTURPURAM,CHENNAI HIGH SCHOOL KOTTUR IN DIVISION 172,UNIT-40,ZONE13.",Own Sources,13,2018-19,2020-21 NN/2018-19/18081,Parks,Completed,NN-ADYAR,172,166600,"ANNUAL MAINTAINANCE FOR PARKS AT DHANDAPANI PARK IN DN 172, ZONE 13 ( Per Six Months ) AREA 2000 SQ M",Own Sources,13,2018-19,2020-21 NN/2018-19/18082,Parks,Completed,NN-ADYAR,172,133900,"ANNUAL MAINTENANCE FOR PARK AT SENIOR CITIZEN PARK IN Dn-172, ZONE -13, ( Per Six Months ) Area=837Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18083,Parks,Completed,NN-ADYAR,172,107600,"ANNUAL MAINTENANCE FOR PARK AT GOVINDASWAMY PARK IN DN-172, ZONE-13, ( Per Six Months ) Area = 800 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18084,Parks,Completed,NN-ADYAR,172,283600,"ANNUAL MAINTENANCE FOR PARK AT CHITRA NAGAR PARK IN DN-172, ZONE-13, ( Per Six Months ) Area = 2750 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/2138,Buildings,Completed,NN-ADYAR,172,720000,IMPROVEMENTS TO GYM AT LAKE VIEW ROAD PLAY GROUND IN DN172 U-40 Z-13,Own Sources,13,2018-19,2019-20 NN/2018-19/2189,Roads,Completed,NN-ADYAR,172,686000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Kottur garden 1,2,3,4th main road,pondicherry road, kalikundram main road, pallipattu main road, lock street, ponniamman kovil street in Div-172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/3785,Roads,Completed,NN-ADYAR,172,195000,"CONVERSION OF EXISTING SPEED BREAKER AT LAKE VIEW ROAD IN DN 172, UNIT 40, ZONE 13",Own Sources,13,2018-19,2019-20 NN/2018-19/3789,Buildings,Completed,NN-ADYAR,172,176000,CONSTRUCTION OF DRESSING ROOM FOR CONSERVANCY WORKERS IN DIVISION OFFICE BUILDING TERRACE AT NEW STREET IN DN 172 UNIT 40 ZONE 13,Own Sources,13,2018-19,2018-19 NN/2018-19/5184,Buildings,Completed,NN-ADYAR,172,16500,REPAIR WORKS FOR STREET NAME BOARD AT THULUKANATHAMMAN KOIL & ELLAIAMMAN KOIL STREET IN DN 172 UNIT 40 ZONE 13,Own Sources,13,2018-19,2019-20 NN/2018-19/5186,Buildings,Completed,NN-ADYAR,172,256000,IMPROVEMENTS TO PLAY FIELD AT KOTTURPURAM 2ND MAIN ROAD IN DN 172 UNIT 40 ZONE 13,Own Sources,13,2018-19,2019-20 NN/2018-19/5369,Roads,Completed,NN-ADYAR,172,141500,"PROVIDING PATCH WORKS IN PERUMAL KOIL EXTN.,KOTTURPURAM 3RD MAIN ROAD ,KOTTURPURAM 2ND MAIN ROAD, PERUMAL KOIL STREET,NEW STREET ,VALLIAMMAN ACHI STREET, ARUNACHALAM STREET, THIRUVALLUVAR 4TH STREET, KOTTUR GARDEN 2ND CROSS STREET, JUNCTION OF PONDICHERRY ROAD & LOCK STREET, MARUTHAI AVENUE, RANJITH ROAD, MURUGAPPA ROAD, RIVER VIEW ROAD, KOTTURPURAM 1ST MAIN ROAD & VELLAIAN ROAD AT DN 172 U 40 Z13",Own Sources,13,2018-19,2019-20 NN/2018-19/5372,Buildings,Completed,NN-ADYAR,172,40000,DISMANTLING THE EXISITNG DILAPIDATED ANGANWAD & PROVIDING FENCING TO EXISTING PLACE IN WEST CANAL BANK ROAD IN DN172 U40 Z13Z13,Own Sources,13,2018-19,2018-19 NN/2018-19/5513,Buildings,Completed,NN-ADYAR,172,567000,IMPROVEMENT WORKS TO THE BURIAL GROUND AT LAKE VIEW ROAD IN DN 172 U 40 Z13,Own Sources,13,2018-19,2019-20 NN/2018-19/7373,Parks,Completed,NN-ADYAR,172,814000,"IMPROVEMENT OF TRAFFIC ISLAND GANDHI MANDABAM RD JN WITH S.P.RD AND CENTERMEDIAN AT KOTTURPURAM RD IN DIV-172,UNIT-40,ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/7943,Storm Water Drain,Completed,NN-ADYAR,172,741000,"Desilting of SWD (0.9X0.9m) at Various streets in Dn172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7944,Storm Water Drain,Completed,NN-ADYAR,172,1100000,"Repairs to SWD (0.9X0.9m) at Various streets in Dn 172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7950,Storm Water Drain,Completed,NN-ADYAR,172,12000,"Desilting of SWD (0.6 X 0.6m) at various streets in Dn172, Unit-40, Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7951,Storm Water Drain,Completed,NN-ADYAR,172,317000,"Repairs to SWD (0.6X0.6m) at various streets in Dn172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7954,Storm Water Drain,Completed,NN-ADYAR,172,139000,"Desilting of SWD (1.2X1.2m) at Sardar patel road ( sriram nagar to B canal ) in Dn172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7955,Storm Water Drain,Completed,NN-ADYAR,172,24000,"Desilting of SWD (1.5 X1.5m) at Kotturpuram Bridge Cross Drain to TNSCB ( kotturpuram housing board to River view road) in Dn172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8379/C,Buildings,Completed,NN-ADYAR,172,898000,"Improvements to shopping market at lake view road in Dn 172, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/9252,Buildings,Completed,NN-ADYAR,172,1500000,"PROPOSED CONSTRUCTION OF 16TH DAY CEREMONY HALL AT RIVER VIEW ROAD IN DN 172,UNIT-40, ZONE-13.",MLACDS,13,2018-19,2020-21 B/2018-19/14848,Buildings,Completed,B-Buildings,173,5322720,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL (G+1 FLOOR) AT SOUTH KESAVAPERUMAL PURAM IN DIV-173,ZONE-13.",MLACDS,13,2018-19,2020-21 B/2018-19/14852,Buildings,Completed,B-Buildings,173,3737170,"CONSTRUCTION OF ICDS AT 1ST MAIN ROAD IN 3RD CROSS STREET SRINIVASAPURAM,R.A PURAM IN DIVISION-173, ZONE-13.",MLACDS,13,2018-19,2020-21 BR/2018-19/10658,Roads,Completed,BR-Bus Route Roads,173,501000,"Footpath Repair Works at R.K.Mutt Road in Dn-173, Zone-XIII",Grants,13,2018-19,2019-20 BR/2018-19/10697,Roads,Completed,BR-Bus Route Roads,173,2680000,"ATTENDING PATCH WORK AT VARIOUS PLACES (SARDAR PATEL ROAD, ALANDUR ROAD,GANDHI MANDAPAM ROAD, DURGA BAI DESH MUKH ROAD) IN ZONE-13.",Own Sources,13,2018-19,2019-20 BR/2018-19/10762,Roads,Completed,BR-Bus Route Roads,173,656000,"Footpath repair works at Durgababi Deshmukh Road in Dn-173, Zone-XIII",Grants,13,2018-19,2019-20 BR/2018-19/1421,Roads,Completed,BR-Bus Route Roads,173,160000,"PAINTING WORK FOR CENTRE MEDIAN AND FOOT PATH AT DURGA BAI DESH MUKH ROAD (FROM THE JUNCTION OF GREEN WAYS ROAD SIGNAL TO ADYAR SIGNAL ) IN DIV-173, ZONE-13.",Own Sources,13,2018-19,2018-19 BR/2018-19/16174,Road Cut,Completed,BR-Bus Route Roads,173,928000,RESTORATION OF OFC ROAD CUT MADE BY ACT IN VARIOUS BRR ROADS IN Z-13(DEPOSIT CODE-57/0252/2018-19),Deposit Works,13,2018-19,2019-20 BR/2018-19/18093,Road Cut,Completed,BR-Bus Route Roads,173,433000,RESTORATION OF ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN UNIT-40 ZONE-13 DEPOSIT CODE- 57/0050/2018-19,Deposit Works,13,2018-19,2019-20 BR/2018-19/18190,Footpath,Completed,BR-Bus Route Roads,173,672000,"Providing Centre Median at Durgabhai Deshmukh Road, [ From the jn of Thiru Vi Ka Bridge to Adayar Bridge Mouth ] in Zone -13, Div -173.",Own Sources,13,2018-19,2019-20 BR/2018-19/6675,Roads,Completed,BR-Bus Route Roads,173,7249000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at City Link Road in Dn-174 & 177, Zone - XIII",Grants,13,2018-19,2019-20 BR/2018-19/6936,Roads,Completed,BR-Bus Route Roads,173,1090000,"Footpath Repair Works at Taluk Office Road in Dn-171, Zone-XIII",Grants,13,2018-19,2019-20 BR/2018-19/7644,Footpath,Completed,BR-Bus Route Roads,173,78000,"Footpath Repair Works at Broadies Castle Road in Dn-173, Zone-XIII",Grants,13,2018-19,2019-20 BR/2018-19/8317,Footpath,Completed,BR-Bus Route Roads,173,1012000,"Footpath Repair Works at P.S.Kumarasamy Raja Road in Dn-173, Zone-XIII",Grants,13,2018-19,2019-20 L/2018-19/14366,Electrical,Completed,L-Electrical,173,2735000,"Removal and Refixing of 15nos OH/9.5/11mtr lamp posts and Erection of 23nos of 9mtr lamp posts with replacement of 1719mtr of 4c x 16sqmm Alu UG cables at Greenways road (PSK Salai), Raja Annamalaipuram in Division-173, Zone-XIII.",Own Sources,13,2018-19,2019-20 L/2018-19/6276,Electrical,Completed,L-Electrical,173,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for NNMP PSK SALAI, Raja Annamalaipuram in Div-173, Zone - XIII. E.B Account Number : 209-039-565. . .",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6285,Electrical,Completed,L-Electrical,173,1140000,"Supply, Installation, Testing & Commissioning of 15 Kwp Grid Tied Solar Rooftop including Civil works and earthing for CHENNAI CORPORATION GUEST HOUSE at DGS Dinakaran Salai, Raja Annamalai puram, Div-173, Zone-XIII. (E.B.Account no: 209.028.220)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/0966,Electrical,Completed,NN-ADYAR,173,245600,"Erection of 8Nos of 6/7mtr (Old ) lamp posts with 40w LED Light fittings for Chennai Corporation Play Ground at 4th cross street, Karpagam avenue in Division-173, Zone-XIII.",Own Sources,13,2018-19,2018-19 NN/2018-19/10415,Roads,Completed,NN-ADYAR,173,283000,"Providing Stage, Shamina, barricading work and forming Temporary Road for the immersion of Ganesha idol in Sea shore at Srinivasapuram in Dn 173, Unit-40, Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/11062,Electrical,Completed,NN-ADYAR,173,450000,"Providing Bio-Shredding Pulverizer Machine, Manure Seiver Machine and Weighing Machine including Civil and Electrical work for Compost yard at Janagi avenue MRC Nagar in division-173, unit- 40, zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/13111,Buildings,Completed,NN-ADYAR,173,68900,"Additional Construction of Compound Wall in R.K.Nagar In Dn - 173, Unit - 40, Zone - 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/13850,Buildings,Completed,NN-ADYAR,173,37700,"Repairs works to amma unavagam at Greenways Road & kamaraj salai in Division-173, Unit- 40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/13998,Buildings,Completed,NN-ADYAR,173,439000,"Proposed Open Gym size 4 m X 9 m = 36 SQM at Dharumambal Park, Kamarajar Salai Div 173, Unit-40, Zone-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/14791,Roads,Completed,NN-ADYAR,173,176000,"Relaying of Bitumen Concrete Road at Subramaniya Gurukal Street in DN-173, UNIT-40, ZONE-13.",Grants,13,2018-19,2019-20 NN/2018-19/14792,Roads,Completed,NN-ADYAR,173,2914000,"Relaying of Bitumen Concrete Road at Sathyadev Avenue & Extention in DN-173, UNIT-40, ZONE-13.",Grants,13,2018-19,2019-20 NN/2018-19/14793,Roads,Completed,NN-ADYAR,173,1153000,"Relaying of Bitumen Concrete Road at South Kesavaperumalpuram North Avenue in DN-173, UNIT-40, ZONE-13.",Grants,13,2018-19,2019-20 NN/2018-19/14794,Roads,Completed,NN-ADYAR,173,727000,"Relaying of Bitumen Concrete Road at Karpagam Avenue 3rd Street in DN-173, UNIT-40, ZONE-13.",Grants,13,2018-19,2019-20 NN/2018-19/14795,Roads,Completed,NN-ADYAR,173,454000,"Relaying of Bitumen Concrete Road at Bishop Garden (Extension) in DN-173, UNIT-40, ZONE-13.",Grants,13,2018-19,2019-20 NN/2018-19/16155,Parks,Completed,NN-ADYAR,173,330000,"ANNUAL MAINTENANCE FOR PARK AT KAMARAJ SALAI (DHARMAMBAL PARK) IN DN-173, ZONE-13, (PER SIX MONTHS) AREA = 2156 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16156,Parks,Completed,NN-ADYAR,173,142000,"ANNUAL MAINTENANCE FOR PARK AT KESAVAPERUMAL PURAM EAST AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA=1055 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16158,Parks,Completed,NN-ADYAR,173,130000,"ANNUAL MAINTENANCE FOR PARK AT SATHYADEV AVENUE EXTN. IN DN-173, ZONE-13, (PER SIX MONTHS) AREA = 1699 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16160,Parks,Completed,NN-ADYAR,173,156000,"ANNUAL MAINTENANCE FOR PARK AT M.R.C. NAGAR MAIN ROAD (NEAR IMAGE AUDITORIUM) IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 1336 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16163,Parks,Completed,NN-ADYAR,173,146000,"ANNUAL MAINTENANCE FOR PARK AT KESAVAPERUMAL PURAM CENTRAL AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 732 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16165,Parks,Completed,NN-ADYAR,173,131000,"ANNUAL MAINTENANCE FOR PARK AT KRISHNAPURI MAIN ROAD IN DN-173, ZONE-13, (PER SIX MONTHS) AREA =1089 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16166,Parks,Completed,NN-ADYAR,173,331000,"ANNUAL MAINTENANCE FOR PARK AT M.R.C. NAGAR EXTN. IN DN-173, ZONE-13, (PER SIX MONTHS) AREA = 3392 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16167,Parks,Completed,NN-ADYAR,173,117000,"ANNUAL MAINTENANCE FOR PARK AT VASANTHA AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 1392 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16169,Parks,Completed,NN-ADYAR,173,132000,"ANNUAL MAINTENANCE FOR PARK AT MAY FLOWER GARDEN, SRINIVASA AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 1274 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/17876,Roads,Completed,NN-ADYAR,173,639000,"Relaying of Bitumen Concrete Road at Pondicherry road (Part) (Ellaiamman koil street to Perumal koil street) in DN-172, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17877,Roads,Completed,NN-ADYAR,173,124000,"Relaying of Bitumen Concrete Road at Pallipattu main road in DN-172, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17981,Parks,Completed,NN-ADYAR,173,136000,"ANNUAL MAINTENANCE FOR PARK AT RK Nagar 2nd Main Road IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 1600 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18071,Parks,Completed,NN-ADYAR,173,97400,"ANNUAL MAINTENANCE FOR PARK AT MAY FLOWER GARDEN, SRINIVASA AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 1274 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18072,Parks,Completed,NN-ADYAR,173,110400,"ANNUAL MAINTENANCE FOR PARK AT VASANTHA AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 1392 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18073,Parks,Completed,NN-ADYAR,173,352800,"ANNUAL MAINTENANCE FOR PARK AT M.R.C. NAGAR EXTN. IN DN-173, ZONE-13, (PER SIX MONTHS) AREA = 3392 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18074,Parks,Completed,NN-ADYAR,173,124200,"ANNUAL MAINTENANCE FOR PARK AT KRISHNAPURI MAIN ROAD IN DN-173, ZONE-13, (PER SIX MONTHS) AREA =1089 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18075,Parks,Completed,NN-ADYAR,173,85200,"ANNUAL MAINTENANCE FOR PARK AT KESAVAPERUMAL PURAM CENTRAL AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 732 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18076,Parks,Completed,NN-ADYAR,173,149000,"ANNUAL MAINTENANCE FOR PARK AT M.R.C. NAGAR MAIN ROAD (NEAR IMAGE AUDITORIUM) IN DN-173, ZONE-13,(PER SIX MONTHS) AREA = 1336 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18077,Parks,Completed,NN-ADYAR,173,122600,"ANNUAL MAINTENANCE FOR PARK AT SATHYADEV AVENUE EXTN. IN DN-173, ZONE-13, (PER SIX MONTHS) AREA = 1699 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18078,Parks,Completed,NN-ADYAR,173,135300,"ANNUAL MAINTENANCE FOR PARK AT KESAVAPERUMAL PURAM EAST AVENUE IN DN-173, ZONE-13,(PER SIX MONTHS) AREA=1055 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18079,Parks,Completed,NN-ADYAR,173,318200,"ANNUAL MAINTENANCE FOR PARK AT KAMARAJ SALAI (DHARMAMBAL PARK) IN DN-173, ZONE-13, (PER SIX MONTHS) AREA = 2156 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/2216,Roads,Completed,NN-ADYAR,173,1070000,"Conversational of Existing Speed Breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at MRC Nagar Main Road, Kasturi Avenue, Vasantha Avenue,Roghini Garden,Karpagam Avenue 3rd Street,Velayudha Raja Street, Kutty (G) Street, R.K.Nagar 4th Street,Cresent Avenue-South Kesavaperumalpuram,Krishnapuri Main Road, Thiruveethiamman Koil Street,School View Road,North Avenue - South Kesavaperumal puram,Raja Muthaiahpuram,South Kesaperumalpuram,Raja (G) Thottem and Govindasamy Nagar in Div - 173, U - 40, Zone - 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2279,Buildings,Completed,NN-ADYAR,173,384000,"Improvements and Repairs to the existing Gym at Dr.D.G.S.Dinakaran Salai jn of R.K.Mutt Road in Dn.173,Unit-40,Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/3392,Buildings,Completed,NN-ADYAR,173,1660000,"DEMOLITION AND RECONSTRUCTION OF FISH MARKET, R.K.Mutt Road, DIVISION-173, UNIT-40, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/3781,Roads,Completed,NN-ADYAR,173,154000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Bishop Garden,Venkatraman Street,Bagirathi Amman Street and Viswanathan Street in Dn.173,Unit-40,Zone - XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/5862,Roads,Completed,NN-ADYAR,173,1038000,"ROAD CUT RESTORISATION WORK AT KARPAGAM AVENUE MAIN ROAD AND SAI NAGAR IN DIV-173, UNIT-40, ZONE-XIII",Deposit Works,13,2018-19,2019-20 NN/2018-19/6453,Buildings,Completed,NN-ADYAR,173,76000,Repair and Improvements of Public Conveniences at Govindasamy Nagar IN Div-173 Unit-40 Zone-13.,Own Sources,13,2018-19,2021-22 NN/2018-19/6793,Roads,Completed,NN-ADYAR,173,255000,"PROVIDING PATCH WORK FOR DAMAGED BITUMINOUS ROAD AT SATHADEV AVE ROAD, SATHAYADEV EXTN ROAD, RK NAGAR 2ND MAIN ROAD, 4TH , 3RD CROSS STREETS, SCHOOL VIEW ROAD, THIRUVEETHI AMMAN STREET, RAJA STREET, T.P.SCHEME ROAD, KARPAGAM AVENEUE 4TH,3RD & 1ST STREET, BISHOP GARDEN EXTN, PARK VIEW ROAD IN DN-173, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7076,Buildings,Completed,NN-ADYAR,173,742000,"ADDITIONAL ROOM CONSTRUCTION IN UPH AT RAJA STREET IN DIVISION -173, UNIT-40,ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7375,Parks,Completed,NN-ADYAR,173,440000,"IMPROVEMENT OF ROAD SIDE PARK AT KESAVAPERUMAL PURAM NORTH AVENUE IN DIVISION-173, UNIT-40, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7377,Parks,Completed,NN-ADYAR,173,106000,"IMPROVEMENT OF ROAD SIDE PARK AT P.S.K. SALAI NEAR LADIES HOSTEL AND PC SIDEIN DIVISION-173, UNIT-40, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7379,Parks,Completed,NN-ADYAR,173,262000,"IMPROVEMENT OF TRAFFIC ISLAND IN DD ROAD IN DIVISION-173, UNIT-40, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7382,Parks,Completed,NN-ADYAR,173,415000,"IMPROVEMENT OF CENTER MEDIAN IN DD ROAD TO GREENWAYS SALAI IN DIVISION-173, UNIT-40, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7404,Buildings,Completed,NN-ADYAR,173,2500000,"ADDITIONAL AND IMPROVEMENTS OF GUEST HOUSE AT 103 DD ROAD IN DIVISION-173, UNIT-40, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7468,Buildings,Completed,NN-ADYAR,173,1000000,"IMPROVEMENT LAWN AND FURNITURE IN GUEST HOUSE NO.103 DD ROAD DIVISION-173, UNIT-40, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7947,Storm Water Drain,Completed,NN-ADYAR,173,857000,"Desilting SWD (0.9X0.9m) at various streets in Dn 173, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8639,Storm Water Drain,Completed,NN-ADYAR,173,776000,"Improvements and demolition and reconstruction to SWD at May flower garden in Dn.173,U-40,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8640,Storm Water Drain,Completed,NN-ADYAR,173,1213000,"Improvements to SWD Road Crossing at Kamaraj Salai jn of 1) Kutty Gramani Street, 2) Shanmugapuram Street and 3) Srinivasa Avenue in Dn.173,U-40, Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8641,Storm Water Drain,Completed,NN-ADYAR,173,220000,"Improvements to SWD Road Crossing and dismantling of RCC Slab at RK nagar 2nd Main Road in Dn.173,U-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8730,Storm Water Drain,Completed,NN-ADYAR,173,362000,"Improvements to SWD Road Crossing at Pre.No.69/44, Kamraj Salai,Kamaraj Salai Crossing and opp to pre No.85/12 R.K.Nagar 4th cross street in Dn.173,U-40,Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8732,Storm Water Drain,Completed,NN-ADYAR,173,588000,"Improvements to SWD Road Crossing at School View Road in Dn.173,U-40,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8733,Storm Water Drain,Completed,NN-ADYAR,173,1423000,"Improvements to SWD Road Crossing at MRC Nagar Main Road in Dn.173,U-40,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8734,Storm Water Drain,Completed,NN-ADYAR,173,496000,"Improvements to SWD Road Crossing at P.S.Kumarasamy salai (3 Locations) in Dn.173,U-40,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8735,Storm Water Drain,Completed,NN-ADYAR,173,685000,"Improvements to SWD Road Crossing at DGS Dinakaran salai in Dn.173,U-40,Zone-13.",Own Sources,13,2018-19,2019-20 P/2018-19/11615,Parks,Completed,P-Parks and Playfields,173,1257000,"IMPROVEMENTS TO CENTRE MEDIAN AT D.G.S.DINAKARAN SALAI (FROM PATTINAPAKKAM SIGNAL TO GREENWAYS ROAD JUNCTION) IN DN-173, ZONE -13 (280 Mts)",Own Sources,13,2018-19,2019-20 BR/2018-19/0325,Roads,Completed,BR-Bus Route Roads,174,836000,"PAINTING WORK FOR CENTRE MEDIAN AND FOOT PATH AT VELACHERY MAIN ROAD (FROM THE JUNCTION OF SARDAR PATEL ROAD TO GURUNANAK COLLEGE ) IN DIV-174, ZONE-13.",Own Sources,13,2018-19,2019-20 BR/2018-19/18192,Road Cut,Completed,BR-Bus Route Roads,174,652000,Restoration of OFC road cut made by Bharathi airtel at Various Bus Route Roads in zone-13(Deposit Code-57/0322/2018-19),Deposit Works,13,2018-19,2019-20 BR/2018-19/3824,Roads,Completed,BR-Bus Route Roads,174,1200000,"PROVIDING MODERN STAINLESS STEEL BUS SHELTER (1 NO) AT VELACHERY 100 FEET ROAD( BY PASS) IN DIV-174, ZONE-13. (UNDER M.P FUND) SIZE:( 9.00MX2.50M)",MPLADS,13,2018-19,2019-20 D/2018-19/0356,Storm Water Drain,Completed,D-Storm Water Drains,174,441000,"Providing and laying 300mm dia. NP3 hume pipe across race course road near race course main gate in Dn.-174,Zone-13.",Own Sources,13,2018-19,2018-19 L/2018-19/6177,Electrical,Completed,L-Electrical,174,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS SCHOOL IN MADUVANKARAI in Div-174, Zone-XIII (E.B.Account no-212.024.847)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6181,Electrical,Completed,L-Electrical,174,462500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at D BLOCK CHS SCHOOL IN MADUVANKARAI in Div-174, Zone-XIII (E.B.Account no-212.024.342)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6182,Electrical,Completed,L-Electrical,174,538000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 7 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C BLOCK CHS SCHOOL IN MADUVANKARAI in Div-174, Zone-XIII (E.B.Account no-212.024.846)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6184,Electrical,Completed,L-Electrical,174,763500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHS SCHOOL IN MADUVANKARAI in Div-174, Zone-XIII (E.B.Account no-212.024.413)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6185,Electrical,Completed,L-Electrical,174,763500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at COMMUNITY HALL IN MADUVANKARAI in Div-174, Zone-XIII (E.B.Account no-212.010.487)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/12654,Electrical,Completed,NN-ADYAR,174,942000,"PROVISION OF OPERATION AND MAINTENANCE OF ELECTRICAL CREMATORIUM AT VELACHERY BURIAL GROUND FOR ONE YEAR IN DIVISION-174, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/13942,Buildings,Completed,NN-ADYAR,174,447000,"PROVIDING WATER SUPPLY AND ELECTRICAL ARRANGEMENTS TO THE E-TOILET AT RACE COURSE ROAD IN DN-174, UT-40A,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14131,Buildings,Completed,NN-ADYAR,174,172000,"Repairs and Improvements to the Amma Unavagam at five fur long road and velechery main Road in Division 174, Unit 40(A), Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/16061,Buildings,Completed,NN-ADYAR,174,639000,"PROVIDING R O PURIFIER TO UPHC AT FIVE FUR LONG ROAD IN DN-174,UT-40A,ZONE-13. (UNDER SAIDAPET MLA FUND)",MLACDS,13,2018-19,2019-20 NN/2018-19/16561,Parks,Completed,NN-ADYAR,174,408000,"Six Months MAINTAINCE FOR THE PARK AT PANDIYAN ST IN DN-174,UNIT-40A,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16621,Parks,Completed,NN-ADYAR,174,259000,"Six Month Maintenance for the Park at City Limit Road (Secretariate Colony) in Division 174, Unit 40(A), Zone 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17844,Roads,Completed,NN-ADYAR,174,1642000,"Relaying the BT Road at New Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17845,Roads,Completed,NN-ADYAR,174,1162000,"Relaying the BT Road at CarTrack road (part) in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17846,Roads,Completed,NN-ADYAR,174,248000,"Relaying the BT Road at Balaji avenue in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17847,Roads,Completed,NN-ADYAR,174,571000,"Relaying the BT Road at Pandian Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17848,Roads,Completed,NN-ADYAR,174,571000,"Relaying the BT Road at Radhakrishan street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17849,Roads,Completed,NN-ADYAR,174,159000,"Relaying the BT Road at Narasingapuram 2nd Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17850,Roads,Completed,NN-ADYAR,174,159000,"Relaying the BT Road at Narasingapuram 3rd Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17851,Roads,Completed,NN-ADYAR,174,67000,"Relaying the BT Road at Old Narasingapuram road in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17852,Roads,Completed,NN-ADYAR,174,439000,"Relaying the BT Road at Narasingapuram main road in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17853,Roads,Completed,NN-ADYAR,174,48000,"Relaying the BT Road at Narasingapuram 4th Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17854,Roads,Completed,NN-ADYAR,174,111000,"Relaying the BT Road at Race View Colony Extn in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17855,Roads,Completed,NN-ADYAR,174,381000,"Relaying the BT Road at Raman Avenue in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17856,Roads,Completed,NN-ADYAR,174,1231000,"Relaying the BT Road at City Limit road in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17857,Roads,Completed,NN-ADYAR,174,1068000,"Relaying the BT Road at Gokulam Colony in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17858,Roads,Completed,NN-ADYAR,174,615000,"Relaying the BT Road at Janakpuri 2nd Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17859,Roads,Completed,NN-ADYAR,174,339000,"Relaying the BT Road at Pandidurai Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17860,Roads,Completed,NN-ADYAR,174,1268000,"Relaying the BT Road at Madavan cross street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17861,Roads,Completed,NN-ADYAR,174,2142000,"Relaying the BT Road at Neduncheliyan Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17862,Roads,Completed,NN-ADYAR,174,1141000,"Relaying the BT Road at Ambedkar Nagar (Nehru Nagar) in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17863,Roads,Completed,NN-ADYAR,174,1847000,"Relaying the BT Road at Anbil Dharmalingam street in Dn - 174, Unit-40A, Zone - 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17864,Roads,Completed,NN-ADYAR,174,1847000,"Relaying the BT Road at Veerapandiya kattabomman street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17865,Roads,Completed,NN-ADYAR,174,2219000,"Relaying the BT Road at Periyar street (Nehru nagar) in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17866,Roads,Completed,NN-ADYAR,174,117000,"Relaying the BT Road at Sattanipet 2nd street extn in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17867,Roads,Completed,NN-ADYAR,174,231000,"Relaying the BT Road at Radha Mohan Street in Dn - 174, Unit-40A, Zone - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/17943,Parks,Completed,NN-ADYAR,174,457400,"ANNUAL MAINTENANCE FOR THE PARK AT PANDIYAN ST IN DN-174,UNIT-40A,ZONE-13. (6 MONTHS)",Own Sources,13,2018-19,2020-21 NN/2018-19/18068,Parks,Completed,NN-ADYAR,174,254500,"Six Month Maintenance for the Park at City Limit Road (Secretariate Colony) in Division 174, Unit 40(A), Zone 13",Own Sources,13,2018-19,2020-21 NN/2018-19/18089,Parks,Completed,NN-ADYAR,174,128100,"Six Months MAINTAINCE FOR THE PARK AT 1st Sea Ward road IN DN-182,UNIT-38,ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/1879,Buildings,Completed,NN-ADYAR,174,434000,"IMPROVEMENTS TO THE GYM BUILDING AT VELECHERY MAIN ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/2093,Roads,Completed,NN-ADYAR,174,224000,"SUPPLYING AND FIXING OF NOTICE BOARD FOR VACANT LANDS IN DIVISIONS - 170 to 182, ZONE - XIII",Own Sources,13,2018-19,2021-22 NN/2018-19/2503,Buildings,Completed,NN-ADYAR,174,43000,"REPAIRS TO THE DAMAGED STREET NAME BOARD AT VARIOUS STREETS IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2506,Roads,Completed,NN-ADYAR,174,255000,"Conversion of Existing Spreed breaker to IRC standards in various Street in division. 174 Unit -40A, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5582,Roads,Completed,NN-ADYAR,174,594000,"ATTENDING B.T. ROAD PATCH WORK AT VARIOUS STREET IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/6401,Buildings,Completed,NN-ADYAR,174,999000,"PROVIDING OPEN GYM AND PLAY MATERIALS TO THE PLAY FIELD AT JUNCTION OF NEDUNCHEZIYAN STREET IN DIVISION - 174, UNIT - 40(A) ZONE - 13 (UNDER SAIDAPET MLA FUND)",MLACDS,13,2018-19,2020-21 NN/2018-19/6508,Buildings,Completed,NN-ADYAR,174,56000,"IMPROVEMENTS TO THE 16th DAY CEREMONY HALL AT RACE COURSE ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/6937,Parks,Completed,NN-ADYAR,174,61000,"REPAIR WORKS AND PROVIDING GREENARY ARRANGEMENTS TO THE ROAD SIDE PARK AT RACE COURSE ROAD IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7575,Parks,Completed,NN-ADYAR,174,80000,"PROVIDING REPAIR WORKS AND GREENARY ARRANGEMENTS TO THE CENTRE MEDIAN AT VELECHERY MAIN ROAD (from HalLda jn. to Race course Interior Road Jn.) in Dn-174 Unit-40A, zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7583,Storm Water Drain,Completed,NN-ADYAR,174,1181000,"Repairs and improvements to the SWD at various location in dn-174,ut-40a,zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7972,Storm Water Drain,Completed,NN-ADYAR,174,1364000,"De-Silting works to Storm Water Drains at Various Location in Division 174, Unit 40(A), Zone 13",Own Sources,13,2018-19,2018-19 P/2018-19/11859,Parks,Completed,P-Parks and Playfields,174,975000,"Providing additional improvements to karpagam Avenue 4th street Park in Dn-173,unit-40, Zone-13",Own Sources,13,2018-19,2019-20 B/2018-19/11867,Buildings,Completed,B-Buildings,175,3000000,"Construction of Ration shop Building at 17th Street Indira Nagar, Adyar in DIv-175, ZOne-13",MLACDS,13,2018-19,2019-20 B/2018-19/14228,Buildings,Completed,B-Buildings,175,3400000,"Proposed Additional Construction of Third floor in Zonal EOC at Venkatarathinam Nagar, Adyar in Div-175, Zone-13.",Grants,13,2018-19,2020-21 BR/2018-19/16175,Road Cut,Completed,BR-Bus Route Roads,175,985000,RESTORATION OF OFC ROAD CUT MADE BY ACT IN VARIOUS BRR ROADS IN Z-13 (DEPOSIT CODE-57/0252/2018-19),Deposit Works,13,2018-19,2019-20 BR/2018-19/18094,Road Cut,Completed,BR-Bus Route Roads,175,1083000,RESTORATION OF ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN UNIT-40 ZONE-13 DEPOSIT CODE-57/0050/2018-19,Deposit Works,13,2018-19,2019-20 BR/2018-19/18191,Road Cut,Completed,BR-Bus Route Roads,175,1048000,Restoration of OFC road cut made by ACT at Various Bus Route Roads in zone-13 (Deposit Code-57/0523/2018-19),Deposit Works,13,2018-19,2019-20 BR/2018-19/18287,Road Cut,Completed,BR-Bus Route Roads,175,958000,Restoration of OFC road cut made by M/s Bharathi Airtel at various bus route roads in Zone-13(Deposit code-57/0398/2018-19),Deposit Works,13,2018-19,2020-21 BR/2018-19/18295,Road Cut,Completed,BR-Bus Route Roads,175,990000,Restoration of OFC road cut made by M/s Bharathi Airtel at various bus route roads in Zone-13(Deposit code-57/0398/2018-19),Deposit Works,13,2018-19,2020-21 BR/2018-19/18296,Road Cut,Completed,BR-Bus Route Roads,175,990000,Restoration of OFC road cut made by M/s Bharathi Airtel at various bus route roads in Zone-13(Deposit code-57/0398/2018-19),Deposit Works,13,2018-19,2020-21 BR/2018-19/2205,Roads,Completed,BR-Bus Route Roads,175,2332000,"PROPOSEDE CONSTRUCTION OF CENTRE MEDIAN (CRASH BARRIER TYPE ) AT VELACHERY MAIN ROAD (100 FEET ROAD JN TO PHONEIX MALL) IN DIV-175, ZONE -13",Own Sources,13,2018-19,2019-20 BR/2018-19/3926,Roads,Completed,BR-Bus Route Roads,175,820000,"PROVIDING SPEED BREAKERS AND TRAFFIC IMPROVEMENTS WORK AT ST.MARYS ROAD , SARDAR PATEL ROAD AND , D.G.S. DINAKARAN SALAI IN ZONE - 9 & 13.",Own Sources,13,2018-19,2020-21 BR/2018-19/5974,Footpath,Completed,BR-Bus Route Roads,175,1947000,"Footpath Repair Works at Dr.Muthulakshmi Salai in Dn-175, Zone-XIII",Grants,13,2018-19,2019-20 L/2018-19/14874,Electrical,Completed,L-Electrical,175,185000,"Painting and Numbering of 537nos of Lamp posts and 20nos of Pillars various locations in Div.173,175 and 176 in Zone-XIII.",Own Sources,13,2018-19,2019-20 L/2018-19/1861,Electrical,Completed,L-Electrical,175,992000,"Providing of 30Nos of 6mtr lamp posts with 40w LED fittings at Indira Nagar (26th cross street, 4th main road and 1st lane 4th aveneu) in Div-175, Zone-XIII",Own Sources,13,2018-19,2018-19 L/2018-19/4854,Electrical,Completed,L-Electrical,175,1885000,"Providing rewiring, electrical accessories and additional wiring for Chennai Corporation Schools (Primary, Middle and High Schools) at 29th cross street, Indira nagar, 11th cross street, Shastri nagar, Kamaraj avenue primary Schools, N.S. Garden, Raja Annamalai puram, Middle School and Adyar, Kamraj Avenue High School in Divisions 175,176 and 173, Zone-XIII.",Own Sources,13,2018-19,2019-20 L/2018-19/6235,Electrical,Completed,L-Electrical,175,462500,"Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Roof top including Civil works and earthing for RDC /South office Annex Building, No.115 L.B Road, Adyar (Primary School Building & NNMP shead Building at Thiruvenkadam street) in Div-175, Zone - XIII. E.B Account Number : 203-008-141.",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6279,Electrical,Completed,L-Electrical,175,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for NNMP SHED . 11th Lane, Indira Nagar, Adyar in Div-175, Zone - XIII.",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6280,Electrical,Completed,L-Electrical,175,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for CHENNAI PRIMARY SCHOOL 29th Cross Street Indira Nagar, Adyar in Div-175, Zone - XIII. E.B Account Number : 217.005.331 .",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6286,Electrical,Completed,L-Electrical,175,1140000,"Supply, Installation, Testing & Commissioning of 15 Kwp Grid Tied Solar Rooftop including Civil works and earthing for EOC HOSPITAL BUILDING, Venkatrathinam nagar main road, Adyar, Div-175, Zone-XIII (E.B.Account no: 203.021.185)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6288,Electrical,Completed,L-Electrical,175,1215000,"Supply, Installation, Testing & Commissioning of 16Kwp Grid Tied Solar Rooftop including Civil works and earthing for BESANT NAGAR GASIFIER CREMATORIUM Building at 1st Mainr road, Besant Nagar,Div-176, Zone-XIII. ( E.B Account No. 213.010.227)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6295,Electrical,Completed,L-Electrical,175,763500,"Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing for CHENNAI HIGH SCHOOL, Kamaraj Avenue, Adyar, Div-175, Zone-XIII (E.B.Account no: 203.020.164)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/7174,Electrical,Completed,L-Electrical,175,769000,"Providing 1no of 12 Mtr High Mast with 10Nos 70-100W LED FL Fitting at junction of 2nd avenue and 1st avenue Indira Nagar, in Div-175, Zone-XIII",Own Sources,13,2018-19,2020-21 NN/2018-19/12690,Buildings,Completed,NN-ADYAR,175,2340000,"IMPROVEMENTS MINOR REPAIRS WATER SUPPLY ARRANGEMENT AND DRAINAGE REPAIR ITEMS TO ZONAL OFFICE- XIII AND REGIONAL DEPUTY COMMISSIONER (SOUTH) OFFICE AT DR.MUTHULAKSHMI SALAI ,ADYAR IN DIV 175, UNIT-40, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/13445,Buildings,Completed,NN-ADYAR,175,419000,"Providing Open Gym at Indira Nagar 4th Cross Street in Div - 175, Unit - 40, Zone - 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/14125,Buildings,Completed,NN-ADYAR,175,230000,"PROVIDING WATER SUPPLY,DRAINAGE AND ELECTRICAL ARRANGEMENTS TO THE E-TOILET AT GANDHI NAGAR BUS STAND NEAR SARDAR PATEL ROAD ,ADYAR IN DN-175,UNIT-40,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/1415,Roads,Completed,NN-ADYAR,175,213000,RELAYING OF ROAD WITH BC-40MM AT BAKTHAVATCHALAM NAGAR 2ND STREET IN DIV-175 UNIT-40 ZONE-13,Own Sources,13,2018-19,2019-20 NN/2018-19/14169,Buildings,Completed,NN-ADYAR,175,50000,"IMPROVEMENTS WORK IN AMMA UNAVAGAM AT THIRUVENGADAM STREET AND INDIRA NAGAR 29TH CROSS STREET, ADYAR, IN DIV - 175, UNIT - 40, ZONE - XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/14206,Buildings,Completed,NN-ADYAR,175,205000,"ATTENDING CEMENT CONCRETE PATCHES AT VARIOUS STREETS IN DIV - 175, UNNIT - 40, ZONE - 13",Own Sources,13,2018-19,2019-20 NN/2018-19/16013,Buildings,Completed,NN-ADYAR,175,166250,"Providing Drinking water provision to ICDS(33603110119) at 18th cross street,Indira nagar in Div-175,U-40,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16057,Buildings,Completed,NN-ADYAR,175,166250,"Providing Drinking water provision to ICDS(33603110112) at thiruvengadam street, LB Road in Div-175,U-40,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16058,Buildings,Completed,NN-ADYAR,175,166250,"Providing Drinking water provision to ICDS(33603110111) at malligaipoo nagar, adayar in Div-175,U-40,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16491,Parks,Completed,NN-ADYAR,175,615000,"ANNUAL MAINTENANCE FOR PARK AT INDIRA NAGAR PARK IN DN-175, ZONE-13,(PER 6 MONTHS) AREA = 7450 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16495,Electrical,Completed,NN-ADYAR,175,620000,"Proposed Supply & Installation of 12 Nos Up-Graded CCTV Camera Unit, 20 Nos LED False Ceiling Fittings and 20 Nos LED T/L Fittings at Zonal Office-13 at Muthulakshmi Salai, Adayar, in Div 175, Zone-XIII,",Own Sources,13,2018-19,2019-20 NN/2018-19/18067,Parks,Completed,NN-ADYAR,175,591500,"ANNUAL MAINTENANCE FOR PARK AT INDIRA NAGAR PARK IN DN-175, ZONE-13,(PER 6 MONTHS) AREA = 7450 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/1841,Roads,Completed,NN-ADYAR,175,1307000,RELAYING OF ROAD WITH BC-40MM AT GANDHI NAGAR 2ND MAIN ROAD DIV-175 UNIT-40 ZONE-13,Own Sources,13,2018-19,2019-20 NN/2018-19/1843,Roads,Completed,NN-ADYAR,175,370000,RELAYING OF ROAD WITH BC-40MM AT GANDHI NAGAR 3RD MAIN ROAD DIV-175 UNIT-40 ZONE-13,Own Sources,13,2018-19,2019-20 NN/2018-19/1845,Roads,Completed,NN-ADYAR,175,755000,RELAYING OF ROAD WITH BC-40MM AT KASTHURIBHAI NAGAR 1ST CROSS STREET DIV-175 UNIT-40 ZONE-13,Own Sources,13,2018-19,2019-20 NN/2018-19/1847,Roads,Completed,NN-ADYAR,175,299000,RELAYING OF ROAD WITH BC-40MM AT NEHRU NAGAR 1ST MAIN ROAD DIV-175 UNIT-40 ZONE-13,Own Sources,13,2018-19,2019-20 NN/2018-19/1848,Roads,Completed,NN-ADYAR,175,308000,RELAYING OF ROAD WITH BC-40MM AT NEHRU NAGAR 2ND MAIN ROAD DIV-175 UNIT-40 ZONE-13,Own Sources,13,2018-19,2019-20 NN/2018-19/1849,Roads,Completed,NN-ADYAR,175,744000,RELAYING OF ROAD WITH BC-40MM AT NEHRU NAGAR 4TH MAIN ROAD DIV-175 UNIT-40 ZONE-13,Own Sources,13,2018-19,2019-20 NN/2018-19/2066,Buildings,Completed,NN-ADYAR,175,198000,"Improvement of gym at Gandhi nagar canal bank road Div-175,Unit-40,zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2068,Electrical,Completed,NN-ADYAR,175,290000,"Improvement of PlayfIeld at Venkatarathinam nagar in ,Div-175,Unit-40,Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2069,Electrical,Completed,NN-ADYAR,175,140000,"Repair and improvement of Playfield in Indira nagar 11th lane in Div-175,Unit-40,Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2214,Roads,Completed,NN-ADYAR,175,733000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at kasthuribai 3rd main road, Kasthuribai 3rd cross street, kamaraj avenue 2nd street, venkatrathnam nagar, Indira nagar 1st avenue,Indira nagar 28th cross street, Indira nagar 6th cross street, Gandhi nagar 3rd cross street, Gandhi nagar1st cross street in Div-175, Unit-40,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2559,Electrical,Completed,NN-ADYAR,175,363000,"Imrovement and repair the Palyfiled at Srinivasamoorthy Avenue in Div-175,Unit-40,Zone-13",Grants,13,2018-19,2019-20 NN/2018-19/2561,Parks,Completed,NN-ADYAR,175,725000,"Repair and improvement of footpath at Bakthavatchalam Nagar 5th Street, Kamaraj Avenue 2nd Street, Indira Nagar 1st Main Road, Gandhi Nagar 4th Main Road, Kasthuribai Nagar 1st & 2nd Cross Street in Div-175,Unit-40, Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/2575,Playfields,Completed,NN-ADYAR,175,332000,Improvement to Play ground at Thiruvengadam street in Div-175 Unit-40 Zone-13,Own Sources,13,2018-19,2019-20 NN/2018-19/4312,Roads,Completed,NN-ADYAR,175,19000,"Repairs to exsisting street name board(Single Arrow) at various streets in div-175,unit-40,zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/4550,Electrical,Completed,NN-ADYAR,175,599000,"Providing Comprehensive Annual Maintenance for 1 No 62.5 KVA Diesel Genset at Multi Speciality Hospital at Maduvankarai in Div-174 and 1 No 100 KVA Diesel Genset at 24x7 E.O.C , Venkatrathinam Nagar in Div-175 and 1 No 30 KVA Diesel Genset at Health Centre at Seva Nagar, Velachery in Div-179, Zone-XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/4843,Buildings,Completed,NN-ADYAR,175,454000,"Providing road patch work at K.B. Nagar 1st Main Road, Gandhi Nagar 1st Main Road, Indira Nagar 29th Cross Street, Indira Nagar 2nd Avenue, Arangannal Salai & Dhanalakshmi Avenue 1st Street in div-175,unit-40,zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5618,Buildings,Completed,NN-ADYAR,175,830000,"Engaging 6Nos of watchmen for one year at Zonal office - XIII, Dr.Muthulakshmi salaI in Division - 175, Zone - XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/6399,Storm Water Drain,Completed,NN-ADYAR,175,330000,"Repair and Improvements to Existing Strom water Drain at L.B Road (From the Jn of Shastri nagar 9th Lane to Mahatma gandhi road Jn) in Div-175,Unit-40,Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/6400,Storm Water Drain,Completed,NN-ADYAR,175,280000,"Repairs and Improvements to Strom water Drain in Indira nagar 2nd Avenue (From the Jn of Indira nagar 1st main road to Indira nagar 1st Avenue jn)in Div-175,Unit-40,Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7374,Parks,Completed,NN-ADYAR,175,164487,"IMPROVEMENT OF TRAFFIC ISLAND AT GANDHI NAGAR 1ST MAIN ROAD & 3RD CROSS STREET JUNCTION, CENTER MEDIAN AT SARDAR PATEL ROADS (2 NOS) , INDIRA NAGAR 2ND & 3RD AVENUE IN DIV -175,UNIT-40,ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7961,Storm Water Drain,Completed,NN-ADYAR,175,879000,"Desilting of SWD (0.6X0.75m) at various streets in Dn175, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7962,Storm Water Drain,Completed,NN-ADYAR,175,1470000,"Repairs to SWD (0.6X.75m) at various streets in Dn175, Unit-40, Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7963,Storm Water Drain,Completed,NN-ADYAR,175,201000,"Desilting of SWD (.9X.9m) at various streets in Dn175, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7966,Storm Water Drain,Completed,NN-ADYAR,175,686000,"Repairs to SWD (0.9X0.9m) at Various streets In Dn175, Unit-40, Zone-13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7967,Storm Water Drain,Completed,NN-ADYAR,175,570000,"Repairs to SWD (1.2X1.2m) at various streets in DN 175, Unit-40,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7968,Storm Water Drain,Completed,NN-ADYAR,175,125000,"Desilting SWD (1.2X1.2m) at various streets in Dn175, unit-40, zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8731,Storm Water Drain,Completed,NN-ADYAR,175,368000,"Improvements to SWD Road Crossing at Thiruveedi Amman koil street in Dn.173,",Own Sources,13,2018-19,2019-20 NN/2018-19/8864,Storm Water Drain,Completed,NN-ADYAR,175,1782000,"minor repairs to SWD at various streets in Din 175, Unit-40, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/9714,Roads,Completed,NN-ADYAR,175,149000,"Proposed 4Nos. of Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking at the Junction of Gandhi Nagar 3rd main road and Gandhi Nagar 3rd cross street in div175,Unit 40,Zone-13",Own Sources,13,2018-19,2018-19 P/2018-19/3281,Parks,Completed,P-Parks and Playfields,175,14817875,"FORMATION OF NEW PARK AT THE BANKS OF RIVER BUCKINGHAM CANAL REAR SIDE OF CANCER INSTITUTE IN DN 175,Z-13.",Own Sources,13,2018-19,2020-21 BR/2018-19/16176,Road Cut,Completed,BR-Bus Route Roads,176,455000,RESTORATION OF ROADCUT MADE BY OFC IN VARIOUS BRR ROADS IN Z-13 (DEPOSIT CODE- 57/0322/2018-19),Deposit Works,13,2018-19,2019-20 BR/2018-19/18092,Road Cut,Completed,BR-Bus Route Roads,176,866000,RESTORATION OF ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN UNIT-38 ZONE-13 DEPOSIT CODE- 57/0050/2018-19,Deposit Works,13,2018-19,2019-20 BR/2018-19/6908,Roads,Completed,BR-Bus Route Roads,176,240000,"Footpath Repair Works at Besant Nagar 2nd Avenue in Dn-176, Zone-XIII",Grants,13,2018-19,2019-20 BR/2018-19/7087,Footpath,Completed,BR-Bus Route Roads,176,162000,"Footpath Repair Works at M.G.Road in Dn-176, Zone-XIII",Grants,13,2018-19,2019-20 L/2018-19/6282,Electrical,Completed,L-Electrical,176,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Roof top including Civil works and earthing for Chennai Primary School 11th cross street, Shastri Nagar, Adyar in Div-176, Zone - XIII. E.B Account Number : 201-042-100. . .",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6287,Electrical,Completed,L-Electrical,176,312000,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing for CHENNAI MIDDLE SCHOOL , Damodrapuram, Adyar, Div-176, Zone-XIII (E.B.Account no: 213.031.366)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/10765,Roads,Completed,NN-ADYAR,176,827000,"Restoration of Road cut made by CMWSSB at Besant Nagar 5th Avenue, Besant Nagar 32nd Cross Street and Besant Nagar 4th Main Road in Dn 176, Unit 38, Zone 13",Own Sources,13,2018-19,2019-20 NN/2018-19/11130,Buildings,Completed,NN-ADYAR,176,36500,"REPAIR AND IMPROVEMENT WORKS TO THE AMMA UNAVAGAM AT BESANT NAGAR 31ST CROSS STREET AND BESANT NAGAR 1ST AVENUE IN DN-176,U-38,Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/12927,Buildings,Completed,NN-ADYAR,176,253000,"REPAIR AND IMPROVEMENT WORKS TO THE FISH MARKET AT BESANT NAGAR 1ST AVENUE ROAD IN DN-176, U-38, Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/12948,Buildings,Completed,NN-ADYAR,176,698000,"REPAIR AND IMPROVEMENT WORKS TO THE DIVISION OFFICE BUILDING AT SASTRI NAGAR 8TH CROSS STREET IN DN-176, U-38, Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/14490,Buildings,Completed,NN-ADYAR,176,584000,"REPAIR AND IMPROVEMENT WORKS TO THE ANGANWADI CENTER AT SASTRI NAGAR 1ST CROSS STREET, KAKKAN COLONY, DHAMODHARAPURAM AND BESANT NAGAR 5TH AVENUE IN DN-176, U-38, Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/14742,Roads,Completed,NN-ADYAR,176,202000,"ATTENDING PATCH WORK USING CEMENT CONCRETE AT PARAMESHWARI NAGAR 1ST & 2ND STREET, SASTRI NAGAR 3RD CROSS STREET, SASTRI NAGAR 4TH & 6TH LANE, DHAMODHARAPURAM 1ST, 3RD, 4TH & 5TH STREET, NEW STREET, VENKATESHWARA NAGAR 3RD STREET IN DN-176, U-38, Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/16059,Buildings,Completed,NN-ADYAR,176,735000,"Providing Drinking water Provision to Arignar Anna Govt Higher secondary school at 4th mainroad,Besant Nagar ,Oorur in Div-176,U-38,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16492,Parks,Completed,NN-ADYAR,176,132500,"ANNUAL MAINTENANCE FOR PARK AT PADMANABHA NAGAR PARK IN DN-176, ZONE-13,(6 MONTHS) AREA = 1170 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16493,Parks,Completed,NN-ADYAR,176,159900,"ANNUAL MAINTENANCE FOR PARK AT AAVIN PARK(Dr.MUTHULAKSHMI) PARK IN DN-176,ZONE-13, (6 MONTHS) AREA = 1300 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16563,Parks,Completed,NN-ADYAR,176,121500,"ANNUAL MAINTENANCE OF KARL SCHMIDT MEMORIAL AT ELLIOTS BEACH ON 6TH MAIN ROAD IN DN-176, ZONE-12 (5 MONTHS)",Own Sources,13,2018-19,2019-20 NN/2018-19/17127,Buildings,Completed,NN-ADYAR,176,250000,"Providing Bore well for Drinking water in Chennai middle school at dhamodharapuram,adayar in Div-176,U-38,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/1754,Electrical,Completed,NN-ADYAR,176,1668500,"PAINTING AND REPAIR WORKS TO THE PLAY GROUND AT SASTRI NAGAR 11TH CROSS STREET, SBI OFFICERS COLONY, BESANT NAGAR 32ND CROSS STREET AND BESANT NAGAR 21ST CROSS STREET IN DN-176,U-38,Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/18065,Parks,Completed,NN-ADYAR,176,126900,"ANNUAL MAINTENANCE FOR PARK AT PADMANABHA NAGAR PARK IN DN-176, ZONE-13,(6 MONTHS) AREA = 1170 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18066,Parks,Completed,NN-ADYAR,176,153900,"ANNUAL MAINTENANCE FOR PARK AT AAVIN PARK(Dr.MUTHULAKSHMI) PARK IN DN-176,ZONE-13, (6 MONTHS) AREA = 1300 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18087,Parks,Completed,NN-ADYAR,176,137300,"ANNUAL MAINTENANCE OF KARL SCHMIDT MEMORIAL AT ELLIOTS BEACH ON 6TH MAIN ROAD IN DN-176, ZONE-12 (6 MONTHS)",Own Sources,13,2018-19,2020-21 NN/2018-19/2006,Roads,Completed,NN-ADYAR,176,1273000,"Providing Single (220Nos) & Double (38Nos) Compactor bin platforms at various streets in Divisions - 176, 181 & 182, Unit - 38, Zone - XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/2468,Roads,Completed,NN-ADYAR,176,477000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Sastri Nagar 8th cross street, Sastri Nagar 10th cross street, Sastri Nagar 1st cross street, Karpagam Garden, Venkateshwara Nagar, Besant Nagar 6th Avenue, Ponninamman koil street, Padmanabha nagar, Besant Nagar 3rd main road in Dn 176, Unit 38, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/3041,Roads,Completed,NN-ADYAR,176,908000,"CONVERSION OF SPEED BREAKER AND PROVIDING THERMOPLASTIC COMPOUND AT PASMANABA NAGAR 5TH STREET, ARUNACHALAPURAM MAIN ROAD, VASANTHA PRESS ROAD, PONNIAMMAN KOIL STREET, BESANT NAGAR 1ST, 2ND, 7TH & 31ST CROSS STREET, BESANT NAGAR 1ST & 4TH MAIN ROAD, BESANT NAGAR 4TH & 5TH AVENUE, ELLAI AMMAN KOIL STREET, DHAMODHARAPURAM MAIN ROAD, SASTRI NAGAR 7TH & 8TH CROSS STREET AND VENGADESHWARA NAGAR 1ST STREET IN DN-176,U-38,Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/3481,Footpath,Completed,NN-ADYAR,176,410000,"REPAIR AND IMPROVEMENT WORKS TO THE FOOTPATH AT BESANT NAGAR 3RD MAIN ROAD, SASTRI NAGAR 1ST, 7TH, 8TH, 11TH & 15TH CROSS STREET, SASTRI NAGAR 1ST MAIN ROAD, KARPAGAM GARDEN 1ST & 2ND MAIN ROAD AND PADMANABA NAGAR 5TH STREET IN DN-176,U-38,Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/5376,Roads,Completed,NN-ADYAR,176,186000,"Repairs to Street Name Boards at Sastri nagar 10th cross street, Besant nagar 32nd cross street, Venkateshwara nagar 2nd street, Vasantha prress road, Parameshwari nagar 1st street, Thiruvalluvar nagar 3rd cross street, Ellaiamman koil street, Dhamodarapuram main road, Besant nagar 17th cross street in Dn 176, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5378,Storm Water Drain,Completed,NN-ADYAR,176,728000,"Providing Rain water Harvesting at various streets in division 176, Unit 38, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/5382,Buildings,Completed,NN-ADYAR,176,416000,"PROVIDING GYM MATERIALS WITH ANNUAL MAINTENANCE AT KAKKAN COLONY,ARUNACHALAPURAM, ELLIOTS BEACH, 5TH AVENUE IN DIVISION-176, UNIT-38,ZONE-XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/5419,Roads,Completed,NN-ADYAR,176,396000,"ATTENDING PATCH WORK BY PAVER FINISHER BESANT NAGAR 6TH CROSS STREET, BESANT NAGAR 22ND CROSS STREET, PONNIAMMAN KOIL STREET, VSANTHA PRESS ROAD, ARUNACHALAM 2ND STREET, PADMANABA NAGAR 1ST & 4TH STREET, BLUE CROSS ROAD, KARPAGAM GARDEN 3RD CROSS STREET, ELLAI AMMAN KOIL STREET AND BESANT NAGAR 4TH AVENUE ROAD IN DN-176,U-38,Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/6972,Footpath,Completed,NN-ADYAR,176,95500,"REPAIR WORKS TO THE DAMAGED FOOTPATH PORTION AT BESANT NAGAR 6TH AVENUE ROAD IN DN-176.U-38,Z-13",Own Sources,13,2018-19,2018-19 NN/2018-19/7285,Electrical,Completed,NN-ADYAR,176,1225000,"REPAIR AND IMPROVEMENT WORKS TO THE TRAFFIC ISLAND AT BESANT NAGAR 2ND AVENUE, DD ROAD JN.OF GANDHI NAGAR & SASTRI NAGAR 1ST AVENUE ROAD AND CENTER MEDIAN AT DD ROAD IN DN-176,U-38,Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7809,Storm Water Drain,Completed,NN-ADYAR,176,1218000,"DESILTING AND SUPPLYING AND FIXING EXISTING STORM WATER DRAIN MANHOLE DOOR AT SASTRI NAGAR 9TH & 10TH CROSS STREET, PADMANABA NAGAR 4TH & 3RD STREETS, VASANTHA PRESS ROAD, JEEVARATHINAM NAGAR MAIN ROAD, RAMASAMY GARDEN, PARAMESHWARI NAGAR 1ST STREET IN DN-176,U-38, Z-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8374,Roads,Completed,NN-ADYAR,176,269000,"Relaying of Bitumen Concrete Road at Besant Nagar 10th Cross Street in DN-176, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8377,Roads,Completed,NN-ADYAR,176,281000,"Relaying of Bitumen Concrete Road at Besant Nagar 11th Cross Street in DN-176, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8378,Roads,Completed,NN-ADYAR,176,261000,"Relaying of Bitumen Concrete Road at Besant Nagar 12th Cross Street in DN-176, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8380,Roads,Completed,NN-ADYAR,176,435000,"Relaying of Bitumen Concrete Road at Besant Nagar 25th Cross Street in DN-176, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8381,Roads,Completed,NN-ADYAR,176,848000,"Relaying of Bitumen Concrete Road at Besant Nagar 26th Cross Street in DN-176, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8382,Roads,Completed,NN-ADYAR,176,676000,"Relaying of Bitumen Concrete Road at Ellaiamman Koil Street in DN-176, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8450,Buildings,Completed,NN-ADYAR,176,154000,"IMPROVEMENT WORKS TO THE UPHC BUILDING AT BESANT NAGAR 1ST AVENUE IN DN-176,U-38,Z-13",Own Sources,13,2018-19,2019-20 L/2018-19/3803,Electrical,Completed,L-Electrical,177,1829000,"PROVISION OF ADDITIONAL & RE-WIRING AT CHSS,CPS SCHOOLS AT TNHB COLONY 3RD MAIN ROAD VELACHERY WEST , MADUVANKARAI SCHOOL GUINDY, POONAMALLEE PRIMARY SCHOOL GUINDY IN DIV-170,177 ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/6242,Electrical,Completed,L-Electrical,177,612900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 8 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Sastri Nagar, 4th Street, Hospital Velachery West in Div-177, Zone-XIII (E.B.Account no243.108.1060)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6245,Electrical,Completed,L-Electrical,177,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MAHALAKSHMI NAGAR MAIN ROAD UNIT 40A OFFICE in Div -177, Zone-XIII.(E.B.ACCOUNT NO-279.003.29)",Own Sources,13,2018-19,2019-20 NN/2018-19/13117,Roads,Completed,NN-ADYAR,177,536000,"IMPROVEMENT WORK OF CHILDREN PLAY FIELD AT Shawlace colony 2nd Street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/13123,Buildings,Completed,NN-ADYAR,177,81000,"IMPROVEMENT WORK OF PLAY FIELD AT Dr.Ambedkar Nagar 1st Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/13247,Buildings,Completed,NN-ADYAR,177,66000,"IMPROVEMENT WORK TO CHILDREN PLAY FIELD AT ANDAL NAGAR 2ND MAIN ROAD in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/13252,Buildings,Completed,NN-ADYAR,177,686000,"IMPROVEMENT WORK TO UNIT OFFICE BUILDING AT MAHALASHMI NAGAR 1ST MAIN ROAD in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/13446,Electrical,Completed,NN-ADYAR,177,679000,"ERECTION OF 10 NOS 6/7MTRS OLD LAMP POST WITH 40W/50W , 90W/120W LED FITTINGS AND LAYING OF 1063mtrs 2x16sq.mm ALU CABLE AT Sastri nagar IV cross street,Telephone colony II main road,Shawwalace colony II street,Andal nagar II main road, New NGO colony, II main road PLAY GROUND IN DIV-177, ZONE-XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/14167,Buildings,Completed,NN-ADYAR,177,242000,"REPAIR WORKS TO AMMA UNAVAGAM AT LAKE VIEW ROAD, KAKKAN NAGAR 2ND CROSS STREET AND TNHB COLONY 3RD AVENUE in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/14784,Buildings,Completed,NN-ADYAR,177,69000,"IMPROVEMENT WORK TO COMMUNITY HALL AT DR AMBEDKAR NAGAR 11th CROSS STREET IN DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/16092,Buildings,Completed,NN-ADYAR,177,735000,"Providing Drinking water Provision to Chennai Primary School at TNHB Colony 3rd Avenue in Dn-177 Unit -40A,Zone-13",MLACDS,13,2018-19,2020-21 NN/2018-19/16512,Parks,Completed,NN-ADYAR,177,111300,"ANNUAL MAINTENANCE FOR PARK AT LH NAGAR IV CROSS STREET PARK IN DN-177, ZONE-13, (6 MONTHS) AREA = 621.56 Sq.m.",Own Sources,13,2018-19,2019-20 NN/2018-19/16514,Parks,Completed,NN-ADYAR,177,151400,"ANNUAL MAINTENANCE FOR PARK AT NEW NGO COLONY II MAIN ROAD PARK IN DN-177, ZONE-13. (6 MONTHS) AREA = 1490 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16517,Parks,Completed,NN-ADYAR,177,101900,"ANNUAL MAINTENANCE FOR PARK AT GANGAI NAGAR II STREET IN DN-177, ZONE-13,(6 MONTHS) AREA = 668 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16564,Parks,Completed,NN-ADYAR,177,213200,"ANNUAL MAINTENANCE FOR PARK AT LABOUR COLONY IN DN-170, ZONE-13,(6 MONTHS) AREA = 1330 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16986,Buildings,Completed,NN-ADYAR,177,320000,"ERECTION OF BORE WELL 50M DEPTH (2 NOS ) WITH WATER SUPPLY ARRANGEMENTS AT CPS TNHB COLONY 3RD AVENUE ( CORE CITY SCHOOL) IN DN 177, UNIT 40A, ZONE 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/18061,Parks,Completed,NN-ADYAR,177,98100,"ANNUAL MAINTENANCE FOR PARK AT GANGAI NAGAR II STREET IN DN-177, ZONE-13,(6 MONTHS) AREA = 668 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18062,Parks,Completed,NN-ADYAR,177,145600,"ANNUAL MAINTENANCE FOR PARK AT NEW NGO COLONY II MAIN ROAD PARK IN DN-177, ZONE-13. (6 MONTHS) AREA = 1490 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18063,Parks,Completed,NN-ADYAR,177,107300,"ANNUAL MAINTENANCE FOR PARK AT LH NAGAR IV CROSS STREET PARK IN DN-177, ZONE-13, (6 MONTHS) AREA = 621.56 Sq.m.",Own Sources,13,2018-19,2020-21 NN/2018-19/18086,Parks,Completed,NN-ADYAR,177,192800,"ANNUAL MAINTENANCE FOR PARK AT LH NAGAR 3rd CROSS STREET PARK IN DN-177, ZONE-13, (6 MONTHS) AREA =1600 Sq.m.",Own Sources,13,2018-19,2020-21 NN/2018-19/2061,Electrical,Completed,NN-ADYAR,177,615000,"IMPROVEMENT WORK TO CHILDREN PLAY FIELD AT MAHALAKSHMI NAGAR 1st CROSS STREET in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2065,Playfields,Completed,NN-ADYAR,177,58000,"IMPROVEMENT WORK TO CHILDREN PLAY FIELD AT Indira Gandhi Nagar 3rd Street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2384,Playfields,Completed,NN-ADYAR,177,136000,"IMPROVEMENT WORK TO PLAY FIELD AT KAKKAN NAGAR 3rd CROSS STREET in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2459,Playfields,Completed,NN-ADYAR,177,228000,"IMPROVEMENT WORK OF PLAY FIELD AT RAMAKRISHNA NAGAR 3rd MAIN ROAD in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/2663,Roads,Completed,NN-ADYAR,177,602000,"Conversion of Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Various street, Adampakkam in Division 177, Unit 40A, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2667,Roads,Completed,NN-ADYAR,177,303000,"Repair to Street Name Boards at Various streets in Adampakkam ,Division 177, Unit 40A, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2674,Buildings,Completed,NN-ADYAR,177,517000,"Improvements and Providing Gym apparatus to GYM at Dr.AmbedkarNagar 3rd cross street in Division 177, Unit 40A, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2748,Buildings,Completed,NN-ADYAR,177,523000,"Improvements and Providing Gym apparatus to GYM at Dr.AmbedkarNagar 22nd Cross street in Division 177, Unit 40A, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5549,Roads,Completed,NN-ADYAR,177,430000,"Attending Patch work at Various street in Division-177, Unit-40A,Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/5550,Buildings,Completed,NN-ADYAR,177,246000,"Demolition Building at UPHC Center and TUCS Shop, TNHB 3rd Avenue in Division-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/5552,Buildings,Completed,NN-ADYAR,177,316000,"Temporary Arrangement for UPHC Center at Multipurpose hall, Dr.Ambedkar Nagar 20th Cross Street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/7215,Storm Water Drain,Completed,NN-ADYAR,177,546000,"Construction of storm water Drain of size 1200mmx900mm ( Road Crossing) at Nethaji salai and Size 900mmx900m at Bashyam Layout in Division-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2018-19 NN/2018-19/7236,Buildings,Completed,NN-ADYAR,177,363000,"Construction of Conservancy Inspector Room at Mahalakshmi nagar 1st Main Road in DN-177, UNIT-40A, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7969,Storm Water Drain,Completed,NN-ADYAR,177,2126000,"Minor Repair Work of Strom Water Drain at Various Streets in Dn 177, Unit 40A, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7973,Storm Water Drain,Completed,NN-ADYAR,177,1758000,"Desilting of storm water drain at various street in DN-177,Unit-40A,Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8482,Roads,Completed,NN-ADYAR,177,146000,"Relaying of Bituminous Concrete Road at Andal Nagar V cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8483,Roads,Completed,NN-ADYAR,177,208000,"Relaying of Bituminous Concrete Road at Andal Nagar VIII cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8485,Roads,Completed,NN-ADYAR,177,391000,"Relaying of Bituminous Concrete Road at Andal Nagar Extn Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8488,Roads,Completed,NN-ADYAR,177,325000,"Relaying of Bituminous Concrete Road at Ashtalakshmi Nagar XII street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8489,Roads,Completed,NN-ADYAR,177,262000,"Relaying of Bituminous Concrete Road at A.G.S Colony VI cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8490,Roads,Completed,NN-ADYAR,177,389000,"Relaying of Bituminous Concrete Road at A.G.S Colony VIII cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8492,Roads,Completed,NN-ADYAR,177,156000,"Relaying of Bituminous Concrete Road at Brindavan Nagar extn III street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8493,Roads,Completed,NN-ADYAR,177,135000,"Relaying of Bituminous Concrete Road at Bashyam Layout Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/8494,Roads,Completed,NN-ADYAR,177,193000,"Relaying of Bituminous Concrete Road at Krishanaraja Nagar extn I street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8496,Roads,Completed,NN-ADYAR,177,1093000,"Relaying of Bituminous Concrete Road at Krishanaraja Nagar extn II street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8497,Roads,Completed,NN-ADYAR,177,277000,"Relaying of Bituminous Concrete Road at Krishnaraja Nagar extn III street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8498,Roads,Completed,NN-ADYAR,177,360000,"Relaying of Bituminous Concrete Road at L H Nagar III Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8500,Roads,Completed,NN-ADYAR,177,626000,"Relaying of Bituminous Concrete Road at Lakshmi Nagar I street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8501,Roads,Completed,NN-ADYAR,177,329000,"Relaying of Bituminous Concrete Road at Lakshmi Nagar V street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8502,Roads,Completed,NN-ADYAR,177,232000,"Relaying of Bituminous Concrete Road at M.G.R Nagar I cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8506,Roads,Completed,NN-ADYAR,177,193000,"Relaying of Bituminous Concrete Road at M.G.R Nagar IV Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8507,Roads,Completed,NN-ADYAR,177,316000,"Relaying of Bituminous Concrete Road at N.N.G.O.Colony V Cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8508,Roads,Completed,NN-ADYAR,177,236000,"Relaying of Bituminous Concrete Road at N.N.G.O.Colony II Main Roadt in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8511,Roads,Completed,NN-ADYAR,177,493000,"Relaying of Bituminous Concrete Road at Nethaji Colony II Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8512,Roads,Completed,NN-ADYAR,177,241000,"Relaying of Bituminous Concrete Road at Nethaji Colony IV Cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8520,Roads,Completed,NN-ADYAR,177,684000,"Relaying of Bituminous Concrete Road at Nethaji Colony VI Cross street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8521,Roads,Completed,NN-ADYAR,177,944000,"Relaying of Bituminous Concrete Road at Ramakrishna Nagar I Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8522,Roads,Completed,NN-ADYAR,177,422000,"Relaying of Bituminous Concrete Road at Venkateswara III Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8523,Roads,Completed,NN-ADYAR,177,253000,"Relaying of Bituminous Concrete Road at Mahalakshmi Nagar I Cross Street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2020-21 NN/2018-19/8526,Roads,Completed,NN-ADYAR,177,542000,"Relaying of Bituminous Concrete Road at M.G.R Nagar 6th Main Road in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8527,Roads,Completed,NN-ADYAR,177,314000,"Relaying of Bituminous Concrete Road at LAKSHMI NAGAR 6TH STREET in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8529,Roads,Completed,NN-ADYAR,177,232000,"Relaying of Bituminous Concrete Road at LH NAGAR 6TH CROSS STREET in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8530,Roads,Completed,NN-ADYAR,177,237000,"Relaying of Bituminous Concrete Road at M.G.R NAGAR 9TH MAIN ROAD in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8572,Roads,Completed,NN-ADYAR,177,479000,"Relaying of Bituminous Concrete Road at VENKATESWARA NAGAR 2ND CROSS STREET in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8573,Roads,Completed,NN-ADYAR,177,465000,"Relaying of Bituminous Concrete Road at Mohanpuri I street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8574,Roads,Completed,NN-ADYAR,177,203000,"Relaying of Bituminous Concrete Road at Mohanpuri II street in DN-177, UNIT-40A, ZONE-13",Own Sources,13,2018-19,2019-20 P/2018-19/11976,Parks,Completed,P-Parks and Playfields,177,5700000,"FORMATION OF NEW PARK AT TNHB, 4TH STREET PLOT NO.R27 IN DN-177, ZONE-13",Grants,13,2018-19,2020-21 L/2018-19/4603,Electrical,Completed,L-Electrical,178,1599000,"PROVISION OF ADDITIONAL & RE-WIRING AT CHSS , CPS & KINDER GARDEN SCHOOL AT , RAJALAKSHMI NAGAR, VELACHERY IN DIV-178 & CHS SCHOOL AT FIVE FURLONG ROAD, MADUVANKARAI IN DIV-174, ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/6178,Electrical,Completed,L-Electrical,178,387500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at kindergarden SCHOOL IN VELACHERY in Div-178, Zone-XIII (E.B.Account no-288.008.614)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6186,Electrical,Completed,L-Electrical,178,1440500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 19 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS SCHOOL IN VELACHERY in Div-178, Zone-XIII (E.B.Account no-288.008.148)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/13153,Buildings,Completed,NN-ADYAR,178,321000,"Improvements and Providing Gym Apparatus at Bhel Shakthi Nagar Main Road in Dn 178,Unit 39, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/13419,Electrical,Completed,NN-ADYAR,178,641000,"Erection of 15nos 6/7mtr old lamp post with 40/50w LED fittings and laying of 1122mtr of 2x16sq.mm Alu cable at Ram Nagar 7th main raod, Ram Nagar 1st street, AGS Colony 7th main road, Bhel shakthi Nagar, Seetharama nagar, Udayam Nagar, Andal Avenue, Muthkrishnan street and Ramagiri Nagar Play Ground in Div 178, 179, Zone-XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16060,Buildings,Completed,NN-ADYAR,178,990000,"Providing Drinking water Provision to Govt Hr.Sec.School at Throwpathy Amman koil 5th street, Velachery in Div-178,U-39,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16389,Roads,Completed,NN-ADYAR,178,387000,"Relaying of Bituminous Road at M.G.R.Nagar X Main Road in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16391,Roads,Completed,NN-ADYAR,178,572000,"Relaying of Bitumen Concrete Road at Golden avenue main road in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/16393,Roads,Completed,NN-ADYAR,178,129000,"Relaying of Bitumen Concrete Road at Golden Avenue 1st Cross Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16394,Roads,Completed,NN-ADYAR,178,113000,"Relaying of Bitumen Concrete Road at Throwpathy Amman Koil 3rd Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16395,Roads,Completed,NN-ADYAR,178,242000,"Relaying of Bitumen Concrete Road at Throwpathy Amman Koil 4th Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16396,Roads,Completed,NN-ADYAR,178,246000,"Relaying of Bitumen Concrete Road at Throwpathy Amman Koil Main Road in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16397,Roads,Completed,NN-ADYAR,178,1068000,"Relaying of Bitumen Concrete Road at Throwpathy Amman Koil 5th Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16398,Roads,Completed,NN-ADYAR,178,282000,"Relaying of Bitumen Concrete Road at Rajalakshmi Nagar 6th Cross Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16399,Roads,Completed,NN-ADYAR,178,648000,"Relaying of Bitumen Concrete Road at Ram Nagar 6th Street(Part) in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16401,Roads,Completed,NN-ADYAR,178,634000,"Relaying of Bitumen Concrete Road at V O C Nagar 3rd Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16402,Roads,Completed,NN-ADYAR,178,648000,"Relaying of Bitumen Concrete Road at Kuberan Nagar in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16403,Roads,Completed,NN-ADYAR,178,687000,"Relaying of Bitumen Concrete Road at Devi Karumariamman Nagar 7th Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16404,Roads,Completed,NN-ADYAR,178,602000,"Relaying of Bitumen Concrete Road at Vijaya Nagar North Extention Main Road in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16405,Roads,Completed,NN-ADYAR,178,116000,"Relaying of Bitumen Concrete Road at Golden Avenue 2nd Cross Street in DN-178, UNIT-39, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16494,Parks,Completed,NN-ADYAR,178,137500,"ANNUAL MAINTENANCE FOR PARK AT AGS COLONY (ALACRITY)IN DN-178, ZONE-13,(6 MONTHS) AREA = 1303 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16496,Parks,Completed,NN-ADYAR,178,131200,"ANNUAL MAINTENACE FOR PARK AT AGS COLONY 4TH MAIN ROAD PARK IN DN-178, ZONE-13,(6 MONTHS) AREA = 983 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16618,Parks,Completed,NN-ADYAR,178,133700,"ANNUAL MAINTENANCE FOR PAR AT AGS COLONY 5TH CROSS STREET IN DN-178, UNIT-39, ZONE-13, (6 MONTHS) AREA=1517.69 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/17124,Buildings,Completed,NN-ADYAR,178,250000,"Providing Bore well for Drinking water in Chennai primary school at velachery in Div-178,U-39,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/17125,Buildings,Completed,NN-ADYAR,178,250000,"Providing Bore well for Drinking water in Chennai Higher secondary school at velachery in Div-178,U-39,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/18058,Parks,Completed,NN-ADYAR,178,126900,"ANNUAL MAINTENACE FOR PARK AT AGS COLONY 4TH MAIN ROAD PARK IN DN-178, ZONE-13,(6 MONTHS) AREA = 983 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18059,Parks,Completed,NN-ADYAR,178,131800,"ANNUAL MAINTENANCE FOR PARK AT AGS COLONY (ALACRITY)IN DN-178, ZONE-13,(6 MONTHS) AREA = 1303 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18064,Parks,Completed,NN-ADYAR,178,125100,"ANNUAL MAINTENANCE FOR PAR AT AGS COLONY 5TH CROSS STREET IN DN-178, UNIT-39, ZONE-13, (6 MONTHS) AREA=1517.69 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/2019,Roads,Completed,NN-ADYAR,178,882000,"Providing Single (124Nos) & Double (44Nos) Compactor bin platforms at various streets in Divisions - 178, 179 & 180, Unit - 39, Zone - XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/2397,Roads,Completed,NN-ADYAR,178,673000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and Providing Thermoplastic Compound marking Road pavement markers and signage boards at Various Streets in Dn 178, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2497,Playfields,Completed,NN-ADYAR,178,565000,"Improvements to Play Ground at Vijaya Nagar 1st Main Road, Ram Nagar North Extn., 1st Street, Ram Nagar 7th main road, A.G.S. Colony 6th main road & Padmavathy Nagar in Dn 178, Unit 39, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/4525,Electrical,Completed,NN-ADYAR,178,744000,"Providing Comprehensive Annual Maintenance for 4 Nos 20 KVA Diesel Genset at Chennai High School at Anna Salai in Div-170, Kotturpuram in Div-172, Kamaraj Avenue in Div-175 & Rajalakshmi Nagar, Velachery in Div-178 and 2 nos 30 KVA Diesel Genset at Chennai Higher Secondary at Maduvankarai in Div-174 and Tharamani in Div-180 & 1 No 62.5 KVA Diesel Genset at Chennai Higher Secondary School at Thiruvanmiyur in Div-182, Zone-XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/5375,Roads,Completed,NN-ADYAR,178,12800,"Repair work for Street Name Board (SINGLE ARROW) at various street in Dn 178, Unit 39 , Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5463,Roads,Completed,NN-ADYAR,178,294000,"Attending Patch work for damaged road portion (B.T. Roads) at various streets in Dn- 178, Unit- 39, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7673,Buildings,Completed,NN-ADYAR,178,682000,"Constuction of Sump and Improvement works to Amma Unavagam at Gurunanak Salai ( Velachery Main Road) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7934,Storm Water Drain,Completed,NN-ADYAR,178,1210000,"Desilting of SWD and Minor Repair works at various streets in DN 178, Unit 39, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/8025,Buildings,Completed,NN-ADYAR,178,857000,"Repairs and Improvement works to Unit Office 39 at Velachery Main Road in Dns 178 & 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2020-21 B/2018-19/11862,Buildings,Completed,B-Buildings,179,3000000,Construction of Ration shop building at Velachery in DIv-179 ZOne-13,MLACDS,13,2018-19,2019-20 L/2018-19/6176,Electrical,Completed,L-Electrical,179,1214800,"ESTIMATE for Supply, Installation, Testing & Commissioning of 16 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Seva Nagar Health Post IN VELACHERY, Div-179, Zone-XIII (E.B.Account no- 275.007.215)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6179,Electrical,Completed,L-Electrical,179,462500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 6 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS SCHOOL UDAYAM NAGAR IN VELACHERY, Div-179, Zone-XIII (E.B.Account no- 275.011.451)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/12402,Buildings,Completed,NN-ADYAR,179,406000,"Improvements to Fish market at Gandhi road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14075,Buildings,Completed,NN-ADYAR,179,177000,"Improvements to Amma Unavagam-II at Velachery-Tambaram Main Road under the flyover bridge, Opp. to Velachery MRTS Railway Station, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14076,Buildings,Completed,NN-ADYAR,179,168000,"Improvements to Amma Unavagam-I at New Colony Main Road, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/14077,Buildings,Completed,NN-ADYAR,179,710000,"Formation of road in parking area and providing gate & gate Pillar for Community Hall at Seva Nagar 1st Street, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14108,Buildings,Completed,NN-ADYAR,179,340000,"Providing water supply and electrical arrangements to e-toilet at Velachery-Taramani 100 feet road, in front of Burial Ground, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/15464,Roads,Completed,NN-ADYAR,179,108000,"Laying of C.C. road patch work at various streets in Dn-179, Unit-39, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16497,Parks,Completed,NN-ADYAR,179,118200,"ANNUAL MAINTENANCE FOR PARK AT BHARATHIAR PARK-VELACHERY MAIN ROAD IN DN-179, ZONE-13,(6 MONTHS) AREA =1200 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16498,Parks,Completed,NN-ADYAR,179,142400,"ANNUAL MAINTENANCE FOR PARK AT RAMAGIRI NAGAR I STREET IN DN-179, ZONE-13,(6 MONTHS) AREA = 1244.7 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16499,Parks,Completed,NN-ADYAR,179,324400,"ANNUAL MAINTENANCE FOR PARK AT V.G.P SELVA NAGAR II MAIN ROAD IN DN-179, ZONE-13, (6 MONTHS) AREA = 2676.5 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/17673,Roads,Completed,NN-ADYAR,179,3560000,"Formation of road with B.T. Coarse at V.G.P. Selva Nagar 4th Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17674,Roads,Completed,NN-ADYAR,179,2115000,"Formation of road with B.T. Coarse at V.G.P. Selva Nagar 5th Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17675,Roads,Completed,NN-ADYAR,179,1044000,"Formation of road with B.T. Coarse at V.G.P. Selva Nagar Extn., 2nd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17676,Roads,Completed,NN-ADYAR,179,961000,"Formation of road with B.T. Coarse at V.G.P. Selva Nagar Extn., 5th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17677,Roads,Completed,NN-ADYAR,179,3418000,"Formation of road with B.T. Coarse at Bhuvaneswari Nagar 3rd Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17678,Roads,Completed,NN-ADYAR,179,417000,"Relaying of road with B.T. Coarse at Dhandeeswaram Nagar 7th Avenue East in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17679,Roads,Completed,NN-ADYAR,179,556000,"Relaying of road with B.T. Coarse at Thiruveethamman Koil Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17680,Roads,Completed,NN-ADYAR,179,281000,"Relaying of road with B.T. Coarse at Seva Nagar 4th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17681,Roads,Completed,NN-ADYAR,179,130000,"Relaying of road with B.T. Coarse at Madhavamani Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17682,Roads,Completed,NN-ADYAR,179,380000,"Relaying of road with B.T. Coarse at V.G.P. Selva Nagar Extn-II 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17683,Roads,Completed,NN-ADYAR,179,92000,"Relaying of road with B.T. Coarse at Seethapathy Nagar 4th Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17684,Roads,Completed,NN-ADYAR,179,407000,"Relaying of road with B.T. Coarse at Venus Colony 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17685,Roads,Completed,NN-ADYAR,179,160000,"Relaying of road with B.T. Coarse at Church Gate Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17686,Roads,Completed,NN-ADYAR,179,312000,"Relaying of road with B.T. Coarse at Annai Theresa Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17687,Roads,Completed,NN-ADYAR,179,121000,"Relaying of road with B.T. Coarse at Dhandeeswaram Nagar 5th Main Road Avenue (Part) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17688,Roads,Completed,NN-ADYAR,179,210000,"Relaying of road with B.T. Coarse at Kokilam 2nd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17689,Roads,Completed,NN-ADYAR,179,85000,"Relaying of road with B.T. Coarse at Anna Nagar Extn., 2nd Cross Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17690,Roads,Completed,NN-ADYAR,179,119000,"Relaying of road with B.T. Coarse at Anna Nagar 4th Main Road (Part) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17691,Roads,Completed,NN-ADYAR,179,320000,"Relaying of road with B.T. Coarse at Bharathiyar Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17692,Roads,Completed,NN-ADYAR,179,249000,"Relaying of road with B.T. Coarse at Sony Nagar 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17693,Roads,Completed,NN-ADYAR,179,108000,"Relaying of road with B.T. Coarse at Sony Nagar 2nd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17694,Roads,Completed,NN-ADYAR,179,179000,"Relaying of road with B.T. Coarse at Sony Nagar 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17698,Roads,Completed,NN-ADYAR,179,416000,"Relaying of road with B.T. Coarse at Dhandeeswaram Nagar 7th Avenue East in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17699,Roads,Completed,NN-ADYAR,179,605000,"Relaying of road with B.T. Coarse at Anna Nagar 3rd Main Road (Part) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/18054,Parks,Completed,NN-ADYAR,179,114100,"ANNUAL MAINTENANCE FOR PARK AT BHARATHIAR PARK-VELACHERY MAIN ROAD IN DN-179, ZONE-13,(6 MONTHS) AREA =1200 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18055,Parks,Completed,NN-ADYAR,179,136700,"ANNUAL MAINTENANCE FOR PARK AT RAMAGIRI NAGAR I STREET IN DN-179, ZONE-13,(6 MONTHS) AREA = 1244.7 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18056,Parks,Completed,NN-ADYAR,179,315300,"ANNUAL MAINTENANCE FOR PARK AT V.G.P SELVA NAGAR II MAIN ROAD IN DN-179, ZONE-13, (6 MONTHS) AREA = 2676.5 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18335,Parks,Completed,P-Parks and Playfields,179,803000,"Plantation of Maintenance of Tree Saplings for One year at Various Places in Division 170,177,179, Unit-39,40A Zone 13.",Own Sources,13,2018-19,2021-22 NN/2018-19/2410,Roads,Completed,NN-ADYAR,179,285000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2466,Playfields,Completed,NN-ADYAR,179,152000,"Improvements to Childrens Play field at Tansi Nagar 6th Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2471,Playfields,Completed,NN-ADYAR,179,542000,"Improvements to Children's Play field at Baby Nagar 2nd main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/2473,Playfields,Completed,NN-ADYAR,179,826000,"Proposed construction of Toilet, Dressing Room & Store Room inside of the Basket Ball Court and Improvement works to Childrens Play Ground at Bethel Avenue 1st Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2479,Roads,Completed,NN-ADYAR,179,32000,"Repair works to existing street name board at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2483,Playfields,Completed,NN-ADYAR,179,100000,"Improvements to Childrens Play field at Andal Avenue in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/3882,Buildings,Completed,NN-ADYAR,179,187000,"Improvements and providing gym equipments to Gym Building at New Colony Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/6297,Roads,Completed,NN-ADYAR,179,942000,"Attending patch work with Bituminous Coarse at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/6685,Footpath,Completed,NN-ADYAR,179,322000,"Repair works to existing footpath at Dhandeeswaram Nagar Main Road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7939,Storm Water Drain,Completed,NN-ADYAR,179,1565000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN 179, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7976,Storm Water Drain,Completed,NN-ADYAR,179,608000,"Dismantling and Re-Construction of S.W.D. (infront of HR & CE Ground) Ch: 0 - 30 m at Dhandeeswaram Nagar 7th main road in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8139,Storm Water Drain,Completed,NN-ADYAR,179,269000,"Minor Repair works of Storm Water Drain at Various Streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8163,Storm Water Drain,Completed,NN-ADYAR,179,162000,"Replacing of damaged S.W.D. manhole doors at various streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8651,Buildings,Completed,NN-ADYAR,179,1296000,"Proposed Construction of Compound wall & Improvements to Childrens Play field at Balamurugan Nagar 3rd Street in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8671,Storm Water Drain,Completed,NN-ADYAR,179,330000,"Desilting of Kallukuttai Lake at Bharani Street, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8672,Storm Water Drain,Completed,NN-ADYAR,179,412000,"Desilting of disposal point of Six Vent Culvert at Bhuvaneswari Nagar, Velachery (Near the Velachery MRTS Railway Station) in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8720,Storm Water Drain,Completed,NN-ADYAR,179,412000,"Dismantling & Re-Construction of existing Storm water drain at Anna Nagar 3rd main road (infront of Sai Sukra Apts) Ch: 0-10m and V.G.P. Selva Nagar 2nd main road (Jn. of V.G.P. Selva Nagar 4th cross street) Ch: 0-20m, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 L/2018-19/0561,Electrical,Completed,L-Electrical,180,1876000,PROVISION OF REMOVAL AND REFIXING OF 138 NOS OF KIOSK PILLAR BOX AT VARIOUS LOCATIONS IN DIV-170 TO 182 IN ZONE-XIII,Own Sources,13,2018-19,2018-19 L/2018-19/0628,Electrical,Completed,L-Electrical,180,721000,"PROVISION OF 3 NOS 9 MTR LAMP POST WITH 2 MTR DOUBLE STRAIGHT BRACKET AND 2 NOS 9 MTR LAMP POST WITH 2 MTR TRIPLE STRAIGHT BRACKET WITH 150-165 W LED FITTING AT THARMANI 100FT ROAD, THARAMANI IN DIV-180 ZONE-XIII",Own Sources,13,2018-19,2018-19 L/2018-19/10679,Electrical,Completed,L-Electrical,180,869500,"PROVISION OF SUPPLY & ERECTION OF 3 NOS 8 MTR G.I OCTAGANAL LAMP POLE WITH G.I DOUBLE BRACKET AND LAYING OF 1351 MTRS 4X16SQ.MM ALUMINIYUM CABLE AT CSIR ROAD, THARAMANI IN DIV-180, ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/12810,Electrical,Completed,L-Electrical,180,2529000,"PROVISION OF SUPPLY AND FIXING OF 148 NOS 63AMPS MICROPROCESSOR BASED DIGITAL AUTOMATIC STREET LIGHTING ON/OFF CONTROLLING TIMER UNTIS AT VARIOUS LOCATIONS IN DIV-170 TO 182, ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/6079,Electrical,Completed,L-Electrical,180,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Unavagam, Tharamani Bus Stand in Div-180, Zone-XIII (E.B.Account no-275.014.2672)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6080,Electrical,Completed,L-Electrical,180,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Unavagam, Gothavari Street, Thanthai Periyar Nagar, Tharamani in Div-180, Zone-XIII (E.B.Account no-275.016.988)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6083,Electrical,Completed,L-Electrical,180,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC at Gothavari Street, Thanthai Periyar Nagar, Tharamani in Div-180, Zone-XIII (E.B.Account no-275.016.996)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/0545,Buildings,Completed,NN-ADYAR,180,350000,"Repair and Improvement Works to Chennai Primary School at Perumal koil Street Taramani in Division 180, Unit 39, Zone 13.",Grants,13,2018-19,2018-19 NN/2018-19/14174,Buildings,Completed,NN-ADYAR,180,363000,"Improvement works in Amma Unavagam at 100ft Road Godhavari Street & Taramani Bus Stand Road Dn 180, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14179,Roads,Completed,NN-ADYAR,180,207000,"CC Road Patch Work for damaged road portion at Kanagam Nehru street, Pillayar koil street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/15940,Buildings,Completed,NN-ADYAR,180,166250,"Providing Drinking water provision to ICDS(33603110423) at tharamani bus depot, tharamani in Div-180,U-39,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16005,Buildings,Completed,NN-ADYAR,180,166250,"Providing Drinking water provision to ICDS(33603110422) at Tharamani bus Depot, Tharamani in Div-180,U-39,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16006,Buildings,Completed,NN-ADYAR,180,166250,"Providing Drinking water provision to ICDS(33603110418) at CPS tharamani, perumal koil street in Div-180,U-39,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16007,Buildings,Completed,NN-ADYAR,180,166250,"Providing Drinking water provision to ICDS(33603110417) at Valluvar Nagar,Thiruvanmiyur in Div-180,U-39,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16198,Parks,Completed,NN-ADYAR,180,227700,"ANNUAL MAINTENANCE FOR PARK AT 4TH WEST STREET, KAMARAJ NAGAR IN DN-180, UNIT 39, ZONE-13 (6 MONTHS) AREA = 1900 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16199,Parks,Completed,NN-ADYAR,180,262000,"ANNUAL MAINTENANCE FOR PARK AT 2ND WEST STREET, KAMARAJ NAGAR IN DN-180, UNIT 39, ZONE-13,(PER YEAR) AREA = 1332 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16200,Parks,Completed,NN-ADYAR,180,199000,"ANNUAL MAINTENANCE FOR PARK AT 13TH WEST STREET, KAMARAJ NAGAR IN DN-180, UNIT 39, ZONE-13(PER YEAR) AREA = 750 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/17920,Roads,Completed,NN-ADYAR,180,271000,"RELAYING OF BT ROAD AT KAMARAJ NAGAR IV WEST STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17921,Roads,Completed,NN-ADYAR,180,220000,"RELAYING OF BT ROAD AT KAMARAJ NAGAR V WEST STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17922,Roads,Completed,NN-ADYAR,180,124000,"RELAYING OF BT ROAD AT KAMARAJ NAGAR VI WEST STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17923,Roads,Completed,NN-ADYAR,180,124000,"RELAYING OF BT ROAD AT KAMARAJ NAGAR VII WEST STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17925,Roads,Completed,NN-ADYAR,180,282000,"RELAYING OF BT ROAD AT KAMARAJ NAGAR IX WEST STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17926,Roads,Completed,NN-ADYAR,180,1238000,"RELAYING OF BT ROAD AT VILAYATTU VINAYAGAR KOIL STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17927,Roads,Completed,NN-ADYAR,180,1024000,"RELAYING OF BT ROAD AT PILLAYAR KOIL STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17928,Roads,Completed,NN-ADYAR,180,265000,"RELAYING OF BT ROAD AT TARAMANI GANDHI STREET EXTENSION IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17929,Roads,Completed,NN-ADYAR,180,459000,"RELAYING OF BT ROAD AT TARAMANI AGASTHIYAR STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17930,Roads,Completed,NN-ADYAR,180,235000,"RELAYING OF BT ROAD AT TARAMANI MA.PO.SI STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17931,Roads,Completed,NN-ADYAR,180,381000,"RELAYING OF BT ROAD AT PEELIAMMAN KOIL STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17932,Roads,Completed,NN-ADYAR,180,821000,"RELAYING OF BT ROAD AT M.G. NAGAR PILLAYAR KOIL STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17934,Roads,Completed,NN-ADYAR,180,667000,"RELAYING OF BT ROAD AT ERIKKARAI STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17935,Roads,Completed,NN-ADYAR,180,407000,"RELAYING OF BT ROAD AT PEELIAMMAN KOIL STREET-2 IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17936,Roads,Completed,NN-ADYAR,180,916000,"RELAYING OF BT ROAD AT KALAINGAR NAGAR - KARUNANITHI STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/17938,Roads,Completed,NN-ADYAR,180,293000,"RELAYING OF BT ROAD AT THANTHAI PERIYAR NAGAR - M.G.R STREET IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/17940,Roads,Completed,NN-ADYAR,180,210000,"RELAYING OF BT ROAD AT M.G.R STREET PART-1 IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/17941,Roads,Completed,NN-ADYAR,180,187000,"RELAYING OF BT ROAD AT KAMBAR STREET(PART) IN DIVISION 180, UNIT 39, ZONE 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/18053,Parks,Completed,NN-ADYAR,180,75000,"ANNUAL MAINTENANCE FOR PARK AT 4TH WEST STREET, KAMARAJ NAGAR IN DN-180, UNIT 39, ZONE-13 (6 MONTHS) AREA = 1900 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/2339,Roads,Completed,NN-ADYAR,180,1692000,"Proposed Speed breakers as IRC Design with Bituminous Concrete and providing Thermoplastic Compound Marking Road pavement markers and sinage board at various streets in Dn 180, Unit 39, Zone 13",Own Sources,13,2018-19,2019-20 NN/2018-19/2340,Buildings,Completed,NN-ADYAR,180,492000,"Improvements and Providing Gym apparatus to Kanagam Nehru street in division 180, Unit 39, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/5360,Roads,Completed,NN-ADYAR,180,21000,"Repair of street name Board (Single Arrow) in Dn 180, Unit 39 ,Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5576,Roads,Completed,NN-ADYAR,180,161000,"BT Patch work for damaged road portion at various streets in Dn-180, Unit-39, Zone-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5785,Storm Water Drain,Completed,NN-ADYAR,180,209000,"Providing Rain Water Harvesting struture at Various street in Dn 180, Unit 39, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/7958,Storm Water Drain,Completed,NN-ADYAR,180,1582000,"Desilting of SWD and Minor repair works at various streets in Dn180, Unit-39, Zone-13.",Own Sources,13,2018-19,2018-19 BR/2018-19/7985,Footpath,Completed,BR-Bus Route Roads,181,319000,"Footpath Repair Works at Besant nagar VII Avenue in Dn-181, Zone-XIII",Grants,13,2018-19,2019-20 L/2018-19/0544,Electrical,Completed,L-Electrical,181,544000,"SUPPLY AND ERECTION OF 6 NOS OF 6 MTR LAMP POST WITH 40-50W LED FITTING AT CGE COLONY PARK, & 7 NOS OF 6 MTR LAMP POST WITH 40-50W LED FITTING AT SIVASUNDAR AVENUE PLAY GROUND AT THIRUVANMIYUR IN DIV-181, ZONE-XIII",Own Sources,13,2018-19,2018-19 L/2018-19/3430,Electrical,Completed,L-Electrical,181,95800,"PROVISION OF MAINTENANCE WORK FOR THE 20 MTR HIGH MAST AT VEMBULIAMMAN KOIL STREET, THIRUVANMIYUR IN DIVISION-181, ZONE-13",Own Sources,13,2018-19,2018-19 L/2018-19/6095,Electrical,Completed,L-Electrical,181,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Unavagam, CGE Colony, Thiruvanmiyur in Div-181, Zone-XIII (E.B.Account no-202.085.1601)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6096,Electrical,Completed,L-Electrical,181,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma Unavagam, Valmiki Street, Thiruvanmiyur in Div-181, Zone-XIII (E.B.Account no-202.053.673)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6097,Electrical,Completed,L-Electrical,181,763500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CMS, Gandhigramam, Besant Nagar in Div-181, Zone-XIII (E.B.Account no-213.018.339)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6098,Electrical,Completed,L-Electrical,181,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, Kuppam Beach Road, Thiruvanmiyur in Div-181, Zone-XIII (E.B.Account no-202.085.185)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6100,Electrical,Completed,L-Electrical,181,161500,"ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, Odaikuppam, Besant Nagar in Div-181, Zone-XIII (E.B.Account no-213.013.329)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6102,Electrical,Completed,L-Electrical,181,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed, Muthulakshmi Salai, Thiruvanmiyur in Div-181, Zone-XIII (E.B.Account no-202.075.123)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/7334,Electrical,Completed,L-Electrical,181,614000,"SUPPLY AND ERECTION OF 14 NOS OF 6 MTR LAMP POST WITH 40-50W LED FITTING AT JAYARAM STREET IN DIV-181, PILLIYAR KOIL STREET EXTN , 22ND EAST STEET EXTN KAMARAJ NAGAR AND 24TH STREET THIRUVALLUVAR NAGAR AT THIRUVANMIYUR IN DIV-182, ZONE-XIII",Own Sources,13,2018-19,2018-19 NN/2018-19/10631,Electrical,Completed,NN-ADYAR,181,450000,"Providing Bio-Shredding Pulverizer Machine, Manure Seiver Machine and Weighing Machine including Civil and Electrical work for Compost yard inside Burial Ground at Rajasrinivasa Nagar in division-181, unit- 38, zone-13.",Grants,13,2018-19,2019-20 NN/2018-19/10761,Electrical,Completed,NN-ADYAR,181,106000,"PROVISION OF ADDITIONAL & RE-WIRING AT DHOBIKANA AT SRIRAM NAGAR MAIN ROAD IN DIV-181, ZONE-XIII",Own Sources,13,2018-19,2018-19 NN/2018-19/12279,Roads,Completed,NN-ADYAR,181,295000,"Laying of drainage line and Construction of Inspection Chamber and improvements to Amma Unavagam at CGE Colony and Valmiki Street in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/13566,Roads,Completed,NN-ADYAR,181,560000,"Providing Barricading arrangements at Elliots Beach in division 176, Ashtalakshmi Koil Beach in division 181 and New Beach in division 182 for New Year-2019 and Pongal Festival in Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/14266,Buildings,Completed,NN-ADYAR,181,415000,"Proposed Open Gym size 4 m X 9 m = 36 m at Gangai Street Park, Thiruvanmiyur, Chennai - 41 in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/16009,Buildings,Completed,NN-ADYAR,181,166250,"Providing Drinking water provision to ICDS(33603100408) at Lakshmipuram,Thiruvanmiyur in Div-181,U-38,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16010,Buildings,Completed,NN-ADYAR,181,166250,"Providing Drinking water provision to ICDS(33603100407) at Lakshmipuram,Thiruvanmiyur in Div-181,U-38,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16011,Buildings,Completed,NN-ADYAR,181,166250,"Providing Drinking water provision to ICDS(33603100409) at thiruvanmiyur kuppam,Thiruvanmiyur in Div-181,U-38,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16012,Buildings,Completed,NN-ADYAR,181,166250,"Providing Drinking water provision to ICDS(33603100403) at marutheeswarar,Thiruvanmiyur in Div-181,U-38,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16014,Buildings,Completed,NN-ADYAR,181,166250,"Providing Drinking water provision to ICDS(33603110120) at 11th Lane, adayar Indira Nagar in Div-175,U-40,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/16500,Parks,Completed,NN-ADYAR,181,150600,"ANNUAL MAINTENANCE FOR PARK AT M.G.R. ROAD IN DN-181, ZONE-13, (6 MONTHS) AREA = 1350 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16501,Parks,Completed,NN-ADYAR,181,431366,"ANNUAL MAINTENANCE FOR PARK AT GANGAI STREET (ARUPADAI VEEDU) IN DN -181, ZONE-13, (6 MONTHS) AREA =3600 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/16502,Parks,Completed,NN-ADYAR,181,131900,"ANNUAL MAINTENANCE FOR PARK AT CGE COLONY IN DIN-181, ZONE-13,(6 MONTHS) AREA = 1230 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/17126,Buildings,Completed,NN-ADYAR,181,250000,"Providing Bore well for Drinking water in Chennai middle school at Gandhigramam, Lakshmipuram in Div-181,U-38,Z-13.",MLACDS,13,2018-19,2020-21 NN/2018-19/18048,Parks,Completed,NN-ADYAR,181,126300,"ANNUAL MAINTENANCE FOR PARK AT CGE COLONY IN DIN-181, ZONE-13,(6 MONTHS) AREA = 1230 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18049,Parks,Completed,NN-ADYAR,181,366600,"ANNUAL MAINTENANCE FOR PARK AT GANGAI STREET (ARUPADAI VEEDU) IN DN -181, ZONE-13, (6 MONTHS) AREA =3600 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/18050,Parks,Completed,NN-ADYAR,181,144800,"ANNUAL MAINTENANCE FOR PARK AT M.G.R. ROAD IN DN-181, ZONE-13, (6 MONTHS) AREA = 1350 Sq.m",Own Sources,13,2018-19,2020-21 NN/2018-19/2141,Roads,Completed,NN-ADYAR,181,1239000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Sivasundar Avenue 1st street, Malaviya Avenue, Kalakshetra Road, Coastal Raod, Kaveri street, Arundale Beach road 3rd street, MGR Road in Dn 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2146,Electrical,Completed,NN-ADYAR,181,530000,"Improvements and Providing Gym apparatus to GYM at Marundeeswarar Nagar, Valmiki street and Vaigai stret in division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/2441,Electrical,Completed,NN-ADYAR,181,825000,"Repairs and Improvements to playgrounds at Kalakshetra road, CGE Colony, Thirumurugan 2nd street, Thirumurugan 4th street, Vaigai street in division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/3183,Roads,Completed,NN-ADYAR,181,557000,"Conversion of Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Kamaraj nagar (Marundeeswarar nagar), Subramania colony 1st street, R.B.I Colony 2nd street, Mahalakshmi Avenue, Anna Colony, Annacolony 30th cross street, Thirumurugan street, Kambar street, Pari street, Kamaraj nagar 1st east street, T.M Maistry street, Nedunchezhiyan salai, Mahalakshmi koil street, Kamarajar salai (Lakshmipuram) and Anna Street in Dn 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/3702,Buildings,Completed,NN-ADYAR,181,2657000,"Proposed Compost yard inside Burial Ground at Rajasrinivasa Nagar in division-181, unit- 38, zone-13.",Grants,13,2018-19,2018-19 NN/2018-19/5251,Footpath,Completed,NN-ADYAR,181,334000,"Repair and Improvements to Footpath at Coastal road, Beach road Near CMS, Thirumurugan Street, R.K.Nagar Main Road in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5322,Roads,Completed,NN-ADYAR,181,211000,"Repairs to Street Name Boards at Sivakamipuram 2nd cross street, M.G.R. Street, Jeevanandam Street, Raja sreenivasa nagar 1st street, Sivakamipuram 1st street, Marundeeswarar nagar, N.S.Krishnan street, Anna Street, Bharathi street, T.M.Maistry street, Thideer nagar, Byndiamman koil street, Raju street, R.K.Nagar 2nd cross street, Natesan Street, Mayana Salai, Anna Street, CGE Colony, Coastal Road, Arunadale Beach road 1st street, T.M.Maistry street Extension, R.K.Nagar Main road, Rajiv Gandhi Nagar in Dn 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5381,Storm Water Drain,Completed,NN-ADYAR,181,784000,"Providing Rain water Harvesting at Arundale Beach road, Valmiki Street, Muthulakshmi Salai, Beach road near CMS, Mahalakshmi koil street, Cholapuram, Coastal road in division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/5581,Electrical,Completed,NN-ADYAR,181,238500,"Repairs and Improvements to Public Convenience at Anna Colony in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5605,Parks,Completed,NN-ADYAR,181,68000,"Construction of Compound wall and improvement works to Road Side park at Sivakamipuram 2nd cross street in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5607,Roads,Completed,NN-ADYAR,181,404000,"Proposed BT Patches with Bituminous McAdam and Bituminous Concrete at Beach road, TM Maistry Lane, Kalakshetra road, Ashtalakshmi Garden, Marundeeswarar nagar main road, TM Maistry Street and Kamarajar nagar(Marundeeswarar nagar) in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7957,Storm Water Drain,Completed,NN-ADYAR,181,1797000,"Desilting and Repair Works to Existing Storm water Drains, Replacing Manhole Doors and Construction of Silt Catch Pits at R.K.Nagar main road and Malaviya Avenue, 7th Avenue, Marundeeswarar nagar Thiruvanmiyur in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/8013,Buildings,Completed,NN-ADYAR,181,424000,"Raising of Compound wall, Improvements of Existing Store room and Fixing of Smart toilet with Plumbing arrangements to Dhobikana at Sriram Nagar main road in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8236,Roads,Completed,NN-ADYAR,181,1305000,"Relaying of Bitumen Concrete Road at Anna Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8242,Roads,Completed,NN-ADYAR,181,1196000,"Relaying of Bitumen Concrete Road at Muthulakshmi Salai in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8259,Roads,Completed,NN-ADYAR,181,552000,"Relaying of Bitumen Concrete Road at Karunanidhi Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8260,Roads,Completed,NN-ADYAR,181,368000,"Relaying of Bitumen Concrete Road at Sivakamipuram 2nd Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8261,Roads,Completed,NN-ADYAR,181,615000,"Relaying of Bitumen Concrete Road at Pilliyar Kovil Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8263,Roads,Completed,NN-ADYAR,181,126000,"Relaying of Bitumen Concrete Road at Malaviya Avenue 1st Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/8264,Roads,Completed,NN-ADYAR,181,311000,"Relaying of Bitumen Concrete Road at Anna Colony 2nd Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8265,Roads,Completed,NN-ADYAR,181,920000,"Relaying of Bitumen Concrete Road at Valmiki Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8266,Roads,Completed,NN-ADYAR,181,653000,"Relaying of Bitumen Concrete Road at Tiger Varadhachari Road 1st Cross Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8267,Roads,Completed,NN-ADYAR,181,763000,"Relaying of Bitumen Concrete Road at Pyndiamman Koil Street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8268,Roads,Completed,NN-ADYAR,181,96000,"Relaying of Bitumen Concrete Road at TM Mastry Road Lane in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8555,Electrical,Completed,NN-ADYAR,181,282000,"Repairs and improvements to Community Hall at Lakshmipuram in Division 181, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 L/2018-19/2201,Electrical,Completed,L-Electrical,182,767000,"Removing of 2 Nos 20 Mtr High Mast at Kasi Theatre Bride Guindy in Div-170 and Ranjith Road, Kotturpuram in Div-172 and Refixing & Replacement of Accessories of 2 Nos 20 Mtr Highmast at 7th Cross Street, Play Ground, Thriuvalluvar Nagar, Thiurvanmiyur in Div-182 Zone-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/2869,Electrical,Completed,L-Electrical,182,2450000,"PROVISION OF ADDITIONAL & RE-WIRING AT CPS , PERUMAL KOIL STREET & CHSS, PEELIAMMAN KOIL STREET,THARAMANI IN DIV-180 & CHSS, A BLOCK AT BHARADIDASAN STREET, THIRUVANMIYUR IN DIV-182, ZONE-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/4116,Electrical,Completed,L-Electrical,182,183000,"PROVISION OF ADDITIONAL ELECTRIFICATION AT SMART CLASS WIRING PROPOSED FOR CHSS MADUVANKARAI IN DIV-174 AND CHSS, BHARADIDASAN STREET, THIRUVANMIYUR IN DIV-182, Z-XIII",Own Sources,13,2018-19,2019-20 L/2018-19/6107,Electrical,Completed,L-Electrical,182,989000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 13 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CHSS, Bharadidasan Street, Thiruvanmiyur in Div-182, Zone-XIII (E.B.Account no-202.086.700)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6108,Electrical,Completed,L-Electrical,182,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at CPS, Bharadidasan Street, Thiruvanmiyur in Div-182, Zone-XIII (E.B.Account no-202.081.118)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6109,Electrical,Completed,L-Electrical,182,312000,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC at 8th East Street, Kamaraj Nagar, Thiruvanmiyur in Div-182, Zone-XIII (E.B.Account no-217.008.795)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 L/2018-19/6110,Electrical,Completed,L-Electrical,182,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at NNMP Shed, Avvai Nagar, Thiruvanmiyur in Div-182, Zone-XIII (E.B.Account no-217.013.984)",SMART CITY - ELECTRICAL,13,2018-19,2019-20 NN/2018-19/13235,Electrical,Completed,NN-ADYAR,182,701000,"PROVISION OF Erection of 26 Nos Old Lamp Post and Laying of 767 Mtrs of 2x16 Sq.mm Alu Cable and S/F of 30 Nos 40-50w LED Fitting at 1st Seaward Road Park, 2nd Main Road Park and 7th Cross street, Thiruvlluvar Nagar Park at Thiruvanmiyur in DIV-182 ZONE-XIII",Own Sources,13,2018-19,2019-20 NN/2018-19/15542,Electrical,Completed,NN-ADYAR,182,432000,"Improvement and Repair works to UPHC at Kamaraj Nagar 8th East street in Division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/16575,Parks,Completed,NN-ADYAR,182,102000,"Park Maintenance for Six Months at AIBEA Nagar (Total Area - 264 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16576,Parks,Completed,NN-ADYAR,182,319000,"Park Maintenance for Six Months at Thiruvalluvar Nagar 1 Avenue (Total Area - 2640 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16577,Parks,Completed,NN-ADYAR,182,145000,"Park Maintenance for Six Months at Thiruvalluvar Nagar 43rd Cross Street (Total Area - 1322 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16578,Parks,Completed,NN-ADYAR,182,129000,"Park Maintenance for Six Months at Journalist Colony (Total Area - 1730 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16579,Parks,Completed,NN-ADYAR,182,102000,"Park Maintenance for Six Months at Kannappa Nagar (Total Area - 357 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16580,Parks,Completed,NN-ADYAR,182,119000,"Park Maintenance for Six Months at Thiruvalluvar Nagar II Main Road (Total Area - 660 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16581,Parks,Completed,NN-ADYAR,182,328000,"Park Maintenance for Six Months at Thiruvalluvar Nagar VII Cross Street (Total Area - 2192 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/16582,Parks,Completed,NN-ADYAR,182,124000,"Park Maintenance for Six Months at Valmigi Nagar 69th Cross Street (Total Area - 909 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2019-20 NN/2018-19/17988,Parks,Completed,NN-ADYAR,182,1390000,"ANNUAL MAINTENANCE FOR PARK AT River View park IN DN-172, ZONE-13,(PER SIX MONTHS) AREA = 21563 Sq.m",Own Sources,13,2018-19,2019-20 NN/2018-19/18012,Parks,Completed,NN-ADYAR,182,188000,"Annual Park Maintenance For Park at Customs Colony in Dn-170, U-40A, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18040,Parks,Completed,NN-ADYAR,182,98100,"Park Maintenance for Six Months at AIBEA Nagar (Total Area - 264 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18041,Parks,Completed,NN-ADYAR,182,309000,"Park Maintenance for Six Months at Thiruvalluvar Nagar 1 Avenue (Total Area - 2640 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18042,Parks,Completed,NN-ADYAR,182,138500,"Park Maintenance for Six Months at Thiruvalluvar Nagar 43rd Cross Street (Total Area - 1322 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18043,Parks,Completed,NN-ADYAR,182,123100,"Park Maintenance for Six Months at Journalist Colony (Total Area - 1730 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18044,Parks,Completed,NN-ADYAR,182,98100,"Park Maintenance for Six Months at Kannappa Nagar (Total Area - 357 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18045,Parks,Completed,NN-ADYAR,182,114400,"Park Maintenance for Six Months at Thiruvalluvar Nagar II Main Road (Total Area - 660 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18046,Parks,Completed,NN-ADYAR,182,317900,"Park Maintenance for Six Months at Thiruvalluvar Nagar VII Cross Street (Total Area - 2192 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18047,Parks,Completed,NN-ADYAR,182,119700,"Park Maintenance for Six Months at Valmigi Nagar 69th Cross Street (Total Area - 909 Sq.m) in Dn-182, U-38, Zone - XIII.",Own Sources,13,2018-19,2020-21 NN/2018-19/18313,Roads,Completed,NN-ADYAR,182,870000,"Relaying of Bitumen Concrete Road at Thiruvalluvar nagar 3rd avenue in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/18338,Buildings,Completed,P-Parks and Playfields,182,2658000,"Plantation of Maintenance of Tree Saplings for One year at Various Places in Division 172,173,175,176,181,182 , Unit 38,40, Zone 13.",Own Sources,13,2018-19,2021-22 NN/2018-19/2101,Buildings,Completed,NN-ADYAR,182,1800000,"Proposed Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Thiruvalluvar Nagar 2nd Avenue, Thiruvalluvar Nagar 24th cross street, Balakrishna Road, 2nd Seaward Road, Nethaji Nagar Main Road, Pillayar koil Street, Kamaraj Nagar 8th East street, Kamaraj Nagar 6th East street, Kamaraj Nagar 3rd Main Road in Dn 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/2105,Electrical,Completed,NN-ADYAR,182,405000,"Improvements and Providing Gym apparatus to GYM at Thiruvalluvar Nagar 7th cross street in division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2020-21 NN/2018-19/2187,Electrical,Completed,NN-ADYAR,182,1325000,"Repairs and Improvements to playgrounds at Thiruvalluvar Nagar 44th Cross Street, Kurinji Playground, Mullai Playground, Thamarai Playground, Thiruvalluvar nagar 7th cross street, Valmiki nagar 69th cross street, Thiruvalluvar Nagar 6th main road-1 and Thiruvalluvar Nagar 6th main road-2 in division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/3181,Roads,Completed,NN-ADYAR,182,956000,"Conversion of Speed breakers as per IRC Design with Bituminous Concrete and providing Thermoplastic Compound marking road pavement markers and signage boards at Kamaraj nagar 21st east street, Thiruveedhiamman koil street, 1st Seaward Road, Valmigi nagar 69th street, Thiruvalluvar Nagar 44th cross street, Kannappa nagar 2nd main road, Kurinji mullai marudam 6th street, Kamaraj nagar 4th main road east, Avvai nagar, Thiruvalluvar nagar 8th main road in Dn 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/3546,Electrical,Completed,NN-ADYAR,182,1165000,"Construction of Entrance gate with Pillar, Additional toilet-3Nos and Bathrooms-4Nos and Additional and Rewiring and Improvements to Night Shelter at Thiruveedhiamman Koil Street, Thiruvanmiyur in Dn-182, Unit-38, Zone-13",Own Sources,13,2018-19,2019-20 NN/2018-19/3923,Buildings,Completed,NN-ADYAR,182,10500,"SUPPLYING AND FIXING OF AWARENESS BOARD FOR BURIAL GROUNDS IN DIVISIONS - 172, 181 AND 182, ZONE - XIII",Own Sources,13,2018-19,2018-19 NN/2018-19/4969,Footpath,Completed,NN-ADYAR,182,394000,"Repair and Improvements to Footpath at Kamaraj Nagar 8th East Street, Kamaraj Nagar 3rd East Main Road, Kamaraj Nagar 6th East Street, Thiruvalluvar Nagar 2nd Avenue and Thiruvalluvar Nagar 1st Avenue, Thiruvanmiyur in Division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5318,Roads,Completed,NN-ADYAR,182,247000,"Repairs to Street Name Boards at 4th Seaward road, Kamaraj Nagar 9th East street, Kamaraj Nagar 15th East street, Bharathi Nagar 2nd cross street, Kannappa Nagar Extension, Thirumudivinayagar koil street, Puthirankanni amman koil street, Valmiki nagar 69th cross street, Avvai nagar main road in Dn 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/5380,Storm Water Drain,Completed,NN-ADYAR,182,366000,"Providing Rain water Harvesting at Balakrishna road, Thiruveediamman koil street, Vasudeva nagar, 3rd Seaward road in division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/5539,Roads,Completed,NN-ADYAR,182,127000,"Proposed laying of Bhagat Singh Salai Lane with Bituminous McAdam and Bituminous Concrete in Division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/5612,Roads,Completed,NN-ADYAR,182,218000,"Proposed BT Patches with Bituminous MacAdam and Bituminous Concrete at Rajaji Nagar main road, Thiruvalluvar nagar 2nd Avenue, Avvai nagar main road and Thiruvalluvar nagar 2nd Main road in Division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/7952,Storm Water Drain,Completed,NN-ADYAR,182,1786000,"Desilting and Repair Works to Existing Storm water Drains, Replacing Manhole Doors and Construction of Silt Catch Pits at Bharathi nagar, South Avenue, Kannappa Nagar 2nd main road, Bharathidasan Street, Rajaji Nagar Main Road, Thiruvanmiyur in Division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8274,Roads,Completed,NN-ADYAR,182,141000,"Relaying of Bitumen Concrete Road at Bharathi Nagar III Cross Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/8276,Roads,Completed,NN-ADYAR,182,196000,"Relaying of Bitumen Concrete Road at AIBEA Nagar I Cross Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8277,Roads,Completed,NN-ADYAR,182,80000,"Relaying of Bitumen Concrete Road at AIBEA Nagar I Cross Street lane in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8279,Roads,Completed,NN-ADYAR,182,232000,"Relaying of Bitumen Concrete Road at Thiruvalluvar Nagar XXIX Cross Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8281,Roads,Completed,NN-ADYAR,182,140000,"Relaying of Bitumen Concrete Road at Thiruvalluvar Nagar XVI Cross Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8282,Roads,Completed,NN-ADYAR,182,350000,"Relaying of Bitumen Concrete Road at Thiruvalluvar Nagar XXXVI Cross Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8283,Roads,Completed,NN-ADYAR,182,189000,"Relaying of Bitumen Concrete Road at Thiruvalluvar Nagar XXXVIII Cross Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8285,Roads,Completed,NN-ADYAR,182,398000,"Relaying of Bitumen Concrete Road at Thiruvalluvar Nagar VI Main Road in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8328,Roads,Completed,NN-ADYAR,182,481000,"Relaying of Bitumen Concrete Road at Radhakrishnan nagar II cross street in DN-181, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2020-21 NN/2018-19/8331,Roads,Completed,NN-ADYAR,182,127000,"Relaying of Bitumen Concrete Road at Thiruveethiamman Kovil 2nd Street in DN-182, UNIT-38, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8334,Roads,Completed,NN-ADYAR,182,331000,"Relaying of Bitumen Concrete Road at ABIEA Nagar III Main Road in DN-182, UNIT-38, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8336,Roads,Completed,NN-ADYAR,182,71000,"Relaying of Bitumen Concrete Road at AIBEA Nagar II Cross Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8338,Storm Water Drain,Completed,NN-ADYAR,182,337000,"Providing Rain water Harvesting at East Coast Road in division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2018-19 NN/2018-19/8340,Roads,Completed,NN-ADYAR,182,515000,"Relaying of Bitumen Concrete Road at Pandiyan Street in DN-182, UNIT-38, ZONE-13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8341,Roads,Completed,NN-ADYAR,182,241000,"Relaying of Bitumen Concrete Road at Kannappan Nagar II Main Road in DN-182, UNIT-38, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8343,Roads,Completed,NN-ADYAR,182,538000,"Relaying of Bitumen Concrete Road at Sannathi Street in DN-182, UNIT-38, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8344,Roads,Completed,NN-ADYAR,182,223000,"Relaying of Bitumen Concrete Road at West Tank Street in DN-182, UNIT-38, ZONE-13",Own Sources,13,2018-19,2019-20 NN/2018-19/8559,Electrical,Completed,NN-ADYAR,182,1448000,"Raising of Compound wall and Laying of Pressed Tiles to Unit Office at Kamaraj nagar 8th East street, Thiruvanmiyur in division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8742,Buildings,Completed,NN-ADYAR,182,128000,"Laying of drainage line and Construction of Inspection Chamber and Providing Syntex tank to Amma Unavagam at Avvai Nagar Main road and Thiruveediamman koil street in Division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/8749,Electrical,Completed,NN-ADYAR,182,326000,"Providing Truss at Journalists Colony Park and Painting of Walls at Valmiki Nagar 69th Crosss street in Division 182, Unit 38, Zone 13.",Own Sources,13,2018-19,2019-20 NN/2018-19/9561,Electrical,Completed,NN-ADYAR,182,2766000,"Proposed Compost yard inside Burial Ground at Thiruvalluvar Nagar 7th cross street in division-182, unit- 38, zone-13.",Grants,13,2018-19,2019-20 L/2018-19/10860,Electrical,Completed,L-Electrical,183,161400,"Work : ESTIMATE for Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kottivakkam Division office, Div-183, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/16088,Electrical,Completed,L-Electrical,183,199700,"Painting of 109nos of 6mtr lamppost with single arch bracket replacement of damaged 137nos of 2core fusebox,23nos of 4core fusebox at Palavakkam beach, Kottivakkam Kuppam and various streets in div 183,185, Zone -14",Own Sources,14,2018-19,2020-21 L/2018-19/5316,Electrical,Completed,L-Electrical,183,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Elango Nagar Anganwadi ,Kottivakkam, Div-183, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/5317,Electrical,Completed,L-Electrical,183,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kuppam Anganwadi ,Kottivakkam, Div-183, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/5320,Electrical,Completed,L-Electrical,183,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Mgr Nagar Anganwadi ,Kottivakkam, Div-183, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/0254,Storm Water Drain,Completed,NP-PERUNGUDI,183,692000,"Repairs to Storm Water Drains at Swaminadhan Nagar 8th street,Swaminadhan Nagar 4th street.Swaminadhan Nagar 1st street,Swaminadhan Nagar 3rd street,New colony main road,Sriram Avenue 2nd street,A.G.S colony 1st main road,A.G.S colony 3rd street,A.G.S colony 4th street in Dn-183, Unit-41, Zone-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/12980,Roads,Completed,NP-PERUNGUDI,183,65000,"Repairs to Existing Bus Shelter at ECR Main Road Near kottivakkam fish market and Infront of div -185 office in DN-183,unit-41,zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/13982,Buildings,Completed,NP-PERUNGUDI,183,143000,"Improvements for Kuppam Beach Public convenience (South) at Kuppam Beach Road in dn-183,Unit-41,Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/13984,Buildings,Completed,NP-PERUNGUDI,183,107000,"Improvements for Kuppam Beach Public convenience (North) at Kuppam Beach Road in dn-183,Unit-41,Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/14776,Roads,Completed,NP-PERUNGUDI,183,409000,"PROVIDING AND CONVERSION (NON IRC STANDARD) OF SPEED BREAKER AS PER IRC STANDARD WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGN BOARD AND STUDS AT VARIOUS STREETS IN DN-183, U-41, Z-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15895,Roads,Completed,NP-PERUNGUDI,183,131000,"Attending B.T Patch work at various streets in Division 183,unit-41,zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15931,Parks,Completed,NP-PERUNGUDI,183,240000,"MAINTENANCE ESTIMATE FOR PARK AT NETCO COLONY IN DIV-183, UNIT-41,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/2790,Roads,Completed,NP-PERUNGUDI,183,9082000,"Forming and Laying of Bituminous concrete Road at Ilango Nagar in Dn-183, Unit-41, Zone-14.",Grants,14,2018-19,2020-21 NP/2018-19/2791,Roads,Completed,NP-PERUNGUDI,183,548000,"Relaying of Bituminous concrete Road at Netco colony in Dn-183, Unit-41, Zone-14.",Grants,14,2018-19,2020-21 NP/2018-19/2882,Roads,Completed,NP-PERUNGUDI,183,671000,"PROVIDING NEW SPEED BREAKER AS PER IRC STANDARD WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGN BOARD AND STUDS AT VARIOUS STREETS IN DN-186, U-41, Z-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/2885,Roads,Completed,NP-PERUNGUDI,183,653000,"Providing new speed breaker as per IRC standard with bituminous concrete and also fixing sign board and studs at various street in dn-183,Unit-41,zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/3092,Playfields,Completed,NP-PERUNGUDI,183,1055400,"Forming Kabaddi Court (3 Nos|) With Electrical Arrangements and Providing FRC Bench(19 Nos) at AGS Colony Play Ground( Beach side) in Dn-183, Unit-41, Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/3696,Roads,Completed,NP-PERUNGUDI,183,562000,"Proposed Construction for R.C.C kitchen room,dining hall and other improvements to existing community hall with Electrical arrangements at Kuppam Beach in DN-183, UNIT-41,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/6518,Parks,Completed,NP-PERUNGUDI,183,798100,"Improvements Works with Electrical Arrangements for A.G.S Colony Play Ground in Dn-183, Unit-41, Zone-XIV.",Own Sources,14,2018-19,2018-19 NP/2018-19/6657,Roads,Completed,NP-PERUNGUDI,183,234000,"Improvements to Street name board at Various locations in Dn-183,184,185 & 186 , Unit-41, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/7579,Parks,Completed,NP-PERUNGUDI,183,361000,"Providing Open Gym at A.G.S Colony Play Ground(Ecr Side) in Dn-183, Unit-41, Zone-XIV.",Own Sources,14,2018-19,2018-19 NP/2018-19/9514,Storm Water Drain,Completed,NP-PERUNGUDI,183,2467000,"DESILTING OF STORM WATER DRAIN, SIDE DRAIN IN DN-183,184,185,186,189,190 AND 191, UNIT-41 AND UNIT-43 , ZONE-14",Own Sources,14,2018-19,2018-19 NP/2018-19/9518,Storm Water Drain,Completed,NP-PERUNGUDI,183,913000,"MINOR REPAIR WORKS IN DN-183,184, AND 185, UNIT-41 , ZONE-14",Own Sources,14,2018-19,2019-20 B/2018-19/4223,Buildings,Completed,B-Buildings,184,10387175,"Supply, Installation, testing and Commissioning of Fire fighting system and Medical Gas System maintenance for 1 year in Communtiy Health Center(100 Beds) at Perungudi in Div 184 zone 14",Grants,14,2018-19,2020-21 L/2018-19/11504,Electrical,Completed,L-Electrical,184,196000,"Work: Provision of removal and refixing of 7nos 6 Mtr lamp hot dip post with Single arch Bracket , 270 mtr 4x16sqmm damaged cable replacement at MGR Salai link road in div 184 Zone-XIV",Own Sources,14,2018-19,2019-20 L/2018-19/16318,Electrical,Completed,L-Electrical,184,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Annasalai, Shopping complex , Div-184, Zone-XIV (E.B.Account no-326-001-549 )",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/16332,Electrical,Completed,L-Electrical,184,311900,"ESTIMATE for Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at MGRSalai jn TNEB, Div-184, Zone-XIV (E.B.Account no-298-004-734 )",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/16334,Electrical,Completed,L-Electrical,184,236600,"ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at School road,Division office, Div-184, Perungudi Zone-XIV (E.B.Account no-326-003-740)",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/0245,Roads,Completed,NP-PERUNGUDI,184,783000,"Improvements for storm water drain at CBI Colony 2nd main road,school road,anna nedunchalai,Ramappa nagar main road, Telephoe nagar main road ,sai ayush pooja street in DN-184,UNIT-41,ZONE-14",Own Sources,14,2018-19,2018-19 NP/2018-19/10896,Parks,Completed,NP-PERUNGUDI,184,22000,"Improvements for Anna Nedunchalai (OSR park ) at Anna Nedunchalai IN div-184,unit-41,zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/13308,Buildings,Completed,NP-PERUNGUDI,184,282000,"Improvements for Unit -41 office at School Road in DN-184,Unit-41,Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15023,Buildings,Completed,NP-PERUNGUDI,184,110000,"IMPROVEMENT WORKS OF GASIFIER AT SCHOOL ROAD IN DN-184,U-41,Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15024,Parks,Completed,NP-PERUNGUDI,184,378000,"Providing Open Gym at Telephone Nagar Park in Dn-184, Unit-41, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/15025,Parks,Completed,NP-PERUNGUDI,184,378000,"Providing Open Gym at Thiruvalluvar Nagar Park in Dn-184, Unit-41, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/15026,Buildings,Completed,NP-PERUNGUDI,184,342000,"Improvement Work for Telephone Nagar Park in Dn-184, Unit-41, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/15029,Buildings,Completed,NP-PERUNGUDI,184,80000,"IMPROVEMENT TO 16TH CERENONY HALL AT ANNA NEDUNCHALAI IN Dn-184, Unit-41, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/15879,Roads,Completed,NP-PERUNGUDI,184,212000,"Attending B.T Patch Work at Various Streets in Division - 184, Unit-41, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15933,Parks,Completed,NP-PERUNGUDI,184,881000,"MAINTENANCE ESTIMATE FOR PARK AT LAKSHMAN NAGAR (CBI COLONY) 2ND MAIN ROAD IN DIV-184, UNIT-41,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15935,Parks,Completed,NP-PERUNGUDI,184,921000,"MAINTENANCE ESTIMATE FOR PARK AT TELEPHONE NAGAR 2ND CROSS STREET IN DIV-184, UNIT-41,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15937,Parks,Completed,NP-PERUNGUDI,184,616000,"MAINTENANCE ESTIMATE FOR PARK AT THIRUVALLUVAR STREET IN DIV-184, UNIT-41,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15938,Parks,Completed,NP-PERUNGUDI,184,268000,"MAINTENANCE ESTIMATE FOR PARK AT ANNA NEDUNCHALAI IN DIV-184, UNIT-41,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15939,Parks,Completed,NP-PERUNGUDI,184,272000,"MAINTENANCE ESTIMATE FOR PARK AT RAMAPPA NAGAR IN DIV-184, UNIT-41,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/16490,Roads,Completed,NP-PERUNGUDI,184,615000,"Attending Patch Work at Various Streets in Dn-184,Unit-41,Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/16773,Buildings,Completed,NP-PERUNGUDI,184,762500,"Maintenance of Gasifier Crematorium in Hindu Burial Ground at School Road in Div-184, Unit-41, Zone-14.",Own Sources,14,2018-19,2020-21 NP/2018-19/2887,Roads,Completed,NP-PERUNGUDI,184,356000,"PROVIDING NEW SPEED BREAKER AS PER IRC STANDARD WITH BITUMINOUS CONCRETE AND ALSO FIXING SIGN BOARD AND STUDS AT VARIOUS STREETS IN DN-184, U-41, Z-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/8376,Parks,Completed,NP-PERUNGUDI,184,477000,"Improvements for TWIN Court (OSR park ) at Anna Nedunchalai IN div-184,unit-41,zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/8779,Electrical,Completed,NP-PERUNGUDI,184,1455120,"Provision of 19 nos 6 Mtr lamp hot dip post with Single st Bracket with 40-50w LED Fitting ,4nos of 6 Mtr lamp hot dip galvanising post with 100w LED FL Fitting at Annanedunchalai (Faery estate )park in Division-184, Zone-XIV",Own Sources,14,2018-19,2018-19 NP/2018-19/8874,Buildings,Completed,NP-PERUNGUDI,184,107000,"Construction of Additional septic tank at Erikarai Public Convenience in Dn-184,Unit-41, Zone-14.",Own Sources,14,2018-19,2019-20 L/2018-19/10853,Electrical,Completed,L-Electrical,185,387200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Palavakkam UPHC, Div-185, Zone-XIV (E.B.Account no-206.010.51 )",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/5321,Electrical,Completed,L-Electrical,185,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Burma Colony Anganwadi ,Palavakkam, Div-185, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/0239,Storm Water Drain,Completed,NP-PERUNGUDI,185,109000,"Repairs to Storm Water Drains at Govindhnagar 1st street (south),Govindhnagar 1st main road,Burma coclony 1st main road,Estate main road,Periyar street,Ambedkar street,Bharathiyar street,Kandahsamy nagar 6th street in Dn-185, Unit-41, Zone-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/14765,Buildings,Completed,NP-PERUNGUDI,185,75000,"Providing Barricading Arrangements and Mobile Toilet Arrangements at Palavakkam beach in Dn-185, Unit-41, Zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/15897,Roads,Completed,NP-PERUNGUDI,185,87900,"Attending B.T Patch Work at Various Streets in Division - 185, Unit-41, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15928,Parks,Completed,NP-PERUNGUDI,185,592000,"MAINTENANCE ESTIMATE FOR PARK AT PALAVAKKAM ECR ( AMARA) IN DIV-185, UNIT-41,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15930,Parks,Completed,NP-PERUNGUDI,185,830000,"MAINTENANCE ESTIMATE FOR PARK AT VGP LAYOUT 4TH MAIN ROAD IN DIV-185, UNIT-41,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/2320,Roads,Completed,NP-PERUNGUDI,185,499000,"Providing new speed breaker as per IRC standard with bituminous concrete and also fixing sign board and studs at various street in dn-185,unit-41,zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/5124,Electrical,Completed,NP-PERUNGUDI,185,444300,"PROVISION OF ADDITIONAL & RE-WIRING IN UPHC AT PALAVAKKAM IN DIVISION -185, ZONE-XIV",Own Sources,14,2018-19,2018-19 NP/2018-19/7685,Roads,Completed,NP-PERUNGUDI,185,721000,"Attending B.T Patch Work at Various Locations in Division - 183,184,185 and 186, Unit-41, Zone-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/7964,Buildings,Completed,B-Buildings,185,1293000,"Improvements to UPHC Building With ElectricalArrangements at East Coast Road in Dn-185,Unit-41,Zone-14.",Own Sources,14,2018-19,2019-20 L/2018-19/12266,Electrical,Completed,L-Electrical,186,199700,Work: Provision of Cement concrete pedestal and fuse box for street lamp post at Perungudi dumping ground in Div 186 Zone XIV,Own Sources,14,2018-19,2019-20 L/2018-19/12851,Electrical,Completed,L-Electrical,186,196600,Work: Provision of 1665 mtr 2x10sqmm cable overhead supply line for three weighbridges at Perungudi dumping ground in Div 186 Zone XIV,Own Sources,14,2018-19,2019-20 L/2018-19/14483,Electrical,Completed,L-Electrical,186,199980,Provision of 912mtr 3 1/2x25sqmm cable overhead supply line for Streetlamp post from PDG Main gate (near corporation road) to towards zone12 dumping area at Perungudi dumping ground in Div 186 Zone XIV,Own Sources,14,2018-19,2019-20 L/2018-19/14484,Electrical,Completed,L-Electrical,186,199600,Provision of 851 mtr 4x16sqmm cable overhead supply line for Streetlamp post from container jn to towards radial road side gate side & 206 mtr 3 1/2 x25sqmm cable overhead supply line for Streetlamp post from zone11 dumping area to zone13 dumping area at Perungudi dumping ground in Div 186 Zone - XIV,Own Sources,14,2018-19,2019-20 L/2018-19/14485,Electrical,Completed,L-Electrical,186,199890,Provision of 592 mtr 4x16sqmm cable overhead supply line for Streetlamp post from container jn to towards radial road side gate side & 193 mtr 3 1/2 x25sqmm cable overhead supply line for Streetlamp post from zone11 dumping area to zone12 dumping area at Perungudi dumping ground in Div 186 Zone - XIV,Own Sources,14,2018-19,2019-20 L/2018-19/16337,Electrical,Completed,L-Electrical,186,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at VPK Street ,Schreding machine room, Div-186, Zone-XIV (E.B.Account no-204-005-740)",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/0242,Roads,Completed,NP-PERUNGUDI,186,211000,"Improvements for storm water drain at Thirumalai nagar main road,Rajiv nagar 2nd main road,Elim nagar manthoppu street in DN-186,UNIT-41,ZONE-14",Own Sources,14,2018-19,2018-19 NP/2018-19/12641,Parks,Completed,NP-PERUNGUDI,186,1300000,"Providing Open Gym and scatting court at Thirumalai Nagar park in Division-186, Unit-41, Zone-XIV.",MLACDS,14,2018-19,2019-20 NP/2018-19/13504,Buildings,Completed,NP-PERUNGUDI,186,3000000,PROPOSED CONSTRUCTION OF ADDITIONAL CLASS ROOMS AND TOILET BLOCKS IN PANCHAYAT UNION PRIMARY SCHOOL AT SCHOOL ROAD IN DIVISION -186 UNIT-41 ZONE-14 (MP FUND),MPLADS,14,2018-19,2019-20 NP/2018-19/15882,Roads,Completed,NP-PERUNGUDI,186,215000,"Attending B.T Patch Work at Various Locations in Division - 186, Unit-41, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15929,Parks,Completed,NP-PERUNGUDI,186,277000,"MAINTENANCE ESTIMATE FOR PARK AT VENGATESWARA NAGAR IN DIV-186, UNIT-41,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15932,Parks,Completed,NP-PERUNGUDI,186,235000,"MAINTENANCE ESTIMATE FOR PARK AT OMATHURAI PARK IN DIV-186, UNIT-41,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15934,Parks,Completed,NP-PERUNGUDI,186,827000,"MAINTENANCE ESTIMATE FOR PARK AT THIRUMALAI NAGAR 1ST MAIN ROAD IN DIV-186, UNIT-41,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15936,Parks,Completed,NP-PERUNGUDI,186,649000,"MAINTENANCE ESTIMATE FOR PARK AT RAJIV NAGAR IN DIV-186, UNIT-41,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/2785,Roads,Completed,NP-PERUNGUDI,186,6448000,"Relaying of Bituminous concrete Road at Corporation Road in Dn-186, Unit-41, Zone-14.",Grants,14,2018-19,2018-19 NP/2018-19/2787,Roads,Completed,NP-PERUNGUDI,186,335000,"Relaying of Bituminous concrete Road at Kamarajar 7th Cross street in Dn-186, Unit-41, Zone-14.",Grants,14,2018-19,2019-20 NP/2018-19/2788,Roads,Completed,NP-PERUNGUDI,186,335000,"Relaying of Bituminous concrete Road at Kamarajar 8th Cross street in Dn-186, Unit-41, Zone-14.",Grants,14,2018-19,2019-20 NP/2018-19/2789,Roads,Completed,NP-PERUNGUDI,186,588000,"Relaying of Bituminous concrete Road at Vargeesh street in Dn-186, Unit-41, Zone-14.",Grants,14,2018-19,2019-20 NP/2018-19/3129,Playfields,Completed,NP-PERUNGUDI,186,386000,"Supplying and Fixing for Pre- Fabricated Sintex Security Cabin(12 Nos) at Perungudi Dumping Ground in Dn-186, Unit-41, Zone-14.",Own Sources,14,2018-19,2018-19 D/2018-19/8359,Storm Water Drain,Completed,D-Storm Water Drains,187,18273000,Restoration and other improvements to the pond at Madiapakkam Lake in Dn - 187 Zone 14.,SMART CITY - SWD,14,2018-19,2020-21 D/2018-19/8456,Storm Water Drain,Completed,D-Storm Water Drains,187,12600000,"Restoration and other improvements to Madipakkam village pond in Dn. - 187, Zone-14.",SMART CITY - SWD,14,2018-19,2020-21 NP/2018-19/10532,Parks,Completed,NP-PERUNGUDI,187,383500,"Proposed Open Gym at Mahatma Gandhi Park in Dn-187, Unit-42, Zone-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/11132,Electrical,Completed,NP-PERUNGUDI,187,352300,"Provision of 5 nos of 6 mtr hot dip galvanized lamp post with 40-50W LED fitting in Senthuran Colony play ground in division 187, zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15758,Roads,Completed,NP-PERUNGUDI,187,366000,"ATTENDING ROAD PATCH WORK IN VARIOUS STREET IN DN-187, U-42, Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15925,Parks,Completed,NP-PERUNGUDI,187,232000,"MAINTENANCE ESTIMATE FOR PARK AT MAHATMA GANDHI PARK IN DIV-187, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15926,Parks,Completed,NP-PERUNGUDI,187,193000,"MAINTENANCE ESTIMATE FOR PARK AT PARK SQUARE COLONY IN DIV-187, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15927,Parks,Completed,NP-PERUNGUDI,187,222000,"MAINTENANCE ESTIMATE FOR PARK AT KARTHIKEYAPURAM 6TH STREET IN DIV-187, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/1676,Roads,Completed,NP-PERUNGUDI,187,1114000,"RE-LAYING OF B.T. ROAD WITH PAVER FINISHER AT NEW KUBERA NAGAR 5TH STREET IN DN-187, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/2746,Roads,Completed,NP-PERUNGUDI,187,760000,"RE-LAYING OF B.T. ROAD WITH PAVER FINISHER AT NEW KUBERA NAGAR 7TH STREET IN DN-187, U-42, Z-14",Grants,14,2018-19,2019-20 NP/2018-19/2773,Roads,Completed,NP-PERUNGUDI,187,319000,"FORMATION AND LAYING OF B.T.ROAD WITH PAVER FINISHER AT KARTHIKEYAPURAM 2ND CROSS STREET (MATHURAKAALI NAGAR WEST) IN DN-187, U-42, Z-14.",Grants,14,2018-19,2019-20 NP/2018-19/5256,Roads,Completed,NP-PERUNGUDI,187,36000,"Providing thermoplast compound marking to existing IRC standard speed breakers for IRR at Madipakkam main road (2 Nos) in DN-187, U-42, Z-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/5674,Roads,Completed,NP-PERUNGUDI,187,267000,"Repair works to Street Name Board at Various streets in Dn-187 & 188, U-42, Z-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/7719,Roads,Completed,NP-PERUNGUDI,187,69000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIV-187, UNIT-42, ZONE-14.",Own Sources,14,2018-19,2019-20 B/2018-19/8632,Buildings,Completed,B-Buildings,188,9710000,"Construction of Urban Primary Health Center at Kulakarai Street, Madipakkam in Div-188, Zone-14",Grants,14,2018-19,2020-21 D/2018-19/1980,Storm Water Drain,Completed,D-Storm Water Drains,188,12510000,"Construction of Storm Water Drain of size 1500 x 1500 along TNEB road from dead end to the existing drain at Tambaram Velachery main road in Dn-188, Zone-XIV.",Own Sources,14,2018-19,2018-19 D/2018-19/2030,Storm Water Drain,Completed,D-Storm Water Drains,188,1900000,"Construction of storm water drain of size 3000X3000mm along Tambaram Velachery Main Road from north end of T.N.E.B Road to south end of T.N.E.B Road in Dn- 188,Zone-XIV.",Own Sources,14,2018-19,2018-19 L/2018-19/16322,Electrical,Completed,L-Electrical,188,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Office Building, Madipakkam, Div-188, Zone-XIV (E.B.Account no- 245-233-1732)",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/16323,Electrical,Completed,L-Electrical,188,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at School Building, Madipakkam, Div-188, Zone-XIV (E.B.Account no- 245-222-1077)",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/16324,Electrical,Completed,L-Electrical,188,236700,"Estimate for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Hall, Madipakkam, Div-188, Zone-XIV.",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/1998,Electrical,Completed,L-Electrical,188,721100,"Work: Provision of 14 nos 6 Mtr lamp hot dip post with Single st Bracket with 40-50w LED Fitting , at (Odisha Bhawan)TNEB road of Tambaram velachery main road near kamatchi hospital junction in Division-188,Madippakkam ,Zone-XIV",Own Sources,14,2018-19,2018-19 NP/2018-19/0205,Storm Water Drain,Completed,NP-PERUNGUDI,188,605000,"REPAIR WORK OF STORM WATER DRAIN AT LIC NAGAR 2ND STREET,RAM NAGAR 8TH CROSS STREET AND ETC IN DN-188,U-42,Z-14",Own Sources,14,2018-19,2018-19 NP/2018-19/10801,Parks,Completed,NP-PERUNGUDI,188,1727000,"Improvements Works at Ram nagar 8th Cross street Park inDiv-188,U-42,Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/10891,Buildings,Completed,NP-PERUNGUDI,188,317000,"PROVIDING FRONT SHED AT 188 DIVISION OFFICE IN DIV-188,UNIT-42,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/10949,Road Cut,Completed,NP-PERUNGUDI,188,1672000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT GANESAN STREET, ARUMUGAM STREET, PONNIAMMAN STREET, PERUMAL STREET, AMMAN STREET, GANGAI STREET, KAVERI STREET, YAMUNA STREET AND SARASWATHY STREET IN DN-188, U-42, Z-14",Deposit Works,14,2018-19,2019-20 NP/2018-19/15158,Buildings,Completed,NP-PERUNGUDI,188,520000,"REPAIRS AND IMPROVEMENTS WORK OF BUS SHELTER AT MADIPAKKAM BUS STAND IN DIV-188,UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15916,Parks,Completed,NP-PERUNGUDI,188,270000,"MAINTENANCE ESTIMATE FOR PARK AT RAMAMOORTHY NAGAR 1ST MAIN ROAD IN DIV-188, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15918,Parks,Completed,NP-PERUNGUDI,188,210000,"MAINTENANCE ESTIMATE FOR PARK AT ANNA NAGAR 5TH STREET IN DIV-188, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15919,Parks,Completed,NP-PERUNGUDI,188,261000,"MAINTENANCE ESTIMATE FOR PARK AT RAJALAKSHMI NAGAR 1ST MAIN ROAD IN DIV-188, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15921,Parks,Completed,NP-PERUNGUDI,188,208000,"MAINTENANCE ESTIMATE FOR PARK AT RAJESH NAGAR VELACHERY MAIN ROAD IN DIV-188, UNIT-42,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/1730,Roads,Completed,NP-PERUNGUDI,188,2447000,"Forming and Laying of BT road with Paver Finishing at Odisha Bhavan TNEB Road Reach 1 near Kamatchi Hospital in Dn-188, Unit-42, Zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/1735,Roads,Completed,NP-PERUNGUDI,188,2445000,"Forming and Laying of BT road with Paver Finishging at Odisha Bhavan TNEB Road Reach 3 near Kamatchi Hospital in Dn-188, Unit-42, Zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/1738,Roads,Completed,NP-PERUNGUDI,188,2447000,"Forming and Laying of BT road with Paver Finishging at Odisha Bhavan TNEB Road Reach 4 near Kamatchi Hospital in Dn-188, Unit-42, Zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/1739,Roads,Completed,NP-PERUNGUDI,188,2493000,"Forming and Laying of BT road with Paver Finishging at Odisha Bhavan TNEB Road Reach 5 near Kamatchi Hospital in Dn-188, Unit-42, Zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/1878,Buildings,Completed,NP-PERUNGUDI,188,1255000,"CONSTRUCTION OF COMPOUND WALL AT SADASIVAM NAGAR BURIAL GROUND IN DN-188,U-42,Z-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/1891,Roads,Completed,NP-PERUNGUDI,188,1928000,"Forming and Laying of BT road with Paver Finishging at Odisha Bhavan TNEB Road Reach 2 near Kamatchi Hospital in Dn-188, Unit-42, Zone-14",Own Sources,14,2018-19,2018-19 NP/2018-19/2554,Roads,Completed,NP-PERUNGUDI,188,764000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN WITH BITUMINOUS CONCRETE ALSO FIXING SIGNAGE BOARD, PAVEMENT MARKER, ROAD STRUDS AT VARIOUS STREETS IN DN -188, U - 42, Z-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/2555,Roads,Completed,NP-PERUNGUDI,188,531000,"PROVIDING SPEED BREAKER AS PER IRC DESIGN WITH BITUMINOUS CONCRETE ALSO FIXING SIGNAGE BOARD, PAVEMENT MARKER, ROAD STRUDS AT VARIOUS STREET IN DN - 188, U - 42, Z-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/2572,Roads,Completed,NP-PERUNGUDI,188,220000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT DR. AMBEDKAR SALAI IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2578,Roads,Completed,NP-PERUNGUDI,188,1610000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT GOVINDAN STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2581,Roads,Completed,NP-PERUNGUDI,188,1508000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT KESAVAN STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2582,Roads,Completed,NP-PERUNGUDI,188,322000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT KUBERA NAGAR EXTN. 3RD STREET PART IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2583,Roads,Completed,NP-PERUNGUDI,188,510000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT KULAKKARAI STREET PART IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2584,Roads,Completed,NP-PERUNGUDI,188,322000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT LIC NAGAR 5TH CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2585,Roads,Completed,NP-PERUNGUDI,188,1438000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT MADHAVA STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2587,Roads,Completed,NP-PERUNGUDI,188,903000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT MUTHAMIZH VIDHYA NAGAR IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2588,Roads,Completed,NP-PERUNGUDI,188,1332000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT MYLLAI BALAJI NAGAR BACKSIDE ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2589,Roads,Completed,NP-PERUNGUDI,188,1484000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT MYLLAI BALAJI NAGAR 3RD BLOCK BACKSIDE ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2590,Roads,Completed,NP-PERUNGUDI,188,1886000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT MYLLAI BALAJI NAGAR 4TH BLOCK BACKSIDE ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2592,Roads,Completed,NP-PERUNGUDI,188,657000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT NARASIMAN STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2593,Roads,Completed,NP-PERUNGUDI,188,1320000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAJAJI NAGAR 1ST CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2595,Roads,Completed,NP-PERUNGUDI,188,1029000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAJAJI NAGAR 2ND CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2596,Roads,Completed,NP-PERUNGUDI,188,501000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAJESH NAGAR 2ND MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2599,Roads,Completed,NP-PERUNGUDI,188,645000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAJESH NAGAR 4TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2609,Roads,Completed,NP-PERUNGUDI,188,2157000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR 14TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2610,Roads,Completed,NP-PERUNGUDI,188,5015000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR 8TH CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2611,Roads,Completed,NP-PERUNGUDI,188,2651000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR SOUTH 10TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2612,Roads,Completed,NP-PERUNGUDI,188,2629000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR SOUTH 11TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2613,Roads,Completed,NP-PERUNGUDI,188,1987000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR SOUTH 12TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2621,Roads,Completed,NP-PERUNGUDI,188,2168000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR SOUTH 13TH MAIN ROAD (PART) IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2623,Roads,Completed,NP-PERUNGUDI,188,2737000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR SOUTH 9TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2626,Roads,Completed,NP-PERUNGUDI,188,2866000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR SOUTH EXTN. 3RD STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2627,Roads,Completed,NP-PERUNGUDI,188,1814000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT RAM NAGAR SOUTH EXTN. 9TH STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2629,Roads,Completed,NP-PERUNGUDI,188,620000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT SADASIVAM NAGAR 3RD STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2630,Roads,Completed,NP-PERUNGUDI,188,492000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT THIRUVALLUVAR STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2631,Roads,Completed,NP-PERUNGUDI,188,306000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT VISHAL NAGAR IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2636,Roads,Completed,NP-PERUNGUDI,188,1234000,"FORMING AND LAYING OF B.T ROAD WITH PAVER FINISHER AT WEST ANNA NAGAR 6TH STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2638,Roads,Completed,NP-PERUNGUDI,188,539000,"RELAYING OF ROAD AT ARULMURUGAN NAGAR 1ST STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2639,Roads,Completed,NP-PERUNGUDI,188,2410000,"RELAYING OF ROAD AT RAM NAGAR 4TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2640,Roads,Completed,NP-PERUNGUDI,188,3175000,"RELAYING OF ROAD AT RAM NAGAR 5TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2641,Roads,Completed,NP-PERUNGUDI,188,2733000,"RELAYING OF ROAD AT RAM NAGAR 6TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2642,Roads,Completed,NP-PERUNGUDI,188,2836000,"RELAYING OF ROAD AT RAM NAGAR 7TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2643,Roads,Completed,NP-PERUNGUDI,188,2965000,"RELAYING OF ROAD AT RAM NAGAR 8TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2644,Roads,Completed,NP-PERUNGUDI,188,526000,"RELAYING OF ROAD AT RAM NAGAR 9TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2645,Roads,Completed,NP-PERUNGUDI,188,1420000,"RELAYING OF ROAD AT RAM NAGAR 11TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2646,Roads,Completed,NP-PERUNGUDI,188,825000,"RELAYING OF ROAD AT RAM NAGAR 12TH MAIN ROAD IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2647,Roads,Completed,NP-PERUNGUDI,188,1911000,"RELAYING OF ROAD AT RAM NAGAR 5TH CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2019-20 NP/2018-19/2648,Roads,Completed,NP-PERUNGUDI,188,1195000,"RELAYING OF ROAD AT RAM NAGAR 6TH CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2649,Roads,Completed,NP-PERUNGUDI,188,2343000,"RELAYING OF ROAD AT RAM NAGAR 7TH CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/2650,Roads,Completed,NP-PERUNGUDI,188,2984000,"RELAYING OF ROAD AT RAM NAGAR 8TH CROSS STREET IN DIV-188, UNIT-42, ZONE-14",Grants,14,2018-19,2018-19 NP/2018-19/5901,Roads,Completed,NP-PERUNGUDI,188,833000,"Providing Hume pipe,Gate and WMM Forming to th road, Repair works to compound wall and Security room Old Dumping ground in Dn-188,U-42,Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/5902,Buildings,Completed,NP-PERUNGUDI,188,680000,"New Construction of Toilet, sump and septic tank at Old Dumping Ground near Compost Yard in Dn-188,U-42,Z-14",Own Sources,14,2018-19,2018-19 NP/2018-19/7720,Roads,Completed,NP-PERUNGUDI,188,1676000,"ATTENDING ROAD PATCH WORK AT VARIOUS STREETS IN Dn-188,U-42,Z-14",Own Sources,14,2018-19,2019-20 NP/2018-19/9358,Storm Water Drain,Completed,NP-PERUNGUDI,188,2007000,"DESILTING OF STORM WATER DRAIN, SIDE DRAIN AND CANAL IN DN-187 AND DN-188, UNIT-42, ZONE-14",Own Sources,14,2018-19,2018-19 NP/2018-19/9516,Storm Water Drain,Completed,NP-PERUNGUDI,188,819000,"MINOR REPAIR WORKS IN DN-187 AND 188,UNIT-42 , ZONE-14",Own Sources,14,2018-19,2018-19 BR/2018-19/5188,Roads,Completed,BR-Bus Route Roads,189,168000,REMOVING AND REFIXING OF MODERN STAINLESS STEEL BUS SHELTER AT VELACHERY TO TAMBARAM ROAD (JUNCTION OF THULUKATHAMMAN KOIL STREET PALLIKARANAI BUS STOP) IN DIV-189 ZONE-14.,Own Sources,14,2018-19,2019-20 BR/2018-19/5189,Roads,Completed,BR-Bus Route Roads,189,168000,REMOVING AND REFIXING OF MODERN STAINLESS STEEL BUS SHELTER AT VELACHERY TO TAMBARAM ROAD (JUNCTION OF PADA SALAI STREET GOVT HIGH SCHOOL BUS STOP) IN DIV-190 ZONE-14.,Own Sources,14,2018-19,2019-20 L/2018-19/11506,Electrical,Completed,L-Electrical,189,182700,Work: Provision of 207 mtr 4x16sqmm damaged cable replacement at MGR Salai and Radial road and clamping in center median at MGR Salai and Radial road in div 184&189 Zone-XIV,Own Sources,14,2018-19,2019-20 L/2018-19/16338,Electrical,Completed,L-Electrical,189,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Kamakotti nagar ,GYM Building, Div-189,Pallikaranai, Zone-XIV (E.B.Account no-312-107-661 )",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/10875,Buildings,Completed,NP-PERUNGUDI,189,37500,IMPROVEMENTS WORKS AT THAMARAI KULAM 16th CEREMONY HALL IN DN-189 UNIT-43 ZONE-14,Own Sources,14,2018-19,2019-20 NP/2018-19/10889,Parks,Completed,NP-PERUNGUDI,189,485000,"Improvements works with Electrical Arrangements at VGP Shanthi Nagar Park in Dn-189, Unit-43, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/10901,Parks,Completed,NP-PERUNGUDI,189,75000,"Improvements works at I.I.T Colony Park in Dn-189, Unit-43, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/11578,Buildings,Completed,NP-PERUNGUDI,189,1511000,"Demolition and Re-construction of Amma Unavagam at Tambaram Velachery Main Road in Dn-189,,Unit-43,Zone-14.",Own Sources,14,2018-19,2020-21 NP/2018-19/11734,Roads,Completed,NP-PERUNGUDI,189,179000,"Providing and Laying for Hume Pipe at Labour colony Main Road and Thangam Avenue Various Roads in Dn-189,Unit-43,Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/11736,Roads,Completed,NP-PERUNGUDI,189,179000,"Providing and Laying for Hume Pipe at Sai Balaji Nagar Part-II Various Streets in Dn-189,Unit-43,Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/11967,Buildings,Completed,NP-PERUNGUDI,189,61000,"IMPROVEMENTS WORKS TO AMMA UNAVAGAM IN DN-189,190 AND 191, UNIT-43 ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/14151,Buildings,Completed,NP-PERUNGUDI,189,360000,"Improvements Work For Kamatchiyamman Nagar Aanganwadi Centre in Div-189, Unit-43, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/14214,Parks,Completed,NP-PERUNGUDI,189,425000,"Providing Open Gym at Arumugam Nagar Park in Dn-189, Unit-43, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/14244,Buildings,Completed,NP-PERUNGUDI,189,293000,"PROVIDING WATER SUPPLY AND ELECTRICAL SUPPLY IN E-TOILET AT TAMBARAM TO VELACHERY MAIN ROAD AND TAMBARAM TO VELACHERY MAIN ROAD NEAR 190 DIVISION OFFICE IN DIV - 189 & 190 , UNIT-43, ZONE - 14",Own Sources,14,2018-19,2020-21 NP/2018-19/14779,Roads,Completed,NP-PERUNGUDI,189,48000,"Improvements to Street name board at Various locations in Dn-189,190 and 191 Unit-43, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/15891,Buildings,Completed,NP-PERUNGUDI,189,265000,"Improvement works for IIT Colony Community Hall in Dn-189, Unit-43, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15901,Parks,Completed,NP-PERUNGUDI,189,592000,"MAINTENANCE ESTIMATE FOR PARK AT ASTALAKSHMI AVENUE 1ST STREET IN DIV-189, UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15902,Parks,Completed,NP-PERUNGUDI,189,674000,"MAINTENANCE ESTIMATE FOR PARK AT IIT COLONY 3RD MAIN ROAD PARK IN DIV-189, UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15905,Parks,Completed,NP-PERUNGUDI,189,1150000,"MAINTENANCE ESTIMATE FOR PARK AT KAMAKOTTI NAGAR 1ST STREET IN DIV-189, UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15907,Parks,Completed,NP-PERUNGUDI,189,346000,"MAINTENANCE ESTIMATE FOR HERBAL PARK AT TAMBARAM VELACHERY MAIN ROAD IN DIV-189, UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15910,Parks,Completed,NP-PERUNGUDI,189,598000,"MAINTENANCE ESTIMATE FOR PARK AT VGP SHANTHI NAGAR, ELANGO STREET PARK IN DIV-189, UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15911,Parks,Completed,NP-PERUNGUDI,189,224000,"MAINTENANCE ESTIMATE FOR PARK AT ARUMUGAM NAGAR 3RD STREET IN DIV-189, UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/15913,Parks,Completed,NP-PERUNGUDI,189,1137000,"MAINTENANCE ESTIMATE FOR PARK AT THAMARAI KULAM, VELACHERY TAMBARAM MAIN ROAD IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/16620,Roads,Completed,NP-PERUNGUDI,189,578000,"Attending Patch Work at Various Streets in Div-189, Unit-43, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/2569,Roads,Completed,NP-PERUNGUDI,189,204000,"EXISTING SPEED BREAKER CONVERSION TO IRC STANDARDS AT SELVAM NAGAR MAIN ROAD,VGP SHANTHI NAGAR-SANTHOSH STREET,ASTALAKSHMI NAGAR 1ST STREET,ASTALAKSHMI NAGAR 2ND STREET (4NOS) IN DN-189, UNIT-43, ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/3699,Buildings,Completed,B-Buildings,189,531000,"Repair and improvement to UPHC in Thulukanathamman Koil Street in Dn 189, Unit 43, Zone 14",Own Sources,14,2018-19,2018-19 NP/2018-19/4084,Roads,Completed,NP-PERUNGUDI,189,753000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BETHEL NAGAR IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4087,Roads,Completed,NP-PERUNGUDI,189,377000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BETHEL NAGAR 2ND CROSS STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4089,Roads,Completed,NP-PERUNGUDI,189,377000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BETHEL NAGAR 1ST CROSS STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4091,Roads,Completed,NP-PERUNGUDI,189,377000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BETHEL NAGAR ANEXURE IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4093,Roads,Completed,NP-PERUNGUDI,189,251000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT MEBAL NAGAR IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4095,Roads,Completed,NP-PERUNGUDI,189,251000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT SATHIYA SELAN NAGAR IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4096,Roads,Completed,NP-PERUNGUDI,189,251000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT SATHIYA SELAN NAGRA 1ST STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4097,Roads,Completed,NP-PERUNGUDI,189,847000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BETHAL NAGAR MAIN ROAD IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4099,Roads,Completed,NP-PERUNGUDI,189,1624000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT KARPAGA VINAYAGA NAGAR IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4101,Roads,Completed,NP-PERUNGUDI,189,1289000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT MERU NAGAR IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4102,Roads,Completed,NP-PERUNGUDI,189,706000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT OM SAKTHI NAGAR IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4103,Roads,Completed,NP-PERUNGUDI,189,4849000,"FORMATION AND LAYING OF B.T. ROAD AT KANNADHASAN STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4105,Roads,Completed,NP-PERUNGUDI,189,961000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT VALLAR STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/4106,Roads,Completed,NP-PERUNGUDI,189,1342000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT MARSAL NESAMANI STREET IN DN-189,UNIT-43,ZONE-14",Own Sources,14,2018-19,2019-20 NP/2018-19/6482,Roads,Completed,NP-PERUNGUDI,189,922000,"PROVIDING THERMO PLASTIC PAINTING AT THULUKATHAAMMAN KOIL STREET,KAMAKOTTI NAGAR AND EARIKARI STREET, VIVENKANANDAR STREET AT VARIOUS STREETS IN DN-189 & DN-190, U-43, Z-14.",Own Sources,14,2018-19,2018-19 NP/2018-19/9659,Playfields,Completed,NP-PERUNGUDI,189,931000,"Proposed Construction of compound wall at kamakottinagar 9th street OSR land in Dn-189, Unit-43, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/9672,Playfields,Completed,NP-PERUNGUDI,189,1150000,"Proposed Construction of compound wall at kamakotti nagar 6th street OSR land( south) in Dn-189, Unit-43, Zone-XIV.",Own Sources,14,2018-19,2019-20 NP/2018-19/9676,Playfields,Completed,NP-PERUNGUDI,189,1046000,"Proposed Construction of compound wall at kamakotti nagar 6th street OSR land(north) in Dn-189, Unit-43, Zone-14.",Own Sources,14,2018-19,2019-20 BR/2018-19/5196,Roads,Completed,BR-Bus Route Roads,190,168000,REMOVING AND REFIXING OF MODERN STAINLESS STEEL BUS SHELTER AT VELACHERY TO TAMBARAM ROAD(NEAR BALAJI DENTAL COLLEGE ) IN DIV-190 ZONE-14.,Own Sources,14,2018-19,2019-20 D/2018-19/8528,Storm Water Drain,Completed,D-Storm Water Drains,190,7274000,"Restoration and other improvements to S.Kolathur lake pond for augmentation of water supply in Dn - 190, Zone -14.",SMART CITY - SWD,14,2018-19,2020-21 D/2018-19/8532,Storm Water Drain,Completed,D-Storm Water Drains,190,3090000,"Restoration and other improvements to Chitteri pond lake for augmentation of water supply in Dn - 190, Zone -14.",SMART CITY - SWD,14,2018-19,2020-21 L/2018-19/16325,Electrical,Completed,L-Electrical,190,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Anganwadi, Pallikarnai, Div-190, Zone-XIV.",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/13113,Buildings,Completed,NP-PERUNGUDI,190,1542000,"Renovation to the Existing Store room building at Tambaram-Velachery Main Road to relocate the Amma Unavagam in Dn-190,Unit-43,Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15915,Parks,Completed,NP-PERUNGUDI,190,601000,"MAINTENANCE ESTIMATE FOR PARK AT CHETTINADU HOUSING PARK - I IN DIV-190, UNIT-43,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15917,Parks,Completed,NP-PERUNGUDI,190,568000,"MAINTENANCE ESTIMATE FOR PARK AT CHETTINADU HOUSING PARK - III IN DIV-190, UNIT-43,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15920,Parks,Completed,NP-PERUNGUDI,190,218000,"MAINTENANCE ESTIMATE FOR DR AMBEDKAR PARK AT KANNABIRAN KOIL STREET IN DIV-190, UNIT-43,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15974,Electrical,Completed,NP-PERUNGUDI,190,1123800,"Maintenance work in various parks in division-190 and 191, Unit-43, Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/3996,Roads,Completed,NP-PERUNGUDI,190,1338000,"Restoration of road cut and relaying of B.T. Road at Nehru street in Division-190, Unit-43, Zone-14.",Grants,14,2018-19,2019-20 NP/2018-19/5826,Buildings,Completed,NP-PERUNGUDI,190,772000,"Construction of Damaged Compound wall , Gate pillar, Pathway Repair and Electrical Repair Works at Kovalan Nagar Burial Ground in Dn-190, Unit-43, Zone-14",Own Sources,14,2018-19,2018-19 L/2018-19/10854,Electrical,Completed,L-Electrical,191,86200,"Work : ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Veerathamman Koil street Anganwadi ,Jalladenpet, Div-191, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/10855,Electrical,Completed,L-Electrical,191,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Jayanthi Natarajan street Anganwadi ,Jalladenpet, Div-191, Zone-XIV",Grants,14,2018-19,2019-20 L/2018-19/10856,Electrical,Completed,L-Electrical,191,86200,"Work: ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Tiruvalluvar Nagar 6thstreet Anganwadi ,Jalladenpet, Div-191, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/10857,Electrical,Completed,L-Electrical,191,86200,"Work : ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Ricemill road Amma Unavagam ,Jalladenpet, Div-191, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/10858,Electrical,Completed,L-Electrical,191,236700,"Work : ESTIMATE for Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC Madambakkam, Div-191, Jalladenpet, Zone-XIV (E.B.Account no-313.209.719 )",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/10859,Electrical,Completed,L-Electrical,191,387200,"Work : ESTIMATE for Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Tiruvalluvar Nagar UPHC Jalladenpet, Div-191, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/5330,Electrical,Completed,L-Electrical,191,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at ExServicemen Colony 4th cross street Anganwadi ,Jalladenpet, Div-191, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 L/2018-19/5332,Electrical,Completed,L-Electrical,191,86200,"ESTIMATE for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Pilliyar Koil street Gym ,Jalladenpet, Div-191, Zone-XIV",SMART CITY - ELECTRICAL,14,2018-19,2019-20 NP/2018-19/10835,Buildings,Completed,NP-PERUNGUDI,191,1379000,"Supplying and Fixing for Bio-Shredding Pulverizer Machine, Manure Seiver Machine and Weighing Machine including Civil and Electrical work for Div-188 (2 nos)& Div-191(1 no),Unit-42&43,Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/11096,Buildings,Completed,NP-PERUNGUDI,191,62900,IMPROVEMENTS WORKS AT THIRUVALLUVAR NAGAR 16th DAY CEREMONY HALL IN DN-191 UNIT-43 ZONE-14.,Own Sources,14,2018-19,2019-20 NP/2018-19/13416,Parks,Completed,NP-PERUNGUDI,191,392000,"IMPROVEMENTS TO SELENE ESTATE PARK IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/13458,Parks,Completed,NP-PERUNGUDI,191,86000,"IMPROVEMENTS TO SELENE ESTATE PARK IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/14769,Roads,Completed,NP-PERUNGUDI,191,640000,"Attending Patch Work at Meenatchipuram,VGP Shanthi Nagar,New Colony ,Ashtalakshmi Avenue, Ambal Nagar,citybabu Nagar,Ganabathipuram,Anchaneyar Nagar,Thiruvalluvar Nagar and Variuos Streets in Division-189,190 & 191 ,Unit-43, Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/15503,Buildings,Completed,NP-PERUNGUDI,191,622000,Additional Improvements to Community Hall at Veerathamman Koil Street in Dn-191 Unit-43 Zone-14.,Own Sources,14,2018-19,2020-21 NP/2018-19/15922,Parks,Completed,NP-PERUNGUDI,191,328000,"MAINTENANCE ESTIMATE FOR PARK AT JAYACHANDRAN NAGAR 5TH MAIN ROAD IN DIV-191, UNIT-43,ZONE-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/2922,Buildings,Completed,NP-PERUNGUDI,191,1277000,"Supplying and Fixing for Bio-Shredding Pulverizer Machine, Manure Seiver Machine and Weighing Machine including Civil and Electrical work for Div-186 (2 nos)& Div-189(1 no),Unit-42&43,Zone-14",Own Sources,14,2018-19,2019-20 NP/2018-19/3683,Buildings,Completed,B-Buildings,191,1304000,"Proposed Construction Of Waiting Hall at UPHC for Thiruvalluvar Nagar 6th Street in Dn-191,Unit-43,Zone-14.",Own Sources,14,2018-19,2020-21 NP/2018-19/4085,Roads,Completed,NP-PERUNGUDI,191,1313000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT ANDAL NAGAR MAIN ROAD IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4086,Roads,Completed,NP-PERUNGUDI,191,440000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT ANDAL NAGAR 1ST CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4088,Roads,Completed,NP-PERUNGUDI,191,211000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT ANDAL NAGAR 2ND STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4090,Roads,Completed,NP-PERUNGUDI,191,1553000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BHARATHIYAR STREET EXTN IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4092,Roads,Completed,NP-PERUNGUDI,191,440000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BHARATHIYAR STREET EXTN 1ST CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4094,Roads,Completed,NP-PERUNGUDI,191,440000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BHARATHIYAR STREET EXTN 2ND CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4098,Roads,Completed,NP-PERUNGUDI,191,440000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT BHARATHIYAR STREET EXTN 3RD CROSS STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4100,Roads,Completed,NP-PERUNGUDI,191,2635000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT SEVALIYAR SEVAJI STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/4104,Roads,Completed,NP-PERUNGUDI,191,706000,"STRENGTHENING AND LAYING FOR B.T. ROAD AT MAHAVERAR STREET EXTN STREET IN DN-191,UNIT-43,ZONE-14",Own Sources,14,2018-19,2020-21 NP/2018-19/7314,Roads,Completed,NP-PERUNGUDI,191,485000,"RESTORATION OF TANGENCO ROAD CUT AT VEERATHAMMAN KOIL STREET IN DN-191,UNIT-43,ZONE-14",Deposit Works,14,2018-19,2018-19 NP/2018-19/7319,Roads,Completed,NP-PERUNGUDI,191,2030000,"RESTORATION OF TANGENCO ROAD CUT AT ERIKARAI ROAD IN DN-191,UNIT-43,ZONE-14",Deposit Works,14,2018-19,2019-20 NP/2018-19/7322,Roads,Completed,NP-PERUNGUDI,191,178000,"RESTORATION OF TANGENCO ROAD CUT AT RICEMILL ROAD IN DN-191,UNIT-43,ZONE-14",Deposit Works,14,2018-19,2019-20 NP/2018-19/7323,Roads,Completed,NP-PERUNGUDI,191,1604000,"RESTORATION OF TANGENCO ROAD CUT AT PILLAYAR KOIL STREET IN DN-191,UNIT-43,ZONE-14",Deposit Works,14,2018-19,2018-19 NP/2018-19/7684,Roads,Completed,NP-PERUNGUDI,191,1703000,"Attending Patch Work At Thulukathamman Koil Street,IIT Colony, Kamakotti Nagar,Erikarai Street,Varatharajapuram Main Road,Pillayar Koil Street,Ricemill Road,Veerathamman Koil Street,Sai Ganesh Nagar, and Various Street in Dn-189,190 & Div-191,Unit-43,Zone-14.",Own Sources,14,2018-19,2019-20 NP/2018-19/8831,Parks,Completed,NP-PERUNGUDI,191,1696000,Additional Improvement to Park at Jayachandiran Nagar 1st Main Raod in DN-191 Unit 43 Zone-14,Own Sources,14,2018-19,2018-19 BR/2018-19/5967,Road Cut,Completed,BR-Bus Route Roads,192,269000,"RESTORATION OF OFC ROAD CUT MADE BY RELIANCE JIO AT VARIOUS STREETS IN DIV-192 &200, ZONE-15(57/0667/2017-18)",Deposit Works,15,2018-19,2019-20 L/2018-19/6380,Electrical,Completed,L-Electrical,192,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Hospital neelankari in Div-192 Zone - 15 E.B Account Number : 294.018.1175",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6381,Electrical,Completed,L-Electrical,192,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Library worker estate in Div-192 Zone - 15 E.B Account Number : 294.007.542",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/10822,Roads,Completed,NQ-SHOZHINGANALLUR,192,200000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-192 U-44 ZONE-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/10830,Roads,Completed,NQ-SHOZHINGANALLUR,192,235000,PROVIDING THERMO PLASTIC PAINT AND STUDS FOR SPEED BREAKER AT VARIOUS STREETS IN DIV-192 U-44 ZONE-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11868,Buildings,Completed,NQ-SHOZHINGANALLUR,192,38500,"IMPROVEMENTS WORKS TO RELIEF CENTRE (GOVERNMENT SCHOOL KAPALEESWARAR NAGAR AT NEELANGARAI IN DN-192,U-44,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11912,Parks,Completed,NQ-SHOZHINGANALLUR,192,182500,OUTSOURCING AND MAINTENANCE OF PARK AT WORKER ESTATE PARK IN DN-192 U-44 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/12540,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,1300000,"Construction of Side Drain at Kakkan Street ,Ambethkar Street and Ambethkar st to Thanthai periyar Street (ECR) Neelankarai in Dn-192 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12700,Roads,Completed,NQ-SHOZHINGANALLUR,192,160000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT KAPALEESWARAR NAGAR BEACH MAIN ROAD IN DIV-192 U-44 ZONE-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/13561,Buildings,Completed,NQ-SHOZHINGANALLUR,192,200000,"Improvement to Amma Unavagam including construction of Toilet in Div-192, U-44, Z-15,",Own Sources,15,2018-19,2020-21 NQ/2018-19/13932,Roads,Completed,NQ-SHOZHINGANALLUR,192,11300,REPAIR AND IMPROVEMENT STREET NAME BOARDS AT VARIOUS STREETS IN Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17311,Roads,Completed,NQ-SHOZHINGANALLUR,192,526000,Forming and Laying of BT Road at Kumaraguru Avenue 4th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17315,Roads,Completed,NQ-SHOZHINGANALLUR,192,1244000,Forming and Laying of BT Road at MGR Nagar 1st Main Road in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17317,Roads,Completed,NQ-SHOZHINGANALLUR,192,571000,Forming and Laying of BT Road at MGR Nagar 2nd Main Road in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17318,Roads,Completed,NQ-SHOZHINGANALLUR,192,1146000,Forming and Laying of BT Road at kazura Garden 1st Main Road 8th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17319,Roads,Completed,NQ-SHOZHINGANALLUR,192,489000,Forming and Laying of BT Road at kazura Garden 1st Main Road 9th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17320,Roads,Completed,NQ-SHOZHINGANALLUR,192,904000,Relaying of BT Road at Rajendra nagar 9th to 11 th street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17321,Roads,Completed,NQ-SHOZHINGANALLUR,192,385000,Relaying of BT Road at Annai Murugammal Avenue in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17322,Roads,Completed,NQ-SHOZHINGANALLUR,192,774000,Relaying of BT Road at Seaview Avenue 2nd Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17323,Roads,Completed,NQ-SHOZHINGANALLUR,192,784000,Relaying of BT Road at Seaview Avenue 1st Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17324,Roads,Completed,NQ-SHOZHINGANALLUR,192,641000,Relaying of BT Road at Maraikayar Nagar Ist Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17326,Roads,Completed,NQ-SHOZHINGANALLUR,192,673000,Relaying of BT Road at Maraikayar Nagar 2nd Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17327,Roads,Completed,NQ-SHOZHINGANALLUR,192,523000,Relaying of BT Road at Maraikayar Nagar 3rd Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17328,Roads,Completed,NQ-SHOZHINGANALLUR,192,442000,Relaying of BT Road at Maraikayar Nagar 4th Cross Street in Dn-192 U-44 Z-15.,Own Sources,15,2018-19,2020-21 NQ/2018-19/17329,Roads,Completed,NQ-SHOZHINGANALLUR,192,429000,Relaying of BT Road at Maraikayar Nagar 5th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17331,Roads,Completed,NQ-SHOZHINGANALLUR,192,452000,Relaying of BT Road at Maraikayar Nagar 6th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17333,Roads,Completed,NQ-SHOZHINGANALLUR,192,225000,Relaying of BT Road at Kumaraguru Avenue 3rd Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17334,Roads,Completed,NQ-SHOZHINGANALLUR,192,834000,Relaying of BT Road at Kumaraguru Avenue 5th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17335,Roads,Completed,NQ-SHOZHINGANALLUR,192,403000,Forming and Laying of CC Road at Chinna neelangarai 5 th cross street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17336,Roads,Completed,NQ-SHOZHINGANALLUR,192,303000,Forming and Laying of CC Road at Chinna neelangarai 7 th cross street in Dn-192 U-44 Z-15,"Loans, Grants And Own Sources",15,2018-19,2020-21 NQ/2018-19/17338,Roads,Completed,NQ-SHOZHINGANALLUR,192,333000,Forming and Laying of CC Road at Chinna neelangarai 8 th cross streett in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17339,Roads,Completed,NQ-SHOZHINGANALLUR,192,675000,Forming and Laying of CC Road at Chinna neelangarai 9 th cross street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17340,Roads,Completed,NQ-SHOZHINGANALLUR,192,1874000,Forming and Laying of CC Road at Chinna neelangarai 15 th cross street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17341,Roads,Completed,NQ-SHOZHINGANALLUR,192,698000,Relaying of BT Road at Blue Beach Lane in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17342,Roads,Completed,NQ-SHOZHINGANALLUR,192,445000,Relaying of BT Road at Kumaraguru Avenue 6th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17343,Roads,Completed,NQ-SHOZHINGANALLUR,192,238000,Relaying of BT Road at Kumaraguru Avenue 7th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17344,Roads,Completed,NQ-SHOZHINGANALLUR,192,434000,Relaying of BT Road at Kumaraguru Avenue 8th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17345,Roads,Completed,NQ-SHOZHINGANALLUR,192,237000,Relaying of BT Road at Kumaraguru Avenue 11th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17346,Roads,Completed,NQ-SHOZHINGANALLUR,192,538000,Forming and Laying of CC Road at Singaranvelan 10th cross street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17347,Roads,Completed,NQ-SHOZHINGANALLUR,192,434000,Forming and Laying of CC Road at Singaranvelan 11th cross street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17348,Roads,Completed,NQ-SHOZHINGANALLUR,192,92000,Relaying of BT Road at Kumaraguru Avenue 1st Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17350,Roads,Completed,NQ-SHOZHINGANALLUR,192,390000,Forming and Laying of CC Road at Singaranvelan 12th cross street in Dn-192 U-44 Z-15,"Loans, Grants And Own Sources",15,2018-19,2020-21 NQ/2018-19/17352,Roads,Completed,NQ-SHOZHINGANALLUR,192,682000,Forming and Laying of CC Road at CLRI Nagar 1st cross street in Dn-192 U-44 Z-15,Loans And Grants,15,2018-19,2020-21 NQ/2018-19/17355,Roads,Completed,NQ-SHOZHINGANALLUR,192,385000,Relaying of BT Road at Kumaraguru Avenue Pirathana Salai in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17356,Roads,Completed,NQ-SHOZHINGANALLUR,192,158000,Relaying of BT Road at Kumaraguru Avenue 2nd Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17358,Roads,Completed,NQ-SHOZHINGANALLUR,192,209000,Relaying of BT Road at Kumaraguru Avenue 9th Cross Street in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17359,Roads,Completed,NQ-SHOZHINGANALLUR,192,2426000,Relaying of BT Road at Pandiyan Salai in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17361,Roads,Completed,NQ-SHOZHINGANALLUR,192,1855000,Relaying of BT Road at M.A.Vaithiyalingam salai in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17362,Roads,Completed,NQ-SHOZHINGANALLUR,192,2484000,Relaying of BT Road at Gazura Gardan 2nd Main Road in Dn-192 U-44 Z-15,Grants,15,2018-19,2020-21 NQ/2018-19/17363,Roads,Completed,NQ-SHOZHINGANALLUR,192,1158000,Relaying of BT Road at CLRI Nagar 3rd Main Road in Dn-192 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17428,Roads,Completed,NQ-SHOZHINGANALLUR,192,283000,Relaying of BT Road at Kumaraguru Avenue 10th Cross Street in Dn-192 U-44 Z-15,"Loans, Grants And Own Sources",15,2018-19,2020-21 NQ/2018-19/2886,Roads,Completed,NQ-SHOZHINGANALLUR,192,870000,"PROVIDING NAME BOARDS AT VARIOUS STREETS IN Dn-192, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/3257,Parks,Completed,NQ-SHOZHINGANALLUR,192,94000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT WORKER ESTATE PARK IN DN-192 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/3268,Buildings,Completed,NQ-SHOZHINGANALLUR,192,24000,"IMPROVEMENT WORK FOR AMMA UNAVAGAM IN 192 AT NEELANGARAI in Dn-192 U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/3274,Buildings,Completed,NQ-SHOZHINGANALLUR,192,119000,"Repair and Improvement works to UPHC at Neelangarai in Dn-192 U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/6155,Buildings,Completed,NQ-SHOZHINGANALLUR,192,103000,"IMPROVEMENTS WORKS TO ANGANWADI CENTER NEELANGARAI IN DN-193 U-44,Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/7891,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,411000,"DESILTING OF SWD AND SIDE DRAIN INCLUDING PRECAST SLAB REFIXING WORKS AT VARIOUS STREETS IN DIVISION-192 UNIT-44, ZONE-XV.",Own Sources,15,2018-19,2018-19 NQ/2018-19/8179,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,98500,"Minor Repair works at Kakkan Street to Thanthai Periyar Street (ECR) in Dn-192, U-44, Z-15",Own Sources,15,2018-19,2018-19 B/2018-19/3185,Buildings,Completed,B-Buildings,193,6985000,"SUPPLY, INSTALLATION AND MAINTANANCE AND HOUSE KEEPING OF 58 SEATS OF RENTAL TOILETS FOR A PERIOD OF 1 YEAR IN VARIOUS PLACES ZONE15.",Own Sources,15,2018-19,2019-20 BR/2018-19/17998,Road Cut,Completed,BR-Bus Route Roads,193,996000,"Road Cut Restoration (Road Cut Made By Reliance Jio For Ofc Cable)At Various Streets In Dn 193 and 194, U45, Z-15",Deposit Works,15,2018-19,2019-20 L/2018-19/6341,Electrical,Completed,L-Electrical,193,311900,"Supply, Installation, Testing & Commissioning of 4 Kwp Grid Tied Solar Rooftop including Civil works and earthing at office building,Rajiv Gandhi salai in 193 Div, Zone - 15 .",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6342,Electrical,Completed,L-Electrical,193,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC rajiv gandhi salai in 193 Div, Zone - 15 .",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6353,Electrical,Completed,L-Electrical,193,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma unavagum building ,pandian nagar in 193 Div, Zone - 15",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/10700,Roads,Completed,NQ-SHOZHINGANALLUR,193,131000,PROVIDING THERMO PLASTIC PAINT AND STUDS FOR SPEED BREAKERS AT VARIOUS STREETS IN DIV-193 U-45 ZONE-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/10704,Roads,Completed,NQ-SHOZHINGANALLUR,193,260000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-193 U-45 ZONE-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11055,Buildings,Completed,NQ-SHOZHINGANALLUR,193,125000,Improvements works to Rental toilet in Dn-193 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/11584,Roads,Completed,NQ-SHOZHINGANALLUR,193,1875000,Road Cut Restoration of CC Road at Ananda Nagar Main Road (from Radial Road to Ananda nagar 3rd street) in Dn-193 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/11587,Roads,Completed,NQ-SHOZHINGANALLUR,193,1935000,Road Cut Restoration of CC Road at Ananda Nagar Main Road (from Ananda nagar 3rd street To Egret park (near APL school) ) in Dn-193 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/11633,Electrical,Completed,NQ-SHOZHINGANALLUR,193,396700,Provision of new 9 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 9 Nos of 40-50w watts LED fitting at Sai nagar park in Dn.193 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11635,Electrical,Completed,NQ-SHOZHINGANALLUR,193,189300,Provision of new 4 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 4 Nos of 40-50w watts LED fitting at RE NAGAR park in Dn.193 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11639,Electrical,Completed,NQ-SHOZHINGANALLUR,193,439100,Provision of new 10 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 10Nos of 40-50w watts LED fitting at Customs colony park in Dn.193 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/12093,Parks,Completed,NQ-SHOZHINGANALLUR,193,217000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT RE NAGAR PARK IN DN-193 U-45 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12123,Parks,Completed,NQ-SHOZHINGANALLUR,193,475000,"MAINTENANCE OF PARK PER SIX MONTH(182 DAYS) AT CUSTOMS COLONY PARK IN DIV-193,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12126,Parks,Completed,NQ-SHOZHINGANALLUR,193,345000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT SAI NAGAR PARK IN DN-193 U-45 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12127,Parks,Completed,NQ-SHOZHINGANALLUR,193,368000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182DAYS) AT ANANDHA NAGAR PARK IN DN-193 U-45 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12813,Buildings,Completed,NQ-SHOZHINGANALLUR,193,260500,"Minor Repair works at Various Street in Dn-193, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/14116,Buildings,Completed,NQ-SHOZHINGANALLUR,193,48000,ATTENDING REPAIR WORKS FOR STREET FURNITURES AT VARIOUS STREET IN DN-193 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17304,Roads,Completed,NQ-SHOZHINGANALLUR,193,967000,"FORMING AND LAYING BT ROAD AT SBI COLONY 2ND STREET IN DIV193,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17354,Roads,Completed,NQ-SHOZHINGANALLUR,193,648000,FORMING AND LAYING BT ROAD AT SHANTHI NIKETAN 5TH CROSS STREET IN DIV 193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17357,Roads,Completed,NQ-SHOZHINGANALLUR,193,930000,"Forming and Laying of BT Road at Karpaga Vinayaga Nagar 6th main road in Div-193,U-45,Zone-45",Own Sources,15,2018-19,2020-21 NQ/2018-19/17360,Roads,Completed,NQ-SHOZHINGANALLUR,193,2345000,"Forming and Laying of BT Road at Karpaga Vinayaga Nagar 7th main road in Div-193,U-45,Zone-45",Own Sources,15,2018-19,2020-21 NQ/2018-19/17365,Roads,Completed,NQ-SHOZHINGANALLUR,193,3398000,"Forming and Laying of BT Road at Karpaga Vinayaga Nagar 3rd,4th,5th,6th & 7th cross street in Div-193,U-45,Zone-4",Own Sources,15,2018-19,2020-21 NQ/2018-19/17366,Roads,Completed,NQ-SHOZHINGANALLUR,193,2492000,"Forming and Laying of BT Road at Mahathma Gandhi nagar 2nd main road in Div-193,U-45,Zone-45",Own Sources,15,2018-19,2020-21 NQ/2018-19/17367,Roads,Completed,NQ-SHOZHINGANALLUR,193,4728000,"Forming and Laying of BT Road at Thiruvalluvar Nagar 1,2,3,4 & 5th street in Div-193,U-45,Zone-45",Own Sources,15,2018-19,2020-21 NQ/2018-19/17368,Roads,Completed,NQ-SHOZHINGANALLUR,193,892000,"Forming and Laying of BT Road at Thiruvalluvar nagar 1st main road in Div-193,U-45,Zone-45",Own Sources,15,2018-19,2020-21 NQ/2018-19/17369,Roads,Completed,NQ-SHOZHINGANALLUR,193,1285000,FORMING AND LAYING OF BT ROAD AT GANESH NAGAR 1ST MAIN ROAD IN DIV-193 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17370,Roads,Completed,NQ-SHOZHINGANALLUR,193,1466000,Forming and laying of bt road at MAHATMAGANDHI NAGAR 1ST 2ND 3RD 4TH CROSS STREET in div-193 U-45 z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17371,Roads,Completed,NQ-SHOZHINGANALLUR,193,1111000,Forming and laying of bt road at BALAMURUGAN GARDEN 3RD MAIN ROAD in div193 U44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17372,Roads,Completed,NQ-SHOZHINGANALLUR,193,1128000,Forming and laying of bt road at BALAMURUGAN GARDEN 4TH MAIN ROAD in div-193 u-45 z-15.,Own Sources,15,2018-19,2020-21 NQ/2018-19/17373,Roads,Completed,NQ-SHOZHINGANALLUR,193,521000,BALAMURUGAN GARDEN 6TH CROSS STREET,Own Sources,15,2018-19,2020-21 NQ/2018-19/17375,Roads,Completed,NQ-SHOZHINGANALLUR,193,930000,"FORMING AND LAYING BT ROAD AT VENKATESWARA NAGAR 5TH STREET NORTH IN DIV-193 U-45, Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17376,Roads,Completed,NQ-SHOZHINGANALLUR,193,439000,FORMING AND LAYING BT ROAD VENKATESWARA NAGAR 6TH STREET NORTH IN DIV 193 U 45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17377,Roads,Completed,NQ-SHOZHINGANALLUR,193,662000,FORMING AND LAYING BT ROAD AT VENKATESWARA NAGAR 7TH STREET NORTH IN DIV-193U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17378,Roads,Completed,NQ-SHOZHINGANALLUR,193,2229000,FORMING AND LAYING BT ROAD AT VENKATESWARA NAGAR 9 AND 10TH STREET NORTH IN DIV 193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17379,Roads,Completed,NQ-SHOZHINGANALLUR,193,759000,FORMING AND LAYING BT ROAD AT VENKATESWARA NAGAR 11TH STREET NORTH IN DIV193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17380,Roads,Completed,NQ-SHOZHINGANALLUR,193,534000,FORMING AND LAYING BT ROAD AT VENKATESWARA NAGAR 12TH STREET NORTH IN DIV193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17381,Roads,Completed,NQ-SHOZHINGANALLUR,193,3185000,FORMING AND LAYING BT ROAD AT MCN NAGAR EXTN IN DIV193 U45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17383,Roads,Completed,NQ-SHOZHINGANALLUR,193,885000,"FORMING AND LAYING BT ROAD IN MCN NAGAR 3RD STREET IN DIV193,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17384,Roads,Completed,NQ-SHOZHINGANALLUR,193,899000,"FORMING AND LAYING BT ROAD AT MCN NAGAR 4TH STREET IN DIV-193,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17385,Roads,Completed,NQ-SHOZHINGANALLUR,193,885000,FORMING AND LAYING BT ROAD AT MCN NAGAR 5TH STREET IN DIV 193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17386,Roads,Completed,NQ-SHOZHINGANALLUR,193,1620000,FORMING AND LAYING BT ROAD AT MCN NAGAR 6TH STREET IN DIV193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17387,Roads,Completed,NQ-SHOZHINGANALLUR,193,1369000,FORMING AND LAYING BT ROAD AT MCN NAGAR 7TH STREET IN DIV193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17389,Roads,Completed,NQ-SHOZHINGANALLUR,193,814000,FORMING AND LAYING BT ROAD AT MCN NAGAR 8TH STREET IN DIV193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17390,Roads,Completed,NQ-SHOZHINGANALLUR,193,277000,"FORMING AND LAYING BT ROAD AT MCN NAGAR 9TH STREET IN DIV193,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17391,Roads,Completed,NQ-SHOZHINGANALLUR,193,1798000,"FORMING AND LAYING BT ROAD IN MCN NAGAR 10TH STREET IN DIV193,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17392,Roads,Completed,NQ-SHOZHINGANALLUR,193,800000,"FORMING AND LAYING BT ROAD AT SBI COLONY 1ST STREET IN DIV193, U45, Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17393,Roads,Completed,NQ-SHOZHINGANALLUR,193,398000,FORMING AND LAYING BT ROAD AT ANNA 1ST STREET DIV193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17395,Roads,Completed,NQ-SHOZHINGANALLUR,193,554000,FORMING AND LAYING BT ROAD AT ANNA 2ND STREET IN DIV193 U45 Z15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17396,Roads,Completed,NQ-SHOZHINGANALLUR,193,255000,"FORMING AND LAYING BT ROAD AT ANNA 3RD STREET IN DIV193,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17397,Roads,Completed,NQ-SHOZHINGANALLUR,193,2319000,"FORMING AND LAYING BT ROAD AT PVS NAGAR, RAMALINGAM 2ND AND 3RD STREET IN DIV193 U45 Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17398,Roads,Completed,NQ-SHOZHINGANALLUR,193,826000,MANGALAMBIGAI NAGAR 3RD STREET,Own Sources,15,2018-19,2020-21 NQ/2018-19/17431,Roads,Completed,NQ-SHOZHINGANALLUR,193,6590000,Forming and Laying of BT Road at Industrial Estate all Roads 1st Part in Dn-193 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17432,Roads,Completed,NQ-SHOZHINGANALLUR,193,6590000,Forming and Laying of BT Road at Industrial Estate all Roads 2nd Part in Dn-193 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/3261,Roads,Completed,NQ-SHOZHINGANALLUR,193,380000,"PROVIDING NAME BOARDS AT VARIOUS STREETS IN Dn-193, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/5193,Roads,Completed,NQ-SHOZHINGANALLUR,193,165000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT Pillayar Koil Street IN DIV-193 U-45 ZONE-XV.,Own Sources,15,2018-19,2019-20 NQ/2018-19/7902,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,531000,"DESILTING OF SWD AND SIDE DRAIN INCLUDING PRECAST SLAB REFIXING WORKS AT VARIOUS STREETS IN DIVISION-193 UNIT-45, ZONE-XV.",Own Sources,15,2018-19,2019-20 NQ/2018-19/8005,Buildings,Completed,NQ-SHOZHINGANALLUR,193,453000,"Providing proposed construction of Open gym at Anandha Nagar Park in Dn-193, U-45, Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/9569,Roads,Completed,NQ-SHOZHINGANALLUR,193,275000,"Attending Patch Work at Mahatma Gandhi Nagr In Dn-193,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/9572,Buildings,Completed,NQ-SHOZHINGANALLUR,193,1050000,"IMPROVEMENT WORK TO PARK BY PROVIDING SHUTTLE COURT OPEN GYM AND YOGA MEDAI AT BALAMURUGAN GARDEN PARK IN DN-193, U45, Z15.",Own Sources,15,2018-19,2019-20 BR/2018-19/5563,Roads,Completed,BR-Bus Route Roads,194,1275000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Raji Nagar 3rd Main Road in Dn-194, Zone - XV",Grants,15,2018-19,2019-20 BR/2018-19/5564,Roads,Completed,BR-Bus Route Roads,194,2742000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Kumaran Kudil 1st Main Road in Dn-194, Zone - XV",Grants,15,2018-19,2019-20 BR/2018-19/5565,Roads,Completed,BR-Bus Route Roads,194,903000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Eswaran Koil Street (part) in Dn-194, Zone - XV",Grants,15,2018-19,2019-20 L/2018-19/6343,Electrical,Completed,L-Electrical,194,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at dicision office building ,rajiv Gandhi salai (near ptc bus stop) in 194 Div, Zone - 15",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/11058,Roads,Completed,NQ-SHOZHINGANALLUR,194,1190000,"Attending Patch Work with WMM at Balaji nagar 2nd street,3 rd streeet,4th street, 5th street,6th street, 7th streeet, Bharathiyar nagat 1st streeet, 2nd street,3rd street 5th streeet, VPG Avenue main road and Foundary salai in DN-194 U-45 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11704,Electrical,Completed,NQ-SHOZHINGANALLUR,194,57200,Construction of new plain cement concrete pedestal AND painting for posts damaged due to rusting and soil erosion at various parks in 194 in zone 15,Own Sources,15,2018-19,2019-20 NQ/2018-19/11895,Parks,Completed,NQ-SHOZHINGANALLUR,194,500000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT CHANDRASEKAR AVENUE IN DN-194 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11899,Parks,Completed,NQ-SHOZHINGANALLUR,194,195000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT SAKTHI SRINIVASA ROAD IN DN-194 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11901,Parks,Completed,NQ-SHOZHINGANALLUR,194,185000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT PTC QUARTERS PARK IN DN-194 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11902,Parks,Completed,NQ-SHOZHINGANALLUR,194,765000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT SECRETARIAT COLONY 1ST MAIN ROAD IN DN-194 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11903,Parks,Completed,P-Parks and Playfields,194,1605000,"Plantation Meintenance of Tree Sapling for one Yera at various Places in Dn-194,197,198,199,200,U-44,U-45, Zone-15",Own Sources,15,2018-19,2021-22 NQ/2018-19/13935,Roads,Completed,NQ-SHOZHINGANALLUR,194,99000,PROVIDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS (REPAIR WORK) UNDER EXITISTING SPEED BREAKER AT PILLAIYAR KOIL STREETS IN DIV-194 U-45 ZONE-XV.,Own Sources,15,2018-19,2019-20 NQ/2018-19/14040,Buildings,Completed,NQ-SHOZHINGANALLUR,194,480000,"IMPROVEMENTS WORKS TO AMMA UNAVAGAM AT RAJIVU GANDHI SALAI AND PTC BUS STOP DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16827,Roads,Completed,NQ-SHOZHINGANALLUR,194,3900000,".FORMING AND LAYING OF CEMENT CONCRETE ROAD AT SECRETARIAT COLONY T-ROAD IN DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16829,Roads,Completed,NQ-SHOZHINGANALLUR,194,1380000,".FORMING AND LAYING OF CEMENT CONCRETE ROAD AT MANTHOPPU PILLAIYAR KOIL STREET IN DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16831,Roads,Completed,NQ-SHOZHINGANALLUR,194,1460000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD AT CHINNAPPANAYAKAR STREETIN DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17337,Roads,Completed,NQ-SHOZHINGANALLUR,194,590000,Forming and Laying of Bituminous Road at Balaji nagar 1st street in Dn-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17349,Roads,Completed,NQ-SHOZHINGANALLUR,194,920000,"FORMING AND LAYING BITUMINOUS ROAD AT NINDHINI HOSPITAL ROAD IN DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17353,Roads,Completed,NQ-SHOZHINGANALLUR,194,670000,"FORMING AND LAYING OF BITUMINOUS ROAD AT DEVARAJ NAGAR APPROACH ROAD IN DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17364,Roads,Completed,NQ-SHOZHINGANALLUR,194,2480000,Forming and Laying of Bituminous Road at Devaraj Nagar in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17382,Roads,Completed,NQ-SHOZHINGANALLUR,194,1700000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT SULAIMA NAGAR 2ND STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17388,Roads,Completed,NQ-SHOZHINGANALLUR,194,1670000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT SULAIMA NAGAR 1ST STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17394,Roads,Completed,NQ-SHOZHINGANALLUR,194,1230000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT SULAIMA NAGAR 3RD STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17399,Roads,Completed,NQ-SHOZHINGANALLUR,194,760000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT SULAIMA NAGAR LINK STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17400,Roads,Completed,NQ-SHOZHINGANALLUR,194,1040000,Forming and Laying of Bituminous Road at Balavinayagar avenue main road in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17401,Roads,Completed,NQ-SHOZHINGANALLUR,194,410000,Forming and Laying of Bituminuous Road at Balavinayagar avenue 1st streeet in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17402,Roads,Completed,NQ-SHOZHINGANALLUR,194,860000,"FORMING AND LAYING OF BITUMINOUS ROAD AT BALAVINAYAGAR AVENUE 2ND STREET IN DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17403,Roads,Completed,NQ-SHOZHINGANALLUR,194,3260000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT VPG AVENUE VINAYAGAR KOIL STREET,VPG AVENUE 1 TO 7 STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17404,Roads,Completed,NQ-SHOZHINGANALLUR,194,650000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL 2ND CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17405,Roads,Completed,NQ-SHOZHINGANALLUR,194,1750000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL 3RD CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17406,Roads,Completed,NQ-SHOZHINGANALLUR,194,1370000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL 4TH CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17407,Roads,Completed,NQ-SHOZHINGANALLUR,194,710000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL 5TH CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17408,Roads,Completed,NQ-SHOZHINGANALLUR,194,1100000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL 6TH CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17409,Roads,Completed,NQ-SHOZHINGANALLUR,194,1880000,Forming and Laying of Bituminuous Road at Rajiv garden 1st main road in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17410,Roads,Completed,NQ-SHOZHINGANALLUR,194,1440000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL ANEX MAIN ROAD IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17412,Roads,Completed,NQ-SHOZHINGANALLUR,194,1970000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL ANEX 2ND CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17413,Roads,Completed,NQ-SHOZHINGANALLUR,194,329000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL ANEX 3RD CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17414,Roads,Completed,NQ-SHOZHINGANALLUR,194,369000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL ANEX 4TH CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17415,Roads,Completed,NQ-SHOZHINGANALLUR,194,420000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL ANEX 5TH CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17416,Roads,Completed,NQ-SHOZHINGANALLUR,194,390000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL ANEX 6TH CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17417,Roads,Completed,NQ-SHOZHINGANALLUR,194,750000,Forming and Laying of Bituminuous Road at Mount pattern 1st cross street in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17418,Roads,Completed,NQ-SHOZHINGANALLUR,194,1380000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION ATAZHIGANDEESWARAR NAGAR EXTN IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17419,Roads,Completed,NQ-SHOZHINGANALLUR,194,1080000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION ATAZHIGANDEESWARAR NAGAR MAIN ROAD IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17420,Roads,Completed,NQ-SHOZHINGANALLUR,194,2680000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT ESWARAN KOIL STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17421,Roads,Completed,NQ-SHOZHINGANALLUR,194,900000,Forming and Laying of Bituminuous Road at Rajiv garden 1st streeet in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17422,Roads,Completed,NQ-SHOZHINGANALLUR,194,1900000,Forming and Laying of Bituminous Road at Rajiv garden 2nd main road in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17423,Roads,Completed,NQ-SHOZHINGANALLUR,194,630000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT GANDHI STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17424,Roads,Completed,NQ-SHOZHINGANALLUR,194,630000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT MGR STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17425,Roads,Completed,NQ-SHOZHINGANALLUR,194,400000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT AZHIGANDEESWARAR NAGAR 2ND STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17426,Roads,Completed,NQ-SHOZHINGANALLUR,194,280000,Forming and Laying Bituminous Road at Sulaima nagar 1st cross street in DN-194 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/17427,Roads,Completed,NQ-SHOZHINGANALLUR,194,1790000,"FORMING AND LAYING OF CEMENT CONCRETE ROAD AT BHARATHIYAR STREET IN DN-194,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/3234,Buildings,Completed,NQ-SHOZHINGANALLUR,194,570000,Providing Name Board at Various Streets in Dn-194 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/3294,Roads,Completed,NQ-SHOZHINGANALLUR,194,218000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT ARIHANTH ROAD IN DIV-194 U-45 ZONE-XV.,Own Sources,15,2018-19,2019-20 NQ/2018-19/7159,Parks,Completed,NQ-SHOZHINGANALLUR,194,50000,Providing PVC Coated weld mesh fencing at kumaran kudiil park pond in Dn 194 U-45 Z-15,Own Sources,15,2018-19,2018-19 NQ/2018-19/7876,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,382000,DESILTING OF STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DIVISION-194 UNIT-45 ZONE-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/8451,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,34500,Minor repair work at various street in Dn194 U-45 Z-15,Own Sources,15,2018-19,2019-20 B/2018-19/4226,Buildings,Completed,B-Buildings,195,6349864,"Supply, Installation, testing and Commissioning of Fire fighting system and Medical Gas System maintenance for 1 year in Community Health Center(30 Beds) at Kannagi Nagar 2nd Main road in Div 195 zone 15",Grants,15,2018-19,2020-21 BR/2018-19/18009,Road Cut,Completed,BR-Bus Route Roads,195,1029000,"ROAD CUT RESTORATION (ROAD CUT MADE BY RELIANCE JIO FOR OFC CABLE)AT VARIOUS STREETS IN U45, Z-15",Deposit Works,15,2018-19,2019-20 L/2018-19/6344,Electrical,Completed,L-Electrical,195,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at dicision office buildinSupplyg ,kannagi nagar 8th main road in 195 Div, Zone",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6348,Electrical,Completed,L-Electrical,195,86200,"Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at gym buiding ,kannagi nagar 2nd main road in 195 Div, Zone - 15",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6351,Electrical,Completed,L-Electrical,195,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC kannagi nagar 1st main road in 195 Div, Zone - 15",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6352,Electrical,Completed,L-Electrical,195,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at UPHC ETRP apparch road , Ezhil nagar in 195 Div, Zone - 15",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6354,Electrical,Completed,L-Electrical,195,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Amma unavagum building,kannagi nagar in 195 Div, Zone - 15 .",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/10376,Buildings,Completed,NQ-SHOZHINGANALLUR,195,488000,"Providing Bio- Shredding Pulverizer Machine, Manure Seiver Machine And Weighing Machine Including Civil And Electrical Work in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/10851,Buildings,Completed,NQ-SHOZHINGANALLUR,195,48000,"Improvement works to Burial Ground (Muslim) Compound Wall at Kannagi Nagar 17th Main Road in Dn-195,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11645,Electrical,Completed,NQ-SHOZHINGANALLUR,195,932700,"Provision of new 18 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 18 Nos of 40-50w watts LED fitting at Kannagi nagar 10th cross road park ,kannagi nagar 9th main road park ,kannagi nagar 7th cross streetpark and kannagi nagar 2nd cross street park in Dn.195 in Zone-XV",Own Sources,15,2018-19,2019-20 NQ/2018-19/11652,Electrical,Completed,NQ-SHOZHINGANALLUR,195,403200,Provision of new 9 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 9 Nos of 40-50w watts LED fitting at annai indira nagar park in Dn.195 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11914,Parks,Completed,NQ-SHOZHINGANALLUR,195,486000,MAINTENANCE OF PARK FOR 6 MONTHS AT ANNAI INDIRA NAGAR IN DN-195 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/11918,Parks,Completed,NQ-SHOZHINGANALLUR,195,131000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT KANNAGI NAGAR 9th MAIN ROAD Dn-195 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11919,Parks,Completed,NQ-SHOZHINGANALLUR,195,190000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT KANNAGI NAGAR 10TH CROSS ROAD (3 ADUKU) IN DN-195 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11920,Parks,Completed,NQ-SHOZHINGANALLUR,195,212000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT KANNGI NAGAR 2ND CROSS ROAD (3 ADUKU) IN DN-195 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11923,Parks,Completed,NQ-SHOZHINGANALLUR,195,211000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT KANNAGI NAGAR 7TH CROSS ROAD IN DN-195 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12141,Buildings,Completed,NQ-SHOZHINGANALLUR,195,160000,REPAIR WORKS TO AMMA UNAVAGAM KANNAGI NAGAR 2ND MAIN ROAD IN DIV 195 U-45 Z-15.,Own Sources,15,2018-19,2019-20 NQ/2018-19/3541,Roads,Completed,NQ-SHOZHINGANALLUR,195,2346000,"FORMING OF CC ROAD AT EZHIL NAGAR IN BETWEEN BLOCKS (29&28),(11&12) AND (12&13) AND EZHIL NAGAR IN FRONT OF BLOCKS (12),(28) PATH IN DN-195 U-45 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/3703,Roads,Completed,NQ-SHOZHINGANALLUR,195,4479000,"RELAYING OF BT ROAD AT KANNAGI NAGAR 2 ADUKKU 33RD,35TH,57TH,60TH,61TH,62TH,63RD,64TH CROSS STREET AND 7TH MAIN ROAD IN DN-195,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/3801,Parks,Completed,NQ-SHOZHINGANALLUR,195,1092000,"Construction of Park compound wall at Thiruvalluvar Street in DN-195,U-45,Z-15",Own Sources,15,2018-19,2021-22 NQ/2018-19/3822,Roads,Completed,NQ-SHOZHINGANALLUR,195,182000,ATTENDING REPAIR WORKS FOR STREET FURNITURES AT VARIOUS STREET IN DIVISION-195 U-45 Z-15.,Own Sources,15,2018-19,2018-19 NQ/2018-19/3823,Roads,Completed,NQ-SHOZHINGANALLUR,195,385000,PROVIDING STREET FURNITURES AT VARIOUS STREET IN DIVISION-195 U-45 Z-15.,Own Sources,15,2018-19,2019-20 NQ/2018-19/5291,Roads,Completed,NQ-SHOZHINGANALLUR,195,824000,"PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT THIRUVALLUVAR STREET, MRG NAGAR, NETHAJI STREET, PILLAYAR KOIL STREET IN DIV-195 U-45 ZONE-XV.",Own Sources,15,2018-19,2019-20 NQ/2018-19/5292,Buildings,Completed,NQ-SHOZHINGANALLUR,195,481000,"Repair and Improvement works to UPHC at Kannagi Nagar in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/5374,Buildings,Completed,NQ-SHOZHINGANALLUR,195,288000,"IMPROVEMENTS WORKS TO ANGANWADI CENTRE (13 & 14) AT KANNAGI NAGAR IN DN-195, U-45,Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/5597,Roads,Completed,NQ-SHOZHINGANALLUR,195,2367000,"FORMING OF CC ROAD AT EZHIL NAGAR IN BETWEEN BLOCKS (17&16),(17&18) AND (27&28) AND EZHIL NAGAR IN FRONT OF BLOCKS (17) PATH IN DN-195 U-45 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/6004,Roads,Completed,NQ-SHOZHINGANALLUR,195,2429000,"FORMING OF CC ROAD AT SANTHOME LANE,EZHIL NAGAR IN BETWEEN BLOCKS (35&36) AND (37&36) AND EZHIL NAGAR IN FRONT OF BLOCKS 36 PATH IN DN-195 U-45 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/7633,Buildings,Completed,NQ-SHOZHINGANALLUR,195,51000,Repair works of shredding machine in Dn-195 U-45 Z-15,Own Sources,15,2018-19,2018-19 NQ/2018-19/7905,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,938500,"Minor Repair Work at Various street in Dn195, U-45 , Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/8166,Road Cut,Completed,NQ-SHOZHINGANALLUR,195,2750000,"Road Cut Restoration of BT Road at Pillayar Koil Street, Kannagi Nagar Link Road, 13th Main Road, 68th Cross Street, 11th Main Road, 17th Main Road in Dn-195 U-45 Z-15",Deposit Works,15,2018-19,2019-20 NQ/2018-19/8173,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,382000,Desilting Of Side Drain in Div-195 U-45 Z--15,Own Sources,15,2018-19,2018-19 NQ/2018-19/8828,Parks,Completed,NQ-SHOZHINGANALLUR,195,173000,IMRPOVEMENTS WORKS TO CHILDREN PLAY SPACE AT KANNAGI NAGAR 3RD CROSS STREET IN DN-195 U-45 Z-15,Own Sources,15,2018-19,2021-22 NQ/2018-19/8832,Parks,Completed,NQ-SHOZHINGANALLUR,195,162000,IMRPOVEMENTS WORKS TO CHILDREN PLAY SPACE AT KANNAGI NAGAR 5TH CROSS STREET IN DN-195 U-45 Z-15,Own Sources,15,2018-19,2021-22 NQ/2018-19/8833,Parks,Completed,NQ-SHOZHINGANALLUR,195,178000,IMRPOVEMENTS WORKS TO CHILDREN PLAY SPACE AT KANNAGI NAGAR 10TH CROSS STREET IN DN-195 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/8834,Parks,Completed,NQ-SHOZHINGANALLUR,195,158000,IMRPOVEMENTS WORKS TO CHILDREN PLAY SPACE AT KANNAGI NAGAR 13TH CROSS STREET IN DN-195 U-45 Z-15,Own Sources,15,2018-19,2021-22 NQ/2018-19/8836,Parks,Completed,NQ-SHOZHINGANALLUR,195,175000,"Improvements works to Children Play Space At Kannagi Nagar 14th Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8837,Parks,Completed,NQ-SHOZHINGANALLUR,195,173000,"Improvements works to Children Play Space At Kannagi Nagar 16th Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2021-22 NQ/2018-19/8838,Parks,Completed,NQ-SHOZHINGANALLUR,195,159000,"Improvements works to Children Play Space At Kannagi Nagar 21st Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8839,Parks,Completed,NQ-SHOZHINGANALLUR,195,159000,"Improvements works to Children Play Space At Kannagi Nagar 27th Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2021-22 NQ/2018-19/8840,Parks,Completed,NQ-SHOZHINGANALLUR,195,137000,"Name of work: Improvements works to Children Play Space At Kannagi Nagar 32nd Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8841,Parks,Completed,NQ-SHOZHINGANALLUR,195,154000,"Improvements works to Children Play Space At Kannagi Nagar 35th Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2021-22 NQ/2018-19/8842,Parks,Completed,NQ-SHOZHINGANALLUR,195,152000,"Improvements works to Children Play Space At Kannagi Nagar 39th Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8843,Parks,Completed,NQ-SHOZHINGANALLUR,195,186000,"Improvements works to Children Play Space At Kannagi Nagar 56th Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8844,Parks,Completed,NQ-SHOZHINGANALLUR,195,154000,"Improvements works to Children Play Space At Kannagi Nagar 63th Cross street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/9021,Buildings,Completed,NQ-SHOZHINGANALLUR,195,112000,"Improvements To Health Sub Center(HSC) at Kannagi Nagar 62nd Cross Street in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/9688,Parks,Completed,NQ-SHOZHINGANALLUR,195,78000,"Improvement works to Anganwadi (17&18) Centre at Kannagi Nagar 6th Main Road in Dn-195, U-45, Z-15",Own Sources,15,2018-19,2019-20 L/2018-19/6371,Electrical,Completed,L-Electrical,196,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Crematorium, Enjambakkam in Div-196 Zone - 15 E.B Account Number : 218.007.1350",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6373,Electrical,Completed,L-Electrical,196,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office in Div-196 Zone - 15 E.B Account Number : 218.007.304",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6382,Electrical,Completed,L-Electrical,196,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Night Shelter at nanjundarao salai in Div-196 Zone - 15 E.B Account Number : 218.007.844",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6384,Electrical,Completed,L-Electrical,196,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Unit office in Div-196 Zone - 15 E.B Account Number : 218.007.1188",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/0581,Roads,Completed,NQ-SHOZHINGANALLUR,196,760000,"FORMING AND LAYING FOR B.T ROAD AT CLASSIC FORM 1ST STREET IN DIV-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/10673,Parks,Completed,NQ-SHOZHINGANALLUR,196,108000,"Improvements to park at V.G.P. layout Rajarathinam Avenue in Division-196, Unit-44, Zone-15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/10826,Buildings,Completed,NQ-SHOZHINGANALLUR,196,89000,"Improvements to Night Shelter at Dr. Nanjundarao Road in Division.196, Unit-44, Zone-15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/11614,Electrical,Completed,NQ-SHOZHINGANALLUR,196,447200,Provision of new 9 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 11Nos of 40-50w watts LED fitting at VGP layout park enjambakkam in Dn.196 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11774,Buildings,Completed,NQ-SHOZHINGANALLUR,196,52000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO TSUNAMI BUILDING (RELIEF CENTRE ) AT DR.NANJUNDARAO ROAD I IN DN-196,U-44,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11888,Parks,Completed,NQ-SHOZHINGANALLUR,196,389000,":OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT VGP LAYOUTS 2ND STREET IN DN-196 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/13168,Buildings,Completed,NQ-SHOZHINGANALLUR,196,180000,"Improvements for Fish Market at Dr.Nanjunda Rao Salai in Dn-196,Unit-44,Zone-14",Own Sources,15,2018-19,2019-20 NQ/2018-19/13395,Buildings,Completed,NQ-SHOZHINGANALLUR,196,230000,"Improvements for unit-44 office at V.O.C Street in DN-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/14178,Buildings,Completed,NQ-SHOZHINGANALLUR,196,1041000,"Construction of Temporary Shed for Amma Unavagam in Anna Enclave OSR land at Anna Enclave in Dn-196, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16757,Roads,Completed,NQ-SHOZHINGANALLUR,196,347000,"FORMING AND LAYING FOR B.T ROAD AT HANUMAN COLONY 3RD STREET IN DIV-196,UNIT-44,ZONE-15","Loans, Grants And Own Sources",15,2018-19,2020-21 NQ/2018-19/16758,Roads,Completed,NQ-SHOZHINGANALLUR,196,453000,"FORMING AND LAYING FOR B.T ROAD AT HANUMAN COLONY 5TH STREET IN DIV-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16799,Roads,Completed,NQ-SHOZHINGANALLUR,196,564000,"FORMING AND LAYING FOR B.T ROAD AT THIRUVALLUVAR 2ND STREET IN DIV-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16800,Roads,Completed,NQ-SHOZHINGANALLUR,196,936000,"FORMING AND LAYING FOR B.T ROAD AT PALLAVAN NAGAR MAIN ROAD IN DIV-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16801,Roads,Completed,NQ-SHOZHINGANALLUR,196,458000,"FORMING AND LAYING FOR B.T ROAD AT PALLAVAN NAGAR 1ST CROSS STREET IN DIV-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16802,Roads,Completed,NQ-SHOZHINGANALLUR,196,296000,"FORMING AND LAYING FOR B.T ROAD AT PALLAVAN NAGAR 2ND CROSS STREET IN DIV-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16813,Roads,Completed,NQ-SHOZHINGANALLUR,196,855000,"Forming and laying for C.C Road at charan street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/16814,Roads,Completed,NQ-SHOZHINGANALLUR,196,686000,"Forming and laying for C.C Road at Hanuman colony 1st street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16815,Roads,Completed,NQ-SHOZHINGANALLUR,196,1561000,"Forming and laying for C.C Road at Cholamandala devi Nagar 1st street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16816,Roads,Completed,NQ-SHOZHINGANALLUR,196,2919000,"Forming and laying for C.C Road at Cholamandala devi Nagar 3rd street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16817,Roads,Completed,NQ-SHOZHINGANALLUR,196,910000,"Forming and laying for C.C Road at Cholamandala devi Nagar 4th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16818,Roads,Completed,NQ-SHOZHINGANALLUR,196,994000,"Forming and laying for C.C Road at Cholamandala devi Nagar 5th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16819,Roads,Completed,NQ-SHOZHINGANALLUR,196,859000,"Forming and laying for C.C Road at Cholamandala devi Nagar 6th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16820,Roads,Completed,NQ-SHOZHINGANALLUR,196,2120000,"Forming and laying for C.C Road at Cholamandala devi Nagar 6th street 1st cross street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16821,Roads,Completed,NQ-SHOZHINGANALLUR,196,1765000,"Forming and laying for C.C Road at Cholamandala devi Nagar 7th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16822,Roads,Completed,NQ-SHOZHINGANALLUR,196,439000,"Forming and laying for C.C Road at Cholamandala devi Nagar 8th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16823,Roads,Completed,NQ-SHOZHINGANALLUR,196,2008000,"Forming and laying for C.C Road at Cholamandala devi Nagar 9th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16824,Roads,Completed,NQ-SHOZHINGANALLUR,196,610000,"Forming and laying for C.C Road at Cholamandala devi Nagar 10th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16825,Roads,Completed,NQ-SHOZHINGANALLUR,196,649000,"Forming and laying for C.C Road at Cholamandala devi Nagar 11th street in div-196,unit-44,zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/17314,Roads,Completed,NQ-SHOZHINGANALLUR,196,934000,"FORMING AND LAYING FOR B.T ROAD AT CLASSIC FORM 2ND STREET IN DIV-196,UNIT-44,ZONE-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/2462,Buildings,Completed,NQ-SHOZHINGANALLUR,196,2510000,"Name of work: Construction of compound wall at M.K.Radha Avenue OSR @ Injambakkam in Dn-196, U-44, Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/3317,Parks,Completed,NQ-SHOZHINGANALLUR,196,109000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT VGP LAYOUTS 2ND STREET IN DN-196 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/3431,Roads,Completed,NQ-SHOZHINGANALLUR,196,350000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT IST AVENUE MAIN ROAD AND BAY WATCH FARM IN DIV-196 U-44 ZONE-XV.,Own Sources,15,2018-19,2018-19 NQ/2018-19/3686,Roads,Completed,NQ-SHOZHINGANALLUR,196,220000,"PROVIDING NAME BOARDS AT VARIOUS STREETS IN Dn-196, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/4082,Roads,Completed,NQ-SHOZHINGANALLUR,196,54000,"PROVIDING AND FIXING FRC BENCHES AT VETTUVANKENI BEACH IN Dn-196,U - 44, Z - 15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/4787,Buildings,Completed,NQ-SHOZHINGANALLUR,196,177000,"IMPROVEMENTS TO ANGANWADI AT VETTUVANKENI, EAST COAST ROAD IN DN-196, U-44, Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/4858,Roads,Completed,NQ-SHOZHINGANALLUR,196,499000,"ATTENDING PATCH WORK WITH,WMM AT 2ND AVENUE 3RD CROSS STREET AND SHALIMAR GARDEN 1ST CROSS STREET IN Dn - 196 , U - 44 , Z- 15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/5363,Buildings,Completed,NQ-SHOZHINGANALLUR,196,89000,"Improvements Works to Amma Unavagam at VOC Street in Dn-196 , U - 44, Z - 15",Own Sources,15,2018-19,2019-20 NQ/2018-19/7639,Buildings,Completed,NQ-SHOZHINGANALLUR,196,42000,"Repair works of Shredding machine in Dn-196, U-44 , Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/7830,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,196,303000,Desilting Of Swd And Side Drain Including Precast Slab Refixing Works At Various Streets In Division-196 Unit-44 Zone-XV,Own Sources,15,2018-19,2018-19 NQ/2018-19/7974,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,196,100500,"Repair to Storm water drain at Dn.196, Zone 15",Own Sources,15,2018-19,2018-19 NQ/2018-19/8743,Buildings,Completed,NQ-SHOZHINGANALLUR,196,348000,"IMPROVEMENT WORK FOR PRIME TOILET AT CHINNADI KUPPAM PALLATH THERU & CHINNADI KUPPAM METTU THERU IN DN-196, U-44, Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/9118,Buildings,Completed,NQ-SHOZHINGANALLUR,196,368000,"Improvements to Sub Health Centre at V. O. C. Street, Injambakkam in Division-196, Unit-44, Zone-15.",Own Sources,15,2018-19,2019-20 B/2018-19/0196,Buildings,Completed,B-Buildings,197,24316851,"CONSTRUCTION OF URBAN PRIMARY HEALTH CENTER (G+2F) AT THORAIPPAKKAM IN DIV- 193, ZONE- 15",Grants,15,2018-19,2020-21 BR/2018-19/18011,Road Cut,Completed,BR-Bus Route Roads,197,354000,"ROAD CUT RESTORATION (ROAD CUT MADE BY RELIANCE JIO FOR OFC CABLE)AT VARIOUS STREETS IN DN 197, U45, Z-15",Deposit Works,15,2018-19,2019-20 D/2018-19/8453,Storm Water Drain,Completed,D-Storm Water Drains,197,2176000,Restoration and other improvements to Chinnakeni kulam street pond in Dn-197 Zone-15.,SMART CITY - SWD,15,2018-19,2020-21 L/2018-19/6331,Electrical,Completed,L-Electrical,197,763400,"Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Hall building at Aringar Anna street in Div-197 in Zone -XV.EB Account number 297.001.3471",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6332,Electrical,Completed,L-Electrical,197,236700,"Supply, Installation, Testing & Commissioning of 3 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office building at Gangai Amman koil street in Div-197 in Zone -XV.EB Account Number-297.001.227",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6333,Electrical,Completed,L-Electrical,197,763400,"Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Hall building at Rajiv Gandhi salai in Div-197 in Zone -XV.EB Account number 280.005.1898",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6338,Electrical,Completed,L-Electrical,197,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Lorry Station building at Modern School Road in Div-197 in Zone -XV.EB Account number 280.005.1958",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6340,Electrical,Completed,L-Electrical,197,763400,"Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Zonal Office building at Rajiv Gandhi Salai in Div-197 in Zone -XV.EB Account number 327.003.1151",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/10508,Buildings,Completed,NQ-SHOZHINGANALLUR,197,457000,"Providing Bio- Shredding Pulverizer Machine, Manure Seiver Machine And Weighing Machine Including Civil And Electrical Work in Dn-197, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/10621,Roads,Completed,NQ-SHOZHINGANALLUR,197,160000,Attending patch work at various street in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/10839,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,1670000,Restoration of Road Cut at Village High Road (from Lalbhagadur Sastri Street to Anna Street) in Dn-197 U-45 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/11602,Electrical,Completed,NQ-SHOZHINGANALLUR,197,629700,Provision of 14 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 14 Nos of 40-50w watts LED fitting at Kumarasamy Nagar park in Dn.197 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11611,Electrical,Completed,NQ-SHOZHINGANALLUR,197,575800,Provision of 10 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 10 Nos of 40-50w watts LED fitting at Lancer west Park in Dn.197 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11817,Buildings,Completed,NQ-SHOZHINGANALLUR,197,62000,Improvements works to Govt Higher Secondary School at Rajiv Gandhi Salai in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/11871,Parks,Completed,NQ-SHOZHINGANALLUR,197,420000,"OUTSOURCING AND MAINTENANCE OF PARK PER SIX MONTH AT NEW KUMARAN NAGAR 2ND MAIN ROAD IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11872,Parks,Completed,NQ-SHOZHINGANALLUR,197,310000,"OUTSORCING AND MAINTENANCE OF PARK PER SIX MONTH AT KUMARASAMY NAGAR 6TH STREET IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11873,Parks,Completed,NQ-SHOZHINGANALLUR,197,169000,"OUTSORCING AND MAINTENANCE OF PARK PER SIX MONTH AT KUMARASAMY NAGAR MAIN ROAD (NORTH) IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11874,Parks,Completed,NQ-SHOZHINGANALLUR,197,106500,"OUTSOURCING OF MAINTENANCE OF PARK SIX MONTH AT KUMARASAMY NAGAR MAIN ROAD WEST IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11875,Parks,Completed,NQ-SHOZHINGANALLUR,197,340000,"OUTSORCING AND MAINTENANCE OF PARK SIX MONTH AT RAJIV GANDHI SALAI (TECHI PARK) IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11876,Parks,Completed,NQ-SHOZHINGANALLUR,197,190000,"OUTSOURCING AND MAINTENANCE OF PARK PERSIX MONTH AT ELCOT AVENUE 1ST STREET IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11877,Parks,Completed,NQ-SHOZHINGANALLUR,197,190000,"OUTSOURCING AND MAINTENANCE OF PARK PER SIX MONTH AT NEDUNCHELIYAN STREET IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11878,Parks,Completed,NQ-SHOZHINGANALLUR,197,380000,"OUTSOURCING AND MAINTENANCE OF PARK PER SIX MONTH AT DEVARAJ NAGAR 2ND MAIN ROAD IN DN-197 ,U-45,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12130,Buildings,Completed,NQ-SHOZHINGANALLUR,197,32600,"Improvements works to Amma Unavagam at Kaliamman koil Street in Dn-197, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12131,Footpath,Completed,NQ-SHOZHINGANALLUR,197,2590000,"Providing Footpath at Prithingira devi koil street in Dn-197, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/13486,Buildings,Completed,NQ-SHOZHINGANALLUR,197,680000,"Improvements works to Amma Unavagam at Neduncheliyan street & Kaliamman koil Street in Dn-197, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/13524,Buildings,Completed,NQ-SHOZHINGANALLUR,197,600000,"Improvements works to Zonal Office Building at Rajiv Gandhi Salai in Dn-197, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/13643,Roads,Completed,NQ-SHOZHINGANALLUR,197,37000,ATTENDING REPAIR WORKS FOR STREET FURNITURES AT VARIOUS STREET IN DN-197 U-45 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/14240,Roads,Completed,NQ-SHOZHINGANALLUR,197,515000,Proposed Construction of open Gym at New Kumaran Nagar 2nd Main Road Park (17.00 m x 2.35 m = 39.95) m2 in div -197 u-45 zone -15,Own Sources,15,2018-19,2019-20 NQ/2018-19/14248,Buildings,Completed,NQ-SHOZHINGANALLUR,197,2800000,"Construction of compound wall for Inside of Burial ground at Kuppusamy street (South Side) in Dn-197, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/14249,Buildings,Completed,NQ-SHOZHINGANALLUR,197,244000,Improvements Works to Community Hall at Anna Street in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/14253,Buildings,Completed,NQ-SHOZHINGANALLUR,197,505000,"Improvements Works to 16th Ceramony Hall at Mahatmagandi Street in Dn-197, U-45, Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/14267,Parks,Completed,NQ-SHOZHINGANALLUR,197,153000,Providing Play Material for Kumarasamy Nagar Main Road North West park in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/14764,Parks,Completed,NQ-SHOZHINGANALLUR,197,2490000,"OUTSOURCING OF PARK MAINTENANCE FOR WATER LORRY FOR 9 MONTHS (270 DAYS) AT ANANTHA NAGAR,RE NAGAR,CUSTOMS COLONY,SECRETARIATE COLONY,KUMARASAMY NAGAR 6TH STREET,KUMARASAMY NAGAR MAIN ROAD (NORTH),RAJIV GANDHI SALAI (TECHI PARK),NEW KUMARAN NAGAR 2ND MAIN ROAD,RAJIV GANDHI SALAI (DOLLER PARK) IN DN-193,194,197 U-45 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/14802,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,618000,"Construction of Culvert (Size 1200X1200 mm) at New Kumaran Nagar School Road Junction in Dn.197, Zone 15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/15045,Electrical,Completed,NQ-SHOZHINGANALLUR,197,32000,Proposed to Painting of 567 nos of 2mtr with one mtr single curved bracket in parks in Dn.192 to 200 in Zone-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/15848,Electrical,Completed,NQ-SHOZHINGANALLUR,197,609800,"Proposed to Replace and Purchase of 8 Nos of Ceiling Fan, 5 Nos of Exhaust Fan,3 nos of Water Heater,4 nos of Wall Mounting fan,4 Nos of Pulvarizer, 5 nos of Mixer Grinder and 3 Nos of Weighing Machine at Amma Unavagam in Dn-192 to 200 in Zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/17305,Roads,Completed,NQ-SHOZHINGANALLUR,197,7452000,"Forming and Laying of CC Road at Rajiv Gandhi Salai 1st Street and Printhingiradevi Street in Dn-197 U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/17308,Roads,Completed,NQ-SHOZHINGANALLUR,197,1180000,"Forming and Laying of CC Road at New kumaran nagar 17th cross street, Rajiv Gandhi Salai 1st cross Street and Kalaimagal Nagar 1st Street in Dn-197 U-45 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17309,Roads,Completed,NQ-SHOZHINGANALLUR,197,4352000,"FORMING AND LAYING OF BT ROAD AT MUTHAMIL NAGAR 1 TO 7TH STREET, NEW KUMARAN NAGAR 11TH CROSS STREET, NEW KUMARAN NAGAR 1ST CROSS STREET AND NATESAN AVENUE IN DN-197,U-45,Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17429,Roads,Completed,NQ-SHOZHINGANALLUR,197,5480000,Forming and Laying of CC Road at Wipro Salai (From Wipro Gate to 250 Mtr) Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/17430,Roads,Completed,NQ-SHOZHINGANALLUR,197,5480000,Forming and Laying of CC Road at Wipro Salai (From ASV Building to 250 Mtr) in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/3682,Roads,Completed,NQ-SHOZHINGANALLUR,197,2050000,PROVIDING NAME BOARDS AT VARIOUS STREETS IN Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/4186,Buildings,Completed,NQ-SHOZHINGANALLUR,197,580000,Improvement works to Compost Yard at Kuppusamy Street in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/4459,Roads,Completed,NQ-SHOZHINGANALLUR,197,108000,ATTENDING REPAIR WORKS FOR STREET FURNITURES AT VARIOUS STREET IN DN-197 U-45 Z-15,Own Sources,15,2018-19,2018-19 NQ/2018-19/5988,Roads,Completed,NQ-SHOZHINGANALLUR,197,1400000,Providing and Laying of Interlocking Blocks Road for Inside of Shopping Complex at Neduncheliyan Salai in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/5993,Parks,Completed,NQ-SHOZHINGANALLUR,197,452000,Proposed Construction of open Gym at Kumarasamy Nagar 6th street Park (17.00 m x 2.35 m = 39.95) m2 in div -197 u-45 zone -15,Own Sources,15,2018-19,2018-19 NQ/2018-19/6268,Buildings,Completed,NQ-SHOZHINGANALLUR,197,310000,Improvements Works to Public Health Sub Center at Gangaiamman koil Street in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/6273,Roads,Completed,NQ-SHOZHINGANALLUR,197,2200000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-197 U-45 ZONE-XV.,Own Sources,15,2018-19,2019-20 NQ/2018-19/7180,Buildings,Completed,NQ-SHOZHINGANALLUR,197,314000,Construction of Septic Tank for Inside of Shopping Complex at Neduncheliyan Salai in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2018-19 NQ/2018-19/7425,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,960000,"Road Cut Restoration of BT Road at Neduncheliyan Salai,Village High Road, Narayanasamy Nagar main Road & 4th Street in Dn-197 U-45 Z-15",Deposit Works,15,2018-19,2019-20 NQ/2018-19/7863,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,255000,Desilting of Swd and Side Drain At Various Streets In Division-197 Unit-45 Zone-XV,Own Sources,15,2018-19,2018-19 NQ/2018-19/7900,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,417000,Supplying and Fixing RCC Hume Pipe at Eswaran Street in Dn-197 U-45 Z-15,Own Sources,15,2018-19,2018-19 NQ/2018-19/8586,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,890000,Road Cut Restoration OF CC Road at Lalbhagadur Sastri Street in Dn-197 U-45 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8870,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,3710000,Restoration of Road Cut at School Road (Village High Road to KK Salai) in Dn-197 U-45 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8872,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,4000000,Restoration of Road Cut at Village High Road ( From Anna street to KK salai ) in Dn-197 U-45 Z-15,Deposit Works,15,2018-19,2019-20 BR/2018-19/17963,Road Cut,Completed,BR-Bus Route Roads,198,753000,"ROAD CUT RESTORATION (ROAD CUT MADE BY RELIANCE JIO FOR OFC CABLE)AT VARIOUS STREETS IN U44, Z-15",Deposit Works,15,2018-19,2019-20 BR/2018-19/17999,Road Cut,Completed,BR-Bus Route Roads,198,434000,"ROAD CUT RESTORATION (ROAD CUT MADE BY ACT FOR OFC CABLE)AT VARIOUS STREETS IN DN 192 ADN 196, U44, Z-15",Deposit Works,15,2018-19,2019-20 BR/2018-19/5575,Roads,Completed,BR-Bus Route Roads,198,37450000,"Forming and laying the road with DBM and BC by paver finisher using plastic waste along with traffic improvement work at TNHB A Road in Dn-198, Zone - XV",Grants,15,2018-19,2020-21 L/2018-19/6336,Electrical,Completed,L-Electrical,198,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office building at Neduncheliyan street in Div-198 in Zone -XV.EB Account Number-327.003.1263",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/10392,Buildings,Completed,NQ-SHOZHINGANALLUR,198,517000,Improvements to Mobile toilet at Erikarai salai in Dn-198 U-44 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/10507,Buildings,Completed,NQ-SHOZHINGANALLUR,198,457000,"Providing Bio- Shredding Pulverizer Machine, Manure Seiver Machine And Weighing Machine Including Civil And Electrical Work in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11163,Buildings,Completed,NQ-SHOZHINGANALLUR,198,61000,"Improvements works to Amma Unavagam at Kudumiyandi Thoppu School street & Ponniamman koil street in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11299,Buildings,Completed,NQ-SHOZHINGANALLUR,198,120000,"PROVIDING BORE WELL IN PUBLIC CONVENIENCE AT PANAIYUR KUPPAM (NORTH) IN DN-198,U-44,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11805,Buildings,Completed,NQ-SHOZHINGANALLUR,198,115000,"IMPROVEMENTS WORKS TO RELIF CENTRE (TSUNAMI BUILDING) AT KUDIMIYANDI THOPPU SCHOOL STREET IN DN-198,U-44,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11869,Parks,Completed,NQ-SHOZHINGANALLUR,198,384000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT TNHB E12 ROAD IN DN-198 ,U-44,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11870,Parks,Completed,NQ-SHOZHINGANALLUR,198,305000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT VGP 2ND MAIN ROAD (SEA CLIFF) IN DN-198 ,U-44,Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/11909,Parks,Completed,P-Parks and Playfields,198,1535000,"Plantation Meintenance of Tree Sapling for one Yera at various Places in Dn-198,199, U-44, Zone-15",Own Sources,15,2018-19,2021-22 NQ/2018-19/13336,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,740000,Road Cut Restoration of BT Road at TNHB B1 Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/13338,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,460000,Road Cut Restoration of BT Road at TNHB C4 Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/13339,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,2870000,Road Cut Restoration OF CC Road at TNHB C3 Road in Dn-198 U-45 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/13340,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,104000,Road Cut Restoration OF CC Road at TNHB A Road in Dn-198 U-45 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/13503,Buildings,Completed,NQ-SHOZHINGANALLUR,198,800000,"Improvements works to Amma Unavagam at Kudumiyandi thoppu & Ponniamman koil Street in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/13686,Roads,Completed,NQ-SHOZHINGANALLUR,198,90000,ATTENDING REPAIR WORKS FOR STREET FURNITURES AT VARIOUS STREET IN DN-198 U-44 Z-15,Own Sources,15,2018-19,2020-21 NQ/2018-19/14763,Parks,Completed,NQ-SHOZHINGANALLUR,198,997000,"OUTSOURCING OF PARK MAINTENANCE FOR WATER LORRY FOR 9 MONTHS (270 DAYS) AT B6 PARK,C6 PARK,E12 PARK IN DN-198 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/15772,Buildings,Completed,NQ-SHOZHINGANALLUR,198,1660000,"CONSTRUCTION OF MULTI PURPOSE HALL AT KUDIMIYANDI THOPPU SCHOOL STREET IN DN-198, U-44, Z-15",MPLADS,15,2018-19,2019-20 NQ/2018-19/17310,Roads,Completed,NQ-SHOZHINGANALLUR,198,4775000,"FORMING AND LAYING OF BT Road at PONDICHERRY PATTAI SALAI,PARAMESHWARA NAGAR 1ST STREET,PADAVATTAMMAN KOIL 4TH STREET, PARAMESHWARA NAGAR MAYANA PATHAI EXTN in Dn-198 U-44 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17312,Roads,Completed,NQ-SHOZHINGANALLUR,198,5446000,"FORMING AND LAYING OF CC ROAD AT PANAIYUR KUPPAM SCHOOL 2ND CROSS STREET,PANAIYUR KUPPAM SCHOOL 1ST CROSS STREET LINK, PANAIYUR MGR 7TH STREET, PANAIYUR KUPPAM SCHOOL 1ST CROSS STREET IN DN-198 U-44 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17313,Roads,Completed,NQ-SHOZHINGANALLUR,198,5123000,"FORMING AND LAYING OF CC ROAD AT PANAIYUR KUPPAM SCHOOL STREET, PAIYANUR MGR 10TH STREET , PAIYANUR MGR 11TH STREET , PAIYANUR MGR 12TH STREET , PAIYANUR MGR 5TH STREET IN DN-198 U-44 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17316,Roads,Completed,NQ-SHOZHINGANALLUR,198,5443000,"FORMING AND LAYING OF CC ROAD AT PANAIYUR MGR 6TH STREET, PANAIYUR MGR 8TH STREET, PANAIYUR MGR 9TH STREET, PANAIYUR MGR 2ND STREET, PANAIYUR MGR 3RD STREET, PANAIYUR MGR 1ST STREET, PANAIYUR MGR 13TH STREET, PANAIYUR MGR 4TH STREET IN DN-198 U-44 Z-15.",Own Sources,15,2018-19,2020-21 NQ/2018-19/17332,Roads,Completed,NQ-SHOZHINGANALLUR,198,2913000,"FORMING AND LAYING OF CC ROAD AT KUDIMIYANDI THOPPU SCHOOL BUILDING 1ST CROSS STREET SOUTH SIDE, ANNAI INDIRA CROSS STREET, GANGAIAMMAN KOIL 2ND STREET 1ST LANE, GANGAIAMMAN KOIL 4TH CROSS STREET IN DN-198 U-44 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/17411,Roads,Completed,NQ-SHOZHINGANALLUR,198,760000,"RELAYING OF BITUMINOUS ROAD WITH ROAD CUT RESTORATION AT KUMARAN KUDIL ANEX 1ST CROSS STREET IN DN-194,U45,Z15",Own Sources,15,2018-19,2020-21 NQ/2018-19/3241,Parks,Completed,NQ-SHOZHINGANALLUR,198,256000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT TNHB E 12 PARK IN DN-198 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/3243,Parks,Completed,NQ-SHOZHINGANALLUR,198,118000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT SEA CLIFF PARK IN DN-198 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/3333,Roads,Completed,NQ-SHOZHINGANALLUR,198,292000,IMPROVEMENTS AND RECTIFICATION OF SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VILLAGE HIGH ROAD IN DIV-198 U-44 ZONE-XV.,Own Sources,15,2018-19,2018-19 NQ/2018-19/3613,Buildings,Completed,NQ-SHOZHINGANALLUR,198,1950000,PROVIDING NAME BOARDS AT VARIOUS STREETS IN Dn-198 U-44 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/4193,Buildings,Completed,NQ-SHOZHINGANALLUR,198,630000,"IMPROVEMENTS WORKS TO COMPOST YARD AT HINDU MAYANA PATHAI BURIAL GROUND IN DN-198,U-44,Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/4277,Roads,Completed,NQ-SHOZHINGANALLUR,198,1958000,"FORMING AND LAYING OF BT ROAD AT SATHIYAVANIMUTHU STREET 2ND STREET,SATHIYAVANIMUTHU 1ST STREET,VAITHIYALINGA SALAI, PARAMESHWARAN NAGAR 2ND STREET in Dn-198 U-44 Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/4278,Roads,Completed,NQ-SHOZHINGANALLUR,198,5493000,"FORMING AND LAYING OF BT ROAD AT LILLY POND 1ST STREET,GANGAIAMMAN KOIL 3RD STREET 1ST LANE,GANGAIAMMAN KOIL 1ST CROSS STREET,GANGAIAMMAN KOIL 2ND CROSS STREET,GANGAIAMMAN KOIL 3RD CROSS STREET,DURAISAMY STREET in Dn-198 U-44 Z-15.",Own Sources,15,2018-19,2020-21 NQ/2018-19/5090,Buildings,Completed,NQ-SHOZHINGANALLUR,198,450000,"IMPROVEMENTS WORKS TO ANGANWADI AT ANNAI INDIRA STREET & PANAIYUR KUPPAM SCHOOL STREET IN DN-198, U-44, Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/5109,Buildings,Completed,NQ-SHOZHINGANALLUR,198,1040000,"MAINTENANCE CONTRACT FOR HOUSE KEEPING SERVICES TO PUBLIC CONVENIENCES AT 32 LOCATIONS FOR THE PERIOD OF 4 MONTHS (120 DAYS) IN U-44 & 45 , ZONE-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/6393,Roads,Completed,NQ-SHOZHINGANALLUR,198,5246000,"Forming and Laying of BT Road at Gangaiamman koil street,Lilly pond 2nd street,Parameshwaran nagar,Rajamanickam street,Ambedkar street in Dn-198 U-44 Z-15.",Own Sources,15,2018-19,2020-21 NQ/2018-19/7850,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,198,63000,"Desilting of Side Drain at Rajiv Gandhi Nagar and Sathiyavanimuthu street in Dn-198 , U-44 ,Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/7865,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,198,139000,"Minor Repair work & Providing Hume Pipe for Road Crossing at TNHB Layout in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/7923,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,1790000,Road Cut Restoration OF CC Road at TNHB A Road in Dn-198 U-45 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/7932,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,754000,Road Cut Restoration of BT Road at TNHB C1 Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8089,Parks,Completed,NQ-SHOZHINGANALLUR,198,30000,"Repair and Maintenance of play apparatus at Sea cliiff Park ,TNHB B6 Park , TNHB C6 Park in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8116,Buildings,Completed,NQ-SHOZHINGANALLUR,198,2290000,"Construction of compound wall at TNHB E1 Road (OSR) in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8118,Buildings,Completed,NQ-SHOZHINGANALLUR,198,1450000,"Construction of compound wall at TNHB C1 Road (OSR) in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8119,Buildings,Completed,NQ-SHOZHINGANALLUR,198,1100000,"Construction of compound wall & Providing Children Play Apparatus at TNHB D2 Road (OSR) in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8739,Buildings,Completed,NQ-SHOZHINGANALLUR,198,258000,"Improvement and Repair Works to Toilet at Panaiyur Kuppam Gents, Panaiyur Kuppam Ladies (south), Panaiyur Kuppam Ladies (North), Kudimiyandi Thoppu School street, Rajiv Gandhi Nagar, Sathiyavanimuthu street, Parameshwaran nagar street & Prime Toilet Modern Layout 6th Avenue in Dn-198 U-44 Z-15",Own Sources,15,2018-19,2018-19 NQ/2018-19/8866,Roads,Completed,NQ-SHOZHINGANALLUR,198,530000,ATTENDING PATCH WORK AT VARIOUS STREET IN DN-198 U-44 Z-15,Own Sources,15,2018-19,2019-20 NQ/2018-19/8894,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,55000,Road Cut Restoration of BT Road at Pondicherry Salai Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8895,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,920000,Road Cut Restoration of BT Road at TNHB D1 Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8897,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,510000,Road Cut Restoration of BT Road at TNHB D3 Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8899,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,520000,Road Cut Restoration of BT Road at Pondicherry Salai Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8901,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,449000,"Road Cut Restoration of BT Road at TNHB D9,D5,E42,B1 Road in Dn-198 U-44 Z-15",Deposit Works,15,2018-19,2019-20 NQ/2018-19/8902,Road Cut,Completed,NQ-SHOZHINGANALLUR,198,70000,Road Cut Restoration OF CC Road at TNHB A Road in Dn-198 U-44 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8918,Buildings,Completed,NQ-SHOZHINGANALLUR,198,1540000,"Construction of compound wall at Akkarai Bhakthivedhantha Salai (OSR) in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8937,Parks,Completed,NQ-SHOZHINGANALLUR,198,1300000,"Construction of compound wall at TNHB E22 Road (OSR) in Dn-198, U-44, Z-15",Own Sources,15,2018-19,2019-20 L/2018-19/6369,Electrical,Completed,L-Electrical,199,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at 16th ceremony hall utthandi in Div-199 Zone - 15 E.B Account Number : 328.001.2713",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6374,Electrical,Completed,L-Electrical,199,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office utthandi in Div-199 Zone - 15 E.B Account Number : 328.001.69",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/10992,Roads,Completed,NQ-SHOZHINGANALLUR,199,740000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-199 U-44 ZONE-XV,Own Sources,15,2018-19,2019-20 NQ/2018-19/11907,Parks,Completed,NQ-SHOZHINGANALLUR,199,194500,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (182 DAYS) AT V.G.P 2ND MAIN ROAD IN DN-199 ,U-44, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/12075,Buildings,Completed,NQ-SHOZHINGANALLUR,199,158000,IMPROVEMENTS WORKS TO RELIF CENTRE,Own Sources,15,2018-19,2019-20 NQ/2018-19/12848,Buildings,Completed,NQ-SHOZHINGANALLUR,199,141000,"Improvements works to Amma Unavagam at Nainar Kuppam (VV Venkata subramanian salai) in Dn-199, U-44, Z-15",Own Sources,15,2018-19,2020-21 NQ/2018-19/13482,Buildings,Completed,NQ-SHOZHINGANALLUR,199,161000,"Providing for Water Supply and Electrical arrangement of E-Toilet for at VGP 1st Main Road in Dn-199, Unit - 44, Zone -15",Own Sources,15,2018-19,2019-20 NQ/2018-19/3337,Parks,Completed,NQ-SHOZHINGANALLUR,199,92000,"OUTSOURCING OF PARK MAINTENANCE INCLUDING SWEEPER, WATCHMAN AND GREENARY MAINTENANCE FOR 6 MONTHS (180 DAYS) AT VGP 2ND MAIN ROAD PARK IN DN-199 U-44 Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/5222,Roads,Completed,NQ-SHOZHINGANALLUR,199,60000,ATTENDING REPAIR WORKS TO NAME BOARDS AT VARIOUS STREETS IN Dn-199 U-44 Z-15,Own Sources,15,2018-19,2018-19 NQ/2018-19/5498,Roads,Completed,NQ-SHOZHINGANALLUR,199,128000,"Providing FRC BENCHES and MODERN DUST BIN in beach at V.G.P 1st and 3rd Main Road in Div.199, Unit-44,Zone-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8225,Buildings,Completed,NQ-SHOZHINGANALLUR,199,108000,Improvement And repairs work To Park At Mahaveer Street In DIv-199 U-44 Z-15.,Own Sources,15,2018-19,2019-20 NQ/2018-19/8747,Buildings,Completed,NQ-SHOZHINGANALLUR,199,300000,"IMPROVEMENT WORK FOR PRIME TOILET AT RAJAJI STREET & KUPPAM MAYANA SALAI IN DN-199, U-44, Z-15",Own Sources,15,2018-19,2018-19 D/2018-19/15010,Storm Water Drain,Completed,D-Storm Water Drains,200,61610000,"Construction of Storm Water Drain of size 1200 x 1500mm along Nookampalayam road from OMR to TNSCB office Dn.-200,Zone - XV,Package - 22.",SMART CITY - SWD,15,2018-19,2019-20 L/2018-19/6334,Electrical,Completed,L-Electrical,200,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Division office building at Pazha Thotta salai in Div-200 in Zone -XV.EB Account Number-295.001.3029",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6335,Electrical,Completed,L-Electrical,200,387200,"Supply, Installation, Testing & Commissioning of 5 Kwp Grid Tied Solar Rooftop including Civil works and earthing at Community Hall in Div-200 in Zone -XV.EB Account number 295.001.504",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6337,Electrical,Completed,L-Electrical,200,161400,"Supply, Installation, Testing & Commissioning of 2 Kwp Grid Tied Solar Rooftop including Civil works and earthing at C.I office building at Pazha Thotta salai in Div-200 in Zone -XV.EB Account Number-295.001.3285",SMART CITY - ELECTRICAL,15,2018-19,2019-20 L/2018-19/6339,Electrical,Completed,L-Electrical,200,763400,"Supply, Installation, Testing & Commissioning of 10 Kwp Grid Tied Solar Rooftop including Civil works and earthing at TNSCB Health Centre in Div-200 in Zone -XV.EB Account number 295.008.241",SMART CITY - ELECTRICAL,15,2018-19,2019-20 NQ/2018-19/0132,Buildings,Completed,NQ-SHOZHINGANALLUR,200,520000,PROVIDING STREET FURNITURES AT VARIOUS STREETS IN DIVISION-200 U-45 Z-15.,Own Sources,15,2018-19,2019-20 NQ/2018-19/11294,Buildings,Completed,NQ-SHOZHINGANALLUR,200,69000,"Repair Works to Community hall (Kitchen Center) at Pazhathotta Salai in Dn.200 U-45,Zone-15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/11295,Buildings,Completed,NQ-SHOZHINGANALLUR,200,189000,"Improvements to UPHC by Providing M.S sheet Roof for Genset, Plumbing and Electrical Works.in Div-200 U-45 Zone-XV",Own Sources,15,2018-19,2019-20 NQ/2018-19/12918,Buildings,Completed,NQ-SHOZHINGANALLUR,200,200000,ATTENDING REPAIR WORKS FOR STREET FURNITURES AT VARIOUS STREET IN DIVISION-200 U-45 Z-15.,Own Sources,15,2018-19,2020-21 NQ/2018-19/1398,Road Cut,Completed,NQ-SHOZHINGANALLUR,200,1100000,"RESTORATION OF ROAD CUT BY CMWSSB AT THIRUVALLUVAR STREET, IN DN 200, U45, Z15",Deposit Works,15,2018-19,2019-20 NQ/2018-19/16593,Parks,Completed,NQ-SHOZHINGANALLUR,200,117000,"OUTSOURCING AND SIX MONTHS MAINTENANCE OF PARK AT TNSCB 33RD CROSS STREET IN DN 200, U45, Z15",Own Sources,15,2018-19,2019-20 NQ/2018-19/16594,Parks,Completed,NQ-SHOZHINGANALLUR,200,527000,OUTSOURCING AND SIX MONTHS MAINTENANCE OF PARK AT TNSCB 1ST MAIN ROAD IN DN 200 U45 Z15,Own Sources,15,2018-19,2019-20 NQ/2018-19/3659,Roads,Completed,NQ-SHOZHINGANALLUR,200,108000,"PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT PAZHATHOTTA SALAI(RAJIV GANDHI NAGAR), MAJESTIC LAYOUT.In Div-200 U-45 Z-15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/3814,Buildings,Completed,NQ-SHOZHINGANALLUR,200,30700,PROVIDING INDICATION BOARDS IN BURIAL GROUNDS AT ZONE-XV,Own Sources,15,2018-19,2018-19 NQ/2018-19/5087,Roads,Completed,NQ-SHOZHINGANALLUR,200,68600,ATTENDING REPAIR WORKS FOR STREET FURNITURES AT VARIOUS STREETS IN DIVISION-200 U-45 Z-15.,Own Sources,15,2018-19,2018-19 NQ/2018-19/5122,Roads,Completed,NQ-SHOZHINGANALLUR,200,96000,PROVIDING THERMO PLASTIC PAINT AND STUDS FOR SPEED BREAKERS AT VARIOUS STREETS IN DIV-200 U-45 ZONE-XV.,Own Sources,15,2018-19,2019-20 NQ/2018-19/5187,Buildings,Completed,NQ-SHOZHINGANALLUR,200,1120000,Improvements to Park At TNSCB 2nd Main road in Dn-200 U-45 Z-15.,Own Sources,15,2018-19,2019-20 NQ/2018-19/5207,Parks,Completed,NQ-SHOZHINGANALLUR,200,985000,"Improvements And Repair Works By Providing Electrical Works, Play Apparatus E.t.c., At TNSCB 1st Main Road Park, 33rd Cross street Park And Various Children Play Space in DN-200 U-45 Z-15.",Own Sources,15,2018-19,2019-20 NQ/2018-19/5672,Buildings,Completed,NQ-SHOZHINGANALLUR,200,430000,PROPOSED CONSTRUCTION OF OPEN GYM AT TNSCB 1ST MAIN ROAD PARK IN DIV-200 U-45 Z-XV,Own Sources,15,2018-19,2018-19 NQ/2018-19/5996,Buildings,Completed,NQ-SHOZHINGANALLUR,200,29400,DEMOLITION OF DILAPIDATED BUILDING IN ANNA 1ST CROSS STREET CPS IN DIV-200 U-45 Z-15,Own Sources,15,2018-19,2018-19 NQ/2018-19/6233,Buildings,Completed,NQ-SHOZHINGANALLUR,200,295000,"Improvements To Various Public Convenience By Providing Additional Septic tank, Soak pit And Other Works in Div-200 U-45 Z-15.",Own Sources,15,2018-19,2018-19 NQ/2018-19/7770,Buildings,Completed,NQ-SHOZHINGANALLUR,200,345000,DESILTING OF SWD AND SIDE DRAIN INCLUDING PRECAST SLAB REFIXING WORKS AT VARIOUS STREETS IN DIVISION-200 UNIT-45 ZONE-XV.,Own Sources,15,2018-19,2018-19 NQ/2018-19/7772,Buildings,Completed,NQ-SHOZHINGANALLUR,200,591100,"PROVIDING ,REPLACING CC SLAB AND REPAIR WORKS TO SIDE DRAIN AND SWD AT VARIOUS STREETS IN DIVISION-200 U-45 Z-15.",Own Sources,15,2018-19,2018-19 NQ/2018-19/8075,Buildings,Completed,NQ-SHOZHINGANALLUR,200,115000,"Improvement Works At Various 16th Day Cremation Room By Providing Flooring, Painting E.t.c., In Div-200 U-45 Z-XV.",Own Sources,15,2018-19,2019-20 NQ/2018-19/8169,Buildings,Completed,NQ-SHOZHINGANALLUR,200,1037000,"I Improvements to Anganwadi Including Electrical Works @TNSCB Cross streets of 4th, 21st, 10th avenue, 8th avenue,98th cross street & pondicherry pattai salai in DN 200 U 45 Z 15",Own Sources,15,2018-19,2019-20 NQ/2018-19/8898,Road Cut,Completed,NQ-SHOZHINGANALLUR,200,245000,RESTORATION OF ROAD CUT BY TNHB AT THIRUVALLUVAR STREET in DIV-200 U-45 Z-15,Deposit Works,15,2018-19,2019-20 NQ/2018-19/8940,Roads,Completed,NQ-SHOZHINGANALLUR,200,238000,"Attending Patch Work For Cross Cut And Pot Holes In Various Streets in TNSCB & Jawahar Nagar in Dn-200, U-45, Z-15",Own Sources,15,2018-19,2019-20 NQ/2018-19/9002,Buildings,Completed,NQ-SHOZHINGANALLUR,200,564000,"Providing Bio- Shredding Pulverizer Machine, Manure Seiver Machine And Weighing Machine Including Civil And Electrical Work",Own Sources,15,2018-19,2019-20 B/2018-19/12440,Buildings,Completed,B-Buildings,,11981890,"Supply and Fxing of Surgical Furniture at 4 UCHC ( Thiruvottiyur UCHC (100 bed),Perungudi UCHC (100 bed),Valasaravakkam UCHC (100 bed) and Madhavaram UCHC (65 bed))",Grants,Greater Chennai Corporation,2018-19,2020-21 B/2018-19/12806,Buildings,Completed,B-Buildings,,1371200,"Supply, Installation ,maintenance and house keeping of 200 nos of portable toilet with necessary conservancy materials etc at Nandambakkam Chennai trade centre (Parking space 1 ) for the Global Investor meeting 2019 for 2 days .",Own Sources,Greater Chennai Corporation,2018-19,2019-20 B/2018-19/12807,Buildings,Completed,B-Buildings,,1371200,"Supply, Installation ,maintenance and house keeping of 200 nos of portable toilet with necessary conservancy materials etc at Nandambakkam Chennai trade centre (Parking space 2 ) for the Global Investor meeting 2019 for 2 days .",Own Sources,Greater Chennai Corporation,2018-19,2019-20 B/2018-19/12808,Buildings,Completed,B-Buildings,,1371200,"Supply, Installation ,maintenance and house keeping of 200 nos of portable toilet with necessary conservancy materials etc at Nandambakkam Chennai trade centre (at inside the campus ) for the Global Investor meeting 2019 for 2 days .",Own Sources,Greater Chennai Corporation,2018-19,2019-20 B/2018-19/13548,Buildings,Completed,B-Buildings,,2140000,"Supplying and Fixing Furnitures at Urban Community Health Centre in Valasaravakkam in Dn - 151, Zone - 11 and Perungudi in Dn - 184, Zone - 14.",Grants,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/0592,Bridges,Completed,J-Bridges,,1900000,"Beautification to existing bridge across B-Canal near kotturpuram Mrts in Dn-172,Zone-13",Grants,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/0987,Bridges,Completed,J-Bridges,,3606000,"Beautification to Existing Alandur Bridge across Adyar River in Dn-142,Zone-10.",Grants,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/11303,ROB,Completed,J-Bridges,,989000,"Repair and Maintenance of deck slab and piers at Existing Stanley via duct bridge Opp to Chennai Central Railway Station in Dn-59,Zone-5",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/11305,Grade Separator,Completed,J-Bridges,,797000,"Maintenance of Handrail and kerb for the existing fly over at junction of Muthulakshmi Road (L.B.Road)and Sardar patel road in DN-175,Zone-XIII",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/11326,Grade Separator,Completed,J-Bridges,,576000,"Maintenance of Handrail,Kerb and wearing coat for existing flyover at junction of Gandhi mandapam road and Sardar patel road in Div -171&172,Zone- XIII",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/11595,Culvert,Completed,J-Bridges,,186000,"Name of the work: Dismantling and Re-construction of Existing wall (East & West side) at Periyar pathai in Dn-105,Zone-8",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/11600,Culvert,Completed,J-Bridges,,185000,"Name of the work: Dismantling and Re-construction of Existing wall (East & West side) at Thirukumarapuram 3rd st jun of Canara bank colony street in Dn-105,Zone-8.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/11607,Culvert,Completed,J-Bridges,,190000,"Name of the work: Dismantling and Re-construction of Existing wall (East & West side) at Kaveri road jun of Thirukumarapuram road in Dn-105,Zone-8.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/11865,Bridges,Completed,J-Bridges,,182000,"Painting and repair of ramp portion of Existing Bridge across Buckhinagam canal at Sardar petal road junction of Rajiv Gandhi Salai (Madhiya kailash) in Division -175 ,Unit - 40,Zone -XIII",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/12072,Bridges,Completed,J-Bridges,,93000,Removal of unwanted plants in various Bridges southern Region in Zone-XIII,Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/12087,Overbridges,Completed,J-Bridges,,118000,"Painting for foot bridge across B'Canal at Kotturpuram in Division - 172 , Unit -40, Zone -XIII",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/12089,Bridges,Completed,J-Bridges,,182000,"Painting for crash barrier and repair ramp for existing bridge across adayar river at Kotturpuram in Division - 172 , Unit -40, Zone -XIII",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/12095,Grade Separator,Completed,J-Bridges,,147000,"Providing name board and traffic sign board at existing bridge across adayar river at Kotturpuram and flyover at junction of Dr,Muthulakshmi salai & L.B.Road in Division - 172 , Unit -40, Zone -XIII",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/12291,Grade Separator,Completed,J-Bridges,,7400000,"Name of the work: Painting work at Dr.Radhakrishnan Road junction of T.T.K.Road flyover in Dn-118 ,Zone - IX.",Own Sources,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/14428,Bridges,Completed,J-Bridges,,964000,"Retrofitting work at Nelson Manikkam Road North side existing bridge in Dn -109,Zone-09.",Own Sources,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/18037,Bridges,Completed,J-Bridges,,478000,"Retrofitting work at Nelson Manikkam Road deck slab of existing bridge in Dn -109,Zone-09.",Own Sources,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/18038,Bridges,Completed,J-Bridges,,200000,Removal of Rank Vegetaion at Various bridges and Subways in Center Region.,Own Sources,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/4855,Subway,Completed,J-Bridges,,512000,"Name of the work: Repairs work under the footpath of south Re-taining wall of madley subway in Dn -135&136 ,Zone - X.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4873,Grade Separator,Completed,J-Bridges,,64000,"Name of the work: Repairs in Damaged wall at Soth usman road flyover in Dn-136 ,Zone - X.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4917,Bridges,Completed,J-Bridges,,183000,Removal of Rank Vegetaion at Various bridges and Subways in Center Region.(ZONE 06-10).,Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4919,Bridges,Completed,J-Bridges,,200000,"Repairs in Existing Footpath and Handrail painting work at Namachivayapuram bridge in Dn -109 ,Zone - IX.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4923,Bridges,Completed,J-Bridges,,117000,Wearing coat patches attended at Subways in Center Region (Z-6 TO 10),Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4924,Bridges,Completed,J-Bridges,,172000,"Repairs in Existing pedestrain staircase at Nungambakkam Subway in Dn -109 ,Zone - IX.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4927,Bridges,Completed,J-Bridges,,83200,"Repairs in Existing revitment at Dr.Gurusamy bridge in Dn-107,Zone -VIII.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4928,Bridges,Completed,J-Bridges,,190000,"Repairs in Existing pedestrain under the staircase at Duraisamy Subway in Dn -136 ,Zone - X.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/4929,Bridges,Completed,J-Bridges,,29500,"Repairs in Existing Handrail at Azadnagar 2nd st Boxculvert in Dn -108 ,Zone - VIII.",Own Sources,Greater Chennai Corporation,2018-19,2018-19 J/2018-19/5533,Culvert,Completed,J-Bridges,,38140000,"Construction of Box Culvert across CMWSSB Channel inside the Kodungaiyur Dumping ground in dn -37,zone-4",Grants,Greater Chennai Corporation,2018-19,2020-21 J/2018-19/5538,Culvert,Completed,J-Bridges,,14600000,"Construction of Box Culvert across kodungaiyur canal at Kodungaiyur Dumping ground near Entrance in dn -37,zone-4",Grants,Greater Chennai Corporation,2018-19,2020-21 J/2018-19/7020,Grade Separator,Completed,J-Bridges,,1970000,"Providing vertical garden around the western side piers (4NOS) of Kalaivanar bridge in G.N.Chetty road in Div 136, zone -10",Grants,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/7092,Grade Separator,Completed,J-Bridges,,1640000,"Providing vertical garden around the Eastern side piers (4NOS) of Kalaivanar bridge in G.N.Chetty road in Div 117, zone -9",Grants,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/7124,Subway,Completed,J-Bridges,,515000,"Repair and Painting work in Existing Pedestrian subway at Kamarajar Salai (Near Queen Mary's College) in Dn -109,Zone-09.",Own Sources,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/7173,Bridges,Completed,J-Bridges,,1005000,"Proposed Construction of Foot bridge across CMWSSB channel in between VEERAPANDIAN ST & Pillayar koil st dn -137,zone -x",MLACDS,Greater Chennai Corporation,2018-19,2019-20 J/2018-19/7931,Bridges,Completed,J-Bridges,,995000,"Retrofitting work at Nelson Manikkam Road South side existing bridge in Dn -109,Zone-09.",Own Sources,Greater Chennai Corporation,2018-19,2019-20 L/2018-19/15773,Electrical,Completed,L-Electrical,,4492000,"Proposal for commissioning of 58 nos. of 8 mtr Octagonal street lamp posts with G.I Double bracket at Ennore Express Way from NTS Road junction to Tiruchinnakuppam road junction in ward-14, Zone-1 Tiruvottriyur [SOR 2017-18]",Own Sources,1,2018-19,2019-20 L/2018-19/7821,Electrical,Completed,L-Electrical,,2900500,"Supply and Erection of 33 nos of 8 mtrs GI Lamp Post with Double Arch Bracket and 3 nos of 8 mtrs GI lamp post with tripple arch bracket laying of 1510mtr 31/2x25 Sqmm PVC Alu.cable for Center Median at E.V.R Salai from junction of Harrington road to Coovam river bridge in Div-102 ,Zone-VIII Area.",Own Sources,8,2018-19,2019-20 L/2018-19/5937,Electrical,Completed,L-Electrical,,86300,"Estimate for Supply, Installation, Testing & Commissioning of 1 Kwp Grid Tied Solar Rooftop including Civil works and earthing at, School, CMS, Sanjivi street, Mylapore, DIVISION-125, ZONE-9 (E.B.Account no-124/045/129 )",SMART CITY - ELECTRICAL,9,2018-19,2019-20 D/2018-19/14951,Storm Water Drain,Completed,D-Storm Water Drains,,55940000,"Demolition and Re-Construc tion of Storm Water Drain for Meenambakkam Sub - Way in Zone - 12,Package - 23.",SMART CITY - SWD,12,2018-19,2019-20 D/2018-19/14953,Storm Water Drain,Completed,D-Storm Water Drains,,13050000,"Demolition and Re-Construc tion of Storm Water Drain for Thilaiganga Sub - Way in Zone - 12,Package - 25.",SMART CITY - SWD,12,2018-19,2019-20 D/2018-19/14962,Storm Water Drain,Completed,D-Storm Water Drains,,15765000,"Construction of Storm Water Drain at Bhell sakthi nagar,Kamarajar Nagar west 1st main road and Journalist colony in Dn.-178,180 &182 ,Zone - 13,Package - 20.",SMART CITY - SWD,13,2018-19,2019-20 D/2018-19/9757,Storm Water Drain,Completed,D-Storm Water Drains,,44928999,Construction of Storm Water Drain at DGS Dinakaran Salai and 10 Other Roads in Zone - 13 - Package - 51.,Grants,13,2018-19,2020-21 D/2018-19/9758,Storm Water Drain,Completed,D-Storm Water Drains,,53955000,Construction of Storm Water Drain at VOC Street and 20 Other Roads in Zone - 13 - Package - 52.,Grants,13,2018-19,2019-20 D/2018-19/9759,Storm Water Drain,Completed,D-Storm Water Drains,,36655000,Construction of Storm Water Drain at MRC Nagar ( Sathyadev Avenue) and 3 Other Roads in Zone - 13 - Package - 53.,Grants,13,2018-19,2019-20 D/2018-19/9760,Storm Water Drain,Completed,D-Storm Water Drains,,28373000,Construction of Storm Water Drain at New Secrratariat Colony 3rd Street and 5 Other Roads in Zone - 13 - Package - 54.,Grants,13,2018-19,2019-20 D/2018-19/9761,Storm Water Drain,Completed,D-Storm Water Drains,,36969000,Construction of Storm Water Drain at Bhuvaneswari Nagar I Main Road and 7 Other Roads in Zone - 13 - Package - 55.,Grants,13,2018-19,2019-20 D/2018-19/9762,Storm Water Drain,Completed,D-Storm Water Drains,,49617000,Construction of Storm Water Drain at Velachery Main Road Right on South Side and 3 Others Roads in Zone - 13 - Package - 64,Grants,13,2018-19,2020-21 D/2018-19/9763,Storm Water Drain,Completed,D-Storm Water Drains,,47550000,Construction of Storm Water Drain at Aranganathan Lane and 14 Other Roads in Zone - 13 - Package - 63,Own Sources,13,2018-19,2019-20 D/2018-19/9764,Storm Water Drain,Completed,D-Storm Water Drains,,48251000,Construction of Storm Water Drain at Gandhi Mandapam Road on North Side and 11 Other Roads in Zone - 13 - Package - 62,Grants,13,2018-19,2019-20 D/2018-19/9765,Storm Water Drain,Completed,D-Storm Water Drains,,47085000,Construction of Storm Water Drain Railway Border 2nd street on South Side and 9 Other Roads in Zone - 13 - Package - 61,Grants,13,2018-19,2020-21 D/2018-19/9766,Storm Water Drain,Completed,D-Storm Water Drains,,48613000,Construction of Storm Water Drain at Srinagar Colony South Avenue on East side and 9 Other Roads in Zone - 13 - Package - 60,Grants,13,2018-19,2020-21 D/2018-19/9767,Storm Water Drain,Completed,D-Storm Water Drains,,37559000,Construction of Storm Water Drain at Devi Karumariamman Nagar 9th Street on South Side and 6 Other Roads in Zone - 13 - Package - 59,Grants,13,2018-19,2019-20 D/2018-19/9768,Storm Water Drain,Completed,D-Storm Water Drains,,35788000,Construction of Storm Water Drain at R.K.Nagar 2nd Cross Street on West Side and 7 Other Roads in Zone - 13 - Package - 58.,Grants,13,2018-19,2020-21 D/2018-19/9769,Storm Water Drain,Completed,D-Storm Water Drains,,40683000,Construction of Storm Water Drain at Vijaya Nagar 6th Cross Street and 6 Other Roads in Zone - 13 - Package - 57.,Grants,13,2018-19,2020-21 D/2018-19/9770,Storm Water Drain,Completed,D-Storm Water Drains,,34988000,Construction of Storm Water Drain at Velachery Main Road and 2 Other Roads in Zone - 13 - Package - 56.,Grants,13,2018-19,2020-21 D/2018-19/9771,Storm Water Drain,Completed,D-Storm Water Drains,,42255000,Construction of Storm Water Drain at Thulukathamman Koil Street and Veeramani Street in Zone - 14 - Package - 70.,Grants,14,2018-19,2019-20 D/2018-19/9772,Storm Water Drain,Completed,D-Storm Water Drains,,45875000,Construction of Storm Water Drain at LICi Nagar and 2 Other Roads in Zone - 14 - Package - 69.,Grants,14,2018-19,2020-21 D/2018-19/9773,Storm Water Drain,Completed,D-Storm Water Drains,,37834000,Construction of Storm Water Drain at Kuberi Nagar and 2 Other Roads in Zone - 14 - Package - 68.,Grants,14,2018-19,2019-20 D/2018-19/9774,Storm Water Drain,Completed,D-Storm Water Drains,,31125000,Construction of Storm Water Drain at Rajalakshmi Nagar and 2 Other Roads in Zone - 14 - Package - 67.,Grants,14,2018-19,2019-20 D/2018-19/9775,Storm Water Drain,Completed,D-Storm Water Drains,,79358000,"Construction of Storm Water Twin Drain of Size 2000 x 2000 mm Along Sri Nagar Main Road From Narayanapuram Lake to Mylai Balaji Canal in Dn - 188, Zone - 14 - Package - 66.",Grants,14,2018-19,2019-20 D/2018-19/9776,Storm Water Drain,Completed,D-Storm Water Drains,,39818000,Construction of Storm Water Drain at Arul Murugan Nagar and 3 Other Roads in Zone - 13 & 14 - Package - 65.,Grants,14,2018-19,2020-21 D/2018-19/9777,Storm Water Drain,Completed,D-Storm Water Drains,,25229000,Construction of Storm Water Drain at Vivekandan Street and 2 Other Roads in Zone - 15 - Package - 73.,Grants,15,2018-19,2019-20 D/2018-19/9778,Storm Water Drain,Completed,D-Storm Water Drains,,31812000,Construction of Storm Water Drain at Saraswathy Nagar North and 3 Other Roads in Zone - 15 - Package - 72,Grants,15,2018-19,2020-21 D/2018-19/9779,Storm Water Drain,Completed,D-Storm Water Drains,,31805000,Construction of Storm Water Drain at Eswaran Koil Street and 2 Other Roads in Zone -15 - Package - 71.,Grants,15,2018-19,2019-20 NA/2019-20/0928,Buildings,Completed,NA-THIRUVOTTIYUR,1,3120000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT SATHANGADU DUMPING GROUND IN DIV-07, UNIT-02, ZONE-01",Own Sources,1,2019-20,2019-20 NA/2019-20/1218,Buildings,Completed,NA-THIRUVOTTIYUR,1,875000,"PROVIDING WELL RING AT VARIOUS LOCATION FOR PRODUCE MANURE IN DIV-1, 2, 3 and 4, UNIT-1, ZONE-1",Own Sources,1,2019-20,2019-20 NA/2019-20/12700,Roads,Completed,NA-THIRUVOTTIYUR,1,1993000,"Improvement to interior C.C road at J.J. Nagar 1st cross street in Division 1, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12701,Roads,Completed,NA-THIRUVOTTIYUR,1,749000,"Improvement to interior C.C road at J.J. Nagar 6th block in Division 1, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12702,Roads,Completed,NA-THIRUVOTTIYUR,1,667000,"Improvement to interior C.C road at J.J. Nagar 7th block in Division 1, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12703,Roads,Completed,NA-THIRUVOTTIYUR,1,796000,"Improvement to interior C.C road at J.J. Nagar 12th block in Division 1, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/13334,Buildings,Completed,NA-THIRUVOTTIYUR,1,4930000,"Construction of MCC at Ennore express road thalangkuppam in Division-1, Unit-01, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/1741,Buildings,Completed,NA-THIRUVOTTIYUR,1,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT THALAKUPPAM IN DIVISION -1, UNIT-1, ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/1802,Buildings,Completed,NA-THIRUVOTTIYUR,1,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT ENNORE EXPRESS ROAD IN DIVISION -9, UNIT-2, ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/1822,Parks,Completed,NA-THIRUVOTTIYUR,1,31500,"PROVIDING METRO WATER DISCARDED TANK (SINTEX TANK) VARIOUS PARK IN DIVISION 1,3,5,7 & 11, UNIT-1,2 &3, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/1858,Buildings,Completed,NA-THIRUVOTTIYUR,1,554000,"SUPPLY AND FIXING OF SEWING MACHINE 3 NOS IN UNIT-1, 2 & 3, ZONE-1",Own Sources,1,2019-20,2019-20 NA/2019-20/2120,Parks,Completed,NA-THIRUVOTTIYUR,1,121000,"PROVIDING MULCHPIT AT VARIOUS LOCATION IN UNIT 1,2,AND 3 ZONE 1",Own Sources,1,2019-20,2019-20 NA/2019-20/3711,Buildings,Completed,NA-THIRUVOTTIYUR,1,696000,"Providing Well Type R W H 90 cm dia at Various Location in dn-1,unit-1,Zone-1",Own Sources,1,2019-20,2021-22 NA/2019-20/3737,Buildings,Completed,NA-THIRUVOTTIYUR,1,955000,"PROVIDING CONSERVANCY WORKERS DRESSING ROOM, PROVIDING BARBED WIRE FENCING FOR ALL AROUND THE RRC AND CI OFFICE IN DN -1,UNIT-1,ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/3952,Buildings,Completed,NA-THIRUVOTTIYUR,1,323000,"Minor repair works to SWD and Side Drain at Thiruvalluvar Nagar in Division-01, Unit-01, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/6087,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,284000,"DESILTING OF SWD AND SIDE DRAINS AT VARIOUS STREETS IN DIV-1,UNIT-1,ZONE-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7467,Parks,Completed,NA-THIRUVOTTIYUR,1,675000,"Abstract for Maintenance Estimate for Park at Glass Factory road (Hansa Estates) near Balakrishna nagar, (per year) in Div-7, Unit-2, Zone-1 (Area -1243.88 Sq.m)",Own Sources,1,2019-20,2020-21 NA/2019-20/8158,Roads,Completed,NA-THIRUVOTTIYUR,1,2555000,"Improvement to interior C.C road at J.J. Nagar main road in Division 1, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/10350,Buildings,Completed,NA-THIRUVOTTIYUR,2,354000,"Repair and Improvement to Periyakuppam Public convenance at Ennore Express road in Division-2, Unit-1, Zone-1",Own Sources,1,2019-20,2021-22 NA/2019-20/10698,Buildings,Completed,NA-THIRUVOTTIYUR,2,365000,"Improvements to Community well at kattukuppam 3rd street in Division-02, Unit-01, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/12707,Roads,Completed,NA-THIRUVOTTIYUR,2,745000,"Improvement to interior CC road at Thilagar nagar 4th street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12708,Roads,Completed,NA-THIRUVOTTIYUR,2,1501000,"Improvement to interior C.C road at Nehru nagar 2nd street (Bajanai koil street) in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12709,Roads,Completed,NA-THIRUVOTTIYUR,2,430000,"Improvement to interior C.C road at Nehru nagar, Vinayagar koil street (Church Street) in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12710,Roads,Completed,NA-THIRUVOTTIYUR,2,841000,"Improvement to interior CC road at Nehru nagar (CSI Church Street) in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12711,Roads,Completed,NA-THIRUVOTTIYUR,2,1618000,"Improvement to interior C.C road at Nehru nagar (Manamakil mandram Street) (opp. To Ulaganathan park) in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12712,Roads,Completed,NA-THIRUVOTTIYUR,2,781000,"Improvement to interior CC road at Sastri nagar 2nd street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12713,Roads,Completed,NA-THIRUVOTTIYUR,2,859000,"Improvement to interior CC road at Sastri nagar 3rd street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12714,Roads,Completed,NA-THIRUVOTTIYUR,2,1335000,"Improvement to interior CC road at Anna nagar 3rd street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12715,Roads,Completed,NA-THIRUVOTTIYUR,2,400000,"Improvement to interior CC road at Anna nagar 3rd cross street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12716,Roads,Completed,NA-THIRUVOTTIYUR,2,553000,"Improvement to interior CC road at Rajiv nagar main road in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12717,Roads,Completed,NA-THIRUVOTTIYUR,2,467000,"Improvement to interior CC road at Rajiv nagar 1st cross street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12718,Roads,Completed,NA-THIRUVOTTIYUR,2,257000,"Improvement to interior CC road at Rajiv nagar 2nd cross street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12719,Roads,Completed,NA-THIRUVOTTIYUR,2,564000,"Improvement to interior CC road at Gandhi Nagar cross street in Division 2, Unit 1, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/1743,Buildings,Completed,NA-THIRUVOTTIYUR,2,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT KATHIVAKKAM HIGH ROAD IN DIVISION-2, UNIT-1, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/1824,Buildings,Completed,NA-THIRUVOTTIYUR,2,3120000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT PERIYAKUPPAM BURIYAL GROUND ENNORE EXPRESS ROAD IN DIV-2,UNIT-1,ZONE-1",Own Sources,1,2019-20,2020-21 NA/2019-20/3686,Buildings,Completed,NA-THIRUVOTTIYUR,2,320000,"Dismantling, Reconstruction of Existing Culvert Slab Desilting and improvements to side drain at Periyakuppam in Dn-2, U-1, Z -1.",Own Sources,1,2019-20,2019-20 NA/2019-20/3706,Buildings,Completed,NA-THIRUVOTTIYUR,2,765000,"Providing Well type RWH 90 cm dia at Various Location in dn-2,unit-1,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/3933,Buildings,Completed,NA-THIRUVOTTIYUR,2,516000,"Minor repair works to Side drains and SWD in Division-02, Unit-01, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/3957,Buildings,Completed,NA-THIRUVOTTIYUR,2,255000,"DESILTING OF SWD AND SIDE DRAIN AT VARIOUS STREETS IN DN-02, UNIT-01, ZONE-01",Own Sources,1,2019-20,2020-21 NA/2019-20/4322,Buildings,Completed,NA-THIRUVOTTIYUR,2,1747000,"Desilting, Repairing & improvements to storm water drain and side drain at Valluvar nagar in Division- 02,Unit-01,Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/4436,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,439000,"Repairs and Improvements to Side Drain at Kamalammal nagar Main road, and 1.st. street to 3 rd. street. in Division-02,Unit-01,Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/4437,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,442000,"Repairs and Improvements to Side Drain at Ellaiyamman koil Main road ( Griyappa Thottam) in Division-02,Unit-01,Zone-01",Own Sources,1,2019-20,2019-20 NA/2019-20/5833,Buildings,Completed,NA-THIRUVOTTIYUR,2,518000,"REPAIRS AND IMPROVEMENTS TO PERIYAKUPPAM CPS AT ENNORE EXPRESS ROAD IN DIVISION-02, UNIT-01, ZONE-01",Own Sources,1,2019-20,2020-21 NA/2019-20/7859,Buildings,Completed,NA-THIRUVOTTIYUR,2,500000,"Dismantling the dilapidated Community hall at Kathivakkam High road in Division-02, Unit-01, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/7995,Buildings,Completed,NA-THIRUVOTTIYUR,2,600000,"Repair and Improvement Works to UPHC at Kathivakkam High Road in Division -02,Unit-01,Zone-01",Own Sources,1,2019-20,2021-22 NA/2019-20/8008,Buildings,Completed,NA-THIRUVOTTIYUR,2,314000,"Improvements to Community Well at Nehru Nagar Park Street ( Ulaganathan Park) in Division-02, Unit-01, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/10293,Buildings,Completed,NA-THIRUVOTTIYUR,3,563000,"Repair and Improvement to Chennai Primary School (CPS) at annai sivagami nagar 10th Street in Division-3, Unit-1, Zone-1.",Own Sources,1,2019-20,2021-22 NA/2019-20/10380,Buildings,Completed,NA-THIRUVOTTIYUR,3,302000,"Repair and Improvements to Chennai Primary School (CPS) at Kasi koil Kuppam in Division - 03 , Unit - 02 , Zone -01.",Own Sources,1,2019-20,2021-22 NA/2019-20/12348,Roads,Completed,NA-THIRUVOTTIYUR,3,2029000,"Improvements to interior CC Road at Nethaji Nagar 3rd Street in Division-03, Unit-01, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/12349,Roads,Completed,NA-THIRUVOTTIYUR,3,1585000,"Improvement to interior CC Road at Nethaji Nagar 5th Street in Division-03, Unit-01, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/12350,Roads,Completed,NA-THIRUVOTTIYUR,3,1268000,"Improvement to interior CC Road at Nethaji Nagar 6th Street in Division-03, Unit-01, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/12629,Buildings,Completed,NA-THIRUVOTTIYUR,3,367000,"Additional work to ICDS Centre No :106 at Annai sivagami nagar 10th street in Division -3, Unit-1,Zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/15249,Roads,Completed,NA-THIRUVOTTIYUR,3,495000,"Laying paver block approach road at T-sunami quarters 5th main road to police station AIR nagar in Division-03, Unit-01, Zone-01.",Own Sources,1,2019-20,2021-22 NA/2019-20/1757,Buildings,Completed,NA-THIRUVOTTIYUR,3,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT ENNORE EXPRESS ROAD IN DIVISION -3, UNIT-1, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/2780,Buildings,Completed,NA-THIRUVOTTIYUR,3,235000,"REPAIR TO ICDS CENTRE NO.106-ANNAI SIVAGAMI NAGAR 10 TH STREET IN DN-03,UNIT-01,ZONE-01",Own Sources,1,2019-20,2019-20 NA/2019-20/3722,Buildings,Completed,NA-THIRUVOTTIYUR,3,557000,"Providing Well Type RWH 90 cm dia at Various Location in dn-3,unit-1,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/3967,Buildings,Completed,NA-THIRUVOTTIYUR,3,196000,"REPAIR TO CHENNAI PRIMARY SCHOOL AT ANNAI SIVAGAMI NAGAR IN DN-03,UNIT-01,ZONE-01",Own Sources,1,2019-20,2019-20 NA/2019-20/15295,Buildings,Completed,NA-THIRUVOTTIYUR,4,538000,"Supply and fixing of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete in Division 4, Unit 1, Zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/1761,Buildings,Completed,NA-THIRUVOTTIYUR,4,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT KATHIVAKKAM HIGH ROAD IN DIVISION-4, UNIT-1, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/3717,Buildings,Completed,NA-THIRUVOTTIYUR,4,493000,"Providing Well Type R W H 90cm dia at Various Location in dn-4,unit-1,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/3954,Buildings,Completed,NA-THIRUVOTTIYUR,4,502000,"Minor repairs to SWD and Side drains in Division-04, Unit-01, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/3960,Buildings,Completed,NA-THIRUVOTTIYUR,4,375500,"DESILTING OF SWD AND SIDE DRAIN AT VARIOUS STREETS IN DN-04, UNIT-01, ZONE-01",Own Sources,1,2019-20,2020-21 NA/2019-20/5479,Buildings,Completed,NA-THIRUVOTTIYUR,4,575000,"REPAIRS AND IMPROVEMENTS TO SIDE DRAIN AT BRINDAVAN NAGAR EXTENSION IN DIVISION-4,. UNIT-1 ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/8442,Buildings,Completed,NA-THIRUVOTTIYUR,4,765000,"Repairs and Improvements to Ramanadhapuram School in Division-4, Unit-1, Zone-1.",Own Sources,1,2019-20,2021-22 BR/2019-20/2246,Roads,Completed,BR-Bus Route Roads,5,1050000,"Proposed construction of Modern Stainless Steel Bus Shelter at Thiruvottiyur high road near Ernavoor Bridge-Service Road Bharath nagar (Towards Ennore )in Div - 05, Zone - I",MLACDS,1,2019-20,2020-21 BR/2019-20/2430,Roads,Completed,BR-Bus Route Roads,5,1050000,"Proposed construction of Modern Stainless Steel Bus Shelter at Thiruvottiyur high road near Ernavoor Bridge-Service Road Bharath nagar (Towards Thiruvottiyur )in Div - 05, Zone - I (6 m X 2.5 m)",MLACDS,1,2019-20,2020-21 BR/2019-20/2848,Roads,Completed,BR-Bus Route Roads,5,1050000,"Proposed construction of Modern Stainless Steel Bus Shelter at Ennore high road near - Bharathiyar nagar (Towards Ennore) in Div - 05, Zone - I",MLACDS,1,2019-20,2020-21 L/2019-20/5421,Electrical,Completed,L-Electrical,5,999800,"Removal of rust eaten and damaged street lamp posts 80 nos. and re fixing of 80 nos of E.L Poles for the rusted and damaged poles at Anjeneyor koil lane, Thanzankuppam,Nettukuppam,Periakuppam, Chinnakuppam, Kasi kovil kuppam beach, Annai sivagami nagar beach road etc in Tiruvottiyur and Ennore section division 1 to 3& 8 zone-1Tiruvottiyur(SOR 2019-20)",Own Sources,1,2019-20,2019-20 NA/2019-20/1505,Buildings,Completed,NA-THIRUVOTTIYUR,5,624000,"PROVIDING WELL RINGS FOR COMPOSTABLE UNIT AT VARIOUS LOCATIONS IN DN-5, 6, 7, 8 and 9, UNIT-2, ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/1765,Buildings,Completed,NA-THIRUVOTTIYUR,5,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT MANALI EXPRESS ROAD, RAMAKRISHNA NAGAR IN DIVISION-5, UNIT-2, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/3895,Buildings,Completed,NA-THIRUVOTTIYUR,5,833000,"PROPOSED CONSTRUCTION OF WELL RING COMPOSTING CENTER AT RAMAKRISHNA NAGAR, MANALI EXPRESS ROAD IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/4085,Buildings,Completed,NA-THIRUVOTTIYUR,5,846000,"PROVIDING RAIN WATER HARVESTING (RE CHARGE WELL) AT VARIOUS WATER LOGGING LOCATIONS IN DN-5,UNIT-2,Z0NE-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/4241,Parks,Completed,NA-THIRUVOTTIYUR,5,30500,"MAINTENANCE OF PARK (1.09.2019 TO 31.10.2019-2 MONTHS) AT HANSA GARDEN OSR LAND, AJAX, THIRUVOTTIYUR IN DN-5, UNIT-2, ZONE-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/4242,Parks,Completed,NA-THIRUVOTTIYUR,5,90000,"MAINTENANCE OF PARK AT SAKTHIPURAM (SRI RANGAM NEW TOWN) IN DN-5, UNIT-2, ZONE-1. (1.09.2019 TO 31.10.2019 - 2 MONTHS)",Own Sources,1,2019-20,2020-21 NA/2019-20/5177,Buildings,Completed,NA-THIRUVOTTIYUR,5,76000,"REPAIR AND IMPROVEMENTS TO COMMUNITY WELL AT CHINNA ERNAVOOR 1ST STREET IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/6038,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,33000,"DESILTING OF STORM WATER DRAIN AT MRF ROAD IN DN-5,UNIT-2,ZONE-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/6081,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,5,124000,"MINOR REPAIR TO SWD AT MRF ROAD IN DN-5, UNIT-2, ZONE-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7856,Roads,Completed,NA-THIRUVOTTIYUR,5,285000,"Attending potholes at various locations in Division 5, Unit 2, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/13518,Roads,Completed,NA-THIRUVOTTIYUR,6,2149000,"Improvement to interior BT road at Rajashanmugam Nagar 2nd street in Division 6, Unit 2, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/1770,Buildings,Completed,NA-THIRUVOTTIYUR,6,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT MANALI EXPRESS ROAD, JOTHI NAGAR IN DIVISION-6, UNIT-2, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/5458,Buildings,Completed,NA-THIRUVOTTIYUR,6,78000,"REPAIR AND IMPROVEMENTS TO COMMUNITY WELL AT SHANMUGAPURAM 1ST STREET IN DN-6, UNIT-2, ZONE-1",Own Sources,1,2019-20,2019-20 NA/2019-20/5660,Buildings,Completed,NA-THIRUVOTTIYUR,6,480000,"Providing Well ring shed at Manali Express road in Divisin 6, Unit 2, Zone I",Own Sources,1,2019-20,2019-20 NA/2019-20/6088,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,1228000,"De-Silting of SWD at Various Streets in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2019-20 NA/2019-20/6127,Buildings,Completed,NA-THIRUVOTTIYUR,6,954000,"Minor repair works to SWD and side drain in Division-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2019-20 NA/2019-20/7211,Roads,Completed,NA-THIRUVOTTIYUR,6,318000,"Attending road potholes in Kalangar nagar Main road Location in Dn-6,Unit-2,Zone-I",Own Sources,1,2019-20,2020-21 NA/2019-20/7240,Roads,Completed,NA-THIRUVOTTIYUR,6,15900,"Attending road potholes at Jothi nagar 10th and 3rd street in Dn-6, Unit-2, Zone-I",Own Sources,1,2019-20,2020-21 NA/2019-20/7242,Roads,Completed,NA-THIRUVOTTIYUR,6,119000,"Attending road potholes at Jothi nagar 4th street in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7244,Roads,Completed,NA-THIRUVOTTIYUR,6,14000,"Attending road potholes at Jothi nagar 4th cross street in Dn-6,Unit-2,Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7246,Roads,Completed,NA-THIRUVOTTIYUR,6,6200,"Attending road potholes at T.K.P nagar 2nd street in Dn-6, Unit-2, Zone-I",Own Sources,1,2019-20,2020-21 NA/2019-20/7982,Roads,Completed,NA-THIRUVOTTIYUR,6,100000,"Attending road potholes at Raja Shanmugam 9th street in Dn-6, Unit-2, Zone-I",Own Sources,1,2019-20,2020-21 NA/2019-20/7983,Roads,Completed,NA-THIRUVOTTIYUR,6,40900,"Attending road potholes at Raja Shanmugam 12th street in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7984,Roads,Completed,NA-THIRUVOTTIYUR,6,142000,"Attending road Potholes at Dr Ambedkar 7th cross and 2nd street in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7985,Roads,Completed,NA-THIRUVOTTIYUR,6,22800,"Attending road Potholes at Dr Ambedkar main road in Dn-6,Unit-2,Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7986,Roads,Completed,NA-THIRUVOTTIYUR,6,20000,"Attending road Potholes at Rajashanmugam 11 th street in Dn-6,Unit-2,Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7988,Roads,Completed,NA-THIRUVOTTIYUR,6,14000,"Attending road Potholes at Rajashanmugam 5th street in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7989,Roads,Completed,NA-THIRUVOTTIYUR,6,380000,"Attending road Potholes at Subramaniyan nagar 2nd street in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7992,Roads,Completed,NA-THIRUVOTTIYUR,6,30900,"Attending road Potholes at Jothi nagar 7th street in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7993,Roads,Completed,NA-THIRUVOTTIYUR,6,42000,"Attending road Potholes at Jothi nagar main road in Dn-6, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 L/2019-20/1111,Electrical,Completed,L-Electrical,7,942700,"Proposal for Replacement of 1501mtr. 31/2 4Cx25 sq.mm Alu. Cable in Basin Canal road near Dumbing yard at sathangadu in division-7, Zone-1 Tiruvottriyur [SOR 2017-18]",Own Sources,1,2019-20,2020-21 L/2019-20/1112,Electrical,Completed,L-Electrical,7,995000,"Proposal for Replacement of 2124mtr. 31/2 4Cx25 sq.mm Alu. Cable in Basin Canal road near Kargil nagar at sathangadu in division-7, Zone-1 Tiruvottriyur [SOR 2017-18]",Own Sources,1,2019-20,2020-21 L/2019-20/2334,Electrical,Completed,L-Electrical,7,540500,"Proposal for Providing 12 Nos. 6 Mtr. Post with Single straing bracket with 40W LED Fitting at KCP Road near Hansa Apartments in division-7, Zone-1 Tiruvottriyur [SOR 2017-18]",Own Sources,1,2019-20,2020-21 L/2019-20/5035,Electrical,Completed,Q-Solid Waste Management,7,984900,"Supply and fixing of LT Panel and MS Fabrication of LTCT EB servicing panel board with all accessories in sathankadu old dumping ground for biomining project, division-07, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/13382,Roads,Completed,NA-THIRUVOTTIYUR,7,716000,"Improvement to interior BT road at Annamalai nagar 5th street (Part) in Division 7, Unit 2, Zone 1.",Own Sources,1,2019-20,2020-21 NA/2019-20/13383,Roads,Completed,NA-THIRUVOTTIYUR,7,425000,"Improvement to interior BT road at Saravana nagar 1st street (Part) in Division 7, Unit 2, Zone 1.",Own Sources,1,2019-20,2020-21 NA/2019-20/13384,Roads,Completed,NA-THIRUVOTTIYUR,7,441000,"Improvement to interior BT road at Ramasamy nagart 4th street in Division 7, Unit 2, Zone 1.",Own Sources,1,2019-20,2020-21 NA/2019-20/13386,Roads,Completed,NA-THIRUVOTTIYUR,7,426000,"Improvement to interior BT road at Saravana nagar main road (Part) in Division 7, Unit 2, Zone 1.",Own Sources,1,2019-20,2020-21 NA/2019-20/13387,Roads,Completed,NA-THIRUVOTTIYUR,7,1136000,"Improvement to interior BT road at Hansa park road (Glass factory road) in Division 7, Unit 2, Zone 1.",Own Sources,1,2019-20,2020-21 NA/2019-20/1775,Buildings,Completed,NA-THIRUVOTTIYUR,7,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT BALAKRISHNA NAGAR MAIN ROAD IN DIVISION -7, UNIT-2, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/4386,Buildings,Completed,NA-THIRUVOTTIYUR,7,1534000,"ADDITIONAL CONSTRUCTION OF MCC 5.00MT CAPACITY AT SATHANKADU DUMPING YARD IN DN-7,UNIT-2,ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/8305,Buildings,Completed,NA-THIRUVOTTIYUR,7,997000,"PROPOSED CONSTRUCTION OF ELECTRICAL ROOM (2 NOS) FOR BIO MINING WORK AT SATHANGADU DUMPING YARD IN DN-7,UNIT-2,ZONE-1",Own Sources,1,2019-20,2021-22 NA/2019-20/8330,Roads,Completed,NA-THIRUVOTTIYUR,7,2223000,"Improvement to interior BT road at Annamalai nagar 7th street in Division 7, Unit 2, Zone 1.",Own Sources,1,2019-20,2020-21 NA/2019-20/8961,Buildings,Completed,NA-THIRUVOTTIYUR,7,996500,"Repairs and Improvements to Kargil nagar school in Div-07, Unit-02, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/9275,Buildings,Completed,NA-THIRUVOTTIYUR,7,538000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete in Division 7, Unit-2, Zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/9538,Roads,Completed,NA-THIRUVOTTIYUR,7,553000,"Providing and Laying 300mm dia C.I.and H.D. pipe for rain water collection and clearing jungle at karkil nagar bund in Division 07, Unit-02, Zone-01",Own Sources,1,2019-20,2020-21 NA/2019-20/12422,Roads,Completed,NA-THIRUVOTTIYUR,8,603000,"Improvement to the interior BT road at Vivekananda street in Div-8, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/12423,Roads,Completed,NA-THIRUVOTTIYUR,8,253000,"Improvement to the interior BT road at Anna street in Div-8, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/1791,Buildings,Completed,NA-THIRUVOTTIYUR,8,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT ENNORE EXPRESS ROAD NEAR MASTHAN KOIL IN DIVISION-8, UNIT-2, ZONE-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/7470,Roads,Completed,NA-THIRUVOTTIYUR,8,1377000,"Improvement to the interior BT road at Colony high road in Div-8, Unit-2, Zone-I.",Own Sources,1,2019-20,2020-21 NA/2019-20/7987,Roads,Completed,NA-THIRUVOTTIYUR,8,59000,"Attending Potholes at Hari street, Periyar nagar and colony high road in Division 8, Unit 2, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/9105,Buildings,Completed,NA-THIRUVOTTIYUR,8,4518000,"Improvment to existing MCC at Ennore Express road in Div-8, Unit-2, Zone-I. (Existing 7 pits, Proposed 4 pits, Total Capacity 9.19 MT)",Own Sources,1,2019-20,2021-22 NA/2019-20/9292,Buildings,Completed,NA-THIRUVOTTIYUR,8,484500,"Supply and installation of tender coconut shredder consists for 10 Hp / Three phase motor having output of 100 to 150 kgs per hour with EN-9, 8mm blade ? 40 nos with 3mm thick M.S.Body (size 1000 x 500 x 800 mm) painted complete inclusive of 18% GST etc at Ennore express road MCC centre in Div-08, Unit-02, Zone 01.",Own Sources,1,2019-20,2020-21 L/2019-20/5319,Electrical,Completed,L-Electrical,9,867200,"Removal of rust eaten and damaged street lamp posts 76 nos. and re-fixing of 76 nos. of Cast Iron E.L lamp Poles at the removal places of rust eaten and damaged poles at Tiruvottiyur kuppam, Kilijosiya nagar, etc., in division-9, Zone-1 Tiruvottriyur [SOR 2019-20]",Own Sources,1,2019-20,2019-20 L/2019-20/5320,Electrical,Completed,L-Electrical,9,949700,"Removal of rust eaten and damaged street lamp posts 76 nos. and re-fixing of 76 nos. of Cast Iron E.L lamp Poles at the removal places of rust eaten and damaged poles at Tiruvottiyur kuppam, Kilijosiya nagar, etc., in division-9, Zone-1 Tiruvottriyur [SOR 2019-20]",Own Sources,1,2019-20,2019-20 NA/2019-20/0866,Buildings,Completed,NA-THIRUVOTTIYUR,9,3120000,"Construction of Composting Yard at Thiruvottiyur Burial ground Ennore Express road in Dn-9, Unit-2, Zone-1.",Own Sources,1,2019-20,2019-20 NA/2019-20/10541,Electrical,Completed,NA-THIRUVOTTIYUR,10,350000,"Supply of 3 Phase EB Connection For Various Place at MCC In Unit-03, Zone-01.",Own Sources,1,2019-20,2021-22 NA/2019-20/1261,Buildings,Completed,NA-THIRUVOTTIYUR,10,570000,"Providing Well rings for Compostable unit at various locations in Dn-10 to Dn-14, Unit-3, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/15369,Buildings,Completed,NA-THIRUVOTTIYUR,10,538000,"Supply and fixing of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete in Division 10, Unit 3, Zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/1730,Buildings,Completed,NA-THIRUVOTTIYUR,10,216000,"PROVIDING ELECTRONIC WEIGHING WITH COUNTING SCALE GREEN LED CAPACITY 200 KG IN DIVISION- 1,2,3,4,5,6,7,10,11,12,13 & 14 UNIT-1,2 & 3, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/1734,Buildings,Completed,NA-THIRUVOTTIYUR,10,3619000,"SUPPLYING AND FIXING SHREDDING MACHINE IN VARIOUS DIVISIONS-1,3,4,6,7,8,9,10,12,13 & 14 UNIT-1,2 & 3, ZONE-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/1772,Buildings,Completed,NA-THIRUVOTTIYUR,10,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT WEST MADA STREET DIVISION-10, UNIT-03, ZONE-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/4312,Buildings,Completed,NA-THIRUVOTTIYUR,10,1332000,"Proposed for Rain Water Collecting to Thiyagarayaswami Temple Tank at North Mada Street Division-10, Unit-03, Zone-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/4313,Buildings,Completed,NA-THIRUVOTTIYUR,10,2437000,"Proposed for Rain Water Collecting to Thiyagarayaswami Temple Tank at Nellikaran Street in Division-10, Unit-03, Zone-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/7133,Buildings,Completed,NA-THIRUVOTTIYUR,10,290000,"Repair and improvement to P.C. at north sannathi street in Div-10,Unit-3,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7675,Roads,Completed,NA-THIRUVOTTIYUR,10,17800,"Restoration of Pot holes in Railway station road, Division-10,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7676,Roads,Completed,NA-THIRUVOTTIYUR,10,9000,"Restoration of Pot holes in Komatha nagar main road, Division-10,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7678,Roads,Completed,NA-THIRUVOTTIYUR,10,17800,"Restoration of Pot holes in Sadayankuppam baatai road, Division-10,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7679,Roads,Completed,NA-THIRUVOTTIYUR,10,7100,"Restoration of Pot holes in Nethaji Nagar main road, Division-10,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7680,Roads,Completed,NA-THIRUVOTTIYUR,10,10700,"Restoration of Pot holes at Poonthotam street in Division-10, Unit-3, Zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7815,Roads,Completed,NA-THIRUVOTTIYUR,10,17800,"Restoration of Pot holes in east tank road, division-10,unit-3,zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7817,Roads,Completed,NA-THIRUVOTTIYUR,10,21400,"Restoration of Pot holes in North mada street, division-10,unit-3,zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7820,Roads,Completed,NA-THIRUVOTTIYUR,10,21400,"Restoration of Pot holes in Amsa garden 1st street, division-10,unit-3,zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7833,Roads,Completed,NA-THIRUVOTTIYUR,10,17800,"Restoration of Pot holes in Amsa garden 4th street, division-10,unit-3,zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7834,Roads,Completed,NA-THIRUVOTTIYUR,10,23100,"Restoration of Pot holes in West mada street, division-10,unit-3,zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/8912,Buildings,Completed,NA-THIRUVOTTIYUR,10,178000,"Repair and Improvements Public Convenance at Poonthottam School in division-10,unit-3,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/9025,Roads,Completed,NA-THIRUVOTTIYUR,10,488000,"Paver block laying work at North mada street in division-10, unit-03, zone-01.",Own Sources,1,2019-20,2021-22 NA/2019-20/9891,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,10,185000,"Desilting of Strom Water Drain at Sannathi Street in Division-10, Unit-03, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/9899,Buildings,Completed,NA-THIRUVOTTIYUR,10,130000,"Desilting of Strom Water Drain at North Mada Street in Division-10, Unit-03, Zone-01.",Own Sources,1,2019-20,2020-21 B/2019-20/8343,Buildings,Completed,B-Buildings,11,2180000,"Supplying and Erection of Additional 15 Passanger Lift Provision for Urban community health center (100 Beds) at Thiruvotriyur in Dn-11, Zone -1.",Grants,1,2019-20,2020-21 L/2019-20/12347,Electrical,Completed,L-Electrical,11,1463100,"Provision of 26 nos. of 7 mtr G.I lamp post with Single Bracket with 40w LED fittings fittings at TNSCB Tenements at Nalla Thanner Odai Kuppam under housing for all scheme at Tiruvottiyur in Division-11, Zone-I [SOR-2019-20]",Deposit Works,1,2019-20,2020-21 NA/2019-20/10126,Parks,Completed,NA-THIRUVOTTIYUR,11,280000,"Desilting and Improvement to well in Shanmuganar Park at T.H.Road in Division-11, Unit-03, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/10936,Buildings,Completed,NA-THIRUVOTTIYUR,11,90000,"Maintenance Estimate For park at Shanmuganagar Park in Division-11, Unit-3, Zone-1,(2 Months) Area = 2900Sq.m",Own Sources,1,2019-20,2020-21 NA/2019-20/11428,Roads,Completed,NA-THIRUVOTTIYUR,11,40000,"Painting of Footpath and Auditorium for Republic Day at Zonal office in Division-11, Unit-03, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/12214,Roads,Completed,NA-THIRUVOTTIYUR,11,543000,"Improvement to interior BT road at Chinametupalayam 2nd Street in Division-11, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/12221,Roads,Completed,NA-THIRUVOTTIYUR,11,1178000,"Improvement to interior BT road at Thirupura Sundari Nagar (North & South) 2nd Street in Division-11, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/12974,Roads,Completed,NA-THIRUVOTTIYUR,11,541000,"Improvement to interior CC road at Periyametupalayam 1 c/st in Division 11, Unit 3, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/12975,Roads,Completed,NA-THIRUVOTTIYUR,11,608000,"Improvement to interior CC road at Periyametupalayam 2nd c/st in Division 11, Unit 2, Zone 1",Own Sources,1,2019-20,2020-21 NA/2019-20/1776,Buildings,Completed,NA-THIRUVOTTIYUR,11,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT ELLAIAMMAN KOIL STREET DIVISION-11 , UNIT-03, ZONE-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/4315,Buildings,Completed,NA-THIRUVOTTIYUR,11,310000,"Proposed for Rain Water Collecting to Perumal Koil Temple Tank at North Pragaram Street in Division-11, Unit-03, Zone-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/4316,Buildings,Completed,NA-THIRUVOTTIYUR,11,342000,"Proposed for Rain Water Collecting to Perumal Koil Temple Tank at Sannathi Street in Division-11, Unit-03, Zone-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/6165,Buildings,Completed,NA-THIRUVOTTIYUR,11,456000,"Proposed additional rain Water harvesting arrangements to Perumal Koil Temple Tank at Sannathi Street and North Pragaram Street in Division-11, Unit-03, Zone-01.",Own Sources,1,2019-20,2019-20 NA/2019-20/7468,Parks,Completed,NA-THIRUVOTTIYUR,11,1070000,"Abstract for Maintenance Estimate for Park at Shanmuganar Park (per year) in Div-11, Unit-3, Zone - 1 (Area-2900 Sq.m)",Own Sources,1,2019-20,2020-21 NA/2019-20/7682,Roads,Completed,NA-THIRUVOTTIYUR,11,7100,"Restoration of pot holes in Ellaiyamman koil street, Division-11,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7686,Roads,Completed,NA-THIRUVOTTIYUR,11,9000,"Restoration of pot holes in Kanakar lane, Division-11,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7687,Roads,Completed,NA-THIRUVOTTIYUR,11,10700,"Restoration of pot holes in sathyamoorthy nagar main road, Division-11,Unit-3,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7816,Roads,Completed,NA-THIRUVOTTIYUR,11,17800,"Restoration of pot holes in kailash sector-1, Division-11,Unit-3,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7818,Roads,Completed,NA-THIRUVOTTIYUR,11,21400,"Restoration of pot holes in kailash sector-2, Division-11,Unit-3,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7819,Roads,Completed,NA-THIRUVOTTIYUR,11,19600,"Restoration of pot holes in Ellaiyamman kovil extention,Division-11,Unit-3,Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7821,Roads,Completed,NA-THIRUVOTTIYUR,11,23200,"Restoring of pot holes in Sannathi street in Division-11, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7836,Roads,Completed,NA-THIRUVOTTIYUR,11,19600,"Restoration of Pot holes in Kanakar 2nd street, Division-11, Unit-3, zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/8424,Buildings,Completed,NA-THIRUVOTTIYUR,11,892000,"Repair and maintenance work at Thasildar office in division-11, unit-3, zone-1",Own Sources,1,2019-20,2021-22 NA/2019-20/8645,Buildings,Completed,NA-THIRUVOTTIYUR,11,214000,"Repair and maintenance works of PC at Sathyamurthy Nagar, Ellaiamman Koil street, Vedhachalam avenue in division-11, unit-03, zone-01.",Own Sources,1,2019-20,2021-22 BR/2019-20/15773,Roads,Completed,BR-Bus Route Roads,12,250000,"Partly relaying the road with BC after cold milling by paver finisher at Sathangadu high Road in Dn-12 , Zone - 1",Grants,1,2019-20,2020-21 NA/2019-20/12212,Roads,Completed,NA-THIRUVOTTIYUR,12,1203000,"Improvement to interior CC Road at BKN Colony 1st Street in Division-12, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/12571,Roads,Completed,NA-THIRUVOTTIYUR,12,784000,"Improvement to interior BT Road at Chetty street in Division-12, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/12572,Roads,Completed,NA-THIRUVOTTIYUR,12,860000,"Improvement to interior BT Road at BKN Colony 1st street, Division-12, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/12573,Roads,Completed,NA-THIRUVOTTIYUR,12,469000,"Improvement to interior BT road at North Pragaram street, Division-12, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/1783,Buildings,Completed,NA-THIRUVOTTIYUR,12,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT WEST MADA STREET NEAR ODIYANMANI THEATRE DIVISION-12, UNIT-03, ZONE-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/7699,Roads,Completed,NA-THIRUVOTTIYUR,12,20000,"Restoration of pot holes in Balakrishna colony 3rd street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7700,Roads,Completed,NA-THIRUVOTTIYUR,12,4100,"Restoration of pot holes in Balakrishna colony 2nd street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7701,Roads,Completed,NA-THIRUVOTTIYUR,12,939,"Restoration of pot holes in Balakrishna colony 5th street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7703,Roads,Completed,NA-THIRUVOTTIYUR,12,7100,"Restoration of pot holes in Balakrishna colony 4th street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7704,Roads,Completed,NA-THIRUVOTTIYUR,12,3800,"Restoration of pot holes in Thilagar Nagar 6th street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7708,Roads,Completed,NA-THIRUVOTTIYUR,12,1660,"Restoration of pot holes in Thilagar Nagar 5th street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7711,Roads,Completed,NA-THIRUVOTTIYUR,12,2400,"Restoration of pot holes in Thilagar Nagar 4th street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7713,Roads,Completed,NA-THIRUVOTTIYUR,12,11700,"Restoration of pot holes in Thilagar Nagar 1st street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7780,Roads,Completed,NA-THIRUVOTTIYUR,12,3900,"Restoration of pot holes in Thilagar Nagar 1st Extention street, Division-12, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7781,Roads,Completed,NA-THIRUVOTTIYUR,12,41600,"Restoration of pot holes at Sathangadu road in Division-12, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7782,Roads,Completed,NA-THIRUVOTTIYUR,12,15100,"Restoration of pot holes in New street, Division-12, Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7783,Roads,Completed,NA-THIRUVOTTIYUR,12,7100,"Restoration of pot holes in Vasantha nagar 3rd street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7785,Roads,Completed,NA-THIRUVOTTIYUR,12,6600,"Restoration of pot holes in Vasantha nagar 2nd street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7787,Roads,Completed,NA-THIRUVOTTIYUR,12,5900,"Restoration of pot holes in Vasantha nagar 1st street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7789,Roads,Completed,NA-THIRUVOTTIYUR,12,3800,"Restoration of pot holes in Ezhuthukaran street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7793,Roads,Completed,NA-THIRUVOTTIYUR,12,13200,"Restoration of pot holes in Kavarai street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7794,Roads,Completed,NA-THIRUVOTTIYUR,12,3600,"Restoration of pot holes in Vanniyar street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7795,Roads,Completed,NA-THIRUVOTTIYUR,12,9500,"Restoration of pot holes in Chetty street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7798,Roads,Completed,NA-THIRUVOTTIYUR,12,19000,"Restoration of pot holes in South Pragharam street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7800,Roads,Completed,NA-THIRUVOTTIYUR,12,19000,"Restoration of pot holes in North Pragharam street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7801,Roads,Completed,NA-THIRUVOTTIYUR,12,1100,"Restoration of pot holes in Srinivasapuram, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7803,Roads,Completed,NA-THIRUVOTTIYUR,12,4300,"Restoration of pot holes in Kumaran nagar main road, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7805,Roads,Completed,NA-THIRUVOTTIYUR,12,17100,"Restoration of pot holes in Balakrishna colony 1st street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7806,Roads,Completed,NA-THIRUVOTTIYUR,12,3900,"Restoration of pot holes in Balakrishna colony 1st cross street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/7808,Roads,Completed,NA-THIRUVOTTIYUR,12,2500,"Restoration of pot holes in Balakrishna colony 2nd street, Division-12,Unit-3, Zone-1",Own Sources,1,2019-20,2020-21 NA/2019-20/1789,Buildings,Completed,NA-THIRUVOTTIYUR,13,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT MGR ROAD DIVISION-13, UNIT-03, ZONE-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/7691,Roads,Completed,NA-THIRUVOTTIYUR,13,35600,"Restoration of Pot holes in Mettu street Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7692,Roads,Completed,NA-THIRUVOTTIYUR,13,17800,"Restoration of Pot holes in M.G.R street Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7694,Roads,Completed,NA-THIRUVOTTIYUR,13,21400,"Restoration of Pot holes in village street Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7847,Roads,Completed,NA-THIRUVOTTIYUR,13,21400,"Restoration of Pot holes in Sesachala gramani street, Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7852,Roads,Completed,NA-THIRUVOTTIYUR,13,17800,"Restoration of Pot holes in Gandhi nagar main road, Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7870,Roads,Completed,NA-THIRUVOTTIYUR,13,19600,"Restoration of Pot holes in Mettu anna street, Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7871,Roads,Completed,NA-THIRUVOTTIYUR,13,17800,"Restoration of Pot holes in Mettu 6th street, Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7872,Roads,Completed,NA-THIRUVOTTIYUR,13,21400,"Restoration of Pot holes in Varatharajan 1st street, Division-13,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/16963,Buildings,Completed,NA-THIRUVOTTIYUR,14,216000,"Repair to ICDS Center Malligapuram In Division-14, Unit-03, Zone-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/1796,Buildings,Completed,NA-THIRUVOTTIYUR,14,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITIES (MRF) AT ENNORE EXPRESS ROAD DIVISION-14, UNIT-03, ZONE-01.",Own Sources,1,2019-20,2020-21 NA/2019-20/7695,Roads,Completed,NA-THIRUVOTTIYUR,14,44700,"Restoration of Pot holes in Thiyagarayapuram main road, Division-14, unit-3, zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7696,Roads,Completed,NA-THIRUVOTTIYUR,14,21400,"Restoration of Pot holes in PPD 2nd cross street, Division-14,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7876,Roads,Completed,NA-THIRUVOTTIYUR,14,23000,"Restoration of Pot holes in Thiruchinna kuppam, Division-14,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7877,Roads,Completed,NA-THIRUVOTTIYUR,14,21500,"Restoration of Pot holes in Thiyagarayapuram 5th street, Division-14,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7878,Roads,Completed,NA-THIRUVOTTIYUR,14,17800,"Restoration of Pot holes in Thiyagarayapuram 2nd street, Division-14,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7881,Roads,Completed,NA-THIRUVOTTIYUR,14,19600,"Restoration of Pot holes in Sathananthapuram main road, Division-14,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NA/2019-20/7883,Roads,Completed,NA-THIRUVOTTIYUR,14,17800,"Restoration of Pot holes in Thiyagarayapuram 1st street, Division-14,unit-3,zone-1.",Own Sources,1,2019-20,2020-21 NB/2019-20/0399,Buildings,Completed,NB-MANALI,15,99900,"Maintenance and Providing water arrangements for hindu burial ground at manali new town 150 road in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2019-20 NB/2019-20/10062,Parks,Completed,NB-MANALI,15,946000,"MAINTENANCE WORK FOR CPS-6 PARK AT MANALI NEW MANALI NEW TOWN BLOCK 54 CPS-6 IN DN-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10072,Parks,Completed,NB-MANALI,15,613000,"MAINTENANCE OF EXISTING PARKS AT MAANALI NEW TOWN BLOCK NO 63 CPS-7 IN DN-15, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10073,Parks,Completed,NB-MANALI,15,633000,"MAINTENANCE OF EXISTING PARKS AT MANALI NEW TOWN BLOCK NO 65 CPS-8 IN DN-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10076,Parks,Completed,NB-MANALI,15,665000,"MAINTENANCE OF EXISTING PARKS AT MANALI NEW TOWN BLOCK NO 29 & 30 CPS-9 IN DN-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10079,Parks,Completed,NB-MANALI,15,1841000,"MAINTENANCE OF EXISTING PARK AT MANALI NEW TOWN BLOCK NO 26 CPS 10 IN DN-15, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10115,Storm Water Drain,Completed,NB-MANALI,15,855000,"Demolition and Reconstruction of storm water Darin Chn 70 to 140 m in at old colony 2nd street (Old nappalayam) in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2020-21 NB/2019-20/10116,Storm Water Drain,Completed,NB-MANALI,15,860000,"Demolition and Reconstruction of storm water Darin Chn 140 to 210m in at old colony 2nd street (Old nappalayam) in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2020-21 NB/2019-20/10256,Buildings,Completed,NB-MANALI,15,250000,"Repair and Improvements works for Existing Toilets at old nappalayam Public Conveniences in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/10265,Buildings,Completed,NB-MANALI,15,245000,"Repair and Improvements works for Existing Toilets at Edayanchavadi and mnali new town Public Conveniences in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/10781,Buildings,Completed,NB-MANALI,15,455000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND EAST SIDE AT MANALI NEW TOWN 42ND BLOCK (OPPOSITE TO HINDU BURIAL GROUND) IN DN-15 U-4, ZONE-02",Own Sources,2,2019-20,2021-22 NB/2019-20/10782,Buildings,Completed,NB-MANALI,15,400000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FOR OSR LAND SOUTH SIDE AT MANALI NEW TOWN 42ND BLOCK (OPPOSITE TO HINDU BURIAL GROUND) IN DN-15 U-4, ZONE-02",Own Sources,2,2019-20,2021-22 NB/2019-20/13414,Roads,Completed,NB-MANALI,15,384000,"Forming and Laying of Interior BT Road at Manali New Town 40th Block 16 feet Road 1 st street (PART) in Dn-15, U-4, Zone-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/14036,Roads,Completed,NB-MANALI,15,569000,"Forming and Laying of Interior BT Road at lakshmi nagar 2nd street 4th cross street in Dn-15, U-4, Zone-2",Own Sources,2,2019-20,2020-21 NB/2019-20/15628,Buildings,Completed,NB-MANALI,15,560000,"Supply of 100kg to 150kg Multiple Bailing Press Machine, Transportation, Erection and Commisioning, Fitting Charges, 2 coats of zinc, chrome, 2 coats of poly urethane paint including 18% GST at Manali new town 150feet Road Inside of RRC Ponit in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/1661,Buildings,Completed,NB-MANALI,15,38000,"PROVIDING OF WELL RING MULCH PIT AT NEW NAPALAYAM THULASI NAGAR IN DN-15,U-4,Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/17374,Roads,Completed,NB-MANALI,15,359000,"Forming of Interior CC Road At Gangai amman koil 1st lane (New nappalayam) part in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/1738,Buildings,Completed,NB-MANALI,15,61200,"Providing Weighing Machines for Composting Purpose at Parks in DN-15,U-4,Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/17382,Roads,Completed,NB-MANALI,15,286000,"Forming of Interior CC Road At Gangai amman koil 2nd lane (New nappalayam) in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/17383,Roads,Completed,NB-MANALI,15,268000,"Forming of Interior CC Road At Gangai amman koil 3rd lane (New nappalayam) in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/17384,Roads,Completed,NB-MANALI,15,653000,"Forming of Interior CC Road At Chinna echankuzhi 1st Lane in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/17385,Roads,Completed,NB-MANALI,15,224000,"Relaying of Interior CC Road At Gangai amman koil 1st lane (New nappalayam) in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/1864,Buildings,Completed,NB-MANALI,15,69000,"Providing water arrangements for old nappalayam vadukar palaiyam PC in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2019-20 NB/2019-20/5897,Storm Water Drain,Completed,NB-MANALI,15,230000,"Desilting and Minor Repairs To SWD and Side Drain in Various Streets in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2019-20 NB/2019-20/6667,Parks,Completed,NB-MANALI,15,165000,"PROVIDING WELL RING & MULCH PIT AT VARIOUS PARKS IN DIV-15, UNIT-4, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6669,Buildings,Completed,NB-MANALI,15,33000,"PROVIDING TO WELL RING RESOURCE RECOVERY CENTRE AT MANALI NEW TOWN 150FEET ROAD IN DIV-15, UNIT-4, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/7889,Buildings,Completed,NB-MANALI,15,337000,"Improvement and repaire works for urban primary health center at manali new town 15th main road in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2021-22 NB/2019-20/7970,Roads,Completed,NB-MANALI,15,189000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DN-15,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/8073,Buildings,Completed,NB-MANALI,15,176000,"Repair and Maintenance work for Pipe laying at Manali new town 4th main road & 10th main road in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2019-20 NB/2019-20/9193,Buildings,Completed,NB-MANALI,15,479000,"PROPOSED CONSTRUCTION OF CREMATION SHED FOR HINDU BURIAL GROUND AT MANALI NEW TOWN 150FEET ROAD IN DN-15 U-4, ZONE-02",Own Sources,2,2019-20,2020-21 NB/2019-20/9329,Buildings,Completed,NB-MANALI,15,348000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT EDAYANCHAVADI MAIN ROAD IN DN-15, U-4, Z-2",Own Sources,2,2019-20,2021-22 NB/2019-20/9331,Buildings,Completed,NB-MANALI,15,229000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT MANALI NEW TOWN IN DN-15, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/9431,Buildings,Completed,NB-MANALI,15,253000,"Providing water arrangements for Christian & Muslim burial ground at manali new town 150Feet road in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2020-21 NB/2019-20/9498,Buildings,Completed,NB-MANALI,15,387000,"Providing Toilet & Electrical arrangement for Christian & Muslim burial ground at manali new town 150Feet road in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2020-21 NB/2019-20/9543,Buildings,Completed,NB-MANALI,15,102000,"Repair and Maintenance work for Electrical work at Various Public Conveniences in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9545,Buildings,Completed,NB-MANALI,15,136000,"Repair and Maintenance work for Plumbing work at Various Public Conveniences in Dn-15, U-4, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9612,Storm Water Drain,Completed,NB-MANALI,15,950000,"Proposed construction of Side drain at Periyaechankuzhi salai (Part) in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2020-21 NB/2019-20/9963,Storm Water Drain,Completed,NB-MANALI,15,850000,"Demolition and Reconstruction of storm water Darin Chn 0 to 70 m in at old colony 2nd street (Old nappalayam) in Dn-15, U-4, Z-02.",Own Sources,2,2019-20,2020-21 L/2019-20/8363,Electrical,Completed,L-Electrical,16,18803000,"Provision of new Street lamp post in Various places at Ward-15,16&17",Grants,2,2019-20,2020-21 NB/2019-20/0362,Storm Water Drain,Completed,NB-MANALI,16,21000,"REPAIRS AND MAINTENANCE TO STORM WATER DRAIN FOR TNHB PHASE 2 60FEET ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/0371,Buildings,Completed,NB-MANALI,16,24000,"REPAIRS AND MAINTENANCE TO PUBLIC CONVENIENCE FOR KAMARAJAPURAM PERUMAL KOIL STREET IN DN-16,U-4,Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/10075,Parks,Completed,NB-MANALI,16,621000,"MAINTENANCE OF EXISTING PARK AT MANALI NEW TOWN BLOCK 134 & 135 CPS-1 IN DN-16, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10080,Parks,Completed,NB-MANALI,16,832000,"MAINTENANCE OF EXISTING PARK AT MANALI NEW TOWN BLOCK 100 & 101 CPS-2 IN DN-16, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10081,Parks,Completed,NB-MANALI,16,592000,"MAINTENANCE OF EXISTING PARK AT MANALI NEW TOWN BLOCK 90 CPS-3 IN DN-16, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10082,Parks,Completed,NB-MANALI,16,672000,"MAINTENANCE OF EXISTING PARK AT MANALI NEW TOWN BLOCK 52 CPS-4 IN DN-16, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10083,Parks,Completed,NB-MANALI,16,238000,"MAINTENANCE OF EXISTING PARK AT MANALI NEW TOWN BLOCK 78 CPS-5 IN DN-16, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10084,Parks,Completed,NB-MANALI,16,1136000,"MAINTENANCE OF EXISTING PARK AT TNHB PHASE2 BLOCK 3 PARK IN DN-16, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10234,Buildings,Completed,NB-MANALI,16,48000,"IMPROVEMENTS TO EXISTING PUBLIC CONVENIENCE (KANNIAMMANPET-2) AT KANNIAMMANPET VICHUR LINK ROAD IN DN-16,U-4,Z-2",Own Sources,2,2019-20,2021-22 NB/2019-20/10246,Buildings,Completed,NB-MANALI,16,50000,"IMPROVEMENTS TO EXISTING PUBLIC CONVENIENCE AT BURMA NAGAR BURIAL GROUND ROAD IN DN-16,U-4,Z-2",Own Sources,2,2019-20,2021-22 NB/2019-20/10247,Buildings,Completed,NB-MANALI,16,40000,"IMPROVEMENTS TO EXISTING PUBLIC CONVENIENCE AT SADAYANKUPPAM IRRULAR COLONY IN DN-16,U-4,Z-2",Own Sources,2,2019-20,2021-22 NB/2019-20/10248,Buildings,Completed,NB-MANALI,16,115000,"IMPROVEMENTS TO EXISTING PUBLIC CONVENIENCE (LADIES & GENTS TOILET) AT KAMARAJAPURAM RADHAKRISHNAN PERUMAL KOIL STREET IN DN-16,U-4,Z-2",Own Sources,2,2019-20,2021-22 NB/2019-20/10249,Buildings,Completed,NB-MANALI,16,46000,"IMPROVEMENTS TO EXISTING PUBLIC CONVENIENCE KADAPAKKAM VICHUR LINK ROAD IN DN-16,U-4,Z-2",Own Sources,2,2019-20,2021-22 NB/2019-20/13052,Roads,Completed,NB-MANALI,16,4013000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 30FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13182,Roads,Completed,NB-MANALI,16,3640000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 30FEET ROAD 1ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13183,Roads,Completed,NB-MANALI,16,2909000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 20FEET ROAD 1ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13184,Roads,Completed,NB-MANALI,16,1752000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 20FEET ROAD 2ND STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13185,Roads,Completed,NB-MANALI,16,1264000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 20FEET ROAD 3RD STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13186,Roads,Completed,NB-MANALI,16,1794000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 20FEET ROAD 4TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13187,Roads,Completed,NB-MANALI,16,913000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 1ST LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13188,Roads,Completed,NB-MANALI,16,825000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 2ND LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13189,Roads,Completed,NB-MANALI,16,543000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 3RD LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13190,Roads,Completed,NB-MANALI,16,740000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 4TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13191,Roads,Completed,NB-MANALI,16,740000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 5TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13192,Roads,Completed,NB-MANALI,16,1124000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 6TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13193,Roads,Completed,NB-MANALI,16,697000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 7TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13194,Roads,Completed,NB-MANALI,16,2041000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 40FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13195,Roads,Completed,NB-MANALI,16,2414000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 30FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13196,Roads,Completed,NB-MANALI,16,2851000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 20FEET ROAD 1ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13197,Roads,Completed,NB-MANALI,16,1457000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 20FEET ROAD 2ND STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13198,Roads,Completed,NB-MANALI,16,1764000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 16FEET ROAD 1ST LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13199,Roads,Completed,NB-MANALI,16,1525000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 16FEET ROAD 2ND LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13200,Roads,Completed,NB-MANALI,16,663000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 3RD LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13201,Roads,Completed,NB-MANALI,16,1124000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK1 16FEET ROAD 4TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13202,Roads,Completed,NB-MANALI,16,740000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 16FEET ROAD 5TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13203,Roads,Completed,NB-MANALI,16,740000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK2 16FEET ROAD 6TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13235,Roads,Completed,NB-MANALI,16,2072000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 20FEET ROAD 3RD STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13236,Roads,Completed,NB-MANALI,16,2678000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 20FEET ROAD 4TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13237,Roads,Completed,NB-MANALI,16,1144000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 1ST LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13238,Roads,Completed,NB-MANALI,16,1144000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 2ND LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13239,Roads,Completed,NB-MANALI,16,753000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 3RD LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13240,Roads,Completed,NB-MANALI,16,744000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 4TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13241,Roads,Completed,NB-MANALI,16,675000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 5TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13242,Roads,Completed,NB-MANALI,16,875000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 6TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13243,Roads,Completed,NB-MANALI,16,1144000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 7TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13244,Roads,Completed,NB-MANALI,16,1153000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE1 BLOCK5 16FEET ROAD 8TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13246,Roads,Completed,NB-MANALI,16,2821000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK1 60FEET MAIN ROAD (R1) IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13247,Roads,Completed,NB-MANALI,16,3644000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK1 60FEET MAIN ROAD (R2) IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13248,Roads,Completed,NB-MANALI,16,2214000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK1 30FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13249,Roads,Completed,NB-MANALI,16,947000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK1 20FEET ROAD 1ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13250,Roads,Completed,NB-MANALI,16,832000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK1 20FEET ROAD 2ND STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13251,Roads,Completed,NB-MANALI,16,1986000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK1 20FEET ROAD 3RD STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13252,Roads,Completed,NB-MANALI,16,2515000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK1 20FEET ROAD 4TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13253,Roads,Completed,NB-MANALI,16,5943000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK2 40FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13254,Roads,Completed,NB-MANALI,16,1665000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK4 16FEET ROAD 7TH LANE IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13255,Roads,Completed,NB-MANALI,16,6652000,"FORMING AND LAYING THE ROAD BY PAVER FINISHER AT TNHB PHASE2 BLOCK5 40FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15663,Buildings,Completed,NB-MANALI,16,998000,"PROPOSED CONSTRUCTION OF MCC POINT INSIDE RRC SHED AT MRB NAGAR MANALI NEW TOWN IN DN-16 U-4,ZONE-02.",Own Sources,2,2019-20,2021-22 NB/2019-20/15954,Roads,Completed,NB-MANALI,16,2928000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK6 40FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15955,Roads,Completed,NB-MANALI,16,2220000,"FORMING AND LAYING OF INTERIOR BT ROAD AT TNHB PHASE2 BLOCK7 40FEET MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15956,Roads,Completed,NB-MANALI,16,1652000,"FORMING AND LAYING OF INTERIOR BT ROAD AT MANALI NEW TOWN 18TH MAIN ROAD(EXTENSION) IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15957,Roads,Completed,NB-MANALI,16,457000,"FORMING AND LAYING OF INTERIOR BT ROAD AT VADIVUDAIAMMAN NAGAR IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15958,Roads,Completed,NB-MANALI,16,768000,"FORMING AND LAYING OF INTERIOR BT ROAD AT MRB NAGAR 1ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15959,Roads,Completed,NB-MANALI,16,1036000,"FORMING AND LAYING OF INTERIOR BT ROAD AT MRB NAGAR 2ND STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15960,Roads,Completed,NB-MANALI,16,1081000,"FORMING AND LAYING OF INTERIOR BT ROAD AT MRB NAGAR 3RD STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15962,Roads,Completed,NB-MANALI,16,3965000,"ROADCUT ONLY FOR INTERIOR BT ROAD AT ANDARKUPPAM MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15963,Roads,Completed,NB-MANALI,16,2602000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT KAMARAJAPURAM RADHAKRISHNAN PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15964,Roads,Completed,NB-MANALI,16,899000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT KADAPPAKKAM PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15965,Roads,Completed,NB-MANALI,16,2353000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT KULAKARAI PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15966,Roads,Completed,NB-MANALI,16,1090000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT BURMA NAGAR 1ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15967,Roads,Completed,NB-MANALI,16,1205000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT BURMA NAGAR 2ND STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15968,Roads,Completed,NB-MANALI,16,1427000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT BURMA NAGAR 3RD STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15969,Roads,Completed,NB-MANALI,16,291000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT BURMA NAGAR 9TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15970,Roads,Completed,NB-MANALI,16,250000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT BURMA NAGAR 10TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15971,Roads,Completed,NB-MANALI,16,174000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT BURMA NAGAR 11TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15972,Roads,Completed,NB-MANALI,16,2558000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT MANALI NEW TOWN 18TH MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15973,Roads,Completed,NB-MANALI,16,1278000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT MANALI NEW TOWN 79TH BLOCK 24FEET ROAD 70TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15974,Roads,Completed,NB-MANALI,16,899000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT MANALI NEW TOWN 84TH BLOCK 16FEET ROAD 71ST STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15975,Roads,Completed,NB-MANALI,16,1318000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT MANALI NEW TOWN 82TH BLOCK 16FEET ROAD 76TH STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15976,Roads,Completed,NB-MANALI,16,2061000,"ROADCUT & RELAYING OF INTERIOR BT ROAD AT VADIVUDUAMMAN NAGAR IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15977,Roads,Completed,NB-MANALI,16,453000,"ROADCUT ONLY FOR INTERIOR BT ROAD AT MANALI NEW TOWN 78TH BLOCK 40FEET 21ST MAIN ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15978,Roads,Completed,NB-MANALI,16,2880000,"FORMING AND LAYING OF INTERIOR BT ROAD AT ELANTHANOOR PERUMAL KOIL STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15979,Roads,Completed,NB-MANALI,16,3352000,"FORMING AND LAYING OF INTERIOR BT ROAD AT KADAPAKKAM VICHURE LINK ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15980,Roads,Completed,NB-MANALI,16,3111000,"ROADCUT & RELAYING OF INTERIOR CC ROAD AT KADAPAKKAM BURIAL GROUND ROAD IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15981,Roads,Completed,NB-MANALI,16,519000,"ROADCUT & RELAYING OF INTERIOR CC ROAD AT BURMA NAGAR 1ST CROSS STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15982,Roads,Completed,NB-MANALI,16,652000,"ROADCUT ONLY FOR INTERIOR CC ROAD AT BURMA NAGAR 4TH CROSS STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/15983,Roads,Completed,NB-MANALI,16,641000,"RELAYING OF INTERIOR CC ROAD AT KANNIAMMANPET GANGAIAMMAN KOIL CROSS STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2021-22 NB/2019-20/1739,Buildings,Completed,NB-MANALI,16,73500,"Providing Weighing Machines for Composting Purpose at Parks in DN-16,U-4,Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/5890,Storm Water Drain,Completed,NB-MANALI,16,260000,"DESILTING & MINOR REPAIRS OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/6387,Buildings,Completed,NB-MANALI,16,30000,"PROVIDING TO WELL RING RESOURCE RECOVERY CENTRE AT MRB NAGAR IN DIV-16, UNIT-4, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6663,Buildings,Completed,NB-MANALI,16,197000,"PROVIDING WELL RING & MULCH PIT AT VARIOUS PARKS IN DIV-16, UNIT-4, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6851,Storm Water Drain,Completed,NB-MANALI,16,594000,"CONSTRUCTION OF STORM WATER DRAIN AT KANNIAMMANPET IN DN-16 ,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/7891,Roads,Completed,NB-MANALI,16,318000,"ATTENDING PATCH WORK AT ANDARKUPPAM MAIN ROAD,TNHB PHASE1 60 FEET ROAD,KGL NAGAR MAIN ROAD AND OTHER STREET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/9021,Buildings,Completed,NB-MANALI,16,97000,"IMPROVEMENT AND REPAIRS TO ANNUAL MAINTENANCE AT MULTIPURPOSE HALL KAMARAJAPURAM IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9022,Buildings,Completed,NB-MANALI,16,116000,"IMPROVEMENT AND REPAIRS TO ANNUAL MAINTENANCE AT MULTIPURPOSE HALL ELANTHNOOR IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9029,Buildings,Completed,NB-MANALI,16,89000,"IMPROVEMENT AND REPAIRS TO ANNUAL MAINTENANCE AT DIVISION OFFICE ANDARKUPPAM REDHILLS ROAD IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9040,Buildings,Completed,NB-MANALI,16,24000,"IMPROVEMENT AND REPAIRS TO ANNUAL MAINTENANCE AT SADAYANKUPPAM AND KADAPAKKAM PUBLIC CONVENIENCE IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9041,Buildings,Completed,NB-MANALI,16,46000,"IMPROVEMENT AND REPAIRS TO ANNUAL MAINTENANCE AT BURMA NAGAR IRON BRIDGE IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9049,Buildings,Completed,NB-MANALI,16,19800,"IMPROVEMENT AND REPAIRS TO ANNUAL MAINTENANCE AT BURMA NAGAR AMMA UNAVAGAM IN DIVISION-16,UNIT-4,ZONE-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9326,Buildings,Completed,NB-MANALI,16,239000,"REPAIRS AND MAINTENANCE FOR AMMA UNAVAGAM AT ANDARKUPPAM REDHILLS ROAD (NEAR BY UNIT OFFICE -4 )IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/9328,Buildings,Completed,NB-MANALI,16,303000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM FOR BURMA NAGAR IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/9361,Playfields,Completed,NB-MANALI,16,180000,"IMPROVEMENT AND REPAIRS WORKS TO CHILDREN PLAY SPACE AT KANNIAMMANPET IN DN-16,U-4,Z-2.",Own Sources,2,2019-20,2019-20 BR/2019-20/15774,Roads,Completed,BR-Bus Route Roads,17,502000,"Partly relaying the road with BC after cold milling by paver finisher at Kosapour vadaperumpakkam Road in Dn-17, Zone - 2",Grants,2,2019-20,2020-21 NB/2019-20/0373,Storm Water Drain,Completed,NB-MANALI,17,7800,"REPAIRS AND MAINTENANCE TO CULVERT FOR VADAPERUMBAKKAM KOSAPUR LINK ROAD IN DN-17,U-4,Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/0396,Buildings,Completed,NB-MANALI,17,53000,"SUPPLYING OF JCB FOR SECTIONING OF VARIOUS BURIAL GROUNDS IN DIV - 17, U - 4, Z - 2",Own Sources,2,2019-20,2019-20 NB/2019-20/10009,Buildings,Completed,NB-MANALI,17,255000,"REPAIRS AND MAINTENANCE WORKS TO COMMUNITY HALL IN CHINNATHOPU IN DN-17, U-4, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/10039,Buildings,Completed,NB-MANALI,17,175000,"IMPROVEMENT WORKS TO COMMUNITY HALL IN CHINNATHOPU IN DN-17, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10067,Parks,Completed,NB-MANALI,17,250000,"MAINTENANCE OF EXISTING PARK AT VADAPERUMBAKKAM IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10070,Parks,Completed,NB-MANALI,17,673000,"MAINTENANCE OF EXISTING PARK AT THIRUPATHI DEVASTHANAM NAGAR IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/13360,Roads,Completed,NB-MANALI,17,977000,"Forming and Laying of interior BT Road at Ambedkar Nagar in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/13363,Roads,Completed,NB-MANALI,17,3457000,"Forming and Laying of interior BT Road at Kathakuzhi Main Road in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/13364,Roads,Completed,NB-MANALI,17,736000,"Forming and Laying of interior BT Road at Dhanalakshmi nagar 1st street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/13365,Roads,Completed,NB-MANALI,17,736000,"Forming and Laying of interior BT Road at Dhanalakshmi nagar 2nd street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/13366,Roads,Completed,NB-MANALI,17,1540000,"Relaying of interior BT Road at Thiruvalluvar salai (Kanniamman nagar) in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/15664,Buildings,Completed,NB-MANALI,17,693000,"PROPOSED CONSTRUCTION OF DRY WASTE STOCK ROOM FOR COMPOST YARD AT SAMUVEL NAGAR IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2021-22 NB/2019-20/17071,Roads,Completed,NB-MANALI,17,153000,"Forming and Laying of interior BT Road at Thanigachalam nagar 1st cross street extension in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17085,Roads,Completed,NB-MANALI,17,3566000,"Roadcut Restoration and Relaying of interior BT Road at ariyalur main road in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17086,Roads,Completed,NB-MANALI,17,7316000,"Roadcut Restoration and Relaying of interior BT Road at Theeyambakkam pillayar koil street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17087,Roads,Completed,NB-MANALI,17,5115000,"Roadcut Restoration and Relaying of interior BT Road at puzhal union road in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17104,Roads,Completed,NB-MANALI,17,822000,"Roadcut Restoration and Relaying of interior CC Road at ariyalur 3rd cross street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17105,Roads,Completed,NB-MANALI,17,727000,"Roadcut Restoration and Relaying of interior CC Road at ariyalur 2nd cross street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17106,Roads,Completed,NB-MANALI,17,651000,"Roadcut Restoration and Relaying of interior CC Road at ariyalur 1st cross street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17107,Roads,Completed,NB-MANALI,17,1739000,"Roadcut Restoration and Relaying of interior CC Road at Kathakuzhi 3rd cross street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17108,Roads,Completed,NB-MANALI,17,1620000,"Roadcut Restoration and Relaying of interior CC Road at Kathakuzhi 2nd cross street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17109,Roads,Completed,NB-MANALI,17,351000,"Forming of interior CC Road at Kathakuzhi 1st cross street extn in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17110,Roads,Completed,NB-MANALI,17,1743000,"Roadcut Restoration and Relaying of interior CC Road at Kathakuzhi 1st cross street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17117,Roads,Completed,NB-MANALI,17,815000,"Roadcut Restoration and Relaying of interior CC Road at Theeyambakkam Perumal koil street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/17119,Roads,Completed,NB-MANALI,17,579000,"Roadcut Restoration and Relaying of interior CC Road at Theeyambakkam appiamman koil street in DN-17,U-4,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/1736,Parks,Completed,NB-MANALI,17,36700,"PROVIDING WEIGHING MACHINES FOR COMPOSTING PURPOSE AT COMPOSTING YARD AND PARKS IN DN-17,U-4,Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/17402,Roads,Completed,NB-MANALI,17,2757000,"Relaying of interior CC Road at Lake view Apartment t in DN-19,U-5,Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/5701,Storm Water Drain,Completed,NB-MANALI,17,463000,"Desilting and Attending Minor Repair Works to Storm Water Drain at Various Streets In Dn - 17, U-4, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/6299,Buildings,Completed,NB-MANALI,17,617000,"IMPROVEMENT WORKS TO BURIAL GROUND AT SAMUVEL NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6625,Parks,Completed,NB-MANALI,17,66000,"PROVIDING WELL RING & MULCH PIT AT VARIOUS PARKS IN DIV-17, UNIT-4, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6670,Buildings,Completed,NB-MANALI,17,30000,"PROVIDING TO WELL RING RESOURCE RECOVERY CENTRE AT KHATHAAKUZHI IN DIV-17, UNIT-4, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/7225,Buildings,Completed,NB-MANALI,17,196000,"PROPOSED RAISING OF PIT DEPTH AT COMPOSTING SHED IN SAMUVEL NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/7403,Buildings,Completed,NB-MANALI,17,93000,"PROVISION OF WATER FACILITIES FOR VEGETATION ACTIVITIES AT COMPOSTING SHED IN SAMUVEL NAGAR IN DN-17, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/7972,Roads,Completed,NB-MANALI,17,365000,"ATTENDING PATCH WORKS AT GANDHI NAGAR AMBEDKAR NAGAR LINK ROAD IN DN-17, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/8521,Storm Water Drain,Completed,NB-MANALI,17,115000,"Repair works to culvert at Gandhi nagar ambedkar nagar link road in Dn - 17, U-4, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9017,Buildings,Completed,NB-MANALI,17,538000,"Supply of 100kg to 150kg Multiple Bailing Press Machine, Transportation, Erection and Commisioning, Fitting Charges, 2 coats of zinc, chrome, 2 coats of poly urethane paint including 18% GST at Compost Yard in samuvel nagar burial ground in Dn-17, U-4, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/9222,Storm Water Drain,Completed,NB-MANALI,17,152000,"Repair works to Road Crossing Drain at Gandhi nagar ambedkar nagar link road in Dn - 17, U-4, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9259,Buildings,Completed,NB-MANALI,17,141000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT KOSAPPUR IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/9355,Buildings,Completed,NB-MANALI,17,323000,"REPAIRS AND MAINTENANCE TO AMMA UNAVAGAM AT VADAPERUMBAKKAM IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/9901,Buildings,Completed,NB-MANALI,17,75000,"REPAIRS AND MAINTENANCE WORKS TO PUBLIC CONVENIENCE AT ANNA STREET IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/9951,Buildings,Completed,NB-MANALI,17,128000,"REPAIRS WORKS TO CORPORATION PUBLIC CONVENIENCE AT THIYAGI VISWANATHADASS NAGAR IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/9952,Buildings,Completed,NB-MANALI,17,61500,"REPAIRS WORKS TO CORPORATION PUBLIC CONVENIENCE AT SAMUVEL NAGAR, THEEYAMBAKKAM AND CHINNATHOPPU IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/9953,Buildings,Completed,NB-MANALI,17,103000,"REPAIRS WORKS TO PUBLIC CONVENIENCE AT KATHAKUZHI IN DN-17, U-4, Z-2",Own Sources,2,2019-20,2020-21 D/2019-20/9282,Storm Water Drain,Completed,D-Storm Water Drains,18,5995000,"Construction of storm water drain of size 900 x 900mm along Sir C.V Raman street from chainage 0 m to chainage 280 mts in Dn - 18,Zone - II.",MLACDS,2,2019-20,2020-21 NB/2019-20/10066,Parks,Completed,NB-MANALI,18,763781,"Maintenance works to Park at Nedunchezhiyan Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10071,Parks,Completed,NB-MANALI,18,526817,"Maintenance works to Park at Vimalapuram 2nd Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10074,Parks,Completed,NB-MANALI,18,211788,"Maintenance works to Park at CPCL 4th Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10078,Parks,Completed,NB-MANALI,18,1531072,"Maintenance works to Park at CPCL Layout in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10085,Parks,Completed,NB-MANALI,18,630891,"Maintenance works to Park at Andarkuppam Redhills High road in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10578,Buildings,Completed,NB-MANALI,18,296000,"REPAIR AND MAINTENANCE WORKS TO DIVISION OFFICE BUILDING AT NEDUNCHEZHIYAN STREET EXTN. IN DN-18, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10776,Buildings,Completed,NB-MANALI,18,763000,"CONSTRUCTION OF SUMP AND WATER TANK FOR INCINERATOR PLANT AT MGR SALAI IN DN-18, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/14606,Roads,Completed,NB-MANALI,18,1837000,"Road cut Restoration and Relaying of CC Road at Edapalayam Jeevanandham Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14607,Roads,Completed,NB-MANALI,18,1983000,"Formation of CC Road at Salaima Nagar (Part) in Dn-18, U-5, Zone-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/14608,Roads,Completed,NB-MANALI,18,1100000,"Formation of BT Road at Bharathiyar Street Manali Burial Ground Road in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14610,Roads,Completed,NB-MANALI,18,1672000,"Road cut Restoration and Relaying of BT Road at Sir CV Raman Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14611,Roads,Completed,NB-MANALI,18,1731000,"Road cut Restoration and Relaying of BT Road at Gramma Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14612,Roads,Completed,NB-MANALI,18,3665000,"Road cut Restoration and Relaying of BT Road at Thiruvalluvar Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14614,Roads,Completed,NB-MANALI,18,1009000,"Road cut Restoration and Relaying of BT Road at Thillaipuram 1st Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14616,Roads,Completed,NB-MANALI,18,1081000,"Road cut Restoration and Relaying of BT Road at Puratchikavi Bharathidasan Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14617,Roads,Completed,NB-MANALI,18,1040000,"Road cut Restoration and Relaying of BT Road at Harikrishnapuram Perumal Koil Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14618,Roads,Completed,NB-MANALI,18,894000,"Road cut Restoration and Relaying of BT Road at Harikrishnapuram Eswaran Koil Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14619,Roads,Completed,NB-MANALI,18,781000,"Road cut Restoration and Relaying of BT Road at Harikrishna Valluvar Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14620,Roads,Completed,NB-MANALI,18,1456000,"Road cut Restoration and Relaying of BT Road at Anna Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14621,Roads,Completed,NB-MANALI,18,1370000,"Road cut Restoration and Relaying of BT Road at Kalaignar Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14622,Roads,Completed,NB-MANALI,18,1127000,"Road cut Restoration and Relaying of BT Road at Edapalayam Main Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14623,Roads,Completed,NB-MANALI,18,733000,"Road cut Restoration and Relaying of BT Road at Labbaimedu Sheik Ansari Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14624,Roads,Completed,NB-MANALI,18,632000,"Road cut Restoration and Relaying of BT Road at A.F Garden Labbaimedu Street in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14629,Roads,Completed,NB-MANALI,18,1308000,"Road cut Restoration and Relaying of CC Road at Kalaignar Karunanidhi Street in Dn-18, U-5, Zone-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/14642,Roads,Completed,NB-MANALI,18,424000,"Formation of BT Road at Zaheer Hussain 2nd Street 2nd Cross Lane (Part) in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14643,Roads,Completed,NB-MANALI,18,2141000,"Formation of CC Road for Approach to Lorry Depot in Dn-20, U-5, Zone-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/14644,Roads,Completed,NB-MANALI,18,1815000,"Formation of CC Road for Approach to Zonal Office Building in Dn-20, U-5, Zone-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/14646,Roads,Completed,NB-MANALI,18,6961000,"Road cut Restoration and Relaying of CC Road at Balaraman Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14647,Roads,Completed,NB-MANALI,18,549000,"Road cut Restoration and Relaying of CC Road at Chandran Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14648,Roads,Completed,NB-MANALI,18,1143000,"Road cut Restoration and Relaying of CC Road at Rajiv Gandhi Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14649,Roads,Completed,NB-MANALI,18,2813000,"Road cut Restoration and Relaying of CC Road at Srinivasaperumal Koil Melandai Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14650,Roads,Completed,NB-MANALI,18,3109000,"Road cut Restoration and Relaying of BT Road at Srinivasa Perumal Koil Keelandai Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14651,Roads,Completed,NB-MANALI,18,1260000,"Road cut Restoration and Relaying of BT Road at Kalthottam MGR Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14652,Roads,Completed,NB-MANALI,18,619000,"Road cut Restoration and Relaying of BT Road at Raghavan 1st Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14653,Roads,Completed,NB-MANALI,18,527000,"Road cut Restoration and Relaying of BT Road at Raghavan 2nd Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14654,Roads,Completed,NB-MANALI,18,2602000,"Road cut Restoration and Relaying of BT Road at JJ Nagar in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14655,Roads,Completed,NB-MANALI,18,1523000,"Road cut Restoration and Relaying of BT Road at New MGR Nagar 2nd Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14656,Roads,Completed,NB-MANALI,18,1293000,"Road cut Restoration and Relaying of BT Road at Lalbagadhur Sastri Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14658,Roads,Completed,NB-MANALI,18,2563000,"Road cut Restoration and Relaying of BT Road at Chockammal kulam Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14659,Roads,Completed,NB-MANALI,18,1925000,"Road cut Restoration and Relaying of BT Road at Santhana Krishnan Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14660,Roads,Completed,NB-MANALI,18,674000,"Road cut Restoration and Relaying of BT Road at Santhana Krishnan 1st Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14662,Roads,Completed,NB-MANALI,18,2072000,"Road cut Restoration and Relaying of BT Road at Thamaraikulam 2nd Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/14663,Roads,Completed,NB-MANALI,18,1035000,"Road cut Restoration and Relaying of BT Road at Kamarajar Street in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/15446,Buildings,Completed,NB-MANALI,18,96000,"REPAIR AND MAINTENANCE WORKS TO THE DAMAGED TOP SLAB OF STORM WATER DRAIN AT ANBAZHAGAN STREET IN DN-18, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15448,Buildings,Completed,NB-MANALI,18,90000,"REPAIR AND MAINTENANCE WORKS TO BURIAL GROUNDS AT BHARATHIYAR STREET IN DN-18, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15449,Buildings,Completed,NB-MANALI,18,47000,"REPAIR AND MAINTENANCE WORKS TO DIVISION ASSETS IN DN-18, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15714,Buildings,Completed,NB-MANALI,18,515000,"IMPROVEMENT WORKS TO RESOURCE RECOVERY CENTRE FOR THE CONSTRUCTION OF MICRO COMPOSTING PITS AT BHARATHIYAR STREET MANALI BURIAL GROUND ROAD IN DN-18, U-5, Z-02",Own Sources,2,2019-20,2021-22 NB/2019-20/1709,Buildings,Completed,NB-MANALI,18,38000,"PROVIDING WELL RING MULCH PIT AT DIVISION OFFICE IN DN-18, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/17345,Buildings,Completed,NB-MANALI,18,354000,"Forming of Interior CC Road at Salaima Nagar 2nd Lane in Dn-18, U-05, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/1855,Buildings,Completed,NB-MANALI,18,61000,"Providing Weighing Machines for Composting Purpose at Parks and Resource Recovery Centre in Dn-18, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/4137,Buildings,Completed,NB-MANALI,18,2125000,"CONSTRUCTION OF TOILET BLOCK, BASE PLATFORM AND FLOORING FOR PROPOSED INCINERATOR PLANT AT MGR SALAI IN DN-18, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/4169,Buildings,Completed,NB-MANALI,18,2244000,"CONSTRUCTION OF OFFICE ROOM AND G.I SHEET ROOF FOR MACHINERIES FOR PROPOSED INCINERATOR PLANT AT MGR SALAI IN DN-18, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/5741,Storm Water Drain,Completed,NB-MANALI,18,757000,"Desilting, Minor Repairs and Providing Manhole Doors for Damaged Doors of Storm Water Drains at Anna Street, CPCL Layout, Edapalayam, Harikrishnapuram and Vimalapuram In Dn-18, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/5742,Storm Water Drain,Completed,NB-MANALI,18,939000,"Desilting, Minor Repairs and Providing Manhole Doors for Damaged Doors of Storm Water Drains at Various Locations In Dn-18, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/6402,Buildings,Completed,NB-MANALI,18,180000,"PROVIDING WELL RING COMPOSITION FOR RESOURCE RECOVERY CENTRE AT BHARATHIYAR STREET BURIAL GROUND AND MGR SALAI IN DN-18, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6531,Parks,Completed,NB-MANALI,18,155000,"PROVIDING WELL RING & MULCH PIT AT VARIOUS PARKS IN DIV-18, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6835,Buildings,Completed,NB-MANALI,18,46000,"REPAIR & MAINTENANCE WORKS TO VARIOUS CORPORATION ASSETS IN DN-18, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/6987,Buildings,Completed,NB-MANALI,18,1821000,"CONSTRUCTION OF COMPOUND WALL, PAVEMENT AND RAIN WATER HARVESTING INSIDE THE GASIFIER BURIAL GROUND AT MGR SALAI IN DN-18, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/7078,Electrical,Completed,NB-MANALI,18,1063000,Supply and Errection of 62.5 KVA DG Set and 1 No of 8Mtr G I Lamp Post with Hexagonal lantern carriage 3 Nos of 70-100 w LED Fittings set and Wiring for Plant shed at M G R Nagar CPCL NAGAR Burial Ground Campous in ward-18/Zone-2,Own Sources,2,2019-20,2019-20 NB/2019-20/7130,Buildings,Completed,NB-MANALI,18,1744000,"PAVING C.C ROAD FOR CAMPUS AREA, ADDITIONAL BASE PLATFORM WORKS, G.I ROOFING SHED FOR GENERATOR ROOM & PAVER BLOCK MANUFACTURING PORTION FOR INCINERATOR PLANT AT MGR SALAI IN DN-18, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/7422,Parks,Completed,NB-MANALI,18,356000,"PROVIDING PLANTATION AREA FOR INCINERATOR PLANT AT MGR SALAI IN DN-18, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/7967,Roads,Completed,NB-MANALI,18,102000,"ATTENDING PATCH WORKS FOR DAMAGED ROADS AT VARIOUS STREETS IN DN-18, U-5, Z-2.",Own Sources,2,2019-20,2020-21 B/2019-20/8344,Buildings,Completed,B-Buildings,19,2600000,"Supplying and Erection of Additional 20 Passenger Lift Provision for Urban community health center (100 Beds) at Nedunzhalian street extension road junction 200 feet in ward 19, Zone 2",Grants,2,2019-20,2020-21 L/2019-20/8366,Electrical,Completed,L-Electrical,19,4417000,"Provision of 99 nos. of 6 Mtr GI Lamp Post with Straight bracket with 40-50 Watts LED Fitting set at Arulanandam Nagar,Chinnasamy Nagar, Bharathiyar Street Extension, Sri Ram Nagar and Various locations in Div.18,19 & 21,Zone-2 (Manali), (As per 2019-20 SOR)",Grants,2,2019-20,2020-21 NB/2019-20/10091,Parks,Completed,NB-MANALI,19,253000,"MAINTENANCE WORK FOR 34TH STREET PARK IN DN-19, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10092,Parks,Completed,NB-MANALI,19,642000,"MAINTENANCE WORK FOR LAKE VIEW PARK IN DN-19, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/10094,Parks,Completed,NB-MANALI,19,2907000,"MAINTENANCE WORK FOR 2ND MAIN ROAD PARK IN DN-19, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/13359,Roads,Completed,NB-MANALI,19,1025000,ROAD CUT AND RELAYING ROAD AT MMDA 96TH STREET IN DN-19 U-05 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13535,Roads,Completed,NB-MANALI,19,380000,ROAD CUT AND RELAYING ROAD AT MMDA 90TH STREET IN DN-19 U-05 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13551,Roads,Completed,NB-MANALI,19,233000,RE-LAYING BT ROAD AT MMDA 102ND STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13552,Roads,Completed,NB-MANALI,19,269999,RE-LAYING BT ROAD AT MMDA 14TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13553,Roads,Completed,NB-MANALI,19,1426000,RE-LAYING BT ROAD AT CHINNAMATHUR EXTENSION ROAD IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13555,Roads,Completed,NB-MANALI,19,2110000,RE-LAYING BT ROAD AT ATHIKULAM STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13556,Roads,Completed,NB-MANALI,19,659000,FORMING OF BT ROAD AT APPOLO AMSTRONG NAGAR IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13802,Roads,Completed,NB-MANALI,19,908009,FORMING OF BT ROAD AT PERUMAL KOIL STREET STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13803,Roads,Completed,NB-MANALI,19,985000,FORMING OF BT ROAD AT GOKULAM STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/13804,Roads,Completed,NB-MANALI,19,680000,FORMING OF BT ROAD AT KAVITHENDRAL KALYANA SUNDHARAM NAGAR IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/1717,Buildings,Completed,NB-MANALI,19,151000,"PROVIDING WELL RING MULCH PIT AT VARIOUS LOCATIONS IN DN-19, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/17880,Roads,Completed,NB-MANALI,19,2011000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 85TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17881,Roads,Completed,NB-MANALI,19,710000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 87TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17882,Roads,Completed,NB-MANALI,19,4547000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 5TH CROSS MAIN ROAD IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17884,Roads,Completed,NB-MANALI,19,912000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 78TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17885,Roads,Completed,NB-MANALI,19,1159000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 24TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17887,Roads,Completed,NB-MANALI,19,2012000,ROAD CUT AND RE-LAYING BT ROAD AT MMDA 15TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17888,Roads,Completed,NB-MANALI,19,579000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 88TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17889,Roads,Completed,NB-MANALI,19,686000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 107TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17890,Roads,Completed,NB-MANALI,19,1357000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 77TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17891,Roads,Completed,NB-MANALI,19,695000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 58TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17892,Roads,Completed,NB-MANALI,19,686000,ROAD CUT AND RE-LAYING OF BT ROAD AT MMDA 61ST STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/17894,Roads,Completed,NB-MANALI,19,645000,ROADCUT AND RE-LAYING OF BT ROAD AT MMDA 121TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/18004,Roads,Completed,NB-MANALI,19,1445000,ROADCUT AND RE-LAYING OF BT ROAD AT ARULANDANAGAR 2ND CROSS STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18005,Roads,Completed,NB-MANALI,19,2064000,ROADCUT AND RE-LAYING OF BT ROAD AT ALAMARAM STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/18006,Roads,Completed,NB-MANALI,19,588000,ROADCUT AND RE-LAYING OF BT ROAD AT PALANI STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/18007,Roads,Completed,NB-MANALI,19,1240000,ROADCUT AND RE-LAYING OF BT ROAD AT BHARATHI NAGAR 4TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18008,Roads,Completed,NB-MANALI,19,1073000,ROADCUT AND RE-LAYING OF BT ROAD AT BHARATHI NAGAR 3RD STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18009,Roads,Completed,NB-MANALI,19,1086000,ROADCUT AND RE-LAYING OF BT ROAD AT BHARATHI NAGAR 2ND STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18010,Roads,Completed,NB-MANALI,19,1102000,ROADCUT AND RE-LAYING OF BT ROAD AT BHARATHI NAGAR 1ST STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18011,Roads,Completed,NB-MANALI,19,2641000,ROADCUT AND RE-LAYING OF BT ROAD AT APPOLLO AMSTRONG NAGAR 3RD STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18012,Roads,Completed,NB-MANALI,19,1682000,ROADCUT AND RE-LAYING OF BT ROAD AT APPOLLO AMSTRONG NAGAR 2ND STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18013,Roads,Completed,NB-MANALI,19,1990000,ROADCUT AND RE-LAYING OF BT ROAD AT APPOLLO AMSTRONG NAGAR 4TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/18014,Roads,Completed,NB-MANALI,19,1089000,ROADCUT AND RE-LAYING OF BT ROAD AT APPOLLO AMSTRONG NAGAR 1ST STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/18016,Roads,Completed,NB-MANALI,19,2904000,ROADCUT AND RE-LAYING OF BT ROAD AT MMDA 59TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2021-22 NB/2019-20/18020,Roads,Completed,NB-MANALI,19,1621000,ROADCUT AND RE-LAYING OF BT ROAD AT MMDA 109TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18021,Roads,Completed,NB-MANALI,19,795000,ROADCUT AND RE-LAYING OF BT ROAD AT ARULANDHA NAGAR 3RD STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18023,Roads,Completed,NB-MANALI,19,2397000,ROADCUT AND RE-LAYING OF BT ROAD AT PERUMAL KOIL STREET (Chinnamathur) IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/18024,Roads,Completed,NB-MANALI,19,1396000,ROADCUT AND RE-LAYING OF BT ROAD AT ARULANDANAGAR 1ST CROSS STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/1834,Buildings,Completed,NB-MANALI,19,61000,"Providing Weighing Machines for Composting Purpose at Parks, Compost Yard and Resource Recovery Centre in Dn-19, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/5030,Roads,Completed,NB-MANALI,19,300000,PROVIDING RAINWATER HARVESTING TO COMMUNITY WELL IN VARIOUS PLACE IN DN-19 U-5Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/5940,Roads,Completed,NB-MANALI,19,1858000,RE-LAYING OF BT ROAD AT M.G.R SALAI IN DN-19 U-05 Z-02,Own Sources,2,2019-20,2019-20 NB/2019-20/6073,Storm Water Drain,Completed,NB-MANALI,19,760000,IMPROVEMENT OF STORM WATER DRAIN DESILTING OF VARIOUS STREET IN DN-19 U-05 ZN-02,Own Sources,2,2019-20,2019-20 NB/2019-20/6535,Parks,Completed,NB-MANALI,19,91000,"PROVIDING WELL RING & MULCH PIT AT VARIOUS PARKS IN DIV-19, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6683,Buildings,Completed,NB-MANALI,19,157000,"PROVIDING WELL RINGS FOR RESOURCE RECOVERY CENTRE AT KOSAPUR AND MGR SALAI IN DN-19, U-5. Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/7442,Roads,Completed,NB-MANALI,19,799935,IMPROVEMENT COMMUNITY WELL AT VARIOUS STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2019-20 NB/2019-20/7471,Buildings,Completed,NB-MANALI,19,198000,RISING OF COMPOSED TUBS IN COMPOSED YARD AT ARULANDAM NAGAR IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/7964,Roads,Completed,NB-MANALI,19,224000,ATTENDING THE PATCHWORK FOR DAMAGE ROAD AT VARIOUS STREET IN DN-19 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/8917,Buildings,Completed,NB-MANALI,19,538000,"SUPPLY OF 100KG TO 150KG MULTIPLE BAILING PRESS MACHINE ,TRANAPORATION,ERECTION ,AND COMMISSIONING,FITTING CHARGES 2 COAT OF ZINC ,CHROME,2COAT OF POLY URETHANE PAINT INCLUDING 18% GST AT KOSAPUR RRC CENTRE IN DN-19 ,U-05,Z-02",Own Sources,2,2019-20,2020-21 NB/2019-20/10087,Parks,Completed,NB-MANALI,20,624637,"Maintenance works to Lake View Park at Chinnamathur Salai in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/11357,Buildings,Completed,NB-MANALI,20,244000,"REPAIR AND MAINTENANCE WORKS TO ZONAL OFFICE-II BUILDING AT KAMARAJAR SALAI IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/15634,Buildings,Completed,NB-MANALI,20,560000,"Supply of 100kg to 150kg Multiple Bailing Press Machine, Transportation, Erection and Commisioning, Fitting Charges, 2 coats of zinc, chrome, 2 coats of poly urethane paint including 18% GST in RRC Point inside Burial Ground at Srinivasa Perumal Koil Street in Dn-20, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/1701,Buildings,Completed,NB-MANALI,20,113000,"PROVIDING WELL RING MULCH PIT AT VARIOUS LOCATIONS IN DN-20, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/1735,Buildings,Completed,NB-MANALI,20,12200,"Providing Weighing Machines for Composting Purpose at Parks in Dn-20, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/2937,Buildings,Completed,NB-MANALI,20,57000,"REPAIR AND MAINTENANCE WORKS AT CORPORATION BUILDINGS IN DIVISION-20, UNIT-5, ZONE-2",Own Sources,2,2019-20,2019-20 NB/2019-20/3881,Buildings,Completed,NB-MANALI,20,1927000,"CLEARING GARBAGES FROM TIPPING PLATFORM (TPF) TO KODUNGAIYUR DUMPING GROUND (KDG) AT KAMARAJAR SALAI IN DN-20, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/5747,Storm Water Drain,Completed,NB-MANALI,20,665000,"Desilting, Minor Repairs and Providing Manhole Doors for Damaged Doors of Storm Water Drains at Kamarajar Salai, Chinnamathur Salai, MGR Nagar, Lalbagadhur Sasthri Nagar and Srinivasa Perumal Koil Street In Dn-20, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/5748,Storm Water Drain,Completed,NB-MANALI,20,642000,"Desilting, Minor Repairs and Providing Manhole Doors for Damaged Doors of Storm Water Drains at Various Locations In Dn-20, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/6401,Buildings,Completed,NB-MANALI,20,137000,"PROVIDING WELL RING COMPOSITION FOR RESOURCE RECOVERY CENTRE AT SRINIVASA PERUMAL KOIL STREET IN DN-20, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6532,Parks,Completed,NB-MANALI,20,39000,"PROVIDING WELL RING & MULCH PIT AT CHINNAMATHUR PARK IN DIV-20, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6836,Buildings,Completed,NB-MANALI,20,22000,"REPAIR & MAINTENANCE WORKS TO VARIOUS CORPORATION ASSETS IN DN-20, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/7874,Buildings,Completed,NB-MANALI,20,370000,"IMPROVEMENT WORKS TO AMMA UNAVAGAM AT KAMARAJAR SALAI (NEAR FIRE SERVICE STATION) IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/7922,Buildings,Completed,NB-MANALI,20,128000,"IMPROVEMENT WORKS TO AMMA UNAVAGAM AT KAMARAJAR SALAI (NEAR MANALI LAKE) IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/7966,Roads,Completed,NB-MANALI,20,194000,"ATTENDING PATCH WORKS FOR DAMAGED ROADS AT VARIOUS STREETS IN DN-20, U-5, Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/9892,Buildings,Completed,NB-MANALI,20,241000,"REPAIR AND MAINTENANCE WORKS TO ZONAL OFFICE BUILDING AND LORRY DEPOT INSIDE THE OFFICE CAMPUS AT KAMARAJAR SALAI IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/9893,Buildings,Completed,NB-MANALI,20,90000,"REPAIR AND MAINTENANCE WORKS TO BURIAL GROUND AT SRINIVASA PERUMAL KOIL STREET IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2019-20 BR/2019-20/5117,Roads,Completed,BR-Bus Route Roads,21,13056000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Neduncheziyan Street & Extn in Dn-21, Zone - II",Grants,2,2019-20,2020-21 NB/2019-20/10100,Parks,Completed,NB-MANALI,21,631000,"Maintenance works to Jalagandamariamman Koil Street Park in Dn-21, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10262,Electrical,Completed,NB-MANALI,21,31000,"REPAIR AND MAINTANANCE TO AMMA UNAVAGAM (PART) AT PADASALAI STREET IN DN-21, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/10282,Buildings,Completed,NB-MANALI,21,32000,"REPAIR AND MAINTANANCE TO AMMA UNAVAGAM AT JALAGANDAMARIAMMAN KOVIL STREET IN DN-21, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/1721,Buildings,Completed,NB-MANALI,21,76000,"PROVIDING WELL RING MULCH PIT AT VARIOUS LOCATIONS IN DN-21, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/1831,Buildings,Completed,NB-MANALI,21,12200,"Providing Weighing Machines for Composting Purpose at Parks in Dn-21, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/2882,Buildings,Completed,NB-MANALI,21,72000,"REPAIR AND MAINTENANCE WORKS AT CORPORATION BUILDINGS IN DIVISION-21, UNIT-5, ZONE-2",Own Sources,2,2019-20,2019-20 NB/2019-20/2941,Buildings,Completed,NB-MANALI,21,179000,Improvements to Anganwadi No:110 at Dr. Ambedkhar Street in Manali Dn21 Unit5 Zone2,Own Sources,2,2019-20,2019-20 NB/2019-20/6148,Storm Water Drain,Completed,NB-MANALI,21,932000,"Name of Work: Desilting ,Minor Repairs And Manhole door of Storm Water Drains at Various Streets Interior route Road InDn-21, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/6150,Storm Water Drain,Completed,NB-MANALI,21,371000,"Desilting ,Minor Repairs And Manhole door of Storm Water Drains at Various Street Bus route Road InDn-21, U-5, Z-2.",Own Sources,2,2019-20,2019-20 NB/2019-20/6539,Parks,Completed,NB-MANALI,21,41000,"PROVIDING WELL RING & MULCH PIT INSIDE PARK AT JALAGANDAMARIAMMAN KOIL STREET IN DIV-21, UNIT-5, ZONE-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/6744,Buildings,Completed,NB-MANALI,21,76000,PROVIDING WELL RINGS FOR RESOURCE RECOVERY SABAPTHY STREET DN-21 U-5 Z-02,Own Sources,2,2019-20,2020-21 NB/2019-20/7277,Roads,Completed,NB-MANALI,21,69000,"REPAIR AND MAINTANANCE FOR EVR STREET ROAD RAMP IN DN-21, U-5, Z-2,",Own Sources,2,2019-20,2019-20 NB/2019-20/7628,Buildings,Completed,NB-MANALI,21,9300,"REPAIR AND MAINTANANCE FOR VARIOUS CORPORATION ASSET IN DN-21, U-5, Z-2",Own Sources,2,2019-20,2019-20 NB/2019-20/7977,Roads,Completed,NB-MANALI,21,182000,"ATTENDING THE PATCH WORK FOR DAMAGED ROAD IN Dn-21,U-5,Z-2.",Own Sources,2,2019-20,2020-21 NB/2019-20/8007,Buildings,Completed,NB-MANALI,21,244000,"IMPROVEMENTS TO UPHC AT NEDUNCHEZHIAN STREET,MANALI IN DN-21, U-5, Z-2",Own Sources,2,2019-20,2020-21 NB/2019-20/8114,Buildings,Completed,NB-MANALI,21,176000,"PROVIDING RAIN WATER DRAIN FACILITIES FOR LOW LAYING AREA AT JUNCTION OF PADASALAI STREET AND KAMARAJAI SALAI TO Dr. AMBEDKAR STREET IN DN-21,U-5,Z-2,",Own Sources,2,2019-20,2019-20 BR/2019-20/3880,Road Cut,Completed,BR-Bus Route Roads,22,2450000,RESTORATION OF ROADCUT LAYING BC40MM AT MADHAVARAM MILK COLONY ROAD (FROM MRH ROAD TO AAVIN DIARY FARM) AGAINST CHALLAN NO-BR/2017-18/0021126 IN DN. 30 & 31 IN ZONE- 3,Deposit Works,3,2019-20,2020-21 NC/2019-20/10749,Buildings,Completed,NC-MADHAVARAM,22,209000,"ADDITIONAL DAMAGED ROAD AT THANIKACHALAM NAGAR C BLOCK MAIN ROAD PART IN DIV-33, UNIT-8, ZONE - 3",Grants,3,2019-20,2021-22 NC/2019-20/10968,Buildings,Completed,NC-MADHAVARAM,22,19000,"Repairs and Maintenance to Amma Unavagam at Valluvar street in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10969,Buildings,Completed,NC-MADHAVARAM,22,88000,"Repairs and Maintenance to Burial Ground at K.S.Nagar main Street in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10979,Buildings,Completed,NC-MADHAVARAM,22,85000,"Repairs and Maintenance to Burial Ground at Kannadapalayam in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10980,Buildings,Completed,NC-MADHAVARAM,22,41000,"Repairs And Maintenance To Urban Primary Health Centre In Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10982,Buildings,Completed,NC-MADHAVARAM,22,15000,"Repairs and Maintenance to Anganvadi at Jeeva Main Street in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10984,Buildings,Completed,NC-MADHAVARAM,22,27000,"Repairs and Maintenance to Multipurpose Hall at K.S.Nagar 26th Street in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10985,Buildings,Completed,NC-MADHAVARAM,22,53000,"Repairs And Maintenance To Multipurpose Hall At Ko.Su.Mani Street In Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10986,Buildings,Completed,NC-MADHAVARAM,22,107000,"Providing and Fixing Street Name Board at K.S.Nagar 24th street, K.S.Nagar 24th 1st cr street,K.S.Nagar 24th 2nd cr street & K.S.Nagar 24th 3rs cr street in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/10987,Buildings,Completed,NC-MADHAVARAM,22,16000,"Repairs and Maintenance to P.C at Subash Chandra Bose Street in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/11519,Roads,Completed,NC-MADHAVARAM,22,413000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 1st Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11590,Roads,Completed,NC-MADHAVARAM,22,691000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 2nd Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11596,Roads,Completed,NC-MADHAVARAM,22,832000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 2nd Cross Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11600,Roads,Completed,NC-MADHAVARAM,22,1450000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 3rd Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11602,Roads,Completed,NC-MADHAVARAM,22,551000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 4th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11603,Roads,Completed,NC-MADHAVARAM,22,410000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 5th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11604,Roads,Completed,NC-MADHAVARAM,22,827000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 6th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11605,Roads,Completed,NC-MADHAVARAM,22,929000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 7th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11606,Roads,Completed,NC-MADHAVARAM,22,710000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 8th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11607,Roads,Completed,NC-MADHAVARAM,22,706000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 9th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11608,Roads,Completed,NC-MADHAVARAM,22,459000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 10th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11609,Roads,Completed,NC-MADHAVARAM,22,477000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 11th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11610,Roads,Completed,NC-MADHAVARAM,22,435000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 12th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11611,Roads,Completed,NC-MADHAVARAM,22,734000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 14th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11612,Roads,Completed,NC-MADHAVARAM,22,642000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 15th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11614,Roads,Completed,NC-MADHAVARAM,22,1120000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 16th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11615,Roads,Completed,NC-MADHAVARAM,22,202000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 19th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11616,Roads,Completed,NC-MADHAVARAM,22,658000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 20th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11617,Roads,Completed,NC-MADHAVARAM,22,1166000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 21st Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11618,Roads,Completed,NC-MADHAVARAM,22,1631000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 22nd Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11619,Roads,Completed,NC-MADHAVARAM,22,538000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 22nd Cross Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11620,Roads,Completed,NC-MADHAVARAM,22,624000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 23rd Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11622,Roads,Completed,NC-MADHAVARAM,22,600000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 24th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11623,Roads,Completed,NC-MADHAVARAM,22,594000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 25th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11624,Roads,Completed,NC-MADHAVARAM,22,343000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 26th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11625,Roads,Completed,NC-MADHAVARAM,22,300000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 27th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11626,Roads,Completed,NC-MADHAVARAM,22,245000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 28th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11627,Roads,Completed,NC-MADHAVARAM,22,811000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 29th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11628,Roads,Completed,NC-MADHAVARAM,22,783000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 30th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11631,Roads,Completed,NC-MADHAVARAM,22,753000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 31st Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11632,Roads,Completed,NC-MADHAVARAM,22,1034000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 32nd Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11633,Roads,Completed,NC-MADHAVARAM,22,379000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 33rd Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11634,Roads,Completed,NC-MADHAVARAM,22,691000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 34th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11635,Roads,Completed,NC-MADHAVARAM,22,1421000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 35th Street (Krishna Nagar) In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11636,Roads,Completed,NC-MADHAVARAM,22,795000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 36th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11637,Roads,Completed,NC-MADHAVARAM,22,624000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 37th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11638,Roads,Completed,NC-MADHAVARAM,22,997000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 38th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11639,Roads,Completed,NC-MADHAVARAM,22,1849000,"Strengthening and Relaying of BT Road at Sakthivel Nagar 39th Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/11640,Roads,Completed,NC-MADHAVARAM,22,1321000,"Strengthening and Relaying of BT Road at Mahalakshmi Nagar Main Street In Div- 22,Unit-6,Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/12947,Buildings,Completed,NC-MADHAVARAM,22,1230500,"Operation and Maintenance of High Quality Treated Drinking Water Plant ( RO/UV Filtration of 2000 litres / Hours Capacity For 1 Year Period at Gandhi Main Road in Division-22, Unit-6, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/12971,Roads,Completed,NC-MADHAVARAM,22,113000,"Providing and Fixing Street Name Board at Mercy Nagar, Mercy Nagar 1st Street, Mercy Nagar 2nd Street, Mercy Nagar 3rd Street in Division-22, Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/1566,Buildings,Completed,NC-MADHAVARAM,22,230000,"PROVIDING WELL RINGS & CONSTRUCTION OF MULCH PITS AT VARIOUS STREETS IN DN-22, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2100,Buildings,Completed,NC-MADHAVARAM,22,710000,"PROVIDING WEIGHING MECHINE & VEGITABLE SHREDDER MECHINE AT VARIOUS STREET IN DIVISION -22 & 23, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2563,Parks,Completed,NC-MADHAVARAM,22,234000,"Maintenance Estimate for Park at Macro Marvel 2nd cross street Park in Dn-22, Unit-6, Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/4151,Buildings,Completed,NC-MADHAVARAM,22,250000,"REPAIR AND IMPROVEMENTS TO ANGANVADI CENTRE AT KANNAPPASWAMY NAGAR 6TH STREET CENTRE NO-202 IN DIVISION-22,UNIT-6,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4167,Buildings,Completed,NC-MADHAVARAM,22,250000,"PROPOSED CONSTRUCTION OF BABY FRIENDLY TOILET TO ANGANVADI CENTRE NO-216 AT GANDHI 1ST STREET IN DIVISION-22,UNIT-6,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4176,Buildings,Completed,NC-MADHAVARAM,22,165000,"REPAIRS AND IMPROVEMENTS TO ANGANVADI CENTRE NO-211 AT PERUMAL KOIL STREET IN DIVISION-22,UNIT-6,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4613,Buildings,Completed,NC-MADHAVARAM,22,75000,"Converting to Rain Water Harvesting Purpose for the Existing Unused Community Well at Gurushanthi Nagar 2nd Street ( park ) in Dn-22, Unit-6,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/4616,Buildings,Completed,NC-MADHAVARAM,22,120000,"Converting to Rain Water Harvesting Purpose for the Existing Unused Community Well at Gandhi 1st Street ( inside of Division Office) in Dn-22, Unit-6,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/5945,Storm Water Drain,Completed,NC-MADHAVARAM,22,634000,"Desilting of Storm Water Drain at Various Streets in Division-22, Unit-6, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6386,Buildings,Completed,NC-MADHAVARAM,22,75000,"Converting to Rain Water Harvesting Purpose for the Existing Unused Community Well at Kannadapalayam inside of Burial Ground in Dn-22, Unit-6,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/6635,Parks,Completed,NC-MADHAVARAM,22,577000,"Maintenance Estimate for Park at Gurusanthi nagar Park in Dn-22, Unit-6, Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/6778,Buildings,Completed,NC-MADHAVARAM,22,500000,"SUPPLING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT KANNAPPASAMY NAGAR IN DIV-22,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/6780,Buildings,Completed,NC-MADHAVARAM,22,500000,"SUPPLING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT GANDHIMAIN ROAD IN DIV-22,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/7527,Roads,Completed,NC-MADHAVARAM,22,633000,"Providing Speed Breakers at Macro Marvel Main Road, Sakthivel Nagar 1st Main Road,Sakthivel Nagar 2nd Main Road, Thiruneelagander Nagar Main Road, Mariyammal Nagar Main Road, K.S.Nagar 28th Street ( Yago Flat ) and K.S.Nagar 6th Street in Ward-22, Unit-6, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8191,Roads,Completed,NC-MADHAVARAM,22,535000,"Attending Cement Concrete Patch works by RMC M20 at various streets in Ward-22, Unit-6, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/8885,Parks,Completed,NC-MADHAVARAM,22,600000,"Maintenance Estimate for Park at Macro Marvel 1st cross street Park in Dn-22, Unit-6, Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/8889,Buildings,Completed,NC-MADHAVARAM,22,538000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete at Kannadapalayam RRC centre jeeva main street in Division 22, Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/9380,Parks,Completed,NC-MADHAVARAM,22,622000,"Maintenance Estimate for Park at Macro Marvel Park Phase -III at 3rd cross street in Dn-22, Unit-6, Zone-3",Own Sources,3,2019-20,2020-21 L/2019-20/8168,Electrical,Completed,L-Electrical,23,35234500,"Provision of 212 Nos of 6mtr lamp post, single straight bracket with 40w LED fitting at Vegetarian village, Britania Nagar, 15 Nos of 6mtr lamppost with 90w LED fitting at KS Nagar 40 feet road, 34 Nos of 8mtr straight bracket with 150w LED fitting at Nagappa Estate, 50 Nos of 8mtr Octogonal post with Single bracket with 150w LED fitting & 132 Nos of 8mtr Octogonal post with double arch bracket with 150w LED fitting at Ambattur Road in Div-22,23,24 & 25 of Zone-III (Madhavaram)",Grants,3,2019-20,2020-21 NC/2019-20/10950,Buildings,Completed,NC-MADHAVARAM,23,266000,"Repairs and Maintenance to Vermi Compost Yard at G.N.T Service Road in DN-23, Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/10951,Buildings,Completed,NC-MADHAVARAM,23,110000,"Repairs to PC at Rettamalai srinivasan street and Gangatharan street in DN-23, Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/12664,Buildings,Completed,NC-MADHAVARAM,23,157000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO OSR LAND (GALAXY) & URBAN FOREST AT GNT SERVICE ROAD IN DN-23, UNIT-06, ZONE-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/12665,Buildings,Completed,NC-MADHAVARAM,23,44000,"PROVIDING COMPOST DRYER PLATFORM FOR VERMI COMPOST YARD AT GNT SERVICE ROAD IN DN-23, UNIT-06, ZONE-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/14341,Buildings,Completed,NC-MADHAVARAM,23,520000,"CONSTRUCTION OF BABY FRIENDLY TOILET AND WATER FACILITY FOR NNMP SHED ( CENTER NO: 33603140201) ANNA NINAIVU NAGAR 7H STREET IN DIVISION-23, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/14343,Buildings,Completed,NC-MADHAVARAM,23,351000,"CONSTRUCTION OF BABY FRIENDLY TOILET FOR NNMP SHED ( CENTER NO: 33603140207) CYCLE SHOP, METTU STREET IN DIVISION-23,UNIT-6, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/14344,Buildings,Completed,NC-MADHAVARAM,23,520000,"CONSTRUCTION OF BABY FRIENDLY TOILET AND WATER FACILITY FOR NNMP SHED ( CENTER NO: 33603140209 ) GANGADARAN STREET IN DIVISION-23, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2021-22 NC/2019-20/14345,Buildings,Completed,NC-MADHAVARAM,23,380000,"CONSTRUCTION OF BABY FRIENDLY TOILET AND WATER FACILITY FOR NNMP ( CENTER NO: 33603140204) SHED LAKSHMI AMMAN KOIL STREET IN DIVISION-23,UNIT-6, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/1610,Buildings,Completed,NC-MADHAVARAM,23,246000,"PROVIDING WELL RINGS & CONSTRUCTION OF MULCH PITS AT VARIOUS STREETS IN DN-23, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4595,Buildings,Completed,NC-MADHAVARAM,23,75000,"Converting to Rain Water Harvesting Purpose for the Existing Unused Community Well at Gangadharan Main Street in Dn-23, Unit-6,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/4596,Buildings,Completed,NC-MADHAVARAM,23,75000,"Converting to Rain Water Harvesting Purpose for the Existing Unused Community Well at Thiruveethi Amman Koil Street in Dn-23, Unit-6,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/4597,Buildings,Completed,NC-MADHAVARAM,23,75000,"Converting to Rain Water Harvesting Purpose for the Existing Unused Community Well at Thiruvalluvar 1st Street in Dn-23, Unit-6,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/5950,Storm Water Drain,Completed,NC-MADHAVARAM,23,377000,"Desilting of Storm Water Drain at Various Streets in Division-23, Unit-6, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6055,Buildings,Completed,NC-MADHAVARAM,23,1130000,"Construction of Cam Shredder Room at G.N.T Service Road in Division-23,Unit-6,Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/7848,Buildings,Completed,NC-MADHAVARAM,23,400000,"IMPROVEMENTS TO VERMI COMPOST YARD AT G.N.T SERVICE ROAD IN DIVISION-23, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/7850,Buildings,Completed,NC-MADHAVARAM,23,950000,"IMPROVEMENTS FOR VERMI COMPOST YARD AT VEGITABLE CUTTING AND SIEVING MACHINE PLACE AT G.N.T SERVICE ROAD IN WARD-23, UNIT-6, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/7887,Buildings,Completed,NC-MADHAVARAM,23,925000,"IMPROVEMENTS TO VERMI COMPOST YARD ROOF SHEET AND PROVIDING THERMOCOL FALL CELING WORK AT G.N.T SERVICE ROAD IN DIVISION-23, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8128,Roads,Completed,NC-MADHAVARAM,23,140000,"Attending patch work at various street in Dn-23,Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8701,Buildings,Completed,NC-MADHAVARAM,23,557000,"CONSTRUCTION OF NEW COMPOUND WALL IN DIVISION-23 OFFICE INBETWEEN URBAN COMMUNITY HOSPITAL AT G.N.T ROAD IN DN-23, UNIT-6,ZONE-3.",Own Sources,3,2019-20,2020-21 P/2019-20/7531,Parks,Completed,P-Parks and Playfields,23,4981648,"Formation of New Park at V S Mani Nagar 3rd Street, park-3 (Northern Side) in Division - 23 ZONE - III",Grants,3,2019-20,2020-21 L/2019-20/9207,Electrical,Completed,L-Electrical,24,95800,"Work-Replacement of 3 Nos. of Rusted, Damaged Kiosk Pillar Box by New Kiosk Pillar Box at Various Locations in Kathir vedu Section ,divisions 24 & 25 in ZONE-III.",Own Sources,3,2019-20,2021-22 NC/2019-20/0852,Roads,Completed,NC-MADHAVARAM,24,4999000,"Laying of BT road at Sivaprakasam nagar (north) in division-24,unit-6, zone-3.",MLACDS,3,2019-20,2020-21 NC/2019-20/10832,Roads,Completed,NC-MADHAVARAM,24,11400000,"FORMATION OF BT ROAD AT BRITTANIA NAGAR MAIN ROAD IN DIVISION-24,UNIT-6,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/11700,Roads,Completed,NC-MADHAVARAM,24,1085000,"Improvements to Existing BT Road at Geetha nagar 1st street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11935,Roads,Completed,NC-MADHAVARAM,24,263000,"Improvements to Existing BT Road at Geetha nagar 2nd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11936,Roads,Completed,NC-MADHAVARAM,24,840000,"Improvements to Existing BT Road at sivaji nagar In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11937,Roads,Completed,NC-MADHAVARAM,24,632000,"Improvements to Existing BT Road at Ganesh nagar In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11938,Roads,Completed,NC-MADHAVARAM,24,286000,"Improvements to Existing BT Road at sarathi nagar extn. 6th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11939,Roads,Completed,NC-MADHAVARAM,24,1821000,"Improvements to Existing BT Road at sarathi nagar extn. 7th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11940,Roads,Completed,NC-MADHAVARAM,24,1018000,"Improvements to Existing BT Road at sarathi nagar extn. 8th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11941,Roads,Completed,NC-MADHAVARAM,24,937000,"Improvements to Existing BT Road at Janki ram nagar 1st street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11942,Roads,Completed,NC-MADHAVARAM,24,1337000,"Improvements to Existing BT Road at Janki ram nagar 2nd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11943,Roads,Completed,NC-MADHAVARAM,24,317000,"Improvements to Existing BT Road at Janki ram nagar 3rd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11944,Roads,Completed,NC-MADHAVARAM,24,605000,"Improvements to Existing BT Road at Janki ram nagar 4th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11945,Roads,Completed,NC-MADHAVARAM,24,1458000,"Improvements to Existing BT Road at singaravellan nagar 3rd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11946,Roads,Completed,NC-MADHAVARAM,24,1343000,"Improvements to Existing BT Road at Ragavan nagar main road In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11947,Roads,Completed,NC-MADHAVARAM,24,2689000,"Improvements to Existing BT Road at Rajaammal nagar main road In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11948,Roads,Completed,NC-MADHAVARAM,24,1664000,"Improvements to Existing BT Road at Bharath nagar In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11949,Roads,Completed,NC-MADHAVARAM,24,1849000,"Improvements to Existing BT Road at subash nagar 1st street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11950,Roads,Completed,NC-MADHAVARAM,24,225000,"Improvements to Existing BT Road at subash nagar 2nd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11951,Roads,Completed,NC-MADHAVARAM,24,1043000,"Improvements to Existing BT Road at subash nagar 3rd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11952,Roads,Completed,NC-MADHAVARAM,24,996000,"Improvements to Existing BT Road at subash nagar 4th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11953,Roads,Completed,NC-MADHAVARAM,24,1085000,"Improvements to Existing BT Road at subash nagar 5th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11954,Roads,Completed,NC-MADHAVARAM,24,530000,"Improvements to Existing BT Road at vallalar street 1st street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11955,Roads,Completed,NC-MADHAVARAM,24,700000,"Improvements to Existing BT Road at vallalar street 2nd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11956,Roads,Completed,NC-MADHAVARAM,24,472000,"Improvements to Existing BT Road at vallalar street 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11957,Roads,Completed,NC-MADHAVARAM,24,343000,"Improvements to Existing BT Road at vallalar street 4th street In divisaion-24,Unit-6,Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/11958,Roads,Completed,NC-MADHAVARAM,24,946000,"Improvements to Existing BT Road at vallalar street 6th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11959,Roads,Completed,NC-MADHAVARAM,24,446000,"Improvements to Existing BT Road at vallalar street 7th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11961,Roads,Completed,NC-MADHAVARAM,24,1446000,"Improvements to Existing BT Road at Elisabeth nagar main road In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11962,Roads,Completed,NC-MADHAVARAM,24,335000,"Improvements to Existing BT Road at Elisabeth nagar 1st street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11963,Roads,Completed,NC-MADHAVARAM,24,708000,"Improvements to Existing BT Road at Elisabeth nagar 2nd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11964,Roads,Completed,NC-MADHAVARAM,24,905000,"Improvements to Existing BT Road at Grace nagar 1st street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11965,Roads,Completed,NC-MADHAVARAM,24,189000,"Improvements to Existing BT Road at Grace nagar 2nd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11966,Roads,Completed,NC-MADHAVARAM,24,824000,"Improvements to Existing BT Road at Grace nagar 3rd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11967,Roads,Completed,NC-MADHAVARAM,24,365000,"Improvements to Existing BT Road at sri ram nagar 2nd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11968,Roads,Completed,NC-MADHAVARAM,24,689000,"Improvements to Existing BT Road at sri ram nagar 3rd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11969,Roads,Completed,NC-MADHAVARAM,24,512000,"Improvements to Existing BT Road at sri ram nagar 4th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11970,Roads,Completed,NC-MADHAVARAM,24,594000,"Improvements to Existing BT Road at sri venkateshwara nagar 3rd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11971,Roads,Completed,NC-MADHAVARAM,24,754000,"Improvements to Existing BT Road at sri venkateshwara nagar 5th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11972,Roads,Completed,NC-MADHAVARAM,24,415000,"Improvements to Existing BT Road at saraswathi nagar 1st street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11974,Roads,Completed,NC-MADHAVARAM,24,415000,"Improvements to Existing BT Road at saraswathi nagar 3rd street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11975,Roads,Completed,NC-MADHAVARAM,24,355000,"Improvements to Existing BT Road at saraswathi nagar 4th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11976,Roads,Completed,NC-MADHAVARAM,24,397000,"Improvements to Existing BT Road at saraswathi nagar 5th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11977,Roads,Completed,NC-MADHAVARAM,24,443000,"Improvements to Existing BT Road at saraswathi nagar 6th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11978,Roads,Completed,NC-MADHAVARAM,24,560000,"Improvements to Existing BT Road at Thirumal nagar 16th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11979,Roads,Completed,NC-MADHAVARAM,24,441000,"Improvements to Existing BT Road at Thirumal nagar 17th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11980,Roads,Completed,NC-MADHAVARAM,24,404000,"Improvements to Existing BT Road at Thirumal nagar 18th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11981,Roads,Completed,NC-MADHAVARAM,24,477000,"Improvements to Existing BT Road at Thirumal nagar Annex In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11982,Roads,Completed,NC-MADHAVARAM,24,777000,"Improvements to Existing BT Road at Vinayakar nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11983,Roads,Completed,NC-MADHAVARAM,24,509000,"Improvements to Existing BT Road at Vinayakar nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11984,Roads,Completed,NC-MADHAVARAM,24,324000,"Improvements to Existing BT Road at Venkata sai nagar extn 6th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11985,Roads,Completed,NC-MADHAVARAM,24,1043000,"Improvements to Existing BT Road at Venkata sai nagar (greedam street) In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11986,Roads,Completed,NC-MADHAVARAM,24,517000,"Improvements to Existing BT Road at Venkata sai nagar extn 10th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11987,Roads,Completed,NC-MADHAVARAM,24,557000,"Improvements to Existing BT Road at Venkata sai nagar extn 11th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11988,Roads,Completed,NC-MADHAVARAM,24,968000,"Improvements to Existing BT Road at Venkata sai nagar extn 12th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11989,Roads,Completed,NC-MADHAVARAM,24,826000,"Improvements to Existing BT Road at Lakshmi nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11990,Roads,Completed,NC-MADHAVARAM,24,1806000,"Improvements to Existing BT Road at Venkata sai nagar extn 14th steeet In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11991,Roads,Completed,NC-MADHAVARAM,24,361000,"ImImprovements to Existing BT Road at Venkata sai nagar extn 15th steeet In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11992,Roads,Completed,NC-MADHAVARAM,24,400000,"Improvements to Existing BT Road at Venkata sai nagar extn 4th steeet In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11993,Roads,Completed,NC-MADHAVARAM,24,310000,"Improvements to Existing BT Road at Venkata sai nagar extn 5th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11994,Roads,Completed,NC-MADHAVARAM,24,505000,"Improvements to Existing BT Road at Venkata sai nagar extn 7th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11995,Roads,Completed,NC-MADHAVARAM,24,993000,"Improvements to Existing BT Road at Venkata sai nagar extn 8th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11996,Roads,Completed,NC-MADHAVARAM,24,966000,"Improvements to Existing BT Road at Venkata sai nagar extn 9th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11997,Roads,Completed,NC-MADHAVARAM,24,685000,"Improvements to Existing BT Road at Venkata sai nagar extn. 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11998,Roads,Completed,NC-MADHAVARAM,24,954000,"Improvements to Existing BT Road at Venkata sai nagar extn. 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/11999,Roads,Completed,NC-MADHAVARAM,24,1114000,"Improvements to Existing BT Road at Dhanalakshmi nagar jeyalakshmi ngar link road In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12000,Roads,Completed,NC-MADHAVARAM,24,195000,"Improvements to Existing BT Road at sarathi nagar extn. 15th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12001,Roads,Completed,NC-MADHAVARAM,24,598000,"Improvements to Existing BT Road at sarathi nagar extn. 17th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12002,Roads,Completed,NC-MADHAVARAM,24,740000,"Improvements to Existing BT Road at sarathi nagar extn. 18th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12003,Roads,Completed,NC-MADHAVARAM,24,984000,"Improvements to Existing BT Road at sarathi nagar extn.jayalakshmi and Golden avenue In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12004,Roads,Completed,NC-MADHAVARAM,24,476000,"Improvements to Existing BT Road at Jayaram nagar1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12005,Roads,Completed,NC-MADHAVARAM,24,429000,"Improvements to Existing BT Road at Jayaram nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12006,Roads,Completed,NC-MADHAVARAM,24,770000,"Improvements to Existing BT Road at Ranganathan nagar In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12007,Roads,Completed,NC-MADHAVARAM,24,952000,"ImprImprovements to Existing BT Road at Ranganathan nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12008,Roads,Completed,NC-MADHAVARAM,24,1078000,"Improvements to Existing BT Road at Ranganathan nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12009,Roads,Completed,NC-MADHAVARAM,24,451000,"Improvements to Existing BT Road at kamala nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12010,Roads,Completed,NC-MADHAVARAM,24,533000,"ImproveImprovements to Existing BT Road at kamala nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12011,Roads,Completed,NC-MADHAVARAM,24,833000,"Improvements to Existing BT Road at kamala nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12012,Roads,Completed,NC-MADHAVARAM,24,637000,"Improvements to Existing BT Road at kamala nagar 4th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12013,Roads,Completed,NC-MADHAVARAM,24,377000,"Improvements to Existing BT Road at Lakshmi nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12014,Roads,Completed,NC-MADHAVARAM,24,276000,"Improvements to Existing BT Road at Lakshmi nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12016,Roads,Completed,NC-MADHAVARAM,24,1440000,"Improvements to Existing BT Road at Madhavan nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12017,Roads,Completed,NC-MADHAVARAM,24,1383000,"Improvements to Existing BT Road at Madhavan nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12019,Roads,Completed,NC-MADHAVARAM,24,1371000,"Improvements to Existing BT Road at Madhavan nagar 7th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12020,Roads,Completed,NC-MADHAVARAM,24,697000,"Improvements to Existing BT Road at vasugei street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12043,Roads,Completed,NC-MADHAVARAM,24,2346000,"Improvements to Existing BT Road at santhosh nagar Main road In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12044,Roads,Completed,NC-MADHAVARAM,24,1258000,"Improvements to Existing BT Road at santhosh nagar (anexe) In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12045,Roads,Completed,NC-MADHAVARAM,24,527000,"Improvements to Existing BT Road at Janaki raman nagar (santhosh nagar) In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12046,Roads,Completed,NC-MADHAVARAM,24,242000,"Improvements to Existing BT Road at santhosh nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12048,Roads,Completed,NC-MADHAVARAM,24,970000,"Improvements to Existing BT Road at santhosh nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12049,Roads,Completed,NC-MADHAVARAM,24,999000,"Improvements to Existing BT Road at Annai theresa street (santhosh nagar ) In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12050,Roads,Completed,NC-MADHAVARAM,24,1386000,"Improvements to Existing BT Road at Thiruvelluver street (santhosh nagar ) In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12051,Roads,Completed,NC-MADHAVARAM,24,234000,"Improvements to Existing BT Road at santhosh nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12052,Roads,Completed,NC-MADHAVARAM,24,986000,"Improvements to Existing BT Road at santhosh nagar 4th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12053,Roads,Completed,NC-MADHAVARAM,24,1305000,"Improvements to Existing BT Road at santhosh nagar 5th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12054,Roads,Completed,NC-MADHAVARAM,24,686000,"Improvements to Existing BT Road at ELUMALAI NAGAR In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12055,Roads,Completed,NC-MADHAVARAM,24,1443000,"Improvements to Existing BT Road at Ayyapan nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12056,Roads,Completed,NC-MADHAVARAM,24,906000,"Improvements to Existing BT Road at eakapanayakar street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12058,Roads,Completed,NC-MADHAVARAM,24,808000,"Improvements to Existing BT Road at subramani nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12059,Roads,Completed,NC-MADHAVARAM,24,319000,"Improvements to Existing BT Road at subramani nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12061,Roads,Completed,NC-MADHAVARAM,24,536000,"Improvements to Existing BT Road at subramani nagar(anexe) 4th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12062,Roads,Completed,NC-MADHAVARAM,24,1472000,"Improvements to Existing BT Road at Thagavel nagar main road In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12064,Roads,Completed,NC-MADHAVARAM,24,870000,"Improvements to Existing BT Road at Vigneshwara nagar In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12065,Roads,Completed,NC-MADHAVARAM,24,616000,"Improvements to Existing BT Road at Thangavel nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12066,Roads,Completed,NC-MADHAVARAM,24,1056000,"Improvements to Existing BT Road at Mullai street street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12067,Roads,Completed,NC-MADHAVARAM,24,713000,"Improvements to Existing BT Road at Mullai cross street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12068,Roads,Completed,NC-MADHAVARAM,24,351000,"Improvements to Existing BT Road at sri ram nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12069,Roads,Completed,NC-MADHAVARAM,24,386000,"Improvements to Existing BT Road at sri ram nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12070,Roads,Completed,NC-MADHAVARAM,24,800000,"Improvements to Existing BT Road at sakthi nagar 9th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12071,Roads,Completed,NC-MADHAVARAM,24,1767000,"Improvements to Existing BT Road at sakthi nagar 10th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12072,Roads,Completed,NC-MADHAVARAM,24,1415000,"Improvements to Existing BT Road at sakthi nagar aneax 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12073,Roads,Completed,NC-MADHAVARAM,24,1463000,"Improvements to Existing BT Road at sakthi nagar aneax 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12074,Roads,Completed,NC-MADHAVARAM,24,642000,"Improvements to Existing BT Road at Gandhi nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12075,Roads,Completed,NC-MADHAVARAM,24,357000,"Improvements to Existing BT Road at Gandhi nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12076,Roads,Completed,NC-MADHAVARAM,24,240000,"Improvements to Existing BT Road at Mahadevinagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12077,Roads,Completed,NC-MADHAVARAM,24,470000,"Improvements to Existing BT Road at v.o.c. nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12078,Roads,Completed,NC-MADHAVARAM,24,475000,"Improvements to Existing BT Road at v.o.c. nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12079,Roads,Completed,NC-MADHAVARAM,24,301000,"Improvements to Existing BT Road at v.o.c. nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12080,Roads,Completed,NC-MADHAVARAM,24,495000,"Improvements to Existing BT Road at v.o.c. nagar 4th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12081,Roads,Completed,NC-MADHAVARAM,24,427000,"Improvements to Existing BT Road at v.o.c. nagar 5th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12082,Roads,Completed,NC-MADHAVARAM,24,1108000,"Improvements to Existing BT Road at Rajaammal nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12083,Roads,Completed,NC-MADHAVARAM,24,332000,"Improvements to Existing BT Road at Rajaammal nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12084,Roads,Completed,NC-MADHAVARAM,24,305000,"Improvements to Existing BT Road at Rajaammal nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12085,Roads,Completed,NC-MADHAVARAM,24,727000,"Improvements to Existing BT Road at Rajaammal nagar 4th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12086,Roads,Completed,NC-MADHAVARAM,24,1834000,"Improvements to Existing BT Road at Jothi nagar subash nagar link road In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12087,Roads,Completed,NC-MADHAVARAM,24,429000,"Improvements to Existing BT Road at sathya nagar In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12088,Roads,Completed,NC-MADHAVARAM,24,789000,"Improvements to Existing BT Road at Thiruvellvar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12089,Roads,Completed,NC-MADHAVARAM,24,252000,"Improvements to Existing BT Road at Thiruvellvar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12090,Roads,Completed,NC-MADHAVARAM,24,1315000,"Improvements to Existing BT Road at Erikarai street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12091,Roads,Completed,NC-MADHAVARAM,24,864000,"Improvements to Existing BT Road at Siva sakthi velan nagar In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12093,Roads,Completed,NC-MADHAVARAM,24,388000,"Improvements to Existing BT Road at Siva Sarathy nagar extn In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12094,Roads,Completed,NC-MADHAVARAM,24,1030000,"Improvements to Existing BT Road at sri ram nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12095,Roads,Completed,NC-MADHAVARAM,24,463000,"Improvements to Existing BT Road at Vengateshwara nagar In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12096,Roads,Completed,NC-MADHAVARAM,24,139000,"Improvements to Existing BT Road at Jayaram nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12097,Roads,Completed,NC-MADHAVARAM,24,754000,"Improvements to Existing BT Road at Subramani nagar annex 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12098,Roads,Completed,NC-MADHAVARAM,24,371000,"Improvements to Existing BT Road at Ashok avenue In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12099,Roads,Completed,NC-MADHAVARAM,24,314000,"Improvements to Existing BT Road at Thangavel nagar cross street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12100,Roads,Completed,NC-MADHAVARAM,24,358000,"Improvements to Existing BT Road at Thangavel nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12167,Roads,Completed,NC-MADHAVARAM,24,407000,"Improvements to Existing BT Road at Thangavel nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12168,Roads,Completed,NC-MADHAVARAM,24,349000,"Improvements to Existing BT Road at Mahadevi nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12169,Roads,Completed,NC-MADHAVARAM,24,712000,"Improvements to Existing BT Road at Gandhi nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12170,Roads,Completed,NC-MADHAVARAM,24,687000,"Improvements to Existing BT Road at Kumaran nagar main road In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12171,Roads,Completed,NC-MADHAVARAM,24,157000,"Improvements to Existing BT Road at Kumara nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12172,Roads,Completed,NC-MADHAVARAM,24,350000,"Improvements to Existing BT Road at Kumara nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12173,Roads,Completed,NC-MADHAVARAM,24,560000,"Improvements to Existing BT Road at Kumara nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12174,Roads,Completed,NC-MADHAVARAM,24,3063000,"Improvements to Existing BT Road at Sri lakshmi amman nagar 40 feet road In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12175,Roads,Completed,NC-MADHAVARAM,24,1567000,"Improvements to Existing BT Road at Sri lakshmi amman nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12176,Roads,Completed,NC-MADHAVARAM,24,569000,"Improvements to Existing BT Road at Sri lakshmi amman nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12177,Roads,Completed,NC-MADHAVARAM,24,1032000,"Improvements to Existing BT Road at pandian street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12178,Roads,Completed,NC-MADHAVARAM,24,266000,"Improvements to Existing BT Road at Annai indira nagar 8th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12179,Roads,Completed,NC-MADHAVARAM,24,242000,"Improvements to Existing BT Road at Annai indira nagar 1st street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12180,Roads,Completed,NC-MADHAVARAM,24,285000,"Improvements to Existing BT Road at Annai indira nagar 2nd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12181,Roads,Completed,NC-MADHAVARAM,24,225000,"Improvements to Existing BT Road at Annai indira nagar 3rd street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12182,Parks,Completed,NC-MADHAVARAM,24,586000,"MAINTENANCE ESTIMATE FOR PARK AT DG NAGAR PARK IN DIV-24,UNIT-6,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/12183,Roads,Completed,NC-MADHAVARAM,24,435000,"Improvements to Existing BT Road at Annai indira nagar 5th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12184,Roads,Completed,NC-MADHAVARAM,24,295000,"Improvements to Existing BT Road at Annai indira nagar 6th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12185,Roads,Completed,NC-MADHAVARAM,24,285000,"Improvements to Existing BT Road at Annai indira nagar 7th street In division-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12186,Roads,Completed,NC-MADHAVARAM,24,417000,"Improvements to Existing BT Road at Annai indira nagar 4th street In divisaion-24,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/13572,Buildings,Completed,NC-MADHAVARAM,24,230000,"Repair and improvements of 16th cermony hall at thangal karai salai and Repair In Division-24, Unit-6, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/13697,Parks,Completed,NC-MADHAVARAM,24,613000,"MAINTENANCE FOR PARK AT SRI LAKSHIMI AMMAN NAGAR PARK IN WARD-24,UNIT-6,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/14342,Buildings,Completed,NC-MADHAVARAM,24,119000,"Repairs and improvements of side drain at thulukanathamman koil 5th street in dn-24,Unit-6,Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/14348,Buildings,Completed,NC-MADHAVARAM,24,139000,"PROVIDING BORE ARRANGEMENTS FOR ICDS AT BRINDHAVAN NAGAR IN DIVISION-24, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/15106,Buildings,Completed,NC-MADHAVARAM,24,444000,"CONSTRUCTION OF BABY FRIENDLY TOILET FOR ICDS AT THIRUVALLUVAR STREET IN DIVISION-24, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/1690,Buildings,Completed,NC-MADHAVARAM,24,412000,"PROVIDING WELL RINGS AT VARIOUS STREETS (PHASE-II) IN DN-24, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/1691,Parks,Completed,NC-MADHAVARAM,24,300000,"CONSTRUCTION OF MULCH PITS & PROVIDING WELL RINGS AT VARIOUS STREETS (PHASE-I) IN DN-24, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2654,Buildings,Completed,NC-MADHAVARAM,24,692000,"PROVIDING WEIGHING MACHINE & VEGITABLE SHREDDER MACHINE AT VARIOUS STREET IN DIV-24, UNIT-6, ZONE - 3",Own Sources,3,2019-20,2019-20 NC/2019-20/3842,Roads,Completed,NC-MADHAVARAM,24,2080000,"Laying of cement concrete road at Madhavan nagar 5th street in Dn-24,Unit-6, Zone-3.",MLACDS,3,2019-20,2020-21 NC/2019-20/3843,Roads,Completed,NC-MADHAVARAM,24,999000,"Laying of cement concrete road at balavinayagarkoil 11th street in Dn-24,Unit-6, Zone-3.",MLACDS,3,2019-20,2020-21 NC/2019-20/3847,Roads,Completed,NC-MADHAVARAM,24,723000,"Laying of cement concrete road at balavinayagarkoil 12th street in Dn-24,Unit-6, Zone-3.",MLACDS,3,2019-20,2020-21 NC/2019-20/3971,Storm Water Drain,Completed,NC-MADHAVARAM,24,593000,"IMPROVEMENTS OF EXISTING SIDE DRAIN AT THULUKANATHAMMAN KOIL 7TH STREET IN DIVISION - 24, UNIT- 6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/3981,Storm Water Drain,Completed,NC-MADHAVARAM,24,870000,"IMPROVEMENTS OF EXISTING SIDE DRAIN AT SCHOOL STREET IN DIVISION - 24, UNIT- 6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4289,Storm Water Drain,Completed,NC-MADHAVARAM,24,814000,"PROVIDING AND LAYING OF HUME PIPE AT AMBATTUR REDHILLS ROAD IN DIVISION-24, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4307,Storm Water Drain,Completed,NC-MADHAVARAM,24,125000,"CONSTRUCTION OF NEW CULVERT AT JUNCTION OF SCHOOL STREET IN DIVISION - 24, UNIT- 6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4309,Storm Water Drain,Completed,NC-MADHAVARAM,24,125000,"CONSTRUCTION OF NEW CULVERT AT JUNCTION OF EZHIL NAGAR DG NAGAR MAIN ROAD IN DIVISION - 24, UNIT- 6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4310,Storm Water Drain,Completed,NC-MADHAVARAM,24,160000,"CONSTRUCTION OF NEW CULVERT AT JUNCTION OF JP NAGAR 1ST AND 2ND MAIN ROAD IN DIVISION - 24, UNIT- 6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4594,Storm Water Drain,Completed,NC-MADHAVARAM,24,411000,"DE- SILTING OF STORM WATER DRAIN AT SERVICE ROAD IN DN-24,UNIT-6,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/6781,Buildings,Completed,NC-MADHAVARAM,24,500000,"SUPPLING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT MARIAMMAN KOIL STREET IN DIV-24,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/6784,Buildings,Completed,NC-MADHAVARAM,24,500000,"SUPPLING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT BHARATHIDASAN NAGAR IN DIV-24,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/6786,Buildings,Completed,NC-MADHAVARAM,24,500000,"SUPPLYING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT J.P NAGAR IN DIV-24,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/6788,Buildings,Completed,NC-MADHAVARAM,24,500000,"SUPPLYING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT SCHOOL ROAD SURAPATTU IN DIV-24,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/6793,Buildings,Completed,NC-MADHAVARAM,24,500000,"SUPPLYING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT BHARATHIDASAN NAGAR 6TH STREET IN DIV-24,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/6796,Buildings,Completed,NC-MADHAVARAM,24,500000,"SUPPLYING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CPS SCHOOL AT BALAVINAYAGAR KOIL 1ST CROSS STREET IN DIV-24,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/8138,Roads,Completed,NC-MADHAVARAM,24,154000,"Attending patch work at various street in Dn-24,Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8890,Buildings,Completed,NC-MADHAVARAM,24,538000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete at Kadappah road RRC centre in Division 24, Unit-6,Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/9717,Footpath,Completed,NC-MADHAVARAM,24,224000,"Providing Foot path for Surapet Under pass In Division-24, Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/10833,Roads,Completed,NC-MADHAVARAM,25,7000000,"FORMATION OF BT ROAD AT INTUC NAGAR BRITTANIA NAGAR JOINT ROAD IN DIVISION-25,UNIT-6,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/10949,Roads,Completed,NC-MADHAVARAM,25,64000,"Providing and Laying of WMM at various street In Division-25, Unit-6, Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/12188,Roads,Completed,NC-MADHAVARAM,25,1079000,"Improvements to Existing BT Road at Padmavathy nagar 4th cross street In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12189,Roads,Completed,NC-MADHAVARAM,25,1165000,"Improvements to Existing BT Road at Padmavathy nagar 9th street In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12190,Roads,Completed,NC-MADHAVARAM,25,410000,"Improvements to Existing BT Road at Padmavathy nagar 3rd cross street In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12191,Roads,Completed,NC-MADHAVARAM,25,602000,"Improvements to Existing BT Road at Moogambikai nagar In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12192,Roads,Completed,NC-MADHAVARAM,25,385000,"Improvements to Existing BT Road at Veeraragavalu extn 4th street In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12193,Roads,Completed,NC-MADHAVARAM,25,605000,"Improvements to Existing BT Road at Veeraragavalu 7th cross street In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12194,Roads,Completed,NC-MADHAVARAM,25,622000,"Improvements to Existing BT Road at Padmavathy nagar 4th street part In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12195,Roads,Completed,NC-MADHAVARAM,25,1227000,"Improvements to Existing BT Road at Sivaraj street In division-25,Unit-6,Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/15882,Parks,Completed,NC-MADHAVARAM,25,575000,"MAINTENANCE ESTIMATE FOR PARK AT PADMAVATHY NAGAR EXTN 5TH STREET IN DIV-25,UNIT-6,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/15883,Parks,Completed,NC-MADHAVARAM,25,999000,"MAINTENANCE FOR PARK AT BIRLA AVENUE IN DIV-25,UNIT-6,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/15884,Parks,Completed,NC-MADHAVARAM,25,632000,"MAINTENANCE FOR PARK AT COLLECTOR NAGAR MAIN ROAD IN DIV-25,UNIT-6,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/15885,Parks,Completed,NC-MADHAVARAM,25,900000,"MAINTENANCE FOR PARK AT PADMAVATHY NAGAR 7TH STREET IN DIV-25,UNIT-6,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/15886,Parks,Completed,NC-MADHAVARAM,25,602000,"MAINTENANCE FOR PARK AT SRINIVASA NAGAR MAIN ROAD IN DIV-25,UNIT-6,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/1747,Buildings,Completed,NC-MADHAVARAM,25,640000,"PROVIDING WELL RINGS & CONSTRUCTION OF MULCH PITS AT VARIOUS STREETS IN DN-25, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2136,Buildings,Completed,NC-MADHAVARAM,25,375000,"PROVIDING WEIGHING MECHINE, VEGITABLE SHREDDER & VEGITABLE CUTTER MECHINE AT VARIOUS STREET IN DIVISION -25, UNIT-6, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/3845,Roads,Completed,NC-MADHAVARAM,25,1186000,"Laying of cement concrete road at balavinayagarkoil 8thth street in Dn-24,Unit-6, Zone-3.",MLACDS,3,2019-20,2020-21 NC/2019-20/3890,Buildings,Completed,NC-MADHAVARAM,25,832000,"Providing Interlocking Block Inside the Division office Campus at EMS Street in DN-25, Unit-6, Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4599,Storm Water Drain,Completed,NC-MADHAVARAM,25,745000,"DE- SILTING AND IMRROVEMENTS OF STORM WATER DRAIN AT VARIOUS STREET IN DN-25,UNIT-6,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/6622,Buildings,Completed,NC-MADHAVARAM,25,74000,"Converting to Rain Water Harvesting Purpose for the Existing Unused Community Well at Thiru.Vi.Ka Street in Dn-25, Unit-6,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/6794,Buildings,Completed,NC-MADHAVARAM,25,500000,"SUPPLYING AND FIXING RO PLANT WITH WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT SEMBIUM ROAD IN DIV-25,UNIT-6,ZONE-3",MLACDS,3,2019-20,2020-21 NC/2019-20/8125,Roads,Completed,NC-MADHAVARAM,25,415000,"Attending patch work at various street in Dn-25,Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/9630,Storm Water Drain,Completed,NC-MADHAVARAM,25,388000,"Repairs and improvements to SWD at Sembium Redhills road and Bajanai koil street in dn-25, Unit-6,Zone-3.",Own Sources,3,2019-20,2019-20 BR/2019-20/15776,Roads,Completed,BR-Bus Route Roads,26,753000,"Partly relaying the road with BC after cold milling by paver finisher at Villivakkam Road in Dn-26&32, Zone - 3",Grants,3,2019-20,2020-21 L/2019-20/10288,Electrical,Completed,L-Electrical,26,319200,"WORK: - Replacement of 10 Nos of Rusted, Damaged Kiosk Pillar Box by New Kiosk Pillar Box at Various Locations in Division -26,29,31 -to-33 of Zone -III areas.",Own Sources,3,2019-20,2021-22 L/2019-20/8167,Electrical,Completed,L-Electrical,26,6254500,"Provision of 135 Nos of 6mtr lamp post, single straight bracket with 40w LED fitting at Vanasakthi Nagar, Nehru Nagar & various streets in Div-26,27,30 & 31 of Zone-III (Madhavaram)",Grants,3,2019-20,2021-22 NC/2019-20/10036,Buildings,Completed,NC-MADHAVARAM,26,312000,"REPARIS AND MAINTANCE WORK AT DIVISION-26 OFFICE IN DIVISION-26, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/10037,Buildings,Completed,NC-MADHAVARAM,26,110000,"REPARIS AND MAINTANCE WORK AT ZONAL OFFICE-3 IN DIVISION-26, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/10233,Buildings,Completed,NC-MADHAVARAM,26,156000,"REPAIRS AND IMPROVEMENTS TO WATER SUPPLY ARRANGEMENTS AT OMAKULAM POND IN DIVISION-26, UNIT-7,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/14588,Roads,Completed,NC-MADHAVARAM,26,554000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT THIRUMALAI NAGAR 2ND CROSS STREET IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/14589,Roads,Completed,NC-MADHAVARAM,26,1378000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT THIRUMALAI NAGAR 2ND MAIN STREET IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/14590,Roads,Completed,NC-MADHAVARAM,26,2640000,"THE PROPOSED FORMING OF BT ROAD AT VANASAKTHI NAGAR EXT IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/1618,Buildings,Completed,NC-MADHAVARAM,26,352000,"PROVIDING WELL RINGS (PHASE-II) AT VARIOUS LOCATIONS DN-26, UNIT-7,ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/1625,Buildings,Completed,NC-MADHAVARAM,26,118000,"CONSTRUCTION OF MULCH PIT & PROVIDING WELL RINGS (PHASE - I )AT VARIOUS LOCATIONS IN DIV-26, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/16978,Buildings,Completed,NC-MADHAVARAM,26,492000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AND MICRO COMPOST CENTRE AT SURAPET MAIN ROAD IN DIVISION-26,UNIT-7,ZONE-3.",Own Sources,3,2019-20,2021-22 NC/2019-20/16979,Buildings,Completed,NC-MADHAVARAM,26,492000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AND MICRO COMPOST CENTRE AT VINAYAGAPURAM BURIAL GROUND ROAD IN DIVISION-26,UNIT-7,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/17025,Roads,Completed,NC-MADHAVARAM,26,181000,"IMPROVEMENTS TO EXISTING BT ROAD AT MANIMEKALI MAIN ROAD IN DN-26, UNIT-7, ZONE-3.",Grants,3,2019-20,2021-22 NC/2019-20/17026,Roads,Completed,NC-MADHAVARAM,26,750000,"FORMING OF BT ROAD AT THANIKACHALAM NAGAR F BLOCK 1ST MAIN ROAD IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2021-22 NC/2019-20/17036,Roads,Completed,NC-MADHAVARAM,26,1017000,"IMPROVEMENTS TO EXISTING BT ROAD AT SRINIVASA NAGAR 1ST STREET IN DN-26, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/17037,Roads,Completed,NC-MADHAVARAM,26,810000,"IMPROVEMENTS TO EXISTING BT ROAD AT SRINIVASA NAGAR 3RD STREET IN DN-26, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/17039,Roads,Completed,NC-MADHAVARAM,26,678000,"IMPROVEMENTS TO EXISTING BT ROAD AT SURYA NAGAR IN DN-26, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/17042,Roads,Completed,NC-MADHAVARAM,26,291000,"IMPROVEMENTS TO EXISTING BT ROAD AT ETTIAPPAN NAGAR EXTN IN DN-26, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/17047,Roads,Completed,NC-MADHAVARAM,26,501000,"IMPROVEMENTS TO EXISTING BT ROAD AT OMAKULAMEDU IN DN-26, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/17048,Roads,Completed,NC-MADHAVARAM,26,724000,"FORMING OF BT ROAD AT PERIYAR AVENUE MAIN ROAD IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2021-22 NC/2019-20/17049,Roads,Completed,NC-MADHAVARAM,26,525000,"FORMING OF BT ROAD AT PERIYAR AVENUE 1ST MAIN ROAD IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2021-22 NC/2019-20/17051,Roads,Completed,NC-MADHAVARAM,26,768000,"FORMING OF BT ROAD AT PILLAYAR KOIL STREET IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2021-22 NC/2019-20/17052,Roads,Completed,NC-MADHAVARAM,26,838000,"IMPROVEMENTS TO EXISTING BT ROAD AT PARIMALAM NAGAR 2ND STREET IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/17053,Roads,Completed,NC-MADHAVARAM,26,345000,"IMPROVEMENTS TO EXISTING BT ROAD AT PARIMALAM NAGAR 1ST STREET IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/17054,Roads,Completed,NC-MADHAVARAM,26,704000,"IMPROVEMENTS TO EXISTING BT ROAD AT PARIMALAM NAGAR 1ST 2ND, 3RD , CROSS STREET IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/17055,Roads,Completed,NC-MADHAVARAM,26,345000,"IMPROVEMENTS TO EXISTING BT ROAD AT KESAVAN STREET IN DN-26, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/4800,Buildings,Completed,NC-MADHAVARAM,26,2232000,"CONSTRUCTION OF COMPOUND WALL AT CANAL SIDE IN BURIAL GROUND AT BURIAL GROUND ROAD (VINAYAGAPURAM) IN DN-26, UNIT-07, ZONE-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/4845,Buildings,Completed,NC-MADHAVARAM,26,255000,"Improvements to exisiting compound wall and caretaker room in burial ground at burial ground road (vinayagapuram) in dn-26,unit-7,zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/6066,Buildings,Completed,NC-MADHAVARAM,26,595000,DESILTING OF STORM WATER DRAIN AND SIDE DRAIN AND IMPROVEMENTS WORKS TO VARIOUS STREETS IN DN-26 UNIT-7 ZONE-3,Own Sources,3,2019-20,2019-20 NC/2019-20/6797,Buildings,Completed,NC-MADHAVARAM,26,69000,"Converted to rain water harvesting purpose the exisiting unused community Well at Samy Nagar in Dn-26, Unit-07,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/8005,Roads,Completed,NC-MADHAVARAM,26,999000,Attending patchwork with WMM at CMDA Truck Terminal Main Road in Division-26 Unit-7 Zone-3,Own Sources,3,2019-20,2020-21 NC/2019-20/8118,Buildings,Completed,NC-MADHAVARAM,26,373000,"Attending Patch Work at Various Street in Division-26, Unit-7, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/8207,Roads,Completed,NC-MADHAVARAM,26,976000,"Attending patchwork with WMM at Vinayagapuram Bus Stand in Division-26,Unit-7,Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8373,Roads,Completed,NC-MADHAVARAM,26,290000,"LAYING OF CC ROAD AT VILLIVAKKAM ROAD (ICDS ) IN DN-26, UNIT-7, ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/8726,Buildings,Completed,NC-MADHAVARAM,26,1900000,"CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT NORTH AND EASTEN SIDE CMDA TRUCK TERMINAL ROAD IN DIVISION-26, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8939,Buildings,Completed,NC-MADHAVARAM,26,1900000,"CONSTRUCTION OF COMPOUND WALL FOR OSR LAND AT WEST AND SOUTH SIDE CMDA TRUCK TERMINAL ROAD IN DIVISION-26, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/9732,Buildings,Completed,NC-MADHAVARAM,26,377000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FAILITY AT 200 FEET ROAD OSR LAND IN DIVISION-26,UNIT-7,ZONE-3.",Own Sources,3,2019-20,2021-22 NC/2019-20/10610,Buildings,Completed,NC-MADHAVARAM,27,278000,"PROVIDING RAINWATER HARVESTING USING WELL RINGS AT VARIOUS LOCATIONS IN DIV-27, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/10746,Buildings,Completed,NC-MADHAVARAM,27,338000,"IMPROVEMENTS TO EXISTING BT ROAD AT MANDAIVELI 6TH STREET IN DN-27, UNIT-7, ZONE-3.",Grants,3,2019-20,2021-22 NC/2019-20/11016,Buildings,Completed,NC-MADHAVARAM,27,428000,"IMPROVEMENTS TO EXISTING BT ROAD AT VENKATESWARA COLONY 2ND STREET IN DN-27, UNIT-7, ZONE-3.",Grants,3,2019-20,2021-22 NC/2019-20/11748,Roads,Completed,NC-MADHAVARAM,27,941000,"IMPROVEMENTS TO EXISTING BT ROAD AT ASSIS NAGAR 8TH CROSS STREET IN DN-27, UNIT-7, ZONE-3.",Grants,3,2019-20,2021-22 NC/2019-20/12540,Roads,Completed,NC-MADHAVARAM,27,629000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT LOGAMBAL NAGAR IN DN-27, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12541,Roads,Completed,NC-MADHAVARAM,27,554000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT TELEPHONE COLONY 4TH STREET NORTH IN DN-27, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12542,Roads,Completed,NC-MADHAVARAM,27,620000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT TELEPHONE COLONY SOUTH MAIN ROAD IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12543,Roads,Completed,NC-MADHAVARAM,27,843000,"THE PROPOSED FORMING OF BT ROAD AT AVM NAGAR IN DN-27, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12544,Roads,Completed,NC-MADHAVARAM,27,2154000,"THE PROPOSED FORMING OF BT ROAD AT CHELLIAMMAN KOIL STREET(MANDAIVELI MAIN ROAD NORTH END TO ASSIS NAGAR TO KUMARAPPAPURAM MAIN ROAD) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12545,Roads,Completed,NC-MADHAVARAM,27,2103000,"THE PROPOSED RELAYING OF BT ROAD AT PERUMAL KOIL STREET IN DN-27, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12546,Roads,Completed,NC-MADHAVARAM,27,426000,"THE PROPOSED RELAYING OF BT ROAD AT MANDAIVELI 4TH STREET IN DN-27, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12547,Roads,Completed,NC-MADHAVARAM,27,1400000,"THE PROPOSED RELAYING OF BT ROAD AT NEHRU MAIN ROAD IN DN-27, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/13145,Roads,Completed,NC-MADHAVARAM,27,607000,IMPROVEMENTS TO EXISTING BT ROAD AT ALEX NAGAR A COLONY 1ST STREETIN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13146,Roads,Completed,NC-MADHAVARAM,27,923000,IMPROVEMENTS TO EXISTING BT ROAD AT ALEX NAGAR A COLONY 2ND STREET IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13147,Roads,Completed,NC-MADHAVARAM,27,389000,IMPROVEMENTS TO EXISTING BT ROAD AT ALEX NAGAR A COLONY 3RD STREET IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13148,Roads,Completed,NC-MADHAVARAM,27,341000,IMPROVEMENTS TO EXISTING BT ROAD AT VENYGOPAL NAGAR IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13149,Roads,Completed,NC-MADHAVARAM,27,566000,IMPROVEMENTS TO EXISTING BT ROAD AT ASSISI NAGAR 9TH STREET IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13150,Roads,Completed,NC-MADHAVARAM,27,2763000,IMPROVEMENTS TO EXISTING BT ROAD AT ASSISI NAGAR TO EDAIMA NAGAR LINK ROAD IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13152,Roads,Completed,NC-MADHAVARAM,27,167000,IMPROVEMENTS TO EXISTING F BT ROAD AT ALEX NAGAR C COLONY IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13153,Roads,Completed,NC-MADHAVARAM,27,429000,IMPROVEMENTS TO EXISTING BT ROAD AT ALEX NAGAR D COLONY MAIN ROAD IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13154,Roads,Completed,NC-MADHAVARAM,27,572000,IMPROVEMENTS TO EXISTING BT ROAD AT ALEX NAGAR D COLONY 1ST STREET IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13155,Roads,Completed,NC-MADHAVARAM,27,358000,IMPROVEMENTS TO EXISTING BT ROAD AT ALEX NAGAR D COLONY 2ND STREET IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13156,Roads,Completed,NC-MADHAVARAM,27,427000,IMPROVEMENTS TO EXISTING BT ROAD AT MCG AVENUE TO MMC HOSPITAL IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13157,Roads,Completed,NC-MADHAVARAM,27,212000,IMPROVEMENTS TO EXISTING BT ROAD AT ALEX NAGAR A COLONY CROSS STREET IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13158,Roads,Completed,NC-MADHAVARAM,27,1191000,IMPROVEMENTS TO EXISTING BT ROAD AT MANDAVELI MAIN ROAD SOUTH SIDE IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/13159,Roads,Completed,NC-MADHAVARAM,27,1392000,FORMING OF BT ROAD AT CHELLIAMMAN KOIL STREET (SOUTH END) IN DIV-27 UNIT-7 ZONE-3,Grants,3,2019-20,2020-21 NC/2019-20/14323,Buildings,Completed,NC-MADHAVARAM,27,300000,"PROVIDING WATER SUPPLY ARRANGMENTS IN NURSERY GARDEN FOR AGARSON COLLEGE OSR LAND AT KUMARAPPAPURAM TO MANJABAKKAM MAIN ROAD IN DN-27, UNIT-7, ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/1627,Buildings,Completed,NC-MADHAVARAM,27,144000,PROVIDING WELL RINGS (PHASE-1) AT VARIOUS LOCATIONS IN DN-27 UNIT-7 ZONE-3,Own Sources,3,2019-20,2019-20 NC/2019-20/1881,Buildings,Completed,NC-MADHAVARAM,27,336000,"PROVIDING WELL RINGS (PHASE-II) AT VARIOUS LOCATIONS IN DN-27, UNIT-7, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2070,Buildings,Completed,NC-MADHAVARAM,27,710000,"PROVIDING WEIGHING MECHINE & VEGITABLE SHREDDER MECHINE AT VARIOUS STREET IN DIVISION -26 & 27, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/7481,Buildings,Completed,NC-MADHAVARAM,27,430000,"Converted to rain water harvesting purpose the exisiting unused community Well at Perumal Koil Street (Opposite to Welding Shop), Telugu Colony, Srinivasa Perumal Koil Street (Near Icds) and Srinivasa Perumal Koil Street (Near Temple) in Dn-27, Unit-07,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/8124,Buildings,Completed,NC-MADHAVARAM,27,420000,"Attending Patch Work at Various Street in Division-27, Unit-7, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/8888,Buildings,Completed,NC-MADHAVARAM,27,538000,"SUPPLY OF 100Kg TO 150Kg MULTIPLE BAILING PRESS MACHINE ,TRANPORTATION , ERECTION AND COMMISSIONING, FITTING CHARGES 2 COATS OF ZINC,CHROME, 2 COATS OF POLY URETHANE PAINT INCLUDING 18% GST AT TELUGU COLONY BURIAL GROUND",Own Sources,3,2019-20,2019-20 NC/2019-20/9088,Roads,Completed,NC-MADHAVARAM,27,453000,"CONSTRUCTION OF CULVERT FOR SIDE DRAIN AT MANDAIVELI MAIN ROAD IN DN-27, UNIT-07, ZONE-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/9090,Roads,Completed,NC-MADHAVARAM,27,410000,"CONSTRUCTION OF CULVERT FOR SIDE DRAIN AT PERUMAL KOIL STREET IN DN-27, UNIT-07, ZONE-03",Own Sources,3,2019-20,2020-21 NC/2019-20/10583,Buildings,Completed,NC-MADHAVARAM,28,240000,"IMPROVEMENTS TO EXISTING BURIAL GROUND AT SASTHRI NAGAR IN DIVISION-28, UNIT-7,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/1084,Buildings,Completed,NC-MADHAVARAM,28,582000,"CONSTRUCTION OF 16 th CERMONY HALL AT MOOLACHATRAM MAIN ROAD NEAR MILK COLONY MAIN GATE IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/10972,Buildings,Completed,NC-MADHAVARAM,28,285000,"HIRING OF 1NO FRONT END LOADER WITH BACK HOE AND 1NO OF HYDRAULIC EXCAVATOR (BOCKLINE) FOR CLEANING OF HEAVY JUNGLE AND BUSHES AT CHINNASEKKADU VILLAGE BEARING SURVEY NO.16/1, 17, 18/1, 19/1, 20/4, 21/3, 73/2, 4 & 74/3 (28 ACRE) IN DN-29 UNIT-7 ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/12152,Roads,Completed,NC-MADHAVARAM,28,10084000,"IMPROVEMENTS TO EXISTING BT ROAD AT ARUL NAGAR TO GANAPATHY NAGAR APPROACH ROAD IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12153,Roads,Completed,NC-MADHAVARAM,28,446000,"IMPROVEMENTS TO EXISTING BT ROAD AT SUBRAMANIYA GARDEN MAIN STREET IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12154,Roads,Completed,NC-MADHAVARAM,28,314000,"IMPROVEMENTS TO EXISTING BT ROAD AT PERIYASEKKADU PERUMAL KOIL STREET IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12156,Roads,Completed,NC-MADHAVARAM,28,125000,"IMPROVEMENTS TO EXISTING BT ROAD AT RADHAMMAL 1ST CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2021-22 NC/2019-20/12158,Roads,Completed,NC-MADHAVARAM,28,121000,"IMPROVEMENTS TO EXISTING BT ROAD AT KRISHNAPPAN STREET PART PERIYASEKKADU IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2021-22 NC/2019-20/12161,Roads,Completed,NC-MADHAVARAM,28,1023000,"FORMING OF BT ROAD AT JAYALAKSHMI STREET (MOOLACHATRAM) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2021-22 NC/2019-20/12162,Roads,Completed,NC-MADHAVARAM,28,691000,"FORMING OF BT ROAD AT AARUMUGA NATESAN STREET (PERIYASEKKADU)IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2021-22 NC/2019-20/12354,Roads,Completed,NC-MADHAVARAM,28,390000,"FORMING OF CC ROAD AT SAGUNTHALA 1ST CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12355,Roads,Completed,NC-MADHAVARAM,28,390000,"FORMING OF CC ROAD AT SAGUNTHALA 2nd CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12356,Roads,Completed,NC-MADHAVARAM,28,963000,"FORMING OF CC ROAD AT PERUMAL STREET (PERIYASEKKADU) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12357,Roads,Completed,NC-MADHAVARAM,28,624000,"FORMING OF CC ROAD AT MURUGAPPAN STREET (KUMARAN NAGAR) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12358,Roads,Completed,NC-MADHAVARAM,28,1102000,"FORMING OF CC ROAD AT PACHAYAPPAN GARDEN 11TH STREET (MOOLACHATRAM) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12359,Roads,Completed,NC-MADHAVARAM,28,494000,"FORMING OF CC ROAD AT NAGOOR MEERAN (MOOLACHATRAM) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12360,Roads,Completed,NC-MADHAVARAM,28,899000,"FORMING OF CC ROAD AT DHARMA GOVINDAN STREET (KUMARAN ST )IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12361,Roads,Completed,NC-MADHAVARAM,28,588000,"FORMING OF CC ROAD AT PACHAYAPPAN GARDEN 3RD STREET 1ST CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12362,Roads,Completed,NC-MADHAVARAM,28,1011000,"FORMING OF CC ROAD AT PACHAYAPPAN GARDEN 3RD STREET 2ND CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12363,Roads,Completed,NC-MADHAVARAM,28,651000,"FORMING OF CC ROAD AT VENU STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12364,Roads,Completed,NC-MADHAVARAM,28,163000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT SUBRAMANI NAGAR(PERIYASEKKADU) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12365,Roads,Completed,NC-MADHAVARAM,28,421000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT MOOOLACHATRAM MAIN ROAD (NEAR AMUDHA NURSERY GARDEN) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12366,Roads,Completed,NC-MADHAVARAM,28,182000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT SURYA GARDEN(KUMARAN STREET) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12367,Roads,Completed,NC-MADHAVARAM,28,239000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT SEEYALN STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12368,Roads,Completed,NC-MADHAVARAM,28,150000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT JOHN VASU 1ST CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12369,Roads,Completed,NC-MADHAVARAM,28,99000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT JOHN VASU 2ND CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12370,Roads,Completed,NC-MADHAVARAM,28,327000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT BINNY NAGAR 1ST CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12373,Roads,Completed,NC-MADHAVARAM,28,171000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT BINNY NAGAR 2nd CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12377,Roads,Completed,NC-MADHAVARAM,28,1825000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT MD SAMI NAGAR 1ST AND 2ND STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12383,Roads,Completed,NC-MADHAVARAM,28,753000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT SUBRAMANI GARDEN EXT 1ST CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12388,Roads,Completed,NC-MADHAVARAM,28,80000,"THE PROPOSED ROAD CUT RESTORATION OF BT ROAD AT BANK COLONY 3RD STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12394,Roads,Completed,NC-MADHAVARAM,28,784000,"THE PROPOSED FORMING OF BT ROAD AT KUPPU 3RD STREET 1ST CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12395,Roads,Completed,NC-MADHAVARAM,28,547000,"THE PROPOSED FORMING OF BT ROAD AT PUSHPAMMAL STREET EXTENSION IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12396,Roads,Completed,NC-MADHAVARAM,28,552000,"THE PROPOSED RELAYING OF BT ROAD AT RADHAMMAL STREET IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12397,Roads,Completed,NC-MADHAVARAM,28,386000,"THE PROPOSED RELAYING OF BT ROAD AT JAYALAKSHMI GARDEN CROSS STREET IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12398,Roads,Completed,NC-MADHAVARAM,28,610000,"THE PROPOSED RELAYING OF BT ROAD AT BANK COLONY 5TH STREET (JAYALAKSHMI GARDEN) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12399,Roads,Completed,NC-MADHAVARAM,28,752000,"THE PROPOSED RELAYING OF BT ROAD ATARUL NAGAR 2ND STREET IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12400,Roads,Completed,NC-MADHAVARAM,28,1038000,"THE PROPOSED RELAYING OF BT ROAD ATMEENACHI BHARATHI CO-OPERATIVE NAGAR IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/12401,Roads,Completed,NC-MADHAVARAM,28,386000,"THE PROPOSED RELAYING OF BT ROAD ATGANAPATHI NAGAR 3RD STREET IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12402,Roads,Completed,NC-MADHAVARAM,28,1685000,"THE PROPOSED RELAYING OF BT ROAD AT SASTHRI NAGAR IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12403,Roads,Completed,NC-MADHAVARAM,28,1051000,"THE PROPOSED RELAYING OF BT ROAD AT KUMARAN STREET IN DN-28, UNIT-7, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12404,Roads,Completed,NC-MADHAVARAM,28,2829000,"THE PROPOSED FORMING OF CC ROAD AT SASTHRI NAGAR (INSIDE BURIAL GROUND) IN DN-28, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/13118,Buildings,Completed,NC-MADHAVARAM,28,114000,"IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL AT PERIYASEKKADU PERUMAL KOIL STREET IN DIVISION-28, UNIT-7,ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/1628,Buildings,Completed,NC-MADHAVARAM,28,119000,CONSTRUCTIONN OF MULCH PIT AND PROVIDING WELL RING AT VARIOUS LOCATIONS IN DN-28 UNIT-7 ZONE-3,Own Sources,3,2019-20,2019-20 NC/2019-20/1629,Buildings,Completed,NC-MADHAVARAM,28,616000,PROVIDING WELL RINGS (PHASE-II) AT VARIOUS LOCATIONS IN DN-28 UNIT-7 ZONE-3,Own Sources,3,2019-20,2019-20 NC/2019-20/1865,Buildings,Completed,NC-MADHAVARAM,28,45000,"PROVIDING WATER SUPPLY ARRENGEMENTS AT SASTHRI NAGAR BURIL GROUND IN DIVISION-28, UNIT-7, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/1866,Buildings,Completed,NC-MADHAVARAM,28,200000,"IIMPROVEMENTS TO DIVISION -28 OFFICE AT ARUL NAGAR APPROACH ROAD IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2071,Buildings,Completed,NC-MADHAVARAM,28,710000,"PROVIDING WEIGHING MECHINE & VEGITABLE SHREDDER AT VARIOUS STREET IN DIVISION -28 & 29, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/5392,Buildings,Completed,NC-MADHAVARAM,28,136000,"Converted to rain water harvesting purpose the exisiting unused community Well at Anna Street (Inside Burial Ground)and periyasekkadu perumal koil street in Dn-28, Unit-07,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/5906,Buildings,Completed,NC-MADHAVARAM,28,592000,"DESILTING AND MINOR REPAIRS TO STORM WATER DRAIN AT M.M.C MAIN ROAD, SASTHRI NAGAR , ARUL NAGAR IN DIV-28, UNIT-7, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6002,Buildings,Completed,NC-MADHAVARAM,28,520000,"DESILTING AND MINOR REPAIRS TO SIDE DRAIN AT VARIOUS STREETS IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/7428,Buildings,Completed,NC-MADHAVARAM,28,410000,"ADDITIONAL WORK FOR 16 th CEREMONY HALL AT MOOLACHATRAM MAIN ROAD IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/7665,Buildings,Completed,NC-MADHAVARAM,28,81000,"PROVIDING RAINWATER HARVESTING USING WELL RINGS AT VARIOUS LOCATIONS IN DIV-28, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8130,Buildings,Completed,NC-MADHAVARAM,28,81000,"Attending Patch Work at Various Street in Division-28, Unit-7, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/8216,Roads,Completed,NC-MADHAVARAM,28,530000,"Providing Speed Breakers at Meenachi Bharathi Co-Operative Nagar phase-2 ,kumaran Street,Subramani Garden Main Street in Ward-28, Unit-7, Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8392,Roads,Completed,NC-MADHAVARAM,28,225000,"NEW FORMATION OF CC ROAD AT ANNA STREET (INSIDE OF BURIAL GROUND) IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8879,Buildings,Completed,NC-MADHAVARAM,28,538000,"SUPPLY OF 100Kg TO 150Kg MULTIPLE BAILING PRESS MACHINE ,TRANPORTATION , ERECTION AND COMMISSIONING , FITTING CHARGES 2 COATS OF ZINC,CHROME,2 COATS OF POLY URETHANE PAINT INCLUDING 18% GST AT SASTHRI NAGAR BURIAL GROUND IN DN-28 UNIT-7 ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/9669,Buildings,Completed,NC-MADHAVARAM,28,49000,"PROVIDING GALVANISED IRON SHEET SHED AT ANNA STREET BURIAL GROUND, WRITING NAME BOARD AT PERIYASAMI STREET IN DIV-28, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/9688,Buildings,Completed,NC-MADHAVARAM,28,95000,"PROVIDING AND SUPPLYING STAINLESS STEEL HANDRAIL AT SASTHRI NAGAR BURIAL GROUND IN DIV-28, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 Q/2019-20/11066,Buildings,Completed,Q-Solid Waste Management,28,24360000,"Construction of shed for setting windrow composting processing facility at a capacity of 50TPD at Madavaram, Zone-3",Own Sources,3,2019-20,2021-22 NC/2019-20/0860,Buildings,Completed,NC-MADHAVARAM,29,2332000,"CONSTRUCTION OF PARTITION WALL INSIDE BURIAL GROUND AT KARUNANIDHI STREET IN DN-29, UNIT-7,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/0904,Buildings,Completed,NC-MADHAVARAM,29,56000,"Improvements to Division Office in Div 29,Unit7,Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/0905,Buildings,Completed,NC-MADHAVARAM,29,38000,"Improvement works to compost yard at velu street in div 29,unit7, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/0908,Buildings,Completed,NC-MADHAVARAM,29,46000,"Improvements to karunanidhi street P.C in div 29,unit7, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/12413,Roads,Completed,NC-MADHAVARAM,29,883000,"THE PROPOSED FORMING OF CC ROAD AT KRISHNAN 3RD CROSS STREET IN DN-29, UNIT-7, ZONE-3",Grants,3,2019-20,2020-21 NC/2019-20/13125,Buildings,Completed,NC-MADHAVARAM,29,210000,"IMPROVEMENTS FOR RRC CENTRE AT KARUNANIDHI STREET IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/13126,Buildings,Completed,NC-MADHAVARAM,29,46000,"REPAIRS AND IMPROVEMEMTS FOR VERMI COMPOST YARD AT VELU STREET IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/13133,Buildings,Completed,NC-MADHAVARAM,29,8000,"REPAIRS AND IMPROVEMEMTS FOR PUBLIC CONVENIENCE AT EVR PERIYAR STREET IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/1630,Buildings,Completed,NC-MADHAVARAM,29,97000,PROVIDING WELL RINGS (PHASE-I) AT VARIOUS LOCATIONS IN DN-29 UNIT-7 ZONE-3,Own Sources,3,2019-20,2019-20 NC/2019-20/1887,Buildings,Completed,NC-MADHAVARAM,29,107000,PROVIDING WELL RINGS (PHASE-II) AT VARIOUS LOCATIONS IN DN-29 UNIT-7 ZONE-3,Own Sources,3,2019-20,2019-20 NC/2019-20/3131,Buildings,Completed,NC-MADHAVARAM,29,130000,"Providing Top slab at Various street in div 29,unit7, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/5916,Storm Water Drain,Completed,NC-MADHAVARAM,29,1820000,"DESILTING AND MINOR REPAIR TO STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-29, UNIT-7,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/6405,Buildings,Completed,NC-MADHAVARAM,29,1130000,"Construction of Cam Shredder Room at Velu street Compost yard in Division-29,Unit-7,Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6457,Buildings,Completed,NC-MADHAVARAM,29,75000,"Converted to rain water harvesting purpose the exisiting unused community Well at Munuswamy street in Dn-29, Unit-07,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/7707,Buildings,Completed,NC-MADHAVARAM,29,860000,"Improvements to the Existing Compost yard at Velu Street in Division-29, Unit-7, Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/7841,Buildings,Completed,NC-MADHAVARAM,29,216000,"IMPROVEMENTS FOR VERMI COMPOST YARD STORE ROM AT VELU STREET IN WARD-29, UNIT-7, ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/8136,Buildings,Completed,NC-MADHAVARAM,29,291000,"Attending Patch Work at Various Street in Division-29, Unit-7, Zone-3",Own Sources,3,2019-20,2019-20 NC/2019-20/8303,Buildings,Completed,NC-MADHAVARAM,29,284000,"REPAIRS AND MAINTENANCE FOR VERMI COMPOST YARD AT VELU STREET IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8337,Buildings,Completed,NC-MADHAVARAM,29,10000,"REPAIRS AND IMPROVEMENTS FOR GOVERNMENT HIGH SCHOOL AT DEVARAJAN STREET IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8384,Roads,Completed,NC-MADHAVARAM,29,895000,"NEW FORMATION OF CC ROAD AT VELU STREET (INSIDE OF VERMI COMPOST YARD) IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/9768,Buildings,Completed,NC-MADHAVARAM,29,25000,"PROVIDING RAIN WATER HARVESTING AT CHINNASAMY STREET AND PERUMAL KOIL EXTENT IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2019-20,2020-21 BR/2019-20/15775,Roads,Completed,BR-Bus Route Roads,30,502000,"Partly relaying the road with BC after cold milling by paver finisher at Madhavaram milk colony Road in Dn-30,27&28, Zone - 3",Grants,3,2019-20,2020-21 NC/2019-20/0997,Buildings,Completed,NC-MADHAVARAM,30,824000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT MRH ROAD AT JUNCTION OF SEETHAPATHY STREET IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/1008,Buildings,Completed,NC-MADHAVARAM,30,703000,"PROVIDING WELL RINGS (PHASE-II) IN VARIOUS LOCATIONS IN DIVISION-30, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/1009,Buildings,Completed,NC-MADHAVARAM,30,405000,"CONSTRUCTION OF MULCH PITS AND PROVIDING OF WELL RINGS (PHASE-I) IN DIVISION-30, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/10671,Roads,Completed,NC-MADHAVARAM,30,126000,"Relaying of BT Road at Victory field in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2021-22 NC/2019-20/10900,Buildings,Completed,NC-MADHAVARAM,30,270000,"Providing Shed for using BOV and maintainence work for unit office-8 at MRH Road In Division-30, Unit-8, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/10925,Roads,Completed,NC-MADHAVARAM,30,183000,"Relaying of BT Road at Thiruvalluvar 3rd cross Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2021-22 NC/2019-20/10973,Buildings,Completed,NC-MADHAVARAM,30,55000,"Repairs to Side drain at Rajaji Street and Padmavathyb nagar main road in Division-30, Unit-8, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/11007,Buildings,Completed,NC-MADHAVARAM,30,100000,"Maintenance for Chennai Primary School at Rajaji Street in Division-30, Unit-8, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/11036,Roads,Completed,NC-MADHAVARAM,30,75000,"Providing Street Name Board at Various street in dn -30,unit-08,zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/11213,Roads,Completed,NC-MADHAVARAM,30,183000,"Relaying of BT Road at Thiruvalluvar 2nd cross Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2021-22 NC/2019-20/11215,Roads,Completed,NC-MADHAVARAM,30,183000,"Relaying of BT Road at Thiruvalluvar 1st cross Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2021-22 NC/2019-20/14468,Roads,Completed,NC-MADHAVARAM,30,395000,"Relaying of BT Road at Pukraj nagar 2nd main Road 3rd Annexure in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14471,Roads,Completed,NC-MADHAVARAM,30,822000,"Relaying of BT road at Pukraj nagar 3rd main Road in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14476,Roads,Completed,NC-MADHAVARAM,30,575000,"Relaying of BT Road at VRD Nagar 4th Cross Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14477,Roads,Completed,NC-MADHAVARAM,30,665000,"Relaying of BT Road At VRD Nagar 5th cross Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14481,Roads,Completed,NC-MADHAVARAM,30,198000,"Relaying of BT Road at Pukraj nagar 1st Cross Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14482,Roads,Completed,NC-MADHAVARAM,30,569000,"Relaying of BT Road At Pukraj nagar 1st Street Annexure in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14484,Roads,Completed,NC-MADHAVARAM,30,266000,"Relaying of BT Road at Thanthai Periyar Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14486,Roads,Completed,NC-MADHAVARAM,30,98000,"Relaying of BT Road at S.V.Koil Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/14497,Roads,Completed,NC-MADHAVARAM,30,918000,"Relaying of CC Road at Rajaji Street in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/2452,Buildings,Completed,NC-MADHAVARAM,30,360000,"DEMOLITION OF DAMAGED OLD COMPOUND WALL AND CONSTRUCTION OF NEW COMPOUND WALL AT SIVASAKTHI NAGAR IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2639,Buildings,Completed,NC-MADHAVARAM,30,183000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT MASILAMANI NAGAR RESOURCE RECOVERY CENTER IN DIVISION- 30, UNIT-8, ZONE - 3",Own Sources,3,2019-20,2019-20 NC/2019-20/2641,Buildings,Completed,NC-MADHAVARAM,30,16300,"BORE FLUSHING AND MOTOR REPAIR WORK IN RING ROAD HOUSING SECTOR LORRY SHED IN DIV-30, UNIT-8, ZONE - 3",Own Sources,3,2019-20,2019-20 NC/2019-20/2643,Buildings,Completed,NC-MADHAVARAM,30,59000,"MOTOR REPAIR WORK AND TILES REPAIR WORK AT VRD NAGAR PARK IN DIV-30, UNIT-8, ZONE- 3",Own Sources,3,2019-20,2019-20 NC/2019-20/3041,Buildings,Completed,NC-MADHAVARAM,30,101000,"BORE FLUSHING AND MOTOR REPAIR WORK AT BHARATHIYAR STREET PC & MADHAVARAM BUS TERMINAL PC IN DIV-30, UNIT-8,ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/3043,Buildings,Completed,NC-MADHAVARAM,30,49000,"IMPROVEMENTS OF SIDE DRAIN WORK AT BHARATHIYAR STREET IN DIV-30, UNIT-8,ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/4741,Buildings,Completed,NC-MADHAVARAM,30,389000,"CONVERTING TO RAIN WATER HARVESTING PURPOSE FOR THE EXISTING UNUSED COMMUNITY WELL AT MRH ROAD JUNCTION OF SEETHAPATHY STREET IN DN-30, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/5978,Storm Water Drain,Completed,NC-MADHAVARAM,30,528000,"Desilting and Improvement of Side Drain VRD nagar main road, Pukraj nagar 4th street, Pukraj nagar 6th street, Aringer Anna street, M.R.H. Road (From T.V.K 1st street to Ring Road Housing Sector) storm water drian IN DIV-, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6035,Storm Water Drain,Completed,NC-MADHAVARAM,30,396000,"Desilting and Improvement of Side Drain Pukraj nagar to conneting road , Bharathiyar main road , Bharathiyar street extn., Mariamman koil street, S.V koil street, Rajaji street , Mohan garden, padamavathi nagar main road, padamavathi nagar 1st main road , padamavathi nagar 2nd main road, Madhavaarm milk colony road, IN DIV-, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6392,Culvert,Completed,NC-MADHAVARAM,30,135000,"Converting to rain water harvesting purpose for the exisiting unused community well at pukraj nagar 3rd mainroad in Dn-30, Unit-8,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/7551,Parks,Completed,NC-MADHAVARAM,30,621000,"Annual Maintenance for Sivasakthi nagar Park at Sivasakthi Nagar 2nd Main road in Div-30, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8117,Roads,Completed,NC-MADHAVARAM,30,592000,"Attending Pot Holes At Aringer Anna street, Thanthai Periyar street, Bharathiyar Street, S.v koil street and other street in Dn-30 Unit-8 Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8220,Parks,Completed,NC-MADHAVARAM,30,597000,"Annual Maintenance for KVT (Phase III) Park at V.S Mani Nagar in Div-30, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8222,Parks,Completed,NC-MADHAVARAM,30,242000,"Annual Maintenance for KVT (Phase II) Park at V.S Mani Nagar in Div-30, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8225,Parks,Completed,NC-MADHAVARAM,30,931000,"Annual Maintenance for VRD Nagar Park at VRD Nagar 1st street in Div-30, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8226,Parks,Completed,NC-MADHAVARAM,30,583000,"Annual Maintenance for KVT (Phase I) Park at V.S Mani Nagar in Div-30, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8227,Parks,Completed,NC-MADHAVARAM,30,730000,"Annual Maintenance for Ring Road Housing Sector Park at Ring Road Housing Sector 1st Main Road in Div-30, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8228,Parks,Completed,NC-MADHAVARAM,30,577000,"Annual Maintenance for RC flats (Arul Nagar) Park at MMC Main Road in Div-30, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8860,Buildings,Completed,NC-MADHAVARAM,30,538000,"Supply of 100kg to 150kg multiple baling Press machine, Transportaion, Erection and Commissioning, Fitting Charges 2 Coats of Zinc Chrome, 2 Coats of Polyurethane paint including 18% GST at Masilamani Nagar Resource Recovery Center in Division-30, Unit-8, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/9812,Roads,Completed,NC-MADHAVARAM,30,56000,"Relaying of BT Road at Rajaji street North in Division-30, Unit-8, Zone-3.",Grants,3,2019-20,2021-22 NC/2019-20/11025,Buildings,Completed,NC-MADHAVARAM,31,146000,"Improvement works for side drain and providing precast slab at Thiruvalluvar, Pandain st Various location in Div-31, Unit-8, Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/11026,Buildings,Completed,NC-MADHAVARAM,31,275000,"IMPROVEMENT AND RAISING OF SIDE DRAIN AT KANNABIRAN KOVIL ST (STAGE) IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/11027,Buildings,Completed,NC-MADHAVARAM,31,79000,"Improvement Works to Divison Office at Palaniappa nagar 5th st Dn-31, unit-8, Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/11208,Buildings,Completed,NC-MADHAVARAM,31,179000,"DISMANTALING EXISTING DAMAGED CONDITION OF COMMUNITY TOILET AT KOLKATTA SHOP ROAD DIV-31,UNIT-8,ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/12499,Buildings,Completed,NC-MADHAVARAM,31,295000,"Improvement works to KKR Garden Park by providing Coloured Pebbles Stone Work in Div-31, Unit-8, Zone-3",Own Sources,3,2019-20,2020-21 NC/2019-20/14447,Roads,Completed,NC-MADHAVARAM,31,253000,"Relaying of Damaged road at KKR garden 4th main road in DN-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14457,Roads,Completed,NC-MADHAVARAM,31,65000,"Relaying of Damaged road at T.V.K 2nd Street in DN-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14460,Roads,Completed,NC-MADHAVARAM,31,453000,"Road cut Restoration work at Ambedkar nagar 3rd main road in Dn-31, Unit-8, zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14462,Roads,Completed,NC-MADHAVARAM,31,140000,"Relaying of Damaged road at Udaiyar thottam 5th street in DN-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14466,Roads,Completed,NC-MADHAVARAM,31,231000,"Relaying of Damaged road at Francis colony 3rd main road in DN-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14469,Roads,Completed,NC-MADHAVARAM,31,108000,"Relaying of Damaged road at Francis colony 2nd street in DN-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14475,Roads,Completed,NC-MADHAVARAM,31,730000,"Road cut Restoration at Rizwan road in Dn-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14479,Roads,Completed,NC-MADHAVARAM,31,461000,"Relaying of Damaged road at Palaniappa nagar 5th street in DN-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/14488,Roads,Completed,NC-MADHAVARAM,31,357000,"Relaying of CC road at V.O.C Cross street in Dn-31, Unit-8, Zone-3",Grants,3,2019-20,2020-21 NC/2019-20/15700,Buildings,Completed,NC-MADHAVARAM,31,160000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PARK AT KKR GARDEN (Area=4315) IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/15731,Buildings,Completed,NC-MADHAVARAM,31,312000,"PROVIDING WATER SUPPLY ARRANGEMENT TO PARK AT KKR NAGAR (Area=4035m2) IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/1921,Buildings,Completed,NC-MADHAVARAM,31,176000,"CONSTRUCTION OF MULCH PIT AND PROVIDING OF WELL RINGS (PHASE-1) AT VARIOUS STREETS IN DIVISION-31, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/1924,Buildings,Completed,NC-MADHAVARAM,31,530000,"PROVIDING WELL RINGS (PHASE-II) AT VARIOUS STREETS IN DIVISION-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2054,Buildings,Completed,NC-MADHAVARAM,31,770000,"PROVIDING WEIGHING MECHINE & VEGITABLE SHREDDER MECHINE AT VARIOUS STREET IN DIVISION - 30 TO 33, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2526,Buildings,Completed,NC-MADHAVARAM,31,663000,"NAME OF WORK: IMPROVEMENTS WORKS TO BURIAL GROUND AT MUTHUMARIAMMAN KOVIL ST IN Div-31,Unit-8,Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2528,Buildings,Completed,NC-MADHAVARAM,31,546000,"PROVIDING COMPOUND WALL FOR SOURCE SEGREGATION AT (Back side of PC ) KOLKATTA SHOP BURIAL GROUND IN Div-31,Unit-8,Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/2531,Buildings,Completed,NC-MADHAVARAM,31,153000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT KKR ESTATE IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2533,Buildings,Completed,NC-MADHAVARAM,31,153000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT BURIAL GROUND IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2539,Buildings,Completed,NC-MADHAVARAM,31,153000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT KOLKATTA SHOP IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2541,Bridges,Completed,NC-MADHAVARAM,31,153000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT KANNABIRAN KOVIL ST IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2543,Buildings,Completed,NC-MADHAVARAM,31,153000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT MAA.POO.VEDHA STREET IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2544,Buildings,Completed,NC-MADHAVARAM,31,153000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT AMBEDKAR NAGAR 2ND MAIN ROAD IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2644,Buildings,Completed,NC-MADHAVARAM,31,97000,"BORE FLUSING AND MOTOR REPAIR WORK AT VARIOUS LOCATION IN DIV-31, UNIT-8, ZONE -3",Own Sources,3,2019-20,2019-20 NC/2019-20/5996,Roads,Completed,NC-MADHAVARAM,31,678000,"Desilting of Strom Water Drain at M.R.H. Road (From Moolakadai to T.V.K 1st street) IN DIV-31, UNIT-8, ZONE-3 (2019)",Own Sources,3,2019-20,2019-20 NC/2019-20/5997,Storm Water Drain,Completed,NC-MADHAVARAM,31,658000,"Desilting of Side Drain and Strom Water Drain at Udaiayar Thottam 7th St, MMC Road, Vinayagar Koil St, Pandian St, Muthumariamman Koil St,Nagathamman kovil street, Ambedkar nagar main road, Udaiyar thottam 6th street, KKR Garden 2nd Main Road, Dhansingh meastry street, T.V.K 1st street, Jangiri Shop, Thiruvalluvar street, V.O.C street, T.V.k 5th street, Kannabiran Koil Street, Palaniappa nagar 5th street, Rizwan road , Kannapuram 1st street , KKR Garden 10TH Street, T.V.K 6th street, K.P Garden, Dhansingh meastry street, Pandian street, KKR Nagar 2nd main road , IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/8119,Roads,Completed,NC-MADHAVARAM,31,272000,"Attending Pot Holes At Muthumariamman Koil st, Kolkatta Shop, KKR Garden, Ambedhkar Nagar, KKR Nagar and other street in Dn-31 Unit-8 Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8230,Parks,Completed,NC-MADHAVARAM,31,1162000,"Annual Maintenance for KKR Garden Park at KKR Garden 2nd Main Road in Div-31, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8233,Parks,Completed,NC-MADHAVARAM,31,1314000,"Annual Maintenance for KKR Nagar Park at KKR Nagar 1st Main Road in Div-31, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8234,Parks,Completed,NC-MADHAVARAM,31,236000,"Annual Maintenance for RC Flats Park at MRH Road in Div-31, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/11015,Buildings,Completed,NC-MADHAVARAM,32,56000,Repairs and Maintenance work in amma unavagam at villivakkam road in Dn-32 Unit -8 Zone -3.,Own Sources,3,2019-20,2020-21 NC/2019-20/11017,Bridges,Completed,NC-MADHAVARAM,32,79000,"Providing Street Furniture at Kamarajar Street and Thilakar street in dn -32,unit-08,zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/11051,Buildings,Completed,NC-MADHAVARAM,32,29000,"Providing partition arrangements around to well ring near Ashoka street in div-32, Unit-8, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/12461,Roads,Completed,NC-MADHAVARAM,32,584000,"Relaying of Existing BT Road at Annai Parasakthi Nagar in Dn-32, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12525,Roads,Completed,NC-MADHAVARAM,32,532000,"Relaying of Existing BT Road at Kalaimagal Nagar Extn in Dn-32, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12526,Roads,Completed,NC-MADHAVARAM,32,307000,"Relaying of Existing BT Road at Sarathi Nagar1st Street in Dn-32, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12528,Roads,Completed,NC-MADHAVARAM,32,394000,"Relaying of Existing BT Road at Sarathi Nagar Extn in Dn-32, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12530,Roads,Completed,NC-MADHAVARAM,32,642000,"Relaying of Existing BT Road at Sarathy Nagar 2nd Street in Dn-32, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/12532,Roads,Completed,NC-MADHAVARAM,32,342000,"Relaying of Existing BT Road at Sarathy Nagar 3rd Street in Dn-32, Unit-8, Zone-3.",Grants,3,2019-20,2020-21 NC/2019-20/1926,Buildings,Completed,NC-MADHAVARAM,32,90000,"CONSTRUCTION OF MULCH PIT AND PROVIDING OF WELL RINGS (PHASE-I) AT VARIOUS STREET IN DIVISION-32, UNIT-8 ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/1928,Buildings,Completed,NC-MADHAVARAM,32,812000,"PROVIDING WELL RINGS (PHASE-II) AT VARIOUS STREET IN DIVISION-32, UNIT-8 ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/2546,Buildings,Completed,NC-MADHAVARAM,32,199000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO SCHOOL AT L.N PERUMAL KOVIL ST IN DN-32, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2547,Buildings,Completed,NC-MADHAVARAM,32,274000,"NAME OF WORK: PROVIDING WATER SUPPLY ARRANGEMENT TO PC AT ASHOKA STREET INDN-32, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2952,Buildings,Completed,NC-MADHAVARAM,32,57000,"NAME OF WORK: REPAIRS TO SIDE DRIAN AT KUMARAN STREET & GANGAIAMMAN KOVIL AT-32, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2958,Buildings,Completed,NC-MADHAVARAM,32,25000,"PAINTING WORK FOR NNMP SHED IN CHENNAI PRIMARY SCHOOL AT L.N PERUMAL KOVIL ST IN DN-32, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2959,Buildings,Completed,NC-MADHAVARAM,32,16900,"PLUMBING WORK IN CHENNAI HIGHER SECONDARY SCHOOL AT BHARATHIYAR KOVIL STREET DN-32, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2964,Buildings,Completed,NC-MADHAVARAM,32,20200,"NAME OF WORK : REPAIR TO MOTOR TEACHERS COLONY 7TH MAIN ROAD (Old division office) IN DN-32, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/2966,Buildings,Completed,NC-MADHAVARAM,32,36900,"NAME OF WORK : WATER SUPPLY ARRANGEMENTS TO DIVISION OFFICE (KADAPPA ROAD) AND AMMA UNAVAGAM ( GANGAI AMMAN KOVIL ST ) AT DN-31, UNIT-8,ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/4738,Buildings,Completed,NC-MADHAVARAM,32,183000,"PROVIDING WATER SUPPLY ARRANGEMENT TO UPHC AT GANGAIAMMAN KOVIL STREET IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/6033,Storm Water Drain,Completed,NC-MADHAVARAM,32,854000,"Desilting and Improvements of Side Drain at LNP kovil st, Bharathiyar st, Vivekanandha st, Nethaji st, Rajaji st, Kumaran st, Thilagar st, VOC st, Kalaingnar st & Gangaiamman kovil st, in div-32, Unit-8, Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/6034,Storm Water Drain,Completed,NC-MADHAVARAM,32,473000,"Desilting and improvements of Side Drain at Teachers Colony, Thiruvalluvar st, Sankaralingam st, EVR st, Amman kovil st, Villivakkam Road, Bajanai kovil st, Ashoka st, Kadapa road & Kamarajar st in div-32, unit-8, Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/7957,Bridges,Completed,NC-MADHAVARAM,32,660000,"PROPOSED CONSTRUCTION OF RETAINING WALL AT AMMAN KOVIL STREET IN DIV-32, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/8120,Roads,Completed,NC-MADHAVARAM,32,390000,"Attending Pot Holes At kadappa road, sarathi nagar , venkateswar nagar, teachers colony and others Street in Dn-32 Unit-8 Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8235,Parks,Completed,NC-MADHAVARAM,32,856000,"Annual Maintenance for Teacher's Colony Park at Teacher's Colony 4th cross street in Div-32, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8236,Parks,Completed,NC-MADHAVARAM,32,600000,"Annual Maintenance for Teacher's Colony Park at Teacher's Colony 6th main road in Div-32, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/9108,Storm Water Drain,Completed,NC-MADHAVARAM,32,46000,"Providing inlet chamber at Teachers Colony 4th main road In Dn -32, Unit -8, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/9123,Buildings,Completed,NC-MADHAVARAM,32,180000,Repairs & Improvements in CHSS School at Bharathiyar street in Dn -32 unit -8 zone 3.,Own Sources,3,2019-20,2020-21 NC/2019-20/9141,Buildings,Completed,NC-MADHAVARAM,32,110000,Repairs and Improvements in CMS School at LNP kovil street in Dn -32 Unit -8 Zone-3.,Own Sources,3,2019-20,2020-21 L/2019-20/8166,Electrical,Completed,L-Electrical,33,8795500,"Provision of 147 Nos of 6mtr lamp post, single straight bracket with 40w LED fitting at AVM Avenue, Dilli Avenue,various streets, 22 Nos of 6mtr lamppost with 90w LED fitting at 80 feet road & 6 Nos of 8mtr straight bracket with 150w LED fitting at TH Road in Div-28,29,32 & 33 of Zone-III (Madhavaram)",Grants,3,2019-20,2020-21 NC/2019-20/0919,Buildings,Completed,NC-MADHAVARAM,33,198000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO PARK AT SELVAM NAGAR EXTN IN DIV-33, UNIT - 8, ZONE - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/0921,Buildings,Completed,NC-MADHAVARAM,33,198000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO PARK AT THANIKACHALAM NAGAR 5/2 CROSS STREET IN DIV-33, UNIT - 8, ZONE - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/10548,Buildings,Completed,NC-MADHAVARAM,33,264000,"ADDITIONAL WORK & PROVIDING OF WELL RINGS FOR COMPOSED YARD RRC INSIDE BURIAL GOURND AT VALLIAMMAI NAGAR MAINROAD IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/10927,Buildings,Completed,NC-MADHAVARAM,33,216000,"Additional Damaged road at Rajaji 5th Cross Street in Div-33, Unit-8, Zone -3",Grants,3,2019-20,2021-22 NC/2019-20/10954,Buildings,Completed,NC-MADHAVARAM,33,56000,"MINOR REPAIRS WORK TO ANGANVADI (INSIDE CPS) AT NEHRU STREET IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2019-20,2020-21 NC/2019-20/11254,Buildings,Completed,NC-MADHAVARAM,33,344000,"PROVIDING WATER SUPPLY, DRINAGE AND ELECTRICAL ARRANGEMENTS TO RRC AND IMPROVEMENTS TO RRC AT VALLIAMMAI NAGAR IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/12431,Roads,Completed,NC-MADHAVARAM,33,559000,"RELAYING OF BT ROAD AT MOHAN NAGAR 1ST STREET IN DIV-33, UNIT-8, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12432,Roads,Completed,NC-MADHAVARAM,33,697000,"ROAD CUT RESORATION OF BT ROAD AT BALAKRISHNA NAGAR 2nd STREET IN DIV-33, UNIT-8, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12434,Roads,Completed,NC-MADHAVARAM,33,186000,"RELAYING OF BT ROAD AT VIDHYA NAGAR 1ST CROSS STREET IN DIV-33, UNIT-8, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12511,Roads,Completed,NC-MADHAVARAM,33,526000,"RELAYING OF BT ROAD AT PRAKASH NAGAR 4TH MAINROAD IN DIV-33, UNIT-8, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12517,Roads,Completed,NC-MADHAVARAM,33,452000,"RELAYING OF BT ROAD AT PRAKASH NAGAR 11th STREET IN DIV-33, UNIT-8, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/12519,Roads,Completed,NC-MADHAVARAM,33,170000,"RELAYING OF BT ROAD AT PRAKASH NAGAR 12th STREET IN DIV-33, UNIT-8, ZONE-3.",Grants,3,2019-20,2020-21 NC/2019-20/13976,Buildings,Completed,NC-MADHAVARAM,33,398000,"Additional Damaged Road at Thanikachalam Nagar A Block 2nd Mainroad Part in Div-33, Unit-8, Zone -3",Grants,3,2019-20,2021-22 NC/2019-20/14001,Buildings,Completed,NC-MADHAVARAM,33,617000,"Additional Damaged road at Thanikachalam Nagar A Block 2nd Mainroad 1st Cross Street in Div-33, Unit-8, Zone - 3",Grants,3,2019-20,2021-22 NC/2019-20/14004,Buildings,Completed,NC-MADHAVARAM,33,367000,"Additional Damaged Road at Thanikachalam Nagar A Block 1st Cross Street in Div-33, Unit-8, Zone -3",Grants,3,2019-20,2021-22 NC/2019-20/1592,Buildings,Completed,NC-MADHAVARAM,33,453000,"PROVIDING WELL RING AT VARIOUS STREET (PHASE II) IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/1601,Buildings,Completed,NC-MADHAVARAM,33,211000,"PROVIDING WELL RING & MULCH PIT AT VARIOUS STREET & PARKS (PHASE I) IN DIV-33, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/4933,Buildings,Completed,NC-MADHAVARAM,33,523000,"Additional Damaged road at Thanikachalam Nagar E Block Rajaji 1st Cross Street in Div-33, Unit-8, Zone -3",Grants,3,2019-20,2021-22 NC/2019-20/5171,Roads,Completed,NC-MADHAVARAM,33,408000,"Additional Damaged Road at Thanikachalam nagar E blk Rajaji 2nd Cross Street in Div-33, Unit-8, Zone -3",Grants,3,2019-20,2021-22 NC/2019-20/6004,Storm Water Drain,Completed,NC-MADHAVARAM,33,722000,"DESILTING OF STROM WATER DRAIN AT BALAKRISHNA NAGAR MAIN ROAD, VPC NAGAR MAIN ROAD, ANNAPOORNA NAGAR MAIN ROAD, PERIYAR NAGAR MAIN ROAD, VIDHYA NAGAR MAIN ROAD, SRINIVASA NAGAR MAIN ROAD, PRAKASH NAGAR 1ST MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6006,Roads,Completed,NC-MADHAVARAM,33,413000,"DESILTING OF SIDE DRAIN AT THANIKACHALAM NAGAR 'A' BLOCK 2ND MAIN ROAD, THANIKACHALAM NAGAR 'A' BLOCK 1ST MAIN ROAD & THANIKACHALAM NAGAR 5/2 CROSS STREET, SRIRAM SALAI & VASUDEVA THOTTAM, RAMALINGA COLONY 'B' BLOCK MAIN ROAD & CROSS STREETS &RAMALINGA COLONY 'C' BLOCK MAIN ROAD & CROSS STREETS & Selvam Nagar 6/3 Cross street IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6010,Buildings,Completed,NC-MADHAVARAM,33,598000,"DESILTING OF SIDE DRAIN AT SARANGAPANI STREET & SUNDARAMURHTY STREET, THIRUVALLUVAR STREET, SELVAM NAGAR MAIN ROAD & SELVAM NAGAR 2ND MAIN ROAD IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6011,Roads,Completed,NC-MADHAVARAM,33,258000,"DESILTING AND IMPROVEMENTS OF SIDE DRAIN AT VGP NAGAR MAIN ROAD, KAMARAJAR WEST & MAHATMA GANDHI STREET IN DIV-33, UNIT-8, ZONE-3",Own Sources,3,2019-20,2019-20 NC/2019-20/6394,Buildings,Completed,NC-MADHAVARAM,33,250000,"Converting to rain water harvesting purpose for the exisiting unused community well at Annai sathya nagar and vasudevan thottam in Dn-33, Unit-8,Zone-03.",Own Sources,3,2019-20,2020-21 NC/2019-20/8123,Roads,Completed,NC-MADHAVARAM,33,461000,"Attending Pot Holes At Thanikachalam Nagar 80 feet road, Selvam Nagar, Anna street, VGP Nagar, Anna Poorni Nagar and other street in Dn-33 Unit-8 Zone-3.",Own Sources,3,2019-20,2019-20 NC/2019-20/8237,Parks,Completed,NC-MADHAVARAM,33,682000,"Annual Maintenance for Thanikachalam nagar Park Thanikachalam nagar 'B' block 5/2 cross street in Div-33, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8239,Parks,Completed,NC-MADHAVARAM,33,608000,"Annual Maintenance for Selvam Nagar Park Selvam Nagar in Div-33, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8243,Parks,Completed,NC-MADHAVARAM,33,603000,"Annual Maintenance for VGP Nagar Park VGP Nagar Main Road in Div-33, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8244,Parks,Completed,NC-MADHAVARAM,33,612000,"Annual Maintenance for Thanikachalam Nagar Park at Thanikachalam Nagar 80 feet road in Div-33, Unit-8, Zone - 3",Own Sources,3,2019-20,2020-21 NC/2019-20/8338,Roads,Completed,NC-MADHAVARAM,33,91200,"Restoration of Road Cut at Chandra Prabhu Colony 7th Main Road in Div-33, Unit - 8, Zone -3",Deposit Works,3,2019-20,2020-21 NC/2019-20/8878,Buildings,Completed,NC-MADHAVARAM,33,538000,"Supply of 100kg to 150kg multiple baling Press machine, Transportaion, Erection and Commissioning, Fitting Charges 2 Coats of Zinc Chrome, 2 Coats of Polyurethane paint including 18% GST at Prakesh Nager Burial ground in Division-33, Unit-8, Zone-3.",Own Sources,3,2019-20,2020-21 NC/2019-20/9024,Roads,Completed,NC-MADHAVARAM,33,80000,"Restoration of Road Cut at Prakash Nagar Main Road in Div-33, Unit - 8, Zone -3",Deposit Works,3,2019-20,2020-21 NC/2019-20/9656,Buildings,Completed,NC-MADHAVARAM,33,180000,"IMPROVEMENTS AND REPAIR WORK TO PUBLIC CONVENIENCE AT VASUDEVAN THOTTAM IN DN 33, UNIT-8, ZONE-3.",Own Sources,3,2019-20,2020-21 BR/2019-20/4133,Road Cut,Completed,BR-Bus Route Roads,34,450000,"REstoration of Roadcut made by OFC Operators at VNM Street, Kadumbadiamman Koil Street, Union carbide Colony 14th Street, Union carbide Colony 18th Street, Jambuli Street, Damodhar Street, Govindasamy Nagar 2nd Main Road in Dn-34, Unit-9, Zone-IV",Deposit Works,4,2019-20,2019-20 ND/2019-20/11543,Roads,Completed,ND-TONDIARPET,34,821000,"Roadcut Restoration of CC road at Jambuli Street main in DN-34, U-09, Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/13649,Roads,Completed,ND-TONDIARPET,34,581000,"Relaying of BT road at Demote Avenue main road in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13653,Roads,Completed,ND-TONDIARPET,34,991000,"Relaying of BT road at Ravi Garden Main Road in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13655,Roads,Completed,ND-TONDIARPET,34,332000,"Relaying of BT road at Ravi Garden 1st street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13667,Roads,Completed,ND-TONDIARPET,34,307000,"Relaying of BT road at Ravi Garden 2nd street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13669,Roads,Completed,ND-TONDIARPET,34,312000,"Relaying of BT road at Ravi Garden 3rd Street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13671,Roads,Completed,ND-TONDIARPET,34,290000,"Relaying of BT road at Ravi Garden 4th Street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13672,Roads,Completed,ND-TONDIARPET,34,768000,"Relaying of BT road at Durgai Avenue 13th Street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13673,Roads,Completed,ND-TONDIARPET,34,364000,"Relaying of BT road at Sasthiri Nagar Extn. in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13674,Roads,Completed,ND-TONDIARPET,34,309000,"Relaying of BT road at Badragiri Nagar 1st Street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13677,Roads,Completed,ND-TONDIARPET,34,360000,"Relaying of BT road at Badragiri Nagar 2nd Street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13678,Roads,Completed,ND-TONDIARPET,34,521009,"Formation of BT road at S.R. 1st Extn in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13680,Roads,Completed,ND-TONDIARPET,34,539009,"Formation of BT road at S.R. 2nd Extn in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13684,Roads,Completed,ND-TONDIARPET,34,342000,"Relaying of BT road at Seetharam Nagar 1st Street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/13692,Roads,Completed,ND-TONDIARPET,34,358000,"Roadcut Restoration of BT road at Dhamodharan Street in Dn-34, U-09, Z-IV.",Own Sources,4,2019-20,2020-21 ND/2019-20/1902,Buildings,Completed,ND-TONDIARPET,34,89500,"Constructing of Bamboo Mulch pit at Various location in DN-34, Unit-09, Zone-IV.",Own Sources,4,2019-20,2019-20 ND/2019-20/1916,Buildings,Completed,ND-TONDIARPET,34,500000,"Construction of Well Ring at Various location in DN-34, Unit-09, Zone-IV.",Own Sources,4,2019-20,2019-20 ND/2019-20/1929,Buildings,Completed,ND-TONDIARPET,34,6800,"Installation of Sintex tank at Various Places in DN-34, Unit-09, Zone-IV.",Own Sources,4,2019-20,2019-20 ND/2019-20/2066,Buildings,Completed,ND-TONDIARPET,34,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT VAZHUTHALAI MEDU IN DN- 34, U- 09, Z-IV",Own Sources,4,2019-20,2019-20 ND/2019-20/3725,Parks,Completed,P-Parks and Playfields,34,854000,"Plantation of maintenance of tree saplings for one year at various street in DN-34,37 U-09,Z-04 (Total No of Trees-318Nos)",Own Sources,4,2019-20,2019-20 ND/2019-20/4061,Buildings,Completed,ND-TONDIARPET,34,960000,"CONSTRUCTION OF RAIN WATER HARVESTING AT UNION CARBIDE COLONY POND IN DN-34, U-09, Z-IV",Own Sources,4,2019-20,2019-20 ND/2019-20/6143,Storm Water Drain,Completed,ND-TONDIARPET,34,1072000,"Desilting of Storm Water Drain and Minor Repairs at Various Location in Dn-34, U-09, Z-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/7579,Parks,Completed,ND-TONDIARPET,34,614000,"Annual Maintenance for Park at Binny nagar main road park in division-34, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7584,Parks,Completed,ND-TONDIARPET,34,610000,"Annual Maintenance for Park at venkateshwara colony in division-34, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7587,Parks,Completed,ND-TONDIARPET,34,585000,"Annual Maintenance for Park at Union carbide colony 14th street in division-34, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2021-22 ND/2019-20/7591,Parks,Completed,ND-TONDIARPET,34,705000,"Annual Maintenance for Park at Kaveri nagar park in division-34, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2021-22 ND/2019-20/7592,Parks,Completed,ND-TONDIARPET,34,683000,"Annual Maintenance for Park at Unian corbite colony 9th street in division-34, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7772,Parks,Completed,ND-TONDIARPET,34,120000,"Maintenance of park at Binny Nagar Main Road, Venkateshwara colony v street, Union carbide colony 14th street, Kaveri Nagar in division-34, Unit-9, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7774,Parks,Completed,ND-TONDIARPET,34,34000,"Maintenance of park at Carbite colony 9th street in division-34, Unit-09, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7938,Roads,Completed,ND-TONDIARPET,34,300000,"ATTENDING PATCH WORKS AT VARIOUS LOCATION IN DN-34, U-09, Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/8484,Buildings,Completed,ND-TONDIARPET,34,984000,"Construction of Additional compost pit at Arul nagar Compost yard in Dn-34, U-09, Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/9039,Buildings,Completed,ND-TONDIARPET,34,2926000,"Construction of compost yard at Seetharam Nagar Burial Ground in Dn-34, U-09, Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/9730,Buildings,Completed,ND-TONDIARPET,34,1289000,"Construction of compost yard at Vazhuthalai medu in Dn-34, U-09, Z-04",Own Sources,4,2019-20,2021-22 Q/2019-20/0088,Buildings,Completed,Q-Solid Waste Management,34,9990000,REMOVAL OF GARBAGE AND CONSTRUCTION DEBRIS ALONG THE COOVUM RIVER BANKS FROM THE BAY OF BENGAL MOUTH OF THE COOVUM RIVER TO THE MADURAVAYAL BYEPASS WITHIN THE CHENNAI CORP LIMIT - CRRT,Own Sources,4,2019-20,2019-20 Q/2019-20/11072,Buildings,Completed,Q-Solid Waste Management,34,6030000,"Construction of Shed for the installation and processing of Garden waste and tender Coconut shell at Kodungaiyur Dumping ground in Division-37, Zone-4",Own Sources,4,2019-20,2020-21 Q/2019-20/1513,Buildings,Completed,Q-Solid Waste Management,34,986000,"Proposed construction of Ramp at Additional Weigh Bridge & Monitoring at Main enterance of inside Kodungaiyur Dumping ground in Dn-34, Z-4",Own Sources,4,2019-20,2020-21 Q/2019-20/1516,Buildings,Completed,Q-Solid Waste Management,34,535000,"Construction of Sump and Septic tank for Additional Weigh Bridge inside Kodungaiyur Dumping ground in Div-34, Z-4",Own Sources,4,2019-20,2020-21 BR/2019-20/10012,Road Cut,Completed,BR-Bus Route Roads,35,257000,"Attending OFC Roadcut Restoration at various locations (Meenambal salai, AA Scheme Road, Kamarajar Salai, Stephens Road,Ethiraj Samy Salai, ) in Zone - IV. Deposit Code - 57/1145/2018-19.",Deposit Works,4,2019-20,2019-20 BR/2019-20/15779,Roads,Completed,BR-Bus Route Roads,35,602000,"Partly relaying the road with BC after cold milling by paver finisher at Thiruvalluvar Salai in Dn-35, Zone - 4",Grants,4,2019-20,2020-21 BR/2019-20/15780,Roads,Completed,BR-Bus Route Roads,35,1505000,"Partly relaying the road with BC after cold milling by paver finisher at North Avenue Road in Dn-35, Zone -4",Grants,4,2019-20,2020-21 BR/2019-20/4410,Road Cut,Completed,BR-Bus Route Roads,35,450000,"REstoration of Roadcut made by OFC Operators at Various Street in Dn-35, Unit-9, Zone-IV",Deposit Works,4,2019-20,2019-20 BR/2019-20/7905,Roads,Completed,BR-Bus Route Roads,35,900000,"ATTENDING PATCHES AT VARIOUS LOCATIONS IN T.H ROAD, MOORTHINGAR SALAI, CENTRAL AVENUE ROAD in DN. 35, 37 & 45 , Zone - 4",Own Sources,4,2019-20,2019-20 ND/2019-20/0808,Buildings,Completed,ND-TONDIARPET,35,585000,"Improvements to Multipurpose hall Compound Wall and ILP at Sharma Nagar 1st main road IN DN-36, Unit-9, Zone-4",Own Sources,4,2019-20,2019-20 ND/2019-20/0814,Buildings,Completed,ND-TONDIARPET,35,493000,"Improvements to Multipurpose Hall at Sharma Nagar 1st Main Road in Div-35 ,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/10314,Playfields,Completed,ND-TONDIARPET,35,252000,"Repair and Improvements to the Play field at Muthamizh nagar 126th street In Div-35, Unit-9, Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/11542,Roads,Completed,ND-TONDIARPET,35,853000,"Relaying of Cement Concrete Road at Om Sakthi Vinagakar Kovil Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11547,Roads,Completed,ND-TONDIARPET,35,556000,"Relaying of Cement Concrete Road at Muthami Nagar 3rd Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11548,Roads,Completed,ND-TONDIARPET,35,400000,"Relaying of Cement Concrete Road at Muthami Nagar 4th Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11550,Roads,Completed,ND-TONDIARPET,35,486000,"Relaying of Cement Concrete Road at Manavalakar Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11551,Roads,Completed,ND-TONDIARPET,35,197000,afe5rtyh,Own Sources,4,2019-20,2020-21 ND/2019-20/11576,Roads,Completed,ND-TONDIARPET,35,632000,"Relaying of BT Road at Gandhi Nagar 1st Street (By Hot Mix Plant) in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11577,Roads,Completed,ND-TONDIARPET,35,351000,"Relaying of BT Road at KKD Nagar 1st Main Road (Partly) in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11578,Roads,Completed,ND-TONDIARPET,35,447000,"Relaying of BT Road at KKD Nagar 2ND Main Road (Partly) in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11579,Roads,Completed,ND-TONDIARPET,35,302000,"Relaying of BT Road at Muthamil Nagar 11th Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11580,Roads,Completed,ND-TONDIARPET,35,412000,"Relaying of BT Road at Muthamil Nagar 97th Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11581,Roads,Completed,ND-TONDIARPET,35,346000,"Relaying of BT Road at Muthamil Nagar 67th Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11582,Roads,Completed,ND-TONDIARPET,35,1450000,"Relaying of BT Road at Krishnamoorthy Salai in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11583,Roads,Completed,ND-TONDIARPET,35,500007,"Relaying of BT Road at KKD Nagar 3rd Main Road in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11584,Roads,Completed,ND-TONDIARPET,35,435893,"Relaying of BT Road at KKD Nagar 4th Block 4th Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11585,Roads,Completed,ND-TONDIARPET,35,315095,"Relaying of BT Road at Muthamil Nagar South Avenue Road in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11630,Roads,Completed,ND-TONDIARPET,35,659000,"Providing and laying Interlocking Paver Blocks at Kamaraj Salai Lanes In Div-35, Unit-9, Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/15578,Buildings,Completed,ND-TONDIARPET,35,819000,"Supply and Fixing Baling Machines at R.C.C Center in Ward-35, Unit-09, Zone-4",Own Sources,4,2019-20,2021-22 ND/2019-20/1645,Buildings,Completed,ND-TONDIARPET,35,294000,"PROPOSED CONSTRUCTION OF MATERIAL RESOURCE RECOVERY FACILITY MICRO COMPOSING CENTRE AT 50TH STREET,MUTHAMIL NAGAR,IN DIV-35, UNIT-9, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/1969,Parks,Completed,ND-TONDIARPET,35,319000,"Installation of well ring at various location in div-35,unit-09,zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1972,Buildings,Completed,ND-TONDIARPET,35,1700,"Installation of Sintex Tank at Various Location in Dn-35, Unit-09, Zone-IV",Own Sources,4,2019-20,2019-20 ND/2019-20/2448,Buildings,Completed,ND-TONDIARPET,35,200000,"Repair and Improvements to Anganwadi Maiyam Center No:( 33603120601&33603120614) at Muthamil Nagar South Avenue Road in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/2908,Buildings,Completed,ND-TONDIARPET,35,180000,"Erection of Bore well 60 m Depth with Water Supply Arrangements at Chennai High School (Erukkanchery) in Div-35,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/2923,Buildings,Completed,ND-TONDIARPET,35,180000,"Erection of Bore well 60 m Depth with Water Supply Arrangements at Chennai Middle School (Chinnadimadam) in Div-35,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/5671,Parks,Completed,ND-TONDIARPET,35,123000,"Providing rain water harvesting at Muthamil nagar 9th street park, Krishnan street park in division-35, unit-09, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/6139,Storm Water Drain,Completed,ND-TONDIARPET,35,1400000,"Desilting of Exsiting Storm Water Drain at Thiruvalluvar salai,Kumaran street,Anna salai main street,srinivasa perumal koil street ,k.k.d.nagar 5th block 5th street,Abirami avenue 6th street ,M.k.ponnan street,E.V.R. salai Erukkanchery, Cavery salai Main Street, Sidco 1st main road, Sidco 2nd main road,Sidco 3rd main road,Kannabiran koil street,Kamatchiamman Kovil Street,Vadiudaiamman koil st,Krishnan street and gandhi nagar main road,ambedkar street (erukkenchery),Anna salai cross street,Kandhasamy kovil street,Chandran Street,Manavalakar Street,Tondierpet high road (BRR) in Div -35,Unit -09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/7614,Parks,Completed,ND-TONDIARPET,35,795000,"Maintenance Estimate for Park at Hansa Garden GNT Road in division-35, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7617,Parks,Completed,ND-TONDIARPET,35,605000,"Maintenance Estimate for Park at Muthamil Nagar 9th Street in division-35, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7619,Parks,Completed,ND-TONDIARPET,35,644000,"Maintenance Estimate for Park at Krishnan Street OSR Park in division-35, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2021-22 ND/2019-20/7757,Parks,Completed,ND-TONDIARPET,35,66000,"Maintenance of park at Krishnan street OSR (RC Appt), Muthamizh Nagar 9th street in division-35, Unit-09, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7775,Parks,Completed,ND-TONDIARPET,35,31000,"Maintenance of GNT road (Erukanchery) park in division-35, Unit-09, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7949,Roads,Completed,ND-TONDIARPET,35,376000,"Attending Patch Works At Various Location in Div-35,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/8173,Buildings,Completed,ND-TONDIARPET,35,132000,"Providing Rain Water Harvesting Structures at various locations in Dn-35, Unit-9, Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/8175,Buildings,Completed,ND-TONDIARPET,35,168000,"Repairs and Improvements to C.P.S at Annasalai in Dn-35, Unit-9, Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/8524,Roads,Completed,ND-TONDIARPET,35,1242000,"Road Cut Restoration at KKD Nagar 6th Main Road in Div-35,Unit-09,Zone-04.",Deposit Works,4,2019-20,2020-21 ND/2019-20/8992,Buildings,Completed,ND-TONDIARPET,35,188000,Repair and Mainenance to Exisiting Annxure Building at Dr.Anna salai Kodungaiyur in Div-35 Unit-9 Zone-4,Own Sources,4,2019-20,2021-22 ND/2019-20/9625,Buildings,Completed,ND-TONDIARPET,35,144000,"Imporvements to RRC Center at Angugam Nagar (EVR Salai) in div-35,unit-09,zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/9629,Buildings,Completed,ND-TONDIARPET,35,300000,"Improvements to RRC Center at Muthamil Nagar 50th street in Div-35, Unit-09, Zone-04.",Own Sources,4,2019-20,2021-22 ND/2019-20/9898,Buildings,Completed,ND-TONDIARPET,35,1127000,"IMPROVEMNTS TO COMPOST YARD AT ANJUGAM NAGAR (EVR SALAI) DN- 35 , UNIT- 09 , Z0NE-04",Own Sources,4,2019-20,2021-22 ND/2019-20/9900,Buildings,Completed,ND-TONDIARPET,35,1690000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT MUTHAMIL NAGAR 7TH BLOCK, 10 TH MAIN RAOD (CANAL EAST SIDE ) IN DN- 35 , UNIT- 09 , ZONE- 04",Own Sources,4,2019-20,2021-22 ND/2019-20/9945,Buildings,Completed,ND-TONDIARPET,35,1690000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT MUTHAMIL NAGAR 8TH BLOCK, 201TH STREET IN DN- 35 , UNIT- 09 , ZONE-04",Own Sources,4,2019-20,2021-22 BR/2019-20/10014,Roads,Completed,BR-Bus Route Roads,36,93000,Attending OFC Roadcut Restoration at various locations(Meenambal Salai) in Zone - 4. Deposit code - 57/1143/2018-19.,Deposit Works,4,2019-20,2019-20 BR/2019-20/15783,Roads,Completed,BR-Bus Route Roads,36,753000,"Partly relaying the road with BC after cold milling by paver finisher at Sidco Main Road in Dn-36, Zone -4",Grants,4,2019-20,2020-21 BR/2019-20/18220,Road Cut,Completed,BR-Bus Route Roads,36,933000,"Restoration of Road cut made by OFC operators various Road in Div-36, Unit - 09, Zone - 4.",Deposit Works,4,2019-20,2021-22 BR/2019-20/5350,Roads,Completed,BR-Bus Route Roads,36,5812000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Ethiraj Samy Salai in Dn-36, Zone - IV",Grants,4,2019-20,2020-21 L/2019-20/7543,Electrical,Completed,L-Electrical,36,191600,"Supply and Erection of 4nos KIOSk PILLAR BOX and Removal of 4 nos Damaged kiosk pillar at Thiruvalluvar nagar 1st main road ,Raniammaiyar street,M.P.M Road in division -36 & 44,zone -4.",Own Sources,4,2019-20,2020-21 ND/2019-20/11575,Roads,Completed,ND-TONDIARPET,36,1170000,"Relaying of CC Road at Sastri Nagar 16th Street in Div-36,Unit-09,Zone-04",Own Sources,4,2019-20,2020-21 ND/2019-20/13287,Buildings,Completed,ND-TONDIARPET,36,277000,Maintanence Work For Health Building at Sharmanagar 1st Main Road in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/13292,Buildings,Completed,ND-TONDIARPET,36,105000,Maintanence Work For Bridge at Thiruvalluvar Nagar in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/13293,Buildings,Completed,ND-TONDIARPET,36,62000,Maintanence Work For Hospital at Apper Street in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/13294,Roads,Completed,ND-TONDIARPET,36,56000,Maintanence Work at SA Colony 3rd Street in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/1900,Buildings,Completed,ND-TONDIARPET,36,104000,installation of Bamboo Mulch Pit at Various Location in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2019-20 ND/2019-20/1903,Buildings,Completed,ND-TONDIARPET,36,139000,Installation Well Rings at Various Location in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2019-20 ND/2019-20/1911,Buildings,Completed,ND-TONDIARPET,36,11700,Providing Sintax Tank at Various Location in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2019-20 ND/2019-20/2413,Buildings,Completed,ND-TONDIARPET,36,200000,Improvement NNMP Shed at Karunanithi salai 2nd street in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2019-20 ND/2019-20/2851,Buildings,Completed,ND-TONDIARPET,36,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT SHARMA NAGAR 2ND MAIN ROAD CHS IN DIVISION-36, UNIT-9, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/5673,Parks,Completed,ND-TONDIARPET,36,485000,"Providing rain water harvestingand other improvements to Vasugi nagar park, M.R nagar park, Sharma nagar 3rd main road park in division-36, unit-09, zone-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/6140,Storm Water Drain,Completed,ND-TONDIARPET,36,329000,Storm Water Drain Desilting Work at Various Streets in Dn-36 U-09 Z-04,Own Sources,4,2019-20,2019-20 ND/2019-20/7461,Electrical,Completed,ND-TONDIARPET,36,357600,"Supply and fixing of 4 Nos. of 1.5 Ton Spilt Air Conditioner and 8 Nos. of CCTV Camera at Multipurpose Building in Sharma Nagar Ist Main Road in Dn:36, Zone IV",Own Sources,4,2019-20,2019-20 ND/2019-20/7629,Buildings,Completed,ND-TONDIARPET,36,611100,"Maintenance Estimate for Park at Indhira gandhi nagar park in division-36, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2021-22 ND/2019-20/7630,Buildings,Completed,ND-TONDIARPET,36,245000,"Maintenance Estimate for Park at Bharathy nagar V street in division-36, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7631,Buildings,Completed,ND-TONDIARPET,36,645000,"Maintenance Estimate for Park at vasuki nagar in division-36, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7632,Buildings,Completed,ND-TONDIARPET,36,643100,"Maintenance Estimate for Park at M.R nagar in division-36, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7657,Buildings,Completed,ND-TONDIARPET,36,684000,"Maintenance Estimate for Park at Sharma nagar 1st main road in division-36, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7659,Buildings,Completed,ND-TONDIARPET,36,615000,"Maintenance Estimate for Park at Sharma nagar 3rd main road in division-36, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7660,Buildings,Completed,ND-TONDIARPET,36,601000,"Maintenance Estimate for Park at 14th west cross street in division-36, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7759,Parks,Completed,ND-TONDIARPET,36,87000,"Maintenance of park at Bharathi nagar V street, Vasugi nagar, M.R nagar park in division-36, Unit-09, Zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/7760,Parks,Completed,ND-TONDIARPET,36,24700,"Maintenance of park at Indira Nagar, E.H road in division-36, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7761,Parks,Completed,ND-TONDIARPET,36,65000,"Maintenance of park at Sharma Nagar 1st main road, 14th west cross (MKB nagar ) street in division-36, Unit-09, Zone-4(2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7762,Parks,Completed,ND-TONDIARPET,36,32000,"Maintenance of park at Sharma nagar 3rd main road in division-36, Unit-9, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7937,Roads,Completed,ND-TONDIARPET,36,126000,"Pot hole for various roads in Division-36,Unit-09,Zone-04",Own Sources,4,2019-20,2019-20 BR/2019-20/10013,Roads,Completed,BR-Bus Route Roads,37,568000,"Attending OFC Roadcut Restoration works at various location (Sathankadai Road, TH Road, MKB Nagar, TH Road-Kodungaitur, Washermenpet, Tiruvottiyur High Road, MS Kovil ) in zone - 4. Deposit code - 57/1053/2018-19",Deposit Works,4,2019-20,2019-20 BR/2019-20/15781,Roads,Completed,BR-Bus Route Roads,37,602000,"Partly relaying the road with BC after cold milling by paver finisher at MKB Central Avenue Road in Dn-37, Zone - 4",Grants,4,2019-20,2020-21 BR/2019-20/15782,Roads,Completed,BR-Bus Route Roads,37,602000,"Partly relaying the road with BC after cold milling by paver finisher at MKB West Avenue Road in Dn-37, Zone - 4",Grants,4,2019-20,2020-21 BR/2019-20/16241,Roads,Completed,BR-Bus Route Roads,37,199000,"Removing and Re-fixing of 1 no of modern Bus shelter at Central Avenue MKB Nagar towards Mullai Nagar in Dn-37, Unit-9, Zone-IV",Own Sources,4,2019-20,2020-21 BR/2019-20/3864,Road Cut,Completed,BR-Bus Route Roads,37,959000,Supplying and Fixing of Digital Awarness Bunner in the Stainless Steel Bus Shelters for Lokh Sabha Election 2019 in Various Bus Route roads in Zone-IV,Own Sources,4,2019-20,2019-20 BR/2019-20/5337,Roads,Completed,BR-Bus Route Roads,37,6847000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Meenambal Salai (From T.H.Road to Gandhi Street) in Dn-37, Zone - IV",Grants,4,2019-20,2020-21 BR/2019-20/5347,Roads,Completed,BR-Bus Route Roads,37,6911000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Kamarajar Salai (From jn of Thiruvalluvar Salai to Pandian Theatre) in Dn-35, Zone - IV",Grants,4,2019-20,2020-21 L/2019-20/8428,Electrical,Completed,L-Electrical,37,18938600,"Replacement of Rusted old street lamp posts by 491 Nos. of New G.I. Street Lamp posts at Various locations in Dn: 37, 45 & 46, Zone IV.",Grants,4,2019-20,2021-22 ND/2019-20/12832,Roads,Completed,ND-TONDIARPET,37,105000,"Laying of Cement Concrete Road at Nesavalar Colony 1st Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12833,Roads,Completed,ND-TONDIARPET,37,157000,"Laying of Cement Concrete Road at Nesavalar Colony 2nd Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12834,Roads,Completed,ND-TONDIARPET,37,98000,"Laying of Cement Concrete Road at Nesavalar Colony 3rd Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12835,Roads,Completed,ND-TONDIARPET,37,105000,"Laying of Cement Concrete Road at Nesavalar Colony 4th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12836,Roads,Completed,ND-TONDIARPET,37,187000,"Laying of Cement Concrete Road at Nesavalar Colony 5th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12837,Roads,Completed,ND-TONDIARPET,37,105000,"Laying of Cement Concrete Road at Nesavalar Colony 6th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12838,Roads,Completed,ND-TONDIARPET,37,187000,"Laying of Cement Concrete Road at Nesavalar Colony 7th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12839,Roads,Completed,ND-TONDIARPET,37,164000,"Laying of Cement Concrete Road at Nesavalar Colony 8th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12840,Roads,Completed,ND-TONDIARPET,37,105000,"Laying of Cement Concrete Road at Nesavalar Colony 9th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12841,Roads,Completed,ND-TONDIARPET,37,105000,"Laying of Cement Concrete Road at Nesavalar Colony 10th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12842,Roads,Completed,ND-TONDIARPET,37,190000,"Laying of Cement Concrete Road at Nesavalar Colony 11tht Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12843,Roads,Completed,ND-TONDIARPET,37,170000,"Laying of Cement Concrete Road at Nesavalar Colony 12tht Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12844,Roads,Completed,ND-TONDIARPET,37,105000,"Laying of Cement Concrete Road at Nesavalar Colony 13th Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12845,Roads,Completed,ND-TONDIARPET,37,433000,"Laying of Cement Concrete Road at Golden Complex 1st Sector in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12846,Roads,Completed,ND-TONDIARPET,37,473000,"Laying of Cement Concrete Road at Golden Complex 2nd Sector in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12847,Roads,Completed,ND-TONDIARPET,37,656000,"Laying of Cement Concrete Road at Golden Complex 3rd Sector in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12875,Roads,Completed,ND-TONDIARPET,37,2118000,"Laying of Cement Concrete Road at RR Nagar 1st Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12876,Roads,Completed,ND-TONDIARPET,37,1765000,"Laying of Cement Concrete Road at RR Nagar 2ND Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12878,Roads,Completed,ND-TONDIARPET,37,726000,"Laying of Cement Concrete Road at KKD Nagar 9th block 2nd Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12879,Roads,Completed,ND-TONDIARPET,37,2374000,"Laying of Cement Concrete Road at RR Nagar F Block in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12880,Roads,Completed,ND-TONDIARPET,37,736000,"Laying of Cement Concrete Road at MKB Nagar 18th East Cross Street in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/12882,Roads,Completed,ND-TONDIARPET,37,860000,"Laying of Cement Concrete Road at RR Nagar 6th Main Road in Div-37,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/14071,Buildings,Completed,ND-TONDIARPET,37,20000,Maintanence Work at Amma unavagam MKB Nagar 3rd main road Detail Estimate in Dn-37 U-09 Z-04.,Own Sources,4,2019-20,2020-21 ND/2019-20/14072,Buildings,Completed,ND-TONDIARPET,37,62000,Maintanence Work at Multipurpose hall SM Nagar main road in Dn-37 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/14075,Buildings,Completed,ND-TONDIARPET,37,165000,Maintanence Work at MKB Nagar 4th cross street Divison Office in Dn-37 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/14076,Buildings,Completed,ND-TONDIARPET,37,107000,Maintanence Work at MGR NAGAR Primary School in Dn-37 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/14077,Buildings,Completed,ND-TONDIARPET,37,50000,Maintanence Work at MKB Nagar 14th east cross street UPHC in Dn-37 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/14080,Buildings,Completed,ND-TONDIARPET,37,48000,Maintanence Work at Mullai nagar Burial ground compost yard in Dn-37 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/14081,Buildings,Completed,ND-TONDIARPET,37,48000,Maintanence Work at North avenue road compost yard in Dn-37 U-09 Z-04,Own Sources,4,2019-20,2020-21 ND/2019-20/17303,Roads,Completed,ND-TONDIARPET,37,1590000,"Relaying of BT Road at MKB Nagar 1st main road in Div-37, Unit-09, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/1905,Parks,Completed,ND-TONDIARPET,37,148800,"Installation of Bamboo Mulch Pit at Various location in Dn-37, Unit-09, Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1920,Parks,Completed,ND-TONDIARPET,37,11800,"Sintex tank at Various location in Dn-37, Unit-09, Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1923,Parks,Completed,ND-TONDIARPET,37,461000,"Installation of Well Ring at Various location in div 37, unit-09, zone-4",Own Sources,4,2019-20,2019-20 ND/2019-20/1965,Parks,Completed,ND-TONDIARPET,37,45000,"Installation Bamboo Mulch Pit at Various location in Dn-35, Unit-09, Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/2843,Buildings,Completed,ND-TONDIARPET,37,542000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT MKB NAGAR 14TH EAST CROSS STREET,MGR NAGAR CPS, RR NAGAR CPS CPS IN DIVISION-37, UNIT-09, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/5676,Parks,Completed,ND-TONDIARPET,37,246000,"Providing rain water harvesting at Mullai nagar burigal ground park, Jawahar street park, Srinivasan street park in division-37, unit-09, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/6220,Storm Water Drain,Completed,ND-TONDIARPET,37,2465210,"Storm water drain desilting and minor repair work at various street in division-37,Unit-09,Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6336,Storm Water Drain,Completed,ND-TONDIARPET,37,1248380,"Storm water drain desilting and minor repair work at various street in division-37,Unit-09,Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/7110,Storm Water Drain,Completed,ND-TONDIARPET,37,1267000,"Removal Of Floating Material / Obstruction Weeds Hyacinth / Garbage / Plastic Items, thermo Coal etc at Captain Cotton Canal in Div-37&41, Unit-09&10, Zone-04(From MKB Nagar Bridge to Mullai Nagar Bridge and B Canal to Mullai nagar bridge)",Own Sources,4,2019-20,2019-20 ND/2019-20/7606,Buildings,Completed,ND-TONDIARPET,37,2100000,"Maintenance Estimate for Park at Mullai nagar burial ground in division-37, unit-9, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/7607,Buildings,Completed,ND-TONDIARPET,37,236000,"Maintenance Estimate for Park at Kannadasan nagar 7th block in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7608,Buildings,Completed,ND-TONDIARPET,37,253000,"Maintenance Estimate for Park at Lingesan street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7609,Buildings,Completed,ND-TONDIARPET,37,654000,"Maintenance Estimate for Park at Jawahar street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7610,Buildings,Completed,ND-TONDIARPET,37,243000,"Maintenance Estimate for Park at Vivekanatha street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7611,Buildings,Completed,ND-TONDIARPET,37,253000,"Maintenance Estimate for Park at Ambedkar nagar in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7612,Buildings,Completed,ND-TONDIARPET,37,602000,"Maintenance Estimate for Park at Sasirekamma nagar in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7622,Buildings,Completed,ND-TONDIARPET,37,258000,"Maintenance Estimate for Park at Srinivasan street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7623,Buildings,Completed,ND-TONDIARPET,37,242000,"Maintenance Estimate for Park at Gandhi street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7624,Buildings,Completed,ND-TONDIARPET,37,708000,"Maintenance Estimate for Park at MKB Nagar 13th east cross street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7626,Buildings,Completed,ND-TONDIARPET,37,631000,"Maintenance Estimate for Park at MKB Nagar 16th east cross street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7627,Parks,Completed,ND-TONDIARPET,37,623000,"Maintenance Estimate for Park at 4th cross street in division-37, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7765,Parks,Completed,ND-TONDIARPET,37,263000,"Maintenance of park at Lingesan Street, Jawahar Street, Vivekananda Street, Ambedkar Street, Sasirekamma Nagar, Srinivasan Street, Gandhi Street, 13th Cross Street MKB Nagar, 16th West cross street MKB Nagar, 4th Cross street MKB Nagar in division-37, Unit-09, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7766,Parks,Completed,ND-TONDIARPET,37,121000,"Maintenance of park at Mullai Nagar in division-37, Unit-09, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7778,Parks,Completed,ND-TONDIARPET,37,24700,"Maintenance of park at Kannadasan Nagar 7th block in division-37, Unit-9, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7935,Roads,Completed,ND-TONDIARPET,37,314000,"Pot hole various for roads in Division-37,Unit-09,Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/9684,Buildings,Completed,ND-TONDIARPET,37,977000,"Construction of RRC at MKB Nagar 4th cross street in Div-37,Unit-09,Zone-04",Own Sources,4,2019-20,2020-21 ND/2019-20/9805,Buildings,Completed,ND-TONDIARPET,37,3600000,"Construction of Sump at Kodungaiyur Dumping Ground in Div-37,unit-09,Zone-04",Own Sources,4,2019-20,2020-21 ND/2019-20/9894,Buildings,Completed,ND-TONDIARPET,37,8500000,"Construction of Multi composting center Backside of weigh bridge west side at KDG in divison-37,unit -09, zone-04",Own Sources,4,2019-20,2021-22 ND/2019-20/9919,Buildings,Completed,ND-TONDIARPET,37,3729000,"Constrcution of new Compost Yard at Mullai nagar burial ground in div-37 unit-09, Zone-4",Own Sources,4,2019-20,2021-22 Q/2019-20/11071,Buildings,Completed,Q-Solid Waste Management,37,3580000,"Providing Concrete pavement for installation ad processing of Garden Waste and Tender Coconut Shell at Kodungaiyur Dumping ground in Division-37, Zone -4",Own Sources,4,2019-20,2020-21 Q/2019-20/14012,Electrical,Completed,Q-Solid Waste Management,37,1600000,"Construction of Electrical Panel Room for garden garbage and tender coconut processing facility at Kodungaiyur Dumping Ground in Dn-37, Zone-4",Own Sources,4,2019-20,2020-21 BR/2019-20/15784,Roads,Completed,BR-Bus Route Roads,38,401000,"Partly relaying the road with BC after cold milling by paver finisher at Vaithiyanathan Bridge Road in Dn-38, Zone - 4",Grants,4,2019-20,2020-21 L/2019-20/7449,Electrical,Completed,L-Electrical,38,195600,Raising of 24Nos. of Kiosk Pillar box at Various Locations in Dn:34 to 47 in Zone IV,Own Sources,4,2019-20,2021-22 L/2019-20/7525,Electrical,Completed,L-Electrical,38,176900,"Replacement of 5 Nos. of Rusted, Damaged Pillar Box by New Kiosk Pillar Box at Various Locations in DN:38,39,40&43, Zone IV",Own Sources,4,2019-20,2020-21 ND/2019-20/11552,Roads,Completed,ND-TONDIARPET,38,561000,"Relaying of BT Road at Vinoba Nagar 1st street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11644,Roads,Completed,ND-TONDIARPET,38,888000,"Relaying of BT Road at Vinoba Nagar 3rd street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11645,Roads,Completed,ND-TONDIARPET,38,610000,"Relaying of BT Road at Vinoba Nagar 4th street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11646,Roads,Completed,ND-TONDIARPET,38,836000,"Relaying of BT Road at Vinoba Nagar 5th street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11647,Roads,Completed,ND-TONDIARPET,38,334000,"Relaying of BT Road at New Vinoba Nagar 1st street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11648,Roads,Completed,ND-TONDIARPET,38,620000,"Relaying of BT Road at Nehru Nagar 12th street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11649,Roads,Completed,ND-TONDIARPET,38,323000,"Relaying of BT Road at Nethaji Nagar A street Extn in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11650,Roads,Completed,ND-TONDIARPET,38,886000,"Relaying of BT Road at Nethaji Nagar 1st cross street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11651,Roads,Completed,ND-TONDIARPET,38,895000,"Relaying of BT Road at Vaithiyanathan street (Part) in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11652,Roads,Completed,ND-TONDIARPET,38,835000,"Relaying of BT Road at Navalar Nagar A street in Div-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/1860,Buildings,Completed,ND-TONDIARPET,38,198000,"CONSTRUCTION OF WELL RING AT ANNAI SANTHIYA NAGAR GYM BUILDING,CANAL ROAD,NEHRU NAGAR 14TH STREET SASTHIRI NAGAR IN DIVISION - 38, UNIT - 09, ZONE - 04.",Own Sources,4,2019-20,2019-20 ND/2019-20/1949,Parks,Completed,ND-TONDIARPET,38,74500,"Construction of Mulch pit at mulch pit at Nehru Nagar,Prince Village 1 2,Patel Nagar park in Division-38, Unit-09, Zone-4",Own Sources,4,2019-20,2019-20 ND/2019-20/1955,Parks,Completed,ND-TONDIARPET,38,8500,"Providing sintex tank at prince village phase I,prince village phase II,patel Nagar park,Nehru Nagar park,Nehru Nagar 14th street in DN-38,U-09,Z-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/2067,Buildings,Completed,ND-TONDIARPET,38,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT VAITHIYANADHAN BRIDGE DOWN IN DN- 38, U- 09, Z-IV",Own Sources,4,2019-20,2019-20 ND/2019-20/2849,Buildings,Completed,ND-TONDIARPET,38,221000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CPS PATEL NAGAR SCHOOL IN DIVISION-38, UNIT-09, ZONE-04",Own Sources,4,2019-20,2019-20 ND/2019-20/2850,Buildings,Completed,ND-TONDIARPET,38,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CHSS PATEL NAGAR SCHOOL IN DIVISION-38, UNIT-09, ZONE-04",Own Sources,4,2019-20,2019-20 ND/2019-20/4399,Buildings,Completed,ND-TONDIARPET,38,2076660,"CONSTRUCTION OF DINING HALL AT CHSS IN PATEL NAGAR IN DN-38, U-09, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4790,Buildings,Completed,ND-TONDIARPET,38,2550000,"Construction of multipurpose hall at Vinoba nagar 2nd street in dn-38, unit-9, zone-04",MLACDS,4,2019-20,2020-21 ND/2019-20/5677,Parks,Completed,ND-TONDIARPET,38,61000,"Providing rain water harvesting at Nehru nagar park in division-38, unit-09, zone-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/6187,Storm Water Drain,Completed,ND-TONDIARPET,38,2132400,"Desilting of Strom Water Drain at Various Streets in Dn-38,U-09,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/7123,Buildings,Completed,ND-TONDIARPET,38,1300000,"Removal of Floating Material / Obstruction Weeds Hyacinth / Garbages / Plastic items,Thermo coal etc at Ennore High Road (From Jn of E.C.I.School to CISF Main Gate) in Dn-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/7197,Buildings,Completed,ND-TONDIARPET,38,90000,"Repairs and Improvements of NNMP Shed at Nethaji Nagar 6th Street in Dn-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/7200,Storm Water Drain,Completed,ND-TONDIARPET,38,243000,"Demolishing of Existing Compound wall and Re construction in NNMP at Nehru Nagar 14th Street Dn-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/7201,Buildings,Completed,ND-TONDIARPET,38,220000,"Impovements Work in Nehru Nagar Main road ICDS in Dn-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/7646,Buildings,Completed,ND-TONDIARPET,38,1545000,"Maintenance of Park at patel nagar in division-38, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7647,Buildings,Completed,ND-TONDIARPET,38,955000,"Maintenance of Park at Nehru nagar in division-38, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7648,Buildings,Completed,ND-TONDIARPET,38,895000,"Maintenance of Park at Ellaya street OSR phase II in division-38, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7649,Buildings,Completed,ND-TONDIARPET,38,909000,"Maintenance of Park at Ellaya street OSR phase I in division-38, unit-9, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7752,Parks,Completed,ND-TONDIARPET,38,127000,"Maintenance of park at Patel Nagar in division-38, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7753,Parks,Completed,ND-TONDIARPET,38,91000,"Maintenance of park at Nehru Nagar in division-38, Unit-9, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7771,Parks,Completed,ND-TONDIARPET,38,66000,"Maintenance of park at (Prince phase-II) in division-38,Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7777,Parks,Completed,ND-TONDIARPET,38,95000,"Maintenance of park at Elaya Street OSR (Prince) in division-38, Unit-9, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7924,Buildings,Completed,ND-TONDIARPET,38,1744000,"Attending Patch work at Ennore High Road & Elaya Street in Dn-38,Unit-09,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/8246,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at patel Nagar 4th street Center No: 33603120701 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8252,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Anna Street Center No: 33603120701 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8263,Buildings,Completed,ND-TONDIARPET,38,500000,"Providing and Fixing RO plant at Patel Nagar Corporation School Laboratory Building in Div-38, Ut-09, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8264,Buildings,Completed,ND-TONDIARPET,38,500000,"Providing and Fixing RO plant at Patel Nagar Corporation Primary School Building in Div-38, Ut-09, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8265,Buildings,Completed,ND-TONDIARPET,38,500000,"Providing and Fixing RO plant at Patel Nagar Corporation High School Building in Div-38, Ut-09, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8268,Buildings,Completed,ND-TONDIARPET,38,500000,"Providing and Fixing RO plant at T H Road Corporation Girls Higher Secondary School in Div-42, Ut-10, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8271,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at New vioba Nagar 1st street Center No: 33603120714 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8272,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at New Vinoba 11th Street Center No: 3360312076 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8274,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at 1Vinoba Nagar 11th Street Center No: 33603120713 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8275,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Karunanithi Nagar 1st Street Center No: 33603120709 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8276,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Karunanithi nagar 1st street Center No: 33603120708 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8277,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Navalar Nagar Kudiiruppu Center No: 33603120813 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8278,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Nethaji 14th Street Center No: 33603120812 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8279,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Nethaji 14th Street Center No: 33603120810 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8280,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Nethaji 14th Street Center No: 33603120811 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8281,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Nethaji 6th Street Center No: 33603120712 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8282,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Nethaji 6th Street Center No: 33603120710 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8283,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Nethaji 6th Street Center No: 33603120703 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8284,Buildings,Completed,ND-TONDIARPET,38,201000,"providing water supply arrangements to ICDS at Nethaji 6th Street Center No: 33603120702 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8285,Buildings,Completed,ND-TONDIARPET,38,201000,"Providing water supply arrangements to ICDS at Nethaji 6th Street Center No: 33603120701 in Div-38,Unit-09,Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8432,Buildings,Completed,ND-TONDIARPET,38,500000,"Providing gym equipments to Annai santhiya nagar gym in Div-38, Unit-09, Zone-04",MLACDS,4,2019-20,2020-21 ND/2019-20/9571,Buildings,Completed,ND-TONDIARPET,38,967000,"CONSTRUCTION OF NEW BIO GAS PLANT 0.15 TPD CAPACITY AT ICDS NEW VINOBA NAGAR IN DN 38, UNIT 09,ZONE IV",Own Sources,4,2019-20,2021-22 ND/2019-20/9599,Buildings,Completed,ND-TONDIARPET,38,2097000,"Proposed construction of source segregation centre at canal Road Near Nehru Nagar 14th Street Extension in Division38,Unit-09,Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/9639,Buildings,Completed,ND-TONDIARPET,38,2097000,"Proposed construction of source segregation centre at canal Road Near Thamizan Nagar in Division38,Unit-09,Zone-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/9641,Buildings,Completed,ND-TONDIARPET,38,1340000,"Proposed construction of source segregation centre at Annai Santhiya Nagar NearGym Building Inside in Division38,Unit-09,Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/9643,Buildings,Completed,ND-TONDIARPET,38,798000,"Proposed construction of source segregation centre at Sastri Nagar Main Road Near Third Bridge in Division38,Unit-09,Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/9895,Buildings,Completed,ND-TONDIARPET,38,4468000,construction of Compost Yard at canal road near Thamilar Nagar in div-38 unit-09. Zone-4,Own Sources,4,2019-20,2021-22 BR/2019-20/10807,Roads,Completed,BR-Bus Route Roads,39,106000,Attendind OFC Roadcut Restoration at various loactions (North Terminus Road) in Zone - V. Dposit code-57/0582/2017-18,Deposit Works,4,2019-20,2019-20 BR/2019-20/15785,Roads,Completed,BR-Bus Route Roads,39,250000,"Partly relaying the road with BC after cold milling by paver finisher at North Terminus Road in Dn-39, Zone -4",Grants,4,2019-20,2020-21 L/2019-20/8729,Electrical,Completed,L-Electrical,39,2889500,"CMRL DEPOSIT WORK: Provision of 21 Nos.of 8 Mtr G.I Lamp Post with double bracket at T.H Road from (Tolgate junction to Cross Road junction) due to Metro Rail Work in Dn:39, Zone IV.",Deposit Works,4,2019-20,2021-22 ND/2019-20/2834,Buildings,Completed,ND-TONDIARPET,39,221000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT C.H.S NEW MARKET (KANNU STREET)FORM IN DIVISION-39, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/5182,Buildings,Completed,ND-TONDIARPET,39,558000,"Improvements to various anganwadi cnetres at DN-39,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6181,Storm Water Drain,Completed,ND-TONDIARPET,39,699000,"Desilting and Minor repairs and Improvement Work on storm water drain at Various Street in DN-39,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6321,Buildings,Completed,ND-TONDIARPET,39,777000,"Operation and Maintenance of amma kudineer (3rd year 2019-20), at T.H Road inside the A.E Koil Street in DN-39, U-10, Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/6581,Buildings,Completed,ND-TONDIARPET,39,2433340,"CONSTRUCTION OF ADDITIONAL 2 CLASSROOM IN THE FIRST FLOOR KANNU PILLAI STREET GROUND SCHOOL AT CHERIAN NAGAR IN DIV-39, UNIT-10, ZONE-4 (UNDER MLA FUND)",MLACDS,4,2019-20,2021-22 ND/2019-20/7513,Storm Water Drain,Completed,ND-TONDIARPET,39,169000,"Dismantling and reconstruction of SWD at A.E Koil Street in DN-39,U-10,Z-04(20m)",Own Sources,4,2019-20,2020-21 ND/2019-20/7944,Roads,Completed,ND-TONDIARPET,39,88000,"Pot hole for AE koil street and QQ scheme street in Div-39,Unit-10,Zone-04",Own Sources,4,2019-20,2019-20 BR/2019-20/15777,Roads,Completed,BR-Bus Route Roads,40,250000,"Partly relaying the road with BC after cold milling by paver finisher at Kamarajar Salai (Washenmenpet)in Dn-40, Zone - 4",Grants,4,2019-20,2020-21 BR/2019-20/15787,Roads,Completed,BR-Bus Route Roads,40,250000,"Partly relaying the road with BC after cold milling by paver finisher at AE Kovil Street in Dn-40 , Zone - 4",Grants,4,2019-20,2020-21 BR/2019-20/17391,Road Cut,Completed,BR-Bus Route Roads,40,970000,"Restoration of Road cut made by OFC operators at various Bus Route Road in Div - 35,39,40,43 & 48,Zone 4.",Deposit Works,4,2019-20,2020-21 ND/2019-20/17742,Parks,Completed,ND-TONDIARPET,40,342000,"Erection of Borewell with water supply arrangements to the public convenience at AA Scheme Road and repair and improvement to Motors in div - 40, Unit 10, Zone IV",Own Sources,4,2019-20,2020-21 ND/2019-20/17743,Storm Water Drain,Completed,ND-TONDIARPET,40,248000,"Water Supply Arrangement for Jeeva Nagar PC , Amma Unavagam Toilet and Division Office Toilet in DN-40,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/5678,Parks,Completed,ND-TONDIARPET,40,61000,"Providing rain water harvesting at Ellaya street (Emmar park) in division-40, unit-10, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/6206,Storm Water Drain,Completed,ND-TONDIARPET,40,878000,"Minor repairs and Improvement Work on storm water drain at Various Street in DN-40,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6323,Buildings,Completed,ND-TONDIARPET,40,897000,"Operation and maintenance of amma kudineer at Vaidhyanathan street (4th Year 2019-20) in DN-40, U-10, Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6914,Parks,Completed,ND-TONDIARPET,40,2500000,"CONSTRUCTION OF COMPOUND WALL AT CHELLIAMMAN KOIL STREET PARK IN DIVISION-40, UNIT-10, ZONE-4. (UNDER MLA FUND)",MLACDS,4,2019-20,2020-21 ND/2019-20/7598,Buildings,Completed,ND-TONDIARPET,40,1180000,"Maintenance of Park at Thanthai periyar park in division-40, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7600,Buildings,Completed,ND-TONDIARPET,40,609000,"Maintenance of Park at Cross road OSR in division-40, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7601,Buildings,Completed,ND-TONDIARPET,40,1798000,"Maintenance of Park at Ellaya street OSR (EMMAR) in division-40, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7602,Buildings,Completed,ND-TONDIARPET,40,1149000,"Maintenance of Park at Thiruvalluvar nagar in division-40, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7603,Buildings,Completed,ND-TONDIARPET,40,452000,"Maintenance of Park at Tsunami quarters (B Block) in division-40, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7604,Buildings,Completed,ND-TONDIARPET,40,491000,"Maintenance of Park at Tsunami quarters (M Block) in division-40, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7725,Parks,Completed,ND-TONDIARPET,40,51000,"Maintenance of Thanthai periyar park in division-40, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7727,Parks,Completed,ND-TONDIARPET,40,80000,"Maintenance of park at cross road osr (Brindavan) in division-40, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7729,Parks,Completed,ND-TONDIARPET,40,139000,"Maintenance of Elaya street OSR (Emmar) Park in division-40, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7740,Parks,Completed,ND-TONDIARPET,40,68000,"Maintenance of Thiruvalluvar Nagar park in division-40, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7923,Roads,Completed,ND-TONDIARPET,40,468000,"Attending patch work at V.O.C nagar main road,vaidhyanathan street,seniamman koil street,LIG colony 3rd cross street,a.e koil street kamarajar salai IN DN-40,U-10,Z-04",Own Sources,4,2019-20,2019-20 BR/2019-20/5331,Roads,Completed,BR-Bus Route Roads,41,12632000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Ennore High Road (From the jn of IOC to Korrukkupet) in Dn41, Zone - IV",Grants,4,2019-20,2020-21 L/2019-20/6756,Electrical,Completed,L-Electrical,41,2496000,"Provision of Additional 75 Nos. of 6 Mtr G.I Street Lamp Post with 1 Mtr Single Straight bracket with 40W LED Fitting at Various Locations in Division 41,42,47 & 48, Zone IV",Own Sources,4,2019-20,2020-21 L/2019-20/7451,Electrical,Completed,L-Electrical,41,197300,"Electrification work at Amma Unavagam at Annai Sathya Nagar and J.J Nagar in Dn:41, Zone IV",Own Sources,4,2019-20,2020-21 ND/2019-20/0261,Buildings,Completed,ND-TONDIARPET,41,363000,"Construction of compost yard at canal road near J.J.Nagar in dn-41,u-10,z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/0395,Buildings,Completed,ND-TONDIARPET,41,363000,"Construction of compost yard at canal road near Ezhil .Nagar in dn-41,u-10,z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/11529,Roads,Completed,ND-TONDIARPET,41,345000,"Relaying the cement concrete road at Sivaji nagar 1st street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11530,Roads,Completed,ND-TONDIARPET,41,309000,"Relaying the cement concrete road at Sivaji nagar 2nd street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11531,Roads,Completed,ND-TONDIARPET,41,291000,"Relaying the cement concrete road at Sivaji nagar 3rd street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11532,Roads,Completed,ND-TONDIARPET,41,222000,"Relaying the cement concrete road at Sivaji nagar 4th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11533,Roads,Completed,ND-TONDIARPET,41,239000,"Relaying the cement concrete road at Sivaji nagar 5th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11534,Roads,Completed,ND-TONDIARPET,41,343000,"Relaying the cement concrete road at Sivaji nagar 6th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11535,Roads,Completed,ND-TONDIARPET,41,268000,"Relaying the cement concrete road at Sivaji nagar 7th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11536,Roads,Completed,ND-TONDIARPET,41,345000,"Relaying the cement concrete road at Sivaji nagar 8th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11537,Roads,Completed,ND-TONDIARPET,41,341000,"Relaying the cement concrete road at Sivaji nagar 9th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11538,Roads,Completed,ND-TONDIARPET,41,324000,"Relaying the cement concrete road at Sivaji nagar 10th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11539,Roads,Completed,ND-TONDIARPET,41,400000,"Relaying the cement concrete road at Sivaji nagar 11th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11540,Roads,Completed,ND-TONDIARPET,41,278000,"Relaying the cement concrete road at Sivaji nagar 12th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11541,Roads,Completed,ND-TONDIARPET,41,527000,"Relaying the cement concrete road at Sivaji nagar main street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11553,Roads,Completed,ND-TONDIARPET,41,1106000,"Restoration of road cut and Relaying the cement concrete road at thiruvalluvar nagar 1st main road in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11554,Roads,Completed,ND-TONDIARPET,41,1485000,"Restoration of road cut and Relaying the cement concrete road at thiruvalluvar nagar 1st street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11555,Roads,Completed,ND-TONDIARPET,41,1516000,"Restoration of road cut and Relaying the cement concrete road at thiruvalluvar nagar 2nd street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11556,Roads,Completed,ND-TONDIARPET,41,1500000,"Restoration of road cut and Relaying the cement concrete road at thiruvalluvar nagar 3rd street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11557,Roads,Completed,ND-TONDIARPET,41,1325000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 1st main road in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11558,Roads,Completed,ND-TONDIARPET,41,573000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 2nd main road in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11559,Roads,Completed,ND-TONDIARPET,41,891000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 1st street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11560,Roads,Completed,ND-TONDIARPET,41,794000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 2nd street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11561,Roads,Completed,ND-TONDIARPET,41,770000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 3rd street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11562,Roads,Completed,ND-TONDIARPET,41,838000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 4th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11563,Roads,Completed,ND-TONDIARPET,41,873000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 5th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11564,Roads,Completed,ND-TONDIARPET,41,812000,"Restoration of road cut and Relaying the cement concrete road at devi karumariamman nagar 6th street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11565,Roads,Completed,ND-TONDIARPET,41,328000,"Restoration of road cut in cement concrete road at j.j nagar i street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11566,Roads,Completed,ND-TONDIARPET,41,269000,"Restoration of road cut in cement concrete road at j.j nagar j street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11567,Roads,Completed,ND-TONDIARPET,41,361000,"Restoration of road cut in cement concrete road at j.j nagar k street in division-41, unit-10, zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/12166,Roads,Completed,ND-TONDIARPET,41,1757004,"RESTORATION OF ROADCUT AND RELAYING THE B.T ROAD AT ANNA NAGAR PERIYAR SALAI IN DIV-41, UN-10, Z-4",Own Sources,4,2019-20,2020-21 ND/2019-20/1908,Parks,Completed,ND-TONDIARPET,41,14900,"Construction of Mulch pit at M.G.R.Nagar park in dn-41,u-10,z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1919,Parks,Completed,ND-TONDIARPET,41,40400,"Providing of Well Ring at canal road (M.G.R nagar) in Division-41, Unit-10, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1933,Parks,Completed,ND-TONDIARPET,41,14900,"Construction of Mulch pit at Bharathi Nagar TNSCB park in dn-47,u-11,z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1944,Parks,Completed,ND-TONDIARPET,41,119000,"Providing of Well Ring at A.E Koil Street,Cheriyan Nagar Main Street in Division-39, Unit-10, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1951,Parks,Completed,ND-TONDIARPET,41,98700,"Providing of Well Ring at Elaya park, Periyar park, brindhavan park & Thiruvalluvar Park in Division-40, Unit-10, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1953,Parks,Completed,ND-TONDIARPET,41,11750,"Detailed Estimate for Sintex tank at Periyar park, Elaya park, Brinthavan park & Thiruvalluvar park in Division-40, Unit-10, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1957,Parks,Completed,ND-TONDIARPET,41,29700,"Construction of mulch pit at Jeeva park & thiyagaraya park in Division-42, Unit-10, Zone-4",Own Sources,4,2019-20,2019-20 ND/2019-20/1958,Parks,Completed,ND-TONDIARPET,41,40400,"Providing of Well Ring at Jeeva park & M.L.A park in Division-42, Unit-10, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1960,Parks,Completed,ND-TONDIARPET,41,1700,"Providing Sintex tank at Jeeva park in Division-42, Unit-10, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1966,Parks,Completed,ND-TONDIARPET,41,161500,"Providing of Well Ring at Telunghu chetty street and venkadakrishnan street park in Division-48, Unit-11, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/2823,Buildings,Completed,ND-TONDIARPET,41,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CORNATION NAGAR CMS IN DIVISION-41, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2824,Buildings,Completed,ND-TONDIARPET,41,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT M.G.R NAGAR CPS IN DIVISION-41, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2825,Buildings,Completed,ND-TONDIARPET,41,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT ANNA NAGAR CPS IN DIVISION-41, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2826,Buildings,Completed,ND-TONDIARPET,41,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT J.J NAGAR CPS IN DIVISION-41, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/5679,Parks,Completed,ND-TONDIARPET,41,61000,"Providing rain water harvesting at M.G.R nagar 5th street park in division-41, unit-10, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/6189,Storm Water Drain,Completed,ND-TONDIARPET,41,638825,"DESILTING OF STROM WATER DRAIN AT VARIOUS LOCATION IN DIVISION-41, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/6192,Storm Water Drain,Completed,ND-TONDIARPET,41,1678348,"DESILTING OF STROM WATER DRAIN AT VARIOUS LOCATION IN DIVISION-47, UNIT-11, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/7452,Buildings,Completed,ND-TONDIARPET,41,777000,"Operation and maintenance of Amma kudineer ( 3rd Year 2019-20) at J.J nagar A1 Street in DN-41,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/7585,Buildings,Completed,ND-TONDIARPET,41,615000,"Maintenance of Park at M.G.R nagar in division-41, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7722,Parks,Completed,ND-TONDIARPET,41,27600,"Maintenance of park at M.G.R Nagar in division-41, Unit-10, Zone-4 (2 MONTHS)",Own Sources,4,2019-20,2020-21 ND/2019-20/7914,Roads,Completed,ND-TONDIARPET,41,1120000,"Attending patchwork at Cornation nagar 2nd street (marimuthu street), Cornation nagar 4th street(kasthuri bai street), Cornation nagar 1st street (ramasamy street), Cornation nagar 3rd street(parthasarathy street), Scb tenements (cornation nagar), Anna road in annai sathya nagar main street, Canal road in m.g.r nagar, Kamaraj salai , Periyar salai in annai sathya nagar , Thoppai vinayagar koil street, ennore high road, manali salai, j.j nagar a1 street, j.j nagar a2 street, j.j nagar c street, anna nagar main road (periyar salai) in dn-41,u-10,z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/8254,Buildings,Completed,ND-TONDIARPET,41,500000,"Providing and Fixing RO plant at Sivaji nagar Amman Kovil Street UPHC in Div-41, Ut-10, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/9876,Buildings,Completed,ND-TONDIARPET,41,3980000,Compost Yard at canal road near J.J.Nagar street in div-41 unit-10 Zone-4,Own Sources,4,2019-20,2021-22 ND/2019-20/9924,Buildings,Completed,ND-TONDIARPET,41,3980000,Compost Yard at canal road near Ezhil.Nagar in div-41 unit-10 Zone-4,Own Sources,4,2019-20,2021-22 BR/2019-20/15788,Roads,Completed,BR-Bus Route Roads,42,1505000,"Partly relaying the road with BC after cold milling by paver finisher at Thiruvottiyur High Road in Dn-42 , 48 & 52, Zone - 4",Grants,4,2019-20,2020-21 L/2019-20/7455,Electrical,Completed,L-Electrical,42,194100,"Electrification work at Amma Unavagam at Seniamman Koil in Dn:42, Zone IV",Own Sources,4,2019-20,2021-22 ND/2019-20/11459,Roads,Completed,ND-TONDIARPET,42,1734000,"Relaying the BT Road at Seniyamman Koil Street in Dn-42, Unit-10, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11461,Roads,Completed,ND-TONDIARPET,42,707000,"Relaying of CC Road at West K.G. 2nd Street in Dn-42, Unit-10, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/11462,Roads,Completed,ND-TONDIARPET,42,279000,"Relaying of CC Road at West Veera Kutty Street in Dn-42, Unit-10, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/14680,Roads,Completed,ND-TONDIARPET,42,618000,"Relaying the CC Road at Thirunavukarasu Thottam 3rd Street in Dn - 42, Unit -10, Zone - 04",Own Sources,4,2019-20,2020-21 ND/2019-20/1520,Buildings,Completed,ND-TONDIARPET,42,112000,"Improvements and Repair Center Mediam at Thiruvottiyur high Road in Div-42,Unit-10,Zone-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/2842,Buildings,Completed,ND-TONDIARPET,42,401000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT BUDDA STREET C.G.H.S.S IN DIVISION-42, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/5181,Buildings,Completed,ND-TONDIARPET,42,265000,"REPAIR AND MAINTENANCE FOR DIVISION OFFICE AT RATHINA SABAPATHY STREET IN DIVISION - 42, UNIT - 10, ZONE - 04",Own Sources,4,2019-20,2019-20 ND/2019-20/5680,Parks,Completed,ND-TONDIARPET,42,210000,"Providing Indoor plants and other improvement works to zonal office in division-42, unit-10, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/5851,Buildings,Completed,ND-TONDIARPET,42,777000,"Operation and Maintenance of amma kudineer (3rd year 2019-20), Thilagar Nagar opp to indian oil corporation in Div - 42, Unit - 10, Zone -4",Own Sources,4,2019-20,2020-21 ND/2019-20/6178,Storm Water Drain,Completed,ND-TONDIARPET,42,722000,"Desilting and Minor Repairs to SWD at Rathinasabapathy Street, Seniamman Koil Street, ,Rettaikuzhi Street, TH.Road, Kothandaraman Street, Arani Rangan Street, Veerakutty Street, MCM Garden 1st Street, MCM Garden 2nd Street, MCM Garden 3rd Street in DN-42,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6339,Buildings,Completed,ND-TONDIARPET,42,263000,"PROVIDING OF NEW RAIN WATER HARVESTING STRUCTURE CONNECT TO JEEVA PARK WELL AT DIVISION-42, UNIT-10, ZONE-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6358,Buildings,Completed,ND-TONDIARPET,42,85000,"PROVIDING OF NEW RAIN WATER HARVESTING STRUCTURE CONNECT TO DHOBIKANA WELL AT KOTHADARAMAN STREET IN DIVISION-42, UNIT-10, ZONE-04",Own Sources,4,2019-20,2019-20 ND/2019-20/7616,Parks,Completed,ND-TONDIARPET,42,631000,"Maintenance of Park at Rettai kuzhi park, in division-42, Unit-10, zone - 04 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7620,Parks,Completed,ND-TONDIARPET,42,663000,"Maintenance of Park at Thiyagaraya park, in division-42, Unit-10, zone - 04 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7754,Parks,Completed,ND-TONDIARPET,42,31900,"Maintenance of park at Rettaikuzhi Street in division-42, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7779,Parks,Completed,ND-TONDIARPET,42,108000,"Maintenance of Thiyagaraya park in division-42, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/8267,Buildings,Completed,ND-TONDIARPET,42,500000,"Providing and Fixing RO plant at Kailasam Street Corporation Primary School in Div-42, Ut-10, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8299,Roads,Completed,ND-TONDIARPET,42,329000,"Attending patch work at ELAYA lane, Kailasam Street, Thirunavukarasu thottam 4th Street, Thirunavukarasu Street 5th, T.H.Road 2nd lane at Division-42,Unit-10, Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/9270,Buildings,Completed,ND-TONDIARPET,42,561000,"Supply and Fixing Baling Machines at R.C.C Center in Ward-42, Unit-10, Zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/9526,Buildings,Completed,ND-TONDIARPET,42,217000,"URGENT WORK FOR COMMISSIONER FUNCTION(SAVING GIRL CHILD PROGRAMME) IN CGHSS AT 540 T.H ROAD IN DIVISION-42, UNIT-10, ZONE-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/9592,Buildings,Completed,ND-TONDIARPET,42,28000,"URGENT REPAIR WORKS TO COMPOST YARD AT KAILASAM STREET IN DN-42,U-10,Z-04.",Own Sources,4,2019-20,2019-20 ND/2019-20/9602,Buildings,Completed,ND-TONDIARPET,42,184000,"Construction of Compost Yard at Vaithiyanathan Service Road in DN-42,U-10,Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/9607,Buildings,Completed,ND-TONDIARPET,42,1172000,"CONSTRUCTION OF NEW BIO GAS PLANT 0.5 TPD CAPACITY AT ELLAYYA STREET (AMMA UNAVAGAM) IN DN 42, UNIT 10,ZONE IV",Own Sources,4,2019-20,2021-22 ND/2019-20/9907,Buildings,Completed,ND-TONDIARPET,42,2020000,"Improvements to compost yard at kailasam street in division-42, un-10, zn-4",Own Sources,4,2019-20,2021-22 BR/2019-20/15789,Roads,Completed,BR-Bus Route Roads,43,903000,"Partly relaying the road with BC after cold milling by paver finisher at SN Chetty Street in Dn-43 & 50, Zone - 4 & 5",Grants,4,2019-20,2020-21 BR/2019-20/3774,Road Cut,Completed,BR-Bus Route Roads,43,408000,"Restoration of road cut at Kummallamman Koil Street & Pillayar Koil Street in Dn-43, Zone-4, against challan No.BR/2018-19/0022171",Deposit Works,4,2019-20,2019-20 BR/2019-20/5368,Roads,Completed,BR-Bus Route Roads,43,1576000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at V.P.Koil Street (From T.H.Road to Pillayar Koil Street) in Dn-43, Zone - IV",Grants,4,2019-20,2020-21 BR/2019-20/5369,Roads,Completed,BR-Bus Route Roads,43,5057000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Kumalamman Koil Street in Dn-43, Zone - IV",Grants,4,2019-20,2020-21 ND/2019-20/0121,Buildings,Completed,ND-TONDIARPET,43,1171000,"PROPOSED CONSTRUCTION AND INSTALLATION OF GAS HOLDER, UTILIZATION SYSTEM OF OF KITCHEN WASTE BASED BIO-GAS PLANT AT CMS PUDUMANAIKUPPAM IN DIV-43, U-10, Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/0122,Buildings,Completed,ND-TONDIARPET,43,908000,"PROPOSED CONSTRUCTION AND INSTALLATION OF GAS HOLDER, UTILIZATION SYSTEM OF OF KITCHEN WASTE BASED BIO-GAS PLANT AT M.G.R NAGAR IN DIV-43, U-10, Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/0194,Buildings,Completed,ND-TONDIARPET,43,1171000,"PROPOSED CONSTRUCTION AND INSTALLATION OF GAS HOLDER, UTILIZATION SYSTEM OF OF KITCHEN WASTE BASED BIO-GAS PLANT AT S.N CHETTY ICDS IN DIV-43, U-10, Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/10008,Buildings,Completed,ND-TONDIARPET,43,3989000,Compost Yard at Kasimedu Hindu Burial Ground in div-43 unit-10 Zone-4,Own Sources,4,2019-20,2021-22 ND/2019-20/1017,Buildings,Completed,ND-TONDIARPET,43,1440000,"Improvement to the Old Ladies Hostel at CDH in DN-43,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1018,Buildings,Completed,ND-TONDIARPET,43,271000,"Providing Iron Sheet Work For Anbagam Gents Hostel at CDH in DN-43,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/15045,Buildings,Completed,ND-TONDIARPET,43,564000,"Operation and maintenance of RO Plant at T.H Road inside the CDH Compus in DN43,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/1940,Parks,Completed,ND-TONDIARPET,43,14900,"Construction of Mulch pit at CDH park in dn-43,u-10,z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1941,Parks,Completed,ND-TONDIARPET,43,40400,"Providing of Well Ring at CDH Park in Division-43, Unit-10, Zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1943,Parks,Completed,ND-TONDIARPET,43,3400,"Providing sintex tank at CDH Park and Burial Ground Park at dn-43,u-10.z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/2052,Buildings,Completed,ND-TONDIARPET,43,377000,"Construction of Sump For Kitchen Shed Back Side at CDH in Dn-43,U-1,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/2053,Buildings,Completed,ND-TONDIARPET,43,959000,"Improvement to the Conference Hall at CDH in DN-43,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/2409,Buildings,Completed,ND-TONDIARPET,43,86600,"Improvement to the Bio Medical Waste Room at CDH in DN-43,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/2831,Buildings,Completed,ND-TONDIARPET,43,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CMS KUMMALAMMAN KOIL STREET IN DIVISION-43, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2832,Buildings,Completed,ND-TONDIARPET,43,40000,"SUPPLYING AND FIXING OF MOTOR AT CMS VINAYAGAPURAM IN DIVISION-43, UNIT-10, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/3072,Electrical,Completed,ND-TONDIARPET,43,768400,"Provision of New cable laying with switch board and replace of wiring in Laundry plant at C.D.HOSPITAL IN DN-43,Z4",Own Sources,4,2019-20,2019-20 ND/2019-20/3136,Buildings,Completed,ND-TONDIARPET,43,115500,"Repair to RO Plant (Kitchen Shed and Admission Block) at CDH in DN-43,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/3718,Parks,Completed,P-Parks and Playfields,43,909000,"Plantation of maintenance of tree saplings for one year at various street in DN-40,41,42,43 U-10,Z-04 (Total No of Trees-339Nos)",Own Sources,4,2019-20,2019-20 ND/2019-20/5089,Buildings,Completed,ND-TONDIARPET,43,558000,"Improvements to various anganwadi centers at DN-43,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/5321,Buildings,Completed,ND-TONDIARPET,43,2957000,"AHO Office Converted to M.P Room at T.H Road in DN-43,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/5681,Parks,Completed,ND-TONDIARPET,43,250000,"Providing rain water harvesting and other improvements to C.D.H park in division-43, unit-10, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/5686,Buildings,Completed,ND-TONDIARPET,43,709000,"Operation and maintenance of RO Plant ( 4th Year 2019-20) at T.H Road inside the CDH Compus in DN-43,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/6147,Storm Water Drain,Completed,ND-TONDIARPET,43,446000,"Desilting and Minor repairs , Improvement Work on storm water drain at Various Street in DN-43,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/7588,Buildings,Completed,ND-TONDIARPET,43,251000,"Maintenance Estimate for Park at S.N chetty street in division-43, unit-10, zone-4 (per year))",Own Sources,4,2019-20,2020-21 ND/2019-20/7593,Buildings,Completed,ND-TONDIARPET,43,731000,"Maintenance Estimate for Park at Kasimedu Burial ground in division-43, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7594,Buildings,Completed,ND-TONDIARPET,43,1750000,"Maintenance Estimate for Park at C.D.H park in division-43, unit-10, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7755,Parks,Completed,ND-TONDIARPET,43,48500,"Maintenance of park at Kasimedu burial ground in division-43, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7763,Parks,Completed,ND-TONDIARPET,43,162000,"Maintenance of park at C D HOSPITAL & Opp Main Building park in division-43, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7767,Parks,Completed,ND-TONDIARPET,43,29400,"Maintenance of park at s.n chetty street in division-43, Unit-10, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7869,Buildings,Completed,ND-TONDIARPET,43,1024000,"Repairs Work for Gasifire Crematorium at Kasimedu Hindu Burial Ground in DN-43,U-10,Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/7880,Buildings,Completed,ND-TONDIARPET,43,992000,"Providing Roofing arrangement and Paver Block work at CDH (OP Ward) in DN-43,U-10,Z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/7926,Roads,Completed,ND-TONDIARPET,43,445000,"Attending patch work at Thandavarayan Street,Sooriyanarayanan Street,Kasipurm B Block 5th Street in DN-43,U-10,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/8181,Buildings,Completed,ND-TONDIARPET,43,1035000,"Repair and Improvement to the CMS at Kummalamman Koil Street in DN-43,U-10,Z-04",Own Sources,4,2019-20,2021-22 BR/2019-20/15786,Roads,Completed,BR-Bus Route Roads,44,953000,"Partly relaying the road with BC after cold milling by paver finisher at Melpatti Ponnappan Street in Dn-44,45 &70, Zone -4",Grants,4,2019-20,2020-21 ND/2019-20/0249,Buildings,Completed,ND-TONDIARPET,44,967000,"PROPOSED CONSTRUCTION AND INSTALLATION OF GAS HOLDER, UTILIZATION SYSTEM OF OF KITCHEN WASTE BASED BIO-GAS PLANT AT NETHAJI STREET ANGANVAI N DIV-44, U-11, Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/0727,Roads,Completed,ND-TONDIARPET,44,1220000,"ROADCUT RESTORATION WORK AT THIRUVALLUVAR STREET IN DN-44,UNIT-11, ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/0821,Roads,Completed,ND-TONDIARPET,44,445000,"ROADCUT RESTORATION WORK AT RANIAMMAIYAR STREET IN DN-44,UNIT-11, ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/0823,Roads,Completed,ND-TONDIARPET,44,651000,"ROADCUT RESTORATION WORK AT NEHRUJI STREET IN DN-44,UNIT-11, ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/0824,Roads,Completed,ND-TONDIARPET,44,318000,"RELAYING B.T ROAD AT THIRUVALLUVAR LANE (RAMANA NAGAR) IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/0825,Roads,Completed,ND-TONDIARPET,44,83000,"LAYING CC ROAD AT M.G.R LANE IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/0826,Roads,Completed,ND-TONDIARPET,44,131000,"IMPROVEMENT TO CC ROAD AT KATTA BOMMAN LANE IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/1956,Buildings,Completed,ND-TONDIARPET,44,132000,"CONSTRUCTION OF WELLRING COMPOSITE YARD AT 2 VARIOUS LOCATIONS IN DIVI-44,U-11,Z-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/2828,Buildings,Completed,ND-TONDIARPET,44,442000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT NEW KAMARA NAGAR CMS IN DIVISION-44, UNIT-11, ZONE-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/5683,Parks,Completed,ND-TONDIARPET,44,160000,"Providing rain water harvesting at Sathyavani muthu nagar park in division-44, unit-11, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/6191,Storm Water Drain,Completed,ND-TONDIARPET,44,1515000,"Desilting of Minor repairs and Improvement Work on storm water drain at Various Street in DN-44,U-11,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/7596,Buildings,Completed,ND-TONDIARPET,44,761000,"Maintenance Estimate for Park at Sathyavani muthu nagar in division-44, unit-11, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7769,Parks,Completed,ND-TONDIARPET,44,53000,"Maintenance of park at Sathiyavani muthu nagar in division-44, Unit-11, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7953,Roads,Completed,ND-TONDIARPET,44,1489000,"Attending Patch Work At Various Streets (MPM Street,Jawahar Street,Sivashakthi Vinayagar Street,Thulasingam Street,Subramaniya Bharathi Street, Kattabomman Street,Ambedkar Street,Veerapandian Street,Amman Koil Street,Manimegalai Street,Alagirisamy Street,Kasthuribai Street,Anna Street,Kamarajar 1st Street,Kamarajar 2nd Street,Kamarajar 4th Street,Kamarajar 3rd Street,Kamarajar 7th Street,Sathyabama Street) In Dn-44,U-11,Z-04",Own Sources,4,2019-20,2019-20 BR/2019-20/5333,Roads,Completed,BR-Bus Route Roads,45,2649000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Dr.Ambedkar College Road in Dn-45, Zone - IV",Grants,4,2019-20,2020-21 BR/2019-20/5334,Roads,Completed,BR-Bus Route Roads,45,5921000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Moorthingar Road in Dn-45 &46, Zone - IV",Grants,4,2019-20,2020-21 BR/2019-20/5371,Roads,Completed,BR-Bus Route Roads,45,3161000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Stephenson Road (From jn of Dr.Ambedkar College Road up to Church) in Dn-45, Zone - IV",Grants,4,2019-20,2020-21 BR/2019-20/6439,Footpath,Completed,BR-Bus Route Roads,45,3520000,"Forming Footpath at Stephenson Road (From Dr.Ambedkar Colege Road to A.A. Road) in Dn-45, Zone-IV",Grants,4,2019-20,2021-22 ND/2019-20/0316,Buildings,Completed,ND-TONDIARPET,45,193000,"Improvement work Bio gas plant (Capacity Increase to 200 Kgs) Amma Unavagan at Mayor Krishnamurthy nagar in Dn-45, Unit-11, Zone-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/0723,Roads,Completed,ND-TONDIARPET,45,490000,"Attending Patch work at Rathinam 1st street In Dn-45,U-11,Z-4",Own Sources,4,2019-20,2020-21 ND/2019-20/0732,Roads,Completed,ND-TONDIARPET,45,19039000,"RELAYING C C ROAD AT SANJAY NAGAR ( MPM STREET) IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/11593,Roads,Completed,ND-TONDIARPET,45,1715000,"RELAYING C C ROAD AT SUNDARAM 2ND LANE IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/11594,Roads,Completed,ND-TONDIARPET,45,1447000,"RELAYING C C ROAD AT SUNDARAM 3RD LANE IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/11597,Roads,Completed,ND-TONDIARPET,45,1154000,"RELAYING C C ROAD AT K K NAGAR ( MPM STREET ) IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/11613,Roads,Completed,ND-TONDIARPET,45,525000,"RELAYING C C ROAD AT M M GARDEN MAIN ROAD & 2ND STREET IN DN-45,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/11629,Roads,Completed,ND-TONDIARPET,45,366000,"RELAYING ROAD AT RATHINAM 2ND STREET IN DIVISION-45, UNIT-11, ZONE-04",Own Sources,4,2019-20,2020-21 ND/2019-20/1922,Buildings,Completed,ND-TONDIARPET,45,93400,"CONSTRUCTION OF WELLRING COMPOSITE YARD AT A A ROAD BSNL QYATERS IN DIV-45,U-11,Z-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/1931,Buildings,Completed,ND-TONDIARPET,45,3400,"Supplying of sintex tankt at Various location in Dn-45, Unit-11, Zone-04",Own Sources,4,2019-20,2019-20 ND/2019-20/1937,Buildings,Completed,ND-TONDIARPET,45,44600,"Mulch pit at vyasar nagar park, sanjay nagar park, sri ram nagar main road road side in division-45, unit-11, zone-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2085,Buildings,Completed,ND-TONDIARPET,45,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT MELPATTI PONNAPPAN STREET IN DN-45 , U-11, Z-IV",Own Sources,4,2019-20,2019-20 ND/2019-20/5218,Buildings,Completed,ND-TONDIARPET,45,118000,"New Proposal Rain Water Harvesting at B B Road Lorry depot in Div-45,Unit-11, Zone-04.",Own Sources,4,2019-20,2020-21 ND/2019-20/6179,Storm Water Drain,Completed,ND-TONDIARPET,45,1234000,"Desilting of Minor repairs and Improvement Work on storm water drain at Various Street in Dn-45,U-11,Z-4",Own Sources,4,2019-20,2019-20 ND/2019-20/6741,Parks,Completed,P-Parks and Playfields,45,522000,"Name of work: Plantation of maintenance of tree saplings for one year at various street in DN-45,46,47 U-11,Z-04 (Total No of Trees-193Nos)",Own Sources,4,2019-20,2019-20 ND/2019-20/7613,Parks,Completed,ND-TONDIARPET,45,274000,"Abstract for Maintenance Estimate for Desiganathapuram Park at Dr.Ambedkar college road, in Dn-45, Unit-11, Zone- (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7618,Parks,Completed,ND-TONDIARPET,45,848000,"Abstract for Maintenance Estimate for Park at Sanjai nagar in division-45, unit-11, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7621,Parks,Completed,ND-TONDIARPET,45,634000,"Abstract for Maintenance Estimate for Park at Kasthuribai gandhi nagar in division-45, unit-11, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7764,Parks,Completed,ND-TONDIARPET,45,67000,"Maintenance of park at Kasthuribai Gandhi Nagar, Desikananda park, Vysar nagar V Street, in division-45, Unit-11, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7768,Parks,Completed,ND-TONDIARPET,45,29000,"Maintenance of park at Sanjai Nagar in division-45, Unit-11, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7930,Roads,Completed,ND-TONDIARPET,45,1223000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DIVISION-45, UNIT-11, ZONE-04",Own Sources,4,2019-20,2019-20 ND/2019-20/9567,Buildings,Completed,ND-TONDIARPET,45,382000,"REPAIR AND MAINTENANCE WORK TO LORRY DEPOT B B ROAD IN DIVISION -45, UNIT-11, ZONE-4..",Own Sources,4,2019-20,2020-21 BR/2019-20/15793,Roads,Completed,BR-Bus Route Roads,46,277000,"Partly relaying ( CC Patch Work ) at sathyamoorthy Main road in Dn-46, Zone - 4",Grants,4,2019-20,2020-21 ND/2019-20/0365,Parks,Completed,ND-TONDIARPET,46,14600,"Construction of Mulch Pit at S.M.Nagar Park in Div - 46, Unit - 11, Zone - 4",Own Sources,4,2019-20,2019-20 ND/2019-20/0900,Storm Water Drain,Completed,ND-TONDIARPET,46,185000,"REAPIRS AND DESILTING OF STROM WATER DRAIN AT SM NAGAR MAIN ROAD FROM E.H ROAD TO C.KALYANAPURAM ROAD EAST,WEST SIDE AND PROVIDING INSPECTION CHAMBERS AT VARIOUS PLACES IN DIVISION - 46 , UNIT - 11 ,ZONE - 4 .",Own Sources,4,2019-20,2019-20 ND/2019-20/0927,Buildings,Completed,ND-TONDIARPET,46,460000,"REPAIRS AND IMPROVEMENTS TO UPHC AT S.M.NAGAR MAIN ROAD IN DIVISION 46,UNIT-11.ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/10125,Buildings,Completed,ND-TONDIARPET,46,960000,"PROVIDING RAIN WATER HARVESTING AT YERI KARAI TNSCB NUMBER OF 10 INNER ROADS IN DIVISION-46, UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/11690,Road Cut,Completed,ND-TONDIARPET,46,1070000,"Laying of CC Improvements to CC road at Old Good Shed road in division-46,unit-11,zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11696,Road Cut,Completed,ND-TONDIARPET,46,817000,"Laying of CC Improvements to CC road at Krishnan kovil street in division-46,unit-11,zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11698,Road Cut,Completed,ND-TONDIARPET,46,1300000,"Laying of CC Improvements to CC road at Venkatesaperumal kovil street in division-46,unit-11,zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11704,Road Cut,Completed,ND-TONDIARPET,46,688000,"Laying of CC Improvements to CC road at Nehru nagar 3rd street in division-46,unit-11,zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/11706,Road Cut,Completed,ND-TONDIARPET,46,723000,"Laying of CC Improvements to CC road at Gananathar kovil street in division-46,unit-11,zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/1849,Buildings,Completed,ND-TONDIARPET,46,265900,"CONSTRUCTION OF WELLRING COMPOSITE YARD AT 2 VARIOUS LOCATIONS IN DIVI-46,U-11,Z-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/2252,Buildings,Completed,ND-TONDIARPET,46,324000,"IMPROVEMENTS TO GYM BUILDING AT KENNADY NAGAR GROUND NORTHEN SIDE IN DIVISION-46 , UNIT-11 , ZONE-4 .",Own Sources,4,2019-20,2020-21 ND/2019-20/2550,Buildings,Completed,ND-TONDIARPET,46,482000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CORE CITY SCHOOL C-KALYANAPURAM CHSS,CMS, VYASARPADI C.H.S.S IN DIVISION-46,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/2744,Buildings,Completed,ND-TONDIARPET,46,275000,"REPAIRS AND COLOUR WASHING TO GYM BUILDING AT C - KALYANAPURAM SCHOOL IN DIVISION-46 , UNIT-11 , ZONE-4 .",Own Sources,4,2019-20,2020-21 ND/2019-20/2852,Buildings,Completed,ND-TONDIARPET,46,340000,"REPAIR AND IMPROVEMENTS TO STORE ROOM AT C-KALYANAPURAM C.H.S SCHOOL IN DIVISION-46,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/4379,Buildings,Completed,ND-TONDIARPET,46,555000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING OFFICE BUILDING [ J E , C.I , SI OFFICE] AT E.H.ROAD IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/6215,Storm Water Drain,Completed,ND-TONDIARPET,46,747000,"Desilting and Minor Repairs at various placeses in division-46,unit-11,zone-4",Own Sources,4,2019-20,2019-20 ND/2019-20/6626,Playfields,Completed,ND-TONDIARPET,46,320000,"IMPROVEMENTS KENNADY NAGAR PLAY GROUND AT NORTHEN SIDE IN DIVISION-46,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/6627,Playfields,Completed,ND-TONDIARPET,46,587000,"IMPROMENTS TO KENNADY NAGAR CHILDREN PLAY GROUND AND SUPPLYING/FIXING PLAY APPARATES AT SOUTHEN SIDE IN DIVISION-46,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/6996,Roads,Completed,ND-TONDIARPET,46,177000,"IMPROVEMENTS TO THE EXISTING - CEMENT CONCRETE ROAD WITH PERCULATION PITS , GULLY , PVC PIPES AND GRANO 50MM THICK @ MOORTHINGER 2ND LANE IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2019-20,2021-22 ND/2019-20/7172,Buildings,Completed,ND-TONDIARPET,46,178000,"PROVIDING PERCOLATION PITS AND INSPECTION CHAMBER AT VARIOUS LOCATIONS AND DISPOSAL OF RAIN WATER IN DIVISION-46,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2021-22 ND/2019-20/7615,Parks,Completed,ND-TONDIARPET,46,805000,"Maintenance of Park at Sathiya moorthi nagar park (per year) in division-46,unit-11,zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/7931,Buildings,Completed,ND-TONDIARPET,46,40000,"SUPPLY OF COOLER AND FLY TRAP AT AMMA UNAVAGAM C-KALYANAPURAM IN DIVISION-46,UNIT-11,ZONE-4",Own Sources,4,2019-20,2021-22 ND/2019-20/7943,Buildings,Completed,ND-TONDIARPET,46,1198000,"Repair and Maintenance of Roads with cement concrete patch's at various roads in division-46,unit-11,zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/8020,Buildings,Completed,ND-TONDIARPET,46,172000,"PROVIDING PERCULATION PIT AT C-KALYANAPURAM SCHOOL GROUND IN DIVISION-46,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/8316,Buildings,Completed,ND-TONDIARPET,46,871000,"PROVIDING PLATFORM FOR C-KALYANAPURAM SCHOOL IN DIVISION-46,UNIT-11,ZONE-4.",Own Sources,4,2019-20,2020-21 ND/2019-20/8325,Buildings,Completed,ND-TONDIARPET,46,80000,"Repairs and Improvement to Sump at C.M.S. Moorthinger street In Dn-46,U-11,Z-4",Own Sources,4,2019-20,2020-21 ND/2019-20/9598,Buildings,Completed,ND-TONDIARPET,46,1172000,"INSTALLATION OF NEW BIO GAS PLANT AT KANNI KOVIL STREET AMMA UNAVAGAM IN DN-48, UNIT-11, ZONE-4.",Own Sources,4,2019-20,2021-22 BR/2019-20/5372,Roads,Completed,BR-Bus Route Roads,47,5022000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at C.B.Road (From flyover to RUB) in Dn-47, Zone - IV",Grants,4,2019-20,2020-21 L/2019-20/7456,Electrical,Completed,L-Electrical,47,199800,"Electrification work at Meenambal Nagar 4th Street and Bommi Sivaramulu Street in Dn:47 & 48, Zone IV",Own Sources,4,2019-20,2021-22 ND/2019-20/0257,Buildings,Completed,ND-TONDIARPET,47,363000,"Construction of compost yard at canal road near bharathi nagar 1st street in dn-47,u-11,z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/10159,Buildings,Completed,ND-TONDIARPET,47,366000,"REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE 47 AT J.J.NAGAR A1 STREET IN DN-47,U-11,Z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/1043,Buildings,Completed,ND-TONDIARPET,47,308000,"Improvements to meenambal nagar cps at k.h.road in dn-47,u-11,z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/12198,Roads,Completed,ND-TONDIARPET,47,626000,"RELAYING THE B.T ROAD AT BHARATHI NAGAR 1ST STREET IN DIV-47,UN-11,Z-4",Own Sources,4,2019-20,2020-21 ND/2019-20/13525,Roads,Completed,ND-TONDIARPET,47,1500000,"FORMATION OF CC ROAD AT KARPAGAVINAYAGAR KOIL STREET IN DN-47, UNIT-11, ZONE-4.",MLACDS,4,2019-20,2020-21 ND/2019-20/13526,Roads,Completed,ND-TONDIARPET,47,1000000,"FORMATION OF CC ROAD AT SUTHANTHIRAPURAM 1ST STREET IN DN-47, UNIT-11, ZONE-4.",MLACDS,4,2019-20,2020-21 ND/2019-20/13527,Roads,Completed,ND-TONDIARPET,47,1500000,"FORMATION OF CC ROAD AT CHIGIRIPALAYAM 12TH STREET IN DN-47, UNIT-11, ZONE-4.",MLACDS,4,2019-20,2020-21 ND/2019-20/2103,Buildings,Completed,ND-TONDIARPET,47,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT CANAL ROAD IN DN- 47, U- 11, Z-IV",Own Sources,4,2019-20,2019-20 ND/2019-20/2470,Buildings,Completed,ND-TONDIARPET,47,200000,"Improvement to the ICDS Center No:33603090401 at Kannan Street in DN-47,U-11,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/2837,Buildings,Completed,ND-TONDIARPET,47,442000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT C.M.S BUDDA SCHOOL AT KANNAN STREET IN DIVISION-47, UNIT-11, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2838,Buildings,Completed,ND-TONDIARPET,47,261000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT HARINARAYANAPURAM C.H.S IN DIVISION-47, UNIT-11, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2839,Buildings,Completed,ND-TONDIARPET,47,180000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT RANGANATHAPURAM CMS IN DIVISION-47, UNIT-11, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/2845,Buildings,Completed,ND-TONDIARPET,47,261000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CMS No.540, TH ROAD IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/3387,Roads,Completed,ND-TONDIARPET,47,344000,"Improvements to C.C..Road at Siggirinthapalayam 11th street in dn-47,u-11,z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/3388,Roads,Completed,ND-TONDIARPET,47,193000,"Improvements to C.C..Road at Meenambal nagar cross street in dn-47,u-11,z-04",Own Sources,4,2019-20,2020-21 ND/2019-20/4395,Buildings,Completed,ND-TONDIARPET,47,490000,"CONSTRUCTION OF SUMP AND WATERSUPPLY ARRANGEMENT TO CHENNAI MIDDLE SCHOOL AT RANGANADHAPURAM IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4771,Buildings,Completed,ND-TONDIARPET,47,500000,"PROVIDING AND FIXING R.O. PLANT AT CMS MEENAMBAL STREET IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4772,Buildings,Completed,ND-TONDIARPET,47,500000,"PROVIDING AND FIXING R.O. PLANT AT CHS HARINARAYANAPURAM IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4773,Buildings,Completed,ND-TONDIARPET,47,500000,"PROVIDING AND FIXING R.O. PLANT AT CMS BUDDHA STREET IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4774,Buildings,Completed,ND-TONDIARPET,47,500000,"PROVIDING AND FIXING R.O. PLANT AT CMS RANGANADHAPURAM IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4776,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS JEEVA NAGAR 14TH STREET IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4777,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS JEEVA NAGAR 16TH STREET IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4778,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS BHARATHI NAGAR 6TH STREET IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4779,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS MEENAMBALI NAGAR 3RD STREET CENTER NO-410 IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4780,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS MEENAMBALI NAGAR 3RD STREET CENTER NO-411 IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4781,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS MEENAMBALI NAGAR 3RD STREET CENTER NO-413 IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4782,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS BUDDHA STREET IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4783,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS RANGANADHAPURAM IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4784,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS HARINARAYANAPURAM IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/4785,Buildings,Completed,ND-TONDIARPET,47,200000,"PROVIDING WATER SUPPLY ARRANGEMENT AT ICDS HARINARAYANAPURAM CENTER NO-405 IN DN-47, U-11, Z-4.",MLACDS,4,2019-20,2019-20 ND/2019-20/5079,Buildings,Completed,ND-TONDIARPET,47,500000,"Maintenance and Improvement work to PC in division-47,unit-11,zone-4",Own Sources,4,2019-20,2021-22 ND/2019-20/5514,Buildings,Completed,ND-TONDIARPET,47,538000,"Painting work for Meenambal nagar cps at K.H.Road in dn-47,u-11,z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/5684,Parks,Completed,ND-TONDIARPET,47,250000,"Providing rain water harvesting and other improvements to Bharathi nagar park in division-47, unit-11, zone-4.",Own Sources,4,2019-20,2019-20 ND/2019-20/7586,Buildings,Completed,ND-TONDIARPET,47,665000,"Maintenance of Park at Bharathi nagar hosing board in division-47, unit-11, zone-4 (per year)",Own Sources,4,2019-20,2020-21 ND/2019-20/7756,Parks,Completed,ND-TONDIARPET,47,38500,"Maintenance of park at Bharathi Nagar Housing board in division-47, Unit-11, Zone-4 (2months)",Own Sources,4,2019-20,2020-21 ND/2019-20/7916,Roads,Completed,ND-TONDIARPET,47,670000,"Attending patch work at K.H.Road,C.B.Road,old glass factory road,Nagappan street,Mannappan street,Egappan street,kannan street,R.K.Ngar 1st street,R.K.Ngar Main street at dn-47,u-11,z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/8032,Buildings,Completed,ND-TONDIARPET,47,610000,"Repairs and Improvements to CMS BUDHA Cshool at kannan street in dn-47,u-11,z-04",Own Sources,4,2019-20,2021-22 ND/2019-20/8257,Buildings,Completed,ND-TONDIARPET,47,500000,"Providing and Fixing RO plant at Harinarayanapuram UPHC in Div-47, Ut-11, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8259,Buildings,Completed,ND-TONDIARPET,47,500000,"Providing and Fixing RO plant at Meenambal Nagar Community Health Hospital in Div-47, Ut-11, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8270,Buildings,Completed,ND-TONDIARPET,47,500000,"Providing and Fixing RO plant at Harinarayanapuram Corporation Primary School in Div-47, Ut-11, Zn-4",MLACDS,4,2019-20,2019-20 ND/2019-20/8340,Buildings,Completed,ND-TONDIARPET,47,1650000,"Providing water supply arrangements and other improvements to Harinarayanapuram high school in Div-47, Unit-11, Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8348,Buildings,Completed,ND-TONDIARPET,47,1370000,"Providing water supply arrangements and other improvements to Harinarayanapuram primary school in Div-47, Unit-11, Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8349,Buildings,Completed,ND-TONDIARPET,47,630000,"Providing water supply arrangements and other improvements to Meenambal nagar primary school at k.h.road in Div-47, Unit-11, Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/8430,Buildings,Completed,ND-TONDIARPET,47,500000,"Providing gym equipments to patel nagar gym in Div-38, Unit-09, Zone-04.",MLACDS,4,2019-20,2020-21 ND/2019-20/9920,Buildings,Completed,ND-TONDIARPET,47,3980000,CONSTRUCTION OF Compost Yard at canal road near Bharathi Nagar 1st street in div-47 unit-11 Zone-4,Own Sources,4,2019-20,2021-22 ND/2019-20/9929,Buildings,Completed,ND-TONDIARPET,47,2810000,CONSTRUCTION OF Compost Yard at C.B Road near flyover bridge (under the bridge) in div-47 unit-11 Zone-4,Own Sources,4,2019-20,2021-22 B/2019-20/9528,Buildings,Completed,B-Buildings,48,3411777,"CONSTRUCTION OF ANGANWADI BUILDING (ICDS CENTER NO.33603010217) AT VENKATAKRISHNAN STREET OLD WASHERMENPET IN DIV. 48, ZONE 4, CHENNAI",MLACDS,4,2019-20,2021-22 L/2019-20/7458,Electrical,Completed,L-Electrical,48,198600,"Electrification work at Amma Unavagam at Kanni Koil Street in Dn:48, Zone iV",Own Sources,4,2019-20,2020-21 ND/2019-20/10528,Buildings,Completed,ND-TONDIARPET,48,2500000,"CONSTRUCTION OF NEW PUBLIC DISTRIBUTION SHOP 1 AT VENKATAKRISHNA STREET IN DIV-48,UNIT-11,ZONE-4",MLACDS,4,2019-20,2020-21 ND/2019-20/10529,Buildings,Completed,ND-TONDIARPET,48,2500000,"CONSTRUCTION OF NEW PUBLIC DISTRIBUTION SHOP 2 AT VENKATAKRISHNA STREET IN DIV-48,UNIT-11,ZONE-4",MLACDS,4,2019-20,2020-21 ND/2019-20/3605,Roads,Completed,ND-TONDIARPET,48,714000,"RELAYING OF BT ROAD AT ANDIAPPAN STREET IN DIV - 48 UNIT-11,ZONE4",Own Sources,4,2019-20,2020-21 ND/2019-20/3606,Roads,Completed,ND-TONDIARPET,48,1202000,"RESTORATION OF B T ROAD CUT AT MUTHAIYA STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3656,Roads,Completed,ND-TONDIARPET,48,628000,"RESTORATION OF B T ROAD CUT AT MANNAPPAN STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3657,Roads,Completed,ND-TONDIARPET,48,699000,"RESTORATION OF B T ROAD CUT AT JAMAL SOWKAR STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3658,Roads,Completed,ND-TONDIARPET,48,269000,"RESTORATION OF B T ROAD CUT AT JAMAL SOWKAR LANE IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3659,Roads,Completed,ND-TONDIARPET,48,1248000,"RESTORATION OF B T ROAD CUT AT DIVAN BAHDUR KUMARASAMY(D.B.K) STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3660,Roads,Completed,ND-TONDIARPET,48,366000,"RESTORATION OF B T ROAD CUT AT THATTANKULAM STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3661,Roads,Completed,ND-TONDIARPET,48,254000,"RESTORATION OF B T ROAD CUT AT NATARAJAR STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3662,Roads,Completed,ND-TONDIARPET,48,1333000,"RESTORATION OF CC ROAD CUT AT MUNIRAM PANDIYAN STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3664,Roads,Completed,ND-TONDIARPET,48,280000,"RESTORATION OF CC ROAD CUT AT NAINIYAPPAN 1ST STREET IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3666,Roads,Completed,ND-TONDIARPET,48,649000,"RESTORATION OF CC ROAD CUT AT SHECHALA GRAMANI THOTTAM IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3667,Roads,Completed,ND-TONDIARPET,48,489000,"RESTORATION OF CC ROAD CUT AT SHECHALA GRAMANI THOTTAM 1ST CROSS LANE IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/3668,Roads,Completed,ND-TONDIARPET,48,579000,"RESTORATION OF CC ROAD CUT AT KAVADI KUDISAI IN DIV -48,UNIT-11,ZONE-4",Own Sources,4,2019-20,2020-21 ND/2019-20/4901,Buildings,Completed,ND-TONDIARPET,48,558000,"Improvements to various anganwadi centers at DN-48,U-11,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/6079,Buildings,Completed,ND-TONDIARPET,48,3000000,"CONSTRUCTION OF NEW GYM BUILDING AT PARTHASARTHY NAGAR IN DIV 48,UNIT-11,ZONE-4",MLACDS,4,2019-20,2020-21 ND/2019-20/6080,Buildings,Completed,ND-TONDIARPET,48,1000000,"PROVIDING GYM APPARATUS IN NEW GYM BUILDING AT PARTHASARATHY NAGAR IN DIV -48,UNIT-11,ZONE 4",MLACDS,4,2019-20,2020-21 ND/2019-20/6082,Playfields,Completed,ND-TONDIARPET,48,1000000,"FORMING FOOTPATH AND SUPPLY /FIXING OF CHILDRENS PLAY APPARATUS AT PARATHASARTHY NAGAR IN DIV 48,UNIT-11,ZONE-4",MLACDS,4,2019-20,2020-21 ND/2019-20/6207,Storm Water Drain,Completed,ND-TONDIARPET,48,799000,"DESILTING OF STROM WATER DRAIN AT VARIOUS LOCATION IN DIVISION-48, UNIT-11, ZONE-4",Own Sources,4,2019-20,2019-20 ND/2019-20/7917,Roads,Completed,ND-TONDIARPET,48,610000,"Attending patch work at TH Road,Namasivayam Street,Nallappa Vathiyar Street,MS Naidu Street,Parthasarathi Street,Basuvaiyan Street Telugu Street,Solaiyappan Street,Muthaiya street,D.B.K. street IN DN-48,U-11,Z-04",Own Sources,4,2019-20,2019-20 ND/2019-20/8023,Buildings,Completed,ND-TONDIARPET,48,990000,"IMPROVEMENT AND MAINTENANCE OF CHENNAI MIDDLE SCHOOL AT NAINNIYAPPAN STREET IN DIV -48,U-11,ZONE-4",Own Sources,4,2019-20,2021-22 ND/2019-20/9269,Buildings,Completed,ND-TONDIARPET,48,561000,"Supply and Fixing Baling Machines at R.C.C Center in Ward-48, Unit-11, Zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/9271,Buildings,Completed,ND-TONDIARPET,48,561000,"Supply and Fixing Baling Machines at R.C.C Center in Ward-35, Unit-09, Zone-4",Own Sources,4,2019-20,2020-21 ND/2019-20/9597,Buildings,Completed,ND-TONDIARPET,48,1172000,"INSTALLATION OF NEW BIO GAS PLANT AT MOTTAI THOTTAM AMMA UNAVAGAM IN DN-48, UNIT-11, ZONE-4.",Own Sources,4,2019-20,2021-22 BR/2019-20/15790,Roads,Completed,BR-Bus Route Roads,49,753000,"Partly relaying the road with BC after cold milling by paver finisher at PAN Rajarathinam Salai in Dn-49 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15791,Roads,Completed,BR-Bus Route Roads,49,176000,"Partly relaying the road with BC after cold milling by paver finisher at West Kalmandapam Road in Dn-49 , Zone - 5",Grants,5,2019-20,2020-21 L/2019-20/8780,Electrical,Completed,L-Electrical,49,1753800,"Replacement of 3010 mtrs 2CX25sq.mm and 650 mtrs 3 1/2 x25 sqmm Alu cable at Various Location in Div 49,50,51,52 and 53 part in Zone-5 ROYAPURAM Section",Grants,5,2019-20,2020-21 NE/2019-20/0530,Roads,Completed,NE-ROYAPURAM,49,1357000,Relaying of BT Road with Paver finisher at Sri Rangammal Street in Division 49 Unit -12 Zone-05,Own Sources,5,2019-20,2019-20 NE/2019-20/10910,Buildings,Completed,NE-ROYAPURAM,49,146000,"Repair and maintenance of Chennai Primary School at Appasamy Street in DN-49,Unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/1176,Buildings,Completed,NE-ROYAPURAM,49,223817,"Providing Well Ring Mulch Pit at Various Street in ( Dn-49, Unit-12, Zone-5 )",Own Sources,5,2019-20,2019-20 NE/2019-20/2148,Buildings,Completed,NE-ROYAPURAM,49,121000,"Construction of Main gate for Corporation Vacant land at somu Chetty 4th lane in Div-49, Unit-12, Zone-V",Own Sources,5,2019-20,2019-20 NE/2019-20/2910,Buildings,Completed,NE-ROYAPURAM,49,160000,"Water Supply & Bore well Arrangement at Chennai Primary School(kapal polu school) Appasamy st in Div-49,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2913,Buildings,Completed,NE-ROYAPURAM,49,160000,"Water Supply & Bore well Arrangement at Chennai Hr Sec School Appasamy st in Div-49,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/5487,Buildings,Completed,NE-ROYAPURAM,49,180000,"Repairs and maintenance work of Division-49,Unit-12,Zone-5 at Various Location.",Own Sources,5,2019-20,2019-20 NE/2019-20/5505,Buildings,Completed,NE-ROYAPURAM,49,150000,"Water Supply & Bore well Arrangement at Urban Primary Health Center at P.A.N Rajarathinam 5th Lane in div-49,Unit-12,Zone-5(Asset Code: 156/2133/865/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/6196,Storm Water Drain,Completed,NE-ROYAPURAM,49,463000,"Desilting of Existing Storm Water Drain at Solaiappan Street,Kothandaramar Street,New Thandavarayan Street,Balu Street,Kappal Polu Street,Thandavarayan Street,Bala Arunachalam Street,Sanjeevirayan Street,Venkatachalam Street,Adam Street,Bashyam Street,Grace Garden Main Road,New Kamaraj Nagar 5th Street,Old Amaranji Puram,Etc. in Dn-49,unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6233,Storm Water Drain,Completed,NE-ROYAPURAM,49,108000,"Replacing of Manhole Doors of at Solaiappan Street,Kothandaramar Street,New Thandavarayan Street,Balu Street,Kappal Polu Street,Thandavarayan Street,Bala Arunachalam Street,Sanjeevirayan Street,Venkatachalam Street,Adam Street,Bashyam Street Grace Garden Main Road,New Kamaraj Nagar 5th Street,Old Amaranji Puram,P A N Rajarathinam Salai,Rajagopal Street,Rajavelu Street,Singara Garden 4th Lane Singara Garden 5th Lane,Somu 1st Lane,Somu 2nd Lane,Somu 5th Lane,Thandavarayan Street,West Kalmandapam Road Various Location in Division-49,Unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6243,Storm Water Drain,Completed,NE-ROYAPURAM,49,462000,"Improvements to Existing Storm Water Drain at Solaiappan Street,New Thandavarayan Street,Kappal Polu Street,Sanjeevirayan Street,Venkatachalam Street,Singara Garden 4th Lane,Kothandaramar Street,Grace Garden Main Road,Old Amaranji Puram,Balu Street,Sanjeevirayan Street,Somu 5th Lane in Div-49,Unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6802,Buildings,Completed,NE-ROYAPURAM,49,434000,"Relaying of BT Road with Paver finisher at Balu Lane in Division-49,Unit-12 ,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/6832,Buildings,Completed,NE-ROYAPURAM,49,241000,"Relaying of BT Road with Paver finisher at Srinivasalu Street in Division-49,Unit-12 ,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/8606,Buildings,Completed,NE-ROYAPURAM,49,200000,"Repairs and Maintenance works to the Chennai High school at Appasamy street in Div-49,Unit-12,Zone-5.(Asset Code: B/2092/237/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/8928,Electrical,Completed,NE-ROYAPURAM,49,270000,"Improvement Class Room to the Chennai High School at Appasamy Street in Div-49,Unit-12,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/9839,Buildings,Completed,NE-ROYAPURAM,49,480000,"Providing Fencing Work and Laying Interlocking Blocks at Muthamil Nagar in Division-49,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 BR/2019-20/15794,Roads,Completed,BR-Bus Route Roads,50,200000,"Partly relaying the road with BC after cold milling by paver finisher at East Kalmandapam Road in Dn-50 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/6988,Roads,Completed,BR-Bus Route Roads,50,60000,"Refixing of 1 no of modern Bus shelter at SN Chetty Street in Dn-50, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/0214,Parks,Completed,NE-ROYAPURAM,50,27000,"Construction of Mulch pit with Bamboo barrier for compost unit Kamrajar Park at S.N Street in Div-50, Unit-12, Zone-V Asset: 013/2159/547/2013-14",Own Sources,5,2019-20,2019-20 NE/2019-20/0231,Parks,Completed,NE-ROYAPURAM,50,14000,"Construction of Mulch pit with Bamboo barrier for compost unit N.R.T Park at N.R.T service road in Div-50, Unit-12, Zone-V",Own Sources,5,2019-20,2019-20 NE/2019-20/1180,Buildings,Completed,NE-ROYAPURAM,50,262000,"Providing Well Ring Mulch Pit at Various Street in ( Dn-50, Unit-12, Zone-5 )",Own Sources,5,2019-20,2019-20 NE/2019-20/1523,Buildings,Completed,NE-ROYAPURAM,50,300000,"Proposed Construction of Material Recovery Facility at East madha church street in Ward - 50, Unit-12, Zone-5 Asset Code: 040/2357/292/2005-06",Own Sources,5,2019-20,2019-20 NE/2019-20/2134,Buildings,Completed,NE-ROYAPURAM,50,199000,Repairs and improvements to Anganwadi shed no.321 at periyatambi street in ward.50 unit.12 zone.5,Own Sources,5,2019-20,2019-20 NE/2019-20/2954,Buildings,Completed,NE-ROYAPURAM,50,195000,"Water Supply & Bore well Arrangement at Chennai Urudu Primary School Arthoon Road in Div-50,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2956,Buildings,Completed,NE-ROYAPURAM,50,160000,"Providing Water Supply & Bore well Arrangement at Chennai Urdhu Primary Schoo Arthoon Road in Div-50, Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/3548,Buildings,Completed,NE-ROYAPURAM,50,65000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO C.H.S AT S.N CHETTY STREET IN DIVISION-50, UNIT-12,ZONE-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/4662,Buildings,Completed,NE-ROYAPURAM,50,3630000,"UNDER ROYAPURAM MLACDS WORKS CONSTRUCTION OF KITCHEN SHED AND DINNING HALL IN CMS AT DURAI STREET IN WARD-50,UNIT-12,ZONE-5.",MLACDS,5,2019-20,2020-21 NE/2019-20/4946,Buildings,Completed,NE-ROYAPURAM,50,44700,Repairs to GYM at Arthoon road in ward .50 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/4947,Buildings,Completed,NE-ROYAPURAM,50,48600,Providing gully connection and rain water harvesting at West madha street in ward.50 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/4948,Buildings,Completed,NE-ROYAPURAM,50,49400,Repairs to Amma unavagam at SN street in ward.50 unit 12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/4949,Buildings,Completed,NE-ROYAPURAM,50,80100,"Repairs and maintenance to Anganwadi Centre No.33603010323, 33603010324 & 33603010324 at G.M.Pettai Road in Div-50, Unit-12, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/4950,Buildings,Completed,NE-ROYAPURAM,50,58800,"Repairs and improvements to Anganwadi Centre No.33603010223, 33603010224 & 33603010225 at East kalmandapam road in ward.50 unit 12 zone.5",Own Sources,5,2019-20,2020-21 NE/2019-20/4951,Buildings,Completed,NE-ROYAPURAM,50,49500,Providing water supply arrangements and electrical arragements and other works to GYM building at SN Street in ward.50 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/4952,Buildings,Completed,NE-ROYAPURAM,50,49400,Repairs to public convenience at venkatesan street in ward.50 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/4953,Buildings,Completed,NE-ROYAPURAM,50,93000,Providing water supply arrangements to anganwadi ( shed no.33603010522) at periyathambi street in ward.50 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/4954,Buildings,Completed,NE-ROYAPURAM,50,25900,Providing water supply and drainage arrangements to public convenience at Thambu street in ward.50 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/5133,Buildings,Completed,NE-ROYAPURAM,50,980000,"SUPPLY, DELIVERY AND INSTALLATION OF PREFABRICATED/ MODULAR TOILET AT ISLAND GROUND ETC., COMPLETE INCLUDING ALL NECESSARY ARRANGEMENTS, FITTINGS, PLUMBING WORKS, ELECTRICAL WORKS AND FOUNDATION WORKS AS DIRECTED BY THE ENGINEER -IN- CHARGE.IN DIVISION-60, UNIT-13, ZONE-5.",Own Sources,5,2019-20,2021-22 NE/2019-20/6190,Buildings,Completed,NE-ROYAPURAM,50,985000,"Desilting of Existing Storm Water Drain at Flag Staff Street,G M Pettai Road (On Eastern Side)(Arch Drain),G M Pettai Road (On Western Side),St Xavier Street,Sheike Mastry Street,Sheike Mastry 1st Lane,Lotus Ramasamy Street,Kuppu Lane,Mariamman Koil Street,Thulukanathamman Koil Street,Etc. in Dn-50,Unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6234,Storm Water Drain,Completed,NE-ROYAPURAM,50,108000,"Replacing of Manhole Doors at Flag Staff Street,G M Pettai Road (On Eastern Side)(Arch Drain),G M Pettai Road (On Western Side),St Xavier Street,Sheike Mastry Street,Sheike Mastry 1st Lane,Lotus Ramasamy Street,Kuppu Lane,Mariamman Koil Street,Thulukanathamman Koil Street,Etc in Division-50,Unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6286,Storm Water Drain,Completed,NE-ROYAPURAM,50,800000,"Improvements to existing storm water Drains at Thulukanathamman Koil Street,East Mada church street,Sheike Mastry Street,West Mada church street,Bazaar street,S N ������������������ Street (West Side),S N ������������������ Street (East Side),Mannarsamy Koil Street (From East Kalmandapam Road to Andiappan Street Eastern Side),Andiappan (From Mannarsamy Koil Street to West Madha koil Street)etc...in Div-50,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6469,Roads,Completed,NE-ROYAPURAM,50,2979000,"FROMING FOOTPATH AT EAST MADHA CHRUCH STREET (FROM AJITH TRAVELS TO AMMAN TEMPLE) IN DIV-50, UNIT-12, ZONE-05",Own Sources,5,2019-20,2021-22 NE/2019-20/7212,Buildings,Completed,NE-ROYAPURAM,50,896000,Providing footpath at aundiappan street (M.S Koil Street to Nagathamman koil street)in ward.50 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/10456,Buildings,Completed,NE-ROYAPURAM,51,215000,"Repais and improvementts to Chennai High School at manikandan 8 th street in dn-51,unit12,zone5.",Own Sources,5,2019-20,2020-21 NE/2019-20/10457,Buildings,Completed,NE-ROYAPURAM,51,169000,"Repairs and improvements to toilet blocks and verandah in division office at manikandan 3rd street in dn-51,unit12,zone5.",Own Sources,5,2019-20,2020-21 NE/2019-20/10459,Buildings,Completed,NE-ROYAPURAM,51,122000,"Repais and improvements to SI room,doctor room in unit office campus at Perambalu street in dn-51,unit12,zone5.",Own Sources,5,2019-20,2020-21 NE/2019-20/1182,Buildings,Completed,NE-ROYAPURAM,51,86000,"Providing Well Ring Mulch Pit at Various Street in ( Dn-51, Unit-12, Zone-5 )",Own Sources,5,2019-20,2019-20 NE/2019-20/14273,Roads,Completed,NE-ROYAPURAM,51,2190000,"Road cut and Relaying of BT Road with Paver finisher at West Cemertry Road in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14335,Roads,Completed,NE-ROYAPURAM,51,895000,"Road cut and Relaying of BT Road with Paver finisher at South Cemertry Road in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14337,Roads,Completed,NE-ROYAPURAM,51,1930000,"Road cut Restoration and Relaying of BT Road at Selva Vinayagar Koil Street in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14338,Roads,Completed,NE-ROYAPURAM,51,2966000,"Road cut Restoration and Relaying of BT Road at Perambalu Street in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14339,Roads,Completed,NE-ROYAPURAM,51,3625000,"Road cut Restoration and Relaying of BT Road at Narayanappan Street in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14340,Roads,Completed,NE-ROYAPURAM,51,85000,"Relaying of Patch Work BT Road at P.C.Lane in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14349,Roads,Completed,NE-ROYAPURAM,51,211000,"Relaying of Patch Work Cement Concrete Road at Selva Vinayagar Koil Lane in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14351,Roads,Completed,NE-ROYAPURAM,51,83000,"Relaying of Patch Work Cement Concrete Road at Manikandan Lane in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14353,Roads,Completed,NE-ROYAPURAM,51,225000,"Road Cut Restoration and Relaying of Cement Concrete Road at Thulukkanam Street in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14355,Roads,Completed,NE-ROYAPURAM,51,328000,"Road Cut Restoration and Relaying of Cement Concrete Road at Gangan Street (East - West) in Div-51, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/1996,Parks,Completed,NE-ROYAPURAM,51,27000,"Construction of Muich pit with Bamboo barrier for compost unit Cemetry road at MIG flats & Manigandan 6th lane in Div-51,Unit-12,Zone-V.",Own Sources,5,2019-20,2019-20 NE/2019-20/2009,Roads,Completed,NE-ROYAPURAM,51,144000,"Providing Weighing Machine at various Location Ward-50,51,52,53,54,55,61,63 Unit-12, 13, 14 in Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2968,Buildings,Completed,NE-ROYAPURAM,51,160000,"Water Supply & Bore well Arrangement at Chennai Primary School in East cementry Road (Manikandan (M) 6th Street) in Div-51,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/2969,Buildings,Completed,NE-ROYAPURAM,51,195000,"Water Supply & Bore well Arrangement at Chennai Primary School Cemetry Road in Div-51,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/2971,Buildings,Completed,NE-ROYAPURAM,51,160000,"Water Supply & Bore well Arrangement at Chennai Urudu Boys Primary School Easst cementry Road, old Washermenpet in Div-51,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/2975,Buildings,Completed,NE-ROYAPURAM,51,390000,"Water Supply & Bore well Arrangement at Chennai High School Manikanda 8th Street in Div-51,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/2976,Buildings,Completed,NE-ROYAPURAM,51,160000,"Water Supply & Bore well Arrangement at Chennai Urudu High School East cementry Road, Old Washermenpet in Div-51,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/2978,Buildings,Completed,NE-ROYAPURAM,51,320000,"Water Supply & Bore well Arrangement at Chennai Middle School Sanjeevirayan st in Div-51,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/6197,Storm Water Drain,Completed,NE-ROYAPURAM,51,233000,"Desilting of Storm Water Drain at N.N. Garden 8th Lane,Narasaiar Street,Ramanujam Street,Jandara Pilliar Koil Street,Manikandan 6th Street,Vadivelu Street,Narayanappan Street,East Cementry Road,Cementry Road,West Cemetry road,Thulukanam Street,Kaligarayan Street in Division-51,Unit-12,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/6235,Storm Water Drain,Completed,NE-ROYAPURAM,51,108000,"Replacing of Manhole Doors of Storm Water Drain at N.N. Garden 8th Lane,Narasaiar Street,Ramanujam Street,Jandara Pilliar Koil Street,Manikandan 6th Street,Vadivelu Street,Narayanappan Street,East Cementry Road,Cementry Road,West Cemetry road,Thulukanam Street,Kaligarayan Street in Division-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/6253,Buildings,Completed,NE-ROYAPURAM,51,87000,"Improvements to Existing Storm Water Drain at Thulukanam Street,Vadivelu Street,East Cementry Road in Div-51,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/0213,Parks,Completed,NE-ROYAPURAM,52,161000,"Construction of Mulch pit with Bamboo barrier for compost unit Anna park at Cementry Road in Div-52, Unit-12, Zone-V ( asset : 013/16041/199/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/1181,Buildings,Completed,NE-ROYAPURAM,52,483000,"Providing Well Ring Mulch Pit at Various Street in ( Dn-52, Unit-12, Zone-5 )",Own Sources,5,2019-20,2019-20 NE/2019-20/13124,Roads,Completed,NE-ROYAPURAM,52,1554000,"Improvement of relaying. B.T road at Thoppai Street( From Cementry road to appaiar lane) in DIv-52, Unit-12, Zone-V Asst code:044/2399/17667/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/13127,Roads,Completed,NE-ROYAPURAM,52,2209000,"Improvement of relaying C.C road at Adam street (Cemetry Road to Barbar lane) in Div-52, Unit-12, Zone-5 Asst code: 044/2350/17666/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/13134,Roads,Completed,NE-ROYAPURAM,52,312000,"Improvement of relaying C.C road at Model line 2nd Lane in Div-52, Unit-12, Zone-5 Asst code: 041/2376/1407/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/13135,Roads,Completed,NE-ROYAPURAM,52,267000,"Improvement of relaying C.C road at Model line 3rd Lane in Div-52, Unit-12, Zone-5 asst code: 041/2375/1408/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/13138,Roads,Completed,NE-ROYAPURAM,52,150000,"Improvement of relaying C.C road at Model line 10th Lane in Div-52, Unit-12, Zone-5 Asst code:041/2378/1415/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/13139,Roads,Completed,NE-ROYAPURAM,52,256000,"Improvement of relaying C.C road at Mannarsamy Koil Lane in Div-52, Unit-12, Zone-5 Asst code: 040/2341/3779/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/15183,Buildings,Completed,NE-ROYAPURAM,52,227000,"Water supply & Bore Well Arrangement at Public Convenience in Vanigavalagam M.C Road in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2021-22 NE/2019-20/15193,Buildings,Completed,NE-ROYAPURAM,52,178000,"Repairs to Public Convenience in Jaganathan Street in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2021-22 NE/2019-20/2630,Roads,Completed,NE-ROYAPURAM,52,950000,"Improvements to storm water drain in Anna park in cementry Road Div-52 , Unit-12, Zone-V asset code: 013/16041/199/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/3632,Buildings,Completed,NE-ROYAPURAM,52,138000,"Water supply & Bore Well Arrangement t at Public Convenience in O.S.H Road in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/4576,Buildings,Completed,NE-ROYAPURAM,52,172000,"Water supply & Bore Well Arrangement t at Public Convenience in Durai Street in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/4803,Storm Water Drain,Completed,NE-ROYAPURAM,52,985000,"Dismantling and reconstruction of slab for storm water drain at munusamy garden 3rd street in Div-52, unit-12, zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/4805,Storm Water Drain,Completed,NE-ROYAPURAM,52,1095000,"Dismantling and reconstruction of slab for storm water drain at Andiappan Street in Div-52, unit-12, zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/5184,Buildings,Completed,NE-ROYAPURAM,52,441000,IMPROVEMENTS TO THE AMMA UNAVAGAM AT M.C ROAD IN DN-52 UNIT-12 ZONE-5,Own Sources,5,2019-20,2020-21 NE/2019-20/6294,Storm Water Drain,Completed,NE-ROYAPURAM,52,195000,"Replace of Manhole doors of Existing Storm Water Drain at Various Streets (Rope Godown Street,Old slaughter House Road,Model lane 5th Street,Model Lane 9th Street,Velayudha Pandi Street,Jagannathan Street,Pitchandi Lane,East Rope Godown Street (Cemetry Lane),Cemetry Road,Andiappan Street,Munusamy 3rd Street,M,C Road (Service road) and M.S.Koil Street) in Division -52,Unit -12,Zone -5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6295,Storm Water Drain,Completed,NE-ROYAPURAM,52,505000,"Desilting of Existing Storm Water Drain at Various Streets (Rope Godown Street,Old slaughter House Road,Model lane 5th Street,Model Lane 9th Street,Velayudha Pandi Street,Jagannathan Street,Pitchandi Lane,East Rope Godown Street (Cemetry Lane),Cemetry Road,Andiappan Street,Munusamy 3rd Street,M,C Road (Service road) and M.S.Koil Street) in Division -52,Unit -12,Zone -5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6296,Storm Water Drain,Completed,NE-ROYAPURAM,52,462000,"Improvements to Existing Storm Water Drain at Various Streets (Rope Godown Street,Old slaughter House Road,Model lane 5th Street,Model Lane 9th Street,Velayudha Pandi Street,Jagannathan Street,Pitchandi Lane,East Rope Godown Street (Cemetry Lane),Andiappan Street,Munusamy 3rd Street and M.S.Koil Street) in Division -52,Unit -12,Zone -5.",Own Sources,5,2019-20,2019-20 NE/2019-20/7313,Roads,Completed,NE-ROYAPURAM,52,192000,"Water supply & Bore Well Arrangement t at Public Convenience in Meenatchi amman pettai (Dhobikana) in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/7314,Roads,Completed,NE-ROYAPURAM,52,192000,"Water supply & Bore Well Arrangement t at Public Convenience in Rope godown street in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/7315,Roads,Completed,NE-ROYAPURAM,52,192000,"Water supply & Bore Well Arrangement t at Public Convenience in Cementry Road in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/7316,Roads,Completed,NE-ROYAPURAM,52,192000,"Water supply & Bore Well Arrangement t at Public Convenience in Raman 8th Street in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/7317,Roads,Completed,NE-ROYAPURAM,52,192000,"Water supply & Bore Well Arrangement t at Public Convenience in Model line 8th street in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/7318,Roads,Completed,NE-ROYAPURAM,52,192000,"Water supply & Bore Well Arrangement t at Public Convenience in Model 1st street in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/7319,Roads,Completed,NE-ROYAPURAM,52,192000,"Water supply & Bore Well Arrangement t at Public Convenience in Old Jail Road ( Inside stanley hospital) in Div- 52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/7929,Buildings,Completed,NE-ROYAPURAM,52,32000,"Repairs to Tower-clock in Anna Park at Cementry Road in DIv-52, Unit-12, Zone-V",Own Sources,5,2019-20,2020-21 BR/2019-20/15814,Roads,Completed,BR-Bus Route Roads,53,1114000,"Partly relaying the road with BC after cold milling by paver finisher at Parthasarathy Over Bridge Road (From the Jn of Basin Bridge Road to Toe point of flyover)- Part in Dn-53 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/6454,Footpath,Completed,BR-Bus Route Roads,53,6260000,"Forming Footpath at Basin Bridge Road in Dn-53, Zone-V",Grants,5,2019-20,2020-21 D/2019-20/8749,Storm Water Drain,Completed,D-Storm Water Drains,53,13033000,"Demolition and Reconstruction of Storm Water Drain of size 900 x 900 mm along PP Koil East street and 1 st street from PP Koil East street end to CB road in Dn - 53, Zone - V",Own Sources,5,2019-20,2020-21 NE/2019-20/0207,Buildings,Completed,NE-ROYAPURAM,53,14000,"Construction of Mulch Pit With Bamboo Barrier for Compose unit Andhra park ( Division-53,unit-12,Zone-5) Asst code; 013/2775/815/2014-15)",Own Sources,5,2019-20,2019-20 NE/2019-20/0230,Buildings,Completed,NE-ROYAPURAM,53,14000,"Construction of Mulch Pit With Bamboo Barrier for Compose unit mint modern city park Division-53,unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/0404,Playfields,Completed,NE-ROYAPURAM,53,1846000,"Relaying of Paver Finisher at T.H SERVICE Road B.T.Road (Div-53,Unit-12,Zone-5) (Asset code 040/19438/3768/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/0943,Buildings,Completed,NE-ROYAPURAM,53,343000,"Improvments of Proposed Compost Yard Using Polypropylene Tubs in the Old Tranfer Station at Basin Bridge Road in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/10551,Buildings,Completed,NE-ROYAPURAM,53,2650000,"Proposed Construction of Multipurpose Hall at Bojaraja nagar main road in Divsion-53,Unit-12,Zone-5.",MLACDS,5,2019-20,2021-22 NE/2019-20/10556,Buildings,Completed,NE-ROYAPURAM,53,2930000,"Providing Chain Link Fencing and Water supply arrangements of Moolakothalam Burial Ground at Kathbada high road in Dn-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/10727,Buildings,Completed,NE-ROYAPURAM,53,950000,"Construction of MCC at North Wall Road in Dn-53,Unit-12,Zone-5.",Swacch Bharat Mission,5,2019-20,2020-21 NE/2019-20/10733,Buildings,Completed,NE-ROYAPURAM,53,950000,"Construction of MCC at North Wall Road in Dn-53,Unit-12,Zone-5.",Swacch Bharat Mission,5,2019-20,2020-21 NE/2019-20/11049,Buildings,Completed,NE-ROYAPURAM,53,2082000,"Construction of Platform and Shed Truss Work at Moolakothalam Burial Ground in Dn-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/1170,Buildings,Completed,NE-ROYAPURAM,53,350000,"Providing Well Ring Mulch Pit at Various Street in ( Dn-53, Unit-12, Zone-5 )",Own Sources,5,2019-20,2019-20 NE/2019-20/1425,Roads,Completed,NE-ROYAPURAM,53,353000,"Repairs and Improvements of Lorry station at Basin Bridge Road ( Division -53,Unit-12,Zone-5)",Own Sources,5,2019-20,2019-20 NE/2019-20/2880,Buildings,Completed,NE-ROYAPURAM,53,195000,"Water Supply & Borewell Arrangement at Chennai primary School C.B road in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/2883,Buildings,Completed,NE-ROYAPURAM,53,160000,"Water Supply & Bore well Arrangement at Chennai primary School Bojaraja Nagar in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/3045,Buildings,Completed,NE-ROYAPURAM,53,1849000,"Construction of compound Wall and improvements to the Burial ground in moolakothalam burial ground in DIV-53, Unit-12, Zone-V Asset:128/52/2013-14",Own Sources,5,2019-20,2020-21 NE/2019-20/3126,Buildings,Completed,NE-ROYAPURAM,53,310000,"Repair and Maintenance Of Building in Kondithope UPHC (Phase - II) at Basin Bridge Road in Dn-53, Unit-12,Zone-5 (Asset: code: 015/19443/2/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/3127,Buildings,Completed,NE-ROYAPURAM,53,980000,"Repairs and Improvements of Stock Room,C.I room,Machine Room,Public Convenience at Micro Composting Center in Division-53,Unit-12,Zone-5 (Asset Code:156/19443/790/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/3622,Buildings,Completed,NE-ROYAPURAM,53,1485000,"Construction of New Shed at Micro Composting Center(M.C.C) in Div-53,Unit-12,Zone-5.(Asset Code:156/19443/790/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/3710,Electrical,Completed,NE-ROYAPURAM,53,70000,"Repairs and Maintenance AMMA UNAVAGAM at Dr.Vijayaraghavalu Road near Kannan Rountana in Div-53,Unit-12,Zone-5 ( Asset code:B/1938/1149/2014-15 )",Own Sources,5,2019-20,2019-20 NE/2019-20/3875,Buildings,Completed,NE-ROYAPURAM,53,1670000,"Room Shifting Arrangement And Entire Building(outer wall) Painting in RDC(North) Office at Div-53,Unit-12,Zone-5.(Asset code:025/19443/9/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/5330,Buildings,Completed,NE-ROYAPURAM,53,154000,"Water Supply & Bore well Arrangement at Public Convenience K.H Road in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/5507,Buildings,Completed,NE-ROYAPURAM,53,220000,"Attending Essential/Urgent Improvement Works to all GCC assets such as P.C,Schools,Community Centre,Division Office,Etc. at Various Location in Div-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/5729,Buildings,Completed,NE-ROYAPURAM,53,820000,"Construction of Proposed Compost Yard Using Polypropylene Tubs PHASE-II in the Micro Composting center(MCC) at Basin Bridge Road in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/6183,Buildings,Completed,NE-ROYAPURAM,53,622000,"Desilting of Existing Storm Water Drain at Parthasarathy Service Road,Pensioners 3rd Street,Pensioners 3rd Cross Street,Pensioners 4th Street,Kathbada Main Road,Basin Bridge Road,C.B. Road,Padavattamman Koil Street,Peddu (N) Street,V.O.C. Salai,North Wall Road,Stanly Nagar 4th Street,Stanly Nagar 5th Street,Stanly Nagar 6th Street,Etc. in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6230,Storm Water Drain,Completed,NE-ROYAPURAM,53,180000,"Replacing of Manhole Doors at Parthasarathy Service Road,Pensioners 3rd Street,Pensioners 3rd Cross Street,Pensioners 4th Street,Kathbada Main Road,Basin Bridge Road,C.B. Road,Padavattamman Koil Street,Peddu (N) Street,V.O.C. Salai,North Wall Road,Stanly Nagar 4th Street,Stanly Nagar 5th Street,Stanly Nagar 6th Street,Etc in Division-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6247,Storm Water Drain,Completed,NE-ROYAPURAM,53,693000,"Improvements to existing Storm Water Drain at Kathbada Main Road,Pensioners 3rd Cross Street,P.P. Amman Koil East Street,P.P. Amman Koil 1st Lane,Stanly Nagar 6th Street,Basin Bridge Road,North Wall Road,V.o.c salai (Wall tax road),C.B. Road in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6288,Buildings,Completed,NE-ROYAPURAM,53,1110000,"Construction of Storm Water Drain at Bojaraja nagar Huting Ground in Div-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/6290,Storm Water Drain,Completed,NE-ROYAPURAM,53,770000,"Laying Cement Concrete Road at Bojaraja nagar huting ground in div-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/6730,Buildings,Completed,NE-ROYAPURAM,53,1995825,"PROPOSED CONSTRUCTION OF TOILET AND BATHROOMS AT DR VIJAYA RAGAVALU SALAI (EAST) IN DIVISION-53, UNIT-12, ZONE-5.",MLACDS,5,2019-20,2020-21 NE/2019-20/6735,Buildings,Completed,NE-ROYAPURAM,53,3000000,"PROPOSED CONSTRUCTION OF 16th CEREMONY HALL AT DR VIJAYA RAGAVALU SALAI (EAST) IN DIVISION-53, UNIT-12, ZONE-5.",MLACDS,5,2019-20,2020-21 NE/2019-20/7079,Buildings,Completed,NE-ROYAPURAM,53,56000,"Providing of Submersible Motor at C.B Road Motor Room and Supply & fixing Drinage Pipe of Public convenience at Kathbada main road near ITI in Div-53,Unit-12,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/7187,Roads,Completed,NE-ROYAPURAM,53,1120000,"Relaying of CC Road at Bojaraja nagar Cross Lane Hunted area in Div -53,unit-12,Zone-5. (Asset code:040/1940/9773/2014-15 )",Own Sources,5,2019-20,2020-21 NE/2019-20/7188,Storm Water Drain,Completed,NE-ROYAPURAM,53,460000,"Desilting at Bojaraja nagar Main Street,1st Street,2nd Street,South Lane,PP Amman Koil East ,Kathpada Main StreetAt Div-53,Unit-12,zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/7234,Buildings,Completed,NE-ROYAPURAM,53,560000,"Providing and Forming of Roof Garden at Regional Deputy Commissioner Office(North) Office In Division-53,Unit-12,Zone-5 (asset code : 025/19443/9/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/7249,Roads,Completed,NE-ROYAPURAM,53,2221000,"Relaying of Paver Finisher at T.H SERVICE Road B.T.Road (Div-53,Unit-12,Zone-5)",Own Sources,5,2019-20,2020-21 NE/2019-20/7335,Buildings,Completed,NE-ROYAPURAM,53,998000,"Improvements of Community Hall at Stanley nagar 5th Street in Dn-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2021-22 NE/2019-20/7340,Buildings,Completed,NE-ROYAPURAM,53,241000,"Laying Cement Concrete at Sajja Munusamy 2nd Lane at Dn-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/7342,Buildings,Completed,NE-ROYAPURAM,53,105000,"Laying Cement Concrete at Sajja Munusamy 8th Lane at Dn-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/7343,Buildings,Completed,NE-ROYAPURAM,53,138000,"Laying Cement Concrete at Parasuram 1st Lane at Dn-53,Unit-12,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/8078,Buildings,Completed,NE-ROYAPURAM,53,275000,"Repairs and Maintenance to the Amma Unavagam at Dr.Vijayaraghavalu road near Kannan Rountana in Dn-53,Unit-12,Zone-5.(Asset code:B/1938/1149/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/8311,Buildings,Completed,NE-ROYAPURAM,53,360000,"Improvements to the Motor Room at C.B Road near Subway in Dn-53,Unit-12,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/8466,Buildings,Completed,NE-ROYAPURAM,53,310000,improvements to tower clock at basin bridge road (near mint old busstand) in ward.53 unit.12 zone.5,Own Sources,5,2019-20,2020-21 NE/2019-20/8667,Electrical,Completed,NE-ROYAPURAM,53,669000,"Electrification work, Panel Board fixing,Supply and Fixing of Fan Tube light,Plug points etc at Micro Composting Centre at Basin Bridge Road in Div-53 in Zone-5.(Asset code:156/19443/790/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/8922,Buildings,Completed,NE-ROYAPURAM,53,654000,"Improvements to RDC North office in basin bridge Road in Div-53, Unit-12, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/9139,Roads,Completed,NE-ROYAPURAM,53,1122000,"Supply and Fixing Baling Machines at M.C.C Center at Basin Bridge Road & Water Basin Street in Ward-53 & 57, Unit-12 & 13, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/9371,ROB,Completed,NE-ROYAPURAM,53,255000,"PROVIDING 4 NOS OF CCTV CAMERA WITH ALL ACCESSRIES AND COMMUNICATING WITH ANDRIOD PHONE TO MONITORING FROM ONLINE IN MICRO COMPOSTING CENTER AT BASIN BRIDGE ROAD IN DIV-53, UNIT-12, ZONE-05",Own Sources,5,2019-20,2020-21 NE/2019-20/9977,Buildings,Completed,NE-ROYAPURAM,53,146000,"Improvement to Zonal Office-5 in Basin Bridge at Ward-53, Unit-12, Zone-5",Own Sources,5,2019-20,2021-22 B/2019-20/3811,Buildings,Completed,B-Buildings,54,3958000,"Proposed Construction of Multipurpose Hall @ Mint Street Division-54, Zone-5.",MLACDS,5,2019-20,2020-21 BR/2019-20/15796,Roads,Completed,BR-Bus Route Roads,54,1003000,"Partly relaying the road with BC after cold milling by paver finisher at Old jail Road in Dn-54 & 58 , Zone - 5",Grants,5,2019-20,2020-21 NE/2019-20/0208,Parks,Completed,NE-ROYAPURAM,54,27000,"Construction of Munch Pit with necessary arrangement of Bamboo Sticks at Sivagnanam Park in div-54, Unit-13, Zone-V (Asset Code: 013/2421/503/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/0670,Buildings,Completed,NE-ROYAPURAM,54,1248000,"Additional Construction of compost yard at Walltax Road in Div - 54, Unit-13, Zone-5 (Asset Code:R/3973/5203/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/0901,Buildings,Completed,NE-ROYAPURAM,54,1000000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) AT THIRUPALLI BUS STAND , VOC SALAI, SOWCARPET(10 Months (300Days)) IN DIV-54, UNIT-13, ZONE-05",Own Sources,5,2019-20,2020-21 NE/2019-20/14288,Roads,Completed,NE-ROYAPURAM,54,946000,"Restoration of CC Road at Nambulyar Street in Divisio-54, Unit-13, Zone-5 (Asset code:040/3979/5669/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14320,Roads,Completed,NE-ROYAPURAM,54,219000,"Patches of CC Road at Peddu Street in Divisio-54, Unit-13, Zone-5 (Asset code:044/2421/16103/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14322,Roads,Completed,NE-ROYAPURAM,54,88000,"Patches of CC Road at Mullah Street in Divisio-54, Unit-13, Zone-5 (Asset code:044/3980/16328/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14325,Roads,Completed,NE-ROYAPURAM,54,55000,"Patches of CC Road at Thandavaran Street in Divisio-54, Unit-13, Zone-5 (Asset code:040/4026/5695/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14328,Roads,Completed,NE-ROYAPURAM,54,6280000,"Relaying of BT Road at Mnit Street in Divisio-54, Unit-13, Zone-5 (Asset code:044/2430/16095/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/1807,Buildings,Completed,NE-ROYAPURAM,54,186000,"Providing Well RIngs Mulch Pit at Various in Ward-54,Unit-13,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/3022,Buildings,Completed,NE-ROYAPURAM,54,192000,"Water supply & Bore Well Arrangement at Public Convenience at Door No.349,V.O.C Salai in Div-54, Unit-13, Zone-V(Asset Code: 180/3973/308/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/3038,Buildings,Completed,NE-ROYAPURAM,54,165000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI HIGH SCHOOL AT AMMAN KOIL STREET IN DN-54,UNIT-13,ZONE-V (ASSET CODE:156/3989/1076/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/4454,Buildings,Completed,NE-ROYAPURAM,54,21673,"Repairs and Maintenance of Division Office at Walltax road, Sowcarpet, George Town,Chennai-79 in Dn-54, Unit-13, Zone-V (Asset Code: B/3973/591/2013-14 )",Own Sources,5,2019-20,2019-20 NE/2019-20/4455,Buildings,Completed,NE-ROYAPURAM,54,41000,"Name of the work :Repairs and Maintenance of Old Division Office(Si/Ci Office) at Mint Street, George Town,Chennai-79 in Dn-54, Unit-13, Zone-V (Asset Code: B/3981/1165/2014-15 )",Own Sources,5,2019-20,2019-20 NE/2019-20/4456,Buildings,Completed,NE-ROYAPURAM,54,57000,"Name of the work :Repairs and Maintenance of Chennai Middle School at Amman Koil Street, George Town,Chennai-79 in Dn-54, Unit-13, Zone-V (Asset Code: 156/3989/1076/2014-15 )",Own Sources,5,2019-20,2019-20 NE/2019-20/4457,Buildings,Completed,NE-ROYAPURAM,54,599000,"Improvement to existing NNMP (Anganwadi Center Code:090311 & 090312) at Wood warf 3rd Lane, George Town,Chennai-79 in Dn-54, Unit-13, Zone-V (Asset Code: 041/16451/1238/2013-14 )",Own Sources,5,2019-20,2021-22 NE/2019-20/4458,Buildings,Completed,NE-ROYAPURAM,54,31000,"Repairs and Maintenance of PC at Wood warf 1st Lane, George Town,Chennai-79 in Dn-54, Unit-13, Zone-V (Asset Code:033/4020/671/2012-13)",Own Sources,5,2019-20,2019-20 NE/2019-20/5667,Buildings,Completed,NE-ROYAPURAM,54,74000,"Repairs and Maintenance work in PC at Wood warf 3rd Lane, Sowcarpet,George Town,Ch-79 in Dn-54, Unit-13, Zone-V (Asset Code: 041/16451/1232/2013-14 )",Own Sources,5,2019-20,2019-20 NE/2019-20/6210,Storm Water Drain,Completed,NE-ROYAPURAM,54,178000,"Desilting of existing SWD at Mint Street, Saravanan street, Bashyakaralu street, Kancheepuram sabapathy street, Amman koil street, Chakkarai street, Sundaram street, PKG 3rd lane, PKG 4th lane, Thirupalli Street in div-54, unit-13, zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6222,Storm Water Drain,Completed,NE-ROYAPURAM,54,108000,"Replacing of Manhole doors at Mint Street, Saravanan street, Bashyakaralu street, Kancheepuram sabapathy street, Amman koil street, Chakkarai street, Sundaram street, PKG 3rd lane, PKG 4th lane, Thirupalli Street in div-54, unit-13, zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6251,Storm Water Drain,Completed,NE-ROYAPURAM,54,231000,"Improvement to existing SWD at Mint street, Saravanan street, Bashyakaralu street, Sundaram street, PKG 3rd lane, PKG 4th lane in div-54, unit-13, zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6409,Buildings,Completed,NE-ROYAPURAM,54,228000,"Repairs and Maintenance work in PC at 349,wall tax road, Sowcarpet,George Town,Ch-79 in Dn-54, Unit-13, Zone-V (Asset Code:033/3973/490/2013-14 )",Own Sources,5,2019-20,2019-20 NE/2019-20/6411,Buildings,Completed,NE-ROYAPURAM,54,52000,"Repairs and Maintenance work in PC at Mint Street, Sowcarpet,George Town,Ch-79 in Dn-54, Unit-13, Zone-V (Asset Code: 033/2430/507/2013-14 )",Own Sources,5,2019-20,2019-20 NE/2019-20/7437,Buildings,Completed,NE-ROYAPURAM,54,508000,"Improvement works at Public Convenience(Gents) in mint street at Div-54, Unit-13, Zone-V (Asset Code: 033/3981/670/2012-13)",Own Sources,5,2019-20,2020-21 NE/2019-20/7844,Roads,Completed,NE-ROYAPURAM,54,2361000,"Attending Potholes at Variou Street in Div-49, 50, 52, 53, 54, 55, 56, 58, 59, 60, 61, 62 & 63, Unit-12, 13 & 14, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/7846,Roads,Completed,NE-ROYAPURAM,54,3890000,"Attending patches at Variou Street in Div-49,52, 53, 57, 58, 59, 60, 61, 62 & 63, Unit-12, 13 & 14, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/8431,Buildings,Completed,NE-ROYAPURAM,54,1135000,"Repairs and Maintenance to existing Chennai Middle School at 130,Amman Koil Street , George Town, Chennai-79 in Dn-54, Unit-13, Zone-V (Asset Code: 156/3989/1076/2014-15 )",Own Sources,5,2019-20,2020-21 NE/2019-20/9596,Buildings,Completed,NE-ROYAPURAM,54,1152000,"Improvement to Multi Purpose Hall at Vadamalai Street in Div-54, Unit-13, Zone-V (Asset Code:B/3974/2311/2019-20)",Own Sources,5,2019-20,2020-21 NE/2019-20/9804,Parks,Completed,NE-ROYAPURAM,54,760000,Providing New Road Side Park at Telegraph abbai lane in Dn-54 Unit-13 zone-05,MLACDS,5,2019-20,2020-21 BR/2019-20/15798,Roads,Completed,BR-Bus Route Roads,55,1003000,"Partly relaying the road with BC after cold milling by paver finisher at Prakasam Salai in Dn-55,56 & 57 , Zone - 5",Grants,5,2019-20,2020-21 D/2019-20/8292,Storm Water Drain,Completed,D-Storm Water Drains,55,11819000,"Dismantling and Reconstruction of Storm Water Drain of Size 900 x 900mm along Telegraph Abboy street from Kuppiahar street to Waltax road in Dn - 55, Zone -V.",Own Sources,5,2019-20,2020-21 D/2019-20/8293,Storm Water Drain,Completed,D-Storm Water Drains,55,11819000,"Construction of Storm Water Drain of Size 900 x 900mm along Portugese Church street from Xavier street to Old Jail road in Dn - 55, Zone -V.",Own Sources,5,2019-20,2020-21 D/2019-20/8750,Storm Water Drain,Completed,D-Storm Water Drains,55,10745000,"Construction of Storm Water Drain of size 900 x 900 mm along Kuppiahar street from Muthukrishnan street to Sevenwells street in Dn - 55, Zone - V.",Own Sources,5,2019-20,2020-21 D/2019-20/8751,Storm Water Drain,Completed,D-Storm Water Drains,55,11819000,"Construction of Storm Water Drain of size 900 x 900 mm along Mint street from Kuppiahar street to Old Jail road in Dn - 55, Zone - V.",Own Sources,5,2019-20,2020-21 L/2019-20/8782,Electrical,Completed,L-Electrical,55,1615300,Replacement of 2450 mtrs 2CX25sq.mm and 875 mtrs 3 1/2 x25 sqmm Alu cable at Various Location in Div 53 Part and 57 part in Zone-5 WEST GT Section,Grants,5,2019-20,2020-21 NE/2019-20/0223,Parks,Completed,NE-ROYAPURAM,55,14000,"Construction of Mulch pit with Bamboo barrier for compost unit at Barracks Play Ground in Division-55, Unit-13, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/10120,Buildings,Completed,NE-ROYAPURAM,55,2958663,"CONSTRUCTION OF ANGANWADI BUILDING AT NATTU PILLAIYAR KOIL STREET IN DIVISION-55,UNIT-13,ZONE-5",MPLADS,5,2019-20,2021-22 NE/2019-20/10369,Buildings,Completed,NE-ROYAPURAM,55,2957658,"CONSTRUCTION OF ANGANWADI BUILDING AT ST XAVIER STREET IN DIVISION-55,UNIT-13,ZONE-5",MPLADS,5,2019-20,2020-21 NE/2019-20/10791,Buildings,Completed,NE-ROYAPURAM,55,209647,"Demolition of Existing Toilet Block at Nattu Pillaiyar Koil Street & Existing Chennai Middle School at St Xavier Street in Division-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/10976,Roads,Completed,NE-ROYAPURAM,55,536000,"Attending Cement Concrete Patch Work at Paramandha Street in Division-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/1187,Buildings,Completed,NE-ROYAPURAM,55,300000,"Proposed Construction of Material Recovery Facility at Old Jail Road ( Below the over bridge ) in Ward - 55, Unit-13, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/13295,Roads,Completed,NE-ROYAPURAM,55,201000,"Improvements to Bituminous Concrete Road at Sevenwells street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/13328,Roads,Completed,NE-ROYAPURAM,55,446000,"Improvements to Bituminous Concrete Road at Barracks Street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/13329,Roads,Completed,NE-ROYAPURAM,55,266000,"Improvements to Bituminous Concrete Road at Nattu Pillaiyar Koil Street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/13331,Roads,Completed,NE-ROYAPURAM,55,365000,"Improvements to Bituminous Concrete Road at St Xavier Street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/13332,Roads,Completed,NE-ROYAPURAM,55,665000,"Improvements to Bituminous Concrete Road at Amman Koil Street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/13563,Roads,Completed,NE-ROYAPURAM,55,1031000,"Improvements to Cement Concrete Road at Anaikara Konan Street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/13564,Roads,Completed,NE-ROYAPURAM,55,793000,"Improvements to Cement Concrete Road at Paramanandha Street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/13566,Roads,Completed,NE-ROYAPURAM,55,1505000,"Improvements to Cement Concrete Road at Nagamani Garden Street in Div-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/1749,Buildings,Completed,NE-ROYAPURAM,55,93000,"Providing Well RIngs mulch pilt at various street in ward-55, unit-12, zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2551,Buildings,Completed,NE-ROYAPURAM,55,2700000,"Construction of Additional Auditorium Building in First Floor at Chennai Middle School Portuguese Chruch Street in Division-55,Unit-13,Zone-5",MLACDS,5,2019-20,2019-20 NE/2019-20/6217,Storm Water Drain,Completed,NE-ROYAPURAM,55,489000,"Desilting of Existing Storm Water Drain at Amman Koil Street, Anaikara konar Street, Barracks 1st Lane, Barracks Street, Davidson Street, Girigory Street, Nattu Pillaiyar Koil Street, P.V.Iyer Street, Prakasam Salai, Sevenwells Street, St Xavier Street, Subramani Street & Old Jail Road in Division - 55, Unit -13, Zone - 5",Own Sources,5,2019-20,2019-20 NE/2019-20/6226,Storm Water Drain,Completed,NE-ROYAPURAM,55,90000,"Replacing of Man Hole Door at Amman Koil Street, Anaikara konar Street, Barracks 1st Lane, Barracks Street, Davidson Street, Girigory Street, Nattu Pillaiyar Koil Street, P.V.Iyer Street, Prakasam Salai, Sevenwells Street, St Xavier Street, Subramani Street & Old Jail Road in Division-55, Unit - 13, Zone - 5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6232,Storm Water Drain,Completed,NE-ROYAPURAM,55,115000,"Improvements to Existing Storm Water Drain at Amman Koil Street, Sevenwells Street, Nattu pillaiyar koil Street, PV Iyer Street, Subramani Street & Barracks 1 st Lane in division-55, Unit-13, Zone-V",Own Sources,5,2019-20,2019-20 NE/2019-20/7406,Storm Water Drain,Completed,NE-ROYAPURAM,55,240000,"PROVIDING RWH STRUCTURES @ PORTUGUESE CHURCH ST,OLD JAIL ROAD,PERIYANNAN ST AND SEVEN WELLS STREET IN Dn55,U13,Z5.",Own Sources,5,2019-20,2019-20 NE/2019-20/7462,Storm Water Drain,Completed,NE-ROYAPURAM,55,209000,"PROVIDING RWH STRUCTURES @ PORTUGUESE CHURCH ST,OLD JAIL ROAD AND PERIYANNAN STREET IN DN55,U13,Z5.",Own Sources,5,2019-20,2019-20 NE/2019-20/7469,Buildings,Completed,NE-ROYAPURAM,55,83000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO HEALTH BUILDINGS AT OLD JAIL ROAD, ST.XAVIER ST AND AMMA UNAVAGAM AT NATTU PILLAYAR KOIL STREET IN DN--55,U13,Z-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/7835,Buildings,Completed,NE-ROYAPURAM,55,115000,"Water Supply Arrangements to Public convenience at Samayavarathamman koil street in Division-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/8182,Roads,Completed,NE-ROYAPURAM,55,462000,"Attending Patch Work at Cement Concrete Road(to Avoid rain water Stagnation) at St Xavier Street in division-55,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/9867,Buildings,Completed,NE-ROYAPURAM,55,890000,"Improvements to Anganwadi Center No.851 (33603090126) at Davidson Street Police Quarters Broad way in Division-55, Unit-13, Zone-5",Own Sources,5,2019-20,2020-21 L/2019-20/11573,Electrical,Completed,L-Electrical,56,176300,"Supply and replacement of 6 nos of damaged KIOSK Pillars at Prakasam salai near Valluvar Nagar, Ibrahim salai Jn of Clive Batery, Rajaji Salai near Customs Office, Narayana Sarang Street jn of Ibrahim Salai, Jaffar Sarang street behind GPO and Jaffar Sarang Street opp to National Hospital in Div - 60 in Zone - 5.",Own Sources,5,2019-20,2021-22 NE/2019-20/0229,Parks,Completed,NE-ROYAPURAM,56,27000,"Construction of Mulch pit with Bamboo barrier for compost unit in Maadi Poonga at Ibhrahim Salai in Division-56, Unit-13, Zone-5(Asset Code - 013/2536/496/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/14200,Roads,Completed,NE-ROYAPURAM,56,770000,"IMPROVEMENTS TO CC ROAD IN MADURAI VASAL STREET IN DN-56,UNIT-13,ZONE-5(Asset code-044/2497/16372/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14201,Roads,Completed,NE-ROYAPURAM,56,365000,"IMPROVEMENTS TO CC ROAD IN MADURAI VASAL LANE IN DN-56,UNIT-13,ZONE-5 (Asset code-044/2498/16373/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/2936,Buildings,Completed,NE-ROYAPURAM,56,197000,"IMPROVEMENTS TO NNMP CENTRE AT BRN GARDEN IN DIVISION-56,UNIT-13,ZONE-5",Own Sources,5,2019-20,2020-21 NE/2019-20/3080,Buildings,Completed,NE-ROYAPURAM,56,117000,"Improvements to NNMP Centre at Asirvadhapuram in Division-56,Unit-13,Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/3529,Buildings,Completed,NE-ROYAPURAM,56,35000,"Repair and Maintenance of Bore well at Corporation Urdu Girls Middle School at Amman koil street in Dn-56, Unit-13,Zone-V (Asset Code:019/2492/94/2013-14 )",Own Sources,5,2019-20,2020-21 NE/2019-20/3530,Buildings,Completed,NE-ROYAPURAM,56,35000,"Repair and Maintenance of Bore well at Chennai Middle School in Ramasamy Street Dn-56, Unit-13,Zone-V (Asset Code:019/2526/95/2013-14 )",Own Sources,5,2019-20,2020-21 NE/2019-20/6236,Storm Water Drain,Completed,NE-ROYAPURAM,56,425000,"DESILTING OF EXISTING STORM WATER DRAIN IN AMMAN KOIL STREET, EBRAHIM SALAI, GEILLS STREET, MEERA LABAI STREET, OLD JAIL ROAD, PRAKASAM SALAI, SALAI VINYAGAR KOIL STREET, SAVARIMUTHU LANE, ST,XAVIER STREET, AT DIV-54, UNIT-13, ZONE-5",Own Sources,5,2019-20,2020-21 NE/2019-20/6256,Storm Water Drain,Completed,NE-ROYAPURAM,56,90000,"REPLACING OF MANHOLE DOORS IN EXISTING STORM WATER DRAIN AT SALAI VINAYAGAR KOIL STREET, AMMAN KOIL STREET, ST.XAVIER STREET, MEERA LABAI STREET, EBRAHIM SALAI, OLD JAIL ROAD, PRAKASAM SALAI IN DIV-56, UNIT-13, ZONE-5",Own Sources,5,2019-20,2020-21 NE/2019-20/6258,Storm Water Drain,Completed,NE-ROYAPURAM,56,115000,"IMPROVEMENT TO EXISTING STORM WATER DRAIN IN SAVARIMUTHU LANE, EBRAHIM SALAI, ST.XAVIER STREET, GEILLS STREET AT DIV-56, UNIT-13, ZONE-5",Own Sources,5,2019-20,2020-21 NE/2019-20/8905,Buildings,Completed,NE-ROYAPURAM,56,76000,"PROVIDING BOREWELL ARRANGEMENTS TO PUBLIC CONVENIENCE INSIDE THE URBAN PRIMARY HEALTH CENTER IN BRN GARDEN IN DIVISION-56, UNIT-13, ZONE-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/8906,Parks,Completed,NE-ROYAPURAM,56,334000,"REPAIRS AND IMPROVEMENTS AND REPAIRS TO COMPOUND WALL,PATHWAY RAMP INSIDE THE TERRACE GARDEN IN EBRAHIM SALAI IN DIVISION-58,UNIT-13,ZONE-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/8907,Storm Water Drain,Completed,NE-ROYAPURAM,56,102000,"REPAIRS AND IMPROVEMENTS TO STORM WATER DRAIN AT OLD JAIL ROAD,PRAKASAM SALAI IN DIVISION -56,UNIT-13, ZONE-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/9897,Buildings,Completed,NE-ROYAPURAM,56,2175000,"Repairs and Maintenance to existing Chennai Middle School at Ramasamy Street in Dn-56,Unit-13,Znoe-5 (Asset Code: 019/2526/95/2013-14)",Own Sources,5,2019-20,2021-22 L/2019-20/10349,Electrical,Completed,L-Electrical,57,600100,Electrification work & replacing of 59 nos tube lights 27 nos fan wiring and 1 nos 1.5 ton AC 5 star rating with 110mtr 3 1/2 * 25 sqmm Alu cable at Water basin Street General Store division-57 in Zone-05.,Own Sources,5,2019-20,2020-21 NE/2019-20/0291,Parks,Completed,NE-ROYAPURAM,57,27000,"Installation of Munch Pit with necessary arrangement of Bamboo Sticks at General Store in div-57, Unit-13, Zone-V (Asset Code:156/4172/773/2013-14 )",Own Sources,5,2019-20,2019-20 NE/2019-20/0980,Buildings,Completed,NE-ROYAPURAM,57,2728000,"New proposal to the Compost Yard in Electrical Work Shop at Basin Water Works Street in Division-57, Unit-13, Zone-V (Asset Code:156/4172/773/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/0983,Buildings,Completed,NE-ROYAPURAM,57,2713000,"New Proposal of Compost shredding machine room, Store room and office room in Electrical Work Shop at Water Basin Works Street in div-57, unit-13, zone-5 (Asset Code:156/4172/773/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/10315,Buildings,Completed,NE-ROYAPURAM,57,2500000,"New proposal of Composting yard Truss and Water Supply at General Store in Division-57, Unit-13,Zone-5 (Asset Code:B/4172/941/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/10344,Buildings,Completed,NE-ROYAPURAM,57,2493000,"New proposal of Composting yard at General Store in Division-57, Unit-13, Zone-5(Asset Code:B/4172/941/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/10539,Buildings,Completed,NE-ROYAPURAM,57,1244000,"Renovation of Existing building in Electrical Work Shop at Water Basin Street in Division-57, Unit-13, Zone-5 (Asset Code:B/4172/941/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/10665,Buildings,Completed,NE-ROYAPURAM,57,1850000,"Repairs and Improvements of General work Shop Shed No.1 at Anna Pillai Street in division-57,Unit-13,Zone-5(Asset code:156/2692/778/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/10666,Buildings,Completed,NE-ROYAPURAM,57,1700000,"Repairs and Improvements to Truss work in General work Shop Shed No.2, at Anna Pillai Street in division-57,Unit-13,Zone-5(Asset code:156/2692/778/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/13256,Parks,Completed,NE-ROYAPURAM,57,1400000,"Providing New Road Side Park at Tiruveliyan Basin street (Under MLA Fund) in Div-57, Unit-13, Zone-V(Asset Code:044/4200/16445/2013-14)",MLACDS,5,2019-20,2021-22 NE/2019-20/14182,Roads,Completed,NE-ROYAPURAM,57,2010000,"Restoration and Relaying of BT Road at Basin water work s Street in division-57, Unit-13, Zone-5(Asset Code: 044/4172/16442/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14183,Roads,Completed,NE-ROYAPURAM,57,3039000,"Restoration of CC Road Cut at Kandappa Chetty Street in division-57, Unit-13, Zone-5(Asset Code:044/2714/16521/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14184,Roads,Completed,NE-ROYAPURAM,57,1241000,"Restoration of CC Road Cut at General Muthaiya street in division-57, Unit-13, Zone-5(Asset Code:044/4189/16444/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/15296,Roads,Completed,NE-ROYAPURAM,57,561000,"SUPPLY AND FIXING BALING MACHINES AT M.C.C CENTER AT WATER BASIN STREET IN DIV-57, UNIT-13, ZONE-5",Own Sources,5,2019-20,2020-21 NE/2019-20/1607,Buildings,Completed,NE-ROYAPURAM,57,165000,"Repairs and Maintenance of Bore well IN CHENNAI HIGH SCHOOL AT WALL TAX ROAD IN DN-57,UNIT-13,ZONE-V (ASSET CODE:020/4201/54/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/1823,Buildings,Completed,NE-ROYAPURAM,57,335000,"Providing Well Rings Mulch Pit at Various in Ward-57,Unit-13,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2940,Buildings,Completed,NE-ROYAPURAM,57,35000,"Repair and Maintenance of Bore well at Chennai Middle School in dn-57, Unit-13,Zone-V (Asset Code:019/2692/104/2013-14 )",Own Sources,5,2019-20,2020-21 NE/2019-20/2943,Buildings,Completed,NE-ROYAPURAM,57,200000,"Repairs and Improvements of Anganwadi at wall tax road in division-57, Unit-13,Zone-V (Asset Code:022/4201/336/2013-14 )",Own Sources,5,2019-20,2020-21 NE/2019-20/4327,Buildings,Completed,NE-ROYAPURAM,57,3000000,"New Construction of Public Convenience at Anna pillai Street in Division-57, Unit-13, Zone-5 (Asset Code:033/2692/508/2013-14)",MLACDS,5,2019-20,2020-21 NE/2019-20/6202,Storm Water Drain,Completed,NE-ROYAPURAM,57,18000,"Replacing of Man Hole Door at Ramanan Road(N) and Ramanan Road(S) in Division-57, Unit - 14, Zone - 5.",Own Sources,5,2019-20,2020-21 NE/2019-20/6205,Storm Water Drain,Completed,NE-ROYAPURAM,57,88000,"Desilting of Existing Storm Water Drain at Ramanan Road (N) and Ramanan Road (S) in division-57, Unit-13, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/6214,Storm Water Drain,Completed,NE-ROYAPURAM,57,58000,"Improvements to Existing Storm Water Drain at Ramanan Road (N) and Ramanan Road (S) in division-57, Unit-13, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/8604,Buildings,Completed,NE-ROYAPURAM,57,216000,"Repairs and maintenance of Chennai High school at Wall Tax Road in Dn-57, Unit-13, Zone-V(Asset Code:032/2692/72/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/8715,Buildings,Completed,NE-ROYAPURAM,57,137000,"Repairs and maintenance of Side drain at Jatkapuram in Dn-57,Unit-13, Zone-V (Asset Code:055/4190/4847/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/8723,Buildings,Completed,NE-ROYAPURAM,57,162000,"Repairs and Maintenance of SWD at Audiyappa Naicken Street in Dn-57,Unit-13, Zone-V (Asset Code:055/4159/4850/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/9632,Electrical,Completed,NE-ROYAPURAM,57,1157000,"Additional improvement works and water supply and electrical arrangements to the compost yard at water basin road in Dn-57, U-13,zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/9634,Buildings,Completed,NE-ROYAPURAM,57,1260000,"Providing truss work to coconut crushing hall in compost yard at Water basin road in Dn.57,U-13,Z-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/9635,Buildings,Completed,NE-ROYAPURAM,57,1280000,"Construction of coconut crushing hall in compost yard at water basin road in Dn.57,U-13,Z-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/9752,Buildings,Completed,NE-ROYAPURAM,57,2365000,"Repairs and Maintenance to the General work Shop flooring at Anna Pillai Street in division-57,Unit-13,Zone-5(Asset code:156/2692/778/2013-14)",Own Sources,5,2019-20,2020-21 Q/2019-20/11058,Buildings,Completed,Q-Solid Waste Management,57,4540000,"Construction of Shed for the installation and processing of Garden waste and tender Coconut shell at Anna Pillai Street (General Work Shop) in Division-57, Zone-5",Own Sources,5,2019-20,2020-21 Q/2019-20/11063,Buildings,Completed,Q-Solid Waste Management,57,1860000,"Providing Concrete pavement for installation ad processing of Garden Waste and Tender Coconut Shell at Anna pillai street in General work shop , Division-57, Zone-5",Own Sources,5,2019-20,2020-21 Q/2019-20/14002,Electrical,Completed,Q-Solid Waste Management,57,1470000,"Construction of Electrical Panel Room for garden garbage and tender coconut processing facility at General Work Shop in Dn-57, Zone-5",Own Sources,5,2019-20,2020-21 BR/2019-20/10018,Roads,Completed,BR-Bus Route Roads,58,110000,"Attending OFC Roadcut Restoration at Various locations (Perambur Barracks Road, Wallajah Salai, Maddocks Road, Vepery High Road ) in Zone-5. Deposit code - 57/1141/2018-19",Deposit Works,5,2019-20,2019-20 BR/2019-20/15806,Roads,Completed,BR-Bus Route Roads,58,1505000,"Partly relaying the road with BC after cold milling by paver finisher at EVK Sambath Road in Dn-58 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15809,Roads,Completed,BR-Bus Route Roads,58,903000,"Partly relaying the road with BC after cold milling by paver finisher at Vepery High Road in Dn-58 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15811,Roads,Completed,BR-Bus Route Roads,58,1505000,"Partly relaying the road with BC after cold milling by paver finisher at Thiru NarayanaGuru Salai in Dn-58 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15812,Roads,Completed,BR-Bus Route Roads,58,250000,"Partly relaying the road with BC after cold milling by paver finisher at Gangu Reddy Subway (From the JN of EVR Salai to Gangu Reddy Subway) in Dn-58 , Zone - 5",Grants,5,2019-20,2020-21 D/2019-20/8289,Storm Water Drain,Completed,D-Storm Water Drains,58,32966000,"Dismantling and Reconstruction of Storm Water Drain of size 1200 x 1200 mm along Sydenhams road on Eastern side from Vepery High road to Elephant Gate Bridge Road in Dn - 58, Unit - 14,Zone - V",Own Sources,5,2019-20,2020-21 D/2019-20/8290,Storm Water Drain,Completed,D-Storm Water Drains,58,13738000,"Dismantling and Reconstruction of Storm Water Drain of Size 1200 x 1200mm along Bakers street from Madox street to Sydenhams road in Dn - 58, Zone -V.",Own Sources,5,2019-20,2020-21 D/2019-20/8291,Storm Water Drain,Completed,D-Storm Water Drains,58,17849000,"Dismantling and Reconstruction of Storm Water Drain of Size 1200 x 1200mm along Hunters road from Gopala Menon street to Choolai High road in Dn - 58, Zone -V.",Own Sources,5,2019-20,2020-21 L/2019-20/10790,Electrical,Completed,L-Electrical,58,1799300,"Erection of 19 nos 8mtr post, replacement of 3 1/2X25sq.mm Cable 1128 mtrs at Narayana Guru Salai(Hunter Road), Division-58, Zone-5.",Own Sources,5,2019-20,2020-21 L/2019-20/2607,Electrical,Completed,L-Electrical,58,538300,"Erection of 4 nos no value 9mtr post and replacement of 266mtrs 3 1/2X25sq.mm alu cable at Whannals Road(Egmore Suburban Railway Station) and EVR Salai, in Division-58, laying 65mtrs 3 1/2X120sq.mm service cable from TNEB Pillar to GCC Streelight Pillar at Pantheon Road in Division-61 and erection of 3 nos no value 7mtr post and replacement of 473mtrs 2x25sq.mm alu cable at S.M.Nagar Main road in Division-59, Zone-5",Own Sources,5,2019-20,2019-20 L/2019-20/4672,Electrical,Completed,L-Electrical,58,523500,"Electrification work in Revenue office department at Revenue building second floor eastern side in Ripon building premises in Division-58,Zone-5",Own Sources,5,2019-20,2020-21 L/2019-20/4735,Electrical,Completed,L-Electrical,58,198700,Supply and errection of 2 nos of 9.5 MTR Lamp Post with Triplr arch bracket & 1 nos of 9.5 MTR Lamp Post with double arch bracket and 99 mtrs of 3 1/2 * 25 SQMM Alumininum Cable in Sydems Road & Choolai 58 in Zone - 5,Own Sources,5,2019-20,2019-20 L/2019-20/5526,Electrical,Completed,L-Electrical,58,177900,"Electrification work at Revenue building third floor east side vigillance officer office,PRO office in Golden Jublee building and Record section in ACC building in Ripon building premises in Division-58,Zone-5",Own Sources,5,2019-20,2020-21 L/2019-20/8966,Electrical,Completed,L-Electrical,58,195100,"Erection of 2 nos no value 7mtr post, replacement of 4cX16 Cable 344mtrs in the Cable Fault Span and Shifting of 1 no Kiosk Pillar Box at A.P.Road and Narayana Guru Salai, Division-58, Zone-5.",Own Sources,5,2019-20,2020-21 L/2019-20/9232,Electrical,Completed,L-Electrical,58,414200,"PROVISION OF LAYING NEW CABLE FOR CONNECTING SOLAR ROOF TOPS 3 PHASE SUPPLY TO MV PANEL IN AMMA MAALIGAI, RIPON BUILDING PREMISES IN DIV 58, ZONE 5",Own Sources,5,2019-20,2020-21 NE/2019-20/0224,Parks,Completed,NE-ROYAPURAM,58,31000,"Construction of Mulch pit with Bamboo barrier for compost unit at Thirumalai Park in Div-58, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/0598,Roads,Completed,NE-ROYAPURAM,58,3351000,"RELAYING OF BT ROAD AT AVADHANAM PAPIER ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2019-20,2019-20 NE/2019-20/10055,Buildings,Completed,NE-ROYAPURAM,58,2900000,"IMPROVEMENTS TO THE COURT HALL AT ALLIKULLAM SHOPPING COMPLEX IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/10732,Buildings,Completed,NE-ROYAPURAM,58,935000,"Construction of New MCC at EVK Sampath Salai in Div-58, Unit-14, Zone-5.",Swacch Bharat Mission,5,2019-20,2020-21 NE/2019-20/1183,Buildings,Completed,NE-ROYAPURAM,58,301000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT CATTLE DEPOT, VEERABADHRAN STREET IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2019-20,2019-20 NE/2019-20/1184,Buildings,Completed,NE-ROYAPURAM,58,301000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT SOUTH COOVAM RIVER ROAD IN DIVISION-63, UNIT-14, ZONE-V",Own Sources,5,2019-20,2019-20 NE/2019-20/11860,Roads,Completed,NE-ROYAPURAM,58,3600000,"RELAYING OF BT ROAD AT RITHERDON ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/11861,Roads,Completed,NE-ROYAPURAM,58,3614000,"RELAYING OF BT ROAD AT AVADHANAM PAPPAIYER ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/11863,Roads,Completed,NE-ROYAPURAM,58,1438000,"RELAYING OF BT ROAD AT MADDOX STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/11864,Roads,Completed,NE-ROYAPURAM,58,575000,"RELAYING OF BT ROAD AT GENERAL COLLINS ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/11865,Roads,Completed,NE-ROYAPURAM,58,1320000,"RELAYING OF CC ROAD AT CUDUPPAH RANGAIAH STREET IN DIVISION-58, UNIT-14, ZONE-V.",Own Sources,5,2019-20,2020-21 NE/2019-20/11872,Roads,Completed,NE-ROYAPURAM,58,3218000,"RELAYING OF CC ROAD AT NAVAL HOSPITAL 1 TO 13 LANES IN DIV-58, UNIT-14, ZONE-5",Own Sources,5,2019-20,2020-21 NE/2019-20/1273,Buildings,Completed,NE-ROYAPURAM,58,394000,"Providing Well Ring Mulch Pit at Various Street in Division-58, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/14018,Footpath,Completed,NE-ROYAPURAM,58,650000,"Improvements to the existing footpath near Raghavendra Park at Avadhanam Pappier Road in Dn-58, Unit-14, Zone-V",Own Sources,5,2019-20,2021-22 NE/2019-20/2920,Buildings,Completed,NE-ROYAPURAM,58,195000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT NO. 3, AVADHANA PAPPIER ROAD IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/2926,Buildings,Completed,NE-ROYAPURAM,58,35000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT V.K. PILLAI STREET IN DIVISION-58, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/4154,Buildings,Completed,NE-ROYAPURAM,58,382000,"Construction of Front side compound wall in TPF at basin elphant bridge road in Division-58,Unit-14,Zone-05.",Own Sources,5,2019-20,2019-20 NE/2019-20/4446,Playfields,Completed,NE-ROYAPURAM,58,239000,"Repairs and Maintenance to Iyyappa playground at Narayana Guru salai in Div-58,Unit-14,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5120,Buildings,Completed,NE-ROYAPURAM,58,499000,"Repairs and improvements to Community Hall at Naval Hospital Road in Div-58, Unit-14, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/5163,Buildings,Completed,NE-ROYAPURAM,58,118000,"REPAIR AND IMPROVEMET TO CHENNAI PRIMARY SCHOOL AT DOOR NO-3 A.P ROAD,IN DN-58, U-14, Z-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5525,Buildings,Completed,NE-ROYAPURAM,58,939000,"Improvements to the existing Gym building at Iyyappa playground in Div-58,Unit-14,Zone-5.",Own Sources,5,2019-20,2021-22 NE/2019-20/5562,Buildings,Completed,NE-ROYAPURAM,58,861000,"REPAIRS AND MAINTENANCE TO AMMA UNNAVAGAM AT KALATHIAPPA STREEET IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5623,Buildings,Completed,NE-ROYAPURAM,58,135000,"IMPROVEMENT TO PC AT NAVAL HOSPITAL ROAD IN DN-58, U-14, Z-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5799,Buildings,Completed,NE-ROYAPURAM,58,36000,"IMPROVEMENT TO PIPE LINE WORK AT SWAMI PILLAI STREET IN DN-58, U-14, Z-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5800,Buildings,Completed,NE-ROYAPURAM,58,116000,"IMPROVEMENT TO FOOTPATH AT NEAR RIBBON BUILDING MORE MARKET IN DN-58, U-14, Z-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5802,Buildings,Completed,NE-ROYAPURAM,58,110000,"IMPROVEMENT TO PC AT DHIDIR NAGAR KANNAPPAR THIDAL IN DN-58, U-14, Z-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5804,Buildings,Completed,NE-ROYAPURAM,58,1140000,"IMPROVEMENTS TO THE DISPENSARY (NUHM) BALANAIDU,AT ROTLER STREET, CHOOLAI IN DIVISION-58, UNIT-14, ZONE-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/5820,Buildings,Completed,NE-ROYAPURAM,58,998000,"Urgent Repairs and maintainance work at Allikullam Court Hall in Div-58,Unit-14,Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/5821,Buildings,Completed,NE-ROYAPURAM,58,2990000,"Proposed construction of Compost Yard at Kannappar Thidal (Near CMWSSB Filling point) in Division-58, Unit-14, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/6174,Storm Water Drain,Completed,NE-ROYAPURAM,58,863041,"Desilting of Existing Storm Water Drain at Sydenhams road (east side and west side ), Vepery high road (north side and south side), People parks road, Rottikindangu thiruvengadam street in Div-58, Unit-14,Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6185,Storm Water Drain,Completed,NE-ROYAPURAM,58,909000,"Desilting of Existing Storm Water Drain at Venkatachalam street, Nellu jalladai street, Samy pillai street, Allikulam Link road, vadamalai street, Thirunarayana guru salai. Avathana pappier road, Kalathiyappa street, Rotler street, Dharmaraja koil street, EVK sampath salai, Dr. Alagappa road, Jothy vemkatachalam salai,Thiruvengadam street, Veerasamy street, Valliammal road, Naval hospital road, Barracks road, Stringers street in Dn-58, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6194,Storm Water Drain,Completed,NE-ROYAPURAM,58,812000,"Improvements to Existing Storm Water Drain at Sydenhams Road (w), Vepery high Road (n), R.t. (m) Street, Arani Muthu Street, Samy Pillai Street, E.V.K.Sampath salai, Jothy Venkatachalam salai in Dn-58, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6201,Storm Water Drain,Completed,NE-ROYAPURAM,58,216000,"Replacing of Manhole doors at Venkatachalam street, Samy pillai street, Allikulam Link road, Thirunarayana guru salai. Avathana pappier road, Kalathiyappa street, Rotler street, EVK sampath salai, Jothy vemkatachalam street, Veerasamy street, Valliammal road, Naval hospital road Dn-58, Unit-14, Zone-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6759,Buildings,Completed,NE-ROYAPURAM,58,415000,"Proposed construction of Material Recovery Facility at Stringers Street ( Jn. of Naval Hospital Road) in Div-58, Unit-14, Zone-5.",Swacch Bharat Mission,5,2019-20,2020-21 NE/2019-20/7178,Buildings,Completed,NE-ROYAPURAM,58,2270000,"Construction of Toilet block and providing tiles and painting works at CGHS School, Rottler street in Division-58, Unit-14, Zone-5.",MLACDS,5,2019-20,2020-21 NE/2019-20/8899,Buildings,Completed,NE-ROYAPURAM,58,2800000,"CONSTRUCTION OF SECURITY ROOM AND TOILET PROVIDING, BORE WELL, WATER SUPPLY ARRANGEMENTS, LAYING FOOTPATH TILES MUSICAL SYSTEM PARK IN RAGAVENDRA PARK AT AVADHANAM PAPPIER ROAD IN DIV-58, UNIT-14,ZONE-5",MLACDS,5,2019-20,2020-21 NE/2019-20/9127,Buildings,Completed,NE-ROYAPURAM,58,850000,"Improvements to the existing toilet area and Providing additional facilities at allikullam court hall in Div-58,unit-14,zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/9566,Buildings,Completed,NE-ROYAPURAM,58,2237000,"Improvements to the MLA office at Periyar EVR Salai in Div-58, Unit-14, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/9984,Parks,Completed,NE-ROYAPURAM,58,2489000,"Formation of Shuttle Court, Greenery, CC TV camera and Pubble walk In RAGAVENDRA PARK AT AVADHANAM PAPPIER ROAD IN DIV-58, UNIT-14, ZONE-V",MLACDS,5,2019-20,2020-21 BR/2019-20/10886,Road Cut,Completed,BR-Bus Route Roads,59,531000,"Attendinf OFC Roadcut Restoration in various location (Basin Bridge Road, Gandhi irwin Bridge Road ) in Zone-V. Deposit code - 57/1145/2018-19.",Deposit-Asset,5,2019-20,2019-20 BR/2019-20/14215,Roads,Completed,BR-Bus Route Roads,59,198000,Repairs and Rectification of damaged 2 Modern Stainless Steel Bus Shleters at Dams Roads in Zone -5 Div-59.,Own Sources,5,2019-20,2020-21 BR/2019-20/14222,Roads,Completed,BR-Bus Route Roads,59,198000,Repairs and Rectification of damaged 2 Modern Stainless Steel Bus Shleters at Dams Roads in Zone -5 Div-59.,Own Sources,5,2019-20,2020-21 BR/2019-20/15799,Roads,Completed,BR-Bus Route Roads,59,1003000,"Partly relaying the road with BC after cold milling by paver finisher at NSC Bose Road in Dn-59 & 60 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15810,Roads,Completed,BR-Bus Route Roads,59,753000,"Partly relaying the road with BC after cold milling by paver finisher at Swami Sivanandha Salai in Dn-59 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/17709,Roads,Completed,BR-Bus Route Roads,59,960000,"Attending Emergency patch work at Broadway Bus Terminus (East side) in Dn-59 , Zone-5",Own Sources,5,2019-20,2020-21 BR/2019-20/17710,Roads,Completed,BR-Bus Route Roads,59,965000,"Attending Emergency patch work at Broadway Bus Terminus (East side) in Dn-59 , Zone-5",Own Sources,5,2019-20,2020-21 BR/2019-20/17711,Roads,Completed,BR-Bus Route Roads,59,980000,"Attending Emergency patch work at Broadway Bus Terminus (South side) in Dn-59 , Zone-5",Own Sources,5,2019-20,2020-21 BR/2019-20/17712,Roads,Completed,BR-Bus Route Roads,59,770000,"Attending Emergency patch work at Broadway Bus Terminus (South side) in Dn-59 , Zone-5",Own Sources,5,2019-20,2020-21 BR/2019-20/5533,Roads,Completed,BR-Bus Route Roads,59,200000,"Repairs to the existing Modern Stainless Steel Bus Shelters at various locations - Pallavan Salai, Adithanar Salai (Harris towers) , Anna Salai (Multispeciality Hospital), Basin bridge road (Mint Bus Terminu) in Zone- 5.",Own Sources,5,2019-20,2020-21 L/2019-20/10752,Electrical,Completed,L-Electrical,59,1470700,Proposal For 15 nos of 7mtr lamp post with single arch bracket & 1 nos of 8mtr Octoganal post with Double Straight bracket along with 1971 mtr of 3 1/2*25 sqmm Alu Cable at TNPSC Road &Wall Tax road Division-59 in Zone-05.,Own Sources,5,2019-20,2020-21 L/2019-20/7156,Electrical,Completed,L-Electrical,59,997200,"PROPOSAL OF 18NOS.OF 9.5MTR GI LAMPPOST WITH SINGLE ARCH RACKET AND 630 MTRS OF 3 1/2*25SQ/MM PVC ALU CABLE AT MULTISPECIALIST HOSPITAL SIDE,ANNASALAI DIV-59 ZONE-5",Own Sources,5,2019-20,2020-21 L/2019-20/7160,Electrical,Completed,L-Electrical,59,975700,"PROPOSAL OF 18NOS.OF 9.5MTR GI LAMPPOST WITH SINGLE ARCH BRACKET AND 600 MTRS OF 3 1/2*25SQ/MM PVC ALU CABLE AT PRR SONS SIDE,ANNASALAI DIV-59 ZONE-5",Own Sources,5,2019-20,2020-21 NE/2019-20/11856,Roads,Completed,NE-ROYAPURAM,59,1052000,"Relaying of BT Road At Mint Street (Part) In Division-59, Unit-14, Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/11858,Roads,Completed,NE-ROYAPURAM,59,1070000,"Relaying of BT Road at Ponnappa (C) Street in Division-59, Unit-14, Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/1260,Buildings,Completed,NE-ROYAPURAM,59,394000,"Providing Well Ring Mulch Pit at Various Street in Division-59, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2446,Buildings,Completed,NE-ROYAPURAM,59,199000,"Repairs and Improvement to ICDS ( Center No. 33603030327) at TNPSC Road in Dn - 59, Unit - 14, Zone - 5",Own Sources,5,2019-20,2019-20 NE/2019-20/2929,Buildings,Completed,NE-ROYAPURAM,59,195000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT NO. 246, MINT STREET IN DIVISION-59, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/2930,Buildings,Completed,NE-ROYAPURAM,59,195000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT ELLISPURAM IN DIVISION-59, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/2934,Buildings,Completed,NE-ROYAPURAM,59,160000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI PRIMARY SCHOOL AT SAIVA MUTHAIAH S.M. NAGAR IN DIVISION-59, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/4644,Buildings,Completed,NE-ROYAPURAM,59,214000,"Repairs and Improvements of Compound wall at SM Nagar PC in Div - 59, Unit - 14, Zone V.",Own Sources,5,2019-20,2019-20 NE/2019-20/5937,Buildings,Completed,NE-ROYAPURAM,59,415000,"Proposed construction of Material Recovery Facility at Muthusamy Salai in Div-59, Unit-14, Zone-5.",Swacch Bharat Mission,5,2019-20,2020-21 NE/2019-20/6173,Storm Water Drain,Completed,NE-ROYAPURAM,59,554000,"Desilting of Existing Storm Water Drain at Memorial hall Street, Rattan bazzar Road, Nsc bose Road, Narayanappa Road, Broadway bus Streetand (inside), Evening Bazar Road, Nyniappa (N) Street and Kellys drain in Dn-59, Unit - 14, Zone - 5.",Own Sources,5,2019-20,2020-21 NE/2019-20/6175,Storm Water Drain,Completed,NE-ROYAPURAM,59,923000,"Improvements to Existing Storm Water Drain at Wallajah Road, Mukthurinnsa Begam Vth Lane, Mukthurinnsa Begam VIth Lane, Owlia Sahib VIth Lane, Owlia Sahib IVth Lane, Tippu Sahib Street, Bangaru (N) Street, Ellis Road, Sathyavani Muthu Nagar, Memorial hall Street, Rattan bazzar Road, Nsc bose Road, Narayanappa Road and Nyniappa (N) Street in Dn-59, Unit - 14, Zone - 5.",Own Sources,5,2019-20,2020-21 NE/2019-20/6176,Storm Water Drain,Completed,NE-ROYAPURAM,59,180000,"Replacing of Manhole Door at Wallajah Road, Mukthurinnsa Begam Vth Lane, Mukthurinnsa Begam VIth Lane, Owlia Sahib VIth Lane, Owlia Sahib IVth Lane, Tippu Sahib Street, Bangaru (N) Street, Ellis Road, Sathyavani Muthu Nagar, Memorial hall Street, Rattan bazzar Road, Nsc bose Road, Narayanappa Road and Nyniappa (N) Street in Dn-59, Unit - 14, Zone - 5.",Own Sources,5,2019-20,2019-20 NE/2019-20/6301,Storm Water Drain,Completed,NE-ROYAPURAM,59,528000,"Desilting of Existing Storm Water Drain at Wallajah Road, Mukthurinnsa Begam Vth Lane, Mukthurinnsa Begam VIth Lane, Owlia Sahib VIth Lane, Owlia Sahib IVth Lane, Tippu Sahib Street, Bangaru (N) Street, Ellis Road and Sathyavani Muthu Nagar in Dn-59, Unit - 14, Zone - 5",Own Sources,5,2019-20,2019-20 NE/2019-20/7425,Buildings,Completed,NE-ROYAPURAM,59,864000,"Proposed Construction of Multipurpose Hall (Under MLA Fund) at Rattan bazaar road in in Division-59, Unit-14, Zone-V.",MLACDS,5,2019-20,2020-21 NE/2019-20/7893,Buildings,Completed,NE-ROYAPURAM,59,849000,"Repairs and Maintenance to amma unavagam inside of rajiv gandhi hospital at poonnamalle high road in div-59, unit-14, zone-05",Own Sources,5,2019-20,2020-21 NE/2019-20/8468,Buildings,Completed,NE-ROYAPURAM,59,2920525,"Proposed Construction Of Public Convenience (Under MP Fund) at VOC Salai in Dn - 59, Unit - 14, Zone - 5.",MPLADS,5,2019-20,2020-21 NE/2019-20/8469,Buildings,Completed,NE-ROYAPURAM,59,141000,"Repairs and Improvements to Public Convenience at SM Nagar in Div - 59, Unit - 14, Zone V",Own Sources,5,2019-20,2020-21 NE/2019-20/8470,Buildings,Completed,NE-ROYAPURAM,59,82000,"Improvements to Public Convenience Drainage Line at SM Nagar in Div - 59, Unit - 14, Zone V",Own Sources,5,2019-20,2019-20 NE/2019-20/8471,Roads,Completed,NE-ROYAPURAM,59,77000,"Repairs and Improvements to Storm Water Drain at NCS Bose Road in Div - 59, Unit - 14, Zone V",Own Sources,5,2019-20,2019-20 NE/2019-20/9231,Buildings,Completed,NE-ROYAPURAM,59,2896026,"Construction of Multipurpose Hall (under MP Fund) at NSC Bose at Dn-59, Unit-14, Zone-V",MPLADS,5,2019-20,2020-21 BR/2019-20/10873,Footpath,Completed,BR-Bus Route Roads,60,530000,"Removing existing footpath and providing Parking entry provision for vehicle parking Area (opposite to Secreteriat building ) at Rajaji salai in Dn. 60, Zone -5",Own Sources,5,2019-20,2020-21 BR/2019-20/10907,Road Cut,Completed,BR-Bus Route Roads,60,164000,Attending OFC Roadcut Restoration at various location (Prakasam Road) in Zone - V. Deposit Code - 57/1143/2018-19.,Deposit-Asset,5,2019-20,2019-20 BR/2019-20/1130,Footpath,Completed,BR-Bus Route Roads,60,9680000,"Improvements / Providing and paving with Granite footpath along with railing of SS pipe and Granite pedestal stones to the existing footpath in Rajaji salai (Dn-60, Zone-5) Reach flag staff road to secretariat building",Grants,5,2019-20,2019-20 BR/2019-20/15800,Roads,Completed,BR-Bus Route Roads,60,1003000,"Partly relaying the road with BC after cold milling by paver finisher at Kamarajar Salai in Dn-60 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15807,Roads,Completed,BR-Bus Route Roads,60,2508000,"Partly relaying the road with BC after cold milling by paver finisher at Rajaji Salai in Dn-60 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15813,Roads,Completed,BR-Bus Route Roads,60,301000,"Partly relaying the road with BC after cold milling by paver finisher at Ibrahimji Road in Dn-60 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/4867,Roads,Completed,BR-Bus Route Roads,60,700000,"ATTENDING PATCHES & PROVIDING SPEED BREAKERS AT VARIOUS LOCATIONS - General Patters Road, Broadway Bus Stand, Mayor Kabalamoorthy Salai,Arunachalam St, Raja Muthiah Salai, NRT Road & Adhithanar Salai in DN.52,58,59,60,61,62 & 63 , Zone - 5",Own Sources,5,2019-20,2020-21 BR/2019-20/7990,Roads,Completed,BR-Bus Route Roads,60,625000,"ATTENDING PATCHES AT VARIOUS LOCATIONS IN Old Jail Road, Rajaji Salai, in DN. 61 & 60 , Zone - 5",Own Sources,5,2019-20,2019-20 BR/2019-20/8004,Roads,Completed,BR-Bus Route Roads,60,930000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shelters at Rajaji Salai, Santhome High Road, Kamaraj Salai, DGS Dinakaran Salai, Sardar Patel Road, Taluk Office Road in Zone-5,9 &13",Own Sources,5,2019-20,2020-21 BR/2019-20/9548,Roads,Completed,BR-Bus Route Roads,60,935000,"APPLYING OF THERMOPLASTIC PAINTING AT VARIOUS LOCATIONS IN RAJAJI SALAI & KAMARAJAR SALAI in DN. 60 , Zone - 5",Own Sources,5,2019-20,2020-21 BR/2019-20/9927,Roads,Completed,BR-Bus Route Roads,60,199000,"Removing and Re-fixing of 1 no of modern Bus shelter at RAJAJI SALAI (Opp. to Secreteriat Building) in Dn.60, Zone - 5.",Own Sources,5,2019-20,2020-21 L/2019-20/5043,Electrical,Completed,L-Electrical,60,138700,"Painting and Numbering of 403 nos of Lamp posts at Kamarajar Salai, Secreteriate park, North fort road and Flag staff Road, Muthu samy Bridge, Muthu samai salai and EVR salai in Div - 60 in zone- 5.",Own Sources,5,2019-20,2019-20 L/2019-20/5045,Electrical,Completed,L-Electrical,60,171900,Removal of 58 nos of 9.5 Mtrs old MS Lamp posts at Rajaji Salai and Mannady Street in Div - 60 in Zone - 5.,Own Sources,5,2019-20,2019-20 L/2019-20/5062,Electrical,Completed,L-Electrical,60,2230700,Removal of 22 nos of 8 mtrs GI lamp posts and refixing of 17 nos of GI Lamp posts and Supply and erection of 5 no of GI Octogonal lamp posts at Kamarajar Salai from Secretariate Park to Napier Bridge East side and Supply and Errection of 2 nos of 8 mtrs GI Octogonal lamp posts with double bracket at War Memorial island and Replacing of damaged 1661 mtrs of 31/2 x 25 sqmm Alu cable at Kamarajar Salai in Div - 60 in Zone - 5.,Own Sources,5,2019-20,2020-21 NE/2019-20/0209,Parks,Completed,NE-ROYAPURAM,60,14000,"Installation of Munch Pit With Necessary Arrangement of Bamboo Sticks in Secreatariat park in Rajaji Salai at Dn.60, Unit-13, Zone-05 (Asset - 013/2646/508/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/0215,Buildings,Completed,NE-ROYAPURAM,60,14000,"Construction of Munch Pit With Necessary Arrangement of Bamboo Sticks in Annai Sathiya Nagar Park in Rajaji Salai At dn.60, Unit-13, Zone -05 ( Asset - 033/2646/503/2013-14 )",Own Sources,5,2019-20,2019-20 NE/2019-20/0433,Roads,Completed,NE-ROYAPURAM,60,2850000,"Relaying Road work in Navi House Road at Dn.60, Unit--13, Zone-05 (Asset - R/2627/6969/2014-15)",Own Sources,5,2019-20,2019-20 NE/2019-20/10338,Footpath,Completed,BR-Bus Route Roads,60,1500000,"IMPROVEMENTS TO FOOTPATH AT N.S.C.BOSE ROAD (FROM PARRYS CORNER TO PRAKASAM SALAI JUNCTION) IN DIVISION-60, UNIT-13, ZONE-5.",Own Sources,5,2019-20,2021-22 NE/2019-20/10569,Roads,Completed,NE-ROYAPURAM,60,990000,"Planting of Plants in centermedian at Kamarajar salai,Rajaji salai,North fort side road,in Dn.60,U-13,Z-05.(Asset Code:043/2646/1098/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/10974,Footpath,Completed,NE-ROYAPURAM,60,1975000,"Painting work to Footpath Kerbs at Rajaji Salai, Kamaraj Salai, Flag Staff House Road, NSC Bose Road, North Fort Side Road and Ibrahim Sahib Street in Div-60, Unit-13, Zone-5. (For Republic Day Celebration).",Own Sources,5,2019-20,2021-22 NE/2019-20/10978,Roads,Completed,NE-ROYAPURAM,60,515000,"Face lift (S/F of RR Studs and Delineaters) to Rajaji Salai and North Fort Side Road in Division -60, Unit-13, Zone-5 (Republic Day Celebration).",Own Sources,5,2019-20,2020-21 NE/2019-20/14213,Roads,Completed,NE-ROYAPURAM,60,879000,"ATTENDING PATCH WORK TO CC ROAD AT METTU STREET IN DIVISION-60, UNIT-13, ZONE-05.(044/2588/16541/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/14216,Roads,Completed,NE-ROYAPURAM,60,208000,"ATTENDING PATCH WORK TO CC ROAD AT ERRABALU CHETTY STREET IN DIVISION-60, UNIT-13, ZONE-05. ( 044/2642/16530/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/1794,Buildings,Completed,NE-ROYAPURAM,60,84000,"Providing Well RIngs Mulch Pit at High Court Campass & NRT Brige Park in Ward-60,Unit-13,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/1808,Buildings,Completed,NE-ROYAPURAM,60,84000,"Providing Well RIngs Mulch Pit at Screatariat Park & Screatariat Car Parking in Ward-60,Unit-13,Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2027,Buildings,Completed,NE-ROYAPURAM,60,28100,"Providing Sintex Tank for composing Secretariat Park in Rajaji Saalai at Dn.60, Unit-13, Zone-5 (Asset- 013/2646/508/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/2961,Roads,Completed,NE-ROYAPURAM,60,2000000,"Laying C.C Road at Annai Sathiya Nagar ( North ) B Block Streets Dn.60, Unit-13, Zone-05 (Asset-043/2646/534/2013-14)",MLACDS,5,2019-20,2020-21 NE/2019-20/2967,Roads,Completed,NE-ROYAPURAM,60,2800000,"Laying Cement Concrete Road at Annai Sathiya Nagar (South) C Block Streets Dn.60, Unit-13, Zone-05",MLACDS,5,2019-20,2020-21 NE/2019-20/4092,Footpath,Completed,NE-ROYAPURAM,60,179000,"REPAIR WORKS TO FOOTPATH AT RAJAJI SALAI, FLAG STAFF HOUSE ROAD, NSC BOSE ROAD AND NORTH FORT SIDE ROAD IN DN.60, UNIT-11, ZONE-5 [ASSET CODE- 053/2646/1951/2013-14, 053/2664/1949/2013-14, 053/2632/1950/2013-14, 053/2663/1952/2013-14]",Own Sources,5,2019-20,2020-21 NE/2019-20/4184,Buildings,Completed,NE-ROYAPURAM,60,270000,"Repair and Maintenance Work Public Convenience N S C Bose Road At Dn.60, Unit.13,Zone-05 (Asset - 033/2632/504/2013-14)",Own Sources,5,2019-20,2020-21 NE/2019-20/6265,Buildings,Completed,NE-ROYAPURAM,60,520000,"Minor Repair works to SWD at Ibrahim Sahib Street (Southern Side), Varadarajan Street , Jeffar Sarang Street, Moore Street, Jeffar Sarang Lane, Mookar Nallamuthu Street, Post Office Street, Rajaji Salai East, Rajaji Salai West, Kamarajar Salai, Flag Staff House Road, North Ford Side Road, N S C Bose Road, Light House Road, Sembudoss Street, Jhones Lane, Angappa Street, Manady Street, Arbut Not Lane in Dn.60, Unit-13, Zone-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/6267,Storm Water Drain,Completed,NE-ROYAPURAM,60,288000,"Replacing of Manhole doors at Ibrahim Sahib Street (Southern Side), Varadarajan Street , Jeffar Sarang Street, Moore Street, Jeffar Sarang Lane, Mookar Nallamuthu Street, Post Office Street, Rajaji Salai East, Rajaji Salai West, Kamarajar Salai, Flag Staff House Road, North Ford Side Road, N S C Bose Road, Light House Road, Sembudoss Street, Jhones Lane, Angappa Street, Manady Street, Arbut Not Lane in Dn.60, Unit-13, Zone-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/6268,Storm Water Drain,Completed,NE-ROYAPURAM,60,700000,"Desilting of existing SWD at brahim Sahib Street (Southern Side), Varadarajan Street , Jeffar Sarang Street, Moore Street, Jeffar Sarang Lane, Mookar Nallamuthu Street, Post Office Street, Light House Road in Dn.60, Unit-13, Zone-05.(Asset-055/2580/4826/2013-14, 055/2613/4830/2013-14, 055/2615/4827/2013-14, 055/2578/4828/2013-14, 055/2599/4829/2013-14, 055/2587/6856/2014-15, 055/2653/7534/2014-15, 055/15609/4833/2013-14)",Own Sources,5,2019-20,2019-20 NE/2019-20/6305,Storm Water Drain,Completed,NE-ROYAPURAM,60,701000,"Desilting of existing SWD at Rajaji Salai East, Rajaji Salai West, Kamarajar Salai, Flag Staff House Road, North Ford Side Road, N S C Bose Road, Sembudoss Street, Jhones Lane, Angappa Street, Manady Street, Arbut Not Lane in Dn.60, Unit-13, Zone-05.",Own Sources,5,2019-20,2019-20 NE/2019-20/6385,Buildings,Completed,NE-ROYAPURAM,60,3000000,"Construction of New Public convenience at Venkata Lingam 2nd lane at Dn-60, Unit-13, Zone-5 (Asset - 044/2614/16575/2013-14)",MLACDS,5,2019-20,2020-21 NE/2019-20/6389,Buildings,Completed,NE-ROYAPURAM,60,2800000,"Construction of New GYM Building at Venkata Lingam 2nd lane in Dn-60, Unit-13, Zone-05. (Asset-033/2614/1081/2015-16)",MLACDS,5,2019-20,2020-21 NE/2019-20/7131,Footpath,Completed,NE-ROYAPURAM,60,775000,"Providing Face Lift To Kamaraj Salai Approach Road to Navy House in Dn.60, Unit-13, Zone-5 (Asset--R/2627/6969/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/7159,Roads,Completed,NE-ROYAPURAM,60,950000,"Providing Fencing Workat Kamaraj Salai Approach Road (Bank Of Koovam Canal) to Navy House in Dn.60, Unit-13, Zone-5. Asset-R/2627/6969/2014-15)",Own Sources,5,2019-20,2020-21 NE/2019-20/7250,Buildings,Completed,NE-ROYAPURAM,60,2999951,"Construction of New Public convenience at Rajaji Salai (Near kandappa Street) at Dn-60, Unit-13, Zone-5 (Asset - 033/2646/499/2013-14)",MPLADS,5,2019-20,2020-21 NE/2019-20/7255,Buildings,Completed,NE-ROYAPURAM,60,193270,"Dismantling of the existing Toilet block at venkata lingam 2nd Lane in Dn.60, unit-13, Zone-05",Own Sources,5,2019-20,2020-21 NE/2019-20/7257,Buildings,Completed,NE-ROYAPURAM,60,83000,"Dismantling of the existing Toilet block at Rajaji Salai (Near Kandappa Street Corner) in Dn.60, unit-13, Zone-05",Own Sources,5,2019-20,2020-21 NE/2019-20/8176,Buildings,Completed,NE-ROYAPURAM,60,800000,"SUPPLY, DELIVERY, INSTALLATION AND COMMISSIONING OF BIO- DIGESTER TO ISLAND GROUND IN DIVISION-60, UNIT-13, ZONE-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/8649,Buildings,Completed,NE-ROYAPURAM,60,2410000,"SUPPLY, DELIVERY, INSTALLATION AND COMMISSIONING OF BIO- DIGESTER TO ANNAI SATHYA NAGAR PUBLIC CONVENIANCE IN DIVISION-60, UNIT-13, ZONE-5.",Own Sources,5,2019-20,2020-21 BR/2019-20/10875,Road Cut,Completed,BR-Bus Route Roads,61,109000,"Attending OFC Roadcut Restoration at various locations(Rukmani Lakshimipathy Salai, Sivanandha salai) in Zone-V. Deposit Code - 57/1139/2018-19.",Deposit-Asset,5,2019-20,2019-20 BR/2019-20/10879,Road Cut,Completed,BR-Bus Route Roads,61,174000,Attending OFC Roadcut Restoration at various location (Casamajor Road) in Zone-V. Deposit Code-57/1141/2018-19,Deposit-Asset,5,2019-20,2019-20 BR/2019-20/10909,Road Cut,Completed,BR-Bus Route Roads,61,283000,"Attending OFC Roadcut Restoration at various location (Pantheon Road, GP Road, Dams Road) in Zone - V. Deposit Code-57/1141/2018-19",Deposit Works,5,2019-20,2019-20 BR/2019-20/11642,Roads,Completed,BR-Bus Route Roads,61,535000,"Attending Patches at various locations in Ethiraj Road ( From Ethiraj College to Jn of Binny Road ) in Dn- 61, Zone-5.",Own Sources,5,2019-20,2020-21 BR/2019-20/11643,Roads,Completed,BR-Bus Route Roads,61,775000,"Attending Patches at various locations in Ethiraj Road including Centre Camber Correction course (Near Kanchi Hotel) in Dn-61, Zone -5.",Own Sources,5,2019-20,2020-21 BR/2019-20/15797,Roads,Completed,BR-Bus Route Roads,61,602000,"Partly relaying the road with BC after cold milling by paver finisher at Pantheon Road in Dn-61 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15801,Roads,Completed,BR-Bus Route Roads,61,753000,"Partly relaying the road with BC after cold milling by paver finisher at Gandhi Irwin Bridge Road in Dn-61 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15802,Roads,Completed,BR-Bus Route Roads,61,502000,"Partly relaying the road with BC after cold milling by paver finisher at Egmore High Road in Dn-61 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15803,Roads,Completed,BR-Bus Route Roads,61,1003000,"Partly relaying the road with BC after cold milling by paver finisher at Rukmani Lakshmipathy Salai in Dn-61 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15805,Roads,Completed,BR-Bus Route Roads,61,1756000,"Partly relaying the road with BC after cold milling by paver finisher at Ethiraj Salai in Dn-61 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/6291,Footpath,Completed,BR-Bus Route Roads,61,199000,"CARRIYING OUT MINOR REPAIR WORKS AT BLACKERS ROAD NEAR CASINO THEATRE AND WHANNELS ROAD JN OF PONNIYAMMAN KOIL STREET IN DN. 63 & 61, ZONE-05",Own Sources,5,2019-20,2020-21 BR/2019-20/8298,Road Cut,Completed,BR-Bus Route Roads,61,2340000,"ROAD CUT RESTORATION AT LANGS GARDEN ROAD (FROM Jn. OF AYYASAMY STREET TO Jn. OF ARUNACHALAM STREET) & GANDHI IRWIN BRIDGE ROAD IN DN. 61 & 63, IN Zone - 5, AGAINST CHALLAN NO-BR/2019-20/0018817",Deposit Works,5,2019-20,2020-21 BR/2019-20/8300,Road Cut,Completed,BR-Bus Route Roads,61,2490000,"Restoration of Roadcut made by TANTRANSCO at Raja Muthiah Salai in Dn. 58, Zone -5 Against challan No: BR/2019-20/0019890 and Reciept No: 09/2019-20/0505088",Deposit Works,5,2019-20,2020-21 L/2019-20/11135,Electrical,Completed,L-Electrical,61,1505900,"Erection of 15 nos no value 9mtr post, replacement of 3 1/2X25sq.mm Cable 1085mtrs in for replacement and Cable Fault Span and main supply cable 3 1/2X120sq.mm alu cable 60 mtrs from TNEB Pillar to GCC Street light Pillar at Gandhi Irvine Road and Athithanar Salai, Division-61, Zone-5.",Own Sources,5,2019-20,2020-21 L/2019-20/12848,Electrical,Completed,L-Electrical,61,496700,"Electrification work in Amma Unavagam at Gengu Reddy Road dn-61 and Whannals Road Dn-58, Zone-5.",Own Sources,5,2019-20,2021-22 L/2019-20/2060,Electrical,Completed,L-Electrical,61,461400,"Supply and fixing of 27 nos Timer Unit at various locations in Division-58 & 61, Zone-5.",Own Sources,5,2019-20,2019-20 L/2019-20/2414,Electrical,Completed,L-Electrical,61,537700,"Erection of 2 nos 9mtr novalue post and replacement of 871 mtr 3 1/2X25sqmm alu cable at Kennet lane, Patheon Road, Whannals road and Gandhi Irvine Road in Division-61, Zone-5",Own Sources,5,2019-20,2019-20 L/2019-20/4227,Electrical,Completed,L-Electrical,61,688200,"Replacement of 991mtrs 3 1/2 X25sq.mm Alu cable at Casa Major Road in Division-61, Zone-5",Own Sources,5,2019-20,2019-20 L/2019-20/4232,Electrical,Completed,L-Electrical,61,626800,"Replacement of 966mtrs 3 1/2 X25sq.mm Alu cable at Sait Colony 1st and 2nd Street in Division-61, Zone-5",Own Sources,5,2019-20,2019-20 L/2019-20/4233,Electrical,Completed,L-Electrical,61,657300,"Replacement of 970mtrs 3 1/2 X25sq.mm Alu cable at Halls Road in Division-61, Zone-5",Own Sources,5,2019-20,2019-20 L/2019-20/7436,Electrical,Completed,L-Electrical,61,146100,"Electrification work at Gengu Reddy Subway Motor Room 1 and 2 in Division-61, Zone-5.",Own Sources,5,2019-20,2020-21 L/2019-20/8788,Electrical,Completed,L-Electrical,61,1819000,"Replacement of 2680mtrs 2cX25sqmm alu cable and 1050mtrs 3 1/2 X25sq.mm Alu cable at Various Location in Division-58 & 61, Zone-5",Grants,5,2019-20,2020-21 NE/2019-20/0087,Roads,Completed,NE-ROYAPURAM,61,258000,"Repairs and improvements to the Amma unavagam at Pantheon road in Division-61,Unit-14,Zone-05.",Own Sources,5,2019-20,2019-20 NE/2019-20/0089,Roads,Completed,NE-ROYAPURAM,61,638000,"IMPROVEMENTS TO AMMA UNAVAGAM INSIDE OF CHILDREN'S HOSPITAL AT Halls Road (Tamil Salai ) IN DIV-61, U-14, ZO-05",Own Sources,5,2019-20,2019-20 NE/2019-20/0271,Parks,Completed,NE-ROYAPURAM,61,31000,"Construction of Mulch pit with Bamboo barrier for compost unit at Mayor Sundara Rao Park at Rukmani Lakshmipathy Salai in Div-61, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/0288,Parks,Completed,NE-ROYAPURAM,61,31000,"Construction of Mulch pit with Bamboo barrier for compost unit at Ethiraj Park at Ethiraj Lane in Div-61, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/1206,Buildings,Completed,NE-ROYAPURAM,61,503000,"Providing Well Ring Mulch Pit at Various Street in Division-61, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/12787,Roads,Completed,NE-ROYAPURAM,61,479000,"Relaying of BT Road at LNP Koil Street in Division-61, Unit-14, Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/12801,Roads,Completed,NE-ROYAPURAM,61,536000,"Relaying of BT Road at Chinna (R) Street in Division-61, Unit-14, Zone-5.",Own Sources,5,2019-20,2020-21 NE/2019-20/12987,Roads,Completed,NE-ROYAPURAM,61,800000,"Relaing the BT Road at Shiyali Street in Division-61, Unit-14, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/2901,Buildings,Completed,NE-ROYAPURAM,61,199000,"REPAIR AND IMPROVEMENT TO ICDS NO-112 AT PANTHEON ROAD IN DN-61, U-14, Z-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/2902,Buildings,Completed,NE-ROYAPURAM,61,150000,"REPAIR AND IMPROVEMENT TO ICDS NO-111 AT SANTHOSH NAGAR IN DN-61, U-14, Z-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/2903,Buildings,Completed,NE-ROYAPURAM,61,117000,"REPAIR AND IMPROVEMENT TO ICDS NO-110 AT SANTHOSE NAGAR IN DN-61, U-14, Z-5.",Own Sources,5,2019-20,2019-20 NE/2019-20/2911,Buildings,Completed,NE-ROYAPURAM,61,195000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI URDU SCHOOL AT LANGS GARDEN ROAD IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/2918,Buildings,Completed,NE-ROYAPURAM,61,35000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT VEERASAMY STREET IN DIVISION-61, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/4560,Buildings,Completed,NE-ROYAPURAM,61,339000,"Repair and Maintenance to Public Convenience at Gandhi irwin road in Division-61,Unit-14,Zone-05.",Own Sources,5,2019-20,2019-20 NE/2019-20/4630,Buildings,Completed,NE-ROYAPURAM,61,167000,"REPAIR AND MAINTENANCE WORK AT MAYOR SUNDARROA ROUNTANA IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2019-20 NE/2019-20/6249,Storm Water Drain,Completed,NE-ROYAPURAM,61,594000,"Desilting of Existing Storm Water Drain at Various Street (Egmore High road, Halls road, Casamajor road, Sait colony I street, Sait colony II street, P.C.O Road, Gandhi Irwin road, Whanels road, Pantheon road, Rangachari street, Gopalsamy Nagar (Gengu(R)Subway service road), Boopathy nagar(Gengu ( R ) Subway service road), Boopathy nagar, Ethiraj salai, Rukmani Lakshmipathy salai, Driver street, Velayutham street, Ayyasami road, Ethiraj lane, Montieth Lane, Montieth Road, Varatharajalu Street) in Division-61, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6261,Storm Water Drain,Completed,NE-ROYAPURAM,61,188000,"Replace of Manhole Doors at Various Street (Egmore High road, Halls road, Casamajor road, Sait colony I street, Sait colony II street, P.C.O Road, Gandhi Irwin road, Whanels road, Pantheon road, Rangachari street, Gopalsamy Nagar (Gengu(R)Subway service road), Boopathy nagar(Gengu ( R ) Subway service road), Boopathy nagar, Ethiraj salai, Rukmani Lakshmipathy salai, Driver street, Velayutham street, Ayyasami road, Ethiraj lane, Montieth Lane, Montieth Road, Varatharajalu Street) in Division-61, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6277,Storm Water Drain,Completed,NE-ROYAPURAM,61,1155000,"Improvements to Existing Storm Water Drain at at Various Street (Egmore High road, Halls road, Casamajor road, Sait colony I street, Sait colony II street, P.C.O Road, Gandhi Irwin road, Whanels road, Pantheon road, Rangachari street, Gopalsamy Nagar (Gengu(R)Subway service road), Boopathy nagar(Gengu ( R ) Subway service road), Boopathy nagar, Ethiraj salai, Rukmani Lakshmipathy salai, Driver street, Velayutham street, Ayyasami road, Ethiraj lane, Montieth Lane, Montieth Road, Varatharajalu Street) in Division-61, Unit-14, Zone-5",Own Sources,5,2019-20,2020-21 NE/2019-20/6400,Footpath,Completed,NE-ROYAPURAM,61,757000,"REPAIRS AND MAINTAINCE OF FOOTBALL GROUND AT RANGACHARI STREET IN DIVISION-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2020-21 NE/2019-20/6403,Footpath,Completed,NE-ROYAPURAM,61,466000,"REPAIRS AND MAINTAINCE OF BASKET BALL GROUND AT VENGU STREET IN DIVISION-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2020-21 NE/2019-20/6534,Roads,Completed,NE-ROYAPURAM,61,78000,"REPAIRS AND MAINTAINCE WORK AT CHENNAI MIDDLE SCHOOL AT PANTHEON ROAD AND THIRUVENGADAM STREET IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2019-20 NE/2019-20/6538,Footpath,Completed,NE-ROYAPURAM,61,71000,"REPAIRS AND MAINTAINCE WORK AT HALLS ROAD (TAMIL SALAI) NEAR AMBASSIDOR PALLAVA HOTEL IN DIV-61, UN-14, ZONE-05",Own Sources,5,2019-20,2019-20 NE/2019-20/6542,Roads,Completed,NE-ROYAPURAM,61,63000,"REPAIRS AND MAINTAINCE WORK AT PCO ROAD & P.V CHERIYAN ROAD IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2019-20 NE/2019-20/6543,Roads,Completed,NE-ROYAPURAM,61,61000,"REPAIRS AND MAINTAINCE WORK AT JERRAT GARDEN (CASA MAJOR LANE) & THIRUVENGADAM LANE IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2019-20 NE/2019-20/6544,Roads,Completed,NE-ROYAPURAM,61,59000,"REPAIRS AND MAINTAICE WORK AT AARAVAMUTHU GARDEN STREET & RANGACHARI STREET IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2019-20 NE/2019-20/7163,Culvert,Completed,NE-ROYAPURAM,61,1531000,"REPAIR AND IMPROVEMENTS TO GENDU REDDY SUBWAY MOTOR ROOM AT BOOPATHY NAGAR IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2019-20,2020-21 NE/2019-20/7976,Buildings,Completed,NE-ROYAPURAM,61,3000000,"Construction of New MCC at Ayyasamy Street in DN-61,U-14, Z-5.",Swacch Bharat Mission,5,2019-20,2020-21 NE/2019-20/9372,Buildings,Completed,NE-ROYAPURAM,61,1437000,"Repair and Maintenance to Chennai middle school at Varadharaja puram pantheon road Division-61,Unit-14,Zone-05.",Own Sources,5,2019-20,2021-22 L/2019-20/11432,Electrical,Completed,L-Electrical,62,1022700,"Supply and Erection of 14Nos.of 7Mtr GI Street Lamppost with Single Straight Bracket and 778Mtrs.of 2x25Sq.mm PVC ALU Cable at May Day Park Chindatripet in Div-62,Zone-5.",Own Sources,5,2019-20,2021-22 L/2019-20/8341,Electrical,Completed,L-Electrical,62,196700,"Electrification work at Singanna chetty street, General Medical store Chindatripet Div-62 Zone-5.",Own Sources,5,2019-20,2020-21 L/2019-20/8786,Electrical,Completed,L-Electrical,62,1588100,"Replacement of 2150 mtrs 2CX25sq.mm and 1075 mtrs 3 1/2 x25 sqmm Alu cable at Various Location in Div 59P, 62 and 63 in Zone-5 Anna Salai Section",Grants,5,2019-20,2020-21 NE/2019-20/10346,Buildings,Completed,NE-ROYAPURAM,62,1584000,"Construction of Proposed Collection hall in Resource Recovery center at Adhikesavalu street in Division-62,Unit-14,Zone-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/1100,Buildings,Completed,NE-ROYAPURAM,62,773000,"Constructions of Storm water drain at Singana chetty street and Guruvappa street four way junction in Division-62,Unit-14,Zone-05.",MLACDS,5,2019-20,2019-20 NE/2019-20/1248,Buildings,Completed,NE-ROYAPURAM,62,537000,"Providing Well Ring Mulch Pit at Various Street in Division-62, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/12962,Roads,Completed,NE-ROYAPURAM,62,636000,"RELAYING OF BT ROAD AT SUNGUWAR AGRAHARAM STREET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14210,Roads,Completed,NE-ROYAPURAM,62,561000,"Supply and Fixing Baling Machines at R.R.Center at Adikesavulu street, Chintadripet in Ward-62, Unit-14, Zone-5",Own Sources,5,2019-20,2021-22 NE/2019-20/2024,Parks,Completed,NE-ROYAPURAM,62,31000,"Construction of Mulch pit with Bamboo barrier for compost unit at May Day Park at arunachala Street in Div-62, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/2931,Buildings,Completed,NE-ROYAPURAM,62,355000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CMS, ADIKESAVULU STREET AT CHINTADRIPET IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/2938,Buildings,Completed,NE-ROYAPURAM,62,160000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI HIGH SCHOOL AT WEST COOVAM RIVER ROAD IN DIVISION-62, UNIT-14, ZONE-V",Own Sources,5,2019-20,2020-21 NE/2019-20/3378,Buildings,Completed,NE-ROYAPURAM,62,2965000,"Constructions of motor room providing bore well and water supply arrangement at West coovam road,South coovam road,Lord govindha nagar,Kaliman puram,veeran puram,Goyathoppu,Kari moideen street,lafond lane,Adhikesavalu street,litchi street in division 62,63 unit 14 ,zone-05",MLACDS,5,2019-20,2020-21 NE/2019-20/3427,Buildings,Completed,NE-ROYAPURAM,62,2978000,"Construction of Storm water drain at Arunachalam road Chintadripet in Front Indian Overseas Bank in Division-62,Unit-14,Zone-05.",MLACDS,5,2019-20,2019-20 NE/2019-20/4077,Buildings,Completed,NE-ROYAPURAM,62,33000,"Plumbing arrangements to division office at adhikesavalu street and electrical arrangements in pc at balakrishnan street in dn-62,unit-14,zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/4078,Storm Water Drain,Completed,NE-ROYAPURAM,62,56000,"Repairs and improvements to storm water drain at jothi ammal nagar and pumping station in dn-62,unit-14,zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/4081,Storm Water Drain,Completed,NE-ROYAPURAM,62,42500,"Providing Rain water Harvesting at balakrishnan street in dn-62,unit-14,zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/5147,Buildings,Completed,NE-ROYAPURAM,62,381000,"REPAIRS WORKS TO AMMA UNAVAGAM AT WEST COOVAM RIVER ROAD IN DN-62,UNIT-14,ZONE-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6199,Storm Water Drain,Completed,NE-ROYAPURAM,62,461000,"Improvements to Existing Storm Water Drain at Samy Pandaram Street ( Kalavai Street ), Lafond street, New Balakrishnan Street, Venkatesan Street, Wallers Road, Sami (N) Street, Balakrishnan Street, Pumping station road, Singanna street,Bazzar street, Dy. Mayor Kabala Moorthy Salai, Arunachalam main Road in DN-62,Unit-14,Zone-05",Own Sources,5,2019-20,2020-21 NE/2019-20/6203,Storm Water Drain,Completed,NE-ROYAPURAM,62,144000,"Replacing of Man Hole Door at Samy Pandaram Street ( Kalavai Street ), Lafond street, New Balakrishnan Street, Venkatesan Street, Wallers Road, Sami (N) Street, Balakrishnan Street, Pumping station road, Singanna street,Bazzar street, Dy. Mayor Kabala Moorthy Salai, Arunachalam main Road, Koovur Vaithianathan Street, Ulagappa (m ) Street , Iyya ( M ) Street, South Padavattamman Koil Street, Rex street in DN-62, Unit-14, Zone-05",Own Sources,5,2019-20,2020-21 NE/2019-20/6221,Storm Water Drain,Completed,NE-ROYAPURAM,62,746000,"Desilting of Existing Storm Water Drain at Samy Pandaram Street ( Kalavai Street ), Lafond street, New Balakrishnan Street, Venkatesan Street, Wallers Road, Sami (N) Street, Balakrishnan Street, Pumping station road, Singanna street,Bazzar street, Dy. Mayor Kabala Moorthy Salai, Arunachalam main Road, Koovur Vaithianathan Street, Ulagappa (m ) Street , Iyya ( M ) Street, South Padavattamman Koil Street, Rex street in DN-62, Unit-14, Zone-05",Own Sources,5,2019-20,2019-20 NE/2019-20/6819,Buildings,Completed,NE-ROYAPURAM,62,1470000,"Construction of Dinning Hall at Chennai High School in West koovam River road in Division-62,Unit-14,Zone-05.",MLACDS,5,2019-20,2019-20 NE/2019-20/6844,Roads,Completed,NE-ROYAPURAM,62,1263000,"PROVIDIING RAIN WATER HARVESTING AT VARIOUS LOCATION IN DIVISION-62, UNIT-14, ZONE-05",MLACDS,5,2019-20,2020-21 NE/2019-20/6850,Roads,Completed,NE-ROYAPURAM,62,996000,"CONSTRUCTION OF TOILET TO ANGAN WADI CENTER NO:127 AT ADHEKESAVALU STREET IN DIV-62, UNIT-14, ZONE-05",MLACDS,5,2019-20,2020-21 NE/2019-20/6993,Buildings,Completed,NE-ROYAPURAM,62,803000,"Providing aluminum partition and interior works in AEE office at Adhikesavalu street in Division-62,Unit-14,Zone-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/7071,Buildings,Completed,NE-ROYAPURAM,62,899000,"REPAIRS AND MAINTENANCE OF RELIEF CENTER AT AYYA MUDHALI STREET IN DIV-62, UNIT-14, ZONE-05",Own Sources,5,2019-20,2020-21 NE/2019-20/9153,Parks,Completed,NE-ROYAPURAM,62,2290000,ANNUAL MAINTENANCE PARK AT MAYOR KABALAMOORTHY SALAI MAY DAY PARK IN DIV-62 UNIT-14 ZONE-5,Own Sources,5,2019-20,2020-21 NE/2019-20/9564,Buildings,Completed,NE-ROYAPURAM,62,1950000,"Providing Childrens play appartues in Mayday park at Mayor Kabalamoorthy salai in Division-62,Unit-14,Zone-05.",MLACDS,5,2019-20,2020-21 P/2019-20/9189,Parks,Completed,P-Parks and Playfields,62,4887000,"CONSTRUCTION OF INDOOR STADIUM (BADMINTON SINGLE COURT) IN VACANT LAND AT MAY DAY PARK, MAYOR KABALAMOORTHY SALAI IN DIV-62, ZONE-5 ( BATMINTON COURT SIZE - 13.40 m X 6.10 m ( 16.44 x 9.14 )",MPLADS,5,2019-20,2020-21 BR/2019-20/10911,Road Cut,Completed,BR-Bus Route Roads,63,70000,Attending OFC Roadcut Restoration at various location (Blackers road) in Zone - V. Deposit Code- 57/0039/2019-20,Deposit Works,5,2019-20,2019-20 BR/2019-20/10912,Road Cut,Completed,BR-Bus Route Roads,63,116000,Attending OFC Roadcut Restoration at various location (Blackers Road) in Zone - V. Deposit Code- 57/0043/2019-20.,Deposit Works,5,2019-20,2019-20 BR/2019-20/15804,Roads,Completed,BR-Bus Route Roads,63,1003000,"Partly relaying the road with BC after cold milling by paver finisher at Bharathi Salai in Dn-63 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/15808,Roads,Completed,BR-Bus Route Roads,63,351000,"Partly relaying the road with BC after cold milling by paver finisher at Thiru vi ka Salai( GP Road) in Dn-63 , Zone - 5",Grants,5,2019-20,2020-21 BR/2019-20/5706,Road Cut,Completed,BR-Bus Route Roads,63,1840000,"Restoration of Roadcut made by TANGEDCO at Dams Road, Raja Muthiah Salai in Dn. 61, 63, Zone -5 against challan No: BR/2019-20/0006178 and Reciept No: 06/2019-20/244956",Deposit Works,5,2019-20,2020-21 BR/2019-20/8211,Road Cut,Completed,BR-Bus Route Roads,63,2430000,"ROAD CUT RESTORATION AT LANGS GARDEN ROAD (FROM Jn. OF ADITHANAR SALAI TO Jn. OF AYYASAMY STREET) in DN. 61 & 63, Zone - 5 AGAINST CHALLAN NO-BR/2019-20/0018817",Deposit Works,5,2019-20,2020-21 L/2019-20/11345,Electrical,Completed,L-Electrical,63,176300,"Supply and Erection of 6Nos.of KIOSK Pillar Box at GP Road and Other Locations in Div59,62 and 63 Zone-5.",Own Sources,5,2019-20,2021-22 NE/2019-20/10362,Buildings,Completed,NE-ROYAPURAM,63,2490000,"Construction of Resource Composting center at South coovam river road in Division-63, Unit-14, Zone-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/10572,Buildings,Completed,NE-ROYAPURAM,63,2490000,"Construction of resource recovery center (Reach-2) (30-60 M) at South coovam river road in Dn.63,U-14,Z-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/10763,Buildings,Completed,NE-ROYAPURAM,63,2498000,"Construction of resource recovery center and Supply of Machineries at South coovam river road in Dn.63,U-14,Z-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/11875,Roads,Completed,NE-ROYAPURAM,63,138000,"Relaying of CC Road at Maroof Lane in Division-63, Unit-14, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/1205,Buildings,Completed,NE-ROYAPURAM,63,360000,"Providing Well Ring Mulch Pit at Various Street in Division-63, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/12977,Roads,Completed,NE-ROYAPURAM,63,940000,"Relaing the BT Road at Nagappa Mudali Street (Avg Width) in Division-63, Unit-14, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/12978,Roads,Completed,NE-ROYAPURAM,63,914000,"Relaing the BT Road at Vijaya Narayana Dass Road in Division-63, Unit-14, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/12979,Roads,Completed,NE-ROYAPURAM,63,360400,"Relaing the BT Road at Hussain Mulik Street in Division-63, Unit-14, Zone-V",Own Sources,5,2019-20,2020-21 NE/2019-20/14189,Buildings,Completed,NE-ROYAPURAM,63,989000,"Improvement work for D Depot at Athithanar Salai in Division-63, Unit-14, Zone-5",Own Sources,5,2019-20,2021-22 NE/2019-20/1878,Buildings,Completed,NE-ROYAPURAM,63,2968000,"Construction of public convenience at babu thootam LGN road in Division-63,Unit-14,Zone-05.",MLACDS,5,2019-20,2020-21 NE/2019-20/2014,Buildings,Completed,NE-ROYAPURAM,63,542000,"Providing Vegetable Shredder and Sewing Machine at South Coovam river in Ward-63, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/5903,Roads,Completed,NE-ROYAPURAM,63,248000,"PROVIDING PIPE LINE ARRANGEMENTS TO WATER STAGNATION AT ADHITHANAR SALAI,DN-63,U-14,Z-5",Own Sources,5,2019-20,2019-20 NE/2019-20/5979,Storm Water Drain,Completed,NE-ROYAPURAM,63,328000,"Improvements to storm water drain at L.G.N main road,L.G.N lanes,Velayudha acharya street and various streets in Dn,63,U-13,Z-05.",Own Sources,5,2019-20,2019-20 NE/2019-20/6163,Storm Water Drain,Completed,NE-ROYAPURAM,63,433000,"Desilting of Existing Storm Water Drain at Various Street (Narayana ( N ) ( Mosque ) Street, Narayana Street Opp Mosque, Velayudha ( A ) Street, Nagappa ( M ) Street, Kancheepuram Paichaiappan street, Goyyathope, Adithanar Salai, Chandra banu Street, Bharathi Salai, Chella Pillayar Koil Street, Begam Sahib Street, Begam Sahib II nd Street, Begam Sahib IV th Street, LGN Road, V N Doss Road, Burrah Sahib Street, Subaraya Street, Veeranpuram Street)in Division-63, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6238,Storm Water Drain,Completed,NE-ROYAPURAM,63,288000,"Replace of Manhole at Various Street (Narayana ( N ) ( Mosque ) Street, Narayana Street Opp Mosque, Velayudha ( A ) Street, Nagappa ( M ) Street, Kancheepuram Paichaiappan street, Goyyathope, Adithanar Salai, Chandra banu Street, Bharathi Salai, Chella Pillayar Koil Street, Begam Sahib Street, Begam Sahib II nd Street, Begam Sahib IV th Street, LGN Road, V N Doss Road, Burrah Sahib Street, Subaraya Street, Veeranpuram Street)in Division-63, Unit-14, Zone-5",Own Sources,5,2019-20,2019-20 NE/2019-20/6240,Storm Water Drain,Completed,NE-ROYAPURAM,63,1270000,"Improvements to Existing Storm Water Drain at L.G.N road in Dn.63,U-14,Z-05.",Own Sources,5,2019-20,2020-21 NE/2019-20/6742,Footpath,Completed,NE-ROYAPURAM,63,230000,"DEMOLITION OF PUBLIC CONVENIENCE AT BORDER THOTTAM LGN ROAD IN DIV-63, UNIT-14, ZONE-05",Own Sources,5,2019-20,2020-21 NE/2019-20/7567,Footpath,Completed,NE-ROYAPURAM,63,1149000,"proposed construction of compound wall at Langs garden road in DN-63,U-5,Z-5",Own Sources,5,2019-20,2020-21 BR/2019-20/10242,Roads,Completed,BR-Bus Route Roads,64,999000,"Restoration of Road Cut Made by OFC Providers in Various Bus Route Roads Dn -64,65,66,68,69,70 & 72, Zone -6 Vide Deposit Code No.57/0509,0589,0520,1053,0808,1159,1145/2018-19",Deposit Works,6,2019-20,2019-20 BR/2019-20/10304,Road Cut,Completed,BR-Bus Route Roads,64,1597000,"Restoration of roadcut made by CMWSSB at Sembium Redhills Road (From the jn of School Road to Jn of 200 Feet Road) in Dn-64, Zone-VI",Deposit Works,6,2019-20,2020-21 BR/2019-20/3247,Road Cut,Completed,BR-Bus Route Roads,64,760000,"Restoration of roadcut Made by CMWSSB at Sembium Redhills road in Dn-64, Zone-6",Deposit Works,6,2019-20,2019-20 BR/2019-20/4058,Road Cut,Completed,BR-Bus Route Roads,64,500000,"Restroration of Road cut made by TANGEDCO for laying 33kV UG cable at Red Hills Road in Dn-64 ,Zone 6",Deposit Works,6,2019-20,2020-21 BR/2019-20/4883,Roads,Completed,BR-Bus Route Roads,64,1174000,Partly relaying the road with BC after cold milling by paver finisher at Balaji Nagar Main Road in Dn-64 Zone - VI,Grants,6,2019-20,2020-21 BR/2019-20/6881,Road Cut,Completed,BR-Bus Route Roads,64,723000,"Restoration of road cut made by TANGEDCO for conversion of OH cable into UG Cable using Trechless method at Poombuhar nagar 1 st Main Road,Kolathur Red Hills road and Jambulingam main road in Dn 64,65 and 67 in Zone 6",Deposit Works,6,2019-20,2020-21 L/2019-20/13430,Electrical,Completed,L-Electrical,64,775800,"Supply and provision of 20 nos of 7 mtr GI new lamp post in kamraj nagar oadai street and poongavanam street in div 64 ,zone6 .",Own Sources,6,2019-20,2021-22 L/2019-20/4804,Electrical,Completed,L-Electrical,64,661900,Supply and provision of 16 nos of 7 mtr GI new lamp post in Kolathur colony haridass street park in div 64 of zone6,Own Sources,6,2019-20,2020-21 L/2019-20/8796,Electrical,Completed,L-Electrical,64,984500,Supply and replacement of damaged 1320mtr of 2X25Sqmm UG cable and 700mtr of 3 1/2 X25Sqmm UG cable at chronicle faulty locations at Various places in Kolathur section in div 64 to 65 in Zone-VI,Grants,6,2019-20,2020-21 L/2019-20/8804,Electrical,Completed,L-Electrical,64,5361600,Supply and replacement of damaged 120Nos of 7Mtr GI Lamp post with single straight bracket & 43Nos of 7Mtr GI Lamp post with single arch bracket at Various places in Kolathur section in div 64 to 65 in zone VI Area.,Grants,6,2019-20,2020-21 NF/2019-20/11114,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,650000,"Construction of Micro compost yard at Lakshmi amman kovil street ( Opp to Ganga theatre ) in Div-64,Unit-15,Zone-6",Grants,6,2019-20,2020-21 NF/2019-20/11115,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,650000,"Construction of Micro compost yard at Uzhavar santhai,Sembium redhills road (Phase-II West portion) in Div-64,Unit-15,Zone-6",Grants,6,2019-20,2020-21 NF/2019-20/13857,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1233000,"IMPROVEMENTS TO BT ROAD AT POOMPUHAR NAGAR 13TH STREET IN DN-64, UNIT-15, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13868,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,453000,"IMPROVEMENTS TO BT ROAD AT THANIGAI NAGAR VEERAMAMUNI STREET IN DN-64, UNIT-15, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13873,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,697000,"IMPROVEMENTS TO BT ROAD AT GIRIJA NAGAR WEST IN DN-64, UNIT-15, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14487,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,900000,"Repair and Improvements works to Chennai Higher Secondary School at School road in Dn-64, U-15, Z-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14579,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,590000,"Raising of ground level and providing Rainwater Harvesting to the existing Ground at Chennai Higher Secondary School in School road Dn-64, Unit-15,Zone-06",Own Sources,6,2019-20,2020-21 NF/2019-20/14593,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,1310000,"Repairs & improvements to Chennai Primary School at Thiruveethiamman koil street in Dn-64, Unit-15, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/1525,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,294000,"Proposed construction of Material recovery Facility In Sembium Redhills road ( ulzhavar sandhai) at Dn -64 , Unit-15,Zone-06",Own Sources,6,2019-20,2019-20 NF/2019-20/16163,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,398000,"Improvements to the CC Road at Ambedkar nagar 1st cross street in Div-64,Unit-15,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16190,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,414000,"Improvements to the CC Road at Ambedkar nagar 2nd cross street in Div-64, Unit-15, Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16191,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,1115000,"Improvements to the CC Road at Ambedkar nagar main road in Div-64,Unit-15,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1752,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,121000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-64,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1782,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,743000,"Proposed construction of well ring for micro compost yard at various locations in Div-64,Unit-15,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1827,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,166000,"REPAIRS AND MAINTENANCE TO STORM WATER DRAIN AT VARIOUS LOCATIONS IN DN-64,UNIT-15,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2726,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,810000,"Providing Borewell to Chennai Higher Secondary School at Kolathur and Chennai Primary School at Thiruveethi amman Koil street in Dn-64, Unit-15, Zone-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3184,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,244000,"Construction Shrudding machine shed at Uzhalavar chanthi , papermills road in Dn -64,Unit-15,Zone-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3288,Buildings,Completed,B-Buildings,64,4100000,"Additional Construction of rooms for Health post in Existing UPHC at Anjugam Nagar 4th street in Dn -64,UNit-17,Zone-06",Own Sources,6,2019-20,2020-21 NF/2019-20/6568,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,380000,"Providing Borewell arrangements at Anjugam nagar 4th street Chennai corporation Park ( Kolathur Constituency MLA Fund scheme) in Div-64,Unit-16,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6569,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,380000,"Providing Borewell arrangements at Poombugar nagar 4th street Chennai corporation Park ( Kolathur Constituency MLA Fund scheme) in Div-64,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6948,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,2455000,"Improvements to Existing Storm water drain including Desilting & Other repair works at Poompughar Nagar 2nd Main Road,Poompughar Nagar 5th street,8th street,13th street,Anjugam Nagar West Main Road,Anjugam Nagar 4th Street,Vetrivel nagar 3rd Street,Samuthuriya Colony Main Road and various streets in Div-64,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/6949,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,1028000,"Improvements to Existing Storm water drain including Desilting & Other repair works at Poompuhar Nagar 1st main road,Balaji Nagar Main Road,Sembium redhills road and various streets in Div-64,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/7144,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,2500000,"Construction of Additional class room for Chennai Corporation Primary school at School road in Dn-64,Unit-15,Zone-6.",MLACDS,6,2019-20,2020-21 NF/2019-20/7223,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,500000,"Providing Reverse Osmasis (RO) Plant at Chennai Corporation High school , School road in Div-64,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/7247,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,2000000,"Construction of New Public Convenience at Nermai nagar in Div-64,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/7860,Footpath,Completed,NF-THIRU-VI-KA NAGAR,64,4800000,"Providing Handrail Arrangements , Art Work , Entrance Purgola Design , Electrical Arrangements with Necessary work in Haridoss Pond in Dn-64 , Un-15 , Zn-6",MPLADS,6,2019-20,2020-21 NF/2019-20/7862,Playfields,Completed,NF-THIRU-VI-KA NAGAR,64,400000,"IMPROVEMENTS TO TNHB PLAY GROUND AT SAMDHARIYA COLONY 5TH STREET IN DN-64,UNIT-15,ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/7863,Electrical,Completed,NF-THIRU-VI-KA NAGAR,64,500000,"IMPROVEMENTS TO TNHB PARK AT TNHB COLONY IN DN-64,UNIT-15,ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/8499,Parks,Completed,NF-THIRU-VI-KA NAGAR,64,530000,"Maintanence of Haridoss pond for the period of one year from (01.11.2019 to 31.10.2020) in Dn-64, Un-15, Z-6",Own Sources,6,2019-20,2020-21 NF/2019-20/8500,Roads,Completed,NF-THIRU-VI-KA NAGAR,64,950000,"Attending potholes & patchworks at Anjugam nagar 18th 13th 16th Streets, Poombugar Nagar and various streets IN DN-64 U-15 Z-06",Own Sources,6,2019-20,2019-20 NF/2019-20/9559,Buildings,Completed,NF-THIRU-VI-KA NAGAR,64,470000,"Repair works & Improvements to Amma unavagam at Papermills road in div-64,Unit-15,Zone-6",Own Sources,6,2019-20,2021-22 BR/2019-20/4882,Roads,Completed,BR-Bus Route Roads,65,3526000,"Partly relaying the road with BC after cold milling by paver finisher at Paper Mills Road in Dn-65 ,66,68 & 69 Zone - VI",Grants,6,2019-20,2020-21 NF/2019-20/10574,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,61000,"Name of Work :Repairs & Improvements to Srinivasan nagar cps school & Dn -65,Unit-15,Zone-6.",Own Sources,6,2019-20,2021-22 NF/2019-20/11118,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,650000,"Construction of Micro compost yard at GKM Colony burial ground in Div-65,Unit-15,Zone-6",Grants,6,2019-20,2020-21 NF/2019-20/12498,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,111000,"IMPROVEMENTS OF CC ROAD IN RAJAJI NAGAR MUTHU STREET IN DN-65 U-15 Z-06,",Own Sources,6,2019-20,2020-21 NF/2019-20/14404,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,400000,"IMPROVEMENTS TO ANGANWADI CENTER NO.33603120101, @SRINIVASAN NAGAR 3RD MAIN ROAD IN DN-65 U-15 Z-06,",Own Sources,6,2019-20,2021-22 NF/2019-20/1527,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN G.K.M COLONY BURIAL GROUND IN DN-65,UNIT-15,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/15468,Electrical,Completed,NF-THIRU-VI-KA NAGAR,65,353808,"ELECTRICAL CREMATORIUM ,REPLACEMENT OF HEATING ELEMENT AND ELEMENT HOLDING TUBING SYSTEM @GKM COLONY, JAMBULINGAM MAIN ROAD , BURIAL GROUND IN DN-65 UNIT-15 ZONE-06,",Own Sources,6,2019-20,2020-21 NF/2019-20/16213,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,956000,"IMPROVEMENTS TO CC ROAD @ RAJAJI NAGAR 2ND STREET PART IN DN-65 UN-15 Z-06,",Own Sources,6,2019-20,2020-21 NF/2019-20/16214,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,205000,"IMPROVEMENTS TO CC ROAD @ SENTHIL NAGAR 8TH CROSS STREET PART IN DN-65 UN-15 Z-06,",Own Sources,6,2019-20,2020-21 NF/2019-20/16215,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,517000,"IMPROVEMENTS TO CC ROAD @ VETRI SELVI ANBALAGAN NAGAR RANGA STREET IN DN-65 UN-15 Z-06,",Own Sources,6,2019-20,2020-21 NF/2019-20/16220,Roads,Completed,NF-THIRU-VI-KA NAGAR,65,1058000,IMPROVEMENTS TO BT ROAD @ KRISHNA NAGAR 1ST STREET IN DN-65 UN-15 Z-06,Own Sources,6,2019-20,2021-22 NF/2019-20/1755,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,147000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-65,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1784,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,607000,"Proposed construction of well ring for micro compost yard at various locations in Div-65,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2739,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,520000,"Providing Bore well arrangements to Chennai Primary School at GKM Colony 27th street and Srinivasa Nagar in Dn-65 , Un-15 , Z-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3186,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,244000,"Construction Shrudding machine shed at GKM Colony burial ground composting yard in Dn -65,Unit-15,Zone-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3193,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,325000,"Providing barbed fencing in Makkaram thottam burial ground at Kolathur Main road in Dn-65 u-15 Z-06,",Own Sources,6,2019-20,2020-21 NF/2019-20/3608,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,285000,"Repair & Improvements to open Community well at Akbar Square 2nd Street in Dn-65 unit-15 Zone-06,",Own Sources,6,2019-20,2019-20 NF/2019-20/6898,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,2231000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN IN SENTHIL NAGAR, GANESH NAGAR, RAJAJI NAGAR ,SRINIVASAN NAGAR AND VARIOUS STREET IN DIVISION-65, UNIT-15, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6899,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,617000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN IN SENTHIL NAGAR 3RD MAIN ROAD , GKM COLONY JAMBULINGAM MAIN ROAD, THILLI NAGAR MAIN ROAD SRINIVASAN NAGAR 1ST MAIN ROAD, AND VARIOUS STREET IN DIVISION-65, UNIT-15, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/7224,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,500000,"Providing Reverse Osmasis (RO) Plant at GKM Colony 27th street ICDS Centre in Div-65,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/7430,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,620000,"MAINTENANCE OF PARK BY PRIVATE AGENCY AT RK SYNTICATE PARK IN DN-65,UNIT-15,ZONE-06",Own Sources,6,2019-20,2021-22 NF/2019-20/7432,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,655000,"Senthil Nagar 10th Street Park������������������ for the period of one year by private agency in Div-65,Unit-15, Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/7433,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,632000,"Senthil Nagar Park 13th Street (Thanthai Periyar Park )������������������ for the period of one year by private agency in Div-65,Unit-15, Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/7434,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,620000,"Janakiraman Colony Nagar Park������������������ for the period of one year by private agency in Div-65,Unit-15, Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/8046,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,840000,"ATTENDING THE POT HOLES AND DAMAGED ROAD IN SENTHIL NAGAR 2ND MAIN ROAD,THILLI NAGAR 1ST MAIN ROAD , RAJAJI NAGAR KAMARAJAR STREET ,SRINIVASAN NAGAR 1ST MAIN ROAD,GKM COLONY JAMBULINGAM MAIN ROAD IN VARIOUS STREET IN DN-65 U-15 Z-06,",Own Sources,6,2019-20,2019-20 NF/2019-20/9033,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,470000,"Repairs & Improvements to AE Office,CI office, SI office and E-Seva Maiyam at Subramaniyan St in Dn -65,Unit-15,Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/9510,Buildings,Completed,NF-THIRU-VI-KA NAGAR,65,498000,"Name of Work :Repairs & Improvements to AE Electrical office @ gkm colony jambulingam main road in Dn -65,Unit-15,Zone-6.",Own Sources,6,2019-20,2020-21 BR/2019-20/3863,Roads,Completed,BR-Bus Route Roads,66,1111000,Supplying and Fixing of Digital Awarness Bunner in the Stainless Steel Bus Shelters for Lokh Sabha Election 2019 in Various Bus Route roads in Zone-VI,Own Sources,6,2019-20,2019-20 BR/2019-20/8333,Roads,Completed,BR-Bus Route Roads,66,1070000,"Proposed Construction of New Modern Stainless Steel Bus Shelter of size 6m x 2.5m at Karthikeyan salai near Thiruvalluvar Thirumana Mandapam ) in Dn- 66, Zone -6 (Under MLA Scheme)",MLACDS,6,2019-20,2020-21 D/2019-20/12430,Storm Water Drain,Completed,D-Storm Water Drains,66,2245000,"NAME OF WORK: Construction of storm water drain of size 900 x 900mm along Periyar nagar 5 th cross street and Periyar nagar Busdepot Road crossing in Dn - 66,Zone - VI.",Own Sources,6,2019-20,2020-21 L/2019-20/8805,Electrical,Completed,L-Electrical,66,11751700,"Supply and replacement of damaged 175Nos of 7Mtr GI Lamp post with single straight bracket, 33Nos of 7Mtr GI Lamp post with single arch bracket, 21Nos 9.5Mtr GI lamp post with Single straight bracket & 75Nos 9.5Mtr Lamp post with Single arch bracket at Various places in div 66 to 67 in Agaram section in zone VI Area.",Grants,6,2019-20,2020-21 NF/2019-20/10294,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,930000,"Improvements to Chennai Middle school at K.C Garden 2nd street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/12504,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,900000,"MAINTENANCE AND OPERATION OF WATER TREATMENT PLANT (AMMA KUDINEER) AT PERIYAR NAGAR PERIPHERAL HOSPITAL CAMPUS, KARTHIKEYAN SALAI IN DN-66,UNIT-16,ZONE-06",Own Sources,6,2019-20,2021-22 NF/2019-20/13682,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,320000,"Providing Borewell arrangements at Sakthivel nagar 2nd cross street Park in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13688,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,320000,"Providing Borewell arrangements at Jawahar nagar 2nd cross street Gym building in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14088,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,1250000,"Repair works & Improvements to Existing School building at Jawahar nagar Temple road 1st cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1530,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN THANTHONRIAMMAN KOIL STREET AT DN-66,UNIT-16,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/15839,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,1300000,"Providing Gym equipments at Jawahar nagar 2nd cross street Chennai Corporation Gym building in Div-66,Unit-16,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/1768,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,94000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-66,UNIT-16,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1788,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,340000,"Proposed construction of well ring for micro compost yard at various locations in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2732,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,260000,"Providing Bore well arrangements to Chennai Middle School at K.C Garden 2nd street in DN-66,Unit-16,Zone-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3046,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,370000,"Improvements to Centremedian with Greenery arrangements at Siva Elango salai in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3178,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,244000,"Construction Shrudding machine shed at Thanthonriyamman kovil street Composting yard in Dn -66,Unit-16,Zone-06",Own Sources,6,2019-20,2020-21 NF/2019-20/3261,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,244000,"Construction Shrudding machine shed at Old Lorry station, Perambur High road (South) in Dn -71,Unit-16,Zone-06",Own Sources,6,2019-20,2020-21 NF/2019-20/3727,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,198000,"Construction of Sump for Division-66th office at Jawahar nagar 3rd circular road in Div-66,Unit-16,Zone-6.",Own Sources,6,2019-20,2019-20 NF/2019-20/3729,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,194000,"Repairs & Improvements to the Unit 16th office at Jawahar nagar 3rd circular 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/4036,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,162000,"Construction of storm water drain manhole inspection chamber for Existing Storm water drain at Siva elango salai,Jawahar nagar 5th circular road,Varatharajan street and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/4238,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,523000,"Improvements to CC Road at Dhakshnamoorthy street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/4239,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,152000,"Improvements to CC Road at Sivalingam street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/4345,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,572000,"Improvements to CC Road at Annalgandhi cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/4979,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,806000,"Improvements to CC Road at Rangasamy street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/5065,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,414000,"Improvements to CC Road at Ramamoorthy colony 4th cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/5069,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,283000,"Improvements to CC Road at Ramamoorthy colony 3rd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/5164,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,326000,"Improvements to CC Road at Ramamoorthy colony 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/6551,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,380000,"Providing Borewell arrangements at Sakthivel nagar 2nd cross street Park ( Kolathur Constituency MLA Fund scheme) in Div-66,Unit-16,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6560,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,380000,"Providing Borewell arrangements at Chennai Corporation Gym building, Jawahar nagar 2nd cross street ( Kolathur Constituency MLA Fund scheme) in Div-66,Unit-16,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6925,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,1938000,"Improvements to Existing Storm water drain including Desilting & Other repair works at Manavalan street,Gandhimathi street,Nagammal street,Krishna nagar main road,Andal avenue ,Jawahar nagar 3rd circular road,SRP Colony main road and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/6941,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,1699000,"Improvements to Existing Storm water drain including Desilting & Other repair works at Kumaran nagar 1st cross street,2nd cross street,4th cross street, Ramamoorthy colony and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/6944,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,2491000,"Improvements to Existing Storm water drain including Desilting & Other repair works at Kumaran nagar 80 feet road, papermills road,Karthikeyan salai,Jawahar nagar 1st main road and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/7407,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,712000,"Annual Maintanence of Park at Periyar nagar 20th street (FOR ONE YEAR) in Dn 66,Unit 16, Zone 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/7408,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,714000,"Annual Maintanence of Park at Jawahar nagar 5th main road (FOR ONE YEAR) in Dn 66,Unit 16, Zone 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/7409,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,469000,"Annual Maintenance of Park at Jawahar nagar 2nd circular road (FOR ONE YEAR) in Dn 66,Unit 16, Zone 6",Own Sources,6,2019-20,2021-22 NF/2019-20/7410,Parks,Completed,NF-THIRU-VI-KA NAGAR,66,303000,"Annual Maintenance of Park at Sakthivel nagar 2nd cross street (FOR ONE YEAR) in Dn 66,Unit 16, Zone 6",Own Sources,6,2019-20,2021-22 NF/2019-20/7804,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,903000,"Micro Composed Center (MCC) Collection tank wall raising at Various locations in Unit-15,16 & Unit-17, Zone-6.",Own Sources,6,2019-20,2019-20 NF/2019-20/7928,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,310000,"Repairs & Improvements to Kamarajar nagar Public Convenience in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/8055,Roads,Completed,NF-THIRU-VI-KA NAGAR,66,950000,"Attending potholes and patchwork at papermills road, Manavalan street,Kumaran nagar 1st main road,Ragavendra link road,Sakthivinayagar kovil street,Thiruvenkadam street,Sivalingam street, Gandhimathi street and various streets in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/9470,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,199000,"Improvements to the 66th Division office at Jawahar nagar 3rd circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/9480,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,510000,"Improvements to the 16th unit office at Jawahar nagar 3rd circular 2nd cross street in Div-66,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/9650,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,620000,"Repair & Improvements to Amma unavagam at Temple road 1st cross street in Div-66,Unit-16,Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/0555,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,197000,"Repairs & Improvements to Jeganathan street Public convenience in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/0586,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,199000,"Providing Borewell and water supply arrangements at Jeganathan street Public Convenience in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/0592,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,180000,"Repair works to Division 67th office at Thanthonriyamman kovil street in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/10593,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,1250000,"Improvements works to Chennai Primary School at G.K.M Colony 12 th street in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/11121,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,650000,"Construction of Micro compost yard at Muthukumarappa street in Div-67,Unit-15,Zone-6",Grants,6,2019-20,2021-22 NF/2019-20/11338,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,350000,"Supply & fixing Shredding machine for existing Bio gas plant ,Loco works road in Dn -67,Unit-15,Zone-06",Own Sources,6,2019-20,2020-21 NF/2019-20/13584,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,320000,"Providing Borewell arrangements at Ananthan Park ,Thanthonriyamman kovil street in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/1533,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORAION IN THANTHONDRI AMMAN KOIL STREET IN DN.67,UNIT-15,,ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/1756,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,13500,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-67,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1795,Parks,Completed,NF-THIRU-VI-KA NAGAR,67,534000,"Proposed construction of well ring for micro compost yard at various locations in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2731,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,553000,"PROVIDING BORE WELL ARRANGEMENTS TO ICDS CENTRE AT LOCO SCHEME 1ST STREET AND CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT MARKET STREET IN DN -67,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3180,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,410000,"Construction Shrudding machine shed and repair works to at Thanthonriyamman kovil street Composting yard in Dn -67,Unit-15,Zone-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3826,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,199000,"Construction of Sump for Division-67 office at S.R.P Koil Street (south) in Div-67,Unit-15,Zone-6.",Own Sources,6,2019-20,2019-20 NF/2019-20/3831,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,375000,"Repairs & Improvements to open community well at Radakrishnan Nagar in Div 67, unit 15 Zone 6",Own Sources,6,2019-20,2019-20 NF/2019-20/6555,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,380000,"Providing Borewell arrangements at Chennai Corporation Primary school , GKM Colony 12th street ( Kolathur Constituency MLA Fund scheme) in Div-67,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6556,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,380000,"Providing Borewell arrangements at GKM Colony 14th street ICDS Centre (Kolathur Constituency MLA Fund scheme) in Div-67,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6558,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,380000,"Providing Borewell arrangements at Ananthan Park @ Thanthondriyamman kovil street ( Kolathur Constituency MLA Fund scheme) in Div-67,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6912,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,1078000,"Repairs to existing strom water drain, desiliting, and Manhole door fixing at Rangasayee street,muthukumarappa street and Various street in Dn 67 , Unit 15 , Zone 6",Own Sources,6,2019-20,2019-20 NF/2019-20/6927,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,513000,"Repairs to existing strom water drain, desiliting, and Manhole door fixing at S.R.P Koil street, Jambulingam Main road and GKM Colony 17th street in Dn 67 , Unit 15 , Zone 6",Own Sources,6,2019-20,2019-20 NF/2019-20/7041,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,814000,"Improvements to CC Road at GKM Colony 8th street in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/7228,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,500000,"Providing Reverse Osmasis (RO) Plant at Chennai Corporation Girls Higher secondary school ,Market street in Div-67,Unit-15,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/7278,Playfields,Completed,NF-THIRU-VI-KA NAGAR,67,2499000,"Providing Football court at Chennai Corporation playground,Rangasayee street in Div-67,Unit-15,Zone-6",MLACDS,6,2019-20,2021-22 NF/2019-20/7289,Playfields,Completed,NF-THIRU-VI-KA NAGAR,67,2498000,"Providing Tennis court and Outoor GYM apparatus at Chennai Corporation playground,Rangasayee street in Div-67,Unit-15,Zone-6",MLACDS,6,2019-20,2021-22 NF/2019-20/8095,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,495000,"Attending Potholes & Patches at Thanthonriyamman kovil street,Jegannathan street,Rangasayee 1st lane ,SRP Koil street ( South) and various streets in Div-67,Unit-15,Zone-6",Own Sources,6,2019-20,2019-20 B/2019-20/10705,Buildings,Completed,B-Buildings,68,9500000,"CONSTRUCTION OF COMMUNITY CENTRE AT SRP KOIL STREET, T.V.K.NAGAR IN DIV-68,ZONE-6.",MPLADS,6,2019-20,2021-22 NF/2019-20/10766,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,520000,"Dismantling Old dilapidated overhead Water tank at Inside of UPHC Campus & Pallavan salai roadside park in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/11493,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1367000,"IMPROVEMENTS TO RRC AT THANGAL BURIAL GROUND AT PALLAVAN SALAI IN DIV-68,UNIT-16,ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14227,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,224000,"REPAIRNG AND IMPROVEMENT WORKS TO WATER SUPPLY ARRANGEMENTS AT JAMALIYA ICDS ,JAIBEAM NAGAR ICDS AND MADURAI SAMY MADAM URUDHU SCHOOL IN DIV-68,UNIT-16, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14437,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,133000,"REPAIRS AND IMPROVEMENTS WORKS TO DAMAGED COMPOUND WALL TO GEORGE COLONY PARK AND WATER SUPPLY ARRANGEMENTS IN KENNEDY SQUARE PARK AT DN 68, UNIT 16 , ZONE 6",Own Sources,6,2019-20,2020-21 NF/2019-20/14832,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,142000,"REPAIRS AND IMPROVEMENTS TO ,TEMPERARY VETRINARY HOSPITAL , UPHC PALLAVAN SALAI AND VARIOUS GCC BUILDINGS IN DN 68 UNIT 16 ZONE 6",Own Sources,6,2019-20,2020-21 NF/2019-20/15190,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,460000,"Repair and Improvement works to Division office 68 at paper mills road In Div-68, Unit-16, Zone - 06",Own Sources,6,2019-20,2020-21 NF/2019-20/1536,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY CENTRE AT THANGAL BURIAL GROUND IN DN.68,UNIT-16,,ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/1769,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,80700,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-68, UNIT-16 ,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1799,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,445000,"Proposed construction of well ring for micro compost yard at various locations in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2715,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,520000,"Providing Bore Well Arrangement to Chennai Primary School and Urudu Primary School at Maduraisamy Madam in Dn-68 , Un-16 , Z-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2748,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,520000,"Providing Borewell Arrangement to Chennai Primary School at TVK Nagar and Chennai Middle School at Gopalapuram in Dn-68 , Un-16 , Z-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3053,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,269000,"Improvements to Centremedian with Greenery arrangements at Pallavana salai in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3507,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,199000,"Repairs & Improvements to Maduraisamy madam street ICDS Centre ( Centre No.33603070223) in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/3549,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1355000,"Repairs & Improvements to Chennai Primary school (Tamil & Urudhu school) at Maduraisamy madam street in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/3562,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1147000,"Repair and Improvement works to Chennai Primary school at Thiru.Vi.Ka nagar main street in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/6275,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,210000,"Repairs & Improvements to open community well at T.V.K nagar 19 st street in Div 68, unit 16 Zone 6",Own Sources,6,2019-20,2019-20 NF/2019-20/6570,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,340000,"Providing Borewell arrangements at K.K.R Park at Pallavan salai ( Kolathur Constituency MLA Fund scheme) in Div-68,Unit-16,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6943,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,2247501,"Repairs to the exisitng Storm water drain at Kennady square main road,cross street,Vasudevan street and Various streets in Dn-68, Unit-16,Zone-06.",Own Sources,6,2019-20,2019-20 NF/2019-20/6945,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,68,600000,"Repairs to the exisitng Storm water drain and desilting work at Maduraisamy madam street,Gurusamy street,Ponnusamy nagar,Andiappan street and Various streets in Dn-68,Unit-16,Zone-06.",Own Sources,6,2019-20,2019-20 NF/2019-20/7108,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,2200000,"Construction of Multipurpose hall at teeds garden 1st street ICDS Center First Floor in Dn-68 , Un-16 , Zn-6",MLACDS,6,2019-20,2020-21 NF/2019-20/7674,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,125000,"Demolition of ICDS at Madurai Samy Madam Street in Dn-68 , Un-16 , Zone - 6.",Own Sources,6,2019-20,2020-21 NF/2019-20/7706,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,159000,"Demolition of Chennai Corporation UPHC adjacent building at Teeds Garden in Dn -68 ,Unit -16 , Zone -6",Own Sources,6,2019-20,2021-22 NF/2019-20/8098,Roads,Completed,NF-THIRU-VI-KA NAGAR,68,1380000,"Attending Potholes & Patchwork at ponnusamy nagar main street,Teeds garden 2nd street,Teeds garden 6th street,Andiyappan street,Vasudevan street and various streets in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/8736,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1000000,"Improvements to Pets health care center at Pallavan salai in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/9138,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,465000,"Supply of 100 Kg to 150 Kg Multiple Pet Bottle Baling Press Machine. Transportation Erection and Commisioning Fitting Charges 2 Coats of Zinc Chrome. 2 coats of ploy urethane paint including 18% GST at Thangal Burrial Ground, Pallavan Salai. in Division-68 , Unit-16, Zone-VI",Own Sources,6,2019-20,2020-21 NF/2019-20/9156,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,260000,"Fixing arrangements and other additional works for Shredding machine and bailing machine at Pallavan salai Resource Recovery Center in Div-68, Unit-16, Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/9209,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,290000,"IMPROVEMENTS TO PUBLIC CONVENIENCE PALLAVAN SALAI DIV-68, UNIT-16, ZONE -06",Own Sources,6,2019-20,2020-21 NF/2019-20/9487,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,250000,Construction of Sump for DIVISION OFFICE BUILDING at paper mills road IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2019-20,2020-21 NF/2019-20/9604,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,275000,MODERNIZATION OF OPEN WELL AT PALLAVAN SALAI IN DN 68 UNIT 16 ZONE 6,Own Sources,6,2019-20,2020-21 NF/2019-20/9678,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,355000,"Providing Borewell arrangements at Thillainayagam 2nd street Public Convenience in Div-68,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/9745,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,3000000,"Construction of Anganwadi building at madurai samy madam street in dn 68, unit 16, zone VI",MLACDS,6,2019-20,2020-21 B/2019-20/8640,Buildings,Completed,B-Buildings,69,16697904,"ADDITIONAL CONSTRUCTION OF 4 CLASS ROOMS, STAFF ROOM WITH TOILET BLOCK IN FIRST FLOOR AND SECOND FLOOR CBHSS BUNDER GARDEN STREET AT PERAMBUR IN DN-69, ZONE-6",MPLADS,6,2019-20,2021-22 BR/2019-20/4580,Roads,Completed,BR-Bus Route Roads,69,1024000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Lakshmi Amman Koil st and Melpatti Ponappan St(Jn of Gopal st to Burial Ground) in Dn-69, Zone -VI",Grants,6,2019-20,2020-21 BR/2019-20/4584,Roads,Completed,BR-Bus Route Roads,69,3471000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Madhavaram high road ( From Lakshmiamman Koil Street to Pallavan Salai) in Dn-69, Zone - VI",Grants,6,2019-20,2020-21 BR/2019-20/4590,Roads,Completed,BR-Bus Route Roads,69,3530000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Anderson Road in Dn-69, Zone - VI",Grants,6,2019-20,2020-21 BR/2019-20/6297,Roads,Completed,BR-Bus Route Roads,69,762000,"Restoration of Roadcut made by CMWSSB @ Madhavaram High road, Bricklin road and Paper mills road in Dn-69 &75 zone-6",Deposit Works,6,2019-20,2021-22 NF/2019-20/10052,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,630000,"Construction of Store room in ST.MARY'S ROAD at div 69, unit 16, zone 6",Own Sources,6,2019-20,2020-21 NF/2019-20/10612,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,930000,"Improvements & repair works to Chennai Middle School at Kabilar street in Div-69, Unit-16, Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/10836,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,540000,"Repair & Improvements to Division 69 office at Raja street in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/12814,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,1900000,"Repair & improvements to GYM at Chinna Kulandai main street at Division -69, Unit -16, Zone -06",Own Sources,6,2019-20,2020-21 NF/2019-20/1535,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,294000,"Proposed construction of Material Recovery Facility in DRBCC School opposite Ground, Tank link road in Division-69, Unit-17, Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/16388,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,104000,"Improvements to CC Road at VASANTHA GARDEN LANE in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16389,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,196000,"Improvements to CC Road at CHINNAKUZANAI 2ND LANE in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16395,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,1162000,"Improvements to CC Road at THIKKAKULAM in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16397,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,168000,"Improvements to CC Road at CHINNA KOLANTHI 1ST LANE Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16398,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,555000,"Improvements to CC Road at AMBEDKAR STREET in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16399,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,775000,"Improvements to BT Road at SIRUVALLUVARPURAM in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16400,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,492000,"Improvements to BT Road at SADIYAPPA STREET in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16401,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,1164000,"Improvements to BT Road at SSV KOVIL STREET in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1758,Parks,Completed,NF-THIRU-VI-KA NAGAR,69,27000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-69,UNIT-16,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1801,Parks,Completed,NF-THIRU-VI-KA NAGAR,69,445000,"Proposed construction of well ring for micro compost yard at various locations in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2728,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,770000,"PROVIDING BORE WELL ARRANGEMENTS TO CHENNAI MIDDLE SCHOOL AT MADUMA NAGAR AND CHENNAI MIDDLE SCHOOL AT VASANTHA GARDEN IN DN -69, UNIT-16,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2729,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,297000,"PROVIDING BORE WELL ARRANGEMENTS TO CHENNAI HIGHER SECONDARY SCHOOL AT BUNDER GARDEN IN DN -69, UNIT-16,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3055,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,112000,"Improvements to Centremedian at M.H Road in Div-69,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3183,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,244000,"Construction Shrudding machine shed at Tank link road Composting yard in Dn -69,Unit-16,Zone-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3240,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,978000,"Repair and improvement works in Chennai middle school Madurai street at div 69, unit 16, zone 6",Own Sources,6,2019-20,2020-21 NF/2019-20/5313,Electrical,Completed,NF-THIRU-VI-KA NAGAR,69,748400,"Providing Comprehensive Annual Maintenance for 1 No 62.5KVA Diesel Genset at Zonal Office-VI and 1 No 62.5 KVA Diesel Genset at Diagonstic centre in Div-70, 2Nos EOC Hospital Thiruvenkatasami street, in Div-73 and 1Nos 62.5 KVA Diesel Genset at Relief centre Perambur Barracks road in Div-76 in Zone-VI",Own Sources,6,2019-20,2021-22 NF/2019-20/5316,Electrical,Completed,NF-THIRU-VI-KA NAGAR,69,1445300,"Providing Comprehensive Annual Maintenance for 62.5KVA DG set in 1 Nos CHS pada salai in Div-64, 1Nos CHS Market street in Div-66, 1Nos CHS Bunder garden in Div-69, 2Nos CHS School road in Div-70 & 30KVA Diesel Genset in 1Nos CHS Thiruvenkatasami street in Div-73 1Nos CHS Ammaiyammal street in Div-73, 1Nos CHS Cooks road in Div-73, 1Nos CHS Chinna babu street in Div-74, 1Nos CHS Padavattamman koil street in Div-75, and 1Nos CHS Stranhans road in Div-76 in Zone-VI.",Own Sources,6,2019-20,2021-22 NF/2019-20/5317,Electrical,Completed,NF-THIRU-VI-KA NAGAR,69,187000,"Providing Comprehensive Annual Maintenance for 2Nos 2Ton Split Air Conditioner, 14Nos 1.5 Ton Split Air Conditioner in Zonal office Building Zone-6 in Div-69, 8Nos 1.5 Ton Split Air Conditioner in Perambur Diagonstic Centre in Div-70 12Nos 1.5 Ton Split Air Conditioner in EOC Hospital Thiruvenkatasami street in Div-73 in Zone-VI.",Own Sources,6,2019-20,2021-22 NF/2019-20/6216,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,256000,"Repairs & Improvements to open community well at Poonuvelpuram 1st street in Div 69, unit 16 Zone 6",Own Sources,6,2019-20,2019-20 NF/2019-20/6536,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,500000,"Providing Reverse Osmasis (RO) Plant at Chennai Corporation High school ,Bunder garden main street in Div-69,Unit-16,Zone-6",MLACDS,6,2019-20,2020-21 NF/2019-20/6913,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,2489001,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT SIRUVALLUR ROAD, JAWAHAR ROAD, RAGAVAN STREET AND VARIOUS STREET IN DIVISION-69, UNIT-16, ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/6923,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,1504000,"Repairs to the exisitng Storm water drain at paper road, Madavaram road, Anderson Road and various streets in Div-69, Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/7122,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,6000000,"Construction of Modern Dobikana at thikkakulam in Divison - 69, Unit - 16, Zone-6",MPLADS,6,2019-20,2020-21 NF/2019-20/8051,Roads,Completed,NF-THIRU-VI-KA NAGAR,69,830000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT ANDERSON ROAD, PAPER MILLS ROAD, M.H. ROAD AND VARIOUS STREETS IN DIVISION-69, UNIT-16, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/9691,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,1650000,"Improvement works in UPHC (Siruvallur) in Kabilar street at div 69, unit 16, zone 6",Own Sources,6,2019-20,2020-21 BR/2019-20/10244,Roads,Completed,BR-Bus Route Roads,70,885000,"Restoration of Road Cut Made by OFC Operators in Various Bus Route Roads, Dn -70,71,77,78,81,82,83,85,92 & 93, Zone -6 & 7 Vide Deposit Code No.57/0509,1053,1145,0451,0550,0003,1159,1147,1145,1149 & 1143/2018-19",Deposit Works,6,2019-20,2019-20 BR/2019-20/6152,Road Cut,Completed,BR-Bus Route Roads,70,2213000,"Restoration of roadcut made by CMWSSB at Perambur High Road (South) in Dn-70 , Zone 6",Deposit Works,6,2019-20,2020-21 D/2019-20/10250,Storm Water Drain,Completed,D-Storm Water Drains,70,4225000,"Demolition and Reconstruction of storm water drain of size 900 x 900mm along Jamalia Nagar main road from jamalia link road to junction of Perambur highr road south in Dn - 70,Zone - VI.",Own Sources,6,2019-20,2020-21 D/2019-20/10251,Storm Water Drain,Completed,D-Storm Water Drains,70,4995000,"Demolition and Reconstruction of storm water drain of size 900 x 900mm along Perambur High road 1 st street from Jamalia link road to junction of Perambur highr road south in Dn - 70,Zone - VI",Own Sources,6,2019-20,2020-21 L/2019-20/6013,Electrical,Completed,L-Electrical,70,2485700,"Provision of 55HP Submersible pump motor with additional cable for pump, chage over panel and erection and commissioning in Ganeshapuram subway division-70 Zone-6",Own Sources,6,2019-20,2019-20 L/2019-20/6017,Electrical,Completed,L-Electrical,70,2487300,"Provision of 1.No 125KVA DG set control panel, 2.Nos 55HP starter Panel and erection and commissioning of 130Mtr Eb & laying (3.5 Core X 120Sqmm) in Ganeshapuram subway in Division-70 in zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/11242,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,1894000,"Reparis and improvements to Burial Ground at Melpatti Ponnappan Street in Dn.70, U-16, Zone-6.",Own Sources,6,2019-20,2021-22 NF/2019-20/12588,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,500000,"REPAIRS AND IMPROVEMENTS TO THE DIVISION OFFICE - 70 BUILDING AT BHARATHI MAIN ROAD IN DN-70, UNIT-16, ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/14220,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,992320,"New Gasifier Unit And Burner Assembly at M.P.M.Street in div-70,unit-16,zone-6.",Own Sources,6,2019-20,2021-22 NF/2019-20/1534,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN DRBCC PLAY GROUND M.H.ROAD IN DN-70,UNIT-16,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1762,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,214000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-70,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1804,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,624000,"Proposed construction of well ring for micro compost yard at various locations in Div-70,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2754,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,560000,"Providing Borewell Arrangements to Chennai Middle School at MH Road and Gokulam Street in Dn-70 , Un-16 , Z-6",Own Sources,6,2019-20,2020-21 NF/2019-20/2755,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,560000,"Providing Borewell Arrangements to Chennai Primary School at School Road and Chennai Girls High. Sec. School at MH Road in Dn-70 , Un-16 , Z-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3077,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,722000,"Repairs and improvements to the Ganeshapuram Subway Pump room , Well and Toilet at Dr.Ambedkar college road in Dn.70,Unit-16,Z-06.",Own Sources,6,2019-20,2020-21 NF/2019-20/3111,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,22000,"Improvements to Centremedian at Perambur high road ( North) in Div-70,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3173,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,244000,"New Proposed construction of Shruddding Machine at DRBBC School Opposite Ground in Div-70, Unit-16, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/3637,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,1450000,"Construction of Composting Yard at inside the campus of the Mel patti ponnapan street Burial Ground Div-70,Unit-16,Zone-6",Grants,6,2019-20,2019-20 NF/2019-20/3638,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,1450000,"Construction of Composting Yard Tank link road Div-70,Unit-16,Zone-6",Grants,6,2019-20,2019-20 NF/2019-20/4106,Buildings,Completed,NF-THIRU-VI-KA NAGAR,70,1014000,"Construction of sump,bore and R O plant and Rain Water Harvesting at lorry shed in Perambur High Road , Jamaliya in dn-71, unit-16, zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/6947,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,1671000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT ANATHAVELU STREET, PATEL ROAD, SUBRAMANI STREET AND VARIOUS STREETS IN DIVISION-70, UNIT-16, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6952,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,1621000,"Desilting and repair works in strom water drain at Perambur High Road(North), Dr.Ambedkar College Road, Melpatti Poonnappan street and various street in Dn-70,Unit-16,Zone-06.",Own Sources,6,2019-20,2019-20 NF/2019-20/7636,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,334000,"Annual Maintanence of Park at Perambur high road (FOR ONE YEAR) in Dn 70,Unit 16, Zone 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/7638,Parks,Completed,NF-THIRU-VI-KA NAGAR,70,1950000,"Annual Maintanence of Murasolimaran park (North) at Perambur High road (North) (FOR ONE YEAR) in Dn 70,Unit 16, Zone 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/8110,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,463000,"Attending Potholes & Patchwork at patel road, vadivel street, jamalaya main road and various streets in Div-70,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/8666,Roads,Completed,NF-THIRU-VI-KA NAGAR,70,1073000,"CMWSSB Road cut at govindhan street, elighan street and poleriamman kovil street in div 70,uint-16,zone-6.",Deposit Works,6,2019-20,2020-21 P/2019-20/7399,Parks,Completed,P-Parks and Playfields,70,770000,CONSTRUCTION OF VOLLEY BALL COURT IN CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT MH ROAD IN DN 70 ZONE -6,Grants,6,2019-20,2020-21 L/2019-20/13137,Electrical,Completed,L-Electrical,71,4860200,Provision of 64 nos of 8mtr GI Lamp post with single straight bracket and Laying of 2368 mtrs of 31/2 x25 sq.mm.UG Cable at existing double centre median portion and removal of 52 nos of old rust eatened lamp post at K.H.Road of dn.71 in zone-6.,Own Sources,6,2019-20,2020-21 NF/2019-20/10137,Playfields,Completed,NF-THIRU-VI-KA NAGAR,71,940000,"PROVIDING GYM MATERIALS IN BRISLEE NAGAR, SETTLEMENT AREA EXISTING GYM HALL IN DN-71, UNIT-17, ZONE-6",MLACDS,6,2019-20,2020-21 NF/2019-20/10801,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,436000,"Providing Water Supply Arrangements to Cattle Dipot at Chandrayogi Samathi Street in Dn-71 , Un-16 , Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/11746,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,142000,"Water supply arrangements to AE,CI and SI office at perambur high road south ,Jamalia,in dn-71,unit-16,zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1532,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,294000,"Proposed construction of Material Recovery Facility Centre in Rajiv Gandhi Park, Perambur High Road South in Division-71, Unit-17, Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/1759,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,67000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-71,UNIT-16, ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1805,Parks,Completed,NF-THIRU-VI-KA NAGAR,71,198000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-71,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2760,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,260000,"Providing Borewell Arrangements to Chennai Middle School at Ekangipuram in Dn-71 , Un-16 , Z-6",Own Sources,6,2019-20,2019-20 NF/2019-20/2762,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,560000,"Providing Borewell Arrangements to Chennai Primary School at Arunthathipalayam and Mangalapuram in Dn-71 , Un-16 , Z-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3112,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,274000,"Improvements to Centremedian at Perambur high road ( South) in Div-71,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/6954,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,71,1432000,"Desilting and minor repair works at Krishnadoss main road,Tank bund road,Semathamman colony and various streets in Dn-71,Unit-16,Zone-06.",Own Sources,6,2019-20,2019-20 NF/2019-20/8112,Roads,Completed,NF-THIRU-VI-KA NAGAR,71,138000,"Attending Potholes & Patchwork at Tank bunk road,krishnadass street and various streets in Div-71 ,Unit-16,Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/8658,Buildings,Completed,NF-THIRU-VI-KA NAGAR,71,368000,"Providing water supply arrangements lorry depot AE office and drivers toilet in lorry shed at Perambur High road in dn -71,Unit-16,Zone-6.",Own Sources,6,2019-20,2019-20 BR/2019-20/4351,Road Cut,Completed,BR-Bus Route Roads,72,2420000,"Restoration of Roadcut made by TANTRANSCO at Basin Power House Road in Dn-72,Zone-6",Deposit Works,6,2019-20,2019-20 NF/2019-20/10134,Playfields,Completed,NF-THIRU-VI-KA NAGAR,72,940000,"PROVIDING GYM MATERIALS IN KANNIKAPURAM PLAY GROUND EXISTING GYM HALL IN DN-72, UNIT-17, ZONE-6",MLACDS,6,2019-20,2020-21 NF/2019-20/13702,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,698000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT NAGATHAMMAN KOIL 1ST STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13704,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,106000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT NAGATHAMMAN KOIL 2ND STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13705,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,67000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT NAGATHAMMAN KOIL 3RD STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13706,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,81000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT NAGATHAMMAN KOIL 4TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13707,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,44000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT NAGATHAMMAN KOIL 5TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13708,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,162191,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT THIRU-VI-KA NAGAR 5TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13709,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,240000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT THIRU-VI-KA NAGAR 6TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13710,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,167000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT THIRU-VI-KA NAGAR 7TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13711,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,208000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT THIRU-VI-KA NAGAR 8TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13712,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,409000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT THIRU-VI-KA NAGAR 9TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13713,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,105000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT THIRU-VI-KA NAGAR 4TH STREET IN DIV-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1526,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,294000,"Proposed construction of Material Recovery Facility in Kannikapuram Main Road in Division-72, Unit-17, Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/1760,Parks,Completed,NF-THIRU-VI-KA NAGAR,72,27000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/18002,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,731000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at V.O.C. Nagar main Road in Dn- 72, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/18003,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,2402000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Venkatesapuram new colony main road in Dn- 72, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/1803,Parks,Completed,NF-THIRU-VI-KA NAGAR,72,482000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-72,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2750,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,780000,"Providing of Bore Well Arrangements to Chennai Middle School at H & S Facory - 1 Nos. and Chennai Primary School, Thiru-vi-ka nagar - 2 Nos. in Dn.72, Unit-17, Zone - 6",Own Sources,6,2019-20,2019-20 NF/2019-20/3214,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT NEW VENKATESAPURAM COLONY IN DN.72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/6890,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,72,1299000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-72, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/7169,Electrical,Completed,NF-THIRU-VI-KA NAGAR,72,1100000,"Construction of Dining Hall Chennai Middle School at Narasima Nagar in Dn-72,Unit-17,Zone-6. (MLA FUND)",MLACDS,6,2019-20,2020-21 NF/2019-20/7810,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,1020000,"PROVIDING SECURITY ARRENGEMENTS AT SLAUGHTER HOUSE IN DN-72, UNIT-17, ZONE-6 FOR ONE YEAR (8NOS X 365 DAYS)",Own Sources,6,2019-20,2020-21 NF/2019-20/8042,Roads,Completed,NF-THIRU-VI-KA NAGAR,72,393000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT VEERASWAMY STREET, NEW THIRU-VI-KA NAGAR 4TH TO 9TH STREET, SATHIYAVANI MUTHU NAGAR 1,2,3 & 5TH STREET AND VARIOUS STREETS IN DIVISION-72, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/8892,Buildings,Completed,NF-THIRU-VI-KA NAGAR,72,2450000,"CONSTRUCTION OF VETERINARY DOCTOR OFFICE ROOM, CONSERVENCY INSPECTER ROOM, COMPOUND WALL AND WATER SUPPLY ARRANGEMENT WORKS AT SLAUGHTER HOUSE INNER SIDE IN DIVISION-72, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2020-21 BR/2019-20/0108,Road Cut,Completed,BR-Bus Route Roads,73,2345000,"Restoration of Roadcut made by TANGEDCO at Dr.Ambedkar College Road and Strahans Road in Dn-73 & 76, Zone-6",Deposit Works,6,2019-20,2019-20 BR/2019-20/4568,Roads,Completed,BR-Bus Route Roads,73,7997000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Dr. Ambedkar College Road(from the Jn of Stephonson Road to Ganesapuram Railway Subway) in Dn - 73 , Zone VI",Grants,6,2019-20,2020-21 BR/2019-20/4880,Roads,Completed,BR-Bus Route Roads,73,988000,"Partly relaying the road with BC after cold milling by paver finisher at Strahans Road in Dn-73 & 76, Zone - VI",Grants,6,2019-20,2020-21 BR/2019-20/4881,Roads,Completed,BR-Bus Route Roads,73,444000,"Partly relaying the road with BC after cold milling by paver finisher at Cooks Road in Dn-73 , Zone - VI",Grants,6,2019-20,2020-21 NF/2019-20/10135,Playfields,Completed,NF-THIRU-VI-KA NAGAR,73,940000,"PROVIDING GYM MATERIALS IN GREY NAGAR YMCA CORPORATION PLAYGROUND IN DN-73, UNIT-17, ZONE-6",MLACDS,6,2019-20,2020-21 NF/2019-20/10637,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,1350000,"Raising of Existing Compound Wall & Construction of New Compound Wall and Others improvements to NNMP Sheds Campus at Old Vazhima Nagar in Division-73, Unit-17, Zone - 6",Own Sources,6,2019-20,2020-21 NF/2019-20/11188,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,768000,"Construction of New Compound Wall and Others improvements to Chennai High School at Ammaiyammal Street, Pulianthope, Chennai- 600 012 in Division-73, Unit-17, Zone - 6",Own Sources,6,2019-20,2020-21 NF/2019-20/11526,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,1610000,"DEMOLITION OF CHENNAI HIGH SCHOOL, A-BLOCK DILAPIDATED EXISTING BUILDING AT COOKS ROAD IN IN DN - 73, UNIT - 17, ZONE - 6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12558,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,786000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at La Singh Street in Dn- 73, Unit-17, Zone - 6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12561,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,430000,"Relaying the CC Road along with traffic improvement work at Strahans Road 3rd Street & Cross Street in Dn-73, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12563,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,1003000,"Relaying the CC Road along with traffic improvement work at Strahans Road 5th Street in Dn-73, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12564,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,548000,"Relaying the CC Road along with traffic improvement work at New Ferrance Lanes (1 &3 Lanes) South Side in Dn-73, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12565,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,190000,"Relaying the CC Road along with traffic improvement work at New Ferrance Lanes (1 &3 Lanes) North Side in Dn 73, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12566,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,186000,"Relaying the CC Road along with traffic improvement work at Kutty Thambiran 1st lane in Dn-73, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12567,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,156000,"Relaying the CC Road along with traffic improvement work at Kutty Thambiran 2nd lane in Dn-73, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/14731,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,223500,"PROVIDING WATER SUPPLY ARRANGEMENT FOR PUBLIC CONVENIENCE AT OTTERI NALLUH NEAR IN DIVISION-73, UNIT-17, ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/14732,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,223500,"PROVIDING WATER SUPPLY ARRANGEMENT FOR DIVISION OFFICE AT NEW FERRANCE ROAD IN DIVISION-73, UNIT-17, ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/14733,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,53000,"PROVIDING AND LAYING OF INTERLOCKING BLOCKS FOR UPHC CAMPUS OLD ZONE-3, MLA OFFICE FRONT SIDE IN DIVISION 73, UNIT-17, ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/14734,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,1870000,"Providing water supply arrangements to Chennai Primary School and Other Improvements works to Chennai High School Campus at Cooks Road in Dn.73, Unit-17, Zone - 6",Own Sources,6,2019-20,2020-21 NF/2019-20/16170,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,534000,"LAYING OF CEMENT CONCRETE ROAD AT PADISONPURAM 1st , 4th, 5th and 6th lane IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16171,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,592000,"LAYING OF CEMENT CONCRETE ROAD AT PENSIONERS 1ST LANE IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16172,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,388000,"LAYING OF CEMENT CONCRETE ROAD AT PENSIONERS LANE M-L BLOCK IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16173,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,344000,"LAYING OF CEMENT CONCRETE ROAD AT PENSIONERS LANE B-J BLOCK IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16174,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,467000,"LAYING OF CEMENT CONCRETE ROAD AT PENSIONERS LANE I-H BLOCK IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16175,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,343000,"LAYING OF CEMENT CONCRETE ROAD AT PENSIONERS LANE G BLOCK IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16177,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,245000,"LAYING OF CEMENT CONCRETE ROAD AT New Parthasarathy Street IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1798,Parks,Completed,NF-THIRU-VI-KA NAGAR,73,340000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-73,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2733,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,781000,"Providing Borewell Arrangements to Chennai Primary School - 1No. and Chennai High School- 2 Nos. at Ammaiammal Street, Pulainthope, Chennai - 600 012 in Dn. 73, Unit-17, Zone - 6",Own Sources,6,2019-20,2019-20 NF/2019-20/2734,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,520000,"Providing Borewell Arrangements to Chennai Urudu Middle School - 2 Nos. at Mannarswamy Street, Pulainthope, Chennai - 600 012 in Dn. 73, Unit-17, Zone - 6",Own Sources,6,2019-20,2020-21 NF/2019-20/2736,Buildings,Completed,NF-THIRU-VI-KA NAGAR,73,260000,"Providing Borewell Arrangements to Chennai Middle School - 1 Nos. at Decoster Road and CHS Cooks road Pulainthope, in Dn. 73, Unit-17, Zone - 6",Own Sources,6,2019-20,2020-21 NF/2019-20/6887,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,1531000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-73, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6888,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,723000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN at BUS ROUTE ROAD IN DIVISION-73, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/8041,Roads,Completed,NF-THIRU-VI-KA NAGAR,73,780000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT OLD VAZHIMA NAGAR, BELLVIDDOR VILLAGE, TRHIRUVENKADASWAMY STREET, STEPHENSON RAOD, DR. AMBEDKAR COLLEGE ROAD AND VARIOUS STREETS IN DIVISION-73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 BR/2019-20/4879,Roads,Completed,BR-Bus Route Roads,74,1481000,"Partly relaying the road with BC after cold milling by paver finisher at Medavakkam Tank Road in Dn-74, Zone - VI",Grants,6,2019-20,2020-21 L/2019-20/9007,Electrical,Completed,L-Electrical,74,605300,"Removing and Refixing of 1Nos 20Mtr High mast at junction of Otteri link road and sspuram A block 1st street to Otteri dumping ground and Replacement of Accessories at 1Nos 16Mtr High Mast in Tana street & 1Nos 20Mtr High Mast in GKM Colony Burial ground respectively in Div-74, 75 & 65 In Zone-VI",Own Sources,6,2019-20,2020-21 NF/2019-20/13413,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,1150000,"CONSTRUCTION OF NEW TOILET AND WATER SUPPLY ARRANGEMENTS AT TROPICAL DRY EVER GREEN FOREST (HERBAL PARK) OTTERI IN.DIVISION-74, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13714,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,602000,"RELAYING THE CC ROAD ALONG WITH TRAFFIC IMPROVEMENT WORK AT SUBBRAYAN 4TH STEET 3RD LANE IN DIV-74, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13870,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,1060000,"PROVIDING PLAY APPARATUS, FRP BENCHES AND GREENERY AT TROPICAL DRY EVER GREEN FOREST (HERBAL PARK) OTTERI IN.DIVISION-74, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1528,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,294000,"Proposed construction of Material Recovery Facility in Pumping Station Raod in Division-74, Unit-17, Zone-6",Own Sources,6,2019-20,2019-20 NF/2019-20/16186,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,402000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at MEDAVAKKAM 1ST STREET in Dn- 74, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/1763,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,67000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-74,UNIT-17,ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/1793,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,927000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-74,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2749,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,740000,"Providing of Bore Well Arrangements to Chennai Primary School at Chinnababu Street - 2 Nos. and Chennai High School, Nammalvar Street - 1 Nos. in Dn.74, Unit-17, Zone - 6",Own Sources,6,2019-20,2020-21 NF/2019-20/3215,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT PUMPING STATION ROAD IN DN.74, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/3216,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT BARRACK ROAD IN DN.74, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/6891,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,1116000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-74, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6892,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,678000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN at BUS ROUTE ROAD IN DIVISION-74, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/7391,Parks,Completed,NF-THIRU-VI-KA NAGAR,74,4938000,"Maintenance of Herbal Park for the period of one year by private agency in Dn. 74, Unit-17,Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/7802,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,510000,"PROVIDING SECURITY ARRENGEMENTS AT OTTERI DUMPING GROUND IN DN-74, UNIT-17, ZONE-6 FOR ONE YEAR (4NOS X 365 DAYS)",Own Sources,6,2019-20,2020-21 NF/2019-20/8040,Roads,Completed,NF-THIRU-VI-KA NAGAR,74,184000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT CHINNA BABU STREET, TEMPLE ROAD, SVM NAGAR AND VARIOUS STREETS IN DIVISION-74, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/10130,Playfields,Completed,NF-THIRU-VI-KA NAGAR,75,940000,"PROVIDING GYM MATERIALS IN S.S PURAM A BLOCK EXISTING GYM HALL IN DN-75, UNIT-17, ZONE-6",MLACDS,6,2019-20,2020-21 NF/2019-20/10133,Playfields,Completed,NF-THIRU-VI-KA NAGAR,75,940000,"PROVIDING GYM MATERIALS IN S.S PURAM B BLOCK, 4Tth CROSS STREET EXISTING GYM HALL IN DN-75, UNIT-17, ZONE-6",MLACDS,6,2019-20,2020-21 NF/2019-20/11245,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,774000,"Improvements to Chennai Middle School at Venkatammal samathi Street in Division 75, Unit 17, Zone 6",Own Sources,6,2019-20,2020-21 NF/2019-20/11247,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,967000,"Improvements to Chennai Primary School at Chellapa Street in Division 75, Unit 17, Zone 6",Own Sources,6,2019-20,2020-21 NF/2019-20/14504,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,58000,"EXISTING COMPOST YARD AND NEW COMPOST YARD FLOOR RAISING WORK AT OTTERI DUMPING GROUND IN DN-75, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14505,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,205000,"IMPROVEMENTS TO ICDS AT VALLUVAN STREET IN DN-75, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14506,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,116000,"IMPROVEMENTS TO ICDS AT CHENNAI MEDDLE SCHOOL CAMPUS IN VENKATTAMMAL SAMATHI STREET IN DN-75, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14507,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,85000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL KITCHEN ROOM AND DRAINAGE LINE AT PADAVATTAMMAN KOIL STRRET IN DN-75 U-17, Z-6",Own Sources,6,2019-20,2020-21 NF/2019-20/14602,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,36000,"IMPROVEMENTS TO COMMUNITY CENTER DRAINAGE PIPE LINE WORK AT VENKADATHIRII STREET IN DN75, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1529,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,294000,"Proposed construction of Material Recovery Facility in Otteri Dumping Ground Campus in Division-75, Unit-17, Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16251,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,589000,"Improvements to the CC Road at Venkatdathiri street in Div-75,Unit-17,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16252,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,79000,"Improvements to the CC Road at Venkatammal Samathi Street in Div-75,Unit-17,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16253,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,509000,"Improvements to the CC Road at SS Puram B Block 6th street in Div-75,Unit-17,Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1764,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,27000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1787,Parks,Completed,NF-THIRU-VI-KA NAGAR,75,287000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-75,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3134,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,200000,"REPAIR AND IMPROVEMENT TO ICDS NO-416 AT CHELLAPPA STREET IN DN-75, U-17, Z-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/3217,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT OTTERI DUMPING GROUND IN DN.75, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/6895,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,401000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN IN DIVISION-75, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6896,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,967000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN IN DIVISION-75, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/8038,Roads,Completed,NF-THIRU-VI-KA NAGAR,75,203000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT NAKKIRAN STREET, KANNAPPAN STREET, NARAYANAN MAISTRY STREET, MOOKU CHETTY STREET AND VARIOUS STREETS IN DIVISION-75, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/10001,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,305000,"IMPROVEMENTS AND COLOUR WASHING TO RELIEF CENTER AT PERAMBUR BARRACKS ROAD IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/10132,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,66000,"IMPROVEMENTS TO COMPOUND WALL FOR KALAIGNAR KARUNANIDHI PARK AT BARRACKS ROAD IN DN-76,U-17,Z-6",Own Sources,6,2019-20,2020-21 NF/2019-20/10182,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,1000000,"DEMOLITION OF RELIEF CENTER , JE & SI OFFICE AT PERAMBUR BARRACKS ROAD IN DN - 76 , UN-17 , ZN-6",Own Sources,6,2019-20,2020-21 NF/2019-20/10411,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,59000,"IMPROVEMENTS TO C S PARK COMPOUND WALL AT C S GARDEN IN DN-76,U-17,Z-6",Own Sources,6,2019-20,2020-21 NF/2019-20/11117,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,587000,"REPAIR AND IMPROVEMENTS TO CHENNAI PRIMARY SCHOOL NO. 127 AT ANGALAMMAN KOIL STREET IN DN-76,UNIT-17,ZONE-6",Own Sources,6,2019-20,2021-22 NF/2019-20/12746,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,511000,"Relaying the CC Road along with traffic improvement work at Angalamman Koil Street in Dn-76,Un-17 Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/12747,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,934000,"Relaying the CC Road along with traffic improvement work at Yacob Garden Street in Dn-76,Un-17 Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/12748,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,997000,"Relaying the CC Road along with traffic improvement work at Yacob Garden Lane in Dn-76,Un-17 Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/13560,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,436000,"WATER SUPPLY ARRANGEMENT TO KALAIGNAR KARUNANITHI PARK AT PERAMBUR BARRACKS ROAD IN DIVISON 76, UNIT - 17, ZONE - 6",Own Sources,6,2019-20,2021-22 NF/2019-20/14498,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,70000,"DISMANTLING AND RECONSTRUCTION OF DILAPLATED COMPOUND WALL AT AE OFFICE & CI OFFICE AT CS NAGAR PARK STREET, PATTALAM, IN DN-76,UNIT-16,ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/1531,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,294000,"Proposed construction of Material Recovery Facility in Division Office Campus in Division-76, Unit-17, Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16240,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,955000,"Improvements to the BT Road at ANGALAMMAN KOIL STREET in Div-76,Unit-17,Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/16242,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,935000,"Improvements to the BT Road at Sachidanandam street from Perambur Barracks Road to Ramanujam Garden Street Junction End in Div-76,Unit-17,Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/16247,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,536000,"Improvements to the BT Road at Sachidanandam street from New Street to Strahans Road in Div-76,Unit-17,Zone-6",Own Sources,6,2019-20,2021-22 NF/2019-20/1766,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,40500,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/1785,Parks,Completed,NF-THIRU-VI-KA NAGAR,76,554000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-76,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2745,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,601000,"Providing of Bore Well Arrangements to Chennai Middle School at Angalamman Koil Street - 1 Nos. and Chennai High School, Strahans Road - 1 Nos. in Dn.76, Unit-17, Zone - 6",Own Sources,6,2019-20,2019-20 NF/2019-20/3199,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT NEW FARRANCE ROAD IN DN.73, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/3746,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,750000,"Repair and improvements to Sathya ammaiyar memorial orphanagae at sachidanandan street in dn-76,unit-17,zone-6",Deposit Works,6,2019-20,2020-21 NF/2019-20/6902,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,240000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN at BUS ROUTE ROAD IN DIVISION-76, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6903,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,1172000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-76, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/7868,Buildings,Completed,NF-THIRU-VI-KA NAGAR,76,620000,"Demolition of Old Gym Building ,Shopping complex, Aavin booth and Public convenience at Strahans road in Dn-76 , Unit-17 , Zone-6",Own Sources,6,2019-20,2020-21 NF/2019-20/8036,Roads,Completed,NF-THIRU-VI-KA NAGAR,76,160000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT SACHIDHANANDHAM STREET, BARRACKS GATE ROAD GOODPET PALLAM 1ST STREET AND VARIOUS STREETS IN DIVISION-76, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/9048,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,787000,"MAINTENANCE AND OPERATION OF WATER TREATMENT PLANT (AMMA KUDINEER) AT CHENNAI HIGH SCHOOL AT STRAHANS ROAD IN DN-76, UNIT-17, ZONE-06",Own Sources,6,2019-20,2020-21 BR/2019-20/4348,Road Cut,Completed,BR-Bus Route Roads,77,1710000,"Restoration of Roadcut made by TANTRANSCO at Demellows Road in Dn-77, Zone -6",Deposit Works,6,2019-20,2019-20 BR/2019-20/4353,Road Cut,Completed,BR-Bus Route Roads,77,2770000,"Restoration of Roadcut Made by TRANTRANSCO at Basin Elephant Gate Road in Dn-77, Zone -6",Deposit Works,6,2019-20,2020-21 BR/2019-20/4884,Roads,Completed,BR-Bus Route Roads,77,1174000,Partly relaying the road with BC after cold milling by paver finisher at Basin Elephant Gate Road in Dn-77 Zone - VI,Grants,6,2019-20,2020-21 BR/2019-20/4892,Roads,Completed,BR-Bus Route Roads,77,1174000,Partly relaying the road with BC after cold milling by paver finisher at Pulianthope High Road in Dn-77 Zone - VI,Grants,6,2019-20,2020-21 NF/2019-20/11681,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,83000,"REPAIR AND IMPROVEMENTS TO MULTIPURPOSE HALL AT OLD SLATTER HOUSE ROAD AND E-SEVA BUILDING AT SIVAROW ROAD IN DN-77, U-17, Z-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/11683,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,337000,"REPAIR AND IMPROVEMENT TO PATCH WORK VARIOUS STREETS IN DN-77, U-17, Z-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/11684,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,80000,"REPAIR AND IMPROVEMENT TO PC AT PULIANTHOPPU 4TH STREETS IN DN-77, U-17, Z-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12733,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1686000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Siva rao road (& Sundarapuram 1st main road ) in Dn- 77, Unit-17, Zone - 6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12736,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,217000,"Relaying RMC M30 Grade concrete road at Asirvathapuram 4th Street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12737,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,195000,"Relaying RMC M30 Grade concrete road at Asirvadhapuram 6th Street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12738,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,195000,"Relaying RMC M30 Grade concrete road at Gurusamy nagar 7th Street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12739,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,195000,"Relaying RMC M30 Grade concrete road at Gurusamy nagar 6th Street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12740,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,414000,"Relaying RMC M30 Grade concrete road at Gurusamy nagar 5th street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12741,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,196000,"Relaying RMC M30 Grade concrete at Asirvathapuram 1st street in Dn-77, Unit 17, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12757,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,195000,"Relaying RMC M30 Grade Concrete at Gurusamy nagar 4th street in Dn-77, Unit 17, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12758,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,195000,"Relaying RMC M30 Grade Concrete road at Gurusamy nagar 3rd street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12759,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,195000,"Relaing RMC M30 Grade concrete road at Gurusamy nagar 1st street in Dn-77, Unit 17, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12760,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,126000,"Relaying RMC M30 Grade concrete road at Sivarajapuram 5th street in Dn-77, Unit 17 Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12761,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,190000,"Relaying RMC M30 Grade Cement Concrete road at Sivarajapuram 4th street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12762,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,212000,"Relaying RMC M30 Grade cement concrete road at Sivarajapuram 3rd Street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12763,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,226000,"Relaying RMC M30 Grade cement concrete road at Sivarajapuram 2nd street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12764,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,217000,"Relaying RMC M30 Grade Cement Concrete road at Gurusamy nagar 10th Street in Dn-77, Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/12765,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,194000,"Relaying RMC M30 Grade Cement Concrete road at Asirvathapuram 5th street in Dn-77, Unit 17 Zone-6.",Own Sources,6,2019-20,2020-21 NF/2019-20/16149,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,582000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Kanagaraya Thootam in Dn- 77, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/16151,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,1267000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Old Slaughter House Road in Dn- 77, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/16164,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,989000,"LAYING OF CEMENT CONCRETE ROAD AT CORPORATION 1 TO 4 LANES IN DN.77, UNIT-77, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16165,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,369000,"LAYING OF CEMENT CONCRETE ROAD AT SUNDARAPURAM 3RD STREET IN DN.77, UNIT-77, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16168,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,462000,"LAYING OF CEMENT CONCRETE ROAD AT MOSQUE STREET IN DN.77, UNIT-77, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1773,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,53000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-77,UNIT-17,ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/1774,Parks,Completed,NF-THIRU-VI-KA NAGAR,77,429000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-77,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/3179,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,200000,"Improvements work to ICDS at Bogipalayam 1st main road in Division 77, Unit 17, Zone 6",Own Sources,6,2019-20,2020-21 NF/2019-20/3218,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT BASIN ELEPHANT GATE ROAD IN DN.77, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/4279,Buildings,Completed,NF-THIRU-VI-KA NAGAR,77,1707000,"Improvement works to TB Hospital at Pulianthope High road, Division 77, Unit 17, Zone 6",Own Sources,6,2019-20,2020-21 NF/2019-20/6900,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,1317000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN IN DIVISION-77, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6901,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,1675000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN IN DIVISION-77, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/8035,Roads,Completed,NF-THIRU-VI-KA NAGAR,77,420000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT KATTUR NALLAMUTHU STREET, PULIANTHOPE 1ST STREET, TK MUDHALI STREET AND VARIOUS STREETS IN DIVISION-77, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 B/2019-20/5908,Buildings,Completed,B-Buildings,78,9000000,"ADDITIONAL CONSTRUCTION OF SECOND FLOOR AND THIRD FLOOR (PART) FOR COMMUNITY CENTRE AT SATCHIDANANDAM SECOND STREET , KOSAPET IN DN-78, ZONE-06",MLACDS,6,2019-20,2021-22 BR/2019-20/4886,Roads,Completed,BR-Bus Route Roads,78,494000,Partly relaying the road with BC after cold milling by paver finisher at Choolai High Road in Dn-78 Zone - VI,Grants,6,2019-20,2020-21 NF/2019-20/11186,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,977000,"Colour Washing and other Improvements work to Chennai Middle School Building at Tana Street in Division - 78, Unit-17, Zone - 6",Own Sources,6,2019-20,2020-21 NF/2019-20/12555,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,2722000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Subbanaidu Street in Dn- 78, Unit-17, Zone - 6.",Own Sources,6,2019-20,2020-21 NF/2019-20/15075,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,213000,"PROVIDING WATER SUPPLY ARRANGEMENTS FOR LADIES GYM AT ARUNACHALAM STREET IN DN-78, UNIT-17, ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/15076,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,55000,"IMPROVEMENTS TO SANITARY INSPECTER ROOM COLOUR WASH AND TRANSFORMER INNER SIDE FILLING WORK AT ANGALAMMAN KOIL STREET IN DN-78, UNIT-17, ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/15078,Playfields,Completed,NF-THIRU-VI-KA NAGAR,78,232000,"IMPROVEMENTS TO CHILDREN PLAY GROUND AT ARUNACHALAM STREET IN DN-78, UNIT-17, ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/16256,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1520000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Kuzhanthai Velu st in Dn- 78, Unit-17, Zone - 6",Own Sources,6,2019-20,2021-22 NF/2019-20/16257,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1137000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at V.V KOIL st in Dn- 78, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/16258,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,1315000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Mooku chetty st in Dn- 78, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/16262,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,817000,"IRelaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at KANDHASAMY KOIL St in Dn- 78, Unit-17, Zone - 6.",Own Sources,6,2019-20,2021-22 NF/2019-20/16265,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,220000,"LAYING OF CEMENT ROAD AT KURAVAN KULAM MAIN ST 2ND LANE IN DN78,UNIT-17 ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16266,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,209000,"LAYING OF CEMENT ROAD AT KURAVAN KULAM MAIN ST 1ST LANE IN DN-78, UNIT-17 ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16267,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,366000,"LAYING OF CEMENT ROAD AT KURAVAN KULAM MAIN ST 3RD LANE IN DN78, UNIT-17 ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16268,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,98000,"LAYING OF CEMENT ROAD AT ERRAN STREET LANE IN DN78, UNIT-17 ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/16269,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,86000,"LAYING OF CEMENT CONCRETE ROAD AT ARUNACHALAM STREET LANE IN DN.78, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/1767,Parks,Completed,NF-THIRU-VI-KA NAGAR,78,27000,"SUPPLYING AND FIXING OF BAMBOO MULCH PIT FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-78,UNIT-17,ZONE-06",Own Sources,6,2019-20,2020-21 NF/2019-20/1779,Parks,Completed,NF-THIRU-VI-KA NAGAR,78,251000,"PROPOSED CONSTRUCTION OF WELL RING FOR MICRO COMPOST YARD AT VARIOUS LOCATIONS IN DN-78,UNIT-17,ZONE-06",Own Sources,6,2019-20,2019-20 NF/2019-20/2740,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,960000,"Providing of Bore Well Arrangements to Chennai MiddleSchool at Tana Street - 2 Nos, Chennai Middle School at V V Koil Street - 1 Nos. and Chennai Middle School at KK Lane - 1 Nos. in Dn.78, Unit-17, Zone - 6",Own Sources,6,2019-20,2019-20 NF/2019-20/3196,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT MANICKAM STREET IN DN.78, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3197,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT ASTAPUJAM ROAD IN DN.78, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3198,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT CHOKKAVEL SUBRAMANIYA SWSAMY KOIL STREET IN DN.78, UNIT-17, ZONE-6",Own Sources,6,2019-20,2020-21 NF/2019-20/3205,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT PERAMBUR BARRACKS ROAD IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/3213,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,244000,"CONSTRUCTION OF MS SHEET SHED FOR PLACING OF SHREDDING MACHINE IN COMPOST YARD AT C S NAGAR PARK STREET IN DN.76, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 NF/2019-20/6821,Buildings,Completed,NF-THIRU-VI-KA NAGAR,78,440000,"Dismantling of Existing Compound Wall and Constructions of New Compound Wall and Others Improvements to Chennai Middle School at Erran Street in Division-78, Unit-17, Zone - 6",Own Sources,6,2019-20,2019-20 NF/2019-20/6882,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,340000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN at BUS ROUTE ROAD IN DIVISION-78, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/6883,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,602000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-78, UNIT-17, ZONE-VI",Own Sources,6,2019-20,2019-20 NF/2019-20/8033,Roads,Completed,NF-THIRU-VI-KA NAGAR,78,410000,"ATTENDING THE POTHOLES AND DAMAGED SURFACE AT ARUNACHALAM STREET, MOOKU STREET, PERAMBUR BARRACKS ROAD, VALLAM BANGARU STREET AND VARIOUS STREETS IN DIVISION-78, UNIT-17, ZONE-6",Own Sources,6,2019-20,2019-20 L/2019-20/5160,Electrical,Completed,L-Electrical,79,163000,"Provision of 80 nos plain cement concreate pedestal, 16 nos Erection of Pillar box raising at Various streets In Div-79 and 82, Ambattur, Zone-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/11771,Roads,Completed,NG-AMBATTUR,79,578000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT MGR STREET IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11773,Roads,Completed,NG-AMBATTUR,79,990000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SAMICHETTY STREET IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11774,Roads,Completed,NG-AMBATTUR,79,1449000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT CHURCH STREET IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/14066,Storm Water Drain,Completed,NG-AMBATTUR,79,217000,"Construction of Culvert at Lenin nagar 3rd main road Division-79, Unit-18, Zone-7",Own Sources,7,2019-20,2021-22 NG/2019-20/17454,Roads,Completed,NG-AMBATTUR,79,288000,"LAYING CEMENT CONCRETE ROAD AT MPC STREET IN DIVISION - 79, UNIT-18,ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/1954,Parks,Completed,NG-AMBATTUR,79,296000,"SUPPLYING AND ERECTING WELL RING AT VARIOUS PLACES IN DIVISION-79,80,81,82 & 83 IN UNIT-18, ZONE-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/1962,Parks,Completed,NG-AMBATTUR,79,279000,"SUPPLYING AND ERECTING MULCH PIT AT VARIOUS PLACES IN DIVISION-79,80,81,82 & 83 UNIT-18, ZONE-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/1964,Parks,Completed,NG-AMBATTUR,79,432000,"SUPPLYING AND ERECTING WELL RING AT VARIOUS PARKS IN DIVISION-79,80,81,82 & 83 IN UNIT-18, ZONE-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/2469,Buildings,Completed,NG-AMBATTUR,79,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT ORAGADAM BURIAL GROUND IN DIVISION-79,UNIT-18,ZONE-7 (AMBATTUR)",Own Sources,7,2019-20,2019-20 NG/2019-20/4525,Buildings,Completed,NG-AMBATTUR,79,3455000,"Proposed Construction Of Micro Composting Center ( MCC ) at Oragadam Burial Ground In Div- 79, Unit-18, Zone-7",Own Sources,7,2019-20,2021-22 NG/2019-20/5999,Storm Water Drain,Completed,NG-AMBATTUR,79,147000,"Desillting of Strom water drains in Division-79,Unit-18,Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/7256,Buildings,Completed,NG-AMBATTUR,79,300000,"RAINWATER HARWESTING OPEN WELL IMPROVEMENT WORK AT COMMUNITY HALL ( SUB REGISTER OFFICE ) IN DIVISION- 79, UNIT-18, ZONE-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/7258,Buildings,Completed,NG-AMBATTUR,79,260000,"RAINWATER HARWESTING OPEN WELL IMPROVEMENT WORK AT ORAGADAM KALAIVANAR STREET NEAR ANGANVADI IN DIVISION- 79, UNIT-18, ZONE-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/8223,Roads,Completed,NG-AMBATTUR,79,1700000,"Attending Pot Holes and Patch work at various streets in Division - 79,80,81,82 & 83, Unit -18, Zone - VII.",Own Sources,7,2019-20,2020-21 NG/2019-20/9394,Parks,Completed,NG-AMBATTUR,79,450000,"Annual Maintenance of GCC Parks for One Year at Lakshmiamman Nagar Park in Division-79, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9395,Parks,Completed,NG-AMBATTUR,79,242000,"Annual Maintenance of GCC Parks for One Year at Ram Nagar Park in Division-79, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9396,Parks,Completed,NG-AMBATTUR,79,243000,"Annual Maintenance of GCC Parks for One Year at Lenin Nagar Park in Division-79, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9397,Parks,Completed,NG-AMBATTUR,79,250000,"Annual Maintenance of GCC Parks for One Year at Gandhi Nagar Park in Division-79, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9420,Roads,Completed,NG-AMBATTUR,79,1562000,"LAYING CEMENT CONCRETE ROAD AT RAJARAJAN STREET IN DIVISION - 79, UNIT-18,ZONE-7",Own Sources,7,2019-20,2020-21 L/2019-20/5438,Electrical,Completed,L-Electrical,80,2860700,"Erection of 60 nos 6 mtr Zinc galvanised lamp post With Straight Bracket , with 40 watts LED fittings & 5 Nos 6 mtr Zinc galvanised lamp post With Arche Bracket , with 90 watts LED fittings ,at various location In div 80 & 91 In banu nagar Section , Zone-7",Grants,7,2019-20,2020-21 NG/2019-20/16345,Roads,Completed,NG-AMBATTUR,80,2228000,"RELAYING THE BT SURFACE ROAD AT KVK SWAMY STREET PUDUR IN DIVISION- 80, UNIT-18, ZONE-7 IN DIVISON-80, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/2485,Buildings,Completed,NG-AMBATTUR,80,286000,"IMPROVEMENT WORK AT RRC FOR MATERIAL RECOVERY FACILITY AT DIVISION OFFICE -80 IN DIVISION-80,UNIT-18,ZONE-7 (AMBATTUR)",Own Sources,7,2019-20,2020-21 NG/2019-20/2944,Buildings,Completed,NG-AMBATTUR,80,280000,"IMPROVEMENT WORKS TO BHARATHI NAGAR PARK IN DIVISION-80, UNIT-18, ZONE-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/2945,Buildings,Completed,NG-AMBATTUR,80,1130000,"IMPROVEMENT AND MAINTENANCE WORK AT THANGAL ERI IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/2946,Buildings,Completed,NG-AMBATTUR,80,950000,"IMPROVEMENT AND MAINTENANCE WORK AT UPHC BUILDING IN DIVISION-80, UNIT-18, ZONE-VII ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/2947,Buildings,Completed,NG-AMBATTUR,80,540000,"IMPROVEMENT AND MAINTENANCE WORK AT DIVISION OFFICE IN DIVISION-80, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/5980,Buildings,Completed,NG-AMBATTUR,80,1490000,"DE-SILTING THE EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS and Repair work of SWD and Side Drains at indra gandhi , vageshwari amman, pudur and thiruvalluvar street IN DIVISION-80,UNIT-18, ZONE-7",Own Sources,7,2019-20,2019-20 NG/2019-20/9387,Parks,Completed,NG-AMBATTUR,80,1621000,ANNUAL MAINTENANCE FOR THANGAL ERI PARK IN DIVISION 80 UNIT 18 ZONE 7,Own Sources,7,2019-20,2020-21 NG/2019-20/9388,Parks,Completed,NG-AMBATTUR,80,240000,ANNUAL MAINTENANCE FOR BHARATHI NAGAR PARK IN DIVISION 80 UNIT 18 ZONE 7,Own Sources,7,2019-20,2020-21 L/2019-20/5264,Electrical,Completed,L-Electrical,81,198700,"Proposal for removal and refixing of 17 nos of Kiosk Pillar Boxes from the Ground Level at various location in Division 81,86 in Zone VII",Own Sources,7,2019-20,2020-21 NG/2019-20/11278,Roads,Completed,NG-AMBATTUR,81,349000,"RELAYING THE BT SURFACE ROAD AT MAJOR HUSSAIN STREET IN DIVISION:81,UNIT-18,ZONE-VII.",Own Sources,7,2019-20,2020-21 NG/2019-20/2549,Buildings,Completed,NG-AMBATTUR,81,200000,"IMPROVEMENT AND MAINTENANCE WORKS AT CHOLAPURAM ICDS IN DIVISION-81, UNIT-18, ZONE-VII.",Own Sources,7,2019-20,2019-20 NG/2019-20/4512,Buildings,Completed,NG-AMBATTUR,81,1057000,"Desilting and Minor repair works to Storm water Drain in Division-81, Unit-18, Zone-7(IRR-2)",Own Sources,7,2019-20,2019-20 NG/2019-20/4972,Roads,Completed,NG-AMBATTUR,81,269000,"RELAYING THE ROAD AT PATTAMMAL CROSS STREET IN DIVISION-81, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/5998,Storm Water Drain,Completed,NG-AMBATTUR,81,930000,"Desilting and Minor repair works to Storm water Drain in Division-81, Unit-18, Zone-7 (BRR)",Own Sources,7,2019-20,2019-20 NG/2019-20/6746,Storm Water Drain,Completed,NG-AMBATTUR,81,1147000,"Desilting and Minor repair works to Storm water Drain in Division-81, Unit-18, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/7161,Roads,Completed,NG-AMBATTUR,81,1086000,"RELAYING THE ROAD AT EAST PARK STREET IN DIVISION-81, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/7210,Roads,Completed,NG-AMBATTUR,81,1167000,"RELAYING ROAD AT WEST PARK STREET IN DIVISION 81, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9460,Parks,Completed,NG-AMBATTUR,81,690000,"Annual maintenance of GCC parks for one year at krishnapuram park in Dn-81, Unit-18, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9463,Parks,Completed,NG-AMBATTUR,81,769000,"ANNUAL MAINTENANCE FOR THIRUVENGADAM NAGAR PARK (PER YEAR) IN DIV-81, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9464,Parks,Completed,NG-AMBATTUR,81,691000,"ANNUAL MAINTENANCE FOR SECRETRIATE COLONY PARK (PER YEAR) IN DIV-81, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11896,Roads,Completed,NG-AMBATTUR,82,2363000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT SHRI CITY IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11897,Roads,Completed,NG-AMBATTUR,82,1218000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT HAZI NAGAR 1ST STREET IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11898,Roads,Completed,NG-AMBATTUR,82,762000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT MUTHAMIZH NAGAR 13TH STREET IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11899,Roads,Completed,NG-AMBATTUR,82,974000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT MOOGAMBIGAI NAGAR 4TH STREET IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11900,Roads,Completed,NG-AMBATTUR,82,1628000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT MOOGAMBIGAI NAGAR 3RD STREET IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11901,Roads,Completed,NG-AMBATTUR,82,1212000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT West Balaji Nagar 3rd Main road IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11902,Roads,Completed,NG-AMBATTUR,82,1733000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT MUTHAMIZH NAGAR 15TH STREET IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11903,Roads,Completed,NG-AMBATTUR,82,880000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT MUTHAMIZH NAGAR 12TH STREET IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11904,Roads,Completed,NG-AMBATTUR,82,654000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT DTP COLONY CROSS STREET IN DIVISION- 82, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/16835,Buildings,Completed,NG-AMBATTUR,82,1226000,"Operation and maintenance for the 4th year period (2019-20) (RO/UV filtration) of 2000litres/hour capacity expandables to 4000litres/hour capacity (2000litres expandables increment of 2000litres/hours and at Munusamy Koil Street, Menambedu in Division-82,Unit-18,Zone-7.",Own Sources,7,2019-20,2021-22 NG/2019-20/2527,Buildings,Completed,NG-AMBATTUR,82,200000,"Repairs and Maintenance works to ICDS (AWC no.-33603150110) at Padasalai street,Kallikuppam in Division-82,Unit-18,Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/3747,Buildings,Completed,NG-AMBATTUR,82,1299000,"PROPOSED CONSTRUCTION OF CAM SHREDDER SHED AT MENAMBEDU BURIAL GROUND in Dn-82, Unit-18, Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/3764,Buildings,Completed,NG-AMBATTUR,82,2238000,"PROPOSED CONSTRUCTION OF MICRO COMPOSTING CENTRE (MCC) AT MENAMBEDU BURIAL GROUND IN DN-82,UNIT-18,ZONE-7",Own Sources,7,2019-20,2019-20 NG/2019-20/3824,Buildings,Completed,NG-AMBATTUR,82,935000,"Operation and Annual Maintanence of ETP for 10 Months and repair works to Existing ETP of Slaughter house at Madhanakuppam in Div-82, Unit-18, Zone-7",Own Sources,7,2019-20,2021-22 NG/2019-20/5991,Storm Water Drain,Completed,NG-AMBATTUR,82,1110000,"Desillting of Strom water drains and providing minor repair works in Strom water drains of Division-82,Unit-18,Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/6000,Storm Water Drain,Completed,NG-AMBATTUR,82,481000,"Desillting of Strom water drains in Division-83,Unit-18,Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/9334,Buildings,Completed,NG-AMBATTUR,82,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY INSIDE SLAUGHTER HOUSE IN DIVISION-82,UNIT-18, ZONE-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9407,Parks,Completed,NG-AMBATTUR,82,616000,"Annual Maintenance of GCC Parks for One Year at Hindustan Colony Park in Division-82, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9493,Buildings,Completed,NG-AMBATTUR,82,3700000,"Proposed Construction Of Micro Compost Centre In Side Slaughter house with a Capacity of 2MT/day Including Bio-Shredder & Electrical Arrangement etc.,In Dn-82,Unit-18, Zone-7",Own Sources,7,2019-20,2020-21 L/2019-20/4402,Electrical,Completed,L-Electrical,83,3756400,"Provision of 26 nos of Zinc Galvanized lamp post with double bracket with 150 W LED fittings and 12 nos of single arch bracket with 150 W LED fittings at korrattur subway(Near Railway station) in Ward 83,Zone VII",Deposit Works,7,2019-20,2020-21 L/2019-20/5471,Electrical,Completed,L-Electrical,83,6674200,ESTIMATE FOR PROVISION OF 142 NOS OF 6 MTR LAMP POST WITH STRAIGHT BRACKET WITH HOT ZINC GALVANISING 40-50 WATTS LED FITTINGS AT VARIOUS LOCATION IN DN 83 ZONE VII AMBATTUR,Grants,7,2019-20,2020-21 NG/2019-20/11873,Roads,Completed,NG-AMBATTUR,83,446000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT ANNAI NAGAR MAIN ROAD IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11874,Roads,Completed,NG-AMBATTUR,83,1900000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT BAJANAI KOIL STREET IN THATHANKUPPAM IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11876,Roads,Completed,NG-AMBATTUR,83,1322000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT BALAJI NAGAR 1ST STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11877,Roads,Completed,NG-AMBATTUR,83,870000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD ATBALAJI NAGAR 2ND STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11878,Roads,Completed,NG-AMBATTUR,83,1174000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT BALAJI NAGAR 3RD STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11879,Roads,Completed,NG-AMBATTUR,83,2423000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT BALAJI STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11880,Roads,Completed,NG-AMBATTUR,83,1002000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT KAMAKODI STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11881,Roads,Completed,NG-AMBATTUR,83,1368000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT IYYAPPA NAGAR IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11882,Roads,Completed,NG-AMBATTUR,83,2821000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT MURUGAN KOIL STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11883,Roads,Completed,NG-AMBATTUR,83,1868000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT NORTH AVENUE ROAD IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11884,Roads,Completed,NG-AMBATTUR,83,1072000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT OLD POST OFFICE ROAD IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11885,Roads,Completed,NG-AMBATTUR,83,1187000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PADMAVATHI NAGAR MAIN ROAD IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11886,Roads,Completed,NG-AMBATTUR,83,1065000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PERUMAL KOIL STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11887,Roads,Completed,NG-AMBATTUR,83,229000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PILLAIYAR KOIL STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11888,Roads,Completed,NG-AMBATTUR,83,1546000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SIVALINGAPURAM IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11889,Roads,Completed,NG-AMBATTUR,83,623000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SRI RANGA GARDEN IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11890,Roads,Completed,NG-AMBATTUR,83,2121000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SRINIVASAPURAM 3RD CROSS STREET IN DIVISION-79, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11891,Roads,Completed,NG-AMBATTUR,83,856000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT SUBBULAKSHMI NAGAR 3RD STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11892,Roads,Completed,NG-AMBATTUR,83,1468000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD ATTNHB 38TH STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11893,Roads,Completed,NG-AMBATTUR,83,1145000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT TVS NAGAR 1ST MAIN ROAD IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11894,Roads,Completed,NG-AMBATTUR,83,1877000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT TVS NAGAR 2ND CROSS STREETIN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11895,Roads,Completed,NG-AMBATTUR,83,970000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD ATV.O.C STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/11905,Roads,Completed,NG-AMBATTUR,83,764000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT KANDIGAI CROSS STREET IN DIVISION- 83, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11907,Roads,Completed,NG-AMBATTUR,83,1319000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT SEEYATHAMMAN NAGAR IN DIVISION- 83, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11908,Roads,Completed,NG-AMBATTUR,83,1108000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT SANTHOSH NAGAR IN DIVISION- 83, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11909,Roads,Completed,NG-AMBATTUR,83,1537000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT SRI THIRUMAL NAGAR IN DIVISION- 83, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11910,Roads,Completed,NG-AMBATTUR,83,1102000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT VANASAKTHI NAGAR EXTENSION IN DIVISION- 83, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/12344,Storm Water Drain,Completed,NG-AMBATTUR,83,385000,"Formation Bund with Sand bags at North Avenue canal Zero Point in Div 83, Unit-18, Zone-7",Own Sources,7,2019-20,2021-22 NG/2019-20/12352,Roads,Completed,NG-AMBATTUR,83,778000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT ELLAIAMMAN NAGAR 6TH STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/12375,Roads,Completed,NG-AMBATTUR,83,1817000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT VANASAKTHI NAGAR MAIN ROAD IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/12376,Roads,Completed,NG-AMBATTUR,83,1166000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT VANASAKTHI NAGAR ANNEX IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/12378,Roads,Completed,NG-AMBATTUR,83,713000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PARTHASARATHY STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/12379,Roads,Completed,NG-AMBATTUR,83,350000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT PADMAVATHY NAGAR 1ST CROSS STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/12380,Roads,Completed,NG-AMBATTUR,83,816000,"STRENGTHENING AND RE LAYING THE BT SURFACE ROAD AT VANASAKTHI NAGAR 2ND STREET IN DIVISION-83, UNIT-18, ZONE-7 ( AMBATTUR )",Own Sources,7,2019-20,2020-21 NG/2019-20/12443,Roads,Completed,NG-AMBATTUR,83,3591000,"FORMING AND LAYING THE BT ROADS AT NETHAJI NAGAR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/12447,Roads,Completed,NG-AMBATTUR,83,4759000,"FORMING AND LAYING THE BT ROADS AT JASMINE NAAGR IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/12448,Roads,Completed,NG-AMBATTUR,83,1431700,"FORMING AND LAYING THE BT ROADS AT AMBEDKAR STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/12449,Roads,Completed,NG-AMBATTUR,83,576000,"FORMING AND LAYING THE BT ROADS AT KANDIGAI 8TH CROSS STREET (SANJEEVI GARDEN) IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/12450,Roads,Completed,NG-AMBATTUR,83,1010000,"FORMING AND LAYING THE BT ROADS AT TVS NAGAR 1ST CROSS STREET IN DIVISION-83 UNIT-18,ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/16289,Roads,Completed,NG-AMBATTUR,83,999000,"FORMING AND STRENGTHENING OF BT SURFACE ROAD AT RAJIV GANDHI NAGAR MAIN ROAD IN DIVISION- 83, UNIT-18, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/17263,Roads,Completed,NG-AMBATTUR,83,881000,"Relaying the existing Bituminous concrete road at New Pillayar Kovil Street in Division-86, Unit-19, Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/8102,Buildings,Completed,NG-AMBATTUR,83,747000,"REPAIR AND MAINTENANCE WORK TO UPHC BUILDING AT TNHB 32ND STREET IN DIVISION-83, UNIT-18, ZONE-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/9208,Buildings,Completed,NG-AMBATTUR,83,500000,"Annual Maintenance for COC Roads, Footpath, COC Building and SWD In Division- 83, Unit-18, Zone-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9398,Parks,Completed,NG-AMBATTUR,83,968000,"Annual Maintenance of GCC Parks for One Year at Thamarikulam Park in Division-83, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9399,Parks,Completed,NG-AMBATTUR,83,410000,"Annual Maintenance of GCC Parks for One Year at Sri Ranga Garden Park in Division-83, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9400,Parks,Completed,NG-AMBATTUR,83,1122000,"Annual Maintenance of GCC Parks for One Year at TNHB 61st Street Park in Division-83, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2021-22 NG/2019-20/9402,Parks,Completed,NG-AMBATTUR,83,410000,"Annual Maintenance of GCC Parks for One Year at Sastha Nagar Park in Division-83, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9403,Parks,Completed,NG-AMBATTUR,83,441000,"Annual Maintenance of GCC Parks for One Year at Subulakshmi Nagar Park in Division-83, Unit-18, Zone-VII(Per Year)",Own Sources,7,2019-20,2020-21 BR/2019-20/4893,Roads,Completed,BR-Bus Route Roads,84,1481000,"Partly relaying the road with BC after cold milling by paver finisher at East Avenue Road in Dn-84, Zone - VII",Grants,7,2019-20,2020-21 BR/2019-20/6078,Road Cut,Completed,BR-Bus Route Roads,84,1894000,"Restoration of roadcut made by CMWSSB at East Avenue road in Dn-84 , Zone 7",Deposit Works,7,2019-20,2019-20 NG/2019-20/10462,Roads,Completed,NG-AMBATTUR,84,91000,"Forming and Laying Cement concrete road at VOC Street in Division-84, Unit-19, Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/10785,Buildings,Completed,NG-AMBATTUR,84,170000,"Maintenance Works to the public convenience at Gangai Amman Koil Street, Periyar Nagar and EB Road in Div - 84, Unit-19, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/10796,Buildings,Completed,NG-AMBATTUR,84,317000,"IMPROVEMENTS TO JAMBUKESHWAR POND AT JAMBUKESHWAR NAGAR IN DIVISION-84, UNIT-19, ZONE-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/10819,Buildings,Completed,NG-AMBATTUR,84,163000,"Improvements to Well at the Kannagi Nagar Burial ground in Div - 84, Unit-19, Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/11740,Roads,Completed,NG-AMBATTUR,84,1471000,"Restoration of Road cut Made by CMWSSB work at TNHB 3rd Street,Kamarajar 3rd Street,Kamarajar 2nd Street,Kannagi Nagar 4th Street In Division-84,Unit-19,Zone-7",Deposit Works,7,2019-20,2020-21 NG/2019-20/11741,Road Cut,Completed,NG-AMBATTUR,84,2740000,"Restoration of Road cut made by CMWSSB work at Janagiraman Street,Kakkai Street,Kamarajar Nagar 1st street in Division-84, Unit-19,Zone-7",Deposit Works,7,2019-20,2020-21 NG/2019-20/11742,Road Cut,Completed,NG-AMBATTUR,84,1372000,"Restoration of road cut made by CMWSSB work at Bharathi Nagar,Kammalar Street,Piothiamman koil Street,Mariamman Koil Street in Division-84,Unit-19,Zone-7",Deposit Works,7,2019-20,2020-21 NG/2019-20/14190,Buildings,Completed,NG-AMBATTUR,84,399000,"Improvements to Playground and Construction of Toilet, Water Supply Arrangement and Play Apparatus at TNHB 2nd street play ground in Division -84, Unit - 19, Zone -7.",Own Sources,7,2019-20,2020-21 NG/2019-20/15182,Buildings,Completed,NG-AMBATTUR,84,234000,"Improvement Work to the Micro Composting Center at Kannagi Nagar in Div - 84, Unit-19, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/4105,Roads,Completed,NG-AMBATTUR,84,480000,"Improvements to Jambukeshwar Pond at Jambukeshwar nagar in Division -84, Unit - 19, Zone -7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6761,Roads,Completed,NG-AMBATTUR,84,1009000,"Repair and Desilting To The Existing Road Side Drain At Various Streets( Phase-I) In Division-84, Unit-19,Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6762,Roads,Completed,NG-AMBATTUR,84,1065000,"Repair and Desilting To The Existing Road Side Drain At Various Streets( Phase-2) In Division-84, Unit-19,Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6763,Roads,Completed,NG-AMBATTUR,84,1412000,"Repair and Desilting To The Existing Storm Water Drain At Various Streets In Division-84, Unit-19,Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/9535,Parks,Completed,NG-AMBATTUR,84,430000,"Annual Maintenance of GCC for One year at KR Nagar Park in Division-84, Unit-19, Zone-7 (Per one year)",Own Sources,7,2019-20,2021-22 NG/2019-20/9536,Parks,Completed,NG-AMBATTUR,84,433000,"Annual Maintenance of GCC for One year at TNHB 4TH STREET Park in Division-84, Unit-19, Zone-7 (Per one year)",Own Sources,7,2019-20,2021-22 NG/2019-20/9709,Roads,Completed,NG-AMBATTUR,84,779000,"Relaying a BT road at Gangai Amman Kovil Street in Div-84, Unit-19, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/10199,Buildings,Completed,NG-AMBATTUR,85,987000,"PROPOSED CONSTRUCTION OF BIOGAS PLANT ON HAVING A CAPACITY OF 500KGS AT AMMA UNAVAGAM, CTH ROAD IN DIVISION-85, UNIT-19, ZONE-7 (AMBATTUR)",Own Sources,7,2019-20,2021-22 NG/2019-20/11488,Buildings,Completed,NG-AMBATTUR,85,50000,"PRE MONSOON WORK BY PROVIDING SAND BAGS, WHEEL BARROW, MOTOR & POWER SAW REPAIR IN DIVISION-85, UNIT-19, ZONE-07.",Own Sources,7,2019-20,2020-21 NG/2019-20/17097,Buildings,Completed,NG-AMBATTUR,85,361000,"Annual Manintanance Work for GCC Building year of 2019-20 in Division-85, Unit-19, Zone-7 (ambattur).",Own Sources,7,2019-20,2020-21 NG/2019-20/1882,Buildings,Completed,NG-AMBATTUR,85,425500,"Providing Bore well with Water supply arrangements and Other maintainance Work for UPHC Building at Station Road in Division-85, Unit-19, Zone-7 (ambattur).",Own Sources,7,2019-20,2019-20 NG/2019-20/1883,Buildings,Completed,NG-AMBATTUR,85,698000,"Providing Bore well with Water supply arrangements and Other manitanance Work for Zonal Office in Division-85, Unit-19,Zone-7 (ambattur).",Own Sources,7,2019-20,2020-21 NG/2019-20/1913,Parks,Completed,NG-AMBATTUR,85,306000,"Providing Well Ring Pit At Various Streets In Division 84, 85, 86 & 88, Unit 19, Zone 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/4055,Parks,Completed,NG-AMBATTUR,85,620000,"Maintenance work for Hidhu Burial Ground at Vanagaram Road in Division-85, Unit-19, Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/4084,Buildings,Completed,NG-AMBATTUR,85,527000,"REPAIRS AND MAINTENANCE WORKS FOR DIVISION OFFICE BUILDING AT C.T.H ROAD IN DIVISION - 85, UNIT - 19, ZONE - 7.",Own Sources,7,2019-20,2020-21 NG/2019-20/4087,Parks,Completed,NG-AMBATTUR,85,694000,"Maintenance work for Christian And Jain Burial Ground at Vanagaram Road in Division-85, Unit-19, Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/5027,Storm Water Drain,Completed,NG-AMBATTUR,85,1839000,"Desilting and Repair work for Side Drain at Various Street in Kamarajapuram in Div-85, Unit-19, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/5108,Storm Water Drain,Completed,NG-AMBATTUR,85,377000,"Desiliting and Manhole door replacement of SWD (BRR) at various Street in Div-85, Unit-19, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6041,Storm Water Drain,Completed,NG-AMBATTUR,85,1757000,"Desilting and Repair work for Side Drain at various Streets Ramapuram in Div-85, Unit-19, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6043,Storm Water Drain,Completed,NG-AMBATTUR,85,1756000,"Desilting Side Drain at Ramapuram & Varadharajapuram various Streets and Repair work for Side Drain at Balaji Street & Pattaravakkam Road in Div-85, Unit-19, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/6045,Storm Water Drain,Completed,NG-AMBATTUR,85,826000,"Desilting Side Drain at various Streets in Teachers Colony & MKB Nagar and Repair work for Side Drain at Elango Street in Div-85, Unit-19, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/6046,Storm Water Drain,Completed,NG-AMBATTUR,85,1083000,"Desiliting and Repair work of Side Drain and Man Hole door Replacement of SWD at Various Street in in Mangalapuram, Div-85, Unit-19, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6052,Storm Water Drain,Completed,NG-AMBATTUR,85,995000,"Dismantling and Reconstruction Of Culvert across the side drain at Raman Street & Bazaar Road In Div-85, Unit-19, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/6053,Storm Water Drain,Completed,NG-AMBATTUR,85,1367000,"Dismantling and Reconstruction Of Culvert across the side drain at Kulakarai Street, Township Quarters, Kamarajar Street, Old ESI Road, Samdariya 3rd Street In Div-85, Unit-19,Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6054,Roads,Completed,NG-AMBATTUR,85,626000,"Restoration Of Road Cut Made by CMWSSB At Pillayar koil Street in Division 85, Unit 19, Zone 7.",Deposit Works,7,2019-20,2020-21 NG/2019-20/7182,Buildings,Completed,NG-AMBATTUR,85,76000,"New Drainage Connection for UPHC Building at Station Road in Division-85, Unit-19, Zone-7 (ambattur).",Own Sources,7,2019-20,2020-21 NG/2019-20/8015,Buildings,Completed,NG-AMBATTUR,85,1530000,"Repair work for Compound Wall, Bore well, painting and other Work for Dobi kana and ICDS at Vanchi Nagar in Division-85, Unit-19, Zone-7.",Own Sources,7,2019-20,2021-22 NG/2019-20/9393,Parks,Completed,NG-AMBATTUR,85,498000,"ANNUAL MAINTENANCE ESTIMATEOF GCC PARK FOR KOCHAR PARK AT CTH ROAD IN DIVISION 85, UNIT 19, ZONE 7.",Own Sources,7,2019-20,2021-22 NG/2019-20/9843,Parks,Completed,NG-AMBATTUR,85,700000,"ANNUAL MAINTENANCE ESTIMATE OF GCC PARK FOR RAIL VIHAR QUARTERS PARK AT CTH ROAD IN DIVISION 85, UNIT 19, ZONE 7.",Own Sources,7,2019-20,2020-21 BR/2019-20/12914,Road Cut,Completed,BR-Bus Route Roads,86,3100000,"Restoration of Road cut made by CMWSSB at ICF Colony Ayanambakkam Road (From the Jn of VOC st to SRS stores) in Dn-86, Zone 7",Deposit Works,7,2019-20,2020-21 BR/2019-20/12957,Road Cut,Completed,BR-Bus Route Roads,86,3200000,"Restoration of Road cut made by CMWSSB at ICF Colony Ayanambakkam Road (From the Jn of Ambattur Vanagaram road to VOC st ) in Dn-86, Zone 7",Deposit Works,7,2019-20,2020-21 BR/2019-20/4135,Road Cut,Completed,BR-Bus Route Roads,86,2400000,"Restroration of Roadcut made by CMWSSB at ICF colony Ayanambakkam road in DN-86, Zone 7(from the Jn of Bharathi street to G.P Natural Supermarket)",Deposit Works,7,2019-20,2019-20 BR/2019-20/6647,Road Cut,Completed,BR-Bus Route Roads,86,958000,"Restoration of roadcut made by CMWSSB at ICF colony Ayapakkam road(from the jn of GB market to the jn of Thirupathi kodai road)in Dn-86, Zone -7",Deposit Works,7,2019-20,2020-21 BR/2019-20/8202,Roads,Completed,BR-Bus Route Roads,86,1320000,"Restoration of Roadcut made by CMWSSB at ICF Colony Ayanambakkam Road in Dn-86, Zone-7",Deposit Works,7,2019-20,2020-21 D/2019-20/12112,Storm Water Drain,Completed,D-Storm Water Drains,86,870000,"Repairs to the damaged sewer lines by providing 200mm Dia Stoneware sewer line at 9th Street of Ambattur Industrial Estate in Division 86, Zone - 7.",Own Sources,7,2019-20,2020-21 D/2019-20/12113,Storm Water Drain,Completed,D-Storm Water Drains,86,780000,"Repairs to the damaged sewer lines by providing 200mm Dia Stoneware sewer line at 10th Street of Ambattur Industrial Estate in Division 86, Zone - 7.",Own Sources,7,2019-20,2020-21 D/2019-20/12114,Storm Water Drain,Completed,D-Storm Water Drains,86,950000,"Repairs to the damaged sewer lines by providing 200mm Dia Stoneware sewer line at 11th Street of Ambattur Industrial Estate in Division 86, Zone - 7.",Own Sources,7,2019-20,2020-21 D/2019-20/14145,Storm Water Drain,Completed,D-Storm Water Drains,86,990000,"Repairs of the damaged sewer lines by providing 200mm dia stoneware sewer line at 1st main road of Ambattur Industrial Estate South phase in Division 86, Zone VII.(Length 130 mtr)",Own Sources,7,2019-20,2021-22 D/2019-20/14147,Storm Water Drain,Completed,D-Storm Water Drains,86,990000,"Repairs to the damaged sewer lines by Providing 200mm dia SN8 - SDR34(S16.5) sewer line at 3rd Main Road of Ambattur Industrial Estate South phase in Division 86, Zone VII. (Length 269 mtr)",Own Sources,7,2019-20,2021-22 L/2019-20/4582,Electrical,Completed,Q-Solid Waste Management,86,999600,"Supply and fixing of LT Panel and MS Fabrication of LTCT EB servicing panel board with all accessories in Athipet dumping ground for biomining project, division-86, Zone-7",Own Sources,7,2019-20,2020-21 L/2019-20/5265,Electrical,Completed,L-Electrical,86,198700,"Proposal for removal and refixing of 17 nos of Kiosk Pillar Boxes from the Ground Level at various location in Division 86, 87,88 in Zone VII",Own Sources,7,2019-20,2020-21 L/2019-20/5463,Electrical,Completed,L-Electrical,86,7765200,"Estimate for provision of 79 Nos of 6 Mtr Lamp post with Straight Bracket with Hot Zinc Galvanising with 40 W LED Fitting & 11 Nos of 6 Mtr Lamp post with Arch Bracket with Hot Zinc Galvanising with 90 W LED Fitting & 32 Nos of 8 Mtr Lamp post with Straight Bracket with Hot Zinc Galvanising with 150 W LED Fitting In ICF Colony, Menambedu Road & Various Streets in Div. 81,86, 87 & 88 in Padi Section, Zone-VII, Ambattur",Grants,7,2019-20,2021-22 L/2019-20/8386,Electrical,Completed,L-Electrical,86,199700,"Replacement of 17 nos of 2 core SMC fuse box and 98 nos 4 core SMC fuse Box at MTH road and Various street in dn 81, 86 in Padi section Zone VII",Own Sources,7,2019-20,2020-21 NG/2019-20/0069,Parks,Completed,NG-AMBATTUR,86,133000,"Maintenance Estimate for Children Park at Gothavari Street ICF Colony in Dn-86, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/0070,Parks,Completed,NG-AMBATTUR,86,146000,"Maintenance Estimate for Children Park at CTH Road opp to Kochar Appartments in Dn-86, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/0071,Parks,Completed,NG-AMBATTUR,86,160000,"Maintenance Estimate for Children Park at Near ICICI Bank in Dn-86, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/0072,Parks,Completed,NG-AMBATTUR,86,240000,"Maintenance Estimate for Children Park at rear side of India Land in Dn-86, Zone-7",Own Sources,7,2019-20,2019-20 NG/2019-20/10471,Roads,Completed,NG-AMBATTUR,86,1043000,"Formation of Temporary pathway for vehicle movement by using B.G Boulders and WMM finish from vanagaram main road to Weigh Bridge at Athipet Transfer Station in Division - 86, Unit - 19, Zone - 7 (Ambattur)",Own Sources,7,2019-20,2020-21 NG/2019-20/10473,Roads,Completed,NG-AMBATTUR,86,940000,"Formation of Temporary pathway for vehicle movement by using B.G Boulders and WMM finish from Weigh Bridge to North east corner at Athipet Transfer Station in Division - 86, Unit - 19, Zone - 7 (Ambattur)",Own Sources,7,2019-20,2020-21 NG/2019-20/10476,Buildings,Completed,NG-AMBATTUR,86,432000,"Improvements to the Micro Composting Centre at Ahitpet Transfer Station in Div - 86, Unit-19, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/15144,Roads,Completed,NG-AMBATTUR,86,710000,"Restoration of road cut made by CMWSSB at Menambedu Main Road in Division-86, Unit-19, Zone-7.",Deposit Works,7,2019-20,2020-21 NG/2019-20/15378,Roads,Completed,NG-AMBATTUR,86,109000,"Restoration of road cut made by CMWSSB at Pugazhendhi Street in Division-86, Unit-19, Zone-7.",Deposit Works,7,2019-20,2020-21 NG/2019-20/15381,Roads,Completed,NG-AMBATTUR,86,109000,"Restoration of road cut made by CMWSSB at Bharathi Street in Division-86, Unit-19, Zone-7.",Deposit Works,7,2019-20,2020-21 NG/2019-20/15382,Roads,Completed,NG-AMBATTUR,86,103500,"Restoration of road cut made by CMWSSB at Kambar Street in Division-86, Unit-19, Zone-7.",Deposit Works,7,2019-20,2020-21 NG/2019-20/4268,Roads,Completed,NG-AMBATTUR,86,330000,"Restoration of road cut made by CMWSSB at Ragavendra Street in Division-86, Unit-19, Zone-7.",Deposit Works,7,2019-20,2020-21 NG/2019-20/4269,Roads,Completed,NG-AMBATTUR,86,1130000,"Restoration of road cut made by CMWSSB on existing BT road at Gandhi Street in Division-86, Unit-19, Zone-7.",Deposit Works,7,2019-20,2020-21 NG/2019-20/6696,Buildings,Completed,NG-AMBATTUR,86,1250000,"Desilting and Repair Works to the existing side drain at Annai Sathya Nagar Kambar Street, Kambar Cross Street, Elango Street, Pillayar Kovil Street, Pillayar Kovil Cross Street in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6697,Buildings,Completed,NG-AMBATTUR,86,1220000,"Desilting and Repair Works to the existing side drain at Annai Sathya Nagar Kalidasan Street,Sathya nagar Main Road, Amman Kovil Street, NSK Street, Kannadasan Street in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6698,Buildings,Completed,NG-AMBATTUR,86,550000,"Desilting and Repair Works to the existing side drain at Mannurpet Nehru Street, Nehru 1st Street, Nehru 2nd Street, Nehru 3rd Street, Nehru 4th Street, New Pillayar Kovil 1st Cross Street, New Pillayar Kovil 2nd Cross Street, New Pillayar Kovil 3rd Cross Street, Logaiah Naidu Street, Kamaraj Nagar Street, Kamaraj Nagar 1st Street, Kamaraj Nagar 2nd Street, Kamaraj Nagar 3rd Street, Kamaraj Nagar 4th Street, Thiruveethiamman Street, Adimoolam Avenue in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6699,Buildings,Completed,NG-AMBATTUR,86,1030000,"Malaiyalathamman Kovil Street, Malaiyalathamman Kovil 1st St, Malaiyalathamman Kovil 2nd St, Malaiyalathamman Kovil 3rd St, Malaiyalathamman Kovil Cross St, Bajani Kovil Street, Perumal Kovil Street, Perumal Kovil 1st Street, Perumal Kovil 2nd Street, Perumal Kovil 3rd Street, Perumal Kovil 4th Street in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6700,Buildings,Completed,NG-AMBATTUR,86,1090000,"Desilting and Repair Works to the existing side drain at Athipet Chinna Colony Padasalai Street, VOC Street, VOC 1st Cross Street, VOC 2nd Cross Street, Ambethkar Street, Anna Street in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6701,Buildings,Completed,NG-AMBATTUR,86,580000,"Desilting and Repair Works to the existing side drain at Athipet Chinna Colony Thirupur Kumaran Street, Thiruvalluvar Street, kavarai Street, Kavarai cross Street, South Reddy Street, Mettu Street, Mettu 1st cross street, Mettu 2nd cross street, Mettu 3rd cross street, Mettu 5th cross street, Mettu 6th cross street, Mettu 7th cross street, Mettu 8th cross street, Mettu 9th cross street in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6702,Buildings,Completed,NG-AMBATTUR,86,1530000,"Desilting to the existing Storm Water drain at Bagavathi Amman Koil Street, Abdulkalam Nagar 3rd Street, Thamirabarani Street, Pugazenthi Street & Kalidas Street, Kambar Street, Kalidoss Street & Ram Poornam Nagar, Chennai City Layout,Chennai New City Main Road,Natesan Nagar, Mel Ayanambakkam Main Road,Kalyani Industrial Estate Road, Ambattur Vanagaram Road,PKM Road & 3rd Main Road, AmbatturInd.Estate 1st Main Road in division -86, unit- 19, Zone - 7",Own Sources,7,2019-20,2019-20 NG/2019-20/6703,Buildings,Completed,NG-AMBATTUR,86,1500000,"Desilting to the existing Storm Water drain at AmbatturInd. Estate 3rd main Road, 1st Cross Main Road, Thirumangalam Main Road, AmbatturInd.Estate 3rd Street, AmbatturInd.Estate 4th & 10th Street, Ambattur Ind.Estate 4th Street, AmbatturInd.Estate 2nd Cross Main Road, Ambattur Ind.Estate 2nd Cross Main Road & 10th Street, AmbatturInd.Estate 3rd Cross Main Road, AmbatturInd.Estate 10th Street, Thirumangalam Main Road (Vaavin) - South Avenue Road, Ambattur IE 12th Street, Ambattur IE 5th Street, Ambattur IE 8th Street, AIE 2nd Cross Main Road, AIE 3rd Cross Main Road, ATC Road, AIE 13th Street, AIE 7th Street, AIE 2nd Cross Main Road, MTH Road (Telephone Exchange), Chelliamman Kovil Street, VGN Shanthi Nagar Main Road, Sri Ganesh Street & Nageshwara Rao 3rd Cross Street, Nageshwara Rao Road, Pugazenthi Street, Chelliamman Nagar, Thulugathamman Street in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6704,Buildings,Completed,NG-AMBATTUR,86,1500000,"Desilting to the existing Storm Water drain at PKM Road Bajanai Kovi Street, Chelliamman Kovi Main Road, Alamaram Street, South Reddy Street, Alamaram Street, Vanniyar Street 2nd Street, SPS 3rd Main Road, Mariyamman Kovil Street, Mahatma Gandhi Road & Jeeva Rathinam Main Road (KSR Nagar), Jawaharalal Nehru Street, VGN Shanthi Nagar Main Road, Athipet Kuppam Road, TNHB Phase - III, Reddy Street, Devadass Street, 2B/8 South Industrial Street, Chellaiamman Kovil Nagar, Vanniyar Street, KSR Nagar, TG Anna Nagar, Township Colony, Munusamy Street, VGN Shanthi Nagar Main Road, Vinayakar Kovil Street, Om Sakthi and Krishna Street, KSR Nagar, KSR Jeevarathinam in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6705,Buildings,Completed,NG-AMBATTUR,86,480000,"Desilting to the existing Storm Water drain at Ayanambakkam Main Road, Thirupathi Kodai Road & Kalaivanar Nagar in division -86, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/8394,Roads,Completed,NG-AMBATTUR,86,2200000,"Attending Pot Holes and Patch work at various streets in Division - 84, 85, 86, 87 & 88, Unit -19, Zone - VII.",Own Sources,7,2019-20,2020-21 NG/2019-20/9471,Parks,Completed,NG-AMBATTUR,86,230000,"ANNUAL MAINTENANCE ESTIMATE OF THE GOPAL SWAMY NAGAR PARK IN DIVISION 86, UNIT - 19, ZONE -VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9472,Parks,Completed,NG-AMBATTUR,86,550000,"ANNUAL MAINTENANCE ESTIMATE OF SINDHU NADHI PARK IN DIVISION-86, UNIT-19, ZONE-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9473,Parks,Completed,NG-AMBATTUR,86,413000,"ANNUAL MAINTENANCE ESTIMATE OF CHELLIAMMAN KOVIL PARK IN DIVISION-86, UNIT-19, ZONE-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9474,Parks,Completed,NG-AMBATTUR,86,904000,"ANNUAL MAINTENANCE ESTIMATE OF VGN SHANTHI NAGAR PARK IN DIVISION-86, UNIT-19, ZONE-VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9475,Parks,Completed,NG-AMBATTUR,86,622000,"ANNUAL MAINTENANCE ESTIMATE OF CHELLIAMMAN KOVIL POND PARK IN DIVISION-86, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9476,Parks,Completed,NG-AMBATTUR,86,481000,"ANNUAL MAINTENANCE ESTIMATE OF GOTHAVARI STREET PARK IN DIVISION-86, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9477,Parks,Completed,NG-AMBATTUR,86,490000,"ANNUAL MAINTENANCE ESTIMATE OF CTH ROAD PARK OPP TO KOCHAR IN DIVISION-86, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9478,Parks,Completed,NG-AMBATTUR,86,484000,"ANNUAL MAINTENANCE ESTIMATE OF ICICI BANK PARK IN DIVISION-86, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9479,Parks,Completed,NG-AMBATTUR,86,819000,"ANNUAL MAINTENANCE ESTIMATE OF INDIA LAND PARK IN DIVISION-86, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9481,Parks,Completed,NG-AMBATTUR,86,442000,"ANNUAL MAINTENANCE OF AP FLATS CHILDERNS PARK IN DIVISION-88, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11280,Roads,Completed,NG-AMBATTUR,87,306000,"Relaying of BT road at Periyar 4th cross street in dividion-87,Unit-19,Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/11281,Roads,Completed,NG-AMBATTUR,87,282000,"Relaying of BT road at kamarajar cross street in dividion-87,Unit-19,Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/11855,Roads,Completed,NG-AMBATTUR,87,438000,"Relaying of BT Road at Sundharar street in Division-87,Unit-19,Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/14834,Buildings,Completed,NG-AMBATTUR,87,463000,"Maintenance works to the Corporation building and parks,roads in division-87,Unit-19,Zone-7.",Own Sources,7,2019-20,2021-22 NG/2019-20/4481,Storm Water Drain,Completed,NG-AMBATTUR,87,1061000,"De silting and Minor Repairing work to side drain at various street in division-87,Unit-19,Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/9265,Roads,Completed,NG-AMBATTUR,87,274000,"Relaying of BT road at South mada cross street in dividion-87,Unit-19,Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/9267,Roads,Completed,NG-AMBATTUR,87,235000,"Relaying of BT road at bharathidasan extn in dividion-87,Unit-19,Zone-7.",Own Sources,7,2019-20,2020-21 BR/2019-20/6833,Road Cut,Completed,BR-Bus Route Roads,88,1160000,"Restoration of road cut made by CMWSSB at Thirupathi Kodai Road in Dn -86 ,Zone - 7",Deposit Works,7,2019-20,2020-21 L/2019-20/5268,Electrical,Completed,L-Electrical,88,178900,"Proposal for removal and refixing of 8 nos of Kiosk Pillar Boxes from the Ground Level and 116 nos of constructing new plain cement concrete pedestal at various location in Division 81,86,85,88 in Zone VII",Own Sources,7,2019-20,2020-21 L/2019-20/8387,Electrical,Completed,L-Electrical,88,198900,"Replacement of 93 nos of 4 core SMC fuse box and 25 nos 2 core SMC fuse Box at Northmada st and Various street in dn 87, 88 in Padi section Zone VII",Own Sources,7,2019-20,2020-21 NG/2019-20/0074,Parks,Completed,NG-AMBATTUR,88,138000,"Maintenance Estimate for park and children play field at CTH Road in Dn-88, Zone - 7",Own Sources,7,2019-20,2019-20 NG/2019-20/10477,Buildings,Completed,NG-AMBATTUR,88,435000,"Improvements to the Micro Composting Centre at Pandurangapuram in Div - 88, Unit-19, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/13968,Buildings,Completed,NG-AMBATTUR,88,530000,"Repairs and improvement works to Millienium Park at Park road in Division -88, Unit-19, Zone -7.",Own Sources,7,2019-20,2020-21 NG/2019-20/16836,Buildings,Completed,NG-AMBATTUR,88,1171000,"Operation and maintenance for the 4th year period (2019-20) (RO/UV filtration) of 2000litres/hour capacity expandables to 4000litres/hour capacity (2000litres expandables increment of 2000litres/hours and at Kalaivanar Nagar, Anna Nagar West in Division- 88,Unit-19, Zone-7.",Own Sources,7,2019-20,2021-22 NG/2019-20/5520,Parks,Completed,NG-AMBATTUR,88,550000,"Improvement works to play apparatus in GCC Park in Division -88, Unit-19, Zone -7.",MLACDS,7,2019-20,2021-22 NG/2019-20/6721,Buildings,Completed,NG-AMBATTUR,88,777000,"Desilting to the existing Storm Water drain at Park Road, North Main Road, 3rd Avenue, 2nd Avenue, Tvs Nagar Main Road, Kavitha Street, Padavattamman Main Road, Kalaivanar Nagar Main Road, Tvs Main Road, Thendral Street, Rajendra Prasad Street, N.S.C.Bose Street, Kattabomman Street, Maduraiveeran Street, Voc Street, Kumaran Nagar, Mg Road Kumaran Nagar, Patel Street, B-Sector 1st Street,B-Sector 2nd Street, B-Sector 3rd Street, B-Sector 4th Street, B-Sector 5th Street, B-Sector 6th Street, B-Sector 7th Street, B-Sector 8th Street, C-Sector 6th Street, C-Sector 7th Street, C-Sector 9th Street, C-Sector 10th Street, C-Sector 11th Street, C-Sector 12th Street, C-Sector 13th Street, C-Sector 14th Street, C-Sector 15th Street, D-Sector 5th Street, D-Sector 7th Street, D-Sector 8th Street, West Gate Road, School Road various street in division -88, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6722,Buildings,Completed,NG-AMBATTUR,88,1567000,"Desilting and Repair Works to the existing side drain at VOC Street, Jawahar Street, Bharathiyar Street, Ambedkar Street, Anna 2nd Street, Anna 1st Street, Amman Koil Street, Gandhi Street , Thiruvalleswarar Colony, Thiruvalluvar Street, Padvattamman Koil 2nd Street, Padvattamman Koil 3rd Street, Padvattamman Koil 4th Street, Kamarajar Street, North Mada Street, North Mada 1st Street, North Mada 2nd Street, North Mada 2nd Cross Street, North Mada 3rd Street, North Mada 4th Street, North Mada 5th Street, Kailasanathar Street, Anna 1st Street, Anna 2nd Street, in division -88, unit- 19, Zone - 7.",Own Sources,7,2019-20,2019-20 NG/2019-20/9482,Parks,Completed,NG-AMBATTUR,88,558000,"ANNUAL MAINTENANCE OF B SECTOR PARK IN DIVISION-88, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9483,Parks,Completed,NG-AMBATTUR,88,559000,"ANNUAL MAINTENANCE OF C SECTOR PARK IN DIVISION-88, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9484,Parks,Completed,NG-AMBATTUR,88,1220000,"ANNUAL MAINTENANCE OF MILLIENIUM PARK IN DIVISION-88, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9485,Parks,Completed,NG-AMBATTUR,88,438000,"ANNUAL MAINTENANCE OF CTH ROAD PARK IN DIVISION-88, UNIT-19, ZONE-7",Own Sources,7,2019-20,2020-21 L/2019-20/5656,Electrical,Completed,L-Electrical,89,512300,"PROVISION FOR ERECTION OF 11 NOS. OF NEW 6M/8M LAMP POSTS TOWARDS REPLACEMENT OF RUSTED POSTS IN WARD 89,92 &93 OF MOGAPPAIR DIVISION , ZONE -7",Own Sources,7,2019-20,2020-21 L/2019-20/7418,Electrical,Completed,L-Electrical,89,324100,provisions of 250 nos plain cement concrete pedestal for old post and replacement of 6nos pillar box completly damaged pillars various street in div-89 and 90 mogapair division ambattur zone-7,Own Sources,7,2019-20,2021-22 NG/2019-20/10420,Electrical,Completed,NG-AMBATTUR,89,1260000,"Improvements to existing burial ground at TVS Avenue Main Road in Div - 89, Unit-20, Zone-7.",Own Sources,7,2019-20,2021-22 NG/2019-20/15246,Buildings,Completed,NG-AMBATTUR,89,360000,"IMPROVEMENTS WORK TO EXISTING DIVISION OFFICE IN DN 89, UNIT-20, ZONE - VII",Own Sources,7,2019-20,2021-22 NG/2019-20/16371,Roads,Completed,NG-AMBATTUR,89,1194000,"IMPROVEMENTS TO INTERIOR B T ROAD AT AKSHAYA COLONY 1ST AVENUE IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2020-21 NG/2019-20/16372,Roads,Completed,NG-AMBATTUR,89,1266000,"IMPROVEMENTS TO INTERIOR B T ROAD AT OLYMPIC COLONY 1ST MAIN ROAD IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2020-21 NG/2019-20/16373,Roads,Completed,NG-AMBATTUR,89,1876000,"IMPROVEMENTS TO INTERIOR B T ROAD AT SATHYA NAGAR PADA SALAI STREET IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16374,Roads,Completed,NG-AMBATTUR,89,2134000,"IMPROVEMENTS TO INTERIOR B T ROAD AT SRINIVASA NAGAR ANNA 1ST CROSS STREE IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16375,Roads,Completed,NG-AMBATTUR,89,3161000,"IMPROVEMENTS TO INTERIOR B T ROAD AT SRINIVASA NAGAR PERIYAR 1st CROSS STREET IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16378,Roads,Completed,NG-AMBATTUR,89,870000,"IMPROVEMENTS TO INTERIOR B T ROAD AT VALLAL PARI STREET IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16380,Roads,Completed,NG-AMBATTUR,89,2466000,"IMPROVEMENTS TO INTERIOR B T ROAD AT T.S.KRISHNA NAGAR NAGAR IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16381,Roads,Completed,NG-AMBATTUR,89,2091000,"IMPROVEMENTS TO INTERIOR B T ROAD AT T.S KRISHNA NAGAR PADASALAI STREET IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16382,Roads,Completed,NG-AMBATTUR,89,4075000,"IMPROVEMENTS TO INTERIOR B T ROAD AT RADIAL NAGAR IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16383,Roads,Completed,NG-AMBATTUR,89,3699000,"IMPROVEMENTS TO INTERIOR B T ROAD AT SM NARAYANAN NAGAR IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16384,Roads,Completed,NG-AMBATTUR,89,1379000,"IMPROVEMENTS TO INTERIOR B T ROAD AT TVS COLONY 50TH STREET IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16385,Roads,Completed,NG-AMBATTUR,89,1050000,"IMPROVEMENTS TO INTERIOR B T ROAD AT TVS COLONY 42ND STREET IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16386,Roads,Completed,NG-AMBATTUR,89,1793000,"IMPROVEMENTS TO INTERIOR B T ROAD AT TVS AVENUE 36TH STREET IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/16387,Roads,Completed,NG-AMBATTUR,89,1061000,"IMPROVEMENTS TO INTERIOR B T ROAD AT OFFICER COLONY LINK ROAD IN DN 89, UNIT 20, ZONE 7",Own Sources,7,2019-20,2021-22 NG/2019-20/2002,Parks,Completed,NG-AMBATTUR,89,790000,"PROVIDING WELL RING PIT AT VARIOUS STREETS IN DN 89 TO 93, UNIT - 20, ZONE - VII",Own Sources,7,2019-20,2019-20 NG/2019-20/3525,Roads,Completed,NG-AMBATTUR,89,1226000,"Operation and maintenance for the 4th year period (2019-20) (RO/UV filtration) of 2000litres/hour capacity expandables to 4000litres/hour capacity (2000litres expandables increment of 2000litres/hours and at Seethakadhi salai in Division-92,Unit-20,Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/5308,Parks,Completed,NG-AMBATTUR,89,900000,"PROVIDING AND FIXING OF CHILDREN PLAY APPARATUS IN PARKS AT TVS AVENUE MAIN ROAD, TVS COLONY 45TH STREET AND OFFICERS COLONY MAIN ROAD IN DIVISION-89 UNIT-20 ZONE-7(AMBATTUR).",MLACDS,7,2019-20,2020-21 NG/2019-20/6074,Buildings,Completed,NG-AMBATTUR,89,431000,"De-silting, Storm Water Drain Repair and Manhole Door Repair at Various Street (BRR) Div-89, Unit-20, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6076,Storm Water Drain,Completed,NG-AMBATTUR,89,1469000,"De-silting, Storm Water Drain Repair and Manhole Door Repair at Various Street (IRR) Div-89, Unit-20, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6077,Buildings,Completed,NG-AMBATTUR,89,2450000,"Proposed Construction of Gym Building At Officers Colony Play Ground In Division-89, Unit-20, Zone-7.",MLACDS,7,2019-20,2020-21 NG/2019-20/9459,Parks,Completed,NG-AMBATTUR,89,470000,Annual Maintenance of GCC Parks for One year at Akshaya Colony in Dn 89 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 NG/2019-20/9461,Parks,Completed,NG-AMBATTUR,89,430000,Annual Maintenance of GCC Parks for One year at Officers Colony in Dn 89 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 NG/2019-20/9462,Parks,Completed,NG-AMBATTUR,89,432000,Annual Maintenance of GCC Parks for One year at TVS Colony in Dn 89 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 NG/2019-20/9465,Parks,Completed,NG-AMBATTUR,89,930000,Annual Maintenance of GCC Parks for One year at Golden Colony in Dn 89 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 NG/2019-20/9467,Parks,Completed,NG-AMBATTUR,89,520000,Annual Maintenance of GCC Parks for One year at TVS Avenue Main Road in Dn 89 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 L/2019-20/9038,Electrical,Completed,L-Electrical,90,730400,"PROVISION FOR SHIFTING OF EXISTING 26 POSTS TO CORNER OF THE ROAD DUE TO ROAD WIDENING AND NEW 4X16 SQ.MM CABLE REPLACEMENT IN PADI PUDHU NAGAR MAIN ROAD IN WARD 90, MOGAPPAIR DIVISION , ZONE -7",Own Sources,7,2019-20,2020-21 NG/2019-20/10063,Buildings,Completed,NG-AMBATTUR,90,850000,"Widening of Road at Padiputhu Nagar Main Road from Padiputhu Nagar 10th to Padiputhu Nagar 12th Street in Div - 90, Unit-20, Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/10129,Buildings,Completed,NG-AMBATTUR,90,930000,"LAYING OF CEMENT CONCRETE ROAD AT KAMARAJAR NAGAR 5TH CROSS STREET TO 8TH CROSS STREET AND PERIYAR NAGAR 1ST CROSS TREET IN DIV 90,UNIT-20, ZONE-7",Own Sources,7,2019-20,2020-21 NG/2019-20/11755,Parks,Completed,NG-AMBATTUR,90,252000,Annual Maintenance of GCC Parks for One year at Padikuppam Main Road TNHB Flats Park in Dn 90 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2021-22 NG/2019-20/2447,Buildings,Completed,NG-AMBATTUR,90,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT BURIAL GROUND ROAD IN DN 90, UNIT-20, ZONE VII",Own Sources,7,2019-20,2019-20 NG/2019-20/2449,Buildings,Completed,NG-AMBATTUR,90,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT MOGAPPAIR ERI SCHEME SCHEME 7TH CROSS ST IN DN 91, UNIT-20, ZONE VII",Own Sources,7,2019-20,2019-20 NG/2019-20/2450,Buildings,Completed,NG-AMBATTUR,90,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT MANGAL ERI PARK (ANNA PARK) IN DN 92, UNIT-20, ZONE VII",Own Sources,7,2019-20,2019-20 NG/2019-20/2451,Buildings,Completed,NG-AMBATTUR,90,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT GANGAI AMMAN NAGAR IN DN 93, UNIT-20, ZONE VII",Own Sources,7,2019-20,2019-20 NG/2019-20/2471,Buildings,Completed,NG-AMBATTUR,90,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT MENAMBEDU BURIAL GROUND IN DIVISION-81,UNIT-18,ZONE-7",Own Sources,7,2019-20,2019-20 NG/2019-20/2473,Buildings,Completed,NG-AMBATTUR,90,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT MENAMBEDU BURIAL GROUND IN DIVISION-82,UNIT-18,ZONE-7 (AMBATTUR)",Own Sources,7,2019-20,2019-20 NG/2019-20/2844,Parks,Completed,NG-AMBATTUR,90,329000,"MAINTENANCE ESTIMATE FOR O.N.G.C PARK AT PARK ROAD IN DIV- 90, UNIT- 20 , ZONE -VII.",Own Sources,7,2019-20,2019-20 NG/2019-20/2854,Parks,Completed,NG-AMBATTUR,90,108000,"MAINTENANCE ESTIMATE T.N.H.B PARK AT THIRUMANGALAM MAIN ROAD IN DN 90, UNIT 20 , ZONE VII",Own Sources,7,2019-20,2019-20 NG/2019-20/6028,Storm Water Drain,Completed,NG-AMBATTUR,90,960000,"De-silting of Storm Water Drain and Manhole Door Repair at Various Street (IRR) Div-90, Unit-20, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6029,Storm Water Drain,Completed,NG-AMBATTUR,90,540000,"De-silting of Storm Water Drain and Manhole Door Repair at Various Street (BRR) Div-90, Unit-20, Zone-7.",Own Sources,7,2019-20,2019-20 NG/2019-20/6920,Storm Water Drain,Completed,NG-AMBATTUR,90,314000,"Repairs and improvements to existing MCC at Padikuppam burial ground road in Div - 90, Unit-20, Zpne-7",Own Sources,7,2019-20,2020-21 NG/2019-20/7157,Buildings,Completed,NG-AMBATTUR,90,158000,"Facelifting of Anganvadi Centre No.19 at Padiputhu Nagar Main Road in Div - 90, Unit-20, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/7181,Roads,Completed,NG-AMBATTUR,90,1820000,"Widdening of Road at Padiputhu Nagar Main Road from Padiputhu Nagar 11th Street to MGR Street in Div - 90, Unit-20, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/7194,Roads,Completed,NG-AMBATTUR,90,2180000,"Widding of Road at Padiputhu Nagar Main Road from Thirumangalam Main Road to MGR Street in Div - 90, Unit-20, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/7404,Storm Water Drain,Completed,NG-AMBATTUR,90,300000,"Repairs and maintenance of side drian at Gandhi Nagar in div-90, Unit-20, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/8039,Roads,Completed,NG-AMBATTUR,90,680000,"ATTENDING OF PATCH WORK AT VARIOUS STREET IN DN 90 TO 93, UNIT - 20, ZONE VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9416,Parks,Completed,NG-AMBATTUR,90,670000,Annual Maintenance of GCC Parks for One year at Asiad Colony Park in Dn 90 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 NG/2019-20/9418,Parks,Completed,NG-AMBATTUR,90,660000,Annual Maintenance of GCC Parks for One year at Golden Jubilee park in Dn 90 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 NG/2019-20/9423,Parks,Completed,NG-AMBATTUR,90,650000,Annual Maintenance of GCC Parks for One year at Collector Nagar Park in Dn 90 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2020-21 NG/2019-20/9425,Parks,Completed,NG-AMBATTUR,90,410000,Annual Maintenance of GCC Parks for One year at Welcome Colony Block No.49-A in Dn 90 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2021-22 NG/2019-20/9427,Parks,Completed,NG-AMBATTUR,90,1000000,Annual Maintenance of GCC Parks for One year at ONGC Park in Dn 90 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2021-22 NG/2019-20/9429,Parks,Completed,NG-AMBATTUR,90,469000,Annual Maintenance of GCC Parks for One year at TNHB Flats Park in Dn 90 Unit-20 Zone-7 (per year),Own Sources,7,2019-20,2021-22 BR/2019-20/4895,Roads,Completed,BR-Bus Route Roads,91,1975000,"Partly relaying the road with BC after cold milling by paver finisher at Mugappair West 3rd main Road in Dn-91, Zone - VII",Grants,7,2019-20,2020-21 NG/2019-20/11753,Roads,Completed,NG-AMBATTUR,91,1314000,RELAYING THE EXISTING ROAD AT MOGAPPAIR ERI SCHEME 2ND STREET IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2019-20,2020-21 NG/2019-20/11760,Roads,Completed,NG-AMBATTUR,91,521000,RELAYING THE EXISTING ROAD AT MEENATCHI AVENUE 1ST STREET IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2019-20,2020-21 NG/2019-20/11765,Roads,Completed,NG-AMBATTUR,91,567000,RELAYING THE EXISTING ROAD AT TNHB 3RD BLOCK 10TH STREET I DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/11766,Roads,Completed,NG-AMBATTUR,91,569000,RELAYING THE EXISTING ROAD AT TNHB 7TH BLOCK 15TH STREET IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/11767,Roads,Completed,NG-AMBATTUR,91,279000,RELAYING THE EXISTING ROAD AT JESWANTH NAGAR 3RD CROSS STREET IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/11768,Roads,Completed,NG-AMBATTUR,91,996000,FORMATION OF NEW BT ROAD AT TRI STAR APARTMENT PARK ROAD IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/14555,Roads,Completed,NG-AMBATTUR,91,473000,FORMATION OF CEMENT CONCRETE ROAD AT MOGAPPAIR ERI SCHEME 18TH CROSS STREET IN DIVISION 91 UNIT 20 ZONE 7,Own Sources,7,2019-20,2020-21 NG/2019-20/6020,Storm Water Drain,Completed,NG-AMBATTUR,91,695000,"DESILTING, MINOR REPAIR WORKS AND REPLACEMENT OF DAMAGED SWD MANHOLES OF STORM WATER DRAIN AT VARIOUS STREETS (IRR) IN DIVISION- 91 UNIT-20 ZONE-7(AMBATTUR)",Own Sources,7,2019-20,2019-20 NG/2019-20/6021,Storm Water Drain,Completed,NG-AMBATTUR,91,359000,"DESILTING, MINOR REPAIR WORKS AND REPLACEMENT OF DAMAGED SWD MANHOLES OF STORM WATER DRAIN AT BUS ROUTE ROADS IN DIVISION- 91 UNIT-20 ZONE-7(AMBATTUR)",Own Sources,7,2019-20,2019-20 NG/2019-20/7186,Buildings,Completed,NG-AMBATTUR,91,110000,IMPROVEMENT WORKS TO EXISTING COMPOST YARD (MCC) AT MOGAPPAIR ERI SCHEME 4TH MAIN ROAD IN DIV-91 UNIT-20 ZONE-07 AMBATTUR,Own Sources,7,2019-20,2020-21 NG/2019-20/7193,Buildings,Completed,NG-AMBATTUR,91,126000,"Improvement works to the existing Division Office at Mogappair Eri Scheme 7th cross street in Division - 91, Unit-20, Zone-7",Own Sources,7,2019-20,2020-21 NG/2019-20/9437,Parks,Completed,NG-AMBATTUR,91,423000,ANNAUAL MAINTANENCE TO THE EXISTING PARK AT MOGAPPAIR ERI SCHEME 1ST MAIN ROAD IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2019-20,2020-21 NG/2019-20/9440,Parks,Completed,NG-AMBATTUR,91,520000,ANNUAL MAINTENANCE OF THE EXISTING PARK AT AIBEA NAGAR IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/9442,Parks,Completed,NG-AMBATTUR,91,670000,ANNUAL MAINTENANCE OF THE EXISTING PARK AT MOGAPPAIR ERI SCHEME 8TH CROSS STREET IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2021-22 NG/2019-20/9445,Parks,Completed,NG-AMBATTUR,91,760000,ANNUAL MAINTENANCE OF THE EXISTING PARK AT MOGAPPAIR WEST BUS STAND IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/9449,Parks,Completed,NG-AMBATTUR,91,480000,ANNUAL MAINTENANCE OF THE EXISTING PARK AT JESWANTH NAGAR PHASE 1 IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/9451,Parks,Completed,NG-AMBATTUR,91,480000,ANNUAL MAINTENANCE OF THE EXISTING PARK AT JESWANTH NAGAR PHASE 2 IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/9454,Parks,Completed,NG-AMBATTUR,91,430000,ANNUAL MAINTENANCE OF THE EXISTING PARK AT TRI STAR IN DIVISION 91 UNIT 20 ZONE 07,Own Sources,7,2019-20,2020-21 NG/2019-20/10113,Buildings,Completed,NG-AMBATTUR,92,143000,IMPROVEMENT WORKS TO EXISTING COMPOST YARD(MCC) AT MOGAPPAIR ROAD IN DIV 92 89 & 87 ZONE 7,Own Sources,7,2019-20,2020-21 NG/2019-20/10160,Roads,Completed,NG-AMBATTUR,92,620000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT EB ROAD SOUTH SIDE (NARAYANA SCHOOL TO SOUNDARYAM FLATS) IN DIV 92 UNIT 20 ZONE 07,Deposit Works,7,2019-20,2020-21 NG/2019-20/10165,Roads,Completed,NG-AMBATTUR,92,600000,RESTORATION OF ROAD CUT MADE BY CMWSSB AT EB ROAD NORTH SIDE ( EB OFFICE TO ORI SALAI) IN DIV 92 UNIT 20 ZONE 07,Deposit Works,7,2019-20,2020-21 NG/2019-20/10475,Buildings,Completed,NG-AMBATTUR,92,260000,"CONSTRUCTION OF COMPOUND WALL AT KANNADASAN SALAI ICDS IN DN 92, UNIT - 20, ZONE - VII",Own Sources,7,2019-20,2020-21 NG/2019-20/10494,Parks,Completed,NG-AMBATTUR,92,440000,"PROVIDING RAIN WATER HARVESTING AT MANGAL ERI PARK IN DN 92, UNIT-20, ZONE - VII",Own Sources,7,2019-20,2020-21 NG/2019-20/10554,Parks,Completed,NG-AMBATTUR,92,265000,"CONSTRUCTION OF YOGA STAGE AT E.B PARK IN DN 92, UNIT - 20, ZONE - VII",Own Sources,7,2019-20,2020-21 NG/2019-20/11287,Buildings,Completed,NG-AMBATTUR,92,89000,ANNUAL MAINTENANCE TO THE EXISTING DIVISION OFFICE AT PATTINATHAR SALAI IN DIV 92 UNIT 20 ZONE 7,Own Sources,7,2019-20,2020-21 NG/2019-20/4225,Buildings,Completed,NG-AMBATTUR,92,1226000,"Operation and maintenance for the 4th year period (2019-20) (RO/UV filtration) of 2000litres/hour capacity expandables to 4000litres/hour capacity (2000litres expandables increment of 2000litres/hours and at Seethakadhi salai in Division-92,Unit-20,Zone-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/4338,Parks,Completed,NG-AMBATTUR,92,40500,"ANNUAL MAINTENANCE OF PARK AT VARUN APARTMENT IN DN - 92, UNIT- 20, ZONE - VII",Own Sources,7,2019-20,2019-20 NG/2019-20/4364,Parks,Completed,NG-AMBATTUR,92,39000,"ANNUAL MAINTENANCE OF PARK AT VANUGOPAL STREET IN DN - 92, UNIT- 20, ZONE - VII",Own Sources,7,2019-20,2019-20 NG/2019-20/4365,Parks,Completed,NG-AMBATTUR,92,42000,"ANNUAL MAINTENANCE OF PARK ATCHRUCH ROAD IN DN - 92, UNIT- 20, ZONE - VII",Own Sources,7,2019-20,2019-20 NG/2019-20/4367,Parks,Completed,NG-AMBATTUR,92,39000,"ANNUAL MAINTENANCE OF PARK AT VEERAMAMUNIVAR SALAI IN DN - 92, UNIT- 20, ZONE - VII",Own Sources,7,2019-20,2019-20 NG/2019-20/6022,Storm Water Drain,Completed,NG-AMBATTUR,92,750000,"DESILTING, MINOR REPAIR WORKS AND REPLACEMENT OF DAMAGED SWD MANHOLES OF STORM WATER DRAIN AT VARIOUS STREETS (IRR) IN DIVISION- 92 UNIT-20 ZONE-7(AMBATTUR)",Own Sources,7,2019-20,2019-20 NG/2019-20/6023,Storm Water Drain,Completed,NG-AMBATTUR,92,900000,"DESILTING, MINOR REPAIR WORKS AND REPLACEMENT OF DAMAGED SWD MANHOLES OF STORM WATER DRAIN AT BUS ROUTE ROADS IN DIVISION- 92 UNIT-20 ZONE-7(AMBATTUR)",Own Sources,7,2019-20,2019-20 NG/2019-20/6985,Buildings,Completed,NG-AMBATTUR,92,1210000,"IMPROVEMENTS TO THE EXISTING R.R. CENTRE, MICRO COMPOST CENTRE AT MOGAPPAIR ROAD IN DN 92, UNIT-20, ZONE - VII",Own Sources,7,2019-20,2020-21 NG/2019-20/7112,Buildings,Completed,NG-AMBATTUR,92,380000,"IMPROVEMENTS TO THE EXISTING DIVISION 87, R.R.CETRE, MICRO COMPOST CENTRE AT MOGAPPAIR ROAD IN DN 92, UNIT-20, ZONE - VII",Own Sources,7,2019-20,2020-21 NG/2019-20/9503,Parks,Completed,NG-AMBATTUR,92,2170000,"Annual Maintenance of GCC Parks for One year at E.B. Road Park in Dn 92, Unit-20, Zone-7 (per year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9504,Parks,Completed,NG-AMBATTUR,92,2300000,"Annual Maintenance of GCC Parks for One year at Anna Park (Mangal Eri) in Dn 92, Unit-20, Zone-7 (per year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9507,Parks,Completed,NG-AMBATTUR,92,419000,"Annual Maintenance of GCC Parks for One year at Varun Apartment in Dn 92, Unit-20, Zone-7 (per year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9508,Parks,Completed,NG-AMBATTUR,92,420000,"Annual Maintenance of GCC Parks for One year at Church Road in Dn 92, Unit-20, Zone-7 (per year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9509,Parks,Completed,NG-AMBATTUR,92,436000,"Annual Maintenance of GCC Parks for One year at Veeramamunivar Salai (Opp to M.G.R. School) in Dn 92, Unit-20, Zone-7 (per year)",Own Sources,7,2019-20,2020-21 NG/2019-20/9511,Parks,Completed,NG-AMBATTUR,92,420000,"Annual Maintenance of GCC Parks for One year at Vengopal street in Dn 92, Unit-20, Zone-7 (per year)",Own Sources,7,2019-20,2020-21 NG/2019-20/0920,Roads,Completed,NG-AMBATTUR,93,1035000,"ROAD CUT RESTORATION BITUMINOUS MACADAM ROAD AT VANDIYAMMAN KOIL STREET,PADIKUPPAM ANNA STREET, IN DIV 93,UNIT-20, ZONE-7 ( EST-1)",Deposit Works,7,2019-20,2020-21 NG/2019-20/0939,Roads,Completed,NG-AMBATTUR,93,1150000,"ROAD CUT RESTORATION BITUMINOUS MACADAM ROAD AT MARAIMALAI ADIKALAR SALAI IN DIV 93,UNIT-20, ZONE-7",Deposit Works,7,2019-20,2020-21 NG/2019-20/0940,Roads,Completed,NG-AMBATTUR,93,1575000,"ROAD CUT RESTORATION BITUMINOUS MACADAM ROAD AT JUSTICE RATHINAVEL PANDIYAN ROAD AND ORI SALAI IN DIV 93,UNIT-20, ZONE-7",Deposit Works,7,2019-20,2020-21 NG/2019-20/1041,Roads,Completed,NG-AMBATTUR,93,1073000,"ROAD CUT RESTORATION BITUMINOUS MACADAM ROAD AT PADIKUPPAM RAIL NAGAR,MGR STREET IN DIV-93,UNIT-20,ZONE-7",Deposit Works,7,2019-20,2020-21 NG/2019-20/10478,Buildings,Completed,NG-AMBATTUR,93,145000,"DISMANTLING OF EXISTING COMMUNITY HALL AT SEETHAKATHI SALAI IN DN 93, UNIT - 20, ZONE - VII",Own Sources,7,2019-20,2020-21 NG/2019-20/11100,Parks,Completed,NG-AMBATTUR,93,268000,"FORMATION OF ROAD SIDE PARK AT PADIKUPPAM BURIAL GROUND ROAD IN DIV-93, UNIT-20, ZONE-7.",Own Sources,7,2019-20,2020-21 NG/2019-20/4020,Storm Water Drain,Completed,NG-AMBATTUR,93,965000,"DESILTING AND REPAIR OF ALL SWD AND SIDE DRAINS AT VARIOUS STREETS IN BUS ROUTE IN DN 93, UNIT- 20, ZONE -7",Own Sources,7,2019-20,2019-20 NG/2019-20/6070,Storm Water Drain,Completed,NG-AMBATTUR,93,635000,"DESILTING AND REPAIR OF ALL SWD AND SIDE DRAINS AT VARIOUS INTERIOR STREETS IRR-2 IN DIVISION -93,UNIT-20,ZONE -7",Own Sources,7,2019-20,2019-20 NG/2019-20/6072,Storm Water Drain,Completed,NG-AMBATTUR,93,500000,"DESILTING AND REPAIR OF ALL SWD AND SIDE DRAINS AT VARIOUS STREETS IN DN 93, UNIT- 20, ZONE -7",Own Sources,7,2019-20,2019-20 NG/2019-20/8768,Buildings,Completed,NG-AMBATTUR,93,476000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. in Division 93 RRC Unit - 20, Zone - 7",Own Sources,7,2019-20,2020-21 NG/2019-20/9432,Parks,Completed,NG-AMBATTUR,93,425000,"Annual Maintenance of GCC Parks for One year at Veeramamunivar Park in Dn 93, Unit-20, Zone-7 (per year)",Own Sources,7,2019-20,2020-21 BR/2019-20/0052,Road Cut,Completed,BR-Bus Route Roads,94,525000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-94, U-21, Zone-VIII",Deposit Works,8,2019-20,2019-20 BR/2019-20/10243,Roads,Completed,BR-Bus Route Roads,94,956000,"Restoration of Road Cut Made by OFC Providers in various Bus Route Roads Dn -94,95,99,100,101,102 & 103, Zone -8 Vide Deposit Code No.57/0451,0432,0589,0520,1053,1147,1145,1143/2018-19",Deposit Works,8,2019-20,2019-20 BR/2019-20/4932,Roads,Completed,BR-Bus Route Roads,94,2349000,"Partly relaying the road with BC after cold milling by paver finisher at MTH Road in Dn-94 & 95,Zone - VIII",Grants,8,2019-20,2020-21 BR/2019-20/5051,Roads,Completed,BR-Bus Route Roads,94,494000,"Partly relaying the road with BC after cold milling by paver finisher at Baliamman Koil Street in Dn-94,Zone - VIII",Grants,8,2019-20,2020-21 D/2019-20/9255,Storm Water Drain,Completed,D-Storm Water Drains,94,25870000,"Construction of Suspension Bridge at Villivalkkam Tank, Part 'A' Civil works for Pile, Pile Cap in Dn - 94, Zone VIII.",SMART CITY - SWD,8,2019-20,2021-22 NH/2019-20/0029,Buildings,Completed,NH-ANNA NAGAR,94,303000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CHENNAI PHYSICAL CENTER AT NORTH JAGANATHAN NAGAR 3RD STREET IN DIVISION-94, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/10542,Buildings,Completed,NH-ANNA NAGAR,94,486000,"DESILTING AND REPAIR WORK FOR COMMUNITY WELL AT ANJALI APPARTMENT (OSR LAND), MTH SERVICE ROAD IN DIVISION - 94, UNIT - 21, ZONE - 8",Own Sources,8,2019-20,2020-21 NH/2019-20/10585,Buildings,Completed,NH-ANNA NAGAR,94,899000,"IMPROVEMENTS TO THE CHENNAI MIDDLE SCHOOL AT SIVAN KOIL WEST MADA STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/10742,Buildings,Completed,NH-ANNA NAGAR,94,1452000,"CONSTRUCTION OF LABOUR REST ROOM AND IMPROVEMENT WORKS AT ELECTRICAL AE OFFICE AT SIDCO NAGAR 33RD STREEET IN DIVISION - 94, UNIT - 21, ZONE -8.",Own Sources,8,2019-20,2021-22 NH/2019-20/11482,Roads,Completed,NH-ANNA NAGAR,94,328000,"ANNUAL MAINTAINANCE OF ROADS AND STORM WATER DRAIN AT VARIOUS STREETS IN DN 94, UNIT 21, ZONE -8",Own Sources,8,2019-20,2020-21 NH/2019-20/11487,Buildings,Completed,NH-ANNA NAGAR,94,172000,"ANNUAL MAINTENANCE OF CHENNAI CORPORATION BUILDING AT VARIOUS LOCATIONS IN DN-94, UNIT 21, ZONE -8",Own Sources,8,2019-20,2020-21 NH/2019-20/12967,Roads,Completed,NH-ANNA NAGAR,94,1597600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THATHANKUPPAM MAIN ROAD (PART) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12968,Roads,Completed,NH-ANNA NAGAR,94,652400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NORTH JAGANNATHAN NAGAR 12TH STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13006,Roads,Completed,NH-ANNA NAGAR,94,324100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT RAMAMANDARAM STREET (PART ) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13007,Roads,Completed,NH-ANNA NAGAR,94,305400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SOUTH JAGANATHAN NAGAR 1ST MAIN ROAD (PART) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13008,Roads,Completed,NH-ANNA NAGAR,94,681300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BHARATHI NAGAR 2ND STREET (PART ) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13009,Roads,Completed,NH-ANNA NAGAR,94,392100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SIDCO NAGAR 8TH STREET (PART ) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13010,Roads,Completed,NH-ANNA NAGAR,94,284100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NORTH JAGANATHAN NAGAR 1ST MAIN ROAD (PART ) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13011,Roads,Completed,NH-ANNA NAGAR,94,543500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BALAMBIGAI NAGAR EXTENSION IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13012,Roads,Completed,NH-ANNA NAGAR,94,1248700,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SIDCO NAGAR L TYPE INDUSTRIAL ESTATE IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13013,Roads,Completed,NH-ANNA NAGAR,94,876300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VALLUVAR NAGAR IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13014,Roads,Completed,NH-ANNA NAGAR,94,494400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT RAJAMANGALAM 2ND STREET PART IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13017,Roads,Completed,NH-ANNA NAGAR,94,1012800,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT SIDCO NAGAR 38TH STREET (PART) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13031,Roads,Completed,NH-ANNA NAGAR,94,1424800,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT AMMAN KUTTAI 3RD STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13036,Roads,Completed,NH-ANNA NAGAR,94,1975700,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT RAJAMANGALAM 1ST STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13049,Roads,Completed,NH-ANNA NAGAR,94,1612400,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT RAJAMANGALAM 2ND STREET EXTENSION IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13051,Roads,Completed,NH-ANNA NAGAR,94,1944200,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT VELLERITHANGAL LANE IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13075,Roads,Completed,NH-ANNA NAGAR,94,286100,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT SIDCO NAGAR 22ND STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13078,Roads,Completed,NH-ANNA NAGAR,94,219600,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT SIDCO NAGAR 30TH STREET ( PART ) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13087,Roads,Completed,NH-ANNA NAGAR,94,762100,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT SIDCO NAGAR 55TH STREET IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13090,Roads,Completed,NH-ANNA NAGAR,94,528300,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT SIVAN KOIL KULAKARAI STREET (PART) IN DIVISION-94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/1613,Buildings,Completed,NH-ANNA NAGAR,94,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT R.K. LINK ROAD IN DIVISION -94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2079,Buildings,Completed,NH-ANNA NAGAR,94,457000,"PROVIDING WELL RINGS AT SIDCO NAGAR 1ST MAIN ROAD, SIDCO NAGAR 60TH STREET, NORTH JAGANATHAN NAGAR 1ST MAIN ROAD, NORTH JAGANATHAN NAGAR 3RD STREET (PLAY GROUND), SIDCO NAGAR 3RD MAIN ROAD, SIDCO NAGAR 10TH STREET, SIDCO NAGAR 42ND STREET, SIDCO NAGAR 50TH STREET, SIDCO NAGAR 51ST STREET (ANGANWADI), NORTH JAGANATHAN NAGAR 2ND MAIN ROAD, SIDCO NAGAR 4TH MAIN ROAD (OSR LAND) IN DIVISION-94, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/3555,Buildings,Completed,NH-ANNA NAGAR,94,2082000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT VILLIVAKKAM BURIAL GROUND IN DN-94, UNIT-21,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/3964,Buildings,Completed,NH-ANNA NAGAR,94,2130000,"Construction of New Noon Meal Center at Sidco Nagar 42nd street in Dn- 94, Unit-21, Zone- 8 (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/4558,Storm Water Drain,Completed,NH-ANNA NAGAR,94,484500,"DESILTING AND MINOR REPAIRS OF STORM WATER DRAIN IN BUS ROUTE ROADS AT VARIOUS STREETS IN DIVISION 94, UNIT 21, ZONE - 8",Own Sources,8,2019-20,2020-21 NH/2019-20/4862,Buildings,Completed,NH-ANNA NAGAR,94,1365500,"DESILTING AND MINOR REPAIRS OF STORM WATER DRAIN AT INTERIOR ROADS AT VARIOUS STREETS IN DIVISION- 94, UNIT 21 ZONE 8",Own Sources,8,2019-20,2019-20 NH/2019-20/6456,Buildings,Completed,NH-ANNA NAGAR,94,4100000,"IMPROVEMENTS WORK AT VILLIVAKKAM BURIAL GROUND IN DIVISION-94, UNIT-21, ZONE 8 (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/7171,Subway,Completed,NH-ANNA NAGAR,94,475000,"MAINTENANCE OF VILLIVAKAM SUBWAY FOR FOUR MONTHS IN DIVISION-94, UNIT-21, ZONE 8",Own Sources,8,2019-20,2019-20 NH/2019-20/7884,Subway,Completed,NH-ANNA NAGAR,94,100000,"DESILTING OF WELLS AND UNDERGROUND SUMP IN VILLIVAKKAM SUBWAY IN DN 94, UNIT- 21 , ZONE 8",Own Sources,8,2019-20,2020-21 NH/2019-20/8156,Roads,Completed,NH-ANNA NAGAR,94,800000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-94, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8157,Roads,Completed,NH-ANNA NAGAR,94,730000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-94, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8816,Subway,Completed,NH-ANNA NAGAR,94,103000,"ATTENDING PATCHES AT VILLIVAKKAM SUBWAY USING M40 CONCRETE IN DIVISION- 94, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9363,Buildings,Completed,NH-ANNA NAGAR,94,37000,"PROVIDING CHAIN LINK FENCING IN MTH ROAD (AS PER HIGH COURT DIRECTION ENCROACHMENT REMOVED AT DOOR NO 249 AND 250 MTH ROAD) IN DIVISION 94, UNIT 21, ZONE 8",Own Sources,8,2019-20,2020-21 P/2019-20/6884,Parks,Completed,P-Parks and Playfields,94,15119365,"FORMATION OF NEW PARK AT SIDCO NAGAR 4TH MAIN ROAD IN DN - 94, ZONE - VIII",Own Sources,8,2019-20,2020-21 BR/2019-20/0055,Road Cut,Completed,BR-Bus Route Roads,95,620000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-95, U-21, Zone-VIII",Deposit Works,8,2019-20,2019-20 BR/2019-20/5052,Roads,Completed,BR-Bus Route Roads,95,494000,"Partly relaying the road with BC after cold milling by paver finisher at Reddy Street in Dn-95,Zone - VIII",Grants,8,2019-20,2020-21 L/2019-20/10664,Electrical,Completed,L-Electrical,95,848800,"Supply and fixing of 182 nos of 10 W to 20 W LED Pathway fitting and 61 Nos 1mtr curved G.I Single bracket at park in div 94 ,95 and 99 under Villivakkam section and Anna nagar west section Zone VIII",Own Sources,8,2019-20,2021-22 L/2019-20/12225,Electrical,Completed,L-Electrical,95,573500,"Electrification of damaged wiring, tube light fittings and ceiling fans at Slaughter House , New Avadi Road , Villivakkam in div-95, Zone-VIII area.",Own Sources,8,2019-20,2020-21 NH/2019-20/0007,Buildings,Completed,NH-ANNA NAGAR,95,245000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE AMMAUNAVAGAM AT THANTHOUI AMMAN KOIL STREET IN DIVISION-95, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/0241,Buildings,Completed,NH-ANNA NAGAR,95,305000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE PUBLIC CONVENIENCE AT I.C.F ANNEX ROAD IN DIVISION-95,UNIT-21,ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/0243,Buildings,Completed,NH-ANNA NAGAR,95,305000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE SLAUGHTER HOUSE AT NEW AVADI ROAD IN DIVISION-95,UNIT-21,ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/11222,Roads,Completed,NH-ANNA NAGAR,95,814000,"IMPROVEMENTS TO THE INTERIOR BT ROADS W-BLOCK 19TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11371,Roads,Completed,NH-ANNA NAGAR,95,826000,"IMPROVEMENTS TO THE INTERIOR BT ROADS AT W BLOCK 20TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11372,Roads,Completed,NH-ANNA NAGAR,95,353000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT CHENNAI BATTAI 2ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11374,Roads,Completed,NH-ANNA NAGAR,95,176000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT NORTH THIRUMALAI NAGAR 4TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11377,Roads,Completed,NH-ANNA NAGAR,95,279000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT BAJANAI KOIL 3RD STREET IN DIVISION-95, UNIT-21, ZONE-08",Own Sources,8,2019-20,2020-21 NH/2019-20/12768,Buildings,Completed,NH-ANNA NAGAR,95,360800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PONNANKIANRU STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12769,Buildings,Completed,NH-ANNA NAGAR,95,170500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BAZAAR STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12770,Buildings,Completed,NH-ANNA NAGAR,95,622400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THIRUMANGALAM ROAD (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12771,Buildings,Completed,NH-ANNA NAGAR,95,662100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AGATHIAR NAGAR M BLOCK 3RD STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12772,Buildings,Completed,NH-ANNA NAGAR,95,567300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AGATHIAR NAGAR 31ST STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12773,Buildings,Completed,NH-ANNA NAGAR,95,789500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT HIGH COURT COLONY MAIN ROAD IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12774,Buildings,Completed,NH-ANNA NAGAR,95,253500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AGATHIAR NAGAR 32ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12775,Buildings,Completed,NH-ANNA NAGAR,95,662400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 11TH STREET(PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12776,Buildings,Completed,NH-ANNA NAGAR,95,312200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 2ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12777,Buildings,Completed,NH-ANNA NAGAR,95,261400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 3RD STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12778,Buildings,Completed,NH-ANNA NAGAR,95,427000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 9TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12779,Buildings,Completed,NH-ANNA NAGAR,95,566900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT METTU STREET 1ST LANE IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12780,Buildings,Completed,NH-ANNA NAGAR,95,409800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 7TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12782,Buildings,Completed,NH-ANNA NAGAR,95,483200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 29TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12783,Buildings,Completed,NH-ANNA NAGAR,95,483200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 30TH STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12784,Buildings,Completed,NH-ANNA NAGAR,95,921400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 18TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12785,Buildings,Completed,NH-ANNA NAGAR,95,236600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 19TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12786,Buildings,Completed,NH-ANNA NAGAR,95,236600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 20TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12788,Buildings,Completed,NH-ANNA NAGAR,95,236600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 21ST STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12789,Buildings,Completed,NH-ANNA NAGAR,95,529600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 25TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12791,Buildings,Completed,NH-ANNA NAGAR,95,548700,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I-BLOCK 35TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12792,Buildings,Completed,NH-ANNA NAGAR,95,405600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MULLAI NAGAR 1ST STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12793,Buildings,Completed,NH-ANNA NAGAR,95,726900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MULLAI NAGAR 2ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12794,Buildings,Completed,NH-ANNA NAGAR,95,1045800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NARAYANA MAISTRY 1ST STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12795,Buildings,Completed,NH-ANNA NAGAR,95,480600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MULLAI NAGAR 3RD STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12796,Buildings,Completed,NH-ANNA NAGAR,95,745100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MULLAI NAGAR 10TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12797,Buildings,Completed,NH-ANNA NAGAR,95,387600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT RADHAKRISHNAN STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12799,Buildings,Completed,NH-ANNA NAGAR,95,42600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MULLAI NAGAR 12TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12800,Buildings,Completed,NH-ANNA NAGAR,95,718000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VASANTHAM COLONY 6TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12823,Buildings,Completed,NH-ANNA NAGAR,95,1074900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W-BLOCK 2ND AVENUE (WEST EXTN) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12824,Buildings,Completed,NH-ANNA NAGAR,95,270100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT RAJAGOPALAN STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12826,Grade Separator,Completed,NH-ANNA NAGAR,95,431100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THIRUNAGAR 5TH STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12827,Buildings,Completed,NH-ANNA NAGAR,95,980400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VASANTHAM COLONY 1ST STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12828,Buildings,Completed,NH-ANNA NAGAR,95,980400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VASANTHAM COLONY 2ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12829,Buildings,Completed,NH-ANNA NAGAR,95,820500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VASANTHAM COLONY 4TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12830,Buildings,Completed,NH-ANNA NAGAR,95,662600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VASANTHAM COLONY 5TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12853,Buildings,Completed,NH-ANNA NAGAR,95,298400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT EMAYAM COLONY 1ST STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12854,Buildings,Completed,NH-ANNA NAGAR,95,377800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MULLAI NAGAR 7TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12856,Buildings,Completed,NH-ANNA NAGAR,95,641800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W-BLOCK 1ST STREET (C SECTOR) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12857,Buildings,Completed,NH-ANNA NAGAR,95,389200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W-BLOCK 2ND STREET (C SECTOR) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12858,Buildings,Completed,NH-ANNA NAGAR,95,641800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W-BLOCK 16TH STREET (C SECTOR) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12859,Buildings,Completed,NH-ANNA NAGAR,95,347100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W-BLOCK 17TH STREET (C SECTOR) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12860,Buildings,Completed,NH-ANNA NAGAR,95,358800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W-BLOCK 18TH STREET (C SECTOR) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12861,Buildings,Completed,NH-ANNA NAGAR,95,1337500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SANNATHI STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12862,Buildings,Completed,NH-ANNA NAGAR,95,480100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT METTU STREET LANE (MTH ROAD LANE ) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12863,Buildings,Completed,NH-ANNA NAGAR,95,1464100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SOUTH MADA STREET (PART) IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12866,Grade Separator,Completed,NH-ANNA NAGAR,95,634900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I BLOCK 6TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12867,Buildings,Completed,NH-ANNA NAGAR,95,330600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I - BLOCK 22ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12870,Buildings,Completed,NH-ANNA NAGAR,95,322600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THIRUNAGAR 20TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12871,Buildings,Completed,NH-ANNA NAGAR,95,1842800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VASANTHAM COLONY 3RD STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/1585,Buildings,Completed,NH-ANNA NAGAR,95,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY CENTER AT NEW AVADI ROAD IN DIV -95, UNIT-21,ZONE -8",Own Sources,8,2019-20,2019-20 NH/2019-20/2041,Buildings,Completed,NH-ANNA NAGAR,95,679000,"PROVIDING WELL RINGS PARK AT I BLOCK 38TH STREET, I BLOCK 2ND STREET W BLOCK GANDHI PARK , THIRU NAGAR PARK IN DIVISION - 95, UNIT - 21 , ZONE - 08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2043,Buildings,Completed,NH-ANNA NAGAR,95,331000,"PROVIDING AND SUPPLYING MULCH PIT AT I BLOCK 2ND STREET , I BLOCK 38TH STREET , W BLOCK GANDHI PARK , THIRU NAGAR PARK IN DIVISION-95, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2044,Buildings,Completed,NH-ANNA NAGAR,95,152000,"PROVIDING AND SUPPLYING BAMBOO MULCH PIT AT I BLOCK 7TH STREET , I BLOCK 28TH STREET , I BLOCK 18TH STREET , I BLOCK 34TH STREET , MULLAI NAGAR 6TH STREET , VASANTHAM COLONY 1ST STREET , VASANTHAM COLONY 3RD STREET , AGATHIYAR NAGAR 3RD STREET , AGATHIYAR NAGAR 9TH STREET , AGATHIYAR NAGAR 12TH STREET , THIRUMANGALAM ROAD PARK AND PLAY GROUND IN DIVISION-95, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/3327,Buildings,Completed,NH-ANNA NAGAR,95,1254000,"SUPPLYING AND FIXING OF PLAY APPARATUS AND GYM EQUIPMENTS FOR VALAIYAN KULAM AT MANNADI OTHAVADAI STREET IN DIV-95, UNIT-21, ZONE-8 (MLA FUND 2018-19)",MLACDS,8,2019-20,2020-21 NH/2019-20/3968,Buildings,Completed,NH-ANNA NAGAR,95,900000,"PROVIDING GYM EQUIPMENT AT THIRU NAGAR PARK IN DIVISION - 95, UNIT - 21, ZONE - 08. (MP FUND)",MPLADS,8,2019-20,2020-21 NH/2019-20/5944,Storm Water Drain,Completed,NH-ANNA NAGAR,95,2296600,"DESILTING AND MINOR REPAIRS TO VARIOUS INTERIOR ROAD IN VILLIVAKKAM AREA IN DIVISION-95, UNIT-21, ZONE-VIII",Own Sources,8,2019-20,2020-21 NH/2019-20/5973,Storm Water Drain,Completed,NH-ANNA NAGAR,95,1925500,"DESILTING AND MINOR REPAIRS TO VARIOUS INTERIOR ROAD IN ANNA NAGAR, THIRU NAGAR AND AGATHIAR NAGAR IN DIVISION-95, UNIT-21, ZONE-VIII",Own Sources,8,2019-20,2020-21 NH/2019-20/5974,Storm Water Drain,Completed,NH-ANNA NAGAR,95,445500,"DESILTING AND MINOR REPAIRS TO VARIOUS BUS ROUTE ROAD IN DIVISION-95, UNIT-21, ZONE-VIII",Own Sources,8,2019-20,2019-20 NH/2019-20/7371,Parks,Completed,NH-ANNA NAGAR,95,1181000,"ANNUAL MAINTENANCE OF PARK AT THIRU NAGAR 13TH BLOCK, 11TH STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7372,Parks,Completed,NH-ANNA NAGAR,95,887000,"ANNUAL MAINTENANCE OF PARK AT I BLOCK 2ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7373,Parks,Completed,NH-ANNA NAGAR,95,698000,"ANNUAL MAINTENANCE OF PARK AT I BLOCK 38TH STREET IN DIVISION 95, UNIT-21, ZONE 8",Own Sources,8,2019-20,2021-22 NH/2019-20/7374,Parks,Completed,NH-ANNA NAGAR,95,920000,"ANNUAL MAINTENANCE OF PARK AT W BLOCK C SECTOR 2ND STREET IN DIVISION-95, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8159,Roads,Completed,NH-ANNA NAGAR,95,740000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-95, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8160,Roads,Completed,NH-ANNA NAGAR,95,249000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-95, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/0031,Buildings,Completed,NH-ANNA NAGAR,96,386000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO CHENNAI PRIMARY SCHOOL AT PALAVAYAL STREET, AYANAVARAM IN WARD-96, UNIT-21, ZONE-VIII",Own Sources,8,2019-20,2019-20 NH/2019-20/0036,Buildings,Completed,NH-ANNA NAGAR,96,395000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO ASSISTANT EXECUTIVE ENGINEER, UNIT-21 OFFICE, AT UNITED INDIA NAGAR 1ST MAIN ROAD, AYANAVARAM IN DIVISION-96, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/11335,Roads,Completed,NH-ANNA NAGAR,96,750000,"FORMING, STRENGTHENING AND LAYING THE ROAD AT AV KOIL 2ND STREET IN DIVISION - 96 UNIT - 21 ZONE- 8 (MLA FUNDS)",MLACDS,8,2019-20,2020-21 NH/2019-20/11437,Roads,Completed,NH-ANNA NAGAR,96,771000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT ANNAI INDRA NAGAR IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/1145,Buildings,Completed,NH-ANNA NAGAR,96,198000,"PROVIDING WELL RINGS AT OSR PARK AT KONNUR HIGH ROAD (SUNNYVALE APARTMENTS), JEEVA PARK AT UNITED INDIA NAGAR, CHSS PALAVAYAL STREET, KONNUR HIGH ROAD IN DIVISION-96, UNIT-21, ZONE-VIII",Own Sources,8,2019-20,2019-20 NH/2019-20/1148,Parks,Completed,NH-ANNA NAGAR,96,164000,"PROVIDING BAMBOO MULCH PIT IN OSR PARK AT KONNUR HIGH ROAD (SUNNYVALE APARTMENTS), JEEVA PARK AT UNITED INDIA NAGAR IN DIVISION-96, UNIT-21, ZONE-VIII",Own Sources,8,2019-20,2019-20 NH/2019-20/12648,Roads,Completed,NH-ANNA NAGAR,96,1026000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT P.E. KOIL WEST MADA STREET IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12654,Roads,Completed,NH-ANNA NAGAR,96,448000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT P.E KOIL NORTH MADA STREET (PART) IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12663,Roads,Completed,NH-ANNA NAGAR,96,428000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT MUTHAMMAN NAGAR IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13024,Roads,Completed,NH-ANNA NAGAR,96,421200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT V.P.COLONY ANGADI STREET IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13055,Roads,Completed,NH-ANNA NAGAR,96,552800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PALAVAYAL ROAD IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/14202,Buildings,Completed,NH-ANNA NAGAR,96,74000,"Providing Two broken manhole doors at ponnusamy street junction and Improvements to MCC (Sayani Park) in Division - 96, Unit- 21, Zone-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/2742,Buildings,Completed,NH-ANNA NAGAR,96,386000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT CHENNAI HIGHER SECONDARY SCHOOL, AYANAVARAM IN WARD-96, UNIT-21, ZONE-VIII",Own Sources,8,2019-20,2019-20 NH/2019-20/3272,Buildings,Completed,NH-ANNA NAGAR,96,1940000,"IMPROVEMENT TO CHENNAI CORPORATION HR.SEC.SCHOOL AND CHENNAI CORPORATION PRIMARY SCHOOL IN PALAVAYOL STREET IN DIVISION - 96, UNIT - 21, ZONE - 8",Own Sources,8,2019-20,2021-22 NH/2019-20/3340,Parks,Completed,NH-ANNA NAGAR,96,482000,"IMPROVEMENTS TO JEEVA PARK AND SAYANI PARK IN DIVISION - 96, UNIT- 21, ZONE -8",Own Sources,8,2019-20,2020-21 NH/2019-20/4011,Buildings,Completed,NH-ANNA NAGAR,96,2620000,"Construction of Auditorium Stage in Palavoyal Hr.Sec.School (MLA Fund) in Div-96,Un-21,Z-08",MLACDS,8,2019-20,2020-21 NH/2019-20/4012,Buildings,Completed,NH-ANNA NAGAR,96,1380000,"Construction of Kitchen Shed and dinning area in Palavoyal Hr.Sec.School (MLA Fund) in Dn-96,U-21,Zn-08",MLACDS,8,2019-20,2020-21 NH/2019-20/4499,Roads,Completed,NH-ANNA NAGAR,96,1453000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT NEW STREET IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/4651,Buildings,Completed,NH-ANNA NAGAR,96,1330000,"Improvement to UPHC at Officers Colony In Div-96,U-21,Z-08",Own Sources,8,2019-20,2021-22 NH/2019-20/5000,Buildings,Completed,NH-ANNA NAGAR,96,2490000,"Improvements to Street Light AE Office at Konnur High Road In Division-96, Unit-21, Zone-08.",Own Sources,8,2019-20,2021-22 NH/2019-20/5918,Storm Water Drain,Completed,NH-ANNA NAGAR,96,1968500,"Desilting and Minor Repair Work and Improvement Storm Water Drain at Interior Roads in Division-96,Unit-21,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/5919,Storm Water Drain,Completed,NH-ANNA NAGAR,96,1997500,"Desilting and Minor Repair Work and Improvement Storm Water Drain at BRR Road in Division-96,Unit-21,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/6327,Buildings,Completed,NH-ANNA NAGAR,96,350000,"IMPROVEMENTS TO PUBLIC TOILET AT ICF ROAD, KONNUR HIGH ROAD, KK NAGAR 5TH STREET IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/7368,Parks,Completed,NH-ANNA NAGAR,96,263000,"ANNUAL MAINTENANCE OF JEEVA PARK AT UNITED INDIA NAGAR IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7370,Parks,Completed,NH-ANNA NAGAR,96,614000,"ANNUAL MAINTENANCE OF OSR LAND PARK AT KONNUR HIGH ROAD IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8161,Roads,Completed,NH-ANNA NAGAR,96,935000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-96, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/8162,Roads,Completed,NH-ANNA NAGAR,96,200000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-96, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/9376,Buildings,Completed,NH-ANNA NAGAR,96,625000,REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE-96 AT OFFICERS COLONY ROAD IN DIVISION-96 UNIT-21 ZONE-8,Own Sources,8,2019-20,2020-21 NH/2019-20/9377,Buildings,Completed,NH-ANNA NAGAR,96,560000,"PROVIDING PARTITION WORK IN UPHC AT UNITED INDIA NAGAR 1ST CROSS STREET IN DIVISION-96, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/0005,Buildings,Completed,NH-ANNA NAGAR,97,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CPS SCHOOL AT SABAPATHI STREET IN DIVISION-97, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/0976,Buildings,Completed,NH-ANNA NAGAR,97,216000,"General Election to Parliament (Lok Sabha) 2019 - Providing facilities for Election Strong Room Arrangements at Vellala street (CPS) in Div-97, unit-21, Zone-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/10189,Buildings,Completed,NH-ANNA NAGAR,97,118000,"IMPROVEMENTS TO COMPOST YARD AT KUNCHITHAM GURUSWAMY STREET, THANTHAI PERIYAR NAGAR 1 ST STREET, MUTHAMMAN KOIL STREET AND VELLALA STREET SCHOOL IN DIVISION-97, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/10540,Buildings,Completed,NH-ANNA NAGAR,97,690000,"PROVIDING SHED FOR BAILING MACHINE AT VELLALA STREET (CPS) IN DIVISION-97, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/10668,Electrical,Completed,NH-ANNA NAGAR,97,288000,"PROVIDING BALING MACHINE OPERATOR FOR ONE YEAR AT VELLALA STREET (CPS SCHOOL) IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11737,Buildings,Completed,NH-ANNA NAGAR,97,225000,"IMPROVEMENT TO COMPOST YARD AT MUTHUAMMAN KOIL MAIN STREET, THANDAI PERIYAR NAGAR AND KUNJITHAM GURUSAMY STREET IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/13168,Roads,Completed,NH-ANNA NAGAR,97,1305000,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT RAMASAMY STREET IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13171,Roads,Completed,NH-ANNA NAGAR,97,543700,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT SEETHA THOPU IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13172,Roads,Completed,NH-ANNA NAGAR,97,495200,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT VELLALA STREET LANE IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13258,Roads,Completed,NH-ANNA NAGAR,97,602800,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT P.E KOIL 2ND LANE IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13259,Roads,Completed,NH-ANNA NAGAR,97,377600,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT BOOPATHY NAGAR LANE IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13262,Roads,Completed,NH-ANNA NAGAR,97,944500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BHARATHI NAGAR IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13264,Roads,Completed,NH-ANNA NAGAR,97,491400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT P.E KOIL NORTH MADA STREET (PART) IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/14221,Storm Water Drain,Completed,NH-ANNA NAGAR,97,70000,"IMPROVEMENT TO STORM WATER DRAIN AT SOLAI MAIN STREET AND SABAPATHY STREET IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/14224,Roads,Completed,NH-ANNA NAGAR,97,85000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DIV-97, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/14357,Electrical,Completed,NH-ANNA NAGAR,97,120000,"REPAIRS AND IMPROVEMENTS, PROVIDING ELECTRICAL ARRANGEMENTS TO COMPOST YARD AT MUTHUMARIAMMAN KOIL MAIN STREET IN DN-97, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/2040,Parks,Completed,NH-ANNA NAGAR,97,217000,"PROVIDING WELL RING AT VELLALA STREET SCHOOL AND PACHIKKAL VEERASAMY STREET PARK IN DIVISION-97, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/2055,Parks,Completed,NH-ANNA NAGAR,97,141000,"PROVIDING MULCH PIT AT CHENNAI PRIMARY SCHOOL, VELLALA STREET AND METRO WATER TANK IN DIVISION-97, UNIT-21, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/2065,Buildings,Completed,NH-ANNA NAGAR,97,590000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY CENTER AT VELLALA STREET IN DIV -97, UNIT-21,ZONE -8",Own Sources,8,2019-20,2019-20 NH/2019-20/2561,Buildings,Completed,NH-ANNA NAGAR,97,200000,"IMPROVEMENT WORKS TO ICDS CENTER NO:33603050213 AT PACHAKKAL VEERASAMY STREET IN DIVISION-97, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/3209,Buildings,Completed,NH-ANNA NAGAR,97,614000,"REPAIR AND IMPROVEMENT TO DESILTING WORK RAIN WATER HARVESTING WELL RING AT VARIOUS STREETS IN DN-97, U-21, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/3210,Buildings,Completed,NH-ANNA NAGAR,97,124000,"REPAIR AND IMPROVEMENT TO WELL AT PACHAIKAL VEERASAMY STREET (TNSB) IN DN-97, U-21, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/6024,Storm Water Drain,Completed,NH-ANNA NAGAR,97,1585500,"DESILTING OF STORM WATER DRAIN AND IMPROVEMENTS WORKS AT VARIOUS STREET IN DIV-97, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/7006,Buildings,Completed,NH-ANNA NAGAR,97,610000,"REPAIRS AND IMPROVEMENT WORKS TO THE CHENNAI PRIMARY SCHOOL AT VELLALA STREET IN DIV-97, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/7362,Parks,Completed,NH-ANNA NAGAR,97,879000,"ANNUAL MAINTENANCE OF PARK AT VELLALA STREET IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7363,Parks,Completed,NH-ANNA NAGAR,97,600000,"ANNUAL MAINTENANCE OF PARK AT PACHAIKAL VEERASAMY STREET IN DIVISION-97, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8034,Storm Water Drain,Completed,NH-ANNA NAGAR,97,3000000,"CONSTRUCTION OF STORM WATER DRAIN AT BHARATHI NAGAR, AND DRAIN LINKED TO PACHAIKAL VEERASAMY STREET (TNSB) WELL IN DIVISION-97, UNIT-21, ZONE-08. (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/8154,Roads,Completed,NH-ANNA NAGAR,97,285000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-97, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/8155,Roads,Completed,NH-ANNA NAGAR,97,69000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-97, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/8663,Storm Water Drain,Completed,NH-ANNA NAGAR,97,3000000,"CONSTRUCTION OF STORM WATER DRAIN AT PACHAIKAL VEERASAMY STREET (TNSB) WELL AND WELL CONVERSION TO RAIN WATER HARVESTING IN DIVISION-97, UNIT-21, ZONE-08. (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/11252,Buildings,Completed,NH-ANNA NAGAR,98,232000,"Providing RWH in Division office , RWH Improvement woprk in Aspiran Garden 1st & 2nd street Compost yard Improvement work in Aspiran Garden 1st street in Division-98, Unit-23, Zone-08",Own Sources,8,2019-20,2020-21 NH/2019-20/13103,Buildings,Completed,NH-ANNA NAGAR,98,346000,"Providing rain water harvesting near Division Office (2nos) and Improvements to MCC (Sayani Park) in Division - 96, Unit - 21, Zone -08.",Own Sources,8,2019-20,2020-21 NH/2019-20/13104,Buildings,Completed,NH-ANNA NAGAR,98,80000,"School broken compound Wall at Palavoyal Street in Division - 96, Unit- 21, Zone-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/13141,Roads,Completed,NH-ANNA NAGAR,98,584500,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT NEELKANDAN STREET IN DIVISION-98, UNIT-23, ZONE-8,",Own Sources,8,2019-20,2020-21 NH/2019-20/13163,Roads,Completed,NH-ANNA NAGAR,98,923400,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT PUDU NAGAR EXTN IN DIVISION-98, UNIT-23, ZONE-8,",Own Sources,8,2019-20,2020-21 NH/2019-20/13164,Roads,Completed,NH-ANNA NAGAR,98,2099600,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT UJJINI DEVI STREET IN DIVISION-98, UNIT-23, ZONE-8,",Own Sources,8,2019-20,2020-21 NH/2019-20/2195,Buildings,Completed,NH-ANNA NAGAR,98,74000,"PROVIDE WELL RING AT DIVISION OFFICE (ASPIRAN GARDEN 1ST STREET) IN DN-98, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/5924,Storm Water Drain,Completed,NH-ANNA NAGAR,98,1238500,"Desilting and minor repair and Improvement work Storm Water Drain at Interior Roads in Division-98,Unit-23,Zone-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/6064,Roads,Completed,NH-ANNA NAGAR,98,260000,"Attenting Patch Work Mettu Street In Division-98,Unit-23,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/6289,Roads,Completed,NH-ANNA NAGAR,98,2970000,"Laying Cement Concrete Road at Police Manickam Street In Division-98,Unit-23,Zone-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/8151,Roads,Completed,NH-ANNA NAGAR,98,196000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-98, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/8152,Roads,Completed,NH-ANNA NAGAR,98,1050000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-98, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8572,Buildings,Completed,NH-ANNA NAGAR,98,390000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND ADDITIONAL IMPROVEMENTS TO SAMYDOSSPURAM, PUMPING STATION COMMUNITY TOILET AND NAMMA TOILET AT ASPIRAN GARDEN FIRST STREET IN DIVISION - 98, UNIT - 23, ZONE - 8",Own Sources,8,2019-20,2019-20 NH/2019-20/9743,Buildings,Completed,NH-ANNA NAGAR,98,254000,PROVIDING WATER SUPPLY AND ADDITIONAL IMPROVEMENTS TO ASSISTANT ENGINEER DIVISION OFFICE WORKERS TOILET IN DIVISION-98 UNIT-23 ZONE-8,Own Sources,8,2019-20,2019-20 BR/2019-20/0056,Road Cut,Completed,BR-Bus Route Roads,99,441000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-99, U-21, Zone-VIII",Deposit Works,8,2019-20,2019-20 BR/2019-20/17855,Road Cut,Completed,BR-Bus Route Roads,99,150000,"RESTORATION OF OFC ROADCUT 18 NOS OF INTERIOR ROADS AT VARIOUS DIV - 97,99,100,101 & 102. IN ZONE - 8.",Deposit Works,8,2019-20,2021-22 BR/2019-20/5053,Roads,Completed,BR-Bus Route Roads,99,988000,"Partly relaying the road with BC after cold milling by paver finisher at Anna Nagar 4th Avenue in Dn-99 & 100, Zone - VIII",Grants,8,2019-20,2020-21 NH/2019-20/0030,Parks,Completed,NH-ANNA NAGAR,99,150000,"PROVIDING BAMBOO MULCH PIT IN BPCL PARK AND RBI PARK AT 15TH MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/0032,Parks,Completed,NH-ANNA NAGAR,99,258000,"PROVIDING WELL RING IN RBI PARK ,BPCL PARK AT 15TH MAIN ROAD,AF BLOCK 8TH STREET PLAY GROUND,J BLOCK 10 TH STREET, KADHIRAVAN COLONY PARK,H BLOCK 15TH STREET,APPU COLONY PARK IN DIVISION-99, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/10225,Buildings,Completed,NH-ANNA NAGAR,99,519000,"IMPROVEMENTS TO COMPOST YARD AT 6TH AVENUE JUNCTION OF 5TH AVENUE IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11749,Parks,Completed,NH-ANNA NAGAR,99,119000,"REPAIRS & IMPROVEMENTS TO ANGANWADI BUILDING & AMMA UNAVAGAM AT VARIOUS LOCATION IN DIVISION - 99, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/11750,Parks,Completed,NH-ANNA NAGAR,99,83500,"REPAIRS AND IMPROVEMENT TO GROUP BINS AT VARIOUS LOCATION IN DIVISION NUMBER 99, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/12127,Buildings,Completed,NH-ANNA NAGAR,99,297000,"PROVIDING RAIN WATER HARVESTING AND WIRE FENCING AT VARIOUS LOCATION IN DIVISION- 99, UNIT-21,ZONE-08",Own Sources,8,2019-20,2020-21 NH/2019-20/12668,Roads,Completed,NH-ANNA NAGAR,99,501000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT RAJAJI STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12669,Roads,Completed,NH-ANNA NAGAR,99,953000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT PILLAYAR KOIL STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12670,Roads,Completed,NH-ANNA NAGAR,99,597000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT 6TH AVENUE IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12671,Roads,Completed,NH-ANNA NAGAR,99,311000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT 5TH AVENUE & 6TH AVENUE (FROM TNEB TO CMWSSB PUMPING STATION) IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13335,Roads,Completed,NH-ANNA NAGAR,99,1398900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AF BLOCK 8TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13337,Roads,Completed,NH-ANNA NAGAR,99,1203300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT G BLOCK 2ND STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13338,Roads,Completed,NH-ANNA NAGAR,99,451300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 11TH MAIN ROAD( 2ND AVENUE TO 15TH MAIN ROAD ) IN DIVISION-99, UNIT-21, ZONE-08",Own Sources,8,2019-20,2020-21 NH/2019-20/13339,Roads,Completed,NH-ANNA NAGAR,99,263200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT THANGAM COLONY 1ST STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13340,Roads,Completed,NH-ANNA NAGAR,99,990300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 12TH MAIN ROAD PART (4TH AVENUE TO 2ND AVENUE ) IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/1341,Buildings,Completed,NH-ANNA NAGAR,99,294000,"PROPOSED CONSTRUCTION OF MATRIAL RECOVERY FACILITY AT 6TH AVENUE IN DIVISION -99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2777,Buildings,Completed,NH-ANNA NAGAR,99,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT CPS ( TV NAGAR ) IN DIVISION- 99 UNIT-21,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/6030,Storm Water Drain,Completed,NH-ANNA NAGAR,99,1211500,"DESILTING OF STORM WATER DRAIN AND IMPROVEMENTS WORKS (IRR) AT VARIOUS STREET IN DIV-99, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/6032,Storm Water Drain,Completed,NH-ANNA NAGAR,99,518500,"DESILTING OF STORM WATER DRAIN AND IMOROVEMENTS WORKS (BRR) AT VARIOUS STREET IN DIV-99, UNIT-21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/7364,Parks,Completed,NH-ANNA NAGAR,99,890000,"ANNUAL MAINTENANCE OF BPCL PARK AT 15TH MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7365,Parks,Completed,NH-ANNA NAGAR,99,859000,"ANNUAL MAINTENANCE OF RBI PARK AT 15TH MAIN ROAD IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8149,Roads,Completed,NH-ANNA NAGAR,99,996000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-99, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8150,Roads,Completed,NH-ANNA NAGAR,99,125000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-99, UNIT 21, ZONE-08.",Own Sources,8,2019-20,2020-21 BR/2019-20/0057,Road Cut,Completed,BR-Bus Route Roads,100,820000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-100, U-22, Zone-VIII",Deposit Works,8,2019-20,2019-20 BR/2019-20/17856,Road Cut,Completed,BR-Bus Route Roads,100,350000,"RESTORATION OF OFC ROADCUT 18 NOS OF INTERIOR ROADS AT VARIOUS DIV - 97,99,100,101 & 102. IN ZONE - 8.",Deposit Works,8,2019-20,2021-22 BR/2019-20/5049,Roads,Completed,BR-Bus Route Roads,100,3457000,Partly relaying the road with BC after cold milling by paver finisher at Anna Nagar 3rd Avenue in Dn-100 & 101 Zone - VIII,Grants,8,2019-20,2020-21 BR/2019-20/5050,Roads,Completed,BR-Bus Route Roads,100,494000,"Partly relaying the road with BC after cold milling by paver finisher at Anna Nagar 5th Avenue in Dn-100,Zone - VIII",Grants,8,2019-20,2020-21 BR/2019-20/5057,Roads,Completed,BR-Bus Route Roads,100,2469000,"Partly relaying the road with BC after cold milling by paver finisher at New Avadi Road in Dn- 100,101 & 102,Zone - VIII",Grants,8,2019-20,2020-21 L/2019-20/14592,Electrical,Completed,L-Electrical,100,6181300,"Supply and Erection of 66 Nos of 8mtr Lamp post with 150W LED Fittings, 2316Mtrs of 3 1/2 x25sqmm UG Cable, 1724Mtrs of 50MM OD HDPE Pipe at Newly proposed Centre mediun formed by Department of Highways at EVR Periyar salai by Deposite work in div 100 Zone VIII.",Deposit Works,8,2019-20,2020-21 NH/2019-20/0872,Parks,Completed,NH-ANNA NAGAR,100,680000,CONSTRUCTION OF RESOURCE RECOVERY CENTER AT 6TH AVENUE IN DIVISION 100 UNIT 22 ZONE 08,Own Sources,8,2019-20,2019-20 NH/2019-20/0876,Buildings,Completed,NH-ANNA NAGAR,100,185000,CONSTRUCTION OF RESOURCE RECOVERY CENTER AT DIVISION OFFICE IN DIVISION 100 UNIT 22 ZONE 08,Own Sources,8,2019-20,2019-20 NH/2019-20/0883,Parks,Completed,NH-ANNA NAGAR,100,89000,CONSTRUCTION OF RESOURCE RECOVERY CENTER AT NSK NAGAR BURIAL GROUND IN DIVISION 100 UNIT 22 ZONE 08,Own Sources,8,2019-20,2019-20 NH/2019-20/10374,Buildings,Completed,NH-ANNA NAGAR,100,148000,"IMPROVEMENTS TO COMPOST YARD AT ARUMBAKKAM BURIAL GROUND AND 6 TH AVENUE IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/10613,Roads,Completed,NH-ANNA NAGAR,100,298000,"IMPROVEMENT TO THE EXISTING FOOT PATH AT HALLS ROAD IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12623,Roads,Completed,NH-ANNA NAGAR,100,351000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT U BLOCK 10TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12625,Roads,Completed,NH-ANNA NAGAR,100,975000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT U BLOCK 6TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12626,Roads,Completed,NH-ANNA NAGAR,100,508000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT AB BLOCK 3RD STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12627,Roads,Completed,NH-ANNA NAGAR,100,388000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT AC BLOCK 3RD STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12628,Roads,Completed,NH-ANNA NAGAR,100,466000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT X BLOCK 5TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12633,Roads,Completed,NH-ANNA NAGAR,100,267000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT Y BLOCK 5TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12634,Roads,Completed,NH-ANNA NAGAR,100,466000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT Z BLOCK 10TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12635,Roads,Completed,NH-ANNA NAGAR,100,777000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT AJ BLOCK 1ST STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12636,Roads,Completed,NH-ANNA NAGAR,100,742000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT V BLOCK 13TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12637,Roads,Completed,NH-ANNA NAGAR,100,586000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT 4TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12638,Roads,Completed,NH-ANNA NAGAR,100,1421000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT 9TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12639,Roads,Completed,NH-ANNA NAGAR,100,630000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BAJANAI KOIL STREET (WEST) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12640,Roads,Completed,NH-ANNA NAGAR,100,311000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT 14TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12642,Roads,Completed,NH-ANNA NAGAR,100,311000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT 5TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12643,Roads,Completed,NH-ANNA NAGAR,100,777000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT AJ BLOCK 2ND STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12644,Roads,Completed,NH-ANNA NAGAR,100,466000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT Y BLOCK 9TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12645,Roads,Completed,NH-ANNA NAGAR,100,223000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT NSK NAGAR 1ST STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12646,Roads,Completed,NH-ANNA NAGAR,100,223000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT NSK NAGAR 3RD STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12647,Roads,Completed,NH-ANNA NAGAR,100,111000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT NSK NAGAR 17TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13307,Roads,Completed,NH-ANNA NAGAR,100,705100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 3RD MAIN ROAD (FROM 4TH MAIN ROAD JN. TO T BLOCK 11TH STREET AND FROM U BLOCK 7TH STREET TO 5TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13309,Roads,Completed,NH-ANNA NAGAR,100,448100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT R-BLOCK 15TH STREET (FROM 6TH AVENUE TO DOOR NO:48/17) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13310,Roads,Completed,NH-ANNA NAGAR,100,1908400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 6TH MAIN ROAD (FROM 4TH MAIN ROAD JN. TO 5TH MAIN ROAD JN.AND FROM 2ND AVENUE TO Y-226) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13317,Roads,Completed,NH-ANNA NAGAR,100,78300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 7TH MAIN ROAD (AH BLOCK 3RD STREET JN.) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13321,Roads,Completed,NH-ANNA NAGAR,100,219400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AG BLOCK 5TH STREET (FROM BEREWARY ROAD TO AG BLOCK 3RD STREET) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13322,Roads,Completed,NH-ANNA NAGAR,100,376000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 8TH MAIN ROAD (FROM AI BLOCK 2ND STREET JN. TO AI-127) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13323,Roads,Completed,NH-ANNA NAGAR,100,188000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AH BLOCK 1ST STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13324,Roads,Completed,NH-ANNA NAGAR,100,814800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 10TH MAIN ROAD (FROM 4TH AVENUE TO AD- 37 AND FROM AJ BLOCK 1ST STREET TO 7TH MAIN ROAD) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13325,Roads,Completed,NH-ANNA NAGAR,100,255700,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AD BLOCK 5TH STREET (FROM AD-3 TO 5TH AVENUE) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13326,Roads,Completed,NH-ANNA NAGAR,100,448100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AA BLOCK 4TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13327,Roads,Completed,NH-ANNA NAGAR,100,599699,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT Y BLOCK 6TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/2115,Parks,Completed,NH-ANNA NAGAR,100,395000,"PROVIDING WELL RINGS AT 7TH MAIN ROAD PARK , AL- BLOCK PARK, AD BLOCK PARK, TAS ENCLEVE, TOWER PARK,TOWER PARK, DIVISION OFFICE, 7TH MAIN ROAD AMMA UNAVAGAM IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2241,Buildings,Completed,NH-ANNA NAGAR,100,927000,"Construction of bamboo mulch pit at AD BLOCK ,AL BLOCK,7TH MAIN ROAD and TOWER park in Division-100, Unit-22, Zone-08",Own Sources,8,2019-20,2019-20 NH/2019-20/2433,Buildings,Completed,NH-ANNA NAGAR,100,900000,"IMPROVEMENT TO PLAYGROUND AT AL BLOCK 4th STREET IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2434,Buildings,Completed,NH-ANNA NAGAR,100,867000,"REPAIRS AND IMPROVEMENTS WORKS AT AE BLOCK 1st STREET PLAYGROUND IN DIVISION-100, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2771,Buildings,Completed,NH-ANNA NAGAR,100,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE N.S.K. NAGAR CPS IN DIV-100, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/3168,Parks,Completed,NH-ANNA NAGAR,100,1940000,"DESILTING OF TOWER PARK POND IN DIVISION 100, UNIT 22,ZONE 08",Own Sources,8,2019-20,2019-20 NH/2019-20/3306,Parks,Completed,NH-ANNA NAGAR,100,840000,"PROVIDING GI SHEET SHED FOR YOGA PLATFORM AT TOWER PARK IN DIVISION -100, UNIT - 22, ZONE -8 (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/3669,Buildings,Completed,NH-ANNA NAGAR,100,2500000,"CONSTRUCTION OF COMPOST YARD AT P.H. ROAD IN AMBEDKAR STREET IN DIV-100, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/3740,Parks,Completed,NH-ANNA NAGAR,100,523000,"CONSTRUCTION OF OPEN GYM FOR LADIES AT TOWER PARK IN DIVISION 100,UNIT 22,ZONE 08 (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/5848,Buildings,Completed,NH-ANNA NAGAR,100,530000,REPAIRS AND IMPROVEMENTS OF DIVISION OFFICE CAMPUS IN DIVISION 100 UNIT 22 ZONE 08,Own Sources,8,2019-20,2020-21 NH/2019-20/5854,Road Cut,Completed,NH-ANNA NAGAR,100,725000,RESTORATION OF ROAD CUT AT 5TH AVENUE (FROM 2ND AVENUE TO 4TH AVENUE ) IN DIVISION 100 UNIT 22 ZONE 08,Deposit Works,8,2019-20,2019-20 NH/2019-20/5857,Road Cut,Completed,NH-ANNA NAGAR,100,1780000,RESTORATION OF ROAD CUT AT 4TH AVENUE (FROM 5TH AVENUE JUNCTION TO 10TH MAIN ROAD JUNCTION) IN DIVISION 100 UNIT 22 ZONE 08,Deposit Works,8,2019-20,2019-20 NH/2019-20/5962,Storm Water Drain,Completed,NH-ANNA NAGAR,100,1984500,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-100, UNIT-22, ZONE-08 (BR ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/5963,Storm Water Drain,Completed,NH-ANNA NAGAR,100,1799500,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-100, UNIT-22, ZONE-08 (IR ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/7145,Buildings,Completed,NH-ANNA NAGAR,100,630000,"REPAIR AND MAINTENANCE WORK FOR COMPOST YARD AT ARUMBAKKAM BURIAL GROUND IN DIV-100, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/7358,Parks,Completed,NH-ANNA NAGAR,100,874000,"ANNUAL MAINTENANCE OF PARK AT AL BLOCK, 14TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7359,Parks,Completed,NH-ANNA NAGAR,100,879000,"ANNUAL MAINTENANCE OF PARK AT AD BLOCK 3RD STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7360,Parks,Completed,NH-ANNA NAGAR,100,240000,"ANNUAL MAINTENANCE OF OSR LAND PARK AT 7TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7645,Roads,Completed,NH-ANNA NAGAR,100,275000,PROVIDING AND LAYING PVC PIPE AT ANNA ARCH IN DIVISION 100 UNIT 22 ZONE 08,Own Sources,8,2019-20,2020-21 NH/2019-20/8143,Roads,Completed,NH-ANNA NAGAR,100,200000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-100, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8308,Buildings,Completed,NH-ANNA NAGAR,100,230000,"SUPPLYING AND FIXING OF FENCING IN TOWER CLUB SOUTH SIDE IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/9218,Buildings,Completed,NH-ANNA NAGAR,100,224000,"SUPPLYING AND FIXING OF FREEZER,RO PLANT & HEATER AT 7TH MAIN ROAD AMMA UNAVAGAM IN DIVISION 100,UNIT 22,ZONE 08",Own Sources,8,2019-20,2020-21 BR/2019-20/0058,Road Cut,Completed,BR-Bus Route Roads,101,425000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-101, U-22, Zone-VIII",Deposit Works,8,2019-20,2019-20 BR/2019-20/17835,Road Cut,Completed,BR-Bus Route Roads,101,320000,Restoration of road cut made by various OFC Operators at various Bus Route Roads in Zone VIII,Deposit Works,8,2019-20,2020-21 BR/2019-20/17836,Road Cut,Completed,BR-Bus Route Roads,101,96000,Restoration of road cut made by various OFC Operators at various Bus Route Roads in Zone VIII,Deposit Works,8,2019-20,2020-21 BR/2019-20/17837,Road Cut,Completed,BR-Bus Route Roads,101,453000,Restoration of road cut made by various OFC Operators at various Bus Route Roads in Zone VIII,Deposit Works,8,2019-20,2020-21 BR/2019-20/17838,Road Cut,Completed,BR-Bus Route Roads,101,85000,Restoration of road cut made by various OFC Operators at various Bus Route Roads in Zone VIII,Deposit Works,8,2019-20,2020-21 BR/2019-20/17857,Road Cut,Completed,BR-Bus Route Roads,101,470000,"RESTORATION OF OFC ROADCUT 18 NOS OF INTERIOR ROADS AT VARIOUS DIV - 97,99,100,101 & 102. IN ZONE - 8.",Deposit Works,8,2019-20,2021-22 L/2019-20/10663,Electrical,Completed,L-Electrical,101,156300,"Supply and fixing of (54+14) 68nos of 1mtr Bougain villea park and C Block park in div 101 under Anna nagar section and 40nos of 1mtr single straight brackets for E Block, D Block, A Block, PH Road side park, 4th Street Railway colony park, Metha nagar play ground, Collectrate colony play ground adn R Block park in div 105,106 and 108 Under MMDA Section zone VIII",Own Sources,8,2019-20,2020-21 NH/2019-20/0063,Buildings,Completed,NH-ANNA NAGAR,101,715000,"DEMOLITION AND RECONSTRUCTION OF COMPOUND WALL AND OTHER REPAIR WORKS AT LORRY STATION IN DIVISION-101, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/10167,Buildings,Completed,NH-ANNA NAGAR,101,51000,"REPAIRS FOR COMPOST YARD AT CRESCENT ROAD IN DN-101, U-22, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/10815,Buildings,Completed,NH-ANNA NAGAR,101,2400000,"PROVIDING NEW GASIFIRE CREMATORIUM MACHINE AT VELANGADU BURIAL GROUND IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11321,Roads,Completed,NH-ANNA NAGAR,101,257000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT I BLOCK 4TH STREET IN DIVISION 101, UNIT -22, ZONE - 8",Own Sources,8,2019-20,2020-21 NH/2019-20/11824,Roads,Completed,NH-ANNA NAGAR,101,5564000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT DR.AMBEDHKAR NAGAR IN DIVISION 101, UNIT -22, ZONE - 8",Own Sources,8,2019-20,2020-21 NH/2019-20/12581,Roads,Completed,NH-ANNA NAGAR,101,1510600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT F BLOCK 2ND STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12583,Roads,Completed,NH-ANNA NAGAR,101,450600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT O BLOCK 35TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12584,Roads,Completed,NH-ANNA NAGAR,101,245700,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ANNAI SATHYA NAGAR 5TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12586,Roads,Completed,NH-ANNA NAGAR,101,512000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SHENOY NAGAR 4TH CROSS STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12587,Roads,Completed,NH-ANNA NAGAR,101,856200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SHENOY NAGAR 5TH CROSS STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12589,Roads,Completed,NH-ANNA NAGAR,101,519600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT F BLOCK 8TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12590,Roads,Completed,NH-ANNA NAGAR,101,1233800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT I BLOCK 10TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12591,Roads,Completed,NH-ANNA NAGAR,101,1048000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT K BLOCK 13TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12592,Roads,Completed,NH-ANNA NAGAR,101,694800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 1ST MAIN ROAD (NEAR H BLOCK) IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12593,Roads,Completed,NH-ANNA NAGAR,101,396599,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT H BLOCK 1ST STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12594,Roads,Completed,NH-ANNA NAGAR,101,308000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W BLOCK SERVICE ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12595,Roads,Completed,NH-ANNA NAGAR,101,957000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT W BLOCK 6TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12596,Roads,Completed,NH-ANNA NAGAR,101,1872200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BREWARY ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12597,Roads,Completed,NH-ANNA NAGAR,101,904100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT H BLOCK 2ND STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12960,Roads,Completed,NH-ANNA NAGAR,101,4505700,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT M.M.COLONY A, B, C BLOCK IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/15056,Buildings,Completed,NH-ANNA NAGAR,101,406000,"CONSTRUCTION OF WATCHMAN ROOM,TOILET AND ADDITIONAL IMPROVEMENTS AT C-BLOCK PARK IN DIVISION-101,UNIT-22, ZONE-8.",Own Sources,8,2019-20,2021-22 NH/2019-20/15064,Buildings,Completed,NH-ANNA NAGAR,101,352000,"CONSTRUCTION OF WATCHMAN ROOM,TOILET AND ADDITIONAL IMPROVEMENTS AT 2ND MAIN ROAD PARK IN DIVISION-101,UNIT-22, ZONE-8.",Own Sources,8,2019-20,2021-22 NH/2019-20/15212,Parks,Completed,NH-ANNA NAGAR,101,641000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT BOUGAINVILLA PARK IN DIVISION-101, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/2240,Parks,Completed,NH-ANNA NAGAR,101,148000,"PROVIDING OF BAMBOO MULCH PITS AT BOUGAINVILLA PARK,C-BLOCK PARK, 2ND MAIN ROAD PARK IN DIVISION -101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2250,Parks,Completed,NH-ANNA NAGAR,101,250000,"PROVIDING OF WELL RINGS AT BOUGAINVILLA PARK,C-BLOCK PARK, 2ND MAIN ROAD PARK, DIVISION OFFICE, CRESCENT ROAD SIDE IN DIVISION -101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2287,Buildings,Completed,NH-ANNA NAGAR,101,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT DIVISION OFFICE IN DN-101,UNIT-22,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2764,Buildings,Completed,NH-ANNA NAGAR,101,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT CPS (NADUVANKARAI ) IN DIVISION- 101 UNIT-22,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/3543,Buildings,Completed,NH-ANNA NAGAR,101,2082000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT VELANGADU BURIAL GROUND AT NEW AVADI ROAD IN DN-101,UNIT-22,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/3643,Buildings,Completed,NH-ANNA NAGAR,101,768000,REPAIRS AND IMPROVEMENTS TO AMMA ARANGAM IN DIV 101 UNIT 22 ZONE 8.,Own Sources,8,2019-20,2019-20 NH/2019-20/3896,Storm Water Drain,Completed,NH-ANNA NAGAR,101,309000,"FACE LIFT & ADDITIONAL IMPROVEMENTS TO EXISTING RAIN WATER COLLECTION WELL AT 3RD AVENUE IN DIV 101, UNIT 22, ZONE 8.",Own Sources,8,2019-20,2019-20 NH/2019-20/3988,Storm Water Drain,Completed,NH-ANNA NAGAR,101,182000,"Providing Disposal Arrangements of rain water from P.P Thottam to Coovum river in Division 101,Unit-22,Zone 8",Own Sources,8,2019-20,2019-20 NH/2019-20/5955,Storm Water Drain,Completed,NH-ANNA NAGAR,101,1226500,"Desillting of Strom water drains in Division-101,Unit-22,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/5956,Storm Water Drain,Completed,NH-ANNA NAGAR,101,877500,"Desillting of Strom water drains in Division-101,Unit-22,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/5957,Storm Water Drain,Completed,NH-ANNA NAGAR,101,1135500,"Desillting of Strom water drains in Division-101,Unit-22,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/7351,Parks,Completed,NH-ANNA NAGAR,101,879000,"ANNUAL MAINTENANCE OF PARK AT C-BLOCK, PULLA AVENUE IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7352,Parks,Completed,NH-ANNA NAGAR,101,618000,"ANNUAL MAINTENANCE OF PARK AT 2ND MAIN ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8133,Roads,Completed,NH-ANNA NAGAR,101,590000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-101, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9057,Buildings,Completed,NH-ANNA NAGAR,101,632000,"IMPROVEMENTS TO SHOPPING COMPLEX AT BREWARY ROAD IN DIVISION-101, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2021-22 NH/2019-20/9059,Buildings,Completed,NH-ANNA NAGAR,101,44000,"SUPPLY & FIXING CROSSING PIPE LINE IN SWD AT A-BLOCK 8TH STREET IN DN-101, U-22, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/9060,Buildings,Completed,NH-ANNA NAGAR,101,170000,"IMPROVEMENT TO PUBLIC CONVENIENCE AT 3RD AVENUE IN DIVISION-101, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/9061,Buildings,Completed,NH-ANNA NAGAR,101,79000,"IMPROVEMENT TO STORM WATER DRAIN AT M-BLOCK 8TH STREET IN DN-101, U-22, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/9062,Buildings,Completed,NH-ANNA NAGAR,101,97000,"REPAIRS AND MAINTENANCE TO DIVISION OFFICE AT CRESCENT ROAD IN DN-101, U-22, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/9064,Buildings,Completed,NH-ANNA NAGAR,101,69000,"IMPROVEMENT TO ICDS AND GYM N-BLOCK 24TH STREET IN DN-101, U-22, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/9227,Buildings,Completed,NH-ANNA NAGAR,101,1136000,"IMPROVEMENT TO CHENNAI PRIMARY SCHOOL AT BREWARY ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9228,Buildings,Completed,NH-ANNA NAGAR,101,776000,"IMPROVEMENT TO ICDS AT BHARATHIPURAM 4TH STREET IN DIVISION-101, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9235,Buildings,Completed,NH-ANNA NAGAR,101,111000,"PROVIDING BARRICADING ARRANGEMENTS AT BREWARY ROAD CANAL IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9236,Buildings,Completed,NH-ANNA NAGAR,101,56000,"IMPROVEMENT TO UPHC AT BHARATHIPURAM 4TH STREET IN DN-101, U-22, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/9237,Buildings,Completed,NH-ANNA NAGAR,101,102000,"IMPROVEMENT TO GAS ROOM AT VELANGADU BURIAL GROUND IN DN-101, U-22, Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/9603,Parks,Completed,NH-ANNA NAGAR,101,466000,"IMPROVEMENTS TO PARK AT 2ND MAIN ROAD, C BLOCK PARK AND BOUGANVILLA PARK IN DIVISION-101, UNIT 22, ZONE 8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9628,Storm Water Drain,Completed,NH-ANNA NAGAR,101,113000,"Providing Fencing around Community Well at 3rd Avenue in Division-101, Unit-22, Zone-08",Own Sources,8,2019-20,2020-21 NH/2019-20/9744,Buildings,Completed,NH-ANNA NAGAR,101,235000,"IMPROVEMENTS TO UNIT OFFICE AT ANNANAGAR 2ND MAIN ROAD IN DIVISION-101, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 BR/2019-20/0060,Road Cut,Completed,BR-Bus Route Roads,102,307000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-102, U-22, Zone-VIII",Deposit Works,8,2019-20,2019-20 NH/2019-20/0024,Buildings,Completed,NH-ANNA NAGAR,102,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CHENNAI GIRLS PRIMARY SCHOOL (ANNEXE) AT MANJAKOLLAI IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/0025,Buildings,Completed,NH-ANNA NAGAR,102,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CHENNAI GIRLS HIGH SCHOOL AT GUJII MAIN ROAD IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/0859,Buildings,Completed,NH-ANNA NAGAR,102,3100000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT TELUGU LANE IN DIVISION-102, UNIT-23, ZONE-8 (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/12553,Roads,Completed,NH-ANNA NAGAR,102,872000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT TP CHATHIRAM 18TH STREET IN DIVISION-102, UNIT-23, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/12556,Roads,Completed,NH-ANNA NAGAR,102,354000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MANDAPAM 1ST STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12562,Roads,Completed,NH-ANNA NAGAR,102,506000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MANDAPAM 2ND STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12568,Roads,Completed,NH-ANNA NAGAR,102,452000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT KVN PURAM 3RD STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12570,Roads,Completed,NH-ANNA NAGAR,102,422000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT EAST STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12599,Roads,Completed,NH-ANNA NAGAR,102,685000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BIG STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12600,Roads,Completed,NH-ANNA NAGAR,102,156100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT R. V NAGAR 1ST STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12601,Roads,Completed,NH-ANNA NAGAR,102,170200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT R. V NAGAR 3RD STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12602,Roads,Completed,NH-ANNA NAGAR,102,315800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT R. V NAGAR 5TH STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12603,Roads,Completed,NH-ANNA NAGAR,102,425900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT R. V NAGAR 6TH STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12604,Roads,Completed,NH-ANNA NAGAR,102,1228600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT OUTER CIRCULAR STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12605,Roads,Completed,NH-ANNA NAGAR,102,573500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT D BLOCK 6TH STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13023,Roads,Completed,NH-ANNA NAGAR,102,523700,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT R. V NAGAR MAIN ROAD IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13025,Roads,Completed,NH-ANNA NAGAR,102,1144800,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT GAJALAKSHMI COLONY 4TH STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13179,Roads,Completed,NH-ANNA NAGAR,102,1657000,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT VOC COLONY IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13261,Roads,Completed,NH-ANNA NAGAR,102,1210600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT D- BLOCK 3RD STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13969,Buildings,Completed,NH-ANNA NAGAR,102,499000,"MAINTENANCE OF CHENNAI CORPORATION BUILDINGS, SWD, PARKS, PLAY GROUNDS, ROADS, ROADCUTS AND FOOTPATH AT VARIOUS PLACES IN DIV-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/16984,Buildings,Completed,NH-ANNA NAGAR,102,1300000,"PROPOSED CONSTRUCTION OF 16TH CEREMONY HALL AT 1ST CROSS STREET EAST IN DIVISION-102, UNIT-23, ZONE-08. (MLA FUND)",MLACDS,8,2019-20,2021-22 NH/2019-20/2254,Parks,Completed,NH-ANNA NAGAR,102,250000,"PROVIDING WELL RINGS AT SKATING PARK, G-BLOCK PARK, ZONAL OFFICE, TAMILAR NAGAR AMMA UNAVAGAM, GAJAPATHY STREET VACANT LAND IN DIVISIIN-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2258,Parks,Completed,NH-ANNA NAGAR,102,46000,"PROVIDING OF BAMBOO MULCH PIT AT G-BLOCK PARK IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2286,Buildings,Completed,NH-ANNA NAGAR,102,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT ZONE 8 ZONAL OFFICE IN DN-102,UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2765,Buildings,Completed,NH-ANNA NAGAR,102,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT AMINJIKARAI CMS IN DIVISION- 102 UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2768,Buildings,Completed,NH-ANNA NAGAR,102,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT PULLA AVENUE SCHOOL IN DIVISION- 102 UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2769,Buildings,Completed,NH-ANNA NAGAR,102,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT MANJAKOLLAI CPS IN DIVISION- 102 UNIT-23,ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/2782,Buildings,Completed,NH-ANNA NAGAR,102,1058000,"REPAIRS AND IMPROVEMENT WORKS AT ZONAL OFFICE IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/2790,Buildings,Completed,NH-ANNA NAGAR,102,419000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND REPAIR WORKS AT ICDS AT KATHIRAVAN COLONY IN DIVISION-102, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/2863,Buildings,Completed,NH-ANNA NAGAR,102,200000,"IMPROVEMENT WORKS TO ICDS CENTER NO:33603050101 AT T.P CHATHIRAM 23RD CROSS STREET IN DIVISION-102, UNIT-23, ZONE-08",Own Sources,8,2019-20,2019-20 NH/2019-20/3542,Buildings,Completed,NH-ANNA NAGAR,102,2082000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT NEW AVADI ROAD OPPOSITE TO KILPAUK WATER HOUSE IN DN-102,UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/3731,Buildings,Completed,NH-ANNA NAGAR,102,1162000,"PROPOSED DEMOLITION OF EXISTING MATERNITY HOSPITAL & ICDS CENTRE AT PULLA AVENUE IN DIVISION-102, UNIT 23, ZONE 8",Own Sources,8,2019-20,2019-20 NH/2019-20/5059,Buildings,Completed,NH-ANNA NAGAR,102,429000,"PROPOSED CONSTRUCTION OF COMPOUND WALL AT MANDAPAM ROAD CORPORATION VACANT LAND IN DIV 102, UNIT 23, ZONE 8.",Own Sources,8,2019-20,2020-21 NH/2019-20/5959,Storm Water Drain,Completed,NH-ANNA NAGAR,102,760500,"Desillting,Repairs and Improvement Works to Strom water drains at Interior Roads in Division-102,Unit-23,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/5960,Storm Water Drain,Completed,NH-ANNA NAGAR,102,678800,"Desillting of Strom water drains in Division-102,Unit-23,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/5961,Storm Water Drain,Completed,NH-ANNA NAGAR,102,823800,"Desillting,Repairs and Improvement Works to Strom water drains at Interior Roads in Division-102,Unit-23,Zone-8",Own Sources,8,2019-20,2019-20 NH/2019-20/7132,Buildings,Completed,NH-ANNA NAGAR,102,526000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT CHENNAI PRIMARY SCHOOL MANJAKOLLAI IN DIVISION-102 UNIT-23, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/7353,Parks,Completed,NH-ANNA NAGAR,102,1031000,"ANNUAL MAINTENANCE OF PARK AT G-BLOCK IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/7354,Parks,Completed,NH-ANNA NAGAR,102,2265000,"ANNUAL MAINTENANCE OF SCATTING PARK AT PULLA AVENUE IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8145,Roads,Completed,NH-ANNA NAGAR,102,397000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-102, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8146,Roads,Completed,NH-ANNA NAGAR,102,91000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-102, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 BR/2019-20/13598,Road Cut,Completed,BR-Bus Route Roads,103,528000,Restoration of Road cut Made by Reliance JIO at various bus route roads in zone 8 (Deposit code-57/0520/2018-19),Deposit Works,8,2019-20,2019-20 BR/2019-20/4605,Roads,Completed,BR-Bus Route Roads,103,5407000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at New Avadi Road(part)(From the Jn of Kilpauk Garden Road to the Jn of EVR Salai) in Dn-103, Zone - VIII",Grants,8,2019-20,2020-21 BR/2019-20/5047,Roads,Completed,BR-Bus Route Roads,103,988000,"Partly relaying the road with BC after cold milling by paver finisher at Barnaby Road in Dn-103, Zone - VIII",Grants,8,2019-20,2020-21 NH/2019-20/1126,Buildings,Completed,NH-ANNA NAGAR,103,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT TEMPLE STREET (DIVISION OFFICE CAMPUS) IN DN-103,UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/12651,Roads,Completed,NH-ANNA NAGAR,103,143500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT KILPAUK GARDEN 1ST STREET ( PART ) IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12655,Roads,Completed,NH-ANNA NAGAR,103,475900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT DHARMARAJA KOIL STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12656,Roads,Completed,NH-ANNA NAGAR,103,1551800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT UMAYAL STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/14249,Buildings,Completed,NH-ANNA NAGAR,103,252000,"PROVIDING WATER SUPPLY ARRANGEMENT (NEW BORE) FOR UNIT-23 OFFICE AT TEMPLE STREET IN DIVISION-103,UNIT-23,ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/14272,Buildings,Completed,NH-ANNA NAGAR,103,96000,"REPAIRS WORK FOR DIVISION -103 OFFICE AT TEMPLE STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/1492,Buildings,Completed,NH-ANNA NAGAR,103,235000,"PROVIDING WELL RINGS AT BASHIYAM PARK , AIR INDIA QUARTERS, HERITAGE APARTMENT PARK,KENCESS PARK, PROF.SUBRAMANIYAM PARK, DIVISION OFFICE, AMMA UNAVAGAM (HALLS ROAD ) AND AMMA UNAVAGAM (KMC HOSPITAL ) IN DIVISION-103, UNIT-23, ZONE-08",Own Sources,8,2019-20,2019-20 NH/2019-20/1511,Buildings,Completed,NH-ANNA NAGAR,103,95000,"Construction of Bamboo mulch pit at Bashiyam park, Air india Quarters , Prof.Subramaniyam park, Road side park (Harleys Road) and Kencess park in DN-103, U-23,Z-08",Own Sources,8,2019-20,2019-20 NH/2019-20/1539,Buildings,Completed,NH-ANNA NAGAR,103,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT KELLYS ROAD (NEAR BAIN SCHOOL) IN DN-103,UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2772,Buildings,Completed,NH-ANNA NAGAR,103,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT CPS (KILPAUK )IN DIVISION- 103 UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/2810,Buildings,Completed,NH-ANNA NAGAR,103,2082000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT (OSR LAND) P.H.ROAD IN DN-103,UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/3505,Buildings,Completed,NH-ANNA NAGAR,103,426000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING C.H.SCHOOL AT THIYAGAPPA STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/4136,Storm Water Drain,Completed,NH-ANNA NAGAR,103,168000,"DESILTING AND IMPROVEMENTS TO THE EXISTING SWD AT T.P.CHATHIRAM 20TH CROSS STREET IN DN-103,U-23,Z-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/5933,Storm Water Drain,Completed,NH-ANNA NAGAR,103,825600,"DESILTING AND MINOR REPAIRS TO THE STORM WATER DRAIN AT VARIOUS BUS ROUTE ROADS IN DIVISION-103, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/5935,Storm Water Drain,Completed,NH-ANNA NAGAR,103,1119500,"DESILTING AND MINOR REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-103, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/5936,Storm Water Drain,Completed,NH-ANNA NAGAR,103,1084800,"DESILTING AND MINOR REPAIRS TO THE STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-103, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/5971,Roads,Completed,NH-ANNA NAGAR,103,580000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT AGASTHIYAR STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/8140,Roads,Completed,NH-ANNA NAGAR,103,513100,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-103, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9446,Buildings,Completed,NH-ANNA NAGAR,103,252000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT KAMARAJAR NAGAR IN DIVISION-103, UNIT-23,ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9447,Buildings,Completed,NH-ANNA NAGAR,103,261000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT T.P.CHATHIRAM 24TH CROSS STREET (JN OF T.P.CHATHIRAM MAIN ROAD) IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9448,Buildings,Completed,NH-ANNA NAGAR,103,263000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT VALLIAMMAL STREET (NEAR RATION SHOP) IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9450,Buildings,Completed,NH-ANNA NAGAR,103,260000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT T.P.CHATHIRAM 24TH CROSS STREET (JN OF LAKSHMI STREET) IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9452,Buildings,Completed,NH-ANNA NAGAR,103,62000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT E.V.R. SALAI (OLD ZONAL OFFICE) IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9453,Buildings,Completed,NH-ANNA NAGAR,103,13000,"REPAIRS AND IMPROVEMENT TO THE EXISTING PUBLIC CONVENIENCE AT VALLIAMMAL STREET (JN OF TEMPLE LANE) IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/9601,Buildings,Completed,NH-ANNA NAGAR,103,652000,"REPAIRS AND IMPROVEMENT TO THE EXISTING STREET LIGHT OFFICE (AE/JE) AT KELLYS ROAD IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 BR/2019-20/13597,Road Cut,Completed,BR-Bus Route Roads,104,496000,Restoration of Road cut Made by ACT at various bus route roads in zone 8 (Deposit code-57/1137/2018-19),Deposit Works,8,2019-20,2019-20 BR/2019-20/4604,Roads,Completed,BR-Bus Route Roads,104,3572000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Bricklin Road in Dn-104 , Zone - VIII",Grants,8,2019-20,2020-21 BR/2019-20/4607,Roads,Completed,BR-Bus Route Roads,104,3206000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Dr.Alagappa Road in Dn-104, Zone - VIII",Grants,8,2019-20,2020-21 NH/2019-20/0004,Buildings,Completed,NH-ANNA NAGAR,104,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CMS SCHOOL AT SUNDARAM STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/10601,Buildings,Completed,NH-ANNA NAGAR,104,53000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT VELLALA STREET IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/11411,Roads,Completed,NH-ANNA NAGAR,104,59000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT SARAVANA PERUMAL MAIN ROAD IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11501,Parks,Completed,NH-ANNA NAGAR,104,380000,"PROVIDING WATER FACILITY ARRANGEMENTS, GREENERY AND IMPROVEMENTS TO BANK MANIKAM PARK IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11504,Buildings,Completed,NH-ANNA NAGAR,104,332000,"IMPROVEMENTS TO PUBLIC CONVENIENCE AT SALIMA NAGAR IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/11505,Buildings,Completed,NH-ANNA NAGAR,104,336000,"IMPROVEMENTS TO NAMMA TOILET BY PROVIDING WATER FACILITY AT Mc.NICOLAS ROAD (back side of ECO Park) IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11506,Buildings,Completed,NH-ANNA NAGAR,104,264000,"IMPROVEMENT AND PROVIDING WATER FACILITY TO NAMMA TOILET AT GANGADESHWARAR KOIL ROAD IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12445,Electrical,Completed,NH-ANNA NAGAR,104,360900,"ELECTRIFICATION WORK AT COMMUNITY COLLEGE SUNDARAM STREET IN DIVISION 104, ZONE - VIII",Own Sources,8,2019-20,2020-21 NH/2019-20/12608,Roads,Completed,NH-ANNA NAGAR,104,283200,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT AUDIAPPA LANE IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12609,Roads,Completed,NH-ANNA NAGAR,104,351000,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT PONNAPPA MUDHALI 2ND STREET IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12610,Roads,Completed,NH-ANNA NAGAR,104,698000,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT PONNAPPA MUDHALI 3RD STREET IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12721,Buildings,Completed,NH-ANNA NAGAR,104,646000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT SUNDARAM STREET IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/12731,Buildings,Completed,NH-ANNA NAGAR,104,370000,"IMPROVEMENTS TO DIAGNOSTIC CENTER AT EVR PERIYAR SALAI IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/14156,Roads,Completed,NH-ANNA NAGAR,104,124000,"LAYING PIPE LINE WORK AT ALAGAPPA ROAD , VELLALA STREET AND BRICK KLIN ROAD CROSSINGS IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/14157,Buildings,Completed,NH-ANNA NAGAR,104,48900,"REPAIR AND IMPROVEMENTS TO STORM WATER DRAIN AT SUNDARAM STREET IN DIVISION 104, UNIT-23, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/14159,Buildings,Completed,NH-ANNA NAGAR,104,325000,"REPAIR AND IMPROVEMENTS TO CORPORATION BUILDING , PARKS IN DIVISION 104, UNIT-23, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/1636,Buildings,Completed,NH-ANNA NAGAR,104,145000,"Providing water facility to public convenience at Thideer nagar in division 104, unit-23, zone -8",Own Sources,8,2019-20,2019-20 NH/2019-20/1644,Buildings,Completed,NH-ANNA NAGAR,104,190000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE PUBLIC CONVENIENCE AT NEW BHOOPATHY NAGAR MAIN ROAD IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/1697,Parks,Completed,NH-ANNA NAGAR,104,334000,"Providing security(watch man) for Nehru park at Poonamalle High Road in Dn-104, Unit-23, Zone - 8",Own Sources,8,2019-20,2019-20 NH/2019-20/1829,Buildings,Completed,NH-ANNA NAGAR,104,207000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO PUBLIC CONVENIENCE AT SADASIVAM STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/1850,Parks,Completed,NH-ANNA NAGAR,104,126000,"Providing equipments for Nehru park at Poonamalle High Road in Dn-104, Zone - 8",Own Sources,8,2019-20,2019-20 NH/2019-20/2042,Parks,Completed,NH-ANNA NAGAR,104,227000,"PROVIDING WELL RINGS AT BANK MANIKAM PARK, ARIHANT TOWER PARK(OSR LAND), TVH LUMINI SQUARE(OSR LAND ), NEHRU PARK, AMMA UNAVAGAM, DIVISION OFFICE IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2019-20,2019-20 NH/2019-20/2045,Parks,Completed,NH-ANNA NAGAR,104,45000,"PROVIDING BAMBOO MULCH PIT AT BANK MANIKAM PARK, ARIHANT TOWER PARK(OSR LAND), TVH LUMINI SQUARE(OSR LAND ), NEHRU PARK, IN DIVISION-104, UNIT-23, ZONE-08",Own Sources,8,2019-20,2019-20 NH/2019-20/2773,Buildings,Completed,NH-ANNA NAGAR,104,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE VELLALA STREET CMS IN DIV-104, UNIT-23, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/2776,Buildings,Completed,NH-ANNA NAGAR,104,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE GANGADEESWARI KOIL STREET CHSS IN DIV-104, UNIT-23, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/3483,Buildings,Completed,NH-ANNA NAGAR,104,653000,"IMPROVEMENTS TO CHENNAI HIGH SCHOOL AT GANGADESHWARAR KOIL STREET IN DIVISION-104, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/3569,Buildings,Completed,NH-ANNA NAGAR,104,2082000,"CONSTRUCTION OF COMPOST YARD AT OTTERI BURIAL GROUND IN DN-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/3715,Buildings,Completed,NH-ANNA NAGAR,104,1460000,"IMPROVEMENTS TO CMS & COMMUNITY COLLEGE AT SUNDARAM STREET BY PROVIDING SUMP, TOILET ROOM , DRINKING WATER FACILITIES AND BASIC FACILITIES IN DIVISION 104,UNIT 23,ZONE 08",Own Sources,8,2019-20,2019-20 NH/2019-20/4705,Buildings,Completed,NH-ANNA NAGAR,104,448000,"IMPROVEMENTS TO EXISTING COMPOST YARD AT OTTERI BURIAL GROUND IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/4965,Roads,Completed,NH-ANNA NAGAR,104,320000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT MADAM 1ST LANE IN DIVISION-104,UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5009,Roads,Completed,NH-ANNA NAGAR,104,260000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT MADAM 2ND LANE IN DIVISION-104,UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5374,Buildings,Completed,NH-ANNA NAGAR,104,339000,"IMPROVEMENTS TO INTEGRATED CHILDREN DEVELOPMENT SCHEME(ICDS) AT NEHRU PARK SLUM TENEMENTS IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/5394,Roads,Completed,NH-ANNA NAGAR,104,297000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT SARAVANA PERUMAL 3RD STREET IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5418,Roads,Completed,NH-ANNA NAGAR,104,3237000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT PULLAPURAM 1ST MAIN ROAD IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5422,Buildings,Completed,NH-ANNA NAGAR,104,300000,"IMPROVEMENTS BY PROVIDING WATER FACILITIES AND MINOR REPAIR WORKS TO PUBLIC CONVENIENCE AT PULLA PURAM IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5423,Buildings,Completed,NH-ANNA NAGAR,104,297000,"IMPROVEMENTS BY PROVIDING WATER FACILITIES AND MINOR REPAIR WORKS TO PUBLIC CONVENIENCE AT SHASTHIRI NAGAR IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5425,Buildings,Completed,NH-ANNA NAGAR,104,83000,"MINOR REPAIR WORKS TO PUBLIC CONVENIENCE AT THIDEER NAGAR IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5969,Storm Water Drain,Completed,NH-ANNA NAGAR,104,307700,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT PURASAIWAKKAM HIGH ROAD, GANGADESHWARAR KOIL ROAD, RAJA ANNAMALAI ROAD, DR.ALAGAPPA ROAD AND BRICK KLIN ROAD IN DIVISION-104, UNIT-23, ZONE-08 (BUS ROUTE ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/5970,Storm Water Drain,Completed,NH-ANNA NAGAR,104,1104700,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-104, UNIT-23, ZONE-08 (IR ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/7375,Parks,Completed,NH-ANNA NAGAR,104,1368000,"ANNUAL MAINTENANCE OF NEHRU PARK AT POONAMALLI HIGH ROAD IN DIVISION-104, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8126,Roads,Completed,NH-ANNA NAGAR,104,416400,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-104, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8127,Roads,Completed,NH-ANNA NAGAR,104,404900,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-104, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 BR/2019-20/5048,Roads,Completed,BR-Bus Route Roads,105,494000,"Partly relaying the road with BC after cold milling by paver finisher at Razak garden Main Road in Dn-105,Zone - VIII",Grants,8,2019-20,2020-21 BR/2019-20/5056,Roads,Completed,BR-Bus Route Roads,105,1174000,"Partly relaying the road with BC after cold milling by paver finisher at MMDA Colony Main Road in Dn- 105, Zone - VIII",Grants,8,2019-20,2020-21 NH/2019-20/10595,Buildings,Completed,NH-ANNA NAGAR,105,1260000,"IMPROVEMENT TO CMS SCHOOL IN C BLOCK AT SCHOOL STREET IN DIVISION:105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/11422,Roads,Completed,NH-ANNA NAGAR,105,881000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT FRIENDS AVENUE IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11423,Roads,Completed,NH-ANNA NAGAR,105,900000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT PILLAIYAR KOIL STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11424,Roads,Completed,NH-ANNA NAGAR,105,1140000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT AMARAVATHI NAGAR MAIN ROAD IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11425,Roads,Completed,NH-ANNA NAGAR,105,1381000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT GANDHI ROAD IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11435,Roads,Completed,NH-ANNA NAGAR,105,672000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT MUTHUMARI AMMAN 2ND LANE IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11436,Roads,Completed,NH-ANNA NAGAR,105,752000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT MUTHURAMALINGAM STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11438,Roads,Completed,NH-ANNA NAGAR,105,1335000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT E-BLOCK 2ND CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11733,Buildings,Completed,NH-ANNA NAGAR,105,187000,"ATTENDING PATCH WORK AND REPAIRS TO FOOT PATH AND NAME BOARD AND MANHOLE DOORS AT VARIOUS PLACE IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13297,Roads,Completed,NH-ANNA NAGAR,105,607300,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT DURGA STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13298,Roads,Completed,NH-ANNA NAGAR,105,295100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ASHOKA NAGAR WEST IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13299,Roads,Completed,NH-ANNA NAGAR,105,491400,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SHANMUGA NAGAR IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13300,Roads,Completed,NH-ANNA NAGAR,105,295100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MARIAMMAN KOIL STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13301,Roads,Completed,NH-ANNA NAGAR,105,441200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SBI OFFICERS COLONY 1ST STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13304,Roads,Completed,NH-ANNA NAGAR,105,595200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT DHAMODHARAN STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13305,Roads,Completed,NH-ANNA NAGAR,105,757800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BALAJI STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13306,Roads,Completed,NH-ANNA NAGAR,105,142600,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AMARAVATHY NAGAR EAST 1ST CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13308,Roads,Completed,NH-ANNA NAGAR,105,194100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AMARAVATHY NAGAR EAST 2ND CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13311,Roads,Completed,NH-ANNA NAGAR,105,246000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AMARAVATHY NAGAR EAST 3RD CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13312,Roads,Completed,NH-ANNA NAGAR,105,347200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AMARAVATHY NAGAR WEST 1ST CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13313,Roads,Completed,NH-ANNA NAGAR,105,142000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AMARAVATHY NAGAR WEST 2ND CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13316,Roads,Completed,NH-ANNA NAGAR,105,252500,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT VASUGI STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13319,Roads,Completed,NH-ANNA NAGAR,105,227200,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AMARAVATHY NAGAR WEST 3RD CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13416,Roads,Completed,NH-ANNA NAGAR,105,718200,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT ANJUGAM STREET (RANI ANNA NAGAR) IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13417,Roads,Completed,NH-ANNA NAGAR,105,657000,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT E BLOCK 3RD CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13418,Roads,Completed,NH-ANNA NAGAR,105,707100,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT E BLOCK 1ST CROSS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/2074,Buildings,Completed,NH-ANNA NAGAR,105,369000,"PROVIDING WELL RINGS AT E-BLOCK, D-BLOCK PARK, A-BLOCK PARK, AMMA UNAVAGAM SBI SAFF COLONY 6TH STREET, AMMA UNAVAGAM MARI AMMAN KOIL STREET, C-BLOCK SCHOOL, V.N NAGAR ICDS CENTER, FRIENDS AVENUE ICDS CENTER, H-BLOCK PARK IN DIVISION-105, UNIT-22, ZONE-08",Own Sources,8,2019-20,2019-20 NH/2019-20/2774,Buildings,Completed,NH-ANNA NAGAR,105,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS AT CMS C BLOCK IN DIVISION- 105 UNIT-22,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/3812,Buildings,Completed,NH-ANNA NAGAR,105,645000,"IMPROVEMENTS TO EXISTING COMPOST YARD AT KALKI STREET(OPPOSITE TO APPASAMY HOSPITAL) IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2021-22 NH/2019-20/3898,Buildings,Completed,NH-ANNA NAGAR,105,607000,"CONSTRUCTION OF COMPOUND WALL INFRONT OF C.I OFFICE AND TAX COLLECTOR OFFICE IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/3912,Buildings,Completed,NH-ANNA NAGAR,105,542000,"IMPROVEMENTS TO DIVISION OFFICE BUILDING IN DIVISION-105, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/4527,Buildings,Completed,NH-ANNA NAGAR,105,227000,"REPAIR AND IMPROVEMENT TO THE CHENNAI CORPORATION BUILDINGS AT VARIOUS PLACES IN DIVISION-105,UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/5705,Buildings,Completed,NH-ANNA NAGAR,105,121000,"DEMOLISHING EXISTING SCHOOL BUILDING INSIDE CMS AT MMDA,C BLOCK IN DIVISION-105, UNIT-23, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/5713,Buildings,Completed,NH-ANNA NAGAR,105,170000,"PROVIDING WATER FACILITY TO PUBLIC CONVENIENCE AT PERUMAL KOIL STREET IN DN-105,U-23,Z-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/5715,Buildings,Completed,NH-ANNA NAGAR,105,273000,"REPAIR AND IMPROVEMENT TO THE ROAD MAINTENANCE WORK AT VARIOUS STREET IN DIVISION-105, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5723,Buildings,Completed,NH-ANNA NAGAR,105,680000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND IMPROVEMENT TO UPHC TO HEALTH POST AT D BLOCK PANDIAN STREET IN DN-105,U-22,Z-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/5869,Buildings,Completed,NH-ANNA NAGAR,105,163000,"PROVIDING WATER SUPPLY ARRANGEMENT FOR E-TOILET AT VINAYAGPURAM MAIN ROAD IN DN-105,U-22,Z-8",Own Sources,8,2019-20,2020-21 NH/2019-20/5922,Storm Water Drain,Completed,NH-ANNA NAGAR,105,1505600,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-105, UNIT-22, ZONE-08 (IR ROADS)",Own Sources,8,2019-20,2020-21 NH/2019-20/5925,Storm Water Drain,Completed,NH-ANNA NAGAR,105,188800,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-105, UNIT-22, ZONE-08 (BR ROADS)",Own Sources,8,2019-20,2020-21 NH/2019-20/8134,Roads,Completed,NH-ANNA NAGAR,105,412600,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-105, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8135,Roads,Completed,NH-ANNA NAGAR,105,38600,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-105, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 BR/2019-20/5055,Roads,Completed,BR-Bus Route Roads,106,3526000,"Partly relaying the road with BC after cold milling by paver finisher at Nelson Manickam Road in Dn- 106 & 109, Zone - VIII",Grants,8,2019-20,2020-21 NH/2019-20/11219,Roads,Completed,NH-ANNA NAGAR,106,216000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT NAVANEETHAMMAL STREET (PART) IN DIVISION-106, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11220,Roads,Completed,NH-ANNA NAGAR,106,419000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT THANTHONI AMMAN KOIL STREET IN DIVISION-106, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13032,Roads,Completed,NH-ANNA NAGAR,106,299700,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NEW STREET IN DIVISION-106, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13033,Roads,Completed,NH-ANNA NAGAR,106,765800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT MUNIRATHINAM STREET IN DIVISION-106, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/13034,Roads,Completed,NH-ANNA NAGAR,106,1332800,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SADASIVA METHA NAGAR IN DIVISION-106, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/17717,Storm Water Drain,Completed,NH-ANNA NAGAR,106,500000,"MAINTENANCE OF CHENNAI CORPORATION BUILDINGS, SWD, PARKS, PLAY GROUNDS, ROADS, ROADCUTS AND FOOTPATH AT VARIOUS PLACES IN DIV-106, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/2029,Buildings,Completed,NH-ANNA NAGAR,106,489000,"PROVIDING WELL RINGS AT SKY WALK PARK , NAVINS OSR , NELSON CHAMBER OSR, KRISHNA OSR, METAL FACTORY ROAD PARK COLLECTOR COLONY PLAY GROUND , OFFICERS COLONY 1ST STREET IN DIVISION-106, UNIT-22, ZONE-08",Own Sources,8,2019-20,2019-20 NH/2019-20/2031,Buildings,Completed,NH-ANNA NAGAR,106,152000,"CONSTRUCTION OF MULCH PIT AT SKYWALK PARK, KRISHNA OSR LAND, METAL FACTORY ROAD PARK AND COLLECTORATE COLONY PLAY GROUND IN DIVISION-106, UNIT-22, ZONE-8..",Own Sources,8,2019-20,2019-20 NH/2019-20/3850,Buildings,Completed,NH-ANNA NAGAR,106,786000,"PROVIDING IMPROVEMENTS TO NIGHT SHELTER AT M.H COLONY 1ST MAIN ROAD IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/5929,Storm Water Drain,Completed,NH-ANNA NAGAR,106,583600,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT NELSON MANICKAM ROAD IN DIVISION-106, UNIT-22, ZONE-08 (BUS ROUTE ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/5931,Storm Water Drain,Completed,NH-ANNA NAGAR,106,1442700,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-106, UNIT-22, ZONE-08 (IRR ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/7355,Parks,Completed,NH-ANNA NAGAR,106,634000,"ANNUAL PARK MAINTENANCE AT SKYWALK PARK IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2021-22 NH/2019-20/7356,Parks,Completed,NH-ANNA NAGAR,106,620000,"ANNUAL MAINTENANCE OF PARK AT METAL FACTORY ROAD IN DIVISION-106, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8090,Roads,Completed,NH-ANNA NAGAR,106,509600,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-106, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8091,Roads,Completed,NH-ANNA NAGAR,106,63200,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-106, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 L/2019-20/11238,Electrical,Completed,L-Electrical,107,192400,Supply and Replacement of damaged 364 mtr of 31/2x25 Sqmm UG Cable at Central Asphault Plant in Shenoynagar section Dn-107Zone-VIII Area.,Own Sources,8,2019-20,2020-21 NH/2019-20/10428,Buildings,Completed,NH-ANNA NAGAR,107,1800000,"PROVIDING AND CONVERTING THE SMART CLASS ROOM IN SUBBARAYAN SCHOOL (CHSS) IN DIVISION-107,UNIT-23, ZONE-8 (MLA FUND)",MLACDS,8,2019-20,2020-21 NH/2019-20/1052,Buildings,Completed,NH-ANNA NAGAR,107,930000,"REPAIRS AND IMPROVEMENT WORKS AT CAP MECHANIC SHED AND PROPOSED COMPOST YARD USING POLYPROPYLENE TUBS IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/1240,Buildings,Completed,NH-ANNA NAGAR,107,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE DHOBIKANA INSIDE (NEAR MULTIPURPOSE HALL) AT SCHOOL ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/12679,Roads,Completed,NH-ANNA NAGAR,107,662600,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT KARUKATHAMMAN KOIL STREET IN DIVISION-107, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/12680,Roads,Completed,NH-ANNA NAGAR,107,662600,"IMPROVEMENT TO THE INTERIOR CEMENT CONCRETE ROAD AT KARUKATHAMMAN KOIL LANE IN DIVISION-107, UNIT-23, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/1277,Buildings,Completed,NH-ANNA NAGAR,107,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE DHOBIKANA INSIDE (NEAR PC) AT SCHOOL ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/13919,Buildings,Completed,NH-ANNA NAGAR,107,778000,"REPAIRS AND IMPROVEMENTS WORKS AT MCNICHOLAS SCHOOL (CHS) IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/1561,Buildings,Completed,NH-ANNA NAGAR,107,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT MCNICHOLS ROAD (BACK SIDE OF OLD ZONAL OFFICE BUILDING) IN DN-107,UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/1587,Buildings,Completed,NH-ANNA NAGAR,107,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE DHOBIKANA INSIDE (NORTH SIDE) AT PILLAYAR KOIL STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2269,Buildings,Completed,NH-ANNA NAGAR,107,147000,"PROVIDING WELL RINGS AT DIVISION OFFICE , AMMAUNAVAGAM, LIONS CLUB PARK,MAYOR SATHYAMOORTHY SALAI PARK, MAYOR RAMANATHAN SALAI PARK, IN DIVISION-107, UNIT-23, ZONE-08",Own Sources,8,2019-20,2019-20 NH/2019-20/2281,Buildings,Completed,NH-ANNA NAGAR,107,76000,"PROVIDING MULCH PIT WITH BAMBOO THATTY PARTITION AT MAYOR SATHYAMOOTHY SALAI PARK, MAYOR RAMANATHAN SALAI PARK, LIONS CLUB PARK, DIVISION OFFICE, AMMA UNAVAGAM IN DIVISION-107, UNIT-23, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/2570,Buildings,Completed,NH-ANNA NAGAR,107,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE SUBBARAYAN CHS SCHOOL AT SUBBARAYAN STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2571,Buildings,Completed,NH-ANNA NAGAR,107,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE MC NICHOLAS ROAD CMS IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2572,Buildings,Completed,NH-ANNA NAGAR,107,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CMS AT JAGANATHAPURAM IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2573,Buildings,Completed,NH-ANNA NAGAR,107,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CMS AT MS NAGAR IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2785,Buildings,Completed,NH-ANNA NAGAR,107,528000,"PROVIDING COMPOST YARD CRS STORE AT CAP IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2786,Buildings,Completed,NH-ANNA NAGAR,107,594000,"PROVIDING MATERIAL RECOVERY FACILITY , ELECTRICAL AND WATER SUPPLY ARRANGEMENTS AT CAP MECHANIC SHED IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/3579,Buildings,Completed,NH-ANNA NAGAR,107,2082000,"PROPOSED CONSTRUCTION OF COMPOST YARD AT MC NICHOLAS ROAD OLD ZONAL OFFICE IN DIVISION-107,UNIT-23,ZONE-8",Own Sources,8,2019-20,2019-20 NH/2019-20/5426,Buildings,Completed,NH-ANNA NAGAR,107,2270000,"PROPOSED CONSTRUCTION OF SHED FOR ERECTING GARDEN GARBAGE SHREDDING MACHINE AT CENTRAL ASPHALT PLANT (CAP) IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/5896,Roads,Completed,NH-ANNA NAGAR,107,744000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT VRR COLONY IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/5898,Roads,Completed,NH-ANNA NAGAR,107,372000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT NEW COLONY IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/5932,Storm Water Drain,Completed,NH-ANNA NAGAR,107,1275000,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-107, UNIT-23, ZONE-08 (IR ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/6062,Buildings,Completed,NH-ANNA NAGAR,107,2300000,"PROPOSED CONSTRUCTION OF STORAGE SHED FOR COCONUT SHELL AT CENTRAL ASPHALT PLANT (CAP) IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/6164,Subway,Completed,NH-ANNA NAGAR,107,207000,"MAINTENANCE OF HARRINGTON ROAD SUBWAY ENGAGING OF ELECTRICIAN/PLUMBER AND UNSKILLED LABOUR FOR THREE MONTHS IN DIVISION-107 UNIT-23, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/6171,Subway,Completed,NH-ANNA NAGAR,107,280000,"DESILTING OF WELL AND IMPROVEMENTS TO HARRINGTON ROAD SUBWAY IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/8163,Roads,Completed,NH-ANNA NAGAR,107,560000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-107, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8164,Roads,Completed,NH-ANNA NAGAR,107,490000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-107, UNIT 23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9010,Buildings,Completed,NH-ANNA NAGAR,107,137000,"ATTENDING CEMENT CONCRETE PATCH WORK AT MC NICHOLAS ROAD 2nd LANE & Dr.GURUSAMY BRIDGE FOOTPATH IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9245,Buildings,Completed,NH-ANNA NAGAR,107,63000,"REPAIR AND IMPROVEMENT WORKS AT UPHC, SUBBARAYAN SCHOOL & AMMAUNAVAGAM BUILDINGS IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9340,Buildings,Completed,NH-ANNA NAGAR,107,287000,"REPAIR AND IMPROVEMENT WORKS AT MAYOR RAMANATHAN SALAI PLAYGROUND IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9579,Buildings,Completed,NH-ANNA NAGAR,107,26800,"REPAIRS AND IMPROVEMENT WORK PUBLIC CONVENIENCE AT SUBBARAYAN STREET IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9582,Buildings,Completed,NH-ANNA NAGAR,107,71000,"REPAIRS AND IMPROVEMENT WORK PUBLIC CONVENIENCE AT HARRINGTON ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9584,Buildings,Completed,NH-ANNA NAGAR,107,132000,"REPAIRS AND IMPROVEMENT WORK PUBLIC CONVENIENCE AT MC NICHOLAS ROAD OLD ZONAL OFFICE IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9585,Buildings,Completed,NH-ANNA NAGAR,107,268000,"PROVIDING WATER SUPPLY ARRANGEMENTS PUBLIC CONVENIENCE AT MANGALAPURAM MAIN ROAD IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9822,Buildings,Completed,NH-ANNA NAGAR,107,260000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE NAMMA TOILET AT MAYOR SATHYAMOORTHY SALAI IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9824,Buildings,Completed,NH-ANNA NAGAR,107,260000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE NAMMA TOILET AT MAYOR RAMANATHAN SALAI IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2019-20,2020-21 Q/2019-20/11062,Buildings,Completed,Q-Solid Waste Management,107,4540000,Construction of Shed for the installation and processing of Garden waste and tender Coconut shell at CAP in Division-107 Zone-8,Own Sources,8,2019-20,2020-21 Q/2019-20/11065,Buildings,Completed,Q-Solid Waste Management,107,1860000,"Providing Concrete pavement for installation ad processing of Garden Waste and Tender Coconut Shell at CAP in Division-107,Zone -8",Own Sources,8,2019-20,2020-21 Q/2019-20/14128,Electrical,Completed,Q-Solid Waste Management,107,1470000,"Construction of Electrical Panel Room for garden garbage and tender coconut processing facility at Central Asphalt Plant in Dn-107, Zone-8",Own Sources,8,2019-20,2020-21 NH/2019-20/0003,Buildings,Completed,NH-ANNA NAGAR,108,246000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE O BLOCK CHENNAI PRIMARY SCHOOL AT BHAGATH SINGH 2nd STREET IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/10089,Buildings,Completed,NH-ANNA NAGAR,108,318000,"REPAIRS AND IMPROVEMENTS TO THE AMMA UNAVAGAM, DIVISON OFFICE IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/10364,Buildings,Completed,NH-ANNA NAGAR,108,182000,"REPAIRS AND IMPROVEMENTS TO THE ANGANWADI CENTER NO:33603040117 AT N-BLOCK AND REPAIRS TO BIN AT VARIOUS STREETS A IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/11224,Roads,Completed,NH-ANNA NAGAR,108,888000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT IYYAPPAN NAGAR IN DIVISION-108, UNIT-22, ZONE-08",Own Sources,8,2019-20,2020-21 NH/2019-20/11225,Roads,Completed,NH-ANNA NAGAR,108,765000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT AVVAI NAGAR NEW WEST STREET IN DN-108, UNIT-22, ZONE-08",Own Sources,8,2019-20,2020-21 NH/2019-20/11226,Roads,Completed,NH-ANNA NAGAR,108,478000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT ANNASAMI STREET IN DIVISION-108, UNIT-22, ZONE-08",Own Sources,8,2019-20,2020-21 NH/2019-20/11229,Roads,Completed,NH-ANNA NAGAR,108,411000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT BHARATHIYAR STREET IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11230,Roads,Completed,NH-ANNA NAGAR,108,735000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT MGR STREET IN DN-108, UNIT-22, ZONE-08",Own Sources,8,2019-20,2020-21 NH/2019-20/11231,Roads,Completed,NH-ANNA NAGAR,108,746000,"IMPROVEMENTS TO THE INTERIOR BT ROAD AT KANNADASAN STREET IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/11232,Roads,Completed,NH-ANNA NAGAR,108,912000,"IMPROVEMENTS TO THE INTERIOR B.T. ROAD AT MARAIMALAIADIGAL STREET IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13059,Roads,Completed,NH-ANNA NAGAR,108,312100,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT JAYAMMAL STREET (PART) IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13064,Roads,Completed,NH-ANNA NAGAR,108,98900,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT KAMARAJ NAGAR 4TH STREET (PART) IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13065,Roads,Completed,NH-ANNA NAGAR,108,391000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT ANDAVAR STREET EXTN IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/13070,Roads,Completed,NH-ANNA NAGAR,108,158700,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NGO COLONY 3RD CROSS STREET (PATCH ) IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2020-21 NH/2019-20/1550,Buildings,Completed,NH-ANNA NAGAR,108,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT DIVISION OFFICE, M.G.R 3D STREET IN DIVISION -108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/2025,Parks,Completed,NH-ANNA NAGAR,108,68000,"CONSTRUCTION OF MULCH PIT AT R-BLOCK PARK , WATER TANK ROAD( ROAD SIDE PARK), AND SIDCO STREET(ROAD SIDE PARK) IN DIVISION-108,UNIT-22,ZONE-8.",Own Sources,8,2019-20,2019-20 NH/2019-20/2280,Buildings,Completed,NH-ANNA NAGAR,108,235000,"PROVIDING WELL RINGS AT DIVISION OFFICE, R - BLOCK PARK ELANGO STREET, WATER TANK ROAD (ROAD SIDE PARK) AND SIDCO STREET (ROAD SIDE PARK) IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/2770,Buildings,Completed,NH-ANNA NAGAR,108,266000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE CHS AT BHAGATH SINGH 2ND STREET N-BLOCK IN DIVISION-108, UNIT-22, ZONE-08.",Own Sources,8,2019-20,2019-20 NH/2019-20/5946,Storm Water Drain,Completed,NH-ANNA NAGAR,108,1291800,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-108, UNIT-22, ZONE-08 (IRR ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/5947,Storm Water Drain,Completed,NH-ANNA NAGAR,108,1163800,"DESILTING, REPAIRS AND IMPROVEMENT WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-108, UNIT-22, ZONE-08 (IRR ROADS)",Own Sources,8,2019-20,2019-20 NH/2019-20/6369,Buildings,Completed,NH-ANNA NAGAR,108,520000,"REPAIRS AND IMPROVEMENTS TO COMPOST YARD AT WATER TANK ROAD IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/6639,Buildings,Completed,NH-ANNA NAGAR,108,486601,"CONSTRUCTION OF COMPOST YARD AT SIDCO STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/6897,Buildings,Completed,NH-ANNA NAGAR,108,385000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE PUBLIC CONVEYANCE AT IN SIDE THE MMDA COLONY BUS TERMINUS IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/7349,Parks,Completed,NH-ANNA NAGAR,108,634000,"ANNUAL MAINTENANCE OF PARK AT R-BLOCK, MMDA COLONY IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2019-20,2021-22 NH/2019-20/8141,Roads,Completed,NH-ANNA NAGAR,108,470000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR CEMENT CONCRETE ROAD AT VARIOUS STREET IN DIVISION-108, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/8142,Roads,Completed,NH-ANNA NAGAR,108,545000,"ATTENDING PATCH WORK FOR DAMAGED INTERIOR BT ROAD AT VARIOUS STREET IN DIVISION-108, UNIT 22, ZONE-08.",Own Sources,8,2019-20,2020-21 NH/2019-20/9758,Roads,Completed,NH-ANNA NAGAR,108,439000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT J. D DURAIRAJ NAGAR 9TH STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9759,Roads,Completed,NH-ANNA NAGAR,108,132000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT J. D DURAIRAJ NAGAR 10TH STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9760,Roads,Completed,NH-ANNA NAGAR,108,142000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT J. D DURAIRAJ NAGAR 11TH STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9761,Roads,Completed,NH-ANNA NAGAR,108,142000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT J. D DURAIRAJ NAGAR 12TH STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9779,Roads,Completed,NH-ANNA NAGAR,108,390000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT AVVAI NAGAR EAST STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9780,Roads,Completed,NH-ANNA NAGAR,108,323000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT VEERAPANDI NAGAR 2ND CROSS STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 NH/2019-20/9781,Roads,Completed,NH-ANNA NAGAR,108,390000,"IMPROVEMENTS TO THE INTERIOR CEMENT CONCRETE ROAD AT DEIVASIGAMANI 2ND STREET IN DIVISION-108, UNIT-22, ZONE-8.",Own Sources,8,2019-20,2020-21 BR/2019-20/5094,Roads,Completed,BR-Bus Route Roads,109,1481000,"Partly relaying the road with BC after cold milling by paver finisher at Dr.MGR Salai in Dn- 109 & 113,Zone - IX",Grants,9,2019-20,2020-21 L/2019-20/8690,Electrical,Completed,L-Electrical,109,1542300,Replacement of Underground Cables in various location in div 109 and 112,Grants,9,2019-20,2021-22 L/2019-20/8692,Electrical,Completed,L-Electrical,109,10589400,"Replacement of Rusted Post, Short Post and EL Post in various location in div 109 and 112",Grants,9,2019-20,2020-21 NJ/2019-20/1219,Buildings,Completed,NJ-TEYNAMPET,109,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY SHED MICRO COMPOSING CENTERS AT INSIDE PLAY GROUND CENTRAL SCHOOL ROAD IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/13529,Roads,Completed,NJ-TEYNAMPET,109,768000,"Improvements to the Existing BT Road at Thiruvengadapuram 1st Street (Part) in Div-109, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/14546,Parks,Completed,NJ-TEYNAMPET,109,1031000,"MAINTENANCE FOR GILL NAGAR PARK AT IN DIV-109, UNIT-24,ZONE-09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16861,Roads,Completed,NJ-TEYNAMPET,109,1025000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT BAJANAI KOIL 7TH STREET IN DN-109,UNIT-24,ZONE-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/16862,Roads,Completed,NJ-TEYNAMPET,109,758000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT JOTHY RAMA LINGA STREET IN DN-109,UNIT-24,ZONE-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/2576,Bridges,Completed,NJ-TEYNAMPET,109,200000,"REPAIRS AND IMPROVEMENTS TO ANGANWADI CENTRE AT EAST NAMACHIVAYA PURAM (NO.33603020119) IN DIV-109, UNIT-24, ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2922,Bridges,Completed,NJ-TEYNAMPET,109,217000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CHS T.V SCHOOL DIVISION -109, UNIT -24,ZONE -09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/3114,Buildings,Completed,NJ-TEYNAMPET,109,217000,"ELECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENT AND MOTOR REPLACED AT CPS NAMACHIVAYAPURAM IN DIVISION -109,UNIT-24,ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/3115,Buildings,Completed,NJ-TEYNAMPET,109,255000,"ERECTION OF BORE WELL 50 M DEPTH WITH WATER SUPPLY ARRANGEMENTS AT CPS SANKARAPURAM DIVISION -109, UNIT -24,ZONE -09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6111,Storm Water Drain,Completed,NJ-TEYNAMPET,109,1077000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION 109, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6112,Storm Water Drain,Completed,NJ-TEYNAMPET,109,1267000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION 109, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2020-21 NJ/2019-20/7927,Buildings,Completed,NJ-TEYNAMPET,109,283000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 109, UNIT-24, ZONE-9",Own Sources,9,2019-20,2020-21 BR/2019-20/13578,Road Cut,Completed,BR-Bus Route Roads,110,528000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0651/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/13579,Road Cut,Completed,BR-Bus Route Roads,110,496000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0649/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/5095,Roads,Completed,BR-Bus Route Roads,110,1294000,"Partly relaying the road with BC after cold milling by paver finisher at Valluvar Kottam High Road in Dn- 110 & 113, Zone - IX",Grants,9,2019-20,2020-21 L/2019-20/11042,Electrical,Completed,L-Electrical,110,198300,Replacement of cable at conrete road in Valluvar Kottam High road in Division-110.,Own Sources,9,2019-20,2020-21 L/2019-20/11043,Electrical,Completed,L-Electrical,110,198800,Replacement of cable at conrete road in Pushpa Nagar Main Road in Division-110.,Own Sources,9,2019-20,2020-21 L/2019-20/11044,Electrical,Completed,L-Electrical,110,199500,Replacement of cable at conrete road in Valluvar Kottam High road and at Kodambakkam High road in Division-110.,Own Sources,9,2019-20,2020-21 L/2019-20/7231,Electrical,Completed,L-Electrical,110,200000,Replacement of underground cable at concrete road at Lake area 4th Cross street div 110,Own Sources,9,2019-20,2019-20 NJ/2019-20/0979,Buildings,Completed,NJ-TEYNAMPET,110,542000,"SERVICING OF EXISTING ELECTRICAL CREMATORIUM AT NUNGAMBAKKAM BURIAL GROUND IN DIV-110, U-24, ZONE-09",Own Sources,9,2019-20,2019-20 NJ/2019-20/10389,Buildings,Completed,NJ-TEYNAMPET,110,500000,"REPAIRS AND IMPROVEMENTS TO ZONAL OFFICER ROOM,ZONE 09 OFFICE CAMPUS IN DIVISION 110, UNIT 24 , ZONE 09",Own Sources,9,2019-20,2019-20 NJ/2019-20/10707,Buildings,Completed,NJ-TEYNAMPET,110,990000,"PROPOSED CONSTRUCTION FOR DRY WASTE AND BAILING SHED AT NUNGAMBAKKAM BURIAL GROUND IN DN 110, UNIT - 24, ZONE - IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/1211,Buildings,Completed,NJ-TEYNAMPET,110,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY SHED MICRO COMPOSING CENTERS AT INSIDE INDEPENDENCE DAY PARK VALLUVARKOTTAM HIGH ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/1321,Buildings,Completed,NJ-TEYNAMPET,110,500000,"DESILTING WELL AND IMPROVEMENTS WORK AT NELSAN MANIKAM SUBWAY IN DN 109,UNIT 24,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/13530,Roads,Completed,NJ-TEYNAMPET,110,1103000,"Improvements to the Existing BT Road at Jayalakshmipuram Main Road in Div-110, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13531,Roads,Completed,NJ-TEYNAMPET,110,2523000,"Improvements to the Existing BT Road at Kothari Road in Div-110, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2638,Buildings,Completed,NJ-TEYNAMPET,110,217000,"Erection of Bore well with 50m depth water supply arrangements to CPS Kamdar Nagar Main Road and motor to be replaced kutty Street in div 110,Unit 25,Zone 9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2647,Buildings,Completed,NJ-TEYNAMPET,110,179000,"Erection of Bore well with 50m depth water supply arrangements to CMS at Appasamy street in div 110,Unit-24,Zone -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/2648,Buildings,Completed,NJ-TEYNAMPET,110,255000,"Erection of Bore well with 50m depth water supply arrangements in CBHSS at School Road in Div-110,Unit-24,Zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/3584,Buildings,Completed,NJ-TEYNAMPET,110,1842000,"PROPOSED CONSTRUCTION MICRO COMPOST CENTRE INSIDE OF NUNGAMBAKKAM BURIAL GROUND IN DN.110,UNIT.24,ZONE.09",Own Sources,9,2019-20,2019-20 NJ/2019-20/6120,Storm Water Drain,Completed,NJ-TEYNAMPET,110,1390000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION -110, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2020-21 NJ/2019-20/6121,Storm Water Drain,Completed,NJ-TEYNAMPET,110,2100000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION 110, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6138,Storm Water Drain,Completed,NJ-TEYNAMPET,110,626000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION 110,UNIT 24,ZONE 09.",Own Sources,9,2019-20,2020-21 NJ/2019-20/6412,Buildings,Completed,NJ-TEYNAMPET,110,350000,"REPAIRS AND IMPROVEMENTS TO CHENNAI BOYS HER.SEC.SCHOOL E BLOCK BUILDING AT SCHOOL ROAD IN DN 110 UNIT 24,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6413,Buildings,Completed,NJ-TEYNAMPET,110,997000,"REPAIRS AND IMPROVEMENTS TO CORPORATION ELECTRICAL SUBSTATION BUILDING AT SCHOOL ROAD IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2019-20,2020-21 NJ/2019-20/7020,Buildings,Completed,NJ-TEYNAMPET,110,664000,"REPAIRS AND IMPROVEMENTS TO EXISTING COMPOSED YARD SHED AT INSIDE NUNGAMBAKKAM BURIAL GROUND IN DN 110,UNIT 24,ZONE 9",Own Sources,9,2019-20,2020-21 NJ/2019-20/7269,Storm Water Drain,Completed,NJ-TEYNAMPET,110,2500000,"CONSTRUCTION OF STORM WATER DRAIN OF SIZE 600MMX750MM AT KAKKAN COLONY 2ND SRTEET(UNDER MLA FUND 2019-2020) IN DN 110,UNIT 24,ZONE 9",MLACDS,9,2019-20,2020-21 NJ/2019-20/7939,Buildings,Completed,NJ-TEYNAMPET,110,239000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 110, UNIT-24, ZONE-9",Own Sources,9,2019-20,2020-21 BR/2019-20/15070,Road Cut,Completed,BR-Bus Route Roads,111,528000,Restoration of Road cut Made by Vodafone at various bus route roads in zone-9 (Deposit code-57/0512/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/15072,Road Cut,Completed,BR-Bus Route Roads,111,496000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0649/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/15073,Road Cut,Completed,BR-Bus Route Roads,111,528000,Restoration of Road cut Made by Vodafone at various bus route roads in zone 9 (Deposit code-57/0512/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/3762,Road Cut,Completed,BR-Bus Route Roads,111,1580000,"Restroration of Roadcut made by CMWSSB at Conron Smith Road(from the Jn of Aavin Booth to Avaishanmugam Salai) in Dn-111,Zone 9",Deposit Works,9,2019-20,2020-21 BR/2019-20/5093,Roads,Completed,BR-Bus Route Roads,111,2938000,"Partly relaying the road with BC after cold milling by paver finisher at Whites Road in Dn- 111,Zone - IX",Grants,9,2019-20,2020-21 BR/2019-20/5098,Roads,Completed,BR-Bus Route Roads,111,1763000,"Partly relaying the road with BC after cold milling by paver finisher at Peters Road in Dn- 111 & 115, Zone - IX",Grants,9,2019-20,2020-21 BR/2019-20/5106,Roads,Completed,BR-Bus Route Roads,111,741000,"Partly relaying the road with BC after cold milling by paver finisher at Pasumpon Muthuramalinga Devar Salai in Dn- 121, Zone - IX",Grants,9,2019-20,2020-21 NJ/2019-20/11711,Buildings,Completed,NJ-TEYNAMPET,111,2024000,"PROPOSED CONSTRUCTION OF COMPOUND WALL FENCING WITH GI SHEET AND WATER FACILITY ARRANGEMENTS FOR AKSHAYA PATRA KITCHEN CENTRE AT GREAMS ROAD IN DIVISION-111,UNIT-24,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/1257,Buildings,Completed,NJ-TEYNAMPET,111,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT COLLEGE LANE PARK IN DIV-111, UNIT-24, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/12938,Buildings,Completed,NJ-TEYNAMPET,111,1050000,"PROVIDING PLASTERING WORKS FOR COMPOUND WALLS AND OTHER IMPROVEMENT WORKS FOR AKSHAYA PATRA KITCHEN CENTRE AT GREAMS ROAD IN DIVISION-111,UNIT-24,ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/13534,Roads,Completed,NJ-TEYNAMPET,111,492000,"Improvements to the Existing BT Road at Gopalapuram 3rd Street in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13536,Roads,Completed,NJ-TEYNAMPET,111,383000,"Improvements to the Existing BT Road at Gopalapuram 5th Street in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13537,Roads,Completed,NJ-TEYNAMPET,111,464000,"Improvements to the Existing BT Road at Gopalapuram 7th Street in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13538,Roads,Completed,NJ-TEYNAMPET,111,1161000,"Improvements to the Existing BT Road at Gopalapuram 2nd Street in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13539,Roads,Completed,NJ-TEYNAMPET,111,668000,"Improvements to the Existing BT Road at Avvai shanmugam Salai (Part) in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13540,Roads,Completed,NJ-TEYNAMPET,111,980000,"Improvements to the Existing BT Road at Wallace Garden 1st Street in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13542,Roads,Completed,NJ-TEYNAMPET,111,428000,"Improvements to the Existing BT Road at Gulam Abas Alikhan 3rd Street in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13543,Roads,Completed,NJ-TEYNAMPET,111,3559000,"Improvements to the Existing BT Road at Kader Nawazkhan Roadin Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13544,Roads,Completed,NJ-TEYNAMPET,111,1795000,"Improvements to the Existing BT Road at Safee Mohammed Street in Div-111, Unit-24, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/14550,Parks,Completed,NJ-TEYNAMPET,111,1382000,"Maintenance for Park at Whites Road Park (Satyam) Park in Div-111,Unit-24, Zone - 9 (per year)",Own Sources,9,2019-20,2020-21 NJ/2019-20/14551,Parks,Completed,NJ-TEYNAMPET,111,237000,Maintenance for Ko.Su.Mani Park in Division 111 unit 24 zone 09 (per year),Own Sources,9,2019-20,2020-21 NJ/2019-20/14552,Parks,Completed,NJ-TEYNAMPET,111,1384000,Maintenance for Nungambakkam 4Th Lane Park in Division 111 unit 24 zone 09 (per year),Own Sources,9,2019-20,2020-21 NJ/2019-20/14553,Parks,Completed,NJ-TEYNAMPET,111,1420000,Maintenance for College Lane Park in Division 111 unit 24 zone 09 (per year),Own Sources,9,2019-20,2021-22 NJ/2019-20/14554,Parks,Completed,NJ-TEYNAMPET,111,1392000,Maintenance for Binny Road-Spencer Plaza Park in Division 111 unit 24 zone 09 (per year),Own Sources,9,2019-20,2021-22 NJ/2019-20/16871,Roads,Completed,NJ-TEYNAMPET,111,495000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT BEGAM SHAIB 1ST STREET IN DN-111,UNIT-24,ZONE-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/16872,Roads,Completed,NJ-TEYNAMPET,111,500000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT BEGAM SHAIB 2ND STREET IN DN-111,UNIT-24,ZONE-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/2540,Buildings,Completed,NJ-TEYNAMPET,111,1665000,"Construction of Sump,Water Supply Arrangements,Repairs and Improvements works to Division-111 Office Campus at Dhamodharan Street in Division 111, Unit 24, Zone 09",Own Sources,9,2019-20,2020-21 NJ/2019-20/2950,Buildings,Completed,NJ-TEYNAMPET,111,255000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS FOR CPS COCHIN HOUSE AT ANDERSON ROAD & CHS AT MODEL SCHOOL ROAD IN DIV-111, UNIT-24,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2951,Buildings,Completed,NJ-TEYNAMPET,111,217000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS FOR CMS 1A MODEL AT MODEL SCHOOL ROAD IN DIV-111, UNIT-24,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/5483,Buildings,Completed,NJ-TEYNAMPET,111,1450000,"Repairs and Improvements to Dhamodharan Street Corporation Building in Division 111, Unit 24, Zone 09",Own Sources,9,2019-20,2020-21 NJ/2019-20/6118,Storm Water Drain,Completed,NJ-TEYNAMPET,111,1680000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION 111, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6119,Storm Water Drain,Completed,NJ-TEYNAMPET,111,1390000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION 111, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7948,Buildings,Completed,NJ-TEYNAMPET,111,656600,"ATTENDING PATCH WORK AT VARIOUS STREET IN DIVISION 111, UNIT 24, ZONE - 9",Own Sources,9,2019-20,2021-22 NJ/2019-20/0855,Parks,Completed,NJ-TEYNAMPET,112,750000,"Improvement and repairs to the Childrens Park at Ganga nagar 1st main road in Division-112, Unit-26, Zone-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/11317,Buildings,Completed,NJ-TEYNAMPET,112,265000,"PROVIDING G.I.SHEET SHED AND SHEDDER MACHINE PLATFORM AT VELLALAR STREET IN DN 112,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/11689,Buildings,Completed,NJ-TEYNAMPET,112,124000,"IMPROVEMENTS TO EXISTING TRUSTPURAM PILLER AT PULIYUR MAIN ROAD IN DN 112,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/11691,Buildings,Completed,NJ-TEYNAMPET,112,108000,"PROVIDING ROOF TOP GARDEN FOR DIVISION OFFICE BUILDING 112 AT PULIYUR MAIN ROAD IN DN 112,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/1221,Buildings,Completed,NJ-TEYNAMPET,112,297000,"Proposed Construction of Material Recovery Facility Centre at Puliyur 1ST main road near Trustpuram canal in division-112, Unit-26, Zone-09,",Own Sources,9,2019-20,2019-20 NJ/2019-20/13547,Roads,Completed,NJ-TEYNAMPET,112,4576000,"Improvements to the Existing BT Road at Choolaimedu High Road in Div-112, Unit-26, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/13548,Roads,Completed,NJ-TEYNAMPET,112,1239000,"Improvements to the Existing BT Road at Vellalar Street in Div-112, Unit-26, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16008,Parks,Completed,NJ-TEYNAMPET,112,734842,"Maintenance for Park at Chitra park in Div-112, Unit-26, Zone - 9 (1 year)",Own Sources,9,2019-20,2020-21 NJ/2019-20/16409,Roads,Completed,NJ-TEYNAMPET,112,778000,"Improvements to the Existing CC Road at Nehru Street in Div--112, Unit-26, Zone -IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2637,Buildings,Completed,NJ-TEYNAMPET,112,179000,"Eraction of Borewell 50M depth with water supply arrangements at CHS School at Choolaimedu high road in Division-112, unit-26, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2704,Buildings,Completed,NJ-TEYNAMPET,112,179000,"Eraction of Borewell 50M depth with water supply arrangements at CMS School at Trustpuram 2nd main road in Division-112, unit-26, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2705,Buildings,Completed,NJ-TEYNAMPET,112,217000,"Eraction of Borewell 50M depth with water supply arrangements and Motor replaced at CPS School at Varadharajapet main road in Division-112, unit-26, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/6093,Storm Water Drain,Completed,NJ-TEYNAMPET,112,1630000,"Desilting and Minor Repair work to Strom Water Drain at various Street in Division-112, Unit-26, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6098,Storm Water Drain,Completed,NJ-TEYNAMPET,112,850000,"Desilting and Minor Repair work to Strom Water Drain at various street in Division-112, Unit-26, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/7823,Roads,Completed,NJ-TEYNAMPET,112,774000,"Patch Work at various street in Dn-112, Unit-26, Zone-09",Own Sources,9,2019-20,2020-21 BR/2019-20/15071,Road Cut,Completed,BR-Bus Route Roads,113,496000,Restoration of Road cut Made by M/s Reliance jio at various bus route roads in zone 9 (Deposit code-57/0552/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/4684,Roads,Completed,BR-Bus Route Roads,113,3497000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Habibulla Road (from the Jn of Thirumalai Pillai road to Ramakanth street ) in Dn-113, Zone -IX",Grants,9,2019-20,2020-21 L/2019-20/5486,Electrical,Completed,L-Electrical,113,199200,Erection of 8mtr Double Arch Bracket at Uthamar Gandhi Sali (Opp to Geminin flyover) and 6 mtr sigle Arch Bracket at Kodambakkam High Road (opp to EB office) div 113 of Zone - IX,Own Sources,9,2019-20,2019-20 NJ/2019-20/1193,Buildings,Completed,NJ-TEYNAMPET,113,297000,PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY CENTRE AT VALLUVARKOTTAM HIGH ROAD NEAR CI OFFICE IN DN 113 UNIT 26 ZONE 9,Own Sources,9,2019-20,2019-20 NJ/2019-20/13836,Buildings,Completed,NJ-TEYNAMPET,113,1820000,"ADDITIONAL IMPROVEMENT AND FURNISHING WORKS TO MP OFFICE BUILDING AT TANK BUND ROAD IN DIVISION 113,UNIT 26,ZONE 09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16010,Parks,Completed,NJ-TEYNAMPET,113,658000,"Maintenance for Kodambakkam High Road park in Div-113, Unit-26, Zone - 9 (1 year)",Own Sources,9,2019-20,2020-21 NJ/2019-20/16306,Roads,Completed,NJ-TEYNAMPET,113,546000,"Improvements to the Existing BT Road at Pillaiyar Kovil Street in Div-113, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16307,Roads,Completed,NJ-TEYNAMPET,113,567000,"Improvements to the Existing BT Road at Pillaiyar Kovil Lane Street in Div-113, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16308,Parks,Completed,NJ-TEYNAMPET,113,566000,"Improvements to the Existing BT Road at Balu Street in Div-113, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16309,Roads,Completed,NJ-TEYNAMPET,113,326000,"Improvements to the Existing BT Road at Parthasarathypuram 2nd Street in Div-113, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16310,Roads,Completed,NJ-TEYNAMPET,113,680000,"Improvements to the Existing BT Road at Ramanajum Street in Div-113, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/1751,Buildings,Completed,NJ-TEYNAMPET,113,540000,"PROVIDING WELL RING FOR COMPOSTING WORK AT VARIOUS PLACE IN DIV -112, 113, 117, & 122 UNIT - 26, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/2522,Buildings,Completed,NJ-TEYNAMPET,113,514000,"SUPPLYING OF BIO-SHREDDING MACHINE AND WEIGHING MACHINE IN UNIT -26, ZONE - 9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2794,Buildings,Completed,NJ-TEYNAMPET,113,255000,ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED AT CMS DHARMAPURAM IN DN-113 UNIT-26 ZONE-09,Own Sources,9,2019-20,2019-20 NJ/2019-20/2864,Buildings,Completed,NJ-TEYNAMPET,113,217000,ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND EXISTING MOTOR REPLACED AT CMS RAMA STREET IN DN-113 UNIT-26 ZONE-09,Own Sources,9,2019-20,2019-20 NJ/2019-20/6102,Storm Water Drain,Completed,NJ-TEYNAMPET,113,528000,"Desilting and Minor Repair work to Strom Water Drain at various street, in Division-113, Unit-26, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6103,Storm Water Drain,Completed,NJ-TEYNAMPET,113,980000,"Desilting and Minor Repair work to Strom Water Drain at various street, in Division-113, Unit-26, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6104,Storm Water Drain,Completed,NJ-TEYNAMPET,113,1180000,"Desilting and Minor Repair work TO Strom Water Drain at various street in Division-113, Unit-26, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6874,Buildings,Completed,NJ-TEYNAMPET,113,2278000,Improvement to the Existing GYM building Converting to Chennai Central M.P. Office at Tank bund Road in Dn-113 unit-26 Zone-09,Own Sources,9,2019-20,2019-20 NJ/2019-20/7251,Buildings,Completed,NJ-TEYNAMPET,113,1295000,"Water supplying, Drainage and Electrical arrangements to the Existing GYM building Converting to Chennai Central M.P. Office at Tank Bund Road in Dn-113, unit-26, Zone-09",Own Sources,9,2019-20,2019-20 NJ/2019-20/7786,Roads,Completed,NJ-TEYNAMPET,113,166000,"Attending Patch Work at various Street in Dn-113, Unit-26, Zone-09",Own Sources,9,2019-20,2020-21 NJ/2019-20/8458,Buildings,Completed,NJ-TEYNAMPET,113,500000,"REPAIRS AND IMPROVEMENTS TO EXISTING COMPOSED YARD FOR INSIDE SSA BUILDING CAMPUS AT VALLUVAR KOTTAM HIGH ROAD IN DN 113,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/9578,Buildings,Completed,NJ-TEYNAMPET,113,2397757,"IMPROVEMENT WORK TO TRANSFERSTATION LORRY SHED AT KODAMBAKKAM HIGH ROAD IN DIVISION -113,UNIT-26,ZONE-09",Own Sources,9,2019-20,2021-22 NJ/2019-20/9595,Buildings,Completed,NJ-TEYNAMPET,113,385000,"Repair and Improvements to the existing corporation lane PC at Kodambakkam high Road in Dn-113, Unit-26,Zone-09.",Own Sources,9,2019-20,2020-21 NJ/2019-20/9605,Buildings,Completed,NJ-TEYNAMPET,113,416000,"Repair and Improvements to the Existing Badhirekarai PC in Dn-113, Unit-26,Zone-09.",Own Sources,9,2019-20,2020-21 NJ/2019-20/9631,Buildings,Completed,NJ-TEYNAMPET,113,217000,"Repair and Improvements to the Existing Gangaikaraipuram PC near singh kovil in Dn-113, Unit-26,Zone-09.",Own Sources,9,2019-20,2020-21 BR/2019-20/13581,Road Cut,Completed,BR-Bus Route Roads,114,496000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0651/2018-19),Deposit Works,9,2019-20,2019-20 BR/2019-20/4685,Roads,Completed,BR-Bus Route Roads,114,2728000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Babu Jagajeevanram salai (from the Jn of Wallaja Salai to Parthasarathy Street) in Dn-114, Zone -IX",Grants,9,2019-20,2020-21 BR/2019-20/5103,Roads,Completed,BR-Bus Route Roads,114,1411000,"Partly relaying the road with BC after cold milling by paver finisher at Kamarajar Salai (Marina) in Dn- 114, Zone - IX",Grants,9,2019-20,2020-21 NJ/2019-20/10726,Parks,Completed,NJ-TEYNAMPET,114,722000,"PROVIDING BARRICADING ARRANGEMENT AND WATCHING TOWER IN VIEW OF KANNUM PONGAL FESTIVAL 2020 AT MARINA BEACH FROM NAPPIER BRIDGE TO LIGHT HOUSE IN DIV 114,116,120,121,125 ,U-27A,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/10728,Parks,Completed,NJ-TEYNAMPET,114,500000,"ARRANGEMENT OF PORTABLE TOILET, ADDITIONAL WATER TANKER LORRY AND SHAMINA, FOR THE VIEW OF KANNUM PONGAL AND REPUBLIC DAY CELEBRATION 2020 AT MARINA BEACH IN DIV 114,116,120,121,125 ,U-27A,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/11257,Parks,Completed,NJ-TEYNAMPET,114,310000,"Improvements to the Road side park at Wallaja Road in Div-114, U-27, Z-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/1245,Buildings,Completed,NJ-TEYNAMPET,114,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT VICTORIA HOSTEL ROAD (NEAR PC) IN DIV-114, UNIT-27, ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/1254,Buildings,Completed,NJ-TEYNAMPET,114,291000,"PROPOSED CONSTRUCTION OF COMPOST PIT WITH WELL RING ARRANGEMENTS AT VARIOUS LOCATIONS IN UNIT-27, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/13030,Buildings,Completed,NJ-TEYNAMPET,114,2680000,"OUTSOURCING FOR PUBLIC CONVENIENCE IN MARINA BEACH (6PC) FOR (6 MONTHS) IN DN.114,116 &125, UNIT-27A, ZONE-IX",Own Sources,9,2019-20,2021-22 NJ/2019-20/14542,Parks,Completed,NJ-TEYNAMPET,114,1693000,"Maintenance for Park at Anna Memorial park in Div-114, Unit-27A, Zone - 9 (per year)",Own Sources,9,2019-20,2021-22 NJ/2019-20/15748,Parks,Completed,NJ-TEYNAMPET,114,2027000,"Annual maintenance of park at Marina Beach(Lawn 1-8) In Dn-114 and 116, Unit-27A, Zone-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/16404,Roads,Completed,NJ-TEYNAMPET,114,364000,"Improvements and laying to the cement concrete road at Yusuf street in Div-114,U-27,Z-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/4276,Buildings,Completed,NJ-TEYNAMPET,114,933000,"IMPROVEMENTS TO BIO-GAS AT KG HOSPITAL NEAR AMMA UNAVAGAM IN DIV-114,UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/5136,Buildings,Completed,NJ-TEYNAMPET,114,54000,"PROVIDING ELECTRICAL AND WATER SUPPLY ARRANGEMENTS TO PC AT JANI BASHA STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/5137,Buildings,Completed,NJ-TEYNAMPET,114,65000,"PROVIDING AND FIXING WELLRINGS FOR COMPOSIT PIT AT VICTORIA HOSTEL ROAD IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/5138,Buildings,Completed,NJ-TEYNAMPET,114,21500,"Improvements to material recovery facility at victoria hostel road in dn-114,unit-27,zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/5139,Buildings,Completed,NJ-TEYNAMPET,114,106000,"IMPROVEMENTS TO DIVISION OFFICE -114 AT ARUNACHALAM STREET IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/5140,Buildings,Completed,NJ-TEYNAMPET,114,32000,"Plumbing arrangements to amma unavagam at vallaba agraharam street in dn-114,unit-27,zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6105,Storm Water Drain,Completed,NJ-TEYNAMPET,114,2498000,"Desilting to the strom water drain and minor repair work at various street IN DN-114,Unit-27,Zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6114,Storm Water Drain,Completed,NJ-TEYNAMPET,114,2430000,"Desilting to the strom water drain and minor repair work at various street IN DN-114,UNIT-27,ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7838,Roads,Completed,NJ-TEYNAMPET,114,486000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 114, UNIT-27, ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/8328,Parks,Completed,NJ-TEYNAMPET,114,215000,"PLANTATION PLANTS IN CENTER MEDIAN AT SIVANANDA SALAI AND KAMARAJAR SALAI IN DN-114, UNIT-27 ,ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/8683,Buildings,Completed,NJ-TEYNAMPET,114,1460000,"OUTSOURCING FOR PUBLIC CONVENIENCE IN MARINA BEACH (6PC) FOR (3 MONTHS) IN DN.114,116 &125, UNIT-27A, ZONE-IX",Own Sources,9,2019-20,2020-21 BR/2019-20/13580,Road Cut,Completed,BR-Bus Route Roads,115,528000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0649/2018-19),Deposit Works,9,2019-20,2019-20 L/2019-20/3702,Electrical,Completed,L-Electrical,115,50100,"Fixing and Removel of 128 Nos Existing 70 Watts SVL Fitting into 40 Watts New LED Fitting at Sheik Dhawth Street, Peters Colony, C N K Road, Pillaiyar Koil Street, Kuppu Muthu Street, Lock Nagar, Indira Garden, R O B Street and Barial Ground in Division - 114, 115,and 120, Zone-IX.",Own Sources,9,2019-20,2019-20 NJ/2019-20/1222,Buildings,Completed,NJ-TEYNAMPET,115,294000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY FACILITY AT COMMUNIY HALL SIDE PARKING AREA IN MIR-BAKSHI ALI STREET AT DIV-115, UNIT- 27, ZONE - IX",Own Sources,9,2019-20,2019-20 NJ/2019-20/16908,Roads,Completed,NJ-TEYNAMPET,115,479000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT J.J.KHAN 4TH LANE IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/16909,Roads,Completed,NJ-TEYNAMPET,115,562000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT PERUMAL LANE IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/2741,Buildings,Completed,NJ-TEYNAMPET,115,217000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS FOR CMS AT SOORAPPA STREET AND MOTOR REPLACED AT CPS MIRSAHIBPET (DR.BESANT ROAD)IN DIV-115, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/5142,Buildings,Completed,NJ-TEYNAMPET,115,81000,"PROPOSED CONSTRUCTION OF COMPOST PIT WITH WELL RING ARRANGEMENTS AND MULCH PIT AT VARIOUS LOCATIONS IN DN-115, UNIT-27, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/5143,Buildings,Completed,NJ-TEYNAMPET,115,65500,"Supplying and fixing well rings in community center at mirbakshi ali street in dn-115,unit-27,zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/5144,Buildings,Completed,NJ-TEYNAMPET,115,266000,"Construction of bio shredder machine room with new electrical room in community hall parking area at mirbakshi ali street in dn-115,unit-27,zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/5146,Buildings,Completed,NJ-TEYNAMPET,115,83000,"Repairs and Improvements to cms at soorapan street in dn-115 ,unit-27,zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6095,Storm Water Drain,Completed,NJ-TEYNAMPET,115,880000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DN-115,UNIT-27,ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7910,Roads,Completed,NJ-TEYNAMPET,115,318000,"ATTENDING MINOR PATCH WORK AT VARIOUS STREETS IN WARD-115, UNIT-27, ZONE-09.",Own Sources,9,2019-20,2020-21 BR/2019-20/13577,Road Cut,Completed,BR-Bus Route Roads,116,1024000,Restoration of Road cut Made by BHARATHI AIRTEL at various bus route roads in zone 9 (Deposit code-57/0522/2018-19),Deposit Works,9,2019-20,2020-21 NJ/2019-20/1204,Buildings,Completed,NJ-TEYNAMPET,116,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT Dr.BESANT ROAD (UNIT-27 OFFICE CAMPUS) IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/16911,Roads,Completed,NJ-TEYNAMPET,116,687000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT RAJA HANUMANTHA LALA LANE IN DN-116,UNIT-27,ZONE-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/2518,Buildings,Completed,NJ-TEYNAMPET,116,351000,"SUPPLYING OF BIO-SHREDDER MACHINE AND WEIGHING MACHINE IN UNIT - 27, ZONE -9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2583,Buildings,Completed,NJ-TEYNAMPET,116,217000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED FOR CMS AT T.H. ROAD IN DIV-116, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/4275,Storm Water Drain,Completed,NJ-TEYNAMPET,116,2460000,"CONSTRUCTION OF RCC STORM WATER DRAIN AT SINGARACHARI STREET ( FROM NALLATHAMBI STREET JN. TO VENKATRANGAM 2nd LANE JN ) IN DIV-116, U-27, Z-9. (UNDER MLA`S FUND SCHEME)",MLACDS,9,2019-20,2019-20 NJ/2019-20/4278,Storm Water Drain,Completed,NJ-TEYNAMPET,116,2460000,"CONSTRUCTION OF RCC STORM WATER DRAIN AT CAR STREET ( FROM VENKATRANGAM 2nd LANE JN. TO SREE VIJAYA NURSERY & PRIMARY SCHOOL ) IN DIV-116, U-27, Z-9.(UNDER MLA`S FUND SCHEME)",MLACDS,9,2019-20,2019-20 NJ/2019-20/4282,Storm Water Drain,Completed,NJ-TEYNAMPET,116,2460000,"CONSTRUCTION OF RCC STORM WATER DRAIN AT CAR STREET (FROM PARTHASARATHI TEMPLE POND TO SREE VIJAYA NURSERY & PRIMARY SCHOOL) IN DIV-116, U-27, Z-9.(UNDER MLA`S FUND SCHEME)",MLACDS,9,2019-20,2019-20 NJ/2019-20/4284,Roads,Completed,NJ-TEYNAMPET,116,1920000,"LAYING CEMENT CONCRETE ROAD AT AYOTHIYA KUPPAM MAIN ROAD ( FROM SUNGUWAR STREET TO BLOCK - I ) IN DIV-116, U-27,Z-9. (UNDER MLA`S FUND SCHEME)",MLACDS,9,2019-20,2019-20 NJ/2019-20/4291,Buildings,Completed,NJ-TEYNAMPET,116,138000,"DEMOLITION OF PUBLIC CONVINIENCE AND PROVIDING COMPOSIT YARD AT SIVARJAPURAM IN DIV-116, U-27, Z-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/4416,Storm Water Drain,Completed,NJ-TEYNAMPET,116,2010000,"Desilting to the strom water drain and minor repair work at various streets in Div-116, Unit-27, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/4718,Buildings,Completed,NJ-TEYNAMPET,116,980000,"Providing RO Purifier and Borewell to CMS at T.H.Road in Div-116, Unit-27, Zone-9.(UNDER MLA`S FUND SCHEME)",MLACDS,9,2019-20,2019-20 NJ/2019-20/6529,Buildings,Completed,NJ-TEYNAMPET,116,948000,"OUTSOURCING FOR PUBLIC CONVENIENCE IN MARINA SERVICE ROAD NEAR THIRUVALLUVAR STATUE IN DN-116, AND NEAR GANDHI STATUE IN DN-121, UNIT-27A,ZONE-IX",Own Sources,9,2019-20,2021-22 NJ/2019-20/7919,Buildings,Completed,NJ-TEYNAMPET,116,471000,"ATTENDING PATCH WORK AT VARIOUS ROADS IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/8416,Buildings,Completed,NJ-TEYNAMPET,116,1082000,"IMPROVEMENTS TO UNIT-27 OFFICE BUILDING AT Dr.BESANT ROAD IN DIV-116, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/9649,Buildings,Completed,NJ-TEYNAMPET,116,250000,"Providing shed arrangements for vegitable shreding machine and improvements works at unit-27 office campus in dn-116, unit-27,zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/9654,Buildings,Completed,NJ-TEYNAMPET,116,248000,"Urgent Repair and improvements for corporation buildings and roads in dn-116,unit-27, zone-9.",Own Sources,9,2019-20,2019-20 BR/2019-20/5107,Roads,Completed,BR-Bus Route Roads,117,1185000,"Partly relaying the road with BC after cold milling by paver finisher at North usman Road in Dn- 117 &136 , Zone - IX & X",Grants,9,2019-20,2020-21 NJ/2019-20/0328,Buildings,Completed,NJ-TEYNAMPET,117,645000,"REPAIRS AND IMPROVEMENTS TO DIVISION OFFICE AND ICDS CENTRE (CENTRE NO 33603080214) AT DR.SEVALIAR SIVAGIGANESAN SALAI IN DN 117,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/1073,Buildings,Completed,NJ-TEYNAMPET,117,297000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY CENTRE AT THIYAGARAYA ROAD NEAR MAMBALAM CANAL IN DIVISION-117,UNIT-26,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/12725,Buildings,Completed,NJ-TEYNAMPET,117,248000,"DISMANTLING OF THE EXISTING HEALTH POST BUILDING AT DR.GIRIAPPA ROAD IN DN 117,UNIT 26,ZONE 9",Own Sources,9,2019-20,2020-21 NJ/2019-20/13991,Buildings,Completed,NJ-TEYNAMPET,117,1500000,"SHEETING WORK FOR SHREADING MACHINE AND OTHER IMPROVEMENT WORKS IN COMPOSED YARD AT THYAGARAYA ROAD IN DIV-117, UNIT-26, ZONE-09",Own Sources,9,2019-20,2020-21 NJ/2019-20/14752,Buildings,Completed,NJ-TEYNAMPET,117,500000,"IMPROVEMENTS TO THE URBAN PRIMARY HEALTH CENTRE BUILDING AT RAMAGAMATHU PURAM IN DN 117,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/16022,Parks,Completed,NJ-TEYNAMPET,117,600000,"MAINTENANCE FOR CHARI PARK AT IN DIV-117, UNIT-26,ZONE-09 (1 Year)",Own Sources,9,2019-20,2021-22 NJ/2019-20/16311,Roads,Completed,NJ-TEYNAMPET,117,2341000,"Improvements to the Existing BT Road at Hindi Prachara Saba Road in Div-117, Unit-26, Zone-IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16312,Roads,Completed,NJ-TEYNAMPET,117,5248000,"Improvements to the Existing BT Road at Mambalam High Road in Div-117, Unit-26, Zone-IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16313,Roads,Completed,NJ-TEYNAMPET,117,2083000,"Improvements to the Existing BT Road at Rajan Street in Div-117, Unit-26, Zone-IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16314,Roads,Completed,NJ-TEYNAMPET,117,1799000,"Improvements to the Existing BT Road at Kirshna Street in Div-117, Unit-26, Zone-IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16315,Roads,Completed,NJ-TEYNAMPET,117,644000,"Improvements to the Existing BT Road at Basudev Street in Div-117, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16316,Roads,Completed,NJ-TEYNAMPET,117,1044000,"Improvements to the Existing BT Road at Daniel Street in Div-117, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16317,Parks,Completed,NJ-TEYNAMPET,117,2673000,"Improvements to the Existing BT Road at Saravana Street in Div-117, Unit-26, Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2866,Buildings,Completed,NJ-TEYNAMPET,117,255000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED AT CMS AT ERIKARAI IN DN-117, UNIT-26 ZONE-09",Own Sources,9,2019-20,2019-20 NJ/2019-20/2868,Buildings,Completed,NJ-TEYNAMPET,117,358000,"Erection of Borewell 50M depth with water supply arrangement at CPS at Giriappa road in Division-117, Unit-26, Zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/4037,Roads,Completed,NJ-TEYNAMPET,117,1437000,Widening and laying CC Road for using RMC M30 Grade Concrete at Thomas Road {Part} in Dn-117 Unit-26 Zone-09,Own Sources,9,2019-20,2019-20 NJ/2019-20/6128,Storm Water Drain,Completed,NJ-TEYNAMPET,117,1580000,"Desilting and Minor Repair work to Strom Water Drain at various street in Division-117, Unit-26, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6131,Storm Water Drain,Completed,NJ-TEYNAMPET,117,1700000,"Desilting and Minor Repair work to Strom Water Drain at various street, in Division-117, Unit-26, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/7807,Roads,Completed,NJ-TEYNAMPET,117,260000,Attending Patch Work at various street in Dn-117 unit-26 zone-09,Own Sources,9,2019-20,2020-21 BR/2019-20/11157,Roads,Completed,BR-Bus Route Roads,118,2500000,PROVIDING AND LAYING OF HOT APPLIED THERMOPLASTIC PAINTING AT CATHEDRAL ROAD AND DR.RADHA KRISHNAN SALAI IN ZONE-9,Own Sources,9,2019-20,2020-21 BR/2019-20/13583,Road Cut,Completed,BR-Bus Route Roads,118,496000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0651/2018-19),Deposit Works,9,2019-20,2019-20 BR/2019-20/1549,Road Cut,Completed,BR-Bus Route Roads,118,2490000,"Restoration of roadcut made by CMWSSB @ Cathedral road ( from the Jn of Prince Jewellery to Anna Salai (South)) in Dn -118,Zone 9",Deposit Works,9,2019-20,2019-20 BR/2019-20/1614,Road Cut,Completed,BR-Bus Route Roads,118,2480000,"Restoration of work (road cut) made by CMWSSB @ Cathedral Road (Southern Side) , Dn-118 , Zone 9 (From the Jn of Kasthuri Rangan Street to Prince Jewellery)",Deposit Works,9,2019-20,2019-20 BR/2019-20/5100,Roads,Completed,BR-Bus Route Roads,118,1174000,"Partly relaying the road with BC after cold milling by paver finisher at Avvai Shanmugam Salai in Dn- 118 & 119, Zone - IX",Grants,9,2019-20,2020-21 BR/2019-20/7003,Road Cut,Completed,BR-Bus Route Roads,118,486000,"Restoration of road cut made by CMWSSB at Cathedral Road (Jn of TTK road , Infront of American Embassy and other service connection) in Dn-118,Zone 9",Deposit Works,9,2019-20,2020-21 NJ/2019-20/1212,Buildings,Completed,NJ-TEYNAMPET,118,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT SCHEME ROAD IN DIVISION-118,UNIT-24,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/12849,Buildings,Completed,NJ-TEYNAMPET,118,400000,"Providing Borewell arrangements for Division Office at Muthiah Street in Div-118. Unit-24, Zone-09",Own Sources,9,2019-20,2019-20 NJ/2019-20/12855,Buildings,Completed,NJ-TEYNAMPET,118,100000,"Improvement works to Compost Yard at Scheme Road in Div-118, Unit-24, Zone-09",Own Sources,9,2019-20,2019-20 NJ/2019-20/14548,Parks,Completed,NJ-TEYNAMPET,118,636000,"Maintenance for Park at Thiru.Vi.Ka Park in Div-118,Unit-24, Zone - 9 (per year)",Own Sources,9,2019-20,2020-21 NJ/2019-20/16319,Roads,Completed,NJ-TEYNAMPET,118,1854000,"IMPROVEMENTS TO THE EXISTING BT ROAD AT KASTHURI ESTATE 2ND STREET IN DIV-118, UNIT-24, ZONE-09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16320,Roads,Completed,NJ-TEYNAMPET,118,867000,"IMPROVEMENTS TO THE EXISTING BT ROAD AMMAIAPPAN STREET IN DIV-118, UNIT-24, ZONE-09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16321,Roads,Completed,NJ-TEYNAMPET,118,297000,"IMPROVEMENTS TO THE EXISTING BT ROAD AT AYYA STREET IN DIV-118, UNIT-24, ZONE-09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16915,Roads,Completed,NJ-TEYNAMPET,118,523000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT REBORIA STREET IN DN-118,UNIT-24,ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/6117,Storm Water Drain,Completed,NJ-TEYNAMPET,118,2210000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS STREET IN DIVISION 118, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7946,Buildings,Completed,NJ-TEYNAMPET,118,630000,"ATTENDING PATCH WORK AT VARIOUS STREET IN DIVISION 118, UNIT 24, ZONE - 9.",Own Sources,9,2019-20,2020-21 BR/2019-20/13585,Road Cut,Completed,BR-Bus Route Roads,119,528000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0649/2018-19),Deposit Works,9,2019-20,2019-20 BR/2019-20/13586,Road Cut,Completed,BR-Bus Route Roads,119,528000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0651/2018-19),Deposit Works,9,2019-20,2019-20 BR/2019-20/5091,Roads,Completed,BR-Bus Route Roads,119,1763000,"Partly relaying the road with BC after cold milling by paver finisher at Royapettah High Road in Dn- 119 & 121,Zone - IX",Grants,9,2019-20,2020-21 NJ/2019-20/1210,Buildings,Completed,NJ-TEYNAMPET,119,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT (UNIT-24 OFFICE CAMPUS) CIT COLONY IN DIV-119, UNIT-24, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/16323,Roads,Completed,NJ-TEYNAMPET,119,587000,"Improvements to the Existing BT Road at Kalingarayan Street in Div-119, Unit-24, Zone -IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16324,Roads,Completed,NJ-TEYNAMPET,119,572000,"Improvements to the Existing BT Road at Lalithapuram in Div-119, Unit-24, Zone -IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16325,Roads,Completed,NJ-TEYNAMPET,119,766000,"Improvements to the Existing BT Road at Avvai Shanmugam Salai 1st Lane in Div-119, Unit-24, Zone -IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16326,Roads,Completed,NJ-TEYNAMPET,119,558000,"Improvements to the Existing BT Road at Appasamy Street in Div-119, Unit-24, Zone -IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16916,Roads,Completed,NJ-TEYNAMPET,119,1978000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT DR. R.K.SALAI 7TH STREET IN DN-119,UNIT-24,ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/1837,Buildings,Completed,NJ-TEYNAMPET,119,1372000,"PROVIDING WELL RING FOR COMPOSTING WORK AT VARIOUS PLACE IN UNIT - 24, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/2512,Roads,Completed,NJ-TEYNAMPET,119,514000,"SUPPLYING OF BIO-SHREDDER MACHINE AND WEIGHING MACHINE IN UNIT - 24, ZONE -9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2617,Buildings,Completed,NJ-TEYNAMPET,119,179000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS FOR CMS AT BALAJI NAGAR IN DIV-119, UNIT-24,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2621,Buildings,Completed,NJ-TEYNAMPET,119,217000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS FOR CHENNAI URDU MIDDLE SCHOOL AT PETERS ROAD IN DIV-119, UNIT-24,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6099,Storm Water Drain,Completed,NJ-TEYNAMPET,119,2485000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS IN DIVISION 119, UNIT - 24, ZONE - 9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6100,Storm Water Drain,Completed,NJ-TEYNAMPET,119,2016000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS BUS ROUTE ROAD IN DIVISION 119, UNIT - 24, ZONE -9",Own Sources,9,2019-20,2019-20 NJ/2019-20/6785,Buildings,Completed,NJ-TEYNAMPET,119,256000,Community well into ornamental well work at Greater Chennai Corporation Unit-24 office at C.I.T Colony 6th street in Division -119 Unit -24 Zone -9,Own Sources,9,2019-20,2019-20 NJ/2019-20/7176,Buildings,Completed,NJ-TEYNAMPET,119,983000,"Providing RO Purifier and Borewell to NNMP Center at Balaji nagar 3rd street in Div.119, Unit.24, Zone.9.(UNDER MLA FUND)",MLACDS,9,2019-20,2019-20 NJ/2019-20/7488,Buildings,Completed,NJ-TEYNAMPET,119,2253000,"Construction of New Toilet Building and Providing Bore well arrangements in Dhobikanna at muthaiya Garden street in div-119,unit-24, zone-9.( Under MLA Fund)",MLACDS,9,2019-20,2020-21 NJ/2019-20/7909,Buildings,Completed,NJ-TEYNAMPET,119,690000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 119, UNIT-24, ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/9655,Buildings,Completed,NJ-TEYNAMPET,119,260000,"Providing shed arrangements for vegitable shreding machine and improvements works at unit-24 office campus in dn-119, unit-24,zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/9657,Buildings,Completed,NJ-TEYNAMPET,119,238000,"Urgent repair and improvements for corporation building and roads in dn-119,unit-24,zone-9.",Own Sources,9,2019-20,2019-20 BR/2019-20/5099,Roads,Completed,BR-Bus Route Roads,120,1174000,"Partly relaying the road with BC after cold milling by paver finisher at Dr.Natesan Road in Dn- 120 & 121, Zone - IX",Grants,9,2019-20,2020-21 NJ/2019-20/1242,Buildings,Completed,NJ-TEYNAMPET,120,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT GAJPTHI STREET (KRISHNAPET BURIAL GROUND) IN DIV-120, UNIT-27, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/13003,Parks,Completed,NJ-TEYNAMPET,120,89000,"improvements to park opp to vinayagar temple in llyods colony in dn-120,unit-27,zone-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/13037,Parks,Completed,NJ-TEYNAMPET,120,249000,"Improvements to the children play field And other works at Lloyds colony ( opposite to vinayagar temple) in div-120,unit-27,zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/13077,Buildings,Completed,NJ-TEYNAMPET,120,158000,"REPAIRS AND IMPROVEMENTS TO CORPORATION BUILDINGS AT VARIOUS LOCATIONS IN DN-120,UNIT-27,ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/15749,Parks,Completed,NJ-TEYNAMPET,120,2027000,"Annual maintenance of park at Marina Beach(Lawn 9-14 ) In Dn-120,121 and 125, Unit-27A, Zone-9",Own Sources,9,2019-20,2021-22 NJ/2019-20/2751,Buildings,Completed,NJ-TEYNAMPET,120,255000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND EXISTING MOTOR REPLACED FOR CMS AT KRISHNAMPET IN DIV-120, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2752,Buildings,Completed,NJ-TEYNAMPET,120,217000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED FOR CGHS AT IRUSAPPA IN DIV-120, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/3566,Buildings,Completed,NJ-TEYNAMPET,120,1842000,"PROPOSED CONSTRUCTION MICRO COMPOST CENTRE INSIDE OF KRISHNAMPET BURIAL GROUND AT GAJAPATHY MAIN STREET IN DIVISION - 120, UNIT-27, ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/6123,Storm Water Drain,Completed,NJ-TEYNAMPET,120,612000,"Desilting and Minor Repair works at various street in Division-120, Unit-27, Zone-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/7333,Storm Water Drain,Completed,NJ-TEYNAMPET,120,2414000,"CONSTRUCTION OF RCC STORM WATER DRAIN AT LLOYDS COLONY IN DIV-120, U-27, Z-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/7334,Buildings,Completed,NJ-TEYNAMPET,120,1530000,"CONSTRUCTION OF COMPOUND WALL AND GATE FOR LORRY STATION( RAMKEY) AT LLOYDS COLONY IN DIV-120, U-27, Z-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/7940,Roads,Completed,NJ-TEYNAMPET,120,430000,"ATTENDING THE PATCH WORK AT VARIOUS ROAD AND STREET IN DN.120,UNIT.27,ZONE.09",Own Sources,9,2019-20,2021-22 L/2019-20/10701,Electrical,Completed,L-Electrical,121,226400,"Painting of 524 nos 8 mtr Octagonal street lamp post at Kamaraj salai Both side, Service Road, (from Napier bridge to Light House ) and Loop Road in view of Repulic day(2020) to Division-114,116,120,121,125 &126. in Zone-IX.",Own Sources,9,2019-20,2020-21 NJ/2019-20/1247,Buildings,Completed,NJ-TEYNAMPET,121,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT IN DIV-121, UNIT-27, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/14969,Buildings,Completed,NJ-TEYNAMPET,121,498000,Urgent Repair works to the corporation buildings and other Bus Routs Road in dn-121 unit-27 zone-9,Own Sources,9,2019-20,2020-21 NJ/2019-20/16829,Roads,Completed,NJ-TEYNAMPET,121,520000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT RAGAVAN THOTTAM MAIN ROAD (PART) IN DN-121,UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16830,Roads,Completed,NJ-TEYNAMPET,121,598000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT RAGAVAN THOTTAM 1ST LANE IN DN-121,UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16831,Roads,Completed,NJ-TEYNAMPET,121,564000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT RAJASEKARAN LANE IN DN-121,UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16833,Roads,Completed,NJ-TEYNAMPET,121,335000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT MECCAPURAM 4TH STREET IN DN-121,UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16834,Roads,Completed,NJ-TEYNAMPET,121,1254000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT DWARAGA NAGAR 1 TO 5 STREET IN DN-121,UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2625,Buildings,Completed,NJ-TEYNAMPET,121,255000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED FOR CPS & CUPS AT LLOYDS ROAD IN DIV-121, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2626,Buildings,Completed,NJ-TEYNAMPET,121,217000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED FOR CHS AT V.P.KOIL STREET IN DIV-121, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2627,Buildings,Completed,NJ-TEYNAMPET,121,398000,"ERECTION OF BORE WELL 50M DEPTH WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED FOR CBHSS AT LLOYDS ROAD (OLD BUILDING) IN DIV-121, UNIT-27,ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/3621,Buildings,Completed,NJ-TEYNAMPET,121,1842000,"PROPOSED CONSTRUCTION MICRO COMPOST CENTRE INSIDE OF KRISHNAMPET BURIAL GROUND AT GAJAPATHY MAIN STREET IN DIVISION - 121, UNIT-27, ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/3982,Footpath,Completed,NJ-TEYNAMPET,121,950000,"PAINTING FOR FOOTPATH KERB FOR INDEPENDENCE DAY AT KAMARAJAR SALAI (FROM NAPPIER BRIDGE TO ALL INDIA RADIO) IN DN.114,116,120,121 and 125 UNIT.25,27,ZONE.09",Own Sources,9,2019-20,2019-20 NJ/2019-20/4460,Buildings,Completed,NJ-TEYNAMPET,121,1600000,"PROPOSED CONSTRUCTION OF CYCLE STAND, NEW BORE WELL AND NEW SHED FOR CHENNAI BOYS HIGHER SECONDARY SCHOOL AT AVVAI SHANMUGAM SALAI IN DIVISION.121,UNIT.27,ZONE.09 (MLA FUND)",MLACDS,9,2019-20,2020-21 NJ/2019-20/6122,Storm Water Drain,Completed,NJ-TEYNAMPET,121,2151000,"Desilting and Minor Repair works at various street in Division-121, Unit-27, Zone-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/7104,Buildings,Completed,NJ-TEYNAMPET,121,500000,"SUPPLY AND ERECTION OF GYM EQUIPMENTS FOR GYM AT GANESAPURAM IN DN.121,UNIT.27,ZONE.09(MLA SCHEME 2019-20)",MLACDS,9,2019-20,2019-20 NJ/2019-20/7936,Roads,Completed,NJ-TEYNAMPET,121,690000,"ATTENDING THE PATCH WORK AT VARIOUS STREET AND ROAD IN DN.121 UNIT.27,ZONE.09",Own Sources,9,2019-20,2021-22 BR/2019-20/11156,Roads,Completed,BR-Bus Route Roads,122,1077000,"PROPOSED CONSTRUCTION OF CENTRE MEDIAN AT CHAMIERS ROAD IN DN-122,ZONE-9",Own Sources,9,2019-20,2021-22 L/2019-20/4308,Electrical,Completed,L-Electrical,122,876000,Provision of 6 nos 8mtr post with double arch bracket the Annasalai on and center median from Anna salai L. R .swamy building Jn. to Nandanam Metro Bhavan. in Division 122Zone IX,Own Sources,9,2019-20,2019-20 L/2019-20/8685,Electrical,Completed,L-Electrical,122,15902100,"Replacement of Rusted Post, Short Post, EL Post and Replacement of Underground Cables in div 117 and 122 of Zone - IX.",Grants,9,2019-20,2020-21 NJ/2019-20/10550,Buildings,Completed,NJ-TEYNAMPET,122,1500000,"CONSTRUCTION OF 16TH DAY CEREMONY HALL AT ALAIYAMMAN KOIL STREET(UNDER MLA FUND 2019-2020) IN DN 122,UNIT 26 AND ZONE 9",MLACDS,9,2019-20,2020-21 NJ/2019-20/1255,Parks,Completed,NJ-TEYNAMPET,122,297000,PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY CENTRE AT TURNBULLS ROAD VACANT LAND IN DN 122 UNIT 26 ZONE 9,Own Sources,9,2019-20,2019-20 NJ/2019-20/16113,Parks,Completed,NJ-TEYNAMPET,122,1780000,"Maintenance for Turn Bulls Road park in Div-122,Unit-26, Zone - 9 (per One year)",Own Sources,9,2019-20,2021-22 NJ/2019-20/16349,Roads,Completed,NJ-TEYNAMPET,122,822000,"Improvements to the Existing BT Road at SM Nagar Main Road in Div-122, Unit-26, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/17732,Roads,Completed,NJ-TEYNAMPET,122,2695000,"IMPROVEMENTS TO THE EXISTING B.T.ROAD AT ADYAR GATE CLUB ROAD IN DN-122,UNIT-26,ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/3694,Buildings,Completed,NJ-TEYNAMPET,122,500000,Supplying and Fixing of GYM Materials for GYM Building at Sathiya Moorthy Nagar in Division -122 Unit -26 Zone -9.(Under MLA Fund),MLACDS,9,2019-20,2019-20 NJ/2019-20/3695,Buildings,Completed,NJ-TEYNAMPET,122,500000,Supplying and Fixing of GYM Materials forTurnbulls Road Play Ground GYM Building at Turnbulls Road in Division -122 Unit -26 Zone -9.(Under MLA Fund),MLACDS,9,2019-20,2019-20 NJ/2019-20/4866,Buildings,Completed,NJ-TEYNAMPET,122,200000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO NNMP SHED(CENTRE NO.33603080108) AT K.B.DASAN SALAI( UNDER MLA FUND 2019-2020) IN DN 122,UNIT 26,ZONE 9",MLACDS,9,2019-20,2019-20 NJ/2019-20/4868,Buildings,Completed,NJ-TEYNAMPET,122,500000,"Providing Purified Drinking Water Provision at Nandanam Govt Higher Secoundary School in Div -122, Unit-26, Zone-9 (Under MLA Fund 2019-2020)",MLACDS,9,2019-20,2020-21 NJ/2019-20/6106,Storm Water Drain,Completed,NJ-TEYNAMPET,122,2387000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT VARIOUS STREETS IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2019-20,2020-21 NJ/2019-20/6107,Buildings,Completed,NJ-TEYNAMPET,122,2410000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT VARIOUS STEETS IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7854,Roads,Completed,NJ-TEYNAMPET,122,347000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 122, UNIT-26, ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/8218,Storm Water Drain,Completed,NJ-TEYNAMPET,122,1728000,"IMPLEMENTATION OF RAIN WATER HARVESTING SCHEME AT MARUDHAM COMPLEX (COMMONDO FORCE) FOR THE CREATION OF GREEN CAMPUS AT BOAT CLUB ROAD IN DIV -122,UNIT-26,ZONE-9",Own Sources,9,2019-20,2020-21 BR/2019-20/13587,Road Cut,Completed,BR-Bus Route Roads,123,496000,Restoration of Road cut Made by Bharathi airtel at various bus route roads in zone 9 (Deposit code-57/0451/2018-19),Deposit Works,9,2019-20,2019-20 BR/2019-20/13588,Road Cut,Completed,BR-Bus Route Roads,123,991000,Restoration of Road cut Made by Bharathi airtel at various bus route roads in zone 9 (Deposit code-57/0522/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/13591,Road Cut,Completed,BR-Bus Route Roads,123,528000,Restoration of Road cut Made by Bharathi airtel at various bus route roads in zone 9 (Deposit code-57/1006/2018-19),Deposit Works,9,2019-20,2019-20 BR/2019-20/5078,Roads,Completed,BR-Bus Route Roads,123,1728000,"Partly relaying the road with BC after cold milling by paver finisher at Luz Church Road in Dn- 123,Zone - IX",Grants,9,2019-20,2020-21 NJ/2019-20/11404,Buildings,Completed,NJ-TEYNAMPET,123,127000,"IMPROVEMENTS TO DIVISION OFFICE 123 AT C.P RAMASAMY ROAD IN DN 123,UNIT 25,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/11406,Buildings,Completed,NJ-TEYNAMPET,123,112000,"DRAINAGE AND WATER SUPPLY ARRANGEMENTS TO AMMAUNAVAGAM AT R.A.PURAM 4TH MAIN ROAD IN DN 123,UNIT25,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/11410,Buildings,Completed,NJ-TEYNAMPET,123,90000,"REPAIRS TO THE EXISTING FOOT PATH AT LUZ AVENUE 5TH STREET ON BOTH SIDES IN DN 123,UNIT 25,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/1226,Buildings,Completed,NJ-TEYNAMPET,123,530000,"IMPROVEMENTS TO THE EXISTING COMPOSING YARD AND PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT C.P RAMASAMY ROAD IN DIV-123, UNIT-25, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/14751,Buildings,Completed,NJ-TEYNAMPET,123,168000,"IMPROVEMENTS TO THE EXISTING TOILET BUILDING FOR CHENNAI HIGHER SECONDARY SCHOOL AT BEMANNA GARDEN STREET IN DN 123,UNIT 25,ZONE 9",Own Sources,9,2019-20,2020-21 NJ/2019-20/16347,Roads,Completed,NJ-TEYNAMPET,123,1588000,"IMPROVEMENTS TO THE EXISTING BT ROAD IN ABIRAMAPURAM 1ST STREET DN 123,UNIT 25,ZONE 9",Own Sources,9,2019-20,2020-21 NJ/2019-20/16348,Roads,Completed,NJ-TEYNAMPET,123,2032000,"IMPROVEMENTS TO THE BT ROAD AT ABIRAMAPURAM 3RD STREET IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16350,Roads,Completed,NJ-TEYNAMPET,123,876000,"IMPROVEMENTS TO THE BT ROAD AT BHEEMANNA GARDERN 1ST STREET IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16351,Roads,Completed,NJ-TEYNAMPET,123,332000,"IMPROVEMENTS TO THE BT ROAD AT KENNADY 1ST STREET IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16352,Roads,Completed,NJ-TEYNAMPET,123,388000,"IMPROVEMENTS TO THE BT ROAD AT KENNADY 2ND STREET IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16353,Roads,Completed,NJ-TEYNAMPET,123,527000,"IMPROVEMENTS TO THE BT ROAD AT LUZ AVENUE LANE IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16354,Roads,Completed,NJ-TEYNAMPET,123,858000,"IMPROVEMENTS TO THE BT ROAD AT KAMARAJ STREET IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16355,Roads,Completed,NJ-TEYNAMPET,123,382000,"IMPROVEMENTS TO THE BT ROAD AT ST.MARRYS LANE IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16356,Roads,Completed,NJ-TEYNAMPET,123,1013000,"IMPROVEMENTS TO THE BT ROAD AT VOC STREET IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16357,Roads,Completed,NJ-TEYNAMPET,123,1630000,"IMPROVEMENTS TO THE BT ROAD AT R.A PURAM 1ST CROSS STREET IN DIV - 123, UNIT -25, ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16358,Roads,Completed,NJ-TEYNAMPET,123,2332000,"IMPROVEMENTS TO THE MUNDAGA KANNIYAMMAN KOVIL STREET IN DIV 124,UNIT-24,ZONE -9",Own Sources,9,2019-20,2020-21 NJ/2019-20/16359,Roads,Completed,NJ-TEYNAMPET,123,340000,"IMPROVEMENTS TO THE KALLUKARAN STREET IN DIV 124,UNIT-24,ZONE -9",Own Sources,9,2019-20,2020-21 NJ/2019-20/16360,Roads,Completed,NJ-TEYNAMPET,123,521000,"IMPROVEMENTS TO THE NATTU VEERACHI STREET IN DIV 124,UNIT-24,ZONE -9",Own Sources,9,2019-20,2020-21 NJ/2019-20/16361,Roads,Completed,NJ-TEYNAMPET,123,590000,"IMPROVEMNETS TO THE EXISTING BT ROAD AT NATTU SUBRAYAN STREET (PART) IN DIV 124, UNIT -25,ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16362,Roads,Completed,NJ-TEYNAMPET,123,1178000,"IMPROVEMNETS TO THE EXISTING BT ROAD AT LOGANATHAN COLONY IN DIV 124, UNIT -25,ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16363,Roads,Completed,NJ-TEYNAMPET,123,280000,"IMPROVEMNETS TO THE EXISTING BT ROAD AT MANDAVELI LANE IN DIV 124, UNIT -25,ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16364,Roads,Completed,NJ-TEYNAMPET,123,643000,"IMPROVEMNETS TO THE EXISTING BT ROAD AT VADAGAR SELVA VINAYAGAR KOVIL STREET IN DIV 124, UNIT -25,ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16365,Roads,Completed,NJ-TEYNAMPET,123,273000,"IMPROVEMNETS TO THE EXISTING BT ROAD AT MALLEESWARAN STREET IN DIV 124, UNIT -25,ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16367,Roads,Completed,NJ-TEYNAMPET,123,1944000,"IMPROVEMNETS TO THE EXISTING BT ROAD AT KALVIVARU STREET IN DIV 124, UNIT -25,ZONE -09",Own Sources,9,2019-20,2020-21 NJ/2019-20/16402,Roads,Completed,NJ-TEYNAMPET,123,2464000,"Improvements and laying to the cement concrete road at Appavoo street in Div-114,U-27,Z-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16403,Roads,Completed,NJ-TEYNAMPET,123,2460000,"Improvements and laying to the cement concrete road at Pachaiyappan street in Div-114,U-27,Z-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16817,Roads,Completed,NJ-TEYNAMPET,123,1035000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT ELDAMS 2ND LANE IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16818,Roads,Completed,NJ-TEYNAMPET,123,362000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT SEETHAMMAL LANE IN DN-123,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/17782,Roads,Completed,NJ-TEYNAMPET,123,4023000,"Improvements to the Existing Bituminous Road at R.A.Puram 1st Main Road in Division - 123 Unit - 25 Zone-0 9",Own Sources,9,2019-20,2020-21 NJ/2019-20/17870,Roads,Completed,NJ-TEYNAMPET,123,1177000,Improvements to the Existing Bituminous Road at Bawa Roadin Division - 123 Unit - 25 Zone-09,Own Sources,9,2019-20,2020-21 NJ/2019-20/17871,Buildings,Completed,NJ-TEYNAMPET,123,1773000,Improvements to the Existing Bituminous Road at Prithivi Avenue in Division - 123 Unit - 25 Zone-09,Own Sources,9,2019-20,2020-21 NJ/2019-20/2059,Buildings,Completed,NJ-TEYNAMPET,123,1434000,"PROVIDING WELL RINGS FOR COMPOSIT AT AMMA UNAVAGAM, PARKS, DIVISION OFFICES AND OTHER PLACES IN UNIT-25 (DIVISION-123,124,125 &126), ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2520,Buildings,Completed,NJ-TEYNAMPET,123,351000,"SUPPLYING OF BIO-SHREDDER MACHINE AND WEIGHING MACHINE IN UNIT - 25, ZONE -9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2591,Buildings,Completed,NJ-TEYNAMPET,123,358000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS (2 NOS) AT CPS, THIRUVALLUVAR SALAI (APPADURAI STREET) IN DIVISION-123, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2592,Buildings,Completed,NJ-TEYNAMPET,123,217000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED AT CPS, VANNIYA TEYNAMPET (THIRUVALLUVAR SALAI) IN DIVISION-123, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2594,Buildings,Completed,NJ-TEYNAMPET,123,435000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED AT CHS, VANNIYA TEYNAMPET (ELLDAMS ROAD) IN DIVISION-123, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2595,Buildings,Completed,NJ-TEYNAMPET,123,255000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AT CHSS, ALWARPET (BHEEMANNA GARDEN STREET) AND MOTOR REPLACED AT CMS THIRUVALLUVARPET (ST.MARYS ROAD) IN DIVISION-123, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/2628,Buildings,Completed,NJ-TEYNAMPET,123,200000,Repairs and Improvements to the Anganwadi Centre (No.33603110301) at Luz Avenue (Near Nageswara rao Park) in Division - 123 Unit - 25 Zone -9,Own Sources,9,2019-20,2019-20 NJ/2019-20/2631,Buildings,Completed,NJ-TEYNAMPET,123,200000,Repairs and Improvements to the Anganwadi Centre (No.33603110313) at Vishalatchi Thottam in Division - 123 Unit - 25 Zone -9,Own Sources,9,2019-20,2019-20 NJ/2019-20/4559,Roads,Completed,NJ-TEYNAMPET,123,1966000,"RELAYING OF ROAD AT BEEMANNA GARDEN STREET IN DIVISION-123, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2021-22 NJ/2019-20/5724,Parks,Completed,NJ-TEYNAMPET,123,290000,Community well into ornamental well work at Greater Chennai Corporation Park at R.A Puram 7th Main Road in Division -123 Unit -25 Zone -9,Own Sources,9,2019-20,2019-20 NJ/2019-20/6124,Storm Water Drain,Completed,NJ-TEYNAMPET,123,1403000,"Desilting and minor repair Works at various streets in Division -123, Unit -25, Zone-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6125,Storm Water Drain,Completed,NJ-TEYNAMPET,123,2020000,"Desilting and minor repair Works at various streets in Division -123, Unit -25, Zone-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/7011,Parks,Completed,NJ-TEYNAMPET,123,775000,Park Improvements Works & Community well into ornamental well work at Greater Chennai Corporation Park at De Monte Colony in Division -123 Unit -25 Zone -9,Own Sources,9,2019-20,2019-20 NJ/2019-20/7673,Roads,Completed,NJ-TEYNAMPET,123,302000,"ATTENDING MINOR PATCH WORK WITH WET MIX MACADAM & M 20 CONCRETE AT VARIOUS STREETS IN WARD-123, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2021-22 BR/2019-20/5104,Roads,Completed,BR-Bus Route Roads,124,494000,"Partly relaying the road with BC after cold milling by paver finisher at R.K Mutt Road in Dn- 124, Zone - IX",Grants,9,2019-20,2020-21 D/2019-20/11834,Storm Water Drain,Completed,D-Storm Water Drains,124,1815000,"NAME OF WORK: Construction of Drain with 315 mm HDPE pipe and Inspection chamber along Sollaiappan street in Dn - 124,Zone - IX.",Own Sources,9,2019-20,2020-21 D/2019-20/11835,Storm Water Drain,Completed,D-Storm Water Drains,124,1935000,"NAME OF WORK: Construction of Drain with 315 mm HDPE pipe and Inspection chamber along Abraham street in Dn - 124,Zone - IX.",Own Sources,9,2019-20,2020-21 D/2019-20/11836,Storm Water Drain,Completed,D-Storm Water Drains,124,2080000,"NAME OF WORK: Construction of Drain with 315 mm HDPE pipe and Inspection chamber along Kesavaperumal koil street in Dn - 124,Zone - IX.",Own Sources,9,2019-20,2020-21 L/2019-20/8738,Electrical,Completed,L-Electrical,124,20539300,"Replacement of Rusted Post, Short Post, EL Post in div 124,125 & 126 of Zone - IX.",Grants,9,2019-20,2020-21 NJ/2019-20/10581,Buildings,Completed,NJ-TEYNAMPET,124,312000,Iron Sheet Fencing work for B Canal Road Side at Kalvivaru Street in Division -124 Unit -25 Zone -9,Own Sources,9,2019-20,2020-21 NJ/2019-20/10588,Buildings,Completed,NJ-TEYNAMPET,124,92000,"Repairs and Improvements to Public Convenience Compound wall at RK Mutt Road in Division 124,Unit 25,Zone 09",Own Sources,9,2019-20,2019-20 NJ/2019-20/1228,Buildings,Completed,NJ-TEYNAMPET,124,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT KUTCHERY ROAD IN DIV-124, UNIT-25, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/16292,Buildings,Completed,NJ-TEYNAMPET,124,200000,"PROVIDING WATER SUPPLYING ARRANGEMENTS TO NNMP SHED AT SHANMUGAPURAM (CENTRE NO 33603110327)( UNDER MLA FUND 2019-2020) IN DN 124,UNIT 25,ZONE 9",MLACDS,9,2019-20,2020-21 NJ/2019-20/16804,Roads,Completed,NJ-TEYNAMPET,124,724000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT KUTCHERY LANE IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16805,Roads,Completed,NJ-TEYNAMPET,124,2243000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT KABALEESWARAR KULAKARAI STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16806,Roads,Completed,NJ-TEYNAMPET,124,922000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT SARADHAPURAM 1ST STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16807,Roads,Completed,NJ-TEYNAMPET,124,1418000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT SARADHAPURAM 2ND STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16808,Roads,Completed,NJ-TEYNAMPET,124,1573000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT MADHAVAPERUMAL 2ND LANE IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16809,Roads,Completed,NJ-TEYNAMPET,124,631000,"IMPROVEMENTS TO THE EXISTING B.T.ROAD AT VALLUVATHULA SINGAM STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16810,Roads,Completed,NJ-TEYNAMPET,124,320000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT PATTU NOOLKARAN THOTTAM 1ST STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16811,Roads,Completed,NJ-TEYNAMPET,124,320000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT PATTU NOOLKARAN THOTTAM 2ND STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16812,Roads,Completed,NJ-TEYNAMPET,124,320000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT PATTU NOOLKARAN THOTTAM 3RD STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16813,Roads,Completed,NJ-TEYNAMPET,124,320000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT PATTU NOOLKARAN THOTTAM 4TH STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16814,Roads,Completed,NJ-TEYNAMPET,124,320000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT PATTU NOOLKARAN THOTTAM 5TH STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16815,Roads,Completed,NJ-TEYNAMPET,124,320000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT PATTU NOOLKARAN THOTTAM 6TH STREET IN DN-124,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2599,Buildings,Completed,NJ-TEYNAMPET,124,217000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED AT CPS, SLATTERPURAM IN DIVISION-124, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/3690,Buildings,Completed,NJ-TEYNAMPET,124,500000,Supplying and Fixing of GYM Materials for GYM Building at Pillaiyar Koil Thottam in Division -124 Unit -25 Zone -9.(Under MLA Fund),MLACDS,9,2019-20,2019-20 NJ/2019-20/4401,Buildings,Completed,NJ-TEYNAMPET,124,500000,"Providing Purified Drinking water provision to Chennai Primary School at Slatterpuram, Shanmugam Pillai Street, in Div-124,Unit-25,Zone-9.(MLA FUND)",MLACDS,9,2019-20,2020-21 NJ/2019-20/6129,Storm Water Drain,Completed,NJ-TEYNAMPET,124,2042000,"Desilting and Minor repair works at Various Street in division-124, unit-25, zone-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6130,Storm Water Drain,Completed,NJ-TEYNAMPET,124,488000,"Desilting and Minor repair works at Various Street in division-124, unit-25, zone-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/7827,Roads,Completed,NJ-TEYNAMPET,124,1675000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 124, UNIT-25, ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/9084,Buildings,Completed,NJ-TEYNAMPET,124,408000,Maintenance to shuding machine shed work for Kutchery Road in Division-124 Unit -25 Zone -9,Own Sources,9,2019-20,2019-20 B/2019-20/4165,Buildings,Completed,B-Buildings,125,7645000,"ADDITIONAL CONSTRUCTION OF COMMUNITY HALL AT DOMMINGKUPPAM IN DN-125,ZONE-9.",MLACDS,9,2019-20,2021-22 BR/2019-20/13592,Road Cut,Completed,BR-Bus Route Roads,125,496000,Restoration of Road cut Made by Vodafone at various bus route roads in zone 9 (Deposit code-57/0512/2018-19),Deposit Works,9,2019-20,2019-20 BR/2019-20/5102,Roads,Completed,BR-Bus Route Roads,125,825000,"Partly relaying the road with BC after cold milling by paver finisher at Karneeshwarar Pagoda Street in Dn- 125, Zone - IX",Grants,9,2019-20,2020-21 BR/2019-20/6809,Road Cut,Completed,BR-Bus Route Roads,125,924000,"Restoration of road cut made by CMWSSB at Kamarajar salai in Dn -125 ,Zone - 9",Deposit Works,9,2019-20,2020-21 D/2019-20/4033,Storm Water Drain,Completed,D-Storm Water Drains,125,14190000,"Construction of Missing Link Storm Water Drain along Karaneeswarar Pakoda Road in Dn. 125,Zone - 9,",SMART CITY - SWD,9,2019-20,2020-21 NJ/2019-20/10820,Buildings,Completed,NJ-TEYNAMPET,125,830000,PROPOSED CONSTRUCTION OF GI SHEET SHED FOR SHREEDING MACHINE INSIDE KAILASAPURAM BURIAL GROUND IN DIVISION 125 UNIT 25 ZONE 09,Own Sources,9,2019-20,2020-21 NJ/2019-20/1209,Buildings,Completed,NJ-TEYNAMPET,125,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVER FACILITY IN MYLAPORE BURIAL GROUND @ KAILASAPURAM 5TH STREET IN DN.125, UNIT-25, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/16291,Buildings,Completed,NJ-TEYNAMPET,125,227436,"PROVIDING WATER SUPPLYING ARRANGEMENTS TO NNMP SHED AT PROF.SANJEEVI STREET (CENTRE NO 33603110414) ( UNDER MLA FUND 2019-2020) IN DN 125,UNIT 25,ZONE 9",MLACDS,9,2019-20,2020-21 NJ/2019-20/16368,Roads,Completed,NJ-TEYNAMPET,125,1916000,"Improvements to the Existing BT Road at Appu Street in div-125, Unit-25, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16369,Roads,Completed,NJ-TEYNAMPET,125,131000,"Improvements to the Existing BT Road at Mathala Narayana Lane Div-125, Unit-25, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16390,Roads,Completed,NJ-TEYNAMPET,125,208000,"Improvements to the Existing BT Road at Bazaar Roadt in div-125, Unit-25, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16803,Buildings,Completed,NJ-TEYNAMPET,125,200000,"PROVIDING WATER SUPPLYING ARRANGEMENTS TO NNMP SHED AT POLICE QUARTRES (CENTRE NO 33603110413)( UNDER MLA FUND 2019-2020) IN DN 125,UNIT 25,ZONE 9",MLACDS,9,2019-20,2020-21 NJ/2019-20/16819,Roads,Completed,NJ-TEYNAMPET,125,2726000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT KAILASAPURAM 5TH STREET IN DN-125,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16821,Roads,Completed,NJ-TEYNAMPET,125,473000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT SYED WAHAB HUSSAIN STREET IN DN-125,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16822,Roads,Completed,NJ-TEYNAMPET,125,405000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT SYED NADHI MULLAH STREET IN DN-125,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16823,Roads,Completed,NJ-TEYNAMPET,125,1053000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT MEENAMBALPURAM IN DN-125,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/16824,Roads,Completed,NJ-TEYNAMPET,125,700000,"IMPROVEMENTS TO THE EXISTING C.C.ROAD AT RUTHERPURAM IN DN-125,UNIT-25,ZONE-9.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2602,Buildings,Completed,NJ-TEYNAMPET,125,179000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AT CMS, PROFF.SANJEEVI STREET IN DIVISION-125, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2020-21 NJ/2019-20/2603,Buildings,Completed,NJ-TEYNAMPET,125,255000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACEMED AT CHS, KARANEESWARAR POGADA STREET IN DIVISION-125, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2020-21 NJ/2019-20/3596,Buildings,Completed,NJ-TEYNAMPET,125,1842000,"PROPOSED CONSTRUCTION MICRO COMPOST CENTRE INSIDE OF MYLAPORE BURIAL GROUND IN KAILASAPURAM 5TH STREET IN DN.125, UNIT-25, ZONE-9.",Own Sources,9,2019-20,2019-20 NJ/2019-20/3693,Buildings,Completed,NJ-TEYNAMPET,125,500000,Supplying and Fixing of GYM Materials for GYM Building at Rosary Church Street in Division -125 Unit -25 Zone -9.(Under MLA Fund),MLACDS,9,2019-20,2019-20 NJ/2019-20/4400,Buildings,Completed,NJ-TEYNAMPET,125,500000,"Providing Purified Drinking water provision to Chennai Primary School at Nochikuppam, Kamarajar salai, in Div-125,U-25,Z-9 (Under MLA Fund 2019-20).",MLACDS,9,2019-20,2020-21 NJ/2019-20/4975,Buildings,Completed,NJ-TEYNAMPET,125,200000,"PROVIDING WATER SUPPLYING ARRANGEMENTS TO NNMP SHED AT BAZAAR ROAD(CENTRE NO 33603110412)( UNDER MLA FUND 2019-2020) IN DN 125,UNIT 25,ZONE 9",MLACDS,9,2019-20,2020-21 NJ/2019-20/5653,Buildings,Completed,NJ-TEYNAMPET,125,4450000,"PROPOSED CONSTRUCTION OF ADDITIONAL CLASS ROOM BUILDING IN GROUND FLOOR AT CHEENAI HIGH SCHOOL KARNEEESWARAR PAKODA STREET [UNDER MLA FUND 2019-2020] IN DN 125,UNIT 25,ZONE 9",MLACDS,9,2019-20,2020-21 NJ/2019-20/6097,Storm Water Drain,Completed,NJ-TEYNAMPET,125,955000,"Desilting and minor repair Works at various streets in Division -125, Unit -25, Zone-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/7139,Buildings,Completed,NJ-TEYNAMPET,125,166000,"PROVIDING G.I.SHEET SHED FOR COMPOSED YARD INSIDE MYLAPORE BURIAL GROUND IN DN 125,UNIT 26,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7140,Buildings,Completed,NJ-TEYNAMPET,125,278000,"IMPROVEMENTS TO URBAN PRIMARY HEALTH CENTRE AT APPU STREET IN DN 125,UNIT 25,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7141,Buildings,Completed,NJ-TEYNAMPET,125,123000,"PROVIDING NEW BORE WELL FOR PUBLIC CONVENIANCE AT DR.NATESAN SALAI IN DN 125,UNIT 25,ZONE 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/7825,Roads,Completed,NJ-TEYNAMPET,125,111000,"ATTENDING PATCH WORK AT VARIOUS STREETS IN DIVISION 125, UNIT-25, ZONE-9",Own Sources,9,2019-20,2021-22 BR/2019-20/13593,Road Cut,Completed,BR-Bus Route Roads,126,528000,Restoration of Road cut Made by Reliance Jio at various bus route roads in zone 9 (Deposit code-57/0520/2018-19),Deposit Works,9,2019-20,2020-21 BR/2019-20/4677,Roads,Completed,BR-Bus Route Roads,126,3041000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Devanathan Street in Dn-126 , Zone -IX",Grants,9,2019-20,2020-21 NJ/2019-20/11141,Footpath,Completed,NJ-TEYNAMPET,126,614000,"BLACK AND WHITE PAINTING FOR FOOTPATH KERB AT SANTHOME HIGH ROAD (FROM PATTINAMPAKKAM TO LIGHT HOUSE) IN VIEW OF REPUBLIC DAY 2020 IN DIVISION - 125 AND 126,UNIT - 25, ZONE - 9",Own Sources,9,2019-20,2019-20 NJ/2019-20/1217,Buildings,Completed,NJ-TEYNAMPET,126,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN SRINGERI MUTT ROAD IN DN.126, UNIT-25, ZONE-9",Own Sources,9,2019-20,2019-20 NJ/2019-20/16391,Roads,Completed,NJ-TEYNAMPET,126,582000,"Improvements to the Existing BT Road at Sammantham street in div-126, Unit-25, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16392,Roads,Completed,NJ-TEYNAMPET,126,499000,"Improvements to the Existing BT Road at Thiruvalluvar Pettai Road in div-126, Unit-25, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16393,Roads,Completed,NJ-TEYNAMPET,126,2413000,"Improvements to the Existing BT Road at Jeth Nagar 2nd & 3rd Cross Street in div-126, Unit-25, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/16394,Roads,Completed,NJ-TEYNAMPET,126,1698000,"Improvements to the Existing BT Road at Lazurus Church Road in div-126, Unit-25, Zone -IX",Own Sources,9,2019-20,2020-21 NJ/2019-20/17989,Roads,Completed,NJ-TEYNAMPET,126,385000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT LEITH CASTLE 1ST CROSS STREET IN DIV-126, UNIT-25, ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/17990,Roads,Completed,NJ-TEYNAMPET,126,1396000,"IMPROVEMENT TO THE INTERIOR BT ROAD AT LEITH CASTLE CENTRE STREET IN DIV-126, UNIT-25, ZONE-9",Own Sources,9,2019-20,2020-21 NJ/2019-20/18110,Buildings,Completed,NJ-TEYNAMPET,126,500000,"ATTENDING EMERGENCY MINOR REPAIR WORKS AT COMPOST YARD SHED IN DIV-126, UNIT - 25, ZONE -9",Own Sources,9,2019-20,2020-21 NJ/2019-20/2606,Buildings,Completed,NJ-TEYNAMPET,126,255000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AND MOTOR REPLACED AT CHS, CANAL BANK ROAD IN DIVISION-126, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2020-21 NJ/2019-20/4535,Buildings,Completed,NJ-TEYNAMPET,126,500000,"Providing Purified Drinking water provision to Chennai Middle School at Santhome 4th link Road in Div-126, U-25, Z-9. (Under MLA Fund 2019-20)",MLACDS,9,2019-20,2020-21 NJ/2019-20/5834,Buildings,Completed,NJ-TEYNAMPET,126,430000,"ARRANGEMENTS TO SCAFFOLDING AND BARRICADES FOR IMMERSION OF VINAYAGAR STATUE AT LOOP ROAD BEACH IN DIV-126,UNIT-25,ZONE-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/6113,Storm Water Drain,Completed,NJ-TEYNAMPET,126,1525000,"Desilting and minor repair Works at various streets in Division -126, Unit -25, Zone-09.",Own Sources,9,2019-20,2019-20 NJ/2019-20/7121,Buildings,Completed,NJ-TEYNAMPET,126,500000,Supplying and Fixing of GYM Materials for GYM Building at Santhome high road amma unavagam near in Division -126 Unit -25 Zone -9.(Under MLA Fund),MLACDS,9,2019-20,2019-20 NJ/2019-20/7811,Roads,Completed,NJ-TEYNAMPET,126,108000,"ATTENDING MINOR PATCH WORK WITH WET MIX MACADAM & M 20 CONCRETE AT VARIOUS STREETS IN WARD-126, UNIT-25, ZONE-09.",Own Sources,9,2019-20,2021-22 BR/2019-20/10299,Roads,Completed,BR-Bus Route Roads,127,810000,"Improvements to the existing centre median,footpath kerb at kaliamman Koil Street in view if VVIP Visit in Dn-127, Zone-X",Own Sources,10,2019-20,2020-21 BR/2019-20/10300,Roads,Completed,BR-Bus Route Roads,127,825000,"Providing and Laying of Hot applied Thermoplastic paint, Studs ,Delineator and Median marker at kaliamman Koil Street,Sterling road and Nelson manickam road in view of VVIP Visit in Zone- 8,9 &10",Own Sources,10,2019-20,2020-21 BR/2019-20/13594,Road Cut,Completed,BR-Bus Route Roads,127,496000,Restoration of Road cut Made by ACT at various bus route roads in zone 9 (Deposit code-57/0649/2018-19),Deposit Works,10,2019-20,2020-21 BR/2019-20/7007,Road Cut,Completed,BR-Bus Route Roads,127,1810000,"Restoration of road cut made by TANTRANCO at Kaliamman Kovil street(from the Jn of E road to the Jn of 200 ft road) in Dn -127 ,Zone - 10",Deposit Works,10,2019-20,2020-21 D/2019-20/5503,Storm Water Drain,Completed,D-Storm Water Drains,127,601000,"Construction of Cast - in - Situ, Silt Catch pit of inner size 450 x 450 x 450 mm including fixing ductile iron Grating hinged with frame clear opening 450 x 450 mm - 25 MT capacity, completing the finishing work etc,.along Kaliamman koil street Eastern side in Division - 127, Zone -10.",Own Sources,10,2019-20,2019-20 D/2019-20/5504,Storm Water Drain,Completed,D-Storm Water Drains,127,751000,"Construction of Cast - in - Situ, Silt Catch pit of inner size 450 x 450 x 450 mm including fixing ductile iron Grating hinged with frame clear opening 450 x 450 mm - 25 MT capacity, completing the finishing work etc,.along Kaliamman koil street Western side in Division - 127, Zone -10.",Own Sources,10,2019-20,2019-20 L/2019-20/8753,Electrical,Completed,L-Electrical,127,2558600,Replacement of 5250 mtrs of 2x25 sq mm Alu cable at various location in Division 127 & 128 under Zone-10,Grants,10,2019-20,2020-21 L/2019-20/8756,Electrical,Completed,L-Electrical,127,4937500,Replacement of 7 mtr street lamp post with one mtr straight bracket 153 nos and 5049 mtrs of 2 X 25 sqmm alu cable at Various locations in Division 127 and 128 under Zone-10,Grants,10,2019-20,2020-21 NK/2019-20/0584,Buildings,Completed,NK-KODAMBAKKAM,127,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School street in Division-127, Unit-29, Zone-10 (for 38 days from 01-6-2019 to 15-7-2019.)",Own Sources,10,2019-20,2020-21 NK/2019-20/0589,Buildings,Completed,NK-KODAMBAKKAM,127,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School street in Division-127, Unit-29, Zone-10 (for 38 days from 01-6-2019 to 15-7-2019.)",Own Sources,10,2019-20,2020-21 NK/2019-20/0591,Buildings,Completed,NK-KODAMBAKKAM,127,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Arumbakkam, Division-127, Unit-29, Zone-10 (for 38 days from 01-6-2019 to 15-7-2019.)",Own Sources,10,2019-20,2020-21 NK/2019-20/0853,Buildings,Completed,NK-KODAMBAKKAM,127,231000,"Construction of new composting yard at saf games village in div-127, unit-29, zone-10",Own Sources,10,2019-20,2019-20 NK/2019-20/11124,Parks,Completed,NK-KODAMBAKKAM,127,1270000,"Improvement to the tennis Court and pc at SAF Games Village in Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11365,Roads,Completed,NK-KODAMBAKKAM,127,490000,Attending patch work using cement concrete at various street in Dn-127 U-29 Z-10,Own Sources,10,2019-20,2019-20 NK/2019-20/13698,Roads,Completed,NK-KODAMBAKKAM,127,995000,"Providing and laying thermoplastic paint and fixing reflective stud at Nerkundram road, Natesan Nagar 1st main road , Natesn Nagar 2nd main road, in Div-127, Unit-29, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13701,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Providing and laying thermoplastic paint and fixing reflective stud at West Natesn Nagar , Natesan Nagar 1st Cross Street,& Ramalingam Nagar 2nd street, in Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13715,Roads,Completed,NK-KODAMBAKKAM,127,990000,"Providing and laying thermoplastic paint and fixing reflective stud at Natesan Nagar 3rd main road, Natesan Nagar 4th main road , Natesan Nagar 5th main road, in Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13732,Roads,Completed,NK-KODAMBAKKAM,127,650000,"Providing and laying Thermoplastic paint and fixing reflective stud at Natesan Nagar 5th cross street ,Natesan Nagar 6th cross street,Ramalingam Nagar 1st street ,Chithirai street ,Masi street, in Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/15584,Buildings,Completed,NK-KODAMBAKKAM,127,236000,"Providing Out Sourcing Private Labours for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at School street in Div-127, Unit-29,Zone-10 (from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/15591,Buildings,Completed,NK-KODAMBAKKAM,127,236000,"Providing Private Laboures for Sweeping and Toilet cleaning work at Chennai Middle School at Arumbakkam in Div-127, Unit-29,Zone-10 (from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/15593,Buildings,Completed,NK-KODAMBAKKAM,127,236000,"Providing Out Sourcing Private Laboures for Sweeping and Toilet cleaning work at Chennai Primary School at School street in Div-127, Unit-29,Zone-10 (from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/1562,Parks,Completed,NK-KODAMBAKKAM,127,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT SAF GAMES VILLAGE IN DN-127, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/15861,Roads,Completed,NK-KODAMBAKKAM,127,500000,ATTENDING PATCH WORK USING CEMENT CONCRETE WORK AT VARIOUS STREET IN DN 127 U-29 Z-10,Own Sources,10,2019-20,2020-21 NK/2019-20/1646,Parks,Completed,NK-KODAMBAKKAM,127,198000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-127,UNIT-29,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2420,Buildings,Completed,NK-KODAMBAKKAM,127,205000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at School street in Division-127, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2421,Buildings,Completed,NK-KODAMBAKKAM,127,205000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School street in Division-127, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2422,Buildings,Completed,NK-KODAMBAKKAM,127,205000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Arumbakkam, Division-127, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2556,Grade Separator,Completed,NK-KODAMBAKKAM,127,160000,"Repair and maintenance of ICDS Centre at School street, Koyambedu in div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2829,Roads,Completed,NK-KODAMBAKKAM,127,218000,"Forming Of Name Plaque, Granite Fixing And Other Improvement At Road Island At The Entrance Of AIS Quarters At West Natesan Nagar Street In Div-127, Unit-29, Zone-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3089,Buildings,Completed,NK-KODAMBAKKAM,127,376000,"Bore Well and Water Supply arrangements at Supply arrangements at CHS School , School street in div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/3091,Buildings,Completed,NK-KODAMBAKKAM,127,376000,"Providing bore well and water aragnements at CMS School, Arumbakkam in Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/3194,Buildings,Completed,NK-KODAMBAKKAM,127,588000,"Providing Bore well water supply and electrical arrangements and other improvement to Existing E-Toilet at Kalliamman Koil street near koyembedu bus stand in div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/3595,Buildings,Completed,NK-KODAMBAKKAM,127,439000,"Proposed Construction of Micro Compost Centre at New colony Burial Ground in Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4670,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,1200000,"Desilting work and minor repair works to the existing Strom Water Drains at Jai Nagar, TSD Nagar, Kaliamman Koil Street and Various street In Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4810,Footpath,Completed,NK-KODAMBAKKAM,127,990000,"Improvement to SWD and Construction of silt catch pit at Natesan nagar in div-127, unit-29, zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/4990,Roads,Completed,NK-KODAMBAKKAM,127,976000,"Forming footpath at SAFGV A Block in Dn. 127, Unit 29, Zone 10",Own Sources,10,2019-20,2020-21 NK/2019-20/5527,Roads,Completed,NK-KODAMBAKKAM,127,860000,Widening of the road using cement concrete at west natesan nagar (Natesan nagar 2nd main road JN to Natesan nagar 3rd main road JN ) in Dn -127 U-29 Z-10,Own Sources,10,2019-20,2020-21 NK/2019-20/5528,Roads,Completed,NK-KODAMBAKKAM,127,710000,Widening of the road using cement concrete and Providing and fixing plastic speed breaker at west nataesan nagar (Natesan nagar 3rd main road JN to canal ) in Dn -127 U-29 Z-10,Own Sources,10,2019-20,2020-21 NK/2019-20/5530,Roads,Completed,NK-KODAMBAKKAM,127,280000,Providing and laying of hot applied thermoplastic paint at West natesan nagar in Dn127 U-29 Z-10,Own Sources,10,2019-20,2020-21 NK/2019-20/7295,Buildings,Completed,NK-KODAMBAKKAM,127,683000,"Providing Security Arrangements and Engaging private labourers for UPHC , Natesan Nagar 5th main road (12 Months) in Division - 127, Unit - 29, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/8636,Roads,Completed,NK-KODAMBAKKAM,127,886000,"ATTENDING EMERGENCY CEMENT CONCRETE PATCH WORK AT NATESAN NAGAR 3RD MAIN ROAD IN DIV-127,U-29,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/8637,Roads,Completed,NK-KODAMBAKKAM,127,1109000,"Attending Emergency Patch work at Sayee Nagar 8th Street , Jakkammal street, Valluvar Salai and Various streets in Div-127,Unit-29,Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/9486,Buildings,Completed,NK-KODAMBAKKAM,127,570000,"Improvement of amma unavagam at Semmathamman Nagar sector 3 in Div-127, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 P/2019-20/11184,Parks,Completed,P-Parks and Playfields,127,2420000,"FORMATION OF NEW PARK AT SAF VILLAGE A3 BLOCK IN DIIVISION - 127, ZONE - 10.",Own Sources,10,2019-20,2020-21 P/2019-20/11190,Parks,Completed,P-Parks and Playfields,127,2480000,"FORMATION OF NEW PARK AT SAF VILLAGE Z BLOCK IN DIVISION - 127, ZONE - 10.",Own Sources,10,2019-20,2020-21 BR/2019-20/7125,Roads,Completed,BR-Bus Route Roads,128,1580000,"Restoration of Roadcut made by TANGEDCO at Arcot Road From The Junction of Alwarthirunagar 1st Main Road to the Junction of AVM Avenue Main road in Dn-128,zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/0012,Buildings,Completed,NK-KODAMBAKKAM,128,150000,"OPERATION AND MAINTENANCE OF ELECTRICAL CREMATORIUM AT THANGAL ERIKKARAI STREET, VIRUGAMBAKKAM IN DIVISION -128,UNIT - 29, ZONE- 10 ( From 23.03.2019 to 30.06.2019)",Own Sources,10,2019-20,2019-20 NK/2019-20/0626,Buildings,Completed,NK-KODAMBAKKAM,128,59000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at School Street, Virugambakkam in Division-128, Unit-29, Zone-10 (for 38 days from 01-6-2019 to 15-7-2019.)",Own Sources,10,2019-20,2020-21 NK/2019-20/0627,Buildings,Completed,NK-KODAMBAKKAM,128,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School Street, Virugambakkam in Division-128, Unit-29, Zone-10 (for 38 days from 01-6-2019 to 15-7-2019.)",Own Sources,10,2019-20,2020-21 NK/2019-20/0628,Buildings,Completed,NK-KODAMBAKKAM,128,59000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Pillaiyar Koil Street, Nesapakkam in Division-128, Unit-29, Zone-10 (for 38 days from 01-6-2019 to 15-7-2019).",Own Sources,10,2019-20,2020-21 NK/2019-20/0715,Buildings,Completed,NK-KODAMBAKKAM,128,89000,"Providing private Labourers for Sweeping and Toilet cleaning work at Jaigopal Garodia Government Girls Higher Secondary School, Kamarajar Salai, Virugambakkam in Div-128, Unit-31, Zone-10.( for 38 days from 01-6-2019 to 15-7-2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0716,Buildings,Completed,NK-KODAMBAKKAM,128,44000,"Providing private Labourers for Sweeping and Toilet cleaning work at Adi Diravida High School in Kaliamman Koil Street, Virugambakkm in Div-128, Unit-29, Zone-10 ( for 38 days from 01-6-2019 to 15-7-2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/10592,Buildings,Completed,NK-KODAMBAKKAM,128,1960000,"Improvements to Virugambakkam Burial Ground at Thangal Erikkarai Street in Division-128, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11047,Buildings,Completed,NK-KODAMBAKKAM,128,990000,"PROPOSED CONSTRUCTION OF YOGA STAGE AT KRISHNA NAGAR PLAY FIELD IN DIVISION-128, UNIT-29, ZONE-10.( UNDER MLA FUND WORK )",MLACDS,10,2019-20,2020-21 NK/2019-20/13687,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,2180000,"Construction of storm water drain of size 900 x 900mm RCC box type drain along Sheik Abdhullah Nagar 1st Main Road from Lakshmi Nagar 1st street to Periyar Nagar in Division-128, Unit-29, Zone-10.( under MLA scheme work )",MLACDS,10,2019-20,2020-21 NK/2019-20/15586,Buildings,Completed,NK-KODAMBAKKAM,128,630000,"Providing private Labourers for sweeping and Toilet cleaning work at Adi Diravida High School in Kaliamman Koil Street, Virugambakkam in Division-128, Unit-29, Zone-10.( From 01.06.2020 to 30.04.2021) & 275 days.",Own Sources,10,2019-20,2021-22 NK/2019-20/15588,Buildings,Completed,NK-KODAMBAKKAM,128,470000,"Providing private Labourers for sweeping and Toilet cleaning work at Chennai Higher Secondary School in School Street, Virugambakkam in Division-128, Unit-29, Zone-10.( From 01.06.2020 to 30.04.2021) & 275 days.",Own Sources,10,2019-20,2021-22 NK/2019-20/15589,Buildings,Completed,NK-KODAMBAKKAM,128,235000,"Providing private Labourers for sweeping and Toilet cleaning work at Chennai Primary School in School Street, Virugambakkam in Division-128, Unit-29, Zone-10. (From 01.06.2020 to 30.04.2021) & 275 days.",Own Sources,10,2019-20,2021-22 NK/2019-20/15590,Buildings,Completed,NK-KODAMBAKKAM,128,470000,"Providing private Labourers for sweeping and Toilet cleaning work at Chennai Primary School in Pillaiyar Koil Street, Nesapakkam in Division-128, Unit-29, Zone-10.( From 01.06.2020 to 30.04.2021) & 275 days.",Own Sources,10,2019-20,2021-22 NK/2019-20/15592,Buildings,Completed,NK-KODAMBAKKAM,128,990000,"Providing private Labourers for sweeping and Toilet cleaning work at Jaigopal Garodia Government Girls Higher Secondary School, Kamarajar Salai in Division-128, Unit-29, Zone-10.( From 01.06.2020 to 30.04.2021) & 275 days.",Own Sources,10,2019-20,2021-22 NK/2019-20/1569,Parks,Completed,NK-KODAMBAKKAM,128,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT VIRUGAMBAKKAM BURIAL GROUND IN DN-128, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/15860,Roads,Completed,NK-KODAMBAKKAM,128,564000,"ATTENDING PATCH WORK AT RUKMANI STREET, SRINIVASAN STREET, BALAMMAL STREET AND VARIOUS STREET IN DIV-128, UNIT-29, ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/1642,Parks,Completed,NK-KODAMBAKKAM,128,125000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-128,UNIT-29,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/1656,Roads,Completed,NK-KODAMBAKKAM,128,560000,"IMPROVEMENT WORK TO THE CENTER MEDIAN AT ARCOT ROAD IN DN-128, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/2011,Buildings,Completed,NK-KODAMBAKKAM,128,439000,"IMPROVEMENT WORK FOR MCC UNIT AND RRC UNIT AT VIRUGAMBAKKAM BURIAL GROUND IN DIV-128,U-29,Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/2245,Buildings,Completed,NK-KODAMBAKKAM,128,865000,"Providing private Labourers for Sweeping and Toilet cleaning work at Jayagopal Carodia School,(Government Girls Hr.Sec.School) Virugambakkm in Div-128, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2247,Buildings,Completed,NK-KODAMBAKKAM,128,411000,"Providing private Labourers for Sweeping and Toilet cleaning work at CPS School pillayar koil street , Virugambakkm in Div-128, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2249,Buildings,Completed,NK-KODAMBAKKAM,128,556000,"Providing private Labourers for Sweeping and Toilet cleaning work at Adi Diravida High School in Kaliamman Koil Street, Virugambakkm in Div-128, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2253,Buildings,Completed,NK-KODAMBAKKAM,128,411000,"Providing private Labourers for Sweeping and Toilet cleaning work at Chennai higher secondary school , School street Virugambakkm in Div-128, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2257,Buildings,Completed,NK-KODAMBAKKAM,128,205000,"Providing private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School , School street Virugambakkm in Div-128, Unit-29, Zone-10 (FROM 16.07.2019 TO 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2307,Buildings,Completed,NK-KODAMBAKKAM,128,485000,"OPERATION AND MAINTENANCE OF ELECTRICAL CREMATORIUM AT ERRIKKARAI STREET, VIRUGAMBAKKAM IN DIVISION -128,UNIT - 29, ZONE- 10 (01.07.2019 TO 30.03.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2584,Buildings,Completed,NK-KODAMBAKKAM,128,408000,"ERECTION OF BORE WELL WITH WATER SUPPLY ARRANGEMENTS AT CHENNAI HIGHER SECONDARY SCHOOL, SCHOOL STREET, VIRUGAMBAKKAM IN DIV-128, UNIT-29, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2622,Buildings,Completed,NK-KODAMBAKKAM,128,376000,"Providing Bore Well and Water supply arrengements at CPS School at Nesappakam in div-128, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3590,Buildings,Completed,NK-KODAMBAKKAM,128,439000,"Proposed Construction of Micro Compost Centre at Virugambakkam Burial Ground in div-128, unit-29, zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4483,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,1035000,"Attending minor repair and desilting to existing storm water drain at Avm Avenue 1st main Road( from Arcot road- chainage140 m to 300m) in Division-128, Unit-29, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4671,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,900000,"Attending minor repair and De-silting to existing storm water drain at Avm Avenue 1st main Road( from Arcot road - chainage 0m to 140m) in Division-128, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/5943,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,900000,"Desilting work and minor repair works to the existing Strom Water Drains at Burial Ground Inside Road , Avm Avenue 4th street and Various street in div-128, unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/6747,Buildings,Completed,NK-KODAMBAKKAM,128,180000,"Improvements to Compacter Bin Platform at Thangal Erikkarai Street near Virugambakkam Burial Ground in Division-128, Unit-29, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/6986,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,800000,"Desilting work and minor repair works to the existing Strom Water Drain at Kamarajar salai and Various street in div-128, unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7275,Buildings,Completed,NK-KODAMBAKKAM,128,550000,":Providing Security Arrangements and Engaging private labourers for UPHC , Virugambakkam at Kamarajar salai (12 Months) in Division - 128, Unit - 29, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/8186,Parks,Completed,NK-KODAMBAKKAM,128,320000,"IMPROVEMENTS TO PARK AT NEW COLONY 5TH STREET IN DIVISION-128, UNIT-29, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/8958,Buildings,Completed,NK-KODAMBAKKAM,128,370000,"CONSTRUCTION OF STAGE AT INSIDE THE CHENNAI HIGHER SECONDARY SCHOOL, SCHOOL STREET, VIRUGAMBAKKAM IN DIVISION-128, UNIT-29, ZONE-10 ( Under M. L. A. fund)",MLACDS,10,2019-20,2020-21 NK/2019-20/9491,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,495000,"IMPROVEMENTS AND REPAIRS TO EXISTING STORM WATER DRAIN AT A.V.M AVENUE 1ST MAIN ROAD (CHAINAGE 300M TO 357M) IN DIVISION-128, UNIT-29, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/9865,Buildings,Completed,NK-KODAMBAKKAM,128,690000,"IMPROVEMENTS TO SCHOOL BUILDING AT CHENNAI HIGHER SECONDARY SCHOOL , SCHOOL STREET, VIRUGAMBAKKAM IN DIVISION-128, UNIT-29, ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/9878,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,2200000,"Construction of Storm Water Drain of size 600 x 750mm along Thangal Ulvail street from Ottaipillaiyar Koil Street to Narayanasamy Street in Division-128, Unit-29, Zone-10. (Under MLA FUND work)",MLACDS,10,2019-20,2020-21 BR/2019-20/14587,Road Cut,Completed,BR-Bus Route Roads,129,991000,"Restoration of Road cut Made by M/s Bharathi Airtel in varioud bus route roads in,Zone -10(Depsite code -57/0520/2018-19)",Deposit Works,10,2019-20,2020-21 BR/2019-20/4755,Roads,Completed,BR-Bus Route Roads,129,7545000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at NSK Salai(from 100 feet road to 80 feet road) in Dn-129 &130 , Zone - X",Grants,10,2019-20,2020-21 BR/2019-20/5186,Roads,Completed,BR-Bus Route Roads,129,988000,"Partly relaying the road with BC after cold milling by paver finisher at KK Salai in Dn- 129, Zone - X",Grants,10,2019-20,2020-21 NK/2019-20/10744,Parks,Completed,NK-KODAMBAKKAM,129,248000,"Repair and imporvement of existing Fountain at Pillayar Koil park , in div-129, unit-29, zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10923,Parks,Completed,NK-KODAMBAKKAM,129,721000,"Improvements of Baskar colony park at vivekanandar street in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11780,Roads,Completed,NK-KODAMBAKKAM,129,1302000,"Improvement to Bituminous Concrete road at V.P. Akilan Street in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11781,Roads,Completed,NK-KODAMBAKKAM,129,1878000,"Improvement to Bituminous concrete road at kamaraj Street M.A nagar in div-129, Unit-29, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11784,Roads,Completed,NK-KODAMBAKKAM,129,280000,"Relaying of road using Bituminous concrete at Kumaran Colony 5th street in div-129, Unit-29, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11785,Roads,Completed,NK-KODAMBAKKAM,129,659000,"Relaying of road using Bituminous concrete at Venkatesa Nagar 1st street extn in div-129, Unit-29, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12569,Parks,Completed,NK-KODAMBAKKAM,129,580000,"Improvement of Parameshwaran wihar , Muthukumarappa and Jain Swarnakamal Park and Playfields at Arcot road in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13827,Roads,Completed,NK-KODAMBAKKAM,129,497000,"Improvement to Bituminous Concrete road at Mullai street, Gandhi Nagar in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13828,Roads,Completed,NK-KODAMBAKKAM,129,857000,"Improvement to Bituminous Concrete Road at VGN street in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13829,Roads,Completed,NK-KODAMBAKKAM,129,639000,"Improvement to Bituminous Concrete road at sathyamoorthy street devaraj nagar in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/14427,Roads,Completed,NK-KODAMBAKKAM,129,2470000,"Providing M30 Concrete and Silt Catch Pit in Between Compound Wall and Strom Water Drain at Abusali Street (Eastern Side) From Arcot Road to Durai Arasan Street in Div-129, Unit-29, Zone-10",Own Sources,10,2019-20,2021-22 NK/2019-20/14502,Roads,Completed,NK-KODAMBAKKAM,129,496000,"Repair and maintenance work at various locations in div-129, Unit -29, zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/15990,Roads,Completed,NK-KODAMBAKKAM,129,4737000,"Improvement to bituminous concrete road at abusali street in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/15993,Roads,Completed,NK-KODAMBAKKAM,129,530000,"Improvement to Bituminous Concrete Road at V.V.Koil street, Gandhi Nagar in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/1606,Roads,Completed,NK-KODAMBAKKAM,129,280000,"IMPROVEMENT WORK TO THE CENTER MEDIAN AT ARCOT ROAD IN DN-129, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/1637,Parks,Completed,NK-KODAMBAKKAM,129,287000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-129,UNIT-29,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4502,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,935000,"Desilting & Minor Repair works at Existing Storm Water Drain at Arcot Road, Arunachalam Road, S.B.I Colony 2nd street and Kumaran Colony 4th street in Div-129, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/4860,Buildings,Completed,NK-KODAMBAKKAM,129,154000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT DIVISION OFFICE IN DIV-129, U-28, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/4861,Buildings,Completed,NK-KODAMBAKKAM,129,154000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT Dr. AMBEDKAR NAGAR ICDS CENTRE OFFICE IN DIV-129, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/6506,Parks,Completed,NK-KODAMBAKKAM,129,812000,"MAINTENANCE ESTIMATE FOR PARK AT Arcot road(Appaswamy) IN DN129, U29, ZONE-10 (Area-2300M2)",Own Sources,10,2019-20,2020-21 NK/2019-20/6507,Parks,Completed,NK-KODAMBAKKAM,129,810000,"MAINTENANCE ESTIMATE FOR PARK AT Baskar Colony IN DN129, U29, ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/6509,Parks,Completed,NK-KODAMBAKKAM,129,698000,"MAINTENANCE ESTIMATE FOR KUMARAN COLONY 4TH STREET PARK AT IN SALIGRAMAM, DN129, U29, ZONE-10 (Area-1736M2)",Own Sources,10,2019-20,2020-21 NK/2019-20/6510,Parks,Completed,NK-KODAMBAKKAM,129,231000,"MAINTENANCE ESTIMATE FOR PARK AT NAVALAR PARK IN DN129, U29, ZONE-10 (Area-360M2)",Own Sources,10,2019-20,2020-21 NK/2019-20/6511,Parks,Completed,NK-KODAMBAKKAM,129,579000,"MAINTENANCE ESTIMATE FOR PARK AT PILLAYAR KOIL PARK IN DN129, U29, ZONE-10 (Area-960M2)",Own Sources,10,2019-20,2020-21 NK/2019-20/6512,Parks,Completed,NK-KODAMBAKKAM,129,831000,"MAINTENANCE ESTIMATE FOR PARK AT ABUSALI ROAD PARK IN DN129, U29, ZONE-10 (Area-2540M2)",Own Sources,10,2019-20,2020-21 NK/2019-20/6872,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,1460000,"Desilting & Minor Repair works at Existing Storm Water Drain at Sri Ramulu Street, Baskar Colony, Logaiah Colony 1st cross street, logaiah colony 1st main road and various street in Div-129, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/6873,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,821000,"Desilting & Minor Repair works at Existing Storm Water Drain at Kumaran colony 5th street, Kumaran Colony 6th street, Natarajan Street and Various street in Div-129, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7286,Buildings,Completed,NK-KODAMBAKKAM,129,555000,"Providing Security Arrangements and Engaging private labourers for UPHC at Dasarathapuram 8th Street (12 Months) in Division - 129, Unit - 29, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/7731,Roads,Completed,NK-KODAMBAKKAM,129,999000,"Restoration of Road Cut made by CMWSSB at Abusali street (From Kannammal street chainage 0m - 513m ) in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7732,Roads,Completed,NK-KODAMBAKKAM,129,493000,"Restoration of Road Cut made by CMWSSB at Kamaraj street in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7733,Roads,Completed,NK-KODAMBAKKAM,129,343000,"Restoration of Road Cut made by CMWSSB at V.P Akilan street in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7734,Road Cut,Completed,NK-KODAMBAKKAM,129,444000,"Restoration of Road Cut made by CMWSSB at Dhasarathapuram main road in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7735,Road Cut,Completed,NK-KODAMBAKKAM,129,221000,"Restoration of Road Cut made by CMWSSB at Dhasarathapuram 2nd street in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7736,Road Cut,Completed,NK-KODAMBAKKAM,129,256000,"Restoration of Road Cut made by CMWSSB at Devaraj Nagar main road in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7738,Road Cut,Completed,NK-KODAMBAKKAM,129,51000,"Restoration of Road Cut made by CMWSSB at Kambar street in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7741,Road Cut,Completed,NK-KODAMBAKKAM,129,126000,"Restoration of Road Cut made by CMWSSB at Mullai street in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7742,Road Cut,Completed,NK-KODAMBAKKAM,129,197000,"Restoration of Road Cut made by CMWSSB at V.V koil street in div-129 , Unit-29, Zone-10",Deposit Works,10,2019-20,2020-21 NK/2019-20/7745,Roads,Completed,NK-KODAMBAKKAM,129,787000,"Improvement to Bituminous Concrete Road at Dhasarathapuram 2nd street In Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7749,Roads,Completed,NK-KODAMBAKKAM,129,530000,"Improvement to Bituminous Concrete Road at Sasthri 2nd cross street in Div-129, Unit-29,Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7750,Roads,Completed,NK-KODAMBAKKAM,129,1096000,"Improvement to Bituminous Concrete Road at Devaraj Nagar Main Road in Div-129, Unit-29, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7751,Roads,Completed,NK-KODAMBAKKAM,129,1847000,"Improvement to Bituminous Concrete Road at Dhasarathapuram main Road in Div-129, Unit-29,Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/8559,Roads,Completed,NK-KODAMBAKKAM,129,497000,"Repair and maintenance work at various locations in div-129, Unit -29, zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/8638,Roads,Completed,NK-KODAMBAKKAM,129,1029000,"ATTENDING PATCH WORK AT KAVERI STREET, L.V PRASAD ROAD, BASKAR COLONY DHASARATHAN STREET AND VARIOUS STREET IN DIV-129, UNIT-29, ZONE-10.",Own Sources,10,2019-20,2021-22 L/2019-20/8778,Electrical,Completed,L-Electrical,130,2917400,Replacement of 6082mtrs of 2x25 sq mm cable at various location in Division 130 & 134 under Zone-10,Grants,10,2019-20,2020-21 NK/2019-20/0833,Buildings,Completed,NK-KODAMBAKKAM,130,59000,"Providing Private Labourers for sweeping and Toilet cleaning work at Chennai Middle School at Amman Kovil Street East Vadapalani in Division-130, Unit-29, Zone-X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/10793,Buildings,Completed,NK-KODAMBAKKAM,130,333000,"Maintanance works to the Anganvadi at Rajanga Madya Street and Amman koil Street in Division - 130, Unit - 29, Zone - 10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11592,Roads,Completed,NK-KODAMBAKKAM,130,2154000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT AT OTHAVADAI STREET IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12405,Roads,Completed,NK-KODAMBAKKAM,130,1595000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT NERKUNDRAM PATHAI (EAST) IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12412,Roads,Completed,NK-KODAMBAKKAM,130,454000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT MEIGAI VINAYAGAR KOIL STREET IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12414,Roads,Completed,NK-KODAMBAKKAM,130,561000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT ALAGARPERUMAL KOIL 1ST STREET IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12415,Roads,Completed,NK-KODAMBAKKAM,130,380000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT NGO COLONY 1ST STREET (PART) IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12416,Roads,Completed,NK-KODAMBAKKAM,130,857000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT KARUNEEGAR STREET IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12417,Roads,Completed,NK-KODAMBAKKAM,130,821000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT PILLAYAR KOIL STREET IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12418,Roads,Completed,NK-KODAMBAKKAM,130,341000,"RELAYING OF ROAD USING BITUMINOUS CONCRETE AT AT DHARAN SINGH COLONY 2ND STREET IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12539,Buildings,Completed,NK-KODAMBAKKAM,130,556000,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV Filter) of 2000 Litres Hours Capacity for 7 months Period (from 17.02.2020 to 16.09.2020) at N.G.O Colony Main Road in DIVISION -130, UNIT-29, ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/14205,Buildings,Completed,NK-KODAMBAKKAM,130,480000,"Maintanence works to the E-Toilet, Amma Unavagam and Public Convenience at Nerkundram Pathai, Alagiri Nagar Main Road and West Sivan Koil Street in Division - 130, Unit - 29, Zone - 10.",Own Sources,10,2019-20,2019-20 NK/2019-20/14749,Footpath,Completed,NK-KODAMBAKKAM,130,328000,"Maintanance and repair works to the footpath at Arcot Road in Division - 130, Unit - 29, Zone - 10.",Own Sources,10,2019-20,2020-21 NK/2019-20/15595,Buildings,Completed,NK-KODAMBAKKAM,130,471000,"Out Sorucing private workers for House Keeping for Chennai Middle School at Amman Koil street in Div-130,Unit-29,Zone-10 (from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/1653,Parks,Completed,NK-KODAMBAKKAM,130,145000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-130,UNIT-29,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2836,Buildings,Completed,NK-KODAMBAKKAM,130,411000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (16.07.2019 TO 30.04.2020) FOR CHENNAI MIDDLE SCHOOL AT AMMAN KOIL STREET(ESAT) IN DN-130,U-29,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/3078,Buildings,Completed,NK-KODAMBAKKAM,130,391000,"PROVIDING BORE WELL FOR CHENNAI MIDDLE SCHOOL AT AMMAN KOIL STREET (EAST), VADAPALANI IN DN-130, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/4122,Roads,Completed,NK-KODAMBAKKAM,130,910000,"PROVIDING RAIN WATER HARVESTING AT NERKUNDRAM PATHAI (EAST) IN DIV-130, U-29, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2019-20)",MLACDS,10,2019-20,2019-20 NK/2019-20/5891,Roads,Completed,NK-KODAMBAKKAM,130,141000,"Attending Patch Work using Wet mix Macadem at Bhakthavachalam Colony and Karumariamman Koil Street in Div-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7232,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,190000,"Repair and Improvements to Storm Water Drain at various streets in Div-130, U-29, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7301,Buildings,Completed,NK-KODAMBAKKAM,130,425000,"PROVIDING SECURITY ARRANGEMENTS AND OUTSOURCING PRIVATE LABOURS FOR UPHC AT RAJANGA MADHYA VEETHI, VADAPALANI IN DIV-130, U-29, Z-10 (FOR 1 YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/7306,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,966000,"DESILTING AND MINOR REPAIR TO THE EXISTING STORM WATER DRAIN AT N.S.K SALAI, VADAPALANI (FROM JN OF KUMARAN COLONY MAIN ROAD TO JN OF GREEN PARK HOTEL) IN DIV-130, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7307,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,1156000,"DESILTING AND MINOR REPAIR TO THE EXISTING STORM WATER DRAIN AT N.S.K SALAI, VADAPALANI (FROM JN OF GREEN PARK HOTEL TO JN OF 100 FEET ROAD) IN DIV-130, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7387,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,1280000,"DESILTING AND MINOR REPAIR TO THE EXISTING STORM WATER DRAIN AT ALAGIRI NAGAR MAIN ROAD, THIRU NAGAR MAIN ROAD, NGO COLONY MAIN ROAD AND OTHER STREETS IN DIV-130, U-29, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/8198,Buildings,Completed,NK-KODAMBAKKAM,130,489000,"Maintanence to the Amma Unavagam at Narkundram Pathai and NGO Colony Main Raod in Division - 130, Unit - 29, Zone - 10.",Own Sources,10,2019-20,2020-21 NK/2019-20/9819,Buildings,Completed,NK-KODAMBAKKAM,130,364000,"Maintenance works to the Health Post at Rajanga Madya Street in Division - 130, Unit - 29, Zone - 10.",Own Sources,10,2019-20,2020-21 BR/2019-20/1045,Road Cut,Completed,BR-Bus Route Roads,131,1880000,"Restoration of Road cut made by CMWSSB at Abusali Street and Arcot Road in Dn-131 , Zone 10(Deposit Code 57/0061/2017-18)",Deposit Works,10,2019-20,2019-20 BR/2019-20/1046,Road Cut,Completed,BR-Bus Route Roads,131,2220000,"Restoration Of road cut made by CMWSSB at 80 Ft Road in Dn 131, Zone-10(Deposit code 57/0061/2018-19)",Deposit Works,10,2019-20,2019-20 BR/2019-20/1069,Road Cut,Completed,BR-Bus Route Roads,131,1880000,"Restroration of road cut made by CMWSSB at Rajamannar Salai from Junction of 80 Ft. road to chainage of 350 m in Dn-131, Zone -10(Deposit Code- 57/0061/2017-18)",Deposit Works,10,2019-20,2019-20 BR/2019-20/1075,Road Cut,Completed,BR-Bus Route Roads,131,1440000,"Restoration of road cut made by CMWSSB at Rajamannar Salai from the Jn of East Vanniar Street to the Chainage of 350m in Dn -131, Zone -10",Deposit Works,10,2019-20,2019-20 BR/2019-20/14163,Road Cut,Completed,BR-Bus Route Roads,131,1747000,"Restoration of roadcut made by TANGEDCO in PV Rajamannar salai(Sivan park to Jn of Alagiri salai) in Division 131,Zone-10.",Deposit Works,10,2019-20,2020-21 BR/2019-20/14164,Road Cut,Completed,BR-Bus Route Roads,131,1310000,"Restoration of roadcut made by TANGEDCO in PV Rajamannar salai (Alagiri salai to Ponnambalam salai) in Division 131,Zone-10.",Deposit Works,10,2019-20,2020-21 BR/2019-20/6159,Road Cut,Completed,BR-Bus Route Roads,131,735000,"Restoration of roadcut made by CMWSSB at 80 feet Road in Dn-131, Zone-10",Deposit Works,10,2019-20,2019-20 NK/2019-20/0141,Buildings,Completed,NK-KODAMBAKKAM,131,56600,"CONSTRUCTION OF COMPOST PIT AT SIVAN PARK AND RANI ANNA NAGAR PARK IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/10239,Buildings,Completed,NK-KODAMBAKKAM,131,225000,"Improvements works to the Amma Unavagam at A.P.Patro Salai and P.V.Rajamannar Salai n Division-131, Unit-28, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11441,Roads,Completed,NK-KODAMBAKKAM,131,1337000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 40MM THICK USING MECHANICAL PAVER FINISHER AT 1ST SECTOR 1ST STREET IN DIVISION-131,UNIT-28,ZONE-10.",Grants,10,2019-20,2020-21 NK/2019-20/11674,Roads,Completed,NK-KODAMBAKKAM,131,1023000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 30MM THICK USING MECHANICAL PAVER FINISHER AT 2ND SECTOR 8TH STREET IN DIVISION-131,UNIT-28,ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11675,Roads,Completed,NK-KODAMBAKKAM,131,1137000,"RELAYING THE ROAD WITH BITUMINOUS CONCRETE 30MM THICK USING MECHANICAL PAVER FINISHER AT 2ND SECTOR 12TH STREET IN DIVISION-131,UNIT-28,ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13439,Roads,Completed,NK-KODAMBAKKAM,131,868000,"Relaying the road with BM and BC after cold milling by paver finisher 2nd sector 9th street in Division-131, Unit-28,Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13440,Roads,Completed,NK-KODAMBAKKAM,131,783000,"Relaying the road with BM and BC after cold milling by paver finisher at 2nd Sector 13th Street in Division-131, Unit-28,Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13441,Roads,Completed,NK-KODAMBAKKAM,131,1783000,"Relaying the road with BM and BC after cold milling by paver finisher at Sunday Observar Balasubramaniam salai in Division-131, Unit-28,Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/14852,Buildings,Completed,NK-KODAMBAKKAM,131,3300000,"Providing Additional Construction for Dining Hall and Electrical Arrangements in second floor to the Multi Purpose Hall at 80 Feet Road in Division-131, Unit-28, Zone-10. (Under MLA Fund)",MLACDS,10,2019-20,2020-21 NK/2019-20/1593,Parks,Completed,NK-KODAMBAKKAM,131,178000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-131,UNIT-28,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/1868,Roads,Completed,NK-KODAMBAKKAM,131,168000,"Improvements work to the center median at P.T.Rajan Salai in Division 131, Unit-28, Zone 10.",Own Sources,10,2019-20,2019-20 NK/2019-20/1869,Roads,Completed,NK-KODAMBAKKAM,131,162000,"Improvements work to the center median at Anna Main Road in Division 131, Unit-28, Zone 10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4569,Parks,Completed,NK-KODAMBAKKAM,131,332000,"Maintanance and Repair works to the GCC Buildings such as Footpath, Anganwadi and Play Grounds etc...in Division-131, Unit-28, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4570,Buildings,Completed,NK-KODAMBAKKAM,131,161000,"Maintanance and Repair Works to the GCC Buildings such as Park, Division Office & Storm Water Drain etc..in Division-131, Unit-28, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5564,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,969000,"DESILTING AND MINOR REPAIR WORK FOR THE EXISTING STORM WATER DRAIN AT P.T.RAJAN SALAI, RAMASAMY SALAI, LAKSHMANASAMY SALAI, SOB SALAI, 8O FEET ROAD, ANNA MAIN ROAD AND VARIOUS STREETS IN DIV-131, UNIT-28, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5565,Storm Water Drain,Completed,NK-KODAMBAKKAM,131,889000,"DESILTING AND MINOR REPAIR WORK FOR THE EXISTING STORM WATER DRAIN AT JEEVANATHAM SALAI, RAJAMANNAR SALAI, RANI ANNA NAGAR MAIN STREET AND VARIOUS STREETS IN DIV-131, UNIT-28, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5740,Parks,Completed,NK-KODAMBAKKAM,131,782000,"MAINTANANCE OF PARK AT RANI ANNA NAGAR IN DIVISION-131, UNIT-28, ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7282,Buildings,Completed,NK-KODAMBAKKAM,131,556000,"Providing Security Arrangements and Engaging private labourers for NHUM Hospital at Vijayaraghavapuram 5th Street (12 Months) in Division - 131, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/7925,Roads,Completed,NK-KODAMBAKKAM,131,300000,"Attending Patch work Jeevanatham Salai,SOB Salai, V.V.Giri Street, 2nd Sector 13th Street and Various Streets in Division-131, Unit-28, Zone-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/8315,Road Cut,Completed,NK-KODAMBAKKAM,131,650000,"Restoration of Road cut made by CMWSSB at P.V.Rajamannar Salai in Division-131, Unit-28, Zone-10.",Deposit Works,10,2019-20,2020-21 BR/2019-20/14165,Road Cut,Completed,BR-Bus Route Roads,132,735000,"Restoration of roadcut made by TANGEDCO in Ashok nagar 2nd avenue in Division 132,Zone-10.",Deposit Works,10,2019-20,2020-21 BR/2019-20/16782,Road Cut,Completed,BR-Bus Route Roads,132,991000,"RESTORATION OF OFC ROAD CUT IN VARIOUS LOCATIONS AT DIVISION -132, ZONE-10. DEPOSIT CODE-57/0523/2018-19",Deposit Works,10,2019-20,2020-21 BR/2019-20/4756,Roads,Completed,BR-Bus Route Roads,132,13896000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Kamarajar Salai(K.K Nagar) in Dn-132 ,Zone X",Grants,10,2019-20,2020-21 BR/2019-20/5192,Roads,Completed,BR-Bus Route Roads,132,825000,"Partly relaying the road with BC after cold milling by paver finisher at Ashok Nagar 2nd Avenue in Dn- 132, Zone - X",Grants,10,2019-20,2020-21 BR/2019-20/5797,Road Cut,Completed,BR-Bus Route Roads,132,740000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-132, U-31, Zone-10",Deposit Works,10,2019-20,2019-20 L/2019-20/8759,Electrical,Completed,L-Electrical,132,16747300,"Supply and Replacement of Damaged 417 Nos of Lamp post at Various places in div 129,132 and 137 in zone X Area.",Grants,10,2019-20,2021-22 NK/2019-20/0442,Buildings,Completed,NK-KODAMBAKKAM,132,59700,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS FOR 38 DAYS (GOVT.GIRLS.HR.SEC.SCHOOL AT 9TH AVENUE, ASHOK NAGAR) IN DN-,132,U-31, Z-10 (FROM 1.6.19 TO 15.7.19)",Own Sources,10,2019-20,2020-21 NK/2019-20/0445,Buildings,Completed,NK-KODAMBAKKAM,132,59700,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS FOR 38 DAYS (GOVT.HR.SEC.SCHOOL PUDHUR AT 3RD AVENUE, ASHOK NAGAR) IN DN-,132,U-31, Z-10 (FROM 1.6.19 TO 15.7.19)",Own Sources,10,2019-20,2020-21 NK/2019-20/0446,Buildings,Completed,NK-KODAMBAKKAM,132,14900,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS FOR 38 DAYS (C.P.S AT KANNIYAPPA NAGAR) IN DN-,132,U-31, Z-10 (FROM 1.6.19 to 15.7.19)",Own Sources,10,2019-20,2020-21 NK/2019-20/0449,Buildings,Completed,NK-KODAMBAKKAM,132,29800,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS FOR 38 DAYS (C.H.S AT KANNIYAPPA NAGAR) IN DN-,132,U-31, Z-10 (FROM 1.6.19 TO 15.7.19)",Own Sources,10,2019-20,2020-21 NK/2019-20/11392,Buildings,Completed,NK-KODAMBAKKAM,132,430000,"IMPROVEMENTS TO ICDS CENTRE 2ND STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11719,Roads,Completed,NK-KODAMBAKKAM,132,343000,"Relaying of Bituminous Concrete Road using BC 30MM at Vedhachalam Nagar 1st Street in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13393,Roads,Completed,NK-KODAMBAKKAM,132,3074000,"Relaying of Bituminous Concrete road with BC 40mm at 18th Avenue, Ashok Nagar (Part) in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13394,Roads,Completed,NK-KODAMBAKKAM,132,1719000,"Relaying of Bituminous Concrete road with BC 40mm at S.V.Lingam Salai in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13395,Roads,Completed,NK-KODAMBAKKAM,132,275000,"Relaying of Bituminous Concrete road with BC 40mm at Vaigai Colony 1st Street (Part) in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13396,Roads,Completed,NK-KODAMBAKKAM,132,2224000,"Relaying of Bituminous Concrete road with BC 40mm at 86th Street (Part), Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13399,Roads,Completed,NK-KODAMBAKKAM,132,470000,"Relaying of Bituminous Concrete road with BC 40mm at Sri Devi Colony Street, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13400,Roads,Completed,NK-KODAMBAKKAM,132,293000,"Relaying of Bituminous Concrete road with BC 40mm at 43rd Street (Part), Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13401,Roads,Completed,NK-KODAMBAKKAM,132,907000,"Relaying of Bituminous Concrete road with BC 40mm at Soundara Pandian Salai(Part), Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13403,Roads,Completed,NK-KODAMBAKKAM,132,1706000,"Relaying of Bituminous Concrete road with BC 40mm at Pudur 8th Street, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13404,Roads,Completed,NK-KODAMBAKKAM,132,152000,"Relaying of Bituminous Concrete road with BC 40mm at 93rd Street, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13405,Roads,Completed,NK-KODAMBAKKAM,132,152000,"Relaying of Bituminous Concrete road with BC 40mm at 94th Street, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13406,Roads,Completed,NK-KODAMBAKKAM,132,141500,"Relaying of Bituminous Concrete road with BC 40mm at 15th Sector 96th Street(Part), K.K Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13407,Roads,Completed,NK-KODAMBAKKAM,132,233000,"Relaying of Bituminous Concrete road with BC 40mm at 15th Sector 97th Street(Part), K.K Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13408,Roads,Completed,NK-KODAMBAKKAM,132,178000,"Relaying of Bituminous Concrete road with BC 30mm at 77th Street, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13442,Roads,Completed,NK-KODAMBAKKAM,132,295000,"Laying of Cement Concrete Road with M30 Grade Concrete at Pudur 1st Lane, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13443,Roads,Completed,NK-KODAMBAKKAM,132,405000,"Laying of Cement Concrete Road with M30 Grade Concrete at Pudur 2nd Lane, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13444,Roads,Completed,NK-KODAMBAKKAM,132,405000,"Laying of Cement Concrete Road with M30 Grade Concrete at Pudur 3rd Lane, Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13445,Roads,Completed,NK-KODAMBAKKAM,132,784000,"Laying of Cement Concrete Road with M30 Grade Concrete at 14th Sector 102nd street in Div-132, U-31, Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13446,Roads,Completed,NK-KODAMBAKKAM,132,170000,"Providing Interlocking Paver Block for Footpath at 14th Sector 104th Street, K.K.Nagar in Div-132, U-31, Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/1507,Roads,Completed,NK-KODAMBAKKAM,132,56000,"Demolition and Reconstruction of Center Median at 11th Avenue in Division 132, Unit-31, Zone -10",Own Sources,10,2019-20,2019-20 NK/2019-20/1508,Roads,Completed,NK-KODAMBAKKAM,132,252000,"Demolition and Reconstruction of Center Median at 4th Avenue in Division 132, Unit-31, Zone -10",Own Sources,10,2019-20,2019-20 NK/2019-20/16424,Roads,Completed,NK-KODAMBAKKAM,132,435000,"LAYING OF PVC PIPE 160MM DIA AT ASHOK NAGAR 7TH AVENUE AND MAINTENANCE WORK TO THE AMMA UNAVAGAM, NNMP SHED, UPHC IN DIV-132,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/18122,Playfields,Completed,NK-KODAMBAKKAM,132,2490000,"DISMANTLING THE EXISTING COMPOUND WALL AND RECONSTRUCTION OF CONCRETE COMPOUND AT 47TH STREET PLAYGROUND, ASHOK NAGAR IN DIV-132, U-31, Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/2072,Buildings,Completed,NK-KODAMBAKKAM,132,205000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (C.H.S AT KANNIYAPPA NAGAR) IN DN-,132,U-31, Z-10 (FROM 16.07.2019 TO 30.04.20)",Own Sources,10,2019-20,2020-21 NK/2019-20/2076,Buildings,Completed,NK-KODAMBAKKAM,132,411000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (GOVT.GIRLS.HR.SEC.SCHOOL AT 9TH AVENUE, ASHOK NAGAR) IN DN-,132,U-31, Z-10 (FROM 16.07.2019 TO 30.04.20)",Own Sources,10,2019-20,2020-21 NK/2019-20/2078,Buildings,Completed,NK-KODAMBAKKAM,132,411000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (GOVT.HR.SEC.SCHOOL PUDHUR AT 3RD AVENUE, ASHOK NAGAR) IN DN-,132,U-31, Z-10 (FROM 16.07.2019 TO 30.04.20)",Own Sources,10,2019-20,2020-21 NK/2019-20/2080,Buildings,Completed,NK-KODAMBAKKAM,132,102000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (C.P.S AT KANNIYAPPA NAGAR) IN DN-,132,U-31, Z-10 (FROM 16.07.2019 TO 30.04.20)",Own Sources,10,2019-20,2020-21 NK/2019-20/2756,Buildings,Completed,NK-KODAMBAKKAM,132,200000,"REPAIR AND IMPROVEMENTS TO ICDS CENTRE (CENTRE NO. 33603040404) AT 77TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3243,Buildings,Completed,NK-KODAMBAKKAM,132,660000,"REPAIR AND IMPROVEMENTS TO ICDS CENTRE 5TH AVENUE, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3785,Buildings,Completed,NK-KODAMBAKKAM,132,1585000,"PROPOSED CONSTRUCTION OF RATION SHOP AT SAIDAPET ROAD, VADAPALANI IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2018-19)",MLACDS,10,2019-20,2019-20 NK/2019-20/4724,Parks,Completed,NK-KODAMBAKKAM,132,952000,"ANNUAL MAINTENANCE OF 1ST AVENUE PARK AT ASHOK NAGAR IN DIV-132, U-31, Z-10 (QUALIFIED HORTICULTURIST ONLY) (FOR 1 YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/4728,Parks,Completed,NK-KODAMBAKKAM,132,990000,"ANNUAL MAINTENANCE OF PARK AT 14TH SECTOR 102ND STREET PARK (FOR 1 YEAR) IN DIVISION-132,UNIT-31,ZONE-10 (EMPLOYED QUALIFIED HORTICULTURIST FOR ONE YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/4870,Parks,Completed,NK-KODAMBAKKAM,132,274000,"ANNUAL MAINTENANCE OF 15TH SECTOR 98TH STREET PARK AT K.K.NAGAR IN DIV-132, U-31, Z-10 (QUALIFIED HORTICULTURIST ONLY) (FOR 1 YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/5728,Roads,Completed,NK-KODAMBAKKAM,132,1600000,"PROVIDING INTERLOCKING PAVER BLOCK FOR ODDAGAPALAYAM SLUM 1 TO 13 STREETS, VADAPALANI IN DIV-132, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2019-20)",MLACDS,10,2019-20,2020-21 NK/2019-20/7094,Buildings,Completed,NK-KODAMBAKKAM,132,555000,"OUTSOURCING PRIVATE LABOURS FOR UPHC AT 35TH STREET, ASHOK NAGAR IN DIV-132, U-31, Z-10 (FOR 1 YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/7237,Roads,Completed,NK-KODAMBAKKAM,132,3742000,"LAYING CEMENT CONCRETE ROAD USING M30 GRADE CONCRETE AT ODDAGAPALAYAM CHURCH ROAD, VADAPALANI IN DIV-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7302,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,880000,"De-silting & Minor Repair to the Existing Storm Water Drain at Ashok Nagar 4th, 8th, & 10th Avenue, Ashok Nagar 41st & 86th Street, Kamarajar Salai and Other streets in Div-132, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7303,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,984000,"De-silting & Minor Repair to the Existing Storm Water Drain at 2nd, 3rd, 6th, 9th, 16th, 18th Avenue, Ashok Nagar and Other streets in Div-132, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7572,Roads,Completed,NK-KODAMBAKKAM,132,500000,"Attending Patch Work with Bituminous Concrete by using Paver Finisher at 9th Avenue, 18th Avenue and other Streets in Div-132, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7581,Roads,Completed,NK-KODAMBAKKAM,132,350000,"Attending Patch Work with Bituminous Concrete by using Paver Finisher at 5th Avenue, Vengeeswarar Nagar 3rd Main Road and other Streets in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/9002,Buildings,Completed,NK-KODAMBAKKAM,132,1035000,"OPERATION AND MAINTENANCE OF GAS (LPG) CREMATORIUM AT AVM BURIAL GROUND IN DIVISION -132,UNIT - 31,ZONE- 10 (FOR 1 YEAR ONLY)",Own Sources,10,2019-20,2020-21 BR/2019-20/11509,Road Cut,Completed,BR-Bus Route Roads,133,633000,Restoration of Road cut Made by M/s Bharathi Airtel at various bus route roads in zone 10 (Deposit code-57/0523/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/11511,Road Cut,Completed,BR-Bus Route Roads,133,147000,Restoration of Road cut Made by M/s Reliance jio at various bus route roads in zone 10 (Deposit code-57/0552/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/5191,Roads,Completed,BR-Bus Route Roads,133,706000,"Partly relaying the road with BC after cold milling by paver finisher at Ashok Nagar 12 th Avenue in Dn- 133, Zone - X",Grants,10,2019-20,2020-21 BR/2019-20/5792,Road Cut,Completed,BR-Bus Route Roads,133,213000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-133,U-31, Zone-10",Deposit Works,10,2019-20,2019-20 L/2019-20/8754,Electrical,Completed,L-Electrical,133,794000,Replacement of 1400 meters of 2x25 sq.mm. Cable in Various Streets in Division 133 and 135 (West Mambalam Section) in Zone X.,Grants,10,2019-20,2020-21 NK/2019-20/0434,Buildings,Completed,NK-KODAMBAKKAM,133,44700,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS FOR 38 DAYS (C.H.S.S. PULIYUR) IN DN-,133,U-31, Z-10 (FROM 1.6.19 TO 15.7.19)",Own Sources,10,2019-20,2020-21 NK/2019-20/0435,Buildings,Completed,NK-KODAMBAKKAM,133,14900,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS FOR 38 DAYS (C.P.S PULIYUR) IN DN-,133,U-31, Z-10 (FROM 1.6.19 TO 15.7.19)",Own Sources,10,2019-20,2020-21 NK/2019-20/0440,Buildings,Completed,NK-KODAMBAKKAM,133,14900,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS FOR 38 DAYS (C.P.S MULLAI NAGAR) IN DN-,133,U-31, Z-10 (FROM 1.6.19 TO 15.7.19)",Own Sources,10,2019-20,2020-21 NK/2019-20/10303,Buildings,Completed,NK-KODAMBAKKAM,133,2435000,"Improvements to the School Building for CHSS, Puliyur at NSK Salai in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/10647,Buildings,Completed,NK-KODAMBAKKAM,133,1850000,"Improvements to the Chennai Primary School, Mullai Nagar at 15th Street, Ashok Nagar in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/10662,Roads,Completed,NK-KODAMBAKKAM,133,536134,"REPAIR AND MAINTENANCE WORKS TO THE CPS & CHSS AT NSK SALAI AND MULLAI NAGAR, PUBLIC CONVENIENCE, CORPORATION OFFICE BUILDING AND OTHERS AT VARIOUS LOCATIONS IN DN-133, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/10777,Buildings,Completed,NK-KODAMBAKKAM,133,65000,"Demolition of existing dilapidated ICDS Building at 15th Street, Ashok Nagar in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11347,Buildings,Completed,NK-KODAMBAKKAM,133,497000,"REPAIR AND IMPROVEMENTS TO THE SCHOOL BUILDING FOR CHSS, PULIYUR AND CPS, MULLAI NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/12537,Buildings,Completed,NK-KODAMBAKKAM,133,556000,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV Filter) of 2000 Litres Hours Capacity for 7 months Period (from 17.02.2020 to 16.09.2020) at 24th Street, Ashok Nagar in DIVISION -133, UNIT-31, ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12538,Buildings,Completed,NK-KODAMBAKKAM,133,556000,"Operation and Maintenance of High Quality Treated Drinking Water Plant (RO/UV Filter) of 2000 Litres Hours Capacity for 7 months Period (from 17.02.2020 to 16.09.2020) at 10th Avenue, Ashok Nagar in DIVISION -133, UNIT-31, ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13447,Roads,Completed,NK-KODAMBAKKAM,133,361000,"Relaying of Bituminous Concrete road with BC 30mm at Vengeeswarar Nagar 3rd Main Road (Part) in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13449,Roads,Completed,NK-KODAMBAKKAM,133,322000,"Relaying of Bituminous Concrete road with BC 40mm at 16th Street, Ashok Nagar in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13450,Roads,Completed,NK-KODAMBAKKAM,133,720000,"Relaying of Bituminous Concrete road with BC 40mm at Kavarai Street in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13451,Roads,Completed,NK-KODAMBAKKAM,133,685000,"Relaying of Bituminous Concrete road with BC 40mm at Kannadasan Street in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13452,Roads,Completed,NK-KODAMBAKKAM,133,714000,"Relaying of Bituminous Concrete road with BC 40mm at Subbrayan Nagar 6th Cross 1st Street in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13453,Roads,Completed,NK-KODAMBAKKAM,133,891000,"Relaying of Bituminous Concrete road with BC 40mm at Vengeeswarar Nagar 1st Main Road in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13454,Roads,Completed,NK-KODAMBAKKAM,133,647000,"Relaying of Bituminous Concrete road with BC 40mm at 5th Avenue (Part), Ashok Nagar in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13455,Roads,Completed,NK-KODAMBAKKAM,133,1134000,"Relaying of Bituminous Concrete road with BC 40mm at Karnan Street in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13456,Roads,Completed,NK-KODAMBAKKAM,133,1025000,"Relaying of Bituminous Concrete road with BC 40mm at Vathiyar Thottam Main Road in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13457,Roads,Completed,NK-KODAMBAKKAM,133,116500,"Relaying of Bituminous Concrete road with BC 40mm at Shayamala Vadana II Cross St [Haribabau St] in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13458,Roads,Completed,NK-KODAMBAKKAM,133,1798000,"Relaying of Bituminous Concrete road with BC 40mm at Raju Street in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13460,Roads,Completed,NK-KODAMBAKKAM,133,190000,"Relaying of Bituminous Concrete road with BC 40mm at Subrarayan Nagar IV Street Part in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13461,Roads,Completed,NK-KODAMBAKKAM,133,572000,"Relaying of Bituminous Concrete road with BC 40mm at Subrarayan Nagar Main Road (Part) in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13462,Roads,Completed,NK-KODAMBAKKAM,133,1101000,"Relaying of Bituminous Concrete road with BC 40mm at Palayakkaran Street (Part) in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13463,Roads,Completed,NK-KODAMBAKKAM,133,679000,"Relaying of Bituminous Concrete road with BC 40mm at Vedhachala Nagar 1st Street (Part) in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13464,Roads,Completed,NK-KODAMBAKKAM,133,951000,"Relaying of Bituminous Concrete road with BC 40mm at Vengeeswarar Nagar 2nd Main Road (Part) in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/1514,Roads,Completed,NK-KODAMBAKKAM,133,56000,"Demolition and Reconstruction of Center Median at 11th Avenue in Division 133, Unit-31, Zone -10",Own Sources,10,2019-20,2019-20 NK/2019-20/1515,Roads,Completed,NK-KODAMBAKKAM,133,179000,"Demolition and Reconstruction of Center Median at 4th Avenue in Division 133, Unit-31, Zone -10",Own Sources,10,2019-20,2019-20 NK/2019-20/1651,Parks,Completed,NK-KODAMBAKKAM,133,124000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-133,UNIT-31,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/1852,Roads,Completed,NK-KODAMBAKKAM,133,123000,"Demolition and Reconstruction of Center Median at NSK Salai in Division 133, Unit-31, Zone -10",Own Sources,10,2019-20,2019-20 NK/2019-20/2081,Buildings,Completed,NK-KODAMBAKKAM,133,308000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (C.H.S.S. PULIYUR) IN DN-,133,U-31, Z-10 (FROM 16.07.2019 TO 30.04.20)",Own Sources,10,2019-20,2020-21 NK/2019-20/2083,Buildings,Completed,NK-KODAMBAKKAM,133,102000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (C.P.S PULIYUR) IN DN-,133,U-31, Z-10 (FROM 16.07.2019 TO 30.04.20)",Own Sources,10,2019-20,2020-21 NK/2019-20/2084,Buildings,Completed,NK-KODAMBAKKAM,133,102000,"ENGAGING PRIVATE LABOURS FOR SCHOOL OUT SOURCING WORK FOR CORPORATION SCHOOLS & TOILETS (C.P.S MULLAI NAGAR) IN DN-,133,U-31, Z-10 (FROM 16.07.2019 TO 30.04.20)",Own Sources,10,2019-20,2020-21 NK/2019-20/2796,Buildings,Completed,NK-KODAMBAKKAM,133,363000,"REPAIR AND IMPROVEMENTS TO ICDS CENTRE 59TH STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/2797,Buildings,Completed,NK-KODAMBAKKAM,133,342000,"REPAIR AND IMPROVEMENTS TO ICDS CENTRE 62ND STREET, ASHOK NAGAR IN DIV-133, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3063,Buildings,Completed,NK-KODAMBAKKAM,133,391000,"PROVIDING WATER SUPPLY ARRANGEMENTS TO SCHOOL BUILDING AT CHSS PULIYUR, AT NSK SALAI, KODAMBAKKAM IN DIV-133, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7098,Buildings,Completed,NK-KODAMBAKKAM,133,555000,"OUTSOURCING PRIVATE LABOURS FOR UPHC AT 5TH AVENUE, ASHOK NAGAR IN DIV-133, U-31, Z-10 (FOR 1 YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/7304,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,1028000,"De-silting & Minor Repair to the existing Storm Water Drain at Rajagopalan Street, Bharathi Street, Iyyappan Stree, Mahadevan Street, 11th Avenue and other street in Div-133, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7305,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,1319000,"De-silting & Minor Repair to the Existing Storm Water Drain at NSK Salai, Postal Colony 1st & 2nd Street, Ashok Nagar 5th Avenue and Other streets in Div-133, U-31, Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/7384,Roads,Completed,NK-KODAMBAKKAM,133,2315000,"Relaying of Bituminous Concrete Road using BC 30MM at Brindhavan Street Extension, West Mambalam in Div-133, U-31, Z-10 (UNDER T.NAGAR CONSTITUENCY MLA FUND 2019-20)",MLACDS,10,2019-20,2020-21 NK/2019-20/9531,Roads,Completed,NK-KODAMBAKKAM,133,281000,"Providing Speed Breaker at Kavarai Street, Subbrayan Nagar 1st Street and various Streets in Div-133, U-31, Z-10",Own Sources,10,2019-20,2020-21 BR/2019-20/11510,Road Cut,Completed,BR-Bus Route Roads,134,264000,Restoration of Road cut Made by M/s Reliance jio at various bus route roads in zone 10 (Deposit code-57/0520/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/11512,Road Cut,Completed,BR-Bus Route Roads,134,401000,Restoration of Road cut Made by M/s Reliance jio at various bus route roads in zone 10 (Deposit code-57/0552/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/11513,Road Cut,Completed,BR-Bus Route Roads,134,423000,Restoration of Road cut Made by M/s ACT at various bus route roads in zone 10 (Deposit code-57/0809/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/11514,Road Cut,Completed,BR-Bus Route Roads,134,221000,Restoration of Road cut Made by M/s Reliance Jio at various bus route roads in zone 10 (Deposit code-57/1145/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/5791,Road Cut,Completed,BR-Bus Route Roads,134,385000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-134, U-31, Zone-10",Deposit Works,10,2019-20,2019-20 NK/2019-20/0387,Buildings,Completed,NK-KODAMBAKKAM,134,29800,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.06.2019 TO 15.07.2019) FOR CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/0388,Buildings,Completed,NK-KODAMBAKKAM,134,29800,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.06.2019 TO 15.07.2019) FOR CHENNAI MIDDLE SCHOOL AT KAMARAJAR COLONY IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/0389,Buildings,Completed,NK-KODAMBAKKAM,134,29800,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.06.2019 TO 15.07.2019) FOR CHENNAI PRIMARY SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/0390,Buildings,Completed,NK-KODAMBAKKAM,134,29800,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.06.2019 TO 15.07.2019) FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/0397,Bridges,Completed,NK-KODAMBAKKAM,134,29800,"OUT SOURCING OF PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK (FROM 01.06.2019 TO 15.07.2019) AT CHENNAI PRIMARY SCHOOL AT ESWARANKOIL STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/10056,Playfields,Completed,NK-KODAMBAKKAM,134,331000,"IMPROVEMENT WORKS TO THE EXISTING PLAY GROUND AND GYM BUILDING AT CORPORATION COLONY 1ST MAIN ROAD IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/10743,Buildings,Completed,NK-KODAMBAKKAM,134,753000,"DISMANTLING THE EXISTING BLOCKED SEWER LINE AND PROVIDING NEW LINE AND PROVIDING BORE WELL FOR CHENNAI MIDDLE SCHOOL AT CORPORATION COLONY ROAD IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/10905,Roads,Completed,NK-KODAMBAKKAM,134,581000,"IMPROVEMENT WORKS TO THE CENTER MEDIAN AT DR.AMBEDKAR ROAD IN DIVISION-134, UNIT-31, ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11136,Roads,Completed,NK-KODAMBAKKAM,134,332000,"RELAYING OF BT ROAD BY USING BC 40MM THICK AT RANGARAJAPURAM Y BRIDGE SOUTH SIDE APPROACH PORTION IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11270,Buildings,Completed,NK-KODAMBAKKAM,134,498000,"REPAIR AND MAINTENANCE WORKS TO THE CPS, CHS AT RANGARAJAPURAM MAIN ROAD, HOSPITAL, CORPORATION BUILDINGS, OFFICES AND PUBLIC CONVENIENCE AT VARIOUS LOCATIONS IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/11688,Roads,Completed,NK-KODAMBAKKAM,134,911000,"RELAYING THE ROAD WITH DBM AND BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT ANUSHIYA STREET IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11718,Roads,Completed,NK-KODAMBAKKAM,134,229000,"RELAYING THE ROAD WITH BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT RANGARAJAPURAM 1ST STREET IN DN-134, U-31, Z-10 (FROM CHAINAGE 0-80.0M)",Own Sources,10,2019-20,2020-21 NK/2019-20/11720,Roads,Completed,NK-KODAMBAKKAM,134,286000,"RELAYING THE ROAD WITH BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT RANGARAJAPURAM 3RD STREET IN DN-134, U-31, Z-10 (FROM CHAINAGE 0-100.0M)",Own Sources,10,2019-20,2020-21 NK/2019-20/11722,Roads,Completed,NK-KODAMBAKKAM,134,740000,"RELAYING THE ROAD WITH BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT AZIZ NAGAR 1ST STREET IN DN-134, U-31, Z-10 (FROM CHAINAGE 0-220M)",Own Sources,10,2019-20,2020-21 NK/2019-20/11724,Roads,Completed,NK-KODAMBAKKAM,134,323000,"RELAYING THE ROAD WITH BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT U.I.COLONY PARK VIEW ROAD IN DN-134, U-31, Z-10 (FROM CHAINAGE 0-70.0M)",Own Sources,10,2019-20,2020-21 NK/2019-20/11725,Roads,Completed,NK-KODAMBAKKAM,134,392000,"RELAYING THE ROAD WITH BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT PADMANABAN STREET IN DN-134, U-31, Z-10 (FROM CHAINAGE 0-90M)",Own Sources,10,2019-20,2020-21 NK/2019-20/11726,Roads,Completed,NK-KODAMBAKKAM,134,738000,"RELAYING THE ROAD WITH BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT U.I.COLONY 2ND CROSS STREET IN DN-134, U-31, Z-10 (FROM CHAINAGE 0-160.0M)",Own Sources,10,2019-20,2020-21 NK/2019-20/11727,Roads,Completed,NK-KODAMBAKKAM,134,559000,"RELAYING THE ROAD WITH BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT U.I.COLONY 6TH CROSS STREET IN DN-134, U-31, Z-10 (FROM CHAINAGE 0-120.0M)",Own Sources,10,2019-20,2020-21 NK/2019-20/12910,Roads,Completed,NK-KODAMBAKKAM,134,1177000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT AZIZ NAGAR MAIN ROAD (FROM CHAINAGE 0-180.0M) IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/12981,Buildings,Completed,NK-KODAMBAKKAM,134,2345000,"DEMOLITION OF EXISTING SHOPPING COMPLEX SECOND FLOOR AT NSK SALAI, KODAMBAKKAM IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13388,Roads,Completed,NK-KODAMBAKKAM,134,956000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT SUBRAMANIYAN NAGAR CROSS STREET (FROM CHAINAGE 0-220.0M) IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13389,Roads,Completed,NK-KODAMBAKKAM,134,1020000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT SUBRAMANIYAN NAGAR 2ND STREET IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13402,Roads,Completed,NK-KODAMBAKKAM,134,596000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT BOOPATHY NAGAR (FROM CHAINAGE 0-255.0M) IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13412,Roads,Completed,NK-KODAMBAKKAM,134,603000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT KAMARAJAR COLONY 9TH STREET (FROM DR.AMBEDKAR ROAD TO PALAYAKARAN STREET) IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13415,Roads,Completed,NK-KODAMBAKKAM,134,468000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT VALLIAMMAL GARDEN 1ST STREET (FROM CHAINAGE 0-165.0M) IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13420,Roads,Completed,NK-KODAMBAKKAM,134,454000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT VALLIAMMAL GARDEN 3RD STREET (FROM CHAINAGE 0-165.0M) IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13422,Roads,Completed,NK-KODAMBAKKAM,134,542000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AT PATEL STREET (FROM CHAINAGE 0-105.0M) IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13423,Roads,Completed,NK-KODAMBAKKAM,134,1350000,"RELAYING THE ROAD WITH BC 40MM THICK BY PAVER FINISHER AND ROAD CUT RESTORATION (FROM DR.GOPALAMENON ROAD TO DEAD END) AT AKBARABAD 2ND STREET IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/14672,Buildings,Completed,NK-KODAMBAKKAM,134,2492000,"PROPOSED CONSTRUCTION OF FIRST FLOOR FOR ELECTRICAL DEPARTMENT AT ZONAL OFFICE HEALTH BUILDING AT NSK SALAI, IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/1590,Roads,Completed,NK-KODAMBAKKAM,134,336000,"IMPROVEMENT WORKS TO THE CENTER MEDIAN AT ARCOT ROAD IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/1647,Parks,Completed,NK-KODAMBAKKAM,134,142000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-134,UNIT-31,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/2089,Buildings,Completed,NK-KODAMBAKKAM,134,205000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (16.07.2019 TO 30.04.2020) FOR CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/2095,Buildings,Completed,NK-KODAMBAKKAM,134,205000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (16.07.2019 TO 30.04.2020) FOR CHENNAI MIDDLE SCHOOL AT KAMARAJAR COLONY IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/2098,Buildings,Completed,NK-KODAMBAKKAM,134,205000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (16.07.2019 TO 30.04.2020) FOR CHENNAI PRIMARY SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/2099,Buildings,Completed,NK-KODAMBAKKAM,134,205000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (16.07.2019 TO 30.04.2020) FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/2633,Buildings,Completed,NK-KODAMBAKKAM,134,391000,"PROVIDING BORE WELL FOR CHENNAI HIGH SCHOOL, RANGARAJAPURAM AT RANGARAJAPURAM MAIN ROAD IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/2721,Buildings,Completed,NK-KODAMBAKKAM,134,145000,"REPAIR AND IMPROVEMENT WORKS TO THE ANGANWADI CENTER NO: 33603080123 AT KAMARAJAR COLONY 3RD STREET IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3647,Buildings,Completed,NK-KODAMBAKKAM,134,1977000,"REPIR AND IMPROVEMENT WORS TO THE COMMUNITY HALL AT DR.AMBEDKAR ROAD IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3736,Buildings,Completed,NK-KODAMBAKKAM,134,1225000,"PAINTING AND IMPROVEMENT WORKS FOR ZONAL OFFICE-10 BUILDING AT NSK SALAI, KODAMBAKKAM IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/4585,Parks,Completed,NK-KODAMBAKKAM,134,638000,"MAINTENANCE WORKS TO THE ANNA PARK AT U.I.COLONY IN DN-134, U-31, Z-10 (FOR ONE YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/4588,Parks,Completed,NK-KODAMBAKKAM,134,890000,"MAINTENANCE WORKS TO THE KALAINGAR PARK AT CORPORATION COLONY ROAD IN DN-134, U-31, Z-10 (FOR ONE YEAR)",Own Sources,10,2019-20,2020-21 NK/2019-20/5046,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,1254000,"DE-SILTING AND MINOR REPAIR WORKS TO THE EXISTING STORM WATER DRAIN AT NSK SALAI, CORPORATION COLONY MAIN ROAD, STATION VIEW ROAD, U.I.COLONY 1ST, 2ND, 3RD & 4TH MAIN ROAD, ASHOKA AVENUE, NTR STREET, THIRUVALLUVAR STREET, AZIZ NAGAR MAIN ROAD, VALLIAMMAL GARDEN MAIN ROAD, RANGARAJAPURAM MAIN ROAD, PARANGUSAPURAM AND VARIOUS STREETS IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7184,Buildings,Completed,NK-KODAMBAKKAM,134,497000,"MAINTENANCE TO CORPORATION BUILDINGS, ROAD, FOOTPATH, PARK, PLAY GROUND AND ROAD CUT RESTORATION AT VARIOUS STREETS IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7310,Buildings,Completed,NK-KODAMBAKKAM,134,461000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING AND ENGAGING SECURITY GUARDS(ONE YEAR) FOR UPHC AT CORPORATION COLONY ROAD IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7311,Buildings,Completed,NK-KODAMBAKKAM,134,923000,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING AND ENGAGING SECURITY GUARDS (ONE YEAR) FOR COMMUNITY WELFARE CENTER VADAPALANI (24 HOURS MATERNITY HOSPITAL & EMERGENCY OPERATIVE CARE) AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7570,Roads,Completed,NK-KODAMBAKKAM,134,339000,"ATTENDING PATCH WORK USING BC 40MM THICK BY PAVER FINISHER AT CHAKRAPANI STREET, RANGARAJAPURAM MAIN ROAD, RAILWAY BORDER ROAD, PATEL STREET, BHOOPATHY NAGAR AND KAMARAJAR COLONY 5TH STREET IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/9955,Buildings,Completed,NK-KODAMBAKKAM,134,1322000,"IMPROVEMENT WORKS TO THE HEALTH & REVENUE DEPARTMENT OFFICE IN ZONAL OFFICE -10 BUILDING AT NSK SALAI IN DN-134, U-31, Z-10",Own Sources,10,2019-20,2020-21 BR/2019-20/11507,Road Cut,Completed,BR-Bus Route Roads,135,739000,Restoration of Road cut Made by M/s Bharathi Airtel at various bus route in zone-10 (Deposit code-57/0522/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/18207,Roads,Completed,BR-Bus Route Roads,135,101000,"RESTORATION OF OFC ROAD SATHYAPURI STREET AND VARIOUS STREETS IN DIV-135, U-31,Z-10",Deposit Works,10,2019-20,2021-22 BR/2019-20/18208,Roads,Completed,BR-Bus Route Roads,135,480000,"RESTORATION OF OFC ROAD CUT AT RAMAKRISHNAPURAM 2ND STREET AND VARIOUS STREETS IN DIV-135,U-31, Z-10.",Deposit Works,10,2019-20,2021-22 BR/2019-20/18209,Roads,Completed,BR-Bus Route Roads,135,410000,"RESTORATION OF OFC ROAD CUT AT UMAPATHY STREET AND VARIOUS STREETS IN DIV-135,U-31, Z-10",Deposit Works,10,2019-20,2021-22 BR/2019-20/5787,Road Cut,Completed,BR-Bus Route Roads,135,200000,"Restoration of Roadcut made by OFC Operators at Various Interior Roads in Dn-135, U-31, Zone-10",Deposit Works,10,2019-20,2019-20 NK/2019-20/10560,Buildings,Completed,NK-KODAMBAKKAM,135,933000,"PROVIDING RAIN WATER HARVESTING STRUCTURE TO ARYA GOWDA ROAD AND VARIOUS STREETS IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11313,Roads,Completed,NK-KODAMBAKKAM,135,366000,"PROVIDING SPEED BREAKER AT POSTAL COLONY 1ST STREET AND VARIOUS STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11395,Buildings,Completed,NK-KODAMBAKKAM,135,493000,"PROVIDING PVC PIPE 110MM DIA FOR AMMA KUDINNER PLANT AT BAKTHAVACHALAM STREET AND IMPROVEMENT WORK TO THE DIVISION AE OFFICE AND IMPROVEMENT WORK TO THE SWD AT GANAPATHY STREET AND VARIOUS STREETS IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11678,Roads,Completed,NK-KODAMBAKKAM,135,786000,"RELAYING OF ROAD WITH BITUMNIOUS CONCRETE 30MM THICK USING MECHANICAL PAVER FINISHING AT MANICKAM STREET IN DIV-135, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/13345,Roads,Completed,NK-KODAMBAKKAM,135,1719500,"RELAYING OF ROAD BY USING 40MM THICK BITUMINOUS CONCRETE BY MECHANICAL PAVER FINISHER AT LAKE VIEW ROAD (PART) IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13349,Roads,Completed,NK-KODAMBAKKAM,135,264000,"RELAYING OF ROAD BY USING 40MM THICK BITUMINOUS CONCRETE BY MECHANICAL PAVER FINISHER AT BAKTHAVACHALAM STREET (PART) IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13350,Roads,Completed,NK-KODAMBAKKAM,135,1500000,"RELAYING OF ROAD BY USING 40MM THICK BITUMINOUS CONCRETE BY MECHANICAL PAVER FINISHER AT THAMBAIAH ROAD (PART) IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13352,Roads,Completed,NK-KODAMBAKKAM,135,1486000,"RELAYING OF ROAD BY USING 40MM THICK BITUMINOUS CONCRETE BY MECHANICAL PAVER FINISHER AT GANAPATHY STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13355,Roads,Completed,NK-KODAMBAKKAM,135,756000,"RELAYING OF ROAD BY USING 40MM THICK BITUMINOUS CONCRETE BY MECHANICAL PAVER FINISHER AT BABU RAJENDRA PRASAD 1ST STREET (PART) IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13357,Roads,Completed,NK-KODAMBAKKAM,135,1085000,"RELAYING OF ROAD BY USING 40MM THICK BITUMINOUS CONCRETE BY MECHANICAL PAVER FINISHER AT KUPPAIAH STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13435,Roads,Completed,NK-KODAMBAKKAM,135,681000,"RELAYING OF ROAD BY USING 40MM THICK BITUMINOUS CONCRETE BY MECHANICAL PAVER FINISHER AT KRISHNAMOORTHY STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/18132,Buildings,Completed,NK-KODAMBAKKAM,135,1380000,"ADDITIONAL CONSTRUCTION OF YOGA CENTER IN EXISTING BUILDING AT BAKTHAVATCHALAM STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/18136,Buildings,Completed,NK-KODAMBAKKAM,135,1970000,"ADDITIONAL CONSTRUCTION OF CHILDREN INDOOR GAMES CENTER IN EXISTING BUILDING AT BAKTHAVATCHALAM STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/2058,Buildings,Completed,NK-KODAMBAKKAM,135,205000,"OUT SOURCING OF PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK(FROM 16.07.2019 TO 30.04.2019) AT CHENNAI PRIMARY SCHOOL AT ESWARANKOIL STREET IN DIV-135, U-31, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/3744,Buildings,Completed,NK-KODAMBAKKAM,135,1469000,"CONSTRUCTION OF MULTIPURPOSE HALL AT SUBRAMANIYAM STREET (UNDER MLA FUND) IN DIV-135,U-31,Z-10.",MLACDS,10,2019-20,2019-20 NK/2019-20/4514,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,597000,"DESILTING AND MINOR REPAIR WORK FOR THE EXISTING STORM WATER DRAIN AT BARODA STREET, MOORTHI STREET,MAHADEVAN STREET AND VARIOUS STREETS IN DIV-135,UNIT-31,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4767,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,1187000,"DESILTING AND MINOR REPAIR WORK TO THE STORM WATER DRAIN AT ARYA GOWDA ROAD, LAKE VIEW AND VARIOUS STREETS IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/5083,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,594000,"DESILTING AND MINOR REPAIR WORK FOR EXISTING STORM WATER DRAIN AT POSTAL COLONY 4TH STREET, GANAPATHY STREET AND VARIOUS STREET IN DIV-135,UNIT-31,ZONE-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7479,Subway,Completed,NK-KODAMBAKKAM,135,236000,"ENGAGING PRIVATE ELECTRICAL CUM PLUMBER (DAY AND NIGHT) FOR ESWARANKOVIL STREET MADLEY SUBWAY AND RANGARAJAPURAM TWO WHEELER SUBWAY IN DIV-134 AND 135, UNIT-31, ZONE-10",Own Sources,10,2019-20,2019-20 NK/2019-20/7569,Roads,Completed,NK-KODAMBAKKAM,135,289000,"REPAIR AND MAINTENANCE WORK FOR CPS SCHOOL AT ESWARANKOIL STREET IN DIV-135,U-31,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7920,Roads,Completed,NK-KODAMBAKKAM,135,235000,"ATTENDING PATCH WORK USING BC 30MM THICK BY PAVER FINISHER AT THAMBAIAH ROAD AND VARIOUS STREET IN DIV-135,U-31,Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/9522,Buildings,Completed,NK-KODAMBAKKAM,135,497000,"REPAIR AND MAINTENANCE WORK AMMA UNAVAGAM, (DURAISAMY SUBWAY SERVICE ROAD) AND K.V.COLONY FOOTPATH IN DIV-135,U-31,Z-10.",Own Sources,10,2019-20,2020-21 BR/2019-20/11508,Road Cut,Completed,BR-Bus Route Roads,136,306000,Restoration of Road cut Made by M/s Reliance jio at various bus route roads in zone 10 (Deposit code-57/0589/2018-19),Deposit Works,10,2019-20,2019-20 BR/2019-20/13595,Road Cut,Completed,BR-Bus Route Roads,136,528000,Restoration of Road cut Made by ACT in various bus route roads in zone 10 (Deposit code-57/0809/2018-19),Deposit Works,10,2019-20,2020-21 BR/2019-20/5189,Roads,Completed,BR-Bus Route Roads,136,2349000,Partly relaying the road with BC after cold milling by paver finisher at G N Chetty Road in Dn- 136 Zone - IX,Grants,10,2019-20,2020-21 L/2019-20/9307,Electrical,Completed,L-Electrical,136,185200,Supply of 160 nos of 1mtr curved GI single Bracket for fixing of FL Led fittings in Div 136 & 141 in zone- x area.,Own Sources,10,2019-20,2020-21 NK/2019-20/0139,Parks,Completed,NK-KODAMBAKKAM,136,99600,"Construction of Mulch pit at Panagal Park, Jeeva Park and Natesan Park in Div -136, unit-30, zone 10.",Own Sources,10,2019-20,2019-20 NK/2019-20/0239,Buildings,Completed,NK-KODAMBAKKAM,136,60000,"Providing Private Labours for Sweeping and Toilet cleaning work at Chennai Middle School at Prakasam Road in Division - 136, Unit - 30, Zone - X.(from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/10034,Buildings,Completed,NK-KODAMBAKKAM,136,390000,"Improvement Works to Prime Toilet at SomaSundaram Play Ground And Usman Road and Prakasamroad in Division -136,Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10704,Buildings,Completed,NK-KODAMBAKKAM,136,767000,"Improvement Works to Chennai Middle School at Prakasam Road in Divsion -136, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10823,Parks,Completed,NK-KODAMBAKKAM,136,1250000,"IMPROVEMENT WORKS TO THE JEEVA PARK AT G.N.CHETTY ROAD IN DIV-136,U-30,Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/11786,Roads,Completed,NK-KODAMBAKKAM,136,1933000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT VENKATESAN STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11787,Roads,Completed,NK-KODAMBAKKAM,136,885000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT MAMBALAM HIGH ROAD IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11788,Roads,Completed,NK-KODAMBAKKAM,136,893000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT RAJAMBAL STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11789,Roads,Completed,NK-KODAMBAKKAM,136,1162000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT JAGADEESWARAN STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11790,Roads,Completed,NK-KODAMBAKKAM,136,602000,"RELAYING OF ROAD WITH BT SURFACE USING PAVER FINSIH AT VYASER STREET IN DIVISION - 136,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/12690,Buildings,Completed,NK-KODAMBAKKAM,136,499000,"Improvement Works to Division Office , Jeeva Park, Amma Unavagam and Various Gcc buidings in Division-136, Unit-30, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/1551,Parks,Completed,NK-KODAMBAKKAM,136,178000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-136,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/15598,Buildings,Completed,NK-KODAMBAKKAM,136,471000,"Providing Private Labours for Sweeping and Toilet cleaning work at Chennai Middle School at Prakasam Road in Division - 136, Unit - 30, Zone - X.(from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/2492,IT Projects,Completed,NK-KODAMBAKKAM,136,412000,"Providing Private Labours for Sweeping and Toilet cleaning work at Chennai Middle School at Prakasam Road in Division - 136, Unit - 30, Zone - X.(from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2535,Buildings,Completed,NK-KODAMBAKKAM,136,373000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS IN CHENNAI PRIMARY SCHOOL PRAKASAM ROAD IN DIVISION-136,UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2874,Buildings,Completed,NK-KODAMBAKKAM,136,928000,"Improvement & Repair Works to Pondy Bazzar Shopping Complex at Thiyagaraya road in Div-136, U-30, z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/3598,Buildings,Completed,NK-KODAMBAKKAM,136,1597000,"FORMATION OF FLOORING FOR MULTI LEVEL CAR PARKING IN SIVAGNANAM STREET AT DIV -136, UNIT-30, ZONE-10",Own Sources,10,2019-20,2019-20 NK/2019-20/5640,Buildings,Completed,NK-KODAMBAKKAM,136,499000,"Additional Improvement Works to Sivagnanam Car Parking (Off Street) Div-136, U-30, Z-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5647,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,1332000,"DE-SILTING AND MINOR REPAIR WORKS OF EXISTING STROM WATER DRAIN AT BASHYAM ROAD AND ANANDHAN STREET , PRAKASAM ROAD AND VARIOUS ROAD IN DN136, UNIT-30, ZONE -X",Own Sources,10,2019-20,2019-20 NK/2019-20/5917,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,998000,"DE-SILTING AND MINOR REPAIR WORKS OF EXISTING STORM WATER DRAIN AT BAZULLA ROAD IN DN136, UNIT-30, ZONE -X",Own Sources,10,2019-20,2019-20 NK/2019-20/6341,Electrical,Completed,NK-KODAMBAKKAM,136,800000,Hiring of 6 nos LED Video Wall installation charges of size (10x8) 80x6 = 480 sq.ft for Theayagraya road Pedastrian Plaza in Div 136 Zone X for New Year and Pongal festival 2020 from 31.12.2019 to 19.01.2020 for Twenty Days .,Own Sources,10,2019-20,2020-21 NK/2019-20/6889,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,979000,"DE-SILTING AND MINOR REPAIR WORKS OF EXISTING STROM WATER DRAIN AT RAJAMANNAR STREET, RAJACHAIR STREET,MAMBALAM ROAD AND VARIOUS ROAD IN DN136, UNIT-30, ZONE -X",Own Sources,10,2019-20,2019-20 NK/2019-20/6893,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,794000,"DE-SILTING AND MINOR REPAIR WORKS OF EXISTING STROM WATER DRAIN AT RAMESHWARAM ROAD, RANGANATHAN STREET, MADLEY ROAD AND VARIOUS ROAD IN DN136, UNIT-30, ZONE -X",Own Sources,10,2019-20,2019-20 NK/2019-20/6938,Electrical,Completed,NK-KODAMBAKKAM,136,2250800,"Providing Temporary Serial set arrangement on Hire basis for Theayagraya road Pedastrian Plaza in Div 136 Zone X for New Year , Pongal festival and Republic Day 2020 from 31.12.2019 to 26.01.2020 for Twenty Seven Days .",Own Sources,10,2019-20,2020-21 NK/2019-20/7220,Buildings,Completed,NK-KODAMBAKKAM,136,740000,"Desliting and Rejuvenate the Existing well as a rain water Harevesting the Structure at panagal park, Bashyam Road in Division-136,Unit-30, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/7337,Buildings,Completed,NK-KODAMBAKKAM,136,499000,"Improvement and Repair Works on Amma Unavagam at Sivagnanam Road in Div-136, U-30, z-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/7379,Buildings,Completed,NK-KODAMBAKKAM,136,556000,"Providing Security Arrangements and Engaging private labourers for UPHC at Radha Krishnan street,T.Nagar (12Months) in Division-136, Unit-30, Zone-X",Own Sources,10,2019-20,2020-21 NK/2019-20/7959,Roads,Completed,NK-KODAMBAKKAM,136,347000,"Attending Patch work Maslilamani Street,SambaSivam Street mahalakshimi Street and Various Streets in Division-136, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/9359,Buildings,Completed,NK-KODAMBAKKAM,136,1215000,"Converting the existing well in to Rain Waater Harvesting Structure, ornamental design to well, Deepining the well & Placing well rings upto a depth of 3m De watering the Well to panagal park at Bashyam Road in Division- 136, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 BR/2019-20/13596,Road Cut,Completed,BR-Bus Route Roads,137,496000,Restoration of Road cut Made by ACT in various bus route roads in zone 10 (Deposit code-57/1136/2018-19),Deposit Works,10,2019-20,2020-21 BR/2019-20/5188,Roads,Completed,BR-Bus Route Roads,137,1174000,"Partly relaying the road with BC after cold milling by paver finisher at Anna main Road in Dn- 137, Zone - X",Grants,10,2019-20,2020-21 L/2019-20/8761,Electrical,Completed,L-Electrical,137,59600,Supply and Erection of 1 No of New Kiosk Pillar Box at 8 TH Sector 42 and 46 th street junction in div 137 in zone X Area.,Grants,10,2019-20,2020-21 L/2019-20/9258,Electrical,Completed,L-Electrical,137,173600,"Supply of 150 nos of 1mtr curved GI single Bracket for fixing of FL Led fittings in Div 129,132 , 137,127,128 & 134 in zone x area.",Own Sources,10,2019-20,2020-21 NK/2019-20/0009,Buildings,Completed,NK-KODAMBAKKAM,137,215000,"Operation and Maintenance of LPG Crematorium at Erikkarai Street in Division -137, Unit-28, Zone-10 (from 15.4.2019 to 30.6.2019)",Own Sources,10,2019-20,2019-20 NK/2019-20/0011,Buildings,Completed,NK-KODAMBAKKAM,137,118000,"Outsourcing of Private Labour for the Maintenance of Burial Ground at Erikarai Street, Nesapakkam in DN-137, Unit-28, Zone-10 (from 15.4.2019 to 30.6.2019)",Own Sources,10,2019-20,2019-20 NK/2019-20/0125,Parks,Completed,NK-KODAMBAKKAM,137,132000,"Construction of Mulch pit at Erikkarai Park, 11th, 4th, 8th & 12th sector park in Div -137, unit-28, zone 10",Own Sources,10,2019-20,2019-20 NK/2019-20/0381,Buildings,Completed,NK-KODAMBAKKAM,137,75000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School and Annexure building near play ground at Erikkarai Street in Division - 137, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/11387,Buildings,Completed,NK-KODAMBAKKAM,137,377000,"Repair works to CHSS at Erikkarai Street in Div -137, U-28, Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11522,Buildings,Completed,NK-KODAMBAKKAM,137,375000,"Repair works to CHSS (Annexure building) at Erikkarai Street in Div -137, U-28, Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11663,Roads,Completed,NK-KODAMBAKKAM,137,1031000,"Relaying of BT Road at 9th Sector - 52nd Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2020-21 NK/2019-20/11670,Roads,Completed,NK-KODAMBAKKAM,137,1122000,"Relaying of BT Road at 9th Sector - 46th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2020-21 NK/2019-20/11705,Roads,Completed,NK-KODAMBAKKAM,137,569000,"Relaying of BT Road at 8th Sector - 44th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2020-21 NK/2019-20/11713,Roads,Completed,NK-KODAMBAKKAM,137,950000,"Relaying of BT Road at 7th Sector - 38th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2020-21 NK/2019-20/11717,Roads,Completed,NK-KODAMBAKKAM,137,777000,"Relaying of BT Road at 7th Sector - 34th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2020-21 NK/2019-20/12041,Roads,Completed,NK-KODAMBAKKAM,137,3497000,"Relaying of BT Road at Khanu Nagar Main Road in Division -137, U-28, Z-10.",Grants,10,2019-20,2020-21 NK/2019-20/12223,Roads,Completed,NK-KODAMBAKKAM,137,806000,"Relaying of BT Road at Jaibalaji Nagar 1st cross street & Main Road (RC) Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2020-21 NK/2019-20/13650,Roads,Completed,NK-KODAMBAKKAM,137,914000,"Relaying of BT Road at 10th Sector - 65th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2021-22 NK/2019-20/13727,Roads,Completed,NK-KODAMBAKKAM,137,1765000,"Relaying of BT Road at 11th Sector - 69th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2021-22 NK/2019-20/13735,Roads,Completed,NK-KODAMBAKKAM,137,1469000,"Relaying of BT Road at 8th Sector - 39th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2021-22 NK/2019-20/13736,Roads,Completed,NK-KODAMBAKKAM,137,693000,"Relaying of BT Road at 8th Sector - 45th Street in Division -137, U-28, Z-10.",Grants,10,2019-20,2021-22 NK/2019-20/1518,Roads,Completed,NK-KODAMBAKKAM,137,168000,"Improvement works to center median at Arcot Road in Div-137, U-28, Z-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/15366,Buildings,Completed,NK-KODAMBAKKAM,137,214000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS TO ANGANWADI CENTER AT ANNA VEETHI 1ST STREET IN DIV-137, U-28, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/15440,Buildings,Completed,NK-KODAMBAKKAM,137,285000,"IMPROVEMENT WORKS TO UPHC AT ERIKKARAI STREET IN DIV-137, U-28, Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/15629,Buildings,Completed,NK-KODAMBAKKAM,137,589300,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Kamaraj Street and Annexure building at Sankaralinganar Steet (01.06.2020 to 30.4.2021) in Division - 137, Unit - 28, Zone - X",Own Sources,10,2019-20,2021-22 NK/2019-20/15630,Buildings,Completed,NK-KODAMBAKKAM,137,589300,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School and Annexure building near play ground at Erikkarai Street in Division - 137, Unit - 28, Zone - X (01.6.2020 to 30.4.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/1626,Buildings,Completed,NK-KODAMBAKKAM,137,303000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-137,UNIT-28,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2209,Buildings,Completed,NK-KODAMBAKKAM,137,930000,"Operation and Maintenance of LPG Crematorium at Erikkarai Street in Division -137, Unit-28, Zone-10 (from 1.7.2019 to 31.3.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2211,Buildings,Completed,NK-KODAMBAKKAM,137,536000,"Outsourcing of Private Labour for the Maintenance of Burial Ground at Erikarai Street, Nesapakkam in DN-137, Unit-28, Zone-10 (from 1.7.2019 to 31.3.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2377,Buildings,Completed,NK-KODAMBAKKAM,137,514000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School and Annexure building near play ground at Erikkarai Street in Division - 137, Unit - 28, Zone - X (from 16.7.2019 to 30.4.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2379,Buildings,Completed,NK-KODAMBAKKAM,137,514000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Kamaraj Street and Annexure building at Sankaralinganar Street (16.7.2019 to 30.4.2020) in Division - 137, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/3108,Buildings,Completed,NK-KODAMBAKKAM,137,354000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS TO CMS SCHOOL AT KAMARAJAR STREET AND IN ANNEXURE BUILDING AT SANKARALINGANAR STREET IN DIV-137, U-28, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/4510,Buildings,Completed,NK-KODAMBAKKAM,137,377000,"Maintenance and repair to GCC buildings such as Anganwadi , office buildings, footpath, etc., in Div-137, U-28, Z-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5615,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,1438000,"Desilting and Repairs to SWD at Alagirisamy Salai, Arcot Road, Munusamy Salai and Various streets in division-137, Unit-28, Zone-10",Own Sources,10,2019-20,2019-20 NK/2019-20/5717,Parks,Completed,NK-KODAMBAKKAM,137,798000,"Maintenance of Park ( for one year) at 4th Sector, K.K. Nagar in Dn-137, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/5718,Parks,Completed,NK-KODAMBAKKAM,137,599000,"Estimate for Maintenance of Park ( for one year) at 8th Sector, K.K. Nagar in Dn-137, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/5719,Parks,Completed,NK-KODAMBAKKAM,137,683000,"Estimate for Maintenance Estimate for Park Cum Play Ground ( for one year) at Erikkarai Street, Nesapakkam in Dn-137, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/5720,Parks,Completed,NK-KODAMBAKKAM,137,968000,"Estimate for Maintenance of Park ( for one year) at 11th Sector, K.K. Nagar in Dn-137, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/5721,Parks,Completed,NK-KODAMBAKKAM,137,657000,"Estimate for Maintenance of Park ( for one year) at 12th Sector, K.K. Nagar in Dn-137, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/5722,Parks,Completed,NK-KODAMBAKKAM,137,1172000,"Estimate for Maintenance of Park ( for one year) at Erikkarai Street, Nesapakkam in Dn-137, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7268,Buildings,Completed,NK-KODAMBAKKAM,137,556000,"Providing Security Arrangements and Engaging private labourers for UPHC at Erikkarai Street, Nesapakkam (12 Months) in Division - 137, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/7950,Roads,Completed,NK-KODAMBAKKAM,137,123000,"BT ROAD PATCH WORK AT 65TH STREET AND VARIOUS STREETS IN DN137, UNIT-28, ZONE -X",Own Sources,10,2019-20,2021-22 NK/2019-20/7952,Roads,Completed,NK-KODAMBAKKAM,137,284000,"CC ROAD PATCH WORK AT NSC BOSE STREET, VOC STREET, MOOGAMBIGAI STREET AND 73RD STREET IN DN137, UNIT-28, ZONE -X",Own Sources,10,2019-20,2021-22 NK/2019-20/9019,Buildings,Completed,NK-KODAMBAKKAM,137,285000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT 10TH SECTOR 61ST STREET AND ANNA MAIN ROAD IN DIVISION-137, U-28, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/9646,Buildings,Completed,NK-KODAMBAKKAM,137,119000,"Maintenance and repair to GCC buildings such as Anganwadi , Public Convenience, etc., in Div-137, U-28, Z-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/9673,Buildings,Completed,NK-KODAMBAKKAM,137,230000,"Providing Wire fencing at Anna main Road in division-137, Unit-28, Zone-10",Own Sources,10,2019-20,2020-21 BR/2019-20/4329,Road Cut,Completed,BR-Bus Route Roads,138,2400000,"Restroration of roadcut made by TANGEDCO at Ashok Pillar road in Dn-138,Zone 10(Jn from P.T Rajan Salai to 100 ft road )",Deposit Works,10,2019-20,2019-20 BR/2019-20/4339,Roads,Completed,BR-Bus Route Roads,138,900000,"Restroration of Roadcut made by TANGEDCO at Anna Main Road from the Jn of EB Office to the Jn of P.T Rajan Salai in Dn-138,Zone -10",Deposit Works,10,2019-20,2019-20 BR/2019-20/6347,Roads,Completed,BR-Bus Route Roads,138,2323000,Restoration of Roadcut made by CMWSSB @ Ashok Pillar road and P.T. Rajan salai in Dn-138 Zone -10,Deposit Works,10,2019-20,2020-21 BR/2019-20/6360,Roads,Completed,BR-Bus Route Roads,138,2619000,"Restoration of Roadcut made by CMWSSB @ P.T. Rajan salai in Dn - 138 , Zone -10",Deposit Works,10,2019-20,2019-20 NK/2019-20/0083,Buildings,Completed,NK-KODAMBAKKAM,138,293000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITER/HOUR CAPACITY FOR 3 MONTHS PERIOD AT 60 FEET ROAD JUNCTION, K.K.NAGAR IN DIV-138, UNIT-29, ZONE-10",Own Sources,10,2019-20,2019-20 NK/2019-20/0276,Parks,Completed,NK-KODAMBAKKAM,138,56500,"Construction of Mulch pit at Bharathidasan Colony 5th Street Park and Bharathidasan Colony 6th Street Park in Div -138, Unit-28, Zone 10",Own Sources,10,2019-20,2019-20 NK/2019-20/0378,Buildings,Completed,NK-KODAMBAKKAM,138,45000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Govindaswamy Street (1 year) in Division - 138, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0379,Buildings,Completed,NK-KODAMBAKKAM,138,93000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Govt. Higher Secondary School at Anna main road, MGR Nagar (1 year ) in Division - 138, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0380,Buildings,Completed,NK-KODAMBAKKAM,138,60000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at Govindasamy street, MGR Nagar (1 year) in Division - 138, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/13096,Roads,Completed,NK-KODAMBAKKAM,138,1361000,"RELAYING THE ROAD WITH DBM AND BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT THIRUVALLUVAR STREET (MGR NAGAR) IN DN-138, U-28, Z-10",Grants,10,2019-20,2020-21 NK/2019-20/13097,Roads,Completed,NK-KODAMBAKKAM,138,1691000,"RELAYING THE ROAD WITH DBM AND BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT ANNAL GANDHI STREET (MGR NAGAR) IN DN-138, U-28, Z-10",Grants,10,2019-20,2020-21 NK/2019-20/13098,Roads,Completed,NK-KODAMBAKKAM,138,831000,"RELAYING THE ROAD WITH DBM AND BC AFTER COLD MILLING BY PAVER FINISHER USING PLASTIC WASTE ALONG WITH TRAFFIC IMPROVEMENT WORK AT KATTABOMMAN STREET (MGR NAGAR) IN DN-138, U-28, Z-10",Grants,10,2019-20,2020-21 NK/2019-20/14394,Roads,Completed,NK-KODAMBAKKAM,138,969000,"Laying of Cement Concrete Road at MGR Nagar Neithal Street in Div-138, Unit-28, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/14407,Roads,Completed,NK-KODAMBAKKAM,138,1259000,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at Thiru Nagar- Valluvar Street in Division -138, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/14408,Roads,Completed,NK-KODAMBAKKAM,138,441000,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at Thiru Nagar - Kambar Street in Division -138, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/14410,Roads,Completed,NK-KODAMBAKKAM,138,201000,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at Thiru Nagar - Thilagar Street in Division -138, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/14411,Roads,Completed,NK-KODAMBAKKAM,138,176000,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at Thiru Nagar - Nakkeran Street in Division -138, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/1611,Parks,Completed,NK-KODAMBAKKAM,138,145000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-138,UNIT-28,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/16837,Buildings,Completed,NK-KODAMBAKKAM,138,276000,"MAINTANANCE AND REPAIR WORKS TO THE GCC BUILDINGS SUCH AS PLAY GROUNDS, PLAYFIELDS, PARKS & ETC., AT VARIOUS LOCATIONS IN DN-138, U-28, Z-10",Own Sources,10,2019-20,2020-21 NK/2019-20/1898,Footpath,Completed,NK-KODAMBAKKAM,138,426000,"Demolition and reconstruction of handrail & Center Median at Anna Main road in div-138,U-28, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/1901,Footpath,Completed,NK-KODAMBAKKAM,138,349000,"Demolition and reconstruction of handrail & Center median at Ashok Pillar Salai in Division-138, Unit-28, Zone -10",Own Sources,10,2019-20,2019-20 NK/2019-20/2294,Buildings,Completed,NK-KODAMBAKKAM,138,1035000,"Operation and Maintenance for 3rd Year of High Quality Treated Drinking Water Plant (RO/UV Filtration) at Anna Main Road 60 feet junction, KK Nagar in Dn-138, Unit-28, Zone-10 (07.07.2019 to 04.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2338,Buildings,Completed,NK-KODAMBAKKAM,138,260000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT PUBLIC CONVENIENCE, AMBADKAR COLONY 100 FEET ROAD IN DIV-138, U-28, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/2394,Buildings,Completed,NK-KODAMBAKKAM,138,308000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Govindaswamy Street (16.7.2019 to 30.4.2020 ) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/2395,Buildings,Completed,NK-KODAMBAKKAM,138,762000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Govt. Higher Secondary School at Anna Main Road, MGR Nagar (16.7.2019 to 30.4.2020) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/2396,Buildings,Completed,NK-KODAMBAKKAM,138,412000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at Govindasamy street, MGR Nagar (16.7.2019 to 30.4.2020) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/2554,Buildings,Completed,NK-KODAMBAKKAM,138,166000,"Repair and Maintenance of ICDS Centre at Zahir hussain street in div-138, unit-28, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2588,Buildings,Completed,NK-KODAMBAKKAM,138,183000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS CHENNAI PRIMARY SCHOOL AT GOVINDASWAY STREET IN DIV-138, U-28, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/5263,Buildings,Completed,NK-KODAMBAKKAM,138,242000,"Maintanance and Repairs works to the GCC Buildings such as Amma Unavagam, School Buildings, Division Office and Public Convenience at Various Locations in Division -138, Unit-28, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5266,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,1178000,"Desilting work and minor repair works to the existing Strom Water Drains at Govindasamy Road, Anna Main Road, pillayar Koil Street and Various streets in division-138, Unit-28, Zone-10",Own Sources,10,2019-20,2019-20 NK/2019-20/5949,Parks,Completed,NK-KODAMBAKKAM,138,311000,"BT Patch work at various street in div 138, unit-28, zone 10",Own Sources,10,2019-20,2021-22 NK/2019-20/6467,Roads,Completed,NK-KODAMBAKKAM,138,821000,"ANNUAL MAINTENANCE AT BHARATHIDASAN COLONY 6TH STREET PARK IN DIV-138,U-28,Z-10.(AREA:2513SQ.M)",Own Sources,10,2019-20,2020-21 NK/2019-20/6468,Roads,Completed,NK-KODAMBAKKAM,138,251000,"Maintanance and Repairs works to the GCC Buildings such as Anganwadi, Amma Kudineer and Fencing Works etc..at Various Streets in Division -138, Unit-28, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/7147,Footpath,Completed,NK-KODAMBAKKAM,138,581000,"ANNUAL MAINTENANCE AT BHARATHIDASAN COLONY 5TH STREET PARK IN DIV-138,U-28,Z-10.(AREA:830SQ.M)",Own Sources,10,2019-20,2020-21 NK/2019-20/7272,Buildings,Completed,NK-KODAMBAKKAM,138,555300,"Providing Security Arrangements and Engaging private labourers for NHUM at Jafferkanpet Hospital at Ayyavoo Street (12 Months) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/9797,Buildings,Completed,NK-KODAMBAKKAM,138,217000,"Maintanance and repairs to GCC Buildings such as Division office, Schools, ICDS Center and Amma Unavagam in etc.. at Various Locations in Division-138, Unit-28, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/0010,Buildings,Completed,NK-KODAMBAKKAM,139,161000,"OPERATION AND MAINTENANCE OF LPG CREMATORIUM AT WEST JONES ROAD IN DIVISION -139,UNIT - 28, ZONE- 10 (FOR 2 MONTHS 15 DAYS ONLY) (01.04.2019 to 15.06.2019)",Own Sources,10,2019-20,2019-20 NK/2019-20/0104,Buildings,Completed,NK-KODAMBAKKAM,139,540500,"Operation and Maintenance For 4th Year Operation of High Quality Treated Drinking Water Plant (RO/UV Filtration) For 1 Year Period (Amma Kudineer) at RR Colony Third Street, RRcolony, in Dn-139, Unit-28, Zone-10",Own Sources,10,2019-20,2021-22 NK/2019-20/0270,Buildings,Completed,NK-KODAMBAKKAM,139,31400,"Construction of Mulch pit in Burial Ground at West Saidapet in Div -139, Unit-28, Zone 10",Own Sources,10,2019-20,2019-20 NK/2019-20/0375,Buildings,Completed,NK-KODAMBAKKAM,139,60000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai High School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0376,Buildings,Completed,NK-KODAMBAKKAM,139,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0377,Buildings,Completed,NK-KODAMBAKKAM,139,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School Street in Division - 139, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0382,Buildings,Completed,NK-KODAMBAKKAM,139,75000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Kamaraj Street and Annexure building at Sankaralinganar Steet in Division - 137, Unit - 28, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/10318,Buildings,Completed,NK-KODAMBAKKAM,139,143000,"Maintenance and repair to GCC buildings such as School Buildings, Anganwadi, etc., in Div-139, U-28, Z-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/10837,Buildings,Completed,NK-KODAMBAKKAM,139,790000,"Repair and Maintenance works to the UPHC at R.R.Colony Second Link Street in Division-139, Unit-28, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10838,Buildings,Completed,NK-KODAMBAKKAM,139,472000,"Repair and Maintenance work of Corporation Buildings at various streets in dn 139, Unit-28, Zone 10",Own Sources,10,2019-20,2020-21 NK/2019-20/13516,Roads,Completed,NK-KODAMBAKKAM,139,478900,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at Janakiraman St in Division -139, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/13520,Roads,Completed,NK-KODAMBAKKAM,139,258000,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at New Colony 4th cross Street in Division -139, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/13521,Roads,Completed,NK-KODAMBAKKAM,139,2139900,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at RR Colony East Street in Division -139, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/13522,Roads,Completed,NK-KODAMBAKKAM,139,264800,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at BK Maistry cross Street in Division -139, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/13523,Roads,Completed,NK-KODAMBAKKAM,139,189200,"Relaying the road with Bituminous Concrete road after cold milling by paver finisher at Subramani Street in Division -139, U-28, Z-10.",Own Sources,10,2019-20,2021-22 NK/2019-20/14864,Roads,Completed,NK-KODAMBAKKAM,139,565000,"Relaying the CC Road along with traffic improvement work at Subramanian Street in Division 139, Unit-28, Zone -10",Own Sources,10,2019-20,2020-21 NK/2019-20/1617,Parks,Completed,NK-KODAMBAKKAM,139,72000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-139,UNIT-28,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2243,Buildings,Completed,NK-KODAMBAKKAM,139,1407000,"OPERATION AND MAINTENANCE OF LPG CREMATORIUM AT WEST JONES ROAD IN DIVISION -139,UNIT - 28, ZONE- 10 FOR A PERIOD FROM 16.06.2019 to 31.03.2020",Own Sources,10,2019-20,2020-21 NK/2019-20/2380,Buildings,Completed,NK-KODAMBAKKAM,139,412000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai High School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from (16.7.2019 to 30.4.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2382,Buildings,Completed,NK-KODAMBAKKAM,139,206000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from 16.7.2019 to 30.4.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2383,Buildings,Completed,NK-KODAMBAKKAM,139,206000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School Street (16.7.2019 to 30.4.2020 ) in Division - 139, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/2830,Buildings,Completed,NK-KODAMBAKKAM,139,311000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT CPS JAFFERKANPET IN DIV-139, U-28, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/2840,Buildings,Completed,NK-KODAMBAKKAM,139,311000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT CPS, SCHOOL STREET IN DIV-139, U-28, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3754,Parks,Completed,NK-KODAMBAKKAM,139,495000,"Maintanance and Repairs to GCC Buildings such as Anganwadi,Amma Unavagam and Division office campus buildings at Various locations etc..in Division-140, Unit-30, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/5560,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,354000,"Maintenance and Repair work to GCC Buildings such as Burial Ground, Composting Yard, Public Convenience etc.. In Division-139, Unit-28, Zone-10",Own Sources,10,2019-20,2019-20 NK/2019-20/5567,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,1424000,"DESILTING & MINOR REPAIR WORKS OF SWD AT ARUMUGAM STREET, WEST JONES ROAD AND VARIOUS STREETS IN DN139, UNIT-28, ZONE -X",Own Sources,10,2019-20,2019-20 NK/2019-20/5774,Parks,Completed,NK-KODAMBAKKAM,139,228000,"Annual Maintenance for Park at Jafferkhanpet Main Road, in Dn-139, Unit- 28, Zone-10 Area - 500 sqm",Own Sources,10,2019-20,2020-21 NK/2019-20/7281,Buildings,Completed,NK-KODAMBAKKAM,139,556000,"Providing Security Arrangements and Engaging private labourers for UPHC at RR Colony 2nd Link Street (12 Months) in Division - 139, Unit - 28, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/7933,Buildings,Completed,NK-KODAMBAKKAM,139,1000000,"CONSTRUCTION OF MULTIPURPOSE HALL (RATION SHOP) AT APPADURAI STREET IN DIVISION-139,UNIT-28, ZONE-10. (UNDER 2017-18 - SAIDAPET MLA FUND)",MLACDS,10,2019-20,2020-21 NK/2019-20/9516,Buildings,Completed,NK-KODAMBAKKAM,139,398000,"Repair works to the Amma Unavagam at R.R.Colony 2nd Street & Gangaiamman Koil Street in Division-139, Unit-28, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/0106,Buildings,Completed,NK-KODAMBAKKAM,140,540500,"Operation and Maintenance For 4th Year Operation of High Quality Treated Drinking Water Plant (RO/UV Filtration) For 1 Year Period (Amma Kudineer) at Kodambakkam Road, in Dn-140, Unit-30, Zone-10",Own Sources,10,2019-20,2021-22 NK/2019-20/0252,Buildings,Completed,NK-KODAMBAKKAM,140,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Vandikkaran Street in Division - 140, Unit - 30, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0253,Buildings,Completed,NK-KODAMBAKKAM,140,59700,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai High School at K.R Kovil Street, West Mambalam in Division - 140, Unit - 30, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0254,Buildings,Completed,NK-KODAMBAKKAM,140,45000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Perumal Kovil Street, Mettupalayam in Division - 140, Unit - 30, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0259,Buildings,Completed,NK-KODAMBAKKAM,140,90000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Boy's Higher Secondary School at Kodambakkam Road in Division - 140, Unit - 30, Zone - X (from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0272,Parks,Completed,NK-KODAMBAKKAM,140,56600,"Construction of Mulch pit at Amma Park and Elaiamman Koil Street Park in Div -140, Unit-30, Zone 10",Own Sources,10,2019-20,2019-20 NK/2019-20/10696,Buildings,Completed,NK-KODAMBAKKAM,140,996000,"Repair work for water supply and Electrical Arrangements of Toilet Rooms to Chennai Middle School at Vandikaran Street Division-140, unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10839,Buildings,Completed,NK-KODAMBAKKAM,140,489000,"Maintenance and Repair works to GCC Buildings such as Public Convenience ,Schools, Anganwadi, Parks & Division Office etc at Various Locations in Division-140, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13372,Roads,Completed,NK-KODAMBAKKAM,140,716000,"Relayiing the road with Bituminous Concrete Road after cold milling by paver finisher at new street in Division-140, U-30,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13373,Roads,Completed,NK-KODAMBAKKAM,140,606000,"Relaying the road with Bituminous Concrete Road after cold milling by paver finisher at Kasikulam in Division-140, u-30,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/13374,Roads,Completed,NK-KODAMBAKKAM,140,768000,"Relaying the Road with Bituminous Concrete road after cold milling by paver finisher at lake view road in division-140 U-30,Z-10",Own Sources,10,2019-20,2021-22 NK/2019-20/15606,Buildings,Completed,NK-KODAMBAKKAM,140,707000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Boys Higher Secondary School at Kodambakkam Road in Division - 140, Unit-30,Zone-X(from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2020-21 NK/2019-20/15607,Buildings,Completed,NK-KODAMBAKKAM,140,353600,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Perumal Koil Street in Division - 140, Unit-30,Zone-X(from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2020-21 NK/2019-20/15608,Buildings,Completed,NK-KODAMBAKKAM,140,471500,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher SecondarySchool at KRKoil Street in Division - 140, Unit-30,Zone-X(from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2020-21 NK/2019-20/15609,Buildings,Completed,NK-KODAMBAKKAM,140,235700,"Providing private lobourers for sweeping and Toillet cleaning work at Chennai Primary School at Vandikaran Street in Division--140,Unit-30,Zone-X(from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2020-21 NK/2019-20/1604,Parks,Completed,NK-KODAMBAKKAM,140,109000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-140,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2493,Buildings,Completed,NK-KODAMBAKKAM,140,412000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at KR Koil Street in Division - 140, Unit - 30, Zone - X (from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2494,Buildings,Completed,NK-KODAMBAKKAM,140,309000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Perumal Kovil Street in Division - 140 Unit - 30, Zone - X (from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2495,Buildings,Completed,NK-KODAMBAKKAM,140,206000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Vandikaran Street in Division - 140, Unit - 30, Zone - X (from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2496,Buildings,Completed,NK-KODAMBAKKAM,140,617000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Boy's Higher Secondary School at Kodambakkam Road in Division - 140, Unit - 30, Zone - X (from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2593,Buildings,Completed,NK-KODAMBAKKAM,140,200000,"REPAIR AND IMPROVEMENTS WORK TO THE ANGANWADI ( 33603100109) AT NEW STREET IN DIVISION - 140 , UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2615,Buildings,Completed,NK-KODAMBAKKAM,140,200000,"REPAIR AND IMPROVEMENTS WORK TO THE ANGANWADI ( 33603100110) AT NEW STREET IN DIVISION - 140 , UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/3098,Buildings,Completed,NK-KODAMBAKKAM,140,363000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS IN CMS AT SCHOOL ROAD, METTUPALAYAM IN DIV-140, U-30, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/3099,Buildings,Completed,NK-KODAMBAKKAM,140,363000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS IN CHSS AT K.R.KOIL STREET IN DIV-140, U-30, Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/5399,Buildings,Completed,NK-KODAMBAKKAM,140,914000,"REPAIR WORKS TO THE CHENNAI MIDDLE SCHOOL B BLOCK AT METTUPALAYAM IN DN-140,U-30,Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/5400,Buildings,Completed,NK-KODAMBAKKAM,140,750000,"REPAIR WORKS TO THE CHENNAI MIDDLE SCHOOL A BLOCK & UNINAL BLOCK AT METTUPALAYAM IN DIV-140, UNIT-30, ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/5548,Buildings,Completed,NK-KODAMBAKKAM,140,441000,"REPAIR WORKS TO THE CHENNAI HIGHER SECONDARY SCHOOL B BLOCK AT K.R.KOIL STREET IN DIVISION -140, UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5559,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,1445000,"DESILTING & MINOR REPAIR WORKS TO THE EXISTING STORM WATER DRAIN AT GOVINDAN ROAD AND VARIOUS STREETS IN DIVISION-140, UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5777,Parks,Completed,NK-KODAMBAKKAM,140,702000,"ANNUAL MAINTENANCE FOR AMMA PARK AT KODAMBAKKAM ROAD IN DIVISION 140, UNIT-30, ZONE 10 (AREA- 2250SQM)",Own Sources,10,2019-20,2020-21 NK/2019-20/5778,Parks,Completed,NK-KODAMBAKKAM,140,646000,"ANNUAL MAINTENANCE FOR PARK AT ELLAIAMMAN KOVIL STREET IN DIVISION 140, UNIT-30, ZONE 10 AREA - 375 SQM",Own Sources,10,2019-20,2020-21 NK/2019-20/6162,Buildings,Completed,NK-KODAMBAKKAM,140,1569000,"Repair works and electrical works to the UPHC Health Post of Ground Floor & First Floor at Govindan Road in Division-140, unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7377,Buildings,Completed,NK-KODAMBAKKAM,140,556000,"Providing Security Arrangements and Engaging private labourers for UPHC at Govindan Road (12 Months) in Division - 140, Unit - 30, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/7954,Roads,Completed,NK-KODAMBAKKAM,140,353000,"Attending patch work at Kasikulam, New Street, KR Kovil Street and various streets in dn140, unit-30, zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/8540,Parks,Completed,NK-KODAMBAKKAM,140,389000,"Repair works to the Childrens Playfield at New Street in Division-140, unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/8787,Buildings,Completed,NK-KODAMBAKKAM,140,724000,"Repair works to the Students Dining Hall in Chennai Boys Higher Secondary School at Kodambakkam Road at in Division-140, unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 P/2019-20/7400,Parks,Completed,P-Parks and Playfields,140,1430000,"CONSTRUCTION OF BASKET BALL COURT AT CHENNAI BOYS HIGHER SECONDARY SCHOOL, SAIDAPET IN DN -140, ZONE - 10",Grants,10,2019-20,2020-21 BR/2019-20/5190,Roads,Completed,BR-Bus Route Roads,141,881000,"Partly relaying the road with BC after cold milling by paver finisher at Burkit Road in Dn- 141, Zone - X",Grants,10,2019-20,2020-21 L/2019-20/8767,Electrical,Completed,L-Electrical,141,1919200,Replacement of 3670 mtrs of 2x25 sq mm cable at various location in Division 136 & 141 under Zone-10,Grants,10,2019-20,2020-21 L/2019-20/8769,Electrical,Completed,L-Electrical,141,4835200,Supply and Replacement of Damaged 129 Nos of Lamp post at Various places in div 136 and 141 in zone X Area.,Grants,10,2019-20,2021-22 NK/2019-20/0084,Buildings,Completed,NK-KODAMBAKKAM,141,1288000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITERS / HOUR CAPACITY FOR (AMMA KUDINEER) CIT NAGAR 4TH MAIN ROAD ,DIV-141,U-30,Z-10 (4TH YEAR MAINTENANCE)",Own Sources,10,2019-20,2019-20 NK/2019-20/0085,Buildings,Completed,NK-KODAMBAKKAM,141,266000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (AMMA KUDINEER) AT MUTHURANGAN SALAI (FROM 04.03.2019 TO 15.06.2019) IN DN-141,U-30,Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/0140,Parks,Completed,NK-KODAMBAKKAM,141,79500,"Construction of Mulch pit at CIT Nagar 3rd Main road Park in Div -141, unit-30, zone 10.",Own Sources,10,2019-20,2019-20 NK/2019-20/0385,Bridges,Completed,NK-KODAMBAKKAM,141,75000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai Higher Secondary School and Chennai Primary School at C.I.T Nagar 4th Main Road in Div -141, U-30, Z-10.(from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2019-20 NK/2019-20/0386,Parks,Completed,NK-KODAMBAKKAM,141,45000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai HighSchool and Chennai Primary School at New Boag Road (Kannamapet) in Div -141, U-30, Z-10.(from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2019-20 NK/2019-20/10771,Buildings,Completed,NK-KODAMBAKKAM,141,996000,"Proposed Elevation work for the main entrance of Cummunity hall at CIT Nagar 3rd Main Road in Division- 141, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11255,Buildings,Completed,NK-KODAMBAKKAM,141,296000,"Improvement Work to CIT Nagar 4th Main Road Hiher Secondary School in Division- 141, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11334,Buildings,Completed,NK-KODAMBAKKAM,141,434000,"Improvement Work to CIT Nagar Park at CIT Nagar 3rd Main Road in Division- 141, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11336,Buildings,Completed,NK-KODAMBAKKAM,141,475000,"Improvement Work to CIT Nagar Cummunity Hall at CIT Nagar 3rd Main Road in Division- 141, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/11838,Buildings,Completed,NK-KODAMBAKKAM,141,499000,"Improvement and Maintenance Work of Kannammapettai Burial Ground and Various location in Division -141, Unit-30, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/12897,Parks,Completed,NK-KODAMBAKKAM,141,2688000,"Providing the Stainless Steel Hand Rail in CIT Nagar Park at CIT Nagar 3rd Main Road in Division -141, Unit-30., Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13432,Parks,Completed,NK-KODAMBAKKAM,141,202000,"Improvement works to Road side park at CIT Nagar 5th Main Road in Division- 141, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/13504,Buildings,Completed,NK-KODAMBAKKAM,141,714000,"Improvement works to Chennai High School at New Boag Road in Division -141, Unit-30, zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/14868,Buildings,Completed,NK-KODAMBAKKAM,141,2790000,"Proposed Construction of First Floor for Urban Primary Health Centre at CIT Nagar 4th Main Road in Division-141, Unit -30, Zone - 10.",Own Sources,10,2019-20,2020-21 NK/2019-20/15442,Buildings,Completed,NK-KODAMBAKKAM,141,2043000,"Proposed Construction First Floor Building in Ayush Hospital at South Usman Road in Division-141, Unit -30, Zone - 10.",Own Sources,10,2019-20,2020-21 NK/2019-20/1553,Parks,Completed,NK-KODAMBAKKAM,141,145000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOST PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DN-141,U-30,Z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/1558,Buildings,Completed,NK-KODAMBAKKAM,141,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT KANNAMAPETAI BURIAL GROUND IN DIVISION -141, UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/15594,Buildings,Completed,NK-KODAMBAKKAM,141,290000,"Repair work for Amma Unavagam at South Usman Road in division 141, Unit-30, Zone-10",Own Sources,10,2019-20,2020-21 NK/2019-20/15596,Buildings,Completed,NK-KODAMBAKKAM,141,354000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai High School and Chennai Primary School at New Boag Road (Kannamapet) in Div -141, U-30, Z-10.(from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/15597,Buildings,Completed,NK-KODAMBAKKAM,141,589000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai Higher Secondary School and Chennai Primary School at C.I.T Nagar 4th Main Road in Div -141, U-30, Z-10.(from 01.06.2020 to 30.04.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/2255,IT Projects,Completed,NK-KODAMBAKKAM,141,919000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) MUTHURANGANSALAI,KANNAMMAPETTAI (FOR 9 MONTHS(16.06.2019-28.02.2020)),DIV-141,U-30,Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/2498,Buildings,Completed,NK-KODAMBAKKAM,141,311000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai HighSchool and Chennai Primary School at New Boag Road (Kannamapet) in Div -141, U-30, Z-10.(from 16.07.2019 to 30.04.2020).",Own Sources,10,2019-20,2020-21 NK/2019-20/2499,Buildings,Completed,NK-KODAMBAKKAM,141,513000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai Higher Secondary School and Chennai Primary School at C.I.T Nagar 4th Main Road in Div -141, U-30, Z-10 (from 16.07.2019 to 30.04.2020).",Own Sources,10,2019-20,2020-21 NK/2019-20/2523,Buildings,Completed,NK-KODAMBAKKAM,141,199000,"Improvement Works on Cit Nagar 4th Main Road Anganvadi ( AWC No.33603080313) in Cit Nagar ad Div-141, U-30, z-10",Own Sources,10,2019-20,2019-20 NK/2019-20/2536,Buildings,Completed,NK-KODAMBAKKAM,141,200000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS IN CHENNAI PRIMARY SCHOOL AT NEW BOAG ROAD (KANNAMMAPETTAI) IN DIVISION-141,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2538,Buildings,Completed,NK-KODAMBAKKAM,141,165000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT CHENNAI HR.SEC SCHOOL CIT NAGAR 4TH MAIN ROAD IN DIVISION-141,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5649,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,1482000,"DE-SILTING AND MINOR REPAIR WORKS OF EXISTING STROM WATER DRAIN AT NEW BOAG ROAD, CIT NAGAR 4TH MAIN ROAD POLICE QUARTERS ROAD AND VARIOUS ROAD IN DN-141, UNIT-30, ZONE -X",Own Sources,10,2019-20,2019-20 NK/2019-20/6132,Buildings,Completed,NK-KODAMBAKKAM,141,597000,"Improvement Works at kannammapettai Burial Ground in New Boag Road in Div-141, U-30, Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/6894,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,952000,"DE-SILTING AND MINOR REPAIR WORKS OF EXISTING STROM WATER DRAIN AT SOUTH DANDAPANI STREET,CANAL BANK ROAD, DEVARAJ STREET AND VARIOUS ROAD IN DN-141, UNIT-30, ZONE -X",Own Sources,10,2019-20,2020-21 NK/2019-20/7262,Buildings,Completed,NK-KODAMBAKKAM,141,230000,"Improvement Work for Kamarajar Colony Anganvadi at Kamarajar Colony in Division-141,Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7381,Buildings,Completed,NK-KODAMBAKKAM,141,556000,"Providing Security Arrangements and Engaging Private labourers for UPHC at South Usman Road (12 Months) in Division - 141, Unit - 30, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/7382,Buildings,Completed,NK-KODAMBAKKAM,141,407000,"Providing Security Arrangements and Engaging private labourers for UPHC at CIT Nagar 4th main road (12 Months) in Division - 141, Unit - 30, Zone - X",Own Sources,10,2019-20,2020-21 NK/2019-20/7960,Roads,Completed,NK-KODAMBAKKAM,141,173000,"Attending Patch work South Dandapani street,South West Boag road, Mooparappan Street and Various Streets in Division-141, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7998,Buildings,Completed,NK-KODAMBAKKAM,141,414000,"Providing I-Section Barricade Both sides at Model House Road in Division-141, unit-30,zone-10",Own Sources,10,2019-20,2019-20 NK/2019-20/8418,Buildings,Completed,NK-KODAMBAKKAM,141,793000,"Proposed Repair and Strengthing at Fish Market CIT Nagar 4th Main Road in Division-141, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/8881,Footpath,Completed,NK-KODAMBAKKAM,141,135000,"Improvement & Repair Works to Muthurangan salai footpath at muthurangan salai in Div-141 U-30, Z-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/9110,Buildings,Completed,NK-KODAMBAKKAM,141,465000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation,Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. at kannammapettai burial Ground in Division 141 Unit - 30, Zone - 10.",Own Sources,10,2019-20,2019-20 J/2019-20/8320,Bridges,Completed,J-Bridges,142,610000,PROVIDING THE TILING FOR THE FOOTPATH OF EXISTING ALANDUR BRIDGE ACROSS ADYAR RIVER IN DIV-142 ZONE-10,Own Sources,10,2019-20,2019-20 L/2019-20/8764,Electrical,Completed,L-Electrical,142,2742100,"Supply and Replacement of Damaged 77 Nos of Lamp post at Various places in div 140,142, in zone X Area.",Grants,10,2019-20,2020-21 L/2019-20/8765,Electrical,Completed,L-Electrical,142,2155900,Replacement of 4174 mtrs of 2x25 sq mm cable at various location in Division 140 & 142 under Zone-10,Grants,10,2019-20,2021-22 NK/2019-20/0275,Parks,Completed,NK-KODAMBAKKAM,142,31400,"Construction of Mulch pit in Park at West Jones Road (Sunshine Appartment) in Div -142, Unit-30, Zone 10",Own Sources,10,2019-20,2019-20 NK/2019-20/0277,Buildings,Completed,NK-KODAMBAKKAM,142,90000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Girls Higher Secondary School at West Jones Road in Division - 142, Unit - 30, Zone - 10(from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0278,Buildings,Completed,NK-KODAMBAKKAM,142,45000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Thideer Nagar in Division - 142, Unit - 30, Zone - 10(from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0279,Buildings,Completed,NK-KODAMBAKKAM,142,30000,"Providing Private Labourers for Sweeping and Toilet cleaning work atChennai Primary School at Bazaar Road in Division - 142, Unit - 30, Zone - 10(from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/0280,Buildings,Completed,NK-KODAMBAKKAM,142,45000,"Providing Private Labourers for Sweeping and Toilet cleaning work atChennai Primary School at West Jones Road in Division - 142, Unit - 30,Zone - 10(from 01.06.2019 to 15.07.2019)",Own Sources,10,2019-20,2020-21 NK/2019-20/10557,Buildings,Completed,NK-KODAMBAKKAM,142,346000,"PROVIDING BOREWELL AND WATER SUPPLY ARRANGEMENT WORK TO AMMA UNAVAGAM AT JEENIS ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10558,Buildings,Completed,NK-KODAMBAKKAM,142,257000,"DISMANDLING OF THE EXISTING DIVISION OFFICE AT VINAYAGAMPET STREET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10676,Buildings,Completed,NK-KODAMBAKKAM,142,638000,"REPAIR AND IMPROVEMENTS WORKS TO THE CHENNAI GIRLS HIGHER SECONDRY SCHOOL AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/10677,Buildings,Completed,NK-KODAMBAKKAM,142,554000,"REPAIR AND IMPROVEMENT WORK AT CHENNAI PRIMARY SCHOOL AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10,",Own Sources,10,2019-20,2020-21 NK/2019-20/10977,Electrical,Completed,NK-KODAMBAKKAM,142,347400,"Electrification work carried out for shifting of existing Patient Ward and Operation Theater at Jeenis Road EOC in Division 142,Zone X",Own Sources,10,2019-20,2020-21 NK/2019-20/11475,Buildings,Completed,NK-KODAMBAKKAM,142,267000,"PROVIDING NEW DRAINAGE CONNECTION AND REPAIRS TO THE EXISTING DRAINAGE CONNECTION IN DHOBIS REST ROOM AT DHOBIKHANA IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/14636,Buildings,Completed,NK-KODAMBAKKAM,142,1560000,"CONSTRUCTION OF OPEN AUDITORIUM (CIVIL WORK) AT CHENNAI GIRLS HIGHER SECONDARY SCHOOL WEST JONES ROAD ,WEST SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10. [ UNDER SAIDAPET M.L.A FUND]",MLACDS,10,2019-20,2020-21 NK/2019-20/14637,Buildings,Completed,NK-KODAMBAKKAM,142,1430000,"CONSTRUCTION OF OPEN AUDITORIUM (FABRICATION WORK) AT CHENNAI GIRLS HIGHER SECONDARY SCHOOL WEST JONES ROAD ,WEST SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10. [ UNDER SAIDAPET M.L.A FUND]",MLACDS,10,2019-20,2020-21 NK/2019-20/15740,Buildings,Completed,NK-KODAMBAKKAM,142,707200,"PROVIDING PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK AT CHENNAI GIRLS HIGHER SECONDARY SCHOOL AT WEST JONES ROAD IN DIVISION 142, UNIT-30. ZONE-10 ( FROM ( 01.6.2020 TO 30.4.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/15742,Buildings,Completed,NK-KODAMBAKKAM,142,353600,"PROVIDING PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK AT CHENNAI MIDDLE SCHOOL AT THIDEER NAGAR IN DIVISION 142, UNIT-30. ZONE-10 ( FROM ( 01.6.2020 TO 30.4.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/15743,Buildings,Completed,NK-KODAMBAKKAM,142,235700,"PROVIDING PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK AT CHENNAI PRIMARY SCHOOL AT BAZAAR ROAD IN DIVISION 142, UNIT-30. ZONE-10 ( FROM ( 01.6.2020 TO 30.4.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/15744,Buildings,Completed,NK-KODAMBAKKAM,142,353600,"PROVIDING PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK AT CHENNAI PRIMARY SCHOOL AT WEST JONES ROAD IN DIVISION 142, UNIT-30. ZONE-10 ( FROM ( 01.6.2020 TO 30.4.2021)",Own Sources,10,2019-20,2021-22 NK/2019-20/1589,Buildings,Completed,NK-KODAMBAKKAM,142,89000,"SUPPLYING AND FIXING OF WELL RING FOR COMPOST PIT AT VARIOUS LOCATIONS IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2298,Buildings,Completed,NK-KODAMBAKKAM,142,617000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Girls Higher Secondary School at West Jones Road in Division - 142, Unit - 30, Zone - 10 (from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2299,Buildings,Completed,NK-KODAMBAKKAM,142,308000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Thideer Nagar in Division - 142, Unit - 30, Zone - 10(from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2300,Buildings,Completed,NK-KODAMBAKKAM,142,308000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at West Jones Road in Division - 142, Unit - 30, Zone - 10(from 16.07.2019 to 30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2301,Roads,Completed,NK-KODAMBAKKAM,142,205000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Bazaar Road in Division - 142, Unit - 30, Zone - 10(from 16.07.2019 to30.04.2020)",Own Sources,10,2019-20,2020-21 NK/2019-20/2860,Buildings,Completed,NK-KODAMBAKKAM,142,358800,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT CGHSS AT WEST JONES ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/2869,Buildings,Completed,NK-KODAMBAKKAM,142,310000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT CPS AT BAZAAR ROAD IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/2870,Buildings,Completed,NK-KODAMBAKKAM,142,310000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS AT CMS AT THIDEER NAGAR IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/4320,Storm Water Drain,Completed,NK-KODAMBAKKAM,142,1541000,"DESILTING & MINOR REPAIR WORKS TO THE EXISTING STORM WATER DRAIN SAMIYAR THOTTAM, MOSQUE STREET, GODHAMEDU AND VARIOUS STREETS IN DIVISION-142, UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/4646,Buildings,Completed,NK-KODAMBAKKAM,142,496000,"Maintanance and Repairs to GCC Buildings such as Schools, EOC & UPHC Hospitals & SWD Missing Links etc..in Division-142, Unit-30, Zone-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/5583,Buildings,Completed,NK-KODAMBAKKAM,142,730000,"PROVIDING SHEET ROOFING AND FENCING ARRANGEMENT WORKS FOR COMPOSITE YARD AT JEENIS ROAD IN DIVISION-142, UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/6001,Roads,Completed,NK-KODAMBAKKAM,142,2160000,"Laying Cement Concrete Road using M30 grade at Flower Street & Flower Street Lane in Division-142, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7298,Buildings,Completed,NK-KODAMBAKKAM,142,1073000,"Providing Security Arrangements and Engaging private labourers for EOC Hospitals at Jeenis Road (12 Months) in Division-142, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7299,Buildings,Completed,NK-KODAMBAKKAM,142,555000,"Providing Security Arrangements and Engaging private labourers for UPHC Hospitals at West Jones Road (12 Months) in Division-142, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7477,Buildings,Completed,NK-KODAMBAKKAM,142,1295000,"IMPROVEMENT WORKS TO THE EOC HOSPITAL AT JEENIS ROAD IN DIVISION-142, UNIT-30, ZONE-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7814,Parks,Completed,NK-KODAMBAKKAM,142,488000,"Maintanance and repairs to GCC Building such as uphc hospital ,footpath,public convenience,subways & strom water drain etc... at various in Division-142,unit-30,zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/7822,Subway,Completed,NK-KODAMBAKKAM,142,417000,"PROVIDING ELECTRICAL CUM PLUMBER (DAY AND NIGHT) TO THE ALANDUR ROAD SUBWAY WEST JONES ROAD C.B.PAVALAVANNAN SUBWAY AND DURAISAMY ROAD SUBWAY IN DIV-142 AND 136, UNIT-30, ZONE-10",Own Sources,10,2019-20,2020-21 NK/2019-20/7955,Roads,Completed,NK-KODAMBAKKAM,142,297000,"Attending Patch Work Kothavalchavadi Street, East Jones Road, Perumal Koil Street and Various Streets in Division-142, Unit-30, Zone-10.",Own Sources,10,2019-20,2020-21 NK/2019-20/8684,Buildings,Completed,NK-KODAMBAKKAM,142,960000,"PROVIDING RAIN WATER HARVESTING STRUCTURE USING WELL RING TYPE [14 NOS] FOR CHENNAI GIRLS HIGHER SECONDARY SCHOOL CAMPUS AT WEST JONES ROAD IN DIV-142 , UNIT-30, ZONE-10.",Own Sources,10,2019-20,2019-20 NK/2019-20/9842,Buildings,Completed,NK-KODAMBAKKAM,142,500000,"Repair and Improvement work to the UPHC at West Jones Road in Division-142, Unit-30, Zone -10",Own Sources,10,2019-20,2020-21 L/2019-20/8365,Electrical,Completed,L-Electrical,143,397000,"Supply and Erection of 9 Numbers of 6 mtr hot dip lamppost with one mtr straight bracket with 40w led streetlight at Madha koil 3rd & 4th street,Anamalai cross &union road cross street in Div 143,144 & 146 Nolambur",Grants,11,2019-20,2020-21 NL/2019-20/10422,Parks,Completed,NL-VALASARAVAKKAM,143,1119000,"Annual Maintenance of Park at Nolambur Phase- II 7th Cross Street ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:4158 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/12943,Parks,Completed,NL-VALASARAVAKKAM,143,602000,"Annual Maintenance of Park at Nolambur Phase-1 7th main road ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:4158 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/1309,Buildings,Completed,NL-VALASARAVAKKAM,143,164000,"Providing and Placing of Well Rings at Various Places in DN-143, U-32, Z-11",Own Sources,11,2019-20,2019-20 NL/2019-20/13699,Parks,Completed,NL-VALASARAVAKKAM,143,599000,"Annual Maintenance of Park at Nolambur Phase- I 9th Main Road (New) ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:989 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/14520,Parks,Completed,NL-VALASARAVAKKAM,143,1175000,"Annual Maintenance of Park at Nolambur Phase- I 3rd Main Road ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park: 4384 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17689,Parks,Completed,NL-VALASARAVAKKAM,143,898000,"Annual Maintenance of Park at Nolambur Phase- I 9th Main Road (Old) ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:4384Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17690,Parks,Completed,NL-VALASARAVAKKAM,143,654000,"Annual Maintenance of Park at Nolambur Channal Road ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:1830 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17691,Parks,Completed,NL-VALASARAVAKKAM,143,875000,"Annual Maintenance of Park at Nolambur Phase- II 13th Cross street ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:2205 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17692,Parks,Completed,NL-VALASARAVAKKAM,143,634000,"Annual Maintenance of Park at Nolambur MCK layout ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:1267Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17693,Parks,Completed,NL-VALASARAVAKKAM,143,603000,"Annual Maintenance of Park at Nolambur Phase- I 1st Main Road ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:1428 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17694,Parks,Completed,NL-VALASARAVAKKAM,143,579000,"Annual Maintenance of Park at Nolambur Phase-1 6th Cross street ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:4158 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17695,Parks,Completed,NL-VALASARAVAKKAM,143,603000,"Annual Maintenance of Park at S&P garden 1st main road ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:1406Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17696,Parks,Completed,NL-VALASARAVAKKAM,143,624000,"Annual Maintenance of Park at V.G.N. Monte carlo, Garden street ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:1052 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17697,Parks,Completed,NL-VALASARAVAKKAM,143,1004000,"Annual Maintenance of Park at V.G.N. Monte carlo, Park street ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:3267 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17698,Parks,Completed,NL-VALASARAVAKKAM,143,208000,"Annual Maintenance of Park at Nolambur Phase- I 6th Main Road (Road side Park) ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:482 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/17699,Parks,Completed,NL-VALASARAVAKKAM,143,635000,"Annual Maintenance of Park at Nolambur Phase- I 13th Cross street ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:1138 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/4138,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,541000,"Desilting of SWD at Various Streets in Division-143, Unit-32, Zone-11",Own Sources,11,2019-20,2019-20 NL/2019-20/4500,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,599500,"Minor repairs and Maintenance to SWD at various Streets in Division-143, Unit-32, Zone-11",Own Sources,11,2019-20,2019-20 NL/2019-20/4887,Parks,Completed,NL-VALASARAVAKKAM,143,250000,"Desilting and Improvements to open Well at Nolambur Phase-I 3rd main Road in Division-143, Unit-32, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/4899,Parks,Completed,NL-VALASARAVAKKAM,143,350000,"Desilting and Improvements to open Well at Nolambur Phase-I 7th main Road in Division-143, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/5431,Parks,Completed,NL-VALASARAVAKKAM,143,95000,"Maintenance for Park at Nolambur Phase-I 7th Main Road( Area=978 sqm) (5months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5432,Parks,Completed,NL-VALASARAVAKKAM,143,422000,"Maintenance for Park at Nolambur Phase-I 3rd Main Road ( Area =4975 m2) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5434,Parks,Completed,NL-VALASARAVAKKAM,143,98000,"Maintenance for Park at Nolambur Phase-I 9th Main Road (New) (Area=1095 sqm) (5 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5435,Parks,Completed,NL-VALASARAVAKKAM,143,98000,"Maintenance for Park at Nolambur Phase-II, 7th Cross Street (Area=1650 sqm) (5 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5436,Parks,Completed,NL-VALASARAVAKKAM,143,117000,"Maintenance for Park at Nolambur Phase-II ,3rd Cross Street (5 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5437,Parks,Completed,NL-VALASARAVAKKAM,143,215000,"Maintenance of corporation park at Nolambur Phase-2 ,13th cross street In Div-143,U-32,Z-11",Own Sources,11,2019-20,2019-20 NL/2019-20/5439,Parks,Completed,NL-VALASARAVAKKAM,143,164000,"Maintenance for Park at Nolambur Phase-1,9th main road (old) (area=1456 sqm) in Dn-143, U - 33, Zone-11",Own Sources,11,2019-20,2019-20 NL/2019-20/5441,Parks,Completed,NL-VALASARAVAKKAM,143,112000,"Maintenance for Park at Nolambur Channal Road (Area-1694 sqm) (5months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5443,Parks,Completed,NL-VALASARAVAKKAM,143,110000,"Maintenance for Park at Nolambur Phase-I 13th Cross Street (area=1163) (5 months) in Dn.143, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5445,Parks,Completed,NL-VALASARAVAKKAM,143,170000,"Maintenance of corporation park at Nolambur MCK Layout Park In Div-143,U-32,Z-11",Own Sources,11,2019-20,2019-20 NL/2019-20/7728,Roads,Completed,NL-VALASARAVAKKAM,143,468000,Attending Minor Pot holes with using Cement Concrete at Various street in Division-143 Unit-32 Zone-11,Own Sources,11,2019-20,2020-21 NL/2019-20/8602,Parks,Completed,NL-VALASARAVAKKAM,143,669000,"Annual Maintenance of Park at Nolambur Phase- II 3rd Cross street ( FOR ONE YEAR ) in Division -143, Unit-32, Zone-11. (Area of Park:2747 Sqm)",Own Sources,11,2019-20,2020-21 NL/2019-20/8609,Buildings,Completed,NL-VALASARAVAKKAM,143,1130000,Proposed Construction of Toilet and Water Supply with Electrical Arrangements in Compost yard at Union Road in Div -143 Unit -32 Zone - XI,Own Sources,11,2019-20,2020-21 NL/2019-20/1227,Buildings,Completed,NL-VALASARAVAKKAM,144,294000,"PROVIDING RESOURCE RECOVERY CENTER AT PILLAYAR KOVIL STREET IN DN-144,UNIT-32,ZONE-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/15077,Buildings,Completed,NL-VALASARAVAKKAM,144,500000,"Maintenance and Improvement to Various works in Div-144, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/15998,Bridges,Completed,NL-VALASARAVAKKAM,144,1872000,"Proposed Construction of compound wall,Toilet Block and Improvement to 16th Ceremony Hall at MMDA Colony 2nd main road in Div-144, Unit-32, Zone-11",Own Sources,11,2019-20,2021-22 NL/2019-20/2235,Buildings,Completed,NL-VALASARAVAKKAM,144,111500,"Supplying and Fixing of Well Rings for Composting Purpose at Various Places in Dn-144,Unit-32,zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/3275,Buildings,Completed,NL-VALASARAVAKKAM,144,242000,"Supplying and fixing of grill gate and grill shutter for collection of floating materials from storm water drain at disposal points in Dn- 144, 145, 146, 148 & 155 , U - 32, 33 & 34, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4553,Buildings,Completed,NL-VALASARAVAKKAM,144,1950000,"Construction of Compound Wall , Footpath and Volley Ball Court at OSR Land in VGP Amutha Nagar in Dn -144, Unit-32,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5446,Parks,Completed,NL-VALASARAVAKKAM,144,143000,"Maintenance for Park at VGP Amutha Nagar Nolambur in Dn.144, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5781,Buildings,Completed,NL-VALASARAVAKKAM,144,595000,"Minor Repairs in SWD at various street in Div-144,Unit-32,Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/5786,Storm Water Drain,Completed,NL-VALASARAVAKKAM,144,520000,"Desilting of storm Water Drain and Side Drain at various street in Div-144,Unit-32,Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/7758,Roads,Completed,NL-VALASARAVAKKAM,144,133000,Attending Minor Pot holes with using Cement Concrete at Various street in Division-144 Unit-32 Zone-11,Own Sources,11,2019-20,2020-21 NL/2019-20/11276,Buildings,Completed,NL-VALASARAVAKKAM,145,215000,"Construction of Culvert at Chelliyaman Nagar Aanni Street Chithirai Street junction in Dn-145,Unit-33,Zone-11.",Own Sources,11,2019-20,2021-22 NL/2019-20/11277,Buildings,Completed,NL-VALASARAVAKKAM,145,188000,"Construction of Culvert at Dhanalaksmi Nagar 2nd Street in Dn-145,Unit-33,Zone-11.",Own Sources,11,2019-20,2021-22 NL/2019-20/12238,Road Cut,Completed,NL-VALASARAVAKKAM,145,1956000,"Restoration of Road Cut Made by CMWSSB UGSS at Alagammal Nagar 4th Street, Alagammal Nagar 5th Street, Alagammal Nagar 6th Street, Alagammal Nagar Main Road part 2, and Krishna Nagar Nethaji Avenue extension part 2- in Div-145, Unit-33, Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/12241,Road Cut,Completed,NL-VALASARAVAKKAM,145,1942000,"Restoration of Road Cut Made by CMWSSB UGSS at Jeye Lakshmi Nagar 1st Anna Main Road & Cross Streets, and Jeye Lakshmi Nagar Gandhi Street - in Div-145, Unit-33, Zone-11.",Own Sources,11,2019-20,2021-22 NL/2019-20/12242,Road Cut,Completed,NL-VALASARAVAKKAM,145,1972000,"Restoration of Road Cut Made by CMWSSB UGSS at Alagammal Nagar 7th Street, Arulmigu Meenakshi Amman Nagar 3rd Street, Jeya Lakshmi Nagar Nehruji Street, and Dhanalakshmi Nagar kakanji Street-in Div-145, Unit-33, Zone-11.",Own Sources,11,2019-20,2021-22 NL/2019-20/12243,Road Cut,Completed,NL-VALASARAVAKKAM,145,1946000,"Restoration of Road Cut Made by CMWSSB UGSS at Dhanalakshmi Nagar Kamarajar Street, Dhanalakshmi Nagar Bharathiyar Street, Dhanalakshmi Nagar kattabomman Street, and Moogambigai Nagar Main Road - in Div-145, Unit-33, Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/12244,Road Cut,Completed,NL-VALASARAVAKKAM,145,1991000,"Restoration of Road Cut Made by CMWSSB UGSS at Moogambigai Nagar 1st Street, Moogambigai Nagar 2nd Street, Moogambigai Nagar 3rd Street, Moogambigai Nagar 4th Street, Moogambigai Nagar 5th Street, Moogambigai Nagar 6th Street, Moogambigai Nagar 7th Street and Sakthi Nagar 19th 3rd Cross Street - in Div-145, Unit-33, Zone-11.",Own Sources,11,2019-20,2021-22 NL/2019-20/12245,Road Cut,Completed,NL-VALASARAVAKKAM,145,1953000,"Restoration of Road Cut Made by CMWSSB UGSS at Dhanalakshmi Nagar Annai Therasa Street, Moogambigai Nagar 8th Street, Moogambigai Nagar 11th Street, Thirumalai Nagar Main Road, and Thirumalai Nagar 1st Street - in Div-145, Unit-33, Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/12246,Road Cut,Completed,NL-VALASARAVAKKAM,145,1915000,"Restoration of Road Cut Made by CMWSSB UGSS at Thirumalai Nagar 2nd Street, Thirumalai Nagar 3rd Street, and Dhanalakshmi Nagar Main Road in Div-145, Unit-33, Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/1308,Buildings,Completed,NL-VALASARAVAKKAM,145,141000,"Providing and Placing of Well Rings at Various Places in DN-145, U-33, Z-11",Own Sources,11,2019-20,2019-20 NL/2019-20/1560,Buildings,Completed,NL-VALASARAVAKKAM,145,20000,"Suppling and fixing of mulch pit at valliyammai nagar burial ground in Dn-145,U-33,zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5412,Buildings,Completed,NL-VALASARAVAKKAM,145,541000,"Improvement of Culvert and Side drain at Palvadi 4th street & Annammal Nagar Main Road in dn-145,u - 33 Zone - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/6244,Buildings,Completed,NL-VALASARAVAKKAM,145,194000,"Construction of Culvert at Chelliyaman Nagar Iyppasi Street Karthigai Street junction in Dn-145,Unit-33,Zone-11.",Own Sources,11,2019-20,2021-22 NL/2019-20/7670,Roads,Completed,NL-VALASARAVAKKAM,145,896000,"ATTENDING PATCHWORK AT VARIOUS Location in DN - 145, U-33, Zone - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/8510,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,623000,"Desilting of Storm Water Side Drain at Various Streets in Dn-145,Unit-33,Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/8511,Buildings,Completed,NL-VALASARAVAKKAM,145,699000,"Minor Repair the Storm Water drain In Various Streets in Dn-145,Unit-33,Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/8933,Road Cut,Completed,NL-VALASARAVAKKAM,145,995000,"Restoration Of Road Cut Made By CMWSSB at Krishna Nagar 13 th Street,Moogambigai Nagar 2nd main Road,Mandaveli 2nd cross Street, And Mandaveli 3rd cross Street in Div-145,Unit-33,Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8936,Road Cut,Completed,NL-VALASARAVAKKAM,145,982000,"Restoration Of Road Cut Made By CMWSSB at Pallavan Nagar Balvadi Exncom cross Street (new),Pallavan Nagar Reddy Street,Pallavan Nagar Balvadi 5th Street , And Nethaji Avenue Bharathi Street- in Div-145,Unit-33,Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8938,Road Cut,Completed,NL-VALASARAVAKKAM,145,982000,"Restoration Of Road Cut Made By CMWSSB at Balakrishna Main Road ,Moogambigai Nagar 9thStreet, Moogambigai Nagar 3rd main road part - 2,Pallavan Nagar VOC Street jn.Karuneekar road crossing,Pallavan Nagar Balvadi 4th Street And Dayasadan Raod in Div-145,Unit-33,Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8940,Road Cut,Completed,NL-VALASARAVAKKAM,145,997000,"Restoration Of Road Cut Made By CMWSSB at Nethaji Avenue Tagore Street,Pallavan Nagar (reddy Cross Street ) ,Janakiram Colony Meenakshi amman koil Street Part-2 ,Ambika Nagar Main Road,Senthamil Nagar Ammaiyappan nagar 4th cross street ,Perumal koil street gap work And Madhakoil Street colony main road- in Div-145,Unit-33,Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8941,Road Cut,Completed,NL-VALASARAVAKKAM,145,992000,"Restoration Of Road Cut Made By CMWSSB at Moogambigai Nagar 8th 2nd cross Street,Pallavan Nagar Balvadi Exncom cross Street ,Alagammal Nagar 1st main road,Moogambigai Nagar 12th Street,Krishna Nagar 1st Street jn of patel road ,New colony 1st street ,Pallavadi street jn to perumal koil street road crossing,Perumal koil street gap jn colony main road And Madhakoil Street - in Div-145,Unit-33,Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8942,Road Cut,Completed,NL-VALASARAVAKKAM,145,996000,"Restoration Of Road Cut Made By CMWSSB at perumal koil street east,perumal koil street west,Santha avanue 1st cross Street,Santha avanue 2nd cross Street,Santha avanue 3rd cross Street,Santha avanue 4th cross Street, And Sakthi Nagar cross street in Div-145,Unit-33, Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8955,Road Cut,Completed,NL-VALASARAVAKKAM,145,978000,"Restoration Of Road Cut Made By CMWSSB at Colony main road,Rajiv gandhi nagar cheran street jn of Mbn 3rd main road crossing Jeya lakshmi nagar anna prathana salaai 1st main road cross ,Jeya lakshmi nagar 2nd street Neruji street,Dhanalakshmi Nagar Ext 2nd street Bharathi street,Muniyappan nagar 5th street And Moogambigai Nagar 3rd main road part - 1 - in Div-145,Unit-33,Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8956,Road Cut,Completed,NL-VALASARAVAKKAM,145,998000,"Restoration Of Road Cut Made By CMWSSB at moogambigai Nagar 3rd main Road,Balakrishna nagar 1st street jn BAK road crossing,Balakrishna nagar 2nd street jn BAK road crossing,Balakrishna nagar 3rd street jn BAK road crossing,Balakrishna nagar 4th street jn BAK road crossing,Janakiram Colony Meenakshi amman koil Street Part-1 And Perumal koil street 16th street jn perumal koil street road crossing- in Div-145,Unit-33,Zone-11.",Deposit Works,11,2019-20,2021-22 NL/2019-20/8967,Buildings,Completed,NL-VALASARAVAKKAM,145,483000,"Improvement and Division Maintanance at Various Location in Division-145, Unit-33, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/1287,Bridges,Completed,NL-VALASARAVAKKAM,146,294000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY CENTER AT METRO NAGAR IN DIV-146, UNIT-32, ZONE-11",Own Sources,11,2019-20,2020-21 NL/2019-20/1424,Parks,Completed,NL-VALASARAVAKKAM,146,92000,"Providing and Placing of Ringwell at Various Location in Div-146, Unit-32, Zone-11",Own Sources,11,2019-20,2019-20 NL/2019-20/4426,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,722000,"Minor Repair works to the existing damaged drains at various streets in Div-146 Unit-32, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5115,Parks,Completed,NL-VALASARAVAKKAM,146,643000,"Annual Maintenance of Metro Nagar park at Metro Nagar 4th Avenue in Div-146, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/5447,Parks,Completed,NL-VALASARAVAKKAM,146,113000,"Maintenance for Park at Metro Nagar (5months) in Dn.146, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5865,Storm Water Drain,Completed,NL-VALASARAVAKKAM,146,617000,"Desilting Of Storm Water Drains and Side Drains At Various Streets in Division- 146,Unit - 32 , Zone -11",Own Sources,11,2019-20,2020-21 NL/2019-20/8377,Buildings,Completed,NL-VALASARAVAKKAM,146,500000,"Maintenance and improvement work to various work in Division 146, Unit-32, Zone-XI",Own Sources,11,2019-20,2020-21 L/2019-20/5536,Electrical,Completed,L-Electrical,147,976000,"Construction of Cement Concrete Pedestial for 1768 Nos of 6/7 Mtr Lamp post with pedestial White washing at Various locations in Divisions 147,149 Zone-XI.",Own Sources,11,2019-20,2020-21 L/2019-20/8360,Electrical,Completed,L-Electrical,147,1963400,"Supply and Erection of 31 Nos of of 6 mtr Lamp Post with 40w LED Fitting on 1mtr Stright bracket and 10 Nos of 6 mtr Lamp Post with 90w LED Fitting on Single Arch bracket at Ramanujam Street, AlwarThiru Nagar 2nd Main Road ,Vivakananantha Street ,Seemathamman Koil Extension , Pallavan Nagar 5th Street in Division 147 ,149 Zone XI",Grants,11,2019-20,2020-21 NL/2019-20/10361,Buildings,Completed,NL-VALASARAVAKKAM,147,495000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITRES/HOUR CAPACITY FOR (AMMA KUDINEER) GANGAIAMMAN KOIL STREET, ALAPAKKAM IN DIV-147, U-32, Z-11(3R YEAR MAINTENANCE)",Own Sources,11,2019-20,2020-21 NL/2019-20/10363,Buildings,Completed,NL-VALASARAVAKKAM,147,1225000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (RO/UV FILTRATION) OF 2000 LITRES/HOUR CAPACITY FOR (AMMA KUDINEER) GANGAIAMMAN KOIL STREET, ALAPAKKAM IN DIV-147, U-32, Z-11(4TH YEAR MAINTENANCE)",Own Sources,11,2019-20,2020-21 NL/2019-20/1415,Buildings,Completed,NL-VALASARAVAKKAM,147,228000,"Providing and Placing of Ringwells at Various Locations in Div-147, Unit-32, Zone-11",Own Sources,11,2019-20,2019-20 NL/2019-20/3271,Bridges,Completed,NL-VALASARAVAKKAM,147,610000,"Improvement works to the Existing Compost Yard at Gangaiamman Koil Street in Div-147, Unit-32, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/4120,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,525000,"DESILTING OF STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DIV 147,UNIT - 32 , ZONE -11",Own Sources,11,2019-20,2019-20 NL/2019-20/4121,Bridges,Completed,NL-VALASARAVAKKAM,147,2368000,"Construction of Compound Wall to the Burial Ground at Alapakkam Main Road in Div-147, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/4423,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,1223500,"MINOR REPAIR WORKS TO THE EXISTING DAMAGED DRAINS AT VARIOUS STREETS IN DIV 147,UNIT 32,ZONE 11.",Own Sources,11,2019-20,2019-20 NL/2019-20/5111,Parks,Completed,NL-VALASARAVAKKAM,147,583000,"Annual Maintenance of Pallavan Nagar park at Pallavan Nagar 1st main road in Div-147, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/5112,Parks,Completed,NL-VALASARAVAKKAM,147,648000,"Annual Maintenance of Arignaranna park at Gangaiamman Koil street in Div-147, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/5113,Parks,Completed,NL-VALASARAVAKKAM,147,614000,"Annual Maintenance of Bharathi park at Bharathi Nagar 3rd street in Div-147, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/5114,Parks,Completed,NL-VALASARAVAKKAM,147,840000,"Annual Maintenance of Thanthai periyar Play Ground at Alapakkam main road in Div-147, Unit-32, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/5428,Parks,Completed,NL-VALASARAVAKKAM,147,102000,"Maintenance for Park at Pallavan Nagar(5months) in Dn.147, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5429,Parks,Completed,NL-VALASARAVAKKAM,147,136000,"Maintenance for Park at Gangai amman koil Street Arignar Anna Park( 5 months) in Dn.147, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5430,Parks,Completed,NL-VALASARAVAKKAM,147,131000,"Maintenance for Park at Bharathiyar Nagar (5 months ) in Dn.147, Unit-32, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/5508,Parks,Completed,NL-VALASARAVAKKAM,147,148000,"Maintenance of Thanthai periyar Thiedal in Div-147, Unit-32, Zone-11",Own Sources,11,2019-20,2019-20 NL/2019-20/5712,Buildings,Completed,NL-VALASARAVAKKAM,147,500000,"Maintenance works at various places in Div- 147, unit-32, Zone-Xl",Own Sources,11,2019-20,2019-20 NL/2019-20/6056,Roads,Completed,NL-VALASARAVAKKAM,147,272000,"Forming of BT Road at Pallavan Nagar 5th Cross Street in Div-147, Unit-32, Zone-XI",Loans And Grants,11,2019-20,2020-21 NL/2019-20/6057,Roads,Completed,NL-VALASARAVAKKAM,147,417000,"Improvements to Interior BT Road at Janaki nagar 5th Street in Div-147, Unit-32, Zone-XI",Loans And Grants,11,2019-20,2020-21 NL/2019-20/6058,Roads,Completed,NL-VALASARAVAKKAM,147,4545000,"Forming of BT Road at Seemathamman nagar extension in Div-147, Unit-32, Zone-XI",Loans And Grants,11,2019-20,2020-21 NL/2019-20/6059,Roads,Completed,NL-VALASARAVAKKAM,147,135000,"Improvements to interior BT Road at Ganga Nagar 12th Cross Street in Div-147, Unit-32, Zone-XI",Loans And Grants,11,2019-20,2020-21 NL/2019-20/6060,Roads,Completed,NL-VALASARAVAKKAM,147,178000,"Improvements to interior BT Road at Pallavan Nagar Bharathi Street in Div-147, Unit-32, Zone-XI",Loans And Grants,11,2019-20,2020-21 NL/2019-20/7490,Buildings,Completed,NL-VALASARAVAKKAM,147,169000,"Providing Raon Water Harvesting to Ganga Nagar Public Purpose land & Well at Ganga Nagar main road and Arcot road in Div-147, Unit-32, Zone-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/7545,Buildings,Completed,NL-VALASARAVAKKAM,147,2996000,"Providing Temporary Sheds for Drivers, and Vehicle Service Center for Lorry Station at Arcot Road in Div-147, Unit-32,Zone-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/7790,Roads,Completed,NL-VALASARAVAKKAM,147,1476000,"Attending CC Patch Work At Various Streets in Dn -147, U-32, Z-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/8449,Electrical,Completed,NL-VALASARAVAKKAM,147,1135000,Electrification Work in Lorry Depot at A.R.S Garden in Division : 147 Zone XI,Own Sources,11,2019-20,2020-21 NL/2019-20/10653,Parks,Completed,NL-VALASARAVAKKAM,148,734000,"Improvement Work at TAISHA Park in Div-148,Unit-33,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/10922,Buildings,Completed,NL-VALASARAVAKKAM,148,483000,"Improvement and Division Maintanance at various Location in Div-148,Unit - 33, Zone-XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/1444,Buildings,Completed,NL-VALASARAVAKKAM,148,71000,"Providing Well Rings at Various Locations in Dn - 148, U- 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/3500,Buildings,Completed,NL-VALASARAVAKKAM,148,220000,"IMPROVEMENTS WORKS TO BHUVANESHWARI NAGAR ANGANWADI IN DN-148, U-33, Z-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/7230,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,882000,"Improvement of side drain at bhuveneshwari nagar amman kovil street in Division - 148 , Unit - 33 in Zone - XI",Own Sources,11,2019-20,2020-21 NL/2019-20/7668,Roads,Completed,NL-VALASARAVAKKAM,148,243000,"Attending Patchwork at kamarajar High Road,Kannagi Street & Annai sathya Street in Dn 148 , u-33 Zone- XI",Own Sources,11,2019-20,2020-21 NL/2019-20/8332,Buildings,Completed,NL-VALASARAVAKKAM,148,986000,"Improvement Work to footpath at TAISHA Park road in DN-148,U-33,Zone-XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8512,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,510000,"Desilting of Storm Water side Drain at Various streets in Dn-148,Unit-33,Zone-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/8513,Buildings,Completed,NL-VALASARAVAKKAM,148,500000,"Minor Repair the Storm Water Drain in various Streets in DN-148, Unit - 33,Zone-XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8978,Storm Water Drain,Completed,NL-VALASARAVAKKAM,148,731000,"iImprovement to side Drain to low laying area at Bhuvaneshwari Nagar in Dn-148, Unit-33,Zone-11.",Own Sources,11,2019-20,2020-21 BR/2019-20/5360,Roads,Completed,BR-Bus Route Roads,149,446000,"Partly relaying the road with BC after cold milling by paver finisher at Sri Devi Kupam Main Road in Dn-149, Zone - 11",Grants,11,2019-20,2020-21 BR/2019-20/5361,Roads,Completed,BR-Bus Route Roads,149,581000,"Partly relaying the road with BC after cold milling by paver finisher at Radha Road in Dn-149, Zone - 11",Grants,11,2019-20,2020-21 NL/2019-20/10259,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,159000,"Repair works to Storm Water Drains at Velan Nagar Main Road, Sridevikuppam Main Road, Nagireddy Street and Muralikrishna Nagar Main Road in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/10264,Buildings,Completed,NL-VALASARAVAKKAM,149,63000,"Providing Mulch pit at Brindhavan Nagar Gasifier Burial Ground and other repair works at sammantham nagar amma unavagam and nakeeran street amma unavagam in Dn - 149, U - 33, Z - XI",Own Sources,11,2019-20,2019-20 NL/2019-20/10266,Buildings,Completed,NL-VALASARAVAKKAM,149,177000,"Improvements to Unit office - 33, and RWH arrangements in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/10268,Buildings,Completed,NL-VALASARAVAKKAM,149,89000,"Providing inlet pipe, chamber and culvert roof slab work at cheran street, velan nagar 6th street and poolakshmi street in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/1258,Buildings,Completed,NL-VALASARAVAKKAM,149,294000,"PROPOSED CONSTRUCTION OF MATRIAL RECOVERY FACILITY AT BRINDHAVAN NAGAR BURIAL GROUND IN DN - 149, U - 33, Z - XI.",Loans And Grants,11,2019-20,2019-20 NL/2019-20/1301,Buildings,Completed,NL-VALASARAVAKKAM,149,46000,"Providing and Erecting Well Rings at Various Locations in Dn - 149, U- 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/14008,Buildings,Completed,NL-VALASARAVAKKAM,149,1109000,"Repair and Service of Gasifier Equipments & Machineries at Brindhavan Nagar Gasifier Burial Ground in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2021-22 NL/2019-20/4192,Parks,Completed,NL-VALASARAVAKKAM,149,754000,"Annual Maintenance of Thanthai Periyar Park at Fathima Nagar (2730.00 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4193,Parks,Completed,NL-VALASARAVAKKAM,149,702000,"Annual Maintenance of Thiru.Vi.Ka Park at Gandhi Road (2415.00 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4194,Parks,Completed,NL-VALASARAVAKKAM,149,253000,"Annual Maintenance of Park at Brindhavan Nagar (510.00 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4195,Parks,Completed,NL-VALASARAVAKKAM,149,657000,"Annual Maintenance of Varadha Park at Brindhavan Nagar (2498.27 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4196,Parks,Completed,NL-VALASARAVAKKAM,149,457000,"Annual Maintenance for Park at OSR land Near Alsa Tower (Total Area - 1512 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4197,Parks,Completed,NL-VALASARAVAKKAM,149,482000,"Annual Maintenance for Park at CEEBROS OSR land (Total Area - 1630 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4997,Parks,Completed,NL-VALASARAVAKKAM,149,321000,"Maintenance for Park at Fathima Nagar (Total Area - 2730 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5001,Parks,Completed,NL-VALASARAVAKKAM,149,260000,"Maintenance for Thiru.Vi.Ka Park at Gandhi Road (Total Area - 2415 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5315,Buildings,Completed,NL-VALASARAVAKKAM,149,555000,"Construction of Toilet Block and Water Supply Arrangements at Palaniappa Nagar Childrens Playground in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/5356,Parks,Completed,NL-VALASARAVAKKAM,149,94000,"Maintenance for Park at Brindavan nagar (Total Area - 510 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5357,Parks,Completed,NL-VALASARAVAKKAM,149,165000,"Maintenance for Park at OSR land Near Alsa Tower (Total Area - 1512 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5359,Parks,Completed,NL-VALASARAVAKKAM,149,174000,"Maintenance for Park at CEEBROS OSR land (Total Area - 1630 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5362,Parks,Completed,NL-VALASARAVAKKAM,149,184000,"Maintenance for Varadha Park at Brindhavan Nagar (Total Area - 2498.27 Sq.m) in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5497,Buildings,Completed,NL-VALASARAVAKKAM,149,167000,"Improvements to community well at brindhavan nagar gasifier burial ground in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5499,Buildings,Completed,NL-VALASARAVAKKAM,149,101000,"Improvements to community well at gandhi road thiru.vi.ka park in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5783,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,525000,"Desilting of SWD at various streets in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/5785,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,600500,"Minor Repair Works at various streets in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/5948,Roads,Completed,NL-VALASARAVAKKAM,149,198000,"Improvements to interior BT road at AGS Colony Thilagar Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2019-20,2020-21 NL/2019-20/5951,Roads,Completed,NL-VALASARAVAKKAM,149,614000,"Improvements to interior BT road Angalaparameswari Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2019-20,2020-21 NL/2019-20/5952,Roads,Completed,NL-VALASARAVAKKAM,149,207000,"Improvements to interior BT road at Thirumalai Nagar 1st Street in Dn - 149, U - 33, Z - XI.",Loans And Grants,11,2019-20,2020-21 NL/2019-20/7198,Roads,Completed,NL-VALASARAVAKKAM,149,93000,"Providing inlet pipe and chambers at Arcot road Jn.of Sridevikuppam main road and Arcot Road junction of Visalatchi Street in - Dn-149,Unit-33-Zone-XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/7662,Roads,Completed,NL-VALASARAVAKKAM,149,401000,"Attending Patches at Various Streets in Dn - 149, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8790,Buildings,Completed,NL-VALASARAVAKKAM,149,480000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete at Brindavan Nagar Burial Ground in Div - 149, Unit - 33, Zone - 11",Own Sources,11,2019-20,2019-20 NL/2019-20/9466,Buildings,Completed,NL-VALASARAVAKKAM,149,869000,"Providing Bailing Centre with MRF for Dry waste Collections at Gandhi Road in Dn - 149, U - 33, Z - XI",Own Sources,11,2019-20,2020-21 D/2019-20/10431,Storm Water Drain,Completed,D-Storm Water Drains,150,570000,"Construction of top slab in existing open Storm Water Drain of Size 3000X1500 mm along Perumal koil 2nd Street in Dn-150, Zone 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/1263,Buildings,Completed,NL-VALASARAVAKKAM,150,294000,"PROPOSED CONSTRUCTION OF MATRIAL RECOVERY FACILITY AT GANDHI NAGAR BURIAL GROUND IN DN - 150, U - 34, Z - XI.",Loans And Grants,11,2019-20,2019-20 NL/2019-20/1439,Parks,Completed,NL-VALASARAVAKKAM,150,249000,"Name of the Work: Supplying and Fixing of Well Rings for composting Purpose at various location (22 Nos) in Div - 150, Unit - 34, Zone - 11",Own Sources,11,2019-20,2019-20 NL/2019-20/1537,Parks,Completed,NL-VALASARAVAKKAM,150,100000,"Name of the Work: Providing Mulchi Pit for dry waste composting at various location (10 Nos) in Div - 150, Unit - 34, Zone - 11",Own Sources,11,2019-20,2019-20 NL/2019-20/3977,Buildings,Completed,NL-VALASARAVAKKAM,150,235000,"IMPROVEMENTS WORK AT EXISTING COMPOST YARD AT GANDHI NAGAR MAIN ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/4999,Buildings,Completed,NL-VALASARAVAKKAM,150,1127000,"PROPOSED MCC AT GANDHI NAGAR BURIAL GROUND GANDHI NAGAR MAIN ROAD KARAMBAKKAM IN DIV ? 150, U -34, ZONE - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/5363,Parks,Completed,NL-VALASARAVAKKAM,150,522000,"Maintenance for Park at Parasnath Nagar Sayarbhai Street (Total Area - 6347 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5365,Parks,Completed,NL-VALASARAVAKKAM,150,323000,"Maintenance for Park at Phase - I Maruthi nagar OSR Land (Total Area - 2676 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5366,Parks,Completed,NL-VALASARAVAKKAM,150,167000,"Maintenance for Park at Phase -III Maruthi nagar OSR Land (Total Area - 1338 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5367,Parks,Completed,NL-VALASARAVAKKAM,150,168000,"Maintenance for Park at Ponniamman Nagar (Total Area - 1000 Sq.m) in Dn - 150, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5672,Buildings,Completed,NL-VALASARAVAKKAM,150,3169000,"PROPOSED MCC AT THUNDALAM BURIAL GROUND THUNDALAM ERIKARAI STREET IN DIV ? 150, U -34, ZONE - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/5838,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,579476,"MINOR REPAIRS WORKS TO SIDE DRAIN AND SWD AT VARIOUS STREET IN DN-150, UNIT-34, ZONE-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/5849,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,493000,"DESILTING OF SWD AND SIDE DRAIN AT VARIOUS LOCATION IN DIV - 150, UNIT - 34, ZONE - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/7791,Roads,Completed,NL-VALASARAVAKKAM,150,506000,"ATTENDING MINOR POT HOLES WITH USING CEMENT CONCRETE AT VARIOUS STREETS IN DIV - 150, UNIT -34. ZONE - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/9807,Buildings,Completed,NL-VALASARAVAKKAM,150,500000,"REPAIR AND MAINTENANCE OF AMMA UNAVAGAM AT PONNI NAGAR MULLAI STREET AND CHETTIYAR AGARAM ROAD IN DIV - 150, UNIT - 34, ZONE - 11",Own Sources,11,2019-20,2019-20 L/2019-20/0149,Electrical,Completed,B-Buildings,151,4710000,"Supply ,Erection,Testing and Commissioning of 500 KVA transformer and availing H.T.Supply at 100 Bedded Hospital (Ccommunity Health Centre),Hospital Road, Chinna Porur,Division -151, Zone-XI",Own Sources,11,2019-20,2019-20 NL/2019-20/0818,Buildings,Completed,NL-VALASARAVAKKAM,151,345000,"Providing Bore well arrangements at Cremetorium and Unit - 34 Office Building in Div-151, Unit-34, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/1433,Buildings,Completed,NL-VALASARAVAKKAM,151,294000,"PROPOSED CONSTRUCTION OF RESOURCE RECOVERY CENTRE AT ANJANEYAR KOVIL AMMA UNAVAGAM IN DN-151,UNIT-34,ZONE-11.",Loans And Grants,11,2019-20,2019-20 NL/2019-20/2230,Buildings,Completed,NL-VALASARAVAKKAM,151,30400,"Providing Mulch Pit for Dry Waste Composting Purpose at Various Places in Dn-151,Unit-34,zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/2231,Buildings,Completed,NL-VALASARAVAKKAM,151,69200,"Supplying and Fixing of Well Rings for Composting Purpose at Various Places in Dn-151,Unit-34,zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/4057,Buildings,Completed,NL-VALASARAVAKKAM,151,200000,"Imporvement Works in Compost Yard At Alapakkam Cross Street in Dn-151, Unit-34,zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/4533,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,493000,"Desilting of side Drain and Storm Water Drain at Various Location in Dn-151, Unit-34,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/4944,Parks,Completed,NL-VALASARAVAKKAM,151,1294000,"Providing and Laying Paver Block At Chinna Porur Hospital in Div-151,Unit-34,zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5404,Parks,Completed,NL-VALASARAVAKKAM,151,101000,"Maintenance for Park at Sabari Nagar 5th street (Total Area - 927.50 Sq.m) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5407,Parks,Completed,NL-VALASARAVAKKAM,151,246000,"Maintenance for Park at T.C.G park (Total Area - 995 Sq.m) in Dn - 151, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5758,Roads,Completed,NL-VALASARAVAKKAM,151,1035000,"Relaying the BT Road At Sabari Nagar 1st Main Road in Div-151,Unit-34,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5771,Roads,Completed,NL-VALASARAVAKKAM,151,302000,"Relaying the BT Road At Thirumurugan Nagar 3rd Cross Street in Div-151,Unit-34,Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/5976,Roads,Completed,NL-VALASARAVAKKAM,151,238000,"Relaying the BT Road At Jawahar Nagar 1st Street in Div-151,Unit-34,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5977,Roads,Completed,NL-VALASARAVAKKAM,151,335000,"Relaying the BT Road At Jawahar Nagar 2nd Street in Div-151,Unit-34,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/6026,Roads,Completed,NL-VALASARAVAKKAM,151,204000,"Relaying the BT Road At Kalappan street in Div-151,Unit-34,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/6027,Roads,Completed,NL-VALASARAVAKKAM,151,281000,"Relaying the BT Road At Thirumurugan Nagar 1st Cross Street in Div-151,Unit-34,Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/6031,Roads,Completed,NL-VALASARAVAKKAM,151,280000,"Relaying the BT Road At Lakshmi Nagar 13th cross Street in Div-151,Unit-34,Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/6658,Roads,Completed,NL-VALASARAVAKKAM,151,859000,"Relaying the BT Road at Perumal kovil street In Div-151,Unit-34,Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/7511,Roads,Completed,NL-VALASARAVAKKAM,151,247000,"Road Cut Restoration at Lakshmi Street NSC Bose Nagar in div- 151, unit-34, zone- 11",Deposit Works,11,2019-20,2020-21 NL/2019-20/7582,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,609000,"Minor Repair Works At Various Street in Div-151,Unit-34,zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/7720,Buildings,Completed,NL-VALASARAVAKKAM,151,380000,"Attending Minor Pot Holes With Using Cement Concrete at Various Street in Div - 151, Unit - 34, Zone - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/8896,Buildings,Completed,NL-VALASARAVAKKAM,151,500000,"DIVISION MAINTENANCE IN DIV -151, UNIT -34, ZONE -XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/9672,Roads,Completed,NL-VALASARAVAKKAM,151,342000,"Relaying the BT Road At Thirumurugan Nagar 2nd Cross Street in Div-151,Unit-34,Zone-11",Own Sources,11,2019-20,2020-21 L/2019-20/5537,Electrical,Completed,L-Electrical,152,375000,"Construction of Cement Concrete Pedestial for 658 Nos of 6/7 Mtr Lamp post and 17 Nos of 8/9 Mtr Lamp post pedestial With White washing at Various locations in Divisions 152, Zone-XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/10245,Buildings,Completed,NL-VALASARAVAKKAM,152,513000,"Supplying and fixing Modular partition and Work station for Health department room in Zonal office building at Arcot Road in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/11138,Roads,Completed,NL-VALASARAVAKKAM,152,499000,"Roadcut Restroration work at Chowdry Nagar 5th Street in Dn - 152, U - 33, Z - XI.",Deposit Works,11,2019-20,2020-21 NL/2019-20/1421,Buildings,Completed,NL-VALASARAVAKKAM,152,46000,"Providing and Erecting Well Rings at Various Locations in Dn - 152, U- 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/1517,Buildings,Completed,NL-VALASARAVAKKAM,152,488000,"Providing Water Supply Arrangement at Zonal Office in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/4610,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,381000,"Providing R.W.H Arrangements for Sivan Kovil Pond Around the Buildings in Dn-152, Unit-33, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5351,Parks,Completed,NL-VALASARAVAKKAM,152,88000,"Maintenance for Park at Zonal Office park (Total Area - 253 Sq.m) in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5779,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,524000,"Desilting of SWD and Side drains at various streets in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/5780,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,348500,"Minor Repair works at various streets in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/7168,Roads,Completed,NL-VALASARAVAKKAM,152,260000,"Providing inlet pipe and chambers at Arcot road Near Perambur Srinivasa hotel to Lamech Street and Arcot Road Near Corporation Bank to SVS Nagar Main Road in - Dn-152,Unit-33-Zone-XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/7541,Buildings,Completed,NL-VALASARAVAKKAM,152,204000,"Providing RWH (Zone with other GCC Buildings) with other repair works to Zonal office building in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/7663,Roads,Completed,NL-VALASARAVAKKAM,152,506000,"Attending Patches at Various Streets in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8353,Parks,Completed,NL-VALASARAVAKKAM,152,275000,"Annual Maintenance of Park at Zonal Office (Total Park Area - 420 m2) in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8354,Parks,Completed,NL-VALASARAVAKKAM,152,232000,"Annual Maintenance of Bharathi Colony Park (Total Park Area - 416.32 m2) in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8355,Parks,Completed,NL-VALASARAVAKKAM,152,236000,"Annual Maintenance of Veerappa Nagar Children Play Space (Total Park Area - 583.26 m2) in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8375,Buildings,Completed,NL-VALASARAVAKKAM,152,285000,"Providing tiles repair works and painting work to Zonal office building in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/8379,Buildings,Completed,NL-VALASARAVAKKAM,152,332000,"Providing partition with cupboard arrangement and other repair works to Zonal office building in Dn - 152, U-33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8381,Buildings,Completed,NL-VALASARAVAKKAM,152,315000,"Providing shed arrangement with flooring for Genshed of Zonal office building in Dn - 152, U-33, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/9066,Buildings,Completed,NL-VALASARAVAKKAM,152,517000,"Formation of Kabbadi Court with International Standards (Size of Court 13m x 10m with service area excluding) at Corporation Playground at Arcot Road in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2021-22 NL/2019-20/9180,Buildings,Completed,NL-VALASARAVAKKAM,152,1337000,"Construction of Audience Gallery (Size L=28.00M ,WIDTH = 3.50 M) for Kabbadi Court and Tennis Court at Corporation Playground at Arcot Road in Dn - 152, U - 33, Z - XI.",Own Sources,11,2019-20,2021-22 NL/2019-20/9310,Roads,Completed,NL-VALASARAVAKKAM,152,749000,"Roadcut Restroration work at Bharathiyar Street and Thirunagar Annex in Dn - 152, U - 33, Z - XI.",Deposit Works,11,2019-20,2020-21 NL/2019-20/9311,Roads,Completed,NL-VALASARAVAKKAM,152,624000,"Roadcut Restroration work at Suresh Nagar Main Road in Dn - 152, U - 33, Z - XI.",Deposit Works,11,2019-20,2020-21 D/2019-20/5281,Storm Water Drain,Completed,D-Storm Water Drains,153,2925000,"Construction of Storm Water Drain of Size 600X750 mm along Jaya bharathi nagar 1st & 2nd street from dead end to the existing drain in Jaya bharathi nagar main road in Dn.153, Zone 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/0123,Roads,Completed,NL-VALASARAVAKKAM,153,1343000,"Providing street name board at various streets (50 Nos) in Div-153, U-34, Z-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/10604,Buildings,Completed,NL-VALASARAVAKKAM,153,488000,"Maintenance works at various locations in Dn - 153, U - 34, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/1416,Buildings,Completed,NL-VALASARAVAKKAM,153,36000,"Providing and Placing of Well Rings at Mount Poonthamalle Road Amma Unavagam, Arivarasan Salai and Udaya Nagar OSR Land (3 Nos) in Dn-153, Unit-34, Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/16917,Roads,Completed,NL-VALASARAVAKKAM,153,1048000,"Relaying of Interior BT road at Subashree Nagar 7th Cross Street in DN-153, Unit-34, Zone-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/16921,Roads,Completed,NL-VALASARAVAKKAM,153,538000,"Relaying of Interior road at Ambal Nagar Kurinji Street in DN-153, Unit-34, Zone-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/4645,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,508000,"Desilting of Storm water drain and Side drain at various streets in Div-153, U-34, Z-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5397,Parks,Completed,NL-VALASARAVAKKAM,153,88000,"Maintenance for Park at Kanniyappan salai (Total Area - 796.70 Sq.m) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5401,Parks,Completed,NL-VALASARAVAKKAM,153,150000,"Maintenance for Park at Ramakrishna nagar (Total Area - 753.47 Sq.m) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5403,Parks,Completed,NL-VALASARAVAKKAM,153,109000,"Maintenance for Park at Ramaswamy nagar (Total Area - 1033.26 Sq.m) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5753,Storm Water Drain,Completed,NL-VALASARAVAKKAM,153,599500,"Minor Repair work to existing drain at Thiruveethiamman Koil 2nd & 3rd Street, Palayakara Street, Meiyammai Street in Dn - 153, U - 34, Z - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/8356,Parks,Completed,NL-VALASARAVAKKAM,153,236000,"Annual Maintenance of Park at Kanniappan Salai (Total Park Area - 796.70 m2) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8357,Parks,Completed,NL-VALASARAVAKKAM,153,241000,"Annual Maintenance of Park at Ramakrishna Nagar (Total Park Area - 753.47 m2) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8358,Parks,Completed,NL-VALASARAVAKKAM,153,431000,"Annual Maintenance of Park at Ramasamy Nagar (Total Park Area - 1033.26 m2) in Dn - 153, U - 34, Z - XI.",Own Sources,11,2019-20,2020-21 NL/2019-20/8497,Roads,Completed,NL-VALASARAVAKKAM,153,637000,"Attending Minor Pot Holes With Using Cement Concrete at Various Street in Div - 153, Unit - 34, Zone - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/1264,Buildings,Completed,NL-VALASARAVAKKAM,154,46000,"Supplying and Fixing of Well Rings for composting purpose Various Places in Dn-154 ,Unit-34, Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/1417,Buildings,Completed,NL-VALASARAVAKKAM,154,10000,"Providing and mulch pit for composting purpose at various streets in Dn-154 st,Unit-34, Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/4539,Buildings,Completed,NL-VALASARAVAKKAM,154,525000,"Desilting of Side drians and SWD at various street in Dn-154, Unit-34, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/5352,Parks,Completed,NL-VALASARAVAKKAM,154,93000,"Maintenance for Park at Kurinji Nagar 3rd cross street (Total Area - 979.58 Sq.m) in Dn - 154, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/7361,Buildings,Completed,NL-VALASARAVAKKAM,154,488000,"PROVIDING RAIN WATER HARVESTING STRUCTURES AT VARIOUS LOCATIONS IN DN154,U34,Z11.",Own Sources,11,2019-20,2019-20 NL/2019-20/8203,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,600000,"Repair and Improvement Minor repair at various street in Dn-154, Unit-34, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/8493,Roads,Completed,NL-VALASARAVAKKAM,154,1150000,"Attending Patch work at Various streets in Dn-154, Unit-34, Zone-11",Own Sources,11,2019-20,2020-21 NL/2019-20/8538,Parks,Completed,NL-VALASARAVAKKAM,154,585000,"ANNUAL MAINTENANCE OF KURINJI NAGAR PARK (TOTAL PARK AREA-790 M2) AT KURINJI NAGAR 3RD STREET IN DN.154, U 34, Z 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/10767,Parks,Completed,NL-VALASARAVAKKAM,155,994000,"Formation of Urban forest (Miyawaki method) in GCC OSR land survey No. 56 at Rayala nagar 2nd main road, Ramapuram in Dn-155, Unit-34, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/1423,Buildings,Completed,NL-VALASARAVAKKAM,155,92000,"Supplying and Fixing of Well Rings for composting purpose Various Places in Dn-155 ,Unit-34, Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/4988,Roads,Completed,NL-VALASARAVAKKAM,155,1749000,"Improvements to Interior BT road at Annai sathya nagar main road in division 155, unit-34, zone- 11",Deposit Works,11,2019-20,2019-20 NL/2019-20/5408,Parks,Completed,NL-VALASARAVAKKAM,155,93000,"Maintenance for Park at Eswaran Nagar (Total Area - 611.16 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5410,Parks,Completed,NL-VALASARAVAKKAM,155,94000,"Maintenance for Park at Giri Nagar (Total Area - 688.24 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5413,Parks,Completed,NL-VALASARAVAKKAM,155,88000,"Maintenance for Park at Jai Balaji Nagar (Total Area - 405.92 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5415,Parks,Completed,NL-VALASARAVAKKAM,155,165000,"Maintenance for Park at Azhagapuri Nagar (Total Area - 1052.64 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5417,Parks,Completed,NL-VALASARAVAKKAM,155,146000,"Maintenance for Park at K.P.Nagar (Total Area - 768.60 Sq.m) in Dn - 155, U - 34, Z - XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/5470,Buildings,Completed,NL-VALASARAVAKKAM,155,319000,"Proposed construction of Material Recovery Facility at Thiruvalluvar salai OSR land in DN-155, Unit-34, Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/5516,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,326000,"Improvement and Minor repairs to existing Side drain and SWD at Various Street in Dn-155, Unit-34, Zone-11.",Own Sources,11,2019-20,2019-20 NL/2019-20/7476,Roads,Completed,NL-VALASARAVAKKAM,155,285000,"Relaying of Interior road at Thirumalai Nagar Angel street in DN-155, Unit-34, Zone-XI",Own Sources,11,2019-20,2020-21 NL/2019-20/7784,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,525000,"Desilting of Side drain and Storm water drain at various location in DN-155, Unit-34, Zone-XI.",Own Sources,11,2019-20,2019-20 NL/2019-20/7796,Roads,Completed,NL-VALASARAVAKKAM,155,538000,"Attending Minor Pot Holes With Using Cement Concrete at Various Street in Div - 155, Unit - 34, Zone - 11",Own Sources,11,2019-20,2020-21 NL/2019-20/8532,Parks,Completed,NL-VALASARAVAKKAM,155,581000,"ANNUAL MAINTENANCE OF GIRI NAGAR PARK (TOTAL PARK AREA-750 M2) AT GIRI NAGAR 1ST STREET IN DN.155, U 34, Z 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/8533,Parks,Completed,NL-VALASARAVAKKAM,155,578000,"ANNUAL MAINTENANCE OF ESWARAN NAGAR PARK (TOTAL PARK AREA-646 M2) AT ESWARAN NAGAR 3RD STREET IN DN.155, U 34, Z 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/8534,Parks,Completed,NL-VALASARAVAKKAM,155,634000,"ANNUAL MAINTENANCE OF AZHAGAPURI NAGAR PARK (TOTAL PARK AREA-1132 M2) AT AZHAGAPURI NAGAR 6TH AVENUE IN DN.155, U 34, Z 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/8535,Parks,Completed,NL-VALASARAVAKKAM,155,582000,"ANNUAL MAINTENANCE OF KP NAGAR PARK (TOTAL PARK AREA- 970 M2) AT KP NAGAR MAIN ROAD IN DN.155, U 34, Z 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/8536,Parks,Completed,NL-VALASARAVAKKAM,155,241000,"ANNUAL MAINTENANCE OF JAI BALAJI NAGAR PARK (TOTAL PARK AREA-406 M2) AT JAI BALAJI NAGAR 1ST MAIN ROAD IN DN.155, U 34, Z 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/8537,Parks,Completed,NL-VALASARAVAKKAM,155,664000,"ANNUAL MAINTENANCE OF RAYALA NAGAR PARK (TOTAL PARK AREA-1319 M2) AT RAYALA NAGAR 1ST MAIN ROAD IN DN-155, U 34, Z 11.",Own Sources,11,2019-20,2020-21 NL/2019-20/8898,Buildings,Completed,NL-VALASARAVAKKAM,155,999000,"Construction of MCC (Micro Compost Centre) at Thiruvalluvar salai Burial Ground in DN-155, Unit-34, Zone-11",Own Sources,11,2019-20,2021-22 NL/2019-20/9382,Roads,Completed,NL-VALASARAVAKKAM,155,114000,"Providing pipe line to storm water drain at EVP santhosh nagar 1st cross street (from EVP santhosh nagar 1st cross street to EVP santhosh nagar 3rd main road) in DN-155, Unit-34, Zone-11.",Own Sources,11,2019-20,2020-21 NL/2019-20/9439,Buildings,Completed,NL-VALASARAVAKKAM,155,483000,"Various Repairs and Maintenence work in roads and Building in DN-155, Unit-34, Zone-11",Own Sources,11,2019-20,2019-20 L/2019-20/10305,Electrical,Completed,L-Electrical,156,999100,REPLACEMENT OF 1050 MTR OF DAMAGED 4X16 SQMM AND 594 MTR OF DAMAGED 2X16 SQMM 7 NOS OF 6 MTR LAMP POST AND 7 NOS OF 8MTR LAMP POST IN SAROJINI STREET AND DHANAM NAGAR IN DN-156 Z-12,Own Sources,12,2019-20,2020-21 L/2019-20/5467,Electrical,Completed,L-Electrical,156,3638300,"DUE TO STORM WATER DRAIN WORK THE EXISTING LAMP POST FOUNDATION AND CABLE GET DAMAGE FOR RECONSTRUCTION OF 37 NOS OF 6MTR LAMP POST WITH STRIAGHT BRACKET AND RELAYING 5318M 2X16SQMM CABLE AT RAJESWERI NAGAR, BELL NAGAR, JAYALASHMI NAGAR, RAMYA NAGAR, MADHA NAGAR, GURUSAMY NAGAR AND KAMACHI NAGAR IN DN-156 ZONE 12",Own Sources,12,2019-20,2021-22 L/2019-20/5480,Electrical,Completed,L-Electrical,156,3117600,"REFIXING OF OF 51 NOS OF 6MTROLD LAMP POST WITH ARCH BRACKET WITH 51NOS OF 40W LED FITTING AND LAYING OF 3499M 2X16SQMM CABLE AT HIMACAHL NAGAR, VND RAJESHWERI AVENUE,LALITHA NAGAR, THIRUMOORTHY NAGAR IN DN 156 ZONE 12",Own Sources,12,2019-20,2020-21 L/2019-20/6643,Electrical,Completed,L-Electrical,156,160400,REMOVAL AND REFIXING OF 4 NOS 6MTR LAMP POST AT BLACK BERRY STREET AND 2 NOS AT S.S KOIL STREET DN-156 ZONE-12,Own Sources,12,2019-20,2020-21 L/2019-20/8372,Electrical,Completed,L-Electrical,156,2644600,SUPPLY & ERECTION AND COMMISIONING OF 15 NOS OF 8MTR GI POST WITH DOUBLE ARCH BRACKET WITH 150 TO 165W LED FITTINGS AND 5NOS OF 8MTR POST WITH TRIBLE ARCH BRACKET WITH 45NOS OF 150 TO 165 LED FITTING AT KUNDRATHUR MAIN ROAD IN DN 156 ZONE 12,Grants,12,2019-20,2021-22 NM/2019-20/1106,Buildings,Completed,NM-ALANDUR,156,294000,"'PROPOSED CONSTRUCTION OF MATRIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT KUNDRUMEDU STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/1108,Buildings,Completed,NM-ALANDUR,156,294000,"'PROPOSED CONSTRUCTION OF MATRIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT OTHAVADAI STREET NEAR COMPOST YARD IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/1179,Buildings,Completed,NM-ALANDUR,156,294000,"'PROPOSED CONSTRUCTION OF MATRIAL RECOVERY FACILITY IN GREATER CHENNAI CORPORATION AT XS REAL PARK NEAR COMPOST YARD IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/1214,Parks,Completed,NM-ALANDUR,156,363000,"PROVIDING MULCH PIT FOR DRY WASTE COMPOSTING PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DN-156,157,158,160,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/1235,Parks,Completed,NM-ALANDUR,156,842000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DN-156,157,158,160,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/15460,Buildings,Completed,NM-ALANDUR,156,132000,"Repair and maintenance work of pc at varios street in dn-156 u-35,z-12",Own Sources,12,2019-20,2021-22 NM/2019-20/15461,Storm Water Drain,Completed,NM-ALANDUR,156,113000,"Repair and maintenance work of swd at various street in dn-156 u-35,z-12",Own Sources,12,2019-20,2021-22 NM/2019-20/15462,Roads,Completed,NM-ALANDUR,156,53000,"Repair and maintenance work of Road at varios street in dn-156 u-35,z-12",Own Sources,12,2019-20,2021-22 NM/2019-20/15463,Buildings,Completed,NM-ALANDUR,156,194000,"Repair and maintenance work of Building at varios street in dn-156 u-35,z-12",Own Sources,12,2019-20,2021-22 NM/2019-20/15874,Buildings,Completed,NM-ALANDUR,156,586000,"ANNUAL MAINTENANCE OF SSL GREEN PARK IN DN 156,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15876,Parks,Completed,NM-ALANDUR,156,1251000,"ANNUAL MAINTENANCE OF KALAIMAGAL NAGAR PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15888,Parks,Completed,NM-ALANDUR,156,733000,"ANNUAL MAINTENANCE OF IVND AVENUE VAIGAI STREET PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15889,Parks,Completed,NM-ALANDUR,156,574000,"ANNUAL MAINTENANCE OF SABARI NAGAR 1ST MAIN ROAD CHILDRENS PARK DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15890,Parks,Completed,NM-ALANDUR,156,930000,"ANNUAL MAINTENANCE OF KUMUTHAM NAGAR PARK DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15891,Parks,Completed,NM-ALANDUR,156,638000,"ANNUAL MAINTENANCE OF MERY GOLD STREET PARK DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15892,Parks,Completed,NM-ALANDUR,156,630000,"ANNUAL MAINTENANCE OF VISWANATHAN PALANI STREET PARK DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15893,Parks,Completed,NM-ALANDUR,156,951000,"ANNUAL MAINTENANCE OF CRR PURAM L&T COLONY PARK DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15894,Parks,Completed,NM-ALANDUR,156,652000,"ANNUAL MAINTENANCE OF SABARI NAGAR 2ND MAIN ROAD PARK DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15895,Parks,Completed,NM-ALANDUR,156,658000,"ANNUAL MAINTENANCE OF ANNAIVELANKANNI NAGAR PH-1 2ND STREET PARK DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15896,Parks,Completed,NM-ALANDUR,156,905000,"ANNUAL MAINTENANCE OF AGS COLONY PH-3 MAIN ROAD PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15897,Parks,Completed,NM-ALANDUR,156,622000,"ANNUAL MAINTENANCE OF ASABARI NAGAR 5TH STREET PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15898,Parks,Completed,NM-ALANDUR,156,658000,"ANNUAL MAINTENANCE OF DEVADOSS STREET PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15899,Parks,Completed,NM-ALANDUR,156,1129000,"ANNUAL MAINTENANCE OF THIRUVALLUVAR NAGAR NATHAMUNI STREET PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15900,Parks,Completed,NM-ALANDUR,156,689000,"ANNUAL MAINTENANCE OF SINDHU SALAI STREET PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15901,Parks,Completed,NM-ALANDUR,156,869000,"ANNUAL MAINTENANCE OF MADHA NAGAR 2ND MAIN ROAD PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15902,Parks,Completed,NM-ALANDUR,156,626000,"ANNUAL MAINTENANCE OF KUNDRATHUR MAIN ROAD PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15903,Parks,Completed,NM-ALANDUR,156,230000,"ANNUAL MAINTENANCE OF SUBHASRI NAGAR EXTN 5 CHILDRENS PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15904,Parks,Completed,NM-ALANDUR,156,1345000,"ANNUAL MAINTENANCE OF SANTHOSH NAGAR RAMACHANDRAN STREET PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15988,Parks,Completed,NM-ALANDUR,156,625000,"ANNUAL MAINTENANCE OF ANNAIVELANKANNI NAGAR PH-1 5TH STREET PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15989,Parks,Completed,NM-ALANDUR,156,949000,"ANNUAL MAINTENANCE OF ANNAIVELANKANNI NAGAR PH-2 MAIN ROAD PARK IN DN 156, UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16459,Roads,Completed,NM-ALANDUR,156,2746000,"FORMATION OF ROAD ALUVANCHERI - PERUMAL KOVIL STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16461,Roads,Completed,NM-ALANDUR,156,1144000,"FORMATION OF ROAD KUNDRUMEDU USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16463,Roads,Completed,NM-ALANDUR,156,407000,"FORMATION OF ROAD KAMATCHI NAGAR 3RD CROSS STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16467,Roads,Completed,NM-ALANDUR,156,1276000,"FORMATION OF BT ROAD AT BAJANAI KOIL STREET KIZHAL COLONY USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16468,Roads,Completed,NM-ALANDUR,156,1002000,"FORMATION OF ROAD ALUVANCHERY MARIAMMAN KOIL STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16470,Roads,Completed,NM-ALANDUR,156,1011000,"FORMATION OF ROAD THIRUPURASUNTHARI AVENUE USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16472,Roads,Completed,NM-ALANDUR,156,976000,"FORMATION OF ROAD SUBHASRI NAGAR EXTN 3RD 1ST CROSS STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16474,Roads,Completed,NM-ALANDUR,156,595000,"FORMATION OF ROAD SUBHAIYA NAGAR VENKADACHALAM STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16477,Roads,Completed,NM-ALANDUR,156,293000,"FORMATION OF ROAD RGL PH-3 USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16479,Roads,Completed,NM-ALANDUR,156,691000,"FORMATION OF ROAD MUGALIVAKKAM COLONY DHULLUKANATHAMMAN KOIL STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16480,Roads,Completed,NM-ALANDUR,156,529000,"FORMATION OF ROAD MRK NAGAR PARK STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16481,Roads,Completed,NM-ALANDUR,156,995000,"FORMATION OF ROAD METTUKUPPAM PERUMAL KOIL STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16484,Roads,Completed,NM-ALANDUR,156,574000,"FORMATION OF ROAD ALUVANCHERY MARAN AVENUE USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16485,Roads,Completed,NM-ALANDUR,156,750000,"FORMATION OF ROAD KUMARI NAGAR 2ND STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16486,Roads,Completed,NM-ALANDUR,156,780000,"FORMATION OF ROAD KUMARI NAGAR 1ST STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16487,Roads,Completed,NM-ALANDUR,156,1481000,"FORMATION OF ROAD KAMATCHI AMMAN NAGAR USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16488,Roads,Completed,NM-ALANDUR,156,1786000,"FORMATION OF ROAD GK NAGAR USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16552,Roads,Completed,NM-ALANDUR,156,310000,"ROAD CUT RESTORATION OF BT ROAD AT AMIRTHALINGAM SALAI USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16553,Roads,Completed,NM-ALANDUR,156,426000,"ROAD CUT RESTORATION OF BT ROAD AT KAMATCHI NAGAR 2ND CROSS STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16574,Roads,Completed,NM-ALANDUR,156,437000,"FORMATION OF BT ROAD OF PERUMAL KOIL STREEET EXTN USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16576,Roads,Completed,NM-ALANDUR,156,236000,"FORMATION OF BT ROAD AT MUTHU MARIAMMAN NAGAR ANDAL AVENUE USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16616,Roads,Completed,NM-ALANDUR,156,910000,"FORMATION OF BT ROAD AT VASUGII STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16617,Roads,Completed,NM-ALANDUR,156,618000,"FORMATION OF BT ROAD AT VAIGAI STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16838,Roads,Completed,NM-ALANDUR,156,195000,"ROAD CUT RESTORATION OF BT ROAD AT THIRUMURTHI NAGAR 1ST STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16839,Roads,Completed,NM-ALANDUR,156,763000,"ROAD CUT RESTORATION OF BT ROAD AT THIRUMURTHI NAGAR 2ND STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16840,Roads,Completed,NM-ALANDUR,156,155000,"ROAD CUT RESTORATION OF CC ROAD AT SUBHASREE NAGAR EXTN 3-7TH MAIN ROAD USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16842,Roads,Completed,NM-ALANDUR,156,136000,"ROAD CUT RESTORATION OF CC ROAD AT KRISHNAVENI NAGAR WEST MAIN ROAD USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16843,Roads,Completed,NM-ALANDUR,156,410000,"ROAD CUT RESTORATION OF CC ROAD AT KRISHNAVENI NAGAR SOUTH MAIN ROAD USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16844,Roads,Completed,NM-ALANDUR,156,259000,"ROAD CUT RESTORATION OF CC ROAD AT KRISHNAVENI NAGAR MAIN ROAD USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16845,Roads,Completed,NM-ALANDUR,156,323000,"ROAD CUT RESTORATION OF CC ROAD AT SUBHASREE NAGAR EXTN-II (5TH MAIN ROAD) USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16846,Roads,Completed,NM-ALANDUR,156,399000,"ROAD CUT RESTORATION OF CC ROAD AT SUBHASREE NAGAR EXTN-III (6TH MAIN ROAD) USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16847,Roads,Completed,NM-ALANDUR,156,129000,"ROAD CUT RESTORATION OF CC ROAD AT SUBHASREE NAGAR EXTN-III (2ND CROSS STREET) USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16848,Roads,Completed,NM-ALANDUR,156,242000,"ROAD CUT RESTORATION OF CC ROAD AT SELVAGANAPAHI NAGAR EAST MAIN ROAD USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16849,Roads,Completed,NM-ALANDUR,156,830000,"ROAD CUT RESTORATION OF CC ROAD AT SABARI NAGAR EXTN 2ND MAIN ROAD PART 2 USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16850,Roads,Completed,NM-ALANDUR,156,647000,"ROAD CUT RESTORATION OF CC ROAD AT KAMTCHI NAGAR MAIN ROAD USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16851,Roads,Completed,NM-ALANDUR,156,93000,"ROAD CUT RESTORATION OF CC ROAD AT KAMTCHI NAGAR 5TH CROSS STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16852,Roads,Completed,NM-ALANDUR,156,108000,"ROAD CUT RESTORATION OF CC ROAD AT KAMTCHI NAGAR 1ST CROSS STREET USING PAVER FINISHER IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17646,Roads,Completed,NM-ALANDUR,156,591000,"FORMATION OF CC ROAD AT VV KOIL LANE-2 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17647,Roads,Completed,NM-ALANDUR,156,240000,"FORMATION OF CC ROAD AT VV KOIL LANE-1 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17648,Roads,Completed,NM-ALANDUR,156,287000,"FORMATION OF CC ROAD AT BHELL NAGAR EXTENSION IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17649,Roads,Completed,NM-ALANDUR,156,917000,"FORMATION OF CC ROAD AT SS KOIL EXTENSION-1 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17650,Roads,Completed,NM-ALANDUR,156,383000,"FORMATION OF CC ROAD AT PERUMAL KOIL EXTENSION-5 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17651,Roads,Completed,NM-ALANDUR,156,289000,"FORMATION OF CC ROAD AT PERUMAL KOIL EXTENSION-4 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17652,Roads,Completed,NM-ALANDUR,156,280000,"FORMATION OF CC ROAD AT PERUMAL KOIL EXTENSION-3 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17653,Roads,Completed,NM-ALANDUR,156,485000,"FORMATION OF CC ROAD AT PERUMAL KOIL EXTENSION-2 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17654,Roads,Completed,NM-ALANDUR,156,476000,"FORMATION OF CC ROAD AT PERUMAL KOIL EXTENSION-1 IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17667,Roads,Completed,NM-ALANDUR,156,1057000,"FORMATION OF BT ROAD AT SANTHOSH NAGAR 1ST STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17668,Roads,Completed,NM-ALANDUR,156,704000,"FORMATION OF BT ROAD AT SANTHOSH NAGAR 2ND STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17669,Roads,Completed,NM-ALANDUR,156,1207000,"FORMATION OF BT ROAD AT SANTHOSH NAGAR MAHALINGAM STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17670,Roads,Completed,NM-ALANDUR,156,509000,"FORMATION OF BT ROAD AT ANANDHA NAGAR CROSS STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17671,Roads,Completed,NM-ALANDUR,156,768000,"FORMATION OF BT ROAD AT THIRUVALLUVAR NAGAR MURUGESNAR STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17672,Roads,Completed,NM-ALANDUR,156,691000,"FORMATION OF BT ROAD AT BRINDHAVAN GARDEN EXTN IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17673,Roads,Completed,NM-ALANDUR,156,2346000,"FORMATION OF BT ROAD AT VGN LAKSHMI NAGAR DEVARAJ STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17674,Roads,Completed,NM-ALANDUR,156,2098000,"FORMATION OF BT ROAD AT VGN LAKSHMI NAGAR YAMUNA STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17675,Roads,Completed,NM-ALANDUR,156,2339000,"FORMATION OF BT ROAD AT VGN LAKSHMI NAGAR KUMARASAMY STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17676,Roads,Completed,NM-ALANDUR,156,351000,"FORMATION OF BT ROAD AT VGN LAKSHMI NAGAR MAHADEVAN STREET IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17677,Roads,Completed,NM-ALANDUR,156,550000,"FORMATION OF BT ROAD AT LALITHAMBAL NAGAR LANE IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17678,Roads,Completed,NM-ALANDUR,156,241000,"FORMATION OF BT ROAD AT DEVADOSS STREET EXTN IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17679,Roads,Completed,NM-ALANDUR,156,687000,"FORMATION OF BT ROAD AT ANNAVELANKANNI NAGAR PHASE-2 MAIN ROAD (PART) IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17680,Roads,Completed,NM-ALANDUR,156,1100000,"FORMATION OF BT ROAD AT KUMUTHAM NAGAR EXTN IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/1876,Buildings,Completed,NM-ALANDUR,156,2995000,"CONSTRUCTION OF COMPOST YARD INCLUDING WATER FACILITY ,SUPPLYING AND ERECTION OF BIO-SHREDDING PULVERIZED MACHINE,MANURE SEIVER MACHINE AND WEIGHING MACHINE AT KUNDRU MEDU BURIAL GROUND IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/2050,Buildings,Completed,NM-ALANDUR,156,760000,"PROVIDING YOGA SHED AT AGS COLONY PH-3 PARK IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/2314,Parks,Completed,NM-ALANDUR,156,327000,ANNUAL MAINTENANCE OF PARK AT KUMUDHAN NAGAR IN DN 156 ZONE 12 (5MONTHS FROM 01.04.2019 TO 31.08.2019),Own Sources,12,2019-20,2019-20 NM/2019-20/2315,Parks,Completed,NM-ALANDUR,156,339000,ANNUAL MAINTENANCE OF PARK AT CRR PURAM (L& T)PARK IN DN 156 ZONE 12 (5MONTHS FROM 01.04.2019 TO 31.08.2019),Own Sources,12,2019-20,2019-20 NM/2019-20/2332,Parks,Completed,NM-ALANDUR,156,304000,ANNUAL MAINTENANCE OF PARK AT NATHAMUNI STREET IN DN 156 (5MONTHS FROM 01.04.2019 TO 31.08.2019),Own Sources,12,2019-20,2019-20 NM/2019-20/3270,Buildings,Completed,NM-ALANDUR,156,355000,"Improvement work of othavadai street compost yard in div-156,U-35,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/4366,Buildings,Completed,NM-ALANDUR,156,520000,Providing of Rain water harvesting structure and Improvement works to the existing RWH at various locations in div-156 u-35 z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/5287,Buildings,Completed,NM-ALANDUR,156,70000,Improvement works to the existing RCC at various locations in DIV-156 U-35 Z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/5288,Buildings,Completed,NM-ALANDUR,156,696000,Improvement works to the XS real compost yard in DIV-156 U-35 Z-12,Own Sources,12,2019-20,2019-20 NM/2019-20/5529,Parks,Completed,NM-ALANDUR,156,103000,ANNUAL MAINTENANCE OF THE PARK AT SABARI NAGAR 5TH STREET IN DN 156 (FOR THE PERIOD OF 01.04.2019 TO 31.08.2019),Own Sources,12,2019-20,2019-20 NM/2019-20/5664,Parks,Completed,NM-ALANDUR,156,83000,"ANNUAL MAINTENANCE FOR PARK AT KUNDRATHUR MAIN ROAD IN 156, ZONE 12(5 MONTHS)",Own Sources,12,2019-20,2019-20 NM/2019-20/5665,Parks,Completed,NM-ALANDUR,156,83000,ANNUAL MAINTENANCE FOR PARK AT VGN LAKSHMI NAGR VISHWANATHAN PALANI STREET IN DN 156(5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/5670,Parks,Completed,NM-ALANDUR,156,131200,"ANNUAL MAINTENANCE FOR PARK AT AGS COLONY, SABARI NAGAR 2ND MAIN ROAD IN DN 156, (5 MONTHS)",Own Sources,12,2019-20,2019-20 NM/2019-20/6252,Parks,Completed,NM-ALANDUR,156,332000,ANNUAL MAINTENANCE FOR PARK AT KALAIMAGAL NAGAR PARK IN DN 156 (5 MONTHS PERIOD),Own Sources,12,2019-20,2019-20 NM/2019-20/6547,Parks,Completed,NM-ALANDUR,156,873000,ANNUAL MAINTENANCE OF PARK AT SANTHOSH NAGAR IN DN 156 (1 YEAR)(01/09/2018 TO 31.08.2019),Own Sources,12,2019-20,2019-20 NM/2019-20/6641,Parks,Completed,NM-ALANDUR,156,171000,ANNUAL MAINTENANCE OF PARK AT MARRY GOLD STREET IN DN 156 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6642,Parks,Completed,NM-ALANDUR,156,150000,"ANNUAL MAINTENANCE OF PARK AT AGS COLONY, SABARI NAGAR 2ND MAIN ROAD IN DN 156 (5 MONTHS)",Own Sources,12,2019-20,2019-20 NM/2019-20/6644,Roads,Completed,NM-ALANDUR,156,989000,"ATTENDING WMM PATCH WORK AT MANGAIYAKARASI STREET AND 7 OTHERS ROAD IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/6645,Roads,Completed,NM-ALANDUR,156,1040500,"ATTENDING WMM PATCH WORK AT CRR PURAM EXTN AND 11 OTHERS ROAD IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/6646,Roads,Completed,NM-ALANDUR,156,967000,"ATTENDING WMM PATCH WORK AT MADHA NAGAR MAIN ROAD AND 6 OTHERS ROAD IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/6648,Parks,Completed,NM-ALANDUR,156,201000,ANNUAL MAINTENANCE OF PARK AT VND RAJESWARI AVENUE VAIGAI STREET IN DN 156 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6653,Parks,Completed,NM-ALANDUR,156,141000,"ANNUAL MAINTENANCE OF PARK AT SSI GREEN PARK, MADHANANDHAPURAM MAIN ROAD IN DN 156 (5 MONTHS)",Own Sources,12,2019-20,2019-20 NM/2019-20/6654,Parks,Completed,NM-ALANDUR,156,133400,ANNUAL MAINTENANCE OF PARK AT ANNAI VELANKANNI NAGAR PHASE 1 ST STREET IN DN 156 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6753,Parks,Completed,NM-ALANDUR,156,189900,ANNAUL MAINTENANCE OF PARK AT ANNAI VELANKANNI NAGAR PHASE 1 5TH STREET IN DN 156 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6755,Parks,Completed,NM-ALANDUR,156,250000,ANNUAL MAINTENANCE OF PARK AT MADHA NAGAR 2ND STREET IN DN 156 (5 MONTHS ),Own Sources,12,2019-20,2019-20 NM/2019-20/6765,Parks,Completed,NM-ALANDUR,156,168000,ANNUAL MAINTENANCE OF PARK AT GURUSAMY NAGAR DEVADOSS STREET IN DN 156(5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6766,Parks,Completed,NM-ALANDUR,156,186000,ANNUAL MAINATENANCE OF PARK AT VND RAJESWARI AVENUE SINDI STREET IN DN 156 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6817,Parks,Completed,NM-ALANDUR,156,371900,"ANNUAL MAINTENANCE FOR PARK AT AGS COLONY IN DN. 156, ZONE 12 (5 MONTHS)",Own Sources,12,2019-20,2019-20 NM/2019-20/6853,Parks,Completed,NM-ALANDUR,156,476000,ANNUAL MAINTENANCE OF PARK AT ANNAI VELANKANNI NAGAR PHASE 2 IN DN 156 (1 YEAR),Own Sources,12,2019-20,2019-20 NM/2019-20/7027,Roads,Completed,NM-ALANDUR,156,315000,"IMPROVEMENT WORKS FOR THE SIDE DRAIN AND PROVIDING PAVER BLOCKS AT V.V. KOIL STREET LANE IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/7029,Storm Water Drain,Completed,NM-ALANDUR,156,439000,"DESILTING OF EXISTING SWD AT VARIOUS STREET (60 NOS OF ROADST) IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/7031,Storm Water Drain,Completed,NM-ALANDUR,156,371000,"DESILTING OF EXISTING SWD AT VARIOUS STREET (117 NOS OF ROAD) IN DN-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/7033,Storm Water Drain,Completed,NM-ALANDUR,156,1144000,"MINOR REPAIRS WORKS OF SWD AND REPLACING OF MANHOLE DOORS AT VARIOUS STREET IN DIVISION-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/7046,Storm Water Drain,Completed,NM-ALANDUR,156,665000,"MINOR REPAIRS WORKS OF SWD AT VARIOUS STREET IN DIVISION-156,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/7056,Storm Water Drain,Completed,NM-ALANDUR,156,850000,"MINOR REPAIRS WORKS OF SWD AND REPLACING OF MANHOLE DOORS AT VARIOUS STREET IN DIVISION-156,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/7996,Roads,Completed,NM-ALANDUR,156,922600,"ATTENDING TEMPORARY PATCH WORK FOR POTHOLES AND ROAD CUT AT VARIOUS STREET IN DN - 156,157,158,159,160,161,UNIT-35 & 36,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/10127,Storm Water Drain,Completed,NM-ALANDUR,157,232900,"Desilting work in various location at Div-157,U-35,Z-12.",Own Sources,12,2019-20,2021-22 NM/2019-20/10359,Storm Water Drain,Completed,NM-ALANDUR,157,126100,"MINOR REPAIR WORKS IN SWD AT VARIOUS LOCATION IN Div -157,U-35,Z-12,",Own Sources,12,2019-20,2021-22 NM/2019-20/15840,Buildings,Completed,NM-ALANDUR,157,857000,"ANNUAL MAINTENANCE OF MARCO MARVAL PARK IN DN 157,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15841,Buildings,Completed,NM-ALANDUR,157,720000,"ANNUAL MAINTENANCE OF RIVER VIEW COLONY PH-I PARK IN DN 157,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15843,Buildings,Completed,NM-ALANDUR,157,673000,"ANNUAL MAINTENANCE OF RIVER VIEW PHASE-III PARK IN DN 157,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15844,Buildings,Completed,NM-ALANDUR,157,632000,"ANNUAL MAINTENANCE OF BEL NAGAR PARK IN DN 157,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15845,Buildings,Completed,NM-ALANDUR,157,646000,"ANNUAL MAINTENANCE OF KAVYA GARDEN PARK IN DN 157,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15846,Buildings,Completed,NM-ALANDUR,157,622000,"ANNUAL MAINTENANCE OF NAVEENS PARK IN DN 157,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/17657,Roads,Completed,NM-ALANDUR,157,881000,"FORMATION OF CC ROAD AT BEL NAGAR & THIRUVALLUVAR NAGAR LINK ROAD IN DN-157,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17658,Roads,Completed,NM-ALANDUR,157,712000,"FORMATION OF CC ROAD AT VALLISHWARAN KOIL CROSS ROAD IN DN-157,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17659,Roads,Completed,NM-ALANDUR,157,4671000,"FORMATION OF CC ROAD AT MACRO MARVEL MAIN ROAD IN DN-157,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17660,Roads,Completed,NM-ALANDUR,157,796000,"FORMATION OF CC ROAD AT MACRO MARVEL 7TH CROSS STREET (RIGHT) IN DN-157,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17661,Roads,Completed,NM-ALANDUR,157,1380000,"FORMATION OF CC ROAD AT MACRO MARVEL 8TH CROSS STREET (LEFT AND RIGHT) IN DN-157,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17662,Roads,Completed,NM-ALANDUR,157,1231000,"FORMATION OF CC ROAD AT MACRO MARVEL 9TH CROSS STREET (LEFT AND RIGHT) IN DN-157,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/3916,Buildings,Completed,NM-ALANDUR,157,202600,Providing of Rain water harvesting structure and Improvement works to the existing RWH at various locations in DIV-157 U-35 Z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/4740,Buildings,Completed,NM-ALANDUR,157,273000,"Improvement works to periya colony P.C in Division 157,Unit 35,Zone 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/6242,Buildings,Completed,NM-ALANDUR,157,134000,"Imrovement work at community well Periya colony 2 nos, various location at DIV-157,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/6254,Parks,Completed,NM-ALANDUR,157,175000,ANNUAL MAINTENANCE FOR PARK AT RIVER VIEW COLONY PHASE 2 IN DN 157(5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6257,Parks,Completed,NM-ALANDUR,157,202000,ANNUAL MAINTENANCE FOR PARK AT RIVER VIEW COLONY PHASE 1 IN DN 157 (5 MONTHS PERIOD),Own Sources,12,2019-20,2019-20 NM/2019-20/6259,Parks,Completed,NM-ALANDUR,157,179000,ANNUAL MAINTENANCE FOR PARK AT BHEL NAGAR IN DN 157 ( 5 MONTHS PERIOD),Own Sources,12,2019-20,2019-20 NM/2019-20/6260,Parks,Completed,NM-ALANDUR,157,124000,ANNUAL MAINTENANCE FOR PERIOD AT KAVYA GARDEN IN DN 157 (5 MONTHS PERIOD),Own Sources,12,2019-20,2019-20 NM/2019-20/6262,Parks,Completed,NM-ALANDUR,157,199000,ANNUAL MAINTENANCE OF PARK AT MACRO MARVEL RIVER COUNTY IN DN 157(5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6264,Parks,Completed,NM-ALANDUR,157,95900,ANNUAL MAINTENANCE OF PARK AT MANAPAKKAM ARCOT SALAI PARK IN DN 157 (5 PERIOD),Own Sources,12,2019-20,2019-20 NM/2019-20/6266,Parks,Completed,NM-ALANDUR,157,95900,ANNUAL MAINTENANCE OF PARK AT RIVER VIEW COLONY PARK IN DN 157 (5 MONTHS),Own Sources,12,2019-20,2019-20 L/2019-20/6160,Electrical,Completed,L-Electrical,158,362600,"Availing of TNEB Supply at MGR Nagar Dumping yard in Div 158,Zone 12",Own Sources,12,2019-20,2020-21 NM/2019-20/1129,Buildings,Completed,NM-ALANDUR,158,1162000,"IMPROVEMENT WORK TO COMPOST YARD AT NANDAMBAKKAM NEAR TPF IN DN 158,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/1502,Buildings,Completed,NM-ALANDUR,158,294000,"'PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN NANDAMBAKKAM BURIAL GROUND NEAR TPF IN DN-158,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/15881,Buildings,Completed,NM-ALANDUR,158,230000,"ANNUAL MAINTENANCE OF SUNDAR NAGAR PARK IN DN 158,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16228,Buildings,Completed,NM-ALANDUR,158,492000,"REPAIRS AND MAINTENANCE OF GCC BUILDINGS AT VARIOS STREET IN DN-158,U-35,Z-12",Own Sources,12,2019-20,2021-22 NM/2019-20/1880,Buildings,Completed,NM-ALANDUR,158,745000,"ADDITIONAL PROPOSED COMPOST YARD AT INSIDE OF NANDAMBAKKAM BURIAL GROUND IN DN-158,U-35,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/3363,Buildings,Completed,NM-ALANDUR,158,155000,"PROVIDING BORE WELL AND COLOUR WASHING TO NANDAMBAKKAM BURIAL GROUND NEAR TPF IN DN-158,UNIT-35,ZONE-12",Own Sources,12,2019-20,2020-21 NM/2019-20/4414,Buildings,Completed,NM-ALANDUR,158,63000,Providing of Rain water harvesting struture and Improvement works to the existing RWH at various locations in DIV-158 U-35 Z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/5561,Buildings,Completed,NM-ALANDUR,158,1848000,"Demolition And Reconstruction of Library Building at West Lakeview street in Div-158, Unit-35, Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/5782,Buildings,Completed,NM-ALANDUR,158,230500,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIVISION -158,UNIT-35,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/6272,Parks,Completed,NM-ALANDUR,158,83000,ANNUAL MAINTENANCE FOR PARK AT SUNDAR NAGAR IN DN 158(5 MONTHS),Own Sources,12,2019-20,2019-20 Q/2019-20/11059,Buildings,Completed,Q-Solid Waste Management,158,4540000,"Construction of Shed for the installation and processing of Garden waste and tender Coconut shell at Nandambakkam in Division-158, Zone-12",Own Sources,12,2019-20,2020-21 Q/2019-20/11064,Buildings,Completed,Q-Solid Waste Management,158,1860000,"Providing Concrete pavement for installation ad processing of Garden Waste and Tender Coconut Shell at Nandambakkam in Division-158, Zone -12",Own Sources,12,2019-20,2020-21 L/2019-20/7524,Electrical,Completed,L-Electrical,159,158700,"Provision of Painting of 64 nos of 9.2 Mtr Single Straight Double Bracket and 244 nos of 9.2 Mtr Single straight bracket and 72 nos of 2 Mtr post and 20 nos of kiosk pillar box Painting in GST Road from Kathipara to Thirusullam Airport in Dn 159, in Zone XII",Own Sources,12,2019-20,2020-21 L/2019-20/8368,Electrical,Completed,L-Electrical,159,2089300,Replacement of old damaged 2500 mtr of 4X25 Sqmm Alu to new 2500 mtr of 4x16 Sqmm alu cable in Short Post Center Median GST Road From Saravana Bhavan hotel to VIP gate abd Replacement of old damaged 5 nos of 2 mtr lamp post to new 5 nos of 2 mtr GI lamp post in gst road location in Div 159 Zone XII.,Own Sources,12,2019-20,2021-22 NM/2019-20/16112,Storm Water Drain,Completed,NM-ALANDUR,159,500000,"Maintenance Works to the Existing GCC Building at Various Street in Division-159,Unit-35,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/1994,Buildings,Completed,NM-ALANDUR,159,933000,"Providing RRC at Meenambakkam compost yard by converting the existing unused damaged pits inside the compost yard , Providing platform for drying the manure , Providing segregation platform and Improvement to existing compost yard in Division-159, Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/2933,Storm Water Drain,Completed,NM-ALANDUR,159,1180000,"IMPROVEMENT WORK TO THE EXISTING STORM WATER DRAIN AT THIRUVALLUVAR STREET IN DN-159,UNIT-36,ZONE-12",Own Sources,12,2019-20,2020-21 NM/2019-20/4418,Buildings,Completed,NM-ALANDUR,159,120000,Providing of Rain water harvesting structure and Improvement works to the existing RWH at various locations in div-159 u-35 z-12,Own Sources,12,2019-20,2021-22 NM/2019-20/7287,Storm Water Drain,Completed,NM-ALANDUR,159,81500,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIV-159,U-35,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/8196,Storm Water Drain,Completed,NM-ALANDUR,159,84000,"MINOR REPAIR AND MAN HOLES DOORS REPAIR WORK AT VARIOUS LOCATION IN MEENAMBAKKAM DI-159,U-35,Z-12.",Own Sources,12,2019-20,2020-21 L/2019-20/12117,Electrical,Completed,L-Electrical,160,172000,"Supply and Fixing of 3 nos of GI sheet of 5mm thickness coated with FRB and glazed with fibreglass mat for the Umbrella Highmast near right side of Porur Guindy Loop at Kathipara, Div - 160, Z-XII",Own Sources,12,2019-20,2020-21 L/2019-20/12118,Electrical,Completed,L-Electrical,160,172000,"Supply and Fixing of 3 nos of GI sheet of 5mm thickness coated with FRB and glazed with fibreglass mat for the Umbrella Highmast Opposite to Le Royal Meridian Hotel at Kathipara, Div - 160, Z-XII",Own Sources,12,2019-20,2020-21 L/2019-20/12119,Electrical,Completed,L-Electrical,160,181000,"Supply and Fixing of 5 nos of GI sheet of 5mm thickness coated with FRB and glazed with fibreglass mat for the Umbrella Highmast in right side of Vadapalani Guindy service road at Kathipara junction, Div - 160, Z-XII",Own Sources,12,2019-20,2020-21 L/2019-20/12120,Electrical,Completed,L-Electrical,160,136000,"Supply and Fixing of 2 nos of GI sheet of 5mm thickness coated with FRB and glazed with fibreglass mat for the Umbrella Highmast near AC Office at Kathipara , Div - 160, Z-XII",Own Sources,12,2019-20,2020-21 L/2019-20/7906,Electrical,Completed,L-Electrical,160,992000,"Removal of 16 nos of 8 mtr Octagonal St.Lamp post , Re-erection of 16 nos of 8mtr Octagonal St.Lamp post, Supply of 21 nos of 2.7mtr long GI Arch St.Bracket and Replacement of 551mts of damaged 4*16 Sq.mm cable at GST Road (Jothi Theatre to AC Office side and Annapoorna Hotel to Alandur metro rail station ) in Div 160, Z-XII (Sch of rate 2019-20)",Own Sources,12,2019-20,2020-21 L/2019-20/7907,Electrical,Completed,L-Electrical,160,990000,"Supply of 8 nos of 8 mtr GI Octagonal streetlamp post, Erection of 12 nos of 8mtr Octagonal streetlamp posts and replacement of 783mts of damaged 4*16 Sq.mm cable at GST Road ( OTA to Jothi theatre) in Div 160, Z-XII (Sch of rate 2019-20)",Own Sources,12,2019-20,2020-21 NM/2019-20/10957,Buildings,Completed,NM-ALANDUR,160,311000,"Providing Water Supply ,Drainage Connection and Electrical Supply in E-Toilet at Mkn Road in Division-160,Unit-36,Zone-12.",Own Sources,12,2019-20,2021-22 NM/2019-20/1342,Buildings,Completed,NM-ALANDUR,160,151300,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT NEW STREET (OLD COURT BUILDING) IN DN-160,U-35,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/15842,Buildings,Completed,NM-ALANDUR,160,673000,"ANNUAL MAINTENANCE OF RIVER VIEW PHASE-II PARK IN DN 157,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15859,Buildings,Completed,NM-ALANDUR,160,230000,"ANNUAL MAINTENANCE OF NANGANALLUR 29TH STREET PARK IN DN 164,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15872,Buildings,Completed,NM-ALANDUR,160,617000,"ANNUAL MAINTENANCE OF NEW STREET PARK IN DN 160,UNIT-35, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15878,Buildings,Completed,NM-ALANDUR,160,233000,"ANNUAL MAINTENANCE OF JEEVAN NAGAR PARK IN DN 161,UNIT-36, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16054,Buildings,Completed,NM-ALANDUR,160,500000,"Repairs and Maintenance Work to Existing GCC Building at various location in Division-160, Unit-36 ,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/2213,Buildings,Completed,NM-ALANDUR,160,930000,"IMPROVEMENT WORKS TO LORRY STATION AT NEW STREET IN DIV -160,U-35,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/4409,Buildings,Completed,NM-ALANDUR,160,474000,Providing of Rain water harvesting structure and Improvement works to the existing RWH at various locations in div-160 u-36 z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/5576,Storm Water Drain,Completed,NM-ALANDUR,160,459500,"Desilting of Existing Storm Water Drain at various Street(No.of Roads - 42) in Division-160,Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/6274,Parks,Completed,NM-ALANDUR,160,160000,ANNUAL MAINTENANCE FOR PARK AT NEW STREET IN DN 160 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6709,Buildings,Completed,NM-ALANDUR,160,329000,"Providing Sump at Newstreet Ammaunavagam in DIvision-160,Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/6710,Buildings,Completed,NM-ALANDUR,160,310000,"Providing Sump at Newstreet Park in DIvision-160,Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7036,Storm Water Drain,Completed,NM-ALANDUR,160,713500,"Minor Repair Works and Replacing of Manhole Doors at Various location in Division-160,Unit-36,Zone-12.",Own Sources,12,2019-20,2019-20 NM/2019-20/7037,Storm Water Drain,Completed,NM-ALANDUR,160,473000,"Minor Repair Works and Replacing of Manhole Doors at Various location in Division-160,Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7148,Buildings,Completed,NM-ALANDUR,160,300000,"DEMOLITION AND RECONSTRUCTION OF DAMAGED COMPOUND WALL AT GANDHI HOSPITAL AT SOWRI STREET IN DIVISION-160,UNIT-36,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7167,Buildings,Completed,NM-ALANDUR,160,129000,"Improvement Works to Existing well at Ramasamy Bandulane in Division -160,Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/13026,Roads,Completed,NM-ALANDUR,161,800000,"FORMATION OF CEMENT CONCRETE ROAD AT RAILWAY STATION ROAD IN DN-161,U-36,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/15877,Buildings,Completed,NM-ALANDUR,161,231000,"ANNUAL MAINTENANCE OF MURUGAN NAGAR PARK IN DN 161,UNIT-36, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15879,Buildings,Completed,NM-ALANDUR,161,617000,"ANNUAL MAINTENANCE OF OFFICERS COLONY PARK IN DN 161,UNIT-36, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15880,Parks,Completed,NM-ALANDUR,161,612000,"ANNUAL MAINTENANCE OF TNGO COLONY PARK IN DN 161,UNIT-36, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/4411,Buildings,Completed,NM-ALANDUR,161,168000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS GCC BUILDINGS IN DN-161 U-36,Z-12.",Own Sources,12,2019-20,2019-20 NM/2019-20/5767,Storm Water Drain,Completed,NM-ALANDUR,161,492700,"MINOR REPAIR WORKS AND REPLACING OF MANHOLE DOORS AT VARIOUS LOCATIONS IN DIV-161,UNIT-36,ZONE-12",Own Sources,12,2019-20,2020-21 NM/2019-20/5776,Storm Water Drain,Completed,NM-ALANDUR,161,371000,"DESILTING OF EXISTING SWD AT VARIOUS STREETS ( 40 ROADS ) IN DIV-161,UNIT-36,ZONE-12",Own Sources,12,2019-20,2020-21 NM/2019-20/6281,Parks,Completed,NM-ALANDUR,161,165000,ANNUAL MAINTENANCE FOR PARK AT OFFICERS COLONY IN DN 161 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6283,Parks,Completed,NM-ALANDUR,161,159000,ANNUAL MAINTENANCE FOR PARK AT TNGO COLONY IN DN 161 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6302,Parks,Completed,NM-ALANDUR,161,85000,ANNUAL MAINTENANCE OF LPARK AT MURUGAN NAGAR IN DN 161 (5 MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/6304,Parks,Completed,NM-ALANDUR,161,88000,ANNUAL MAINTENANCE OF PARK AT JEEVAN NAGAR IN DN 161 (5MONTHS),Own Sources,12,2019-20,2019-20 NM/2019-20/7080,Storm Water Drain,Completed,NM-ALANDUR,161,594500,"MINOR REPAIR WORKS AND REPLACING OF MANHOLE DOORS AT VARIOUS LOCATIONS IN DIV-161,UNIT-36,ZONE-12",Own Sources,12,2019-20,2019-20 Q/2019-20/14125,Buildings,Completed,Q-Solid Waste Management,161,3200000,"Construction of Electrical Panel Room for garden garbage and tender coconut processing facility at Nandambakkam in Dn-161, Zone-12 and Perungudi Dumping Ground in Dn-186, Zone-14",Own Sources,12,2019-20,2020-21 NM/2019-20/10938,Buildings,Completed,NM-ALANDUR,162,126000,"DESILTING OF SWD AT KANNAN COLONY, KANNAN COLONY 3RD STREET, KANNAN COLONY MAIN ROAD AND NOBLE 1ST STREET IN DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/10940,Storm Water Drain,Completed,NM-ALANDUR,162,221500,"SIDE DRAIN REPAIRS WORK AT MORRISION 6TH STREET IN DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/10941,Buildings,Completed,NM-ALANDUR,162,40200,"REPAIRS WORK IN TOILETS AT KANNAN COLONY, MKN ROAD E TOILET AND THILLAI GANGA NAGAR 45TH STREET ETOILET IN DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/10942,Storm Water Drain,Completed,NM-ALANDUR,162,14200,"REPAIRS TO SWD DOORS AT KANNAN COLONY 3RD STREET AND THILLAI GANGA NAGAR 47TH STREET IN DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/11170,Storm Water Drain,Completed,NM-ALANDUR,162,47400,"PROVIDING RWH AT MORRISON 5TH STREET IN DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/11174,Buildings,Completed,NM-ALANDUR,162,37500,"REPAIRS TO BORE WELL AT MORRISION 2ND STREET AND IMPROVEMENT WORK TO INDOOR GAME STADIUM AT NOBLE 1ST STREET IN DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/11177,Buildings,Completed,NM-ALANDUR,162,13200,"PROVIDING PATCH WORK AT THILLAI GANGA NAGAR 3RD MAIN ROAD IN DN-162,U-36,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/1295,Buildings,Completed,NM-ALANDUR,162,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT THILLAI GANGA NAGAR 1ST MAIN ROAD BURIAL GROUND IN DN-162,U-36,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/15869,Buildings,Completed,NM-ALANDUR,162,234000,"ANNUAL MAINTENANCE OF THILLAIGANGA NAGAR 34TH STREET PARK IN DN 162, UNIT-36, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15871,Buildings,Completed,NM-ALANDUR,162,579000,"ANNUAL MAINTENANCE OF THIRUVALLUVAR NAGAR 1ST STREET PARK IN DN 162, UNIT-36, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16789,Roads,Completed,NM-ALANDUR,162,1380000,"RELAYING OF EXISTING BT ROAD AT THILLAI GANGA NAGAR 1ST MAIN ROAD IN DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/17723,Roads,Completed,NM-ALANDUR,162,1082200,"STRENTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAI GANGA NAGAR 2ND MAIN ROAD DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/17724,Roads,Completed,NM-ALANDUR,162,340200,"STRENTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAI GANGA NAGAR 8TH STREET DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/17725,Roads,Completed,NM-ALANDUR,162,291800,"STRENTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAI GANGA NAGAR 32ND STREET DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/17726,Roads,Completed,NM-ALANDUR,162,244700,"STRENTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAI GANGA NAGAR 44THSTREET DN-162, U-36, Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/1828,Buildings,Completed,NM-ALANDUR,162,2996000,"PROPOSED COMPOST YARD AT KANNAN COLONY BURIAL GROUND IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2019-20,2019-20 NM/2019-20/3165,Storm Water Drain,Completed,NM-ALANDUR,162,330000,"PROVIDING TRASH ARRESTER FOR SWD DISPOSAL POINT AT VARIOUS LOCATION IN DN-161,162,UNIT-36,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/4016,Buildings,Completed,NM-ALANDUR,162,680000,"IMPROVEMENT WORKS TO EXISTING COMPOST YARD AT KANNAN COLONY BURIAL GROUND IN DIVISION-162,UNIT-36,ZONE-12.",Own Sources,12,2019-20,2019-20 NM/2019-20/5639,Storm Water Drain,Completed,NM-ALANDUR,162,414400,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-162, UNIT-36,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/5645,Storm Water Drain,Completed,NM-ALANDUR,162,316500,"MINOR AND MAJOR REPAIR WORKS TO SWD AT VARIOUS STREETS IN DN-162,U-36,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/6338,Parks,Completed,NM-ALANDUR,162,121000,ANNUAL NMAINTENANCE FOR PARK AT THIRUVALLUVAR NAGAR IN DN 162 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6340,Parks,Completed,NM-ALANDUR,162,83000,ANNUAL MAINTENANCE FOR PARK AT T.G.NAGAR 34TH STREET IN DN 162 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6361,Parks,Completed,NM-ALANDUR,162,164000,ANNUAL MAINTENANCE FOR PARK AT BHARATH NAGAR IN DN 165(5MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6362,Parks,Completed,NM-ALANDUR,162,84800,ANNUAL MAINTENANCE FOR PARK AT SURENDRA NAGAR IN DN 165 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6376,Parks,Completed,NM-ALANDUR,162,57600,ANNUAL MAINTENANCE FOR PARK AT NETHAJI PARK IN DN 165 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/10144,Road Cut,Completed,NM-ALANDUR,163,322940,Attending Road cut Restoration work Made by CMWSSB at Karuneegar Street in Dn-163 U-36 Z-12,Deposit Works,12,2019-20,2020-21 NM/2019-20/10202,Road Cut,Completed,NM-ALANDUR,163,1158300,"Attending Road cut Restoration made by TAN-TRANSCO at Ramakrishnapuram 2nd street and Masthon Gori street in Division -163,Unit-36,Zone-12.",Deposit Works,12,2019-20,2020-21 NM/2019-20/1356,Buildings,Completed,NM-ALANDUR,163,294000,"PROPOSED CONSTRUCTION OF MATRIAL RECOVERY FACILITY AT BALAKRISHNAPURAM BURIAL GROUND IN DN-163,U-37,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/15868,Buildings,Completed,NM-ALANDUR,163,567000,"ANNUAL MAINTENANCE OF SHANTHI NAGAR 4TH STREET PARK IN DN 163,UNIT-36, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16061,Buildings,Completed,NM-ALANDUR,163,440000,Repairs And Maintenance Work Existing GCC Building park in Dn-163 u-36 z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/16062,Buildings,Completed,NM-ALANDUR,163,60000,Repairs And Maintenance Work Existing SWD in Dn-163 u-36 z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/16784,Roads,Completed,NM-ALANDUR,163,211000,"RELAYING OF EXISTING BT ROAD AT SHANTHI NAGAR 8TH STREET (PART) IN DIVISION 163, UNIT 36, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16785,Roads,Completed,NM-ALANDUR,163,300000,"RELAYING OF EXISTING BT ROAD AT SHANTHI NAGAR 9TH STREET IN DIVISION 163, UNIT 36, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16786,Roads,Completed,NM-ALANDUR,163,539000,"RELAYING OF EXISTING BT ROAD AT PARTHASARATHY NAGAR 2ND STREET (PART) IN DIVISION 163, UNIT 36, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16787,Roads,Completed,NM-ALANDUR,163,428000,"RELAYING OF EXISTING BT ROAD AT RAMAKRISHNAPURAM 3RD STREET IN DIVISION 163, UNIT 36, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16788,Roads,Completed,NM-ALANDUR,163,187000,"RELAYING OF EXISTING BT ROAD AT SHANTHI NAGAR MAIN ROAD (PART) IN DIVISION 163, UNIT 36, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/1836,Buildings,Completed,NM-ALANDUR,163,2612000,"PROPOSED COMPOST YARD AT BALAKRISHNAPURAM BURIAL GROUND IN DIVISION-163, UNIT-37,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/1961,Roads,Completed,NM-ALANDUR,163,647000,CONSTRUCTION OF COMPOUND WALL(DEMOLISHED PORTION)AND PROVIDING PLATFORM AND RAMP AT BALAKRISHNAPURAM BURIAL GROUND IN DIV-163 U-37 Z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/4004,Buildings,Completed,NM-ALANDUR,163,499000,"IMPROVEMENT WORKS TO THE EXISTING COMPOST YARD AT BALAKRISHNAPURAM BURIAL GROUND IN DIVISION-163,UNIT-36,ZONE-12.",Own Sources,12,2019-20,2019-20 NM/2019-20/4113,Buildings,Completed,NM-ALANDUR,163,238000,Providing Rain water harvesting structures and Improvement works to the existing RWH at various locations in Division 163 Unit 36 Zone 12,Own Sources,12,2019-20,2020-21 NM/2019-20/5405,Buildings,Completed,NM-ALANDUR,163,274000,"IMPROVEMENDS WORKS TO EXISTING RRC ,WELL RING AT BALAKRISHNAPURAM BURIAL GROUND IN DN -163 U-36 Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/5577,Storm Water Drain,Completed,NM-ALANDUR,163,284000,"Desilting of Storm Water Drain at Various Street (No of Roads - 33) in Division-163,Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/6344,Parks,Completed,NM-ALANDUR,163,84000,ANNUAL MAINENANCE FOR PARK AT SHANTHI NAGAR 4TH STREET IN DN 163 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/7092,Storm Water Drain,Completed,NM-ALANDUR,163,320000,"Minor Repair Works and Replacing of Manhole Door at various Locations in Division -163,Unit-36,Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/8318,Road Cut,Completed,NM-ALANDUR,163,201850,Attending Restoration of Road cut made by CMWSSB at Karuneegar Street in Division-163 Unit-36 Zone-12.,Deposit Works,12,2019-20,2020-21 NM/2019-20/8391,Buildings,Completed,NM-ALANDUR,163,311000,"Providing Water Supply ,Drainage Connection and Electrical Supply in E-Toilet at Madavakkam main road( near West karikaln street) in Division-163,Unit-36,Zone-12.",Own Sources,12,2019-20,2021-22 NM/2019-20/15858,Buildings,Completed,NM-ALANDUR,164,604000,"ANNUAL MAINTENANCE OF NEHRU STREET PARK IN DN 164,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16733,Roads,Completed,NM-ALANDUR,164,331000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANALLUR 36TH STREET IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16734,Roads,Completed,NM-ALANDUR,164,579000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANALLUR 3RD MAIN ROAD (PART) IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16735,Roads,Completed,NM-ALANDUR,164,299000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT JOHN DESIGAR STREET(PART) IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16736,Roads,Completed,NM-ALANDUR,164,373000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT THILLAIGANGA NAGAR 5TH MAIN ROAD(PART) IN DIVISION 164, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16737,Roads,Completed,NM-ALANDUR,164,340000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT JAYARAMAN STREET IN DIVISION 164,UNIT 37,ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/2458,Buildings,Completed,NM-ALANDUR,164,266000,"PROVIDING ELECTRICAL ARRANGEMENTS AT CHENNAI PRIMARY SCHOOL AT VEMBULI AMMAN KOVIL STREET IN DN-164,UNIT-37,ZONE-12",Own Sources,12,2019-20,2019-20 NM/2019-20/3048,Buildings,Completed,NM-ALANDUR,164,268000,"PROVIDING UNDER GROUND SUMP FOR AMMA KUDINEER R.O CONCENTRATE WATER RECYCLING PROCESS AT HINDU COLONY BUS TERMINUS IN DN-167,U-36,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/3050,Buildings,Completed,NM-ALANDUR,164,286000,"PROVIDING UNDER GROUND SUMP FOR AMMA KUDINEER R.O CONCENTRATE WATER RECYCLING PROCESS AT NANGANALLUR 29TH STREET PARK IN DN-164,U-37,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/4100,Storm Water Drain,Completed,NM-ALANDUR,164,777000,"Providing of Rain water harvesting structure various locations in Div-164, U-37 ,Z-12.",Own Sources,12,2019-20,2019-20 NM/2019-20/6349,Parks,Completed,NM-ALANDUR,164,85000,ANNUAL MAINTENANCE FOR PARK AT NANGANALLUR 29TH STREET IN DN 164 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6350,Parks,Completed,NM-ALANDUR,164,91000,ANNUAL MAINTENANCE FOR PARK AT NEHRU STREET IN DN 164 (5MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/7117,Storm Water Drain,Completed,NM-ALANDUR,164,247200,"DESILTING OF EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DN - 164, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7118,Storm Water Drain,Completed,NM-ALANDUR,164,703200,"MINOR REPAIR WORKS AND REPLACING OF MANHOLE DOORS AT VARIOUS STREET IN DN - 164, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/9358,Buildings,Completed,NM-ALANDUR,164,495000,"REPAIRS AND MAINTENANCE OF EXISTING GCC BUILDINGS,ROADS,SWD AND PARKS IN DN 164, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/0653,Buildings,Completed,NM-ALANDUR,165,433000,"Improvement works to Vanuvampet Burial Ground at Muthiyal Reddy Nagar Main Road in Division 165,Unit 37,Zone 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/10010,Roads,Completed,NM-ALANDUR,165,151000,"Restoration of Road cut (Road Cut made by CMWSSB) at Surender Nagar 10th street in Dn - 165, U - 37, Z- 12.",Deposit Works,12,2019-20,2020-21 NM/2019-20/1216,Parks,Completed,NM-ALANDUR,165,437000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DN-163,164,165,166,U-37,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/1262,Buildings,Completed,NM-ALANDUR,165,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT VANUVAMPET BURIAL GROUND IN DN-165,U-37,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/1410,Parks,Completed,NM-ALANDUR,165,481000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTIMG PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DN-161,162,167,U-36,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/1411,Parks,Completed,NM-ALANDUR,165,158000,"PROVIDING MULCH PIT FOR DRY WASTE COMPOSTING PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DN-161,162,167,U-36,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/15852,Buildings,Completed,NM-ALANDUR,165,576000,"ANNUAL MAINTENANCE OF SOUTH SECTOR II ND STREET PARK IN DN 165,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15853,Buildings,Completed,NM-ALANDUR,165,581000,"ANNUAL MAINTENANCE OF BALAJI NAGAR PARK IN DN 165,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15854,Buildings,Completed,NM-ALANDUR,165,232000,"ANNUAL MAINTENANCE OF LAKSHMI NAGAR PARK IN DN 165,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15855,Buildings,Completed,NM-ALANDUR,165,626000,"ANNUAL MAINTENANCE OF BHARATH NAGAR PARK IN DN 165,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15856,Buildings,Completed,NM-ALANDUR,165,230000,"ANNUAL MAINTENANCE OF SURENDRA NAGAR PARK IN DN 165,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15857,Buildings,Completed,NM-ALANDUR,165,230000,"ANNUAL MAINTENANCE OF NETHAJI ROAD PARK IN DN 165,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16729,Roads,Completed,NM-ALANDUR,165,523000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT BHARADHIDASAN NAGAR MAIN ROAD IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16731,Roads,Completed,NM-ALANDUR,165,483000,"RELAYING OF EXISTING BT ROAD AT BHARADHIDASAN NAGAR 2ND STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16761,Roads,Completed,NM-ALANDUR,165,253000,"RELAYING OF EXISTING BT ROAD AT VEL NAGAR EXTN IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16762,Roads,Completed,NM-ALANDUR,165,196000,"RELAYING OF EXISTING BT ROAD AT BHUVANESHWARI NAGAR 1ST STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16763,Roads,Completed,NM-ALANDUR,165,108000,"RELAYING OF EXISTING BT ROAD AT THAZABOO STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16764,Roads,Completed,NM-ALANDUR,165,602000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NEW COLONY 1ST STREET (jn of new colony main road to jn of new colony 9th street -PART) IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16765,Roads,Completed,NM-ALANDUR,165,341000,"RELAYING OF EXISTING BT ROAD AT SURENDAR NAGAR 6TH AND 4TH STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16767,Roads,Completed,NM-ALANDUR,165,134000,"RELAYING OF EXISTING BT ROAD AT BHUVANESHWARI NAGAR 5TH STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16768,Roads,Completed,NM-ALANDUR,165,195000,"RELAYING OF EXISTING BT ROAD AT BHUVANESHWARI NAGAR 6TH STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16769,Roads,Completed,NM-ALANDUR,165,260000,"RELAYING OF EXISTING BT ROAD AT BHARATH NAGAR YAMUNA STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16770,Roads,Completed,NM-ALANDUR,165,252000,"RELAYING OF EXISTING BT ROAD AT BHARATH NAGAR GANGA STREET IN DN - 165, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/2097,Parks,Completed,NM-ALANDUR,165,69000,"Improvement works to Balaji nagar park in Division 165,Unit 37,Zone 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/2598,Roads,Completed,NM-ALANDUR,165,185000,"Supplying and providing chain link fence at odai street (along the Veerangal odai) in Division 165,Unit 37,Zone 12.",Own Sources,12,2019-20,2019-20 NM/2019-20/2634,Buildings,Completed,NM-ALANDUR,165,305000,PROVIDING SUMP TO CPS & ANGANWADI AT VANUVAMPET IN DIV 165 UNIT 37 ZONE 12.,Own Sources,12,2019-20,2019-20 NM/2019-20/3167,Storm Water Drain,Completed,NM-ALANDUR,165,351000,"PROVIDING TRASH ARRESTER FOR SWD DISPOSAL POINT AT VARIOUS LOCATION IN DN-163,164,165,UNIT-37,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/4102,Buildings,Completed,NM-ALANDUR,165,193000,"IMPROVEMENT WORKS TO EXISTING COMPOST YARD AT VANUVAMPET BURIAL GROUND IN DIVISION-165, UNIT-37, ZONE-12.",Own Sources,12,2019-20,2019-20 NM/2019-20/4518,Buildings,Completed,NM-ALANDUR,165,279000,"Providing of Rain water harvesting structure at various locations in Div-165,Unit-37, Zone-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/5634,Storm Water Drain,Completed,NM-ALANDUR,165,234000,"DESILTING OF EXISTING SWD AT VARIOUS STREETS IN DN-165,U-37,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/5635,Storm Water Drain,Completed,NM-ALANDUR,165,95000,"REPLACING OF MANHOLE DOORS AT VARIOUS LOCATION IN DN-165,U-37,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/6353,Parks,Completed,NM-ALANDUR,165,142000,ANNUAL MAINTENANCE FOR PARK AT SOUTH SECTOR 2ND STREET IN DN 165 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6355,Parks,Completed,NM-ALANDUR,165,93000,ANNUAL MAINTENANCE FOR PARK AT BALAJI NAGAR IN DN 165 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6359,Parks,Completed,NM-ALANDUR,165,84000,ANNUAL MAINTENANCE FOR PARK AT LAKSHMI NAGAR IN DN 165 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/7326,Roads,Completed,NM-ALANDUR,165,406000,"The strengthening and Relaying the Road by using Paver finisher at kavery street in DN 165,U-37,Z-12",Own Sources,12,2019-20,2020-21 NM/2019-20/9974,Roads,Completed,NM-ALANDUR,165,166000,"Restoration of Road cut (Road Cut made by CMWSSB) at surender nagar 6th street 4th cross street in dn 165,U - 37, Z - 12.",Deposit Works,12,2019-20,2020-21 NM/2019-20/1284,Buildings,Completed,NM-ALANDUR,166,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT NERHU HIGH ROAD IN DN-166,U-37,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/13167,Roads,Completed,NM-ALANDUR,166,1347000,"Relaying the road with Bituminous Concrete 30mm thick by using paver finisher at B.V Nagar 12th street in Div-166,Unit-37,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/13176,Roads,Completed,NM-ALANDUR,166,1782000,"Relaying the road with Bituminous Concrete 30mm thick by using paver finisher at B.V Nagar 13th street in Div-166,Unit-37,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/15847,Buildings,Completed,NM-ALANDUR,166,235000,"ANNUAL MAINTENANCE OF ANNA PARK IN DN 166,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16713,Roads,Completed,NM-ALANDUR,166,2691000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NEHRU NEDUNCHALAI IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16714,Roads,Completed,NM-ALANDUR,166,106000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT K K NAGAR 1ST STREET IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16715,Roads,Completed,NM-ALANDUR,166,380000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT EZHUR AMMAN KOIL STREET IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16716,Roads,Completed,NM-ALANDUR,166,113000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT BURMATAMIZHAR COLONY 3RD CROSS STREET IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16717,Roads,Completed,NM-ALANDUR,166,351000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT BALAVINAYAGAR KOIL STREET IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16718,Roads,Completed,NM-ALANDUR,166,527000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT JOSEPH 2ND STREETIN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16719,Roads,Completed,NM-ALANDUR,166,132000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT AMBEDKAR NAGAR (GANDHI NAGAR) IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16720,Roads,Completed,NM-ALANDUR,166,2839000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT B.V NAGAR 3RD MAIN ROAD (PART) IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16721,Roads,Completed,NM-ALANDUR,166,412000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT B.V NAGAR 19TH STREET IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16722,Roads,Completed,NM-ALANDUR,166,288000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT K K NAGAR 10TH STREETIN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16723,Roads,Completed,NM-ALANDUR,166,127000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT K K NAGAR 2ND STREET IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16724,Roads,Completed,NM-ALANDUR,166,238000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT K K NAGAR 8TH STREET IN DIVISION 166, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/4099,Storm Water Drain,Completed,NM-ALANDUR,166,583000,Providing of Rain water harvesting structure at various locations in Div-166 U-37 Z-12,Own Sources,12,2019-20,2020-21 NM/2019-20/5637,Storm Water Drain,Completed,NM-ALANDUR,166,169500,"DESILTING OF EXISTING SWD AT VARIOUS STREETS IN DN-166,U-37,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/5638,Storm Water Drain,Completed,NM-ALANDUR,166,95000,"REPLACING OF MANHOLE DOORS AT VARIOUS LOCATION IN DN-166,U-37,Z-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/6378,Parks,Completed,NM-ALANDUR,166,82750,ANNUAL MAINTENANCE FOR PARK AT ANNA PARK IN DN 166 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/9350,Buildings,Completed,NM-ALANDUR,166,500000,"Improvements works to corporation buildings in Div-166 , Unit-35, Z-12",Own Sources,12,2019-20,2020-21 BR/2019-20/5358,Roads,Completed,BR-Bus Route Roads,167,388000,"Partly relaying the road with BC after cold milling by paver finisher at Nanganallur 5 th Main Road in Dn-167, Zone - 12",Grants,12,2019-20,2020-21 NM/2019-20/1293,Buildings,Completed,NM-ALANDUR,167,294000,"PROPOSED CONSTRUCTION OF MATERIALS RECOVERY FACILITY AT NANGANALLUR 100 FEET ROAD IN DN-167,U-36,Z-12",Own Sources,12,2019-20,2019-20 NM/2019-20/13094,Roads,Completed,NM-ALANDUR,167,2311000,"Relaying the road with Bituminous Concrete 30mm thick by using paver finisher at lakshmi nagar main road in Div-167,Unit-37,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/13099,Roads,Completed,NM-ALANDUR,167,804000,"Relaying the road with Bituminous Concrete 30mm thick by using paver finisher at lakshmi nagar 8th street in Div-167,Unit-37,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/13102,Roads,Completed,NM-ALANDUR,167,900000,"Relaying the road with Bituminous Concrete 30mm thick by using paver finisher at Hindu colony 13th cross street in Div-167,Unit-37,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/13107,Roads,Completed,NM-ALANDUR,167,905000,"Relaying the road with Bituminous Concrete 30mm thick by using paver finisher at Hindu colony 12th cross street in Div-167,Unit-37,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/13109,Roads,Completed,NM-ALANDUR,167,659000,"Relaying the road with Bituminous Concrete 30mm thick by using paver finisher at Kannan Nagar 1st cross street in Div-167,Unit-37,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/15819,Parks,Completed,NM-ALANDUR,167,1091000,"ANNUAL MAINTENANCE OF INDEPENDENCE DAY PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15820,Buildings,Completed,NM-ALANDUR,167,805000,"ANNUAL MAINTENANCE OF SBI COLONY MAIN ROAD PARK IN DN 167,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15821,Buildings,Completed,NM-ALANDUR,167,611000,"ANNUAL MAINTENANCE OF VOLTAS COLONY 1ST STREET PARK IN DN 167,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15822,Buildings,Completed,NM-ALANDUR,167,603000,"ANNUAL MAINTENANCE OF LAKSHMI NAGAR 7TH STREET PARK IN DN 167,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15823,Buildings,Completed,NM-ALANDUR,167,230000,"ANNUAL MAINTENANCE OF VIJAY AVENUE PARK IN DN 167,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15824,Buildings,Completed,NM-ALANDUR,167,230000,"ANNUAL MAINTENANCE OF HINDU COLONY 26TH STREET PARK IN DN 167,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15825,Buildings,Completed,NM-ALANDUR,167,603000,"ANNUAL MAINTENANCE OF LAKSHMI NAGAR 4TH STAGE PARK IN DN 167,UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15826,Buildings,Completed,NM-ALANDUR,167,577000,"ANNUAL MAINTENANCE OF KANNIKA COLONY PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15827,Buildings,Completed,NM-ALANDUR,167,577000,"ANNUAL MAINTENANCE OF CIVIL AVIATION COLONY PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15828,Buildings,Completed,NM-ALANDUR,167,574000,"ANNUAL MAINTENANCE OF NANGANALLUR 46TH STREET PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15829,Buildings,Completed,NM-ALANDUR,167,574000,"ANNUAL MAINTENANCE OF KANNAN NAGAR 1ST MAIN ROAD PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15830,Buildings,Completed,NM-ALANDUR,167,574000,"ANNUAL MAINTENANCE OF NANGANALLUR 100 FEET ROAD SIDE PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15831,Buildings,Completed,NM-ALANDUR,167,230000,"ANNUAL MAINTENANCE OF JAIN STAFF COLONY PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15832,Buildings,Completed,NM-ALANDUR,167,230000,"ANNUAL MAINTENANCE OF MMTC COLONY EASWARAN KOVIL STREET PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15833,Buildings,Completed,NM-ALANDUR,167,230000,"ANNUAL MAINTENANCE OF VOLTAS COLONY 3RD STREET PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15834,Buildings,Completed,NM-ALANDUR,167,230000,"ANNUAL MAINTENANCE OF KANNAN NAGAR 1ST CROSS STREET IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/15835,Buildings,Completed,NM-ALANDUR,167,230000,"ANNUAL MAINTENANCE OF EAST MAIN ROAD PARK IN DN 167, UNIT-37, ZONE 12 (1YEAR)",Own Sources,12,2019-20,2020-21 NM/2019-20/16193,Storm Water Drain,Completed,NM-ALANDUR,167,329000,"DESILTING OF WELL AT VOLTAS COLONY ST STREET FOR THE PURPOSE OF RAIN WATER HARVESTING IN DN-167,UNIT-37,ZONE-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16194,Storm Water Drain,Completed,NM-ALANDUR,167,55000,"IMPROVEMENT TO THE EXISTING CORPORATION BUILDING IN DIVISION-167,UNIT-37,ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16195,Storm Water Drain,Completed,NM-ALANDUR,167,112000,"IMPROVEMENT TO THE EXISTING TO THE EXISTING VOLTAS COLONY 1ST STREET PARK IN DIVISION-167,UNIT,37,ZONE-12",Own Sources,12,2019-20,2020-21 NM/2019-20/16694,Roads,Completed,NM-ALANDUR,167,320000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 4TH STAGE 2ND CROSS IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16695,Roads,Completed,NM-ALANDUR,167,962000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT KANNAN NAGAR 3RD MAIN ROAD (PART) IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16696,Roads,Completed,NM-ALANDUR,167,491000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 17TH STREET IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16698,Roads,Completed,NM-ALANDUR,167,1152000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT VOLTAS COLONY MAIN ROAD IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16699,Roads,Completed,NM-ALANDUR,167,1669000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT VOLTAS COLONY 5TH STREET IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16700,Roads,Completed,NM-ALANDUR,167,1061000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 2ND MAIN ROAD IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16701,Roads,Completed,NM-ALANDUR,167,749000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 6TH STREET IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16702,Roads,Completed,NM-ALANDUR,167,155000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 7TH STREET EXTN 1ST CROSS IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16703,Roads,Completed,NM-ALANDUR,167,103000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 7TH STREET EXTN 3RD CROSS IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16704,Roads,Completed,NM-ALANDUR,167,2451000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT NANGANALLUR 100 FEET ROAD (PART) IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16705,Roads,Completed,NM-ALANDUR,167,307000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 4TH STREET IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16706,Roads,Completed,NM-ALANDUR,167,344000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT LAKSHMI NAGAR 7TH STREET IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16707,Roads,Completed,NM-ALANDUR,167,245000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 16TH STREET IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16708,Roads,Completed,NM-ALANDUR,167,314000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT STATE BANK MAIN COLONY IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/16709,Roads,Completed,NM-ALANDUR,167,1026000,"STRENGTHENING AND RELAYING OF EXISTING BT ROAD AT HINDU COLONY 8TH STREET IN DIVISION 167, UNIT 37, ZONE 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/17685,Roads,Completed,NM-ALANDUR,167,828000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at Officers colony 5th street in Div-161,Unit-36,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17688,Roads,Completed,NM-ALANDUR,167,891000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at Jeevan nagar main road in Div-161,Unit-36,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/17707,Roads,Completed,NM-ALANDUR,167,1010000,"Relaying the road with Bituminous Concrete 40mm thick by using paver finisher at Jeevan nagar 2nd Street in Div-161,Unit-36,Zone-12",Own Sources,12,2019-20,2020-21 NM/2019-20/2482,Parks,Completed,NM-ALANDUR,167,280000,"PROVIDING SUMP AND WATER SUPPLY ARRANGEMENT AT VOLTAS COLONY 3RD STREET PARK IN DN-167,UNIT-36,ZONE-12",Own Sources,12,2019-20,2019-20 NM/2019-20/3757,Storm Water Drain,Completed,NM-ALANDUR,167,243000,"IMPROVEMENT TO THE EXISTING STORM WATER DRAIN AT VOLTAS COLONY 6TH STREET IN DN-167, UNIT-37, ZONE-12.",Own Sources,12,2019-20,2020-21 NM/2019-20/4096,Storm Water Drain,Completed,NM-ALANDUR,167,428000,"Providing of Rain water harvesting structure at various locations in Div-167,Unit-37, Zone-12.",Own Sources,12,2019-20,2021-22 NM/2019-20/6380,Parks,Completed,NM-ALANDUR,167,469000,ANNUAL MAINTENANCE FOR PARK AT INDEPENDENCE DAY PARK IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6382,Parks,Completed,NM-ALANDUR,167,136000,ANNUAL MAINTENANCE OF PARK AT NANGANALLUR 46TH STREET IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6383,Parks,Completed,NM-ALANDUR,167,136000,ANNUAL MAINTENANCE OF PARK AT LAKSHMI NAGAR 7TH STREET IN DN 167(5MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6384,Parks,Completed,NM-ALANDUR,167,83000,ANNUAL MAINTENANCE FOR PARK AT VIJAY AVENUE IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6408,Parks,Completed,NM-ALANDUR,167,250000,ANNUAL MAINTENANCE OF PARK AT HINDU COLONY IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6417,Parks,Completed,NM-ALANDUR,167,83600,ANNUAL MAINTENANCE OF PARK AT JAIN STAFF COLONY IN DN 167 FOR THE PERIOD FROM 01.04.2019 TO 31.08.2019 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6418,Parks,Completed,NM-ALANDUR,167,83000,"ANNUAL MAINTENANCE OF PARK AT MMTC COLONY, ESWARAN KOIL STREET IN DN 167(5 MONTHS)",Own Sources,12,2019-20,2020-21 NM/2019-20/6422,Parks,Completed,NM-ALANDUR,167,88000,ANNUAL MAINTENANCE FOR PARK AT KANNIGA COLONY IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6423,Parks,Completed,NM-ALANDUR,167,83500,ANNUAL MAINTENANCE FOR PARK AT VOLTAS COLONY 3RD STREET IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6426,Parks,Completed,NM-ALANDUR,167,152000,ANNUAL MAINTENANCE OF PARK AT LAKSHMI NAGAR 4TH STREET IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6427,Parks,Completed,NM-ALANDUR,167,83000,ANNUAL MAINTENANCE OF PARK AT KANNAN NAGAR 1ST CROSS STREET IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6428,Parks,Completed,NM-ALANDUR,167,224000,ANNUAL MAINTENANCE OF PARK AT SBI COLONY MAIN ROAD IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6429,Parks,Completed,NM-ALANDUR,167,139000,ANNUAL MAINTENANCE OF PARK AT KANNAN NAGAR 1ST MAIN ROAD IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6434,Parks,Completed,NM-ALANDUR,167,136000,ANNUAL MAINTENANCE OF PARK AT CIVIL AVIATION COLONY IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/6549,Parks,Completed,NM-ALANDUR,167,188000,ANNUAL MAINTENANCE OF PARK AT EAST MAIN ROAD IN DN 167(1 YEAR 014.09.2018 TO 31.08.2019),Own Sources,12,2019-20,2020-21 NM/2019-20/6550,Parks,Completed,NM-ALANDUR,167,188000,ANNUAL MAINTENANCE OF PARK AT 100FT ROAD ROADSIDE PARK IN DN 167 (1 YEAR 01.09.2019. TO 31.08.2019),Own Sources,12,2019-20,2020-21 NM/2019-20/6824,Parks,Completed,NM-ALANDUR,167,101000,ANNUAL MAINTENANCE FOR PARK AT VOLTAS COLONY 1ST STREET IN DN 167 (5 MONTHS),Own Sources,12,2019-20,2020-21 NM/2019-20/7097,Storm Water Drain,Completed,NM-ALANDUR,167,465000,"DESILTING OF EXISTING STORM WATER DRAIN AT VARIOUS STREETS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7100,Storm Water Drain,Completed,NM-ALANDUR,167,909000,"MINOR REPAIRS WORKS AT VARIOUS STREETS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7101,Storm Water Drain,Completed,NM-ALANDUR,167,862000,"MINOR REPAIRS WORKS AT VARIOUS STREETS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7102,Storm Water Drain,Completed,NM-ALANDUR,167,895000,"MINOR REPAIR AND REPLACING OF MANHOLE DOORS AT VARIOUS STREETS IN DN - 167, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NM/2019-20/7903,Roads,Completed,NM-ALANDUR,167,598000,"ATTENDING TEMPORARY PATCH WORK FOR POTHOLES AND ROAD CUT AT VARIOUS STREET IN DN - 162, 163, 164, 165, 166 & 167, U - 36 & 37, Z - 12.",Own Sources,12,2019-20,2019-20 NM/2019-20/7912,Buildings,Completed,NM-ALANDUR,167,49600,"Providing Platform and Ramp to E-Toilet at MGR road in Dn-167, U-37, Zone-12.",Own Sources,12,2019-20,2021-22 NM/2019-20/7913,Buildings,Completed,NM-ALANDUR,167,116700,"Providing Water supply, Drainage connection and Electrical supply in E-Toilet at Lakshmi nagar 4th stage park at Voltas colony 5th street in Dn-167, U-37, Zone-12.",Own Sources,12,2019-20,2021-22 NM/2019-20/7915,Buildings,Completed,NM-ALANDUR,167,116000,"Providing Water supply, Drainage connection and Electrical supply in E-Toilet at Nanganallur 100feet road in Dn-167, U-37, Zone-12.",Own Sources,12,2019-20,2021-22 NM/2019-20/8872,Storm Water Drain,Completed,NM-ALANDUR,167,179000,"IMPROVEMENT TO EXISTING STORM WATER DRAIN TO COMMUNITY WELL AT VOLTAS COLONY 1ST STREET IN DN - 167, U - 37, Z - 12.",Own Sources,12,2019-20,2020-21 NP/2019-20/11145,Buildings,Completed,NP-PERUNGUDI,168,407000,"Improvement Works for Division 168 Office at M.G Nagar Main Road in Div-168, Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/11164,Storm Water Drain,Completed,NP-PERUNGUDI,168,74000,"Improvements Works for Culvert at Alex Street in Division-168,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/11165,Buildings,Completed,NP-PERUNGUDI,168,18000,"Improvement Works to Srinivasan Nagar Amma Unavagam in Div-168, Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/1185,Buildings,Completed,NP-PERUNGUDI,168,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN COMPOST YARD AT TAMBARAM VELACHERY MAIN ROAD IN DN-168 AND DN-169 ,UNIT-42,ZONE-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/13696,Roads,Completed,NP-PERUNGUDI,168,296000,"Relaying For BT Road at usha nagar 2nd street in Dn-168,Unit-42,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/14503,Roads,Completed,NP-PERUNGUDI,168,309000,"Relaying of BT road in Lakshmi nagar 5th street extn 1st street in dn-168,unit-42,zone14.",Grants,14,2019-20,2020-21 NP/2019-20/14517,Roads,Completed,NP-PERUNGUDI,168,465000,"Relaying of BT road in MGR 2nd cross street in dn-168,unit-42,zone14.",Grants,14,2019-20,2020-21 NP/2019-20/14531,Roads,Completed,NP-PERUNGUDI,168,318000,"Relaying of BT road in Vidhya nagar 1st street in dn-168,unit-42,zone14.",Grants,14,2019-20,2020-21 NP/2019-20/14532,Roads,Completed,NP-PERUNGUDI,168,91000,"Relaying of BT road in MGR 3rd cross street in dn-168,unit-42,zone14.",Grants,14,2019-20,2020-21 NP/2019-20/14563,Roads,Completed,NP-PERUNGUDI,168,154000,"Partly Relaying of BT road in Kamarajar street in dn-168,unit-42,zone14",Grants,14,2019-20,2020-21 NP/2019-20/14564,Roads,Completed,NP-PERUNGUDI,168,76000,"Partly Relaying of BT road in SelvaganapathI koil street in dn-168,unit-42,zone14",Grants,14,2019-20,2020-21 NP/2019-20/14567,Roads,Completed,NP-PERUNGUDI,168,91000,"Partly Relaying of BT road in NSC Bose road in dn-168,unit-42,zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/15360,Roads,Completed,NP-PERUNGUDI,168,2390781,"Relaying of BT road in Kuberamunusamy street in Dn-168,Unit-42,zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/2586,Roads,Completed,NP-PERUNGUDI,168,790000,"Relaying of B.T. Road Samy nagar 2nd street extn in DN-168, U-42, Z-14",Grants,14,2019-20,2020-21 NP/2019-20/2605,Roads,Completed,NP-PERUNGUDI,168,325000,"Relaying of road in Usha nagar 3rd street in Dn-168,unit-42,zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/4995,Buildings,Completed,NP-PERUNGUDI,168,196000,"Providing of RWH Works at Various Locations in Dn168,Unit-42,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6904,Roads,Completed,NP-PERUNGUDI,168,641000,"Desilting Side Drain and Storm water drain at Various streets in Dn -168 Unit- 42, Zone - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/6905,Storm Water Drain,Completed,NP-PERUNGUDI,168,344000,"Minor repairs of Side Drain and Storm water drain at Various streets in Dn -168 Unit- 42, Zone - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/6915,Roads,Completed,NP-PERUNGUDI,168,102000,"Relaying For BT Road at usha nagar 1st cross street in Dn-168,Unit-42,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/7060,Parks,Completed,NP-PERUNGUDI,168,243000,"Maintenance of Park at LAKSHMI NAGAR 10TH STREET in Dn. 168, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/8345,Roads,Completed,NP-PERUNGUDI,168,1285000,"Relaying For BT Road at usha nagar 1st street in Dn-168,Unit-42,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/8414,Roads,Completed,NP-PERUNGUDI,168,440000,"ATTENDING THE BT ROAD PATCH WORK AT VARIOUS STREETS IN DIV - 168, UNIT - 42, ZONE - 14",Own Sources,14,2019-20,2020-21 BR/2019-20/17492,Road Cut,Completed,BR-Bus Route Roads,169,959000,"Restoration of OFC Road cut at 18 Nos of interior Roads in Div-169, Unit 42, Zone 14",Deposit Works,14,2019-20,2020-21 BR/2019-20/17495,Road Cut,Completed,BR-Bus Route Roads,169,975000,"Restoration of OFC Road cut at 17 Nos of interior Roads in Div-161,168,169, Unit 42, Zone 14",Deposit Works,14,2019-20,2020-21 BR/2019-20/17497,Road Cut,Completed,BR-Bus Route Roads,169,975000,"Restoration of OFC Road cut at 16 Nos of interior Roads in Div-169, Unit 42, Zone 14",Deposit Works,14,2019-20,2020-21 BR/2019-20/17635,Road Cut,Completed,BR-Bus Route Roads,169,959000,RESTORATION OF ROAD CUT MADE BY RELIANCE JIO AT VARIOUS INTERIOR ROADS IN DIV-169 UNIT-42 ZONE-14(DEPOSIT CODE-57/1144/2018-19),Deposit Works,14,2019-20,2020-21 L/2019-20/8185,Electrical,Completed,L-Electrical,169,14631000,"Supply and erection of 3 nos of 6mtr Hot Dip Lamp Post with Single Straight Bracket, 34 nos of 6mtr Hot Dip Lamp Post with Single Arch Bracket, 2 nos of 8mtr Hot Dip Lamp Post with Single Arch Bracket, 64 nos of 8mtr Hot Dip Lamp Post with Double Arch Bracket and 15 nos of 8mtr Hot Dip Lamp Post with Triple Arch Bracket, 2 nos of 8mtr Hot Dip Lamp Post with Single Straight Bracket with 150 - 165 W LED fitting at Various Places in division-169 Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/10154,Buildings,Completed,NP-PERUNGUDI,169,331800,"Construction of septic tank with chambers, and other Improvement works at Compost Yard in Div-169 ,Unit-42,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/10835,Bridges,Completed,NP-PERUNGUDI,169,831600,"Maintenance of Gasifier Crematorium at Puzhuthivakkam burial ground in dn 169,u-42,zone-14",Own Sources,14,2019-20,2021-22 NP/2019-20/11168,Roads,Completed,NP-PERUNGUDI,169,1058000,"PROVIDING NEW SPEED BREAKERS AS PER IRC STANDARD WITH BITUMINOUS CONCRETE AND ALSO FIXING BOARD AND STUDS AT VARIOUS STREET IN DN 169,UNIT-42,ZONE14",Own Sources,14,2019-20,2021-22 NP/2019-20/1275,Buildings,Completed,NP-PERUNGUDI,169,900000,"Supply and Fixing of Well Rings for composting purposes at Various Places in Dn-168, Dn-169 , Dn -187 and Dn-188 Unit-42,zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/13881,Roads,Completed,NP-PERUNGUDI,169,733000,"Relaying of BT road in Vigneswara 3rd street in Dn- 169 ,unit-42,Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/13894,Roads,Completed,NP-PERUNGUDI,169,1141000,"Relaying of BT road in NSC Bose road in Dn- 169 , unit-42, Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/13895,Roads,Completed,NP-PERUNGUDI,169,3335000,"Relaying of BT road in Balaji nagar 24th street in Dn- 169 , unit-42, Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/13897,Roads,Completed,NP-PERUNGUDI,169,835000,"Relaying of BT road in Sadasivam nagar 2nd main road in Dn- 169 , unit-42, Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/13908,Roads,Completed,NP-PERUNGUDI,169,882000,"Forming of BT road in Sadasivam nagar main road Dn- 169,Unit-42,Zone - 14. .",Grants,14,2019-20,2020-21 NP/2019-20/2360,Buildings,Completed,NP-PERUNGUDI,169,1230000,"Improvements works for West side Compost yard at Old Dumping Ground in dn-169,unit-42,zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4587,Electrical,Completed,NP-PERUNGUDI,169,1024000,"Supply and Installation of Conference P.A System, 1 No of LCD projector, 4 nos of 1.5 Ton Air conditioners and LED indoor fittings for conference hall in Zonal office, zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4996,Buildings,Completed,NP-PERUNGUDI,169,325000,"Providing of RWH Works in GCC Buildings at Various Locations in Dn169,Unit-42,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6172,Buildings,Completed,NP-PERUNGUDI,169,524000,"Construction of Car shed and Visitors shed in front of E Sevai Centre to Zonal Office Building in Dn-169, Unit-42, Zone-14.",Own Sources,14,2019-20,2021-22 NP/2019-20/6424,Buildings,Completed,NP-PERUNGUDI,169,235000,"Improvement works to Community Well at Gangaiamman Koil Kulam in Div-169,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6808,Roads,Completed,NP-PERUNGUDI,169,371000,"Forming of B.T. Road at Annai therasa nagar 3rd cross street in DN-168, U-42, Z-14",Grants,14,2019-20,2020-21 NP/2019-20/6906,Storm Water Drain,Completed,NP-PERUNGUDI,169,999000,"Desilting for Storm Water Drains and Side Drains in Div-169,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6907,Buildings,Completed,NP-PERUNGUDI,169,215000,"Desilting for Side Drain and Storm water drain at Various streets in Dn -169 Unit- 42, Zone - 14",Own Sources,14,2019-20,2019-20 NP/2019-20/6908,Storm Water Drain,Completed,NP-PERUNGUDI,169,349000,"Minor Repair Works for Storm Water Drains and Side Drains in Div-169,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6909,Storm Water Drain,Completed,NP-PERUNGUDI,169,769000,"Minor repair for Side Drain and Storm water drain at Various streets in Dn -169 Unit- 42, Zone - 14",Own Sources,14,2019-20,2019-20 NP/2019-20/6976,Roads,Completed,NP-PERUNGUDI,169,1090000,"Relaying of BT road in Eswaran koil street in Dn- 169 ,unit-42,Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/6977,Roads,Completed,NP-PERUNGUDI,169,2786000,"Relaying of BT road in Village road in Dn- 169 ,unit-42,Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/6980,Roads,Completed,NP-PERUNGUDI,169,255000,"Forming of BT road in Balaji cross street in Dn- 169 ,unit-42,Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/6982,Roads,Completed,NP-PERUNGUDI,169,1111000,"Formation of CC Road at Annai Thersa Nagar 2nd Street in Dn-169, Unit-42, Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/6983,Roads,Completed,NP-PERUNGUDI,169,982000,"Formation of CC Road at Senghazanaiammani koil cross street in Dn-169, Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/7063,Parks,Completed,NP-PERUNGUDI,169,248000,"Maintenance of Park at HINDU COLONY PARK in Dn. 169, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7066,Parks,Completed,NP-PERUNGUDI,169,639000,"Maintenance of Park at IYYAN THIRUVALLUVAR PARK in Dn. 169, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7068,Parks,Completed,NP-PERUNGUDI,169,1164000,"Maintenance of Park at BALAJI NAGAR 19TH STREET in Dn. 169, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7069,Parks,Completed,NP-PERUNGUDI,169,649000,"Maintenance of Park at AGS COLONY in Dn. 169, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7070,Parks,Completed,NP-PERUNGUDI,169,844000,"Maintenance of Park at ANNAI THERASA 14TH STREET in Dn. 169, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7072,Parks,Completed,NP-PERUNGUDI,169,640000,"Maintenance of Park at EPR NAGAR in Dn. 169, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7074,Parks,Completed,NP-PERUNGUDI,169,595000,"Maintenance of Park at BALAJI NAGAR EXTN SOUTH in Dn. 169, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7203,Buildings,Completed,NP-PERUNGUDI,169,104000,"IMPROVEMENT WORKS TO AMMA UNAVAGAM IN DIV-169, UNIT-42, ZONE-14",Own Sources,14,2019-20,2020-21 NP/2019-20/7457,Buildings,Completed,NP-PERUNGUDI,169,599000,"Improvements and repairs to Zonal Office Building in Dn-169, Unit-42, Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8342,Electrical,Completed,NP-PERUNGUDI,169,1004200,"Providing Comprehensive Annual Maintenance for 1 No 100 KVA Diesel Genset at Zonal office-14, division-169, 1 No 100 KVA Diesel Genset at Perungudi Dumping Ground, division-186, 1 No of 30 KVA Diesel Genset at Balaji Nagar Burial Ground, Division - 169 and 6 nos of mobile mast in various sections in Zone-14",Own Sources,14,2019-20,2021-22 NP/2019-20/8413,Roads,Completed,NP-PERUNGUDI,169,1062000,"ATTENDING THE ROAD PATCH WORK AT VARIOUS STREETS IN DIV - 169, UNIT - 42, ZONE - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/8909,Roads,Completed,NP-PERUNGUDI,169,42500,"Providing and laying 300mm dia Hume pipe at Annai therasa nagar 7th street ,and Laying WMM at Srinivasa nagar main road in Div-169, Unit-42, Zone-14",Own Sources,14,2019-20,2020-21 NP/2019-20/9392,Roads,Completed,NP-PERUNGUDI,169,129000,"Providing and laying WMM at Various streets in Div-169, Unit-42, Zone-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/9401,Roads,Completed,NP-PERUNGUDI,169,42000,"Providing and laying 450mm dia Hume pipe at various streets in Div-169, Unit-42, Zone-14",Own Sources,14,2019-20,2020-21 NP/2019-20/9404,Roads,Completed,NP-PERUNGUDI,169,42000,"Providing and laying 450mm dia Hume pipe at srinivasa nagar main road in Div-169, Unit-42, Zone-14",Own Sources,14,2019-20,2020-21 NP/2019-20/9405,Roads,Completed,NP-PERUNGUDI,169,8053500,"Formation of CC Road at Ramakrishna raji nagar main road street in Dn-169, Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/9406,Roads,Completed,NP-PERUNGUDI,169,108000,"ARRANGING AND ENGAGING JCB AND TIPPER LORRY FOR PROVIDING KATCHA DRAIN IN DIV 169, UNIT 42,ZONE 14",Own Sources,14,2019-20,2020-21 NP/2019-20/9422,Buildings,Completed,NP-PERUNGUDI,169,41500,"IMPROVEMENTS TO ZONAL OFFICE AND REPAIRS TO SWD AT VILLAGE ROAD IN DIV-169, UNIT-42, ZONE-14",Own Sources,14,2019-20,2020-21 NP/2019-20/9837,Roads,Completed,NP-PERUNGUDI,169,3199500,"Formation of CC Road along at Puzhuthivakkam bus terminus in Dn-169,Unit -42, Zone-14.",Grants,14,2019-20,2020-21 BR/2019-20/10495,Roads,Completed,BR-Bus Route Roads,170,480000,Attending Patch work at Sardar Patel road from the jn of DOTE to the jn of C.E.G in Zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/10736,Road Cut,Completed,BR-Bus Route Roads,170,991000,"Restoration of Roadcut made by OFC Operators at Kathipara Road and Alandur Road in Dn-170, Zone-XIII",Deposit Works,13,2019-20,2020-21 BR/2019-20/8101,Roads,Completed,BR-Bus Route Roads,170,740000,Attending Patch work at Sardar Patel road from the jn of Gandhi Mandapam road to the jn of Madyakailash in Zone-13,Own Sources,13,2019-20,2019-20 L/2019-20/9364,Electrical,Completed,L-Electrical,170,134600,"RAISING OF 13 NOS OF KIOSK PILLAR BOX IN GROUND LEVEL IN VARIOUS LOCATION DIV-170, ZONE -XIII",Own Sources,13,2019-20,2020-21 L/2019-20/9383,Electrical,Completed,L-Electrical,170,98300,"PAINTING OF 129 NOS 6/7 MTR AND 125 NOS 8/9 MTR STREET LIGHTS POLE WITH SINGLE COST ALUMINIUM PAINT KIOSK PILLAR BOX AT KATHIPARA SALAI JN TO MADHYA KAILASH DUE TO CHINA - INDIA INFORMAL MEET IN DIV-170,171,172 ,ZONE-XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/10317,Buildings,Completed,NN-ADYAR,170,1630000,"PROVIDING INFRASTRUCTURE ARRANGEMENTS TO THE PLASTIC BAILING PRESS MACHINE DN -170,UT-40A,ZONE-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13021,Buildings,Completed,NN-ADYAR,170,510000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING M C C AT ARULAYAMPET BURIAL GROUND IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2019-20,2021-22 NN/2019-20/15750,Roads,Completed,NN-ADYAR,170,625000,RELAYING OF BITUMINOUS CONCRETE ROAD AT PILLAYAR KOIL 3RD STREET IN DN-170 UNIT-40A ZONE-13.,Own Sources,13,2019-20,2020-21 NN/2019-20/16674,Parks,Completed,NN-ADYAR,170,582000,"Annual Maintanance Estimate for park at Central execise colony street in Division 170,Unit-40A,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16675,Roads,Completed,NN-ADYAR,170,577000,"Annual Maintanance Estimate for park at Customs colony street in Division 170,Unit-40A,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16676,Roads,Completed,NN-ADYAR,170,622000,"Annual Maintenance for Labour colony park in Division 170,Unit-40A,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16966,Roads,Completed,NN-ADYAR,170,405000,RELAYING OF BITUMINOUS CONCRETE ROADS AT STATION ROAD IN DN-170 UNIT-40A ZONE 13,Own Sources,13,2019-20,2020-21 NN/2019-20/16967,Roads,Completed,NN-ADYAR,170,215000,RELAYING OF BITUMINOUS CONCRETE ROAD AT PARATHASARATHY 2ND STREET IN DN-170 UNIT-40A ZONE-13,Own Sources,13,2019-20,2020-21 NN/2019-20/16968,Roads,Completed,NN-ADYAR,170,470000,RELAYING OF BITUMINOUS CONCRETE ROADS AT SHANMUGARAJA STREET IN DN-170 UNIT-40A ZONE-13,Own Sources,13,2019-20,2020-21 NN/2019-20/16969,Roads,Completed,NN-ADYAR,170,166000,RELAYING OF BITUMINOUS CONCRETE ROADS AT LAKSHMI VINAYAGAR KOVIL STREET(PART) IN DIV-170 UNIT-40A ZONE-13,Own Sources,13,2019-20,2020-21 NN/2019-20/16970,Roads,Completed,NN-ADYAR,170,304000,RELAYING OF BITUMINOUS CONCRETE ROAD AT MANJOLAI 3RD STREET IN DN-170 UNIT-40A ZONE-13,Own Sources,13,2019-20,2020-21 NN/2019-20/16971,Roads,Completed,NN-ADYAR,170,232000,RELAYING OF BITUMINOUS CONCRETE ROAD AT MANJOLAI 2 STREET IN DN 170 UNIT 40A ZONE 13,Own Sources,13,2019-20,2020-21 NN/2019-20/16972,Roads,Completed,NN-ADYAR,170,166000,Relaying of Bituminous Concrete Road at Manjolai 1st Street in Dn-170 Unit-40A Zone-13,Own Sources,13,2019-20,2020-21 NN/2019-20/16973,Roads,Completed,NN-ADYAR,170,241000,Relaying of Bituminous concrete road at Achuthan nagar 5th street in Dn-170 Unit-40A Zone-13,Own Sources,13,2019-20,2020-21 NN/2019-20/16985,Roads,Completed,NN-ADYAR,170,444000,Relaying of Cement concrete road at Dhamodharan Street in Dn-170 Unit-40A Zone-13,Own Sources,13,2019-20,2020-21 NN/2019-20/16986,Roads,Completed,NN-ADYAR,170,2187000,Relaying of Cement concrete road at Alandur Service Road in Dn-170 Unit-40A Zone-13,Own Sources,13,2019-20,2020-21 NN/2019-20/1722,Buildings,Completed,NN-ADYAR,170,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT ARULAYAMMANPET BURIAL GROUND IN DIVISION 170, UNIT 40(A), ZONE 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/1890,Buildings,Completed,NN-ADYAR,170,180000,"Construction of Mulch pit at Various location in Div -170, Unit-40A, Zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/1895,Buildings,Completed,NN-ADYAR,170,387000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTIMG PURPOSE AT VARIOUS LOCATION IN DN-170,U-40A,Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/3650,Buildings,Completed,NN-ADYAR,170,513000,"Additional improvement to Micro Composting Centre in Arulayammanpet Burial Ground at Arulayammanpet 2nd street in Division - 170, Unit - 40(A), Zone - 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6671,Storm Water Drain,Completed,NN-ADYAR,170,146000,"De-silting of Storm Water Drain at Labour Colony Area in Division 170, Unit 40(A), Zone -13",Own Sources,13,2019-20,2019-20 NN/2019-20/6672,Storm Water Drain,Completed,NN-ADYAR,170,996000,"Minor Repair works in Storm Water Drain at Labour Colony Area in Division 170, Unit 40(A), Zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6673,Storm Water Drain,Completed,NN-ADYAR,170,277000,"De-silting of Storm Water Drain at Various Location Part -1 in Division 170, Unit 40(A), Zone -13",Own Sources,13,2019-20,2019-20 NN/2019-20/6674,Storm Water Drain,Completed,NN-ADYAR,170,877000,"Minor Repair works in Storm Water Drain at Various Location Part 1 in Division 170, Unit 40(A), Zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6675,Storm Water Drain,Completed,NN-ADYAR,170,329000,"De-silting of Storm Water Drain at Various Location Part -2 in Division 170, Unit 40(A), Zone -13",Own Sources,13,2019-20,2019-20 NN/2019-20/6676,Storm Water Drain,Completed,NN-ADYAR,170,815000,"Minor Repair works in Storm Water Drain at Various Location Part 2 in Division 170, Unit 40(A), Zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/9931,Buildings,Completed,NN-ADYAR,170,2500000,"Proposed construction of Library in Chennai Higher Secondary School , little mount (under MLA Fund) in dn-170,ut-40a,zone-13",MLACDS,13,2019-20,2020-21 BR/2019-20/10492,Roads,Completed,BR-Bus Route Roads,171,720000,Attending Patch work at Sardar Patel road from the jn of taluk office road to the jn of DOTE in Zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/10493,Roads,Completed,BR-Bus Route Roads,171,974000,"Providing View Cutter at sardar patel Road in Dn-171, Zone-XIII",Own Sources,13,2019-20,2019-20 BR/2019-20/15987,Roads,Completed,BR-Bus Route Roads,171,241000,RESTORATION OF OFC ROAD CUT AT VARIOUS BUS ROUTE ROADS IN ZONE-13.,Deposit Works,13,2019-20,2020-21 BR/2019-20/16064,Roads,Completed,BR-Bus Route Roads,171,894000,"Restoration of OFC Roadcut at 10nos of Road by Service Department in Div - 149, 150 & 171, Zone - 11 & 13",Deposit Works,13,2019-20,2020-21 BR/2019-20/5293,Roads,Completed,BR-Bus Route Roads,171,193000,"Partly relaying the road with BC after cold milling by paver finisher at Gandhi Mandapam Road in Dn-171 & 172 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5296,Roads,Completed,BR-Bus Route Roads,171,388000,"Partly relaying the road with BC after cold milling by paver finisher at Taluk Office Road in Dn-171 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/8057,Roads,Completed,BR-Bus Route Roads,171,950000,Supplying and fixing of Solar studs and Vertical Delineator at Sardar patel road in Zone -13,Own Sources,13,2019-20,2020-21 BR/2019-20/8064,Roads,Completed,BR-Bus Route Roads,171,980000,Supplying and fixing of solar Studs and Median marker at sardar patel road in zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/8065,Roads,Completed,BR-Bus Route Roads,171,995000,Supplying and fixing of Studs at Sardar Patel road in zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/8097,Roads,Completed,BR-Bus Route Roads,171,920000,Attending Patch work at Sardar Patel road from the jn of taluk office road to the jn of Gandhi mandapam road in Zone-13,Own Sources,13,2019-20,2019-20 BR/2019-20/8109,Roads,Completed,BR-Bus Route Roads,171,990000,"Providing Thermoplastic Painting work at Sardar Patel Road from the Jn. of Anna Salai to the Jn. of Taluk Office road and Taluk Office Road in Zone-13, Div -171",Grants,13,2019-20,2019-20 BR/2019-20/8111,Roads,Completed,BR-Bus Route Roads,171,998000,"Providing Thermoplastic Painting work at Sardar Patel Road from the Jn. of Taluk Office road to the Jn. of Gandhi Mandapam Road in Zone-13, Div -171",Grants,13,2019-20,2019-20 BR/2019-20/8192,Roads,Completed,BR-Bus Route Roads,171,880000,"PROVIDING AND IMPROVEMENTS OF DAMAGED MODERN STAINLESS STEEL BUS SHELTERS AT VARIOUS LOCATIONS OF SARDAR PATEL ROAD, TALUK OFFICE & ANNA SALAI IN ZONE - 13, DIV - 171.",Grants,13,2019-20,2020-21 BR/2019-20/8351,Roads,Completed,BR-Bus Route Roads,171,975000,Attending Patch work at Sardar Patel road from the jn of Anna Salai to the jn of Taluk office road and Taluk office Road in Zone -13,Own Sources,13,2019-20,2019-20 L/2019-20/1098,Electrical,Completed,L-Electrical,171,287000,REMOVAL AND REFIXING OF 8 NOS 9 MTR LAMP POST WITH 2.7 MTR DOUBLE ARCH BRACKET AT ANNA SALAI IN DIV-171 ZONE-XIII,Deposit Works,13,2019-20,2019-20 L/2019-20/5125,Electrical,Completed,L-Electrical,171,164500,"Provision of Re-Winding and Servicing of 25HP Sewage Submergible Motor at Aranganathan Subway in Div-171, ZXIII",Own Sources,13,2019-20,2020-21 L/2019-20/8670,Electrical,Completed,L-Electrical,171,1119900,"PROVISION OF LAYING OF DAMAGED 1815 MTRS 2X16SQ.MM AND 205 MTRS 4X16 SQ.MM ALUMINIUM CABLE AND 290MTRS OF31/2Cx25SQMM ALU CABLE AT VARIOUS STREETS IN DIV-171 TO 172, ZONE-XIII",Grants,13,2019-20,2020-21 NN/2019-20/16662,Roads,Completed,NN-ADYAR,171,695000,"Annual Maintanance Estimate for park at Chinnamalai park in Division 171,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/17253,Roads,Completed,NN-ADYAR,171,1912000,"Relaying of bitumen concrete at West CIT Nagar North Road in Division 171,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1904,Buildings,Completed,NN-ADYAR,171,192000,"PROVIDING MULCH PIT FOR DRY WASTE COMPOSTING PURPOSE AT VARIOUS LOCATION IN DIV-171,U-40,ZONE-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1907,Buildings,Completed,NN-ADYAR,171,209000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE AT VARIOUS LOCATION IN DN-171,UNIT-40,ZONE-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/3738,Roads,Completed,NN-ADYAR,171,217000,"ADDITIONAL IMPROVEMENT IN MCC AT RICHARD PARK IN DN 171, UNIT-40, ZONE 13",Own Sources,13,2019-20,2020-21 NN/2019-20/5907,Buildings,Completed,NN-ADYAR,171,304000,"PROVIDING OF RAIN WATER HARVESTING WORKS IN GCC BUILDINGS AT VARIOUS LOCATIONS IN DIV-171, UNIT-40, ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6727,Buildings,Completed,NN-ADYAR,171,656000,"Desilting of Storm Watrer Drain at Various Location (Package 1) in Division 171,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6729,Buildings,Completed,NN-ADYAR,171,295000,"Minor Repair Works in Storm Water Drain Various Location (Package 1) in Division 171,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6732,Buildings,Completed,NN-ADYAR,171,478000,"Desilting of Storm Watrer Drain at Various Location (Package 2) in Division 171,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6734,Buildings,Completed,NN-ADYAR,171,1071000,"Minor Repair Works in Storm Water Drain Various Location (Package 2) in Division 171,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/8884,Buildings,Completed,NN-ADYAR,171,117000,"Improvements to Community Well at Velachery Main Road in Division 171, Unit 40, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/9871,Footpath,Completed,NN-ADYAR,171,567000,"COLOUR WASHING TO TALUK OFFICE ROAD,SP ROAD AND ADDITIONAL FENCYING WORK AT VELACHERY MAIN ROAD FOR PM FUNCTION IN DN 171,U-40,Z-13.",Own Sources,13,2019-20,2021-22 BR/2019-20/4581,Roads,Completed,BR-Bus Route Roads,172,9751000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Sardar Patel Road(From the JN of Gandhi Mandapam to Madhya Kailash) in Dn-172, Zone - XIII",Grants,13,2019-20,2020-21 BR/2019-20/4635,Roads,Completed,BR-Bus Route Roads,172,460000,"Providing and Laying Mastic Asphalt at Sardar Patel road U Turn Portion opposite to Cancer Institute in Dn-172, Z-13.",Own Sources,13,2019-20,2020-21 BR/2019-20/8113,Roads,Completed,BR-Bus Route Roads,172,985000,"Providing Thermoplastic Painting work at Sardar Patel Road from the Jn. of Gandhi Mandapam Road to the Jn. of Madhya Kailash Road in Zone-13, Div -172",Grants,13,2019-20,2019-20 J/2019-20/8415,Buildings,Completed,J-Bridges,172,646000,Painting the Existing Crash barrier and kerb for the grade separator at junction of Sardar patel Road and Gandhi Mandapam road in division -171 & 172 zone-13,Own Sources,13,2019-20,2019-20 J/2019-20/8742,Bridges,Completed,J-Bridges,172,174000,Removal of rank vegetation in south region from Zone- 11 to 15,Own Sources,13,2019-20,2019-20 J/2019-20/8744,Bridges,Completed,J-Bridges,172,55000,Maintenance of Kotturpuram Bridge across Adyar River in Div-172.Zone-13.,Own Sources,13,2019-20,2019-20 J/2019-20/8745,Bridges,Completed,J-Bridges,172,363000,Relaying of wearing coat Patches and providing Iron Gratings in South Region Zone -11.to 15,Own Sources,13,2019-20,2019-20 L/2019-20/13812,Electrical,Completed,L-Electrical,172,978000,Provision of 8 Mtrs Street Lamp Post 8 nos With 2 Mtrs Single Straight Bracket and 14 nos of 120 to 130 W LED flood light fitting at Erikarai Salai Panneer Selvam Nagar play Ground in Kotturpuram Div-172 Zone-XIII.,Own Sources,13,2019-20,2020-21 NN/2019-20/10631,Buildings,Completed,NN-ADYAR,172,169000,"Defacing the compound wall at Regional Labour Institute Sardar Patel Road during India-China Informal Summit in Division-172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10843,Buildings,Completed,NN-ADYAR,172,92000,"Demolition of the existing dilapidated Crematorium building inside the burial ground at Lake view street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2021-22 NN/2019-20/1234,Buildings,Completed,NN-ADYAR,172,162000,"PROVIDING MULCH PIT FOR DRY WASTE COMPOSTING PURPOSE AT VARIOUS LOCATION IN DN-172,U-40,Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1236,Buildings,Completed,NN-ADYAR,172,243000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE AT VARIOUS LOCATION IN DIV-172,U-40,Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13554,Buildings,Completed,NN-ADYAR,172,112000,"Improvements to Division Office at New Street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13561,Buildings,Completed,NN-ADYAR,172,11000,"Improvements works to Chennai High School at New street,Kottur in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13651,Buildings,Completed,NN-ADYAR,172,76000,"Improvement works to Amma unavagam at New street ,Kottur in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/14780,Buildings,Completed,NN-ADYAR,172,2000000,"Proposed construction of Ground Floor Kitchen Shed at Chitra nagar, Kotturpuram under Saidapet MLA Constituency fund in Division 172,Unit-40,Zone-13.",MLACDS,13,2019-20,2021-22 NN/2019-20/1621,Buildings,Completed,NN-ADYAR,172,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT INSIDE THE SURIYA NAGAR BURIAL GROUND IN DIV-171,UNIT-40,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/1624,Buildings,Completed,NN-ADYAR,172,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT WEST CANAL BANK ROAD IN DIV-172,UNIT-40,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/16270,Buildings,Completed,NN-ADYAR,172,1998000,"Relaying of Bitumen concrete Road at Ponniamman Koil Street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16272,Buildings,Completed,NN-ADYAR,172,598000,"Relaying of Bitumen concrete Road at Ellaiamman Koil Street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16273,Buildings,Completed,NN-ADYAR,172,391000,"Relaying of Bitumen concrete Road at Kalikundram I street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16274,Buildings,Completed,NN-ADYAR,172,1684000,"Relaying of Bitumen concrete Road at Kottur Garden IV Main Road in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16275,Buildings,Completed,NN-ADYAR,172,416000,"Relaying of Bitumen concrete Road at Thulukkanathamman Koil Street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16276,Buildings,Completed,NN-ADYAR,172,586000,"Relaying of Bitumen concrete Road at Tank bund road in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16277,Buildings,Completed,NN-ADYAR,172,806000,"Relaying of Bitumen concrete Road at East Ellaiamman koil street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16624,Roads,Completed,NN-ADYAR,172,892000,"Annual Maintanance Estimate for park at Chitra nagar park in Division 172,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16630,Roads,Completed,NN-ADYAR,172,734000,"Annual Maintanance Estimate for park at Dhandayuthapani nagar park in Division 172,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16631,Roads,Completed,NN-ADYAR,172,597000,"Annual Maintanance Estimate for park at Senior Citizen park in Division 172,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16632,Roads,Completed,NN-ADYAR,172,593000,"Annual Maintanance Estimate for park at Govindaswamy park in Division 172,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16647,Buildings,Completed,NN-ADYAR,172,210000,"Relaying of Cement concrete road at Thiruveethiamman koil 1st street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16648,Buildings,Completed,NN-ADYAR,172,228000,"Relaying of Cement concrete road at Thiruveethiamman koil 2nd street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16649,Buildings,Completed,NN-ADYAR,172,199000,"Relaying of Cement concrete road at Thiruveethiamman koil 3rd street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16653,Buildings,Completed,NN-ADYAR,172,852000,"Formation of Cement concrete road at Narikuravar colony 2nd street in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16659,Buildings,Completed,NN-ADYAR,172,728000,"Relaying of Cement concrete road at Kotturpuram 4th main road (part) in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1727,Buildings,Completed,NN-ADYAR,172,294000,"PROPOSED CONSTRUCTION OF MATERIAL RESOURCE FACILITY AT NADAR STREET IN DIV-178,UNIT-39,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/3465,Buildings,Completed,NN-ADYAR,172,62000,"Providing trash arrester for SWD disposal point at various location in DN-172,U-40,Zone13.",Own Sources,13,2019-20,2019-20 NN/2019-20/5628,Buildings,Completed,NN-ADYAR,172,439000,"PROVIDING OF RAIN WATER HARVESTING WORKS IN GCC BUILDINGS AT VARIOUS LOCATIONS IN DIV172,UNIT-40,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6306,Buildings,Completed,NN-ADYAR,172,132000,"PAINTING BLACK AND WHITE TO THE FOOTPATH KERBS IN THE VIEW OF INDEPENDENCE DAY-2019 AT SARDAR PATEL ROAD IN DN-172, UNIT-40, ZONE-13",Own Sources,13,2019-20,2020-21 NN/2019-20/6601,Buildings,Completed,NN-ADYAR,172,188000,"Desilting of Storm Water Drain at Sardar Patel Road and Gandhi Mandapam Road (Pakage 1) in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6602,Buildings,Completed,NN-ADYAR,172,793000,"Desilting of Storm Watrer Drain at Various Location of Interior Roads (Package 2) in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6605,Buildings,Completed,NN-ADYAR,172,1100000,"Minor repair works in Storm Water Drain at Sardar Patel Road and Gandhi Mandapam Road (Pakage 1) in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6606,Buildings,Completed,NN-ADYAR,172,710000,"Minor Repair Works in Storm Water Drain Various Location of Interior Roads (Package 2) in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6660,Buildings,Completed,NN-ADYAR,172,78000,"Desilting of Storm Water Drain at Various Location of Interior Roads (Package 3) in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6661,Buildings,Completed,NN-ADYAR,172,1815000,"Minor Repair Works in Storm Water Drain Various Location of Interior Roads (Package 3) in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/9770,Roads,Completed,NN-ADYAR,172,1084000,"Relaying of bitumen concrete at Kotturpuram 1st main road in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/9771,Roads,Completed,NN-ADYAR,172,709000,"Relaying of bitumen concrete at Kotturpuram 2nd main road in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/9772,Roads,Completed,NN-ADYAR,172,608000,"Relaying of bitumen concrete at Kotturpuram 3rd main road in Division 172,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 BR/2019-20/11077,Roads,Completed,BR-Bus Route Roads,173,1600000,"Improvements to Signals, Providing Sign Boards, Stainless steel hand rails, Safety Studs, and centre median maintanance works under road safety at various Roads in P.S. Kumarasami raja salai, DGS Dinakaran Road, Broadies castle road, Durgabai deshmukh road in Dn. 173 & 176 in Zone -13.",Own Sources,13,2019-20,2021-22 BR/2019-20/11240,Roads,Completed,BR-Bus Route Roads,173,997000,"Forming Granite Footpath at D.G.S Dinakaran salai in front of Ambedkar Mani Mandapam (Inner and Outer Gate Pathway) in Dn. 173, Zone- 13",Own Sources,13,2019-20,2020-21 BR/2019-20/11241,Roads,Completed,BR-Bus Route Roads,173,992000,"Forming Granite Footpath at D.G.S Dinakaran Salai in front of Ambedkar Mani Mandapam (Southern side of Inner Gate Pathway) in Dn. 173, Zone -13",Own Sources,13,2019-20,2020-21 BR/2019-20/11243,Roads,Completed,BR-Bus Route Roads,173,998000,"Forming Granite Footpath at D.G.S Dinakaran Salai in front of Ambedkar Mani Mandapam (Southern side of Outer Gate Pathway) in Dn. 173, Zone -13",Own Sources,13,2019-20,2020-21 BR/2019-20/11244,Roads,Completed,BR-Bus Route Roads,173,995000,"Forming Granite Footpath at D.G.S Dinakaran Salai in front of Ambedkar Mani Mandapam (Northern side of Inner Gate Pathway) in Dn. 173, Zone -13.",Own Sources,13,2019-20,2020-21 BR/2019-20/16065,Roads,Completed,BR-Bus Route Roads,173,926000,"Restoration of OFC Roadcut at 14nos of Road by Service Department in Div - 173, Zone - 13",Deposit Works,13,2019-20,2020-21 BR/2019-20/3423,Roads,Completed,BR-Bus Route Roads,173,2490000,"Strengthing and relaying of the road at Dr.D.G.S Dinakaran salai (from Jn CMA Building to Jn of MRC nagar main road) in Div -173, Zone 13",Own Sources,13,2019-20,2020-21 BR/2019-20/4859,Roads,Completed,BR-Bus Route Roads,173,8278000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Durgabai Deshmukh Road(from the jn of Adyar signal to Thiru Vi Ka Bridge towards Adyar ) in Dn-173, Zone - XIII",Grants,13,2019-20,2020-21 BR/2019-20/5209,Roads,Completed,BR-Bus Route Roads,173,291000,"Partly relaying the road with BC after cold milling by paver finisher at P.S.Kumaraswamy Raja Salai in Dn-173 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5307,Roads,Completed,BR-Bus Route Roads,173,388000,"Partly relaying the road with BC after cold milling by paver finisher at Srinivasa Avenue in Dn-173 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5309,Roads,Completed,BR-Bus Route Roads,173,678000,"Partly relaying the road with BC after cold milling by paver finisher at Dr.DGS Dinakaran Salai in Dn-173 , Zone - XIII",Grants,13,2019-20,2020-21 BR/2019-20/5496,Roads,Completed,BR-Bus Route Roads,173,550000,"Providing and laying Mastic Asphalt at DGS Dinakaran Salai in Front of Metro Water Filling Station in Dn-173, Z-13",Own Sources,13,2019-20,2020-21 BR/2019-20/6837,Roads,Completed,BR-Bus Route Roads,173,2346000,"Attending urgent patch work at D.G.S.Dinakaran Salai and D.D.Road in Dn.173, Zone-XIII",Own Sources,13,2019-20,2020-21 D/2019-20/4027,Storm Water Drain,Completed,D-Storm Water Drains,173,49470000,"Construction of Missing Link Storm Water Drain at R.K.Mutt Road and 5 other roads in Dn. 173,,Zone - 13, Package -6.",SMART CITY - SWD,13,2019-20,2020-21 L/2019-20/7517,Electrical,Completed,L-Electrical,173,648000,"Replacement of 14nos of damaged and rusted post into new 8mtr mtr GI posts without double arch bracket and 54 nos of pedestal construction of exising lamp posts at DGS Dinakaran Salai in Division-173, Zone-XIII.",Own Sources,13,2019-20,2020-21 NN/2019-20/16682,Roads,Completed,NN-ADYAR,173,658000,"Annual Maintanance Estimate for park at Kesavaperumalpuram East Avenue in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16683,Roads,Completed,NN-ADYAR,173,600000,"Annual Maintanance Estimate for park at Kesavaperumalpuram Central Avenue in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16684,Roads,Completed,NN-ADYAR,173,630000,"Annual Maintanance Estimate for park at Krishnapuri main road in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16685,Roads,Completed,NN-ADYAR,173,930000,"Annual Maintanance Estimate for park at Kamarajar salai (Dharmambal park) in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16686,Roads,Completed,NN-ADYAR,173,627000,"Annual Maintanance Estimate for park at RK Nagar 2nd street in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16687,Roads,Completed,NN-ADYAR,173,647000,"Annual Maintanance Estimate for park at May flower garden,Srinivasa avenue in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16688,Roads,Completed,NN-ADYAR,173,988000,"Annual Maintanance Estimate for park at MRC Nagar .Extn in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16689,Roads,Completed,NN-ADYAR,173,647000,"Annual Maintanance Estimate for park at Vasantha avenue in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16690,Roads,Completed,NN-ADYAR,173,645000,"Annual Maintanance Estimate for park at Sathyadev avenue in Division 173,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/1710,Buildings,Completed,NN-ADYAR,173,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT MRC NAGAR IN DIV-173,UNIT-40,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/17289,Electrical,Completed,NN-ADYAR,173,1031000,"Relaying of Bitumen concrete Road at School View Road (part) in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2021-22 NN/2019-20/17290,Electrical,Completed,NN-ADYAR,173,2293000,"Relaying of Bitumen concrete Road at Janaki Avenue in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/17291,Electrical,Completed,NN-ADYAR,173,374000,"Relaying of Bitumen concrete Road at Karpagam Avenue IV Street and Lane in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2021-22 NN/2019-20/17292,Electrical,Completed,NN-ADYAR,173,877000,"Relaying of Bitumen concrete Road at Rohini Garden Main Road in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/17293,Electrical,Completed,NN-ADYAR,173,1046000,"Relaying of Bitumen concrete Road at RK Nagar III Cross Street in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2021-22 NN/2019-20/17294,Roads,Completed,NN-ADYAR,173,3710000,"Relaying of Bitumen concrete Road at M.R.C Nagar Main Road in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/17304,Electrical,Completed,NN-ADYAR,173,2008000,"Relaying of Bitumen concrete Road at Thiruveedhiamman koil street in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/17305,Electrical,Completed,NN-ADYAR,173,78000,"Relaying of Bitumen concrete Road at Bagirathi Amman Street in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/17306,Electrical,Completed,NN-ADYAR,173,1207000,"Relaying of Bitumen Concrete Road at Sathyadev Avenue Extn in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/2005,Buildings,Completed,NN-ADYAR,173,101000,"PROVIDING MULCH PIT FOR DRY WASTE COMPOSTING PURPOSE AT VARIOUS LOCATION IN DN-173,U-40,Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/2007,Buildings,Completed,NN-ADYAR,173,391000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE AT VARIOUS LOCATION IN DIV-173,U-40,Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/3107,Buildings,Completed,NN-ADYAR,173,625000,"Outsourcing for maintanance the Guest house at DGS Dinakaran salai in Dn 173,U-40,Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/4545,Buildings,Completed,NN-ADYAR,173,500000,Supplying and Fixing of GYM Materials for GYM Building at R.K Nagar Kamarajar salai in Division -173 Unit -40 Zone -13.(Under MLA Fund),MLACDS,13,2019-20,2019-20 NN/2019-20/5535,Roads,Completed,NN-ADYAR,173,350000,"Providing Stage, Shamina, barricading work and forming Temporary Road for the immersion of Ganesha idol in Sea shore at Srinivasapuram in Dn 173, Unit-40, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/5613,Buildings,Completed,NN-ADYAR,173,221000,"PROVIDING OF RAIN WATER HARVESTING WORKS IN GCC BUILDINGS AT VARIOUS LOCATIONS IN DIV173,UNIT-40,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6603,Buildings,Completed,NN-ADYAR,173,384000,"Desilting of Storm Water Drain at Interior roads in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6604,Buildings,Completed,NN-ADYAR,173,202000,"Desilting of Storm Water Drain at Bus Route Roads in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6607,Buildings,Completed,NN-ADYAR,173,706000,"Minor Repair Works in Strorm Water Drain at Inteior roads in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6608,Buildings,Completed,NN-ADYAR,173,714000,"Minor Repair works in storm water drain at Bus Route Roads in Division 173,Unit-40,Zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/8719,Roads,Completed,NN-ADYAR,173,476000,"Supply of 100kg to 150kg multiple bailing Press machine, Transportation, Erection and Commissioning, Fitting charges 2 Coats, of Zinc chrome, 2 Coats of poly Urethane paint including 18% GST at Arulayampet Burial Ground Compost Yard in Dn.170, Unit-40A, Zone-13",Own Sources,13,2019-20,2019-20 NN/2019-20/9790,Roads,Completed,NN-ADYAR,173,556000,"Relaying of bitumen concrete at Sringeri Mutt Road in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/9792,Roads,Completed,NN-ADYAR,173,1031000,"Relaying of bitumen concrete at Kutti Gramani Street in Division 173,Unit-40,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/9979,Buildings,Completed,NN-ADYAR,173,246000,"REPAIR AND IMPROVEENT TO FOOTPATH PAINTING DGS DINAGARAN SALAI IN DN-173, U-40, Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/9980,Buildings,Completed,NN-ADYAR,173,155000,"REPAIR AND IMPROVEENT TO PIPE LINE WORK AND SILT CATCH PIT , FRC DOOR RAISING AT VARIOUS STREETS IN DN-173, U-40, Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/9981,Buildings,Completed,NN-ADYAR,173,173000,"REPAIR AND IMPROVEENT TO FOUNDAN, GUEST HOUSE AT DINAGARAN SALAI, IN DN-173, U-40, Z-13.",Own Sources,13,2019-20,2020-21 BR/2019-20/16066,Roads,Completed,BR-Bus Route Roads,174,894000,"Restoration of OFC Roadcut at 07nos of Road by Service Department in Div - 171, 173 & 174, Zone - 13",Deposit Works,13,2019-20,2020-21 BR/2019-20/5210,Roads,Completed,BR-Bus Route Roads,174,291000,"Partly relaying the road with BC after cold milling by paver finisher at Velachery Main Road in Dn-174 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5306,Roads,Completed,BR-Bus Route Roads,174,581000,"Partly relaying the road with BC after cold milling by paver finisher at Five Furlong Road in Dn-174 , Zone - 13",Grants,13,2019-20,2020-21 L/2019-20/14911,Electrical,Completed,L-Electrical,174,328000,"PROVISION OF 7NOS 6MTR LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 40/50W LED FITTINGS AT BLUE CROSS ROAD IN DIV 174, ZONE-XIII.",Own Sources,13,2019-20,2021-22 L/2019-20/5556,Electrical,Completed,L-Electrical,174,129500,"Removal of Existing 42nos of 11mtr old lamp post at Velachery main road (Sardarpatel road JN to Swimming pool road JN ) in div 174, Zone-XIII.",Own Sources,13,2019-20,2020-21 L/2019-20/7293,Electrical,Completed,L-Electrical,174,839000,"Provision of Painting of 997 NOS 6/7 Mtr Lamp Post, 136 Nos 8 Mtrs Lamp Post, 209nos 9.2mtr lamp post and 16nos 2/3 lamp post, 30nos KIOSK Pillar Box and 1358 post Numbering and 762Nos lamp post new concrete pedestal at Various Streets at Velachery and maduvankarai in Div-174, Zone-XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/11728,Buildings,Completed,NN-ADYAR,174,420000,"Annual maintance to the public convience at city link road and velechery main road in dn -174,ut-40a,zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/1426,Buildings,Completed,NN-ADYAR,174,334000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTIMG PURPOSE AT VARIOUS LOCATION IN DN-174,U-40A,Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/1427,Buildings,Completed,NN-ADYAR,174,180000,"Construction of Mulch pit at Various location in Div -174, Unit-40A, Zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/14984,Buildings,Completed,NN-ADYAR,174,34000,"Minors repairs works to the amma unavagam at race course rd,velechery main rd, at in dn -174,ut-40a,zone-13.",Own Sources,13,2019-20,2021-22 NN/2019-20/14985,Buildings,Completed,NN-ADYAR,174,48000,"DEFACING THE WALL AT RACE COURSE ROAD FOR ARRIVAL OF CHINA PRESIDENT AT DN-174,UT-40A,ZONE-13",Own Sources,13,2019-20,2021-22 NN/2019-20/1658,Buildings,Completed,NN-ADYAR,174,3571000,"Proposed Micro Compost Center at Velachery Burial Ground, Velachery Main Road (Near Gurunanak college) in Division-174, unit- 40A, Zone-13",Own Sources,13,2019-20,2019-20 NN/2019-20/16710,Roads,Completed,NN-ADYAR,174,1167000,"Annual Maintanance Estimate for park at City Limit Road in Division 174,Unit-40A,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16711,Roads,Completed,NN-ADYAR,174,1607000,"Annual Maintanance Estimate for park at Pandian street in Division 174,Unit-40A,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/17009,Roads,Completed,NN-ADYAR,174,214000,"Relaying the Bt Road At Sengeniamman Koil Street (Part) in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17010,Roads,Completed,NN-ADYAR,174,608000,"Relaying the Bt Road At Vigneshwara street in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17011,Roads,Completed,NN-ADYAR,174,495000,"Relaying the Bt Road At Indira street in Dn-174,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17012,Roads,Completed,NN-ADYAR,174,188000,"Relaying the Bt Road At Cart Track road lane in Dn-174,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17013,Roads,Completed,NN-ADYAR,174,617000,"Relaying the Bt Road At Race View Colony main road in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17014,Roads,Completed,NN-ADYAR,174,249000,"Relaying the Bt Road At Anna Garden 2nd Street in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17015,Roads,Completed,NN-ADYAR,174,289000,"Relaying the Bt Road At Narasingapuram 4th Street in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17016,Roads,Completed,NN-ADYAR,174,391000,"Relaying the Bt Road At Narasingapuram 5th Street in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17017,Roads,Completed,NN-ADYAR,174,824000,"Relaying the Bt Road At Madhavan Street in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17018,Roads,Completed,NN-ADYAR,174,336000,"Relaying the Bt Road At Pillaiyar Koil Street (Part) in Dn-174,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17029,Roads,Completed,NN-ADYAR,174,166000,"Relaying the CC Road At Kannigapuram 6th Street in Dn-174 , Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/1723,Buildings,Completed,NN-ADYAR,174,294000,"'PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT VELACHERY BURIAL GROUND (Near Guru Nanak College) IN DIVISION 174, UNIT 40(A), ZONE 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/2094,Buildings,Completed,NN-ADYAR,174,179000,"Providing Compactor bin platform and apporch at various streets Dn-174,Unit - 40A, Zone - XIII",Own Sources,13,2019-20,2019-20 NN/2019-20/3913,Buildings,Completed,NN-ADYAR,174,590000,"Providing Rain Water Harvesting at GCC Buildings in Div - 174, Unit - 40A, Zone - 13",Own Sources,13,2019-20,2019-20 NN/2019-20/4215,Electrical,Completed,NN-ADYAR,174,451000,"Repair & Replacement of Electrical Cremation Furnace Burning Coils, Panel Board Service and Automatic Timer, Connecter and Temperature Meter Change, 5HP Centrifugal Fan ID and Bearing Change, Furnace Door Gear Motor and Fully Service Work and Smoke Water Recycling Plumping work in Electrical Crematorium at Velachery main road in Div-174, Zone-XIII.",Own Sources,13,2019-20,2019-20 NN/2019-20/6656,Buildings,Completed,NN-ADYAR,174,1347000,"MINOR REPAIR WORK to SWD at various locations in Div-174, Unit-40(A), Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/8063,Buildings,Completed,NN-ADYAR,174,92000,"Attending minor Patch Work and potholes for damaged portions at Various Street in DN - 174, Unit-40A , Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/9689,Buildings,Completed,NN-ADYAR,174,1999600,"NEW FORMATION OF ROAD SIDE PARK AT RACE VIEW COLONY MAIN ROAD (UNDER MLA FUND)IN DN-174,UT-40A ,ZONE-13",MLACDS,13,2019-20,2021-22 NN/2019-20/9690,Buildings,Completed,NN-ADYAR,174,606000,"PROPOSED B T ROAD AT ANGALAMMAN KOVIL 2 ND STREET IN DN-174,UT-40A ZONE-13.",Own Sources,13,2019-20,2020-21 B/2019-20/5135,Buildings,Completed,B-Buildings,175,9300000,"Proposed Construction of Additional Floor in First Floor for Chennai primary School at Kamaraj Avenue, Adyar in Div -175, Zone-13",Own Sources,13,2019-20,2020-21 BR/2019-20/10451,Buildings,Completed,BR-Bus Route Roads,175,980000,Supplying and fixing barbed wire fencing over the proposed compound wall with L angle supports From Kasturibai nagar railway station to near leather institute Reach 1 in Div-175 Zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/10453,Buildings,Completed,BR-Bus Route Roads,175,998000,Supplying and fixing barbed wire fencing over the proposed compound wall with L angle From Indira nagar railway station steel bridge to Tidal park road crossing bridge Reach 3 in Div-175 Zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/10454,Buildings,Completed,BR-Bus Route Roads,175,975000,Supplying and fixing barbed wire fencing over the proposed compound wall with L angle From Tidal park road crossing bridge to Tiruvanmiyur railway station (near signal)Reach 4 in Div-175 Zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/10455,Buildings,Completed,BR-Bus Route Roads,175,317000,Supplying and fixing barbed wire fencing over the proposed compound wall with L angle From Tiruvanmiyur railway station (near signal) to Csir road junction Reach 5 in Div-175 Zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/11075,Roads,Completed,BR-Bus Route Roads,175,991000,RESTORATION OF OFC ROAD CUT AT VARIOUS BUS ROUTE ROADS IN ZONE-13. Deposit code -57/0357/2018-19,Deposit Works,13,2019-20,2020-21 BR/2019-20/14511,Road Cut,Completed,BR-Bus Route Roads,175,530000,"Restoration of Road cut made by OFC operators at various Bus Route Road in Div - 175 ,Zone 13",Deposit Works,13,2019-20,2020-21 BR/2019-20/15992,Road Cut,Completed,BR-Bus Route Roads,175,439000,"Restoration of OFC Road-cut at various location in Division 175,176 & 177, Zone -13",Deposit Works,13,2019-20,2020-21 BR/2019-20/16067,Roads,Completed,BR-Bus Route Roads,175,926000,Restoration of OFC Roadcut at 6nos of Road by Service Department in Div - 174 & 175 Zone - 13,Deposit Works,13,2019-20,2020-21 BR/2019-20/16068,Roads,Completed,BR-Bus Route Roads,175,926000,Restoration of OFC Roadcut at 6nos of Road by Service Department in Div - 174 & 175 Zone - 13,Deposit Works,13,2019-20,2020-21 BR/2019-20/16189,Buildings,Completed,BR-Bus Route Roads,175,977000,Supplying and fixing barbed wire fencing over the proposed compound wall with L angle supports From leather institute to Indira nagar railway station steel bridge Reach 2 in Div-175 Zone-13,Own Sources,13,2019-20,2020-21 BR/2019-20/18121,Road Cut,Completed,BR-Bus Route Roads,175,991000,"Restoration of OFC Road cut at 16 Nos of interior Roads in Div-175 & 176, Zone-13.",Deposit Works,13,2019-20,2020-21 BR/2019-20/4856,Roads,Completed,BR-Bus Route Roads,175,6469000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Dr.Muthulakshmi Salai(from Adyar Signal to Sastri Nagar Jn) in Dn-175, Zone - XIII",Grants,13,2019-20,2020-21 BR/2019-20/5207,Roads,Completed,BR-Bus Route Roads,175,581000,"Partly relaying the road with BC after cold milling by paver finisher at Kalki Krishnamurthy Salai in Dn-175 &178 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/8148,Roads,Completed,BR-Bus Route Roads,175,975000,Restoration of OFC Roadcut at 08nos of Road by Service Department in Div - 175 & 176 Zone - 13,Deposit Works,13,2019-20,2020-21 D/2019-20/4028,Storm Water Drain,Completed,D-Storm Water Drains,175,27840000,"Construction of Missing Link Storm Water Drain at Anna Avenue and 4 other roads in Dn. 175 & 176,Zone - 13, Package -7.",SMART CITY - SWD,13,2019-20,2020-21 J/2019-20/10816,Buildings,Completed,J-Bridges,175,309000,"Painting the existing kerb and side of lattice bridge flyover in division -175,Zone-13",Own Sources,13,2019-20,2019-20 J/2019-20/8219/C,Bridges,Completed,J-Bridges,175,539997,Reconstruction of Retaining wall along B canal at madhya kailash & sardar patel road junction in zone-13,Own Sources,13,2019-20,2019-20 NN/2019-20/12144,Road Cut,Completed,NN-ADYAR,175,2734000,"Milling and Laying of Bituminous road at B-Ramachandra Adhithanar Salai (Part) From Gandhi Nagar Sports Club to junction of Gandhi Nagar 1st main road in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/12576,Roads,Completed,NN-ADYAR,175,2370000,"Milling and Relaying of road with B.T.coarse at Kasthuribai nagar 2nd cross street in Dn175,Unit 40, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/12720,Roads,Completed,NN-ADYAR,175,1005000,"Milling and Relaying of road with B.T.coarse at Thiruvengadam street in Dn175,Unit 40, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/12723,Roads,Completed,NN-ADYAR,175,546000,"Milling and Relaying of road with B.T.coarse at Dhanalakshmi Avenue I Road in Dn175,Unit 40, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/12724,Roads,Completed,NN-ADYAR,175,643000,"Milling and Relaying of road with B.T.coarse at Bakthavatchalam nagar I Street in Dn175, Unit 40, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/14416,Buildings,Completed,NN-ADYAR,175,83000,"Providing shed for Composting Well Ring in GCC Land at Canal Bank Road, K.B nagar, jn. of K.B Nagar 3rd main road in Dn-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/14855,Roads,Completed,NN-ADYAR,175,436000,"Milling and Laying of Bituminous road at Gandhi nagar 3rd canal cross street (part) in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/14859,Roads,Completed,NN-ADYAR,175,399000,"Milling and Laying of Bituminous road at Kasthuribai nagar 2nd main road (part) in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/14860,Roads,Completed,NN-ADYAR,175,2951000,"Milling and Laying of Bituminous road at Gandhi nagar 2nd main road (part) junction of 1st cross street to junction of Ramachandra adhithanar salai in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/14861,Roads,Completed,NN-ADYAR,175,920000,"Milling and Laying of Bituminous road at Gandhi nagar 2nd canal cross street in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/14862,Roads,Completed,NN-ADYAR,175,2381000,"Milling and Laying of Bituminous road at Gandhi nagar cresent avenue road in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2021-22 NN/2019-20/14863,Roads,Completed,NN-ADYAR,175,2827000,"Milling and Laying of Bituminous road at Gandhi nagar 3rd main road (part) in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1688,Buildings,Completed,NN-ADYAR,175,106000,"Providing Mulch pit for Dry Waste Composting Purpose inside the Park and Various Streets in Div -175, Unit-40, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1689,Buildings,Completed,NN-ADYAR,175,350000,"Supplying and Fixing of Well Rings for Composting Purpose at inside the Park and Various Streets in Dn-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1716,Buildings,Completed,NN-ADYAR,175,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT LAKE VIEW ROAD IN DIV-175,UNIT-40,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/17339,Roads,Completed,NN-ADYAR,175,1550000,"Annual Maintanance Estimate for park at Indira Nagar 4th cross street,Adyar in Division 175,Unit-40,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/17354,Roads,Completed,NN-ADYAR,175,572000,"Milling and Laying of Bituminous road at Gandhi nagar 3rd crescent park in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/17358,Roads,Completed,NN-ADYAR,175,2477000,"Milling and Laying of Bituminous road at Gandhi nagar 1st main road (part) junction of Ramachandra Adhithanar Salai to junction of 1dt cross street in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/2427,Parks,Completed,NN-ADYAR,175,683000,"IMPROVEMENT OF CENTERMEDIAN IN DIV-173,175 UNIT-40,DIV176,, Div- 181, UNIT-38,DIV-180 UNIT-39 ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4689,Road Cut,Completed,NN-ADYAR,175,367000,"Restoration of road cut made by CMWSSB at Indira nagar 26th cross street (ch 0 to 140m) in dn-175, Unit-40, Zone-13.",Deposit Works,13,2019-20,2019-20 NN/2019-20/4696,Buildings,Completed,NN-ADYAR,175,160000,"Erection of Bore well 50 m depth with water supply arrangements in CHS at Kamaraj Avenue, Adyar in Dn-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/4700,Storm Water Drain,Completed,NN-ADYAR,175,336000,"Providing Trash arrester for ISWD disposal points at Various Locations in Dn-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4744,Electrical,Completed,NN-ADYAR,175,682500,"Providing Comprehensive Annual Maintenance for 1 No 62.5 KVA Diesel Genset at Multi Speciality Hospital at Maduvankarai in Div-174 and 1 No 100 KVA Diesel Genset at 24x7 E.O.C , Venkatrathinam Nagar in Div-175 and 2 Nos 30 KVA Diesel Genset at Health Centre, Seva Nagar, Velachery in Div-179 and Gothavari Street, Thanthai Periyar Nagar, Tharamani in Div-180 Zone-XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/4747,Electrical,Completed,NN-ADYAR,175,703500,"Providing Comprehensive Annual Maintenance for 4 Nos 20 KVA Diesel Genset at Chennai High School at Anna Salai in Div-170, Kotturpuram in Div-172, Kamaraj Avenue in Div-175 & Rajalakshmi Nagar, Velachery in Div-178 and 2 nos 30 KVA Diesel Genset at Chennai Higher Secondary������������������ Maduvankarai in Div-174 and Peeliamman Koil Street,Tharamani in Div-180 & 1 No 62.5 KVA Diesel Genset at Chennai Higher Secondary School, Bharadidasan Street, Thiruvanmiyur in Div-182, Zone-XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/4749,Electrical,Completed,NN-ADYAR,175,1118000,"Providing Comprehensive Annual Maintenance for 1 No 100 KVA Diesel Genset at Zonal Office-XIII and 1 No 62.5 KVA Diesel Genset at Lorry Station, Saidapet in Div-171 and 2 Nos 40 KVA Diesel Genset at Aranganathan Subway in Div-171, 1 No 30 KVA Diesel Genset at Unit Office Building-38, Kamaraj Nagar West, Thiruvanmiyur in Div-182 and 1 No 20 KVA Diesel Genset at Unit Office Building-40A, Brindavan Nagar Main Road, Adambakkam in Div-177 and 4 Nos 5 KVA Diesel Genset at Saidapet, Indira Nagar, Velachery and Thruvanmiyur Substations and 1 No 5KVA Genset Fixed in Mobile Highamst at Zonal Office in Zone-XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/5324,Roads,Completed,NN-ADYAR,175,136000,"Restoration of road cut made by CMWSSB at Indira nagar 26th cross street (ch 140.00 m to 190 m) in dn-175, Unit-40, Zone-13.",Deposit Works,13,2019-20,2019-20 NN/2019-20/5691,Roads,Completed,NN-ADYAR,175,189000,"PAINTING BLACK AND WHITE TO THE FOOTPATH KERBS IN THE VIEW OF INDEPENDENCE DAY 2019 AT SARDAR PATEL ROAD AND DD ROAD IN DN-175, UNIT-40, ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/5911,Buildings,Completed,NN-ADYAR,175,484000,"Providing Rain water Harvesting structures in GCC Buildings at Various Locations in division 175, Unit 40, Zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6287,Buildings,Completed,NN-ADYAR,175,545000,"Proposed Construction of Compound wall with Gate & Gate pillars for GCC land (western side) in Kottur village, Block no.24, T.S no.2, old survey no. 2/2B2PT, 2/2APT, 2/2BPT, 2/1PT at Canal Bank Road, Gandhi nagar Near Kotturpuram MRTS Railway station, Adyar in Dn 175, Unit 40, Zone 13. (Reach ch 0 m to 45 m)",Own Sources,13,2019-20,2020-21 NN/2019-20/6300,Buildings,Completed,NN-ADYAR,175,234000,"Providing Chain Link Fencing with RCC post for GCC land at Canal Bank Road, Gandhi Nagar Behind of Kottourpuram MRTS Railway station, Adyar in Div-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6682,Storm Water Drain,Completed,NN-ADYAR,175,1099000,"Minor Repair Work of Storm Water Drain at Various Streets in Division-175, Unit-40, Zone-13. (Part-1), Package-1",Own Sources,13,2019-20,2019-20 NN/2019-20/6687,Storm Water Drain,Completed,NN-ADYAR,175,337000,"Desilting of Storm Water Drain at Various Streets in Division-175, Unit-40, Zone-13 (Part-1), Package-1",Own Sources,13,2019-20,2019-20 NN/2019-20/6689,Storm Water Drain,Completed,NN-ADYAR,175,1237000,"Desilting of Storm Water Drain at Various Streets in Division-175, Unit-40, Zone-13. (Part-2) Package-2",Own Sources,13,2019-20,2019-20 NN/2019-20/6690,Storm Water Drain,Completed,NN-ADYAR,175,478000,"Minor Repair Work of Storm Water Drain at Various Streets in Division-175, Unit-40, Zone-13, (Part-2), Package-2.",Own Sources,13,2019-20,2019-20 NN/2019-20/6693,Buildings,Completed,NN-ADYAR,175,980000,"Engaging 6Nos of watchmen for one year at Zonal office - XIII, Dr.Muthulakshmi salaI in Division - 175, Zone - XIII.",Own Sources,13,2019-20,2021-22 NN/2019-20/6972,Buildings,Completed,NN-ADYAR,175,2450000,"Repairs and Improvements work of Annex Building in Zonal office 13 campus at Thiruvengadam street in Dn-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/7969,Footpath,Completed,NN-ADYAR,175,495000,"Repair and Improvement work of existing footpath on both sides at Indira nagar 2nd Avenue Bridge Jn. Of Rajiv Gandhi Salai in Dn-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/7978,Footpath,Completed,NN-ADYAR,175,333000,"Providing Chain Link Fencing with RCC post for GCC land in Kottur village, Block no.24, T.S no.2, old survey no. 2/2B2PT, 2/2APT, 2/2BPT, 2/1PT at Canal Bank Road, Gandhi nagar Near Kotturpuram MRTS Railway station, Adyar in Div-175, Unit-40, Zone-13",Own Sources,13,2019-20,2019-20 NN/2019-20/8193,Roads,Completed,NN-ADYAR,175,407000,"Attending minor C.C. patch work with RMC M20 at various streets in DN 175, Unit 40, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/8214,Roads,Completed,NN-ADYAR,175,315000,"Providing Thermoplastic marking on existing speed breakers at Various strees in Dn-175, Unit-40, Zone-40.",Own Sources,13,2019-20,2020-21 NN/2019-20/8335,Roads,Completed,NN-ADYAR,175,1105000,"Providing Rain water Harvesting at Various Locations in Gandhi Nagar, K.B Nagar and Indira Nagar in division-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/8613,Roads,Completed,NN-ADYAR,175,141000,"Supplying and erecting of 21 Nos of Leaves Dumping cylindrical storage container with lid at various locations of Gandhi Nagar and Kasturibai Nagar in Division 175, Unit 40, Zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/9336,Buildings,Completed,NN-ADYAR,175,1669000,"Removal of Debris / Excavation earth and filling the sand from outside for formation of mini forest in GCC land in kottur village,block No 23,T.S No.3,old survey No.2/2APT,2/2BPT,2/2B2PT at canal bank road ,Gandhi nagar behind the Kotturpuram MRTS railway station in Dn-175, Unit-40, Zone-13.",Own Sources,13,2019-20,2020-21 BR/2019-20/11105,Road Cut,Completed,BR-Bus Route Roads,176,1005000,"RESTORATION OF OFC ROAD CUT IN VARIOUS LOCATIONS AT DIVISION -176, ZONE-13. DEPOSIT CODE-57/0522/2018-19",Deposit Works,13,2019-20,2020-21 BR/2019-20/5298,Roads,Completed,BR-Bus Route Roads,176,193000,"Partly relaying the road with BC after cold milling by paver finisher at Mahatma Gandhi Road in Dn-176 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/7383,Road Cut,Completed,BR-Bus Route Roads,176,975000,Restoration of OFC Roadcut at 07nos of Road by Service Department in Div - 176 & 181 Zone - 13,Deposit Works,13,2019-20,2020-21 NN/2019-20/10496,Roads,Completed,NN-ADYAR,176,295000,"Relaying of Bituminous Concrete Road at Abaranjini Avenue in division 176,Unit-38,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/10497,Roads,Completed,NN-ADYAR,176,741000,"Relaying of Bituminous Concrete Road at Sastri Nagar 2nd Cross Street in division 176, Unit 38, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10498,Roads,Completed,NN-ADYAR,176,124000,"Relaying of Bituminous Concrete Road at Sastri Nagar X Lane(Part) in division 176, Unit 38, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10499,Roads,Completed,NN-ADYAR,176,868000,"Relaying of Bituminous Concrete Road at Besant Nagar 33rd Cross Street in division 176, Unit 38, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10500,Roads,Completed,NN-ADYAR,176,192447,"Relaying of Bituminous Concrete Road at MGR Colony in division 176, Unit 38, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10501,Roads,Completed,NN-ADYAR,176,429000,"Relaying of Bituminous Concrete Road at Arunachalapuram 1st Street in division 176, Unit 38, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10502,Roads,Completed,NN-ADYAR,176,577000,"Relaying of Bituminous Concrete Road at Karpagam Garden 3rd Cross Street in division 176, Unit 38, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10712,Buildings,Completed,NN-ADYAR,176,1142000,"Additional work for MICRO COMPOST CENTRE AT BURIAL GROUND, BESANT NAGAR 1ST MAIN ROAD IN DIV176, UNIT-38, ZONE-13",Own Sources,13,2019-20,2021-22 NN/2019-20/13268,Buildings,Completed,NN-ADYAR,176,55000,"Improvement works to footpath at karpagam garden 2nd cross street in Division 176.Unit-38,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13269,Buildings,Completed,NN-ADYAR,176,114000,"Improvement works Public Convenience at Arunachalapuram in Division 176.Unit-38,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13270,Buildings,Completed,NN-ADYAR,176,125000,"Improvement works Public Conveniance at Thiruvalluvar nagar in Division 176.Unit-38,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13271,Buildings,Completed,NN-ADYAR,176,122000,"Improvement works to Chennai Middle school at Dhamodharapuram in Division 176.Unit-38,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13272,Buildings,Completed,NN-ADYAR,176,51000,"Improvement works at 32nd cross street playground, Besant Nagar in Division 176.Unit-38,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13273,Buildings,Completed,NN-ADYAR,176,33000,"Repair works to Burial Ground at Besant Nagar 1st main road in Division 176.Unit-38,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13780,Roads,Completed,NN-ADYAR,176,119000,"Relaying of Bituminous Concrete Road at Sastri Nagar 11th Cross Street in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/13781,Roads,Completed,NN-ADYAR,176,97000,"Relaying of Bituminous Concrete Road at Sastri Nagar 12th Cross Street in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/13783,Roads,Completed,NN-ADYAR,176,58000,"Relaying of Bituminous Concrete Road at Sastri Nagar 8th Cross Street Part in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/13784,Roads,Completed,NN-ADYAR,176,53000,"Relaying of Bituminous Concrete Road at Karpagam Garden 2nd Main Road- Part in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/13785,Roads,Completed,NN-ADYAR,176,80000,"Relaying of Bituminous Concrete Road at Padmanbha Nagar 4th Street- Part in Division-176, Unit-38 Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13786,Footpath,Completed,NN-ADYAR,176,221000,"Relaying of Bituminous Concrete Road at Besant Nagar 6th Street- Part in Division-176, Unit-38 Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/13787,Roads,Completed,NN-ADYAR,176,87000,"Relaying of Bituminous Concrete Road at Besant Nagar 7th Cross Street- Part in Division-176, Unit-38 Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13788,Roads,Completed,NN-ADYAR,176,60000,"Relaying of Bituminous Concrete Road at Besant Nagar 14th Cross Street- Part in Division-176, Unit-38 Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13789,Roads,Completed,NN-ADYAR,176,66000,"Relaying of Bituminous Concrete Road at Besant Nagar 21st Cross Street- Part in Division-176, Unit-38 Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13790,Roads,Completed,NN-ADYAR,176,53000,"Relaying of Bituminous Concrete Road at Besant Nagar 32nd Cross Street- Part in Division-176, Unit-38 Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13791,Roads,Completed,NN-ADYAR,176,122000,"Relaying of Bituminous Concrete Road at Venkateswara Nagar 5th Street- Part in Division-176, Unit-38 Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/14030,Roads,Completed,NN-ADYAR,176,2556000,"Relaying of Bituminous Concrete Road at Ellai Amman Koil Street in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/14032,Roads,Completed,NN-ADYAR,176,948000,"Relaying of Bituminous Concrete Road at Sastri Nagar 1st Cross Street in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/14034,Roads,Completed,NN-ADYAR,176,1221000,"Relaying of Bituminous Concrete Road at Sastri Nagar 6th Cross Street in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/14035,Roads,Completed,NN-ADYAR,176,1864000,"Relaying of Bituminous Concrete Road at Vasantha Press Road in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/14037,Roads,Completed,NN-ADYAR,176,853000,"Relaying of Bituminous Concrete Road at Ponniamman Koil Street in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/14038,Roads,Completed,NN-ADYAR,176,562000,"Relaying of Bituminous Concrete Road at Thiruvalluvar Nagar 1st Main Road- Part in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/14039,Roads,Completed,NN-ADYAR,176,1948000,"Relaying of Bituminous Concrete Road at Blue Cross Street in division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/1443,Parks,Completed,NN-ADYAR,176,406000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DIV - 176, U-38, Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/1448,Parks,Completed,NN-ADYAR,176,173000,"PROVIDING MULCH PIT FOR DRY WASTE COMPOSTING PURPOSE INSIDE PARKS AT VARIOUS LOCATION IN DN-176, UNIT - 38, ZONE - 13",Own Sources,13,2019-20,2019-20 NN/2019-20/1464,Buildings,Completed,NN-ADYAR,176,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT BURIAL GROUND, BESANT NAGAR 1ST MAIN ROAD IN DIV - 176, UNIT - 38, ZONE - 13",Own Sources,13,2019-20,2020-21 NN/2019-20/1548,Roads,Completed,NN-ADYAR,176,3410000,"PROPOSED CONSTRUCTION OF MICRO COMPOST CENTRE AT BURIAL GROUND,BESANT NAGAR 1ST MAIN ROAD IN DIV176,UNIT-38,ZONE-13",Own Sources,13,2019-20,2019-20 NN/2019-20/1640,Buildings,Completed,NN-ADYAR,176,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT KAMARAJ NAGAR 22nd STREET OSR LAND IN DIV - 182, UNIT - 38, ZONE - 13",Own Sources,13,2019-20,2020-21 NN/2019-20/16667,Roads,Completed,NN-ADYAR,176,634000,"Annual Maintanance Estimate for park at Padmanbha nagar 4th cross street in Division 176,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16668,Roads,Completed,NN-ADYAR,176,677000,"Annual Maintanance Estimate for park at Dr Muthulakshmi park in Division 176,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/3161,Buildings,Completed,NN-ADYAR,176,160000,"Providing Bore Well for Chennai Middle School at Dhamodharapuram 5th Street in Div - 176, Unit - 38, Zone - 13",Own Sources,13,2019-20,2020-21 NN/2019-20/3452,Roads,Completed,NN-ADYAR,176,669000,"Supplying and erecting of 100 Nos of Leaves Dumping cylindrical storage container with lid at various locations in Division - 176, Unit - 38, Zone - XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/3768,Roads,Completed,NN-ADYAR,176,1765000,"Providing Rain Water Harvesting at various locations in Div - 176, Unit - 38, Zone - 13",Own Sources,13,2019-20,2019-20 NN/2019-20/3805,Storm Water Drain,Completed,NN-ADYAR,176,46000,"Providing trash arrester for ISWD disposal point at Durgabhai Deshmukh Road in DN-176,U-38,Zone13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4701,Buildings,Completed,NN-ADYAR,176,160000,"Providing Bore Well for Chennai Primary School at Shastri Nagar 11th Cross Street in Div - 176, Unit - 38, Zone - 13",Own Sources,13,2019-20,2020-21 NN/2019-20/4704,Buildings,Completed,NN-ADYAR,176,716000,"Improvements to Police Boys Club at Urur Alcot Kuppam Salai ,Besant Nagar in Div176,Unit-38,Zone-13",Own Sources,13,2019-20,2019-20 NN/2019-20/5909,Storm Water Drain,Completed,NN-ADYAR,176,763000,"Providing Rain Water Harvesting Structure in GCC Buildings at Various locations Dn-176, Unit-38, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6357,Storm Water Drain,Completed,NN-ADYAR,176,65000,"Providing Rain water Harvesting Awarness Board of Size 2 Feet X 3 Feet at various locations in Division 176, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/6679,Storm Water Drain,Completed,NN-ADYAR,176,226000,"Desilting to Existing Storm water drain at Sastri Nagar I avenue, Sastri Nagar I Main Road, Sastri Nagar IX lane, Sastri Nagar I Cross Street, Sastri Nagar VIII Cross Street, Sastri Nagar IX Cross Street, Sastri Nagar X Cross Street, Sastri Nagar XI Cross Street, Sastri Nagar XIII Cross Street, Sastri Nagar XV Cross Street, Sastri Nagar II Cross Street and Sastri Nagar II Avenue in division 176, unit 38, zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6680,Storm Water Drain,Completed,NN-ADYAR,176,164000,"Desilting to Existing Storm water drain at Karpagam Garden I Main Road, Padmanabanagar I street, Ramasamy Garden, Parameaswary nagar II street, Parameswari nagar I street, Vasantha Press Road, Jeevaratinam nagar main road, Venkateswara III street, Jeevaratinam I street, Jeevaratinam II street, Padmanabanagar III street, Padmanabanagar IV street, Padmanabanagar V street, Besant nagar I main road, Besant avenue and Durgabai Deshmuk road in division 176, unit 38, zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6681,Storm Water Drain,Completed,NN-ADYAR,176,1573000,"Repair Works to Existing Storm water drain at Sastri Nagar I avenue, Sastri Nagar I Main Road, Sastri Nagar IX lane, Sastri Nagar I Cross Street, Sastri Nagar VIII Cross Street, Sastri Nagar IX Cross Street, Sastri Nagar X Cross Street, Sastri Nagar XI Cross Street, Sastri Nagar XIII Cross Street, Sastri Nagar XV Cross Street, Sastri Nagar II Cross Street and Sastri Nagar II Avenue in division 176, unit 38, zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6684,Storm Water Drain,Completed,NN-ADYAR,176,1745000,"Repairs to Existing Storm water drain at Karpagam Garden I Main Road, Padmanabanagar I street, Ramasamy Garden, Parameaswary nagar II street, Parameswari nagar I street, Vasantha Press Road, Jeevaratinam nagar main road, Venkateswara III street, Jeevaratinam I street, Jeevaratinam II street, Padmanabanagar III street, Padmanabanagar IV street, Padmanabanagar V street, Besant nagar I main road, Besant avenue and Durgabai Deshmuk road in division 176, unit 38, zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/8058,Roads,Completed,NN-ADYAR,176,402000,"Attending Minor Patch work and Pot holes in Various interior roads in Division-176,Unit-38,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/8464,Buildings,Completed,NN-ADYAR,176,172000,"Providing Fish type Modular bin at Elliots Beach in division 176, Unit 38 Zone 13.",Own Sources,13,2019-20,2019-20 BR/2019-20/17636,Roads,Completed,BR-Bus Route Roads,177,975000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-177 UNIT-40A ZONE-13(DEPOSIT CODE-57/1133/2018-19),Deposit Works,13,2019-20,2020-21 BR/2019-20/17637,Roads,Completed,BR-Bus Route Roads,177,975000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-177 UNIT-40A ZONE-13(DEPOSIT CODE-57/1133/2018-19),Deposit Works,13,2019-20,2020-21 BR/2019-20/4855,Roads,Completed,BR-Bus Route Roads,177,1336000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Lake view Road(part) in Dn-177, Zone - XIII",Grants,13,2019-20,2020-21 BR/2019-20/4857,Roads,Completed,BR-Bus Route Roads,177,2396000,"Relaying the road with DBM and BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Mahalakshmi Nagar 1 st main Road in Dn-177, Zone - XIII",Grants,13,2019-20,2020-21 BR/2019-20/5294,Roads,Completed,BR-Bus Route Roads,177,218000,"Partly relaying the road with BC after cold milling by paver finisher at Kakkan Nagar Main Road in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5295,Roads,Completed,BR-Bus Route Roads,177,218000,"Partly relaying the road with BC after cold milling by paver finisher at Sastri Nagar Main Road in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5299,Roads,Completed,BR-Bus Route Roads,177,291000,"Partly relaying the road with BC after cold milling by paver finisher at Mahalakshmi Nagar 2nd Main Road in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5300,Roads,Completed,BR-Bus Route Roads,177,291000,"Partly relaying the road with BC after cold milling by paver finisher at Mahalakshmi Nagar 3rd Main Road in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5301,Roads,Completed,BR-Bus Route Roads,177,193000,"Partly relaying the road with BC after cold milling by paver finisher at Andal Nagar 1 st Cross Street in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5302,Roads,Completed,BR-Bus Route Roads,177,193000,"Partly relaying the road with BC after cold milling by paver finisher at Andal Nagar 1 st Main Road in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5303,Roads,Completed,BR-Bus Route Roads,177,193000,"Partly relaying the road with BC after cold milling by paver finisher at Andal Nagar 6 th Cross Street in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/5304,Roads,Completed,BR-Bus Route Roads,177,388000,"Partly relaying the road with BC after cold milling by paver finisher at AGS Colony 4 th Main Road in Dn-177 , Zone - 13",Grants,13,2019-20,2020-21 D/2019-20/4029,Storm Water Drain,Completed,D-Storm Water Drains,177,58080000,"Construction of Missing Link Storm Water Drain at TNHB 3rd Main Road and 9 other roads in Dn. 177,Zone - 13, Package -8.",SMART CITY - SWD,13,2019-20,2020-21 L/2019-20/7288,Electrical,Completed,L-Electrical,177,933200,PROVISION OF PAINTING OF 2483 NOS 6/7 Mtr LAMP POST AND 621 NOS NEW CONCRETE PEDESTAL AT VARIOUS STREETS AT VELACHERY WEST IN DIV-177 IN ZONE-XIII,Own Sources,13,2019-20,2020-21 L/2019-20/8669,Electrical,Completed,L-Electrical,177,8510000,"PROVISION OF REPLACEMENT OF 227 NOS 6/7 MTRS RUSTED AND SHORT LAMP POST TO NEW 6 MTR GI LAMP POST AND 2 NOS 8 MTR RUSTED AND SHORT LAMP POST TO NEW 8 MTR GI LAMP POST IN DIV-170,177 ZONE-XIII",Grants,13,2019-20,2020-21 L/2019-20/8672,Electrical,Completed,L-Electrical,177,1351000,PROVISION OF LAYING OF DAMAGED 2380 MTRS 31/2X25 SQ.MM ALUMINIUM CABLE AT VARIOUS STREETS IN DIV-170 & 177 ZONE-XIII,Grants,13,2019-20,2020-21 NN/2019-20/1096,Buildings,Completed,NN-ADYAR,177,562000,"Providing Bore well , Under Ground Sump and Repairs Work to UPHC at Sastri Nagar 4th street IN DN-177,UNIT-40A,ZONE-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/11871,Parks,Completed,NN-ADYAR,177,462000,"Annual Maintenance Estimate for Park at TNHB Colony 4th Street in DN-177, Unit40A, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1250,Buildings,Completed,NN-ADYAR,177,389000,"Supplying and Fixing of Well Rings for Composting Purpose at Various locations in Dn-177, Unit-40A, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1290,Buildings,Completed,NN-ADYAR,177,26000,"Construction of Mulch pit at LH Nagar 3rd cross street Play ground in Div -177, Unit-40A, Zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/13288,Roads,Completed,NN-ADYAR,177,309000,"Relaying the Bitumen Road At Ex Serviceman colony 2nd street in Dn-177,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13290,Roads,Completed,NN-ADYAR,177,363000,"Relaying the Bitumen Road At TNHB Colony 3rd street in Dn-177,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13291,Roads,Completed,NN-ADYAR,177,341000,"Relaying the Bitumen Road At Rajiv gandhi Nagar Main Road in Dn-177,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/14015,Buildings,Completed,NN-ADYAR,177,418000,"Attending Patch Work at Various Street in DN - 177, Unit-40A , Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/14016,Buildings,Completed,NN-ADYAR,177,152000,"Repair and improvement works to Anganwadi at NNGO Colony 2nd main road, N.G.O. Colony 1st main road, N.S.K. 2nd Street in DN - 177, Unit-40A , Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16671,Roads,Completed,NN-ADYAR,177,703000,"Annual Maintanance Estimate for park at New NGO colony 2nd main road in Division 177,Unit-40A,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16672,Roads,Completed,NN-ADYAR,177,615000,"Annual Maintanance Estimate for park at LH Nagar 4th cross street in Division 177,Unit-40A,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16673,Roads,Completed,NN-ADYAR,177,574000,"Annual Maintanance Estimate for park at Gangai nagar 2nd main road in Division 177,Unit-40A,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/17098,Roads,Completed,NN-ADYAR,177,424000,"Relaying the Bt Road At TNHB Colony 10th Street in Dn-177,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17099,Roads,Completed,NN-ADYAR,177,418000,"Relaying the Bt Road At TNHB Colony 8th Street in Dn-177,Unit-40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17100,Roads,Completed,NN-ADYAR,177,588000,"Relaying the Bt Road At TNHB Colony 4th avenue in Dn-177,Unit- 40A,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17126,Roads,Completed,NN-ADYAR,177,295000,"Relaying the Bt Road At TNHB Colony 3rd main road(Part) in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17127,Roads,Completed,NN-ADYAR,177,478000,"Relaying the Bt Rajiv Nagar Amman Koil Street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17128,Roads,Completed,NN-ADYAR,177,551000,"Relaying the Bt Road At Venkateshwara Nagar 3rd Main Road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17129,Roads,Completed,NN-ADYAR,177,136000,"Relaying the Bt Road At Venkateshwara Nagar 3rd Main Road 1st Cross street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17130,Roads,Completed,NN-ADYAR,177,801000,"Relaying the Bt Road At Venkateshwara Nagar 3rd Main Road 2nd Cross street in Dn-177, Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17132,Roads,Completed,NN-ADYAR,177,284000,"Relaying the Bt Road At Venkateshwara Nagar 5th street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17133,Roads,Completed,NN-ADYAR,177,375000,"Relaying the Bt Road At MGR Nagar 3rd Main Road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17134,Roads,Completed,NN-ADYAR,177,211000,"Relaying the Bt Road At Vadivambal nagar 2nd Main Road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17135,Roads,Completed,NN-ADYAR,177,518000,"Relaying the Bt Road At Venkateshwara Nagar 2nd Main Road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17140,Roads,Completed,NN-ADYAR,177,625000,"Relaying the Bt Road At Lakshmi Nagar Main Road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17141,Roads,Completed,NN-ADYAR,177,385000,"Relaying the Bt Road At Lakshmi Nagar 1st cross street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17142,Roads,Completed,NN-ADYAR,177,235000,"Relaying the Bt Road At VV Colony 4th street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17143,Roads,Completed,NN-ADYAR,177,159000,"Relaying the Bt Road At Ganesh Nagar 4th street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17153,Roads,Completed,NN-ADYAR,177,234000,"Relaying the Bt Road At Ganesh Nagar Main road (M.L.Nagar)in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17168,Roads,Completed,NN-ADYAR,177,331000,"Relaying the Bt Road At Joseph Colony Main road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17169,Roads,Completed,NN-ADYAR,177,351000,"Relaying the Bt Road At Mahalakshmi Nagar 13th cross street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17170,Roads,Completed,NN-ADYAR,177,351000,"Relaying the Bt Road At Mahalakshmi Nagar 14th cross street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17171,Roads,Completed,NN-ADYAR,177,176000,"Relaying the Bt Road At Ashtalakshmi Nagar 5th street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17172,Roads,Completed,NN-ADYAR,177,662000,"Relaying the Bt Road At ASK Nagar Main road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17173,Roads,Completed,NN-ADYAR,177,336000,"Relaying the Bt Road At E.B. Colony 5th Street 1st cross street in Dn-177, Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17174,Roads,Completed,NN-ADYAR,177,456000,"Relaying the Bt Road At Gangai Nagar 3rd Main road in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17175,Roads,Completed,NN-ADYAR,177,284000,"Relaying the Bt Road At New Secretraiat Colony 1st street in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2021-22 NN/2019-20/17178,Roads,Completed,NN-ADYAR,177,1499000,"Relaying the CC Road At TNHB colony 2nd Main road(Part) in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/17179,Roads,Completed,NN-ADYAR,177,276000,"Relaying the CC Road At Netaji colony 7th cross street (part) in Dn-177,Unit-40A, Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/3461,Buildings,Completed,NN-ADYAR,177,220000,"Trash Arrestor in Storm Water Drains At Various Location in Division - 177, Unit - 40A, Zone - 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4198,Buildings,Completed,NN-ADYAR,177,614000,"PROVIDING RAIN WATER HARVESTING AT GCC BUILDINGS IN DIVISION 177,UNIT40A, ZONE13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6617,Buildings,Completed,NN-ADYAR,177,1137000,"SWD DESILTING WORK AT VARIOUS STREETS (PART - 2) IN DN 177, unit - 40(A), ZONE - 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6618,Buildings,Completed,NN-ADYAR,177,1347000,"Minor Repair Work of STORM WATER DRAIN at Various Streets (PART-1) in Division-177, UNIT-40A, ZONE-13",Own Sources,13,2019-20,2019-20 NN/2019-20/6633,Buildings,Completed,NN-ADYAR,177,1137000,"SWD DESILTING WORK AT VARIOUS STREETS (PART - 1) IN DN 177, unit - 40(A), ZONE - 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6634,Buildings,Completed,NN-ADYAR,177,1350000,"Minor Repair Work of STORM WATER DRAIN at Various Streets ( PART -2 )in Division-177, UNIT-40A, ZONE-13",Own Sources,13,2019-20,2019-20 NN/2019-20/6651,Buildings,Completed,NN-ADYAR,177,1079000,"SWD DESILTING WORK AT VARIOUS STREETS IN DN 174, unit - 40(A), ZONE - 13",Own Sources,13,2019-20,2019-20 NN/2019-20/8060,Buildings,Completed,NN-ADYAR,177,388000,"Attending minor Patch Work and potholes for damaged portions at Various Street in DN - 177, Unit-40A , Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/8861,Roads,Completed,NN-ADYAR,177,490000,"FORMING THE CC ROAD AT NGO COLONY 3RD CROSS STREET (LANE) IN DN-177,UNIT-40A,ZONE-13",Own Sources,13,2019-20,2020-21 L/2019-20/2410,Electrical,Completed,L-Electrical,178,4255000,"PROVISION OF 44NOS 8MTR G.I LAMP POST WITH SINGLE STRAIGHT BRACKET WITH 150/165W LED FITTINGS C.SET AT VELACHERY 100FEET ROAD (VIJAYA NAGAR SIGNAL TO VELACHERY PETROL BUNK) ONLY SERVICE ROAD IN VELACHERY DIV-178, ZONE-XIII (DEPOSIT WORK)",Deposit Works,13,2019-20,2020-21 NN/2019-20/11481,Buildings,Completed,NN-ADYAR,178,490000,"Maintenance works to CPS & CHSS at Rajalakshmi Nagar 2nd main road in Dn-178, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1246,Parks,Completed,NN-ADYAR,178,262000,"Supplying and Fixing of Well Rings for Composting Purpose at Various locations in Dn-178, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13275,Roads,Completed,NN-ADYAR,178,905000,"Relaying the Bt Road At Ram Nagar 7th Main Road (Part) in Dn-178,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13277,Roads,Completed,NN-ADYAR,178,414000,"forming Bt Road At Officer Colony(Part) in Dn-178,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/13280,Roads,Completed,NN-ADYAR,178,306000,"Relaying the Bt Road At AGS Colony 10th CrossStreet Extn 1st Street in Dn-178,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16626,Roads,Completed,NN-ADYAR,178,409000,"Laying of C.C. Road at Throwpathy Amman Koil 1st Lane in Dn-178,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16627,Roads,Completed,NN-ADYAR,178,298000,"Laying of C.C. Road at Throwpathy Amman Koil 3rd Lane in Dn-178,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16628,Roads,Completed,NN-ADYAR,178,600000,"Laying of C.C. Road at Throwpathy Amman Koil 6th Lane in Dn-178,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16629,Roads,Completed,NN-ADYAR,178,803000,"Laying of C.C. Road at Lakshmipuram 1st cross street in Dn-178,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16663,Roads,Completed,NN-ADYAR,178,641000,"Annual Maintanance Estimate for park at AGS colony 4th main road in Division 178,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16664,Roads,Completed,NN-ADYAR,178,639000,"Annual Maintanance Estimate for park at AGS colony 4th cross street in Division 178,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16665,Roads,Completed,NN-ADYAR,178,610000,"Annual Maintanance Estimate for park at AGS colony 5th cross street in Division 178,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/3520,Buildings,Completed,NN-ADYAR,178,222000,"Trash Arrestor in Storm Water Drains at Various location in Dn-178, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/3969,Storm Water Drain,Completed,NN-ADYAR,178,374000,"Providing Rain Water Harvesting at various location of GCC Buildings in Dn-178, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/4586,Storm Water Drain,Completed,NN-ADYAR,178,285000,"Desilting of storm water drain at Kalki Nagar,A.G.S Colony,Srinivasa Nagar,Kuberan Nagar,Shankar Nagar,Padmavathi Nagar in DN-178,Unit-39,Zone-13",Own Sources,13,2019-20,2019-20 NN/2019-20/4591,Storm Water Drain,Completed,NN-ADYAR,178,350000,"Desilting of storm water drain at Ram Nagar,Vijaya Nagar, Murugu Nagar,Srinivasa Nagar extn in DN-178,Unit-39,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4600,Storm Water Drain,Completed,NN-ADYAR,178,1180000,"Minor Repair works & Replacing of damaged manhole door for Storm Water Drain at Various Streets in Dn-178, Unit-39, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4840,Buildings,Completed,NN-ADYAR,178,320000,"Erection of two bore well 50m depth each with water supply arrangements in CHSS & CPS at Rajalakshmi Nagar 2nd main road (core city) in Dn 178, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6237,Buildings,Completed,NN-ADYAR,178,57000,"Improvement work at Anganwadi, Rajalakshmi Nagar 2nd Main Road in Dn-178,Unit-39,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6239,Buildings,Completed,NN-ADYAR,178,179000,"Improvement work at Anganwadi, Throwpathy amman koil 5th street in DN-178,Unit-39,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6241,Buildings,Completed,NN-ADYAR,178,286000,"Improvement work at Anganwadi, Brahmin street in Dn-178, Unit-39,Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6678,Storm Water Drain,Completed,NN-ADYAR,178,1700000,"Minor Repair Work & Replacing of damaged manhole door for Storm water drain at Various Streets in Division-178, UNIT-39, ZONE-13",Own Sources,13,2019-20,2019-20 NN/2019-20/6997,Storm Water Drain,Completed,NN-ADYAR,178,67000,"Providing RCC NON PRESSURE SPUN PIPE at Nattar Kullam,Nattar street in DN-178, Unit-39,Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/8077,Roads,Completed,NN-ADYAR,178,403000,"Attending Minor Patch work and Pot holes at various streets in Dn 178, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 BR/2019-20/13656,Road Cut,Completed,BR-Bus Route Roads,179,845000,RESTORATION OF ROAD CUT MADE BY RELIANCE JIO AT VARIOUS INTERIOR ROADS IN DIV-179&182 UNIT-39 ZONE-13(DEPOSIT CODE-57/1144/2018-19),Deposit Works,13,2019-20,2020-21 BR/2019-20/13659,Roads,Completed,BR-Bus Route Roads,179,942000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-179 UNIT-39 ZONE-13(DEPOSIT CODE-57/1144/2018-19),Deposit Works,13,2019-20,2020-21 BR/2019-20/13662,Road Cut,Completed,BR-Bus Route Roads,179,942000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-179 UNIT-39 ZONE- 13 (DEPOSIT CODE-57/1144/2018-19),Deposit Works,13,2019-20,2020-21 BR/2019-20/16069,Road Cut,Completed,BR-Bus Route Roads,179,674000,"Restoration of OFC Roadcut at 11nos of Road by Service Department in Div - 176, 177, 179, 180 & 182 Zone - 13",Deposit Works,13,2019-20,2020-21 BR/2019-20/5297,Roads,Completed,BR-Bus Route Roads,179,291000,"Partly relaying the road with BC after cold milling by paver finisher at Gandhi Road in Dn-179 , Zone - 13",Grants,13,2019-20,2020-21 L/2019-20/5554,Electrical,Completed,L-Electrical,179,998000,"Provision of 22nos of 6mtr G.I lamp post with single st. bracket with 12nos 40/50w LED fittings and 10nos 10/20W LED fittings at Natarajan cross street, Muthukrishnan Street , VGP Selva Nagar 3rd street, Srinivasa nagar 2nd street and Ram Nagar 8th street in Velachery Div-179 and 178 Zone-XIII.",Own Sources,13,2019-20,2020-21 L/2019-20/7292,Electrical,Completed,L-Electrical,179,986000,"Provision of Painting of 3033 NOS 6/7 Mtr Lamp Post, 243 Nos 8 Mtrs Lamp Post, 88nos 9.2mtr lamp post and 113nos 2/3 lamp post, 76nos KIOSK Pillar Box and 3477 post Numbering and 164nos lamp post new concrete pedestal at Various Streets at Velachery in Div-178 & 179, ZONE-XIII",Own Sources,13,2019-20,2020-21 L/2019-20/8678,Electrical,Completed,L-Electrical,179,2237000,"REPLACEMENT OF LAYING OF DAMAGED 2376 MTR 2X16SQ.MM AND 2105 MTR 4X16 SQ.M AND 140MTR 31/2X25 SQ.MM ALUMINIUM CABLE AT VARIOUS STREETS AT VARIOUS LOCATION IN VELACHERY AND MADUVAKARAI IN DIV174,178 AND 179, ZONE-XIII",Grants,13,2019-20,2020-21 NN/2019-20/1220,Buildings,Completed,NN-ADYAR,179,3577000,"PROPOSED CONSTRUCTION OF COMPOST YARD INSIDE THE CORPORATION BURIAL GROUND AT VELACHERY - TARAMANI 100 FEET ROAD IN DN-179, UNIT-39, ZONE-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1241,Buildings,Completed,NN-ADYAR,179,693000,"Supplying and Fixing of Well Rings for Composting Purpose at Various locations in Dn-179, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/13286,Roads,Completed,NN-ADYAR,179,444000,"Relaying the Bt Road At Balamurugan Nagar 2nd Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16506,Roads,Completed,NN-ADYAR,179,774000,"Relaying of road with B.T. Coarse at Natrajan Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16509,Roads,Completed,NN-ADYAR,179,317000,"Relaying of road with B.T. Coarse at Dhandeeswaram Nagar 11th Cross Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16510,Roads,Completed,NN-ADYAR,179,331000,"Relaying of road with B.T. Coarse at Dhandeeswaram Nagar 10th main road in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16518,Roads,Completed,NN-ADYAR,179,380000,"Relaying of road with B.T. Coarse at New Colony 2nd main road in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16519,Roads,Completed,NN-ADYAR,179,675000,"Relaying of road with B.T. Coarse at Ambika Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16527,Roads,Completed,NN-ADYAR,179,1215000,"Relaying of road with B.T. Coarse at Bethel Avenue main road in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16529,Roads,Completed,NN-ADYAR,179,226000,"Relaying of road with B.T. Coarse at Bethel Avenue 2nd Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16531,Roads,Completed,NN-ADYAR,179,241000,"Relaying of road with B.T. Coarse at Bethel Avenue 4th Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16539,Roads,Completed,NN-ADYAR,179,530000,"Relaying of road with B.T. Coarse at Seethapathy Nagar 2nd cross street (Part) in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16541,Roads,Completed,NN-ADYAR,179,903000,"Relaying of road with B.T. Coarse at Shanthi Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16545,Roads,Completed,NN-ADYAR,179,166000,"Relaying of road with B.T. Coarse at Sarathy Nagar 3rd Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16546,Roads,Completed,NN-ADYAR,179,181000,"Relaying of road with B.T. Coarse at Sarathy Nagar 4th Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16547,Roads,Completed,NN-ADYAR,179,166000,"Relaying of road with B.T. Coarse at Sarathy Nagar 6th Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16548,Roads,Completed,NN-ADYAR,179,337000,"Relaying of road with B.T. Coarse at Dhandeeswaram Nagar 2nd main road in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16549,Roads,Completed,NN-ADYAR,179,318000,"Relaying of road with B.T. Coarse at Ambika Cross Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16551,Roads,Completed,NN-ADYAR,179,213000,"Relaying of road with B.T. Coarse at Chellappa Street in Dn-179,Unit-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/16725,Roads,Completed,NN-ADYAR,179,930000,"Annual Maintanance Estimate for park at V.G.P.Selva nagar 2nd main road in Division 179,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16726,Roads,Completed,NN-ADYAR,179,655000,"Annual Maintanance Estimate for park at Ramagiri nagar 1st street in Division 179,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16727,Roads,Completed,NN-ADYAR,179,632000,"Annual Maintanance Estimate for park at Bharathiyar park at Velachery main road in Division 179,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16728,Roads,Completed,NN-ADYAR,179,230000,"Annual Maintanance Estimate for park at Thiruvalluvar park at Gandhi Road in Division 179,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/1724,Buildings,Completed,NN-ADYAR,179,294000,"PROPOSED CONSTRUCTION OF MATERIAL RESOURCE FACILITY AT VELACHERY THARAMANI BYPASS ROAD IN DIV-179,UNIT-39,ZONE-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4174,Storm Water Drain,Completed,NN-ADYAR,179,383000,"Providing Rain Water Harvesting Structure in GCC Buildings at various locations in Dn-179, Unit-39, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4287,Parks,Completed,NN-ADYAR,179,886000,"Proposed Construction of Compound wall with Gate & Gate pillar for Road Side Park at Velachery Main Road, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6075,Buildings,Completed,NN-ADYAR,179,998000,"Conversion and improving of Existing Gasifier Crematorium to manual LPG Burner system crematorium at Velachery-Taramani 100 feet road Burial ground (Opp. to TCS), Velachery in Dn-179, unit-39, zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6393,Buildings,Completed,NN-ADYAR,179,286000,"Converting to Rain Water Harvesting purpose for the existing unused Community Well at Mahalakshmi Street in Dn-179, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6395,Buildings,Completed,NN-ADYAR,179,303000,"Converting to Rain Water Harvesting purpose for the existing unused Community Well at Gandhi Road in Div-179,U-39,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/6628,Storm Water Drain,Completed,NN-ADYAR,179,1050000,"Desilting of Storm Water Drain at Various Streets in Dn-179, Unit 39, Zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6630,Storm Water Drain,Completed,NN-ADYAR,179,1208000,"Minor Repair works of Storm Water Drain at Various Streets in Dn-179, Unit-39, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6695,Storm Water Drain,Completed,NN-ADYAR,179,290000,"Converting to Rain Water Harvesting purpose for the existing unused Community Well at East Mada Street in Dn-179, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6842,Buildings,Completed,NN-ADYAR,179,151000,"Proposed construction of Sump for Public Convenience at Thiruveetiamman Koil Street in Dn-179, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/7179,Buildings,Completed,NN-ADYAR,179,404000,"Proposed Construction of Compound wall with gate & gate pillar for O.S.R. land at Seshadripuram 1st main road in Dn-179, Unit-39, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/7180,Buildings,Completed,NN-ADYAR,179,577000,"Proposed Construction of Compound wall with Gate & Gate pillar for OSR land at Anna Nagar 5th main road, Velachery in Dn 179, Unit 39, Zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/8052,Roads,Completed,NN-ADYAR,179,394000,"Restoration of Potholes with cement concrete patches in Div-179, U-39, Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/8180,Buildings,Completed,NN-ADYAR,179,298000,"Maintenance works to existing public convenience and toilet at UPHC in Dn 179, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/8440,Buildings,Completed,NN-ADYAR,179,278000,"Providing GSB, Wetmix at various streets & Repair works to existing SWD at Dhandapani Street, Providing FRC manhole door at various streets and Providing bin platform at various streets in Dn 179, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 BR/2019-20/18034,Roads,Completed,BR-Bus Route Roads,180,3930000,"Relaying the road with DBM and BC after cold milling by paver finisher using along with traffic improvement work at CPT Campus, 4th Street, Taramani in Dn-180, Zone - XIII",Grants,13,2019-20,2020-21 BR/2019-20/5305,Roads,Completed,BR-Bus Route Roads,180,388000,"Partly relaying the road with BC after cold milling by paver finisher at CSIR Road in Dn-180 , Zone - 13",Grants,13,2019-20,2020-21 BR/2019-20/8089,Roads,Completed,BR-Bus Route Roads,180,680000,"Laying of DBM & BC and other Traffic improvement works at kanagam Periyar Nagar salai & Kanagam Pillayar koil street in div-180,zone-13.",Own Sources,13,2019-20,2019-20 L/2019-20/13848,Electrical,Completed,L-Electrical,180,198000,"PROVISION OF REPLACEMENT OF DAMAGED AND RUSTED 5 NOS KIOSK PILLAR BOX AT COASTAL ROAD, BESANT NAGAR, VEMBULIAMMAN KOIL STREET, NEW BEACH ROAD AND LB ROAD IN DIV-180, 181 & 182 ZONE-XIII",Own Sources,13,2019-20,2020-21 L/2019-20/7018,Electrical,Completed,L-Electrical,180,974000,"PROVISION OF PAINTING OF 4050 NOS 6/7 Mtr Lamp Post AND 387 Nos 8 Mtrs LAMP POST AT VARIOUS STREETS AT THARAMANI, BESANT NAGAR AND THIRUVANMIYUR IN DIV-180, 181 & 182 IN ZONE-XIII",Own Sources,13,2019-20,2020-21 L/2019-20/7441,Electrical,Completed,L-Electrical,180,1546000,"PROVISION OF SUPPLY AND ERECTION OF 41 NOS OF 6 MTR LAMP POST WITH 1 MTR GI CURVED SINGLE BRACKET WITH 41 NOS 10-20W LED FITTING AT M.G NAGAR KAMARAJAR CROSS STREETS AND GANDHI ST EXTN, ANNA NAGAR VAIGAI & MGR STREET AND ANBALAGAN NAGAR CROSS STREET AT THARAMANI IN DIV-180, ZONE-XIII",Own Sources,13,2019-20,2020-21 L/2019-20/8644,Electrical,Completed,L-Electrical,180,2546000,"PROVISION OF REPLACEMENT OF DAMAGED 5595 MTRS 2X16SQ.MM ALUMINIUM CABLE AND 153 MTRS 31/2X25 SQ.MM ALU CABLE AT VARIOUS STREETS IN THARAMANI, THIRUVANMIYUR & BESANT NAGAR IN DIV-180, 181 & 182, ZONE-XIII",Grants,13,2019-20,2020-21 L/2019-20/8652,Electrical,Completed,L-Electrical,180,16339000,"PROVISION OF REPLACEMENT OF 434 NOS 6/7 MTRS RUSTED AND SHORT LAMP POST TO NEW 6 MTR GI LAMP POST AND 7 NOS 8 MTR RUSTED AND SHORT LAMP POST TO NEW 8 MTR GI LAMP POST AT VARIOUS STREETS AT THARAMANI, THIRUVANMIYUR & BESANT NAGAR IN DIV-180, 181 & 182, ZONE-XIII",Grants,13,2019-20,2020-21 NN/2019-20/10343,Buildings,Completed,NN-ADYAR,180,246000,"Improvements to Hospital at Thiruvalluvar Salai, Taramani in Dn 180, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/1591,Buildings,Completed,NN-ADYAR,180,561000,"Supplying and Fixing of Well Rings for Composting Purpose at Various locations in Dn-180, Unit-39, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16613,Roads,Completed,NN-ADYAR,180,367000,"Relaying of C.C. road at Gandhi Street Jayanthi Periyar Nagar in Dn 180, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16614,Roads,Completed,NN-ADYAR,180,1236000,"Relaying of C.C. road at Anna Street Jayanthi Periyar Nagar in Dn 180, Unit 39, Zone 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16633,Roads,Completed,NN-ADYAR,180,695000,"Annual Maintanance Estimate for park at Kamaraj nagar 4th west street in Division 180,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16634,Roads,Completed,NN-ADYAR,180,644000,"Annual Maintanance Estimate for park at Kamaraj nagar 2nd west street in Division 180,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16660,Roads,Completed,NN-ADYAR,180,575000,"Annual Maintanance Estimate for park at Kamaraj nagar 13th west street in Division 180,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16661,Roads,Completed,NN-ADYAR,180,604000,"Annual Maintanance Estimate for park at Nehru street,Kanagam in Division 180,Unit-39,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/3539,Storm Water Drain,Completed,NN-ADYAR,180,400000,"Trash Arrestor in Storm Water Drains At Various Location in Division - 180, Unit - 39, Zone - 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/4359,Roads,Completed,NN-ADYAR,180,400000,"Improvement works to Community Well with Ornamental work at Kanagam Pillaiyar Koil Street, in Div-180,U-39,Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/4621,Buildings,Completed,NN-ADYAR,180,616000,"Providing Rain Water Harvesting Structure using precast well ring in GCC Building at various location in Dn-180, Unit-39, Zone-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6686,Storm Water Drain,Completed,NN-ADYAR,180,786000,"Storm water drain Minor Repair Works and Replacing of damaged Mon hole doors at Kamaraj Nagar 2nd West Street to 12th West Street, Ranganathapuram, West Avenue, L.B. Road,Judges Avenue,Pernthalaivar Kamaraj Nagar, 5th main Road in Dn-180, Unit-39, Zone-13 (Package -1)",Own Sources,13,2019-20,2019-20 NN/2019-20/6688,Storm Water Drain,Completed,NN-ADYAR,180,1115000,"Storm Water Drain Minor Repair Works and Replacing of damaged Mon hole doors at C.S.I.R. Road, Taramani Bus Stand, V.V. Koil Street, Thiruvalluvar Salai, Aragannal Street, Erikkarai Street, Kanagam Periyar Nagar, Peeliamman Koil Street, Anna Street, Ramanujam I.T. Park road, Taramani 4th cross road, Periyar Nagar Tenaments in Dn-180, Unit-39, Zone-13 (Package -2)",Own Sources,13,2019-20,2019-20 NN/2019-20/6725,Storm Water Drain,Completed,NN-ADYAR,180,242000,"Desilting of SWD at Various Streets (Kamaraj Nagar 2nd West Street to 12th West Street, Ranganathapuram, West Avenue, L.B. Road,Judges Avenue,Pernthalaivar Kamaraj Nagar, 5th main Road) in Dn.180 Unit-39 Zone-13",Own Sources,13,2019-20,2019-20 NN/2019-20/6728,Storm Water Drain,Completed,NN-ADYAR,180,712000,"Desilting of SWD at Various Streets (C.S.I.R. Road, Taramani Bus Stand, V.V. Koil Street, Thiruvalluvar Salai, Aragannal Street, Erikkarai Street, Kanagam Periyar Nagar, Peeliamman Koil Street, Anna Street, Ramanujam I.T. Park road, Taramani 4th cross road, Periyar Nagar Tenaments) in Dn.180 Unit-39 Zone-13",Own Sources,13,2019-20,2019-20 NN/2019-20/7077,Buildings,Completed,NN-ADYAR,180,496000,"Improvement works to Community Well with Ornamental work at Kanagam TNSCB Tenaments, in Div-180,U-39,Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/8105,Roads,Completed,NN-ADYAR,180,406000,"Restoration of Potholes with cement concrete patches in Div-180, U-39, Z-13.",Own Sources,13,2019-20,2020-21 BR/2019-20/7146,Roads,Completed,BR-Bus Route Roads,181,975000,Restoration of OFC Roadcut at 07nos of Road by Service Department in Div - 176 & 181 Zone - 13,Deposit Works,13,2019-20,2020-21 BR/2019-20/8165,Roads,Completed,BR-Bus Route Roads,181,820000,"Providing and laying of Bituminous concrete at Kanagam Periyar Nagar Salai in Dn 181, Zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/13755,Roads,Completed,NN-ADYAR,181,693000,"Relaying of Bituminous Concrete Road at T.M.Maistry Street - Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/13756,Roads,Completed,NN-ADYAR,181,1271000,"Relaying of Bituminous Concrete Road at Beach Road - Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/13757,Roads,Completed,NN-ADYAR,181,663000,"Relaying of Bituminous Concrete Road at Parvathy Street - Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/13758,Roads,Completed,NN-ADYAR,181,205000,"Relaying of Bituminous Concrete Road at RBI Colony 2nd Street in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/13759,Roads,Completed,NN-ADYAR,181,982000,"Relaying of Bituminous Concrete Road at 7th Avenue- Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/13760,Roads,Completed,NN-ADYAR,181,342000,"Relaying of Bituminous Concrete Road at Muthulakshmi Salai- Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/13761,Roads,Completed,NN-ADYAR,181,120000,"Relaying of Bituminous Concrete Road at Thirumurugan Street- Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/13762,Roads,Completed,NN-ADYAR,181,64000,"Relaying of Bituminous Concrete Road at Kamaraj Nagar (Marundeeswarar Nagar) Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/13763,Roads,Completed,NN-ADYAR,181,215000,"Relaying of Bituminous Concrete Road at Arundale Beach Road- Part Part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/13764,Roads,Completed,NN-ADYAR,181,63000,"Relaying of Bituminous Concrete Road at Kalakshetra Road- Part division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/13765,Roads,Completed,NN-ADYAR,181,63000,"Relaying of Bituminous Concrete Road at Sriram Nagar Main Road- part in division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2021-22 NN/2019-20/1612,Buildings,Completed,NN-ADYAR,181,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY AT RAJASRINIVASAPURAM BURIAL GROUND, THIRUVANMIYUR, IN DIV 181,UNIT-38,ZONE-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16677,Roads,Completed,NN-ADYAR,181,649000,"Annual Maintanance Estimate for park at M.G.R.Road in Division 181,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16678,Roads,Completed,NN-ADYAR,181,917000,"Annual Maintanance Estimate for park at Gangai street park in Division 181,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16679,Roads,Completed,NN-ADYAR,181,618000,"Annual Maintanance Estimate for park at Yemuna street in Division 181,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16680,Roads,Completed,NN-ADYAR,181,582000,"Annual Maintanance Estimate for park at Tiger Varadhachariyar Park in Division 181,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16681,Roads,Completed,NN-ADYAR,181,656000,"Annual Maintanance Estimate for park at C.G.E Colony in Division 181,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/1977,Buildings,Completed,NN-ADYAR,181,414000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE AT VARIOUS LOCATIONS IN DIV - 181, U-38, Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/3064,Roads,Completed,NN-ADYAR,181,471000,"Improvements to Speed Breakers and Centre Medians at various locations in Div - 181, Unit - 38, Zone - 13.",Own Sources,13,2019-20,2020-21 NN/2019-20/3304,Roads,Completed,NN-ADYAR,181,334000,"Supplying and erecting of 50 Nos of Leaves Dumping cylindrical storage container with lid at various locations in Division - 181, Unit - 38, Zone - XIII",Own Sources,13,2019-20,2019-20 NN/2019-20/3756,Roads,Completed,NN-ADYAR,181,1765000,"Providing Rain Water Harvesting at various locations in Div - 181, Unit - 38, Zone - 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/5892,Buildings,Completed,NN-ADYAR,181,635000,"Providing Rain Water Harvesting Structures in GCC Buildings at Various locations in Div-181, U-38, Z-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6356,Storm Water Drain,Completed,NN-ADYAR,181,65000,"Providing Rain water Harvesting Awarness Board of Size 2 Feet X 3 Feet at various locations in Division 181, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/6717,Storm Water Drain,Completed,NN-ADYAR,181,55000,"Desilting to Existing Storm water drain at Marundeeshwarar Nagar main road, Sivagami puram I Street, Radhakrishnan Nagar III Cross St, Sri ram Nagar main road, Sivagami puram II Street, Malaviya Avenue Main Road, Malaviya Avenue II Street, Malaviya Avenue I Street and II East Street, Kamaraj nagar in division 181, unit 38, zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6720,Storm Water Drain,Completed,NN-ADYAR,181,662000,"Repair works to Existing Storm water drain at Marundeeshwarar Nagar main road, Sivagami puram I Street, Radhakrishnan Nagar III Cross St, Sri ram Nagar main road, Sivagami puram II Street, Malaviya Avenue Main Road, Malaviya Avenue II Street, Malaviya Avenue I Street and II East Street, Kamaraj nagar in division 181, unit 38, zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/8066,Roads,Completed,NN-ADYAR,181,160000,"Attending Minor Patch works and Pothole in Various interior roads in Division-181,Unit-38,Zone-13",Own Sources,13,2019-20,2020-21 NN/2019-20/9861,Footpath,Completed,NN-ADYAR,181,625000,"Providing Barricading arrangements at Elliots Beach in division 176, Ashtalakshmi Koil Beach in division 181 and New Beach in division 182 for New Year-2020 and Pongal Festival 2020 in Unit 38, Zone 13.",Own Sources,13,2019-20,2020-21 P/2019-20/5939,Parks,Completed,P-Parks and Playfields,181,1660000,"IMPROVEMENT AND PROVINDING OF MODERN GYM EQUIPMENTS AT SIVAGAMIPURAM 2ND STREET IN DIV-181,ZONE-13.",Own Sources,13,2019-20,2020-21 BR/2019-20/13053,Road Cut,Completed,BR-Bus Route Roads,182,450000,"Restoration of Road cut made by OFC operators at various Bus Route Road in Div - 182,Zone 13",Deposit Works,13,2019-20,2020-21 NN/2019-20/10011,Buildings,Completed,NN-ADYAR,182,1049000,"Providing hiring of Welding Machines and other materials for Scrap Sculptures Work at CHSS school at Bharathidasan street in Div-182, U-38, Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/10674,Electrical,Completed,NN-ADYAR,182,74000,"Repair and Improvements to MLA office at Kamaraj Nagar 8th East Street in Division-182, Unit-38, Zone-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/11004,Buildings,Completed,NN-ADYAR,182,151000,"Providing Additional Estimate to Nano Compost fard and Material Recovery Facility in Division -182, Unit -38, Zone -13.",Own Sources,13,2019-20,2020-21 NN/2019-20/16635,Roads,Completed,NN-ADYAR,182,927000,"Annual maintenance estiamte for park at Thiruvalluvar nagar 1st avenue in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16636,Roads,Completed,NN-ADYAR,182,663000,"Annual maintenance estiamte for park at Thiruvalluvar nagar 43 rd cross street in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16637,Roads,Completed,NN-ADYAR,182,626000,"Annual maintenance estiamte for park at Journalist colony in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16638,Roads,Completed,NN-ADYAR,182,612000,"Annual maintenance estiamte for park at 1st seaward road in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16639,Roads,Completed,NN-ADYAR,182,622000,"Annual maintenance estiamte for park at Thiruvalluvar nagar 2nd main road in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16640,Roads,Completed,NN-ADYAR,182,920000,"Annual maintenance estiamte for park at Thiruvalluvar nagar 7th cross street in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16641,Roads,Completed,NN-ADYAR,182,623000,"Annual maintenance estiamte for park at Valmigi nagar 69th cross street in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16643,Roads,Completed,NN-ADYAR,182,236000,"Annual maintenance estiamte for park at Kannappa nagar in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/16645,Roads,Completed,NN-ADYAR,182,239000,"Annual maintenance estiamte for park at AIBEA Nagar(Devandra nagar) in Division 182,Unit-38,Zone-13.(Per year)",Own Sources,13,2019-20,2020-21 NN/2019-20/2006,Parks,Completed,NN-ADYAR,182,440000,"SUPPLYING AND FIXING OF WELL RINGS FOR COMPOSTING PURPOSE AT VARIOUS LOCATIONS IN DIV - 182, U-38, Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/2015,Parks,Completed,NN-ADYAR,182,58000,"PROVIDING MULCH PIT FOR DRY WASTE COMPOSTING PURPOSE AT VARIOUS LOCATION IN DN-182, UNIT - 38, ZONE - 13",Own Sources,13,2019-20,2019-20 NN/2019-20/3189,Electrical,Completed,NN-ADYAR,182,217000,"PROVISION OF 8 NOS CCTV CAMERA UNITS AT CHSS, BHARADIDASAN STREET, THIRUVANMIYUR IN DIV-182, ZONE-XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/3538,Storm Water Drain,Completed,NN-ADYAR,182,42000,"Trash Arrestor in Storm Water Drains At two Locations in Avvai Nagar Main Road in Division - 182, Unit - 38, Zone - 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/3679,Buildings,Completed,NN-ADYAR,182,334000,"Supplying and erecting of 50 Nos of Leaves Dumping cylindrical storage container with lid at various locations in Division - 182, Unit - 38, Zone - XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/3775,Roads,Completed,NN-ADYAR,182,1550000,"Providing Rain water Harvesting at East Coast Road, Thiruveediamman koil street, Thiruvalluvar nagar 7th main road, Thiruvalluvar nagar 39th cross street, Thiruvalluvar nagar 48th cross street, Thiruvalluvar nagar 54th cross street, Thiruvalluvar nagar 52nd cross street, in division 182, Unit 38, Zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/4641,Buildings,Completed,NN-ADYAR,182,500000,"Repairs and Maintenance to GCC Assets in Dn - 182, Unit-38, Zone-XIII",Own Sources,13,2019-20,2020-21 NN/2019-20/4710,Buildings,Completed,NN-ADYAR,182,160000,"Providing Borewell for Chennai Primary School at Bharathidhasan Street in Div - 182, Unit - 38, Zone - 13",Own Sources,13,2019-20,2020-21 NN/2019-20/4711,Buildings,Completed,NN-ADYAR,182,160000,"Providing Borewell for Chennai Higher Secondary School at Bharathidhasan Street in Div - 182, Unit - 38, Zone - 13",Own Sources,13,2019-20,2020-21 NN/2019-20/5794,Buildings,Completed,NN-ADYAR,182,972000,"Providing Rain Water Harvesting Structures in GCC Buildings at Various locations in Div-182, U-38, Z-13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6231,Buildings,Completed,NN-ADYAR,182,342000,"Construction of Precast Micro Composting Centre at Unit Office 38 in Div-182, U-38, Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6280,Buildings,Completed,NN-ADYAR,182,672000,"Repair and improvements to Public Conveyances at East Coast Road and Thiruveediamman koil street, Smart toilets at Valmiki nagar 69th cross street, Bhagat Singh Salai, North mada street and Thiruvanmiyur Bus stand, Bio-toilet at Avvai nagar main road in Div-182, U-38, Z-13.",Own Sources,13,2019-20,2020-21 NN/2019-20/6354,Storm Water Drain,Completed,NN-ADYAR,182,65000,"Providing Rain water Harvesting Awarness Board of Size 3Feet X 2 Feet at various locations in Division 182, Unit 38, Zone 13",Own Sources,13,2019-20,2020-21 NN/2019-20/6707,Storm Water Drain,Completed,NN-ADYAR,182,86000,"Desilting to Existing Storm water drain at Kamaraj nagar - VI East Street, Kamaraj Nagar -IV Main road, Kamaraj Nagar - III Main road, Kamaraj Nagar -IX East street, Kamaraj Nagar -XIII East street, Kamaraj Nagar - XIV East street, Kamaraj Nagar -VIII East Street, Kamaraj nagar - V East Street, Kamaraj nagar - South Avenue, Chitrakulam Street, North mada street and Bharathidasan street in division 182, unit 38, zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6708,Storm Water Drain,Completed,NN-ADYAR,182,133000,"Desilting to Existing Storm water drain at Kannappa Nagar Extn, Rajaji nagar main road, Avvai Nagar, Kannappa nagar I main road, Kannappa nagar II street, Kannappa nagar II main road, Dharmambal street, AIBEA Nagar 5th Main road, AIBEA Nagar 5th Main road, AIBEA nagar 3rd main road, AIBEA nagar 1st main road, AIBEA nagar 2nd cross street, AIBEA nagar 4th main road, AIBEA nagar 2nd main road, Rajaji nagar I cross street, Rajaji Nagar II cross street, Pillaiyar Koil Street, Thiruvalluvar Nagar 2nd Avenue ad Rain water Harvesting Structures in division 182, unit 38, zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/6711,Storm Water Drain,Completed,NN-ADYAR,182,610000,"Repair works to Existing Storm water drain at Kamaraj nagar - VI East Street, Kamaraj Nagar -IV Main road, Kamaraj Nagar - III Main road, Kamaraj Nagar -IX East street, Kamaraj Nagar -XIII East street, Kamaraj Nagar - XIV East street, Kamaraj Nagar -VIII East Street, Kamaraj nagar - V East Street, Kamaraj nagar - South Avenue, Chitrakulam Street, North mada street and Bharathidasan street in division 182, unit 38, zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6713,Storm Water Drain,Completed,NN-ADYAR,182,1420000,"Repair works to Existing Storm water drain at Kannappa Nagar Extn, Rajaji nagar main road, Avvai Nagar, Kannappa nagar I main road, Kannappa nagar II street, Kannappa nagar II main road, Dharmambal street, AIBEA Nagar 5th Main road, AIBEA Nagar 5th Main road, AIBEA nagar 3rd main road, AIBEA nagar 1st main road, AIBEA nagar 2nd cross street, AIBEA nagar 4th main road, AIBEA nagar 2nd main road, Rajaji nagar I cross street, Rajaji Nagar II cross street, Pillaiyar Koil Street, Thiruvalluvar Nagar 2nd Avenue ad Rain water Harvesting Structures in division 182, unit 38, zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6718,Storm Water Drain,Completed,NN-ADYAR,182,221000,"Desilting to Existing Storm water drain at III East Street, Kamaraj nagar, I East Street, Kamaraj nagar, Valmigi street, Kamaraj salai, Sivasundar avenue I avenue, Sivasundar avenue II avenue, Kalakshetra Main Road, Radhakrishnan Nagar Main Road, Malaviya avenue III street and Besant Nagar VII Avenue in division 181, unit 38, zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/6723,Storm Water Drain,Completed,NN-ADYAR,182,1236000,"Repair works to Existing Storm water drain at III East Street, Kamaraj nagar, I East Street, Kamaraj nagar, Valmigi street, Kamaraj salai, Sivasundar avenue I avenue, Sivasundar avenue II avenue, Kalakshetra Main Road, Radhakrishnan Nagar Main Road, Malaviya avenue III street and Besant Nagar VII Avenue in division 181, unit 38, zone 13",Own Sources,13,2019-20,2019-20 NN/2019-20/8049,Roads,Completed,NN-ADYAR,182,389000,"Restoration of Potholes with cement concrete patches in Div-182, U-38, Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/8462,Buildings,Completed,NN-ADYAR,182,240000,"Providing Recycling Waste Storage Unit at Unit 38 Office, Unit 40 Office, Unit 40A Office and Unit 39 Office in Zone 13.",Own Sources,13,2019-20,2019-20 NN/2019-20/8556,Buildings,Completed,NN-ADYAR,182,1065000,"Construction of See-through Compound wall to vacant land at Thiruvalluvar nagar 2nd main road, Kamaraj Nagar 22nd East street and Avvai nagar main road in Div-182, U-38, Z-13",Own Sources,13,2019-20,2020-21 NN/2019-20/9563,Buildings,Completed,NN-ADYAR,182,737000,"Supplying of Scrap materials for sculpture work including transportation charges at CHSS School at Bharathidasan street in Div-182, U-38, Z-13.",Own Sources,13,2019-20,2020-21 NP/2019-20/10204,Parks,Completed,NP-PERUNGUDI,183,9000,"Improvements Works for AGS Colony Park(ECR) in Dn-183,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/1077,Electrical,Completed,NP-PERUNGUDI,183,2769200,"Work:Maintenance work in various parks in division-183,184,185,186, Unit-41, Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/13116,Road Cut,Completed,NP-PERUNGUDI,183,670000,"STRENGTHENING AND LAYING OF BT ROAD at RAJIV STREET IN DN-183, UNIT-41, ZONE-14",Own Sources,14,2019-20,2020-21 NP/2019-20/15561,Roads,Completed,NP-PERUNGUDI,183,807000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHRU NAGAR 2nd CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15562,Roads,Completed,NP-PERUNGUDI,183,684000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHRU NAGAR 1st LINK STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15563,Roads,Completed,NP-PERUNGUDI,183,1349000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHURU NAGAR 2nd LINK STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15564,Roads,Completed,NP-PERUNGUDI,183,1549000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHURU NAGAR 3rd LINK STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15565,Roads,Completed,NP-PERUNGUDI,183,213000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHURU NAGAR 7th LINK STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15566,Roads,Completed,NP-PERUNGUDI,183,243000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHURU NAGAR 8th LINK STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15574,Roads,Completed,NP-PERUNGUDI,183,916000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHRU NAGAR 11th LINK STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15585,Roads,Completed,NP-PERUNGUDI,183,1439000,"IMPROVEMENTS TO THE EXISTING B.T ROAD COOLD MILLING AND RELAYING AT NEHRU NAGAR 1ST CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15615,Roads,Completed,NP-PERUNGUDI,183,104000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT KALATHUMEDU STREET (DR. AMBEDKAR CROSS STREET) IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15616,Roads,Completed,NP-PERUNGUDI,183,232000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT KALATHUMEDU 1ST CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15625,Roads,Completed,NP-PERUNGUDI,183,139000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT KALATHUMEDU 5TH CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15627,Roads,Completed,NP-PERUNGUDI,183,352000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHRU NAGAR 13TH LINK STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15631,Roads,Completed,NP-PERUNGUDI,183,168000,"IMPROVEMENTS TO THE EXISTING B.T ROAD CUT RESTORATION AT NEHRU NAGAR 3rd CROSS 2ND EXTN IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15637,Roads,Completed,NP-PERUNGUDI,183,781000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT SELVARAJ AVENUE IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15640,Roads,Completed,NP-PERUNGUDI,183,1404000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT SANGAM COLONY 1ST STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15641,Roads,Completed,NP-PERUNGUDI,183,312000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT SANGAM COLONY 1ST CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15642,Roads,Completed,NP-PERUNGUDI,183,312000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT SANGAM COLONY 2ND CROSS STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15647,Roads,Completed,NP-PERUNGUDI,183,64000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT VIVEKANADHAR 1ST STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15650,Roads,Completed,NP-PERUNGUDI,183,278000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT VIVEKANADHAR 4TH STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/15651,Roads,Completed,NP-PERUNGUDI,183,196000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT VIVEKANADHAR 5TH STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/4355,Roads,Completed,NP-PERUNGUDI,183,392000,"Proposed Construction of RCC Precast drain at Venkatesapuram Main Road in div-183,unit-41,zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/5118,Storm Water Drain,Completed,NP-PERUNGUDI,183,216600,"Providing Rain Water Structures at various locations in dn-183, Unit-41, Zone-14",Own Sources,14,2019-20,2020-21 NP/2019-20/5122,Storm Water Drain,Completed,NP-PERUNGUDI,183,143600,"Improvement work to RWH Structure at various palces in Dn-183, Unit 41, Zone-14",Own Sources,14,2019-20,2020-21 NP/2019-20/5128,Roads,Completed,NP-PERUNGUDI,183,739000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD CUT RESTORATION AT VENKATESAPURAM 6TH STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/6777,Roads,Completed,NP-PERUNGUDI,183,601000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD CUT RESTORATION AT SWAMINATHAN NAGAR 11TH STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2019-20,2021-22 NP/2019-20/6863,Storm Water Drain,Completed,NP-PERUNGUDI,183,279000,"Desilting for Storm Water Drains and Side Drains in Div-183,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6864,Storm Water Drain,Completed,NP-PERUNGUDI,183,644000,"Minor Repair Works for Storm Water Drains and Side Drains in Div-183,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/7028,Parks,Completed,NP-PERUNGUDI,183,603000,"Maintenance of Park at NATCO COLONY in Dn. 183, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8405,Roads,Completed,NP-PERUNGUDI,183,453000,"Attending the B.T Road Patch Work at Karpagambal Nagar,Lakshmana Perumal Nagar, Vengateshwara Nagar and Various Streets in Division-183,Unit-41,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8626,Storm Water Drain,Completed,NP-PERUNGUDI,183,12000,"Improvements Works for Storm Water Drain at Sriram Avenue 2nd Street in Dn-183,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/8627,Roads,Completed,NP-PERUNGUDI,183,399000,"Providing Rain Water Harvesting,Hume Pipe and Wet Mix at Various Places for Dn-183,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/8633,Buildings,Completed,NP-PERUNGUDI,183,79000,"Improvements Works for Amma Unavagam and Other Maintenance Works in Dn-183,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/4812,Buildings,Completed,NP-PERUNGUDI,184,222000,"Providing of RWH Works in GCC Buildings at Various Locations in Dn184,Unit-41,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4935,Storm Water Drain,Completed,NP-PERUNGUDI,184,338000,"Desilting for Side Drain and Storm Water Drains at various street in Dn -184, Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6861,Storm Water Drain,Completed,NP-PERUNGUDI,184,465000,"Minor Repair works for Side Drain and Storm Water Drains at various street in Dn -184, Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/7030,Parks,Completed,NP-PERUNGUDI,184,872000,"Maintenance of Park at THIRUVALLUVAR STREET in Dn. 184, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7032,Parks,Completed,NP-PERUNGUDI,184,635000,"Maintenance of Park at RAMAPPA NAGAR 1ST CROSS STREET in Dn. 184, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7034,Parks,Completed,NP-PERUNGUDI,184,638000,"Maintenance of Park at ANNA NEDUNCHALAI in Dn. 184, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7039,Parks,Completed,NP-PERUNGUDI,184,1166000,"Maintenance of Park at CBI CIOLONY 2ND MAIN ROAD in Dn. 184, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7043,Parks,Completed,NP-PERUNGUDI,184,1236000,"Maintenance of Park at TELEPHONE NAGAR 2ND CROSS STREET in Dn. 184, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7045,Parks,Completed,NP-PERUNGUDI,184,1163000,"Maintenance of Park at Anna Nedunsalai Ferrai House park in Dn. 184, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7048,Parks,Completed,NP-PERUNGUDI,184,267000,"Maintenance of Park at Anna Nedunsalai twin court park in Dn. 184, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8067,Roads,Completed,NP-PERUNGUDI,184,222000,"Providing Wetmix and Quarry Rubbish at Anna Nedunchalai and Karpagavinayagar Koil Street in Div-184,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/8407,Roads,Completed,NP-PERUNGUDI,184,460000,"Attending the B.T Road Patch Work at Kodhandaraman Nagar Main Road, Telephone Nagar 1st Main Road, Nethaji nagar Main Road and Various Streets in Division-184,Unit-41,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/9833,Buildings,Completed,NP-PERUNGUDI,184,238000,"DISMANTLING PRESSED TILES ,ARRESTING WATER PROOFING WORKS AND RELAYING PRESSED TILES AT MGR SALAI AMMA UNAVAGAM IN DIV-184,UNIT-41,ZONE-14",Own Sources,14,2019-20,2021-22 NP/2019-20/10021,Storm Water Drain,Completed,NP-PERUNGUDI,185,778000,"Improvements to the Existing Culvert at Mahathma Gandhi Street, Mahathma Gandhi 1st Street, Kolavizhiamman Nagar 5th Street,6th Street, 8th Street and Kamarajar Salai in Dn-185,Unit-41, Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/10121,Buildings,Completed,NP-PERUNGUDI,185,26000,"REPAIRS TO THE UPHC BUILDING AND OTHER WORKS IN DIV-185,UNIT-42,ZONE-14",Own Sources,14,2019-20,2020-21 NP/2019-20/10122,Buildings,Completed,NP-PERUNGUDI,185,67000,"REPAIRS AND IMPROVEMENTS TO ROAD WORK AT VEERAMANI SALAI AND KOLAVIZHI AMMAN KOIL 11TH STREET IN DIV-185, UNIT-41,ZONE-14",Own Sources,14,2019-20,2020-21 NP/2019-20/10829,Buildings,Completed,B-Buildings,185,748000,"Improvement Works with Electrical Arrangements for Palavakkam UPHC in Division-185,Unit-41,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/10874,Storm Water Drain,Completed,NP-PERUNGUDI,185,541000,"Improvements to the Existing Culvert Rising at Govindhan Nagar 1st Cross 1st Street and 2nd Street,Govindhan Nagar 2nd Street and 3rd Street in Dn-185,Unit-41,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/10918,Buildings,Completed,NP-PERUNGUDI,185,180000,"Providing Barricading Arrangement ,Watch Tower and Mobile Toilet for Pongal Holiday at Palavakkam Beach in Dn 185, Unit 41 ,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/1846,Parks,Completed,NP-PERUNGUDI,185,586000,"Supply and Fixing of Well Rings for composting purposes at Various Places in Dn-183, 184,185 and 186 Unit-41,zone",Own Sources,14,2019-20,2019-20 NP/2019-20/1874,Parks,Completed,NP-PERUNGUDI,185,99000,"Providing Mulch Pit for Dry Waste Composting Purpose inside the Parks at Variuos Location in Dn-184, 185 and 186 Unit-41,zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/3241,Roads,Completed,NP-PERUNGUDI,185,532000,"Improvements to side drain at Dr.Ambedkar street in div-185,unit-41,zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/3787,Buildings,Completed,NP-PERUNGUDI,185,296000,"Providing Trash Arrester for ISWD Disposal Point at various location in DN-183, 184, 185 & 186 Unit - 41, Z-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4209,Storm Water Drain,Completed,NP-PERUNGUDI,185,1626000,"Improvement work to side drain at Govindha nagar 1st st,2nd st,3rd st,4th st,and 5th streer in Dn-185,Unit-41,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/5129,Storm Water Drain,Completed,NP-PERUNGUDI,185,225100,"Providing Rain water harvesting structures at various locations in Dn-185, Unit-41, Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/5131,Storm Water Drain,Completed,NP-PERUNGUDI,185,179700,"Improvement works to RWH structures at various locations in Dn-185, Unit-41, Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6319,Buildings,Completed,NP-PERUNGUDI,185,790000,"Providing Track and Trolly Barricading Arrangement and Mobile Toilet Arrangement at Palavakkam Beach in Div-185,Unit-41, Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6865,Storm Water Drain,Completed,NP-PERUNGUDI,185,640000,"Desilting for Storm Water Drain and Side Drains at Various Street in Div-185,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6866,Storm Water Drain,Completed,NP-PERUNGUDI,185,565000,"Minor Repair Works for Storm Water Drains and Side Drains at Various Streets in Div-185,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/7050,Parks,Completed,NP-PERUNGUDI,185,1117000,"Maintenance of Park at VGP LAYOUT 4TH MAIN ROAD in Dn. 185, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7052,Parks,Completed,NP-PERUNGUDI,185,843000,"Maintenance of Park at PALAVAKKA ECR (AMARA) PARK in Dn. 185, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7556,Buildings,Completed,NP-PERUNGUDI,185,114000,"SUPPLYING AND LAYING 300MM DIA HUME PIPE AT PACHAYAPPA STREET AND OTHER REPAIR WORKS IN DIV-185, UNIT-41, ZONE-14",Own Sources,14,2019-20,2020-21 NP/2019-20/8408,Roads,Completed,NP-PERUNGUDI,185,456000,"Attending the B.T Road Patch Work at Govindhan nagar,Maniammai street, Veeramani salai main road and Various Streets in Division-185,Unit-41,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/9836,Roads,Completed,NP-PERUNGUDI,185,293000,"ATTENDING WMM PATCH WORKS AT PERIYAR SALAI,KAMARAJAR SALAI,MANIYAMMAI STREET, GOVINDAN NAGARMAIN ROAD IN DIV-185, UNIT-41, ZONE-14",Own Sources,14,2019-20,2020-21 BR/2019-20/11162,Road Cut,Completed,BR-Bus Route Roads,186,685000,"RESTORATION OF OFC ROAD CUT IN VARIOUS LOCATIONS AT DIVISION -186, ZONE-14. DEPOSIT CODE-57/0509/2018-19",Deposit Works,14,2019-20,2020-21 L/2019-20/9188,Electrical,Completed,L-Electrical,186,199800,"Provision of Re-wiring in main building,weighbridges and security room at Perungudi dumping ground,div 186,zone14",Own Sources,14,2019-20,2020-21 NP/2019-20/1298,Parks,Completed,NP-PERUNGUDI,186,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN COMPOST YARD AT INDUSTRIAL ESTATE IN DN-186,UNIT-42,ZONE-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/1299,Parks,Completed,NP-PERUNGUDI,186,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN COMPOST YARD AT VEERAPANDIYA KATTABOMMNAN STREET IN DN-186,UNIT-41,ZONE-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/1968,Buildings,Completed,NP-PERUNGUDI,186,1166000,"Improvements for Compost yard at Estate 4th main road in Dn-186, Unit-41, Zone -14",Own Sources,14,2019-20,2019-20 NP/2019-20/1975,Buildings,Completed,NP-PERUNGUDI,186,1263000,"Improvements for Compost yard at Veerapandiya kattapomman street in Dn-186, Unit-41, Zone -14",Own Sources,14,2019-20,2019-20 NP/2019-20/4825,Buildings,Completed,NP-PERUNGUDI,186,305000,"Providing of RWH Works in GCC Buildings at Various Locations in Dn186,Unit-41,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4938,Storm Water Drain,Completed,NP-PERUNGUDI,186,268000,"Minor Repair works for Side Drain and Storm Water Drains at various street in Dn -186, Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6421,Buildings,Completed,NP-PERUNGUDI,186,363000,"Improvement works to Community Well at Panchayat Main Road in Div-186,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6862,Storm Water Drain,Completed,NP-PERUNGUDI,186,394000,"Desilting for Side Drain and Storm Water Drains at various street in Dn -186, Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/7065,Parks,Completed,NP-PERUNGUDI,186,650000,"Maintenance of Park at VENGATESWARA NAGAR PARK in Dn. 186, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7067,Parks,Completed,NP-PERUNGUDI,186,261000,"Maintenance of Park at OMATHURAI PARK in Dn. 186, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7073,Parks,Completed,NP-PERUNGUDI,186,1091000,"Maintenance of Park at THIRUMALAI NAGAR 1ST MAIN ROAD in Dn. 186, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7076,Parks,Completed,NP-PERUNGUDI,186,912000,"Maintenance of Park at RAJIV NAGAR in Dn. 186, Unit 41, Zone 14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8350,Roads,Completed,NP-PERUNGUDI,186,499000,"Attending Patch Work at Various Streets and Repairs and Improvements to Compost Yard at Estate 4th Main Road in Div-186,Unit-41,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/8410,Roads,Completed,NP-PERUNGUDI,186,457000,"Attending the B.T Road Patch Work at Thirumalai Nagar Anexe 1st Main Road,2nd Main Road,Panchayat Main Road, Senthil Nagar Main Road and Various Streets in Division-186,Unit-41,Zone-14.",Own Sources,14,2019-20,2020-21 Q/2019-20/11069,Buildings,Completed,Q-Solid Waste Management,186,6030000,"Construction of Shed for the installation and processing of Garden waste and tender Coconut shell at Perungudi Dumping ground in Division-189, Zone-14",Own Sources,14,2019-20,2020-21 Q/2019-20/11070,Buildings,Completed,Q-Solid Waste Management,186,3580000,"Providing Concrete pavement for installation ad processing of Garden Waste and Tender Coconut Shell at Perungudi Dumping ground in Division-186, Zone -14",Own Sources,14,2019-20,2020-21 NP/2019-20/10214,Buildings,Completed,NP-PERUNGUDI,187,495000,"Maintanance and Repair work at various location at Div-187,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/4832,Parks,Completed,NP-PERUNGUDI,187,87000,"Providing of RWH Works in GCC Buildings at Various Locations in Dn187,Unit-42,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4939,Storm Water Drain,Completed,NP-PERUNGUDI,187,203000,"Minor Repair works for Side Drain and Storm Water Drains at various street in Dn -187, Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/4978,Buildings,Completed,NP-PERUNGUDI,187,474000,"Improvement works to Community Well at Lakeview main road in Div-187,U-42,Z-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6860,Storm Water Drain,Completed,NP-PERUNGUDI,187,237000,"Desilting for Side Drain and Storm Water Drains at various street in Dn -187, Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/7055,Parks,Completed,NP-PERUNGUDI,187,238000,"Maintenance of Park at PARK SQUARE COLONY PARK in Dn. 187, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7057,Parks,Completed,NP-PERUNGUDI,187,594000,"Maintenance of Park at KARHTIKEYAPURAM 6TH STREET in Dn. 187, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7058,Parks,Completed,NP-PERUNGUDI,187,604000,"Maintenance of Park at MAHATMA GANTHI PARK in Dn. 187, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/8411,Roads,Completed,NP-PERUNGUDI,187,363000,"ATTENDING THE B.T ROAD PATCH WORK AT VARIOUS STREETS IN DIV - 187, UNIT - 42, ZONE - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/8848,Road Cut,Completed,NP-PERUNGUDI,187,2207000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT AYYAPPA NAGAR 10TH STREET, AYYAPPA NAGAR 11TH STREET, AYYAPPA NAGAR 12TH STREET, AYYAPPA NAGAR 13TH STREET, AYYAPPA NAGAR 14TH STREET, AYYAPPA NAGAR 1ST STREET, AYYAPPA NAGAR 2ND STREET, AYYAPPA NAGAR 3RD STREET, AYYAPPA NAGAR 4TH STREET, AYYAPPA NAGAR 5TH STREET, AYYAPPA NAGAR 6TH STREET, AYYAPPA NAGAR 7TH STREET AND VARIOUS STREETS IN DN-187, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8849,Road Cut,Completed,NP-PERUNGUDI,187,2279000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT AYYAPPA NAGAR 8TH STREET, AYYAPPA NAGAR 9TH STREET, AYYAPPA NAGAR SANNATHI STREET, DEIVANAI NAGAR 3RD STREET, KARTHIKEYAPURAM 10TH STREET, KARTHIKEYAPURAM 11TH STREET, KARTHIKEYAPURAM 11TH 3RD CROSS STREET, KARTHIKEYAPURAM 12TH STREET, KARTHIKEYAPURAM 13TH CROSS STREET, KARTHIKEYAPURAM 3RD, 1ST CROSS STREET, KARTHIKEYAPURAM 3RD, 2ND CROSS STREET, KARTHIKEYAPURAM 3RD, 3RD CROSS STREET AND VARIOUS STREETS IN DN-187, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8850,Road Cut,Completed,NP-PERUNGUDI,187,2244000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KARTHIKEYAPURAM 13TH STREET, KARTHIKEYAPURAM 2ND CROSS STREET, KARTHIKEYAPURAM 3RD STREET, KARTHIKEYAPURAM 9TH STREET AND VARIOUS STREETS IN DN-187, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8851,Road Cut,Completed,NP-PERUNGUDI,187,2229000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KARTHIKEYAPURAM 3RD, 4TH CROSS STREET, KARTHIKEYAPURAM 4TH STREET, KARTHIKEYAPURAM 5TH STREET, KARTHIKEYAPURAM 6TH STREET, KARTHIKEYAPURAM 7TH STREET AND VARIOUS STREETS IN DN-187, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8852,Road Cut,Completed,NP-PERUNGUDI,187,472000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT LAKEVIEW MAIN ROAD, LAKEVIEW MAIN ROAD EXTN AND VARIOUS STREETS. IN DN-187, U-42, Z-14",Deposit Works,14,2019-20,2020-21 L/2019-20/8187,Electrical,Completed,L-Electrical,188,1751200,"Supply and erection of 27 nos of 6mtr Hot Dip Lamp Post with Single Straight Bracket, 2 nos of 6mtr Hot Dip Lamp Post with Single Arch Bracket with 90 - 120 W LED fitting at Various Places in division-183,184,185,186 and 188 Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/10472,Roads,Completed,NP-PERUNGUDI,188,1581000,"Providing 600MM Hume pipe at Ram nagar 17th street, Ram nagar 13th street,Anna nagar 4th street and Thirumurugan street, Stagnation water removed used for tracter motor, Trench work, Proclain work and sucker lorry in Div - 188, U - 42, Z - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/1191,Buildings,Completed,NP-PERUNGUDI,188,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN COMPOST YARD AT TAMBARAM VELACHERY MAIN ROAD IN DN-187 AND DN-188,UNIT-42,ZONE-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/1291,Parks,Completed,NP-PERUNGUDI,188,122000,"Providing Mulch Pit for Dry Waste Composting Purpose inside the Parks at Variuos Location in Dn-168, 168,187 and 188 Unit-42,zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/2330,Buildings,Completed,NP-PERUNGUDI,188,1230000,"Improvements works for East side Compost yard at Old Dumping Ground in dn-188,unit-42,zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/3268,Buildings,Completed,NP-PERUNGUDI,188,399000,"Construction of Shed for segragating decomposing and non decomposing materials at Old Dumping Yard in Dn 188, Uit 42 Zone 14",Own Sources,14,2019-20,2019-20 NP/2019-20/3493,Storm Water Drain,Completed,NP-PERUNGUDI,188,732000,"Providing Trash Arrester for SWD, CANAL & VEERANGAL ODAI Disposal Point at various location in DN-168,169,187 & 188, Unit - 42, Z-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4667,Roads,Completed,NP-PERUNGUDI,188,1012000,"Forming and laying of WMM Road with Compost yard Left side, Right side and centre at Old Dumping Ground in DN-188, U-42, Z-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4739,Roads,Completed,NP-PERUNGUDI,188,910000,"Forming and laying of WMM Road with Compost yard front side and Trees arrangements at Old Dumping Ground in DN-188, U-42, Z-14",Own Sources,14,2019-20,2019-20 NP/2019-20/4837,Buildings,Completed,NP-PERUNGUDI,188,409000,"Providing of RWH Works in GCC Buildings at Various Locations in Dn188,Unit-42,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6330,Buildings,Completed,NP-PERUNGUDI,188,476000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete at Division 188 Compost yard, Old Dumpping Ground in Div - 188, Unit - 42, Zone - 14",Own Sources,14,2019-20,2019-20 NP/2019-20/6867,Storm Water Drain,Completed,NP-PERUNGUDI,188,829000,"Minor Repair Works for Storm Water Drains and Side Drains at Various Streets in Div-188,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6868,Storm Water Drain,Completed,NP-PERUNGUDI,188,616000,"Desilting Works for Storm Water Drains and Side Drains at Various Streets in Div-188,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6869,Storm Water Drain,Completed,NP-PERUNGUDI,188,668000,"Desilting Works for Storm Water Drains and Side Drains at Various Streets in Div-188,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6870,Storm Water Drain,Completed,NP-PERUNGUDI,188,775000,"Minor Repair Works for Storm Water Drains and Side Drains at Various Streets in Div-188,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/7042,Parks,Completed,NP-PERUNGUDI,188,639000,"Maintenance of Park at RAJALAKSHMI NAGAR in Dn. 188, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7044,Parks,Completed,NP-PERUNGUDI,188,238000,"Maintenance of Park at ANNA NAGAR 5TH MAIN ROAD in Dn. 188, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7047,Parks,Completed,NP-PERUNGUDI,188,645000,"Maintenance of Park at DR RAMAMOORTHY NAGAR PARK in Dn. 188, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/7051,Parks,Completed,NP-PERUNGUDI,188,578000,"Maintenance of Park at RAJESH NAGAR in Dn. 188, Unit 42, Zone 14",Own Sources,14,2019-20,2020-21 NP/2019-20/8402,Buildings,Completed,NP-PERUNGUDI,188,867000,"Construction of septic tank with chambers, bailing machine shed work, with additional cable laying works in Bailing Machine and other works at Compost Yard in Div-188,Unit-42,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8406,Roads,Completed,NP-PERUNGUDI,188,541000,"Providing 300MM dia hume pipe at Rajesh nagar 3rd street, Srinagar 5th street, Govindasamy nagar 4th street, sadasivam nagar 5th street, Srinagar 2nd street and Sadasivam nagar 4th cross street; 600MM dia hume pipe at Govindasamy nagar 6th street, Kuberan nagar main road, New kuberan nagar 4th street and Govindasamy nagar 8th street; 1.0M dia hume pipe at Ram nagar 8th cross street Doshi Flot and Compost yard back side in Div - 188, U - 42, Z - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/8409,Roads,Completed,NP-PERUNGUDI,188,1028000,"ATTENDING THE B.T ROAD PATCH WORK AT VARIOUS STREETS IN DIV - 188, UNIT - 42, ZONE -14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8819,Road Cut,Completed,NP-PERUNGUDI,188,2281000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT RAM NAGAR SOUTH 4TH STREET, RAM NAGAR 16TH MAIN ROAD, RAM NAGAR SOUTH 18TH MAIN ROAD, RAM NAGAR SOUTH 11TH MAIN ROAD, PERIYAR NAGAR EXTN. 2ND STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8820,Road Cut,Completed,NP-PERUNGUDI,188,1822000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KUBERA NAGAR 7TH STREET, KUBERA NAGAR 8TH STREET LAKSHMI NAGAR 2ND STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8821,Road Cut,Completed,NP-PERUNGUDI,188,1975000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KUBERA NAGA 9TH STREET, KUBERA NAGAR 10TH STREET LIC NAGAR 5TH CROSS STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8823,Road Cut,Completed,NP-PERUNGUDI,188,1609000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KUBERA NAGAR 14TH STREET, KUBERA NAGAR 15TH STREET LIC NAGAR 1ST STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8824,Road Cut,Completed,NP-PERUNGUDI,188,1920000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT LIC NAGAR 2ND STREET, LIC NAGAR 3RD STREET, LIC NAGAR 1ST CROSS STREET PERIYAR NAGAR EXT. 2ND STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8825,Road Cut,Completed,NP-PERUNGUDI,188,1925000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT LIC NAGAR 4TH STREET, LIC NAGAR EXTN. 4TH STREET, LIC NAGAR 2ND CROSS STREET, PERIYAR NAGAR 7TH STREET, PERIYAR NAGAR EXTN. I 4TH STREET, PERIYAR NAGAR EXTN. I 5TH STREET, PERIYAR NAGAR EXTN. II 3RD STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8826,Road Cut,Completed,NP-PERUNGUDI,188,2295000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT PERIYAR NAGAR EXTN. II 5TH STREET, PERIYAR NAGAR EXTN. 7TH STREET & ENFIELD AVENUE, PERIYAR NAGAR VEERAMANI STREET, PERIYAR NAGAR BHARATHIDASAN STREET LAKSHMI NAGAR 1ST STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8827,Road Cut,Completed,NP-PERUNGUDI,188,2155000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT PERIYAR NAGAR EXTN. II 6TH STREET, LAXMI NAGAR 3RD STREET, LAXMI NAGAR 4TH STREET, LAXMI NAGAR 5TH STREET, LAXMI NAGAR 6TH STREET, LAXMI NAGAR 7TH STREET, LAXMI NAGAR 8TH STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8828,Road Cut,Completed,NP-PERUNGUDI,188,2165000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT LAXMI NAGAR MAIN ROAD, ALAYAMMAN NAGAR MAIN ROAD, ALAYAMMAN NAGAR 1ST STREET, ALAYAMMAN NAGAR 2ND STREET DR.AMBEDKAR SALAI AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8829,Road Cut,Completed,NP-PERUNGUDI,188,1345000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT DR.AMBEDKAR SALAI, AMBEDKAR SALAI 1ST CROSS STREET, AMBEDKAR SALAI 2ND CROSS STREET, KANCHI KAMATCHI NAGAR 1ST STREET, KANCHI KAMATCHI NAGAR 2ND STREET, KANCHI KAMATCHI NAGAR 3RD STREET, SIGAMANI NAGAR 1ST STREET, SIGAMANI NAGAR 2ND STREET, SIGAMANI NAGAR 3RD STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8830,Road Cut,Completed,NP-PERUNGUDI,188,2014000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KUBERA NAGAR EXT. 5TH STREET, KUBERA NAGAR EXTN. 6TH STREET RAMACHANDRA SALAI AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8831,Road Cut,Completed,NP-PERUNGUDI,188,1817000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KUBERA NAGAR EXTN. 3RD STREET KUBERA NAGAR EXTN. 2ND STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8832,Road Cut,Completed,NP-PERUNGUDI,188,2202000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KUBERA NAGAR EXTN. 1ST STREET, GOVINDASAMY NAGAR 1ST STREET, GOVINDASAMY NAGAR 2ND STREET, RAJAJI NAGAR 1ST CROSS STREET, RAJAJI NAGAR 3RD STREET, RAJAJI NAGAR 2ND STREET, RAJAJI NAGAR 1ST STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8833,Road Cut,Completed,NP-PERUNGUDI,188,2197000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT RAJAJI NAGAR 2ND CROSS STREET, RAJAJI NAGAR MAIN ROAD, SADASIVAM NAGAR 4TH CROSS STREET, VAIGAI STREET, KAVERI STREET, VENKATESAN STREET, PERIYAR NAGAR VEERAMANI STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8834,Road Cut,Completed,NP-PERUNGUDI,188,2207000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KARPAGAMBAL NAGAR 1ST CROSS STREET, UNMAI NAGAR MAIN ROAD, KRISHNAVENI AMMAL STREET, SARATHI NAGAR, ANNA NAGAR 7TH STREET, ANNA NAGAR 6TH STREET, ANNA NAGAR 2ND STREET, ANNA NAGAR 4TH STREET, ANNA NAGAR 3RD STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8835,Road Cut,Completed,NP-PERUNGUDI,188,2159000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT PONNIAMMAN STREET, ANNA NAGAR 1ST STREET, MAHALAKSHMI NAGAR MAIN ROAD, MAHALAKSHMI NAGAR 8TH STREET, MAHALAKSHMI NAGAR 6TH STREET, MAHALAKSHMI NAGAR EXTN. 5TH STREET, MAHALAKSHMI NAGAR BHARATHIAR STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8836,Road Cut,Completed,NP-PERUNGUDI,188,2227000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT MAHALAKSHMI NAGAR EXTN. 2ND STREET, MAHALAKSHMI NAGAR 5TH EXT. 1ST CROSS STREET, MAHALAKSHMI NAGAR EXT. 3RD STREET, ANNA NAGAR 9TH STREET, ANNA NAGAR 10TH STREET, LAKSHMI STREET, TENDULKAR STREET, ANNA NAGAR 11TH STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8837,Road Cut,Completed,NP-PERUNGUDI,188,2244000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT MAHALAKSHMI NAGAR 7TH STREET, MAHALAKSHMI NAGAR EXTN. 4TH STREET, ANNA NAGAR EXT. AAVIN GARDEN, SENTHIL NAGAR MAIN ROAD, SENTHIL NAGAR 3RD STREET, SENTHIL NAGAR 2ND STREET, ARULMURUGAN NAGAR 4TH STREET, SENTHIL NAGAR 1ST STREET, ARULMURUGAN NAGAR 3RD STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8838,Road Cut,Completed,NP-PERUNGUDI,188,1918000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT MURTHY STREET (EAST BAJANAI KOVIL STREET, SADASIVAM NAGAR 6TH MAIN ROAD, SADASIVAM NAGAR 4TH MAIN ROAD AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8839,Road Cut,Completed,NP-PERUNGUDI,188,2157000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KALEESWARAR NAGAR 2ND STREET, AMBEDKAR SALAI, ANNA NAGAR MAIN ROAD, PERUMAL NAGAR MAIN ROAD, PERUMAL NAGAR, BAJANAI KOVIL STREET, KRISHNA COLONY AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8841,Road Cut,Completed,NP-PERUNGUDI,188,2287000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT MAHALSKHMI NAGAR EXT. 3RD STREET, MAHALAKSHMI NAGAR 2ND STREET & 4TH STREET, MAHALAKSHMI NAGAR 4TH STREET, MAHALAKSHMI NAGAR 5TH STREET, KRISHNA NAGAR 3RD STREET, KRISHNA NAGAR 4TH STREET, KRISHNA NAGAR 5TH STREET, KRISHNA NAGAR MAIN ROAD AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8842,Road Cut,Completed,NP-PERUNGUDI,188,2246000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KRISHNAMOORTHI NAGAR, KRISHNA NAGAR 1ST STREET, KRISHNA NAGAR 2ND STREET, RAJALAKSHMI NAGAR 1ST CROSS STREET, RAJALAKSHMI NAGAR 1ST MAIN ROAD, RAJALAKSHMI NAGAR 2ND CROSS STREET, RAJALAKSHMI NAGAR 2ND MAIN ROAD, RAJALAKSHMI NAGAR 3RD MAIN ROAD, RAJALAKSHMI NAGAR 4TH CROSS STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8843,Road Cut,Completed,NP-PERUNGUDI,188,2278000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT RAJALAKSHMI NAGAR 4TH MAIN ROAD, RAJARAJESWARI NAGAR 1ST MAIN ROAD, RAJARAJESWARI NAGAR 3RD CROSS STREET, RAJARAJESWARI NAGAR 4TH CROSS STREET, RAJARAJESWARI NAGAR 4TH STREET, RAJARAJESWARI NAGAR 5TH STREET, RAJARAJESWARI NAGAR 6TH STREET, RAJARAJESWARI AVENUE AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8844,Road Cut,Completed,NP-PERUNGUDI,188,2157000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT RAJARAJESWARI NAGAR, RAJARAJESWARI NAGAR 1ST STREET, RAJARAJESWARI NAGAR 2ND STREET, RAJARAJESWARI NAGAR 3RD STREET, RAJARAJESWARI NAGAR 7TH STREET, VISHAL NAGAR, SETHUPATHI NAGAR MAIN ROAD, KUBERA NAGAR 2ND CROSS STREET, GOVINDASAMY NAGAR 5TH STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8845,Road Cut,Completed,NP-PERUNGUDI,188,2243000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT KUBERA NAGAR EXT. 4TH STREET, KARPAGAMBAL NAGAR, KARPAGAMBAL NAGAR 15TH STREET, SIVA VISHNU KOVIL STREET, THILAKAR AVENUE 11TH CROSS STREET, SAIRAM AVENUE 1ST STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8846,Road Cut,Completed,NP-PERUNGUDI,188,2267000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT SADASIVAM NAGAR 3RD MAIN ROAD, MANNADIAMMAN KOVIL STREET, GOVINDASAMY NAGAR 8TH STREET, GOVINDASAMY NAGAR 9TH STREET, GOVINDASAMY NAGAR 3RD STREET, GOVINDASAMY NAGAR 4TH CROSS STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2021-22 NP/2019-20/8847,Road Cut,Completed,NP-PERUNGUDI,188,1491000,"RESTORATION OF METRO WATER (CMWSSB) ROAD CUT PORTION AT GOVINDASAMY NAGAR 7TH STREET, GOVINDASAMY NAGAR 1ST CROSS STREET, GOVINDASAMY NAGAR 2ND CROSS STREET, GOVINDASAMY NAGAR 3RD CROSS STREET, GOVINDASAMY NAGAR 10TH STREET, GOVINDASAMY NAGAR 11TH STREET, GOVINDASAMY NAGAR 11TH CROSS STREET, THANTHAI PERIYAR NAGAR JAYALALITHA STREET, THANTHAI PERIYAR NAGAR ELANGO STREET AND VARIOUS STREETS IN DN-188, U-42, Z-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/8960,Buildings,Completed,NP-PERUNGUDI,188,89000,"Improvement works to Community Well at Kaniamman Koil Street in Div-188,U-42,Z-14",Own Sources,14,2019-20,2020-21 NP/2019-20/8995,Roads,Completed,NP-PERUNGUDI,188,401000,"IMPROVEMENT ROAD AT GANDHI STREET, NEHRU STREET, RAJESH NAGAR 1ST MAIN ROAD AND VGP RAJESH NAGAR IN DIV-188, U-42, Z-14",Own Sources,14,2019-20,2021-22 NP/2019-20/8996,Buildings,Completed,NP-PERUNGUDI,188,494000,"Maintenance work at various location at Div-188,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 BR/2019-20/10667,Road Cut,Completed,BR-Bus Route Roads,189,970000,"Restoration of Roadcut made by OFC Operators at Various Roads (Interior Roads) in Dn-189, Zone- 14",Deposit Works,14,2019-20,2019-20 BR/2019-20/10811,Road Cut,Completed,BR-Bus Route Roads,189,970000,"Restoration of Roadcut made by OFC Operators at Various Roads (Interior Roads) in Dn-189, Zone- 14",Deposit Works,14,2019-20,2019-20 NP/2019-20/0788,Parks,Completed,NP-PERUNGUDI,189,609000,"Improvements Works With Greenary for Herbal Park at Tambaram Velachery Main Road in Dn-189,Unit-43,zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/10147,Buildings,Completed,NP-PERUNGUDI,189,78000,"Improvements Work at Parasuram Nagar Anganwadi and Malligeswaran Nagar Resource Recovery Center in Dn-189,Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/10148,Roads,Completed,NP-PERUNGUDI,189,145000,"Providing WMM and Laying for Hume pipe at Sai Balaji Nagar,Om Sakthi Nagar,Manogar Nagar 12th Cross street and Various Street in Dn -189, U-43,Z-14",Own Sources,14,2019-20,2019-20 NP/2019-20/1169,Buildings,Completed,NP-PERUNGUDI,189,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN COMPOST YARD AT MALLIGESHWARAN NAGAR IN DN-189,UNIT-43,ZONE-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/11692,Roads,Completed,NP-PERUNGUDI,189,923000,"Relaying of BT Road at Labour colony 2nd street in Dn-189,Unit-43,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/11701,Roads,Completed,NP-PERUNGUDI,189,552000,"Formation of BT Road at Sai Balaji Nagar Part-V in Dn-189,Unit-43,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/11703,Roads,Completed,NP-PERUNGUDI,189,1342000,"Relaying of BT Road at Labour Colony Main Road in Dn-189,Unit-43,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/14891,Roads,Completed,NP-PERUNGUDI,189,1150000,"Strengthening and Relaying of BT road at VGP Shanthi nagar V.O.C.street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14892,Roads,Completed,NP-PERUNGUDI,189,1212000,"Strengthening and Relaying of BT road at Ambethkar Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14893,Roads,Completed,NP-PERUNGUDI,189,1177000,"Strengthening and Relaying of BT road at Ambedkar cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14894,Roads,Completed,NP-PERUNGUDI,189,118000,"Partly relaying of BT road at Rajalakshmi nagar main road Extn in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14895,Roads,Completed,NP-PERUNGUDI,189,990000,"Strengthening and Relaying of BT road at Arun Nagar 1st Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14896,Roads,Completed,NP-PERUNGUDI,189,37000,"Partly relaying of BT Road at Thulukanathamman koil main road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14897,Roads,Completed,NP-PERUNGUDI,189,375000,"Strengthening and Relaying of BT road at Malligeshwaran nagar cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14898,Roads,Completed,NP-PERUNGUDI,189,31000,"Partly relaying of BT road at Kamakoti nagar 3rd main road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14899,Roads,Completed,NP-PERUNGUDI,189,705000,"Road cut and Relaying of BT road at Manogar Nagar Main Road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14901,Roads,Completed,NP-PERUNGUDI,189,758000,"Relaying of BT road at Mada Veethi street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14903,Roads,Completed,NP-PERUNGUDI,189,412000,"Relaying of BT road at Meru nagar 2nd cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14906,Roads,Completed,NP-PERUNGUDI,189,1930000,"Strengthening and Relaying of BT road at Sengazhani Amman Koil Main Roadin Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14907,Roads,Completed,NP-PERUNGUDI,189,456000,"Relaying of Bt road at Varadarajan Nagar 1st Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14908,Roads,Completed,NP-PERUNGUDI,189,909000,"Strengthening and Relaying of BT road at VGP Shanthi Nagar (Perumal Nagar Main road) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14910,Roads,Completed,NP-PERUNGUDI,189,529000,"Partly relaying of BT road at VGP Shanthi nagar Bharathi street(Part) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14912,Roads,Completed,NP-PERUNGUDI,189,968000,"Relaying of BT road at VGP Shanthi Nagar Main Road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14913,Roads,Completed,NP-PERUNGUDI,189,629000,"Partly relaying of BT road at VGP Shanthi nagar Vallalar street (Part) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14914,Roads,Completed,NP-PERUNGUDI,189,640000,"Road cut and Relaying of BT road at Adhisami Nagar Exten in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14922,Roads,Completed,NP-PERUNGUDI,189,380000,"Road cut and Relaying of BT road at Adisami Nagar 1st Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14923,Roads,Completed,NP-PERUNGUDI,189,300000,"Roadcut and Relaying of BT road at Adisami Nagar 2nd Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14924,Roads,Completed,NP-PERUNGUDI,189,600000,"Road cut and Relaying of BT road at Adisami Nagar Main Road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14925,Roads,Completed,NP-PERUNGUDI,189,482000,"Roadcut and Relaying of BT road at Agathiyar Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14930,Roads,Completed,NP-PERUNGUDI,189,188000,"Road cut and Relaying of BT road at Anna MGR Nagar Iyyappan 1st cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14931,Roads,Completed,NP-PERUNGUDI,189,128000,"Roadcut and Relaying of BT road at Anna MGR Nagar Iyyappan 2nd cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14932,Roads,Completed,NP-PERUNGUDI,189,128000,"Roadcut and Relaying of BT road at Anna MGR Nagar Iyyappan 3rd cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14933,Roads,Completed,NP-PERUNGUDI,189,200000,"Road cut and Relaying of BT road at Anna MGR Nagar Iyyappan 4th cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14934,Roads,Completed,NP-PERUNGUDI,189,184000,"Road cut and Relaying of BT road at Anna MGR Nagar Iyyappan 5th cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14937,Roads,Completed,NP-PERUNGUDI,189,620000,"Roadcut and Relaying of BT road at Anna MGR Nagar Nehru street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14938,Roads,Completed,NP-PERUNGUDI,189,896000,"Roadcut and Relaying of Bt road at Anna MGR Nagar NSK street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14948,Roads,Completed,NP-PERUNGUDI,189,228000,"Road cut and Relaying of BT road at Arumugam nagar 1st street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14949,Roads,Completed,NP-PERUNGUDI,189,480000,"Road cut and Relaying of BT road at Arun Nagar 1st Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14950,Roads,Completed,NP-PERUNGUDI,189,124000,"Road cut and Relaying of BT road at Arun Nagar 2nd Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14951,Roads,Completed,NP-PERUNGUDI,189,380000,"Road cut and Relaying of BT road at Arun Nagar 2nd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14952,Roads,Completed,NP-PERUNGUDI,189,232000,"Road cut and Relaying of BT road at Arun Nagar 3rd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14953,Roads,Completed,NP-PERUNGUDI,189,300000,"Road cut and Relaying of BT road at Ashtalakshmi Avenue 1st Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14954,Roads,Completed,NP-PERUNGUDI,189,369000,"Road cut and Relaying of BT road at Ashtalakshmi Avenue 2 nd street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14955,Roads,Completed,NP-PERUNGUDI,189,210000,"Road cut and Relaying of BT road at Ashtalakshmi Avenue 3rd street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14956,Roads,Completed,NP-PERUNGUDI,189,112000,"Road cut and Relaying of BT road at Ashtalakshmi Avenue 3rd Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14957,Roads,Completed,NP-PERUNGUDI,189,383000,"Road cut and Relaying of BT road at Ashtalakshmi Avenue I st street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14958,Roads,Completed,NP-PERUNGUDI,189,534000,"Road cut and Relaying of BT road at Ashtalakshmi Avenue Main road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14996,Roads,Completed,NP-PERUNGUDI,189,275000,"Road cut and Relaying of BT road at Church Avenue 3rd Main Road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14997,Roads,Completed,NP-PERUNGUDI,189,340000,"Road cut and Relaying of BT road at Dhanam Nagar 1st cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14998,Roads,Completed,NP-PERUNGUDI,189,348000,"Road cut and Relaying of BT road at Dhanam Nagar 2nd cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/14999,Roads,Completed,NP-PERUNGUDI,189,297000,"Road cut and Relaying of BT road at Dhanam Nagar Main Road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15001,Roads,Completed,NP-PERUNGUDI,189,580000,"Road cut and Relaying of BT road at I.I.T Colony - Rajaji avenue in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15002,Roads,Completed,NP-PERUNGUDI,189,806000,"Road cut and Relaying of BT road at I.I.T Colony 2nd cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15003,Roads,Completed,NP-PERUNGUDI,189,280000,"Road cut and Relaying of BT road at I.I.T Colony 2nd street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15004,Roads,Completed,NP-PERUNGUDI,189,216000,"Road cut and Relaying of BT road at I.I.T Colony 7th street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15005,Roads,Completed,NP-PERUNGUDI,189,145000,"Road cut and Relaying of BT road at I.I.T Colony 8th street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15006,Roads,Completed,NP-PERUNGUDI,189,580000,"Road cut and Relaying of BT road at Jayabal Nagar 1st street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15007,Roads,Completed,NP-PERUNGUDI,189,120000,"Road cut and Relaying of BT road at Jayabal Nagar 2nd stret in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15008,Roads,Completed,NP-PERUNGUDI,189,1209000,"Road cut and Relaying of BT road at Kamakotti nagar 10th street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15010,Roads,Completed,NP-PERUNGUDI,189,306000,"Road cut and Relaying of BT road at Kamakotti nagar 1st street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15011,Roads,Completed,NP-PERUNGUDI,189,289000,"Road cut and Relaying of BT road at Kamakotti nagar 2nd cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15013,Roads,Completed,NP-PERUNGUDI,189,446000,"Road cut and Relaying of BT road at Kamakotti nagar 2nd street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15014,Roads,Completed,NP-PERUNGUDI,189,195000,"Road cut and Relaying of BT road at Kamakotti nagar 4th cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15015,Roads,Completed,NP-PERUNGUDI,189,594000,"Road cut and Relaying of BT road at Kamakotti nagar 4th street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15016,Roads,Completed,NP-PERUNGUDI,189,195000,"Road cut and Relaying at Kamakotti nagar 4th street ext. in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15017,Roads,Completed,NP-PERUNGUDI,189,115000,"Road cut and Relaying at Kamakotti nagar 5th cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15018,Roads,Completed,NP-PERUNGUDI,189,1252000,"Road cut and Relaying of BT road at Kamakotti nagar 5th street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15019,Roads,Completed,NP-PERUNGUDI,189,683000,"Road cut and Relaying at Kamakotti nagar 6th cross street (north) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15020,Roads,Completed,NP-PERUNGUDI,189,416000,"Road cut and Relaying at Kamakotti nagar 7th cross street (north) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15021,Roads,Completed,NP-PERUNGUDI,189,407000,"Road cut and Relaying at Kamakotti nagar 7th cross street (south) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15022,Roads,Completed,NP-PERUNGUDI,189,352000,"Road cut and Relaying at Kamakotti nagar 9th cross street (north) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15023,Roads,Completed,NP-PERUNGUDI,189,384000,"Road cut and Relaying of BT road at Kamatchi Colony 1st Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15024,Roads,Completed,NP-PERUNGUDI,189,384000,"Road cut and Relaying at Kamatchi Colony 2nd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15033,Roads,Completed,NP-PERUNGUDI,189,384000,"Road cut and Relaying at Kamatchi Colony 3rd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15034,Roads,Completed,NP-PERUNGUDI,189,246000,"Road cut and Relaying at Kamatchi Colony cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15035,Roads,Completed,NP-PERUNGUDI,189,600000,"Road cut and at Relaying Kavimani 1st cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15036,Roads,Completed,NP-PERUNGUDI,189,564000,"Road cut and Relaying at Kavimani 1st Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15037,Roads,Completed,NP-PERUNGUDI,189,280000,"Road cut and Relaying at Kavimani 2nd Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15038,Roads,Completed,NP-PERUNGUDI,189,144000,"Road cut and Relaying at Kavimani 2nd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15041,Roads,Completed,NP-PERUNGUDI,189,280000,"Roadcut and Relaying at Kavimani 3rd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15042,Roads,Completed,NP-PERUNGUDI,189,600000,"Road cut and Relaying of BT road at Kavimani 4th cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15043,Roads,Completed,NP-PERUNGUDI,189,120000,"Road cut and Relaying at Kavimani 5th cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15044,Roads,Completed,NP-PERUNGUDI,189,160000,"Road cut and Relaying at Kavimani 6th cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15082,Roads,Completed,NP-PERUNGUDI,189,280000,"Road cut and Relaying at Kavimani cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15083,Roads,Completed,NP-PERUNGUDI,189,320000,"Road cut and Relaying at Krishna Nagar 1st cross St in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15085,Roads,Completed,NP-PERUNGUDI,189,332000,"Road cut and Relaying at Krishna Nagar 2nd cross St in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15177,Roads,Completed,NP-PERUNGUDI,189,625000,"Road cut and Relaying of BT road at Krishna Nagar Main Road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15208,Roads,Completed,NP-PERUNGUDI,189,282000,"Road cut and Relaying of BT road at Veerathamman kovil 1st Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15210,Roads,Completed,NP-PERUNGUDI,189,780000,"Road cut and Relaying of BT road at Malligeswaran Nagar 2nd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15211,Roads,Completed,NP-PERUNGUDI,189,820000,"Road cut and Relaying of BT road at Malligeswaran Nagar 3rd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15213,Roads,Completed,NP-PERUNGUDI,189,720000,"Road cut and Relaying of BT road at Malligeswaran Nagar 4th street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15214,Roads,Completed,NP-PERUNGUDI,189,640000,"Road cut and Relaying of BT road at Manimekalai 1st cross Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15215,Roads,Completed,NP-PERUNGUDI,189,540000,"Road cut and Relaying of BT road at Manimekalai 1st Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15216,Roads,Completed,NP-PERUNGUDI,189,380000,"Road cut and Relaying of BT road at Manimekalai 2nd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15217,Roads,Completed,NP-PERUNGUDI,189,380000,"Road cut and Relaying of BT road at Manimekalai main road in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15218,Roads,Completed,NP-PERUNGUDI,189,216000,"Road cut and Relaying of BT road at Manokar Nagar 10th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15219,Roads,Completed,NP-PERUNGUDI,189,1050371,"Road cut and Relaying of BT road at Manokar Nagar 11th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15220,Roads,Completed,NP-PERUNGUDI,189,380000,"Road cut and Relaying of BT road at Manokar Nagar 12th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15221,Roads,Completed,NP-PERUNGUDI,189,400000,"Road cut and Relaying of BT road at Manokar Nagar 13th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15222,Roads,Completed,NP-PERUNGUDI,189,332000,"Road cut and Relaying of BT road at Manokar Nagar 14th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15223,Roads,Completed,NP-PERUNGUDI,189,960000,"Road cut and Relaying of BT road at Manokar Nagar 17th Steeet in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15224,Roads,Completed,NP-PERUNGUDI,189,96000,"Road cut and Relaying of BT road at Manokar Nagar 18th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15225,Roads,Completed,NP-PERUNGUDI,189,672000,"Road cut and Relaying of BT road at Manokar Nagar 1st Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15226,Roads,Completed,NP-PERUNGUDI,189,440000,"Road cut and Relaying of BT road at Manokar Nagar 2nd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15227,Roads,Completed,NP-PERUNGUDI,189,360000,"Road cut and Relaying of BT road at Manokar Nagar 3rd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15228,Roads,Completed,NP-PERUNGUDI,189,1000000,"Road cut and Relaying of BT road at Manokar Nagar 4th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15229,Roads,Completed,NP-PERUNGUDI,189,658000,"Road cut and Relaying of BT road at Manokar Nagar 5th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15230,Roads,Completed,NP-PERUNGUDI,189,286000,"Road cut and Relaying of BT road at Manokar Nagar 6th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15231,Roads,Completed,NP-PERUNGUDI,189,221000,"Road cut and Relaying of BT road at Manokar Nagar 7th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15232,Roads,Completed,NP-PERUNGUDI,189,124000,"Road cut and Relaying of BT road at Manokar Nagar 8th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15233,Roads,Completed,NP-PERUNGUDI,189,233000,"Road cut and Relaying at Manokar Nagar 9th Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15236,Roads,Completed,NP-PERUNGUDI,189,433000,"Road cut and Relaying Meru nagar 5th cross street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15237,Roads,Completed,NP-PERUNGUDI,189,255000,"Road cut and Relaying at Meru nagar 5th street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15238,Roads,Completed,NP-PERUNGUDI,189,800000,"Road cut and Relaying at Nagammal Avenue 1st Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15239,Roads,Completed,NP-PERUNGUDI,189,209000,"Road cut and Relaying at Neela Nagar in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15240,Roads,Completed,NP-PERUNGUDI,189,543000,"Road cut and Relaying New colony - Deivasaigamani street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15242,Roads,Completed,NP-PERUNGUDI,189,240000,"Road cut and Relaying at New colony - Deivasaigamani street Ext. in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15243,Roads,Completed,NP-PERUNGUDI,189,656000,"Road cut and Relaying at New colony 1st street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15245,Roads,Completed,NP-PERUNGUDI,189,272000,"Road cut and Relaying at New Colony 2nd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15247,Roads,Completed,NP-PERUNGUDI,189,728000,"Road cut and Relaying at New colony cross street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15248,Roads,Completed,NP-PERUNGUDI,189,76000,"Road cut and Relaying at Parasuram Nagar cross street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15250,Roads,Completed,NP-PERUNGUDI,189,778000,"Road cut and Relaying at Parasuram Nagar Main Road in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15252,Roads,Completed,NP-PERUNGUDI,189,320000,"Road cut and Relaying at Periyar Nagar 2nd cross street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15253,Roads,Completed,NP-PERUNGUDI,189,300000,"Road cut and Relaying at Periyar nagar Avvai 1st Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15254,Roads,Completed,NP-PERUNGUDI,189,338000,"Road cut and Relaying at Periyar nagar Avvai 2nd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15255,Roads,Completed,NP-PERUNGUDI,189,220000,"Road cut and Relaying at Periyar nagar Avvai Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15256,Roads,Completed,NP-PERUNGUDI,189,304000,"Road cut and Relaying at Periyar Nagar Indira Ammaiyar Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15257,Roads,Completed,NP-PERUNGUDI,189,200000,"Roa cut and Relaying at Periyar Nagar Kambar Cross Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15258,Roads,Completed,NP-PERUNGUDI,189,520000,"Road cut and Relaying at Periyar Nagar Kambar Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15259,Roads,Completed,NP-PERUNGUDI,189,560000,"Road cut and Relaying at Periyar Nagar Main Road in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15260,Roads,Completed,NP-PERUNGUDI,189,780000,"Road cut and Relaying at Periyar Nagar Manickavasagar 1st Cross Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15261,Roads,Completed,NP-PERUNGUDI,189,420000,"Road cut and Relaying at Periyar Nagar Manickavasagar 2nd Cross Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15262,Roads,Completed,NP-PERUNGUDI,189,540000,"Road cut and Relaying at Periyar Nagar Manickavasagar Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15263,Roads,Completed,NP-PERUNGUDI,189,680000,"Road cut and Relaying at Periyar Nagar Nakkirar Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15264,Roads,Completed,NP-PERUNGUDI,189,766000,"Road cut and Relaying at Periyar Nagar Pugalenthi Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15265,Roads,Completed,NP-PERUNGUDI,189,308000,"Road cut and Relaying at Periyar nagar Sekkilar Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15266,Roads,Completed,NP-PERUNGUDI,189,1080000,"Road cut and Relaying at Periyar Nagar Thiruvallur Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15267,Roads,Completed,NP-PERUNGUDI,189,320000,"Road cut and Relaying at Periyar Nagar Valmiki Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15271,Roads,Completed,NP-PERUNGUDI,189,500000,"Road cut and Relaying at Periyar Nagar Viyasar Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15272,Roads,Completed,NP-PERUNGUDI,189,806000,"Road cut and Relaying of BT road at Rajalakshmi Nagar 2nd Main Road in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15273,Roads,Completed,NP-PERUNGUDI,189,240000,"Road cut and Relaying at Rajalakshmi Nagar 1st cross street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15282,Roads,Completed,NP-PERUNGUDI,189,113000,"Road cut and Relaying at Rajalakshmi Nagar 1st Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15283,Roads,Completed,NP-PERUNGUDI,189,244000,"Road cut and Relaying at Rajalakshmi Nagar 2nd Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15284,Roads,Completed,NP-PERUNGUDI,189,541000,"Road cut and Relaying at Rajalakshmi Nagar 3rd Cross Street in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15285,Roads,Completed,NP-PERUNGUDI,189,188000,"Road cut and Relaying at Rajalakshmi Nagar 3rd Cross Street Ext. in Dn -189 Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15286,Roads,Completed,NP-PERUNGUDI,189,263000,"Road cut and Relaying at Rajalakshmi Nagar 3rd Street in Dn -189,Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15287,Roads,Completed,NP-PERUNGUDI,189,901000,"Road cut and Relaying at Rajalakshmi Nagar 3rd Street (Maruthi avenue) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15288,Roads,Completed,NP-PERUNGUDI,189,420000,"Road cut and Relaying at Krishna Nagar 3rd Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15299,Roads,Completed,NP-PERUNGUDI,189,488000,"Road cut and Relaying at Rajalakshmi Nagar 4th Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15300,Roads,Completed,NP-PERUNGUDI,189,375000,"Roadcut and Relaying at Rajalakshmi Nagar 4th Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15303,Roads,Completed,NP-PERUNGUDI,189,338000,"Road cut and Relaying at Rajalakshmi Nagar 5th Street in Dn -189,Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15305,Roads,Completed,NP-PERUNGUDI,189,413000,"Road cut and Relaying at Rajalakshmi Nagar 7th Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15306,Roads,Completed,NP-PERUNGUDI,189,676000,"Road cut and Relaying at Rajalakshmi Nagar 8th Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15307,Roads,Completed,NP-PERUNGUDI,189,338000,"Road cut and Relaying at Selvam nagar Gandhi Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15308,Roads,Completed,NP-PERUNGUDI,189,920000,"Road cut and Relaying at Selvam nagar Main road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15309,Roads,Completed,NP-PERUNGUDI,189,320000,"Road cut and Relaying at Selvam Nagar Vallalar 1st Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15310,Roads,Completed,NP-PERUNGUDI,189,520000,"Road cut and Relaying at Selvam Nagar Vallalar Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15311,Roads,Completed,NP-PERUNGUDI,189,560000,"Road cut and Relaying at Selvam Nagar Vallalar Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15312,Roads,Completed,NP-PERUNGUDI,189,460000,"Road cut and Relaying at .I.I.T colony 3rd street in Dn -189,Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15313,Roads,Completed,NP-PERUNGUDI,189,688000,"Road cut and Relaying at .I.I.T colony 4th street in Dn -189,Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15316,Roads,Completed,NP-PERUNGUDI,189,800000,"Road cut and Relaying at Shree Avenue in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15317,Roads,Completed,NP-PERUNGUDI,189,826000,"Road cut and Relaying at Sri Ganapathy nagar (Thangam nagar) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15318,Roads,Completed,NP-PERUNGUDI,189,440000,"Road cut and Relaying at Sri Vengateswaran Nagar 1st Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15319,Roads,Completed,NP-PERUNGUDI,189,520000,"Road cut and Relaying at Sri Vengateswaran Nagar cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15320,Roads,Completed,NP-PERUNGUDI,189,580000,"Road cut and Relaying at Sri Venkateswaran Nagar 2nd St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15321,Roads,Completed,NP-PERUNGUDI,189,320000,"Roadcut and Relaying at Sri Venkateswaran Nagar Ext. in Dn -189, Unit- 43, Zone- XI",Grants,14,2019-20,2020-21 NP/2019-20/15322,Roads,Completed,NP-PERUNGUDI,189,212000,"Road cut and Relaying at Syndicate Bank Colony 3rd Street in Dn -189, Unit- 43, Zone- XI",Grants,14,2019-20,2020-21 NP/2019-20/15323,Roads,Completed,NP-PERUNGUDI,189,493000,"Road cut and Relaying at Syndicate Bank Venkatraman Street in Dn -189, Unit- 43, Zone- XI",Grants,14,2019-20,2020-21 NP/2019-20/15324,Roads,Completed,NP-PERUNGUDI,189,1600000,"Road cut and Relaying at Thangam avenue main road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15325,Roads,Completed,NP-PERUNGUDI,189,179000,"Road cut and Relaying at Thangam Nagar in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15326,Roads,Completed,NP-PERUNGUDI,189,318000,"Road cut and Relaying at Thangam Nagar 1st Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15327,Roads,Completed,NP-PERUNGUDI,189,348000,"Roadcut and Relaying at Thangam Nagar 2nd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15328,Roads,Completed,NP-PERUNGUDI,189,406000,"Roadcut and Relaying at Thiru. Vi. Ka Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15329,Roads,Completed,NP-PERUNGUDI,189,225000,"Road cut and Relaying at Thirumalai Nagar in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15330,Roads,Completed,NP-PERUNGUDI,189,563000,"Road cut and Relaying at Thulukanathamman 11th Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15336,Roads,Completed,NP-PERUNGUDI,189,638000,"Roadcut and Relaying at Thulukanathamman 12th Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15338,Roads,Completed,NP-PERUNGUDI,189,319000,"Road cut and Relaying at Thulukanathamman 13th Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15339,Roads,Completed,NP-PERUNGUDI,189,131000,"Road cut and Relaying at Thulukanathamman 14th Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15340,Roads,Completed,NP-PERUNGUDI,189,394000,"Road cut and Relaying at Thulukanathamman 15th cross street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15341,Roads,Completed,NP-PERUNGUDI,189,207000,"Road cut and Relaying at Veerathamman kovil 2nd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15342,Roads,Completed,NP-PERUNGUDI,189,582000,"Road cut and Relaying at Thulukanathamman 8th Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15343,Roads,Completed,NP-PERUNGUDI,189,638000,"Road cut and Relaying at Thulukanathamman 9th Cross Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15344,Roads,Completed,NP-PERUNGUDI,189,38000,"Road cut and RelayingThulukanathamman Koil 17th Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15345,Roads,Completed,NP-PERUNGUDI,189,195000,"Road cut and Relaying at Thulukanathamman Koil 1st Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15346,Roads,Completed,NP-PERUNGUDI,189,244000,"Road cut and Relaying at Thulukanathamman Koil 2nd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15347,Roads,Completed,NP-PERUNGUDI,189,300000,"Road cut and Relaying at Thulukanathamman Koil 3rd Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15348,Roads,Completed,NP-PERUNGUDI,189,225000,"Road cut and Relaying at Thulukanathamman Koil 4th Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15350,Roads,Completed,NP-PERUNGUDI,189,338000,"Road cut and Relaying of BT road at Thulukanathamman Koil 5th Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15351,Roads,Completed,NP-PERUNGUDI,189,176000,"Road cut and Relaying at Thulukanathamman Nagar Koil 16th Cross St in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15352,Roads,Completed,NP-PERUNGUDI,189,480000,"Road cut and Relaying at Tropical colony - Meenatchi Nagar in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15353,Roads,Completed,NP-PERUNGUDI,189,290000,"Road cut and Relaying at V.G.P Shanthi Nagar Abdul Azad Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15354,Roads,Completed,NP-PERUNGUDI,189,255000,"Road cut and Relaying at VGP Shanthi Nagar (Perumal Nagar 1st Street) in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15355,Roads,Completed,NP-PERUNGUDI,189,330000,"Road cut and Relaying at VGP Shanthi Nagar Church Avenue Extn., in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15356,Roads,Completed,NP-PERUNGUDI,189,435000,"Road cut and Relaying at VGP shanthi Nagar Elango St Extn in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15359,Roads,Completed,NP-PERUNGUDI,189,552000,"Road cut and Relaying of BT road at VGP Shanthi nagar Ext. Church avenue in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15361,Roads,Completed,NP-PERUNGUDI,189,330000,"Roadcut and Relaying at VGP Shanthi nagar Ext. Church avenue 2nd main road in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15362,Roads,Completed,NP-PERUNGUDI,189,206000,"Road cut and Relaying at VGP Shanthi Nagar Green Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15363,Roads,Completed,NP-PERUNGUDI,189,313000,"Road cut and Relaying at VGP Shanthi Nagar Kabilar Street in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15388,Roads,Completed,NP-PERUNGUDI,189,615000,"Road cut and Relaying of BT road at VGP Shanthi Nagar Kambar Street in Dn -189,Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15389,Roads,Completed,NP-PERUNGUDI,189,505000,"Road cut and Relaying of Bt road at VGP Shanthi nagar Lakshmi street Extn in Dn -189, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15390,Roads,Completed,NP-PERUNGUDI,189,106000,"Road cut and Relaying at VGP Shanthi Nagar Pari Cross Street in Dn -189,Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15391,Roads,Completed,NP-PERUNGUDI,189,253000,"Road cut and Relaying at Vimala Nagar in Dn -189,Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/2335,Buildings,Completed,NP-PERUNGUDI,189,1486000,"Improvements works for Malligeshwaran Nagar Compost Yard in Dn-189,Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/3611,Road Cut,Completed,NP-PERUNGUDI,189,2067000,"Restoration of Metro Water Road Cut (CMWSSB) at Kamakotti Nagar 9th Street, Meenatchipuram 1st & 2nd Street,Meru Nagar 1st Cross Street and Meru Nagar Main Road in Div-189, Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/3612,Road Cut,Completed,NP-PERUNGUDI,189,1946000,"Restoration of Metro Water Road Cut (CMWSSB) at Meru Nagar 1st Street, Kamakotti Nagar 6th Cross & 9th Cross Street,VGP Shanthi Nagar Thiruvalluvar Street,Anna MGR Nagar Indhira Gandhi Street and Kamber Street in Div-189, Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/3614,Road Cut,Completed,NP-PERUNGUDI,189,1946000,"Restoration of Metro Water Road Cut (CMWSSB) at Anna MGR Nagar Moovendar Street,Gandhi Street,Rajiv Gandhi Street and Sabari Nagar Chellamuthu Street in Div-189, Unit-43, Zone-14.",Deposit Works,14,2019-20,2019-20 NP/2019-20/3615,Road Cut,Completed,NP-PERUNGUDI,189,1920000,"Restoration of Metro Water Road Cut (CMWSSB) at Anna MGR Nagar Sathya Moorthy Colony,Thulukanathamman Koil 10th Street,7th Street,6th Street,Tropical Colony Thangaraj Street and Varadharajan Nagar 2nd Street in Div-189, Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/3616,Road Cut,Completed,NP-PERUNGUDI,189,1819000,"Restoration of Metro Water Road Cut (CMWSSB) at VGP Shanthi Nagar Kurunji Street & Kanchi Street & Labour Colony 1st Street & 3rd Street and Monohar Nagar 15th Street,16th Street in Div-189, Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/3617,Road Cut,Completed,NP-PERUNGUDI,189,894000,"Restoration of Metro Water Road Cut (CMWSSB) at Tropical Colony and Anna MGR Nagar Iyyapan Street in Div-189, Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/3671,Storm Water Drain,Completed,NP-PERUNGUDI,189,87000,"Providing Trash Arrester for ISWD Disposal Point at Kamatchiyamman Nagar and Kamakotti Nagar 3rd Main Road,Pallavan Nagar,Anchaneyar Nagar and Various Streets in Dn-189,190&191,Unit - 43,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/3905,Buildings,Completed,NP-PERUNGUDI,189,787000,"Construction of Compound wall(West Side) at Malligeshwaran nagar Compost yard in Dn-189, Unit-43, Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/5123,Storm Water Drain,Completed,NP-PERUNGUDI,189,70000,"Providing Rain water harvesting structures at various locations in Dn189,Unit-43,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/5485,Roads,Completed,NP-PERUNGUDI,189,117000,"Relaying of Periyar Nagar Thiruvalluvar Street in Div - 189, Unit - 43, Zone - 14",Grants,14,2019-20,2020-21 NP/2019-20/6636,Roads,Completed,NP-PERUNGUDI,189,1850000,"ROAD FORMATION AT MALLIGESHWARAN NAGAR COMPOST YARD IN DN-189,UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6858,Storm Water Drain,Completed,NP-PERUNGUDI,189,158000,"Desilting for Storm Water Drain and Side Drain at Various Street in Dn-189,Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6859,Storm Water Drain,Completed,NP-PERUNGUDI,189,736000,"Minor Repair Work for Storm Water Drain and Side Drain at Various Streets in Dn-189,Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6965,Parks,Completed,NP-PERUNGUDI,189,836000,"MAINTENANCE OF PARK AT ASTALAKSHMI AVENUNE IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6966,Parks,Completed,NP-PERUNGUDI,189,668000,"MAINTENANCE OF PARK AT VGP SHANTHI NAGAR IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6967,Parks,Completed,NP-PERUNGUDI,189,591000,"MAINTENANCE OF PARK AT ARUMUGAM NAGAR IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6969,Parks,Completed,NP-PERUNGUDI,189,1672000,"MAINTENANCE OF PARK AT KAMAKOTTI NAGAR IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6970,Parks,Completed,NP-PERUNGUDI,189,1185000,"MAINTENANCE OF PARK AT THAMARAIKULAM IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6971,Parks,Completed,NP-PERUNGUDI,189,691000,"MAINTENANCE OF HERBAL PARK IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7267,Roads,Completed,NP-PERUNGUDI,189,1320000,"Providing and Laying for Hume pipe at Malligeshwaran nagar 2nd cross street and various street in Dn -189, U-43,Z-14",Own Sources,14,2019-20,2020-21 NP/2019-20/7605,Buildings,Completed,NP-PERUNGUDI,189,277000,Repairs and Improvements to IIT Colony Community Hall in Dn 189 Unit 43 Zone 14,Own Sources,14,2019-20,2019-20 NP/2019-20/8401,Roads,Completed,NP-PERUNGUDI,189,578000,"Attending The BT Road Patch Work at kamakoti nagar 1st main road,kamakoti nagar 3rd Main Road,IIT Colony 1st Main Road,VGP Shanthi Nagar Main Road and Variuos Streets in Division-189,Unit-43,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/8601,Roads,Completed,NP-PERUNGUDI,189,2134000,"Restoration of Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO) BT Roadcut at Selvam Nagar Main Road,Manogar Nagar,IIT Colony 2nd Main Road,Manogar Nagar 7th Street,Elango Streeet-Varatharaj Nagar,,Bharathi Street-Vgp Shanthi Nagar and Vallalar Street in Div-189, Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/9164,Roads,Completed,NP-PERUNGUDI,189,3711000,"Relaying of BT Road in Thulukanathamman koil main road in Div - 189, Unit - 43, Zone -14.",Grants,14,2019-20,2020-21 NP/2019-20/9165,Roads,Completed,NP-PERUNGUDI,189,230000,"Relaying of BT road in manohar Nagar 1st street in Div - 189, Unit - 43, Zone - 14.",Grants,14,2019-20,2020-21 NP/2019-20/9166,Roads,Completed,NP-PERUNGUDI,189,641000,"Relaying of BT Road in Malligeshwaran nagar main road in Div - 189, Unit - 43, Zone - 14",Grants,14,2019-20,2020-21 NP/2019-20/9514,Roads,Completed,NP-PERUNGUDI,189,835000,"Attending Patch Work with GSB,WMM at Manogar Nagar 1st Street , Manogar Nagar 5th Street , Manogar Nagar Main road , Malligeshwaran nagar cross street in Dn-189,Unit-43,Zone-14",Own Sources,14,2019-20,2020-21 BR/2019-20/17631,Roads,Completed,BR-Bus Route Roads,190,959000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-190 & 191 UNIT-43 ZONE-14(DEPOSIT CODE-57/1132/2018-19),Deposit Works,14,2019-20,2020-21 NP/2019-20/1251,Buildings,Completed,NP-PERUNGUDI,190,586000,"Supply and Fixing of Well Rings for composting purposes at Various Places in Dn-189, 190 and 191 Unit-43,zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/15456,Roads,Completed,NP-PERUNGUDI,190,763000,"Formation of BT Road at Ganapathi Nagar extn in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15458,Roads,Completed,NP-PERUNGUDI,190,2018000,"Formation of BT Road at Ambal Nagar Rajesh Avenue in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15459,Roads,Completed,NP-PERUNGUDI,190,255000,"Relaying at BT Road Ambedkar cross street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15465,Roads,Completed,NP-PERUNGUDI,190,308000,"Strengthening and Relaying at BT Road Ambedkar Nagar Nehru 1st Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15467,Roads,Completed,NP-PERUNGUDI,190,987000,"Formation of BT Road at Chitti Babu Nagar 1st Cross Street Extn in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15498,Roads,Completed,NP-PERUNGUDI,190,384000,"Roadcut and Relaying at BT Road Pandian nagar 2nd cross street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15499,Roads,Completed,NP-PERUNGUDI,190,512000,"Roadcut and Relaying at BT Road Pandian nagar 3rd cross street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15500,Roads,Completed,NP-PERUNGUDI,190,392000,"Roadcut and Relaying at BT Road Pandian nagar 4th cross street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15503,Roads,Completed,NP-PERUNGUDI,190,444000,"Roadcut and Relaying of BT Road at Esadiyan Well Salai in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15529,Roads,Completed,NP-PERUNGUDI,190,491000,"Formation of BT Road at Pasumpon Nagar 1st Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15530,Roads,Completed,NP-PERUNGUDI,190,238000,"Formation of BT Road at Ambedkar nagar cross Street Extn.in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15531,Roads,Completed,NP-PERUNGUDI,190,865000,"Formation of BT Road at Pasumpon Nagar 2nd Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15532,Roads,Completed,NP-PERUNGUDI,190,842000,"Formation of BT Road at Pasumpon Nagar 3rd Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15533,Roads,Completed,NP-PERUNGUDI,190,562000,"Formation of BT Road at Pasumpon Nagar 4th Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/15534,Roads,Completed,NP-PERUNGUDI,190,1615000,"Formation of BT Road at Pasumpon Nagar 5th Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2019-20,2020-21 NP/2019-20/3498,Roads,Completed,NP-PERUNGUDI,190,1354000,"Restoration of CMWSSB Road Cut Portion at Sai Ganesh Nagar 6th Cross Street, Sai Ganesh Nagar 4th Cross Street, Sai Ganesh Nagar 5th Cross Street, Sai Ganesh Nagar 8th Cross Street, Sri Nagar 3rd Main Road, Sri Nagar 4th Cross Street, Sri Nagar 3rd Cross Street, and Sri Nagar 2nd Main road in Dn-190,Unit-43,Zone-14",Deposit Works,14,2019-20,2019-20 NP/2019-20/3499,Roads,Completed,NP-PERUNGUDI,190,1611000,"Restoration of CMWSSB Road Cut Portion at Easadiyan 1st Street, Easadiyan Street, Ganabathipuram 3rd Street, Ganabathipuram 2nd Street, Prabu Nagar, Prabu Nagar 1st Main Road, Ambal Nagar 3rd Main Road and Ambal Nagar 1st Cross Street in Dn-190,Unit-43,Zone-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/3501,Roads,Completed,NP-PERUNGUDI,190,1994000,"Restoration of CMWSSB Road Cut Portion at Vivekanadhar 1st Main Road, Ambal Nagar 2nd Main Road, Sai Ganesh Nagar 16th Cross Street and Sai Ganesh Nagar 15th Cross Street in Dn-190,Unit-43,Zone-14",Deposit Works,14,2019-20,2019-20 NP/2019-20/3502,Roads,Completed,NP-PERUNGUDI,190,1067000,"Restoration of CMWSSB Road Cut Portion at Bavaniamman Koil Street in Dn-190,Unit-43,Zone-14",Deposit Works,14,2019-20,2019-20 NP/2019-20/3887,Buildings,Completed,NP-PERUNGUDI,190,453000,Proposed Construction of Compound Wall at Division Office at Tambaram-Velachery Main Road In Dn-190 Unit-43 Zone-14,Own Sources,14,2019-20,2020-21 NP/2019-20/4714,Parks,Completed,NP-PERUNGUDI,190,2999000,"Strenghthening of Bund, Providing Footpath, Open Gym and FRC Chairs and Pebble Walk for Amman Kulam at Ambal Nagar in Division-190,Unit-43,Zone-14.",MLACDS,14,2019-20,2020-21 NP/2019-20/5126,Storm Water Drain,Completed,NP-PERUNGUDI,190,167000,"Providing Rain water harvesting structures at various locations in Dn.190, Unit-43, Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6363,Roads,Completed,NP-PERUNGUDI,190,1679000,"Restoration of CMWSSB Road Cut Portion and Relaying of at Chitti Babu Nagar Main Road in Dn-190,Unit-43,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/6364,Roads,Completed,NP-PERUNGUDI,190,1408000,"Formation of BT Road at Dill Babu Nagar Main Road in Dn-190,Unit-43,Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/6365,Roads,Completed,NP-PERUNGUDI,190,393000,"Formation of BT Road at Dill Babu Nagar 2nd Cross Street in Dn-190,Unit-43,Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/6366,Roads,Completed,NP-PERUNGUDI,190,516000,"Formation of BT Road at Ambal Nagar 4th Cross Street in Dn-190,Unit-43,Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/6367,Roads,Completed,NP-PERUNGUDI,190,373000,"Formation of BT Road at Ambal Nagar 9th Cross Street in Dn-190,Unit-43,Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/6368,Roads,Completed,NP-PERUNGUDI,190,465000,"Formation of BT Road at Prabu Nagar in Div-190, Unit-43, Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/6774,Storm Water Drain,Completed,NP-PERUNGUDI,190,200000,"Repairs and Maintenance to Kannabiran Koil street Anganwadi,Moovendar street PC,Amman Tank etc in Div - 190, U - 43, Z - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/6792,Storm Water Drain,Completed,NP-PERUNGUDI,190,194000,"Improvements Works to Community Well at Paladiyamman Koil street in Dn-190, Unit-43, Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6856,Storm Water Drain,Completed,NP-PERUNGUDI,190,68000,"Desilting for Storm Water Drain and Side Drain at Various Streets in Dn-190,Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6857,Storm Water Drain,Completed,NP-PERUNGUDI,190,193000,"Minor Repair Work For Storm Water Drain and Side Drain at Various Street In Dn-190,Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/6973,Parks,Completed,NP-PERUNGUDI,190,866000,"MAINTENANCE OF CHETTINADU HOUSING PARK-I IN DIV-190, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6974,Parks,Completed,NP-PERUNGUDI,190,824000,"MAINTENANCE OF CHETTINADU HOUSING PARK-III IN DIV-190, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6975,Parks,Completed,NP-PERUNGUDI,190,241000,"MAINTENANCE OF AMBEDKAR PARK IN DIV-190, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7150,Buildings,Completed,NP-PERUNGUDI,190,546000,Construction of Septic Tank and Providing Barbed Wire Fencing at Rear side of Division-190 Office at Velachery-Tambaram Main Road in Dn-190 Unit-43 Zone-14,Own Sources,14,2019-20,2020-21 NP/2019-20/7191,Buildings,Completed,NP-PERUNGUDI,190,336970,Painting and Improvement Works to Division Office and Conservancy Godown in Dn-190 Unit-43 Zone-14,Own Sources,14,2019-20,2020-21 NP/2019-20/7378,Roads,Completed,NP-PERUNGUDI,190,713000,"Providing and Laying for Hume pipe at Vivekanadhar Nagar 1st Main Road and various street in Dn -190, U-43,Z-14",Own Sources,14,2019-20,2020-21 NP/2019-20/8403,Roads,Completed,NP-PERUNGUDI,190,520000,"Attending The BT Road Patch Work at Kannabiran Koil street,vivekanadhar street,Ambal nagar main road and Various Streets in Division-190,Unit-43,Zone-14.",Own Sources,14,2019-20,2021-22 NP/2019-20/8603,Roads,Completed,NP-PERUNGUDI,190,2524000,"Restoration of Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO) Roadcut at Kinatru Salai,Vallal Pari Street,Moovendhar Street,Kovalan Nagar 2nd Main Road,Kovalan Nagar 4th Cross Street,Vivekandha Nagar Main Road,Erikarai Street,Kovalan Nagar 1st Street-2nd Main Road,Sai Ganesh Nagar 3rd Street,Sai Ganesh Nagar 4th Street and Jeeva Nagar in Div-190 ,Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/8810,Buildings,Completed,NP-PERUNGUDI,190,317000,"Improvement Works for Division 190 Office at Tambaram Velachery Main Road in Div-190, Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/8812,Roads,Completed,NP-PERUNGUDI,190,132000,"Providing Wet Mix at Chittibabu Nagar Various Locations in Div-190, Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/8855,Buildings,Completed,NP-PERUNGUDI,190,50000,"Improvements to Amma Unavagam,Public Conveniences and Other Maintenance Works in Div-190, Unit-43,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/9539,Roads,Completed,NP-PERUNGUDI,190,956000,"Attending Patch Work with GSB,WMM at Meenakshipuram 1st street,Labour Colony main road,Labour colony cross street and Labour colony 2nd street in Dn-189,Unit-43,Zone-14",Own Sources,14,2019-20,2020-21 BR/2019-20/17632,Road Cut,Completed,BR-Bus Route Roads,191,975000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-191&190 UNIT-43 ZONE-14(DEPOSIT CODE-57/1132/2018-19),Deposit Works,14,2019-20,2020-21 BR/2019-20/17633,Road Cut,Completed,BR-Bus Route Roads,191,959000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-191 UNIT-43 ZONE-14(DEPOSIT CODE-57/1132/2018-19),Deposit Works,14,2019-20,2020-21 BR/2019-20/17634,Roads,Completed,BR-Bus Route Roads,191,82000,RESTORATION OF ROAD CUT MADE BY ACT AT VARIOUS INTERIOR ROADS IN DIV-191 UNIT-43 ZONE-14(DEPOSIT CODE-57/1132/2018-19),Deposit Works,14,2019-20,2020-21 NP/2019-20/10228,Buildings,Completed,NP-PERUNGUDI,191,347000,"Providing Top Slab for open side Drain at Kalaikuthu Nagar Public Convenience and improvements works to , Ex Serviceman Colony Amma Unavagam,Compost yard and various location at Div-191,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/10229,Roads,Completed,NP-PERUNGUDI,191,153000,"Providing WMM at Jaganathapuram Main Road,Jayachandiran Nagar 1st Main Road and various Street in Div-191,Unit-42,Zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/10231,Storm Water Drain,Completed,NP-PERUNGUDI,191,382000,"Relaying of BT Road at Nesavalar Nagar Avvai street in Div-191,Unit-42,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/10587,Buildings,Completed,NP-PERUNGUDI,191,200000,"Repairs and Maintenance to Puthu nagar and Rice Mill road Amma Unavagam,Kalai Koothu nagar and Gandhi road PC etc in Div - 191, U - 43, Z - 14",Own Sources,14,2019-20,2020-21 NP/2019-20/1174,Buildings,Completed,NP-PERUNGUDI,191,294000,"PROPOSED CONSTRUCTION OF MATERIAL RECOVERY FACILITY IN COMPOST YARD AT PUDHU NAGAR IN DN-190 AND DN-191,UNIT-43,ZONE-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/1253,Buildings,Completed,NP-PERUNGUDI,191,196000,"Providing Mulch Pit for Dry Waste Composting Purpose inside the Parks at Variuos Location in Dn-189, 190 and 191 Unit-43,zone-14.",Own Sources,14,2019-20,2019-20 NP/2019-20/15507,Roads,Completed,NP-PERUNGUDI,191,394000,"Partly relaying at Jayachandiran Nagar 2nd Main Road in Dn -191, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15512,Roads,Completed,NP-PERUNGUDI,191,514000,"Relaying of BT Road at Masuthi Street in Dn -191, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15514,Roads,Completed,NP-PERUNGUDI,191,501000,"Relaying of BT Road at Quithe Millath Street in Dn -191, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/15515,Roads,Completed,NP-PERUNGUDI,191,106000,"Relaying of BT Road at Quithe Millath 1st Cross Street in Dn -191, Unit- 43, Zone- XIV",Grants,14,2019-20,2021-22 NP/2019-20/2337,Buildings,Completed,NP-PERUNGUDI,191,1290000,Improvements to Compost Yard at Pudhu Nagar Burial Ground In Dn-191 Unit-43 Zone-14,Own Sources,14,2019-20,2019-20 NP/2019-20/3497,Roads,Completed,NP-PERUNGUDI,191,1272000,"Restoration of CMWSSB Road Cut Portion at Sai Ganesh Nagar 9th,10th,17th Street and Sai Ganesh Nagar 2nd Main Road in Dn-191,Unit-43,Zone-14",Deposit Works,14,2019-20,2020-21 NP/2019-20/5127,Storm Water Drain,Completed,NP-PERUNGUDI,191,194000,"Providing Rain water harvesting structures at various locations in Dn.191, Unit-43, Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/5930,Parks,Completed,NP-PERUNGUDI,191,611000,"Maintenance Estimate for Park at Jayachandiran Nagar Main Road in Dn-191, Unit-43, Zone-14.(For The Period 6 Months)",Own Sources,14,2019-20,2019-20 NP/2019-20/6375,Roads,Completed,NP-PERUNGUDI,191,187000,"Formation of BT Road at Padmavathi Nagar Mageswari Cross Street in Dn-191,Unit-43,Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/6706,Storm Water Drain,Completed,NP-PERUNGUDI,191,454000,"Improvement works to Community Well at Pillayar koil Street in Dn-191,Unit-43,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6754,Roads,Completed,NP-PERUNGUDI,191,233000,Formation of BT road at Padmavathi Nagar Rajeswari Cross Street in Dn-191 Unit-43 Zone-14,Grants,14,2019-20,2020-21 NP/2019-20/6854,Storm Water Drain,Completed,NP-PERUNGUDI,191,247000,"Desilting for Storm Water Drain and Side Drain at Various Streets in Dn-191,Unit-43,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6855,Storm Water Drain,Completed,NP-PERUNGUDI,191,1350000,"Minor Repair Works for Storm Water Drain and Side Drain at Various Streets in Dn-191,Unit-43,Zone-14",Own Sources,14,2019-20,2019-20 NP/2019-20/6962,Parks,Completed,NP-PERUNGUDI,191,714000,"MAINTENANCE OF PARK AT JAYACHANDRAN NAGAR 5TH MAIN ROAD IN DIV-191, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6963,Parks,Completed,NP-PERUNGUDI,191,1101000,"MAINTENANCE OF PARK AT SELENE ESTATE IN DIV-191, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6964,Parks,Completed,NP-PERUNGUDI,191,1147000,"MAINTENANCE OF PARK AT JAYACHANDRAN NAGAR 1ST MAIN ROAD IN DIV-191, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/6968,Parks,Completed,NP-PERUNGUDI,191,930000,"MAINTENANCE OF PARK AT IIT COLONY IN DIV-189, UNIT-43,ZONE-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/7014,Buildings,Completed,NP-PERUNGUDI,191,1036000,Construction of Compound Wall and Raising the existing Compound Wall and Providing manure drying bed area at compost yard in Pudhu Nagar 5th Street in Dn-191 Unit-43 Zone-14,Own Sources,14,2019-20,2020-21 NP/2019-20/7270,Roads,Completed,NP-PERUNGUDI,191,237000,"Providing and Laying for Hume pipe at Jayachandiran Nagar 2nd Main Road and various street in Dn -191, U-43,Z-14",Own Sources,14,2019-20,2020-21 NP/2019-20/8404,Roads,Completed,NP-PERUNGUDI,191,520000,"Attending The BT Road Patch Work at Pillayar koil street,Pillayar koil Street,Pudhu Nagar and Variuos Streets in Division-191,Unit-43,Zone-14.",Own Sources,14,2019-20,2020-21 NP/2019-20/9125,Roads,Completed,NP-PERUNGUDI,191,429000,"Relaying of BT Road at Pallavan Nagar Nagathamman koil street in Dn-191,Unit-43,Zone-14",Grants,14,2019-20,2020-21 NP/2019-20/9525,Roads,Completed,NP-PERUNGUDI,191,545000,"Restoration of Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO) CC Roadcut at Nagathamman Koil Street Pallavan Nagar main road in Div-191, Unit-43, Zone-14.",Deposit Works,14,2019-20,2020-21 NP/2019-20/9869,Roads,Completed,NP-PERUNGUDI,191,335000,"Relaying of BT Road at Pallavan Nagar Muthu vinayagar Koil Street in Dn-191,Unit-43,Zone-14.",Grants,14,2019-20,2020-21 NP/2019-20/9873,Roads,Completed,NP-PERUNGUDI,191,546000,"Relaying of BT road at Nesavalar Nagar Logambal street in Dn-191,Unit-43,Zone-14.",Grants,14,2019-20,2020-21 NQ/2019-20/11285,Buildings,Completed,NQ-SHOZHINGANALLUR,192,88000,"PROVIDING RAINWATER HARAVESTING AT DIVISION OFFICE AND UPHC BULDING IN Dn-192, U-44, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/11751,Buildings,Completed,NQ-SHOZHINGANALLUR,192,175000,"IMPROVEMENT AND REPAIR WORK FOR AMMAUNAVAGAM, BIN PLATFORM AND TOILET AT NEELANGARAI IN DN-192, U-44, Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/1435,Roads,Completed,NQ-SHOZHINGANALLUR,192,194000,"Construction of Footpath at Raja Nagar 1st Main Road, 2nd Main Road And 2nd Cross Steet Neelangarai Div-192, U-44, Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/16025,Roads,Completed,NQ-SHOZHINGANALLUR,192,904000,"Relaying of BT Road at Balaji nagar 1st streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16026,Roads,Completed,NQ-SHOZHINGANALLUR,192,950000,"Forming and Laying of BT Road at Balaji nagar 2nd streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16027,Roads,Completed,NQ-SHOZHINGANALLUR,192,949000,"Forming and Laying of BT Road at Balaji nagar 3rd streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16028,Roads,Completed,NQ-SHOZHINGANALLUR,192,689000,"Forming and Laying of BT Road at Ellaiamman koil 5th streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16029,Roads,Completed,NQ-SHOZHINGANALLUR,192,1926000,"Forming and Laying of BT Road at Singaranvelan 1st Cross Street in Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16030,Roads,Completed,NQ-SHOZHINGANALLUR,192,4536000,"Forming and Laying of BT Road at Beach Roadin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16031,Roads,Completed,NQ-SHOZHINGANALLUR,192,648000,"Relaying of BT Road at Ruby complex 4th streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16032,Roads,Completed,NQ-SHOZHINGANALLUR,192,690000,"Forming and Laying of BT Road at Kazura Garden 10th Cross Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16033,Roads,Completed,NQ-SHOZHINGANALLUR,192,261000,"Relaying of BT Road at Ranjith Nagar 1st Cross Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16034,Roads,Completed,NQ-SHOZHINGANALLUR,192,873000,"Forming and Laying of BT Road at Saraswathi Nagar North 3rd Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16035,Roads,Completed,NQ-SHOZHINGANALLUR,192,1021000,"Relaying of BT Road at Sengeni Amman Koil Main Roadin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16036,Roads,Completed,NQ-SHOZHINGANALLUR,192,893000,"Relaying of BT Road at Singaranvelan Street North 1st Main Roadin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16037,Roads,Completed,NQ-SHOZHINGANALLUR,192,723000,"Relaying of BT Road at Saraswathi Nagar North 2rd Main Roadin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16038,Roads,Completed,NQ-SHOZHINGANALLUR,192,545000,"Forming and Laying of BT Road at Ruby Complex in Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16039,Roads,Completed,NQ-SHOZHINGANALLUR,192,893000,"Forming and Laying of CC Road at Sengeni Amman Koil 4th Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16041,Roads,Completed,NQ-SHOZHINGANALLUR,192,661000,"Forming and Laying of CC Road at CLRI Nagar 4th Cross Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16042,Roads,Completed,NQ-SHOZHINGANALLUR,192,491000,"Forming and Laying of CC Road at Bharathiyar Nagar 16 th Cross Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16044,Roads,Completed,NQ-SHOZHINGANALLUR,192,3475000,"Forming and Laying of CC Road at Chinna Neelangarai Kuppam North ALL Cross Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16049,Roads,Completed,NQ-SHOZHINGANALLUR,192,299000,"Forming and Laying of CC Road at Sengeni Amman Koil 1st Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/16051,Roads,Completed,NQ-SHOZHINGANALLUR,192,635000,"Forming and Laying of CC Road at Sulthan Streetin Div- 192, U- 44, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/1742,Buildings,Completed,NQ-SHOZHINGANALLUR,192,867000,"Providing integrated 1.22m dia Well Ring and M.S.Grill Cover Slab for new Compost Pit and providing M.S.Grill cover slab to Existing compost pit in Dn-192,196,197, U-44 & 45, Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/3057,Roads,Completed,NQ-SHOZHINGANALLUR,192,579000,"Relaying of BT Road at Sandeep Avenue 1st Street in Div-192, U-45,Z-15.",Grants,15,2019-20,2021-22 NQ/2019-20/3058,Roads,Completed,NQ-SHOZHINGANALLUR,192,1100000,"Relaying of BT Road at Sandeep Avenue in Div-192, U-45,Z-15.",Grants,15,2019-20,2021-22 NQ/2019-20/4492,Buildings,Completed,NQ-SHOZHINGANALLUR,192,58000,"PROVIDING RAINWATER HARAVESTING AT VARIOUS STREETS IN Dn-192, U-44, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/4532,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,455000,"Desilting At Various streets in Div-192, U-44 Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/4593,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,478000,"IMPROVEMENT WORK TO SIDE DRAIN AT ELLAI AMMAN KOIL 5TH STREET AND CHINNA NEELANGARAI KUPPAM AND PROVIDING MANHOLE DOOR AT VERIOUS STREET IN DIN-192, U-45, Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/5575,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,137000,"PROVIDING TRASH ARRESTER AT STORM WATER DRAIN IN DIV-192, UNIT-44, ZONE-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/6918,Parks,Completed,NQ-SHOZHINGANALLUR,192,638000,Maintenance Work for Park at Workers Estate in Dn-192 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6919,Parks,Completed,NQ-SHOZHINGANALLUR,192,689000,Maintenance Work for Park at Raja Nagar Park in Dn-192 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7981,Roads,Completed,NQ-SHOZHINGANALLUR,192,61000,"Attending Patch Work at Singaravelan Street, Sengeniamman koil main road, Aringar anna 4th street in DN-192, U-44, ZONE-15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/9879,Buildings,Completed,NQ-SHOZHINGANALLUR,192,237000,"IMPROVEMENT AND REPAIR WORK FOR ALL TOILET AND AT NEELANGARAI IN DN-192, U-44, Z-15",Own Sources,15,2019-20,2019-20 L/2019-20/5234,Electrical,Completed,L-Electrical,193,542300,"Painting of 1996 nos of old 6mtr lamp post with single straight bracket,painting of 202 nos of old 6mtr lamp post with singel arch bracket ,painting of 10 nos of old 8mtr lamp post with double arch bracket and paint of 3 nos of old 8 mtr lamp post with triple arch brqcket and numbering 2211 posts at various locations in Dn.193,Zone15",Own Sources,15,2019-20,2020-21 L/2019-20/5238,Electrical,Completed,L-Electrical,193,999400,"Construction of 1833 nos of new plane concrete Pedestal for old base rusted 6 mtr MS street lamp post at various locations in dn 192 to 200,Zone 15 and construction of 36 nos of new plane concrete Pedestal for old base rusted 8 mtr MS street lamp post in dn 195 , Zone 15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11097,Parks,Completed,NQ-SHOZHINGANALLUR,193,62000,REPAIR AND MAINTAINENCE WORK AT DIV-193 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/11172,Buildings,Completed,NQ-SHOZHINGANALLUR,193,29000,Defacing At Private Compound Wall In Ragiv Gandhi Salai (OMR) and 200 Feet Road Radial Road and Barricading At Kannan Pond and Palichavan Pond,Own Sources,15,2019-20,2019-20 NQ/2019-20/11173,Buildings,Completed,NQ-SHOZHINGANALLUR,193,60000,Providing Platform for Garbage bin at Vulnerable point of Mahathma Ganthi nagar in DIV-193 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/11212,Parks,Completed,NQ-SHOZHINGANALLUR,193,169000,Improvements works to sai nagar park and customs colony park at DIV-193 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/11253,Roads,Completed,NQ-SHOZHINGANALLUR,193,180000,Providing RCC Hume pipe at New Ganesh Nagar 8th street in Dn- 193 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/16098,Roads,Completed,NQ-SHOZHINGANALLUR,193,1726000,Forming and laying of BT road at Srinivasa Nagar in DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16099,Roads,Completed,NQ-SHOZHINGANALLUR,193,1090000,Forming and laying of BT road at Pandiyan Nagar 2nd street DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16100,Roads,Completed,NQ-SHOZHINGANALLUR,193,2222000,Forming and laying of BT road at Kasthuri Bai nagar 2nd Main Road DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16101,Roads,Completed,NQ-SHOZHINGANALLUR,193,1012000,Forming and laying of BT road at Ganesh Nagar 2nd main road in DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16102,Roads,Completed,NQ-SHOZHINGANALLUR,193,1438000,Forming and laying of BT road at Ganesh Nagar 3rd Main road DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16103,Roads,Completed,NQ-SHOZHINGANALLUR,193,3478000,Forming and laying of BT road at Mangala ambigai nagar 2nd street DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16106,Roads,Completed,NQ-SHOZHINGANALLUR,193,1605000,Forming and laying of BT road at karpaga vinayaga nagar 5th main road in DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16107,Roads,Completed,NQ-SHOZHINGANALLUR,193,4519000,Forming and laying of BT road at kasthuribai nagar 1st main road DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16108,Roads,Completed,NQ-SHOZHINGANALLUR,193,2497000,Forming and laying of BT road at mahatma gandhi nagar 1st main road DIV-193 U-45 Z-15.,Grants,15,2019-20,2020-21 NQ/2019-20/16109,Roads,Completed,NQ-SHOZHINGANALLUR,193,3756000,"Forming and Laying OF CC ROAD AT SELVAKUMAR AVENUE IN DIV-193, U-45 Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17146,Roads,Completed,NQ-SHOZHINGANALLUR,193,407000,"Forming and Laying of BT Road at Anandh nagar 6th Cross streetin Div- 193, U- 45, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/17148,Roads,Completed,NQ-SHOZHINGANALLUR,193,1206000,"Forming and Laying of BT Road at MCN 1st streetin Div- 193, U- 45, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/17151,Roads,Completed,NQ-SHOZHINGANALLUR,193,686000,"Forming and Laying of BT Road at Vinayaga Nagar 2nd street in Div- 193, U- 45, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/17156,Roads,Completed,NQ-SHOZHINGANALLUR,193,539000,"Relaying of BT Road at Balamurugan garden 2nd main road in Div- 193, U- 45, Z- 15",Grants,15,2019-20,2020-21 NQ/2019-20/1754,Buildings,Completed,NQ-SHOZHINGANALLUR,193,599000,"Providing integrated 1.22m dia Well Ring and M.S.Grill Cover Slab for new Compost Pit and providing M.S.Grill cover slab to Existing compost pit in Dn-193,194,195,U-45, Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/2339,Buildings,Completed,NQ-SHOZHINGANALLUR,193,824000,"Providing Well Ring compost pit (as per design) at Various Location in Dn-192,193,194,195,196,197,198,199,200,U-45,U-44 Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/4230,Buildings,Completed,NQ-SHOZHINGANALLUR,193,59000,Providing Trash Arrest for Storm water drain B-Canal Disposal Point at Various Location in Dn-193 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/5641,Buildings,Completed,NQ-SHOZHINGANALLUR,193,143000,"Proposed Rain Water Haresting at Various Location in div-193, Unit-45,Zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6146,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,412000,"Desilting At Various streets in Div-193, U-45 Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/6153,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,1127000,"Providing and Laying of Cement Pipe for disposced rain water at low laying area at Sakthi Nagar & Sai Nagar and subburayan Nagar Thoraipakkam in Dn 193,U45, Z-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/7038,Parks,Completed,NQ-SHOZHINGANALLUR,193,957000,MAINTENANCE ESTIMATE FOR PARK AT ANANTHA NAGAR IN DIV-193 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7040,Parks,Completed,NQ-SHOZHINGANALLUR,193,1557000,MAINTENANCE FOR PARK AT SAI NAGAR IN DIV-193 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7049,Parks,Completed,NQ-SHOZHINGANALLUR,193,602000,MAINTENANCE ESTIMATE FOR PARK AT R.E NAGAR PARK IN DIV-193 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7053,Parks,Completed,NQ-SHOZHINGANALLUR,193,888000,"MAITENANCE ESTIMATE FOR PARK AT CUSTOMS COLONY PARK IN DIV-193,U-45,Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/8044,Roads,Completed,NQ-SHOZHINGANALLUR,193,690000,"Attending Cement Concrete patch work at various location in div-193,unit-45,zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/9244,Roads,Completed,NQ-SHOZHINGANALLUR,193,2028000,"RESTORATION OF ROAD CUT AND REFORMING AND LAYING OF BT ROAD AT VINAYAGA NAGAR 5TH STREET, VINAYAGA NAGAR 6TH STREET AND PILLAYAR KOIL STREET IN DN-193 UNIT-45 ZONE-15",Deposit Works,15,2019-20,2020-21 NQ/2019-20/9249,Roads,Completed,NQ-SHOZHINGANALLUR,193,2190000,RESTORATION OF ROAD CUT AND REFORMING AND LAYING OF BT ROAD AT VINAYAGA NAGAR 1ST STREET AND VINAYAGA NAGAR 4TH STREET IN DN-193 UNIT-45 ZONE-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/9264,Parks,Completed,NQ-SHOZHINGANALLUR,193,1250000,Annual Maintenance for park at balamurugan garden in DIV 193 U 45 Z 15,Own Sources,15,2019-20,2020-21 NQ/2019-20/9841,Roads,Completed,NQ-SHOZHINGANALLUR,193,2185000,RESTORATION OF ROAD CUT AND REFORMING AND LAYING OF BT ROAD AT ANANDHA NAGAR 2ND CROSS STREET AND ANANDHA NAGAR 8TH CROSS STREET IN DN-193 UNIT-45 ZONE-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/9844,Roads,Completed,NQ-SHOZHINGANALLUR,193,2100000,RESTORATION OF ROAD CUT AND REFORMING AND LAYING OF BT ROAD AT ANANDA NAGAR 1ST CROSS STREET IN DN-193 UNIT-45 ZONE-15,Deposit Works,15,2019-20,2020-21 BR/2019-20/11106,Road Cut,Completed,BR-Bus Route Roads,194,1040000,"RESTORATION OF OFC ROAD CUT IN VARIOUS DIVISIONS IN 193,194,195&197,UNIT-45, ZONE-15. Deposit Code - 57/0520/2018-19",Deposit Works,15,2019-20,2020-21 L/2019-20/5236,Electrical,Completed,L-Electrical,194,860300,"Painting of 2424 nos of old 6mtr lamp post with single straight bracket,painting of 933 nos of old 6mtr lamp post with singel arch bracket , numbering 3449 posts at various locations in Dn. 194 and 195,Zone15",Own Sources,15,2019-20,2020-21 NQ/2019-20/10373,Parks,Completed,NQ-SHOZHINGANALLUR,194,259000,Improvements to the existing park at Secretariat Colony Park in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/10761,Buildings,Completed,NQ-SHOZHINGANALLUR,194,129000,"Defacing and barricading of private compound wall for chinese president visit purpose at Rajiv Gandhi salai in Div-194, U-45, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/11110,Buildings,Completed,NQ-SHOZHINGANALLUR,194,38000,Improvements work at Division office (OMR Road) in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2021-22 NQ/2019-20/11702,Roads,Completed,NQ-SHOZHINGANALLUR,194,4157000,FORMING AND LAYING BITUMINUOUS ROAD WITH USING PAVER FINISHER AT SECRETARIAT COLONY 1ST CIRCLE ROAD IN DN104 U-45 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/11709,Roads,Completed,NQ-SHOZHINGANALLUR,194,2765000,"RELAYING OF BITUMINOS ROAD USING PAVER FINISHER AT SECRETARIAT COLONY 3RD CIRCLE ROAD IN DN-194, UNIT-45, ZONE-15",Grants,15,2019-20,2020-21 NQ/2019-20/11710,Roads,Completed,NQ-SHOZHINGANALLUR,194,1673000,RELAYING OF BITUMINUOUS ROAD WITH USING PAVER FINISHER AT SECRETARIAT COLONY 6TH CROSS STREET IN DN-194 U-45 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/11716,Roads,Completed,NQ-SHOZHINGANALLUR,194,1634000,FORMING AND LAYING BITUMINOUS ROAD WITH USING PAVER FINISHER AT SECRETARIAT COLONY 6TH CROSS EXTN IN DN-194 U-45 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/11868,Roads,Completed,NQ-SHOZHINGANALLUR,194,878000,FORMING AND LAYING BITUMINOUS ROAD WITH USING PAVER FINISHER AT DEVARAJ AVENUE 1ST CROSS STREET IN DN-194 U-45 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/11869,Roads,Completed,NQ-SHOZHINGANALLUR,194,1015000,"FORMING AND LAYING BITUMINOUS ROAD WITH USING PAVER FINISHER DEVARAJ AVENUE 2ND CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/12123,Roads,Completed,NQ-SHOZHINGANALLUR,194,1012000,"FORMING AND LAYING BITUMINUOUS ROAD WITH USING PAVER FINISHER AT DEVARAJ AVENUE 3RD CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/14570,Buildings,Completed,NQ-SHOZHINGANALLUR,194,993000,Forming of Mini Forest By Miyawaki Method in OSR Land at Rajiv Garden Main Road in Div - 194 U - 45 Zone - XV,Own Sources,15,2019-20,2021-22 NQ/2019-20/15365,Roads,Completed,NQ-SHOZHINGANALLUR,194,535000,"RESTORATION OF ROADCUT AND RELAYING BITUMINOS ROAD USING PAVER FINISHER AT PARTHASARATHY NAGAR 1ST STREET IN DN-194, UNIT-45, ZONE-15",Grants,15,2019-20,2020-21 NQ/2019-20/15411,Roads,Completed,NQ-SHOZHINGANALLUR,194,320000,RESTORATION OF ROAD CUT AND RELAYING OF BITUMINUOUS ROAD WITH USING PAVER FINISHER AT PARTHASARATHY NAGAR 2ND STREET IN DN-194 U-45 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/15420,Roads,Completed,NQ-SHOZHINGANALLUR,194,556000,PARTHASARATHY NAGAR 4TH STREET,Grants,15,2019-20,2020-21 NQ/2019-20/17136,Roads,Completed,NQ-SHOZHINGANALLUR,194,779000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT SECRETARIAT COLONY LINK STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17137,Roads,Completed,NQ-SHOZHINGANALLUR,194,146000,"RELAYING BT ROAD WITH PAVER FINISHER AT SECRETARIAT COLONY 1ST LANE IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17138,Roads,Completed,NQ-SHOZHINGANALLUR,194,322000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT SECRETARIAT COLONY 2ND LANE IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17139,Roads,Completed,NQ-SHOZHINGANALLUR,194,150000,"RELAYING BT ROAD WITH PAVER FINISHER AT SECRETARIAT COLONY 3RD LANE IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17182,Roads,Completed,NQ-SHOZHINGANALLUR,194,885000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT PALLAVAN STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17183,Roads,Completed,NQ-SHOZHINGANALLUR,194,1512000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KUMARAGURU AVENUE IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17184,Roads,Completed,NQ-SHOZHINGANALLUR,194,269000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KRISHNA NAGAR ARUL AVENUE IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17185,Roads,Completed,NQ-SHOZHINGANALLUR,194,388000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KRISHNA NAGAR MAIN ROAD IN DN-15,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17186,Roads,Completed,NQ-SHOZHINGANALLUR,194,122000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KRISHNA NAGAR 1ST STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17187,Roads,Completed,NQ-SHOZHINGANALLUR,194,162000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KRISHNA NAGAR 2ND STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17188,Roads,Completed,NQ-SHOZHINGANALLUR,194,607000,"RELAYING BT ROAD WITH PAVER FINISHER AT SRI NAGAR NEW STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17189,Roads,Completed,NQ-SHOZHINGANALLUR,194,1243000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT VPG AVENUE EXTN MAIN ROAD IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17192,Roads,Completed,NQ-SHOZHINGANALLUR,194,248000,"RELAYING BT ROAD WITH PAVER FINISHER AT GUINDY ENGINEERING COLLEGE 1ST CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17193,Roads,Completed,NQ-SHOZHINGANALLUR,194,683000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT GUINDY ENGINEERING COLLEGE 2ND CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17194,Roads,Completed,NQ-SHOZHINGANALLUR,194,557000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT GUINDY ENGINEERING COLLEGE 3RD CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17195,Roads,Completed,NQ-SHOZHINGANALLUR,194,426000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT GUINDY ENGINEERING COLLEGE 4TH CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17198,Roads,Completed,NQ-SHOZHINGANALLUR,194,693000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT RAJU NAGAR MAIN ROAD IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17199,Roads,Completed,NQ-SHOZHINGANALLUR,194,820000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT RAJU NAGAR 4TH STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17200,Roads,Completed,NQ-SHOZHINGANALLUR,194,266000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT RAJU NAGAR 8TH STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17222,Roads,Completed,NQ-SHOZHINGANALLUR,194,405000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT KEP AVENUE IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17225,Roads,Completed,NQ-SHOZHINGANALLUR,194,511000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT ROYAL AVENUE 4TH STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17226,Roads,Completed,NQ-SHOZHINGANALLUR,194,1103000,"RELAYING BT ROAD WITH PAVER FINISHER AT BAMBAN BABA NAGAR IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17227,Roads,Completed,NQ-SHOZHINGANALLUR,194,223000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT VENKATESHWARA NAGAR IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17236,Roads,Completed,NQ-SHOZHINGANALLUR,194,1047000,"RELAYING BT ROAD WITH PAVER FINISHER AT SECRETARIAT COLONY 3RD CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17237,Roads,Completed,NQ-SHOZHINGANALLUR,194,2392000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT KAMARAJAR STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17239,Roads,Completed,NQ-SHOZHINGANALLUR,194,2292000,"RELAYING BT ROAD WITH PAVER FINISHER AT SECRETARIAT COLONY 4TH MAIN ROAD IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17240,Roads,Completed,NQ-SHOZHINGANALLUR,194,341000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT CPS NAGAR 1ST STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17241,Roads,Completed,NQ-SHOZHINGANALLUR,194,198000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT CPS NAGAR 2ND STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17242,Roads,Completed,NQ-SHOZHINGANALLUR,194,235000,"RESTORATION OF ROAD-CUT RELAYING BT ROAD WITH PAVER FINISHER AT CPS NAGAR 3RD STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17243,Roads,Completed,NQ-SHOZHINGANALLUR,194,741000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT MOUNT PETTAN 4TH CROSS STREET IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17244,Roads,Completed,NQ-SHOZHINGANALLUR,194,456000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT TANK ROAD IN DN-194,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17393,Roads,Completed,NQ-SHOZHINGANALLUR,194,1611000,RESTORATION OF ROAD CUT AND RELAYING OF BITUMINUOUS ROAD WITH USING PAVER FINISHER AT PARTHASARATHY NAGAR 3RD STREET IN DN-194 U-45 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/4470,Buildings,Completed,NQ-SHOZHINGANALLUR,194,100000,Providing Trash Arrest for Storm Water Drain B-Canal Disposal Point at Various location in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/5629,Buildings,Completed,NQ-SHOZHINGANALLUR,194,140000,"Providing Rain Watter Harvesting at Various Location in DN-194,U-45,Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/5866,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,942000,Improvements to Minor repair work at pillaiyar koil street in Dn194 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/6177,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,419000,"Desilting of storm water drain and side drain at various street in Dn-194, U-45 Z-15V",Own Sources,15,2019-20,2019-20 NQ/2019-20/7002,Parks,Completed,NQ-SHOZHINGANALLUR,194,646000,Annual Maintenance for Park at PTC Quarters in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7004,Parks,Completed,NQ-SHOZHINGANALLUR,194,1860000,Annual Maintenance for Park at Secretariat colony 1st Main Road in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7005,Parks,Completed,NQ-SHOZHINGANALLUR,194,1279000,Annual Maintenance for Park at Chandrasekaran avenue in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7008,Parks,Completed,NQ-SHOZHINGANALLUR,194,663000,Annual Maintenance for Park at Sakthi srinivasa road in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/8003,Roads,Completed,NQ-SHOZHINGANALLUR,194,354000,"Attending Patch Work at foundary salai,mahathma gandhi street,pillaiyar koil street & kamarajar Street in DN-194, U-45, ZONE-15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/8395,Buildings,Completed,NQ-SHOZHINGANALLUR,194,760000,Providing fencing work and name board OSR Land at Rajiv Garden in dn-194 u-45 z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/9012,Roads,Completed,NQ-SHOZHINGANALLUR,194,1010000,"Attending Patch Work with GSB AND WMM at Balaji nagar 2nd street,3rd street,4th street, 5th street, 6th street 7th street Kumaraguru avenue Krishna nagar main road and Krishna nagar 1st street in dn194 u-45 Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/9013,Road Cut,Completed,NQ-SHOZHINGANALLUR,194,898000,"Attending Patch Work with GSB AND WMM at Bharathiyar Nagar 1st street,2nd street,3rd street,4th street, 5th street,6th street Bharathiyar nagar 1st cross street Krishna nagar 2nd street and Krishna nagar arul avenue in dn194 u-45 Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/9700,Buildings,Completed,NQ-SHOZHINGANALLUR,194,74000,Providing Chain link Fencing work at PTC Quarters pond in Dn-194 U-45 Z-15,Own Sources,15,2019-20,2021-22 NQ/2019-20/10506,Buildings,Completed,NQ-SHOZHINGANALLUR,195,265000,"Additional Improvement Works to World Vision Room by Providing Borewell, Plumbing, Painting and Electrical works At Compost Yard in Kannagi Nagar Road in Dn- 195 U-45 Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11295,Buildings,Completed,NQ-SHOZHINGANALLUR,195,39000,MAINTAINES WORK AT OMR AMMA UNAVAGAM IN DN-195 UNIT-45 ZONE-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/11296,Buildings,Completed,NQ-SHOZHINGANALLUR,195,87000,IMPROVEMENT OF GYM AND HOSPITAL AT KANNAGI NAGAR IN DN-195 UNIT-45 ZONE-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/11297,Buildings,Completed,NQ-SHOZHINGANALLUR,195,46000,IMPROVEMENT OF CHRISTIAN BURIAL GROUND IN DN-195 UNIT-45 ZONE-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/11298,Buildings,Completed,NQ-SHOZHINGANALLUR,195,258000,MAINTAINES WORK AT COMPOST YARD KANNAGI NAGAR IN DN-195 UNIT-45 ZONE-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/1239,Buildings,Completed,NQ-SHOZHINGANALLUR,195,294000,"Proposed Construction of Material Recovery Facility in Compost Yard @ Kannagi Nagar 17th Main Road In Dn-195, U-45, Z15",Own Sources,15,2019-20,2019-20 NQ/2019-20/16094,Roads,Completed,NQ-SHOZHINGANALLUR,195,820000,"Forming and laying of BT road at Sowdeeswari nagar 4th cross street in Dn-195, U-45, Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/16095,Roads,Completed,NQ-SHOZHINGANALLUR,195,840000,"Forming and laying of BT road at Sakthi garden 4th cross street in Dn-195, U-45, Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17190,Roads,Completed,NQ-SHOZHINGANALLUR,195,312000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT Kannagi Nagar 12th main road IN DN-195,U-45,Z-15.",Grants,15,2019-20,2020-21 NQ/2019-20/17197,Roads,Completed,NQ-SHOZHINGANALLUR,195,239000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT Kannagi Nagar 66th Cross Street IN DN-195,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17202,Roads,Completed,NQ-SHOZHINGANALLUR,195,239000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KANNAGI NAGAR 67th CROSS STREET IN DN 195, U 45, Z15",Grants,15,2019-20,2020-21 NQ/2019-20/17203,Roads,Completed,NQ-SHOZHINGANALLUR,195,567000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KANNAGI NAGAR 6th MAIN ROAD IN DN 195 U 45,Z15",Grants,15,2019-20,2020-21 NQ/2019-20/17205,Roads,Completed,NQ-SHOZHINGANALLUR,195,756000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT PILLAYAR KOIL STREET IN-195,U-45,Z-15.",Grants,15,2019-20,2020-21 NQ/2019-20/17206,Roads,Completed,NQ-SHOZHINGANALLUR,195,1910000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT MADHA KOIL STREET IN-195,U-45,Z-15.",Grants,15,2019-20,2021-22 NQ/2019-20/17217,Roads,Completed,NQ-SHOZHINGANALLUR,195,483000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT SAKTHI GARDEN 2nd CROSS STREETIN DN-195,U-45,Z-15.",Grants,15,2019-20,2020-21 NQ/2019-20/17218,Roads,Completed,NQ-SHOZHINGANALLUR,195,97000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT SAKTHI GARDEN 3rd CROSS STREET IN DN-195,U-45,Z-15.",Grants,15,2019-20,2020-21 NQ/2019-20/17219,Roads,Completed,NQ-SHOZHINGANALLUR,195,1010000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT SOWDESHWARI NAGAR 2nd MAIN ROAD IN DN-195,U-45,Z-15.",Grants,15,2019-20,2021-22 NQ/2019-20/17220,Roads,Completed,NQ-SHOZHINGANALLUR,195,810000,"FORMING AND LAYING BT ROAD WITH PAVER FINISHER AT KANNAGI NAGAR 8th MAIN ROAD( WEST SIDE ) IN DN-195,U-45,Z-15.",Grants,15,2019-20,2020-21 NQ/2019-20/17288,Roads,Completed,NQ-SHOZHINGANALLUR,195,344000,RELAYING OF BT ROAD KANNAGI NAGAR 2ND CROSS STREET DIV-195 U-45 Z-15,Grants,15,2019-20,2021-22 NQ/2019-20/17390,Roads,Completed,NQ-SHOZHINGANALLUR,195,1828000,Relaying of BT Road at Kannagi Nagar 11th main road in div 195 unit 45 zone 15,Grants,15,2019-20,2021-22 NQ/2019-20/3476,Buildings,Completed,NQ-SHOZHINGANALLUR,195,1500000,"Improvement Work to Compost Yard and Construction of Toilet At Kannagi Nagar 17th Main Road in Div-195, U-45, Z-15,",Own Sources,15,2019-20,2019-20 NQ/2019-20/4471,Buildings,Completed,NQ-SHOZHINGANALLUR,195,63000,Providing Trash Arrest for Storm Water Drain B-Canal Disposal Point at Various location in Dn-195 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/5643,Buildings,Completed,NQ-SHOZHINGANALLUR,195,402000,"Proposed Rain Water Harvesting at Various Location in Div-195,Unit-45, Zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6637,Buildings,Completed,NQ-SHOZHINGANALLUR,195,346000,"Desilting of Storm water Drain At Various streets in Div-195, U-45 Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/6638,Buildings,Completed,NQ-SHOZHINGANALLUR,195,295000,"Minor Repair works and manhole At Various streets in Div-195, U-45 Z-15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/6885,Buildings,Completed,NQ-SHOZHINGANALLUR,195,164000,Improvements to Community Well at Annai Indra 1st Street In Div-195 Unit-45 Zone-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7083,Parks,Completed,NQ-SHOZHINGANALLUR,195,1188000,Abstract for Maintenance Estimate for Park at Annai Indra gandhi road (per Year ),Own Sources,15,2019-20,2020-21 NQ/2019-20/7084,Parks,Completed,NQ-SHOZHINGANALLUR,195,661000,Annual Maintenance for Park at Kannagi nagar 9th main road IN DN 195 U45 Z-15.,Own Sources,15,2019-20,2020-21 NQ/2019-20/7085,Parks,Completed,NQ-SHOZHINGANALLUR,195,633000,"Annual Maintenance for Park at Kannagi nagar 10th cross street in Dn.195 U-45, Z-15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/7086,Parks,Completed,NQ-SHOZHINGANALLUR,195,734000,"Annual Maintenance for Park at Kannagi nagar 2nd cross street in Dn-195, U-45,Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/7087,Parks,Completed,NQ-SHOZHINGANALLUR,195,680000,"Annual Maintenance for Park at Kannagi nagar 7th cross road ( 2adduku) in Dn-195 U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/7088,Parks,Completed,NQ-SHOZHINGANALLUR,195,728000,"Annual Maintenance for Park at Sowdeeswari nagar in Dn-195, U-45, Z-15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/7090,Parks,Completed,NQ-SHOZHINGANALLUR,195,1074000,"Annual Maintenance for Park at Sowdeeswari nagar (CTS O.M.R) in Dn-195,U-45, Z-15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/8002,Roads,Completed,NQ-SHOZHINGANALLUR,195,140000,ATTENDING OF PATCH WORK AT VARIOUS STREETS IN DN-195 UNIT-45 ZONE-15,Own Sources,15,2019-20,2020-21 B/2019-20/4623,Buildings,Completed,B-Buildings,196,4300000,"Supply, installation, testing, commissioning and maintenance for one year of Medical Gas systems in Urban Community Health Centre(100 Beds) at Injambakkam in Div-196 Zone-15",Grants,15,2019-20,2020-21 B/2019-20/4666,Buildings,Completed,B-Buildings,196,9920678,"Supply, Installation, Testing, Commissioning and Maintenance for one year of Fire Protection Systems in Urban Community Health Centre(100 Beds) at Injambakkam in Div-196 Zone-15",Grants,15,2019-20,2021-22 L/2019-20/3113,Electrical,Completed,L-Electrical,196,650300,"Provision of 13 Nos of 6/7 Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 13 Nos of 40-50w LED fittings at VGP Golden Beach Part II in Division -196, Injambakkam, Zone-XV",Own Sources,15,2019-20,2019-20 L/2019-20/8171,Electrical,Completed,L-Electrical,196,4731000,"Provision of 78 Nos of 6 Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 78 Nos of 40-50w watts LED fitting and 24 Nos of 6 Mtr Hot Dip Zinc galvanising street lamp post with Single Arch bracket with 24 Nos of 90-120w watts LED fitting at various location in dn-192,196 and 199 in Zone-XV",Grants,15,2019-20,2020-21 NQ/2019-20/10201,Roads,Completed,NQ-SHOZHINGANALLUR,196,140000,"Attending patch work at various location in Div-196,U-44,Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/10323,Buildings,Completed,NQ-SHOZHINGANALLUR,196,1096000,"Proposed construction of compound wall at infront of injambakkam 100 bed UCHC hospital Ration shop,post office,VOC and Ecr Road along sides,Name board compound wall in div-196,unit-44,zone-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11307,Roads,Completed,NQ-SHOZHINGANALLUR,196,140000,"Attending patch work at various location in Div-196,U-44,Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11308,Roads,Completed,NQ-SHOZHINGANALLUR,196,140000,"Attending patch work at various location in Div-196,U-44,Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11454,Buildings,Completed,NQ-SHOZHINGANALLUR,196,81000,"Improvements works to Division Office at VOC Street in Dn-196, U-44, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/16014,Roads,Completed,NQ-SHOZHINGANALLUR,196,2581000,"Forming and Laying of BT Road at V.G.P Layout 1st Cross Street in Dn-196,U-44,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/16015,Roads,Completed,NQ-SHOZHINGANALLUR,196,1566000,"Relaying of BT Road at Kamaraj street in Dn-196,U-44,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/16016,Roads,Completed,NQ-SHOZHINGANALLUR,196,1446000,"Relaying of BT Road at Ramalingam nagar 2nd street in Dn-196,U-44,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/16017,Roads,Completed,NQ-SHOZHINGANALLUR,196,715000,"Forming and Laying of BT Road at Hanuman Colony 2nd Cross Streetin Dn-196,U-44,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/16018,Roads,Completed,NQ-SHOZHINGANALLUR,196,1235000,"Relaying of BT Road at Ramalingam nagar Main Road in Dn-196,U-44,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/16859,Roads,Completed,NQ-SHOZHINGANALLUR,196,1064000,"Relaying of BT Road at Shalimar Garden 6th Street Extn in Division -196, Unit -44, Zone -15.",Grants,15,2019-20,2021-22 NQ/2019-20/16860,Roads,Completed,NQ-SHOZHINGANALLUR,196,529000,"Relaying of BT Road at Shalimar Garden 7th Street in Division -196, Unit -44, Zone -15.",Grants,15,2019-20,2021-22 NQ/2019-20/16928,Roads,Completed,NQ-SHOZHINGANALLUR,196,178000,"Relaying of BT Road at Prathana 3rd Cross Street in Division -196, Unit -44, Zone -15.",Grants,15,2019-20,2021-22 NQ/2019-20/16929,Roads,Completed,NQ-SHOZHINGANALLUR,196,668000,"Relaying of BT Road at Selva Nagar Main Road Extn in Division -196, Unit -44, Zone -15.",Grants,15,2019-20,2021-22 NQ/2019-20/16930,Roads,Completed,NQ-SHOZHINGANALLUR,196,707000,"Relaying of BT Road at Prathana Avenue Main Road in Division -196, Unit -44, Zone -15.",Grants,15,2019-20,2021-22 NQ/2019-20/16933,Roads,Completed,NQ-SHOZHINGANALLUR,196,1991000,"Relaying of BT Road at Kala Kuruthi Avenue Main Road in Division -196, Unit -44, Zone -15.",Grants,15,2019-20,2021-22 NQ/2019-20/4877,Buildings,Completed,NQ-SHOZHINGANALLUR,196,196000,"Proposed Rain Water Haresting at Various Street in div-196,Unit-44,Zone-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/5688,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,196,50000,"Providing Trash Arrester at Storm Water Drain in div-196,unit-44,Zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/5698,Buildings,Completed,NQ-SHOZHINGANALLUR,196,99000,"Desilting of SWD Drain Including Slab Refixing Work at Various Streets in Div-196, U-44, Z15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/6631,Buildings,Completed,NQ-SHOZHINGANALLUR,196,314000,"Minor Works to Side Drain at Boomphukar street and Providing Manhole Covers at Gowriamman koil 1st and 4th street in Dn-196, U-44 , Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/6921,Parks,Completed,NQ-SHOZHINGANALLUR,196,929000,Maintenance Work for Park at VGP layout 2nd street in Dn-196 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/8048,Roads,Completed,NQ-SHOZHINGANALLUR,196,240000,"Attending patch work at various location in Div-196,unit-44,zone-15.",Own Sources,15,2019-20,2020-21 B/2019-20/7245,Buildings,Completed,B-Buildings,197,3440000,"Construction of Compound wall, Waiting Shelter, UG sump (Drinking), Septic Tank and Laying of Paver Blocks in Urban Primary Health Center at Shozhinganallur in Div-197, Zone-15",Grants,15,2019-20,2020-21 L/2019-20/5250,Electrical,Completed,L-Electrical,197,885700,"Proposed to Painting of 2656 nos of 6 mtr lamp post with single straight bracket,614 nos of 6 mtr lamp post with single Arch bracket,115 nos of 8 mtr lamp post with Double straight bracket,40 nos of 8 mtr lamp post with Single Arch bracket,98 nos of Kiosk pillar box and 3425 nos of Numbering on the lamp post at Dn-197 and Dn-200 in zone-15.",Own Sources,15,2019-20,2020-21 L/2019-20/8364,Electrical,Completed,L-Electrical,197,4917700,"Provision of 74 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 74 Nos of 40-50w watts LED fitting and 27 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single Arch bracket with 27 Nos of 90-120w watts LED fitting at various location in dn-193,194,197,198 and 200 in Zone-XV",Grants,15,2019-20,2020-21 NQ/2019-20/10365,Roads,Completed,NQ-SHOZHINGANALLUR,197,2330000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-197 U-45 ZONE-XV.,Own Sources,15,2019-20,2020-21 NQ/2019-20/10429,Buildings,Completed,NQ-SHOZHINGANALLUR,197,163000,"Providing Aluminum Partition for ARO-II Office ( Revenue building) at Rajiv Gandhi salai in Div-197, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11112,Buildings,Completed,NQ-SHOZHINGANALLUR,197,110000,"Providing Hume pipe at Kuppusamy street & Providing chain link fencing at Gangaiamman koil street in Dn-197,U-45,Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/11301,Buildings,Completed,NQ-SHOZHINGANALLUR,197,2330000,"Providng Cement concrete pathway for Additional Compost Yard at Kuppusamy street in Div-197, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11446,Buildings,Completed,NQ-SHOZHINGANALLUR,197,80000,"Defacing of compound wall at Rajiv Gandhi salai & KK Salai in Div-197, U-45, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/11655,Buildings,Completed,NQ-SHOZHINGANALLUR,197,300000,"Construction of Material Recovery Facility Shed For Additional Compost Yard at Kuppusamy street in Div-197, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11656,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1180000,"Construction of Leach Pit Drain, Cross Culvert, Raising of Column & Weld Mesh for Additional Compost Yard at Kuppusamy street in Div-197, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11657,Buildings,Completed,NQ-SHOZHINGANALLUR,197,270000,"Construction of Platform for Compost Yard at Kuppusamy street in Div-197, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/1223,Buildings,Completed,NQ-SHOZHINGANALLUR,197,294000,"PROPOSED CONSTRUCTION OS MATERIAL RECOVERY FACILITY IN COMPOST YARD @ KUPPUSAMY STREET KARAPAKKAM IN DN 197 U-45,Z15",Own Sources,15,2019-20,2019-20 NQ/2019-20/16071,Roads,Completed,NQ-SHOZHINGANALLUR,197,1060000,"Forming and Laying of CC Road at Chinraj Street in Dn-197, U-45, Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/2431,Electrical,Completed,NQ-SHOZHINGANALLUR,197,207900,"Proposed Comprehensive annual maintanance contract for 9 Nos of 1 Ton Air Conditioner,7 Nos of 1.5 Ton Air Conditioner and 15 Nos of 2 Ton Air Conditioner units at Zonal office building and UPHCS in Zone-XV.",Own Sources,15,2019-20,2020-21 NQ/2019-20/2432,Electrical,Completed,NQ-SHOZHINGANALLUR,197,394200,"Proposed Comprehensive Annual Maintenance for 1 No 62.5 KVA Diesel Genset,1 No 30 KVA Diesel Genset and 1 No 5 KVA Mobile Diesel Genset at Zonal Office in Div-197 in Zone-XV.",Own Sources,15,2019-20,2020-21 NQ/2019-20/3424,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1440000,"Improvement Work to Compost Yard and Construction of Toilet at kuppusamy street in Dn 197 U-45,Zone 15",Own Sources,15,2019-20,2019-20 NQ/2019-20/3853,Buildings,Completed,NQ-SHOZHINGANALLUR,197,4920000,"Proposed Construction of Additional Compost yard at Kuppusamy street (inside Burial Ground) in Dn-197, U-45, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/3856,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1020000,"Providing Water Supply, Sump , Electrical and Machinery for Additional Compost Yard at Kuppusamy street in Dn-197, U-45 , Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/3920,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,1880000,Road Cut Restoration of BT Road at Classic Farm 1st cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3921,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,1990000,Road Cut Restoration of BT Road at Classic Farm 2nd cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3922,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,1980000,Road Cut Restoration of BT Road at Classic Farm 3rd cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2019-20 NQ/2019-20/3923,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,2080000,Road Cut Restoration of BT Road at Classic Farm 4th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2019-20 NQ/2019-20/3924,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,2140000,Road Cut Restoration of BT Road at Classic Farm 5th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2019-20 NQ/2019-20/3925,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,2470000,Road Cut Restoration of BT Road at Classic Farm 6th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3927,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,2150000,Road Cut Restoration of BT Road at Classic Farm 7th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3935,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,1680000,Road Cut Restoration of BT Road at Classic Farm 8th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2019-20 NQ/2019-20/3936,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,2900000,Road Cut Restoration of BT Road at Classic Farm 5th Main Road in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3937,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,1660000,Road Cut Restoration of BT Road at Classic Farm 9th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3938,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,1840000,Road Cut Restoration of BT Road at Classic Farm 10th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3939,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,940000,Road Cut Restoration of BT Road at Classic Farm 11th cross street in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3940,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,3180000,Road Cut Restoration of BT Road at Classic Farm 4th Main Road in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2019-20 NQ/2019-20/3941,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,2710000,Road Cut Restoration of BT Road at Classic Farm 2nd Main Road in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/3942,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,3360000,Road Cut Restoration of BT Road at Classic Farm 3rd Main Road in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/4111,Road Cut,Completed,NQ-SHOZHINGANALLUR,197,4990000,Restoration of Road Cut made by CMWSSB (Water supply and Sewerage line) CC road at Classic Farm 1st main road in Dn-197 U-45 Z-15,Deposit Works,15,2019-20,2020-21 NQ/2019-20/5488,Electrical,Completed,NQ-SHOZHINGANALLUR,197,542000,Proposed to Electrification and Replace of main board by Panel board and laying of 3-1/2 X 120 Sqmm Service cable at Zonal Office building in Dn-197 zone-15.,Own Sources,15,2019-20,2020-21 NQ/2019-20/5650,Buildings,Completed,NQ-SHOZHINGANALLUR,197,700000,"Proposed Rain Water Haresting at Various Location in div-197,Unit-45,Zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6068,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,224000,Desilting of Swd and Side Drain at Various Streets In Div-197 Unit-45 Zone-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/6315,Buildings,Completed,NQ-SHOZHINGANALLUR,197,1640000,Improvements to Community Well for Rain water Harvesting at Various Location In Div-197 Unit-45 Zone-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/6609,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,1090000,Improvements to Storm Water Drain and Side Drain & Providing Cross Culvert at Various Streets In Div-197 Unit-45 Zone-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/6917,Parks,Completed,NQ-SHOZHINGANALLUR,197,950000,Maintenance work for Park at Kumarasamy Nagar 6th street Park (per year) in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6924,Parks,Completed,NQ-SHOZHINGANALLUR,197,700000,Maintenance work for Park at Kumarasamy Nagar Main Road west in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6926,Parks,Completed,NQ-SHOZHINGANALLUR,197,640000,Maintenance work for Park at Kumarasamy Nagar Main Road (North) in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6930,Parks,Completed,NQ-SHOZHINGANALLUR,197,639000,Maintenance work for Park at Elcot Avenue 1st street in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6934,Parks,Completed,NQ-SHOZHINGANALLUR,197,650000,Maintenance work for Park at Neduncheliyan street in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6936,Parks,Completed,NQ-SHOZHINGANALLUR,197,989000,Maintenance work for Park at Devaraj nagar 2nd main road park in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6940,Parks,Completed,NQ-SHOZHINGANALLUR,197,854000,Maintenance work for Park at Rajiv Gandhi salai Techi park in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6942,Parks,Completed,NQ-SHOZHINGANALLUR,197,1280000,Maintenance work for Park at New kumaran nagar 2nd main road in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6950,Parks,Completed,NQ-SHOZHINGANALLUR,197,660000,Maintenance work for Park at Rajiv Gandhi salai (Near Divyashree point ) Dollor in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6953,Parks,Completed,NQ-SHOZHINGANALLUR,197,650000,Maintenance work for Park at Sadagoppan street in Dn-197 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/8050,Roads,Completed,NQ-SHOZHINGANALLUR,197,710000,"Patch Work at Various Streets In Div-197, U-45, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/8591,Buildings,Completed,NQ-SHOZHINGANALLUR,197,310000,Providing Bore well and pipe line arrangements at Neduncheliyan street Public Convenience inside of Shpping complex In Div-197 Unit-45 Zone-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/8718,Buildings,Completed,NQ-SHOZHINGANALLUR,197,480000,"Supply of 100 Kg to 150Kg Multiple baling Press machine, Transportation, Erection and Commissioning, Fitting Charges 2 Coats of Zinc chrome, 2 coats of poly Urethane paint including 18% GST etc.. Complete at Compost yard Kuppusamy Street, Karapakkam in Div - 197, Unit - 45, Zone - 15",Own Sources,15,2019-20,2019-20 NQ/2019-20/9099,Buildings,Completed,NQ-SHOZHINGANALLUR,197,980000,"Dismantling and construction of Compound wall at Zonal office Building in Dn-197, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/9456,Electrical,Completed,NQ-SHOZHINGANALLUR,197,649000,"Supply and Installation of P A system,2 nos of 2 TON Air conditioner and additional Electrification for Conference hall at Zonal Office building in Dn-197 zone-15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/9697,Roads,Completed,NQ-SHOZHINGANALLUR,197,850000,"Raising the Platform for community hall at Kajarajan street in Dn-197,U-45,Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/9698,Buildings,Completed,NQ-SHOZHINGANALLUR,197,660000,"Raising Platform in Division office at Gangaiamman koil street in Dn-197,U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/9773,Buildings,Completed,NQ-SHOZHINGANALLUR,197,207000,"Improvements to Public convenience at periyapalayathamman koil street, kaliamman koil street, Gangaiamman koil street,Neduncheliyan street inside of shopping complex & model school road in Dn-197,U-45,Z-15",Own Sources,15,2019-20,2020-21 L/2019-20/10764,Electrical,Completed,L-Electrical,198,10645500,Provision of 101 Nos of 8 MTR LONG G.I OCTAGONAL STREET LAMP POLE WITH G.I Single bracket with 101 Nos of 150-165w watts LED fitting at TNHB 'A' Road from C2 Road junction to Pandiyan Kudi irruppu Road juntion and to replace of 4 nos of single straight bracket with 40-50W LED fitting into 4 nos of GI Single Arch bracket with 90-120W LED fittings in junctions of B4 and B6 Roads jn roads in dn-198 in Zone-XV.,Own Sources,15,2019-20,2021-22 L/2019-20/3460,Electrical,Completed,L-Electrical,198,873300,"Provision of 4 nos of 8 mtr OCTAGONAL Street lamp pole with DOUBLE BRACKET WITH Hot dip zinc galvanising with 8 nos of 150 to 165 W LED Fittings and 9 nos of 6 mtr GI Street lamp pole with Single Straight Bracket WITH Hot dip zinc galvanising with 9 nos of 40 to 50 W LED Fittings at Sai Illam Extn,Juhu Beach Road,Nookampalayam Link road in Dn-198,199 and 200 in Zone-XV",Own Sources,15,2019-20,2019-20 L/2019-20/5254,Electrical,Completed,L-Electrical,198,687300,"Proposed to Painting of 2422 nos of 6 mtr lamp post with single straight bracket,273 nos of 6 mtr lamp post with single Arch bracket,63 nos of 8 mtr lamp post with Double Arch bracket,3 nos of 8 mtr lamp post with Triple Arch bracket,56 nos of Kiosk pillar box and 2761 nos of Numbering on the lamp post in Dn-198 zone-15.",Own Sources,15,2019-20,2020-21 NQ/2019-20/1011,Roads,Completed,NQ-SHOZHINGANALLUR,198,2360000,Forming and Laying of BT Road at Seshadri Main Street in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/10205,Buildings,Completed,NQ-SHOZHINGANALLUR,198,2000000,"Construction of Gym Building with Gym Equipments at Padavattamman Koil 1st street Park (Under MLA Fund 2019-20) in Dn-198, U-44, Z-15",MLACDS,15,2019-20,2020-21 NQ/2019-20/10690,Buildings,Completed,NQ-SHOZHINGANALLUR,198,388000,"Providing Barricading Arrangements During Pongal Festival Using Casurina Pole e.t.c., at Beach and Aproach Roads in Divisions of Unit-44, Zone-XV.",Own Sources,15,2019-20,2019-20 NQ/2019-20/11283,Buildings,Completed,NQ-SHOZHINGANALLUR,198,980000,Improvement Works to Compost Yard by Providing Platform and fencing works At TNHB B6 Burial Ground in Dn- 198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/11400,Buildings,Completed,NQ-SHOZHINGANALLUR,198,444000,Proposed Open gym at Annai indira Nagar Park Size 9.00 m X 4.00 m = 99.00 m2 in Div -198 U-44 Zone -15,Own Sources,15,2019-20,2020-21 NQ/2019-20/1188,Buildings,Completed,NQ-SHOZHINGANALLUR,198,294000,"Proposed Construction of Material Recovery Facility in Compost Yard at Hindhu Mayana Pathai Burial Ground in Dn-198, U-44, Z15.",Own Sources,15,2019-20,2019-20 NQ/2019-20/1213,Roads,Completed,NQ-SHOZHINGANALLUR,198,2498000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-198 U-44 ZONE-XV.,Own Sources,15,2019-20,2020-21 NQ/2019-20/13166,Buildings,Completed,NQ-SHOZHINGANALLUR,198,247000,"Supplying and erecting 37 Nos of Leaves Dumping cylindrical storage container lid at various locations in Division - 198, Unit - 44, Zone -XV",Own Sources,15,2019-20,2020-21 NQ/2019-20/1317,Roads,Completed,NQ-SHOZHINGANALLUR,198,2417000,Forming and Laying of BT Road at Vrishabadri main Street in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/1327,Roads,Completed,NQ-SHOZHINGANALLUR,198,1210000,Forming and Laying of BT Road at Garudadri Mian Street in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/1332,Roads,Completed,NQ-SHOZHINGANALLUR,198,961000,Forming and Laying of BT Road at Adinath Main Street in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/1338,Roads,Completed,NQ-SHOZHINGANALLUR,198,893000,Forming and Laying of BT Road at Anjanadri Main Street in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/13425,Buildings,Completed,NQ-SHOZHINGANALLUR,198,426000,"Construction of New Cremation Yard at TNHB B6 Burial Ground in Dn-198, U-44, Z-15",Own Sources,15,2019-20,2021-22 NQ/2019-20/1348,Roads,Completed,NQ-SHOZHINGANALLUR,198,9706000,Forming and Laying of BT Road at Alamelumangapuram Main Road in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/1351,Roads,Completed,NQ-SHOZHINGANALLUR,198,1994000,Forming and Laying of BT Road at Copper beach 1st street in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/1353,Roads,Completed,NQ-SHOZHINGANALLUR,198,5429000,Forming and Laying of BT Road at Kudimiyandithoppu school street in Dn-198 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/14533,Parks,Completed,NQ-SHOZHINGANALLUR,198,406000,Improvement and Repair Works to MGR Nagar Children Play Space in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/15704,Buildings,Completed,NQ-SHOZHINGANALLUR,198,847000,"IMPROVEMENTS WORKS TO RELIF CENTRE (TSUNAMI BUILDING) AT KUDIMIYANDI THOPPU SCHOOL STREET IN DN-198,U-44,Z-15",Own Sources,15,2019-20,2021-22 NQ/2019-20/17510,Roads,Completed,NQ-SHOZHINGANALLUR,198,4382000,"Forming and Laying of C.C..Road at Lilly pond 1st Street in div-198,unit-44,Zone-15",Grants,15,2019-20,2020-21 NQ/2019-20/17522,Roads,Completed,NQ-SHOZHINGANALLUR,198,4799000,"Forming and Laying of C.C Road at Lilly pond main street in div-198,unit-44,Zone-15",Grants,15,2019-20,2020-21 NQ/2019-20/3308,Buildings,Completed,NQ-SHOZHINGANALLUR,198,690000,"Improvements to Compost Yard at Hindhu Mayana Pathai in Div-198,Unit-44,Zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/3986,Buildings,Completed,NQ-SHOZHINGANALLUR,198,90000,"Repair Works to Toilet at Panaiyur Kuppam Gents, Panaiyur Kuppam Ladies (south), Panaiyur Kuppam Ladies (North), Kudimiyandi Thoppu School street, Rajiv Gandhi Nagar, Sathiyavanimuthu street, Parameshwaran nagar street in Dn-198 U-44 Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/4253,Buildings,Completed,NQ-SHOZHINGANALLUR,198,245000,"Providing Rain Water Harvesting at Various Location in Dn-198, U-44, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/4544,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,198,48000,"Desilting to Side Drain at Rajiv Gandhi Nagar & Sathiyavanimuthu street in Dn-198 , U-44 ,Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/4546,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,198,263000,"Providing Cross Culvert at Sathiyavanimuthu street & Providing Hume pipe at Uma mageshwari Avenue in Dn-198, U-44 , Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/6246,Roads,Completed,NQ-SHOZHINGANALLUR,198,630000,Laying of BT Road at Sea Cliff approach in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/6553,Buildings,Completed,NQ-SHOZHINGANALLUR,198,950000,"Improvements for Community Well located at TNHB D1,D3,D5 & D3 OSR In Dn-198 U-44 Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6561,Buildings,Completed,NQ-SHOZHINGANALLUR,198,990000,"Improvements for Community Well located at Padavattamman koil 3rd street Ration Shop, Sathiyavanimuthu 2nd street,Parameshwaran Nagar Main Street,Golden Shore avenue In Dn-198 U-44 Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6577,Buildings,Completed,NQ-SHOZHINGANALLUR,198,600000,Improvements for Community Well located at TNHB B1 & B1 OSR in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/6719,Buildings,Completed,NQ-SHOZHINGANALLUR,198,500000,"Improvements to Side Drain at Sathiyavanimuthu street & Proposed Culvert at TNHB in Dn-198, U-44 , Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6731,Buildings,Completed,NQ-SHOZHINGANALLUR,198,780000,"Improvements to Side Drain at Rajiv Gandhi nagar 1st & 2nd streets in Dn-198, U-44 , Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6733,Buildings,Completed,NQ-SHOZHINGANALLUR,198,850000,"Improvements to Side Drain at Rajiv Gandhi nagar 3rd & 4 streets in Dn-198, U-44 , Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6928,Parks,Completed,NQ-SHOZHINGANALLUR,198,953000,Annual Maintenance Work for Park at VGP 2nd main road (sea cliff) in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6931,Parks,Completed,NQ-SHOZHINGANALLUR,198,914000,Annual Maintenance Work for Park at TNHB E12 in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6933,Parks,Completed,NQ-SHOZHINGANALLUR,198,1301000,Annual Maintenance Work for Park at TNHB B6 Road in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6935,Parks,Completed,NQ-SHOZHINGANALLUR,198,603000,Annual Maintenance Work for Park at TNHB C6 Road in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6937,Parks,Completed,NQ-SHOZHINGANALLUR,198,642000,Annual Maintenance Work for Park at TNHB E17 Road in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6939,Parks,Completed,NQ-SHOZHINGANALLUR,198,639000,Annual Maintenance Work for Park at Pondichery pattai Road in Dn-198 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/8009,Roads,Completed,NQ-SHOZHINGANALLUR,198,290000,"Attending Patch Work at Various street in Div-198, U-44, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/8488,Buildings,Completed,NQ-SHOZHINGANALLUR,198,308000,"Additional Improvement Works by Providing Weld mesh gate, Plumbing and Electrical works At Compost Yard at TNHB B6 Road in Dn- 198 U-44 Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/8620,Roads,Completed,NQ-SHOZHINGANALLUR,198,1580000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-198 U-44 ZONE-XV.,Own Sources,15,2019-20,2020-21 NQ/2019-20/9565,Buildings,Completed,NQ-SHOZHINGANALLUR,198,108000,Repair works on Street Furniture by Providing Sticker and Attending CC Patch in Div-198 U-44 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/11312,Buildings,Completed,NQ-SHOZHINGANALLUR,199,204000,Providing of Kabadi playground at Nainar Kuppam in Div-199 U-44 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/11369,Buildings,Completed,NQ-SHOZHINGANALLUR,199,12000,Defacing At Private Compound Wall In East Cost Road At UTHANDI DIV-199 U-44 Z-15.,Own Sources,15,2019-20,2019-20 NQ/2019-20/16020,Roads,Completed,NQ-SHOZHINGANALLUR,199,8605000,Forming and Laying of BT Road at VGP Gandhi 1st main road in Dn-199 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/16021,Roads,Completed,NQ-SHOZHINGANALLUR,199,2832000,Forming and Laying of BT Road at VGP Gandhi 2nd main road Dn-199U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/16045,Roads,Completed,NQ-SHOZHINGANALLUR,199,2940000,Forming and Laying of BT Road at VGP Gandhi 3rd main road in Dn-199 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/16046,Roads,Completed,NQ-SHOZHINGANALLUR,199,528000,Forming and Laying of BT Road at VGP Gandhi 1st Cross street road in Dn-199 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/16047,Roads,Completed,NQ-SHOZHINGANALLUR,199,580000,Forming and Laying of BT Road at VGP Gandhi 2nd Cross in Dn-199 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/16048,Roads,Completed,NQ-SHOZHINGANALLUR,199,687000,Forming and Laying of BT Road at VGP Gandhi 3rd cross street in Dn-199 U-44 Z-15,Grants,15,2019-20,2020-21 NQ/2019-20/17248,Roads,Completed,NQ-SHOZHINGANALLUR,199,1998000,"Restoration of Roadcut (CMWSSB) and Relaying for cement concrete Road at Periyar street in div-199,Unit-44,Zone-15",Grants,15,2019-20,2020-21 NQ/2019-20/17722,Roads,Completed,NQ-SHOZHINGANALLUR,199,970000,"Restoration of Roadcut (CMWSSB) and Relaying for cement concrete Road at Gaingai amman Koil street (East) in div-199,Unit-44,Zone-15",Grants,15,2019-20,2020-21 NQ/2019-20/6922,Parks,Completed,NQ-SHOZHINGANALLUR,199,729000,Maintenance Works for Park at VGP 2nd main road in Dn-199 U-44 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/9104,Buildings,Completed,NQ-SHOZHINGANALLUR,199,157000,"IMPROVEMENT AND REPAIR WORK FOR BIO TOILET AT V.G.P 2nd MAIN ROAD IN DN-199, U-44, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/9783,Buildings,Completed,NQ-SHOZHINGANALLUR,199,127000,PROVIDING STREET FURNITURES AT VARIOUS STREETS IN DIVISION-199 U-44 Z-15.,Own Sources,15,2019-20,2019-20 BR/2019-20/18104,Roads,Completed,BR-Bus Route Roads,200,2000000,"Relaying the road with DBM and BC along with traffic improvement work at Nookampalayam Road in Dn- 200, Zone - 15",Grants,15,2019-20,2020-21 NQ/2019-20/11013,Buildings,Completed,NQ-SHOZHINGANALLUR,200,8400,"Improvements For Public Convinience at TNSCB 7th Avenue in Div-200, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11018,Buildings,Completed,NQ-SHOZHINGANALLUR,200,67000,"Improvements For Public Convinience at Jawagar Nagar & Ezhilmuga Nagar in Div-200, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11024,Buildings,Completed,NQ-SHOZHINGANALLUR,200,118000,"Improvements For Public Convinience Veeravanjinathan Street in Div-200, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11084,Buildings,Completed,NQ-SHOZHINGANALLUR,200,108000,"Improvements For Public Convinience Pondicherry Paatai Salai in Div-200, U-45, Z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/11300,Buildings,Completed,NQ-SHOZHINGANALLUR,200,240000,"Improvements to Side Drain at TNSCB 9th Avenue and TNSCB 2nd Main Road in Div-200, U-45, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/11375,Buildings,Completed,NQ-SHOZHINGANALLUR,200,419000,Providing Machine Shed for Compost Yard at TNSCB 2nd main Road in Div-200 U-45 Zone - XV,Own Sources,15,2019-20,2020-21 NQ/2019-20/11376,Buildings,Completed,NQ-SHOZHINGANALLUR,200,260000,"Improvements to Compost yard for Additional work at TNSCB 2nd Main Road Chemmanchery in DN-200,U-45, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/1194,Buildings,Completed,NQ-SHOZHINGANALLUR,200,294000,"Proposed Construction of Material Recovery Facility in Compost Yard @ 9th Avenue Tsunami Nagar Semmencherry in Dn 200, U45, Z15",Own Sources,15,2019-20,2019-20 NQ/2019-20/17505,Roads,Completed,NQ-SHOZHINGANALLUR,200,497000,"Forming and Laying of CC Road at Retaimalai Srinivasan street in DN-200,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17506,Roads,Completed,NQ-SHOZHINGANALLUR,200,2594000,"Forming and Laying of CC Road at City Limit Road (Near TNSCB Tenentments) in Dn-200,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17507,Roads,Completed,NQ-SHOZHINGANALLUR,200,410000,"Forming and Laying of CC Road at Kattabomman Street in Dn-200,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17508,Roads,Completed,NQ-SHOZHINGANALLUR,200,1946000,"Forming and Laying of CC Road at Veeravanjinathan Salai Link in Dn-200,U-45,Z-15",Grants,15,2019-20,2020-21 NQ/2019-20/17513,Roads,Completed,NQ-SHOZHINGANALLUR,200,234000,"Relaying of BT Road at TNSCB 4th Main Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17514,Roads,Completed,NQ-SHOZHINGANALLUR,200,256000,"Relaying of BT Road at TNSCB 5th Main Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17524,Roads,Completed,NQ-SHOZHINGANALLUR,200,266000,"Relaying of BT Road at TNSCB 4th Avenue Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17525,Roads,Completed,NQ-SHOZHINGANALLUR,200,266000,"Relaying of BT Road at TNSCB 5th Avenue Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17526,Roads,Completed,NQ-SHOZHINGANALLUR,200,266000,"Relaying of BT Road at TNSCB 6th Avenue Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17527,Roads,Completed,NQ-SHOZHINGANALLUR,200,275000,"Relaying of BT Road at TNSCB 8th Avenue Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17530,Roads,Completed,NQ-SHOZHINGANALLUR,200,106000,"Relaying of BT Road at TNSCB 2nd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17531,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 3rd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17534,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 6th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17538,Roads,Completed,NQ-SHOZHINGANALLUR,200,69000,"Relaying of BT Road at TNSCB 10th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17541,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 12th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17542,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 13th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17544,Roads,Completed,NQ-SHOZHINGANALLUR,200,191000,"Relaying of BT Road at TNSCB 15th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17545,Roads,Completed,NQ-SHOZHINGANALLUR,200,41000,"Relaying of BT Road at TNSCB 16th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17546,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 17th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17551,Roads,Completed,NQ-SHOZHINGANALLUR,200,48000,"Relaying of BT Road at TNSCB 22nd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17559,Roads,Completed,NQ-SHOZHINGANALLUR,200,191000,"Relaying of BT Road at TNSCB 30th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17560,Roads,Completed,NQ-SHOZHINGANALLUR,200,85000,"Relaying of BT Road at TNSCB 31st Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17564,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 35th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17565,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 36th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17567,Roads,Completed,NQ-SHOZHINGANALLUR,200,133000,"Relaying of BT Road at TNSCB 38th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17568,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 39th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17574,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 46th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17579,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 51st Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17580,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 52nd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17583,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 55th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17584,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 56th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17592,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 64th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17593,Roads,Completed,NQ-SHOZHINGANALLUR,200,135000,"Relaying of BT Road at TNSCB 65th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17595,Roads,Completed,NQ-SHOZHINGANALLUR,200,64000,"Relaying of BT Road at TNSCB 67th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17598,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 70th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17599,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 71st Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17604,Roads,Completed,NQ-SHOZHINGANALLUR,200,48000,"Relaying of BT Road at TNSCB 76th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17606,Roads,Completed,NQ-SHOZHINGANALLUR,200,212000,"Relaying of BT Road at TNSCB 78th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17607,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 79th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17608,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 80th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17610,Roads,Completed,NQ-SHOZHINGANALLUR,200,234000,"Relaying of BT Road at TNSCB 82nd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17611,Roads,Completed,NQ-SHOZHINGANALLUR,200,117000,"Relaying of BT Road at TNSCB 83rd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17612,Roads,Completed,NQ-SHOZHINGANALLUR,200,48000,"Relaying of BT Road at TNSCB 84th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17616,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 88th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17617,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 89th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17620,Roads,Completed,NQ-SHOZHINGANALLUR,200,47000,"Relaying of BT Road at TNSCB 92nd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17621,Roads,Completed,NQ-SHOZHINGANALLUR,200,52000,"Relaying of BT Road at TNSCB 93rd Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17623,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 95th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17624,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 96th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17625,Roads,Completed,NQ-SHOZHINGANALLUR,200,37000,"Relaying of BT Road at TNSCB 97th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17626,Roads,Completed,NQ-SHOZHINGANALLUR,200,42000,"Relaying of BT Road at TNSCB 98th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17627,Roads,Completed,NQ-SHOZHINGANALLUR,200,45000,"Relaying of BT Road at TNSCB 99th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/17628,Roads,Completed,NQ-SHOZHINGANALLUR,200,48000,"Relaying of BT Road at TNSCB 100th Cross Road in Dn-200,U-45,Z-15",Grants,15,2019-20,2021-22 NQ/2019-20/3433,Buildings,Completed,NQ-SHOZHINGANALLUR,200,1590000,"Improvements for compost yard at TNSCB 2nd Main Road Chemmancherry in DN-200, U-45, Zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/4083,Buildings,Completed,NQ-SHOZHINGANALLUR,200,156000,Providing Trash Arrest for Storm Water Drain B-Canal Disposal Point at Various location in Dn-200 U-45 Z-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/5651,Buildings,Completed,NQ-SHOZHINGANALLUR,200,220000,"Proposed Rain Water Harvesting at Various Location in div-200,Unit-45,Zone-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/6069,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,199000,DESILTING OF SWD AND SIDE DRAIN AT VARIOUS STREETS IN DIVISION-200 UNIT-45 ZONE-XV.,Own Sources,15,2019-20,2019-20 NQ/2019-20/6314,Buildings,Completed,NQ-SHOZHINGANALLUR,200,590000,Improvements to Community Well for Rain water Harvesting at Various Location In Div-200 Unit-45 Zone-15,Own Sources,15,2019-20,2019-20 NQ/2019-20/6610,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,1660000,IMPROVEMENTS TO STORM WATER DRAIN AND SIDE DRAIN & PROVIDING CROSS CULVERT AT VARIOUS STREETS IN DIVISION-200 UNIT-45 ZONE-XV.,Own Sources,15,2019-20,2019-20 NQ/2019-20/6956,Parks,Completed,NQ-SHOZHINGANALLUR,200,640000,Maintenance Work for Park at TNSCB 33rd cross street in Dn-200 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/6957,Parks,Completed,NQ-SHOZHINGANALLUR,200,1250000,Maintenance work for Park at TNSCB 1st Main road in Dn-200 U-45 Z-15,Own Sources,15,2019-20,2020-21 NQ/2019-20/7283,Parks,Completed,NQ-SHOZHINGANALLUR,200,680000,"Maintenance Estimate For Park at TNSCB 2nd Main Road in Div-200, u-45, z-15",Own Sources,15,2019-20,2020-21 NQ/2019-20/7962,Roads,Completed,NQ-SHOZHINGANALLUR,200,519000,"Patch Work in Div-200, U-45, Z-15",Own Sources,15,2019-20,2019-20 NQ/2019-20/9094,Roads,Completed,NQ-SHOZHINGANALLUR,200,650000,PROVIDING SPEED BREAKER WITH IRC SPECIFICATION INCLUDING CAUTION BOARD THERMO PLASTIC PAINT AND STUDS AT VARIOUS STREETS IN DIV-200 U-45 ZONE-XV.,Own Sources,15,2019-20,2020-21 NQ/2019-20/9633,Buildings,Completed,NQ-SHOZHINGANALLUR,200,53000,"Improvements For Public Convenience at Panchayath Saaalai in Div-200, U-45, Z-15",Own Sources,15,2019-20,2020-21 BR/2019-20/11159,Roads,Completed,BR-Bus Route Roads,,836000,"PROVIDING AND LAYING HOT APPLIED THERMOPLASTIC PAINT DUE TO JAN 26TH REPUBLIC DAY FUNCTION FOR THE YEAR 2020 AT KAMARAJAR SALAI(MARINA) AND RADHAKRISHANAN SALAI IN DN - 116,114,121 AND 125 IN ZONE-9",Own Sources,Central Region,2019-20,2020-21 BR/2019-20/11239,Roads,Completed,BR-Bus Route Roads,,990000,"PROVIDNG AND LAYING HOT APPLIED THERMOPLASTIC PAINT DUE TO JAN 26TH REPUBLIC DAY FUNCTION FOR THE YEAR 2020 AT KAMARAJAR SALAI(MARINA) IN DN - 116,114,121 AND 125 IN ZONE-9",Own Sources,Central Region,2019-20,2020-21 BR/2019-20/17539,Road Cut,Completed,BR-Bus Route Roads,,945000,"Restoration of OFC Roadcut 14 Nos of Various Bus Route Roads in Div-64,73,92,93.101,103&106, Zone -6 & 7",Deposit Works,Central Region,2019-20,2020-21 BR/2019-20/8301,Roads,Completed,BR-Bus Route Roads,,870000,"Repairs and Rectification of damaged Modern Stainless Steel Bus Shleters in Various Bus Route Roads in Zone -6,7,9 & 10.",Own Sources,Central Region,2019-20,2020-21 BR/2019-20/8302,Roads,Completed,BR-Bus Route Roads,,975000,"Removing and Refixing of Bus Shelters in Various Bus Route Roads in Zone 7, 8,& 9.",Own Sources,Central Region,2019-20,2020-21 B/2019-20/3051,Buildings,Completed,B-Buildings,,2084000,SUPPLYING AND FIXING OF FURNITURE FOR URBAN COMMUNITY HEALTH CENTER IN THIRUVOTTRIYUR,Own Sources,Greater Chennai Corporation,2019-20,2020-21 B/2019-20/3278,Buildings,Completed,B-Buildings,,2108000,SUPPLYING AND FIXING OF FURNITURE FOR URBAN PRIMARY HEALTH CENTER IN MADHAVARAM,Own Sources,Greater Chennai Corporation,2019-20,2019-20 B/2019-20/3281,Buildings,Completed,B-Buildings,,2126000,SUPPLYING AND FIXING OF FURNITURE FOR URBAN PRIMARY HEALTH CENTER IN THIRUVOTTIYUR AND MADHAVARAM,Own Sources,Greater Chennai Corporation,2019-20,2019-20 B/2019-20/4059,Buildings,Completed,B-Buildings,,973000,"PROVIDING RAIN WATER HARVESTING AT RIPON BUILDING IN DIV-58, ZONE-5",Own Sources,Greater Chennai Corporation,2019-20,2020-21 B/2019-20/4110,Buildings,Completed,B-Buildings,,2150000,"CONSTRUCTION OF DIVISION OFFICE IN SECOND FLOOR OF URBAN PRIMARY HEALTH CENTER AT MALLIGAPURAM IN DIVISION-14, ZONE-1",Own Sources,Greater Chennai Corporation,2019-20,2021-22 B/2019-20/6818,Buildings,Completed,B-Buildings,,1730000,"CONSTRUCTION OF DIVISION OFFICE IN SECOND FLOOR OF URBAN PRIMARY HEALTH CENTER AT THIRUVOTTIYUR DIVISION-11,ZONE-1",Own Sources,Greater Chennai Corporation,2019-20,2020-21 J/2019-20/10794,Overbridges,Completed,J-Bridges,,305093,"Repair and Maintenance work at Uthamar Gandhi Salai in existing (Murasolimaran)Foot Over Bridge in Dn -113,Zone-09.",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/10797,Subway,Completed,J-Bridges,,50000,Wearing coat patches attended at Subways in Center Region.,Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/14600,Bridges,Completed,J-Bridges,,3127000,"Providing vertical garden with STP for existing Flyover at junction of Sardar Patel Road and Gandhi Mandapam Road in Dn -171&172, Zone-13",Own Sources,Greater Chennai Corporation,2019-20,2021-22 J/2019-20/8489,Bridges,Completed,J-Bridges,,276000,"Repair the existing Steel bridge across Puzhal surplus canal at Burma Nagar, in Dn-16, Zone-II",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8507,Bridges,Completed,J-Bridges,,268000,"Repair the existing Steel bridge across Puzhal surplus canal at Sadyan kuppam, in Dn-16, Zone-II",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8547,Grade Separator,Completed,J-Bridges,,611000,"Providing name Board & Traffic sign board for Existing Flyover at Purasawalkkam High Road - Perambur Barracks Road Junction in Div- 58, Zone-V",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8589,Bridges,Completed,J-Bridges,,316000,Removal of Rank Vegetaion at Various bridges and Subways in North region (Zone -1 to 5),Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8757,ROB,Completed,J-Bridges,,996000,"Repair the embankment and painting the existing Gandhi irwin road bridge in Dn-61, Zone-V",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8760,Bridges,Completed,J-Bridges,,591000,"Providing gate and raising of Retaining wall at Thoppai vinayagar koil st in Dn -41, Zone -IV",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8766,RUB,Completed,J-Bridges,,96000,"Providing name Board and Relaying of wearing coat patches in M.C Road Div- 52, Zone-V",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8770,Grade Separator,Completed,J-Bridges,,189000,"Painting the centre median and Providing name Board & Traffic sign board in Mint bridge, Div- 53, Zone-V",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/8773,RUB,Completed,J-Bridges,,85100,"Repair staircase Hand rail and Relaying of wearing coat patches in RBI Subway in Div- 60, Zone-V",Own Sources,Greater Chennai Corporation,2019-20,2019-20 J/2019-20/9609,Bridges,Completed,J-Bridges,,4395000,"Providing vertical garden with STP for existing Grade Separator at Vallar Nagar at Mint junction in Dn -53, Zone-V",Grants,Greater Chennai Corporation,2019-20,2021-22 J/2019-20/9614,Bridges,Completed,J-Bridges,,10786000,"Providing Vertical Garden with STP for existing flyover at Perambur road junction in Dn-7071,Zone-VI",Grants,Greater Chennai Corporation,2019-20,2021-22 J/2019-20/9615,Bridges,Completed,J-Bridges,,3392000,"Providing vertical garden with STP for existing flyover at Doveton junction in Dn -58, Zone-V",Grants,Greater Chennai Corporation,2019-20,2021-22 J/2019-20/9621,Bridges,Completed,J-Bridges,,3746000,"Providing vertical garden with STP for existing flyover at Casa major road junction in Dn -58, Zone-V",Grants,Greater Chennai Corporation,2019-20,2021-22 J/2019-20/9624,Bridges,Completed,J-Bridges,,4454000,"Providing vertical garden with STP for existing Flyover at junction of Sardar Patel Road and L.B.Road in Dn -175&176, Zone-13",Grants,Greater Chennai Corporation,2019-20,2021-22 B/2019-20/1037,Buildings,Completed,B-Buildings,,2885000,"Retrofitting and Lifting the existing School lab building at CGHSS 540, T.H Road at Old Washermenpet in ward-42, Zone-4.",Own Sources,4,2019-20,2020-21 B/2019-20/9742,Buildings,Completed,B-Buildings,,3412585,"Construction of Anganwadi Building (ICDS CENTER NO. 33603010220) at Venkatakrishnan Street , Old Washermenpet in Dn-48,Zone-4",MLACDS,4,2019-20,2021-22 D/2019-20/4005,Storm Water Drain,Completed,D-Storm Water Drains,,39900000,"Construction of Missing Link Storm Water Drain at Ganpathy Street,Krishnamoorthy Nagar,Palani Street and 8 other roads in Dn. 37,38 & 46 Zone -4,Package - 1.",SMART CITY - SWD,4,2019-20,2021-22 D/2019-20/4018,Storm Water Drain,Completed,D-Storm Water Drains,,49770000,"Construction of Missing Link Storm Water Drain at Cochraine Basin under ground sump and 9 other roads in Dn. 53,54,56,59&60,Zone - 5, Package -2.",SMART CITY - SWD,5,2019-20,2020-21 D/2019-20/4019,Storm Water Drain,Completed,D-Storm Water Drains,,24560000,"Construction of Missing Link Storm Water Drain at V.V.Nagar 2nd and 5th street and 3 other roads in Dn. 63,113 & 117,,Zone - 6 & 9, Package -3.",SMART CITY - SWD,9,2019-20,2020-21 D/2019-20/4024,Storm Water Drain,Completed,D-Storm Water Drains,,47330000,"Construction of Missing Link Storm Water Drain at Jai Nagar 8th street and 2nd main road (part) and 7 other roads in Dn. 127,128,129 & 132,,Zone - 10, Package -4.",SMART CITY - SWD,10,2019-20,2020-21 B/2019-20/7577,Buildings,Completed,B-Buildings,,820000,"Supply, Installation, maintenance and house keeping of 200 nos portable toilet with necessary conservancy materials etc at various locations in between Chennai Airport to Mahabalipuram for two days visit honourable Prime minister of India & China meet on 10.10.2019 &11.10.2019",Own Sources,12,2019-20,2019-20 BR/2019-20/8014,Footpath,Completed,BR-Bus Route Roads,,997000,Traffic Improvements works at Sardar Patel Road from the jn of Gandhi mandapam road to the jn of Taluk office road in Zone -13,Own Sources,13,2019-20,2020-21 BR/2019-20/8016,Footpath,Completed,BR-Bus Route Roads,,991000,Traffic Improvements works at Sardar Patel Road from the jn of Gandhi mandapam road to the jn of Madhyakailash in Zone -13,Own Sources,13,2019-20,2020-21 BR/2019-20/8017,Footpath,Completed,BR-Bus Route Roads,,955000,TRAFFIC IMPROVEMENT WORKS AT TALUK OFFICE ROAD AND SARDAR PATEL ROAD (FROM JN OF ANNA SALAI TO THE JN OF TALUK OFFICE ROAD) AND TALUK OFFICE ROAD IN ZONE-13.,Own Sources,13,2019-20,2020-21 D/2019-20/4031,Storm Water Drain,Completed,D-Storm Water Drains,,32730000,"Construction of Missing Link Storm Water Drain at Jothi ammal nagar main road and 4 other roads in Dn. 169,171,183,193 & 197,Zone - 13,14&15, Package -10.",SMART CITY - SWD,14,2019-20,2020-21 D/2019-20/4794,Storm Water Drain,Completed,D-Storm Water Drains,,14600000,"Restoration and rejuvenation work in Gangai Amman Koil Kulam, Annai Theresa Nagar 10th street, Naicker Kuttai - Madipakkam,Thiruvalluvar Nagar Pond in Dn.169,188&191, Zone-14,Package - 2.",SMART CITY - SWD,14,2019-20,2020-21 BR/2019-20/10017,Roads,Completed,BR-Bus Route Roads,,778000,"Attendind OFC Roadcut Restoration at various loactions (Parthasarathy bridge, Vijayaraghavulu Street, Thiruvottriyur High Road,Wallajah Salai, EVK sampath salai) in Zone - V. Deposit code-57/0450/2018-19",Deposit Works,North Region,2019-20,2019-20 BR/2019-20/16692,Roads,Completed,BR-Bus Route Roads,,198000,"Repairs to the existing Modern Stainless Steel Bus Shelters at various locations -Melpatti Ponnappan St(Easwari Kalyana Mandapam), Perambur(Chinnadi madam School), Manali(Opp to Meenakshi Theatre), SN Chetty Road(Balakrishna Nagar ) in Zone- 4.",Own Sources,North Region,2019-20,2020-21 BR/2019-20/16697,Roads,Completed,BR-Bus Route Roads,,198000,"Repairs to the existing Modern Stainless Steel Bus Shelters at various locations - Whannels Road, Parthasarathy Over Bridge(Pencil factory Bus stop), Prakasam Salai(Jn of Truckers St), Anna Salai (Multispeciality Hospital), in Zone- 5.",Own Sources,North Region,2019-20,2020-21 BR/2019-20/17638,Road Cut,Completed,BR-Bus Route Roads,,985000,"Restoration of OFC Roadcut 12 Nos of Various Bus Route Roads in Div-48,50,51,56,58& 59. Zone - 4 & 5",Deposit Works,North Region,2019-20,2020-21 BR/2019-20/17639,Road Cut,Completed,BR-Bus Route Roads,,983000,"Restoration of OFC Roadcut 13 Nos of Various Bus Route Roads in Div61,62 & 63 Zone - 5",Deposit Works,North Region,2019-20,2020-21 NA/2020-21/0970,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,1,425500,"Desilting work in various streets in Division-1, Unit-1, Zone-1",Own Sources,1,2020-21,2020-21 NA/2020-21/1540,Roads,Completed,NA-THIRUVOTTIYUR,1,271500,"Improvement to interior CC road at Ulaganathapuram 1st Cross street in Dn 1, Unit 1, Zone 1",Own Sources,1,2020-21,2020-21 NA/2020-21/1556,Roads,Completed,NA-THIRUVOTTIYUR,1,1423500,"Improvement to interior CC road at Nettukuppam Cross lane in Dn 1, Unit 1, Zone 1",Own Sources,1,2020-21,2020-21 NA/2020-21/4487,Buildings,Completed,NA-THIRUVOTTIYUR,1,155000,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT NETTUKUPPAM IST STREET IN DIVISION-1, UNIT-1, ZONE-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/4502,Buildings,Completed,NA-THIRUVOTTIYUR,1,194000,"Repair and improvements to public convenience at Thalankuppam Colony street in Division - 1, Unit - 1, Zone - 1",Own Sources,1,2020-21,2021-22 NA/2020-21/4503,Buildings,Completed,NA-THIRUVOTTIYUR,1,177000,"Repair and improvements to public convenience at Nettukuppam main road in Division - 1, Unit - 1, Zone - 1.",Own Sources,1,2020-21,2021-22 NA/2020-21/0031,Buildings,Completed,NA-THIRUVOTTIYUR,2,4945000,"Construction of Additional MRF with Bailing Machine and Demolition and Reconstruction of Compound wall at Kathivakkam high road in Division-02, Unit-01, Zone-01",Own Sources,1,2020-21,2021-22 NA/2020-21/0465,Buildings,Completed,NA-THIRUVOTTIYUR,2,220000,"Repairs and Improvements to P.C.at South lock road in Division -02,Unit-01,Zone-01",Own Sources,1,2020-21,2021-22 NA/2020-21/0994,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,327000,"DESILTING OF SIDE DRAIN AND STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION-02,UNIT-01,ZONE-01",Own Sources,1,2020-21,2020-21 NA/2020-21/1192,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,2,781000,"MINOR REPAIR WORKS IN STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DIVISION-2, UNIT-1, ZONE-1",Own Sources,1,2020-21,2020-21 NA/2020-21/3224,Roads,Completed,NA-THIRUVOTTIYUR,2,565000,"Improvement to the interior CC road at Ramamuthy nagar main street in Division-2, Unit-1, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9290,Roads,Completed,NA-THIRUVOTTIYUR,3,222000,"Improvement to the interior BT road at Tsunami Quarters main road 6 (part) in Division-3, Unit-1, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9292,Roads,Completed,NA-THIRUVOTTIYUR,3,396000,"Improvement to the interior BT road at Tsunami Quarters cross road 19 in Division-3, Unit-1, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/0412,Buildings,Completed,NA-THIRUVOTTIYUR,4,500000,"Additional Improvements to UPHC at Makaliamman kovil School road in Division-04, Unit-01, Zone-01",Own Sources,1,2020-21,2021-22 NA/2020-21/10987,Roads,Completed,NA-THIRUVOTTIYUR,4,461000,"Improvement to interior CC road at Girija nagar, Selva vinayagar koil st,(part) in Dn 4, Unit 1, Zone 1",Own Sources,1,2020-21,2020-21 NA/2020-21/9294,Roads,Completed,NA-THIRUVOTTIYUR,4,676000,"Improvement to the interior BT road at Shanmugapuram Extension 3rd street in Division-4, Unit-1, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9297,Roads,Completed,NA-THIRUVOTTIYUR,5,1334000,"Improvement to interior (Relaying) BT road at Bharath Nagar 3rd Street in Division-05, Unit-02, Zone-01.",Own Sources,1,2020-21,2020-21 NA/2020-21/9298,Roads,Completed,NA-THIRUVOTTIYUR,5,1696000,"Improvement to interior (Re laying) BT road at Gandhi Nagar Main Road in Division-05, Unit-02, Zone-01.",Own Sources,1,2020-21,2020-21 NA/2020-21/9299,Roads,Completed,NA-THIRUVOTTIYUR,5,1145000,"Improvement to the interior BT road at Thiruvalluvar street in Division-5, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/1141,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,386000,"De-Silting of Storm Water Drain at Various Streets in Dn-6, Unit-2, Zone-I",Own Sources,1,2020-21,2021-22 NA/2020-21/1499,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,6,696000,"Minor Repair Work in Existing Storm Water Drain in Div-6,Unit-2, Zone-I.",Own Sources,1,2020-21,2021-22 NA/2020-21/9306,Roads,Completed,NA-THIRUVOTTIYUR,6,683500,"Improvement to the interior BT road at Saraswathi nagar 1st street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9307,Roads,Completed,NA-THIRUVOTTIYUR,6,1489000,"Improvement to the interior BT road at Kalaivanar nagar in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9308,Roads,Completed,NA-THIRUVOTTIYUR,6,920000,"Improvement to the interior BT road at Ambedkar nagar main road in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9309,Roads,Completed,NA-THIRUVOTTIYUR,6,433000,"Improvement to the interior BT road at Ambedkar nagar 7th cross street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9310,Roads,Completed,NA-THIRUVOTTIYUR,6,1086500,"Improvement to the interior BT road at Kalaignar nagar 5th street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9311,Roads,Completed,NA-THIRUVOTTIYUR,6,2126000,"Improvement to the interior BT road at Kalaignar nagar 9th street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9312,Roads,Completed,NA-THIRUVOTTIYUR,6,434000,"Improvement to the interior BT road at Kalaignar nagar 9th cross street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9313,Roads,Completed,NA-THIRUVOTTIYUR,6,260000,"Improvement to the interior BT road at Kalaignar nagar 11th street extension in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9314,Roads,Completed,NA-THIRUVOTTIYUR,6,962500,"Improvement to the interior BT road at Kalaignar nagar 12th cross street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9315,Roads,Completed,NA-THIRUVOTTIYUR,6,2087000,"Improvement to the interior BT road at Sakthi ganapathi nagar 1st street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9316,Roads,Completed,NA-THIRUVOTTIYUR,6,1497000,"Improvement to the interior BT road at Sakthi ganapathi nagar 3rd street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9317,Roads,Completed,NA-THIRUVOTTIYUR,6,640000,"Improvement to the interior BT road at Kalaignar nagar 2nd street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9318,Roads,Completed,NA-THIRUVOTTIYUR,6,454500,"Improvement to the interior BT road at Kalaignar nagar 2nd cross street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9319,Roads,Completed,NA-THIRUVOTTIYUR,6,1705000,"Improvement to the interior BT road at Jothi nagar 7th street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9320,Roads,Completed,NA-THIRUVOTTIYUR,6,1779000,"Improvement to the interior BT road at Jothi nagar 8th street in Division-6, Unit-2, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/3422,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,7,494000,"Minor Repair Work in Existing Storm Water Drain in Div-7, Unit-2, Zone-I.",Own Sources,1,2020-21,2021-22 NA/2020-21/9362,Roads,Completed,NA-THIRUVOTTIYUR,7,1172500,"Improvement to the interior BT road at Balakrishna Nagar Main Road in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9363,Roads,Completed,NA-THIRUVOTTIYUR,7,1854000,"Improvement to the interior BT road at RMV nagar mainroad in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9364,Roads,Completed,NA-THIRUVOTTIYUR,7,854500,"Improvement to the interior BT road at Annamalai nagar 2nd street in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9365,Roads,Completed,NA-THIRUVOTTIYUR,7,1584000,"Improvement to the interior BT road at Annamalai nagar 4th street in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9366,Roads,Completed,NA-THIRUVOTTIYUR,7,197000,"Improvement to the interior BT road at Ragavendra colony 1st street in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9367,Roads,Completed,NA-THIRUVOTTIYUR,7,100500,"Improvement to the interior BT road at Ragavendra colony 2nd street in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9368,Roads,Completed,NA-THIRUVOTTIYUR,7,235000,"Improvement to the interior BT road at Balakrishna Nagar Vinayagapuram 1st St in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9369,Roads,Completed,NA-THIRUVOTTIYUR,7,354500,"Improvement to the interior BT road at Balakrishna Nagar Vinayagapuram 2nd St in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9370,Roads,Completed,NA-THIRUVOTTIYUR,7,2901000,"Improvement to the interior BT road at Ramasamy nagar main road in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/9371,Roads,Completed,NA-THIRUVOTTIYUR,7,1305500,"Improvement to the interior BT road at Charles nagar main road in Division-7, Unit-2, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/2037,Roads,Completed,NA-THIRUVOTTIYUR,8,674000,"Improvement to interior BT Road at Chellappa nagar 1st and 2nd Street In Division-08, unit-02, Zone-01.",Own Sources,1,2020-21,2020-21 NA/2020-21/2136,Buildings,Completed,NA-THIRUVOTTIYUR,8,1186000,"Improvement to MRF shed at Ennore Express road in Div-8, Unit-2, Zone-I.",Own Sources,1,2020-21,2021-22 NA/2020-21/9377,Roads,Completed,NA-THIRUVOTTIYUR,8,461500,"Improvement to the interior BT road at Egavaliamman koil street in Division-8, Unit-2, Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/10984,Roads,Completed,NA-THIRUVOTTIYUR,9,264000,"Improvement to interior CC road at T S Gopal nagar cross street in Dn 9, Unit 2, Zone 1",Own Sources,1,2020-21,2020-21 NA/2020-21/1027,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,10,112000,"Desilting of Strom Water Drain at Sannathi Street in Division-10, Unit-03, Zone-01.",Own Sources,1,2020-21,2020-21 NA/2020-21/1029,Storm Water Drain,Completed,NA-THIRUVOTTIYUR,10,113000,"Desilting of Strom Water Drain at North mada Street in Division-10, Unit-03, Zone-01.",Own Sources,1,2020-21,2020-21 NA/2020-21/9325,Roads,Completed,NA-THIRUVOTTIYUR,10,1243000,"Improvement to the interior BT road at Sannathi Street in Division-10, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9327,Roads,Completed,NA-THIRUVOTTIYUR,10,2498000,"Improvement to the interior BT road at Sadayankuppam Battai Road in Division-10, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9335,Roads,Completed,NA-THIRUVOTTIYUR,10,1378000,"Improvement to the interior BT road at Railway Station Road and North Railway Station Road in Division-10, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 B/2020-21/1026,Buildings,Completed,B-Buildings,11,7250000,"CONSTRUCTION OF STP, PUMP ROOM & OUTER ALL ROUND FLOORING AND OTHER ADDITIONAL WORKS FOR URBAN COMMUNITY HEALTH CENTRE AT TH ROAD IN DVN-11, ZONE-01.",Grants,1,2020-21,2021-22 B/2020-21/2952,Buildings,Completed,B-Buildings,11,9440000,"Supply, installation, testing, commissioning and maintenance of Fire Fighting systems in Urban Community Health Centre(100 Beds) at Thiruvottiyur in Div-11 Zone-1",Grants,1,2020-21,2020-21 B/2020-21/3044,Buildings,Completed,B-Buildings,11,4130000,"Supply, installation, testing, commissioning and maintenance for one year of Medical Gas systems in Urban Community Health Centre(100 Beds) at Thiruvotriyur in Div-11 Zone-1",Grants,1,2020-21,2020-21 L/2020-21/0498,Electrical,Completed,L-Electrical,11,1405200,"PROVISION OF 4 TUBE LIGHTS AND 2 CEILING FANS IN EACH OF THE 480 FLATS OF NALLA THANNEER ODAI KUPPAM SLUM BOARD TENEMENTS, PHASE 1, DIVISION-11, ZONE-1",Own Sources,1,2020-21,2020-21 L/2020-21/6488,Electrical,Completed,L-Electrical,11,177800,"Supply and fixing of additional 30 nos. Ceiling Fan, 10 nos. Pedestal Fan, and 10 nos. Wall mount Fans and 15-amps point with electrical wiring at 100 BED UCHC (Ground+3 Floors), at Tiruvottiyur High Road, Dn-11, Zone-I, Tiruvottiyur",Own Sources,1,2020-21,2021-22 NA/2020-21/1394,Buildings,Completed,NA-THIRUVOTTIYUR,11,228000,"Proposed The Electrical Arrangements and Plumbing Works (Covid-19) in Government Hospital Campus at T.H. Road In Division-11,Unit-3,Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/1412,Buildings,Completed,NA-THIRUVOTTIYUR,11,1743000,"Proposed The Construction of Screening Lab Center (COVID-19) in Government Hospital Campus at T.H. Road In Division-11,Unit-3,Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/1452,Buildings,Completed,NA-THIRUVOTTIYUR,11,417000,"Proposal of Provision of Electrical Accessories with wiring for Zonal Control Center (Covid-19) Work at Zonal Office Premises in Division-11,Unit,3 ,Zone-1.",Own Sources,1,2020-21,2020-21 NA/2020-21/1453,Buildings,Completed,NA-THIRUVOTTIYUR,11,360000,"Altration and Repairing Works of Zonal Control Center for 1st Floor (COVID-19) in Zonal office Campus at Thiruvottiyur High Road,Chennai-19,In Zone-01,Unit-03,Division-11.",Own Sources,1,2020-21,2020-21 NA/2020-21/3547,Buildings,Completed,NA-THIRUVOTTIYUR,11,2977000,"Proposed Construction of MRF at Corporation Hospital Backside in Division-11, Unit-03, Zone-01.",Own Sources,1,2020-21,2021-22 NA/2020-21/3754,Buildings,Completed,NA-THIRUVOTTIYUR,11,2133000,"Proposed Construction of Interlocking Blocks at Corporation Hospital Backside in Division-11, Unit-03, Zone-01.",Own Sources,1,2020-21,2020-21 NA/2020-21/9322,Roads,Completed,NA-THIRUVOTTIYUR,11,2580000,"Improvement to the interior BT road at Kanakar Strret in Division-11, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9323,Roads,Completed,NA-THIRUVOTTIYUR,11,1555000,"Improvement to the interior BT road at Kanakar Lane in Division-11, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9324,Roads,Completed,NA-THIRUVOTTIYUR,11,3628000,"Improvement to the interior BT road at Sannathi Street in Division-11, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9345,Roads,Completed,NA-THIRUVOTTIYUR,12,824000,"Improvement to the interior BT road at Balakrishna Colony 3rd Street (part) in Division- 12, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9346,Roads,Completed,NA-THIRUVOTTIYUR,12,651000,"Improvement to the interior BT road at Kavarai Street (part) in Division- 12, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9347,Roads,Completed,NA-THIRUVOTTIYUR,12,267000,"Improvement to the interior BT road at Vasantha Nagar 4th Street in Division- 12, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 BR/2020-21/5918,Roads,Completed,BR-Bus Route Roads,13,2057000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Toll Gate Road (MGR Road) in Dn-13 , Zone - I",Grants,1,2020-21,2021-22 NA/2020-21/9338,Roads,Completed,NA-THIRUVOTTIYUR,14,1431500,"Improvement to the interior BT road at Thiruchinankuppam main road in Division-14, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9339,Roads,Completed,NA-THIRUVOTTIYUR,14,1210000,"Improvement to the interior BT road at Malligapuram main road in Division-14, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NA/2020-21/9340,Roads,Completed,NA-THIRUVOTTIYUR,14,1288000,"Improvement to the interior BT road at A Sadananthapuram in Division-14, Unit-3, Zone-1.",Own Sources,1,2020-21,2021-22 NB/2020-21/0264,Buildings,Completed,NB-MANALI,15,995000,"PROPOSED CONSTRUCTION OF MCC POINT INSIDE HINDU BURIAL GROUND AT MANALI NEW TOWN 150FEET ROAD IN DN-15 U-4, ZONE-02",Own Sources,2,2020-21,2021-22 NB/2020-21/2263,Buildings,Completed,NB-MANALI,15,161000,"REPAIR AND MAINTENANCE WORK FOR WARD BUILDINGS (TOILET & HOSPITAL) AND LAYING HOT APPLIED THERMOPLASTIC AT MANALI NEW TOWN VARIUS STREET AND OLD NAPPALAYAM IN DN-15, U-4,Z-2 .",Own Sources,2,2020-21,2020-21 NB/2020-21/2312,Buildings,Completed,NB-MANALI,15,997000,"PROPOSED CONSTRUCTION OF MANURE STOCK ROOM (RRC POINT) INSIDE HINDU BURIAL GROUND AT MANALI NEW TOWN 150FEET ROAD IN DN-15 U-4, ZONE-02",Own Sources,2,2020-21,2021-22 NB/2020-21/3728,Storm Water Drain,Completed,NB-MANALI,15,285000,"Attending Minor Repairs To Storm water & Side Darin in Various Streets (IRR) in Dn-15, U-4, Z-02.",Own Sources,2,2020-21,2021-22 NB/2020-21/3732,Storm Water Drain,Completed,NB-MANALI,15,38900,"Desilting of Storm Water Drain At Various Streets (IRR) In Dn - 15, U-4, Z-2.",Own Sources,2,2020-21,2021-22 NB/2020-21/2317,Buildings,Completed,NB-MANALI,16,961000,"PROPOSED CONSTRUCTION OF MANURE STOCK ROOM (RRC POINT) INSIDE AT MRB NAGAR MANALI NEW TOWN IN DN-16, U-4, ZONE-02.",Own Sources,2,2020-21,2021-22 NB/2020-21/3734,Storm Water Drain,Completed,NB-MANALI,16,105000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-16,U-4,Z-2.",Own Sources,2,2020-21,2021-22 NB/2020-21/3735,Storm Water Drain,Completed,NB-MANALI,16,56000,"MINOR REPAIRS OF STORM WATER DRAIN AT VARIOUS STREETS IN DN-16,U-4, Z-2",Own Sources,2,2020-21,2021-22 NB/2020-21/2323,Buildings,Completed,NB-MANALI,17,797000,"PROPOSED RE-CONSTRUCTION OF DAMAGED COMPOUND WALL OF COMPOST YARD AT SAMUVEL NAGAR BURIAL GROUND IN VADAPERUMBAKKAM IN DN-17, U-4, Z-2.",Own Sources,2,2020-21,2021-22 NB/2020-21/2479,Buildings,Completed,NB-MANALI,17,484500,"Supply and installation of tender coconut shredder consists for 10 Hp / Three phase motor having output of 100 to 150 kgs per hour with EN-9, 8mm blade ? 40 nos with 3mm thick M.S.Body (size 1000 x 500 x 800 mm) painted complete inclusive of 18% GST etc for Compost Yard at Samuvel nagar burial ground in Div-17, Unit-04, Zone-02.",Own Sources,2,2020-21,2020-21 NB/2020-21/3729,Storm Water Drain,Completed,NB-MANALI,17,325000,"Attending minor repair works of Storm Water Drain at Various Streets (IRR) In Dn - 17, U-4, Z-2.",Own Sources,2,2020-21,2020-21 NB/2020-21/3740,Storm Water Drain,Completed,NB-MANALI,17,200000,"Attending minor repair works of Storm Water Drain at Various Streets (BRR) In Dn - 17, U-4, Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/3730,Storm Water Drain,Completed,NB-MANALI,18,844000,"Desilting of Storm Water Drains at Various Streets In Dn-18, U-5, Z-2.",Own Sources,2,2020-21,2020-21 NB/2020-21/3731,Storm Water Drain,Completed,NB-MANALI,18,285000,"Attending Minor Repair Works and Replacing Damaged Manhole Doors of Storm Water Drains at Various locations In Dn-18, U-5, Z-2.",Own Sources,2,2020-21,2020-21 NB/2020-21/9028,Buildings,Completed,NB-MANALI,18,884000,"PROPOSED FORMING OF MIYAWAKI FOREST IN OSR LAND AT ANDARKUPPAM REDHILLS HIGH ROAD (NEAR M/S.NATCO ORGANIC LTD COMPANY) IN DIVISION-18, UNIT-5, ZONE-2.",Own Sources,2,2020-21,2020-21 B/2020-21/2923,Buildings,Completed,B-Buildings,19,3800000,"SUPPLY, INSTALLATION, TESTING, COMMISSIONING AND MAINTENANCE FOR ONE YEAR OF MEDICAL GAS SYSTEMS IN URBAN COMMUNITY HEALTH CENTER (100 BEDS) AT MANALI IN DN-19, ZONE 2.",Grants,2,2020-21,2021-22 NB/2020-21/0639,Roads,Completed,NB-MANALI,19,83000,"CONVERTING TO RAIN WATER HARWESTING PURPOSE FOR THE EXISTING WELL INSIDE THE PARK AT KOSAPUR ROAD MANJAMBAKKAM ( RRC POINT NEAR) IN DN-19, U-5, Z-02.",Own Sources,2,2020-21,2021-22 NB/2020-21/2133,Buildings,Completed,NB-MANALI,19,570000,REPAIR AND MAINTENANCE OF VARIOUS WORK {Division office } IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/2461,Buildings,Completed,NB-MANALI,19,484500,"Supply and installation of tender coconut shredder consists for 10 Hp / Three phase motor having output of 100 to 150 kgs per hour with EN-9, 8mm blade ? 40 nos with 3mm thick M.S.Body (size 1000 x 500 x 800 mm) painted complete inclusive of 18% GST etc at Ennore express road MCC centre Composed Yard at Arulandha nagar in Div-19 Unit-05, Zone 02",Own Sources,2,2020-21,2020-21 NB/2020-21/8230,Roads,Completed,NB-MANALI,19,478000,ROAD CUT RESTORATION OF BT ROAD AT SAKTHI NAGAR IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8231,Roads,Completed,NB-MANALI,19,399000,ROAD CUT RESTORATION OF BT ROAD AT TEACHER COLONY 2ND STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8232,Roads,Completed,NB-MANALI,19,483000,ROAD CUT RESTORATION OF BT ROAD AT NEHRU NAGAR 1ST STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8234,Roads,Completed,NB-MANALI,19,149000,ROAD CUT RESTORATION OF BT ROAD AT GANAPATH NAGAR 2ND STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8235,Roads,Completed,NB-MANALI,19,527000,ROAD CUT RESTORATION OF BT ROAD AT PONNUSAMY NAGAR IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8236,Roads,Completed,NB-MANALI,19,314000,ROAD CUT RESTORATION OF BT ROAD AT MMDA 66TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8238,Roads,Completed,NB-MANALI,19,149000,ROAD CUT RESTORATION OF BT ROAD AT MGR NAGAR 3RD STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8239,Roads,Completed,NB-MANALI,19,278000,ROAD CUT RESTORATION OF BT ROAD AT CHINNASAMY NAGAR 5TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8240,Roads,Completed,NB-MANALI,19,199000,ROAD CUT RESTORATION OF BT ROAD AT KARUMARIAMMAN KOIL 2ND STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8243,Roads,Completed,NB-MANALI,19,199000,ROAD CUT RESTORATION OF BT ROAD AT BABUJI NAGAR 3RD STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8244,Roads,Completed,NB-MANALI,19,378000,ROAD CUT RESTORATION OF BT ROAD AT BABUJI NAGAR 4TH STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8245,Roads,Completed,NB-MANALI,19,99000,ROAD CUT RESTORATION OF BT ROAD AT GANAPATHY NAGAR 1ST STREET IN DN-19 U-5 Z-02,Own Sources,2,2020-21,2020-21 NB/2020-21/8487,Buildings,Completed,NB-MANALI,19,200000,"IMPROVING THE EXISTING TOILET TO BABY FRIENDLY TOILET IN ANGANVADI AT KAMARAJAR SALAI INSIDE MANJAMBAKKAM CMS IN DIVISION-19, UNIT-5, ZONE-2.",Own Sources,2,2020-21,2021-22 B/2020-21/13720,Buildings,Completed,B-Buildings,20,970641,"SUPPLY AND FIXING OF OFFICE TABLE, CHAIR & HDU STORAGE UNIT FOR REVENUVE DEPARTMENT, ELECTRICAL, ADMIN DEPARTMENT ETC FOR THE NEWLY CONSTRUCTED ZONAL OFFICE 2 AT KAMARAJAR SALAI IN DN-20, ZONE-2",Own Sources,2,2020-21,2020-21 NB/2020-21/7857,Parks,Completed,NB-MANALI,20,190000,"PROVIDING FENCING FOR PROPOSED MIYAWAKI FOREST IN SIDE ZONAL OFFICE CAMPUS AT KAMARAJAR SALAI IN DN-20, UNIT-5, ZONE-2.",Own Sources,2,2020-21,2020-21 NB/2020-21/9043,Parks,Completed,NB-MANALI,20,1250000,"PROPOSED FORMING OF MIYAWAKKI FOREST IN SIDE ZONAL OFFICE CAMPUS AT KAMARAJAR SALAI IN DN - 20, UNIT - 5, ZONE - 2",Own Sources,2,2020-21,2020-21 NB/2020-21/0791,Roads,Completed,NB-MANALI,21,921000,"Road Cut Restoration and relaying of BT Road Ayeerakathamman koil streetin Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/0803,Roads,Completed,NB-MANALI,21,961000,"Road Cut Restoration and relaying of BT Road NSK Street in Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/0804,Roads,Completed,NB-MANALI,21,3002000,"Road Cut Restoration and relaying of BT Road Dr.Ambedkhar street streetin Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/0805,Buildings,Completed,NB-MANALI,21,1506000,"Road Cut Restoration and relaying of BT Road PRK Sharma streetin Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/0806,Roads,Completed,NB-MANALI,21,1643000,"Road Cut Restoration and relaying of BT Road Sannathy street streetin Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/0807,Roads,Completed,NB-MANALI,21,2768000,"Road Cut Restoration and relaying of BT Road Thiruvengadam streetin Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/0808,Roads,Completed,NB-MANALI,21,1901000,"Road Cut Restoration and relaying of BT Road Thamaraikulam streetin Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/0809,Roads,Completed,NB-MANALI,21,1420000,"Road Cut Restoration and relaying of BT Road Dr.Rajendhraprasad streetin Dn-21,U-5,Z-2",Own Sources,2,2020-21,2020-21 NB/2020-21/1959,Buildings,Completed,NB-MANALI,21,72000,"Repairing Motor Pump and Water Supply and Drainage Arrangements at Various Building in Dn-21 ,U-5,Z-2.",Own Sources,2,2020-21,2020-21 NB/2020-21/2231,Buildings,Completed,NB-MANALI,21,32000,"Repairing Damaged Slab to Strom Water Drain at Padasalai street in Dn-21 ,U-5,Z-2.",Own Sources,2,2020-21,2021-22 NB/2020-21/2297,Buildings,Completed,NB-MANALI,21,232000,"Repair and Maintenance for Unit-5 / Division -21 Office at Padasalai street in Dn-21,U-5,Z-2.",Own Sources,2,2020-21,2020-21 NB/2020-21/3737,Storm Water Drain,Completed,NB-MANALI,21,204000,"Attending Minor Repairs And Manhole door of Storm Water Drains at Various Streets Interior route Road In Dn-21, U-5, Z-2.",Own Sources,2,2020-21,2020-21 NB/2020-21/3742,Storm Water Drain,Completed,NB-MANALI,21,80000,"Attending Minor Repairs And Manhole door of Storm Water Drains at Various Street Bus route Road InDn-21, U-5, Z-2.",Own Sources,2,2020-21,2020-21 L/2020-21/4823,Electrical,Completed,L-Electrical,22,7356000,"Provision of 127 Nos of 6mtr lamp post, single straight bracket with 40w LED fitting at Micro marvel Nagar,vegitarian Nagar,Sree Balaji,Gangadaran Street,and Various Location Streets in Div-22 & 23 of Zone-III",Grants,3,2020-21,2021-22 NC/2020-21/0190,Buildings,Completed,NC-MADHAVARAM,22,651000,"RELAYING OF CC ROAD BY RMC 30 AT PUNITHA ANTHONIYAR 4TH BRANCH STREET IN WARD-23,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/0191,Roads,Completed,NC-MADHAVARAM,22,717000,"RELAYING OF CC ROAD BY RMC 30 AT PUNITHA ANTHONIYAR 1ST MAIN STREET IN WARD-23,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/0192,Buildings,Completed,NC-MADHAVARAM,22,455000,"RELAYING OF CC ROAD BY RMC 30 AT METTU 3RD CROSS STREET IN WARD-23,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/0752,Roads,Completed,NC-MADHAVARAM,22,923000,"RELAYING OF CC ROAD BY RMC 30 AT MERCY NAGAR 1ST STREET IN WARD-22,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/10352,Buildings,Completed,NC-MADHAVARAM,22,400000,"Maintenance to Mini Clinic Center ( Shopping Complex ) at Rettai Malai Srinivasan Street in Ward-23, Unit-6,Zone-3",Own Sources,3,2020-21,2021-22 NC/2020-21/10354,Buildings,Completed,NC-MADHAVARAM,22,210000,"Providing RCC Hume Pipe(600mm) To Drain Out The Rain Water From Low Laying Areas Of Various Streets at (Dhanalakshmi Nagar, Dhanalakshmi Nagar cross street, Sakthivel nagar 36th street, Vegeterian Village) In Division-22, Unit-06, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/11469,Buildings,Completed,NC-MADHAVARAM,22,36000,"Repairs and Maintenance to CMS at Gandhi Main Road in Division-22, Unit-6,Zone-3",Own Sources,3,2020-21,2021-22 NC/2020-21/13577,Roads,Completed,NC-MADHAVARAM,22,32000,"Annual Maintenance Extention for November 2020 Park at Gurusanthi nagar Park in Dn-22, Unit-6, Zone-3 (per year) Area = 958.91 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13578,Parks,Completed,NC-MADHAVARAM,22,36000,"Annual Maintenance Extention for November 2020 Park at Macro marvel 1st cross street Park in Dn-22, Unit-6, Zone-3 (per year) Area = 1008.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13579,Parks,Completed,NC-MADHAVARAM,22,16000,"Annual Maintenance Extention for November 2020 Park at Macro marvel 2nd cross street Park in Dn-22, Unit-6, Zone-3 (per year) Area = 504.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13580,Parks,Completed,NC-MADHAVARAM,22,33000,"Annual Maintenance Extention for November 2020 Park at Macro marvel Park Phase -III in Dn-22, Unit-6, Zone-3 (per year) Area = 1090.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/2801,Buildings,Completed,NC-MADHAVARAM,22,2985000,"ADDITIONAL CONSTRUCTION OF RRC TO IMPROVE WET WASTE AT JEEVA MAIN STREET KANNADAPALAYAM IN WARD-22, UNIT-6, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2922,Buildings,Completed,NC-MADHAVARAM,22,660000,"Construction of Rest Room (1+1) and other Improvements to Existing RRC inside of Burial Ground at Kannadapalayam in Division-22, Unit-6, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/2932,Electrical,Completed,NC-MADHAVARAM,22,800000,"Construction of Rest Room (2+2) and other Improvements to Existing RRC at Kannappaswamy Nagar inside of Burial Ground in Division-22, Unit-6, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/3246,Buildings,Completed,NC-MADHAVARAM,22,1120000,"RAISING OF COMPOUND WALL AT KANNADAPALAYAM BURIAL GROUND IN WARD-22,UNIT-6,ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/3478,Storm Water Drain,Completed,NC-MADHAVARAM,22,230000,"DE- SILTING AND IMRROVEMENTS OF STORM WATER DRAIN AT VARIOUS STREET IN DN-22,UNIT-6,ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/4693,Storm Water Drain,Completed,NC-MADHAVARAM,22,192000,"DE- SILTING AND IMRROVEMENTS OF STORM WATER DRAIN AT VARIOUS STREET IN DN-23,UNIT-6,ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/9510,Buildings,Completed,NC-MADHAVARAM,22,310000,"Repairs to Mini Clinic Center (Conversion of Multipurpose Hall Building to Mini Clinic) at Ko.Su.Mani Street in Ward-22, Unit-6,Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/9527,Buildings,Completed,NC-MADHAVARAM,22,44000,"Repairs and Maintenance to Ward-22 office at Gandhi 1st Street in Division-22, Unit-6,Zone-3",Own Sources,3,2020-21,2021-22 NC/2020-21/9528,Buildings,Completed,NC-MADHAVARAM,22,120000,"Improvements to Amma Mini Clinic and Supplying Furnitures at Ko.Su.Mani Street in Division-22, Unit-6, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/0319,Buildings,Completed,NC-MADHAVARAM,23,300000,"RELAYING OF CC ROAD BY RMC 30 AT LAKSHMIAMMAN KOIL 2ND CROSS STREET IN WARD-23,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/0329,Buildings,Completed,NC-MADHAVARAM,23,403000,"RELAYING OF CC ROAD BY RMC 30 AT PUNITHA ANTHONIYAR 2ND MAIN STREET IN WARD-23,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/0330,Roads,Completed,NC-MADHAVARAM,23,528000,"RELAYING OF CC ROAD BY RMC 30 AT ANNA NAGAR 3RD STREET IN WARD-23,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/0331,Buildings,Completed,NC-MADHAVARAM,23,449000,"RELAYING OF CC ROAD BY RMC 30 AT METTU 1ST BRANCH STREET IN WARD-23,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/0772,Parks,Completed,NC-MADHAVARAM,23,582000,"Abstract for Maintenance Estimate for Park at Gangatharan Street Park in Dn-23,Unit-7,Zone-3 (per year) Area = 848.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/0773,Parks,Completed,NC-MADHAVARAM,23,835000,"Abstract for Maintenance Estimate for Park at Ambattur- Redhills road Park in Dn-23,Unit-7,Zone-3 (per year) Area = 3458.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13587,Parks,Completed,NC-MADHAVARAM,23,34000,"Annual Maintenance Extention for November 2020 Park at Ambattur-Redhills road Park in Dn-23, Unit-6, Zone-3 (per year) Area = 992.00 Sq.m in ward-23,unit-6,zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/13588,Parks,Completed,NC-MADHAVARAM,23,32000,"Annual Maintenance Extention for November 2020 Park at Gangatharan Street Park in Dn-23, Unit-6, Zone-3 (per year) Area = 848.00 Sq.m in ward-23,unit-6,zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2943,Buildings,Completed,NC-MADHAVARAM,23,2567000,"Additinonal construction of RRC to improve Wet waste process at GNT Service road Inside burial ground in Division-23, Unit-6, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2958,Buildings,Completed,NC-MADHAVARAM,23,409000,"REPAIRS to Existing RRC CENTRE AT G.N.T SERVICE ROAD (inside burial ground) IN DIV-23,UNIT-6,ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/3751,Parks,Completed,NC-MADHAVARAM,23,1175000,"CALXY OSR LAND (MIYAWAKI URBAN FOREST) IMPROVEMNET WORKS IN DIVISION-23, UNIT-6,ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/4473,Parks,Completed,NC-MADHAVARAM,23,550000,"CALXY OSR LAND (MIYAWAKI URBAN FOREST) GREENERYS AND TREE PLANTATION IN DIVISION-23, UNIT-6,ZONE-3",Own Sources,3,2020-21,2020-21 L/2020-21/4304,Electrical,Completed,L-Electrical,24,2782600,"Work: Provision of 30 Nos of 8mtrs GI Octagonal Street Lamp Post with Single Straight bracket and with 90W LED Fittings and 903 Mtrs of 31/2 X 25 SQ.MM PVC ( Alum ) U G .Cables at Brittania Nagar 40 Feet Road,Div-24 & 25 , Zone-3.areas.",Own Sources,3,2020-21,2021-22 NC/2020-21/10061,Parks,Completed,NC-MADHAVARAM,24,35000,"ANNUAL MAINTENANCE FOR PARK AT SRI LAKSHIMI AMMAN NAGAR PARK IN WARD-24, UNIT-6,ZONE-3 (AREA=900.00 SQM)",Own Sources,3,2020-21,2020-21 NC/2020-21/13690,Parks,Completed,NC-MADHAVARAM,24,32000,"ANNUAL MAINTENANCE ESTIMATE FOR PARK AT PADMAVATHY NAGAR EXTN 5TH STREET IN DIV-25,UNIT-6,ZONE-3 (AREA=973.00 SQM)",Own Sources,3,2020-21,2020-21 NC/2020-21/13692,Parks,Completed,NC-MADHAVARAM,24,34000,"ANNUAL MAINTENANCE FOR PARK AT SRINIVASA NAGAR MAIN ROAD IN DIV-25, UNIT-6,ZONE-3 (AREA= 368.00 SQM)",Own Sources,3,2020-21,2020-21 NC/2020-21/13693,Parks,Completed,NC-MADHAVARAM,24,52000,"ANNUAL MAINTENANCE FOR PARK AT COLLECTOR NAGAR MAIN ROAD IN DIV-25, UNIT-6, ZONE-3 (AREA= 1630.00 SQM)",Own Sources,3,2020-21,2020-21 NC/2020-21/13694,Parks,Completed,NC-MADHAVARAM,24,51000,"ANNUAL MAINTENANCE FOR PARK AT BIRLA AVENUE IN DIV-25,UNIT-6,ZONE-3 (AREA= 2620.00 SQM)",Own Sources,3,2020-21,2020-21 NC/2020-21/13695,Parks,Completed,NC-MADHAVARAM,24,57000,"ANNUAL MAINTENANCE FOR PARK AT PADMAVATHY NAGAR 7TH STREET IN DIV-25, UNIT-6,ZONE-3 (AREA= 2397.00 SQM)",Own Sources,3,2020-21,2021-22 NC/2020-21/2954,Buildings,Completed,NC-MADHAVARAM,24,1970000,"Construction of Source seggregation shed at Soorapattu burial ground(Near Velammal) In Division-24, Unit-6, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2955,Buildings,Completed,NC-MADHAVARAM,24,2460000,"Construction of Source seggregation shed at at Kadapa road Near Amma unavagam In Division-24, Unit-6, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/3540,Storm Water Drain,Completed,NC-MADHAVARAM,24,665000,"DE-SILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-24, UNIT-6, ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/4663,Buildings,Completed,NC-MADHAVARAM,24,81000,"Improvement works to the newly installed caravan clinic at at Mettur link road In Div-24, Unit-6, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/5544,Roads,Completed,NC-MADHAVARAM,24,920000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT JP NAGAR 3RD MAIN ROAD IN DIV-24,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/5546,Roads,Completed,NC-MADHAVARAM,24,2325000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT THIRUMAL NAGAR 1ST MAIN ROAD IN DIV-24,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/5547,Roads,Completed,NC-MADHAVARAM,24,811000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT THIRUMAL NAGAR 2ND MAIN ROAD IN DIV-24,UNIT-6, ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/8401,Bridges,Completed,NC-MADHAVARAM,24,968000,"CONSTRUCTION OF COMPOUND WALL NEAR RRC CENTRE PUTHAGARAM IN DIVISION-24, UNIT-6, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/9384,Buildings,Completed,NC-MADHAVARAM,24,965000,"Improvements work for Sanitary inspector office convering into Mini Clinic in at Subash nagar 1st street in Div-24, Unit-6, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/9388,Buildings,Completed,NC-MADHAVARAM,24,250000,"Providing water supply and Electrical arrangemants to Mini Clinic ( Sanitary inspector office) in at Subash nagar 1st street in Div-24, Unit-6, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/9828,Parks,Completed,NC-MADHAVARAM,24,32000,"ANNUAL MAINTENANCE FOR PARK AT DG NAGAR PARK IN DIV-24, UNIT-6, ZONE-3 (AREA=700.00 SQM)",Own Sources,3,2020-21,2020-21 D/2020-21/9202,Roads,Completed,D-Storm Water Drains,25,2100000,"Providing wearing coat over the Double vent Storm Water Drain at Eastern side Service Road of Chennai Bye pass(Ch 30/400 - Ch 31/250) in Div 25, Zone 3.",Own Sources,3,2020-21,2020-21 D/2020-21/9203,Roads,Completed,D-Storm Water Drains,25,2100000,"Providing wearing coat over the Double vent Storm Water Drain at Western side Service Road of Chennai Bye pass(Ch 30/400 - Ch 31/250) in Div 25, Zone 3.",Own Sources,3,2020-21,2020-21 NC/2020-21/13264,Buildings,Completed,NC-MADHAVARAM,25,121000,"Repairs and Improvements to Division Office at EMS Street In Div-25, Unit-6, Zone-3",Own Sources,3,2020-21,2021-22 NC/2020-21/13265,Buildings,Completed,NC-MADHAVARAM,25,104000,"Furniture Arrangements to Minic Clinic in Division Office at EMS Street In Div-25, Unit-6, Zone-3",Own Sources,3,2020-21,2021-22 NC/2020-21/2921,Buildings,Completed,NC-MADHAVARAM,25,474000,"construction of Toilet and repairs to the Existing RRC Centre at Bharathiyar Street Burial Ground in Div-25, Unit-6, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/2930,Buildings,Completed,NC-MADHAVARAM,25,999000,"construction of Toilet and repairs to the Existing RRC Centre at Padmavathy Nagar Burial Ground in Div-25, Unit-6, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/2945,Buildings,Completed,NC-MADHAVARAM,25,1960000,"Additinonal construction of RRC to improve Wet waste process at Bharathiyar street burial ground in Division-25, Unit-6, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2956,Buildings,Completed,NC-MADHAVARAM,25,1470000,"Additinonal construction of RRC to improve Wet waste process at Padmavathy nagar street burial ground in Division-25, Unit-6, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/3689,Storm Water Drain,Completed,NC-MADHAVARAM,25,617000,"DE- SILTING AND REPAIRS TO STORM WATER DRAIN AT SERVICE ROAD,SRINIVASA NAGAR 3RD STREET,LINGAM MAIN STREET AND LINGAM 1ST STREET IN DN-25, UNIT-6, ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/3690,Storm Water Drain,Completed,NC-MADHAVARAM,25,700000,"DE- SILTING AND REPAIRS TO STORM WATER DRAIN AT VARIOUS STREET IN DN-25, UNIT-6, ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/6213,Roads,Completed,NC-MADHAVARAM,25,533000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT BALAJI NAGAR 5TH STREET IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6215,Roads,Completed,NC-MADHAVARAM,25,489000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT BALAJI NAGAR 6TH STREET IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6217,Roads,Completed,NC-MADHAVARAM,25,1384000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT VEERARAGAVALU NAGAR 2ND MAIN ROAD IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6218,Roads,Completed,NC-MADHAVARAM,25,1024000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT BABUJI NAGAR IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6219,Roads,Completed,NC-MADHAVARAM,25,1682000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT VEERARAGAVALU NAGAR 1ST MAIN ROAD IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6220,Roads,Completed,NC-MADHAVARAM,25,445000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT INTUC NAGAR 3RD CROSS STREET PART IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6221,Roads,Completed,NC-MADHAVARAM,25,578000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT INTUC NAGAR 7TH CROSS STREET (PART) IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6222,Roads,Completed,NC-MADHAVARAM,25,293000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT MADURA METTURPALAYAM 1ST STREET IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6278,Roads,Completed,NC-MADHAVARAM,25,1854000,"FORMATION OF BT ROAD AT INTUC NAHAR 7TH STREET PART IN DIVISION-25,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/6279,Roads,Completed,NC-MADHAVARAM,25,800000,"FORMATION OF BT ROAD AT BRITTANIA NAGAR MAIN ROAD PART IN DIVISION-25,UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/6280,Roads,Completed,NC-MADHAVARAM,25,603000,"FORMATION OF BT ROAD AT RASI NAGAR 4TH STREET PART IN DIVISION-25, UNIT-6,ZONE-3",Grants,3,2020-21,2020-21 NC/2020-21/6282,Roads,Completed,NC-MADHAVARAM,25,1161000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT REDDY 3RD STREET IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6297,Roads,Completed,NC-MADHAVARAM,25,396000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT LINGAM 3RD CROSS STREET IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6299,Roads,Completed,NC-MADHAVARAM,25,302000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT Arignar anna nagar 1st street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6300,Roads,Completed,NC-MADHAVARAM,25,377000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT Arignar anna nagar 2nd street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6301,Roads,Completed,NC-MADHAVARAM,25,704000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT Arignar anna nagar 3rd street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6303,Roads,Completed,NC-MADHAVARAM,25,291000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT Arignar anna nagar 5th street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6304,Roads,Completed,NC-MADHAVARAM,25,529000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT Arignar anna nagar 6th street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6305,Roads,Completed,NC-MADHAVARAM,25,502000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT Arignar anna nagar 7th street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6306,Roads,Completed,NC-MADHAVARAM,25,554000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT Lingam 1st street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 NC/2020-21/6308,Roads,Completed,NC-MADHAVARAM,25,561000,"RELAYING OF BT ROAD WITH PAVER FINISHER AT INTUC nagar 4th street IN DIV-25,UNIT-6,ZONE-3.",Grants,3,2020-21,2020-21 BR/2020-21/5920,Roads,Completed,BR-Bus Route Roads,26,5420000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Villivakkam Road in Dn-26 & 32, Zone - III",Grants,3,2020-21,2021-22 NC/2020-21/0485,Buildings,Completed,NC-MADHAVARAM,26,870000,"IMPROVEMENT WORKS TO EXISTING BUILDING AT ZONAL OFFICE , AND CHENNAI MIDDLE SCHOOL FOR COVID-19 SAMPLE COLLECTION CENTRE IN DN-26 AND DN-27 UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/0764,Parks,Completed,NC-MADHAVARAM,26,622000,"Abstract for Maintenance Estimate for Canal Park at Burial Ground Road (Vinayagapuram) in Dn-26, Unit-7, Zone-3 (per year) Area = 855 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/0765,Parks,Completed,NC-MADHAVARAM,26,612000,"Abstract for Maintenance Estimate for Park at Secretariat Colony Park in Dn-26, Unit-7, Zone-3 (per year) Area = 1200.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/0820,Buildings,Completed,NC-MADHAVARAM,26,580000,"IMPROVEMENT WORKS TO EXISTING BUILDING AT CMDA TRUCK TERMINAL ADJOINING SIDE OF AMMA UNAVAGAM FOR COVID-19 SAMPLE COLLECTION CENTRE IN DIVISION-26, UNIT-7, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/0833,Parks,Completed,NC-MADHAVARAM,26,2989000,"PROVIDING GREERNARIES AT OMAKULAM POND IN DN-26 UNIT-7, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/0996,Buildings,Completed,NC-MADHAVARAM,26,265000,PROVIDING BOREWELL TO DIVISINAL OFFICE AT THANIKACHALAM NAGAR F BLOCK 3RD STREET IN DN-26 UNIT-7 ZONE-3,Own Sources,3,2020-21,2021-22 NC/2020-21/10595,Buildings,Completed,NC-MADHAVARAM,26,1086000,NAME OF WORK: CONSTRUCTION OF C&D WASTE CENTER AT CMDA TRUCK TERMINAL IN DN-26 UNIT-7 ZONE-3,Own Sources,3,2020-21,2020-21 NC/2020-21/10701,Roads,Completed,NC-MADHAVARAM,26,231000,"Annual mainteanance work for damaged road portion at various street (vasantha nagar, thanikachalam nagar 10th street, and gilburn nagar name board)in Division-26,Unit-7,Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13089,Buildings,Completed,NC-MADHAVARAM,26,115000,"ANNUAL REPAIRS & MAINTANANCE WORK FOR DIVISION OFFICE AT THANIKACHALAM NAGAR IN DIVISION-26, UNIT-07, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13090,Buildings,Completed,NC-MADHAVARAM,26,231000,"ANNUAL MAINTENANCE OF THATTANKULAM PC IN DIVISION-26, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13766,Buildings,Completed,NC-MADHAVARAM,26,36000,"Annual Maintenance Extention for November 2020 Canal Park at Burial Ground Road (Vinayagapuram) in Dn-26, Unit-7, Zone-3 (per year) Area = 855 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13767,Buildings,Completed,NC-MADHAVARAM,26,48000,"Annual Maintenance Extention for November 2020 Park at Secretariat Colony in Dn-26, Unit-7, Zone-3 (per year) Area = 1200.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/1521,Buildings,Completed,NC-MADHAVARAM,26,590000,"SUPPLYING AND PROVIDING GALVANISED IRON PURLIN SHEET SHED AT WESTERN SIDE OF CMDA TRUCK TERMINAL ADJOINING SIDE OF AMMA UNAVAGAM FOR COVID-19 SAMPLE COLLECTION CENTRE IN DIVISION-26, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/1522,Buildings,Completed,NC-MADHAVARAM,26,543000,"SUPPLYING AND PROVIDING GALVANISED IRON PURLIN SHEET SHED AT SOUTHERN SIDE OF CMDA TRUCK TERMINAL ADJOINING SIDE OF AMMA UNAVAGAM FOR COVID-19 SAMPLE COLLECTION CENTRE IN DIVISION-26, UNIT-7, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/2950,Buildings,Completed,NC-MADHAVARAM,26,2550000,PROPOSED CONSTRUCTION OF MICRO COMPOST CENTRE AT DIVISIONAL OFFICE IN DN-26 UNIT-7 ZONE-3,Own Sources,3,2020-21,2021-22 NC/2020-21/3433,Roads,Completed,NC-MADHAVARAM,26,1190000,"FORMATION OF BT ROAD AT VINAYAGAPURAM BUS STAND IN DN-26, UNIT-7, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/3472,Buildings,Completed,NC-MADHAVARAM,26,98800,"PROPOSED CONSTRUCTION OF TERRACE GARDENING AT DIVISIONAL OFFICE IN DN-26,UNIT-7,ZONE-03.",Own Sources,3,2020-21,2021-22 NC/2020-21/3473,Buildings,Completed,NC-MADHAVARAM,26,98800,"PROPOSED CONSTRUCTION OF TERRACE GARDENING AT ZONAL OFFICE-3 IN DN-26,UNIT-7,ZONE-03.",Own Sources,3,2020-21,2021-22 NC/2020-21/3695,Storm Water Drain,Completed,NC-MADHAVARAM,26,453000,"DESILTING STORM WATER DRAIN AND SIDE DRAIN WORK AT VARIOUS STREET IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/3699,Buildings,Completed,NC-MADHAVARAM,26,445000,"DESILTING OF STORM WATER DRAIN IMPROVEMENT WORK AT PRH ROAD IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/3700,Buildings,Completed,NC-MADHAVARAM,26,435000,"DESILTING AND MINOR REPAIRS TO STORM WATER DRAIN AND SIDE DRAIN WORK AT VARIOUS STREET IN DIV-26, UNIT-7, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/4151,Buildings,Completed,NC-MADHAVARAM,26,75000,"REPAIR WORKS OF AMMA UNAVAGAM AT THANIKACHALAM NAGAR F BLOCK 6TH STREET IN DIVISION-26,UNIT-7,ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/6145,Buildings,Completed,NC-MADHAVARAM,26,65000,"IMPROVEMENT WORKS AT NIGHT SHELTER IN CMDA TRUCK TERMINAL IN DIVISION-26,UNIT-7,ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/6686,Electrical,Completed,NC-MADHAVARAM,26,54000,"Repairs and maintenance of Bore well at Ganapathi Siva nagar in Dn-26, Unit-7, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/6859,Roads,Completed,NC-MADHAVARAM,26,1585000,LAYING OF WMM AT OSR LAND OF 200 FEET ROAD IN DIVISION-26 UNIT-7 ZONE-3,Own Sources,3,2020-21,2020-21 NC/2020-21/7849,Buildings,Completed,NC-MADHAVARAM,26,839000,"PROVIDING RCC HUME PIPE TO DRAIN OUT THE RAIN WATER FROM LOW LAYING AREA OF GANAPATHY SIVA NAGAR AND DEVI NAGAR IN DIVISION-26, UNIT-07, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/7850,Buildings,Completed,NC-MADHAVARAM,26,1067000,"PROVIDING RCC HUME PIPE TO DRAIN OUT THE RAIN WATER FROM LOW LAYING AREA OF PARIMALAM NAGAR IN DIVISION-26, UNIT-07, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/8280,Buildings,Completed,NC-MADHAVARAM,26,338000,"CONSTRUCTION OF WATCH MAN ROOM AT GANAPATHY SIVA NAGAR IN DIVISION-26,UNIT-07,ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/9652,Buildings,Completed,NC-MADHAVARAM,26,616000,"REPAIRS AND MAINTENANCE OF MINI CLINIC AT THANIKACHALAM NAGAR OLD DIVISION OFFICE BUILDING IN DIVISION-26, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 BR/2020-21/5921,Roads,Completed,BR-Bus Route Roads,27,5535000,"Relaying the road with DBM and BC after cold milling by paver finisher along with traffic improvement work at Assisi Nagar Main Road in Dn- 27 , Zone - III",Grants,3,2020-21,2021-22 NC/2020-21/10288,Buildings,Completed,NC-MADHAVARAM,27,155000,"IMPROVEMENT WORKS TO EXISTING CHENNAI MIDDLE SCHOOL AT MADHAVARAM MILK COLONY IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2606,Buildings,Completed,NC-MADHAVARAM,27,347000,"PROVIDING WATER SUPPLY ARRANGEMENTS FOR BURIAL GROUND AT TELUGU COLONY IN DN-27, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2948,Buildings,Completed,NC-MADHAVARAM,27,2430000,PROPOSED CONSTRUCTION OF MICRO COMPOST CENTRE AT TELUGU COLONY BURIAL GROUND IN DN-27 UNIT-7 ZONE-3,Own Sources,3,2020-21,2021-22 NC/2020-21/3698,Storm Water Drain,Completed,NC-MADHAVARAM,27,438000,"DESILTING AND MINOR REPAIRS TO SIDE DRAIN AT VARIOUS STREETS IN DIV-27, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/9546,Buildings,Completed,NC-MADHAVARAM,27,770000,"IMPROVEMENTS THE EXISTING CI OFFICE CONVERSION TO AMMA MINI CLINIC AT KRISHNA NAGAR EXTENSION IN DIV-27,UNIT-7,ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/0220,Buildings,Completed,NC-MADHAVARAM,28,1315000,"CONSTRUCTION OF COMPOUND WALL FOR GOVT LAND AT MOOLACHATRAM MAIN ROAD (NEAR AAVIN POND) IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/0760,Parks,Completed,NC-MADHAVARAM,28,1327000,"Abstract for Maintenance Estimate for Park at Padmagiri Park in Dn-28, Unit-7, Zone-3 (per year) Area = 4340.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/0761,Parks,Completed,NC-MADHAVARAM,28,259000,"Abstract for Maintenance Estimate for Park at Krishna Nagar and Children Play field in Dn-28, Unit-7, Zone-3 (per year) Area = 500 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13485,Buildings,Completed,NC-MADHAVARAM,28,120000,"SUPPLYING AND PROVIDING WET MIX MACADAM AT M.M.C POTTU ROOM IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13486,Buildings,Completed,NC-MADHAVARAM,28,41000,"SUPPLYING AND FIXING INVERTER AT DIVISION -28 OFFICE AT ARUL NAGAR APPROACH ROAD IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13487,Buildings,Completed,NC-MADHAVARAM,28,5000,"IMPROVEMENTS WORKS TO M.M.C POTTU ROOM AT MADHAVARAM MILK COLONY IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13488,Buildings,Completed,NC-MADHAVARAM,28,9500,"IMPROVEMENTS WORKS TO AMMA UNAVAGAM AT ARUL NAGAR APPROACH ROAD AND PADAVATTAMMAN KOIL STREET IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13489,Buildings,Completed,NC-MADHAVARAM,28,56000,"DEWATERING OF FLOOD STAGNATION OF AREA BY USING 7.5HP MOTOR PUMP AT AVM AVENUE PERIYASEKKADU PERUMAL KOIL STREET IN DIVISION-28, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13746,Buildings,Completed,NC-MADHAVARAM,28,50000,"Annual Maintenance Extention for November 2020 Park at Krishna Nagar in Dn-28, Unit-7, Zone-3 (per year) Area = 1200 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13747,Buildings,Completed,NC-MADHAVARAM,28,73000,"Annual Maintenance Extention for November 2020 Park at Padmagiri Nagar in Dn-28, Unit-7, Zone-3 (per year) Area = 4340.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/2946,Buildings,Completed,NC-MADHAVARAM,28,2550000,PROPOSED CONSTRUCTION OF MICRO COMPOST CENTRE AT SASTHRI NAGAR BURIAL GROUND IN DN-28 UNIT-7 ZONE-3,Own Sources,3,2020-21,2020-21 NC/2020-21/3686,Storm Water Drain,Completed,NC-MADHAVARAM,28,448000,"DESILTING AND MINOR REPAIRS TO STORM WATER DRAIN AT M.M.C MAIN ROAD, SASTHRI NAGAR , ARUL NAGAR IN DIV-28, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/9674,Buildings,Completed,NC-MADHAVARAM,28,452000,"IMPROVEMENTS THE EXISTING DN-28 OFFICE CONVERSION TO AMMA MINI CLINIC AT ARUL NAGAR APPROACH ROAD IN DIV-28,UNIT-7,ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/0916,Buildings,Completed,NC-MADHAVARAM,29,304000,"BIO SHREDDING MACHINE TO MCC/RCC/COMPOST YARD AT VELU STREET IN DN-29, UNIT-7,ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/10227,Buildings,Completed,NC-MADHAVARAM,29,615000,"PROVIDING RCC HUME PIPE TO CUTCHA DRAIN FOR RAIN WATER AT FUTURA BUSINEES PARK IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2338,Buildings,Completed,NC-MADHAVARAM,29,731000,"SUPPLYING AND PROVIDING ILP FOR FRONT SIDE OPEN AREA INSIDE OF COMPOSED YARD AT VELU STREET IN DN-29, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2358,Buildings,Completed,NC-MADHAVARAM,29,680000,"SUPPLYING AND PROVIDING ILP FOR BACK SIDE OPEN AREA INSIDE OF COMPOSED YARD AT VELU STREET IN DN-29, UNIT-7, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/2359,Buildings,Completed,NC-MADHAVARAM,29,1730000,"SUPPLYING AND PROVIDING GALVANISED IRON PURLIN SHEET SHED NORTHERN SIDE - I (INSIDE COMPOST YARD) AT VELU STREET IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2363,Buildings,Completed,NC-MADHAVARAM,29,1730000,"SUPPLYING AND PROVIDING GALVANISED IRON PURLIN SHEET SHED NORTHERN SIDE - IV (INSIDE COMPOST YARD) AT VELU STREET IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/2366,Buildings,Completed,NC-MADHAVARAM,29,1318000,"PROVIDING GALVANISED IRON PURLIN SHEET SHED , PAINTING WORK AND, SEPTIC TANK OF EXISTING COMPOST PIT (INSIDE COMPOST YARD) AT VELU STREET IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2949,Buildings,Completed,NC-MADHAVARAM,29,2550000,PROPOSED CONSTRUCTION OF MICRO COMPOST CENTRE AT KARUNANIDHI STREET BURIAL GROUND IN DN-29 UNIT-7 ZONE-3,Own Sources,3,2020-21,2020-21 NC/2020-21/3701,Storm Water Drain,Completed,NC-MADHAVARAM,29,540000,"DESILTING AND MINOR REPAIRS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIV-29, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/3708,Storm Water Drain,Completed,NC-MADHAVARAM,29,460000,"DESILTING AND MINOR REPAIRS TO STORM WATER DRAIN AT VARIOUS STREETS IN DIV-29, UNIT-7, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/8147,Buildings,Completed,NC-MADHAVARAM,29,230000,"CONSTRUCTION OF BABY FRIENDLY TOILET FOR ICDS (CENTRE NO. 33603140103 ) AT DEVARAJAN STREET IN DIVISION-29, UNIT-7, ZONE-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/9394,Buildings,Completed,NC-MADHAVARAM,29,995000,"CONSTRUCTION OF MINI CLINIC AT DEVARAJAN STREET (INSIDE OF DIVISION OFFICE) IN DIV-29,UNIT-7,ZONE-3.",Own Sources,3,2020-21,2020-21 Q/2020-21/2744,Roads,Completed,Q-Solid Waste Management,29,2560000,"Formation of road from Amma unavagam to Proposed pyrolysis site(0-200m) in Dn-29,Z-3",Own Sources,3,2020-21,2020-21 Q/2020-21/2882,Roads,Completed,Q-Solid Waste Management,29,2980000,"Formation of road from Proposed pyrolysis site to Windrow composting yard (200-430m) in Dn-29,Z-3",Own Sources,3,2020-21,2020-21 Q/2020-21/9508,Roads,Completed,Q-Solid Waste Management,29,2327000,"Forming Wet Mix Macadam Road from Windrow compost yard to proposed Baling machine platform at Madhavaram , Dn-29,Z-3",Own Sources,3,2020-21,2021-22 BR/2020-21/10662,Road Cut,Completed,BR-Bus Route Roads,30,991000,"Restoration of Road Cut made by OFC department at Various Streets in Unit-6,Zone 3",Deposit Works,3,2020-21,2020-21 BR/2020-21/10672,Road Cut,Completed,BR-Bus Route Roads,30,975000,Restoration of Road Cut made by OFC department at Various Streets in Zone 3,Deposit Works,3,2020-21,2020-21 NC/2020-21/12288,Buildings,Completed,NC-MADHAVARAM,30,159000,"Construction of Shredding Machine platform and Providing Inspection Chamber Arrangements for Micro Composting Center in Secreteriats officers colony in Division-30, Unit-8, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/12299,Buildings,Completed,NC-MADHAVARAM,30,62600,"Provinding Ramp and Inspection Chamber Arrangements for Micro Composting Center in Masilamani nagar in Division-30, Unit-8, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13730,Parks,Completed,NC-MADHAVARAM,30,33800,"Annual Maintenance Extention for November 2020 Sivasakthi nagar Park at Sivasakthi Nagar 2nd Main road in Div-30, Unit-8, Zone - 3 Area =830.00 Sq.m",Own Sources,3,2020-21,2021-22 NC/2020-21/13731,Parks,Completed,NC-MADHAVARAM,30,49000,"Annual Maintenance Extention for November 2020KVT (Phase III) Park at V.S Mani Nagar in Div-30, Unit-8, Zone - 3 Area =1485.00Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13732,Parks,Completed,NC-MADHAVARAM,30,32700,"Annual Maintenance Extention for November 2020KVT (Phase II) Park at V.S Mani Nagar in Div-30, Unit-8, Zone - 3 Area =372.00Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13733,Parks,Completed,NC-MADHAVARAM,30,55000,"Annual Maintenance Extention for November 2020 VRD Nagar Park at VRD Nagar 1st street in Div-30, Unit-8, Zone - 3 Area =3375.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13734,Parks,Completed,NC-MADHAVARAM,30,32000,"Annual Maintenance Extention for November 2020KVT (Phase I) Park at V.S Mani Nagar in Div-30, Unit-8, Zone - 3 Area =537.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13735,Parks,Completed,NC-MADHAVARAM,30,57000,"Annual Maintenance Extention for November 2020 Ring Road Housing Sector Park at Ring Road Housing Sector 1st Main Road in Div-30, Unit-8, Zone - 3 Area =1780.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13736,Parks,Completed,NC-MADHAVARAM,30,31800,"Annual Maintenance Extention for November 2020 RC flats (Arul Nagar) Park at MMC Main Road in Div-30, Unit-8, Zone - 3 Area =1000.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/2924,Buildings,Completed,NC-MADHAVARAM,30,604000,"REPAIRS AND IMPORVEMENTS TO THE EXISTING RRC AT SECRETERIATS OFFICERS COLONY IN DIV-30, UNIT-8, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/2925,Buildings,Completed,NC-MADHAVARAM,30,886000,"Proposed construction of Micro Composting Yard Cum material Recovery Facility in RRC Campus @ Secreteriat Officers Colony in Dn-30, Unit-08, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2928,Buildings,Completed,NC-MADHAVARAM,30,2029000,"Construction of Compound wall and Water Supply arrangements for OSR land at Masilamani nagar in Division-30, Unit-8, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/2966,Buildings,Completed,NC-MADHAVARAM,30,2076000,"Proposed Construction of Micro Composting Centre at Masilamani Nagar in Dn-30,Unit-8,Zone-03.",Own Sources,3,2020-21,2020-21 NC/2020-21/3705,Storm Water Drain,Completed,NC-MADHAVARAM,30,320000,"Desilting Works and Minor Repair work at S.V.Kovil Street, VRD Nagar 1st main road, Pukraj nagar 4th street, Pukraj nagar 6th street,Pukraj nagar to bharathiyar street Connection, Padmavathi nagar 1st main road, Padmavathi nagar 2nd main road, Madhavaram Milk Colony Road, Rajaji Street,Bharathiyar main road, Bharthiyar Street Extension, Mariamman Kovil Street, Aringar Anna Street, Mohan Garden, In Division-30, Unit-8, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/3706,Storm Water Drain,Completed,NC-MADHAVARAM,30,676000,"Desilting Works and Minor Repair work at MRH Road In Division-30, Unit-8, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/4873,Bridges,Completed,NC-MADHAVARAM,30,503000,"Providing Sewage Connection and Water Supply Arrangements for the Public Convenience at Madhavaram Bus Stand (inside) in Division-30, Unit-8, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/9570,Buildings,Completed,NC-MADHAVARAM,30,604000,"Proposed Amma Mini Clinic in existing Division-30 office (converting CI Room and CI Store Room) at MRH Road in Division-30, Unit-8, Zone-3.",Own Sources,3,2020-21,2020-21 NC/2020-21/13423,Buildings,Completed,NC-MADHAVARAM,31,50000,"REPAIRS TO STROM WATER DRAIN AT KKR NAGAR 2ND MAIN ROAD, DHANSING MEASTRY ST, KANNAPURAM 3RD STREET IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13426,Buildings,Completed,NC-MADHAVARAM,31,55000,"Repairs and Providing Street Furniture at ambedkar nagar main road, nagathamman kovil st and other streets in Dn -31,unit-08, Zone-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/13737,Parks,Completed,NC-MADHAVARAM,31,79000,"Annual Maintenance Extention for November 2020 KKR Garden Park at KKR Garden 2nd Main Road in Div-31, Unit-8, Zone - 3 Area =4315.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13738,Parks,Completed,NC-MADHAVARAM,31,93828,"Annual Maintenance Extention for November 2020 KKR Nagar Park at KKR Nagar 1st Main Road in Div-31, Unit-8, Zone - 3 Area =4035.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13739,Parks,Completed,NC-MADHAVARAM,31,32000,"Annual Maintenance Extention for November 2020 RC Flats Park at MRH Road in Div-31, Unit-8, Zone - 3 Area =350.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/2275,Buildings,Completed,NC-MADHAVARAM,31,180000,"Improvements work to PC at Muthumariamman kovil st in Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2277,Buildings,Completed,NC-MADHAVARAM,31,61900,Improvements work to PC at Muthumariamman kovil st (inside burial ground)Zone-3,Own Sources,3,2020-21,2020-21 NC/2020-21/2278,Buildings,Completed,NC-MADHAVARAM,31,60000,"Improvements work to PC at KKR Estate, Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2279,Buildings,Completed,NC-MADHAVARAM,31,152000,"Improvements work to PC at Maa.Po.Vedha Street, Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2280,Buildings,Completed,NC-MADHAVARAM,31,61000,"Improvements work to PC at Ambedkar nagar 2nd main road, Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2281,Buildings,Completed,NC-MADHAVARAM,31,111800,"Improvements work to PC at Kannabiran kovil street (indital company ), Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2283,Buildings,Completed,NC-MADHAVARAM,31,75700,"Improvements work to PC at Kannabiran kovil street in Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2284,Buildings,Completed,NC-MADHAVARAM,31,74000,"Improvements work to PC at Jangri shop, Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/2285,Buildings,Completed,NC-MADHAVARAM,31,180000,"Improvements work to PC at Pandiyan street, Dn-31, Unit-8, Zone-3",Own Sources,3,2020-21,2020-21 NC/2020-21/3679,Buildings,Completed,NC-MADHAVARAM,31,579000,"Desilting of Strom Water Drain and Side drain at M.R.H. Road (From Moolakadai to T.V.K 1st street) & MMC ROAD IN DIV-31, UNIT-8, ZONE-3 (2020)",Own Sources,3,2020-21,2020-21 NC/2020-21/3680,Buildings,Completed,NC-MADHAVARAM,31,497000,"Desilting of Side Drain and Strom Water Drain at Pandian St, Muthumariamman Koil St, Ambedkar nagar main road, Udaiyar thottam 6th street, Dhansingh meastry street, T.V.K 1st street, Jangiri Shop & Other Streets IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/3691,Buildings,Completed,NC-MADHAVARAM,31,403000,"Desilting of Side Drain and Strom Water Drain at KKR Garden 2nd Main Road, Rizwan road, Kannapuram 1st street , KKR Garden 10TH Street, Palaniappa nagar 5th street, K.P Garden, Nagathamman kovil street, & Other Streets IN DIV-31, UNIT-8, ZONE-3",Own Sources,3,2020-21,2020-21 NC/2020-21/3939,Buildings,Completed,NC-MADHAVARAM,31,160000,"PROVIDING WATER SUPPLY ARRANGEMENT TO AMMA UNAVAGAM AT MUTHUMARIAMMAN KOVIL ST IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/3941,Buildings,Completed,NC-MADHAVARAM,31,160000,"PROVIDING WATER SUPPLY ARRANGEMENT TO UPHC AT KANNABIRAN KOVIL ST IN DN-31, UNIT-8, ZONE-3",Own Sources,3,2020-21,2021-22 NC/2020-21/5923,Buildings,Completed,NC-MADHAVARAM,31,634000,"PROPOSED TO MORDENISE THE EXISTING ICDS (CENTER NO : 33603150405) BUILDING AT MUTHUMARIAMMAN KOVIL ST IN DIV-31, UNIT-8, ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/9587,Buildings,Completed,NC-MADHAVARAM,31,742000,"PROVIDING MINI CLINIC AT PALANIAPPA NAGAR 5TH STREET (INSIDE OF DIVISION OFFICE) IN DIV-31,UNIT-8,ZONE-3.",Own Sources,3,2020-21,2021-22 NC/2020-21/9846,Buildings,Completed,NC-MADHAVARAM,31,124000,"ADDITIONAL IMPROVEMENTS TO MINI CLINIC AT PALANIAPPA NAGAR 5TH STREET ( Old Unit Office) IN DIV-31,UNIT-8, ZONE-3.",Own Sources,3,2020-21,2021-22 BR/2020-21/10663,Road Cut,Completed,BR-Bus Route Roads,32,942000,"Restoration of Roadcut made by OFC companies at various street in Unit-8,Zone 3",Deposit Works,3,2020-21,2020-21 NC/2020-21/13740,Parks,Completed,NC-MADHAVARAM,32,51000,"Annual Maintenance Extention for November 2020 Teacher's Colony Park at Teacher's Colony 4th cross street in Div-32, Unit-8, Zone - 3 Area =1255.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13741,Parks,Completed,NC-MADHAVARAM,32,33900,"Annual Maintenance Extention for November 2020 Teacher's Colony Park at Teacher's Colony 6th main road in Div-32, Unit-8, Zone - 3 Area = 665.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/3702,Storm Water Drain,Completed,NC-MADHAVARAM,32,491000,"DESILTING OF SIDE DRAIN at Teachers Colony 5th Main road, Thiruvallur St, Vivekananda St, Nethaji St,Kadappah Road,Amman koil St,Bajanai Koil St, Ashoka St,Kamaraj St & Villivakkam Road in Div-32, Unit-8, Zone - 3",Own Sources,3,2020-21,2020-21 NC/2020-21/3704,Storm Water Drain,Completed,NC-MADHAVARAM,32,502000,"DESILTING OF SIDE DRAIN AT Gangaiamman Koil street,V.O.C. street, Lakshmi Narayana Perumal Koil St,Bharathiar St,Thilagar St, IN DIV-32, UNIT-8, ZONE -3",Own Sources,3,2020-21,2020-21 NC/2020-21/9562,Buildings,Completed,NC-MADHAVARAM,32,416000,"Proposed converted new Amma mini clinic to the exisitng division office building (E-Seva and CI office) at Kadappa road in Dn-32, Unit-08, Zone-03.",Own Sources,3,2020-21,2021-22 NC/2020-21/13742,Parks,Completed,NC-MADHAVARAM,33,54000,"Annual Maintenance Extention for November 2020 Thanikachalam nagar Park Thanikachalam nagar 'B' block 5/2 cross street in Div-33, Unit-8, Zone - 3 Area = 1221.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13743,Parks,Completed,NC-MADHAVARAM,33,34000,"Annual Maintenance Extention for November 2020S elvam Nagar Park Selvam Nagar in Div-33, Unit-8, Zone - 3 Area = 743 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13744,Parks,Completed,NC-MADHAVARAM,33,34000,"Annual Maintenance Extention for November 2020 VGP Nagar Park VGP Nagar Main Road in Div-33, Unit-8, Zone - 3 Area = 1000.00 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/13745,Parks,Completed,NC-MADHAVARAM,33,34900,"Annual Maintenance Extention for November 2020 Thanikachalam Nagar Park at Thanikachalam Nagar 80 feet road in Div-33, Unit-8, Zone - 3 Area = 951 Sq.m",Own Sources,3,2020-21,2020-21 NC/2020-21/1877,Roads,Completed,NC-MADHAVARAM,33,224000,"Additional Damaged Road at VPC Nagar 1st Part in Division-33, Unit-8, Zone-3.",Grants,3,2020-21,2020-21 NC/2020-21/1878,Roads,Completed,NC-MADHAVARAM,33,808000,"Additional Damaged Road at Patel street in Division-33, Unit-8, Zone-3.",Grants,3,2020-21,2020-21 NC/2020-21/1879,Roads,Completed,NC-MADHAVARAM,33,1274000,"Additional Damaged Road at Prakash Nagar 1st cross street in Division-33, Unit-8, Zone-3.",Grants,3,2020-21,2020-21 NC/2020-21/1882,Roads,Completed,NC-MADHAVARAM,33,997000,"Additional Damaged Road at Prakash Nagar 2ND cross street in Division-33, Unit-8, Zone-3.",Grants,3,2020-21,2020-21 NC/2020-21/2005,Roads,Completed,NC-MADHAVARAM,33,481000,"Additional Damage Road Work at Prakash Nagar 2nd Main Road in Division - 33 , Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2006,Roads,Completed,NC-MADHAVARAM,33,241000,"Additional Damage Road Work at Valliammai Nagar Extn in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2007,Roads,Completed,NC-MADHAVARAM,33,314000,"Additional Damage Road Work at Vidhya Nagar Main Road in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2009,Roads,Completed,NC-MADHAVARAM,33,149000,"Additional Damage Road Work at Balakrishna Nnagar 3rd Street in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2011,Roads,Completed,NC-MADHAVARAM,33,1144000,"Additional Damage Road at Thanikachalam Nagar B Blk 5/2 Cross Street in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2013,Roads,Completed,NC-MADHAVARAM,33,297000,"Additional Damage Road at Sriraman Salai Part in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2014,Roads,Completed,NC-MADHAVARAM,33,619000,"Additional Damage Road at Selvam Nagar Main road in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2015,Roads,Completed,NC-MADHAVARAM,33,276000,"Additional Damage Road at Raghavendra Nagar Ext Part in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2023,Roads,Completed,NC-MADHAVARAM,33,1322000,"Additional Damage Road work CC road at Munusamy Nagar Extn 1st Street in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2024,Roads,Completed,NC-MADHAVARAM,33,1581000,"Additional Damage Road work (CC Road) at Munusamy Nagar Extn 2nd Street in Division - 33, Unit - 8, Zone - 3",Grants,3,2020-21,2020-21 NC/2020-21/2961,Buildings,Completed,NC-MADHAVARAM,33,1210000,"Proposed construction of Micro Composting Yard Cum Material Recovery Facility in RRC Campus @Valliammai Nagar Main Road In Dn-33,Unit-08,Zone-03.",Own Sources,3,2020-21,2020-21 NC/2020-21/3710,Roads,Completed,NC-MADHAVARAM,33,604000,"DESILTING AND MINOR REPAIR WORK FOR STROM WATER DRAIN AT PERIYAR NAGAR MAIN ROAD,BALAKRISHNA NAGAR MAIN ROAD,ANNAPOORNA NAGAR MAIN ROAD,SRINIVASAN NAGAR MAIN ROAD,PRAKASH NAGAR 3RD MAIN ROAD AND OTHER STREETS IN DIV-33, UNIT-8, ZONE-3 (2020)",Own Sources,3,2020-21,2021-22 NC/2020-21/3711,Roads,Completed,NC-MADHAVARAM,33,715000,"DESILTING AND MINOR REPAIR WORK FOR SIDE DRAIN AT VGP NAGAR MAIN ROAD, KAMARAJAR NAGAR MAIN ROAD,MAHATMA GANDHI STREET, THANIKACHALAM NAGAR 'A' BLOCK 2ND MAINROAD ,THANIKACHALAM NAGAR 'B' BLOCK 5TH MAINROAD,ANNA STREET ,SWAMY RAMALINGA COLONY B BLK MAINROAD,SELVAM NAGAR 6/3 CROSS STREETAND OTHER STREETS IN DIV-33, UNIT-8, ZONE-3 (2020)",Own Sources,3,2020-21,2021-22 NC/2020-21/4683,Roads,Completed,NC-MADHAVARAM,33,1526000,"Restoration of Road Cut Made by CMWSSB From Prakash Nagar Main Road to Thanikachalam Nagar by rerouting (From Madurai Manavalan Nagar Main Road to Prakash Nagar Main Road) in Dn - 33, Unit - 8, Zone -3.",Deposit Works,3,2020-21,2021-22 NC/2020-21/9189,Storm Water Drain,Completed,NC-MADHAVARAM,33,300000,"Manufacturing and Replacing to the existing side drain at Swamy Ramalinga colony in Dn-33, Unit-08, Zone-03.",Own Sources,3,2020-21,2020-21 NC/2020-21/9190,Storm Water Drain,Completed,NC-MADHAVARAM,33,358000,"Providing RCC HUME pipe to drain out the rain water from low laying area at Elizabeth Nagar,AnnaPoorna Nagar, Ragavendra Nagar,Gandhi Nagar And Chelliya nagar in Dn-33, Unit-08, Zone-03",Own Sources,3,2020-21,2020-21 NC/2020-21/9467,Buildings,Completed,NC-MADHAVARAM,33,600000,"Proposed Amma mini clinic to the exisitng division office building (converting S.I Rooam And C.I Room )at Thanikachalam Ngar B Blk 5th Main road 2nd Cross Street in Division-33, Unit-8, Zone-3.",Own Sources,3,2020-21,2021-22 L/2020-21/6195,Electrical,Completed,L-Electrical,34,645300,"Supply and Erection of 13 Nos of new 6 mtr lamp post with single straight bracket and laying of 436 mtr of 2 x25 sqmm Alu U.G cable at Kattabomman Main Road Ext in Div-34, Zone -4",Own Sources,4,2020-21,2020-21 ND/2020-21/3810,Storm Water Drain,Completed,ND-TONDIARPET,34,398000,"Desilting of storm water drain at Various Street in DN-34,U-09,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3812,Storm Water Drain,Completed,ND-TONDIARPET,34,263000,"Minor Repair Work of storm water drain at Various Street in DN-34,U-09,Z-04",Own Sources,4,2020-21,2021-22 BR/2020-21/2990,Roads,Completed,BR-Bus Route Roads,35,1006000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Thiruvalluvar Salai in Dn-35, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/2991,Roads,Completed,BR-Bus Route Roads,35,3654000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Muthamil Nagar North Avenue in Dn-35, Zone IV",Grants,4,2020-21,2020-21 ND/2020-21/3103,Roads,Completed,ND-TONDIARPET,35,91000,"Relaying of BT Additional Road Muthamil Nagar 6th Block 158th street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3104,Roads,Completed,ND-TONDIARPET,35,138000,"Relaying of BT Additional Road Muthamil Nagar 6th Block 159 th street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3105,Roads,Completed,ND-TONDIARPET,35,124000,"Relaying of BT Additional Road Muthamil Nagar 5TH Block 128 th street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3106,Roads,Completed,ND-TONDIARPET,35,145000,"Relaying of BT Additional Road Muthamil Nagar 5TH Block 129 th street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3109,Roads,Completed,ND-TONDIARPET,35,1296000,"Relaying of CC Additional Road KKD Nagar 2nd block 1st street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3110,Roads,Completed,ND-TONDIARPET,35,923000,"Relaying of CC Additional Road KKD Nagar 2nd Block 3rd Street street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3111,Roads,Completed,ND-TONDIARPET,35,165000,"Relaying of CC Additional Road Teachers Colony 1st Street (Part) in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3112,Roads,Completed,ND-TONDIARPET,35,239000,"Relaying of CC Additional Road Chinnathambiran street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3113,Roads,Completed,ND-TONDIARPET,35,1123000,"Relaying of CC Additional Road Srinivasa Perumal Kovil street (Kodungaiyur) in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3114,Roads,Completed,ND-TONDIARPET,35,1059000,"Relaying of CC Additional Road Muthamil Nagar 7th Block 175th street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3115,Roads,Completed,ND-TONDIARPET,35,1118000,"Relaying of CC Additional Road KKD Nagar 2nd Block 4th Street in Div -35,Unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3657,Storm Water Drain,Completed,ND-TONDIARPET,35,229999,"Desilting of storm water drain at Various Street in DN-35,U-09,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3684,Storm Water Drain,Completed,ND-TONDIARPET,35,493000,"Improvements and Repair SWD at Thiruvalluvar Salai,Ambedkar Street,Sidco 1st Main Road, Vadivudaiamman Kovil street,Anna Salai Main Road in Div-35,Unit-09,Zone-04",Own Sources,4,2020-21,2021-22 ND/2020-21/4020,Buildings,Completed,ND-TONDIARPET,35,476000,"Improvements to RRC Center at muthamil nagar 50th Street in Div-35, Unit-09, Zone-04.",Own Sources,4,2020-21,2021-22 BR/2020-21/2993,Roads,Completed,BR-Bus Route Roads,36,4170000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Sidco Main Road in Dn-36, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/2995,Roads,Completed,BR-Bus Route Roads,36,4935000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at MKB Nagar West Avenue Road up to middle of bridge portion in Dn-36, Zone IV",Grants,4,2020-21,2020-21 ND/2020-21/3055,Roads,Completed,ND-TONDIARPET,36,3589000,Relaying CC Road at SA Colony 1st Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3056,Roads,Completed,ND-TONDIARPET,36,3517000,Relaying CC Road at SA Colony 3rd Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3058,Roads,Completed,ND-TONDIARPET,36,2928000,Relaying CC Road at SA Colony 5th Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3059,Roads,Completed,ND-TONDIARPET,36,1264000,Relaying CC Road at Pudhu Nagar 7th Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3060,Roads,Completed,ND-TONDIARPET,36,1715000,Relaying CC Road at Pudhu Nagar 8th Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3070,Roads,Completed,ND-TONDIARPET,36,1252000,Relaying BT Road at Sastri Nagar Anna Salai in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3084,Roads,Completed,ND-TONDIARPET,36,516000,Relaying BT Road at MR Nagar 1st Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3086,Roads,Completed,ND-TONDIARPET,36,1722000,Relaying BT Road at Sharmanagar 1st Main Road in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3088,Roads,Completed,ND-TONDIARPET,36,511000,Relaying BT Road at TV Nagar 3rd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3116,Roads,Completed,ND-TONDIARPET,36,2101000,Relaying BT Road at MR Nagar 3rd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3117,Roads,Completed,ND-TONDIARPET,36,350000,Relaying BT Road at Meenambal Service Road in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3118,Roads,Completed,ND-TONDIARPET,36,424000,Relaying BT Road at TV Nagar 7th Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3119,Roads,Completed,ND-TONDIARPET,36,856000,Relaying BT Road at TV Nagar 2nd Main Road in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3120,Roads,Completed,ND-TONDIARPET,36,126000,Relaying BT Road at TV Nagar 5th Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3121,Roads,Completed,ND-TONDIARPET,36,427000,Relaying BT Road at TV Nagar 2nd Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3123,Roads,Completed,ND-TONDIARPET,36,381000,Relaying BT Road at TV Nagar 3rd Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3124,Roads,Completed,ND-TONDIARPET,36,376000,Relaying BT Road at TV Nagar 10th Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3125,Roads,Completed,ND-TONDIARPET,36,187000,Relaying BT Road at TV Nagar 1st Main Road 4th Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3126,Roads,Completed,ND-TONDIARPET,36,472000,Relaying BT Road at TV Nagar 1st Main Road 5th Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3127,Roads,Completed,ND-TONDIARPET,36,485000,Relaying BT Road at MKB Nagar 15th West Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3128,Roads,Completed,ND-TONDIARPET,36,446000,Relaying BT Road at MKB Nagar 16th West Cross Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2020-21 ND/2020-21/3764,Storm Water Drain,Completed,ND-TONDIARPET,36,795000,Desilting For Storm Water Drain at Various Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2021-22 ND/2020-21/3765,Storm Water Drain,Completed,ND-TONDIARPET,36,418000,Minor Repair Work For Storm Water Drain at Various Street in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2021-22 ND/2020-21/4010,Buildings,Completed,ND-TONDIARPET,36,660000,Improvement to Segrigation Center in Mennambal Salai Service Road in Dn-36 U-09 Z-04,Own Sources,4,2020-21,2021-22 BR/2020-21/2996,Roads,Completed,BR-Bus Route Roads,37,5219000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at MKB nagar Centre Avenue in Dn-37, Zone IV",Grants,4,2020-21,2020-21 L/2020-21/6461,Electrical,Completed,L-Electrical,37,8345000,"SUPPLY,ERECTION, TESTING AND COMMISSIONING OF 630KVA TRANSFORMER AND AVIALING OF HT SUPPLY FOR 400KVA INCINERATOR PLANT FACILITY AT KODUNGAIYUR DUMPING STATION AT DIV-37,ZONE 4",Own Sources,4,2020-21,2020-21 ND/2020-21/0640,Roads,Completed,ND-TONDIARPET,37,744000,"Relaying of BT Road at Abirami avenue 14th street in div-37,unit-09,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/0646,Roads,Completed,ND-TONDIARPET,37,1958000,"Relaying of road at North avenue road in Div-37,Unit-09,Zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/0648,Roads,Completed,ND-TONDIARPET,37,1710000,"Relaying of MKB Nagar 4th main road in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/0654,Roads,Completed,ND-TONDIARPET,37,96000,"Relaying of road at MKB Nagar 14th east cross street in div-37,Unit-9,Zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/0655,Roads,Completed,ND-TONDIARPET,37,855000,"Relaying of road MKB Nagar 4th cross street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/0656,Roads,Completed,ND-TONDIARPET,37,212000,"Relaying of road anna cross street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/3824,Storm Water Drain,Completed,ND-TONDIARPET,37,513000,"Minor Repair Work of storm water drain at Various Street in DN-37,U-09,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3826,Storm Water Drain,Completed,ND-TONDIARPET,37,665000,"Desilting Work of storm water drain at Various Street in DN-37,U-09,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/4254,Buildings,Completed,ND-TONDIARPET,37,245000,"Improvements of Mullai Nagar Burial Ground compost yard in Dn-37,U-09,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/4255,Buildings,Completed,ND-TONDIARPET,37,529000,"Improvements of North Avenue Compost Yard in Dn-37,U-09,Z-IV",Own Sources,4,2020-21,2021-22 ND/2020-21/5568,Roads,Completed,ND-TONDIARPET,37,980000,"Relaying of BT Road at Ramakrishna street in div-37, Unit-09, Zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5575,Roads,Completed,ND-TONDIARPET,37,407000,"Relaying of BT Road at Agathiyar street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5607,Roads,Completed,ND-TONDIARPET,37,1064000,"Relaying of BT Road at jawahar street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5609,Roads,Completed,ND-TONDIARPET,37,311000,"Relaying of BT Road at jawahar cross street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5610,Roads,Completed,ND-TONDIARPET,37,1084000,"Relaying of BT road at KKD Nagar 7th Block 1st Street (Part) in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5614,Roads,Completed,ND-TONDIARPET,37,167011,"Relaying of BT road at KKD Nagar 6th Block 4th Street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5617,Roads,Completed,ND-TONDIARPET,37,136000,"Relaying of BT Road at KKD Nagar 9th Block 2nd Street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5628,Roads,Completed,ND-TONDIARPET,37,522000,"Relaying of BT Road at kkd nagar 10th main road in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5652,Roads,Completed,ND-TONDIARPET,37,501000,"Relaying of CC Road at Damodaran nagar 2nd streetin div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5653,Roads,Completed,ND-TONDIARPET,37,734000,"Relaying of CC Road at Damodaran nagar 4th street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5654,Roads,Completed,ND-TONDIARPET,37,591000,"Relaying of CC Road at Damodaran nagar 4th cross street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5656,Roads,Completed,ND-TONDIARPET,37,717000,"Relaying of CC Road at MGR Nagar 1st cross street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5657,Roads,Completed,ND-TONDIARPET,37,825000,"Relaying of CC Road at MGR Nagar 2nd cross street in div-37,unit-09,zone-04",Own Sources,4,2020-21,2020-21 ND/2020-21/5658,Roads,Completed,ND-TONDIARPET,37,382000,"Relaying of CC Road at KKD Nagar 8th block 4th lane in div-37,unit-09,zone-04",Own Sources,4,2020-21,2021-22 ND/2020-21/6825,Buildings,Completed,ND-TONDIARPET,37,525000,"IMPROVEMENTS TO ICDS AY UDHASURIYAN NAGAR CENTRE NO. 33603120503 IN DIVISION -37, UNIT-9,ZONE-4",Own Sources,4,2020-21,2021-22 ND/2020-21/6826,Buildings,Completed,ND-TONDIARPET,37,585000,"Improvement of Chennai primary school at MKB Nagar 14th east cross street (Night Shelter) in Div-37,unit-09,zone-04",Own Sources,4,2020-21,2021-22 Q/2020-21/1745,Buildings,Completed,Q-Solid Waste Management,37,2648000,"Construction of Electrical panel Room for C&D waste Prossing at Kodungaiyur Dumping Ground in Dn-37, Zone-4.",Own Sources,4,2020-21,2021-22 Q/2020-21/3439,Buildings,Completed,Q-Solid Waste Management,37,4170000,"Construction of compound wall (Western side of proposed incinerator) near Weigh Bridge(Gate-1) at Kodungaiyur Dumping ground in Dn-37,Z-4",Own Sources,4,2020-21,2021-22 Q/2020-21/3562,Buildings,Completed,Q-Solid Waste Management,37,1570000,"Construction of Electrical Panel room for 50MT Incinerator at Kodungaiyur Dumping ground in Dn-37,Zone-4",Own Sources,4,2020-21,2020-21 BR/2020-21/2999,Roads,Completed,BR-Bus Route Roads,38,5276000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Vaithyanathan Bridge in Dn-38, Zone IV",Grants,4,2020-21,2020-21 ND/2020-21/3077,Buildings,Completed,ND-TONDIARPET,38,605000,"Relaying of CC Road at Rajasekaran nagar 1st street in Div-38, unit-9, zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3079,Buildings,Completed,ND-TONDIARPET,38,580000,"Relaying of CC Road at Rajasekaran nagar 2nd street in Div-38, unit-9, zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3080,Buildings,Completed,ND-TONDIARPET,38,574000,"Relaying of CC Road at Rajasekaran nagar 3rd street in Div-38, unit-9, zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3081,Buildings,Completed,ND-TONDIARPET,38,587000,"Relaying of CC Road at Rajasekaran nagar 4th street in Div-38, unit-9, zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3082,Buildings,Completed,ND-TONDIARPET,38,636000,"Relaying of CC Road at Rajasekaran nagar 5th street in Div-38, unit-9, zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3083,Buildings,Completed,ND-TONDIARPET,38,1414000,"Relaying of CC Road at Sundram nagar 1st street in Div-38, unit-9, zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3087,Roads,Completed,ND-TONDIARPET,38,153842,"Relying of BT road at Durga Devi Nagar 4th cross street in Div-38,unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 ND/2020-21/3667,Roads,Completed,ND-TONDIARPET,38,2040000,"RELAYING OF CC ROAD AT SUNDRAM PILLAI NAGAR 1ST MAIN ROAD IN DN-38, UNIT-09, ZONE-4",MLACDS,4,2020-21,2020-21 ND/2020-21/3668,Roads,Completed,ND-TONDIARPET,38,980000,"RELAYING OF CC ROAD AT SUNDRAM PILLAI NAGAR 1ST CROSS STREET ROAD IN DN-38, UNIT-09, ZONE-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/3669,Roads,Completed,ND-TONDIARPET,38,890000,"RELAYING OF CC ROAD AT SUNDRAM PILLAI NAGAR 2ND CROSS STREET ROAD IN DN-38, UNIT-09, ZONE-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/3670,Roads,Completed,ND-TONDIARPET,38,1050000,"RELAYING OF CC ROAD AT SUNDRAM PILLAI NAGAR 3RD CROSS STREET ROAD IN DN-38, UNIT-09, ZONE-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/3671,Roads,Completed,ND-TONDIARPET,38,1120000,"RELAYING OF CC ROAD AT SUNDRAM PILLAI NAGAR 4TH CROSS STREET ROADIN DN-38, UNIT-09, ZONE-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/3672,Roads,Completed,ND-TONDIARPET,38,1320000,"RELAYING OF CC ROAD AT SUNDRAM PILLAI NAGAR 1ST STREET ROAD IN DN-38, UNIT-09, ZONE-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/3673,Roads,Completed,ND-TONDIARPET,38,1590000,"RELAYING OF CC ROAD AT SUNDRAM PILLAI NAGAR 2ND STREET ROAD IN DN-38, UNIT-09, ZONE-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/3749,Storm Water Drain,Completed,ND-TONDIARPET,38,527000,"Desilting of storm water drain at Various Street in DN-38,U-09,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3750,Storm Water Drain,Completed,ND-TONDIARPET,38,304000,"Minor Repair Work of storm water drain at Various Street in DN-38,U-09,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3752,Roads,Completed,ND-TONDIARPET,38,380000,"Laying of cc road at Rajiv gandhi lane in Div-38,Unit-09,Zone-04.",Own Sources,4,2020-21,2021-22 ND/2020-21/4743,Roads,Completed,ND-TONDIARPET,38,776000,"Relying of BT road at Harbour Colony 2nd Street (Part) in Div-34,unit-09,Zone-04.",Own Sources,4,2020-21,2020-21 BR/2020-21/3001,Roads,Completed,BR-Bus Route Roads,39,1739000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at North Terminous Road in Dn-39, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/3003,Roads,Completed,BR-Bus Route Roads,39,17176000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Surya Narayana (Chetty) Street in Dn-39 ,43 & 50, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/3005,Roads,Completed,BR-Bus Route Roads,39,6823000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Thiruvottriyur High Road(From the Jn of Rettai Kuli Street to Ramanujam Street) in Dn-39,40,42 & 48, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/7408,Roads,Completed,BR-Bus Route Roads,39,2130000,"Providing Crash Barrier Center Median at SN Chetty Salai ( From the jn of Jeevarathinam Salai to jn of Hazrat Dargah ) in Div -39 & 43, Zone -4.",Own Sources,4,2020-21,2020-21 BR/2020-21/7409,Roads,Completed,BR-Bus Route Roads,39,2000000,"Providing Crash Barrier Center Median at SN Chetty Salai ( From the jn of Hazrat Dargah to jn of Indian Oil Petrol Pump ) in Div -39 & 43, Zone -4.",Own Sources,4,2020-21,2021-22 BR/2020-21/7410,Roads,Completed,BR-Bus Route Roads,39,2350000,"Providing Crash Barrier Center Median at SN Chetty Salai (From the Indian Oil Petrol Pump to jn of Poondi Thangammal Street ) in Div -39 & 43, Zone -4.",Own Sources,4,2020-21,2020-21 ND/2020-21/0594,Buildings,Completed,ND-TONDIARPET,39,275000,"REPAIRS AND MAINTENANCE OF 731 CHSS AT T.H.ROAD IN DN-39,U-10,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/2315,Buildings,Completed,ND-TONDIARPET,39,2490000,Construction of Compost Yard (M.C.C) at S.N chetty street in div-39 unit-10 Zone-4,Own Sources,4,2020-21,2021-22 ND/2020-21/3241,Roads,Completed,ND-TONDIARPET,39,1465000,"Restoration of roadcut made by CMWSSB,and relaying the road at Cheriyan nagar main street in dn-39 un-10,zn-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3252,Roads,Completed,ND-TONDIARPET,39,1230000,"Relaying for B.T road at Poondi thangammal street in div-39,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3262,Roads,Completed,ND-TONDIARPET,39,3269000,"Relaying for B.T road at A.E koil street in div-39,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3265,Roads,Completed,ND-TONDIARPET,39,1295000,"Relaying for B.T road at Irusappa main street in div-39,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3267,Roads,Completed,ND-TONDIARPET,39,1096000,"Relaying for B.T road at Butchammal street in div-39,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3269,Roads,Completed,ND-TONDIARPET,39,629000,"Relaying for b.t road at Q.Q Scheme road in div-39,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3278,Roads,Completed,ND-TONDIARPET,39,1223000,"Relaying for b.t road at washer varadappa street in div-39,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3279,Roads,Completed,ND-TONDIARPET,39,252000,"Relaying for b.t road at Market form 5th street in div-39,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3286,Roads,Completed,ND-TONDIARPET,39,1863000,"Restoration of roadcut made by CMWSSB,and relaying the road at Kannu street in dn-39 un-10,zn-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3288,Roads,Completed,ND-TONDIARPET,39,719000,"Restoration of roadcut made by CMWSSB,and relaying the road at Irusappa 2nd street in dn-39 un-10,zn-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3289,Roads,Completed,ND-TONDIARPET,39,632000,"Restoration of roadcut made by CMWSSB,and relaying the road at Veeraraghavan street in dn-39 un-10,zn-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3895,Storm Water Drain,Completed,ND-TONDIARPET,39,263000,"Desilting of Storm Water Drain at Various Street in DN-39,U-10,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3897,Storm Water Drain,Completed,ND-TONDIARPET,39,565000,"Minor repairs and Improvement Work on Storm water drain at Various Street in DN-39,U-10,Z-04",Own Sources,4,2020-21,2021-22 BR/2020-21/3007,Roads,Completed,BR-Bus Route Roads,40,711000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at New Vaithyanathan Street in Dn-40, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/3011,Roads,Completed,BR-Bus Route Roads,40,1584000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at A.A.Road (Tondairpet Bus Depot) in Dn-40, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/3013,Roads,Completed,BR-Bus Route Roads,40,1121000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Arunachaleswarar Koil Street in Dn-40, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/3016,Roads,Completed,BR-Bus Route Roads,40,639000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Seniamman Koil Street in Dn-40, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/3017,Roads,Completed,BR-Bus Route Roads,40,848000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Vaithyanathan Street in Dn-40, Zone IV",Grants,4,2020-21,2020-21 ND/2020-21/0714,Buildings,Completed,ND-TONDIARPET,40,1170000,Supplying 6 Nos of Bio Shredding Machine with 10 HP Motor to Zone IV,Own Sources,4,2020-21,2020-21 ND/2020-21/3270,Roads,Completed,ND-TONDIARPET,40,3304000,"Relaying of b.t road at Kamarajar Street in div-40,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3271,Roads,Completed,ND-TONDIARPET,40,2442000,"Relaying of b.t road at AE Koil Street in div-40,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3273,Roads,Completed,ND-TONDIARPET,40,3265000,"Relaying of b.t road at Cross Road in div-40,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3274,Roads,Completed,ND-TONDIARPET,40,1975000,"Relaying of b.t road at VOC Nagar Market Street in div-40,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3275,Roads,Completed,ND-TONDIARPET,40,704000,"Relaying of b.t road at Ammani Ammal Thottam in div-40,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3280,Roads,Completed,ND-TONDIARPET,40,637077,"Relaying of C.C Road at Seniamman Koil 5th Street in div-40, unit-10, zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3282,Roads,Completed,ND-TONDIARPET,40,339001,"Relaying of C.C Road at VOC Nagar 4th Cross Street in div-40, unit-10, zone-4",Own Sources,4,2020-21,2021-22 ND/2020-21/3283,Roads,Completed,ND-TONDIARPET,40,1415001,"Relaying of C.C Road at VOC Nagar 18th Cross Street in div-40, unit-10, zone-4",Own Sources,4,2020-21,2021-22 ND/2020-21/3284,Roads,Completed,ND-TONDIARPET,40,225000,"Relaying of C.C Road at VOC Nagar 29th Cross Street in div-40, unit-10, zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3738,Storm Water Drain,Completed,ND-TONDIARPET,40,87000,"Desilting of stormwater drain at the various street in div-40,unit-10, zone-4",Own Sources,4,2020-21,2021-22 ND/2020-21/3739,Storm Water Drain,Completed,ND-TONDIARPET,40,176000,"minor repairs to swd at various street in div-40,unit-10,zone-4",Own Sources,4,2020-21,2021-22 BR/2020-21/2986,Roads,Completed,BR-Bus Route Roads,41,7401000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Manali Salai (Part II) in Dn-41, Zone IV",Grants,4,2020-21,2020-21 BR/2020-21/7404,Roads,Completed,BR-Bus Route Roads,41,2350000,"Providing Crash Barrier Center Median at Manali Salai ( From Near canal Jn of Corporation play ground to Near Railway Track Crossing ) in Div -41, Zone -4.",Own Sources,4,2020-21,2020-21 ND/2020-21/3225,Roads,Completed,ND-TONDIARPET,41,599000,"Relaying of b.t road at Cornation nagar 2nd street (marimuthu street) in div-41,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3226,Roads,Completed,ND-TONDIARPET,41,468000,"Relaying of b.t road at Cornation nagar 4th street (kasthuri bai street) in div-41,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3227,Roads,Completed,ND-TONDIARPET,41,514000,"Relaying of b.t road at Cornation nagar 1st street (ramasamy street) in div-41,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3228,Roads,Completed,ND-TONDIARPET,41,710000,"Relaying of b.t road at Cornation nagar 3rd street (parthasarathy street) in div-41,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3229,Roads,Completed,ND-TONDIARPET,41,353000,"Relaying of b.t road at Gandhi street (cornation nagar) in div-41,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3230,Roads,Completed,ND-TONDIARPET,41,881000,"Relaying of b.t road at J.J Nagar A1 street in div-41,unit-10,zone-4",Own Sources,4,2020-21,2020-21 ND/2020-21/3249,Roads,Completed,ND-TONDIARPET,41,796000,"Relaying of C.C road at Kumaran Nagar 1st street in div-41,unit-10,zone-4",Own Sources,4,2020-21,2021-22 ND/2020-21/0644,Buildings,Completed,ND-TONDIARPET,42,330700,"Repairs and Maintainance work at Chennai Girls Higher Secondary School in DN-42,U-10,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/0733,Buildings,Completed,ND-TONDIARPET,42,830000,Supplying and Fixing 11 Nos Weighing Machine and 6Nos of Seiving Machine to Zone IV,Own Sources,4,2020-21,2020-21 ND/2020-21/3744,Storm Water Drain,Completed,ND-TONDIARPET,42,216000,"Minor Repair Work of storm water drain at Various Street in DN-42,U-10,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3746,Buildings,Completed,ND-TONDIARPET,42,168000,"Desilting of storm water drain at Various Street in DN-42,U-10,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/2294,Buildings,Completed,ND-TONDIARPET,43,808000,"Repair and Improvement Work to Compost yard and RRC Center at Hindu Burial Ground in DN-43,U-10,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/2800,Buildings,Completed,ND-TONDIARPET,43,1086000,"Providing Iron Sheet Shed and Other Improvement work to E.B sub Station Office at CDH in Dn-43,U-10,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3095,Roads,Completed,ND-TONDIARPET,43,133000,Vinayagapuram Main Street (Part),Own Sources,4,2020-21,2020-21 ND/2020-21/3097,Roads,Completed,ND-TONDIARPET,43,28000,Kasipuram B Block 11th Street (Part),Own Sources,4,2020-21,2020-21 BR/2020-21/3019,Roads,Completed,BR-Bus Route Roads,44,10042000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Melpatti Ponnappan Street in Dn-44 & 45, Zone IV",Grants,4,2020-21,2020-21 ND/2020-21/3291,Roads,Completed,ND-TONDIARPET,44,337000,"LAYING CC ROAD AT ALAGIRISWAMY 7TH LANE IN DN-44,UNIT-11,ZONE-4.",Own Sources,4,2020-21,2020-21 ND/2020-21/3185,Roads,Completed,ND-TONDIARPET,45,1068000,"NEWLY LAYING CC ROAD AT KAKKANJI COLONY 5TH CROSS STREET AT DIV-45, UNIT-11, ZONE-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3186,Roads,Completed,ND-TONDIARPET,45,512036,"RELAYING CC ROAD AT B V COLONY 28TH STREET (PART) IN DIV-45, UNIT-11, ZONE-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3189,Roads,Completed,ND-TONDIARPET,45,418000,"RELAYING C C ROAD AT B V COLONY 29TH CROSS STREET (PART) IN DIV-45, UNIT-11, ZONE-04",Own Sources,4,2020-21,2021-22 ND/2020-21/7604,Roads,Completed,ND-TONDIARPET,45,2500000,"LAYING C C ROAD WORK ATB V COLONY CROSS STREETS IN DN-45, UNIT-11, ZONE-4",MLACDS,4,2020-21,2021-22 BR/2020-21/5050,Roads,Completed,BR-Bus Route Roads,46,196000,"Attendind Repairs to existing roads & Speed Breaker at Sathya Moorthy Main Road in Dn-46 & Manalai Salai Jn of Ennore High Road in Dn-41, Zone-IV",Deposit Works,4,2020-21,2020-21 BR/2020-21/5838,Roads,Completed,BR-Bus Route Roads,46,2340000,"Providing Crash Barrier Center Median at SathyaMoorthy Nagar Main Road( From North Avenue road to Central Avenue Road) in Div -46, Zone -4.",Own Sources,4,2020-21,2020-21 BR/2020-21/8139,Road Cut,Completed,BR-Bus Route Roads,46,275000,"Restoration of Road cut made byTANGEDCO at Muthu Street in Div -46, Zone -4. Against Challan No.BR/2020-21/0005790 dt-07/09/2020 -Deposite Code -57/0196/2020-21",Deposit Works,4,2020-21,2020-21 ND/2020-21/1886,Roads,Completed,ND-TONDIARPET,46,817000,"Improvement of CC Road at Sadagopar Alwar Street in Div - 46, Unit - 11, Zone IV",Own Sources,4,2020-21,2020-21 ND/2020-21/3643,Storm Water Drain,Completed,ND-TONDIARPET,47,379000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-47,UNIT-11,ZONE-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3646,Storm Water Drain,Completed,ND-TONDIARPET,47,489000,"MINOR REPAIR WORK TO STORM WATER DRAIN AT VARIOUS STREET IN DIVISION-47,UNIT-11,ZONE-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3677,Roads,Completed,ND-TONDIARPET,47,1320000,"RELAYING OF CC ROAD AT KAMARAJAR NAGAR MAIN ROAD IN DN-47, UNIT-11, ZONE-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/3847,Buildings,Completed,ND-TONDIARPET,47,2000000,"Providing Water supply arrangements and Basic infrastructure works to Chennai corporation middle school (budda school) located at kannan street in div-47, unit-11, zone-4.",MLACDS,4,2020-21,2020-21 ND/2020-21/5814,Buildings,Completed,ND-TONDIARPET,47,660000,"CONSTRUCTION OF FISH MARKET AT CANAL ROAD IN DIVISION-47,UNIT-11,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3647,Storm Water Drain,Completed,ND-TONDIARPET,48,137000,"DESILTING OF STORM WATER DRAIN AT VARIOUS STREET IN DN-48,U-11,Z-04",Own Sources,4,2020-21,2021-22 ND/2020-21/3720,Storm Water Drain,Completed,ND-TONDIARPET,48,232000,"MINOR REPAIR WORKS TO STORM WATER DRAIN AT VARIOUS STREET IN DN-48,U-11,Z-04",Own Sources,4,2020-21,2021-22 NE/2020-21/1615,Buildings,Completed,NE-ROYAPURAM,49,330000,"Relaying of BT Road with Paver finisher at G.A Road 3rd lane in Division-49,Unit-12 ,Zone-5",Grants,5,2020-21,2020-21 NE/2020-21/3896,Buildings,Completed,NE-ROYAPURAM,49,470000,"Desilting of Existing SWD at Various Street at Solaiappan Street,Kothandaramar Street,New Thandavarayan Street,Balu Street,Kappal Polu Street,Thandavarayan Street,Bala Arunachalam Street,Sanjeevirayan Street,Venkatachalam Street,Bashyam Street,Grace Garden Main Road,New Kamaraj Nagar 5th Street,Old Amaranji Puram,Thandavarayan Gramani Street,Rajagopal Street,Rajavelu Street, Singara Garden 4th Lane,Singara Garden 5th Lane,Somu 1st Lane,Somu 2nd Lane,Somu 5th Lane,Thandavarayan Street in Div-49,Unit-12,Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/3950,Storm Water Drain,Completed,NE-ROYAPURAM,49,270000,"improvements of storm water Drains At VArious Street In Division-49,Unit-12,Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/4918,Buildings,Completed,NE-ROYAPURAM,49,1480000,"Constructions of motor room providing bore well and water supply arrangement at West Kalmandapam Road ,Old Amaranji Puram Street ,Pudumanai Kuppam,Muthutamil Nagar in division-49, unit 12 ,zone-05",MLACDS,5,2020-21,2021-22 NE/2020-21/1362,Roads,Completed,NE-ROYAPURAM,50,328000,"ROAD CUT AND RELAYING EAST MADHA 4TH STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1364,Roads,Completed,NE-ROYAPURAM,50,328000,"ROAD CUT AND RELAYING EAST MADHA 3RD STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1389,Roads,Completed,NE-ROYAPURAM,50,328000,"ROAD CUT AND RELAYING EAST MADHA 5th STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1390,Roads,Completed,NE-ROYAPURAM,50,328000,"ROAD CUT AND RELAYING EAST MADHA 8TH STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1391,Roads,Completed,NE-ROYAPURAM,50,328000,"ROAD CUT AND RELAYING EAST MADHA 9TH STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1413,Roads,Completed,NE-ROYAPURAM,50,328000,"ROAD CUT AND RELAYING EAST MADHA 2ND STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1414,Roads,Completed,NE-ROYAPURAM,50,328000,"ROAD CUT AND RELAYING EAST MADHA 1ST STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1415,Roads,Completed,NE-ROYAPURAM,50,813000,"ROAD CUT AND RELAYING CORPORATION COLONY 2ND STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1416,Roads,Completed,NE-ROYAPURAM,50,314000,"ROAD CUT AND RELAYING CORPORATION COLONY 3RD STREET IN DIV-50,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1430,Roads,Completed,NE-ROYAPURAM,50,375000,"Road cut and Relaying to CC Road at Venkatesan 1st street in Div-52, Unit-12, Zone-5",Grants,5,2020-21,2020-21 NE/2020-21/1431,Roads,Completed,NE-ROYAPURAM,50,450000,"Road cut and Relaying to CC Road at Venkatesan 2ND street in Div-52, Unit-12, Zone-5",Grants,5,2020-21,2020-21 NE/2020-21/1432,Roads,Completed,NE-ROYAPURAM,50,1717000,"Road cut and Relaying to CC Road at Market Lane in Div-50, Unit-12, Zone-5",Grants,5,2020-21,2020-21 NE/2020-21/1483,Roads,Completed,NE-ROYAPURAM,50,155000,"Repair and maintenance Works in B.T Road at A . J Colony 1st Lane (part) at Division-50, Unit-12, Zone-05.",Grants,5,2020-21,2021-22 NE/2020-21/1489,Roads,Completed,NE-ROYAPURAM,50,210000,"Repair and maintenance Works in BT Road at A J Colony 3rd Lane (part) at Division-50, Unit-12, Zone-05. (",Grants,5,2020-21,2021-22 NE/2020-21/1491,Roads,Completed,NE-ROYAPURAM,50,232000,"Repair and maintenance Works in BT Road at A J Colony 4th Lane (part) at Division-50, Unit-12, Zone-05.",Grants,5,2020-21,2021-22 NE/2020-21/3887,Storm Water Drain,Completed,NE-ROYAPURAM,50,435000,"Desilting if Existing Storm Water Drains at Various Street (Andiappan Street East Madha Koil Street (From East Madha Koil 1st Lane to Thiruvenkadam Street) (And East Madha Koil 10th Lane to North Madha Koil Street)Flag Staff Street (Arch Drain)G M Pettai Road (On Eastern Side)(Arch Drain)G M Pettai Road (On Western Side)Kuppu Lane,Lotus Ramasamy Street,Mariamman Koil Street,North Madha Koil Street (From West Madha Koil Street to East Madha Koil Street,Sheike Mastry 1st Lane,Sheike Mastry Street,St Xavier Street,Thiruvenkadam Street in Division-50,Unit-12,Zone-5.",Own Sources,5,2020-21,2021-22 NE/2020-21/3910,Storm Water Drain,Completed,NE-ROYAPURAM,50,206000,"Replace of Manhole Doors of Existing Storm Water Drains in Various Street (IRR) East Madha Curch Street,G.M Petta Road (On Eastern Side)(Arch Drain),G.M Petta Road (On Western Side),Lotus Ramasamy Street,North Madha Koil Street,Shaike Maistry Sreet,St.Xavier Street,West Madha Church Street,South Madha Church Street in Div-50,Unit-12,Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/3943,Storm Water Drain,Completed,NE-ROYAPURAM,50,839000,"IMPROVEMENTS TO STORM WATER DRAINS AT VARIOUS STREET IN DN-50,UNIT-12,ZONE-5",Own Sources,5,2020-21,2021-22 NE/2020-21/1482,Roads,Completed,NE-ROYAPURAM,51,507000,"ROAD CUT AND RELAYING OF CC ROAD AT Gangan Street (North-South) (Part) IN DN-51,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1484,Roads,Completed,NE-ROYAPURAM,51,620000,"ROAD CUT AND RELAYING OF CC ROAD AT Bishop Lane (TNSCB Slum Road) IN DN-51,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1485,Roads,Completed,NE-ROYAPURAM,51,649000,"RELAYING OF CC ROAD AT Company Chatiram Street IN DN-51,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1490,Roads,Completed,NE-ROYAPURAM,51,615000,"RELAYING OF CC ROAD AT Nainiappan Garden 3RD Lane IN DN-51,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1492,Roads,Completed,NE-ROYAPURAM,51,1156000,"RELAYING OF CC ROAD AT East Cemetry Road L.& K. Block Slum Road IN DN-51,UNIT-12,ZONE-5",Grants,5,2020-21,2020-21 NE/2020-21/1726,Roads,Completed,NE-ROYAPURAM,51,1167000,"Relaying BT Road at Narasier Street in Division-51,Unit-12,Zone-5",Grants,5,2020-21,2021-22 NE/2020-21/4914,Buildings,Completed,NE-ROYAPURAM,51,1480000,"Construction of Motor Room Providing bore well and Water Supply arrangements at Bishop Lane,West Cemetry Road,manikandan 8th lane,East Cemetry Road in Div-51,Unit-12,Zone-5",MLACDS,5,2020-21,2021-22 NE/2020-21/9087,Buildings,Completed,NE-ROYAPURAM,51,507000,"Repairs and Maintenance Work For Division office Building at Manikandan 5th Street in DN-51,U-13,Z-05",Own Sources,5,2020-21,2021-22 D/2020-21/0638,Storm Water Drain,Completed,D-Storm Water Drains,52,6774000,"Construction of Storm Water Drain of size 900 x 900 mm along Mosque Street ,Thopai Street and Raman Street from Adam Street to Cemetery Road in Division - 52, Unit - 12, Zone - 5.",Own Sources,5,2020-21,2020-21 D/2020-21/0658,Storm Water Drain,Completed,D-Storm Water Drains,52,7724000,"Construction of Storm Water Drain of size 1200 x 1200 mm along Cemetery Road from Adam Street to Anna Park ( CMWSSB in gate ) in Division - 52, Unit - 12, Zone - 5.",Own Sources,5,2020-21,2020-21 NE/2020-21/1427,Roads,Completed,NE-ROYAPURAM,52,497000,"Improvement to CC Road at Model line 6th Lane in Div-52, Unit-12, Zone-5",Grants,5,2020-21,2020-21 NE/2020-21/1428,Roads,Completed,NE-ROYAPURAM,52,439000,"Improvement to CC Road at Model line 7th Lane in Div-52, Unit-12, Zone-5",Grants,5,2020-21,2020-21 NE/2020-21/2676,Buildings,Completed,NE-ROYAPURAM,52,4114000,"Relaying of the BT Road at O.S.H Road in Div-52, Unit-12, Zone-V",Grants,5,2020-21,2021-22 NE/2020-21/4909,Buildings,Completed,NE-ROYAPURAM,52,3155000,"Construction of New GYM building(MLA Scheme) at O.S.H Road in div- 52, unit- 12, zone- 5",MLACDS,5,2020-21,2021-22 NE/2020-21/4910,Buildings,Completed,NE-ROYAPURAM,52,1229000,"Providing GYM equipments (MLA Scheme) for GYM at O.S.H Road in div- 52, unit- 12, zone- 5",MLACDS,5,2020-21,2021-22 NE/2020-21/4923,Buildings,Completed,NE-ROYAPURAM,52,1454000,"Construction of motor room providing bore well and water supply arrangement at Model line 1st Street, O.S.H Road, Pichandi Lane, Dhobikana Lane in Div-52, Unit-12, Zone-V",MLACDS,5,2020-21,2021-22 NE/2020-21/2225,Electrical,Completed,NE-ROYAPURAM,53,4650000,"Proposed Construction of New Shed (Block-A) at MCC,Basin Bridge Road at Div-53,Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/2226,Buildings,Completed,NE-ROYAPURAM,53,4650000,"Proposed Construction of Additional MCC at Micro Composting Centre(Block-A) ,Basin bridge road in Div-53,Zone-5.",Own Sources,5,2020-21,2021-22 NE/2020-21/3868,Buildings,Completed,NE-ROYAPURAM,53,469000,"Improvements to existing Storm Water Drain at T.H SERVICE ROAD,BOJARAJA NAGAR 1ST STREET,KATHBADA MAIN ROAD,PENSIONER 3rd CROSS STREET,N.N NAGAR,AZEEZ GOUSE MOHAMMED GOUS STREET,SAJA MUNUSAMY CHETTY STREET(S.NO.64-126),PARASURAM MUDALI STREET in Div-53,Zone-5.",Own Sources,5,2020-21,2021-22 NE/2020-21/3870,Storm Water Drain,Completed,NE-ROYAPURAM,53,271000,"Replacing of Manhole Doors at Various Streets in Div-53,Zone-5.",Own Sources,5,2020-21,2021-22 NE/2020-21/4430,Buildings,Completed,NE-ROYAPURAM,53,1603000,"Renovation and Improvement Work to RDC Room at Basin Bridge Road in DN-53,U-12,Z-05",Own Sources,5,2020-21,2021-22 NE/2020-21/4439,Buildings,Completed,NE-ROYAPURAM,53,1880000,"Improvement to Electrical,Networking AC System in RDC Room at Basin Bridge Road in DN-53,U-12,Z-05",Own Sources,5,2020-21,2021-22 NE/2020-21/4891,Buildings,Completed,NE-ROYAPURAM,53,1500000,"CONSTRUCTION OF CARE TAKER ROOM IN MOOLAKOTHALAM BURIAL GROUND IN DIV-53,UNIT-12,ZONE-05.",MLACDS,5,2020-21,2021-22 NE/2020-21/4922,Buildings,Completed,NE-ROYAPURAM,53,1480000,"Constructions of motor room providing bore well and water supply arrangement at Kathbada Main Road,Bojaraja nagar, Srinivasapuram and New Labour Lane , in division 53, unit 12 ,zone-05",MLACDS,5,2020-21,2021-22 NE/2020-21/4925,Buildings,Completed,NE-ROYAPURAM,53,2800000,"Construction of Dining hall,Kitchen room & Toilet at Chennai Primary School,Bojaraja nagar in Dn-53,Zone-5",MLACDS,5,2020-21,2021-22 NE/2020-21/4990,Buildings,Completed,NE-ROYAPURAM,53,940000,"Maintenance to Existing R.O Plant Unit at Zonal Office Campus in Dn-53,Zone-5.",Own Sources,5,2020-21,2021-22 Q/2020-21/6588,Buildings,Completed,Q-Solid Waste Management,53,3130000,"Construction of Platform by modifying existing TPF for erecting Baling machine at Old TPF in Dn-53, Z-5",Own Sources,5,2020-21,2021-22 NE/2020-21/1702,Roads,Completed,NE-ROYAPURAM,54,916000,"Repair and Maintenance works in BT Road at Venkatraman Street in Division-54, Unit-13, Zone-05",Grants,5,2020-21,2021-22 NE/2020-21/5291,Roads,Completed,NE-ROYAPURAM,54,1149000,"Attending Patch work at Mint Street (From Amman koil Street to Thatha M Street) in Dn-54, Unit-13, Zone-5.(Asset-044/2430/16090/2013-14)",Deposit Works,5,2020-21,2021-22 NE/2020-21/5292,Roads,Completed,NE-ROYAPURAM,54,1731000,"Attending Patch work at Mint Street (From Saravana Street to Amman koil Street) in Dn-54, Unit-13, Zone-5.(Asset- 044/2430/16090/2013-14)",Deposit Works,5,2020-21,2021-22 D/2020-21/11446,Storm Water Drain,Completed,D-Storm Water Drains,55,2485000,"Demolition and Reconstruction of Storm Water Drain of Size 900X900 mm along P.V.Iyer Street (From Varadhamuthiappan Street to Acharappan Street) in Dn.55, Zone 5.",Own Sources,5,2020-21,2021-22 D/2020-21/4033,Storm Water Drain,Completed,D-Storm Water Drains,56,1800000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at B.R.N. Garden in Div-56 ,Zone - V.",Grants,5,2020-21,2020-21 D/2020-21/4403,Storm Water Drain,Completed,D-Storm Water Drains,56,1800000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at Thiruvalluvar Nagar in Div-56 ,Zone - V.",Own Sources,5,2020-21,2021-22 D/2020-21/5045,Storm Water Drain,Completed,D-Storm Water Drains,56,598000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at Alwarpet lane in Div-56 ,Zone - V.",Own Sources,5,2020-21,2021-22 D/2020-21/6003,Storm Water Drain,Completed,D-Storm Water Drains,56,4150000,"Construction of Storm Water Drain of Size 900X900 mm along Asirvathapuram Main Street and 8th Lane in Dn.56, Zone 5.",Own Sources,5,2020-21,2020-21 NE/2020-21/2582,Buildings,Completed,NE-ROYAPURAM,56,2995000,Construction of P.C at B.R.N Garden in div-56 unit-13 Zone-5 (Asset Code:033/2501/484/2013-14),MLACDS,5,2020-21,2021-22 BR/2020-21/6119,Roads,Completed,BR-Bus Route Roads,57,1450000,"Proposed construction of New Modern Stainless Steel Bus Shelter at size 9m X 3m at Prakasam Salai ( Minarva Theatre) in Div - 57, Zone - V",Deposit-Asset,5,2020-21,2020-21 D/2020-21/4404,Storm Water Drain,Completed,D-Storm Water Drains,57,1469000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at Aadhi Andhra colony 1 to 6 lanes in Div-57 ,Zone - V.",Own Sources,5,2020-21,2020-21 D/2020-21/4405,Storm Water Drain,Completed,D-Storm Water Drains,57,1469000,"Construction of Drain with 315 mm HDPE pipe and Inspection chamber at Jatkapuram in Div-57 ,Zone - V.",Own Sources,5,2020-21,2020-21 NE/2020-21/0787,Buildings,Completed,NE-ROYAPURAM,57,669000,"Improvements of PC at Jatkapuram in Division-57, Unit-13, Zone-V(Asset Code:033/4190/510/2013-14)",Own Sources,5,2020-21,2020-21 NE/2020-21/1143,Buildings,Completed,NE-ROYAPURAM,57,998000,"REPAIRS AND IMPROVEMENTS TO CORPORATION HIGH SCHOOL AT ANNA PILLAI STREET IN DIV-57, UNIT-13, ZONE-5",Own Sources,5,2020-21,2020-21 NE/2020-21/1361,Roads,Completed,NE-ROYAPURAM,57,2434000,"Repair And Maintenance Works in BT Road at NSC Bose Road in Division-57, Unit-13, Zone-05.(Asset- 043/2632/852/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1472,Roads,Completed,NE-ROYAPURAM,57,1313000,"Repair and maintenance Works in CC Road in Anna Pillai Street (Part) at Dn.57, Unit-13. Zone-05 (Asset- 040/4161/5384/2013-14)",Grants,5,2020-21,2020-21 NE/2020-21/1487,Roads,Completed,NE-ROYAPURAM,57,165000,"Repair and maintenance Works in BT Road at A J Colony 2nd Lane (part) at Division-50, Unit-12, Zone-05.",Grants,5,2020-21,2021-22 NE/2020-21/2129,Buildings,Completed,NE-ROYAPURAM,57,4889473,"Proposed Construction Of Micro Composting Centre (MCC) At Water Basin Street In Division-57, Unit-13, Zone-5.(156/4172/773/2013-14)",Own Sources,5,2020-21,2021-22 NE/2020-21/2458,Buildings,Completed,NE-ROYAPURAM,57,980000,"Improvement Works on General Work Shop at Water Basin Street in Division -57, Unit -13, Zone-05",Own Sources,5,2020-21,2020-21 NE/2020-21/3414,Buildings,Completed,NE-ROYAPURAM,57,1050000,"Supply and Fixing Sherrding Machine & Sieving machine Cutter in Micro Composting Centre (MCC) at Water Basin Street In Division-57, Unit-13, Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/7875,Buildings,Completed,NE-ROYAPURAM,57,710000,"CONSTRUCTION OF COMPOUND WALL FOR VACANT LAND AT WALL TAX ROAD NEAR KRLS PARCEL SERVICE, OTHA VADAI STREET, OTTHA VADAI STREET JNCTION & NSC BOSE ROAD JUNCTION IN DIV-57, UNIT-13, ZONE-05",Own Sources,5,2020-21,2021-22 BR/2020-21/10617,Road Cut,Completed,BR-Bus Route Roads,58,1542000,"Restoration of Road cut made by TANTRANSCO for laying 230KV cable at Rajamuthiah salai from the Jawaharlal Nehru Indoor Stadium gate No.4 to Allikulam link Road in Div - 58, Zone -5.",Deposit Works,5,2020-21,2021-22 BR/2020-21/12773,Roads,Completed,BR-Bus Route Roads,58,4954000,"Relaying the Road with DBM and BC at Nehru Indoor Stadium for Honourable Prime minister Visiting at Nehru Indoor Stadium Road , Chennai which came under control of Sport Development Authority in Dn-58,Zone-5.",Own Sources,5,2020-21,2020-21 BR/2020-21/13173,Road Cut,Completed,BR-Bus Route Roads,58,1750000,"Restoration of Road cut made by TANTRANSCO for laying 230KV cable at RajMuthaiah salai from the Purasaiwakkam thasildar office to nehru indoor satdium gate N0;3 in Div - 58, Zone -5.",Deposit Works,5,2020-21,2020-21 BR/2020-21/7894,Roads,Completed,BR-Bus Route Roads,58,955000,"Relaying the Road with BC at My Ladies park access road through Rajamuthaiah salai to enter the Nehru Indoor stadium for attending government function in Division - 58 , zone-5.",Own Sources,5,2020-21,2021-22 BR/2020-21/9060,Roads,Completed,BR-Bus Route Roads,58,199000,"Repairs and painting to centre median at Rajamuthaiah salai from EVR Salai to Nehru Stadium (out door) Gate no.2 in Dn-58, zone-5.",Own Sources,5,2020-21,2020-21 L/2020-21/1332,Electrical,Completed,L-Electrical,58,561700,"Electrification work in old conference hall in second floor eastern side at Ripon building Division-58,Zone-5",Own Sources,5,2020-21,2020-21 L/2020-21/1349,Electrical,Completed,L-Electrical,58,906700,"Supply and Erection of 6 nos 3mtr park lamp post, replacement of 3 1/2X25sq.mm cable 245mtrs and 2cX16sq.mm alu cable 248mtrs and fixing of 8 nos 120-130w fl LED, 5 nos 70-100w fl LED 12 nos 30-60w FL LED and 6 nos 10-20w LED fittings at Ragavendra park, division-58, zone-5.",Own Sources,5,2020-21,2021-22 L/2020-21/8513,Electrical,Completed,L-Electrical,58,286100,"Provision of 15Nos. AC Sockets suitable for the Split Air conditioners and 5/15A sockets for the Workstations at the 2nd floor of Revenue Department Building in Ripon Building premises in Dn 58, Zone 5.",Own Sources,5,2020-21,2020-21 NE/2020-21/0797,Buildings,Completed,NE-ROYAPURAM,58,2848000,"IMPROVEMENTS TO ADDITIONAL COURT HALLS IN ALLIKULAM SHOPPING COMPLEX IN DIV-58,UNIT-14,ZONE-5.",Own Sources,5,2020-21,2021-22 NE/2020-21/1401,Parks,Completed,NE-ROYAPURAM,58,2499000,"PROVIDING FOOTPATH TILES,MOTOR, WATER SUPPLY ARRANGEMENTS PIPES AND HAND RAILS (ADDITIONAL WORKS) IN RAGAVENDRA PARK AT AVADHANAM PAPPIER ROAD IN DIV-58, UNIT-14, ZONE-5",MLACDS,5,2020-21,2020-21 NE/2020-21/3129,Playfields,Completed,NE-ROYAPURAM,58,2445000,"Forming base layer to the synthetic turf and providing fencing for the play ground at Naval Hospital Road in Dn-58, U-14, Z-5",Own Sources,5,2020-21,2021-22 NE/2020-21/3349,Buildings,Completed,NE-ROYAPURAM,58,2879000,"ADDITIONAL WORK CONSTRUCTION OF POTHIGAI MOUNTAIN WITH AGASTHIYAR STATUE AND CONSTRUCTION OF ENTRANCE ARCH AND EIGHT WALK INFORMATION BOARD, PROVIDING ADDITIONAL BOREWELLS IN RAGAVENDRA PARK AT AVADHANAM PAPAIYERROAD IN DIV-58, UNIT-14, ZONE-05",MLACDS,5,2020-21,2020-21 NE/2020-21/3851,Storm Water Drain,Completed,NE-ROYAPURAM,58,473400,"Minor repairs to the storm water drain at EVK Sampath Road, Dr.Alagappa Road in Div-58, U-14, Z-5",Own Sources,5,2020-21,2021-22 NE/2020-21/4146,Parks,Completed,P-Parks and Playfields,58,2467000,"FORMING GRANITE FOOTPATH, ELECTRICAL ARRANGEMENTS AND GREENARY TO RAGAVENDRA PARK AT AVADHANA PAPPAIER ROAD IN DIV-58, UNIT-14, ZONE-05",Own Sources,5,2020-21,2021-22 NE/2020-21/6100,Buildings,Completed,NE-ROYAPURAM,58,1750000,"CONSTRUCTION OF COMPOUND WALL FOR COMPOST YARD (RRC) AT KANNAPPAR THIDAL (NEAR CMWSSB FILLING POINT) IN DIV-58, UNIT-14, ZONE-5",Own Sources,5,2020-21,2021-22 NE/2020-21/6833,Buildings,Completed,P-Parks and Playfields,58,2491000,"CONSTRUCTION OF OVER HEAD TANK, WATER SUPPLY ARRANGEMENTS, PROVIDING AND FIXING STAINLESS STEEL HANDRAIL AND RO WATER SUPPLY ARRANGEMENTS TO RAGAVENDRA PARK AT AVADHANA PAPPAIER ROAD IN DIV-58, UNIT-14, ZONE-05",Own Sources,5,2020-21,2021-22 NE/2020-21/1542,Roads,Completed,NE-ROYAPURAM,59,904000,"Repair and maintenance Works in BT Road at Amman Koil Street in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1544,Roads,Completed,NE-ROYAPURAM,59,268000,"Repair and maintenance Works in BT Road at Subbu (C) Street in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1545,Roads,Completed,NE-ROYAPURAM,59,255000,"Repair and maintenance Works in BT Road at Bommu (C) Street in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1546,Roads,Completed,NE-ROYAPURAM,59,317000,"Repair and maintenance Works in BT Road at Nainiappan (N) Street (Part) in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1547,Roads,Completed,NE-ROYAPURAM,59,1809000,"Repair and maintenance Works in BT Road at Ellis Road in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1549,Roads,Completed,NE-ROYAPURAM,59,265000,"Repair and maintenance Works in BT Road at Venkatachalam (M) Street (Part) in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1550,Roads,Completed,NE-ROYAPURAM,59,1518000,"Repair and maintenance Works in BT Road at Ekambareswarar Agraharam Street in Dn - 59, Unit - 14, Zone - 5.",Own Sources,5,2020-21,2021-22 NE/2020-21/1551,Roads,Completed,NE-ROYAPURAM,59,346000,"Repair and maintenance Works in BT Road at Kesava (I) Street in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1552,Roads,Completed,NE-ROYAPURAM,59,476000,"Repair and maintenance Works in BT Road at Ravaniyar Street in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/1553,Roads,Completed,NE-ROYAPURAM,59,289000,"Repair and maintenance Works in BT Road at Sivaram (S) Street in Dn - 59, Unit - 14, Zone - 5.",Grants,5,2020-21,2021-22 NE/2020-21/3888,Storm Water Drain,Completed,NE-ROYAPURAM,59,514000,"Repairs and improvements to Existing Storm Water Drain at Mukthurinnsa Begam Vth Lane, Owlia Sahib IVth Lane, Wallajah Road, Nsc bose Road, Narayanappa Road, Nsc bose Road, Bangaru (N) Street and SM Nagar in Dn - 59, Unit - 14, Zone - 5",Own Sources,5,2020-21,2021-22 NE/2020-21/8502,Buildings,Completed,NE-ROYAPURAM,59,1410000,"Proposed Construction of Public Convenience (Gents) at Sathyavani Muthu Nagar (Near Bridge) in Division-59, Unit-14, Zone-05.",Own Sources,5,2020-21,2021-22 BR/2020-21/0882,Road Cut,Completed,BR-Bus Route Roads,60,959000,"Restoration of roadcut by OFC Operators at Various Road in Dn-60, U-13, Z-05",Deposit Works,5,2020-21,2020-21 BR/2020-21/1328,Road Cut,Completed,BR-Bus Route Roads,60,991000,"Restoration of road cut made by service departments(OFC) at Interior roads in Div 60,Zone 5",Deposit Works,5,2020-21,2020-21 NE/2020-21/0009,Buildings,Completed,NE-ROYAPURAM,60,5000000,"Formation of Traffic island Park/ Play Ground at Clive battery (Junction of Rajaji Salai and Ibrahim Sahib Street) in Division-60, Unit-13, Zone-5.(012/2580/188/2013-14)",MLACDS,5,2020-21,2020-21 NE/2020-21/0015,Buildings,Completed,NE-ROYAPURAM,60,800000,"Supply,Delivery,Installation and Commissioning of Bio-Digester to Annai Sathya Nagar Childrens PC in Division-60, Unit-13, Zone-5.",Own Sources,5,2020-21,2020-21 NE/2020-21/0016,Buildings,Completed,NE-ROYAPURAM,60,800000,"Supply,Delivery,Installation and Commissioning of Bio-Digester to Public Convenience at MLA Carparking area (Opp. To Secretariat) in Division-60, Unit-13, Zone-5.",Own Sources,5,2020-21,2020-21 NE/2020-21/0028,Buildings,Completed,NE-ROYAPURAM,60,2380000,"Improvement Works to Armenian Street (From NSC Bose road to Mannady Street) in Dn.60, Unit-13, Zone-05.(044/2617/1417/2007-08)",Own Sources,5,2020-21,2020-21 NE/2020-21/1618,Roads,Completed,NE-ROYAPURAM,60,2084000,"Repair and maintenance Works in BT Road at Armenian Street in Dn - 60, Unit - 13, Zone - 5.(Asset- 044/2617/16578/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1619,Roads,Completed,NE-ROYAPURAM,60,377000,"Repair and maintenance Works in BT Road at Bakers Street Street in Dn - 60, Unit - 13, Zone - 5. (Asset- 043/2610/845/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1620,Roads,Completed,NE-ROYAPURAM,60,269000,"Repair and maintenance Works in BT Road at Philiphs Street Street in Dn - 60, Unit - 13, Zone - 5.(Asset-044/2628/16682/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1621,Roads,Completed,NE-ROYAPURAM,60,673000,"Repair and maintenance Works in BT Road at Post office Street Street in Dn - 60, Unit - 13, Zone - 5.(Asset- 044/2653/16559/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1622,Roads,Completed,NE-ROYAPURAM,60,295000,"Repair and maintenance Works in BT Road at Kachaleeswarar Pakoda Lane in Dn - 60, Unit - 13, Zone - 5.(Asset- 044/2637/16590/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1623,Roads,Completed,NE-ROYAPURAM,60,596000,"Repair and maintenance Works in BT Road at Sunkuram (C) Street in Dn - 60, Unit - 13, Zone - 5. (Asset- 044/2648/16686/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1624,Roads,Completed,NE-ROYAPURAM,60,320000,"Repair and maintenance Works in BT Road at Kondi (C) Street in Dn - 60, Unit - 13, Zone - 5. (Asset- 044/2625/16591/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1625,Roads,Completed,NE-ROYAPURAM,60,687000,"Repair and maintenance Works in BT Road at Mooker Nallamuthu Street in Dn - 60, Unit - 13, Zone - 5.(Asset-043/2646/843/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1626,Roads,Completed,NE-ROYAPURAM,60,220000,"Repair and maintenance Works in BT Road at Krishnan Kovil Street in Dn - 60, Unit - 13, Zone - 5.(Asset- 044/2611/23554/2013-14)",Grants,5,2020-21,2021-22 NE/2020-21/1628,Roads,Completed,NE-ROYAPURAM,60,419000,"Repair and maintenance works CC Road in Tailor's Lane at Division-60, Unit-13, Zone-05.(Asset- 040/2561/350/2001-02)",Grants,5,2020-21,2020-21 NE/2020-21/1629,Roads,Completed,NE-ROYAPURAM,60,286000,"Repair and maintenance works CC Road in Hussain Marakkayar Street at Division-60, Unit-13, Zone-05.(Asset- 044/2583/16567/2013-14)",Grants,5,2020-21,2020-21 NE/2020-21/1630,Roads,Completed,NE-ROYAPURAM,60,439000,"Repair and maintenance works CC Road in Buddu Street at Division-60, Unit-13, Zone-05. (Asset- 044/2575/16522/2013-14)",Grants,5,2020-21,2020-21 NE/2020-21/1631,Roads,Completed,NE-ROYAPURAM,60,228000,"Repair and maintenance works CC Road in Moore Street Second Lane at Division-60, Unit-13, Zone-05. (Asset- 044/2608/16544/2013-14)",Grants,5,2020-21,2020-21 NE/2020-21/1632,Roads,Completed,NE-ROYAPURAM,60,429000,"Repair and maintenance works CC Road in Ayya (M) Lane at Division-60, Unit-13, Zone-05.(Asset- 044/2576/16519/2013-14)",Grants,5,2020-21,2020-21 NE/2020-21/1633,Roads,Completed,NE-ROYAPURAM,60,160000,"Repair and maintenance works CC Road in Marakkayar Labbai Street at Division-60, Unit-13, Zone-05.(Asset- 044/2590/1402/2007-08)",Grants,5,2020-21,2020-21 NE/2020-21/1755,Footpath,Completed,NE-ROYAPURAM,60,1837000,"Painting work to Footpath Kerbs at Rajaji Salai, North Fort Side Road in Div-60, Unit-13, Zone-5. (For Independence Day Celebration).",Own Sources,5,2020-21,2021-22 NE/2020-21/1756,Footpath,Completed,NE-ROYAPURAM,60,1116000,"Painting work to Footpath Kerbs at Kamaraj Salai, Flag Staff House Road, NSC Bose Road and Ibrahim Sahib Street in Div-60, Unit-13, Zone-5. (For Independence Day Celebration).",Own Sources,5,2020-21,2020-21 NE/2020-21/2586,Footpath,Completed,NE-ROYAPURAM,60,976000,"Improvements to footpath at flag staff road near traffic police booth in Div-60, Unit-13 ,Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/2588,Parks,Completed,NE-ROYAPURAM,60,800000,"Providing plantation at Flag Staff Road near traffic control booth in Dn-60, Unit-13,Zone-V",Own Sources,5,2020-21,2021-22 NE/2020-21/3760,Roads,Completed,NE-ROYAPURAM,60,1670000,"Attending Cement Concrete Patches at Annai Sathya Nagar ( North ) B Block Streets (Asset-043/2646/534/2013-14) in Division-60,Unit-13,Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/3908,Storm Water Drain,Completed,NE-ROYAPURAM,60,253000,"Desilting of Existing Storm Water Drain at Varadarasan Street,Jaffar Syrang Street,Moore Street,Jaffar Sarang Lane,Mooker Nallamuthu Street,Post Office Street,Sembudoss Street & Jones Lane in Division-60, Unit-13, Zone -5",Own Sources,5,2020-21,2021-22 NE/2020-21/3920,Storm Water Drain,Completed,NE-ROYAPURAM,60,604000,"Improvements to Existing Storm Water Drain at Varadarasan Street,Jaffar Syrang Street,Moore Street,Mooker Nallamuthu Street,Sembudoss Street,Post Office Street,Light House Road (west),Rajaji Salai(East),Rajaji Salai(West),North Fort Side Road,Ibrahim Salai(Southern Side)& NSC Bose Road in Division-60 , Unit -13, Zone - 5",Own Sources,5,2020-21,2021-22 NE/2020-21/3923,Storm Water Drain,Completed,NE-ROYAPURAM,60,142000,"Replacing of Manholes at Varadarasan Street,Jaffar Syrang Street,Moore Street,Mooker Nallamuthu Street,Sembudoss Street,Post Office Street,Light House Road (west),Rajaji Salai(East),Rajaji Salai(West),North Fort Side Road,Ibrahim Salai(Southern Side)& NSC Bose Road in Division-60,Unit-13,Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/4238,Storm Water Drain,Completed,NE-ROYAPURAM,60,1300000,"Providing Rain Water Harvesting at Annai Sathya Nagar(North) B Block Streets in Division-60,Unit-13,Zone-5 (Asset Code- 153/2646/1060/2014-15)",Own Sources,5,2020-21,2021-22 NE/2020-21/4260,Roads,Completed,NE-ROYAPURAM,60,1350000,"Attending Cement Concrete Patches at Annai Sathya Nagar(North) C Block Streets in Division-60,Unit-13,Zone-5 (Asset Code- 043/2646/534/2013-14)",Own Sources,5,2020-21,2021-22 NE/2020-21/4263,Roads,Completed,NE-ROYAPURAM,60,1400000,"Providing Rain Water Harvesting at Annai Sathya Nagar(North) C Block Streets in Division-60,Unit-13,Zone-5 (Asset Code-055/2646/6417/2014-15)",Own Sources,5,2020-21,2021-22 BR/2020-21/0215,Road Cut,Completed,BR-Bus Route Roads,61,2485000,"Roadcut Restoration of Pantheon Road From the Jn of college Road to Jn of Montieth Road in Dn. 61, Zone- 5 Against Challan No : BR/2019-20/0039262",Deposit Works,5,2020-21,2020-21 BR/2020-21/0294,Road Cut,Completed,BR-Bus Route Roads,61,2485000,"Roadcut Restoration of Pantheon Road From the Jn of Montieth Road to Jn of Sri Rangam avenue in Dn. 61, Zone- 5 Against Challan No : BR/2019-20/0039262",Deposit Works,5,2020-21,2020-21 BR/2020-21/0295,Road Cut,Completed,BR-Bus Route Roads,61,2485000,"Roadcut Restoration of Pantheon Road From the Jn of Sri Rangam avenue to Jn of Police Commissioner Office road Roundtana in Dn. 61, Zone- 5 Against Challan No : BR/2019-20/0039262",Deposit Works,5,2020-21,2020-21 BR/2020-21/0296,Road Cut,Completed,BR-Bus Route Roads,61,2485000,"Roadcut Restoration of Pantheon Road From the Jn of Police Commissioner Office road Roundtana to Jn of kennet Lane in Dn. 61, Zone- 5 Against Challan No : BR/2019-20/0039262",Deposit Works,5,2020-21,2020-21 BR/2020-21/0298,Road Cut,Completed,BR-Bus Route Roads,61,2050000,"Roadcut Restoration of Pantheon Road From the Jn of kennet Lane to Jn of Langs Garden Road in Dn. 61, Zone- 5 Against Challan No : BR/2019-20/0039262",Deposit Works,5,2020-21,2020-21 BR/2020-21/10613,Road Cut,Completed,BR-Bus Route Roads,61,2440000,"Restoration of Road cut made by CMWSSB for laying of interceptors and diversion of Sewage at Gandhi irwin Bridge langs garden road from the gandhi irwin park to ayyaswamy street in in Div -61, Zone -5.",Deposit Works,5,2020-21,2020-21 BR/2020-21/10621,Road Cut,Completed,BR-Bus Route Roads,61,1590000,"Restoration of Road cut made by TANTRANSCO for laying 230KV cable at Gandhi Irwin Bridge Road from the Arunachalam Road to Ponamalle High Road in Div -61, Zone -5.",Deposit Works,5,2020-21,2021-22 BR/2020-21/3107,Roads,Completed,BR-Bus Route Roads,61,4274000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Dr.Nair Bridge Road in Dn-61, Zone V",Grants,5,2020-21,2020-21 BR/2020-21/3715,Road Cut,Completed,BR-Bus Route Roads,61,949000,"Restoration of Roadcut (OFC) at various street in Dn-61,64,65,66, and 67,Unit -15 &16 ,Zone VI",Deposit Works,5,2020-21,2020-21 BR/2020-21/9098,Roads,Completed,BR-Bus Route Roads,61,198000,"Removing and Replacing the Damaged SS hand rail at Rukumani lakshmipathy Salai in Division-61 ,Zone - 5",Own Sources,5,2020-21,2020-21 NE/2020-21/0434,Buildings,Completed,NE-ROYAPURAM,61,2245000,"Supply and Fixing Baling Machines at M.C.C Center at Various Locations in Unit-14, Zone-5",Own Sources,5,2020-21,2021-22 NE/2020-21/1742,Roads,Completed,NE-ROYAPURAM,61,790000,"Relaying of BT at Montieth Road in Division-61, Unit-14, Zone-V",Grants,5,2020-21,2021-22 NE/2020-21/1743,Roads,Completed,NE-ROYAPURAM,61,788000,"Relaying of BT at Velayutham Street in Division-61, Unit-14, Zone-V",Grants,5,2020-21,2021-22 NE/2020-21/3881,Storm Water Drain,Completed,NE-ROYAPURAM,61,231500,"Desilting of Strom water drain at Sait colony I street, Sait colony II street, Rangachari street, Boopathy nagar, Driver street, Boopathy nagar(Gengu ( R ) Subway service road), Velayutham street, Ayyasami road, Ethiraj lane, Montieth Lane, Montieth Road, Gengu road, Aaravmuthu garden, Varatharajalu Street in Division-61, Unit-14, Zone-V",Own Sources,5,2020-21,2021-22 NE/2020-21/4947,Buildings,Completed,NE-ROYAPURAM,61,733000,"REPAIRS AND MAINTAINCE OF ATHITHANAR ISLAND AT PANTHEON ROAD JUNCTION AND MINOR REPAIR WORK AT EGMORE HIGH ROAD IN DIV-61, UNIT-14, ZONE-05",Own Sources,5,2020-21,2021-22 NE/2020-21/1748,Roads,Completed,NE-ROYAPURAM,62,595000,"Relaying of BT at Sivapragasam Street in Division-62, Unit-14, Zone-V",Grants,5,2020-21,2021-22 NE/2020-21/3846,Storm Water Drain,Completed,NE-ROYAPURAM,62,441000,"Desilting of existing Storm water Drain at Pumping Station Road,Singanna C Street,Iyya (M) Street,Koovur Vaithiyanathan Street,Bazzar Street,Rex Street,New Balakrishnan Street,Inside May Day Park,Padavattamman Koil Street,Venkatesan Street,Waller Road,Samy (P) Street,Lafond Street,Kovilur amman Koil Street,Pumping Station lane side Drain,Arunachalam lane side drain and Samy (N) Street in DN 62,Unit-14,Zone-05.",Own Sources,5,2020-21,2021-22 BR/2020-21/3311,Roads,Completed,BR-Bus Route Roads,63,4066000,"Relaying the road with DBM and BC after cold milling by paver finisher along with traffic improvement work at Dams Road in Dn-63, Zone V",Grants,5,2020-21,2020-21 BR/2020-21/9099,Roads,Completed,BR-Bus Route Roads,63,199000,"Removing and Replacing the Damaged SS hand rail at Adhithinar Salai in Division-63 ,Zone - 5.",Own Sources,5,2020-21,2020-21 NE/2020-21/1738,Roads,Completed,NE-ROYAPURAM,63,508000,"Relaying of BT at Vengadesan 1st Street in Division-63, Unit-14, Zone-V",Grants,5,2020-21,2021-22 NE/2020-21/1739,Roads,Completed,NE-ROYAPURAM,63,206500,"Relaying of BT at Chella pillayar koil 3rd Street in Division-63, Unit-14, Zone-V",Grants,5,2020-21,2021-22 NE/2020-21/1740,Roads,Completed,NE-ROYAPURAM,63,350000,"Relaying of BT at Bura Sahip Street and Lane in Division-63, Unit-14, Zone-V",Grants,5,2020-21,2021-22 NE/2020-21/1741,Roads,Completed,NE-ROYAPURAM,63,210000,"Relaying of BT at Veerabathiran Street (Part) in Division-63, Unit-14, Zone-V",Grants,5,2020-21,2021-22 NF/2020-21/4387,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,826000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT VELAVAN NAGAR MAIN ROAD, NERMAI NAGAR MAIN ROAD, ANJUGAM NAGAR WEST MAIN ROAD, RAJAN NAGAR MAIN ROAD, UNITED COLONY MAIN ROAD AND VARIOUS STREETS IN DIVISION-64, UNIT-15, ZONE-VI",Own Sources,6,2020-21,2021-22 NF/2020-21/4388,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,64,826000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT POOMPUHAR NAGAR 2ND MAIN ROAD, JAYARAM NAGAR MAIN ROAD, MURUGAN NAGAR MAIN ROAD, HARIDOSS MAIN ROAD AND VARIOUS STREETS IN DIVISION-64, UNIT-15, ZONE-6",Own Sources,6,2020-21,2021-22 NF/2020-21/4427,Playfields,Completed,NF-THIRU-VI-KA NAGAR,64,830000,"Improvements to the Anjugam nagar Park at Anjugam nagar 4th street in Dn -64, unit-15,zone-06",Own Sources,6,2020-21,2021-22 BR/2020-21/2980,Roads,Completed,BR-Bus Route Roads,65,1491000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Thillai Nagar 1st Main Road (Senthil Nagar 1st Main road to Ring Road) in Dn-65 , Zone - VI",Grants,6,2020-21,2021-22 NF/2020-21/4242,Parks,Completed,NF-THIRU-VI-KA NAGAR,65,842000,IMPROVEMENTS WORKS TO THIRUMALAI NAGAR PARK AT HIRUMALAI NAGAR 1ST STREET IN DN-65 U-15 Z-06.,Own Sources,6,2020-21,2021-22 NF/2020-21/4494,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,65,825500,"Desilting And Minor Repair Works To Existing Storm Water Drain in Dn-65,Unit-15,Zone-06.",Own Sources,6,2020-21,2021-22 BR/2020-21/10626,Road Cut,Completed,BR-Bus Route Roads,66,1168000,"Restoration of Roadcut made by CMWSSB for attending damaged pumping main 300mm Dia pipe line at Paper mills Road in Div-66 & 68, Zone -VI",Deposit Works,6,2020-21,2020-21 BR/2020-21/12758,Roads,Completed,BR-Bus Route Roads,66,1120000,"Restoration of Road cut made by Cmwssb for attending damaged pumping main 300mm dia pipe line at Paper Mills Road in Division -66,&68,zone -6.",Deposit Works,6,2020-21,2020-21 BR/2020-21/5927,Roads,Completed,BR-Bus Route Roads,66,3144000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Kandasamy Salai in Dn-66,Zone VI",Grants,6,2020-21,2021-22 NF/2020-21/4013,Buildings,Completed,NF-THIRU-VI-KA NAGAR,66,470000,"Repair works & Improvements to Existing school building and annexture building at Jawahar nagar 1st circular road in Div-66,Unit-16,Zone-6",Own Sources,6,2020-21,2021-22 NF/2020-21/4511,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,938900,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT GANDHIMATHI STREET,sAKTHIVINAYAGAR KOVIL STREET,RAGAVENDRALINK ROAD,ANDAL AVENUE,KUMARAN NAGAR,JAWAHAR NAGARAND VARIOUS STREETS IN DIVISION-66, UNIT-16, ZONE-VI",Own Sources,6,2020-21,2021-22 NF/2020-21/4512,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,66,650000,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT KANDASAMY SALAI,BALASUBRAMANIAN SALAI,JEGANATHAN SALAI AND VARIOUS STREETS IN DIVISION-66, UNIT-16, ZONE-VI",Own Sources,6,2020-21,2021-22 NF/2020-21/1423,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,424000,"Improvements to the CC Road at DIMMASAMY DURGA STREET IN DN-67, UNIT-15, ZONE-06",Own Sources,6,2020-21,2020-21 NF/2020-21/1424,Roads,Completed,NF-THIRU-VI-KA NAGAR,67,198000,"Improvements to the CC Road at MOORTHY STREET IN DN-67, UNIT-15, ZONE-06",Own Sources,6,2020-21,2020-21 NF/2020-21/3268,Buildings,Completed,NF-THIRU-VI-KA NAGAR,67,2000000,"PROVIDING GYM EQUIPMENT AT JAGANNATHAN SALAI GYM BUILDING IN DN-67, U-15, Z-6. [MLA FUND].",MLACDS,6,2020-21,2021-22 NF/2020-21/4986,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,67,267800,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT RANGASAYEE STREET, MARKET STREET,BALLARD STREET, AMIRTHAMMAL COLONY, SOMASUNDARAM MAIN STREET,KANAGAR STREET,GKM COLONY 17TH STREET AND VARIOUS STREETS IN DIVISION-67, UNIT-15, ZONE-VI",Own Sources,6,2020-21,2021-22 BR/2020-21/6888,Road Cut,Completed,BR-Bus Route Roads,68,1670000,"Restoration of Roadcut made by CMWSSB for attending damaged pumping main 300mm Dia pipe line at Paper mills Road in Div-66 & 68, Zone -VI",Deposit Works,6,2020-21,2020-21 NF/2020-21/3552,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,2000000,"Construction of Additional Class Room of Gopalapuram Corporation Middle School at SRP Koil street (North) in Dn-68 , Un-16 , Zn-6",MLACDS,6,2020-21,2021-22 NF/2020-21/3608,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,4000000,"The Proposed Construction of Indoor Ladies GYM with Apparatus, Electrical Facilities and Compound wall works to Greater Chennai Corporation OSR land at Thiru.Vi.ka Nagar main road in Division-68, Unit-16, Zone-6.",MLACDS,6,2020-21,2021-22 NF/2020-21/3610,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,500000,"Providing Semi Modular Kitchen, Electrical Facilities, Children Play Apparatus and Furniture at Madurai Samy madam ICDS (33603070222) in Division-68, Unit-16.Zone-06.",MLACDS,6,2020-21,2021-22 NF/2020-21/3625,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,1500000,"Providing Children Play Apparatus facilities of Greater Chennai Corporation OSR Land at Thiru.Vi.Ka Nagar Main Road in Division-68, Unit-16,Zone-06.",MLACDS,6,2020-21,2021-22 NF/2020-21/5526,Buildings,Completed,NF-THIRU-VI-KA NAGAR,68,2500000,"Proposed Construction of 16th day Death Ceremony Hall Opposite to Thangal Burial Ground at Pallavan Salai in Division -68, Unit-16, Zone-06.",Own Sources,6,2020-21,2021-22 NF/2020-21/8532,Parks,Completed,NF-THIRU-VI-KA NAGAR,68,250000,"Improvement works to Thiru.Vi. Nagar Road side park at Pallavan Salai in Division-68, Unit -16, Zone - 06.",Own Sources,6,2020-21,2021-22 NF/2020-21/2164,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,436000,"REPAIR AND IMPROVEMENTS TO ICDS AT RAJA STREET IN DIVISION-69, UNIT-16, ZONE-06",Own Sources,6,2020-21,2021-22 NF/2020-21/2879,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,69,782200,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN IN DIVISION-69, UNIT-16, ZONE-6",Own Sources,6,2020-21,2021-22 NF/2020-21/3281,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,500000,"Supply of equipment for Ladies GYM at Sadayappadoss Street at Division -69, Unit -16, Zone -06(MLA FUND)",MLACDS,6,2020-21,2021-22 NF/2020-21/3984,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,500000,"PROVIDING BORE WELL ARRANGEMENTS AND REPAIR TO COMMUNITY CENTRE AT RAJA STREET IN DN -69, UNIT-16, ZONE-06",Own Sources,6,2020-21,2021-22 NF/2020-21/3985,Buildings,Completed,NF-THIRU-VI-KA NAGAR,69,500000,"IMPROVEMENTS & BORE WELL ARRANGEMENTS TO CHENNAI HIGHER SECONDARY SCHOOL AT BANDER GARDEN MAIN STREET IN DIVISION -69, UNIT-16,ZONE-06",Own Sources,6,2020-21,2020-21 BR/2020-21/6441,Road Cut,Completed,BR-Bus Route Roads,70,1800000,"Restoration of Roadcut made by CMWSSB at Perambur High Road(South)- Jamaliya in Div-70, Zone -VI",Deposit Works,6,2020-21,2020-21 NF/2020-21/5882,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,70,721900,"De-Silting and Minor Repairs Works to the exisitng Storm water drain at Nelvayal Road, N.S.K. Street, Bharathi Main Road and Various road in Div-70,Unit-16,Zone-6",Own Sources,6,2020-21,2021-22 NF/2020-21/3605,Parks,Completed,NF-THIRU-VI-KA NAGAR,73,326000,"Providing of Bore Well Arrangements and Reparing of Play Apparatus to Waidya Park at New Farrance Road, Pattalam, Chennai - 600 012 in Dn.73, Unit-17, Zone - 6",Own Sources,6,2020-21,2021-22 NF/2020-21/4154,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,73,560400,"Desilting Work to the exisitng SWD at Darga Street,Parthasarathy street,Lal singh street,Prakash rao colony,Bolu (n) street,Ammiyanmal street,Kutty thambiran street,Natchiarammal lane,Natchiarammal street,New Ferrance Road,Narayana Swamy Street,Mannarswamy Street Dr.AmbedKar College Road,Cooks Road,Stephenson Road and Various streets in Dn-73,Unit-17,Zone-06.",Own Sources,6,2020-21,2021-22 NF/2020-21/2433,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,500000,"IMPROVEMENTS OF CHENNAI PRIMARY SCHOOL AUDITORIYAM AND COMPUTER ROOM AT CHINNABABU STREET IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2020-21,2020-21 NF/2020-21/3633,Buildings,Completed,NF-THIRU-VI-KA NAGAR,74,570000,"IMPROVEMENTS TO AE OFFICE, SI OFFICE BARACKA ROAD IN DN-74, UNIT-17, ZONE-06.",Own Sources,6,2020-21,2021-22 NF/2020-21/4155,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,74,422000,"DESILTING OF STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-74, UNIT-17, ZONE-VI",Own Sources,6,2020-21,2021-22 BR/2020-21/3012,Roads,Completed,BR-Bus Route Roads,75,4556000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Bricklin Road in Dn-75 , Zone VI",Grants,6,2020-21,2020-21 NF/2020-21/1578,Buildings,Completed,NF-THIRU-VI-KA NAGAR,75,780000,"Improvements to multi purpose hall ground floor at ss puram b block main street in dn-75, unit-17, zone-06.",Own Sources,6,2020-21,2021-22 NF/2020-21/4156,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,75,270000,"DESILTING OF STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION-75, UNIT-17, ZONE-VI",Own Sources,6,2020-21,2021-22 BR/2020-21/3015,Roads,Completed,BR-Bus Route Roads,76,1551000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Barracks Gate Road in Dn-76,Zone VI",Grants,6,2020-21,2020-21 BR/2020-21/3027,Roads,Completed,BR-Bus Route Roads,76,2756000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Dr.Ambedkar College Road(from the Ferannnce Road to Stephenson Road) in Dn-73&76 , Zone VI",Grants,6,2020-21,2020-21 BR/2020-21/7998,Road Cut,Completed,BR-Bus Route Roads,76,1980000,"Restoration of Road cut made by TANTRANSCO for laying 110KV cable at Demellows road and Rajamuthiah salai from the Basin Elephant Gate Road to Choolai High Road in Div - 76 & 77, Zone -6.",Deposit Works,6,2020-21,2020-21 NF/2020-21/0899,Electrical,Completed,NF-THIRU-VI-KA NAGAR,76,451180,Shifting of 1 no 40KVA Diesel generator set from Perambur barrakks road relief centre to CYS Road lorry station with additional work in dn 76 of zone-6.,Own Sources,6,2020-21,2021-22 NF/2020-21/4159,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,76,532300,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-76, UNIT-17, ZONE-VI",Own Sources,6,2020-21,2021-22 L/2020-21/0502,Electrical,Completed,L-Electrical,77,2531600,"PROVISION OF 4 NOS. 36W TUBE LIGHTS AND 2 NOS 48 CEILING FANS IN EACH OF THE 432 FLATS OF K P PARK SLUM BOARD TENAMENTS, PHASE I ,DN77, ZONE VI",Own Sources,6,2020-21,2020-21 L/2020-21/0503,Electrical,Completed,L-Electrical,77,2531600,"NAME OF THE WORK: PROVISION OF 4 NOS. 36W TUBE LIGHTS AND 2 NOS 48 CEILING FANS IN EACH OF THE 432 FLATS OF K P PARK SLUM BOARD TENEMENTS, PHASE 2 ,DN77, ZONE VI",Own Sources,6,2020-21,2020-21 NF/2020-21/4158,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,77,509800,"DESILTING OF STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-77, UNIT-17, ZONE-VI",Own Sources,6,2020-21,2021-22 NF/2020-21/4161,Storm Water Drain,Completed,NF-THIRU-VI-KA NAGAR,78,552600,"DESILTING AND MINOR REPAIR WORKS TO EXISTING STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-78, UNIT-17, ZONE-VI",Own Sources,6,2020-21,2021-22 NG/2020-21/2502,Buildings,Completed,NG-AMBATTUR,79,138000,"ANNUAL MAINTENANCE FOR COC ROADS FOOTPATH COC BUILDING AND SWD IN DIVISION-79, UNIT-18, ZONE-VII ( AMBATTUR )",Own Sources,7,2020-21,2021-22 NG/2020-21/4119,Storm Water Drain,Completed,NG-AMBATTUR,79,260000,"Desilting works to Storm water Drain and Minor Repair works to Storm water/Side Drains (IRR) in Division-79, Unit-18, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/4121,Storm Water Drain,Completed,NG-AMBATTUR,79,1028000,"Desilting works to Storm water Drain (IRR) and Minor Repair works to Storm water/Side Drains (IRR) in Division-81, Unit-18, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3621,Buildings,Completed,NG-AMBATTUR,80,300000,"ANNUAL MAINTENANCE WORK IN DIVISION -80, UNIT-18, ZONE-7(AMBATTUR)",Own Sources,7,2020-21,2021-22 NG/2020-21/3848,Storm Water Drain,Completed,NG-AMBATTUR,80,955000,"DE-SILTING AND MINOR REPAIR WORK TO THE EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-80,UNIT-18, ZONE-7",Own Sources,7,2020-21,2020-21 BR/2020-21/5931,Roads,Completed,BR-Bus Route Roads,81,6227000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Cholapuram Main Road in Dn-81,Zone VII",Grants,7,2020-21,2021-22 BR/2020-21/5940,Roads,Completed,BR-Bus Route Roads,81,6615000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Kalli Kuppam Road (K.K Road) in Dn-81,Zone VII",Grants,7,2020-21,2021-22 NG/2020-21/4643,Buildings,Completed,NG-AMBATTUR,81,190000,"ANNUAL MAINTENANCE FOR COC ROADS, FOOTPATH, COC BUILDING AND SWD IN DIVISION-81, ZONE-7 AMBATTUR",Own Sources,7,2020-21,2021-22 BR/2020-21/5941,Roads,Completed,BR-Bus Route Roads,82,9592000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Karrku Main Road in Dn-82,Zone VII",Grants,7,2020-21,2021-22 BR/2020-21/5942,Roads,Completed,BR-Bus Route Roads,82,2046000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Gnanamoorthy Nagar Main road in Dn-82,Zone VII",Grants,7,2020-21,2021-22 BR/2020-21/5943,Roads,Completed,BR-Bus Route Roads,82,2431000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Prithiv Pakkam main Road in Dn-82,Zone VII",Grants,7,2020-21,2021-22 NG/2020-21/10086,Roads,Completed,NG-AMBATTUR,82,2669000,"RELAYING OF BT ROAD AT BALAVINAYAGAR NAGAR IN DIV 82,UNIT-18, ZONE-7",Own Sources,7,2020-21,2020-21 NG/2020-21/10088,Roads,Completed,NG-AMBATTUR,82,2140000,"RELAYING OF BT ROAD AT THEEPANJI STREET IN DIV 82,UNIT-18, ZONE-7",Own Sources,7,2020-21,2020-21 NG/2020-21/10090,Roads,Completed,NG-AMBATTUR,82,1444000,"RELAYING OF BT ROAD AT VIJAYALAKSHMI NAGAR (NEAR MOOBAMBIGAI NAGAR) IN DIV 82,UNIT-18, ZONE-7",Own Sources,7,2020-21,2020-21 NG/2020-21/10092,Roads,Completed,NG-AMBATTUR,82,322000,"RELAYING OF BT ROAD AT MUTHAMIZH NAGAR 16TH STREET IN DIV 82,UNIT-18, ZONE-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3963,Storm Water Drain,Completed,NG-AMBATTUR,82,575000,"DE-SILTING AND MINOR REPAIR WORKS TO THE EXISTING STORM WATER DRAINS & SIDE DRAINS AT VARIOUS STREETS IN DIVISION-82,UNIT-18, ZONE-7",Own Sources,7,2020-21,2020-21 BR/2020-21/8457,Road Cut,Completed,BR-Bus Route Roads,83,770000,"Roadcut Restoration at TNHB 41 St Street,Thiruvaluvar Street,Rukmani Ammal 2 nd Street,Rukmani Ammal 1 st Street,Station Road and Ramalinga Achari Street in Dn-83, Unit-18,Zone 7",Deposit Works,7,2020-21,2020-21 NG/2020-21/4068,Storm Water Drain,Completed,NG-AMBATTUR,83,682000,"Desillting of Strom water drains in Division-83,Unit-18,Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/5462,Buildings,Completed,NG-AMBATTUR,83,3200000,"Proposed Additional Construction Of Micro Compost Centre at TNHB 61ST Street with a Capacity of 2MT/day Including Bio-Shredder & Electrical Arrangement etc.,In Dn-83,Unit-18, Zone-7",Own Sources,7,2020-21,2021-22 BR/2020-21/11461,Roads,Completed,BR-Bus Route Roads,84,1250000,"Restoration of Road cut made by CMWSSB at East Avenue Road in Div-84, Zone-7. Against Challan No.BR/2020-21/0017694 dt-31/12/2020 -Deposite Code -57/0398/2020-21",Deposit Works,7,2020-21,2020-21 BR/2020-21/2893,Roads,Completed,BR-Bus Route Roads,84,2350000,"Improvement to Centre Median at East Avenue Road (From MTH road to Tony Guy Essentual Shop) in Division - 84 ,Zone -7",Own Sources,7,2020-21,2021-22 BR/2020-21/7788,Road Cut,Completed,BR-Bus Route Roads,84,221000,"Restoration of OFC Roadcut at TNHB 18 th , 17 th ,16 th ,11th, 2nd street and Gangai Amman koil street,Railway station Road,Dn- 84,Zone 07",Deposit Works,7,2020-21,2020-21 NG/2020-21/3130,Roads,Completed,NG-AMBATTUR,84,1225000,"Relaying a BT road at Kamaraj Nagar 7th Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3131,Roads,Completed,NG-AMBATTUR,84,697000,"Relaying a BT road at Kamaraj Nagar 8th Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3132,Roads,Completed,NG-AMBATTUR,84,408000,"Relaying a BT road at Kannagi Nagar 4th Street(Partly) in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3134,Roads,Completed,NG-AMBATTUR,84,252000,"Relaying a BT road at TNHB 7th Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3144,Roads,Completed,NG-AMBATTUR,84,1154000,"Relaying a BT road at Reddy Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3153,Roads,Completed,NG-AMBATTUR,84,953000,"Relaying a BT road at Kanni Amman Koil Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3162,Roads,Completed,NG-AMBATTUR,84,2329000,"Relaying a BT road at TNHB 3rd Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3166,Roads,Completed,NG-AMBATTUR,84,762000,"Relaying a BT road at Bramin 1st Street(Patravakkam)in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3167,Roads,Completed,NG-AMBATTUR,84,1175000,"Relaying a BT road at Bramin 2nd Street (Patravakkam) in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3168,Roads,Completed,NG-AMBATTUR,84,483000,"Relaying a BT road at Bramin 3rd Street (Patravakkam) in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3169,Roads,Completed,NG-AMBATTUR,84,903000,"Relaying a BT road at Thirumalai Nagar in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3170,Roads,Completed,NG-AMBATTUR,84,1775000,"Relaying a BT road at TNHB 17th Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3201,Roads,Completed,NG-AMBATTUR,84,781000,"Relaying a BT road at Kamarajar 1st street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3203,Roads,Completed,NG-AMBATTUR,84,1754000,"Relaying a BT road at Kamarajar nagar 2nd Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3204,Roads,Completed,NG-AMBATTUR,84,945000,"Relaying a BT road at Kamarajar nagar 3RD Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3206,Roads,Completed,NG-AMBATTUR,84,167000,"Relaying a BT road at Kamarajar nagar 4th Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3208,Roads,Completed,NG-AMBATTUR,84,759000,"Relaying a BT road at Kamarajar nagar 5TH Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3211,Roads,Completed,NG-AMBATTUR,84,398000,"Relaying a BT road at Shanthi nagar 1st Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3213,Roads,Completed,NG-AMBATTUR,84,273000,"Relaying a BT road at Shanthi nagar 2nd Street in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3214,Roads,Completed,NG-AMBATTUR,84,393000,"Relaying a BT road at Chavadi Street(Partly) in Div-84, Unit-19, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/4079,Electrical,Completed,NG-AMBATTUR,84,600000,"Desilting & Minor Repair Work To The Existing Road Side Drain At Various Interior Streets In Division-84, Unit-19,Zone-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/5087,Buildings,Completed,NG-AMBATTUR,84,3200000,"Proposed Additional Construction of Micro Compost Center at Kannagi Nagar Burial Ground with a capacity of 2MT/day Including Bio-Shredder & Electrical Arrangements in Dn-84,Unit-19,Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/5139,Buildings,Completed,NG-AMBATTUR,84,150000,"Maintenance Works to the Amma Unavagam at EB Road,Division office ,Micro Compost Center and Flood Precaution Work in Div - 84, Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/3874,Storm Water Drain,Completed,NG-AMBATTUR,85,800000,"Desilting of Side Drain &Storm water Drain at various Streets in Div-85, Unit-19, Zone-7 (Ambattur).",Own Sources,7,2020-21,2020-21 BR/2020-21/5945,Roads,Completed,BR-Bus Route Roads,86,11249000,"Relaying the road with DBM and BC after cold milling by paver finisher along with traffic improvement work at ICF Colony Ayyapakkam Main Road in Dn-86,Zone VII",Grants,7,2020-21,2021-22 BR/2020-21/5954,Roads,Completed,BR-Bus Route Roads,86,3634000,"Relaying the road with DBM and BC after cold milling by paver finisher along with traffic improvement work at Kalaivanar Nagar Main Road in Dn-86,Zone VII",Grants,7,2020-21,2021-22 L/2020-21/1049,Electrical,Completed,L-Electrical,86,2099000,"PROVISION OF 6 NOS TUBE LIGHTS AND 3 NOS FANS AND 4 NOS 10W LED BULB IN EACH OF THE 228 FLATS IN BLOCK NO. 2, TAMIL NADU HOUSING BOARD TENAMENTS, VANAGARAM MAIN ROADATHIPETTU, DIV 86, ZONE 7",Own Sources,7,2020-21,2020-21 L/2020-21/1050,Electrical,Completed,L-Electrical,86,2099000,"PROVISION OF 6 NOS TUBE LIGHTS AND 3 NOS FANS AND 4 NOS 10W LED BULB IN EACH OF THE 228 FLATS IN BLOCK NO. 3,TAMIL NADU HOUSING BOARD TENAMENTS, VANAGARAM MAIN ROADATHIPETTU, DIV 86, ZONE 7",Own Sources,7,2020-21,2020-21 L/2020-21/1051,Electrical,Completed,L-Electrical,86,2099000,"PROVISION OF 6 NOS TUBE LIGHTS AND 3 NOS FANS AND 4 NOS 10W LED BULB IN EACH OF THE 228 FLATS IN BLOCK NO. 5, TAMIL NADU HOUSING BOARD TENAMENTS, VANAGARAM MAIN ROADATHIPETTU, DIV 86, ZONE 7",Own Sources,7,2020-21,2020-21 L/2020-21/1052,Electrical,Completed,L-Electrical,86,1399400,"PROVISION OF 6 NOS TUBE LIGHTS AND 3 NOS FANS AND 4 NOS 10W LED BULB IN EACH OF THE 152 FLATS IN BLOCK NO. 7, TAMIL NADU HOUSING BOARD TENAMENTS, VANAGARAM MAIN ROADATHIPETTU, DIV 86, ZONE 7",Own Sources,7,2020-21,2020-21 L/2020-21/1053,Electrical,Completed,L-Electrical,86,2573800,"PROVISION OF TUBE LIGHTS , FANS AND 10W LED BULB IN 285 FLATS IN BLOCK NO. 10, TAMIL NADU HOUSING BOARD TENAMENTS, VANAGARAM MAIN ROADATHIPETTU, DIV 86, ZONE 7",Own Sources,7,2020-21,2020-21 L/2020-21/1054,Electrical,Completed,L-Electrical,86,2573800,"PROVISION OF TUBE LIGHTS , FANS AND 10W LED BULB IN 285 FLATS IN BLOCK NO. 11, TAMIL NADU HOUSING BOARD TENAMENTS, VANAGARAM MAIN ROADATHIPETTU, DIV 86, ZONE 7",Own Sources,7,2020-21,2020-21 NG/2020-21/10623,Buildings,Completed,NG-AMBATTUR,86,355000,"Repairs and Maintenance works to existing GCC Buildings in division -86, unit- 19, Zone - 7.",Own Sources,7,2020-21,2021-22 NG/2020-21/4280,Storm Water Drain,Completed,NG-AMBATTUR,86,900000,"Desilting Works to the existing side drain and Storm Water Drain at various Streets in division -86, unit- 19, Zone - 7.",Own Sources,7,2020-21,2020-21 NG/2020-21/5458,Buildings,Completed,NG-AMBATTUR,86,3200000,"Proposed Additional Construction Of Micro Compost Centre at Manikkam Pillai Street with a Capacity of 2MT/day Including Bio-Shredder & Electrical Arrangement etc.,In Dn-86,Unit-19, Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/9065,Buildings,Completed,NG-AMBATTUR,86,140000,"Repairs and Mantenance works to existing GCC Buildings in division -86, unit- 19, Zone - 7.",Own Sources,7,2020-21,2021-22 NG/2020-21/3089,Roads,Completed,NG-AMBATTUR,87,133000,"Relaying of BT Road at Thiruvalluvar 2nd cross street in Division-87,Unit-19,Zone-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/3091,Roads,Completed,NG-AMBATTUR,87,102000,"Relaying if BT Road at Thiruvalluvar 3rd cross street in Division-87,Unit-19,Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3092,Roads,Completed,NG-AMBATTUR,87,331000,"Re laying of BT Road at Sathiyavathi nagar 3rd cross street in Division-87,Unit-19,Zone-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/3997,Storm Water Drain,Completed,NG-AMBATTUR,87,500000,"De silting of various street in division-87,Unit-19,Zone-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/2528,Buildings,Completed,NG-AMBATTUR,88,1196500,"Operation and maintenance for the 5th year period (2020-21) (RO/UV filtration) of 2000 litres/hour capacity expandables to 4000litres/hour capacity (2000 litres expandables increment of 2000litres/hours and at Kalaivanar Nagar, Anna Nagar West in Division-88,Unit-19,Zone-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/4942,Storm Water Drain,Completed,NG-AMBATTUR,88,700000,DESILTING OF STORM WATER DRAIN AT VARIOUS STREETS IN DIVISION- 88 UNIT-19 ZONE-7(AMBATTUR),Own Sources,7,2020-21,2020-21 NG/2020-21/5323,Buildings,Completed,NG-AMBATTUR,88,335000,"Repairs and maintanance for corporation buildings, parks,etc.,Annual maintanance works in Division -88, Unit-19, Zone-VII",Own Sources,7,2020-21,2021-22 NG/2020-21/0907,Buildings,Completed,NG-AMBATTUR,89,1520000,"Operation and maintenance for the 5th year period (2020-21) (RO/UV filtration) of 2000 litres/hour capacity expandables to 4000litres/hour capacity (2000 litres expandables increment of 2000litres/hours and at Thirumangalam Main Road in Division-89,Unit-20,Zone-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/4175,Storm Water Drain,Completed,NG-AMBATTUR,89,700000,"De-silting, Storm Water Drain and Minnor Repair work at Various Street (IRR) Div-89, Unit-20, Zone-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/9779,Playfields,Completed,NG-AMBATTUR,89,990000,"PROVIDING GYM EQUIPMENTS TO GYM BUILDING AT ELANGO NAGAR IN DN 89, UNIT - 20, ZONE VII",Own Sources,7,2020-21,2020-21 NG/2020-21/0840,Buildings,Completed,NG-AMBATTUR,90,84000,"Maintenance work for Amma Unavagam at Collector Nagar and Padi Pudhu Nagar 3rd Street in Div - 90, Unit-20, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/10237,Buildings,Completed,NG-AMBATTUR,90,128000,"Maintenance work for Division Office at Padiputhu Nagar Main Road in Div - 90, Unit-20, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/1881,Roads,Completed,NG-AMBATTUR,90,628000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 1ST STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1884,Roads,Completed,NG-AMBATTUR,90,591000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 2ND STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1885,Roads,Completed,NG-AMBATTUR,90,483000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 4TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1887,Roads,Completed,NG-AMBATTUR,90,479000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 5TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1889,Roads,Completed,NG-AMBATTUR,90,471000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 7TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/1892,Roads,Completed,NG-AMBATTUR,90,433000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 8TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/1908,Roads,Completed,NG-AMBATTUR,90,475000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 9TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1915,Roads,Completed,NG-AMBATTUR,90,446000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 10TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/1917,Roads,Completed,NG-AMBATTUR,90,395000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 11TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/1923,Roads,Completed,NG-AMBATTUR,90,369000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 12TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/1924,Roads,Completed,NG-AMBATTUR,90,356000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 13TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2020-21 NG/2020-21/1926,Roads,Completed,NG-AMBATTUR,90,366000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 14TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1928,Roads,Completed,NG-AMBATTUR,90,330000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 15TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1929,Roads,Completed,NG-AMBATTUR,90,335000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 16TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1930,Roads,Completed,NG-AMBATTUR,90,296000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 17TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1931,Roads,Completed,NG-AMBATTUR,90,272000,"RELAYING OF BT ROAD AT PADIPUTHU NAGAR 18TH STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1935,Roads,Completed,NG-AMBATTUR,90,426000,"RELAYING OF BT ROAD AT COLLECTOR NAGAR 2ND STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1936,Roads,Completed,NG-AMBATTUR,90,53000,"RELAYING OF BT ROAD AT COLLECTOR NAGAR 2ND CROSS STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1938,Roads,Completed,NG-AMBATTUR,90,1264000,"RELAYING OF BT ROAD AT RAM NAGAR IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1941,Roads,Completed,NG-AMBATTUR,90,276000,"RELAYING OF BT ROAD AT GANDHI STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1945,Roads,Completed,NG-AMBATTUR,90,276000,"RELAYING OF BT ROAD AT RAJAJI STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/1947,Roads,Completed,NG-AMBATTUR,90,276000,"RELAYING OF BT ROAD AT VINAYAGAR KOVIL STREET IN DIVISION-90, UNIT-20, ZONE-7.",Own Sources,7,2020-21,2021-22 NG/2020-21/2555,Buildings,Completed,NG-AMBATTUR,90,122000,"IMPROVEMENTS WORKS TO EXISTING PUBLIC TOILET AT THIRUMANGALAM MAIN ROAD IN DN 90, UNIT - 20, ZONE - VII",Own Sources,7,2020-21,2020-21 NG/2020-21/4164,Storm Water Drain,Completed,NG-AMBATTUR,90,600000,"De-silting of Storm Water Drain and Minor repair at Various Street (IRR) Div-90, Unit-20, Zone-7.",Own Sources,7,2020-21,2020-21 BR/2020-21/5946,Roads,Completed,BR-Bus Route Roads,91,5587000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Mogappair West 3 rd main Road in Dn-91,Zone VII",Grants,7,2020-21,2021-22 NG/2020-21/1131,Buildings,Completed,NG-AMBATTUR,91,282000,"Improvement works to the existing Community Hall at Mogappair West 3rd Main Road in Division - 91, Unit-20, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/3020,Roads,Completed,NG-AMBATTUR,91,449000,FORMING OF BT ROAD AT MOGAPPAIR ERI SCHEME 20TH CROSS STREET IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2020-21,2020-21 NG/2020-21/3029,Roads,Completed,NG-AMBATTUR,91,191000,FORMING OF BT ROAD AT MOGAPPAIR ERI SCHEME 25TH CROSS STREET IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2020-21,2020-21 NG/2020-21/3031,Roads,Completed,NG-AMBATTUR,91,359000,FORMING OF BT ROAD AT MOGAPPAIR ERI SCHEME 24TH CROSS STREET IN DIVISION-91 UNIT-20 ZONE-07,Own Sources,7,2020-21,2020-21 NG/2020-21/4021,Storm Water Drain,Completed,NG-AMBATTUR,91,600000,"DESILTING (IRR-SIDE DRAIN) AND MINOR REPAIRS AT VARIOUS STREETS IN DN-91,UNIT-20, ZONE-7",Own Sources,7,2020-21,2020-21 BR/2020-21/5949,Roads,Completed,BR-Bus Route Roads,92,2255000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Vellalar Street in Dn-92,Zone VII",Grants,7,2020-21,2021-22 BR/2020-21/5953,Roads,Completed,BR-Bus Route Roads,92,3985000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Venugopal Street in Dn-92,Zone VII",Grants,7,2020-21,2021-22 NG/2020-21/0911,Buildings,Completed,NG-AMBATTUR,92,1520000,"Operation and maintenance for the 5th year period (2020-21) (RO/UV filtration) of 2000 litres/hour capacity expandables to 4000litres/hour capacity (2000 litres expandables increment of 2000litres/hours and at Seethakathi Salai in Division-92,Unit-20,Zone-7",Own Sources,7,2020-21,2021-22 NG/2020-21/1165,Buildings,Completed,NG-AMBATTUR,92,235000,"Providing Deep Bore Well at Mogappair Road Burial ground in Div - 92, Unit-20, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/1169,Buildings,Completed,NG-AMBATTUR,92,185000,"Providing Deep Bore Well at Division Office, Pattinathar Salai in Dn - 92, Unit-20, Zone-7",Own Sources,7,2020-21,2020-21 NG/2020-21/2613,Buildings,Completed,NG-AMBATTUR,92,223000,"Providing Toilet for Conservancy Workers at Division Office, Pattinathar Salai in Dn 92, Unit -20, Zone VII",Own Sources,7,2020-21,2020-21 NG/2020-21/3000,Buildings,Completed,NG-AMBATTUR,92,525000,"CONSTRUCTION OF TOILET (CONSERVANCY WORKERS) AT DIVISION OFFICE, PATTINATHAR SALAI IN DN 92, UNIT - 20, ZONE - VII",Own Sources,7,2020-21,2021-22 NG/2020-21/4022,Storm Water Drain,Completed,NG-AMBATTUR,92,800000,"DESILTING (IRR-SIDE DRAIN) AND MINOR REPAIRS AT VARIOUS STREETS IN DN-92,UNIT-20, ZONE-7",Own Sources,7,2020-21,2020-21 NG/2020-21/5870,Buildings,Completed,NG-AMBATTUR,92,710000,"CONSTRUCTION OF C.I. ROOM AT DIVISION OFFICE, PATTINATHAR SALAI IN DN 92, UNIT - 20, ZONE - VII",Own Sources,7,2020-21,2020-21 NG/2020-21/1076,Roads,Completed,NG-AMBATTUR,93,290000,"Laying B.T. Surface at Mogappair East Industrial Road in Div - 93, Unit-20, Zone-7",Deposit Works,7,2020-21,2020-21 NG/2020-21/1174,Electrical,Completed,NG-AMBATTUR,93,318200,"Supply and erection of nos. of 15 Nos of 2 mtr lamp posts with single bracket and 2 nos. of 4 way bracket posts with 23 Nos. of 15 W LED Lattern type Fittings for New GCC -Yuga Kalpataru Park , Rail Nagar in Division 93, Zone VII",Own Sources,7,2020-21,2021-22 NG/2020-21/1903,Roads,Completed,NG-AMBATTUR,93,803000,"RELAYING OF BT ROAD AT GANAGAIAMMAN NAGAR MAIN ROAD IN DIV 93,UNIT-20, ZONE-7",Own Sources,7,2020-21,2021-22 NG/2020-21/1905,Roads,Completed,NG-AMBATTUR,93,567000,"RELAYING OF BT ROAD AT MGR STREET IN DIV 93,UNIT-20, ZONE-7",Own Sources,7,2020-21,2021-22 NG/2020-21/1910,Roads,Completed,NG-AMBATTUR,93,2582000,"RELAYING OF BT ROAD AT MARAIMALAI ADIKALAR SALAI IN DIV 93,UNIT-20, ZONE-7",Own Sources,7,2020-21,2021-22 NG/2020-21/1911,Roads,Completed,NG-AMBATTUR,93,530000,"RELAYING OF BT ROAD AT 2ND BLOCK AGATHIYAR SALAI 5TH STREET IN DIV 93,UNIT-20, ZONE-7",Own Sources,7,2020-21,2021-22 NG/2020-21/4167,Storm Water Drain,Completed,NG-AMBATTUR,93,800000,"DESILTING (IRR-SIDE DRAIN) AND MINOR REPAIRS AT VARIOUS STREETS IN DN-93,UNIT-20, ZONE-7",Own Sources,7,2020-21,2020-21 BR/2020-21/1764,Roads,Completed,BR-Bus Route Roads,94,12816000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Konnur High Road in Dn-94 & 96, Zone - VIII",Grants,8,2020-21,2020-21 BR/2020-21/1766,Roads,Completed,BR-Bus Route Roads,94,3310000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Sidco Nagar 1 st Main Road in Dn-94, Zone - VIII",Grants,8,2020-21,2020-21 BR/2020-21/1769,Roads,Completed,BR-Bus Route Roads,94,1878000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Sidco Nagar 4th Main Road in Dn-94, Zone - VIII",Grants,8,2020-21,2020-21 BR/2020-21/1770,Roads,Completed,BR-Bus Route Roads,94,4308000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at MTH Road in Dn-94 & 95, Zone - VIII",Grants,8,2020-21,2020-21 NH/2020-21/2336,Subway,Completed,NH-ANNA NAGAR,94,513000,"MAINTENANCE OF VILLIVAKAM SUBWAY FOR FOUR MONTHS IN DIVISION-94, UNIT-21, ZONE 8",Own Sources,8,2020-21,2021-22 NH/2020-21/3769,Storm Water Drain,Completed,NH-ANNA NAGAR,94,689000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION - 94, UNIT-21, ZONE 8",Own Sources,8,2020-21,2021-22 BR/2020-21/1773,Roads,Completed,BR-Bus Route Roads,95,1593000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Reddy Street in Dn-95, Zone - VIII",Grants,8,2020-21,2020-21 NH/2020-21/2147,Buildings,Completed,NH-ANNA NAGAR,95,96900,"DISMANTLING AND REMOVAL OF COLLAPSED RCC COVER SLAB OVER THE TVS CANAL AT SIVASAKTHI COLONY IN DN - 95, UNIT - 21, ZONE - 08",Own Sources,8,2020-21,2021-22 NH/2020-21/2150,Buildings,Completed,NH-ANNA NAGAR,95,91300,"PROVIDING BIN PLATFORM AT AGATHIYAR NAGAR 1ST STREET , 18TH MAIN ROAD & REPAIR OF DAMAGED SWD MH COVER AND RCC SLAB AT THIRUMANGALAM IN DIVISION - 95, UNIT - 21, ZONE - 08",Own Sources,8,2020-21,2021-22 NH/2020-21/3774,Storm Water Drain,Completed,NH-ANNA NAGAR,95,699000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION - 95, UNIT-21, ZONE 8",Own Sources,8,2020-21,2020-21 NH/2020-21/10002,Buildings,Completed,NH-ANNA NAGAR,96,989000,"IMPROVEMENTS WORKS TO THE EXISTING MULTIPURPOSE HALL BUILDING AT K.K NAGAR 5TH STREET IN DIVISION-96, UNIT-21, ZONE-VIII",Own Sources,8,2020-21,2021-22 NH/2020-21/4135,Storm Water Drain,Completed,NH-ANNA NAGAR,96,691000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION - 96, UNIT-21, ZONE 8",Own Sources,8,2020-21,2021-22 NH/2020-21/4186,Storm Water Drain,Completed,NH-ANNA NAGAR,97,691000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-97, UNIT-21, ZONE 8",Own Sources,8,2020-21,2021-22 NH/2020-21/2295,Buildings,Completed,NH-ANNA NAGAR,98,144000,"REPAIRS AND IMPROVEMENT TO THE AMMA UNAVAGAM AT AYANAVARAM ROAD IN DIVISION-98, UNIT-23, ZONE-8.",Own Sources,8,2020-21,2020-21 NH/2020-21/3778,Storm Water Drain,Completed,NH-ANNA NAGAR,98,666000,"DESILTING AND MINOR REPAIRS WORKS TO STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION-98, UNIT-23, ZONE 8",Own Sources,8,2020-21,2020-21 NH/2020-21/7064,Buildings,Completed,NH-ANNA NAGAR,98,314200,"DEMOLITION OF DHOBIGANA AT PUDU NAGAR 1ST STREET IN DIVISION-98, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/2809,Roads,Completed,NH-ANNA NAGAR,99,2300000,"PROVIDING AND LAYING OF CEMENT CONCRETE ROAD AT V.O.C. STREET, GANDHI MAIN ROAD (PART), W-BLOCK 1ST STREET, CHURCH CROSS STREET AND CHURCH 1ST CROSS STREET IN DIVISION-99, UNIT-21, ZONE-8 (MLA FUND)",MLACDS,8,2020-21,2020-21 NH/2020-21/3773,Storm Water Drain,Completed,NH-ANNA NAGAR,99,690000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -99, UNIT-21, ZONE 8",Own Sources,8,2020-21,2020-21 NH/2020-21/5203,Roads,Completed,NH-ANNA NAGAR,99,735000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT G BLOCK 14TH STREET & EXTN., (PART) IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5204,Roads,Completed,NH-ANNA NAGAR,99,342000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT G BLOCK 16TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5205,Roads,Completed,NH-ANNA NAGAR,99,342000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AF BLOCK 7TH STREET (PART) IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5206,Roads,Completed,NH-ANNA NAGAR,99,565000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AF BLOCK 1ST STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5207,Roads,Completed,NH-ANNA NAGAR,99,479000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT H BLOCK 1ST STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5208,Roads,Completed,NH-ANNA NAGAR,99,240000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT J BLOCK 13TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5209,Roads,Completed,NH-ANNA NAGAR,99,206000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT J BLOCK 12TH STREET IN DIVISION-99, UNIT-21, ZONE-8",Own Sources,8,2020-21,2021-22 BR/2020-21/2466,Roads,Completed,BR-Bus Route Roads,100,6016000,"Relaying the road with BC after cold milling by paver finisher using plastic waste along with traffic improvement work at Anna Nagar 3 rd Avenue in Dn-100 &101 ,Zone - VIII",Grants,8,2020-21,2020-21 NH/2020-21/10300,Roads,Completed,NH-ANNA NAGAR,100,714100,"RESTORATION OF ROAD CUT MADE BY ACT (OPTICAL FIBER CABLE )AT VARIOUS STREET IN DIVISION-100,UNIT-22,ZONE-08..",Deposit Works,8,2020-21,2021-22 NH/2020-21/3775,Storm Water Drain,Completed,NH-ANNA NAGAR,100,699000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -100, UNIT-22, ZONE 8",Own Sources,8,2020-21,2020-21 NH/2020-21/3776,Roads,Completed,NH-ANNA NAGAR,100,466000,"RELAYING OF BT ROAD AT R BLOCK 12th STREET DIVISION-100, UNIT-22, ZONE-08",Own Sources,8,2020-21,2020-21 NH/2020-21/3777,Roads,Completed,NH-ANNA NAGAR,100,740000,"RELAYING OF BT ROAD AT R BLOCK 16th STREET DIVISION-100, UNIT-22, ZONE-08",Own Sources,8,2020-21,2020-21 NH/2020-21/5933,Buildings,Completed,NH-ANNA NAGAR,100,177000,"IMPROVEMENTS TO KITCHEN SHED AT NSK NAGAR CPS SCHOOL IN DIVISION -100 ,UNIT-22, ZONE- 8",Own Sources,8,2020-21,2021-22 NH/2020-21/6721,Roads,Completed,NH-ANNA NAGAR,100,1105000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 9TH MAIN ROAD IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6722,Roads,Completed,NH-ANNA NAGAR,100,550000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT R BLOCK 16TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6723,Roads,Completed,NH-ANNA NAGAR,100,1421000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT Z BLOCK 11TH STREET (FROM Z BLOCK 12TH STREET TO Z BLOCK 6TH STREET) IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6724,Roads,Completed,NH-ANNA NAGAR,100,228000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AK BLOCK 5TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6735,Roads,Completed,NH-ANNA NAGAR,100,228000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AK BLOCK 6TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6736,Roads,Completed,NH-ANNA NAGAR,100,228000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AK BLOCK 7TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6737,Roads,Completed,NH-ANNA NAGAR,100,228000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT AK BLOCK 8TH STREET IN DIVISION-100, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 BR/2020-21/11541,Road Cut,Completed,BR-Bus Route Roads,101,975000,"Restoration of Roadcut (OFC) at various Street in Dn-101,Unit 22, Zone VIII",Deposit Works,8,2020-21,2020-21 BR/2020-21/11542,Road Cut,Completed,BR-Bus Route Roads,101,991000,"Restoration of Roadcut (OFC) at Various street in Dn-101 &102, Unit -22, Zone VIII",Deposit Works,8,2020-21,2020-21 BR/2020-21/4833,Road Cut,Completed,BR-Bus Route Roads,101,2333000,Restoration of Roadcut done by TANGEDCO in Anna Nagar 1 St avenue(From the Jn of New Avadi Road to Nilgiris Shop) in Dn-101 Zone VIII,Deposit Works,8,2020-21,2021-22 NH/2020-21/3014,Buildings,Completed,NH-ANNA NAGAR,101,1170000,"NEW CONSTRUCTION OF OPEN GYM AT BOUGAINVILLA PARK IN DIVISION-101,UNIT-22,ZONE-8.(MLA FUND)",MLACDS,8,2020-21,2020-21 NH/2020-21/3032,Buildings,Completed,NH-ANNA NAGAR,101,1629000,"NEW CONSTRUCTION OF YOGA STAGE AT BOUGAINVILLA PARK IN DIVISION-101, UNIT-22, ZONE-8.(MLA FUND)",MLACDS,8,2020-21,2020-21 NH/2020-21/4139,Storm Water Drain,Completed,NH-ANNA NAGAR,101,696000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2020-21 NH/2020-21/5322,Roads,Completed,NH-ANNA NAGAR,101,258000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SHENOY NAGAR 3RD MAIN ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5336,Roads,Completed,NH-ANNA NAGAR,101,557000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT C BLOCK 9TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5341,Roads,Completed,NH-ANNA NAGAR,101,837000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT H BLOCK 4TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5343,Roads,Completed,NH-ANNA NAGAR,101,837000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT H BLOCK 5TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5346,Roads,Completed,NH-ANNA NAGAR,101,166000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 4TH MAIN ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5348,Roads,Completed,NH-ANNA NAGAR,101,919000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT WEST CLUB ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5351,Roads,Completed,NH-ANNA NAGAR,101,618000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 5TH MAIN ROAD IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5355,Roads,Completed,NH-ANNA NAGAR,101,1353000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT F BLOCK 9TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5379,Roads,Completed,NH-ANNA NAGAR,101,835000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT O BLOCK GANAPATHY COLONY IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5382,Roads,Completed,NH-ANNA NAGAR,101,474000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT C BLOCK 5TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5385,Roads,Completed,NH-ANNA NAGAR,101,280000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT K BLOCK 17TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5388,Roads,Completed,NH-ANNA NAGAR,101,529000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SHENOY NAGAR 8TH CROSS STREET (PART) IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5392,Roads,Completed,NH-ANNA NAGAR,101,1246000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT SHENOY NAGAR 1ST MAIN ROAD ( FROM SHENOY NAGAR 7TH CROSS STREET TO BREWARY ROAD) IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5394,Roads,Completed,NH-ANNA NAGAR,101,524000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT A BLOCK 11TH STREET IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5450,Buildings,Completed,NH-ANNA NAGAR,101,302000,"REPAIRS AND IMPROVEMENT WORKS TO THE ICDS CENTER AT BREWARY ROAD IN DIVISION-101,UNIT-22, ZONE-8.",Own Sources,8,2020-21,2021-22 NH/2020-21/5451,Buildings,Completed,NH-ANNA NAGAR,101,787800,"REPAIRS AND IMPROVEMENT WORKS TO THE ICDS CENTER AT N-BLOCK IN DIVISION-101,UNIT-22, ZONE-8.",Own Sources,8,2020-21,2021-22 NH/2020-21/9009,Buildings,Completed,NH-ANNA NAGAR,101,827000,"ERECTION OF NEW CHIMNEY FOR GASIFIRE CREMATORIUM MACHINE AT VELANGADU BURIAL GROUND IN DIVISION-101, UNIT-22, ZONE-8",Own Sources,8,2020-21,2020-21 NH/2020-21/10006,Roads,Completed,NH-ANNA NAGAR,102,943000,"Restoration of Interior BT road cut made by TNEB at 2nd Avenue Extension in Division 102, Unit 23, Zone 8",Deposit Works,8,2020-21,2021-22 NH/2020-21/10267,Buildings,Completed,NH-ANNA NAGAR,102,995000,"IMPROVEMENTS TO THE EXISTING MULTI PUPOSE HALL AT V.S. PURAM 18TH CROSS STREET IN DIVISION -102, UNIT -23, ZONE - 8",Own Sources,8,2020-21,2021-22 NH/2020-21/1758,Buildings,Completed,NH-ANNA NAGAR,102,1720000,"IMPROVEMENT WORKS AT REGIONAL DEPUTY COMMISSIONER OFFICE IN DIVISION-102, UNIT-23, ZONE-8.",Own Sources,8,2020-21,2021-22 NH/2020-21/1759,Buildings,Completed,NH-ANNA NAGAR,102,1600000,"REPAIR WORKS DUE TO FIRE ACCIDENT AT ALO AND ACHO OFFICE AT ZONAL OFFICE BUILDING IN DIVISION-102, UNIT-23, ZONE-8.",Own Sources,8,2020-21,2021-22 NH/2020-21/2334,Buildings,Completed,NH-ANNA NAGAR,102,398000,"IMPROVEMENT WORKS TO THE AMMA UNAVAGAM AT VS PURAM IN DIVISION-102, UNIT-23, ZONE-8.",Own Sources,8,2020-21,2021-22 NH/2020-21/4178,Storm Water Drain,Completed,NH-ANNA NAGAR,102,698000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -102, UNIT-23, ZONE-8",Own Sources,8,2020-21,2020-21 NH/2020-21/6827,Roads,Completed,NH-ANNA NAGAR,102,765000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TP CHATHIRAM 15TH CROSS STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6828,Roads,Completed,NH-ANNA NAGAR,102,769000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT 1ST MAIN ROAD EAST IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6829,Roads,Completed,NH-ANNA NAGAR,102,1153000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT EAST CLUB ROAD IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6830,Roads,Completed,NH-ANNA NAGAR,102,312000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT CONVENT STREET IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/6831,Roads,Completed,NH-ANNA NAGAR,102,667000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT NEW MANDAPAM ROAD IN DIVISION-102, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/10553,Buildings,Completed,NH-ANNA NAGAR,103,980000,"REPAIRS AND IMPROVEMENTS TO THE EXISTING GYM BUILDING AT RANI ANNA NAGAR IN DIVISION-103, UNIT-23,ZONE-8.",Own Sources,8,2020-21,2021-22 NH/2020-21/3771,Storm Water Drain,Completed,NH-ANNA NAGAR,103,537000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION -103, UNIT-23, ZONE 8",Own Sources,8,2020-21,2021-22 NH/2020-21/4137,Storm Water Drain,Completed,NH-ANNA NAGAR,103,399000,"DESILTING AND MINOR REPAIRS WORKS TO STORM WATER DRAIN AT BUS ROUTE ROADS IN DIVISION -103, UNIT-23, ZONE-8",Own Sources,8,2020-21,2020-21 NH/2020-21/5097,Roads,Completed,NH-ANNA NAGAR,103,747000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT BANK STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5129,Roads,Completed,NH-ANNA NAGAR,103,1189000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TEMPLE STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5131,Roads,Completed,NH-ANNA NAGAR,103,3113000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT TAYLORS ROAD IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/5132,Roads,Completed,NH-ANNA NAGAR,103,509000,"IMPROVEMENT TO THE INTERIOR B.T. ROAD AT PONNAPPA STREET IN DIVISION-103, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/2409,Road Cut,Completed,NH-ANNA NAGAR,104,930000,"RESTORATION OF BT ROAD CUT MADE BY CMWSSB AT SUNDRAM STREET IN DN-104,UNIT-23,ZONE-VIII",Deposit Works,8,2020-21,2020-21 NH/2020-21/4184,Storm Water Drain,Completed,NH-ANNA NAGAR,104,695000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -104, UNIT-23, ZONE-8",Own Sources,8,2020-21,2020-21 NH/2020-21/7040,Buildings,Completed,NH-ANNA NAGAR,104,262000,"IMPROVEMENTS TO URBAN PRIMARY HEALTH CENTRE AT RATHINA SABAPATHY STREET IN DIVISION 104, UNIT-23, ZONE 8",Own Sources,8,2020-21,2020-21 NH/2020-21/7041,Buildings,Completed,NH-ANNA NAGAR,104,315000,"IMPROVEMENTS TO PUBLIC CONVENIENCE BY PROVIDING WATER SUPPLY AND BASIC REPAIRS (LADIES) AT PULLAPURAM IN DIVISION 104, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 BR/2020-21/1733,Road Cut,Completed,BR-Bus Route Roads,105,1421000,"Restoration of Roadcut made by TANGEDCO at Vinayagapuram Main Road in Dn-105, Zone-VIII",Deposit Works,8,2020-21,2020-21 BR/2020-21/1985,Road Cut,Completed,BR-Bus Route Roads,105,1550000,"Restoration of Roadcut made by TANGEDCO at MMDA Colony Main Road (From the Jn Of Vinayagapuram Main Road to Thirupur Kumaran Street) in Dn-105, Zone-VIII",Deposit Works,8,2020-21,2020-21 BR/2020-21/1986,Road Cut,Completed,BR-Bus Route Roads,105,1550000,"Restoration of Roadcut made by TANGEDCO at MMDA Colony Main Road (From the Jn Of Thirupur Kumaran Street to Samuganalakudam Street) in Dn-105, Zone-VIII",Deposit Works,8,2020-21,2020-21 NH/2020-21/3342,Buildings,Completed,NH-ANNA NAGAR,105,3364957,"PROPOSED CONSTRUCTION OF ICDS CENTER AT MUTHUMARIAMMAN KOIL STREET (MMDA) IN DIVISION-105, UNIT-22, ZONE-8 (MLA FUND)",MLACDS,8,2020-21,2021-22 NH/2020-21/4142,Storm Water Drain,Completed,NH-ANNA NAGAR,105,888000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -105, UNIT-22, ZONE 8",Own Sources,8,2020-21,2021-22 NH/2020-21/6228,Buildings,Completed,NH-ANNA NAGAR,105,246000,"REPAIR AND IMPROVEMENTS WORK TO THE ICDS CENTER AT E BLOCK , D BLOCK PANIDYAN STREET AND G BLOCK IN DIVISION-105, UNIT-22, ZONE-08.",Own Sources,8,2020-21,2021-22 NH/2020-21/10406,Roads,Completed,NH-ANNA NAGAR,106,1165000,"RESTORATION OF ROAD CUT TO THE INTERIOR B.T ROAD MADE BY CMWSSB AT RAJARAM METHA NAGAR MAIN ROAD IN DIVISION-106, UNIT-22, ZONE-08.",Deposit Works,8,2020-21,2021-22 NH/2020-21/10417,Roads,Completed,NH-ANNA NAGAR,106,752000,"RESTORATION OF ROAD CUT TO THE INTERIOR B.T ROAD MADE BY CMWSSB AT GOVINDAN ROAD (PART) IN DIVISION-106, UNIT-22, ZONE-08.",Deposit Works,8,2020-21,2021-22 NH/2020-21/1963,Buildings,Completed,NH-ANNA NAGAR,106,314700,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE PUBLIC CONVENIENCE AT AMMAN KOIL STREET (MH COLONY) IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2020-21,2020-21 NH/2020-21/1964,Buildings,Completed,NH-ANNA NAGAR,106,282100,"PROVIDING WATER SUPPLY ARRANGEMENTS TO THE PUBLIC CONVENIENCE AT PERUMAL KOIL STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2020-21,2021-22 NH/2020-21/3770,Storm Water Drain,Completed,NH-ANNA NAGAR,106,709000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -106, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/3786,Roads,Completed,NH-ANNA NAGAR,106,214000,"RESTORATION OF INTERIOR CEMENT CONCRETE ROAD CUT MADE BY CMWSSB AT INDIRA GANDHI NAGAR 1ST STREET IN DIVISION-106, UNIT-22, ZONE-VIII",Deposit Works,8,2020-21,2021-22 NH/2020-21/3795,Roads,Completed,NH-ANNA NAGAR,106,587000,"RESTORATION OF INTERIOR BT ROAD CUT MADE BY CMWSSB AT VADA AGARAM ROAD IN DIVISION-106, UNIT-22, ZONE-VIII",Deposit Works,8,2020-21,2020-21 NH/2020-21/5787,Buildings,Completed,NH-ANNA NAGAR,106,300000,"REPAIRS AND IMPROVEMENT WORKS TO THE ICDS CENTER AT COLLECTORATE COLONY 6TH CROSS STREET IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2020-21,2020-21 NH/2020-21/5788,Buildings,Completed,NH-ANNA NAGAR,106,421000,"REPAIRS AND IMPROVEMENT WORKS TO THE ICDS CENTER AT INDIRAGANDHI NAGAR 1ST STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2020-21,2021-22 NH/2020-21/5789,Buildings,Completed,NH-ANNA NAGAR,106,277000,"REPAIRS AND IMPROVEMENT WORKS TO THE ICDS CENTER AT MH COLONY 3RD CROSS STREET IN DIVISION-106, UNIT-22, ZONE-8.",Own Sources,8,2020-21,2021-22 NH/2020-21/5790,Buildings,Completed,NH-ANNA NAGAR,106,276000,"REPAIRS AND IMPROVEMENT WORKS TO THE ICDS CENTER AT OFFICERS COLONY 3RD CROSS STREET IN DIVISION-106, UNIT-22, ZONE-08.",Own Sources,8,2020-21,2021-22 L/2020-21/3863,Electrical,Completed,L-Electrical,107,346100,"Removal and Re-Fixing of 16 Mtr. High Mast at Central Asphaltic plant Campus in Div.107, Zone - VIII Area.",Own Sources,8,2020-21,2020-21 NH/2020-21/1616,Playfields,Completed,NH-ANNA NAGAR,107,2490000,"PROVIDING CONCRETE BASE COURSE ,FOOTPATH TILES AND LIGHTING ARRANGEMENTS FOR THE PROPOSED SYNTHETIC TURF OF FOOTBALL GROUND AT Dr.AMBEDKAR PLAY GROUND IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2020-21,2021-22 NH/2020-21/1708,Buildings,Completed,NH-ANNA NAGAR,107,2400000,"CONSTRUCTION OF COMPOUND WALL AND GATE WITH GATE PILLAR AND RETAINING WALL OF RCC FLOORS AT CAP IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2020-21,2020-21 NH/2020-21/1795,Subway,Completed,NH-ANNA NAGAR,107,280000,"MAINTENANCE OF HARRINGTON ROAD SUBWAY ENGAGING OF ELECTRICIAN,PLUMBER AND WATCHMAN FOR FOUR MONTHS IN DIVISION-107 UNIT-23, ZONE-8.",Own Sources,8,2020-21,2020-21 NH/2020-21/3886,Storm Water Drain,Completed,NH-ANNA NAGAR,107,577000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS AND BUS ROUTE ROADS IN DIVISION -107, UNIT-23, ZONE-8",Own Sources,8,2020-21,2020-21 NH/2020-21/5456,Playfields,Completed,NH-ANNA NAGAR,107,4000000,"SUPPLYING AND LAYING OF ARTIFICIAL GRASS AND FIXING OF TURF MONOFILAMENT GRASS FIBRE AT Dr.AMBEDKAR PLAY GROUND IN DIVISION-107, UNIT-23, ZONE-08.(MLA FUND)",MLACDS,8,2020-21,2020-21 NH/2020-21/5460,Playfields,Completed,NH-ANNA NAGAR,107,550000,"RAISING THE EXISTING GROUND LEVEL BY PROVIDING AND LAYING WETMIX MACADAM AT Dr.AMBEDKAR PLAY GROUND IN DIVISION-107, UNIT-23, ZONE-08. (MLA FUND)",MLACDS,8,2020-21,2020-21 NH/2020-21/6128,Playfields,Completed,NH-ANNA NAGAR,107,1100000,"SUPPLYING AND INSTALLATION OF INFRASTRUCTURE FACILITIES PROVIDING VERTICAL AND HORIZONTAL POLES WITH NYLON NETS AT Dr.AMBEDKAR PLAYGROUND IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2020-21,2020-21 NH/2020-21/6212,Buildings,Completed,NH-ANNA NAGAR,107,590000,"DEMOLITION AND RECONSTRUCTION OF COMPOUND WALL AT MAYOR SATHYAMOORTHY SALAI COMMUNITY HALL IN DIVISION-107, UNIT-23, ZONE-08.",Own Sources,8,2020-21,2021-22 NH/2020-21/9404,Buildings,Completed,NH-ANNA NAGAR,107,435000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL AT MS NAGAR IN DIVISION-107, UNIT-23, ZONE-8",Own Sources,8,2020-21,2021-22 Q/2020-21/1662,Buildings,Completed,Q-Solid Waste Management,107,1447000,"Construction of electrical panel room for Bio CNG processing facility at Central asphalt plant in Dn 107, Zone 8",Own Sources,8,2020-21,2020-21 Q/2020-21/1668,Buildings,Completed,Q-Solid Waste Management,107,4980000,"Proposed Construction of Compound wall (Bio CNG side)at CAP Bio CNG plant in Dn-107,Zone8",Own Sources,8,2020-21,2020-21 Q/2020-21/1682,Buildings,Completed,Q-Solid Waste Management,107,3840000,"Proposed construction of compound wall (garden waste side) at CAP Bio CNG Plant in Dn-107,Zone-8",Own Sources,8,2020-21,2020-21 NH/2020-21/10587,Buildings,Completed,NH-ANNA NAGAR,108,359000,"REPAIRS AND IMPROVEMENTS TO AMMA UNAVAGAM AT MGR 3rd STREET AND MMDA BUS DEPOT IN DIVISION-108, UNIT-22, ZONE-8",Own Sources,8,2020-21,2021-22 NH/2020-21/3600,Storm Water Drain,Completed,NH-ANNA NAGAR,108,689000,"DESILTING AND MINOR REPAIR WORKS TO STORM WATER DRAIN AT INTERIOR ROADS IN DIVISION -108, UNIT-22, ZONE 8",Own Sources,8,2020-21,2021-22 NH/2020-21/3793,Roads,Completed,NH-ANNA NAGAR,108,277000,"RESTORATION OF INTERIOR CEMENT CONCRETE ROAD CUT MADE BY CMWSSB AT J.D DURAIRAJ NAGAR 1ST STREET IN DIVISION-108, UNIT-22, ZONE-VIII",Deposit Works,8,2020-21,2020-21 NJ/2020-21/10603,Buildings,Completed,NJ-TEYNAMPET,109,233000,"IMPROVEMENTS TO EXISTING RATION SHOP BUILDING AT NAMACHIVAYAPURAM WEST IN DIVISION 109,UNIT 24,ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/2654,Buildings,Completed,NJ-TEYNAMPET,109,250000,REPAIRS AND IMPROVEMENTS TO SHREDDING MACHINE SHED AT DIVISION OFFICE 109 CAMPUS IN DIVISION 109 UNIT 24 ZONE 09,Own Sources,9,2020-21,2020-21 NJ/2020-21/3789,Buildings,Completed,NJ-TEYNAMPET,109,250000,"PROVIDING BORE WELL AND WATER SUPPLY ARRANGEMENTS TO DIVISION 109 OFFICE CAMPUS IN DIVISION 109,UNIT 24,ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/4042,Buildings,Completed,NJ-TEYNAMPET,109,655000,"DISMANTLING & RE-CONSTRUCTION OF DAMAGED COMPOUND WALL and OTHER IMPROVEMENT WORKS IN AMMA UNAVAGAM AT SHANMUGANAR SALAI IN DIVISION 109,UNIT 24,ZONE 09.",Own Sources,9,2020-21,2020-21 NJ/2020-21/4349,Buildings,Completed,NJ-TEYNAMPET,109,1700712,"REPAIRS AND IMPROVEMENTS TO ICDS CENTRE AND CONSTRUCTION OF ADDITIONAL SHED IN FIRST FLOOR AT UPHC CAMPUS PERIYAR NAGAR (SHERPUTHIN STREET) IN DIVISION 109,UNIT 24,ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/4887,Storm Water Drain,Completed,NJ-TEYNAMPET,109,687000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-109, UNIT-24, ZONE-09",Own Sources,9,2020-21,2020-21 BR/2020-21/0845,Roads,Completed,BR-Bus Route Roads,110,700000,Attending Emergency Patch work at Sterling Road and College Road in Zone IX,Own Sources,9,2020-21,2020-21 BR/2020-21/7862,Road Cut,Completed,BR-Bus Route Roads,110,980000,"Restoration of IRR Roadcut (OFC) at various street in Dn-110, Unit -24,Zone IX",Deposit Works,9,2020-21,2020-21 L/2020-21/9418,Electrical,Completed,L-Electrical,110,154400,"Electrification Work at Appasamy 6th Street Public Covenience div 110, Zone-IX.",Own Sources,9,2020-21,2020-21 NJ/2020-21/2346,Storm Water Drain,Completed,NJ-TEYNAMPET,110,2500000,Construction of storm water Drain of size 900x1200mm RCC Box type drain at Kodambakkam High Road Bridge North Side From Madhavan salai (0 to 70 metre) in Dn-110 unit-24 Zone-9.,MLACDS,9,2020-21,2021-22 NJ/2020-21/2889,Buildings,Completed,NJ-TEYNAMPET,110,2450000,"ADDITIONAL WORKS TO PROPOSED RENOVATION AND INSTALLATION OF MODULAR WORK STATION IN GROUND FLOOR ZONAL OFFICE-09, GREATER CHENNAI CORPORATION AT NUNGAMBAKKAM IN DIVISION-110,UNIT-24,ZONE-09",Own Sources,9,2020-21,2020-21 NJ/2020-21/6342,Storm Water Drain,Completed,NJ-TEYNAMPET,110,672000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-110, UNIT-24, ZONE-09",Own Sources,9,2020-21,2020-21 NJ/2020-21/9455,Buildings,Completed,NJ-TEYNAMPET,110,178000,"DISMANTLING AND RE-CONSTRUCTION OF COMPOUND WALL AT NUNGAMBAKKAM BURIAL GROUND IN DIVISION 110, UNIT 24, ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/9456,Buildings,Completed,NJ-TEYNAMPET,110,425000,"IMPROVEMENTS TO DISPENSARY OFFICE AT APPASAMY STREET IN DIVISION 110, UNIT 24,ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/9458,Buildings,Completed,NJ-TEYNAMPET,110,345000,"CONSTRUCTION OF TOILET ROOM AND REPAIRS TO AMMA UNAVAGAM AT KUTTY STREET IN DIVISION 110, UNIT 24, ZONE 09.",Own Sources,9,2020-21,2020-21 BR/2020-21/0382,Roads,Completed,BR-Bus Route Roads,111,182000,"Replacing the Information board on Overhead Gantry Board at Annasalai Near Spencer Plaza, Division -111, Zone-9",Own Sources,9,2020-21,2021-22 BR/2020-21/0392,Roads,Completed,BR-Bus Route Roads,111,2479000,"Restoration of Roadcut made by TANTRANSCO at Greams Road in Dn-111,Zone-9",Deposit Works,9,2020-21,2020-21 BR/2020-21/0847,Roads,Completed,BR-Bus Route Roads,111,875000,Attending Emergency Patch work at Nelson Manickam Road and Raja Muthaiah Salai in Zone IX,Own Sources,9,2020-21,2020-21 BR/2020-21/1161,Roads,Completed,BR-Bus Route Roads,111,330000,Attending Emergency Patch work at Mohan Kumaramangalam Street in Zone IX,Own Sources,9,2020-21,2020-21 BR/2020-21/1162,Roads,Completed,BR-Bus Route Roads,111,681000,Attending Emergency Patch work at Uthamar Gandhi Salai in Zone IX,Own Sources,9,2020-21,2020-21 BR/2020-21/9682,Road Cut,Completed,BR-Bus Route Roads,111,276000,"Restoration of OFC Roadcuts at Wallace Garden 2nd Street,Khadhar Nawaskhan Road & Pycrofts Road in Division 111,Unit 24,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/9684,Road Cut,Completed,BR-Bus Route Roads,111,64000,"Restoration of OFC Roadcuts at Avenue Road (Approach) in Division 111,Unit 24,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/9685,Road Cut,Completed,BR-Bus Route Roads,111,64000,"Restoration of OFC Roadcuts at Nungambakkam 4 th Lane in Division 111,Unit 24,Zone IX",Deposit Works,9,2020-21,2020-21 NJ/2020-21/13028,Buildings,Completed,NJ-TEYNAMPET,111,477000,"IMPROVEMENTS TO EXISTING BUILDING FOR DIVISION OFFICE AT DAMODARAN STREET IN DIV -111,UNIT -24,ZONE -9",Own Sources,9,2020-21,2021-22 NJ/2020-21/2657,Storm Water Drain,Completed,NJ-TEYNAMPET,111,500000,"REPAIRS AND IMPROVEMENTS TO GANESH STREET STORM WATER DRAIN AND IMPROVEMENTS SHREDDING MACHINE SHED AT SPENCERS PARK IN DIVISION 111,UNIT 24,ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/4913,Storm Water Drain,Completed,NJ-TEYNAMPET,111,706000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-111, UNIT-24, ZONE-09",Own Sources,9,2020-21,2021-22 BR/2020-21/9687,Road Cut,Completed,BR-Bus Route Roads,112,396000,"Restoration of OFC Roadcuts at Choolaimedu High Road,Sowrasthra Nagar 5 &6 th Street in Dn-112,Unit 26,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/9689,Road Cut,Completed,BR-Bus Route Roads,112,80000,"Restoration of OFC Roadcuts at Choolaimedu High Road in Dn-112,Unit 26,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/9690,Road Cut,Completed,BR-Bus Route Roads,112,47500,"Restoration of OFC Roadcuts at Kanniyappan Street in Dn-112,Unit 26,Zone IX",Deposit Works,9,2020-21,2020-21 NJ/2020-21/10881,Buildings,Completed,NJ-TEYNAMPET,112,493000,"IMPROVEMENTS TO EXISTING BUILDING FOR SANITARY INSPECTOR OFFICE AT PULIYUR 1ST MAIN ROAD IN DIV -112, UNIT -26, ZONE -9",Own Sources,9,2020-21,2021-22 NJ/2020-21/4848,Buildings,Completed,NJ-TEYNAMPET,112,359000,"PROPOSED DEMOLITION BUILDING OLD UNIT OFFICE AT VELLALAR STREET, DIV-112, UNIT-26, ZONE-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/9577,Buildings,Completed,NJ-TEYNAMPET,112,383000,"IMPROVEMENTS TO EXISTING DISPENSARY BUILDING AT PULIYUR 1ST MAIN ROAD IN DN 112,UNIT26,ZONE 9",Own Sources,9,2020-21,2021-22 BR/2020-21/9692,Road Cut,Completed,BR-Bus Route Roads,113,47500,"Restoration of OFC Roadcuts at Jeganathan Street in Dn-113,Unit 26,Zone IX",Deposit Works,9,2020-21,2020-21 NJ/2020-21/10641,Buildings,Completed,NJ-TEYNAMPET,113,352000,"IMPROVEMENTS TO E SEVA BUILDING AT DHARAMAPURAM 6TH STREET IN DIVISION 113,UNIT 26, ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/4755,Storm Water Drain,Completed,NJ-TEYNAMPET,113,696000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DN-113,UNIT-26,ZONE-09",Own Sources,9,2020-21,2020-21 NJ/2020-21/9648,Storm Water Drain,Completed,NJ-TEYNAMPET,113,1145000,Improvements to the existing storm water drain in Bala Muthukrishna street in Div-113 Unit-26 Zone-9,Own Sources,9,2020-21,2020-21 NJ/2020-21/9655,Storm Water Drain,Completed,NJ-TEYNAMPET,113,710000,"Providing road crossing using Hume pipe & repairs to existing SWD in Habibulla road, Shenoy road, Krishnabai Street & thirumullaipillar Road in Div 113 Unit 26 Zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/9832,Storm Water Drain,Completed,NJ-TEYNAMPET,113,198000,"REPAIRS TO STORM WATER DRAIN AT UTHAMAR GANDHI SALAI (NEAR GEMINI BRIDGE) IN DIVISION113, UNIT 26, ZONE 09",Own Sources,9,2020-21,2020-21 BR/2020-21/13649,Road Cut,Completed,BR-Bus Route Roads,114,845000,"Restoration of OFC Roadcut at lalbegam street,Wallaja Road ,Big Mosque street,Veeraraghavan Street,Typhoon Alikhan Street, Arunachalam Street and TH Road in Dn-114,U-27, Zone IX",Deposit Works,9,2020-21,2020-21 NJ/2020-21/11067,Buildings,Completed,NJ-TEYNAMPET,114,778000,"Improvements to existing dispensary building first floor at khanabagh street in dn-114,Unit -27,Zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/1135,Buildings,Completed,NJ-TEYNAMPET,114,1670000,"Construction of new toilet block with fencing around the PC for COVID care center at victoria hostel in dn-114,unit-27,zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/1699,Buildings,Completed,NJ-TEYNAMPET,114,1145000,"Providing Water, Drainage Arrangements And Fixing Fencing Sheet Around The Mobile Toilets (Presidency College) To Covid Care Centres At Victoria Hostel And Presidency College In Dn-114 ,U-27,Z-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/1701,Buildings,Completed,NJ-TEYNAMPET,114,1216000,"Providing Electrical Arrangements And Aluminium Partition To Covid Care Centres At Presidency College In Dn-114 ,U-27,Z-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/3546,Buildings,Completed,NJ-TEYNAMPET,114,442000,"Providing borewell, painting and Repairs work to amma unavagam at kasturiba gandhi hospital in dn -114,unit-27,zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/3899,Storm Water Drain,Completed,NJ-TEYNAMPET,114,699000,"Desilting of storm water drain and minor repair works at various interior roads and streets in Dn -114 , unit -27 , zone -9",Own Sources,9,2020-21,2020-21 NJ/2020-21/4108,Buildings,Completed,NJ-TEYNAMPET,114,627000,"Improvements to night shelter at lock nagar in dn-114, Unit-27,Zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/4637,Buildings,Completed,NJ-TEYNAMPET,114,359000,"Construction of compound wall around EB transformer at jn of Mayor chitibabu street and subathral street in Div-114,U-27,Z-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/7432,Storm Water Drain,Completed,NJ-TEYNAMPET,114,418000,"Providing rain water drain arrangements at kamarajar salai near traffic park in dn-114, unit-27,zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/7574,Storm Water Drain,Completed,NJ-TEYNAMPET,114,714000,"Providing rain water drain arrangements at Sydoji street Jn of bells road in dn-114,unit-27,zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/9547,Buildings,Completed,NJ-TEYNAMPET,114,367000,"Improvements to existing dispensary ground floor at khana bagh street in dn -114,unit-27,zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/10083,Footpath,Completed,NJ-TEYNAMPET,115,194000,"Repairs to footpath at west cott road and peters road in dn -115,Unit-27,Zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/9726,Buildings,Completed,NJ-TEYNAMPET,115,346000,"Improvements to Existing Division Office (part) at Devarajan street in dn-115,unit-27,zone-9",Own Sources,9,2020-21,2020-21 BR/2020-21/13648,Road Cut,Completed,BR-Bus Route Roads,116,130000,"Restoration of OFC Roadcut at Venkatarangam 2nd Street in Div-116,U-27,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/3389,Road Cut,Completed,BR-Bus Route Roads,116,327000,"Attending OFC cable Patch Work at Various Location in Div-116,Unit -27,Zone IX",Deposit Works,9,2020-21,2020-21 NJ/2020-21/12301,Buildings,Completed,NJ-TEYNAMPET,116,354000,"Improvements to the Ayurvedic Dispensary at Thanigachalam street in div-116, unit-27, zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/4172,Storm Water Drain,Completed,NJ-TEYNAMPET,116,692000,"Desilting and Minor Repair works to the storm water drain at interior Road in div-116, unit-27, zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/4646,Buildings,Completed,NJ-TEYNAMPET,116,495000,"Improvements For Health Post At Dr.Besant Road In div-116, Unit-27, Zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/9013,Parks,Completed,NJ-TEYNAMPET,116,389000,"IMPROVEMENTS TO THE ROAD SIDE (ANNIBESANT) PARK AT KAMARAJAR SALAI IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/9025,Buildings,Completed,NJ-TEYNAMPET,116,782000,"URGENT REPAIR WORKS TO THE AMMA UNAVAGAM (PHASE- II) AT VENGATRANGAM PILLAI STREET IN DIV-116, UNIT-27, ZONE-9.",Own Sources,9,2020-21,2020-21 BR/2020-21/1021,Road Cut,Completed,BR-Bus Route Roads,117,327000,"Restoration of Road cut made by OFC operator at various Road in Div-117,Unit 26, Zone 9",Deposit Works,9,2020-21,2020-21 BR/2020-21/5779,Roads,Completed,BR-Bus Route Roads,117,2157000,"Restoration of Roadcut done by TANGEDCO in B V Narasiman Road(From the Jn of TheagarayaRoad to Oriental Technologies Pvt Ltd.) in Dn-117,Zone 9",Deposit Works,9,2020-21,2021-22 BR/2020-21/5780,Road Cut,Completed,BR-Bus Route Roads,117,2255000,"Restoration of Roadcut done by TANGEDCO in B V Narasiman Road(from the Jn of Oriental Technologies to Jn of Vijaya Ragava Road) in Dn-117,Zone 9",Deposit Works,9,2020-21,2021-22 NJ/2020-21/10889,Buildings,Completed,NJ-TEYNAMPET,117,388000,"IMPROVEMENTS TO OLD DIVISION OFFICE BUILDING AT DR.SEVALIAR SIVAGIGANESAN SALAI IN DN 117,UNIT 26, ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/1386,Buildings,Completed,NJ-TEYNAMPET,117,423000,"Improvements to Public Convenience at Giriyappa road ( North ), in Div-117, Unit - 26, Zone - 9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/1425,Buildings,Completed,NJ-TEYNAMPET,117,218000,"Improvements to Public Convenience at Giriyappa road ( Drivers Colony ) in Div - 117 , Unit - 26, Zone - 9.",Own Sources,9,2020-21,2020-21 BR/2020-21/1325,Road Cut,Completed,BR-Bus Route Roads,118,565000,"Restoration of Roadcut by OFC Operators at various Street in Dn-118, Zone 9",Deposit Works,9,2020-21,2020-21 BR/2020-21/1592,Road Cut,Completed,BR-Bus Route Roads,118,360000,"Restoration of Roadcut by OFC Operators at various road in Dn-119,U-24,Zone 09",Deposit Works,9,2020-21,2020-21 BR/2020-21/3392,Road Cut,Completed,BR-Bus Route Roads,118,327000,"Attending OFC cable patch work at various location in Div-118,Unit -24,Zone IX",Deposit Works,9,2020-21,2020-21 L/2020-21/9420,Electrical,Completed,L-Electrical,118,158400,"Electrification Work at Thomaiyappan street Public Convenience (PC),Gopalapuram in div 118, Zone-IX.",Own Sources,9,2020-21,2020-21 NJ/2020-21/10842,Buildings,Completed,NJ-TEYNAMPET,118,840000,"Improvement works to Primary Health Centre at Muththiah Street in Division- 118, Unit-24,Zone-09.",Own Sources,9,2020-21,2020-21 NJ/2020-21/4491,Buildings,Completed,NJ-TEYNAMPET,118,659000,"Improvements to the public convenience at Thomaiappan in Dn-118, Unit-24, Zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/4917,Storm Water Drain,Completed,NJ-TEYNAMPET,118,686000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-118, UNIT-24, ZONE-09",Own Sources,9,2020-21,2021-22 BR/2020-21/2307,Road Cut,Completed,BR-Bus Route Roads,119,376000,"Restoration of Roadcut made by OFC operator at Various Road in Division-119,Unit-24,Zone 09",Deposit Works,9,2020-21,2020-21 NJ/2020-21/11037,Buildings,Completed,NJ-TEYNAMPET,119,372000,"Improvements to the Chennai Primary School at Saiva muthaiya 6th street in div-119, unit-24, zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/4901,Storm Water Drain,Completed,NJ-TEYNAMPET,119,698000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS IN DIVISION 119, UNIT - 24, ZONE-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/6499,Buildings,Completed,NJ-TEYNAMPET,119,267000,"PROVIDING NEW DRAINAGE CONNECTION AND OTHER IMPROVEMENT WORKS FOR CMS TOILET BLOCK AT BEGAM STREET IN DIV-119, UNIT-24, ZONE-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/8531,Buildings,Completed,NJ-TEYNAMPET,119,479000,"PROVIDING NEW BOREWELL AND WATER SUPPLY ARRANGEMENTS FOR UNIT-24 OFFICE AT CIT COLONY 6th CROSS STREET IN DIVISION-119, UNIT-24, ZONE-9.",Own Sources,9,2020-21,2020-21 BR/2020-21/2306,Road Cut,Completed,BR-Bus Route Roads,120,438000,"Restoration of Roadcut made by OFC operator at Various Road in Division-120&121,Unit-27,Zone 09",Deposit Works,9,2020-21,2020-21 NJ/2020-21/11180,Buildings,Completed,NJ-TEYNAMPET,120,378000,"Improvements to division office ground floor at gajapathy 1st street in dn-120 ,unit-27,zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/12187,Buildings,Completed,NJ-TEYNAMPET,120,2496000,"PROVIDING ARRANGEMENTS FOR CND WASTE COLLECTION CENTER AT LLOYDS COLONY IN DIV-120, UNIT-27, ZONE-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/4173,Storm Water Drain,Completed,NJ-TEYNAMPET,120,696000,"Desilting and Minor Repair works to the storm water drain at Interior Road in div-120, unit-27, zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/4859,Buildings,Completed,NJ-TEYNAMPET,120,1760000,"Dismantling and Replacement of GCS (Gas cleaning system, body bricks centrifugal fans (5HP), Gasifier & overall service work and Construction of New Chimney at Krishnampet Burial Ground in Division -120, Unit-27, Zone IX",Own Sources,9,2020-21,2021-22 NJ/2020-21/4863,Buildings,Completed,NJ-TEYNAMPET,120,765525,"Improvements to Existing Burial Ground Furnace Building at Krishnapet burial ground Campus in Division -120, Unit-27, Zone IX",Own Sources,9,2020-21,2021-22 NJ/2020-21/9079,Buildings,Completed,NJ-TEYNAMPET,120,1493000,"IMPROVEMENTS TO THE ITI CAMPUS AT LLOYDS COLONY IN DIV-120, UNIT-27, ZONE-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/9725,Buildings,Completed,NJ-TEYNAMPET,120,88000,"Demolished and Reconstruction the storm water Drain (part) at elephant tank 2nd street jn of Dr. besant road in Dn-120,Unit-27,Zone-9",Own Sources,9,2020-21,2020-21 L/2020-21/9097,Electrical,Completed,L-Electrical,121,276300,"Painting of 515 nos 8 mtr Octagonal street lamp post and 257 nos 2 mtr Lamp Postat Kamaraj salai Both side, Service Road, (from Napier bridge to Light House ) and Loop Road in view of Repulic day(2021)to Division-114,116,120,121,125 &126. in Zone-IX.",Own Sources,9,2020-21,2021-22 NJ/2020-21/10958,Buildings,Completed,NJ-TEYNAMPET,121,170000,"Improvements to the SI Office at Lloyds Road in div-121, unit-27, zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/2031,Buildings,Completed,NJ-TEYNAMPET,121,972000,"providing Electrical,Water and Drainage Arrangements to covid care centre (Gents and Ladies block) at Queen mary's college in Dn-121 , U-27,Z-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/2397,Roads,Completed,NJ-TEYNAMPET,121,1090000,"BLACK AND WHITE PAINTING FOR FOOTPATH KERB AT KAMARAJAR SALAI IN VIEW OF INDEPENDENCE DAY 2020 IN DIVISION - 114, 116, 120,121 AND 125,UNIT - 25 and 27, ZONE - 9",Own Sources,9,2020-21,2020-21 NJ/2020-21/5290,Buildings,Completed,NJ-TEYNAMPET,121,343000,"Demolition to the Health post at Royapettah High Road in div-121, unit-27, zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/7876,Buildings,Completed,NJ-TEYNAMPET,121,1764000,"PROVIDING SEATING AND ELECTRICAL ARRANGEMENTS FOR NAMMA CHENNAI BOARD WORK AT KAMARAJAR SALAI (LAWN No:11) IN DIV-121, UNIT-27A,ZONE-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/8367,Parks,Completed,NJ-TEYNAMPET,121,2055000,"PROVIDING FLOORING ARRANGEMENTS FOR NAMMA CHENNAI BOARD WORK AT KAMARAJAR SALAI (LAWN No:11) IN DIV-121, UNIT-27A,ZONE-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/9542,Buildings,Completed,NJ-TEYNAMPET,121,240000,"Improvements to the Dispensary at Lloyds Road in div-121, unit-27, zone-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/9680,Parks,Completed,NJ-TEYNAMPET,121,545000,"Repairs to the granite Planter box and Repolishing the stainless steel handrail around the Namma chennai Name board at Kamarajar salai in div-121, unit-27A, zone-9.",Own Sources,9,2020-21,2020-21 BR/2020-21/0301,Roads,Completed,BR-Bus Route Roads,122,370000,"Removing and Fixing of Bus Shelter at TTK Road towards Crown Plaza Hotel in Dn-122, unit -26,Zone-9",Deposit Works,9,2020-21,2020-21 BR/2020-21/10011,Road Cut,Completed,BR-Bus Route Roads,122,360413,"Restoration of OFC Roadcut at Krishna Avenue,Nandhanam extn 1 st,Nandhanam Main Road , Play Ground View St, Nandhanam main Road, Ratna Nagar Divison -122,Unit 25,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/2304,Road Cut,Completed,BR-Bus Route Roads,122,160000,"Restoration of Roadcut made by OFC operator at Various Road in Division-122,Unit-26,Zone 09",Deposit Works,9,2020-21,2020-21 NJ/2020-21/10534,Storm Water Drain,Completed,NJ-TEYNAMPET,122,509000,"IMPROVEMENTS TO STORM WATER DRAIN AT TURNBULLS ROAD 1ST CROSS STREET IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2020-21,2020-21 NJ/2020-21/10536,Storm Water Drain,Completed,NJ-TEYNAMPET,122,370000,"IMPROVEMENTS TO STORM WATER DRAIN AT CHITRANJAN ROAD IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2020-21,2020-21 NJ/2020-21/10549,Storm Water Drain,Completed,NJ-TEYNAMPET,122,351000,"IMPROVEMENTS TO STORM WATER DRAIN AT CENOTAPH 2ND LANE IN DN 122,UNIT 26 ZONE 9",Own Sources,9,2020-21,2020-21 NJ/2020-21/11001,Buildings,Completed,NJ-TEYNAMPET,122,578000,"IMPROVEMENTS TO UNIT 26 OFFICE AND J.E/E.B OFFICE AT ANNASALAI IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/2499,Buildings,Completed,NJ-TEYNAMPET,122,340533,"IMPROVEMENTS TO THE PULIC CONVENIENCE AT CENOTOPH ROAD 1ST LANE IN DN 122,UNIT 26,ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/2655,Buildings,Completed,NJ-TEYNAMPET,122,250000,"REPAIRS AND IMPROVEMENTS TO ALAYAMMAN KOVIL STREET PUBLIC CONVENIENCE & EB OFFICE IN DIVISION 122, UNIT 26,ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/2816,Buildings,Completed,NJ-TEYNAMPET,122,250000,"Improvements for Division office Building in div-122,unit-26,Zone-09",Own Sources,9,2020-21,2020-21 NJ/2020-21/4931,Storm Water Drain,Completed,NJ-TEYNAMPET,122,695000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-122, UNIT-26, ZONE-09",Own Sources,9,2020-21,2020-21 BR/2020-21/10572,Road Cut,Completed,BR-Bus Route Roads,123,206500,"Restoration of OFC Roadcut At Canal Bank Road,RA Puram 7 th Main Road ,Ra Puram 1 st Cross Street and RA Puram 4 th Main Road in Dn-123,Unit 25,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/10573,Road Cut,Completed,BR-Bus Route Roads,123,47000,"Restoration of OFC Roadcut At RA Puram 1 st Main Road in Divison 123,Unit 25 Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/12897,Road Cut,Completed,BR-Bus Route Roads,123,981469,"Restoration of OFC Roadcut at Anantha Street,Ashoka Street, Seethammal 1 st main Road Extn, Seethammal 2nd Main road Extn, Seethammal 1 st cross street extn,Seethammal 2nd cross street Extn, Seethammal 3rd cross street extn, Thiruvalluvar Street,Venkatraman Street,Kamarajar Street in Dn-123, Unit 25, Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/7954,Road Cut,Completed,BR-Bus Route Roads,123,949600,"Restoration of OFC Roadcut at Periyar Road ,Ramalinga Eswari Kovil Street, VOC street,Bharathiyar St,Bakthavachallam St,Seethammal road, Seethammal 1 st main road , Appadurai st,Seethammmal 1st and 2 nd Cross st,H D Raja St, R A Puram 1 st main Road in Division -123,Unit-25, Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/9170,Road Cut,Completed,BR-Bus Route Roads,123,630588,"Restroration of OFC roadcut at Raja Nayakkar St,Appa Durai St,Seethammal Colony,Thiruvalluvar Salai ,Abhirampuraram,Ananthapuram st,Krishna Avenue in Div-123,Unit -25,Zone IX",Deposit Works,9,2020-21,2020-21 NJ/2020-21/12977,Buildings,Completed,NJ-TEYNAMPET,123,368000,"IMPROVEMENTS TO MULTIPURPOSE HALL AT VENGATARAMAN STREET IN DN 123,UNIT 25,ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/12979,Buildings,Completed,NJ-TEYNAMPET,123,253000,"PROVIDING WATER SUPPLY,DRAINAGEAND ELECTRICAL ARRANGEMENTS TO MULTI PURPOSE HALL AT VENGATARAMAN STREET IN DN 123,UNIT 25,ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/6812,Buildings,Completed,NJ-TEYNAMPET,123,551000,"DEMOLITION OF SCHOOL BUILDING AT LUZ AVANUE 5th STREET IN DIV-123, UNIT-25, ZONE-9.",Own Sources,9,2020-21,2020-21 NJ/2020-21/8160,Storm Water Drain,Completed,NJ-TEYNAMPET,123,800000,"Demolition and Reconstruction of storm water drain at C.V.Raman road (From T.T.K Road to ananda road Junction) in dn-123,unit-25, zone-09.",Own Sources,9,2020-21,2021-22 NJ/2020-21/8169,Storm Water Drain,Completed,NJ-TEYNAMPET,123,632000,"Repairs and Improvements to Storm Water Drains at C.P.Ramasamy Road and Warren road Junction in division-123, unit-25, zone-9.",Own Sources,9,2020-21,2021-22 NJ/2020-21/9062,Storm Water Drain,Completed,NJ-TEYNAMPET,123,197000,"Repairs and Improvements to Storm Water Drain at R.A.Puram 1st Main Road and Junction of R.A.Puram 2nd Main Road and R.A.Puram 2nd Cross Street in dn-123, unit-25, zone-09.",Own Sources,9,2020-21,2021-22 NJ/2020-21/9466,Storm Water Drain,Completed,NJ-TEYNAMPET,123,923000,"Demolition and Reconstruction of storm water drain at C.V.Raman Road (Road Crossing (Ananda Road), Near door no 33/17 and Near door no 29/15) in dn-123, unit-25, zone-9.",Own Sources,9,2020-21,2021-22 BR/2020-21/10570,Road Cut,Completed,BR-Bus Route Roads,124,32500,"Restoration of OFC Roadcut At Chitirakulam East Street in Division 124,Unit 25,Zone IX",Deposit Works,9,2020-21,2020-21 D/2020-21/3837,Storm Water Drain,Completed,D-Storm Water Drains,124,2330000,"Construnction of Storm Water Infiltration Drain by German Techonology at Mosque Street in Div -124, Zone - IX",Own Sources,9,2020-21,2021-22 D/2020-21/3838,Storm Water Drain,Completed,D-Storm Water Drains,124,2474000,"Construnction of Storm Water Infiltration Drain by German Techonology at Chitrakulam west Street in Div -124, Zone - IX",Own Sources,9,2020-21,2021-22 NJ/2020-21/10169,Buildings,Completed,NJ-TEYNAMPET,124,365000,"IMPROVEMENTS TO DISPENSARY AND SANITARY INSPECTOR OFFICE AT MANDAIVELI MARKET ROAD IN DIVISION 124, UNIT 25, ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/10974,Buildings,Completed,NJ-TEYNAMPET,124,187000,"IMPROVEMENTS TO HOMEOPATHY HOSPITAL AT MANDAIVELI MARKET ROAD IN DIVISION 124, UNIT 25, ZONE 09",Own Sources,9,2020-21,2020-21 NJ/2020-21/2418,Storm Water Drain,Completed,NJ-TEYNAMPET,124,760000,"Desilting and repair to existing strom water drain at R.K MUTT ROAD in division 124 , unit -25 , zone-09",Own Sources,9,2020-21,2021-22 NJ/2020-21/2484,Storm Water Drain,Completed,NJ-TEYNAMPET,124,902760,"Desilting and repair to existing strom water drain at VENKATESH AGRAGARAM STREET in division 124 , unit -25 , zone-09",Own Sources,9,2020-21,2020-21 BR/2020-21/10574,Road Cut,Completed,BR-Bus Route Roads,125,166000,"Restoration of OFC Roadcut At Bazzar Road and PV Koil Street in Dn-125,Unit 25,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/10575,Road Cut,Completed,BR-Bus Route Roads,125,206500,"Restoration of OFC Roadcut At Chithrakulam North street ,East Mada Street and Nadu Street in Division 125 Unit 25,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/10576,Road Cut,Completed,BR-Bus Route Roads,125,158000,"Restoration of OFC Roadcut At Arundale Street, Bazaar Road and Paripoorna Vinayagar Koil Street in Dn-125,Unit 25,Zone IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/10577,Road Cut,Completed,BR-Bus Route Roads,125,16500,"Restoration of OFC Roadcut At East Mada Street in Div-125,Unit 25,Zone IX",Deposit Works,9,2020-21,2020-21 D/2020-21/8384,Storm Water Drain,Completed,D-Storm Water Drains,125,1720000,"Supplying and laying of 315mm HDPE pipe with inspection chamber at Chirthakullam North Street in Dn- 125,Zone - IX.",Grants,9,2020-21,2020-21 NJ/2020-21/2507,Roads,Completed,NJ-TEYNAMPET,125,345000,"BLACK AND WHITE PAINTING FOR FOOTPATH KERB AT SANTHOME HIGH ROAD IN VIEW OF INDEPENDENCE DAY 2020 IN DIVISION - 125 AND 126, UNIT - 25, ZONE - 9",Own Sources,9,2020-21,2020-21 NJ/2020-21/3448,Buildings,Completed,NJ-TEYNAMPET,125,639000,"PROPOSED DEMOLITION BUILDING NIGHT SHELTER AT DOOMING STREET IN DIV.NO.125, UNIT-25, ZONE-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/4890,Storm Water Drain,Completed,NJ-TEYNAMPET,125,694000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-125, UNIT-25, ZONE-09",Own Sources,9,2020-21,2021-22 NJ/2020-21/7434,Storm Water Drain,Completed,NJ-TEYNAMPET,125,846000,"Providing rain water drain arrangements at kamarajar salai near Light house in dn-125,Unit-25,zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/7441,Storm Water Drain,Completed,NJ-TEYNAMPET,125,760000,"Providing rain water harvesting at Syed Nadhi Mullah Street, Syed Wahab Hussain Street,Kailasapuram 5th street, Kamarajar Salai in Dn-125,Unit-25,Zone-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/8145,Roads,Completed,NJ-TEYNAMPET,125,420000,"PROVIDING AND FIXING NO PARKING NAME BOARD FOR VAROIUS STREETS IN DN-125,UNIT-25,ZONE-9",Own Sources,9,2020-21,2020-21 NJ/2020-21/9584,Buildings,Completed,NJ-TEYNAMPET,125,389000,"IMPROVEMENTS TO SANITARY INSPECTOR OFFICE AT DOOR NO 160.KUTCHERY ROAD IN DN 125,UNIT 25,ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/13495,Buildings,Completed,NJ-TEYNAMPET,126,365000,"MPROVEMENTS TO THE EXISTING OLD JUNIOR ENGINEER (ELECTRICAL) OFFICE BUILDING AT SANTHOME HIGH ROAD IN DN 126,UNIT 25,ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/13497,Buildings,Completed,NJ-TEYNAMPET,126,275000,"WEATHERING COURSE AND ELECTRICAL ARRANGEMENTS AT OLD JUNIOR ENGINEER (ELECTRICAL) OFFICE BUILDING SANTHOME HIGH ROAD IN DN 126,UNIT 25,ZONE 9",Own Sources,9,2020-21,2021-22 NJ/2020-21/4928,Storm Water Drain,Completed,NJ-TEYNAMPET,126,696000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-126, UNIT-25, ZONE-09",Own Sources,9,2020-21,2021-22 NJ/2020-21/5723,Buildings,Completed,NJ-TEYNAMPET,126,700000,"Supplying and Fixing of GYM Materials for GYM Building at Alphonsa ground south canal bank road in Division -126, Unit -25 Zone -9.(Under MLA Fund)",MLACDS,9,2020-21,2021-22 NJ/2020-21/8498,Roads,Completed,NJ-TEYNAMPET,126,255000,"REPAIRS AND DESILTING OF SANTHOME HIGH ROAD SWD IN DIVISION 126, UNIT 25, ZONE 09",Own Sources,9,2020-21,2021-22 NJ/2020-21/8846,Roads,Completed,NJ-TEYNAMPET,126,420000,"SUPPLYING AND FIXING OF CAUTION NAME BOARDS TO LOOP ROAD IN DIVISION 126, UNIT 25, ZONE 09",Own Sources,9,2020-21,2021-22 BR/2020-21/0851,Roads,Completed,BR-Bus Route Roads,127,855000,"Attending Emergency Patch work at Kalliamman Kovil Street, PV Rajamannar Salai, vannier Street, NSK Salaai and Duraisamy Salai in Div 127 and 128 ,Zone X",Own Sources,10,2020-21,2020-21 BR/2020-21/10571,Road Cut,Completed,BR-Bus Route Roads,127,158000,"Restoration of OFC Roadcut At Balakrishna Street,East Abhiramapuram 1 st and 2nd Street in Division 124,Unit 25,Zone IX",Deposit Works,10,2020-21,2020-21 BR/2020-21/10583,Roads,Completed,BR-Bus Route Roads,127,969000,PROVIDING RAIN WATER HARVESTING AT KALIYAMMAN KOIL STREET (VARIOUS LOCATIONS)IN dn127 ZONE 10,Own Sources,10,2020-21,2020-21 BR/2020-21/10590,Road Cut,Completed,BR-Bus Route Roads,127,790000,PROVIDING PAINTING TO THE EXISTING FOOT PATH KERB AND CENTRE MEDIAN IN KALIAMMAN KOVIL STREET AT DV127 ZONE 10,Own Sources,10,2020-21,2020-21 BR/2020-21/10591,Road Cut,Completed,BR-Bus Route Roads,127,847000,"PROVIDING WATER TABLE, THERMOPLATIC PAINTING AND ROAD FURNITURES IN KALIAMMANN KOVIL STREET DV127 ZONE 10",Own Sources,10,2020-21,2020-21 BR/2020-21/12780,Roads,Completed,BR-Bus Route Roads,127,900500,"Attending patch work at kaliamman koil street infront of jj hospital,Opp K-10 police station, jn of jawarhalal nehru road, opp KJR sweets,opp indian oil petrol pump, opp karan sound designer in div-127, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/12781,Roads,Completed,BR-Bus Route Roads,127,572000,"Attending patch work at kaliamman koil street near cotton zone, infront of natesan nagar 3rd main road, near koimbedu market,near sewage treatment plant in div-127, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/12782,Roads,Completed,BR-Bus Route Roads,127,458000,"Attending patch work at kaliamman koil street Infront of union school in div-127, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/12784,Roads,Completed,BR-Bus Route Roads,127,882000,"Attending patch work at Kaliamman koil street Opp CMBT bus depot 0-165m chainage in div-127, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/12785,Roads,Completed,BR-Bus Route Roads,127,590000,"Attending patch work at kaliamman koil street Opp CMBT bus depot 165-300m chainage in div-127, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/12791,Roads,Completed,BR-Bus Route Roads,127,992000,"Supplying and fixing solar studs, thermoplastic compound at kaliamman koil street in div-127, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/4023,Road Cut,Completed,BR-Bus Route Roads,127,1680000,"Restoration of Roadcut made by CMWSSB in Kaliamman Kovil Street in Dn-127, Zone-X",Deposit Works,10,2020-21,2020-21 BR/2020-21/8543,Roads,Completed,BR-Bus Route Roads,127,950000,"Attending Patch Work at KALIYAMMAN KOVIL STREET (From the jn of 3rd phase treatment plant gate to 2nd gate) in Div-127,Zone X",Own Sources,10,2020-21,2020-21 BR/2020-21/8595,Roads,Completed,BR-Bus Route Roads,127,965000,"Attending Patch Work at kaliamman kovil street(From the jn of CMWSSB Depot Office to jn of 3rd phase treatment plant 1st gate) in Div-127,Zone X",Own Sources,10,2020-21,2020-21 NK/2020-21/0707,Buildings,Completed,NK-KODAMBAKKAM,127,21500,"Providing Private Laboures for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at School street in Div-127, Unit-29, Zone-10 ( from 01.05.2020 to 31.05.2020) for (25 Days Only)",Own Sources,10,2020-21,2020-21 NK/2020-21/0708,Buildings,Completed,NK-KODAMBAKKAM,127,21500,"Providing Private Laboures for Sweeping and Toilet cleaning work at Chennai Primary School at School street in Div-127, Unit-29, Zone-10 ( from 01.05.2020 to 31.05.2020) for (25 Days Only)",Own Sources,10,2020-21,2020-21 NK/2020-21/0709,Buildings,Completed,NK-KODAMBAKKAM,127,21500,"Providing Private Laboures for Sweeping and Toilet cleaning work at Chennai Middle School at Arumbakkam in Div-127, Unit-29, Zone-10 ( from 01.05.2020 to 31.05.2020) for (25 Days Only)",Own Sources,10,2020-21,2020-21 NK/2020-21/1168,Roads,Completed,NK-KODAMBAKKAM,127,1240000,"Providing Rain Water Harvesting Structure using precast well ring size 1200 (outer dia) x 4500mm (Height) (300mm x 15 nos) x40mm (thk) using 1:1.5:3 concrete necessary earthwork excavation, filling with 20mm HBG metal out side peripheral of the well, providing of RCC frame and covered with RCC cover slab , cleaning the site and finishing etc., complete at Various Locations in Dn - 127, Unit - 29, Zone - 10.",Own Sources,10,2020-21,2020-21 NK/2020-21/13748,Roads,Completed,NK-KODAMBAKKAM,127,1780000,"Providing protecting mesh and repair work at SAFGV B14,B15 & A1,A2 Block Park in Dn127 U-29 Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/13751,Roads,Completed,NK-KODAMBAKKAM,127,2140000,"Providing protecting mesh and repair work at SAFGV C11 & C9,C10 Block Park in Dn127 U-29 Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/13752,Roads,Completed,NK-KODAMBAKKAM,127,1940000,Providing protecting mesh and repair work at SAFGV Reserve Bank Quarters & Indian oil Quarters Park in Dn127 U-29 Z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/13753,Roads,Completed,NK-KODAMBAKKAM,127,2360000,"Providing protecting mesh and repair work at SAFGV C8 & C7,C4 & C3 Block Park in Dn127 U-29 Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/13754,Roads,Completed,NK-KODAMBAKKAM,127,1760000,Painting of Kerb stones ( OSR 1 to 12) at SAF Games Village all park in Dn-127 U-29 z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/13755,Roads,Completed,NK-KODAMBAKKAM,127,2000000,"Providing protecting mesh and repair work at SAFGV B1,B2,B3,B4,B5,B6 Block Park in Dn127 U-29 Z-10",Own Sources,10,2020-21,2021-22 NK/2020-21/13757,Roads,Completed,NK-KODAMBAKKAM,127,798000,Improvement to Park at Ayyapa nagar in Dn-127 U-29 Z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/13758,Roads,Completed,NK-KODAMBAKKAM,127,1800000,Improvment to Nehru park at munuswamy street in Dn 127 U-29 Z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/1925,Roads,Completed,NK-KODAMBAKKAM,127,1570000,Providing and fixing stainless steel handrail road side area at West natesan nagar in Dn-127 U-29 Z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/2531,Footpath,Completed,NK-KODAMBAKKAM,127,490000,"Improvements and repairs to Anganwadi at T.S.D Nagar,Arumbakkam in Div-127, Unit-29, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/2532,Buildings,Completed,NK-KODAMBAKKAM,127,2410000,Improvement and repair work of CHSS at School street in DN-127 U-29 Z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/2587,Buildings,Completed,NK-KODAMBAKKAM,127,2490000,"Repair & Improvements works to the School Building for CPS at TSD Nagar in Div-127, U-29, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/2853,Buildings,Completed,NK-KODAMBAKKAM,127,820000,Improvement and repair work to public toilet at New colony PC and sivan koil street PC in Dn -127 U-29 Z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/3566,Roads,Completed,NK-KODAMBAKKAM,127,1700000,"Supplying and fixing of Ductile Iron grating silt catch pit (SWD) at west natesan nagar ,natesan nagar 2nd main road & natesan nagar 3rd main road in Dn-127 U-29 Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4231,Storm Water Drain,Completed,NK-KODAMBAKKAM,127,951000,"DESILTING AND MINOR REPAIR WORK AT SRINIVASAN NAGAR MAIN ROAD, SRINIVASAN NAGAR 2ND STREET, SEMATHAMMAN NAGAR 3RD SECTOR AND TSD NAGAR MAIN ROAD AND VARIOUS STREET IN DIV -127, UNIT-29, ZONE-10.",Own Sources,10,2020-21,2020-21 BR/2020-21/8541,Roads,Completed,BR-Bus Route Roads,128,490000,"Attending Patch Work at Arcot road (From Kamarajar salai to 80 feet road) and Traffic Improvement work at Kaliamman Koil Street in Div-128 and 129 ,Zone X",Own Sources,10,2020-21,2020-21 BR/2020-21/8596,Roads,Completed,BR-Bus Route Roads,128,817000,"Attending Patch Work at Kaliyamman Kovil street Near RTO office (North side) and from the jn of K10 police station to Seemathamman Nagar( south side) in Div-127,Zone X",Own Sources,10,2020-21,2020-21 BR/2020-21/8597,Roads,Completed,BR-Bus Route Roads,128,919000,"Attending Patch Work at kaliamman kovil street(From the jn of 100 feet road to CMWSSB Depot Office) in Div - 127,Zone X",Own Sources,10,2020-21,2020-21 D/2020-21/7912,Storm Water Drain,Completed,D-Storm Water Drains,128,2460000,"Demolition and Re-Construction of Storm Water Drain of Size 900x900 mm along Thiruvalluvar 3rd Street in Dn.128, Zone 10.",Grants,10,2020-21,2020-21 NK/2020-21/0585,Buildings,Completed,NK-KODAMBAKKAM,128,990000,"Providing Outsourcing Labour for Cleaning work and Security Arrangements for Temporary Quarantine Area (for COVID - 19) at Meenakshi Engineering College, Vembuliamman Koil Street in Division-128, Unit-29, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/0650,Buildings,Completed,NK-KODAMBAKKAM,128,43000,"Providing Private Labourers for sweeping and Toilet Cleaning work at Chennai Higher Secondary School, School Street, Virugambakkam in Division-128, Unit-29, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0651,Buildings,Completed,NK-KODAMBAKKAM,128,21500,"Providing Private Labourers for sweeping and Toilet Cleaning work at Chennai Primary School, School Street, Virugambakkam in Division-128, Unit-29, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0652,Buildings,Completed,NK-KODAMBAKKAM,128,43000,"Providing Private Labourers for sweeping and Toilet Cleaning work at Chennai Primary School, Pillaiar Koil Street, Nesapakkam in Division-128, Unit-29, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/10447,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,1232000,"Repairs and Improvements to the existing storm water drain at Annai Sathya nagar 3rd street in Division - 128 , Unit - 29 , Zone - X.",Own Sources,10,2020-21,2021-22 NK/2020-21/10448,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,1193000,"Repairs and Improvements to the existing storm water drain at Annai Sathya nagar 2nd street and 5th street in Division - 128 , Unit - 29 , Zone - X.",Own Sources,10,2020-21,2021-22 NK/2020-21/1934,Buildings,Completed,NK-KODAMBAKKAM,128,269000,"PROVIDING U.G CABLE TO ELECTRICAL CREMATORIUM AT VIRUGAMBAKKAM BURIYAL GROUND , THANGAL ERIKKARAI STREET IN DIV-128, UNIT - 29, ZONE - X.",Own Sources,10,2020-21,2020-21 NK/2020-21/3296,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,650000,"Improvements and Repairs to Storm Water Drain at Elango nagar Main Road in Dn - 128 , Unit -29, Zone - 10.",Own Sources,10,2020-21,2021-22 NK/2020-21/4222,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,1008000,"Desilting of Storm Water Drain and Minor repair works at Various Interior Roads and Streets in Div - 128 , Unit - 29, Zone - 10.",Own Sources,10,2020-21,2021-22 NK/2020-21/6808,Roads,Completed,NK-KODAMBAKKAM,128,218000,"Attending Cement Concrete patches at Various street in Division - 127 and 128 in Unit - 29 , Zone - X.",Own Sources,10,2020-21,2020-21 NK/2020-21/7599,Storm Water Drain,Completed,NK-KODAMBAKKAM,128,760000,"Construction of Rain Water Harvesting Structure at Various streets in Division-128 , Unit-29 , Zone - X.",Own Sources,10,2020-21,2020-21 NK/2020-21/0600,Buildings,Completed,NK-KODAMBAKKAM,129,990000,"Providing Outsourcing Labour for Cleaning work and Security Arrangements for Temporary Quarantine Area (for COVID - 19) at jawahar Engineering College, K.K salai, Kaveri Rangan Nagar in Division-129, Unit-29, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/10433,Buildings,Completed,NK-KODAMBAKKAM,129,430000,"Improvement work at E seva Service Center at Ponniamman Koil street in Div-129, Unit-29, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/2340,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,2470000,"Improvement to storm water drain at Nehru nagar main road in div-129, Unit-29, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/2494,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,470000,"Providing Pipe Line at Dhasarathapuram main road and Kaveri street in Div-129, Unit-29, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/4196,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,1022000,"DESILTING AND MINOR REPAIR WORK AT ARCOT ROAD(NORTH SIDE), ARUNACHALAM ROAD , SRI RAMULU STREET, V.O.C STREET M.A NAGAR AND VARIOUS STREET IN DIV -129, UNIT-29, ZONE-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/5414,Buildings,Completed,NK-KODAMBAKKAM,129,710000,"Improvements to the NNMP Shed at Mullai Street, Majith Nagar and Ponniyamman Koil Street in Div-129, U-29, Z-10",Own Sources,10,2020-21,2021-22 NK/2020-21/8598,Buildings,Completed,NK-KODAMBAKKAM,129,2450000,"Construction of storm water drain at Rathjinammal colony from Gandhi Nagar Anna St to Agathiyar st in div-129, Unit-29, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/8736,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,438000,"Construction of storm water drain at Anna street, Gandhi Nagar road crossing (From Gandhi Nagar Anna street to Rathinammal Colony) in div-129, Unit-29, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/9195,Storm Water Drain,Completed,NK-KODAMBAKKAM,129,677000,"Providing pipe line for Missing Link at Rajaji street to Virugambakkam canal in Division - 129, Unit - 29, Zone - 10.",Own Sources,10,2020-21,2020-21 D/2020-21/3841,Storm Water Drain,Completed,D-Storm Water Drains,130,2500000,"Construnction of Storm Water Infiltration Drain by German Techonology at Andavar Kovil Sreet in Div -130, Zone - X",Own Sources,10,2020-21,2021-22 D/2020-21/3844,Storm Water Drain,Completed,D-Storm Water Drains,130,2297800,"Construnction of Storm Water Infiltration Drain by German Techonology at North Mada Street in Div -130, Zone - X (100 feet Road to Alzagiri Nagar main road)",Own Sources,10,2020-21,2021-22 D/2020-21/3845,Storm Water Drain,Completed,D-Storm Water Drains,130,1068200,"Construnction of Storm Water Infiltration Drain by German Techonology at North Mada Street in Div -130, Zone - X ( Alzagiri Nagar to Vadapanani Temple Tank)",Grants,10,2020-21,2021-22 D/2020-21/5076,Storm Water Drain,Completed,D-Storm Water Drains,130,2500000,"Constrnction of storm water infiltration Drain by German Technology at Andavar Kovil street in Div -130, Zone-X ( From Arcot road Junction to Amman kovil street)",Own Sources,10,2020-21,2021-22 NK/2020-21/0647,Buildings,Completed,NK-KODAMBAKKAM,130,43000,"Providing Private Labourers for Sweeping and Toilet Cleaning work at Chennai Middle School, Amman Koil Street, Vadapalani in Division-130, Unit-29, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/2505,Buildings,Completed,NK-KODAMBAKKAM,130,2495000,Improvement and repair work of cms at amman koil street in DN-130 U-29 Z-10,Own Sources,10,2020-21,2020-21 NK/2020-21/4047,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,984000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-130, UNIT-29, ZONE-10",Own Sources,10,2020-21,2021-22 NK/2020-21/4157,Buildings,Completed,NK-KODAMBAKKAM,130,262000,"Construction of compound wall at Thiru Nagar 6th Street in Division - 130, Unit - 29, Zone - 10.",Own Sources,10,2020-21,2021-22 NK/2020-21/9178,Storm Water Drain,Completed,NK-KODAMBAKKAM,130,958000,"Construction of Storm Water Drain Missing Link at Kumaran Colony Main Road in Division - 130, Unit - 29, Zone - 10.",Own Sources,10,2020-21,2021-22 BR/2020-21/12788,Roads,Completed,BR-Bus Route Roads,131,688000,"Attending patch work at Kamarajar salai, P.T Rajan salai in div-131, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/3365,Roads,Completed,BR-Bus Route Roads,131,2238000,"Providing Centre Median and traffic improvements work at PV rajamannar Salai (From the jn of RK Shanmugam Salai to jn of Alagiri Swamy Salai in Dn-131 & 137, Zone-X",Own Sources,10,2020-21,2020-21 BR/2020-21/3410,Roads,Completed,BR-Bus Route Roads,131,1884000,"Providing Centre Median and traffic improvements work at PV rajamannar Salai (From the jn of Alagiriswamy Salai to jn of Ponnambalam Salai in Dn-131 & 137, Zone-X",Own Sources,10,2020-21,2020-21 D/2020-21/1505,Storm Water Drain,Completed,D-Storm Water Drains,131,13427000,"Construction of storm water drain of size 1200 x 1200mm at Anna Main Road in Dn- 131, Zone - X",Grants,10,2020-21,2021-22 NK/2020-21/10449,Buildings,Completed,NK-KODAMBAKKAM,131,371000,"Improvements works to the Multipurpose hall at 13th Sector 86th Street in Division-131,Unit-28,Zone-10.",Own Sources,10,2020-21,2021-22 NK/2020-21/2679,Buildings,Completed,NK-KODAMBAKKAM,131,495000,"Maintenance of corporation buildings, Roads, Public Conviennace , Gym Buildings & Health Buildings at Various Location in Division-131,Unit-28,Zone-10",Own Sources,10,2020-21,2021-22 NK/2020-21/3210,Buildings,Completed,NK-KODAMBAKKAM,131,1380000,"Construction of Multipurpose Hall B at Rani Anna Nagar Near in Div -131, Unit - 28, Zone -10 (Under MLA Fund )",MLACDS,10,2020-21,2020-21 NK/2020-21/3330,Buildings,Completed,NK-KODAMBAKKAM,131,1620000,"Construction of Multipurpose Hall A at Rani Anna Nagar Near in Div -131, Unit - 28, Zone -10 (Under MLA Fund )",MLACDS,10,2020-21,2020-21 BR/2020-21/14130,Road Cut,Completed,BR-Bus Route Roads,132,980000,"RESTORATION OF OFC ROAD CUT AT 81ST STREET, 82ND STREET, 91ST STREET, ASHOK NAGAR AND VARIOUS STREET IN DIVISION-132, UNIT-31, ZONE-10",Deposit Works,10,2020-21,2021-22 BR/2020-21/6130,Roads,Completed,BR-Bus Route Roads,132,7912000,"Relaying the road with DBM and BC after cold milling by paver finisher along with traffic improvement work at Ashok Nagar 12 th Avenue in Div-132, Zone X",Grants,10,2020-21,2021-22 NK/2020-21/0677,Buildings,Completed,NK-KODAMBAKKAM,132,21400,"Providing private labourers for sweeping and toilet cleaning work at Chennai High School at 83rd Street, Ashok Nagar, Kanniyappa Nagar in Div-132, U-31, Z-10 (01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0679,Buildings,Completed,NK-KODAMBAKKAM,132,10700,"Providing private labourers for sweeping and toilet cleaning work at Chennai Primary School at 83rd Street, Ashok Nagar, Kanniyappa Nagar in Div-132, U-31, Z-10 (01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0699,Buildings,Completed,NK-KODAMBAKKAM,132,42800,"Providing private labourers for sweeping and toilet cleaning work at Government Higher Secondary School, Pudur at 3rd Avenue, Ashok Nagar, in Div-132, U-31, Z-10 (01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0701,Buildings,Completed,NK-KODAMBAKKAM,132,42800,"Providing private labourers for sweeping and toilet cleaning work at Government Girls Higher Secondary School at 54th Street, Ashok Nagar, in Div-132, U-31, Z-10 (01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/13763,Footpath,Completed,NK-KODAMBAKKAM,132,1121000,"FORMING FOOTPATH FOR EAST, WEST AND SOUTH SIDE OF PLAYFIELD AT 47TH STREET PLAYGROUND, ASHOK NAGAR, IN DIV-132, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/2257,Electrical,Completed,NK-KODAMBAKKAM,132,1887000,"Replacement of 6mt post to 8mtr Lamp post with 160w - 200w FL LED fitting at 9th Avenue jun of 47th street Play Ground in div 132,Zone -10 area",Own Sources,10,2020-21,2021-22 NK/2020-21/3638,Playfields,Completed,NK-KODAMBAKKAM,132,700000,"Proposed Construction of Compound Wall at Somasundhara Bharathi Nagar 5th Street Playground in Div-132, U-31, Z-10 (Under T.Nagar Constituency MLA Fund 2019-2020)",MLACDS,10,2020-21,2020-21 NK/2020-21/4061,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,700000,"Desilting of Storm Water Drain and minor repair work at 3rd Avenue, 7th Avenue, S.V.Lingam Salai and other various streets in Div-132, U-31, Z-10",Own Sources,10,2020-21,2021-22 NK/2020-21/4492,Storm Water Drain,Completed,NK-KODAMBAKKAM,132,63000,"Improvements to the Storm water drain at 4th Avenue (Jn of 33rd Street) & 7th Avenue (Jn of Balakrishna Street Extension) and various streets in Div-132, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/8258,Roads,Completed,NK-KODAMBAKKAM,132,2255000,"Providing Interlocking Paverblocks at Bajanai Koil Street Lanes (1st Lane to 7th Lane), Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/8268,Roads,Completed,NK-KODAMBAKKAM,132,2410000,"Providing Interlocking Paverblocks at Bajanai Koil Street Lanes (8th Lane to 24th Lane), Ashok Nagar in Div-132, U-31, Z-10",Own Sources,10,2020-21,2020-21 BR/2020-21/1018,Road Cut,Completed,BR-Bus Route Roads,133,844000,"Attending OFC cable patch work at various location in Div-133,Unit-31 ,Zone X",Deposit Works,10,2020-21,2020-21 BR/2020-21/1019,Road Cut,Completed,BR-Bus Route Roads,133,137000,"Restoration of Road cut made by OFC operator at various Road in Div-133,Unit 31, Zone 10",Deposit Works,10,2020-21,2020-21 BR/2020-21/7712,Road Cut,Completed,BR-Bus Route Roads,133,991000,"Restoration of OFC Road cuts at Various streets in Dn-133,U-31,Zone X",Deposit Works,10,2020-21,2020-21 NK/2020-21/0691,Buildings,Completed,NK-KODAMBAKKAM,133,32100,"Providing private labourers for sweeping and toilet cleaning work at Chennai Higher Secondary School at NSK Salai, Puliyur, Kodambakkam in Div-133, U-31, Z-10 (01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0696,Buildings,Completed,NK-KODAMBAKKAM,133,10700,"Providing private labourers for sweeping and toilet cleaning work at Chennai Primary School at NSK Salai, Puliyur, Kodambakkam in Div-133, U-31, Z-10 (01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0697,Buildings,Completed,NK-KODAMBAKKAM,133,10700,"Providing private labourers for sweeping and toilet cleaning work at Chennai primary School at 15th street, Ashok Nagar, Mullai Nagar in Div-133, U-31, Z-10 (01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0856,Buildings,Completed,NK-KODAMBAKKAM,133,202000,Construction of Baby friendly toilet in Anganvadi at Ram colony (center number-387) in DIV 133 Unit 31 Zone 10,Own Sources,10,2020-21,2021-22 NK/2020-21/0857,Buildings,Completed,NK-KODAMBAKKAM,133,202000,Construction of Baby friendly toilet in Anganvadi at Ram colony (center number-389) in DIV 133 Unit 31 Zone 10,Own Sources,10,2020-21,2021-22 NK/2020-21/1681,Buildings,Completed,NK-KODAMBAKKAM,133,1980000,"Repair and Improvements to Toilets (all floors) and providin terrace tiles (Western side) to CHSS School, Puliyur, Kodambakkam at N.S.K Salai, Kodambakkam in Div-133, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4045,Storm Water Drain,Completed,NK-KODAMBAKKAM,133,608000,"DESILT OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-133, UNIT-31, ZONE-10",Own Sources,10,2020-21,2021-22 NK/2020-21/0539,Buildings,Completed,NK-KODAMBAKKAM,134,171000,"DISMANTLING THE EXISTING BLOCKED SEWER LINE AND PROVIDING NEW LINE FOR CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0682,Buildings,Completed,NK-KODAMBAKKAM,134,21400,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.05.2020 TO 31.05.2020) FOR CHENNAI PRIMARY SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0685,Buildings,Completed,NK-KODAMBAKKAM,134,21400,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.05.2020 TO 31.05.2020) FOR CHENNAI HIGH SCHOOL AT RANGARAJAPURAM MAIN ROAD IN DN-134,U-31,Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0686,Buildings,Completed,NK-KODAMBAKKAM,134,21400,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.05.2020 TO 31.05.2020) FOR GOVERNMENT HIGHER SECONDARY SCHOOL AT NSK SALAI IN DN-134,U-31,Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0687,Buildings,Completed,NK-KODAMBAKKAM,134,21400,"OUT SOURCING PRIVATE WORKERS FOR HOUSE KEEPING (01.05.2020 TO 31.05.2020) FOR CHENNAI MIDDLE SCHOOL AT KAMARAJAR COLONY IN DN-134, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/2522,Buildings,Completed,NK-KODAMBAKKAM,134,2089000,"REPAIR AND IMPROVEMENT WORKS TO THE EXISTING MATERNITY HOSPITAL AT NSK SALAI, KODAMBAKKAM IN DN-134, U-31,Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4027,Storm Water Drain,Completed,NK-KODAMBAKKAM,134,609000,"DESILTING TO THE EXISTING STORM WATER DRAIN, MINOR REPAIRS AND REPLACING THE DAMAGED MANHOLE DOORS AT VARIOUS STREETS IN DN-134, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4136,Electrical,Completed,NK-KODAMBAKKAM,134,762000,"Electrification work of Zonal office , Schools , NM Shed, EOC / Hospitals, , Amma Unavagam, Division office 130 & 134 and others COC Buildings in Zone - 10",Own Sources,10,2020-21,2021-22 NK/2020-21/4552,Buildings,Completed,NK-KODAMBAKKAM,134,2499000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL 1 & 2 AT KAMARAJAR COLONY 1ST STREET IN DN-134, U-31, Z-10",Own Sources,10,2020-21,2021-22 NK/2020-21/4565,Buildings,Completed,NK-KODAMBAKKAM,134,1129000,"PROVIDING BOREWELL, PLUMBING AND SEWER LINE FOR MULTIPURPOSE HALL AT KAMARAJAR COLONY 1ST STREET IN DN-134, U-31, Z-10",Own Sources,10,2020-21,2021-22 BR/2020-21/4025,Road Cut,Completed,BR-Bus Route Roads,135,557000,"Restoration of Roadcut made by CMWSSB in Arya Gowda Road in Dn-135 , Zone-X",Deposit Works,10,2020-21,2021-22 NK/2020-21/0668,Buildings,Completed,NK-KODAMBAKKAM,135,21400,"PROVIDING PRIVATE LABOURS FOR SWEEPING AND TOILET CLEANING WORK AT CHENNAI PRIMARY SCHOOL AT ESWARANKOIL STREET(01.05.2020 TO 31.05.2020) IN DIV-135, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/1397,Subway,Completed,NK-KODAMBAKKAM,135,338000,"PROVIDING ELECTRICAL CUM PLUMBER (DAY AND NIGHT) TO THE ESWARANKOVIL STREET MADLEY SUBWAY AND RANGARAJAPURAM TWO WHEELER SUBWAY FOR MONSOONS (SW&NE MONSOONS-2020) IN DIV-134 AND 135, UNIT-31, ZONE-10",Own Sources,10,2020-21,2021-22 NK/2020-21/1984,Roads,Completed,NK-KODAMBAKKAM,135,449000,"LAYING OF ROAD USING CC AT GANAPATHY STREET IN DIV-135, U-31,Z-10 (UNDER T.NAGAR MLA FUND)",MLACDS,10,2020-21,2020-21 NK/2020-21/4053,Storm Water Drain,Completed,NK-KODAMBAKKAM,135,558000,"DESILT OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-135, UNIT-31, ZONE-10",Own Sources,10,2020-21,2021-22 BR/2020-21/7612,Road Cut,Completed,BR-Bus Route Roads,136,800000,"Restoration of Road cut made by OFC Operators at Various Streets in Dn-136,U-30,Zone 10",Deposit Works,10,2020-21,2020-21 NK/2020-21/0681,Buildings,Completed,NK-KODAMBAKKAM,136,43000,"Providing Private Labours for Sweeping and Toilet cleaning work at Chennai Middle School at Prakasam Road in Division - 136, Unit - 30, Zone - X.(from (from 01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/1801,Buildings,Completed,NK-KODAMBAKKAM,136,1678000,"IMPROVEMENTS TO THE EXISTING WARD-136 OFFICE BUILDING AT MASILAMANI STREET IN DN 136,UNIT 30,ZONE 10",Own Sources,10,2020-21,2021-22 NK/2020-21/2181,Buildings,Completed,NK-KODAMBAKKAM,136,2500000,"Proposed Construction of Gym Building at Somasundaram Play Ground in Division-136, Unit -30, Zone - 10.(MLA FUND)",MLACDS,10,2020-21,2020-21 NK/2020-21/2190,Subway,Completed,NK-KODAMBAKKAM,136,2077000,"IMPROVEMENTS TO THE SUBWAY MOTOR ROOM BUILDING AND SUBWAY AT DURAISAMY ROAD IN DN 136,UNIT 30,ZONE 10",Own Sources,10,2020-21,2021-22 NK/2020-21/3356,Buildings,Completed,NK-KODAMBAKKAM,136,2044000,"IMPROVEMENTS TO THE DINING HALL AT P.T.THEYAGARAYA KALAIARANGAM G,N,CHETTY ROAD IN DN 136,UNIT 30.ZONE 10",Own Sources,10,2020-21,2020-21 NK/2020-21/3372,Buildings,Completed,NK-KODAMBAKKAM,136,1500000,"IMPROVEMENTS TO INSIDE OF AUDITORIUM FOR P.T. THEYAGARAYA KALAIARANGAM AT G.N.CHETTY ROAD IN DN 136,UNIT 30,ZONE 10",Own Sources,10,2020-21,2020-21 NK/2020-21/3514,Buildings,Completed,NK-KODAMBAKKAM,136,1500000,"IMPROVEMENTS TO THE OUTSIDE BUILDING OF P.T.THEYAGARAYA KALAIARANGAM AT G.N.CHETTY ROAD IN DN 136,UNIT 30,ZONE 10",Own Sources,10,2020-21,2020-21 NK/2020-21/4300,Storm Water Drain,Completed,NK-KODAMBAKKAM,136,908000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR STREETS IN DIV-136, UNIT-30, ZONE-10",Own Sources,10,2020-21,2021-22 NK/2020-21/8224,Buildings,Completed,NK-KODAMBAKKAM,136,660000,"PROVIDING ELECTRICAL ARRANGEMENTS TO THE GROUND FLOOR AND FIRST FLOOR OFFICE BUILDING( FOR THE OFFICE PURPOSE OF SRIPERAMBATHUR MEMBER OF PARLIMENT) AT BAZULLAH ROAD IN DN 136,UNIT 30,ZONE 10",Own Sources,10,2020-21,2021-22 NK/2020-21/9801,Buildings,Completed,NK-KODAMBAKKAM,136,827000,"CONVERTING OF SUBWAY MOTOR ROOM AND EXTENSION OF WAITING HALL BY ANGULAR TRUSS WITH GALVANIZED ZINC SHEET AT MAMBALAM HIGH ROAD IN DIVISION-136,UNIT-30,ZONE-10.",Own Sources,10,2020-21,2021-22 BR/2020-21/10658,Road Cut,Completed,BR-Bus Route Roads,137,685000,"Restoration of OFC Roadcut at Jeevanatham Street,Alagiri samy Salai ,Anna 4 th Street,Venkatraman Salai and Various street in Dn-137,U-28,Zone 10",Deposit Works,10,2020-21,2020-21 BR/2020-21/12786,Roads,Completed,BR-Bus Route Roads,137,657000,"Attending patch work at Munusamy salai infront of IDFC bank,opp to Pondichery guest house in div-137, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/12789,Roads,Completed,BR-Bus Route Roads,137,908000,"Attending patch work at Lakhmana sami salai,thiyagaraya road infront of naidu hall in div-136&137, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/1398,Road Cut,Completed,BR-Bus Route Roads,137,2000000,"Restoration of Roadcut made by CMWSSB at Nesapakkam Link Road in Dn-137, Zone-X",Deposit Works,10,2020-21,2021-22 BR/2020-21/1399,Road Cut,Completed,BR-Bus Route Roads,137,1916000,"Restoration of Roadcut made by CMWSSB at Erikarai Salai (From the jn of Nesapakkam Link Road to park) in Dn-137, Zone-X",Deposit Works,10,2020-21,2021-22 BR/2020-21/3413,Roads,Completed,BR-Bus Route Roads,137,2322000,"Providing Centre Median and traffic improvements work at PV rajamannar Salai (From the jn of Ponnamalam Salai to jn of Vannier Street) in Dn-137, Zone-X",Own Sources,10,2020-21,2020-21 BR/2020-21/3858,Road Cut,Completed,BR-Bus Route Roads,137,1724000,"Restoration of Roadcut made by CMWSSB at Erikarai Road from the jn of Corporation Park to MGR Statue in Dn-137, Zone-10",Deposit Works,10,2020-21,2021-22 BR/2020-21/7611,Road Cut,Completed,BR-Bus Route Roads,137,191000,"Restoration of Road cut made by OFC Operators at Various Streets in Div-137,U-28,Zone 10",Deposit Works,10,2020-21,2020-21 BR/2020-21/8547,Roads,Completed,BR-Bus Route Roads,137,774000,"Attending Patch Work at P.V Rajamannar Salai South Side (From the jn of Ponnambalam salai) in Div 137,Zone X",Own Sources,10,2020-21,2020-21 BR/2020-21/8568,Roads,Completed,BR-Bus Route Roads,137,600000,"Attending Patch Work at P.V Rajamannar Salai South Side (Infront of Thai Satya Matriculation School) in Div -137,Zone X",Own Sources,10,2020-21,2020-21 D/2020-21/1510,Storm Water Drain,Completed,D-Storm Water Drains,137,19392000,"Construction of storm water drain of size 1200 x 1200mm at Anna Main Road in Dn- 137, Zone - X",Grants,10,2020-21,2021-22 NK/2020-21/0671,Buildings,Completed,NK-KODAMBAKKAM,137,54000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School and Annexure building near play ground at Erikkarai Street in Division - 137, Unit - 28, Zone - X (01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0672,Buildings,Completed,NK-KODAMBAKKAM,137,54000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Kamaraj Street and Annexure building at Sankaralinganar Steet (15.7.2019 to 30.4.2020) in Division - 137, Unit - 28, Zone - X",Own Sources,10,2020-21,2020-21 NK/2020-21/0767,Buildings,Completed,NK-KODAMBAKKAM,137,137200,"Repair and maintenance works to 61st street playground, 64th street crematorium and unit office building etc.., at various streets in Div-137, U-28, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4226,Storm Water Drain,Completed,NK-KODAMBAKKAM,137,629000,"Desilting and Repairs to SWD at Ramasamy Salai, Arcot Road, Munusamy Salai and Various streets in division-137, Unit-28, Zone-10",Own Sources,10,2020-21,2021-22 NK/2020-21/7249,Buildings,Completed,NK-KODAMBAKKAM,137,685000,"Maintenance works to furnace bed and other repair works in burial ground at Erikkarai Street in Div-137, U-28, Z-10.",Own Sources,10,2020-21,2021-22 NK/2020-21/9534,Buildings,Completed,NK-KODAMBAKKAM,137,180000,"Improvement works to Division office building at 61st Street - 10th Sector in Div-137, U-28, Z-10.",Own Sources,10,2020-21,2021-22 NK/2020-21/9676,Buildings,Completed,NK-KODAMBAKKAM,137,360000,"Dismantling and Reconstruction of SWD at Munusamy Salai in division-137, Unit-28, Zone-10",Own Sources,10,2020-21,2021-22 BR/2020-21/1059,Roads,Completed,BR-Bus Route Roads,138,648000,"Attending Patch Work at Anna Main Road in Dn-138, Zone-10",Own Sources,10,2020-21,2020-21 BR/2020-21/10659,Road Cut,Completed,BR-Bus Route Roads,138,287000,"Restoration of Road cut made at Valluvar street,Pugazhenthi Street, Bharathiyar Street,Periyar Street and Various Streets in Dn-138,U-28,Zone 10",Deposit Works,10,2020-21,2020-21 BR/2020-21/13170,Road Cut,Completed,BR-Bus Route Roads,138,609000,"Restoration of OFC Roadcut made by cable operators at various interior roads in Dn-138,139,140 & 141,Unit -28 & 30 ,Zone X",Deposit Works,10,2020-21,2020-21 NK/2020-21/0069,Buildings,Completed,NK-KODAMBAKKAM,138,1900000,"Repair and Painting work for Ground Floor to the Chennai Higher Secondary School for block -I at M.G.R Nagar Govindasamy Street at Dn-138, Unit-28, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/0214,Buildings,Completed,NK-KODAMBAKKAM,138,353600,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Govindaswamy Street in Division - 138, Unit - 28, Zone - X (from 01.6.2020 to 30.4.2021)",Own Sources,10,2020-21,2021-22 NK/2020-21/0216,Buildings,Completed,NK-KODAMBAKKAM,138,471500,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at Govindasamy street, MGR Nagar in Division - 138, Unit - 28, Zone - X ( (01.6.2020 to 30.4.2021)",Own Sources,10,2020-21,2021-22 NK/2020-21/0218,Buildings,Completed,NK-KODAMBAKKAM,138,862100,"Providing Private Labourers for Sweeping and Toilet cleaning work at Govt. Higher Secondary School at Anna main road, MGR Nagar in Division - 138, Unit - 28, Zone - X (01.6.2020 to 30.4.2021)",Own Sources,10,2020-21,2021-22 NK/2020-21/0275,Buildings,Completed,NK-KODAMBAKKAM,138,2000000,"Repair and Painting works for Chennai Higher Secondary School (Block I and II) at M.G.R Nagar, Govindasamy Street at Dn-138, Unit-28, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0596,Buildings,Completed,NK-KODAMBAKKAM,138,1058000,"Construction of Yoga shed inside playground at Thiru Nagar VOC Street (MLA Fund) in Div- 138, U-28, Z-10",MLACDS,10,2020-21,2020-21 NK/2020-21/0692,Buildings,Completed,NK-KODAMBAKKAM,138,33000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Govindaswamy Street in Division - 138, Unit - 28, Zone - X (01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0693,Buildings,Completed,NK-KODAMBAKKAM,138,79000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Govt. Higher Secondary School at Anna main road, MGR Nagar in Division - 138, Unit - 28, Zone - X (01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0695,Buildings,Completed,NK-KODAMBAKKAM,138,43000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at Govindasamy street, MGR Nagar (01.5.2020 to 31.5.2020) in Division - 138, Unit - 28, Zone - X",Own Sources,10,2020-21,2020-21 NK/2020-21/0823,Buildings,Completed,NK-KODAMBAKKAM,138,1881000,"Improvements Works to the Chennai Higher seondary school B Block at M.G.R Nagar Govindasamy Street at Dn-138, Unit-28, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/1180,Buildings,Completed,NK-KODAMBAKKAM,138,2250000,"PROVIDING PAINTING AND COLOUR WASHING AND REPAIRS WORKS TO THE EXISTING CHENNAI PRIMARY SCHOOL AT GOVINDASAMY STREET,MGR NAGAR IN DN-138,UNIT-28,ZONE-10",Own Sources,10,2020-21,2020-21 NK/2020-21/1300,Buildings,Completed,NK-KODAMBAKKAM,138,583000,"Operation and Maintenance for 4th Year of High Quality Treated Drinking Water Plant (RO/UV Filtration) at Anna Main Road, 60' junction in Dn-138, Unit 28, Zone-10 (05.04.2020 to 31.8.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/2351,Buildings,Completed,NK-KODAMBAKKAM,138,970000,"Improvements to the 16 th day Ceremony building at Guru siva street,SM Block,Jafferkhanpet,Dn-138,Unit-28,Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/3381,Buildings,Completed,NK-KODAMBAKKAM,138,1898000,"REPAIR AND IMPROVEMENT WORKS TO THE CHENNAI PRIMARY SCHOOL AT GOVIDASAMY STREET IN DN-138, U-28, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/3403,Buildings,Completed,NK-KODAMBAKKAM,138,1100000,"PROVIDING GYM EQUIPMENTS TO THE EXISTING GYM BUILDING AT GOVINDASAMY STREET,UNDER MLACDS ,MGR NAGAR IN DN138,UNIT-28,ZONE-10",MLACDS,10,2020-21,2020-21 NK/2020-21/3553,Buildings,Completed,NK-KODAMBAKKAM,138,1550000,"PROPOSED CONSTRUCTION OF MULTIPURPOSE HALL AT GOVINDASAMY STREET (ADJACENT TO GYM BUILDING),M.G.R NAGAR UNDER MLA CDS FUND IN DN138,UNIT-28,ZONE-10.",MLACDS,10,2020-21,2020-21 NK/2020-21/4214,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,863000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-138, UNIT-28, ZONE-10",Own Sources,10,2020-21,2020-21 NK/2020-21/8564,Storm Water Drain,Completed,NK-KODAMBAKKAM,138,998800,"CONSTRUCTION OF STORM WATER DRAIN AT BHARATHIDASAN COLONY JN OF 60 FEET ROAD IN DN-138, U-28, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0179,Buildings,Completed,NK-KODAMBAKKAM,139,471500,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai High School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from (01.6.2020 to 30.4.2021)",Own Sources,10,2020-21,2021-22 NK/2020-21/0180,Buildings,Completed,NK-KODAMBAKKAM,139,235700,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from (01.6.2020 to 30.4.2021)",Own Sources,10,2020-21,2021-22 NK/2020-21/0181,Buildings,Completed,NK-KODAMBAKKAM,139,235700,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School Street in Division - 139, Unit - 28, Zone - X (01.6.2020 to 30.4.2021)",Own Sources,10,2020-21,2021-22 NK/2020-21/0389,Buildings,Completed,NK-KODAMBAKKAM,139,1171000,"Providing Borewell arrangements and Repairs works to the Community Hall at vadivelu Main Street in Division-139, Unit-28, Zone-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/0676,Buildings,Completed,NK-KODAMBAKKAM,139,43000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai High School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from (01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0678,Buildings,Completed,NK-KODAMBAKKAM,139,22000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Jafferkanpet in Division - 139, Unit - 28, Zone - X (from (01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0680,Buildings,Completed,NK-KODAMBAKKAM,139,22000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at School Street in Division - 139, Unit - 28, Zone - X (01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/4083,Buildings,Completed,NK-KODAMBAKKAM,139,1494000,"Providing Kitchen Shed and Flooring work in the Night Shelter at Periyar Ramaswamy Street in division -139, Unit-28, Zone-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4197,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,1030000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-131, UNIT-28, ZONE-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4357,Storm Water Drain,Completed,NK-KODAMBAKKAM,139,965000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR ROADS AND STREETS IN DIV-139, UNIT-28, ZONE-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0736,Buildings,Completed,NK-KODAMBAKKAM,140,43000,"Providing Private labourers for Sweeping and Toilet cleaning work at Chennai Higher Secondary School at KR Koil Street in Division - 140,Unit-30,Zone-X(from 01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0737,Buildings,Completed,NK-KODAMBAKKAM,140,43000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Perumal Koil Street in Division - 140, Unit-30, Zone-X",Own Sources,10,2020-21,2020-21 NK/2020-21/0738,Buildings,Completed,NK-KODAMBAKKAM,140,65000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Boys Higher Secondary School at Kodambakkam Road in Division - 140, Unit-30, Zone-X",Own Sources,10,2020-21,2020-21 NK/2020-21/0739,Buildings,Completed,NK-KODAMBAKKAM,140,22000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Vandikaran Koil Street in Division - 140, Unit-30, Zone-X(from 01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/1351,Buildings,Completed,NK-KODAMBAKKAM,140,977000,"IMPROVEMENTS TO CHENNAI MIDDLE SCHOOL C-BLOCK AT METTUPALAYAM IN DN-140,U-30,Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/1574,Buildings,Completed,NK-KODAMBAKKAM,140,579000,"IMPROVEMENTS TO DIVISION OFFICE AT KODAMBAKKAM ROAD IN DN-140,U-30,Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/2288,Buildings,Completed,NK-KODAMBAKKAM,140,950000,"PROVIDING WATER SUPPLY ARRANGEMENTS AND DISMANTLING RECONSTRUCTION OF COMPOUND WALL AT CMS SCHOOL VANDIKARAN STREET IN DN-140,U-30,Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4007,Buildings,Completed,NK-KODAMBAKKAM,140,500000,"CONSTRUCTION OF UNDER GROUND SUMP AT CHENNAI BOYS HIGHER SECONDARY SCHOOL KODAMBAKKAM ROAD SAIDAPET IN DN-140,U-30,Z-10",MLACDS,10,2020-21,2020-21 NK/2020-21/4235,Storm Water Drain,Completed,NK-KODAMBAKKAM,140,428000,"DESILTING AND MINOR REPAIR WORKS TO THE EXISTING STORM WATER DRAIN AT GOVINDAN ROAD AND VARIOUS STREET IN DN-140, U-30, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4754,Buildings,Completed,NK-KODAMBAKKAM,140,210000,"Improvements to Chennai primary School at Vandikaran Street in div-140 , U-30, Z-10",Own Sources,10,2020-21,2021-22 NK/2020-21/4851,Buildings,Completed,NK-KODAMBAKKAM,140,200000,"Improvements to community Hall at Panneer Selvam Nagar in DN-140, U-30, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0617,Buildings,Completed,NK-KODAMBAKKAM,141,973000,"IMPROVEMENT WORKS TO THE CHENNAI HIGH SCHOOL AT KANNAMMAPET IN DN-141, U-31, Z-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/0618,Buildings,Completed,NK-KODAMBAKKAM,141,481000,"IMPROVEMENT WORKS TO THE CHENNAI PRIMARY SCHOOL AT KANNAMMAPET IN DN-141, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/0683,Buildings,Completed,NK-KODAMBAKKAM,141,54000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai Higher Secondary School and Chennai Primary School at C.I.T Nagar 4th Main Road in Div -141, U-30, Z-10.(from 01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0684,Buildings,Completed,NK-KODAMBAKKAM,141,33000,"Providing Private Labourers Sweeping Toilet cleaning work at Chennai High School and Chennai Primary School at New Boag Road (Kannamapet) in Div -141, U30, Z-10.(from 01.05.2020 to 31.05.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0713,Buildings,Completed,NK-KODAMBAKKAM,141,550000,"Repair and painting to CHSS Building at CIT Nagar 4th main road in Dn-141, U-30, Z-X",Own Sources,10,2020-21,2020-21 NK/2020-21/1182,Buildings,Completed,NK-KODAMBAKKAM,141,1348000,"IMPROVEMENT WORKS TO THE CHENNAI HIGHER SECONDARY SCHOOL AT CIT NAGAR 4TH MAIN ROAD IN DN-141, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/1183,Buildings,Completed,NK-KODAMBAKKAM,141,487000,"IMPROVEMENT WORKS TO THE CHENNAI PRIMARY SCHOOL AT CIT NAGAR 4TH MAIN ROAD IN DN-141, U-31, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/1467,Buildings,Completed,NK-KODAMBAKKAM,141,657000,"Operation and Maintenance for 4th Year of high quality treated drinking water plant (RO/UV Filtration) at Muthurangan Salai, Kannammapettai in Div-141, U-30, Z-10 (From 01.03.2020 to 31.08.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/1794,Buildings,Completed,NK-KODAMBAKKAM,141,635000,"PAINTING AND IMPROVEMENT WORKS TO THE EXISTING DIVISION OFFICE BUILDING AT CIT NAGAR 4TH MAIN ROAD IN DN-141, U-30, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4239,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,798000,"DESILTING OF STORM WATER DRAIN AND MINOR REPAIR WORK AT VARIOUS INTERIOR STREETS IN DIV-141, UNIT-30, ZONE-10",Own Sources,10,2020-21,2020-21 NK/2020-21/4650,Buildings,Completed,NK-KODAMBAKKAM,141,883000,"REPAIRS AND IMPROVEMENTS WORK AT DOG SHELTER AT MUTHURANGAN SALAI IN DIV-141,UNIT-30,ZONE-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/4810,Buildings,Completed,NK-KODAMBAKKAM,141,404000,"CONSTRUCTION OF COMPOUND WALL FOR KANNAMMAPET HIGH SCHOOL AT NEW BOAG ROAD IN DN-141, U-30, Z-10",Own Sources,10,2020-21,2020-21 NK/2020-21/7125,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,1317000,"OPERATION AND MAINTENANCE OF HIGH QUALITY TREATED DRINKING WATER PLANT (AMMA KUDINEER) AT CIT NAGAR 4TH MAIN ROAD (12MONTHS) IN DN-141,U-30,Z-10.",Own Sources,10,2020-21,2021-22 NK/2020-21/9123,Storm Water Drain,Completed,NK-KODAMBAKKAM,141,833000,"PROPOSED FOR NEW STORM WATER DRAIN LINK AT SOUTH WEST BOAG ROAD IN DIV-141,UNIT-30,ZONE-10.",Own Sources,10,2020-21,2020-21 BR/2020-21/10353,Road Cut,Completed,BR-Bus Route Roads,142,686000,"Roadcut Restoration work to the interiors roads(Roadcut made by Reliance Jio and ACT for OFC cable ) at various streets in division -142 ,U-30,Zone 10",Deposit Works,10,2020-21,2020-21 NK/2020-21/0673,Buildings,Completed,NK-KODAMBAKKAM,142,65000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Girl's Higher Secondary School at West Jones Road in Division-142, Unit-30, Zone -10 (from 01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0674,Buildings,Completed,NK-KODAMBAKKAM,142,33000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Middle School at Thideer Nagar in Division-142, Unit-30, Zone -10 (from 01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0675,Buildings,Completed,NK-KODAMBAKKAM,142,22000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at Bazaar Road in Division-142, Unit-30, Zone -10 (from 01.5.2020 to 31.5.2020)",Own Sources,10,2020-21,2020-21 NK/2020-21/0694,Buildings,Completed,NK-KODAMBAKKAM,142,32000,"Providing Private Labourers for Sweeping and Toilet cleaning work at Chennai Primary School at West Jones Road (1 Months) in Division-142, Unit-30, Zone -10",Own Sources,10,2020-21,2020-21 NK/2020-21/2114,Buildings,Completed,NK-KODAMBAKKAM,142,509000,"PROVIDING ELECTRICAL CUM PLUMBER (DAY AND NIGHT) TO THE ALANDUR ROAD SUBWAY WEST JONES ROAD C.P.PAVALAVANNAN SUBWAY AND DURAISAMY ROAD SUBWAY IN DIVISION-142 AND DIVISION-136, UNIT-30,ZONE-10.",Own Sources,10,2020-21,2020-21 NK/2020-21/2785,Buildings,Completed,NK-KODAMBAKKAM,142,1098000,"PAINTING EXTERIOR, INTERIOR AND REPAIR WORK FOR BLOCK A AT CGHSS CAMPUS ,WEST JONES ROAD SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2020-21,2021-22 NK/2020-21/2787,Buildings,Completed,NK-KODAMBAKKAM,142,500000,"PAINTING EXTERIOR, INTERIOR AND REPAIR WORK FOR( C BLOCK AND TOILET BLOCK ) AT CGHSS CAMPUS ,WEST JONES ROAD SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2020-21,2021-22 NK/2020-21/3798,Buildings,Completed,NK-KODAMBAKKAM,142,1000000,"CONSTRUCTION OF OPEN AUDITORIUM AT CHENNAI PRIMARY SCHOOL,BAZAAR ROAD SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10.(UNDER 2020-2021 SAIDAPET MLA FUND)",MLACDS,10,2020-21,2021-22 NK/2020-21/3803,Buildings,Completed,NK-KODAMBAKKAM,142,500000,"CONSTRUCTION OF UNDER GROUND SUMP AT CHENNAI PRIMARY SCHOOL ,WEST JONES ROAD,SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10.(UNDER 2020-2021 SAIDAPET MLA FUND)",MLACDS,10,2020-21,2020-21 NK/2020-21/3804,Buildings,Completed,NK-KODAMBAKKAM,142,500000,"CONSTRUCTION OF UNDER GROUND SUMP AT CHENNAI GIRLS HIGHER SECONDARY SCHOOL ,WEST JONES ROAD,SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10.(SAIDAPET MLA FUND 2020-2021)",MLACDS,10,2020-21,2020-21 NK/2020-21/3805,Buildings,Completed,NK-KODAMBAKKAM,142,530000,"DESILTIONG OF STORM WATER DRAIN AT VARIOUS STREETS, SAIDAPET IN DIVISION-142, UNIT-30, ZONE-10.",Own Sources,10,2020-21,2021-22 NK/2020-21/9609,Buildings,Completed,NK-KODAMBAKKAM,142,990000,"IMPROVEMENT OF AMMA UNAVAGAM AT ABDUL RAZAK STREET ,GODHAMEDU, SAIDAPET IN DIVISION-142,UNIT-30,ZONE-10.",Own Sources,10,2020-21,2021-22 BR/2020-21/0836,Road Cut,Completed,BR-Bus Route Roads,143,942000,Restoration for road cut made by OFC Providers at various interior roads in Dn-143. Zone XI,Deposit Works,11,2020-21,2020-21 BR/2020-21/0838,Road Cut,Completed,BR-Bus Route Roads,143,975000,"Restoration for road cut made by OFC Providers at various interior roads in Dn-143,147,149 &150. Zone XI",Deposit Works,11,2020-21,2020-21 BR/2020-21/3832,Road Cut,Completed,BR-Bus Route Roads,143,926000,"Restoration of Road cut made by OFC Operators at Various interior Roads In Dn.143 &144, Zone 11",Deposit Works,11,2020-21,2020-21 BR/2020-21/3903,Road Cut,Completed,BR-Bus Route Roads,143,926000,"Restoration of Road cut made by OFC Operators at Various interior Roads In Dn.143 ,Zone 11",Deposit Works,11,2020-21,2020-21 L/2020-21/2680,Electrical,Completed,L-Electrical,143,708400,"Construction of cement concrete pedestial for 1283 Nos of 6/7 Mtr Lamp post with ppedestial white washing at various locations in Zone XI in Divisions 143,144,145,146,148,150,151,153,154 and 155.",Own Sources,11,2020-21,2020-21 NL/2020-21/2899,Roads,Completed,NL-VALASARAVAKKAM,143,315000,"Forming interior Bt Road at Nolambur Phase-2, 2nd Main Road Extension in Div-143, Un-32, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/2900,Roads,Completed,NL-VALASARAVAKKAM,143,280000,"Relaying interior Bt Road at MCK Layout 2nd main road in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2901,Roads,Completed,NL-VALASARAVAKKAM,143,499000,"Relaying interior Bt Road at Annamalai avenue Chanakiya 1st cross street in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2902,Roads,Completed,NL-VALASARAVAKKAM,143,484000,"Relaying interior Bt Road at Annamali Avenue Chanakiya 2nd cross street in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2903,Roads,Completed,NL-VALASARAVAKKAM,143,519000,"Relaying interior Bt Road at Annamali Avenue Chanakiya 3rd cross street in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2910,Roads,Completed,NL-VALASARAVAKKAM,143,3116000,"Relaying interior Bt Road at Pada salai street in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2911,Roads,Completed,NL-VALASARAVAKKAM,143,2969000,"Widening and Relaying interior Bt Road at Union road in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2912,Roads,Completed,NL-VALASARAVAKKAM,143,1184000,"Relaying interior Bt Road at Sakthi nagar 2nd avenue in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2913,Roads,Completed,NL-VALASARAVAKKAM,143,1578000,"Relaying interior Bt Road at Sakthi nagar main road in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2914,Roads,Completed,NL-VALASARAVAKKAM,143,3068000,"Relaying interior Bt Road at Sriram nagar main road in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2915,Roads,Completed,NL-VALASARAVAKKAM,143,409000,"Relaying interior Bt Road at MCK Layout 2nd main road in Div-143, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 NL/2020-21/2933,Roads,Completed,NL-VALASARAVAKKAM,143,1117000,"Forming tha Cement concrete road at perumal koil 1st cross street in Div-143,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2934,Roads,Completed,NL-VALASARAVAKKAM,143,1038000,"Forming tha Cement concrete road at Perumal koil 2nd cross street in Div-143,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2935,Roads,Completed,NL-VALASARAVAKKAM,143,1116000,"Forming tha Cement concrete road at VGN nagar Phase-3, 1st cross extension in Div-143,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2936,Roads,Completed,NL-VALASARAVAKKAM,143,561000,"Forming tha Cement concrete road at VGN nagar Phase-3, 1st cross 1st lane in Div-143,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2937,Roads,Completed,NL-VALASARAVAKKAM,143,282000,"Forming tha Cement concrete road at VGN nagar Phase-3, 1st cross 2nd lane in Div-143,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2939,Roads,Completed,NL-VALASARAVAKKAM,143,295000,"Forming tha Cement concrete road at Vellaler Pradhana Salai 2nd Lane street in Div-143,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/4048,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,382000,"Desilting Of SWD at Various Streets in Division-143 Unit-32,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/4049,Storm Water Drain,Completed,NL-VALASARAVAKKAM,143,465000,"Minor repairs and Maintenance to SWD at various Streets in Division-143, Unit -32 , Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/4399,Parks,Completed,NL-VALASARAVAKKAM,143,364000,"Providing water supply facility in (Miyawaki Forest) S&P Garden OSR land at S&P Garden 2nd cross street in Dn-143, Unit-32, Zone-XI",Own Sources,11,2020-21,2021-22 BR/2020-21/3901,Road Cut,Completed,BR-Bus Route Roads,144,910000,"Restoration of Road cut made by OFC Operators at Various interior Roads In Dn.144,145 &147 ,Zone 11",Deposit Works,11,2020-21,2020-21 NL/2020-21/2981,Parks,Completed,NL-VALASARAVAKKAM,144,232000,"Annual Maintenance of VGP Amudha nagar park (One year) in Dn -144. Unit-32, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/3021,Roads,Completed,NL-VALASARAVAKKAM,144,1088000,"Relaying interior BT road at Kamatchi Nagar 2nd main road in Div-144,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/3039,Roads,Completed,NL-VALASARAVAKKAM,144,495000,"Relaying interior BT road at Abirami Nagar 7th Street in Div-144,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/3040,Roads,Completed,NL-VALASARAVAKKAM,144,479000,"Relaying interior BT road at Abirami Nagar 8th Street in Div-144,Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/3041,Roads,Completed,NL-VALASARAVAKKAM,144,752000,"Relaying Cement Concrete road at Kanniappa mudali street in DN-144, Unit-32. Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/3047,Roads,Completed,NL-VALASARAVAKKAM,144,1779000,"Relaying Cement Concrete road at Bharathiyar street in DN-144, Unit-32. Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/4050,Roads,Completed,NL-VALASARAVAKKAM,144,458000,"Desilting of Storm water drain and side drain at Various Streets in Dn-144, Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/4051,Roads,Completed,NL-VALASARAVAKKAM,144,342000,"Minor Repair and Maintenance to SWD at various streets in Division-144. Unit-32, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/1716,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,443000,"Desilting of SWD and Side Drains at Various Streets in Dn - 145,Unit - 33,Zone -11",Own Sources,11,2020-21,2021-22 NL/2020-21/1729,Storm Water Drain,Completed,NL-VALASARAVAKKAM,145,602000,"Minor Repair Works to Side Drain and Strom Water Drain at Various Streets in Div - 145,Unit - 33,Zone 11",Own Sources,11,2020-21,2020-21 NL/2020-21/3052,Roads,Completed,NL-VALASARAVAKKAM,146,367000,"Relaying tha Cement concrete road at Jeeva street ( lakshmi nagar) in Dn -146, U - 32, Z - XI.",Own Sources,11,2020-21,2020-21 NL/2020-21/3053,Roads,Completed,NL-VALASARAVAKKAM,146,193000,"Forming tha Cement concrete road at Sri Lakshmi Nagar 12th Cross Street in Div-146, U-32, Z - XI.",Own Sources,11,2020-21,2020-21 NL/2020-21/3054,Roads,Completed,NL-VALASARAVAKKAM,146,1442000,"Forming tha Cement concrete road at Metro Nagar 7th Cross Street in Dn-146, U- 32, Z - XI.",Own Sources,11,2020-21,2020-21 NL/2020-21/4623,Roads,Completed,NL-VALASARAVAKKAM,146,378000,"Relaying interior Bt Road at Iyappan Nagar 6th Cross street in Div-146, Un-32, Zone-11 .",Own Sources,11,2020-21,2020-21 BR/2020-21/3831,Road Cut,Completed,BR-Bus Route Roads,147,910000,"Restoration of Road cut made by OFC Operators at Various interior roads in Dn-147 &148,Zone 11",Deposit Works,11,2020-21,2020-21 NL/2020-21/2534,Roads,Completed,NL-VALASARAVAKKAM,147,713000,"Improvements to Interior BT Road at Pump Room Pattai in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2020-21 NL/2020-21/2536,Roads,Completed,NL-VALASARAVAKKAM,147,329000,"Forming of Interior BT Road at Astalakshmi Nagar 23rd Street Extension in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2538,Roads,Completed,NL-VALASARAVAKKAM,147,467000,"Improvements to Interior BT Road at Sri Devi Nagar 1st Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2020-21 NL/2020-21/2539,Roads,Completed,NL-VALASARAVAKKAM,147,580000,"Improvements to Interior BT Road at Krishnamachari Nagar 3rd Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2540,Roads,Completed,NL-VALASARAVAKKAM,147,557000,"Improvements to Interior BT Road at Baghyalakshmi Nagar 3rd Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2541,Roads,Completed,NL-VALASARAVAKKAM,147,585000,"Improvements to Interior BT Road at D.S. Nagar 1st Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2542,Roads,Completed,NL-VALASARAVAKKAM,147,1165000,"Forming of Interior BT Road at Sri Devi Seemathamman Nagar Cross Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2543,Roads,Completed,NL-VALASARAVAKKAM,147,384000,"Improvements to Interior BT Road at Janaki Nagar Main Road in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2544,Roads,Completed,NL-VALASARAVAKKAM,147,720000,"Improvements to Interior BT Road at Kandasamy Nagar 8th Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2020-21 NL/2020-21/2545,Roads,Completed,NL-VALASARAVAKKAM,147,377000,"Improvements to Interior BT Road at Kandasamy Nagar 6th Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2546,Roads,Completed,NL-VALASARAVAKKAM,147,251000,"Forming of Interior BT Road at Kandasamy Nagar 3rd Cross Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2548,Roads,Completed,NL-VALASARAVAKKAM,147,668000,"Improvements to Interior BT Road at Kandasamy Nagar 1st Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2549,Roads,Completed,NL-VALASARAVAKKAM,147,689000,"Improvements to Interior BT Road at Astalakshmi nagar 1st Main Road in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2550,Roads,Completed,NL-VALASARAVAKKAM,147,490000,"Improvements to Interior BT Road at Sridevi Nagar 5th Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2551,Roads,Completed,NL-VALASARAVAKKAM,147,268000,"Improvements to Interior BT Road at Omsakthi Nagar 1st Street in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/2552,Roads,Completed,NL-VALASARAVAKKAM,147,694000,"Improvements to Interior BT Road at Srikrishna Nagar Annex in Dn - 147, U - 32, Z - XI.",Loans And Grants,11,2020-21,2021-22 NL/2020-21/4064,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,682000,"DESILTING OF STORM WATER DRAINS AND SIDE DRAINS AT VARIOUS STREETS IN DIV-147, U-32, Z-XI",Own Sources,11,2020-21,2020-21 NL/2020-21/4066,Storm Water Drain,Completed,NL-VALASARAVAKKAM,147,318000,"MINOR REPAIR WORKS AT VARIOUS STREETS IN DIV-147, U-32,ZONE-XI",Own Sources,11,2020-21,2020-21 NL/2020-21/8132,Roads,Completed,NL-VALASARAVAKKAM,147,406000,"Improvements to interior CC road at Nagendran Street in Div-147,U-32,Z-XI.",Own Sources,11,2020-21,2020-21 NL/2020-21/8144,Roads,Completed,NL-VALASARAVAKKAM,147,649000,"Improvements to Interior CC Road at Janaki Nagar 4th Cross street in Div-147,U-32,Z-XI",Own Sources,11,2020-21,2020-21 NL/2020-21/1580,Parks,Completed,NL-VALASARAVAKKAM,148,996000,"Improvement works to TAISHA Park in Dn - 148, U - 33, Z - XI.",Own Sources,11,2020-21,2020-21 NL/2020-21/4902,Parks,Completed,NL-VALASARAVAKKAM,148,923000,"Improvement to Footpath on out side of the park and repair to indoor stadium situated inside the TAISHA park in DN-148,U-33, Z-XI.",Own Sources,11,2020-21,2021-22 NL/2020-21/4904,Roads,Completed,NL-VALASARAVAKKAM,148,400000,"Providing SS barriers to avoid unauthorized parking in front of AIS Quartets in DN-148,U-33, Z-XI.",Own Sources,11,2020-21,2021-22 BR/2020-21/1209,Road Cut,Completed,BR-Bus Route Roads,149,1907000,"Restoration of Roadcut at Radha Avenue Road from jn of Sri Lakshmi Nagar 3rd Main Road to Anbu Nagar 11th Street by CMWSSB Div - 149, Zone - 11",Deposit Works,11,2020-21,2020-21 BR/2020-21/1212,Road Cut,Completed,BR-Bus Route Roads,149,1604000,"Restoration of Roadcut at Radha Avenue Road from jn of Anbu Nagar 11th Street to Velan Nagar Main Road by CMWSSB Div - 149, Zone - 11",Deposit Works,11,2020-21,2020-21 BR/2020-21/1214,Road Cut,Completed,BR-Bus Route Roads,149,2407000,"Restoration of Roadcut at Sri Devi Kuppam Main Road from jn of Arcot Road to Putthu Koil by CMWSSB Div - 149, Zone - 11",Deposit Works,11,2020-21,2020-21 BR/2020-21/1217,Road Cut,Completed,BR-Bus Route Roads,149,2362000,"Restoration of Roadcut at Sri Devi Kuppam Main Road from jn of Putthu Koil to Clear Vision Opticals by CMWSSB Div - 149, Zone - 11",Deposit Works,11,2020-21,2020-21 NL/2020-21/1406,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,342000,"Desilting of SWD and Side drains at Various Streets in Dn - 149, U-33, Z - XI.",Own Sources,11,2020-21,2021-22 NL/2020-21/1407,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,466000,"Minor Repair Works at Various Streets SWD in Dn - 149, U-33, Z - XI.",Own Sources,11,2020-21,2021-22 NL/2020-21/3849,Storm Water Drain,Completed,NL-VALASARAVAKKAM,149,92000,"Desilting of BRR SWD in Dn - 149, U-33, Z - XI.",Own Sources,11,2020-21,2021-22 NL/2020-21/4076,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,200000,"MINOR REPAIR OF STORM WATER DRAIN AND SIDE DRAIN AT VARIOUS STREETS IN DIV-153, U-34, Z-11.",Own Sources,11,2020-21,2021-22 NL/2020-21/4077,Storm Water Drain,Completed,NL-VALASARAVAKKAM,150,650000,"Desilting of SWD and Side drains at Various Streets in Dn - 153, U-34, Z - XI.",Own Sources,11,2020-21,2021-22 NL/2020-21/5784,Roads,Completed,NL-VALASARAVAKKAM,150,18898000,"RELAYING OF BT ROAD AT CHETTIYAR AGARAM MAIN ROAD DIV - 150, UNIT - 34, ZONE - 11",Own Sources,11,2020-21,2021-22 NL/2020-21/13845,Roads,Completed,NL-VALASARAVAKKAM,151,110000,"Relaying the BT Road at Lakshmi Nagar 1st Main Road Lane In Div-151, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13847,Roads,Completed,NL-VALASARAVAKKAM,151,604000,"Relaying the BT Road at Lakshmi Nagar 2nd Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13848,Roads,Completed,NL-VALASARAVAKKAM,151,244000,"Relaying the BT Road at Lakshmi Nagar 4th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13849,Roads,Completed,NL-VALASARAVAKKAM,151,198000,"Relaying the BT Road at Lakshmi Nagar 6th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13850,Roads,Completed,NL-VALASARAVAKKAM,151,276000,"Relaying the BT Road at Lakshmi Nagar 7th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13851,Roads,Completed,NL-VALASARAVAKKAM,151,457000,"Relaying the BT Road at Lakshmi Nagar 8th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13852,Roads,Completed,NL-VALASARAVAKKAM,151,251000,"ReRelaying the BT Road at Lakshmi Nagar 9th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13853,Roads,Completed,NL-VALASARAVAKKAM,151,502000,"Relaying the BT Road at Lakshmi Nagar 10th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13854,Roads,Completed,NL-VALASARAVAKKAM,151,266000,"Relaying the BT Road at Lakshmi Nagar 11th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13855,Roads,Completed,NL-VALASARAVAKKAM,151,278000,"Relaying the BT Road at Lakshmi Nagar 12th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13856,Roads,Completed,NL-VALASARAVAKKAM,151,316000,"Relaying the BT Road at Lakshmi Nagar Ext 1st Main Road In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13858,Roads,Completed,NL-VALASARAVAKKAM,151,269000,"RRelaying the BT Road at Lakshmi Nagar Ext 1st Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13859,Roads,Completed,NL-VALASARAVAKKAM,151,110000,"Relaying the BT Road at Lakshmi Nagar Ext 5th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13860,Roads,Completed,NL-VALASARAVAKKAM,151,549000,"Relaying the BT Road at Lakshmi Nagar Ext 3rd Main Road(W) In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13861,Roads,Completed,NL-VALASARAVAKKAM,151,369000,"Relaying the BT Road at Lakshmi Nagar Ext 4th Main Road In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13863,Roads,Completed,NL-VALASARAVAKKAM,151,482000,"Relaying the BT Road at Astalakshmi Nagar 1st Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13864,Roads,Completed,NL-VALASARAVAKKAM,151,203000,"Relaying the BT Road at Astalakshmi Nagar 2nd Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13865,Roads,Completed,NL-VALASARAVAKKAM,151,218000,"Relaying the BT Road at Astalakshmi Nagar 3rd Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/13866,Roads,Completed,NL-VALASARAVAKKAM,151,287000,"Relaying the BT Road at Astalakshmi Nagar 4th Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2660,Roads,Completed,NL-VALASARAVAKKAM,151,402000,"Relaying the BT Road at St. Johns School 1st Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2661,Roads,Completed,NL-VALASARAVAKKAM,151,228000,"Relaying the BT Road at Kamala Nagar In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2662,Roads,Completed,NL-VALASARAVAKKAM,151,162000,"Relaying the BT Road at Alapakkam Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2663,Roads,Completed,NL-VALASARAVAKKAM,151,916000,"Relaying the BT Road at Lakshmi Nagar Extn. 7th Main Road In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2664,Roads,Completed,NL-VALASARAVAKKAM,151,1097000,"Relaying the BT Road at Poothapedu School Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2665,Roads,Completed,NL-VALASARAVAKKAM,151,268000,"elaying the BT Road at NSC Bose Nagar Meenakshi Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2666,Roads,Completed,NL-VALASARAVAKKAM,151,191000,"Relaying the BT Road at Sabari Nagar 2nd Main Road (Part) In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2667,Roads,Completed,NL-VALASARAVAKKAM,151,558000,"Relaying the BT Road at Sri Ram Nagar Park Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2668,Roads,Completed,NL-VALASARAVAKKAM,151,365000,"Relaying the BT Road at Officers Colony 3rd Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2669,Roads,Completed,NL-VALASARAVAKKAM,151,156000,"Relaying the BT Road at Officers Colony Main Road In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2670,Roads,Completed,NL-VALASARAVAKKAM,151,203000,"Relaying the BT Road at Chinna Porur Maariamman Koil Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2817,Roads,Completed,NL-VALASARAVAKKAM,151,478000,"Relaying the BT Road at Chinna Porur Bajanai Koil Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2818,Roads,Completed,NL-VALASARAVAKKAM,151,269000,"Relaying the BT Road at Chinna Porur Valluvar Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2819,Roads,Completed,NL-VALASARAVAKKAM,151,326000,"Relaying the BT Road at Chinna Porur Nehru Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2820,Roads,Completed,NL-VALASARAVAKKAM,151,359000,"Relaying the BT Road at Chinna Porur Gandhi Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2821,Roads,Completed,NL-VALASARAVAKKAM,151,649000,"Relaying the BT Road at Chinna Porur Navamani Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2823,Roads,Completed,NL-VALASARAVAKKAM,151,184000,"Relaying the BT Road at Lakshmi Nagar Extn. 4th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2824,Roads,Completed,NL-VALASARAVAKKAM,151,126000,"Relaying the BT Road at LLakshmi Nagar Extn. 3rd Main Road In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2825,Roads,Completed,NL-VALASARAVAKKAM,151,878000,"Relaying the BT Road at Lakshmi Nagar 5th Cross Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2826,Roads,Completed,NL-VALASARAVAKKAM,151,335000,"Relaying the BT Road at Lakshmi Nagar Extn. 6th Main Road In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2846,Roads,Completed,NL-VALASARAVAKKAM,151,189000,"Relaying the BT Road at Annai Sathya Nagar 1st Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2847,Roads,Completed,NL-VALASARAVAKKAM,151,201000,"Relaying the BT Road at Annai Sathya Nagar 2nd Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2848,Roads,Completed,NL-VALASARAVAKKAM,151,220000,"Relaying the BT Road at Annai Sathya Nagar 3rd Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2849,Roads,Completed,NL-VALASARAVAKKAM,151,325000,"Relaying the BT Road at Annai Sathya Nagar 4th Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2850,Roads,Completed,NL-VALASARAVAKKAM,151,262000,"Relaying the BT Road at Annai Sathya Nagar 5th Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2851,Roads,Completed,NL-VALASARAVAKKAM,151,202000,"Relaying the BT Road at Annai Sathya Nagar 6th Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2852,Roads,Completed,NL-VALASARAVAKKAM,151,241000,"Relaying the BT Road at Annai Sathya Nagar 7th Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2854,Roads,Completed,NL-VALASARAVAKKAM,151,265000,"Relaying the BT Road at Annai Sathya Nagar 8th Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2855,Roads,Completed,NL-VALASARAVAKKAM,151,134000,"Relaying the BT Road at Suresh Nagar 1st Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2857,Roads,Completed,NL-VALASARAVAKKAM,151,118000,"Relaying the BT Road at Suresh Nagar 2nd Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2858,Roads,Completed,NL-VALASARAVAKKAM,151,161000,"Relaying the BT Road at TNHB Quarters 1st Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2859,Roads,Completed,NL-VALASARAVAKKAM,151,151000,"Relaying the BT Road at TNHB Quarters 2nd Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2860,Roads,Completed,NL-VALASARAVAKKAM,151,168000,"Relaying the BT Road at NSC Bose Nagar Kamatchi Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2861,Roads,Completed,NL-VALASARAVAKKAM,151,428000,"Relaying the BT Road at NSC Bose Nagar Golden Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2862,Roads,Completed,NL-VALASARAVAKKAM,151,324000,"Relaying the BT Road at NSC Bose Nagar Diamond Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/2863,Roads,Completed,NL-VALASARAVAKKAM,151,232000,"Relaying the BT Road at Venkateswara Avenue Road (Part) In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2864,Roads,Completed,NL-VALASARAVAKKAM,151,62000,"Relaying the BT Road at Venkateswara Avenue Lane In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2865,Roads,Completed,NL-VALASARAVAKKAM,151,617000,"Relaying the BT Road at Pillaiyar Koil Street In Div-151,Unit-34,Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/3876,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,540000,"Desilting Of Side Drain And Storm Water Drain at Various Streets in Div-151 U-34,Z-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/3912,Storm Water Drain,Completed,NL-VALASARAVAKKAM,151,360000,"Minor Repair work at Various streets in Dn-151, Unit-34,Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/4118,Buildings,Completed,NL-VALASARAVAKKAM,151,44000,"Demolishing of Panchayath Union Middel School Classroom at School street in DN-151, Unit-34, Zone-XI",Own Sources,11,2020-21,2021-22 NL/2020-21/1403,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,332000,"Desilting of SWD and Side drains at Various Streets in Dn - 152, U-33, Z - XI.",Own Sources,11,2020-21,2021-22 NL/2020-21/1404,Storm Water Drain,Completed,NL-VALASARAVAKKAM,152,467000,"Minor Repair Works at Various Streets in Dn - 152, U-33, Z - XI.",Own Sources,11,2020-21,2021-22 BR/2020-21/0835,Road Cut,Completed,BR-Bus Route Roads,153,942000,Restoration for road cut made by OFC Providers at various interior roads in Dn-153 & 154. Zone XI,Deposit Works,11,2020-21,2020-21 BR/2020-21/0837,Road Cut,Completed,BR-Bus Route Roads,153,942000,"Restoration for road cut made by OFC Providers at various interior roads in Dn-150 ,151 & 153. Zone XI",Deposit Works,11,2020-21,2020-21 NL/2020-21/14056,Roads,Completed,NL-VALASARAVAKKAM,153,441000,"Relaying the BT Road at Sakthi Nagar New Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14057,Roads,Completed,NL-VALASARAVAKKAM,153,663000,"Relaying the BT Road at Sakthi Nagar Pleasant Avenue in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14058,Roads,Completed,NL-VALASARAVAKKAM,153,414000,"Relaying the BT Road at Parvathi Avenue 2nd Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14059,Roads,Completed,NL-VALASARAVAKKAM,153,275000,"Relaying the BT Road at Parvathi Avenue 3rd Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14060,Roads,Completed,NL-VALASARAVAKKAM,153,380000,"Relaying the BT Road at Parvathi Avenue 5th Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14061,Roads,Completed,NL-VALASARAVAKKAM,153,185000,"Relaying the BT Road at Somasundaram Avenue 1st Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14062,Roads,Completed,NL-VALASARAVAKKAM,153,215000,"Relaying the BT Road at Somasundaram Avenue 2nd Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14063,Roads,Completed,NL-VALASARAVAKKAM,153,175000,"Relaying the BT Road at Somasundaram Avenue 3rd Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14064,Roads,Completed,NL-VALASARAVAKKAM,153,147000,"Relaying the BT Road at Somasundaram Avenue 4th Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14065,Roads,Completed,NL-VALASARAVAKKAM,153,103000,"Relaying the BT Road at Somasundaram Avenue 6th Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14066,Roads,Completed,NL-VALASARAVAKKAM,153,149000,"Relaying the BT Road at Ganesh Avenue 2nd Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14067,Roads,Completed,NL-VALASARAVAKKAM,153,213000,"Relaying the BT Road at Ganesh Avenue 10th Street (Partly) in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14068,Roads,Completed,NL-VALASARAVAKKAM,153,248000,"Relaying the BT Road at Subashree Nagar 6th Cross Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14069,Roads,Completed,NL-VALASARAVAKKAM,153,343000,"Relaying the BT Road at Athibagavan Nagar 3rd Street (Partly) in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14070,Roads,Completed,NL-VALASARAVAKKAM,153,706000,"Relaying the BT Road at Mangala Nagar 8th Cross Street (Partly) in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14075,Roads,Completed,NL-VALASARAVAKKAM,153,440000,"Relaying the BT Road at Mangala Nagar 9th Cross Street (Partly) in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14076,Roads,Completed,NL-VALASARAVAKKAM,153,438000,"Relaying the BT Road at Mangala Nagar 12th Cross Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14077,Roads,Completed,NL-VALASARAVAKKAM,153,96000,"Relaying the BT Road at Mangala Nagar 12th Cross Street-3rd Lane in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14078,Roads,Completed,NL-VALASARAVAKKAM,153,381000,"Relaying the BT Road at RE Nagar 5th Street to Melpallikuppam (West) in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14079,Roads,Completed,NL-VALASARAVAKKAM,153,358000,"Relaying the BT Road at RE Nagar 7th Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/14080,Roads,Completed,NL-VALASARAVAKKAM,153,344000,"Relaying the BT Road at RE Nagar 8th Street in Div-153, Unit-34, Zone-11",Own Sources,11,2020-21,2021-22 NL/2020-21/5627,Roads,Completed,NL-VALASARAVAKKAM,153,398000,"Relaying of BT road at Mangala Nagar 12th Cross Street - 2nd Lane in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5629,Roads,Completed,NL-VALASARAVAKKAM,153,533000,"Relaying of BT road at Mangala Nagar 5th Cross Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5630,Roads,Completed,NL-VALASARAVAKKAM,153,240000,"Relaying of BT road at Mangala Nagar 13th Cross Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5631,Roads,Completed,NL-VALASARAVAKKAM,153,744000,"Relaying of BT road at Mangala Nagar 6th Cross Street (East) - Partly in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5632,Roads,Completed,NL-VALASARAVAKKAM,153,717000,"Relaying of BT road at Mangala Nagar Millenium Mantra in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5633,Roads,Completed,NL-VALASARAVAKKAM,153,364000,"Relaying of BT road at Thiruveethi Amman Koil 1st Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5634,Roads,Completed,NL-VALASARAVAKKAM,153,442000,"Relaying of BT road at Thiruveethi Amman Koil 2nd Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5635,Roads,Completed,NL-VALASARAVAKKAM,153,462000,"Relaying of BT road at Thiruveethi Amman Koil 4th Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5636,Roads,Completed,NL-VALASARAVAKKAM,153,354000,"Relaying of BT road at Kaviya Garden Nakeeran Street (Partly) in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5637,Roads,Completed,NL-VALASARAVAKKAM,153,317000,"Relaying of BT road at Ambal Nagar Mullai Street (South) in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5638,Roads,Completed,NL-VALASARAVAKKAM,153,508000,"Relaying of BT road at Ambal Nagar Malligai Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5639,Roads,Completed,NL-VALASARAVAKKAM,153,1006000,"Relaying of BT road at Sakthi Nagar Main Road in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5641,Roads,Completed,NL-VALASARAVAKKAM,153,666000,"Relaying of BT road at Vigneshwara Nagar Ganga Kaveri Street (West) in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5642,Roads,Completed,NL-VALASARAVAKKAM,153,184000,"Relaying of BT road at Ambal Nagar Thalamboo Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5643,Roads,Completed,NL-VALASARAVAKKAM,153,363000,"Relaying of BT road at Ambal Nagar Thalamboo 1st Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5644,Roads,Completed,NL-VALASARAVAKKAM,153,236000,"Relaying of BT road at Ambal Nagar Sooryagandhi Street in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5645,Roads,Completed,NL-VALASARAVAKKAM,153,375000,"Relaying of BT road at Mangala Nagar 2nd Main Road in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/5647,Roads,Completed,NL-VALASARAVAKKAM,153,374000,"Relaying of BT road at Mangala Nagar 4th Cross Street - Lane in DN-153, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 BR/2020-21/0839,Road Cut,Completed,BR-Bus Route Roads,154,423000,Restoration for road cut made by OFC Providers at various interior roads in Dn-154. Zone XI,Deposit Works,11,2020-21,2020-21 NL/2020-21/2908,Roads,Completed,NL-VALASARAVAKKAM,154,531000,"Relaying of BT road at Venkateshwara Nagar 20th street in DN-154, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/2963,Roads,Completed,NL-VALASARAVAKKAM,154,710000,"Relaying of BT road at Venkateshwara Nagar 1st Main Road Extn in DN-154, Unit-34, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/2969,Roads,Completed,NL-VALASARAVAKKAM,154,780000,"Formation of Cement concrete road at Venu street in DN-154,Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/2974,Roads,Completed,NL-VALASARAVAKKAM,154,798000,"Formation of Cement concrete road at Avvai street in DN-154, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/3955,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,350000,"Minor Pepair to the Exising SWD in DN-154, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/4067,Storm Water Drain,Completed,NL-VALASARAVAKKAM,154,500000,"Desilting of side drain and storm water Drain at Various streets in Dn-154, U-34, Z-11.",Own Sources,11,2020-21,2020-21 BR/2020-21/1218,Road Cut,Completed,BR-Bus Route Roads,155,1889000,"Restoration of Roadcut at Kamaraj Street(Ramapuram) by from jn of Arasa Maram to senthamil Nagar Road CMWSSB Div - 155, Zone - 11",Deposit Works,11,2020-21,2020-21 BR/2020-21/1221,Road Cut,Completed,BR-Bus Route Roads,155,1689000,"Restoration of Roadcut at Kamaraj Street(Ramapuram) by from jn of senthamil Nagar Road to Arjunan Street CMWSSB Div - 155, Zone - 11",Deposit Works,11,2020-21,2020-21 NL/2020-21/3861,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,245000,"Minor repairs to SWD at various streets in DN-155, Unit-34, Zone-11",Own Sources,11,2020-21,2020-21 NL/2020-21/3866,Storm Water Drain,Completed,NL-VALASARAVAKKAM,155,655000,"Desilting side drain and storm water drain at various street in DN-155, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/6120,Buildings,Completed,NL-VALASARAVAKKAM,155,155000,"Formation of Cement concrete road at Eswaran koil street (School road) in DN-155, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 NL/2020-21/6121,Buildings,Completed,NL-VALASARAVAKKAM,155,655000,"Formation of Cement concrete road at Mahalakshmi nagar annex in DN-155, Unit-34, Zone-11.",Own Sources,11,2020-21,2020-21 BR/2020-21/0880,Road Cut,Completed,BR-Bus Route Roads,156,959000,"Restoration of Road cut made by OFC Operators at Various Interior Road in Div 156 ,Zone 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/7881,Road Cut,Completed,BR-Bus Route Roads,156,975000,"Restoration of OFC roadcuts at Various Streets in Div-156,157,158,160,161,U-35 & 36 ,Zone 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/7887,Road Cut,Completed,BR-Bus Route Roads,156,959000,"Restoration of OFC roadcuts at Various Streets in Div-156, U-35 ,Zone 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/7888,Road Cut,Completed,BR-Bus Route Roads,156,942000,"Restoration of OFC roadcuts at Various Streets in Div-156, U-35 ,Zone 12",Deposit Works,12,2020-21,2020-21 NM/2020-21/2086,Roads,Completed,NM-ALANDUR,156,2383000,"ROAD CUT RESTORATION OF BT ROAD AT AGS COLONY PH-3 MAIN ROAD 1ST AVENUE,2ND AVENUE,3RD AVENUE,4TH AVENUE,4TH AVENUE CROSS , 5TH AVENUE AND ANNAI VELANKANNI NAGAR PH-1 9TH STREET IN DN-156,U-35,Z-12",Deposit Works,12,2020-21,2020-21 NM/2020-21/2106,Roads,Completed,NM-ALANDUR,156,2356000,"ROAD CUT RESTORATION OF BT ROAD AT KRISHNA NAGAR 1ST MAIN ROAD AND 2ND MAIN ROAD, PILLAYAR STREET, KRISHNA NAGAR EXTN 4TH CROSS STREET, LAKSHMI AVENUE 1ST CROSS,2ND CROSS,3RD CROSS,4TH CROSS STREET IN DN-156,U-35,Z-12",Deposit Works,12,2020-21,2021-22 NM/2020-21/2111,Roads,Completed,NM-ALANDUR,156,2411000,"ROAD CUT RESTORATION OF BT ROAD AT ANNAIVELANKANNI NAGAR PH-1,11TH STREET(NATARAJAN NAGAR) , 2ND STREET , 3RD STREET,4TH STREET,5TH STREET,6TH STREET, 7TH STREET 8TH STREET , AND 9TH CROSS STREET IN DN-156,U-35,Z-12",Deposit Works,12,2020-21,2021-22 L/2020-21/2269,Electrical,Completed,L-Electrical,158,2001000,SUPPLY AND ERECTION OF 8 NOS OF 6MTR LAMP POST WITH 2.7MTR SINGLE ARCH BRACKET WITH 150-165W LED FITTING AND 31 NOS OF 6MTR ST BRACKET WITH 40W LED FITTING AT THULASIGAPURAM AND DEFENCE COLONY 4TH STREET AND WOOD GREEKCOUNTRY IN DN 158 ZONE 12 ,Grants,12,2020-21,2021-22 L/2020-21/0741,Electrical,Completed,L-Electrical,159,7194700,"Supply and erection of 48 nos of 6m GI Street lamp post with Single straight bracket , with 48 nos of 40-50 W LED Fitting and Erection of 22 nos 8 mtr Octagonal sigle bracket and 10 nos of 8 mtr Double Bracket and 11 nos of 8 mtr GI lamp post arch Bracketwith 53 Nos of 150 W LED Fittings in GST Raod Mariosn 6 street Jeevan St and Various Location In DN 159,161,162 Zone XII.",Grants,12,2020-21,2021-22 BR/2020-21/6180,Roads,Completed,BR-Bus Route Roads,160,2973000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Railway Station Road in Dn-160,Zone XII",Grants,12,2020-21,2021-22 L/2020-21/6760,Electrical,Completed,L-Electrical,160,195000,"Replacement of 5 Nos of Rusted, Damaged Kiosk Pillar Box by New Kiosk Pillar Box at AC office service road, Porur vadapalani service road, vadapalani guindy service road, Le royal meridian service road , vadapalani centre median pillar in Division160 , Z-XII, Alandur (Sch of rate 2020-21)",Own Sources,12,2020-21,2021-22 NM/2020-21/5419,Buildings,Completed,NM-ALANDUR,160,360000,"Improvement Work To Existing Zonal Office Building At New Street In Division -160 ,Unit-36,Zone-12.",Own Sources,12,2020-21,2021-22 NM/2020-21/5428,Buildings,Completed,NM-ALANDUR,160,794000,"IMPROVEMENT WORKS TO EXISTING ZONAL OFFICE BUILDING (INTERIOR REPAIR WORKS )AT NEW STREET IN DIVISION -160,UNIT-36,ZONE-12.",Own Sources,12,2020-21,2020-21 BR/2020-21/1277,Road Cut,Completed,BR-Bus Route Roads,161,2049000,"Restoration of Roadcut at West Karaikalan Street from jn of Medavakkam Main road to Thirumala Store by TANTRANSCO Div - 161, Zone - 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/1278,Road Cut,Completed,BR-Bus Route Roads,161,1899000,"Restoration of Roadcut at West Karaikalan Street from jn of Inner Ring road to Thirumala Store by TANTRANSCO Div - 161, Zone - 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/1280,Road Cut,Completed,BR-Bus Route Roads,161,1036000,Restoration of Roadcut at Alandur Road(Railway Station Road) from jn of MKN Road to NRaja Street by TANTRANSCO in Div 161 Zone - 12,Deposit Works,12,2020-21,2020-21 BR/2020-21/6183,Roads,Completed,BR-Bus Route Roads,161,1012000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Officer Colony IV Street in Dn-161,Zone XII",Grants,12,2020-21,2021-22 BR/2020-21/6184,Roads,Completed,BR-Bus Route Roads,161,1366000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Thiruvalluvar Street in Dn-161,Zone XII",Grants,12,2020-21,2021-22 L/2020-21/6866,Electrical,Completed,L-Electrical,161,183000,"Replacement of 4 Nos of Rusted, Damaged Kiosk Pillar Box by New Kiosk Pillar Box at Marrison 1st st Div 162, Nanganallur 1st main road , Nanganallur 10th st and Kesari Nagar main road in Div165 and Shifting of Kiosk pillar boxes at Velachery road and officers colony 1st st in Div 161, Z-XII, Alandur (Sch of rate 2020-21)",Own Sources,12,2020-21,2021-22 NM/2020-21/2272,Road Cut,Completed,NM-ALANDUR,161,603000,"ROAD CUT RESTORATION WORK MADE BY CMWSSB AT PUDUPET STREET IN DN-161,U-36,Z-12.",Deposit Works,12,2020-21,2020-21 NM/2020-21/2491,Buildings,Completed,NM-ALANDUR,161,137000,"DEMOLITION OF PUBLIC CONVENIENCE AT VOC NAGAR IN DN-161,UNIT-36,ZONE-12",Own Sources,12,2020-21,2020-21 BR/2020-21/1032,Road Cut,Completed,BR-Bus Route Roads,162,975000,"Restoration of Road cut made by OFC Operators at Various Interior Road in Div 162,163,164 and 165 ,Zone 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/6185,Roads,Completed,BR-Bus Route Roads,162,1710000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at T.G.Nagar 4th Main Road in Dn-162,Zone XII",Grants,12,2020-21,2021-22 NM/2020-21/2096,Road Cut,Completed,NM-ALANDUR,162,537000,"ROAD CUT RESTORATION WORK MADE BY CMWSSB AT NOBLE 1ST STREET IN DN-162, U-36, Z-12.",Deposit Works,12,2020-21,2020-21 NM/2020-21/2112,Road Cut,Completed,NM-ALANDUR,162,513000,"ROAD CUT RESTORATION WORK MADE BY CMWSSB AT THIRUVALLUVAR NAGAR 1ST CROSS STREET IN DN-162, U-36, Z-12.",Deposit Works,12,2020-21,2020-21 NM/2020-21/2113,Road Cut,Completed,NM-ALANDUR,162,213800,"ROAD CUT RESTORATION WORK MADE BY CMWSSB AT THIRUVALLUVAR NAGAR 4TH CROSS STREET IN DN-162, U-36, Z-12.",Deposit Works,12,2020-21,2020-21 NM/2020-21/4495,Road Cut,Completed,NM-ALANDUR,162,560000,"RESTORATION OF ROAD CUT MADE CMWSSB AT THIRUVALLUVAR NAGAR MAIN ROAD IN DIVISION-162, UNIT-36, ZONE-12.",Deposit Works,12,2020-21,2021-22 BR/2020-21/1279,Road Cut,Completed,BR-Bus Route Roads,163,98500,"Restoration of Roadcut at Erikkarai Street from jn of Karuneegar Street to Balagangadhar Street by CMWSSB Div - 163, Zone - 12",Deposit Works,12,2020-21,2021-22 BR/2020-21/1281,Road Cut,Completed,BR-Bus Route Roads,163,200000,"Restoration of Roadcut at Erikkarai Street from jn of kumarapuram 1st street by CMWSSB Div - 163, Zone - 12",Deposit Works,12,2020-21,2021-22 BR/2020-21/1286,Road Cut,Completed,BR-Bus Route Roads,163,2475000,"Restoration of Roadcut at Lake View(Erikarai Street) Road from jn of Sastri Nagar Main Road to Medavakkam Main Road by TANTRANSCO Div - 163, Zone - 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/6190,Roads,Completed,BR-Bus Route Roads,163,920000,"Relaying the road with DBM and BC after cold milling by paver finisher along with traffic improvement work at Erikarai Street in Dn-163,Zone XII",Grants,12,2020-21,2021-22 NM/2020-21/2399,Buildings,Completed,NM-ALANDUR,163,21000,DEMOLITION OF THE EXISTING DAMAGED ANGANWADI BUILDING AT NERUPPUMEDAI (KUNDRAKUDI NAGAR) IN DN-163 U-36 Z-12.,Own Sources,12,2020-21,2021-22 NM/2020-21/2402,Buildings,Completed,NM-ALANDUR,163,20500,DEMOLITION OF THE EXISTING DAMAGED ANGANWADI BUILDING AT MASTHON GORI STREET (MANNADIYAMMAN KOIL STREET) IN DN-163 U-37 Z-12.,Own Sources,12,2020-21,2021-22 BR/2020-21/1033,Road Cut,Completed,BR-Bus Route Roads,165,536000,"Restoration of Road cut made by OFC Operators at Various Interior Road in Div 165 and 167 ,Zone 12",Deposit Works,12,2020-21,2020-21 BR/2020-21/6189,Roads,Completed,BR-Bus Route Roads,165,2153000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at New Colony Main Road in Dn-165,Zone XII",Grants,12,2020-21,2021-22 J/2020-21/6193,Bridges,Completed,J-Bridges,165,1700000,"Construction of Additional Box Culvert-(2vent) across veerangal odai connecting Muthiyal reddy Nagar and Inner Ring Road dn -165,zone-12",Own Sources,12,2020-21,2020-21 BR/2020-21/6186,Roads,Completed,BR-Bus Route Roads,167,10246000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at MGR Road in Dn-167,Zone XII",Grants,12,2020-21,2021-22 BR/2020-21/6188,Roads,Completed,BR-Bus Route Roads,167,3441000,"Relaying the road with BC after cold milling by paver finisher along with traffic improvement work at Nanganallur 5th Main Road in Dn-167,Zone XII",Grants,12,2020-21,2021-22 BR/2020-21/0842,Road Cut,Completed,BR-Bus Route Roads,168,1271000,"Restoration for Reliance Jio road cut at various streets in Div-168,169,187 & 188,Unit - 42, Zone 14",Deposit Works,14,2020-21,2020-21 NP/2020-21/3945,Storm Water Drain,Completed,NP-PERUNGUDI,168,164000,"Desilting of Storm Water Drain and Side drain in div -168, Unit - 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3946,Storm Water Drain,Completed,NP-PERUNGUDI,168,252000,"Minor Repair Works of Storm Water Drain and Side drain in div -168, Unit - 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/9261,Buildings,Completed,NP-PERUNGUDI,168,200000,"Improvements and repairs to Division Office in Dn-168, Unit-42, Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/2273,Buildings,Completed,NP-PERUNGUDI,169,200000,"Improvements and repairs to Composit Yard and Division Office Building in Dn-169, Unit-42, Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/2370,Parks,Completed,NP-PERUNGUDI,169,591000,"Providing Water Faciltity, EB supply & Fencing of Mini Forest by Miyawaki Method in Balaji Nagar 24th Street OSR Land in Div 169, Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/3393,Roads,Completed,NP-PERUNGUDI,169,609000,"Providing and Laying for Hume pipe at Puzhuthivakkam Bus stand , Annaitherasa Nagar 11th Street, in Dn -169, U-42,Z-14",Own Sources,14,2020-21,2020-21 NP/2020-21/3938,Storm Water Drain,Completed,NP-PERUNGUDI,169,491000,"Desilting for Side Drain and Storm water drain at Various streets in Dn -169 Unit- 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3944,Storm Water Drain,Completed,NP-PERUNGUDI,169,143000,"Minor repair Works for Side Drain and Storm water drain at Various streets in Dn -169 Unit- 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/4165,Roads,Completed,NP-PERUNGUDI,169,2093000,"WORK:- Restoration of CMWSSB BT Road Cut Portion Balaji Nagar 24th Street, Annai therasa Nagar 17th, 18th, 20th street, Sivaprakasam Nagar 2nd Street, Ramalingam Nagar main road, Ram Nagar 9th Street, JK Salai in Dn-169, Unit-42, Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/4169,Roads,Completed,NP-PERUNGUDI,169,2131000,"WORK:- Restoration of CMWSSB BT Road Cut Portion Mullai Street, Srinivsa road, Ram Nagar (North)8th Street, Inner ring road (Ram nagar 7th Street), Arivoli Street, Vivekandar Street, in Dn-169,Unit-42,Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/9679,Buildings,Completed,NP-PERUNGUDI,169,259000,"Converting the shop of Shopping Complex in Puzhuthivakkam Bus stand into MINI CLINIC in DN-169, UNIT-42, ZONE-14.",Own Sources,14,2020-21,2020-21 BR/2020-21/0659,Road Cut,Completed,BR-Bus Route Roads,170,975000,"Restoration of Roadcut made by OFC Operators at Various Streets in Dn-170,171 and 173, Zone-13",Deposit Works,13,2020-21,2020-21 NN/2020-21/3942,Storm Water Drain,Completed,NN-ADYAR,170,360000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREETS IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4032,Storm Water Drain,Completed,NN-ADYAR,170,640000,"MINOR REPAIR WORKS TO THE STORM WATER DRAIN AT VARIOUS STREETS IN DN-170,UT-40A,ZONE-13.",Own Sources,13,2020-21,2021-22 L/2020-21/4564,Electrical,Completed,L-Electrical,171,606000,"Supply & installation of 1 No of 20HP Submersible Pump complete set with suitable pump controller panel board for dewatering of rain water during monsoon, in Aranganathan Subway in Div-171, ZXIII",Own Sources,13,2020-21,2021-22 NN/2020-21/3856,Buildings,Completed,NN-ADYAR,172,693000,"Minor Repair Works in Storm Water Drain Various Location in Division 172,Unit-40,Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4143,Buildings,Completed,NN-ADYAR,172,307000,"Desilting in Storm Water Drain Various Location in Division 172,Unit-40,Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4257,Buildings,Completed,NN-ADYAR,172,398000,"Restoration of Road cut made by CMWSSB at East Ellaiamman koil street,West canal bank road Kottur in Division -172,Unit -40,Zone XIII.",Deposit Works,13,2020-21,2021-22 NN/2020-21/4285,Buildings,Completed,NN-ADYAR,172,664000,"Restoration of Road cut made by CMWSSB at River view road,Kotturpuram in Division -172,Unit -40,Zone XIII.",Deposit Works,13,2020-21,2021-22 NN/2020-21/4377,Roads,Completed,NN-ADYAR,172,1569000,"Restoration of Road cut made by CMWSSB at Pondichery road ,Kottur in Division -172,Unit -40,Zone XIII.",Deposit Works,13,2020-21,2021-22 BR/2020-21/10018,Roads,Completed,BR-Bus Route Roads,173,500000,Repairs and Rectification of SS Hand Rail Center Median at DGS Dinakaran Salai in Div - 173 & Zone - 13,Own Sources,13,2020-21,2021-22 BR/2020-21/2770,Roads,Completed,BR-Bus Route Roads,173,470000,Providing Black and White Painting for Footpath Kerb & Centre Median at Dr. D.G.S. Dhinakaran Salai in Div - 173 Zone - 13,Own Sources,13,2020-21,2021-22 BR/2020-21/2771,Roads,Completed,BR-Bus Route Roads,173,198000,"Providing Black and White Painting for Footpath Kerb & Centre Median at P.S. Kumarasamy Raja Road, Ramakrishna Mutt Road (Part) & Broadies Castle Road in Div - 173 Zone - 13",Own Sources,13,2020-21,2020-21 NN/2020-21/2758,Buildings,Completed,NN-ADYAR,173,398000,"Improvements to footpath works RK Nagar 2nd cross street in Division 173,Unit-40,Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4138,Buildings,Completed,NN-ADYAR,173,710000,DESILTING OF STROM WATER DRAINS AT VARIES STREETS IN DN-173 UNIT-40 ZONE-13,Own Sources,13,2020-21,2021-22 NN/2020-21/4174,Storm Water Drain,Completed,NN-ADYAR,173,287000,"Minor Repair Works in Storm Water Drains at Various Location in Division 173,Unit-40,Zone-13.",Own Sources,13,2020-21,2021-22 L/2020-21/2987,Electrical,Completed,L-Electrical,174,6175000,"Provision of 72nos of 8mtr GI Lamp post with Double straight bracket and 6nos of 8mtr GI Lamp Post with Tribel Straight Bracket and Removal of 143nos 9/11mtr old lamp post at Velachery Main Road (Halda Junction to Gurunanak College) in Div 174, Zone-XIII",Own Sources,13,2020-21,2021-22 NN/2020-21/3893,Storm Water Drain,Completed,NN-ADYAR,174,418000,"DESILTING OF STROM WATER DRAIN AT VARIOUS STREETS IN DN-174, UT-40A,ZONE-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4019,Storm Water Drain,Completed,NN-ADYAR,174,582000,"MINOR REPAIR OF STROM WATER DRAIN AT VARIOUS STREETS IN DN-174,UT-40A,ZONE-13.",Own Sources,13,2020-21,2021-22 Q/2020-21/0769,Buildings,Completed,Q-Solid Waste Management,174,1500000,"Construction of Domestic Hazardous waste Collection centre at Burial ground near Gurunanak College,Velachery main road in Div-174, Z-13",Grants,13,2020-21,2020-21 BR/2020-21/0844,Road Cut,Completed,BR-Bus Route Roads,175,975000,"Restoration of Road cut made by OFC Operators at Various Bus Route Roads In Dn.175 &182, Zone 13",Deposit Works,13,2020-21,2020-21 BR/2020-21/13171,Road Cut,Completed,BR-Bus Route Roads,175,382000,"Restoration of Road cut made by OFC Operators at Various Bus Route Roads In Dn.176 &181, Zone 13",Deposit Works,13,2020-21,2020-21 BR/2020-21/3362,Road Cut,Completed,BR-Bus Route Roads,175,975000,"Restoration of Road cut made by OFC Operators at Various Bus Route Roads In Dn.176 &181, Zone 13",Deposit Works,13,2020-21,2020-21 NN/2020-21/0753,Buildings,Completed,NN-ADYAR,175,534000,"Proposed construction of RCC Sump (3.00mx2.40mx2.40m) and Improvements to Water supply and Drainage arrangements for Zonal office Building at Dr.Muthulakshmi Salai in Div-175, Unit-40, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/0862,Buildings,Completed,NN-ADYAR,175,873000,"Repair and Improvements to Zonal office Building at Dr.Muthulakshmi Salai in Div-175, Unit-40, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/1132,Buildings,Completed,NN-ADYAR,175,1247000,"Dismantling and Reconstruction of Compound Wall in CPS at Indira nagar 29th cross street in Div-175, Unit-40, Zone-13. (Reach ch 0 m to 88 m)",Own Sources,13,2020-21,2021-22 NN/2020-21/3815,Buildings,Completed,NN-ADYAR,175,390000,"Repair and Additional Improvement work in South Region Office at Zonal office Building Dr.Muthulakshmi Salai in Div-175, Unit-40, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/3978,Storm Water Drain,Completed,NN-ADYAR,175,215000,"Minor Repair work of Storm Water Drain at Various Streets in Division-175, Unit-40, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4153,Storm Water Drain,Completed,NN-ADYAR,175,785000,"Desilting work of Storm Water Drain at Various Streets in Division-175, Unit-40, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4815,Roads,Completed,NN-ADYAR,175,2989000,"Laying of C.C. road with RMC M30 at Indira Nagar 18th cross street in Dn-175, Unit-40, Zone-13.",MLACDS,13,2020-21,2020-21 BR/2020-21/2374,Road Cut,Completed,BR-Bus Route Roads,176,980000,"Restoration of roadcut made by Service department (OFC) at interior roads in division 176,181 and 182 ,Zone 13",Deposit Works,13,2020-21,2020-21 NN/2020-21/4125,Storm Water Drain,Completed,NN-ADYAR,176,377000,"Desilting of Existing Storm water drain at various Streets in Division 176, Unit 38, zone 13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4127,Storm Water Drain,Completed,NN-ADYAR,176,450000,"Minor Repair works to existing Storm Water Drain at Various Streets in Div-176,Unit-38,Zone-13",Own Sources,13,2020-21,2021-22 BR/2020-21/1282,Road Cut,Completed,BR-Bus Route Roads,177,2436000,"Restoration of Roadcut at TNHB Colony Road from jn of Judge Ramakrishnan Road to TNHB 9th street by TANTRANSCO Div - 177, Zone - 13",Deposit Works,13,2020-21,2020-21 BR/2020-21/1283,Road Cut,Completed,BR-Bus Route Roads,177,2231000,"Restoration of Roadcut at TNHB Colony Road from jn of TNHB 1st Main Road to TNHB 9th street by TANTRANSCO Div - 177, Zone - 13",Deposit Works,13,2020-21,2020-21 NN/2020-21/2159,Storm Water Drain,Completed,NN-ADYAR,177,86000,"Providing Trash Arrestor in Rajbhavan Canal At Velachery Lake Disposal Point in Division - 177, Unit - 40A, Zone - 13.",Own Sources,13,2020-21,2021-22 NN/2020-21/3857,Roads,Completed,NN-ADYAR,177,444000,"Minnor Repair work of Strom Water Drain at various location in Dn-177,Unit-40A,Zone-XIII",Own Sources,13,2020-21,2021-22 NN/2020-21/4028,Storm Water Drain,Completed,NN-ADYAR,177,320000,"Desilting of Storm water drain at various location in DN -177 , UNIT 40A , ZONE -13.",Own Sources,13,2020-21,2021-22 NN/2020-21/3892,Storm Water Drain,Completed,NN-ADYAR,178,447000,"Desilting of Storm Water Drain at Various Streets (Package-I) in Division-178, UNIT-39, ZONE-13",Own Sources,13,2020-21,2021-22 NN/2020-21/3998,Storm Water Drain,Completed,NN-ADYAR,178,812000,"Minor Repair Work of Storm Water Drain at Various Streets (Package-II) in Division-178, UNIT-39, ZONE-13",Own Sources,13,2020-21,2021-22 NN/2020-21/4034,Storm Water Drain,Completed,NN-ADYAR,178,273000,"Minor Repair Work of Storm Water Drain at Various Streets (Package-I) in Division-178, Unit-39, Zone-13",Own Sources,13,2020-21,2021-22 NN/2020-21/4168,Storm Water Drain,Completed,NN-ADYAR,178,276000,"Desilting of Storm Water Drain at Various Streets (Package-II) in Division-178, UNIT-39, ZONE-13",Own Sources,13,2020-21,2021-22 BR/2020-21/1022,Road Cut,Completed,BR-Bus Route Roads,179,959000,"Restoration of Road cut made by service department(OFC) at interior roads in division 179,180 and 181,Zone 13",Deposit Works,13,2020-21,2020-21 NN/2020-21/3933,Storm Water Drain,Completed,NN-ADYAR,179,640000,"Desilting of Storm Water Drain at Various Streets in Dn-179, Unit-39, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4001,Storm Water Drain,Completed,NN-ADYAR,179,352000,Minor Repair works of Storm Water Drain at Various Streets in Dn-179,Own Sources,13,2020-21,2021-22 NN/2020-21/3885,Storm Water Drain,Completed,NN-ADYAR,180,340000,"Desilting of Storm Water Drain at Various Streets (Package-I) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/3917,Storm Water Drain,Completed,NN-ADYAR,180,366000,"Minor repair works of Storm Water Drain at Various Streets (Package-I) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4003,Storm Water Drain,Completed,NN-ADYAR,180,175000,"Minor repair works of Storm Water Drain at Various Streets (Package-II) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4148,Storm Water Drain,Completed,NN-ADYAR,180,498000,"Desilting of Storm Water Drain at Various Streets (Package-II) in Dn-180, Unit-39, Zone-13.",Own Sources,13,2020-21,2021-22 NN/2020-21/4434,Buildings,Completed,NN-ADYAR,180,196000,"Dismantling of Existing UPHC Building at Thiruvalluvar Salai in Dn-180, Unit-39, Zone-13.",Own Sources,13,2020-21,2021-22 BR/2020-21/13631,Road Cut,Completed,BR-Bus Route Roads,181,975000,"Restoration of OFC Road made by Cable Operators at various interior roads in Div-181 & 182 ,Zone XIII",Deposit Works,13,2020-21,2020-21 L/2020-21/2984,Electrical,Completed,L-Electrical,181,494000,"PROVISION OF REMOVAL & RE-ERECTION OF 23 NOS 6 MTR GI LAMP POST WITH ARCH BRACKET AT TIGER VARADACHARI ROAD, BESANT NAGAR IN DIV-181, ZXIII",Own Sources,13,2020-21,2020-21 NN/2020-21/4140,Storm Water Drain,Completed,NN-ADYAR,181,160000,"Desilting of Existing Storm Water Drain at Various Streets in Div181,Unit 38,Zone-13",Own Sources,13,2020-21,2021-22 NN/2020-21/4141,Storm Water Drain,Completed,NN-ADYAR,181,546000,"Minor Repairs works to Existing Storm Water Drain at Various Streets in Div181,Unit 38,Zone-13",Own Sources,13,2020-21,2021-22 NN/2020-21/6391,Roads,Completed,NN-ADYAR,182,531000,"Providing Interlocking blocks at Thiruveediamman koil street 1st and 2nd lanes under MLACDS Scheme in Div-182, U-38, Z-13",MLACDS,13,2020-21,2020-21 NN/2020-21/6392,Roads,Completed,NN-ADYAR,182,572000,"Providing Interlocking blocks at Thiruveediamman koil street 3rd lane, 4th lane and 5th lanes under MLACDS Scheme in Div-182, U-38, Z-13",MLACDS,13,2020-21,2020-21 NN/2020-21/6393,Roads,Completed,NN-ADYAR,182,511000,"Providing Interlocking blocks at Chithrakulam street 1st lane and Mettu street 2nd lane under MLACDS Scheme in Div-182, U-38, Z-13",MLACDS,13,2020-21,2020-21 NN/2020-21/6394,Roads,Completed,NN-ADYAR,182,529000,"Providing Interlocking blocks at Chithrakulam street 2nd lane under MLACDS Scheme in Div-182, U-38, Z-13.",MLACDS,13,2020-21,2020-21 NN/2020-21/8389,Bridges,Completed,NN-ADYAR,182,4200000,"Construction of Open well at ganesh nagar under MLACDS Scheme in Div-182, U-38, Z-13.",MLACDS,13,2020-21,2021-22 BR/2020-21/0660,Road Cut,Completed,BR-Bus Route Roads,183,964000,"Restoration of Roadcut made by OFC Operators at Various Streets in Dn-183 & 184, Zone-14",Deposit Works,14,2020-21,2020-21 NP/2020-21/0631,Buildings,Completed,NP-PERUNGUDI,183,533000,"IMPROVEMENTS OF ECR AMMA UNAVAGAM & M.G.R.NAGAR AMMA UNAVAGAM IN DIVISION-183,UNIT-41,ZONE-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/1060,Roads,Completed,NP-PERUNGUDI,183,5916000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT SWAMINATHAN NAGAR 3RD STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2020-21,2021-22 NP/2020-21/2158,Roads,Completed,NP-PERUNGUDI,183,186500,"RELAYING THE BITUMINIOUS ROAD WITH PAVER FINISH AT VENKATESAPURAM 1st STREET IN DIVISION-183,UNIT - 41,ZONE - 14.",Grants,14,2020-21,2020-21 NP/2020-21/2166,Roads,Completed,NP-PERUNGUDI,183,224000,"RELAYING THE BITUMINIOUS ROAD WITH PAVER FINISH AT VENKATESAPURAM 2nd STREET IN DIVISION -183,UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/2167,Roads,Completed,NP-PERUNGUDI,183,396000,"RELAYING THE BITUMINIOUS ROAD WITH PAVER FINISH AT VENKATESAPURAM 5th STREET IN DIVISION -183,UNIT-41,ZONE -14.",Grants,14,2020-21,2020-21 NP/2020-21/2168,Roads,Completed,NP-PERUNGUDI,183,34000,"RELAYING THE BITUMINIOUS ROAD WITH PAVER FINISH AT VENKATESAPURAM 3rd STREET IN DIVISION -183, UNIT - 41, ZONE - 14.",Grants,14,2020-21,2020-21 NP/2020-21/2169,Roads,Completed,NP-PERUNGUDI,183,52000,"RELAYING THE BITUMINIOUS ROAD WITH PAVER FINISH AT SWAMINATHAN NAGAR 2ND STREET IN DIVISION -183, UNIT - 41, ZONE - 14.",Grants,14,2020-21,2020-21 NP/2020-21/2170,Roads,Completed,NP-PERUNGUDI,183,4990000,"RELAYING THE BITUMINIOUS ROAD WITH PAVER FINISH AT VENKATESAPURAM MAIN ROAD IN DIVISION -183, UNIT - 41, ZONE - 14.",Grants,14,2020-21,2020-21 NP/2020-21/3958,Storm Water Drain,Completed,NP-PERUNGUDI,183,272000,"Desilting for Storm Water Drains and Side Drains in Div-183,Unit-41,Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/3961,Storm Water Drain,Completed,NP-PERUNGUDI,183,243000,"Minor repair Works for Side Drain and Storm water drain at Various streets in Dn -183 Unit- 41, Zone - 14",Own Sources,14,2020-21,2021-22 NP/2020-21/7128,Buildings,Completed,NP-PERUNGUDI,183,250000,"IMPROVEMENTS TO THE EXISTING CEMENT CONCRETE ROAD AT ANNA STREET IN DIVISION-183, UNIT-41, ZONE-14.",Grants,14,2020-21,2021-22 NP/2020-21/7668,Storm Water Drain,Completed,NP-PERUNGUDI,183,514000,"PROVIDING 600mm dia HUME PIPE LAYING AT NEHRU NAGAR 13th STREET (FROM NEHRU NAGAR 13th STREET TO NEHURU NAGAR 14th STREET) IN FLOOD WORK DIVISION-183, UNIT-41, ZONE-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/8222,Roads,Completed,NP-PERUNGUDI,183,200000,"Repairs and Maintenance to Dn Office kuppam Beach PC and Venkateshwara nagar 7th street,Saminathan 5th street and Venkatesapuram 7th street etc, in Div-183,U41,Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/9683,Buildings,Completed,NP-PERUNGUDI,183,143000,"Converting room into AMMA MINI CLINIC inside Dn 183 Office Complex in DN-183, UNIT-41,ZONE-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/0186,Roads,Completed,NP-PERUNGUDI,184,113000,"RELAYING OF CEMENT CONCRETE ROAD AT PILLAIYAR KOIL 2ND LANE STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0187,Roads,Completed,NP-PERUNGUDI,184,113000,"RELAYING OF CEMENT CONCRETE ROAD AT PILLAIYAR KOIL 3RD LANE STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0188,Roads,Completed,NP-PERUNGUDI,184,113000,"RELAYING OF CEMENT CONCRETE ROAD AT PILLAIYAR KOIL 4TH LANE STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0189,Roads,Completed,NP-PERUNGUDI,184,168000,"RELAYING OF CEMENT CONCRETE ROAD AT SASTHIRI STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0196,Roads,Completed,NP-PERUNGUDI,184,200000,"RELAYING OF CEMENT CONCRETE ROAD AT BHARADHIYAR STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0198,Roads,Completed,NP-PERUNGUDI,184,391000,"RELAYING OF CEMENT CONCRETE ROAD AT GOVINDASAMY NAGAR 3RD STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0199,Roads,Completed,NP-PERUNGUDI,184,268000,"RELAYING OF CEMENT CONCRETE ROAD AT GANDHI STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0234,Roads,Completed,NP-PERUNGUDI,184,368000,"RELAYING OF CEMENT CONCRETE ROAD AT VIVEGANANDHAR STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0236,Roads,Completed,NP-PERUNGUDI,184,246000,"RELAYING OF CEMENT CONCRETE ROAD AT BALAGANGADHAR STREET STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0238,Roads,Completed,NP-PERUNGUDI,184,234000,"RELAYING OF CEMENT CONCRETE ROAD AT KAMBAR STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0239,Roads,Completed,NP-PERUNGUDI,184,201000,"RELAYING OF CEMENT CONCRETE ROAD AT MANIMEGALAI STREET STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0240,Roads,Completed,NP-PERUNGUDI,184,280000,"RELAYING OF CEMENT CONCRETE ROAD AT KANNAGI STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0242,Roads,Completed,NP-PERUNGUDI,184,179000,"RELAYING OF CEMENT CONCRETE ROAD AT AVVAIYAR STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0369,Roads,Completed,NP-PERUNGUDI,184,931000,"RELAYING OF B.T ROAD AT MAYANASALAI SCHOOL ROAD IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0375,Roads,Completed,NP-PERUNGUDI,184,538000,"RELAYING OF B.T ROAD AT CBI COLONY 5TH CROSS STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0376,Roads,Completed,NP-PERUNGUDI,184,175000,"RELAYING OF B.T ROAD AT CBI COLONY 6TH CROSS STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0377,Roads,Completed,NP-PERUNGUDI,184,175000,"RELAYING OF B.T ROAD AT CBI COLONY 7TH CROSS STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0379,Roads,Completed,NP-PERUNGUDI,184,231000,"RELAYING OF B.T ROAD AT TELEPHONE NAGAR 8TH STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0380,Roads,Completed,NP-PERUNGUDI,184,428000,"RELAYING OF B.T ROAD AT SAI AYUSH POOJA MAIN ROAD IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0381,Roads,Completed,NP-PERUNGUDI,184,516000,"FORMATION OF SAI AYUSH POOJA 4TH CROSS STREET IN DIVISION-184, UNIT-41, ZONE-14.",Grants,14,2020-21,2020-21 NP/2020-21/0832,Buildings,Completed,NP-PERUNGUDI,184,762500,"Maintenance of Gasifier Crematorium in Hindu Burial Ground at School Road in Div-184, Unit-41, Zone-14.",Own Sources,14,2020-21,2021-22 NP/2020-21/3965,Storm Water Drain,Completed,NP-PERUNGUDI,184,266000,"Desilting of Storm Water Drain and Side Drain in Div -184, Unit -41, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3966,Storm Water Drain,Completed,NP-PERUNGUDI,184,267000,"Minor Repair Works for Storm Water Drain and Side Drain in Div -184, Unit -41, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/4170,Buildings,Completed,NP-PERUNGUDI,184,200000,"Improvements to Division Office and Other Maintenance Work in Division - 184, Unit-41, Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/4907,Storm Water Drain,Completed,NP-PERUNGUDI,184,800000,"Providing 600 mm dia Hume pipe connections at Telephone Nagar Main road in Div - 184, U - 41, Z - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/4975,Buildings,Completed,NP-PERUNGUDI,184,713000,"Repairs and Improvements works in Urban Community Health Centre, 100 Bed Hospital, Perungudi in Div - 184, U - 41, Z - 14",Own Sources,14,2020-21,2021-22 NP/2020-21/6742,Roads,Completed,NP-PERUNGUDI,184,270000,"Relaying of CC Road at Kothanda raman nagar main road in Division-184,Unit-41,Zone-14.",Grants,14,2020-21,2021-22 NP/2020-21/6746,Roads,Completed,NP-PERUNGUDI,184,60000,"Relaying of CC Road at kothanda raman nagar 1st cross street in Division-184,Unit-41,Zone-14.",Grants,14,2020-21,2021-22 NP/2020-21/6748,Roads,Completed,NP-PERUNGUDI,184,642000,"Relaying of CC Road at kothanda raman nagar 2nd cross street in Division-184,Unit-41,Zone-14.",Grants,14,2020-21,2021-22 NP/2020-21/6749,Roads,Completed,NP-PERUNGUDI,184,831000,"Relaying of CC Road at kothanda raman nagar 3rd cross street in Division-184,Unit-41,Zone-14.",Grants,14,2020-21,2021-22 NP/2020-21/6750,Roads,Completed,NP-PERUNGUDI,184,531000,"Relaying of CC Road at kothanda raman nagar 4th cross street in Division-184,Unit-41,Zone-14.",Grants,14,2020-21,2021-22 NP/2020-21/6774,Roads,Completed,NP-PERUNGUDI,184,627000,"Relaying of CC Road at Govindasamy Nagar 4st street in Division-184,Unit-41,Zone-14.",Grants,14,2020-21,2021-22 NP/2020-21/6775,Roads,Completed,NP-PERUNGUDI,184,722000,"Relaying of CC Road at Govindasamy nagar 6th street in Division-184,Unit-41,Zone-14.",Grants,14,2020-21,2021-22 NP/2020-21/8080,Buildings,Completed,NP-PERUNGUDI,184,500000,"Construction of Precast Micro Composting Centre and Nano Compost Yard and Material Recovery Facility at Division Office in Div -184, U-41, Z-14",Own Sources,14,2020-21,2020-21 BR/2020-21/0661,Road Cut,Completed,BR-Bus Route Roads,185,932000,"Restoration of Roadcut made by OFC Operators at Various Streets in Dn-185, Zone-14",Deposit Works,14,2020-21,2020-21 BR/2020-21/0662,Road Cut,Completed,BR-Bus Route Roads,185,964000,"Restoration of Roadcut made by OFC Operators at Various Streets in Dn- 185 & 186, Zone-14",Deposit Works,14,2020-21,2020-21 NP/2020-21/2130,Roads,Completed,NP-PERUNGUDI,185,164000,Formation of BT Road at Greenways Salai (Jaishankar Nagar) in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/2132,Roads,Completed,NP-PERUNGUDI,185,1383000,Strengthening and Relaying of BT Road at Jaishankar Nagar Main Road in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/2134,Roads,Completed,NP-PERUNGUDI,185,774000,Strengthening and Relaying of BT Road at Jaishankar Nagar 2nd Street in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/2135,Roads,Completed,NP-PERUNGUDI,185,411000,Relaying of BT Road at Kanthasamy Nagar 5th Street in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/2137,Roads,Completed,NP-PERUNGUDI,185,1322000,Strengthening and Relaying of BT Road at Estate Main Road in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/2139,Roads,Completed,NP-PERUNGUDI,185,2549000,Strengthening and Relaying of BT Road at Kamaraj Salai in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/2140,Roads,Completed,NP-PERUNGUDI,185,2057000,Formation of BT Road at Pachaiappan Main Street in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/2144,Roads,Completed,NP-PERUNGUDI,185,2371000,Strengthening and Relaying of BT Road at Periyar Salai in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/3665,Roads,Completed,NP-PERUNGUDI,185,200000,"Improvements Works and Providing for WMM at Various Streets in Division - 185, Unit-41, Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/3709,Storm Water Drain,Completed,NP-PERUNGUDI,185,433000,"Improvements to Side Drain at N.S.Krishnan salai in Div - 185, Unit -41, Zone -14.",Own Sources,14,2020-21,2020-21 NP/2020-21/3967,Storm Water Drain,Completed,NP-PERUNGUDI,185,343000,"Minor Repair Works for Storm Water Drain and Side Drain in Div -185, Unit -41, Zone - 14",Own Sources,14,2020-21,2021-22 NP/2020-21/3969,Storm Water Drain,Completed,NP-PERUNGUDI,185,230000,"Desilting of Storm Water Drain and Side Drain in Div -185, Unit -41, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/5471,Roads,Completed,NP-PERUNGUDI,185,1066000,Relaying of BT Road at Veeramani Salai in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/5472,Roads,Completed,NP-PERUNGUDI,185,240000,Strengthening and Relaying of BT Road at Kanthasamy Nagar 1st Street (Part) in Dn-185 U-41 Z-14,Grants,14,2020-21,2021-22 NP/2020-21/7930,Storm Water Drain,Completed,NP-PERUNGUDI,185,97000,"Providing of Rain Water Harvesting at Suburayan Street in Dn-185, Unit-41, Zone-14",Own Sources,14,2020-21,2021-22 NP/2020-21/8084,Buildings,Completed,NP-PERUNGUDI,185,1114000,"Providing 600mm Dia Hume Pipe Laying at Jai Shankar Nagar 2nd Cross Street in Division-185,Unit-41,Zone-14.",Own Sources,14,2020-21,2021-22 NP/2020-21/8087,Roads,Completed,NP-PERUNGUDI,185,343000,"Providing 600mm Dia Hume Pipe Laying at JP Narayanasamy Street in Division-185,Unit-41,Zone-14.",Own Sources,14,2020-21,2021-22 NP/2020-21/9814,Buildings,Completed,NP-PERUNGUDI,185,156000,"Converting Room into MINI CLINIC Palavakkam Beach Road in DN-185, UNIT-41,ZONE-14.",Grants,14,2020-21,2020-21 BR/2020-21/0657,Road Cut,Completed,BR-Bus Route Roads,186,964000,"Restoration of Roadcut made by OFC Operators at Various Streets in Dn-186, Zone-14",Deposit Works,14,2020-21,2020-21 BR/2020-21/2384,Road Cut,Completed,BR-Bus Route Roads,186,959000,"Restoration of roadcut made by Service department (OFC) at various roads in division 186 ,Zone 14",Deposit Works,14,2020-21,2020-21 NP/2020-21/0221,Roads,Completed,NP-PERUNGUDI,186,1114000,"Relatying of BT road at Panchayat main road (part) in Dn-186,Unit-42,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0222,Roads,Completed,NP-PERUNGUDI,186,708000,"Relatying of BT road at Pillayar koil 2nd cross street in Dn-186,Unit-42,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0224,Roads,Completed,NP-PERUNGUDI,186,531000,"Relaying of BT road at Kuruji nagar 4th cross street in Dn-186,Unit-42,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0226,Roads,Completed,NP-PERUNGUDI,186,711000,"Relaying of BT road at Rajalakshmi Avenue main road at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0232,Roads,Completed,NP-PERUNGUDI,186,1683000,"Relaying of BT road at Thirumalai nagar anex 1st main road at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0233,Roads,Completed,NP-PERUNGUDI,186,1636000,"Relaying of BT road at Thirumalai nagar anex 2nd main road at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0235,Roads,Completed,NP-PERUNGUDI,186,986000,"Relaying of BT road at Thirumalai nagar anex 3rd main road at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0237,Roads,Completed,NP-PERUNGUDI,186,513000,"Relaying of BT road at Thirumalai nagar anex 3rd cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0254,Roads,Completed,NP-PERUNGUDI,186,118000,"Relaying of BT road at Thirumalai nagar anex 5th cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0256,Roads,Completed,NP-PERUNGUDI,186,203000,"Relaying of BT road at Thirumalai nagar anex 6th cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0258,Roads,Completed,NP-PERUNGUDI,186,965000,"Relaying of BT road at Thirumalai nagar anex pathmavathy avenue at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0260,Roads,Completed,NP-PERUNGUDI,186,252000,"Relaying of BT road at school street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0262,Roads,Completed,NP-PERUNGUDI,186,440000,"Relaying of BT road at Panchayat main road 2nd cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0267,Roads,Completed,NP-PERUNGUDI,186,700000,"Relaying of BT road at Rajiv nagar 1st cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0268,Roads,Completed,NP-PERUNGUDI,186,83000,"Relaying of BT road at Janakiraman 1st cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0270,Roads,Completed,NP-PERUNGUDI,186,296000,"Relaying of BT road at Adhiyaman street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0272,Roads,Completed,NP-PERUNGUDI,186,221000,"Relaying of BT road at Siva vishnu street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0718,Roads,Completed,NP-PERUNGUDI,186,663000,"Relaying of BT road at Pillayar koil main road south at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0720,Roads,Completed,NP-PERUNGUDI,186,1807000,"Relaying of BT road at Veerasamy street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0721,Roads,Completed,NP-PERUNGUDI,186,179000,"Relaying of BT road at Kurinji nagar 2nd street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0722,Roads,Completed,NP-PERUNGUDI,186,280000,"Relaying of BT road at Kurinji nagar 5th cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0723,Roads,Completed,NP-PERUNGUDI,186,500000,"Relaying of BT road at Kurinji nagar 6Th cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0724,Roads,Completed,NP-PERUNGUDI,186,1400000,"Relaying of BT road at Kamarajar nagar 2nd main road at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/0725,Roads,Completed,NP-PERUNGUDI,186,83000,"Relaying of BT road at Rajalakshmi avenue 1st cross street at Dn-186,Unit-41,zone-14",Grants,14,2020-21,2020-21 NP/2020-21/10459,Buildings,Completed,NP-PERUNGUDI,186,359000,"Improvement Works to Multi Purpose Hall for Mini Clinic at Panchayath Main Road in Dn-186,Unit-41,Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/10718,Buildings,Completed,NP-PERUNGUDI,186,4589000,"PROPOSED CONSTRUCTION OF SECONDARY COLLECTION CENTRE AT PERUNGUDI DUMPING GROUND IN DIVISION-186,UNIT-41,ZONE-14.",Own Sources,14,2020-21,2021-22 NP/2020-21/3660,Buildings,Completed,NP-PERUNGUDI,186,200000,"Improvements to Division Office and Other Maintanence Work in Division - 186, Unit-41, Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/3970,Storm Water Drain,Completed,NP-PERUNGUDI,186,208000,"Desilting of Storm Water Drain and Side Drain in Div -186, Unit -41, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3972,Storm Water Drain,Completed,NP-PERUNGUDI,186,260000,"Minor Repair Works for Storm Water Drain and Side Drain in Div -186, Unit -41, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/9374,Roads,Completed,NP-PERUNGUDI,186,753000,"Providing 600 mm dia Hume pipe at Mahakavi Bharadhiyar Street(OMR Main Road) in Div - 186, Unit - 41, Zone - 14.",Own Sources,14,2020-21,2021-22 Q/2020-21/5266,Buildings,Completed,Q-Solid Waste Management,186,990000,Demolition and Reconstruction of Existing damaged Compound wall for Garden Waste Processing Plant (south side) at Perungudi dumping ground in Div-186 Unit-41 Zone-14.,Own Sources,14,2020-21,2021-22 NP/2020-21/0048,Roads,Completed,NP-PERUNGUDI,187,172000,"FORMING AND LAYING OF B.T ROAD AT KARTHIKEYAPURAM 3RD STREET 3RD CROSS STREET IN DIV - 187,UNIT- 42, ZONE-14.",Grants,14,2020-21,2021-22 NP/2020-21/0050,Roads,Completed,NP-PERUNGUDI,187,132000,"PARTLY RELAYING THE ROAD AT KARTHIKAYAPURAM 11TH 1ST CROSS STREET IN DIV-187, UNIT 42, ZONE 14.",Grants,14,2020-21,2021-22 NP/2020-21/0053,Roads,Completed,NP-PERUNGUDI,187,292000,"RELAYING OF BT ROAD AT DEIVANAI NAGAR 4TH STREET IN DIV-187, UNIT-42, ZONE-14.",Grants,14,2020-21,2021-22 NP/2020-21/0055,Roads,Completed,NP-PERUNGUDI,187,350000,"PARTLY RELAYING OF BT ROAD AT ESWARAN KOIL MAIN ROAD IN DIV-187, UNIT-42, ZONE-14.",Grants,14,2020-21,2021-22 NP/2020-21/10079,Buildings,Completed,NP-PERUNGUDI,187,481000,"Converting room into MINI CLINIC inside the Store room of Amma unavagam at Lake View Main Road in DN-187, UNIT-42,ZONE-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/3949,Storm Water Drain,Completed,NP-PERUNGUDI,187,142000,"Desilting of Storm Water Drain and Side drain in div -187, Unit - 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3951,Storm Water Drain,Completed,NP-PERUNGUDI,187,109000,"Minor Repair Works for Storm Water Drain and Side drain in div -187, Unit - 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/9459,Buildings,Completed,NP-PERUNGUDI,187,199000,"Maintenance works for 187 Division office and etc in Div - 187, U - 42, Z - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/0362,Buildings,Completed,NP-PERUNGUDI,188,212000,"Supply and Fixing of 1 HP Motor at Community Hall, 1.5HP Motor at Division - 188 Office and Provision of 4 Nos. of 4 tap wash basin fitted wherever necessary and Rental of 2 tap wash basin provided wherever necessary in Unit-42, Unit-41 & Unit-43, Zone -14",Own Sources,14,2020-21,2020-21 NP/2020-21/0426,Roads,Completed,NP-PERUNGUDI,188,23000,"PARTLY RELAYING OF B.T. ROAD AT LIC NAGAR 5TH STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0427,Roads,Completed,NP-PERUNGUDI,188,94000,"PARTLY RELAYING OF B.T.ROAD AT SADASIVAM NAGAR 4TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0428,Roads,Completed,NP-PERUNGUDI,188,297000,"PARTLY RELAYING OF ROAD AT MAHALAKSHMI NAGAR MAIN ROAD BHARATHIAR SALAI IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0429,Roads,Completed,NP-PERUNGUDI,188,51000,"PARTLY RELAYING OF B.T. ROAD AT KRISHNAVENIAMMAL NAGAR MAIN ROAD IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0430,Roads,Completed,NP-PERUNGUDI,188,184000,"PARTLY RELAYING OF B.T. ROAD AT ANNA NAGAR 9TH STREET (PART) IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0431,Roads,Completed,NP-PERUNGUDI,188,165000,"PARTLY RELAYING OF B.T. ROAD AT RAM NAGAR 6TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0432,Roads,Completed,NP-PERUNGUDI,188,93000,"PARTLY RELAYING OF B.T. ROAD AT RAJAJI NAGAR 3RD STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0433,Roads,Completed,NP-PERUNGUDI,188,93000,"PARTLY RELAYING OF B.T. ROAD AT RAJESH NAGAR 3RD MAIN ROAD IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0438,Roads,Completed,NP-PERUNGUDI,188,269000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK I MAIN ROAD 1ST CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0439,Roads,Completed,NP-PERUNGUDI,188,513000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 5TH STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0440,Roads,Completed,NP-PERUNGUDI,188,287000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 2ND CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0441,Roads,Completed,NP-PERUNGUDI,188,281000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 3RD CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0442,Roads,Completed,NP-PERUNGUDI,188,285000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 4TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0446,Roads,Completed,NP-PERUNGUDI,188,671000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 5TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0447,Roads,Completed,NP-PERUNGUDI,188,543000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 6TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0448,Roads,Completed,NP-PERUNGUDI,188,88000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 7TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0450,Roads,Completed,NP-PERUNGUDI,188,85000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 8TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0451,Roads,Completed,NP-PERUNGUDI,188,88000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 9TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0452,Roads,Completed,NP-PERUNGUDI,188,91000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 10TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0453,Roads,Completed,NP-PERUNGUDI,188,94000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 1ST MAIN ROAD 11TH CROSS STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0454,Roads,Completed,NP-PERUNGUDI,188,165000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 1ST STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0456,Roads,Completed,NP-PERUNGUDI,188,171000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 2ND STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0457,Roads,Completed,NP-PERUNGUDI,188,168000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 3RD STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0458,Roads,Completed,NP-PERUNGUDI,188,173000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 4TH STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0459,Roads,Completed,NP-PERUNGUDI,188,175000,"RELAYING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 2ND BLOCK 2ND MAIN ROAD 1ST CROSS 5TH STREET IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/0460,Roads,Completed,NP-PERUNGUDI,188,989000,"FORMING OF CEMENT CONCRETE ROAD AT MYLLAI BALAJI NAGAR 3RD BLOCK CANAL ROAD IN DIV.188, UNIT-42, ZONE-14",Grants,14,2020-21,2020-21 NP/2020-21/1011,Roads,Completed,NP-PERUNGUDI,188,121000,"COVID-19, Providing 3 Nos. of Sintex Tank 500 Litres capacity with 12 Nos. of Stainless steel wash basin outlet connected to choke pit for hand washing arrangements in slum for prevention and control of COVID-19 at Myllai Balaji Nagar 1st & 2nd Block (Common Near Canal), Myllai Balaji Nagar 3rd Block (1st Main Road) and 4th Block (Near Canal Side) in Division-188, Unit-42, Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/3948,Storm Water Drain,Completed,NP-PERUNGUDI,188,589000,"Minor repair Works for Side Drain and Storm water drain at Various streets in Dn -188 Unit- 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3952,Storm Water Drain,Completed,NP-PERUNGUDI,188,486000,"Desilting for Storm Water Drains and Side Drains in Div-188,Unit-42,Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/4423,Storm Water Drain,Completed,NP-PERUNGUDI,188,588000,"Providing 600MM Hume pipe at Ram nagar 17th street, Kuberan nagar 3rd street road crossing and Ram nagar 13th street in Div -188, unit - 42, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/4424,Storm Water Drain,Completed,NP-PERUNGUDI,188,981000,"Improvements works for Storm water Drain at Ram nagar 8th cross street in Div - 188, U - 42, Z - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/4425,Storm Water Drain,Completed,NP-PERUNGUDI,188,337000,"Engaging of Pocline machine for removal of hyacinth and silt from the existing canals at (Myllai balaji nagar 1st Block and 4th Block) and Cutting katcha drain inside of Old Dumping ground in Div - 188, U - 42, Z - 14",Own Sources,14,2020-21,2021-22 NP/2020-21/4426,Storm Water Drain,Completed,NP-PERUNGUDI,188,527000,"Engaging Float with Pocline for Jungle Cleaning inside the Marsh Land from Kaiveli Junction to kamatchi Hospital in Div - 188, U - 42, Z - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/4591,Storm Water Drain,Completed,NP-PERUNGUDI,188,316000,"Providing 600MM Hume pipe at Rajesh nagar 5th main road and ram nagar 11th main road in Div - 188, U - 42, Z - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/9066,Buildings,Completed,NP-PERUNGUDI,188,595000,"Construction of store room for AE, SI and CI and Providing aluminium Cupboard in AE office room in Div-188, Unit-42, Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/9161,Buildings,Completed,NP-PERUNGUDI,188,199000,"Maintenance works for 188 Division, Blaji nagar 2 nd block School, PC, Community Hall etc in Div - 188, U - 42, Z - 14",Own Sources,14,2020-21,2021-22 NP/2020-21/9691,Buildings,Completed,NP-PERUNGUDI,188,526000,"Converting room into MINI CLINIC inside Anganwadi at Balaji Nagar 2 nd Block in DN-188, UNIT-42,ZONE-14.",Own Sources,14,2020-21,2020-21 Q/2020-21/2223,Buildings,Completed,Q-Solid Waste Management,188,2495000,"Construction of Platform for erecting bailing machine at pallikkaranai dumping ground in Dn-188, Zone-14",Own Sources,14,2020-21,2020-21 Q/2020-21/3719,Buildings,Completed,Q-Solid Waste Management,188,4550000,"Providing shed for Bailing machine Erected at Pallikaranai Dumping ground in dn-188, zone14.",Own Sources,14,2020-21,2020-21 Q/2020-21/4519,Buildings,Completed,Q-Solid Waste Management,188,1450000,"Providing sidewalls, weldmesh, sintex water tank and ramp arrangements for Bailing machine erected at pallikaranai dumping ground in Dn-188, Zone-14.",Own Sources,14,2020-21,2021-22 NP/2020-21/0887,Storm Water Drain,Completed,NP-PERUNGUDI,189,38500,"COVID-19, Providing sintex tank 500 ltrs capacity with 3 nos steel wash basin outlet connected to choke pit for hand washing arrangements in slum for prevention and control of COVID 19 at Anna MGR Nagar North side in dn-189, Unit-43 Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/0888,Storm Water Drain,Completed,NP-PERUNGUDI,189,39000,"Covid-19, Providing sintex tank 500 ltrs capacity with 3steel wash basin outlet connected to SWD for hand washing arrangements in Slum for prevention and control of COVID 19 at Kamatchiamman nagar in dn-189, Unit-43 Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/2117,Buildings,Completed,NP-PERUNGUDI,189,200000,"Repairs and Maintenance to Dn Office ,Amma Unavagam Toilet, Community Hall Syndigate Cony Bank road culvert, Thulukanathamman Koil street Culvert etc in Div - 189, U - 43, Z - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3953,Storm Water Drain,Completed,NP-PERUNGUDI,189,354000,"Minor Repair Works for Storm Water Drain and Side drain in div -189 Unit - 43, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3954,Storm Water Drain,Completed,NP-PERUNGUDI,189,104000,"Desilting of Storm Water Drain and Side drain in div -189 Unit - 43, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/4183,Roads,Completed,NP-PERUNGUDI,189,878000,"Providing and Laying 600mm diameter Hume pipe at Sai Balaji Nagar Part-III and various streets in Dn -189,U-43,Z-14",Own Sources,14,2020-21,2020-21 NP/2020-21/9841,Buildings,Completed,NP-PERUNGUDI,189,422000,"Conversion of chapathi centre to Amma mini clinic with improvement works at kamakotti nagar 6th cross street north in dn-189,unit-43,zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/0095,Roads,Completed,NP-PERUNGUDI,190,395000,"Roadcut and Relaying at BT Road Kannabiran Koil Cross Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0109,Roads,Completed,NP-PERUNGUDI,190,624000,"Roadcut and Relaying at BT Road Padasalai Street in Dn -190, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0120,Roads,Completed,NP-PERUNGUDI,190,580000,"Roadcut and Relaying at BT Road Rajiv Gandhi Cross Lanes in Dn -190, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0121,Roads,Completed,NP-PERUNGUDI,190,400000,"Roadcut and Relaying at BT Road Rajiv Gandhi St Extn., in Dn -190, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0122,Roads,Completed,NP-PERUNGUDI,190,260000,"Roadcut and Relaying at BT Road Rajiv Gandhi St Extn., 1st Cross St in Dn -190, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0176,Roads,Completed,NP-PERUNGUDI,190,959000,"Roadcut and Relaying of BT Road at Well Approach Road in Dn -190, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0300,Roads,Completed,NP-PERUNGUDI,190,248000,"Roadcut and Relaying at BT Road Well Salai 2nd Cross St in Dn -190, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0896,Storm Water Drain,Completed,NP-PERUNGUDI,190,49500,"Covid-19,Providing sintex tank 1000 ltrs capacity with 4 nos steel wash basin connected to choke pit for hand washing arrangements in slum for prevention and control of COVID 19 at Kovalan nagar in dn-190, Unit-43 Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/0897,Storm Water Drain,Completed,NP-PERUNGUDI,190,35500,"Covid-19, Providing sintex tank 1000 ltrs capacity with 3 nos steel wash basin connected to choke pit for hand washing arrangements in slum for prevention and control of COVID 19 at Kannabiran koil street in dn-190, Unit-43 Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/0898,Storm Water Drain,Completed,NP-PERUNGUDI,190,38500,"Covid-19, Providing sintex tank 500 ltrs capacity with 3 nos steel wash basin outlet connected to choke pit for hand washing arrangements in slum for prevention and control of COVID 19 at Bharathidasan street in dn-190, Unit-43 Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/6023,Buildings,Completed,NP-PERUNGUDI,190,563000,"Providing and Laying for Hume Pipe at Pasumpon Nagar and Various Street in Dn-190,U-43,Z-14",Own Sources,14,2020-21,2020-21 NP/2020-21/9681,Buildings,Completed,NP-PERUNGUDI,190,610000,"Converting and Providing Lite Roof to the Old Amma Unavagam Building to Amma Mini Clinic Inside Division Office Compound In Dn-190, Unit-43, ZONE-14",Own Sources,14,2020-21,2020-21 NP/2020-21/0338,Roads,Completed,NP-PERUNGUDI,191,854000,"Road cut restoration and Relaying of CC Road at Indhira Gandhi Street in Dn -191, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0348,Roads,Completed,NP-PERUNGUDI,191,3768000,"Road cut restoration and Relaying at Nesavalar Nagar Periyar Salai in Dn -191, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0356,Roads,Completed,NP-PERUNGUDI,191,892000,"Road cut restoration and Partly Relaying at Jayachandiran Nagar 1st Main Road(Part) in Dn -191, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0357,Roads,Completed,NP-PERUNGUDI,191,724000,"Road cut restoration and Partly Relaying at Jayachandiran Nagar 2nd Main Road(Part) in Dn -191, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0358,Roads,Completed,NP-PERUNGUDI,191,436000,"Road cut restoration and Partly Relaying at Jayachandiran Nagar 6th Main Road(Part) in Dn -191, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0359,Roads,Completed,NP-PERUNGUDI,191,750000,"Road cut restoration and Partly Relaying of CC Road at Jayachandiran Nagar 4th Main Road(Part) in Dn -191, Unit- 43, Zone- XIV",Grants,14,2020-21,2021-22 NP/2020-21/0889,Storm Water Drain,Completed,NP-PERUNGUDI,191,44500,"Covid-19, Providing sintex tank 500 ltrs capacity with 4 nos steel wash basin connected to choke pit for hand washing arrangements in slum for prevention and control of COVID 19 at Anjaneyar nagar in dn-191, Unit-43 Zone-14",Own Sources,14,2020-21,2020-21 NP/2020-21/0891,Storm Water Drain,Completed,NP-PERUNGUDI,191,38500,"Covid-19, Providing sintex tank 500 ltrs capacity with 3 nos steel wash basin outlet connected to choke pit for hand washing arrangements in slum for prevention and control of COVID 19 at Pallavan nagar in dn-191, Unit-43 Zone-14.",Own Sources,14,2020-21,2020-21 NP/2020-21/3956,Storm Water Drain,Completed,NP-PERUNGUDI,191,227000,"Desilting of Storm Water Drain and Side drain in div -191 Unit - 43, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/3957,Storm Water Drain,Completed,NP-PERUNGUDI,191,247000,"Minor Repair Works for Storm Water Drain and Side drain in div -191 Unit - 43, Zone - 14",Own Sources,14,2020-21,2020-21 NP/2020-21/9428,Buildings,Completed,NP-PERUNGUDI,191,510000,"Proposed additions to the existing building to convert into a AMMA MINI CLINIC at Veerathamman koil street in DN-191, UNIT-43,ZONE-14.",Own Sources,14,2020-21,2020-21 BR/2020-21/1327,Road Cut,Completed,BR-Bus Route Roads,192,910000,"Restoration of Roadcut(OFC) at Various Streets in Dn-192 & 193,Unit - 44 &45 ,Zone - 15",Deposit Works,15,2020-21,2020-21 NQ/2020-21/2753,Buildings,Completed,NQ-SHOZHINGANALLUR,192,450000,"IMPROVEMENT AND REPAIR WORK FOR DIVISION OFFICE, UPHC AND FISH MARKET AT NELANGARAI IN DIV-192, U-44, Z-15",Own Sources,15,2020-21,2020-21 NQ/2020-21/2822,Buildings,Completed,NQ-SHOZHINGANALLUR,192,475000,"IMPROVEMENT AND REPAIR WORK FOR AMMAUNAVAGAM AT NELANGARAI IN DIV-192, U-44, Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/3982,Roads,Completed,NQ-SHOZHINGANALLUR,192,262000,"Desilting SWD AND Side Drain At Various streets in Div-192, U-44 Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/3983,Roads,Completed,NQ-SHOZHINGANALLUR,192,597000,"IMPROVEMENT WORK TO SWD AND SIDE DRAIN AT VARIOUS STREET AND CHINNA NEELANGARAI KUPPAM PRECASE SALB WORK IN DIN-192, U-44, Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/6959,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,192,420000,"Desilting and refixing of existing underground cc hume pipe at chinna neelangarai kuppam beach road in Dn-192, U-44, Zone-15",Own Sources,15,2020-21,2020-21 BR/2020-21/2775,Road Cut,Completed,BR-Bus Route Roads,193,975000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-193,U-45 Zone XV",Deposit Works,15,2020-21,2020-21 BR/2020-21/2776,Road Cut,Completed,BR-Bus Route Roads,193,942000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-193 & 194 ,U-45 Zone XV",Deposit Works,15,2020-21,2020-21 NQ/2020-21/2813,Buildings,Completed,NQ-SHOZHINGANALLUR,193,889000,"Providing Platform for infront of UPHC at Rajiv Gndhi Salai (OMR) in Div-193, U-45, Z-15",Own Sources,15,2020-21,2020-21 NQ/2020-21/3959,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,193,314000,"Desilting At Various drains at various street in DIV-193, U-45 , Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/3962,Buildings,Completed,NQ-SHOZHINGANALLUR,193,274000,"Minor repair work at Mahalaxmi street in Dn-193, U-45 Z-15",Own Sources,15,2020-21,2021-22 BR/2020-21/2777,Road Cut,Completed,BR-Bus Route Roads,194,959000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-194 &195 ,U-45 Zone XV",Deposit Works,15,2020-21,2020-21 BR/2020-21/2778,Road Cut,Completed,BR-Bus Route Roads,194,959000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-194,U-45 Zone XV",Deposit Works,15,2020-21,2020-21 BR/2020-21/2779,Road Cut,Completed,BR-Bus Route Roads,194,942000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-194,U-45 Zone XV",Deposit Works,15,2020-21,2020-21 D/2020-21/7382,Storm Water Drain,Completed,D-Storm Water Drains,194,10480000,"Construction of storm water drain of size 1200 x 1200mm along Secretariate Colony 3rd Main Road from existing canal to Secretariate Colony 4th Main Road Dn- 194,Zone - XV.",Own Sources,15,2020-21,2021-22 D/2020-21/7396,Storm Water Drain,Completed,D-Storm Water Drains,194,17520000,"Construction of storm water drain of size 1500 x 1500mm along Secretariate Colony 4th Main Road from Secretariate Colony 3rd Main Road to existing drain near Secretariate Colony park Dn- 194,Zone - XV.",Own Sources,15,2020-21,2021-22 NQ/2020-21/3986,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,275000,"Improvements to minor repair work at pillaiyar koil street in Dn-194, U-45 Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/3994,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,194,306000,"Desilting of storm water drain and side drain at various street in Dn-194, U-45 Z-15",Own Sources,15,2020-21,2021-22 BR/2020-21/2780,Road Cut,Completed,BR-Bus Route Roads,195,959000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-195,196 and 197,U-45 Zone XV",Deposit Works,15,2020-21,2021-22 NQ/2020-21/1514,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,325000,"Desilting of Storm water Drain At Various streets in Div-195, U-45 Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/2287,Buildings,Completed,NQ-SHOZHINGANALLUR,195,4680000,"Construction of compound wall for open space reserved for school building at Ezhil Nagar ETRP Approch Road in Dn-195, U-445, Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/4469,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,195,214000,MINOR REPAIR WORKS AND MANHOLE DOOR AT VARIOUS STREETS IN DN-195,Own Sources,15,2020-21,2021-22 NQ/2020-21/5523,Buildings,Completed,NQ-SHOZHINGANALLUR,195,499000,"Construction of Precast Micro Composting Centre and Nano Conpost Yard and Material Recovery Facility at Kannagi Nagar 8th Main Road inside of Division Ofiice in Dn-195,U-45,Z-15",Own Sources,15,2020-21,2020-21 BR/2020-21/2781,Road Cut,Completed,BR-Bus Route Roads,197,975000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-197,U-45 Zone XV",Deposit Works,15,2020-21,2020-21 BR/2020-21/2782,Road Cut,Completed,BR-Bus Route Roads,197,942000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-197,U-45 Zone XV",Deposit Works,15,2020-21,2020-21 L/2020-21/1344,Electrical,Completed,L-Electrical,197,5524100,Provision of 84 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single straight bracket with 84 Nos of 40-50w watts LED fitting and 32 Nos of 6Mtr Hot Dip Zinc galvanising street lamp post with Single Arch bracket with 32 Nos of 90-120w watts LED fitting at various location in dn-198 in Zone-XV.,Grants,15,2020-21,2021-22 NQ/2020-21/2763,Buildings,Completed,NQ-SHOZHINGANALLUR,197,115400,"Improvements to Shopping complex by Providing Good earth, WMM & Attending Repair Works to Toilet In Zonal Office in Div - 197 U - 45 Zone - XV.",Own Sources,15,2020-21,2020-21 NQ/2020-21/3975,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,80000,"Attending minor repair Works For Side Drains at Various Streets in Dn-197, U-45,Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/3979,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,197,137000,Desilting of Swd and Side Drain at Various Streets In Div-197 Unit-45 Zone-15,Own Sources,15,2020-21,2021-22 NQ/2020-21/4056,Roads,Completed,NQ-SHOZHINGANALLUR,197,745000,"Providing WMM To Model School Road Extn in Div -197, Unit - 45, Zone - Xv.",Own Sources,15,2020-21,2020-21 NQ/2020-21/4845,Buildings,Completed,NQ-SHOZHINGANALLUR,197,490000,Providing Water Supply Arrangements To Mini Forest By Miyawaki Method in OSR Land at Model School Road in Div - 197 U - 45 Zone - XV.,Own Sources,15,2020-21,2021-22 BR/2020-21/2773,Road Cut,Completed,BR-Bus Route Roads,198,975000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-198,U-44 Zone XV",Deposit Works,15,2020-21,2020-21 BR/2020-21/2774,Road Cut,Completed,BR-Bus Route Roads,198,975000,"Roadcut restoration (Roadcut made by Reliance Jio & Act for OFC Cable) at various streets in Dn-198 & 200 ,U-44 &45 Zone XV",Deposit Works,15,2020-21,2020-21 NQ/2020-21/0478,Buildings,Completed,NQ-SHOZHINGANALLUR,198,290000,"Additional Improvement Work for Providing GI Roofing sheet to Multipurpose Hall at Kudumiyandi Thoppu School Street in Div-198,Unit-44,Zone-15",Own Sources,15,2020-21,2020-21 NQ/2020-21/0625,Buildings,Completed,NQ-SHOZHINGANALLUR,198,149000,"Repair Works to Toilet at Panaiyur Kuppam Gents, Panaiyur Kuppam Ladies (south), Panaiyur Kuppam Ladies (North), Kudimiyandi Thoppu School street, Rajiv Gandhi Nagar, Sathiyavanimuthu street, Parameshwaran nagar street in Dn-198 U-44 Z-15",Own Sources,15,2020-21,2020-21 NQ/2020-21/3971,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,198,142000,"Desilting of Side Drain at Rajiv Gandhi Nagar 1st, 2nd,3rd & 4th street and Sathiyavanimuthu street in Dn-198 , U-44 ,Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/3974,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,198,292000,"Providing Cross Culvert at Kudimiyandithoppu School street & Providing Hume pipe at TNHB C1 & C2 Road in Dn-198, U-44 , Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/4018,Buildings,Completed,NQ-SHOZHINGANALLUR,198,270000,Improvements to Anganwadi at annai indira Street in Div-198 Unit-44 Zone-15,Own Sources,15,2020-21,2021-22 NQ/2020-21/4984,Buildings,Completed,NQ-SHOZHINGANALLUR,198,511000,"Providing water Supply to the Miyawaki @ D40 Road (TNHB Layout) in div-198,Unit-44,Zone-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/4988,Buildings,Completed,NQ-SHOZHINGANALLUR,198,682000,"Providing water Supply to the Miyawaki at Hindu mayana pathai Burial ground at TNHB Layout Div-198,Unit-44,Zone-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/3481,Buildings,Completed,NQ-SHOZHINGANALLUR,199,342000,"Improvements for Amma Unavagam at V.V.Venkata Subramaniyam salai (Nainar Kuppam) in div-199,unit-44,Zone-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/6999,Roads,Completed,NQ-SHOZHINGANALLUR,199,492000,"Providing Granular Sub Base (GSB),Wet Mix Macadam (WMM) at Mahaveerar Street in Div-199,Unit-44,Zone-15",Own Sources,15,2020-21,2020-21 NQ/2020-21/3973,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,319000,Desilting of Swd and Side Drain at Various Streets In Div-200 Unit-45 Zone-15,Own Sources,15,2020-21,2021-22 NQ/2020-21/3977,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,218000,"Providing Cross Cuverts and Precase Slab at TNSCB Various Streets in Dn-200, U-45,Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/6841,Buildings,Completed,NQ-SHOZHINGANALLUR,200,150000,"Improvements to UPHC by Attending Plumbing And Other repair works in Div- 200 U-45,Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/6842,Storm Water Drain,Completed,NQ-SHOZHINGANALLUR,200,1240000,"Raising Side Drain at TNSCB 8th,6th Avenue And Attending Repairs to Existing Drainin Tsunami Nagar in Dn-200, U-45,Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/6977,Buildings,Completed,NQ-SHOZHINGANALLUR,200,1230000,"Construction of Cross Culvert of Size 900x900 mm along TNSCB Various Streets at Semmancherry in Div 200, U-45, Z-15",Own Sources,15,2020-21,2021-22 NQ/2020-21/7637,Buildings,Completed,NQ-SHOZHINGANALLUR,200,860000,"Providing Precast Slabs At Various Streets in Tsunami Nagar in Div-200,U-45,Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/7669,Buildings,Completed,NQ-SHOZHINGANALLUR,200,68000,"Attending Repair works to Public Convenience at TNSCB 7th Avenue in Div-200,U-45,Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/7677,Buildings,Completed,NQ-SHOZHINGANALLUR,200,59000,"Attending Repair works to Public Convenience at Jawahar Nagar in Div-200,U-45,Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/7679,Buildings,Completed,NQ-SHOZHINGANALLUR,200,96000,"Attending Repair works to Public Convenience at Veeravanjinathan Street in Div-200,U-45,Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/7681,Buildings,Completed,NQ-SHOZHINGANALLUR,200,29700,"Attending Repair works to Public Convenience at Panchayat Office Street in Div-200,U-45,Z-15.",Own Sources,15,2020-21,2021-22 NQ/2020-21/7685,Buildings,Completed,NQ-SHOZHINGANALLUR,200,128000,"Attending Repair works to Public Convenience at Pondicherry Pattai Salai in Div-200,U-45,Z-15.",Own Sources,15,2020-21,2021-22 B/2020-21/13718,Buildings,Completed,B-Buildings,,951885,"NAME OF WORK : SUPPLY DAND FIXING OF OFFICE FURNITURE HODs IN ZONE OFFICE 2 AT KAMARAJAR SALAI IN DN-20, ZONE-2",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4281,Overbridges,Completed,J-Bridges,,142000,"Riding surface patch work and Foot path patchwork in Stanley via duct bridge in Dn-61, Zone-5",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4283,Bridges,Completed,J-Bridges,,226000,Removal of Rank Vegetaion at Various bridges and Subways in North region (Zone -1 to 5),Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4286,ROB,Completed,J-Bridges,,190000,"Riding surface patch work in Nair bridge in Dn-61, Zone-5",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4671,Subway,Completed,J-Bridges,,50000,"Painting for Rajaji salai subway in Div-60, Zone-V",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4685,Subway,Completed,J-Bridges,,629000,"Painting and Relaying of wearing coat patches in M.C Road Div- 52, Zone-V",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4691,Bridges,Completed,J-Bridges,,995000,"Laying of foot path tiles and Painting the Existing Harris Bridge across coovum river in Dn-63, Zone-5",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4730,Bridges,Completed,J-Bridges,,851000,"Repair the hand rail and painting the Existing Laws bridge across coovum river in Dn-62, Zone-5",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/4734,Bridges,Completed,J-Bridges,,43000,"Construction of Compound wall at Thoppai vinayagar koil st in Dn -41, Zone -IV",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5325,Grade Separator,Completed,J-Bridges,,945000,"Painting work at South Usman Road flyover in Dn-136,Zone-10.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5342,Subway,Completed,J-Bridges,,245000,"Painting work under railway portion at Harrington road Subway in Dn-107,Zone-08.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5347,Subway,Completed,J-Bridges,,227000,"Painting work under railway portion at Nungambakkam Subway in Dn-109,Zone-09.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5377,Subway,Completed,J-Bridges,,453000,"Painting work under railway portion at Villivakkam Subway in Dn-94,Zone-08.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5381,Subway,Completed,J-Bridges,,216000,"Painting work under railway portion at Duraisamy road Subway in Dn-136,Zone-10.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5386,Subway,Completed,J-Bridges,,78000,"Painting work under railway portion at Rangarajapuram two wheeler subway in Dn-134,Zone-10.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5389,Subway,Completed,J-Bridges,,200000,"Painting work at Jones road Subway in Dn-142,Zone-10.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5418,ROB,Completed,J-Bridges,,72000,"Providing Center Median at Kodambakkam bridge in Dn -136,Zone-10.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5420,Subway,Completed,J-Bridges,,671000,"Improvements of existing two wheeler subway (Eastern side)at Perambur in Dn -70,Zone-06.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5423,Bridges,Completed,J-Bridges,,730000,"Repair the Approach slab of existing bridge across B-Canal near kottur puram MRTS Div-172,Zone-13",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5424,Subway,Completed,J-Bridges,,627000,"Improvements of existing two wheeler subway (Weatern side)at Perambur in Dn -70,Zone-06.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5425,Culvert,Completed,J-Bridges,,278000,"Providing Center Median at Powder mills road in Dn -77,Zone-06.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5427,Bridges,Completed,J-Bridges,,59000,"Laying Patchwork in Existing footpath at Naduvankarai Bridge in Dn -100,Zone-08.",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5430,Bridges,Completed,J-Bridges,,198000,Removal of Rank Vegetation at Various bridges and Subways in Center Region.,Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5433,Bridges,Completed,J-Bridges,,141000,Wearing coat patches attended at Subways and flyovers in Center Region (Zone-06 to 10),Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5439,Bridges,Completed,J-Bridges,,539000,"Repair the Storm water Drain and Abutment wall of existing bridge across B-Canal near kottur puram MRTS Div-172,Zone-13",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5483,Subway,Completed,J-Bridges,,774000,"Painting for Gengu reddy subway Railway portion in Div- 61, Zone-V",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5484,Subway,Completed,J-Bridges,,242000,"Relaying of wearing coat patches in existing Aranganathan subway Div- 171, Zone-XIII",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5485,ROB,Completed,J-Bridges,,33000,Repair foot path in existing Dr.Gurusamy Bridge in Div-107 Zone-VIII,Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5486,Grade Separator,Completed,J-Bridges,,254000,"Relaying of wearing coat patches in existing flyover at Sardar patel road junction of Gandhi mandam road Div- 172, Zone-XIII",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5487,Grade Separator,Completed,J-Bridges,,250000,"Relaying of wearing coat patches in existing flyover at Sardar patel road junction of L.B. road Div- 175, Zone-XIII",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5492,Bridges,Completed,J-Bridges,,226000,Removal of Rank Vegetaion at Various bridges and Subways in South region (Zone -11 to 15),Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/5493,Bridges,Completed,J-Bridges,,84000,"Relaying of wearing coat patches in existing Thiru -vi-ka Bridge Div- 173, Zone-XIII",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/7320,Subway,Completed,J-Bridges,,350000,"Providing Holes using diamond core cutting system in Existing RBI Subway in Dn -60,Zone-5",Own Sources,Greater Chennai Corporation,2020-21,2020-21 J/2020-21/8556,Bridges,Completed,J-Bridges,,278000,"Painting for Manickam nagar subway in Div- 5, Zone-I",Own Sources,Greater Chennai Corporation,2020-21,2020-21 BR/2020-21/13637,Roads,Completed,BR-Bus Route Roads,,980000,Repairs and Rectification of Damaged Modern Stainless Steel BUS SHELTERS at Various Divisions in Zone - 09,Own Sources,9,2020-21,2021-22 BR/2020-21/1408,Road Cut,Completed,BR-Bus Route Roads,,949000,"Restoration of Roadcut made by OFC Providers at Various Bus Route Roads in Dn-111,113,114,&117 Zone-IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/1410,Road Cut,Completed,BR-Bus Route Roads,,933000,"Restoration of Roadcut made by OFC Providers at Various Bus Route Roads in Dn-117,118,119,&121 Zone-IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/1417,Road Cut,Completed,BR-Bus Route Roads,,933000,"Restoration of Roadcut made by OFC Providers at Various Bus Route Roads in Dn-122,123, & 124 Zones-IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/1418,Road Cut,Completed,BR-Bus Route Roads,,949000,"Restoration of Roadcut made by OFC Providers at Various Bus Route Roads in Dn-123,124,125,126 & 128, Zone-IX",Deposit Works,9,2020-21,2020-21 BR/2020-21/1421,Road Cut,Completed,BR-Bus Route Roads,,965000,"Restoration of Roadcut made by OFC Providers at Various Bus Route Roads in Dn- 53, 59, 102, 103, 104, 106, 107, 110, 111, 113 & 114 Zones 8 & 9",Deposit Works,9,2020-21,2020-21 BR/2020-21/13638,Roads,Completed,BR-Bus Route Roads,,998000,Repairs and Rectification of Damaged Modern Stainless Steel BUS SHELTERS at Various Divisions in Zone - 10,Own Sources,10,2020-21,2021-22 BR/2020-21/10620,Road Cut,Completed,BR-Bus Route Roads,,1360000,"Restoration of Road cut made by TANTRANSCO for laying 230KV cable at Blackers Road, Adhithinar salai , Langs Garden Road and Vepery High Road ( from J.V Street to Veterinary College Hostel) in Div - 58 & 61, Zone -5.",Deposit Works,North Region,2020-21,2020-21 BR/2020-21/12756,Roads,Completed,BR-Bus Route Roads,,671000,"Repairs and painting to the center Median at Ibrahimji salai , M.S.Koil street and S.N.Chetty street in Division-60,52,50 in Zone -5.",Own Sources,North Region,2020-21,2021-22 BR/2020-21/12801,Road Cut,Completed,BR-Bus Route Roads,,280000,"Restoration of OFC Roadcut 9 Nos of Bus Route Roads in Div-152,157,161,164 & 167. Zone - 11 &12",Deposit Works,South Region,2020-21,2021-22 NC/2021-22/0162,Buildings,Completed,NC-MADHAVARAM,23,16200,"IMPROVEMENTS WORKS TO DIVISION OFFICE IN DN-23, UNIT-6,ZONE-3.",Own Sources,3,2021-22,2021-22 NC/2021-22/0172,Buildings,Completed,NC-MADHAVARAM,23,63000,"PROVIDING RAIN WATER HARVESTING AT VARIOUS STREETS IN DN-23, UNIT-6, ZONE-3",Own Sources,3,2021-22,2021-22 NC/2021-22/0173,Buildings,Completed,NC-MADHAVARAM,23,49700,"REPAIRS AND IMPROVEMENTS TO PUBLIC CONVENIENCE AT RETTAI MALAI SRINIVASAN STREET ( MALE & FEMALE UNIT ) IN DN-23, UN IT-6, ZONE-3",Own Sources,3,2021-22,2021-22 NC/2021-22/0174,Buildings,Completed,NC-MADHAVARAM,23,101000,"ADDITIONAL IMPROVEMENTS WORKS TO MINI CLINIC AT RETTAI MALAI SRINIVASAN STREET IN DN-23, UNIT-6, ZONE-3",Own Sources,3,2021-22,2021-22 NC/2021-22/0459,Buildings,Completed,NC-MADHAVARAM,29,57000,"REPAIR AND REPLACEMENT OF NEW BLADE , BUSH AND SOLID BUSH ROD FOR COCONUT SHREDDING MACHINE (BIG) AT VELU STREET COMPOST YARD IN DN-29, UNIT-7, ZONE-3",Own Sources,3,2021-22,2021-22 NC/2021-22/0460,Buildings,Completed,NC-MADHAVARAM,29,67000,"REPAIR AND REPLACEMENT OF NEW BLADE , BUSH AND SOLID BUSH ROD FOR COCONUT SHREDDING MACHINE (SMALL) AT VELU STREET COMPOST YARD IN DN-29, UNIT-7, ZONE-3",Own Sources,3,2021-22,2021-22 NC/2021-22/0463,Buildings,Completed,NC-MADHAVARAM,29,110000,"IMPROVEMENTS WORKS TO EXISTING MINI CLINIC IN DIVISION OFFICE COMPLEX AT DEVARAJAN STREET IN DN-29, UNIT-7, ZONE-3",Own Sources,3,2021-22,2021-22